Dam Operational Improvement and Safety Project Phase 2 (DOISP 2) LOAN NO. P 8711 Procurement Plan Version No.: 1 Date: July 16, 2018 I. General Information 1. Project information: a. Country: Indonesia b. Recipient: Ministry of Finance (MOF) c. Project Name: Dam Operational Improvement and Safety Project Phase 2 d. Project Implementing Agency (PIA): (i) Directorate General of Water Resources – Ministry of Public Works and Housing 2. Bank’s No Objection Date of the Procurement Plan: a. Version 1: June 5, 2017 b. Version 2: November 10, 2017 c. Version 3: July 5, 2018 3. Date of General Procurement Notice: 4. Period covered by this procurement plan: January 1, 2017 to December 31, 2018 II. Types of Contract, Bank’s Review Requirements and Applied Methods A. Works, Goods and Non-consulting Services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procureme Ref. Bank’s Review Procurement Method nt Method No. Requirement Threshold 1. International Competitive ≥ $2,000,000 Each contract equal Bidding (Goods/IT System) to or above $1,500,000 equivalent shall be subject to Bank’s prior review. All other contracts subject to post 2. International Competitive ≥ review. Each contract equal Bidding (Non-consulting $10,000,000 to or above Services) $1,500,000 equivalent shall be subject to Bank’s prior review. All other contracts subject to post 3. National Competitive < $2,000,000 Each contract equal review. Bidding (Goods/IT System) to or above $1,500,000 equivalent shall be subject to Bank’s prior review. All other contracts 4. National Competitive < subject Each to post contract equal Bidding (Non-consulting review. $10,000,000 to or above Services) $1,500,000 equivalent shall be subject to Bank’s prior review. All other contracts 5. Shopping (Goods/IT < $ 100,000 subject No priorto post review System) review. (only post review). 6. Shopping (Small Works and < $ 200,000 No prior review Non-consulting Services) (only post review). 7. Direct Contracting (Small No Each contract equal Works, Goods and Non- procurement to or above consulting Services) method $1,500,000 threshold. equivalent shall be Subject to subject to Bank’s prior review. All justification other contracts for Direct subject to post Contracting review. as per para. 3.6 of the Justification for Procurementproposed use of Guidelines Direct Contracting method in any contract, regardless of value, shall be sent for the Bank’s 1. Pre-qualification: Not applicable. prior approval as part of the procurement plan. 2. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable. 3. Reference to (if any) Project Operational/Procurement Manual: Not Applicable 4. Any Other Special Procurement Arrangements: (i) PIU may use its own forms of contract for goods/non-consulting services procured under shopping method, which have been reviewed and found acceptable by the Bank; (ii) The Bank may review technical aspects of procurement documents and other non-procurement matters (technical specifications, environmental documents, cost estimate, etc.) related to the procurement activity in questioned, if needed. 5. Summary of the Procurement Packages planned after project effectiveness (including those that are subject to retroactive financing and advance procurement) 1 2 3 4 5 6 7 Ref. Descripti Estimat Packag Domesti Revie Comment No. on ed es c w s Cost Prefere by (US$ nce Bank million) (yes/no) (Prior / Post) 1. Summary 2,222,22 1 No Prior of the ICB 2 (Goods/IT Systems) 2. Summary 3,310,80 9 No Post of the NCB 6 (Goods/IT Systems) 3. Summary [to be [to be No Post of the NCB updated, updated (Non- if any] , if any] consulting Services) 4. Summary 18,108,5 11 No Post of the NCB 26 (Works) 5. Summary 391,111 8 No Post of the Shopping (Goods) 1 2 3 4 5 6 7 Ref. Descripti Estimat Packag Domesti Revie Comment No. on ed es c w s Cost Prefere by (US$ nce Bank million) (yes/no) (Prior / Post) 6. Summary [to be [to be No Post of the updated, updated Shopping if any] , if any] (Non- consulting Services) 7. Summary 481,481 3 No Post of the Shopping (Small Works) 8. Summary [to be [to be No Post of the updated updated Direct , if any] , if any] Contractin g (Goods/IT systems, Non- Consulting Services and Small Works) B. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to prior review by Bank as stated in Appendix 1 to the Guidelines for Selection and Employment of Consultants: Ref. Selection Selection Method Bank’s Prior Review No. Method Threshold Requirement Ref. Selection Selection Method Bank’s Prior Review No. Method Threshold Requirement 1. QCBS (Firms) Applied to all Each contract equal to estimated value. No or above $500,000 threshold. equivalent shall be subject to Bank’s prior review. All other contracts subject to post review. (Prior review from technical perspective of only the draft TOR 2. CQS (Firms) Only for estimated and No draft prior cost (only review contract value < $ estimate). post review). 300,000 as per paragraph 3.7 of the 3. Single Source Consultant No selection Guidelines. method Each contract equal to Selection of threshold. Subject to or above $500,000 Firms justification for Singe equivalent shall be Source Selection of subject to Bank’s prior firms as per para. 3.9 review. All other and 3.10 of the contracts subject to Consultant Guidelines. post review. (Prior review from technical perspective of only the draft TOR, Justification for use of Single Source Selection method and draft cost estimate, shall be sent for the Bank’s prior 4. Competitive No threshold. approval No as part prior review of the (only Selection of procurement post review), plan). unless Individual contract is equal to or Consultants above $200,000. (comparison of at least 3 CVs) (Prior review from technical perspective of only the draft TOR 5. Single Source No Threshold. and No draft prior cost (only review Selection of estimate). post review), unless Individual Subject to justification contract is equal to or Consultants for single source of above $200,000. individuals as per para. 5.4 of the (Prior review from Consultant Guidelines technical perspective of only the draft TOR, Justification for use of Single Source Selection method together with CV of the recommended candidate and draft cost estimate, shall be sent for the Bank’s 2. Shortlist comprising entirely of national consultants prior approval : Short as part of the procurement list of consultants for services (firms), estimated to cost less than $ 400,000 equivalent per contract, may comprise plan). entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Consultants may be hired under Indefinite Delivery Contract (IDCs) or Price Agreement as per paragraph 4.5 of the Consultant Guidelines. 4. Summary of Consultancy Assignments with Selection Methods and Time Schedule after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref Descripti Type of Estimat Packag Revie Commen . on of Assignme ed es/Posit w ts No. Assignme nts Cost ions by nts (US$ Bank million) (Prior / Post) 1. Summary (Time- 18,335,7 18 Prior of number Based/Lum 77 and of psump) Post contracts that will be let under QCBS 2. Summary (Time- 5,813,77 43 Post of number Based 8 of /Lump- contracts Sum) that will be let under other methods (QBS, FBS, LCS and CQS) 1 2 3 4 5 6 7 Ref Descripti Type of Estimat Packag Revie Commen . on of Assignme ed es/Posit w ts No. Assignme nts Cost ions by nts (US$ Bank million) (Prior / Post) 3. Summary (Time- 67,407 6 Post of number Based of /Lump- individual Sum) consultant contracts that will be let under competitiv e selection 4. Summary (Time- [to be [to be Post of number Based updated, updated, of /Lump- if any] if any] individual Sum) consultant contracts that will be let under single- source selection PROCUREMENT Indonesia : Dam Operational Improvement and Safety PLAN General Information Country: Indonesia 2018-09-05 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P096532 GPN Date: Project Name: Dam Operational Improvement and Safety Loan / Credit No: COFN / C1460 Directorate of Operation and Maintenance, Directorate General of Water Resources Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned RDC-CW-1 / Construction of Dam Operational Improvem Single Stage - One E 2020-03-0 Laboratory Building and Wor COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 724,444.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 nvelope 3 kshop at Balai Litbang BHGK udies SMT-CW-2 / Construction of Dam Operational Improvem Single Stage - One E 2020-03-0 Safety Measures and Support COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 370,370.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 nvelope 3 ing Facilities at Keuliling Dam udies SMT-CW-3 / Improvement of Dam Safety Institutional Imp Single Stage - One E 2020-03-0 COFN / C1460 Post Request for Bids Open - National 259,259.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 the Office of UPB BWS Suma rovement nvelope 3 tera I SMR-CW-3 / Rehabilitation of Dam Safety Institutional Imp Single Stage - One E 2020-03-2 DMU (Dam Management Unit COFN / C1460 Post Request for Bids Open - National 185,185.00 0.00 Canceled 2019-01-21 2019-02-10 2019-03-02 2019-03-10 2019-03-30 rovement nvelope 9 ) Building at BWS Sumatera I V Office CC-CW-1 / Rehabilitation of Dam Operational Improvem Single Stage - One E 2020-09-0 COFN / C1460 Post Request for Bids Open - National 1,481,481.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 Gintung Dam ent and Safety Works and St nvelope 8 udies BSO-CW-3 / Rehabilitation of Dam Operational Improvem Single Stage - One E 2020-09-0 COFN / C1460 Post Request for Bids Open - National 2,222,222.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 Lalung Dam ent and Safety Works and St nvelope 8 udies BSO-CW-4 / Rehabilitation of Dam Operational Improvem Single Stage - One E 2020-09-0 COFN / C1460 Post Request for Bids Open - National 3,703,704.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 Pacal Dam ent and Safety Works and St nvelope 8 udies BSO-CW-5 / Improvement an d Maintenance of the Dam Cr est, Instrumentataion, and Li Dam Operational Improvem Single Stage - One E 2020-09-0 ghting at Dawuhan Dam, and COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 2,222,222.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 nvelope 8 Reinforcement of Dam Slope udies and Improvement of Hydrom echanical Gate at Gonggang Dam BSO-CW-6 / Improvement an d Maintenance of the Dam Cr Dam Operational Improvem est, Instrumentataion, Lightin Single Stage - One E 2020-03-0 COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 222,222.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 g, and Reinforcement of Dam nvelope 3 udies Slope and Improvement of H ydromechanical Gate at Prije tan Dam KLM-CW-2 / Reinforcement o Dam Operational Improvem Single Stage - One E 2020-02-2 COFN / C1460 Post Request for Bids Open - National 518,519.00 0.00 Canceled 2019-01-07 2019-01-14 2019-01-28 2019-02-04 2019-02-25 f Manggar Dam in Balikpapan ent and Safety Works and St nvelope 5 City udies KLM-CW-3 / Safety Measures Dam Operational Improvem Single Stage - One E 2019-04-0 COFN / C1460 Post Request for Bids Open - National 222,222.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 at Binalatung Dam, Tarakan ent and Safety Works and St nvelope 9 City udies KLM-CW-4 / Improvement of Dam Safety Institutional Imp Single Stage - One E 2020-03-0 the Office of UPB BWS Kalim COFN / C1460 Post Request for Bids Open - National 518,519.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 rovement nvelope 3 antan III, Samarinda City NTG-CW-1 / Rehabilitation of Dam Operational Improvem Single Stage - One E 2020-09-0 COFN / C1460 Post Request for Bids Open - National 862,963.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 Haikrit Dam ent and Safety Works and St nvelope 8 udies NTE-CW-5 / Installation of Fe Dam Operational Improvem Request for Quota Single Stage - One E 2020-03-0 COFN / C1460 Post Open - National 74,074.00 0.00 Canceled 2019-01-14 2019-03-04 nces at Batujai Dam Greenbe ent and Safety Works and St tions nvelope 3 lt udies NTG-CW-2 / Rehabilitation of Dam Operational Improvem Single Stage - One E 2020-03-0 COFN / C1460 Post Request for Bids Open - National 370,370.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 Haliwen Dam ent and Safety Works and St nvelope 3 udies BP-CW-3 / Hydromechanical Dam Operational Improvem Rehabilitation Works Palasari Single Stage - One E 2020-08-2 COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 936,981.00 0.00 Canceled 2018-12-28 2019-01-04 2019-01-25 2019-02-01 2019-02-22 , Grokgak, Telaga Tunjung da nvelope 9 udies n Benel Dams in Bali Provinc e PJE-CW-4 / Rehabilitation Po Dam Operational Improvem Single Stage - One E 2020-02-2 COFN / C1460 Post Request for Bids Open - National 455,556.00 0.00 Canceled 2018-12-28 2019-01-04 2019-01-25 2019-02-01 2019-02-22 nre-Ponre Dam ent and Safety Works and St nvelope 2 udies National Procure OP-CW-1 / Improvement of E ment Document - quipment/Operational Faciliti Dam Safety Institutional Imp Single Stage - One E Pending Imp 2021-11-2 COFN / C1460 Post Request for Bids Open - National 1 Envelope proce 433,333.00 0.00 2021-02-10 2021-02-15 2021-03-29 2021-04-28 2021-06-02 es for CDMU at Dit. of O&M, rovement nvelope lementation 9 ss (Non Bank-SPD DGWR (Phase IV) ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual OP-GD-3 / Improvement of E Dam Operational Improvem quipment/Operational Faciliti Single Stage - One E Under Imple COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 222,222.00 0.00 2017-11-21 2019-06-27 2017-11-28 2017-12-21 2019-09-05 2017-12-28 2018-01-05 2018-05-05 es for Central Dam Monitorin nvelope mentation udies g Unit (CDMU) at Dit. of O&M , DGWR OP-GD-1 / Provision of BDSF Dam Operational Improvem Open - Internationa Single Stage - One E COFN / C1460 Prior Request for Bids 2,222,222.22 0.00 Canceled 2018-12-04 2018-12-09 2019-01-20 2019-02-19 2019-03-26 2019-09-22 (Basic Dam Safety Facilities) ent and Safety Works and St l nvelope udies RDC-GD-2 / Provision of Auto Dam Operational Improvem Single Stage - One E matization System for Hydro COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 173,741.00 0.00 Canceled 2019-01-22 2019-01-27 2019-02-17 2019-02-24 2019-03-02 2019-10-28 nvelope ulic Laboratory Equipment udies Page 1 BSO-GD-2 / Provision of Falic Dam Safety Institutional Imp Request for Quota Single Stage - One E COFN / C1460 Post Open - National 15,333.00 0.00 Canceled 2019-01-14 2019-03-04 2019-10-30 ities for UPB rovement tions nvelope NTG-GD-1 / Provision of Dam Dam Operational Improvem Single Stage - One E COFN / C1460 Post Request for Bids Open - National 148,148.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-03 2019-10-29 Monitoring Equipment ent and Safety Works and St nvelope udies BB-GD-2 / Provision of Dam Dam Safety Institutional Imp Request for Quota Single Stage - One E COFN / C1460 Post Open - National 7,407.00 0.00 Canceled 2019-03-18 2019-05-05 2019-11-01 Books rovement tions nvelope OP-GD-7 / Operational Impro Dam Operational Improvem Open - Internationa Single Stage - One E COFN / C1460 Prior Request for Bids 6,666,666.67 0.00 Canceled 2019-06-11 2020-04-10 2019-06-18 2020-06-29 2019-07-09 2019-07-16 2019-08-05 2021-07-25 vement of CDMU ent and Safety Works and St l nvelope udies OP-GD-4 / Provision of Opera Operation and Maintenance I Request for Quota Single Stage - One E tion and Maintenance of Dam COFN / C1460 mprovement and Capacity B Post Open - National 66,667.00 0.00 Signed 2019-06-17 2019-08-12 2020-02-08 tions nvelope facilities and infrastructure uilding OP-GD-5 / Improvement of E quipment/Operational Faciliti Dam Safety Institutional Imp Single Stage - One E COFN / C1460 Post Request for Bids Open - National 233,333.00 0.00 Signed 2019-06-12 2019-06-27 2019-06-17 2019-07-08 2019-09-05 2019-07-15 2019-09-23 2019-07-22 2020-03-18 es for Central Dam Monitorin rovement nvelope g Unit (CDMU),at Dit. of O&M , DGWR Stage II OP-GD-6 / Provision of Mean Dam Safety Institutional Imp Single Stage - One E s & Infrastructure Support for COFN / C1460 Post Request for Bids Open - National 333,333.00 345,474.72 Signed 2019-06-12 2019-06-27 2019-06-17 2019-07-08 2019-09-09 2019-07-15 2019-09-23 2019-07-23 2019-12-12 2020-03-19 rovement nvelope Activities OP Bendungan OP-GD-1A / Provision of BDS Dam Operational Improvem Single Stage - One E COFN / C1460 Prior Request for Bids Open - National 1,966,667.00 0.00 Canceled 2019-06-27 2019-09-26 2019-07-02 2019-09-27 2019-07-16 2019-07-23 2019-08-24 2020-08-23 F (Basic Dam Safety Facilities ent and Safety Works and St nvelope ) udies OP-GD-2 / Procurement of D am Monitoring Equipment, To pographic & Bathymetric Sur Dam Operational Improvem veys and Speed Boat Survey Single Stage - One E COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 710,433.00 807,136.78 Signed 2019-06-18 2019-06-27 2019-06-23 2019-08-04 2019-09-05 2019-09-03 2019-09-23 2019-10-08 2019-12-12 2020-04-05 s to support the implementat nvelope udies ion of dam monitoring in acc ordance with the objectives o f operation, maintenance and monitoring OP-GD-8 / Provision of Equip Reservoir Sedimentation Miti Open - Internationa Single Stage - One E COFN / C1460 Prior Request for Bids 1,933,333.33 0.00 Canceled 2020-03-30 2020-04-04 2020-05-16 2020-06-15 2020-07-20 2021-01-16 ment for Sedimentation Mitig gation l nvelope ation OP-GD-1B / Provision of BDS Dam Operational Improvem Single Stage - One E COFN / C1460 Prior Request for Bids Open - National 1,966,667.00 1,944,732.29 Signed 2020-03-02 2020-03-12 2020-03-07 2020-05-08 2020-04-18 2020-06-01 2020-05-18 2020-07-07 2020-06-22 2020-08-11 2020-12-19 F (Basic Dam Safety Facilities ent and Safety Works and St nvelope ) udies OP-GD-9 / Dam Asset Manag Operation and Maintenance I Single Stage - One E COFN / C1460 Post Request for Bids Open - National 333,333.00 0.00 Canceled 2020-04-06 2020-04-11 2020-05-23 2020-06-22 2020-07-27 2021-01-23 ement System mprovement and Capacity B nvelope uilding OP-GD-10 / Software for Sup Operation and Maintenance I Single Stage - One E COFN / C1460 Post Request for Bids Open - National 133,333.00 0.00 Signed 2020-04-06 2020-06-11 2020-04-11 2020-05-23 2020-07-03 2020-06-22 2020-07-22 2020-07-27 2021-01-23 porting CDMU mprovement and Capacity B nvelope uilding OP-GD-11 / Improvement of Dam Safety Institutional Imp Single Stage - One E Equipment /Operational Facili COFN / C1460 Post Request for Bids Open - National 1,333,333.00 0.00 Signed 2020-04-06 2020-05-29 2020-04-11 2020-05-23 2020-07-01 2020-06-22 2020-07-22 2020-07-27 2021-01-23 rovement nvelope ties for CDMU at Dit. of O&M, DGWR (Phase III) OP-GD-8A / Provision of Equi Reservoir Sedimentation Miti Single Stage - One E COFN / C1460 Prior Request for Bids Open - National 1,933,333.33 1,770,109.27 Signed 2020-05-11 2020-06-12 2020-05-16 2020-06-15 2020-06-27 2020-07-29 2020-07-27 2020-09-01 2020-08-31 2020-09-24 2021-02-27 pment for Sedimentation Miti gation nvelope gation OP-GD-7A / Operational Impr Dam Operational Improvem Open - Internationa Single Stage - One E COFN / C1460 Prior Request for Bids 6,666,666.67 0.00 Canceled 2020-09-15 2020-09-27 2020-09-20 2020-09-28 2020-11-01 2020-11-18 2020-12-01 2021-02-03 2021-01-05 2021-07-04 ovement of CDMU ent and Safety Works and St l nvelope udies OP-GD-12 / Software for Sup Operation and Maintenance I Single Stage - One E COFN / C1460 Post Request for Bids Open - National 200,000.00 0.00 Signed 2021-08-20 2021-08-31 2021-08-25 2021-10-06 2021-10-01 2021-11-05 2021-10-12 2021-12-10 2022-06-08 porting CDMU Phase II mprovement and Capacity B nvelope uilding OP-GD-13 / Provision of Dam Dam Safety Institutional Imp Single Stage - One E COFN / C1460 Post Request for Bids Open - National 266,667.00 0.00 Signed 2021-08-20 2022-01-11 2021-08-25 2021-10-06 2022-02-07 2021-11-05 2022-03-25 2021-12-10 2022-06-08 Monitoring Equipment rovement nvelope OP-GD-14 / Improvement of Dam Operational Improvem Equipment/Operational Facili Single Stage - One E COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 433,333.00 0.00 Signed 2021-10-31 2022-07-05 2021-11-05 2021-12-17 2022-07-29 2022-01-16 2022-08-15 2022-02-20 2022-08-19 ties for CDMU at Dit. of O&M, nvelope udies DGWR (Phase IV) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual OP-NCS-1 / Mini-Series Movi Dam Safety Institutional Imp Single Stage - One E COFN / C1460 Post Request for Bids Open - National 266,667.00 0.00 Signed 2021-08-20 2021-08-30 2021-08-25 2021-10-06 2021-09-30 2021-11-05 2021-10-12 2021-12-10 2022-06-08 es of Dam Education rovement nvelope CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual OP-CS-1 / TA Consultancy Se Dam Operational Improvem rvices for Supporting the Cen Quality And Cost- Open - Internationa COFN / C1460 ent and Safety Works and St Prior 3,342,815.00 2,800,378.60 Signed 2017-09-13 2017-10-04 2017-11-17 2017-12-15 2018-01-14 2018-02-18 2018-11-16 2018-03-25 2018-11-02 2019-03-25 tral Project Management Unit Based Selection l udies of DOISP II (TA CPMU) OP-CS-2 / TA Consultancy Se Dam Operational Improvem rvices for Supporting the Imp Quality And Cost- Open - Internationa COFN / C1460 ent and Safety Works and St Prior 11,212,444.00 9,814,105.27 Signed 2017-09-13 2017-10-04 2017-11-17 2017-12-15 2018-01-14 2018-02-18 2018-12-14 2018-03-25 2018-11-30 2019-03-25 lementation Management an Based Selection l udies d Supervision of the DOISP II (TA CPIU) OP-CS-5 / Guidelines for Gov Dam Operational Improvem Quality And Cost- ement-owned Dam Managem COFN / C1460 ent and Safety Works and St Post Open - National 148,148.00 0.00 Signed 2018-12-31 2019-05-03 2019-01-07 2019-03-07 2019-09-05 2019-03-08 2019-09-27 2019-03-14 2019-10-06 2019-04-24 2019-11-06 2019-05-05 2020-05-04 Based Selection ent by Business Entity udies OP-CS-6 / Reservoir Inspecti Dam Operational Improvem Quality And Cost- on and Evaluation Dam Cate COFN / C1460 ent and Safety Works and St Post Open - National 233,233.00 0.00 Signed 2019-01-02 2019-04-29 2019-01-23 2019-03-07 2019-07-11 2019-03-08 2019-09-27 2019-03-15 2019-11-06 2019-04-01 2019-11-15 2019-04-15 2020-04-14 Based Selection gory Stage I udies Page 2 RDC-CS-2 / Supervision of La Dam Operational Improvem Quality And Cost- boratory and Workshop Build COFN / C1460 ent and Safety Works and St Post Open - National 16,296.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-05-07 Based Selection ing of Balai Litbang BHGK udies SMT-CS-7 / Supervision of Im provement of UPB/ DMU (Da Dam Safety Institutional Imp Quality And Cost- COFN / C1460 Post Open - National 12,963.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-05-07 m Management Unit), in BWS rovement Based Selection Sumatera I, Phase I SMR-CS-10 / Supervision of Dam Safety Institutional Imp Quality And Cost- Rehabilitation of DMU Buildin COFN / C1460 Post Open - National 17,778.00 0.00 Canceled 2019-02-04 2019-02-09 2023-01-10 2023-02-07 2023-02-14 2023-03-18 2023-04-10 2024-04-09 rovement Based Selection g of BWS Sumatera IV SMR-CS-11 / DD of DMU Buil Dam Safety Institutional Imp Quality And Cost- ding Rehabilitation of BWS S COFN / C1460 Post Open - National 22,222.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2019-12-29 rovement Based Selection umatera IV and Heavy Mechi nery Workshop MSE-CS-4 / EAP Study of Wa Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 97,778.00 0.00 Canceled 2019-02-04 2019-02-09 2019-03-12 2019-04-09 2019-04-16 2019-05-18 2019-06-10 2019-10-08 y Jepara Dam ent and Safety Works and St Based Selection udies CC-CS-2 / Supervision on Gin Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 103,704.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-11-12 tung Dam Rehabilitation ent and Safety Works and St Based Selection udies CTR-CS-3A / Supervision of R Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 125,926.00 0.00 Canceled 2019-01-01 2019-01-20 2019-02-20 2019-03-20 2019-03-27 2019-04-28 2019-05-21 2020-05-20 ehabilitation Works of Cipanc ent and Safety Works and St Based Selection uh Dam udies BSO-CS-7 / Supervision for R Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 111,111.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-11-12 ehabilitation Works of Lalung ent and Safety Works and St Based Selection Dam udies BSO-CS-8 / Supervision for R Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 185,185.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-11-12 ehabilitation Works of Pacal ent and Safety Works and St Based Selection Dam udies BSO-CS-9 / Special Study for Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 222,222.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2019-10-30 Gonggang, Prijetan, and Pon ent and Safety Works and St Based Selection dok Dams udies BSO-CS-10 / Supervision on Rehabilitation and Maintenan ce of Crest, Instrumentation Dam Operational Improvem Quality And Cost- and Lighting of Dawuhan Da COFN / C1460 ent and Safety Works and St Post Open - National 111,111.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-11-12 Based Selection m, and Slope Reinforcement udies and Improvement of Hydrom echanical Gate of Gonggang Dam. BSO-CS-11 / Supervision on Rehabilitation and Maintenan Dam Operational Improvem ce of Crest, Instrumentation, Quality And Cost- COFN / C1460 ent and Safety Works and St Post Open - National 11,111.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-05-07 Lighting and Slope Reinforce Based Selection udies ment and Improvement of Hy dromechanical Gate of Prijet an Dam. BSO-CS-12 / Detailed Desain of Rehabilitation and Moderni Dam Operational Improvem zation of Instrumentation an Quality And Cost- COFN / C1460 ent and Safety Works and St Post Open - National 200,000.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-01-03 d Hydromechanical at Dams i Based Selection udies n Bengawan Solo River Basin / Wilayah Sungai Bengawan Solo BSO-CS-13 / Special Study of Dam Operational Improvem Quality And Cost- Saradan Dam, Kab. Madiun J COFN / C1460 ent and Safety Works and St Post Open - National 200,000.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2019-11-04 Based Selection awa Tengah udies BSO-CS-16 / Preparation and Operation and Maintenance I Quality And Cost- Legalization Operation Permi COFN / C1460 mprovement and Capacity B Post Open - National 222,222.00 0.00 Canceled 2019-01-09 2019-01-14 2019-02-14 2019-03-14 2019-03-21 2019-04-22 2019-05-15 2020-02-09 Based Selection t of Gondang and Prijetan Da uilding ms BT-CS-2 / SID for Conservati Reservoir Sedimentation Miti Quality And Cost- on and Sedimentation Treat COFN / C1460 Post Open - National 148,148.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-01-03 gation Based Selection ment at Sengguruh Reservoir KLM-CS-8 / Supervision of Im Dam Operational Improvem Quality And Cost- provement of Manggar Dam, COFN / C1460 ent and Safety Works and St Post Open - National 14,815.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-05-07 Based Selection Kota Balikpapan udies KLM-CS-9 / Supervision of Se Dam Operational Improvem Quality And Cost- faety Measures of Binalatung COFN / C1460 ent and Safety Works and St Post Open - National 7,407.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-05-07 Based Selection Dam, Kota Tarakan udies KLM-CS-10 / Preparation of E Operation and Maintenance I Quality And Cost- AP / TRD for Lempake Dam, COFN / C1460 mprovement and Capacity B Post Open - National 59,259.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2019-10-30 Based Selection Kota Samarinda uilding KLM-CS-11 / Supervision of I Dam Safety Institutional Imp Quality And Cost- mprovement of UPB / DMU in COFN / C1460 Post Open - National 74,074.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-05-07 rovement Based Selection BWS Kalimantan IIII, Samarin da NTE-CS-8 / Spatial Arrangem Dam Operational Improvem Quality And Cost- ent for Batujai Reservoir and COFN / C1460 ent and Safety Works and St Post Open - National 74,074.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-01-03 Based Selection Dam, Pulau Lombok udies NTE-CS-11 / Desain of UPB O Dam Operational Improvem Quality And Cost- ffice Rehabilitation, BWS Nus COFN / C1460 ent and Safety Works and St Post Open - National 11,111.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-01-03 Based Selection a Tenggara I udies NTG-CS-4 / Supervision of Re Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 44,444.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-11-12 habilitation Haikrit and Haliw ent and Safety Works and St Based Selection en Dams udies SMT-CS-6 / UKL / UPL Study Dam Operational Improvem of Roads and Connecting Bri Quality And Cost- COFN / C1460 ent and Safety Works and St Post Open - National 77,778.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2020-05-02 dges, and Supervision of Keul Based Selection udies iling Dam Safety Mesures Co nstruction BB-CS-3 / Study of Hydrogeo Dam Operational Improvem Quality And Cost- logical Influence on Dam Con COFN / C1460 ent and Safety Works and St Post Open - National 92,593.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-01-03 Based Selection struction Plans udies BB-CS-4 / Evaluation of Stud Dam Operational Improvem Quality And Cost- y on Approval of Dam Design COFN / C1460 ent and Safety Works and St Post Open - National 87,037.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-01-03 Based Selection on Dam Rehabilitation Imple udies mentation Page 3 BB-CS-5 / Guidelines of Seis Dam Safety Institutional Imp Quality And Cost- COFN / C1460 Post Open - National 100,000.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2019-12-29 mic Hazard Assessmet rovement Based Selection BB-CS-6 / Guidelines of Sism Dam Safety Institutional Imp Quality And Cost- COFN / C1460 Post Open - National 103,704.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2019-12-29 ic Hazard Analysis rovement Based Selection BB-CS-7 / Guidelines of Dyna Dam Safety Institutional Imp Quality And Cost- mic Analysis of Embankment COFN / C1460 Post Open - National 92,593.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-01-03 rovement Based Selection Type Dams) BB-CS-8 / Organize Inventor Dam Safety Institutional Imp Quality And Cost- y, Registration, and Clarificat COFN / C1460 Post Open - National 104,148.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-01-03 rovement Based Selection ion of Dam Hazard OP-CS-4 / Guidelines for Det Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 111,111.00 0.00 Signed 2018-10-17 2019-01-24 2018-11-07 2019-03-13 2019-03-11 2019-04-10 2019-02-21 2019-05-10 2019-04-29 2019-06-14 2019-05-16 2019-07-19 2020-07-18 ermining The Reservoir Bord ent and Safety Works and St Based Selection er Line udies CTR-CS-7 / DED, LARAP and Dam Operational Improvem Quality And Cost- Environment Permit for Capa COFN / C1460 ent and Safety Works and St Post Open - National 259,259.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-05-07 Based Selection city Development of Cikemba udies ng River CMC-CS-2 / Preparation and Dam Operational Improvem Legalization Operation Permi Quality And Cost- Open - Internationa COFN / C1460 ent and Safety Works and St Prior 1,037,037.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-10-10 t of Darma, Malahayu, Situp Based Selection l udies atok snd Situ Bolang Dams PMJ-CS-6 / Preparation and L egalization Operation Permit Dam Operational Improvem Quality And Cost- Open - Internationa of Dams in Pemali River Basi COFN / C1460 ent and Safety Works and St Prior 888,889.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2021-10-10 Based Selection l n (Lodan, Panohan, Banyuku udies wung, Klego, Kedung Ombo a nd Cacaban) PMJ-CS-7 / Preparation and L Dam Operational Improvem egalization Operation Permit Quality And Cost- Open - Internationa COFN / C1460 ent and Safety Works and St Prior 1,037,037.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2021-10-10 of Dams in Pemali Comal Riv Based Selection l udies er Basin (Simo, Penjalin, Gre neng and Tempuran) SRO-CS-4 / SID of Sedimenta tion Control and Managemen Dam Operational Improvem t at Sermo and Wadas Lintan Quality And Cost- Open - Internationa COFN / C1460 ent and Safety Works and St Post 407,407.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-08-06 g Dams, and Zoning Arrange Based Selection l udies ment in the Area of Sermo, S empor and Wadas Lintang D ams SRO-CS-5 / Preparation and Dam Operational Improvem Quality And Cost- Open - Internationa Legalization of Operation Per COFN / C1460 ent and Safety Works and St Post 466,667.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-10-10 Based Selection l mit for Wadaslintang and Se udies mporDams BSO-CS-14 / Preparation and Operation and Maintenance I Legalization Operation Permi Quality And Cost- Open - Internationa COFN / C1460 mprovement and Capacity B Prior 518,519.00 0.00 Canceled 2019-03-20 2019-04-08 2019-05-09 2019-06-06 2019-06-13 2019-07-14 2019-08-07 2020-08-06 t of Song Putri, Parangjoho, N Based Selection l uilding awangan, Cengklik, Delingan , and Ketro Dams BSO-CS-17 / SID Sedimentati Reservoir Sedimentation Miti Quality And Cost- Open - Internationa on Coveservation of 6 Reserv COFN / C1460 Post 355,556.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-10-10 gation Based Selection l oir and UKL+UPL BT-CS-1 / Preparation and Le galization Operation Permits Dam Operational Improvem Quality And Cost- Open - Internationa (Kd. Sengon, Sumber Kepuh, COFN / C1460 ent and Safety Works and St Prior 1,111,111.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-10-10 Based Selection l Klampis, Sengguruh, Selorejo udies , and Bening Dams) NTE-CS-9 / Preparation and L egalization of Operation Per Dam Operational Improvem Quality And Cost- Open - Internationa mit of Dams in Lombok Islan COFN / C1460 ent and Safety Works and St Prior 518,519.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-10-10 Based Selection l d Stage II (Pengga, Telaga L udies ebur, Tibu Kuning, dan Jerow aru) NTE-CS-10 / Preparation and Legalization of Operation Per Dam Operational Improvem Quality And Cost- Open - Internationa mit of Dams in Sumbawa Isla COFN / C1460 ent and Safety Works and St Prior 592,593.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2021-10-10 Based Selection l nd Stage II (Sumi, Batu Bulan udies , Olat Rawa, Ncera, Gapit dan Laju) MSE-CS-3 / Preparation and Dam Operational Improvem Quality And Cost- Open - Internationa Legalization Operation Permi COFN / C1460 ent and Safety Works and St Post 355,556.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-08-06 Based Selection l t of Way Jepara and Way Rar udies em Dams BP-CS-4 / Supervision for Re Dam Operational Improvem storation of Hydromechanical Quality And Cost- COFN / C1460 ent and Safety Works and St Post Open - National 40,466.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2020-11-07 at Palasari, Grokgak, Telaga Based Selection udies Tunjung and Benel Dams di P rovinsi Bali PJE-CS-9 / Supervision of Re Dam Operational Improvem Quality And Cost- habilitation and Remedial Wo COFN / C1460 ent and Safety Works and St Post Open - National 44,444.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2020-11-07 Based Selection rks of Kalola and Bili-Bili Dam udies s PJE-CS-8 / Supervision of Re Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 14,815.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2020-05-02 habilitation Works of Ponre-P ent and Safety Works and St Based Selection onre Dam udies PJE-CS-10 / Detailed Desain Dam Operational Improvem and UKL/UPL Study for Conve Quality And Cost- COFN / C1460 ent and Safety Works and St Post Open - National 185,185.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2020-01-28 rvation Building at upstream Based Selection udies of Kalola, Salomekko snd Pon re-Ponre Dams OP-CS-7 / Reservoir Inspecti Dam Operational Improvem Quality And Cost- on and Evaluation Dam Cate COFN / C1460 ent and Safety Works and St Post Open - National 210,000.00 0.00 Under Review 2019-06-11 2020-04-13 2019-06-18 2019-07-19 2019-08-16 2019-08-23 2019-09-23 2019-10-17 2020-10-16 Based Selection gory Stage II udies OP - CS - 8 / Dam Asset Man Operation and Maintenance I Quality And Cost- Open - Internationa COFN / C1460 Post 333,333.00 0.00 Under Review 2020-06-24 2020-08-06 2020-07-15 2020-08-28 2020-09-25 2020-10-25 2020-11-29 2021-01-03 2022-01-03 agement System mprovement and Capacity B Based Selection l uilding OP-CS-9 / Study of Dam Mon Dam Safety Institutional Imp Quality And Cost- Open - Internationa Pending Impleme itoring using Interferometric COFN / C1460 Post 333,333.00 0.00 2021-08-20 2021-09-10 2021-10-24 2021-11-21 2021-12-21 2022-01-25 2022-03-01 2023-03-01 rovement Based Selection l ntation Syntetic Radar (InSAR) OP-CS-9A / Study of Dam Mo Dam Operational Improvem Quality And Cost- nitoring using Interferometric COFN / C1460 ent and Safety Works and St Post Open - National 298,970.00 0.00 Under Review 2021-10-27 2022-01-20 2021-11-17 2021-12-31 2022-01-28 2022-02-27 2022-04-03 2022-05-08 2023-05-08 Based Selection Syntetic Radar (InSAR) udies Page 4 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 5 PROCUREMENT PLAN (Textual Part) Project information: Country: Federal Democratic Republic of Ethiopia De-Risking, Inclusion and Value Enhancement of Pastoral Economies (DRIVE) in the Horn of Africa Project, Project ID No. P176517 Project Implementation agency: Ministry of Agriculture and Ministry of trade and Regional Integration Date of the Procurement Plan: July 14, 2022 Period covered by this Procurement Plan: July 2022 to Dec 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (Fourth Edition, November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Public Procurement and Property Administration Proclamation No. 649/2009, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works is not applicable for those contracts identified in the Procurement Plan tables] Other Relevant Procurement Information. Not Applicable PROCUREMENT Eastern and Southern Africa : De-risking, inclusion and value enhancement of pastoral economies in the Horn of Africa PLAN General Information Country: Eastern and Southern Africa 2022-10-06 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P176517 GPN Date: 2022-08-24 Project Name: De-risking, inclusion and value enhancement of pastoral economies in the Horn of Africa Loan / Credit No: IDA / E0380 Ministry of Agriculture- Ethiopia Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOA-ETH-311250-GO-RF Livestock Value Chains and Open - Internationa Single Stage - One E Under Imple IDA / E0380 Post Request for Bids 800,000.00 0.00 2022-11-30 2023-01-31 2022-12-05 2023-02-16 2022-12-20 2023-03-15 2023-02-18 2023-05-31 2023-03-25 2023-09-21 B / Procurement of 21 Vehicl Trade Facilitation l nvelope mentation es NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOA-ETH-311207-CS-QC BS / Trade Logistics Economi Livestock Value Chains and Quality And Cost- Open - Internationa Under Implement c Feasibility Study for the tra IDA / E0380 Post 500,000.00 0.00 2022-09-20 2022-10-13 2022-10-20 2023-01-23 2022-12-09 2023-01-08 2023-02-17 2023-04-08 2023-05-13 2023-11-09 Trade Facilitation Based Selection l ation de route from Mille to Djibout i, Jigjiga to Djibouti and Jigjig a to Berbera ports ET-MOA-ETH-321413-CS-LCS Livestock Value Chains and Least Cost Selecti Pending Impleme IDA / E0380 Post Open - National 30,000.00 0.00 2023-03-31 2023-03-31 2023-04-14 2023-05-14 2023-06-13 2023-07-18 2023-08-22 2025-08-21 / Hiring External Financial Au Trade Facilitation on ntation dit ET-MOA-ETH-311206-CS-QC BS / Recruitment of Consulta nt to assess capacity gaps an Livestock Value Chains and Quality And Cost- Under Implement d propose interventions in rel IDA / E0380 Post Open - National 100,000.00 0.00 2022-11-30 2023-01-23 2022-12-25 2023-01-25 2023-03-10 2023-04-09 2023-05-24 2023-08-07 2023-09-27 2024-03-25 Trade Facilitation Based Selection ation ation to testing, certification and inspection services, trac eability system, export abatt oirs and export quarantine sy stem ET-MOA-ETH-321384-CS-QC BS / Feasibility study for a re Livestock Value Chains and Quality And Cost- Pending Impleme IDA / E0380 Post Open - National 100,000.00 0.00 2023-02-28 2023-03-25 2023-06-08 2023-07-08 2023-08-22 2023-11-05 2023-12-26 2024-03-25 st point at Bole airport for ex Trade Facilitation Based Selection ntation port of sheep and goats thro ugh cargo ET-MOA-ETH-321391-CS-QC BS / Conducting studies to str Livestock Value Chains and Quality And Cost- Pending Impleme IDA / E0380 Post Open - National 100,000.00 0.00 2023-04-24 2023-05-19 2023-08-02 2023-09-01 2023-10-16 2023-12-30 2024-02-19 2024-08-17 engthen linkages between pa Trade Facilitation Based Selection ntation storalists and live animal exp orters/abattoirs INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 Partial Risk Sharing Facility in Energy Efficiency PROCUREMENT PLAN I. General 1. Project information: • Project Name: Partial Risk Sharing Facility in Energy Efficiency • Country: India • Project Code: P128921 2. Bank’s approval Date of the procurement Plan Draft Procurement Plan dated November 13, 2014 Revision 0 agreed by the Bank on November 13, 2014 3. Implementing Agencies: Small Industries Development Bank of India (SIDBI) and Energy Efficiency Services Limited (EESL) 4. Period covered by this procurement plan: 18 months 5. Risk Rating for the Implementing Agency: Moderate 6. Original Procurement Risk Rating for the Project: Moderate 7. Current Procurement Risk Rating for the Project: Moderate II. Non-consulting services and Goods. 1 a) Procurement Methods and Thresholds Categor Method of Procurement Threshold (USD Equivalent) y Goods International Competitive Bidding > 3,000,000 and (ICB) Non- Limited International Bidding (LIB) wherever agreed by Bank consulta National Competitive Bidding Up to 3,000,000 (with NCB nt (NCB) conditions) services Shopping Up to 100,000 Direct Contracting (DC) As per paragraph 3.7 of Guidelines Public-Private Partnership (PPP) As per paragraph 3.14 of Services Guidelines Force Account As per paragraph 3.9 of Guidelines Framework Agreement (FA) As per paragraph 3.6 of Guidelines Procurement from United Nations As per paragraph 3.10 of (UN) Agencies Guidelines Performance Based Procurement As per paragraph 3.16 of Guidelines 1 b) Prior Review Threshold Goods: All contracts more than USD 6 million equivalent Non-Consultant Services and IT systems: All contracts more than USD 6 million equivalent In addition, the justifications for all contracts to be issued using LIB or direct contracting shall be subject to prior review. First framework agreement will be subject to prior review irrespective of value. For prior review contracts, the amendments for increasing the cost or extension of time beyond 15% of original value shall also be subject to Bank’s prior review. 2. Pre-qualification – Not envisaged 3. Applicable Guidelines: All the contracts issued under the project will follow the World Bank’s “Guidelines: Procurement of goods, works and non-consulting services under IBRD loans and IDA credits & grants by World Bank borrowers” dated January 2011 (as updated in July 2014). 4. Any Other Special Procurement Arrangements: NCB will be conducted in accordance with paragraph 3.3 and 3.4 of the Guidelines and the following provisions: i. Only the model bidding documents for NCB agreed with the GOI Task Force (and as amended for time to time), shall be used for bidding; ii. Invitations to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily inter-alia giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids; iii. No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprises from any given State; iv. Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; v. Extension of bid validity shall not be allowed with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by Bank only in cases of Force Majeure and circumstances beyond the control of the Purchaser/ Employer) vi. Re-bidding shall not be carried out with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank vii. The system of rejecting bids outside a pre-determined margin or "bracket" of prices shall not be used in the project; viii. Rate contracts entered into by Directorate General of Supplies and Disposals will not be acceptable as a substitute for NCB procedures. Such contracts will be acceptable however for any procurement under the Shopping procedures; ix. Two or three envelope system will not be used (except when using e-Procurement system assessed and agreed by the Bank) Other agreed provisions are: • Any discount received from the bidders after bid submission deadline will not be considered either during the bid evaluation or the contract award. • Domestic preference will be applicable for ICB procurement of Goods as per Appendix 2 of the Procurement Guidelines. • Bids received from foreign bidders will not be rejected under NCB. 5. Procurement Packages with Methods and Time Schedule – As per STEP. III. Selection of Consultants 1 a) Selection Methods and Thresholds Category Method of Procurement Threshold (USD Equivalent) Consultants’ Selection Based on Up to 300,000 Services Consultants’ Qualifications (CQS)/Least-Cost Selection (LCS) Single-Source Selection As per paragraphs 3.9-3.11 of (SSS) Guidelines Individuals As per Section V of Guidelines Particular Types of As per paragraphs 3.15-3.21 of Consultants Guidelines Quality- and Cost-Based for all other cases Selection (QCBS)/ Quality- Based Selection (QBS)/ Selection under a Fixed Budget (FBS) 1 b) Prior Review Threshold Consultancy Services: > US$ 4 Million equivalent for firms; and > US$ 500,000 equivalent for individuals In addition, the justifications for all contracts to be issued on the basis of single-source selection will be subject to prior review. For prior review contracts, the amendments for increasing the cost or extension of time beyond 15% of original value shall also be subject to Bank’s prior review. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: The evaluation committees will have external experts, as and when required, apart from in-house experts. 4. Applicable Guidelines: All the contracts issued under the project will follow the World Bank’s “Guidelines: Selection and employment of consultants under IBRD loans and IDA credits & grants by World Bank borrowers” dated January 2011 (as updated in July 2014). 5. Consultancy Assignments with Selection Methods and Time Schedule – As per STEP. PROCUREMENT India : Partial Risk Sharing Facility in Energy Efficiency PLAN General Information Country: India 2016-08-06 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P128921 GPN Date: Project Name: Partial Risk Sharing Facility in Energy Efficiency Loan / Credit No: TF / 19308 Small Industries Development Bank of India Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-SIDBI-256556-GO-RFQ / L aptops 10 nos, Printer (Desk) 2. Component 2: Technical Request for Quota Single Stage - One E 2 nos. and Printer (Office) 1 n TF / 19308 assistance and capacity buil Post Limited 35,000.00 17,687.36 Completed 2021-10-20 2021-11-09 2021-12-15 2021-12-16 2022-01-14 2021-12-29 tions nvelope o are proposed to be procure ding d for the PMU Staff working a t PEA SIDBI. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-SIDBI-346774-NC-RFB / Hi 2. Component 2: Technical Single Stage - Two E Pending Impl ring of agency for Developm TF / 19308 assistance and capacity buil Post Request for Bids Open - National 22,000.00 0.00 2023-03-10 2023-03-22 2023-05-03 2023-07-16 2023-08-20 2026-03-31 nvelope ementation ent and Maintenance of PRSF ding website IN-SIDBI-346782-NC-RFB / Hi ring a CA Firm for Maintenan 2. Component 2: Technical Single Stage - Two E Pending Impl ce of Books of Accounts and TF / 19308 assistance and capacity buil Post Request for Bids Open - National 32,000.00 0.00 2023-03-17 2023-03-29 2023-05-10 2023-07-23 2023-08-27 2025-03-31 nvelope ementation providing administrative and ding record keeping Services und er PRSF IN-SIDBI-346806-NC-RFB / Hi ring an agency for performin 2. Component 2: Technical g Measurement & Verificatio Single Stage - Two E Pending Impl TF / 19308 assistance and capacity buil Post Request for Bids Open - National 91,000.00 0.00 2023-03-02 2023-03-07 2023-04-18 2023-07-01 2023-08-05 2024-02-01 n (M&V) activities including E nvelope ementation ding nvironment & Social Safegua rd (E&SS) aspects under PRS F CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-SIDBI-151148-CS-CQS / M arketing and Promotion of PR 2. Component 2: Technical SF Facility and its Results thr Consultant Qualifi TF / 19308 assistance and capacity buil Post Open - National 45,000.00 0.00 Canceled 2020-01-30 2020-01-17 2020-02-09 2020-06-03 2020-02-29 2020-08-04 2020-03-10 2020-03-30 2020-09-26 ough Products such as Audio cation Selection ding Video Documentary Film, Mul timedia Presentations and bo oklets/pamphlets IN-SIDBI-155422-CS-QCBS / 2. Component 2: Technical Quality And Cost- Zone 1: Hiring of an agency f TF / 19308 assistance and capacity buil Post Open - National 150,000.00 0.00 Canceled 2020-02-10 2020-01-24 2020-03-09 2020-05-20 2020-04-16 2020-07-21 2020-05-16 2020-06-05 2020-07-18 2020-08-27 2021-08-27 Based Selection or generating pipeline in Zon ding e 1 States IN-SIDBI-155429-CS-QCBS / 2. Component 2: Technical Quality And Cost- Zone 2: Hiring of an agency f TF / 19308 assistance and capacity buil Post Open - National 150,000.00 0.00 Canceled 2020-02-10 2020-01-24 2020-03-09 2020-05-20 2020-04-16 2020-07-21 2020-05-16 2020-06-05 2020-07-18 2020-08-27 2021-08-27 Based Selection or pipeline generation in Zon ding e 2 States. IN-SIDBI-100763-CS-CDS / D esign & Development of Stan dard Product viz. Techno-Fin 2. Component 2: Technical ancial Analysis Tool for evalu Consultant Qualifi TF / 19308 assistance and capacity buil Post Open - National 70,000.00 0.00 Canceled 2020-05-22 2020-05-22 2020-06-12 2020-06-03 2020-07-26 2020-08-04 2020-08-25 2020-09-29 2020-11-22 ation of Energy Efficiency pro cation Selection ding jects by Participating Financi al Institutions (PFIs) and gen eration of pipelines for issuan ce of guarantee under PRSF Project IN-SIDBI-185402-CS-QBS / Z 2. Component 2: Technical one 1: Hiring of an agency fo Quality Based Sel TF / 19308 assistance and capacity buil Post Open - National 150,000.00 141,016.13 Completed 2020-08-17 2020-01-24 2020-09-07 2020-10-21 2020-08-27 2020-11-18 2020-11-04 2020-12-18 2020-12-30 2021-01-17 2021-02-25 2021-02-21 2021-04-07 2022-02-21 2022-04-06 r Generating pipeline of sub- ection ding projects under PRSF Project IN-SIDBI-185407-CS-QBS / Z 2. Component 2: Technical one 2: Hiring of an agency fo Quality Based Sel TF / 19308 assistance and capacity buil Post Open - National 150,000.00 119,329.08 Completed 2020-08-20 2020-01-24 2020-09-10 2020-10-24 2020-08-27 2020-11-21 2020-11-04 2020-12-21 2020-12-30 2021-01-20 2021-02-25 2021-02-24 2021-04-07 2022-02-24 2022-04-06 r Generating pipeline of sub- ection ding projects under PRSF Project IN-SIDBI-196292-CS-QCBS / Hiring of an agency for devel 2. Component 2: Technical oping Marketing and Promoti Quality And Cost- TF / 19308 assistance and capacity buil Post Open - National 95,000.00 33,590.06 Completed 2020-10-05 2020-10-16 2020-10-26 2020-11-09 2020-12-09 2020-12-30 2021-01-06 2021-03-03 2021-02-05 2021-04-01 2021-03-12 2021-05-12 2021-04-16 2021-07-14 2021-09-13 2022-03-01 on products such as Audio Vi Based Selection ding deo Film, Multimedia Present ations and Booklets covering PRSF Project. IN-SIDBI-874-CS-QCBS / PRS 2. Component 2: Technical Quality And Cost- F 13. Impact Assessment / Ev TF / 19308 assistance and capacity buil Post Open - National 100,000.00 0.00 Canceled 2017-08-01 2017-08-22 2017-10-05 2017-11-02 2017-12-02 2018-01-06 2018-02-10 2019-02-10 Based Selection aluation Study (Mid-Term & F ding inal) Page 1 IN-SIDBI-196300-CS-QCBS / Design & Development of Sta ndard Product viz. Techno-Fi 2. Component 2: Technical nancial Analysis Tool for eval Quality And Cost- TF / 19308 assistance and capacity buil Post Open - National 130,000.00 0.00 Canceled 2020-10-05 2020-03-11 2020-10-26 2020-11-09 2020-12-09 2020-12-30 2021-01-06 2021-02-05 2021-03-12 2021-04-16 2022-10-13 uation of Energy Efficiency pr Based Selection ding ojects by Participating Financ ial Institutions (PFIs) and gen eration of pipelines for issuan ce of guarantee under PRSF Project. IN-SIDBI-177161-CS-CQS / SI DBI is seeking the services of a reputed consulting agency 2. Component 2: Technical to assist SIDBI and EESL in D Consultant Qualifi TF / 19308 assistance and capacity buil Post Open - National 155,000.00 0.00 Canceled 2020-06-05 2020-07-05 2020-08-19 2020-09-18 2020-11-02 2021-11-02 esign and Development of Ec cation Selection ding osystem including document ations for Super ESCO Dema nd Aggregation Model and Is suance of Guarantees under PRSF Project. IN-SIDBI-229449-CS-QCBS / Legal agency for Developme nt of Standard ESPC Agreem 2. Component 2: Technical Quality And Cost- ents and other documents fo TF / 19308 assistance and capacity buil Post Open - National 85,000.00 0.00 Canceled 2021-04-26 2021-05-24 2021-05-26 2021-05-28 2021-07-09 2021-08-06 2021-09-05 2021-10-19 2021-11-30 2022-05-29 Based Selection r Energy Efficiency sub-proje ding ct implemented through Sup er ESCO Demand Aggregatio n Model IN-SIDBI-875-CS-QCBS / Hirin 2. Component 2: Technical Quality And Cost- g of Measurement & Verificat TF / 19308 assistance and capacity buil Post Open - National 220,000.00 0.00 Canceled 2017-04-01 2021-05-24 2017-04-22 2021-05-28 2017-06-05 2021-07-19 2017-07-03 2017-08-02 2017-09-06 2017-10-11 2018-10-11 Based Selection ion Agency (MVA) under PRS ding F project INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-SIDBI-878-CS-INDV / PRSF Component 1: Partial risk sh Individual Consult 16 (A). Hiring of Office Mana TF / 19308 Post Open - National 300,000.00 0.00 Canceled 2017-03-01 2017-04-19 2017-05-10 2017-06-14 2018-06-13 aring facility ant Selection ger / Office Executive IN-SIDBI-870-CS-CDS / PRSF- 2. Component 2: Technical 1. Marketing of PRSF scheme TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 12,698.58 Completed 2016-08-29 2016-08-29 2016-09-08 2017-01-23 2016-11-12 2017-02-03 2018-11-11 2018-06-15 - Awareness workshops inclu ding ding sponsoring the event / p rogram IN-SIDBI-872-CS-CDS / PRSF- 2. Component 2: Technical TF / 19308 Post Direct Selection Direct 100,000.00 11,215.32 Completed 2019-01-31 2015-02-23 2019-02-10 2015-03-19 2019-04-16 2015-04-01 2019-10-13 2015-09-24 5. Hiring of Legal Firm assistance and capacity buil ding IN-SIDBI-86268-CS-INDV / PR Component 1: Partial risk sh Pending Impleme SF 16C. Hiring of Expert Oper TF / 19308 Post Direct Selection Direct 17,600.00 0.00 2018-11-19 2018-11-29 2019-01-08 2020-01-08 aring facility ntation ations under the PRSF projec t. IN-SIDBI-92321-CS-CDS / ES 2. Component 2: Technical CO projects pipeline generati TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 98,151.27 Completed 2018-12-21 2019-01-08 2018-12-31 2018-12-07 2019-01-23 2019-03-30 2020-01-23 2020-02-11 on for Building Sector. ding IN-SIDBI-92322-CS-CDS / ES 2. Component 2: Technical CO projects pipeline generati TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 98,248.36 Completed 2018-12-21 2019-01-08 2018-12-31 2018-12-07 2019-01-23 2019-02-12 2020-01-18 2020-02-11 on for Industries sector. ding IN-SIDBI-92325-CS-CDS / ES 2. Component 2: Technical CO projects pipeline generati TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 98,170.52 Completed 2018-12-28 2019-01-08 2019-01-07 2018-12-18 2019-01-27 2019-04-02 2020-01-27 2020-02-19 on for Municipalities. ding IN-SIDBI-92326-CS-CDS / Hiri 2. Component 2: Technical Individual Consult TF / 19308 Post Direct 65,000.00 64,152.00 Terminated 2019-01-14 2019-01-10 2019-01-27 2018-12-04 2019-02-06 2019-02-11 2019-03-03 2020-02-19 2020-03-02 ng of Chief Technical Speciali assistance and capacity buil ant Selection st ding IN-SIDBI-80059-CS-CDS / PR 2. Component 2: Technical SF 5B - External Audit of the TF / 19308 assistance and capacity buil Post Direct Selection Direct 897.00 844.29 Completed 2019-01-11 2018-11-01 2019-01-21 2018-10-01 2019-03-27 2018-11-05 2020-03-26 2019-01-14 PRSF project (FY 2017-18). ding IN-SIDBI-99536-CS-INDV / Hi Component 1: Partial risk sh Individual Consult TF / 19308 Post Open - National 100,000.00 60,500.11 Terminated 2019-02-07 2019-04-05 2019-03-13 2016-09-29 2019-03-23 2016-09-29 2019-04-08 2017-01-10 2021-04-07 ring of Lead Technical Expert aring facility ant Selection . IN-SIDBI-100747-CS-INDV / H Component 1: Partial risk sh Individual Consult TF / 19308 Post Open - National 100,000.00 72,488.13 Terminated 2019-02-14 2019-04-05 2019-03-20 2016-03-09 2019-03-30 2016-04-25 2019-04-15 2016-04-27 2021-05-04 iring of Senior Technical Exp aring facility ant Selection ert IN-SIDBI-100749-CS-CDS / Hi 2. Component 2: Technical ring of CA firm for maintenan TF / 19308 assistance and capacity buil Post Direct Selection Direct 10,000.00 8,418.91 Completed 2019-02-14 2016-01-01 2019-02-18 2016-02-02 2019-02-27 2016-02-22 2020-03-03 2019-02-21 ce of Books of Accounts and ding Providing Secretarial /Admini strative Services. IN-SIDBI-129278-CS-INDV / H 2. Component 2: Technical Individual Consult TF / 19308 Post Open - National 55,000.00 44,630.64 Terminated 2019-09-02 2019-08-23 2019-10-10 2019-10-23 2019-10-20 2019-10-23 2019-11-05 2019-11-26 2021-11-04 iring of Technical Expert assistance and capacity buil ant Selection ding IN-SIDBI-129277-CS-INDV / H 2. Component 2: Technical Individual Consult TF / 19308 Post Open - National 65,000.00 51,877.11 Signed 2019-09-02 2019-08-23 2019-10-10 2019-10-21 2019-10-20 2019-10-23 2019-11-05 2019-12-03 2021-11-04 iring of Procurement and Ad assistance and capacity buil ant Selection min Expert ding IN-SIDBI-151134-CS-INDV / H 2. Component 2: Technical Individual Consult IRING OF ENVIRONMENT AND TF / 19308 assistance and capacity buil Post Open - National 85,000.00 34,080.60 Signed 2020-02-07 2020-01-20 2020-03-26 2020-08-19 2020-04-10 2020-08-19 2020-05-13 2020-09-24 2022-05-13 ant Selection SOCIAL SAFEGUARD EXPERT ding IN-SIDBI-129275-CS-INDV / H 2. Component 2: Technical Individual Consult TF / 19308 Post Open - National 60,000.00 50,583.52 Terminated 2019-09-02 2019-08-23 2019-10-10 2019-10-23 2019-10-20 2019-10-23 2019-11-05 2019-11-30 2021-11-04 iring of Experts Operations assistance and capacity buil ant Selection ding IN-SIDBI-129274-CS-INDV / H 2. Component 2: Technical Individual Consult TF / 19308 Post Open - National 90,000.00 84,100.71 Signed 2019-09-02 2019-08-23 2019-10-10 2019-10-14 2019-10-20 2019-11-05 2020-01-07 2021-11-04 iring of Lead Technical Exper assistance and capacity buil ant Selection t ding IN-SIDBI-129243-CS-INDV / H 2. Component 2: Technical Individual Consult TF / 19308 Post Open - National 151,000.00 218,024.05 Terminated 2019-09-02 2019-08-23 2019-10-10 2019-10-23 2019-10-20 2019-10-23 2019-11-05 2019-10-25 2021-11-04 iring of Chief Technical Speci assistance and capacity buil ant Selection alist. ding IN-SIDBI-1009-CS-INDV / PRS Component 1: Partial risk sh Individual Consult F 16A. Hiring of Technical Ex TF / 19308 Post Open 300,000.00 0.00 Canceled 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2018-06-12 aring facility ant Selection perts (Environment) IN-SIDBI-92330-CS-CDS / ES 2. Component 2: Technical CO projects pipeline generati TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 0.00 Canceled 2019-01-11 2019-01-24 2019-01-26 2019-04-02 2019-09-29 on in selected 10 clusters (Zo ding ne:1) Page 2 IN-SIDBI-92332-CS-CDS / ES 2. Component 2: Technical CO projects pipeline generati TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 0.00 Canceled 2019-01-11 2019-01-24 2019-01-26 2019-04-02 2019-09-29 on in selected 10 clusters (Zo ding ne:2) IN-SIDBI-225805-CS-INDV / H 2. Component 2: Technical Individual Consult TF / 19308 Post Open 72,000.00 73,113.83 Signed 2021-03-30 2021-04-06 2021-07-03 2021-05-18 2021-07-23 2021-06-23 2021-09-11 2021-07-16 2023-09-11 iring of Senior Technical Exp assistance and capacity buil ant Selection ert ding IN-SIDBI-225807-CS-INDV / H 2. Component 2: Technical Individual Consult iring of Environment & Social TF / 19308 assistance and capacity buil Post Open 85,000.00 73,113.83 Signed 2021-03-30 2021-04-06 2021-07-03 2021-05-18 2021-07-23 2021-06-23 2021-09-11 2021-07-16 2023-09-11 ant Selection Safeguard Expert ding IN-SIDBI-1012-CS-CDS / PRS 2. Component 2: Technical F-8A. Training of PFIs - Condu TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 0.00 Canceled 2018-04-02 2018-04-12 2018-06-16 2019-06-15 cting Classroom Training ding IN-SIDBI-871-CS-CDS / PRSF- 2. Component 2: Technical 3. Development of appraisal / TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 0.00 Canceled 2016-09-30 2016-10-10 2016-12-14 2017-06-12 due diligence tool for PFIs ding IN-SIDBI-1006-CS-CDS / PRS 2. Component 2: Technical F- 1A. Marketing of PRSF sch TF / 19308 assistance and capacity buil Post Direct Selection Direct 50,000.00 0.00 Canceled 2019-04-01 2019-04-11 2019-06-15 2020-06-14 eme - Awareness workshops ding including sponsoring the eve nt / program IN-SIDBI-80070-CS-CDS / PR 2. Component 2: Technical SF - 5C - Internal Financial Au TF / 19308 assistance and capacity buil Post Direct Selection Direct 1,860.00 0.00 Canceled 2018-11-19 2018-11-29 2019-02-02 2020-02-02 dit and Operational Audit for ding PRSF (FY 2018-19). IN-SIDBI-129280-CS-INDV / H 2. Component 2: Technical Individual Consult TF / 19308 Post Open - National 40,000.00 0.00 Canceled 2019-09-02 2019-08-23 2019-10-10 2019-10-14 2019-10-20 2019-11-05 2021-11-04 iring of Technical Executive assistance and capacity buil ant Selection ding IN-SIDBI-876-CS-INDV / PRSF 2. Component 2: Technical Individual Consult TF / 19308 Post Open - National 200,000.00 0.00 Canceled 2016-09-01 2016-10-20 2016-11-10 2016-12-15 2017-12-14 -6. Hiring of Chief Technical S assistance and capacity buil ant Selection pecialist ding IN-SIDBI-1014-CS-CDS / PRS 2. Component 2: Technical F-8 C. Training of PFIs - Cond TF / 19308 assistance and capacity buil Post Direct Selection Direct 66,000.00 0.00 Canceled 2021-04-01 2021-04-11 2021-06-15 2022-06-14 ucting Classroom Training ding IN-SIDBI-1013-CS-CDS / PRS 2. Component 2: Technical F-8 B. Training of PFIs - Cond TF / 19308 assistance and capacity buil Post Direct Selection Direct 66,000.00 0.00 Canceled 2020-04-02 2020-04-12 2020-06-16 2021-06-15 ucting Classroom Training ding IN-SIDBI-1011-CS-INDV / PRS Component 1: Partial risk sh Individual Consult TF / 19308 Post Open 200,000.00 0.00 Canceled 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2018-06-12 F 16 B. Hiring of Technical Ex aring facility ant Selection perts IN-SIDBI-877-CS-INDV / PRSF Component 1: Partial risk sh Individual Consult 16. Hiring of Technical Expert TF / 19308 Post Open - National 300,000.00 0.00 Canceled 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2018-06-12 aring facility ant Selection s (Energy) IN-SIDBI-151152-CS-CQS / In 2. Component 2: Technical ternational Conference on im TF / 19308 assistance and capacity buil Post Direct Selection Direct 40,000.00 0.00 Canceled 2019-12-20 2020-01-19 2020-02-13 2020-08-11 plementation of Energy Effici ding ency Projects through ESCO mode IN-SIDBI-225801-CS-INDV / H 2. Component 2: Technical Individual Consult TF / 19308 Post Open 60,000.00 0.00 Canceled 2021-03-30 2021-04-06 2021-07-03 2021-06-14 2021-07-23 2021-09-11 2023-09-11 iring of Expert Operations assistance and capacity buil ant Selection ding IN-SIDBI-873-CS-CDS / PRSF- 2. Component 2: Technical 8. Training of PFIs - Conducti TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 0.00 Canceled 2016-08-31 2016-09-16 2016-09-10 2016-11-14 2017-11-13 ng Classroom Training ding IN-SIDBI-1008-CS-CDS / PRS 2. Component 2: Technical TF / 19308 Post Direct Selection Direct 50,000.00 0.00 Canceled 2021-04-01 2021-04-11 2021-06-15 2021-12-12 F-5A. Hiring of Legal Firm assistance and capacity buil ding IN-SIDBI-251297-CS-CDS / Hi 2. Component 2: Technical ring of CA firm for maintenan TF / 19308 assistance and capacity buil Post Direct Selection Direct 40,000.00 0.00 Under Review 2021-09-05 2019-02-15 2021-09-09 2021-09-18 2024-09-17 ce of Books of Accounts and ding Providing Secretarial / Admini strative Services. IN-SIDBI-273146-CS-CDS / Hi ring of Legal agency for Deve lopment of Standard Energy 2. Component 2: Technical Saving Performance Contract Under Implement TF / 19308 assistance and capacity buil Post Direct Selection Direct 60,000.00 0.00 2022-02-01 2021-04-02 2022-02-11 2022-04-17 2022-09-14 Agreements and other docu ation ding ments for Energy Efficiency s ub-project implemented thro ugh Super ESCO based Dema nd Aggregation Model IN-SIDBI-297288-CS-INDV / P 2. Component 2: Technical Individual Consult Under Implement TF / 19308 Post Open - National 55,000.00 0.00 2022-06-01 2022-06-06 2022-07-16 2022-07-26 2022-08-20 2023-08-20 rocurement & Admin Expert assistance and capacity buil ant Selection ation Hiring ding IN-SIDBI-305836-CS-INDV / S eeking to hire the services of 5 nos. of Technical Officers, o 2. Component 2: Technical Individual Consult Under Implement n contract basis, to undertak TF / 19308 assistance and capacity buil Post Open - National 90,000.00 0.00 2022-07-25 2022-08-01 2022-09-08 2022-09-18 2022-10-13 2023-10-13 ant Selection ation e several tasks related to de ding veloping the market of energ y services Officers under PRS F Project IN-SIDBI-364598-CS-INDV / H 2. Component 2: Technical Individual Consult Pending Impleme iring 06 Experts / Consultants TF / 19308 assistance and capacity buil Post Open - National 225,000.00 0.00 2023-06-07 2023-07-26 2023-08-16 2023-09-20 2024-03-18 ant Selection ntation Under PRSF Scheme ding Page 3 PROCUREMENT PLAN (Textual Part) Project information: [Ghana] [Ghana Productive Safety Net Project 2 (GPSNP 2) [P-175588] Project Implementation agency: [Ministry of Gender, Children and Social Protection (MoGCSP) and Ministry of Local Government, Decentralisation and Rural Development (MLGDRD) Date of the Procurement Plan: [26/02/2021] Period covered by this Procurement Plan: [01 July 2021 – 31 December 2022] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Act, 2003 (Act 663) which was amended in 2016 by the Public Procurement (Amendment) Act, 2016, (Act 914), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. 56 (1) Tenders shall be opened (a) at the time specified in the tender documents as the deadline for the submission of tenders or at the deadline specified in any extension of the deadline; and (b) at the place and in accordance with the procedures specified the tender documents. (2) The time for opening of the tenders shall be the same as the deadline for the receipt of the tenders or promptly after that deadline. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information. Procedures for CDD components: Community Driven Development (CDD) activities are works activities, which are carried out directly by communities. Procurement of Materials Procurement of materials for the activities would be done through the procurement method limited- open. The activities to be carried out: i. Issuance of Request for quotation (at least 3 bidders); ii. Submission and opening of bids for bidders; iii. Evaluation of bids iv. Issuance of Acceptance Letters; v. Signing of Contracts Selection of Community Members Selection of communities to participate in the CDD activities shall be done through direct selection procurement method. Agreement is then signed between the Implementation Agencies (Municipals and District Assemblies) to cover the duration of the activity. PROCUREMENT Ghana : Ghana Productive Safety Net Project 2 PLAN General Information Country: Ghana 2021-03-01 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175588 GPN Date: Project Name: Ghana Productive Safety Net Project 2 Loan / Credit No: IDA / 68590 MINISTRY OF LOCAL GOVERNMENT AND RURAL DEVELOPMENT - RCU Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GH-MLGRD-RCU-334785-CW Request for Quota -RFQ / Rehabilitation of Abon Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 IDA / 68590 Post Open - National 72,000.00 0.00 2023-03-05 2023-04-30 gokrom -Tiabante - Owusukr Program tions nvelope s (Emergency) SP lementation 9 om Feeder Road (5.50km) D -Competitive Request for Quota GH-MLGRD-RCU-334788-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Yabe IDA / 68590 Post Open - National 70,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 neagya - Kwamekuma Feede D -Competitive r Road (3.50km) GH-MLGRD-RCU-334790-CW Request for Quota -RFQ / Rehabilitation of Sunk Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 IDA / 68590 Post Open - National 66,000.00 0.00 2023-03-05 2023-04-09 wa -Tenso-Onwe-Dinkyini Fee Program tions nvelope s (Emergency) SP lementation 8 der Road (5.0km) D -Competitive Request for Quota GH-MLGRD-RCU-334791-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Derm IDA / 68590 Post Open - National 33,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 a - Monta Feeder Road (2.50 D -Competitive km) GH-MLGRD-RCU-334792-CW Request for Quota -RFQ / Rehabilitation of New Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 23,500.00 0.00 2023-03-05 2023-04-09 Bosankro - Akuraadadaa-Man Program tions nvelope s (Emergency) SP mentation 8 hutem Feeder Road (2.0km) D -Competitive Request for Quota GH-MLGRD-RCU-334793-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Drom IDA / 68590 Post Open - National 69,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ankuma -Fakawa Feeder Roa D -Competitive d (4.50km) GH-MLGRD-RCU-334794-CW Request for Quota -RFQ / Rehabilitation of Nkwa Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 IDA / 68590 Post Open - National 48,000.00 0.00 2023-03-05 2023-04-09 nta Farm Jnc.-Hiawoanwu Fe Program tions nvelope s (Emergency) SP lementation 8 eder Road (4.2km) D -Competitive Request for Quota GH-MLGRD-RCU-336045-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Abes IDA / 68590 Post Open - National 44,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ewa-Databi Feeder Road (4.4 D -Competitive km) Request for Quota GH-MLGRD-RCU-336046-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Bons IDA / 68590 Post Open - National 54,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ukrom Jnc.-Adense Feeder Ro D -Competitive ad (5.0km) Request for Quota GH-MLGRD-RCU-336047-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Srent IDA / 68590 Post Open - National 36,200.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 iantia-Abrofoa Feeder Road ( D -Competitive 2.50km) GH-MLGRD-RCU-336049-CW Request for Quota -RFQ / Rehabilitation of Yebo Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 67,500.00 0.00 2023-03-05 2023-04-09 ah Apatam - Nsuguasua Feed Program tions nvelope s (Emergency) SP mentation 8 er Road (5.70km) D -Competitive GH-MLGRD-RCU-336050-CW Request for Quota -RFQ / Rehabilitation of Ayaa Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 IDA / 68590 Post Open - National 60,000.00 0.00 2023-03-05 2023-04-09 kwa Junction-Bebeduaso Fee Program tions nvelope s (Emergency) SP lementation 8 der Road(4.50km) D -Competitive GH-MLGRD-RCU-336051-CW Request for Quota -RFQ / Rehabilitation of Mang Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 51,000.00 0.00 2023-03-05 2023-04-09 oase Jnc -Akyease - Mpentua Program tions nvelope s (Emergency) SP mentation 8 se Feeder Road (4.0km) D -Competitive GH-MLGRD-RCU-336052-CW Request for Quota -RFQ / Rehabilitation of Hani- Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 64,400.00 0.00 2023-03-05 2023-04-09 Proposed Tourist Site (Gbeho Program tions nvelope s (Emergency) SP mentation 8 ) Feeder Road (3.50km) D -Competitive Request for Quota GH-MLGRD-RCU-336053-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Mire IDA / 68590 Post Open - National 83,800.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 mano -Berekumkroaso Feede D -Competitive r Road (5.50km) GH-MLGRD-RCU-336054-CW Request for Quota -RFQ / Rehabilitation of Nwoa Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 69,000.00 0.00 2023-03-05 2023-04-09 se - Seiduakuraa - Aboabo Fe Program tions nvelope s (Emergency) SP mentation 8 eder Road (4.80km) D -Competitive Request for Quota GH-MLGRD-RCU-336055-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Sikaa IDA / 68590 Post Open - National 58,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 -Wansamkuraa Feeder Road D -Competitive (5.0km) Request for Quota GH-MLGRD-RCU-336330-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Akru IDA / 68590 Post Open - National 56,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ma - Bobrobo Feeder Road (3 D -Competitive .80km) Request for Quota GH-MLGRD-RCU-336331-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation Of Kobe IDA / 68590 Post Open - National 80,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 da No. 1 - Kobeda No. 2 Feed D -Competitive er Road (5.80km) Request for Quota GH-MLGRD-RCU-336336-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Bami IDA / 68590 Post Open - National 70,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ra - Asantanso Feeder Road ( D -Competitive 5.70km) Request for Quota GH-MLGRD-RCU-336341-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Tawia IDA / 68590 Post Open - National 53,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 kwaa-Annan Feeder Road (3. D -Competitive 1km) Page 1 Request for Quota GH-MLGRD-RCU-336342-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Enyis IDA / 68590 Post Open - National 60,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 am - Takyiman Feeder Road ( D -Competitive 3.5km) Request for Quota GH-MLGRD-RCU-336343-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Yaw IDA / 68590 Post Open - National 66,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 Duodo-Kobiso Feeder Road ( D -Competitive 3.9km) Request for Quota GH-MLGRD-RCU-336344-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Kwab IDA / 68590 Post Open - National 51,100.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 oadi No.2-Aboso Jnc. Feeder D -Competitive Road (4.7km) GH-MLGRD-RCU-336345-CW Request for Quota -RFQ / Rehabilitation of Sema Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 75,000.00 0.00 2023-03-05 2023-04-09 nhyia-Kyeame Kissi-Kyemfre Program tions nvelope s (Emergency) SP mentation 8 Feeder Road (10.60km) D -Competitive GH-MLGRD-RCU-336346-CW Request for Quota -RFQ / Rehabilitation of Mota Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 46,000.00 0.00 2023-03-05 2023-04-09 Afarikrom-Nkwaakwaasem F Program tions nvelope s (Emergency) SP mentation 8 eeder Road (2.4km) D -Competitive Request for Quota GH-MLGRD-RCU-336347-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Agog IDA / 68590 Post Open - National 62,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 o-Okyerekrom Feeder Road ( D -Competitive 3.1km) Request for Quota GH-MLGRD-RCU-336348-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Akrus IDA / 68590 Post Open - National 66,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 u Jnc.-Asekeso Feeder Road ( D -Competitive 3.64km) Request for Quota GH-MLGRD-RCU-336349-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Wate IDA / 68590 Post Open - National 29,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 r Works Jnc.-Muerter Feeder D -Competitive Road (1.5km) Request for Quota GH-MLGRD-RCU-336350-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Dave IDA / 68590 Post Open - National 41,200.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 -Gbleve Feeder Road (2.0km) D -Competitive Request for Quota GH-MLGRD-RCU-336352-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Adze IDA / 68590 Post Open - National 66,400.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 kofe Jnc.-Adzekofe Feeder Ro D -Competitive ad (3.95km) Request for Quota GH-MLGRD-RCU-336354-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Tsrib IDA / 68590 Post Open - National 62,400.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ormi-Kesenyemito Feeder Ro D -Competitive ad (4.2km) Request for Quota GH-MLGRD-RCU-336355-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation Of Kped IDA / 68590 Post Open - National 44,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ze Tordze-Anagokope Feeder D -Competitive Road (1.8km) Request for Quota GH-MLGRD-RCU-336356-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Duku IDA / 68590 Post Open - National 77,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ma Tsrukpe-Zanukope Feede D -Competitive r Road (4.6km) Request for Quota GH-MLGRD-RCU-336549-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-10-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 86,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 7 Earth Dam at Adaklu Torda D -Competitive GH-MLGRD-RCU-336551-CW Request for Quota -RFQ / Rehabilitation of Korsi Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 36,000.00 0.00 2023-03-05 2023-04-09 ve Jnc.-Cashew Plantation Sit Program tions nvelope s (Emergency) SP mentation 8 e Feeder Road (2.0km) D -Competitive Request for Quota GH-MLGRD-RCU-336555-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Ladu IDA / 68590 Post Open - National 60,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 mdo-Nalogni-Tindando Feede D -Competitive r Road 5.00km Request for Quota GH-MLGRD-RCU-336557-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-10-2 -RFQ / Construction of Paralle IDA / 68590 Post Open - National 50,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 7 l Drain at Wulensi Dam D -Competitive Request for Quota GH-MLGRD-RCU-336559-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Mpah IDA / 68590 Post Open - National 27,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 a-Chukonto Feeder Road (2.0 D -Competitive 0 km) Request for Quota GH-MLGRD-RCU-336561-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Naku IDA / 68590 Post Open - National 81,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 nga Jnt - Nakunga Feeder Ro D -Competitive ad (5.0km) Request for Quota GH-MLGRD-RCU-336562-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Gbanl IDA / 68590 Post Open - National 84,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ua - Ditani Feeder Road (6.5k D -Competitive m) Request for Quota GH-MLGRD-RCU-336564-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 91,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 9 Earth Dam at Kumoayili D -Competitive Request for Quota GH-MLGRD-RCU-336566-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Bagli IDA / 68590 Post Open - National 51,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 - Bagkurli Feeder Road (3.5k D -Competitive m) Request for Quota GH-MLGRD-RCU-336567-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Nant IDA / 68590 Post Open - National 76,700.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 on - Yapalsi Feeder Road (4. D -Competitive 8km) Request for Quota GH-MLGRD-RCU-336569-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Nach IDA / 68590 Post Open - National 78,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 amba No. 2 - Tatale Feeder D -Competitive Road (5.2km) Request for Quota GH-MLGRD-RCU-336570-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 55,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 Earth Dam at Nanton Kurugu D -Competitive Request for Quota GH-MLGRD-RCU-336581-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Gork IDA / 68590 Post Open - National 61,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ugani- Natindo Feeder Road ( D -Competitive 5.0km) Page 2 Request for Quota GH-MLGRD-RCU-336584-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 92,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 9 Earth Dam at Kuyuli D -Competitive Request for Quota GH-MLGRD-RCU-336585-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 86,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 9 Earth Dam At Kpalgigbeni D -Competitive Request for Quota GH-MLGRD-RCU-336588-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 91,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 9 Earth Dam at Kuyuli D -Competitive Request for Quota GH-MLGRD-RCU-336589-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 55,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 Earth Dam at Nanton Kurugu D -Competitive Request for Quota GH-MLGRD-RCU-336590-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 91,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 Earth Dam at Buegmal D -Competitive Request for Quota GH-MLGRD-RCU-336591-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Dika- IDA / 68590 Post Open - National 60,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 Ahamansu Feeder Roads (4.0 D -Competitive km) Ph2 Request for Quota GH-MLGRD-RCU-336592-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Kachi IDA / 68590 Post Open - National 44,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 nke-Lugnuldo Feeder Road 2. D -Competitive 60 Km GH-MLGRD-RCU-336593-CW Request for Quota -RFQ / Rehabilitation of Pechi Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 65,000.00 0.00 2023-03-05 2023-04-09 Akura Jnt. - Ahiamankyene F Program tions nvelope s (Emergency) SP mentation 8 eeder Road (5.0km D -Competitive Request for Quota GH-MLGRD-RCU-336594-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Tsafo IDA / 68590 Post Open - National 71,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 kura Jnc. - Tsafokura Feeder D -Competitive Road (5.0km) Request for Quota GH-MLGRD-RCU-336595-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Grubi IDA / 68590 Post Open - National 58,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 - Akaniem Feeder Road (4.0 D -Competitive km) GH-MLGRD-RCU-336596-CW Request for Quota -RFQ / Rehabilitation of Mam Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 49,000.00 0.00 2023-03-05 2023-04-09 a Kura- Hundokope Feeder R Program tions nvelope s (Emergency) SP mentation 8 oad(3.0km) Phase 2 D -Competitive Request for Quota GH-MLGRD-RCU-336597-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Kito- IDA / 68590 Post Open - National 48,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 Kito Nkwanta Feeder Road 4. D -Competitive 6km Request for Quota GH-MLGRD-RCU-336598-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Fuu. - IDA / 68590 Post Open - National 83,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 Takpli Feeder Road (6.7km) D -Competitive Request for Quota GH-MLGRD-RCU-336600-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Bonb IDA / 68590 Post Open - National 29,000.00 0.00 2023-03-05 2023-03-14 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ontey Jnc - Bonbontey Feeder D -Competitive (1.50km) Request for Quota GH-MLGRD-RCU-336601-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Noko IDA / 68590 Post Open - National 48,500.00 0.00 2023-03-05 2023-03-15 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 yiri - Samariyiri Feeder Road D -Competitive (2.50km) Request for Quota GH-MLGRD-RCU-336602-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation Of Mank IDA / 68590 Post Open - National 78,000.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 arigu-Sakpala-Kpatarigu Fee D -Competitive der Road (4.5km) Request for Quota GH-MLGRD-RCU-336604-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Rehabilitation of Kagb IDA / 68590 Post Open - National 85,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 al Small Earth Dam D -Competitive Request for Quota GH-MLGRD-RCU-336616-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Moyir IDA / 68590 Post Open - National 77,800.00 0.00 2023-03-05 2023-03-15 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 i - Konzokala Feeder Road (4. D -Competitive 5km) Request for Quota GH-MLGRD-RCU-336636-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Kont IDA / 68590 Post Open - National 77,400.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 wiri - Chachaa Feeder Road ( D -Competitive 3.5km) Request for Quota GH-MLGRD-RCU-336637-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Kohu IDA / 68590 Post Open - National 77,800.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 o - Pina Feeder Road (4.7km) D -Competitive Request for Quota GH-MLGRD-RCU-336640-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 85,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 Earth Dam at Boo D -Competitive Request for Quota GH-MLGRD-RCU-336641-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Furo - IDA / 68590 Post Open - National 42,100.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 Gbier Feeder Road (2.5km) D -Competitive Request for Quota GH-MLGRD-RCU-336644-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Goli - IDA / 68590 Post Open - National 64,000.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 Kaabogu Feeder Road (3.35k D -Competitive m) Request for Quota GH-MLGRD-RCU-336648-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Domi IDA / 68590 Post Open - National 36,000.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ngye - Nabugangn Feeder Ro D -Competitive ad (2.2km) Request for Quota GH-MLGRD-RCU-336649-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Guo IDA / 68590 Post Open - National 43,400.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 mwaane - Hayore Feeder Ro D -Competitive ad (2.5km) Request for Quota GH-MLGRD-RCU-336652-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Puze IDA / 68590 Post Open - National 78,000.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ne-Boo Feeder Road (6.6km) D -Competitive Page 3 Request for Quota GH-MLGRD-RCU-336656-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Dorn IDA / 68590 Post Open - National 98,000.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ye - Dorkyire Feeder Road (5. D -Competitive 0km) Request for Quota GH-MLGRD-RCU-337227-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Wiidi- IDA / 68590 Post Open - National 76,900.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 Kukanga-Buzunde Feeder Ro D -Competitive ad (5.8km) Request for Quota GH-MLGRD-RCU-337229-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Gund IDA / 68590 Post Open - National 76,200.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ago- Gbango-Kansogo Feeder D -Competitive Road (5.0km) Request for Quota GH-MLGRD-RCU-337232-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Samb IDA / 68590 Post Open - National 80,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 oliga-Agatuse Feeder Road (3 D -Competitive .7km) Request for Quota GH-MLGRD-RCU-337234-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Nayo IDA / 68590 Post Open - National 75,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ko No. 2 - Gore Clinic Feeder D -Competitive Road (5.5km) Request for Quota GH-MLGRD-RCU-337235-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Aniisi IDA / 68590 Post Open - National 58,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 - Belimpiisi Feeder Road (3.5 D -Competitive km) Request for Quota GH-MLGRD-RCU-337236-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Sana IDA / 68590 Post Open - National 87,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 biisi -Kabre - Akulyor Feeder D -Competitive Road (5.0km) GH-MLGRD-RCU-337237-CW Request for Quota -RFQ / Rehabilitation of Akuy Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 IDA / 68590 Post Open - National 86,000.00 0.00 2023-03-05 2023-04-09 elingo - Tingre -Wegurigo Fee Program tions nvelope s (Emergency) SP lementation 8 der Road (5.0km) D -Competitive Request for Quota GH-MLGRD-RCU-337238-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Donin IDA / 68590 Post Open - National 68,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ga - Banyangsa Feeder Road D -Competitive (4.0km) Request for Quota GH-MLGRD-RCU-337239-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Gban IDA / 68590 Post Open - National 84,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 koni - Nanjong No. 2 Feeder D -Competitive Road (6.9km) Request for Quota GH-MLGRD-RCU-337240-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Natur IDA / 68590 Post Open - National 77,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 i -Tichangu Feeder Road (5.0 D -Competitive km) Request for Quota GH-MLGRD-RCU-337242-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Natur IDA / 68590 Post Open - National 65,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 i Junc- Naturi Feeder Road (3. D -Competitive 4km) Request for Quota GH-MLGRD-RCU-337243-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Gam IDA / 68590 Post Open - National 84,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 baga - Zimasa Feeder Road ( D -Competitive 5.0km) Request for Quota GH-MLGRD-RCU-337244-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Song IDA / 68590 Post Open - National 81,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 o-Songure Feeder Road (5.0k D -Competitive m) Request for Quota GH-MLGRD-RCU-337246-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Farfa IDA / 68590 Post Open - National 83,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 r- Walkman Feeder Road (5.0 D -Competitive km) Request for Quota GH-MLGRD-RCU-337247-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Jade IDA / 68590 Post Open - National 86,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ma-Buyinga Feeder Road (5. D -Competitive 4km) Request for Quota GH-MLGRD-RCU-337249-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Kulsa IDA / 68590 Post Open - National 51,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 lboug - Zanlerigu Feeder Ro D -Competitive ad (2.1 Km) GH-MLGRD-RCU-337250-CW Request for Quota -RFQ / Rehabilitation of Zopel Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 IDA / 68590 Post Open - National 71,000.00 0.00 2023-03-05 2023-04-09 iga - Dagliga Basic School Fe Program tions nvelope s (Emergency) SP lementation 8 eder Road (4.0km) D -Competitive Request for Quota GH-MLGRD-RCU-337251-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Ajeng IDA / 68590 Post Open - National 71,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 o Natinga- Tesnatinga Feede D -Competitive r Road (4.3km) Request for Quota GH-MLGRD-RCU-337252-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Pwal IDA / 68590 Post Open - National 58,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ugu-Manpelugu Feeder Road D -Competitive (3.5km) Request for Quota GH-MLGRD-RCU-337253-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Wink IDA / 68590 Post Open - National 66,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ongo-Dapore Feeder Road (4. D -Competitive 0km) Request for Quota GH-MLGRD-RCU-337254-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Imigr IDA / 68590 Post Open - National 79,100.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ation Junc- Tafakwan Feeder D -Competitive Road (5.0km) Request for Quota GH-MLGRD-RCU-337256-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Completion of Small E IDA / 68590 Post Open - National 24,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 arth Dam at Nayorku D -Competitive Request for Quota GH-MLGRD-RCU-337257-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 -RFQ / Completion of Small E IDA / 68590 Post Open - National 79,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 9 arth Dam at Agargo D -Competitive Request for Quota GH-MLGRD-RCU-337258-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 -RFQ / Completion of Small E IDA / 68590 Post Open - National 22,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 9 arth Dam at Mangor D -Competitive Request for Quota GH-MLGRD-RCU-337260-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Completion of Small E IDA / 68590 Post Open - National 68,500.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 arth Dam at Namongo D -Competitive Page 4 Request for Quota GH-MLGRD-RCU-336599-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 127,000.00 0.00 2023-03-05 2023-03-15 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Sornyo D -Competitive Request for Quota GH-MLGRD-RCU-336619-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 137,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Dapuoha D -Competitive Request for Quota GH-MLGRD-RCU-337262-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 111,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Dagubaa D -Competitive Request for Quota GH-MLGRD-RCU-337261-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 170,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Dagbigu D -Competitive Request for Quota GH-MLGRD-RCU-336651-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 111,400.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Bakwalla D -Competitive Request for Quota GH-MLGRD-RCU-336617-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 170,800.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Nakpala D -Competitive Request for Quota GH-MLGRD-RCU-336642-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 102,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Gbankor D -Competitive Request for Quota GH-MLGRD-RCU-336657-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 128,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Janbob D -Competitive Request for Quota GH-MLGRD-RCU-336639-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 176,500.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 1 Earth Dam at Hachagagan D -Competitive Request for Quota GH-MLGRD-RCU-336618-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation Of Smal IDA / 68590 Post Open - National 132,600.00 0.00 2023-03-05 2023-03-15 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 l Earth Dam at Saapari D -Competitive Request for Quota GH-MLGRD-RCU-336653-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 174,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Nyentie D -Competitive Request for Quota GH-MLGRD-RCU-336654-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 148,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Sogla D -Competitive GH-MLGRD-RCU-334786-CW Request for Quota -RFQ / Rehabilitation of Amo Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-12-3 IDA / 68590 Post Open - National 64,000.00 0.00 2023-03-05 2023-04-30 maso -Ninkyeama - Sentaso Program tions nvelope s (Emergency) SP lementation 1 Feeder Road (5.20km) D -Competitive Request for Quota GH-MLGRD-RCU-336334-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Kofi IDA / 68590 Post Open - National 92,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 1 Djankrom - Kakraka Feeder R D -Competitive oad(6.30km) GH-MLGRD-RCU-337255-CW Request for Quota -RFQ / Rehabilitation of Bimb Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-01-3 IDA / 68590 Post Open - National 83,400.00 0.00 2023-04-05 2023-05-10 ago-Gbingbalanchet Phase 1 Program tions nvelope s (Emergency) SP lementation 1 Feeder Road (5.0km) D -Competitive Request for Quota GH-MLGRD-RCU-341117-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-02-1 -RFQ / Rehabilitation of Nako IDA / 68590 Post Open - National 113,500.00 0.00 2023-04-05 2023-05-31 Program tions nvelope s (Emergency) SP mentation 1 re - Kpongu Feeder Road (5.0 D -Competitive km) Request for Quota GH-MLGRD-RCU-341120-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-02-1 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 132,000.00 0.00 2023-04-05 2023-05-31 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Bokpieriyiri D -Competitive GH-MLGRD-RCU-365594-CW -RFQ / Construction of On-sit e Creches and Temporary Toi lets for CCMI Nurseries and Pl Request for Quota Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Imp 2024-02-2 antations for Builsa South, B IDA / 68590 Post Open - National tions (Non Bank-S 32,000.00 0.00 2023-07-02 2023-08-27 Program tions nvelope lementation 3 uilsa North Municipal, Bongo, PD) Talensi, Nabdam, Bawku Wes t , Binduri, Bawku Municipal, Pusiga, Tempane and Garu Districts by the UERCC GH-MLGRD-RCU-365602-CW -RFQ / Construction of Fencin g for CCMI Nurseries and Pla Request for Quota ntations sites (119.3 Ha) for Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Imp 2024-02-2 IDA / 68590 Post Open - National tions (Non Bank-S 131,664.00 0.00 2023-07-02 2023-08-27 Builsa South, Builsa North Mu Program tions nvelope lementation 3 PD) nicipal, Bongo, Talensi, Nabd am, Bawku West ,Binduri, Ba wku Municipal, Pusiga, Temp ane and Garu Districts by th e UERCC. GH-MLGRD-RCU-365610-CW -RFQ / Construction of Boreh oles for CCMI Nurseries and P lantations for Builsa South, B Request for Quota Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Imp 2024-02-2 uilsa North Municipal, Bongo, IDA / 68590 Post Open - National tions (Non Bank-S 50,909.00 0.00 2023-07-02 2023-08-27 Program tions nvelope lementation 3 Talensi, Nabdam, Bawku Wes PD) t, Bawku Municipal, Binduri, Garu, Pusiga, Tempane, Bunk prugu, East mamprusi, and o ther Districts in UERCC. GH-MLGRD-RCU-365627-CW -RFQ / Construction of On-sit e Creches & Temporary Toile Request for Quota ts for CCMI Nurseries and Pla Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Imp 2024-02-2 IDA / 68590 Post Open - National tions (Non Bank-S 12,273.00 0.00 2023-07-02 2023-08-27 ntations for Mamprugu Moag Program tions nvelope lementation 3 PD) duri, East Mamprusi Municipa l, Bunkpurugu-Nakpanduri an d Yunyoo-Nasuan Districts by the NERCC Page 5 GH-MLGRD-RCU-365630-CW -RFQ / Construction of Fence for CCMI Nurseries and Plant Request for Quota Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Imp 2024-02-2 ations for Mamprugu Moagdu IDA / 68590 Post Open - National tions (Non Bank-S 4,727.00 0.00 2023-07-02 2023-08-27 Program tions nvelope lementation 3 ri, East Mamprusi Municipal, PD) Bunkpurugu - Nakpanduri an d Yunyoo-Nasuan Districts by the NERCC GH-MLGRD-RCU-364275-GO- RFQ / Supply of materials for Request for Quota concrete works for the rehabi Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Imp 2024-01-2 IDA / 68590 Post Open - National tions (Non Bank-S 17,497.00 0.00 2023-06-25 2023-08-01 litation of 10ha degraded co Program tions nvelope lementation 8 PD) mmunal land and developme nt of watershed, facility at Ns esresu - concrete works GH-MLGRD-RCU-365584-CW Request for Quota -RFQ / Construction of 3 No. Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-02-2 Ancillary structures (On - site IDA / 68590 Post Open - National 4,910.00 0.00 2023-07-02 2023-08-27 Program tions nvelope s (Emergency) SP lementation 3 Creche and Temporary toilet) D -Competitive at Liati Soba and Ve Deme in Afadzato District GH-MLGRD-RCU-367456-CW -RFQ / Construction of on-site Request for Quota Creches and Temporary Toile Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-02-2 t for Kpandai, Gushegu, Nanu IDA / 68590 Post Open - National 29,444.00 0.00 2023-07-01 2023-08-26 Program tions nvelope s (Emergency) SP lementation 2 mba South, Saboba Tatale - D -Competitive Sanguli, Zabzugu, Karaga, Mi on and Nanton District Asse mblies. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLGRD-RCU-220729-GO- RFB / Procurement of 500 No Productive Inclusion Progra Single Stage - One E IDA / 68590 Post Request for Bids Open - National 300,000.00 0.00 Signed 2022-07-22 2022-07-08 2022-07-27 2022-07-23 2022-09-07 2022-08-16 2022-10-17 2022-08-12 2022-11-21 2023-02-19 . tablets with Biometric Scan m nvelope ners for LIPW and PI Activitie s GH-MLGRD-RCU-286190-GO- RFB / Supply and Delivery of Labor-Intensive Public Works Single Stage - One E 294 All-Terrain Motorbikes fo IDA / 68590 Post Request for Bids Open - National 420,000.00 0.00 Completed 2022-07-22 2022-07-08 2022-07-27 2022-07-23 2022-09-07 2022-08-16 2022-10-21 2022-08-12 2022-11-25 2023-03-25 Program nvelope r Labour Intensive Public Wor ks (LIPW) and Productive Incl usion (PI) Monitoring Activitie s GH-MLGRD-RCU-220725-GO- RFB / Supply and Delivery of 7No. Photocopiers, 175 0No. Productive Inclusion Progra Single Stage - One E Printers, 175 Scanners, 5 Des IDA / 68590 Post Request for Bids Open - National 885,000.00 0.00 Signed 2022-07-22 2022-07-08 2022-07-27 2022-07-23 2022-09-07 2022-08-16 2022-10-21 2022-08-12 2022-11-25 2023-02-23 m nvelope ktops, 195 No. Laptops, 5 No. Projectors, 6 Digital Cameras and 5 No. Commercial Drone s GH-MLGRD-RCU-220726-GO- Project Management, Coordi RFB / Procurement of 8No. 4 Single Stage - One E IDA / 68590 nation, and Institutional Stre Post Request for Bids Open - National 650,000.00 0.00 Signed 2022-07-22 2022-07-08 2022-07-27 2022-07-23 2022-09-07 2022-08-16 2022-10-21 2022-08-12 2022-11-25 2023-02-23 X4 Vehicles for LIPW and PI M nvelope ngthening onitoring and Supervision GH-MLGRD-RCU-264274-GO- RFQ / Supply and Delivery of Labor-Intensive Public Works Request for Quota Single Stage - One E 400 Bags of Polyclonal Cashe IDA / 68590 Post Limited 70,000.00 0.00 Signed 2023-02-15 2022-03-28 2023-04-12 2023-06-11 Program tions nvelope w Seeds for LIPW activities in the 34 Southern Districts. GH-MLGRD-RCU-272643-GO- RFQ / Supply and Delivery of Labor-Intensive Public Works Request for Quota Single Stage - One E IDA / 68590 Post Limited 50,000.00 0.00 Completed 2023-02-22 2022-03-28 2023-04-19 2023-06-18 4Million Units of Polypots (Pol Program tions nvelope y bags) for Nursery Activities under LIPW GH-MLGRD-RCU-341125-GO- Labor-Intensive Public Works Request for Quota Single Stage - One E RFQ / Supply and Delivery of IDA / 68590 Post Open - National 85,000.00 0.00 Completed 2023-03-01 2023-04-26 2023-10-23 Program tions nvelope 7,000 Wellington Boots for LI PW Activities GH-MLGRD-RCU-341122-GO- RFB / Supply and Delivery of Productive Inclusion Progra Single Stage - One E Pending Impl 1 (One) Server to Host GMIS IDA / 68590 Post Request for Bids Open - National 90,000.00 0.00 2023-03-31 2023-04-05 2023-05-17 2023-06-16 2023-07-21 2024-01-17 m nvelope ementation PRO, E-DASH, PI System Appl ication Software and Data Ba se GH-MLGRD-RCU-365616-GO- RFQ / Procurement of Signag e and Transparency Account ability Boards for CCMI Nurse Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Impl ries and Plantations for Buils IDA / 68590 Post Open - National 7,727.00 0.00 2023-07-02 2023-08-27 2024-02-23 Program tions nvelope ementation a South, Builsa North Municip al, Bongo, Talensi, Nabdam, Bawku West, Bawku Municip al, Binduri, Garu, Pusiga, Te mpane, and other Districts in EURCC GH-MLGRD-RCU-365618-GO- RFQ / Procurement of Tools, Equipment & PPEs for CCMI N Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Impl urseries and Plantations for IDA / 68590 Post Open - National 5,338.00 0.00 2023-07-02 2023-08-27 2024-02-23 Program tions nvelope ementation Mamprugu Moagduri, East M amprusi Municipal, Bunkpuru gu - Nakpanduri and Yunyoo - Nasuan Districts by the NER CC GH-MLGRD-RCU-365573-GO- RFQ / Procurement of Tools, Equipment, and Materials for Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Impl the establishment of coconut IDA / 68590 Post Open - National 31,000.00 0.00 2023-07-02 2023-08-27 2024-02-23 Program tions nvelope ementation plantation, including nursery at Liati Soba and establishme nt of oil palm plantation at V e Deme in Afadzato South Di strict. GH-MLGRD-RCU-365587-GO- RFQ / Procurement of Tools, Equipment & PPEs for CCMI N urseries and Plantations for B Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Impl IDA / 68590 Post Open - National 22,404.00 0.00 2023-07-03 2023-08-28 2024-02-24 uilsa South, Builsa North, Bon Program tions nvelope ementation go, Talensi, Nabdam, Bawku West, Bawku Mun, Pusiga, Te mpani, Garu, Binduri, District s by the UERCC. Page 6 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLGRD-RCU-322569-NC- RFB / Procurement of Service Productive Inclusion Progra Open - Internationa Single Stage - One E Under Imple IDA / 68590 Prior Request for Bids 4,000,000.00 0.00 2022-10-31 2022-10-25 2022-11-05 2022-10-26 2022-12-17 2022-08-19 2023-01-16 2022-11-14 2023-02-20 2025-12-31 Provider for LEAP, LIPW and P m l nvelope mentation I E-Payment Service GH-MLGRD-RCU-220724-NC- RFB / Procurement of Service Productive Inclusion Progra Open - Internationa Single Stage - Two E IDA / 68590 Prior Request for Bids 4,000,000.00 0.00 Canceled 2022-05-16 2022-06-22 2022-05-21 2022-07-14 2022-07-02 2022-08-19 2022-09-14 2022-10-19 2025-12-31 Provider for LEAP, LIPW and P m l nvelope I E-Payment Service CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLGRD-RCU-341523-CS- Project Management, Coordi CQS / Selection of Consultant Consultant Qualifi IDA / 68590 nation, and Institutional Stre Post Open - National 40,000.00 0.00 Under Review 2023-02-28 2023-02-27 2023-03-04 2023-03-29 2023-04-05 2023-04-19 2023-05-30 to undertake Independent Pr cation Selection ngthening ocurement Audit of Project a ctivities for 2022 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLGRD-RCU-363850-CS- CDS / Selection of Consultant Labor-Intensive Public Works Pending Impleme to undertake impact Evaluati IDA / 68590 Prior Direct Selection Direct - National 250,000.00 0.00 2023-06-26 2023-07-28 2023-09-01 2025-09-26 Program ntation on of the Labour-Intensive Pu blic Works Component. Page 7 PROCUREMENT PLAN (Textual Part) Project information: Republic of Trinidad and Tobago: COVID-19 EMERGENCY RESPONSE PROJECT (P173989) Project Implementation agency: MOH – Ministry of Health Date of the Procurement Plan: June 30th, 2020 Period covered by this Procurement Plan: From July 2020 to December 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the national procurement legislation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: The corresponding Procurement Documents must be acceptable to the World Bank. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations and the corresponding Procurement Documents must be acceptable to the World Bank. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: “Not Applicable”; Works: “Not Applicable” Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is “Not Applicable” Other Relevant Procurement Information. Since the Project triggers Paragraph 12 of the IPF Policy, which relates to Projects in Situations of Urgent Need of Assistance or Capacity Constraints, the GoRTT and the Bank have agreed that the MOH would directly engage PAHO/WHO to source all PPEs, pharmaceuticals, medical supplies, equipment and vaccines the Project needs to respond the COVID-19 pandemic, given PAHO/WHO’s rapid mobilization on the ground and expertise in responding emergency situations like the current one. When entering into a contract with PAHO/WHO, the MOH will use a standard form of agreement previously negotiated and approved by the Bank. PROCUREMENT Trinidad and Tobago : Republic of Trinidad and Tobago: COVID-19 EMERGENCY RESPONSE PROJECT PLAN General Information Country: Trinidad and Tobago 2021-05-03 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173989 GPN Date: 2021-05-10 Project Name: Republic of Trinidad and Tobago: COVID-19 EMERGENCY RESPONSE PROJECT Loan / Credit No: IBRD / 91570 Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TT-MOH-232028-GO-RFB / Pr ocurement/supply of COVID- Emergency Response to CO IBRD / 91570 Prior Direct Selection Direct 11,617,613.85 0.00 Signed 2021-05-16 2021-05-20 2021-05-23 2021-06-01 2021-06-27 2022-06-22 19 related PPEs, pharmaceuti VID-19 cals, medical supplies and eq uipments TT-MOH-343910-GO-RFQ / P Project Management and Mo Request for Quota Single Stage - One E IBRD / 91570 Post Limited 18,680.00 0.00 Signed 2023-02-22 2022-12-28 2023-04-19 2023-10-16 urchasing of ICT Equipment f nitoring tions nvelope or the PIU TT-MOH-348518-GO-DIR / Pu Support to COVID-19 Vaccin Direct - Internation Under Revie IBRD / 91570 Prior Direct Selection 7,500,000.00 0.00 2023-03-09 2023-03-14 2023-04-18 2023-10-15 rchasing of COVID-19 Vaccin ation Campaign al w es TT-MOH-348548-GO-DIR / Pu Support to COVID-19 Vaccin Direct - Internation Under Revie IBRD / 91570 Prior Direct Selection 173,432.00 0.00 2023-03-09 2023-03-14 2023-04-18 2023-10-15 rchasing of COVID-19 vaccin ation Campaign al w es TT-MOH-348554-GO-DIR / Th Project Management and Mo e purchasing of SAGE 50 Acc IBRD / 91570 Post Direct Selection Direct - National 4,412.00 0.00 Signed 2023-03-09 2023-03-17 2023-03-14 2023-03-03 2023-04-18 2023-10-15 nitoring ounting Software for the PIU Team NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TT-MOH-365711-CS-LCS / Fi nancial Audit Services for the COVID 19 Emergency Respo Project Management and Mo Least Cost Selecti Under Implement IBRD / 91570 Post Open - National 60,000.00 0.00 2023-06-06 2023-05-25 2023-06-27 2023-08-10 2023-09-07 2023-10-07 2023-11-11 2023-12-16 2024-06-13 nse Project for the periods M nitoring on ation arch 15, 2021 to September 30, 2023, October 1, 2023 to June 30, 2024. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TT-MOH-IC-1 / PIU Project Ma Project Management and Mo Individual Consult IBRD / 91570 Post Limited 39,000.00 0.00 Under Review 2021-03-01 2022-08-08 2021-08-28 2022-02-24 2022-04-14 2023-04-14 nager nitoring ant Selection TT-MOH-IC-3 / PIU Financial Project Management and Mo Individual Consult IBRD / 91570 Post Limited 39,000.00 0.00 Under Review 2021-03-01 2022-08-09 2021-08-28 2022-02-24 2022-04-14 2023-04-14 Management Officer nitoring ant Selection TT-MOH-IC-4 / PIU Environm Project Management and Mo Individual Consult IBRD / 91570 Post Limited 39,000.00 0.00 Under Review 2021-03-01 2022-08-09 2021-08-28 2022-02-24 2022-04-14 2023-04-14 ental and Social Specialist nitoring ant Selection TT-MOH-IC-2 / PIU Procurem Project Management and Mo Individual Consult IBRD / 91570 Post Limited 39,000.00 0.00 Under Review 2021-03-01 2022-10-20 2021-08-28 2022-02-24 2022-04-14 2023-04-14 ent Officer nitoring ant Selection Page 1 Plan de Passation de marchés I. Généralités 1. L'information sur le projet : Pays : Madagascar ; Emprunteur : République de Madagascar ; Nom de projet : Projet Filets Sociaux de Sécurité – Financement Additionnel (P160 544) ; Numéro du Crédit : D1450-MG ; Agence d’exécution du Projet : Unité Programme National de Nutrition Communautaire. 2. Date d’approbation du Plan de passation de marchés par la Banque : - ; Révision : - ; 3. Date de notification du Plan Général de Passation de marchés : - ; 4. Période couverte par le Plan de Passation de marchés : DOUZE (12) mois. II. Biens et Travaux et Services hors consultants 1. Seuil de Revue préalable : Les décisions de passation de marchés sujet aux revues préalables de la Banque comme indiqué dans le paragraphe 3.1 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016) et sur la base de l'évaluation de la capacité de l'agence d’exécution : Seuil de Méthode de Passation de revue à Commentaires marchés priori (USD) Les montants 1 Biens : AOI/AON/UN/ED 2 000 000 estimatifs des marchés prévus 2 Travaux : AOI/AON/ED 10 000 000 sont au-dessous des seuils. Niveau de Services autres que 3 2 000 000 risque : consultants : AOI/AON/UN/ED « SUBSTANTIEL » 2. Pré-qualification (selon les dispositions des paragraphes 6.19 à 6.24 de la Section VI du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016)) : Non Applicable. 3. Procédures proposées pour les composantes CDD (selon le paragraphe. 6.52 et 6.53 de la Section VI du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016)) : Non Applicable 4. Référence (s’il y en a) au Manuel d’exécution du projet / Manuel de Passation de marchés : Manuels en cours de mise à jour 5. Tout autre arrangement spécial en passation de marchés : Non Applicable. 6. Allotissement de fournitures avec méthodes et calendrier : [Enumérer d’abord les allotissements qui nécessitent la revue préalable de la Banque, ensuite les autres allotissements] 1 2 3 4 5 6 7 8 9 Réf. No Description Contrat Approche/Méthod Revue de la Coût Pré- Préféren Date Commentaire e de sélection Banque (à estimatif qualificati ce prévue s priori / à (USD) on nationale d’ouverture posteriori) Oui / Non Oui / Non des soumission s Lot 1 : N°9 : Impression et Achevée multiplication de bulletins LIMITE 01 A.11 COT Post 12 000,00 NON NON 21-juin-18 Lot 2 : N°10 : en périodiques (02 numéros NATIONAL attente semestrielles) Maquette Acquisition outils de LIMITE Ordre de Service 03 A.11 COT Post 10 000,00 NON NON 13-mai-18 communication (Pagnes) NATIONAL signé Acquisition divers Pas encore LIMITE 04 A.17 équipements et mobiliers COT Post 5 000,00 NON NON 14-févr-19 lancée NATIONAL de bureau A programmer Acquisition de 293,2 SELECTION 1 475 246 Nouvelle activité 05 A.13 ED Post NON NON 12-févr-19 tonnes de Plumpy Sup DIRECTE ,46 PTA 2019 Acheminement vers LIMITE Nouvelle activité 06 A.13 Districts de 293,2 tonnes COT Post 77 644,55 NON NON 19-févr-19 NATIONAL PTA 2019 de Plumpy Sup Confection d’outils pour les sites : impression et LIMITE Nouvelle activité A.6.0 COT Post 11 812,50 NON NON 04-juin-19 livraison d’outils de NATIONAL PTA 2019 gestion : Registres Confection de plaques d'indication des sites et A.11.0 Supports de LIMITE Nouvelle activité COT Post 27 514,03 NON NON 04-juin-19 .1 communication : NATIONAL PTA 2019 Impression plaque, livrets et bulletins périodiques 1 2 3 4 5 6 7 8 9 Réf. No Description Contrat Approche/Méthod Revue de la Coût Pré- Préféren Date Commentaire e de sélection Banque (à estimatif qualificati ce prévue s priori / à (USD) on nationale d’ouverture posteriori) Oui / Non Oui / Non des soumission s Confection de Pagnes et A.11.0 T-shirt, Blouses pour LIMITE 17 578,13 Nouvelle activité .2 COT Post NON NON 04-juin-19 intervenants (Reny NATIONAL PTA 2019 mavitrika, …) Acquisition de matériels informatiques adaptés à l'actualisation du SIG et LIMITE Nouvelle activité A.14 COT Post 13 312,50 NON NON 04-juin-19 du développement du NATIONAL PTA 2019 Géoportail des données en ligne III. Sélection de consultants 1. Seuil de Revue Préalable : Décisions de sélection sujet à la revue préalable de la Banque comme indiqué dans le paragraphe 3 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016) : Méthode de sélection Seuil de Commentaires revue à priori (USD) 1. Méthode compétitive (firmes) 1 000 000 Les montants 2. Entente directe (firmes) 1 000 000 estimatifs des 3. Méthode compétitive (Consultant 300 000 contrats prévus individuel) sont au-dessous 4. Entente directe (Consultant 300 000 des seuils. individuel) Niveau de risque : « SUBSTANTIEL » 2. Liste restreinte composée entièrement de consultants nationaux : Selon les dispositions du paragraphe 7.25 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016), la liste restreinte de consultants peut comporter entièrement des consultants nationaux pour les cas suivants : Catégorie de Montant estimatif consultant 1. Firmes Inférieur à USD 300 000 2. Consultants individuels Inférieur à USD 100 000 3. Tout autre arrangement spécial de Sélection de consultants : Non applicable 4. Tâches de consultation avec des méthodes de sélection et calendrier 1 2 3 4 5 6 7 Réf. No Description des missions Approche/Méth Revue de la Coût Date Commentaires ode de Banque (à estimatif prévue de sélection priori / à (USD) soumission posteriori) s des proposition s Consultant en charge de la maintenance Nouvelle activité PTA 01 A.14 ED ED Post 12 000,00 29-avril-19 du système Géoportail 2019 Consultants chargés de saisie des Nouvelle activité PTA 02 A.16 Registres des sites ED ED Post 34 321,33 20-mai-19 2019 Consultant Individuel en charge de Nouvelle activité PTA 03 B.2 l’élaboration de l’ICR INDV ED Post 5 000,00 21-mai-19 2019 IV. Activités de renforcement de capacités de l’Agence d’exécution avec calendrier 1. Dans cette section, les activités de renforcement de capacité acceptées (quelques articles pourraient être des recommandations de CPAR) sont énumérées avec le calendrier No. Résultats Coût Durée Date de Commentaires escomptés / estimatif estimative début Description de l’activité PROCUREMENT Madagascar : Improving Nutrition Outcomes using the Multiphase Programmatic Approach PLAN General Information Country: Madagascar Bank’s Approval Date of the Original Procurement Plan:2017-11-15 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160848 GPN Date: 2020-09-07 Project Name: Improving Nutrition Outcomes using the Multiphase Programmatic Approach Loan / Credit No: IDA / V0970, IDA / D2570 Community Nutrition National Program Unit Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process S Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Comple Description Component Review Type Method Amount (U ount (US$ and Recommendatio Signed Contract o. h cess (Y/N) isk ocument Type tatus n Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes tion S$) ) n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned UPNNC 3 25 DC TRX / Trava ux d'extension du Bureau de Project Management, Capac Request for Quot Single Stage - One 2018-04-2 l'Unité de Coordination de Pr IDA / V0970 ity Building and Operations Post Limited 45,000.00 34,783.92 Completed 2017-11-08 2017-11-20 2017-12-27 2018-03-27 ations Envelope 6 ojet - Ministère de la Santé P Support ublique à Ambohimiandra MG-UPNNC-233827-CW-RFB / Sélection d'entreprise pour Request for Bids - Project Management, Capac les travaux de réhabilitation, Single Stage - One Small Works SPD 2022-04-3 IDA / D2570 ity Building and Operations Post Request for Bids Open - National 450,000.00 0.00 Canceled 2021-08-03 2021-08-08 2021-09-20 2021-10-04 2021-11-01 d'extension et de surélévati Envelope (1 envelope proc 0 Support on d'un bâtiment public pour ess) servir de bureau à l'UPNNC e t l'ONN Request for Bids - MG-UPNNC-254375-CW-RFB Project Management, Capac Single Stage - One Works French Civ 2023-03-0 / Travaux de réhabilitation d IDA / D2570 ity Building and Operations Post Request for Bids Open - National 760,000.00 0.00 Canceled 2022-12-15 2023-02-02 2022-12-22 2023-02-02 2023-01-21 2023-02-17 2023-01-28 2023-02-14 Envelope il Law (French) SP 2 u bâtiment pour bureau de l' Support D ONN/UPNNC GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus n Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UPNNC 2 1 ET 2 2 UNOPS / Acquisition de divers matéri els informatiques, bureautiq Strengthen capacity to man UN Agencies (Dir ues et de communication (2 IDA / V0970 age and deliver the RMCHN Post Direct 272,000.00 316,648.00 Signed 2017-11-10 2017-11-15 2017-12-21 2017-12-27 2018-04-12 2018-03-27 ect) 3 Ordinateurs de bureau ave minimum package c onduleurs, 28 ordinateurs portables, 22 photocopieuse s, 22 vidéoprojecteurs et 92 tablettes UPNNC 2 1 ET 2 3 AON / Ac quisition kits de communicat Strengthen capacity to man Single Stage - One ion pour le Ministère de la S IDA / V0970 age and deliver the RMCHN Post Request for Bids Open - National 166,000.00 92,426.63 Completed 2017-11-12 2018-02-07 2017-11-17 2017-12-15 2018-03-07 2018-01-12 2018-05-22 2018-02-09 2018-06-13 2018-04-10 2018-09-05 Envelope anté Publique : Kit vidéocon minimum package férence et kit central de com munication Strengthen capacity to man UPNNC 3 1 DC / Multiplicati Request for Quot Single Stage - One IDA / V0970 age and deliver the RMCHN Post Limited 86,000.00 2,961.47 Signed 2017-11-05 2018-01-18 2017-12-24 2018-03-23 2018-02-22 2018-05-18 on et diffusion de PNAN III ations Envelope minimum package UPNNC 3 2 AON / Acquisitio Strengthen capacity to man Single Stage - One n supports de diffusion de d IDA / V0970 age and deliver the RMCHN Post Request for Bids Open - National 245,000.00 63,185.88 Signed 2017-11-03 2018-01-27 2017-11-08 2017-12-06 2018-02-27 2018-01-03 2018-03-28 2018-01-31 2018-05-02 2018-04-01 Envelope ocument cadre minimum package PARN UPNNC 1 6 UNICEF / A Strengthen capacity to man cquisition de matériels et éq UN Agencies (Dir IDA / D2570 age and deliver the RMCHN Post Direct 900,000.00 620,630.00 Signed 2018-05-14 2018-06-07 2018-05-28 2018-06-07 2018-07-02 2018-06-20 2018-08-31 uipements pour la mise en p ect) minimum package lace des sites communautair es PARN UPNNC 16 27 UNOPS1 Scale up coverage and utiliz UN Agencies (Dir / Acquisition de motos pour l IDA / D2570 ation of the RMCHN minimu Post Direct 1,200,000.00 1,135,115.00 Signed 2018-05-07 2018-06-06 2018-05-21 2018-06-06 2018-07-02 2018-06-26 2018-09-30 ect) es Animateurs et ES auprès m package UNOPS PARN UPNNC 27 31 UNOPS2 Strengthen capacity to man / Acquisition de véhicules de UN Agencies (Dir IDA / D2570 age and deliver the RMCHN Post Direct 275,000.00 249,715.01 Signed 2018-05-07 2018-06-06 2018-05-21 2018-06-06 2018-07-02 2018-06-26 2018-09-30 supervision pour les ORN et ect) minimum package l'UPNNC auprès de l'UNOPS PARN UPNNC 24 27 31 UNO Scale up coverage and utiliz PS1 / Acquisition de matériel UN Agencies (Dir IDA / D2570 ation of the RMCHN minimu Post Direct 300,000.00 295,744.00 Signed 2018-05-07 2018-06-06 2018-05-21 2018-06-06 2018-07-02 2018-08-14 2018-09-30 s informatiques, bureautique ect) m package s et de communication aupr ès UNOPS PARN UPNNC 16 AON01 / Ac Strengthen capacity to man Single Stage - One quisition de radio destinés a IDA / D2570 age and deliver the RMCHN Post Request for Bids Open - National 100,000.00 63,982.54 Signed 2018-05-01 2018-08-25 2018-05-15 2018-06-12 2018-10-10 2018-06-26 2019-01-22 2018-07-17 2019-03-23 2018-09-15 2019-06-18 Envelope ux sites communautaires minimum package PARN UPNNC 1 6 SUPPORT Strengthen capacity to man COM / Confection supports d Single Stage - One IDA / D2570 age and deliver the RMCHN Post Request for Bids Open - National 200,000.00 153,223.74 Signed 2018-08-06 2018-08-25 2018-08-20 2018-09-17 2018-09-26 2018-10-01 2019-02-13 2018-10-22 2019-03-22 2018-12-21 e communication répartis en Envelope minimum package cinq (05) lots (Banderoles, T ee-shirts, Pagnes, ...) PARN UPNNC 1 6 SUPPORT COM2 / Impression et multip Strengthen capacity to man Request for Quot Single Stage - One lication divers supports de c IDA / D2570 age and deliver the RMCHN Post Limited 65,000.00 5,971.68 Signed 2018-09-02 2019-06-25 2018-10-21 2019-10-16 2018-12-20 ations Envelope ommunication répartis en tr minimum package ois (03) lots (Affiches, Guide s, Bulletins périodiques) PARN UPNNC 2 4 OUTILS DE Scale up coverage and utiliz GESTION / Impression et mul Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Limited 70,000.00 26,344.31 Signed 2018-05-15 2019-01-07 2018-07-03 2019-01-31 2018-07-31 tiplication des outils de gesti ations Envelope m package on répartis en deux (02) lots (Registres) PARN UPNNC 3 1 MOB BURE Project Management, Capac Request for Quot Single Stage - One IDA / D2570 Post Limited 6,000.00 5,149.31 Signed 2018-05-27 2019-11-05 2018-07-15 2019-11-21 2018-08-14 AU / Acquisition de mobiliers ity Building and Operations ations Envelope de bureau Support PARN UPNNC 1 6 SUPPORT Strengthen capacity to man Request for Quot Single Stage - One COM3 / Confection et multipl IDA / D2570 age and deliver the RMCHN Post Limited 35,000.00 0.00 Canceled 2018-08-21 2018-10-16 2018-12-15 ations Envelope ication calendriers 2019 minimum package PARN UPNNC 1 6 BALANCES Strengthen capacity to man / Acquisition de balances pè Request for Quot Single Stage - One IDA / D2570 age and deliver the RMCHN Post Limited 100,000.00 0.00 Canceled 2018-05-22 2018-07-17 2018-09-15 se-personne destinées aux s ations Envelope minimum package ites communautaires MG-UPNNC-93276-GO-DIR / Scale up coverage and utiliz UN Agencies (Dir Acquisition de matériels des IDA / D2570 ation of the RMCHN minimu Post Direct 450,000.00 350,213.45 Signed 2018-12-29 2018-05-28 2018-12-30 2018-11-27 2019-01-09 2018-12-11 2019-07-08 ect) tinés aux sites (Pèse-person m package nes) MG-UPNNC-93277-GO-RFQ / Scale up coverage and utiliz Request for Quot Single Stage - One Acquisition de piles recharge IDA / D2570 ation of the RMCHN minimu Post Limited 60,000.00 0.00 Canceled 2019-01-17 2019-03-14 2019-05-28 ations Envelope ables pour les Pèse-personn m package e PARN UPNNC 11 LNS / Acqui Strengthen capacity to man sition de suppléments alime IDA / D2570 age and deliver the RMCHN Prior Direct Selection Direct 1,188,074.00 1,286,399.27 Signed 2019-01-10 2019-11-01 2019-01-17 2019-11-06 2019-02-14 2019-12-28 2020-02-09 ntaires LNS riches en protéin minimum package es et lipides pour les enfants 6 à 18 mois Page 1 PARN UPNNC 13 PLUMPY / A Strengthen capacity to man cquisition d'aliments thérap IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 935,299.00 794,644.66 Signed 2019-01-10 2019-01-29 2019-02-07 2019-01-28 2019-03-21 2019-02-14 2020-03-15 eutiques Plumpy Sup pour tr minimum package aiter le cas de MAM MG-UPNNC-1 1 06 02-OUTIL S COMM / Production et livra ison des Outils de communic Scale up coverage and utiliz Single Stage - One ation Institutionnelle repartis IDA / D2570 ation of the RMCHN minimu Post Request for Bids Open - National 160,000.00 0.00 Canceled 2019-07-01 2019-07-06 2019-08-05 2019-09-04 2019-09-25 2019-12-24 Envelope en 5 lots (Stylo flash, Stylo m package personnalisé- Affiche offre d e services, Blouse sans man che, Tee-shirts FAFY) MG-UPNNC-1 1 06 02-OUTIL S DE COMMUNICATI / Produc Scale up coverage and utiliz Request for Quot Single Stage - One tion et livraison des outils de IDA / D2570 ation of the RMCHN minimu Post Limited 10,000.00 2,232.12 Signed 2019-06-05 2019-02-27 2019-06-29 2019-05-02 2019-07-14 ations Envelope communication institutionne m package lle (Agenda et blocs note) MG-UPNNC-110602-OUTILS Scale up coverage and utiliz Request for Quot Single Stage - One COMM / Confection des plaq IDA / D2570 ation of the RMCHN minimu Post Limited 87,000.00 32,636.06 Signed 2019-06-13 2019-06-21 2019-07-07 2019-06-25 2019-09-05 ations Envelope ues pour les sites m package MG-UPNNC-2 1 01 04-DOCU MENT DE FORMATION / Trav Strengthen capacity to man aux d'impression des docum Request for Quot Single Stage - One IDA / D2570 age and deliver the RMCHN Post Limited 16,000.00 15,438.71 Signed 2019-06-06 2019-03-04 2019-06-28 2019-03-05 2019-07-08 ents de formation AC (docu ations Envelope minimum package ment formateur, document participant et courbes de cro issance) MG-UPNNC-154719-GO-DIR / Acquérir des matériels et é quipements informatiques, i mprimante multifonction, ta Strengthen capacity to man UN Agencies (Dir blettes pour les Animateurs IDA / D2570 age and deliver the RMCHN Post Direct 375,000.00 374,327.00 Signed 2020-02-24 2019-10-25 2020-03-02 2019-12-16 2020-03-23 2019-12-28 2020-09-19 ect) de la Région Bongolava et p minimum package our la communication institu tionnelle, matériels techniq ues pour la communication, matériels de communication MG-UPNNC-154727-GO-DIR Strengthen capacity to man / Acquérir un véhicule pour UN Agencies (Dir IDA / D2570 age and deliver the RMCHN Post Direct 177,626.00 374,327.00 Signed 2020-02-10 2019-10-25 2020-02-17 2019-10-16 2020-03-09 2019-12-28 2020-09-05 ORN Bongolava et des moto ect) minimum package s pour Animateurs et ES de la Région Bongolava MG-UPNNC-154750-GO-DIR Scale up coverage and utiliz / Acquérir des matériels ant UN Agencies (Dir IDA / D2570 ation of the RMCHN minimu Post 164,926.00 83,634.60 Signed 2020-02-24 2019-09-11 2020-03-02 2019-11-11 2020-03-09 2019-11-12 2020-09-05 hropométriques pour les site ect) m package s de la région Bongolava MG-UPNNC-154769-GO-RFB Strengthen capacity to man / Impression et multiplicatio Single Stage - One IDA / D2570 age and deliver the RMCHN Post Request for Bids Open - National 135,000.00 27,978.36 Completed 2020-02-24 2020-01-14 2020-03-02 2020-04-01 2020-02-06 2020-04-15 2020-02-14 2020-05-02 2020-04-23 2020-07-01 2020-06-06 n de des feuillets d'animatio Envelope minimum package n et des bâches alimentaires MG-UPNNC-156503-GO-RFP Strengthen capacity to man / IMPRESSION ET LIVRAISON Request for Propo Single Stage - Two IDA / D2570 age and deliver the RMCHN Post Limited 15,400.00 0.00 Canceled 2020-02-24 2020-03-02 2020-03-17 2020-03-31 2020-04-17 2020-10-14 DE DEPLIANTS GUIDE DE ME sals Envelope minimum package SSAGE ET AFFICHES REPART IS EN DEUX (02) LOTS MG-UPNNC-152791-GO-RFQ Strengthen capacity to man Request for Quot Single Stage - One / Acquérir des registres pour IDA / D2570 age and deliver the RMCHN Post Limited 4,297.00 0.00 Canceled 2020-03-02 2020-04-06 2020-05-19 ations Envelope les sites de la Région de Bon minimum package golava MG-UPNNC-174129-GO-DIR / Acquisition des aliments th Scale up coverage and utiliz érapeutiques Plumpy sup po IDA / D2570 ation of the RMCHN minimu Prior Direct Selection Direct 5,543,428.00 3,925,665.69 Signed 2020-08-03 2020-10-15 2020-08-10 2020-11-05 2020-10-07 2020-12-16 2021-04-05 ur les 7 régions ( Itasy, Vaki m package nakaratra, Amoron'i Mania, Haute Matsiatra, Bongolava, Anlamanga, Alaotra Mangor o) MG-UPNNC-173972-GO-DIR Scale up coverage and utiliz / Acquisition des supplément IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 593,492.00 1,286,894.53 Signed 2020-08-03 2019-11-01 2020-08-17 2019-11-18 2020-10-14 2019-12-27 2021-04-12 s alimentaires LNS riches en m package protéeines et lipides pour la région Itasy MG-UPNNC-181784-GO-RFB Scale up coverage and utiliz Single Stage - One / Fourniture et livraison de 2 IDA / D2570 ation of the RMCHN minimu Post Request for Bids Open - National 73,000.00 59,981.37 Completed 2020-07-27 2020-06-24 2020-08-03 2020-09-02 2020-08-14 2020-09-17 2020-09-04 2020-10-04 2020-11-04 2020-12-03 2021-01-26 Envelope 440 Radios solaires pour les m package sites. MG-UPNNC-186046-GO-UN / Acquisition des matériels inf Strengthen capacity to man UN Agencies (Dir ormatiques pour les régions IDA / D2570 age and deliver the RMCHN Post Direct 24,500.00 0.00 Canceled 2020-09-01 2020-08-03 2020-09-08 2020-11-21 2022-05-15 ect) Analamanga et Alaotra Man minimum package goro (Lap top, Imprimante e t vidéo projecteur) MG-UPNNC-199566-GO-UN / Acquisition des mobiliers et Scale up coverage and utiliz UN Agencies (Dir des matériels pour sites : 10 IDA / D2570 ation of the RMCHN minimu Prior Direct 2,500,000.00 0.00 Canceled 2020-11-16 2020-12-16 2021-02-14 2021-05-15 ect) 622 Tables, 21 244 Chaises, m package kits de matériels de mesures anthropométriques MG-UPNNC-174121-GO-UN / Scale up coverage and utiliz Acquisition de 2 139 armoire UN Agencies (Dir IDA / D2570 ation of the RMCHN minimu Post Direct 400,000.00 0.00 Canceled 2020-07-27 2020-08-03 2020-08-03 2020-09-19 2022-03-13 s métalliques pour les région ect) m package s Analamanga et Alaotra Ma ngoro MG-UPNNC-173960-GO-UN / Strengthen capacity to man Acquisition de 366 tablettes UN Agencies (Dir IDA / D2570 age and deliver the RMCHN Post Direct 172,695.00 0.00 Canceled 2020-07-27 2020-08-03 2020-08-03 2020-08-06 2020-10-16 2022-04-09 pour les animateurs des régi ect) minimum package ons Analamange et Alaotra Mangoro MG-UPNNC-173975-GO-UN / Scale up coverage and utiliz Acquisition des Motos pour l UN Agencies (Dir IDA / D2570 ation of the RMCHN minimu Post Direct 1,064,452.00 0.00 Canceled 2020-07-27 2020-08-03 2020-08-03 2019-10-14 2020-09-14 2021-03-13 es régions Analamanga et Al ect) m package aotra Mangoro (Animateurs et ES) MG-UPNNC-174122-GO-UN / Strengthen capacity to man Acquisition de 02 véhicules UN Agencies (Dir IDA / D2570 age and deliver the RMCHN Post Direct 92,000.00 0.00 Canceled 2020-07-27 2020-08-03 2020-08-03 2020-08-06 2020-10-16 2022-04-09 4x4 tout terrain pour les régi ect) minimum package ons Analama,ga et Alaotra M angoro MG-UPNNC-154740-GO-RFQ Strengthen capacity to man Request for Quot Single Stage - One / Imprimer des documents d IDA / D2570 age and deliver the RMCHN Post Limited 345,287.00 56,046.16 Signed 2020-12-28 2020-09-25 2021-01-25 2021-02-04 2021-02-24 ations Envelope e formation PCIME minimum package MG-UPNNC-216420-GO-RFQ Project Management, Capac Request for Quot Single Stage - One / Acquisition de 05 Ordinate IDA / D2570 ity Building and Operations Post Limited 20,119.00 23,286.27 Signed 2021-03-08 2021-08-12 2021-04-12 2021-11-03 2021-05-12 2021-12-14 ations Envelope urs portables pour l'Entité d Support e Coordination MG-UPNNC-216421-GO-RFQ Project Management, Capac / Acquisition des consomptib Request for Quot Single Stage - One Pending Impl IDA / D2570 ity Building and Operations Post Limited 7,400.00 0.00 2021-03-01 2021-04-05 2021-05-05 les informatiques et access ations Envelope ementation Support oires pour l'Entité de Coordi nation MG-UPNNC-173973-GO-UN / Scale up coverage and utiliz Acquisition des mesures ant UN Agencies (Dir IDA / D2570 ation of the RMCHN minimu Prior Direct 3,505,727.00 0.00 Canceled 2020-07-27 2021-02-04 2020-08-03 2021-02-19 2020-08-25 2021-02-21 hropométriques pour les rég ect) m package ions Alaotra Mangoro et Anal amanga MG-UPNNC-154774-GO-DIR Scale up coverage and utiliz UN Agencies (Dir IDA / D2570 Post Direct 844,000.00 0.00 Canceled 2020-12-28 2021-01-04 2021-01-25 2021-07-24 / Acquérir des mobiliers pour ation of the RMCHN minimu ect) les sites m package Page 2 MG-UPNNC-181777-GO-UN / Scale up coverage and utiliz Acquisition des mobiliers po UN Agencies (Dir IDA / D2570 ation of the RMCHN minimu Post Direct 370,000.00 0.00 Canceled 2021-01-25 2021-02-01 2021-02-22 2021-08-21 ur site: ect) m package 10 622 Tables 21 244 Chaises MG-UPNNC-222708-GO-UN / Scale up coverage and utiliz Acquisition de 1 584 Armoir UN Agencies (Dir IDA / D2570 ation of the RMCHN minimu Post Direct 380,000.00 0.00 Canceled 2021-04-26 2021-06-15 2021-05-10 2022-12-02 2021-05-31 2021-11-27 es métalliques pour Analam ect) m package anga, Alaotra Mangoro, Bon golava MG-UPNNC-222198-GO-UN / Acquisition des matériels de Scale up coverage and utiliz UN Agencies (Dir mesures anthropométriques IDA / D2570 ation of the RMCHN minimu Post Direct 360,000.00 338,142.33 Signed 2021-03-22 2021-01-04 2021-04-05 2021-01-06 2021-05-10 2021-03-27 2021-11-06 ect) pour les régions Analamang m package a et Alaotra Mangoro MG-UPNNC-203413-GO-UN / Acquisition des matériels inf ormatiques (02 ordinateurs Scale up coverage and utiliz UN Agencies (Dir portables, 02 imprimantes IDA / D2570 ation of the RMCHN minimu Post Direct 145,000.00 0.00 Canceled 2021-01-01 2021-01-31 2021-04-03 2021-08-06 ect) multifonction, 02 vidéos proj m package ecteurs, 366 tablettes) pour les régions Analamanga et A laotra Mangoro MG-UPNNC-202074-GO-UN / Strengthen capacity to man UN Agencies (Dir Acquisition de matériels roul IDA / D2570 age and deliver the RMCHN Post Direct 1,156,450.00 0.00 Canceled 2021-01-01 2021-01-15 2021-02-26 2021-05-28 ect) ants : véhicules tout terrain minimum package et motos MG-UPNNC-222712-GO-UN / Acquisition de mobiliers pou Scale up coverage and utiliz UN Agencies (Dir r les sites des 7 régions: IDA / D2570 ation of the RMCHN minimu Post Direct 891,000.00 0.00 Canceled 2021-04-19 2021-05-03 2021-05-24 2021-11-20 ect) - 8 524 Tables m package - 17 048 Chaises MG-UPNNC-248082-GO-RFB Strengthen capacity to man Single Stage - One / Acquisition de 283 tablette IDA / D2570 age and deliver the RMCHN Post Request for Bids Open - National 302,286.00 53,501.86 Signed 2021-10-07 2021-09-24 2021-10-14 2021-10-12 2021-11-13 2021-10-28 2021-11-20 2021-11-25 2021-12-07 2021-12-22 2022-02-05 Envelope s et accessoires minimum package MG-UPNNC-254374-GO-RFB Strengthen capacity to man Single Stage - One / Acquisition de 04 véhicules IDA / D2570 age and deliver the RMCHN Post Request for Bids Limited 195,274.00 129,701.56 Signed 2021-09-13 2021-09-24 2021-11-09 2021-09-24 2021-11-24 2021-10-27 2021-12-01 2021-11-05 2021-12-15 2022-04-29 2022-06-13 Envelope 4x4 station wagon minimum package MG-UPNNC-254371-GO-RFB Scale up coverage and utiliz Single Stage - One / Acquisition de 196 motos p IDA / D2570 ation of the RMCHN minimu Post Request for Bids Open - National 498,500.00 344,070.16 Signed 2021-10-15 2021-09-24 2021-10-22 2021-10-12 2021-11-21 2021-10-27 2021-11-28 2021-11-25 2021-12-15 2021-12-31 2022-02-13 Envelope our les animateurs et emplo m package yés de suivi MG-UPNNC-256591-GO-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Fourniture et livraison de g IDA / D2570 ation of the RMCHN minimu Post Open - National 52,000.00 11,217.02 Completed 2021-12-08 2021-10-25 2022-01-08 2021-12-30 2022-02-07 2022-02-15 ations Envelope oodies _coffret article m package MG-UPNNC-252116-GO-RFQ Strengthen capacity to man Request for Quot Single Stage - One Under Imple / Acquisition de matériels inf IDA / D2570 age and deliver the RMCHN Post Open - National 60,532.00 0.00 2021-11-15 2021-10-24 2021-12-31 2022-03-01 ations Envelope mentation ormatiques minimum package MG-UPNNC-241657-GO-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Acquisition de 43 000 boîte IDA / D2570 ation of the RMCHN minimu Post Open - National 43,106.00 23,845.82 Completed 2021-11-19 2021-10-25 2021-12-26 2021-12-31 2022-02-24 2022-01-21 ations Envelope s plastiques m package MG-UPNNC-254369-GO-RFB Scale up coverage and utiliz Single Stage - One / Acquisition de 6 000 table IDA / D2570 ation of the RMCHN minimu Post Request for Bids Open - National 492,000.00 0.00 Canceled 2021-10-26 2021-10-08 2021-11-02 2021-10-12 2021-12-02 2021-12-09 2022-01-09 2022-04-09 Envelope s pour les 7 régions répartie m package en 07lots MG-UPNNC-254361-GO-RFB Scale up coverage and utiliz Single Stage - One / Acquisition de 12 000 chais IDA / D2570 ation of the RMCHN minimu Post Request for Bids Open - National 372,000.00 0.00 Canceled 2021-10-26 2021-10-08 2021-11-02 2021-12-02 2021-12-09 2021-12-23 2022-03-23 Envelope es pour les 7 régions réparti m package e en 07 lots PARN UPNNC 3 1 KIT SONO Project Management, Capac Request for Quot Single Stage - One IDA / D2570 Post Limited 5,000.00 0.00 Canceled 2021-02-08 2021-03-29 2021-05-28 / Acquisition d'un kit de sono ity Building and Operations ations Envelope risation Support MG-UPNNC-283396-GO-RFB Strengthen capacity to man Single Stage - One / Acquisition de 283 tablette IDA / D2570 age and deliver the RMCHN Post Request for Bids Open - National 302,286.00 154,879.23 Signed 2022-04-01 2022-03-28 2022-04-03 2022-04-04 2022-05-03 2022-05-04 2022-05-17 2022-06-10 2022-06-07 2022-07-29 2022-12-04 Envelope s et accessoires. minimum package MG-UPNNC-286345-GO-RFQ / Fourniture et livraison des équipements informatiques Project Management, Capac Request for Quot Single Stage - One Under Imple répartis en 02 lots: IDA / D2570 ity Building and Operations Post Open - National 19,000.00 0.00 2022-04-27 2022-06-10 2022-08-09 ations Envelope mentation - lot 1: 2 Imprimantes multif Support onction - lot 2: 2 Onduleurs MG-UPNNC-303535-GO-RFB Scale up coverage and utiliz Single Stage - One IDA / D2570 Post Request for Bids Open - National 5,768.00 0.00 Canceled 2022-07-15 2022-08-19 2022-07-20 2022-08-31 2022-09-20 2022-09-30 2022-11-04 2023-02-10 / Acquisition de Balance Pès ation of the RMCHN minimu Envelope e-personne m package MG-UPNNC-258111-GO-RFQ Scale up coverage and utiliz Request for Quot IDA / D2570 Post 1,000.00 0.00 Canceled 2021-11-29 2022-01-17 2022-02-07 / Confection et livraison de 1 ation of the RMCHN minimu ations 00 Gilets. m package MG-UPNNC-310835-GO-RFQ Project Management, Capac / Fourniture et livraison d'éq Request for Quot Single Stage - One Under Imple IDA / D2570 ity Building and Operations Post Open - National 30,000.00 0.00 2022-09-12 2022-11-07 2023-02-15 uipements informatiques et ations Envelope mentation Support accessoires répartie en quat re lots PARN UPNNC 16 AON02 / Ac Strengthen capacity to man Single Stage - One quisition de kits pour démon IDA / D2570 age and deliver the RMCHN Post Request for Bids Open - National 300,000.00 0.00 Canceled 2021-01-25 2021-02-08 2021-03-08 2021-03-22 2021-04-19 2021-06-03 Envelope stration culinaire minimum package MG-UPNNC-283296-GO-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Acquisition de 210 Clés US IDA / D2570 ation of the RMCHN minimu Post Open - National 4,700.00 0.00 Canceled 2022-04-03 2022-05-17 2022-07-01 ations Envelope B et gravage. m package MG-UPNNC-330791-GO-DIR Scale up coverage and utiliz / Fourniture et livraison de s Pending Impl IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct - National 700,727.00 0.00 2022-12-21 2023-01-10 2023-02-28 2023-07-18 upplément nutritif à base de ementation m package lipide "Lipid Nutrient Supple ment - LNS" MG-UPNNC-357336-GO-RFQ Project Management, Capac / Acquisition de Vidéo projec Request for Quot Single Stage - One Under Imple IDA / D2570 ity Building and Operations Post Open - National 20,000.00 0.00 2023-05-03 2023-05-30 2023-06-28 2023-07-26 teur, Imprimantes et Ondule ations Envelope mentation Support urs répartie en 3 lots MG-UPNNC-357585-GO-RFQ Project Management, Capac Request for Quot Single Stage - One Under Imple IDA / D2570 Post Open - National 82,000.00 0.00 2023-05-03 2023-05-30 2023-06-28 2023-07-26 / Acquisition d'ordinateurs p ity Building and Operations ations Envelope mentation ortables Support MG-UPNNC-357337-GO-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One Under Imple / Fourniture et livraison de d IDA / D2570 ation of the RMCHN minimu Post Open - National 90,000.00 0.00 2023-05-03 2023-05-30 2023-06-28 2023-07-26 ations Envelope mentation eux véhicules Mini-bus m package MG-UPNNC-283292-GO-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Fourniture et livraison de 0 IDA / D2570 ation of the RMCHN minimu Post Open - National 4,000.00 0.00 Canceled 2022-06-15 2022-07-25 2022-10-23 ations Envelope 8 appareils photos m package MG-UPNNC-315400-GO-RFQ Project Management, Capac Request for Quot Single Stage - One IDA / D2570 Post Open - National 100,000.00 0.00 Canceled 2022-10-02 2022-10-14 2022-11-27 2023-02-10 / Acquisition de 65 Moto-Cro ity Building and Operations ations Envelope ss Support NON CONSULTING SERVICES Page 3 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus n Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-UPNNC-181754-NC-RFB / Confection, impression et li vraison des outils de commu nications: lot 1:Tee-shirts, Strengthen capacity to man Single Stage - One lot 2: Casquettes IDA / D2570 age and deliver the RMCHN Post Request for Bids Open - National 205,736.00 91,092.95 Signed 2020-08-03 2020-06-24 2020-08-10 2020-09-09 2020-08-14 2020-09-23 2020-09-04 2020-10-24 2020-10-16 2020-12-28 2021-12-11 Envelope lot 3: Banderoles minimum package lot 4: Pagnes lot 5: Polos lot 6: Chapeaux Bob lot 7:Sacs à dos lot 8: Masques caches bouch es MG-UPNNC-184858-NC-RFB / Impression et livraison des Strengthen capacity to man Single Stage - One registres SPC et PECMAM po IDA / D2570 age and deliver the RMCHN Post Request for Bids Open - National 400,000.00 26,211.11 Signed 2020-08-03 2020-05-18 2020-08-10 2020-09-09 2020-06-05 2020-09-16 2020-06-29 2020-10-03 2020-07-23 2021-04-01 Envelope ur les 7 régions (Enimbolana minimum package voalohany et Enimbolana Fa haroa) MG-UPNNC-186044-NC-RFB / Travaux d'impression repar tis en 4 lots: Scale up coverage and utiliz lot 1: Agenda 2021 Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Request for Bids Open - National 35,200.00 33,759.77 Signed 2020-09-01 2020-06-23 2020-09-08 2020-10-08 2020-08-14 2020-10-22 2020-09-04 2020-11-08 2021-03-16 2020-12-23 2021-12-15 lot 2: Calendriers muraux Envelope m package lot 3: Calendriers chevalets lot 4: Bulletins périodiques N°15 et N°16 MG-UPNNC-186002-NC-RFQ Scale up coverage and utiliz / Impression et livraison de d Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Open - National 15,400.00 15,715.12 Completed 2020-09-08 2020-10-06 2020-03-19 2020-11-05 2020-05-08 épliants guide de message e ations Envelope m package t affiches répartis en 2 lots MG-UPNNC-203393-NC-RFQ Project Management, Capac Request for Quot Single Stage - One / Déménagement de l'UPNN IDA / D2570 ity Building and Operations Post Limited 30,000.00 2,909.87 Signed 2020-11-13 2020-08-04 2020-12-18 2020-09-24 2021-12-18 ations Envelope C, Prospection d'un nouveau Support local MG-UPNNC-189838-NC-RFP Project Management, Capac Request for Propo Single Stage - Two / Déménagement de l' UPNN IDA / D2570 ity Building and Operations Prior Limited 30,000.00 0.00 Canceled 2020-08-24 2020-08-25 2020-09-09 2020-09-15 2021-09-15 sals Envelope C. Prospection d'un nouveau Support local MG-UPNNC-154757-NC-RFQ Scale up coverage and utiliz / Transport vers districts (LN Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Limited 90,156.00 568.79 Signed 2021-01-25 2021-06-15 2021-03-01 2021-06-23 2021-03-31 S/Plumpy/Matériels/Supports ations Envelope m package vers la région Bongolava MG-UPNNC-216417-NC-RFQ / lot 1: Acheminement de pl umpy sup pours les 06 régio ns lot 2: Acheminement de 2 4 Scale up coverage and utiliz Request for Quot Single Stage - One 40 Radios solaires pour Anal IDA / D2570 ation of the RMCHN minimu Post Limited 100,000.00 1,116.76 Completed 2021-03-01 2021-01-21 2021-03-26 2021-02-05 2021-04-09 2021-04-06 ations Envelope amanga et Alaotra Mangoro m package lot 3: Acheminement de 2 6 78 Armoires métalliques pou r les 05 régions lot 4: Acheminement des out ils de communication MG-UPNNC-221886-NC-RFQ / Confection et livraison des Scale up coverage and utiliz outils de communication rép Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Limited 11,000.00 12,154.39 Completed 2021-04-06 2021-07-17 2021-05-11 2021-09-22 2021-06-10 2021-10-05 arties en 03 lots: ations Envelope m package Lot 1: 86 Roll up Lot 2: 36 Oriflammes Lot 3: 04 Fanions MG-UPNNC-221890-NC-RFB / Confection et livraison des outils de communications ré partis en 04 lots: Scale up coverage and utiliz Lot 1: 1 114 Banderoles Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Request for Bids Open - National 65,800.00 41,399.77 Completed 2021-03-29 2021-03-01 2021-04-05 2021-05-20 2021-05-05 2021-04-12 2021-05-19 2021-06-15 2021-06-05 2021-08-05 2021-07-20 2021-11-26 Lot 2: 2 200 Blouses pour le Envelope m package s AC Lot 3: 2 200 Chapeaux bob p our les AC Lot 4: 1 400 Drapeaux pour l es sites communautaires Lot 5: 4 000 Tee shirts MG-UPNNC-223751-NC-RFB / Acquisition de visuel en co mmunication réparties en 0 5 lots: Lot 1: Confection 1 385 Plaq Scale up coverage and utiliz Single Stage - One ues pour sites IDA / D2570 ation of the RMCHN minimu Post Request for Bids Open - National 94,000.00 51,853.17 Completed 2021-03-15 2021-03-15 2021-03-22 2021-04-21 2021-04-19 2021-05-05 2021-06-21 2021-05-22 2021-07-16 2021-07-01 2021-08-28 Envelope Lot 2: Confection 10 Présen m package toirs de tables Lot 3: Impression 11 000 Dé pliants Lot 4: Impression 1 100 Feui llets Lot 5: Production 1 100 Bâch MG-UPNNC-240942-NC-RFQ es alim Scale up coverage and utiliz / Travaux d'impression et liv Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Open - National 46,500.00 20,808.83 Completed 2021-06-30 2021-08-06 2021-08-26 2021-09-07 2021-09-17 raison de Registres SPC dest ations Envelope m package inés aux sites communautair es MG-UPNNC-241663-NC-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Production de 6 500 Bulleti IDA / D2570 ation of the RMCHN minimu Post Limited 3,143.00 1,348.84 Completed 2021-07-14 2021-07-08 2021-08-06 2021-08-05 2021-08-21 2021-08-18 ations Envelope ns périodiques N°17 m package MG-UPNNC-242513-NC-RFQ / Production et livraison des outils de communication rep arties en 5 lots: Scale up coverage and utiliz - lot 1: Calendriers muraux 2 Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Open - National 29,000.00 21,690.57 Completed 2021-10-05 2021-10-05 2021-11-07 2021-12-11 2022-01-06 2022-04-07 022 ations Envelope m package - lot 2: Calendriers chevalets 2022 - lot 3: Agenda modèle N°01 - lot 4: Kaliana N°18 - lot 5: Kaliana N°19 - lot 6: Production de 20 100 MG-UPNNC-248144-NC-RFQ stickers au / Acquisition de supports de Scale up coverage and utiliz communication pour LNS _ I Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Open - National 69,111.00 0.00 Signed 2021-11-01 2022-02-08 2021-12-17 2022-01-16 mpression Affiche et guide ations Envelope m package Acquisition de supports de c ommunication imprimés MG-UPNNC-254378-NC-RFQ Scale up coverage and utiliz / Acheminement des matéri Request for Quot Single Stage - One Pending Impl IDA / D2570 ation of the RMCHN minimu Post Open - National 23,394.00 0.00 2021-11-22 2022-01-07 2022-02-06 els anthropométriques et su ations Envelope ementation m package pports de communication MG-UPNNC-254377-NC-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Acheminement de 326 ton IDA / D2570 ation of the RMCHN minimu Post Open - National 43,329.00 568.61 Completed 2021-11-29 2022-01-14 2021-06-23 2022-01-29 2021-06-30 ations Envelope nes de LNS au niveaux distri m package cts MG-UPNNC-254376-NC-RFQ Scale up coverage and utiliz / Acheminement des aliment Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Open - National 98,500.00 7,579.36 Signed 2021-11-08 2021-10-20 2022-01-06 2021-07-27 2022-01-21 s thérapeutiques plumpy su ations Envelope m package p aux districts (ONG) MG-UPNNC-257082-NC-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Impression et pose affichag IDA / D2570 ation of the RMCHN minimu Post Open - National 1,700.00 444.30 Signed 2021-11-16 2022-03-07 2021-12-26 2022-06-30 2022-01-25 ations Envelope e sur panneau publicitaire 4 m package m x 3m Page 4 MG-UPNNC-248124-NC-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One Pending Impl / Acquisition des supports de IDA / D2570 ation of the RMCHN minimu Post Open - National 94,800.00 0.00 2022-01-24 2022-03-08 2022-04-07 ations Envelope ementation communication confection/s m package érigraphie MG-UPNNC-261457-NC-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Impression et livraison de 4 IDA / D2570 ation of the RMCHN minimu Post Open - National 18,000.00 14,380.15 Completed 2021-12-11 2022-01-18 2022-03-12 2022-01-21 2022-04-02 ations Envelope 526 registres SPC m package MG-UPNNC-252115-NC-RFQ Scale up coverage and utiliz / Acheminement des tables Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Open - National 64,970.00 0.00 Canceled 2021-12-07 2022-01-21 2022-02-05 et chaises pour les sites com ations Envelope m package munautaires aux niveaux sit es communautaires MG-UPNNC-283287-NC-RFQ / Impression des bulletins KA LIANA répartie en 4 lots: Scale up coverage and utiliz Request for Quot Single Stage - One lot 1: KA LIANA N°20 IDA / D2570 ation of the RMCHN minimu Post Open - National 8,700.00 3,854.70 Signed 2022-12-03 2023-01-16 2022-08-20 2023-07-15 ations Envelope lot 2: KA LIANA N°21 m package lot 3: KA LIANA N°22 lot 4: KA LIANA N°23 MG-UPNNC-281937-NC-RFQ / Confection et production ré parties en 5 lots: lot 1: Pochette à rabat perso Scale up coverage and utiliz nnalisée Request for Quot Single Stage - One Under Imple IDA / D2570 ation of the RMCHN minimu Post Open - National 4,000.00 0.00 2022-06-08 2022-07-22 2022-09-20 lot 2: Sac kraft ations Envelope mentation m package lot 3: X banner lot 4: Mug VIP personnalisé lot 5: Impression bâches de f ond de stand pour les ORN P ARN MG-UPNNC-283277-NC-RFQ / Confection et livraison répa Scale up coverage and utiliz rtie en 3 lots: Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Open - National 36,000.00 0.00 Signed 2022-04-27 2022-06-10 2022-09-08 lot 1: 1 000 Polos VIP ations Envelope m package lot 2: 6 000 Casquettes lot 3 : 100 Gilets MG-UPNNC-303662-NC-RFQ / Acquisition des supports de communication imprimés re partie en 3 lots : Strengthen capacity to man Lot 1 : Impression de 1 000 J Request for Quot Single Stage - One Under Imple IDA / D2570 age and deliver the RMCHN Post Open - National 5,000.00 0.00 2022-08-20 2022-10-15 2022-11-19 ob aids Coaching ations Envelope mentation minimum package Lot 2 : Impression de 9 000 J ob aids CIP Lot 3 : Impression de 2 000 Affiches des offres de servic e FAFY MG-UPNNC-281923-NC-RFQ / Impression et livraison rép Strengthen capacity to man arties en 3 lots: Request for Quot Single Stage - One IDA / D2570 age and deliver the RMCHN Post Open - National 26,500.00 0.00 Signed 2022-07-25 2022-09-09 2022-10-14 lot 1: 4 600 Registres SPC ations Envelope minimum package lot 2: 4 600 Registre PECMA M lot 3: 500 Rapports grand pu blic MG-UPNNC-248131-NC-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Impression des supports de IDA / D2570 ation of the RMCHN minimu Post Open - National 66,000.00 0.00 Canceled 2022-01-10 2022-02-22 2022-03-24 ations Envelope communication (imprimés n m package umériques) MG-UPNNC-310887-NC-RFQ / Impression et livraison rép arties en cinq lots : Scale up coverage and utiliz Lot 1 Impression Affiches LN Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Open - National 35,950.00 0.00 Completed 2022-10-19 2022-12-14 2023-01-18 S ations Envelope m package Lot 2 Impression Dépliants L NS Lot 3 Agenda VIP 2023 Lot 4 Calendriers chevalets Lot 5 Calendriers muraux MG-UPNNC-311035-NC-DIR Project Management, Capac / Consultant en charge du p Under Imple IDA / D2570 ity Building and Operations Post Direct Selection Direct - National 50,000.00 0.00 2022-12-12 2023-01-09 2022-12-19 2023-03-03 2023-01-16 2024-01-16 aiement des indemnités des mentation Support Agents Communautaires MG-UPNNC-221899-NC-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Production de 1 000 Stylos IDA / D2570 ation of the RMCHN minimu Post Limited 1,800.00 0.00 Canceled 2021-03-22 2021-04-26 2021-05-26 ations Envelope personnalisé m package CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Techni Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) t (US$) Notice equest for Proposals as Issued Proposals / Minutes cal Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UPNNC 3 15 SMC / Consulta Project Management, Capac Least Cost Selecti IDA / V0970 Post Open - National 15,000.00 7,385.25 Completed 2017-11-08 2017-12-14 2017-11-22 2017-12-27 2017-12-13 2018-03-08 2017-12-27 2018-04-05 2018-01-10 2018-05-02 2018-02-14 2018-05-14 2018-03-14 2018-05-28 2018-06-12 2018-06-25 nt - Auditeur Externe ity Building and Operations on Support UPNNC 3 18 SQC MANUELS Project Management, Capac Consultant Qualifi / Consultant chargé de la mi IDA / V0970 ity Building and Operations Post Open - National 20,000.00 14,408.60 Completed 2017-12-26 2017-12-14 2018-01-09 2018-01-30 2018-01-22 2018-02-13 2018-02-07 2018-03-13 2018-02-07 2018-07-11 2018-04-12 cation Selection se à jour du manuel d'opérat Support ion du Projet UPNNC 3 16 SQC SUPPL / C Project Management, Capac Consultant Qualifi abinet de recrutement du pe IDA / V0970 ity Building and Operations Post Limited 10,000.00 9,876.60 Completed 2018-01-01 2018-01-11 2018-01-15 2018-02-16 2018-01-29 2018-02-22 2018-03-05 2018-02-22 2018-04-04 2018-05-23 cation Selection rsonnel supplémentaire (UC Support P) UPNNC 3 36 SQC EVAL BES OIN EN FORMATION / CONSE ILS ET ASSISTANCE TECHNIQ UE INTERNATIONALE POUR Strengthen capacity to man Consultant Qualifi Open - Internation MODERNISER LA FORMATIO IDA / V0970 age and deliver the RMCHN Post 500,000.00 312,906.00 Signed 2018-02-15 2018-03-08 2018-03-01 2018-03-09 2018-04-14 2018-05-16 2018-05-14 2018-09-28 2018-06-07 2018-10-01 2018-10-05 cation Selection al N DES AGENTS DANS LES CE minimum package NTRES DE SANTE DE BASE E T DES AGENTS COMMUNAUT AIRES DE SANTE ET DE NUT RITION A MADAGASCAR UPNNC 3 25 SMC CONTROL Project Management, Capac E TRAVAUX UCP / Bureau d'é Least Cost Selecti IDA / V0970 ity Building and Operations Post Open - National 12,000.00 6,811.02 Signed 2018-02-15 2018-01-11 2018-03-01 2018-03-29 2018-03-14 2018-04-26 2018-04-17 2018-05-10 2018-04-27 2018-06-07 2018-05-16 2018-07-05 2018-05-15 2019-01-01 2018-09-26 tude chargé du contrôle des on Support travaux extension Bureau U CP UPNNC 1 8 FORMATION EN Project Management, Capac AUDIT INTERNE / Renforcem Consultant Qualifi IDA / V0970 ity Building and Operations Post Limited 5,000.00 2,588.70 Signed 2018-02-15 2018-02-08 2018-03-01 2018-02-08 2018-03-15 2018-04-19 2018-02-16 2018-04-24 ent de capacité en matière d cation Selection Support 'audit interne de projets UPNNC 3 38 SFQC EVALUAT Scale up coverage and utiliz Quality And Cost- Open - Internation ION MIS / Firme international IDA / V0970 ation of the RMCHN minimu Post 350,000.00 329,513.00 Signed 2018-05-04 2018-03-28 2018-05-25 2018-07-08 2018-05-24 2018-08-05 2018-08-03 2018-09-04 2018-10-12 2018-10-09 2018-10-12 2018-11-13 2019-07-30 2019-05-12 Based Selection al e chargée de l'évaluation du m package HMIS PARN UPNNC 1 6 1 23 ONG HAUTE MATSIATRA / Sélectio n de ONG/Associations parte Strengthen capacity to man Consultant Qualifi naires chargées du fonction IDA / D2570 age and deliver the RMCHN Post Open - National 875,000.00 29,122.48 Signed 2018-05-18 2019-07-22 2018-06-30 2018-08-11 2018-09-21 2018-09-08 2018-08-02 2018-09-22 2018-10-31 2019-12-31 cation Selection nement des sites communa minimum package utaires et vouchers dans la Région Haute Matsiatra (737 sites dans 7 districts répartis en 33 lots) Page 5 PARN UPNNC 1 6 ONG VAKI NANKARATRA / Sélection de ONG/Associations partenaire Strengthen capacity to man Consultant Qualifi s chargées du fonctionneme IDA / D2570 age and deliver the RMCHN Post Open - National 1,100,000.00 30,623.37 Signed 2018-05-18 2018-05-17 2018-06-30 2018-08-11 2018-08-20 2018-09-08 2018-11-19 2018-09-22 2018-10-31 2019-12-31 cation Selection nt des sites communautaires minimum package et vouchers - Région Vakina nkaratra (904 sites dans 7 di stricts répartis en 40 lots) PARN UPNNC 1 6 1 23 ONG AMORONIMANIA / ONG/Asso ciations partenaires chargée Strengthen capacity to man Consultant Qualifi s du fonctionnement des sit IDA / D2570 age and deliver the RMCHN Post Open - National 875,000.00 36,728.23 Signed 2018-05-18 2018-09-12 2018-06-30 2018-08-11 2018-09-11 2018-09-08 2018-10-29 2018-09-22 2018-10-31 2019-12-31 cation Selection es communautaires et vouc minimum package hers dans la Région Amoron' i Mania (713 sites dans 4 dis tricts répartis en 32 lots) PARN UPNNC 1 6 1 23 ONG ITASY / ONG/Associations pa Strengthen capacity to man rtenaires chargées du foncti Consultant Qualifi IDA / D2570 age and deliver the RMCHN Post Open - National 650,000.00 31,789.95 Signed 2018-05-18 2018-05-17 2018-06-30 2018-08-11 2018-09-07 2018-09-08 2018-10-30 2018-09-22 2018-11-10 2019-12-31 onnement des sites commu cation Selection minimum package nautaires et vouchers dans l a Région Itasy (539 sites da ns 3 districts répartis en 24 l ots) PARN UPNNC 3 1 SMC RECR Project Management, Capac UTEMENT / Cabinet chargé d Least Cost Selecti IDA / D2570 ity Building and Operations Post Open - National 10,000.00 0.00 Canceled 2018-08-10 2018-08-10 2018-08-24 2018-09-21 2018-10-05 2018-11-02 2018-11-16 2018-12-14 u recrutement du personnel on Support complémentaire pour l'U-PN NC UPNNC 3 38 EVALUATION S Scale up coverage and utiliz Consultant Qualifi YSTEME INFO SANIT / Evalua IDA / V0970 ation of the RMCHN minimu Post Limited 250,000.00 0.00 Canceled 2017-12-26 2018-03-21 2018-01-09 2018-01-30 2018-02-20 2018-08-19 cation Selection tion du système d'informatio m package n sanitaire UPNNC 3 9 SQC ONG VAKIN ANKARATRA / Réactivation e Strengthen capacity to man Consultant Qualifi t redynamisation des activit IDA / V0970 age and deliver the RMCHN Post Open - National 123,000.00 0.00 Canceled 2017-11-17 2017-12-01 2017-12-29 2018-01-19 2018-02-16 2018-09-14 cation Selection és des sites de nutrition dan minimum package s le Vakinankaratra (22ONG/ 541sites/54animateurs) UPNNC 3 9 SQC ONG AMOR ONIMANIA / Réactivation et r Strengthen capacity to man Consultant Qualifi edynamisation des activités IDA / V0970 age and deliver the RMCHN Post Open - National 78,000.00 0.00 Canceled 2017-11-17 2017-12-01 2017-12-29 2018-01-19 2018-02-16 2018-09-14 cation Selection des sites de nutrition dans l' minimum package AmoronImania (17ONG/330s ites/33animateurs) UPNNC 3 9 SQC ONG ITASY / Réactivation et redynamisa Strengthen capacity to man Consultant Qualifi tion des activités des sites d IDA / V0970 age and deliver the RMCHN Post Open - National 22,000.00 0.00 Canceled 2017-11-17 2017-12-01 2017-12-29 2017-12-31 2018-01-21 2018-08-19 cation Selection e nutrition dans l'Itasy (6ON minimum package G/125sites/13animateurs) UPNNC 3 9 SQC ONG HAUT E MATSIATRA / Réactivation Strengthen capacity to man Consultant Qualifi et redynamisation des activi IDA / V0970 age and deliver the RMCHN Post Open - National 110,000.00 0.00 Canceled 2017-11-17 2017-12-01 2017-12-29 2018-01-19 2018-02-16 2018-09-14 cation Selection tés des sites de nutrition da minimum package ns la Haute Matsiatra (19ON G/484sites/48animateurs) UPNNC 1 14 SQC / Consulta Strengthen capacity to man Consultant Qualifi nt chargé de l'étude de faisa IDA / V0970 age and deliver the RMCHN Post Open - National 50,000.00 0.00 Canceled 2017-11-07 2017-11-21 2018-01-02 2018-01-16 2018-02-13 2018-06-13 cation Selection bilité pour la mise en place d minimum package u fonds dédié UPNNC 3 38 SQC EVALUATI Scale up coverage and utiliz Consultant Qualifi Open - Internation ON MIS / Firme international IDA / V0970 ation of the RMCHN minimu Post 350,000.00 0.00 Canceled 2018-03-09 2018-03-23 2018-03-21 2018-04-27 2018-05-27 2018-07-01 2018-12-28 cation Selection al e chargée de l'évaluation du m package HMIS MG-UPNNC-94277-CS-CQS / Project Management, Capac Consultant Qualifi Recrutement Directeur Natio IDA / D2570 ity Building and Operations Post Open - National 22,400.00 0.00 Canceled 2018-06-11 2018-06-07 2018-07-20 2019-07-22 2018-11-06 2019-01-11 2019-02-18 2020-02-18 cation Selection nal U-PNNC Support MG-UPNNC-3 1 01 03 00 CA BINET DE RECRUTE / Cabine Project Management, Capac Consultant Qualifi t chargé du recrutement du IDA / D2570 ity Building and Operations Post Open - National 5,000.00 5,890.25 Signed 2019-06-04 2018-12-31 2019-06-09 2019-07-01 2019-05-23 2019-07-06 2019-06-21 2019-07-13 2019-06-21 2019-08-02 cation Selection personnel complémentaire p Support our l'UPNNC (RSE-AI,Logistici en) MG-UPNNC-94277-B / Recru Project Management, Capac Consultant Qualifi Pending Impleme IDA / D2570 Post Open - National 22,400.00 0.00 2018-06-01 2018-06-29 2018-10-19 2018-12-14 2019-01-04 2023-01-04 tement Directeur National p ity Building and Operations cation Selection ntation our l'UPNNC Support MG-UPNNC-170818-CS-FBS / ONG/Partenaires chargées Strengthen capacity to man Fixed Budget Sele Under Implement du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Open - National 200,000.00 0.00 2020-08-03 2020-03-21 2020-08-17 2020-09-14 2020-10-14 2020-11-13 2020-12-27 2021-02-09 2022-08-03 ction ation communautaires et voucher minimum package s dans la région Amoron'i M ania repartie en 7 lots. MG-UPNNC-170815-CS-FBS / ONG/Partenaires chargées Strengthen capacity to man Fixed Budget Sele Under Implement du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Open - National 200,000.00 0.00 2020-08-03 2020-03-21 2020-08-17 2020-09-30 2020-10-30 2020-11-06 2020-12-04 2021-02-02 2022-07-27 ction ation communautaires et voucher minimum package s dans la région Haute Matsi atra repartie en 7 lots. MG-UPNNC-170820-CS-FBS / ONG/Partenaires chargées Strengthen capacity to man Fixed Budget Sele Under Implement du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Open - National 120,000.00 0.00 2020-08-03 2020-03-21 2020-08-17 2020-09-30 2020-10-30 2020-11-29 2020-12-27 2021-02-25 2022-08-19 ction ation communautaires et voucher minimum package s dans la région Itasy reparti es en 4 lots MG-UPNNC-170841-CS-FBS / ONG/Partenaires chargées Strengthen capacity to man Fixed Budget Sele Under Implement du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Open - National 330,000.00 0.00 2020-08-03 2020-03-21 2020-08-17 2020-09-30 2020-10-30 2020-11-13 2020-12-27 2021-02-25 2022-08-19 ction ation communautaires et voucher minimum package s dans la région Vakinakarat ra repartie en 10 lots MG-UPNNC-186006-CS-FBS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites Fixed Budget Sele Under Implement IDA / D2570 age and deliver the RMCHN Post Open - National 400,000.00 0.00 2020-09-01 2019-10-08 2020-10-01 2020-10-17 2020-11-16 2020-11-30 2020-12-14 2021-01-07 2021-03-02 communautaires et voucher ction ation minimum package s dans la région Bongolava, dont 02 Districts répartis en 15 lots. MG-UPNNC-199553-CS-FBS / Sélection ONG/Associations Scale up coverage and utiliz Partenaires pour l'interventi Fixed Budget Sele Under Implement IDA / D2570 ation of the RMCHN minimu Post Open - National 900,000.00 0.00 2020-11-02 2020-06-15 2020-12-02 2021-01-31 2021-03-02 2021-04-01 2021-05-31 2021-06-08 2022-11-30 on dans les secteurs de la n ction ation m package utrition et de la santé dans l a région Alaotra Mangoro (3 0 lots dont 30 contrats) MG-UPNNC-199548-CS-FBS / Sélection ONG/Associations Scale up coverage and utiliz partenaires pour l'interventi Fixed Budget Sele Under Implement IDA / D2570 ation of the RMCHN minimu Prior Open - National 1,900,000.00 0.00 2020-12-28 2021-01-27 2021-03-28 2021-04-27 2021-05-27 2021-07-26 2021-08-12 2023-02-03 on dans les secteurs de la n ction ation m package utrition et de la santé dans l a région Analamanga (61 lot s c'est à dire 61 contrats) MG-UPNNC-234950-CS-CQS / Sélection de consultant en charge de l'étude Phase 1 et Project Management, Capac Consultant Qualifi Under Implement , Phase 2 la gestion, contrôle IDA / D2570 ity Building and Operations Post Limited 80,000.00 0.00 2021-06-15 2021-08-24 2021-06-22 2021-07-22 2021-08-12 2022-04-12 cation Selection ation et surveillance des travaux Support d'extension et surélévation d'un bâtiment à usage de bu reau pour l'UPNNC et l'ONN Page 6 MG-UPNNC-248121-CS-CQS / Recrutement de consultant Project Management, Capac Consultant Qualifi Open - Internation Under Implement en charge de renforcement IDA / D2570 ity Building and Operations Post 25,000.00 0.00 2021-09-23 2021-10-12 2021-10-08 2021-10-22 2021-10-29 2021-11-12 2021-12-12 cation Selection al ation de capacité des personnels Support de l'UPNNC en comptabilité et finances MG-UPNNC-254373-CS-CQS / Recrutement de consultant Project Management, Capac Consultant Qualifi Open - Internation Under Implement en charge de renforcement IDA / D2570 ity Building and Operations Post 132,000.00 0.00 2021-10-07 2021-10-12 2021-10-22 2021-11-05 2021-11-12 2021-11-26 2021-12-26 cation Selection al ation de capacité des personnels Support de l'UPNNC dans divers dom aines MG-UPNNC-267017-CS-FBS / Rescrutement de 2 ONG/Pa Scale up coverage and utiliz rtenaires chargés du fonctio Fixed Budget Sele Pending Impleme IDA / D2570 ation of the RMCHN minimu Post Open - National 33,000.00 0.00 2022-04-04 2022-04-18 2022-05-02 2022-05-16 2022-05-23 2022-06-06 2022-06-23 2023-03-20 nnement des sites commun ction ntation m package autaires de la région Vakina karatra__Districts Faratsiho et Betafo. MG-UPNNC-265950-CS-FBS / Recrutement 2 ONG/Parten Scale up coverage and utiliz aire chargé du fonctionneme Fixed Budget Sele Pending Impleme IDA / D2570 ation of the RMCHN minimu Post Open - National 21,700.00 0.00 2022-04-04 2022-04-18 2022-05-09 2022-05-23 2022-05-30 2022-06-20 2022-07-07 2023-06-02 nt des sites communautaires ction ntation m package dans les régions Bongolava_l ot 3_Districts Fenoarivobe et Tsiroanomandidy. MG-UPNNC-268843-CS-FBS / Recrutement de 02 ONG/Pa Scale up coverage and utiliz Fixed Budget Sele Pending Impleme rtenaires chargés du fonctio IDA / D2570 ation of the RMCHN minimu Post Open - National 40,000.00 0.00 2022-04-04 2022-04-18 2022-05-02 2022-05-16 2022-05-23 2022-06-06 2022-06-20 2023-03-17 ction ntation nnement des sites commun m package autaires de la région Ambosi tra__District Fandriana MG-UPNNC-267218-CS-FBS / Recrutement de 6 ONG/Par tenaires chargés du fonction Scale up coverage and utiliz Fixed Budget Sele Pending Impleme nement des sites communa IDA / D2570 ation of the RMCHN minimu Post Open - National 173,000.00 0.00 2022-04-04 2022-04-18 2022-05-02 2022-05-16 2022-05-23 2022-06-06 2022-06-23 2023-03-20 ction ntation utaires dans la région Haute m package Matsiatra_ Districts Ambalav ao, Ambohimahasoa, Isandr a et Lalangina. MG-UPNNC-283581-CS-CQS / Sélection de consultant en charge de l'étude, de la gest Project Management, Capac Consultant Qualifi ion, du contrôle et de la surv IDA / D2570 ity Building and Operations Post Open - National 80,000.00 0.00 Canceled 2022-04-07 2022-03-30 2022-04-21 2022-04-26 2022-06-04 2022-06-07 2022-07-12 2023-04-08 cation Selection eillance des travaux de réha Support bilitation (extension et surél évation) d'un bâtiment à usa ge de bureau pour l'UPNNC et l'ONN. MG-UPNNC-257627-CS-CQS Project Management, Capac Consultant Qualifi / Recrutement d'un cabinet IDA / D2570 ity Building and Operations Post Open - National 100,000.00 0.00 Canceled 2021-12-13 2022-02-11 2021-12-27 2022-02-11 2022-02-09 2022-05-18 2022-02-23 2022-03-16 2023-03-17 cation Selection pour le suivi de la gestion de Support s intrants INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Draft Negotiated Con Description Component Review Type Method Process Status Terms of Reference d/Selected Consultan Signed Contract Contract Completion o. h unt (US$) t (US$) tract t Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UPNNC 1-3 INDV / Consulta Scale up coverage and utiliz Individual Consult nt chargé de la consolidatio IDA / V0970 ation of the RMCHN minimu Post Open 64,000.00 33,580.86 Signed 2017-11-07 2017-12-14 2017-12-26 2018-01-19 2018-01-09 2018-02-13 2018-02-06 2018-05-14 2018-06-06 ant Selection n des mécanismes de gratui m package tés UPNNC 1 12 INDV / Consult Strengthen capacity to man ant chargé de l'analyse et co Individual Consult IDA / V0970 age and deliver the RMCHN Post Open 50,000.00 10,096.46 Signed 2017-11-07 2018-03-08 2018-01-02 2018-06-06 2018-01-16 2018-09-24 2018-02-13 2018-11-19 2018-05-14 nception de base de donnée ant Selection minimum package s intégrées sur tablettes UPNNC 3 3 INDV / Consulta Strengthen capacity to man Individual Consult nt chargé de l'évaluation de IDA / V0970 age and deliver the RMCHN Post Open 60,000.00 12,232.05 Signed 2017-11-07 2018-02-08 2017-12-24 2018-04-11 2018-01-07 2018-05-18 2018-02-04 2018-05-22 2018-04-05 ant Selection s besoins de renforcement d minimum package e capacité UPNNC 1 13 ED / Consultant Strengthen capacity to man chargé de l'étude préalable IDA / V0970 age and deliver the RMCHN Post Direct Selection Direct 115,000.00 101,480.00 Completed 2017-10-20 2017-11-21 2017-11-17 2017-11-27 2018-01-05 2017-11-29 2018-04-05 2018-09-26 à la mise à l'échelle du Fina minimum package ncement Basé sur les Résult ats (FBR) UPNNC 1 5 ED JHU / Consult ant chargé de la consolidatio n des systèmes de motivatio n utilisées et charges de tra Scale up coverage and utiliz vail /prestation de services, IDA / V0970 ation of the RMCHN minimu Post Direct Selection Direct 350,000.00 280,927.00 Signed 2017-11-16 2017-12-17 2017-11-26 2018-01-30 2018-03-27 2018-07-29 connaissances acquises et c m package ompétences des ACN et AC au niveau des 8 Régions (ro uge et jaune) et 2 Régions d u FA FSS dans le cadre des UPNNC 3 33 ED ALIVE THRI Scale up coverage and utiliz VE / Etat des lieux et prépar IDA / V0970 ation of the RMCHN minimu Post Direct Selection Direct 450,000.00 449,678.00 Signed 2017-11-17 2017-11-29 2017-11-27 2018-01-22 2018-02-12 2018-07-21 ation du Plan de communica m package tion pour le Projet suivant le PNAN III. UPNNC 1 13 INDV RBF2 / Dé termination des coûts et niv Strengthen capacity to man eaux de subvention par résu Individual Consult IDA / V0970 age and deliver the RMCHN Post Limited 15,000.00 16,600.00 Completed 2017-11-17 2017-12-14 2017-12-01 2017-12-16 2017-12-22 2018-02-08 2018-01-26 2018-02-24 2018-03-27 2018-04-18 ltat de la mise en oeuvre du ant Selection minimum package financement basé sur la perf ormance dans le secteur san té à Madagascar UPNNC 3 29 ED STIMULATIO N PRECOCEE / Stimulation pr écoce : appuyer la préparati Scale up coverage and utiliz on des différentes phases d'i IDA / V0970 ation of the RMCHN minimu Post Direct Selection Direct 50,000.00 5,123.42 Signed 2017-12-26 2018-03-08 2018-01-10 2018-03-21 2018-02-07 2018-03-26 2018-04-08 mplémentation et d'assurer m package un transfert de compétence à l'équipe nationale dans la f ormation, le suivi et la super vision UPNNC 3 40 COACH ED NAT Project Management, Capac / Consultant National chargé IDA / V0970 ity Building and Operations Post Direct Selection Direct 50,000.00 80,730.64 Signed 2018-01-01 2018-01-30 2018-01-11 2018-01-30 2018-03-17 2018-03-27 2019-03-12 de la facilitation et Coaching Support pour la mise en œuvre PARN -APPM UPNNC 3 15 IND AUDIT NAT IONAL MSANP / Consultant c Project Management, Capac hargé de l'exploitation des i Individual Consult IDA / V0970 ity Building and Operations Post Open 10,000.00 5,594.89 Signed 2018-02-16 2018-02-21 2018-04-06 2018-03-30 2018-04-27 2018-04-06 2018-05-25 2018-04-06 2018-06-24 nformations collectées et éla ant Selection Support boration du rapport de l'audi t national - Ministère de la S anté UPNNC 3 29 ED ECD INSTIT UTEUR / Assistance en ECD - Scale up coverage and utiliz Appuyer la psychologue (1) Individual Consult IDA / V0970 ation of the RMCHN minimu Post Direct 5,000.00 1,114.11 Signed 2018-03-20 2018-03-08 2018-03-30 2018-03-21 2018-04-13 2018-03-26 2018-05-11 2018-03-26 2019-03-07 dans la préparation et facilit ant Selection m package ation des ateliers, (2) réalisa tion du pré-test et (3) réunio n de discussion UPNNC 3 29 ED ECD EDUCA TEUR / Assistance en ECD - Scale up coverage and utiliz Appuyer la psychologue (1) Individual Consult IDA / V0970 ation of the RMCHN minimu Post Direct 5,000.00 571.34 Signed 2018-03-20 2018-03-08 2018-03-30 2018-03-21 2018-04-13 2018-03-26 2018-05-11 2018-03-26 2019-03-07 dans la préparation et facilit ant Selection m package ation des ateliers, (2) réalisa tion du pré-test et (3) réunio n de discussion Page 7 UPNNC 3 29 ED ECD ASSIST ANTE SOCIALE / Assistance e Scale up coverage and utiliz n ECD - Appuyer la psycholo Individual Consult IDA / V0970 ation of the RMCHN minimu Post Direct 5,000.00 1,114.11 Signed 2018-03-20 2018-03-08 2018-03-30 2018-03-21 2018-04-13 2018-03-26 2018-05-11 2018-03-26 2019-03-07 gue (1) dans la préparation ant Selection m package et facilitation des ateliers, (2 ) réalisation du pré-test et (3 ) réunion de discussion UPNNC 3 29 ED ECD ASSIST ANTE SOCIALE 2 / Assistanc Scale up coverage and utiliz e en ECD - Appuyer la psych Individual Consult IDA / V0970 ation of the RMCHN minimu Post Direct 5,000.00 1,114.11 Signed 2018-03-20 2018-03-08 2018-03-30 2018-03-21 2018-04-13 2018-03-26 2018-05-11 2018-03-26 2019-03-07 ologue (1) dans la préparati ant Selection m package on et facilitation des ateliers , (2) réalisation du pré-test e t (3) réunion de discussion PARN UPNNC 2 10 JHU / Assi Scale up coverage and utiliz stance technique internation IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 400,000.00 0.00 Canceled 2018-05-20 2019-10-14 2018-06-17 2018-07-29 2019-12-31 ale effectuée par l'Université m package John Hopkins PARN UPNNC 2 10 TANGERI Scale up coverage and utiliz NE HCD / Consultant chargé IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 100,000.00 0.00 Canceled 2018-05-04 2019-12-03 2018-05-18 2018-06-01 2019-06-01 de la recherche HCD m package PARN UPNNC 2 10 HCD CI / Scale up coverage and utiliz Groupe de consultants indivi Individual Consult IDA / D2570 ation of the RMCHN minimu Post Direct 100,000.00 7,578.65 Signed 2018-05-10 2018-06-14 2018-05-24 2018-05-31 2018-07-15 2018-05-31 2018-07-15 2019-05-31 duels - assistants locaux dan ant Selection m package s les recherches HCD PARN UPNNC 1 6 MANOP O Strengthen capacity to man NG / Consultant Individuel c Individual Consult IDA / D2570 age and deliver the RMCHN Post Direct 5,000.00 4,676.91 Signed 2018-08-03 2018-07-17 2018-08-17 2018-08-22 2018-08-31 2018-09-19 2018-09-14 2018-09-19 2018-11-13 hargé de l'élaboration du Ma ant Selection minimum package nuel d'Opération des ONG PARN UPNNC AT CP / Recrut Project Management, Capac Individual Consult ement Assistant Technique IDA / D2570 ity Building and Operations Post Direct 1,500.00 1,335.69 Signed 2018-08-16 2018-08-01 2018-08-30 2018-08-01 2018-09-06 2018-08-01 2018-09-06 2018-08-01 2018-12-31 ant Selection UPNNC - Coursier Planton Support PARN UPNNC AT RNAF / Rec Project Management, Capac rutement Assistant Techniqu Individual Consult IDA / D2570 ity Building and Operations Post Direct 9,000.00 7,643.24 Signed 2018-08-16 2018-08-01 2018-08-30 2018-08-01 2018-09-06 2018-08-01 2018-09-06 2018-08-01 2018-12-31 e UPNNC - Responsable Nati ant Selection Support onal Administratif et Financi er Intérimaire PARN UPNNC AT CPT01 / Re Project Management, Capac Individual Consult crutement Assistant Techniq IDA / D2570 ity Building and Operations Post Direct 3,000.00 2,412.10 Signed 2018-08-16 2018-08-01 2018-08-30 2018-08-01 2018-09-06 2018-08-01 2018-09-06 2018-08-01 2018-12-31 ant Selection ue UPNNC - Comptable Support PARN UPNNC AT CPT02 / Re Project Management, Capac Individual Consult crutement Assistant Techniq IDA / D2570 ity Building and Operations Post Direct 3,000.00 2,364.29 Signed 2018-08-16 2018-08-01 2018-08-30 2018-08-01 2018-09-06 2018-08-01 2018-09-06 2018-08-01 2018-12-31 ant Selection ue UPNNC - Comptable Support PARN UPNNC AT SCPT / Rec Project Management, Capac Individual Consult rutement Assistant Techniqu IDA / D2570 ity Building and Operations Post Direct 2,000.00 1,623.78 Signed 2018-08-16 2018-08-01 2018-08-30 2018-09-06 2018-08-01 2018-09-06 2018-08-01 2018-12-31 ant Selection e UPNNC - Secrétaire Comp Support table PARN UPNNC AT APM / Recr Project Management, Capac Individual Consult utement Assistant Techniqu IDA / D2570 ity Building and Operations Post Direct 3,000.00 2,389.55 Signed 2018-08-16 2018-08-01 2018-08-30 2018-09-06 2018-08-16 2018-09-06 2018-08-01 2018-12-31 ant Selection e UPNNC - Passation de Mar Support chés PARN UPNNC AT TM / Recru Project Management, Capac Individual Consult tement Assistant Technique IDA / D2570 ity Building and Operations Post Direct 2,000.00 1,528.26 Signed 2018-08-16 2018-08-01 2018-08-30 2018-08-01 2018-09-06 2018-08-01 2018-09-06 2018-08-01 2018-12-31 ant Selection UPNNC - Technicien de Main Support tenance PARN UPNNC AT MAG / Recr Project Management, Capac Individual Consult utement Assistant Techniqu IDA / D2570 ity Building and Operations Post Direct 2,000.00 1,623.78 Signed 2018-08-16 2018-08-01 2018-08-30 2018-08-01 2018-09-06 2018-08-01 2018-09-06 2018-08-01 2018-12-31 ant Selection e UPNNC - Magasinier Support UPNNC 1 11 INDV / Consult Strengthen capacity to man Individual Consult ant chargé de l'évaluation d IDA / V0970 age and deliver the RMCHN Post Open 82,000.00 0.00 Canceled 2017-11-07 2017-11-17 2017-12-31 2018-01-14 2018-02-11 2018-05-12 ant Selection u système MIS au niveau de minimum package s 2 Régions FSS UPNNC 3 36 INDV / Deux co nsultants individuels chargé de l'évaluation exhausitive d Strengthen capacity to man es besoins en formation et D Individual Consult IDA / V0970 age and deliver the RMCHN Post Open 500,000.00 0.00 Canceled 2017-11-16 2018-02-02 2018-01-04 2018-01-25 2018-03-01 2018-08-28 éveloppement de curriculum ant Selection minimum package (FdF et supports) des interve nants au niveau des platefor mes communautaires exista nts (AC, ACN et CSB) UPNNC 3 18 INDV / Consult ant chargé de la mise à jour Project Management, Capac Individual Consult du manuel de procédures du IDA / V0970 ity Building and Operations Post Open 20,000.00 0.00 Canceled 2017-11-07 2017-12-14 2017-12-17 2017-12-31 2018-01-28 2018-04-28 ant Selection projet (opérationnel et admi Support nistratif, santé et nutrition) UPNNC 3 40 COACH ED INT Project Management, Capac / Consultant International ch IDA / V0970 ity Building and Operations Post Direct Selection Direct 100,000.00 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2019-01-11 argé de la facilitation et Coa Support ching pour la mise en œuvre PARN-APPM MG-UPNNC-93278-CS-CDS / Sélection de Cabinet chargé Project Management, Capac de recrutement du personne IDA / D2570 ity Building and Operations Post Direct Selection Direct 10,000.00 7,107.95 Signed 2018-12-29 2018-12-03 2019-01-03 2018-12-11 2019-01-12 2018-12-29 2019-02-02 l complémentaire pour l'U-P Support NNC (RNAF, RPM, ACOM et C hargé de Suivi CT) MG-UPNNC-93279-CS-INDV / Sélection de Consultant Ind ividuel chargé d'appuyer l'U Project Management, Capac Individual Consult nité pour le recrutement du IDA / D2570 ity Building and Operations Post Direct 3,000.00 4,339.04 Signed 2018-12-29 2018-11-01 2019-01-05 2018-11-30 2019-01-08 2018-12-14 2019-01-14 2018-12-14 2019-02-04 ant Selection personnel complémentaire d Support e l'U-PNNC (Assistant Passati on de Marché, Comptable, In formaticien, Logisticien, ...) MG-UPNNC-93281-CS-CDS / Sélection de Consultant char gé de la Stratégie de change Strengthen capacity to man ment social et de comporte IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 1,300,000.00 1,353,791.00 Signed 2018-12-29 2019-01-17 2019-01-08 2019-02-22 2019-02-27 2019-09-10 2019-12-31 ment pour l'amélioration de minimum package l'Alimentation de Nourrisson et du Jeune Enfant et de la N utrition de la Femme (ANJE/ NdF) MG-UPNNC-95691-CS-CDS / Project Management, Capac Pending Impleme Recrutement Responsable P IDA / D2570 ity Building and Operations Post Direct Selection Direct 8,000.00 0.00 2018-10-22 2018-11-08 2018-12-13 2019-06-11 ntation assation de Marchés Intérim Support aire MG-UPNNC-3101 03 00-IND Project Management, Capac Individual Consult V / Recrutement Responsabl IDA / D2570 ity Building and Operations Post Direct 4,500.00 0.00 Canceled 2019-06-05 2019-06-15 2019-06-30 2019-07-10 2019-10-08 ant Selection e Suivi Evaluation pi Support MG-UPNNC-2 5 01 04-ASSIS Strengthen capacity to man TANCE TECHNIQUE / Assista IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 500,000.00 0.00 Canceled 2019-07-29 2019-09-26 2019-08-08 2019-09-04 2019-12-03 nce Technique minimum package (John Hopkins University) MG-UPNNC-124140-CS-IND Strengthen capacity to man V CONSULTANT HCD / Consu Individual Consult IDA / D2570 age and deliver the RMCHN Post Direct 21,772.80 4,215.84 Signed 2019-07-24 2019-08-01 2019-08-07 2019-08-07 2019-08-14 2019-08-14 2019-08-28 2019-08-14 2020-08-27 ltant chargé des recherches ant Selection minimum package HCD- Consultant 1 Page 8 MG-UPNNC-124143-CS-IND Strengthen capacity to man Individual Consult V / Consultant chargé des re IDA / D2570 age and deliver the RMCHN Post Direct 21,120.00 14,313.02 Signed 2019-07-24 2019-08-13 2019-08-07 2019-08-07 2019-08-14 2019-08-12 2019-08-28 2019-08-14 2020-08-27 ant Selection cherches HCD-Consultant 2 minimum package MG-UPNNC-124145-CS-IND Strengthen capacity to man Individual Consult V / Consultant chargé des re IDA / D2570 age and deliver the RMCHN Post Direct 6,220.80 14,771.21 Signed 2019-07-24 2019-08-13 2019-08-07 2019-08-07 2019-08-14 2019-08-13 2019-08-28 2019-08-14 2020-08-27 ant Selection cherches HCD-Consultant 3 minimum package MG-UPNNC-124161-CS-IND Strengthen capacity to man Individual Consult V / Consultant chargé des re IDA / D2570 age and deliver the RMCHN Post Direct 6,220.80 4,220.35 Signed 2019-07-24 2019-08-13 2019-08-07 2019-08-07 2019-08-14 2019-08-13 2019-08-28 2019-08-14 2020-08-27 ant Selection cherches HCD- Consultant 4 minimum package MG-UPNNC-124162-CS-IND Strengthen capacity to man Individual Consult V / Consultant chargé des re IDA / D2570 age and deliver the RMCHN Post Direct 16,800.00 14,746.79 Signed 2019-07-24 2019-08-13 2019-08-07 2019-08-07 2019-08-14 2019-08-12 2019-08-28 2019-08-14 2020-08-27 ant Selection cherches HCD- Consultant 5 minimum package MG-UPNNC-124243 / Consul tant assistant chargé de la c Scale up coverage and utiliz onception, développement e Individual Consult IDA / D2570 ation of the RMCHN minimu Post Direct 5,000.00 3,040.86 Signed 2019-01-04 2019-08-12 2019-04-05 2019-09-19 2019-05-03 2019-09-25 2019-06-21 2019-09-25 2019-07-02 t préparation à l'implémenta ant Selection m package tion des activités de stimulat ion précoce des jeunes enfa nts-Assistant 1 MG-UPNNC-124242 / Consul tant assistant chargé de la c Scale up coverage and utiliz onception, développement e Individual Consult IDA / D2570 ation of the RMCHN minimu Post Direct 5,000.00 3,040.86 Signed 2019-01-04 2019-08-12 2019-04-05 2019-09-19 2019-05-03 2019-09-25 2019-06-21 2019-09-26 2019-07-02 t préparation à l'implémenta ant Selection m package tion des activités de stimulat ion précoce des jeunes enfa nts- Assistant 2 MG-UPNNC-124236 / Consul tant assistant chargé de la c Scale up coverage and utiliz onception, développement e Individual Consult IDA / D2570 ation of the RMCHN minimu Post Direct 5,000.00 3,040.86 Signed 2019-01-04 2019-08-12 2019-04-05 2019-09-19 2019-05-03 2019-09-25 2019-06-21 2019-09-26 2019-07-02 t préparation à l'implémenta ant Selection m package tion des activités de stimulat ion précoce des jeunes enfa nts - Assistant 3 MG-UPNNC-124232 / Consul tant assistant chargé de la c Scale up coverage and utiliz onception, développement e IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 50,000.00 13,249.64 Signed 2019-01-04 2019-08-12 2019-04-05 2019-09-19 2019-06-14 2019-09-26 2019-07-03 t préparation à l'implémenta m package tion des activités de stimulat ion précoce des jeunes enfa nts- Consultant MG-UPNNC-127989-CS-IND Scale up coverage and utiliz V / Recruter un Coordonnate Individual Consult IDA / D2570 ation of the RMCHN minimu Post Direct 75,000.00 70,000.00 Signed 2019-08-29 2019-08-28 2019-09-12 2019-08-29 2019-09-19 2019-10-03 2019-10-03 2019-10-06 2020-03-31 ur terrain des activités de pil ant Selection m package otage de la Stimulation Préc oce des enfants MG-UPNNC-127996-CS-CDS Project Management, Capac / Recrutement d'un cabinet Pending Impleme IDA / D2570 ity Building and Operations Post Direct Selection Direct 6,000.00 0.00 2019-08-26 2019-09-09 2019-09-30 2019-10-07 pour le renforcement de cap ntation Support acité en Passation de March és Strengthen capacity to man MG-UPNNC-134497-CS-CDS IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 4,000.00 4,005.42 Signed 2019-09-18 2019-09-16 2019-09-28 2019-09-24 2019-10-19 2019-10-12 2019-10-24 / Recyclage TOM 2 PRO minimum package MG-UPNNC-170725-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 30,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communaitaires et vouchers minimum package dans la région Amoron'i Man ia lot 7 - Ambositra MG-UPNNC-170777-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 33,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 2 Ambatolampy MG-UPNNC-170781-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 65,280.82 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 3 Antanifotsy et lot 4 Ambatolampy MG-UPNNC-170267-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 24,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 6) - Ambalavao MG-UPNNC-170281-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 31,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 2) - Ikalamavony MG-UPNNC-170788-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 91,772.74 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 1 Ambatolampy, lot 1 et lot 10 Antanifotsy MG-UPNNC-170791-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 47,989.23 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 1 et lot 3 Antsirabe I MG-UPNNC-170797-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 33,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 5 Antsirabe II MG-UPNNC-170284-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 26,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 2) - Isandra MG-UPNNC-170736-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 48,809.16 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Amoron'i M minimum package ania: lot 11 Fandriana lot 12 Fandriana MG-UPNNC-170747-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 39,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Amboron'i Mania lot 2 Ambatofinandra hana Page 9 MG-UPNNC-170737-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 61,247.54 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Amoron'i M minimum package ania: lot 11 Ambositra lot 3 Manandriana MG-UPNNC-170764-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 34,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 1 Miarinarivo MG-UPNNC-170801-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 34,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 8 Antsirabe II MG-UPNNC-170716-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 67,029.98 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Amoron'i M minimum package ania lot 1-Ambositra lot 3 Ambositra MG-UPNNC-170728-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 40,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Amoron'i M ania lot 4- Fandriana MG-UPNNC-170745-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 34,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Amoron'i M ania lot 3- Ambatofinandrah ana MG-UPNNC-170756-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 29,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 4 A rivonimamo MG-UPNNC-170760-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 27,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 8 Arivonimamo MG-UPNNC-170766-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 32,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 3 Miarinarivo MG-UPNNC-170772-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 28,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 3 S oavinandriana MG-UPNNC-170775-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 58,049.26 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 4 e t lot 5 Soavinandriana MG-UPNNC-170782-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 30,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 6 Antanifotsy MG-UPNNC-170787-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 76,729.35 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 7, lot 8 et lot 9 Antanif otsy MG-UPNNC-170795-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 31,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 4 Antsirabe II MG-UPNNC-170799-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 31,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 7 Antsirabe II MG-UPNNC-170802-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 31,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 1 Betafo I MG-UPNNC-170809-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 27,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 1 Faratsiho MG-UPNNC-170810-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 27,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 3 Faratsiho MG-UPNNC-170813-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 29,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 3 Mandoto MG-UPNNC-170290-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 33,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dns la régions Haute Matsi atra (lot 4) Isandra MG-UPNNC-170307-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man des sites communautaires et IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 38,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 vouchers dans la région Hau minimum package te Matsiatra (lot 2) - Vohibat o Page 10 MG-UPNNC-170748-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 39,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Amoron'i M ania lot 1 Ambatofinandrah ana MG-UPNNC-170754-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 30,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 2 A rivonimamo MG-UPNNC-170758-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 30,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 6 Arivonimamo MG-UPNNC-170769-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 32,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 5 Miarinarivo MG-UPNNC-170778-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 27,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 3 Ambatolampy MG-UPNNC-170798-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 33,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 6 Antsirabe II MG-UPNNC-170297-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 30,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 3) Lalangina MG-UPNNC-170712-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 54,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Amoron'i M minimum package ania lot 6-Ambositra lot 8 - Ambositra MG-UPNNC-170733-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 69,316.35 0.00 Canceled 2020-08-03 2020-09-09 2020-10-26 2022-04-19 s dans la région Amoron'i M minimum package ania: lot 6- Fandriana lot 2 Fandriana MG-UPNNC-170759-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 29,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 7 A rivonimamo MG-UPNNC-170770-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 232,504.36 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Itasy : minimum package lot 2, lot 4 et lot 6 Miarinari vo lot 1, lot 3, lot 5, lot 9 et lot 10 Arivonimamo MG-UPNNC-170771-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 31,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 1 S oavinandriana MG-UPNNC-170808-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 30,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 6 Betafo MG-UPNNC-170812-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 55,171.63 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 2 Mandoto et lot 5 Bet afo MG-UPNNC-170720-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnent des sites co IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 24,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 mmunautaires et vouchers d minimum package ans la région Amoron'i Mani a lot 5-Ambositra MG-UPNNC-170724-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 25,000.00 0.00 Canceled 2020-08-03 2020-08-13 2020-10-26 2022-04-19 communautaires et voucher minimum package s dans la région Amoron'i M ania lot 9- Ambositra MG-UPNNC-170727-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 38,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-10-26 2022-04-19 communautaires et voucher minimum package s dans la région Amoron'i M ania - lot 3- Fandriana MG-UPNNC-170730-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 25,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Amoron'i M ania lot 5- Fandriana MG-UPNNC-170741-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 56,457.81 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Amoron'i M minimum package ania: lot 1 Manandriana lot 4 Ambositra MG-UPNNC-170278-CS-CDS / ONG/Partenaires chargées du fonctionnement dans les Strengthen capacity to man sites communautaires et vo IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 63,362.21 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 uchers dans la région Haute minimum package Matsiatra lot 1- Fianarantsoa I lot 4 - Lalalngina Page 11 MG-UPNNC-170286-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 32,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 3) - Isandra MG-UPNNC-170738-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 49,134.14 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Amoron'i M minimum package ania: lot 2 Manandriana lot 7 Fandriana MG-UPNNC-170743-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 28,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Amoron'i M ania lot 4 Manandriana MG-UPNNC-170265-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 27,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-06 2022-04-30 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 3)-Ambalavao MG-UPNNC-170291-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 34,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 1) - Lalangina MG-UPNNC-170293-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 31,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 2) - Lalangina MG-UPNNC-170266-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 28,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-06 2022-04-30 communautaires et voucher minimum package s dans la région Haute Matsi atra (lo 5) - Ambalavao MG-UPNNC-170272-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 55,753.37 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Haute Matsi minimum package atra lot 4 - Ambohimahasoa lot 6 - Ambohimahasoa MG-UPNNC-170277-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 62,184.24 0.00 Canceled 2020-08-03 2020-08-13 2020-10-26 2022-04-19 s dans la région Haute Matsi minimum package atra lot 7- Ambohimahasoa lot 2 Ambalavao MG-UPNNC-170279-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 36,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Mats iatra (lot 2) - Fianarantsoa I MG-UPNNC-170283-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 67,651.61 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Haute Matsi minimum package atra lot 1- Isandra lot 1 Ambalavao MG-UPNNC-170269-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 54,299.59 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Haute Matsi minimum package atra: lot 2- Ambohimahasoa lot 3 Vohibato MG-UPNNC-170271-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communaitaires et vouchers IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 57,001.68 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 dans la région Haute Matsiat minimum package ra lot 3- Ambohimahasoa lot 5 Ambohimahasoa MG-UPNNC-170306-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 30,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 5) Lalangina MG-UPNNC-170803-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 32,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 4 Betafo MG-UPNNC-170792-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 88,622.76 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 1, lot 2 et lot 3 Antsira be II MG-UPNNC-170811-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 35,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 1 Mandoto MG-UPNNC-173702-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 40,258.41 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra lot 6 Vohibato MG-UPNNC-181752-CS-CDS / Consultant chargé du renfo Scale up coverage and utiliz rcement du système de soin IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 980,000.00 1,046,548.00 Signed 2020-09-01 2020-12-08 2020-09-15 2021-01-14 2020-10-20 2020-04-25 2022-04-13 2022-04-20 s de santé primaires à base m package communautaire à travers de s études et des recherches o pérationnelles MG-UPNNC-185994-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 815,000.00 31,208.05 Signed 2020-09-01 2020-03-21 2020-09-22 2020-06-10 2020-11-12 2020-07-07 2022-05-06 communautaires et voucher minimum package s dans la région Amoron'i M ania, dont 4 Districts réparti s en 25 lots Page 12 MG-UPNNC-185995-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 830,000.00 26,466.97 Signed 2020-09-01 2020-03-21 2020-09-22 2020-06-10 2020-10-20 2020-07-07 2020-12-13 communautaires et voucher minimum package s dans la région Haute Matsi atra, dont 07 districts réparti s en 25 lots MG-UPNNC-185996-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 930,000.00 23,763.36 Signed 2020-09-01 2020-03-16 2020-09-22 2020-06-10 2020-10-20 2020-07-14 2022-04-13 communautaires et voucher minimum package s dans la région Vakinakarat ra, dont 07 Districts répartis en 30 lots MG-UPNNC-185997-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man Under Implement du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 570,000.00 0.00 2020-09-01 2020-03-21 2020-09-22 2020-10-20 2022-04-13 ation communautaires et voucher minimum package s dans la région Itasy, dont 03 Districts répartis en 20 lo ts MG-UPNNC-199559-CS-CDS / Migration en version Web d Project Management, Capac u logiciel TOP2PRO et renfor IDA / D2570 ity Building and Operations Post Direct Selection Direct 45,000.00 37,750.48 Signed 2020-11-09 2020-09-28 2020-11-23 2021-08-12 2020-12-14 2021-10-16 2021-01-13 cement de capacités de l'éq Support uipe fiduciaire de l'UPNNC, O NN et des ORN sur l'utilisatio n du logiciel comptable TOM 2PRO MG-UPNNC-201768-CS-CDS / Consultant chargé de la co Scale up coverage and utiliz nception, développement et Under Implement IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 230,000.00 0.00 2020-12-15 2020-11-11 2020-12-29 2020-11-17 2021-02-09 2022-08-03 préparation à l'implémentati ation m package on des activités de stimulati on précoce des jeunes enfan ts (ECD) PARN UPNNC 1 4 STIMULATI Strengthen capacity to man ON PRECOCE / Groupe de six Individual Consult IDA / D2570 age and deliver the RMCHN Post Direct 100,000.00 0.00 Canceled 2018-05-04 2018-03-08 2018-05-18 2018-06-15 2018-06-29 2019-12-31 (06) consultants individuels ant Selection minimum package chargé de la stimulation pré coce des enfants MG-UPNNC-203412-CS-IND Project Management, Capac Individual Consult Under Implement V / Recrutement d'un(e) Assi IDA / D2570 ity Building and Operations Post Open 4,800.00 0.00 2020-11-12 2020-08-17 2020-12-23 2021-01-13 2021-01-28 2021-07-27 ant Selection ation stant (e) en Passation de Ma Support rchés de l'UPNNC MG-UPNNC-201808-CS-CDS / Consultant chargé de l’app Scale up coverage and utiliz ui technique à l’intégration d Under Implement IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 220,000.00 0.00 2020-12-21 2020-12-16 2021-01-04 2021-02-01 2022-07-26 e l’Approche Human Centere ation m package d Design dans le cadre du Pr ojet FAFY ainsi que la prépar ation de la mise à l’échelle MG-UPNNC-204559-CS-IND Strengthen capacity to man Individual Consult Under Implement V / 65 Consultants Animateu IDA / D2570 age and deliver the RMCHN Post Open 100,000.00 0.00 2020-11-12 2020-10-15 2020-12-20 2020-12-27 2021-01-17 2022-07-11 ant Selection ation rs encadreurs dans la région minimum package VV7V MG-UPNNC-204566-CS-IND Strengthen capacity to man Individual Consult Under Implement V / 16 Consultant Technicien IDA / D2570 age and deliver the RMCHN Post Open 100,000.00 0.00 2020-11-12 2020-10-15 2020-12-20 2020-12-27 2021-01-17 2022-07-11 ant Selection ation s Superviseurs dans la régio minimum package n VV7V MG-UPNNC-214558-CS-CDS Scale up coverage and utiliz / Recrutement d’une firme p IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 240,000.00 277,945.50 Signed 2020-12-23 2020-12-23 2021-01-06 2021-01-12 2021-01-27 2021-04-21 2022-01-27 our la mise à jour du systèm m package e de collecte de données Nu trition/Santé MG-UPNNC-223763-CS-CDS / Consultant chargé de l'app Scale up coverage and utiliz ui technique à l'intégration d IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 106,000.00 67,785.67 Signed 2021-05-03 2021-04-21 2021-05-24 2021-05-19 2021-06-14 2021-10-20 2022-06-14 e l'approche Human Centere m package d Design dans le cadre du pr ojet FAFY (HDA) MG-UPNNC-231573-CS-CDS Scale up coverage and utiliz / Consultant chargé de l'élab IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 730,000.00 624,271.00 Signed 2021-05-03 2021-05-03 2021-05-24 2021-05-15 2021-06-14 2021-05-25 2022-04-11 oration et de la mise en œuv m package re de la stratégie du change ment social. MG-UPNNC-233819-CS-CDS / Sélection de consultant en charge du suivi de la mise e Strengthen capacity to man n place de la plateforme co IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 9,000.00 9,807.14 Signed 2021-05-18 2021-05-25 2021-05-22 2021-06-01 2021-06-03 2021-05-08 2021-11-30 mmunautaire et du démarra minimum package ge effectif des activités dans les régions d’Alaotra Mangor o, d’Analamanga et de Vato vavy Fito Vignany MG-UPNNC-235501-CS-IND V / Sélection de Consultant e Project Management, Capac n charge du Pilotage, de la p Individual Consult Under Implement IDA / D2570 ity Building and Operations Post Direct 1,500.00 0.00 2021-05-27 2021-05-25 2021-06-08 2021-06-01 2021-06-29 2021-06-30 2021-07-14 2022-05-14 réparation de la Mise à l’éch ant Selection ation Support elle des interventions de Sti mulation Précoce des Jeunes Enfants MG-UPNNC-247277-CS-CDS / ONG/Partenaires chargées Scale up coverage and utiliz du fonctionnement des sites Under Implement IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 46,755.00 0.00 2021-10-21 2021-11-12 2021-12-03 2023-05-27 communautaires et voucher ation m package s dans la région Bongolava_ lot 1 et lot 10_Districts Tsiro anomandidy MG-UPNNC-247279-CS-CDS / ONG/Partenaires chargées Scale up coverage and utiliz du fonctionnement des sites Under Implement IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 96,208.00 0.00 2021-10-21 2021-11-25 2021-11-12 2021-12-10 2023-06-03 communautaires et voucher ation m package s dans la région Bongolava_l ot 3,lot 4, lot 5 et lot 9_Distri ct Tsiroanomandidy MG-UPNNC-254524-CS-IND Project Management, Capac Individual Consult Under Implement V / Sélection d'un Supervise IDA / D2570 ity Building and Operations Post Open 10,000.00 0.00 2021-10-12 2021-10-11 2021-11-14 2021-12-05 2022-01-09 2022-07-08 ant Selection ation ur Régional au sein de l'UPN Support NC MG-UPNNC-247281-CS-CDS / ONG/Partenaires chargées Scale up coverage and utiliz du fonctionnement des sites Under Implement IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 44,633.00 0.00 2021-10-21 2021-10-29 2021-11-19 2023-05-13 communautaires et voucher ation m package s dans la région Bogolava_lo t 6, lot 7_District Tsiroanoma ndidy MG-UPNNC-258108-CS-IND Project Management, Capac Individual Consult Under Implement V / Recrutement d'un Consul IDA / D2570 ity Building and Operations Post Open 12,000.00 0.00 2021-10-26 2021-10-14 2021-11-23 2021-12-14 2022-01-18 2022-07-17 ant Selection ation tant Spécialiste en Nutrition Support MG-UPNNC-261440-CS-IND Project Management, Capac Individual Consult Under Implement V / Recrutement d'un(e) Assi IDA / D2570 ity Building and Operations Post 10,000.00 0.00 2021-11-25 2021-11-17 2021-12-23 2022-01-13 2022-02-03 2023-02-03 ant Selection ation stant(e) de Programme (AP) Support à l’U-PNNC. MG-UPNNC-170722-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 39,000.00 0.00 Canceled 2020-09-01 2020-10-08 2020-12-21 2022-06-14 communautaires et voucher minimum package s dans la région Amoron'i M ANIA, dont 4 districts réparti s en 25 lots. Page 13 MG-UPNNC-267250-CS-CDS / Recrutement de 30 ONG/Pa rtenaires chargés du fonctio Scale up coverage and utiliz Pending Impleme nnement des sites commun IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 300,000.00 0.00 2022-02-28 2022-03-21 2022-04-04 2022-10-31 ntation autaires dans la Région Amo m package ron'i Mania_Districts Ambosi tra, Manandriana et Ambatof inandrahina, Fandriana MG-UPNNC-265257-CS-CDS / Recrutement 6 ONG/Parten Scale up coverage and utiliz aire chargé du fonctionneme Pending Impleme IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 85,400.00 0.00 2021-12-27 2022-01-15 2022-02-12 2023-01-08 nt des sites communautaires ntation m package dans la région Bongolava__D istricts Tsiroanomandidy et F enoarivobe MG-UPNNC-266386-CS-CDS / Recrutement de 24 ONG/Pa Scale up coverage and utiliz rtenaires chargés du fonctio Pending Impleme IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 295,000.00 0.00 2022-01-17 2022-02-07 2022-03-03 2022-12-28 nnement des sites commun ntation m package autaires de la région Itasy_D istricts Arivonimamo, Miarin arivo et Soavinandriana MG-UPNNC-267020-CS-CDS / Recrutement de 38 ONG/Pa rtenaires chargés du fonctio Scale up coverage and utiliz nnement des sites commun Pending Impleme IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 300,000.00 0.00 2022-04-04 2022-04-25 2022-05-16 2023-02-10 autaires de la région Vakina ntation m package karatra__Districts Ambatola mpy, Antanifotsy, Antsirabe I Antsirabe II, Betafo, Farats iho et Mandoto MG-UPNNC-267054-CS-CDS / Recrutement de 27 ONG/Pa rtenaires chargés du fonctio Scale up coverage and utiliz nnement des sites commun Pending Impleme IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 289,800.00 0.00 2022-04-04 2022-04-25 2022-05-16 2023-02-10 autaires dans la région Haut ntation m package e Matsiatra__District Vohibat o, Ambalavao, Isandra, Lala ngina, Ambohimahasoa, Fia narantsoa I et Ikalamavony MG-UPNNC-295461-CS-IND Project Management, Capac Individual Consult V / Recrutement d'un(e) Assi IDA / D2570 ity Building and Operations Post Open - National 4,800.00 0.00 Canceled 2022-07-26 2022-09-16 2022-09-13 2022-10-04 2022-11-08 2023-05-07 ant Selection stant(e) en Passation de Mar Support ché MG-UPNNC-303654-CS-CDS / Sélection de consultant en charge de l'étude, de la gest Project Management, Capac Under Implement ion, du contrôle et de la surv IDA / D2570 ity Building and Operations Post Direct Selection Direct - National 80,000.00 0.00 2022-08-05 2022-08-11 2022-08-15 2022-08-11 2022-10-19 2023-05-17 ation eillance des travaux de réha Support bilitation (extension et surél évation) d'un bâtiment à usa ge de bureau pour l'UPNNC et l'ONN. MG-UPNNC-303926-CS-IND Project Management, Capac Individual Consult Under Implement V / Recrutement d'un(e) Spé IDA / D2570 ity Building and Operations Post Open - National 6,000.00 0.00 2022-07-27 2023-01-06 2022-09-14 2022-10-05 2022-11-09 2023-07-27 ant Selection ation cialiste en Passation de Marc Support hé MG-UPNNC-303928-CS-IND Project Management, Capac Individual Consult Pending Impleme V / Recrutement d'un Consul IDA / D2570 ity Building and Operations Post Limited 6,000.00 0.00 2022-08-26 2022-08-31 2022-09-21 2022-10-26 2023-04-24 ant Selection ntation tant Conseil Juridique Support MG-UPNNC-316965-CS-IND Project Management, Capac Individual Consult V / Recrutement d'un(e) Assi IDA / D2570 ity Building and Operations Post Open - National 4,800.00 0.00 Signed 2022-10-05 2022-12-04 2022-11-07 2023-04-12 2022-11-28 2023-04-17 2022-12-19 2023-07-31 ant Selection stant(e) en Communication Support UPNNC 1 9 FORMATION EN Project Management, Capac GESTION FINANCIE / Renforc IDA / V0970 ity Building and Operations Post Direct Selection Direct 5,000.00 0.00 Canceled 2018-02-16 2018-02-26 2018-05-02 2018-05-09 ement de capacité en matièr Support e d'audit interne de projets MG-UPNNC-330094-CS-IND Strengthen capacity to man Individual Consult Under Implement V / Consultant Spécialiste en IDA / D2570 age and deliver the RMCHN Post Open - National 5,000.00 0.00 2022-12-21 2023-01-09 2023-02-08 2023-04-14 2023-03-01 2023-04-05 2023-07-31 ant Selection ation Nutrition minimum package MG-UPNNC-330095-CS-IND Strengthen capacity to man Individual Consult Under Implement V / Recrutement de consulta IDA / D2570 age and deliver the RMCHN Post Open - National 6,000.00 0.00 2022-12-21 2023-01-09 2023-02-08 2023-04-18 2023-03-01 2023-06-08 2023-04-05 2023-07-31 ant Selection ation nt en Suivi Evaluation de l'U minimum package PNNC MG-UPNNC-330792-CS-IND Project Management, Capac Individual Consult Under Implement V / Recrutement d'un consul IDA / D2570 ity Building and Operations Prior Open - National 5,200.00 0.00 2023-03-15 2023-05-03 2023-05-03 2023-05-24 2023-06-28 2024-03-24 ant Selection ation tant Gestionnaire de Contrat Support MG-UPNNC-349848-CS-IND Project Management, Capac Individual Consult Under Implement V / Recrutement d'un Assista IDA / D2570 ity Building and Operations Post Open - National 4,500.00 0.00 2023-04-07 2023-04-18 2023-05-17 2023-06-07 2023-07-12 2024-01-08 ant Selection ation nt Audit Interne Support MG-UPNNC-349854-CS-IND Project Management, Capac Individual Consult Under Implement IDA / D2570 Post Open - National 3,500.00 0.00 2023-04-14 2023-04-19 2023-05-24 2023-06-14 2023-07-19 2024-01-15 V / Recrutement d'un(e) Co ity Building and Operations ant Selection ation mptable Support MG-UPNNC-281592-CS-IND Project Management, Capac Individual Consult V / Recrutement d'un Consul IDA / D2570 ity Building and Operations Post Open 3,000.00 0.00 Canceled 2022-04-11 2022-03-10 2022-05-02 2022-05-09 2022-05-30 2022-08-29 ant Selection tant chargé du Data Analyst Support MG-UPNNC-337076-CS-IND Project Management, Capac Individual Consult V / Recrutement Assistant(e) IDA / D2570 ity Building and Operations Post Open - National 6,000.00 0.00 Canceled 2023-03-03 2023-04-21 2023-05-12 2023-06-16 2024-06-15 ant Selection en Passation de Marchés Support Page 14 PROCUREMENT PLAN Project information: Higher Education for Economic Transformation Project P166415 Project Implementation agency: ARU, COSTECH, DUCE, HESLB, MJNUAT,MOCU, MUCE, MUHAS,MUST, MZUMBE, MoEST, OUT, SUA, SUZ, TCU, UDOM, UDSM Date of the Procurement Plan: Sep 28, 2021 Period covered by this Procurement Plan: Oct 2021- Oct 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international and national competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: When approaching the national market, as agreed in the Procurement Plan, the country’s own procurement procedures may be used. These procurement procedures shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti- Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. For national open competitive procurement the requirements as per National Procurement Procedure (5.4) of Bank’s Procurement Regulations will apply Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations –Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not applicable Other Relevant Procurement Information. None PROCUREMENT Tanzania : Higher Education for Economic Transformation Project PLAN General Information Country: Tanzania 2022-10-13 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166415 GPN Date: 2021-11-28 Project Name: Higher Education for Economic Transformation Project Loan / Credit No: IDA / 68870 Tanzania Commission for Universities Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-TCU-312339-GO-RFQ / Su pply and Installation of vario Strengthening the Managem Request for Quota Single Stage - One E Under Imple us ICT Facilities (Server Com IDA / 68870 ent of the Higher Education Post Open - National 100,000.00 0.00 2022-09-30 2022-11-08 2022-11-25 2023-05-24 tions nvelope mentation puter, Desktop Computers, L System aptops, Printers and Photoco pier Machine) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-TCU-350608-CS-CQS / Pr ovision of Consultancy Servic es for Undertaking Environm Strengthening the Managem Consultant Qualifi Under Implement ental Impact Assessment (ES IDA / 68870 ent of the Higher Education Post Open - National 10,323.00 0.00 2023-03-17 2023-04-19 2023-04-07 2023-05-08 2023-05-21 2023-06-20 2023-07-25 2023-10-23 cation Selection ation IA) for Construction of the Pr System oposed TCU Head Quarters O ffice Building on Plot No. 56/4 , Block ''E'' Kisasa ''B'' in Dod oma City TZ-TCU-350606-CS-CQS / Pr ovision of Consultancy Servic Strengthening the Managem es for Design Review and Co Consultant Qualifi IDA / 68870 ent of the Higher Education Post Open - National 253,054.00 0.00 Canceled 2023-03-17 2023-04-19 2023-04-07 2023-05-21 2023-06-20 2023-07-25 2025-01-15 nstruction Supervision of TCU cation Selection System Head Quarters Office Buildin g on Plot No. 56/4 Block ''E'' at Kisasa ''B'' in Dodoma City TZ-TCU-361021-CS-CQS / Pr ovision of Consultancy Servic Strengthening the Managem es for Design Review and Co Consultant Qualifi Under Implement IDA / 68870 ent of the Higher Education Post Open - National 253,054.00 0.00 2023-05-15 2023-05-26 2023-05-21 2023-06-05 2023-06-19 2023-06-25 2023-07-21 2025-12-07 nstruction Supervision of TCU cation Selection ation System Head Quarters Office Buildin g on Plot No. 56/4 Block ''E'' at Kisasa ''B'' in Dodoma City INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 UNITED REPUBLIC OF TANZANIA Procurement Plan General 1. Project Information Country: Tanzania Project Name: Sustainable Rural Water Supply and Sanitation Program Project ID: P163732 2. Project Implementation Agency: Ministry of Water and Irrigation 3. Date of the Procurement Plan: March 5, 2018 4. Period Covered by this Procurement Plan: 18 months I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. III. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in The Public Procurement Act, 2011, The Public 1 Procurement (Amendment) Act, 2016 and the Regulations, 2016, such arrangements shall be subject to paragraph 5.3 and 5.4 of the Procurement Regulations and the following conditions: o There should be no mandatory requirements for inclusion of local experts and firms for the consulting assignments; o There should be no exclusive preference based on threshold prescribed in PPA and its Regulations; o Negotiations with the lowest evaluated bidder to reduce price in the case of goods, works and non-consulting services where competitive methods have been used shall not be allowed; o The fixed budget method shall not be used for goods, works and non- consulting services; o Established and approved procurement standards by the government may be used, provided that they are not restrictive. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. IV. Prequalification: Not Applicable V. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable VI. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable VII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Domestic preference is not applicable for National Open Competitive Procurement VIII. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Not Applicable 2 IX. Other Relevant Procurement Information: Not Applicable 3 X. Threshold for Prior Review, Procurement Approaches and Methods – Good, Works and Non- Consulting Services Procurement Approaches and Methods (US$ millions) Prior Review Category Open Open National Request for (US$ millions) International Quotation (RfQ) Works ≥5 ≥ 15 < 15 ≤ 0.2 Goods, IT, and non-consulting ≥ 1.5 ≥5 <5 ≤ 0.1 services Post Review: All contracts not subject to prior review shall be subject to post review. XI. Thresholds for Prior Review, Selection Approaches and Methods – Consulting Services Category Prior Review Short List of National Consultants (US$ millions) Consulting Engineering and Construction Supervision Services Consultants (Firms) ≥ 0.5 ≤ 0.3 ≤ 0.3 Individual Consultants ≥ 0.2 n.a. n.a. Note: Consultancy services estimated to cost US$ 300,000 and above equivalent per contract shall be advertised in the United Nations Development Business (UNDB) online in addition to advertising in national newspaper(s) of wide circulation and/or regional newspaper. 4 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank- financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub- 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 5 contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 6 Title of the person signing the Letter: 7 PROCUREMENT Tanzania : Sustainable Rural Water Supply and Sanitation Program PLAN General Information Country: Tanzania 2018-08-15 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163732 GPN Date: Project Name: Sustainable Rural Water Supply and Sanitation Program Loan / Credit No: IDA / 62950 Ministry of Water and Irrigation Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MOW-155712-CW-RFB / R ehabilitate and Vertical Exte Single Stage - One E Under Imple 2023-05-0 IDA / 62950 Post Request for Bids Open - National 0.00 2020-02-09 2022-09-19 2020-02-16 2022-09-22 2020-03-08 2022-10-19 2020-03-22 2022-11-12 2020-05-03 nsion for the existing buildin nvelope mentation 1 gs at Water Institute Main C ampus GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MOW-154120-GO-UN / Su UN Agencies (Dire IDA / 62950 Post Direct 248,840.36 Completed 2020-02-02 2020-03-30 2020-02-18 2020-03-30 2020-04-14 2020-07-01 2020-07-13 2021-12-01 pply of four (4) Motor Vehicle ct) s TZ-MOW-154797-GO-RFQ / S Single Stage - One E IDA / 62950 Post Request for Bids Open - National 98,640.09 Completed 2020-02-05 2020-04-06 2020-02-12 2020-04-07 2020-02-26 2020-05-05 2020-03-18 2020-06-16 2020-04-15 2020-09-10 2020-07-14 2021-12-01 UPPLY OF ICT EQUIPMENT nvelope TZ-MOW-154813-GO-RFQ / P rocurement of Water Well Dri Single Stage - One E IDA / 62950 Post Request for Bids Open - National 379,106.26 Signed 2020-02-03 2020-04-06 2020-02-10 2020-04-06 2020-02-24 2020-05-12 2020-03-16 2020-06-03 2020-03-31 2020-10-28 2020-06-29 lling Laboratory Equipment, P nvelope ipe testing equipment and M eter Test Bench TZ-MOW-254422-GO-RFB / P Single Stage - One E IDA / 62950 Post Request for Bids Open - National 0.00 Signed 2022-01-16 2022-01-24 2022-01-21 2022-01-27 2022-02-11 2022-02-25 2022-03-13 2022-04-29 2022-04-17 2022-10-14 rocurement of Video Confere nvelope nce TZ-MOW-305947-GO-RFB / T Single Stage - One E Pending Impl o purchase Fixed Lecture The IDA / 62950 Post Request for Bids Open - National 0.00 2024-04-03 2024-04-08 2024-05-08 2024-05-22 2024-06-26 2024-12-23 nvelope ementation atre Chairs with Writing Tops for WI TZ-MOW-305948-GO-RFB / T Single Stage - One E Pending Impl o purchase furniture and fitti IDA / 62950 Post Request for Bids Open - National 0.00 2023-08-01 2023-08-08 2023-09-17 2023-10-08 2023-11-12 2024-05-10 nvelope ementation ngs for classrooms for WI NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MOW-69883-CS-QCBS / V erification of the Sustainable Quality And Cost- Open - Internationa IDA / 62950 Prior 2,786,067.44 Signed 2018-09-03 2019-01-13 2018-09-24 2019-01-21 2018-11-07 2019-04-26 2018-12-05 2019-07-29 2019-01-04 2019-09-03 2019-02-08 2020-01-16 2019-03-15 2020-04-26 2020-03-14 Rural Water Supply and Sanit Based Selection l ation Program for 2019-2021 TZ-MOW-69879-CS-QCBS / S trategic Program Support Co Quality And Cost- Open - Internationa IDA / 62950 Prior 0.00 Canceled 2018-07-17 2018-09-11 2018-08-07 2018-09-19 2018-09-18 2019-02-11 2018-10-16 2019-06-14 2018-11-15 2020-10-12 2018-12-20 2019-01-24 2020-01-24 nsultant for the Sustainable Based Selection l Rural Water Supply and Sanit ation Program TZ-MOW-130039-CS-CQS / Fi Consultant Qualifi Open - Internationa Pending Impleme eld -level Leadership Develop IDA / 62950 Post 0.00 2019-09-20 2019-10-11 2019-11-24 2019-12-24 2020-01-28 2020-07-26 cation Selection l ntation ment Initiative TZ-MOW-165318-CS-CQS / D esign and Supervision of Con struction of Vertical Extensio Consultant Qualifi n of Buildings Containing Cla IDA / 62950 Post Open - National 155,052.00 Signed 2020-03-25 2020-06-11 2020-04-15 2020-06-25 2020-05-29 2020-09-04 2020-06-28 2020-11-15 2020-08-02 2021-01-27 2021-10-01 cation Selection ssrooms, Lecture Theaters, Li brary, ICT/Computers, Labora tories, Workshops and Admi nistration for the Water Instit ute (WI) TZ-MOW-306185-CS-QCBS / Feasibility Study for the desi Quality And Cost- Open - Internationa Under Implement gn, installation and operation IDA / 62950 Post 0.00 2022-08-10 2022-09-27 2022-08-31 2022-09-28 2022-09-28 2022-11-29 2022-09-30 2023-04-11 2022-10-07 2022-10-30 2022-12-04 2023-12-04 Based Selection l ation of pre-paid water meters in r ural Tanzania under a PPP Sc heme TZ-MOW-306188-CS-QCBS / Provision of consultancy serv ices for MIS data manageme Quality And Cost- Open - Internationa Pending Impleme IDA / 62950 Post 0.00 2022-08-29 2022-09-28 2022-11-02 2022-11-04 2022-11-05 2022-11-28 2023-01-02 2024-01-02 nt for linkage of NSMIS and B Based Selection l ntation EMIS to RSDMS central and Fi n-Tech APP for Communicatio n interchangeability - Phase I I. TZ-MOW-362155-CS-QCBS / Provision of Consultancy Serv ices for FS and DD and prepa ration of tender documents f Quality And Cost- Open - Internationa Pending Impleme IDA / 62950 Post 0.00 2023-07-01 2023-07-22 2023-09-04 2023-10-02 2023-11-01 2023-12-06 2024-01-10 2025-01-09 or FSM facilities, Climate resil Based Selection l ntation ient infrastructures, Solar/hy brid pumping rural for water and sanitation projects includ ing asset management Page 1 TZ-MOW-199787-CS-QCBS / Strategic Program Support C Quality And Cost- Open - Internationa IDA / 62950 Prior 0.00 Canceled 2020-10-28 2020-12-24 2020-11-18 2021-01-07 2021-01-01 2021-11-08 2021-01-29 2021-09-23 2021-02-28 2022-04-25 2021-04-04 2021-05-09 2024-05-08 onsultant For the Sustainabl Based Selection l e Rural Water Supply and Sa nitation Program INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MOW-69881-CS-CDS / Fie ld-level Leadership Develop IDA / 62950 Post Direct Selection Direct 0.00 Canceled 2018-07-17 2018-07-27 2018-09-20 2019-03-19 ment Initiative TZ-MOW-191418-CS-CDS / P rogram Management Consult ant for the sustainable Rural IDA / 62950 Post Direct Selection Direct 126,000.00 Signed 2020-09-04 2020-09-30 2020-09-14 2020-11-24 2020-11-18 2021-04-15 2021-11-13 Water Supply and Sanitation Program (SRWS) (Individual Consultant) TZ-MOW-306191-CS-INDV / Provision of consultancy serv ices for FS and operationaliza tion of technical support cent Individual Consult Open - Internationa Pending Impleme IDA / 62950 Prior 0.00 2022-08-26 2022-10-05 2022-10-26 2022-11-30 2023-05-29 er for PPP and TA shops for g ant Selection l ntation oods and services to CBWSO s for sustaining WPs function ality and strengthening O&M of to Rural water schemes TZ-MOW-306192-CS-INDV / Procurement of Consultant t o be based at RUWASA to co nduct assessment of O&M ca Individual Consult Open - Internationa Pending Impleme pacity, develop strategy with IDA / 62950 Prior 0.00 2023-08-16 2023-09-25 2023-10-16 2023-11-20 2024-05-18 ant Selection l ntation RUWASA for Service delivery guidelines, Capacity Building Guidelines, Operation and Ma intenance Guidelines, and Re gulation Guide Page 2 PROCUREMENT PLAN for SURP II General 1. Project Information Country: Federal Republic of Somalia Project Name: Somali Urban Resilience Project (SURP) Phase II Project Number: P170922 Total Finance: USD 112,000,000 2. Project Implementation Agencies: Ministry of Public Works, Benadir Regional Administration (BRA), Garowe Municipality, Kismayo Municipality, Baidoa Municipality 3. Date of Project Plan: October 2019 4. Period Covered by this Procurement: May 2020 to December 2021 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Document: The Bank’s standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified into Procurement Plan tables in STEP III. National Procurement Arrangements: Not applicable IV. Prequalification: Not applicable V. Leased Assets: Not Applicable VI. Procurement of Second hand Goods: Not Applicable 1 VII. Domestic Preference: Not Applicable VIII. Hands on Expanded Implementation Support (HEIS): Not Applicable IX. Other Relevant Procurement Information: Not Applicable X. Thresholds for Procurement Approaches and Method (US$ millions) Thresholds for Procurement Approaches and Methods (US$ millions)– Goods, Works, and Non-Consulting Services Category Prior Open Open Request for Review Internation National Quotation (US$ al (RfQ) millions) Works All ≥ 5.0 < 5.0 ≤ 0.2 Goods, IT, and all ≥ 0.5 < 0.5 ≤ 0.1 non-consulting services Thresholds for Procurement Approaches and Methods (US$, millions) – Consulting Services Category Prior Short List of National Consultants Review Consulting Services Engineering and (US$, Construction millions) Supervision Consultants all ≤ 0.1 ≤ 0.2 (Firms) Individual all n.a. n.a. Consultants 2 1) Baidoa Municipality Sr. Contract Estima Rev Marke Sele Evalua Procure Prequalifi Domes Expec Expected No Description ted iew t ctio tion ment cation tic ted date of Cost by Appro n Optio Process (Yes/ No) Prefer date Contract (US$) Ban ach Met ns (Single ence of bid/ Signatur k (Open- hod (BAFO stage- (Yes/N propo e (Pri Nation (RFP , single o) sal or/ al/ , Rated envelop openi Pos Limite RFB, Criteri e etc.) ng t) d etc.) RFQ a etc.) etc.) GOODS Procurement Lowest Single of Three 4WD Shoppi Evaluat stage 05/05/ 06/07/202 G1 80,000. Prior RFQ N/A N/A motor Vehicle ng ed One- 2020 0 00 pick ups Cost Envelop Survey and Lowest Single Laboratory 20,000. Shoppi Evaluat stage 07/07/ 09/09/202 G2 Prior RFQ N/A N/A equipment 00 ng ed One- 2020 0 Cost Envelop Hired vehicles for a period Lowest Single of time before 30,000. Shoppi Evaluat stage 04/07/ 31/12/202 G3 Prior RFQ N/A N/A the new 00 ng ed One- 2020 0 vehicles are Cost Envelop delivered Total Goods WORKS Construction of section Lowest Single Open 3,000,00 Evaluat stage 20/04/ 01/05/202 of Ali Prior Nation RFB N/A N/A W1 0 ed One- 2020 0 Amhar al Cost Envelop Road in 3 Baidoa Construction of Section Lowest Single Open of 30 KA 4,000,00 Evaluat stage 20/04/ 01/05/202 W2 Prior Nation RFB N/A N/A Road in 0 ed One- 2020 0 al Baidoa Cost Envelop Construction Lowest Single of Section Open 4,000,00 Evaluat stage 20/04/ 01/05/202 W3 of Hospital Prior Nation RFB N/A N/A 0 ed One- 2020 0 Road in al Cost Envelop Baidoa Lowest Construction 60.000.0 Shoppi Evaluat 01/03/20 01/04/202 01/06/ 01/08/202 W4 of RFQ N/A 0 Prior ng ed 20 0 2020 0 Laboratory Cost Total 12,070, Works 000 Non -Consulting Services – Not applicable Consulting Services Sr No. Contract Estimated Review Market Selection Shortlisti Expected Expected Descripti Cost by Bank Approach Method ng Date of Date of on (Prior/P (Open- (QCBS, (Yes/No) Bid Contract ost) National/ LCBCS, QBS, Proposal Signatur Limited etc.) DS Opening e Engineerin g 02/10/202 supervisio 1,500,000.00 Prior Open National QCBS N/A 01/11/2019 C1 1 n of Urban Roads M&E 02/02/202 C2 Survey 750,000.00 Prior Open National QCBS N/A 01/03/2020 1 (Base line, 4 Mid and Impact Control) Project 01/10/202 Direct C3 Coordinato 66,000.00 Prior CDS N/A 01/07/2020 1 Selection r Procureme 01/10/202 Direct C4 nt 46,000.00 Prior CDS N/A 01/07/2020 1 Selection Specialist Financial 01/10/202 Managem Direct 01/07/202 1 C5 46,000.00 Prior CDS N/A ent Selection 0 Specialist 01/10/202 Project Direct C6 Prior CDS N/A 01/07/2020 1 Engineer Selection 48,000.00 Social/Envi 01/10/202 Direct C7 ronmental 61,200.00 Prior CDS N/A 01/07/2020 1 Selection Specialist M&E 01/10/202 C8 42,000.00 Prior Open National INDV N/A 01/03/2020 Specialist 1 Communit 01/10/202 y Direct 1 C9 30,000.00 Prior CDS N/A 01/03/2020 Mobilizatio Selection n Officer Female 01/10/202 Communit 1 C10 y 30,000.00 Prior Open National INDV N/A 01/03/2020 Mobilizatio n Officer Total 2,619,200.0 Consultin 0 g Services Grand 14,926,200. Total 00 5 6 PROCUREMENT Somalia : Somalia Urban Resilience Project II PLAN General Information Country: Somalia 2020-11-13 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P170922 GPN Date: Project Name: Somalia Urban Resilience Project II Loan / Credit No: IDA / D5310, TF / B1519 Beledweyne Municipality Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-BW-265896-GO-RFQ / Pr ocurement of Office Equipme Project Management and Ca Request for Quota Single Stage - One E IDA / D5310 Prior Limited 13,300.00 12,810.00 Signed 2021-12-09 2021-12-09 2022-02-03 2022-02-03 2022-08-02 nt (Laptops, Projector and Pri pacity Building tions nvelope nter) for Beledweyn PIU SO-BW-359893-GO-RFQ / Pr Project Management and Ca Request for Quota Single Stage - One E Under Imple ocurement of new vehicle for TF / B1519 Prior Limited 50,000.00 0.00 2023-06-03 2023-07-29 2024-01-25 pacity Building tions nvelope mentation Beledweyn PIU SO-BW-359699-GO-RFQ / Pr ocurement of Office Furniture Project Management and Ca Request for Quota Single Stage - One E Under Imple (Office Desks, Office Chairs, TF / B1519 Prior Limited 11,900.00 0.00 2023-06-03 2023-07-29 2024-01-25 pacity Building tions nvelope mentation Meeting Table, Meeting Chair s, Filling Cabinet, Plastic Chai rs and Fridge) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-BW-360146-NC-RFQ / Off Project Management and Ca Request for Quota Single Stage - One E Under Imple TF / B1519 Prior Limited 10,500.00 0.00 2023-06-03 2023-07-29 2024-01-25 ice rent for Beledweyn PIU fo pacity Building tions nvelope mentation r 7 Months CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-BW-324122-CS-CQS / Pre paration of Detailed Engineer Urban Infrastructure and Ser Consultant Qualifi Under Implement ing Designs and Bidding Doc IDA / D5310 Prior Limited 50,000.00 0.00 2022-11-02 2023-01-09 2022-11-16 2023-03-28 2022-12-16 2023-01-20 2023-07-19 vices cation Selection ation uments for Beledweyn PIU Of fice Block and Laboratory INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-BW-204509-CS-INDV / PI Project Management and Ca Individual Consult IDA / D5310 Prior Open 54,000.00 0.00 Canceled 2020-11-16 2020-11-17 2021-01-04 2021-01-25 2021-03-01 2021-08-28 U Coordinator for Hirshabelle pacity Building ant Selection FMS SO-BW-204539-CS-INDV / En Project Management and Ca Individual Consult vironmental and Social Safeg IDA / D5310 Prior Open 51,000.00 0.00 Canceled 2020-11-16 2020-11-17 2021-01-04 2021-01-25 2021-03-01 2021-08-28 pacity Building ant Selection uards Specialist for Hirshabel le FMS SO-BW-204540-CS-INDV / Pr Project Management and Ca Individual Consult ocurement Specialist for Hirs IDA / D5310 Prior Open 42,000.00 0.00 Canceled 2020-11-17 2020-11-17 2021-01-05 2021-01-26 2021-03-02 2021-08-29 pacity Building ant Selection habelle FMS SO-BW-204542-CS-INDV / Fi Project Management and Ca Individual Consult nancial Management Speciali IDA / D5310 Prior Open 42,000.00 0.00 Canceled 2020-11-16 2020-11-17 2021-01-04 2021-01-25 2021-03-01 2021-08-28 pacity Building ant Selection st for Hirshabelle FMS SO-BW-204544-CS-INDV / Pr Project Management and Ca Individual Consult IDA / D5310 Prior Open 42,000.00 0.00 Canceled 2020-11-17 2020-11-17 2021-01-05 2021-01-26 2021-03-02 2021-08-29 oject Engineer for Hirshabelle pacity Building ant Selection FMS SO-BW-204609-CS-INDV / M Urban Infrastructure and Ser Individual Consult onitoring and Evaluation (M IDA / D5310 Prior Open 42,000.00 0.00 Canceled 2020-11-18 2020-11-17 2021-01-06 2021-01-27 2021-03-03 2021-08-30 vices ant Selection & E) Specialist for Hirshabelle FMS SO-BW-205268-CS-INDV / Pr Project Management and Ca Individual Consult IDA / D5310 Prior Open 54,000.00 140,400.00 Under Review 2020-11-21 2020-11-19 2021-01-09 2021-05-05 2021-01-30 2021-05-11 2021-03-06 2021-06-01 2021-09-02 oject Coordinator for Beledw pacity Building ant Selection eyne PIU SO-BW-205271-CS-INDV / En vironmental and Social Safeg Project Management and Ca Individual Consult IDA / D5310 Prior Open 50,400.00 92,160.00 Under Review 2020-11-21 2020-11-19 2021-01-09 2021-05-05 2021-01-30 2021-05-10 2021-03-06 2021-06-07 2021-09-02 uards (E&SS) Specialist for B pacity Building ant Selection eledweyne PIU. SO-BW-205273-CS-INDV / Fi Project Management and Ca Individual Consult nancial Management Speciali IDA / D5310 Prior Open 42,000.00 96,000.00 Signed 2020-11-21 2020-11-19 2021-01-09 2021-05-05 2021-01-30 2021-09-08 2021-03-06 2021-09-22 2021-09-02 pacity Building ant Selection st for Beledweyne PIU SO-BW-205275-CS-INDV / Pr Project Management and Ca Individual Consult ocurement Specialist for Bele IDA / D5310 Prior Open 42,000.00 92,160.00 Under Review 2020-11-21 2020-11-19 2021-01-09 2021-05-05 2021-01-30 2021-05-10 2021-03-06 2021-06-06 2021-09-02 pacity Building ant Selection dweyne PIU Page 1 SO-BW-205278-CS-INDV / M Project Management and Ca Individual Consult onitoring and Evaluation (M& IDA / D5310 Prior Open 42,000.00 92,160.00 Under Review 2020-11-21 2020-11-19 2021-01-09 2021-05-05 2021-01-30 2021-05-10 2021-03-06 2021-06-09 2021-09-02 pacity Building ant Selection E) Specialist for Beledweyne PIU SO-BW-205270-CS-INDV / Pr Project Management and Ca Individual Consult IDA / D5310 Post Open 42,000.00 0.00 Canceled 2020-11-21 2020-11-19 2021-01-09 2021-01-30 2021-03-06 2021-09-02 oject Engineer for Beledweyn pacity Building ant Selection e PIU SO-BW-276043-CS-INDV / Pr Project Management and Ca Individual Consult Under Implement IDA / D5310 Prior Open 46,080.00 0.00 2022-02-06 2022-12-20 2022-03-27 2022-04-17 2022-05-22 2022-11-18 oject Engineer for Beledweyn pacity Building ant Selection ation e PIU Page 2 Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: February 1,2017]: Revision 1 of Updated Procurement Plan, June 21,2017] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 4. Reference to (if any) Project Operational/Procurement Manual: Project Operations Manual for World Bank Loan Project P158099 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] July 9, 2010 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contrac (Works) t for Prior Review Summary 1.86 4 No Post 1st of the NCB contrac (Goods) t for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 110,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. July 9, 2010 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Pakistan : PK: Punjab Tourism for Economic Growth Project PLAN General Information Country: Pakistan 2017-12-21 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P158099 GPN Date: 2020-08-11 Project Name: PK: Punjab Tourism for Economic Growth Project Loan / Credit No: IDA / 59820 Punjab Tourism for Economic Growth Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PK-PTEG-40086-CW-RFB / Fa 3. Public Investment Facilit Open - Internationa Single Stage - One E 11,386,666.0 2021-09-3 IDA / 59820 Prior Request for Bids 0.00 Canceled 2018-08-31 2018-09-05 2018-10-17 2018-11-01 2018-11-22 cilities & Amenities up-gradat y l nvelope 0 0 ion at sites PK-PTEG-40077-CW-RFB / Da 3. Public Investment Facilit Single Stage - One E 2019-04-1 rbar sahib road Kartarpur - R IDA / 59820 Prior Request for Bids Open - National 588,219.00 0.00 Canceled 2018-08-06 2018-08-11 2018-09-22 2018-10-07 2018-10-21 y nvelope 9 ehabilitation of secondary & t ertiary roads PK-PTEG-40079-CW-RFB / Ta 3. Public Investment Facilit Single Stage - One E 2019-04-2 xila- Toap Mankila- Mohra - R IDA / 59820 Post Request for Bids Open - National 1,437,133.00 0.00 Canceled 2018-08-13 2018-08-18 2018-09-29 2018-10-14 2018-10-28 y nvelope 6 ehabilitation of roads PK-PTEG-40080-CW-RFB / Na 3. Public Investment Facilit Open - Internationa Single Stage - One E 2019-03-2 nkana Sahib-Farooqabad roa IDA / 59820 Post Request for Bids 5,262,066.00 0.00 Canceled 2018-07-16 2018-07-21 2018-09-01 2018-09-16 2018-09-30 y l nvelope 9 d - Rehabilitation of road PK-PTEG-40081-CW-RFB / E 3. Public Investment Facilit Single Stage - One E 2018-12-1 minabad - Rori roads - Rehab IDA / 59820 Post Request for Bids Open - National 399,228.00 0.00 Canceled 2018-04-04 2018-04-09 2018-05-21 2018-06-05 2018-06-19 y nvelope 6 ilitation of roads PK-PTEG-40084-CW-RFB / Uc 3. Public Investment Facilit Single Stage - One E 2019-04-1 IDA / 59820 Post Request for Bids Open - National 1,199,457.00 0.00 Canceled 2018-08-06 2018-08-11 2018-09-20 2018-10-04 2018-10-18 h Sharif road - Rehabilitation y nvelope 6 of roads PK-PTEG-40085-CW-RFB / Gh 3. Public Investment Facilit Single Stage - One E 2019-03-2 ulam Farid Mithan Kot Rajanp IDA / 59820 Post Request for Bids Open - National 1,024,428.00 0.00 Canceled 2018-07-09 2018-07-14 2018-08-25 2018-09-09 2018-09-23 y nvelope 2 ur - Rehabilitation of roads PK-PTEG-194132-CW-RFB / R 3. Public Investment Facilit Single Stage - One E 4,346,514.4 2021-11-2 oads Rehabilitation in Punjab IDA / 59820 Post Request for Bids Open - National 6,000,000.00 Signed 2020-09-16 2020-09-17 2020-09-18 2020-09-17 2020-10-20 2020-10-20 2020-10-30 2020-11-10 2020-11-20 2020-12-10 y nvelope 3 0 (4 Packages, 6 Roads) PK-PTEG-238517-CW-RFB / R 3. Public Investment Facilit Single Stage - One E Other (with field f Under Imple 2022-08-1 ehabilitation of Roads - Uch S IDA / 59820 Post Request for Bids Open - National 3,300,000.00 0.00 2021-06-08 2021-06-30 2021-06-10 2021-07-14 2021-07-10 2021-08-03 2021-07-25 2021-08-22 y nvelope or explanation) mentation 7 harif & Channan Pir PK-PTEG-269512-CW-RFQ / T Request for Quota 3. Public Investment Facilit Request for Quota Single Stage - One E 2022-08-0 axila Museum - Design & Con IDA / 59820 Post Open - National tions (Non Bank-S 95,000.00 20,833.57 Signed 2021-12-31 2022-03-25 2022-02-04 2022-04-27 y tions nvelope 3 struction of Entrance Gate PD) Request for Bids - PK-PTEG-279723-CW-RFB / C 3. Public Investment Facilit Single Stage - One E Small Works SPD 2023-04-2 onstruction/Rehabilitation of IDA / 59820 Post Request for Bids Open - National 1,950,000.00 0.00 Canceled 2022-02-22 2022-03-25 2022-02-27 2022-03-29 2022-03-29 2022-04-13 2022-04-27 y nvelope (2 envelope proce 2 Toilet facilities at Heritage & ss) Tourist Sites Request for Bids - PK-PTEG-314721-CW-RFB / C 3. Public Investment Facilit Single Stage - One E Small Works SPD 2023-11-1 onstruction/Rehabilitation of IDA / 59820 Post Request for Bids Open - National 1,950,000.00 0.00 Canceled 2022-09-19 2022-09-24 2022-10-24 2022-11-08 2022-11-22 y nvelope (1 envelope proce 7 Toilet Blocks at Tourist sites - ss) Punjab PK-PTEG-330987-CW-RFB / R ehabilitation / Improvement 3. Public Investment Facilit Single Stage - One E Other (with field f Under Imple 2024-02-1 of Metaled Road from Lahore IDA / 59820 Post Request for Bids Open - National 1,000,000.00 0.00 2022-12-12 2023-02-20 2022-12-12 2023-02-24 2023-01-16 2023-03-27 2023-01-26 2023-04-12 2023-02-19 y nvelope or explanation) mentation 9 -Sheikhupura-Sargodha Road to Gurdwara Sucha Soda Dist rict Sheikhupura. PK-PTEG-331277-CW-RFB / R ehabilitation / Improvement 3. Public Investment Facilit Single Stage - One E Other (with field f 2024-02-1 of Metalled Road from Lahore IDA / 59820 Post Request for Bids Open - National 950,000.00 0.00 Canceled 2022-12-12 2023-02-20 2022-12-12 2023-02-24 2023-01-16 2023-01-26 2023-02-19 y nvelope or explanation) 9 -Sheikhupura-Sargodha Road to Mariumabad (Right Side of canal) District Sheikhupura PK-PTEG-331281-CW-RFB / R ehabilitation / Improvement 3. Public Investment Facilit Single Stage - One E Other (with field f 2024-08-1 IDA / 59820 Post Request for Bids Open - National 8,250,000.00 0.00 Signed 2022-12-12 2023-02-20 2022-12-12 2023-02-24 2023-01-16 2023-03-27 2023-01-26 2023-04-10 2023-02-19 of Road from Kallar Kahar to y nvelope or explanation) 7 Manara District Boundary Ch akwal District Chakwal PK-PTEG-331284-CW-RFB / C 3. Public Investment Facilit Single Stage - One E Other (with field f Pending Imp 2024-08-1 onstruction of Rohtas Fort By IDA / 59820 Post Request for Bids Open - National 8,700,000.00 0.00 2022-12-12 2022-12-12 2023-01-16 2023-01-26 2023-02-19 y nvelope or explanation) lementation 7 pass Road District Jhelum. Request for Bids - PK-PTEG-333401-CW-RFB / C 3. Public Investment Facilit Single Stage - One E Small Works SPD Under Imple 2024-03-1 onstruction/Rehabilitation of IDA / 59820 Post Request for Bids Open - National 1,950,000.00 0.00 2022-12-23 2023-03-20 2022-12-28 2023-04-02 2023-02-01 2023-02-11 2023-03-19 y nvelope (1 envelope proce mentation 8 Toilet Blocks at Tourist sites - ss) Punjab Request for Bids - PK-PTEG-360704-CW-RFB / C 2. Private Investment and Single Stage - One E Small Works SPD Under Imple 2024-07-1 onservation & Rehabilitation IDA / 59820 Post Request for Bids Open - National 610,000.00 0.00 2023-05-09 2023-05-17 2023-05-09 2023-05-17 2023-06-03 2023-06-10 2023-06-22 Entrepreneurship Promotion nvelope (1 envelope proce mentation 5 of Buildings/Façade Work on ss) West Side Request for Bids - PK-PTEG-360710-CW-RFB / C 2. Private Investment and Single Stage - One E Small Works SPD Under Imple 2024-07-1 onservation & Rehabilitation IDA / 59820 Post Request for Bids Open - National 780,000.00 0.00 2023-05-09 2023-05-17 2023-05-09 2023-05-17 2023-06-03 2023-06-10 2023-06-22 Entrepreneurship Promotion nvelope (1 envelope proce mentation 5 of Buildings/Façade Work on ss) East Side-1 Request for Bids - PK-PTEG-360711-CW-RFB / C 2. Private Investment and Single Stage - One E Small Works SPD Under Imple 2024-07-1 onservation & Rehabilitation IDA / 59820 Post Request for Bids Open - National 780,000.00 0.00 2023-05-09 2023-05-17 2023-05-09 2023-05-17 2023-06-03 2023-06-10 2023-06-22 Entrepreneurship Promotion nvelope (1 envelope proce mentation 5 of Buildings/Façade Work On ss) East Side-2 PK-PTEG-360715-CW-RFB / C Request for Bids - onservation of Bhatti Gate: 2. Private Investment and Single Stage - One E Small Works SPD Under Imple 2024-07-1 Façade Rehabilitation of Main IDA / 59820 Post Request for Bids Open - National 545,000.00 0.00 2023-05-09 2023-05-17 2023-05-09 2023-05-17 2023-06-03 2023-06-10 2023-06-22 Entrepreneurship Promotion nvelope (1 envelope proce mentation 5 Trail, Relocation of Water Filt ss) ration Plant and Establishme nt of Parking Area Page 1 PK-PTEG-363215-CW-RFB / R ehabilitation / Improvement of Metaled Road from Lahore 2. Private Investment and Single Stage - One E Other (with field f Pending Imp 2024-07-1 IDA / 59820 Post Request for Bids Open - National 950,000.00 0.00 2023-05-23 2023-05-25 2023-06-15 2023-06-25 2023-07-15 -Sheikhupura-Sargodha Road Entrepreneurship Promotion nvelope or explanation) lementation 4 to Mariumabad Length 4.10K M (Right Side of canal) Distri ct Sheikhupura GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PTEG-32430-GO-RFQ / Ve 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 40,000.00 0.00 Canceled 2018-02-05 2018-04-02 2018-09-29 hicles Procurement onitoring and Evaluation tions nvelope PK-PTEG-32431-GO-RFQ / Of 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 58,650.00 23,294.21 Signed 2018-02-04 2018-04-01 2018-05-18 2018-09-28 fice Furniture onitoring and Evaluation tions nvelope PK-PTEG-40059-GO-RFQ / Po 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 9,600.00 6,930.48 Signed 2018-03-03 2018-04-28 2018-06-01 2018-10-25 wer Generator onitoring and Evaluation tions nvelope PK-PTEG-40060-GO-RFQ / Of fice Equipment 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 17,000.00 5,280.80 Signed 2018-01-13 2018-06-30 2018-03-10 2018-06-01 2018-09-06 (Telephone Exchange, CCTV, onitoring and Evaluation tions nvelope Air conditioners, refrigerators etc.) PK-PTEG-40065-GO-RFQ / M 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 600.00 0.00 Canceled 2018-01-24 2018-03-21 2018-09-17 otor Bike onitoring and Evaluation tions nvelope PK-PTEG-40054-GO-RFQ / IT Equipment 4. Project Management, M Request for Quota Single Stage - One E (Laptops, Desktops, Server, P IDA / 59820 Post Open - National 39,000.00 22,115.80 Signed 2017-12-30 2018-02-14 2018-02-24 2018-06-01 2018-08-23 onitoring and Evaluation tions nvelope rinters, Scanner, Multimedia Projector etc.) PK-PTEG-40058-GO-RFQ / Ne 4. Project Management, M Request for Quota Single Stage - One E tworking for IT connectivity & IDA / 59820 Post Open - National 7,000.00 2,693.07 Signed 2018-02-25 2018-04-22 2018-06-01 2018-10-19 onitoring and Evaluation tions nvelope Telephone Exchange PK-PTEG-40067-GO-RFB / Hu 1. Policy, Institutions and Open - Internationa Single Stage - One E IDA / 59820 Post Request for Bids 200,000.00 0.00 Canceled 2018-04-16 2018-04-21 2018-06-02 2018-06-18 2018-07-02 2018-12-29 man Resource Information Sy Governance for Tourism Dev l nvelope stem elopment PK-PTEG-93484-GO-RFB / To 1. Policy, Institutions and Open - Internationa Single Stage - One E IDA / 59820 Prior Request for Bids 3,500,000.00 0.00 Canceled 2019-02-04 2019-02-09 2019-03-23 2019-04-22 2019-05-27 2019-11-23 urism Mobile Application Governance for Tourism Dev l nvelope elopment PK-PTEG-151606-GO-RFQ / P urchase of new IT Equipment and software for project staf 4. Project Management, M Request for Quota Single Stage - One E Pending Impl f. IDA / 59820 Post Open - National 15,000.00 0.00 2019-12-24 2019-12-28 2020-01-31 onitoring and Evaluation tions nvelope ementation 7 Laptops Core i-5 8GB ram 1 3.3" Screen size 256/512 GB HDD Windows 10 + MS Office 1 Tablet PK-PTEG-161181-GO-RFQ / I 4. Project Management, M Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 17,300.00 0.00 2020-03-14 2020-05-09 2020-11-05 T Equipment onitoring and Evaluation tions nvelope ementation PK-PTEG-161189-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 11,800.00 0.00 2020-03-14 2020-05-09 2020-11-05 ffice Equipment onitoring and Evaluation tions nvelope ementation PK-PTEG-161192-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 16,000.00 10,960.00 Signed 2020-03-14 2020-03-17 2020-05-09 2020-03-21 2020-11-05 ffice Furniture onitoring and Evaluation tions nvelope PK-PTEG-186934-GO-RFB / Si 3. Public Investment Facilit Single Stage - One E Under Imple IDA / 59820 Post Request for Bids Open - National 1,000,000.00 0.00 2020-08-13 2020-08-31 2020-08-18 2020-09-03 2020-09-29 2020-10-05 2020-10-14 2020-11-04 2023-10-20 gnboards - Supply and Install y nvelope mentation ation (FA) PK-PTEG-200114-GO-RFQ / P 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Limited 2,500.00 2,580.69 Signed 2020-10-20 2020-10-26 2020-11-05 2020-10-31 2020-11-12 rofessional Camera y tions nvelope PK-PTEG-200602-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 36,000.00 19,551.99 Signed 2020-10-27 2020-10-28 2020-11-26 2020-11-12 2021-02-24 ffice Furniture - Tourism Dep onitoring and Evaluation tions nvelope artment PK-PTEG-200605-GO-RFQ / I 4. Project Management, M Request for Quota Single Stage - One E Under Imple IDA / 59820 Post Open - National 25,200.00 0.00 2020-10-30 2020-10-28 2020-12-11 2021-02-09 T Equipment - Tourism Depar onitoring and Evaluation tions nvelope mentation tment PK-PTEG-200606-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 15,000.00 12,992.20 Signed 2020-10-31 2020-11-19 2020-12-15 2020-12-11 2021-02-13 ffice Equipment - Tourism De onitoring and Evaluation tions nvelope partment PK-PTEG-230268-GO-RFQ / G 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 150,000.00 163,734.37 Signed 2021-04-30 2021-05-07 2021-06-04 2021-06-10 2021-12-01 olf Carts for Heritage Sites y tions nvelope PK-PTEG-230269-GO-RFQ / H 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 70,000.00 34,537.37 Signed 2021-05-01 2021-05-07 2021-06-05 2021-06-23 2021-12-02 eritage Rikshaws y tions nvelope PK-PTEG-230271-GO-RFQ / C 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 100,000.00 80,079.55 Signed 2021-05-01 2021-05-07 2021-06-05 2021-06-08 2021-12-02 oaster - Shuttle Bus y tions nvelope PK-PTEG-228308-GO-RFQ / S 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 95,000.00 38,012.80 Signed 2021-05-01 2021-09-03 2021-06-05 2021-10-29 2021-12-02 MD for Taxila Museum y tions nvelope PK-PTEG-231715-GO-RFB / S 3. Public Investment Facilit Single Stage - One E IDA / 59820 Post Request for Bids Open - National 700,000.00 207,024.82 Terminated 2021-05-05 2021-08-04 2021-05-10 2021-08-05 2021-06-09 2021-09-02 2021-06-23 2021-09-23 2021-07-14 2022-01-02 2022-01-10 olid Waste Management Equi y nvelope pment PK-PTEG-256404-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 35,000.00 34,327.89 Signed 2021-10-15 2021-10-07 2021-11-16 2021-10-27 2022-05-15 ffice Furniture - Tourism Dep onitoring and Evaluation tions nvelope artment PK-PTEG-256408-GO-RFQ / O ffice Equipment - Tourism De 4. Project Management, M Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 24,000.00 0.00 2021-10-15 2021-11-19 2022-05-18 partment onitoring and Evaluation tions nvelope ementation DSLR, AC, Generator 15 KV, Refrigirator, Fax Machine PK-PTEG-256411-GO-RFQ / I T Equipment - Tourism Depar 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 25,000.00 8,175.37 Signed 2021-10-15 2021-10-11 2021-11-19 2021-10-29 2022-05-18 tment onitoring and Evaluation tions nvelope LEDs, Printers, Smart Phones , Video Conferencing System Page 2 PK-PTEG-271627-GO-RFB / S olid Waste Management Equi 3. Public Investment Facilit Single Stage - One E pment IDA / 59820 Post Request for Bids Open - National 200,000.00 148,710.58 Signed 2022-01-05 2022-01-10 2022-01-07 2022-01-13 2022-02-06 2022-02-11 2022-02-13 2022-02-22 2022-02-27 2022-03-25 2022-08-26 y nvelope 10 Mini Tippers 05 Mechanical Sweepers (Tra ctor driven) PK-PTEG-222318-GO-RFB / G 3. Public Investment Facilit Single Stage - One E IDA / 59820 Post Request for Bids Open - National 165,000.00 0.00 Canceled 2021-03-10 2021-03-15 2021-04-14 2021-04-24 2021-05-15 2021-11-11 olf Carts & Heritage Rikshaw y nvelope s PK-PTEG-227444-GO-RFB / S 3. Public Investment Facilit Single Stage - One E olar Power Energy System for IDA / 59820 Post Request for Bids Open - National 410,000.00 0.00 Canceled 2021-04-02 2021-04-06 2021-04-04 2021-04-08 2021-05-06 2021-05-21 2021-06-16 2022-06-11 y nvelope Heritage Sites PK-PTEG-275532-GO-RFB / D 3. Public Investment Facilit Open - Internationa Single Stage - One E IDA / 59820 Prior Request for Bids 3,000,000.00 0.00 Canceled 2022-02-11 2022-05-06 2022-02-16 2022-05-07 2022-04-02 2022-06-20 2022-04-16 2022-08-25 2022-05-21 2022-11-17 ouble Decker Buses - 9 buses y l nvelope PK-PTEG-283628-GO-RFB / P 3. Public Investment Facilit Single Stage - One E re-fabricated Containers for IDA / 59820 Post Request for Bids Open - National 240,000.00 0.00 Canceled 2022-03-18 2022-03-23 2022-04-22 2022-04-29 2022-05-20 2022-11-16 y nvelope Rescue Services - Murree Im plementation Plan PK-PTEG-283630-GO-RFB / R 3. Public Investment Facilit Single Stage - One E ecovery Vehicles for Rescue IDA / 59820 Post Request for Bids Open - National 400,000.00 0.00 Canceled 2022-03-18 2022-03-23 2022-04-22 2022-04-29 2022-05-20 2022-11-16 y nvelope Services - Murree Implement ation Plan PK-PTEG-283631-GO-RFB / A 3. Public Investment Facilit Single Stage - One E mbulances with fabrication R IDA / 59820 Post Request for Bids Open - National 600,000.00 0.00 Canceled 2022-03-18 2022-03-23 2022-04-22 2022-05-06 2022-05-27 2022-11-23 y nvelope escue Services - Murree Impl ementation Plan PK-PTEG-283632-GO-RFB / R 3. Public Investment Facilit Single Stage - One E escue Equipment for Rescue IDA / 59820 Post Request for Bids Open - National 300,000.00 0.00 Canceled 2022-03-18 2022-03-23 2022-04-22 2022-05-06 2022-05-27 2022-11-23 y nvelope Services - Murree Implement ation Plan PK-PTEG-283634-GO-RFQ / R 3. Public Investment Facilit Request for Quota Single Stage - One E ehabilitation of Takht-e-Babri IDA / 59820 Post Open - National 100,000.00 32,388.30 Signed 2022-03-16 2022-03-16 2022-04-16 2022-03-30 2022-06-15 y tions nvelope , Kalar Kahar PK-PTEG-286749-GO-RFQ / A 3. Public Investment Facilit Request for Quota Single Stage - One E rcheological Laboratory Equi IDA / 59820 Post Open - National 68,000.00 47,017.08 Signed 2022-03-30 2022-05-16 2022-05-05 2022-06-21 2022-11-01 y tions nvelope pment - Directorate of Arche ology PK-PTEG-293035-GO-RFB / V 4. Project Management, M Single Stage - One E Pending Impl ehicles for PTEGP (PMU-Touri IDA / 59820 Post Request for Bids Open - National 750,000.00 0.00 2022-05-09 2022-05-14 2022-06-11 2022-06-18 2022-07-02 2023-06-27 onitoring and Evaluation nvelope ementation sm Department and C&W) & IDAP PK-PTEG-295160-GO-RFB / P 3. Public Investment Facilit Single Stage - One E rocurement of Architectural a IDA / 59820 Post Request for Bids Open - National 725,000.00 0.00 Canceled 2022-06-26 2022-07-01 2022-07-31 2022-08-14 2022-09-11 2023-03-10 y nvelope nd Civil Engineering related S oftware PK-PTEG-295161-GO-RFB / P rocurement of Computer Equ 3. Public Investment Facilit Single Stage - One E Pending Impl IDA / 59820 Post Request for Bids Open - National 795,000.00 0.00 2022-06-27 2022-07-02 2022-08-01 2022-08-15 2022-09-19 2023-03-18 ip. Drones, Terrestrial Laser y nvelope ementation Scanner & Total Station for I DAP PK-PTEG-302801-GO-RFQ / S upply of Uniforms and relate 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 70,000.00 0.00 Signed 2022-07-18 2022-07-18 2022-08-20 2023-02-16 d accessories for Tourism Sq y tions nvelope uad - Tourism Department PK-PTEG-302808-GO-RFB / S upply & Installation of Revers 3. Public Investment Facilit Single Stage - One E IDA / 59820 Post Request for Bids Open - National 500,000.00 0.00 Canceled 2022-07-25 2022-08-31 2022-07-30 2022-09-02 2022-08-29 2022-09-12 2022-10-10 2023-04-08 ible Tuck shops & Washroom y nvelope s - Tourist sites Punjab PK-PTEG-302810-GO-RFQ / S 3. Public Investment Facilit Request for Quota Single Stage - One E Pending Impl upply of Garbage Collection IDA / 59820 Post Open - National 72,000.00 0.00 2022-07-23 2022-09-17 2023-03-16 y tions nvelope ementation Carts - Tourist Sites Punjab PK-PTEG-303027-GO-RFQ / S 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple upply & Installation of SMD S IDA / 59820 Post Open - National 50,000.00 0.00 2022-07-20 2022-07-15 2022-08-17 2022-10-16 y tions nvelope mentation creens - Murree District PK-PTEG-317860-GO-RFQ / P unjab Tourism Squad - Procur 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 96,000.00 0.00 Signed 2022-10-05 2022-11-01 2023-01-30 ement of equipment for cap y tions nvelope acity building of PTS PK-PTEG-319157-GO-RFB / S upply & Installation of Solar P ower System (Jahangir Tomb, Lahore, Shal 3. Public Investment Facilit Single Stage - One E amar Gardens, Lahore, Hiran IDA / 59820 Post Request for Bids Open - National 430,000.00 0.00 Canceled 2022-10-03 2022-11-10 2022-10-08 2022-11-11 2022-11-19 2022-12-19 2023-01-23 2023-07-22 y nvelope Minar, Sheikhupura, Rohtas F ort, Jhelum, Taxila Museum, Taxila Rawalpindi, Wah Gard ens Wah Rawalpindi & Harap pa Museum & Site, Sahiwal ) PK-PTEG-324234-GO-RFB / S upply & Installation of Revers 3. Public Investment Facilit Single Stage - One E IDA / 59820 Post Request for Bids Open - National 550,000.00 0.00 Signed 2022-11-01 2022-11-10 2022-11-02 2022-11-11 2022-12-02 2022-12-13 2022-12-05 2022-12-20 2022-12-11 2023-03-11 ible Tuck shops & Washroom y nvelope s - Tourist sites Punjab PK-PTEG-335666-GO-RFB / S 3. Public Investment Facilit Single Stage - One E Under Imple upply & Installation of Solar P IDA / 59820 Post Request for Bids Open - National 500,000.00 0.00 2023-01-16 2023-01-17 2023-01-21 2023-03-04 2023-02-27 2023-04-03 2023-05-08 2023-08-06 y nvelope mentation ower System PK-PTEG-351380-GO-RFB / P 3. Public Investment Facilit Open - Internationa Single Stage - One E Under Imple rocurement of 06-Double De IDA / 59820 Post Request for Bids 2,000,000.00 0.00 2023-03-27 2023-05-01 2023-04-01 2023-05-20 2023-05-13 2023-05-28 2023-06-03 2023-11-30 y l nvelope mentation cker Bus (Diesel Hybrid) PK-PTEG-351387-GO-RFQ / P 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple IDA / 59820 Post Open - National 575,000.00 0.00 2023-03-31 2023-04-28 2023-07-27 rocurement of 05-Coasters ( y tions nvelope mentation Diesel) PK-PTEG-351403-GO-RFQ / P 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple IDA / 59820 Post Open - National 400,000.00 0.00 2023-03-31 2023-04-30 2023-07-29 rocurement of 07-VANS y tions nvelope mentation PK-PTEG-351418-GO-RFQ / F 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple urniture and Inverter Floor St IDA / 59820 Post Open - National 53,000.00 0.00 2023-03-31 2023-04-16 2023-06-15 y tions nvelope mentation anding Cabinet A.C for Lahor e Museum Page 3 PK-PTEG-351405-GO-RFQ / P rocurement of I.T. Equipment for Lahore Museum Lot-1: Desktop Computer, est 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple imated budget=USD$=15,00 IDA / 59820 Post Open - National 50,000.00 0.00 2023-03-31 2023-04-27 2023-07-26 y tions nvelope mentation 0/- Lot-2: Laptop, estimated bud get=USD$=12,00/- Lot-3: Server 96TB storage, e stimated budget=USD$=33, 800/- PK-PTEG-353673-GO-RFQ / P 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple rocurement of Office Equipm IDA / 59820 Post Open - National 15,000.00 0.00 2023-03-29 2023-05-02 2023-07-31 y tions nvelope mentation ent for Lahore Museum PK-PTEG-355575-GO-RFQ / P ROCUREMENT OF EQUIPMEN T FOR AUDIO-VIDEOGRAPHY 3. Public Investment Facilit Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 90,000.00 0.00 2023-04-15 2023-05-10 2023-08-08 STUDIO, PORTABLE PUBLIC A y tions nvelope ementation DDRESS SYSTEM AND WEBIN AR ROOM FOR LAHORE MUSE UM PK-PTEG-363800-GO-RFQ / E QUIPMENT (LED) LIGHTS FOR 2. Private Investment and Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 16,000.00 0.00 2023-05-29 2023-06-29 2023-09-27 ILLUMINATION OF FRONT ELE Entrepreneurship Promotion tions nvelope ementation VATION FOR LAHORE MUSEU M BUILDING PK-PTEG-363804-GO-RFQ / P ROCUREMENT OF GOLF CART 2. Private Investment and Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 95,000.00 0.00 2023-05-29 2023-06-21 2023-09-19 FOR TDCP AT CHANGA MANG Entrepreneurship Promotion tions nvelope ementation A RESORT, LAHORE PK-PTEG-365225-GO-RFB / P 1. Policy, Institutions and rocurement of 11-Seater Golf Single Stage - One E Pending Impl IDA / 59820 Governance for Tourism Dev Post Request for Bids Open - National 300,000.00 0.00 2023-06-05 2023-06-07 2023-07-03 2023-07-08 2023-07-19 2024-01-15 Carts for Walled City Lahore nvelope ementation elopment Authority (WCLA) PK-PTEG-365229-GO-RFQ / P 1. Policy, Institutions and Request for Quota Single Stage - One E Pending Impl rocurement of Coaster for W IDA / 59820 Governance for Tourism Dev Post Open - National 120,000.00 0.00 2023-06-10 2023-07-03 2023-12-30 tions nvelope ementation alled City Lahore Authority ( elopment WCLA) PK-PTEG-365231-GO-RFQ / P 1. Policy, Institutions and Request for Quota Single Stage - One E Pending Impl rocurement of High Roof-VAN IDA / 59820 Governance for Tourism Dev Post Open - National 120,000.00 0.00 2023-06-07 2023-07-01 2023-12-28 tions nvelope ementation S for Walled City Lahore Auth elopment ority (WCLA) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PTEG-48673-NC-RFQ / Ev 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 30,000.00 27,702.75 Signed 2018-02-14 2018-02-15 2018-02-26 2018-02-13 2018-03-08 ent Management Firm - Proje onitoring and Evaluation tions nvelope ct Launch PK-PTEG-91147-NC-RFQ / Su 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 35,000.00 10,591.35 Signed 2019-01-12 2019-02-13 2019-03-09 2019-04-22 2019-09-05 rvey Firm for Data collection onitoring and Evaluation tions nvelope PK-PTEG-103229-NC-RFQ / T 4. Project Management, M Request for Quota Single Stage - One E ourism Sector regulation and IDA / 59820 Post Open - National 20,000.00 0.00 Canceled 2019-03-04 2019-04-29 2019-06-30 onitoring and Evaluation tions nvelope Inspection Mapping Exercise -4 Months PK-PTEG-103234-NC-RFQ / D ocumentary Preparation of K 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 100,000.00 0.00 Canceled 2019-03-10 2019-05-05 2019-06-30 artarpur site (Non Consultanc onitoring and Evaluation tions nvelope y Services) 2-Months PK-PTEG-103260-NC-RFQ / T 4. Project Management, M Request for Quota Single Stage - One E raining need assessment of S IDA / 59820 Post Open - National 100,000.00 0.00 Canceled 2019-03-04 2019-04-29 2019-06-30 onitoring and Evaluation tions nvelope kill training 4-Months PK-PTEG-141301-NC-DIR / Pr 4. Project Management, M Pending Impl ocurement of Planning & Mon IDA / 59820 Post Direct Selection Direct 1,260.00 0.00 2019-10-21 2019-10-26 2019-11-08 2019-11-18 onitoring and Evaluation ementation itoring Software (SMARTSHEE T) PK-PTEG-140344-NC-DIR / H all and Auditorium facility ch 1. Policy, Institutions and arges for conduct of Lahore I IDA / 59820 Governance for Tourism Dev Post Direct Selection Direct 50,000.00 0.00 Canceled 2019-10-23 2019-10-28 2019-12-07 2019-12-28 nternational Tourism Expo (LI elopment TE) at Expo center Lahore PK-PTEG-134818-NC-RFQ / H 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 20,000.00 0.00 Canceled 2019-09-19 2019-09-24 2019-09-27 iring of Firm for Event Manag onitoring and Evaluation tions nvelope ement PK-PTEG-159994-NC-RFQ / E 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 12,000.00 4,442.20 Signed 2020-02-24 2020-02-25 2020-03-18 2020-03-18 2022-03-08 nvironment Laboratory y tions nvelope PK-PTEG-300757-NC-RFQ / T 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple opographic Survey of Archeol IDA / 59820 Post Open - National 100,000.00 0.00 2022-07-01 2022-07-18 2022-08-05 2023-02-01 y tions nvelope mentation ogical Sites PK-PTEG-306845-NC-RFB / Hi 1. Policy, Institutions and ring of Training Service Provi Single Stage - One E IDA / 59820 Governance for Tourism Dev Post Request for Bids Open - National 2,000,000.00 0.00 Canceled 2022-08-04 2022-10-03 2022-08-09 2022-09-08 2022-09-28 2022-10-26 2023-04-24 ders (TSPs) for Skills Develop nvelope elopment ment - Tourism Sector Punja b CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PTEG-32421-CS-QCBS / H 3. Public Investment Facilit UN Agencies (Dire iring of Heritage Firm IDA / 59820 Prior Direct 500,000.00 2,834,843.00 Signed 2018-01-27 2018-02-19 2021-01-29 y ct) UNESCO PK-PTEG-32423-CS-QCBS / H 1. Policy, Institutions and Quality And Cost- Open - Internationa Under Implement iring of firm for Legal & Regul IDA / 59820 Governance for Tourism Dev Prior 750,000.00 0.00 2017-12-25 2018-07-24 2018-01-15 2018-02-28 2018-03-28 2018-04-27 2018-06-01 2018-07-06 2019-07-06 Based Selection l ation atory Review elopment Page 4 PK-PTEG-32425-CS-CQS / Int 4. Project Management, M Least Cost Selecti ernal Audit Firm IDA / 59820 Post Open - National 150,000.00 0.00 Canceled 2017-12-18 2018-01-08 2018-02-21 2018-03-21 2018-04-20 2018-05-25 2018-06-29 2022-12-30 onitoring and Evaluation on Estimated cost for 5 years PK-PTEG-32422-CS-QCBS / Fi 2. Private Investment and Quality And Cost- Open - Internationa IDA / 59820 Post 1,500,000.00 0.00 Canceled 2018-01-31 2018-12-28 2018-02-16 2018-03-09 2018-04-23 2018-05-08 2018-05-22 2018-06-05 2020-10-13 rm Hiring for Skills Developm Entrepreneurship Promotion Based Selection l ent PK-PTEG-32418-CS-QCBS / S 3. Public Investment Facilit Quality And Cost- Open - Internationa upervision & Quality Assuran IDA / 59820 Prior 952,380.00 94,799.46 Signed 2018-01-15 2019-02-11 2018-01-30 2019-02-11 2018-02-27 2020-05-08 2018-04-01 2020-04-15 2018-04-17 2020-05-09 2018-05-08 2020-07-17 2018-05-22 2020-07-09 2020-09-29 y Based Selection l ce Firm Civil Works consultant firm - PISC PK-PTEG-32427-CS-CQS / Up 1. Policy, Institutions and Quality And Cost- Open - Internationa gradation of Existing Institute IDA / 59820 Governance for Tourism Dev Prior 750,000.00 0.00 Canceled 2018-02-01 2018-02-16 2018-03-12 2018-04-24 2018-05-09 2018-05-23 2018-06-06 2019-06-06 Based Selection l s - Hiring of firm elopment PK-PTEG-51948-CS-CQS / Int 4. Project Management, M Consultant Qualifi IDA / 59820 Post Open - National 150,000.00 0.00 Canceled 2018-03-06 2018-05-01 2018-03-26 2018-05-10 2018-05-17 2018-06-14 2023-04-30 ernal Audit Firm - 5 Years Co onitoring and Evaluation cation Selection ntract PK-PTEG-64589-CS-CQS / Up 1. Policy, Institutions and Consultant Qualifi gradation of Existing Institute IDA / 59820 Governance for Tourism Dev Post Open - National 400,000.00 0.00 Canceled 2018-06-11 2018-06-19 2018-07-02 2018-08-15 2018-09-14 2018-10-19 2019-06-28 cation Selection s - Restructuring of TDCP elopment PK-PTEG-93553-CS-QCBS / R 1. Policy, Institutions and Quality And Cost- IDA / 59820 Post Open - National 500,000.00 0.00 Canceled 2019-01-14 2019-01-08 2019-02-04 2019-02-13 2019-03-20 2019-04-17 2019-05-17 2019-06-21 2019-07-26 2020-07-25 e-structuring of TDCP Governance for Tourism Dev Based Selection elopment PK-PTEG-110939-CS-CQS / D 4. Project Management, M Consultant Qualifi Under Implement ocumentary Preparation of K IDA / 59820 Post Open - National 100,000.00 0.00 2019-04-22 2019-05-10 2019-05-13 2019-07-08 2019-06-26 2019-08-21 2019-07-26 2019-08-30 2020-04-30 onitoring and Evaluation cation Selection ation artarpur site PK-PTEG-110942-CS-CQS / T 4. Project Management, M Consultant Qualifi Under Implement IDA / 59820 Post Open - National 100,000.00 0.00 2019-04-22 2019-05-10 2019-05-13 2019-07-08 2019-06-26 2019-07-26 2019-08-30 2020-04-30 raining need assessment of S onitoring and Evaluation cation Selection ation kill training PK-PTEG-128723-CS-LCS / Hi 4. Project Management, M Least Cost Selecti IDA / 59820 Post Open - National 250,000.00 0.00 Canceled 2019-08-25 2020-03-09 2019-09-15 2019-10-29 2019-11-26 2019-12-26 2020-01-30 2020-03-05 2023-03-05 ring of Media Firm onitoring and Evaluation on PK-PTEG-103226-CS-LCS / Hi 4. Project Management, M Least Cost Selecti IDA / 59820 Post Open - National 150,000.00 0.00 Canceled 2019-02-27 2019-03-08 2019-03-20 2019-03-11 2019-05-03 2019-07-19 2019-05-31 2019-08-23 2019-06-30 2019-08-04 2019-09-08 2022-06-30 ring of Internal Audit Firm 5- onitoring and Evaluation on Years PK-PTEG-32414-CS-CQS / Me 2. Private Investment and Consultant Qualifi IDA / 59820 Prior Open - National 2,500,000.00 0.00 Canceled 2017-11-20 2018-09-20 2017-12-11 2018-01-24 2018-02-23 2018-03-30 2020-11-23 dia Firm hiring Entrepreneurship Promotion cation Selection PK-PTEG-163250-CS-QCBS / I 1. Policy, Institutions and Quality And Cost- IDA / 59820 Post Open - National 300,000.00 188,305.86 Signed 2020-03-13 2020-03-09 2020-04-02 2020-03-13 2020-04-19 2020-07-29 2020-05-19 2020-08-31 2020-05-29 2020-09-17 2020-06-15 2020-10-20 2020-07-06 2020-12-17 2021-07-01 SMP Qila Kohna Qasim Bagh Governance for Tourism Dev Based Selection elopment PK-PTEG-164014-CS-QCBS / 1. Policy, Institutions and Quality And Cost- IDA / 59820 Post Open - National 250,000.00 544,997.13 Signed 2020-03-12 2020-03-11 2020-04-02 2020-03-13 2020-05-16 2020-07-13 2020-06-13 2020-08-25 2020-07-13 2020-09-16 2020-08-17 2020-10-05 2020-09-21 2021-02-04 2023-09-06 Media Firm Hiring Governance for Tourism Dev Based Selection elopment PK-PTEG-183974-CS-QCBS / Destination Investment & Ma 1. Policy, Institutions and Quality And Cost- Open - Internationa nagement Plans (DIMPs) Con IDA / 59820 Governance for Tourism Dev Prior 3,000,000.00 614,175.00 Signed 2020-07-16 2020-07-24 2020-07-26 2020-08-28 2020-08-30 2020-11-26 2020-09-27 2021-01-11 2020-10-12 2021-03-03 2020-11-02 2021-03-16 2020-12-07 2021-05-15 2022-12-07 Based Selection l sultancy Services - elopment IDC (Framework contract) PK-PTEG-206682-CS-CQS / E 3. Public Investment Facilit Consultant Qualifi Under Implement nvironment Impact Assessme IDA / 59820 Post Open - National 100,000.00 0.00 2020-12-01 2020-12-15 2020-12-16 2020-12-30 2021-01-06 2021-02-11 2021-01-13 2021-01-25 2022-01-25 y cation Selection ation nt Services PK-PTEG-223666-CS-QCBS / 3. Public Investment Facilit Quality And Cost- Open - Internationa Pending Impleme Taxila Museum Upgradation - IDA / 59820 Post 450,000.00 0.00 2021-03-19 2021-04-03 2021-04-20 2021-05-18 2021-06-01 2021-06-22 2021-07-13 2022-07-13 y Based Selection l ntation Consulting Firm PK-PTEG-228305-CS-CQS / A 3. Public Investment Facilit Consultant Qualifi Pending Impleme rchitectural Firm for Design o IDA / 59820 Post Open - National 100,000.00 0.00 2021-04-11 2021-04-26 2021-05-17 2021-05-24 2021-06-07 2021-12-04 y cation Selection ntation f New Museum at Harappa PK-PTEG-246068-CS-QCBS / 3. Public Investment Facilit Quality And Cost- Under Implement Design Review and Supervisi IDA / 59820 Post Open - National 550,000.00 0.00 2021-08-02 2021-08-02 2021-08-17 2021-09-07 2021-10-05 2021-10-19 2021-11-02 2021-11-23 2022-11-23 y Based Selection ation on Firm (Roads & Buildings) PK-PTEG-267389-CS-CQS / S 3. Public Investment Facilit Consultant Qualifi Under Implement olar Energy - Design & Super IDA / 59820 Post Open - National 45,000.00 0.00 2021-12-13 2021-12-14 2021-12-28 2022-01-20 2022-01-26 2022-04-05 2022-02-09 2022-02-23 2023-02-18 y cation Selection ation vision Firm PK-PTEG-295159-CS-CQS / T 3. Public Investment Facilit Consultant Qualifi Under Implement opographic & Utilities Survey IDA / 59820 Post Open - National 100,000.00 0.00 2022-05-20 2022-05-30 2022-06-04 2022-07-03 2022-07-17 2022-08-14 2023-02-10 y cation Selection ation - IDAP Hiran Minar PK-PTEG-295158-CS-QCBS / Services for Preparation of As 3. Public Investment Facilit Consultant Qualifi Pending Impleme -Built Drawings & Scan-Base IDA / 59820 Post Open - National 175,000.00 0.00 2022-06-26 2022-07-17 2022-08-14 2022-08-28 2022-09-11 2023-03-10 y cation Selection ntation d 3D Models - IDAP Hiran Minar, Rohtas Fort & Ta xila PK-PTEG-320789-CS-CQS / D ESIGN AND RESIDENT SUPER 3. Public Investment Facilit Consultant Qualifi Under Implement VISION OF URBAN REHABILIT IDA / 59820 Post Open - National 150,000.00 0.00 2022-10-12 2022-11-10 2022-10-22 2022-12-28 2022-11-16 2022-12-01 2023-01-05 2024-10-31 y cation Selection ation ATION OF FAÇADE AND ESTA BLISHMENT OF PARKING ARE A - BHATTI GATE PK-PTEG-320794-CS-CQS / D ESIGN AND RESIDENT SUPER 3. Public Investment Facilit Consultant Qualifi Under Implement VISION OF URBAN REHABILIT IDA / 59820 Post Open - National 250,000.00 0.00 2022-10-12 2022-11-10 2022-10-27 2022-12-28 2022-11-20 2022-12-05 2023-01-09 2024-10-31 y cation Selection ation ATION OF INFRASTRUCTURE I MPROVEMENT - BHATTI GATE PK-PTEG-320797-CS-CQS / D ESIGN AND RESIDENT SUPER 3. Public Investment Facilit Consultant Qualifi IDA / 59820 Post Open - National 200,000.00 0.00 Under Review 2022-10-12 2022-11-10 2022-10-27 2022-11-20 2022-12-05 2022-12-25 2024-10-31 VISION FIRM FOR QILA KOHN y cation Selection A QASIM BAGH PROJECT PK-PTEG-330668-CS-QCBS / 3. Public Investment Facilit Quality And Cost- Under Implement Hiring of Firm for Digital Cura IDA / 59820 Post Open - National 600,000.00 0.00 2022-12-13 2022-12-06 2023-01-17 2023-01-02 2023-01-28 2023-03-04 2023-03-14 2023-03-27 2023-04-20 2024-04-19 y Based Selection ation tion of Lahore and Taxila Mus eum INDIVIDUAL CONSULTANTS Page 5 Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PTEG-32377-CS-INDV / So 4. Project Management, M Individual Consult cial Gender Specialist IDA / 59820 Post Open 189,450.00 26,773.76 Signed 2017-10-17 2017-08-01 2017-12-05 2018-01-02 2017-12-26 2018-01-01 2018-01-30 2018-02-01 2018-12-20 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32381-CS-INDV / E 4. Project Management, M Individual Consult nvironmental Specialist IDA / 59820 Post Open 189,450.00 24,361.53 Signed 2017-10-17 2017-07-17 2017-12-05 2017-12-26 2017-12-11 2018-01-30 2018-01-11 2019-01-10 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32410-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Bahawalpur IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-32411-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Rajanpur IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-40044-CS-INDV / R 4. Project Management, M Individual Consult IDA / 59820 Post Open 85,714.00 5,361.93 Signed 2017-12-18 2017-10-02 2018-02-05 2017-10-27 2018-02-26 2017-11-27 2018-04-02 2017-10-27 2018-09-28 esearch Associate onitoring and Evaluation ant Selection PK-PTEG-40046-CS-INDV / R 4. Project Management, M Individual Consult esearch Associate IDA / 59820 Post Open 85,714.00 5,361.93 Signed 2017-12-18 2017-12-04 2018-02-05 2018-01-03 2018-02-26 2018-01-02 2018-04-02 2018-01-08 2019-04-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-32376-CS-INDV / Fi 4. Project Management, M Individual Consult nancial Management Speciali IDA / 59820 Post Open 189,450.00 21,440.76 Signed 2017-10-17 2017-12-05 2017-09-11 2017-12-26 2017-09-13 2018-01-30 2017-09-26 2018-10-10 onitoring and Evaluation ant Selection st Estimated amount for 5 year s PK-PTEG-32398-CS-INDV / M 4. Project Management, M Individual Consult & E Specialist IDA / 59820 Post Open 225,000.00 29,233.84 Signed 2017-10-17 2017-07-01 2017-12-05 2017-09-11 2017-12-26 2017-09-25 2018-01-30 2017-09-26 2018-10-01 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-32389-CS-INDV / Pr 4. Project Management, M Individual Consult oject Director IDA / 59820 Prior Open 600,000.00 0.00 Canceled 2017-10-17 2018-08-16 2017-12-05 2017-12-26 2018-02-19 2019-02-19 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32391-CS-INDV / D 4. Project Management, M Individual Consult eputy Project Director IDA / 59820 Prior Open 370,000.00 0.00 Canceled 2017-10-17 2017-12-05 2017-12-26 2018-01-30 2018-10-25 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-40047-CS-INDV / R 4. Project Management, M Individual Consult esearch Associate - Account/ IDA / 59820 Post Open 85,714.00 14,616.92 Signed 2017-12-18 2017-09-11 2018-01-21 2017-12-08 2018-01-28 2017-12-11 2018-02-19 2017-12-12 2019-01-02 onitoring and Evaluation ant Selection Admin Estimated cost for 5 years PK-PTEG-68956-CS-INDV / Pu 4. Project Management, M Individual Consult IDA / 59820 Post Open 47,000.00 0.00 Canceled 2018-07-16 2018-09-03 2018-09-24 2018-10-29 2019-04-27 blic Sector Development Spe onitoring and Evaluation ant Selection cialist PK-PTEG-73991-CS-INDV / Pr 4. Project Management, M Individual Consult IDA / 59820 Post Open 47,000.00 17,457.63 Signed 2018-08-16 2019-01-14 2018-10-04 2019-09-20 2018-10-25 2019-09-24 2018-11-29 2019-09-24 2019-05-28 ivate Sector Development Sp onitoring and Evaluation ant Selection ecialist PK-PTEG-93482-CS-INDV / To 4. Project Management, M Individual Consult urism Expert IDA / 59820 Post Open 40,000.00 25,119.61 Signed 2019-01-11 2019-09-30 2019-03-01 2020-02-27 2019-03-22 2019-04-26 2020-04-09 2019-10-23 onitoring and Evaluation ant Selection (One year estimated cost) PK-PTEG-103221-CS-INDV / 4. Project Management, M Individual Consult Monitoring & Evaluation Spec IDA / 59820 Post Open 150,000.00 21,524.65 Signed 2019-02-27 2019-05-04 2019-04-17 2019-11-20 2019-05-08 2019-06-12 2019-11-26 2022-06-30 onitoring and Evaluation ant Selection ialist 3-Years and 4 Months PK-PTEG-103232-CS-INDV / P 4. Project Management, M Individual Consult rocurement & Contract Admi IDA / 59820 Post Open 16,000.00 0.00 Canceled 2019-02-27 2019-04-17 2019-05-08 2019-06-12 2020-04-30 onitoring and Evaluation ant Selection nistration Support 1-Year PK-PTEG-32401-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Rawalpindi IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32405-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Gujranwala IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32407-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Sheikhupura IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-136467-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 170,000.00 0.00 Canceled 2019-10-02 2019-10-03 2019-10-28 2019-11-04 2019-11-18 2022-11-16 Hiring of Sr. Procurement Sp onitoring and Evaluation ant Selection ecialist PK-PTEG-136466-CS-INDV / 4. Project Management, M Individual Consult Pending Impleme IDA / 59820 Post Open 4,260.00 0.00 2019-10-03 2019-10-12 2019-10-14 2019-10-19 2020-02-16 Hiring of Graphic Designer onitoring and Evaluation ant Selection ntation PK-PTEG-138460-CS-INDV / 4. Project Management, M Individual Consult Hiring of Monitoring & Evalua IDA / 59820 Post Open 76,600.00 0.00 Canceled 2019-10-03 2019-10-29 2019-11-05 2019-11-13 2022-10-31 onitoring and Evaluation ant Selection tion (M&E) Specialist PK-PTEG-139666-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 170,000.00 0.00 Canceled 2019-10-14 2019-11-16 2019-11-26 2019-12-10 2023-10-31 Hiring of Sr. Communication onitoring and Evaluation ant Selection Specialist PK-PTEG-139667-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 87,500.00 8,612.44 Signed 2019-10-14 2019-12-02 2019-11-09 2020-01-22 2019-11-16 2020-01-23 2019-11-30 2020-01-24 2023-10-30 Hiring of Research Associate onitoring and Evaluation ant Selection PK-PTEG-103217-CS-INDV / 4. Project Management, M Individual Consult Senior Communication Speci IDA / 59820 Prior Open 168,000.00 0.00 Canceled 2019-02-27 2019-03-07 2019-04-17 2019-05-08 2019-06-12 2022-06-30 onitoring and Evaluation ant Selection alist 3-Years and 4 Months PK-PTEG-145106-CS-INDV / P 4. Project Management, M Individual Consult IDA / 59820 Post Limited 150,000.00 26,016.25 Signed 2019-11-11 2019-11-08 2019-11-12 2019-11-08 2019-11-13 2019-11-19 2019-11-14 2019-11-20 2022-09-14 roject Manager onitoring and Evaluation ant Selection PK-PTEG-145603-CS-INDV / P 4. Project Management, M Individual Consult rocurement and Contract Ad IDA / 59820 Post Limited 12,000.00 8,863.64 Signed 2019-11-14 2019-10-15 2019-11-15 2021-02-24 2019-11-15 2021-03-22 2019-11-15 2021-03-23 2020-11-14 onitoring and Evaluation ant Selection ministration Support Assistan t PK-PTEG-145698-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Limited 12,000.00 0.00 Canceled 2019-11-14 2019-11-15 2019-11-15 2019-11-15 2020-02-16 Short Term Media Advisor for onitoring and Evaluation ant Selection YASAT Page 6 PK-PTEG-32372-CS-INDV / Se 4. Project Management, M Individual Consult nior Procurement Specialist IDA / 59820 Prior Open 255,000.00 0.00 Canceled 2017-10-17 2017-12-05 2017-12-26 2018-01-30 2018-10-08 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-103202-CS-INDV / 4. Project Management, M Individual Consult Senior Procurement Specialis IDA / 59820 Prior Open 170,000.00 0.00 Canceled 2019-02-27 2019-02-28 2019-04-17 2019-05-08 2019-06-12 2022-06-30 onitoring and Evaluation ant Selection t-3 Years & 4-Months PK-PTEG-145723-CS-INDV / 1. Policy, Institutions and Individual Consult Pending Impleme Short Term Media Consultant IDA / 59820 Governance for Tourism Dev Post Limited 12,000.00 0.00 2019-11-14 2019-11-15 2019-11-15 2019-11-15 2019-11-24 ant Selection ntation for YASA&T. Demand Driven elopment PK-PTEG-151717-CS-INDV / Estimated cost for Project Off icer -1 for 3 years 4. Project Management, M Individual Consult IDA / 59820 Post Limited 45,000.00 10,762.33 Signed 2019-12-24 2019-12-02 2019-12-29 2020-01-02 2019-12-30 2020-01-03 2020-01-07 2021-01-02 We will use limited competiti onitoring and Evaluation ant Selection on as we will select a candid ate from existing pool of can didates. PK-PTEG-151720-CS-INDV / P roject Officer -2 . Estimated cost for 3 years USD 45,000. 4. Project Management, M Individual Consult IDA / 59820 Post Limited 45,000.00 12,197.30 Signed 2019-12-24 2019-12-02 2019-12-29 2020-01-06 2020-01-03 2020-01-10 2020-01-07 2021-01-09 We will use limited competiti onitoring and Evaluation ant Selection on since we have existing po ol of consultants to select fro m. PK-PTEG-32404-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Chakwal IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-32385-CS-INDV / Se 4. Project Management, M Individual Consult nior Communication Specialis IDA / 59820 Prior Open 252,000.00 0.00 Canceled 2017-10-17 2018-08-31 2017-12-05 2017-12-26 2018-01-30 2019-01-30 onitoring and Evaluation ant Selection t Estimated amount for 5 year s PK-PTEG-153682-CS-INDV / 4. Project Management, M Individual Consult Hiring of Procurement Specia IDA / 59820 Post Limited 170,000.00 22,959.63 Signed 2020-01-14 2020-01-01 2020-01-17 2020-01-10 2020-01-18 2020-02-10 2020-01-20 2020-02-11 2023-01-19 onitoring and Evaluation ant Selection list PTEGP- cost for 3 years PK-PTEG-115815-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 168,000.00 0.00 Canceled 2019-05-21 2019-07-09 2019-07-30 2019-09-03 2022-06-30 Senior Communication Speci onitoring and Evaluation ant Selection alist PK-PTEG-32387-CS-INDV / In 4. Project Management, M Individual Consult frastructure Development Sp IDA / 59820 Post Open 189,450.00 0.00 Canceled 2017-10-17 2019-01-21 2017-12-05 2017-12-26 2018-01-30 2019-03-29 onitoring and Evaluation ant Selection ecialist Estimated amount for 5 year s PK-PTEG-162559-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Limited 100,000.00 18,126.90 Signed 2020-03-09 2020-03-09 2020-03-14 2020-03-06 2020-04-04 2020-03-16 2020-05-09 2020-03-21 2022-04-29 Civil Engineer onitoring and Evaluation ant Selection PK-PTEG-163247-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Limited 15,000.00 11,229.64 Signed 2020-03-10 2020-03-24 2020-03-15 2020-10-03 2020-04-05 2020-12-11 2020-05-10 2020-12-18 2021-05-10 Assistant Civil Engineer onitoring and Evaluation ant Selection PK-PTEG-190459-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 75,000.00 14,972.86 Signed 2020-09-02 2020-09-01 2020-10-21 2020-11-12 2020-11-11 2020-12-03 2020-12-16 2020-12-08 2021-06-14 Social Safeguard & Gender S onitoring and Evaluation ant Selection pecialist PK-PTEG-196847-CS-INDV / 3. Public Investment Facilit Individual Consult IDA / 59820 Post Limited 20,000.00 12,496.10 Signed 2020-10-05 2020-10-09 2020-10-10 2020-10-16 2020-10-24 2020-11-15 2020-11-17 2020-11-17 2022-11-17 Content Writer - Informative y ant Selection Signboards PK-PTEG-197173-CS-INDV / 3. Public Investment Facilit Individual Consult Under Implement IDA / 59820 Post Limited 20,000.00 0.00 2020-10-09 2022-07-19 2020-10-14 2020-11-04 2020-12-09 2021-12-04 Conservation Architect - PCR y ant Selection ation MP PK-PTEG-228307-CS-INDV / P 4. Project Management, M Individual Consult IDA / 59820 Post Open 20,000.00 12,954.55 Signed 2021-04-26 2021-04-26 2021-05-29 2021-06-04 2021-06-05 2021-06-04 2021-06-19 2021-07-08 2022-06-14 roject Officer - 1 onitoring and Evaluation ant Selection PK-PTEG-228310-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 30,000.00 0.00 2021-04-26 2021-09-23 2021-05-29 2021-06-12 2021-06-26 2022-06-21 Architect onitoring and Evaluation ant Selection ation PK-PTEG-232086-CS-INDV / L 4. Project Management, M Individual Consult Under Implement egal Consultant for Tourism IDA / 59820 Post Open 9,500.00 0.00 2021-05-03 2021-04-30 2021-06-05 2021-06-12 2021-06-26 2021-09-24 onitoring and Evaluation ant Selection ation Department PK-PTEG-243329-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 45,000.00 0.00 2021-07-16 2021-07-07 2021-08-18 2021-09-01 2021-09-18 2023-04-30 Environment Specialist onitoring and Evaluation ant Selection ation PK-PTEG-256619-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Limited 23,500.00 0.00 2021-11-21 2022-03-25 2021-11-26 2021-12-03 2021-12-17 2022-06-15 Consultant for Integrated Tou onitoring and Evaluation ant Selection ation rism Plan PK-PTEG-264216-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 20,000.00 0.00 2021-11-28 2021-12-14 2021-12-24 2021-12-31 2022-01-14 2023-01-09 Research Associate - I onitoring and Evaluation ant Selection ation PK-PTEG-264217-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 20,000.00 0.00 2021-11-28 2021-12-14 2021-12-24 2021-12-31 2022-01-14 2023-01-09 Research Associate - II onitoring and Evaluation ant Selection ation PK-PTEG-267380-CS-INDV / P 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 100,000.00 0.00 2021-12-17 2021-12-16 2022-01-26 2022-02-09 2022-02-23 2023-04-30 roject Director onitoring and Evaluation ant Selection ation PK-PTEG-274905-CS-INDV / 4. Project Management, M Individual Consult Under Implement Coordination Officer for Touri IDA / 59820 Post Open 21,000.00 0.00 2022-01-31 2022-01-28 2022-02-26 2022-03-05 2022-03-19 2023-03-14 onitoring and Evaluation ant Selection ation sm Department PK-PTEG-274909-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 14,000.00 0.00 2022-01-31 2022-01-28 2022-02-26 2022-03-05 2022-03-19 2023-03-14 Data Analyst for Tourism Dep onitoring and Evaluation ant Selection ation artment PK-PTEG-274911-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 14,000.00 0.00 2022-01-31 2022-01-28 2022-02-26 2022-03-05 2022-03-19 2023-03-14 Analyst for Tourism Departm onitoring and Evaluation ant Selection ation ent PK-PTEG-279726-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Limited 28,000.00 0.00 Signed 2022-02-22 2022-02-18 2022-02-27 2022-07-21 2022-03-13 2022-08-04 2022-03-27 2023-03-22 Environment Specialist onitoring and Evaluation ant Selection PK-PTEG-279729-CS-INDV / L 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Limited 20,000.00 0.00 2022-02-21 2022-02-18 2022-02-24 2022-03-03 2022-03-17 2023-03-12 iaison Officer onitoring and Evaluation ant Selection ation PK-PTEG-279736-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 21,000.00 0.00 2022-02-21 2022-02-18 2022-03-19 2022-04-02 2022-04-16 2023-04-11 Coordination Officer onitoring and Evaluation ant Selection ation PK-PTEG-286751-CS-INDV / 1. Policy, Institutions and Individual Consult Under Implement Economist - Assessment of e IDA / 59820 Governance for Tourism Dev Post Open 16,000.00 0.00 2022-04-25 2022-04-21 2022-05-21 2022-05-28 2022-06-11 2022-09-09 ant Selection ation conomic impact of the PTEGP elopment Page 7 PK-PTEG-293040-CS-INDV / 3. Public Investment Facilit Individual Consult Pending Impleme IDA / 59820 Post Open 26,000.00 0.00 2022-05-09 2022-06-04 2022-06-11 2022-06-25 2023-06-20 Conservation Specialist y ant Selection ntation PK-PTEG-302813-CS-INDV / P 4. Project Management, M Individual Consult Under Implement rocurement and Contract Ad IDA / 59820 Post Open 12,000.00 0.00 2022-07-18 2023-03-20 2022-08-20 2022-08-27 2022-09-10 2023-04-29 onitoring and Evaluation ant Selection ation ministration Officer PK-PTEG-305507-CS-INDV / P 4. Project Management, M Individual Consult IDA / 59820 Prior Open - National 20,000.00 0.00 Signed 2022-07-25 2022-07-26 2022-08-27 2022-10-21 2022-09-10 2023-05-25 2022-10-01 2023-06-01 2023-04-29 rocurement Specialist onitoring and Evaluation ant Selection PK-PTEG-321724-CS-INDV / 4. Project Management, M Individual Consult Under Implement Hiring of Financial Managem IDA / 59820 Post Open - National 15,000.00 0.00 2022-10-17 2022-10-31 2022-11-07 2023-01-05 2022-11-09 2022-11-12 2023-05-11 onitoring and Evaluation ant Selection ation ent Specialist PK-PTEG-332494-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open - National 12,000.00 0.00 2022-12-19 2022-12-12 2023-01-10 2023-01-15 2023-01-26 2023-04-30 Hiring of Electrical Engineer onitoring and Evaluation ant Selection ation PK-PTEG-347113-CS-INDV / 4. Project Management, M Individual Consult Under Implement Hiring of Digital Media & Com IDA / 59820 Post Open - National 25,000.00 0.00 2023-03-07 2023-03-20 2023-04-11 2023-04-16 2023-04-22 2024-04-21 onitoring and Evaluation ant Selection ation munication Expert PK-PTEG-347155-CS-INDV / 1. Policy, Institutions and Individual Consult Hiring of Museum Educator a IDA / 59820 Governance for Tourism Dev Post Open - National 5,000.00 0.00 Canceled 2023-03-10 2023-03-20 2023-04-08 2023-04-13 2023-04-23 2023-10-20 ant Selection t Lahore Museum elopment PK-PTEG-347167-CS-INDV / 4. Project Management, M Individual Consult Under Implement Hiring of Social Safeguard & IDA / 59820 Post Open - National 31,000.00 0.00 2023-03-10 2023-03-06 2023-04-13 2023-04-18 2023-04-28 2024-04-27 onitoring and Evaluation ant Selection ation Gender Specialist Page 8 Procurement Plan Colombia - Plan PAZcifico: WSS Infrastructure & Service Delivery Project P156239 I. General 1. Bank’s approval Date of the procurement Plan: Original 2016/08/29; Revision 2016/12/15 and 2017/4/19 2. Date of General Procurement Notice: Dec 13, 2016 3. Period covered by this procurement plan: First 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank will be marked in the procurement plan according to the level of risk of the agency 2. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P156239 issued by National Unit For The Management Of Disaster Risk – UNGRD 3. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 40.00 1 No Prior of the ICB (Works) Summary 54.00 09 No Post of the NCB (Works) Summary 1.00 1 No Post of the NCB (Goods) III. Selection of Consultants July 9, 2010 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank will be marked in the procurement plan according to the level of risk of the agency 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_400,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 11.6 6 Post of number of contracts that will be let under QCBS Summary 1.6 5 Post CQS, of number LCBS of contracts that will be let under other methods July 9, 2010 PROCUREMENT Colombia : CO Plan PAZcifico:Water Supply and Basic Sanitation Infrastructure and Service Delivery Project PLAN General Information Country: Colombia Bank’s Approval Date of the Original Procurement Plan: 2016-12-15 Revised Plan Date(s): (comma delineated, leave blank if 2023-05-24 none) Project ID: P156239 GPN Date: 2016-12-13 Project Name: CO Plan PAZcifico:Water Supply and Basic Sanitation Infrastructure and Service Delivery Project Loan / Credit No: IBRD / 86490 National Unit for the Management of Disaster Risk Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PTSP-BIRF8649-002 / Acued Component 2. Water Supply ucto Tumaco, Nariño. Aducci and Basic Sanitation Improv Single Stage - One E 2019-06-0 IBRD / 86490 Post Request for Bids Open - National 2,973,324.00 0.00 Canceled 2017-07-06 2017-08-06 2017-09-24 2017-11-06 2017-12-11 on: suministro e instalacion d ements in the Municipality o nvelope 4 e 5.5 km de tuberia en HD de f Tumaco 20" (1 de 4) PTSP-BIRF8649-003 / Acued ucto Tumaco, Nariño. Optimi zación PTAP Buchelly (incluy Component 2. Water Supply e: construccion empate con l and Basic Sanitation Improv Single Stage - One E 2019-06-0 IBRD / 86490 Post Request for Bids Open - National 1,547,966.00 0.00 Canceled 2017-07-06 2017-08-06 2017-09-24 2017-11-06 2017-12-11 a nueva aduccion de 20", co ements in the Municipality o nvelope 4 nstruccion 4 modulos de des f Tumaco arenacion, mejoramiento sist ema dosificacion coagulante, construccion 4 modulos de fl oculacion. (2 de 4) PTSP-BIRF8649-004 / Acued ucto Tumaco, Nariño. Red m Component 2. Water Supply atriz continental: suministro and Basic Sanitation Improv Single Stage - One E 2019-06-0 IBRD / 86490 Post Request for Bids Open - National 822,003.00 0.00 Canceled 2017-07-06 2017-08-06 2017-09-24 2017-11-06 2017-12-11 e instalacion de 2229 metros ements in the Municipality o nvelope 4 de tuberia HD y suministro e f Tumaco instalacion de macromedidor es. (3 de 4) PTSP-BIRF8649-005 / Acued Component 2. Water Supply ucto Tumaco, Nariño. Sumini and Basic Sanitation Improv Single Stage - One E 2019-06-0 stro e instalacion de 12331 IBRD / 86490 Post Request for Bids Open - National 1,519,053.00 0.00 Canceled 2017-07-06 2017-08-06 2017-09-24 2017-11-06 2017-12-11 ements in the Municipality o nvelope 4 metros de redes de distribuci f Tumaco on de PVC RDE 21 (4 de 4) PTSP-BIRF8649-055 / CONST RUCCION DE 7.800 M DE AD UCCION EN TUBERIA EN HD DE 20", OPTIMIZACION Y AMP Component 2. Water Supply LIACION DE LA PTAP BUCHEL and Basic Sanitation Improv Open - Internationa Single Stage - One E 2019-01-0 IBRD / 86490 Post Request for Bids 7,779,897.00 0.00 Canceled 2017-08-25 2017-10-17 2017-08-30 2017-10-11 2018-03-14 2017-11-10 2018-06-08 2017-12-15 LI EN 50 LPS, CONSTRUCCIO ements in the Municipality o l nvelope 9 N DE 2.231 M DE RED MATRI f Tumaco Z EN TUBERIA HD, CONSTRU CCION DE 15.298 M DE REDE S DE DISTRIBUCION EN TUBE RIA PVC-POI SEGUNDO Q PTSP-BIRF8649-045 / CONST RUCCION DE 5.500 M DE AD UCCION EN TUBERIA EN HD DE 20", OPTIMIZACION Y AMP Component 2. Water Supply LIACION DE LA PTAP BUCHEL and Basic Sanitation Improv Single Stage - One E 2018-09-1 IBRD / 86490 Post Request for Bids Open - National 6,862,347.00 0.00 Canceled 2017-08-25 2017-08-30 2017-10-20 2017-10-11 2017-11-10 2017-12-15 LI EN 50 LPS, CONSTRUCCIO ements in the Municipality o nvelope 1 N DE 2.231 M DE RED MATRI f Tumaco Z EN TUBERIA HD, CONSTRU CCION DE 15.298 M DE REDE S DE DISTRIBUCION EN TUBE RIA PVC - POI SEGUNDO QUI NQ PTSP-BIRF8649-018 / “Red M Component 2. Water Supply enor de  distribución de la zo and Basic Sanitation Improv Single Stage - One E 2020-05-1 IBRD / 86490 Post Request for Bids Open - National 1,724,138.00 0.00 Canceled 2018-02-01 2018-02-06 2018-03-20 2018-04-19 2018-05-24 na continental fase 2 en el M ements in the Municipality o nvelope 3 unicipio de Tumaco, Departa f Tumaco mento de Nariño” PTSP-BIRF8649-017 / “Const Component 2. Water Supply rucción segunda fase de 20” and Basic Sanitation Improv Single Stage - One E 2019-05-1 en tubería de hierro dúctil pa IBRD / 86490 Post Request for Bids Open - National 1,436,782.00 0.00 Canceled 2018-02-01 2018-02-06 2018-03-20 2018-04-19 2018-05-24 ements in the Municipality o nvelope 9 ra aducción, Municipio de Sa f Tumaco n Andrés de Tumaco, Depart amento de Nariño” PTSP-BIRF8649-014 / Constr Component 1. Water Supply Single Stage - One E 2020-09-1 ucción del sistema definitivo IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 1,353,180.00 0.00 Canceled 2018-06-01 2018-06-06 2018-07-18 2018-08-17 2018-09-21 nvelope 0 de disposición final de residu ements in the Municipality o os. f Guapi PTSP-BIRF8649-013 / Constr Component 1. Water Supply Single Stage - One E 12,865,288.0 2021-07-3 uccion del Sistema de Manej IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 0.00 Canceled 2018-04-02 2018-05-01 2018-06-12 2018-07-12 2018-08-16 nvelope 0 1 o de las Aguas Residuales Ca ements in the Municipality o sco Urbano f Guapi PTSP-BIRF8649-019 / Constr Component 2. Water Supply Single Stage - One E 2019-04-1 ucción nuevo relleno sanitari IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 4,281,100.00 0.00 Canceled 2018-07-01 2018-07-06 2018-08-17 2018-09-16 2018-10-21 nvelope 9 o del municipio de Tumaco ements in the Municipality o f Tumaco PTSP-BIRF8649-074 / "OBRA S DE OPTIMIZACION Y AM PLIACION DEL SISTEMA DE Component 2. Water Supply ACUEDUCTO DEL DISTRIT and Basic Sanitation Improv Single Stage - One E 13,263,597.0 9,353,680.1 2020-11-2 IBRD / 86490 Post Request for Bids Open - National Signed 2019-03-04 2019-03-07 2019-03-06 2019-04-03 2019-04-26 2019-05-03 2019-05-24 2019-06-07 2019-09-13 O ESPECIAL DE TUMACO FA ements in the Municipality o nvelope 0 6 8 SE II, COMPONENTES PARA f Tumaco EL ABASTECIMIENTO A LOS SECTORES DE CONTINENTE E ISLA TUMACO". PTSP-BIRF8649-076 / "OBRA S DE OPTIMIZACION Y AMPLI Component 2. Water Supply ACION DEL SISTEMA DE ACU and Basic Sanitation Improv Single Stage - One E 5,357,696.2 2020-07-2 IBRD / 86490 Post Request for Bids Open - National 7,700,000.00 Signed 2019-04-30 2019-06-07 2019-05-05 2019-06-04 2019-07-15 2019-06-29 2019-10-21 2019-08-03 2019-12-18 EDUCTO DEL DISTRITO ESPE ements in the Municipality o nvelope 6 8 CIAL DE TUMACO FASE I, DEP f Tumaco ARTAMENTO DE NARIÑO, CO LOMBIA" PTSP-BIRF8649-064 / Constr ucción de 7.800 m de aducci ón tubería hd 20", optimizaci Component 2. Water Supply ón y ampliación PTAP Buchell and Basic Sanitation Improv Single Stage - One E 2020-04-1 i 50 lps, construcción de 2.23 IBRD / 86490 Post Request for Bids Open - National 7,733,591.00 0.00 Canceled 2018-12-28 2019-01-02 2019-01-02 2019-02-13 2019-02-26 2019-03-15 2019-04-19 ements in the Municipality o nvelope 3 1 m red matriz tubería hd, co f Tumaco nstruccion de 15.298 m rede s de distribución tubería pvc - poi segundo quinquenio del municipio de Tumaco Page 1 PTSP-BIRF8649-083 / “OPTIM IZACION Y AMPLIACION DEL Component 1. Water Supply SISTEMA DE ACUEDUCTO DE and Basic Sanitation Improv Single Stage - One E 3,118,398.3 2021-04-0 IBRD / 86490 Post Request for Bids Open - National 4,500,000.00 Signed 2019-07-10 2019-08-30 2019-07-12 2019-10-01 2019-08-09 2019-10-28 2019-09-08 2020-03-27 2019-10-13 2017-12-19 LA CABECERA MUNICIPAL DE ements in the Municipality o nvelope 0 5 GUAPI, DEPARTAMENTO DEL f Guapi CAUCA, COLOMBIA – ETAPA I ” PTSP-BIRF8649-100 / OBRAS DE OPTIMIZACIÓN Y AMPLIAC Component 2. Water Supply IÓN DEL SISTEMA DE ACUED and Basic Sanitation Improv Single Stage - One E 2020-10-1 IBRD / 86490 Post Request for Bids Open - National 1,262,000.00 902,276.97 Signed 2020-01-10 2020-01-17 2020-01-15 2020-02-14 2020-03-04 2020-03-10 2020-04-07 2020-04-14 2020-08-21 UCTO DEL DISTRITO ESPECIA ements in the Municipality o nvelope 3 L DE TUMACO, DEPARTAMEN f Tumaco TO DE NARIÑO, COLOMBIA - FASE III ETAPA I PTSP-BIRF8649-146 / Constr National Procure Component 1. Water Supply ucción de la Fase II de acued ment Document - and Basic Sanitation Improv Single Stage - One E Pending Imp 2023-05-3 ucto GUAPI (técnico+ gestión IBRD / 86490 Post Request for Bids Open - National 1 Envelope proce 3,080,000.00 0.00 2022-05-27 2022-05-29 2022-06-26 2022-07-26 2022-08-30 ements in the Municipality o nvelope lementation 0 social+ambiental) - LICITACI ss (Non Bank-SPD f Guapi ON PUBLICA NACIONAL - LPN ) PTSP-BIRF8649-147 / Constr National Procure Component 1. Water Supply ucción de la Fase III de acued ment Document - and Basic Sanitation Improv Single Stage - One E Pending Imp 2023-04-2 ucto GUAPI (técnico+ gestión IBRD / 86490 Post Request for Bids Open - National 1 Envelope proce 2,110,000.00 0.00 2022-05-27 2022-05-29 2022-06-26 2022-07-26 2022-08-30 ements in the Municipality o nvelope lementation 8 social+ambiental) - LICITACI ss (Non Bank-SPD f Guapi ON PUBLICA NACIONAL - LPN ) National Procure PTSP-BIRF8649-152 / Constr Component 1. Water Supply ment Document - Single Stage - One E Pending Imp 2023-08-0 ucción obras cierre botadero IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 1 Envelope proce 557,000.00 0.00 2022-04-29 2022-05-01 2022-05-29 2022-06-28 2022-08-02 nvelope lementation 2 barrio El Olimpico GUAPI ements in the Municipality o ss (Non Bank-SPD f Guapi ) National Procure PTSP-BIRF8649-153 / Constr Component 2. Water Supply ment Document - Single Stage - One E Pending Imp 2023-08-2 ucción de obra Fase 3 etapa IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 1 Envelope proce 9,950,000.00 0.00 2022-01-20 2022-01-22 2022-02-19 2022-03-21 2022-04-25 nvelope lementation 5 2 (PTAP) ements in the Municipality o ss (Non Bank-SPD f Tumaco ) National Procure PTSP-BIRF8649-154 / Constr Component 2. Water Supply ment Document - Single Stage - One E Pending Imp 2023-09-2 ucción de obra Fase 4 E1 (ob IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 1 Envelope proce 4,820,000.00 0.00 2022-02-16 2022-02-18 2022-03-18 2022-04-17 2022-05-22 nvelope lementation 1 ras Morro) ements in the Municipality o ss (Non Bank-SPD f Tumaco ) National Procure PTSP-BIRF8649-155 / Constr Component 2. Water Supply ment Document - Single Stage - One E Pending Imp 2023-09-2 ucción acueducto - Fase 4 E2 IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 1 Envelope proce 740,000.00 0.00 2022-02-16 2022-02-18 2022-03-18 2022-04-17 2022-05-22 nvelope lementation 1 (Paso de aguas claras) ements in the Municipality o ss (Non Bank-SPD f Tumaco ) National Procure PTSP-BIRF8649-163 / Constr Component 1. Water Supply ment Document - Single Stage - One E 14,500,000.0 Pending Imp 2024-12-0 ucción alcantarillado GUAPI - IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 1 Envelope proce 0.00 2023-01-10 2023-01-12 2023-02-09 2023-03-11 2023-04-15 nvelope 0 lementation 3 implementación alcantarillad ements in the Municipality o ss (Non Bank-SPD o Condominial f Guapi ) National Procure PTSP-BIRF8649-165 / Constr Component 2. Water Supply ment Document - ucción alcantarillado Tumaco and Basic Sanitation Improv Single Stage - One E 14,800,000.0 Pending Imp 2024-07-1 IBRD / 86490 Post Request for Bids Open - National 1 Envelope proce 0.00 2023-02-10 2023-02-12 2023-03-12 2023-04-11 2023-05-16 (obras derivadas del ajuste al ements in the Municipality o nvelope 0 lementation 8 ss (Non Bank-SPD Plan Maestro de Alcantarillad f Tumaco ) o) National Procure PTSP-BIRF8649-166 / Constr Component 2. Water Supply ment Document - Single Stage - One E 14,800,000.0 Pending Imp 2024-01-0 ucción piloto alcantarillado C IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 1 Envelope proce 0.00 2022-09-30 2022-10-02 2022-10-30 2022-11-29 2023-01-03 nvelope 0 lementation 3 ondominial Tumaco ements in the Municipality o ss (Non Bank-SPD f Tumaco ) National Procure PTSP-BIRF8649-149 / Constr Component 1. Water Supply ment Document - ucción del centro de restaura and Basic Sanitation Improv Single Stage - One E Pending Imp 2023-01-0 IBRD / 86490 Post Request for Bids Open - National 1 Envelope proce 430,000.00 0.00 2022-01-12 2022-01-17 2022-02-28 2022-03-30 2022-05-04 ción ambiental CRAU - LICITA ements in the Municipality o nvelope lementation 5 ss (Non Bank-SPD CION PUBLICA NACIONAL - LP f Guapi ) N GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF8649-092 / Adquisi ción de un (1) Vehículo Comp Component 2. Water Supply actador Para La Prestación D and Basic Sanitation Improv Single Stage - One E IBRD / 86490 Post Request for Bids Open - National 154,000.00 102,817.39 Signed 2019-10-28 2019-11-29 2019-11-06 2019-12-18 2020-01-21 2020-01-17 2020-03-30 2020-02-21 2020-07-22 2020-08-19 el Servicio Público De Aseo E ements in the Municipality o nvelope n El Distrito De San Andrés D f Tumaco e Tumaco Departamento de Nariño PTSP-BIRF8649-094 / CARAC Component 3. Capacity Buil TERIZACIÓN DE AGUA CRUD ding and Institutional Streng A Y MEDICIÓN DE NIVEL ESTA Request for Quota Single Stage - One E IBRD / 86490 thening of Service Providers Post Open - National 13,800.00 11,563.31 Signed 2019-11-02 2019-12-28 2021-01-28 2020-06-25 TICO EN LOS POZOS Ccgua- tions nvelope in the Municipalities of Guap 01 - Ccgua-02, MUNICIPIO GU i and Tum aco API, DEPARTAMENTO CAUCA PTSP-BIRF8649-095 / SONDA Component 3. Capacity Buil DE NIVEL PARA MEDICIÓN DE ding and Institutional Streng Request for Quota Single Stage - One E NIVEL ESTATICO EN LOS PO IBRD / 86490 thening of Service Providers Post Open - National 5,200.00 2,240.94 Signed 2019-11-02 2019-12-28 2020-11-13 2020-06-25 tions nvelope ZOS Ccgua-01 - Ccgua-02, M in the Municipalities of Guap UNICIPIO GUAPI, DEPARTAME i and Tum aco NTO CAUCA Component 3. Capacity Buil PTSP-BIRF8649-118 / Adquiri ding and Institutional Streng Request for Quota Single Stage - One E r motobombas y accesorios h IBRD / 86490 Post Open - National 81,226.00 44,630.67 Signed 2020-07-13 2020-09-07 2020-11-04 2020-10-07 thening of Service Providers tions nvelope idráulicos in the Municipalities of Guap i and Tum aco Component 3. Capacity Buil PTSP-BIRF8649-119 / Adquiri ding and Institutional Streng Request for Quota Single Stage - One E r tanques para almacenamie IBRD / 86490 Post Open - National 90,263.00 140,822.49 Signed 2020-07-13 2020-09-07 2020-12-10 2020-10-07 thening of Service Providers tions nvelope nto de agua in the Municipalities of Guap i and Tum aco Component 3. Capacity Buil PTSP-BIRF8649-120 / Adquiri ding and Institutional Streng Request for Quota Single Stage - One E IBRD / 86490 Post Open - National 16,197.00 17,599.95 Signed 2020-07-13 2020-09-07 2020-11-06 2020-10-22 r moto cargueros thening of Service Providers tions nvelope in the Municipalities of Guap i and Tum aco Component 3. Capacity Buil PTSP-BIRF8649-121 / Adquiri ding and Institutional Streng Request for Quota Single Stage - One E IBRD / 86490 Post Open - National 12,009.00 56,225.83 Signed 2020-07-13 2020-09-07 2020-11-12 2020-10-22 r filtros purificadores de agua thening of Service Providers tions nvelope in the Municipalities of Guap i and Tum aco Component 3. Capacity Buil PTSP-BIRF8649-122 / Adquiri ding and Institutional Streng Request for Quota Single Stage - One E r estructuras de soporte met IBRD / 86490 Post Open - National 38,541.00 44,630.67 Signed 2020-07-13 2020-09-07 2020-11-20 2020-10-07 thening of Service Providers tions nvelope álicas in the Municipalities of Guap i and Tum aco Page 2 PTSP-BIRF8649-160 / Adquisi Component 2. Water Supply Single Stage - One E Pending Impl ción de segundo vehículo co IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 141,000.00 0.00 2022-01-31 2022-02-09 2022-03-23 2022-04-22 2022-05-27 2022-11-23 nvelope ementation mpactador ements in the Municipality o f Tumaco PTSP-BIRF8649-168 / Adquisi Component 2. Water Supply ción de equipos resultado de and Basic Sanitation Improv Single Stage - One E Pending Impl IBRD / 86490 Post Request for Bids Open - National 1,037,000.00 0.00 2022-11-16 2022-11-21 2023-01-02 2023-02-01 2023-03-08 2023-12-29 la consultoría reingenieria Bu ements in the Municipality o nvelope ementation cheli (bulldozer + pajarita) f Tumaco PTSP-BIRF8649-182 / Adquiri r un (1) vehículo compactado Component 2. Water Supply r de residuos sólidos para la and Basic Sanitation Improv Single Stage - One E Pending Impl IBRD / 86490 Post Request for Bids Open - National 136,476.00 0.00 2022-07-06 2022-07-11 2022-08-22 2022-09-21 2022-10-26 2023-04-24 prestación del servicio públic ements in the Municipality o nvelope ementation o de aseo en el Distrito de Sa f Tumaco n Andrés de Tumaco – Nariño . NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF8649-053 / Progra Component 1. Water Supply Request for Quota Single Stage - One E ma de monitoreo de aguas s IBRD / 86490 and Basic Sanitation Improv Post Limited 17,242.00 0.00 Canceled 2017-12-27 2018-02-21 2018-05-22 tions nvelope ub-superficiales ements in the Municipality o f Guapi PTSP-BIRF8649-078 / ADQUI SICIÓN EN MODALIDAD DE A Component 3. Capacity Buil RRENDAMIENTO DE UN SOFT ding and Institutional Streng WARE INTEGRAL QUE PERMIT Request for Quota Single Stage - One E IBRD / 86490 thening of Service Providers Post Open - National 86,210.00 0.00 Canceled 2019-11-18 2020-01-16 2020-10-30 A A AGUAS DE TUMACO SA E tions nvelope in the Municipalities of Guap SP, EJECUTAR EN FORMA EFI i and Tum aco CIENTE EL CONTROL DE LOS PROCESOS COMERCIALES, C ONTABLES Y FINANCIEROS" CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1. Water Supply PTSP-BIRF8649-015 / Consul Quality And Cost- IBRD / 86490 and Basic Sanitation Improv Post Open - National 112,024.00 101,622.79 Signed 2017-07-01 2017-10-02 2017-07-22 2017-10-02 2017-09-04 2017-11-07 2017-10-02 2018-01-19 2017-11-01 2018-02-07 2017-12-06 2018-02-15 2018-01-10 2018-02-23 2018-08-08 toría Restauración Urbana Based Selection ements in the Municipality o f Guapi PTSP-BIRF8649-021 / Asisten Component 3. Capacity Buil cia fortalecimiento institucio ding and Institutional Streng Consultant Qualifi IBRD / 86490 Post Open - National 235,000.00 78,605.00 Signed 2018-06-01 2018-05-17 2018-06-22 2018-08-05 2018-08-31 2018-09-04 2018-12-03 2018-10-09 2018-12-03 2020-09-28 nal Aguas de Tumaco en el a thening of Service Providers cation Selection rea urbana in the Municipalities of Guap i and Tum aco Component 4. Project Manag PTSP-BIRF8649-043 / Auditor Quality And Cost- IBRD / 86490 ement and Environmental a Post Open - National 450,000.00 0.00 Canceled 2017-08-01 2017-09-01 2017-10-15 2017-11-12 2017-12-12 2018-01-16 2018-02-20 2019-02-15 ia Externa Based Selection nd Social Management PTSP-BIRF8649-001 / Interve Component 2. Water Supply ntoría integral para obras de and Basic Sanitation Improv Quality And Cost- Open - Internationa IBRD / 86490 Prior 6,266,775.00 0.00 Canceled 2016-12-14 2017-01-28 2016-12-16 2017-03-14 2017-04-13 2017-05-13 2017-06-12 2017-07-07 2023-07-06 acueducto, alcantarillado y r ements in the Municipality o Based Selection l esiduos sólidos en el Municipi f Tumaco o de Tumaco. PTSP-BIRF8649-049 / Interve Component 2. Water Supply ntoria integral para obras de and Basic Sanitation Improv Quality And Cost- Open - Internationa IBRD / 86490 Prior 5,762,334.24 4,364,033.42 Signed 2017-12-20 2017-12-21 2018-01-12 2017-12-21 2018-02-25 2018-05-28 2018-03-25 2018-09-11 2018-04-24 2019-03-27 2018-05-29 2019-08-10 2018-07-03 2019-09-13 2022-07-02 acueducto y alcantarillado y ements in the Municipality o Based Selection l residuos sòlidos en el Munici f Tumaco pio de Tumaco PTSP-BIRF8649-062 / REALIZ AR LOS ESTUDIOS Y DISEÑOS PARA LA PLANTA DE TRATAM Component 1. Water Supply IENTO AGUAS RESIDUALES D and Basic Sanitation Improv Quality And Cost- IBRD / 86490 Post Open - National 259,310.00 0.00 Canceled 2018-06-15 2018-09-04 2018-07-06 2018-08-19 2018-09-16 2018-10-01 2018-10-19 2018-11-13 2019-06-11 EL MUNICIPIO DE GUAPI, DEP ements in the Municipality o Based Selection ARTAMENTO DEL CAUCA, EN f Guapi EL MARCO DEL FONDO PARA EL DESARROLLO DEL PLAN T ODOS SOMOS PAZCÍFICO PTSP-BIRF8649-041 / Asisten Component 3. Capacity Buil cia fortalecimiento institucio ding and Institutional Streng Consultant Qualifi IBRD / 86490 Post Open - National 235,000.00 0.00 Canceled 2018-06-01 2018-06-22 2018-08-05 2018-09-04 2018-10-09 2020-09-28 nal Aguas de Tumaco (para e thening of Service Providers cation Selection l piloto de la politica en el are in the Municipalities of Guap a rural) i and Tum aco PTSP-BIRF8649-022 / Imple Component 4. Project Manag Least Cost Selecti mentacion del Plan de Inform IBRD / 86490 ement and Environmental a Post Open - National 400,000.00 0.00 Canceled 2017-11-01 2018-09-13 2017-11-22 2018-01-05 2018-02-02 2018-03-04 2018-04-08 2018-05-13 2018-11-09 on acion, Comunicacion y Partici nd Social Management pacion PTSP-BIRF8649-016 / Interve Component 1. Water Supply ntoria Obras Alcantarillado, A and Basic Sanitation Improv Quality And Cost- IBRD / 86490 Prior Open - National 2,333,451.00 0.00 Canceled 2018-05-21 2018-06-11 2018-07-25 2018-08-22 2018-09-21 2018-10-26 2018-11-30 2019-11-30 cueducto y Residuos Solidos ements in the Municipality o Based Selection en Municipio de Guapi f Guapi PTSP-BIRF8649-082 / Interve ntoría técnica, administrativa Component 1. Water Supply , financiera, legal, ambiental and Basic Sanitation Improv Quality And Cost- Open - Internationa y social para los estudios, dis IBRD / 86490 Prior 2,900,000.00 1,741,709.58 Signed 2019-07-10 2019-07-17 2019-08-02 2019-08-12 2019-09-15 2020-02-17 2019-10-13 2020-05-21 2019-11-12 2020-07-22 2019-12-17 2020-09-29 2020-01-21 2020-10-16 2024-01-20 ements in the Municipality o Based Selection l eños y obras de los sistemas f Guapi de acueducto y alcantarillado y proyectos de residuos sólid os del municipio de Guapi. PTSP-BIRF8649-096 / ACOMP Component 3. Capacity Buil AÑAR A EMGUAPI S.A.S. ESP ding and Institutional Streng EN LA OPERACIÓN DE LOS SE Quality And Cost- IBRD / 86490 thening of Service Providers Post Open - National 662,000.00 377,390.55 Signed 2019-10-31 2020-05-28 2019-11-21 2020-01-04 2020-07-24 2020-02-01 2020-09-22 2020-03-02 2020-10-29 2020-04-06 2020-11-23 2020-05-11 2021-03-04 2021-04-06 RVICIOS PÚBLICOS DE ACUE Based Selection in the Municipalities of Guap DUCTO, ALCANTARILLADO Y i and Tum aco ASEO Y ESTRUCTURACIÓN D EL SERVICIO PUBICOS DE AS EO. PTSP-BIRF8649-097 / Desarr ollar la Interventoría técnica, Component 3. Capacity Buil operativa, administrativa, co ding and Institutional Streng Quality And Cost- mercial, financiera, contable, IBRD / 86490 thening of Service Providers Post Open - National 215,000.00 111,207.81 Signed 2019-10-31 2020-01-28 2019-11-21 2020-01-04 2020-01-28 2020-02-01 2020-07-15 2020-03-02 2020-10-09 2020-04-06 2020-11-09 2020-05-11 2021-01-28 2021-05-11 Based Selection ambiental, social y jurídica al in the Municipalities of Guap proyecto de acompañamient i and Tum aco o a la empresa E guapi S.A. E SP. En el municipio de Guapi – Cauca. Page 3 PTSP-BIRF8649-077 / INTERV ENTORÍA TÉCNICA, ADMINIST RATIVA, FINANCIERA, CONTA Component 3. Capacity Buil BLE, AMBIENTAL, SOCIAL Y JU ding and Institutional Streng Quality And Cost- RÍDICA PARA LA "CONSULTO IBRD / 86490 thening of Service Providers Post Open - National 211,800.00 0.00 Canceled 2019-04-30 2019-10-01 2019-05-21 2019-07-04 2019-08-01 2019-08-31 2019-10-05 2019-11-09 2020-11-08 Based Selection RÍA DE ACOMPAÑAMIENTO E in the Municipalities of Guap N LA OPERACIÓN DE LOS SER i and Tum aco VICIOS PÚBLICOS DE ACUED UCTO, ALCANTARILLADO Y A SEO PARA EMGUAPI SAS ESP PTSP-BIRF8649-079 / FORTA Component 3. Capacity Buil LECIMIENTO Y ACOMPAÑAMI ding and Institutional Streng ENTO EN LA OPERACIÓN DE Quality And Cost- IBRD / 86490 thening of Service Providers Post Open - National 1,380,000.00 0.00 Canceled 2019-04-30 2019-10-01 2019-05-21 2019-07-04 2019-08-01 2019-08-31 2019-10-05 2019-11-09 2020-11-08 LOS SERVICIOS PÚBLICOS DE Based Selection in the Municipalities of Guap ACUEDUCTO, ALCANTARILLA i and Tum aco DO Y ASEO DEL OPERADOR DE GUAPI - FASE I, II Y III PTSP-BIRF8649-056 / Consul Component 1. Water Supply toría de Diseño de la Planta d and Basic Sanitation Improv Quality And Cost- e Tratamiento de Aguas de R IBRD / 86490 Post Open - National 141,300.00 0.00 Canceled 2018-05-02 2019-09-27 2018-05-23 2018-07-06 2018-08-03 2018-09-02 2018-10-07 2018-11-11 2019-11-11 ements in the Municipality o Based Selection esiduales para el Sistema de f Guapi Alcantarillado del Municipio d e Guapi Component 3. Capacity Buil PTSP-BIRF8649-020 / Asegur ding and Institutional Streng Quality And Cost- amiento en la prestación de l IBRD / 86490 Post Open - National 1,800,000.00 0.00 Canceled 2018-06-01 2019-09-27 2018-06-22 2018-08-05 2018-09-02 2018-10-02 2018-11-06 2018-12-11 2019-12-11 thening of Service Providers Based Selection os servicios públicos Guapi. in the Municipalities of Guap i and Tum aco PTSP-BIRF8649-112 / Auditor ía a los Estados Financieros d Component 4. Project Manag Least Cost Selecti e Propósito Especial de Proye IBRD / 86490 ement and Environmental a Post Open - National 31,050.00 0.00 Canceled 2020-05-15 2020-05-14 2020-06-05 2020-07-19 2020-08-16 2020-09-15 2020-10-20 2020-11-24 2021-04-23 on ctos Financiados por el Banc nd Social Management o Mundial a través de présta mos PTSP-BIRF8649-137 / Consul toría para realizar el ajuste y complementación a los estud Component 1. Water Supply ios y diseños de las Etapas II and Basic Sanitation Improv Consultant Qualifi IBRD / 86490 Post Open - National 77,860.00 109,528.65 Signed 2021-04-29 2021-05-10 2021-05-20 2021-06-18 2021-07-21 2021-07-08 2021-08-10 2021-08-12 2022-03-06 2021-12-12 y III del proyecto denominad ements in the Municipality o cation Selection o “OPTIMIZACIÓN Y AMPLIACI f Guapi ÓN DEL SISTEMA DE ACUEDU CTO DE LA CABECERA MUNIC IPAL DE GUAPI, CAUCA”. PTSP-BIRF8649-142 / ESTRU CTURACIÓN DE UN NUEVO E Component 3. Capacity Buil SQUEMA DE PRESTACIÓN DE ding and Institutional Streng Quality And Cost- Under Implement LOS SERVICIOS PÚBLICOS DE IBRD / 86490 thening of Service Providers Post Open - National 334,200.00 0.00 2021-09-28 2021-09-29 2021-10-19 2021-11-17 2021-12-15 2021-12-30 2022-01-28 2022-03-04 2023-02-02 Based Selection ation ACUEDUCTO Y ALCANTARILL in the Municipalities of Guap ADO EN EL MUNICIPIO DE SA i and Tum aco N ANDRÉS DE TUMACO, DEP ARTAMENTO DE NARIÑO PTSP-BIRF8649-156 / Consul Component 2. Water Supply toria de ajustes de estudios y and Basic Sanitation Improv Quality And Cost- Pending Impleme IBRD / 86490 Post Open - National 360,000.00 0.00 2022-01-20 2022-02-10 2022-03-11 2022-04-08 2022-04-23 2022-05-08 2022-06-12 2023-02-15 diseños Plan Maestro de alca ements in the Municipality o Based Selection ntation ntarillado TUMACO f Tumaco PTSP-BIRF8649-164 / Servici Component 3. Capacity Buil os resultado de consultoría d ding and Institutional Streng Quality And Cost- Pending Impleme IBRD / 86490 Post Open - National 1,700,000.00 0.00 2022-02-24 2022-03-17 2022-04-10 2022-05-08 2022-05-23 2022-06-17 2022-07-22 2023-07-22 e fortalecimiento instituciona thening of Service Providers Based Selection ntation l y el tema de aprovechamie in the Municipalities of Guap nto i and Tum aco PTSP-BIRF8649-167 / Consul Component 2. Water Supply Quality And Cost- Open - Internationa Pending Impleme toria de estudios y diseños n IBRD / 86490 and Basic Sanitation Improv Post 489,000.00 0.00 2022-06-15 2022-07-06 2022-08-19 2022-09-16 2022-10-16 2022-11-20 2022-12-25 2023-12-25 Based Selection l ntation uevo relleno sanitario ements in the Municipality o f Tumaco PTSP-BIRF8649-161 / Ejecuci Component 3. Capacity Buil ón - Fase II. Acompañamient ding and Institutional Streng o en la recepción y operación Quality And Cost- Open - Internationa Pending Impleme IBRD / 86490 thening of Service Providers Post 461,000.00 0.00 2022-02-16 2022-03-09 2022-04-22 2022-05-20 2022-06-19 2022-07-24 2022-08-28 2023-08-28 de las obras de acueducto, al Based Selection l ntation in the Municipalities of Guap cantarillado. Diseño, estructu i and Tum aco ración e implementación de l a operación del SPA PTSP-BIRF8649-159 / Consul Component 2. Water Supply Consultant Qualifi Pending Impleme toría para inclusión social de IBRD / 86490 and Basic Sanitation Improv Post Open - National 213,000.00 0.00 2022-04-27 2022-05-18 2022-07-01 2022-07-31 2022-09-04 2023-06-04 cation Selection ntation recicladores ements in the Municipality o f Tumaco PTSP-BIRF8649-158 / Consul Component 2. Water Supply Consultant Qualifi Pending Impleme toría de estudios y diseños M IBRD / 86490 and Basic Sanitation Improv Post Open - National 285,000.00 0.00 2022-01-20 2022-02-10 2022-02-25 2022-03-12 2022-04-16 2022-10-20 cation Selection ntation ineria Bucheli TUMACO ements in the Municipality o f Tumaco PTSP-BIRF8649-151 / Consul Component 1. Water Supply Consultant Qualifi Pending Impleme toría de estudios y diseños ci IBRD / 86490 and Basic Sanitation Improv Post Open - National 245,000.00 0.00 2022-03-16 2022-04-06 2022-05-05 2022-05-25 2022-06-27 2023-02-27 cation Selection ntation erre botadero barrio El Olimp ements in the Municipality o ico GUAPI f Guapi PTSP-BIRF8649-150 / Consul Component 1. Water Supply Consultant Qualifi Under Implement toría para aprovechamiento IBRD / 86490 and Basic Sanitation Improv Post Open - National 278,000.00 0.00 2022-01-17 2022-02-21 2022-02-07 2022-03-08 2022-03-28 2022-04-30 2023-01-31 cation Selection ation de residuos orgánicos ements in the Municipality o f Guapi PTSP-BIRF8649-157 / Consul Component 2. Water Supply toria de diseños de ingenierí and Basic Sanitation Improv Consultant Qualifi Pending Impleme IBRD / 86490 Post Open - National 155,000.00 0.00 2022-02-17 2022-03-10 2022-03-25 2022-04-09 2022-05-14 2022-09-15 a y proyecto social alcantarill ements in the Municipality o cation Selection ntation ado condominial Tumaco f Tumaco PTSP-BIRF8649-162 / Ejecuci Component 3. Capacity Buil ón - Fase III. Acompañamient ding and Institutional Streng Consultant Qualifi Pending Impleme o en el diseño e implementac IBRD / 86490 thening of Service Providers Post Open - National 248,000.00 0.00 2023-01-18 2023-02-08 2023-03-24 2023-04-23 2023-05-28 2023-10-28 cation Selection ntation ión del sistema de seguimien in the Municipalities of Guap to y monitoreo de la operació i and Tum aco n PTSP-BIRF8649-169 / INTERV ENTORÍA PARA LA CONSULTO RÍA QUE TIENE COMO OBJET Component 3. Capacity Buil O LA “ESTRUCTURACIÓN DE ding and Institutional Streng Consultant Qualifi Under Implement UN NUEVO ESQUEMA DE PRE IBRD / 86490 thening of Service Providers Post Open - National 78,000.00 0.00 2022-01-21 2022-02-04 2022-02-11 2022-03-12 2022-04-01 2022-05-06 2023-05-05 cation Selection ation STACIÓN DE LOS SERVICIOS in the Municipalities of Guap PÚBLICOS DE ACUEDUCTO Y i and Tum aco ALCANTARILLADO EN EL MU NICIPIO DE SAN ANDRÉS DE TUMACO, DEPARTAMENTO D E NARIÑO”. Page 4 PTSP-BIRF8649-170 / REALIZ AR LOS ESTUDIOS PARA LA C ONCEPCIÓN DE UN SISTEMA CONDOMINIAL Component 1. Water Supply DE ALCANTARILLADO SANITA and Basic Sanitation Improv Quality And Cost- Open - Internationa Under Implement IBRD / 86490 Post 408,000.00 0.00 2022-02-14 2022-02-09 2022-03-07 2022-02-17 2022-04-05 2022-05-03 2022-05-18 2022-06-22 2022-07-27 2023-03-24 RIO Y DISEÑO DE PROYECTO ements in the Municipality o Based Selection l ation S BÁSICOS PARA SU f Guapi IMPLEMENTACIÓN EN LA CAB ECERA MUNICIPAL DE GUAPI, DEPARTAMENTO DEL CAUCA. PTSP-BIRF8649-183 / Realiza r la actualización y ajuste del Estudio de evaluación de imp Component 2. Water Supply acto ambiental y social EIAS and Basic Sanitation Improv Consultant Qualifi Under Implement IBRD / 86490 Post Open - National 61,352.00 0.00 2022-07-11 2022-07-15 2022-08-01 2022-09-14 2022-10-14 2022-11-18 2023-05-17 para la optimización del relle ements in the Municipality o cation Selection ation no sanitario de Tumaco de ac f Tumaco uerdo con lo requerido por la s salvaguardas ambientales y sociales de Banco Mundial. PTSP-BIRF8649-143 / CONSU LTORÍA PARA REALIZAR LA A CTUALIZACIÓN, AJUSTE Y CO MPLEMENTACIÓN DE LOS ES Component 1. Water Supply TUDIOS Y DISEÑOS EXISTENT and Basic Sanitation Improv Quality And Cost- IBRD / 86490 Post Open - National 363,000.00 0.00 Canceled 2021-10-18 2021-11-08 2021-12-22 2022-01-19 2022-02-18 2022-03-25 2022-04-29 2023-01-04 ES DE ALCANTARILLADO SAN ements in the Municipality o Based Selection ITARIO Y REALIZAR LOS ESTU f Guapi DIOS PARA LA CONCEPCIÓN DE UN SISTEMA CONDOMINIA L DE ALCANTARILLADO SANI TARIO Y DISEÑO DE PROYECT OS PTSP-BIRF8649-148 / Consul toría de ajuste y complement Component 1. Water Supply ación del plan maestro de alc and Basic Sanitation Improv Quality And Cost- IBRD / 86490 Post Open - National 359,000.00 0.00 Canceled 2022-02-28 2022-03-21 2022-05-04 2022-06-01 2022-07-01 2022-08-05 2022-09-09 2023-05-30 antarillado + diseños de inge ements in the Municipality o Based Selection niería + proyecto social alca f Guapi ntarillado condominial Guapi INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF8649-010 / Apoyar el componente social, en el D epartamento del Cauca en la Component 4. Project Manag Individual Consult implementaciòn y ejecuciòn IBRD / 86490 ement and Environmental a Post Open 21,450.78 16,386.55 Completed 2017-05-11 2017-08-16 2017-06-05 2017-06-15 2017-09-06 2017-07-05 2017-09-18 2018-07-05 2018-09-17 ant Selection del FDPTSP que adelanta co nd Social Management mo entidad ejecutora la Unid ad Nacional para la Gestiòn d el Riesgo de Desastres. PTSP-BIRF8649-009 / Liderar el componente social, en la i mplementación y ejecución d Component 4. Project Manag el Fondo para el Desarrollo d Individual Consult IBRD / 86490 ement and Environmental a Post Open 82,299.37 62,869.64 Completed 2017-05-11 2017-08-28 2017-06-11 2017-06-21 2017-09-18 2018-07-01 2017-09-18 2018-12-28 2018-09-18 el Plan Todos Somos Pazcífic ant Selection nd Social Management o que adelanta como entidad ejecutora la Unidad Nacional para la Gestión del Riesgo de Desastres. PTSP-BIRF8649-007 / Brindar apoyo al FTSP que adelanta c omo entidad ejecutora la Uni dad Nacional para la Gestión Component 4. Project Manag Individual Consult del Riesgo de Desastres, en l IBRD / 86490 ement and Environmental a Post Open 48,873.76 36,452.16 Signed 2017-06-01 2017-05-22 2017-06-16 2017-07-01 2017-06-19 2017-07-21 2017-06-27 2018-07-21 ant Selection a viabilización de proyectos d nd Social Management el componente de Agua y Sa neamiento Básico, ante el Mi nisterio de Vivienda, Ciudad y Territorio - MVCT PTSP-BIRF8649-006 / Brindar apoyo al FTSP en la coordina ción de las acciones y activid Component 4. Project Manag ades al interior del MVCT rela Individual Consult IBRD / 86490 ement and Environmental a Post Open 56,033.61 40,456.30 Signed 2017-06-01 2018-04-18 2017-06-16 2017-06-21 2018-05-03 2017-07-02 2018-05-18 2018-07-02 cionadas con el crédito para ant Selection nd Social Management dar respuesta a los requerimi entos de la Banca Multilatera l y las entidades del gobierno nacional PTSP-BIRF8649-008 / Apoyar el componente social, en el D epartamento de Nariño en la implementación y ejecución Component 4. Project Manag Individual Consult del Fondo para el Desarrollo IBRD / 86490 ement and Environmental a Post Open 21,450.78 1,660.60 Signed 2017-05-18 2017-08-22 2017-06-11 2017-06-26 2017-09-12 2017-07-16 2018-04-03 2018-07-16 ant Selection del Plan Todos Somos Pazcífi nd Social Management co que adelanta como entida d ejecutora la Unidad Nacion al para la Gestión del Riesgo de Desastres. Component 4. Project Manag PTSP-BIRF8649-024 / Apoyo Individual Consult IBRD / 86490 ement and Environmental a Post Open 17,908.97 12,960.77 Completed 2017-05-16 2017-03-22 2017-07-04 2017-07-25 2017-05-19 2017-08-29 2017-05-19 2018-02-25 2018-05-18 Administrativo (nivel técnico) ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-028 / Lider d Individual Consult IBRD / 86490 ement and Environmental a Post Direct 99,507.79 63,711.53 Completed 2017-03-01 2017-03-01 2017-03-11 2017-04-01 2017-03-06 2017-05-06 2017-03-16 2017-11-02 2018-03-15 e Adquisiciones ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-029 / Especi Individual Consult IBRD / 86490 ement and Environmental a Post Open 70,938.36 48,197.86 Completed 2017-04-01 2017-03-20 2017-05-20 2017-03-22 2017-06-10 2017-04-03 2017-07-15 2017-04-04 2018-01-11 2018-04-03 alista Adquisiciones ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-033 / Lider A Individual Consult IBRD / 86490 ement and Environmental a Post Direct 93,771.65 61,167.00 Signed 2017-04-01 2017-03-22 2017-04-11 2017-03-24 2017-05-02 2017-03-28 2017-06-06 2017-04-04 2017-12-03 mbiental ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-034 / Especi Individual Consult IBRD / 86490 ement and Environmental a Post Open 56,458.32 36,452.16 Completed 2017-06-01 2017-08-01 2017-07-20 2017-08-08 2017-08-10 2017-08-15 2017-09-14 2017-04-04 2018-03-13 2018-04-03 alista ambiental ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-035 / Lider C Individual Consult IBRD / 86490 ement and Environmental a Post Direct 99,507.79 61,167.00 Signed 2017-03-01 2017-03-02 2017-03-11 2017-04-01 2017-03-13 2017-05-06 2017-03-16 2017-11-02 omponente Agua ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-036 / Especi Individual Consult IBRD / 86490 ement and Environmental a Post Direct 63,844.53 41,645.62 Signed 2017-04-01 2017-03-17 2017-04-11 2017-05-02 2017-03-22 2017-06-06 2018-04-05 2017-12-03 alista Proyectos Agua ant Selection nd Social Management Page 5 Component 4. Project Manag PTSP-BIRF8649-037 / Especi Individual Consult IBRD / 86490 ement and Environmental a Post Open 56,033.61 36,452.16 Signed 2017-06-01 2017-11-01 2017-07-20 2017-08-10 2017-11-20 2017-09-14 2017-11-20 2018-03-13 alista Proyectos RSU ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-038 / Ingenie Individual Consult IBRD / 86490 ement and Environmental a Post Open 35,053.71 16,386.55 Completed 2017-06-01 2017-07-19 2017-07-20 2017-08-10 2017-08-15 2017-09-14 2017-08-31 2018-03-13 2018-08-30 ro de apoyo (Agua Tumaco) ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-039 / Ingenie Individual Consult IBRD / 86490 ement and Environmental a Post Open 35,053.71 19,500.00 Completed 2017-06-01 2017-12-12 2017-07-20 2017-08-10 2018-01-03 2017-09-14 2017-09-25 2018-03-13 2018-09-24 ro de apoyo ( Agua Guapi) ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-040 / Apoyo Individual Consult IBRD / 86490 ement and Environmental a Post Open 16,742.07 12,960.77 Completed 2017-06-01 2017-06-28 2017-07-20 2017-09-12 2017-08-10 2017-09-18 2017-09-14 2017-09-22 2018-03-13 2018-09-21 Administrativo (lideres) ant Selection nd Social Management PTSP-BIRF8649-023 / Coordi Component 4. Project Manag Individual Consult nación General - LUZ AMAND IBRD / 86490 ement and Environmental a Post Direct 116,664.30 71,591.30 Signed 2017-03-01 2017-03-08 2017-03-11 2017-03-16 2017-04-01 2017-03-10 2017-05-06 2017-03-16 2017-11-02 ant Selection A PULIDO nd Social Management PTSP-BIRF8649-026 / Lider Fi Component 4. Project Manag Individual Consult nanciero - CLAUDIA AGUDEL IBRD / 86490 ement and Environmental a Post Direct 99,507.79 63,711.53 Completed 2017-03-01 2017-02-15 2017-03-11 2017-04-01 2017-03-08 2017-05-06 2017-03-16 2017-11-02 2018-03-15 ant Selection O SEDANO - Por continuidad nd Social Management de Servicios PTSP-BIRF8649-031 / Lider d Component 4. Project Manag e Planeación y Seguimiento - Individual Consult IBRD / 86490 ement and Environmental a Post Direct 99,507.79 61,063.18 Signed 2017-03-01 2017-03-08 2017-03-11 2017-03-10 2017-04-01 2017-03-13 2017-05-06 2017-03-16 2017-11-02 JUAN DE DIOS CISNEROS - - P ant Selection nd Social Management or continuidad de Servicios PTSP-BIRF8649-032 / Especi Component 4. Project Manag alista Planeación y Seguimie Individual Consult IBRD / 86490 ement and Environmental a Post Direct 67,749.98 41,574.93 Signed 2017-03-01 2017-03-08 2017-03-11 2017-03-16 2017-04-01 2017-03-22 2017-05-06 2017-03-31 2017-11-02 nto - JULIAN ANDRES VALBUE ant Selection nd Social Management NA - Por continuidad de Servi cios PTSP-BIRF8649-025 / Asisten Component 4. Project Manag te Financiero y Administrativ Individual Consult IBRD / 86490 ement and Environmental a Post Direct 37,173.93 0.00 Canceled 2017-07-03 2017-07-13 2017-08-03 2017-09-07 2018-09-02 o - BEATRIZ PARRA - Continui ant Selection nd Social Management dad de Servicios PTSP-BIRF8649-048 / Tulio f Component 4. Project Manag Individual Consult uentes Especialista en Adqui IBRD / 86490 ement and Environmental a Post Direct 49,242.00 46,194.37 Signed 2017-11-02 2017-10-23 2017-11-07 2017-10-12 2017-11-08 2017-10-20 2017-11-10 2017-11-10 2018-11-09 ant Selection siciones 2 nd Social Management Component 4. Project Manag PTSP-BIRF8649-046 / Especi Individual Consult IBRD / 86490 ement and Environmental a Post Open 49,242.00 0.00 Canceled 2017-10-31 2017-11-06 2017-11-09 2017-11-13 2018-11-13 alista Adquisiciones 2 ant Selection nd Social Management Component 3. Capacity Buil PTSP-BIRF8649-044 / Especi ding and Institutional Streng Individual Consult alista Fortalecimiento Instituc IBRD / 86490 Post Open 49,242.00 47,560.97 Signed 2017-08-18 2017-10-12 2017-09-01 2017-11-10 2017-09-03 2017-12-20 2017-09-17 2017-12-28 2018-09-12 thening of Service Providers ant Selection ional in the Municipalities of Guap i and Tum aco PTSP-BIRF8649-51 / IEH GRU CON-Realizar los estudios y d iseños de los proyectos priori Component 2. Water Supply zados para la optimización y and Basic Sanitation Improv ampliación del sistema de ac IBRD / 86490 Post Direct Selection Direct 792,345.00 708,875.23 Signed 2017-12-18 2018-02-20 2017-12-31 2018-02-21 2018-01-15 2018-02-23 2019-01-10 ements in the Municipality o ueducto del municipio de Tu f Tumaco maco, departamento de Nari ño, en el marco del Fondo pa ra el Desarrollo del Plan Todo s Somos PAZcífico Component 4. Project Manag PTSP-BIRF8649-054 / KPMG- IBRD / 86490 ement and Environmental a Post Direct Selection Direct 35,000.00 69,291.56 Signed 2017-12-29 2018-04-04 2018-01-08 2018-04-05 2018-03-14 2018-04-13 2018-09-10 AUDITORIA EXTERNA nd Social Management PTSP-BIRF8649-057 / Antoni Component 1. Water Supply Individual Consult o Nieto - Director de Interven IBRD / 86490 and Basic Sanitation Improv Post Direct 26,897.00 25,232.22 Signed 2018-04-26 2018-04-23 2018-04-27 2018-04-24 2018-05-02 2018-05-08 2018-05-07 2018-05-19 2018-11-03 ant Selection torìa ements in the Municipality o f Guapi PTSP-BIRF8649-058 / Ramiro Component 1. Water Supply Individual Consult Gutierrez. Especialista Electr IBRD / 86490 and Basic Sanitation Improv Post Direct 6,771.00 6,351.73 Signed 2018-04-26 2018-04-23 2018-04-27 2018-04-24 2018-05-02 2018-05-08 2018-05-07 2018-05-17 2018-11-03 ant Selection o-mecànico de Interventorìa ements in the Municipality o f Guapi PTSP-BIRF8649-060 / Alvaro Component 1. Water Supply Individual Consult Bravo - Especialista Geotecni IBRD / 86490 and Basic Sanitation Improv Post Direct 9,233.00 8,661.44 Signed 2018-04-26 2018-04-23 2018-04-27 2018-04-24 2018-05-02 2018-05-08 2018-05-07 2018-05-17 2018-11-03 ant Selection sta de Interventorìa ements in the Municipality o f Guapi PTSP-BIRF8649-059 / Eduard Component 1. Water Supply Individual Consult o Gòmez - Especialista Estruc IBRD / 86490 and Basic Sanitation Improv Post Direct 9,233.00 0.00 Canceled 2018-04-26 2018-04-27 2018-05-02 2018-05-07 2018-11-03 ant Selection tural de Interventorìa ements in the Municipality o f Guapi PTSP-BIRF8649-061 / FERNA Component 1. Water Supply Individual Consult NDO VARGAS RODRÍGUEZ. E IBRD / 86490 and Basic Sanitation Improv Post Direct 9,233.00 8,661.44 Signed 2018-05-07 2018-05-04 2018-05-08 2018-05-11 2018-05-13 2018-06-08 2018-06-12 2018-06-08 2018-12-09 ant Selection specialista Estructural de Int ements in the Municipality o erventoria. f Guapi PTSP-BIRF8649-011 / Apoyar el componente social, en el D epartamento del Chocò, en la Component 4. Project Manag Individual Consult implementaciòn y ejecuciòn IBRD / 86490 ement and Environmental a Post Open 27,082.76 0.00 Canceled 2017-04-07 2017-08-22 2017-05-02 2017-05-12 2017-06-01 2018-06-01 ant Selection del FDPTSP que adelanta co nd Social Management mo entidad ejecutora la Unid ad Nacional para la Gestiòn d el Riesgo de Desastres. PTSP-BIRF8649-012 / Apoyar el componente social, en el D epartamento del Valle en la i Component 4. Project Manag Individual Consult mplementaciòn y ejecuciòn d IBRD / 86490 ement and Environmental a Post Open 27,082.76 0.00 Canceled 2017-04-07 2017-05-02 2017-05-12 2017-06-01 2018-06-01 ant Selection el FDPTSP que adelanta com nd Social Management o entidad ejecutora la Unidad Nacional para la Gestiòn del Riesgo de Desastres. Component 4. Project Manag PTSP-BIRF8649-030 / Apoyo Individual Consult IBRD / 86490 ement and Environmental a Post Open 26,159.48 0.00 Canceled 2017-06-30 2017-07-21 2017-07-23 2017-07-27 2018-07-22 en adquisiciones ant Selection nd Social Management PTSP-BIRF8649-042 / Asisten Component 4. Project Manag Individual Consult te Financiero y Administrativ IBRD / 86490 ement and Environmental a Post Open 37,173.93 0.00 Canceled 2017-08-25 2017-10-13 2017-11-03 2017-12-08 2018-06-06 ant Selection o nd Social Management Page 6 CO-UNGRD-87418-CS-INDV / Brindar apoyo jurídico en la g estión predial y catastral de l Component 1. Water Supply os bienes inmuebles que sea and Basic Sanitation Improv Individual Consult n necesarios para la viabiliza IBRD / 86490 Post Open 7,763.00 7,763.00 Signed 2018-11-30 2018-11-28 2019-01-18 2019-02-08 2019-02-05 2019-03-15 2019-02-05 2019-09-11 ements in the Municipality o ant Selection ción de los proyectos que se f Guapi ejecutan en el marco del Fon do para el Desarrollo del Plan Todos Somos Pazcífico, que a delanta como entidad PTSP-BIRF8649-063 / Liderar el componente de Agua y Sa neamiento Básico, en la impl Component 4. Project Manag ementación y ejecución del F Individual Consult IBRD / 86490 ement and Environmental a Post Open 34,200.00 34,200.00 Signed 2018-12-26 2019-02-18 2019-02-13 2019-03-06 2019-04-04 2019-04-10 2019-04-08 2019-10-07 ondo para el Desarrollo del Pl ant Selection nd Social Management an Todos Somos Pazcífico qu e adelanta como entidad eje cutora la Unidad Nacional pa ra la Gestión del Riesgo de D esastres. PTSP-BIRF8649-072 / Especi Component 4. Project Manag Individual Consult alista de Adquisiciones - Rec IBRD / 86490 ement and Environmental a Post Direct 53,560.00 26,780.00 Signed 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-15 2019-03-18 2019-03-18 2020-03-12 ant Selection ontratación Pilar Valero nd Social Management PTSP-BIRF8649-073 / Especi Component 4. Project Manag Individual Consult alista de Adquisiciones - Rec IBRD / 86490 ement and Environmental a Post Direct 53,560.00 53,560.00 Signed 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-13 2019-03-15 2019-03-15 2020-03-09 ant Selection ontratación Tulio Fuentes nd Social Management PTSP-BIRF8649-075 / Especi Component 4. Project Manag Individual Consult alista Financiera - Recontrata IBRD / 86490 ement and Environmental a Post Direct 53,560.00 26,780.00 Signed 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-15 2019-03-18 2019-03-18 2020-03-12 ant Selection ción Sandra Lorena Peña nd Social Management PTSP-BIRF8649-069 / Líder d Component 4. Project Manag Individual Consult e Adquisiciones - Recontrata IBRD / 86490 ement and Environmental a Post Direct 70,800.00 35,400.00 Signed 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-13 2019-03-18 2019-03-18 2020-03-12 ant Selection ción Elkin Adolfo Pinilla Cañó nd Social Management n PTSP-BIRF8649-065 / Directo Component 4. Project Manag ra Ejecutiva / Coordinadora d Individual Consult IBRD / 86490 ement and Environmental a Post Direct 83,000.00 41,500.00 Signed 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-14 2019-03-18 2019-03-18 2020-03-12 el Proyecto FTSP - Recontrata ant Selection nd Social Management ción Luz Amanda Pulido PTSP-BIRF8649-067 / Líder A Component 4. Project Manag Individual Consult mbiental - Recontratación Al IBRD / 86490 ement and Environmental a Post Direct 70,800.00 35,400.00 Signed 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-14 2019-03-18 2019-03-18 2020-03-12 ant Selection ejandra Catacoli nd Social Management PTSP-BIRF8649-068 / Líder Fi Component 4. Project Manag Individual Consult nanciera - Recontratación Cla IBRD / 86490 ement and Environmental a Post Direct 70,800.00 35,400.00 Signed 2019-03-04 2019-02-25 2019-03-11 2019-03-11 2019-03-14 2019-03-18 2019-03-18 2020-03-12 ant Selection udia Agudelo nd Social Management PTSP-BIRF8649-066 / Líder d Component 4. Project Manag Individual Consult e Planeación y Seguimiento - IBRD / 86490 ement and Environmental a Post Direct 70,800.00 35,400.00 Signed 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-13 2019-03-18 2019-03-15 2020-03-12 ant Selection Luis Ignacio Alfonso nd Social Management PTSP-BIRF8649-070 / Líder S Component 4. Project Manag Individual Consult ocial - Recontratación Kelly R IBRD / 86490 ement and Environmental a Post Direct 23,600.00 11,800.00 Signed 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-13 2019-03-18 2019-03-18 2019-07-17 ant Selection uiz nd Social Management PTSP-BIRF8649-080 / Especi Component 4. Project Manag alista Social para la Evaluaci Individual Consult IBRD / 86490 ement and Environmental a Post Open 13,140.00 0.00 Canceled 2019-04-12 2019-07-16 2019-04-29 2019-05-10 2019-05-20 2019-07-30 ón Social de los municipios d ant Selection nd Social Management e Tumaco (Nariño) y Guapi ( Cauca) PTSP-BIRF8649-084 / Electro Mecanico - Realizar apoyo a l a Interventoría Integral de lo Component 1. Water Supply s contratos de Estudios y Dis and Basic Sanitation Improv Individual Consult IBRD / 86490 Post Open 16,000.00 9,050.40 Signed 2019-07-10 2019-06-21 2019-08-28 2019-09-27 2019-09-18 2019-09-25 2019-10-23 2019-10-01 2020-04-20 eños como interventor en los ements in the Municipality o ant Selection aspectos eléctricos y mecáni f Guapi cos de los proyectos de prein versión priorizados en el com ponente de Agua y Saneamie nto Básico. PTSP-BIRF8649-081 / Direcci ón de Interventoría Integral d Component 1. Water Supply e Estudios y Diseños de los p and Basic Sanitation Improv Individual Consult IBRD / 86490 Post Open 27,000.00 12,926.59 Signed 2019-06-25 2019-07-26 2019-08-13 2019-09-10 2019-09-03 2019-10-01 2019-10-08 2019-10-12 2020-04-05 royectos de preinversión prio ements in the Municipality o ant Selection rizados en el componente de f Guapi Agua y Saneamiento Básico en el marco del préstamo BIR F. Component 4. Project Manag PTSP-BIRF8649-085 / Líder d Individual Consult IBRD / 86490 ement and Environmental a Post Open 20,000.00 25,517.85 Signed 2019-06-21 2019-07-29 2019-08-09 2019-09-24 2019-08-30 2019-09-02 2019-10-04 2019-09-07 2020-04-01 e Seguridad FTSP ant Selection nd Social Management PTSP-BIRF8649-086 / Líder S Component 4. Project Manag Individual Consult ocial - Recontratación Kelly R IBRD / 86490 ement and Environmental a Post Direct 47,200.00 39,330.50 Signed 2019-07-11 2019-07-15 2019-07-12 2019-07-23 2019-07-12 2019-08-22 2019-07-18 2019-08-23 2020-03-17 ant Selection uiz nd Social Management PTSP-BIRF8649-089 / Topogr afo - Prestación de servicios profesionales para la realizac Component 1. Water Supply ión de levantamientos topogr and Basic Sanitation Improv Individual Consult áficos requeridos para el san IBRD / 86490 Post Open 13,800.00 9,943.53 Signed 2019-08-26 2019-08-22 2019-10-14 2019-09-19 2019-11-04 2019-10-18 2019-12-09 2019-10-24 2020-03-08 ements in the Municipality o ant Selection eamiento de los predios requ f Guapi eridos para la ejecución de lo s proyectos del Fondo para el Desarrollo del Plan Todos So mos PAZcífico. PTSP-BIRF8649-090 / Catastr al - Brindar apoyo técnico cat astral y de avalúos en la gest Component 1. Water Supply ión predial de los bienes inm and Basic Sanitation Improv Individual Consult IBRD / 86490 Post Open 27,600.00 8,438.74 Signed 2019-08-26 2019-08-30 2019-10-14 2019-10-01 2019-11-04 2019-10-25 2019-12-09 2019-11-06 2020-06-08 uebles que sean necesarios p ements in the Municipality o ant Selection ara la viabilización de los pro f Guapi yectos que se ejecutan en el marco del Fondo para el Des arrollo del Plan Todos Somos PAZcífico. PTSP-BIRF8649-091 / Apoyo jurídico en las gestiones juríd Component 1. Water Supply icas y administrativas que se and Basic Sanitation Improv Individual Consult requiera adelantar dentro del IBRD / 86490 Post Open 16,000.00 12,098.26 Signed 2019-08-26 2020-04-08 2019-10-14 2020-04-10 2019-11-04 2020-04-16 2019-12-09 2020-04-24 2020-06-08 ements in the Municipality o ant Selection proceso de saneamiento, adq f Guapi uisición predial y reasentami ento de población, a través d e las modalidades de enajen ación PTSP-BIRF8649-088 / Gestor Component 1. Water Supply Individual Consult a Predial - Recontratación NI IBRD / 86490 and Basic Sanitation Improv Post Direct 27,600.00 10,207.20 Signed 2019-08-30 2019-09-02 2019-09-06 2019-12-09 2019-09-06 2020-01-31 2019-09-13 2020-02-01 2020-03-12 ant Selection NFA LUCIA SANTANA ESCOBA ements in the Municipality o R. f Guapi Page 7 Component 4. Project Manag PTSP-BIRF8649-027 / Especi Individual Consult IBRD / 86490 ement and Environmental a Post Open 63,844.53 0.00 Canceled 2017-04-01 2017-04-11 2017-05-20 2017-06-10 2017-07-15 2018-01-11 alista Financiero ant Selection nd Social Management PTSP-BIRF8649-093 / JOHN O Component 4. Project Manag Individual Consult TALVARO CORTES - Especiali IBRD / 86490 ement and Environmental a Post Direct 18,000.00 11,102.00 Signed 2019-11-15 2019-11-25 2019-11-22 2020-01-02 2019-11-22 2020-01-02 2019-11-26 2020-01-03 2020-05-24 ant Selection sta de Adquisiciones nd Social Management PTSP-BIRF8649-099 / Líder d Component 4. Project Manag Individual Consult e Planeación - JOAN NATALIE IBRD / 86490 ement and Environmental a Post Direct 17,700.00 25,806.54 Signed 2019-11-15 2019-11-25 2019-11-22 2019-12-05 2019-11-22 2019-12-19 2019-11-26 2019-12-28 2020-05-24 ant Selection GARZON nd Social Management PTSP-BIRF8649-101 / Directo Component 4. Project Manag ra Ejecutiva / Coordinadora d Individual Consult IBRD / 86490 ement and Environmental a Post Direct 26,400.00 64,142.90 Signed 2020-02-24 2020-03-03 2020-03-02 2020-03-09 2020-03-02 2020-03-12 2020-03-18 2020-03-19 2021-03-17 el Proyecto FTSP - Recontrata ant Selection nd Social Management ción Luz Amanda Pulido PTSP-BIRF8649-102 / Líder A Component 4. Project Manag Individual Consult mbiental - Recontratación Al IBRD / 86490 ement and Environmental a Post Direct 22,520.00 54,713.29 Signed 2020-02-24 2020-03-03 2020-03-02 2020-03-10 2020-03-02 2020-03-16 2020-03-18 2020-03-19 2021-03-17 ant Selection ejandra Catacoli nd Social Management PTSP-BIRF8649-103 / Líder Fi Component 4. Project Manag Individual Consult nanciera - Recontratación Cla IBRD / 86490 ement and Environmental a Post Direct 22,520.00 54,127.85 Signed 2020-02-24 2020-03-03 2020-03-02 2020-03-10 2020-03-02 2020-03-12 2020-03-18 2020-03-19 2021-03-17 ant Selection udia Agudelo nd Social Management PTSP-BIRF8649-104 / Líder d Component 4. Project Manag Individual Consult e Adquisiciones - Recontrata IBRD / 86490 ement and Environmental a Post Direct 22,520.00 54,713.29 Signed 2020-02-24 2020-03-03 2020-03-02 2020-03-09 2020-03-02 2020-03-16 2020-03-18 2020-03-19 2021-03-17 ant Selection ción Elkin Adolfo Pinilla Cañó nd Social Management n PTSP-BIRF8649-105 / Líder d Component 4. Project Manag Individual Consult e Seguridad FTSP - WILSON L IBRD / 86490 ement and Environmental a Post Direct 22,520.00 16,685.59 Signed 2020-02-24 2020-03-02 2020-03-02 2020-03-04 2020-03-02 2020-03-11 2020-03-06 2020-03-24 2021-03-05 ant Selection AVERDE FLÓREZ nd Social Management PTSP-BIRF8649-106 / Especi Component 4. Project Manag Individual Consult alista Financiera - Recontrata IBRD / 86490 ement and Environmental a Post Direct 17,050.00 41,402.62 Signed 2020-02-25 2020-03-03 2020-03-03 2020-03-09 2020-03-03 2020-03-16 2020-03-18 2020-03-19 2021-03-17 ant Selection ción Sandra Lorena Peña nd Social Management PTSP-BIRF8649-107 / Especi Component 4. Project Manag Individual Consult alista de Adquisiciones - Rec IBRD / 86490 ement and Environmental a Post Direct 56,800.00 41,391.10 Signed 2020-02-25 2020-03-03 2020-03-03 2020-03-09 2020-03-03 2020-03-12 2020-03-16 2020-03-17 2021-03-15 ant Selection ontratación Tulio Jose Fuente nd Social Management s PTSP-BIRF8649-108 / Líder C Component 4. Project Manag omponente Agua y Saneamie Individual Consult IBRD / 86490 ement and Environmental a Post Direct 37,523.00 53,829.69 Signed 2020-03-24 2020-03-24 2020-03-28 2020-03-30 2020-04-01 2020-03-31 2020-04-07 2020-04-09 2021-04-07 nto Básico - Recontratación F ant Selection nd Social Management ABIOLA IGUARAN ARAUJO PTSP-BIRF8649-110 / Liderar el componente social, en la i mplementación y ejecución d e los proyectos de agua, san Component 4. Project Manag Individual Consult eamiento y energía del Fond IBRD / 86490 ement and Environmental a Post Direct 22,520.00 16,685.59 Signed 2020-04-14 2020-04-15 2020-04-15 2020-04-03 2020-04-15 2020-04-20 2020-04-23 2020-04-24 2021-04-22 ant Selection o para el Desarrollo del Plan nd Social Management Todos Somos PAZcífico finan ciados por la Banca Multilate ral que adelanta como entida d ejecutora la Unidad PTSP-BIRF8649-087 / Especi Component 4. Project Manag alista Social para la Evaluaci Individual Consult IBRD / 86490 ement and Environmental a Post Open 13,140.00 0.00 Canceled 2019-08-23 2019-08-30 2019-09-09 2019-09-27 2019-09-20 2019-09-30 2019-12-29 ón Social de los municipios d ant Selection nd Social Management e Tumaco (Nariño) y Guapi ( Cauca) Component 4. Project Manag PTSP-BIRF8649-098 / KPMG- IBRD / 86490 ement and Environmental a Post Direct Selection Direct 34,500.00 0.00 Canceled 2019-11-25 2019-12-02 2019-11-30 2020-02-03 2020-08-01 AUDITORIA EXTERNA nd Social Management PTSP-BIRF8649-111 / “Realiz ar Los Estudios Y Diseños Par Component 1. Water Supply a La Construcción, Operación and Basic Sanitation Improv , Clausura Y Post Clausura De IBRD / 86490 Post Direct Selection Direct 7,350.00 89,848.30 Signed 2020-05-15 2020-05-14 2020-05-20 2020-06-12 2020-08-02 2020-12-17 2021-01-02 ements in the Municipality o l Centro De Restauración Am f Guapi biental Urbano – CRAU Del M unicipio De Guapi, Departam ento Del Cauca” PTSP-BIRF8649-113 / Especi alista de Planeación y Segui miento. - Brindar apoyo profe Component 4. Project Manag Individual Consult sional en la gestión de planifi IBRD / 86490 ement and Environmental a Post Open 17,050.00 42,576.52 Signed 2020-05-14 2020-05-22 2020-06-03 2020-05-25 2020-06-18 2021-05-27 2020-08-01 2021-05-28 2021-08-01 ant Selection cación, monitoreo y seguimie nd Social Management nto a las actividades del Fon do para el Desarrollo del Plan Todos Somos Pazcífico. PTSP-BIRF8649-114 / Realiza r la evaluación de medio tér mino del PROYECTO DE INFR AESTRUCTURA PARA EL SUMI Component 4. Project Manag Individual Consult NISTRO DE AGUA Y SANEAMI IBRD / 86490 ement and Environmental a Post Open 15,870.00 11,192.26 Signed 2020-05-20 2020-05-20 2020-06-14 2020-06-30 2020-06-29 2020-07-15 2020-07-10 2020-08-16 2020-11-07 ant Selection ENTO BÁSICO & PROVISIÓN nd Social Management DE SERVICIOS, en cumplimie nto de las condiciones establ ecidas en el Contrato de Prés tamo N° 8649-CO. PTSP-BIRF8649-115 / Liderar la planificación, gestión, mon itoreo y seguimiento de las di ferentes herramientas de ges Component 4. Project Manag Individual Consult tión IBRD / 86490 ement and Environmental a Post Open 22,520.00 0.00 Canceled 2020-06-24 2020-06-22 2020-07-05 2020-07-25 2020-08-10 2021-08-10 ant Selection establecidas para el cumplim nd Social Management iento de las metas y objetivo s del Fondo para el Desarroll o del Plan Todos Somos PAZcífico que a delanta como entidad ejecut PTSP-BIRF8649-116 / Auditor ora ía a los Estados Financieros d Component 4. Project Manag e Propósito Especial de Proye IBRD / 86490 ement and Environmental a Post Direct Selection Direct 31,050.00 23,247.90 Signed 2020-06-26 2020-06-22 2020-07-06 2020-07-01 2020-08-20 2020-09-26 2020-11-18 ctos Financiados por el Banc nd Social Management o Mundial a través de présta mos. PTSP-BIRF8649-117 / Liderar la planificación, gestión, mon itoreo y seguimiento de las di ferentes herramientas de ges Component 4. Project Manag Individual Consult tión establecidas para el cum IBRD / 86490 ement and Environmental a Post Limited 22,520.00 56,302.02 Signed 2020-06-23 2020-06-22 2020-06-28 2020-06-19 2020-07-08 2020-06-23 2020-07-28 2020-07-01 2021-07-28 ant Selection plimiento de las metas y obje nd Social Management tivos del Fondo para el Desar rollo del Plan Todos Somos P AZcífico que adelanta como entidad ejecutora Page 8 PTSP-BIRF8649-123 / AUDIT ORÍA DE LOS ESTADOS FINA NCIEROS DE PROPÓSITO ESP ECIAL Y ASEGURAMIENTO Component 4. Project Manag RAZONABLE SOBRE LOS PRO IBRD / 86490 ement and Environmental a Post Direct Selection Direct 26,600.00 23,668.95 Signed 2020-10-19 2020-11-05 2020-11-08 2020-11-19 2021-01-07 2021-02-20 2021-07-06 CESOS DE ADQUISICIONES D nd Social Management EL PROYECTO/PROGRAMA FI NANCIADO POR EL BID Y EL B ANCO MUNDIAL A TRAVÉS DE PRÉSTAMOS PTSP-BIRF8649-124 / Líder C Component 4. Project Manag omponente Agua y Saneamie Individual Consult IBRD / 86490 ement and Environmental a Post Direct 27,500.00 56,506.60 Signed 2021-02-23 2021-02-25 2021-02-27 2021-04-07 2021-03-03 2021-04-07 2021-04-08 2021-04-09 2022-04-08 nto Básico - Recontratación F ant Selection nd Social Management ABIOLA IGUARAN ARAUJO PTSP-BIRF8649-125 / Directo Component 4. Project Manag ra Ejecutiva / Coordinadora d Individual Consult IBRD / 86490 ement and Environmental a Post Direct 19,330.00 66,005.44 Signed 2021-02-24 2021-02-25 2021-03-03 2021-03-17 2021-03-03 2021-03-16 2021-03-18 2021-03-19 2022-03-18 el Proyecto FTSP - Recontrata ant Selection nd Social Management ción Luz Amanda Pulido PTSP-BIRF8649-126 / Líder d Component 4. Project Manag Individual Consult e Adquisiciones - Recontrata IBRD / 86490 ement and Environmental a Post Direct 16,500.00 56,090.91 Signed 2021-02-24 2021-02-25 2021-03-03 2021-03-17 2021-03-03 2021-02-17 2021-03-18 2021-03-20 2022-03-17 ant Selection ción Elkin Adolfo Pinilla Cañó nd Social Management n PTSP-BIRF8649-127 / Líder Fi Component 4. Project Manag Individual Consult nanciera - Recontratación Cla IBRD / 86490 ement and Environmental a Post Direct 16,500.00 56,280.26 Signed 2021-02-24 2021-02-25 2021-03-03 2021-03-16 2021-03-03 2021-03-12 2021-03-18 2021-03-19 2022-03-17 ant Selection udia Agudelo nd Social Management PTSP-BIRF8649-128 / Líder S Component 4. Project Manag Individual Consult ocial - Recontratación Kelly R IBRD / 86490 ement and Environmental a Post Direct 16,500.00 56,643.71 Signed 2021-02-24 2021-02-25 2021-02-25 2021-04-22 2021-02-25 2021-04-22 2021-04-23 2021-04-24 2022-04-22 ant Selection uiz nd Social Management PTSP-BIRF8649-129 / Líder d Component 4. Project Manag Individual Consult e Seguridad FTSP -Recontrat IBRD / 86490 ement and Environmental a Post Direct 16,500.00 56,090.91 Signed 2021-02-24 2021-02-25 2021-03-03 2021-03-22 2021-03-03 2021-02-22 2021-03-22 2021-03-24 2022-03-21 ant Selection ación WILSON LAVERDE FLÓ nd Social Management REZ PTSP-BIRF8649-130 / Especi Component 4. Project Manag Individual Consult alista Financiera - Recontrata IBRD / 86490 ement and Environmental a Post Direct 12,473.00 42,851.48 Signed 2021-03-03 2021-03-15 2021-03-10 2021-03-17 2021-03-10 2021-03-17 2021-03-18 2021-03-19 2022-03-17 ant Selection ción Sandra Lorena Peña nd Social Management PTSP-BIRF8649-132 / Especi Component 4. Project Manag Individual Consult alista de Adquisiciones - Rec IBRD / 86490 ement and Environmental a Post Direct 20,788.00 42,433.29 Signed 2021-03-03 2021-03-15 2021-03-10 2021-03-12 2021-03-10 2021-03-15 2021-03-15 2021-03-19 2022-03-14 ant Selection ontratación Tulio Jose Fuente nd Social Management s PTSP-BIRF8649-131 / Contra tación Líder Ambiental para l a ejecución y cumplimiento d Component 4. Project Manag e los Marcos de Gestión Ambi IBRD / 86490 ement and Environmental a Post Direct Selection Direct 8,244.00 28,045.46 Signed 2021-03-03 2021-03-05 2021-03-11 2021-03-05 2021-03-18 2021-03-17 2021-09-17 ental adoptados para la ejec nd Social Management ución del Fondo para el desar rollo del Plan Todos Somos P AZcífico - Fernando Rey PTSP-BIRF8649-133 / Especi alista de Planeación y Segui miento. - Brindar apoyo profe Component 4. Project Manag Individual Consult sional en la gestión de planifi IBRD / 86490 ement and Environmental a Post Open 10,394.00 17,829.14 Signed 2021-03-11 2021-03-15 2021-03-16 2021-03-24 2021-03-17 2021-03-24 2021-03-25 2021-03-27 2022-09-24 ant Selection cación, monitoreo y seguimie nd Social Management nto a las actividades del Fon do para el Desarrollo del Plan Todos Somos Pazcífico. PTSP-BIRF8649-134 / Contra tación Líder Fortalecimiento I nstitucional para Liderar la i Component 4. Project Manag mplementación y ejecución d IBRD / 86490 ement and Environmental a Post Direct Selection Direct 8,244.00 0.00 Canceled 2021-04-14 2021-04-24 2021-05-17 2021-11-16 e los componentes de Capaci nd Social Management dad y Fortalecimiento Institu cional de Agua y Saneamient o Básico - Jorge Silva PTSP-BIRF8649-135 / Contra tación Líder Fortalecimiento I nstitucional para Liderar la i Component 4. Project Manag mplementación y ejecución d Individual Consult IBRD / 86490 ement and Environmental a Post Direct 8,244.00 28,321.85 Signed 2021-04-15 2021-04-19 2021-04-23 2021-04-14 2021-04-26 2021-05-07 2021-05-17 2021-05-12 2021-11-16 e los componentes de Capaci ant Selection nd Social Management dad y Fortalecimiento Institu cional de Agua y Saneamient o Básico para el desarrollo de l Plan Todos Somos PAZcífico - Jorge Silva. PTSP-BIRF8649-136 / Especi Component 4. Project Manag alista de Adquisiciones - Rec Individual Consult IBRD / 86490 ement and Environmental a Post Direct 12,473.00 42,851.48 Signed 2021-04-22 2021-04-22 2021-04-26 2021-05-26 2021-04-26 2021-05-04 2021-05-04 2021-05-07 2022-05-03 ontratación JOHN MAURICIO ant Selection nd Social Management OTÁLVARO CORTÉS PTSP-BIRF8649-138 / Líder d Component 4. Project Manag Individual Consult e Planeación - JOAN NATALIE IBRD / 86490 ement and Environmental a Post Direct 16,490.00 56,643.71 Signed 2021-06-04 2021-06-11 2021-06-11 2021-06-22 2021-06-11 2021-06-23 2021-06-30 2021-07-01 2022-06-29 ant Selection GARZON nd Social Management PTSP-BIRF8649-139 / AUDIT ORÍA DE LOS ESTADOS FINA NCIEROS DE PROPÓSITO ESP ECIAL Y ASEGURAMIENTO Component 4. Project Manag RAZONABLE SOBRE LOS PRO IBRD / 86490 ement and Environmental a Post Direct Selection Direct 26,238.00 21,580.38 Signed 2021-09-06 2021-09-15 2021-09-26 2021-10-04 2021-12-22 2022-02-03 2022-07-29 CESOS DE ADQUISICIONES D nd Social Management EL PROYECTO/PROGRAMA FI NANCIADO POR EL BID Y EL B ANCO MUNDIAL A TRAVÉS DE PRÉSTAMOS PTSP-BIRF8649-140 / Líder A Component 4. Project Manag Individual Consult mbiental FTSP - Recontrataci IBRD / 86490 ement and Environmental a Post Direct 8,902.00 27,880.05 Signed 2021-09-09 2021-09-09 2021-09-09 2021-09-10 2021-09-20 2021-09-20 2021-09-23 2021-09-24 2022-03-22 ant Selection ón Fernando Rey nd Social Management PTSP-BIRF8649-141 / Especi Component 4. Project Manag alista de Planeación y Segui Individual Consult IBRD / 86490 ement and Environmental a Post Direct 22,425.00 41,939.36 Signed 2021-09-09 2021-09-09 2021-09-17 2021-09-16 2021-09-17 2021-09-20 2021-09-27 2021-09-29 2022-09-26 miento FTSP - Recontratación ant Selection nd Social Management Natalia García Medina PTSP-BIRF8649-144 / Líder d Component 3. Capacity Buil e Fortalecimiento Institucion ding and Institutional Streng Individual Consult IBRD / 86490 Post Direct 17,805.00 55,760.11 Signed 2021-10-19 2021-10-19 2021-10-19 2021-10-19 2021-10-26 2021-10-26 2021-11-11 2021-11-12 2022-11-10 al - Recontratación Jorge Silv thening of Service Providers ant Selection a in the Municipalities of Guap i and Tum aco Component 4. Project Manag PTSP-BIRF8649-145 / Líder S Individual Consult IBRD / 86490 ement and Environmental a Post Open 14,837.00 24,051.50 Signed 2021-10-27 2021-10-27 2021-11-30 2022-03-16 2021-12-03 2022-03-17 2021-12-20 2022-04-10 2022-06-19 ocial FTSP ant Selection nd Social Management Page 9 PTSP-BIRF8649-171 / Líder d Component 1. Water Supply Individual Consult e Agua BM - Recontratación F IBRD / 86490 and Basic Sanitation Improv Post Direct 31,342.00 57,727.68 Signed 2022-03-04 2022-03-04 2022-03-04 2022-03-04 2022-03-24 2022-03-09 2022-04-08 2022-04-11 2023-04-07 ant Selection abiola del Rosario Iguarán ements in the Municipality o f Guapi PTSP-BIRF8649-176 / Recont Component 4. Project Manag Individual Consult ratación Especialista de Adqu IBRD / 86490 ement and Environmental a Post Direct 23,711.00 43,671.56 Signed 2022-03-04 2022-03-04 2022-03-09 2022-03-04 2022-03-09 2022-03-04 2022-03-16 2022-03-19 2023-03-15 ant Selection isiciones - Tulio José Fuentes nd Social Management PTSP-BIRF8649-172 / Recont Component 4. Project Manag Individual Consult ratación Directora Ejecutiva- IBRD / 86490 ement and Environmental a Post Direct 22,046.00 62,078.79 Signed 2022-03-04 2022-03-04 2022-03-11 2022-03-11 2022-03-11 2022-03-11 2022-03-18 2022-03-19 2023-03-17 ant Selection Coordinadora General - Luz A nd Social Management manada Pulido PTSP-BIRF8649-173 / Recont Component 4. Project Manag Individual Consult ratación Líder de Adquisicion IBRD / 86490 ement and Environmental a Post Direct 18,805.00 52,952.63 Signed 2022-03-04 2022-03-04 2022-03-11 2022-03-11 2022-03-11 2022-03-11 2022-03-18 2022-03-21 2023-03-17 ant Selection es - Élkin Pinilla nd Social Management PTSP-BIRF8649-174 / Recont Component 4. Project Manag Individual Consult ratación Líder Financiera - Cl IBRD / 86490 ement and Environmental a Post Direct 18,805.00 53,292.14 Signed 2022-03-04 2022-03-04 2022-03-11 2022-03-04 2022-03-11 2022-04-11 2022-03-18 2022-03-19 2023-03-17 ant Selection audia Agudelo nd Social Management PTSP-BIRF8649-175 / Recont Component 4. Project Manag Individual Consult ratación Líder Ambiental - Fe IBRD / 86490 ement and Environmental a Post Direct 9,403.00 26,646.07 Signed 2022-03-04 2022-03-04 2022-03-04 2022-03-04 2022-03-15 2022-03-15 2022-03-23 2022-03-24 2022-09-22 ant Selection rnando Rey nd Social Management PTSP-BIRF8649-177 / Recont Component 4. Project Manag Individual Consult ratación Especialista Financie IBRD / 86490 ement and Environmental a Post Direct 14,226.00 40,315.98 Signed 2022-03-04 2022-03-04 2022-03-11 2022-03-04 2022-03-11 2022-03-11 2022-03-18 2022-03-19 2023-03-17 ant Selection ra - Lorena Peña nd Social Management PTSP-BIRF8649-178 / Recont Component 4. Project Manag Individual Consult Under Implement ratación Líder de Seguridad - IBRD / 86490 ement and Environmental a Post Direct 8,910.00 0.00 2022-04-26 2022-05-05 2022-05-02 2022-04-26 2022-05-02 2022-05-05 2022-11-04 ant Selection ation Wilson Laverde nd Social Management PTSP-BIRF8649-180 / Liderar los procesos de adquisicione s que adelanta la Unidad Nac ional para la Gestión del Ries Component 4. Project Manag Individual Consult go de Desastres como entida IBRD / 86490 ement and Environmental a Post Limited 17,900.00 0.00 Canceled 2022-05-23 2022-05-27 2022-05-28 2022-06-15 2022-06-02 2022-06-17 2023-06-16 ant Selection d ejecutora del Fondo para el nd Social Management Desarrollo del Plan Todos So mos PAZcífico, según las Polí ticas, normas y regulaciones del BID y Banco M. PTSP-BIRF8649-181 / Liderar la planificación, monitoreo, s eguimiento y gestión de los p réstamos del BID y el Banco Component 4. Project Manag Individual Consult Pending Impleme Mundial, ejecutados por la U IBRD / 86490 ement and Environmental a Post Direct 17,805.00 0.00 2022-06-16 2022-06-17 2022-06-24 2022-06-29 2023-06-29 ant Selection ntation nidad Nacional para la Gestió nd Social Management n del Riesgo de Desastres co mo entidad ejecutora del Fon do para el Desarrollo del Plan Todos Somos FTSP PTSP-BIRF8649-184 / Brindar apoyo profesional como Espe cialista de Adquisiciones en l Component 4. Project Manag os procesos que adelanta la Individual Consult Under Implement IBRD / 86490 ement and Environmental a Post Limited 20,979.00 0.00 2022-07-11 2022-07-19 2022-07-16 2022-08-06 2022-09-10 2023-03-09 Unidad Nacional para la Gesti ant Selection ation nd Social Management ón del Riesgo de Desastres c omo entidad ejecutora del Fo ndo para el Desarrollo del Pla n Todos Somos PAZcífico. PTSP-BIRF8649-185 / Especi Component 4. Project Manag alista de Planeación y Segui Individual Consult Under Implement IBRD / 86490 ement and Environmental a Post Direct - National 20,979.00 0.00 2022-08-30 2022-08-30 2022-08-30 2022-09-28 2022-09-28 2023-09-27 miento FTSP - Recontratación ant Selection ation nd Social Management Natalia García Medina PTSP-BIRF8649-186 / Liderar la planificación, seguimiento y gestión ambiental de los pr oyectos que se adelanten en Component 4. Project Manag Individual Consult Pending Impleme el marco de los préstamos de IBRD / 86490 ement and Environmental a Post Direct - National 8,319.00 0.00 2022-09-19 2022-09-19 2022-10-07 2022-10-28 2023-04-26 ant Selection ntation l BID y el Banco Mundial, ejec nd Social Management utados por la Unidad Naciona l para la Gestión del Riesgo d e Desastres como entidad ej ecutora del Fondo PTSP-BIRF8649-187 / Coordi nar la implementación y sup ervisión de los préstamos del Component 4. Project Manag BID y el Banco Mundial, ejecu Individual Consult IBRD / 86490 ement and Environmental a Post Open - National 19,506.00 0.00 Canceled 2022-09-23 2022-09-20 2022-10-15 2022-10-17 2022-11-21 2023-05-20 tados por la Unidad Nacional ant Selection nd Social Management para la Gestión del Riesgo de Desastres como entidad ejec utora del Fondo para el Desa rrollo del Plan Todos Somos P AZcífico PTSP-BIRF-8649-188 / Presta r los servicios jurídicos como especialista para los proceso s de adquisiciones del Fondo Component 4. Project Manag Individual Consult Pending Impleme para el Desarrollo del Plan To IBRD / 86490 ement and Environmental a Post Open - National 12,587.00 0.00 2022-10-10 2022-11-28 2022-12-19 2023-01-23 2023-10-23 ant Selection ntation dos Somos PAZcífico que ade nd Social Management lanta como entidad ejecutora la Uni-dad Nacional para la G estión del Riesgo de Desastr es, en el marco PTSP-BIRF-8649-189 / AUDIT ORÍA DE LOS ESTADOS FINA NCIEROS DE PROPÓSITO ESP Component 4. Project Manag ECIAL Y ASEGURAMIENTO RA Pending Impleme IBRD / 86490 ement and Environmental a Post Direct Selection Direct - National 28,410.00 0.00 2022-10-10 2022-10-16 2023-01-09 2023-05-05 ZONABLE SOBRE LOS PROCE ntation nd Social Management SOS DE ADQUISICIONES DEL PROYECTO/PROGRAMA FINA NCIADO POR EL BID Y EL BAN CO MUNDIAL A TRAVÉS DE P RÉSTAMOS - PTSP-BIRF-8649-190 / Coordi nar la implementación y sup ervisión de los préstamos del Component 4. Project Manag BID y el Banco Mundial, ejecu Individual Consult Under Implement IBRD / 86490 ement and Environmental a Post Limited 19,506.00 0.00 2022-10-14 2022-10-07 2022-10-19 2022-09-27 2022-11-09 2022-12-14 2023-06-12 tados por la Unidad Nacional ant Selection ation nd Social Management para la Gestión del Riesgo de Desastres como entidad ejec utora del Fondo para el Desa rrollo del Plan Todos Somos P AZcífico Page 10 PTSP-BIRF-8649-191 / Lidera r el componente social de los proyectos que se generen en el marco de los préstamos de Component 4. Project Manag Individual Consult Pending Impleme l Banco Mundial ejecutados p IBRD / 86490 ement and Environmental a Post Direct - National 5,826.00 0.00 2022-11-07 2022-11-17 2022-12-08 2023-01-12 2023-07-11 ant Selection ntation or la Unidad Nacional para la nd Social Management Gestión del Riesgo de Desast res como entidad ejecutora d el Fondo para el Desarrollo d el Plan Todos Somos PTSP-BIRF-8649-192 / Lidera r la planificación, estructurac ión, seguimiento y gestión de Component 3. Capacity Buil los proyectos de Capacidad y ding and Institutional Streng Individual Consult Pending Impleme Fortalecimiento Institucional IBRD / 86490 thening of Service Providers Post Direct - National 4,160.00 0.00 2022-11-11 2022-11-16 2022-12-07 2023-01-11 2023-07-10 ant Selection ntation que hagan parte de los prést in the Municipalities of Guap amos del BID y el Banco Mun i and Tum aco dial, ejecutados por la Unida d Nacional para la Gestión de l Riesgo de Des PTSP-BIRF-8649-193 / Lidera r los procesos de adquisicion es que adelanta la Unidad Na cional para la Gestión del Rie Component 4. Project Manag Individual Consult sgo de Desastres como entid IBRD / 86490 ement and Environmental a Post Open - National 16,639.00 0.00 Signed 2022-11-11 2022-11-18 2022-12-19 2022-11-23 2023-01-09 2022-12-19 2023-02-13 2023-08-12 ant Selection ad ejecutora del Fondo para nd Social Management el Desarrollo del Plan Todos Somos PAZcífico, según las P olíticas, normas y regulacion es del BID y el Banc PTSP-BIRF-8649-194 / Lidera r las actividades relacionad as con protocolos y herrami Component 4. Project Manag entas de seguridad, para miti Pending Impleme IBRD / 86490 ement and Environmental a Post Direct Selection Direct - National 4,160.00 0.00 2022-11-10 2022-11-19 2023-01-23 2023-07-22 gar las posibles amenazas o ntation nd Social Management riesgos en la ejecución de los proyectos que se desarrollan en el marco de los préstamos del BID y el Banco Mundial, q ue ejecuta la PTSP-BIRF8649-194 / Brindar apoyo profesional como espe cialista de planeación, monit oreo, seguimiento y gestión Component 4. Project Manag Individual Consult Pending Impleme de los préstamos del Banco IBRD / 86490 ement and Environmental a Post Direct - National 23,731.00 0.00 2023-01-27 2023-02-01 2023-02-22 2023-03-29 2023-09-25 ant Selection ntation Mundial, ejecutados por la U nd Social Management nidad Nacional para la Gestió n del Riesgo de Desastres co mo entidad ejecutora del Fon do para el Desarrollo d PTSP-BIRF8649-195 / Liderar la planificación, seguimiento y gestión ambiental de los pr oyectos que se adelanten en Component 4. Project Manag Individual Consult Pending Impleme el marco de los préstamos de IBRD / 86490 ement and Environmental a Post Direct - National 18,822.00 0.00 2023-01-27 2023-02-01 2023-02-22 2023-03-29 2023-09-25 ant Selection ntation l BID y el Banco Mundial, ejec nd Social Management utados por la Unidad Naciona l para la Gestión del Riesgo d e Desastres como entidad ej ecutora del Fondo PTSP-BIRF-8649-195 / Realiz ar apoyo como profesional es pecializado en los procesos c ontractuales y relaciones jurí Component 4. Project Manag Individual Consult Pending Impleme dico negociales del Fondo pa IBRD / 86490 ement and Environmental a Post Limited 14,239.00 0.00 2023-02-06 2023-02-11 2023-03-04 2023-04-08 2023-10-05 ant Selection ntation ra el Desarrollo del Plan Todo nd Social Management s Somos PAZcífico - FTSP, cu ya entidad ejecutora es la Un idad Nacional para la Gestión del Riesgo de Des PTSP-BIRF-8649-196 / Brinda r apoyo profesional como Esp ecialista de Adquisiciones del préstamo 8649-CO en los pro Component 4. Project Manag Individual Consult Pending Impleme cesos que adelanta la Unidad IBRD / 86490 ement and Environmental a Post Direct - National 39,885.00 0.00 2023-02-22 2023-03-04 2023-03-25 2023-04-29 2023-10-26 ant Selection ntation Nacional para la Gestión del nd Social Management Riesgo de Desastres como en tidad ejecutora del Fondo par a el Desarrollo del Plan Todos Somos PAZcífico, s PTSP-BIRF-8649-199 / Lidera r las actividades relacionadas con protocolos y herramienta s de seguridad, para mitigar l Component 4. Project Manag Under Implement as posibles amenazas o riesg IBRD / 86490 ement and Environmental a Post Direct Selection Direct - National 18,822.00 0.00 2023-03-13 2023-03-22 2023-03-22 2023-05-26 2023-11-22 ation os en la ejecución de los proy nd Social Management ectos que se desarrollan en e l marco de los préstamos del BID y el Banco Mundial, que ejecuta la Unida PTSP-BIRF-8649-197 / TDR - Especialista Financiera en la gestión presupuestal y financ iera de los préstamos del BID Component 4. Project Manag Individual Consult Pending Impleme y el Banco Mundial, ejecutad IBRD / 86490 ement and Environmental a Post Direct - National 14,239.00 0.00 2023-03-13 2023-03-22 2023-04-12 2023-05-17 2023-11-13 ant Selection ntation os por la Unidad Nacional par nd Social Management a la Gestión del Riesgo de De sastres como entidad ejecuto ra del Fondo para el Desarrol lo del Plan Todos PTSP-BIRF-8649-198 / TDR- L iderar la gestión presupuesta l y financiera de los préstamo s del BID y el Banco Mundial, Component 4. Project Manag Individual Consult Pending Impleme ejecutados por la Unidad Nac IBRD / 86490 ement and Environmental a Post Direct - National 18,822.00 0.00 2023-03-13 2023-03-22 2023-04-12 2023-05-17 2023-11-13 ant Selection ntation ional para la Gestión del Ries nd Social Management go de Desastres como entida d ejecutora del Fondo para el Desarrollo del Plan Todos So mos PAZcífico. PTSP-BIRF-8649-201 / Lidera r la planificación, estructurac ión, seguimiento y gestión de Component 3. Capacity Buil los proyectos de Capacidad y ding and Institutional Streng Individual Consult Pending Impleme Fortalecimiento Institucional IBRD / 86490 thening of Service Providers Post Direct - National 18,822.00 0.00 2023-03-13 2023-03-22 2023-04-12 2023-05-17 2023-11-13 ant Selection ntation que hagan parte de los prést in the Municipalities of Guap amos del BID y el Banco Mun i and Tum aco dial, ejecutados por la Unida d Nacional para la Gestión de l Riesgo de Desa Page 11 PTSP- BIRF-8649-200 / Lider ar el componente social de lo s proyectos que se generen e n el marco de los préstamos Component 4. Project Manag Individual Consult del Banco Mundial ejecutado IBRD / 86490 ement and Environmental a Post Limited 15,685.00 0.00 Canceled 2023-03-13 2023-04-04 2023-03-17 2023-04-07 2023-05-12 2023-11-08 ant Selection s por la Unidad Nacional para nd Social Management la Gestión del Riesgo de Des astres como entidad ejecutor a del Fondo para el Desarroll o del Plan Todos Somos PTSP-BIRF-8649-202 / Presta r los servicios juridicos como especialista al Ordenador del Gasto, en los procesos de ad Component 4. Project Manag Individual Consult Pending Impleme quisiciones, así como en las IBRD / 86490 ement and Environmental a Post Direct - National 11,965.00 0.00 2023-04-04 2023-04-14 2023-05-05 2023-06-09 2023-12-06 ant Selection ntation actividades inherentes a la ej nd Social Management ecución de los proyectos que se desarrollan en el marco d e los prestamos del BID y el Banco Mundial.. PTSP-BIRF-8649-204 / Lidera r el componente social de los proyectos que se generen en el marco de los préstamos de Component 4. Project Manag Individual Consult Under Implement l Banco Mundial ejecutados p IBRD / 86490 ement and Environmental a Post Limited 31,370.00 0.00 2023-05-05 2023-05-11 2023-05-19 2023-05-16 2023-06-09 2023-07-14 2024-01-10 ant Selection ation or la Unidad Nacional para la nd Social Management Gestión del Riesgo de Desast res como entidad ejecutora d el Fondo para el Desarrollo d el Plan Todos Somos PSTP-BIRF-8649-206 / Lidera r la planificación, monitoreo, seguimiento y gestión de los Component 4. Project Manag Individual Consult Under Implement préstamos del BID y el Banco IBRD / 86490 ement and Environmental a Post Direct - National 18,822.00 0.00 2023-05-15 2023-05-25 2023-05-25 2023-06-15 2023-07-20 2024-01-16 ant Selection ation Mundial, ejecutados por la U nd Social Management nidad Nacional para la Gestió n del Riesgo de Desastres co mo entidad ejecutora del FTS P PTSP-BIRF-8649-203 / Lidera r la planificación,estructuraci ón, seguimiento y gestión de Component 1. Water Supply los proyectos de Agua y Sane and Basic Sanitation Improv Individual Consult amiento Básico que hagan p IBRD / 86490 Post Direct - National 15,684.00 0.00 Canceled 2023-04-04 2023-04-14 2023-05-05 2023-06-09 2023-12-06 ements in the Municipality o ant Selection arte de los préstamos del Ba f Guapi nco Mundial 8649 CO y 8798 CO, ejecutados por la Unidad Nacional para la Gestión del Riesgo de Desastres... PTSP-BIRF-8649-205 / Brinda r acompañamiento técnico pr ofesional ambiental en la ges Component 4. Project Manag tión de los Planes de Manejo Individual Consult Under Implement IBRD / 86490 ement and Environmental a Post Limited 17,438.00 0.00 2023-05-15 2023-05-25 2023-05-20 2023-06-10 2023-07-15 2024-01-11 Ambiental y Estudios de Imp ant Selection ation nd Social Management acto Ambiental de los proyec tos que se desarrollen en el marco del PTSP, que adelant a como entidad ejecutora de la UNGRD PTSP-BIRF-8649-208 / Presta r los servicios de acompaña miento integral y exclusivo al Ordenador del Gasto del FTS Component 4. Project Manag Individual Consult Pending Impleme P, en las actividades inherent IBRD / 86490 ement and Environmental a Post Limited 11,866.00 0.00 2023-06-02 2023-06-07 2023-06-28 2023-08-02 2024-01-29 ant Selection ntation es a la ejecución de los proye nd Social Management ctos que se desarrollan en el marco de los préstamos del BID y el Banco Mundial, que ejecuta la UNGRD. PTSP-BIRF-8649-209 / Coordi nar y dirigir la implementació n y supervisión de los présta mos del BID y el Banco Mund Component 4. Project Manag Individual Consult Pending Impleme ial, ejecutados por la Unidad IBRD / 86490 ement and Environmental a Post Direct - National 12,872.00 0.00 2023-06-02 2023-06-12 2023-07-03 2023-08-07 2024-02-03 ant Selection ntation Nacional para la Gestión del nd Social Management Riesgo de Desastres como en tidad ejecutora del Fondo par a el Desarrollo del Plan Todos Somos PAZcífico PTSP-BIRF-8649-212 / Actual ización, ajuste y complement Component 2. Water Supply ación de estudios y diseños d and Basic Sanitation Improv Under Implement IBRD / 86490 Post Direct Selection Direct - National 133,327.00 0.00 2023-06-09 2023-06-23 2023-06-19 2023-08-23 2024-02-19 e la nueva línea de aducción ements in the Municipality o ation del sistema de acueducto del f Tumaco distrito especial de Tumaco d epartamento de Nariño. PTSP-BIRF-8649-211 / LÍDER AGUA Y SANEAMIENTO BÁSIC Component 1. Water Supply O (TUMACO - GUAPI) - Liderar and Basic Sanitation Improv Individual Consult Pending Impleme IBRD / 86490 Post Open - National 62,739.00 0.00 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 la planificación, estructuració ements in the Municipality o ant Selection ntation n, seguimiento y gestión de l f Guapi os proyectos de Agua y Sane amiento Básico PTSP-BIRF-8649-210 / Lidera r la planificación, seguimient o y gestión ambiental de los proyectos que se adelanten e Component 4. Project Manag Individual Consult Pending Impleme n el marco de los préstamos IBRD / 86490 ement and Environmental a Post Open - National 18,822.00 0.00 2023-06-30 2023-08-18 2023-09-08 2023-10-13 2024-04-10 ant Selection ntation del BID y el Banco Mundial, e nd Social Management jecutados por la Unidad Naci onal para la Gestión del Ries go de Desastres como entida d ejecutora del FTSP Page 12 PROCUREMENT PLAN (Textual Part) CAMBODIA Sustainable Livelihood for Indigenous Communities Project (CSLICP—P174951) Project Implementation agency: Analyzing Development Issues Centre (ADIC) Date of the Procurement Plan: May 2021 Period covered by this Procurement Plan: January 2022 to June 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016; Revised November 2017 and November 2020) (“Procurement Regulations for IPF Borrower – 4th Edition”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Government of the Kingdom of Cambodia’s Updated Standard Operating Procedures and Procurement Manual for All Externally Financed Projects/Programs, promulgated through the Sub‐decree 181 ANK/BK dated December 2, 2019, which is issued pursuant to Article 3 of the Government of the Kingdom of Cambodia’s Law on Public Procurement dated January 14, 2012, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. i. Procurement shall be open to eligible firms from any country. ii. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, without limitation the Bank’s right to sanction and the Bank’s inspection 1 and audit rights as per attached confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including format; iii. Each Project shall put in place an effective complaint review system that includes review by the implementing agency and subsequent review by another party not involved in the in the procurement process, if not satisfied with the review of the implementing agency When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Other Relevant Procurement Information. The project will be followed the Project Implementation Manual and the Community Operational Manual; all the procurement activities under other components and sub- components will be governed by World Bank Procurement Regulations for IPF Borrowers, July 2016 (revised November 2017, Revised August 2018 and November 2020) Procurement Method and Prior Review Thresholds Procurement at National Open (USD) Prior Review Level Threshold International National RFQ (*) Moderate Risk Goods, IT, and non- 600k & above Below 600k Below 100k 4 million consulting services Consulting Firm 200k & above Below 200k N/A 2 million Individual Consultant 0.4 million (*) if the estimated cost over USD 25,000 SPN is required. 2 PROCUREMENT Cambodia : Cambodia Sustainable Livelihood for Indigenous Communities Project (CSLICP) PLAN General Information Country: Cambodia 2022-01-27 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174951 GPN Date: 2022-02-22 Project Name: Cambodia Sustainable Livelihood for Indigenous Communities Project (CSLICP) Loan / Credit No: TF / B6238 Analyzing Development Issues Centre Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Sub-component 1.1. Introdu ADIC-CSLICP-NS-G-001-A / M ction of new improved hortic aterials for demo-farms at pil Request for Quota Single Stage - One E Pending Impl TF / B6238 ulture production practices f Post Open - National 37,000.00 0.00 2022-05-10 2022-07-05 2022-10-03 oting phase (18 months perio tions nvelope ementation or community farmers throu d of implementing) gh farmer- ma naged demon stration farms. Sub-component 1.1. Introdu ADIC-CSLICP-NS-G-001-B / M ction of new improved hortic aterials for Demo-farms (in p Request for Quota Single Stage - One E Pending Impl TF / B6238 ulture production practices f Post Open - National 73,000.00 0.00 2023-07-16 2023-09-10 2023-12-09 eriod of implementing and ex tions nvelope ementation or community farmers throu panding phases) gh farmer- ma naged demon stration farms. ADIC-CSLICP-NS-G-002-A / M Sub-component 1.2. Provisio aterials for water solution init n of environmentally sustain Request for Quota Single Stage - One E Pending Impl iatives (i.e. gravity models, r TF / B6238 able water solutions for agri Post Open - National 28,133.33 0.00 2022-04-15 2022-06-10 2022-09-08 tions nvelope ementation am-pump, solar-powered, hy culture and adaptation to cli dro-powered pumps) (23 loca mate chan ge. tions) ADIC-CSLICP-NS-G-002-B / M Sub-component 1.2. Provisio aterials for water solution init n of environmentally sustain Request for Quota Single Stage - One E Pending Impl iatives (i.e. gravity models, r TF / B6238 able water solutions for agri Post Open - National 56,266.00 0.00 2023-07-16 2023-09-10 2023-12-09 tions nvelope ementation am-pump, solar-powered, hy culture and adaptation to cli dro-powered pumps) (23 loca mate chan ge. tions)- ADIC-CSLICP-NS-G-003-A / M Sub-component 1.3. Setting Request for Quota Single Stage - One E Under Imple aterials for school bio garden TF / B6238 Up School Bio-Gardens for C Post Open - National 30,000.00 0.00 2022-05-15 2023-05-26 2022-07-10 2022-10-08 tions nvelope mentation s apacity Development of Stu dents. ADIC-CSLICP-NS-G-003-B / M Sub-component 3.1. Project Request for Quota Single Stage - One E Pending Impl TF / B6238 Post Open - National 60,000.00 0.00 2023-07-16 2023-09-10 2023-12-09 aterials for school bio garden Management and Administra tions nvelope ementation s tion. Component 2. Improving Pro ADIC-CSLICP-NS-G-004 / Sig Request for Quota Single Stage - One E Pending Impl TF / B6238 ducer Links to Markets and Post Limited 5,000.00 0.00 2022-11-06 2023-01-01 2023-04-01 nage in the project areas tions nvelope ementation Horticulture Support Service s. ADIC-CSLICP-NS-G-005 / Offi Sub-component 3.1. Project Request for Quota Single Stage - One E TF / B6238 Post Limited 9,000.00 0.00 Signed 2022-02-06 2022-12-01 2022-04-03 2022-07-02 ce Equipment Management and Administra tions nvelope tion. ADIC-CSLICP-NS-G-006 / Offi Sub-component 3.1. Project Request for Quota Single Stage - One E TF / B6238 Post Limited 2,000.00 0.00 Completed 2022-02-06 2022-12-06 2022-04-03 2022-05-03 2023-03-19 ce furniture ( Management and Administra tions nvelope tion. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ADIC-CSLICP-CS-017 / Baseli Sub-component 3.2. Monitori Consultant Qualifi Under Implement TF / B6238 Post Open - National 10,000.00 0.00 2022-02-01 2022-09-01 2022-02-22 2022-03-23 2022-04-07 2022-05-12 2022-11-08 ne Survey ng and Evaluation. cation Selection ation ADIC-CSLICP-CS-018 / Mid Te Sub-component 3.2. Monitori Consultant Qualifi Pending Impleme TF / B6238 Post Open - National 8,000.00 0.00 2023-02-01 2023-02-22 2023-04-07 2023-05-07 2023-06-11 2023-09-09 rm Review ng and Evaluation. cation Selection ntation ADIC-CSLICP-CS-019 / End of Sub-component 3.2. Monitori Consultant Qualifi Pending Impleme TF / B6238 Post Open - National 10,000.00 0.00 2025-04-01 2025-04-22 2025-06-05 2025-07-05 2025-08-09 2025-11-07 Project Impact Assessment ng and Evaluation. cation Selection ntation ADIC-CSLICP-CS-020 / Projec Sub-component 3.1. Project Consultant Qualifi TF / B6238 Post Open - National 28,000.00 0.00 Canceled 2022-08-01 2022-12-09 2022-08-22 2023-01-18 2022-10-05 2022-11-04 2022-12-09 2026-03-02 t Audit (4 times of auditing) Management and Administra cation Selection tion. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Sub-component 1.1. Introdu ction of new improved hortic ADIC-CSLICP-CS-002 / Nation Individual Consult TF / B6238 ulture production practices f Post Open 40,000.00 0.00 Completed 2022-02-01 2022-04-02 2022-03-22 2022-11-12 2022-04-12 2022-11-18 2022-05-17 2022-11-13 2023-03-25 al Agronomist ant Selection or community farmers throu gh farmer- ma naged demon stration farms. Page 1 Sub-component 1.1. Introdu ction of new improved hortic ADIC-CSLICP-CS-003 / Nation Individual Consult TF / B6238 ulture production practices f Post Open 21,000.00 0.00 Completed 2022-02-01 2022-04-02 2022-03-22 2022-12-07 2022-04-12 2022-12-15 2022-05-17 2025-09-30 2023-03-26 al Demo-Farm Coordinator ant Selection or community farmers throu gh farmer- ma naged demon stration farms. Sub-component 1.1. Introdu ADIC-CSLICP-CS-004 / Nation ction of new improved hortic Individual Consult al PAR Community Coordinat TF / B6238 ulture production practices f Post Open 37,800.00 0.00 Completed 2022-02-01 2022-04-19 2022-03-22 2022-09-12 2022-04-12 2022-09-12 2022-05-17 2025-09-30 2023-03-25 ant Selection ors (3 positions) or community farmers throu gh farmer- ma naged demon stration farms. ADIC-CSLICP-CS-007 / Nation Sub-component 1.3. Setting Individual Consult al School Bio-garden Coordin TF / B6238 Up School Bio-Gardens for C Post Open 21,000.00 0.00 Completed 2022-02-01 2022-04-02 2022-02-27 2022-09-14 2022-03-06 2022-09-15 2022-04-10 2025-08-24 2023-03-25 ant Selection ator apacity Development of Stu dents. Sub-component 1.4. Commu ADIC-CSLICP-CS-021 / TVET Pending Impleme TF / B6238 nity-Based Vocational Traini Post Direct Selection Direct 31,000.00 0.00 2022-06-01 2022-06-11 2022-08-15 2023-12-31 Service Provider ntation ng for Youth. Sub-component 1.4. Commu ADIC-CSLICP-CS-008 / Nation Individual Consult TF / B6238 nity-Based Vocational Traini Post Open 21,000.00 0.00 Completed 2022-02-01 2022-04-02 2022-03-22 2022-09-01 2022-04-12 2022-09-13 2022-05-17 2025-09-30 2023-03-25 al TVET Coordinator ant Selection ng for Youth. Component 2. Improving Pro ADIC-CSLICP-CS-010 / Nation Individual Consult Under Implement TF / B6238 ducer Links to Markets and Post Open 25,000.00 0.00 2022-04-01 2022-04-19 2022-05-20 2022-06-10 2022-07-15 2025-09-30 al Agribusiness Expert ant Selection ation Horticulture Support Service s. ADIC-CSLICP-CS-015 / Financ Sub-component 3.1. Project Individual Consult TF / B6238 Post Open 48,000.00 0.00 Completed 2022-02-01 2022-02-26 2022-03-22 2022-06-22 2022-04-12 2022-07-01 2022-05-17 2025-12-31 2022-12-01 e Officer Management and Administra ant Selection tion. ADIC-CSLICP-CS-016 / Projec Sub-component 3.1. Project Individual Consult Pending Impleme TF / B6238 Post Open 8,000.00 0.00 2025-07-01 2025-08-19 2025-09-09 2025-10-14 2025-12-31 t Completion Report (ICR) Management and Administra ant Selection ntation tion. ADIC-CSLICP-CS-009 / M&E Sub-component 3.2. Monitori Individual Consult Under Implement Database System (Developer TF / B6238 Post Direct 20,000.00 0.00 2022-02-01 2022-03-04 2022-02-11 2022-03-04 2022-04-08 2022-10-05 ng and Evaluation. ant Selection ation ) (System Project Manageme nt) ADIC-CSLICP-CS-013 / Nation Sub-component 3.2. Monitori Individual Consult Under Implement TF / B6238 Post Direct 36,000.00 0.00 2022-06-01 2023-01-30 2022-06-11 2022-07-02 2022-08-06 2024-08-31 al M&E Database Expert ng and Evaluation. ant Selection ation Component 2. Improving Pro ADIC-CSLICP-CS-011 / Intern Individual Consult TF / B6238 ducer Links to Markets and Post Direct 37,500.00 0.00 Signed 2023-02-01 2022-04-02 2023-02-11 2022-09-12 2023-03-04 2022-07-01 2023-04-08 2023-07-07 ational Horticulture Advisor ant Selection Horticulture Support Service s. Component 2. Improving Pro ADIC-CSLICP-CS-012 / Media Individual Consult Under Implement TF / B6238 ducer Links to Markets and Post Direct 12,600.00 0.00 2022-02-01 2022-04-29 2022-02-11 2023-04-01 2022-03-03 2022-04-03 2025-12-31 & Communication Specialist ant Selection ation Horticulture Support Service s. ADIC-CSLICP-CS-014 / Procur Sub-component 3.1. Project Individual Consult TF / B6238 Post Open 24,000.00 0.00 Completed 2022-02-01 2022-04-19 2022-03-22 2022-10-09 2022-04-12 2022-09-09 2022-05-17 2024-05-31 2023-03-25 ement Consultant Management and Administra ant Selection tion. Sub-component 1.2. Provisio ADIC-CSLICP-CS-005 / Nation n of environmentally sustain Individual Consult Under Implement TF / B6238 Post Open 12,000.00 0.00 2022-03-01 2022-03-04 2022-04-19 2022-05-10 2022-06-14 2023-12-31 al Water-Technical Experts able water solutions for agri ant Selection ation culture and adaptation to cli mate chan ge. Sub-component 1.1. Introdu ction of new improved hortic ADIC-CSLICP-CS-001 / Select Individual Consult TF / B6238 ulture production practices f Post Open 72,000.00 0.00 Signed 2022-02-01 2022-04-02 2022-02-27 2022-09-01 2022-03-06 2022-09-01 2022-04-10 2025-11-24 ion of Project Manager ant Selection or community farmers throu gh farmer- ma naged demon stration farms. Sub-component 1.1. Introdu ADIC-CSLICP-CS-004-B / Nati ction of new improved hortic Individual Consult Under Implement onal Community PAR Coordin TF / B6238 ulture production practices f Post Open 12,600.00 0.00 2022-04-20 2022-09-09 2022-06-08 2022-09-09 2022-06-29 2022-09-13 2022-12-31 2026-05-16 ant Selection ation ator or community farmers throu gh farmer- ma naged demon stration farms. Sub-component 1.1. Introdu ADIC-CSLICP-CS-004-C / Nati ction of new improved hortic Individual Consult Under Implement onal Community PAR Coordin TF / B6238 ulture production practices f Post Open 12,600.00 0.00 2022-04-30 2022-09-09 2022-06-18 2022-09-12 2022-07-09 2022-09-14 2022-08-13 2023-02-09 ant Selection ation ator or community farmers throu gh farmer- ma naged demon stration farms. ADIC-CSLICP-CS-006-B / Nati Sub-component 1.3. Setting Individual Consult Pending Impleme onal Community PAR Coordin TF / B6238 Up School Bio-Gardens for C Post Open 12,600.00 0.00 2023-03-01 2023-04-19 2023-05-10 2023-06-14 2023-12-11 ant Selection ntation ator apacity Development of Stu dents. Sub-component 1.2. Provisio ADIC-CSLICP-CS-006 / Nation n of environmentally sustain Individual Consult Pending Impleme al PAR Community Coordinat TF / B6238 Post Open 12,600.00 0.00 2023-03-01 2023-04-19 2023-05-10 2023-06-14 2025-10-31 able water solutions for agri ant Selection ntation or culture and adaptation to cli mate chan ge. ADIC-CSLICP-SSS-020 / Inde Sub-component 3.1. Project Under Implement pendent External Auditor for TF / B6238 Management and Administra Post Direct Selection Direct - National 5,500.00 0.00 2023-05-04 2023-05-01 2023-05-14 2023-07-18 2024-01-14 ation Annual Project Financial Stat tion. ements Audit Page 2 PROCUREMENT PLANS (Textual Part) Information on the Projects: Ukraine Emergency COVID-19 Response Vaccination Project, P175895 Additional financing to Ukraine Emergency COVID-19 Response Vaccination Project, P177894 Project Implementation agency: Ministry of Health of Ukraine Date of the Procurement Plans: September and December 2021 Period covered by these Procurement Plans: September 2021 - March 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers”, dated November 2020 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Projects. This textual part along with the Procurement Plans tables in STEP constitute the Procurement Plans for the Projects. The following conditions apply to all procurement activities in the Procurement Plans. The other elements of the Procurement Plans as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Law of Ukraine "On Public Procurement" № 922-VIII dated December 25, 2015 and introduced by Law of Ukraine № 114-IX dated September 19, 2019 (with changes), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements (other than national open competitive procurement arrangements) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables. Other Relevant Procurement Information. Procurement for COVID-19 Vaccines and logistic services under Subcomponent 1.1 (COVID-19 Vaccination Support) of the Part 1 of the Projects (Strengthen Public Health System) will be carried out through retroactive financing. Procurement under Part 2 of the Projects (Support Service Delivery) will be carried out in accordance with the Loan Agreement, the Operations Manual, the Vaccines Delivery and Distribution Manual, the Anti-Corruption Guidelines and the Environmental and Social Commitment Plan. PROCUREMENT Ukraine : Ukraine Emergency COVID-19 Response and Vaccination Project PLAN General Information Country: Ukraine 2021-09-20 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175895 GPN Date: 2022-03-11 Project Name: Ukraine Emergency COVID-19 Response and Vaccination Project Loan / Credit No: IBRD / 92500, IBRD / 93150, IBRD / 93690 Ministry of Health of Ukraine Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RF-1.1.1 / COVID-19 vaccine Strengthen public health sys Under Imple IBRD / 92500 Prior Direct Selection Direct 0.00 2021-09-30 2021-09-21 2021-10-05 2021-09-21 2021-11-09 2022-05-08 s and logistics tem mentation UN-1.2.1 / COVID-19 Antigen Strengthen public health sys IBRD / 92500 Prior Direct Selection Direct 0.00 Canceled 2021-10-05 2021-10-15 2021-11-19 2022-11-14 -based Rapid Diagnostic Test tem s UN-1.1.2 / Cold chain equip Strengthen public health sys IBRD / 92500 Prior Direct Selection Direct 14,723,388.09 Signed 2021-12-13 2021-12-09 2021-12-18 2021-12-13 2022-01-17 2022-01-01 2023-01-12 ment for COVID-19 vaccine st tem orage AF/RF-1.1.1 / COVID-19 vacci IBRD / 93150 Strengthen public health sys Prior Direct Selection Direct 105,007,763.00 Signed 2021-12-16 2021-12-16 2021-12-17 2021-12-16 2021-12-20 2021-05-01 2022-03-30 nes tem AF/RF-1.1.2 / COVID-19 vacci IBRD / 93150 Strengthen public health sys Prior Direct Selection Direct 14,992,237.50 Signed 2022-02-27 2022-02-26 2022-02-28 2022-02-26 2022-03-03 2021-06-09 2022-05-12 nes tem AF2/RF-1.1.1 / COVID-19 vac IBRD / 93690 Strengthen public health sys Prior Direct Selection Direct 91,163,261.00 Signed 2022-03-11 2022-03-12 2022-03-12 2022-03-12 2022-03-15 2021-06-09 2022-05-24 cines tem DS-1.1.7 / Procurement of m Strengthen public health sys IBRD / 92500 Post Direct Selection Direct 0.00 Signed 2022-07-13 2022-06-24 2022-07-20 2022-07-11 2022-08-10 2022-11-08 edical waste containers tem AF/RFQ-1.1.8 / Procurement Strengthen public health sys Request for Quota Single Stage - One E IBRD / 93150 Post Open - National 0.00 Signed 2022-08-17 2022-09-21 2022-11-20 of computer equipment tem tions nvelope RFB-1.1.2/1 / Procurement of Strengthen public health sys Single Stage - One E vehicles with refrigerators for IBRD / 92500 Post Request for Bids Open - National 0.00 Canceled 2022-09-05 2022-09-10 2022-10-22 2022-11-05 2022-12-10 2023-03-31 tem nvelope SOE "Ukrvaktsina" AF/RFQ-1.1.10 / Procuremen Strengthen public health sys Request for Quota Single Stage - One E t of computer equipment for IBRD / 93150 Post Open - National 0.00 Signed 2022-08-29 2022-10-03 2023-01-01 tem tions nvelope regional offices of MOH's Pub lic Health Center RFB-1.1.9 / Equipment for m Strengthen public health sys Open - Internationa Single Stage - One E Under Imple IBRD / 93150 Prior Request for Bids 0.00 2022-12-31 2023-02-08 2023-01-14 2023-05-13 2023-02-28 2023-05-16 2023-03-14 2023-04-04 2023-10-01 edical waste decontaminatio tem l nvelope mentation n RFQ-1.1.5/7 / Procurement a Strengthen public health sys Request for Quota Single Stage - One E Under Imple IBRD / 92500 Post Open - National 0.00 2022-10-02 2022-11-09 2023-02-07 nd installation of RAM tem tions nvelope mentation RFQ-1.1.15 / Procurement of Strengthen public health sys Request for Quota Single Stage - One E Pending Impl Electronic Document Manage IBRD / 93150 Post Open - National 0.00 2023-01-10 2023-02-08 2023-04-09 tem tions nvelope ementation ment System RFQ-1.1.16 / Procurement of Strengthen public health sys Request for Quota Single Stage - One E Under Imple IBRD / 93150 Post Open - National 0.00 2023-01-10 2023-02-08 2023-05-09 Uninterruptible Power Supply tem tions nvelope mentation RFQ-1.1.17 / Implementation Strengthen public health sys Request for Quota Single Stage - One E Pending Impl IBRD / 93150 Post Open - National 0.00 2023-01-17 2023-03-15 2024-02-08 of Controlled and Segmented tem tions nvelope ementation Network RFQ-1.1.19 / Procurement of Strengthen public health sys Request for Quota Single Stage - One E IBRD / 93150 Post Open - National 0.00 Canceled 2023-01-17 2023-02-22 2023-04-23 Computer Equipment tem tions nvelope DS-1.1.18 / Procurement of Strengthen public health sys Direct - Internation IBRD / 92500 Prior Direct Selection 0.00 Signed 2022-12-28 2023-01-07 2022-12-28 2023-01-09 2023-01-05 2023-03-06 2024-01-05 backup power generators tem al RFQ-1.1.2/1 / Procurement o Strengthen public health sys Request for Quota Single Stage - One E Under Imple f vehicles with refrigerators f IBRD / 92500 Post Open - National 0.00 2023-04-08 2023-06-03 2023-11-30 tem tions nvelope mentation or SOE "Ukrvaktsina" DS-1.2.3 / Supply of Comput Strengthen public health sys Direct - Internation IBRD / 93150 Prior Direct Selection 0.00 Signed 2023-04-25 2023-05-09 2023-04-25 2023-05-17 2023-05-12 2023-06-26 2023-10-27 er Tomography Scanners tem al DS-1.1.2/1 / Supply of Sinov Strengthen public health sys Direct - Internation IBRD / 92500 Post Direct Selection 0.00 Canceled 2023-05-01 2023-05-01 2023-05-14 2023-07-13 enture Goods tem al DS-1.2.2/2 / Supply of Mehec Strengthen public health sys Direct - Internation Pending Impl IBRD / 92500 Post Direct Selection 0.00 2023-05-18 2023-05-18 2023-05-31 2023-07-30 o Goods tem al ementation DS-1.2.2/1 / Supply of Sinov Strengthen public health sys Direct - Internation Pending Impl IBRD / 92500 Post Direct Selection 0.00 2023-05-18 2023-05-18 2023-05-31 2023-07-30 enture Goods tem al ementation DS-1.2.2/3 / Supply of Sinop Strengthen public health sys Direct - Internation Pending Impl IBRD / 92500 Post Direct Selection 0.00 2023-05-25 2023-05-25 2023-06-07 2023-10-25 harm Goods tem al ementation RFQ-1.1.5/11 / Purchase of A Strengthen public health sys Request for Quota Single Stage - One E Pending Impl IBRD / 92500 Post Open - National 0.00 2023-07-06 2023-08-10 2023-10-09 tlassian software products tem tions nvelope ementation DS-1.2.2/4 / Supply of Therm Strengthen public health sys Direct - Internation Pending Impl IBRD / 92500 Post Direct Selection 0.00 2023-06-23 2023-06-23 2023-07-06 2024-01-02 o Fisher Scientific Goods and tem al ementation Services NON CONSULTING SERVICES Page 1 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AF/DS-1.1.7 / Services of the National Contact Center for C Strengthen public health sys IBRD / 93150 Post Direct Selection Direct 701,207.15 Signed 2022-04-02 2022-04-11 2022-04-05 2022-04-11 2022-04-09 2022-05-01 2023-03-31 OVID-19 Counteraction and S tem upport during Martial Law RFQ-1.1.8/1 / Services of tra nsportation and thermal disp Strengthen public health sys Request for Quota Single Stage - One E IBRD / 92500 Post Open - National 0.00 Canceled 2022-06-13 2022-07-31 2023-02-28 osal of epidemiologically haz tem tions nvelope ardous medical waste in Zak arpats’ka oblast’ RFQ-1.1.8/2 / Services of tra nsportation and thermal disp Strengthen public health sys Request for Quota Single Stage - One E IBRD / 92500 Post Open - National 0.00 Canceled 2022-06-13 2022-07-31 2023-02-28 osal of epidemiologically haz tem tions nvelope ardous medical waste in Lviv s’ka oblast’ RFQ-1.1.8/3 / Services of tra nsportation and thermal disp Strengthen public health sys Request for Quota Single Stage - One E IBRD / 92500 Post Open - National 0.00 Canceled 2022-06-13 2022-07-31 2023-02-28 osal of epidemiologically haz tem tions nvelope ardous medical waste in Ivan o-Frankivs’ka oblast’ RFQ-1.1.8/4 / Services of tra nsportation and thermal disp Strengthen public health sys Request for Quota Single Stage - One E IBRD / 92500 Post Open - National 0.00 Canceled 2022-06-13 2022-07-31 2023-02-28 osal of epidemiologically haz tem tions nvelope ardous medical waste in Tern opils’ka oblast’ RFQ-1.1.8/5 / Services of tra nsportation and thermal disp Strengthen public health sys Request for Quota Single Stage - One E IBRD / 92500 Post Open - National 0.00 Canceled 2022-06-13 2022-07-31 2023-02-28 osal of epidemiologically haz tem tions nvelope ardous medical waste in Cher nivets’ka oblast’ RFQ-1.1.8/6 / Services of tra nsportation and thermal disp Strengthen public health sys Request for Quota Single Stage - One E IBRD / 92500 Post Open - National 0.00 Canceled 2022-06-13 2022-07-31 2023-02-28 osal of epidemiologically haz tem tions nvelope ardous medical waste in Vinn yts’ka oblast’ RFQ-1.1.5/6 / Development of the module “Procurement, Strengthen public health sys Request for Quota Single Stage - One E IBRD / 92500 Post Open - National 0.00 Canceled 2022-09-23 2022-11-04 2023-06-02 services and basic configurat tem tions nvelope ion” of the eStock system RFQ-1.1.11 / Procurement of Strengthen public health sys Request for Quota Single Stage - One E MIS cyber vulnerabilities acc IBRD / 93150 Post Open - National 0.00 Signed 2022-10-12 2022-11-23 2023-01-22 tem tions nvelope essment software DS-1.1.5/8 / Implementation Strengthen public health sys Under Imple of SAP Ariba Contracts Mana IBRD / 92500 Post Direct Selection Direct - National 0.00 2022-11-20 2022-11-28 2022-11-25 2022-12-13 2023-03-14 tem mentation gement module RFQ-1.1.5/5 / MOH of Ukrain Strengthen public health sys Request for Quota Single Stage - One E Under Imple IBRD / 92500 Post Open - National 0.00 2022-10-20 2022-12-15 2023-04-14 e web portal development se tem tions nvelope mentation rvices DS-1.1.20 / Transport servic Under Imple es for the delivery of equipm IBRD / 92500 Support service delivery Post Direct Selection Direct - National 0.00 2023-05-24 2023-05-12 2023-05-29 2023-05-30 2023-06-03 2023-12-31 mentation ent in Ukraine CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CQS-1.1.6 / Support to COVI Strengthen public health sys Consultant Qualifi D-19 vaccination communica IBRD / 92500 Post Open - National 0.00 Canceled 2022-01-23 2022-02-13 2022-03-13 2022-03-27 2022-04-24 2023-03-20 tem cation Selection tion campaign CQS-1.1.5/1 / Development of the module “Procurement, Strengthen public health sys Consultant Qualifi IBRD / 92500 Post Open - National 0.00 Canceled 2022-05-18 2022-06-10 2022-06-08 2022-07-13 2022-07-27 2022-08-17 2023-04-14 services and basic configurat tem cation Selection ion” of the eStock system CQS-1.1.5/2 / Optimization o Strengthen public health sys Consultant Qualifi Under Implement IBRD / 92500 Post Open - National 0.00 2022-06-15 2022-08-31 2022-07-06 2022-08-03 2022-08-10 2022-08-24 2023-03-22 f the Electronic Health Care S tem cation Selection ation ystem CQS-1.1.5/3 / Increasing the Strengthen public health sys Consultant Qualifi Under Implement capacity of the patient notific IBRD / 92500 Post Open - National 0.00 2022-06-30 2022-07-28 2022-07-21 2022-08-11 2022-08-18 2022-09-01 2022-11-30 tem cation Selection ation ation in the Electronic Health Care System CQS-1.1.5/4 / Development of a component of the format Strengthen public health sys Consultant Qualifi IBRD / 92500 Post Open - National 0.00 Under Review 2022-08-31 2022-09-27 2022-09-21 2022-10-12 2022-10-19 2022-11-02 2023-03-31 ion of COVID-certificates with tem cation Selection in the Electronic Health Care System AF/QCBS-1.1.12 / Developm Strengthen public health sys Quality And Cost- Under Implement ent of specific modules of the IBRD / 93150 Post Open - National 0.00 2022-11-22 2022-11-21 2022-12-13 2023-01-03 2023-01-31 2023-02-14 2023-03-21 2023-04-25 2023-12-21 tem Based Selection ation eStock System CQS-1.1.5/9 / Doctors` and p Strengthen public health sys Consultant Qualifi atients` login separation in t IBRD / 92500 Post Open - National 0.00 Signed 2022-12-15 2022-12-19 2023-01-05 2023-01-26 2023-03-02 2023-02-02 2023-05-16 2023-02-16 2023-06-16 tem cation Selection he eHealth CDB CQS-1.1.5/10 / Study of the Strengthen public health sys Consultant Qualifi Under Implement asynchronous data transmiss IBRD / 92500 Post Open - National 0.00 2023-01-12 2023-01-12 2023-01-26 2023-02-08 2023-03-01 2023-03-05 2023-09-01 tem cation Selection ation ion model in the eHealth CQS-1.1.18 / Development o f the new software for the es sence "Sample of biomaterial Strengthen public health sys Consultant Qualifi Under Implement IBRD / 93150 Post Open - National 0.00 2022-12-30 2023-01-12 2023-01-13 2023-01-30 2023-02-20 2023-02-24 2023-05-25 " accounting functionality alo tem cation Selection ation ng with modification of the e xisting software in the eHealt h CDB CQS-1.1.14 / Preparation of t he Terms of reference for the Strengthen public health sys Consultant Qualifi Under Implement IBRD / 93150 Post Open - National 0.00 2023-01-16 2023-03-08 2023-01-30 2023-02-16 2023-03-09 2023-03-13 2023-08-10 development of a Register of tem cation Selection ation human resources in healthca re Page 2 CQS-1.1.20 / Improvement o Strengthen public health sys Consultant Qualifi Under Implement f epidemiological surveillanc IBRD / 93150 Post Open - National 0.00 2022-12-23 2022-12-07 2023-01-13 2023-02-03 2023-02-10 2023-02-13 2023-08-12 tem cation Selection ation e processes 1.1.4/1 / Trainings on medic Strengthen public health sys Consultant Qualifi Under Implement IBRD / 92500 Post Open - National 0.00 2023-02-01 2023-01-27 2023-02-15 2023-02-28 2023-03-21 2023-03-25 2024-03-24 al waste management tem cation Selection ation CQS-1.1.21 / Development o f the new software for the es Strengthen public health sys Consultant Qualifi Under Implement sence "Care Team" accountin IBRD / 93150 Post Open - National 0.00 2023-03-12 2023-05-12 2023-03-26 2023-04-12 2023-05-03 2023-05-07 2023-09-19 tem cation Selection ation g functionality along with mo dification of the existing soft ware in the eHealth CDB INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DS-1.1.9 / Consultant for exp Strengthen public health sys ert support of vaccination ag IBRD / 92500 Post Direct Selection Direct - National 20,943.64 Signed 2022-07-20 2022-07-01 2022-07-30 2022-08-08 2022-08-10 2022-08-26 2023-03-31 tem ainst COVID-19 DS-1.1.10 / Consultant for P Strengthen public health sys Under Implement IBRD / 92500 Post Direct Selection Direct - National 0.00 2022-08-25 2022-09-06 2022-08-30 2022-10-01 2023-03-31 ublic Health tem ation DS-1.1.11 / Immunoprophyla Strengthen public health sys Under Implement IBRD / 92500 Post Direct Selection Direct - National 0.00 2022-08-25 2022-09-06 2022-08-30 2022-10-01 2023-03-31 xis Consultant tem ation DS-1.1.12 / Сonsultant on inf Strengthen public health sys Under Implement ormation and technical issue IBRD / 92500 Post Direct Selection Direct - National 0.00 2022-08-25 2022-09-06 2022-08-30 2022-10-01 2023-03-31 tem ation s and software IC-1.1.13 / Information Tech Strengthen public health sys Individual Consult IBRD / 92500 Post Open - National 0.00 Signed 2022-09-21 2022-09-27 2022-10-07 2022-11-12 2022-10-14 2022-11-15 2022-10-24 2023-04-22 nology Consultant tem ant Selection IC-1.1.14 / Consultancy Supp Individual Consult Pending Impleme ort to the Ministry of Health o IBRD / 92500 Support service delivery Post Open - National 0.00 2022-09-25 2022-10-11 2022-10-18 2022-10-28 2023-03-31 ant Selection ntation f Ukraine to Receive Addition al Financing DS-1.1.15 / Regional Coordin Under Implement IBRD / 92500 Support service delivery Post Direct Selection Direct - National 0.00 2022-09-18 2022-09-16 2022-09-23 2022-10-01 2023-03-31 ation Consultant ation IC-1.1.17 / Consultant for vis Strengthen public health sys Individual Consult ual accompaniment of the co IBRD / 92500 Post Open - National 0.00 Signed 2022-10-03 2022-09-27 2022-10-19 2022-10-28 2022-10-26 2022-11-03 2022-11-05 2023-05-04 tem ant Selection mmunication support for refo rms IC-1.1.16 / Medical Waste M Strengthen public health sys Individual Consult IBRD / 92500 Post Open - National 0.00 Signed 2022-09-30 2022-09-27 2022-10-22 2022-11-14 2022-10-29 2022-11-14 2022-11-06 2023-03-31 anagement Consultant tem ant Selection DS-1.1.21 / Audit of NHSU b udget reports under 9110-UA Strengthen public health sys Under Implement IBRD / 92500 Post Direct Selection Direct - National 0.00 2023-05-31 2023-06-19 2023-06-06 2023-06-30 2024-06-29 and 9250-UA Projects (2020, tem ation 2021 and 2022) and 9369-U A Project audit (2022) Page 3 Republic of Malawi Ministry of Education, Science and Technology Private Bag 328 Lilongwe 3 PROCUREMENT PLAN For PROJECT PREPARATORY ADVANCE (PPA) Name of Project: Skills for A Vibrant Economy (SAVE) Loan No./Credit No./Grant No.: P172627 Financiers: World Bank Implementing Agency: Ministry of Education, Science & Technology Beneficiary Institutions: Ministry of Education, Science & Technology Ministry of Labour Ministry of Youth TEVETA NCHE Ministry of Gender Selected Public Universities SAVE PROJECT PPA PROCUREMENT PLAN I. General 1.Project information Country: Malawi Project Name: Skills for A Vibrant Economy (SAVE) Project ID: P172627 2.Project Implementation Agency: Ministry of Education Science and Technology 3.Date of the Procurement Plan: June 22, 2020 4.Period covered by this Procurement Plan: June 2020 to November 2021 II. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. III. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. IV. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in The Public Procurement and Disposal of Assets Act, 2017 and its subsidiary instruments namely: The Public Procurement Regulations, 2004, Desk Instructions (2005), Standard bidding Documents and Circulars for the Public Procurement and Disposal of Assets (PPDA) Authority such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations under the following conditions: o Provision of “set-asides” contracts for small enterprises shall not be applied. o Criteria such as environmental aspect, extent of local content, technology transfer, and managerial, scientific & operational skills development shall not be used in the evaluation of bids unless specifically agreed by the Bank on case to case basis. o Procurement Documents include provisions, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. V. Prequalification: Not expected for works/goods packages in the procurement plan. VI. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable VII. Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. VIII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable for those contracts identified in the Procurement Plan tables; Works: Not Applicable for those contracts identified in the Procurement Plan tables. IX. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not Applicable. X. Proposed Procedures for CDD Components: Not Applicable XI. Other Relevant Procurement Information: None XII. Reference to (if any) Project Operational/Procurement Manual: The Ministry of Education Science and Technology (MoEST) team will prepare Procurement manual. The Procurement Plan will also form part of the Project Implementation Manual. XIII. Procurement Approach and Prior Review Thresholds: The Procurement Arrangements as indicated in the below table will be used. The thresholds for the Bank’s prior review requirements are also provided in the table: Prior-review Thresholds for Procurement Methods Thresholds Procurem Substanti Works Goods, IT & Non-Consulting Shortlist of National ent al Services Consultants Type Risk ($`000) Works 10,000 Open Request Request Engineerin Internatio for for Open Open Open Consultin g& nal or Quotatio Quotatio National internatio National g Constructio n or n or or NCB nal or ICB or NCB Services n ICB National National ($'000) ($'000) ($'000) ($'000) Supervision ($'000 Shopping Shopping ($'000) ($'000) ($'000) Goods, IT 2,000 & Non- Consulting ≧ < ≦ ≧ < ≦ < ≦ Services Consultan 1,000 ts (Firms) 7,000 7,000 200 1,000 1,000 100 200 300 Individual 300 Consultan ts *These prior review thresholds are for the purposes of the initial procurement plan for the first 18 months. The thresholds will be revised periodically based on re-assessment of risks. All contracts not subject to prior review will be post-reviewed. Procurement Packages/Plan with Procurement Arrangements and Time Schedule: as per the table below: b) PROCUREMENT PLAN A. Works There are no envisaged works under the PPA. 1 2 3 4 5 6 7 8 9 10 Ref. Contract Estimat Market Selecti Prequ Domesti Revie Expect Expecte No. Description ed Approa on alifica c w ed bid d Cost ch Method tion Prefere by openin Contrac US$ (yes/n nce Bank g date t o) (yes/no) (Prior Signatu / Post) re Date 1. N/A B. Goods and Non-Consulting Services 1 2 3 4 5 6 7 8 9 10 Ref. Contract Estimat Market Selecti Prequ Domesti Revie Expect Expecte No. Description ed Approa on alifica c w ed bid d Cost ch Method tion Prefere by openin Contrac US$ (yes/n nce Bank g date t o) (yes/no) (Prior Signatu / Post) re Date 1. Procurement of 1 motor 75,000.0 Limited RFQ No No Post 21-Jul- 21-Aug- vehicle (4 x 4 Twin Cab 0 20 20 Vehicles) for the PIU 2. Procurement of various 85,500.0 Limited RFQ No No Post 21-Jul- 21-Aug- ICT Items: Computer 0 20 20 laptops, Computer Desktops, Photocopier, printers, cameras, Flash discs, Anti-virus, MS package, Extension cables, Extension cables 3. Procurement of 187,000. Open RFB No No Post 1-Aug- 1-Oct-20 Teleconferencing 00 National 20 equipment and licences under COVID- 19 support 4. Procurement of 14,500.0 Limited RFQ No No Post 1-Aug- 31-Aug- Internet modems 0 20 20 devices under COVID- 19 support 5. Procurement of Hand 7,000.00 Limited RFQ No No Post 1-Aug- 31-Aug- sanitizers, face 20 20 masks/shields and gloves under COVID-19 support C. Consultancy Services 1 2 3 4 5 6 7 8 9 10 Ref. Contract Estimat Market Selecti Evalua Shortli Review Review Expecte No. Description ed Approa on tion sting by by Bank d bid Cost ch Method Option (yes/n Bank (Prior / opening US$ o) (Prior / Post) date Post) 1. Consultancy service to 46,000. Open INDV No No Post 1-Aug-20 7-Sep-20 develop Project 00 Implementation Manual 2. Consultancy service to 86,000. Open CQS Rated No Post 1-Aug-20 7-Sep-20 carry out Environmental 00 National Social Safeguard studies-ESMF, SEP, ESMCP, P4R (Firm) 3. Hiring of Project 64,000. Open INDV No No Post 1-Aug-20 7-Sep-20 Manager 00 4. Hiring of Financial 48,000. Open INDV No No Post 1-Aug-20 7-Sep-20 Management Specialist 00 5. Hiring of Procurement 48,000. Open INDV No No Post 1-Aug-20 7-Sep-20 Specialist 00 6. Hiring of M & E Specialist 48,000. Open INDV No Post 1-Aug-20 7-Sep-20 00 7. Hiring of 48,000. Open INDV No Post 1-Aug-20 7-Sep-20 Communications 00 Specialist 8. Hiring of Social 48,000. Open INDV No Post 1-Oct-20 15-Nov- Safeguards Specialist 00 20 9. Hiring of Environmental 48,000. Open INDV No Post 31-Jan- 15-Mar- Specialist 00 21 21 10. Consultancy Service to 92,000. Open CQS Rated No Post 28-Feb- 15-Apr- conduct a Skills Needs 00 National 21 21 Assessment (Firm) 11. Consultancy to 60,000. Open CQS Rated No Post 1-Oct-20 15-Nov- conceptualize a holistic, 00 National 20 integrated ICT-based structure that details elements related to M&E (including EMIS), labor market information and integration platform, communications channels, and mobile- based activities (Firm) 12. Consultant on Dual 53,000. Open CQS Rated No Post 28-Feb- 15-Apr- Learning -Engage, 00 National 21 21 Inception reports, sensitization meetings and advertisements, Engage Partner organizations to participate in the programme, Engage and Train Master Trainers, Build capacity of the key staff in the project, Benchmark Dual Learning, Pilot Dual learning with STC, LTC, MZTC (Firm) 13. Consultancy Service to 75,000. Open CQS Rated No Post 21-Oct- 28-Nov- conduct assessment of 00 National 20 20 ODeL requirements (infrastructure for Higher Education Institutions (HEI) and Technical and Vocational Education) in TEVET institutions (Firm) 14. Consultancy Services on 33,000. Open INDV No Post 1-Aug-20 22-Sep- proposal development 00 20 for tertiary institutions such as TEVET Providers, Nalikule and DCE 15. RFQ – Request for Quotations; CQS - Consultant’s Qualification-based Selection; QCBS – Quality and Cost-based Selection and; INDV - Individual Consultant Selection. Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. Title of the person signing the Letter: PROCUREMENT Malawi : Skills for A Vibrant Economy Project PLAN General Information Country: Malawi 2022-10-25 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172627 GPN Date: 2021-09-24 Project Name: Skills for A Vibrant Economy Project Loan / Credit No: IDA / 68910 Nalikule College of Education Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MW-NCE-321433-CW-RFB / C Request for Bids - onstruction of Odel Centre (L Supporting Increased Access Single Stage - One E Small Works SPD Pending Imp 2023-11-2 ecturer rooms, Offices, Repro IDA / 68910 to Skills Development Progra Post Request for Bids Open - National 1,400,000.00 0.00 2022-12-22 2022-12-27 2023-02-07 2023-03-09 2023-03-30 nvelope (1 envelope proce lementation 5 graphic room, ICT room, Foo ms in Higher Education ss) d nutrition & Analysis, Clothi ng and Textiles) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-NCE-321390-GO-RFQ / P Supporting Increased Access rocurement of Ict Equipment Request for Quota Single Stage - One E Pending Impl IDA / 68910 to Skills Development Progra Post Limited 67,000.00 0.00 2023-01-17 2023-02-14 2023-03-28 (Desktop Computers, Printers tions nvelope ementation ms in Higher Education , Laptops,Photocopiers) Supporting Increased Access MW-NCE-321434-GO-RFQ / P Request for Quota Single Stage - One E Under Imple IDA / 68910 to Skills Development Progra Post Limited 73,000.00 0.00 2023-01-10 2023-02-07 2023-03-21 rocurement of motor Vehicle tions nvelope mentation ms in Higher Education Supporting Increased Access MW-NCE-321429-GO-RFQ / P Request for Quota Single Stage - One E Pending Impl IDA / 68910 to Skills Development Progra Post Open - National 80,000.00 0.00 2024-02-05 2024-03-26 2024-05-07 rocurement of Furniture tions nvelope ementation ms in Higher Education MW-NCE-321379-GO-RFB / P Supporting Increased Access Single Stage - One E Pending Impl rocurement of Teaching and IDA / 68910 to Skills Development Progra Post Request for Bids Open - National 120,000.00 0.00 2023-06-20 2023-06-30 2023-08-04 2023-08-18 2023-09-06 2023-10-21 nvelope ementation Learning Materials ms in Higher Education MW-NCE-322030-GO-RFQ / P Supporting Increased Access Request for Quota Single Stage - One E Pending Impl rocurement of Science Consu IDA / 68910 to Skills Development Progra Post Limited 26,000.00 0.00 2023-06-06 2023-08-01 2024-01-28 tions nvelope ementation mables ms in Higher Education NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-NCE-326404-CS-CQS / C Supporting Increased Access onsultancy service for design Consultant Qualifi Under Implement IDA / 68910 to Skills Development Progra Post Open - National 125,000.00 0.00 2022-12-05 2023-05-12 2022-12-26 2023-02-08 2023-03-10 2023-03-26 2024-04-19 & construction supervision of cation Selection ation ms in Higher Education the Labs and Odel Centre. MW-NCE-362977-CS-CQS / D Supporting Increased Access esign and Construction Super Consultant Qualifi Pending Impleme IDA / 68910 to Skills Development Progra Post Open - National 50,000.00 0.00 2023-05-29 2023-06-19 2023-08-02 2023-09-01 2023-10-06 2025-07-07 vision for ODeL centre at Nali cation Selection ntation ms in Higher Education kule College of Education INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-NCE-322020-CS-INDV / Supporting Increased Access Individual Consult Pending Impleme Consultancy to design online IDA / 68910 to Skills Development Progra Post Open - National 15,000.00 0.00 2023-01-04 2023-02-06 2023-02-20 2023-03-20 2023-05-19 ant Selection ntation platform for Odel Programme ms in Higher Education MW-NCE-326460-CS-INDV / Supporting Increased Access Consultancy services for dev Individual Consult Pending Impleme IDA / 68910 to Skills Development Progra Post Limited 6,000.00 0.00 2022-11-23 2022-11-28 2022-12-19 2022-12-26 2023-02-24 elopment of Environmental & ant Selection ntation ms in Higher Education Social Management Plan for Odel Centre Page 1 PROCUREMENT PLAN General 1. Project Information a. Country: Federal Republic of Somalia b. Project Name: Horn of Africa - Ground Water for Resilience - Somalia Component c. Project Number: P174867 d. Total Finance: USD 30 million 2. Project Implementation Agency: Ministry of Energy and Water Resources (MoEWR) 3. Date of Project Plan: January 2022 4. Period Covered by this Procurement: April2021 – Nov 2023 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” November 2020 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Document: The Bank’s standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified into Procurement Plan tables in STEP III. National Procurement Arrangements: Not applicable IV. Prequalification: Not applicable V. Leased Assets: Not Applicable VI. Procurement of Second-hand Goods: Not Applicable VII. Domestic Preference: Not Applicable 1 VIII. Hands on Expanded Implementation Support (HEIS): Not applicable IX. Other Relevant Procurement Information: Not Applicable X. Thresholds for Procurement Approaches and Method (US$ millions) Based on the risks identified above, the following procurement arrangements are proposed: a) Approach to Market: Based on previous experience and available local market, the following threshold will be used of open national/international and RFQ bidding (all figures in million USD) Table 1.2: Thresholds for procurement approaches and methods Procurement Methods (US$ millions)–Goods, Works, and Non- Consulting Services Open Open Request for Direct Category Internatio National Quotation Selection nal (RfQ) Works ≥ 5.0 <5.0 ≤ 0.2 All Values Goods, IT, and non- ≥ 0.5 <0.5 ≤ 0.1 All Values consultin g services Thresholds for Procurement Approaches and Methods (US$, millions) – Consulting Services Category Short List of National Consultants Consulting Engineering and Services Construction Supervision Consultants (Firms) ≤ 0.1 ≤ 0.2 Individual Consultants N/A N/A Direct Selection Consultants (Firms) All Values All Values Individual Consultants All Values All Values 2 XI. Table Packages for Goods, Works and Non-Consulting Services (At Negotiations – to be entered in STEP) Procurement Selection Estimat Bank Approach Ref. Contract Title, Description and Method Evaluation ed Cost Oversig (Open- No Category (RFP, RFB, Method (US$) ht National/ RFQ etc.) Limited etc.) Most Water Quality Testing kits for 5 states - G1 37,500.0 Prior Limited RFQ advantageous FGS 0 Bid Most Vehicles (1 per MS, 2 for FGS/MoEWR) - G2 315,000. Prior Open-National RFB advantageous FGS & 5 states 00 Bid Most GW office furniture and equipment - FGS & 144,000. Prior Open-National RFB advantageous G3 5 states 00 Bid Most Hydromet center data, information and 30,000.0 G4 Prior Limited RFQ advantageous national monitoring equipment - FGS 0 Bid 526,50 0.00 Works Most Design new/rehabilitate FGS MoEWR office 100,000. W1 Prior Limited RFQ advantageous - FGS 00 Bid Most 250,000. W2 Build new offices - 5 states Prior Open-National RFB advantageous 00 Bid Establish GW-data and information office Most 10,000.0 W3 section within National Hydromet Center - Prior Limited RFQ advantageous 0 FGS Bid 1 Procurement Selection Estimat Bank Approach Ref. Contract Title, Description and Method Evaluation ed Cost Oversig (Open- No Category (RFP, RFB, Method (US$) ht National/ RFQ etc.) Limited etc.) Engage construction engineering firm in Most 600,000. Open- W4 water point development / investments - 5 Prior RFB advantageous 00 International state Bid Most Open- W5 Develop the manually drilling technique 320,000 Prior RFB advantageous International Bid Sub- 1,280,000 Total Market Method Review by Approach Estimated (QCBS, Ref No. Contract Description Bank (Open- Cost (US$) LCBCS, QBS, (Prior/Post) National/ DS Limited etc.) Consulting Services Consultancy Services for back-stopping Open- C1 528,000.00 Prior QCBS engineers - FGS International Consultancy - Comprehensive hydrogeological Open C2 600,000.00 Prior QCBS survey - FGS International Consultancy - Study and development of Merti C3 200,000.00 Prior Open – National CQS auifer water - FGS 2 Market Method Review by Approach Estimated (QCBS, Ref No. Contract Description Bank (Open- Cost (US$) LCBCS, QBS, (Prior/Post) National/ DS Limited etc.) Consultancy - Study on resilient water supply Open- C4 for densely populated rural/peri-urban areas - 480,000.00 Prior QCBS International FGS & 5 States Consultancy Services - Rapid assessment of existing GW-governance condition (incl standards, guidelines) and (i) arrange interim C5 200,000.00 Prior Open - National CQS project system and (ii) present to government national comprehensive system - FGS (50% of project total) Consultancy Services - Develop national GW- C6 75,000.00 Prior Limited CQS strategy - FGS C7 Arrange water quality testing in Nairobi - FGS 10,000.00 Prior TBD TBD Consultancy Services - Develop business models for private sector engagement in GW C8 210,000.00 Prior Open-National CQS development, distribution and management - FGS Consultancy Services - Develop transboundary C9 water management models and engage in 150,000.00 Prior Open-National CQS cooperation - FGS Develop national GW data and information C10 25,000.00 Prior Open-National CQS management system - FGS Consultancy Services - Transfer of knowledge and method development (incl manual well- C11 250,000.00 Prior Open-National QCBS drilling, sustainable gw-management; reduce cost of investments) - FGS Consultancy Services - Develop academic BSc C12 education in GW development, management 150,000.00 Prior Open-National QCBS and monitoring - FGS 3 Market Method Review by Approach Estimated (QCBS, Ref No. Contract Description Bank (Open- Cost (US$) LCBCS, QBS, (Prior/Post) National/ DS Limited etc.) Consultancy Services - Arrange and deliver 1 year long "learning by doing & organized C13 40,000.00 Prior Limited INDV training" package in groundwater development and management. Consultancy Services - Assess capacity development status/needs, develop linked C14 strategy, prepare project training and 70,000.00 Prior Limited INDV curriculum in selected GW capacity development topics - FGS Consultancy Services - Develop, establish and C15 support project monitoring, evaluation and 60,000.00 Prior Limited INDV internal learning system - FGS Consultancy Services - Arrange and deliver GW C16 75,000.00 Prior Limited INDV capacity development (a package) - FGS Consultancy Services - Arrange and deliver GW Open- C17 400,000.00 Prior QCBS capacity development (a package) - 5 states International C18 Project Coordinator NPCU (18 month) - FGS 126,000.00 Prior Open-National INDV C19 Groundwater Engineer NPCU (18 month) - FGS 99,000.00 Prior Open-National INDV Social & Environmental Safeguard Specialist C20 63,000.00 Prior Open-National INDV NPCU (18 month) - FGS C21 Finance Specialist NPCU (18 month) - FGS 63,000.00 Prior Open-National INDV Procurement Specialist for NPCU (18 months) – C22 63,000.00 Prior Open-National INDV FGS C23 Security Specialist for NPCU (18 months) - FGS 63,000.00 Prior Open-National INDV Gender and Social Safeguard Specialist for C24 63,000.00 Prior Open-National INDV NPCU (18 months) - FGS Community Development Specialist for NPCU C25 63,000.00 Prior Open-National INDV (18 months) - FGS C26 Office Manager for NPCU - FGS 18,000.00 Prior Open-National INDV 4 Market Method Review by Approach Estimated (QCBS, Ref No. Contract Description Bank (Open- Cost (US$) LCBCS, QBS, (Prior/Post) National/ DS Limited etc.) Consultancy Services - Arrange a project C27 18,000.00 Prior Open-National INDV website and develop information strategy - FGS Security and Safeguard arrangements - FGS C28 450,000.00 Prior Open-National QCBS and 5 states C29 Water Engineer PIUs (18 month) – for 5 States 270,000.00 Prior Open-National QCBS Consultancy Services - Annual audit Services - C31 50,000.00 Prior Open-National LCS FGS Sub-total 4,932,000 Grand Total 6,738,500 5 PROCUREMENT Eastern and Southern Africa : Horn of Africa - Groundwater for Resilience Project PLAN General Information Country: Eastern and Southern Africa 2022-09-12 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174867 GPN Date: 2022-11-22 Project Name: Horn of Africa - Groundwater for Resilience Project Loan / Credit No: IDA / 70820 Water Sector Trust Fund Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-WSTF-307268-GO-RFB / S Component one: Delivery of upply and Delivery of various Single Stage - One E IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 381,000.00 0.00 Canceled 2022-08-22 2022-08-27 2022-10-08 2022-11-07 2022-12-12 2023-06-10 Groundwater management e nvelope es to priority areas quipment for Counties KE-WSTF-307271-GO-RFQ / P Component one: Delivery of Request for Quota Single Stage - One E rovision for Microsoft Office 3 IDA / 70820 inclusive groundwater servic Post Limited 30,000.00 0.00 Canceled 2022-10-12 2022-12-07 2023-02-27 tions nvelope 60 license es to priority areas KE-WSTF-307267-GO-RFB / S upply and Delivery of assorte Component one: Delivery of Single Stage - One E d office furniture and Confere IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 300,000.00 0.00 Canceled 2022-10-07 2022-10-12 2022-11-23 2022-12-23 2023-01-27 2023-03-27 nvelope nce Facilities for WSTF and th es to priority areas e 5 County Governments KE-WSTF-307242-GO-RFB / S Component one: Delivery of upply and Delivery of 7 No. P Single Stage - One E IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 620,000.00 0.00 Canceled 2022-10-07 2022-10-12 2022-11-23 2022-12-23 2023-01-27 2023-03-01 roject Vehicles for WSTF PIU nvelope es to priority areas and 5 Counties implementing the project KE-WSTF-307265-GO-RFB / S upply and Delivery of assorte Component one: Delivery of Single Stage - One E d ICT Equipment and Accesso IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 150,000.00 0.00 Canceled 2022-10-07 2022-10-12 2022-11-23 2022-12-23 2023-01-27 2023-04-03 nvelope ries (Laptops, Printers) for W es to priority areas STF and the 5 Counties KE-WSTF-307270-GO-RFQ / P Component one: Delivery of Request for Quota Single Stage - One E rovision for Auto Desk licens IDA / 70820 inclusive groundwater servic Post Limited 20,000.00 0.00 Canceled 2022-10-12 2022-12-07 2023-02-27 tions nvelope e (Civil 3D) - Multiple users es to priority areas KE-WSTF-307273-GO-RFQ / Component one: Delivery of Request for Quota Single Stage - One E Communication Equipment a IDA / 70820 inclusive groundwater servic Post Limited 40,000.00 0.00 Canceled 2022-10-12 2022-12-07 2023-02-07 tions nvelope nd Publicity for WSTF and 5 C es to priority areas ounties KE-WSTF-332744-GO-RFB / S Component one: Delivery of upply and Delivery of 7 No. P Single Stage - One E Pending Impl IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 620,000.00 0.00 2023-01-04 2023-01-09 2023-01-30 2023-02-20 2023-03-27 2023-06-25 roject Vehicles for WSTF PIU nvelope ementation es to priority areas and 5 Sub-PIUs Counties KE-WSTF-332761-GO-RFB / S Component one: Delivery of Single Stage - One E Pending Impl upply and Installation of Auto IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 20,000.00 0.00 2023-01-04 2023-01-09 2023-01-30 2023-02-20 2023-03-27 2023-06-25 nvelope ementation Desk License (Civil 3D) for M es to priority areas ultiple Users KE-WSTF-332828-GO-RFB / P Component one: Delivery of Single Stage - One E Pending Impl rovision for Microsoft Office 3 IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 30,000.00 0.00 2023-01-04 2023-01-09 2023-01-30 2023-02-20 2023-03-27 2023-05-26 nvelope ementation 60 License es to priority areas KE-WSTF-332758-GO-RFB / S Component one: Delivery of upply and Delivery of Various Single Stage - One E Pending Impl IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 381,000.00 0.00 2023-05-02 2023-05-07 2023-05-28 2023-06-18 2023-07-23 2023-10-21 Groundwater Management E nvelope ementation es to priority areas quipment for Counties KE-WSTF-332751-GO-RFB / S upply and Delivery of Assorte Component one: Delivery of Single Stage - One E Pending Impl d Office Furniture and Confer IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 300,000.00 0.00 2023-05-02 2023-05-07 2023-05-28 2023-06-18 2023-07-23 2023-10-21 nvelope ementation ence Facilities for WSTF and t es to priority areas he 5 County Governments KE-WSTF-332748-GO-RFB / S upply and Delivery of Assorte Component one: Delivery of Single Stage - One E Pending Impl d ICT Equipment and Accesso IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 170,000.00 0.00 2023-05-12 2023-05-17 2023-06-07 2023-06-28 2023-08-02 2023-10-31 nvelope ementation ries (Laptops and Printers) fo es to priority areas r WSTF and the 5 Counties KE-WSTF-332832-GO-RFB / S Component one: Delivery of upply and Delivery of Comm Request for Quota Single Stage - One E Pending Impl IDA / 70820 inclusive groundwater servic Post Limited 20,000.00 0.00 2023-06-04 2023-07-30 2023-09-28 unication and Publicity Equip tions nvelope ementation es to priority areas ment for WaterFund and 5 Su b-PIU Counties NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 KE-WSTF-307237-CS-QCBS / Component one: Delivery of Consultancy to undertake Ind Quality And Cost- Open - Internationa IDA / 70820 inclusive groundwater servic Post 800,000.00 0.00 Canceled 2023-06-22 2023-07-13 2023-08-26 2023-09-23 2023-10-23 2023-11-27 2024-01-01 2024-12-31 ependent Verification of Resu Based Selection l es to priority areas lts under the Performance-Ba sed Grant KE-WSTF-307238-CS-QCBS / Consultancy to provide TA to County Governments of Turk Component one: Delivery of Quality And Cost- Open - Internationa ana, Wajir, Garissa, Mandera, IDA / 70820 inclusive groundwater servic Post 200,000.00 0.00 Canceled 2022-08-22 2022-09-12 2022-10-26 2022-11-23 2022-12-23 2023-01-27 2023-03-03 2024-03-02 Based Selection l and Marsabit to develop Insti es to priority areas tutional Systems for sustaina ble O&M of rural Water suppl y Infrastructure KE-WSTF-307240-CS-QCBS / Consultancy for the Develop ment and Implementation Su Component one: Delivery of pport of a Web-based Inform Quality And Cost- Open - Internationa IDA / 70820 inclusive groundwater servic Post 500,000.00 0.00 Canceled 2022-08-22 2022-09-12 2022-10-26 2022-11-23 2022-12-23 2023-01-27 2023-03-03 2024-03-02 ation Management System (I Based Selection l es to priority areas MS) and Decision Support Sy stem (DSS) for the O&M of ru ral water supply systems at t he county level KE-WSTF-307241-CS-QCBS / Consultancy for TA to County Component one: Delivery of Governments for the Prepara Quality And Cost- IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2022-12-16 2023-01-06 2023-02-19 2023-03-19 2023-04-18 2023-05-23 2023-06-27 2024-06-26 tion of the County Water Sec Based Selection es to priority areas tor Drought Contingency Plan s for Turkana, Marsabit, Wajir , and Mandera counties KE-WSTF-328819-CS-QCBS / Lot 1: Implementation Suppo rt Consultancy to undertake Component one: Delivery of Feasibility studies, Detailed d Quality And Cost- Open - Internationa Under Implement IDA / 70820 inclusive groundwater servic Prior 1,200,000.00 0.00 2022-12-20 2023-04-05 2022-12-24 2023-05-18 2023-01-21 2023-02-11 2023-03-13 2023-04-10 2023-05-15 2023-07-14 esigns , preparation of ESF in Based Selection l ation es to priority areas struments and Construction Supervision of various new, R ehabilitations and Upgrading of existing groundwater infra structure KE-WSTF-328828-CS-QCBS / Component one: Delivery of Consultancy to Undertake In Quality And Cost- Open - Internationa Under Implement IDA / 70820 inclusive groundwater servic Prior 800,000.00 0.00 2023-01-04 2023-04-05 2023-01-11 2023-05-18 2023-02-22 2023-03-08 2023-03-29 2023-05-03 2023-06-07 2024-06-06 dependent Verification of Res Based Selection l ation es to priority areas ults under the Performance-B ased Grant KE-WSTF-330591-CS-QCBS / Consultancy to provide Tech nical Assistance to County G Component one: Delivery of Quality And Cost- Open - Internationa Under Implement overnments to develop Instit IDA / 70820 inclusive groundwater servic Post 200,000.00 0.00 2022-12-18 2023-04-03 2023-01-08 2023-05-11 2023-02-21 2023-03-21 2023-04-20 2023-05-25 2023-06-29 2024-06-28 Based Selection l ation utional Systems for Sustaina es to priority areas ble Operation & Maintenance of Rural Water Supply Infrast ructure KE-WSTF-330626-CS-QCBS / Consultancy for Technical As Component one: Delivery of Quality And Cost- Open - Internationa Under Implement sistance to County Governme IDA / 70820 inclusive groundwater servic Post 100,000.00 0.00 2023-01-04 2023-01-25 2023-03-10 2023-04-07 2023-05-07 2023-06-11 2023-07-16 2024-01-12 Based Selection l ation nts for the Preparation of the es to priority areas County Water Sector Drought Contingency Plans KE-WSTF-332741-CS-QCBS / Lot 2 - Implementation Supp ort Consultancy to Undertake Component one: Delivery of Feasibility Studies, Detailed Quality And Cost- Open - Internationa Under Implement IDA / 70820 inclusive groundwater servic Prior 1,800,000.00 0.00 2022-12-27 2023-04-05 2023-01-17 2023-05-18 2023-02-21 2023-03-14 2023-04-04 2023-05-09 2023-06-13 2023-12-12 Designs, Preparation of ESF I Based Selection l ation es to priority areas nstruments and Construction Supervision of various new, R ehabilitations and Upgrading of existing Groundwater Infra structure. KE-WSTF-332742-CS-QCBS / Consultancy for the Develop Component one: Delivery of ment and Implementation Su Quality And Cost- Open - Internationa Under Implement IDA / 70820 inclusive groundwater servic Prior 500,000.00 0.00 2023-01-04 2023-04-24 2023-01-25 2023-05-18 2023-03-01 2023-03-22 2023-04-12 2023-05-17 2023-06-21 2023-12-20 pport of a Web-based Inform Based Selection l ation es to priority areas ation Management System a nd Decision Support System KE-WSTF-307233-CS-QCBS / Implementation Support Con sultancy to undertake Feasibi lity studies, Detailed designs Component one: Delivery of Quality And Cost- Open - Internationa , preparation of ESF instrume IDA / 70820 inclusive groundwater servic Post 3,000,000.00 0.00 Canceled 2022-08-22 2022-09-22 2022-11-22 2022-12-20 2023-01-19 2023-02-23 2023-03-30 2024-03-29 Based Selection l nts and Construction Supervi es to priority areas sion of various new, Rehabilit ations and Upgrading of exist ing groundwater infrastructur e in the implementing INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-WSTF-307277-CS-INDV / Component one: Delivery of Individual Consult M&E Consultant to Support IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2022-08-22 2022-10-10 2022-10-31 2022-12-05 2023-06-03 ant Selection WSTF PIU es to priority areas KE-WSTF-307280-CS-INDV / Component one: Delivery of Individual Consult Procurement Specialist Supp IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2022-08-22 2022-10-10 2022-10-31 2022-12-05 2023-06-03 ant Selection ort to the Counties through es to priority areas WSTF KE-WSTF-307282-CS-INDV / Component one: Delivery of Individual Consult Environmental Safeguards C IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2022-08-22 2022-10-10 2022-10-31 2022-12-05 2023-06-03 ant Selection onsultant to Support WSTF a es to priority areas nd WRA PIUs KE-WSTF-307284-CS-INDV / Component one: Delivery of Individual Consult Consultant Project Accountan IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2022-08-22 2022-10-10 2022-10-31 2022-12-05 2023-06-03 ant Selection t for WSTF to support PBG Di es to priority areas sbursements KE-WSTF-307842-CS-INDV / Component one: Delivery of This is an Individual Consulta Individual Consult IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2027-11-19 ncy support to the PIU, mainl ant Selection es to priority areas y for administration of PBG. KE-WSTF-346281-CS-INDV / Component one: Delivery of Individual Consult Pending Impleme Monitoring and Evaluation (M IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 2023-05-12 2023-06-30 2023-07-21 2023-08-25 2025-02-15 ant Selection ntation &E) Consultant to support W es to priority areas STF PIU Page 2 KE-WSTF-346285-CS-INDV / Component one: Delivery of Individual Consult Pending Impleme Procurement specialist suppo IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 2023-05-12 2023-06-30 2023-07-21 2023-08-25 2025-02-15 ant Selection ntation rt to the 5 Counties through es to priority areas WSTF KE-WSTF-346290-CS-INDV / Component one: Delivery of Individual Consult Gender Based Violence Cons IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2023-05-12 2023-05-22 2023-06-30 2023-07-21 2023-08-25 2025-02-15 ant Selection ultant to support PIUs and SP es to priority areas IUs through WSTF KE-WSTF-363462-CS-INDV / Component one: Delivery of Individual Consult Under Implement Gender Based Violence Cons IDA / 70820 inclusive groundwater servic Post Limited 100,000.00 0.00 2023-05-31 2023-05-28 2023-06-05 2023-06-26 2023-07-31 2025-07-30 ant Selection ation ultant to support PIUs and SP es to priority areas IUs through WSTF Page 3 REPUBLIQUE DU TCHAD UNITE – TRAVAIL – PROGRES PRESIDENCE DE LA REPUBLIQUE MINISTER DE L’ELEVAGE ET DES PRODUCTIONS ANIMALES DEIRECTION GENERALE DU MINISTERE Projet Régional d’Appui au Pastoralisme au Sahel (PRAPS) Coordination Nationale PROJET DE PLAN DE PASSATION DES MARCHES (PPM) SIMPLIFIE PPA PRAPS 2 Information sur le Projet : République du Tchad Nom du Projet : Projet Régional d’Appui au Pastoralisme au Sahel (PRAPS) Tchad 2 No d’identification du projet : P173197 Agence d’exécution du Projet : Unité de Coordination du Projet (UCP). Date du plan de passation des marchés : juillet 2020 Période couverte par ce plan de passation des marchés : 12 mois Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016 révisé en septembre 2017 et août 2018 ) (“Règlement de Passation des Marchés”) le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marchés se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus de STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans le Décret No 2417/PR/PM/2015 du 17 Décembre 2015 portant Code des Marches Publics au Tchad, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : a) Les entreprises éligibles de tout pays peuvent concourir ; b) Le dossier d’appel d’offres/a propositions oblige le Soumissionnaire/Proposant présentant une Offre/Proposition à déposer un agreement signe, qui sera joint à tout contrat éventuel, pour confirmer qu’il applique et respecte les Directives de la Banque pour la lutte contre la corruption, y compris sans limitation, le droit de la Banque de sanctionner et les droits de la Banque pour l’inspection et l’audit ; c) les documents de passation des marchés contiennent des dispositions convenues avec la Banque, destinées à atténuer les risques et impacts environnementaux, sociaux (y compris l’exploitation et les abus sexuels et les violences à caractère sexiste), et sur l’hygiène et la sécurité (« ESHS ») d) Les marchés doivent comporter une répartition appropriée des attributions, risques et responsabilités ; e) La publication des informations relatives à l’attribution du marché ; f) Le droit de la Banque d’examiner le dossier et les activités de passation des marchés ; g) L’existence d’un mécanisme efficace d’examen des plaintes ; et h) La gestion et l’archivage des dossiers relatifs au Processus de passation des marchés. Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés : « Sans objet ». Achat de biens d’occasion tel que spécifié au paragraphe 5.11du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet ». Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas Travaux ne s’applique pas Autres informations pertinentes sur la passation des marchés : « Sans Objet » Les seuils pour les méthodes de passation des marchés : Les seuils de passation des marchés se présentent comme suit au vu des conditions du marché : TRAVAUX (US$ équivalent) FOURNITURES (US$ équivalent) Appel d’offres Ouvert Demand Appel d’Offres Ouvert Demande e de de Cotation Internatio Cotations International National National s nal <10.000.00 <200,000 ≥ < 100,000 ≥10,000.000 <1.000.000 0 1.000.000 Les seuils pour la revue préalable par la Banque mondiale Estimation des coûts en millions de dollars américains Type de marches Faible Modéré Substantiel Elevé Travaux 5.0 10.0 15.0 20.0 Fournitures et équipements 1.5 2.0 4.0 6.0 Consultants (firmes) 0.5 1.0 2.0 4.0 Consultant individuel 0.2 0.3 0.4 0.5 Liste des Consultations, avec les méthodes de sélection et le calendrier de mise œuvre 1 2 3 4 5 6 7 N# Descriptions des Cout Méthode Revue par Date Observations Ref activites Projet de la Banque prévue de Date de fin (US$) Sélection l’ouverture des des plis prestations Recrutement d’un consultant pour A 12/08/202 30/09/202 1 41 391 CI l’élaboration de cadre de posteriori 0 0 Gestion Environnementale Recrutement d’un consultant pour A 12/08/202 30/09/202 2 41 391 CI l’élaboration de cadre de posteriori 0 0 Gestion Sociale Recrutement d’un consultant principal pour la A 12/08/202 30/09/202 3 coordination et contrôle 41 391 CI posteriori 0 0 de qualité des instruments et la réalisation de l’ESCP 116 Recrutement d’un bureau 30/09/202 A 30/4/2021 4 pour la sélection du 16 556 SQC 030/5/202 posteriori 5562/08/2 personnel du Projet 1 020 Total III 140 729 TOTAL GENERAL 140729 Lexique des Sigles et Abréviations AOI : Appel d’Offres Ouvert International SFQC : Sélection Fondée sur la Qualité et le Coût AON : Appel d’Offres Ouvert National QC : Sélection fondée sur les Qualifications des Consultants CF : Consultation des Fournisseurs SFQ : Sélection Fondée sur la Qualité ED : Entente Directe (Gré à Gré) SMC : Sélection au Moindre Coût A posteriori : Revue à posteriori CI : Consultant Individuel A Priori : Revue à priori SED : Sélection par Entente Directe PROCUREMENT Western and Central Africa : Regional Sahel Pastoralism Support Project II PLAN General Information Country: Western and Central Africa 2021-07-16 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173197 GPN Date: 2022-02-24 Project Name: Regional Sahel Pastoralism Support Project II Loan / Credit No: IDA / V3510, IDA / D7970, IDA / D7990 Regional Sahel Pastoralism Support Project - Chad Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure TD-PRAPS-TD-291265-CW-R Project coordination, instituti ment Document - Request for Quota Single Stage - One E 2023-01-2 FQ / Extension du bureau loc IDA / D7970 onal strengthening, crisis pr Post Limited 1 Envelope proce 92,696.00 75,535.31 Completed 2022-05-30 2022-07-21 2022-07-25 2022-09-01 tions nvelope 1 ald'archivage evention and response ss (Non Bank-SPD ) Request for Bids - TD-PRAPS-TD-346838-CW-R Animal health improvement Single Stage - One E Small Works SPD Pending Imp 2024-07-2 FB / Construction de 50 parcs IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 1,086,957.00 0.00 2023-10-10 2023-10-15 2023-11-26 2023-12-26 2024-01-30 nvelope (1 envelope proce lementation 8 de vaccination trol ss) Request for Bids - TD-PRAPS-TD-346858-CW-R Animal health improvement Single Stage - One E Small Works SPD Pending Imp 2024-05-2 FB / Construction /Réhabilitat IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 478,261.00 0.00 2023-08-10 2023-08-15 2023-09-26 2023-10-26 2023-11-30 nvelope (1 envelope proce lementation 8 ion de 11 postes d'inspection trol ss) frontaliers TD-PRAPS-TD-346866-CW-R Request for Bids - Sustainable landscape mana FB / Aménagement des band Single Stage - One E Small Works SPD Pending Imp 2024-06-2 IDA / D7970 gement and governance enh Post Request for Bids Open - National 125,217.00 0.00 2023-09-05 2023-09-10 2023-10-22 2023-11-21 2023-12-26 es des par feu dans les zones nvelope (1 envelope proce lementation 3 ancement de hautes prairies d'herbes ss) Request for Bids - TD-PRAPS-TD-346869-CW-R Sustainable landscape mana Single Stage - One E Small Works SPD Pending Imp 2024-07-2 FB / Construction de 2 statio IDA / D7970 gement and governance enh Post Request for Bids Open - National 417,391.00 0.00 2023-10-05 2023-10-10 2023-11-21 2023-12-21 2024-01-25 nvelope (1 envelope proce lementation 3 ns pastorales neuves au nord ancement ss) Borkou TD-PRAPS-TD-346927-CW-R Request for Bids - Sustainable landscape mana FB / Travaux de construction Single Stage - One E Small Works SPD Pending Imp 2024-07-2 IDA / D7970 gement and governance enh Post Request for Bids Open - National 973,913.00 0.00 2023-10-05 2023-10-10 2023-11-21 2023-12-21 2024-01-25 de 7 nouveaux points d'eau e nvelope (1 envelope proce lementation 3 ancement t de réhabilitation de 7 ancie ss) ns forages TD-PRAPS-TD-346929-CW-R Request for Bids - Sustainable landscape mana FB / Aménagement et sécuris Single Stage - One E Small Works SPD Pending Imp 2024-06-0 IDA / D7970 gement and governance enh Post Request for Bids Open - National 278,261.00 0.00 2023-08-16 2023-08-21 2023-10-02 2023-11-01 2023-12-06 ation de 200km des couloirs nvelope (1 envelope proce lementation 3 ancement de transhumances des zones ss) conflictuelles. TD-PRAPS-TD-346930-CW-R Sustainable landscape mana Request for Quota FB / Travaux de couverture d Request for Quota Single Stage - One E Pending Imp 2024-05-0 IDA / D7970 gement and governance enh Post Limited tions (Non Bank-S 78,261.00 0.00 2023-09-10 2023-11-05 es bandes pare-feu dans le b tions nvelope lementation 3 ancement PD) arh-elgazel et Wadi-Fira Request for Quota TD-PRAPS-TD-346932-CW-R Project coordination, instituti Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-03-1 FQ / Réparer hangar et install IDA / D7970 onal strengthening, crisis pr Post Limited 16,522.00 0.00 2023-07-22 2023-09-16 tions nvelope s (Emergency) SP lementation 4 er la clôture locale d'archivag evention and response D -Competitive e. Request for Quota TD-PRAPS-TD-346933-CW-R Sustainable landscape mana Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-03-0 FQ / Aménagement 2 mares IDA / D7970 gement and governance enh Post Limited 86,957.00 0.00 2023-07-17 2023-09-11 tions nvelope s (Emergency) SP lementation 9 dans le hadjer-lamis et chari- ancement D -Competitive bagruimi Request for Bids - TD-PRAPS-TD-346937-CW-R Livestock value chain impro Single Stage - One E Small Works SPD Pending Imp 2024-07-0 IDA / D7970 Post Request for Bids Open - National 173,913.00 0.00 2023-09-19 2023-09-24 2023-11-05 2023-12-05 2024-01-09 FB / Construction de 2 tanner vement nvelope (1 envelope proce lementation 7 ies ss) TD-PRAPS-TD-360568-CW-R FB / Travaux de construction Request for Bids - Sustainable landscape mana de 45 ouvrages de rétention Single Stage - One E Works (without pr Pending Imp 2024-05-0 IDA / D7970 gement and governance enh Prior Request for Bids Open - National 2,426,087.00 0.00 2023-07-20 2023-07-25 2023-09-05 2023-10-05 2023-11-09 d'eau dans les provinces de l' nvelope equalification) SP lementation 7 ancement Ennedi Est , l'Ennedi Ouest et D Waddi -fira repartis en trois ( 3) lots. TD-PRAPS-TD-360572-CW-R Request for Bids - Sustainable landscape mana FB / Travaux de construction Single Stage - One E Small Works SPD Pending Imp 2024-05-1 IDA / D7970 gement and governance enh Prior Request for Bids Open - National 2,295,653.00 0.00 2023-07-25 2023-07-30 2023-09-10 2023-10-10 2023-11-14 de 33 nouveaux sites pastora nvelope (1 envelope proce lementation 2 ancement ux repartis en quatre (04) lot ss) s. TD-PRAPS-TD-360576-CW-R Request for Bids - FB / Travaux de construction Livestock value chain impro Single Stage - One E Small Works SPD Pending Imp 2024-05-2 IDA / D7970 Prior Request for Bids Open - National 5,426,087.00 0.00 2023-08-07 2023-08-12 2023-09-23 2023-10-23 2023-11-27 de 12 marché à bétail reparti vement nvelope (1 envelope proce lementation 5 s en douze lots dans 12 provi ss) nces. Request for Bids - TD-PRAPS-TD-360578-CW-R Animal health improvement Single Stage - One E Small Works SPD Pending Imp 2024-05-0 FB / Construction de 10 poste IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 347,826.00 0.00 2023-07-20 2023-07-25 2023-09-05 2023-10-05 2023-11-09 nvelope (1 envelope proce lementation 7 s vétérinaires trol ss) Request for Bids - TD-PRAPS-TD-360581-CW-R Animal health improvement Single Stage - One E Small Works SPD Pending Imp 2024-04-3 FB / Construction de 5 secteu IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 217,392.00 0.00 2023-07-13 2023-07-18 2023-08-29 2023-09-28 2023-11-02 nvelope (1 envelope proce lementation 0 rs d'élevages trol ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TD-PRAPS-TD-291178-GO-RF Project coordination, instituti Request for Quota Single Stage - One E Q / Acquisition des matériel i IDA / D7970 onal strengthening, crisis pr Post Limited 48,696.00 43,900.90 Completed 2022-06-27 2022-07-21 2022-08-22 2022-08-21 2023-02-18 2022-11-01 tions nvelope nformatiques et accessoires evention and response TD-PRAPS-TD-291180-GO-RF Animal health improvement Request for Quota Single Stage - One E Q / Acquisition des glacière e IDA / D7970 and veterinary medicine con Post Limited 52,174.00 46,068.98 Completed 2022-09-24 2022-07-15 2022-11-19 2022-08-08 2023-05-18 2023-01-08 tions nvelope t porte glace trol TD-PRAPS-TD-291181-GO-RF Animal health improvement Request for Quota Single Stage - One E Q / Acquisition des matériels IDA / D7970 and veterinary medicine con Post Limited 60,870.00 73,789.84 Completed 2022-08-30 2022-08-12 2022-10-25 2022-09-02 2023-04-23 2022-10-06 tions nvelope de bureau pour la composant trol e1 Page 1 TD-PRAPS-TD-291182-GO-RF Animal health improvement Single Stage - One E B / Acquisition des pinces po IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 104,348.00 0.00 Completed 2022-10-11 2022-07-08 2022-10-16 2022-07-21 2022-11-27 2022-08-24 2022-12-27 2022-08-26 2023-01-31 2023-07-30 2023-01-17 nvelope ur marquage des petits rumi trol nants TD-PRAPS-TD-291183-GO-RF Animal health improvement B / Acquisition des tylap (intr Single Stage - One E IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 304,635.00 0.00 Completed 2022-10-18 2022-05-18 2022-10-23 2022-05-20 2022-12-04 2022-06-20 2023-01-03 2022-06-27 2023-02-07 2023-08-06 2023-01-17 ants vétérinaires,matériels te nvelope trol chniques fiches et autres) TD-PRAPS-TD-291185-GO-RF Animal health improvement Q / Acquisition de carnet de v Request for Quota Single Stage - One E IDA / D7970 and veterinary medicine con Post Limited 26,087.00 22,539.25 Completed 2022-10-11 2022-09-05 2022-12-06 2022-09-26 2023-06-04 2022-10-12 accination et productions des tions nvelope trol rapports (carnets PPR et PPC B) TD-PRAPS-TD-291186-GO-RF Animal health improvement Request for Quota Single Stage - One E Q / Acquisition d'antiparasitai IDA / D7970 and veterinary medicine con Post Open - National 52,174.00 39,011.75 Completed 2022-09-21 2022-07-21 2022-11-16 2022-08-08 2023-05-15 2022-11-19 tions nvelope res internes (carbendazoles e trol t levamisoles) TD-PRAPS-TD-291188-GO-RF Project coordination, instituti Request for Quota Single Stage - One E Q / confection des supports e IDA / D7970 onal strengthening, crisis pr Post Limited 79,304.00 0.00 Completed 2022-06-20 2022-09-14 2022-08-15 2023-02-11 2022-12-20 tions nvelope t des visibilité evention and response TD-PRAPS-TD-291283-GO-RF Animal health improvement Request for Quota Single Stage - One E Under Imple Q / Acquisition du carburant IDA / D7970 and veterinary medicine con Post Limited 8,696.00 0.00 2022-06-20 2023-03-23 2022-08-15 2023-02-11 tions nvelope mentation du groupe électrogène de l'IR trol ED TD-PRAPS-TD-291288-GO-RF Animal health improvement Request for Quota Single Stage - One E Q / Acquisition et Maintenanc IDA / D7970 and veterinary medicine con Post Limited 8,696.00 7,604.16 Completed 2022-09-20 2022-09-05 2022-11-15 2022-09-24 2023-05-14 2022-10-12 tions nvelope e chambre froide de l'IRED trol TD-PRAPS-TD-291292-GO-RF Animal health improvement Q / Acquisition des consomm Request for Quota Single Stage - One E IDA / D7970 and veterinary medicine con Post Open - National 26,087.00 0.00 Completed 2022-08-30 2022-08-31 2022-10-25 2023-04-23 2022-10-08 ables et Réactifs pour la surv tions nvelope trol eillance et épidémiologie de maladie animale TD-PRAPS-TD-291300-GO-RF Animal health improvement Request for Quota Single Stage - One E Q / Acquisition de 200 Smart IDA / D7970 and veterinary medicine con Post Limited 60,869.00 53,604.72 Completed 2022-08-31 2022-07-15 2022-10-26 2022-08-08 2023-04-24 2022-10-21 tions nvelope phones pour la plateforme trol TD-PRAPS-TD-312637-GO-RF B / Acquisition de 3 020 000 doses de vaccins et diluants Animal health improvement Single Stage - One E contre la peste péripneumoni IDA / D7990 and veterinary medicine con Post Request for Bids Open - National 420,870.00 0.00 Completed 2022-09-15 2022-05-20 2022-09-20 2022-09-20 2022-11-01 2022-06-24 2022-12-01 2022-07-12 2023-01-05 2023-07-04 nvelope e contagieuse bovine (PPCB) trol pour la campagne de vaccina tion qui se déroulera en oct.2 022 TD-PRAPS-TD-312644-GO-RF Animal health improvement B / Acquisition de deux cent Single Stage - One E IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 217,391.00 0.00 Completed 2022-09-14 2022-05-20 2022-09-19 2022-09-14 2022-10-31 2022-06-28 2022-11-30 2022-06-28 2023-01-04 2023-07-03 cinquante (250) chaines de fr nvelope trol oids et accessoires (conainer s) TD-PRAPS-TD-312646-GO-DI Animal health improvement R / Acquisition de 7000 000 d Direct - Internation IDA / D7970 and veterinary medicine con Post Direct Selection 513,043.00 0.00 Signed 2022-09-15 2022-08-29 2022-09-20 2022-10-11 2022-10-25 2023-04-23 e doses de vaccins et diluant al trol s contre la peste de petits ru minants (PPR) . TD-PRAPS-TD-291299-GO-RF Animal health improvement Single Stage - One E B / Acquisition de 250 chaine IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 108,696.00 0.00 Canceled 2022-10-18 2022-05-20 2022-10-23 2022-05-27 2022-12-04 2023-01-03 2023-02-07 2023-08-06 nvelope s de froids et accessoires (co trol ntenair) TD-PRAPS-TD-291296-GO-RF Animal health improvement Single Stage - One E B / Acquisition de 3 020 000 IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 262,609.00 0.00 Canceled 2022-10-20 2022-05-20 2022-10-25 2022-05-24 2022-12-06 2023-01-05 2023-02-09 2023-08-08 nvelope doses de vaccins et diluants trol PPCB TD-PRAPS-TD-291179-GO-RF Animal health improvement Single Stage - One E B / Acquisition de 6 050 000 IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 473,478.00 0.00 Canceled 2022-09-20 2022-09-25 2022-11-06 2022-12-06 2023-01-10 2023-07-09 nvelope doses et diluants PPR trol TD-PRAPS-TD-291285-GO-RF Project coordination, instituti Request for Quota Single Stage - One E Q / Acquisition d'un groupe él IDA / D7970 onal strengthening, crisis pr Post Limited 26,087.00 0.00 Canceled 2022-05-30 2022-07-25 2023-01-21 tions nvelope ectrogène de l'UCP evention and response TD-PRAPS-TD-291290-GO-RF Project coordination, instituti Request for Quota Single Stage - One E Q / Acquisition des pièces de IDA / D7970 onal strengthening, crisis pr Post Limited 52,174.00 0.00 Canceled 2022-09-20 2022-07-15 2022-11-15 2023-05-14 tions nvelope rechanges evention and response TD-PRAPS-TD-291293-GO-RF Animal health improvement Q / Acquisition des réactifs et Request for Quota Single Stage - One E IDA / D7970 and veterinary medicine con Post Open - National 34,783.00 0.00 Canceled 2022-09-10 2022-11-05 2023-05-04 consommables pour le contr tions nvelope trol ôle de qualité des médicame nts vétérinaires TD-PRAPS-TD-321123-GO-RF Animal health improvement B / Acquisition des 17 Véhicul Single Stage - One E Under Imple IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 686,725.00 0.00 2022-11-28 2022-12-14 2022-12-03 2023-01-16 2023-01-14 2023-02-16 2023-02-13 2023-02-21 2023-03-20 2023-09-16 es de la composante 1 pour l nvelope mentation trol a campagne de vaccination . TD-PRAPS-TD-321130-GO-RF B / Acquisition des Matériels I Project coordination, instituti Single Stage - One E nformatiques (51ordinateurs, IDA / D7970 onal strengthening, crisis pr Post Request for Bids Open - National 202,678.00 0.00 Canceled 2022-11-23 2022-11-28 2023-01-09 2023-02-08 2023-03-15 2023-09-11 nvelope 15 imprimantes,06 Scanners, evention and response Equipements salle de réunio n +VC) TD-PRAPS-TD-346767-GO-RF Animal health improvement Single Stage - One E Pending Impl B / Acquisition de 10 véhicule IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 733,970.00 0.00 2023-05-18 2023-05-23 2023-07-04 2023-08-03 2023-09-07 2024-03-05 nvelope ementation s à quatre (4) roues et 120 M trol otos. TD-PRAPS-TD-346772-GO-RF Animal health improvement Single Stage - One E Under Imple B / Acquisition de seize (16) IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 834,783.00 0.00 2023-06-20 2023-05-22 2023-06-25 2023-05-24 2023-08-06 2023-09-05 2023-10-10 2024-04-07 nvelope mentation millions doses de vaccins +D trol iluants PPR TD-PRAPS-TD-346775-GO-RF Animal health improvement B / Acquisition de six millions Single Stage - One E Under Imple IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 879,304.00 0.00 2023-06-15 2023-05-22 2023-06-20 2023-05-24 2023-08-01 2023-08-31 2023-10-05 2024-04-02 trois cent vingt mille (6 320 nvelope mentation trol 000) doses de vaccins PPCB TD-PRAPS-TD-346779-GO-RF Animal health improvement B / Acquisition des( tylap) int Single Stage - One E Under Imple IDA / D7970 and veterinary medicine con Post Request for Bids Open - National 173,914.00 0.00 2023-06-06 2023-05-29 2023-06-11 2023-05-31 2023-07-23 2023-08-22 2023-09-26 2024-03-24 rants vétérinaires, matériels nvelope mentation trol techniques et autres Page 2 TD-PRAPS-TD-346780-GO-RF Animal health improvement Request for Quota Single Stage - One E Q / Acquisition de chaine de f IDA / D7970 and veterinary medicine con Post Limited 52,174.00 0.00 Signed 2023-05-01 2023-04-27 2023-06-26 2023-12-23 tions nvelope roid mobile (glacière et porte trol s glaces ) TD-PRAPS-TD-346784-GO-RF Animal health improvement Request for Quota Single Stage - One E Q / Acquisition des pinces de IDA / D7970 and veterinary medicine con Post Limited 34,783.00 0.00 Signed 2023-05-02 2023-04-26 2023-06-27 2023-12-24 tions nvelope marquages pour les petits ru trol minants TD-PRAPS-TD-346789-GO-RF Animal health improvement Request for Quota Single Stage - One E Q / Acquisition d'antiparasitai IDA / D7970 and veterinary medicine con Post Open - National 52,174.00 0.00 Signed 2023-05-30 2023-04-14 2023-07-25 2024-01-21 tions nvelope res internes (carbendazoles l trol evamisole) TD-PRAPS-TD-346792-GO-RF Animal health improvement Request for Quota Single Stage - One E Under Imple Q / Acquisition de carnets de IDA / D7970 and veterinary medicine con Post Limited 17,391.00 0.00 2023-05-01 2023-06-26 2023-12-23 tions nvelope mentation vaccination PPR et PPCB trol TD-PRAPS-TD-346801-GO-RF Animal health improvement Q / Acquisition des réactifs et Request for Quota Single Stage - One E Under Imple IDA / D7970 and veterinary medicine con Post Open - National 69,565.00 0.00 2023-06-20 2023-04-20 2023-08-15 2024-02-11 consommables seromonitorin tions nvelope mentation trol g PPCB et PPR TD-PRAPS-TD-346805-GO-RF Animal health improvement Q / Acquisition des réactifs e Request for Quota Single Stage - One E Pending Impl IDA / D7970 and veterinary medicine con Post Open - National 34,783.00 0.00 2023-07-30 2023-09-24 2024-03-22 t consommables pour le cont tions nvelope ementation trol rôle des médicaments vétéri naires TD-PRAPS-TD-346808-GO-RF Animal health improvement Request for Quota Single Stage - One E Pending Impl Q / Acquisition des piquets le IDA / D7970 and veterinary medicine con Post Limited 11,826.00 0.00 2023-05-20 2023-07-15 2024-01-11 tions nvelope ementation marquages du tracé des par f trol eu TD-PRAPS-TD-346813-GO-RF Animal health improvement Request for Quota Single Stage - One E Pending Impl Q / Acquisition de 22 congéla IDA / D7970 and veterinary medicine con Post Limited 72,696.00 0.00 2023-06-05 2023-07-31 2024-01-27 tions nvelope ementation teurs solaires et accessoires trol TD-PRAPS-TD-346826-GO-RF Project coordination, instituti Request for Quota Single Stage - One E Pending Impl Q / confection des supports d IDA / D7970 onal strengthening, crisis pr Post Limited 67,826.00 0.00 2023-06-20 2023-08-15 2024-02-11 tions nvelope ementation e communication et des visib evention and response ilité TD-PRAPS-TD-353995-GO-RF Animal health improvement Request for Quota Single Stage - One E Pending Impl IDA / D7970 Post Limited 8,696.00 0.00 2023-06-27 2023-08-22 2024-02-18 Q / carburant groupe électro and veterinary medicine con tions nvelope ementation gène-IRED trol NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TD-PRAPS-TD-291270-NC-RF Project coordination, instituti Request for Quota Single Stage - One E Q / Assurance maladie du per IDA / D7970 onal strengthening, crisis pr Post Limited 52,279.00 0.00 Canceled 2022-06-13 2022-07-21 2022-08-08 2023-02-04 tions nvelope sonnel du PRAPS 2 evention and response TD-PRAPS-TD-321136-GO-RF Project coordination, instituti Q / Edition et Multiplication d' Request for Quota Single Stage - One E Pending Impl IDA / D7970 onal strengthening, crisis pr Post Limited 17,391.00 0.00 2023-01-31 2023-03-28 2023-09-24 un Guide pour les interventio tions nvelope ementation evention and response ns en hydrauliques pastorale s. TD-PRAPS-TD-321139-NC-RF Project coordination, instituti Request for Quota Single Stage - One E Pending Impl Q / Titrage de 508échantion IDA / D7970 onal strengthening, crisis pr Post Limited 38,261.00 0.00 2023-02-19 2023-04-16 2023-10-13 tions nvelope ementation de vaccins. evention and response TD-PRAPS-TD-346811-NC-RF Project coordination, instituti Request for Quota Single Stage - One E Pending Impl P / Assurance maladie pour l IDA / D7970 onal strengthening, crisis pr Post Limited 52,279.00 0.00 2023-06-05 2023-07-31 2024-01-27 tions nvelope ementation e personnel du praps-2 evention and response TD-PRAPS-TD-346814-NC-RF Project coordination, instituti P / Sélection d'un garage agr Request for Quota Single Stage - One E Under Imple IDA / D7970 onal strengthening, crisis pr Post Limited 42,609.00 0.00 2023-07-05 2023-04-17 2023-08-30 2024-02-26 éée pour l'entretien et répara tions nvelope mentation evention and response tion véhicules et Motos TD-PRAPS-TD-346819-NC-RF Project coordination, instituti Q / Location de bande passa Request for Quota Single Stage - One E Under Imple IDA / D7970 onal strengthening, crisis pr Post Limited 45,217.00 0.00 2023-06-05 2023-05-17 2023-07-31 2024-01-27 nte pour la salle Multimédia ( tions nvelope mentation evention and response connectivité wifi) TD-PRAPS-TD-353991-NC-RF Animal health improvement Request for Quota Single Stage - One E Pending Impl IDA / D7970 Post Limited 8,696.00 0.00 2023-05-31 2023-07-26 2024-01-22 Q / Maintenance chambre fro and veterinary medicine con tions nvelope ementation ide -IRED trol CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TD-PRAPS-TD-224055-CS-CQ Project coordination, instituti Consultant Qualifi Open - Internationa S / Recrutement d’un bureau IDA / V3510 onal strengthening, crisis pr Post 16,556.00 14,128.88 Completed 2021-04-20 2021-07-21 2021-05-11 2021-08-03 2021-06-24 2021-09-01 2021-07-24 2021-10-05 2021-08-28 2021-09-29 2022-02-24 2022-04-27 cation Selection l pour la sélection du personn evention and response el du Projet TD-PRAPS-TD-273732-CS-LC Project coordination, instituti Least Cost Selecti Open - Internationa S / Recrutement d'un cabinet IDA / D7970 onal strengthening, crisis pr Post 21,728.00 20,585.08 Signed 2022-01-27 2022-02-07 2022-02-17 2022-02-08 2022-04-02 2022-04-08 2022-04-30 2022-05-03 2022-05-30 2022-05-12 2022-07-04 2022-06-10 2022-08-08 2022-05-25 2023-02-04 on l d'audit interne evention and response TD-PRAPS-TD-291251-CS-LC Project coordination, instituti Least Cost Selecti Open - Internationa Under Implement S / Cabinet d'audit externe p IDA / D7970 onal strengthening, crisis pr Post 15,652.00 0.00 2022-05-27 2022-05-10 2022-06-17 2022-09-26 2022-07-31 2022-12-19 2022-08-28 2023-01-24 2022-09-27 2023-03-03 2022-11-01 2023-03-27 2022-12-06 2023-06-04 on l ation our l'exercice 2022 evention and response TD-PRAPS-TD-291256-CS-QC Animal health improvement Quality And Cost- Open - Internationa Pending Impleme BS / Étude pour la constructi IDA / D7970 and veterinary medicine con Post 434,783.00 0.00 2023-01-17 2023-02-07 2023-03-23 2023-04-20 2023-05-20 2023-06-24 2023-07-29 2024-07-28 Based Selection l ntation on des ouvrages (hydrauliqu trol e et pastorale) TD-PRAPS-TD-291263-CS-CQ Animal health improvement Consultant Qualifi Open - Internationa IDA / D7970 Post 55,071.00 0.00 Canceled 2023-02-15 2023-03-08 2023-04-21 2023-05-21 2023-06-25 2023-12-22 S / Étude et contrôle des trav and veterinary medicine con cation Selection l aux trol TD-PRAPS-TD-321154-CS-CQ Project coordination, instituti S / Recrutement d'une ONG p Consultant Qualifi Under Implement IDA / D7970 onal strengthening, crisis pr Post Open - National 43,826.00 0.00 2023-01-17 2022-11-29 2023-02-07 2023-01-27 2023-03-23 2023-04-22 2023-05-27 2023-11-23 restataire locale dans les pro cation Selection ation evention and response vinces de : Ennedi Ouest et B orkou Page 3 TD-PRAPS-TD-321155-CS-CQ Project coordination, instituti S / Recrutement d'une ONG p Consultant Qualifi Under Implement IDA / D7970 onal strengthening, crisis pr Post Open - National 43,826.00 0.00 2023-01-18 2022-11-29 2023-02-08 2023-01-27 2023-03-24 2023-04-23 2023-05-28 2023-11-24 restataire locale dans les pro cation Selection ation evention and response vinces de: Guerra, Ouaddai e t Sila TD-PRAPS-TD-321156-CS-CQ Project coordination, instituti S / Recrutement d'une ONG p Consultant Qualifi Under Implement IDA / D7970 onal strengthening, crisis pr Post Open - National 43,826.00 0.00 2022-11-28 2022-11-29 2022-12-19 2023-01-27 2023-02-01 2023-03-03 2023-04-07 2023-10-04 restataire locale dans les pro cation Selection ation evention and response vinces de: Batha, Hadjer Lam is et Chari Bagruimi TD-PRAPS-TD-321157-CS-CQ Project coordination, instituti S / Recrutement d'une ONG p Consultant Qualifi Under Implement IDA / D7970 onal strengthening, crisis pr Post Open - National 43,826.00 0.00 2022-11-25 2022-11-29 2022-12-16 2023-01-27 2023-01-29 2023-02-28 2023-04-04 2023-10-01 restataire locale dans les pro cation Selection ation evention and response vinces de : Lac, Kanem et Ba hr-Elgazel TD-PRAPS-TD-321145-CS-CQ Animal health improvement S / Recrutement d'un bureau Quality And Cost- Pending Impleme IDA / D7970 and veterinary medicine con Post Open - National 434,783.00 0.00 2023-02-15 2023-03-08 2023-04-21 2023-05-19 2023-06-18 2023-07-23 2023-08-27 2024-08-26 pour les contrôles des travau Based Selection ntation trol x des infrastructures du pool 1 TD-PRAPS-TD-321148-CS-CQ Sustainable landscape mana S / Etude géophysique aux co Consultant Qualifi Open - Internationa Under Implement IDA / D7970 gement and governance enh Post 80,000.00 0.00 2023-01-25 2023-01-09 2023-02-15 2023-02-22 2023-03-31 2023-06-12 2023-04-30 2023-05-25 2023-06-04 2023-12-01 nfins Nord Batha (05 sites) et cation Selection l ation ancement Sud Borkou (05 sites) TD-PRAPS-TD-321146-CS-CQ S / Recrutement une firme po Sustainable landscape mana Quality And Cost- Pending Impleme ur les études , contrôles et la IDA / D7970 gement and governance enh Post Open - National 434,783.00 0.00 2023-02-16 2023-03-09 2023-04-22 2023-05-20 2023-06-19 2023-07-24 2023-08-28 2024-08-27 Based Selection ntation supervision des travaux des i ancement nfrastructures du pool3 TD-PRAPS-TD-346950-CS-CQ S / Cabinet pour étude de fai sabilité techniques des autre Livestock value chain impro Consultant Qualifi Open - Internationa IDA / D7970 Post 69,565.00 0.00 Under Review 2023-09-14 2023-06-12 2023-10-05 2023-11-18 2023-12-18 2024-01-22 2024-07-20 s infrastructures de la compo vement cation Selection l sante 3 (quaies d'embarque ment, tanneries, étal de bouc heries et aires de quarantain es ) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TD-PRAPS-TD-291247-CS-IN Project coordination, instituti Individual Consult Under Implement DV / Restructuration de site IDA / D7970 onal strengthening, crisis pr Post Limited 5,217.00 0.00 2022-07-19 2022-05-09 2022-07-24 2023-04-03 2022-08-14 2022-09-18 2023-03-17 ant Selection ation web PRAPS2 evention and response TD-PRAPS-TD-291249-CS-IN Project coordination, instituti Individual Consult DV / Élaboration de stratégie IDA / D7970 onal strengthening, crisis pr Post Limited 17,391.00 0.00 Signed 2022-08-24 2022-05-09 2022-08-29 2022-10-03 2022-09-19 2022-10-11 2022-10-24 2023-04-22 ant Selection de communication du PRAPS evention and response 2 TD-PRAPS-TD-291252-CS-IN DV / Étude d'évaluation du ni Livestock value chain impro Individual Consult Under Implement IDA / D7970 Post Open 20,000.00 0.00 2022-10-26 2022-05-23 2022-12-14 2022-12-09 2023-01-04 2022-12-20 2023-02-08 2023-08-07 veau d'inclusion des pasteurs vement ant Selection ation et agropasteurs dans le regis tres sociaoux. TD-PRAPS-TD-291254-CS-IN DV / Préparation plan de for Livestock value chain impro Individual Consult IDA / D7970 Post Open 25,200.00 0.00 Signed 2022-08-26 2023-03-09 2022-10-14 2022-11-04 2022-11-04 2022-11-21 2022-12-09 2023-06-07 mation professionnelle des fe vement ant Selection mmes et des jeunes issus du milieu pastoral TD-PRAPS-TD-291255-CS-IN Livestock value chain impro Individual Consult DV / Élaboration du PNS de c IDA / D7970 Post Open 20,870.00 0.00 Canceled 2022-08-24 2022-05-16 2022-10-12 2022-11-02 2022-12-07 2023-06-05 vement ant Selection ontrôle des médicaments TD-PRAPS-TD-291260-CS-IN Livestock value chain impro Individual Consult DV / Étude d'impact environn IDA / D7970 Post Open 34,783.00 0.00 Canceled 2022-09-20 2022-11-08 2022-11-29 2023-01-03 2023-07-02 vement ant Selection ementale et sociale TD-PRAPS-TD-321152-CS-IN Project coordination, instituti DV / Recrutement d'une ONG Individual Consult Under Implement IDA / D7970 onal strengthening, crisis pr Post Limited 43,826.00 0.00 2023-01-18 2022-11-29 2023-01-23 2023-02-13 2023-03-20 2023-09-16 prestataire locale dans les pr ant Selection ation evention and response ovinces de: Ennedi Est et Wa di Fira. TD-PRAPS-TD-321161-CS-IN DV / Recrutement d'un consu Project coordination, instituti Individual Consult Under Implement ltant chargé d'un guide d'inté IDA / D7970 onal strengthening, crisis pr Post Limited 27,826.00 0.00 2023-01-25 2023-03-09 2023-01-30 2023-02-20 2023-03-27 2023-09-23 ant Selection ation gration de genre VBG , la car evention and response tographie des intervenants e t acteurs VBG. TD-PRAPS-TD-321160-CS-IN DV / Recrutement d'un consu Project coordination, instituti ltant chargé de faire un diag Individual Consult Under Implement IDA / D7970 onal strengthening, crisis pr Post Limited 27,826.00 0.00 2023-01-10 2023-03-09 2023-01-15 2023-05-23 2023-02-05 2023-05-31 2023-03-12 2023-09-08 nostic genre VBG et élaborati ant Selection ation evention and response on d'une stratégie genre VBG assorti d'un plan d'action . TD-PRAPS-TD-334518-CS-IN Project coordination, instituti DV / Recrutement d'un(e) res Individual Consult Under Implement IDA / D7970 onal strengthening, crisis pr Post Open - National 25,043.00 0.00 2023-01-27 2023-01-24 2023-03-17 2023-04-07 2023-05-12 2023-11-08 ponsable administratif et fina ant Selection ation evention and response ncier (RAF) du Projet PRAPS- 2-TD. TD-PRAPS-TD-334521-CS-IN Project coordination, instituti Individual Consult Under Implement DV / Recrutement d'un (e) c IDA / D7970 onal strengthening, crisis pr Post Open - National 20,868.00 0.00 2023-01-27 2023-01-24 2023-03-17 2023-04-07 2023-05-12 2023-11-08 ant Selection ation omptable principal (e) du Pro evention and response jet PRAPS-2-TD. TD-PRAPS-TD-291231-CS-IN Social and economic inclusio Individual Consult DV / Identification des zones IDA / D7970 n improvement, women and Post Limited 6,574.00 0.00 Canceled 2022-09-16 2022-05-18 2022-09-21 2022-10-12 2022-11-16 2023-05-15 ant Selection prioritaires en besoin de form youth ation TD-PRAPS-TD-346952-CS-IN DV / audit du SIM bétail et él Livestock value chain impro Individual Consult Under Implement IDA / D7970 Post Limited 8,696.00 0.00 2023-08-16 2023-05-05 2023-08-21 2023-09-11 2023-10-16 2024-04-13 aboration d'une stratégie pér vement ant Selection ation enne pour son fonctionneme nt TD-PRAPS-TD-360584-CS-IN DV / Etude d'évaluation de la Social and economic inclusio Individual Consult durabilité et des impacts des IDA / D7970 n improvement, women and Post Limited 20,000.00 0.00 Under Review 2023-08-25 2023-06-06 2023-08-30 2023-09-20 2023-10-25 2024-04-22 ant Selection activités génératrices de rev youth enus (AGR) soutenus par le p raps-2 Page 4 TD-PRAPS-TD-360585-CS-IN Animal health improvement DV / Recrutement d'un consu Individual Consult IDA / D7970 and veterinary medicine con Post Limited 30,435.00 0.00 Under Review 2023-07-20 2023-06-22 2023-07-25 2023-08-15 2023-09-19 2024-03-17 ltant individuel chargé de for ant Selection trol mation sur le management e t communication Page 5 FINAL GEWEL PROCUREMENT PLAN Date of this revision: May 26, 2016 Zambia Girls Education and Women’s Empowerment (GEWEL) Project. (Project ID No P151451) 1. General: The project development objective (PDO) is to support the Government of Zambia to increase access to livelihood support for women and access to secondary education for disadvantaged adolescent girls in extremely poor households in selected districts. The Project consists of the following three components: Component 1. Supporting Women's Livelihoods(US$36 million) The objective of this component is to provide them with access to opportunities that will increase the productivity of their livelihood activities and their economic empowerment. Component 2. : Keeping Girls in School (US$25.78 million) The objective of this component is to support adolescent girls in extremely poor households to access secondary education. Component 3. Institutional Strengthening and Systems Building (US$3.22 million) The main objectives of this component is to strengthen institutional capacity and build systems to increase efficiency and improve coordination of targeted programs. 2. Project ID No:P151451 3. Project Implementing Agencies: Component 1: Ministry of Community Development and Social Welfare (MCDSW) Component 2: Ministry of Education, Science Vocational Training and Early Education (MGE) Component 3: Ministry of Gender (MOG); and MCDSW 4. Bank’s approval Date of the Procurement Plan: April 10, 2015 5. Date of General Procurement Notice: April, 2014, revised August 13, 2015 6. Period covered by this Procurement Plan: September 2015 to February 2017 I. Goods and Works and Non-Consulting Services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by IDA as stated in Appendix 1 to the Guidelines for Procurement: Table 1: Thresholds for Procurement Methods and Prior Review Goods, Works and Non Consultant Services Expendit Procurement Method Contract Value Contracts Subject to ure Threshold For use of Prior Review (US$) Category Method (US$) 1 1. Works ICB (Works/Supply & >=10,000,000 All contracts Installation) NCB >=200,000 - As in procurement <10,000,000 plan Shopping <200,000 None Direct Contracting All values All contracts 2. Goods ICB >=2,000,000 All contracts NCB >=100,000 <2,000,000 As in procurement plan Shopping <300,000 (motor None vehicles only) Shopping <100,000 000 (rest not None motor vehicles) Direct Contracting All values All contracts Procurement from All values None UNOPS Agency Note: Contracts with a cost estimate below US$300,000 for motor vehicles only may be procured on basis of Shopping procurement method 2. Prequalification. N/A 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines). N/A 4. Reference to (if any) Project Operational/Procurement Manual: The components will besides provisions of the Banks Guidelines for Selection and Employment of Consultants under IBRD Loans and IDA Credits & Grants by World Bank Borrowers, dated January 2011, revised April 2014 and the Banks Guidelines Procurement of Goods, works, and Non-Consulting Services under IDRD Loans and IDA Credits & Grants by World bank Borrowers, dated January 2011, revised April 2014 and will also make use of the additional information and guidance provided in Manual – Guidance for Procurement of Small Contracts; World Bank Africa Region Procurement February 2011, revised March 2014 and in the case of all contracts entered into using NCB based on use of National standard Bidding Documents, additional provisions of the attachments and standard clauses of the Bank’s Policy – Corrupt and Fraudulent Practices whose text may not be modified will be used in both the bidding documents and the ensuing contracts. 5. Any Other Special Procurement Arrangements. None 6. Procurement Packages with Methods and Time Schedule. Procurement of Good and Non Services Do Comme me nts Pre Expecte Packa sti Prior Expected Est Proc q d ge Plan/ c or Contract Descripti Amount Bid Actu Pr Post Signatur on in Metho (yes Openin Numb al ef Revie e US $ d / g er er w Date no) Date en ce 2 Component 1: Supporting Women's Livelihoods(Ministry of Community Development and Social Welfare) Printing of MCDS Plan NCB No No Post Feb April 2016 May teaching W/NCS/ 448,300 2016 require and 001 Actua to split learning l between materials MCDS Plan 1,255,000 NCB No No Prior Nov Feb 2016 Purchase W/NCS/ 2015 of motor 002 Actua vehicles l MCDS Plan Aug Aug 2016 550,000 Prior W/NCS/ Procure 2016 003 Actua ment l from UN Yes No Agenci Purchase es of motor (UNOP vehicles S) MCDS Plan NCB No No Post Nov Feb 2016 230,000 Purchase W/NCS/ 2015 of Motor 004 Actua Bikes l MCDS Plan Shoppi No No Post Nov Feb 2016 16,000 W/NCS/ ng 2015 Purchase 005 Actua of Bicycles l MCDS Plan Shoppi No No Post Nov Feb 2016 82,000 W/NCS/ ng 2015 006 Actua Purchase l of Boats Purchase MCDS Plan 100,000 Shoppi No No Post Mar Apr 2016 of Various W/NCS/ ng 2016 Office 007 Actua Furniture l and Equipment for H/Q and Districts Computers MCDS Plan March May 2016 Needed 281,300 Post , Laptops, W/NCS/ 2016 for the Scanners, 008 Actua SWL Printers, l NCB No No operatio Projectors, ns Cameras, UPS Launching Plan 535,000 Post April 2016 and Actua Equipment MCDS NCB No No l for W/NCS/ operation 009 3 of GRS Equipment MCDS Plan April June 2016 200,000 Post for ICT- W/NCS/ 2016 based 010 Actua NCB No No learning l tools Developm MCDS Plan 120,000 Post Jan 2016 June 2016 ent of W/NCS/ Actua software 011 l and database for real- time NCB No No registratio n of SWL beneficiari es and monitoring of activities. Sub Total Component 1; Goods and Non 3,817,600 Consultant Services Component 2. Keeping Girls in School (Ministry of Education, Science Vocational Training and Early Education ) Purchase MGE/G/ Plan 60,000 Shoppi No No Post Jan 2016 Feb 2016 Hand of Laptops, 01 ng held Tablets Actua devices and l for the Routers Impleme ntation of the model to capture real-time informati on in the field. IT MGE/G/ Plan 100,000 Shoppi No No Post Jan 2016 March (includin Equipment 02 ng 2016 g Actua compute l rs and other IT equipme nt) Vehicles MGE/G/ Plan Shoppi Nov Jan 2016 250,000 No No Post for 03 ng 2015 selected 4 districts Actua l Component 2. Keeping Girls in School (Ministry of Community Development ) Procureme MCDS Plan Shoppi Nov Jan 2016 37,500 No No Post nt of W/NCS/ ng 2015 Project 001 Actua Vehicle l Sub Total Component 2; Goods and Non 447,500 Consultant Services Component 3 (a): Institutional Strengthening and Systems Building: (Ministry of Gender) Setting up MOG/G Plan Shoppi No No Post Jun 2016 July 2016 IT /01 100,000 ng infrastruct Actua ure for l M&E in MOG vehicle for MOG/G Plan 50,000 Shoppi No No Post Nov Jan 2016 training, /02 ng 2015 and M&E Actua l Purchase MOG/G Plan 40,000.00 Shoppi No No Post Jun, July, 2016 of IT /03 ng 2016 Equipment Actua (Laptop l Computer, Desk top Computers , LAN, Camera, Projector and other IT Equipment s Purchase MOG/0 Plan 3,000 Shoppi No No Post Jun, July, 2016 of Office 4 ng 2016 Furniture Actua l Sub Total Component 3 A- Goods and Non 193,000 Consultant Services Component 3 (b) Institutional Strengthening and Systems: (Ministry of Community Development and Social Welfare) IT MCDS Plan 400,000 NCB No No Post Aug Dec 2015 Infrastruct W/G/01 2016 ure for Actua informatio l n systems 5 for MCDSW business at various levels Hardware MCDS Plan 150,000 NCB No No Post Nov Jan 2017 and W/G/02 2016 Software Actua for unique l identificati on solution Procureme MCDS Plan 60,000 Shoppi No No Post May June 2016 nt of W/G/03 ng 2016 devices for Actua field and l identificati on of beneficiari es Purchase MCDS Plan 100,000 Shoppi No No Post May July 2016 Goods of office W/G/04 ng 2016 for the furniture Actua National and l Social equpment Protectio n Co- ordinatio n Unit Purchase MCDS Plan 150,000 Shoppi No No Post July July 2016 For of Motor W/G/05 ng 2016 National Vehicles Actua Co- for l dination, National M&E and Social MIS. Protection Co- ordination Unit Sub Total Component 3 (b) : Goods and Non 860,000 Consultant Services Procurement of Works Sub Component 1: Supporting Women's Livelihoods(Ministry of Community Development and Social Welfare) MCDS Plan Shoppi No No Post Oct Oct 2016 45,000.00 Office W/W/0 ng 2016 refurbish 01 Actual ment Sub Component 3(b): Institutional Strengthening and Systems: (Ministry of Community Development and Social Welfare) Support to MCDS Plan 70,000 Shoppi No No Post Aug Aug 2016 office W/G/02 ng 2016 6 refurbish Actual ment Component 3 a). Institutional Strengthening and Systems: (Ministry of Gender ) Partitionin MOG/ Plan 2,000 Shoppi No No Post Sep Sep 2016 g of the W/01 ng 2016 Foyer for Actual the Conferenc e Room Sub Total: Works 127,000 II. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Table 2: Thresholds for Consultants Selection Methods and Prior Review Contract Value Contracts Subject Expenditure Procurement Threshold for use of to Prior Review Category Method selection method (US$ millions) (US$) QCBS, QBS >=200,000 All contracts Consulting As in procurement CQS, LCS, QBS, FBS <200,000 Firms plan SSS All values All Contracts Individual Competitive selection >=100,000 All contracts Consultants IC Single Source (IC) All values All contracts Selection NOTE: Contracts selected on basis of CQS should not exceed US$200,000 equivalent. Note: Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$200,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. Engineering and contract management contracts with cost estimates of less than US$300,000 may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. The procurement plan will indicate those contracts using CQS whose short lists by exception may not comprise entirely national firms. Terms of Reference (TOR) for all consultancy contracts as well as all single source selections, irrespective of the contract value, will be subject to prior review. Any Other Special Selection Arrangements: N/A 2. Consultancy Assignments with Selection Methods and Time 1 2 3 4 5 6 7 7 Expected Prior Plan Estimate proposal Selecti / Ref. / d submissio Description on Post Comments No. Actu Cost in n Method Revie al US$ /opening w Date Component 1: Supporting Women’s Livelihoods(Ministry of Community Development and Social Welfare) Adoption and Roll-out of SWL sub component 1(a) MCDSW/ Survey Plan March 937,500 C/001 Enumeration of 2016 SWL beneficiaries Actua QCBS Prior l MCDSW/ Information, Plan CQS 200,000 Post May 2016 C/002 education and communications Actua outreach at local l and national level Service provider to Plan 845,000 Jan 2016 MCDSW/ pay productivity Actua QCBS Prior C/003 grants to l beneficiaries Sub-component 1b – Building National Implementation and Monitoring Capacity MCDSW/ Plan 112,500 Prior April 2016 C/004 Hiring of SWL Actua Contract Duration IC manager l is 24 Months MCDSW/ Plan IC 97,500 Post April 2016 C/005 Hiring of SWL M&E Actua Contract Duration Specialist l is 24 Months 97,500 April 2016 MCDSW/ Plan IC 89,100 Post Nov 2015 C/006 Contract Duration M&E Officer Actua is 24 Months l 89,100 July 2016 MCDSW/ Plan IC 97,500 Post Nov 2015 C/007 Contract Duration ICT Specialist Actua is 24 Months l July 2016 MCDSW/ Plan IC 89,100 Post Nov 2015 C/008 Contract Duration ICT Officer Actua is 24 Months l 89,100 July 2016 MCDSW/ Plan IC 89,100 Post Nov 2015 C/009 Contract Duration Program Officer Actua is 24 Months 89,100 July 2016 l 8 MCDSW/ Plan IC 89,100 Post Nov 2015 C/010 Contract Duration Program Officer Actua is 24 Months l 89,100 July 2016 MCDSW/ Plan IC 89,100 Post Nov 2015 C/011 Contract Duration Program Officer Actua is 24 Months l 89,100 July 2016 MCDSW/ Plan IC 89,100 Post Nov 2015 C/012 Contract Duration Program Officer Actua is 24 Months l 89,100 July 2016 MCDSW/ Plan IC 89,100 Post Nov 2015 C/013 Contract Duration Program Officer Actua is 24 Months l 89,100 July 2016 MCDSW/ Plan IC 97,200 Post April 2016 C/014 Program Contract Duration Actua Accountant is 24 Months l 97,200 April 2016 MCDSW/ Assistant Plan IC 77,760 Post Nov 2015 C/015 Accountant Contract Duration Actua is 24 Months l 77,760 July 2016 MCDSW/ Plan Notes: assignment QBS 1,300,000 Prior May 2016 C/016 will include Actua finalizing SWL l training curriculum, design of communications strategy for Consultancy to outreach support roll out and awareness raising implementation of and support for SWL implementation of SWL activities (Short list will comprise for profit and not for profit firms i.e. Private sector and NGOs hence use of QBS) MCDSW/ Design of and Plan CQS 90,000 Post Jan 2016 C/017 operational guidelines for Actua targeting and l identification of 9 SWL beneficiaries MCDSW/ Development of Plan CQS 120,000 Post Jan 2016 C/018 strategy and tools for SWL GRS, and Actua support to launch l and operate the GRS MCDSW/ Plan IC 60,000 Post June 2016 C/019 Strategy for harmonization of Actua MCDSW l empowerment/liveli hood programs MCDSW/ Plan January Implementation QCBS 200,000 Post C/020 2017 evaluation and Actua beneficiary l satisfaction survey MCDSW/ Plan QCBS 1,030,000 Prior June 2016 C/021 Impact evaluation data collection Actua l Sub Total Component 1; Consulting 5,702,06 Services 0 Component 2. Keeping Girls in School (Ministry of Education, Science Vocational Training and Early Education ) Assessment for the Plan IC 45,000 Post Sept 2015 MGE/C/0 identification of 01 technological Actua innovations l MGE/C/0 Development of a Plan IC 50,000 Post Dec 2015 02 beneficiary awareness strategy Actua for Keeping Girls in l School MGE/C/0 Design of Plan QCBS 200,000 Prior Jan 2016 03 Complaints & Grievance Mechanism for the Actua Keeping Girls in l School Initiative MGE/C/0 Plan CQS 60,000 Post Sept 2016 04 Actua TA to harmonize existing bursary l and assessment, strategy MGE/C/0 Support to Plan CQS 51,000 Post March 05 implement the 2017 action plan to harmonize existing 10 secondary school Actua support schemes l MGE/C/0 Information System Plan QCBS 500,000 Prior February 06 Module, 2016 Development of the software to capture real time information in the field and testing of Real time Data Sub Total Component 2: Consulting Actual 906,000 Services Component 3 (a). Institutional Strengthening and Systems Building: (Ministry of Gender) MOG/C/ Development of a Plan CQS 50,000 Post Oct 2015 01 monitoring Actua framework l MOG/C/ Development of Plan CQS 100,000 Post Jun 2016 02 software for a M&E Actua and evaluation l system MOG/C/ Technical Plan CQS /IC 100,000 Post Sept 2015 Various over the 03 assistance to the life of the project. National Secretariat Actua Activity may be for project l split when defined management Sub Total Component 3(a): 250,000 Consulting Services Component 3 (b). Institutional Strengthening and Systems Building: (Ministry of Community Development and Social Welfare MCDS Development of M&E Plan CQS 150,000 Prior Aug 2015 W/C/01 framework Actua l MCDS Development of a Plan QCBS 350,000 Prior July 2016 W/C/02 MIS module for SWL and non formal Actua Literacy l MCDS Enhancement of Plan CQS 150,000 Prior Jan 2017 W/C/03 MIS/SRB Actua l MCDS Update the training Plan IC 20,000 Post March W/C/04 strategy for MCDSW 2016 staff in M&E and Actua develop a strategy l 11 for capacity development in policy analysis MCDS Updating Operations Plan CQS 100,000 Post Dec 2015 W/C/05 Manuals Actua l MCDS Assessment of Actua CQS 100,000 Post Jul 2016 W/C/06 options to l identifying Plan beneficiaries of NRCs, MCDS Inventory of existing Plan CQS 40,000 Jan 2016 W/C/07 complimentary Post activities Actua l MCDS Software design and Actua CQS 150,000 Feb March W/C/08 implementation l Post Plan MCDS TA to National Plan IC 40,000 Post Oct 2016 W/C/10 Social Protection Co- Various TA Actua ordination Unit, l MCDS Development of a Plan IC 15,000 Post Jan 2016 W/C/9 strategy for good Actua practice l Sub Total Component 3 (b): 1,115,00 Consulting Services 0 III. Training, workshops and consultations Estimated Ref. Training, workshop Estimated Expected Duration No. and study tours Cost (US$) Training/workshop (Days) Component 1: Supporting Women’s Livelihoods(Ministry of Community Development and Social We Sub-component 1a – Adoption and Roll-out of SWL MCDSW/T/01 Training of Trainers (ToT) 2,416,000 Recurrent (July 2016; Ju workshop 2017; July 2018) MCDSW/T/02 1,172,000 Recurrent (July-Feb 201 Training of beneficiaries in life, July-Feb 2017/8; July-Fe business and savings 2018/9) 12 MCDSW/T/03 Training of beneficiaries in agri- 186,000 Recurrent (Sept-Feb 20 business and other sector- Sept-Feb 2017/8; Sept-F specific topics 2018/9) MCDSW/T/04 Recurrent (September 2 Provision of safe space for September 2017; Septe training and follow-up meetings 375,000 2018) MCDSW/T/05 Launching and operation of GRS 735,000 Recurrent MCDSW/T/06 Launching and operation of ICT- Recurrent (August 2016 based learning tools 325,000 August 2017, August 20 MCDSW/T/07 Launching and Equipment for operation of GRS 100,000 MCDSW/T/08 Launching and operation of ICT- based learning tools 125,000 Sub-component 1b – Building National Implementation and Monitoring Capacity MCDSW/T/009 Workshop for preparation of the March 2016 Operations Manual 20,000 MCDSW/T/010 Training of DCD staff on POM Recurrent and training curriculum 60,000 MCDSW/T/11 Training of DCD staff on Recurrent (August 2016 beneficiary enumeration and August 2017; August 20 registration 50,000 MCDSW/T/12 Training of DCD staff on Recurrent (August 2016 monitoring and reporting 50,000 August 2017; August 20 MCDSW/T/13 Recurrent (March 2017; Annual review 30,000 2018; March 2019) MCDSW/T/14 Training of HQ and district staff Recurrent (April-August training prior to SWL activities 270,000 2017, 2018) MCDSW/T/15 Study tours to learn from international experience in the implementation of livelihood support programs 100,000 MCDSW/T/16 Capacity Building of SWL Staff in January 2017 Bank Procurement and regulations and implementation 150,000 Institutional Strengthening and Systems Building MCDSW/T/14 South-south exchange on social 35,000 May 2016 protection policy and implementation issues. Sub Total Training , Workshops and Capacity 6,199,000 Building Component 1 Supporting Women’s Livelihoods(Ministry of Community Development and Social Welfare Component 2. Keeping Girls in School (Ministry of Education, Science Vocational Training and Early Education) Sub-component 2b - System Strengthening and Consolidation Training Plan for MGE to implement the Keeping Girls in MGE /T/01 School initiative 40,000 March 2016 to May 201 13 MGE /T/02 Training of staff as per the training plan 135,000 Feb 2017 MGE /T/03 Training of the primary users of the Keeping Girls in School Information System Module 25,000 Dec 2015 MGE /T/04 Workshops and consultations for the action plan. 20,000 Feb 2017 MGE /T/05 South-south exchange on Keeping Girls in School initiative. 70,000 Dec 2016 MGE /T/06 Sharing of lessons learned between district officers 124,000 June 2016 – Sept 2020 Sub Total Training , Workshops and Capacity 414,000 Building Component 2 Subcomponent 2c: - System Strengthening for MCDSW to support Keeping Girls in School Initiativ MCDSW/T/15 Trainers of Trainers 100,000 November 2015 workshop for District Social Welfare Officers to train officers in the implementation of the Project MCDSW/T/16 Awareness raising and 25,000 November – December sensitization of Community onwards Welfare Assistance Committees (CWACs) MCDSW/T/17 Conduct inception visits to 65,000 December 2015 respective Districts and communities for programme buy-in particularly from traditional leaders, District Government officials and other stake holders. MCDSW/T/18 Hold a workshop to develop 10,000 November 2015 protocols for the implementation of the programme MCDSW/T/19 Verification of Girls on the 70,000 December 2015 list (Headcount) both in communities and villages. MCDSW/T/20 Quality Assurance, 130,000 March 2016 onwards Monitoring and mentoring of girls in school MCDSW/T/21 Follow up on girls in school 100,000 January 2016 by the CWACs, Districts, Provincial offices and Headquarters. MCDSW/T/22 Monitoring and supervision 171,250 March 2016 of follow up outcomes by the districts, provincial offices and Headquarters 14 MCDSW/T/23 Hold community validation 71,250 December 2015 meetings to provide feedback on enlisted girls Sub Total Subcomponent 2c 742,500 System Strengthening for MCDSW to support Keeping Girls in School Initiative Component 3 a). Institutional Strengthening and Systems: (Ministry of Gender ) MOG /T/01 Training of the primary users 50,000 Sept 2016 – March 2 of the monitoring and evaluation system in MOG MOG /T/02 Competency-based training 70,000 in co-ordination skills, gender analysis and gender mainstreaming June 2016 – Dec 20 MOG /T/03 Learning exchange on 70,000 empowerment programs March 2016 – May 2 MOG /T/04 Short-course local training of 4,000 staff in Project Management- 4 Staff Jan 2016 – June 20 MOG /T/05 Regional staff training in 28,000 impact evaluation • Master of Arts in Economic Policy Management – 2 Staff • Advanced M & E; Integrating Planning, Implementation, Budgeting, M&E-2 Staff • Project Management – 3 Staff Jan 2016 – Dec 20 MOG /T/06 Training of at least 10 65,000 district gender sub- committees per province in all 10 provinces in national provincial centres Jan 2016- Dec 201 MOG/T/07 Competency-based training 20,000 in Women Economic Entrepreneurship skills Nov - Dec 2016 Sub Total Training , Workshops and Capacity 327,000 Building Component 3(a) Component 3 a). Institutional Strengthening and Systems: (Ministry of Community Development ) MCDSW/T/01 Training and support for 90,000 Jun 2016 – Dec 2019 capacity development in line with training strategy for senior, middle-level and operational staff in MCDSW 15 MCDSW/T/02 Training of the primary users 10,000 May 2017 – Aug 2017 of the unique identification solution Sub Total Training , Workshops and Capacity Building Component 3(a) 100,000 GENERAL NOTES 1. Training and capacity building: The institutions charged with implementation responsibility for the componentswill identify the total cost of required training and prepare and submit to the Bank, for its prior review, a detailed training program. The training program will, inter alia, identify: (i) the training envisaged; (ii) the justification for the training, how it will lead to effective performance and implementation of the project (iii) the personnel to be trained; (iv) the selection methods of institutions or individuals conducting such training; (v) the institutions which will conduct training, if already selected; (vi) the duration of proposed training; and (vii) the cost estimate or specified cost of the training. Preparation and submission of a report, including to the Bank by the trainee upon completion of training would be mandatory. 2. Operating costs: For this project, the Bank has agreed with the implementing agencies of the various components that the procurement methods for works, goods and non-consulting services as described in the Procurement Guidelines do not have to be followed for payments made for operating costs arising from the implementation of the project. Instead, the Bank has assessed the Governments and other implementing agency own procurement and administrative procedures for these expenditures (during appraisal) and agrees that these procedures are adequate for procuring items for operating costs. The operating costs constitute recurrent costs (excluding purchase of motor vehicles, computers etc.) and typically include equipment rental and maintenance, vehicle operating costs, maintenance and repair, office rental and maintenance, office materials and supplies, utility costs (including electricity, water and gas) communications (including telephone and internet charges) equipment rent, operation and maintenance and cost of banking services (bank charges), travel cost and transport of the staff associated with project implementation. The Project Appraisal Document (PAD) and the Financing Agreement (FA) will include a list of the eligible items to be covered under the project. These items will be procured using the implementing Government agency’s administrative procedures, which have been reviewed and found acceptable to the Bank. Contracts for these items should not be included in the procurement plan. 16 PROCUREMENT Zambia : Girls Education and Womens Empowerment and Livelihood Project PLAN General Information Country: Zambia 2021-02-02 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151451 GPN Date: Project Name: Girls Education and Womens Empowerment and Livelihood Project Loan / Credit No: IDA / 65690 Ministry of Community Development and Social Services-SCT Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MCDSS/SCT/3/003/21 / Procu Request for Quota Single Stage - One E IDA / 65690 Keeping Girls in School Post Limited 82,000.00 59,559.25 Signed 2021-02-17 2021-03-25 2021-04-14 2021-05-13 2021-10-11 rement of Money Safes for th tions nvelope e Districts MCDSS/SCT/004/4/21 / Procu Request for Quota Single Stage - One E rement of 36 Executive Table IDA / 65690 Keeping Girls in School Post Limited 70,000.00 89,465.05 Completed 2021-02-24 2021-03-25 2021-04-21 2021-04-29 2021-10-18 2021-05-12 tions nvelope s and Chairs, 50 Filling cabin ets MCDSS/SCT/008/21 / Procure ment and supply of Navision Request for Quota Single Stage - One E IDA / 65690 Keeping Girls in School Post Limited 95,000.00 124,542.28 Signed 2021-03-03 2021-03-30 2021-04-28 2021-06-22 2021-10-25 User Licenses, Visual Private tions nvelope Network and Operating softw are MCDSS/SCT/007/7/21 / Procu Single Stage - One E rement of 45 Motor Bikes for IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 280,000.00 356,538.64 Signed 2021-02-28 2021-03-19 2021-03-05 2021-04-16 2021-04-16 2021-05-16 2021-07-23 2021-06-20 2021-12-08 2021-12-17 nvelope the SCT Districts MCDSS/SCT/006/21 / Procure Single Stage - One E ment of 5000 Bicycles for the IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 554,585.00 754,120.87 Signed 2021-02-26 2021-04-08 2021-03-03 2021-04-14 2021-05-07 2021-05-14 2021-06-23 2021-06-18 2021-08-06 2021-12-15 nvelope SCT Districts MCDSS/SCT/005/5/21 / Procu Single Stage - One E IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 150,000.00 0.00 Canceled 2021-02-26 2021-03-03 2021-04-14 2021-05-14 2021-06-18 2021-12-15 rement of 2 Boats for SCT nvelope MCDSS/SCT/010 / Procureme Single Stage - One E nt of 120 Desktop Computers IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 185,000.00 254,212.61 Completed 2021-02-26 2021-04-09 2021-03-03 2021-04-14 2021-05-14 2021-05-14 2021-06-11 2021-06-18 2021-08-11 2021-12-15 2021-11-05 nvelope and 35 Laptops MCDSS/SCT/014/21 / Procure Request for Quota Single Stage - One E IDA / 65690 Keeping Girls in School Post Limited 43,000.00 76,654.06 Completed 2021-04-05 2021-04-01 2021-05-31 2021-05-13 2021-11-27 2021-05-22 ment of various COVID 19 Ma tions nvelope terials MCDSS/SCT/012/21 / Procure Request for Quota Single Stage - One E IDA / 65690 Keeping Girls in School Post Limited 140,600.00 189,947.77 Completed 2021-04-21 2021-04-02 2021-06-16 2021-04-16 2021-12-13 2021-04-16 ment of 1,300 smart mobile tions nvelope phones MCDSS/SCT/016/2021 / Proc Single Stage - One E urement of 15 4 x 4 Double C IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 735,000.00 879,170.47 Signed 2021-05-14 2021-05-20 2021-05-19 2021-06-30 2021-06-18 2021-07-30 2021-07-15 2021-09-03 2021-08-12 2022-03-02 nvelope ab Motor Vehicles MCDSS/SCT/017/21 / Procure Request for Quota Single Stage - One E IDA / 65690 Keeping Girls in School Post Limited 71,000.00 94,890.51 Completed 2021-05-12 2021-04-21 2021-07-07 2021-05-12 2022-01-03 2021-05-13 ment of 1,300 Power Banks tions nvelope MCDSS/SCT/018/21 / Procure Request for Quota Single Stage - One E ment of solar power batteries IDA / 65690 Keeping Girls in School Post Limited 30,000.00 80,637.00 Signed 2021-05-19 2020-05-18 2021-07-14 2021-01-07 2022-01-10 tions nvelope and charger controllers MCDSS/SCT/013/21 / Procure Single Stage - One E ment of 5700 mobile smart p IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 900,000.00 920,552.14 Signed 2021-04-09 2021-04-08 2021-04-14 2021-05-26 2021-05-14 2021-06-25 2021-06-10 2021-07-30 2021-08-11 2022-01-26 2021-10-29 nvelope hones and power banks for S CT MCDSS/SCT/019/21 / Procure Request for Quota Single Stage - One E IDA / 65690 Keeping Girls in School Post Limited 85,000.00 89,886.71 Completed 2021-06-02 2021-08-23 2021-07-28 2021-10-15 2022-01-24 2021-12-15 ment of aluminum partitionin tions nvelope g MCDSS/SCT/022/21 / Supply Request for Quota Single Stage - One E IDA / 65690 Keeping Girls in School Post Limited 70,000.00 134,721.25 Completed 2021-06-16 2021-05-28 2021-08-11 2021-07-09 2022-02-07 2021-09-21 and Delivery of Servers tions nvelope MCDSS/SCT/025/21 / Procure Request for Quota Single Stage - One E ment of Various Office equip IDA / 65690 Keeping Girls in School Post Limited 77,550.00 59,515.36 Completed 2021-09-01 2021-08-23 2021-10-27 2021-11-17 2022-04-25 2021-11-27 tions nvelope ment for the SCT PIU MCDSS/SCT/027/21 / Procure Request for Quota Single Stage - One E IDA / 65690 Keeping Girls in School Post Limited 95,500.00 58,840.58 Signed 2021-09-22 2021-11-11 2021-11-17 2022-01-05 2022-05-16 ment of T Shirts for the CWA tions nvelope S MCDSS/SCT/024/21 / Procure Request for Quota Single Stage - One E ment of Electrical accessorie IDA / 65690 Keeping Girls in School Post Limited 43,000.00 0.00 Canceled 2021-09-22 2021-11-17 2022-05-16 tions nvelope s for the new SCT PIU offices MCDSS/SCT/026/21 / Procure Request for Quota Single Stage - One E Under Imple IDA / 65690 Keeping Girls in School Post Limited 84,500.00 0.00 2021-09-22 2022-10-11 2021-11-17 2022-05-16 ment of 46,000 for CWACs b tions nvelope mentation adges MCDSS/SCT/028/21 / Procure Request for Quota Single Stage - One E Under Imple ment of five (5) Printers and IDA / 65690 Keeping Girls in School Post Limited 26,000.00 0.00 2021-11-03 2021-10-11 2021-12-29 2022-06-27 tions nvelope mentation sixteen LAN Land Phones for the SCT MCDSS/SCT/031/21 / Procure Request for Quota Single Stage - One E Under Imple ment of Power Back up Soluti IDA / 65690 Keeping Girls in School Post Open - National 18,000.00 0.00 2022-01-04 2022-03-01 2022-08-28 tions nvelope mentation ons for the ZISPIS Servers MCDSS/SCT/032/21 / Procure Request for Quota Single Stage - One E Under Imple ment of 120 Microsoft Office IDA / 65690 Keeping Girls in School Post Open - National 78,000.00 0.00 2022-01-04 2022-03-01 2022-08-28 tions nvelope mentation 2019 Licences 120 Internet ant virus Page 1 MCDSS/SCT/001/22 / Procure Request for Quota Single Stage - One E Pending Impl IDA / 65690 Keeping Girls in School Post Limited 83,000.00 0.00 2022-04-20 2022-06-15 2022-12-12 ment of COVID 19 materials f tions nvelope ementation or the SCT MCDSS/SCT/OO3/22 / Procur Request for Quota Single Stage - One E Under Imple ement of Microsoft Dynamics IDA / 65690 Keeping Girls in School Post Limited 99,000.00 0.00 2022-04-25 2022-04-04 2022-06-20 2022-12-17 tions nvelope mentation (40) Licenses MCDSS/SCT/004/22 / Procure ment of photocopiers, multif Single Stage - One E Pending Impl unctional printers, laptop co IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 365,000.00 0.00 2022-04-20 2022-04-25 2022-06-06 2022-07-06 2022-08-10 2023-02-06 nvelope ementation mputers, projectors , desktop computers and external hard drives MCDSS/SCT/006/22 / Procure Request for Quota Single Stage - One E Under Imple IDA / 65690 Keeping Girls in School Post Limited 94,117.65 0.00 2022-04-20 2022-04-04 2022-06-15 2022-12-12 ment of 100 air conditioners tions nvelope mentation for SCT MCDSS/SCT/007/22 / Procure Request for Quota Single Stage - One E IDA / 65690 Keeping Girls in School Post Limited 44,000.00 0.00 Completed 2022-04-20 2022-04-04 2022-06-15 2022-12-12 2022-07-31 ment of office furniture for S tions nvelope CT MCDSS/SCT/008/22 / Procure Single Stage - One E Under Imple ment of Six (6) double cab an IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 322,000.00 0.00 2022-04-20 2022-05-16 2022-04-25 2023-04-20 2022-06-06 2022-06-23 2022-07-06 2022-08-10 2023-02-06 nvelope mentation d One (1) station wagon Mot or vehicles MCDSS/SCT/009/22 / Procure Single Stage - One E Under Imple IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 1,475,858.82 0.00 2022-04-20 2022-05-18 2022-04-25 2023-02-26 2022-06-06 2022-06-23 2022-07-06 2022-11-18 2022-08-10 2023-02-06 ment of 10,000 bicycles for S nvelope mentation CT MCDSS/SCT/005/22 / Procure ment of four (4) multi –fiber o ptic CISCO 10GB SR SFP, one Request for Quota Single Stage - One E Under Imple IDA / 65690 Keeping Girls in School Post Limited 48,000.00 0.00 2022-08-03 2022-07-08 2022-09-28 2023-03-27 (1) CISCO 10 GB 48 Port swit tions nvelope mentation ch SFP and three (3) HPE AJ6 4-630028Q2X8GB Fibre shirt wave LC multi dual port PCI E xpress MCDSS/SCT/033/21 / Procure ment of Back Up Firewall for Request for Quota Single Stage - One E Under Imple the installed Servers, 5 Zoom IDA / 65690 Keeping Girls in School Post Open - National 97,000.00 0.00 2022-08-03 2022-09-28 2023-03-27 tions nvelope mentation Business Software Licences a nd 120 pieces Foxit PDF Rea der MCDSS/SCT/010/22 / Procure Request for Quota Single Stage - One E Pending Impl ment of 50,000 Badges for C IDA / 65690 Keeping Girls in School Post Limited 98,000.00 0.00 2022-12-25 2023-02-19 2023-08-18 tions nvelope ementation WAC Members in the District s MCDSS/SCT/011/22 / Procure Single Stage - One E Pending Impl ment of 3,000 Mobile Smart IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 416,666.67 0.00 2022-12-23 2022-12-28 2023-02-08 2023-03-10 2023-04-14 2023-10-11 nvelope ementation Phones for pay point manage rs MCDSS/013/22 / Procuremen Request for Quota Single Stage - One E Pending Impl t of 1,600 Rain suits and 1,60 IDA / 65690 Keeping Girls in School Post Limited 48,539.00 0.00 2023-01-25 2023-03-22 2023-09-18 tions nvelope ementation 0 gum boots for the districts MCDSS/SCT/004/2/23 / Procu Single Stage - One E Pending Impl rement of additional Mobile S IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 497,560.98 0.00 2023-03-30 2023-04-04 2023-05-16 2023-06-15 2023-07-20 2024-01-16 nvelope ementation mart Phones for PayPoint ma nagers MCDSS/SCT/003/23 / Procure Request for Quota Single Stage - One E Under Imple IDA / 65690 Keeping Girls in School Post Limited 94,000.00 0.00 2023-04-05 2023-03-22 2023-05-31 2023-11-27 ment of annual Navision Lice tions nvelope mentation nces MCDSS/SCT/005/23 / Procure Request for Quota Single Stage - One E Pending Impl ment of Branded T- Shirts for IDA / 65690 Keeping Girls in School Post Limited 92,745.00 0.00 2023-05-23 2023-07-18 2024-01-14 tions nvelope ementation CWACs in the SCT implement ing Districts MCDSS/SCT/009/23 / Procure ment of 100 Executive Table Single Stage - One E Pending Impl IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 200,000.00 0.00 2023-05-31 2023-06-05 2023-07-17 2023-08-16 2023-09-20 2024-03-18 s, 100 Executive Chairs, 100 nvelope ementation Visitors Chairs and 100 Filing Cabinets MCDSS/SCT/011/23 / Procure Request for Quota Single Stage - One E Pending Impl ment of 1,500 Chronically for IDA / 65690 Keeping Girls in School Post Limited 61,800.00 0.00 2023-05-30 2023-07-25 2024-01-21 tions nvelope ementation ms and 1,500 Disability form s. MCDSS/SCT/013/23 / Procure ment of 40 Desktop Compute Single Stage - One E Pending Impl IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 200,000.00 0.00 2023-06-01 2023-06-06 2023-07-18 2023-08-17 2023-09-21 2024-03-19 rs nvelope ementation Procurement of 40 Laptops Procurement of 200 tablets MCDSS/SCT/015/23 / Procure Request for Quota Single Stage - One E Pending Impl IDA / 65690 Keeping Girls in School Post Limited 48,750.00 0.00 2023-07-01 2023-08-26 2024-02-22 ment of 65 Safes for the Dist tions nvelope ementation ricts MCDSS/SCT/016/23 / Procure Single Stage - One E Pending Impl ment of 6,400 Power Banks f IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 208,000.00 0.00 2023-06-26 2023-07-01 2023-08-12 2023-09-11 2023-10-16 2024-04-13 nvelope ementation or the Districts NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MCDSS/SCT/009/21 / Networ Request for Quota Single Stage - One E IDA / 65690 Keeping Girls in School Post Limited 20,000.00 56,494.24 Completed 2021-03-03 2021-05-18 2021-04-28 2021-06-17 2021-10-25 2021-06-22 king of SCT Offices tions nvelope MCDSS/SCT/002/21 / Tender for the engagement of Mobil IDA / 65690 Keeping Girls in School Post Direct Selection Direct 288,654.55 359,784.67 Signed 2021-03-26 2021-03-29 2021-03-31 2021-04-07 2021-05-05 2021-12-11 2021-11-01 e Network Operators (MNOs) for the payment of beneficiar ies MCDSS/SCT/011/21 / Tender for the engagement of banks IDA / 65690 Keeping Girls in School Post Direct Selection Direct 96,218.18 120,642.92 Signed 2021-03-26 2021-03-29 2021-03-31 2021-04-07 2021-05-05 2021-09-07 2021-11-01 for the payment of Social Cas h Grants MCDSS/SCT/015/21 / Printin Request for Quota Single Stage - One E g of Disability Certification an IDA / 65690 Keeping Girls in School Post Limited 13,000.00 16,934.31 Completed 2021-05-19 2021-04-21 2021-07-14 2021-05-12 2022-01-10 2021-05-14 tions nvelope d chronic illness books MCDSS/SCT/030/21 / Printin Supporting Women's Livelih Request for Quota Single Stage - One E g of Additional Disability Cert IDA / 65690 Post Limited 30,000.00 0.00 Completed 2021-11-24 2021-11-10 2022-01-19 2022-07-18 2022-03-04 oods tions nvelope ification and Chronic Illness F orms Page 2 MCDSS/SCT/C/16/22 / Tende r for the engagement of pay Single Stage - One E Pending Impl IDA / 65690 Keeping Girls in School Post Request for Bids Open - National 200,000.00 0.00 2022-12-02 2022-12-07 2023-01-18 2023-02-17 2023-03-24 2023-09-20 ment service providers for th nvelope ementation e Social Cash Transfer (SCT) beneficiaries CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MCDSS/SCT/023/21 / Consult ancy Services for the Impact Quality And Cost- Open - Internationa Under Implement IDA / 65690 Keeping Girls in School Prior 2,000,000.00 0.00 2021-06-01 2021-06-04 2021-06-22 2021-06-18 2021-08-05 2021-11-04 2021-09-02 2021-12-24 2021-10-02 2022-01-25 2021-11-06 2022-02-22 2021-12-11 2022-12-11 Evaluation for the Social Cas Based Selection l ation h Transfer (SCT) program MCDSS/SCT/C/001/2/22 / Co Consultant Qualifi Pending Impleme nsultancy for the conducting IDA / 65690 Keeping Girls in School Post Open - National 300,000.00 0.00 2022-05-10 2022-05-31 2022-07-14 2022-08-13 2022-09-17 2023-03-16 cation Selection ntation of external Monitoring and Ev aluation MCDSS/SCT/C/017/22 / Back stopping and live operations Consultant Qualifi Pending Impleme IDA / 65690 Keeping Girls in School Post Open - National 98,000.00 0.00 2022-12-20 2023-01-10 2023-02-23 2023-03-25 2023-04-29 2023-10-26 technical assistance in 116 di cation Selection ntation stricts for Navision INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MCDSS/SCT/C/001/21 / Cons Individual Consult ultancy services for capacity IDA / 65690 Keeping Girls in School Post Limited 150,000.00 0.00 Canceled 2021-02-26 2021-03-03 2021-03-24 2021-04-28 2021-10-25 ant Selection building in financial manage ment MCDSS/SCT/021/21 / Consult ancy services for the engage Individual Consult Under Implement IDA / 65690 Keeping Girls in School Post Open 64,800.00 0.00 2021-05-28 2021-04-30 2021-07-16 2021-08-06 2021-09-10 2022-03-09 ment of a Management and I ant Selection ation mplementation Officer MCDSS/SCT/020/21 / Consult Individual Consult Under Implement ancy services for the engage IDA / 65690 Keeping Girls in School Post Open 78,000.00 0.00 2021-11-12 2021-11-10 2021-12-31 2022-01-21 2022-02-25 2022-08-24 ant Selection ation ment of a Payment Specialist MCDSS/SCT/029/21 / Consult ancy Services for the engage Individual Consult Under Implement IDA / 65690 Keeping Girls in School Post Open 78,000.00 0.00 2021-11-19 2021-11-10 2022-01-07 2022-01-28 2022-03-04 2022-08-31 ment of a Monitoring and Eva ant Selection ation luation (M&E) Specialist MCDSS/SCT/012/22 / Consult Individual Consult ancy services for THE engag IDA / 65690 Keeping Girls in School Post Direct 7,400.00 0.00 Canceled 2022-05-31 2022-06-10 2022-07-01 2022-08-05 2023-02-01 ant Selection ement of MIS Specialist for T wo year Contract MCDSS/SCT/C/012/22 / Enga Individual Consult Under Implement gement of the MIS Specialist IDA / 65690 Keeping Girls in School Post Direct - National 78,000.00 0.00 2023-01-02 2023-04-12 2023-01-12 2023-02-02 2023-03-09 2023-09-05 ant Selection ation for two years Contract. MCDSS/SCT/C/018/22 / Cons ultancy services for the enga Individual Consult Pending Impleme IDA / 65690 Keeping Girls in School Post Open - National 78,000.00 0.00 2023-01-20 2023-03-10 2023-03-31 2023-05-05 2023-11-01 gement of Grievance Redres ant Selection ntation s Mechanism / GBV Specialist for two years. Page 3 PROCUREMENT PLAN Version 1.8 – Date: February 16, 2022 INSTITUTIONAL STRENGTHENING FOR IMPROVED VILLAGE SERVICE DELIVERY PROJECT A. Project information: Country: Indonesia Borrower: Republic of Indonesia Project ID: P165543 Financing Agreement IBRD Loan 8941-ID Number: Project Implementation Agency(ies): CPMU: Ministry of Home Affairs (MOHA), Directorate General of Village Government Affairs CPIU: Ministry of Home Affairs (MOHA), Directorate General of Village Government Affairs Ministry of Villages, Directorate General of Village Development and Community Empowerment (PPMD) Ministry of National Development Planning/BAPPENAS, Deputy for Regional Development Directorate for the Development of Disadvantaged Regions, Transmigration and Rural Areas Coordinating Ministry of Human Development and Cultural Affairs (PMK), Deputy for Community Empowerment, Village and Regions B. Key Dates: 1. Procurement Plan: a. Version 1.0 (for Feb 28, 2019 negotiation) Bank’s Approval to this Mar 12, 2019 version: Period covered by this Apr 1, 2019 – December 31, version: 2020 b. Version 1.7 (previous June 17, 2021 version) Bank’s Approval to this June 21, 2021 version: Period covered by this Apr 1, 2019 – December 31, version: 2023 c. Version 1.8 (this version) Feb 16, 2022 Bank’s Approval to this Feb 21, 2022 version: Period covered by this Apr 1, 2019 – December 31, version: 2023 d. [next version, if any] [to be updated] 2. General Procurement Mar 26, 2020 Notice: C. Preamble All Procurement under the Project shall be carried out in accordance with the World Bank’s Procurement Regulations for IPF Borrowers of July 2016, revised November 2017 and August 2018, and the provisions of the Procurement Plan and Project Operations Manual and shall take precedence over any national procurement regulations. In accordance with paragraph 5.9 of the Procurement Regulations, the Bank’s online procurement planning and tracking tools i.e. Systematic Tracking and Exchanges in Procurement (STEP) will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. D. Key Provisions The following conditions apply to all procurement activities in this Procurement Plan. The Bank’s procurement prior review thresholds: The identified procurement risk under this Project is ‘Substantial’. Accordingly, all contracts listed in the Procurement Plan that are at or above the thresholds set out below are subject to the Bank’s prior review. All other contracts are subject to the Bank’s ex-post review. Table 1. Applied Prior Review Threshold Type of procurement Procurement Prior Review Thresholds (US$ millions) Works (including turnkey, supply & installation of 10 plant and equipment, and PPP) Goods, Information Technology and Non- 2 consulting Services Consultants: Firms 1 Consultants: Individuals 0.3 The Bank’s approved selection methods thresholds: The following selection method thresholds shall apply for procurement of goods & information technology, non-consulting services and consulting services of each identified activity. Table 2. Applied Approved Selection Method Threshold Type of procurement and Approved Selection Method Thresholds Approved Selection (US$ millions) Method National International Works (including turnkey, supply & installation of plant and equipment, and PPP) (i) Request for Request for at or above $0.2 and at or above $25 Bids (RFB) less than $25 (ii) Request for Quotations less than $0.2 N/A (RFQ) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 6.8, 6.9 paragraph 6.8, 6.9 and 6.10 of the and 6.10 of the Procurement Procurement Regulations Regulations Type of procurement and Approved Selection Method Thresholds Approved Selection (US$ millions) Method National International Goods, Information Technology and Non-consulting services a. For Goods and Information Technology: (i) Request for Request for at or above $0.1 and at or above $2 Bids (RFB) less than $2 (ii) Request for Quotations less than $0.1 N/A (RFQ) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 6.8, 6.9 paragraph 6.8, 6.9 and 6.10 of the and 6.10 of the Procurement Procurement Regulations Regulations b. For Non-consulting Services: (i) Request for Request for at or above $0.1 and at or above $10 Bids (RFB) less than $10 (ii) Request for Quotations less than $0.1 N/A (RFQ) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 6.8, 6.9 paragraph 6.8, 6.9 and 6.10 of the and 6.10 of the Procurement Procurement Regulations Regulations Consultants: firms a. For Selection of Consulting Firms (i) Quality Cost Based Shortlist of firms for at or above $0.4 Selection (QCBS), Fixed contracts below $0.4 Budget Based Selection may comprise (FBS), Least Cost Based entirely national Selection (LCS) and firms Quality Based Selection (QBS) (ii) Consultant’s less than $0.3 N/A Qualifications Based Selection (CQS) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per Type of procurement and Approved Selection Method Thresholds Approved Selection (US$ millions) Method National International paragraph 7.13, 7.14 paragraph 7.13, 7.14 and 7.15 of the and 7.15 of the Procurement Procurement Regulations Regulations b. For Selection of Individual Consultants (i) Open Competitive All, no monetary All, no monetary Selection of Individual threshold threshold Consultants and Limited Competitive Selection of Individual Consultants (ii) Direct Selection of On exceptional basis On exceptional basis Individual Consultants if justified as per if justified as per paragraph 7.39 of paragraph 7.39 of the Procurement the Procurement Regulations Regulations Standard Procurement Documents (SPD): The Bank’s SPD shall be used when approaching the international market (specifically for international competitive procurement and those contracts shall be as specified in the Procurement Plan tables in STEP. Use of National Procurement Procedures: In accordance with paragraphs 5.3 of the Procurement Regulations, when approaching the national market all contracts to be procured through open national competitive procurement will follow the GoI’s procurement regulation. The procedures applicable to the procurement of goods and non-consulting services awarded on the basis of open national competitive procurement shall be those of the Tender method as set forth in the Peraturan Presiden No. 16/2018 and its subsequent amendment Peraturan Presiden No. 12/2021) provided that such arrangements continue to meet requirements set forth under paragraph 5.4 of these Regulations and the following conditions: 1. The procurement is open to eligible firms from any country. There shall not any restriction to the bidders’ participation including mandatory requirement to form in joint venture; 2. Any gaps between National Procurement Procedures and the Procurement Regulations will be addressed and incorporated in the harmonized bidding documents acceptable by the Bank. Use of National e-Procurement System (SPSE): Unless informed otherwise by the Bank in writing, SPSE e-procurement system may be used only for procurement of works, goods and non-consulting services under Request for Bids (RFB) method through national open competitive procurement method, applying the harmonized model bidding documents for national open competitive procurement agreed by the Bank. For selection of consulting services through QCBS method, only the modified SPSE (termed by LKPP as SPSE-“ICB”) may be used applying the Bank’s Standard Request for Proposal (RFP) document. The Bank has further accepted GOI’s proposal for use of SPSE-ICB for selection of consulting services through CQS method applying a modified Bank’s Standard RFP. Two consulting services activities (contracts) under other Bank-financed project are being performed as pilot use of SPSE-ICB for CQS method to ensure that the system is working as intended. Since at the present time LKPP has not yet developed the modified SPSE for procurement of goods, works and non-consulting services under international open Competitive method, nor for selection of consulting services under QBS, LCS, FBS, and individual consultant selection methods, therefore procurement of all contract packages under these methods shall be carried out through non- electronic process with manual issuance of specific procurement notice (request for expression of interest or invitation for bids/proposals and receipt of bids/proposals), until such time that the modified SPSE has been completed by LKPP and assessed by the Bank to be acceptable. If the Bank determines the modified SPSE to be acceptable for use under the above- mentioned remaining procurement methods, the Bank will confirm through the Bank’s written no objection to LKPP and will also notify in writing to CMPU/CPIUs. Use of National e-Catalogue System. Based on the Bank’s assessment of the national e-catalogue system, the Bank allows the Project Implementing Units (PIUs) under World Bank financed projects to use the national e- catalogue for procurement of small value of goods in lieu of the Request for Quotations (RFQ) method specified in these Regulations within the parameters as below: a) For Goods (other than medicines) with estimated cost not more than USD 15,000 equivalent per contract. PIUs may use the national e-catalogue for procuring such items of goods within the above-specified threshold, if such goods are required under the project and specified in the Procurement Plan approved by the Bank. b) Goods (other than medicines) with estimated cost greater than USD 15,000 but less than USD 100,000 equivalent per contract. PIUs may use the national e-catalogue for procuring such items of goods if such goods are required under the project subject to fulfilling the following additional procedural requirement as below: PIU shall carry out a secondary procurement process through mini competition, by comparing the prices of similar goods offered by at least three different suppliers which available in the national e-catalogue and then selecting the Supplier with the lowest evaluated price on the basis of “as delivered" price at final destination (i.e., including inland transportation, insurance, applicable taxes and any other incidental charges for the delivery of the required quantity of goods at final destination). E. Other Relevant Procurement Information • Project Operations Manual (POM) shall set out the operating procedures for procurement and contract implementation matters under the Project written in Bahasa, which shall be consistent with the procedures and rules specified under the Bank’s Procurement Regulations. In case of any difference of interpretation between the POM and the Bank’s Procurement Regulations, the later shall prevail; • CPMU and CPIUs may use its own forms of contract for goods/non- consulting services procured under Request for Quotations (RFQ) method when approaching to national market, acceptable to the Bank; • Advance procurement may be applied under the project and shall be valid by signing of the Loan Agreement. CPMU and CPIUs may commence the procurement process prior to issuance of the DIPA for any anticipated activity to be procured under the Project, while signing of the contract shall be subject to issuance of the DIPA of the respective activity. All contracts shall not be designed as single-year contract, and therefore procurement process shall continue throughout multiple calendar years without limitation of contract period up to end of the GoI’s fiscal year; • Regardless of the Bank’s review requirement (prior or post), the Bank may review technical aspects of procurement documents and other non- procurement matters (terms of reference, statement of works, technical specifications, environmental documents, cost estimate, etc.) related to the procurement activity in question, if needed; • The Bank will continue to provide guidance and support to the CPMUs, and CPIUs for procurement processing through the STEP. • Project Implementation Support Personnel as defined in the PPSD shall not be included in this Procurement Plan. Their selection and hiring procedures shall continue to apply the GoI’s selection and hiring procedures as further defined in the POM. The Procurement Plan is a living document and can be revised if there are any changes during the implementation of the project. PROCUREMENT Indonesia : Institutional Strengthening for Improved Village Service Delivery PLAN General Information Country: Indonesia 2020-05-07 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P165543 GPN Date: 2020-03-26 Project Name: Institutional Strengthening for Improved Village Service Delivery Loan / Credit No: IBRD / 89410 DG PPMD, KEMENDES Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-PPMD-190471-GO-RFB / P engadaan Server Storage da Promoting Participatory Villa Single Stage - One E n Virtualisasi, Firewall, Link C IBRD / 89410 Post Request for Bids Open - National 1,033,000.00 973,400.83 Completed 2020-09-01 2020-09-21 2020-09-04 2020-09-25 2020-10-13 2020-10-02 2020-10-16 2020-10-14 2020-11-07 2020-12-28 2020-12-24 ge Development nvelope ontroller, DNS Server serta R evitalisasi Jaringan Campus L AN Gedung Utama ID-PPMD-190499-GO-RFQ / P Promoting Participatory Villa Request for Quota Single Stage - One E engadaan Infrastruktur Ruan IBRD / 89410 Post Limited 97,500.00 98,051.77 Completed 2020-09-06 2020-09-29 2020-10-12 2020-11-04 2020-11-11 2020-12-16 ge Development tions nvelope g Kendali dan Media Center ID-PPMD-203501-NC-RFQ / P rinting and Distribution of P3 Promoting Participatory Villa Request for Quota Single Stage - One E Pending Impl PD Support Guidelines Subco IBRD / 89410 Post Limited 14,145.00 0.00 2020-11-13 2020-11-20 2020-12-20 ge Development tions nvelope ementation mponent 2B: Community Cap acity Building and Social Acc ountability Systems ID-PPMD-363604-GO-RFB / D evelopment of Digital Comm Promoting Participatory Villa Single Stage - One E Pending Impl unity Space (Fase 1) IBRD / 89410 Post Request for Bids Open - National 396,959.00 0.00 2023-05-29 2023-06-02 2023-06-22 2023-06-29 2023-07-10 2024-01-06 ge Development nvelope ementation (Pengembangan Ruang Kom unitas Digital Fase 1) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-PPMD-169353-NC-RFB / A dministrative Services Firm ( Promoting Participatory Villa Single Stage - One E ASF) for Managing Contracts IBRD / 89410 Prior Request for Bids Open - National 4,000,000.00 3,535,875.79 Signed 2020-05-11 2020-05-18 2020-05-16 2020-06-06 2020-08-19 2020-07-06 2021-01-20 2020-08-10 2021-02-25 2024-12-17 ge Development nvelope of Technical Assistance Supp orts for MOV under Compone nt 2 ID-PPMD-203511-NC-RFQ / P reparation of Policy Documen Promoting Participatory Villa Request for Quota Single Stage - One E IBRD / 89410 Post Limited 73,741.00 72,865.12 Completed 2020-11-12 2020-11-05 2020-11-19 2020-11-21 2020-12-31 2020-12-22 ts and Socialization Materials ge Development tions nvelope of P3PD Subcomponent 2B ID-PPMD-203859-NC-RFQ / Promoting Participatory Villa Request for Quota Single Stage - One E Workshop for Regulation Har IBRD / 89410 Post Limited 30,000.00 27,158.30 Signed 2020-11-12 2020-11-19 2020-11-19 2020-12-09 2020-12-31 ge Development tions nvelope monization of Sub-Componen t 2A-P3PD PIU PMD ID-PPMD-234734-NC-RFB / S trengthening Capacity of Ten Promoting Participatory Villa Single Stage - One E IBRD / 89410 Prior Request for Bids Open - National 2,750,000.00 2,555,432.43 Signed 2021-05-17 2021-08-13 2021-05-24 2021-06-07 2021-09-03 2021-06-21 2021-10-22 2021-07-08 2021-11-19 2021-11-05 aga Pendamping Profesional ge Development nvelope (TPP) P3PD Project Fiscal Ye ar 2021 ID-PPMD-234735-NC-RFB / Pr eparation of P3PD Learning Promoting Participatory Villa Single Stage - One E IBRD / 89410 Post Request for Bids Open - National 365,000.00 386,213.30 Signed 2021-05-17 2021-05-31 2021-05-24 2021-06-03 2021-06-08 2021-06-10 2021-06-09 2021-06-21 2021-08-03 2021-10-19 Materials Subcomponent 2b ge Development nvelope and Women's Leadership Wo rkshop ID-PPMD-234757-NC-RFB / T echnical Guidance for Inclusi Promoting Participatory Villa Single Stage - One E ve Village P3PD and Tryout o IBRD / 89410 Post Request for Bids Open - National 850,000.00 766,486.38 Signed 2021-05-17 2021-08-13 2021-05-24 2021-06-03 2021-09-02 2021-06-11 2021-09-03 2021-06-21 2021-10-12 2021-11-28 ge Development nvelope f Social Accountability Imple mentation in P3PD Village ID-PPMD-249694-NC-RFB / E Promoting Participatory Villa Single Stage - One E vent Organizer for Communit IBRD / 89410 Post Request for Bids Open - National 380,000.00 342,046.87 Signed 2021-09-06 2021-09-20 2021-09-08 2021-09-22 2021-10-05 2021-09-29 2021-10-08 2021-10-14 2021-10-29 2021-12-14 ge Development nvelope y Based Learning Video Prod uction ID-PPMD-250405-NC-RFQ / P roduction Village Developme Promoting Participatory Villa Request for Quota Single Stage - One E IBRD / 89410 Post Limited 97,000.00 92,383.37 Completed 2021-09-09 2021-09-07 2021-09-29 2021-10-19 2021-11-29 2021-12-17 nt Information Campaign Tha ge Development tions nvelope t Impact On Village SDGs ID-PPMD-250407-NC-RFQ / E vent Organizer for Socializati Promoting Participatory Villa Request for Quota Single Stage - One E on P3PD Subcomponent 2b: IBRD / 89410 Post Limited 91,000.00 90,877.75 Completed 2021-09-09 2021-09-17 2021-09-30 2021-10-19 2021-12-07 2021-12-18 ge Development tions nvelope Community Capacity Develo pment And Social Accountabi lity System ID-PPMD-258819-NC-RFB / C Promoting Participatory Villa Single Stage - One E Under Imple apacity Building for Digital C IBRD / 89410 Post Request for Bids Open - National 393,000.00 0.00 2021-10-28 2022-02-07 2021-11-01 2021-11-11 2022-02-17 2021-11-15 2021-11-27 2022-01-31 ge Development nvelope mentation adres for P3PD Program ID-PPMD-258830-NC-RFQ / C Promoting Participatory Villa Request for Quota Single Stage - One E apacity Building For Digital A IBRD / 89410 Post Limited 98,700.00 72,064.94 Completed 2021-11-01 2021-11-22 2021-11-17 2021-12-15 2021-12-17 2021-12-31 ge Development tions nvelope mbassadors For P3PD Progra m ID-PPMD-259097-NC-RFQ / V Promoting Participatory Villa Request for Quota Single Stage - One E IBRD / 89410 Post Limited 99,700.00 93,346.69 Completed 2021-11-01 2021-10-25 2021-11-19 2021-11-09 2021-12-29 2021-12-28 illage Best Practice Documen ge Development tions nvelope tation Page 1 ID-PPMD-269320-NC-RFB / A dministrative Services Firm ( Promoting Participatory Villa Single Stage - One E Under Imple IBRD / 89410 Prior Request for Bids Open - National 10,789,642.00 0.00 2022-03-16 2022-09-13 2022-03-21 2022-04-11 2022-10-17 2022-05-11 2022-11-29 2022-06-01 2025-04-01 ASF) for Digital Ambassadors ge Development nvelope mentation and Cadres for smart village development ID-PPMD-290481-NC-RFB / Vi llage Development Informati Promoting Participatory Villa Single Stage - One E Pending Impl IBRD / 89410 Post Request for Bids Open - National 142,858.00 0.00 2022-05-05 2022-05-09 2022-05-23 2022-05-30 2022-06-10 2022-12-07 on Campaigns That Have an I ge Development nvelope ementation mpact on Village SDGs ID-PPMD-290489-NC-RFQ / P 3PD Subcomponent 2D Work shop : Promoting Participatory Villa Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 60,205.00 0.00 2022-04-26 2022-05-15 2022-06-14 1. Workshop on Preparation ge Development tions nvelope ementation of PTO Component 2 P3PD 2. Workshop Finalization of P TO Component 2 P3PD ID-PPMD-290971-NC-RFB / E Promoting Participatory Villa Single Stage - One E Pending Impl xpansion of Social Accountab IBRD / 89410 Post Request for Bids Open - National 178,571.00 0.00 2022-04-24 2022-04-27 2022-05-17 2022-05-24 2022-05-31 2022-09-28 ge Development nvelope ementation ility Score Card Trials in Villa ges ID-PPMD-290972-NC-RFQ / P 3PD Subcomponent 2b Coord Promoting Participatory Villa Request for Quota Single Stage - One E Under Imple ination Meeting: Community IBRD / 89410 Post Limited 89,286.00 0.00 2022-04-27 2022-06-07 2022-05-26 2022-06-25 ge Development tions nvelope mentation Capacity Development And S ocial Accountability System ID-PPMD-290975-NC-RFB / C Promoting Participatory Villa Single Stage - One E Under Imple apacity Building of The Smart IBRD / 89410 Post Request for Bids Open - National 663,223.00 0.00 2022-05-29 2022-07-17 2022-06-03 2022-06-17 2022-08-01 2022-06-27 2022-08-10 2022-07-06 2022-08-05 ge Development nvelope mentation Village Master of Training ID-PPMD-295259-NC-RFB / C apacity Building for Professio Promoting Participatory Villa Single Stage - One E Under Imple nal Facilitators in the Progra IBRD / 89410 Prior Request for Bids Open - National 5,732,302.00 0.00 2022-05-29 2022-08-11 2022-06-03 2022-06-17 2022-09-14 2022-07-01 2022-11-09 2022-07-13 2022-10-11 ge Development nvelope mentation m for Strengthening Village Government and Developme nt (P3PD) for Fiscal Year 202 2 ID-PPMD-295267-NC-RFB / L earning Video Content Produ ction contain (Event Organiz Promoting Participatory Villa Single Stage - One E Under Imple IBRD / 89410 Post Request for Bids Open - National 239,286.00 0.00 2022-05-29 2022-07-04 2022-06-03 2022-06-17 2022-07-15 2022-07-01 2022-07-13 2023-01-09 ation Services): ge Development nvelope mentation Capacity building on the Prod uction of Learning Videos for the community ID-PPMD-295272-NC-RFB / F Promoting Participatory Villa Single Stage - One E Pending Impl IBRD / 89410 Post Request for Bids Open - National 267,857.00 0.00 2022-05-29 2022-06-03 2022-06-17 2022-07-01 2022-07-13 2023-01-09 acilitate Sustainable AD Utiliz ge Development nvelope ementation ation ID-PPMD-295275-NC-RFB / C Promoting Participatory Villa Single Stage - One E Under Imple apacity Building for Digital C IBRD / 89410 Prior Request for Bids Open - National 2,170,375.00 0.00 2022-05-29 2022-09-23 2022-06-03 2022-06-17 2022-10-24 2022-07-01 2023-01-15 2022-07-13 2022-08-12 ge Development nvelope mentation adre Phase I and II ID-PPMD-295740-NC-RFB / L earning Video Content Produ ction contain : Promoting Participatory Villa Single Stage - One E Under Imple IBRD / 89410 Post Request for Bids Open - National 228,571.00 0.00 2022-05-27 2022-07-04 2022-06-01 2022-06-15 2022-07-15 2022-06-29 2022-07-22 2022-07-11 2023-01-07 1. Production of learning vide ge Development nvelope mentation os 2. Curation and production o f learning video content ID-PPMD-308899-NC-RFQ / D Promoting Participatory Villa Request for Quota Single Stage - One E Pending Impl evelopment of Community Le IBRD / 89410 Post Limited 90,592.00 0.00 2022-08-22 2022-09-19 2022-12-20 ge Development tions nvelope ementation arning Center ID-PPMD-314475-NC-RFQ / Workshop on Village Technic al Capacity Building Develop Promoting Participatory Villa Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 90,255.00 0.00 2022-09-16 2022-10-17 2022-11-15 ment Planning ge Development tions nvelope ementation (Workshop Perencanaan Pen gembangan Penyedia Pening katan Kapasitas Teknis Desa (P2KTD) ID-PPMD-295273-NC-RFB / C Promoting Participatory Villa Single Stage - One E Pending Impl IBRD / 89410 Post Request for Bids Open - National 408,128.00 0.00 2022-05-29 2022-06-03 2022-06-17 2022-07-01 2022-07-13 2022-08-12 apacity Building for Digital A ge Development nvelope ementation mbassador ID-PPMD-363600-NC-RFB / S ocialization and Disseminatio Promoting Participatory Villa Single Stage - One E Pending Impl n of P3PD Subcomponent 2B IBRD / 89410 Post Request for Bids Open - National 296,352.00 0.00 2023-05-29 2023-06-02 2023-06-22 2023-06-29 2023-07-13 2024-01-09 ge Development nvelope ementation (Sosialisasi dan Diseminasi P 3PD Subkomponen 2B) ID-PPMD-363601-NC-RFB / Pr oduction of Learning Video C ontent of 2 lots : 1. Capacity building on the Pr Promoting Participatory Villa Single Stage - One E Pending Impl oduction of IBRD / 89410 Post Request for Bids Open - National 402,027.00 0.00 2023-05-29 2023-06-03 2023-06-23 2023-06-30 2023-07-12 2024-01-08 ge Development nvelope ementation Learning Videos 2. Video Production by Villag e Content Creator with The Firm ID-PPMD-363602-NC-RFB / Vi llage Academy Online Video Promoting Participatory Villa Single Stage - One E Pending Impl Platform Strengthening IBRD / 89410 Post Request for Bids Open - National 122,041.00 0.00 2023-05-29 2023-06-02 2023-06-22 2023-06-29 2023-07-11 2024-01-07 ge Development nvelope ementation (Penguatan Online Video Plat form Akademi Desa) ID-PPMD-363603-NC-RFQ / C oordination Across Piu For Th e Implementation Of P3PD C Promoting Participatory Villa Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 68,790.00 0.00 2023-06-05 2023-07-07 2023-07-27 omponent 2 Activities ge Development tions nvelope ementation (Koordinasi Lintas PIU Pelaks anaan Kegiatan P3PD Kompo nen 2) ID-PPMD-367223-NC-RFB / P Promoting Participatory Villa Single Stage - One E Pending Impl IBRD / 89410 Post Request for Bids Open - National 100,280.00 0.00 2023-06-25 2023-06-30 2023-07-14 2023-07-21 2023-08-02 2023-10-31 3PD Subcomponent 2B Work ge Development nvelope ementation Meeting ID-PPMD-367224-NC-RFB / F Promoting Participatory Villa Single Stage - One E Pending Impl acilitating the Utilization of th IBRD / 89410 Post Request for Bids Open - National 353,078.00 0.00 2023-06-25 2023-06-30 2023-07-14 2023-07-21 2023-07-31 2023-12-28 ge Development nvelope ementation e Sustainable Village Academ y ID-PPMD-367225-NC-RFB / In stitutionalization of Online Vi Promoting Participatory Villa Single Stage - One E Pending Impl deo Platforms and Curation o IBRD / 89410 Post Request for Bids Open - National 155,503.00 0.00 2023-06-25 2023-06-30 2023-07-14 2023-07-21 2023-07-31 2023-12-28 ge Development nvelope ementation f Learning Video Content Con tain 2 (two) Lots of Procure ment Packages Page 2 ID-PPMD-367295-NC-RFB / C apacity Building TPP P3PD co Promoting Participatory Villa Single Stage - One E Pending Impl IBRD / 89410 Prior Request for Bids Open - National 3,437,497.00 0.00 2023-06-25 2023-06-30 2023-07-20 2023-07-27 2023-08-08 2023-11-06 ntain 11 (Eleven) Lots of pro ge Development nvelope ementation curement packages CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-PPMD-187415-CS-QCBS / Consultant services for NGO Promoting Participatory Villa Quality And Cost- Open - Internationa IBRD / 89410 Prior 3,882,000.00 0.00 Canceled 2020-08-12 2020-10-19 2020-09-02 2020-09-23 2020-10-21 2020-11-04 2020-12-09 2021-01-04 2024-12-24 Village Community Capacity ge Development Based Selection l Development Region I ID-PPMD-187419-CS-QCBS / Consultant services for NGO Promoting Participatory Villa Quality And Cost- Open - Internationa IBRD / 89410 Prior 4,327,000.00 0.00 Canceled 2020-08-12 2020-10-19 2020-09-02 2020-09-23 2020-10-21 2020-11-04 2020-12-09 2021-01-04 2024-12-24 Village Community Capacity ge Development Based Selection l Development Region II ID-PPMD-187423-CS-QCBS / Consultant services for NGO Promoting Participatory Villa Quality And Cost- Open - Internationa IBRD / 89410 Prior 4,436,000.00 0.00 Canceled 2020-08-12 2020-10-19 2020-09-02 2020-09-23 2020-10-21 2020-11-04 2020-12-09 2021-01-04 2024-12-24 Village Community Capacity ge Development Based Selection l Development Region III ID-PPMD-240060-CS-QCBS / Community Capacity Develo pment And Social Accountabi Promoting Participatory Villa Quality And Cost- Open - Internationa IBRD / 89410 Prior 2,067,500.00 0.00 Canceled 2021-06-21 2021-06-27 2021-07-12 2021-07-21 2021-08-10 2022-02-20 2021-09-07 2022-04-25 2021-10-07 2022-08-12 2021-11-25 2021-12-27 2024-12-10 lity Systems Through Digital ge Development Based Selection l Platforms (Non-Government Organization) Western Regio n ID-PPMD-240069-CS-QCBS / Community Capacity Develo pment And Social Accountabi Promoting Participatory Villa Quality And Cost- Open - Internationa Under Implement IBRD / 89410 Prior 2,275,500.00 0.00 2021-06-21 2021-06-27 2021-07-12 2021-07-21 2021-08-10 2022-02-20 2021-09-07 2022-04-25 2021-10-07 2022-08-11 2021-11-25 2022-11-17 2021-12-27 2024-12-10 lity Systems Through Digital ge Development Based Selection l ation Platforms (Non-Government Organization) middle Region ID-PPMD-240074-CS-QCBS / Community Capacity Develo pment And Social Accountabi Promoting Participatory Villa Quality And Cost- Open - Internationa Under Implement IBRD / 89410 Prior 2,340,500.00 0.00 2021-06-21 2021-06-27 2021-07-12 2021-07-21 2021-08-10 2022-02-21 2021-09-07 2022-04-25 2021-10-07 2022-08-11 2021-11-25 2022-11-16 2021-12-27 2024-12-10 lity Systems Through Digital ge Development Based Selection l ation Platforms (Non-Government Organization) Eastern Region ID-PPMD-250406-CS-CQS / C onsultant Services for Prepar Promoting Participatory Villa Consultant Qualifi IBRD / 89410 Post Open - National 55,000.00 0.00 Under Review 2021-09-06 2021-08-09 2021-09-20 2021-09-30 2021-10-14 2021-10-20 2022-01-18 ation For Online Design Deve ge Development cation Selection lopment Video Village Acade mic Platform 4.0 ID-PPMD-259698-CS-CQS / G rand Design Learning Manag Promoting Participatory Villa Consultant Qualifi Pending Impleme IBRD / 89410 Post Open - National 82,500.00 0.00 2021-10-28 2021-11-11 2021-11-22 2021-11-24 2021-12-01 2022-03-01 ement System (LMS) for Ten ge Development cation Selection ntation aga Pendamping Profesional (TPP) ID-PPMD-265590-CS-CQS / I Promoting Participatory Villa Consultant Qualifi Pending Impleme IBRD / 89410 Post Open - National 111,545.00 0.00 2021-11-29 2021-12-03 2021-12-15 2021-12-19 2021-12-23 2022-04-22 mpact Evaluation Smart villa ge Development cation Selection ntation ge ID-PPMD-265592-CS-CQS / M Promoting Participatory Villa Consultant Qualifi Pending Impleme IBRD / 89410 Post Open - National 95,975.00 0.00 2021-11-29 2021-12-03 2021-12-15 2021-12-19 2021-12-23 2022-04-22 onitoring and Evaluation Sma ge Development cation Selection ntation rt Village ID-PPMD-296768-CS-CQS / Vi Promoting Participatory Villa Consultant Qualifi Pending Impleme llage Academic Online Video IBRD / 89410 Post Open - National 285,715.00 0.00 2022-05-30 2022-06-13 2022-07-01 2022-07-06 2022-07-25 2023-03-22 ge Development cation Selection ntation Platform 4.0 Development ID-PPMD-314439-CS-CQS / G Promoting Participatory Villa Consultant Qualifi Pending Impleme rand Design And Business Re IBRD / 89410 Post Open - National 54,297.00 0.00 2022-09-11 2022-09-26 2022-10-10 2022-10-13 2022-10-22 2022-12-21 ge Development cation Selection ntation quirement Platform Digital M arketplace P2KTD ID-PPMD-325914-CS-QCBS / Promoting Participatory Villa Quality And Cost- Development of Learning Ma IBRD / 89410 Post Open - National 557,050.00 0.00 Under Review 2022-11-27 2023-03-06 2022-12-18 2023-01-16 2023-02-13 2023-02-23 2023-03-01 2023-03-22 2023-10-18 ge Development Based Selection nagement System Method ID-PPMD-367283-CS-CQS / C Promoting Participatory Villa Consultant Qualifi Pending Impleme onsulting Services Module an IBRD / 89410 Post Open - National 112,051.00 0.00 2023-06-25 2023-07-10 2023-07-24 2023-07-27 2023-08-07 2023-12-05 ge Development cation Selection ntation d LMS Content ID-PPMD-367289-CS-CQS / D evelopment of Digital Market Promoting Participatory Villa Consultant Qualifi Pending Impleme place Platform for Village Tec IBRD / 89410 Post Open - National 258,091.00 0.00 2023-06-25 2023-07-10 2023-07-31 2023-08-03 2023-08-15 2023-12-13 ge Development cation Selection ntation hnical Capacity Building Provi ders (P2KTD) P3PD Program ID-PPMD-352662-CS-CQS / S Promoting Participatory Villa Consultant Qualifi Pending Impleme mart Village Module Develop IBRD / 89410 Post Open - National 28,989.00 0.00 2023-03-30 2023-04-13 2023-04-25 2023-05-02 2023-05-15 2023-07-14 ge Development cation Selection ntation ment (Pengembangan Modul Desa Cerdas) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-PPMD-203715-CS-INDV / Procurement of Individual Co Promoting Participatory Villa Individual Consult Pending Impleme nsultant for Participatory Pla IBRD / 89410 Post Limited 2,840.00 0.00 2020-11-09 2020-11-11 2020-11-13 2020-11-17 2021-01-16 ge Development ant Selection ntation nning, Inclusion and Social A ccountability for the P3PD Pr ogram, Subcomponent 2B ID-PPMD-367227-CS-INDV / Promoting Participatory Villa Individual Consult Pending Impleme IBRD / 89410 Post Limited 6,687.00 0.00 2023-06-26 2023-07-03 2023-07-06 2023-07-13 2023-08-12 P3PD Module Development S ge Development ant Selection ntation pecialist Page 3 PROCUREMENT PLAN (Textual Part) Project information: Pakistan Higher Education Development Project P- 161386 Project Implementation agency: Higher Education Commission Date of the Procurement Plan: May 15, 2019 Period covered by this Procurement Plan: May 15, 2019- May 15, 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) Revised November 2017 and August 2018 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Public Procurement Rules 2004, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 2) For national open competitive procurement, only the model procurement documents acceptable to the World Bank, shall be used. 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 5) Access to procurement opportunities shall not be restricted to firms that have pre-registered and/or paid a registration fee. 6) No preference of any kind shall be given to national bidders in the bidding process. When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable]; Works: [is not applicable s] PROCUREMENT Pakistan : Higher Education Development in Pakistan PLAN General Information Country: Pakistan 2019-09-13 Bank’s Approval Date of the Original Procurement Plan: 2023-05-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161386 GPN Date: 2019-05-14 Project Name: Higher Education Development in Pakistan Loan / Credit No: IDA / 64380 Higher Education Commission Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-HEC-123692-GO-RFB / Ex Supporting Decentralized Hi Pending Impl pansion the PERN connectivit IDA / 64380 gher Education Institutes for Prior Direct Selection Direct 12,120,000.00 0.00 2019-11-15 2019-11-20 2019-12-25 2020-06-22 ementation y to Affiliated Colleges of Pak Improved Teaching and Lear istan ning PK-HEC-123699-GO-RFB / Pr Supporting Decentralized Hi Single Stage - One E Pending Impl ovisioning of Power backups IDA / 64380 gher Education Institutes for Prior Request for Bids Open - National 2,118,000.00 0.00 2019-11-15 2019-11-20 2020-01-01 2020-01-31 2020-03-06 2020-09-02 nvelope ementation related to PERN expansion Improved Teaching and Lear ning PK-HEC-133940-GO-RFP / Inf Equipping Students and Hig Request for Propo Open - Internationa Pending Impl rastructure to setup High Per IDA / 64380 her Education Institutions wi Prior Multi Stage 6,700,000.00 0.00 2019-11-15 2019-11-20 2020-01-29 2020-06-16 2021-12-08 sals l ementation formance Compute Services th Modern Technology under PERN PK-HEC-133944-GO-RFB / Eq Supporting Decentralized Hi uipping Colleges with Next G gher Education Institutes for Single Stage - Two E Pending Impl IDA / 64380 Prior Request for Bids Open - National 11,900,000.00 0.00 2019-11-15 2019-11-20 2020-01-01 2020-03-15 2020-04-19 2020-10-16 eneration Networks and Audi Improved Teaching and Lear nvelope ementation o/Video Technology ning Higher Education Manageme PK-HEC-133946-GO-RFP / ER Request for Propo Open - Internationa IDA / 64380 nt Information System and D Prior Multi Stage 19,500,000.00 0.00 Canceled 2019-11-15 2019-11-20 2020-01-29 2020-05-12 2020-06-16 2021-12-08 P Solution for HEIs sals l ata Driven Services PK-HEC-133994-GO-RFB / Ha Higher Education Manageme Open - Internationa Single Stage - Two E Pending Impl rdware Infrastructure for Digi IDA / 64380 nt Information System and D Prior Request for Bids 11,800,000.00 0.00 2020-02-01 2020-02-06 2020-03-19 2020-06-01 2020-07-06 2021-01-02 l nvelope ementation tization of Universities ata Driven Services PK-HEC-123673-CS-QCBS / D Higher Education Manageme evelopment of the Tool, Impl Single Stage - One E IDA / 64380 nt Information System and D Post Request for Bids Open - National 880,000.00 0.00 Canceled 2019-09-16 2019-09-21 2019-11-02 2019-12-02 2020-01-06 2020-07-04 ementation and Training for nvelope ata Driven Services Data Repository Portal. PK-HEC-123702-GO-RFB / Es Supporting Decentralized Hi Open - Internationa Single Stage - One E Pending Impl tablishment of Smart Classro IDA / 64380 gher Education Institutes for Prior Request for Bids 5,820,000.00 0.00 2019-11-01 2019-11-06 2019-12-18 2020-01-17 2020-02-21 2023-12-31 l nvelope ementation oms in Universities and Affilia Improved Teaching and Lear ted Colleges ning PK-HEC-133948-GO-RFP / St Higher Education Manageme Request for Propo Open - Internationa udent Life Cycle Solution for IDA / 64380 nt Information System and D Prior Multi Stage 36,600,000.00 0.00 Canceled 2019-11-15 2019-11-20 2020-01-29 2020-05-12 2020-06-16 2021-12-08 sals l HEIs ata Driven Services PK-HEC-133936-GO-RFP / Inf Equipping Students and Hig Request for Propo Open - Internationa Single Stage - Two E Pending Impl rastructure for the establish IDA / 64380 her Education Institutions wi Prior 8,700,000.00 0.00 2019-12-15 2019-12-20 2020-01-31 2020-04-14 2020-05-19 2021-05-19 sals l nvelope ementation ment for cloud services unde th Modern Technology r PERN PK-HEC-123696-GO-DIR / Str Supporting Decentralized Hi Request for Quota Single Stage - One E Pending Impl engthening the PERN Backbo IDA / 64380 gher Education Institutes for Prior Limited 8,275,000.00 0.00 2019-11-20 2020-01-15 2024-06-30 tions nvelope ementation ne and population of IP Upstr Improved Teaching and Lear eam ning PK-HEC-211458-GO-RFP / En Higher Education Manageme Request for Propo Open - Internationa terprise Resources Planning ( IDA / 64380 nt Information System and D Prior 5,500,000.00 0.00 Canceled 2020-12-29 2021-02-03 2021-03-16 2021-10-22 2021-03-22 2022-07-28 2021-01-10 2021-03-31 2021-05-06 2021-07-16 2021-08-30 2024-05-31 sals l ERP) -3 LOTs ata Driven Services PK-HEC-211652-GO-RFP / St Higher Education Manageme Request for Propo Open - Internationa udent Life Cycle Solution (SL IDA / 64380 nt Information System and D Prior 9,375,000.00 0.00 Canceled 2020-12-29 2021-02-03 2021-03-16 2021-12-14 2021-03-22 2022-07-28 2021-01-10 2021-03-30 2021-05-06 2021-07-16 2021-08-30 2024-05-31 sals l CS) -3 LOTS ata Driven Services PK-HEC-217178-GO-RFB / O Nurturing Academic Excellen Open - Internationa Single Stage - One E IDA / 64380 Post Request for Bids 600,000.00 565,442.32 Signed 2021-02-02 2021-03-04 2021-03-09 2021-03-10 2021-04-22 2021-04-22 2021-05-22 2021-12-21 2021-06-26 2022-03-11 2021-12-23 RICs / BICs Automation Platfo ce in Strategic Sectors l nvelope rm Capacity Building through Pa PK-HEC-223795-GO-RFQ / Su Request for Quota Single Stage - One E IDA / 64380 rtnerships, Project Managem Post Open - National 60,000.00 37,169.19 Signed 2021-03-19 2021-04-06 2021-04-27 2021-06-15 2021-05-27 pply of IT/Office Equipment tions nvelope ent, Monitoring and Evaluati on PK-HEC-291120-GO-DIR / Su Equipping Students and Hig Pending Impl rvey & Experience Managem IDA / 64380 her Education Institutions wi Post Direct Selection Direct 125,000.00 0.00 2022-04-22 2022-05-02 2022-05-27 2024-05-26 ementation ent Software th Modern Technology PK-HEC-334177-GO-DIR / Lic Equipping Students and Hig Pending Impl ense Procurement for SAP ER IDA / 64380 her Education Institutions wi Post Direct Selection Direct - National 355,000.00 0.00 2022-12-30 2023-01-04 2023-02-08 2023-08-07 ementation P Upgrade at HEC th Modern Technology Capacity Building through Pa PK-HEC-345535-GO-RFQ / Pr Request for Quota Single Stage - One E Under Imple IDA / 64380 rtnerships, Project Managem Post Open - National 40,000.00 0.00 2023-03-10 2023-03-30 2023-05-06 2023-06-05 ocurement of Laptops tions nvelope mentation ent, Monitoring and Evaluati on PK-HEC-347464-GO-RFB / De Equipping Students and Hig Open - Internationa Single Stage - One E Under Imple sign, Supply and Installation IDA / 64380 her Education Institutions wi Prior Request for Bids 6,000,000.00 0.00 2023-03-10 2023-04-19 2023-03-17 2023-04-20 2023-05-01 2023-05-31 2023-06-29 2023-12-26 l nvelope mentation of Data Center POD and its C th Modern Technology omponents PK-HEC-352912-GO-RFB / Pr Equipping Students and Hig ocurement of Hardware and Open - Internationa Single Stage - One E Under Imple IDA / 64380 her Education Institutions wi Prior Request for Bids 17,000,000.00 0.00 2023-03-31 2023-06-23 2023-04-07 2023-06-26 2023-05-22 2023-06-21 2023-07-26 2024-05-31 Enterprise Resource Planning l nvelope mentation th Modern Technology and Student Life Cycle Syste m (ERP/ SLCS) Page 1 PK-HEC-352924-GO-RFB / Su Equipping Students and Hig Open - Internationa Single Stage - One E Under Imple pply and Installation of Datac IDA / 64380 her Education Institutions wi Prior Request for Bids 4,000,000.00 0.00 2023-03-30 2023-04-05 2023-04-06 2023-04-05 2023-05-21 2023-05-25 2023-06-20 2023-07-25 2023-11-02 l nvelope mentation enter Network Components th Modern Technology PK-HEC-363822-GO-RFB / Up Equipping Students and Hig Single Stage - One E Under Imple gradation of ERP Solution at IDA / 64380 her Education Institutions wi Post Request for Bids Open - National 700,000.00 0.00 2023-05-30 2023-06-01 2023-06-05 2023-06-20 2023-06-27 2023-07-27 2023-08-25 2024-05-31 nvelope mentation HEC th Modern Technology PK-HEC-369008-GO-RFB / Pr Equipping Students and Hig Open - Internationa Single Stage - One E Pending Impl ocurement of Edge and IP Su IDA / 64380 her Education Institutions wi Prior Request for Bids 4,000,000.00 0.00 2023-06-30 2023-07-10 2023-08-24 2023-09-23 2023-10-22 2024-06-30 l nvelope ementation rveillance Equipment th Modern Technology PK-HEC-369013-GO-RFB / Pr Equipping Students and Hig Open - Internationa Single Stage - One E Pending Impl ocurement of Video Conferen IDA / 64380 her Education Institutions wi Prior Request for Bids 3,500,000.00 0.00 2023-06-30 2023-07-10 2023-08-24 2023-09-23 2023-10-22 2024-06-24 l nvelope ementation cing Equipment th Modern Technology NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-HEC-192667-NC-DIR / Ma Equipping Students and Hig ssive Open Online Courses ( IDA / 64380 her Education Institutions wi Post Direct Selection Direct 95,000.00 74,971.63 Signed 2020-09-09 2020-07-11 2020-09-14 2020-10-19 2020-10-19 2020-12-11 2022-10-19 MOOCs) Platform at HEC th Modern Technology PK-HEC-280661-NC-DIR / Hig Higher Education Manageme Under Imple her Education Data Repositor IDA / 64380 nt Information System and D Post Direct Selection Direct 120,000.00 0.00 2022-02-28 2022-03-02 2022-03-05 2022-04-24 2024-06-30 mentation y(HEDR) , Service Level Agre ata Driven Services ement CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-HEC-123657-CS-QCBS / N Supporting Decentralized Hi eed Assessment study for de gher Education Institutes for Quality And Cost- IDA / 64380 Prior Open - National 1,000,000.00 0.00 Canceled 2019-10-15 2019-10-29 2019-12-12 2020-01-09 2020-02-08 2020-03-14 2020-04-18 2020-10-15 veloping courses for Commu Improved Teaching and Lear Based Selection nity colleges and Associates ning Degree Program PK-HEC-123665-CS-QCBS / F Supporting Decentralized Hi acilitate the implementation gher Education Institutes for Quality And Cost- of the HEC’s mandate to roll IDA / 64380 Post Open - National 600,000.00 0.00 Canceled 2019-10-15 2019-11-05 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2021-04-25 Improved Teaching and Lear Based Selection out 4-year Bachelor of Scienc ning e (BS) programs and Curricul a Revision PK-HEC-123666-CS-CQS / Dr Equipping Students and Hig Consultant Qualifi afting of ICT Strategy - Consu IDA / 64380 her Education Institutions wi Post Open - National 250,000.00 0.00 Canceled 2019-10-15 2019-11-05 2019-12-19 2020-01-18 2020-02-22 2021-02-21 cation Selection ltancy th Modern Technology PK-HEC-123674-CS-QCBS / C Higher Education Manageme Quality And Cost- onsultants to Assist HEC in th IDA / 64380 nt Information System and D Post Open - National 600,000.00 0.00 Canceled 2019-10-15 2019-11-05 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2021-04-25 Based Selection e selection of the ERP Solutio ata Driven Services n PK-HEC-123678-CS-QCBS / S upport to the ORICs and BICs Nurturing Academic Excellen Quality And Cost- IDA / 64380 Prior Open - National 2,000,000.00 0.00 Canceled 2019-10-15 2019-11-05 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2023-04-25 for the implementation of bot ce in Strategic Sectors Based Selection h the TTSF grant and the ISF – Consultants PK-HEC-123685-CS-QCBS / S Capacity Building through Pa Quality And Cost- tudies (Tracer study, Satisfac IDA / 64380 rtnerships, Project Managem Prior Open - National 2,000,000.00 0.00 Canceled 2019-10-15 2019-11-05 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2023-04-25 Based Selection tion survey, gender study) ent, Monitoring and Evaluati on PK-HEC-133769-CS-CQS / Co Equipping Students and Hig Consultant Qualifi Open - Internationa Pending Impleme nsultant to help develop an i IDA / 64380 her Education Institutions wi Post 300,000.00 0.00 2019-10-15 2019-11-05 2019-12-19 2020-01-18 2020-02-22 2021-02-21 cation Selection l ntation mproved governance system th Modern Technology for PERN Capacity Building through Pa PK-HEC-123683-CS-QCBS / T Least Cost Selecti IDA / 64380 rtnerships, Project Managem Prior Open - National 1,000,000.00 0.00 Canceled 2019-10-15 2020-05-14 2019-10-30 2019-12-13 2020-01-10 2020-02-09 2020-03-15 2020-04-19 2024-06-30 hird party verification agency on ent, Monitoring and Evaluati on PK-HEC-180837-CS-CQS / Thi Capacity Building through Pa Consultant Qualifi rd Party Verification Agency- IDA / 64380 rtnerships, Project Managem Post Open - National 350,000.00 135,759.74 Signed 2020-06-18 2020-06-18 2020-07-09 2020-06-21 2020-08-22 2020-12-09 2020-09-21 2021-02-09 2020-10-26 2021-03-30 2021-04-24 cation Selection Consulting Firm ent, Monitoring and Evaluati on PK-HEC-217177-CS-CQS / Co Nurturing Academic Excellen Consultant Qualifi nsultancy for Capacity Buildi IDA / 64380 Post Open - National 200,000.00 0.00 Canceled 2021-02-10 2021-04-05 2021-03-03 2021-04-09 2021-04-16 2021-05-16 2021-06-20 2022-12-12 ce in Strategic Sectors cation Selection ng of ORICs & BICs PK-HEC-256557-CS-CQS / Co Capacity Building through Pa nsultancy for National Acade rtnerships, Project Managem Consultant Qualifi Under Implement IDA / 64380 Post Limited 75,000.00 0.00 2021-10-05 2021-10-08 2021-10-19 2021-11-18 2021-12-23 2022-06-21 my for Higher Education(NAH ent, Monitoring and Evaluati cation Selection ation E) Strategic Planning on PK-HEC-256558-CS-CQS / Co Equipping Students and Hig Consultant Qualifi Under Implement nsultancy for IT Security Asse IDA / 64380 her Education Institutions wi Post Limited 66,000.00 0.00 2021-10-05 2021-10-08 2021-10-19 2021-11-18 2021-12-23 2022-06-21 cation Selection ation ssment th Modern Technology PK-HEC-256560-CS-CQS / Co Equipping Students and Hig Consultant Qualifi Under Implement nsultancy for updating the Po IDA / 64380 her Education Institutions wi Post Limited 70,000.00 0.00 2021-10-05 2021-10-08 2021-10-19 2021-11-18 2021-12-23 2022-06-21 cation Selection ation licy Framework for ICT th Modern Technology PK-HEC-256564-CS-QCBS / C Improving access and qualit onsultancy for Improving the Quality And Cost- Open - Internationa Under Implement IDA / 64380 y of remote learning and sup Post 660,000.00 0.00 2021-10-05 2021-10-08 2021-10-26 2021-11-16 2021-12-10 2022-10-31 2022-01-24 2022-12-15 2022-02-23 2023-01-10 2022-03-25 2022-04-22 2024-04-21 Revenue Generation of Public Based Selection l ation port to universities Sector Universities PK-HEC-256566-CS-CQS / Pr Higher Education Manageme Consultant Qualifi Under Implement obity Assurance Provider for IDA / 64380 nt Information System and D Post Limited 20,000.00 0.00 2021-10-05 2021-10-08 2021-10-19 2022-12-02 2021-11-02 2023-01-12 2021-11-19 2022-03-19 cation Selection ation ERP & SLCS Discovery Meetin ata Driven Services gs PK-HEC-256567-CS-QCBS / C Nurturing Academic Excellen Quality And Cost- Open - Internationa onsultancy - Innovator Seed IDA / 64380 Post 200,000.00 0.00 Canceled 2021-10-05 2021-10-26 2021-11-17 2022-01-01 2022-01-16 2022-01-30 2022-03-06 2023-09-07 ce in Strategic Sectors Based Selection l Fund Capacity Building Progr am Page 2 PK-HEC-257206-CS-LCS / Co Nurturing Academic Excellen Least Cost Selecti Open - Internationa nsultancy – Innovator Seed F IDA / 64380 Post 200,000.00 190,486.95 Signed 2021-10-07 2021-10-07 2021-10-28 2021-10-16 2021-11-14 2021-12-17 2021-12-29 2022-01-31 2022-01-08 2022-02-21 2022-01-28 2022-03-08 2022-02-18 2022-04-09 2023-10-11 ce in Strategic Sectors on l und Capacity Building Progra m PK-HEC-281977-CS-LCS / Co Capacity Building through Pa Least Cost Selecti Open - Internationa Under Implement nsultancy for Strategic Com IDA / 64380 rtnerships, Project Managem Post 160,000.00 0.00 2022-03-10 2022-03-24 2022-03-25 2022-04-18 2022-04-11 2022-05-26 2022-06-05 2022-06-25 2022-07-16 2024-06-30 on l ation munication of HEDP ent, Monitoring and Evaluati on PK-HEC-345542-CS-CQS / Sel Capacity Building through Pa Consultant Qualifi Under Implement ection of Consulting Firm for IDA / 64380 rtnerships, Project Managem Post Open - National 120,000.00 0.00 2023-03-02 2023-03-01 2023-03-23 2023-03-30 2023-04-21 2023-05-29 2023-05-06 2023-05-26 2024-06-30 cation Selection ation Third Party Verification ent, Monitoring and Evaluati on PK-HEC-123681-CS-QCBS / S Supporting Decentralized Hi election of Consulting Firm fo gher Education Institutes for Quality And Cost- IDA / 64380 Post Open - National 170,000.00 0.00 Canceled 2019-10-15 2019-11-05 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2021-04-25 r Study on Affiliation System Improved Teaching and Lear Based Selection of Public Sector Universities ning PK-HEC-350217-CS-CQS / Sel Capacity Building through Pa Consultant Qualifi Under Implement ection of Firm for Study on Af IDA / 64380 rtnerships, Project Managem Post Open - National 170,000.00 0.00 2023-03-21 2023-04-05 2023-04-11 2023-05-25 2023-06-08 2023-07-02 2023-12-29 cation Selection ation filiation System of Public Sect ent, Monitoring and Evaluati or Universities on PK-HEC-350221-CS-CQS / Sel Capacity Building through Pa ection of Consulting Firm for rtnerships, Project Managem Consultant Qualifi Under Implement Study on Contribution of Publ IDA / 64380 Post Open - National 40,000.00 0.00 2023-03-22 2023-04-05 2023-04-12 2023-05-26 2023-06-09 2023-07-03 2023-12-30 ent, Monitoring and Evaluati cation Selection ation ic Sector Universities towards on Sustainable Development Go als (SDGs) PK-HEC-353662-CS-CQS / Sel Capacity Building through Pa ection of Consulting Firm for rtnerships, Project Managem Consultant Qualifi Under Implement IDA / 64380 Post Open - National 80,000.00 0.00 2023-04-03 2023-04-04 2023-04-24 2023-06-07 2023-06-21 2023-07-15 2023-12-12 Training Need Assessment of ent, Monitoring and Evaluati cation Selection ation Public Sector Universities of on Punjab and Sindh INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-HEC-134012-CS-INDV / C Nurturing Academic Excellen Individual Consult onsultant for Remodeling of IDA / 64380 Post Open 250,000.00 0.00 Canceled 2019-10-01 2019-11-03 2019-11-13 2019-11-19 2020-11-18 ce in Strategic Sectors ant Selection Business Incubation Centers Capacity Building through Pa PK-HEC-134422-CS-INDV / Pr Individual Consult IDA / 64380 rtnerships, Project Managem Prior Open 300,000.00 36,694.53 Signed 2019-09-16 2019-09-24 2019-10-12 2020-05-21 2019-10-17 2020-06-09 2019-10-23 2020-06-17 2024-06-30 ogram Specialist ant Selection ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-134423-CS-INDV / Pr Individual Consult Under Implement IDA / 64380 rtnerships, Project Managem Prior Open 300,000.00 0.00 2019-09-16 2019-09-22 2019-10-12 2020-02-26 2019-10-17 2020-04-28 2019-10-23 2024-06-30 ogram Specialist - IT ant Selection ation ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-134424-CS-INDV / Pr Individual Consult Under Implement IDA / 64380 rtnerships, Project Managem Prior Open 300,000.00 0.00 2019-09-16 2019-09-22 2019-10-12 2020-02-26 2019-10-17 2019-10-23 2024-06-30 ogram Specialist - Academics ant Selection ation ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-134428-CS-INDV / Pr Individual Consult IDA / 64380 rtnerships, Project Managem Prior Open 300,000.00 88,066.87 Signed 2019-09-16 2019-09-22 2019-10-12 2020-05-21 2019-10-17 2020-06-09 2019-10-23 2020-06-12 2024-06-30 ogram Specialist-R&D ant Selection ent, Monitoring and Evaluati on PK-HEC-123559-CS-INDV / T Capacity Building through Pa echnical Assistance for devel rtnerships, Project Managem Individual Consult Pending Impleme IDA / 64380 Post Open 100,000.00 0.00 2019-10-15 2019-11-08 2019-11-29 2020-01-03 2021-01-02 opment of Criteria for enhanc ent, Monitoring and Evaluati ant Selection ntation ed autonomy -Consultancy on Capacity Building through Pa PK-HEC-134417-CS-INDV / Pr Individual Consult IDA / 64380 rtnerships, Project Managem Post Open 240,000.00 3,003.34 Signed 2019-09-16 2019-09-16 2019-10-12 2020-02-26 2019-10-17 2020-02-26 2019-10-23 2021-05-21 2024-10-21 ocurement Specialist ant Selection ent, Monitoring and Evaluati on PK-HEC-134418-CS-INDV / M Capacity Building through Pa Individual Consult onitoring & Evaluation Specia IDA / 64380 rtnerships, Project Managem Post Open 240,000.00 2,937.52 Signed 2019-09-16 2019-09-16 2019-10-12 2020-03-06 2019-10-17 2020-03-06 2019-10-23 2020-04-14 2024-06-30 ant Selection list ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-134420-CS-INDV / C Individual Consult IDA / 64380 rtnerships, Project Managem Post Open 240,000.00 2,937.52 Signed 2019-09-16 2019-09-16 2019-10-12 2020-02-26 2019-10-17 2020-02-26 2019-10-23 2020-04-07 2024-06-30 ommunication Specialist ant Selection ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-134431-CS-INDV / E Individual Consult IDA / 64380 rtnerships, Project Managem Post Open 270,000.00 0.00 Canceled 2019-09-16 2019-09-16 2019-10-12 2019-10-17 2019-10-23 2024-06-30 nvironmental Specialist ant Selection ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-134432-CS-INDV / S Individual Consult IDA / 64380 rtnerships, Project Managem Post Open 270,000.00 0.00 Canceled 2019-09-16 2020-04-14 2019-10-12 2019-10-17 2019-10-23 2024-06-30 ocial Specialist ant Selection ent, Monitoring and Evaluati on PK-HEC-145841-CS-INDV / C Nurturing Academic Excellen Individual Consult IDA / 64380 Post Open 100,000.00 0.00 Canceled 2019-11-15 2019-10-08 2019-12-11 2020-04-17 2019-12-16 2019-12-22 2020-12-21 onsultant (ORIC/BIC mapping ce in Strategic Sectors ant Selection ) PK-HEC-134419-CS-INDV / Fi Capacity Building through Pa Individual Consult nancial Management Speciali IDA / 64380 rtnerships, Project Managem Post Open 270,000.00 73,510.36 Signed 2019-09-16 2019-11-01 2019-10-12 2020-04-10 2019-10-17 2020-04-28 2019-10-23 2020-05-05 2024-10-21 ant Selection st ent, Monitoring and Evaluati on PK-HEC-172414-CS-CDS / Int Supporting Decentralized Hi ernational Expert/Consultant IDA / 64380 gher Education Institutes for Post Direct Selection Direct 53,000.00 49,000.00 Signed 2020-05-06 2020-04-14 2020-05-16 2020-04-02 2020-07-20 2020-04-21 2021-01-16 Research and Academic Gov Improved Teaching and Lear ernance ning PK-HEC-172415-CS-CDS / Int Supporting Decentralized Hi ernational Expert/Consultant IDA / 64380 gher Education Institutes for Post Direct Selection Direct 53,000.00 66,000.00 Signed 2020-05-06 2020-04-14 2020-05-16 2020-03-22 2020-07-20 2020-04-21 2021-01-16 Research, Teaching and Lear Improved Teaching and Lear ning ning PK-HEC-172417-CS-CDS / Int Supporting Decentralized Hi ernational Expert/Consultant IDA / 64380 gher Education Institutes for Post Direct Selection Direct 39,000.00 49,000.00 Signed 2020-05-06 2020-04-06 2020-05-16 2020-03-22 2020-07-20 2020-04-21 2021-01-16 Teaching & Learning Improved Teaching and Lear ning PK-HEC-172418-CS-CDS / Na Supporting Decentralized Hi tional Expert/Consultant Onli IDA / 64380 gher Education Institutes for Post Direct Selection Direct 10,400.00 27,114.79 Signed 2020-05-06 2020-04-06 2020-05-16 2020-04-18 2020-07-20 2020-04-20 2021-01-16 ne Instruction and Online Tec Improved Teaching and Lear hnology ning PK-HEC-173498-CS-CDS / Co Supporting Decentralized Hi ordinator for Educational Tec IDA / 64380 gher Education Institutes for Post Direct Selection Direct 5,000.00 4,544.08 Signed 2020-05-13 2020-05-14 2020-05-23 2020-05-28 2020-07-27 2020-06-06 2021-01-23 hnology Improved Teaching and Lear ning Page 3 PK-HEC-173499-CS-CDS / Co Supporting Decentralized Hi nsultant IT – Learning Manag IDA / 64380 gher Education Institutes for Post Direct Selection Direct 15,000.00 5,618.88 Terminated 2020-05-13 2020-05-14 2020-05-23 2020-05-28 2020-07-27 2020-06-06 2021-01-23 ement System Improved Teaching and Lear ning PK-HEC-173490-CS-INDV / Pr Supporting Decentralized Hi Individual Consult ogramme Specialist - Teachi IDA / 64380 gher Education Institutes for Post Open 200,000.00 0.00 Canceled 2020-05-13 2020-06-09 2020-06-14 2020-07-10 2024-06-22 ant Selection ng & Learning Improved Teaching and Lear ning PK-HEC-173489-CS-INDV / Pr Supporting Decentralized Hi Individual Consult ogramme Specialist – Resear IDA / 64380 gher Education Institutes for Post Open 200,000.00 0.00 Canceled 2020-05-13 2020-06-09 2020-06-14 2020-07-10 2024-06-30 ant Selection ch and Knowledge Managem Improved Teaching and Lear ent ning PK-HEC-173487-CS-INDV / Pr Supporting Decentralized Hi ogramme Specialist - Acade gher Education Institutes for Individual Consult IDA / 64380 Post Open 200,000.00 0.00 Canceled 2020-05-13 2020-06-09 2020-06-14 2020-07-10 2024-06-30 mic Governance, Leadership Improved Teaching and Lear ant Selection and Management in HEIs ning PK-HEC-173485-CS-INDV / Pr Supporting Decentralized Hi Individual Consult ogramme Coordinator – Inter IDA / 64380 gher Education Institutes for Post Open 200,000.00 0.00 Canceled 2020-05-13 2020-06-09 2020-06-14 2020-07-10 2024-06-30 ant Selection nationalisation Improved Teaching and Lear ning Capacity Building through Pa PK-HEC-134421-CS-INDV / Pr Individual Consult IDA / 64380 rtnerships, Project Managem Prior Open 360,000.00 0.00 Canceled 2019-09-16 2019-09-22 2019-10-12 2019-10-17 2019-10-23 2024-06-30 oject Coordinator ant Selection ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-173859-CS-INDV / Pr IDA / 64380 rtnerships, Project Managem Prior Direct Selection Direct 360,000.00 122,068.46 Signed 2020-05-19 2020-05-20 2020-05-29 2020-06-09 2020-08-02 2020-06-12 2024-06-30 oject Coordinator ent, Monitoring and Evaluati on PK-HEC-180214-CS-CDS / En Capacity Building through Pa vironmental Specialist for Ra IDA / 64380 rtnerships, Project Managem Post Direct Selection Direct 5,000.00 6,051.47 Signed 2020-06-16 2020-06-16 2020-06-26 2020-06-17 2020-07-11 2020-06-19 2020-09-09 pid Research & Innovation Ini ent, Monitoring and Evaluati tiative on PK-HEC-198929-CS-INDV / Pr Capacity Building through Pa Individual Consult ogram Specialist - Research IDA / 64380 rtnerships, Project Managem Post Open 50,000.00 0.00 Canceled 2020-10-09 2020-11-27 2020-12-18 2021-01-22 2023-01-22 ant Selection and Research Management ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-198952-CS-INDV / E Individual Consult IDA / 64380 rtnerships, Project Managem Post Open 100,000.00 56,403.51 Signed 2020-10-09 2020-08-14 2020-11-27 2021-04-06 2020-12-18 2021-04-06 2021-01-22 2021-04-15 2023-01-22 nvironmental Specialist ant Selection ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-198956-CS-INDV / S Individual Consult IDA / 64380 rtnerships, Project Managem Post Open 100,000.00 60,201.50 Signed 2020-10-09 2022-01-21 2020-11-27 2022-03-24 2020-12-18 2022-03-24 2021-01-22 2022-04-12 2021-07-21 ocial Development Specialist ant Selection ent, Monitoring and Evaluati on PK-HEC-198938-CS-INDV / Pr Capacity Building through Pa Individual Consult ogram Specialist - Teaching a IDA / 64380 rtnerships, Project Managem Post Open 50,000.00 0.00 Canceled 2020-10-09 2020-11-27 2020-12-18 2021-01-22 2023-01-22 ant Selection nd Learning ent, Monitoring and Evaluati on PK-HEC-198922-CS-INDV / Pr Capacity Building through Pa ogram Specialist - Academic rtnerships, Project Managem Individual Consult IDA / 64380 Post Open 50,000.00 0.00 Canceled 2020-10-09 2020-11-27 2020-12-18 2021-01-22 2023-01-22 Leadership, Governance and ent, Monitoring and Evaluati ant Selection Financial Management on PK-HEC-198916-CS-INDV / E Capacity Building through Pa Individual Consult ducational Technology Speci IDA / 64380 rtnerships, Project Managem Post Open 30,000.00 15,277.72 Terminated 2020-10-09 2020-08-15 2020-11-27 2020-12-09 2020-12-18 2020-12-10 2021-01-22 2020-12-11 2023-01-22 ant Selection alist ent, Monitoring and Evaluati on PK-HEC-198920-CS-INDV / K Capacity Building through Pa Individual Consult nowledge Management and IDA / 64380 rtnerships, Project Managem Post Open 30,000.00 34,535.97 Terminated 2020-10-09 2020-08-20 2020-11-27 2020-12-09 2020-12-18 2020-12-09 2021-01-22 2020-12-22 2023-01-22 ant Selection Communication Specialist ent, Monitoring and Evaluati on PK-HEC-202636-CS-INDV / N Capacity Building through Pa Individual Consult Pending Impleme ational Expert-Consultant Onl IDA / 64380 rtnerships, Project Managem Post Limited 5,500.00 0.00 2020-11-03 2020-11-08 2020-11-29 2021-01-03 2021-07-02 ant Selection ntation ine Instruction: Program Deli ent, Monitoring and Evaluati very on PK-HEC-202638-CS-INDV / N Capacity Building through Pa Individual Consult Pending Impleme ational Expert-Consultant Onl IDA / 64380 rtnerships, Project Managem Post Limited 5,500.00 0.00 2020-11-03 2020-11-08 2020-11-29 2021-01-03 2021-07-02 ant Selection ntation ine Instruction: Program Deli ent, Monitoring and Evaluati very on Capacity Building through Pa PK-HEC-208294-CS-INDV / Pr Individual Consult IDA / 64380 rtnerships, Project Managem Post Open 240,000.00 128,125.07 Signed 2020-12-07 2020-12-10 2021-01-02 2021-02-01 2021-01-07 2021-02-01 2021-01-13 2021-03-27 2024-03-28 oject Coordinator ant Selection ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-210837-CS-INDV / E Individual Consult Under Implement IDA / 64380 rtnerships, Project Managem Post Direct 4,000.00 0.00 2020-12-18 2020-12-01 2020-12-19 2020-12-19 2020-12-21 2021-02-19 nvironmental Specialist ant Selection ation ent, Monitoring and Evaluati on PK-HEC-212740-CS-INDV / Fi Capacity Building through Pa Individual Consult nancial Specialist- Resource IDA / 64380 rtnerships, Project Managem Post Open 40,000.00 0.00 Canceled 2021-01-07 2021-02-25 2021-03-02 2021-03-17 2023-03-17 ant Selection Mobilization ent, Monitoring and Evaluati on PK-HEC-212742-CS-INDV / Pr Capacity Building through Pa Individual Consult oject Specialist- Resource Mo IDA / 64380 rtnerships, Project Managem Post Open 100,000.00 0.00 Canceled 2021-01-07 2021-01-28 2021-02-02 2021-02-17 2026-01-24 ant Selection bilization ent, Monitoring and Evaluati on PK-HEC-212744-CS-INDV / Pr Capacity Building through Pa Individual Consult ogram Specialist- Resource M IDA / 64380 rtnerships, Project Managem Post Open 120,000.00 0.00 Canceled 2021-01-31 2021-03-12 2021-03-17 2021-04-01 2023-03-22 ant Selection obilization ent, Monitoring and Evaluati on PK-HEC-217176-CS-INDV / C Supporting Decentralized Hi Individual Consult onsultant Need Assessment IDA / 64380 gher Education Institutes for Post Limited 35,000.00 0.00 Canceled 2021-02-02 2021-02-07 2021-02-28 2021-04-04 2021-10-01 ant Selection Study QECs Improved Teaching and Lear ning Capacity Building through Pa PK-HEC-223755-CS-INDV / C Individual Consult IDA / 64380 rtnerships, Project Managem Post Limited 80,000.00 0.00 Canceled 2021-03-09 2021-02-15 2021-03-14 2021-05-05 2021-04-04 2021-05-09 2023-04-29 onsultant-Academics ant Selection ent, Monitoring and Evaluati on Supporting Decentralized Hi PK-HEC-223760-CS-INDV / C Individual Consult IDA / 64380 gher Education Institutes for Post Limited 45,000.00 37,904.48 Signed 2021-03-09 2021-02-15 2021-03-14 2021-05-05 2021-04-04 2021-05-05 2021-05-09 2021-07-02 2023-04-29 onsultant (Capacity Building) ant Selection Improved Teaching and Lear ning PK-HEC-223761-CS-INDV / C Supporting Decentralized Hi Individual Consult onsultant (Course Developm IDA / 64380 gher Education Institutes for Post Limited 45,000.00 40,446.04 Signed 2021-03-09 2021-02-15 2021-03-14 2021-05-05 2021-04-04 2021-05-05 2021-05-09 2021-06-08 2023-04-29 ant Selection ent) Improved Teaching and Lear ning Supporting Decentralized Hi PK-HEC-223781-CS-INDV / C Individual Consult IDA / 64380 gher Education Institutes for Post Limited 45,000.00 0.00 Canceled 2021-03-09 2021-02-15 2021-03-14 2021-05-05 2021-04-04 2021-05-09 2023-04-29 onsultant (Quality) ant Selection Improved Teaching and Lear ning Page 4 PK-HEC-223786-CS-INDV / C Nurturing Academic Excellen Individual Consult Pending Impleme IDA / 64380 Post Limited 35,000.00 0.00 2021-03-09 2021-03-14 2021-04-04 2021-05-09 2023-04-29 onsultant Research Grants ce in Strategic Sectors ant Selection ntation PK-HEC-223787-CS-INDV / C Nurturing Academic Excellen Individual Consult IDA / 64380 Post Limited 35,000.00 59,429.85 Signed 2021-03-09 2021-04-15 2021-03-14 2021-05-05 2021-04-04 2021-05-06 2021-05-09 2021-05-25 2023-04-29 onsultant Research Grants ce in Strategic Sectors ant Selection PK-HEC-223790-CS-INDV / C Nurturing Academic Excellen Individual Consult IDA / 64380 Post Limited 35,000.00 31,587.04 Signed 2021-03-09 2021-02-15 2021-03-14 2021-05-05 2021-04-04 2021-05-05 2021-05-09 2021-05-26 2023-04-29 onsultant Startups Ecosyste ce in Strategic Sectors ant Selection m PK-HEC-223791-CS-INDV / C Nurturing Academic Excellen Individual Consult IDA / 64380 Post Limited 30,000.00 0.00 Canceled 2021-03-09 2021-02-15 2021-03-14 2021-04-04 2021-05-09 2023-04-29 onsultant Innovators Seed Fu ce in Strategic Sectors ant Selection nd(ISF) PK-HEC-211642-CS-INDV / M Capacity Building through Pa Individual Consult onitoring & Evaluation Specia IDA / 64380 rtnerships, Project Managem Post Open 240,000.00 12,438.41 Terminated 2021-04-15 2021-04-23 2021-05-06 2021-10-15 2021-05-11 2021-11-19 2021-05-18 2021-11-20 2023-05-18 ant Selection list ent, Monitoring and Evaluati on PK-HEC-231594-CS-INDV / N Capacity Building through Pa Individual Consult ational Expert/Consultant Onl IDA / 64380 rtnerships, Project Managem Post Open 48,000.00 17,218.71 Signed 2021-04-27 2021-04-28 2021-05-26 2021-07-26 2021-05-31 2021-07-26 2021-06-04 2021-07-28 2022-05-30 ant Selection ine Instruction: Program Deli ent, Monitoring and Evaluati very on PK-HEC-231597-CS-INDV / In Capacity Building through Pa Individual Consult ternational Expert/Consultant IDA / 64380 rtnerships, Project Managem Post Open 60,000.00 42,000.00 Signed 2021-04-27 2021-04-28 2021-05-26 2021-07-26 2021-05-31 2021-07-26 2021-06-04 2021-07-28 2022-05-30 ant Selection Research, Teaching and Lear ent, Monitoring and Evaluati ning on PK-HEC-231598-CS-INDV / In Capacity Building through Pa ternational Expert/Consultant rtnerships, Project Managem Individual Consult IDA / 64380 Post Open 66,000.00 46,200.00 Signed 2021-04-27 2021-04-28 2021-05-26 2021-07-26 2021-05-31 2021-07-26 2021-06-04 2021-07-28 2022-05-30 Teaching, Research and Facu ent, Monitoring and Evaluati ant Selection lty Development on PK-HEC-231599-CS-INDV / N Capacity Building through Pa Individual Consult ational Expert/Consultant Onl IDA / 64380 rtnerships, Project Managem Post Open 18,000.00 18,000.00 Signed 2021-04-27 2021-04-28 2021-05-26 2021-07-26 2021-05-31 2021-07-26 2021-06-04 2021-07-28 2022-05-30 ant Selection ine Instruction and Online Te ent, Monitoring and Evaluati chnology on PK-HEC-269376-CS-INDV / C Supporting Decentralized Hi Individual Consult Under Implement onsultant Capacity Building - IDA / 64380 gher Education Institutes for Post Open 30,000.00 0.00 2021-12-20 2022-01-18 2022-01-18 2022-01-28 2022-02-12 2023-02-12 ant Selection ation UEP Improved Teaching and Lear ning PK-HEC-269379-CS-INDV / C Supporting Decentralized Hi Individual Consult Under Implement onsultant Capacity Building - IDA / 64380 gher Education Institutes for Post Open 30,000.00 0.00 2021-12-20 2022-01-18 2022-01-18 2022-08-26 2022-01-28 2022-08-26 2022-02-12 2023-02-12 ant Selection ation QECAC Improved Teaching and Lear ning Capacity Building through Pa PK-HEC-273516-CS-INDV / Pr Individual Consult Under Implement IDA / 64380 rtnerships, Project Managem Post Open 60,000.00 0.00 2022-01-18 2022-02-03 2022-03-09 2022-03-24 2022-03-14 2022-03-24 2022-03-24 2024-03-23 ogram Specialist ant Selection ation ent, Monitoring and Evaluati on PK-HEC-273524-CS-INDV / C Capacity Building through Pa Individual Consult ontract Management Speciali IDA / 64380 rtnerships, Project Managem Post Open 48,000.00 38,953.91 Signed 2022-01-18 2022-01-18 2022-03-09 2022-03-24 2022-03-19 2022-03-24 2022-03-29 2022-04-01 2022-06-13 ant Selection st ent, Monitoring and Evaluati on PK-HEC-280667-CS-INDV / E Capacity Building through Pa Individual Consult Under Implement ducation Technology Speciali IDA / 64380 rtnerships, Project Managem Post Open 40,000.00 0.00 2022-02-28 2022-04-14 2022-05-05 2022-06-09 2024-06-30 ant Selection ation st ent, Monitoring and Evaluati on PK-HEC-289626-CS-INDV / Pr Capacity Building through Pa Individual Consult ogram Specialist IT IDA / 64380 rtnerships, Project Managem Post Open 95,000.00 66,488.89 Signed 2022-04-15 2022-04-14 2022-05-20 2022-08-26 2022-05-25 2022-08-26 2022-05-31 2022-09-01 2024-06-30 ant Selection For Supporting Comp-3 &4 ent, Monitoring and Evaluati on PK-HEC-289627-CS-INDV / M Capacity Building through Pa Individual Consult Under Implement onitoring & Evaluation Specia IDA / 64380 rtnerships, Project Managem Post Open 70,000.00 0.00 2022-04-15 2022-04-14 2022-05-20 2022-05-25 2022-06-04 2024-06-03 ant Selection ation list ent, Monitoring and Evaluati on PK-HEC-289630-CS-INDV / C Improving access and qualit Individual Consult onsultant- University Autono IDA / 64380 y of remote learning and sup Post Open 24,000.00 23,602.41 Signed 2022-04-15 2022-04-14 2022-05-25 2022-08-26 2022-05-30 2022-08-26 2022-06-14 2022-08-30 2024-06-03 ant Selection my port to universities Capacity Building through Pa PK-HEC-313409-CS-INDV / Pr Individual Consult Open - Internationa Under Implement IDA / 64380 rtnerships, Project Managem Post 150,000.00 0.00 2022-09-01 2022-09-02 2022-10-04 2022-10-09 2022-10-15 2024-06-30 oject Coordinator ant Selection l ation ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-314935-CS-INDV / Pr Individual Consult Open - Internationa Under Implement IDA / 64380 rtnerships, Project Managem Post 100,000.00 0.00 2022-09-08 2022-10-03 2022-10-12 2022-12-16 2022-10-22 2022-11-01 2024-06-30 ogram Specialist- Academics ant Selection l ation ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-320705-CS-INDV / Pr Individual Consult Open - Internationa Under Implement IDA / 64380 rtnerships, Project Managem Post 60,000.00 0.00 2022-10-19 2022-10-11 2022-12-08 2022-12-13 2022-12-23 2024-06-30 ogram Specialist ant Selection l ation ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-330240-CS-INDV / Pr Individual Consult Under Implement IDA / 64380 rtnerships, Project Managem Post Open - National 100,000.00 0.00 2022-12-07 2022-12-12 2023-01-25 2023-02-15 2023-03-22 2024-06-30 ocurement Specialist ant Selection ation ent, Monitoring and Evaluati on PK-HEC-355464-CS-INDV / S Capacity Building through Pa Individual Consult Under Implement election of Contract & HR Ma IDA / 64380 rtnerships, Project Managem Post Open - National 30,000.00 0.00 2023-04-07 2023-04-07 2023-05-23 2023-06-06 2023-06-30 2024-06-30 ant Selection ation nagement Specialist ent, Monitoring and Evaluati on Page 5 PROCUREMENT PLAN (Textual Part) Project information: [Ethiopiacountry] [Program for Results Enhancing Shared Prosperity Through Equitable Services (ESPES) Project name] [P151432-number]] Project Implementation agency: [Channel One Programs Coordinating Directorate (COPCD)insert legal name] Date of the Procurement Plan: [24/02/2019insert date] Period covered by this Procurement Plan: [24/02/2019insert from – 31/05/2023to period] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Public Procurement and Property Administration Proclamation No. 649/2009, [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Ethiopia : Enhancing Shared Prosperity through Equitable Services PLAN General Information Country: Ethiopia 2019-02-26 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151432 GPN Date: 2020-03-04 Project Name: Enhancing Shared Prosperity through Equitable Services Loan / Credit No: IDA / 61310, IDA / D2290 MOFEC/Channel One Programs Coordinating Unit Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOFEC-COPCU-129556-G O-RFB / Procurement of 33 V Open - Internationa Single Stage - One E IDA / D2290 Prior Request for Bids 2,633,000.00 1,474,098.90 Signed 2020-01-28 2020-05-18 2020-02-27 2020-05-26 2020-04-13 2020-07-15 2020-05-18 2020-09-30 2020-06-22 2020-11-07 2021-02-17 ehicles for EIO,OFAG,MOF & l nvelope BOFED with field kits ET-MOFEC-COPCU-158455-G O-RFB / Procurement of MIS I Open - Internationa Single Stage - Two E Pending Impl IDA / D2290 Post Request for Bids 500,000.00 0.00 2020-08-17 2020-08-22 2020-10-03 2020-12-16 2021-01-20 2021-07-19 T equipment for Implementat l nvelope ementation ion of KPI at Federal and regi onal Basic Service ET-MOFEC-COPCU-158476-G O-RFB / Procurement of Offic Single Stage - One E Under Imple IDA / D2290 Post Request for Bids Open - National 377,827.00 0.00 2020-05-13 2020-05-11 2020-05-18 2020-05-13 2020-06-29 2020-07-29 2020-09-02 2021-04-30 e Equipment for WoFEDS and nvelope mentation Zonal Ethics and Anti Corrupt ion Branches ET-MOFEC-COPCU-158854-G O-RFB / Procurement of Offic Open - Internationa Single Stage - One E IDA / D2290 Prior Request for Bids 1,500,000.00 961,754.34 Signed 2020-04-14 2020-06-18 2020-04-19 2020-07-21 2020-05-31 2020-08-20 2020-06-30 2020-11-14 2020-08-04 2020-12-31 2021-04-01 e Equipment for Ministry of A l nvelope griculture Information Syste m (AGMIS) ET-MOFEC-COPCU-158863-G Open - Internationa Single Stage - One E O-RFB / Procurement of IT eq IDA / D2290 Prior Request for Bids 1,500,000.00 413,834.28 Signed 2020-05-20 2020-04-26 2020-05-25 2020-05-11 2020-07-06 2020-06-25 2020-08-05 2020-09-21 2020-09-09 2020-10-18 2021-05-07 l nvelope uipment for Ethiopia Road Au thority ET-MOFEC-COPCU-158926-G O-RFB / Procurement of IT eq Single Stage - One E Under Imple uipment for Scale upping of IDA / D2290 Post Request for Bids Open - National 200,000.00 0.00 2020-02-12 2020-05-11 2020-02-17 2020-05-13 2020-03-30 2020-04-29 2020-06-03 2020-11-30 nvelope mentation Data Center and establishme nt of Disaster Recovery Site ET-MOFEC-COPCU-166578-G O-DIR / Procurement of Video IDA / D2290 Post Direct Selection Direct 200,000.00 164,643.07 Signed 2020-03-30 2020-04-03 2020-04-04 2020-04-03 2020-05-09 2020-04-07 2020-07-08 conference Equipment with accessaries ET-MOFEC-COPCU-186947-G Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of Vide IDA / D2290 Post Limited 50,000.00 0.00 2020-08-24 2020-10-19 2020-12-18 tions nvelope ementation o Conference Equipment and related service ET-MOFEC-COPCU-186953-G O-RFB / Procurement of Lapt Single Stage - One E Pending Impl ops and Multipurpose Copier IDA / D2290 Post Request for Bids Open - National 75,000.00 0.00 2020-08-26 2020-08-31 2020-10-12 2020-11-11 2020-12-16 2021-06-14 nvelope ementation s for Federal Public Procurem ent and Property Administrati on Agency ET-MOFEC-COPCU-278820-G O-RFB / Supply ,Installation , Single Stage - One E Pending Impl Training and support of Case IDA / D2290 Post Request for Bids Open - National 168,000.00 0.00 2022-02-14 2022-02-19 2022-04-02 2022-05-02 2022-06-06 2022-12-03 nvelope ementation Management System for Ethi opia Institution of the Ombud sman (EOI) ET-MOFEC-COPCU-291039-G O-DIR / Procurement of vario IDA / D2290 Prior Direct Selection Direct 2,100,000.00 0.00 Signed 2022-06-21 2023-01-13 2022-06-26 2023-02-08 2022-07-31 2023-06-06 2023-01-27 us IT Equipment for conflict a ffected Zone and Woreda Fin ance Office ET-MOFEC-COPCU-318684-G Single Stage - One E Pending Impl O-RFB / Procurement Laptop IDA / D2290 Post Request for Bids Open - National 147,000.00 0.00 2022-10-24 2022-10-29 2022-12-10 2023-01-09 2023-02-13 2023-05-14 nvelope ementation Computers ET-MOFEC-COPCU-242283-G O-RFB / Procurement of vario Single Stage - One E IDA / D2290 Post Request for Bids Open - National 52,000.00 0.00 Canceled 2021-07-14 2021-07-19 2021-08-30 2021-09-29 2021-11-03 2022-05-02 us Office equipment for Wat nvelope er Development Commission ET-MOFEC-COPCU-318682-G Open - Internationa Single Stage - One E O-RFB / Procurement of hardt IDA / D2290 Prior Request for Bids 2,800,000.00 0.00 Signed 2022-10-26 2022-11-22 2022-10-31 2022-12-09 2022-12-12 2023-02-01 2023-01-11 2023-03-31 2023-02-15 2023-06-23 2023-08-14 l nvelope op Station Wagon Vehicles ET-MOFEC-COPCU-321033-G Request for Quota Single Stage - One E Under Imple O-RFQ / Procurement of Mid IDA / D2290 Post Limited 330,000.00 0.00 2022-10-31 2022-12-26 2023-03-26 tions nvelope mentation bus and Automobile ET-MOFEC-COPCU-321547-G O-RFB / Procurement of Serv er upgrading equipment for d Open - Internationa Single Stage - One E Pending Impl IDA / D2290 Post Request for Bids 284,000.00 0.00 2022-11-30 2022-12-05 2023-01-16 2023-02-15 2023-03-22 2023-09-18 igital system enhancement o l nvelope ementation f Ethics and Anti Corruption C ommission of Ethiopia (EACC ) ET-MOFEC-COPCU-323941-G O-RFB / Supply , Installation Single Stage - One E Under Imple & Commissioning of Data Ba IDA / D2290 Post Request for Bids Open - National 104,000.00 0.00 2022-11-22 2023-01-20 2022-11-27 2023-01-23 2023-01-08 2023-03-13 2023-02-07 2023-03-14 2023-09-10 nvelope mentation ckup and Storage related har dware and system software f or E-GP system Page 1 ET-MOFEC-COPCU-158915-G O-RFB / Procurement of IT an Open - Internationa Single Stage - One E IDA / D2290 Post Request for Bids 1,060,714.00 0.00 Canceled 2020-04-15 2020-04-20 2020-06-01 2020-07-01 2020-08-05 2021-04-02 d Office Equipment for (MoF, l nvelope BoFEC and Woreda) Finance ET-MOFEC-COPCU-158457-G O-RFB / Procurement of Offic Single Stage - One E IDA / D2290 Post Request for Bids Open - National 390,000.00 0.00 Canceled 2020-04-14 2020-04-19 2020-05-31 2020-06-30 2020-08-04 2021-01-31 e Equipment to Regional Ethi nvelope cs and Anti Corruption Comm ission ET-MOFEC-COPCU-186964-G O-RFP / Procurement of Offic e equipment(Laptop comput Request for Quota Single Stage - One E IDA / D2290 Post Limited 37,038.00 0.00 Canceled 2020-08-18 2020-10-07 2020-12-06 er, Desktop Computer, Flash tions nvelope Disk and Dlink) for Environm ent , Forest and Climate Cha nge Commission ET-MOFEC-COPCU-334162-G O-RFB / Supply and Installati Open - Internationa Single Stage - One E Under Imple IDA / D2290 Post Request for Bids 150,000.00 0.00 2023-01-10 2023-01-20 2023-01-15 2023-01-23 2023-02-26 2023-03-28 2023-05-02 2023-10-29 on of Elevator/Lift for Ministr l nvelope mentation y of Finance main building ET-MOFEC-COPCU-334165-G O-RFB / Procurement of Audi Open - Internationa Single Stage - One E Under Imple IDA / D2290 Post Request for Bids 340,000.00 0.00 2023-01-18 2023-01-20 2023-01-23 2023-01-23 2023-03-06 2023-03-14 2023-04-05 2023-05-10 2023-11-06 o Video Conference Infrastru l nvelope mentation cture Solution for OFAG ET-MOFEC-COPCU-334166-G O-RFB / Supply , Installation Open - Internationa Single Stage - One E Under Imple and Commissioning of Corres IDA / D2290 Post Request for Bids 378,000.00 0.00 2023-01-15 2023-01-20 2023-01-20 2023-01-23 2023-03-03 2023-04-02 2023-05-07 2023-11-03 l nvelope mentation pondence Management and Document management Syst em for OFAG ET-MOFEC-COPCU-321560-G O-RFB / Scaleup data center & establishment of audio & vi Open - Internationa Single Stage - One E IDA / D2290 Post Request for Bids 731,000.00 0.00 Canceled 2022-12-29 2023-01-03 2023-02-14 2023-03-16 2023-04-20 2023-10-17 deo conference solutions & d l nvelope igitalization and archiving of audit records, correspondenc es, and contents manageme nt ET-MOFEC-COPCU-334163-G O-RFB / Procurement of IT eq Open - Internationa Single Stage - One E Pending Impl IDA / D2290 Post Request for Bids 283,000.00 0.00 2023-01-30 2023-02-04 2023-03-18 2023-04-17 2023-05-22 2023-11-18 uipment for Digital System e l nvelope ementation nhancement of FEACC NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOFEC-COPCU-158908-N C-DIR / procurement of Mass Pending Impl media Service for disseminat IDA / D2290 Post Direct Selection Direct 111,112.00 0.00 2020-04-14 2020-04-19 2020-05-24 2021-05-24 ementation ion of budget , expenditure a nd basic service delivery sta ndard information ET-MOFEC-COPCU-321541-N C-RFQ / Media service procur Request for Quota Single Stage - One E Pending Impl IDA / D2290 Post Limited 58,400.00 0.00 2023-01-15 2023-03-12 2023-09-08 ement for design and executi tions nvelope ementation on of platform for citizen eng agement ET-MOFEC-COPCU-323942-N C-RFQ / Website Upgrading T Request for Quota Single Stage - One E Pending Impl IDA / D2290 Post Limited 50,000.00 0.00 2022-11-29 2023-01-24 2023-07-23 raining for MoF Information S tions nvelope ementation ystem Administration Staffs ET-MOFEC-COPCU-327020-N Request for Quota Single Stage - One E Pending Impl C-RFQ / Printing of EFY 2015 IDA / D2290 Post Limited 2,000.00 0.00 2022-12-03 2022-12-28 2023-01-17 tions nvelope ementation Citizen Budget information CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOFEC-COPCU-129904-C S-QCBS / Selection and empl Quality And Cost- Open - Internationa Under Implement IDA / D2290 Post 200,000.00 0.00 2020-04-21 2020-09-16 2020-05-12 2020-07-11 2021-04-08 2020-07-16 2021-05-18 2020-08-15 2021-11-03 2020-09-10 2021-07-08 2020-10-08 2021-02-05 oyment of consultancy Impac Based Selection l ation t assessment of FTA Initiative for MOF ET-MOFEC-COPCU-158438-C S-QCBS / Consultancy service Quality And Cost- Open - Internationa Under Implement IDA / D2290 Post 250,000.00 0.00 2020-07-23 2022-12-12 2020-08-13 2020-09-26 2023-03-20 2020-10-24 2020-11-23 2020-12-28 2021-02-01 2021-07-31 to Conduct Public Finance Ma Based Selection l ation nagement /PFM/ reform impa ct assessment ET-MOFEC-COPCU-158440-C S-QCBS / Specialized Consulti Quality And Cost- Open - Internationa Pending Impleme IDA / D2290 Prior 500,000.00 0.00 2020-06-23 2020-07-14 2020-08-27 2020-09-24 2020-10-24 2020-11-28 2021-01-02 2021-07-01 ng service for development Based Selection l ntation of MIS for KPI at Federal and Regional Basic Sectors ET-MOFEC-COPCU-250154-C S-QCBS / Consultancy Servic Quality And Cost- Under Implement IDA / D2290 Post Open - National 195,450.00 0.00 2021-09-13 2021-09-28 2021-10-04 2021-11-17 2023-02-25 2021-12-15 2023-02-01 2022-01-14 2023-02-24 2022-02-18 2023-04-28 2022-03-25 2022-09-21 e to undertake Study on GRM Based Selection ation effectiveness for EIO ET-MOFEC-COPCU-291024-C S-QCBS / Consultancy Firm S Quality And Cost- Pending Impleme IDA / D2290 Post Open - National 78,000.00 0.00 2022-06-29 2022-07-20 2022-09-02 2022-09-30 2022-10-30 2022-12-04 2023-01-08 2024-01-08 election for the Development Based Selection ntation of BOFED Website ET-MOFEC-COPCU-250153-C S-QCBS / Consultancy Servic Quality And Cost- e for Development of Integr IDA / D2290 Post Open - National 168,500.00 0.00 Canceled 2021-09-09 2021-09-30 2021-11-13 2021-12-11 2022-01-10 2022-02-14 2022-03-21 2023-03-21 Based Selection ated case management syste m for Ethiopia Institution of t he Ombudsman (EIO) Page 2 ET-MOFEC-COPCU-158852-C S-QCBS / Consultancy Servic Quality And Cost- Open - Internationa IDA / D2290 Post 300,000.00 0.00 Canceled 2020-05-20 2020-06-10 2020-07-24 2020-08-21 2020-09-20 2020-10-25 2020-11-29 2021-05-28 e to undertake pilot Survey o Based Selection l n Education Service Delivery phase 2 ET-MOFEC-COPCU-158479-C S-QCBS / Consultancy Servic Quality And Cost- IDA / D2290 Post Open - National 61,185.00 0.00 Canceled 2020-07-16 2020-06-16 2020-08-06 2020-09-19 2020-10-17 2020-11-16 2020-12-21 2021-01-25 2021-07-24 e to Prepare Sectorial ESIA g Based Selection uideline for Environmental C ommission ET-MOFEC-COPCU-321540-C S-QCBS / Consultancy service Quality And Cost- Pending Impleme IDA / D2290 Post Open - National 136,000.00 0.00 2022-12-01 2022-12-22 2023-02-04 2023-03-04 2023-04-03 2023-05-08 2023-06-12 2023-12-09 to undertake study on existin Based Selection ntation g CE platform efficiency, effe ctiveness ET-MOFEC-COPCU-321544-C S-QCBS / Consultancy service Quality And Cost- Open - Internationa Pending Impleme IDA / D2290 Post 250,000.00 0.00 2022-11-22 2022-12-13 2023-01-26 2023-02-23 2023-03-25 2023-04-29 2023-06-03 2023-11-30 for web site development an Based Selection l ntation d upgrading of Regional Fina nce ET-MOFEC-COPCU-321554-C S-QCBS / Consultancy service Quality And Cost- Pending Impleme for updating scope and functi IDA / D2290 Post Open - National 198,000.00 0.00 2023-01-30 2023-02-20 2023-04-05 2023-05-03 2023-06-02 2023-07-07 2023-08-11 2024-02-07 Based Selection ntation onality of WaSH Managemen t Information System ET-MOFEC-COPCU-321558-C S-QCBS / Consultancy Servic Quality And Cost- Pending Impleme e for conducting public expe IDA / D2290 Post Open - National 142,000.00 0.00 2023-01-17 2023-02-07 2023-03-23 2023-04-20 2023-05-20 2023-06-24 2023-07-29 2024-01-25 Based Selection ntation nditure tracking survey on na tional Health or Education Pr ogram ET-MOFEC-COPCU-323940-C Quality And Cost- Pending Impleme S-QCBS / Consultancy for De IDA / D2290 Post Open - National 132,000.00 0.00 2022-11-15 2022-12-06 2023-01-19 2023-02-16 2023-03-18 2023-04-22 2023-05-27 2023-11-23 Based Selection ntation velopment of E-Learning Platf orm for FPPA ET-MOFEC-COPCU-327012-C S-QCBS / Consultancy Servic Quality And Cost- Pending Impleme e for the Development of Dy IDA / D2290 Post Open - National 56,600.00 0.00 2022-11-30 2022-12-21 2023-02-03 2023-03-03 2023-04-02 2023-05-07 2023-06-11 2023-10-09 Based Selection ntation namic Website for Accountin g and Auditing Board of Ethio pia ET-MOFEC-COPCU-327023-C S-LCS / Consultancy Service f Least Cost Selecti Pending Impleme or the development of Brand IDA / D2290 Post Open - National 20,000.00 0.00 2022-12-01 2022-12-22 2023-02-04 2023-03-04 2023-04-03 2023-05-08 2023-06-12 2023-10-10 on ntation for Accounting and Auditing Board of Ethiopia (AABE) ET-MOFEC-COPCU-327034-C S-QCBS / Consultancy to Und Quality And Cost- Pending Impleme ertake study on the use of lo IDA / D2290 Post Open - National 58,400.00 0.00 2022-12-30 2023-01-20 2023-03-05 2023-04-02 2023-05-02 2023-06-06 2023-07-11 2023-10-09 Based Selection ntation cal media to promote social a ccountability to improve basi c service delivery ET-MOFEC-COPCU-158860-C S-QCBS / Consultancy Servic e firm to provide support Wat Quality And Cost- Open - Internationa IDA / D2290 Prior 517,936.00 0.00 Canceled 2020-09-15 2020-10-06 2020-11-19 2020-12-17 2021-01-16 2021-02-20 2021-03-27 2022-03-27 er Development Commission Based Selection l on updating annual inventory (NWI2) and Data Verification ET-MOFEC-COPCU-158439-C S-QCBS / Consultancy Servic e to conduct assessment and Quality And Cost- Open - Internationa identify gap and prepare Gui IDA / D2290 Prior 500,000.00 0.00 Canceled 2020-07-16 2020-08-06 2020-09-19 2020-10-17 2020-11-16 2020-12-21 2021-01-25 2021-07-24 Based Selection l deline to address gaps in pro curement process, complaint handling and procurement A udit ET-MOFEC-COPCU-158478-C S-QCBS / Consultancy Servic e to Prepare National Environ Quality And Cost- mental Audit Guideline Stand IDA / D2290 Post Open - National 50,438.00 0.00 Canceled 2020-04-20 2020-06-16 2020-05-11 2020-06-24 2020-07-22 2020-08-21 2020-09-25 2020-10-30 2021-04-28 Based Selection ards and Environmental and Social Management plan fra mework for Environmental C ommission ET-MOFEC-COPCU-158436-C S-QCBS / Consultancy Servic Quality And Cost- Open - Internationa e to undertake study on the IDA / D2290 Post 200,000.00 0.00 Canceled 2020-04-17 2020-05-08 2020-06-21 2020-07-19 2020-08-18 2020-09-22 2020-10-27 2021-04-25 Based Selection l move towards International P ublic Sectors Accounting Sta ndard (IPSAS) ET-MOFEC-COPCU-158437-C S-QCBS / Consultancy Servic Quality And Cost- e providing firm for customizi IDA / D2290 Post Open - National 50,000.00 0.00 Canceled 2020-07-07 2020-07-28 2020-09-10 2020-10-08 2020-11-07 2020-12-12 2021-01-16 2021-05-16 Based Selection ng the Public Financial Mana gement strategy for MoF ET-MOFEC-COPCU-321967-C Quality And Cost- S-QCBS / Website Developme IDA / D2290 Post Open - National 250,000.00 0.00 Canceled 2022-11-08 2022-11-29 2023-01-12 2023-02-09 2023-03-11 2023-04-15 2023-05-20 2023-11-16 Based Selection nt and upgrading for Regions ET-MOFEC-COPCU-334172-C S-LCS / Consultancy Service f Least Cost Selecti Pending Impleme IDA / D2290 Post Open - National 19,000.00 0.00 2023-01-13 2023-02-03 2023-03-19 2023-04-16 2023-05-16 2023-06-20 2023-07-25 2024-01-21 or the Development of Brand on ntation and Branding Strategy for AA BE ET-MOFEC-COPCU-336276-C S-QCBS / Consultancy Servic Quality And Cost- Under Implement IDA / D2290 Post Open - National 100,000.00 0.00 2023-01-24 2023-01-30 2023-02-14 2023-03-30 2023-03-19 2023-04-27 2023-05-25 2023-05-27 2023-07-01 2023-08-05 2024-02-01 e for Program Based Budget Based Selection ation Rollout to Pilot Regions ET-MOFEC-COPCU-363858-C S-QCBS / Consultancy service Quality And Cost- Under Implement firm Selection for conducting IDA / D2290 Post Open - National 150,000.00 0.00 2023-05-31 2023-05-31 2023-06-21 2023-08-04 2023-09-01 2023-10-01 2023-11-05 2023-12-10 2024-06-07 Based Selection ation Water Sector Public Expendit ure Tracking Survey INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Page 3 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOFEC-COPCU-101801-C S-CDS / Consultant Service to IDA / 61310 Post Direct Selection Direct 80,000.00 59,916.10 Completed 2019-02-19 2019-03-04 2019-03-01 2019-03-15 2019-03-23 2019-03-18 2019-05-22 2019-06-28 prepare PBSIII Implementatio n Completion Report ET-MOFEC-COPCU-186933-C S-CDS / consulancy Service f IDA / D2290 Post Direct Selection Direct 120,000.00 106,361.92 Signed 2020-08-18 2020-08-14 2020-08-28 2020-09-30 2020-11-01 2021-04-14 2021-04-30 or Conducting Assessment o n Oversight Function of FPPA ET-MOFEC-COPCU-202819-C Individual Consult Under Implement S-INDV / Senior Inter - Gover IDA / D2290 Post Limited 25,000.00 0.00 2020-11-05 2020-11-08 2020-11-10 2021-02-11 2020-12-01 2021-01-05 2021-03-06 ant Selection ation nmental Fiscal Transfer Natio nal Consultant ET-MOFEC-COPCU-202820-C Individual Consult Under Implement S-INDV / Lead inter governm IDA / D2290 Post Limited 30,000.00 0.00 2020-11-05 2020-11-08 2020-11-10 2020-12-01 2021-01-05 2021-03-06 ant Selection ation ental fiscal transfer national consultant ET-MOFEC-COPCU-242287-C S-CDS / Consultancy for the Under Implement IDA / D2290 Post Direct Selection Direct 50,000.00 0.00 2021-07-12 2021-07-09 2021-07-22 2021-08-12 2021-09-25 2022-03-24 Development of KPI Web bas ation ed system for FPPA ET-MOFEC-COPCU-248691-C S-INDV / Constancy Service f or the preparation stakehold Individual Consult Under Implement er engagement plan , labor IDA / D2290 Post Limited 30,000.00 0.00 2021-08-24 2021-08-25 2021-08-29 2021-09-13 2021-10-08 2022-01-06 ant Selection ation Management Procedure and conduct Social Assessment a nd prepare underserved local community planning framew ork ET-MOFEC-COPCU-250156-C S-CDS / Consultancy Service Under Implement for Item definition, Classificat IDA / D2290 Post Direct Selection Direct 100,000.00 0.00 2021-09-13 2021-09-28 2021-09-23 2021-10-04 2021-11-27 2022-05-26 ation ion , adaptation, translation a nd mapping of UNSPCS ET-MOFEC-COPCU-300644-C S-INDV / Recruitment of cons Individual Consult IDA / D2290 Post Direct 70,000.00 36,000.00 Signed 2022-06-25 2022-06-22 2022-07-05 2022-04-28 2022-07-15 2022-06-27 2022-08-08 2022-07-09 2022-10-07 ultant to Prepare PFM project ant Selection Implementation completion R eport (ICR) ET-MOFEC-COPCU-318942-N C-DIR / E-Gp Software further Under Implement IDA / D2290 Prior Direct Selection Direct - National 566,000.00 0.00 2022-10-27 2022-10-28 2022-11-06 2022-12-02 2023-01-10 2025-01-09 enhancement and rollout of t ation he System to Procuring Entiti es ET-MOFEC-COPCU-323932-C S-INDV / Recruitment of Audi Individual Consult Under Implement IDA / D2290 Post Open - National 36,000.00 0.00 2022-11-09 2022-11-24 2022-12-28 2023-01-18 2023-02-22 2024-02-22 t Quality Assurance review A ant Selection ation dvisor and coordinator ET-MOFEC-COPCU-323933-C Individual Consult S-INDV / Recruitment of Audi IDA / D2290 Post Open - National 36,000.00 0.00 Under Review 2022-11-14 2022-11-24 2023-01-02 2023-01-23 2023-02-27 2024-02-27 ant Selection t Quality Assurance review C onsultant ET-MOFEC-COPCU-323935-C S-INDV / Recruitment of Fina Individual Consult Under Implement ncial report review advisor a IDA / D2290 Post Open - National 36,000.00 0.00 2022-11-15 2022-11-24 2023-01-03 2023-01-24 2023-02-28 2024-02-28 ant Selection ation nd consultant for Accounting and Audit Board of Ethiopia ( AABE) ET-MOFEC-COPCU-323937-C S-INDV / Recruitment of Fina Individual Consult Under Implement IDA / D2290 Post Open - National 36,000.00 0.00 2022-11-17 2022-11-24 2023-01-05 2023-04-26 2023-01-26 2023-04-19 2023-03-02 2024-03-01 ncial Report Review Consulta ant Selection ation nt for Accounting and Audit B oard of Ethiopia (AABE) ET-MOFEC-COPCU-327036-C S-INDV / Recruitment of cons Individual Consult Pending Impleme IDA / D2290 Post Open - National 38,000.00 0.00 2022-12-26 2023-02-13 2023-03-06 2023-04-10 2023-07-09 ultant for the preparation of ant Selection ntation Strategic Environmental Asse ssment (SEA) ET-MOFEC-COPCU-158456-C S-INDV / Recruitment of Local expert to develop a training Individual Consult IDA / D2290 Post Limited 30,000.00 0.00 Canceled 2020-04-15 2020-04-20 2020-05-11 2020-06-15 2020-12-12 module and provide Training ant Selection of trainer of Federal and Regi onal Ethics and Anti-Corrupti on Commission ET-MOFEC-COPCU-158477-C S-INDV / Recruitment of Cons ultant to develop a training Individual Consult IDA / D2290 Post Limited 20,000.00 0.00 Canceled 2020-04-14 2020-04-19 2020-05-10 2020-06-14 2020-12-11 module and Provide training ant Selection on asset registration, conflict of interest , public disclose, v erification and illicit enrichm ent ET-MOFEC-COPCU-290997-C S-INDV / Consultancy Service Individual Consult IDA / D2290 Post Open 30,000.00 0.00 Canceled 2022-06-22 2022-07-29 2022-08-10 2022-08-31 2022-10-05 2023-04-03 to Roll Out Program Budgetin ant Selection g to Regions and City Admini stration. ET-MOFEC-COPCU-338803-C S-INDV / Consultancy service Individual Consult IDA / D2290 Post Open - National 39,000.00 0.00 Signed 2023-01-27 2023-01-30 2023-03-17 2023-02-13 2023-04-07 2023-03-21 2023-05-12 2023-11-08 to prepare National Sterategi ant Selection c Environmental Assessment (SEA) Guidline Page 4 PROCUREMENT PLAN Project information: South Asia, Bangladesh, Nepal, Pakistan; Climate Adaptation and Resilience for South Asia (CARE) P171054 Project Implementation agency: Regional Integrated Multi-Hazard Early Warning System (RIMES) Date of the Procurement Plan: 30March 2020 Period covered by this Procurement Plan: Jul 2020 – Dec 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the project. This textual part, along with the Procurement Plan tables in STEP, constitute the Procurement Plan for the project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. Agency’s Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market, the country’s own procurement procedures may be used. Under this project, in place of a country’s procurement procedures, RIMES’ open tender procedure as set forth in the RIMES’ Procurement Manual may be used when the local market is approached, subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) Only the model procurement documents for Open Tender Procedure agreed with the World Bank shall be used for bidding. 2) Procurement will be open to eligible firms from any country. This eligibility shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts. When RIMES’ other procurement arrangements other than open competitive procurement arrangements are applied, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: - Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations - Not Applicable Selection Methods and Prior Review Thresholds RIMES will be responsible for all procurements under this procurement plan. Selection methods indicated in Table 1 will be used for procurement under the project. Appropriate thresholds applicable to the project with ‘substantial risk’ rating have been provided. Table 1 Selection Methods to Be Used in the Project Contracts Subject to Selection Method Expenditure Contract Value Prior Review (thresholds as Category (threshold) (thresholds as guidance) mandatory) Works ≥US$5,000,000 Request for Bids - All contracts above including International US$ 10,000,000 turnkey, ≥US$200,000, Request for Bids -Local supply and =1,000,000 All Contracts 2. ICB (Works/Supply & >=10,000,000 All Contracts Installation) 3. ICB (Non-Consultant >=500,000 All Contracts Services) 4. Direct Contracting All Values All Contracts 5. NCB (Goods) <=1,000,000 All Contracts 6. NCB (Works) <=10,000,000 All Contracts 7. Shopping <=100,000 All Contracts (a) List of contract Packages which will be procured following ICB and Direct contracting. (b) ICB Contracts estimated to cost above US$500,000 equivalent or more per Contract and all Direct Contracting will be subject to prior review by the Bank. 6. Prequalification: Nil 7. Proposed Procedures for CDD Components (as per paragraph 3.17 of the Guidelines): NA Reference to (if any) Project Operational/Procurement Manual: The Procurement Plan will also form part of the Project Implementation Manual. Any Other Special Procurement Arrangements: (including advance procurement and retroactive financing, if applicable): N/A. 8. Procurement Packages with Methods and Time Schedule. 9. Procurement Packages with Methods and Time Schedule for Goods and Works Procurement Reviews and Thresholds Table 2.4. Procurement of Goods and Works and Non-consulting Services Prior Review Threshold Procurement Method Comments (US$) 1 NCB (goods) packages Above 750,000 All 2 Non-consultant Services packages Above 750,000 All 3 Shopping (goods) Below 100,000 None 4 Shopping (works) Below 200,000 None Summary of the procurement packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement). 18-Month Procurement Plan for Goods and Works Contract Original Prior Expected Activi Type Procureme or Estimated ty List of Time nt Estimate Proposal Completio Post n Contrac Revie Submissi # ts Based or Type (US$, w on Dates Lump Sum thousands) Dates Equipmen Lump July 1, 1 t Sum Not 2,000.00 Prior 2017 September for Stated 29, 2017 vocationa l training Lump 2 Office Sum NS 200.00 Post June 1, 30 August, Equipmen t 2017 2017 for MinDiver and other agencies Solar Lump 3 System Sum NS 50.00 Post August 1, October 30, system for 2017 2017 NGSA Lump 5 Motor Sum NS 75.00 Prior June 1, August 30, vehicles - 2017 2017 Saloon Cars (6) Lump 6 Motor Sum NS 175.00 Prior May 1, July 30, vehicles - 4 2017 2017 ×4 (seven) Completi 7 on Bill of NS 70.00 Post of the Quantities dimensio n stone laborator y in Kaduna Selection of Consultants Prior review threshold. Selection decisions subject to prior review by the World Bank as stated in the Procurement Regulations. Selections Subject to Prior Review by the World Bank Prior Review Threshold Selection Method (US$) Comments Competitive Methods 1. (Firms) Above 300,000 2. Single Source (Firms) All 3. Individual Above 100,000 41. Short list consisting entirely of national consultants. A short list of consultants for services estimated to cost less than US$300,000 equivalent per contract may consist entirely of national consultants. Consultancy Assignments with Selection Methods and Time Schedule 18-Month Procurement Plan for Consultancy Contract Original Prior Expected Activit Procur or Estimated y List of Type Time Estimate Proposal Completio Contracts ement Post Submissio n # Based or (US$, n Type Review Dates thousands Lump Sum ) Dates Consultancies May 1, A1-1.1 Functional analysis Lump Sum QCBS 1,000.00 Prior 2017 October 28, within the MMSD, its 2018 associated agencies, and other MDAs based on identifying and reviewing the workflows and information flows A1-1.2 Upgrading and Lump Sum SS 440.00 Prior November June 29, automation of the 1, 2017 2018 MCO Review and update May 6, A1-2.1 of Lump Sum QCBS 600.00 Prior 2017 May 1, 2019 the NMMA, 2007 Assisting the GoN A1-4.1 to Lump Sum QCBS 250.00 Post November October 27, build the required 1, 2017 2018 technical skills and managerial capabilities to service and develop the mining sector Design and May 1, A1-7.1 develop a Lump Sum IC 300.00 Prior 2017 March 27, mechanism for citizen 2018 engagement and social accountability in the MinDiver project and the mining sector Contract Original Prior Expected Activit Procur or Estimated y List of Type Time Estimate Proposal Completio Contracts ement Post Submissio n # Based or (US$, n Type Review Dates thousands Lump Sum ) Dates Geological May 1, A2-1-3.1 mapping, Lump Sum QCBS 14,000.00 Prior 2017 December GIS geodata base, 22, 2018 mapping, and reinterpretation of data, and mineral prospectivity targeting May 1, A2-1.2 TA on exploration Lump Sum CQ 150.00 Post 2017 August 24, embedded within the 2018 NGSA Scoping analysis A3-1.1 and Lump Sum QCBS 400.00 Prior September November strategy development 1, 2017 25, 2018 to create the basis for reintroducing and/or providing vocational training to achieve excellence for the training of the Government's technical staff as well as private sector (national pole) Analyze and design A3-1.2 a Lump Sum CQ 180.00 Post November August 28, program to address 1, 2017 2018 the skill gap in the domestic mining industry Design and A3-1.3 implement Lump Sum IC 100.00 Post November April 30, partnership program 1, 2017 2018 between the MMSD, Nigerian universities, and the NGSA on selected topics Assess and A3-1.4 develop Lump Sum CQ 150.00 Post November November policy and strategy for 1, 2017 26, 2018 achieving local content in Nigerian mining sector A4-1.1 Update SESA and Lump Sum CQ 150.00 Post July 1, 2017 April 27, prepare action plan for 2018 implementation of recommendations May 1, A4-2.1 Phase 1: Address Lump Sum QCBS 250.00 Post 2017 October 28, potential medical 2018 geology issues arising from interaction between geological Contract Original Prior Expected Activit Procur or Estimated y List of Type Time Estimate Proposal Completio Contracts ement Post Submissio n # Based or (US$, n Type Review Dates thousands Lump Sum ) Dates background and its influence on the plants, animals, and humans to explore general mining- related health impacts. Support the June 1, A4-5.1 creation Lump Sum CQ 250.00 Post 2017 January 27, of opportunities for 2018 women and gender mainstreaming in the mining sector June 1, B1-1-3.1 Providing ASM Lump Sum QCBS 2,800.00 Prior 2017 November inventory, 28, 2018 operations/activitie s to assess scale and extent B3-1.2 Analyze economic Lump Sum QCBS 200.00 Post January 1, December drivers linking supply 2017 27, 2017 of industrial minerals with demand for construction and industrial materials; analyzing benefit sharing aspects (different stages of the value chain) institutional and governance. Needs assessment May 1, B3-1.3 and Lump Sum QCBS 4,120.00 Prior 2017 April 26, evaluation for 2018 accrediting and certifying laboratories including operationalization geological research laboratories December B3-1.4 Development of Lump Sum QCBS 500.00 Prior 1, November support action to 2017 26, 2018 improve the metallurgical and steel Inspectorate including an initial baseline study B4-1.1 Analysis and Lump Sum QCBS 540.00 Prior November October 27, development of 1, 2017 2018 strategies for addressing access to Contract Original Prior Expected Activit Procur or Estimated y List of Type Time Estimate Proposal Completio Contracts ement Post Submissio n # Based or (US$, n Type Review Dates thousands Lump Sum ) Dates finances constraints for local ASM, junior and medium scale companies Assess the SMDF B4-1.2 and Lump Sum QCBS 600.00 Prior March 1, November provide 2018 26, 2018 recommendations for its restructuring and operationalization, covering governance, structure, organization, strategies, and operations June 1, B4-1.3 Assist in building Lump Sum QCBS 600.00 Prior 2017 November capacity for financial 28, 2018 institutions, public and semipublic bodies through the Bankers Committee, in understanding of mining financing, preparation of bankable FS, business plans, and marketing June 1, B5-1.1 Initial review and Lump Sum QCBS 3,000.00 Prior 2017 November development of 28, 2018 potential assets in different mining cycle stages to select some Mineral Assets, and Mining Operators requiring Support, to bring those Assets to a higher Level or Advancing transactions on specific Assets. B5-1.2 Preliminary Lump Sum IC 40.00 Post November December identification of ‘proof 1, 2017 26, 2018 of concept’ investment May 1, February B5-2.1 Preliminary Lump Sum CQ 180.00 Post 2017 25, assessment and 2018 transaction advisory services for State Own Enterprise NIOMCO Consultancy May 1, A2-2.2 services Lump Sum IC 150.00 Post 2017 January 26, Contract Original Prior Expected Activit Procur or Estimated y List of Type Time Estimate Proposal Completio Contracts ement Post Submissio n # Based or (US$, n Type Review Dates thousands Lump Sum ) Dates for review of legal 2018 framework Consultancy May 1, A1-5.1 services Lump Sum IC 75.00 Post 2017 January 26, for identifying revenue 2018 leakages, strengthening the administrative system, and oversight of revenue assessment and collection Consultancy May 1, B5-1.1 service for Lump Sum IC 400.00 Prior 2017 January 26, identifying prospective 2018 mineral targets and mining assets to be analyzed as candidates for transaction processes and investment promotion. (Geological Analyst) Technical expert C1-1 for Lump Sum IC 600.00 Prior n.a. October 23, the project (1 and 2) 2018 Procurement Time C1-2 Specialist based IC 75.00 Post n.a. October 23, 2018 Time C1-3 M&E Specialist based IC 75.00 Post n.a. October 23, 2018 Time C1-4 Project Coordinator based IC 120.00 Post n.a. October 23, 2018 PMO (for C1-5 subsequent Lump Sum QCBS 1,500.00 Prior n.a. October 23, months) 2018 Note: IC = Individual Consultant; QCBS = Quality- and Cost-Based Selection; SS = Single- Source Selection. PROCUREMENT Nigeria : Nigeria: Mineral Sector Support for Economic Diversification Project (MinDiver) PLAN General Information Country: Nigeria 2018-02-13 Bank’s Approval Date of the Original Procurement Plan: 2023-05-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P159761 GPN Date: 2017-12-27 Project Name: Nigeria: Mineral Sector Support for Economic Diversification Project (MinDiver) Loan / Credit No: IDA / 59900, IDA / V0270 Mineral Sector Support for Economic Diversification Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-MINDIVER-107430-CW-R Facilitating Downstream Sec FQ / Refurbishment of Buildin Request for Quota Single Stage - One E 2020-01-0 IDA / 59900 tor Development & Enhancin Post Limited 25,000.00 26,267.17 Signed 2019-05-14 2019-05-10 2019-07-09 2019-06-20 g in JOS zones of the Mining tions nvelope 5 g Competitiveness Cadastre Office for online ap plication NG-MINDIVER-107432-CW-R FQ / MAIDUGURI, Refurbishm Facilitating Downstream Sec Request for Quota Single Stage - One E 2019-12-2 ent of Identified Building in 6 IDA / 59900 tor Development & Enhancin Post Limited 25,000.00 27,082.68 Completed 2019-04-29 2019-05-10 2019-06-24 2019-06-20 tions nvelope 1 Geopolitical zones of the Mini g Competitiveness ng Cadastre for Online applic ation NG-MINDIVER-107434-CW-R FQ / KADUNA: Refurbishment Facilitating Downstream Sec Request for Quota Single Stage - One E 2019-12-2 of the identified building in K IDA / 59900 tor Development & Enhancin Post Limited 25,000.00 28,187.06 Signed 2019-04-29 2019-05-10 2019-06-24 2019-06-20 tions nvelope 1 aduna Geopolitical area of th g Competitiveness e Mining Cadastre office for o nline application. NG-MINDIVER-107435-CW-R FQ / ENUGU: Refurbishment Facilitating Downstream Sec Request for Quota Single Stage - One E 2019-12-2 of the identified building in E IDA / 59900 tor Development & Enhancin Post Limited 25,000.00 34,144.43 Signed 2019-04-29 2019-06-10 2019-06-24 2019-06-20 tions nvelope 1 nugu Geopolitical area of the g Competitiveness Mining Cadastre office for onl ine application. MINDIVER/RFB/W-004/18 / C Establishing a Strong Found Single Stage - One E 2018-10-2 onstruction of feeder roads a IDA / 59900 ation for Mining Sector Deve Post Request for Bids Open - National 2,000,000.00 0.00 Canceled 2018-01-01 2018-01-06 2018-02-17 2018-03-19 2018-04-23 nvelope 0 nd bridges under proof of co lopment ncept NG-MINDIVER-107436-CW-R FQ / BENIN: Refurbishment of Facilitating Downstream Sec Request for Quota Single Stage - One E Under Imple 2020-04-0 the identified building in Beni IDA / 59900 tor Development & Enhancin Post Limited 60,000.00 0.00 2019-08-14 2019-05-17 2019-10-09 tions nvelope mentation 6 n Geopolitical area of the Min g Competitiveness ing Cadastre office for online application. NG-MINDIVER-107433-CW-R FQ / IBADAN: Refurbishment Facilitating Downstream Sec Request for Quota Single Stage - One E 2020-04-0 of the identified building in Ib IDA / 59900 tor Development & Enhancin Post Limited 50,000.00 41,825.32 Signed 2019-08-11 2019-05-10 2019-10-06 2019-06-20 tions nvelope 3 adan Geopolitical area of the g Competitiveness Mining Cadastre office for onl ine application. NG-MINDIVER-156832-CW-R Facilitating Downstream Sec FB / Renovation of National S Single Stage - One E 2020-11-2 IDA / 59900 tor Development & Enhancin Prior Request for Bids Limited 550,000.00 0.00 Canceled 2020-02-10 2020-02-15 2020-03-28 2020-04-27 2020-06-01 teel Raw Material and Explor nvelope 8 g Competitiveness ation Agency (NSRMEA), Kad una NG-MINDIVER-156221-CW-R FQ / Renovation of Server Ro oms at the Nigeria Geological Facilitating Downstream Sec Request for Quota Single Stage - One E Pending Imp 2020-05-2 Survey Agency (NGSA) and T IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 0.00 2020-02-12 2020-04-08 tions nvelope lementation 3 he National Steel Raw Materi g Competitiveness al and Exploration Agency (N SRMEA) for the delivery of Ni geria Geodata centre in both Location NG-MINDIVER-156372-CW-R Facilitating Downstream Sec Single Stage - One E 2020-11-2 FB / Renovation of National M IDA / 59900 tor Development & Enhancin Prior Request for Bids Limited 600,000.00 0.00 Canceled 2020-02-06 2020-02-11 2020-03-24 2020-04-23 2020-05-28 nvelope 4 etallurgical Development cen g Competitiveness tre (NMDC), Jos NG-MINDIVER-153-CW-RFB / Facilitating Downstream Sec Single Stage - One E 2020-07-0 Renovation of National Metall IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 700,000.00 0.00 Canceled 2019-09-15 2019-09-20 2019-11-01 2019-12-01 2020-01-05 nvelope 3 urgy Development Centre (N g Competitiveness MDC) – Jos. MINDIVER/RFB/W-001/18 / R Facilitating Downstream Sec Single Stage - One E 2018-10-2 enovation of Labouratory (N IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 500,000.00 0.00 Canceled 2018-01-01 2018-01-06 2018-02-17 2018-03-19 2018-04-23 nvelope 0 GSA Kaduna) g Competitiveness NG-MINDIVER-156373-CW-R Facilitating Downstream Sec FB / Renovation of Laborator Single Stage - One E 2021-01-2 IDA / 59900 tor Development & Enhancin Prior Request for Bids Limited 550,000.00 0.00 Canceled 2020-02-10 2020-02-15 2020-03-28 2020-04-27 2020-06-01 y for Nigeria Geological Surv nvelope 7 g Competitiveness ey Agency (NGSA) Laborator y, Kaduna. NG-MINDIVER-156374-CW-R Facilitating Downstream Sec Single Stage - One E 2021-01-3 FB / Renovation of Nigeria Ins IDA / 59900 tor Development & Enhancin Prior Request for Bids Limited 630,000.00 0.00 Canceled 2020-02-13 2020-02-18 2020-03-31 2020-04-30 2020-06-04 nvelope 0 titute of Mining and Geoscien g Competitiveness ces (NIMG), Jos MINDIVER/RFB/W-003/18 / C Facilitating Downstream Sec Single Stage - One E 2018-10-2 ompletion of the dimension s IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 500,000.00 0.00 Canceled 2018-01-01 2018-01-06 2018-02-17 2018-03-19 2018-04-23 nvelope 0 tone labouratory in Kaduna g Competitiveness NG-MINDIVER-167847-CW-R Facilitating Downstream Sec FB / Renovation of National S Single Stage - One E Under Imple 2021-03-2 IDA / 59900 tor Development & Enhancin Post Request for Bids Limited 550,000.00 0.00 2020-04-10 2020-04-20 2020-04-15 2020-05-27 2020-06-26 2020-07-31 teel Raw Material and Explor nvelope mentation 8 g Competitiveness ation Agency (NSRMEA) – Ka dunA. NG-MINDIVER-167848-CW-R Facilitating Downstream Sec FB / Renovation of Nigeria Ge Single Stage - One E Under Imple 2021-04-0 IDA / 59900 tor Development & Enhancin Post Request for Bids Limited 550,000.00 0.00 2020-04-17 2020-05-08 2020-04-22 2020-06-03 2020-07-03 2020-08-07 ological Survey Agency Labo nvelope mentation 4 g Competitiveness uratory (NGSA Kaduna) NG-MINDIVER-167849-CW-R Facilitating Downstream Sec Single Stage - One E Under Imple 2021-03-2 FB / Renovation of National M IDA / 59900 tor Development & Enhancin Post Request for Bids Limited 600,000.00 0.00 2020-04-10 2020-04-08 2020-04-15 2020-05-27 2020-06-26 2020-07-31 nvelope mentation 8 etallurgy Development Centr g Competitiveness e (NMDC) – Jos. NG-MINDIVER-167850-CW-R Facilitating Downstream Sec Single Stage - One E Under Imple 2021-03-3 FB / Renovation of Nigerian I IDA / 59900 tor Development & Enhancin Post Request for Bids Limited 630,000.00 0.00 2020-04-13 2020-03-31 2020-04-18 2020-05-11 2020-05-30 2020-06-29 2020-08-03 nvelope mentation 1 nstitute of Mining and Geosci g Competitiveness ences (NIMG), Jos Page 1 NG-MINDIVER-168710-CW-R FQ / Renovation of facilities f Facilitating Downstream Sec Request for Quota Single Stage - One E Pending Imp 2020-12-2 or the training of candidates IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 0.00 2020-04-28 2020-06-23 tions nvelope lementation 0 for the development of Gems g Competitiveness tone and Jewellery industry. NG-MINDIVER-103111-CW-R Facilitating Downstream Sec Single Stage - One E 2020-03-0 FB / Rehabilitation of Ladi Kw IDA / 59900 tor Development & Enhancin Post Request for Bids Limited 70,000.00 0.00 Canceled 2019-05-16 2019-05-21 2019-07-02 2019-08-01 2019-09-05 nvelope 3 ali Centre on Poetry Works g Competitiveness NG-MINDIVER-174609-CW-DI R / Installation of Fire Assay Establishing a Strong Found 2021-01-1 Equipment and training at th IDA / 59900 ation for Mining Sector Deve Post Direct Selection Direct 50,000.00 72,587.23 Signed 2020-05-27 2020-07-24 2020-06-10 2020-07-27 2020-07-15 2020-09-18 1 e NIGERIAN Geological Surve lopment y Agency Laboratory (NGSA), Kaduna. NG-MINDIVER-216691-CW-R FQ / Renovation of 2nd Buildi Facilitating Downstream Sec ng at the Gemstone and Jewe Request for Quota Single Stage - One E Under Imple 2021-10-1 IDA / 59900 tor Development & Enhancin Post Limited 45,000.00 0.00 2021-02-20 2021-04-17 llery, centre, Abuja for the tr tions nvelope mentation 4 g Competitiveness aining of candidates for the g emstone and jewellery activit y NG-MINDIVER-211936-CW-R Facilitating Downstream Sec FB / Partial renovation of the Single Stage - One E 2021-11-1 IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 500,000.00 0.00 Canceled 2021-01-26 2021-01-31 2021-03-14 2021-04-13 2021-05-18 facilities and infrastructure at nvelope 4 g Competitiveness Ladi Kwali Pottery Site, Sulej a NG-MINDIVER-250850-CW-R Facilitating Downstream Sec Request for Bids - FB / Partial renovation of the Single Stage - One E Pending Imp 2022-09-0 IDA / 59900 tor Development & Enhancin Post Request for Bids Limited Works SPD (after 500,000.00 0.00 2021-09-20 2021-09-25 2021-11-06 2021-12-06 2022-01-10 facilities and infrastructure at nvelope lementation 7 g Competitiveness prequalification) Ladi Kwali Pottery Site, Sulej a NG-MINDIVER-278341-CW-R FB / Renovation of further wo Request for Bids - rks at the National Institute o Establishing a Strong Found Single Stage - One E Small Works SPD Under Imple 2022-12-2 f Mining and Geosciences, (NI IDA / 59900 ation for Mining Sector Deve Post Request for Bids Open - National 1,200,000.00 0.00 2022-04-10 2022-12-05 2022-04-17 2022-12-07 2022-05-17 2022-05-27 2022-07-01 nvelope (1 envelope proce mentation 8 MG) Jos (LOT 1) and Remodel lopment ss) ling of Modern Core Shed for the National Geological Surv ey Agency, Kaduna. (LOT 2) NG-MINDIVER-361479-CW-R Facilitating Downstream Sec Request for Quota FQ / Security Reinforcement Request for Quota Single Stage - One E Pending Imp 2024-01-1 IDA / 59900 tor Development & Enhancin Post Limited tions (Non Bank-S 50,000.00 0.00 2023-05-22 2023-07-17 of Ibadan Gemstone and Jew tions nvelope lementation 3 g Competitiveness PD) elry market center GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MINDIVER/GO/RFQ/001/18 / Project Management and Co Request for Quota Single Stage - One E Procurement of Office Equip IDA / 59900 Post Limited 100,000.00 67,232.55 Completed 2018-02-10 2018-06-25 2018-04-07 2018-08-01 2018-10-04 2018-09-24 ordination tions nvelope ment for MinDiver Project us e MINDIVER/GO/RFQ/004/18 / Project Management and Co Project Management Server, IDA / 59900 Post Direct Selection Direct 65,000.00 0.00 Canceled 2018-04-15 2018-04-20 2018-06-08 2018-12-05 ordination Softwares and Hardwares MINDIVER/GO/RFQ/007/17 / Establishing a Strong Found Request for Quota Single Stage - One E Procurement of Office Furnitu IDA / 59900 ation for Mining Sector Deve Post Limited 100,000.00 60,921.44 Signed 2018-02-20 2018-06-25 2018-04-24 2019-12-03 2018-10-21 tions nvelope re for MinDiver Project lopment MINDIVER/GO/RFB/008/18 / Establishing a Strong Found Procurement of Office Furnitu Single Stage - One E IDA / 59900 ation for Mining Sector Deve Post Request for Bids Open - National 400,000.00 0.00 Canceled 2018-02-10 2018-02-15 2018-03-29 2018-04-28 2018-06-02 2018-11-29 re for Mining Cadastre office nvelope lopment (MCO) -6 Geopolitical Zones MINDIVER/GO/RFQ/008/18 / Establishing a Strong Found Request for Quota Single Stage - One E Pending Impl Supply and Installation of ICT IDA / 59900 ation for Mining Sector Deve Post Limited 100,000.00 0.00 2018-02-20 2018-04-17 2018-10-14 tions nvelope ementation equipment for MinDiver Proje lopment ct Office MINDIVER/NCB/G-007/18 / S Facilitating Downstream Sec Single Stage - One E Under Imple upply and Installation of ICT IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 400,000.00 0.00 2018-02-15 2019-05-17 2018-03-01 2018-04-12 2019-07-15 2018-05-12 2019-08-01 2018-06-16 2018-12-13 nvelope mentation equipment for 6 Geopolitical g Competitiveness Zones of the MCO MINDIVER/GO/RFQ/005/18 / Project Management and Co Request for Quota Single Stage - One E Procurement of Stationeries IDA / 59900 Post Limited 100,000.00 13,783.60 Signed 2018-03-01 2018-03-13 2018-04-26 2018-11-09 2018-10-23 ordination tions nvelope and Printing materials for Min diver Project office MINDIVER/GO/RFB/006/18 / Procurement of Office Equip Establishing a Strong Found Single Stage - One E ment, Stationeries and Printi IDA / 59900 ation for Mining Sector Deve Post Request for Bids Open - National 600,000.00 0.00 Canceled 2018-04-01 2018-04-15 2018-05-27 2018-06-26 2018-07-31 2019-01-27 nvelope ng materials for 6 Geopolitic lopment al Zones of the Mining Cadas tre Office MINDIVER/GO/RFQ/014/18 / Facilitating Downstream Sec Request for Quota Single Stage - One E Solar Panel system for NGSA, IDA / 59900 tor Development & Enhancin Post Limited 95,000.00 82,362.76 Signed 2018-03-15 2019-05-30 2018-05-10 2019-07-28 2018-11-06 tions nvelope Kaduna g Competitiveness MINDIVER/GO/RFB/005/18 / Facilitating Downstream Sec Single Stage - One E Laboratory Equipment for NG IDA / 59900 tor Development & Enhancin Prior Request for Bids Open - National 1,500,000.00 2,985,098.37 Signed 2018-03-15 2019-06-24 2018-03-20 2018-05-01 2019-09-12 2018-05-31 2020-01-29 2018-07-05 2020-03-19 2019-01-01 nvelope SA Kaduna g Competitiveness MINDIVER/RFQ/G-004/18 / Pr Facilitating Downstream Sec ocurement of Motor Vehicles Request for Quota Single Stage - One E IDA / 59900 tor Development & Enhancin Post Limited 500,000.00 471,052.40 Completed 2018-02-15 2018-03-29 2018-04-19 2018-04-26 2018-10-16 2018-06-26 for Project office -Saloon Cars tions nvelope g Competitiveness (4NOS), 4X4 (1Nos) MINDIVER/RFQ/GD-016/18 / Establishing a Strong Found Procurement of Hardware up Request for Quota Single Stage - One E Pending Impl IDA / 59900 ation for Mining Sector Deve Post Limited 100,000.00 0.00 2018-02-20 2018-04-17 2018-10-14 grade for Information Manag tions nvelope ementation lopment ement System at the NGSA ( DSS, Exploration, IT) MINDIVER/RFQ/GD-078/18 / Establishing a Strong Found Request for Quota Single Stage - One E Procurement of Topographic IDA / 59900 ation for Mining Sector Deve Post Limited 50,000.00 48,377.13 Completed 2018-09-05 2018-08-16 2018-10-31 2018-09-19 2019-04-29 2018-09-24 tions nvelope al Maps covering the entire c lopment ountry, Nigeria Page 2 MINDIVER/GO/RFQ/108/19 / Project Management and Co Request for Quota Single Stage - One E Pending Impl Procurement of Office Furnitu IDA / 59900 Post Limited 20,000.00 0.00 2019-04-20 2019-06-15 2019-12-12 ordination tions nvelope ementation re for PMO (MindIVER) MINDIVER/GO/RFB/102/19 / Procurement and installation Project Management and Co Request for Quota Single Stage - One E of Manual Shelving/Rack syst IDA / 59900 Post Limited 25,000.00 21,604.91 Signed 2019-03-20 2019-05-28 2019-05-15 2019-08-01 2019-11-11 ordination tions nvelope em for safekeping of docume nts for MinDiverProcurement unit) MINDIVER/GO/RFQ/104/19 / Facilitating Downstream Sec Request for Quota Single Stage - One E Under Imple Printing of NGSA Technical R IDA / 59900 tor Development & Enhancin Post Limited 50,000.00 0.00 2019-08-20 2019-10-15 2020-04-12 tions nvelope mentation eports and Manuals g Competitiveness NG-MINDIVER-103110-GO-R Project Management and Co Request for Quota Single Stage - One E Under Imple FQ / Procurement of office Eq IDA / 59900 Post Limited 20,000.00 0.00 2019-08-06 2019-10-14 2019-10-01 2020-03-29 ordination tions nvelope mentation uipment for Mindiver project NG-MINDIVER-104557-GO-R Facilitating Downstream Sec FB / Procurement of Solar Pa Single Stage - One E IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 150,000.00 129,107.70 Signed 2019-05-01 2019-06-05 2019-05-06 2019-07-19 2019-06-17 2019-08-15 2019-07-17 2019-11-14 2019-08-21 2019-11-29 2020-02-17 nel System for 6 Zonal office nvelope g Competitiveness s of the Mining Cadastre Offic e (MCO) MINDIVER/GO/RFQ/003/17 / Facilitating Downstream Sec Procurement of 4X4 wheel dr Single Stage - One E Under Imple IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 1,200,000.00 0.00 2019-05-24 2019-05-17 2019-05-29 2019-07-10 2019-07-10 2019-08-09 2019-07-14 2019-09-13 2020-03-11 ive Double cabin pick-up vehi nvelope mentation g Competitiveness cles MCO 6/ASM 2/M1 2/SMD F 1 /Metal and Steel 1 MINDIVER/RFB/GO/021-18 / Procurement and installation of Laboratory Equipment for Facilitating Downstream Sec Open - Internationa Single Stage - One E Nigerian Metallurgical and De IDA / 59900 tor Development & Enhancin Prior Request for Bids 1,700,000.00 1,528,118.75 Signed 2019-05-25 2019-08-04 2019-05-30 2019-08-06 2019-07-11 2019-09-23 2019-08-10 2020-02-24 2019-09-14 2020-05-21 2020-03-12 l nvelope velopment Centre (NMDC),Jo g Competitiveness s and Nigerian INSTITUTE of MINING and Geosciences (NI MG), Jos . MINDIVER/GO/RFB/106/19 / Procurement and installation Facilitating Downstream Sec Single Stage - One E of Laboratory Equipment for IDA / 59900 tor Development & Enhancin Prior Request for Bids Open - National 500,000.00 0.00 Canceled 2019-05-01 2019-05-06 2019-06-17 2019-07-17 2019-08-21 2020-02-17 nvelope Nigerian INSTITUTE of MININ g Competitiveness G and Geosciences (NIMG) NG-MINDIVER-115030-GO-R Facilitating Downstream Sec FQ / Procurement of 45kva S Request for Quota Single Stage - One E IDA / 59900 tor Development & Enhancin Post Limited 90,000.00 83,951.17 Signed 2019-06-12 2019-05-30 2019-08-07 2019-07-08 2020-02-03 olar/inverter system for the tions nvelope g Competitiveness Mining Cadastre Office (CO)H eadquarters, Abuja NG-MINDIVER-115033-GO-R Facilitating Downstream Sec FQ / Procurement of Furnitur Request for Quota Single Stage - One E IDA / 59900 tor Development & Enhancin Post Limited 75,000.00 72,231.77 Signed 2019-06-07 2019-05-28 2019-08-02 2019-07-08 2020-01-29 e for the Solid Mineral Develo tions nvelope g Competitiveness pment Fund (SMDF) NG-MINDIVER-119247-GO-R Facilitating Downstream Sec FQ / Procurement of IT and C Request for Quota Single Stage - One E Under Imple IDA / 59900 tor Development & Enhancin Post Open - National 100,000.00 0.00 2019-08-02 2019-09-27 2020-03-25 ommunication Equipment for tions nvelope mentation g Competitiveness Solid Mineral Development F und (SMDF) MINDIVER/RFQ/GO/008/18 / Establishing a Strong Found Procurement of Office Furnitu Request for Quota Single Stage - One E Under Imple IDA / 59900 ation for Mining Sector Deve Post Limited 100,000.00 0.00 2019-08-02 2019-04-18 2019-09-27 2020-03-25 re for Mining Cadastre office tions nvelope mentation lopment (MCO) -6 Geopolitical Zones NG-MINDIVER-144-GO-RFQ / Facilitating Downstream Sec Procurement of Furniture for Request for Quota Single Stage - One E IDA / 59900 tor Development & Enhancin Post Limited 35,000.00 29,034.52 Signed 2019-08-30 2019-07-23 2019-10-25 2019-08-30 2020-04-22 training on Remote sensing f tions nvelope g Competitiveness or the Formalisation of ASM NG-MINDIVER-154-GO-RFB / Procurement of Jewellery ma Facilitating Downstream Sec Open - Internationa Single Stage - One E king and Gemmology Equipm IDA / 59900 tor Development & Enhancin Prior Request for Bids 500,000.00 1,751,693.77 Signed 2019-08-20 2019-10-22 2019-08-25 2019-11-27 2019-10-06 2020-01-14 2019-11-05 2020-10-05 2019-12-10 2020-11-01 2020-06-07 l nvelope ent for the Development of t g Competitiveness he Gemstone and Jewellery I ndustry NG-MINDIVER-143-GO-RFQ / Facilitating Downstream Sec Procurement of Equipment fo Request for Quota Single Stage - One E IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 85,794.05 Signed 2019-09-30 2019-07-19 2019-11-25 2019-08-28 2019-12-25 r Remote sensing in the Form tions nvelope g Competitiveness alisation of Artisanal Miners- Phase 1 MINDIVER/GO/RFB/013/18 / Procurement of 6 nos tableto Facilitating Downstream Sec Single Stage - One E Under Imple p X-ray Fluorescence (XRF) IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 600,000.00 0.00 2019-09-25 2019-10-18 2019-10-09 2019-11-18 2019-11-20 2020-01-28 2019-12-20 2020-01-24 2020-07-22 nvelope mentation machine and 20 nos handhel g Competitiveness d X-ray Fluorescence (XRF) a nalysers for exit ports. MINDIVER/GO/RFB/011/17 / Facilitating Downstream Sec Single Stage - One E XRF Analyzer X-Ray machine IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 300,000.00 0.00 Canceled 2018-03-15 2018-03-29 2018-05-10 2018-06-09 2018-07-14 2019-01-10 nvelope s for exit Ports (10) g Competitiveness NG-MINDIVER-128956-GO-DI R / Procurement of Arc GIS S Facilitating Downstream Sec oftware for utilisation of the IDA / 59900 tor Development & Enhancin Post Direct Selection Direct 150,000.00 83,887.20 Completed 2019-09-30 2019-09-13 2019-10-05 2019-09-18 2019-11-09 2019-10-17 2019-12-09 2019-11-20 Remote sensing system for t g Competitiveness he Formalisation of Artisanal miners. NG-MINDIVER-137-GO-RFQ / Facilitating Downstream Sec Request for Quota Single Stage - One E Procurement of Thematic Ma IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 0.00 Canceled 2019-08-25 2019-10-20 2019-12-19 tions nvelope ps for restricted areas of the g Competitiveness Country. NG-MINDIVER-136-GO-RFQ / Facilitating Downstream Sec Acquisition, Georeferencing a Request for Quota Single Stage - One E IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 0.00 Canceled 2019-09-14 2019-11-09 2020-05-07 nd Geocoding of Topographic tions nvelope g Competitiveness maps for the country. NG-MINDIVER-134539-GO-R Facilitating Downstream Sec FB / Procurement of I.T Equip Single Stage - One E IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 250,000.00 267,614.68 Signed 2019-09-30 2019-10-07 2019-10-14 2019-10-07 2019-11-25 2019-12-03 2019-12-25 2020-01-09 2020-01-29 2020-02-29 2020-07-27 ment to support the Nigeria nvelope g Competitiveness Geodata Centre at the NGSA and NSRMEA Kaduna MINDIVER/GO/RFQ/004/19 / Project Management and Co Request for Quota Single Stage - One E Pending Impl Procurement of Project Mana IDA / 59900 Post Limited 65,000.00 0.00 2019-09-30 2019-11-25 2020-05-23 ordination tions nvelope ementation gement Server, Softwares an d Hardware. Page 3 NG-MINDIVER-115035-GO-R Facilitating Downstream Sec FB / Procurement of IT and C Single Stage - One E IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 200,000.00 0.00 Canceled 2019-06-03 2019-06-08 2019-07-20 2019-08-19 2019-09-23 2020-03-21 ommunication Equipment for nvelope g Competitiveness Solid Mineral Development F und (SMDF) MINDIVER/GO/RFQ/107/19 / Project Management and Co Request for Quota Single Stage - One E Under Imple Procurement of office Station IDA / 59900 Post Limited 50,000.00 0.00 2020-04-05 2020-07-03 2020-05-31 2020-06-30 ordination tions nvelope mentation ery amd printing supplies for MinDiver Project NG-MINDIVER-165410-GO-R Project Management and Co Request for Quota Single Stage - One E Under Imple FQ / Procurement of office eq IDA / 59900 Post Limited 50,000.00 0.00 2020-04-20 2020-06-15 2020-07-30 ordination tions nvelope mentation uipment for Mindiver Project (2020) NG-MINDIVER-168709-GO-R FB / Procurement of Equipme Facilitating Downstream Sec Open - Internationa Single Stage - One E Under Imple nt for Remote sensing activit IDA / 59900 tor Development & Enhancin Post Request for Bids 350,000.00 0.00 2020-04-27 2020-06-16 2020-05-02 2020-06-16 2020-06-13 2020-07-29 2020-07-13 2020-08-17 2021-02-13 l nvelope mentation y under the Formalization of g Competitiveness Artisanal Miners activity. NG-MINDIVER-168711-GO-R FQ / Procurement of Goods a Facilitating Downstream Sec Request for Quota Single Stage - One E Under Imple nd IT Equipment for the Train IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 0.00 2020-04-29 2020-04-22 2020-06-24 2020-07-24 tions nvelope mentation ing facilities at the Gemstone g Competitiveness and Jewellery centre, Abuja NG-MINDIVER-168713-GO-R FB / Procurement of Accessor Facilitating Downstream Sec Open - Internationa Single Stage - One E Under Imple ies for PM 6 Auto precision L IDA / 59900 tor Development & Enhancin Post Request for Bids 350,000.00 0.00 2020-04-21 2020-06-17 2020-04-26 2020-06-19 2020-06-07 2020-07-31 2020-07-07 2020-08-11 2021-02-07 l nvelope mentation apping and polishing machin g Competitiveness e for the National Metallurgic al Development Centre, Jos MINDIVER/GO/RFB/012/18 / Facilitating Downstream Sec Single Stage - One E Equiping of the dimension st IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 300,000.00 0.00 Canceled 2018-02-15 2018-02-20 2018-04-03 2018-05-03 2018-06-07 2019-06-07 nvelope one laboratory in Kaduna g Competitiveness NG-MINDIVER-128949-GO-R FQ / Procurement of IT infrast Facilitating Downstream Sec Request for Quota Single Stage - One E ructure and Data Systems at IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 0.00 Canceled 2019-09-10 2019-11-05 2020-01-04 tions nvelope the Nigeria Geological Surve g Competitiveness y Agency for the automation information system NG-MINDIVER-134-GO-RFQ / Facilitating Downstream Sec Request for Quota Single Stage - One E Procurement of Goods and Li IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 0.00 Canceled 2019-09-05 2019-10-31 2020-04-28 tions nvelope cences for the MMSD portal s g Competitiveness olution. NG-MINDIVER-184755-GO-DI R / Enhancement of internet Project Management and Co Pending Impl IDA / 59900 Post Direct Selection Direct 50,000.00 0.00 2020-07-21 2020-07-28 2020-09-06 2021-09-01 Bandwidth subscription for M ordination ementation indiver Project from 20mbps to 100mbps NG-MINDIVER-184758-GO-R FQ / Procurement of Statione Facilitating Downstream Sec Request for Quota Single Stage - One E Pending Impl ries and Security Printing ma IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 0.00 2020-08-07 2020-10-02 2021-03-31 tions nvelope ementation terials for the Headquarters a g Competitiveness nd 6 Zonal Offices of the Mini ng Cadastre Office (MCO) MINDIVER/GO/RFB/306/18 / / Procurement of Office Equip Facilitating Downstream Sec ment, Stationeries and Printi Single Stage - One E IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 300,000.00 0.00 Canceled 2019-03-21 2019-03-26 2019-05-07 2019-06-06 2019-07-11 2020-01-07 ng materials for Headquarter nvelope g Competitiveness s and 6 Geopolitical Zones of the Mining Cadastre Office ( MCO) NG-MINDIVER-184760-GO-R FQ / Procurement of Solar Sy stem for the Nigeria Geologic Facilitating Downstream Sec al Survey Agency (NGSA) Ab Request for Quota Single Stage - One E Pending Impl IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 0.00 2020-08-06 2020-10-01 2021-03-30 uja, Kaduna, and NationaL St tions nvelope ementation g Competitiveness eel Raw Material Agency (NS RMEA)Kaduna for the implem entation of the Nigeria Geoda ta centre. NG-MINDIVER-184766-GO-R Facilitating Downstream Sec FQ / Procurement & Installati Request for Quota Single Stage - One E Pending Impl IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 0.00 2020-07-25 2020-09-19 2021-03-18 on of Fire safety equipment f tions nvelope ementation g Competitiveness or the Mindiver Project office NG-MINDIVER-184764-GO-R FQ / Procurement of Internet Bandwidth for NGSA Abuja (1 00mbps Primary & 50 Mbps s Facilitating Downstream Sec Request for Quota Single Stage - One E Under Imple econdary), NGSA Kaduna (50 IDA / 59900 tor Development & Enhancin Post Limited 250,000.00 0.00 2020-07-27 2020-08-07 2020-09-21 2021-03-20 tions nvelope mentation mbps Primary & 20 Mbps sec g Competitiveness ondary) and NSRMEA (50mb ps Primary & 20 Mbps secon dary) for the Nigeria Geodata centres at these locations. MINDIVER/GO/RFB/009/19 / Establishing a Strong Found Open - Internationa Single Stage - Two E Procurement of efficient Tech IDA / 59900 ation for Mining Sector Deve Prior Request for Bids 1,200,000.00 0.00 Canceled 2019-06-05 2019-06-10 2019-07-22 2019-10-04 2019-11-08 2020-05-06 l nvelope nology Equipmemt for safer lopment and Cleaner Mining NG-MINDIVER-211940-GO-R Facilitating Downstream Sec FQ / Procurement of simple p Request for Quota Single Stage - One E Under Imple IDA / 59900 tor Development & Enhancin Post Limited 70,000.00 0.00 2021-02-12 2021-05-17 2021-04-09 2021-07-08 ottery-making equipment for tions nvelope mentation g Competitiveness training at Ladi Kwali Pottery centre NG-MINDIVER-211941-GO-R Facilitating Downstream Sec FB / Procurement of modern Single Stage - One E Under Imple IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 400,000.00 0.00 2021-01-28 2021-04-11 2021-02-11 2021-04-19 2021-03-25 2021-04-24 2021-05-29 2021-11-25 and mechanized equipment f nvelope mentation g Competitiveness or the Ladi Kwali pottery cent re. NG-MINDIVER-211118-GO-R FQ / Procurement and Install Facilitating Downstream Sec ation Equipment at the Gems Request for Quota Single Stage - One E Under Imple IDA / 59900 tor Development & Enhancin Post Limited 40,000.00 0.00 2021-03-01 2021-04-26 2021-07-25 tone and Jewellery, centre, A tions nvelope mentation g Competitiveness buja for the training of candi dates for THE gemstone and jewellery activity NG-MINDIVER-211116-GO-R Facilitating Downstream Sec FB / Procurement of equipme Single Stage - One E Under Imple IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 650,000.00 0.00 2021-02-15 2021-04-15 2021-02-20 2021-04-15 2021-04-03 2021-06-03 2021-05-03 2021-08-13 2021-06-07 2021-12-04 nt for the development of the nvelope mentation g Competitiveness gemstone market in southwe st Nigeria Page 4 NG-MINDIVER-216703-GO-R FQ / Procurement of 3nos Vid eo Conferencing Equipment f Facilitating Downstream Sec or the Ministers Conference Request for Quota Single Stage - One E Pending Impl IDA / 59900 tor Development & Enhancin Post Limited 46,000.00 0.00 2021-03-21 2021-05-16 2021-07-15 Room at the Ministry of Mine tions nvelope ementation g Competitiveness s and Steel Development (M MSD), Mining Cadastre Office (MCO) Conference Room, an d NGSA, Abuja Conference R oom NG-MINDIVER-234530-GO-R FB / Procurement and Installa tion of modern technical and Facilitating Downstream Sec Single Stage - One E Under Imple logistics equipment and tools IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 250,000.00 0.00 2021-07-25 2022-03-08 2021-07-30 2022-03-09 2021-09-10 2022-04-19 2021-10-10 2022-05-10 2021-11-14 2022-05-13 nvelope mentation for the Mines Inspectorate De g Competitiveness partment of the Ministry of M ines and Steel Development ( MMSD) NG-MINDIVER-234526-GO-R FQ / Procurement and install Facilitating Downstream Sec Request for Quota Single Stage - One E Pending Impl ation of 2nos of professional IDA / 59900 tor Development & Enhancin Post Limited 45,000.00 0.00 2021-07-30 2021-09-24 2022-03-23 tions nvelope ementation Large format scanner for the g Competitiveness NGSA/NSRMEA Geodata Cent re NG-MINDIVER-250851-GO-R FQ / Procurement of 1nos 4X Project Management and Co Request for Quota Single Stage - One E Under Imple IDA / 59900 Post Limited 130,000.00 0.00 2021-09-12 2021-11-07 2022-02-05 4 Wheel drive vehicle for Sup ordination tions nvelope mentation ervision and Monitoring of Pr ojects activities NG-MINDIVER-278371-GO-R FB / Procurement of 6 nos of Double cabin Motor vehicle f Facilitating Downstream Sec or NGSA for the supervision o Single Stage - One E Under Imple IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 800,000.00 0.00 2022-03-15 2022-04-01 2022-03-20 2022-04-08 2022-05-01 2022-05-11 2022-05-31 2022-07-05 2023-01-01 f Airborne Geophysical works nvelope mentation g Competitiveness , Geochemical and Topo map s works including Procureme nt of 1nos 30-seater minibus to support the NIMG. NG-MINDIVER-278435-GO-R FQ / Procurement of Statione Project Management and Co Request for Quota Single Stage - One E Pending Impl IDA / 59900 Post Limited 75,000.00 0.00 2022-02-20 2022-04-17 2022-06-16 ry and office equipment and I ordination tions nvelope ementation T Consumables for Mindiver f or yr2022-2023) NG-MINDIVER-278436-GO-R FQ / Printing and Binding of P Project Management and Co Request for Quota Single Stage - One E Pending Impl IDA / 59900 Post Limited 35,000.00 0.00 2022-09-06 2022-11-01 2022-12-31 roject’s activity Reports for cl ordination tions nvelope ementation osure. (Final Reports) NG-MINDIVER-278445-NC-RF B / Engagement of a Consulti ng Firm to undertake the Des ign, Development and Opera Facilitating Downstream Sec Single Stage - One E Pending Impl tionalization of an Environme IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 950,000.00 0.00 2022-03-30 2022-04-04 2022-05-16 2022-06-15 2022-07-20 2023-01-16 nvelope ementation ntal Information System inclu g Competitiveness ding Procurement of Informat ion and Communication Tech nology system for the Ministr y of Mines and Steel Develop ment (MM NG-MINDIVER-280369-GO-R FB / Procurement of goods an Establishing a Strong Found Single Stage - One E Under Imple d equipment to carry out Geo IDA / 59900 ation for Mining Sector Deve Post Request for Bids Open - National 900,000.00 0.00 2022-03-15 2022-05-25 2022-03-20 2022-05-25 2022-05-01 2022-05-31 2022-07-05 2023-01-01 nvelope mentation chemical mapping of selecte lopment d areas under the proof of co ncept in Nigeria. NG-MINDIVER-277985-GO-R FB / Procurement and Installa Establishing a Strong Found tion of Laboratory Equipment Open - Internationa Single Stage - One E IDA / 59900 ation for Mining Sector Deve Post Request for Bids 2,500,000.00 0.00 Canceled 2022-03-01 2022-03-06 2022-04-05 2022-04-08 2022-04-29 2022-10-26 for the ISO Certification of th l nvelope lopment e National Geological Survey Laboratory (NGRL), Kaduna. I ncl Training NG-MINDIVER-289161-GO-R FB / Procurement and Installa Establishing a Strong Found tion of Laboratory equipment Under Imple IDA / 59900 ation for Mining Sector Deve Post Direct Selection Direct 2,500,000.00 0.00 2022-04-24 2022-05-05 2022-05-22 2022-05-17 2022-07-01 2022-12-28 for the ISO Certification of th mentation lopment e National Geological Survey Laboratory (NGRL), Kaduna. I ncl Training. NG-MINDIVER-315215-GO-DI R / Procurement of basic jew Facilitating Downstream Sec elry-making tools (Starter Pa Under Imple IDA / 59900 tor Development & Enhancin Post Direct Selection Direct - National 264,000.00 0.00 2022-09-15 2022-09-08 2022-09-20 2022-09-21 2022-10-25 2022-12-24 ck) for the 1st and 2nd Batch mentation g Competitiveness of graduates of the Master Tr aining in Jewellery making an d design. NG-MINDIVER-361258-GO-R Facilitating Downstream Sec FQ / Procurement of 150KVA Request for Quota Single Stage - One E Pending Impl IDA / 59900 tor Development & Enhancin Post Limited 35,000.00 0.00 2023-05-20 2023-07-15 2024-01-11 soundproof, Diesel-powered tions nvelope ementation g Competitiveness Generator for the mining cad astre office. NG-MINDIVER-361291-GO-DI Facilitating Downstream Sec R / Procurement of starter kit Pending Impl IDA / 59900 tor Development & Enhancin Post Direct Selection Direct - National 185,000.00 0.00 2023-05-15 2023-05-20 2023-06-24 2023-12-21 for Batch 3 trainees on Gems ementation g Competitiveness tone and jewelry making. 30 trainees- NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MINDIVER/NC/RFP/105/19 / A irborne Geophysical Survey o Establishing a Strong Found f selected areas under proof Request for Propo Open - Internationa Single Stage - Two E IDA / 59900 ation for Mining Sector Deve Prior 4,500,000.00 0.00 Canceled 2019-05-23 2019-05-28 2019-07-09 2019-09-21 2019-10-26 2020-04-23 of concept programme- High sals l nvelope lopment resolution magnetic & Radio metric. Areas A-1, A-2 and c- 1 (100 sheets (TLM50 (38-32 NG-MINDIVER-103087-NC-RF P / Production of Topographic Establishing a Strong Found Mapping (Geodata Base) usin Request for Propo Open - Internationa Single Stage - Two E IDA / V0270 ation for Mining Sector Deve Prior 4,000,000.00 0.00 Canceled 2019-05-22 2019-05-27 2019-07-08 2019-09-20 2019-10-25 2020-04-22 g international Standards (M sals l nvelope lopment GCPOVmap2) for Areas A-1 , A-2 and c-1 (100 sheets (TLM 50 (38-32percent. Page 5 NG-MINDIVER-107437-NC-RF B / Airborne Geophysical Sur Facilitating Downstream Sec vey of selected areas under Open - Internationa Single Stage - One E IDA / 59900 tor Development & Enhancin Prior Request for Bids 10,000,000.00 0.00 Canceled 2019-04-21 2019-12-15 2019-05-12 2020-01-15 2019-06-23 2019-07-23 2019-08-27 2020-02-23 proof of concept programme- l nvelope g Competitiveness High resolution magnetic & R adiometric. Areas A-1 , A-2 a nd c-1 (100 sheets (TLM50 ) NG-MINDIVER-107438-NC-RF B / Production of Topographic Facilitating Downstream Sec Mapping (Geodata Base) usin Open - Internationa Single Stage - One E IDA / 59900 tor Development & Enhancin Prior Request for Bids 4,000,000.00 0.00 Canceled 2019-07-31 2019-12-15 2019-08-21 2019-10-02 2019-11-01 2019-12-06 2020-06-03 g international Standards (M l nvelope g Competitiveness GCPOVmap2) for Areas A-1 , A-2 and c-1 (100 sheets (TLM 50 NG-MINDIVER-138-NC-RFB / Facilitating Downstream Sec Scanning and digitization of L Single Stage - One E IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 200,000.00 230,769.97 Signed 2019-08-29 2020-01-16 2019-09-03 2020-03-24 2019-10-15 2020-06-10 2019-11-14 2020-06-25 2019-12-19 2020-08-27 2020-06-16 icense documents for E-recor nvelope g Competitiveness ding and Archiving of the Min ing Cadastre office NG-MINDIVER-133910-NC-RF B / Production of Thematic M Facilitating Downstream Sec Single Stage - One E Under Imple apping of Mineral Title of rest IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 120,000.00 0.00 2019-10-03 2019-11-04 2019-10-08 2019-11-19 2019-12-19 2020-01-23 2020-02-28 nvelope mentation ricted (Protected)Areas and i g Competitiveness ntegration into the Nigeria Di gital Cadastral Database NG-MINDIVER-133911-NC-RF Q / Acquisition, Georeferenci Facilitating Downstream Sec Single Stage - One E Under Imple ng and Geocoding of Topogra IDA / 59900 tor Development & Enhancin Post Request for Bids Open - National 125,000.00 0.00 2019-09-30 2019-11-01 2019-10-05 2020-01-17 2019-11-16 2020-02-07 2019-12-16 2020-01-20 2020-07-18 nvelope mentation phic maps for the country in g Competitiveness the Nigeria Mining Cadastre Database NG-MINDIVER-160204-NC-RF B / Procurement of Firm to un Facilitating Downstream Sec dertake Airborne Geophysica Open - Internationa Single Stage - One E IDA / 59900 tor Development & Enhancin Prior Request for Bids 15,000,000.00 26,987,344.40 Signed 2020-02-25 2020-03-30 2020-03-17 2020-04-27 2020-04-28 2020-07-01 2020-05-28 2020-10-08 2020-07-02 2020-12-05 2021-06-27 l Survey of selected areas un l nvelope g Competitiveness der the proof of concept prog ramme using High resolution magnetic & Radiometric. NG-MINDIVER-160211-NC-RF B / Procurement of firm for th Facilitating Downstream Sec e Production of Topographic Open - Internationa Single Stage - One E IDA / 59900 tor Development & Enhancin Prior Request for Bids 6,000,000.00 4,448,322.44 Signed 2020-02-25 2020-03-23 2020-03-17 2020-03-26 2020-04-28 2020-07-03 2020-05-28 2020-10-19 2020-07-02 2021-01-05 2021-06-27 Mapping (Geodata Base) usin l nvelope g Competitiveness g international Standards (M GCPOVmap2) for identified A reas under the Proof of conc ept. NG-MINDIVER-165575-NC-DI Facilitating Downstream Sec R / Engagement of Security o Under Imple IDA / 59900 tor Development & Enhancin Post Direct Selection Direct 100,000.00 0.00 2020-03-31 2020-03-30 2020-04-05 2020-05-10 2020-11-06 utfit for the 6 Zonal Offices of mentation g Competitiveness the Nigerian Mining Cadastre Office NG-MINDIVER-210663-NC-RF B / Engagement of firm for M Establishing a Strong Found apping of clean energy miner Open - Internationa Single Stage - Two E IDA / 59900 ation for Mining Sector Deve Prior Request for Bids 6,700,000.00 0.00 Canceled 2021-02-10 2021-03-03 2021-04-14 2021-06-27 2021-08-01 2022-07-27 al resources as part of the Na l nvelope lopment tional Integrated Mineral Expl oration Programme (NIMEP) phase 2 NG-MINDIVER-278437-NC-RF Q / Development and Product Project Management and Co Request for Quota Single Stage - One E Pending Impl ion of Brochure and Compen IDA / 59900 Post Limited 50,000.00 0.00 2022-08-28 2022-10-23 2023-04-21 ordination tions nvelope ementation dium of all Mindiver activities /Projects (Past/Present) in Ag encies across the Country CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MINDIVER/QCBS/CS/002-18 / Advisory Firm to Strengthen t he Institutional Frameworks Establishing a Strong Found Quality And Cost- Governing the Mining Sector IDA / 59900 ation for Mining Sector Deve Prior Open - National 1,200,000.00 0.00 Canceled 2018-01-15 2018-07-23 2018-02-05 2018-10-23 2018-03-21 2018-04-18 2018-05-18 2018-06-22 2018-07-27 2019-07-27 Based Selection (Functional analysis and insti lopment tutional restructuring) and Se ctor Administrative Capacity Building MINDIVER/QCBS/CS/006-17 / Review of legal & regulatory frameworks for environment al mgt, the design of policy fr Establishing a Strong Found Quality And Cost- Under Implement ameworks to apply WB safeg IDA / 59900 ation for Mining Sector Deve Prior Open - National 2,000,000.00 0.00 2018-05-02 2018-03-20 2018-05-23 2018-07-28 2018-07-06 2019-02-20 2018-08-03 2019-04-23 2018-09-02 2019-06-11 2018-10-07 2019-10-18 2018-11-11 2019-11-11 Based Selection ation uards policies & the devt of lopment mitigation measures & guidel ines for addressing potential conflicts between ASM opera tors & other land users MINDIVER/QCBS/CS/009-18 / Consultancy to design and i Facilitating Downstream Sec Quality And Cost- mplement safer and cleaner IDA / 59900 tor Development & Enhancin Prior Open - National 1,650,000.00 0.00 Canceled 2018-01-16 2018-02-06 2018-03-22 2018-04-19 2018-05-19 2018-06-23 2018-07-28 2019-07-28 Based Selection mining programmes, efficient g Competitiveness technologies and practies in t he mining and steel sector MINDIVER/QCBS/CS/011-18 / Develop Mines Inspectorate f or ASM field inspection and r Facilitating Downstream Sec Quality And Cost- Under Implement ecommend how to equip the IDA / 59900 tor Development & Enhancin Prior Open - National 450,000.00 0.00 2018-03-30 2018-03-06 2018-04-20 2018-03-27 2018-06-03 2018-08-24 2018-07-01 2018-10-18 2018-07-31 2019-06-23 2018-09-04 2020-02-24 2018-10-09 2019-10-09 Based Selection ation Mines Inspectorate with appr g Competitiveness opriate and modern technical and logistics equipment and tools MINDIVER/QCBS/CS/013-18 / Consultancy to assist with id Establishing a Strong Found Quality And Cost- Under Implement entification of revenue leaka IDA / 59900 ation for Mining Sector Deve Post Open - National 450,000.00 0.00 2018-03-30 2018-04-25 2018-04-20 2018-06-03 2018-10-22 2018-07-01 2019-01-28 2018-07-31 2019-03-20 2018-09-04 2019-05-27 2018-10-09 2019-10-09 Based Selection ation ges, strengthen revenue ass lopment essment and develop action plan to combat smuggling MINDIVER/IC/CS/015-17 / Co nsultancy to provide support Establishing a Strong Found to NGSA and MMSD for miner Quality And Cost- Open - Internationa IDA / 59900 ation for Mining Sector Deve Prior 12,600,000.00 0.00 Canceled 2018-08-01 2018-08-22 2018-10-05 2018-11-02 2018-12-02 2019-01-06 2019-02-10 2020-02-10 al prospectivity testing, integ Based Selection l lopment ration and packaging using s atellite data-based foundatio n layers and collection of geo data Page 6 MINDIVER/QCBS/CS/020-18 / Development of support acti Facilitating Downstream Sec Quality And Cost- on to improve the Metallurgic IDA / 59900 tor Development & Enhancin Post Open - National 480,000.00 404,061.01 Signed 2018-02-05 2018-02-19 2018-02-26 2018-03-15 2018-04-11 2018-07-25 2018-05-09 2018-09-17 2018-06-08 2018-10-25 2018-07-13 2019-01-15 2018-08-17 2019-04-17 2019-08-17 Based Selection al and steel Inspectorate incl g Competitiveness uding an initial baseline stud y MINDIVER/QCBS/CS/023-18 / Consultancy to assess and b Establishing a Strong Found uild capacity in mining financ Quality And Cost- Open - Internationa IDA / 59900 ation for Mining Sector Deve Prior 1,300,000.00 0.00 Canceled 2018-01-04 2018-01-25 2018-03-10 2018-04-07 2018-05-07 2018-06-11 2018-07-16 2019-07-16 ing through design and imple Based Selection l lopment mentation of training progra mmes and support within fin ancing institutions MINDIVER/QCBS/CS/025-18 / Facilitating Downstream Sec Quality And Cost- Institutional and Administrati IDA / 59900 tor Development & Enhancin Post Open - National 450,000.00 0.00 Canceled 2018-02-15 2017-11-20 2018-03-08 2018-03-15 2018-04-21 2018-05-19 2018-06-18 2018-07-23 2018-08-27 2019-08-27 Based Selection ve restructuring of the SMDF g Competitiveness MINDIVER/QCBS/CS/026-18 / Facilitating Downstream Sec Design and implementation o Quality And Cost- IDA / 59900 tor Development & Enhancin Prior Open - National 450,000.00 0.00 Canceled 2018-02-15 2018-07-23 2018-03-08 2018-04-21 2018-05-19 2018-06-18 2018-07-23 2018-08-27 2019-08-27 f a public/Private sector Inves Based Selection g Competitiveness tment funding framework for the SMDF MINDIVER/QCBS/CS/027-18 / Consultancy to advance sele Facilitating Downstream Sec cted 'proof of concept' assets Quality And Cost- Open - Internationa IDA / 59900 tor Development & Enhancin Prior 3,000,000.00 0.00 Canceled 2017-11-30 2017-12-21 2018-02-03 2018-03-03 2018-04-02 2018-05-07 2018-06-11 2019-06-11 , assess their infrastructure n Based Selection l g Competitiveness eeds and also assist with dev elopment of a tender strateg y MINDIVER/QCBS/CS/046-18 / Project Management and Co Quality And Cost- Open - Internationa IDA / 59900 Prior 1,200,000.00 920,973.62 Signed 2017-11-12 2018-03-06 2017-12-03 2018-03-27 2018-01-16 2018-07-23 2018-02-13 2018-09-28 2018-03-15 2018-11-28 2018-04-19 2019-01-28 2018-05-24 2019-02-20 2019-05-24 Project Management Office ordination Based Selection l MINDIVER/QCBS/CS/053-18 / Facilitating Downstream Sec Design and implement a stra Quality And Cost- Open - Internationa Under Implement IDA / 59900 tor Development & Enhancin Post 450,000.00 0.00 2018-01-31 2018-03-06 2018-02-21 2018-06-08 2018-04-06 2018-05-04 2018-06-03 2019-04-11 2018-07-08 2018-08-12 2019-08-12 tegy for developing Nigeria’s Based Selection l ation g Competitiveness gemstone and jewellery indu stry MINDIVER/CQ/CS/058-18 / C Establishing a Strong Found onsultancy Service for design Consultant Qualifi IDA / 59900 ation for Mining Sector Deve Post Open - National 200,000.00 0.00 Canceled 2018-05-21 2018-06-11 2018-07-25 2018-08-24 2018-09-28 2019-03-27 and Supervision of Road Con cation Selection lopment struction under 'proof of conc ept' . MINDIVER/CQ/CS-059/18 / C Establishing a Strong Found onsultancy Service for the D Consultant Qualifi IDA / 59900 ation for Mining Sector Deve Post Open - National 50,000.00 0.00 Canceled 2018-06-05 2018-06-26 2018-08-09 2018-09-08 2018-10-13 2019-04-11 esign and Supervision of Ren cation Selection lopment ovation of NIMG,Jos MINDIVER/CQ/CS-054/18 / C onsultancy Service for the D Establishing a Strong Found Consultant Qualifi esign and Supervision of Ren IDA / 59900 ation for Mining Sector Deve Post Open - National 100,000.00 0.00 Canceled 2018-06-05 2018-06-26 2018-08-09 2018-09-08 2018-10-13 2019-04-11 cation Selection ovation of NGSA and Dimensi lopment on stone Laboratories in Kad una MINDIVER/CQ/CS-034/18 / C Establishing a Strong Found Consultant Qualifi Under Implement onsultancy Services for the u IDA / 59900 ation for Mining Sector Deve Post Limited 250,000.00 0.00 2018-01-25 2017-11-22 2018-02-08 2018-02-15 2018-03-10 2018-04-14 2018-10-11 cation Selection ation pdate of the Mineral and Mini lopment ng Act of 2007 MINDIVER/CQ/CS-028/18 / C Establishing a Strong Found onsultancy services for the D Consultant Qualifi Under Implement IDA / 59900 ation for Mining Sector Deve Post Limited 250,000.00 0.00 2018-01-28 2017-12-06 2018-02-11 2018-03-13 2018-04-17 2018-10-14 evelopment and Implementa cation Selection ation lopment tion of Communication Strate gies MINDIVER/QCBS/CS/008-18 / Formalization of artisanal mi ners into cooperatives and s Facilitating Downstream Sec mall-scale miners into larget Quality And Cost- Open - Internationa IDA / 59900 tor Development & Enhancin Prior 3,500,000.00 0.00 Canceled 2018-03-15 2018-03-06 2018-04-05 2018-03-27 2018-05-19 2018-08-16 2018-06-16 2018-07-16 2018-08-20 2018-09-24 2019-09-24 mineral and financial enterpri Based Selection l g Competitiveness ses together with the design and implememtation of an A SM remote sensing montorin g system in the mining and s teel sector MINDIVER/CQ/CS/0070-18 / ENGAGEMENT OF CONSULTI Establishing a Strong Found NG FIRM TO CARRY OUT NEE Consultant Qualifi IDA / 59900 ation for Mining Sector Deve Post Limited 250,000.00 332,263.22 Signed 2018-07-16 2018-08-15 2018-07-30 2018-08-01 2018-08-29 2018-12-18 2018-10-03 2019-01-11 2019-04-01 DS ASSESSMENT AND EVALU cation Selection lopment ATION OF THE NIGERIAN GEO LOGICAL SURVEY AGENCY (N GSA) MINDIVER/CQ/CS-071/ -18 / Engagement of a Consulting Establishing a Strong Found Consultant Qualifi Under Implement firm to carry out a review of i IDA / 59900 ation for Mining Sector Deve Post Limited 250,000.00 0.00 2018-07-16 2018-08-24 2018-08-15 2018-09-06 2018-08-30 2018-11-13 2018-10-04 2019-04-02 cation Selection ation mplemented Nigeria Mineral lopment Resources Decision Support System (NMRDSS). MINDIVER/QCBS/CS/080/18 / Formalization of artisanal mi Establishing a Strong Found Quality And Cost- Open - Internationa ners into cooperatives the d IDA / 59900 ation for Mining Sector Deve Prior 3,500,000.00 2,716,867.64 Signed 2018-07-30 2018-08-20 2018-09-10 2018-08-27 2018-10-08 2018-11-30 2018-11-07 2019-02-11 2018-12-12 2019-05-22 2019-01-16 2019-06-22 2020-01-16 Based Selection l esign and implememtation of lopment an ASM remote sensing mont oring system MINDIVER/QCBS/CS/081/18 / Facilitating Downstream Sec Institutional and Administrati Quality And Cost- Open - Internationa Under Implement IDA / 59900 tor Development & Enhancin Prior 900,000.00 0.00 2018-08-10 2018-08-31 2018-10-14 2018-10-24 2018-11-11 2018-12-14 2018-12-11 2019-02-18 2019-01-15 2019-05-07 2019-02-19 2020-02-19 ve restructuring of the Solid Based Selection l ation g Competitiveness Mineral Development Fund ( SMDF) MINDIVER/CQ/CS/014-18 / D esign and develop a mechani Establishing a Strong Found Consultant Qualifi Under Implement sm for citizens engagement IDA / 59900 ation for Mining Sector Deve Post Open - National 200,000.00 0.00 2019-03-31 2019-11-06 2019-04-21 2020-01-22 2019-06-04 2020-03-24 2019-07-04 2020-06-04 2019-08-08 2020-02-04 cation Selection ation and social accountability in t lopment he MinDiver Project and the Mining sector MINDIVER/CS/CQ/122-19 / E ngagement of a Firm to prep Facilitating Downstream Sec Consultant Qualifi Under Implement are/update the Strategic Envi IDA / 59900 tor Development & Enhancin Post Open - National 200,000.00 0.00 2019-02-05 2019-02-08 2019-02-26 2019-04-11 2019-05-11 2019-06-15 2019-12-12 cation Selection ation ronment and Social Assesme g Competitiveness nt (SESA) Report for Mindiver Project MINDIVER/CS/CQ/121/19 / E Facilitating Downstream Sec ngagement of Firm for overal Quality And Cost- IDA / 59900 tor Development & Enhancin Post Open - National 350,000.00 326,969.58 Signed 2019-06-19 2019-04-05 2019-07-10 2019-05-03 2019-08-23 2019-10-22 2019-09-20 2019-12-12 2019-10-20 2020-01-15 2019-11-24 2020-10-05 2019-12-29 2021-01-08 2020-12-28 l Quality Asurance of the Pro Based Selection g Competitiveness duction of Topographic Maps Page 7 NG-MINDIVER-103090-CS-C Facilitating Downstream Sec QS / Engagement of Firm for Quality And Cost- IDA / 59900 tor Development & Enhancin Prior Open - National 350,000.00 769,181.35 Signed 2019-04-20 2019-04-05 2019-05-11 2019-05-03 2019-06-24 2019-10-22 2019-07-22 2019-12-04 2019-08-21 2020-01-07 2019-09-25 2020-11-11 2019-10-30 2021-01-04 2020-10-29 overall Quality Assurance of Based Selection g Competitiveness Airborne Geophysical Survey- 5percent MINDIVER/CQ/CS/082-19 / E ngagement of Consultant to Facilitating Downstream Sec Quality And Cost- design and implement a Fra IDA / 59900 tor Development & Enhancin Prior Open - National 400,000.00 0.00 Canceled 2019-04-26 2019-05-17 2019-06-30 2019-07-28 2019-08-27 2019-10-01 2019-11-05 2020-11-04 Based Selection mework to restructure and re g Competitiveness position the Women in Minin g in Nigeria MINDIVER/QCBS/CS/050-18 / Project Management and Co Quality And Cost- IDA / 59900 Prior Open - National 600,000.00 0.00 Canceled 2018-05-30 2018-06-20 2018-08-03 2018-08-31 2018-09-30 2018-11-04 2018-12-09 2019-12-09 Quality Assurance Consultant ordination Based Selection MINDIVER/QCBS/CS/012-18 / Establishing a Strong Found Design and implement an Ele Quality And Cost- Open - Internationa IDA / 59900 ation for Mining Sector Deve Prior 500,000.00 0.00 Canceled 2018-02-28 2018-03-21 2018-05-04 2018-06-01 2018-07-01 2018-08-05 2018-09-09 2019-09-09 ctronic Archiving Manageme Based Selection l lopment nt System for NGSA MINDIVER/CQ/CS-018/18 / C Establishing a Strong Found onduct needs assessment of Consultant Qualifi IDA / 59900 ation for Mining Sector Deve Post Open - National 250,000.00 0.00 Canceled 2018-02-05 2019-03-15 2018-02-26 2018-04-11 2018-05-11 2018-06-15 2018-12-12 NIMG training infrastructure cation Selection lopment and setup procurement proc ess for refurbishment NG-MINDIVER-103077-CS-C QS / Engagement of Consulti Facilitating Downstream Sec Quality And Cost- ng Firm for preparation of BO IDA / 59900 tor Development & Enhancin Post Open - National 300,000.00 0.00 Canceled 2019-03-13 2019-04-03 2019-05-17 2019-06-14 2019-07-14 2019-08-18 2019-09-22 2020-09-21 Based Selection Q and Supervision of ALL Wo g Competitiveness rks activities for the Mindiver Project. NG-MINDIVER-114357-CS-C QS / Engagement of Consulti Facilitating Downstream Sec Consultant Qualifi Under Implement ng Firm for preparation of BO IDA / 59900 tor Development & Enhancin Post Limited 300,000.00 0.00 2019-05-20 2019-05-02 2019-06-03 2019-04-19 2019-07-03 2019-08-07 2020-02-03 cation Selection ation Q and Supervision of ALL Wo g Competitiveness rks activities for the Mindiver Project. MINDIVER/QCBS/CS/016-18 / Consultancy to provide advic e in the dissemination of geol Establishing a Strong Found Quality And Cost- ogical knowledge and in parti IDA / 59900 ation for Mining Sector Deve Prior Open - National 720,000.00 0.00 Canceled 2018-08-01 2018-08-22 2018-10-05 2018-11-02 2018-12-02 2019-01-06 2019-02-10 2020-02-10 Based Selection cular by the development of lopment a web application portal and system architecture to suppo rt MMIS MINDIVER/QCBS/CS/022-18 / Consultancy to undertake ne eds assessment and evaluati Facilitating Downstream Sec Quality And Cost- Open - Internationa on addressing mineral value IDA / 59900 tor Development & Enhancin Prior 1,150,000.00 0.00 Canceled 2018-08-03 2018-08-24 2018-10-07 2018-11-04 2018-12-04 2019-01-08 2019-02-12 2020-02-12 Based Selection l chain technical skills demand g Competitiveness gap including analysis of ext ension benefits and opportun ities. MINDIVER/QCBS/CS/030-18 / Advisory firm to prepare and Establishing a Strong Found Quality And Cost- implement a Road Map to cat IDA / 59900 ation for Mining Sector Deve Post Open - National 480,000.00 0.00 Canceled 2018-03-31 2018-04-21 2018-06-04 2018-07-02 2018-08-01 2018-09-05 2018-10-10 2019-10-10 Based Selection alyse the mineral Sector for lopment Regional Development.(Econ omic corridor) MINDIVER/QCBS/CS/019-18 / Design policy, regulatory fra mework & programmes to ad Facilitating Downstream Sec d value to mineral support ce Quality And Cost- Open - Internationa IDA / 59900 tor Development & Enhancin Prior 3,650,000.00 0.00 Canceled 2018-02-15 2018-03-08 2018-04-21 2018-05-19 2018-06-18 2018-07-23 2018-08-27 2019-08-27 nters, processing & fabricatin Based Selection l g Competitiveness g activities together with the analysis of ecoN drivers to de velop & impl a strategy to uti lise domestic SS of minerals MINDIVER/CQ/CS/049-18 / Ec Facilitating Downstream Sec Consultant Qualifi onomic impact analysis (and IDA / 59900 tor Development & Enhancin Post Limited 220,000.00 0.00 Canceled 2017-03-12 2017-03-26 2017-04-25 2017-05-30 2017-11-26 cation Selection Economic Linkages)in the Mi g Competitiveness ning Sector MINDIVER/CQ/CS/047-18 / In ternational Consultant to Pro vide technical assistance on t Establishing a Strong Found Consultant Qualifi Open - Internationa he geological and mineralizat IDA / 59900 ation for Mining Sector Deve Post 200,000.00 0.00 Canceled 2017-09-19 2018-05-24 2017-10-10 2017-11-23 2017-12-23 2018-01-27 2018-07-26 cation Selection l ion characterisation of pegm lopment atites with potentials of Lithi um, metals & REE in the Mini ng sector NG-MINDIVER-132-CS-QCBS / Engagement of Firm to dev Facilitating Downstream Sec elop strategy and Design pro Quality And Cost- Open - Internationa IDA / 59900 tor Development & Enhancin Prior 750,000.00 0.00 Canceled 2019-08-25 2019-10-18 2019-09-15 2019-10-29 2019-11-26 2019-12-26 2020-01-30 2020-03-05 2021-03-05 grammes to support educatio Based Selection l g Competitiveness n, training and expansion of skills necessary for the devel opment of the Mining Sector. NG-MINDIVER-139-CS-QCBS / Consultancy services for th Facilitating Downstream Sec e Local Capacity building in E Quality And Cost- Under Implement IDA / 59900 tor Development & Enhancin Post Open - National 400,000.00 0.00 2019-09-30 2019-09-10 2019-10-21 2020-06-30 2019-12-04 2020-10-06 2020-01-01 2020-11-17 2020-01-31 2020-03-06 2020-04-10 2021-04-10 nvironmental management f Based Selection ation g Competitiveness or regulators and Practitioner s in the Nigerian Mineral and Mining Sector MINDIVER/QCBS/CS/003-17 / Establishing a Strong Found Consultancy for Geological A Quality And Cost- Open - Internationa IDA / 59900 ation for Mining Sector Deve Prior 3,000,000.00 0.00 Canceled 2018-02-05 2018-07-23 2018-02-26 2018-04-18 2018-05-16 2018-06-15 2018-07-20 2018-08-24 2021-08-23 dvisory Services (TA embed) Based Selection l lopment in the Mining and Steel secto r MINDIVER/QCBS/CS/007-18 / Consultancy for the develop Establishing a Strong Found ment of a comprehensive act Quality And Cost- IDA / 59900 ation for Mining Sector Deve Post Open - National 450,000.00 0.00 Canceled 2018-02-15 2018-03-26 2018-03-08 2018-04-21 2018-05-19 2018-06-18 2018-07-23 2018-08-27 2019-08-27 ion plan to create opportuniti Based Selection lopment es for women in the mining a nd steel sector and to mitigat e risks that are unique to wo men MINDIVER/QCBS/CS/004-18 / Establishing a Strong Found Consultancy to provide skills Quality And Cost- IDA / 59900 ation for Mining Sector Deve Prior Open - National 6,000,000.00 0.00 Canceled 2018-02-01 2018-07-23 2018-02-22 2018-04-07 2018-05-05 2018-06-04 2018-07-09 2018-08-13 2019-08-13 building and education suppo Based Selection lopment rt for mining sector develop ment to MMSD Page 8 NG-MINDIVER-147931-CS-C Q / Engagement of an adviso ry firm to undertake an asses Establishing a Strong Found Consultant Qualifi Open - Internationa sment of the identified prosp IDA / 59900 ation for Mining Sector Deve Post 300,000.00 0.00 Canceled 2019-12-31 2020-03-20 2020-01-21 2020-03-05 2020-04-04 2020-05-09 2020-11-05 cation Selection l ective mineral targets and mi lopment ning assets selected as pote ntial Proof of Concept suppor t and/or investment promotio n  NG-MINDIVER-151185-CS-Q CBS / Engagement of a firm t o design a special incubation Facilitating Downstream Sec Quality And Cost- Open - Internationa programme to create viable, IDA / 59900 tor Development & Enhancin Prior 600,000.00 0.00 Canceled 2019-12-31 2020-01-21 2020-03-05 2020-04-02 2020-05-02 2020-06-06 2020-07-11 2021-04-07 Based Selection l homegrown junior mining co g Competitiveness mpanies and the incorporatio n of an SPV for investing in b rownfield mines developmen t NG-MINDIVER-147944-CS-Q CBS / Engagement of a Cons Establishing a Strong Found Quality And Cost- Open - Internationa Under Implement ultant to support the MMSD i IDA / 59900 ation for Mining Sector Deve Post 500,000.00 0.00 2020-01-20 2020-03-16 2020-02-10 2020-03-25 2020-04-22 2020-05-22 2020-06-26 2020-07-31 2022-07-31 Based Selection l ation n analyzing and implementin lopment g a Roadmap for economic c orridor development NG-MINDIVER-114360-CS-C QS / Engagement of Consulti ng Firm to carry out a Gende Facilitating Downstream Sec Consultant Qualifi r impact assessment and de IDA / 59900 tor Development & Enhancin Post Limited 250,000.00 0.00 Canceled 2019-10-16 2019-09-19 2019-10-30 2019-11-29 2020-01-03 2020-07-01 cation Selection velopment of a comprehensi g Competitiveness ve action plan to create oppo rtunities for women in the mi ning and steel sector NG-MINDIVER-151-CS-QCBS / Engagement of Consulting F irm to undertake the prepara tion of (Abbreviated) Resettle Facilitating Downstream Sec Consultant Qualifi ment Action Plan (ARAP) for IDA / 59900 tor Development & Enhancin Post Limited 150,000.00 0.00 Canceled 2019-09-15 2019-09-13 2019-09-29 2019-10-29 2019-12-03 2020-03-02 cation Selection Ladi Kwali pottery centre and g Competitiveness Environmental and Social Ma nagement Plan (ESMP) for La di Kwali, NGSA Kaduna, NGRL Kaduna, NIMG Jos & NMDC Jo s. NG-MINDIVER-165414-CS-Q CBS / Engagement of a Cons ulting Firm to Conduct a Gen der Impact Assessment of Mi Facilitating Downstream Sec Quality And Cost- Open - Internationa nDiver Project and the Nigeri IDA / 59900 tor Development & Enhancin Post 275,000.00 221,247.27 Signed 2020-04-30 2020-04-14 2020-05-11 2020-06-16 2020-06-24 2021-01-13 2020-07-22 2021-03-05 2020-08-21 2021-03-29 2020-09-25 2021-04-12 2020-10-30 2021-07-31 2021-10-30 Based Selection l an Mining Sector and to Deve g Competitiveness lop a Comprehensive Action Plan to Create Opportunities for Women in the Mining and Steel Sector and to Mitigate Risks NG-MINDIVER-147944-QCBS -CS / Engagement of a Consu Establishing a Strong Found Quality And Cost- Open - Internationa ltant to support the MMSD in IDA / 59900 ation for Mining Sector Deve Prior 750,000.00 854,069.22 Signed 2020-04-15 2020-05-07 2020-05-06 2020-07-15 2020-06-19 2021-03-08 2020-07-17 2021-04-15 2020-08-16 2021-06-14 2020-09-20 2021-09-07 2020-10-25 2021-10-04 2022-10-25 Based Selection l analyzing and implementing lopment a Roadmap for economic corr idor development NG-MINDIVER-147931-CS-Q CBS / Engagement of an advi sory firm to undertake an ass Establishing a Strong Found Quality And Cost- Open - Internationa Under Implement essment of the identified pro IDA / 59900 ation for Mining Sector Deve Prior 750,000.00 0.00 2020-04-15 2020-04-23 2020-05-06 2020-07-15 2020-06-19 2020-07-17 2020-08-16 2020-09-20 2020-10-25 2021-10-25 Based Selection l ation spective mineral targets and lopment mining assets selected as po tential proof of concept supp ort and/or investment promo tion MINDIVER/QCBS/CS/029-18 / Establishing a Strong Found Quality And Cost- Open - Internationa Design, develop and implem IDA / 59900 ation for Mining Sector Deve Prior 1,500,000.00 0.00 Canceled 2018-01-12 2018-02-02 2018-03-18 2018-04-15 2018-05-15 2018-06-19 2018-07-24 2019-07-24 Based Selection l ent an integrated MMIS for th lopment e mining sector NG-MINDIVER-115028-CS-C QS / / Consulting firm to carr y out enhancements to the N Facilitating Downstream Sec Consultant Qualifi igerian Mineral Resources De IDA / 59900 tor Development & Enhancin Post Open - National 200,000.00 0.00 Canceled 2020-03-31 2020-04-21 2020-06-04 2020-07-04 2020-08-08 2021-02-04 cation Selection cision Support System (NMR g Competitiveness DSS) including Transaction A reas in an Open System Archi tecture- NG-MINDIVER-200688-CS-Q CBS / Engagement of a consu Facilitating Downstream Sec lting firm to support the MMS Quality And Cost- Open - Internationa Under Implement IDA / 59900 tor Development & Enhancin Prior 650,000.00 0.00 2020-11-30 2021-01-25 2020-12-21 2021-03-10 2021-02-03 2021-03-03 2021-04-02 2021-05-07 2021-06-11 2022-06-11 D in implementing a strategy Based Selection l ation g Competitiveness for the development of Barite and Tin Industries in Nigeria. MINDIVER/CQ/CS/088-18 / E ngagement of Consultant to Establishing a Strong Found Consultant Qualifi Support the MMSD in develo IDA / 59900 ation for Mining Sector Deve Post Open - National 100,000.00 0.00 Canceled 2018-11-20 2018-11-29 2018-12-11 2019-01-24 2019-02-23 2019-03-30 2019-09-26 cation Selection ping and implementing a stra lopment tegy to revive the Tin Industr y in Nigeria NG-MINDIVER-107441-CS-C QS / Engagement of Consulta Facilitating Downstream Sec Consultant Qualifi nt to design and implement a IDA / 59900 tor Development & Enhancin Post Limited 175,000.00 0.00 Canceled 2019-05-14 2019-05-13 2019-05-28 2019-06-27 2019-08-01 2020-01-28 cation Selection Framework to restructure an g Competitiveness d reposition the Women in Mi ning in Nigeria MINDIVER/CQ/CS/209-19 / C onsultancy to design and imp Facilitating Downstream Sec Consultant Qualifi lement safer and cleaner min IDA / 59900 tor Development & Enhancin Post Open - National 300,000.00 0.00 Canceled 2019-05-01 2019-05-28 2019-05-22 2019-09-24 2019-07-05 2019-08-04 2019-09-08 2020-03-06 cation Selection ing programmes, efficient tec g Competitiveness hnologies and practices in th e mining and steel sector MINDIVER/QCBS/CS-057/18 / Needs assessment and evalu Facilitating Downstream Sec Quality And Cost- Open - Internationa ation for accrediting and cert IDA / 59900 tor Development & Enhancin Prior 3,000,000.00 0.00 Canceled 2018-02-15 2019-05-01 2018-03-08 2019-05-23 2018-04-21 2018-05-19 2018-06-18 2018-07-23 2018-08-27 2021-08-26 Based Selection l ifying laboratories including g Competitiveness operationalization geological research laboratories NG-MINDIVER-184765-CS-C QS / Engagement of a consul Facilitating Downstream Sec Consultant Qualifi Open - Internationa ting firm to support the MMS IDA / 59900 tor Development & Enhancin Post 200,000.00 0.00 Canceled 2020-07-24 2020-08-14 2020-09-27 2020-10-27 2020-12-01 2021-05-30 cation Selection l D in implementing a strategy g Competitiveness for the development of the B arite Industry in Nigeria. Page 9 NG-MINDIVER-210664-CS-C QS / Engagement of consulti Establishing a Strong Found ng firm to undertake the pre Consultant Qualifi IDA / 59900 ation for Mining Sector Deve Post Limited 200,000.00 206,476.94 Signed 2021-02-04 2021-03-07 2021-02-18 2021-05-11 2021-03-20 2021-07-28 2021-04-24 2021-07-19 2021-10-21 paration of Environmental an cation Selection lopment d Social Management Plan (E SMP) as part of NIMEP extens ion NG-MINDIVER-210845-CS-C Q / Engagement of a Consult Facilitating Downstream Sec Consultant Qualifi Under Implement ant to Identify 20 prioritized IDA / 59900 tor Development & Enhancin Post Open - National 200,000.00 0.00 2021-02-11 2021-02-12 2021-03-04 2021-02-18 2021-04-17 2021-04-16 2021-05-17 2021-06-21 2021-12-18 cation Selection ation Abandoned Mine Sites in Nig g Competitiveness eria and Develop an Action Pl an for their Rehabilitation MINDIVER/QCBS/CS/023B-19 / Consultancy to assess and Facilitating Downstream Sec build capacity in mining finan Quality And Cost- IDA / 59900 tor Development & Enhancin Prior Open - National 500,000.00 0.00 Canceled 2019-06-05 2019-09-10 2019-06-26 2019-12-04 2019-08-09 2019-09-06 2019-10-06 2019-11-10 2019-12-15 2020-12-14 cing through design and impl Based Selection g Competitiveness ementation of training progra mmes and support within fin ancing institutions NG-MINDIVER-221903-CS-Q CBS / Consultancy to assess Facilitating Downstream Sec and build capacity in mining f Quality And Cost- Open - Internationa Under Implement IDA / 59900 tor Development & Enhancin Post 350,000.00 0.00 2021-03-15 2021-03-22 2021-04-05 2021-04-08 2021-05-19 2021-06-23 2021-06-16 2021-08-10 2021-07-16 2021-08-10 2021-08-20 2021-09-24 2022-06-21 inancing through design and Based Selection l ation g Competitiveness implementation of training pr ogrammes and support withi n financing institutions NG-MINDIVER-278370-CS-C QS / Engagement of Consulta nt for the engineering design , preparation of Bill of Quanti Establishing a Strong Found Consultant Qualifi Under Implement ties (BOQ) and Supervision of IDA / 59900 ation for Mining Sector Deve Post Limited 250,000.00 0.00 2022-02-27 2022-03-04 2022-03-13 2022-04-12 2022-05-17 2023-02-11 cation Selection ation the National Institute of Mini lopment ng and Geosciences, (NIMG) J os and the Remodelling of M odern Core Shed for the Nati onal Geological Survey Agen cy NG-MINDIVER-278444-CS-C QS / Engagement of Consulti Facilitating Downstream Sec Consultant Qualifi Under Implement ng firm to provide transactio IDA / 59900 tor Development & Enhancin Post Limited 250,000.00 0.00 2022-02-28 2022-04-19 2022-03-14 2022-04-13 2022-05-18 2022-11-14 cation Selection ation n advisory services for the La g Competitiveness di Kwali centre Concession NG-MINDIVER-278442-CS-Q CBS / Engagement of firm to Establishing a Strong Found provide technical assistance Quality And Cost- Open - Internationa IDA / 59900 ation for Mining Sector Deve Prior 4,800,000.00 0.00 Under Review 2022-03-01 2022-03-09 2022-03-22 2022-03-18 2022-05-05 2022-05-31 2022-06-02 2022-07-14 2022-07-02 2022-09-29 2022-08-06 2022-12-20 2022-09-10 2023-09-10 and supervise the carrying o Based Selection l lopment ut geochemical mapping of s elected areas under the proo f of concept in Nigeria NG-MINDIVER-278438-CS-Q Facilitating Downstream Sec Quality And Cost- CBS / Engagement of Consult IDA / 59900 tor Development & Enhancin Post Open - National 500,000.00 0.00 Canceled 2022-02-28 2022-03-04 2022-03-21 2022-05-04 2022-06-01 2022-07-01 2022-08-05 2022-09-09 2023-09-09 Based Selection ing Firm for Domestic Invest g Competitiveness ment facilitation. NG-MINDIVER-289144-CS-Q CBS / Engagement of an advi Facilitating Downstream Sec Quality And Cost- Open - Internationa Under Implement sory firm to carry out Mining i IDA / 59900 tor Development & Enhancin Prior 2,000,000.00 0.00 2022-04-15 2022-05-19 2022-05-06 2022-05-30 2022-06-19 2022-10-17 2022-07-17 2022-11-29 2022-08-16 2023-02-28 2022-09-20 2022-10-25 2023-10-25 Based Selection l ation nvestment facilitation activiti g Competitiveness es on acquired geological inf ormation. NG-MINDIVER-295393-CS-Q CBS / Engagement of a Cons Establishing a Strong Found ulting Firm to undertake the Quality And Cost- Under Implement IDA / 59900 ation for Mining Sector Deve Post Open - National 750,000.00 0.00 2022-05-19 2022-05-23 2022-06-09 2022-06-26 2022-07-23 2022-09-21 2022-08-20 2022-11-02 2022-09-19 2022-12-08 2022-10-24 2022-12-20 2022-11-28 2023-05-27 Design, Development and Op Based Selection ation lopment erationalization of an Environ mental and Social Informatio n System (ESIS) NG-MINDIVER-200721-CS-C Facilitating Downstream Sec Consultant Qualifi QS / Engagement of External IDA / 59900 tor Development & Enhancin Post Limited 50,000.00 0.00 Canceled 2020-10-30 2020-11-13 2020-12-13 2021-01-17 2021-07-16 cation Selection auditor for the Mindiver Proje g Competitiveness ct NG-MINDIVER-278441-CS-Q CBS / Engagement of a Mana Facilitating Downstream Sec gement Consulting Firm for C Quality And Cost- IDA / 59900 tor Development & Enhancin Post Open - National 400,000.00 0.00 Canceled 2022-03-13 2022-03-24 2022-04-03 2022-05-17 2022-06-14 2022-07-14 2022-08-18 2022-09-22 2023-09-22 hange Management and Cap Based Selection g Competitiveness ability Transfer in MMSD to e nsure the sustainability of Mi nDiver Activities. NG-MINDIVER-300335-CS-Q CBS / ENGAGEMENT OF A CO Establishing a Strong Found NSULTING FIRM FOR THE MA Quality And Cost- Open - Internationa Under Implement IDA / 59900 ation for Mining Sector Deve Post 800,000.00 0.00 2022-06-27 2022-06-22 2022-07-18 2022-08-11 2022-08-31 2022-10-27 2022-09-28 2022-12-07 2022-10-28 2022-12-02 2023-01-06 2023-10-03 RKET ASSESSMENT AND BAT Based Selection l ation lopment TERY STORAGE VALUE–CHAI N CREATION FOR MARKET TR ANSFORMATION IN NIGERIA INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MINDIVER/SS/CS/001-17 / Up grading and automation of th Establishing a Strong Found e MCO for online applications IDA / 59900 ation for Mining Sector Deve Prior Direct Selection Direct 700,000.00 504,718.66 Under Review 2018-01-16 2018-03-06 2018-02-02 2018-04-12 2018-04-08 2018-10-01 2018-10-05 , e-recording, archiving & est lopment ablishment of the Mining Cad astre Offices in the Six Geo-P olitical Zones MINDIVER/IC/CS/005-18 / Re Establishing a Strong Found view the existing Strategic E Individual Consult IDA / 59900 ation for Mining Sector Deve Post Limited 100,000.00 39,888.00 Signed 2018-01-25 2017-06-29 2018-02-08 2018-03-27 2018-03-01 2018-05-01 2018-04-05 2019-05-15 2018-11-01 nvironmental and Social Asse ant Selection lopment ssment (SESA) and update w here necessary MINDIVER/IC/CS/010-18 / De Facilitating Downstream Sec Individual Consult velopment of Small Grants M IDA / 59900 tor Development & Enhancin Post Limited 60,000.00 17,124.80 Completed 2018-02-08 2017-06-19 2018-02-13 2018-02-28 2018-03-06 2018-04-12 2018-04-10 2018-06-01 2018-10-07 2019-11-13 ant Selection anual for the Mining and Stee g Competitiveness l Sector. MINDIVER/IC/CS/038-18 / En Project Management and Co Individual Consult Under Implement IDA / 59900 Post Limited 50,000.00 0.00 2017-11-01 2017-06-29 2017-11-06 2018-03-21 2017-11-27 2019-07-30 2018-01-01 2018-06-30 vironmental Safeguard Speci ordination ant Selection ation alist MINDIVER/SS/CS//044-17 / C Establishing a Strong Found onsultant to design a workpla IDA / 59900 ation for Mining Sector Deve Prior Direct Selection Direct 150,000.00 0.00 Canceled 2018-03-15 2018-03-30 2018-06-03 2018-11-30 n for the Implementation of lopment Mineral Assets around NIOMC O Page 10 MINDIVER/IC/CS-037/18 / So Project Management and Co Individual Consult IDA / 59900 Post Limited 50,000.00 0.00 Canceled 2018-01-25 2018-01-30 2018-02-20 2018-03-27 2018-09-23 cial Safeguard Specialist ordination ant Selection MINDIVER/SS/CS-056/18 / En gagement of an Advisory Fir Facilitating Downstream Sec m to convert Analogue Datas IDA / 59900 tor Development & Enhancin Prior Direct Selection Direct 480,000.00 1,107,929.94 Under Review 2018-01-31 2018-07-23 2018-02-22 2018-08-08 2018-04-28 2019-08-05 2018-10-25 ets into Digital Format and in g Competitiveness stallation of IT infrastructure and Data systems at the Nig eria Geological Survey Agenc y MINDIVER/IC/CS/017-18 / An alysis, development and impl ementation of adequate diss Establishing a Strong Found Individual Consult emination results for geoscie IDA / 59900 ation for Mining Sector Deve Post Limited 100,000.00 109,900.00 Signed 2018-03-05 2018-07-16 2018-03-10 2018-06-28 2018-03-31 2018-08-16 2018-05-05 2020-10-01 2018-11-01 ant Selection nces activities and to transfe lopment r knowledge to all interested stakeholders, via organizing seminars /conferences, MINDIVER/IC/CS/024-18 / As Facilitating Downstream Sec sesment of Recommendation Individual Consult Under Implement IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 0.00 2018-02-19 2017-11-20 2018-02-24 2018-03-17 2018-04-21 2018-10-18 on SMDF restructuring and In ant Selection ation g Competitiveness vestment Framework MINDIVER/CQ/CS/048-18 / N ational Consultant to assist I nternational Consultant to Pr Establishing a Strong Found Individual Consult ovide technical assistance on IDA / 59900 ation for Mining Sector Deve Post Limited 75,000.00 33,676.97 Signed 2018-02-01 2018-04-24 2018-02-06 2018-04-27 2018-02-27 2019-05-07 2018-04-03 2019-04-15 2018-09-30 ant Selection the geological and mineraliza lopment tion characterisation of pegm atites with potentials of Lithi um, metals & REE in the Mini ng sector MINDIVER/IC/CS/077-18 / Na tional Consultant for the Pro motion of Mining Projects an Establishing a Strong Found Individual Consult d Facilitation of the Nigerian IDA / 59900 ation for Mining Sector Deve Post Limited 50,000.00 41,305.00 Signed 2018-08-15 2018-08-16 2018-08-29 2018-09-03 2018-09-19 2018-10-15 2018-10-24 2018-11-01 2019-04-22 ant Selection Delegation Participation in N lopment ational and International Mini ng Conferences, Workshops and Trade shows. MINDIVER/IC/CS/076-18 / En gagement of an Individual Co nsultant to Conduct Training Establishing a Strong Found Individual Consult and Capacity Building Needs IDA / 59900 ation for Mining Sector Deve Post Limited 50,000.00 0.00 Canceled 2018-08-13 2018-08-16 2018-08-27 2018-09-17 2018-10-22 2019-04-20 ant Selection Assessment to the personnel lopment of the Ministry of Mines and S teel Development and its Ag encies MINDIVER/DS/CS/078-18 / En Facilitating Downstream Sec Individual Consult gagement of Mining Cadastre IDA / 59900 tor Development & Enhancin Post Open 50,000.00 0.00 Canceled 2018-11-20 2019-01-08 2019-01-29 2019-03-05 2019-09-01 ant Selection Expert g Competitiveness MINDIVER/IC/CS/037-18 / En Facilitating Downstream Sec Individual Consult Under Implement gagement of Social Safeguar IDA / 59900 tor Development & Enhancin Post Open 50,000.00 0.00 2018-11-20 2018-12-10 2019-01-08 2019-01-29 2019-03-05 2019-09-01 ant Selection ation d Specialist for MinDiver Proj g Competitiveness ect MINDIVER/IC/CS/090-18 / En Establishing a Strong Found Individual Consult Under Implement gagement of Geological Anal IDA / 59900 ation for Mining Sector Deve Post Open 100,000.00 0.00 2018-11-30 2019-03-21 2019-01-18 2019-02-08 2019-03-15 2019-09-11 ant Selection ation yst for Mindiver Project lopment MINDIVER/SS/CS/001-18 / Up Facilitating Downstream Sec grade of the Mining Cadastre IDA / 59900 tor Development & Enhancin Post Direct Selection Direct 30,000.00 0.00 Canceled 2019-12-01 2022-11-01 2019-12-11 2020-02-14 2020-08-12 office for Online Application - g Competitiveness SYSTEM MAINTENANCE SERV ICES MINDIVER/IC/CS/123-19 / En gagement of Consultant to pr Facilitating Downstream Sec Individual Consult epare the Grievance Redress IDA / 59900 tor Development & Enhancin Post Limited 75,000.00 0.00 Canceled 2019-05-01 2019-05-06 2019-05-27 2019-07-01 2019-12-28 ant Selection Mechanism (GRM) for the Min g Competitiveness Diver Project and the Mining Sector. MINDIVER/CQ/CS/051-17 / Pr Project Management and Co Individual Consult omotion and Export Strategis IDA / 59900 Post Limited 80,000.00 0.00 Canceled 2018-01-17 2018-01-22 2018-02-12 2018-03-19 2019-03-19 ordination ant Selection t for the Mining Sector MINDIVER/IC/CS/075-018 / In Establishing a Strong Found dividual Consultant for super Individual Consult IDA / 59900 ation for Mining Sector Deve Post Limited 25,000.00 0.00 Canceled 2018-08-13 2018-08-16 2018-08-18 2018-09-08 2018-10-13 2019-04-11 vision of renovation works of ant Selection lopment dimension stone lab of NGSA in Kaduna. NG-MINDIVER-104552-CS-IN DV / Engagement of an indivi Facilitating Downstream Sec dual Consultant to carry out Individual Consult IDA / 59900 tor Development & Enhancin Post Limited 25,000.00 0.00 Canceled 2019-05-08 2019-05-13 2019-06-03 2019-07-08 2020-01-04 needs assessment and Evalu ant Selection g Competitiveness ation of Equipment of the Nat ional Metallurgical Developm ent centre, Jos NG-MINDIVER-103076-CS-IN Facilitating Downstream Sec DV / Engagement of Individu Individual Consult IDA / 59900 tor Development & Enhancin Post Limited 45,000.00 0.00 Canceled 2019-07-01 2019-07-06 2019-07-27 2019-08-31 2020-02-27 al Consultant to carry out Ge ant Selection g Competitiveness nder impact assesment in Mi ning Sector NG-MINDIVER-114471-CS-C DS / Eengagement of a Cons ulting firm to carry out enhan Facilitating Downstream Sec cements to the Nigerian Mine IDA / 59900 tor Development & Enhancin Prior Direct Selection Direct 200,000.00 0.00 Canceled 2019-05-25 2019-06-04 2019-08-08 2020-02-04 ral Resources Decision Suppo g Competitiveness rt System (NMRDSS) includin g Transaction Areas in an Op en System Architecture NG-MINDIVER-130-CS-IC / En Facilitating Downstream Sec Individual Consult Under Implement gagement of M& E Specialist IDA / 59900 tor Development & Enhancin Post Limited 45,000.00 0.00 2019-08-30 2019-09-10 2019-09-04 2019-09-25 2019-10-30 2020-10-29 ant Selection ation for Mindiver Project g Competitiveness NG-MINDIVER-152-CS-IC / Int Facilitating Downstream Sec ernational Technical Assistan Individual Consult Under Implement IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 0.00 2019-10-08 2019-10-21 2019-10-13 2019-12-13 2019-11-03 2019-12-08 2020-06-05 t for National Steel Raw Mate ant Selection ation g Competitiveness rial Exploration Agency (NSR MEA), Kaduna MINDIVER/IC/CS/099-19 / En Establishing a Strong Found gagement of International Co Individual Consult IDA / 59900 ation for Mining Sector Deve Post Limited 75,000.00 0.00 Canceled 2019-05-01 2019-05-28 2019-05-22 2019-06-12 2019-07-17 2020-01-13 nsultant for Quality Assuranc ant Selection lopment e of the Geodata Centre of N GSA Page 11 MINDIVER/IC/CS/073/018 / In dividual Consultant for the su pervision and quality assuran Establishing a Strong Found ce of the upgrade and autom Individual Consult IDA / 59900 ation for Mining Sector Deve Post Limited 60,000.00 0.00 Canceled 2018-07-16 2018-07-18 2018-07-26 2018-08-16 2018-09-20 2019-09-20 ation of Mining Cadastre Offi ant Selection lopment ce for online applications, e-r ecording, archiving and the e stablishment of Mining Cadas tre Offices in six geopolitical zones NG-MINDIVER-133782-CS-IN DV / Engagement of Individu al Consultant for the supervis Establishing a Strong Found ion and Quality assurance Of Individual Consult Under Implement IDA / 59900 ation for Mining Sector Deve Post Limited 100,000.00 0.00 2019-09-25 2019-10-10 2019-09-30 2019-10-21 2019-11-25 2020-05-23 the establishment of a Nigeri ant Selection ation lopment an geodata centre at NGSA and the upgrade and automa tion of MCO for online applica tions, e-recording, archiving. NG-MINDIVER-138854-CS-IN DV / Engagement of Individu Facilitating Downstream Sec Individual Consult Under Implement al Consultant for the prepara IDA / 59900 tor Development & Enhancin Post Limited 30,000.00 0.00 2019-10-15 2019-12-16 2019-10-20 2020-01-27 2019-11-10 2020-05-29 2019-12-15 2020-06-12 ant Selection ation tion of (Abbreviated) Resettl g Competitiveness ement Action Plan for Ladi K wali Pottery Centre. NG-MINDIVER-90376-CS-IND Establishing a Strong Found V / Engagement of a Consult Individual Consult IDA / 59900 ation for Mining Sector Deve Post Limited 50,000.00 0.00 Canceled 2019-01-05 2019-01-10 2019-01-31 2019-03-07 2019-09-03 ant to develop Grievance Re ant Selection lopment dress Mechanism for the Min Diver Project MINDIVER/IC/CS/072/018 / N ational Consultant to design Facilitating Downstream Sec Individual Consult and implement a strategy for IDA / 59900 tor Development & Enhancin Post Limited 60,000.00 0.00 Canceled 2018-07-16 2019-10-15 2018-07-31 2018-08-21 2018-09-25 2019-09-25 ant Selection developing Nigeria's gemsto g Competitiveness ne and jewellery industry NG-MINDIVER-147-CS-IC / En gagement of Expert Geoscie ntist to provide technical sup port and advice to the Nigeri Facilitating Downstream Sec Individual Consult an Geological Survey Agency IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 124,620.00 Signed 2019-08-30 2020-10-27 2019-09-04 2020-12-18 2019-09-25 2021-02-01 2019-10-30 2021-05-01 2020-04-27 ant Selection (NGS)- Consultancy for Geolo g Competitiveness gical Advisory Services (TA E mbedded) for the mining and Steel Sector (NGSA)- (Techni cal Advisor for NGSA) NG-MINDIVER-147922-CS-C Project Management and Co DS / Engagement of Procure IDA / 59900 Prior Direct Selection Direct 85,000.00 105,385.06 Signed 2020-01-01 2019-12-23 2020-01-11 2019-12-15 2020-03-16 2020-01-01 2021-12-31 ordination ment Specialist for Mindiver Project NG-MINDIVER-147926-CS-C DS / Engagement of Monitori Project Management and Co IDA / 59900 Prior Direct Selection Direct 85,000.00 106,982.79 Signed 2019-12-16 2019-12-23 2019-12-26 2019-12-15 2020-02-29 2020-01-01 2021-12-31 ng and Evaluation Specialist f ordination or Mindiver Project NG-MINDIVER-147927-CS-C Facilitating Downstream Sec DS / Engagement of Technica IDA / 59900 tor Development & Enhancin Prior Direct Selection Direct 100,000.00 184,450.00 Signed 2019-12-01 2019-12-19 2019-12-11 2019-12-15 2020-02-14 2020-01-01 2021-12-31 l Advisor for Mindiver Project g Competitiveness NG-MINDIVER-147928-CS-C Facilitating Downstream Sec DS / Engagement of Mineral IDA / 59900 tor Development & Enhancin Prior Direct Selection Direct 85,000.00 105,385.06 Signed 2019-12-18 2019-12-19 2019-12-28 2019-12-15 2020-03-02 2020-01-01 2021-12-31 Sector Policy and Governanc g Competitiveness e Advisor NG-MINDIVER-145-CS-IC / En gagement of an Individual Co nsultant for the Supervision a Facilitating Downstream Sec Individual Consult Under Implement nd Quality Assurance of the IDA / 59900 tor Development & Enhancin Post Limited 60,000.00 0.00 2019-12-12 2020-01-09 2019-12-17 2020-01-20 2020-01-07 2021-08-20 2020-02-11 2021-02-10 ant Selection ation Design and implementation o g Competitiveness f a Strategy for the Develop ment of Nigeria’sGemstone a nd Jewellery Industry NG-MINDIVER-128772-CS-IN Facilitating Downstream Sec Individual Consult DV / Engagement of Geoscie IDA / 59900 tor Development & Enhancin Post Open 100,000.00 0.00 Canceled 2019-12-15 2020-02-02 2020-02-23 2020-03-29 2020-05-04 ant Selection nce Advisor for the Mindiver g Competitiveness Project MINDIVER/IC/CS/98-19 / Con Facilitating Downstream Sec Individual Consult sultant Geologist to asssist M IDA / 59900 tor Development & Enhancin Post Limited 100,000.00 0.00 Canceled 2019-05-01 2019-04-05 2019-05-06 2019-05-27 2019-07-01 2019-12-28 ant Selection MSD on Geology and GIS g Competitiveness NG-MINDIVER-138853-CS-IN DV / Engagement of Individu Facilitating Downstream Sec Individual Consult al Geophycist to assist the Mi IDA / 59900 tor Development & Enhancin Prior Direct 180,000.00 0.00 Canceled 2019-10-31 2019-11-10 2019-12-01 2020-01-05 2021-01-04 ant Selection nistry of Mines and Steel Dev g Competitiveness elopment (MMSD) on Geolog y and GIS NG-MINDIVER-151182-CS-IN DV / Engagement of an exper Establishing a Strong Found t Consultant to develop a str Individual Consult Under Implement IDA / 59900 ation for Mining Sector Deve Post Open 45,000.00 0.00 2020-01-14 2020-01-09 2020-03-03 2020-03-24 2020-04-28 2020-10-25 ategy for the development of ant Selection ation lopment baryte production, processin g and marketing in the minin g and steel sector NG-MINDIVER-147932-CS-C Facilitating Downstream Sec DS / Engagement of a Consul Individual Consult Under Implement IDA / 59900 tor Development & Enhancin Post Direct 110,000.00 0.00 2020-01-14 2020-01-09 2020-01-24 2019-11-15 2020-02-14 2020-01-15 2020-03-20 2021-03-20 tant Expert Geoscientist to a ant Selection ation g Competitiveness ssist MMSD on Geology and GIS. NG-MINDIVER-156383-CS-IN Facilitating Downstream Sec Individual Consult Under Implement DV / Engagement of Procure IDA / 59900 tor Development & Enhancin Post Limited 50,000.00 0.00 2020-01-31 2020-09-01 2020-02-05 2020-02-26 2020-04-01 2021-03-27 ant Selection ation ment Consultant for Mindiver g Competitiveness Project NG-MINDIVER-148367-CS-IN DV / Engagement of Individu al consultant to undertake th Facilitating Downstream Sec e preparation of Environment Individual Consult IDA / 59900 tor Development & Enhancin Post Limited 45,000.00 34,577.80 Signed 2020-02-25 2020-03-04 2020-03-01 2020-03-05 2020-03-22 2020-03-25 2020-04-26 2020-04-21 2020-06-25 al and Social Management Pl ant Selection g Competitiveness an (ESMPs) for the rehabilitat ion and construction works of priority infrastructures in Nig er, Kaduna and Plateau State s. NG-MINDIVER-156800-CS-IN DV / Engagement of an Indivi Facilitating Downstream Sec dual Consultant to develop a Individual Consult IDA / 59900 tor Development & Enhancin Post Direct 100,000.00 0.00 Canceled 2020-02-05 2020-02-15 2020-03-07 2020-04-11 2020-10-08 strategy for the development ant Selection g Competitiveness of barite production, processi ng and marketing in Nigeria. Page 12 NG-MINDIVER-165582-CS-IN Facilitating Downstream Sec Individual Consult Under Implement DV / Engagement of Social S IDA / 59900 tor Development & Enhancin Post Direct 55,000.00 0.00 2020-04-30 2020-04-15 2020-05-10 2020-04-17 2020-05-31 2020-07-05 2021-01-01 ant Selection ation afeguard Specialist for MinDi g Competitiveness ver Project NG-MINDIVER-165583-CS-IN Facilitating Downstream Sec Individual Consult Under Implement DV / Engagement of Environ IDA / 59900 tor Development & Enhancin Post Direct 55,000.00 0.00 2020-04-30 2020-04-15 2020-05-10 2020-05-31 2020-07-05 2021-01-01 ant Selection ation mental Specialist for Mindive g Competitiveness r Project NG-MINDIVER-165592-CS-IN DV / Engagement of Internati Facilitating Downstream Sec onal Individual Consultant to Individual Consult Under Implement IDA / 59900 tor Development & Enhancin Post Open 175,000.00 0.00 2020-04-15 2020-06-12 2020-06-03 2020-06-24 2020-07-29 2021-01-25 develop a strategy for the De ant Selection ation g Competitiveness velopment of Gemstone and Jewellery trading and Marketi ng platform MINDIVER-CDS-CS--046-202 0 / Consulting services for th Project Management and Co Under Implement IDA / 59900 Prior Direct Selection Direct 850,000.00 0.00 2020-03-19 2020-05-07 2020-03-29 2020-05-15 2020-06-02 2020-11-29 e engagement of project ma ordination ation nagement firm for the projec t management unit NG-MINDIVER-168712-CS-IN DV / Engagement of National Facilitating Downstream Sec Individual Consult Under Implement Consultant to develop a strat IDA / 59900 tor Development & Enhancin Post Open 75,000.00 0.00 2020-05-12 2020-12-20 2020-06-30 2021-02-02 2020-07-21 2021-02-02 2020-08-25 2021-08-25 ant Selection ation egy for the Development of g Competitiveness Gemstone and Jewellery tradi ng and Marketing platform NG-MINDIVER-133-CS-CDS / Engagement of firm for the M Facilitating Downstream Sec anagement, Maintenance an IDA / 59900 tor Development & Enhancin Post Direct Selection Direct 200,000.00 0.00 Canceled 2019-10-04 2019-10-14 2019-12-18 2020-06-15 d integration of all Data syst g Competitiveness em for the Mining Sector. NG-MINDIVER-146-CS-IC / Pr Facilitating Downstream Sec ocurement of Consultant to p Individual Consult IDA / 59900 tor Development & Enhancin Post Limited 60,000.00 0.00 Canceled 2019-08-30 2019-09-04 2019-09-25 2019-10-30 2020-04-27 rovide MMSD Advisory servic ant Selection g Competitiveness es on change management NG-MINDIVER-184767-CS-C DS / Consulting firm to carry out enhancements to the Nig Facilitating Downstream Sec erian Mineral Resources Deci IDA / 59900 tor Development & Enhancin Post Direct Selection Direct 200,000.00 346,843.83 Signed 2020-08-05 2021-04-01 2020-08-15 2021-04-16 2020-10-19 2021-07-25 2021-10-19 sion Support System (NMRDS g Competitiveness S) including Transaction Area s in an Open System Architec ture- NG-MINDIVER-200691-CS-IN DV / Consultancy to design a Facilitating Downstream Sec nd implement safer and clea Individual Consult Under Implement IDA / 59900 tor Development & Enhancin Post Limited 120,000.00 0.00 2020-11-24 2020-10-27 2020-11-29 2020-12-20 2021-01-24 2021-10-21 ner mining programmes, effi ant Selection ation g Competitiveness cient technologies and practi ces in the mining and steel s ector NG-MINDIVER-200701-CS-C Facilitating Downstream Sec DS / Engagement of Technica Individual Consult Under Implement IDA / 59900 tor Development & Enhancin Post Direct 55,000.00 0.00 2020-10-29 2020-10-27 2020-11-08 2020-11-29 2021-01-03 2021-07-02 l advisor to the Ministry of Mi ant Selection ation g Competitiveness nes and Steel Development o n Mindiver affairs. NG-MINDIVER-200708-CS-IN Project Management and Co Individual Consult Under Implement DV / Extension of contract for IDA / 59900 Post Direct 70,000.00 0.00 2020-10-23 2020-10-27 2020-11-02 2020-11-23 2020-12-28 2022-03-28 ordination ant Selection ation the National Technical Adviso r for Mindiver NG-MINDIVER-210843-CS-IN DV / Engagement of Consulta nt for the Assessment of Con flicts associated with mining Facilitating Downstream Sec Individual Consult operations and its impacts to IDA / 59900 tor Development & Enhancin Post Limited 120,000.00 73,573.30 Signed 2021-01-21 2021-02-04 2021-02-04 2021-02-05 2021-02-25 2021-03-28 2021-04-01 2021-04-23 2021-09-28 ant Selection the host mining communities g Competitiveness in selected Geopolitical zone s with an emphasis on failed Community Development (C D) implementation NG-MINDIVER-211128-CS-C Facilitating Downstream Sec DS / Engagement of consulta Under Implement IDA / 59900 tor Development & Enhancin Post Direct Selection Direct 40,000.00 0.00 2021-01-24 2021-01-29 2021-02-03 2021-02-04 2021-04-09 2021-10-06 nt for the management of da ation g Competitiveness shboard and asset register fo r Mindiver project NG-MINDIVER-211138-CS-IN DV / Contract Extension-Enga Facilitating Downstream Sec gement of Technical Advisor Individual Consult Pending Impleme IDA / 59900 tor Development & Enhancin Post Direct 195,000.00 0.00 2021-01-01 2021-01-11 2021-02-01 2021-03-08 2021-09-04 (General Purpose) to the Gov ant Selection ntation g Competitiveness ernment of Nigeria for the “M inDiver” Project- John Eyre NG-MINDIVER-211146-CS-IN DV / Extention of contract - E ngagement of a Consultant f Facilitating Downstream Sec or the Promotion of Mining Pr Individual Consult Pending Impleme IDA / 59900 tor Development & Enhancin Post Direct 130,000.00 0.00 2021-01-01 2021-01-11 2021-02-01 2021-03-08 2021-09-04 ojects and Facilitation of the ant Selection ntation g Competitiveness Nigerian Delegation Participa tion in International Mining C onferences, Workshops, and Trade shows - Emma Kinder NG-MINDIVER-211148-CS-IN DV / Extension of Services for Facilitating Downstream Sec Consultant Expert Geologist t Individual Consult Pending Impleme IDA / 59900 tor Development & Enhancin Post Direct 140,000.00 0.00 2021-01-01 2021-01-11 2021-02-01 2021-03-08 2021-09-04 o assist the Project and the M ant Selection ntation g Competitiveness inistry of Mines and Steel De velopment (MMSD) on Geolo gy and GIS- Francisco Iguala da NG-MINDIVER-211934-CS-IN DV / Consultancy services to support the NMCT in establis Facilitating Downstream Sec Individual Consult Under Implement hing an incorporated Trust a IDA / 59900 tor Development & Enhancin Post Limited 70,000.00 0.00 2021-01-29 2021-07-15 2021-02-12 2021-03-05 2021-04-09 2021-10-06 ant Selection ation nd the enhancement of down g Competitiveness stream mineral processing fo r Ladi kwali pottery centre, S uleja Niger State NG-MINDIVER-211134-CS-C DS / Extension of Consultanc Facilitating Downstream Sec Under Implement y services for the provision of IDA / 59900 tor Development & Enhancin Post Direct Selection Direct 450,000.00 0.00 2021-02-14 2021-02-12 2021-02-24 2021-01-15 2021-04-30 2021-06-05 ation Project Management office fu g Competitiveness nction for the Mindiver Projec t -Ernst and Young Page 13 NG-MINDIVER-200705-NC-RF B / Engagement of a Consult ant to conduct a needs asses sment and implementation of Establishing a Strong Found Under Implement Accreditation/Certification of IDA / 59900 ation for Mining Sector Deve Prior Direct Selection Direct 700,000.00 0.00 2021-02-15 2021-02-25 2021-03-06 2021-03-02 2021-05-10 2021-11-06 ation the National Geosciences Re lopment search Laboratory (NGRL) Ce ntre Kaduna for the attainme nt of ISO 9001 and 17025 sta ndards including Capacity Bu ilding. NG-MINDIVER-216702-CS-IN Facilitating Downstream Sec DV / Engagement of an indivi Individual Consult Under Implement IDA / 59900 tor Development & Enhancin Post Open 75,000.00 0.00 2021-03-02 2021-06-28 2021-04-20 2021-05-11 2021-06-15 2022-06-15 dual National Consultant for t ant Selection ation g Competitiveness he Topomaps Mapping activit y NG-MINDIVER-216699-CS-IN Facilitating Downstream Sec DV / Engagement of Individu Individual Consult Under Implement IDA / 59900 tor Development & Enhancin Post Open 75,000.00 0.00 2021-03-02 2021-06-28 2021-04-20 2021-05-11 2021-06-15 2022-06-15 al National Consultant for the ant Selection ation g Competitiveness Airborne Geophysical Survey activity. NG-MINDIVER-234529-CS-IN DV / ENGAGEMENT OF INDIVI DUAL CONSULTANT TO PROV Facilitating Downstream Sec Individual Consult Under Implement IDE SUSTAINABLE POTTERY A IDA / 59900 tor Development & Enhancin Post Open 75,000.00 0.00 2021-07-25 2021-09-01 2021-09-12 2021-09-02 2021-10-03 2021-11-07 2022-05-06 ant Selection ation DVISORY SERVICE, PRODUCT g Competitiveness ION, AND TRAINING ADVISOR Y SERVICES FOR THE LADI K WALI POTTERY CENTER NG-MINDIVER-234527-CS-IN DV / engagement of an Indivi dual Consultant for Independ ent Peer Review of the Upgra Facilitating Downstream Sec Individual Consult Under Implement de and Automation of Mining IDA / 59900 tor Development & Enhancin Post Limited 50,000.00 0.00 2021-07-05 2021-07-04 2021-07-10 2021-07-31 2021-09-04 2021-12-03 ant Selection ation Cadastre Office for Online Ap g Competitiveness plications, E-recording, Archi ving and Establishment of Mi ning Cadastre Offices in the Six Geopolitical Zones NG-MINDIVER-234528-CS-IN Facilitating Downstream Sec DV / Engagement of an indivi Individual Consult Under Implement IDA / 59900 tor Development & Enhancin Post Open 75,000.00 0.00 2021-07-18 2021-07-15 2021-09-05 2021-09-26 2021-10-31 2022-04-29 dual heritage advisor for Ladi ant Selection ation g Competitiveness kwali Pottery centre NG-MINDIVER-278432-CS-IN Facilitating Downstream Sec DV / Engagement of external Individual Consult Under Implement IDA / 59900 tor Development & Enhancin Post Limited 30,000.00 0.00 2022-02-28 2022-02-22 2022-03-05 2022-03-07 2022-03-26 2022-04-30 2022-10-27 Consultant for the audit of th ant Selection ation g Competitiveness e Ladi Kwali ARAP implement ation document NG-MINDIVER-278433-CS-C DS / Provision of Support, Mai ntenance and coordination a Facilitating Downstream Sec greement for ICT Hardware f Under Implement IDA / 59900 tor Development & Enhancin Post Direct Selection Direct 25,000.00 0.00 2022-02-28 2022-03-29 2022-03-10 2022-05-14 2023-05-14 or the Formalisation of Artisa ation g Competitiveness nal Miners & Remote sensing activity located Abuja- (Service Level Agreement co ntract-SLA). NG-MINDIVER-278434-CS-C DS / Provision of Support, Mai ntenance and coordination a Facilitating Downstream Sec Under Implement greement for ICT Hardware f IDA / 59900 tor Development & Enhancin Post Direct Selection Direct 25,000.00 0.00 2022-02-28 2022-03-29 2022-03-10 2022-05-14 2023-05-14 ation or the Establishment of Geod g Competitiveness ata Centre – Abuja and Kadu na- (Service Level Agreemen t contract). NG-MINDIVER-278441-DS-RF P / Engagement of firm for ch Facilitating Downstream Sec ange management and capa Under Implement IDA / 59900 tor Development & Enhancin Post Direct Selection Direct 400,000.00 0.00 2022-06-08 2022-06-03 2022-06-18 2022-04-13 2022-08-22 2023-02-18 bility transfer in the Ministry ation g Competitiveness of Mines and Steel Developm ent (MMSD) to ensure sustain ability of MinDiver activities. NG-MINDIVER-338874-CS-C DS / Engagement of a Nation al Consulting Firm for the Bat Facilitating Downstream Sec ch 3 Master training in Jewell Under Implement IDA / 59900 tor Development & Enhancin Post Direct Selection Direct - National 350,000.00 0.00 2023-02-20 2023-02-15 2023-03-02 2023-05-06 2023-11-02 ery making and design and t ation g Competitiveness he implementation of a Traini ng Programme for the Devel opment of Nigeria’s Gemston e and Jewellery Industry NG-MINDIVER-358963-CS-C Project Management and Co DS / Procurement of Financia IDA / 59900 Post Direct Selection Direct - National 10,000.00 0.00 Under Review 2023-04-27 2023-05-11 2023-05-07 2023-07-11 2023-09-09 ordination l Management Specialist NG-MINDIVER-361260-CS-IN Facilitating Downstream Sec DV / Procurement of a Consul Individual Consult Pending Impleme IDA / 59900 tor Development & Enhancin Post Limited 50,000.00 0.00 2023-05-31 2023-06-05 2023-06-26 2023-07-31 2024-01-27 tant to carry out an Environm ant Selection ntation g Competitiveness ental and social audit of the Mindiver Project. NG-MINDIVER-361298-CS-C DS / Engagement of consulta nt for the update and implem entation of the Mindiver grie Facilitating Downstream Sec vance redress mechanism (M IDA / 59900 tor Development & Enhancin Post Direct Selection Direct - National 75,000.00 0.00 Under Review 2023-05-18 2023-05-31 2023-05-28 2023-08-01 2024-01-28 -GRM) to a sector-fit GRM an g Competitiveness d undertake the pilot implem entation of citizen’s engage ment and social accountabilit y integration in the mining se ctor. Page 14 Procurement Plan Project information: Pacific Regional Oceanscape Program – Economic Resilience (PROPER) Project (P178237) Project Implementation agency: National Oceanic Resource Management Authority (NORMA) Date of the Procurement Plan: March 15, 2022 Period covered by this Procurement Plan: March 15, 2022 – March 15, 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Code of 1988, as amended, and Financial Management Regulations, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1. The procurement is open to all eligible firms from any country; 2. The request for bids/request for proposals document shall require the Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting signed contracts, confirming application of, and compliance with, the Bank's Anti-Corruption Guidelines, including without limitation the Bank's right to sanction and the Bank's inspection and audit rights; 3. Publication of contract award information; 4. Rights for the Bank to review procurement documentation and activities; and 5. An effective complaints mechanism. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Work) Goods: is not applicable; Works: is not applicable. PROCUREMENT Micronesia, Federated States of : Federated States of Micronesia: Pacific Islands Regional Oceanscape Program - Second Phase for Economic Resilience PLAN General Information Country: Micronesia, Federated States of Bank’s Approval Date of the Original Procurement Plan: 2022-03-15 Revised Plan Date(s): (comma delineated, leave blank if 2023-05-24 none) Project ID: P178237 GPN Date: Project Name: Federated States of Micronesia: Pacific Islands Regional Oceanscape Program - Second Phase for Economic Resilience Loan / Credit No: / Department of Finance and Administration Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FM-DOFA-282383-GO-RFQ / Request for Quota Open - Internationa Single Stage - One E / Post 25,000.00 0.00 Signed 2022-04-27 2022-06-22 2022-12-19 Office Equipment and Furnitu tions l nvelope re NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FM-DOFA-282358-CS-CQS / Design Preparation Consulta Consultant Qualifi Open - Internationa nt - Design preparation work / Post 300,000.00 0.00 Signed 2022-03-22 2022-08-15 2022-04-12 2022-08-17 2022-05-10 2022-11-28 2022-05-24 2023-01-25 2022-06-21 2023-06-21 cation Selection l in collaboration with DOFA, D RD, NORMA and other stakeh olders FM-DOFA-361309-CS-CQS / Design and Supervision: NOR Consultant Qualifi Open - Internationa / Post 100,000.00 0.00 Under Review 2023-06-19 2023-06-20 2023-07-09 2023-07-30 2023-08-06 2023-08-27 2024-02-23 MA Oceanic Fisheries Central cation Selection l ized Services Center FM-DOFA-361315-CS-CQS / Consultant Qualifi Open - Internationa Design and Supervision: Chu / Post 100,000.00 0.00 Under Review 2023-06-19 2023-06-20 2023-07-09 2023-07-30 2023-08-06 2023-08-27 2024-02-23 cation Selection l uk State Marina/Central Mark et FM-DOFA-365968-CS-CQS / Design and Supervision : Chu Consultant Qualifi Open - Internationa Under Implement / Post 100,000.00 0.00 2023-06-19 2023-06-20 2023-07-09 2023-07-30 2023-08-06 2023-08-27 2024-02-23 uk State Recyclable Waste S cation Selection l ation egregation/Collection & Repu rposing Center FM-DOFA-365969-CS-CQS / Consultant Qualifi Open - Internationa Design and Supervision : Poh / Post 100,000.00 0.00 Under Review 2023-06-19 2023-06-20 2023-07-09 2023-07-30 2023-08-06 2023-08-27 2024-02-23 cation Selection l npei State Marina/ Boat Pool INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FM-DOFA-280800-CS-CDS / P / Post Direct Selection Direct 130,000.00 0.00 Signed 2022-02-24 2022-02-16 2022-03-06 2022-02-16 2022-04-08 2023-04-08 MU Project Manager FM-DOFA-280804-CS-CDS / P / Post Direct Selection Direct 25,000.00 0.00 Signed 2022-02-27 2022-02-16 2022-03-09 2022-02-16 2022-04-11 2023-04-11 MU Project Officer FM-DOFA-280805-CS-INDV / Individual Consult / Post Open 18,000.00 0.00 Signed 2022-03-01 2022-02-16 2022-04-03 2022-06-01 2022-04-10 2022-06-03 2022-05-06 2023-05-06 PMU Project Assistant ant Selection FM-DOFA-282364-CS-INDV / Individual Consult National Safeguards/Coordin / Post Open 5,000.00 0.00 Canceled 2022-04-22 2022-05-23 2022-06-06 2022-07-02 2023-07-02 ant Selection ation Consultant – Pohnpei FM-DOFA-282365-CS-INDV / Individual Consult National Safeguards/Coordin / Post Open 5,000.00 0.00 Canceled 2022-04-22 2022-05-23 2022-06-06 2022-07-02 2023-07-02 ant Selection ation Consultant – Chuuk FM-DOFA-282368-CS-INDV / Individual Consult National Safeguards/Coordin / Post Open 5,000.00 0.00 Canceled 2022-04-22 2023-02-13 2022-05-23 2022-06-06 2022-07-02 2023-07-02 ant Selection ation Consultant – Yap FM-DOFA-282377-CS-INDV / POM Consultant – developme Individual Consult / Post Open 5,000.00 0.00 Canceled 2022-06-22 2022-08-26 2022-07-23 2022-08-06 2022-09-01 2023-09-01 nt of the Project Operations ant Selection Manual (POM) and training th e PMU staff on the POM FM-DOFA-282378-CS-INDV / Individual Consult / Post Open 30,000.00 0.00 Canceled 2022-06-22 2022-08-10 2022-08-31 2022-10-05 2023-10-05 Monitoring and Evaluation Co ant Selection nsultant FM-DOFA-282379-CS-INDV / Individual Consult / Post Open 30,000.00 0.00 Signed 2022-06-22 2022-06-24 2022-07-23 2022-12-20 2022-08-06 2023-01-03 2022-09-01 2023-09-01 Gender Specialist Consultant ant Selection Page 1 FM-DOFA-282381-CS-INDV / Legal Consultant – conduct le Individual Consult / Post Open 30,000.00 0.00 Completed 2022-04-22 2022-07-12 2022-05-23 2022-10-28 2022-06-06 2022-11-03 2022-07-02 2023-07-02 2023-02-07 gal assessment on UNCLOS A ant Selection rticle 73 compliance FM-DOFA-282382-CS-INDV / Individual Consult / Post Open 30,000.00 0.00 Canceled 2022-03-22 2022-03-16 2022-05-10 2022-05-31 2022-07-05 2023-07-05 PMU Project Finance Officer ant Selection FM-DOFA-282380-CS-INDV / Individual Consult / Post Open 30,000.00 0.00 Canceled 2022-04-22 2022-06-10 2022-07-01 2022-08-05 2023-02-01 Civil Engineering Consultant ant Selection FM-DOFA-282359-CS-INDV / Individual Consult Feasibility study to inform PR / Post Open 40,000.00 0.00 Canceled 2022-04-22 2022-05-25 2022-06-08 2022-07-04 2023-07-04 ant Selection OPER oceanic fisheries comp onent FM-DOFA-282360-CS-INDV / Individual Consult Feasibility study to inform PR / Post Open 40,000.00 0.00 Canceled 2022-04-22 2022-05-23 2022-06-06 2022-07-02 2023-07-02 ant Selection OPER Coastal Fisheries comp onent FM-DOFA-282366-CS-INDV / Individual Consult National Safeguards/Coordin / Post Open 5,000.00 0.00 Canceled 2022-04-22 2022-05-23 2022-06-06 2022-07-02 2023-07-02 ant Selection ation Consultant – Kosrae FM-DOFA-340901-CS-INDV / Individual Consult Open - Internationa Under Implement Consultancy: Development of / Post 15,000.00 0.00 2023-02-07 2023-02-24 2023-03-14 2023-06-05 2023-03-28 2023-06-13 2023-04-21 2024-04-20 ant Selection l ation a Project Operations Manual FM-DOFA-345427-CS-INDV / Individual Consult National Facilitation/Coordina / Post Open - National 5,000.00 0.00 Canceled 2023-02-27 2023-02-28 2023-03-19 2023-04-02 2023-04-28 2024-04-27 ant Selection tion Consultant – Yap State FM-DOFA-362110-CS-INDV / Individual Consult Pending Impleme Environment & Social Safegu / Post Limited 40,000.00 0.00 2023-05-17 2023-05-22 2023-06-05 2023-07-03 2023-12-30 ant Selection ntation ards Consultant FM-DOFA-282361-CS-INDV / Feasibility study to inform PR Individual Consult / Post Open 40,000.00 0.00 Canceled 2022-04-22 2022-05-23 2022-06-06 2022-07-02 2023-07-02 OPER activities on climate ch ant Selection ange and ecosystem issues i n fisheries FM-DOFA-291395-CS-INDV / Environment/Social Safeguar ds Consultant – development Individual Consult Open - Internationa / Post 40,000.00 0.00 Canceled 2023-02-28 2023-04-18 2023-05-09 2023-06-13 2024-06-12 of an environmental and soci ant Selection l al safeguards framework/pla n; training staff and stakehol ders FM-DOFA-282362-CS-INDV / Individual Consult Feasibility study to inform Pol / Post Open 40,000.00 0.00 Canceled 2022-04-22 2022-05-23 2022-06-06 2022-07-02 2023-07-02 ant Selection lution and fisheries in PROPE R project FM-DOFA-282396-CS-CQS / F isheries Investment Policy - I Individual Consult Open - Internationa / Post 30,000.00 0.00 Under Review 2023-06-19 2023-06-15 2023-07-22 2023-07-27 2023-08-31 2024-02-27 mplementation Plan ant Selection l Consultant Page 2 PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, Desert Locust Response Project, P173702 Project Implementation agency: Ministry of Agriculture, Ethiopia Date of the Procurement Plan: April 6, 2012 Period covered by this Procurement Plan: April 2020 to March 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Directives of the Federal and Regional Governments of Ethiopia, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. For national open competitive procurement the following requirement apply: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts; e. contracts with an appropriate allocation of responsibilities, risks, and liabilities; f. publication of contract award information; g. rights for the Bank to review procurement documentation and activities; h. an effective complaints mechanism; and i. maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Secondhand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable For national open competitive procurement the following requirement apply: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts; e. contracts with an appropriate allocation of responsibilities, risks, and liabilities; f. publication of contract award information; g. rights for the Bank to review procurement documentation and activities; h. an effective complaints mechanism; and i. maintenance of records of the Procurement Process. cable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. Since the project is an emergency response project the provisions of Procurement in Situations of Urgent Need of Assistance shall apply. PROCUREMENT Eastern and Southern Africa : Emergency Locust Response Program PLAN General Information Country: Eastern and Southern Africa 2022-11-23 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173702 GPN Date: 2020-12-03 Project Name: Emergency Locust Response Program Loan / Credit No: IDA / 66480 Mandera County Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MANDERA COUNTY-3266 56-GO-RFQ / SUPPLY OF 1200 Livelihoods Protection and R Request for Quota Single Stage - One E 0 BALES HAY OF 15KG'S EAC IDA / 66480 Post Limited 80,500.00 0.00 Canceled 2022-12-07 2023-01-03 2023-05-03 ehabilitation tions nvelope H FOR EMERGENCY LIVESTO CK FEEDS FOR DROUGHT MIT IGATION. KE-MANDERA COUNTY-3621 66-GO-RFQ / Supply and Deli very of 1780 bags each 50kg Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66480 Post Limited 64,070.00 0.00 2023-05-19 2023-06-20 2023-10-18 of drought pellets (Range cu ehabilitation tions nvelope ementation bes) livestock feeds supplem ents for Mandera North Sub- county, Mandera county. KE-MANDERA COUNTY-3490 31-GO-RFQ / Supply and Deli very of 1700 bags of (50 kg's Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66480 Post Limited 64,666.00 0.00 2023-03-17 2023-04-14 2023-06-13 ) each drought pellets livesto ehabilitation tions nvelope ementation ck feeds supplement for dro ught mitigation Mandera cou nty. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, Urban Productive Safety Net and Jobs Project (P169943) Project Implementation agency: Ministry of Labor and Social Affairs (MoLSA), Ministry of Urban Development and Construction (MoUDC), Urban Job Creation and Food Security Agency (UJCFSA) Date of the Procurement Plan: November 2020. Period covered by this Procurement Plan: December 2020 to December 2021. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Section 33(1)(a) from page 35-48 of the Proclamation Number 649/2009 of the Ethiopian Federal Government Procurement and Property Administration Proclamation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. • Open Advertising of the procurement opportunity at the national level; • The procurement is open to eligible firms from any country; • The request for bids/Proposal documents shall require that bidders/proposers submitting Bids/Proposal present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of and compliance with the Bank’s Anti-Corruption Guidelines, including without limitation the bank’s right to sanction and the Bank’s inspection and audit right; • Contracts with an appropriate allocation of responsibilities, risks and liabilities; • Application of Standstill period and Publication of contract award information; • Maintenance of records of the procurement process; and • The Bank has the right to review procurement documentation and activities. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Is applicable for those contracts identified in the Procurement Plan; Works: Is applicable for those contracts identified in the Procurement Plan. Other Relevant Procurement Information. None PROCUREMENT Ethiopia : Urban Productive Safety Net and Jobs Project PLAN General Information Country: Ethiopia 2022-08-01 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169943 GPN Date: 2020-12-18 Project Name: Urban Productive Safety Net and Jobs Project Loan / Credit No: IDA / D7320 Ministry of Urban Development and Infrastructure Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ET-HAWASSA-347872-CW-RF Request for Quota Foster Urban Youth Employ Request for Quota Single Stage - One E Pending Imp 2023-07-1 Q / Refurbishment of Menahe IDA / D7320 Post Limited tions (Non Bank-S 65,000.00 0.00 2023-03-16 2023-04-14 ment tions nvelope lementation 3 rya OSSC in Hawassa by com PD) ponent 2.2 ET-HARER-347873-CW-RFQ / Request for Quota Foster Urban Youth Employ Request for Quota Single Stage - One E Pending Imp 2023-06-1 Refurbishment of Aboker OS IDA / D7320 Post Limited tions (Non Bank-S 49,000.00 0.00 2023-03-16 2023-04-14 ment tions nvelope lementation 3 SC in Harar city by compone PD) nt 2.2 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOUDI-300547-GO-RFQ / Expand the Urban Productiv Procurement of 10 pcs of lapt Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 17,695.00 0.00 2022-06-29 2022-08-10 2022-09-09 op computer for Ethiopia refu tions nvelope ementation Urban Environment gees and returnees service ET-HAWASSA-325903-GO-DI Expand the Urban Productiv Under Imple R / Procurement of Cement f IDA / D7320 e Safety Net to Improve the Post Direct Selection Direct - National 207,700.00 0.00 2022-11-22 2023-04-10 2022-11-26 2022-12-26 2023-02-24 mentation or Hawassa City Urban Environment ET-HAWASSA-325907-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Q / Procurement of Safety Ma IDA / D7320 e Safety Net to Improve the Post Limited 46,035.00 0.00 2022-11-27 2022-12-27 2023-02-25 tions nvelope ementation terials for Hawassa City Urban Environment ET-HAWASA-325909-GO-RFQ Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl / Procurement of Angle Iron, IDA / D7320 e Safety Net to Improve the Post Limited 31,730.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation RHS and reinforced Bar Urban Environment ET-HAWASA-325918-GO-RFQ Institutional Strengthening, Request for Quota Single Stage - One E Pending Impl / Procurement of Local Const IDA / D7320 Project Management and Mo Post Limited 66,650.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation ruction Materials for Hawasa nitoring and Evaluation City ET-HAWASSA-325919-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Q / Procurement of Hallow Co IDA / D7320 e Safety Net to Improve the Post Limited 26,500.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation ncrete Block Urban Environment ET-HAWASA-325922-GO-RFQ Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl / Procurement of Morale, Perl IDA / D7320 e Safety Net to Improve the Post Limited 6,000.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation in and timber Urban Environment ET-HAWASSA-325924-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Under Imple Q / Procurement of metal doo IDA / D7320 e Safety Net to Improve the Post Limited 35,900.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope mentation r, window and Sign board Urban Environment ET-YIRGALEM-325940-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Q / Procurement of Hand tool IDA / D7320 e Safety Net to Improve the Post Limited 8,550.00 0.00 2022-11-20 2022-12-19 2023-01-18 tions nvelope ementation s for Yirhalem city Urban Environment ET-YIRGALEM-325945-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Q / Procurement of Safety m IDA / D7320 e Safety Net to Improve the Post Limited 48,000.00 0.00 2022-11-26 2022-12-25 2023-01-24 tions nvelope ementation aterials for Yirgalem City Urban Environment ET-YIRGALEM-325946-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Q / Procurement of Industrial IDA / D7320 e Safety Net to Improve the Post Limited 28,400.00 0.00 2022-11-26 2022-12-25 2023-01-24 tions nvelope ementation Construction Materials Urban Environment ET-YIIRGALEM-325948-GO-R Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl FQ / Procurement of Local Co IDA / D7320 e Safety Net to Improve the Post Limited 15,200.00 0.00 2022-11-20 2022-12-19 2023-01-18 tions nvelope ementation nstruction Materials Urban Environment ET-HARAR-326742-GO-RFQ / Expand the Urban Productiv Request for Quota Single Stage - One E Under Imple Procurement of Hand tools fo IDA / D7320 e Safety Net to Improve the Post Limited 11,570.00 0.00 2022-11-26 2022-12-25 2023-01-24 tions nvelope mentation r Harar City Urban Environment ET-HARAR-326823-GO-RFQ / Expand the Urban Productiv Request for Quota Single Stage - One E Under Imple Procurement of Safety Materi IDA / D7320 e Safety Net to Improve the Post Limited 15,500.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope mentation als for Harar City Urban Environment ET-HARAR-326826-GO-RFQ / Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Procurement of Construction IDA / D7320 e Safety Net to Improve the Post Limited 32,600.00 0.00 2022-11-26 2023-01-07 2023-02-06 tions nvelope ementation materials Urban Environment ET-HARAR-326828-GO-DIR / Expand the Urban Productiv Procurement of Cement for H IDA / D7320 e Safety Net to Improve the Post Direct Selection Direct - National 9,300.00 0.00 Canceled 2022-11-21 2022-11-26 2022-12-13 2023-01-12 arar City Urban Environment ET-MIZAN AMAN-326829-GO Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl -RFQ / Procurement of hand t IDA / D7320 e Safety Net to Improve the Post Limited 27,675.00 0.00 2022-11-26 2022-12-25 2023-01-24 tions nvelope ementation ools for Mizan Aman City Urban Environment ET-MIZAN AMAN-326830-GO Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl -RFQ / Procurement of Safety IDA / D7320 e Safety Net to Improve the Post Limited 99,500.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation materials for mizan Aman Cit Urban Environment y ET-TEPI-326831-GO-RFQ / Pr Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl ocurement of hand tools for IDA / D7320 e Safety Net to Improve the Post Limited 27,600.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation Tepi city Urban Environment Page 1 ET-TEPI-326832-GO-RFQ / Pr Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl ocurement of Safety Material IDA / D7320 e Safety Net to Improve the Post Limited 94,100.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation s for Tepi City Urban Environment ET-TEPI-326836-GO-RFQ / Pr Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl ocurement of Construction m IDA / D7320 e Safety Net to Improve the Post Limited 61,500.00 0.00 2022-11-28 2022-12-27 2023-01-26 tions nvelope ementation aterials for Tepi city Urban Environment ET-SEMERA LOGYA-326840- GO-RFQ / Procurement of ha Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl nd tools, safety materials an IDA / D7320 e Safety Net to Improve the Post Limited 7,580.00 0.00 2022-11-27 2023-01-08 2023-07-07 tions nvelope ementation d other construction material Urban Environment s in three lots for Semera log ya city ET-ABEALA-326842-GO-RFQ Expand the Urban Productiv / Procurement of Hand tools, Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 19,000.00 0.00 2022-11-27 2022-12-26 2023-01-25 safety materials and other co tions nvelope ementation Urban Environment nstruction materials for abeal a city by lot system ET-ASOSA-326844-GO-RFQ / Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Procurement of hand tools fo IDA / D7320 e Safety Net to Improve the Post Limited 15,260.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation r Asosa City Urban Environment ET-ASOSA-326846-GO-RFQ / Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Procurement of safety Materi IDA / D7320 e Safety Net to Improve the Post Limited 43,400.00 0.00 2022-11-27 2022-12-25 2023-01-24 tions nvelope ementation als for Asosa City Urban Environment ET-ASOSA-326847-GO-RFQ / Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Procurement of construction IDA / D7320 e Safety Net to Improve the Post Limited 10,000.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation materials Urban Environment ET-GILGEL BELES-326848-G O-RFQ / Procurement of Hand Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl tools, safety materials and co IDA / D7320 e Safety Net to Improve the Post Limited 12,600.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation nstruction materials for Gilge Urban Environment l beles city in three lots ET-GAMBELA-326852-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Q / Procurement of Hand tool IDA / D7320 e Safety Net to Improve the Post Limited 24,700.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation s for gambela city Urban Environment ET-GAMBELAI-326855-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Q / Procurement of safety ma IDA / D7320 e Safety Net to Improve the Post Limited 16,500.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation terials for Gambela city Urban Environment ET-METI-326859-GO-RFQ / Pr Expand the Urban Productiv ocurement of Hand tools, Saf Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 23,650.00 0.00 2022-11-27 2022-12-26 2022-12-29 ety materials and constructio tions nvelope ementation Urban Environment n materials for meti city in th ree lots ET-MOUDI-326890-GO-RFQ / Institutional Strengthening, Request for Quota Single Stage - One E Procurement of Scanners for IDA / D7320 Project Management and Mo Post Limited 95,000.00 0.00 Signed 2022-11-28 2023-03-10 2022-12-27 2023-02-10 tions nvelope cities nitoring and Evaluation ET-MOUDI-326892-GO-RFQ / Institutional Strengthening, Request for Quota Single Stage - One E Under Imple Procurement of laptop comp IDA / D7320 Project Management and Mo Post Limited 95,000.00 0.00 2022-11-28 2023-03-10 2022-12-27 2023-01-26 tions nvelope mentation uter nitoring and Evaluation ET-MOUDI-326896-GO-RFB / Procurement of Computer, Sc Foster Urban Youth Employ Single Stage - One E Under Imple IDA / D7320 Post Request for Bids Open - National 655,400.00 0.00 2022-11-28 2023-06-03 2022-12-03 2023-06-15 2023-01-03 2023-02-02 2023-03-09 2023-05-08 aner, Printer, Copy machine ment nvelope mentation and tablet computer for com ponent 2.2 ET-HAWASSA-336189-GO-RF Q / Procurement of Laptop, P Foster Urban Youth Employ Request for Quota Single Stage - One E Pending Impl rinter, Desktop computer and IDA / D7320 Post Limited 58,175.00 0.00 2023-01-23 2023-02-21 2023-03-23 ment tions nvelope ementation LCD Projectors for Hawassa C ity in Youth Employment, ET-HAWASSA -336190-GO-R FQ / Procurement of Office Fu Foster Urban Youth Employ Request for Quota Single Stage - One E Pending Impl IDA / D7320 Post Limited 385.00 0.00 2023-01-23 2023-02-21 2023-03-13 rniture for Hawwasa City in ment tions nvelope ementation Youth Employment, Expand the Urban Productiv ET-HARER-347871-GO-RFQ / Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 9,300.00 0.00 2023-03-20 2023-04-18 2023-05-18 Procurement of cement tions nvelope ementation Urban Environment ET-MOUDI-321006-GO-RFQ / Expand the Urban Productiv Procurement of digital came Request for Quota Single Stage - One E IDA / D7320 e Safety Net to Improve the Post Limited 12,000.00 0.00 Canceled 2022-10-22 2022-11-16 2022-12-16 ra for Ethiopian refuges and r tions nvelope Urban Environment eturnees service ET-HARER-MOUDI-362247-G Expand the Urban Productiv O-RFQ / Procurement of differ Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 16,350.00 0.00 2023-06-04 2023-07-06 2023-07-21 ent seedlings and fertile soil f tions nvelope ementation Urban Environment or Harer greenery activities ET-GILGEL BELES-MOUDI-36 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 2273-GO-RFQ / Procurement IDA / D7320 e Safety Net to Improve the Post Limited 275.00 0.00 2023-06-04 2023-07-05 2023-07-20 tions nvelope ementation of different seeds for gilgel b Urban Environment eles ET-ASOSSA-MOUDI-362285- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of diff IDA / D7320 e Safety Net to Improve the Post Limited 5,060.00 0.00 2023-06-05 2023-07-06 2023-07-26 tions nvelope ementation erent seeds and seedlings Urban Environment ET-MOUDI- RRS-356027-GO- Expand the Urban Productiv RFQ / Procurement of laptop Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 52,000.00 0.00 2023-06-04 2023-07-03 2023-08-02 computer and tablet for Ethio tions nvelope ementation Urban Environment pian refuges and returnees s ervice ET-MOUDI- RRS-356026-GO- Expand the Urban Productiv RFQ / Procurement of digital Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 16,500.00 0.00 2023-06-04 2023-07-03 2023-07-18 camera for Ethiopian refuges tions nvelope ementation Urban Environment and returnees service ET-MOUDI-362396-GO-RFQ / Institutional Strengthening, Request for Quota Single Stage - One E Pending Impl Procurement of Scaners for E IDA / D7320 Project Management and Mo Post Limited 82,000.00 0.00 2023-06-04 2023-07-03 2023-08-02 tions nvelope ementation merging cities and subcities nitoring and Evaluation in Addis Ababa Page 2 ET-MOUDI-362398-GO-DIR-U Foster Urban Youth Employ Pending Impl N / Procurement of 18 Moter IDA / D7320 Post Direct Selection Direct - National 82,000.00 0.00 2023-05-30 2023-06-20 2023-08-14 2024-02-10 ment ementation Biscle for OSSC ET-HAWASSA-367397-GO-RF Expand the Urban Productiv Q / Procurement of Cement f Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 98,000.00 0.00 2023-06-29 2023-07-28 2023-08-27 or hawassa city for social infr tions nvelope ementation Urban Environment astructure building and main tenance NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-HAWASA-326882-NC-RFQ / Semi Skill for Hawassa city t Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl o construct additional class r IDA / D7320 e Safety Net to Improve the Post Limited 99,000.00 0.00 2022-11-27 2022-12-26 2023-03-11 tions nvelope ementation oom for schools, additional h Urban Environment ealth care Buildings and Gre enery fences ET-YIRGALEM-328433-NC-RF Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Q / Semi Skill for social infra IDA / D7320 e Safety Net to Improve the Post Limited 30,200.00 0.00 2022-12-04 2023-01-08 2023-03-27 tions nvelope ementation structure in Yirgalem city Urban Environment ET-ASOSA-328436-NC-RFQ / Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Semi skill for social infrastruc IDA / D7320 e Safety Net to Improve the Post Limited 5,000.00 0.00 2022-12-04 2023-01-02 2023-03-03 tions nvelope ementation ture in Assosa City Urban Environment ET-GILGEL BELES-328438-N Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl C-RFQ / Semi skill for Social I IDA / D7320 e Safety Net to Improve the Post Limited 3,000.00 0.00 2022-12-04 2023-01-02 2023-03-03 tions nvelope ementation nfrastructure in Gil gel Beles Urban Environment ET-MOUDI-335570-NC-DIR / Institutional Strengthening, Procurement of Third Party s Direct - Internation IDA / D7320 Project Management and Mo Prior Direct Selection 3,200,000.00 0.00 Signed 2023-01-16 2023-02-10 2023-01-21 2023-02-13 2023-02-19 2024-02-19 ervice provider for Tigray Re al nitoring and Evaluation gion in UPSNJP additional Fin ance ET-MOUDI- GILGEL BELES-36 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 2397-NC-RFQ / Semi Skill for IDA / D7320 e Safety Net to Improve the Post Limited 2,500.00 0.00 2023-06-02 2023-07-01 2023-07-31 tions nvelope ementation Commun latrin construction Urban Environment at Gilgel beles CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOUDI-326889-CS-QCBS Institutional Strengthening, Quality And Cost- Pending Impleme / Environmental and social A IDA / D7320 Project Management and Mo Post Open - National 250,000.00 0.00 2022-11-23 2022-12-14 2023-01-27 2023-02-24 2023-03-26 2023-04-30 2023-06-04 2023-08-18 Based Selection ntation udit for 2014 EFY nitoring and Evaluation ET-MOUDI-328491-CS-QCBS Institutional Strengthening, Quality And Cost- Under Implement / Public work review for the y IDA / D7320 Project Management and Mo Post Open - National 220,000.00 0.00 2022-11-29 2023-05-18 2022-12-14 2023-06-15 2023-01-27 2023-02-27 2023-03-29 2023-05-03 2023-06-07 2023-08-21 Based Selection ation ear 2014 EFY nitoring and Evaluation ET-MOUDI-328495-CS-QCBS Institutional Strengthening, Quality And Cost- Under Implement / Procurement Audit for the y IDA / D7320 Project Management and Mo Prior Open - National 200,000.00 0.00 2022-11-30 2022-12-15 2023-01-28 2023-02-28 2023-03-30 2023-05-04 2023-06-08 2023-08-22 Based Selection ation ear 2014 EFY nitoring and Evaluation ET-MOUDI-345014-CS-QCBS Institutional Strengthening, / UPSNJP Multiyear independ Quality And Cost- Open - Internationa Under Implement IDA / D7320 Project Management and Mo Prior 500,000.00 0.00 2023-06-07 2023-06-14 2023-06-22 2023-06-27 2023-07-27 2023-08-28 2023-09-27 2023-10-26 2023-11-24 2026-04-07 ent procurement Audit FY22/ Based Selection l ation nitoring and Evaluation EFY 2014 to FY26/EFY2018" INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOUDI-325892-CS-INDV / Institutional Strengthening, Individual Consult Under Implement Recruit Senior Procurement s IDA / D7320 Project Management and Mo Post Direct - National 16,500.00 0.00 2022-11-14 2023-02-13 2022-11-24 2022-12-09 2023-01-07 2024-01-07 ant Selection ation pecialist/ Consultant nitoring and Evaluation ET-MOUDI-325893-CS-INDV / Institutional Strengthening, Individual Consult Under Implement Recruit Senior Procurement S IDA / D7320 Project Management and Mo Prior Direct - National 16,500.00 0.00 2022-11-15 2023-02-16 2022-11-25 2022-12-10 2023-01-08 2024-01-08 ant Selection ation pecialist/ Consultant nitoring and Evaluation ET-MOUDI-325894-CS-INDV / Institutional Strengthening, Individual Consult Under Implement Recruit Safeguard Specialist f IDA / D7320 Project Management and Mo Post Open - National 8,350.00 0.00 2022-11-15 2023-02-01 2023-01-04 2023-01-25 2023-03-01 2024-02-29 ant Selection ation or Federal PCU nitoring and Evaluation ET-MOUDI-325897-CS-INDV / Recruit Procurement Speciali Institutional Strengthening, st for Federal PCU who will su Individual Consult Pending Impleme IDA / D7320 Project Management and Mo Post Open - National 8,350.00 0.00 2022-11-17 2023-01-05 2023-01-26 2023-03-02 2024-03-01 pport cities in the region of S ant Selection ntation nitoring and Evaluation omale , Benshangul , Gambel a, Afar, South West Ethiopia and Harari ET-SIDAMA-325934-CS-INDV Foster Urban Youth Employ Individual Consult Under Implement / Recruitment of Youth Emplo IDA / D7320 Post Open - National 5,000.00 0.00 2022-11-15 2023-01-13 2023-01-04 2023-01-25 2023-03-01 2024-02-29 ment ant Selection ation yment Specialist for Hawassa City ET-MOUDI-325358-CS-INDV / Institutional Strengthening, Individual Consult Under Implement Recruitment of project coordi IDA / D7320 Project Management and Mo Post Direct - National 20,000.00 0.00 2022-11-29 2023-02-14 2022-12-08 2022-12-29 2023-01-18 2024-01-18 ant Selection ation nator for UPSNJP at Federal P nitoring and Evaluation CU ET-MOUDI-328498-CS-INDV / Institutional Strengthening, Individual Consult Pending Impleme Recruit additional Monitoring IDA / D7320 Project Management and Mo Post Open - National 8,150.00 0.00 2022-11-30 2023-01-19 2023-02-09 2023-03-16 2024-03-15 ant Selection ntation and evaluation specialist at f nitoring and Evaluation ederal PCU Page 3 ET-MOUDI-344999-CS-INDV / Recruit Federal Project Coord Institutional Strengthening, ination Unit Coordinator who Individual Consult Pending Impleme IDA / D7320 Project Management and Mo Post Limited 26,500.00 0.00 2023-03-13 2023-03-18 2023-04-07 2023-04-20 2024-04-19 will responsible for managem ant Selection ntation nitoring and Evaluation ent, coordination and implem entation of all components a nd activities of the UPSNJP ET-MOUDI-345001-CS-INDV / Recruit Senior Procurement S Institutional Strengthening, pecialist/ Consultant at Feder Individual Consult Pending Impleme IDA / D7320 Project Management and Mo Prior Limited 20,000.00 0.00 2023-03-13 2023-03-18 2023-04-07 2023-04-20 2024-04-19 al PCU who will manage and ant Selection ntation nitoring and Evaluation coordinate the over all procu rement activities across all i mplementing institutions. ET-MOUDI-345006-CS-INDV / Recruit Senior Procurement S Institutional Strengthening, pecialist/ Consultant at Feder Individual Consult Pending Impleme IDA / D7320 Project Management and Mo Prior Limited 20,000.00 0.00 2023-03-13 2023-03-18 2023-04-07 2023-04-20 2024-04-19 al PCU who will manage and ant Selection ntation nitoring and Evaluation coordinate the over all procu rement activities across all i mplementing institutions. ET-HARAR-367398-CS-INDV / Institutional Strengthening, Individual Consult Pending Impleme Recruit UPSNJP Safeguard sp IDA / D7320 Project Management and Mo Post Open - National 4,000.00 0.00 2023-06-26 2023-08-15 2023-08-25 2023-09-14 2024-09-13 ant Selection ntation ecialist for Harar city nitoring and Evaluation ET-AFAR-367402-CS-INDV / Institutional Strengthening, Individual Consult Pending Impleme Recruit UPSNJP Safeguard sp IDA / D7320 Project Management and Mo Post Open - National 4,000.00 0.00 2023-06-26 2023-08-15 2023-08-25 2023-09-14 2024-09-13 ant Selection ntation ecialist for cities in Afar Regi nitoring and Evaluation on ET-GAMBELA-367403-CS-IND Institutional Strengthening, Individual Consult Pending Impleme V / Recruit UPSNJP Safeguard IDA / D7320 Project Management and Mo Post Open - National 4,000.00 0.00 2023-06-25 2023-08-14 2023-08-24 2023-09-13 2024-09-12 ant Selection ntation specialist for cities in Gambel nitoring and Evaluation la Region ET-SIDAMA-367404-CS-INDV Institutional Strengthening, Individual Consult Pending Impleme / Recruit UPSNJP Safeguard s IDA / D7320 Project Management and Mo Post Open - National 4,000.00 0.00 2023-06-25 2023-08-14 2023-08-24 2023-09-13 2024-09-12 ant Selection ntation pecialist for cities in Sidama nitoring and Evaluation Region ET-B/GUMUZ-367410-CS-IND Institutional Strengthening, V / Recruit UPSNJP Safeguard Individual Consult Pending Impleme IDA / D7320 Project Management and Mo Post Open - National 4,000.00 0.00 2023-06-26 2023-08-15 2023-08-25 2023-09-14 2024-09-13 specialist for cities in Bensha ant Selection ntation nitoring and Evaluation ngul Gumuz Region ET-SOUTH WEST ETHIOPIA-3 Institutional Strengthening, 67411-CS-INDV / Recruit UPS Individual Consult Pending Impleme IDA / D7320 Project Management and Mo Post Open - National 4,000.00 0.00 2023-06-26 2023-08-15 2023-08-25 2023-09-14 2024-09-13 NJP Safeguard specialist for c ant Selection ntation nitoring and Evaluation ities in South West Ethiopia R egion Page 4 PROCUREMENT PLAN Turkey-Municipal Services Improvement Project Project information: (P169996) Project Implementation General Directorate of ILBANK Agency: Date of the Procurement 04 March 2020 Plan: Period covered by this 04 March 2020 - 31 December 2024 Procurement Plan: Date of General 27 May 2020 Procurement Notice: Bank's Approval Date of 04 March 2020 the Procurement Plan: I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 and revised August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. Any procurement activity under the Project shall not be initiated before it is approved by the Bank through STEP. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Goods, Works and Non-Consulting Services Procurement Method Procurement Method Threshold RFB/Open Default Method (No procurement method threshold) International Goods and Non-consulting Services Contracts less than US$3,000,000 RFB/Open National Works contracts Contracts less than $70,000,000 Goods, Works, Non-Consulting Services RFQ Contracts less than US$500,000 Direct Selection No threshold III. Selection of Consultants Selection Method Selection Method Threshold Quality and Cost Based No selection method threshold Selection (QCBS) Least Cost Selection No selection method threshold (LCS) 1/3 Quality Based Selection No selection method threshold (QBS) Selection Based on Consultants Contracts valued less than $3,000,000 Qualification (CQS) Single Source Selection No selection method threshold of Firms (SSS) Individual Consultants No selection method threshold (IC) Direct Selection No selection method threshold The terms of references of any audit, procurement or legal consultants financed by the project shall be sent to the Bank for its comments. IV. Special Arrangements 1. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. 2. Review Procedure: All the procurements under the project are subject to the Bank’s ex-post review unless otherwise specified in the procurement schedule given below in Section V. 3. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. 4. Mandatory Provisions for Procurement under Bank-Financed Contracts Subject to National Procurement Procedures The procedures to be followed for National Open Competitive Bidding shall be those set forth in the Public Procurement Law of the Borrower (Law No. 4734), as amended from time to time, with the latest amendment dated December 07, 2019 (the “PPL”) notwithstanding anything to the contrary in the Borrower’s Law on Public Procurement Contracts (Law No. 4735), as amended from time to time, with the latest amendment dated January 18, 2019, and subject to the following provisions: A. Eligibility The eligibility of bidders shall be as defined under Section III of the World Bank Procurement Regulations for IPF Borrowers; accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. Bidding shall not be restricted to domestic bidders. No restrictions in respect of eligibility to participate in bidding for contracts shall be placed on the basis of 2/3 nationality of the bidder and/or the origin of goods other than those set forth in paragraph 3.23 of the Procurement Regulations. No restriction of any kind shall be applied to foreign bidders who wish to submit a bid. Bidding shall not be restricted to pre-registered firms, and foreign bidders shall not be required to be registered with local authorities as a prerequisite for submitting bids. Participation shall be allowed from joint ventures on the condition that such joint venture partners will be jointly and severally liable under the contract. Procuring entities shall use bidding documents agreed by the Bank. B. Fraud and Corruption The request for bids/request for proposals document shall require that Bidders/Proposes submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. C. Debarment The Bank may recognize, if requested by the Borrower, exclusion from participation as a result of debarment under the national system, provided that the debarment is for offenses involving fraud and corruption and further provided that the Bank confirms that the particular debarment procedure afforded due process and the debarment decision is final. 5. Procurement of Second-Hand Goods: Not Applicable. 6. Domestic preference (as specified under paragraph 5.51 of the Procurement Regulations): Not applicable. 7. Operational costs will not be considered under procurement implementation which means reasonable incremental expenses directly incurred on account of the implementation, management, and monitoring of the Project by the Borrower; such costs may include, as relevant, and as the Bank may agree, for the following: (a) travel, accommodation, and per diem associated with training, workshop, and study tour participants and trainers, and other training- related miscellaneous costs, all such costs which shall not be covered under Training, and which are based on an Annual Work Plan and Budget agreed with the Bank; (b) Project audits; (c) office supplies; (d) office rental; (e) vehicle rental; (f) office and equipment maintenance and repair; (g) communications; (h) translation and interpretation (not covered under Training); 3/3 (i) travel and Project supervision; (j) publication fees; (k) ownership of intellectual property rights; and (l) other miscellaneous expenses directly associated with the Project and agreed between the Bank and the Borrower. V. Procurement Packages with Methods and Time Schedule The estimated costs in the attached tables (sheets) (including VAT in the Loan). 4/3 PROCUREMENT Turkiye : Municipal Services Improvement Project PLAN General Information Country: Turkiye 2020-06-11 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169996 GPN Date: 2020-05-27 Project Name: Municipal Services Improvement Project Loan / Credit No: IBRD / 90770, TF / B4957 Ilbank PMU Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Request for B KMARAS-W2 / KMARAS-W2 C ids - Small W Environmental Infrastructure Single Stage - One E 2025-11-1 onstruction of Elbistan Water IBRD / 90770 Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-02-25 2022-07-18 2022-03-11 2022-08-05 2022-04-08 2022-08-25 2022-05-06 2022-11-25 2022-06-03 Investments nvelope 4 Network Project nvelope proc ess) Request for B KONYA-W1 / KONYA-W1 Con Environmental Infrastructure Single Stage - One E ids - Small W 2024-03-1 struction of Akşehir Water Su IBRD / 90770 Post Request for Bids Open - National 0.00 Signed 2021-12-28 2022-08-02 2022-01-11 2022-02-08 2022-09-08 2022-03-08 2022-11-08 2022-03-29 Investments nvelope orks SPD (1 e 8 pply Project nvelope proc ess) OSMANİYE-W1 / OSMANİYE- W1 (Lot 1) Construction of Os Request for B maniye (Centrum) Water Sup ids - Small W Environmental Infrastructure Single Stage - One E 2024-08-2 ply and Sewerage Project - W IBRD / 90770 Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2021-12-09 2022-04-28 2021-12-23 2022-06-28 2022-01-20 2022-06-30 2022-02-17 2022-09-22 2022-03-10 Investments nvelope 6 est Part nvelope proc (Lot 2) Construction of Osma ess) niye (Centrum) Water Suppl y and Sewerage Project - Eas t Part Request for B ADANA-W1 / ADANA -W1 Co ids - Small W Environmental Infrastructure Single Stage - One E Pending Imp 2025-12-1 nstruction of Kozan İmamoğl IBRD / 90770 Post Request for Bids Open - National orks SPD (1 e 0.00 2022-10-03 2022-10-17 2022-11-14 2022-12-12 2022-12-26 Investments nvelope lementation 0 u Yedigöze Water Transmissi nvelope proc on Line ess) Request for B ADANA-W3 / ADANA-W3 Con ids - Small W Environmental Infrastructure Single Stage - One E Pending Imp 2025-12-2 struction of Kozan Water Net IBRD / 90770 Post Request for Bids Open - National orks SPD (1 e 0.00 2022-10-17 2022-10-31 2022-11-28 2022-12-26 2023-01-09 Investments nvelope lementation 4 work Project and Pınargözü T nvelope proc ransmission Line ess) Request for B ADANA-W2 / ADANA-W2 Co ids - Small W Environmental Infrastructure Single Stage - One E Pending Imp 2025-11-2 nstruction of Yedigöze Water IBRD / 90770 Post Request for Bids Open - National orks SPD (1 e 0.00 2022-09-15 2022-09-29 2022-10-27 2022-11-24 2022-12-08 Investments nvelope lementation 2 Treatment Plant nvelope proc ess) Request for B KONYA-W2 / KONYA-W2 Con ids - Small W Environmental Infrastructure Single Stage - One E 2025-02-2 struction of Ilgın & Çumra Wa IBRD / 90770 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2022-09-21 2023-01-25 2022-10-19 2022-11-16 2023-03-21 2022-12-14 2023-05-05 2023-01-04 Investments nvelope 2 stewater Treatment Plants nvelope proc ess) Request for B KONYA-W3 / KONYA-W3 Con ids - Small W Environmental Infrastructure Single Stage - One E 2025-03-0 struction of Cumra Wastewat IBRD / 90770 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-12-21 2022-01-04 2022-02-01 2022-03-01 2022-03-22 Investments nvelope 6 er Treatment Plant nvelope proc ess) Request for B KMARAS-W1 / KAMARAS-W1 ids - Small W Construction of Kahramanma Environmental Infrastructure Single Stage - One E Pending Imp 2026-08-2 IBRD / 90770 Post Request for Bids Open - National orks SPD (1 e 0.00 2022-10-10 2022-11-07 2022-12-05 2023-01-02 2023-01-16 raş Northern Districts Integra Investments nvelope lementation 8 nvelope proc ted Solid Waste Project ess) Request for B KMARAS-W3 / KMARAS-W3 C ids - Small W Environmental Infrastructure Single Stage - One E Pending Imp 2026-04-1 onstruction of Elbistan Water IBRD / 90770 Post Request for Bids Open - National orks SPD (1 e 0.00 2022-09-13 2022-09-27 2022-10-25 2022-11-22 2022-12-06 Investments nvelope lementation 9 Transmission Line nvelope proc ess) Request for B KMARAS-W5 / KMARAS-W5 C ids - Small W onstruction of Ceyhan Basin Environmental Infrastructure Single Stage - One E Pending Imp 2024-12-1 IBRD / 90770 Post Request for Bids Open - National orks SPD (1 e 0.00 2022-09-15 2022-10-13 2022-11-10 2022-12-08 2022-12-22 Wastewater Treatment Plant Investments nvelope lementation 1 nvelope proc s (Goksun & Ekinozu) ess) Request for B KMARAS-W6 / KMARAS-W6 C ids - Small W onstruction of Ceyhan Basin Environmental Infrastructure Single Stage - One E Pending Imp 2024-12-2 IBRD / 90770 Post Request for Bids Open - National orks SPD (1 e 0.00 2022-10-13 2022-10-27 2022-11-24 2022-12-22 2023-01-05 Wastewater Treatment Plant Investments nvelope lementation 5 nvelope proc s (Caglayancerit & Andirin) ess) KONYA-W2 / RB / Constructio Request for B n of Çumra and Ilgın Wastew ids - Small W Environmental Infrastructure Single Stage - One E Pending Imp 2025-10-1 ater Treatment Plants (Lot 1: IBRD / 90770 Post Request for Bids Open - National orks SPD (1 e 0.00 2023-05-24 2023-05-31 2023-06-28 2023-07-26 2023-08-30 Investments nvelope lementation 8 Construction of Çumra WWTP nvelope proc & Lot 2: Construction of Ilgın ess) WWTP) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KMARAS-G2 / KMARAS-G2 Ka hramanmaraş Northern Distri Environmental Infrastructure Single Stage - One E Pending Impl IBRD / 90770 Post Request for Bids Open - National 0.00 2023-06-27 2023-07-11 2023-08-08 2023-09-12 2023-10-10 2024-01-08 cts Integrated Solid Waste Pr Investments nvelope ementation oject - Container Supply KMARAS-G1 / KMARAS-G1 Ka hramanmaraş Northern Distri Environmental Infrastructure Single Stage - One E Pending Impl IBRD / 90770 Post Request for Bids Open - National 0.00 2023-06-27 2023-07-11 2023-08-08 2023-09-12 2023-10-10 2024-01-08 cts Integrated Solid Waste Pr Investments nvelope ementation oject - Vehicle Supply NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Technical Assistance for Proj ILBANK NCS 2 / A / ILBANK N ect Management and Superv Request for Quota Single Stage - One E Under Imple CS 2 / A - Creation of Visual I IBRD / 90770 Post Limited 0.00 2021-05-01 2021-05-25 2021-08-23 ision, Capacity Building, Co tions nvelope mentation dentity mmunication and Citizen En gagement Technical Assistance for Proj ILBANK NCS 1 / Ilbank NCS 1 ect Management and Superv Request for Quota Single Stage - One E Pending Impl - Project Printed Materials Pro IBRD / 90770 Post Limited 0.00 2021-05-11 2021-06-15 2021-09-13 ision, Capacity Building, Co tions nvelope ementation duction mmunication and Citizen En gagement Page 1 ILBANK NCS 5/A / ILBANK NC Technical Assistance for Proj S 5/A - Logistical & Organiza ect Management and Superv Request for Quota Single Stage - One E Pending Impl IBRD / 90770 Post Limited 0.00 2021-05-11 2021-05-28 2021-05-30 tional Services for Project Op ision, Capacity Building, Co tions nvelope ementation ening/Mid Term/Closing Even mmunication and Citizen En ts and etc. gagement Technical Assistance for Proj ILBANK NCS 2 / Ilbank NCS 2 ect Management and Superv Request for Quota Single Stage - One E Under Imple - Producing the Project Visual IBRD / 90770 Post Limited 0.00 2021-05-11 2022-06-24 2021-07-06 2021-10-04 ision, Capacity Building, Co tions nvelope mentation Production & Materials mmunication and Citizen En gagement ILBANK NCS 3 / A / ILBANK N Technical Assistance for Proj CS 3 / A - Capacity Building T ect Management and Superv Request for Quota Single Stage - One E Pending Impl TF / B4957 Post Limited 0.00 2021-11-22 2021-12-04 2021-12-08 raining for Ilbank and Final B ision, Capacity Building, Co tions nvelope ementation eneficiaries-1 mmunication and Citizen En gagement ILBANK NCS 3 / B / ILBANK N Technical Assistance for Proj CS 3 / B - Capacity Building T ect Management and Superv Request for Quota Single Stage - One E Pending Impl TF / B4957 Post Limited 0.00 2023-02-02 2023-02-20 2023-02-25 raining for Ilbank and Final B ision, Capacity Building, Co tions nvelope ementation eneficiaries-2 mmunication and Citizen En gagement CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KMARAS-C1 / KMARAS-C1 Re Technical Assistance for Proj view of Existing Designs, Pre ect Management and Superv Consultant Qualifi Open - Internationa IBRD / 90770 Post 3,125,959.83 Signed 2020-06-10 2020-07-21 2020-06-15 2020-08-12 2020-08-10 2020-12-24 2020-10-05 2021-07-09 2020-10-19 2021-10-15 2024-12-27 paration of Bidding Documen ision, Capacity Building, Co cation Selection l ts and Construction Supervisi mmunication and Citizen En on Services gagement KMARAS-C2 / KMARAS-C2 Re Technical Assistance for Proj view of Existing Designs, Pre ect Management and Superv Consultant Qualifi Open - Internationa IBRD / 90770 Post 2,225,805.01 Signed 2020-06-10 2020-07-21 2020-06-15 2020-08-12 2020-09-21 2020-12-24 2020-10-26 2021-07-08 2020-11-09 2021-09-08 2024-04-22 paration of Bidding Documen ision, Capacity Building, Co cation Selection l ts and Construction Supervisi mmunication and Citizen En on Services gagement KAY-C1 / KAY-C1 Review of E Technical Assistance for Proj xisting Designs, Preparation ect Management and Superv Consultant Qualifi Open - Internationa IBRD / 90770 Post 1,460,538.82 Signed 2020-06-10 2020-07-21 2020-06-15 2020-08-12 2020-08-17 2020-12-24 2020-10-26 2021-07-08 2020-11-09 2021-08-21 2024-09-28 of Bidding Documents and C ision, Capacity Building, Co cation Selection l onstruction Supervision Servi mmunication and Citizen En ces gagement ADANA-C1 / ADANA-C1 Revi Technical Assistance for Proj ew of Existing Designs, Prepa ect Management and Superv Consultant Qualifi Open - Internationa IBRD / 90770 Post 2,281,381.20 Signed 2020-07-15 2020-07-21 2020-07-20 2020-08-12 2020-09-14 2020-12-24 2020-11-09 2021-07-08 2020-11-23 2021-08-13 2024-07-05 ration of Bidding Documents ision, Capacity Building, Co cation Selection l and Construction Supervision mmunication and Citizen En Services gagement OSMANİYE-C1 / OSMANİYE-C Technical Assistance for Proj 1 Review of Existing Designs, ect Management and Superv Consultant Qualifi Open - Internationa IBRD / 90770 Post 2,041,336.25 Signed 2020-07-15 2020-07-21 2020-07-20 2020-08-12 2020-11-16 2020-12-24 2020-12-28 2021-07-02 2021-01-18 2021-07-30 2024-01-03 Preparation of Bidding Docu ision, Capacity Building, Co cation Selection l ments and Construction Supe mmunication and Citizen En rvision Services gagement KON-C1 / KON-C1 Review of Technical Assistance for Proj Existing Designs, Preparation ect Management and Superv Consultant Qualifi Open - Internationa IBRD / 90770 Post 1,550,727.51 Signed 2020-07-15 2020-07-21 2020-07-20 2020-08-12 2020-11-23 2020-12-24 2021-01-11 2021-07-12 2021-02-08 2021-08-14 2024-07-29 of Bidding Documents and C ision, Capacity Building, Co cation Selection l onstruction Supervision Servi mmunication and Citizen En ces gagement Technical Assistance for Proj ILBANK-C1 / ILBANK C1 - Proj ect Management and Superv Consultant Qualifi Under Implement ect Visual Design and Social IBRD / 90770 Post Open - National 0.00 2021-05-06 2022-09-28 2021-05-13 2021-06-10 2021-06-24 2021-07-08 2022-12-30 ision, Capacity Building, Co cation Selection ation Media Management mmunication and Citizen En gagement Technical Assistance for Proj ILBANK-C2 / ILBANK C2 - Pub ect Management and Superv Consultant Qualifi Pending Impleme IBRD / 90770 Post Open - National 0.00 2022-09-08 2022-09-15 2022-10-13 2022-10-27 2022-11-10 2024-10-30 lic Awareness Campaign ision, Capacity Building, Co cation Selection ntation mmunication and Citizen En gagement ILBANK-C3 / ILBANK C3 - Con Technical Assistance for Proj sultancy Services for Gender, ect Management and Superv Consultant Qualifi Under Implement IBRD / 90770 Post Open - National 0.00 2022-09-15 2022-11-04 2022-09-22 2022-10-20 2022-11-03 2022-11-17 2024-11-06 Citizen Engagement and Co ision, Capacity Building, Co cation Selection ation mmunication Activities mmunication and Citizen En gagement INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Technical Assistance for Proj INDV-02 (PMU-IND-02) / Envi ect Management and Superv Individual Consult IBRD / 90770 Post Open 40,328.27 Signed 2020-07-03 2020-07-20 2020-08-14 2020-12-01 2020-08-21 2020-12-11 2020-09-04 2020-12-12 2024-08-14 ronmental Expert ision, Capacity Building, Co ant Selection mmunication and Citizen En gagement Technical Assistance for Proj INDV-03 (PMU-IND-03) / Fina ect Management and Superv Individual Consult IBRD / 90770 Post Open 50,188.62 Terminated 2020-07-03 2020-07-20 2020-08-14 2020-12-01 2020-08-21 2020-12-04 2020-09-04 2020-12-08 2022-08-25 ncial Expert ision, Capacity Building, Co ant Selection mmunication and Citizen En gagement Technical Assistance for Proj INDV-05 (PMU-IND-05) / Proc ect Management and Superv Individual Consult IBRD / 90770 Post Open 46,350.33 Terminated 2020-07-03 2020-07-20 2020-08-14 2020-12-01 2020-08-21 2020-12-08 2020-09-04 2020-12-25 2022-08-25 urement Expert ision, Capacity Building, Co ant Selection mmunication and Citizen En gagement Technical Assistance for Proj INDV-06 (PMU-IND-06) / Soci ect Management and Superv Individual Consult IBRD / 90770 Post Open 37,102.01 Signed 2020-07-03 2020-07-20 2020-08-14 2020-12-01 2020-08-21 2020-12-08 2020-09-04 2021-01-06 2021-08-30 al Expert ision, Capacity Building, Co ant Selection mmunication and Citizen En gagement Technical Assistance for Proj INDV-07 (PMU-IND-07) / Tec ect Management and Superv Individual Consult IBRD / 90770 Post Open 48,366.48 Signed 2020-07-03 2020-07-20 2020-08-14 2020-12-01 2020-08-21 2020-12-15 2020-09-04 2021-02-02 2024-08-14 hnical Expert ision, Capacity Building, Co ant Selection mmunication and Citizen En gagement Technical Assistance for Proj INDV-08 (PMU-IND-08) / Prob ect Management and Superv Individual Consult IBRD / 90770 Post Limited 11,350.78 Signed 2020-11-23 2020-11-30 2020-11-28 2020-12-03 2020-12-03 2021-02-24 2020-12-10 2021-03-02 2021-01-24 ity Assurance Provider ision, Capacity Building, Co ant Selection mmunication and Citizen En gagement Technical Assistance for Proj INDV-04 (PMU-IND-04) / Mon ect Management and Superv Individual Consult IBRD / 90770 Post Open 0.00 Canceled 2020-07-03 2020-07-20 2020-08-14 2020-08-21 2020-09-04 2024-08-14 itoring and Evaluation Expert ision, Capacity Building, Co ant Selection mmunication and Citizen En gagement Page 2 Technical Assistance for Proj INDV-01 (PMU-IND-01) / Com ect Management and Superv Individual Consult munication and Visibility Exp IBRD / 90770 Post Open 0.00 Canceled 2020-07-03 2020-07-20 2020-08-14 2020-08-21 2020-09-04 2024-08-14 ision, Capacity Building, Co ant Selection ert mmunication and Citizen En gagement Technical Assistance for Proj INDV-01/RB (PMU-IND-01/RB ect Management and Superv Individual Consult ) / Communication and Visibil IBRD / 90770 Post Limited 16,413.91 Terminated 2021-05-06 2021-05-05 2021-05-11 2021-06-14 2021-05-18 2021-07-05 2021-05-25 2021-07-30 2022-05-20 ision, Capacity Building, Co ant Selection ity Expert mmunication and Citizen En gagement Technical Assistance for Proj INDV-04/RB (PMU-IND-04/RB ect Management and Superv Individual Consult ) / Monitoring and Evaluation IBRD / 90770 Post Limited 45,475.75 Signed 2021-05-06 2021-05-07 2021-05-11 2021-06-14 2021-05-18 2021-07-05 2021-05-25 2021-07-27 2022-05-20 ision, Capacity Building, Co ant Selection Expert (RB) mmunication and Citizen En gagement Technical Assistance for Proj INDV-09/RB (PMU-IND-09/RB ect Management and Superv Individual Consult ) / Occupational Health and S TF / B4957 Post Open - National 0.00 Canceled 2022-09-06 2022-10-07 2022-10-14 2022-10-28 2024-10-17 ision, Capacity Building, Co ant Selection afety (OHS) Expert mmunication and Citizen En gagement Technical Assistance for Proj INDV-09 (PMU-IND-09) / Occ ect Management and Superv Individual Consult upational Health and Safety ( TF / B4957 Post Open 0.00 Canceled 2021-11-22 2021-11-23 2021-12-25 2022-01-08 2022-01-22 2023-01-17 ision, Capacity Building, Co ant Selection OHS) Expert mmunication and Citizen En gagement Technical Assistance for Proj INDV-03/RB (PMU-IND-03/RB ect Management and Superv Individual Consult Pending Impleme TF / B4957 Post Open - National 0.00 2022-09-06 2022-10-07 2022-10-14 2022-10-28 2024-10-17 ) / Finance Expert (RB) ision, Capacity Building, Co ant Selection ntation mmunication and Citizen En gagement Technical Assistance for Proj INDV-05/RB (PMU-IND-05/RB ect Management and Superv Individual Consult Pending Impleme IBRD / 90770 Post Open - National 0.00 2022-09-06 2022-10-07 2022-10-14 2022-10-28 2024-10-17 ) / Procurement Expert (RB) ision, Capacity Building, Co ant Selection ntation mmunication and Citizen En gagement Technical Assistance for Proj INDV-01/RB-2 (PMU-IND-01/ ect Management and Superv Individual Consult Pending Impleme RB-2) / Communication and V IBRD / 90770 Post Open - National 0.00 2022-09-06 2022-10-07 2022-10-14 2022-10-28 2024-10-17 ision, Capacity Building, Co ant Selection ntation isibility Expert (RB-2) mmunication and Citizen En gagement Technical Assistance for Proj INDV-06/RB (PMU-IND-06/RB ect Management and Superv Individual Consult Under Implement IBRD / 90770 Post Open - National 0.00 2023-01-26 2023-01-30 2023-02-23 2023-03-02 2023-03-16 2024-09-06 ) / Social Expert (RB) ision, Capacity Building, Co ant Selection ation mmunication and Citizen En gagement Technical Assistance for Proj INDV-09/RB-2 (PMU-IND-09/ ect Management and Superv Individual Consult Pending Impleme RB-2) / Occupational Health a TF / B4957 Post Limited 0.00 2023-04-04 2023-04-07 2023-04-14 2023-04-20 2024-12-10 ision, Capacity Building, Co ant Selection ntation nd Safety (OHS) Expert mmunication and Citizen En gagement Page 3 PROCUREMENT PLAN (Textual Part) Project information: [Ghana] [Ghana Productive Safety Net Project 2 (GPSNP 2) [P-175588] Project Implementation agency: [Ministry of Gender, Children and Social Protection (MoGCSP) and Ministry of Local Government, Decentralisation and Rural Development (MLGDRD) Date of the Procurement Plan: [26/02/2021] Period covered by this Procurement Plan: [01 July 2021 – 31 December 2022] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Act, 2003 (Act 663) which was amended in 2016 by the Public Procurement (Amendment) Act, 2016, (Act 914), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. 56 (1) Tenders shall be opened (a) at the time specified in the tender documents as the deadline for the submission of tenders or at the deadline specified in any extension of the deadline; and (b) at the place and in accordance with the procedures specified the tender documents. (2) The time for opening of the tenders shall be the same as the deadline for the receipt of the tenders or promptly after that deadline. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information. Procedures for CDD components: Community Driven Development (CDD) activities are works activities, which are carried out directly by communities. Procurement of Materials Procurement of materials for the activities would be done through the procurement method limited- open. The activities to be carried out: i. Issuance of Request for quotation (at least 3 bidders); ii. Submission and opening of bids for bidders; iii. Evaluation of bids iv. Issuance of Acceptance Letters; v. Signing of Contracts Selection of Community Members Selection of communities to participate in the CDD activities shall be done through direct selection procurement method. Agreement is then signed between the Implementation Agencies (Municipals and District Assemblies) to cover the duration of the activity. PROCUREMENT Ghana : Ghana Productive Safety Net Project 2 PLAN General Information Country: Ghana 2022-07-18 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175588 GPN Date: Project Name: Ghana Productive Safety Net Project 2 Loan / Credit No: IDA / 68590 Ministry of Gender, Children and Social Protection 2 Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MOGCSP-222363-GO-RF B / Procurement of Office Fu Project Management, Coordi rniture (142 tables, 734 Chair Single Stage - One E IDA / 68590 nation, and Institutional Stre Post Request for Bids Open - National 1,000,000.00 0.00 Canceled 2022-08-08 2022-08-08 2022-08-13 2022-09-24 2022-10-24 2022-11-28 2023-05-27 s, 23 Workstation, 31 pieces nvelope ngthening of 2 in 1 Sofa, 17 pieces of 3 in 1 Sofa ) for GPSNP Office i n MoGCSP GH-MOGCSP-362074-GO-RF B / Procurement of Vehicles ( Livelihood Empowerment Ag 4 no. Pick-Ups and 1 no. SUV Single Stage - One E Pending Impl IDA / 68590 ainst Poverty Cash Transfers Post Request for Bids Open - National 870,000.00 0.00 2023-06-01 2023-06-06 2023-07-18 2023-08-17 2023-09-21 2024-03-19 for GNHR, 4 no. Pick-Ups for nvelope ementation Program LEAP Management Secretaria t and1 no. Pick-Up for Project Coordinating Unit) GH-MOGCSP-222358-GO-RF Project Management, Coordi Single Stage - One E B / Procurement of Vehicles ( IDA / 68590 nation, and Institutional Stre Post Request for Bids Open - National 700,000.00 0.00 Canceled 2023-02-03 2022-09-15 2023-02-08 2023-03-22 2023-04-21 2023-05-26 2023-11-22 nvelope 8 No. Pick-ups and 2 No. SUV ngthening s) GH-MOGCSP-362194-GO-RF Q / Procurement of Office Eq Social Protection System Str Request for Quota Single Stage - One E Pending Impl uipment (30 No. Laptops, 5 N IDA / 68590 Post Open - National 88,264.05 0.00 2023-06-06 2023-08-01 2024-01-28 engthening tions nvelope ementation o. Desktops + UPS and 5 No. Photocopiers/Printers for Proj ect Coordinating Unit) GH-MOGCSP-336638-GO-RF B / Supply and Delivery of Off ice Equipment (40 No. 3-in-1 Project Management, Coordi Single Stage - One E Computer & Accessories, 90 IDA / 68590 nation, and Institutional Stre Post Request for Bids Open - National 546,401.17 0.00 Canceled 2023-02-03 2023-02-03 2023-02-08 2023-03-22 2023-04-21 2023-05-26 2023-11-22 nvelope Desktops, 130 UPS,60 Laptop ngthening s, 55 printers,17 Copiers,26 s hredders,6 Electronic Comb Binder/ Manual comb Binder) GH-MOGCSP-362213-GO-RF Project Management, Coordi Single Stage - One E Pending Impl B / Supply and Installation of IDA / 68590 nation, and Institutional Stre Post Request for Bids Open - National 104,086.88 0.00 2023-06-01 2023-06-06 2023-07-18 2023-08-17 2023-09-21 2024-03-19 nvelope ementation Office Blinds for Project Coor ngthening dinating Unit GH-MOGCSP-334640-GO-RF Q / Supply and Installation of Office Fixtures and Fittings (2 Project Management, Coordi Request for Quota Single Stage - One E 000 square meter binds, 20 IDA / 68590 nation, and Institutional Stre Post Open - National 78,500.42 0.00 Canceled 2023-02-08 2023-04-05 2023-10-02 tions nvelope No wall clocks, 100 No, Wall ngthening Mount Sanitizer for all floors, and 3 No. Hand Washing Dis penser Machines) GH-MOGCSP-362373-GO-RF Q / Procurement of Conferen ce Equipment (4 Conferencin Project Management, Coordi Request for Quota Single Stage - One E Pending Impl g Microphones (Table fit), 7 S IDA / 68590 nation, and Institutional Stre Post Open - National 65,326.19 0.00 2023-06-06 2023-08-01 2024-01-28 tions nvelope ementation mart Board and Accessories/ ngthening Video Conferencing Facility(s ),4 Podiums with Microphone for Conference Hall) GH-MOGCSP-336677-GO-RF Q / Procurement of Conferen ce Equipment (4 Conferencin Project Management, Coordi g Microphones (Table fit) Request for Quota Single Stage - One E IDA / 68590 nation, and Institutional Stre Post Open - National 39,740.19 0.00 Canceled 2023-02-08 2023-04-05 2023-10-02 7 Smart Board and Accessori tions nvelope ngthening es/Video Conferencing Facilit y(s),4 Podiums with Micropho ne for Conference Hall) GH-MOGCSP-362374-GO-RF Q / Procurement of Screen Pr Social Protection System Str Request for Quota Single Stage - One E Pending Impl otectors, Case and Peripheral IDA / 68590 Post Open - National 60,000.00 0.00 2023-06-06 2023-08-01 2024-01-28 engthening tions nvelope ementation s for 800 no. Tablets for Gha na National Household Regist ry GH-MOGCSP-362376-GO-RF Project Management, Coordi Q / Procurement of Office Acc Request for Quota Single Stage - One E Pending Impl IDA / 68590 nation, and Institutional Stre Post Open - National 30,000.00 0.00 2023-06-06 2023-08-01 2024-01-28 ess Control for Project Manag tions nvelope ementation ngthening ement and Coordination Unit GH-MOGCSP-362917-GO-RF Q / Procurement of Stationer y and Office Consumables (A Project Management, Coordi 4, Papers, Toners and Cartrid Request for Quota Single Stage - One E Pending Impl IDA / 68590 nation, and Institutional Stre Post Open - National 54,000.00 0.00 2023-06-06 2023-08-01 2024-01-28 ges, Pens and Pencils, Bindin tions nvelope ementation ngthening g Materials, Office Pins, Pape r Clips, Envelopes, Arch Files, Binder Clips, Notebooks, Rule rs, Staplers etc. ) for Project Coordinating Unit GH-MOGCSP-334641-GO-RF B / Procurement of Office Ele ctronic Equipment (32 No. 65 ", 75" 55",50", 43",32" Led S Project Management, Coordi Single Stage - One E mart TVs, TV Accessories,83 IDA / 68590 nation, and Institutional Stre Post Request for Bids Open - National 160,968.49 0.00 Canceled 2023-02-03 2023-01-20 2023-02-08 2023-03-22 2023-04-21 2023-05-26 2023-11-22 nvelope No. various fridges and freez ngthening ers,12 No. microwaves, 20 N o. water kettles, 32 No. TV g uards, 90 No refrigerator gua rds & 200 No. extension cabl es) Page 1 GH-MOGCSP-334789-GO-RF Q / Procurement and Installat Project Management, Coordi Request for Quota Single Stage - One E ion of Double-Glazed Alumin IDA / 68590 nation, and Institutional Stre Post Open - National 10,000.00 0.00 Canceled 2023-02-20 2023-04-17 2023-10-14 tions nvelope um doors (Double & Single @ ngthening Reception, Conference Room s) GH-MOGCSP-318115-GO-RF B / Procurement of Assorted Furniture (4 No. Wheel Chairs Project Management, Coordi ,25 No. 1.4m L- Shape Desk, Single Stage - One E IDA / 68590 nation, and Institutional Stre Post Request for Bids Open - National 128,451.51 0.00 Canceled 2023-02-03 2023-02-08 2023-03-22 2023-04-21 2023-05-26 2023-11-22 10 No. 1.6m L- Shape Desk, nvelope ngthening 35 No. 1.4m Desk, 10 No. 2- Seater Workstation, 90 No. S wivel Chair, 90 No. 4-Drawer Steel Cabinet, 40 No. Visitors Chairs. etc) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MOGCSP-334784-NC-RFB Project Management, Coordi Single Stage - One E / Supply and Installation of 2 IDA / 68590 nation, and Institutional Stre Post Request for Bids Open - National 105,000.00 0.00 Canceled 2023-02-20 2023-02-25 2023-04-08 2023-05-08 2023-06-12 2023-12-09 nvelope No. 250KVA Power Generatin ngthening g Plant GH-MOGCSP-362479-NC-RFB / Designing, Printing and Diss Livelihood Empowerment Ag emination of LEAP and SWCE Single Stage - One E Pending Impl IDA / 68590 ainst Poverty Cash Transfers Post Request for Bids Open - National 204,600.00 0.00 2023-06-01 2023-06-06 2023-07-18 2023-08-17 2023-09-21 2024-03-19 SS Information, Education a nvelope ementation Program nd Communication (IEC) Mat erials as well as GNHR Parap hernalia GH-MOGCSP-362484-NC-RFB / Development of Documenta ry on the LEAP Programme ( Livelihood Empowerment Ag Develop & validate the story Single Stage - One E Pending Impl IDA / 68590 ainst Poverty Cash Transfers Post Request for Bids Open - National 40,000.00 0.00 2023-06-01 2023-06-06 2023-07-18 2023-08-17 2023-09-21 2024-03-19 line for the production of a vi nvelope ementation Program deographical evidence by bui lding of how the LEAP progra mme is supporting the lives a nd livelihoods of households) GH-MOGCSP-317202-NC-NU LL / Design and print LEAP In Livelihood Empowerment Ag Single Stage - One E formation, Education and Co IDA / 68590 ainst Poverty Cash Transfers Post Request for Bids Open - National 160,500.00 0.00 Canceled 2023-02-15 2023-02-20 2023-04-03 2023-05-03 2023-06-07 2023-12-04 nvelope mmunication Materials and G Program NHR Paraphernalia for field o fficers GH-MOGCSP-334787-NC-RF Project Management, Coordi Request for Quota Single Stage - One E Q / Installation of Intercom C IDA / 68590 nation, and Institutional Stre Post Open - National 69,000.00 0.00 Canceled 2023-02-20 2023-04-17 2023-10-14 tions nvelope onnectivity and Biometric Clo ngthening ck in System CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MOGCSP-314349-CS-QC BS / Engagement of Data Coll ection Firm for data collectio n in the Bono Region. It invol Social Protection System Str Quality And Cost- Open - Internationa ves collection of basic inform IDA / 68590 Prior 5,000,000.00 0.00 Canceled 2023-06-15 2023-07-06 2023-08-19 2023-09-16 2023-10-16 2023-11-20 2023-12-25 2024-12-24 engthening Based Selection l ation on the social-economic status of extremely poor hou seholds to establish a nation al register of extremely hous eholds in Ghana. GH-MOGCSP-222409-CS-QC BS / Engagement of Data Coll ection Firm for data collectio n in the Greater Accra region Social Protection System Str Quality And Cost- Open - Internationa . It involves collection of basi IDA / 68590 Prior 5,000,000.00 0.00 Canceled 2023-06-15 2023-07-06 2023-08-19 2023-09-16 2023-10-16 2023-11-20 2023-12-25 2024-12-24 engthening Based Selection l c information on the social-ec onomic status of extremely p oor households to establish a national register of extremel y households in Ghana. GH-MOGCSP-222403-CS-QC BS / Engagement of Data Coll ection Firm for data collectio n in the Bono East Region. It i Social Protection System Str Quality And Cost- Open - Internationa nvolves collection of basic inf IDA / 68590 Prior 5,000,000.00 0.00 Canceled 2023-06-15 2023-07-06 2023-08-19 2023-09-16 2023-10-16 2023-11-20 2023-12-25 2024-12-24 engthening Based Selection l ormation on the social-econo mic status of extremely poor households to establish a nat ional register of extremely ho useholds in Ghana. GH-MOGCSP-222411-CS-QC BS / Engagement of Data Coll ection Firm for data collectio n in the Eastern Region.It inv Social Protection System Str Quality And Cost- Open - Internationa olves collection of basic infor IDA / 68590 Prior 5,000,000.00 0.00 Canceled 2023-06-15 2023-07-06 2023-08-19 2023-09-16 2023-10-16 2023-11-20 2023-12-25 2024-12-24 engthening Based Selection l mation on the social-economi c status of extremely poor ho useholds to establish a natio nal register of extremely hou seholds in Ghana. GH-MOGCSP-222373-CS-QC BS / Engagement of Data Coll ection Firm for data collectio n in the Ahafo Region. It invol Social Protection System Str Quality And Cost- Open - Internationa ves collection of basic inform IDA / 68590 Prior 3,042,000.00 0.00 Canceled 2023-06-15 2023-07-06 2023-08-19 2023-09-16 2023-10-16 2023-11-20 2023-12-25 2024-12-24 engthening Based Selection l ation on the social-economic status of extremely poor hou seholds to establish a nation al register of extremely hous eholds in Ghana. GH-MOGCSP-222413-CS-QC BS / Engagement of Data Coll ection Firm for data collectio n in the Western Region. It in Social Protection System Str Quality And Cost- Open - Internationa volves collection of basic info IDA / 68590 Prior 5,000,000.00 0.00 Canceled 2023-06-15 2023-07-06 2023-08-19 2023-09-16 2023-10-16 2023-11-20 2023-12-25 2024-12-24 engthening Based Selection l rmation on the social-econo mic status of extremely poor households to establish a nat ional register of extremely ho useholds in Ghana. Page 2 GH-MOGCSP-222407-CS-QC BS / Engagement of Data Coll ection Firm for data collectio n in the Ashanti Region. It inv Social Protection System Str Quality And Cost- Open - Internationa olves collection of basic infor IDA / 68590 Prior 5,000,000.00 0.00 Canceled 2023-06-15 2023-07-06 2023-08-19 2023-09-16 2023-10-16 2023-11-20 2023-12-25 2024-12-24 engthening Based Selection l mation on the social-economi c status of extremely poor ho useholds to establish a natio nal register of extremely hou seholds in Ghana. GH-MOGCSP-222412-CS-QC BS / Engagement of Data Coll ection Firm for data collectio n in the Western North Regio Social Protection System Str Quality And Cost- Open - Internationa n. It involves collection of ba IDA / 68590 Prior 5,000,000.00 0.00 Canceled 2023-06-15 2023-07-06 2023-08-19 2023-09-16 2023-10-16 2023-11-20 2023-12-25 2024-12-24 engthening Based Selection l sic information on the social- economic status of extremel y poor households to establis h a national register of extre mely households in Ghana. GH-MOGCSP-324695-CS-QC BS / ENGAGEMENT OF A CON SULTANT TO UNDERTAKE AN Social Protection System Str Quality And Cost- Pending Impleme IDA / 68590 Post Open - National 100,000.00 0.00 2023-06-12 2023-07-03 2023-08-16 2023-09-13 2023-10-13 2023-11-17 2023-12-22 2024-12-21 ASSESSMENT OF THE STATU engthening Based Selection ntation S OF SOCIAL SECURITY AND SOCIAL INSURANCE IN THE IN FORMAL SECTOR ECONOMY INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MOGCSP-334441-CS-CD S / Engagement of firms for Social Protection System Str Under Implement Data Collection in the Volta R IDA / 68590 Prior Direct Selection Direct - National 5,500,000.00 0.00 2023-01-23 2023-02-20 2023-02-02 2023-05-19 2023-04-08 2023-10-05 engthening ation egion of Ghana for Ghana Na tional Household Registry GH-MOGCSP-334435-CS-CD S / Engagement of Firms for Social Protection System Str Under Implement Data Collection in the Central IDA / 68590 Prior Direct Selection Direct - National 3,500,000.00 0.00 2023-01-23 2023-02-20 2023-02-02 2023-05-19 2023-04-08 2023-10-05 engthening ation Region of Ghana for Ghana N ational Household Registry Page 3 PROCUREMENT PLAN (Textual Part) Project information: Timor-Leste Basic Education Strengthening and Transformation Project (P166744) Project Implementation agency: Ministry of Education, Youth and Sport (MOEYS) Date of the Procurement Plan: February 26, 2020. Period covered by this Procurement Plan: July 1, 2020 to December 31, 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, the procedures applicable to the procurement of Goods, Works, Non-Consulting services and Consulting Services under the contracts awarded on the basis of National Open Competitive Procurement shall be those procurement methods set forth in the Timor Leste Procurement Legal Regime Decree Law 10/2005, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When the Borrower uses its own national open competitive procurement arrangements as set forth Timor Leste Procurement Legal Regime Decree Law 10/2005, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. 1. The procurement is open to eligible firms from any country; 2. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; 3. Right for the Bank to review procurement documentation and activities; 4. Maintenance of records of the Procurement process; 5. Procurement Documents acceptable to the Bank shall be used; 6. Bids shall be evaluated using only post-qualification for procurement of goods, works and non-consulting services. 7. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health safety ("ESHS") risks impacts. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables PROCUREMENT Timor-Leste : Basic Education Strengthening and Transformation Project PLAN General Information Country: Timor-Leste 2020-10-28 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166744 GPN Date: 2020-11-16 Project Name: Basic Education Strengthening and Transformation Project Loan / Credit No: IDA / 65510, TF / B2130 Ministry of Education Youth and Sport Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned 001/BEST/TL / 3 packages of new classrooms construction Component 1: Developing 2 Single Stage - One E Pending Imp 2022-08-0 (each package covers differe IDA / 65510 Post Request for Bids Open - National 1,100,000.00 0.00 2021-07-01 2021-07-06 2021-08-17 2021-09-16 2022-02-04 1st Century Learning Spaces nvelope lementation 3 nt municipalities) - 3 schools in 3 different municipalities BEST/WORKS/RFQ01 / PIMU Component 5: Project Manag Request for Quota Single Stage - One E Other (with field f 2022-03-3 TF / B2130 Post Open - National 22,655.50 0.00 Canceled 2021-12-01 2021-12-15 Office Refurbishment ement and Implementation tions nvelope or explanation) 1 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 003/BEST/TL / Provision & In Component 4: Data Driven P Request for Quota Single Stage - One E Under Imple stallation of hardware, includ TF / B2130 lanning, Budgeting, Financin Post Open - National 80,000.00 0.00 2020-11-06 2022-05-19 2022-02-04 2022-08-03 tions nvelope mentation ing servers, software at MoE g and Implementation YS for EMIS 033/BEST/TL / Office electro nic- equipment (computer, pr Component 5: Project Manag Request for Quota Single Stage - One E TF / B2130 Post Open - National 20,000.00 20,000.00 Signed 2020-10-09 2022-06-21 2020-12-04 2022-05-07 2021-06-02 inter potocopier machine, sc ement and Implementation tions nvelope anner, camera etc) 031/BEST/TL / Furniture and Fixtures for PIMU including Ai Component 5: Project Manag Request for Quota TF / B2130 Post 20,000.00 8,830.00 Signed 2020-10-10 2020-12-05 2022-03-01 2021-06-03 r conditions, telephones, des ement and Implementation tions ks and chairs and office rack s 030/BEST/TL / Purchasing an Component 3: Improving Te d distribution of set of age/gr Single Stage - One E Pending Impl TF / B2130 aching-Learning Material an Prior Request for Bids Open - National 741,000.00 0.00 2021-01-19 2021-01-24 2021-03-07 2021-04-06 2021-06-18 2021-12-15 ade appropriate children's b nvelope ementation d Assessment ooks for Cycle 1 and 2 and fa brication of book corners 002/BEST/TL / Provision and Installation of relevant hardw Component 4: Data Driven P Single Stage - One E Pending Impl are and internet connectivity TF / B2130 lanning, Budgeting, Financin Post Request for Bids Open - National 120,000.00 0.00 2021-08-03 2021-08-08 2021-09-19 2021-10-19 2022-06-05 2022-12-02 nvelope ementation in selected municipal offices g and Implementation and selected central schools 004/BEST/TL / Operational v Component 1: Developing 2 Request for Quota Single Stage - One E IDA / 65510 Post Open - National 80,000.00 36,500.00 Signed 2021-12-05 2022-05-18 2022-01-30 2022-03-02 2022-03-31 ehicles for the use of PIMU 1st Century Learning Spaces tions nvelope 057/BEST/TL / Operational M Component 5: Project Manag Request for Quota Single Stage - One E TF / B2130 Post Open - National 2,000.00 1,495.00 Signed 2022-05-03 2022-08-11 2022-06-28 2022-08-13 2022-12-25 otorcycle for PIMU Office ement and Implementation tions nvelope 062/BEST/TL / PIMU Operatio Component 5: Project Manag Request for Quota Single Stage - One E nal Vehicles (1 Pick-up, 4WD TF / B2130 Post Open - National 43,500.00 0.00 Completed 2022-07-01 2022-12-03 2022-08-26 2023-02-22 2023-01-06 ement and Implementation tions nvelope and 1 sedan for Dili-based op eration) 065/BEST/TL / PIMU Office i Component 5: Project Manag Request for Quota Single Stage - One E TF / B2130 Post Open - National 5,000.00 0.00 Terminated 2022-06-10 2022-12-03 2022-08-05 2023-02-01 mprovement (Work Space im ement and Implementation tions nvelope provement) BEST/GOODS/RFQ032 / PIMU Component 5: Project Manag Request for Quota Single Stage - One E TF / B2130 Post Open - National 22,654.45 22,654.45 Signed 2022-01-15 2022-07-28 2022-03-12 2022-02-22 2022-09-08 Office Refurbishment ement and Implementation tions nvelope 094/BEST/TL / RFQ to purcha Component 4: Data Driven P Request for Quota Single Stage - One E se 25 tablets for Master Train TF / B2130 lanning, Budgeting, Financin Post Open - National 17,500.00 0.00 Completed 2022-11-14 2022-12-27 2023-01-09 2023-07-08 2023-01-12 tions nvelope ers Training g and Implementation 101/BEST/TL / Purchase of e quipment for topography sur vey (Digital Theodolite) Total Station complete set with su Component 1: Developing 2 Request for Quota Single Stage - One E Pending Impl IDA / 65510 Post Open - National 7,500.00 0.00 2023-03-13 2023-05-08 2023-11-04 pporting stuffs: 1 unit of alu 1st Century Learning Spaces tions nvelope ementation minum tripod, 1 unit of leveli ng/reading staff (5 meter), 1- unit hardcase, and waterproo f protective cover NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 070/BEST/TL / A higher educ ation (University or Institute) to provide 36 junior engineer s for School Infrastructure da Component 1: Developing 2 Request for Quota Single Stage - One E IDA / 65510 Post Open - National 198,508.00 0.00 Canceled 2022-08-02 2022-09-27 2023-03-26 ta collection including perdie 1st Century Learning Spaces tions nvelope m and supervision managem ent; (Remuniration, Payment Perdiem,Comunication Fees, Rental of Equipment, Other O perational Se CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 006/BEST/TL / Consultant Fir m (Experts) for Quality assur Component 1: Developing 2 Consultant Qualifi Pending Impleme IDA / 65510 Post Open - National 175,000.00 0.00 2021-07-01 2021-07-22 2021-09-04 2021-10-04 2021-11-08 2022-05-07 ance of new construction and 1st Century Learning Spaces cation Selection ntation rehabilitation of school infras tructures 009/BEST/TL / A Firm to desi Component 3: Improving Te gn the implementation, analy Consultant Qualifi Open - Internationa Under Implement TF / B2130 aching-Learning Material an Post 400,000.00 0.00 2021-01-31 2022-10-04 2021-02-21 2023-01-17 2021-04-06 2021-05-06 2021-06-10 2021-12-07 sis and reporting of EGRA an cation Selection l ation d Assessment d EGMA and basic capacity b uilding (grades 1,2, 3) 061/BEST/TL / Consultant fir Component 5: Project Manag Consultant Qualifi Open - Internationa Under Implement TF / B2130 Post 42,000.00 0.00 2022-04-29 2023-03-06 2022-05-20 2023-06-15 2022-07-03 2022-08-02 2022-09-06 2023-03-05 m for External Auditors for B ement and Implementation cation Selection l ation EST Project 036/BEST/TL / Online system and training/orientation of sc Component 1: Developing 2 Consultant Qualifi Pending Impleme IDA / 65510 Post Open - National 45,000.00 0.00 2021-02-01 2021-02-22 2021-04-07 2021-05-07 2021-06-11 2021-12-08 hool infrastructure managem 1st Century Learning Spaces cation Selection ntation ent or module linked to EMIS (Component I) 047/BEST/TL / Consultant Fir Component 3: Improving Te m to design the implementat Consultant Qualifi Pending Impleme TF / B2130 aching-Learning Material an Post Open - National 350,000.00 0.00 2022-04-28 2022-05-19 2022-07-02 2022-08-01 2022-09-05 2023-03-04 ion, analysis and reporting of cation Selection ntation d Assessment EGRA and EGMA (grades 1,2, 3) 060/BEST/TL / Consultant Fir Component 1: Developing 2 Consultant Qualifi Pending Impleme m for school infrastructure su IDA / 65510 Post Open - National 328,385.00 0.00 2022-04-29 2022-05-20 2022-07-03 2022-08-02 2022-09-06 2023-03-05 1st Century Learning Spaces cation Selection ntation pervision and quality control 059/BEST/TL / Consultant Fir m for detailed engineering d Component 1: Developing 2 Quality And Cost- Pending Impleme IDA / 65510 Prior Open - National 900,000.00 0.00 2022-06-19 2022-07-10 2022-08-23 2022-09-20 2022-10-20 2022-11-24 2022-12-29 2023-12-29 esign, bidding document pre 1st Century Learning Spaces Based Selection ntation paration/Works and supervisi on. 034/BEST/TL / Implementati Component 1: Developing 2 Consultant Qualifi Open - Internationa on of school census includin IDA / 65510 Post 450,000.00 0.00 Canceled 2021-01-19 2022-01-20 2021-02-09 2022-07-11 2021-03-25 2022-04-24 2021-04-24 2021-05-29 2021-11-25 1st Century Learning Spaces cation Selection l g school infrastructure and E MIS census 005A/BEST/TL / A Firm for sy stem core development for t Component 4: Data Driven P he integrated for Sistema de Quality And Cost- Open - Internationa Pending Impleme TF / B2130 lanning, Budgeting, Financin Post 500,000.00 0.00 2022-12-01 2022-12-22 2023-02-04 2023-03-04 2023-04-03 2023-05-08 2023-06-12 2024-06-11 Gestao Escolar, PMIS and EMI Based Selection l ntation g and Implementation S and other data base syste m, software development/mo dification/testing/production 005/BEST/TL / A Firm for sys tem core development for th Component 4: Data Driven P e integrated for Sistema de G Quality And Cost- Open - Internationa TF / B2130 lanning, Budgeting, Financin Post 500,000.00 0.00 Canceled 2021-06-01 2021-12-13 2021-06-22 2021-08-05 2021-09-02 2021-10-02 2021-11-06 2022-02-01 2022-12-29 estao Escolar, PMIS and EMIS Based Selection l g and Implementation and other data base system, software development/modifi cation/testing/production 037-2023/BEST/TL / Consult ancy Services DED of School Infrastructure facilities (21st Component 1: Developing 2 Quality And Cost- Pending Impleme Century learning spaces), Re IDA / 65510 Post Open - National 824,315.00 0.00 2023-06-27 2023-07-18 2023-08-31 2023-09-28 2023-10-28 2023-12-02 2024-01-06 2025-01-05 1st Century Learning Spaces Based Selection ntation muneration Cost -Phase 1, R eimbursable -phase 1, Remu neration Cost -Phase 2, Reim bursable -phase 2 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 021/BEST/TL / Infrastructure Component 5: Project Manag Individual Consult Development Specialist of 21 IDA / 65510 Post Open 135,000.00 0.00 Canceled 2020-10-09 2020-11-09 2020-11-27 2020-12-18 2021-01-22 2023-07-21 ement and Implementation ant Selection st Century School standards 035/BEST/TL / Consultant for implementation of a school i Component 1: Developing 2 Individual Consult Under Implement nfrastucture survey of a smal IDA / 65510 Post Limited 18,000.00 0.00 2021-02-01 2021-11-04 2021-02-06 2021-02-27 2021-04-03 2021-09-30 1st Century Learning Spaces ant Selection ation l purposive sample of school to test the prioritazation guid elines 037/BEST/TL / Technical exp Component 2: Improving Te Individual Consult ert in education (curriculum, TF / B2130 Post Open 205,200.00 205,200.00 Terminated 2020-10-23 2021-11-11 2020-12-11 2021-12-03 2021-01-01 2022-01-14 2021-02-05 2022-01-29 2023-02-20 acher Effectiveness ant Selection training, school management ) 022/BEST/TL / TA for enhanci ng the reporting and dashbo ard facilities of the classroom Component 2: Improving Te Individual Consult Under Implement observation module to gener TF / B2130 Post Open 20,000.00 0.00 2021-08-02 2021-09-20 2021-10-11 2021-11-15 2022-05-14 acher Effectiveness ant Selection ation ate and display aggregate da ta on results of classroom ob servations by indicator, scho ol, cluster and municipal offic e 015/BEST/TL / Review and U Component 2: Improving Te Individual Consult Pending Impleme pgrade training materials for TF / B2130 Post Open 20,000.00 0.00 2020-12-15 2021-02-02 2021-02-23 2021-03-30 2021-09-26 acher Effectiveness ant Selection ntation school leaders training 016/BEST/TL / Upgrading/De Component 2: Improving Te Individual Consult Pending Impleme velop teacher training monit TF / B2130 Post Open 20,000.00 0.00 2021-01-01 2021-02-19 2021-03-12 2021-04-16 2021-10-13 acher Effectiveness ant Selection ntation oring/observation tool for INF ORDEPE 017/BEST/TL / Training obser Component 2: Improving Te Individual Consult Pending Impleme vation/evaluation report on t TF / B2130 Post Open 20,000.00 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 acher Effectiveness ant Selection ntation eachers training quality 011/BEST/TL / Curriculum sp Component 3: Improving Te ecialist for reviewing and qu Individual Consult Pending Impleme TF / B2130 aching-Learning Material an Post Limited 25,000.00 0.00 2021-01-29 2021-02-03 2021-02-24 2021-03-31 2021-09-27 ality checks for 3rd cycle boo ant Selection ntation d Assessment ks (language and social scien ces) 018/BEST/TL / Curriculum sp Component 3: Improving Te ecialist for reviewing and qu Individual Consult Pending Impleme TF / B2130 aching-Learning Material an Post Open 15,000.00 0.00 2021-01-29 2021-03-19 2021-04-09 2021-05-14 2021-11-10 ality assurance for 3rd cycle ant Selection ntation d Assessment TLM (natural sciences) 027/BEST/TL / Curriculum sp Component 3: Improving Te Individual Consult Pending Impleme ecialist for revision and qualit TF / B2130 aching-Learning Material an Post Open 15,000.00 0.00 2021-01-29 2021-03-19 2021-04-09 2021-05-14 2021-11-10 ant Selection ntation y assurance for 3rd cycle TL d Assessment M (mathematics) Page 2 007BEST/TL / A consultant to Component 3: Improving Te Individual Consult Pending Impleme develop Physical Education B TF / B2130 aching-Learning Material an Post Open 38,400.00 0.00 2020-11-13 2021-01-01 2021-01-22 2021-02-26 2022-02-25 ant Selection ntation ook and Manual for Grade 7 ( d Assessment Third Cycle) 020/BEST/TL / Financial Man Component 5: Project Manag Individual Consult TF / B2130 Post Open 151,200.00 151,200.00 Signed 2020-10-04 2020-11-09 2020-11-22 2022-06-03 2020-12-13 2022-06-03 2021-01-17 2021-10-28 2023-01-17 agement Specialist ement and Implementation ant Selection 023/BEST/TL / Procurement Component 5: Project Manag Individual Consult TF / B2130 Post Open 151,200.00 40,650.00 Terminated 2020-10-02 2020-11-09 2020-11-20 2021-10-13 2020-12-11 2021-10-25 2021-01-15 2021-10-19 2023-01-15 Specialist ement and Implementation ant Selection 013/BEST/TL / Environmenta Component 5: Project Manag Individual Consult TF / B2130 Post Open 124,200.00 124,200.00 Signed 2020-12-01 2020-11-09 2021-01-19 2022-01-11 2021-02-09 2021-10-18 2021-03-16 2021-10-28 2023-03-16 l and Social safeguard specia ement and Implementation ant Selection list 024/BEST/TL / M&E Specialis Component 5: Project Manag Individual Consult TF / B2130 Post Open 108,000.00 0.00 Canceled 2020-12-01 2020-11-09 2021-01-19 2021-02-09 2021-03-16 2023-03-16 t for PIMU ement and Implementation ant Selection 012/BEST/TL / ICT specialist Component 5: Project Manag Individual Consult TF / B2130 Post Open 118,000.00 118,000.00 Terminated 2020-10-29 2020-11-09 2020-12-17 2021-10-13 2021-01-07 2021-10-13 2021-02-11 2021-10-19 2023-02-10 for PIMU ement and Implementation ant Selection 032/BEST/TL / Administratio Component 5: Project Manag Individual Consult TF / B2130 Post Open 67,500.00 0.00 Canceled 2020-11-01 2020-11-09 2020-12-20 2021-01-10 2021-02-14 2023-02-14 n assistant to PIMU ement and Implementation ant Selection 008/BEST/TL / A consultant t o design a Paper based temp late for supporting the acquis Component 3: Improving Te ition, packaging, and distribu Individual Consult Pending Impleme TF / B2130 aching-Learning Material an Post Open 4,500.00 0.00 2021-02-01 2021-03-22 2021-04-12 2021-05-17 2021-08-31 tion of TLM, estimate the nu ant Selection ntation d Assessment mber of books to be printed each year, and provide the s chools with updates on the st atus on their TLM needs; 038/BEST/TL / A consultant t Component 3: Improving Te Individual Consult Pending Impleme o develop Art Book and Manu TF / B2130 aching-Learning Material an Post Open 38,400.00 0.00 2020-11-13 2021-01-01 2021-01-22 2021-02-26 2022-02-25 ant Selection ntation al for Grade 7th d Assessment 019/BEST/TL / Project manag Component 5: Project Manag Individual Consult TF / B2130 Prior Open 305,100.00 0.00 Canceled 2020-10-08 2020-11-15 2020-11-26 2020-12-17 2021-01-08 2023-01-08 er for PMIU ement and Implementation ant Selection BEST/INDV/005 / Monitoring Component 5: Project Manag Individual Consult IDA / 65510 Post Open 119,025.00 119,025.00 Signed 2021-10-15 2021-11-11 2021-11-17 2022-01-11 2021-12-08 2022-01-17 2022-01-12 2022-01-30 2024-07-10 and Evaluation Specialist ement and Implementation ant Selection BEST/INDV/001 / BEST Proje Component 5: Project Manag Individual Consult TF / B2130 Post Open 244,350.00 64,304.46 Signed 2021-10-15 2021-01-24 2021-12-03 2021-11-04 2021-12-24 2021-10-25 2022-01-28 2021-10-28 2022-07-27 ct Manager ement and Implementation ant Selection BEST/INDV/006 / Infrastructu Component 5: Project Manag Individual Consult TF / B2130 Post Open 180,675.00 180,675.00 Signed 2021-10-15 2021-11-11 2021-12-03 2022-05-14 2021-12-24 2022-01-16 2022-01-28 2022-01-30 2022-07-27 re Development Specialist ement and Implementation ant Selection BEST/INDV/008 / Administrat Component 5: Project Manag Individual Consult TF / B2130 Post Open 56,250.00 56,250.00 Signed 2021-11-15 2021-11-11 2021-12-10 2022-01-18 2021-12-13 2022-01-18 2021-12-14 2022-01-30 2022-12-30 ion Assistant to PIMU ement and Implementation ant Selection BEST/INDV/003 / Procureme Component 5: Project Manag Individual Consult TF / B2130 Post Open 126,000.00 126,000.00 Signed 2021-12-05 2021-11-25 2022-01-23 2022-02-28 2022-02-13 2022-03-04 2022-03-20 2022-03-19 2022-09-16 nt Specialist (National) ement and Implementation ant Selection 025/BEST/TL / Architect to pr Component 1: Developing 2 Individual Consult Under Implement oduce standardized designs IDA / 65510 Post Open 30,000.00 0.00 2020-12-02 2022-05-18 2021-01-20 2021-02-10 2021-03-17 2021-09-13 1st Century Learning Spaces ant Selection ation and infrastructure standards 014/BEST/TL / Quality assura nce consultant for reviewing Component 4: Data Driven P Individual Consult Pending Impleme designing and development TF / B2130 lanning, Budgeting, Financin Post Open 15,000.00 0.00 2021-11-01 2021-12-20 2022-01-10 2022-02-14 2022-08-13 ant Selection ntation of system for infrastructure c g and Implementation omponent in EMIS (in 2020 a nd 2021) 010/BEST/TL / Technical Spe cialist to support the develop ment and finalization of the p Component 1: Developing 2 Individual Consult Pending Impleme IDA / 65510 Post Open 20,000.00 0.00 2020-10-30 2020-12-18 2021-01-08 2021-02-12 2021-08-11 rioritization methodology , pr 1st Century Learning Spaces ant Selection ntation eparation of prioritization pla n including priority list for sc hool construction 043/BEST/TL / Technical Assi stance to update school lead Component 2: Improving Te Individual Consult TF / B2130 Post Open 17,500.00 0.00 Signed 2022-05-08 2022-06-26 2022-06-26 2022-09-14 2022-07-17 2022-12-22 2022-08-21 2023-02-17 ers training package, develo acher Effectiveness ant Selection ping of training materials (inc luding the use experts) 039/BEST/TL / Technical Assi stance for school infrastructu Component 1: Developing 2 Individual Consult Under Implement IDA / 65510 Post Open 27,000.00 0.00 2022-04-28 2022-06-23 2022-06-16 2022-06-21 2022-07-07 2022-08-11 2023-02-07 re planning and prioritization 1st Century Learning Spaces ant Selection ation guideline development and t esting Component 3: Improving Te 045/BEST/TL / Specialist in b Individual Consult TF / B2130 aching-Learning Material an Post Open 60,000.00 51,180.00 Signed 2022-04-28 2022-06-10 2022-06-16 2022-08-23 2022-07-07 2022-08-20 2022-08-11 2022-09-02 2023-02-07 asic Education Curriculum ant Selection d Assessment 072/BEST/TL / An Internation Component 1: Developing 2 Individual Consult Open - Internationa IDA / 65510 Post 63,750.00 39,869.30 Completed 2022-07-25 2022-07-29 2022-09-12 2022-09-12 2022-10-03 2022-09-24 2022-11-07 2022-10-08 2023-05-06 2022-11-21 al Team Leader for School Ce 1st Century Learning Spaces ant Selection l nsus 073/BEST/TL / Local Technic al Consultant 1 Person (Exp ert for Design the instrument Component 1: Developing 2 Individual Consult /Questionnaire Format and T IDA / 65510 Post Open - National 22,000.00 20,730.00 Signed 2022-07-25 2022-07-29 2022-09-12 2022-09-26 2022-10-03 2022-09-14 2022-11-07 2022-09-26 2023-05-06 1st Century Learning Spaces ant Selection abulation) duration of the co ntract 4 months ( estamate $ 4,400/month incluiding Tax 1 0%) Prepare Questionnaire F orm 074/BEST/TL / TA to develop an application (Kobo Toolbox Component 1: Developing 2 Direct - Internation Under Implement IDA / 65510 Post Direct Selection 11,928.00 0.00 2022-10-28 2022-10-28 2022-11-07 2022-11-06 2023-01-11 2023-07-10 or Cs-Pro) to support School 1st Century Learning Spaces al ation Census Data Collection Proce ss 086/BEST/TL / ICT Specialist Component 5: Project Manag Individual Consult Under Implement TF / B2130 Post Open - National 73,352.00 0.00 2022-10-13 2022-09-29 2022-12-01 2022-12-22 2023-01-26 2023-07-25 for BEST Project ement and Implementation ant Selection ation 044/BEST/TL / Technical Assi stance to develop or upgrade Component 2: Improving Te Individual Consult TF / B2130 Post Open 20,250.00 0.00 Canceled 2022-04-28 2022-06-28 2022-06-16 2022-07-07 2022-08-11 2023-02-07 teacher training monitoring/ acher Effectiveness ant Selection Observation Tool and module Page 3 087/BEST/TL / Procurement Component 5: Project Manag Individual Consult Under Implement Officer to Support BEST PIMU TF / B2130 Post Open - National 64,500.00 0.00 2022-12-06 2023-04-13 2023-01-24 2023-02-14 2023-03-21 2023-09-17 ement and Implementation ant Selection ation with procurement related act ivities 098/BEST/TL / LM -Tracking Component 3: Improving Te System Development to supp Individual Consult Under Implement TF / B2130 aching-Learning Material an Post Open - National 20,000.00 0.00 2022-12-09 2022-12-02 2023-01-30 2023-02-20 2023-03-27 2023-09-23 ort the acquisition, packagin ant Selection ation d Assessment g, and distribution of TLM; es timate Component 4: Data Driven P 095/BEST/TL / TA- EMIS Dev Individual Consult Open - Internationa Pending Impleme TF / B2130 lanning, Budgeting, Financin Post 39,000.00 0.00 2022-12-26 2023-02-13 2023-03-06 2023-04-10 2023-10-07 elopment Assessment ant Selection l ntation g and Implementation 072A/BEST/TL / International Component 4: Data Driven P Individual Consult Open - Internationa Under Implement position School Census Team TF / B2130 lanning, Budgeting, Financin Post 58,000.00 0.00 2023-01-05 2022-12-03 2023-02-23 2023-03-16 2023-04-20 2023-10-17 ant Selection l ation Leader g and Implementation Component 4: Data Driven P 099/BEST/TL / ICT EMIS Deve Individual Consult Open - Internationa Under Implement TF / B2130 lanning, Budgeting, Financin Post 38,000.00 0.00 2023-01-05 2023-01-26 2023-02-23 2023-06-05 2023-03-16 2023-06-20 2023-04-20 2023-10-17 lopment Analyst ant Selection l ation g and Implementation 082/BEST/TL / Polo Bases Su Component 1: Developing 2 Individual Consult IDA / 65510 Post Open - National 2,250.00 0.00 Canceled 2022-07-25 2022-07-29 2022-09-12 2022-10-03 2022-11-07 2023-05-06 pervisor for Maliana Municipa 1st Century Learning Spaces ant Selection lity 083/BEST/TL / Polo Bases Su Component 1: Developing 2 Individual Consult IDA / 65510 Post Open - National 2,250.00 0.00 Canceled 2022-07-25 2022-07-29 2022-09-12 2022-10-03 2022-11-07 2023-05-06 pervisor for Oecussi Municipa 1st Century Learning Spaces ant Selection lity 078/BEST/TL / Polo Bases Su Component 1: Developing 2 Individual Consult IDA / 65510 Post Open - National 2,250.00 0.00 Canceled 2022-07-17 2022-07-29 2022-09-04 2022-09-25 2022-10-30 2023-04-28 pervisor for Dili Municipality 1st Century Learning Spaces ant Selection 069/BEST/TL / Polo-based su Component 1: Developing 2 Individual Consult IDA / 65510 Post Open - National 2,250.00 0.00 Canceled 2022-07-25 2022-07-29 2022-09-12 2022-10-03 2022-11-07 2023-05-06 pervisor for Manufahi Munici 1st Century Learning Spaces ant Selection pality 080/BEST/TL / Polo Bases Su pervisor for Baucau Municip Component 1: Developing 2 Individual Consult IDA / 65510 Post Open - National 2,250.00 0.00 Canceled 2022-07-25 2022-07-29 2022-09-12 2022-10-03 2022-11-07 2023-05-06 ality (duration of Contract 3 1st Century Learning Spaces ant Selection months $ 750/month) 037A/BEST/TL / Technical ex pert in education (curriculum Component 5: Project Manag Individual Consult Under Implement TF / B2130 Post Open - National 87,200.00 0.00 2023-01-10 2023-02-07 2023-02-28 2023-03-21 2023-04-25 2023-10-22 , training, school manageme ement and Implementation ant Selection ation nt) 28 months Contract 028/BEST/TL / Independent v Component 2: Improving Te Individual Consult Under Implement TF / B2130 Post Open - National 15,000.00 0.00 2021-06-30 2023-05-17 2021-08-18 2021-09-08 2021-10-13 2022-04-11 erification of DLI achievemen acher Effectiveness ant Selection ation ts 026-2023/IDV/BEST/TL / Proj Component 5: Project Manag Under Implement TF / B2130 Post Direct Selection Direct - National 115,000.00 0.00 2023-05-12 2023-05-03 2023-05-22 2023-05-03 2023-07-26 2024-01-22 ect Manager ement and Implementation ation 025-2023/IDV/BEST/TL / Proc Component 5: Project Manag Pending Impleme TF / B2130 Post Direct Selection Direct - National 88,500.00 0.00 2023-05-12 2023-05-22 2023-07-26 2024-01-22 urement Specialist ement and Implementation ntation 030-2023/IDV/BEST/TL / Envi Component 5: Project Manag Under Implement ronmental and Social Safegu TF / B2130 Post Direct Selection Direct - National 50,600.00 0.00 2023-05-12 2023-05-03 2023-05-22 2023-07-26 2024-01-22 ement and Implementation ation ard Specialist (ESSS) 028-2023/IDV/BEST/TL / Edu Component 4: Data Driven P Under Implement cation Infrastructure Plannin TF / B2130 lanning, Budgeting, Financin Post Direct Selection Direct - National 81,000.00 0.00 2023-05-12 2023-05-03 2023-05-22 2023-07-26 2024-01-22 ation g and Project Management S g and Implementation pecialist-National 029-2023/IDV/BEST/TL / Mon Component 5: Project Manag Under Implement TF / B2130 Post Direct Selection Direct - National 52,000.00 0.00 2023-05-12 2023-05-03 2023-05-22 2023-07-26 2024-01-22 itoring and Evaluation Specia ement and Implementation ation list 027-2023/IDV/BEST/TL / Ad Component 5: Project Manag Under Implement TF / B2130 Post Direct Selection Direct - National 23,500.00 0.00 2023-05-12 2023-05-03 2023-05-22 2023-05-03 2023-07-26 2024-01-22 ministration Assistant ement and Implementation ation 034-2023/IDV/BEST/TL / Inte Component 5: Project Manag Individual Consult Open - Internationa Under Implement rnational Project Managemen TF / B2130 Post 227,500.00 0.00 2023-05-12 2023-06-01 2023-06-30 2023-07-21 2023-08-25 2024-02-21 ement and Implementation ant Selection l ation t Consultant 031-2023/IDV/BEST/TL / Fina Component 5: Project Manag Individual Consult Under Implement TF / B2130 Post Open - National 58,500.00 0.00 2023-05-23 2023-06-01 2023-07-11 2023-08-01 2023-09-05 2024-03-03 nce Management Specialist ement and Implementation ant Selection ation Strengthening Forest Manag 035-2023/INDV/BEST/TL / Fin Under Implement TF / B2130 ement, Conservation, and B Post Direct Selection Direct - National 33,020.00 0.00 2023-05-23 2023-05-03 2023-06-02 2023-05-03 2023-08-06 2024-02-02 ance Officer ation usiness Development 036-2023/INDV/BEST/TL / Na Component 5: Project Manag Under Implement TF / B2130 Post Direct Selection Direct - National 63,600.00 0.00 2023-05-23 2023-05-03 2023-06-02 2023-08-06 2024-02-02 tional Project Management C ement and Implementation ation onsultant Page 4 Procurement Plan I. General 1. Project information: Loan No Nom du Projet: SUPPORTING THE ECONOMIC INCLUSION OF YOUTH PROJECT Pays: Maroc Référence du Projet : P161169 Numéro du Prêt/Crédit : Agence d’exécution : MINISTERE DE L’EMPLOI ET DE L’INSERTION PROFESSIONNELLE - 2. Bank’s approval Date of the procurement Plan Original :7/9/2019; 3. Date of General Procurement Notice: 4. Period covered by this procurement plan: 06-2019- to-31-2020 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Prior review threshold 2. Type of procurement (US$ thousands) Works (including turnkey, supply & installation of plant and equipment, 10,000 and PPP) Goods, information technology and 2,000 non-consulting services Consultants: firms 1,000 Consultants: individuals 300 Table 2.7. Thresholds for Procurement Approaches and Methods (US$ thousands) Open Open RfQ =< Type of procurement international national < ≧ Works (including turnkey, supply & installation of plant and equipment, 10,000 10,000 300 and PPP) Goods, information technology and 3,000 3,000 200 non-consulting services Shortlist of national consulting firms 300 300 2. Prequalification. NA 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: MOP of the Project 5. Any Other Special Procurement Arrangements: NA PROCUREMENT Morocco : Supporting the economic inclusion of youth PLAN General Information Country: Morocco 2020-02-11 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151169 GPN Date: Project Name: Supporting the economic inclusion of youth Loan / Credit No: IBRD / 89540 Agence nationale de promotion de l' emploi et des competances Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MA-ANAPEC-207327-CW-RF Promoting youth employabili Request for Quota Single Stage - One E 2021-07-1 IBRD / 89540 Post Open - National 25,000.00 27,786.07 Completed 2020-12-12 2021-03-02 2021-01-19 2020-12-30 Q / Aménagement EEJ Bengu ty and economic inclusion tions nvelope 8 erir MA-ANAPEC-207507-CW-RF Promoting youth employabili Request for Quota Single Stage - One E 2021-07-1 IBRD / 89540 Post Open - National 25,000.00 27,871.41 Completed 2020-12-12 2021-01-19 2021-01-03 Q / Aménagement EEJ Safi ty and economic inclusion tions nvelope 8 MA-ANAPEC-207510-CW-RF Promoting youth employabili Request for Quota Single Stage - One E 2021-07-1 Q / Aménagement EEJ Marrak IBRD / 89540 Post Open - National 25,000.00 27,950.62 Terminated 2020-12-12 2021-01-19 2021-02-27 ty and economic inclusion tions nvelope 8 ech Syba Ennakhil MA-ANAPEC-207513-CW-RF Promoting youth employabili Request for Quota Single Stage - One E 2021-07-1 Q / Aménagement EEJ Amez IBRD / 89540 Post Open - National 25,000.00 27,724.72 Terminated 2020-12-12 2021-01-19 2020-12-30 ty and economic inclusion tions nvelope 8 miz El Haouz MA-ANAPEC-207515-CW-RF Promoting youth employabili Request for Quota Single Stage - One E 2021-07-1 Q / Aménagement EEJ Attaou IBRD / 89540 Post Open - National 25,000.00 27,793.12 Completed 2020-12-12 2021-01-19 2020-12-30 ty and economic inclusion tions nvelope 8 ia El Kalaa de Sraghna MA-ANAPEC-207517-CW-RF Promoting youth employabili Request for Quota Single Stage - One E 2021-07-1 Q / Aménagement EEJ Echam IBRD / 89540 Post Open - National 25,000.00 27,910.96 Completed 2020-12-12 2021-01-19 2020-12-30 ty and economic inclusion tions nvelope 8 aiaa Youssoufia MA-ANAPEC-207518-CW-RF Promoting youth employabili Request for Quota Single Stage - One E 2021-07-1 Q / Aménagement EEJ Taman IBRD / 89540 Post Open - National 25,000.00 27,947.70 Terminated 2020-12-12 2021-01-19 2021-02-27 ty and economic inclusion tions nvelope 8 ar Essaouira MA-ANAPEC-207519-CW-RF Promoting youth employabili Request for Quota Single Stage - One E 2021-07-1 Q / Aménagement EEJ Iminta IBRD / 89540 Post Open - National 25,000.00 27,825.37 Completed 2020-12-12 2021-01-19 2020-12-30 ty and economic inclusion tions nvelope 8 nout Chichaoua MA-ANAPEC-207521-CW-RF Promoting youth employabili Request for Quota Single Stage - One E 2021-07-1 Q / Acquisition et installation IBRD / 89540 Post Open - National 25,000.00 14,432.71 Completed 2020-12-12 2021-06-29 2021-01-19 2021-07-02 ty and economic inclusion tions nvelope 8 de la signalétique des 8 EEJ MA-ANAPEC-220942-CW-RF Promoting youth employabili Request for Quota Single Stage - One E 2021-10-1 Q / Relance aménagement E IBRD / 89540 Post Open - National 25,000.00 27,549.87 Completed 2021-02-27 2021-04-17 2021-02-27 ty and economic inclusion tions nvelope 4 EJ Amezmiz El Haouz MA-ANAPEC-220943-CW-RF Promoting youth employabili Request for Quota Single Stage - One E 2021-10-1 Q / Relance aménagement E IBRD / 89540 Post Open - National 25,000.00 27,897.72 Completed 2021-02-27 2021-04-17 2021-02-27 ty and economic inclusion tions nvelope 4 EJ Syba Marrakech MA-ANAPEC-220949-CW-RF Promoting youth employabili Request for Quota Single Stage - One E 2021-10-1 Q / Relance aménagement E IBRD / 89540 Post Open - National 25,000.00 27,953.48 Completed 2021-02-27 2021-04-17 2021-03-03 ty and economic inclusion tions nvelope 4 EJ Tamanar Essaouira GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MA-ANAPEC-116706-GO-RFB Promoting youth employabili Open - Internationa Single Stage - Two E IBRD / 89540 Post Request for Bids 395,000.00 0.00 Canceled 2020-02-10 2020-04-30 2020-02-15 2020-04-30 2020-03-28 2020-07-01 2020-06-10 2020-07-07 2020-07-15 2021-01-11 / Acquisition d'unités mobiles ty and economic inclusion l nvelope MA-ANAPEC-187148-GO-RFB / ( relance suite à un AO infru ctueux) Acquisition de deux unités mobiles (deux lots) Promoting youth employabili Open - Internationa Single Stage - One E Lot 1 : deux unités mobiles p IBRD / 89540 Post Request for Bids 470,000.00 585,484.06 Completed 2020-09-30 2020-10-27 2020-10-05 2020-11-16 2020-12-03 2020-12-16 2020-12-11 2021-01-20 2021-01-01 2021-07-19 2021-10-08 ty and economic inclusion l nvelope our l’emploi (430 000 $) Lot 2 : deux Antennes VSAT à pointage automatique pour U nité mobile d’emploi (40 000 $) MA-ANAPEC-213686-GO-RFQ / Matériel de bureau pour les Promoting youth employabili Request for Quota Single Stage - One E 8 EEJ (Amizmiz, Attaouia, Be IBRD / 89540 Post Open - National 28,185.00 27,845.96 Completed 2021-02-01 2021-03-15 2021-07-27 2021-09-11 2021-08-17 ty and economic inclusion tions nvelope nguerir, Echamia, Immintano ut, Tamanar, Syba Marrakech et Safi) MA-ANAPEC-213697-GO-RFB / Appel d'offres en 2 lots : Matériel informatique (Lot 1) Promoting youth employabili Single Stage - One E et mobilier de bureau (Lot 2) IBRD / 89540 Post Request for Bids Open - National 272,830.00 223,869.73 Completed 2021-01-27 2021-03-15 2021-02-01 2021-02-22 2021-04-06 2021-03-01 2021-04-06 2021-03-22 2021-06-20 2021-09-18 2021-09-06 ty and economic inclusion nvelope pour les 8 EEJ (Amizmiz, Atta ouia, Benguerir, Echamaia, I mmintanout, Tamanar, Syba Marrakech, Safi) MA-ANAPEC-303919-GO-RFP / Renforcement du système d Promoting youth employabili Request for Propo Open - Internationa IBRD / 89540 Post Multi Stage 400,000.00 0.00 Canceled 2022-11-11 2023-02-07 2022-11-16 2023-02-07 2023-01-25 2023-03-21 2023-05-09 2023-06-13 2024-12-04 e profilage, de bilan des com ty and economic inclusion sals l pétences, de suivi et d’évalu ation MA-ANAPEC-359918-GO-RFP / Renforcement du système d Promoting youth employabili Request for Propo Open - Internationa Under Imple IBRD / 89540 Post Multi Stage 400,000.00 0.00 2023-05-07 2023-05-07 2023-05-12 2023-07-21 2023-06-19 2023-11-02 2023-12-07 2025-05-30 e profilage, de bilan des com ty and economic inclusion sals l mentation pétences, de suivi et d’évalu ation NON CONSULTING SERVICES Page 1 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MA-ANAPEC-213855-NC-RFP Promoting youth employabili Single Stage - One E / Sélection des gestionnaires IBRD / 89540 Prior Request for Bids Open - National 4,410,000.00 4,324,840.76 Signed 2021-02-08 2021-07-28 2021-02-13 2021-08-30 2021-03-06 2021-11-04 2021-04-05 2021-12-09 2021-05-10 2022-02-19 2022-05-05 ty and economic inclusion nvelope des Espaces Emploi Jeunes (E EJ) MA-ANAPEC-258496-NC-RFB / Programme Taehil Appel d'offres réalisation d’a ctions de formations qualifia Promoting youth employabili Single Stage - One E ntes ou de reconversion au p IBRD / 89540 Post Request for Bids Open - National 520,000.00 0.00 Signed 2022-04-20 2021-12-09 2022-04-20 2022-04-27 2022-09-15 2022-05-27 2022-09-16 2022-06-24 2023-06-19 ty and economic inclusion nvelope rofit des chercheurs d’emploi non diplômés dans le cadre d u projet « Appui à l’insertion économique des jeunes dans la région de Marrakech Safi » MA-ANAPEC-258497-NC-RFB / Programme Taehil AO réalis ation d’actions de formations qualifiantes ou de reconversi Promoting youth employabili Single Stage - One E on au profit des chercheurs d IBRD / 89540 Post Request for Bids Open - National 520,000.00 0.00 Signed 2022-04-20 2021-12-09 2022-04-20 2022-04-22 2022-05-10 2022-05-22 2022-08-29 2022-06-19 2023-06-14 ty and economic inclusion nvelope ’emploi diplômés inscrits à l’ ANAPEC dans le cadre du pro jet « Appui à l’insertion écon omique des jeunes dans la ré gion de MARRAKECH SAFI » MA-ANAPEC-363415-NC-RFB / Programme Taehil Appel d'o ffre réalisation d’actions de f ormations qualifiantes ou de Promoting youth employabili Single Stage - One E Under Imple reconversion filières restante IBRD / 89540 Post Request for Bids Open - National 520,000.00 0.00 2023-06-01 2023-06-02 2023-06-05 2023-06-09 2023-06-26 2023-07-10 2023-08-07 2023-09-12 ty and economic inclusion nvelope mentation s 2022 au profit des cherche urs d’emploi non diplômés pr ojet « Appui à l’insertion éco nomique des jeunes dans la r égion de Marrakech Safi » MA-ANAPEC-363416-NC-RFB / Programme Taehil Appel d'o ffre réalisation d’actions de f ormations qualifiantes ou de Promoting youth employabili Single Stage - One E Under Imple reconversion filières restante IBRD / 89540 Post Request for Bids Open - National 520,000.00 0.00 2023-06-01 2023-06-02 2023-06-05 2023-06-09 2023-06-26 2023-07-10 2023-08-07 2024-08-01 ty and economic inclusion nvelope mentation s 2022 au profit des cherche urs d’emploi diplômés projet « Appui à l’insertion économi que des jeunes dans la régio n de Marrakech Safi » CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MA-ANAPEC-213847-CS-QCB S / Sélection d’un bureau d’é tudes chargé de l’assistance Promoting youth employabili Consultant Qualifi IBRD / 89540 Post Open - National 45,000.00 36,110.40 Signed 2021-02-01 2021-04-19 2021-02-08 2021-03-08 2021-08-02 2021-04-07 2021-09-30 2021-05-05 2022-01-27 2021-11-01 technique pour la mise en pl ty and economic inclusion cation Selection ace et l’opérationnalisation d es Espaces Emploi Jeunes (EE J) et des Unités Mobiles (UM) MA-ANAPEC-228099-CS-CQS / Consultant pour Accompagn Promoting youth employabili Consultant Qualifi ement à IBRD / 89540 Post Open - National 7,100.00 0.00 Canceled 2021-04-06 2021-06-01 2021-04-07 2021-04-09 2021-05-09 2021-06-13 2021-08-12 ty and economic inclusion cation Selection l’aménagement et la réceptio n des EEJ MA-ANAPEC-228100-CS-CQS / Consultant pour Accompagn Promoting youth employabili Consultant Qualifi ement à IBRD / 89540 Post Open - National 7,900.00 0.00 Canceled 2021-05-17 2021-05-03 2021-05-31 2021-06-28 2021-07-28 2021-09-01 2021-11-30 ty and economic inclusion cation Selection l’aménagement et la réceptio n des UM MA-ANAPEC-239221-CS-CQS / Le suivi, le contrôle et la réc Promoting youth employabili Consultant Qualifi eption de la fabrication de de IBRD / 89540 Post Open - National 7,900.00 9,153.52 Completed 2021-06-14 2021-07-16 2021-06-24 2021-06-28 2021-07-27 2021-07-05 2021-07-27 2021-07-13 2021-07-30 2021-10-11 2021-10-14 ty and economic inclusion cation Selection ux unités mobiles d’emploi d estinées à la région MARRAK ECH – SAFI. MA-ANAPEC-239224-CS-CQS / Contrôle et réception des Tr avaux d’aménagement de hu Promoting youth employabili Consultant Qualifi it espaces Emploi des jeunes IBRD / 89540 Post Open - National 7,100.00 7,068.84 Signed 2021-06-14 2021-07-15 2021-06-24 2021-06-26 2021-07-27 2021-07-03 2021-07-27 2021-07-15 2021-07-30 2021-11-12 ty and economic inclusion cation Selection situés à : Marrakech, Amezmi z, Imintanout, El Attaouia, Be nguerir, Tamanar, Safi et Ech emaaia. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 Southern African Power Pool’s Program for Advancing Regional Energy Transformational Projects Project Procurement Strategy Document (PPSD) 1 Project Overview The Project Development Objective of the US$20 million IDA grant parent project— the Southern African Power Pool’s Program for Advancing Regional Energy Transformational Projects (SAPP AREP, P126661)—is to advance the preparation of selected priority regional energy projects in the Southern African Power Pool (SAPP) participating countries. The IDA funds from the parent project can be used to finance preparatory activities for only those regional energy projects that would be carried out on the territories of at least one IDA country (in good standing with IDA). However, some of the identified regional priority projects include projects that would be carried out on the territories of only IBRD countries and/or Zimbabwe (currently in arrears with IDA), even though the SAPP as a whole and other IDA member countries of the region would benefit from these projects as well. Therefore, the use of IDA funds from, and achieving fully the PDO of, the parent project is significantly constrained. Given this constraint, interest and need in further scaling up of the SAPP AREP activities, the available financing from several development partners for advancing regional integration in the SAPP region, and their strong interest to utilize the SAPP AREP implementation framework (benefiting from its well- established technical and fiduciary capacity and the World Bank supervision), a Multi-Donor Trust Fund (MDTF) was established to complement the existing IDA funds in advancing preparation of the regional projects. The MDTF has both Bank- executed and Recipient-executed portions. The proposed Additional Financing will utilize the Recipient-executed portion of the MDTF in the amount of US$8.5 million to finance the scaled up SAPP AREP activities, including expenditures and activities for the regional projects not eligible for IDA financing. Country: Southern African Power Pool Full Parent Project Name: Southern African Power Pool’s Program for Advancing Regional Energy Transformational Projects Initial Finance ($): 20 million PAD Project Reference P126661 Number: Additional Financing ($): 8.5 million PAD Project Reference P163545 Number: 2 Overview of Country, Borrower and Marketplace a. Operational Context Southern Africa is a large and diverse region with huge growth potential but also major development needs. The Southern Africa region spans a vast geographical area of nearly 9.09 million sq. km and is home to over 280 million people. The fifteen countries in the region are members of the Southern African Development Community (SADC), established in 1992 to promote socio-economic integration as well as political and security cooperation among its members. A challenging economic geography poses major constraints to expanding growth and shared prosperity in the region. Out of its fifteen countries, six are landlocked, eight have populations below 15 million people, six have economies smaller than US$10 billion per annum, and several rely on transnational river basins for their water resources. Among all African regional economic communities, the SADC presents the largest concentration of middle-income countries but also a striking disparity in the level of development of its members. South Africa is the economic engine of the region, driving demand and market opportunities in Southern Africa and beyond. Angola, Botswana, Namibia, Mauritius, Seychelles, and South Africa have a GDP per capita well in excess of US$5,000. On the opposite side of the spectrum, there are a handful of low-income countries with a GDP per capita below US$1,000 and poverty rates among the highest in Africa. However, most of these low-income countries, including DRC, Mozambique, Tanzania, Zambia, and Zimbabwe are large or potentially large economies. Knitting these emerging economies more closely together and linking them to markets in South Africa would help create a larger market and greater economic opportunities in the region. Key Conclusions Inadequate electricity access poses a major constraint to the twin goals of ending extreme poverty and boosting shared prosperity in Southern Africa. Electricity access in Southern Africa is around 28 percent – below the continental average of 31 percent – and would barely reach 17 percent – the lowest rate among all Africa sub-regions – if South Africa were excluded. In Madagascar, Zambia, Lesotho, Tanzania, DRC and Malawi less than 20 percent of the population has access to electricity; DRC and Malawi report rates below 10 percent2. In all these countries expanding electricity access is critical to complement poverty reduction efforts and thus is at the core of their national development plans. In Malawi, an electricity access rate of 30 percent of the population by 2020 has been identified in line with the Government’s goal to reach middle income status. In Zambia, the Government aims at expanding access to 66 percent of the population by 2030. In Mozambique, the national target is in the order of 50 percent of the population, to be reached by 2023. Access cannot be realistically expanded without first increasing power supply in the region. Increases in connections to households and businesses require more electricity flowing into distributions systems. Project Development Objectives (PDO): The Project Development Objective (PDO) of the project, SAPP AREP, is to advance the preparation of selected priority regional energy projects in the SAPP participating countries. The program was designed to address the lack of project preparation capacity within the SAPP to design and deliver transformational regional energy projects in Southern Africa. Result Indicators: a) Priority regional energy projects whose preparation is advanced (number); b) Projects Acceleration Team staff recruited and operational (number); c) Preparatory studies/activities for priority regional energy projects completed (number); and d) Regional analytical studies completed (number) High Level Statement of requirement: The main requirements of the project that will be delivered include, the technical feasibility and design studies for preparation generation and transmission infrastructure. b. Client Capability and PIU Assessment Given the experience with the project, robust governance, and FM/auditing arrangements, the implementation risks are Moderate. Risks related to implementation capacity within the SAPP also remain Moderate. However, the risk for long-term sustainability of the SAPP capacity-building activities remains Substantial. To mitigate this risk, a proposed colocation of the PAU function with the SAPP CC and the triggered commitment from the SAPP members to scaled-up support, coupled with the extended implementation period of the AREP Program, would substantially reduce and/or mitigate the risks. Staff loss risk associated with the relocation if the PAU office to Zimbabwe is Moderate. To mitigate this risk, positions are being advertised requiring similar qualifications and experience as with the current staff. Key Conclusions The SAPP has started work on expanding office space for PAU members relocating to Harare, utilizing their own funds with a commitment to also ensure that the project coordinator, PM, and project management adviser are kept on board after the development institutions’ support ends. c. Market Analysis The procurements and selections envisaged under the project include the Consultancy services for the Transmission Interconnector Projects. Consultancy services have many qualified firms in the international market. The SAPP also attracts several competent firms as it covers the SADC region. The following are some of the assignments that have been contracted by the SAPP-PAU: I. Luapula Project: Luapula Technical Studies EOI’s received: 20 RFP’s Received: 5 Luapula Environmental Studies EOI’s received: 16 RFP’s Received: 4 II. Mozambique Zambia Project Mozambique Zambia Technical Studies EOI’s received: 35 RFP’s Received: 6 Mozambique Zambia Environmental Studies EOI’s received: 29 RFP’s Received: 6 Key Conclusions Based on the SAPP records of awarded and implemented projects there is adequate capacity, both in terms of numbers and capability of consultants to compete for the packages. The packages are considered attractive because their values are high, and complexity is within what has been execute before. For local Zimbabwe specific Contracts, SAPP will encourage local firms to participate. To avoid paying premiums from international firms unfamiliar with doing business in Zimbabwe, SAPP will hold engagement meetings to reassure firms of availability of finances and the payment mechanisms for foreign accounts. Procurement Complexity Packaging for procurement is decided basically on following major criteria: a. Packages are decided in such a way that encourages adequate participation. b. Similar type of work is included in a package to the extent possible. c. Size of Package: The size of package has been decided taking into consideration technical requirement, the geographic spread, etc. Based on similar projects undertaken in the past generally the execution period for such packages is between 24 to 36 months. The above procurement packages can be categorized as standard and common for SAPP, based on the implementation of a series of similar projects funded by other donors. Conclusion on Procurement complexity to be included in procurement Strategy The procurement complexity is categorized as standard as the procurement packages envisaged under the project are standard consultancy services for Feasibility studies packages. International firms have implemented similar and even larger projects before. 3 Procurement Risk Analysis Risk Description Description of Mitigation Risk Owner Project Implementing Unit The SAPP is in the recruitment SAPP capacity process to strengthen the unit SAPP PAU sustainability SAPP has proposed colocation of SAPP the PAU function with the SAPP CC Staff loss risk associated with Positions are being advertised SAPP the relocation of the PAU requiring similar qualifications and office experience as with the current staff. Contract management The SAPP-PAU Procurement SAPP PAU Specialist has experience in Contract Management. Project management The SAPP-PAU work closely with SAPP PAU the Utility technical staff to project manage the studies. 4 Risk Analysis Using the information documented in the Strategic Analysis above, identify the risks associated with Project that could be mitigated by the Procurement approach. Where rating is used 5=H, 3 = M, 1=L Risk A. B C Overall Description of Description Likelihood Impact Duration Risk proposed Rating Rating rating Rating mitigation (A*B*C) Project M H M M The SAPP is in Implementing the recruitment Unit capacity process to strengthen the unit SAPP PAU M M H M SAPP has sustainability proposed colocation of the PAU function with the SAPP CC Contract M M M M The SAPP-PAU management Procurement Specialist has experience in Contract Management. Project H H M H The SAPP-PAU management work closely with the Utility technical staff to project manage the studies. 5 Stakeholder Analysis Stakehold Interest in Responsib Accountab Consul Infor er Name the Project le le t m SAPP Borrower Y Y Y Y SADC Energy Implementati - - Y Y Ministers on of priority projects SAPP - - Y Y Executive Committee SAPP - - Y Y Management Committee Consulting For - - - Y Firms undertaking the activities World Bank Financing - - Y Y Regional Regulation - - - Y Electricity Regulators Association Other - - - Y Departments NGO and - - - Y civil society 6 Procurement Objective 1. Packaging based on market analysis - to aim for an average 10 bidders; 2. Familiarizing the consulting firms with the RFPs for international approach to market through vendor conferences and pre-bid meetings and site visits, and suitably modifying and customizing the bidding conditions like qualification requirements and application of bid securities. 3. Implementation of services under the procurement in time to ensure 90 percent of bids are awarded without extending bid validity and rebid in not more than 5 percent cases, for all procurements; 4. Awarding contracts to qualified, experienced, capable bidders so that 90 percent of contracts are executed in original allocated time; 5. Contracts are completed with not more than 15 percent cost overruns by drafting detailed Terms of Reference at bidding stage and employing sound contract management services. 7 Recommended Procurement Strategy for the Project Based on the project requirements, technical solutions and market base, procurement strategy has been developed to go for individual separate packages each less than US$800,000 for consulting assignments using international approach to markets as this is a regional project. For consultant selection for firms the selection method is QCBS using RFP. Individual Consultants to support implementation will be hired using Individual Consultants Selection Method. The procurement packaging has been drafted and are presented in the next section. 8 Summary of PPSD to be inform the Bank’s preparation of the PAD Contract Title, Estimated Bank Procurement Selection Description and Cost US$ Oversight Approach Method Category Angola - Namibia $200k Post review Open QCBS Project Feasibility Study (Co-Financing) DRC - Angola Project $350k Post review Open QCBS Feasibility Study to interconnector SAPP non-Operating Member (Angola) Mozambique - Tanzania $800k Post review Open QCBS Project Pre - Feasibility Scoping Study Develop Load Forecast $300k Post review Open QCBS Methodology for SAPP Programmes Manager $500k Prior review Open Individual Consulting Project Specialist $400k Prior review Open Individual Consulting Environmental and $350k Post review Open Individual Social Development Consulting Specialist Procurement Specialist $350k Post review Open Individual Consulting Finance Officer $350k Post review Open Individual Consulting Component Description: Consulting Services Contract Attribute Selected Approach Justification Procurement Method Open International There are a is numbers of Bidding Approach Expression of Interest (EOI) consultants in the and RFP international market and Qualification Pre competition can be Standard Bidding RFP encouraged by considering Document international approach Number of Envelopes Two Conditions of Contract Standard Pricing/ Costing Method Fees and reimbursable costs Sustainability No Requirements Price Review No Negotiation No BAFO No Value Engineering No Proposal or Bid Highest combined score for Evaluation Method QCBS, and Best qualified for IC Contract Management Dedicated contract managers Approach for each contract package with regular monitoring Key Measures of Delivery of services within Success for Contract time and cost Management Thresholds PROCUREMENT HIGH SUBSTANTIAL MODERATE LOW TYPE RISK RISK RISK RISK Works 5.0 10.0 15.0 20.0 Goods, IT & Non- Consulting 1.5 2.0 4.0 6.0 Services Consultants 0.5 1.0 2.0 4.0 (Firms) Individual 0.2 0.3 0.4 0.5 Consultants PROCUREMENT Southern Africa : AFR RI-SAPP-Program for Accelerating Regional Energy/Transformational Projects PLAN General Information Country: Southern Africa 2017-08-25 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P126661 GPN Date: Project Name: AFR RI-SAPP-Program for Accelerating Regional Energy/Transformational Projects Loan / Credit No: IDA / H9890, TF / A4772 Southern African Power Pool Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZW-SAPP-34802-NC-DIR / ES IDA / H9890 Analytical support to SAPP Prior Direct Selection Direct 0.00 Canceled 2017-11-06 2017-11-11 2017-12-16 2018-06-14 MF Report translation and Pri nting ZW-SAPP-50450-NC-RFP / SA Open - Internationa Single Stage - One E PP Transmission Grid Maps D IDA / H9890 Analytical support to SAPP Post Request for Bids 0.00 Canceled 2018-03-11 2018-04-16 2018-04-12 2018-04-16 2018-05-24 2018-06-23 2018-07-28 2019-01-24 l nvelope evelopment ZW-SAPP-46472-NC-RFQ / St Request for Quota Single Stage - One E Under Imple udy Visit to the USA by the E IDA / H9890 Analytical support to SAPP Post Limited 0.00 2019-02-18 2018-05-31 2019-04-15 2019-10-12 tions nvelope mentation nvironmental Sub-Committee (ESC) ZW-SAPP-46471-NC-RFQ / ST UDY TOUR BY SAPP TRANSMI Request for Quota Single Stage - One E IDA / H9890 Analytical support to SAPP Post Limited 70,505.00 Signed 2019-02-18 2018-05-31 2019-04-15 2018-08-01 2019-10-12 SION PRICING TASK TEAM ME tions nvelope MBERS TO EUROPE AND INDI A ZW-SAPP-46468-NC-RFQ / ST UDY TOUR BY SAPP OPERATI Request for Quota Single Stage - One E NG SUB-COMMITTEE MEMBE IDA / H9890 Analytical support to SAPP Post Limited 0.00 Canceled 2019-02-15 2019-04-12 2019-10-09 tions nvelope RS TO POWER POOLS, NERC AND FERC IN THE UNITED ST ATES ZW-SAPP-73994-NC-DIR / SA PP Transmission Grid Maps D IDA / H9890 Analytical support to SAPP Post Direct Selection Direct 71,127.64 Signed 2018-08-27 2018-10-09 2018-09-01 2018-10-09 2018-10-06 2019-01-22 2019-04-04 evelopment ZW-SAPP-46474-NC-RFQ / St Request for Quota Single Stage - One E udy Tour to Europe for the S IDA / H9890 Analytical support to SAPP Post Limited 0.00 Canceled 2019-02-18 2019-04-15 2019-10-12 tions nvelope APP Executive Committee CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZW-SAPP-25547-CS-QCBS / Quality And Cost- Open - Internationa EAPP SAPP Interconnection I IDA / H9890 Project Preparation Funds Prior 829,359.44 Completed 2017-08-21 2017-08-21 2017-08-21 2017-08-21 2017-08-21 2017-08-21 2018-03-22 2017-08-21 2017-04-25 2018-08-21 2018-10-31 Based Selection l mpact Studies Consultant ZW-SAPP-25548-CS-QCBS / L Quality And Cost- Open - Internationa IDA / H9890 Project Preparation Funds Prior 381,187.30 Completed 2017-08-21 2017-08-21 2017-09-05 2018-02-07 2017-10-03 2018-03-09 2017-11-02 2018-05-15 2017-12-07 2018-07-09 2018-01-11 2018-07-09 2019-01-11 2019-12-31 uapula Environmental Consul Based Selection l tant ZW-SAPP-25549-CS-QCBS / I Quality And Cost- Open - Internationa IDA / H9890 Analytical support to SAPP Prior 10,622.34 Signed 2017-08-21 2017-08-21 2017-08-21 2017-08-21 2017-08-22 2017-08-23 2017-10-27 2017-09-27 2017-07-03 2018-09-27 nternal Auditors Based Selection l ZW-SAPP-28082-CS-QCBS / Quality And Cost- Open - Internationa Renewables energy Integrati IDA / H9890 Analytical support to SAPP Prior 0.00 Canceled 2017-09-11 2017-10-02 2017-11-15 2017-12-13 2018-01-12 2018-02-16 2018-03-23 2019-03-23 Based Selection l on Impact Study ZW-SAPP-28091-CS-QCBS / P Quality And Cost- Open - Internationa roduce roadmap for the creat IDA / H9890 Analytical support to SAPP Prior 660,495.90 Signed 2017-10-02 2017-10-30 2017-10-23 2018-02-05 2017-12-06 2018-04-05 2018-01-03 2018-02-02 2019-01-19 2018-03-09 2019-03-26 2018-04-13 2019-04-05 2019-04-13 Based Selection l ion of the fund to remove co ngestion ZW-SAPP-36767-CS-QCBS / Quality And Cost- Open - Internationa IDA / H9890 Analytical support to SAPP Prior 1,006,000.00 Completed 2017-11-14 2017-11-14 2017-11-14 2017-11-14 2017-11-14 2017-11-14 2018-05-24 2017-11-17 2016-01-15 2018-11-17 2017-12-31 SAPP Pool Plan Based Selection l ZW-SAPP-47109-CS-QCBS / T o Assess the Impact of Rene Quality And Cost- Open - Internationa wable Energy Technologies o IDA / H9890 Analytical support to SAPP Prior 459,604.59 Completed 2018-02-05 2018-02-07 2018-02-26 2018-04-24 2018-04-11 2018-10-03 2018-05-09 2018-06-08 2019-02-28 2018-07-13 2019-05-06 2018-08-17 2019-05-09 2018-12-15 2020-01-31 Based Selection l n the Operations in the South ern African Power Pool: Part 1 ZW-SAPP-47110-CS-QCBS / T o Assess the Impact of Rene Quality And Cost- Open - Internationa wable Energy Technologies o IDA / H9890 Analytical support to SAPP Prior 725,660.05 Completed 2018-02-26 2018-02-07 2018-03-19 2018-04-24 2018-05-02 2018-10-03 2018-05-30 2018-06-29 2019-04-12 2018-08-03 2019-09-26 2018-09-07 2019-10-08 2019-09-07 2023-03-23 Based Selection l n the Operations in the South ern African Power Pool Part 2 ZW-SAPP-28084-CS-QCBS / Quality And Cost- Open - Internationa Develop and implement a Bal IDA / H9890 Analytical support to SAPP Post 716,100.00 Signed 2019-03-04 2019-02-26 2019-03-25 2019-04-11 2019-05-08 2019-05-13 2019-06-05 2019-06-21 2019-07-05 2019-06-27 2019-08-09 2019-06-28 2019-09-13 2019-08-22 2020-09-12 Based Selection l ancing Market for SAPP ZW-SAPP-118444-CS-QCBS / Quality And Cost- Open - Internationa Zambia-Tanzania-Kenya (ZTK IDA / H9890 Project Preparation Funds Post 658,062.39 Signed 2019-06-18 2019-07-11 2019-07-09 2019-07-29 2019-08-22 2019-09-19 2019-09-19 2019-11-14 2019-10-19 2019-11-14 2019-11-23 2019-12-12 2019-12-28 2020-02-19 2020-12-27 Based Selection l ) Interconnector Page 1 ZW-SAPP-143657-CS-QCBS / Quality And Cost- Open - Internationa Develop Load forecast metho IDA / H9890 Analytical support to SAPP Post 459,200.00 Signed 2019-11-03 2019-11-25 2019-11-24 2019-12-02 2020-01-07 2020-03-02 2020-02-04 2020-04-21 2020-03-05 2020-05-18 2020-04-09 2020-05-18 2020-05-14 2020-07-07 2021-05-14 Based Selection l dology for SAPP ZW-SAPP-28097-CS-QCBS / Quality And Cost- Open - Internationa Develop Load forecast metho IDA / H9890 Analytical support to SAPP Prior 0.00 Canceled 2018-11-05 2019-10-03 2018-11-26 2019-01-09 2019-02-06 2019-03-08 2019-04-12 2019-05-17 2020-05-16 Based Selection l dology for SAPP ZW-SAPP-28096-CS-QCBS / P Quality And Cost- Open - Internationa reparatory work for Business IDA / H9890 Analytical support to SAPP Post 0.00 Canceled 2019-06-03 2019-06-24 2019-08-07 2019-09-04 2019-10-04 2019-11-08 2019-12-13 2020-12-12 Based Selection l Opportunities on SAPP MTP ZW-SAPP-28086-CS-CQS / D Consultant Qualifi Open - Internationa evelop and operationalize lon IDA / H9890 Analytical support to SAPP Post 0.00 Canceled 2020-08-02 2020-08-23 2020-10-06 2020-11-05 2020-12-10 2021-06-08 cation Selection l g term market surveillance in SAPP ZW-SAPP-28099-CS-QBS / Tr Quality Based Sel Open - Internationa ansmission Pricing model vali IDA / H9890 Analytical support to SAPP Post 204,593.00 Completed 2020-08-02 2020-06-02 2020-08-23 2020-06-24 2020-10-06 2020-08-19 2020-11-03 2020-09-17 2020-12-03 2020-12-10 2021-01-02 2021-02-09 2021-02-06 2021-03-06 2022-02-06 2022-09-08 ection l dation and wheeling ZW-SAPP-166910-CS-QCBS / Quality And Cost- Open - Internationa External Auditors for World B TF / A4772 Analytical support to SAPP Post 23,565.00 Signed 2020-05-03 2020-03-31 2020-05-24 2020-04-08 2020-07-07 2020-05-21 2020-08-04 2020-06-19 2020-09-03 2020-06-29 2020-10-08 2020-06-18 2020-11-12 2020-07-31 2021-11-12 Based Selection l ank Financed Projects ZW-SAPP-175715-CS-QCBS / Quality And Cost- Open - Internationa Enhancing Visibility of the Im IDA / H9890 Analytical support to SAPP Post 0.00 Canceled 2020-06-15 2020-07-06 2020-08-19 2020-09-16 2020-10-16 2020-11-20 2020-12-25 2021-12-25 Based Selection l pact of COVID-19 Regional E nergy Sector ZW-SAPP-175712-CS-QBS / I Quality And Cost- Open - Internationa TF / A4772 Analytical support to SAPP Post 75,050.00 Signed 2020-06-07 2020-06-02 2020-06-28 2020-06-30 2020-08-11 2020-08-24 2020-09-08 2020-09-21 2020-10-08 2020-10-19 2020-11-12 2020-10-29 2020-12-17 2020-12-02 2021-12-17 RP Training Based Selection l ZW-SAPP-203155-CS-QCBS / Development of the SADC Re Quality And Cost- Open - Internationa TF / A4772 Analytical support to SAPP Post 249,420.00 Completed 2020-11-15 2020-11-09 2020-12-06 2020-11-23 2021-01-19 2021-03-11 2021-02-16 2021-04-23 2021-03-18 2021-05-24 2021-04-22 2021-06-21 2021-05-27 2021-07-12 2022-05-27 2022-06-09 gional Grid Code for the Elect Based Selection l ricity Supply Industry (ESI) ZW-SAPP-219698-CS-QCBS / Quality And Cost- Open - Internationa MALAWI – ZAMBIA 400KV T TF / A4772 Project Preparation Funds Prior 0.00 Canceled 2021-04-01 2021-02-23 2021-04-22 2021-03-18 2021-06-05 2021-09-28 2021-07-03 2021-11-16 2021-08-02 2021-12-21 2021-09-06 2021-10-11 2022-10-11 Based Selection l RANSMISSION INTERCONNEC TOR ZW-SAPP-219702-CS-QCBS / MALAWI – ZAMBIA 400 kV TR Quality And Cost- Open - Internationa TF / A4772 Project Preparation Funds Post 0.00 Canceled 2021-04-01 2021-02-19 2021-04-22 2021-03-17 2021-06-05 2021-09-30 2021-07-03 2021-11-18 2021-08-02 2022-02-02 2021-09-06 2022-03-09 2021-10-11 2022-10-11 ANSMISSION INTERCONNECT Based Selection l OR ENVIRONMENTAL STUDIE S ZW-SAPP-220412-CS-QCBS / Quality And Cost- Open - Internationa IDA / H9890 Analytical support to SAPP Post 208,500.00 Completed 2021-04-01 2021-02-19 2021-04-22 2021-03-29 2021-06-05 2021-07-01 2021-07-03 2021-07-28 2021-08-02 2021-08-30 2021-09-06 2021-11-10 2021-10-11 2021-11-22 2022-10-11 2022-12-11 SAPP Data Management Syst Based Selection l em ZW-SAPP-235085-CS-QCBS / Formulation of the SADC Reg ional Infrastructure Develop Quality And Cost- Open - Internationa IDA / H9890 Analytical support to SAPP Post 0.00 Completed 2021-05-31 2021-06-01 2021-06-21 2021-10-12 2021-08-04 2022-02-02 2021-09-01 2021-12-03 2021-10-01 2022-02-01 2021-11-05 2022-02-01 2021-12-10 2022-12-10 2022-12-11 ment Master Plan (RIDMP) Sh Based Selection l ort Term Action Plan (STAP) II - Energy Chapter 2021-2027 ZW-SAPP-235489-CS-QCBS / Quality And Cost- Open - Internationa SADC 2021 Renewable Energ IDA / H9890 Analytical support to SAPP Post 0.00 Canceled 2021-06-01 2021-05-27 2021-06-22 2022-01-26 2021-08-05 2022-04-07 2021-09-02 2022-05-06 2021-10-02 2021-11-06 2021-12-11 2022-12-11 Based Selection l y and Energy Efficiency Annu al Report ZW-SAPP-235498-CS-QCBS / the Design and Development Quality And Cost- Open - Internationa IDA / H9890 Analytical support to SAPP Post 161,130.00 Completed 2021-06-01 2021-06-02 2021-06-22 2022-01-26 2021-08-05 2022-04-07 2021-09-02 2022-05-05 2021-10-02 2022-06-13 2021-11-06 2022-06-08 2021-12-11 2022-07-11 2022-12-11 2022-12-11 of a web-based Sustainable E Based Selection l nergy Knowledge Hub for SA CREEE ZW-SAPP-219708-CS-QCBS / Quality And Cost- Open - Internationa Inga – Soyo Interconnector Pr TF / A4772 Project Preparation Funds Post 0.00 Canceled 2021-11-22 2022-06-01 2021-12-13 2022-01-26 2022-02-23 2022-03-25 2022-04-29 2022-06-03 2023-06-03 Based Selection l oject Environmental Studies ZW-SAPP-219707-CS-QCBS / Quality And Cost- Open - Internationa TF / A4772 Project Preparation Funds Post 0.00 Canceled 2021-11-22 2022-06-01 2021-12-13 2022-01-26 2022-02-23 2022-03-25 2022-04-29 2022-06-03 2023-06-03 Inga – Soyo Interconnector Pr Based Selection l oject ZW-SAPP-263128-CS-QCBS / Climate Change Vulnerability Quality And Cost- Open - Internationa TF / A4772 Analytical support to SAPP Post 0.00 Completed 2021-11-22 2021-11-30 2021-12-13 2022-03-15 2022-01-26 2022-07-01 2022-02-23 2022-08-05 2022-03-25 2022-08-18 2022-04-29 2022-08-23 2022-06-03 2023-06-03 2022-12-11 Study and Provide Adaptatio Based Selection l n options for the SAPP ZW-SAPP-263140-CS-QCBS / Development of the SADC Re Quality And Cost- Open - Internationa gional Guidelines and Standa TF / A4772 Analytical support to SAPP Post 192,950.00 Completed 2021-11-22 2021-11-30 2021-12-13 2022-01-05 2022-01-26 2022-04-27 2022-02-23 2022-05-26 2022-03-25 2022-06-09 2022-04-29 2022-06-14 2022-06-03 2022-08-01 2023-06-03 2022-12-11 Based Selection l rd Agreements for the Electri city Supply Industry (ESI) ZW-SAPP-263057-CS-QCBS / Quality And Cost- Open - Internationa TF / A4772 Analytical support to SAPP Post 0.00 Canceled 2021-12-01 2022-06-16 2021-12-22 2022-02-04 2022-03-04 2022-04-03 2022-05-08 2022-06-12 2023-06-12 SAPP Pool Plan Update Based Selection l ZW-SAPP-28095-CS-QCBS / Quality And Cost- Open - Internationa Develop and implement ener IDA / H9890 Analytical support to SAPP Post 0.00 Canceled 2022-04-01 2022-04-22 2022-06-05 2022-07-03 2022-08-02 2022-09-06 2022-10-11 2023-10-11 Based Selection l gy mechanisms between EAP P and SAPP ZW-SAPP-299133-CS-QCBS / Feasibility study for concentr Quality And Cost- Open - Internationa ated dispatchable solar, wind TF / A4772 Project Preparation Funds Post 0.00 Signed 2022-06-27 2022-06-16 2022-07-18 2022-06-20 2022-08-31 2022-08-30 2022-09-28 2022-10-07 2022-10-28 2022-10-20 2022-12-02 2023-01-26 2023-01-06 2024-01-06 Based Selection l and photo-voltaic power plan ts with storage in Botswana ZW-SAPP-299440-CS-CQS / Develop and implement forei Consultant Qualifi Open - Internationa TF / A4772 Analytical support to SAPP Post 0.00 Canceled 2022-06-26 2022-06-16 2022-07-17 2022-08-30 2022-09-29 2022-11-03 2023-05-02 gn exchange management to cation Selection l ols for trading purposes ZW-SAPP-299441-CS-CQS / E Consultant Qualifi Open - Internationa nergy storage harmonisation TF / A4772 Analytical support to SAPP Post 0.00 Canceled 2022-06-27 2022-06-16 2022-07-18 2022-08-03 2022-08-31 2022-09-30 2022-11-04 2023-05-03 cation Selection l standards ZW-SAPP-310845-CS-CQS / T Consultant Qualifi Open - Internationa TF / A4772 Analytical support to SAPP Post 0.00 Canceled 2022-08-31 2022-09-21 2022-11-04 2022-12-04 2023-01-08 2023-07-07 he SAPP Multi-Media Campai cation Selection l gn ZW-SAPP-346038-CS-QCBS / Quality And Cost- Open - Internationa Pending Impleme TF / A4772 Project Preparation Funds Post 0.00 2023-04-07 2023-04-28 2023-05-13 2023-06-12 2023-06-24 2023-07-03 2023-07-22 2024-03-20 ZTK Environmental Study Up Based Selection l ntation date Page 2 ZW-SAPP-346045-CS-QCBS / Quality And Cost- Open - Internationa Pending Impleme Regional Infrastructure Finan TF / A4772 Project Preparation Funds Post 0.00 2023-03-31 2023-04-21 2023-05-26 2023-06-25 2023-07-02 2023-07-14 2023-08-04 2024-04-10 Based Selection l ntation cing Facility (RTIFF) ZW-SAPP-346050-CS-QCBS / Quality And Cost- Open - Internationa Pending Impleme IDA / H9890 Analytical support to SAPP Post 0.00 2023-03-31 2023-04-21 2023-05-03 2023-06-02 2023-06-09 2023-06-21 2023-07-07 2024-05-06 SAPP Pool Plan Update Based Selection l ntation ZW-SAPP-346066-CS-LCS / S Least Cost Selecti Open - Internationa Pending Impleme atellite Data for the Botswan IDA / H9890 Project Preparation Funds Post 0.00 2023-03-31 2023-04-12 2023-04-19 2023-05-01 2023-05-05 2023-05-10 2023-05-20 2023-06-05 on l ntation a Assignment ZW-SAPP-346082-CS-QCBS / Quality And Cost- Open - Internationa Pending Impleme TF / A4772 Project Preparation Funds Post 0.00 2023-03-31 2023-04-21 2023-05-03 2023-06-02 2023-06-16 2023-06-30 2023-07-23 2024-01-22 Inga Soyo Pre-Feasibility Stu Based Selection l ntation dy ZW-SAPP-346092-CS-QCBS / Quality And Cost- Open - Internationa Pending Impleme TF / A4772 Project Preparation Funds Post 0.00 2023-03-31 2023-04-21 2023-05-03 2023-06-02 2023-06-16 2023-06-30 2023-07-23 2024-03-22 Inga Soyo Environmental Sco Based Selection l ntation ping ZW-SAPP-346102-CS-QCBS / Quality And Cost- Open - Internationa Pending Impleme Renewable Energy and Energ IDA / H9890 Analytical support to SAPP Post 0.00 2023-03-31 2023-04-21 2023-05-01 2023-05-31 2023-06-09 2023-06-21 2023-07-12 2024-01-10 Based Selection l ntation y Efficiency 2023 Status repo rt ZW-SAPP-346110-CS-QCBS / Quality And Cost- Open - Internationa Pending Impleme TF / A4772 Project Preparation Funds Post 0.00 2023-03-31 2023-04-21 2023-05-01 2023-05-31 2023-06-07 2023-06-23 2023-07-14 2024-04-14 Financial/Legal Firm Based Selection l ntation ZW-SAPP-346117-CS-LCS / I Least Cost Selecti Open - Internationa Pending Impleme IDA / H9890 Analytical support to SAPP Post 0.00 2023-04-16 2023-05-07 2023-05-17 2023-06-16 2023-06-25 2023-07-09 2023-07-29 2024-04-30 nternal Auditors on l ntation ZW-SAPP-346120-CS-LCS / E Least Cost Selecti Open - Internationa Pending Impleme IDA / H9890 Analytical support to SAPP Post 0.00 2023-04-07 2023-04-28 2023-05-09 2023-06-07 2023-06-16 2023-07-03 2023-07-23 2023-09-22 xternal Auditors on l ntation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZW-SAPP-30314-CS-INDV / T Setting up the Project Accele Individual Consult o extend Environmental advi IDA / H9890 Prior Direct 136,236.42 Signed 2017-09-27 2017-09-28 2017-09-28 2017-10-02 2017-11-02 2017-09-29 2018-05-01 ration Team ant Selection sors contract ZW-SAPP-43423-CS-INDV / T Setting up the Project Accele Individual Consult o extend the Senior Transacti IDA / H9890 Prior Direct 0.08 Signed 2018-01-12 2018-01-12 2018-01-15 2018-01-17 2018-02-06 2018-01-19 2018-08-05 ration Team ant Selection on Advisor Contract ZW-SAPP-43426-CS-INDV / T Setting up the Project Accele Individual Consult o extend the Transaction Adv IDA / H9890 Prior Direct 241,431.36 Signed 2018-01-12 2018-01-12 2018-01-15 2018-02-05 2018-02-05 2018-02-07 2018-08-04 ration Team ant Selection isor Contract ZW-SAPP-43430-CS-INDV / T Setting up the Project Accele Individual Consult o extend the Office Administr IDA / H9890 Prior Direct 26,887.06 Signed 2018-01-12 2018-01-12 2018-01-15 2018-01-18 2018-02-05 2018-01-19 2018-08-04 ration Team ant Selection ator Coctract ZW-SAPP-43437-CS-INDV / M ozambique Malawi Regional I Individual Consult IDA / H9890 Analytical support to SAPP Post Limited 45,478.87 Completed 2018-01-12 2018-01-17 2018-01-17 2018-02-07 2018-03-14 2018-02-20 2018-09-10 2019-05-31 nterconnector Project, Revie ant Selection w of Power Pool Commercial Agreements ZW-SAPP-45217-CS-CDS / U pdating and finalising the En IDA / H9890 Analytical support to SAPP Prior Direct Selection Direct 97,985.25 Completed 2018-01-26 2018-02-06 2018-02-05 2018-04-11 2018-04-17 2018-10-08 2018-11-30 vironmental and Social Mana gement Framework (ESMF) ZW-SAPP-49291-CS-CDS / SA IDA / H9890 Analytical support to SAPP Prior Direct Selection Direct 300,000.00 Completed 2018-02-19 2018-03-15 2018-03-01 2018-05-05 2018-04-03 2018-11-01 2019-01-31 PP Pool Plan Dissemination ZW-SAPP-50458-CS-INDV / In Individual Consult dividual Consultant for SAPP IDA / H9890 Analytical support to SAPP Post Limited 0.00 Canceled 2018-02-26 2018-03-03 2018-03-24 2018-04-28 2018-10-25 ant Selection EXCO Workshop ZW-SAPP-54436-CS-INDV / O Setting up the Project Accele Individual Consult IDA / H9890 Post Open 17,300.41 Signed 2018-03-19 2018-04-18 2018-05-07 2018-05-28 2018-06-19 2018-07-02 2018-06-20 2018-12-29 ffice Administrator ration Team ant Selection ZW-SAPP-60299-CS-CDS / C ONSULTING ASSIGNMENT TO SUPPORT TWINNING ARRANG IDA / H9890 Analytical support to SAPP Post Direct Selection Direct 50,000.00 Signed 2018-05-01 2018-04-25 2018-05-11 2018-07-15 2018-06-18 2019-01-11 EMENT BETWEEN SAPP AND ENTSO-E TO BOLSTER SAPP CAPACITY ZW-SAPP-68634-CS-INDV / P Setting up the Project Accele Individual Consult IDA / H9890 Prior Direct 143,414.43 Signed 2018-07-16 2018-07-26 2018-08-16 2018-07-19 2018-09-20 2015-08-20 2019-03-19 rocurement Specialist ration Team ant Selection ZW-SAPP-81270-CS-INDV / O Setting up the Project Accele Individual Consult IDA / H9890 Post Limited 11,883.58 Signed 2018-10-14 2018-10-25 2018-10-19 2018-11-09 2018-12-14 2018-12-05 2019-06-12 ffice Aministrator ration Team ant Selection ZW-SAPP-81938-CS-INDV / Fi Setting up the Project Accele Individual Consult IDA / H9890 Post Limited 25,126.74 Signed 2018-10-22 2018-10-25 2018-10-27 2018-11-17 2018-12-22 2018-11-30 2019-06-20 nance Administrator ration Team ant Selection ZW-SAPP-84114-CS-INDV / C Setting up the Project Accele Individual Consult IDA / H9890 Prior Open 576,000.00 Signed 2018-12-03 2019-02-26 2019-01-21 2019-07-15 2019-02-11 2020-10-29 2019-03-18 2020-11-03 2021-03-07 hief Transactions Advisor ration Team ant Selection ZW-SAPP-84115-CS-INDV / P Setting up the Project Accele Individual Consult IDA / H9890 Prior Open 0.00 Canceled 2018-12-03 2019-02-26 2019-01-21 2019-02-11 2019-03-18 2021-03-07 roject Management Advisor ration Team ant Selection ZW-SAPP-84129-CS-CDS / Co mmunication Advisor for the IDA / H9890 Analytical support to SAPP Post Direct Selection Direct 25,700.00 Completed 2018-10-30 2018-10-30 2018-11-05 2018-11-13 2018-11-13 2018-12-13 2018-12-12 Pool Plan Dissemination Wor kshop ZW-SAPP-46476-CS-INDV / C APACITY BUILDING ACTIVITIE Individual Consult IDA / H9890 Analytical support to SAPP Post Limited 0.00 Canceled 2018-12-03 2019-03-05 2019-03-26 2019-04-30 2019-10-27 S FOR THE SAPP QUALITY OF ant Selection SUPPLY WORKING GROUP ZW-SAPP-84128-CS-INDV / P Setting up the Project Accele Individual Consult IDA / H9890 Post Open 101,770.32 Signed 2019-04-01 2019-04-01 2019-05-20 2020-02-10 2019-06-10 2020-05-05 2019-07-15 2020-05-10 2022-06-29 rocurement Specialist ration Team ant Selection Page 3 ZW-SAPP-94431-CS-CDS / Za mbia Tanzania Environmenta IDA / H9890 Analytical support to SAPP Prior Direct Selection Direct 441,773.06 Signed 2019-02-04 2019-01-29 2019-02-14 2019-04-02 2019-04-20 2019-07-28 2019-10-17 l and Social Impact Assessme nt (ESIA) Update ZW-SAPP-105363-CS-CDS / Review of the SAPP transmis IDA / H9890 Analytical support to SAPP Post Direct Selection Direct 3,208.45 Signed 2019-03-25 2019-03-18 2019-04-04 2019-06-08 2019-04-23 2019-12-05 sion pricing code ZW-SAPP-84118-CS-INDV / P Setting up the Project Accele Individual Consult IDA / H9890 Post Open 200,178.36 Signed 2019-06-03 2020-03-09 2019-07-22 2020-11-02 2019-08-12 2021-03-02 2019-09-16 2021-06-05 2022-08-31 roject Coordinator ration Team ant Selection ZW-SAPP-84123-CS-INDV / P Setting up the Project Accele Individual Consult IDA / H9890 Post Open 173,682.68 Signed 2019-06-03 2019-04-01 2019-07-22 2020-06-05 2019-08-12 2020-10-01 2019-09-16 2020-09-05 2022-08-31 roject Manager ration Team ant Selection ZW-SAPP-84124-CS-INDV / E Setting up the Project Accele Individual Consult nvironmental and Social Dev IDA / H9890 Post Open 104,765.84 Signed 2019-06-03 2019-04-01 2019-07-22 2019-04-01 2019-08-12 2020-02-28 2019-09-16 2020-03-04 2022-08-31 ration Team ant Selection elopment Specialist ZW-SAPP-119023-CS-CDS / Mozambique Zambia Environ IDA / H9890 Project Preparation Funds Prior Direct Selection Direct 158,553.50 Signed 2019-06-23 2020-01-22 2019-07-03 2020-02-05 2019-09-06 2020-06-30 2020-03-04 mental deviation of the trans mission line in Zambia ZW-SAPP-119027-CS-INDV / Individual Consult IDA / H9890 Analytical support to SAPP Post Open 150,000.00 Signed 2019-06-17 2019-07-08 2019-08-05 2020-12-09 2019-08-26 2021-07-14 2019-09-30 2021-07-19 2020-03-28 Communication Advisor ant Selection ZW-SAPP-136442-CS-INDV / Setting up the Project Accele Individual Consult IDA / H9890 Post Open 57,804.96 Signed 2019-10-13 2019-11-07 2019-12-01 2019-11-11 2019-12-22 2020-02-03 2020-01-26 2020-02-19 2020-07-24 Accounts Officer ration Team ant Selection ZW-SAPP-119018-CS-CDS / Mozambique Zambia Geotec IDA / H9890 Project Preparation Funds Prior Direct Selection 0.00 Canceled 2019-06-23 2019-06-23 2019-06-23 2019-06-23 hnical Investigations ZW-SAPP-119021-CS-CDS / Mozambique Zambia Technic IDA / H9890 Project Preparation Funds Prior Direct Selection Direct 0.00 Canceled 2019-06-23 2019-07-03 2019-09-06 2020-03-04 al Project deviation of the tra nsmission line in Zambia ZW-SAPP-148568-CS-CDS / Mozambique Zambia Geotec IDA / H9890 Project Preparation Funds Prior Direct Selection Direct 463,300.00 Signed 2019-12-17 2020-01-07 2019-12-27 2020-01-27 2020-03-01 2020-06-09 2020-08-28 hnical studies and Technical Deviation ZW-SAPP-161516-CS-INDV / Individual Consult Setting up of the SAPP Data IDA / H9890 Analytical support to SAPP Post Open 29,400.00 Signed 2020-03-01 2020-02-26 2020-04-19 2020-07-01 2020-05-10 2020-09-01 2020-06-14 2020-09-08 2020-12-11 ant Selection Management System ZW-SAPP-158700-CS-INDV / I Individual Consult nfrastructure Project Adminis IDA / H9890 Analytical support to SAPP Post Open 60,000.00 Signed 2020-06-01 2020-04-20 2020-07-20 2020-08-21 2020-08-10 2020-08-21 2020-09-14 2020-08-30 2021-03-13 ant Selection tration Officer ZW-SAPP-158690-CS-INDV / Individual Consult SADC Coordinator/Project Tra IDA / H9890 Analytical support to SAPP Post Open 120,000.00 Signed 2020-06-01 2020-04-20 2020-07-20 2020-08-21 2020-08-10 2020-08-21 2020-09-14 2020-08-30 2021-03-13 ant Selection nsaction Advisor ZW-SAPP-169121-CS-INDV / Individual Consult TF / A4772 Analytical support to SAPP Post Open 100,000.00 Signed 2020-05-03 2020-05-04 2020-06-21 2020-08-04 2020-07-12 2020-10-15 2020-08-16 2020-10-23 2021-02-12 SACREE Renewable Energy E ant Selection xpert ZW-SAPP-177339-CS-CDS / E nhancing Visibility of the Imp IDA / H9890 Analytical support to SAPP Prior Direct Selection Direct 0.00 Canceled 2020-06-22 2020-06-23 2020-07-02 2020-09-05 2021-03-04 act of COVID-19 Regional En ergy Sector ZW-SAPP-180507-CS-INDV / Setting up the Project Accele Individual Consult TF / A4772 Post Open 0.00 Canceled 2020-07-20 2019-04-01 2020-09-07 2020-09-28 2020-11-02 2021-05-01 Project Specialist 2 ration Team ant Selection ZW-SAPP-180505-CS-INDV / Setting up the Project Accele Individual Consult TF / A4772 Post Open 0.00 Canceled 2020-07-01 2020-08-19 2020-09-09 2020-10-14 2021-04-12 Project Specialist 1 ration Team ant Selection ZW-SAPP-189142-CS-INDV / Preparation of Discussion Pa Individual Consult per and Facilitation of a High- IDA / H9890 Analytical support to SAPP Post Limited 9,300.00 Signed 2020-08-21 2020-08-04 2020-08-26 2020-08-28 2020-09-16 2020-10-05 2020-10-21 2020-10-10 2021-04-19 2021-12-11 ant Selection level Ministerial Engagement Webinar for Energy and Wate r Sectors ZW-SAPP-193142-CS-INDV / Setting up the Project Accele Individual Consult TF / A4772 Post Open 55,937.11 Signed 2020-09-20 2020-09-15 2020-11-08 2020-11-11 2020-11-29 2021-01-11 2021-01-03 2021-02-16 2021-07-02 Procurement Specialist 2 ration Team ant Selection ZW-SAPP-219712-CS-CDS / Design, Implementation, and Operationalization of the Reg IDA / H9890 Project Preparation Funds Prior Direct Selection Direct 1,016,710.00 Completed 2021-04-01 2021-05-10 2021-04-11 2021-05-19 2021-06-15 2021-10-05 2021-12-12 2023-03-13 ional Infrastructure Financing Facility (RTIFF) for the South ern African Power Pool ZW-SAPP-246582-CS-INDV / Individual Consult IDA / H9890 Analytical support to SAPP Post Open 0.00 Canceled 2021-11-29 2021-11-30 2022-01-17 2022-02-07 2022-03-14 2022-09-10 SAPP Project Financial Analys ant Selection t ZW-SAPP-263050-CS-CDS / S APP Balancing Market Additio TF / A4772 Analytical support to SAPP Post Direct Selection Direct 73,000.00 Signed 2021-11-22 2021-10-29 2021-12-02 2022-01-26 2022-02-05 2022-02-01 2022-08-04 nal Capacity Building Exercis e ZW-SAPP-158699-CS-INDV / SADC Project Finance and Le Individual Consult gal Expert. The date for the s IDA / H9890 Analytical support to SAPP Post Open 0.00 Canceled 2020-03-02 2020-04-20 2020-05-11 2020-06-15 2020-12-12 ant Selection ubmission of TORs has chang ed from 2 March 2020 to 2 M ay 2022. ZW-SAPP-158697-CS-INDV / Individual Consult IDA / H9890 Analytical support to SAPP Post Open 0.00 Canceled 2020-03-02 2020-04-20 2020-05-11 2020-06-15 2020-12-12 SADC Project Development E ant Selection xpert ZW-SAPP-293759-CS-CDS / TF / A4772 Analytical support to SAPP Post Direct Selection Direct 0.00 Canceled 2022-05-13 2022-05-23 2022-07-27 2023-01-23 Communications and Media Services ZW-SAPP-299442-CS-INDV / Individual Consult Workshop on Market Surveill TF / A4772 Analytical support to SAPP Post Open 0.00 Canceled 2022-06-27 2022-06-16 2022-08-15 2022-09-05 2022-10-10 2023-04-08 ant Selection ance for MANCO Page 4 ZW-SAPP-299443-CS-CDS / P hase III for Feasibility Study f IDA / H9890 Project Preparation Funds Post Direct Selection Direct 0.00 Canceled 2022-06-27 2022-06-16 2022-07-07 2022-09-10 2023-03-09 or the Mozambique – Zambia Interconnector ZW-SAPP-336403-CS-CDS / P Direct - Internation hase III for Feasibility Study f IDA / H9890 Project Preparation Funds Post Direct Selection 0.00 Canceled 2023-01-22 2023-02-01 2023-04-07 2023-10-04 al or the Mozambique – Zambia Interconnector ZW-SAPP-336627-CS-CDS / RTIFF Finalisation - Design, I mplementation, and Operatio Direct - Internation IDA / H9890 Analytical support to SAPP Post Direct Selection 0.00 Canceled 2023-01-29 2023-02-08 2023-04-14 2023-10-11 nalization of the Regional Infr al astructure Financing Facility (RTIFF) for the Southern Afric an Power Pool ZW-SAPP-336630-CS-CDS / Conclusion of the Developing Direct - Internation TF / A4772 Analytical support to SAPP Post Direct Selection 0.00 Canceled 2023-01-29 2023-02-08 2023-04-14 2023-10-11 a regional information and kn al owledge management syste m / HUB ZW-SAPP-336632-CS-CDS / Direct - Internation TF / A4772 Analytical support to SAPP Post Direct Selection 0.00 Canceled 2023-01-29 2023-02-08 2023-04-14 2023-10-11 RIDMP - STAP 2 – Energy Cha al pter ZW-SAPP-346029-CS-INDV / SAPP Transmission Pricing im Individual Consult Open - Internationa Pending Impleme IDA / H9890 Analytical support to SAPP Post 0.00 2023-03-31 2023-04-26 2023-05-05 2023-05-26 2023-08-25 plementation arrangements ant Selection l ntation stakeholders' engagements ZW-SAPP-346099-CS-CDS / Develop a regional informati Direct - Internation Pending Impleme TF / A4772 Analytical support to SAPP Post Direct Selection 0.00 2023-03-31 2023-04-10 2023-05-12 2023-11-10 on and knowledge managem al ntation ent system / HUB ZW-SAPP-346112-CS-CDS / L Direct - Internation Pending Impleme TF / A4772 Analytical support to SAPP Post Direct Selection 0.00 2023-04-14 2023-04-24 2023-05-31 2023-11-29 egal Consultant al ntation ZW-SAPP-363801-CS-CDS / P Setting up the Project Accele Direct - Internation IDA / H9890 Post Direct Selection 0.00 Signed 2023-05-29 2023-05-31 2023-05-31 2023-06-02 2023-06-02 2023-11-30 rocurement Specialist ration Team al ZW-SAPP-364116-CS-CDS / E Setting up the Project Accele Direct - Internation nvironmental and Safeguards IDA / H9890 Post Direct Selection 0.00 Signed 2023-05-29 2023-06-02 2023-05-31 2023-06-02 2023-06-02 2023-11-30 ration Team al Specialist ZW-SAPP-364117-CS-CDS / P Setting up the Project Accele Direct - Internation IDA / H9890 Post Direct Selection 0.00 Signed 2023-05-29 2023-05-31 2023-05-31 2023-06-02 2023-06-02 2023-11-30 roject Specialist ration Team al ZW-SAPP-364118-CS-CDS / A Setting up the Project Accele Direct - Internation IDA / H9890 Post Direct Selection 0.00 Signed 2023-05-29 2023-06-02 2023-05-31 2023-06-02 2023-06-02 2023-11-30 ccounts Officer ration Team al ZW-SAPP-364120-CS-CDS / A Setting up the Project Accele Direct - Internation IDA / H9890 Post Direct Selection 0.00 Signed 2023-05-29 2023-05-31 2023-05-31 2023-06-02 2023-06-02 2023-11-30 dministration Officer ration Team al ZW-SAPP-364121-CS-CDS / P Setting up the Project Accele Direct - Internation IDA / H9890 Post Direct Selection 0.00 Signed 2023-05-29 2023-05-31 2023-05-31 2023-06-02 2023-06-02 2023-11-30 rogrammes Manager ration Team al ZW-SAPP-364122-CS-CDS / S Setting up the Project Accele Direct - Internation ADC Infrastructure Project Ad TF / A4772 Post Direct Selection 0.00 Signed 2023-05-29 2023-05-31 2023-05-31 2023-06-02 2023-06-02 2023-11-30 ration Team al ministration Officer ZW-SAPP-364124-CS-CDS / S Setting up the Project Accele Direct - Internation TF / A4772 Post Direct Selection 0.00 Signed 2023-05-29 2023-06-01 2023-05-31 2023-06-02 2023-06-02 2023-11-30 ACREEE Renewables Expert ration Team al ZW-SAPP-364125-CS-CDS / S Setting up the Project Accele Direct - Internation Pending Impleme ADC Coordinator/Project Tran TF / A4772 Post Direct Selection 0.00 2023-05-29 2023-05-31 2023-06-02 2023-11-30 ration Team al ntation saction Advisor Page 5 Summarized Procurement Plan I. GENERAL Project information: Borrower: Government of Lesotho Project Name: Eswatini COVID19 FTCF Project Project ID No: P 173883 Grant No.: Project Implementing Agency: Ministry of Health Bank’s approval Date of the Procurement Plan: May 2020 Date of General Procurement Notice: Period covered by this procurement plan: 18 months II. Goods and Works and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by IDA as stated in the Procurement Regulations for IPF Borrowers: Thresholds for Procurement Methods and Prior Review Goods, Works and Non- Consulting Services Procurement Approaches and Methods (US$ Prior millions) Review Category Open Open Request for (US$ millions) International National Quotation (RfQ) Works ≥ 15 ≥7 <7 ≤ 0.2 Goods, IT, and non- ≥4 ≥1 <1 ≤ 0.1 consulting services 2. Reference to (if any) Project Operational/Procurement Manual: The Procurement Plan also forms part of the Project Implementation Manual approved on May 2020. 1 3. Procurement Packages with Methods and Time Schedule Procurement of Goods & Non-consulting Services Summary 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Comments No. Cost Preference by Bank US$ million (yes/no) (Prior / Post) Summary of the ICB & NIL NIL NIL Nil NCB (Works) Summary of the RFQ 0.31 2 NIL Post NIL (Works) Summary of the ICB NIL NIL NIL NIL NIL (Goods) Summary of the NCB NIL NIL NIL NIL NIL (Goods) Summary of the RfQ 1.13 14 NIL Post Nil (Goods & Non- Consulting Services) Summary of the DC 1.7 7 NIL Post (Goods &NCS) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in the Procurement Regulations for IPF Borrowers: Thresholds for Consultants Selection Methods and Prior Review Thresholds for Consultants Selection Methods and Prior Review for Consulting Services Category Prior Short List of National Consultants (US$ million) Review 2 (US$ Consulting Engineering and millions) Services Construction Supervision Consultants (Firms) ≥2 ≤ 0.1 ≤ 0.3 Individual Consultants ≥ 0.3 NA. NA. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of the Procurement Regulations for IPF Borrowers. 3. Terms of Reference (TOR) for all consultancy contracts as well as all direction selections, irrespective of the contract value, will be subject to prior review. 4. Any Other Special Selection Arrangements: N/A 5. Consultancy Assignments with Selection Methods and Time Procurement of Consulting Services Summary 1 2 3 4 5 6 Ref. No. Description of Estimated Package Review Comments Assignment Cost s by Bank (Prior / US$ million Post) Summary of NIL 0 Post contracts through QCBS Summary of Nil Nil Post NIL contracts through CQS 3 Summary of 0.036 3 Post NIL contracts through IC 4 PROCUREMENT Eswatini : Eswatini COVID-19 Emergency Response Project PLAN General Information Country: Eswatini 2020-05-18 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173883 GPN Date: 2020-07-29 Project Name: Eswatini COVID-19 Emergency Response Project Loan / Credit No: IBRD / 90980, IBRD / 92310, TF / B5461 Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SZ-MOH-191062-CW-RFQ / I Component 1: Emergency C Request for Quota Single Stage - One E 2021-04-2 nstallation of HVAC system a IBRD / 90980 OVID-19 Response and Eval Post Limited 200,000.00 198,526.57 Signed 2020-09-02 2020-09-16 2020-10-28 2020-10-29 tions nvelope 6 t RFM ICU and Renal wards uation Request for Quota SZ-MOH-300662-CW-RFQ / C Component 1: Emergency C Request for Quota Single Stage - One E tions - Small Work 2023-02-2 onstruction of Access Road fo IBRD / 92310 OVID-19 Response and Eval Post Limited 74,000.00 83,091.83 Signed 2022-07-05 2022-06-30 2022-08-30 2022-09-17 tions nvelope s (Emergency) SP 6 r Bulk Tank at RFMH uation D -Competitive Request for Quota SZ-MOH-343519-CW-RFQ / F Component 1: Emergency C Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-10-2 encing of Incinerator House a IBRD / 92310 OVID-19 Response and Eval Post Limited 58,800.00 0.00 2023-02-28 2023-03-28 2023-04-25 tions nvelope s (Emergency) SP mentation 2 t Mbabane Government Hosp uation D -Competitive ital Request for Quota SZ-MOH-364394-CW-RFQ / C Component 1: Emergency C Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-01-2 onstruction of Drainage at RF IBRD / 92310 OVID-19 Response and Eval Post Limited 35,294.00 0.00 2023-06-07 2023-06-02 2023-08-02 tions nvelope s (Emergency) SP mentation 9 M uation D -Competitive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SZ-MOH-174106-GO-RFQ / P rint and distribute Public Hea Component 1: Emergency C lth Emergency Operations Ce Request for Quota Single Stage - One E IBRD / 90980 OVID-19 Response and Eval Post Limited 11,000.00 0.00 Canceled 2020-06-03 2020-07-29 2021-01-25 ntre Manual (# of copies??), tions nvelope uation 500 copies of Case definition, 1000 copies of IDNS booklets , 1000 investigation forms SZ-MOH-174107-GO-RFQ / U Component 1: Emergency C Request for Quota Single Stage - One E pgrade of Infectious Disease IBRD / 90980 OVID-19 Response and Eval Post Limited 370,000.00 0.00 Canceled 2020-06-03 2020-07-29 2021-01-25 tions nvelope Notification Systems (IDNS) uation SZ-MOH-174114-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 90980 Post Limited 8,000.00 0.00 Canceled 2020-06-03 2020-07-29 2021-01-25 rocure 20 phones for RRTs OVID-19 Response and Eval tions nvelope uation SZ-MOH-174116-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 90980 Post Limited 10,000.00 0.00 Canceled 2020-06-03 2020-07-29 2021-01-25 rocure and Setup Surveillanc OVID-19 Response and Eval tions nvelope e Server uation SZ-MOH-174123-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E rint 30,000 copies of SOPs fo IBRD / 90980 OVID-19 Response and Eval Post Limited 2,500.00 0.00 Canceled 2020-06-03 2020-07-29 2021-01-25 tions nvelope r entry and exit screening uation SZ-MOH-174124-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E rocure and Install 9 mounted IBRD / 90980 OVID-19 Response and Eval Post Limited 372,000.00 0.00 Canceled 2020-06-03 2020-07-29 2021-01-25 tions nvelope Med-thermal scanners uation SZ-MOH-174127-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E rocure 35 handheld thermo s IBRD / 90980 OVID-19 Response and Eval Post Limited 155,738.00 0.00 Canceled 2020-06-03 2020-07-29 2021-01-25 tions nvelope canners and batteries uation SZ-MOH-174135-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E rocure 4 prefabs for isolation/ IBRD / 90980 OVID-19 Response and Eval Post Limited 67,000.00 0.00 Canceled 2020-06-03 2020-07-29 2021-01-25 tions nvelope separation rooms for entry p uation oints SZ-MOH-174142-GO-RFP / Pr Component 1: Emergency C Request for Propo Single Stage - Two E ocure 15 temporary toilets fo IBRD / 90980 OVID-19 Response and Eval Post Limited 18,700.00 0.00 Canceled 2020-06-01 2020-06-06 2020-07-18 2020-09-30 2020-11-04 2021-05-03 sals nvelope r ports of entry uation SZ-MOH-174145-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 90980 Post Limited 18,600.00 0.00 Canceled 2020-06-06 2020-08-01 2021-01-28 rocure 15 water tanks for por OVID-19 Response and Eval tions nvelope ts of entry uation SZ-MOH-174147-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E rocure 2 large portable medi IBRD / 90980 OVID-19 Response and Eval Post Limited 33,000.00 0.00 Canceled 2020-06-06 2020-08-01 2021-01-28 tions nvelope cal emergency tents uation SZ-MOH-174151-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 90980 Post Limited 28,000.00 53,105.93 Completed 2020-06-06 2020-09-25 2020-08-01 2020-11-26 2021-01-28 2021-02-20 rocure Tablets for reporting a OVID-19 Response and Eval tions nvelope nd calling uation SZ-MOH-174154-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E rint and disseminate protocol IBRD / 90980 OVID-19 Response and Eval Post Limited 1,000.00 0.00 Canceled 2020-06-06 2020-08-01 2021-01-28 tions nvelope s for specimen collection and uation shipment SZ-MOH-186250-GO-RFQ / S Component 1: Emergency C Request for Quota Single Stage - One E upply and Delivery of advanc IBRD / 90980 OVID-19 Response and Eval Post Limited 226,600.00 0.00 Canceled 2020-08-03 2020-08-04 2020-09-28 2021-03-27 tions nvelope ed life support ambulances uation SZ-MOH-174-GO-RFQ / 4x4 Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 90980 Post Limited 350,000.00 398,405.51 Terminated 2020-09-20 2020-06-22 2020-11-15 2020-10-10 2021-05-14 Double Cabs with Canopy OVID-19 Response and Eval tions nvelope uation SZ-MOH-196092-GO-APA / S Component 1: Emergency C IBRD / 90980 Post Direct Selection Direct 655,000.00 655,650.00 Completed 2020-09-24 2020-09-30 2020-09-29 2020-09-30 2020-11-03 2020-06-12 2021-05-02 2021-01-15 upply of PPE OVID-19 Response and Eval uation SZ-MOH-197198-GO-RFQ / Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 90980 Post Limited 300,000.00 94,793.08 Signed 2020-10-07 2020-10-08 2020-12-02 2020-12-10 2021-05-31 2021-02-05 Waste Care management co OVID-19 Response and Eval tions nvelope mmodities uation SZ-MOH-203322-GO-RFQ / S Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 90980 Post Limited 226,600.00 170,994.63 Completed 2020-11-11 2020-11-25 2021-01-06 2021-01-27 2021-07-05 2021-11-13 upply and Delivery Of Ambul OVID-19 Response and Eval tions nvelope ances uation Page 1 SZ-MOH-206386-GO-RFQ / C Component 1: Emergency C Request for Quota Single Stage - One E ovid-19 Reagents and Suppli IBRD / 90980 OVID-19 Response and Eval Post Limited 140,000.00 0.00 Canceled 2020-11-30 2021-01-25 2021-07-24 tions nvelope es for Laboratory uation SZ-MOH-216521-GO-RFQ / R Component 1: Emergency C Request for Quota Single Stage - One E e-award of Contract for Dou IBRD / 90980 OVID-19 Response and Eval Post Limited 350,000.00 445,196.07 Completed 2021-02-02 2020-06-22 2021-03-30 2021-01-08 2021-09-26 2021-06-04 tions nvelope ble Cab Vehicles uation SZ-MOH-217168-GO-RFQ / S Component 1: Emergency C Request for Quota Single Stage - One E upply and Delivery Of Person IBRD / 90980 OVID-19 Response and Eval Post Limited 500,000.00 1,229,608.56 Signed 2021-02-08 2021-02-05 2021-04-05 2021-04-17 2021-10-02 2021-07-26 tions nvelope al Protective Equipment (PPE uation ) SZ-MOH-224484-GO-DIR / Pr Component 1: Emergency C IBRD / 90980 Post Direct Selection Direct 140,000.00 165,967.20 Signed 2021-03-12 2021-03-18 2021-03-17 2021-03-18 2021-04-21 2021-04-21 2021-10-18 ocurement of PCR Reagents OVID-19 Response and Eval uation SZ-MOH-228120-GO-RFQ / S Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 90980 Post Limited 1,200,000.00 1,199,644.95 Completed 2021-04-12 2021-06-07 2020-05-12 2021-12-04 2020-11-03 upply and delivery of PPE OVID-19 Response and Eval tions nvelope uation SZ-MOH-229360-GO-RFQ / S Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 90980 Post Limited 10,000.00 0.00 Canceled 2021-04-24 2021-04-28 2021-06-19 2021-12-16 upply and Delivery of a serve OVID-19 Response and Eval tions nvelope r uation SZ-MOH-235163-GO-RFQ / S Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Post Limited 120,000.00 170,287.60 Completed 2021-05-25 2021-07-29 2021-07-20 2021-08-27 2022-01-16 2022-02-03 upply and Delivery of Tablets OVID-19 Response and Eval tions nvelope uation SZ-MOH-236497-GO-RFQ / S Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Prior Limited 200,000.00 0.00 Canceled 2021-06-05 2021-07-31 2022-01-27 upply and Delivery of Patient OVID-19 Response and Eval tions nvelope s cards uation SZ-MOH-239217-GO-DIR / Su Component 1: Emergency C IBRD / 92310 Post Direct Selection Direct 15,200.00 17,179.80 Completed 2021-06-11 2021-06-03 2021-06-16 2021-06-17 2021-07-21 2021-08-14 2022-01-17 2022-03-30 pply of Covid Sequencing rea OVID-19 Response and Eval gents uation SZ-MOH-240788-GO-RFQ / Pl Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Post Limited 550,000.00 4,642.02 Signed 2021-06-28 2021-07-27 2021-08-23 2021-09-14 2022-02-19 umbing Material OVID-19 Response and Eval tions nvelope uation SZ-MOH-256462-GO-RFQ / S Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Post Limited 200,000.00 98,046.11 Completed 2021-10-09 2021-05-27 2021-12-04 2021-09-14 2022-06-02 2021-12-18 upply and delivery of patient OVID-19 Response and Eval tions nvelope cards uation SZ-MOH-278864-GO-DIR / Cl Component 1: Emergency C ass II, Type A2 4' Biological S IBRD / 92310 OVID-19 Response and Eval Post Direct Selection Direct 13,632.94 16,656.80 Completed 2022-02-16 2022-02-02 2022-02-21 2022-03-09 2022-03-28 2022-05-13 2022-09-24 2022-07-01 afety Cabinet uation SZ-MOH-282168-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Post Limited 666,667.00 625,764.83 Terminated 2022-03-12 2022-03-08 2022-05-07 2022-05-08 2022-11-03 ersonal Protective Equipment OVID-19 Response and Eval tions nvelope (PPEs) uation SZ-MOH-282172-GO-RFQ / C Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Post Limited 28,129.00 8,733.64 Completed 2022-03-12 2022-03-24 2022-05-07 2022-05-18 2022-11-03 2022-08-09 omputers and Accessories OVID-19 Response and Eval tions nvelope uation SZ-MOH-282174-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Post Limited 115,833.00 0.00 Canceled 2022-03-20 2022-05-15 2022-11-11 rocure RDT Abbot test kits an OVID-19 Response and Eval tions nvelope d PCR kits uation SZ-MOH-285470-GO-RFQ / Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Post Limited 16,000.00 5,507.66 Completed 2022-03-27 2022-03-23 2022-05-22 2022-05-20 2022-11-18 2022-06-14 Water Dispensers OVID-19 Response and Eval tions nvelope uation SZ-MOH-288610-GO-DIR / A Component 1: Emergency C IBRD / 92310 Prior Direct Selection Direct 116,000.00 0.00 Canceled 2022-04-07 2022-04-12 2022-05-17 2022-11-13 bbott Panbio COVID-19 Antig OVID-19 Response and Eval en Test uation SZ-MOH-288995-GO-DIR / A Component 1: Emergency C IBRD / 92310 Post Direct Selection Direct 116,000.00 93,328.40 Completed 2022-04-08 2022-04-12 2022-04-13 2022-04-12 2022-05-18 2022-05-20 2022-11-14 2022-06-28 bbott Panbio COVID-19 Antig OVID-19 Response and Eval en Test Kits uation SZ-MOH-293887-GO-RFQ / P Component 2: Implementati Request for Quota Single Stage - One E rocurement of Double Cabin IBRD / 92310 on Management and Monitor Post Limited 50,000.00 0.00 Canceled 2022-05-15 2022-05-10 2022-07-10 2023-01-06 tions nvelope 4x4 vehicle ing and Evaluation SZ-MOH-293889-GO-RFQ / S Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Post Limited 3,300.00 0.00 Canceled 2022-05-17 2022-05-18 2022-07-12 2023-01-08 tress Management Tools OVID-19 Response and Eval tions nvelope uation SZ-MOH-295771-GO-RFQ / M Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Post Limited 31,500.00 99,232.46 Completed 2022-05-28 2022-05-19 2022-07-23 2022-09-03 2023-01-19 2022-09-30 obile X-ray OVID-19 Response and Eval tions nvelope uation SZ-MOH-296025-GO-RFQ / N Component 1: Emergency C Request for Quota Single Stage - One E on Communicable Diseases a IBRD / 92310 OVID-19 Response and Eval Post Limited 233,000.00 0.00 Canceled 2022-05-25 2022-05-23 2022-07-20 2023-01-16 tions nvelope nd COVID Starter Packs Medi uation cines SZ-MOH-303921-GO-RFQ / N Component 1: Emergency C Request for Quota Single Stage - One E on-Communicable Diseases a IBRD / 92310 OVID-19 Response and Eval Post Limited 233,000.00 0.00 Signed 2022-07-20 2022-07-14 2022-09-14 2023-03-13 tions nvelope nd COVID Starter Packs Medi uation cines Component 2: Implementati SZ-MOH-306652-GO-RFQ / D Request for Quota Single Stage - One E IBRD / 92310 on Management and Monitor Post Limited 50,000.00 0.00 Completed 2022-08-09 2022-08-04 2022-10-04 2023-04-02 ouble Cabin 4x4 Vehicle tions nvelope ing and Evaluation Component 2: Implementati SZ-MOH-306654-GO-RFQ / L Request for Quota Single Stage - One E IBRD / 92310 on Management and Monitor Post Limited 10,700.00 14,625.48 Signed 2022-08-09 2022-08-04 2022-10-04 2022-09-25 2023-04-02 aptop Computers tions nvelope ing and Evaluation SZ-MOH-306657-GO-RFQ / T Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Post Limited 86,700.00 0.00 Canceled 2022-08-09 2022-08-04 2022-10-04 2023-04-02 ents OVID-19 Response and Eval tions nvelope uation SZ-MOH-306648-GO-RFQ / S Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Post Limited 3,300.00 0.00 Canceled 2022-08-09 2022-08-04 2022-10-04 2023-04-02 tress Management Tools OVID-19 Response and Eval tions nvelope uation SZ-MOH-316726-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Post Limited 86,700.00 0.00 Signed 2022-09-26 2022-09-20 2022-11-21 2023-05-20 rocurement of Tents OVID-19 Response and Eval tions nvelope uation SZ-MOH-319155-GO-RFQ / S Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 92310 Post Limited 3,300.00 0.00 Signed 2022-10-11 2022-10-05 2022-12-06 2023-06-04 tress Management Tools OVID-19 Response and Eval tions nvelope uation SZ-MOH-343529-GO-RFQ / P Component 1: Emergency C Request for Quota Single Stage - One E Under Imple IBRD / 92310 Post Limited 27,600.00 0.00 2023-02-28 2023-02-23 2023-04-25 2023-10-22 CR Reagents OVID-19 Response and Eval tions nvelope mentation uation SZ-MOH-349218-GO-RFQ / In Component 1: Emergency C Request for Quota Single Stage - One E Under Imple IBRD / 92310 Post Limited 1,294.00 0.00 2023-03-21 2023-03-14 2023-05-16 2023-11-12 cinerator Site Signage OVID-19 Response and Eval tions nvelope mentation uation SZ-MOH-357234-GO-RFQ / P Component 2: Strengthening Request for Quota Single Stage - One E Under Imple ower Backup Generator for N TF / B5461 Capacity in Preparedness for Post Limited 19,396.56 0.00 2023-04-25 2023-04-20 2023-06-20 2023-12-17 tions nvelope mentation ational PHEOC Health Emergencies Page 2 Component 2: Strengthening SZ-MOH-357237-GO-RFQ / P Request for Quota Single Stage - One E Under Imple TF / B5461 Capacity in Preparedness for Post Limited 75,000.00 0.00 2023-04-25 2023-04-20 2023-06-20 2023-12-17 HEOC Furniture tions nvelope mentation Health Emergencies Component 2: Strengthening SZ-MOH-357240-GO-RFQ / IT Request for Quota Single Stage - One E Under Imple TF / B5461 Capacity in Preparedness for Post Limited 50,603.44 0.00 2023-04-25 2023-04-20 2023-06-20 2023-12-17 Equipment for PHEOC tions nvelope mentation Health Emergencies Component 2: Strengthening SZ-MOH-358698-GO-RFQ / P Request for Quota Single Stage - One E Under Imple TF / B5461 Capacity in Preparedness for Post Limited 282,353.00 0.00 2023-05-08 2023-05-03 2023-07-03 2023-12-30 rocurement of 4x vehicles tions nvelope mentation Health Emergencies SZ-MOH-364397-GO-RFQ / IT Component 2: Strengthening Request for Quota Single Stage - One E Under Imple Equipment and Software for TF / B5461 Capacity in Preparedness for Post Limited 83,490.00 0.00 2023-06-07 2023-06-02 2023-08-02 2024-01-29 tions nvelope mentation EDCU Health Emergencies NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SZ-MOH-174128-NC-RFQ / C Component 1: Emergency C Request for Quota Single Stage - One E alibration of buffer stock med IBRD / 90980 OVID-19 Response and Eval Post Limited 33,300.00 0.00 Canceled 2020-06-03 2020-07-29 2021-01-25 tions nvelope i-thermo scanners uation SZ-MOH-294512-NC-RFQ / M Component 1: Emergency C Request for Quota Single Stage - One E aintenance of Incinerators at IBRD / 92310 OVID-19 Response and Eval Post Limited 98,000.00 71,596.80 Completed 2022-05-17 2022-05-19 2022-07-12 2022-07-10 2023-01-08 2022-09-16 tions nvelope Health facilities uation SZ-MOH-336909-NC-DIR / M Component 1: Emergency C aintenance of Incinerator at IBRD / 92310 OVID-19 Response and Eval Post Direct Selection Direct - National 27,500.00 0.00 Canceled 2023-01-19 2023-01-24 2023-02-28 2023-08-27 Mbabane Government Hospit uation al CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Strengthening SZ-MOH-312844-CS-CQS / P Consultant Qualifi TF / B5461 Capacity in Preparedness for Post Limited 187,500.00 0.00 Canceled 2022-09-12 2022-09-26 2022-10-26 2022-11-30 2023-05-29 ublic Health Consultant Local cation Selection Health Emergencies SZ-MOH-360814-CS-CQS / T Component 2: Strengthening Consultant Qualifi Open - Internationa Under Implement A for training on Basic Public TF / B5461 Capacity in Preparedness for Post 247,647.00 0.00 2023-05-15 2023-05-16 2023-06-05 2023-05-23 2023-07-19 2023-08-18 2023-09-22 2024-03-20 cation Selection l ation Health Emergency Managem Health Emergencies ent INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SZ-MOH-201290-CS-INDV / H Component 1: Emergency C Individual Consult IBRD / 90980 Post Open 45,000.00 106,277.89 Signed 2020-10-23 2020-05-11 2020-12-11 2020-10-06 2021-01-01 2020-10-06 2021-02-05 2020-11-28 2021-08-04 iring of Social Officer OVID-19 Response and Eval ant Selection uation SZ-MOH-201292-CS-INDV / P Component 1: Emergency C Individual Consult IBRD / 90980 Post Open 60,000.00 78,000.00 Signed 2020-10-23 2020-05-11 2020-12-11 2020-08-03 2021-01-01 2020-11-24 2021-02-05 2020-11-26 2021-08-04 rocurement Specialist OVID-19 Response and Eval ant Selection uation SZ-MOH-201295-CS-INDV / S Component 1: Emergency C Individual Consult ENIOR MONOTORING AND EV IBRD / 90980 OVID-19 Response and Eval Post Open 60,000.00 164,372.01 Signed 2020-10-23 2021-01-20 2020-12-11 2021-02-17 2021-01-01 2021-04-06 2021-02-05 2021-04-14 2021-08-04 ant Selection ALUATION OFFICER uation SZ-MOH-201297-CS-INDV / S Component 1: Emergency C Individual Consult ENIOR FINANCIAL MANAGEM IBRD / 90980 OVID-19 Response and Eval Post Open 60,000.00 156,000.00 Terminated 2020-10-23 2020-05-11 2020-12-11 2020-10-06 2021-01-01 2020-10-05 2021-02-05 2020-12-02 2021-08-04 ant Selection ENT SPECIALIST uation SZ-MOH-201305-CS-INDV / S Component 1: Emergency C Individual Consult IBRD / 90980 Post Open 45,000.00 48,694.71 Signed 2020-10-23 2020-05-11 2020-12-11 2020-08-13 2021-01-01 2020-10-06 2021-02-05 2020-11-28 2021-08-04 ENIOR ENVORONMENTAL OF OVID-19 Response and Eval ant Selection FICER uation SZ-MOH-229441-CS-INDV / A Component 1: Emergency C Individual Consult IBRD / 90980 Post Open 84,400.00 59,057.19 Signed 2021-04-15 2021-05-03 2021-06-03 2021-08-06 2021-06-24 2021-09-08 2021-07-29 2021-09-09 2022-01-25 ssistant Procurement Officer OVID-19 Response and Eval ant Selection uation SZ-MOH-231575-CS-INDV / C Component 1: Emergency C Individual Consult IBRD / 92310 Post Open 158,400.00 109,689.22 Signed 2021-05-10 2021-05-18 2021-06-28 2021-08-02 2021-07-19 2021-08-25 2021-08-23 2021-08-28 2022-02-19 ommunications Officer OVID-19 Response and Eval ant Selection uation Component 2: Implementati SZ-MOH-314781-CS-INDV / A Individual Consult IBRD / 92310 on Management and Monitor Post Open - National 28,000.00 0.00 Signed 2022-09-13 2022-09-13 2022-11-01 2023-02-02 2022-11-22 2023-02-14 2022-12-27 2023-06-25 ssistant Accountant ant Selection ing and Evaluation Component 2: Strengthening SZ-MOH-324004-CS-INDV / P Individual Consult TF / B5461 Capacity in Preparedness for Post Limited 187,500.00 0.00 Canceled 2023-01-13 2023-01-17 2023-01-18 2023-02-01 2023-02-08 2023-03-15 2023-09-11 ublic Health Consultant Local ant Selection Health Emergencies Component 2: Strengthening SZ-MOH-352822-CS-INDV / D Individual Consult Under Implement TF / B5461 Capacity in Preparedness for Post Open - National 11,765.00 0.00 2023-03-30 2023-03-28 2023-05-18 2023-05-04 2023-06-08 2023-07-13 2024-01-09 ata Architect ant Selection ation Health Emergencies Component 2: Strengthening SZ-MOH-352824-CS-INDV / D Individual Consult Under Implement TF / B5461 Capacity in Preparedness for Post Open - National 22,059.00 0.00 2023-03-30 2023-03-28 2023-05-18 2023-05-04 2023-06-08 2023-07-13 2024-01-09 ata Analyst ant Selection ation Health Emergencies Component 2: Strengthening SZ-MOH-353918-CS-INDV / P Individual Consult TF / B5461 Capacity in Preparedness for Post Open - National 48,000.00 0.00 Canceled 2023-04-05 2023-04-03 2023-05-24 2023-06-14 2023-07-19 2024-01-15 ublic Health Consultant Local ant Selection Health Emergencies SZ-MOH-358893-CS-INDV / P Component 1: Emergency C Individual Consult Under Implement IBRD / 92310 Post Open - National 15,882.00 0.00 2023-05-03 2023-04-28 2023-06-21 2023-07-12 2023-08-16 2024-02-12 lumbing Supervisor OVID-19 Response and Eval ant Selection ation uation Page 3 Procurement Plan: Project Preparation Advance to the Gambia State Owned Enterprises Restructuring Project I. General 1. Project information: The Gambia, Directorate of Public and Private Partnership and Public Enterprises – DPPP & PC, Ministry of Finance and Economic Affairs (MoFEA) Project Name: Gambia State Owned Enterprises Restructuring Project Project ID: P166695 Loan/Credit No: N/A Project Implementing Agency (PIA): Project Coordination Unit of the PIU of NAWEC 2. Bank’s approval Date of the procurement Plan: NA 3. Date of General Procurement Notice: N/A 4. Date of Procurement Plan: 05/02/2019 5. Period covered by this procurement plan: 6 months II. Goods and Non - Consulting Services. 1. Prior Review Threshold: Project Preparation Advance to the Gambia State Owned Enterprises Restructuring Project – March 2019 1 Procurement Procurement Method Prior Review Threshold US$ Method Thresholds US$ Substanti Moderate Low High Risk al Risk Risk Risk ICB Goods, Information ≥300,000 2 million 4 million 6 million 1. Technology and Non- NCB ≥100,000 1.5 million Consulting Services Shopping <100,000 2. 3. Proposed Procedures for CDD: NA 4. Reference to (if any) Project Operational/Procurement Manual: NA 5. Any Other Special Procurement Arrangements: NA Project Preparation Advance to the Gambia State Owned Enterprises Restructuring Project – March 2019 2 6. Procurement Packages with Methods and Time Schedule Goods and Service Pre- Domes Revie Expec Estimat tic w ted Comme Nº Procureme qualific Contract ed Prefer by Bid- nts nt ation (Description) Cost (yes/no ence Bank Openi Method USD ) (yes/n (Prior ng o) / Post) Date IT Equipment and 1 support to fiduciary 10,000 Shopping No No Post May-19 staff Project Preparation Advance to the Gambia State Owned Enterprises Restructuring Project – March 2019 3 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Sq Selection Method Procurement Prior Review Threshold US$ Method Thresholds US$ High Risk Substanti Modera Low risk al Risk te Risk 1. Consultant Services QCBS ≥300,000 (Firms) QCBS, LCS, FBS ≥200,000 0.5 million 1 million 2 million 4 million QC <200,000 3 Qualified EOI CV 2. Individual Consultants 0.2 million ≥100,00 0.3 million 0.4 0.5 million 0 <100,000 million 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $200,000_______equivalent per contract, may comprise entirely of national consultants in accordance with the procedures as described in the Procurement Regulations for IPF. 3. Any Other Special Selection Arrangements: N/A Project Preparation Advance to the Gambia State Owned Enterprises Restructuring Project – March 2019 4 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 7 Expecte Review d Estimat Selecti Ref by Proposal Description of Assignment ed on Commen . Bank s Cost Metho ts No. (Prior / Submiss (USD) d Post) ion Date Transaction advisor (consortium) for 1,000,0 1 QCBS Prior June 2019 the whole fibre network 00 Transaction advisor (consortium) for 1,000,0 2 privatization of GAMCEL and QCBS Prior June 2019 00 repositioning of GAMTEL Elaboration of the Project Procurement 3 Development Strategy (PPSD) and 30,000 IC Post May 2019 support procurement activities. Extension of Ernst & Special purpose audits of seven state- Single Young 4 500,000 Prior June 2019 owned enterprises source LLP to cover the balance Elaboration of an Environmental and 5 25,000 IC Post May 2019 Social Commitment Plan Elaboration of a Retrenchment Plan- 6 40,000 IC Post May 2019 and the Grievance Redress Mechanism Elaboration of a Stakeholder 7 30,000 IC Post May 2019 Engagement Plan (SEP) For Elaboration of Labor Management 8 informati Procedures on 9 Legal specialist (review and finalization 50,000 IC Post May 2019 Single Project Preparation Advance to the Gambia State Owned Enterprises Restructuring Project – March 2019 5 1 2 3 4 5 6 7 Expecte Review d Estimat Selecti Ref by Proposal Description of Assignment ed on Commen . Bank s Cost Metho ts No. (Prior / Submiss (USD) d Post) ion Date of the SOE Act at) source Elaboration of an operational manual including FM and procurement 10 50,000 IC Post May 2019 procedures of the SOE Restructuring Project) May - 11 Financial Management Specialist 25,000 IC Post 2019 12 Procurement specialist 25,000 IC Post May-2019 Project Preparation Advance to the Gambia State Owned Enterprises Restructuring Project – March 2019 6 PROCUREMENT Gambia, The : GAMBIA FISCAL MANAGEMENT DEVELOPMENT PROJECT PLAN General Information Country: Gambia, The 2019-05-13 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166695 GPN Date: Project Name: GAMBIA FISCAL MANAGEMENT DEVELOPMENT PROJECT Loan / Credit No: IDA / V2740, IDA / D6190 Public Private Partnerships and Public Enterprises Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GM-PPPPE-114268-GO-RFQ / Component 3: Project Imple Request for Quota Single Stage - One E Under Imple IT Equipment and support to IDA / V2740 mentation Support and Refo Post Limited 10,000.00 0.00 2019-05-20 2019-07-15 2020-01-11 tions nvelope mentation fiduciary staff rm Coordination Component 2: Supporting Fi GM-PPPPE-148456-CS-CQS / scal Management of State-O Request for Quota Single Stage - One E Accounting Software for the IDA / V2740 Post Limited 20,000.00 17,486.11 Signed 2020-10-03 2021-06-11 2020-11-28 2021-07-28 2021-05-27 wned Enterprises (“SOEs”) a tions nvelope Project nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-219722-GO-RFQ / Component 3: Project Imple Request for Quota Single Stage - One E Refurbishment of PIU Office f IDA / V2740 mentation Support and Refo Post Open - National 50,000.00 53,169.98 Signed 2021-02-20 2021-02-15 2021-04-17 2021-03-10 2021-10-14 tions nvelope or the Project rm Coordination Component 2: Supporting Fi GM-PPPPE-221302-GO-RFQ / scal Management of State-O Request for Quota Single Stage - One E Purchase of Motor Vehicle for IDA / V2740 Post Open - National 48,100.00 50,889.85 Completed 2021-03-05 2021-03-15 2021-04-30 2021-04-27 2021-10-27 2021-05-06 wned Enterprises (“SOEs”) a tions nvelope NAO nd Restructuring Plans of Tel ecom SOEs Component 2: Supporting Fi GM-PPPPE-221303-GO-RFQ / scal Management of State-O Request for Quota Single Stage - One E Purchase Laptops and Printer IDA / V2740 Post Open - National 16,000.00 33,542.26 Completed 2021-03-05 2021-03-18 2021-04-30 2021-09-22 2021-10-27 2021-10-29 wned Enterprises (“SOEs”) a tions nvelope s for NAO nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-228409-GO-RFQ / Component 3: Project Imple Request for Quota Single Stage - One E Purchase of 4x4 Wheel drive IDA / D6190 mentation Support and Refo Post Open - National 50,000.00 49,038.46 Completed 2021-04-14 2021-05-03 2021-05-04 2021-07-21 2021-08-02 2021-08-14 tions nvelope Station Wagon for the Project rm Coordination Office GM-PPPPE-240117-GO-RFB / Component 2: Supporting Fi ACQUISITION OF A BILLING V scal Management of State-O Single Stage - One E IDA / D6190 Prior Request for Bids Open - National 150,000.00 0.00 Canceled 2021-06-28 2021-07-03 2021-07-31 2021-08-14 2021-09-11 2021-12-10 ERIFICATION SYSTEM FOR M wned Enterprises (“SOEs”) a nvelope OBILE SERVICES IN THE GAM nd Restructuring Plans of Tel BIA ecom SOEs GM-PPPPE-252161-GO-RFB / Acquisition of a of Data Cent Component 1: Strengthening er Migration Equipment and Open - Internationa Single Stage - One E IDA / D6190 Revenue Collection and Publ Post Request for Bids 300,000.00 0.00 Canceled 2021-10-01 2021-10-12 2021-10-06 2021-10-18 2021-11-17 2021-12-17 2022-01-21 2022-04-21 Provision of Migration Service l nvelope ic Procurement Processes s for the Ministry of Informati on and Communication Infras tructure GM-PPPPE-258306-GO-RFQ / Component 3: Project Imple Request for Quota Single Stage - One E Supply and Delivery of Diesel IDA / D6190 mentation Support and Refo Post Open - National 25,000.00 0.00 Canceled 2021-10-15 2021-11-01 2022-04-30 tions nvelope Fuel for the Project Vehicles rm Coordination GM-PPPPE-262487-GO-RFQ / Component 2: Supporting Fi Request for Quotation for Su scal Management of State-O Request for Quota Single Stage - One E IDA / D6190 Post Limited 15,000.00 16,952.91 Signed 2021-11-20 2021-11-26 2022-01-15 2021-12-16 2022-03-16 pply and Delivery of 10 Lapto wned Enterprises (“SOEs”) a tions nvelope p Computers for DPPP nd Restructuring Plans of Tel ecom SOEs Component 2: Supporting Fi GM-PPPPE-264676-GO-RFB / scal Management of State-O Open - Internationa Single Stage - One E ELECTROMAGNETIC RADIATI IDA / D6190 Post Request for Bids 250,000.00 240,000.00 Signed 2021-12-06 2021-12-14 2021-12-11 2022-01-13 2022-01-22 2022-02-22 2022-02-21 2022-05-05 2022-03-28 2022-05-13 2022-09-24 wned Enterprises (“SOEs”) a l nvelope ON TOOLS nd Restructuring Plans of Tel ecom SOEs Component 2: Supporting Fi GM-PPPPE-240117-GO-RFB-2 scal Management of State-O Open - Internationa Single Stage - One E / Acquisition of a Billing Syste IDA / D6190 Post Request for Bids 150,000.00 223,611.00 Signed 2022-02-02 2021-10-25 2022-02-07 2022-05-14 2022-03-21 2021-12-09 2022-04-20 2021-12-16 2022-05-25 2022-03-08 2022-11-21 wned Enterprises (“SOEs”) a l nvelope m for PURA nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-296209-GO-RFQ / Component 2: Supporting Fi Acquisition of Office Furnitur scal Management of State-O Request for Quota Single Stage - One E Under Imple IDA / D6190 Post Limited 25,000.00 0.00 2022-05-28 2022-06-02 2022-07-23 2022-08-22 e and related accessories for wned Enterprises (“SOEs”) a tions nvelope mentation Directorate of State-owned E nd Restructuring Plans of Tel nterprises ecom SOEs GM-PPPPE-296210-GO-RFQ / Component 2: Supporting Fi Acquisition of IT and Office E scal Management of State-O Request for Quota Single Stage - One E IDA / D6190 Post Open - National 15,000.00 0.00 Canceled 2022-05-28 2022-06-09 2022-07-23 2022-08-22 quipment for Directorate of S wned Enterprises (“SOEs”) a tions nvelope tate-owned Enterprises DSOE nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-305097-GO-RFQ / Component 1: Strengthening Request for Quota Single Stage - One E Under Imple Acquisition of a Project and C IDA / D6190 Revenue Collection and Publ Post Open - National 100,000.00 0.00 2022-07-30 2022-09-24 2022-11-23 tions nvelope mentation ontract Management Softwar ic Procurement Processes e for GRA GM-PPPPE-307311-GO-RFB / Component 2: Supporting Fi DIGITAL MAPPING AND INVEN scal Management of State-O Open - Internationa Single Stage - One E Under Imple IDA / D6190 Post Request for Bids 200,000.00 0.00 2022-08-09 2023-06-21 2022-08-14 2022-08-17 2022-09-25 2022-10-25 2022-11-29 2023-05-28 TRY OF TELECOMMS/ICT INFR wned Enterprises (“SOEs”) a l nvelope mentation ASTRUCTURE nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-319779-GO-RFB / SUPPLY, IMPLEMENTATION A Component 1: Strengthening Open - Internationa Single Stage - One E Under Imple ND COMMISSIONING OF AN I IDA / D6190 Revenue Collection and Publ Prior Request for Bids 7,000,000.00 0.00 2022-10-10 2022-11-16 2022-10-15 2022-11-24 2022-12-14 2023-02-10 2023-01-13 2023-02-17 2023-08-16 l nvelope mentation NTEGRATED TAX ADMINISTR ic Procurement Processes ATION SYSTEM FOR THE GAM BIA REVENUE AUTHORITY GM-PPPPE-321775-GO-RFQ / Component 2: Supporting Fi Request for Quotation for IT scal Management of State-O Request for Quota Single Stage - One E Under Imple IDA / D6190 Post Limited 20,000.00 0.00 2022-10-20 2022-11-17 2022-12-01 Equipment for National Asse wned Enterprises (“SOEs”) a tions nvelope mentation mbly nd Restructuring Plans of Tel ecom SOEs Page 1 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GM-PPPPE-294405-NC-RFQ / Component 1: Strengthening Request for Quota Single Stage - One E Design, Develop and Validate IDA / D6190 Revenue Collection and Publ Post Open - National 60,000.00 0.00 Canceled 2022-05-18 2022-07-13 2023-01-09 tions nvelope Website for the Gambia Reve ic Procurement Processes nue Authority CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GM-PPPPE-114252-CS-QCBS Component 3: Project Imple Quality And Cost- Open - Internationa / Transaction Advisor (Consor IDA / V2740 mentation Support and Refo Prior 1,000,000.00 0.00 Canceled 2019-05-21 2019-06-11 2019-07-25 2019-08-22 2019-09-21 2019-10-26 2019-11-30 2020-11-29 Based Selection l tium) for the whole fibre net rm Coordination work GM-PPPPE-114250-CS-QCBS Component 2: Supporting Fi / Transaction Advisor (consor scal Management of State-O Quality And Cost- Open - Internationa IDA / V2740 Post 1,000,000.00 723,565.00 Signed 2019-05-21 2019-08-21 2019-06-11 2019-10-02 2019-07-25 2020-09-11 2019-08-22 2020-12-23 2019-09-21 2021-03-30 2019-10-26 2021-06-17 2019-11-30 2021-07-15 2020-11-29 tium) for privatization of GAM wned Enterprises (“SOEs”) a Based Selection l CEL and repositioning of GAM nd Restructuring Plans of Tel TEL ecom SOEs GM-PPPPE-161632-CS-CQS / Advisory services to elaborat Component 1: Strengthening e a Business Process Re-engi Consultant Qualifi Open - Internationa Under Implement IDA / V2740 Revenue Collection and Publ Post 250,000.00 0.00 2020-02-28 2020-04-29 2020-03-20 2020-04-29 2020-05-03 2020-10-05 2020-06-02 2020-07-07 2021-01-03 neering (BPR) that covers all cation Selection l ation ic Procurement Processes GRA processes including stud y tours; and provision of TA GM-PPPPE-176407-CS-QCBS Component 1: Strengthening Quality And Cost- Open - Internationa / Tax expenditure review poli IDA / V2740 Revenue Collection and Publ Prior 1,000,000.00 0.00 Canceled 2020-06-01 2020-06-22 2020-08-05 2020-09-02 2020-10-02 2020-11-06 2020-12-11 2021-12-11 Based Selection l cy ic Procurement Processes GM-PPPPE-180663-CS-QCBS Component 2: Supporting Fi / Review and update of the In scal Management of State-O Quality And Cost- Open - Internationa formation Communication Ac IDA / V2740 wned Enterprises (“SOEs”) a Post 300,000.00 245,921.00 Signed 2020-06-17 2020-06-29 2020-07-08 2020-06-30 2020-08-21 2020-11-09 2020-09-18 2021-04-16 2020-10-18 2021-04-16 2020-11-22 2021-06-07 2020-12-27 2021-07-17 2021-12-27 Based Selection l t 2009 and PURA Act 2001 (i nd Restructuring Plans of Tel ncluding data protection and ecom SOEs cyber security) Component 2: Supporting Fi GM-PPPPE-192433-CS-QCBS scal Management of State-O Quality And Cost- Open - Internationa / Data Center Migration Proje IDA / V2740 Post 300,000.00 0.00 Canceled 2020-09-24 2020-10-05 2020-10-15 2020-10-05 2020-11-28 2021-01-18 2020-12-26 2021-01-25 2021-03-01 2021-04-05 2022-04-05 wned Enterprises (“SOEs”) a Based Selection l ct nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-194498-CS-QCBS Component 2: Supporting Fi / Consultancy for the develop scal Management of State-O Quality And Cost- Open - Internationa ment of the “Government Clo IDA / V2740 wned Enterprises (“SOEs”) a Post 150,000.00 374,057.29 Signed 2020-09-24 2020-10-05 2020-10-15 2020-10-05 2020-11-28 2022-02-02 2020-12-26 2022-03-14 2021-01-25 2022-05-04 2021-03-01 2022-06-06 2021-04-05 2022-07-13 2022-04-05 Based Selection l ud Strategy/Policy and the Cl nd Restructuring Plans of Tel oud Migration Plan” in The G ecom SOEs ambia GM-PPPPE-199306-CS-LCS / Component 3: Project Imple Recruitment of an external a Least Cost Selecti IDA / D6190 mentation Support and Refo Post Open - National 60,000.00 20,635.87 Signed 2020-10-12 2020-11-09 2020-11-02 2020-11-16 2020-12-16 2021-02-11 2021-01-13 2021-04-13 2021-02-12 2021-04-13 2021-03-19 2021-05-26 2021-04-23 2021-06-23 2021-10-20 udit and independent verifica on rm Coordination tion of the DLIs of the GFMDP GM-PPPPE-211260-CS-CQS / Component 1: Strengthening Consultant Qualifi Open - Internationa Under Implement Professionalization of the Pub IDA / V2740 Revenue Collection and Publ Post 150,000.00 0.00 2020-12-28 2022-03-01 2021-01-18 2022-03-04 2021-03-03 2022-05-07 2021-04-02 2021-05-07 2021-11-03 cation Selection l ation lic Procurement Function in T ic Procurement Processes he Gambia Component 2: Supporting Fi GM-PPPPE-212607-CS-CQS / scal Management of State-O Consultant Qualifi Open - Internationa IDA / V2740 Post 150,000.00 169,607.00 Completed 2021-01-11 2021-01-13 2021-02-01 2021-02-11 2021-03-17 2021-04-21 2021-04-16 2021-06-02 2021-05-21 2021-06-15 2021-11-17 2021-11-18 PURA Spectrum Management wned Enterprises (“SOEs”) a cation Selection l nd Restructuring Plans of Tel ecom SOEs Component 2: Supporting Fi GM-PPPPE-212608-CS-CQS / scal Management of State-O Consultant Qualifi Open - Internationa IDA / V2740 Post 150,000.00 0.00 Canceled 2021-01-11 2021-01-13 2021-02-01 2021-03-17 2021-04-16 2021-05-21 2021-11-17 QOS 4G Upgrade wned Enterprises (“SOEs”) a cation Selection l nd Restructuring Plans of Tel ecom SOEs Component 2: Supporting Fi GM-PPPPE-212606-CS-CQS / scal Management of State-O Consultant Qualifi Open - Internationa PURA Billing System Verificat IDA / V2740 Post 150,000.00 0.00 Canceled 2021-01-11 2021-01-13 2021-02-01 2021-02-14 2021-03-17 2021-04-16 2021-05-21 2021-11-17 wned Enterprises (“SOEs”) a cation Selection l ion nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-240119-CS-CQS / Component 1: Strengthening Capacity Building in Project a Consultant Qualifi Open - Internationa IDA / D6190 Revenue Collection and Publ Post 150,000.00 97,290.00 Signed 2021-06-21 2021-07-07 2021-07-12 2021-07-12 2021-08-25 2021-09-21 2021-09-24 2021-11-17 2021-10-29 2021-11-24 2022-04-27 nd Contract Management Tra cation Selection l ic Procurement Processes ining of Staff of the Gambia R evenue Authority GM-PPPPE-264481-CS-QCBS Component 2: Supporting Fi / ICT MARKET DEFINITION AN scal Management of State-O Quality And Cost- Open - Internationa Under Implement IDA / D6190 Post 220,000.00 0.00 2021-11-29 2021-12-02 2021-12-14 2021-12-07 2022-01-12 2022-04-11 2022-02-09 2022-04-11 2022-02-23 2022-04-27 2022-03-16 2022-05-23 2022-04-20 2022-07-19 D SIGNIFICANT MARKET POW wned Enterprises (“SOEs”) a Based Selection l ation ER (SMP) ASSESSMENT nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-264689-CS-CQS / Component 2: Supporting Fi CONSULTANCY SERVICES FO scal Management of State-O Consultant Qualifi IDA / D6190 Post Open - National 25,000.00 0.00 Canceled 2021-11-24 2021-11-23 2021-12-15 2022-01-13 2022-01-28 2022-02-27 2022-04-03 2022-09-30 R THE DEVELOPMENT OF AN wned Enterprises (“SOEs”) a cation Selection INTERNAL AUDIT REGULATOR nd Restructuring Plans of Tel Y FRAMEWORK ecom SOEs GM-PPPPE-264700-CS-QCBS Component 1: Strengthening / CONSULTANCY SERVICES F Quality And Cost- Open - Internationa IDA / D6190 Revenue Collection and Publ Post 370,000.00 0.00 Canceled 2021-11-24 2021-12-15 2022-01-28 2022-02-25 2022-03-27 2022-05-01 2022-06-05 2022-11-12 OR THE DEVELOPMENT OF A Based Selection l ic Procurement Processes COMPLIANCE MANAGEMENT STRATEGY GM-PPPPE-277676-CS-CQS / Component 2: Supporting Fi Technical Assistance to Stren scal Management of State-O Consultant Qualifi IDA / D6190 Post Open - National 150,000.00 221,000.00 Signed 2022-02-09 2022-02-08 2022-03-02 2022-02-08 2022-04-15 2022-05-04 2022-05-15 2022-04-28 2022-06-19 2022-05-13 2023-06-19 gthen State Owned Enterpris wned Enterprises (“SOEs”) a cation Selection e Performance Management nd Restructuring Plans of Tel Capacity ecom SOEs GM-PPPPE-278183-CS-QCBS / Development of a Complian Component 1: Strengthening Quality And Cost- Open - Internationa ce Risk Management Framew IDA / D6190 Revenue Collection and Publ Post 170,000.00 0.00 Canceled 2022-02-14 2022-02-10 2022-03-07 2022-04-20 2022-05-18 2022-06-17 2022-07-22 2022-08-26 2023-02-22 Based Selection l ork and Policy, Manual and St ic Procurement Processes rategy for the Domestic Taxe s Department Page 2 GM-PPPPE-281769-CS-CQS / Recruitment of Consultant Fir Component 2: Supporting Fi m to provide Technical Assist scal Management of State-O Consultant Qualifi Under Implement ance for the Internal Audit D IDA / D6190 wned Enterprises (“SOEs”) a Post Open - National 25,000.00 0.00 2022-03-02 2022-03-02 2022-03-23 2022-03-04 2022-05-06 2022-04-21 2022-06-05 2022-07-28 2022-07-10 2023-01-06 cation Selection ation epartment for the Developm nd Restructuring Plans of Tel ent of Audit Charters and Rel ecom SOEs ated services for State-owne d Enterprises (SOEs). GM-PPPPE-282058-CS-CQS / Component 2: Supporting Fi INFRASTRUCTURE SHARING scal Management of State-O Consultant Qualifi Open - Internationa Under Implement IDA / D6190 Post 150,000.00 0.00 2022-03-04 2022-03-04 2022-03-25 2022-04-04 2022-05-08 2023-02-15 2022-06-07 2023-02-15 2022-07-12 2022-11-09 REGULATIONS AND PRICE CA wned Enterprises (“SOEs”) a cation Selection l ation PS nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-284338-CS-CQS / Component 2: Supporting Fi EXECUTIVE Training on Corpo scal Management of State-O Consultant Qualifi rate Governance and Strateg IDA / D6190 wned Enterprises (“SOEs”) a Post Open - National 150,000.00 0.00 Canceled 2022-03-21 2022-03-22 2022-04-11 2022-05-25 2022-06-24 2022-07-29 2023-01-25 cation Selection ic Leadership & Effectiveness nd Restructuring Plans of Tel for Board Of Directors ecom SOEs GM-PPPPE-286101-CS-CQS / Component 2: Supporting Fi Leadership Development Trai scal Management of State-O Consultant Qualifi Under Implement IDA / D6190 Post Open - National 200,000.00 0.00 2022-03-28 2022-03-23 2022-04-18 2022-03-29 2022-06-01 2022-04-19 2022-07-01 2022-08-05 2022-10-04 ning for Women In STATE OW wned Enterprises (“SOEs”) a cation Selection ation NED ENTERPRISES” nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-286110-CS-CQS / Component 2: Supporting Fi RECRUITMENT OF CONSULTA scal Management of State-O NT FIRM TO CARRY OUT AN E Consultant Qualifi Under Implement IDA / D6190 wned Enterprises (“SOEs”) a Post Open - National 25,000.00 0.00 2022-03-28 2022-03-23 2022-04-18 2022-04-19 2022-06-01 2023-02-15 2022-07-01 2023-02-15 2022-08-05 2023-02-01 XTERNAL QUALITY ASSESSME cation Selection ation nd Restructuring Plans of Tel NT OF THE INTERNAL AUDIT ecom SOEs FUNCTION-GOVERNMENT OF THE GAMBIA GM-PPPPE-287077-CS-CQS / Component 2: Supporting Fi THE REVIEW OF LEGAL AND scal Management of State-O Consultant Qualifi Open - Internationa REGULATORY FRAMEWORK P IDA / D6190 wned Enterprises (“SOEs”) a Post 100,000.00 0.00 Canceled 2022-03-29 2022-03-30 2022-04-19 2022-06-02 2022-07-02 2022-08-06 2023-02-02 cation Selection l ERTAINING TO THE GAMBIA P nd Restructuring Plans of Tel UBLIC UTILITIES REGULATOR ecom SOEs Y AUTHORITY (PURA) GM-PPPPE-307600-CS-CQS / Component 2: Supporting Fi EXECUTIVE Training on Corpo scal Management of State-O Consultant Qualifi Open - Internationa Under Implement rate Governance and Strateg IDA / D6190 wned Enterprises (“SOEs”) a Post 220,000.00 0.00 2022-08-08 2022-10-04 2022-08-23 2022-10-05 2022-09-20 2023-01-12 2022-10-04 2022-11-01 2022-12-01 cation Selection l ation ic Leadership & Effectiveness nd Restructuring Plans of Tel for Board Of Directors ecom SOEs INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GM-PPPPE-114227-CS-CDS / Component 3: Project Imple Individual Consultant to deve IDA / V2740 mentation Support and Refo Post Direct Selection Direct 10,000.00 8,843.98 Completed 2019-05-10 2019-05-13 2019-05-20 2019-05-07 2019-07-24 2019-05-27 2020-01-20 2019-08-01 lop the PPSD for The Gambia rm Coordination SOE Project GM-PPPPE-114255-CS-INDV / Component 3: Project Imple Individual Consult Elaboration of an Environme IDA / V2740 mentation Support and Refo Post Limited 25,000.00 23,980.00 Completed 2019-05-14 2019-05-21 2019-05-19 2019-06-07 2019-06-09 2019-06-14 2019-07-14 2019-06-18 2020-01-10 2019-11-08 ant Selection ntal and Social Commitment rm Coordination Plan MOFEA/GSOERP/C3/07 / Elab Component 3: Project Imple Individual Consult oration of a Stakeholder Eng IDA / V2740 mentation Support and Refo Post Limited 30,000.00 23,500.00 Completed 2019-05-15 2019-06-18 2019-05-20 2019-06-18 2019-06-10 2019-07-03 2019-07-15 2019-07-04 2020-01-11 2019-11-08 ant Selection agement Plan (SEP) rm Coordination GM-PPPPE-114260-CS-INDV / Component 3: Project Imple Individual Consult Financial Management Speci IDA / V2740 mentation Support and Refo Post Open 25,000.00 1,788.79 Signed 2019-05-15 2019-05-17 2019-07-03 2019-10-21 2019-07-24 2019-11-20 2019-08-28 2019-11-28 2020-02-24 ant Selection alist rm Coordination Component 3: Project Imple GM-PPPPE-114263-CS-INDV / Individual Consult IDA / V2740 mentation Support and Refo Post Open 25,000.00 1,788.79 Signed 2019-05-15 2019-05-17 2019-07-03 2019-10-21 2019-07-24 2019-11-20 2019-08-28 2019-11-28 2020-02-24 Procurement Specialist ant Selection rm Coordination GM-PPPPE-114262-CS-INDV / Component 3: Project Imple Legal Specialist (review and f IDA / V2740 mentation Support and Refo Post Direct Selection Direct 50,000.00 8,750.00 Signed 2019-05-20 2019-07-23 2019-05-30 2019-08-05 2019-08-03 2019-08-21 2020-01-30 inalization of SOE Act) rm Coordination Component 2: Supporting Fi GM-PPPPE-114253-CS-CDS / scal Management of State-O Special purpose audits of sev IDA / V2740 Post Direct Selection Direct 500,000.00 500,000.00 Completed 2019-05-21 2019-06-14 2019-05-31 2019-06-03 2019-08-04 2019-06-18 2020-01-31 2021-01-19 wned Enterprises (“SOEs”) a en state-owned enterprises nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-115124-CS-INDV / Component 3: Project Imple Elaboration of a Retrenchme Individual Consult IDA / V2740 mentation Support and Refo Post Open 40,000.00 47,200.00 Completed 2019-05-23 2019-06-06 2019-07-11 2019-06-11 2019-08-01 2019-06-14 2019-09-05 2019-06-18 2020-03-03 2019-11-08 nt Plan and the Grievance Re ant Selection rm Coordination dress Mechanism GSOERP/MOFEA/C3/09 / Elab Component 3: Project Imple oration of an operational ma Individual Consult IDA / V2740 mentation Support and Refo Post Open 50,000.00 0.00 Canceled 2019-06-10 2019-07-29 2019-08-19 2019-09-23 2020-03-21 nual including FM and Procur ant Selection rm Coordination ement procedures of the SOE Restructuring Project GM-PPPPE-123479-CS-INDV / Component 2: Supporting Fi Local Legal Consultant to furt scal Management of State-O Individual Consult her review and update the dr IDA / V2740 wned Enterprises (“SOEs”) a Post Limited 10,000.00 9,245.74 Completed 2019-07-22 2019-07-18 2019-07-27 2019-07-29 2019-08-17 2019-07-29 2019-09-21 2019-08-13 2020-03-19 2019-12-19 ant Selection aft SOE Bill pertaining to Publ nd Restructuring Plans of Tel ic Enterprises (SOE) in The G ecom SOEs ambia GM-PPPPE-130023-CS-INDV / Component 2: Supporting Fi Recruitment of a Legal Advis scal Management of State-O or to support the establishme Individual Consult IDA / V2740 wned Enterprises (“SOEs”) a Post Limited 100,000.00 1,811.08 Signed 2019-09-04 2019-09-04 2019-09-09 2020-08-12 2019-09-30 2020-09-24 2019-11-04 2020-09-29 2020-05-02 nt of a new Special Purpose ant Selection nd Restructuring Plans of Tel Vehicle for National Wholesal ecom SOEs e Fibre Infrastructure in The Gambia GM-PPPPE-148398-CS-INDV / Component 2: Supporting Fi Consultant for the preparatio scal Management of State-O Individual Consult IDA / V2740 Post Limited 5,000.00 4,844.21 Completed 2019-12-15 2019-12-24 2019-12-20 2020-02-27 2020-01-10 2020-03-26 2020-02-14 2020-03-28 2020-08-12 2020-10-15 n of Project Implementation wned Enterprises (“SOEs”) a ant Selection Manual nd Restructuring Plans of Tel ecom SOEs Component 2: Supporting Fi GM-PPPPE-148454-CS-INDV / scal Management of State-O Individual Consult Recruitment of Monitoring an IDA / V2740 Post Open 25,000.00 1,752.15 Signed 2019-12-06 2019-12-16 2020-01-24 2020-02-09 2020-02-14 2020-03-03 2020-03-20 2020-02-25 2020-09-16 wned Enterprises (“SOEs”) a ant Selection d Evaluation Specialist nd Restructuring Plans of Tel ecom SOEs Page 3 GM-PPPPE-150591-CS-CDS / Component 2: Supporting Fi Special Purpose Audit on 6 re scal Management of State-O IDA / V2740 Post Direct Selection Direct 850,000.00 850,000.00 Completed 2019-12-20 2019-12-17 2019-12-30 2019-12-24 2020-03-04 2019-12-19 2020-08-31 2021-01-20 maining State -Owned Enterp wned Enterprises (“SOEs”) a rises nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-158957-CS-INDV / Component 3: Project Imple PROJECT MANAGER OF THE G Individual Consult IDA / V2740 mentation Support and Refo Post Open 25,000.00 0.00 Canceled 2020-02-17 2020-02-24 2020-04-06 2020-04-27 2020-06-01 2020-11-28 AMBIA FISCAL MANAGEMENT ant Selection rm Coordination DEVELOPMENT PROJECT GM-PPPPE-158965-CS-INDV / Component 3: Project Imple LEGAL AND GRM SPECIALIST Individual Consult IDA / V2740 mentation Support and Refo Post Open 25,000.00 1,773.27 Signed 2020-02-17 2020-02-24 2020-04-06 2020-09-08 2020-04-27 2020-09-08 2020-06-01 2020-09-15 2020-11-28 OF THE GAMBIA FISCAL MAN ant Selection rm Coordination AGEMENT DEVELOPMENT PR OJECT GM-PPPPE-158967-CS-INDV / Component 3: Project Imple CORPORATE GOVERNANCE S Individual Consult IDA / V2740 mentation Support and Refo Post Open 25,000.00 1,754.66 Signed 2020-02-17 2020-02-24 2020-04-06 2020-07-15 2020-04-27 2020-07-15 2020-06-01 2020-07-21 2020-11-28 PECIALIST OF THE GAMBIA FI ant Selection rm Coordination SCAL MANAGEMENT DEVELO PMENT PROJECT GM-PPPPE-159536-CS-INDV / Component 1: Strengthening Individual Consult Elaborate a e-GP Readiness A IDA / V2740 Revenue Collection and Publ Post Limited 100,000.00 0.00 Canceled 2020-02-28 2020-03-03 2020-03-04 2020-04-16 2020-03-25 2020-04-29 2020-10-26 ant Selection ssessment, an e-GP strategy ic Procurement Processes and Road Map GM-PPPPE-180613-CS-INDV / Component 1: Strengthening Individual Consult Tax Expenditure Policy Revie IDA / V2740 Revenue Collection and Publ Post Open 100,000.00 154,300.00 Signed 2020-06-22 2020-06-29 2020-08-10 2020-10-27 2020-08-31 2021-03-04 2020-10-05 2021-03-16 2021-04-03 ant Selection w ic Procurement Processes GM-PPPPE-197242-CS-INDV / Component 1: Strengthening CONSULTANT E-PROCUREME Individual Consult IDA / D6190 Revenue Collection and Publ Post Limited 100,000.00 15,000.00 Signed 2020-09-30 2020-10-15 2020-10-05 2020-10-28 2020-10-26 2021-04-12 2020-11-30 2021-04-20 2021-05-29 NT READINESS ASSESSMENT ant Selection ic Procurement Processes AND E-GP STRATEGY GM-PPPPE-202559-CS-INDV / Component 3: Project Imple Project Manager for the Gam Individual Consult Under Implement IDA / D6190 mentation Support and Refo Post Open 25,000.00 0.00 2020-11-02 2020-11-03 2020-12-21 2021-02-26 2021-01-11 2021-03-30 2021-02-15 2021-08-14 bia Fiscal Management Devel ant Selection ation rm Coordination opment Project Relaunch GM-PPPPE-204418-CS-INDV / Component 3: Project Imple Procurement Officer for Impl Individual Consult Under Implement IDA / D6190 mentation Support and Refo Post Open 25,000.00 0.00 2020-11-11 2020-11-20 2020-12-30 2021-03-17 2021-01-20 2021-02-24 2021-08-23 ementing Agency of the Gam ant Selection ation rm Coordination bia Fiscal Management Devel opment Project GM-PPPPE-211480-CS-INDV / Component 1: Strengthening Local Consultant to support e Individual Consult IDA / V2740 Revenue Collection and Publ Post Open 6,000.00 7,317.08 Completed 2021-01-10 2021-03-29 2021-02-28 2021-06-01 2021-03-21 2021-06-01 2021-04-25 2021-05-06 2021-10-22 2021-07-14 -government procurement re ant Selection ic Procurement Processes adiness assessment GM-PPPPE-225543-CS-CDS / Component 2: Supporting Fi Technical Assistance AFROSA scal Management of State-O I-E support to the National Au IDA / V2740 wned Enterprises (“SOEs”) a Prior Direct Selection Direct 421,250.00 386,324.00 Signed 2021-03-22 2021-03-24 2021-04-01 2021-04-29 2021-06-05 2021-12-13 2021-12-02 dit Office, The Gambia for Pe nd Restructuring Plans of Tel rformance Audit of State Ow ecom SOEs ned Enterprises and Establis hment of Quality Assurance Unit Component 2: Supporting Fi GM-PPPPE-240126-CS-CDS / scal Management of State-O QoQ Upgrade of the Quality o IDA / D6190 Post Direct Selection Direct 200,000.00 172,500.00 Signed 2021-06-28 2021-07-07 2021-07-08 2021-09-02 2021-09-11 2021-11-30 2022-03-10 wned Enterprises (“SOEs”) a f Service Monitoring Network nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-277690-CS-INDV / Component 2: Supporting Fi Recruitment of a Consultant scal Management of State-O Individual Consult Under Implement IDA / D6190 Post Open 100,000.00 0.00 2022-02-09 2022-02-08 2022-03-30 2022-04-20 2022-05-25 2023-05-25 as Resident Senior Adviser to wned Enterprises (“SOEs”) a ant Selection ation the Directorate of State-own nd Restructuring Plans of Tel ed Enterprises ecom SOEs GM-PPPPE-279367-CS-INDV / Development of Compliance Component 1: Strengthening Individual Consult Under Implement Risk Management Framewor IDA / D6190 Revenue Collection and Publ Post Open 170,000.00 0.00 2022-02-17 2022-02-17 2022-04-07 2022-06-02 2022-04-28 2022-06-02 2022-11-29 ant Selection ation k and Policy, Manual and Stra ic Procurement Processes tegy for the Domestic Taxes Department GM-PPPPE-286105-CS-INDV / Recruitment of Individual Co Component 2: Supporting Fi nsultant to provide Technical scal Management of State-O Individual Consult Under Implement Assistance for the Establishm IDA / D6190 wned Enterprises (“SOEs”) a Post Open 80,000.00 0.00 2022-03-28 2022-03-23 2022-05-16 2022-05-16 2022-06-06 2022-07-11 2023-01-07 ant Selection ation ent of a Quality Assurance U nd Restructuring Plans of Tel nit and Review – Update the ecom SOEs Regulatory Framework of the Directorate of Internal Audit GM-PPPPE-295856-CS-INDV / Component 1: Strengthening Individual Consult Under Implement Design and Development of IDA / D6190 Revenue Collection and Publ Post Open 60,000.00 0.00 2022-05-19 2022-05-19 2022-06-04 2022-08-03 2022-06-11 2022-10-17 2022-06-25 2022-10-23 ant Selection ation GRA Website ic Procurement Processes GM-PPPPE-297960-CS-INDV / Component 1: Strengthening TECHNICAL ASSISTANCE FOR Individual Consult Under Implement IDA / D6190 Revenue Collection and Publ Post Open 200,000.00 0.00 2022-06-12 2022-06-30 2022-07-31 2022-09-01 2022-08-21 2022-11-17 2022-09-25 2023-03-24 THE OPERATIONALIZATION O ant Selection ation ic Procurement Processes F THE TAX POLICY UNIT GM-PPPPE-326587-CS-INDV / Component 1: Strengthening Individual Consult Under Implement Microsoft Excel Training for t IDA / D6190 Revenue Collection and Publ Post Open - National 30,000.00 0.00 2022-11-18 2023-01-18 2022-12-14 2022-12-28 2023-02-01 2023-07-31 ant Selection ation he Gambia Revenue Authorit ic Procurement Processes y Personnel GM-PPPPE-338182-CS-INDV / Component 3: Project Imple Individual Consult Open - Internationa Under Implement Consultancy to Support Socia IDA / D6190 mentation Support and Refo Post 30,000.00 0.00 2023-01-30 2023-02-01 2023-03-20 2023-03-01 2023-04-10 2023-06-19 2023-05-15 2023-11-11 ant Selection l ation l and Environmental Risk Ma rm Coordination nagement GM-PPPPE-340201-CS-INDV / CONSULTANT – Development Component 1: Strengthening Individual Consult Open - Internationa Under Implement of an E-Procurement Strateg IDA / D6190 Revenue Collection and Publ Prior 100,000.00 0.00 2023-02-10 2023-03-09 2023-03-31 2023-04-21 2023-05-26 2023-11-22 ant Selection l ation y, Roadmap and E-Procurem ic Procurement Processes ent System Technical Requir ements Component 2: Supporting Fi GM-PPPPE-346049-CS-INDV / scal Management of State-O Individual Consult Open - Internationa Under Implement SPECTRUM MANAGEMNT CO IDA / D6190 Post 150,000.00 0.00 2023-03-06 2023-03-06 2023-04-24 2023-05-15 2023-06-19 2023-12-16 wned Enterprises (“SOEs”) a ant Selection l ation NSULTANT nd Restructuring Plans of Tel ecom SOEs GM-PPPPE-360301-CS-INDV / Component 2: Supporting Fi Development of a Dividend P scal Management of State-O Individual Consult Open - Internationa Under Implement olicy for the IDA / D6190 wned Enterprises (“SOEs”) a Post 50,000.00 0.00 2023-05-15 2023-05-30 2023-07-03 2023-07-24 2023-08-28 2023-11-26 ant Selection l ation State-Owned Enterprises (SO nd Restructuring Plans of Tel E) of the Gambia ecom SOEs Page 4 PROCUREMENT PLAN Project information: NIGERIA AGILE PROJECT P 170664 Project Implementation agency: FEDERAL MINISTRY OF EDUCATION Date of the Procurement Plan: 2021-10-25 Period covered by this Procurement Plan: 2021-2023] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Bureau of Public Procurement Act (PPA 2007), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations.. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods, Services and Works Goods: is not applicable. Works: is not applicable. Other Relevant Procurement Information. Procedures for CDD components: PROCUREMENT Nigeria : Adolescent Girls Initiative for Learning and Empowerment PLAN General Information Country: Nigeria 2022-04-05 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P170664 GPN Date: Project Name: Adolescent Girls Initiative for Learning and Empowerment Loan / Credit No: IDA / 67380 Plateau State Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-PLATEAU STATE -310006 -CW-RFB / Procurement of Co Request for Bids - ntractors for Construction of J Creating Safe and Accessibl Single Stage - One E Works (without pr 11,508,932.3 Under Revie 2024-04-0 IDA / 67380 Prior Request for Bids Open - National 0.00 2022-09-13 2022-10-03 2022-09-20 2022-12-22 2022-11-01 2022-12-28 2022-12-01 2023-01-05 unior and Senior Secondary S e Learning Spaces nvelope equalification) SP 8 w 9 chools Across Senitorial Distri D cts of Plateau State –Lots 1- 5 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-PLATEAU STATE -286185 -GO-RFQ / Procurement of 2N Project management and sy Request for Quota Single Stage - One E Under Imple IDA / 67380 Post Limited 200,000.00 0.00 2022-05-14 2022-08-17 2022-07-09 2023-01-05 o. Project operational vehicle stem strengthening tions nvelope mentation (s) 1 Hilux Vehicle and 18 se ater Bus NG-PLATEAU STATE -297092 Project management and sy Request for Quota Single Stage - One E -GO-RFQ / Procurement of 1N IDA / 67380 Post Limited 45,000.00 37,601.28 Signed 2022-06-25 2022-06-15 2022-08-20 2022-07-05 2023-02-16 stem strengthening tions nvelope o 30Kva power generator for SPIU Office NG-PLATEAU STATE -297101 Project management and sy Request for Quota Single Stage - One E -GO-RFQ / Procurement of Off IDA / 67380 Post Limited 25,000.00 24,440.07 Signed 2022-06-20 2022-06-20 2022-08-15 2022-07-16 2023-02-11 stem strengthening tions nvelope ice Stationaries and other co nsumables NG-PLATEAU STATE -297102 -GO-RFQ / Procurement of 15 Project management and sy Request for Quota Single Stage - One E No Laptops, 5 No Desktops, 5 IDA / 67380 Post Limited 75,000.00 47,985.04 Signed 2022-07-09 2022-06-17 2022-09-03 2022-07-05 2023-03-02 stem strengthening tions nvelope No Printers, 4 No Scanners, 5 No Photocopier for SPIU Key staff and Office. NG-PLATEAU STATE -297105 Project management and sy Request for Quota Single Stage - One E -GO-RFQ / Procurement of Off IDA / 67380 Post Limited 37,000.00 34,706.40 Signed 2022-07-19 2022-06-14 2022-09-13 2022-07-02 2023-03-12 stem strengthening tions nvelope ice Furnitures for SPIU office. NG-PLATEAU STATE -302847 Project management and sy Request for Quota Single Stage - One E IDA / 67380 Post Limited 45,650.00 43,226.81 Signed 2022-07-23 2022-07-25 2022-09-17 2022-08-20 2023-03-16 -GO-RFQ / Setting Up of Acco stem strengthening tions nvelope unt Unit NG-PLATEAU STATE -310179 -GO-RFQ / Procurement of ne cessary equipment and conn Project management and sy Request for Quota Single Stage - One E Under Imple IDA / 67380 Post Limited 100,000.00 0.00 2022-09-24 2022-09-19 2022-11-19 2023-05-18 ectivity, as well as establish stem strengthening tions nvelope mentation ment/ strengthening of EMIS units at 3 zonal offices, 17 Ar ea Offices, SUBEB and MoE. NG-PLATEAU STATE -310213 -GO-RFQ / Supply and Installa Project management and sy Request for Quota Single Stage - One E Pending Impl IDA / 67380 Post Limited 50,000.00 0.00 2022-09-19 2022-11-14 2023-05-13 tion of Video Conference Equ stem strengthening tions nvelope ementation ipment for SPIU office NG-PLATEAU STATE -324635 -GO-RFB / Procurement of La ptops & Desktops computers Fostering an enabling enviro Single Stage - One E Under Imple IDA / 67380 Post Request for Bids Open - National 1,900,000.00 0.00 2022-11-04 2022-11-11 2022-11-09 2022-11-11 2022-12-21 2023-01-20 2023-02-24 2023-08-23 and accessories for Digital Lit nment for girls nvelope mentation eracy Training to 80No. Senio r Secondary Schools (20 Lapt ops & 1 Desktops per School) . NG-PLATEAU STATE -324665 -GO-RFB / Procurement and I Fostering an enabling enviro Single Stage - One E Under Imple nstallation of Solar Power for IDA / 67380 Post Request for Bids Open - National 380,000.00 0.00 2022-11-08 2022-11-11 2022-11-13 2022-11-11 2022-12-25 2023-01-24 2023-02-28 2023-08-27 nment for girls nvelope mentation Digital Literacy Training to 8 0No. Senior Secondary Schoo ls. NG-PLATEAU STATE -357378 -GO-RFQ / Procurement of Off ice Equipment's (2 scanners, Project management and sy Request for Quota Single Stage - One E Pending Impl IDA / 67380 Post Limited 45,000.00 0.00 2023-06-04 2023-07-30 2024-01-26 internet router, file shelve, c stem strengthening tions nvelope ementation onstruction of bid collection boxes/locks) to aid the Procu rement Unit. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-PLATEAU STATE -286180 -NC-RFQ / Production of SBM C, SIG, SIP manuals complain t/suggestion boxes and griev Creating Safe and Accessibl Request for Quota Single Stage - One E IDA / 67380 Post Limited 29,580.00 71,275.65 Signed 2022-05-02 2022-05-02 2022-06-27 2022-06-15 2022-12-24 ances registers for 333 JSS & e Learning Spaces tions nvelope SS, plus 30 copies for MOE a nd SUBEB. (boxes made by lo cal carpenters and two manu als per school) NG-PLATEAU STATE -302888 Project management and sy Request for Quota Single Stage - One E -NC-RFQ / Provision of SPIU o IDA / 67380 Post Limited 5,000.00 4,972.35 Signed 2022-07-23 2022-07-25 2022-09-17 2022-08-24 2023-03-16 stem strengthening tions nvelope ffice with Internet connectivit y Page 1 NG-PLATEAU STATE -310186 -NC-RFQ / Provision of dedica Project management and sy Request for Quota Single Stage - One E Under Imple IDA / 67380 Post Limited 187,500.00 0.00 2022-09-24 2022-10-06 2022-11-19 2023-05-18 ted GRM toll free lines/phone stem strengthening tions nvelope mentation s to the GRCs/GRM NG-PLATEAU STATE -315704 Project management and sy Request for Quota Single Stage - One E Pending Impl -NC-RFQ / Production of GRM IDA / 67380 Post Limited 80,000.00 0.00 2022-10-04 2022-11-29 2023-05-28 stem strengthening tions nvelope ementation Manuals, Complain Boxes an d Registers. NG-PLATEAU STATE -324666 -NC-RFB / Procurement and I Fostering an enabling enviro Single Stage - One E Under Imple nstallation of Internet Conne IDA / 67380 Post Request for Bids Open - National 300,000.00 0.00 2022-11-10 2022-11-11 2022-11-15 2022-11-11 2022-12-27 2023-01-26 2023-03-02 2023-08-29 nment for girls nvelope mentation ctivity for Digital Literacy Tra ining to 80No. Senior Second ary Schools CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-PLATEAU STATE -286186 -CS-CQS / Engagement of an implementing partner to prov Fostering an enabling enviro Consultant Qualifi ide comprehensive technical IDA / 67380 Post Open - National 25,000.00 0.00 Canceled 2022-05-18 2022-06-11 2022-06-08 2022-07-07 2022-07-22 2022-08-21 2022-09-25 2023-03-24 nment for girls cation Selection support, Development of saf e space/life skills curriculum, IEC materials, M&E tools, faci litation of safe space session s. NG-PLATEAU STATE -286188 Project management and sy Consultant Qualifi Under Implement -CS-CQS / Engagement of Co IDA / 67380 Post Open - National 37,500.00 0.00 2022-04-28 2022-06-03 2022-05-19 2022-07-07 2022-07-02 2022-08-10 2022-08-01 2022-09-05 2023-03-04 stem strengthening cation Selection ation nsulting firm for Project Moni toring. NG-PLATEAU STATE -286175 -CS-CDS / Engagement of Co nsultant to Support and Train School Based Management C Creating Safe and Accessibl Consultant Qualifi Under Implement IDA / 67380 Post Limited 304,500.00 0.00 2022-04-27 2022-05-04 2022-05-11 2022-06-10 2022-07-15 2023-01-11 ommittee (SBMC) on Utilizati e Learning Spaces cation Selection ation on and Managing AGILE Fund ed School Improvement Gran t (SIG) to 609 SBMCs - 300 S BMCs in Phase I and 309 in P hase II each. NG-PLATEAU STATE -302828 -CS-CQS / Engagement of an implementing partner to prov Creating Safe and Accessibl Consultant Qualifi ide comprehensive technical IDA / 67380 Post Limited 50,000.00 0.00 Canceled 2022-07-05 2022-07-19 2022-08-18 2022-09-22 2023-03-21 e Learning Spaces cation Selection support, Development of saf e space/life skills curriculum, IEC materials, M&E tools, faci litation of safe space session s. NG-PLATEAU STATE -287083 -CS-CQS / Engagement of MI S consulting firm for identific Fostering an enabling enviro Consultant Qualifi ation, enrollment, registratio IDA / 67380 Post Limited 75,000.00 0.00 Canceled 2022-04-18 2022-06-15 2022-05-02 2022-06-01 2022-07-06 2023-01-02 nment for girls cation Selection n and development of databa se management system for Girls Scholarship Programme (GSP) beneficiaries for disbur sement. NG-PLATEAU STATE -304881 -CS-CQS / Consultancy Servic Creating Safe and Accessibl Consultant Qualifi Under Implement e for the Engagement of Con IDA / 67380 Post Limited 23,809.50 0.00 2022-07-27 2022-08-05 2022-08-10 2022-08-12 2022-09-09 2022-09-07 2022-10-14 2023-04-12 e Learning Spaces cation Selection ation sulting Firm to Conduct Audi ence Research that Hinders Girl Child Education. NG-PLATEAU STATE -304888 -CS-CQS / Engagement of Co nsulting Firm to Develop an I Creating Safe and Accessibl Consultant Qualifi Under Implement IDA / 67380 Post Limited 95,238.10 0.00 2022-08-08 2022-08-29 2022-08-22 2022-09-21 2022-10-26 2023-04-24 ntegrated Marketing Commu e Learning Spaces cation Selection ation nications Campaign and to pr oduce Creative Media Conten t for Plateau State. NG-PLATEAU STATE -304912 -CS-CQS / Engagement of Co Fostering an enabling enviro Consultant Qualifi Under Implement nsulting Firm to Design and C IDA / 67380 Post Limited 150,000.00 0.00 2022-07-27 2022-08-04 2022-08-10 2022-08-08 2022-09-09 2022-09-05 2022-10-14 2023-04-12 nment for girls cation Selection ation onduct a Training Program o n Digital Skills for secondary schools. NG-PLATEAU STATE -309995 -CS-QCBS / Engagement of C onsultancy Firm for Verificati Creating Safe and Accessibl Quality And Cost- Under Implement on of Contractor’s Technical I IDA / 67380 Post Open - National 600,000.00 0.00 2022-09-13 2022-08-24 2022-10-04 2022-09-08 2022-11-17 2022-11-22 2022-12-15 2022-12-21 2023-01-14 2022-12-29 2023-02-18 2023-03-25 2024-06-27 e Learning Spaces Based Selection ation nput and Construction Super vision of Selected Schools un der the AGILE Project in Plate au State NG-PLATEAU STATE -310175 Project management and sy Consultant Qualifi Pending Impleme -CS-CQS / Development and IDA / 67380 Post Limited 45,000.00 0.00 2022-09-15 2022-09-29 2022-10-29 2022-12-03 2023-06-01 stem strengthening cation Selection ntation Hosting of Project Website fo r Plateau State. NG-PLATEAU STATE -320650 -CS-CQS / Engagement of Co Creating Safe and Accessibl Consultant Qualifi Under Implement IDA / 67380 Post Limited 150,000.00 0.00 2022-10-20 2022-10-20 2022-11-03 2022-10-24 2022-12-03 2023-01-07 2023-07-06 nsultant for Security Risk Ass e Learning Spaces cation Selection ation essment and Security Manag ement Plan NG-PLATEAU STATE -320652 -CS-CQS / Engagement of Co nsultant for Development of Creating Safe and Accessibl Consultant Qualifi Under Implement IDA / 67380 Post Limited 150,000.00 0.00 2022-10-20 2022-10-20 2022-11-03 2022-12-03 2023-01-07 2023-07-06 Site Specific Environmental a e Learning Spaces cation Selection ation nd Social Management Plan ( ESMP) for Rehabilitation of Sc hools NG-PLATEAU STATE -323390 -CS-CQS / Engagement of a C Creating Safe and Accessibl Consultant Qualifi Under Implement onsultant to develop Environ IDA / 67380 Post Limited 150,000.00 0.00 2022-10-25 2022-11-03 2022-11-08 2022-12-08 2023-01-12 2023-07-11 e Learning Spaces cation Selection ation mental and Social Manageme nt Plan (ESMP) for Constructi on of New Schools. NG-PLATEAU STATE -329291 -CS-CQS / Engagement of Co Project management and sy Consultant Qualifi nsultant to carry out Root Ca IDA / 67380 Post Limited 150,000.00 0.00 Canceled 2022-12-13 2023-01-03 2022-12-27 2023-01-26 2023-03-02 2023-08-29 stem strengthening cation Selection use Analyses for Kidnap Case s Under Plateau AGILE Projec t. Page 2 NG-PLATEAU STATE -339671 -CS-CQS / Engagement of a D ata Science Survey Firm to V Fostering an enabling enviro Consultant Qualifi Under Implement alidate all Targeted and Enrol IDA / 67380 Post Limited 170,000.00 0.00 2023-04-11 2023-05-16 2023-04-25 2023-05-25 2023-06-29 2023-12-26 nment for girls cation Selection ation led AGILE Cohorts and Issuan ce of Unique Identification Nu mbers Tied Quick Response ( QR) in Plateau State. NG-PLATEAU STATE -286167 -CS-CQS / Appointment of co Creating Safe and Accessibl Consultant Qualifi nsultant for the preparation o IDA / 67380 Post Open - National 36,250.00 0.00 Canceled 2022-04-04 2022-04-25 2022-06-08 2022-07-08 2022-08-12 2023-02-08 e Learning Spaces cation Selection f an ESMP and to conduct trai ning to the CPMCs members i n ESMP related issues NG-PLATEAU STATE -297162 Project management and sy Consultant Qualifi -CS-CQS / Capacity Assessme IDA / 67380 Post Limited 170,000.00 0.00 Canceled 2022-07-20 2022-08-03 2022-09-02 2022-10-07 2023-04-05 stem strengthening cation Selection nt on Teachers Digital Literac y level NG-PLATEAU STATE -286162 -CS-CQS / Engagement of co Creating Safe and Accessibl Consultant Qualifi nsultant to train the first pha IDA / 67380 Post Limited 29,166.90 0.00 Canceled 2022-04-19 2022-05-03 2022-06-02 2022-07-07 2023-01-03 e Learning Spaces cation Selection se 13 schools CPMC member s on Bank Norms for FM and Procurement. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-PLATEAU STATE -297164 Project management and sy Individual Consult Under Implement -CS-INDV / Engagement of Pr IDA / 67380 Post Direct 50,000.00 0.00 2022-06-17 2022-06-09 2022-06-27 2022-06-17 2022-07-18 2022-08-22 2023-02-18 stem strengthening ant Selection ation ocurement Specialist NG-PLATEAU STATE -302826 -CS-INDV / Engagement of MI S consultant (T.A) to support identification, enrollment, re Fostering an enabling enviro Individual Consult IDA / 67380 Post Limited 75,000.00 76,548.26 Signed 2022-07-06 2022-07-16 2022-07-11 2022-07-18 2022-08-01 2022-08-15 2022-09-05 2022-08-16 2023-03-04 gistration and development o nment for girls ant Selection f database management sys tem for Girls Scholarship Pro gramme (GSP) beneficiaries f or disbursement. NG-PLATEAU STATE -304891 -CS-INDV / Engagement of an Fostering an enabling enviro Individual Consult IDA / 67380 Post Limited 75,000.00 0.00 Signed 2022-07-20 2022-08-04 2022-07-25 2022-08-08 2022-08-15 2022-10-06 2022-09-19 2023-03-18 Environment and Social (E&S nment for girls ant Selection ) Technical Assistant (TA) NG-PLATEAU STATE -304903 -CS-INDV / Engagement of a Project management and sy Individual Consult Under Implement IDA / 67380 Post Limited 50,000.00 0.00 2022-07-20 2022-08-04 2022-07-25 2022-08-08 2022-08-15 2022-10-06 2022-09-19 2023-03-18 Gender Based Violence (GBV stem strengthening ant Selection ation ) Technical Assistant (TA) NG-PLATEAU STATE -304937 -CS-INDV / Engagement of Te Project management and sy Individual Consult Pending Impleme IDA / 67380 Post Limited 50,000.00 0.00 2022-08-02 2022-08-07 2022-08-28 2022-10-02 2023-03-31 chnical Assistant (TA) for Gra stem strengthening ant Selection ntation diences Redress Mechanism (GRM) NG-PLATEAU STATE -331444 -CS-CDS / Engagement of an Implementing Partner to Prov ide Technical Support, Devel Fostering an enabling enviro Under Implement IDA / 67380 Post Direct Selection Direct - National 360,000.00 0.00 2022-12-13 2023-01-03 2022-12-23 2023-02-26 2023-08-25 opment of Safe Space/Life Sk nment for girls ation ills Curriculum, IEC Materials, M&E Tools and Facilitation of Safe Space Sessions in Secon dary Schools in Plateau State . NG-PLATEAU STATE -334493 -CS-INDV / Engagement of a Project management and sy Individual Consult Under Implement IDA / 67380 Post Limited 150,000.00 0.00 2023-01-09 2023-05-05 2023-01-14 2023-02-04 2023-03-11 2023-09-07 Technical Assistant (T.A) for stem strengthening ant Selection ation Project System Strengthen of AGILE Plateau State. NG-PLATEAU STATE -356054 -CS-INDV / Engagement of Te Creating Safe and Accessibl Individual Consult Under Implement chnical Assistant (T.A) for Co IDA / 67380 Post Limited 150,000.00 0.00 2023-04-11 2023-04-18 2023-04-16 2023-04-20 2023-05-07 2023-05-15 2023-06-11 2023-12-08 e Learning Spaces ant Selection ation mponent 1.2(Improving Existi ng Infrastructure in Secondar y School) NG-PLATEAU STATE -359707 Project management and sy Under Implement -CS-CDS / Engagement of an IDA / 67380 Post Direct Selection Direct - National 20,000.00 0.00 2023-05-03 2023-05-05 2023-05-13 2023-07-17 2024-01-13 stem strengthening ation External Audit Firm for AGILE Plateau State. NG-PLATEAU STATE -336737 -CS-CQS / Engagement of Co Project management and sy nsultant to carry out Root Ca IDA / 67380 Post Direct Selection Direct - National 150,000.00 0.00 Canceled 2023-01-18 2023-02-15 2023-01-28 2023-04-03 2023-09-30 stem strengthening use Analyses for Kidnap Case s Under Plateau AGILE Projec t. Page 3 PROCUREMENT PLAN (Textual Part) Project information: [country] [Project name] [P-number] Project Implementation agency: [insert legal name] Date of the Procurement Plan: [insert date] Period covered by this Procurement Plan: [insert from – to period] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Brazil : SABESP - IMPROVING WATER SERVICE ACCESS AND SECURITY IN THE METROPOLITAN REGION OF SÃO PAULO PROJECT PLAN General Information Country: Brazil 2018-11-13 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P165695 GPN Date: Project Name: SABESP - IMPROVING WATER SERVICE ACCESS AND SECURITY IN THE METROPOLITAN REGION OF SÃO PAULO PROJECT Loan / Credit No: IBRD / 89160, / Company of Water and Sewage of the State of São Paulo Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-SABESP-86308-CW-RFB / SES Itapecerica da Serra Reduce pollution loads to sc Implantação de Redes coleto Single Stage - One E 8,995,802.8 2021-05-1 IBRD / 89160 arce water resources in the Post Request for Bids Open - National Signed 2020-06-30 2019-05-10 2020-07-30 2021-03-24 2020-09-10 2021-05-02 2020-10-10 2021-06-28 2020-11-14 2021-09-11 ras de Esgoto, Ligações de E nvelope 5 3 Guarapiranga Water Basin sgoto, E.E.E, Linhas de recalq ue e Coletores troncos Secun dários BR-SABESP-86329-CW-RFB / Expand access to water serv Regularização de ligações e ices, reduce water losses, an Single Stage - One E 2021-04-1 m áreas de alta vulnerabilida / Prior Request for Bids Open - National 0.00 Canceled 2020-06-30 2020-07-05 2020-08-16 2020-09-15 2020-10-20 d increase system resilience nvelope 8 de social - UGRs Santana, Fr in the MRSP eguesia, Extremo Norte e Piri tuba BR-SABESP-86323-CW-RFB / Expand access to water serv Regularização de ligações e ices, reduce water losses, an Single Stage - One E 2020-10-0 m áreas de alta vulnerabilida / Post Request for Bids Open - National 0.00 Canceled 2019-12-20 2019-12-25 2020-02-05 2020-03-06 2020-04-10 d increase system resilience nvelope 7 de social - UGRs Moóca, Jardi in the MRSP ns, Alto Tietê, Santana e Freg uesia BR-SABESP-86317-CW-RFB / Regularização de ligações e Expand access to water serv m áreas de alta vulnerabilida ices, reduce water losses, an Single Stage - One E 2020-04-1 / Post Request for Bids Open - National 0.00 Canceled 2019-06-30 2019-07-05 2019-08-16 2019-09-15 2019-10-20 de social - UGRs Interlagos, G d increase system resilience nvelope 7 uarapiranga, Santo Amaro, Bi in the MRSP llings, Butantã, Cotia, Osasco e Tietê BR-SABESP-86318-CW-RFB / Reduce pollution loads to sc Implantação de Coletor Tronc Single Stage - One E 3,483,739.6 2021-06-1 IBRD / 89160 arce water resources in the Post Request for Bids Open - National Signed 2020-08-30 2021-05-28 2020-09-04 2021-08-20 2020-10-16 2021-09-27 2020-11-15 2021-11-03 2020-12-20 2021-12-22 o (Guavirituba) e Linha de Re nvelope 1 8 Guarapiranga Water Basin calque (Talamanca) BR-SABESP-154205-CW-RFP Expand access to water serv Single Stage - One E 2021-05-1 / Manutenção das barragens: IBRD / 89160 ices, reduce water losses, an Post Request for Bids Open - National 0.00 Canceled 2020-07-31 2021-03-24 2020-08-05 2021-03-24 2020-09-16 2021-05-10 2020-10-16 2020-11-20 nvelope 9 Jaguari, Jacareí e Cachoeira d increase system resilience in the MRSP BR-SABESP-165391-CW-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E 2022-08-1 IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2020-06-15 2020-06-20 2020-06-23 2020-07-23 2020-08-27 m áreas de alta vulnerabilida d increase system resilience nvelope 7 de social - Extremo Norte in the MRSP BR-SABESP-182851-CW-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E 2022-10-0 IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2020-07-31 2020-08-05 2020-08-08 2020-09-07 2020-10-12 m áreas de alta vulnerabilida d increase system resilience nvelope 2 de social - Santo André in the MRSP BR-SABESP-182852-CW-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E 2022-10-0 IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2020-07-31 2020-08-05 2020-08-08 2020-09-07 2020-10-12 m áreas de alta vulnerabilida d increase system resilience nvelope 2 de social - São Miguel in the MRSP BR-SABESP-182853-CW-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E 2022-10-0 IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2020-07-31 2020-08-05 2020-08-08 2020-09-07 2020-10-12 m áreas de alta vulnerabilida d increase system resilience nvelope 2 de social - Pantanal - Várzea in the MRSP do Tiête BR-SABESP-175912-CW-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E 2022-09-0 IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2020-06-30 2020-07-05 2020-07-08 2020-08-07 2020-09-11 m áreas de alta vulnerabilida d increase system resilience nvelope 1 de social - Itaquera in the MRSP BR-SABESP-165395-CW-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E 2022-08-1 IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2020-06-15 2020-06-20 2020-06-23 2020-07-23 2020-08-27 m áreas de alta vulnerabilida d increase system resilience nvelope 7 de social - Osasco in the MRSP BR-SABESP-165396-CW-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E 2022-08-1 IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2020-06-15 2020-06-20 2020-06-23 2020-07-23 2020-08-27 m áreas de alta vulnerabilida d increase system resilience nvelope 7 de social - Cotia in the MRSP BR-SABESP-165390-CW-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E 2022-08-1 IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2020-06-15 2020-07-08 2020-06-20 2020-08-19 2020-06-23 2020-07-23 2020-08-27 m áreas de alta vulnerabilida d increase system resilience nvelope 7 de social - Guarulhos in the MRSP BR-SABESP-216713-CW-RFB Expand access to water serv / Obras de Substituição de R ices, reduce water losses, an Single Stage - One E 2025-01-0 edes de Água - Setores: Sant IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2021-04-30 2021-05-05 2021-06-16 2021-07-16 2021-08-20 d increase system resilience nvelope 1 ana, Derivação Santana e S in the MRSP anto Amaro - Campo Belo BR-SABESP-216718-CW-RFB / Obras de Substituição de R Expand access to water serv edes de Água - Setores: Jardi ices, reduce water losses, an Single Stage - One E 2025-01-0 ns - Setor Lapa, Jardins - Seto IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2021-04-30 2021-05-05 2021-06-16 2021-07-16 2021-08-20 d increase system resilience nvelope 1 r Vila Romana, Jardins - Setor in the MRSP Lapa, Jardins - Setor Derivaçã o Brooklin e Jardins - Setor Ja rdim América BR-SABESP-216720-CW-RFB Expand access to water serv / Obras de Substituição de R ices, reduce water losses, an Single Stage - One E 2025-01-0 edes de Água - Setores: Buta IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2021-07-31 2021-08-05 2021-09-16 2021-10-16 2021-11-20 d increase system resilience nvelope 3 ntã - Setor Morumbi, Jardins - in the MRSP Setor Vila Romana e São Mig uel - Setor Penha Page 1 BR-SABESP-216722-CW-RFB / Obras de Substituição de R Expand access to water serv edes de Água - Setores: São ices, reduce water losses, an Single Stage - One E 2025-04-1 IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2022-03-13 2022-03-18 2022-04-29 2022-05-29 2022-07-03 Miguel - Setor Der. Vila Matil d increase system resilience nvelope 8 de + Penha, Santana - Setor in the MRSP Tucuruvi e Butantã - Setor M orumbi BR-SABESP-216725-CW-RFB / Obras de Substituição de R edes de Água - Setores: Tiête Expand access to water serv - Setor Barueri Jd. Tupã (Mun. ices, reduce water losses, an Single Stage - One E 2025-04-1 Jandira), Setor Carapicuíba V IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2022-03-13 2022-03-18 2022-04-29 2022-05-29 2022-07-03 d increase system resilience nvelope 8 ila Dirce e Tiête - Setor Carap in the MRSP icuíba Centro + Carapicuíba COHAB / Ipiranga - Setor Deri v Cambuci e Butantã - Setor Vila Sônia + Jaguaré BR-SABESP-216729-CW-RFB / Obras de Substituição de R Expand access to water serv edes de Água - Setores: Perdi ices, reduce water losses, an Single Stage - One E 2025-04-1 IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2022-03-13 2022-03-18 2022-04-29 2022-05-29 2022-07-03 zes, Osasco Vila Iracema I + d increase system resilience nvelope 8 Osasco Quitaúna + Osasco B in the MRSP ela Vista + Osasco Conceição e Artur Alvim BR-SABESP-86310-CW-RFB / Execução de obras para impl antação dos sistemas de rem oção de sólidos e contingênci Reduce pollution loads to sc Single Stage - One E 2021-04-0 a de bombeamento, incluind IBRD / 89160 arce water resources in the Post Request for Bids Open - National 0.00 Canceled 2020-06-15 2019-04-09 2020-06-20 2020-08-01 2020-08-31 2020-10-05 nvelope 3 o montagem e fornecimento Guarapiranga Water Basin de equipamentos e adequaç ão nas instalações elétricas e m seis Estações Elevatórias d e Esgoto National Proc Expand access to water serv BR-SABESP-230942-CW-RFB urement Doc ices, reduce water losses, an Single Stage - One E 1,738,398.2 2022-04-1 / Piloto - Substituição de Red IBRD / 89160 Post Request for Bids Open - National ument - 1 En Signed 2021-06-30 2022-02-18 2021-07-05 2022-03-17 2021-08-16 2022-04-12 2021-09-15 2022-04-29 2021-10-20 2022-07-27 d increase system resilience nvelope 8 8 es - Deriv. Santana velope proce in the MRSP ss (Non Bank -SPD) BR-SABESP-230951-CW-RFB National Proc / Implementação de eficiênci Expand access to water serv urement Doc a nas redes e ramais de distri ices, reduce water losses, an Single Stage - One E ument - 1 En 2022-06-1 IBRD / 89160 Prior Request for Bids Open - National 0.00 Signed 2021-08-31 2022-09-27 2021-09-05 2022-11-29 2021-10-17 2022-12-14 2021-11-16 2023-02-24 2021-12-21 2023-05-10 buição de água, por meio da d increase system resilience nvelope velope proce 9 substituição de infraestrutura in the MRSP ss (Non Bank linear comissionada - Licitaçã -SPD) o 3 - Troca de Redes BR-SABESP-230954-CW-RFB National Proc / Implementação de eficiênci Expand access to water serv urement Doc a nas redes e ramais de distri ices, reduce water losses, an Single Stage - One E ument - 1 En 2022-10-2 IBRD / 89160 Prior Request for Bids Open - National 0.00 Signed 2022-01-02 2022-09-27 2022-01-07 2022-11-29 2022-02-18 2022-12-15 2022-03-20 2023-03-29 2022-04-24 2023-05-15 buição de água, por meio da d increase system resilience nvelope velope proce 1 substituição de infraestrutura in the MRSP ss (Non Bank linear comissionada - Licitaçã -SPD) o 4 - Troca de Redes Reduce pollution loads to sc BR-SABESP-86309-CW-RFP / Request for Propo Open - Internationa Single Stage - Two E 2021-10-0 IBRD / 89160 arce water resources in the Prior 0.00 Canceled 2020-10-30 2020-11-04 2020-12-16 2021-02-28 2021-04-04 Remoção de Carga Poluidora sals l nvelope 1 Guarapiranga Water Basin BR-SABESP-216732-CW-RFB Request for B / Implementação de eficiênci Expand access to water serv ids - Small W a nas redes e ramais de distri ices, reduce water losses, an Single Stage - One E 2024-06-2 IBRD / 89160 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-09-12 2021-09-17 2021-10-29 2021-11-28 2022-01-02 buição de água, por meio da d increase system resilience nvelope 0 nvelope proc substituição de infraestrutura in the MRSP ess) linear comissionada - Plano B - Troca de Redes Request for B BR-SABESP-290423-CW-RFB Expand access to water serv ids - Works ( Single Stage - One E 2023-02-1 / MANUTENÇÃO DAS BARRAG IBRD / 89160 ices, reduce water losses, an Post Request for Bids Open - National without preq 0.00 Canceled 2022-05-02 2022-04-18 2022-05-07 2022-06-18 2022-07-18 2022-08-22 nvelope 8 ENS JAGUARI, JACAREÍ E CAC d increase system resilience ualification) HOEIRA (TR19) in the MRSP SPD BR-SABESP-299720-CW-RFB / SES EMBU das ARTES - 2ª E National Proc tapa - Execução de rede cole urement Doc Reduce pollution loads to sc toras de esgoto no Jardim Vis Single Stage - One E ument - 1 En Pending Imp 2025-03-2 IBRD / 89160 arce water resources in the Post Request for Bids Open - National 0.00 2023-02-24 2023-03-01 2023-04-12 2023-05-12 2023-06-16 ta Alegre e no Jardim Santa R nvelope velope proce lementation 7 Guarapiranga Water Basin ita, de ligações domiciliares ss (Non Bank e de execução de EEE Jardim -SPD) Vista Alegre e EEE Jardim Sa nta Rita, em Embu das Artes. National Proc BR-SABESP-299727-CW-RFB Expand access to water serv urement Doc / Adequação da estação de tr ices, reduce water losses, an Single Stage - One E ument - 1 En Under Imple 2025-06-0 atamento de água eng. Rodo IBRD / 89160 Prior Request for Bids Open - National 0.00 2023-02-28 2023-02-02 2023-03-05 2023-04-16 2023-05-16 2023-06-20 d increase system resilience nvelope velope proce mentation 9 lfo José da Costa e Silva (ETA in the MRSP ss (Non Bank RJCS, antiga ETA ABV). -SPD) Request for P roposal Work BR-SABESP-279566-CW-RFP s and Operati / IMPLANTAÇÃO DE INFRAEST Reduce pollution loads to sc on Service - Request for Propo Open - Internationa Single Stage - Two E 2023-02-0 RUTURA E DO SISTEMA DE R IBRD / 89160 arce water resources in the Prior Design, Build 0.00 Canceled 2022-03-03 2022-03-08 2022-04-19 2022-07-02 2022-08-06 sals l nvelope 2 EMOÇÃO DE NUTRIENTES NO Guarapiranga Water Basin and Operatio RIO EMBU MIRIM | ERN n for Water a nd Wastewat er Treatment Plants SPD (S BR-SABESP-308629-CW-RFB ingle-stage) / SES EMBU das ARTES - 1ª E National Proc tapa - Execução do Coletor T urement Doc Reduce pollution loads to sc ronco Jardim Magali, de rede Single Stage - One E ument - 1 En Under Imple 2025-06-0 IBRD / 89160 arce water resources in the Prior Request for Bids Open - National 0.00 2022-08-26 2022-10-05 2022-08-31 2022-12-22 2022-10-12 2023-02-28 2022-11-11 2023-03-29 2022-12-16 coletoras de Esgoto no Jardi nvelope velope proce mentation 3 Guarapiranga Water Basin m Magali e no Jardim Isis Cris ss (Non Bank tina, de ligações domiciliares -SPD) e de Retrofit da EEE Embu 4, no município de Embu das Ar tes. BR-SABESP-230955-CW-RFB National Proc / Implementação de eficiênci Expand access to water serv urement Doc a nas redes e ramais de distri ices, reduce water losses, an Single Stage - One E ument - 1 En 2024-09-1 IBRD / 89160 Prior Request for Bids Open - National 0.00 Signed 2022-09-15 2022-10-05 2022-10-15 2022-11-29 2022-11-26 2022-12-16 2022-12-26 2023-02-24 2023-02-28 2023-05-19 buição de água, por meio da d increase system resilience nvelope velope proce 0 substituição de infraestrutura in the MRSP ss (Non Bank linear comissionada - Licitaçã -SPD) o 5 - Troca de Redes BR-SABESP-230957-CW-RFB National Proc / Implementação de eficiênci Expand access to water serv urement Doc a nas redes e ramais de distri ices, reduce water losses, an Single Stage - One E ument - 1 En Under Imple 2025-05-0 IBRD / 89160 Prior Request for Bids Open - National 0.00 2022-12-30 2023-02-24 2023-01-29 2023-03-12 2023-04-11 2023-05-16 buição de água, por meio da d increase system resilience nvelope velope proce mentation 5 substituição de infraestrutura in the MRSP ss (Non Bank linear comissionada - Licitaçã -SPD) o 6 - Troca de Redes Page 2 BR-SABESP-86326-CW-RFB / SES EMBU das ARTES - 1ª Et National Proc apa - Execução do Coletor Tr urement Doc Reduce pollution loads to sc onco Jardim Magali, de rede c Single Stage - One E ument - 1 En 2025-06-0 IBRD / 89160 arce water resources in the Post Request for Bids Open - National 0.00 Canceled 2022-08-26 2022-07-29 2022-08-31 2022-10-12 2022-11-11 2022-12-16 oletoras de Esgoto no Jardim nvelope velope proce 3 Guarapiranga Water Basin Magali e no Jardim Isis Cristin ss (Non Bank a, de ligações domiciliares e -SPD) de Retrofit da EEE Embu 4, n o município de Embu das Art es. BR-SABESP-230959-CW-RFB National Proc / Implementação de eficiênci Expand access to water serv urement Doc a nas redes e ramais de distri ices, reduce water losses, an Single Stage - One E ument - 1 En Pending Imp 2026-06-0 IBRD / 89160 Prior Request for Bids Open - National 0.00 2022-11-25 2022-12-25 2023-02-28 2023-04-11 2023-06-20 buição de água, por meio da d increase system resilience nvelope velope proce lementation 5 substituição de infraestrutura in the MRSP ss (Non Bank linear comissionada - Licitaçã -SPD) o 7 - Troca de Redes BR-SABESP-230960-CW-RFB National Proc / Implementação de eficiênci Expand access to water serv urement Doc a nas redes e ramais de distri ices, reduce water losses, an Single Stage - One E ument - 1 En Pending Imp 2026-08-0 IBRD / 89160 Prior Request for Bids Open - National 0.00 2023-05-02 2023-05-07 2023-06-18 2023-07-18 2023-08-22 buição de água, por meio da d increase system resilience nvelope velope proce lementation 6 substituição de infraestrutura in the MRSP ss (Non Bank linear comissionada - Licitaçã -SPD) o 8 - Troca de Redes BR-SABESP-299738-CW-RFB / Execução de obras e monta National Proc gens dos equipamentos para urement Doc Reduce pollution loads to sc Retrofit das Estações Elevató Single Stage - One E ument - 1 En Under Imple 2024-11-1 IBRD / 89160 arce water resources in the Post Request for Bids Open - National 0.00 2023-01-31 2023-04-14 2023-02-05 2023-03-19 2023-04-18 2023-05-23 rias de Esgoto nvelope velope proce mentation 3 Guarapiranga Water Basin Talamanca. Riviera, Jardim S ss (Non Bank olange (Retrofit EEE - Lote 1) -SPD) e Estações Elevatórias de Es goto Iporã e Caulim (Retrofit EEE - Lote 2) BR-SABESP-230955-CW-RFB National Proc CONT LOTE 1 E 3 / Implemen Expand access to water serv urement Doc tacao de eficiencia nas redes ices, reduce water losses, an Single Stage - One E ument - 1 En Under Imple 2023-10-1 e ramais de distribuicao de a IBRD / 89160 Post Request for Bids Open - National 0.00 2022-01-02 2022-10-05 2022-01-07 2022-02-18 2022-03-20 2022-04-24 d increase system resilience nvelope velope proce mentation 6 gua, por meio da substituica in the MRSP ss (Non Bank o de infraestrutura linear co -SPD) missionada - Licitação 5 - Tro ca de Redes - Lote 1 e 3 con tinuacao GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-SABESP-233538-GO-RFB Expand access to water serv Single Stage - One E / AQUISIÇÃO DE TUBOS - SUB IBRD / 89160 ices, reduce water losses, an Prior Request for Bids Open - National 2,832,892.57 Signed 2021-06-30 2021-08-30 2021-07-05 2021-10-22 2021-08-16 2021-10-19 2021-09-15 2021-11-04 2021-10-20 2021-11-30 2022-04-18 nvelope STITUIÇÃO DE REDES d increase system resilience in the MRSP BR-SABESP-233539-GO-RFB Expand access to water serv Single Stage - One E / AQUISIÇÃO DE CONEXÕES - IBRD / 89160 ices, reduce water losses, an Prior Request for Bids Open - National 1,869,411.20 Signed 2021-06-30 2021-08-30 2021-07-05 2021-10-22 2021-08-16 2021-10-21 2021-09-15 2022-01-13 2021-10-20 2022-02-19 2022-04-18 nvelope SUBSTITUIÇÃO DE REDES d increase system resilience in the MRSP BR-SABESP-86314-GO-RFB / Expand access to water serv Open - Internationa Single Stage - One E Tubos para Renovação de Re IBRD / 89160 ices, reduce water losses, an Prior Request for Bids 0.00 Canceled 2020-08-30 2020-09-04 2020-10-16 2020-11-15 2020-12-20 2021-06-18 l nvelope des Secundárias (parte 01) d increase system resilience in the MRSP BR-SABESP-86328-GO-RFB / Technical assistance and Pro Implantação de pilotos de Efi Single Stage - One E / ject management and super Post Request for Bids Open - National 0.00 Canceled 2020-06-01 2020-06-06 2020-07-18 2020-08-17 2020-09-21 2021-03-20 ciência Energética - BFT (Bo nvelope vision mba operando como turbina) BR-SABESP-86325-GO-RFB / Technical assistance and Pro Implantação de pilotos de Efi Single Stage - One E / ject management and super Post Request for Bids Open - National 0.00 Canceled 2020-03-01 2020-03-06 2020-04-17 2020-05-17 2020-06-21 2020-12-18 ciência Energética - Acionam nvelope vision ento de motor à gás encanad o BR-SABESP-244315-GO-RFB / Fornecimento de equipame Reduce pollution loads to sc Single Stage - One E ntos e adequação nas instala IBRD / 89160 arce water resources in the Prior Request for Bids Open - National 0.00 Canceled 2021-09-30 2021-10-05 2021-11-16 2021-12-16 2022-01-20 2022-07-19 nvelope ções elétricas - Sistema Marg Guarapiranga Water Basin em Esquerda: EEEs RIVIERA, TALAMANCA e SOLANGE BR-SABESP-244316-GO-RFB / Execução de obras para im plantação dos sistemas de re moção de sólidos e contingê Reduce pollution loads to sc Single Stage - One E ncia de bombeamento, inclui IBRD / 89160 arce water resources in the Post Request for Bids Open - National 0.00 Canceled 2021-10-31 2021-11-05 2021-12-17 2022-01-16 2022-02-20 2022-08-19 nvelope ndo montagem e fornecimen Guarapiranga Water Basin to de equipamentos e adequ ação nas instalações elétrica s - Sistema Margem Direita: EEEs IPORÃ e CAULIM BR-SABESP-86312-GO-RFB / Technical assistance and Pro Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2020-04-15 2022-06-13 2020-04-20 2020-05-20 2020-06-19 2020-07-24 2021-01-20 Automação - projeto piloto B ject management and super nvelope arueri vision BR-SABESP-299792-GO-RFB Reduce pollution loads to sc / Fornecimento de equipame Single Stage - One E Pending Impl IBRD / 89160 arce water resources in the Post Request for Bids Open - National 0.00 2023-07-12 2023-07-17 2023-08-28 2023-09-27 2023-11-01 2024-06-18 ntos para trituração e remoç nvelope ementation Guarapiranga Water Basin ão de sólidos para o Retrofit das EEEs. BR-SABESP-299795-GO-RFB Reduce pollution loads to sc / Fornecimento e instalação d Single Stage - One E Under Imple IBRD / 89160 arce water resources in the Post Request for Bids Open - National 0.00 2023-07-14 2023-06-13 2023-07-19 2023-08-30 2023-09-29 2023-11-03 2024-03-02 e painéis elétricos e gerador nvelope mentation Guarapiranga Water Basin es para o Retrofit das EEEs. BR-SABESP-362091-GO-RFB Reduce pollution loads to sc Single Stage - One E Pending Impl / Fornecimento de conjunto IBRD / 89160 arce water resources in the Post Request for Bids Open - National 0.00 2023-07-14 2023-07-19 2023-08-30 2023-09-29 2023-11-03 2024-03-02 nvelope ementation motobombas para o Retrofit Guarapiranga Water Basin das EEEs. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-SABESP-191289-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2020-09-30 2021-05-21 2020-10-05 2021-05-26 2020-11-16 2021-06-25 2020-12-16 2021-08-05 2021-01-20 2021-07-19 m áreas de alta vulnerabilida d increase system resilience nvelope de social -São Miguel in the MRSP Page 3 BR-SABESP-191290-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2020-09-30 2020-10-05 2020-10-05 2021-05-26 2020-11-16 2021-06-25 2020-12-16 2021-08-05 2021-01-20 2021-07-19 m áreas de alta vulnerabilida d increase system resilience nvelope de social - Pantanal / Várzea in the MRSP do Tiête BR-SABESP-191291-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 1,132,014.32 Signed 2020-09-30 2021-05-03 2020-10-05 2021-05-03 2020-11-16 2021-05-26 2020-12-16 2021-06-16 2021-01-20 2022-01-11 2021-07-19 m áreas de alta vulnerabilida d increase system resilience nvelope de social - Extremo Norte in the MRSP BR-SABESP-191292-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E m áreas de alta vulnerabilida IBRD / 89160 Post Request for Bids Open - National 2,530,608.92 Signed 2020-09-30 2021-05-11 2020-10-05 2021-05-25 2020-11-16 2021-06-28 2020-12-16 2021-07-26 2021-01-20 2022-01-26 2021-07-19 d increase system resilience nvelope de social - Cotia, Taboão da S in the MRSP erra, Itapevi, Osasco, Barueri BR-SABESP-191293-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 1,115,977.23 Signed 2020-09-30 2021-05-03 2020-10-05 2021-05-03 2020-11-16 2021-06-28 2020-12-16 2021-07-21 2021-01-20 2022-02-01 2021-07-19 m áreas de alta vulnerabilida d increase system resilience nvelope de social - Freguesia do Ó / S in the MRSP antana BR-SABESP-191295-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 1,986,584.39 Signed 2020-09-30 2020-10-05 2020-10-05 2020-11-13 2020-11-16 2020-12-14 2020-12-16 2021-01-06 2021-01-20 2021-04-14 2021-07-19 m áreas de alta vulnerabilida d increase system resilience nvelope de social - Centro UGRs in the MRSP BR-SABESP-191296-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 1,267,799.23 Signed 2020-09-30 2020-09-01 2020-10-05 2020-11-16 2020-10-27 2020-12-16 2020-11-25 2021-01-20 2021-04-21 2021-07-19 m áreas de alta vulnerabilida d increase system resilience nvelope de social - Itaquera in the MRSP BR-SABESP-191297-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 2,446,057.20 Signed 2020-09-30 2020-10-05 2020-10-05 2020-11-12 2020-11-16 2020-12-14 2020-12-16 2021-01-21 2021-01-20 2021-04-18 2021-07-19 m áreas de alta vulnerabilida d increase system resilience nvelope de social - Santo André in the MRSP BR-SABESP-192964-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E IBRD / 89160 Prior Request for Bids Open - National 1,502,916.12 Signed 2020-06-15 2020-11-12 2020-06-20 2020-08-01 2020-10-09 2020-08-31 2020-12-15 2020-10-05 2021-04-14 2021-04-03 m áreas de alta vulnerabilida d increase system resilience nvelope de social - Guarulhos (correta in the MRSP ) BR-SABESP-207023-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 778,240.31 Signed 2021-02-28 2021-05-04 2021-03-05 2021-05-06 2021-04-16 2021-06-02 2021-05-16 2021-06-21 2021-06-20 2021-11-18 2021-12-17 m áreas de alta vulnerabilida d increase system resilience nvelope de social - Interlagos in the MRSP BR-SABESP-230965-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 1,726,266.99 Signed 2021-06-30 2021-11-29 2021-07-05 2021-12-10 2021-08-16 2022-01-13 2021-09-15 2022-04-14 2021-10-20 2022-07-12 2022-04-18 m áreas de alta vulnerabilida d increase system resilience nvelope de social - Guarulhos II in the MRSP BR-SABESP-230964-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 1,226,338.01 Signed 2021-06-30 2021-11-29 2021-07-05 2021-12-10 2021-08-16 2022-01-14 2021-09-15 2022-04-06 2021-10-20 2022-07-22 2022-04-18 m áreas de alta vulnerabilida d increase system resilience nvelope de social - Pirituba III in the MRSP BR-SABESP-249548-NC-DIR / Expand access to water serv EXECUÇÃO DE LEVANTAMEN ices, reduce water losses, an IBRD / 89160 Post Direct Selection Direct 144,315.37 Completed 2021-09-10 2021-09-02 2021-09-15 2021-11-03 2021-10-20 2021-12-31 2022-04-18 2022-07-01 TO GEOFÍSICO NA BARRAGE d increase system resilience M ATIBAINHA (TR13 - Willows in the MRSP tick). BR-SABESP-254285-NC-RFB / EXECUÇÃO DE ENSAIO PIZO Expand access to water serv CONE (CPTu), INSTALAÇÃO D ices, reduce water losses, an Single Stage - One E E MEDIDORES DE NÍVEL D'ÁG IBRD / 89160 Post Request for Bids Open - National 139,129.06 Signed 2021-10-31 2021-11-19 2021-11-05 2022-03-15 2021-12-17 2022-04-07 2022-01-16 2022-05-30 2022-02-20 2022-07-14 2022-08-19 d increase system resilience nvelope UA E PIEZÔMETROS DE TUBO in the MRSP ABERTO NA BARRAGEM ATIB AINHA – SISTEMA CANTAREIR A (TR14) BR-SABESP-257101-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 3,676,868.76 Signed 2021-11-22 2022-02-18 2021-11-27 2022-01-08 2022-03-29 2022-02-07 2022-05-10 2022-03-14 2022-07-29 2022-09-10 m áreas de alta vulnerabilida d increase system resilience nvelope de social - São Miguel in the MRSP BR-SABESP-257109-NC-RFB Expand access to water serv / Regularização de ligações e ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 4,421,756.15 Signed 2021-11-22 2022-02-18 2021-11-27 2022-01-08 2022-03-29 2022-02-07 2022-05-10 2022-03-14 2022-07-28 2022-09-10 m área de alta vulnerabilidad d increase system resilience nvelope e social - Pantanal / Várzea d in the MRSP o Tietê BR-SABESP-208469-NC-RFB / Regularização de ligações d e água, supressão da infraest Expand access to water serv rutura irregular e recuperaçã ices, reduce water losses, an Single Stage - One E o de clientes, por meio de co IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2021-02-28 2021-06-04 2021-03-05 2021-04-16 2021-07-12 2021-05-16 2021-06-20 2021-12-17 d increase system resilience nvelope ntrato de performance, visan in the MRSP do o aumento da eficiência o peracional nos setores de ab astecimento de água Suzano e Recanto Mônica BR-SABESP-248804-NC-RFB / EXECUÇÃO DE SERVIÇOS D E ENGENHARIA PARA MANUT Technical assistance and Pro ENÇÃO DAS BARRAGENS DA Single Stage - One E IBRD / 89160 ject management and super Post Request for Bids Open - National 0.00 Canceled 2021-09-30 2022-01-03 2021-10-05 2021-11-16 2021-12-16 2022-01-20 2022-07-19 DIRETORIA METROPOLITANA nvelope vision E ESTRUTURAS ASSOCIADAS NO ÂMBITO DO PROGRAMA S ANEAMENTO SUSTENTÁVEL E INCLUSIVO BR-SABESP-299730-NC-RFB Expand access to water serv / Serviços de inspeção e elab ices, reduce water losses, an Single Stage - One E Under Imple oração de laudo de diagnósti IBRD / 89160 Post Request for Bids Open - National 0.00 2022-09-01 2022-06-29 2022-09-06 2022-10-18 2022-11-17 2022-12-22 2023-06-20 d increase system resilience nvelope mentation co das estruturas de concret in the MRSP o submersas de barragens (T R4A) BR-SABESP-254281-NC-RFB / Fornecimento e instalação d Expand access to water serv e extensômetro de haste em ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2021-10-31 2021-11-05 2021-12-17 2022-01-16 2022-02-20 2022-08-19 estruturas de concreto de uni d increase system resilience nvelope dades Operacionais de Produ in the MRSP ção de Água da Sabesp (TR1 2). Page 4 BR-SABESP-299808-NC-RFB / Regularização de ligações e m áreas de alta vulnerabilida Expand access to water serv de social, com ações de regu ices, reduce water losses, an Single Stage - One E Under Imple IBRD / 89160 Post Request for Bids Open - National 0.00 2022-12-08 2023-02-13 2022-12-13 2023-04-28 2023-01-24 2023-05-29 2023-02-23 2023-03-30 2025-05-28 larização de ligações de água d increase system resilience nvelope mentation e esgoto, supressão da infrae in the MRSP strutura irregular e recupera ção de clientes - UGRs Fregu esia do Ó e Santana (TR 15) BR-SABESP-182857-NC-RFB / PRESTAÇÃO DE SERVIÇOS D Expand access to water serv E ENGENHARIA PARA GESTÃ ices, reduce water losses, an Open - Internationa Single Stage - One E O E MONITORAMENTO DOS R IBRD / 89160 Prior Request for Bids 0.00 Canceled 2020-09-30 2020-10-05 2020-11-16 2020-12-16 2021-01-20 2021-07-19 d increase system resilience l nvelope ESULTADOS DA in the MRSP INSTRUMENTAÇÃO DE BARR AGENS E ESTRUTURAS HIDR ÁULICAS ASSOCIADAS (TDR1 ) BR-SABESP-254266-NC-RFB / Prestação de serviços de So Expand access to water serv ndagem, Coleta de Amostras ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2021-10-31 2021-10-06 2021-11-05 2022-03-15 2021-12-17 2022-04-13 2022-01-16 2022-02-20 2022-08-19 e Ensaios em Estruturas de C d increase system resilience nvelope oncreto de Unidades Operaci in the MRSP onais de Produção de Água d a Sabesp (TR10/11). BR-SABESP-314515-NC-RFB / Prestação de serviços de So Expand access to water serv ndagem, Coleta de Amostras ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 0.00 Canceled 2022-09-06 2022-09-03 2022-09-11 2022-09-13 2022-10-23 2022-10-06 2022-11-22 2022-11-07 2022-12-27 2024-03-21 e Ensaios em Estruturas de C d increase system resilience nvelope oncreto de Unidades Operaci in the MRSP onais de Produção de Água d a Sabesp (TR10/11). BR-SABESP-318184-NC-RFB / (Automação) Prestação de s erviços de engenharia para f ornecimento, desenvolvimen Technical assistance and Pro to, instalação, integração, Single Stage - One E IBRD / 89160 ject management and super Post Request for Bids Open - National 0.00 Canceled 2022-10-11 2022-12-01 2022-10-16 2022-12-01 2022-11-15 2023-01-17 2022-12-06 2023-01-10 2025-01-09 comissionamento, manutenç nvelope vision ão e disponibilidade de Hard ware e Software do sistema de supervisão e controle na E TE Barueri. BR-SABESP-299924-NC-RFB / Regularização de ligações e m áreas de alta vulnerabilida Expand access to water serv de social - Setores de Abaste ices, reduce water losses, an Single Stage - One E Under Imple IBRD / 89160 Post Request for Bids Open - National 0.00 2022-12-01 2023-02-19 2022-12-06 2023-04-24 2023-01-17 2023-05-24 2023-02-16 2023-06-11 2023-03-23 2025-05-31 cimento Vila Jaguara, Jaraguá d increase system resilience nvelope mentation , Perus, Pirituba e Parque An in the MRSP hanguera - Unidade de Geren ciamento Regional (UGR) Piri tuba (TR 14). BR-SABESP-299802-NC-DIR / Technical assistance and Pro Serviços de engenharia para IBRD / 89160 ject management and super Post Direct Selection Direct 0.00 Canceled 2022-11-01 2022-11-06 2022-12-11 2023-06-09 inspeção e elaboração de lau vision do de integridade de túneis ( TR 4) BR-SABESP-318398-NC-RFB Technical assistance and Pro / Serviços de engenharia par Single Stage - One E Under Imple IBRD / 89160 ject management and super Post Request for Bids Open - National 0.00 2022-10-31 2022-11-05 2022-12-17 2023-01-26 2023-03-09 2024-03-03 a inspeção e elaboração de l nvelope mentation vision audo de integridade de túnei s (TR 4) BR-SABESP-321872-NC-RFB / Regularização de ligações e m áreas de alta vulnerabilida Expand access to water serv de social, com ações de regu ices, reduce water losses, an Single Stage - One E Under Imple IBRD / 89160 Post Request for Bids Open - National 0.00 2022-10-31 2023-02-13 2022-11-05 2023-04-28 2022-12-17 2023-05-26 2023-01-16 2023-06-27 2023-02-20 2025-06-09 larização de ligações de água d increase system resilience nvelope mentation e esgoto, supressão da infrae in the MRSP strutura irregular e recupera ção de clientes - Guarulhos III (TR 16) BR-SABESP-321880-NC-RFB / Regularização de ligações e m áreas de alta vulnerabilida Expand access to water serv de social, com ações de regu ices, reduce water losses, an Single Stage - One E Under Imple IBRD / 89160 Post Request for Bids Open - National 0.00 2022-10-31 2023-04-20 2022-11-05 2023-05-05 2022-12-17 2023-06-12 2023-01-16 2023-02-20 2025-06-09 larização de ligações de água d increase system resilience nvelope mentation e esgoto, supressão da infrae in the MRSP strutura irregular e recupera ção de clientes - Mauá e Sant o André II (TR 17) BR-SABESP-321882-NC-RFB / Regularização de ligações e m áreas de alta vulnerabilida Expand access to water serv de social, com ações de regu ices, reduce water losses, an Single Stage - One E Under Imple IBRD / 89160 Post Request for Bids Open - National 0.00 2022-10-31 2023-04-20 2022-11-05 2023-05-03 2022-12-17 2023-06-13 2023-01-16 2023-02-20 2025-06-09 larização de ligações de água d increase system resilience nvelope mentation e esgoto, supressão da infrae in the MRSP strutura irregular e recupera ção de clientes - Centro UGR s II (TR 18) BR-SABESP-321885-NC-RFB / Regularização de ligações e m áreas de alta vulnerabilida Expand access to water serv de social, com ações de regu ices, reduce water losses, an Single Stage - One E Under Imple IBRD / 89160 Post Request for Bids Open - National 0.00 2022-10-31 2023-02-13 2022-11-05 2023-04-28 2022-12-17 2023-05-30 2023-01-16 2023-06-15 2023-02-20 2025-06-09 larização de ligações de água d increase system resilience nvelope mentation e esgoto, supressão da infrae in the MRSP strutura irregular e recupera ção de clientes - Butantã I (T R 19) BR-SABESP-321887-NC-RFB / Regularização de ligações e m áreas de alta vulnerabilida Expand access to water serv de social, com ações de regu ices, reduce water losses, an Single Stage - One E Under Imple IBRD / 89160 Post Request for Bids Open - National 0.00 2022-10-31 2023-02-13 2022-11-05 2023-04-28 2022-12-17 2023-05-31 2023-01-16 2023-02-20 2025-06-09 larização de ligações de água d increase system resilience nvelope mentation e esgoto, supressão da infrae in the MRSP strutura irregular e recupera ção de clientes - Butantã Pira jussaraI (TR 20) BR-SABESP-321888-NC-RFB / Regularização de ligações e m áreas de alta vulnerabilida Expand access to water serv de social, com ações de regu ices, reduce water losses, an Single Stage - One E Under Imple IBRD / 89160 Post Request for Bids Open - National 0.00 2022-10-31 2023-02-13 2022-11-05 2023-04-28 2022-12-17 2023-06-01 2023-01-16 2023-02-20 2025-06-09 larização de ligações de água d increase system resilience nvelope mentation e esgoto, supressão da infrae in the MRSP strutura irregular e recupera ção de clientes - Extremo Nor te/Pirituba (TR 21) Page 5 BR-SABESP-321889-NC-RFB / Regularização de ligações e m áreas de alta vulnerabilida Expand access to water serv de social, com ações de regu ices, reduce water losses, an Single Stage - One E Under Imple IBRD / 89160 Post Request for Bids Open - National 0.00 2022-10-31 2023-04-03 2022-11-05 2023-04-28 2022-12-17 2023-05-31 2023-01-16 2023-06-23 2023-02-20 2025-06-09 larização de ligações de água d increase system resilience nvelope mentation e esgoto, supressão da infrae in the MRSP strutura irregular e recupera ção de clientes - Guarulhos I V (TR 22) BR-SABESP-321890-NC-RFB / Regularização de ligações e m áreas de alta vulnerabilida Expand access to water serv de social, com ações de regu ices, reduce water losses, an Single Stage - One E Pending Impl IBRD / 89160 Post Request for Bids Open - National 0.00 2022-12-11 2022-12-16 2023-01-27 2023-02-26 2023-04-02 2025-07-20 larização de ligações de água d increase system resilience nvelope ementation e esgoto, supressão da infrae in the MRSP strutura irregular e recupera ção de clientes - Itaquera Pay olzinho (TR 23) BR-SABESP-314515-NC-RFB - NOVA / Prestacao de servic Expand access to water serv os de sondagem, coleta de a ices, reduce water losses, an Single Stage - One E IBRD / 89160 Post Request for Bids Open - National 0.00 Signed 2022-09-03 2022-09-03 2022-09-08 2022-10-20 2022-10-06 2022-11-19 2022-11-04 2022-12-24 2023-06-22 mostras e ensaios em estrut d increase system resilience nvelope uras de concreto de unidade in the MRSP s operacionais de producao e m aguas da SABEST (TR10-1 1) BR-SABESP-318184-NC-RFB- 2 / Prestação de serviços de engenharia para forneciment Technical assistance and Pro o, desenvolvimento, instalaç Single Stage - One E Under Imple IBRD / 89160 ject management and super Post Request for Bids Open - National 0.00 2023-03-24 2023-06-11 2023-03-29 2023-06-22 2023-04-28 2023-05-13 2023-06-12 2025-06-11 ão, integração, comissionam nvelope mentation vision ento, manutenção e disponib ilidade de Hardware e Softwa re do sistema de supervisão e controle na ETE Barueri (Au tomação). CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-SABESP-182859-NC-RFB / PRESTAÇÃO DE SERVIÇOS D Expand access to water serv E ENGENHARIA PARA DESEN ices, reduce water losses, an Quality And Cost- Under Implement VOLVIMENTO DE SISTEMA IN IBRD / 89160 Post Open - National 0.00 2020-09-30 2021-04-27 2020-10-21 2021-05-14 2020-12-04 2021-01-01 2021-01-31 2021-03-07 2021-04-11 2022-04-11 d increase system resilience Based Selection ation FORMATIZADO DE MONITOR in the MRSP AMENTO E INSPEÇÃO DAS BA RRAGENS E ESTRUTURAS HI DRÁULICAS (TDR2) BR-SABESP-189732-NC-RFB / PRESTAÇÃO DE SERVIÇOS D E ENGENHARIA PARA IMPLEM Technical assistance and Pro Quality And Cost- Open - Internationa Under Implement ENTAÇÃO E OPERACIONALIZ IBRD / 89160 ject management and super Prior 0.00 2020-09-30 2021-07-08 2020-10-21 2020-12-04 2022-11-14 2021-01-01 2021-01-31 2021-03-07 2021-04-11 2022-04-11 Based Selection l ation AÇÃO DO PLANO DE AÇÃO E vision MERGENCIAL (PAE) DAS BAR RAGENS E ESTRUTURAS HID RÁULICAS (TDR3) BR-SABESP-86311-CS-QCBS Technical assistance and Pro / Consultoria para avaliar pot Quality And Cost- IBRD / 89160 ject management and super Post Open - National 0.00 Canceled 2020-06-30 2020-10-09 2020-09-11 2020-09-27 2020-10-12 2020-11-11 2020-12-16 2021-01-20 2022-01-20 enciais para Eficiência Energ Based Selection vision ética - EEA e EEE BR-SABESP-278388-CS-QCB S / ELABORAÇÃO DE PROJET O BÁSICO E EXECUTIVO DAS OBRAS NECESSÁRIAS PARA Technical assistance and Pro Quality And Cost- MANUTENÇÃO DAS BARRAGE IBRD / 89160 ject management and super Post Open - National 0.00 Canceled 2022-02-20 2022-04-13 2022-03-13 2022-04-26 2022-05-24 2022-06-23 2022-07-28 2022-09-01 2023-09-01 Based Selection NS CAPIVARI, POÇO PRETO, vision OMBREIRA ESQUERDA DO CA CHOEIRA, OMBREIRAS DO JA CAREÍ E PAVIMENTAÇÃO DAS CRISTAS DE ÁGUAS CLARAS E CASCATA (TR6) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-SABESP-182423-CS-CDS / Contratação direta de PAUL O TEIXEIRA DA CRUZ CONSU LTORIA EM GEOTECNIA LTDA Technical assistance and Pro - Consultor Geotécnico para IBRD / 89160 ject management and super Post Direct Selection Direct 16,631.55 Signed 2020-07-30 2020-06-10 2020-08-09 2020-07-08 2020-10-13 2020-07-22 2021-04-11 avaliar informações, diagnóst vision ico e sugestão de investigaçõ es do aumento das cargas pi ezométricas e encharcament o do pé de jusante da barrag em Atibainha. BR-SABESP-182427-CS-CDS / Contratação direta de Ricar do Abrahão Geociências S/S. - Consultor Hidrogeólogo par Technical assistance and Pro a avaliar informações, diagnó IBRD / 89160 ject management and super Post Direct Selection Direct 16,852.43 Signed 2020-07-30 2020-06-10 2020-08-09 2020-07-08 2020-10-13 2020-07-22 2021-04-11 stico e sugestão de investiga vision ções no tema do aumento da s cargas piezométricas e enc harcamento do pé de jusante da barragem Atibainha. BR-SABESP-174589-CS-CDS / Ahmed Fouad CHRAIBI - Co Technical assistance and Pro nsultor Geotécnico para o De IBRD / 89160 ject management and super Post Direct Selection Direct 188,661.92 Signed 2020-07-31 2020-07-23 2020-08-10 2020-07-23 2020-10-14 2020-08-04 2021-04-12 senvolvimento do Plano de A vision ção relacionado à Barragem Atibainha (Sistema de Produç ão de Água Cantareira) BR-SABESP-174591-CS-CDS / Wynfrith Hugo Rodolf Klaus Riemer - Consultor Hidrogeól Technical assistance and Pro ogo para o Desenvolvimento IBRD / 89160 ject management and super Post Direct Selection Direct 122,572.91 Signed 2020-07-30 2020-07-23 2020-08-09 2019-12-23 2020-10-13 2020-07-31 2021-04-11 do Plano de Ação relacionado vision à Barragem Atibainha (Siste ma de Produção de Água Can tareira) BR-SABESP-246834-CS-CDS Technical assistance and Pro / PRESTAÇÃO DE SERVIÇOS D IBRD / 89160 ject management and super Post Direct Selection Direct 42,253.52 Signed 2021-10-31 2021-08-19 2021-11-10 2021-10-03 2022-01-14 2021-10-21 2022-07-13 E ENGENHARIA-CONSULTOR vision HDROGEÓLOGO Ricardo Anto nio Abrahão Page 6 BR-SABESP-246832-CS-CDS Technical assistance and Pro / PRESTAÇÃO DE SERVIÇOS D IBRD / 89160 ject management and super Post Direct Selection Direct 38,732.39 Signed 2021-10-31 2021-08-20 2021-11-10 2021-10-03 2022-01-14 2021-10-16 2022-07-13 E ENGENHARIA - CONSULTOR vision GEOTÉCNICO Paulo Teixeira da Cruz BR-SABESP-285415-CS-CDS / Prestação de serviços de Co Technical assistance and Pro nsultoria em Barragens e Est IBRD / 89160 ject management and super Post Direct Selection Direct 0.00 Signed 2022-03-21 2022-07-11 2022-03-31 2022-09-21 2022-06-04 2022-12-01 ruturas de Concreto - Especia vision lidade Cálculo Estrutural (TR 17) BR-SABESP-285419-CS-CDS / Prestação de serviços de co Technical assistance and Pro nsultoria em Barragens e Est IBRD / 89160 ject management and super Post Direct Selection Direct 0.00 Signed 2022-03-21 2022-07-11 2022-03-31 2022-09-05 2022-06-04 2022-12-01 ruturas de Concreto - Especia vision lidade Tecnologia dos Materi ais (TR 18) Page 7 PLAN DE PASSATION DE MARCHÉS (Texte) Information sur le Projet : République de Djibouti- Projet de Riposte au COVID-19- P173807 Agence d’exécution du Projet : Ministère de la Santé Date du plan de passation des marchés : 13 Avril 2020 Période couverte par ce plan de passation des marchés : Avril 2020 – Juin 2020 Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016, révisé en Novembre 2107 et Août 2018) (“Règlement de Passation des Marchés”) le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marché se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus de STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans la Loi n°53/AN/09/6ème L portant Nouveau Code des Marchés Publics, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas/ Travaux ne s’applique pas/ L’Assistance directe à la mise en œuvre (sigle HEIS en anglais) tel que précisée aux paragraphes 3.10 et 3.11 du Règlement de Passation des marchés s’applique. Autres informations pertinentes sur la passation des marchés Utilisation de procédures pour un besoin urgent d’assistance ou de faible capacité PROCUREMENT Djibouti : Djibouti COVID-19 Response PLAN General Information Country: Djibouti 2020-05-03 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173807 GPN Date: 2020-05-12 Project Name: Djibouti COVID-19 Response Loan / Credit No: IDA / 66000 Ministere de la Sante Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DJ-MOS-168492-GO-DIR / Ac quisition des fournitures, mé Emergency COVID-19 Respo dicaments , consommables, IDA / 66000 Post Direct Selection Direct 1,900,000.00 1,875,000.00 Completed 2020-04-19 2020-04-30 2020-04-21 2020-04-30 2020-05-10 2020-05-06 2020-08-08 2021-02-15 nse kit de diagnostic et équipem ents médicaux pour le site d e quarantaine. DON PEF TF0B4364 / FOURN Emergency COVID-19 Respo ITURE DES CONSOMMABLES IDA / 66000 Post Direct Selection Direct 942,856.60 942,856.60 Completed 2021-01-21 2021-02-01 2021-01-24 2021-02-03 2021-01-30 2021-02-07 2021-02-24 2022-01-21 nse ET EQUIPEMENTS MEDICAUX DJ-MOS-234856-GO-RFQ / Co nception et impression d’ima Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66000 Post Limited 25,000.00 24,856.07 Completed 2020-11-06 2020-12-02 2021-01-01 2021-01-04 2021-06-30 2021-01-04 ge sur la prévention de la pa nse tions nvelope ndémie de la COVID-19 à Dji bouti DJ-MOS-292879-GO-DIR / Ac Strengthening Overall Healt hat de medicament et conso IDA / 66000 hcare Services and Clinical C Post Direct Selection Direct 1,746,511.10 0.00 Completed 2022-01-01 2022-01-23 2022-01-06 2022-01-23 2022-02-10 2022-08-09 2023-01-13 mmable medicaux apacity for Emergency COVI D-19 Response DJ-MOS-220948-GO-RFQ / Ac Emergency COVID-19 Respo Request for Quota Single Stage - One E quisition des kits et matériel IDA / 66000 Post Limited 27,000.00 0.00 Completed 2021-03-03 2022-05-22 2021-04-03 2021-07-02 2022-06-25 nse tions nvelope s pour le lavage des mains DJ-MOS-298583-GO-DIR / Ac Implementation Managemen quisition d'un Scanner CT po IDA / 66000 t and Monitoring and Evaluat Post Direct Selection Direct - National 655,000.00 0.00 Completed 2022-07-31 2022-10-27 2022-08-05 2022-10-27 2022-09-09 2023-03-08 ur l'hôpital d'Ali-Sabieh. ion DJ-MOS-298584-GO-DIR / Ac Implementation Managemen Under Imple quisition de 02 chambre froid IDA / 66000 t and Monitoring and Evaluat Post Direct Selection Direct - National 80,000.00 0.00 2022-07-31 2022-09-01 2022-08-05 2022-09-01 2022-09-09 2023-03-08 mentation es morgues (6-8 corps). ion DJ-MOS-305782-GO-RFQ / Ac Strengthening Overall Healt Request for Quota Single Stage - One E quisition des fournitures des IDA / 66000 hcare Services and Clinical C Post Limited 27,696.33 0.00 Completed 2020-01-06 2020-01-07 2020-03-02 2020-08-29 2020-01-21 tions nvelope matériels tels que peintures, apacity for Emergency COVI ciments etc D-19 Response DJ-MOS-305781-GO-RFQ / Ac Strengthening Overall Healt Request for Quota Single Stage - One E quisition des lits d'hôpital po IDA / 66000 hcare Services and Clinical C Post Limited 24,927.61 0.00 Completed 2020-01-06 2020-02-20 2020-03-02 2020-08-29 2020-04-01 tions nvelope ur l'hôpital d'Ali-sabieh. apacity for Emergency COVI D-19 Response DJ-MOS-305777-GO-RFQ / Ac Strengthening Overall Healt quisition des fournitures, équ hcare Services and Clinical C Request for Quota Single Stage - One E IDA / 66000 Post Limited 25,937.28 0.00 Completed 2020-01-06 2020-01-16 2020-03-02 2020-08-29 2020-03-02 ipements de plomberie et de apacity for Emergency COVI tions nvelope s petits outillages. D-19 Response DJ-MOS-305778-GO-RFQ / Ac Strengthening Overall Healt Request for Quota Single Stage - One E quisition des lits d'hôpital po IDA / 66000 hcare Services and Clinical C Post Limited 24,927.61 0.00 Completed 2020-01-06 2020-02-20 2020-03-02 2020-08-29 2020-04-01 tions nvelope ur le site de PK13. apacity for Emergency COVI D-19 Response DJ-MOS-306572-GO-DIR / Sy Implementation Managemen stème de visualisation pour l IDA / 66000 t and Monitoring and Evaluat Post Direct Selection Direct - National 27,000.00 0.00 Canceled 2022-08-10 2022-08-15 2022-09-19 2023-03-18 e scanner de l'hôpital Cheiko. ion DJ-MOS-306573-GO-DIR / Ac quisition d'un injecteur pour l Implementation Managemen e scanner de l'hôpital Cheiko IDA / 66000 t and Monitoring and Evaluat Post Direct Selection Direct - National 31,000.00 0.00 Canceled 2022-08-10 2022-08-15 2022-09-19 2023-03-18 et un nouveau onduleur pour ion l'hôpital d'Ali-SABIEH (toujour s avec la CAMME). DJ-MOS-315525-GO-RFQ / Ac quisition des matériels adéqu ats pour la gestion des déche Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66000 Post Limited 17,500.00 0.00 Completed 2022-09-25 2022-10-13 2022-11-20 2023-05-19 2022-12-18 ts sanitaires en termes ( sacs nse tions nvelope plastiques codifiés, corbeilles et boites de sécurité à aiguill es etc.) DJ-MOS-364536-GO-DIR / Ac Implementation Managemen quisition de 4 appareils d'éch Direct - Internation Pending Impl IDA / 66000 t and Monitoring and Evaluat Post Direct Selection 154,980.00 0.00 2023-06-14 2023-06-17 2023-06-18 2023-06-30 ographies fixes et 5 échogra al ementation ion phies mobiles pour les forma tions sanitaires. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DJ-MOS-291207-NC-RFQ / Pr oduire des outils de communi Emergency COVID-19 Respo Request for Quota Single Stage - One E cation sur la prévention contr IDA / 66000 Post Limited 24,000.00 0.00 Canceled 2022-06-04 2022-07-30 2023-01-26 nse tions nvelope e la COVID-19 et l'importanc e de la vaccination contre le covid-19 Page 1 DJ-MOS-291203-NC-RFQ / Co nception et production des af Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66000 Post Limited 25,000.00 0.00 Canceled 2022-06-03 2022-07-29 2023-01-25 fiches de communication pou nse tions nvelope r promouvoir la vaccination c ontre le covid-19 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DJ-MOS-182922-CS-QCBS / R Implementation Managemen Consultant Qualifi Open - Internationa ecrutement d'une agence po IDA / 66000 t and Monitoring and Evaluat Post 40,000.00 0.00 Canceled 2020-08-25 2020-09-15 2020-10-29 2020-11-28 2021-01-02 2021-07-01 cation Selection l ur l'audit technique et des pe ion rformances DJ-MOS-182925-CS-LCS / Re Implementation Managemen Least Cost Selecti crutement d’un cabinet char IDA / 66000 t and Monitoring and Evaluat Post Open - National 10,000.00 0.00 Canceled 2020-08-25 2020-12-10 2020-09-15 2020-10-07 2020-10-17 2020-11-01 2020-11-23 2020-12-10 2021-01-29 on gé de l’audit des comptes du ion nouveau projet DJ-MOS-241365-CS-LCS / Re Implementation Managemen Least Cost Selecti Under Implement crutement d'un consultant en IDA / 66000 t and Monitoring and Evaluat Post Open - National 10,000.00 0.00 2021-08-09 2021-07-22 2021-08-30 2021-10-13 2021-11-10 2021-12-10 2022-01-14 2022-02-18 2022-08-17 on ation audit externe ion DJ-MOS-306569-CS-CQS / Re Implementation Managemen crutement d'un cabinet pour Consultant Qualifi Open - Internationa Under Implement IDA / 66000 t and Monitoring and Evaluat Post 130,000.00 0.00 2022-08-03 2022-08-07 2022-08-24 2022-10-07 2022-11-06 2022-12-11 2023-06-09 l'élaboration d'une stratégie cation Selection l ation ion de digitalisation. DJ-MOS-352712-CS-CQS / Re Implementation Managemen crutement d’un cabinet médi Consultant Qualifi Open - Internationa IDA / 66000 t and Monitoring and Evaluat Post 60,000.00 0.00 Canceled 2023-03-30 2023-04-20 2023-06-03 2023-07-03 2023-08-07 2024-02-03 cal chargé de services de tél cation Selection l ion é radiologie et de formation en radiologie. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DJ-MOS-291137-CS-INDV / R ecrutement d'un consultant p Implementation Managemen Individual Consult our élaborer le document de IDA / 66000 t and Monitoring and Evaluat Post Open 20,000.00 0.00 Canceled 2022-04-28 2022-06-16 2022-07-07 2022-08-11 2023-02-07 ant Selection PLIGD et sa mise en œuvre d ion ans la cadre du projet DJ-MOS-306571-CS-CDS / Co ntrat de maintenance préven Implementation Managemen tive pour le scanner de l'hôpi IDA / 66000 t and Monitoring and Evaluat Post Direct Selection Direct - National 60,000.00 0.00 Canceled 2022-08-10 2022-08-20 2022-10-24 2023-04-22 tal cheiko et formation des b ion énéficiaires (toujours avec la CAMME). DJ-MOS-361196-NC-DIR / Re Implementation Managemen crutement d’un cabinet médi Direct - Internation Under Implement IDA / 66000 t and Monitoring and Evaluat Post Direct Selection 60,000.00 0.00 2023-05-11 2023-05-16 2023-05-14 2023-05-18 2023-06-30 cal chargé des services de té al ation ion lé radiologie et des formation s en radiologie. DJ-MOS-362017-CS-CDS / Re Implementation Managemen crutement d'un cabinet pour Direct - Internation Under Implement IDA / 66000 t and Monitoring and Evaluat Post Direct Selection 45,000.00 0.00 2023-05-21 2023-06-04 2023-05-24 2023-06-20 2023-06-30 l'Installation, la Formation et al ation ion la maintenance des incinérat eurs Page 2 CENTRAL SULAWESI REHABILITATION AND RECONSTRUCTION PROJECT (CSRRP) LOAN No. IBRD Ln.8979; AIIB LN 004-IDN Summary of Procurement Plan Version No.: 1 Date: February 11, 2020 I. General Information 1. Project information: a. Country: Indonesia b. Recipient: Republic of Indonesia c. Project Name: Indonesia Disaster Resilience Initiatives Project ((IDRIP) d. Project Implementing Agency (PIA): (i) Badan Nasional Penanggulangan Bencana (National Disaster Management Authority) (BNPB) (ii) Badan Meteorologi, Klimatologi, dan Geofisika (Indonesian Agency for Meteorology, Climatology, and Geophysics) (BMKG) 2. Bank’s No Objection Date of the Procurement Plan: a. Original : 5 March 2021 b. Version 2 : c. Version 3 : 3. Date of General Procurement Notice: 23 February 2021 4. Period covered by this procurement plan: Effectiveness – Loan Closing (31 December 2024) II. Types of Contract, Bank’s Review Requirements and Applied Methods A. Works, Goods and Non-Consulting Services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Ref. Procureme Bank’s Review Procurement Method No. nt Method Requirement Threshold 1. International Competitive ≥ $50 million Each contract shall Bidding (Works) be subject to Bank’s prior review. 2. National Competitive $200k - $50 Each contract ≥ Bidding (Works) million $20 million equivalent shall be subject to Bank’s prior review. All other contracts 3. Request for Quotations for < $200k priorto subject No post review Works review. (only post review). 4 Direct Selection for works Subject to ≥ US$ 10 million conditions as per paragraph 6.8, 6.9 and 6.10 of the 5. International Competitive Procurement ≥$4 million Each contract ≥ $4 Bidding (Goods) Regulations million equivalent shall be subject to Bank’s prior review. All other contracts subject to post 6. National Competitive $100k - $4 review. Each contract ≥ $2 Bidding (Goods) million million equivalent shall be subject to Bank’s prior review. All other contracts subject to post 7. Request for Quotations for <100k review. No prior review Goods (only post review). 8. Direct Selection for goods Subject to ≥ US$ 2 million conditions as per paragraph 6.8, 6.9 and 6.10 of the 9. International Competitive Procurement ≥$20 million Each contract shall Bidding (Non-Consultant Regulations be subject to Bank’s Service) prior review. 10. National Competitive $100k - $20 Each contract ≥ Bidding (Non-Consultant million $10 million Service) equivalent shall be subject to Bank’s prior review. All other contracts 11. Request for Quotations for <$100,000 priorto subject No post review Non-Consulting Service review. (only post review). 12. Direct Contracting for non- Subject to ≥ US$ 5 million consulting services conditions as per paragraph 6.8, 6.9 and 6.10 of the Procurement Regulations 1. Pre-qualification: Not applicable. 2. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: As specified in the Project Operations Manual (POM) 3. Reference to (if any) Project Operational/Procurement Manual: Project Operations Manual of CSRRP 4. Any Other Special Procurement Arrangements: -NA- 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Descripti Estimat Packag Domesti Revie Comments No. on ed es c w Cost Prefere by (US$ nce Bank million) (yes/no) (Prior / Post) 1. Summary 9.167 1 Yes Prior of the Internatio nal Open Competiti ve Procurem ent (Goods) 2. Summary 3.731 3 No Post of the NCB (Goods) 2. Summary 0.371 2 No Post of the NCB (Non- consulting Services) 3. Summary 0.694 1 No Post of the NCB (Works) B. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to prior review by Bank as stated in Appendix 1 to the Guidelines for Selection and Employment of Consultants: Ref. Selection Selection Method Bank’s Prior Review No. Method Threshold Requirement 1. International ≥$ 1 million Each contract ≥ Open (Firms) $1,000,000 equivalent QCBS, QBS, shall be subject to LCS, FBS Bank’s prior review. All other contracts subject to post review. Ref. Selection Selection Method Bank’s Prior Review No. Method Threshold Requirement 2. National Open <$ 1 million Each contract ≥ (Firms) QCS $1,000,000 equivalent shall be subject to Bank’s prior review. All other contracts subject to post review. 3 Direct Selection Subject to conditions as ≥ US$ 0.5 million per paragraph 7.13, 7.14 and 7.15 of the Procurement Regulations 4. Individual Competitive Selection by ≥ US$ 600k or as stated Consultant comparing at least three in the procurement plan CVs 5. Single Source Subject to conditions as ≥ US$ 300k (Firms and per paragraph 7.39 of the Individual) Procurement Regulations 2. Short list comprising entirely of national consultants: Short list of consultants for services (firms), estimated to cost less than $ 600,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: N/A 4. Summary of Consultancy Assignments with Selection Methods and Time Schedule during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref Descripti Type of Estimat Packag Revie Commen . on of Assignme ed es/Posit w ts No. Assignme nts Cost ions by nts (US$ Bank million) (Prior / Post) 1 Summary (Time- 0.17 10 Post of number Based) of individual consultant contracts that will be selected through competitiv 1 2 3 4 5 6 7 Ref Descripti Type of Estimat Packag Revie Commen . on of Assignme ed es/Posit w ts No. Assignme nts Cost ions by nts (US$ Bank million) (Prior / Post) e selection PROCUREMENT Indonesia : Indonesia Disaster Resilience Initiatives Project (IDRIP) PLAN General Information Country: Indonesia 2021-03-17 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P170874 GPN Date: 2021-02-22 Project Name: Indonesia Disaster Resilience Initiatives Project (IDRIP) Loan / Credit No: IBRD / 89800 Meteorological, Climatological, and Geophysical Agency Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-BMKG-224452-GO-RFB / P Component 2 Geophysical e Open - Internationa Single Stage - One E rocurement of Broadband sei IBRD / 89800 Prior Request for Bids 9,167,000.00 0.00 Canceled 2021-03-21 2021-03-26 2021-05-07 2021-06-06 2021-07-11 2022-01-07 arly warning services l nvelope smograph Sensors ID-BMKG-224958-GO-RFB / P Component 2 Geophysical e Single Stage - One E IBRD / 89800 Post Request for Bids Open - National 1,250,000.00 0.00 Canceled 2021-03-30 2021-04-04 2021-05-16 2021-06-15 2021-07-20 2022-01-16 rocurement of Portable Seis arly warning services nvelope mograph ID-BMKG-226123-GO-RFB / P Component 2 Geophysical e Single Stage - One E rocurement of Big Database IBRD / 89800 Post Request for Bids Open - National 703,200.00 0.00 Canceled 2021-05-02 2021-05-07 2021-06-18 2021-07-18 2021-08-22 2022-02-18 arly warning services nvelope Development ID-BMKG-226126-GO-RFB / P Component 2 Geophysical e Single Stage - One E rocurement of Relocation ser IBRD / 89800 Post Request for Bids Open - National 1,105,000.00 0.00 Canceled 2021-05-12 2021-05-17 2021-06-28 2021-07-28 2021-09-01 2022-02-28 arly warning services nvelope ver InaTEWS phase I ID-BMKG-226127-GO-RFB / P Component 2 Geophysical e Single Stage - One E rocurement of Communicatio IBRD / 89800 Post Request for Bids Open - National 694,400.00 0.00 Canceled 2021-05-12 2021-05-17 2021-06-28 2021-07-28 2021-09-01 2022-02-28 arly warning services nvelope n Infrastructure Network Dev elopment ID-BMKG-252877-GO-RFB / E Component 2 Geophysical e Single Stage - One E quipment for earthquake and IBRD / 89800 Post Request for Bids Open - National 392,000.00 0.00 Canceled 2021-09-27 2021-11-30 2021-10-02 2021-11-30 2021-10-25 2021-12-21 2021-11-10 2021-12-16 2022-03-26 arly warning services nvelope tsunami assessment survey ID-BMKG-252881-GO-RFB / C Component 2 Geophysical e Single Stage - One E ommunication Infrasturcture IBRD / 89800 Post Request for Bids Open - National 1,389,000.00 0.00 Canceled 2021-09-27 2022-01-13 2021-10-02 2022-01-12 2021-10-25 2022-02-08 2021-11-10 2021-12-15 2022-10-11 arly warning services nvelope network development ID-BMKG-252882-GO-RFB / P Component 2 Geophysical e Single Stage - One E rocurement of Facilities and I IBRD / 89800 Post Request for Bids Open - National 1,097,194.00 0.00 Canceled 2021-09-27 2021-12-14 2021-10-02 2021-12-13 2021-10-25 2022-01-04 2021-11-10 2021-12-15 2022-10-11 arly warning services nvelope nfrastructure for STMKG ID-BMKG-258410-GO-RFB / S Component 2 Geophysical e Open - Internationa Single Stage - Two E Under Imple IBRD / 89800 Prior Request for Bids 17,914,000.00 0.00 2021-10-27 2021-12-21 2021-11-01 2022-05-09 2021-12-13 2022-05-25 2022-01-14 2022-08-30 2022-02-18 2023-02-13 eismograph Sensors arly warning services l nvelope mentation ID-BMKG-258412-GO-RFB / P Component 2 Geophysical e Single Stage - Two E rocurement of Infrastructure IBRD / 89800 Prior Request for Bids Open - National 2,125,000.00 0.00 Canceled 2021-10-27 2021-11-01 2021-11-22 2021-12-24 2022-01-28 2023-01-25 arly warning services nvelope for Data Center ID-BMKG-258425-GO-RFB / S Component 2 Geophysical e Open - Internationa Single Stage - Two E IBRD / 89800 Prior Request for Bids 14,726,730.00 0.00 Canceled 2021-12-15 2021-12-20 2022-01-31 2022-03-04 2022-04-08 2023-02-02 trongmotion Sensors arly warning services l nvelope ID-BMKG-272444-GO-RFB / P rocurement Of Equipment Fo Component 2 Geophysical e Single Stage - One E IBRD / 89800 Post Request for Bids Open - National 392,000.00 0.00 Canceled 2022-01-17 2022-03-21 2022-01-22 2022-03-20 2022-02-14 2022-04-12 2022-03-02 2022-04-07 2022-07-16 r Earthquake And Tsunami As arly warning services nvelope sessment Survey ID-BMKG-274826-GO-RFB / P Component 2 Geophysical e Single Stage - One E rocurement of Facilities and I IBRD / 89800 Post Request for Bids Open - National 1,097,194.00 1,083,765.81 Signed 2022-01-31 2022-02-15 2022-02-05 2022-02-16 2022-02-28 2022-03-09 2022-03-16 2022-03-24 2022-04-20 2022-04-21 2022-07-29 arly warning services nvelope nfrastructure for STMKG ID-BMKG-282652-GO-RFB / C Component 2 Geophysical e Single Stage - One E ommunication Infrastructure IBRD / 89800 Post Request for Bids Open - National 1,389,000.00 1,179,500.00 Signed 2022-03-14 2022-04-25 2022-03-19 2022-04-24 2022-04-11 2022-05-24 2022-04-27 2022-06-10 2022-06-01 2022-07-16 2023-03-28 arly warning services nvelope Network Development ID-BMKG-294953-GO-RFB / P rocurement Of Equipment Fo Component 2 Geophysical e Single Stage - One E IBRD / 89800 Post Request for Bids Open - National 392,000.00 379,107.36 Signed 2022-05-19 2022-07-07 2022-05-24 2022-07-06 2022-06-16 2022-07-28 2022-07-02 2022-08-05 2022-08-07 2022-08-17 2023-01-04 r Earthquake And Tsunami As arly warning services nvelope sessment Survey ID-BMKG-297710-GO-RFB / P Component 2 Geophysical e Single Stage - Two E rocurement of Supporting Inf IBRD / 89800 Prior Request for Bids Open - National 2,123,000.00 0.00 Canceled 2022-06-06 2022-09-05 2022-06-11 2022-07-02 2022-08-03 2022-09-04 2023-09-04 arly warning services nvelope rastructure Facilities for Com putation Building ID-BMKG-299115-GO-RFB / B IG Data Development and HP Component 2 Geophysical e Open - Internationa Single Stage - Two E C Procurement for Tsunami I IBRD / 89800 Prior Request for Bids 10,494,440.00 0.00 Canceled 2022-06-26 2022-07-16 2022-07-01 2022-08-25 2022-08-12 2022-10-25 2022-11-29 2023-11-29 arly warning services l nvelope nformation Development and Earthquake Processing ID-BMKG-302781-GO-RFB / Component 2 Geophysical e Single Stage - One E IBRD / 89800 Post Request for Bids Open - National 1,695,486.00 0.00 Canceled 2022-07-14 2022-07-17 2022-08-07 2022-08-22 2022-09-15 2023-04-13 WRS Dissemination System arly warning services nvelope ID-BMKG-336605-GO-RFB / Component 2 Geophysical e Single Stage - One E Under Imple IBRD / 89800 Post Request for Bids Open - National 744,385.00 0.00 2023-01-24 2023-05-16 2023-01-27 2023-05-19 2023-02-17 2023-06-09 2023-03-04 2023-06-26 2023-04-15 2023-09-12 WRS Dissemination System arly warning services nvelope mentation ID-BMKG-336606-GO-RFB / S Component 2 Geophysical e Open - Internationa Single Stage - Two E Under Imple IBRD / 89800 Prior Request for Bids 11,027,600.00 0.00 2023-01-27 2023-02-01 2023-03-15 2023-04-16 2023-05-21 2024-06-24 trongmotion Sensors arly warning services l nvelope mentation ID-BMKG-339713-GO-RFB / C Component 2 Geophysical e Open - Internationa Single Stage - Two E Under Imple ommunication Infrastructure IBRD / 89800 Prior Request for Bids 7,000,000.00 0.00 2023-02-06 2023-04-11 2023-02-11 2023-05-24 2023-03-25 2023-06-07 2023-07-12 2024-12-31 arly warning services l nvelope mentation Network Development (Phas e II) Page 1 ID-BMKG-344962-GO-RFB / B IG Data Development and HP Component 2 Geophysical e Open - Internationa Single Stage - Two E Under Imple C Procurement for Tsunami I IBRD / 89800 Prior Request for Bids 10,494,440.00 0.00 2023-03-08 2023-05-04 2023-03-13 2023-05-29 2023-04-24 2023-07-07 2023-08-11 2024-11-29 arly warning services l nvelope mentation nformation Development and Earthquake Processing ID-BMKG-358502-GO-RFB / I Component 2 Geophysical e Single Stage - One E Pending Impl IBRD / 89800 Post Request for Bids Open - National 1,999,999.00 0.00 2023-05-26 2023-05-28 2023-06-18 2023-07-18 2023-08-22 2024-08-21 ntensitymeter For EEWS arly warning services nvelope ementation ID-BMKG-362563-GO-RFB / E Component 2 Geophysical e Single Stage - One E Pending Impl IBRD / 89800 Post Request for Bids Open - National 920,000.00 0.00 2023-05-31 2023-06-02 2023-06-23 2023-07-23 2023-08-27 2024-11-29 EWS Development arly warning services nvelope ementation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-BMKG-226125-NC-RFB / P Component 2 Geophysical e Single Stage - One E IBRD / 89800 Post Request for Bids Open - National 222,200.00 208,049.00 Signed 2021-05-09 2021-11-10 2021-05-14 2021-11-09 2021-06-25 2021-12-01 2021-07-25 2021-12-16 2021-08-29 2022-01-22 2022-02-25 rocurement of Data Rescue S arly warning services nvelope ervices CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-BMKG-287147-CS-CQS / C onstruction Management Con Component 2 Geophysical e Consultant Qualifi IBRD / 89800 Post Open - National 415,600.00 0.00 Signed 2022-04-04 2022-04-12 2022-04-18 2022-07-28 2022-05-07 2022-09-20 2022-06-06 2022-10-17 2022-06-16 2024-06-05 sultant InaTEWS Operational arly warning services cation Selection System Development (Buildi ng) Jakarta-Bali ID-BMKG-287351-CS-CQS / P rocurement of Planning Cons Component 2 Geophysical e Consultant Qualifi ultant Services InaTEWS Ope IBRD / 89800 Post Open - National 432,208.00 0.00 Signed 2022-04-04 2022-04-12 2022-04-18 2022-07-28 2022-05-07 2022-10-04 2022-06-06 2022-11-21 2022-06-16 2024-06-05 arly warning services cation Selection rational System Developmen t (Building) Jakarta-Bali ID-BMKG-342612-CS-CQS / Component 2 Geophysical e Consultant Qualifi IBRD / 89800 Post Open - National 229,550.00 0.00 Canceled 2023-02-17 2023-02-17 2023-03-03 2023-03-13 2023-03-22 2023-04-21 2023-05-01 2023-10-28 Management for EEWS Devel arly warning services cation Selection opment ID-BMKG-342612-CS-CQS-2 / Component 2 Geophysical e Consultant Qualifi Under Implement IBRD / 89800 Post Open - National 240,000.00 0.00 2023-05-29 2023-06-22 2023-06-12 2023-06-23 2023-07-01 2023-07-06 2023-07-16 2024-11-04 Management for EEWS Devel arly warning services cation Selection ation opment INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-BMKG-225934-CS-INDV / Component 2 Geophysical e Individual Consult Procurement of Monitoring a IBRD / 89800 Post Limited 21,370.00 41,751.60 Signed 2021-03-30 2021-03-31 2021-04-04 2021-04-26 2021-04-25 2021-04-27 2021-05-30 2021-05-07 2022-02-24 arly warning services ant Selection nd Evaluation Consultant ID-BMKG-224455-CS-INDV / Component 2 Geophysical e Individual Consult IBRD / 89800 Post Limited 21,370.00 44,393.92 Signed 2021-03-30 2021-03-29 2021-04-04 2021-04-14 2021-04-25 2021-04-15 2021-05-30 2021-04-24 2022-02-24 Procurement Consultant arly warning services ant Selection ID-BMKG-282654-CS-INDV / I ndividual Consultant Service Component 2 Geophysical e Individual Consult of High Performance Computi IBRD / 89800 Post Limited 21,528.00 19,437.93 Signed 2022-03-08 2022-03-21 2022-03-13 2022-03-24 2022-04-03 2022-04-14 2022-05-08 2022-04-21 2023-03-04 arly warning services ant Selection ng (HPC) and Hyper Converg ed Infrastructure (HCI) ID-BMKG-287146-CS-INDV / I ndividual Consultant Services Component 2 Geophysical e Individual Consult IBRD / 89800 Post Open 7,500.00 0.00 Canceled 2022-03-30 2022-04-12 2022-04-15 2022-04-18 2022-04-20 2022-07-19 For Environmental And Social arly warning services ant Selection Risk Screening For BMKG Buil ding Construction ID-BMKG-287360-CS-INDV / I ndividual Consultant Services Component 2 Geophysical e Individual Consult for Communication Infrastruc IBRD / 89800 Post Open 11,687.00 0.00 Canceled 2022-04-25 2022-04-25 2022-05-11 2022-05-14 2022-05-16 2022-11-12 arly warning services ant Selection ture Network Development, a nd Communication Network L ease ID-BMKG-287365-CS-INDV / I Component 2 Geophysical e Individual Consult ndividual Consultant Services IBRD / 89800 Post Open 11,687.00 9,907.80 Signed 2022-04-18 2022-04-20 2022-05-04 2022-06-24 2022-05-07 2022-06-27 2022-05-09 2022-07-01 2022-11-05 arly warning services ant Selection for Data Center ID-BMKG-287370-CS-INDV / I Component 2 Geophysical e Individual Consult ndividual Consultant Services IBRD / 89800 Post Open 11,270.00 9,721.44 Signed 2022-04-25 2022-04-20 2022-05-11 2022-06-20 2022-05-14 2022-06-20 2022-05-16 2022-06-28 2022-11-12 arly warning services ant Selection for Environmental and Social Management ID-BMKG-287359-CS-INDV / I Component 2 Geophysical e Individual Consult ndividual Consultant Services IBRD / 89800 Post Open 9,121.00 8,056.53 Signed 2022-04-25 2022-05-13 2022-05-11 2022-06-24 2022-05-14 2022-06-27 2022-05-16 2022-07-02 2022-08-14 arly warning services ant Selection Assesment of BMKG IDRIP Bu ilding Needs ID-BMKG-287371-CS-INDV / I ndividual Planning Consultan Component 2 Geophysical e Individual Consult t Services for Renovation Wo IBRD / 89800 Post Limited 8,348.00 0.00 Canceled 2022-04-25 2022-06-23 2022-04-30 2022-05-21 2022-06-25 2022-09-23 arly warning services ant Selection rk of 25 Shelter/ Bungker Buil ding Sites for Seismograph U pgrading ID-BMKG-296737-CS-INDV / I ndividual Consultant Services Component 2 Geophysical e Individual Consult IBRD / 89800 Post Open 7,500.00 5,206.65 Signed 2022-05-27 2022-05-31 2022-06-12 2022-06-24 2022-06-15 2022-06-27 2022-06-17 2022-07-02 2022-09-15 For Environmental And Social arly warning services ant Selection Risk Screening For BMKG Buil ding Construction ID-BMKG-299112-CS-INDV / I ndividual Consultant Services Component 2 Geophysical e Individual Consult for Communication Infrastruc IBRD / 89800 Post Open 11,687.00 0.00 Canceled 2022-06-13 2022-07-07 2022-06-29 2022-07-02 2022-07-04 2022-12-31 arly warning services ant Selection ture Network Development, a nd Communication Network L ease Page 2 ID-BMKG-301555-CS-INDV / I ndividual Planning Consultan Component 2 Geophysical e Individual Consult t Services for Renovation Wo IBRD / 89800 Post Limited 8,348.00 7,368.43 Signed 2022-07-01 2022-06-28 2022-07-06 2022-08-30 2022-07-27 2022-08-31 2022-08-31 2022-09-07 2022-11-29 arly warning services ant Selection rk of 24 Shelter/ Bunker Build ing Sites for Upgrading Seism ograph Broadband Sensor ID-BMKG-303900-CS-INDV / I ndividual Consultant Services Component 2 Geophysical e Individual Consult for Communication Infrastruc IBRD / 89800 Post Open - National 10,150.00 0.00 Canceled 2022-07-15 2022-07-26 2022-07-31 2022-08-03 2022-08-05 2023-01-02 arly warning services ant Selection ture Network Development, a nd Communication Network L ease ID-BMKG-303900-CS-INDV-2 / Individual Consultant Servic Component 2 Geophysical e Individual Consult es for Communication Infrast IBRD / 89800 Post Open - National 6,093.00 5,753.31 Signed 2022-08-26 2022-09-07 2022-09-11 2022-09-22 2022-09-14 2022-09-23 2022-09-16 2022-10-07 2022-12-15 arly warning services ant Selection ructure Network Developmen t, and Communication Netwo rk Lease Page 3 PROCUREMENT PLAN General 1. Project Information a. Country: Federal Republic of Somalia b. Project Name: Somalia Recurrent Cost and Reform Financing Project – Phase III c. Project Number: P173731 d. Total Finance: USD 68,000,000 2. Project Implementation Agency: Ministry of Finance, Federal Government of Somalia 3. Date of Project Plan: 7 June 2021 4. Period Covered by this Procurement: June 2021 – December 2022 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised November 2017, August 2018 and November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Document: The Bank’s standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified into Procurement Plan tables in STEP III. National Procurement Arrangements: Not applicable IV. Prequalification: Not applicable V. Leased Assets: Not Applicable VI. Procurement of Second-hand Goods: Not Applicable VII. Domestic Preference: Not Applicable 1 VIII. Hands on Expanded Implementation Support (HEIS): Not applicable IX. Other Relevant Procurement Information: Not Applicable X. Thresholds for Procurement Approaches and Method (US$ millions) Based on the risks identified above, the following procurement arrangements are proposed: a) Approach to Market: Based on previous experience and available local market, the following threshold will be used of open national/international and RFQ bidding (all figures in million USD) Table 1.2: Thresholds for procurement approaches and methods Procurement Methods (US$ millions)–Goods, Works, and Non- Consulting Services Open Open Request for Direct Category Internatio National Quotation Selection nal (RfQ) Works ≥ 5.0 <5.0 ≤ 0.2 All Values Goods, IT, and non- ≥ 0.5 <0.5 ≤ 0.1 All Values consultin g services Thresholds for Procurement Approaches and Methods (US$, millions) – Consulting Services Category Short List of National Consultants Consulting Engineering and Services Construction Supervision Consultants (Firms) ≤ 0.1 ≤ 0.2 Individual Consultants N.A. N.A. Direct Selection Consultants (Firms) All Values All Values Individual Consultants All Values All Values 2 3 XI. Table Packages for Goods, Works and Non-Consulting Services (At Negotiations – to be entered in STEP) Market Selecti Procurem Revi Approa on Evaluatio ent ew Expected Expected ch Metho n Options Process Contract Estimat by date of date of Ref. (Open- d (BAFO (Single Descripti ed Cost Bank bid/ Contract No Nation (RFP, Rated stage- on (US$) (Prio proposal Signatur al/ RFB, Criteria single r/ opening e Limited RFQ etc.) envelope Post) etc.) etc.) etc.) Goods Supply of Single Smart Most stage One- Open 02/July/20 30/July/20 G1 Phones 300,000. Prior RFB advantage Envelop National 21 21 with Solar 00 ous Bid System Office Furniture Most Single 28/June/2 25/July/20 Limited G2 for RCRF 22,000.0 Prior RFQ advantage stage One- 021 21 National PIU 0 ous Bid Envelop Offices 322,00 Subtotal (Goods) 0.00 Non-Consulting Services Provision of Most Single 20/June/2 01/July/20 12,000.0 Limited NC1 WhatsApp Prior DS advantage stage One- 021 21 0 National Messagin ous Bid Envelop g Services Translatio Most 50,000.0 Limited Single 20/June/2 10/July/20 NC2 n, Voice Prior RFP advantage 0 National stage One- 021 21 Over ous Bid Envelop 1 Market Selecti Procurem Revi Approa on Evaluatio ent ew Expected Expected ch Metho n Options Process Contract Estimat by date of date of Ref. (Open- d (BAFO (Single Descripti ed Cost Bank bid/ Contract No Nation (RFP, Rated stage- on (US$) (Prio proposal Signatur al/ RFB, Criteria single r/ opening e Limited RFQ etc.) envelope Post) etc.) etc.) etc.) Recording Service Event Most Managem 60,000.0 Limited Single 20/June/2 10/July/20 NC3 Prior RFP advantage ent 0 National stage One- 021 21 ous Bid Services Envelop Subtotal 122,00 (Non-consulting) 0.00 Consulting Services. Market Expected Method Expected Contract Estimate Review by Approach Date of Ref (QCBS, Date of Descriptio d Cost Bank (Open- Bid No. LCBCS, Contract n (US$) (Prior/Post) National/ Proposal QBS, DS Signature Limited etc.) Opening Health 4,300,000. C1 Technical Prior Direct DS 01/March/2 30/March/20 00 Partner 021 21 ICT based Community Engagement 20/June/202 10/July/2021 150,000.0 Limited C2 and Prior CQS 1 0 National Feedback (Call Centre) Service 2 Consulting Services. Market Expected Method Expected Contract Estimate Review by Approach Date of Ref (QCBS, Date of Descriptio d Cost Bank (Open- Bid No. LCBCS, Contract n (US$) (Prior/Post) National/ Proposal QBS, DS Signature Limited etc.) Opening Mass Media Activity for 27/June/202 01/August/2 C3 100,000.0 Prior Open National CQS Citizen 1 021 0 Engagement Community Mobilization 100,000.0 27/June/202 01/August/2 C4 Prior Open National CQS for Citizen 0 1 021 Engagement Procuremen DS 01/March/2 01/April/202 C5 t Specialist 180,000 Prior Direct 021 1 MoH Financial Managemen 14/June/202 1/July/2021 C6 180,000 Prior Direct t Specialist DS 1 MoH HR 20/June/202 15/July/2021 Limited C7 Governance 60,000.00 Prior INDV 1 National Advisor Communicat ion and Open 20/June/202 01/August/2 C8 60,000.00 Prior INDV Reporting International 1 021 Specialist Health 28/June/202 01/August/2 Limited C9 Program 70,000.00 Prior INDV 1 021 National Coordinator Subtotal 5,200,00 Consulting service 0.00 3 Consulting Services. Market Expected Method Expected Contract Estimate Review by Approach Date of Ref (QCBS, Date of Descriptio d Cost Bank (Open- Bid No. LCBCS, Contract n (US$) (Prior/Post) National/ Proposal QBS, DS Signature Limited etc.) Opening Grand Total (Goods+ 5,644,00 Non-consulting + 0.00 Consulting Services) 4 PROCUREMENT Somalia : Somalia Recurrent Cost & Reform Financing Project - Phase 3 PLAN General Information Country: Somalia 2021-06-15 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173731 GPN Date: 2021-06-14 Project Name: Somalia Recurrent Cost & Reform Financing Project - Phase 3 Loan / Credit No: IDA / D6580 Federal Government of Somalia Ministry of Finance Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-239594-GO-RFQ / O Component 5: Project Manag Request for Quota Single Stage - One E IDA / D6580 Prior Limited 22,000.00 23,840.00 Signed 2021-06-22 2021-07-28 2021-07-27 2021-08-15 2021-09-10 ffice Equipment for RCRF PIU ement tions nvelope Offices Component 3: Transfers for SO-MOF-238764-GO-RFB / Pr core government functions a Single Stage - One E ocurement of Android Smart IDA / D6580 nd foundational education h Prior Request for Bids Open - National 300,000.00 213,350.00 Signed 2021-06-16 2021-06-16 2021-06-18 2021-06-17 2021-07-16 2021-07-25 2021-08-05 2021-09-07 2021-08-24 2021-09-30 2021-10-08 nvelope Phones with Solar System ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-240070-GO-RFQ / P core government functions a Request for Quota Single Stage - One E urchase of Vehicle (4x4 Doub IDA / D6580 nd foundational education h Prior Limited 40,000.00 0.00 Canceled 2021-07-01 2021-08-19 2021-10-18 tions nvelope le Cabin Pick Up) for MOH PIU ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-240071-GO-RFQ / P core government functions a Request for Quota Single Stage - One E urchase of Office Furniture fo IDA / D6580 nd foundational education h Prior Limited 40,000.00 0.00 Canceled 2021-07-03 2021-08-21 2021-10-05 tions nvelope r MoH PIU ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-243680-GO-RFQ / P core government functions a Request for Quota Single Stage - One E urchase of Vehicle for MoH PI IDA / D6580 nd foundational education h Prior Limited 40,000.00 40,000.00 Signed 2021-07-22 2021-10-06 2021-09-09 2021-10-22 2021-10-24 tions nvelope U ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-244019-GO-RFQ / P core government functions a Request for Quota Single Stage - One E urchase of Office Furniture fo IDA / D6580 nd foundational education h Prior Limited 28,000.00 27,880.00 Signed 2021-07-21 2021-10-13 2021-08-19 2021-10-25 2021-09-09 tions nvelope r MoH PIU ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-244027-GO-RFQ / Pr core government functions a ocurement of Supply and Del Request for Quota Single Stage - One E IDA / D6580 nd foundational education h Prior Limited 13,000.00 24,050.00 Signed 2021-07-22 2021-10-14 2021-08-20 2021-12-21 2021-09-10 ivery of IT Equipment’s for M tions nvelope ealth service delivery mecha oH PIU nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-253188-GO-RFQ / O core government functions a Request for Quota Single Stage - One E ffice Equipment for Hirshabel IDA / D6580 nd foundational education h Prior Limited 17,300.00 0.00 Canceled 2021-09-20 2021-10-23 2021-11-22 tions nvelope le MoH ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-255298-GO-RFQ / S core government functions a Request for Quota Single Stage - One E upply of ICT and Office Equip IDA / D6580 nd foundational education h Prior Limited 9,050.00 9,740.00 Signed 2021-10-06 2022-01-02 2021-11-02 2022-01-26 2022-05-01 tions nvelope ment for HSS - MoH. ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-255302-GO-RFQ / S core government functions a Request for Quota Single Stage - One E upply of Office Furniture for IDA / D6580 nd foundational education h Prior Limited 8,250.00 8,400.00 Signed 2021-10-07 2022-01-02 2021-11-03 2022-01-26 2022-05-02 tions nvelope Hirshabelle State - MoH. ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-258810-GO-RFQ / S Component 3: Transfers for upply of Office furniture and core government functions a Request for Quota Single Stage - One E Equipment for GSS External IDA / D6580 nd foundational education h Prior Limited 18,890.00 17,890.00 Signed 2021-10-29 2022-01-02 2021-11-23 2022-02-27 2021-12-23 tions nvelope Assistance Fiduciary Section ealth service delivery mecha (EAFS) and the GSS - MOH PI nisms in elig ible Federal Me U offices. mber States (FMS) SO-MOF-258815-GO-RFQ / S Component 3: Transfers for upply of ICT for the GSS MoF core government functions a Request for Quota Single Stage - One E External Assistance Fiduciary IDA / D6580 nd foundational education h Prior Limited 16,090.00 16,250.00 Signed 2021-10-29 2022-01-02 2021-11-25 2022-02-25 2021-12-25 tions nvelope Section (EAFS) and the ealth service delivery mecha MOH PIU offices. nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-268882-GO-RFQ / P core government functions a urchase of 4x4 Seven Seater Request for Quota Single Stage - One E IDA / D6580 nd foundational education h Prior Limited 40,000.00 36,500.00 Signed 2021-12-28 2022-03-28 2022-02-11 2022-05-23 2022-03-28 Station Wagon (Toyota Prado tions nvelope ealth service delivery mecha or Equivalent) nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-274468-GO-RFQ / S core government functions a upply of office furniture and Request for Quota Single Stage - One E IDA / D6580 nd foundational education h Prior Limited 25,000.00 24,930.00 Signed 2022-01-31 2022-04-25 2022-02-18 2022-07-27 2022-08-17 equipment for Ministry of Ed tions nvelope ealth service delivery mecha ucation nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-324962-GO-RFQ / S core government functions a upply of Office Furniture and Request for Quota Single Stage - One E Under Imple IDA / D6580 nd foundational education h Prior Limited 21,000.00 0.00 2022-11-13 2022-12-15 2022-12-01 2023-01-15 Equipment for MoF - South W tions nvelope mentation ealth service delivery mecha est nisms in elig ible Federal Me mber States (FMS) Page 1 SO-MOF-332532-GO-RFQ / S Component 5: Project Manag Request for Quota Single Stage - One E Pending Impl upply of Office Furniture and IDA / D6580 Prior Limited 50,000.00 0.00 2022-12-26 2023-02-03 2023-03-20 ement tions nvelope ementation Equipment for RCRF - PIU Offi ce Component 3: Transfers for SO-MOF-354692-GO-RFB / S core government functions a upply and Delivery of Mobile Single Stage - One E Under Imple IDA / D6580 nd foundational education h Prior Request for Bids Open - National 180,000.00 0.00 2023-04-10 2023-05-09 2023-04-15 2023-06-07 2023-05-27 2023-06-11 2023-06-25 2023-08-09 devices, Tablets and Solar Ch nvelope mentation ealth service delivery mecha arging Solutions nisms in elig ible Federal Me mber States (FMS) SO-MOF-362174-GO-RFQ / O Component 5: Project Manag Request for Quota Single Stage - One E ffice Furniture and renovatio IDA / D6580 Prior Limited 20,000.00 0.00 Canceled 2023-05-25 2023-06-16 2023-07-31 ement tions nvelope n for RCRF Office - FGS Component 3: Transfers for SO-MOF-364142-GO-RFQ / S core government functions a Request for Quota Single Stage - One E Pending Impl upply of ICT and equipment f IDA / D6580 nd foundational education h Prior Limited 10,000.00 0.00 2023-06-05 2023-07-11 2023-08-25 tions nvelope ementation or MOECHE - FGS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-364505-GO-RFQ / P Component 5: Project Manag Request for Quota Single Stage - One E Under Imple urchase of Office Furniture a IDA / D6580 Prior Limited 5,200.00 0.00 2023-06-08 2023-07-14 2023-08-28 ement tions nvelope mentation nd Equipment for RCRF Offic e NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-238775-NC-DIR / W Component 4: Citizen Engag IDA / D6580 Prior Direct Selection Direct 12,000.00 14,652.00 Signed 2021-06-16 2021-06-16 2021-06-19 2021-06-17 2021-07-02 2021-12-13 2022-07-02 hatsApp Messaging Services ement and Feedback SO-MOF-238778-NC-RFQ / Tr Component 4: Citizen Engag Request for Quota Single Stage - One E IDA / D6580 Prior Limited 50,000.00 35,595.00 Signed 2021-06-20 2021-06-29 2021-07-23 2021-08-02 2022-07-23 anslation Voice over Recordi ement and Feedback tions nvelope ng Services SO-MOF-238779-NC-RFQ / E Component 5: Project Manag Request for Quota Single Stage - One E IDA / D6580 Prior Limited 60,000.00 69,125.00 Signed 2021-06-19 2021-06-29 2021-07-20 2021-08-08 2021-08-25 vents Management Services ement tions nvelope Component 3: Transfers for SO-MOF-268864-NC-DIR / Ad core government functions a ditional Work on English-Som IDA / D6580 nd foundational education h Prior Direct Selection Direct 135,000.00 131,980.00 Signed 2021-12-18 2022-01-26 2021-12-23 2022-02-17 2022-01-04 2022-03-30 2022-07-03 ali Somali-English Translation ealth service delivery mecha , Voice -Over Recording nisms in elig ible Federal Me mber States (FMS) SO-MOF-299401-NC-RFQ / W Component 4: Citizen Engag Request for Quota Single Stage - One E Pending Impl ritten Translation of Budget R IDA / D6580 Prior Limited 50,000.00 0.00 2022-06-27 2022-08-11 2023-08-11 ement and Feedback tions nvelope ementation eports and Related Documen ts SO-MOF-362638-NC-DIR / Pr Component 3: Transfers for ocurement of Non Consultin core government functions a g Services for a Health Tech nd foundational education h Direct - Internation Under Imple nical Partner (HTP) to Suppor IDA / D6580 Prior Direct Selection 10,746,208.00 0.00 2023-05-22 2023-06-07 2023-05-27 2023-06-15 2023-07-01 2023-12-28 ealth service delivery mecha al mentation t Implementation of Somalia’ nisms in elig ible Federal Me s Female Health Worker Prog mber States (FMS) ram and Capacity Developm ent in Ministries of Health CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-238785-CS-CQS / C Component 4: Citizen Engag Consultant Qualifi all Centre Service for Citizen IDA / D6580 Prior Limited 150,000.00 156,513.65 Signed 2021-06-17 2021-06-16 2021-07-01 2021-07-23 2021-07-22 2021-10-28 2021-08-19 2021-11-14 2021-09-24 ement and Feedback cation Selection Engagement SO-MOF-238789-CS-CQS / C Component 4: Citizen Engag Consultant Qualifi ommunity Mobilization for Cit IDA / D6580 Prior Open - National 100,000.00 0.00 Canceled 2021-06-18 2021-07-02 2021-08-06 2021-08-07 2021-09-04 2022-09-04 ement and Feedback cation Selection izen Engagement SO-MOF-239596-CS-CQS / M Component 4: Citizen Engag Consultant Qualifi ass Media Activity for Citizen IDA / D6580 Prior Open - National 100,000.00 102,824.90 Signed 2021-06-17 2021-08-18 2021-07-05 2021-08-26 2021-08-08 2021-11-11 2021-09-07 2022-01-10 2021-09-28 2022-01-24 2022-09-28 ement and Feedback cation Selection Engagement SO-MOF-246715-CS-CQS / C Component 4: Citizen Engag Consultant Qualifi ommunity Mobilization for Cit IDA / D6580 Prior Open - National 200,000.00 167,070.12 Signed 2021-08-09 2021-08-16 2021-08-23 2021-08-26 2021-09-27 2021-11-03 2021-10-18 2022-01-04 2021-11-15 2022-01-24 2022-11-15 ement and Feedback cation Selection izen Engagement SO-MOF-290903-CS-LCS / In Component 5: Project Manag Least Cost Selecti Open - Internationa Under Implement dependent Verification Agent IDA / D6580 Prior 100,000.00 0.00 2022-04-24 2022-04-29 2022-05-08 2022-05-03 2022-06-19 2022-11-24 2022-06-20 2023-01-18 2022-07-04 2023-04-18 2022-07-12 2023-06-09 2022-07-26 2023-04-22 ement on l ation for RCRF Expenditure Progra m - 2022/2023 SO-MOF-284926-CS-QCBS / Component 4: Citizen Engag Quality And Cost- Open - Internationa Consultant Services for Impr IDA / D6580 Prior 500,000.00 0.00 Canceled 2022-03-21 2022-04-04 2022-04-21 2022-05-21 2022-06-04 2022-06-18 2022-07-09 2023-12-31 ement and Feedback Based Selection l oving Budget Transparency SO-MOF-299399-CS-CQS / T hink Tank for Policy Briefs on Component 4: Citizen Engag Consultant Qualifi Under Implement IDA / D6580 Prior Open - National 100,000.00 0.00 2022-06-16 2022-06-15 2022-07-07 2022-06-20 2022-08-11 2022-12-24 2022-08-18 2022-09-08 2023-09-08 Budget Cycle: Citizen Engage ement and Feedback cation Selection ation ment and Feedback SO-MOF-299400-CS-CQS / S Component 4: Citizen Engag Consultant Qualifi Under Implement upport for Budget Transpare IDA / D6580 Prior Open - National 200,000.00 0.00 2022-06-16 2022-06-15 2022-06-30 2022-06-20 2022-08-04 2022-10-11 2022-08-25 2023-02-16 2022-09-18 2023-09-18 ement and Feedback cation Selection ation ncy under Citizen Engageme nt and Feedback SO-MOF-348226-CS-LCS / Pr Component 5: Project Manag Least Cost Selecti Open - Internationa Under Implement ojects Audit for WB funded Pr IDA / D6580 Prior 250,000.00 0.00 2023-03-20 2023-04-03 2023-03-22 2023-04-12 2023-04-15 2023-04-22 2023-04-28 2023-05-18 2023-06-02 2024-06-01 ement on l ation ojects for 2022 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 SO-MOF-238781-CS-CDS / H Component 3: Transfers for EALTH TECHNICAL PARTNER core government functions a (HTP) TO SUPPORT IMPLEME nd foundational education h NTATION OF SOMALIA FEMAL IDA / D6580 Prior Direct Selection Direct 4,300,000.00 4,268,149.12 Signed 2021-06-16 2021-06-16 2021-06-22 2021-06-24 2021-07-16 2021-07-01 2022-07-16 ealth service delivery mecha E HEALTH WORKER PROGRA nisms in elig ible Federal Me M & CAPACITY DEVELOPMEN mber States (FMS) T IN MINISTRIES OF HEALTH Component 3: Transfers for SO-MOF-238791-CS-CDS / Pr core government functions a ocurement Specialist Consult IDA / D6580 nd foundational education h Prior Direct Selection Direct 180,000.00 254,400.00 Signed 2021-06-16 2021-06-16 2021-06-24 2021-07-11 2021-07-14 2021-08-02 2021-08-19 ing Services ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-238800-CS-INDV / I core government functions a ndependent Verification Age Individual Consult IDA / D6580 nd foundational education h Prior Limited 15,000.00 14,900.00 Signed 2021-06-16 2021-07-23 2021-06-21 2021-08-22 2021-07-01 2021-08-26 2021-07-15 2021-08-29 2021-08-26 nt for RCRF II Expenditure Pr ant Selection ealth service delivery mecha ogram - Individual Consultant nisms in elig ible Federal Me mber States (FMS) SO-MOF-239592-CS-INDV / H Component 2: Strengthen in uman Resource Governance Individual Consult IDA / D6580 ter-governmental fiscal relat Prior Limited 70,000.00 129,360.00 Signed 2021-06-16 2021-06-16 2021-06-21 2021-07-29 2021-07-05 2021-08-04 2021-07-19 2021-08-06 2022-07-19 Advisor for National Civil Ser ant Selection ions vice Commission Component 3: Transfers for SO-MOF-239593-CS-CDS / Fi core government functions a nancial Management Speciali IDA / D6580 nd foundational education h Prior Direct Selection Direct 200,000.00 0.00 Canceled 2021-06-16 2021-06-16 2021-06-21 2021-07-12 2021-07-12 2022-07-12 st for Ministry of Health ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-240056-CS-CDS / PF Component 5: Project Manag MRCU Financial Management IDA / D6580 Prior Direct Selection Direct 55,000.00 0.00 Canceled 2021-06-19 2021-06-29 2021-08-12 2022-08-12 ement Specialist Services SO-MOF-240057-CS-CDS / S Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 85,000.00 0.00 Canceled 2021-06-19 2021-06-29 2021-07-20 2022-07-20 enior Financial Management ement Consultant Component 3: Transfers for SO-MOF-240062-CS-INDV / S core government functions a Individual Consult enior RCRF Health Focal Poin IDA / D6580 nd foundational education h Prior Open 70,000.00 76,800.00 Signed 2021-06-22 2021-06-29 2021-08-09 2021-11-14 2021-08-23 2022-02-02 2021-09-20 2022-02-23 2022-09-20 ant Selection t ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-240064-CS-INDV / S core government functions a Individual Consult enior Monitoring and Evaluati IDA / D6580 nd foundational education h Prior Open 70,000.00 67,440.00 Signed 2021-06-26 2021-06-28 2021-08-05 2021-10-28 2021-08-26 2021-11-11 2021-09-23 2021-11-29 2022-09-23 ant Selection on Specialist ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-240067-CS-CDS / G Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 55,000.00 121,880.00 Signed 2021-06-20 2021-06-28 2021-06-30 2021-07-20 2021-07-21 2021-08-03 2022-07-21 almudug RCRF Project Manag ement er SO-MOF-240068-CS-CDS / Ex Component 5: Project Manag ternal Financing Coordination IDA / D6580 Prior Direct Selection Direct 50,000.00 104,400.00 Signed 2021-06-19 2021-07-13 2021-06-29 2021-07-20 2021-07-20 2021-07-29 2022-07-20 ement Specialist SO-MOF-241523-CS-CDS / H Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 31,800.00 60,480.00 Signed 2021-06-30 2021-06-30 2021-07-06 2021-07-20 2021-07-28 2021-07-23 2022-07-28 SS Community Health Coordi ement nator SO-MOF-241524-CS-CDS / H Component 5: Project Manag SS Contracts Management a IDA / D6580 Prior Direct Selection Direct 31,800.00 60,480.00 Signed 2021-06-30 2021-06-30 2021-07-10 2021-07-20 2021-07-25 2021-07-20 2022-07-25 ement nd M&E Specialist SO-MOF-244091-CS-CDS / E Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 55,000.00 117,220.00 Signed 2021-07-17 2021-07-28 2021-07-27 2021-08-03 2021-08-18 2021-08-09 2022-08-18 AFS Financial Management C ement onsultant SO-MOF-244094-CS-CDS / R Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 85,000.00 171,960.00 Signed 2021-07-17 2021-07-28 2021-07-27 2021-08-02 2021-08-15 2021-09-03 2021-09-20 CRF Financial Management C ement onsultant SO-MOF-245179-CS-CDS / R Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 88,000.00 174,960.00 Signed 2021-07-27 2021-08-19 2021-08-06 2021-09-06 2021-09-01 2021-09-12 2022-09-01 CRF Project Coordinator ement SO-MOF-246702-CS-CDS / R Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 50,000.00 102,120.00 Signed 2021-08-07 2021-08-17 2021-08-17 2021-08-22 2021-09-12 2021-09-12 2022-09-12 CRF Program Officer ement Component 3: Transfers for SO-MOF-246709-CS-INDV / F core government functions a Individual Consult Under Implement inancial and Accounting Tech IDA / D6580 nd foundational education h Prior Open 50,000.00 0.00 2021-08-09 2021-08-17 2021-09-27 2021-10-11 2021-11-08 2021-12-14 ant Selection ation nical Assistant ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-246711-CS-INDV / H core government functions a Individual Consult R and Administration Technic IDA / D6580 nd foundational education h Prior Open 50,000.00 0.00 Canceled 2021-08-09 2021-08-25 2021-08-30 2021-09-20 2021-10-18 2022-10-18 ant Selection al Assistant ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-246712-CS-INDV / P core government functions a Individual Consult rocurement Technical Assista IDA / D6580 nd foundational education h Prior Open 50,000.00 60,280.00 Signed 2021-08-09 2021-08-17 2021-09-18 2022-01-25 2021-10-09 2022-02-02 2021-11-06 2022-02-07 2022-11-06 ant Selection nt ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-248385-CS-CDS / C core government functions a ommunity Health Coordinato IDA / D6580 nd foundational education h Prior Direct Selection Direct 30,240.00 60,480.00 Signed 2021-08-18 2021-08-19 2021-08-28 2021-08-23 2021-09-19 2021-08-31 2022-09-19 r for Jubbaland State ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-253451-CS-CDS / M core government functions a OH Financial Management Sp IDA / D6580 nd foundational education h Prior Direct Selection Direct 200,000.00 216,000.00 Signed 2021-09-17 2021-10-06 2021-09-25 2021-10-08 2021-10-23 2021-10-28 2022-10-23 ecialist ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-257038-CS-CDS / E Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 55,000.00 110,880.00 Signed 2021-10-11 2021-10-20 2021-10-21 2021-10-27 2021-11-07 2021-11-02 2022-11-07 AFS Financial Management S ement pecialist 1 SO-MOF-257049-CS-CDS / E Component 5: Project Manag Under Implement IDA / D6580 Prior Direct Selection Direct 62,000.00 0.00 2021-10-11 2021-10-20 2021-10-21 2021-11-16 2022-11-16 AFS Financial Management S ement ation pecialist 2 Page 3 Component 3: Transfers for SO-MOF-259508-CS-CDS / Ju core government functions a bbaland Contract Manageme IDA / D6580 nd foundational education h Prior Direct Selection Direct 35,000.00 34,200.00 Signed 2021-10-24 2021-11-01 2021-11-03 2021-11-02 2021-11-24 2021-11-08 2022-11-24 nt, Monitoring & Evaluation S ealth service delivery mecha pecialist nisms in elig ible Federal Me mber States (FMS) SO-MOF-263366-CS-INDV / S Component 5: Project Manag Individual Consult IDA / D6580 Prior Limited 40,000.00 0.00 Canceled 2021-11-22 2021-11-19 2021-11-27 2021-12-11 2022-01-08 2022-07-07 ecurity Risk Management Co ement ant Selection nsultant SO-MOF-264788-CS-CDS / PF Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 80,000.00 73,420.00 Signed 2021-11-30 2021-11-29 2021-12-08 2021-12-07 2021-12-27 2022-01-20 2022-12-27 MRCU Office Secretary ement SO-MOF-264796-CS-CDS / G Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 61,000.00 65,880.00 Signed 2021-11-27 2021-12-22 2021-12-07 2021-12-25 2021-12-24 2022-01-26 2022-12-24 ender Based Violence (GBV) ement Expert SO-MOF-264800-CS-CDS / Fi Component 2: Strengthen in IDA / D6580 Prior Direct Selection Direct 98,980.00 98,980.00 Signed 2021-11-27 2021-12-06 2021-12-07 2022-02-16 2021-12-27 2022-03-08 2022-12-27 scal Federalism Expert ter-governmental fiscal relat ions SO-MOF-264804-CS-CDS / As Component 2: Strengthen in sistant to Extended Credit Fa IDA / D6580 ter-governmental fiscal relat Prior Direct Selection Direct 74,000.00 73,420.00 Signed 2021-11-27 2021-11-29 2021-12-08 2021-12-11 2021-12-26 2022-01-10 2022-12-26 cility Coordinator ions SO-MOF-264807-CS-CDS / S Component 2: Strengthen in ecretary 3 Intergovernmental IDA / D6580 ter-governmental fiscal relat Prior Direct Selection Direct 40,000.00 39,840.00 Signed 2021-11-27 2021-12-01 2021-12-07 2021-12-11 2021-12-27 2022-01-12 2022-12-27 Fiscal Federalism Secretariat ions SO-MOF-264808-CS-CDS / S Component 2: Strengthen in ecretary 1 Intergovernmental IDA / D6580 ter-governmental fiscal relat Prior Direct Selection Direct 40,000.00 39,840.00 Signed 2021-11-27 2021-12-01 2021-12-05 2021-12-11 2021-12-26 2022-01-12 2022-12-26 Fiscal Federalism Secretariat ions SO-MOF-265944-CS-CDS / S Component 5: Project Manag ocial Safeguarding Specialist, IDA / D6580 Prior Direct Selection Direct 15,780.00 18,600.00 Signed 2021-12-04 2021-12-07 2021-12-12 2021-12-08 2021-12-31 2022-01-09 2022-12-31 ement for Jubbaland SO-MOF-266896-CS-CDS / S Component 5: Project Manag ocial Safeguarding Specialist, IDA / D6580 Prior Direct Selection Direct 18,000.00 18,000.00 Signed 2021-12-08 2021-12-07 2021-12-17 2021-12-08 2021-12-31 2021-12-25 2022-12-31 ement for Galnudug State SO-MOF-267657-CS-CDS / S Component 5: Project Manag ocial Safeguard Specialist -So IDA / D6580 Prior Direct Selection Direct 24,000.00 24,000.00 Signed 2021-12-12 2021-12-16 2021-12-20 2021-12-19 2021-12-31 2021-12-24 2022-12-31 ement uthwest State, Somalia Component 3: Transfers for core government functions a SO-MOF-268873-CS-INDV / E Individual Consult IDA / D6580 nd foundational education h Prior Open 65,000.00 61,920.00 Signed 2021-12-20 2022-01-14 2022-02-07 2022-04-14 2022-02-21 2022-04-21 2022-03-17 2022-04-24 2023-03-17 MIS Data Analyst/Specialist ant Selection ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-270404-CS-CDS / S Component 5: Project Manag ocial Safeguards Specialists- IDA / D6580 Prior Direct Selection Direct 18,000.00 18,000.00 Signed 2021-12-23 2021-12-25 2021-12-27 2021-12-28 2022-01-02 2021-12-29 2023-01-02 ement Hirshabelle State of Somalia SO-MOF-272465-CS-CDS / S Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 56,000.00 57,700.00 Signed 2022-01-12 2022-01-11 2022-01-18 2022-01-27 2022-01-31 2022-02-06 2023-01-31 WSS RCRF III Project Manage ement r Component 3: Transfers for SO-MOF-275267-CS-INDV / H core government functions a uman Resource/Civil Service Individual Consult IDA / D6580 nd foundational education h Prior Direct 55,000.00 26,160.00 Signed 2022-02-03 2022-03-02 2022-02-09 2022-03-15 2022-02-14 2022-03-21 2022-02-24 2022-04-18 2023-02-24 Advisor for Civil Service Com ant Selection ealth service delivery mecha mission of FMSs nisms in elig ible Federal Me mber States (FMS) SO-MOF-276050-CS-CDS / Hi Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 55,000.00 51,630.00 Under Review 2022-02-03 2022-02-15 2022-02-08 2022-02-16 2022-02-21 2022-03-05 2023-02-21 rshabelle RCRF III Project Ma ement nager SO-MOF-276052-CS-INDV / S Component 5: Project Manag Individual Consult IDA / D6580 Prior Open 40,000.00 54,700.00 Signed 2022-02-03 2022-02-15 2022-02-27 2022-05-14 2022-03-09 2022-05-20 2022-03-19 2022-06-02 2022-09-15 ecurity Risk Management Co ement ant Selection nsultant SO-MOF-279657-CS-INDV / S Component 5: Project Manag Individual Consult IDA / D6580 Prior Limited 50,000.00 49,920.00 Signed 2022-02-21 2022-03-07 2022-02-26 2022-04-20 2022-03-19 2022-04-29 2022-04-12 2022-05-22 2023-04-12 ocial Safeguard Specialist ement ant Selection SO-MOF-281899-CS-CDS / Ju bbaland RCRF III Project Man ager. The Consultant was co Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 90,480.00 90,480.00 Signed 2022-03-05 2022-03-17 2022-03-10 2022-03-21 2022-03-19 2022-05-18 2023-03-19 ntracted for this position und ement er RCRF II and is being move d to RCRF III under same ter ms and conditions. SO-MOF-284568-CS-CDS / R Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 74,000.00 73,380.00 Signed 2022-03-19 2022-04-13 2022-03-23 2022-04-21 2022-03-30 2022-05-08 2023-03-30 CRF Education Coordinator ement SO-MOF-284574-CS-CDS / S Component 5: Project Manag enior Adviser - Intergovernm IDA / D6580 Prior Direct Selection Direct 72,000.00 71,600.00 Signed 2022-03-19 2022-03-29 2022-03-24 2022-04-03 2022-03-31 2022-04-24 2023-03-31 ement ental Education Forum Com mittee) (IGEFC) SO-MOF-284579-CS-CDS / Pr Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 59,000.00 58,900.00 Signed 2022-03-19 2022-03-21 2022-03-24 2022-04-06 2022-04-04 2022-04-22 2023-04-04 oject Administrative Assistan ement t SO-MOF-284835-CS-CDS / S Component 5: Project Manag ecretary 4, Inter-Government IDA / D6580 Prior Direct Selection Direct 39,840.00 39,840.00 Signed 2022-03-19 2022-03-21 2022-03-29 2022-03-22 2022-04-09 2022-05-15 2023-04-09 ement al Federalism SO-MOF-284840-CS-CDS / E Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 62,800.00 63,240.00 Signed 2022-03-19 2022-03-28 2022-03-25 2022-03-29 2022-04-07 2022-04-22 2022-04-10 AFS Financial Management S ement pecialist SO-MOF-284894-CS-CDS / H Component 3: Transfers for uman Resource and Civil Ser core government functions a vant Advisor for Hirshabelle S IDA / D6580 nd foundational education h Prior Direct Selection Direct 30,000.00 26,160.00 Signed 2022-03-20 2022-03-28 2022-03-30 2022-03-31 2022-04-12 2022-04-17 2022-10-09 tate Civil Service Commissio ealth service delivery mecha n. nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-284921-CS-CDS / H core government functions a ealth Technical Partner for Fe IDA / D6580 nd foundational education h Prior Direct Selection Direct 5,000,000.00 4,700,000.00 Signed 2022-03-21 2022-04-06 2022-03-31 2022-04-13 2022-04-13 2022-06-02 2023-01-08 male Health Worker Program ealth service delivery mecha . nisms in elig ible Federal Me mber States (FMS) SO-MOF-284562-CS-CDS / N Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 67,800.00 65,020.00 Signed 2022-03-19 2022-03-30 2022-03-25 2022-04-03 2022-04-06 2022-04-22 2023-04-06 ational Procurement Speciali ement st Page 4 SO-MOF-284853-CS-CDS / R Component 5: Project Manag IDA / D6580 Post Direct Selection Direct 87,720.00 0.00 Canceled 2022-03-19 2022-03-27 2022-04-09 2022-05-15 CRF Financial Management C ement onsultant Component 3: Transfers for SO-MOF-287023-CS-INDV / C core government functions a Individual Consult ommunity Health Coordinato IDA / D6580 nd foundational education h Prior Direct 30,240.00 30,240.00 Signed 2022-04-02 2022-04-20 2022-04-09 2022-04-26 2022-04-14 2022-05-02 2022-04-22 2022-05-22 2023-04-22 ant Selection r Southwest ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-287027-CS-CDS / C core government functions a ontracts Management and M IDA / D6580 nd foundational education h Prior Direct Selection Direct 30,240.00 30,240.00 Signed 2022-04-02 2022-04-20 2022-04-09 2022-04-26 2022-04-22 2022-05-20 2023-04-22 &E Specialist –MoH SWSS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-287034-CS-CDS / C core government functions a ommunity Health Coordinato IDA / D6580 nd foundational education h Prior Direct Selection Direct 56,000.00 56,520.00 Signed 2022-04-02 2022-04-20 2022-04-12 2022-04-27 2022-04-25 2022-05-21 2023-04-25 r, MoH – FGS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-287219-CS-INDV / A core government functions a Individual Consult Under Implement ssessment of Female particip IDA / D6580 nd foundational education h Prior Limited 15,000.00 0.00 2022-04-02 2022-04-08 2022-04-07 2022-11-14 2022-04-28 2022-11-29 2022-05-26 2022-07-25 ant Selection ation ation in Teaching. ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for core government functions a SO-MOF-288270-CS-CDS / D IDA / D6580 nd foundational education h Prior Direct Selection Direct 43,440.00 43,440.00 Signed 2022-04-06 2022-04-20 2022-04-12 2022-04-27 2022-04-25 2022-05-21 2023-04-25 ata Analyst – MoH – FGS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-288274-CS-CDS / C core government functions a ommunity Health Coordinato IDA / D6580 nd foundational education h Prior Direct Selection Direct 30,240.00 30,240.00 Signed 2022-04-06 2022-04-20 2022-04-12 2022-05-04 2022-04-27 2022-05-26 2023-04-27 r -GSS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-288420-CS-CDS / C Component 5: Project Manag ustoms Automated System L IDA / D6580 Prior Direct Selection Direct 50,000.00 49,970.00 Signed 2022-04-07 2022-04-08 2022-04-13 2022-04-21 2022-04-26 2022-05-23 2022-06-10 ement ead Consultant SO-MOF-288421-CS-CDS / Pu Component 2: Strengthen in blic Financial Management (P IDA / D6580 ter-governmental fiscal relat Prior Direct Selection Direct 55,000.00 50,900.00 Signed 2022-04-07 2022-04-19 2022-04-13 2022-05-05 2022-04-28 2022-06-08 2022-10-25 FM) Reform Expert ions SO-MOF-288422-CS-CDS / Ac Component 2: Strengthen in counting and Financial Mana IDA / D6580 ter-governmental fiscal relat Prior Direct Selection Direct 90,000.00 86,640.00 Signed 2022-04-07 2022-04-12 2022-04-13 2022-04-23 2022-04-28 2022-05-17 2023-04-28 gement Technical Assistant ions Component 3: Transfers for SO-MOF-290902-CS-INDV / H core government functions a uman Resource & Administra Individual Consult IDA / D6580 nd foundational education h Prior Open 50,000.00 0.00 Signed 2022-04-23 2022-04-26 2022-06-07 2022-10-03 2022-06-17 2022-10-11 2022-07-11 2023-06-07 2023-07-11 tion Technical Assistant, Mini ant Selection ealth service delivery mecha stry of Education nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-292062-CS-INDV / C core government functions a ontract Management and M& Individual Consult IDA / D6580 nd foundational education h Prior Open 30,240.00 30,240.00 Signed 2022-04-28 2022-04-29 2022-05-22 2022-08-28 2022-05-23 2022-09-05 2022-06-07 2022-09-02 2023-06-07 E Specialist - Galmudug Stat ant Selection ealth service delivery mecha e of Somalia nisms in elig ible Federal Me mber States (FMS) SO-MOF-284871-CS-CDS / Ac counting and Financial Mana Component 5: Project Manag IDA / D6580 Post Direct Selection Direct 86,640.00 0.00 Canceled 2022-03-20 2022-03-26 2022-04-08 2023-04-08 gement Technical Advisor - O ement ffice of the Accountant Gener al. Component 3: Transfers for SO-MOF-299395-CS-INDV / I core government functions a Individual Consult Under Implement nternal Audit Technical Assist IDA / D6580 nd foundational education h Prior Open 55,000.00 0.00 2022-06-16 2022-06-15 2022-08-04 2022-08-11 2022-09-01 2023-09-01 ant Selection ation ant for MoH - FGS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-299397-CS-INDV / D core government functions a Individual Consult Under Implement igital Health Coordinator for IDA / D6580 nd foundational education h Prior Open 55,000.00 0.00 2022-06-16 2022-06-14 2022-08-04 2022-08-11 2022-09-01 2023-09-01 ant Selection ation MoH, FGS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-257051-CS-INDV / E Component 5: Project Manag Individual Consult IDA / D6580 Prior Open 50,000.00 0.00 Canceled 2021-10-11 2021-10-20 2021-11-20 2021-12-04 2021-12-25 2022-12-25 AFS Risk Management Specia ement ant Selection list SO-MOF-301510-CS-CDS / Pr Component 5: Project Manag ocurement Specialist/Technic IDA / D6580 Post Direct Selection Direct 100,000.00 0.00 Canceled 2022-06-28 2022-07-19 2022-07-06 2022-07-19 2023-07-19 ement al Assistant SO-MOF-312477-CS-INDV / P Component 5: Project Manag Individual Consult Open - Internationa rocurement Specialist/Techni IDA / D6580 Prior 180,000.00 0.00 Signed 2022-09-03 2022-09-23 2022-10-07 2023-02-22 2022-10-12 2023-03-01 2022-10-25 2023-06-07 2023-10-25 ement ant Selection l cal Assistant SO-MOF-299402-CS-INDV / C Component 5: Project Manag Individual Consult Under Implement ommunications Specialist for IDA / D6580 Prior Limited 50,000.00 0.00 2022-09-13 2022-10-24 2022-09-19 2022-09-29 2022-10-14 2023-10-14 ement ant Selection ation RCRF Project SO-MOF-325518-CS-INDV / F Component 2: Strengthen in Individual Consult IDA / D6580 Prior Open - National 70,000.00 0.00 Signed 2022-11-13 2022-11-21 2022-12-12 2023-02-26 2022-12-22 2023-03-01 2023-01-06 2023-06-07 2024-01-06 ederalism Adviser ter-governmental fiscal relat ant Selection ions Component 3: Transfers for SO-MOF-330993-CS-INDV / J core government functions a Individual Consult Under Implement ubbaland Community Health IDA / D6580 nd foundational education h Prior Open - National 30,240.00 0.00 2022-12-14 2022-12-24 2023-01-12 2023-04-13 2023-01-22 2023-04-17 2023-02-04 2024-02-04 ant Selection ation Coordinator ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-330988-CS-INDV / T Component 5: Project Manag Individual Consult Under Implement IDA / D6580 Prior Limited 59,000.00 0.00 2022-12-15 2022-12-14 2022-12-20 2023-02-04 2022-12-30 2023-02-09 2023-01-14 2024-01-14 echnical Administrative Assis ement ant Selection ation tant SO-MOF-330991-CS-INDV / R Component 5: Project Manag Individual Consult eform Reporting and Perform IDA / D6580 Prior Direct - National 74,000.00 0.00 Signed 2022-12-15 2022-12-15 2022-12-25 2022-12-21 2023-01-04 2023-01-11 2023-01-19 2023-06-07 2024-01-19 ement ant Selection ance Specialist Page 5 Component 3: Transfers for SO-MOF-337754-CS-CDS / Hi core government functions a Under Implement rshabelle Social Safeguards S IDA / D6580 nd foundational education h Prior Direct Selection Direct - National 18,000.00 0.00 2023-01-25 2023-01-30 2023-01-29 2023-02-02 2023-02-06 2024-02-06 ation pecialist ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-337757-CS-CDS / S core government functions a Under Implement ocial Safeguards Specialist -S IDA / D6580 nd foundational education h Prior Direct Selection Direct - National 24,000.00 0.00 2023-01-25 2023-01-31 2023-01-29 2023-02-04 2023-02-05 2024-02-05 ation outh West State ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-346749-CS-CDS / IC Component 4: Citizen Engag Under Implement T-Based Call Center Services IDA / D6580 Prior Direct Selection Direct - National 450,000.00 0.00 2023-03-04 2023-03-25 2023-03-11 2023-04-24 2023-04-05 2024-09-26 ement and Feedback ation for Citizen Engagement and Feedback SO-MOF-354687-CS-INDV / S Component 5: Project Manag Individual Consult Under Implement enior Social and Gender Bas IDA / D6580 Prior Open - National 61,000.00 0.00 2023-04-06 2023-04-17 2023-05-01 2023-05-11 2023-05-26 2024-05-25 ement ant Selection ation ed Violence Specialist Component 3: Transfers for SO-MOF-356886-CS-INDV / A core government functions a dmin and Finance Specialist - IDA / D6580 nd foundational education h Prior Direct Selection Direct - National 36,000.00 0.00 Signed 2023-04-27 2023-05-18 2023-05-05 2023-05-27 2023-05-30 2023-06-20 2024-05-29 MoH ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-369294-CS-INDV / P Component 5: Project Manag Individual Consult Under Implement rocurement of Individual Con IDA / D6580 Prior Open - National 60,000.00 0.00 2023-06-30 2023-06-29 2023-08-18 2023-09-08 2023-10-13 2024-04-10 ement ant Selection ation sultant: Security Specialist Page 6 PROCUREMENT PLAN (Textual Part) Project Country: Kyrgyz Republic information Full Project Name: CASA 1000 Community Support Project Total Finance ($): $10.0 million (IDA) $1.0 million (CASA1000-MDTF) Project Number: P163592 Project Implementation agency ARIS Date of the Procurement Plan February 1, 2018 Period covered by this Procurement February 1, 2018 - 2023 Plan: Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), procurement under World Bank financed operations may be carried out in accordance with “Single-Stage Bidding” method set forth in the Public Procurement Law of the Kyrgyz Republic dated April 3, 2015 № 72 (the “PPL”) with amendments dated November 18, 2016 N 182, December 10, 2016 N 195, February 14, 2017 N 25, May 30, 2017 N 93, provided that such arrangements continue to meet requirements of the paragraph 5.4 of the Procurement Regulations and the following conditions: • The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; • Bidding documents, including contract forms, acceptable to the Bank shall be used. • The Bidding process shall not be cancelled sole on the reason that minimum bid price is larger than the amount allocated by procuring entity for this procurement. • There shall be no preference applied during procurement of goods and works. • Implementing agency shall have an option to publish procurement notice without disclosing cost estimate. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Other national procurement arrangements such as “Simplified Method” (Request for Quotation) may be applied on the same conditions stated above for procuring limited quantities of ready available off-the-shelf goods or simple civil works of small value. In addition, not less than three quotations shall be requested to ensure competition. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable Other Relevant Procurement Information. The CDD approach and procurement by the communities will follow Procurement Regulations paragraph 6.52 and Annex XII - Selection Methods, paragraphs 6.9 and 6.10. The procurement arrangements at the community level (including procurement responsibilities, procedures, disclosure requirements and sample documentation) and the oversight mechanisms described in Subcomponent 2B will be detailed in the POM. Community procurement will follow the Community Procurement Handbook and the Guidance Note for Design and Management of Procurement Responsibilities in Community Driven Development Projects (March 15, 2012). PROCUREMENT Central Asia : CASA1000 Community Support Project - Kyrgyz Republic PLAN General Information Country: Central Asia 2020-04-09 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163592 GPN Date: 2020-09-10 Project Name: CASA1000 Community Support Project - Kyrgyz Republic Loan / Credit No: IDA / D2940, IDA / 62190, IDA / 67560 Community Development and Investment Agency Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Request for B ARIS-CSP-AF-WORKS-RFB-20 Support for community-led i ids - Small W 22-2 / Renewal works of Villa Single Stage - One E Under Imple 2022-12-0 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 2022-02-15 2022-02-11 2022-02-22 2022-02-15 2022-04-05 2022-03-28 2022-05-05 2022-05-12 2022-06-09 ge ambulatories of Noken ray nvelope mentation 6 onomic infrastructure nvelope proc on of Jalal-Abad oblast ess) Request for B ARIS-CSP-AF-WORKS-RFB-20 Support for community-led i ids - Small W 22-1 / Renewal works of Villa Single Stage - One E 2022-11-2 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-02-01 2022-02-04 2022-02-08 2022-02-15 2022-03-22 2022-03-22 2022-04-21 2022-05-10 2022-05-26 ge ambulatories of Kadamjai nvelope 2 onomic infrastructure nvelope proc & Leilek rayons of Batken obl ess) ast Request for B ARIS-CSP-AF-WORKS-RFB-20 Support for community-led i ids - Small W 22-4 / Renewal works of Villa Single Stage - One E 2023-01-0 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2022-03-15 2022-03-22 2022-05-03 2022-06-02 2022-07-07 ge ambulatories of Bazar-Kor nvelope 3 onomic infrastructure nvelope proc gon rayon of Jalal-Abad oblas ess) t Request for B ARIS-CSP-AF-WORKS-RFB-20 Support for community-led i ids - Small W 22-3 / Renewal works of Villa Single Stage - One E 2022-12-2 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2022-03-01 2022-03-08 2022-04-19 2022-05-19 2022-06-23 ge ambulatories of Suzak ray nvelope 0 onomic infrastructure nvelope proc ons of Jalal-Abad oblast ess) Request for B ARIS-CSP-AF-WORKS-RFB-20 Support for community-led i ids - Small W 22-5 / Renewal works of Villa Single Stage - One E 2022-12-2 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-03-18 2022-03-18 2022-03-25 2022-03-18 2022-04-26 2022-04-19 2022-05-26 2022-05-14 2022-06-30 ge ambulatories of Suzak & nvelope 7 onomic infrastructure nvelope proc Bazar-Korgon rayons of Jalal- ess) Abad oblast Request for B ARIS-CSP-AF-WORKS-RFB-20 Support for community-led i ids - Small W 22-6 / Renewal works of Villa Single Stage - One E 2023-01-2 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-04-15 2022-04-14 2022-04-22 2022-05-24 2022-05-17 2022-06-23 2022-07-11 2022-07-28 ge ambulatories of Nookat, U nvelope 4 onomic infrastructure nvelope proc zgen & Kara Suu rayons of O ess) sh oblast Request for ARIS-CSP-AF-WORKS-RFQ-20 Quotations - Support for community-led i 22-02 / Renewal works of Vill Request for Quota Single Stage - One E Small Works 2023-02-1 IDA / D2940 nvestments in social and ec Post Open - National 0.00 Signed 2022-06-01 2022-06-14 2022-08-22 age ambulatories of Nookat, tions nvelope (Emergency) 8 onomic infrastructure Uzgen & Kara Suu rayons of SPD -Compet Osh oblast itive Request for ARIS-CSP-AF-WORKS-RFQ-20 Quotations - Support for community-led i 22-03 / Renewal works of Vill Request for Quota Single Stage - One E Small Works 2023-02-1 IDA / D2940 nvestments in social and ec Post Open - National 0.00 Signed 2022-06-01 2022-06-14 2022-08-22 age ambulatories of Kadamja tions nvelope (Emergency) 8 onomic infrastructure i & Leilek rayons of Batken o SPD -Compet blast itive Request for ARIS-CSP-WORKS-RFQ-2022- Quotations - Support for community-led i 01 / Installation of street light Request for Quota Single Stage - One E Small Works 2023-02-2 IDA / 67560 nvestments in social and ec Post Open - National 0.00 Signed 2022-05-25 2022-06-05 2022-08-28 ing in Jany-Jer and Koltso villa tions nvelope (Emergency) 4 onomic infrastructure ges in Batken oblast SPD -Compet itive Request for ARIS-CSP-AF-WORKS-RFQ-20 Quotations - Support for community-led i 22-06 / Renewal works of Vill Request for Quota Single Stage - One E Small Works 2023-02-2 IDA / D2940 nvestments in social and ec Post Open - National 0.00 Signed 2022-06-05 2022-07-19 2022-08-26 age ambulatories of Nookat, tions nvelope (Emergency) 2 onomic infrastructure Uzgen & Kara Suu rayons of SPD -Compet Osh oblast itive Request for B ARIS-CASA-CSP-WORKS-RFB- Support for community-led i ids - Small W Single Stage - One E 2023-03-2 2022-09 / Renewal works of v IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-06-28 2022-06-15 2022-07-05 2022-07-20 2022-08-04 2022-08-18 2022-09-03 2022-09-10 2022-09-23 nvelope 2 illage ambulatories onomic infrastructure nvelope proc ess) Request for B ARIS-CASA-CSP-WORKS-RFB- Support for community-led i ids - Small W Single Stage - One E 2023-03-2 2022-10 / Renewal works of s IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-06-29 2022-06-01 2022-07-06 2022-07-20 2022-08-05 2022-08-18 2022-09-04 2022-09-12 2022-09-24 nvelope 3 chools and irrigation system onomic infrastructure nvelope proc ess) ARIS-CSP-AF-WORKS-RFB-20 22-07 / Renewal works of Vill Request for B age ambulatories in villages Support for community-led i ids - Small W Single Stage - One E 2023-04-1 Kashkar-Kyshtak & Kyzyl-Sha IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-06-30 2022-07-14 2022-07-07 2022-07-20 2022-08-06 2022-08-17 2022-09-07 2022-08-30 2022-10-12 nvelope 0 rk of Kara-Suu rayon; in villa onomic infrastructure nvelope proc ge Jany-Nookat of Nookat ray ess) on and in the villages Progre ss & Ak-Terek of Uzgen rayon ARIS-CASA-CSP-WORKS-RFB- Request for B 2022-08 / Procurement of sm Support for community-led i ids - Small W all works on renewal paveme Single Stage - One E 2023-03-2 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-06-27 2022-06-15 2022-07-04 2022-07-20 2022-08-03 2022-08-17 2022-09-02 2022-08-30 2022-09-22 nt in Tash-Korgon village; of i nvelope 1 onomic infrastructure nvelope proc rrigation tray in Alysh village; ess) of schools in Pulgon and Jiyd elik villages Request for ARIS-CSP-WORKS-RFQ-2022- Quotations - Support for community-led i 10 / Procurement of works fo Request for Quota Single Stage - One E Small Works 2023-03-1 IDA / 67560 nvestments in social and ec Post Open - National 0.00 Signed 2022-07-17 2022-06-29 2022-09-17 r installation of street lightin tions nvelope (Emergency) 6 onomic infrastructure g in Jany-Jer village in Batken SPD -Compet oblast itive Request for ARIS-CSP-AF-WORKS-RFQ-20 Quotations - Support for community-led i 22-11 / Renewal works of Vill Request for Quota Single Stage - One E Small Works 2023-04-0 IDA / D2940 nvestments in social and ec Post Open - National 0.00 Signed 2022-07-16 2022-07-20 2022-10-06 age ambulatory in Margun of tions nvelope (Emergency) 4 onomic infrastructure Leilek rayon of Batken oblast SPD -Compet itive ARIS-CSP-AF-WORKS-RFB-20 Request for B 22-11 / Renewal works of Vill Support for community-led i ids - Small W Single Stage - One E 2023-05-1 age ambulatories in Arbyn, Is IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-08-08 2022-08-08 2022-08-15 2022-08-10 2022-09-14 2022-09-06 2022-10-16 2022-10-06 2022-11-20 nvelope 9 anova, Kok-Bel, Kumaidan, T onomic infrastructure nvelope proc emir-Koruk villages of Nookat ess) rayon of Osh oblast Request for ARIS-CASA-CSP-WORKS-RFQ Quotations - Support for community-led i -2022-12 / Renewal works of Request for Quota Single Stage - One E Small Works 2023-05-2 IDA / D2940 nvestments in social and ec Post Open - National 0.00 Signed 2022-08-08 2022-08-10 2022-11-21 school #21 Kan in Soviet vill tions nvelope (Emergency) 0 onomic infrastructure age of Batken oblast SPD -Compet itive Page 1 Request for ARIS-CASA-CSP-WORKS-RFQ Quotations - Support for community-led i -2022-13 / Construction of pl Request for Quota Single Stage - One E Small Works 2023-05-2 IDA / D2940 nvestments in social and ec Post Open - National 0.00 Signed 2022-08-08 2022-08-10 2022-11-21 ayground in the village of Ka tions nvelope (Emergency) 0 onomic infrastructure shka-Terek, Uzgen rayon of SPD -Compet Osh oblast. itive ARIS-CASA-CSP-WORKS-RFB- Request for B 2002-12 / Renovation of irrig Support for community-led i ids - Small W Single Stage - One E Under Imple 2023-06-1 ation ditches in Choyunchu, L IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 2022-08-29 2022-09-01 2022-09-05 2022-09-05 2022-10-05 2022-10-25 2022-12-15 nvelope mentation 3 eilek, Ak-Terek & Korgon villa onomic infrastructure nvelope proc ges of Leilek rayon of Batken ess) oblast ARIS-CASA-CSP-WORKS-RFB- 2022-13 / Renovation works Request for B of school in the village of Kar Support for community-led i ids - Small W a-Suu of Leilek rayon, constr Single Stage - One E 2023-06-3 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-09-15 2022-09-01 2022-09-22 2022-09-05 2022-10-22 2022-10-06 2022-11-11 2022-10-28 2023-01-01 uction of playground in the vi nvelope 0 onomic infrastructure nvelope proc llage of Ak-Say, Borehole drill ess) ing in the village of Ravat, Co nstruction of sidewalk in the city of Sulukta ARIS-CASA-CSP-WORKS-RFB- 2022-14 / Construction of ca Request for B nteen in the school of Kedei- Support for community-led i ids - Small W Aryk village of Suzak rayon / Single Stage - One E 2023-06-3 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-09-15 2022-09-01 2022-09-22 2022-09-06 2022-10-22 2022-10-06 2022-11-11 2022-10-28 2023-01-01 Redevelopment of premises f nvelope 0 onomic infrastructure nvelope proc or additional classrooms for ess) 150 student places in the sch ool of Kok-Bulak village, Bore hole drilling in Bagysh village of Suzak rayon. ARIS-CASA-CSP-CSPAF-WOR KS-RFB-2022-15 / Constructio n of VA in the villages of Kos Request for B h-Korgon and Kyzyl-Kyrman Support for community-led i ids - Small W of Uzgen rayon of Osh oblast Single Stage - One E 2023-06-3 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-09-15 2022-09-01 2022-09-22 2022-09-05 2022-10-22 2022-10-05 2022-11-11 2022-10-24 2023-01-01 (under CSP project). nvelope 0 onomic infrastructure nvelope proc Renewal works of Village am ess) bulatories of Nookat, Uzgen & Kara Suu rayons of Osh ob last (Kara-Tash, Kors-Etti, Kos h-Eter, Kyzyl-Tuu villag ARIS-CASA-CSP-WORKS-RFB- 2022-16 / Street lighting, Con Request for B struction of power lines, Cons Support for community-led i ids - Small W Single Stage - One E 2023-07-0 truction of pump station and IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-09-23 2022-09-19 2022-09-30 2022-09-19 2022-10-30 2022-10-17 2022-11-19 2022-11-11 2023-01-09 nvelope 8 laying of conduit, Constructio onomic infrastructure nvelope proc n of Village Ambulatories, Re ess) pair of kindergarden, Repair of channel and irrigation ditc hes Request for B ARIS-CASA-CSP-WORKS-RFB- Support for community-led i ids - Small W 2022-17 / Small works in Jany Single Stage - One E 2023-07-2 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-10-10 2022-10-10 2022-10-17 2022-10-17 2022-11-16 2022-11-09 2022-12-06 2022-11-10 2023-01-26 -Jer, Kurshab, Kapchygai, Kyz nvelope 5 onomic infrastructure nvelope proc yl-Senir and Kyzyl-Korgon vill ess) ages. ARIS-CASA-CSP-WORKS-RFB- Request for B 2022-18 / Repair and constru Support for community-led i ids - Small W Single Stage - One E Under Imple 2023-08-1 ction works in Kainar, Karatai IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 2022-10-31 2022-10-18 2022-11-07 2022-10-25 2022-12-07 2022-12-27 2023-02-16 nvelope mentation 5 , Ana-Kyzyl, Ak-Say, Kara-Suu onomic infrastructure nvelope proc , Vostochnyi villages and in S ess) uluktu town ARIS-CASA-CSP-WORKS-RFB- 2022-19 / Repair of the irriga Request for B tion well in Doskana village, Support for community-led i ids - Small W Single Stage - One E Under Imple 2023-08-3 pipeline laying for irrigation i IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 2022-11-15 2022-11-07 2022-11-22 2022-11-12 2022-12-22 2023-01-11 2023-03-03 nvelope mentation 0 n Choko-Dobo village, constr onomic infrastructure nvelope proc uction of VA in Uch-Korgon vi ess) llage, irrigation for Kara-Dob o village ARIS-CASA-CSP-WORKS-RFB- Request for B 2022-20 / Asphalt constructio Support for community-led i ids - Small W Single Stage - One E Under Imple 2023-09-1 n in the village of Myrza-Aryk IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 2022-11-30 2022-11-20 2022-12-07 2022-11-24 2023-01-06 2022-12-30 2023-01-26 2023-03-18 nvelope mentation 4 , Sheraly, Karool and constru onomic infrastructure nvelope proc ction of Village ambulatory in ess) the village of Ak-Terek ARIS-CASA-CSP-WORKS-RFB- Request for B 2022-21 / Repair and extensi Support for community-led i ids - Small W Single Stage - One E Under Imple 2023-09-1 on of kindegarten in Kara-Bul IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 2022-11-30 2022-11-20 2022-12-07 2022-11-25 2023-01-06 2023-01-26 2023-03-18 nvelope mentation 4 ak village; Repair of existing i onomic infrastructure nvelope proc rrigation ditch in Ak-Terek an ess) d Leilek villages ARIS-CASA-CSP-AF-WORKS-R Request for B FB-2022-15_RETEN / Repair o Support for community-led i ids - Small W f VA in Kara-Tash village; Rep Single Stage - One E Under Imple 2023-09-1 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 2022-11-30 2022-11-20 2022-12-07 2022-11-25 2023-01-06 2022-12-26 2023-01-26 2023-03-18 air of VA in Kyzyl-Tuu village; nvelope mentation 4 onomic infrastructure nvelope proc Repair of VA in Kors-Etti villa ess) ge; Repair of VA in Kosh-Eter village ARIS-CASA-CSP-WORKS-RFB- Request for B 2022-22 / Construction of a k Support for community-led i ids - Small W Single Stage - One E Under Imple 2023-10-2 indergarten for 50 places on IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 2023-01-09 2023-01-09 2023-01-16 2023-01-15 2023-02-15 2023-02-14 2023-03-07 2023-04-27 nvelope mentation 4 the territory of the kindergart onomic infrastructure nvelope proc en "Aydanek" on Toktogul str ess) eet in the city of Kyzyl-Kiya ARIS-CASA-CSP-WORKS-RFB- 2023-23 / Construction of Vill Request for B age ambulatory (VA) in Valak Support for community-led i ids - Small W Single Stage - One E Under Imple 2023-11-1 ysh village of Kadamjai. Repa IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 2023-01-31 2023-01-27 2023-02-07 2023-01-27 2023-03-09 2023-02-24 2023-03-29 2023-05-19 nvelope mentation 5 ir of potable water supply sys onomic infrastructure nvelope proc tem in Koltso village. Street li ess) ghting in Jinjigen village, Kyz yk-Kyia city ARIS-CASA-CSP-WORKS-RFB- Request for B 2023-24 / Street asphalting i Support for community-led i ids - Small W n Ana-Kyzyl & Shagym villag Single Stage - One E Under Imple 2023-11-2 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 2023-02-07 2023-01-27 2023-02-14 2023-01-27 2023-03-16 2023-02-28 2023-04-05 2023-05-26 es. Reprofiling of building to nvelope mentation 2 onomic infrastructure nvelope proc VA and fencing in Ozgur villa ess) ge. Construction of a playgro und in Chelekchi village. ARIS-CASA-CSP-AFCSP-WOR KS-RFB-2023-25 / Constructio n of park for children in Uch- Request for B Korgon village, Kadamjai ray Support for community-led i ids - Small W on, Batken oblast (CSP). Single Stage - One E Under Imple 2023-12-0 IDA / D2940 nvestments in social and ec Post Request for Bids Open - National orks SPD (1 e 0.00 2023-02-20 2023-02-19 2023-02-27 2023-03-01 2023-03-29 2023-03-27 2023-04-30 2023-06-04 Construction of VA in Baglan nvelope mentation 1 onomic infrastructure nvelope proc village, Nookat rayon, Osh ob ess) last (CSP). Renewal works of VA in Kosh- Eter village, Uzgen rayon, Os h oblast (AF CSP). Page 2 ARIS-CASA-CSP-WORKS-RFQ Request for -2023-28 / Renovation of pol Quotations - es and transformers in the vil Support for community-led i Request for Quota Single Stage - One E Small Works Under Imple 2023-12-2 lage of Ak-Jar of Kara-Suu ray IDA / D2940 nvestments in social and ec Post Open - National 0.00 2023-05-06 2023-04-18 2023-07-01 tions nvelope (Emergency) mentation 8 on of Osh oblast onomic infrastructure SPD -Compet Construction of playground in itive the village of Chelekchi of Yn tymak AO of Nookat rayon ARIS-CASA-CSP-WORKS-RFQ Request for -2023-34 / Repair of existing Quotations - buildings in the village of Ak Support for community-led i Request for Quota Single Stage - One E Small Works Under Imple 2024-01-2 Sai Ak, Sai AA, Batken region IDA / D2940 nvestments in social and ec Post Open - National 0.00 2023-05-20 2023-05-09 2023-07-25 tions nvelope (Emergency) mentation 1 , in the village of Kara Dobo, onomic infrastructure SPD -Compet Masalievsky AA, Kadamjai re itive gion, and in the city of Sulukt a, Batken region Request for ARIS-CASA-CSP-WORKS-RFQ Quotations - Support for community-led i -2023-35 / Construction of ad Request for Quota Single Stage - One E Small Works Under Imple 2024-02-1 IDA / D2940 nvestments in social and ec Post Open - National 0.00 2023-06-12 2023-06-12 2023-08-17 ditional premises to the scho tions nvelope (Emergency) mentation 3 onomic infrastructure ol of Naray village SPD -Compet itive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ARIS-CASA-CSP-GOODS-20-1 Project management, and m Request for Quota Single Stage - One E / procurement of personal pr IDA / 62190 Post Limited 0.00 Canceled 2020-04-22 2020-05-22 2020-06-05 onitoring and evaluation tions nvelope otective equipment for the s outh regions ARIS-CASA-CSP-GOODS-20-2 Support for community-led i /1 / Procurement of personal IDA / 62190 nvestments in social and ec Post Direct Selection Direct 4,000.80 Completed 2020-06-05 2020-06-01 2020-06-05 2020-06-01 2020-06-10 2020-06-02 2020-06-30 2020-06-03 protective equipment for the onomic infrastructure south regions ARIS-CASA-CSP-GOODS-20-2 Support for community-led i /2 / Supply of Personal Protec IDA / 62190 nvestments in social and ec Post Direct Selection Direct 17,627.20 Completed 2020-06-05 2020-06-01 2020-06-05 2020-06-01 2020-06-08 2020-06-03 2020-06-28 2020-06-22 tive Equipment onomic infrastructure ARIS-CASA-CSP-GOODS-20-2 Support for community-led i /3 / Supply of Personal Protec IDA / 62190 nvestments in social and ec Post Direct Selection Direct 11,449.44 Completed 2020-06-05 2020-06-01 2020-06-05 2020-06-01 2020-06-08 2020-06-03 2020-06-28 2020-07-03 tive Equipment for the South onomic infrastructure Regions ARIS-CASA-CSP-GOODS-20-2 Support for community-led i /4 / Procurement of personal IDA / 62190 nvestments in social and ec Post Direct Selection Direct 15,612.88 Completed 2020-06-05 2020-06-01 2020-06-05 2020-06-01 2020-06-08 2020-06-03 2020-06-28 2020-07-22 protective equipment for the onomic infrastructure south regions ARIS-CASA-CSP-GOODS-20-2 Support for community-led i /5 / Procurement of personal IDA / 62190 nvestments in social and ec Post Direct Selection Direct 39,910.41 Completed 2020-06-05 2020-06-01 2020-06-05 2020-06-01 2020-06-08 2020-06-03 2020-06-28 2020-06-21 protective equipment for the onomic infrastructure south regions ARIS-CASA-CSP-GOODS-20-2 Support for community-led i /6 / Procurement of personal IDA / 62190 nvestments in social and ec Post Direct Selection Direct 8,782.24 Terminated 2020-06-05 2020-06-01 2020-06-05 2020-06-01 2020-06-07 2020-06-03 2020-06-27 protective equipment for the onomic infrastructure south regions ARIS-CASA-CSP-GOODS-RFB- Support for community-led i Open - Internationa Single Stage - One E 2020-01 / Procurement of sp IDA / D2940 nvestments in social and ec Post Request for Bids 0.00 Canceled 2020-11-22 2020-11-24 2020-11-27 2020-12-17 2021-01-08 2021-01-12 2021-03-09 2021-02-05 2021-04-13 2021-07-12 l nvelope ecial machinery for electric c onomic infrastructure ompanies ARIS-CASA-CSP-GOODS-RFB- Support for community-led i 2020-01-RETENDER / Procure Open - Internationa Single Stage - One E IDA / D2940 nvestments in social and ec Post Request for Bids 0.00 Canceled 2021-02-22 2021-02-19 2021-02-27 2021-02-18 2021-04-12 2021-04-02 2021-06-11 2021-07-16 2021-10-14 ment of special machinery fo l nvelope onomic infrastructure r energy companies ARIS-CASA-CSP-GOODS-RFB- Support for community-led i 20-01-RETENDER-2 / Procure Open - Internationa Single Stage - One E IDA / D2940 nvestments in social and ec Post Request for Bids 353,700.00 Completed 2021-05-15 2021-05-02 2021-05-22 2021-05-06 2021-07-03 2021-06-18 2021-08-02 2021-07-24 2021-08-16 2021-09-07 2021-11-14 2021-12-29 ment of special machinery fo l nvelope onomic infrastructure r energy companies ARIS-CSP-GOODS-RFB-2021- Support for community-led i 02 / Electric equipment for e Open - Internationa Single Stage - One E IDA / D2940 nvestments in social and ec Post Request for Bids 1,661,547.60 Signed 2021-05-23 2021-05-14 2021-05-30 2021-05-17 2021-07-11 2021-06-25 2021-08-10 2021-07-15 2021-09-16 2021-09-03 2021-12-15 2021-11-22 nergy companies to conduct l nvelope onomic infrastructure the repair of electric distribut ion networks ARIS-CSP-GOODS-RFB-2021- Support for community-led i 03 / Electric equipment for e Open - Internationa Single Stage - One E IDA / D2940 nvestments in social and ec Post Request for Bids 0.00 Canceled 2021-06-10 2021-06-11 2021-06-15 2021-06-11 2021-07-27 2021-07-23 2021-08-26 2021-11-26 2021-10-02 2021-12-31 nergy companies to conduct l nvelope onomic infrastructure the repair of electric distribut ion networks ARIS/CSP/GOODS/RFB/2021/ Support for community-led i 03_RETENDER / Electric equi Open - Internationa Single Stage - One E IDA / D2940 nvestments in social and ec Post Request for Bids 167,433.40 Signed 2021-12-31 2022-01-14 2022-01-07 2022-01-16 2022-02-21 2022-02-28 2022-03-23 2022-03-15 2022-04-27 2022-04-25 2022-10-24 pment for energy companies l nvelope onomic infrastructure to conduct the repair of elect ric distribution networks ARIS-CSP-GOODS-RFB-2022- 08 / Electric equipment for Ja Support for community-led i Open - Internationa Single Stage - One E lalabatelectro to conduct the IDA / D2940 nvestments in social and ec Post Request for Bids 333,061.01 Signed 2022-05-05 2022-04-22 2022-05-10 2022-04-24 2022-06-24 2022-06-03 2022-07-24 2022-06-22 2022-08-28 2022-08-10 2023-02-24 l nvelope repair of electric distribution onomic infrastructure networks under 2 cycle ARIS-CSP-AF-GOODS-RFB-20 Support for community-led i 22-07 / Medical equipment, a Open - Internationa Single Stage - One E IDA / D2940 nvestments in social and ec Post Request for Bids 0.00 Signed 2022-05-02 2022-04-29 2022-05-07 2022-05-03 2022-06-21 2022-06-13 2022-07-05 2022-08-02 2022-08-30 2023-02-26 mbulance and laboratory fur l nvelope onomic infrastructure nuture for Osh, Jalal-Abad an d Batken oblasts ARIS-CASA-CSP-GOODS-RFQ Support for community-led i Request for Quota Single Stage - One E Under Imple -2022-04 / Garbage truck for IDA / 67560 nvestments in social and ec Post Open - National 0.00 2022-05-27 2022-06-05 2022-07-24 2023-01-20 tions nvelope mentation communities onomic infrastructure ARIS-CASA-CSP-GOODS-RFQ Support for community-led i Request for Quota Single Stage - One E Under Imple -2022-05 / Procurement of mi IDA / 67560 nvestments in social and ec Post Open - National 0.00 2022-05-27 2022-06-05 2022-07-24 2023-01-20 tions nvelope mentation nibus onomic infrastructure ARIS-CSP-AF-GOODS-RFQ-20 Support for community-led i 22-07 / Medical equipment & Request for Quota Single Stage - One E IDA / D2940 nvestments in social and ec Post Open - National 0.00 Signed 2022-06-05 2022-07-20 2022-07-31 2023-01-27 furniture for Salam-Alik & Zer tions nvelope onomic infrastructure ger AA of Uzgen rayon of Osh oblast ARIS-CASA-CSP-GOODS-RFQ Support for community-led i Request for Quota Single Stage - One E -2022-08 / Procurement of sp IDA / D2940 nvestments in social and ec Post Open - National 0.00 Canceled 2022-07-04 2022-06-30 2022-09-07 2023-03-06 tions nvelope ecial machinery onomic infrastructure Page 3 ARIS-CASA-CSP-GOODS-RFQ Project management, and m Request for Quota Single Stage - One E -2022-09 / Procurement of of IDA / D2940 Post Open - National 0.00 Signed 2022-07-02 2022-06-30 2022-08-26 2023-02-22 onitoring and evaluation tions nvelope fice equipment ARIS-CASA-CSP-GOODS-RFQ Support for community-led i Request for Quota Single Stage - One E Under Imple -2022-05_RETENDER / Procur IDA / 67560 nvestments in social and ec Post Open - National 0.00 2022-07-16 2022-06-28 2022-09-12 2023-03-11 tions nvelope mentation ement of minibus onomic infrastructure ARIS-CSP-GOODS-RFB-2022- 09 / Procurement of Electric Support for community-led i equipment for Oshtelectro & Open - Internationa Single Stage - One E Under Imple IDA / D2940 nvestments in social and ec Post Request for Bids 0.00 2022-07-11 2022-07-11 2022-07-18 2022-07-16 2022-09-01 2022-08-26 2022-10-01 2022-10-05 2022-11-05 2023-05-04 procurement of transformers l nvelope mentation onomic infrastructure for Jalalabatelectro to repair electric distribution networks under 2 cycle ARIS-CASA-CSP-GOODS-RFQ Support for community-led i Request for Quota Single Stage - One E Under Imple -2022-14 / Rice harvesters fo IDA / D2940 nvestments in social and ec Post Open - National 0.00 2022-08-15 2022-08-22 2022-11-09 2023-05-08 tions nvelope mentation r Chogorok & Tokoi villages onomic infrastructure ARIS-CASA-CSP-GOODS-RFQ -2022-08_RETENDER / Procur Support for community-led i ement of special machinery f Request for Quota Single Stage - One E IDA / D2940 nvestments in social and ec Post Open - National 0.00 Signed 2022-08-15 2022-08-22 2022-11-09 2023-05-08 or Ak-Otok & Shybran village tions nvelope onomic infrastructure s (wheel tractor, baler, plow & wheeled excavator-bulldoz er). ARIS-CSP-AF-GOODS-RFQ-20 22-15 / Computer equipment Project management, and m Request for Quota Single Stage - One E IDA / D2940 Post Open - National 0.00 Canceled 2022-08-20 2022-08-16 2022-11-12 2023-05-11 for village ambulatories of Jal onitoring and evaluation tions nvelope al-Abad & Osh oblasts ARIS-CASA-CSP-GOODS-RFQ -2022-22 / Procurement of co Project management, and m Request for Quota Single Stage - One E IDA / D2940 Post Open - National 0.00 Signed 2022-09-14 2022-09-06 2022-12-09 2023-06-07 mputer equipment for 3 scho onitoring and evaluation tions nvelope ols of Kulatov AA of Nookat r ayon of Osh oblast ARIS-CSP-AF-GOODS-RFQ-20 Project management, and m Request for Quota Single Stage - One E IDA / D2940 Post Open - National 0.00 Signed 2022-09-08 2022-09-13 2022-12-03 2023-06-01 22-21 / Ambulance vehicles f onitoring and evaluation tions nvelope or VA ARIS-CSP-AF-GOODS-RFQ-20 Project management, and m Request for Quota Single Stage - One E 22-23 / Medical instruments, IDA / D2940 Post Open - National 0.00 Canceled 2022-09-14 2022-12-09 2023-06-07 onitoring and evaluation tions nvelope equipment and medical furni ture for VA ARIS-CASA-CSP-GOODS-RFQ Support for community-led i Request for Quota Single Stage - One E Under Imple -2022-16 / Procurement of mi IDA / 67560 nvestments in social and ec Post Open - National 0.00 2022-09-22 2022-09-06 2022-11-30 2023-05-29 tions nvelope mentation nibus for Kyr-Dzhol and Kok- onomic infrastructure Bulak villages ARIS-CSP-AF-GOODS-RFB-20 Support for community-led i 22-10 / Procurement of Medic Open - Internationa Single Stage - One E IDA / D2940 nvestments in social and ec Post Request for Bids 0.00 Signed 2022-09-23 2022-09-01 2022-09-28 2022-09-15 2022-11-12 2022-10-31 2022-11-26 2022-11-30 2023-01-21 2023-07-20 al equipment and laboratory l nvelope onomic infrastructure equipment/furnuture ARIS-CASA-CSP-GOODS-RFQ Support for community-led i Request for Quota Single Stage - One E -2022-24 / Procurement of co IDA / D2940 nvestments in social and ec Post Open - National 0.00 Canceled 2022-10-15 2023-01-07 2023-07-06 tions nvelope mputer equipment for CVIAs onomic infrastructure ARIS-CSP-GOODS-RFB-2022- 09_RETENDER / Electric equi Support for community-led i Open - Internationa Single Stage - One E Under Imple pment for Osh & Batken obla IDA / D2940 nvestments in social and ec Post Request for Bids 0.00 2022-10-30 2022-11-01 2022-11-06 2022-11-13 2022-12-21 2022-12-19 2023-01-20 2023-02-24 2023-08-23 l nvelope mentation sts to conduct the repair of el onomic infrastructure ectric distribution networks u nder 2 cycle ARIS-CASA-CSP-GOODS-RFQ Support for community-led i -2022-25 / Procurement of ex Request for Quota Single Stage - One E Under Imple IDA / D2940 nvestments in social and ec Post Open - National 0.00 2022-11-05 2022-10-27 2023-01-28 2023-07-27 cavator and tractor for Orto- tions nvelope mentation onomic infrastructure Aryk and Tash-Bulak villages. ARIS-CASA-CSP-GOODS-RFQ Support for community-led i Request for Quota Single Stage - One E Under Imple -2022-25_RETENDER / Procur IDA / D2940 nvestments in social and ec Post Open - National 0.00 2023-02-05 2023-01-27 2023-04-30 2023-10-27 tions nvelope mentation ement of tractor for Tash-Bul onomic infrastructure ak village. ARIS-CSP-GOODS-RFQ-2023- Support for community-led i Request for Quota Single Stage - One E Under Imple 26 / Computer equipment for IDA / 67560 nvestments in social and ec Post Open - National 0.00 2023-02-13 2023-01-27 2023-04-23 2023-10-20 tions nvelope mentation NESK onomic infrastructure ARIS-CSP-AF-GOODS-RFB-20 Support for community-led i 22-10_RETENDER / Medical in Open - Internationa Single Stage - One E Under Imple IDA / D2940 nvestments in social and ec Post Request for Bids 0.00 2023-02-06 2023-01-27 2023-02-11 2023-01-27 2023-03-28 2023-04-27 2023-06-02 2023-11-29 struments, equipment and m l nvelope mentation onomic infrastructure edical furniture for VA ARIS-CASA-CSP-GOODS-RFQ Support for community-led i -2023-27 / Procurement of a Request for Quota Single Stage - One E Under Imple IDA / D2940 nvestments in social and ec Post Open - National 0.00 2023-04-10 2023-04-05 2023-07-03 2023-12-30 bulldozer excavator for Kapc tions nvelope mentation onomic infrastructure hygai village of Ak-Say AO of Batken rayon. ARIS-CSP-AF-GOODS-RFQ-20 22-15-2 / Procurement of co mputer equipment for village Project management, and m Request for Quota Single Stage - One E IDA / D2940 Post Open - National 0.00 Canceled 2022-09-28 2022-09-14 2022-12-21 2023-06-19 ambulatories of Jalal-Abad & onitoring and evaluation tions nvelope Osh oblasts. Retender of Lot#10 of ARIS-C SP-AF-GOODS-RFB-2022-07. ARIS-CSP-AF-GOODS-RFQ-20 22-15-2-2 / Procurement of c Project management, and m Request for Quota Single Stage - One E Under Imple IDA / D2940 Post Open - National 0.00 2023-04-08 2023-04-05 2023-07-01 2023-12-28 omputer equipment for villag onitoring and evaluation tions nvelope mentation e ambulatories of Jalal-Abad & Osh oblasts. ARIS-CASA-CSP-GOODS-RFB- 2023-26 / Equipment for the production of wool pile carpe ts for Ak-Say AO and for Sulu Support for community-led i Single Stage - One E Under Imple kta IDA / D2940 nvestments in social and ec Post Request for Bids Open - National 0.00 2023-04-05 2023-04-03 2023-04-12 2023-04-18 2023-05-12 2023-06-01 2023-07-22 2024-01-18 nvelope mentation Wool processing equipment f onomic infrastructure or Barpy AO Equipment for the processing of felt products and carpet w eaving for Dzhoosh AO Page 4 ARIS-CASA-CSP-GOODS-RFB- 2023-27 / Apricot processing equipment for Tort-Gul AO Support for community-led i Equipment for processing ap Single Stage - One E Under Imple IDA / D2940 nvestments in social and ec Post Request for Bids Open - National 0.00 2023-04-05 2023-04-03 2023-04-12 2023-05-19 2023-05-12 2023-06-01 2023-07-22 2024-01-18 ples, apricots, raspberries for nvelope mentation onomic infrastructure jam, jam, syrup, fruit drinks f or Kadamjai; Equipment for drying apples and other berries for A.Masali ev AO ARIS-CASA-CSP-GOODS-RFQ Support for community-led i Request for Quota Single Stage - One E Under Imple -2023-29 / Rice Processing E IDA / D2940 nvestments in social and ec Post Open - National 0.00 2023-04-08 2023-04-13 2023-06-03 2023-11-30 tions nvelope mentation quipment for Ak-Turpak AO onomic infrastructure ARIS-CASA-CSP-GOODS-RFQ Support for community-led i -2023-30 / Honey packaging Request for Quota Single Stage - One E Under Imple IDA / D2940 nvestments in social and ec Post Open - National 0.00 2023-04-10 2023-04-14 2023-06-05 2023-12-02 equipment for the Logistics C tions nvelope mentation onomic infrastructure enter for Jalal-Abad city ARIS-CASA-CSP-GOODS-RFB- 2023-28 / Apricot storage an d processing equipment for Support for community-led i Single Stage - One E Under Imple MTU Turan IDA / D2940 nvestments in social and ec Post Request for Bids Open - National 0.00 2023-04-16 2023-04-10 2023-04-23 2023-04-19 2023-05-23 2023-06-12 2023-08-02 2024-01-29 nvelope mentation Apparatus (portable) for juice onomic infrastructure processing for On-Eki-Bel AO Juice processing equipment f or Kulatov AO ARIS-CASA-CSP-GOODS-RFQ -2023-31 / Procurement of co mputer equipment, furniture, kitchen equipment for school Support for community-led i Request for Quota Single Stage - One E Under Imple s & kinder gardens of Tash-K IDA / D2940 nvestments in social and ec Post Open - National 0.00 2023-04-29 2023-05-18 2023-07-22 2024-01-18 tions nvelope mentation orgon,Alysh, Sovet, Pulgon, Ji onomic infrastructure ydelik, Chogorok, Tokoi, Ak-T urpak, Jany-Jer, Korgon, & Ra vat villages of Kadamjai, Bat ken & Leilek rayons of Batke n oblast ARIS-CASA-CSP-GOODS-RFQ -2023-32 / Procurement of co mputer equipment, furniture, kitchen equipment for school Support for community-led i Request for Quota Single Stage - One E Under Imple s, kinder gardens & Equipme IDA / D2940 nvestments in social and ec Post Open - National 0.00 2023-04-29 2023-05-23 2023-07-22 2024-01-18 tions nvelope mentation nt for Village Ambulatories fo onomic infrastructure r Karool, Sheraly, Ak-Terek, J any-Jol, Kyzyl-Kyrman, Kosh- Korgon villages of Ozgon & K ara-Suu rayons of Osh oblast. ARIS-CASA-CSP-GOODS-RFQ -2023-33 / Procurement of sp ecial machinery, equipment Support for community-led i Request for Quota Single Stage - One E Pending Impl & furniture for Choko-Dobo, T IDA / D2940 nvestments in social and ec Post Open - National 0.00 2023-05-06 2023-07-29 2024-01-25 tions nvelope ementation ashtak, Jashasyn-2 Kachkync onomic infrastructure hy, Yntymak, Orto-Aryk, Tosh -Kutchu & Orto-Sai villages of Osh & Jalal-Abad oblast. ARIS-CSP-GOODS-DC-2023-0 Support for community-led i Under Imple 1 / Procurement of wires & c IDA / D2940 nvestments in social and ec Post Direct Selection Direct - National 0.00 2023-05-10 2023-04-28 2023-05-15 2023-03-31 2023-06-19 2023-12-16 mentation ables for Batken PES onomic infrastructure ARIS-CSP-GOODS-DC-2023-0 Support for community-led i Under Imple 2 / Procurement of traverse T IDA / D2940 nvestments in social and ec Post Direct Selection Direct - National 0.00 2023-05-10 2023-03-31 2023-05-15 2023-03-31 2023-06-19 2023-12-16 mentation M-3 onomic infrastructure ARIS-CASA-CSP-GOODS-RFQ -2023-36 / Procurement of sp Support for community-led i ecial machinery, equipment Request for Quota Single Stage - One E Pending Impl IDA / D2940 nvestments in social and ec Post Open - National 0.00 2023-07-03 2023-09-16 2024-03-14 & furniture for Tash-Bulak, M tions nvelope ementation onomic infrastructure TU Turan Jinjigen, Leilek, Kolt so, Ak-Terek, Valakysh villag es. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ARIS-CSP-CQ-20-2 / Develop Support for community mobi ment and implementation of Consultant Qualifi IDA / D2940 lization, youth engagement Post Open - National 47,473.65 Signed 2020-05-21 2020-05-29 2020-05-22 2020-06-22 2020-06-19 2020-08-05 2020-06-26 2020-08-25 2020-07-10 2020-09-09 2021-04-06 information campaign of the cation Selection and communications Communities Support Project CASA1000 IDA-ARIS-CSP-AFCSP-CQ-21- Project management, and m Consultant Qualifi IDA / 62190 Post Open - National 71,654.94 Signed 2021-03-12 2021-03-10 2021-03-27 2021-03-10 2021-04-26 2021-04-06 2021-05-11 2021-04-23 2021-05-25 2021-05-12 2022-02-19 4 / Baseline survey onitoring and evaluation cation Selection ARIS-AUDIT-LCS-2021-1 / Co Project management, and m Least Cost Selecti Open - Internationa Under Implement IDA / 62190 Post 0.00 2021-08-17 2021-09-07 2021-08-20 2021-09-24 2021-10-01 2021-11-03 2021-11-05 2021-11-12 2021-11-26 2023-12-31 mmunity Support Project aud onitoring and evaluation on l ation it. IDA-ARIS-CSP-CQ-2021-05 / Consulting services to develo p detailed design and estima Support for community mobi Consultant Qualifi tes for the installation of tran IDA / D2940 lization, youth engagement Post Open - National 0.00 Canceled 2021-12-10 2021-12-22 2022-01-07 2022-03-23 2022-04-07 2022-04-21 2022-08-22 cation Selection sformer substation (TS) and c and communications onstruction of new overhead lines (OL) in target villages of Batken, Osh and Jalal-Abad O blasts IDA-CASA-AF-CSP-CQ-2021-0 Support for community mobi Consultant Qualifi Under Implement 6 / Development and product IDA / D2940 lization, youth engagement Post Open - National 0.00 2021-12-10 2022-01-17 2022-01-07 2022-02-16 2022-03-03 2022-03-06 2022-03-20 2022-07-21 cation Selection ation ion of animated videos and communications IDA-CASA-AF-CSP-CQS-2022- 07 / Consulting services to id entify priority value chain of t Support for community mobi Consultant Qualifi Under Implement arget 100 ayil aimaks, develo IDA / 62190 lization, youth engagement Post Open - National 0.00 2022-05-23 2022-06-06 2022-06-13 2022-06-28 2022-08-18 2022-08-25 2022-08-29 2023-03-27 cation Selection ation p feasibility study, train CSP and communications and CSP AF staff, develop an d implement business partne r capacity building program Page 5 IDA-ARIS-CSP-CQ-2022-08 / Support for community mobi Selection of Consulting comp Consultant Qualifi IDA / D2940 lization, youth engagement Post Open - National 0.00 Canceled 2022-06-25 2022-07-16 2022-07-21 2022-07-22 2022-08-27 2022-08-30 2022-09-13 2023-01-14 any to develop of a feasibility cation Selection and communications study of economic objects INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-CASA-IC-CDSO-2020-1 / Support for community mobi Community Development an Individual Consult IDA / D2940 lization, youth engagement Post Limited 6,950.32 Signed 2020-03-18 2020-02-28 2020-03-23 2020-08-06 2020-04-13 2020-08-10 2020-05-18 2020-08-11 2023-08-31 d Support Officer for Suuzak ant Selection and communications rayon Djalal-Abad oblast (1). IDA-CASA-IC-CDSO-2020-2 / Support for community mobi Community Development an Individual Consult IDA / D2940 lization, youth engagement Post Limited 7,089.01 Signed 2020-03-18 2020-02-28 2020-03-23 2020-08-06 2020-04-13 2020-08-10 2020-05-18 2020-08-11 2023-08-31 d Support Officer for Suuzak ant Selection and communications rayon Djalal-Abad oblast (2). IDA-CASA-IC-CDSO-2020-3 / Support for community mobi Community Development an Individual Consult IDA / D2940 lization, youth engagement Post Limited 8,823.99 Signed 2020-03-18 2020-02-28 2020-03-23 2020-08-06 2020-04-13 2020-08-10 2020-05-18 2020-08-11 2023-08-31 d Support Officer for Suuzak ant Selection and communications rayon Djalal-Abad oblast (3). IDA-CASA-IC-CDSO-2020-4 / Support for community mobi Community Development an Individual Consult IDA / D2940 lization, youth engagement Post Limited 8,490.69 Completed 2020-03-18 2020-02-28 2020-03-23 2020-08-05 2020-04-13 2020-08-10 2020-05-18 2020-08-11 2023-08-31 2021-06-24 d Support Officer for Ozgon r ant Selection and communications ayon Osh oblast (1). IDA-CASA-IC-CDSO-2020-5 / Support for community mobi Community Development an Individual Consult IDA / D2940 lization, youth engagement Post Limited 8,539.34 Signed 2020-03-18 2020-02-28 2020-03-23 2020-08-05 2020-04-13 2020-08-10 2020-05-18 2020-08-11 2023-08-31 d Support Officer for Ozgon r ant Selection and communications ayon Osh oblast (2). IDA-CASA-IC-CDSO-2020-6 / Support for community mobi Community Development an Individual Consult IDA / D2940 lization, youth engagement Post Limited 7,638.05 Signed 2020-03-18 2020-02-28 2020-03-23 2020-07-31 2020-04-13 2020-08-10 2020-05-18 2020-08-11 2023-08-31 d Support Officer for Kara-Su ant Selection and communications u rayon Osh oblast. IDA-CASA-IC-CDSO-2020-7 / Support for community mobi Community Development an Individual Consult IDA / D2940 lization, youth engagement Post Limited 8,679.75 Signed 2020-03-18 2020-02-28 2020-03-23 2020-08-04 2020-04-13 2020-08-10 2020-05-18 2020-08-11 2023-08-31 d Support Officer for Nookat r ant Selection and communications ayon Osh oblast (1). IDA-CASA-IC-CDSO-2020-8 / Support for community mobi Community Development an Individual Consult IDA / D2940 lization, youth engagement Post Limited 7,901.54 Signed 2020-03-18 2020-02-28 2020-03-23 2020-08-04 2020-04-13 2020-08-10 2020-05-18 2020-08-11 2023-08-31 d Support Officer for Nookat r ant Selection and communications ayon Osh oblast (2). IDA-CASA-IC-CDSO-2020-9 / Support for community mobi Community Development an Individual Consult IDA / D2940 lization, youth engagement Post Limited 7,628.07 Signed 2020-03-18 2020-02-28 2020-03-23 2020-07-30 2020-04-13 2020-08-10 2020-05-18 2020-08-11 2023-08-31 d Support Officer for Kadamj ant Selection and communications ay rayon Batken oblast (1). IDA-CASA-IC-CDSO-2020-10 Support for community mobi / Community Development a Individual Consult IDA / D2940 lization, youth engagement Post Limited 7,979.45 Signed 2020-03-18 2020-02-28 2020-03-23 2020-07-30 2020-04-13 2020-08-10 2020-05-18 2020-08-11 2023-08-31 nd Support Officer for Kadam ant Selection and communications jay rayon Batken oblast (2). IDA-CASA-IC-CDSO-2020-11 Support for community mobi / Community Development a Individual Consult IDA / D2940 lization, youth engagement Post Limited 7,933.73 Completed 2020-03-18 2020-02-28 2020-03-23 2020-07-29 2020-04-13 2020-08-10 2020-05-18 2020-08-11 2023-08-31 2021-05-25 nd Support Officer for Batken ant Selection and communications rayon Batken oblast. IDA-CASA-IC-CDSO-2020-12 Support for community mobi / Community Development a Individual Consult IDA / D2940 lization, youth engagement Post Limited 8,010.45 Signed 2020-03-18 2020-02-28 2020-03-23 2020-08-03 2020-04-13 2020-08-10 2020-05-18 2020-08-11 2023-08-31 nd Support Officer for Leylek ant Selection and communications rayon Batken oblast (1). IDA-CASA-IC-CDSO-2020-13 Support for community mobi / Community Development a Individual Consult IDA / D2940 lization, youth engagement Post Limited 7,462.43 Signed 2020-03-18 2020-02-28 2020-03-23 2020-08-03 2020-04-13 2020-08-10 2020-05-18 2020-08-11 2023-08-31 nd Support Officer for Leylek ant Selection and communications rayon Batken oblast (2). IDA-CASA-IC-CDSO-2020-14 Support for community mobi / Community Development a Individual Consult IDA / D2940 lization, youth engagement Post Limited 7,301.51 Completed 2020-06-24 2020-02-28 2020-06-29 2020-08-06 2020-07-20 2020-08-10 2020-08-24 2020-08-11 2021-02-20 2021-07-01 nd Support Officer for Suzak ant Selection and communications rayon Dzhalal-Abad oblast. IDA-CASA-IC-2020-15 / Cons ultant to design the Updated Project Operational Manual, t Support for community mobi raining modules, information Individual Consult IDA / 62190 lization, youth engagement Post Limited 9,855.86 Completed 2020-08-26 2020-08-27 2020-08-31 2020-09-02 2020-09-21 2020-09-03 2020-10-26 2020-09-04 2021-04-24 2021-04-06 al materials on scopes, tasks ant Selection and communications and CSP implementation mec hanisms to account for the C SP additional financing in the context of COVID-19 IDA/CASA-1000/CSP/AF/IC-20 21-2 / Community and Techn Support for community mobi Individual Consult ology Expert for Kara-Suu ray IDA / 67560 lization, youth engagement Post Open 3,140.85 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ant Selection on. and communications Kyzyl-Suu, Kashkar-Kyshtak & Savay AAs IDA/CASA-1000/CSP/AF/IC-20 Support for community mobi 21-3 / Community and Techn Individual Consult IDA / 67560 lization, youth engagement Post Open 3,404.41 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ology Expert for Kara-Suu ray ant Selection and communications on. Papan & Mady AAs IDA/CASA-1000/CSP/AF/IC-20 21-4 / Community and Techn Support for community mobi Individual Consult ology Expert for Ozgon rayon IDA / 67560 lization, youth engagement Post Open 3,490.41 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ant Selection . and communications Kyzyl-Too, Zerger & Kara-Tas h AAs. IDA/CASA-1000/CSP/AF/IC-20 21-5 / Community and Techn Support for community mobi Individual Consult ology Expert for Ozgon rayon IDA / 67560 lization, youth engagement Post Open 3,429.75 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ant Selection . and communications Altyn-Bulak, Salam-Alik & Kol duk AAs. Page 6 IDA/CASA-1000/CSP/AF/IC-20 Support for community mobi 21-6 / Community and Techn Individual Consult IDA / 67560 lization, youth engagement Post Open 3,513.33 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ology Expert for Ozgon rayon ant Selection and communications . Iyri-Suu, Changet & Jylaldy A As. IDA/CASA-1000/CSP/AF/IC-20 Support for community mobi 21-7 / Community and Techn Individual Consult IDA / 67560 lization, youth engagement Post Open 3,618.25 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ology Expert for Nookat rayo ant Selection and communications n. Isanov, Kok-Bel and Kenesh AAs. IDA/CASA-1000/CSP/AF/IC-20 21-8 / Community and Techn Support for community mobi Individual Consult ology Expert for Nookat rayo IDA / 67560 lization, youth engagement Post Open 3,371.30 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ant Selection n. and communications Kara-Tash, T. Zulpuev & Kyrg yz-Ata AAs. IDA/CASA-1000/CSP/AF/IC-20 Support for community mobi 21-9 / Community and Techn Individual Consult IDA / 67560 lization, youth engagement Post Open 3,542.75 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ology Expert for Nookat rayo ant Selection and communications n. Bel, Jany-Nookat & Nayman A As. IDA/CASA-1000/CSP/AF/IC-20 21-10 / Community and Tech Support for community mobi Individual Consult nology Expert for Bazar-Korg IDA / 67560 lization, youth engagement Post Open 3,762.39 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ant Selection on rayon. and communications Kyzyl-Unkur, Arstanbap and Talduu-Bulak AAs. IDA/CASA-1000/CSP/AF/IC-20 21-11 / Community and Tech Support for community mobi Individual Consult nology Expert for Bazar-Korg IDA / 67560 lization, youth engagement Post Open 3,765.62 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ant Selection on rayon. and communications Kenesh, Seidykum & Beshik-J on AAs. IDA/CASA-1000/CSP/AF/IC-20 21-12 / Community and Tech Support for community mobi Individual Consult nology Expert for Bazar-Korg IDA / 67560 lization, youth engagement Post Open 3,832.73 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ant Selection on/Suzak rayon. and communications Akman, Kara-Darya & Saipidi n-Atabek AAs. IDA/CASA-1000/CSP/AF/IC-20 21-13 / Community and Tech Support for community mobi Individual Consult nology Expert for Suzak rayo IDA / 67560 lization, youth engagement Post Open 3,856.98 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ant Selection n. and communications Kegart, Kara-Alma & Kurman bek AAs. IDA/CASA-1000/CSP/AF/IC-20 21-14 / Community and Tech Support for community mobi Individual Consult nology Expert for Nooken ray IDA / 67560 lization, youth engagement Post Open 3,727.63 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ant Selection on. and communications Burgondu, Sakaldy, Dostuk & Mombekov AAs. IDA/CASA-1000/CSP/AF/IC-20 21-15 / Community and Tech Support for community mobi Individual Consult nology Expert for Nooken ray IDA / 67560 lization, youth engagement Post Open 4,141.06 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 ant Selection on. and communications Nooken, Shaydan, Masy & Ar al AAs. IDA/CASA-1000/CSP/AF/IC-20 Support for community mobi 21-16 / Community and Tech Individual Consult IDA / 67560 lization, youth engagement Post Open 3,641.51 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 nology Expert for Kadamjay r ant Selection and communications ayon. Birlik, Chauvay & Orozbekov AAs. IDA/CASA-1000/CSP/AF/IC-20 Support for community mobi 21-17 / Community and Tech Individual Consult IDA / 67560 lization, youth engagement Post Open 3,787.57 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 nology Expert for Leilek rayo ant Selection and communications n. Margun & Beshkent AAs. IDA/CASA-1000/CSP/AF/IC-20 Support for community mobi 21-18 / Community and Tech Individual Consult IDA / 67560 lization, youth engagement Post Open 3,397.76 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-21 2021-12-31 nology Expert for Leilek rayo ant Selection and communications n. Ak-Suu & Katran AAs. ARIS-CSP-IC-19-2 / Consulta Support for community mobi Individual Consult nt for Design of technical sp IDA / D2940 lization, youth engagement Post Limited 4,952.96 Signed 2021-05-03 2021-05-04 2021-05-31 2021-06-23 2021-07-07 2021-07-05 2021-08-11 2021-07-23 2022-02-07 ant Selection ecifications for Subcomponen and communications t 1A ARIS-CSP-IC-21-33 / Consult Support for community mobi ant for Design of technical s Individual Consult IDA / D2940 lization, youth engagement Post Limited 0.00 Canceled 2021-05-20 2021-05-15 2021-06-17 2021-07-08 2021-07-24 2021-08-28 2022-02-24 pecifications for Subcompone ant Selection and communications nt 1A for Osh, Batken abd Jal al-Abad oblasts IDA-CASA-CSP-IC-CDSO-202 Support for community mobi 1-16 / Community Developm Individual Consult IDA / D2940 lization, youth engagement Post Limited 1,334.75 Signed 2021-07-30 2021-07-26 2021-08-13 2021-09-13 2021-09-12 2021-09-13 2021-09-29 2021-10-02 2021-12-31 ent and Support Officer for S ant Selection and communications uzak rayon Djalal-Abad oblas t (CDSO) IDA-CASA-CSP-IC-CDSO-202 Support for community mobi 1-17 / Community Developm Individual Consult IDA / D2940 lization, youth engagement Post Limited 1,413.46 Signed 2021-07-30 2021-07-26 2021-08-13 2021-09-13 2021-09-12 2021-09-13 2021-09-29 2021-10-02 2021-12-31 ent and Support Officer for B ant Selection and communications atken rayon Batken oblast (C DSO) IDA-CASA-CSP-IC-CDSO-202 Support for community mobi 1-18 / Community Developm Individual Consult IDA / D2940 lization, youth engagement Post Limited 1,537.14 Signed 2021-07-30 2021-07-26 2021-08-13 2021-09-13 2021-09-12 2021-09-13 2021-09-29 2021-10-02 2021-12-31 ent and Support Officer for O ant Selection and communications zgon rayon Osh oblast (CDSO ) IDA-CASA-AF-CSP-IC-2021-1 Support for community mobi 9 / Community and Technolo Individual Consult IDA / 67560 lization, youth engagement Post Limited 1,671.20 Signed 2021-07-30 2021-07-26 2021-08-27 2021-09-10 2021-09-26 2021-09-10 2021-10-31 2021-10-02 2021-12-31 gy Expert for Uzgen rayon Sa ant Selection and communications lam-Alik, Kolduk, Altyn-Bulak AAs. IDA-CASA-AF-CSP-IC-2021-2 Support for community mobi 1 / Community and Technolo Individual Consult IDA / 67560 lization, youth engagement Post Limited 1,454.75 Signed 2021-07-30 2021-07-26 2021-08-27 2021-09-13 2021-09-26 2021-09-13 2021-10-31 2021-10-02 2021-12-31 gy Expert for Bazar-Korgon r ant Selection and communications ayon Kenesh & AkmanAAs. IDA-CASA--AF-CSP-IC-2021-2 Support for community mobi 2 / Community and Technolo Individual Consult IDA / 67560 lization, youth engagement Post Limited 1,393.49 Signed 2021-07-30 2021-07-26 2021-08-27 2021-09-13 2021-09-26 2021-09-13 2021-10-31 2021-10-02 2021-12-31 gy Expert for Nooken rayon ant Selection and communications Masy, Dostuk & Sakaldy AAs. IDA-CASA-CSP-IC-2021-19 / Support for community mobi Individual Consult Consultant on Local self-gove IDA / 62190 lization, youth engagement Post Limited 7,405.65 Signed 2021-07-30 2021-07-29 2021-09-03 2021-11-29 2021-09-17 2021-11-30 2021-09-24 2021-12-16 2022-03-23 ant Selection rnance and municipal propert and communications y. Page 7 IDA-CASA-AF-CSP-2021-35 / Support for community mobi Individual Consult Development and production IDA / D2940 lization, youth engagement Post Limited 0.00 Canceled 2021-11-30 2021-11-28 2021-12-30 2022-01-06 2022-02-10 2022-08-09 ant Selection of animated videos and communications IDA-ARIS-CSP-DC-2022-01 / Geo-referencing the design a Support for community mobi Under Implement nd estimate documentation a IDA / 62190 lization, youth engagement Post Direct Selection Direct 0.00 2022-03-18 2022-03-23 2022-04-08 2022-04-04 2022-06-12 2022-08-31 ation nd calculating cost estimates and communications of work and materials IDA-CASA-AF-CSP-DC-IC-202 Support for community mobi 2-43 / Consulting services to Individual Consult IDA / D2940 lization, youth engagement Post Direct 16,834.85 Signed 2022-04-11 2022-04-07 2022-04-21 2022-04-18 2022-04-23 2022-04-18 2022-04-29 2022-04-19 2022-07-26 identify priority Value-added ant Selection and communications chains for 50 aiyl aimaks for Сycle-1 IDA-CASA-IC-CTE-DC-2022-0 3 / Community and Technolo Support for community mobi Individual Consult Under Implement gy Expert for Suzak rayon, Le IDA / D2940 lization, youth engagement Post Direct 0.00 2022-04-29 2022-04-29 2022-05-13 2022-05-15 2022-05-21 2023-01-04 ant Selection ation nin, Bagysh, Tash-Bulak Aas and communications Djalal-Abad oblast (CDSO) IDA-CASA-IC-CTE-DC-2022-0 Support for community mobi 4 / Community and Technolo Individual Consult Under Implement IDA / D2940 lization, youth engagement Post Direct 0.00 2022-04-29 2022-04-29 2022-05-13 2022-05-15 2022-05-21 2023-01-04 gy Expert for Suzak rayon, B ant Selection ation and communications arpy, Suzak Aas Djalal-Abad oblast (CDSO) IDA-CASA-AF-CSP-DC-IC-202 2-02 / Community and Techn Support for community mobi Individual Consult Under Implement ology Expert for Ak-Sy rayon, IDA / D2940 lization, youth engagement Post Direct 0.00 2022-04-29 2022-04-29 2022-05-13 2022-05-15 2022-05-21 2023-01-04 ant Selection ation Avletim, Ak-Jol, Jany-Jol, Kara- and communications Jygach, Kyzyl-Tuu, Kara-Suu Aas IDA-CASA-AF-CSP-IC-2022-4 Support for community mobi 4 / Community and Technolo Individual Consult Under Implement IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 gy Expert for Alay rayon, Ala ant Selection ation and communications y, Budalyk, Bulolu, Gulcho, D zhosholu As IDA-CASA-AF-CSP-IC-2022-4 Support for community mobi 5 / Community and Technolo Individual Consult Under Implement IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 gy Expert for Alay rayon, Kon ant Selection ation and communications ur-Dobo, Kabylankol, Korul, L enin, Uch-Dobo Aas IDA-CASA-AF-CSP-IC-2022-4 6 / Community and Technolo Support for community mobi gy Expert for Alay rayon, Sar Individual Consult Under Implement IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 y-Tash, Taldy-Suu, Sarymgol ant Selection ation and communications AAs & Chon-Alay rayon, Jeke ndi, Kashka-Suu, Chon-Alay A As IDA-CASA-AF-CSP-IC-2022-4 7 / Community and Technolo Support for community mobi Individual Consult Under Implement gy Expert for Aravan rayon, IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 ant Selection ation Allya Anarov, Kerme-Too, Jus and communications upov, Tepe-Korgon, Nurabad AAs IDA-CASA-AF-CSP-IC-2022-4 8 / Community and Technolo Support for community mobi Individual Consult Under Implement gy Expert for Kara-Kulja rayo IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 ant Selection ation n, Akaikuu, Kapchygai, Oi-Tal and communications , Chalmin, Kyzyl-Jar AAs IDA-CASA-AF-CSP-IC-2022-4 9 / Community and Technolo Support for community mobi Individual Consult Under Implement gy Expert for Kara-Kulja rayo IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 ant Selection ation n, Kenesh, Karaguz, Kara-Kulj and communications a, Ylai-Talin, Sary-Bulak AAs IDA-CASA-AF-CSP-IC-2022-5 0 / Community and Technolo Support for community mobi Individual Consult Under Implement gy Expert for Toktogul rayon, IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 ant Selection ation Sary-Kamysh, Bel-Aldy, Nichk and communications e-Say, Cholpon-Ata, Ketmen- Dobo AAs IDA-CASA-AF-CSP-IC-2022-5 1 / Community and Technolo Support for community mobi Individual Consult Under Implement gy Expert for Toktogul rayon, IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 ant Selection ation Aralbaev, A.Suerkulov, Jany-J and communications ol, Kyzyl-Ozgorush, Uch-Tere k AAs IDA-CASA-AF-CSP-IC-2022-5 Support for community mobi 2 / Community and Technolo Individual Consult Under Implement IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 gy Expert for Ala-Buka rayon, ant Selection ation and communications Pervymai, Oruktu, Kok-Tash, Kok-Serek AAs IDA-CASA-AF-CSP-IC-2022-5 Support for community mobi 3 / Community and Technolo Individual Consult Under Implement IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 gy Expert for Chatkal rayon, ant Selection ation and communications Kanysh-Kyia, Chatkal, Sumsa r, Terek-Sai AAs IDA-CASA-AF-CSP-IC-2022-5 4 / Community and Technolo Support for community mobi Individual Consult Under Implement gy Expert for Toguz-Toro ray IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 ant Selection ation on, Ataiu, Kok-Irim, Kargalyk, and communications Sary-Bulun, Toguz-Toro AAs IDA-CASA-AF-CSP-IC-2022-5 5 / Community and Technolo Support for community mobi Individual Consult Under Implement gy Expert for Kadamjay rayo IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 ant Selection ation n, Kotormo, Kyrgyz-Kyshtak, and communications Halmion, Orozbekov AAs IDA-CASA-AF-CSP-IC-2022-5 Support for community mobi 6 / Community and Technolo Individual Consult Under Implement IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 gy Expert for Batken rayon, S ant Selection ation and communications amarkandek, Kyshtut, Suu-B ashy, Kara-Bak AAs IDA-CASA-AF-CSP-IC-2022-5 Support for community mobi 7 / Community and Technolo Individual Consult Under Implement IDA / 67560 lization, youth engagement Post Limited 0.00 2022-04-29 2022-04-29 2022-05-13 2022-06-08 2022-07-10 2022-12-31 gy Expert for Ala-Buka rayon, ant Selection ation and communications Ala-Buka, Ak-Tam, Ak-Korgon , T.Baltagulov AAs IDA-CASA-CSP-IC-CTE-2022- Support for community mobi 59 / Community & Technolog Individual Consult Under Implement IDA / 67560 lization, youth engagement Post Open 0.00 2022-06-30 2022-06-30 2022-08-18 2022-09-08 2022-10-13 2023-04-11 y Expert for Suzak rayon Jalal ant Selection ation and communications -Abad oblast (CTE) Page 8 IDA-CASA-CSP-IC-CTE-2022- Support for community mobi 60 / Community & Technolog Individual Consult Under Implement IDA / 67560 lization, youth engagement Post Open 0.00 2022-06-30 2022-06-30 2022-08-18 2022-09-08 2022-10-13 2023-04-11 y Expert for Kadamjai rayon ant Selection ation and communications Batken oblast (CTE) IDA-CASA-AF-CSP-DC-IC-202 Support for community mobi 2-05 / Community and Techn Under Implement IDA / D2940 lization, youth engagement Post Direct Selection Direct - National 0.00 2022-08-22 2022-08-01 2022-09-05 2022-09-19 2022-12-31 ology Support Officer for Ak- ation and communications Sy rayon of Jalal-Abad oblast IDA-CASA-CSP-IC-2022-61 / Support for community mobi Individual Consult Under Implement Consultant on LSG and munic IDA / D2940 lization, youth engagement Post Open - National 0.00 2022-09-15 2022-09-01 2022-11-03 2022-11-24 2022-12-29 2023-06-27 ant Selection ation ipal property and communications IDA-CASA-AF-CSP-IC-2022-6 Support for community mobi 2 / Local value chain speciali Individual Consult Under Implement IDA / D2940 lization, youth engagement Post Open - National 0.00 2022-12-01 2022-12-02 2023-01-17 2023-01-26 2023-02-15 2023-12-31 st/Coach for Nookat & Arava ant Selection ation and communications n rayons of Osh oblast IDA-CASA-AF-CSP-IC-2022-6 Support for community mobi 3 / Local value chain speciali Individual Consult Under Implement IDA / D2940 lization, youth engagement Post Open - National 0.00 2022-12-01 2022-12-02 2023-01-17 2023-01-26 2023-02-15 2023-12-31 st/Coach for Aravan, Kara-Su ant Selection ation and communications u & Alay rayons of Osh oblast IDA-CASA-AF-CSP-IC-2022-6 Support for community mobi Individual Consult Under Implement 4 / Local value chain speciali IDA / D2940 lization, youth engagement Post Open - National 0.00 2022-12-01 2022-12-02 2023-01-17 2023-01-26 2023-02-15 2023-12-31 ant Selection ation st/Coach for Uzgen rayon of and communications Osh oblast IDA-CASA-AF-CSP-IC-2022-6 Support for community mobi 5 / Local value chain speciali Individual Consult Under Implement IDA / D2940 lization, youth engagement Post Open - National 0.00 2022-12-01 2022-12-02 2023-01-17 2023-01-26 2023-02-15 2023-12-31 st/Coach for Alay & Chon-Ala ant Selection ation and communications y rayons of Osh oblast IDA-CASA-AF-CSP-IC-2022-6 Support for community mobi Individual Consult Under Implement 6 / Local value chain speciali IDA / D2940 lization, youth engagement Post Open - National 0.00 2022-12-01 2022-12-02 2023-01-17 2023-01-26 2023-02-15 2023-12-31 ant Selection ation st/Coach for Kara-Kuldzha ra and communications yon of Osh oblast IDA-CASA-AF-CSP-IC-2022-6 Support for community mobi 7 / Local value chain speciali Individual Consult Under Implement IDA / D2940 lization, youth engagement Post Open - National 0.00 2022-12-01 2022-12-02 2023-01-17 2023-01-26 2023-02-15 2023-12-31 st/Coach for Bazar-Korgon & ant Selection ation and communications Nooken rayons of Jalal-Anad oblast IDA-CASA-AF-CSP-IC-2022-6 Support for community mobi 8 / Local value chain speciali Individual Consult Under Implement IDA / D2940 lization, youth engagement Post Open - National 0.00 2022-12-01 2022-12-02 2023-01-17 2023-01-26 2023-02-15 2023-12-31 st/Coach for Nooken & Suzak ant Selection ation and communications rayons of Jalal-Abad oblast IDA-CASA-AF-CSP-IC-2022-6 Support for community mobi Individual Consult Under Implement 9 / Local value chain speciali IDA / D2940 lization, youth engagement Post Open - National 0.00 2022-12-01 2022-12-02 2023-01-17 2023-01-26 2023-02-15 2023-12-31 ant Selection ation st/Coach for Toktogul rayon o and communications f Jalal-Abad oblast IDA-CASA-AF-CSP-IC-2022-7 Support for community mobi Individual Consult Under Implement 0 / Local value chain speciali IDA / D2940 lization, youth engagement Post Open - National 0.00 2022-12-01 2022-12-02 2023-01-17 2023-01-26 2023-02-15 2023-12-31 ant Selection ation st/Coach for Aksy rayon of Jal and communications al-Abad oblast IDA-CASA-AF-CSP-IC-2022-7 Support for community mobi 1 / Local value chain speciali Individual Consult Under Implement IDA / D2940 lization, youth engagement Post Open - National 0.00 2022-12-01 2022-12-02 2023-01-17 2023-01-26 2023-02-15 2023-12-31 st/Coach for Ala-Buka & Chat ant Selection ation and communications kal rayons of Jalal-Abad oblas t IDA-CASA-AF-CSP-IC-2022-7 Support for community mobi 2 / Local value chain speciali Individual Consult Under Implement IDA / D2940 lization, youth engagement Post Open - National 0.00 2022-12-01 2022-12-02 2023-01-17 2023-01-26 2023-02-15 2023-12-31 st/Coach for Kadamjay & Bat ant Selection ation and communications ken rayons of Batken oblast IDA-CASA-AF-CSP-IC-2022-7 Support for community mobi 3 / Local value chain speciali Individual Consult Under Implement IDA / D2940 lization, youth engagement Post Open - National 0.00 2022-12-01 2022-12-02 2023-01-17 2023-01-26 2023-02-15 2023-12-31 st/Coach forBatken & Leylek ant Selection ation and communications rayons of Batken oblast IDA-CASA-CSP-IC-2023-74 / Support for community mobi Individual Consult Under Implement Supervision Engineer for Bat IDA / D2940 lization, youth engagement Post Open - National 0.00 2023-01-31 2023-01-23 2023-03-19 2023-03-28 2023-04-17 2024-03-01 ant Selection ation ken rayon and communications IDA-CASA-CSP-IC-2023-75 / Support for community mobi Individual Consult Under Implement Supervision Engineer Jalal-Ab IDA / D2940 lization, youth engagement Post Open - National 0.00 2023-01-31 2023-01-23 2023-03-19 2023-03-28 2023-04-17 2024-03-01 ant Selection ation ad, Suzak rayon and communications IDA-CASA-CSP-IC-2023-76 / Support for community mobi Individual Consult Under Implement Supervision Engineer Kadamj IDA / D2940 lization, youth engagement Post Open - National 0.00 2023-01-31 2023-01-23 2023-03-19 2023-03-28 2023-04-17 2024-03-01 ant Selection ation ai rayon and communications IDA-CASA-CSP-IC-2023-77 / Support for community mobi Individual Consult Under Implement Supervision Engineer for Noo IDA / D2940 lization, youth engagement Post Open - National 0.00 2023-01-31 2023-01-23 2023-03-19 2023-03-28 2023-04-17 2024-03-01 ant Selection ation kat rayon and communications IDA-CASA-CSP-IC-2023-78 / Support for community mobi Individual Consult Under Implement Supervision Engineer for Sulu IDA / D2940 lization, youth engagement Post Open - National 0.00 2023-01-31 2023-01-23 2023-03-19 2023-03-28 2023-04-17 2024-03-01 ant Selection ation kta and communications IDA-CASA-CSP-IC-2023-79 / Support for community mobi Individual Consult Under Implement Supervision Engineer Suzak r IDA / D2940 lization, youth engagement Post Open - National 0.00 2023-01-31 2023-01-23 2023-03-19 2023-03-28 2023-04-17 2024-03-01 ant Selection ation ayon and communications IDA-CASA-CSP-IC-2023-80 / Support for community mobi Individual Consult Under Implement Supervision Engineer for Uzg IDA / D2940 lization, youth engagement Post Open - National 0.00 2023-01-31 2023-01-23 2023-03-19 2023-03-28 2023-04-17 2024-03-01 ant Selection ation en rayon and communications IDA-CASA-CSP-IC-CDSO-202 Support for community mobi 3-81 / Community Developm Individual Consult Under Implement IDA / D2940 lization, youth engagement Post Open - National 0.00 2023-02-06 2023-01-25 2023-03-25 2023-04-03 2023-04-23 2024-03-07 ent and Support Officer for U ant Selection ation and communications zgen rayon of Osh oblast IDA-CASA-CSP-IC-CDSO-202 Support for community mobi 3-82 / Community Developm Individual Consult Under Implement IDA / D2940 lization, youth engagement Post Open - National 0.00 2023-02-06 2023-01-25 2023-03-25 2023-04-03 2023-04-23 2024-03-07 ent and Support Officer for N ant Selection ation and communications ookat rayon of Osh oblast IDA-CASA-CSP-IC-CDSO-202 Support for community mobi 3-83 / Community Developm Individual Consult Under Implement IDA / D2940 lization, youth engagement Post Open - National 0.00 2023-02-06 2023-01-25 2023-03-25 2023-04-03 2023-04-23 2024-03-07 ent and Support Officer for K ant Selection ation and communications adamjai rayon of Batken obla st Page 9 IDA-CASA-CSP-IC-2023-84 / Support for community mobi Individual Consult Under Implement Supervision Engineer Kara-Su IDA / D2940 lization, youth engagement Post Open - National 0.00 2023-02-20 2023-02-07 2023-04-08 2023-04-17 2023-05-07 2024-03-21 ant Selection ation u rayon and communications IDA-CASA-CSP-IC-2023-85 / Support for community mobi Individual Consult Under Implement Supervision EngineerKyzyl-Ky IDA / D2940 lization, youth engagement Post Open - National 0.00 2023-02-20 2023-02-07 2023-04-08 2023-04-17 2023-05-07 2024-03-21 ant Selection ation ia city and communications IDA-CASA-CSP-IC-DC-2022-0 5 / Consulting services for pr Support for community mobi eparation of the videoclip on Individual Consult Under Implement IDA / D2940 lization, youth engagement Post Direct - National 0.00 2023-02-27 2023-02-28 2023-03-13 2023-04-03 2023-03-15 2023-04-24 2023-03-21 2023-11-04 women's empowerment and ant Selection ation and communications economic empowerment in t he implementation of the CS P CASA-1000 IDA-CASA-CSP-IC-2023-88 / Support for community mobi Individual Consult Under Implement Supervision Engineer for Uzg IDA / D2940 lization, youth engagement Post Open - National 0.00 2023-06-26 2023-06-16 2023-08-14 2023-09-04 2023-10-09 2024-04-06 ant Selection ation en rayon and communications Page 10 PROCUREMENT PLAN (Textual Part) Project information: Kiribati South Tarawa Sanitation Project (STSP) – P176478 Project Implementation Agency: Ministry of Infrastructure and Sustainable Energy (MISE) Date of the Procurement Plan: March 15, 2022 Period covered by this Procurement Plan: June 2022 to December 2023 (18 months) Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (Fourth Edition, November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in 2002 Kiribati Procurement Act, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Secondhand Goods as specified under paragraph 5.11 of the Procurement Regulations – “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information. - Procurement Implementation Guidance (version as of April 2018): Making Procurement Work for Fragile and Small States in the Pacific under World Bank Investment Project Financing following the Procurement Regulations for IPF Borrowers [July 2016, revised in November 2017]. Procurement Plan Fiduciary_Procurement Risk: Substantial. Procurement WB Review Category Threshold CW $2,000,000.00 GO $500,000.00 NC $500,000.00 CS except INDV $500,000.00 CS INDV Only $300,000.00 Packag Project Procuremen Estimated WB review Expected e No. comp. Description Scope t Method Cost US$mil starting date Procurement Category: Works KS1 1 In BBB areas - Sewer service connections RFB 2.23 (1831), salt-water connections (3030), salt- Sewer and Salt-water water drains, sewer connections to schools connections and and health-centers, equipment Equipment - septage collection and transport equipment, sewer and salt-water O&M equipment for PUB 2 Construction of onsite Onsite systems in BBB areas and the RFB 5.15 KS2 sanitation systems villages, including communal toilets Total Works 7.38 Consultant Service 2 Management services Management services of PUB sewerage and QCBS 1.84 KS3 contract salt-water assets 2 Performance based contract for O&M of CQS 0.085 Community toilets community toilets between local council KS4 operations (owner) and service provider (community based organization or other third party) 2 Develop monitoring and evaluation CQS 0.459 procedures for sanitation performance and environmental health, including establishing KS5 M&E development required platforms/databases, documenting roles of PUB, MISE, MELAD, procurement of equipment and training for ongoing monitoring 2 Sector technical training and capacity CQS 0.240 building for construction, operation and Training and Capacity maintenance of sewered and on-site KS5 Building sanitation systems, including procurement of minor goods and tools to carry out maintenance activities of communal toilets 2 Review (i) institutional arrangements in CQS 0.200 sector, (ii) sector capacity, (iii) partnerships with local, national and international partners, (iv) identify recommendations for Institutional KS7 improved coordination, key capacity Assessments building needs, (v) coordinate study tours in response to capacity building needs, and (vi) identify and operationalize post- implementation support mechanisms. 2 Review (i) long-term financing options for CQS 0.030 capital and operational costs, (ii) tariff Financing Framework KS8 structure, and provide recommendations for review long-term sustainable financing/tariff options 2 Assess risks and impacts of sanitation CQS 0.090 Commented [MDC1]: Can KS7, KS8 and KS9 services, including climate impacts, be as one contract? Consultant firm contract and environmental impacts of current practices selection process to be CQS. Risk assessment and KS9 and develop recommendations for further Mitigation mitigation, needs and options for treatment and citywide inclusive sanitation options for unsewered 3B areas. 3 WASH and Community QCBS 1.4 WASH awareness raising, community KS10 Development mobilization activities 4 Implementation Project Implementation Assistance to CQS 0.766 KS11 Assistance support the PMU KS12 4 PMU Individual staffing of the PMU 2.43 Commented [MDC2]: I understand that the budget line intended for hiring individual 4 Ongoing community feedback survey-start, CQS 0.055 consultants to be stationed at the PMU to KS13 Community Feedback mid, end support MISE. Please list/detail out the consultant positions and its estimated service Total Consultant Service 5.165 cost. PROCUREMENT Kiribati : South Tarawa Sanitation Project PLAN General Information Country: Kiribati 2021-10-27 Bank’s Approval Date of the Original Procurement Plan: 2023-05-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P176478 GPN Date: Project Name: South Tarawa Sanitation Project Loan / Credit No: IDA / E0240 Ministry of Infrastructure and Sustainable Energy Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 1. Investments for improved KI-MISE-259203-CS-CDS / Pr IDA / E0240 sanitation access and liquid Post Direct Selection Direct 500,000.00 500,000.00 Signed 2021-11-01 2021-10-27 2021-11-13 2021-11-16 2021-11-25 2021-12-25 2022-05-24 oject Management Unit waste management KI-MISE-311215-CS-INDV / S Individual Consult Under Implement outh Tarawa Sanitation Proje IDA / E0240 4. Project Management Prior Open - National 384,000.00 0.00 2022-11-30 2022-12-05 2023-01-18 2023-06-07 2023-02-08 2023-06-27 2023-03-15 2025-03-04 ant Selection ation ct - Deputy Project Manager DPM (full time) KI-MISE-311216-CS-INDV / S Individual Consult Open - Internationa Under Implement outh Tarawa Sanitation Proje IDA / E0240 4. Project Management Prior 598,000.00 0.00 2022-12-17 2022-12-18 2023-02-04 2023-05-28 2023-02-25 2023-06-26 2023-04-01 2025-03-21 ant Selection l ation ct - Project Manager KI-MISE-311217-CS-INDV / S Individual Consult Under Implement afeguards Manager, Environ IDA / E0240 4. Project Management Post Open - National 288,000.00 0.00 2023-01-15 2023-04-03 2023-03-05 2023-03-26 2023-04-30 2025-04-19 ant Selection ation mental Specialist (full time) KI-MISE-312504-CS-INDV / S Individual Consult Under Implement IDA / E0240 4. Project Management Post Open - National 252,000.00 0.00 2022-11-30 2023-04-03 2023-01-18 2023-02-08 2023-03-15 2025-03-04 ocial Safeguards Specialist (f ant Selection ation ull time) KI-MISE-312505-CS-INDV / C 3. Community engagement Individual Consult Under Implement ommunity Engagement Speci IDA / E0240 Post Open - National 252,000.00 0.00 2023-01-15 2023-04-03 2023-03-05 2023-03-26 2023-04-30 2023-05-07 and support ant Selection ation alist (full time) KI-MISE-312506-CS-INDV / Pr Individual Consult Under Implement IDA / E0240 4. Project Management Post Open - National 280,000.00 0.00 2023-01-15 2023-04-03 2023-03-05 2023-03-26 2023-04-30 2025-04-19 oject Accountant (full time) ant Selection ation KI-MISE-312508-CS-INDV / E Individual Consult Under Implement IDA / E0240 4. Project Management Prior Open - National 312,000.00 0.00 2023-02-15 2023-02-16 2023-04-05 2023-04-26 2023-05-31 2023-11-27 ngineer (full time) ant Selection ation KI-MISE-312509-CS-INDV / M Individual Consult IDA / E0240 4. Project Management Post Open - National 264,000.00 0.00 Under Review 2023-06-01 2023-06-21 2023-07-20 2023-08-10 2023-09-14 2025-09-03 &E Specialist (full time) ant Selection KI-MISE-312510-CS-INDV / O Individual Consult IDA / E0240 4. Project Management Post Open - National 93,600.00 0.00 Under Review 2023-06-01 2023-06-21 2023-07-20 2023-08-10 2023-09-14 2025-09-03 ffice Assistant (full time) ant Selection KI-MISE-365250-CS-INDV / Pr Individual Consult Pending Impleme IDA / E0240 4. Project Management Post Open - National 100,000.00 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-24 2024-03-22 ocurement Officer ant Selection ntation Page 1 PROCUREMENT PLAN Project information: Country: Bangladesh Project Name: Bangladesh COVID-19 Emergency Preparedness and Response Project P-number: P173757 Project Implementation agency: (i) Ministry of Health and Family Welfare (MoHFW) (ii) Central Medical Stores Depot (CMSD) (iii) Public Works Department (PWD) Period covered by this Procurement Plan: Entire Project Period Preamble In accordance with paragraph 5.9 of the World Bank Procurement Regulations for IPF Borrowers, July 2016, revised November 2017 and August 2018 (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to record all procurement actions for the Project, including preparing, updating and clearing its Procurement Plan, and seeking and receiving the Bank’s review and No-objection to procurement actions as required. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents (SPDs) shall be used for goods, works and non- consulting services where international competition is required and for consulting services, including their respective forms of contract. National Procurement Arrangements: In accordance with paragraph 5.3 of the World Bank Procurement Regulations, when approaching the national market, as agreed in the Procurement Plan, the country’s own procurement procedures may be used. These procurement procedures shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti- Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Act 2006 and the Public Procurement Rules 2008, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: i. Lottery in award of contracts shall not be allowed; ii. Bidders’ qualification[s]/experience requirement[s] shall be mandatory; iii. Bids shall not be rejected based on percentage above or below the estimated cost; iv. Model Bidding Documents agreed with the Bank shall be used for all national open competitive procurement; v. The eligibility of bidders shall be as defined under Section III of the World Bank Procurement Regulations for IPF Borrowers: accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. vi. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. vii. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. As per paragraph 5.4 of the Procurement Regulations, the “Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework” as attached to this document shall form part of the Model Bidding Documents. Leased Assets: Not Applicable. Procurement of Second-Hand Goods: as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables - Applicable” Domestic preference: as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works) as follows: Goods: Applicable; Works: Not applicable. Hands-on Expanded Implementation Support (HEIS): as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Bank’s Procurement Prior Review Thresholds: As this is an emergency response project, there will be no prior review for all procurement during the immediate response period. The project will also have increased threshold for Request for Quotations (RFQ) and national procurement, as applicable in emergency projects. Fraud and Corruption (F&C) Checklist: Fraud and Corruption (F&C) checklist, as developed and provided by the Bank, shall be properly filled in during the evaluation and be attached with the evaluation report in case of contracts following national competitive procurement and request for quotations. Attachment 1 Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. Title of the person signing the Letter: PROCUREMENT Bangladesh : COVID-19 Emergency Response and Pandemic Preparedness Project PLAN General Information Country: Bangladesh 2021-05-26 Bank’s Approval Date of the Original Procurement Plan: 2023-05-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173757 GPN Date: 2020-07-21 Project Name: COVID-19 Emergency Response and Pandemic Preparedness Project Loan / Credit No: IDA / 66050 Public Works Department Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned DHK-2/WB-AIIB/WD-1 / Estab National Procure lishment of Modern Microbiol ment Document - ogy Laboratory with PCR (Dh Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 177,305.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 aka Medical College, Sir Sali OVID-19 Response nvelope 1 ss (Non Bank-SPD mullah Medical College Mitfor ) d Hospital and Mugda 500 Be dded General Hospital ) DHK-3/WB-AIIB/WD-2 / 1) Est ablishment of Modern Microb iology Lab at Kurmitola Gen National Procure eral Hospital. ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 2) Establishment of 10 bed IC IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 591,017.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 U at Shaheed Sohrawardi M. ss (Non Bank-SPD C.Hospital. ) 3) Estab. of medical centre in HSIA 4) BSL lab at IEDCR 5) Estab. of 5 bed ICU in IDH Medical gas pipe.sy / 1) Es SAVAR/WB-AIIB/WD-3 6) tablishment of Modern Micro National Procure biology Lab in Shaheed Tajud ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 din Ahmed M.C.H IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 153,664.00 0.00 Canceled 2021-04-25 2021-04-28 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 2) Establishment of 10 bed IC ss (Non Bank-SPD U at Colonel Malek M.C.H, Ma ) nikganj 3) Installation of Medical gas pipeline system. GOPAL/WB-AIIB/WD-4 / 1) Es tablishment of Modern Micro National Procure biology Lab at Shekh Sayera ment Document - Khatun Medical College Hospi Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 153,664.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 tal. OVID-19 Response nvelope 1 ss (Non Bank-SPD 2) Establishment of 10 bed IC ) U at Faridpur M.C.H 3) Installation of gas pipeline system. National Procure RAJ/WB-AIIB/WD-5 / 1) Establ ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 ishment of Modern Microbiolo IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 59,102.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 gy Lab at Rajshahi Medical C ss (Non Bank-SPD ollege Hospital. ) National Procure PABN/WB-AIIB/WD-6 / 1) Est ment Document - ablishment of Modern Microb Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 59,102.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 iology Lab with PCR at Pabna OVID-19 Response nvelope 1 ss (Non Bank-SPD Medical College Hospital. ) BAGU/WB-AIIB/WD-7 / 1) Est ablishment of Modern Microb iology Lab with PCR in Shahe National Procure ed Ziaur Rahman Medical Col ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 lege and Hospital. IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 153,664.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 2) Establishment of 10 bed IC ss (Non Bank-SPD U at Shaheed Ziaur Rahman ) Medical College and Hospital at Bogura. 3) Installation of gaspipeline system. KHUL/WB-AIIB/WD-8 / 1) Est National Procure ablishment of Modern Microb ment Document - iology Lab with PCR in Khuln Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 224,586.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 a and Shatkhira Medical Colle OVID-19 Response nvelope 1 ss (Non Bank-SPD ge hospital. ) 2) Establishment of medical centre in Mongla seaport at B agerhat National Procure JESOR/WB-AIIB/WD-9 / Establ ment Document - ishment of Modern Microbiolo Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 59,102.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 gy lab with PCR in Kushtia M OVID-19 Response nvelope 1 ss (Non Bank-SPD edical College Hospital. ) BAR/WB-AIIB/WD-10 / 1) Est ablishment of Modern Microb iology Lab with PCR in Barish National Procure al Medical College and Hospit ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 al. IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 153,664.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 2) Establishment of 10 bed IC ss (Non Bank-SPD U at Shere Bangla Medical C ) ollege and Hospital, Barishal. 3) Installation of gaspipeline system. National Procure CTG-1/WB-AIIB/WD-11 / 1) E ment Document - stablishment of Modern Micr Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 118,203.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 obiology Lab with PCR in Cha OVID-19 Response nvelope 1 ss (Non Bank-SPD ttogram Medical College and ) Hospital. CTG-2/WB-AIIB/WD-12 / 1) E stablishment of Modern Micr obiology Lab with PCR in Cox' s Bazar Medical College and National Procure Hospital. ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 2) Estab. of medical center at IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 437,352.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 Chattagram seaport and SASI ss (Non Bank-SPD A ) 3) Estab. of 5 bed ICU at IDH Chattagram . 4) Installation of gaspipeline system. 5) BSL 3 LAB National Procure RANGA/WB-AIIB/WD-13 / 1) ment Document - Establishment of Modern Mic Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 118,203.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 robiology Lab with PCR in Ra OVID-19 Response nvelope 1 ss (Non Bank-SPD ngamati Medical College and ) Hospital. Page 1 National Procure CUM/WB-AIIB/WD-14 / 1) Est ment Document - ablishment of Modern Microb Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 59,102.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 iology Lab with PCR in Chand OVID-19 Response nvelope 1 ss (Non Bank-SPD pur Medical College and Hos ) pital. SYLHET/WB-AIIB/WD-15 / 1) Establishment of Modern Mic robiology Lab with PCR in Syl het, Shekh Hasina and Habig National Procure anj Medical College Hospital. ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 260,047.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 2) Estab. of 10 bed ICU at Syl ss (Non Bank-SPD het MAG Osmani Medical Coll ) ege Hospital. 3)Estab. of medical center 3) Installation of gaspipeline system. National Procure RANG/WB-AIIB/WD-16 / 1) Es ment Document - tablishment of Modern Micro Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 59,102.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 biology Lab with PCR in Rang OVID-19 Response nvelope 1 ss (Non Bank-SPD pur Medical College and Hos ) pital. National Procure DHK-3/WB-AIIB/WD-1 / Const ment Document - ruction of Building for Medica Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 177,305.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 l Waste Management system OVID-19 Response nvelope 1 ss (Non Bank-SPD s at Shaheed Sohrawardi Me ) dical College Hospital. DHK-4/WB-AIIB/WD-2 / 1) Co nstruction of Building for Med ical Waste Management syst National Procure ems( Narayanganj 300 bede ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 d sadar hospital and Narshin IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 1,170,213.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 di sadar hospital) ss (Non Bank-SPD 2) Establishment of 20 bed is ) olation unit and 10 bed ICU a t Narshindi sadar hospital. 3) Installation of medical gas pipe SAVAR/WB-AIIB/WD-3/1 / Co National Procure nstruction of Building for Med ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 ical Waste Management Syst IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 177,305.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 em at Colonel Malek Medical ss (Non Bank-SPD College Hospital, Manikganj ) GOPAL/WB-AIIB/WD-4/1 / 1) Construction of Building for Medical Waste Management National Procure System at Faridpur Medical C ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 ollege Hospital. IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 1,808,511.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 2) Estab. of 20 bed isolation ss (Non Bank-SPD unit and 10 bed ICU at Sharia ) tpur and Rajbari sadar hospit al 3) Installation of medical gas p. sy. at Shariatpur Rajbari RAJ/WB-AIIB/WD-5/1 / 1) Con struction of Building for Medi cal Waste Management Syste National Procure m at Chapainowabganj Gene ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 ral Hospital. IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 945,626.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 2) Establishment of 20 bed is ss (Non Bank-SPD olation unit and 10 bed ICU a ) t Chapainowabganj sadar Ho spital. 3) Installation of medical gas pipeline system at Chapai.S. HPABN/WB-AIIB/WD-6/1 / 1) C onstruction of Building for Me dical Waste Management Sys National Procure tem at Natore District Hospit ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 al. IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 1,808,511.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 2) Establishment of 20 bed is ss (Non Bank-SPD olation unit and 10 bed ICU a ) t Shirajganj and Natore sadar Hospital 3)Instal. of medical gas pipeli ne sys. at Shirajganj ,Natore BAGU/WB-AIIB/WD-7/1 / 1) C S.H onstruction of Building for Me dical Waste Management Sys National Procure tem at Shaheed Ziaur Rahma ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 n Medical College. IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 992,908.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 2) Establishment of 20 bed is ss (Non Bank-SPD olation unit and 10 bed ICU a ) t Joypurhat sadar hospital. 3)Installation of medical gas pipeline system at Joypurhat sadrH KHUL/WB-AIIB/WD-8/1 / 1) C onstruction of Building for Me dical Waste Management Sys National Procure tem at Khulna M.C.H ment Document - 2) Establishment of 20 bed is Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 992,908.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 olation unit and 10 bed ICU a OVID-19 Response nvelope 1 ss (Non Bank-SPD t Khulna Sadar hospital ) 3) Installation of medical gas pipeline system at Khulna Sa dar hospital. JESOR/WB-AIIB/WD-9/1 / 1)C onstruction of Building for Me dical Waste Management Sys National Procure tem at jashore District Hospit ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 al. IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 3,900,709.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 2)Estab. of 20 bed isolation u ss (Non Bank-SPD nit and 10 bed ICU at Narail,J ) hinaidah,Kushtia,Magura,Me herpur sadar.H 3)Instal. of medical gas pipeli ne system at above hospitals BAR/WB-AIIB/WD-10/1 / 1) C onstruction of Building for Me dical Waste Management Sys National Procure tem at shere bangla M.C.H,B ment Document - arishal, Bhola District H. Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 3,617,021.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 2)Establishment of 20 bed is OVID-19 Response nvelope 1 ss (Non Bank-SPD olation unit and 10 bed ICU a ) t Bhola,Jhalokathi,Barguna,Pi rojpur S.H. 3) Instal. of medical gas pipel ine system Page 2 CUM/WB-AIIB/WD-11 / 1) Co nstruction of Building for Med ical Waste Management Syst National Procure em in feni District hospital an ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 d Cumilla M.C IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 1,168,204.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 2)Establishment of 20 bed is ss (Non Bank-SPD olation unit and 10 bed ICU a ) t Laxmipur sadar hospital 3) Installation of medical gas pipeline system at Laxmipur sadar.H RANGM/WB-AIIB/WD-12 / 1) Establishment of 20 bed isola National Procure tion unit and 10 bed ICU at R ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 angamati,Khagrachori,Banda IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 2,446,809.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 rban sadar hospital ss (Non Bank-SPD 2)Installation of medical gas ) pipeline system at Rangamat i,Khagrachori,Bandarban sad ar hospital SYLHET/WB-AIIB/WD-13 / 1)C onstruction of Building for Me dical Waste Management Sys National Procure tem at Sylhet MAG Osmani M ment Document - .C.H and Moulvibazar District Component 1: Emergency C Single Stage - One E 2022-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 1,170,213.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 Hospital OVID-19 Response nvelope 1 ss (Non Bank-SPD 2)Establishment of 20 bed is ) olation unit and 10 bed ICU a t Sylhet S.H 3)Installation of medical gas pipeline system at Sylhet S.H DINJ/WB-AIIB/WD-14 / 1) Con struction of Building for Medi cal Waste Management Syste National Procure m at M.A.Rahim M.C.H Dinajp ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 ur, Thakurgaon,Nilphamari D. IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 3,745,035.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 H ss (Non Bank-SPD 2) Estab. of 20 bed isolation ) unit and 10 bed ICU at Dinaj pur, Thakurgaon,Nilphamari , Pnchagar sadar H. 3)Instal. of medical gas P.S RANG/WB-AIIB/WD-16/1 / 1) Establishment of 20 bed isola National Procure tion unit and 10 bed ICU at G ment Document - Component 1: Emergency C Single Stage - One E 2022-02-1 aibandha,Lalmonirhat sadar IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 1,631,206.00 0.00 Canceled 2021-04-25 2021-04-30 2021-06-11 2021-07-11 2021-08-15 OVID-19 Response nvelope 1 Hospital ss (Non Bank-SPD 2) Installation of medical gas ) pipeline system at Gaibandh a,Lalmonirhat sadar Hospital DHK-3/WB-AIIB/WD-1-C / Co National Procure nstruction of Building for Med ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 ical Waste Management Syst IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 176,824.20 0.00 2021-07-25 2021-07-30 2021-09-10 2021-10-10 2021-11-14 OVID-19 Response nvelope lementation 3 ems at Shaheed Sohrawardi ss (Non Bank-SPD Medical College Hospital ) DHK-4/WB-AIIB/WD-2/A-C / C National Procure onstruction of Building for M ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 edical Waste Management Sy IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 353,648.50 0.00 2021-07-25 2021-07-30 2021-09-10 2021-10-10 2021-11-14 OVID-19 Response nvelope lementation 3 stems (Narayanganj 300 bed ss (Non Bank-SPD sadar Hospital and Narsingdi ) Sadar Hospital). National Procure DHK-4/WB-AIIB/WD-2/B-C / E ment Document - stablishment of 20 bed Isolati Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 707,296.90 0.00 2021-07-25 2021-07-30 2021-09-10 2021-10-10 2021-11-14 on unit & 10 bed ICU at Narsi OVID-19 Response nvelope lementation 3 ss (Non Bank-SPD ngdi Sadar Hospital ) National Procure DHK-4/WB-AIIB/WD-2/C-C / I ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 nstallation of Medical Gas Pip IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 106,094.50 0.00 2021-07-25 2021-07-30 2021-09-10 2021-10-10 2021-11-14 OVID-19 Response nvelope lementation 3 eline system at Narsingdi Sa ss (Non Bank-SPD dar Hospital ) SAVAR/WB-AIIB/WD-3-C / Co National Procure nstruction of Building for Med ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 ical Waste Management Syst IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 176,824.20 0.00 2021-07-25 2021-07-30 2021-09-10 2021-10-10 2021-11-14 OVID-19 Response nvelope lementation 3 ems at Colonel Malek Medica ss (Non Bank-SPD l College Hospital,Manikgonj ) National Procure GOPAL/WB-AIIB/WD-4/A-C / ment Document - Construction of Building for Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 176,824.20 0.00 2021-07-25 2021-07-30 2021-09-10 2021-10-10 2021-11-14 Medical Waste Management OVID-19 Response nvelope lementation 3 ss (Non Bank-SPD Systems in Faridpur Medical ) College Hospital National Procure GOPAL/WB-AIIB/WD-4/B / Est ment Document - ablishment of 20 bed Isolatio Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 1,414,593.90 0.00 2021-07-25 2021-07-30 2021-09-10 2021-10-10 2021-11-14 n unit & 10 bed ICU at Rajbar OVID-19 Response nvelope lementation 3 ss (Non Bank-SPD i & Shariatpur Sadar Hospital ) National Procure GOPAL/WB-AIIB/WD-4/C-C / I ment Document - nstallation of Medical Gas Pip Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 212,189.10 0.00 2021-07-25 2021-07-30 2021-09-10 2021-10-10 2021-11-14 eline system at Rajbari Sadar OVID-19 Response nvelope lementation 3 ss (Non Bank-SPD Hospital and Shariatpur Sada ) r Hospital National Procure RAJ/WB-AIIB/WD-5/A-C / Con ment Document - struction of Building for Medi Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 176,824.20 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 cal Waste Management Syste OVID-19 Response nvelope lementation 4 ss (Non Bank-SPD ms atChapaiNowabganj Gene ) ral Hospital National Procure RAJ/WB-AIIB/WD-5/B-C / Esta ment Document - blishment of 20 bed Isolation Component 1: Emergency C Single Stage - One E 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 660,143.80 521,152.68 Signed 2021-07-26 2021-09-05 2021-07-31 2021-09-11 2021-09-29 2021-10-11 2021-10-30 2021-11-15 2021-11-18 unit & 10 bed ICU at Chapain OVID-19 Response nvelope 4 ss (Non Bank-SPD awabganj Sadar Hospital ) National Procure RAJ/WB-AIIB/WD-5/C-C / Inst ment Document - Component 1: Emergency C Single Stage - One E 2022-05-1 allation of Medical Gas Pipeli IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 106,094.50 83,459.18 Signed 2021-07-26 2021-08-05 2021-07-31 2021-09-11 2021-08-29 2021-10-11 2021-10-30 2021-11-15 2021-11-26 OVID-19 Response nvelope 4 ne system at Chapainawabga ss (Non Bank-SPD nj Sadar Hospital ) National Procure PABN/WB-AIIB/WD-6/A-C / Co ment Document - nstruction of Building for Med Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 176,824.20 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 ical Waste Management Syst OVID-19 Response nvelope lementation 4 ss (Non Bank-SPD ems in Natore District Hospit ) al National Procure PABN/WB-AIIB/WD-6/B-C / Es ment Document - tablishment of 20 bed Isolati Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 1,414,593.90 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 on unit & 10 bed ICU at Siraj OVID-19 Response nvelope lementation 4 ss (Non Bank-SPD ganj & Natore Sadar Hospital ) Page 3 National Procure PABN/WB-AIIB/WD-6/C-C / In ment Document - stallation of Medical Gas Pipe Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 212,189.10 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 line system at Sirajganj Sada OVID-19 Response nvelope lementation 4 ss (Non Bank-SPD r Hospital and Natore Sadar ) Hospital BAGU/WB-AIIB/WD-7/A-C / C National Procure onstruction of Building for Me ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 dical Waste Management Sys IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 176,824.20 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 OVID-19 Response nvelope lementation 4 tems in Shaheed ziaur Rahm ss (Non Bank-SPD an Medical College Hospital ) National Procure BAGU/WB-AIIB/WD-7/B-C / Es ment Document - tablishment of 20 bed Isolati Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 707,296.90 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 on unit & 10 bed ICU at Joypu OVID-19 Response nvelope lementation 4 ss (Non Bank-SPD rhat Sadar Hospital ) National Procure BAGU/WB-AIIB/WD-7/C-C / In ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 stallation of Medical Gas Pipe IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 106,094.50 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 OVID-19 Response nvelope lementation 4 line system at Joypurhat Sad ss (Non Bank-SPD ar Hospital ) National Procure KHUL/WB-AIIB/WD-8/A-C / Co ment Document - nstruction of Building for Med Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 176,824.20 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 ical Waste Management Syst OVID-19 Response nvelope lementation 4 ss (Non Bank-SPD ems in Khulna Medical Colleg ) e Hospital National Procure KHUL/WB-AIIB/WD-8/B-C / Es ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 tablishment of 20 bed Isolati IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 707,296.90 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 OVID-19 Response nvelope lementation 4 on unit & 10 bed ICU at Khul ss (Non Bank-SPD na Sadar Hospital ) National Procure KHUL/WB-AIIB/WD-8/C-C / In ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 stallation of Medical Gas Pipe IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 106,094.50 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 OVID-19 Response nvelope lementation 4 line system at Khulna Sadar ss (Non Bank-SPD Hospital ) National Procure JESOR/WB-AIIB/WD-9/A-C / C ment Document - onstruction of Building for Me Component 1: Emergency C Single Stage - One E 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 176,824.20 101,905.35 Signed 2021-07-26 2022-03-14 2021-07-31 2021-09-11 2022-03-31 2021-10-11 2022-04-21 2021-11-15 2022-05-24 dical Waste Management Sys OVID-19 Response nvelope 4 ss (Non Bank-SPD tems in Jashore District Hospi ) tal National Procure JESOR/WB-AIIB/WD-9/B-C / E ment Document - stablishment of 20 bed Isolati Component 1: Emergency C Single Stage - One E 1,310,181.9 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 1,768,242.40 Signed 2021-07-26 2021-10-26 2021-07-31 2021-09-11 2021-11-18 2021-10-11 2021-12-02 2021-11-15 2022-01-07 on unit & 10 bed ICU at Magu OVID-19 Response nvelope 8 4 ss (Non Bank-SPD ra, Jhinaidah & Kushtia Sadar ) Hospital National Procure JESOR/WB-AIIB/WD-9/C-C / E ment Document - stablishment of 20 bed Isolati Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 1,414,593.90 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 on unit & 10 bed ICU at Narai OVID-19 Response nvelope lementation 4 ss (Non Bank-SPD l, Meherpur Sadar Hospital ) National Procure JESOR/WB-AIIB/WD-9/D-C / In ment Document - stallation of Medical Gas Pipe Component 1: Emergency C Single Stage - One E 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 318,283.60 192,913.65 Signed 2021-07-26 2022-03-01 2021-07-31 2021-09-11 2022-04-04 2021-10-11 2022-05-24 2021-11-15 2022-06-14 line system at Jhinaidah, Kus OVID-19 Response nvelope 4 ss (Non Bank-SPD htia & Magura Sadar Hospita ) l National Procure JESOR/WB-AIIB/WD-9/E-C / In ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 stallation of Medical Gas Pipe IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 212,189.10 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 OVID-19 Response nvelope lementation 4 line system at Narail, Meher ss (Non Bank-SPD pur Sadar Hospital ) BAR /WB-AIIB/WD-10/A-C / C National Procure onstruction of Building for Me ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 dical Waste Management Sys IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 353,648.50 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 OVID-19 Response nvelope lementation 4 tems (Shere Bangla Medical ss (Non Bank-SPD College Hospital, Barishal & ) Bhola District Hospital ) National Procure BAR /WB-AIIB/WD-10/B-C / E ment Document - stablishment of 20 bed Isolati Component 1: Emergency C Single Stage - One E 1,378,748.0 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 1,414,593.90 Signed 2021-07-26 2021-06-29 2021-07-31 2021-09-11 2021-08-04 2021-10-11 2021-08-12 2021-11-15 2021-09-06 on unit & 10 bed ICU at Barg OVID-19 Response nvelope 8 4 ss (Non Bank-SPD una & Bhola Sadar Hospital ) National Procure BAR /WB-AIIB/WD-10/C-C / E ment Document - stablishment of 20 bed Isolati Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 1,414,593.90 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 on unit & 10 bed ICU at Jhalo OVID-19 Response nvelope lementation 4 ss (Non Bank-SPD khati & Pirojpur Sadar Hospit ) al National Procure BAR /WB-AIIB/WD-10/D-C / In ment Document - stallation of Medical Gas Pipe Component 1: Emergency C Single Stage - One E 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 212,189.10 187,773.16 Signed 2021-07-26 2021-06-29 2021-07-31 2021-09-11 2021-08-04 2021-10-11 2021-08-14 2021-11-15 2021-09-08 line system at Barguna & Bh OVID-19 Response nvelope 4 ss (Non Bank-SPD ola Sadar Hospital ) National Procure BAR /WB-AIIB/WD-10/E-C / In ment Document - stallation of Medical Gas Pipe Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 212,189.10 0.00 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 line system at Jhalokhati & Pi OVID-19 Response nvelope lementation 4 ss (Non Bank-SPD rojpur Sadar Hospital ) CUM/WB-AIIB/WD-11/A-C / C National Procure onstruction of Building for Me ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 dical Waste Management Sys IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 353,648.50 0.00 2021-07-27 2021-08-01 2021-09-12 2021-10-12 2021-11-16 OVID-19 Response nvelope lementation 5 tems (Feni District Hospital a ss (Non Bank-SPD nd Cumilla Medical College H ) ospital) National Procure CUM/WB-AIIB/WD-11/B-C / E ment Document - stablishment of 20 bed Isolati Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 707,296.90 0.00 2021-07-27 2021-08-01 2021-09-12 2021-10-12 2021-11-16 on unit & 10 bed ICU at Laxm OVID-19 Response nvelope lementation 5 ss (Non Bank-SPD ipur Sadar Hospital ) National Procure CUM/WB-AIIB/WD-11/C-C / In ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 stallation of Medical Gas Pipe IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 106,094.50 0.00 2021-07-27 2021-08-01 2021-09-12 2021-10-12 2021-11-16 OVID-19 Response nvelope lementation 5 line system at Laxmipur Sad ss (Non Bank-SPD ar Hospital ) SYLHET/WB-AIIB/WD-13/A-C National Procure / Construction of Building for ment Document - Medical Waste Management Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 353,648.50 0.00 2021-07-27 2021-08-01 2021-09-12 2021-10-12 2021-11-16 Systems (Sylhet MAG Osmani OVID-19 Response nvelope lementation 5 ss (Non Bank-SPD Medical College Hospital & M ) oulvibazar District Hospital) National Procure SYLHET/WB-AIIB/WD-13/B-C ment Document - / Establishment of 20 bed Isol Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 707,296.90 0.00 2021-07-27 2021-08-01 2021-09-12 2021-10-12 2021-11-16 ation unit & 10 bed ICU at Syl OVID-19 Response nvelope lementation 5 ss (Non Bank-SPD het Sadar Hospital ) Page 4 National Procure SYLHET/WB-AIIB/WD-13/C-C ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 / Installation of Medical Gas P IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 106,094.50 0.00 2021-07-27 2021-08-01 2021-09-12 2021-10-12 2021-11-16 OVID-19 Response nvelope lementation 5 ipeline system at Sylhet Sada ss (Non Bank-SPD r Hospital ) DINJ/WB-AIIB/WD-14/A-C / Co National Procure nstruction of Building for Med ment Document - ical Waste Management Syst Component 1: Emergency C Single Stage - One E Pending Imp 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 530,472.70 0.00 2021-07-27 2021-08-01 2021-09-12 2021-10-12 2021-11-16 ems (M Abdur Rahim Medical OVID-19 Response nvelope lementation 5 ss (Non Bank-SPD College Hospital, Dinajpur, T ) hakurgaon & Nilphamary Dis trict Hospital) National Procure DINJ/WB-AIIB/WD-14/B-C / Es ment Document - tablishment of 20 bed Isolati Component 1: Emergency C Single Stage - One E 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 707,296.90 569,843.32 Signed 2021-07-27 2021-11-01 2021-08-01 2021-09-12 2021-12-07 2021-10-12 2021-12-23 2021-11-16 2022-01-20 on unit & 10 bed ICU at Dinaj OVID-19 Response nvelope 5 ss (Non Bank-SPD pur Sadar Hospital ) National Procure DINJ/WB-AIIB/WD-14/C-C / Es ment Document - tablishment of 20 bed Isolati Component 1: Emergency C Single Stage - One E 1,923,637.5 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 2,072,733.70 Signed 2021-07-27 2021-08-29 2021-08-01 2021-09-12 2021-10-06 2021-10-12 2021-10-31 2021-11-16 2021-11-10 on unit & 10 bed ICU at Panc OVID-19 Response nvelope 2 5 ss (Non Bank-SPD hagar, Thakurgaon & Nilpha ) mari Sadar Hospital National Procure DINJ/WB-AIIB/WD-14/D-C / In ment Document - Component 1: Emergency C Single Stage - One E 2022-05-1 stallation of Medical Gas Pipe IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 106,094.50 80,615.29 Signed 2021-07-27 2021-10-27 2021-08-01 2021-09-12 2021-11-22 2021-10-12 2022-01-12 2021-11-16 2022-02-02 OVID-19 Response nvelope 5 line system at Dinajpur, Sada ss (Non Bank-SPD r Hospital ) National Procure DINJ/WB-AIIB/WD-14/E-C / In ment Document - stallation of Medical Gas Pipe Component 1: Emergency C Single Stage - One E 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 318,283.60 235,638.23 Signed 2021-07-27 2021-09-13 2021-08-01 2021-09-12 2021-10-17 2021-10-12 2021-12-09 2021-11-16 2021-12-23 line system at Panchagar, Th OVID-19 Response nvelope 5 ss (Non Bank-SPD akurgaon & Nilphamari Sadar ) Hospital National Procure RANG/WB-AIIB/WD-15/A-C / ment Document - Establishment of 20 bed Isola Component 1: Emergency C Single Stage - One E 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 707,296.90 606,235.70 Signed 2021-07-27 2021-07-26 2021-08-01 2021-09-12 2021-09-01 2021-10-12 2021-10-21 2021-11-16 2021-11-02 tion unit & 10 bed ICU at Gai OVID-19 Response nvelope 5 ss (Non Bank-SPD bandah Sadar Hospital ) National Procure RANG/WB-AIIB/WD-15/B-C / ment Document - Establishment of 20 bed Isola Component 1: Emergency C Single Stage - One E 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 707,296.90 589,168.37 Signed 2021-07-27 2021-09-21 2021-08-01 2021-09-12 2021-10-18 2021-10-12 2021-10-25 2021-11-16 2021-11-07 tion unit & 10 bed ICU at Lal OVID-19 Response nvelope 5 ss (Non Bank-SPD monirhat Sadar Hospital ) National Procure RANG/WB-AIIB/WD-15/C-C / I ment Document - Component 1: Emergency C Single Stage - One E 2022-05-1 nstallation of Medical Gas Pip IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 106,094.50 76,212.22 Signed 2021-07-27 2021-09-02 2021-08-01 2021-09-12 2021-09-27 2021-10-12 2021-11-23 2021-11-16 2021-12-23 OVID-19 Response nvelope 5 eline system at at Gaibanda ss (Non Bank-SPD h Sadar Hospital ) National Procure RANG/WB-AIIB/WD-15/D-C / I ment Document - nstallation of Medical Gas Pip Component 1: Emergency C Single Stage - One E 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 106,094.50 76,759.40 Signed 2021-07-27 2021-09-02 2021-08-01 2021-09-12 2021-09-27 2021-10-12 2022-08-11 2021-11-16 2021-12-03 eline system at at Lalmonirh OVID-19 Response nvelope 5 ss (Non Bank-SPD at Sadar Hospital ) National Procure CUM/WB-AIIB/WD-14-R / Esta ment Document - blishment of Modern Microbi Component 1: Emergency C Single Stage - One E 2022-06-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 58,823.50 47,329.98 Signed 2021-09-03 2021-05-24 2021-09-08 2021-10-20 2021-06-13 2021-11-19 2021-06-16 2021-12-24 2021-07-20 ology Laboratory with PCR (C OVID-19 Response nvelope 2 ss (Non Bank-SPD handpur Medical College Hos ) pital) National Procure DHK-2/WB-AIIB/WD-1/A-R / E ment Document - stablishment of Modern Micr Component 1: Emergency C Single Stage - One E 2022-06-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 58,823.50 51,870.65 Signed 2021-09-03 2021-05-20 2021-09-08 2021-10-20 2021-06-14 2021-11-19 2021-07-07 2021-12-24 2021-07-15 obiology Laboratory with PCR OVID-19 Response nvelope 2 ss (Non Bank-SPD (Dhaka Medical College Hosp ) ital) National Procure DHK-2/WB-AIIB/WD-1/B-R / E ment Document - stablishment of Modern Micr Component 1: Emergency C Single Stage - One E 2022-06-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 58,823.50 50,970.40 Signed 2021-09-03 2021-05-20 2021-09-08 2021-10-20 2021-06-14 2021-11-19 2021-07-07 2021-12-24 2021-07-15 obiology Laboratory with PCR OVID-19 Response nvelope 2 ss (Non Bank-SPD ( Sir Salimullah Medical Colle ) ge Mitford Hospital) National Procure DHK-2/WB-AIIB/WD-1/C-R / E ment Document - stablishment of Modern Micr Component 1: Emergency C Single Stage - One E 2022-06-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 58,823.50 58,244.02 Signed 2021-09-03 2021-05-18 2021-09-08 2021-10-20 2021-06-10 2021-11-19 2021-06-28 2021-12-24 2021-07-30 obiology Laboratory with PCR OVID-19 Response nvelope 2 ss (Non Bank-SPD (Mugda 500 Bedded General ) Hospital). SAVAR/WB-AIIB/WD-3/A-R / E National Procure stablishment of Modern Micr ment Document - Component 1: Emergency C Single Stage - One E 2022-06-2 obiology Laboratory with PCR IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 19,117.60 16,932.76 Signed 2021-09-03 2021-04-21 2021-09-08 2021-10-20 2021-05-12 2021-11-19 2021-05-19 2021-12-24 2021-06-11 OVID-19 Response nvelope 2 in Shaheed Tajuddin Ahmed ss (Non Bank-SPD Medical College Hospital ) National Procure SAVAR/WB-AIIB/WD-3/B-R / E ment Document - stablishment of 10 bed ICU a Component 1: Emergency C Single Stage - One E 2022-06-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 58,764.70 47,306.97 Signed 2021-09-03 2021-04-21 2021-09-08 2021-10-20 2021-05-12 2021-11-19 2021-05-17 2021-12-24 2021-05-25 t Colonel Malek Medical Colle OVID-19 Response nvelope 2 ss (Non Bank-SPD ge Hospital, Manikgonj ) National Procure GOPAL/WB-AIIB/WD-4/B-R / E ment Document - Component 1: Emergency C Single Stage - One E 2022-06-2 stablishment of 10 bed ICU a IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 35,294.10 25,480.44 Signed 2021-09-03 2021-05-06 2021-09-08 2021-10-20 2021-05-27 2021-11-19 2021-06-01 2021-12-24 2021-06-11 OVID-19 Response nvelope 2 t Faridpur Medical College Ho ss (Non Bank-SPD spital ) National Procure RAJ/WB-AIIB/WD-5-R / Establi ment Document - shment of Modern Microbiolo Component 1: Emergency C Single Stage - One E 2022-06-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 58,823.50 52,617.75 Signed 2021-09-03 2021-05-25 2021-09-08 2021-10-20 2021-06-14 2021-11-19 2021-06-16 2021-12-24 2021-05-10 gy Laboratory with PCR (Rajs OVID-19 Response nvelope 2 ss (Non Bank-SPD hahi Medical College Hospital ) ) National Procure PABN/WB-AIIB/WD-6-R / Esta ment Document - blishment of Modern Microbi Component 1: Emergency C Single Stage - One E 2022-06-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 58,823.50 52,046.29 Signed 2021-09-03 2021-08-05 2021-09-08 2021-10-20 2021-09-06 2021-11-19 2021-10-12 2021-12-24 2021-10-20 ology Laboratory with PCR (P OVID-19 Response nvelope 2 ss (Non Bank-SPD abna Medical College Hospita ) l) BAGU/WB-AIIB/WD-7-R / 1. E stablishment of Modern Micr obiology Laboratory with PCR National Procure in Shaheed ziaur Rahman Me ment Document - Component 1: Emergency C Single Stage - One E 2022-06-2 dical College Hospital IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 152,941.20 122,859.04 Signed 2021-09-03 2021-06-01 2021-09-08 2021-10-20 2021-06-20 2021-11-19 2021-06-20 2021-12-24 2021-06-22 OVID-19 Response nvelope 2 2.Establishment of 10 bed IC ss (Non Bank-SPD U at Shaheed ziaur Rahman ) Medical College Hospital at B ogura 3.Installation of Medical Gas Pipeline system KHUL/WB-AIIB/WD-8-R / 1.Es tablishment of Modern Micro National Procure biology Laboratory with PCR i ment Document - n Khulna Medical College Hos Component 1: Emergency C Single Stage - One E 2022-06-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 223,529.40 0.00 Canceled 2021-09-03 2021-09-08 2021-10-20 2021-11-19 2021-12-24 pital and Satkhira Medical C OVID-19 Response nvelope 2 ss (Non Bank-SPD ollege Hospital. ) 2.Establishment of Medical C entre With Screening facility at Mongla Seaport in Bagerh at Page 5 National Procure JESOR/WB-AIIB/WD-9-R / Est ment Document - ablishment of Modern Microb Component 1: Emergency C Single Stage - One E 2022-06-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 58,823.50 46,303.62 Signed 2021-09-03 2021-12-21 2021-09-08 2021-10-20 2022-01-12 2021-11-19 2022-02-17 2021-12-24 2022-03-14 iology Laboratory with PCR in OVID-19 Response nvelope 2 ss (Non Bank-SPD Kushtia Medical College Hos ) pital BAR /WB-AIIB/WD-10/A-R / 1. Establishment of Modern Mic National Procure robiology Laboratory with PC ment Document - Component 1: Emergency C Single Stage - One E 2022-06-2 R in Barishal Medical College IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 104,359.20 91,109.44 Signed 2021-09-03 2021-05-02 2021-09-08 2021-10-20 2021-05-23 2021-11-19 2021-06-09 2021-12-24 2021-07-16 OVID-19 Response nvelope 2 Hospital. ss (Non Bank-SPD 2.Establishment of 10 bed IC ) U at Shere Bangla Medical Co llege Hospital, Barishal National Procure BAR /WB-AIIB/WD-10/B-R / In Component 1: Emergency C Single Stage - One E ment Document - 2022-06-2 stallation of Medical Gas Pipe IDA / 66050 Post Request for Bids Open - National 35,294.10 31,461.00 Signed 2021-09-03 2021-05-04 2021-09-08 2021-10-20 2021-05-25 2021-11-19 2021-09-08 2021-12-24 2021-09-10 OVID-19 Response nvelope 1 Envelope proce 2 line system ss (Non Bank-SPD ) National Procure CTG-1/WB-AIIB/WD-11-R / Es ment Document - tablishment of Modern Micro Component 1: Emergency C Single Stage - One E 2022-06-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 117,647.10 81,485.21 Signed 2021-09-03 2021-04-21 2021-09-08 2021-10-20 2021-05-17 2021-11-19 2021-06-19 2021-12-24 2021-07-01 biology Laboratory with PCR i OVID-19 Response nvelope 2 ss (Non Bank-SPD n Chattogram Medical Colleg ) e Hospital CTG-2/WB-AIIB/WD-12-R / 1. Modern Microbiology Laborat ory with PCR in Cox's bazar Medical College Hospital. National Procure 2.Medical Centre With Screen ment Document - Component 1: Emergency C Single Stage - One E 2022-06-2 ing facility at Chattragram Se IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 435,294.10 0.00 Canceled 2021-09-03 2021-09-08 2021-10-20 2021-11-19 2021-12-24 OVID-19 Response nvelope 2 aport and SASIA. ss (Non Bank-SPD 3.5 bed ICU in IDH ) 4. Installation of Medical Gas Pipeline system 5.Functional BSL3 lab atBITID National Procure RANGA/WB-AIIB/WD-13-R / E ment Document - stablishment of Modern Micr Component 1: Emergency C Single Stage - One E 2022-06-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 117,647.10 100,126.86 Signed 2021-09-03 2021-04-28 2021-09-08 2021-10-20 2021-05-24 2021-11-19 2021-08-01 2021-12-24 2021-08-18 obiology Laboratory with PCR OVID-19 Response nvelope 2 ss (Non Bank-SPD in Rangamati Medical Colleg ) e Hospital SYLHET/WB-AIIB/WD-15/A-R / 1.Establishment of Modern Microbiology Laboratory with National Procure PCR & 10 bed ICU at Sylhet ment Document - Component 1: Emergency C Single Stage - One E 2022-06-2 MAG Osmani Medical College IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 200,000.00 174,758.18 Signed 2021-09-03 2021-06-01 2021-09-08 2021-10-20 2021-06-17 2021-11-19 2021-06-17 2021-12-24 2021-07-12 OVID-19 Response nvelope 2 Hospital ss (Non Bank-SPD 2.Establishment of Medical C ) entre With Screening facility i n OIA 3.Installation of Medical Gas Pipeline system SYLHET/WB-AIIB/WD-15/B-R National Procure / Establishment of Modern Mi ment Document - Component 1: Emergency C Single Stage - One E 2022-06-2 crobiology Laboratory with P IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 58,823.50 47,065.39 Signed 2021-09-03 2021-04-22 2021-09-08 2021-10-20 2021-05-11 2021-11-19 2021-06-22 2021-12-24 2021-07-01 OVID-19 Response nvelope 2 CR (Sheikh Hasina Medical C ss (Non Bank-SPD ollege Hospital, Hobigonj) ) National Procure RANG/WB-AIIB/WD-16-R / Est ment Document - ablishment of Modern Microb Component 1: Emergency C Single Stage - One E 2022-06-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 58,823.50 51,460.16 Signed 2021-09-03 2021-07-04 2021-09-08 2021-10-20 2021-07-29 2021-11-19 2021-09-07 2021-12-24 2021-09-14 iology Laboratory with PCR in OVID-19 Response nvelope 2 ss (Non Bank-SPD Rangpur Medical College Hos ) pital DHK-3/WB-AIIB/WD-2-R / Est ablishment of Modern Microb iology Laboratory with PCR at National Procure Kurmitola General Hospital,1 ment Document - Component 1: Emergency C Single Stage - One E 2022-06-2 0 bed ICU at Shaheed Sohra IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 588,235.30 0.00 Canceled 2021-09-03 2021-09-08 2021-10-20 2021-11-19 2021-12-24 OVID-19 Response nvelope 2 wardi Medical College Hospit ss (Non Bank-SPD al, Medical Centre With Scree ) ning facility in HSIA, 5 bed IC U in IDH Dhaka,Functional BS L 3 Lab of IEDCR, Dhaka. DHK-3/WB-AIIB/WD-2/A-R / E stablishment of modern Micr obiology laboratory with PCR National Procure (Kurmitola general Hospital) ment Document - Establishment of 10 bed ICU Component 1: Emergency C Single Stage - One E 2023-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 347,118.30 277,821.72 Signed 2022-04-28 2021-11-03 2022-05-03 2022-06-14 2021-12-12 2022-07-14 2021-12-30 2022-08-18 2022-02-15 at Sheed Sohrawardi medical OVID-19 Response nvelope 4 ss (Non Bank-SPD college hospital ) Functional of BSL3 of IEDCR, Dhaka Establishment of 5 bed ICU in IDH,Dhaka National Procure DHK-3/WB-AIIB/WD-2/1B-R / ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2023-02-1 Establishment of medical cen IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 208,586.70 0.00 2022-04-28 2022-05-03 2022-06-14 2022-07-14 2022-08-18 OVID-19 Response nvelope lementation 4 tre with screening facility in ss (Non Bank-SPD HSIA ) National Procure KHUL/WB-AIIB/WD-8/1A-R / E ment Document - stablishment of modern micr Component 1: Emergency C Single Stage - One E Pending Imp 2023-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 115,881.50 0.00 2022-04-28 2022-05-03 2022-06-14 2022-07-14 2022-08-18 obiology laboratory with PCR OVID-19 Response nvelope lementation 4 ss (Non Bank-SPD in Khulna madical college (2 ) nos) National Procure KHUL/WB-AIIB/WD-8/1B-R / E ment Document - stablishment of modern micr Component 1: Emergency C Single Stage - One E 2023-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 57,940.75 52,400.76 Signed 2022-04-28 2022-06-12 2022-05-03 2022-06-14 2022-07-03 2022-07-14 2022-07-05 2022-08-18 2022-07-06 obiology laboratory with PCR OVID-19 Response nvelope 4 ss (Non Bank-SPD in Satkhira Medical college H ) ospital (1 nos) National Procure KHUL/WB-AIIB/WD-8/1C-R / E ment Document - stablishment of Medical Cent Component 1: Emergency C Single Stage - One E Pending Imp 2023-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 46,352.60 0.00 2022-04-28 2022-05-03 2022-06-14 2022-07-14 2022-08-18 re with screening facility at M OVID-19 Response nvelope lementation 4 ss (Non Bank-SPD ongla seaport in Bagerhat ) National Procure CTG-2/WB-AIIB/WD-12/1B-R / ment Document - Establishment of Medical cen Component 1: Emergency C Single Stage - One E Pending Imp 2023-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 139,057.80 0.00 2022-04-28 2022-05-03 2022-06-14 2022-07-14 2022-08-18 tre with screening facility at OVID-19 Response nvelope lementation 4 ss (Non Bank-SPD Chattagram seaaport and SA ) SIA National Procure CTG-2/WB-AIIB/WD-12/1C-R / ment Document - Establishment of 5 bed ICU in Component 1: Emergency C Single Stage - One E 2023-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 46,352.60 41,781.51 Signed 2022-04-28 2021-08-01 2022-05-03 2022-06-14 2021-08-22 2022-07-14 2021-10-05 2022-08-18 2021-10-20 IDH Chattagram and Functio OVID-19 Response nvelope 4 ss (Non Bank-SPD nal BSL 3 Lab of BITID (Civil ) work) National Procure CTG-2/WB-AIIB/WD-12/1D-R ment Document - / Establishment of 5 Bed ICU Component 1: Emergency C Single Stage - One E 2023-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 57,940.75 51,234.04 Signed 2022-04-28 2021-07-11 2022-05-03 2022-06-14 2021-10-01 2022-07-14 2021-08-11 2022-08-18 2021-09-03 and Installation of medical ga OVID-19 Response nvelope 4 ss (Non Bank-SPD s pipeline system in IDH Chat ) tagram (E/M Work) Page 6 National Procure CTG-2/WB-AIIB/WD-12/1E-R / Component 1: Emergency C Single Stage - One E ment Document - 2023-02-1 Functional BSL-3 Lab of BITID IDA / 66050 Post Request for Bids Open - National 121,675.57 107,498.98 Signed 2022-04-28 2021-11-28 2022-05-03 2022-06-14 2021-12-20 2022-07-14 2022-01-11 2022-08-18 2022-02-21 OVID-19 Response nvelope 1 Envelope proce 4 (E/M Work) ss (Non Bank-SPD ) National Procure RANGA/WB-AIIB/WD-12/2A / ment Document - Establishment of 20 Bed Isol Component 1: Emergency C Single Stage - One E Pending Imp 2024-01-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 560,642.87 0.00 2023-04-03 2023-04-09 2023-05-21 2023-06-20 2023-07-25 ation Unit & 10 Bed ICU at Kh OVID-19 Response nvelope lementation 1 ss (Non Bank-SPD agrachari Sadar Hospital. ) National Procure RANGA/WB-AIIB/WD-12/3A / ment Document - Establishment of 20 Bed Isol Component 1: Emergency C Single Stage - One E Pending Imp 2024-01-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 560,642.87 0.00 2023-04-03 2023-04-09 2023-05-21 2023-06-20 2023-07-25 ation Unit & 10 Bed ICU at Ba OVID-19 Response nvelope lementation 1 ss (Non Bank-SPD ndarban Sadar Hospital. ) National Procure RANGM/WB-AIIB/WD-12/A-C ment Document - / Establishment of 20 bed Isol Component 1: Emergency C Single Stage - One E 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 2,121,890.80 0.00 Canceled 2021-07-27 2021-08-01 2021-09-12 2021-10-12 2021-11-16 ation unit & 10 bed ICU at Ra OVID-19 Response nvelope 5 ss (Non Bank-SPD ngamati, Khagachari & Band ) arban Sadar Hospital National Procure RANGA/WB-AIIB/WD-12/1B / ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2024-01-2 Installation of Medical Gas Pi IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 84,096.43 0.00 2023-04-03 2023-04-08 2023-05-20 2023-06-19 2023-07-24 OVID-19 Response nvelope lementation 0 peline System at Rangamati ss (Non Bank-SPD Sadar Hospital. ) National Procure RANGA/WB-AIIB/WD-12/2B / ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2024-01-2 Installation of Medical Gas Pi IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 84,096.43 0.00 2023-04-03 2023-04-08 2023-05-20 2023-06-19 2023-07-24 OVID-19 Response nvelope lementation 0 pe Line System at Khagracha ss (Non Bank-SPD ri Sadar Hospital. ) National Procure RANGA/WB-AIIB/WD-12/3B / ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2024-01-2 Installation of Medical Gas Pi IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 84,096.43 0.00 2023-04-03 2023-04-08 2023-05-20 2023-06-19 2023-07-24 OVID-19 Response nvelope lementation 0 pe Line System at Bandarban ss (Non Bank-SPD Sadar Hospital. ) National Procure RANGM/WB-AIIB/WD-12/B-C ment Document - / Installation of Medical Gas P Component 1: Emergency C Single Stage - One E 2022-05-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 318,283.60 0.00 Canceled 2021-07-27 2021-08-01 2021-09-12 2021-10-12 2021-11-16 ipeline system at Rangamati, OVID-19 Response nvelope 5 ss (Non Bank-SPD Khagarachari & Bandarban S ) adar Hospital National Procure CTG-2/WB-AIIB/WD-12/A / Es ment Document - tablishment of Modern Micro Component 1: Emergency C Single Stage - One E Pending Imp 2024-01-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 51,392.26 0.00 2023-04-04 2023-04-09 2023-05-21 2023-06-20 2023-07-25 biology Laboratory with PCR i OVID-19 Response nvelope lementation 1 ss (Non Bank-SPD n Cox's Bazar Medical Colleg ) e Hospital. National Procure CTG-2/WB-AIIB/WD-12/1A-R / ment Document - Establishment of Modern Mic Component 1: Emergency C Single Stage - One E 2023-02-1 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 63,734.83 0.00 Canceled 2022-04-28 2021-06-22 2022-05-03 2022-06-14 2022-07-14 2022-08-18 robiology laboratory with PC OVID-19 Response nvelope 4 ss (Non Bank-SPD R in Coxs Bazar Medical Colle ) ge Hospital GOPAL/WB-AIIB/WD-4/A / Est National Procure ablishment of Modern Microb ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2024-01-2 iology Laboratory with PCR in IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 46,720.24 0.00 2023-04-04 2023-04-09 2023-05-21 2023-06-20 2023-07-25 OVID-19 Response nvelope lementation 1 Sheikh Sayera Khatun Medic ss (Non Bank-SPD al College Hospital, Gopalgan ) j GOPAL/WB-AIIB/WD-4/A-R / E National Procure stablishment of Modern Micr ment Document - Component 1: Emergency C Single Stage - One E 2022-06-2 obiology Laboratory with PCR IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 58,823.50 0.00 Canceled 2021-09-03 2021-05-11 2021-09-08 2021-10-20 2021-11-19 2021-12-24 OVID-19 Response nvelope 2 in Sheikh Sayera Khatun Med ss (Non Bank-SPD ical College Hospital, Gopalg ) anj National Procure SAVAR/WB-AIIB/WD-3/C / Ins Component 1: Emergency C Single Stage - One E ment Document - Pending Imp 2024-01-2 tallation of Medical Gas Pipeli IDA / 66050 Post Request for Bids Open - National 27,751.82 0.00 2023-04-04 2023-04-09 2023-05-21 2023-06-20 2023-07-25 OVID-19 Response nvelope 1 Envelope proce lementation 1 ne System ss (Non Bank-SPD ) National Procure SAVAR/WB-AIIB/WD-3/C-R / I ment Document - Component 1: Emergency C Single Stage - One E 2022-06-2 nstallation of Medical Gas Pip IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 34,988.20 0.00 Canceled 2021-09-03 2021-04-21 2021-09-08 2021-10-20 2021-11-19 2021-12-24 OVID-19 Response nvelope 2 eline system ss (Non Bank-SPD ) National Procure RANGA/WB-AIIB/WD-12/1A / ment Document - Establishment of 20 Bed Isol Component 1: Emergency C Single Stage - One E Pending Imp 2024-01-2 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 560,643.00 0.00 2023-04-06 2023-04-12 2023-05-24 2023-06-23 2023-07-28 ation Unit & 10 Bed ICU at Ra OVID-19 Response nvelope lementation 4 ss (Non Bank-SPD ngamati Sadar Hospital. ) National Procure SYL/WB-AIIB/WD-16 / Establi ment Document - shment of 20 Bed Isolation U Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 560,609.00 0.00 2023-05-21 2023-05-27 2023-07-08 2023-08-07 2023-09-11 nit & 10 Bed ICU at Moulovib OVID-19 Response nvelope lementation 9 ss (Non Bank-SPD azar Sadar Hospital. ) National Procure SYL/WB-AIIB/WD-17 / Establi ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 shment of 20 Bed Isolation U IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 560,609.00 0.00 2023-05-21 2023-05-27 2023-07-08 2023-08-07 2023-09-11 OVID-19 Response nvelope lementation 9 nit & 10 Bed ICU at Hobiganj ss (Non Bank-SPD Sadar Hospital. ) National Procure SYL/WB-AIIB/WD-18 / Installa ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 tion of Medical Gas Pipeline S IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 84,091.00 0.00 2023-05-21 2023-05-27 2023-07-08 2023-08-07 2023-09-11 OVID-19 Response nvelope lementation 9 ystem at Moulovibazar Sadar ss (Non Bank-SPD Hospital. ) National Procure SYL/WB-AIIB/WD-19 / Installa ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 tion of Medical Gas Pipeline S IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 84,091.00 0.00 2023-05-21 2023-05-27 2023-07-08 2023-08-07 2023-09-11 OVID-19 Response nvelope lementation 9 ystem at Hobiganj Sadar Hos ss (Non Bank-SPD pital. ) National Procure SYL/WB-AIIB/WD-20 / Installa ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 tion of Medical Waste Treatm IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 140,152.00 0.00 2023-05-21 2023-05-27 2023-07-08 2023-08-07 2023-09-11 OVID-19 Response nvelope lementation 9 ent Plant at Sunamgonj Sada ss (Non Bank-SPD r Hospital. ) National Procure RANGA/WB-AIIB/WD-21 / Inst ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 allation of Medical Waste Tre IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 140,152.00 0.00 2023-05-21 2023-05-27 2023-07-08 2023-08-07 2023-09-11 OVID-19 Response nvelope lementation 9 atment Plant at Rangamati S ss (Non Bank-SPD adar Hospital. ) National Procure SAVAR-CRL/WB-AIIB/WD-1 / ment Document - Establishment of Modern Mic Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 93,435.00 0.00 2023-05-21 2023-05-26 2023-07-07 2023-08-06 2023-09-10 robiology Laboratory with PC OVID-19 Response nvelope lementation 8 ss (Non Bank-SPD R in Colonel Malek Medical C ) ollege, Manikganj MYMEN-CRL/WB-AIIB/WD-2 / National Procure Establishment of Modern Mic ment Document - Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 robiology Laboratory with PC IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 93,435.00 0.00 2023-05-21 2023-05-26 2023-07-07 2023-08-06 2023-09-10 OVID-19 Response nvelope lementation 8 R in Shaheed Saiyad Nazrul I ss (Non Bank-SPD slam Medical College, Kishor ) egonj National Procure CUM-CRL/WB-AIIB/WD-3 / Est ment Document - ablishment of Modern Microb Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 46,718.00 0.00 2023-05-21 2023-05-26 2023-07-07 2023-08-06 2023-09-10 iology Laboratory with PCR in OVID-19 Response nvelope lementation 8 ss (Non Bank-SPD Abdul Malek Ukil Medical Coll ) ege, Noakhali Page 7 National Procure PABN-CRL/WB-AIIB/WD-4 / E ment Document - stablishment of Modern Micr Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 46,718.00 0.00 2023-05-21 2023-05-26 2023-07-07 2023-08-06 2023-09-10 obiology Laboratory with PCR OVID-19 Response nvelope lementation 8 ss (Non Bank-SPD in M. monsur Ali Medical Coll ) ege, Sirajgonj National Procure TANGL-CRL/WB-AIIB/WD-5 / ment Document - Establishment of Modern Mic Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 46,718.00 0.00 2023-05-21 2023-05-26 2023-07-07 2023-08-06 2023-09-10 robiology Laboratory with PC OVID-19 Response nvelope lementation 8 ss (Non Bank-SPD R in Shaikh Hasina Medical C ) ollege, Jamalpur National Procure RANG-CRL/WB-AIIB/WD-6 / E ment Document - stablishment of Modern Micr Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 46,718.00 0.00 2023-05-21 2023-05-26 2023-07-07 2023-08-06 2023-09-10 obiology Laboratory with PCR OVID-19 Response nvelope lementation 8 ss (Non Bank-SPD in Rangpur Medical College H ) ospital, Rangpur National Procure BAR-CRL/WB-AIIB/WD-7 / Est ment Document - ablishment of Modern Microb Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 46,718.00 0.00 2023-05-21 2023-05-26 2023-07-07 2023-08-06 2023-09-10 iology Laboratory with PCR in OVID-19 Response nvelope lementation 8 ss (Non Bank-SPD Barisal Medical College Hospi ) tal, Barisal National Procure CUM-CRL/WB-AIIB/WD-8 / Est ment Document - ablishment of Modern Microb Component 1: Emergency C Single Stage - One E Pending Imp 2024-03-0 IDA / 66050 Post Request for Bids Open - National 1 Envelope proce 46,718.00 0.00 2023-05-21 2023-05-26 2023-07-07 2023-08-06 2023-09-10 iology Laboratory with PCR in OVID-19 Response nvelope lementation 8 ss (Non Bank-SPD Cumilla Medical College Hosp ) ital, Cumilla GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 8 PROCUREMENT PLAN (Textual Part) Project information: OECS Regional Health Project P168539 , Commonwealth of Dominica, Grenada, Saint Lucia, Saint Vincent, Caribbean Public Health Agency (CARPHA) and the OECS Commission Project Implementation agencies: MoH StL, MoH SVG, MoH Grenada, MoH Domonica, CARPHA & OECS Commission Date of the Procurement Plan: [01-24-2020] Period covered by this Procurement Plan: 01/24/2020-01-24/2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Other Relevant Procurement Information. 1. Procurement Plan for the Project- St. Lucia Type of Contract Ref. Selection Me Contract Signing . Activity Description Procurem Completion Date No. thod Date (Planned) ent (Planned) Establish National Standards for the implementation and use of an independent 1 1.01 quality control mechanism Consultant CQS 15 Feb 2020 15 Aug 2020 for physical infrastructure and internal finishing of health facilities. Type of Contract Ref. Selection Me Contract Signing . Activity Description Procurem Completion Date No. thod Date (Planned) ent (Planned) SMART Health Facilities 2 Works RFB (National) 15 Jan 2020 15 Jan 2023 1.02 Retrofitting a. Design and Supervision Consultant CQS 15 Jan 2020 15 Jan 2023 RFQ 3 Laboratory Infrastructure Goods/ICT 15 Mar 2020 15 Jun 2020 (International) 1.03 Capacity Building (Food Consultant CQS 15 Mar 2020 15 Jun 2020 Safety) 9 1.08 Specimen Transportation Goods/ICT RFQ (National) 15 Jul 2021 15 Dec 2022 10 2.1 Lab Data Management Tool Goods/ICT RFQ (National) 15 Apr 2020 15 Jun 2021 4 Medical Technologists 11 2.2 Training NA TBD TBD (Training Skills) 2 Pathologists (Training 12 3 Training NA TBD TBD Skills) 2 Histotechnologists 13 3 Training NA TBD TBD (Training Skills) 14 3 Lab Disaster Management Training NA TBD TBD Training for Capacity Type of Contract Ref. Selection Me Contract Signing . Activity Description Procurem Completion Date No. thod Date (Planned) ent (Planned) Building/skills for laboratory staff RFQ 17 2.03 Food safety equipment Goods/ICT 15 Apr 2020 15 Jun 2021 (International) Health and Safety RFQ 18 2.04 improvement in the Goods/ICT 15 Apr 2020 15 Jun 2021 (International) workplace (equipment) Vector Control Programme – Capacity Building for Vector Control Officers in Vector Consultant CQS 15 Jun 2021 15 Jul 2022 Management and Surveillance Capacity Building for 19 2.05 Community Groups and Local Consultant CQS Government Procurement of Essential equipment to support and RFQ implement the vector control Goods/ICT 15 Aug 2020 15 Dec 2021 (International) programme (Entomology Laboratory) Type of Contract Ref. Selection Me Contract Signing . Activity Description Procurem Completion Date No. thod Date (Planned) ent (Planned) 2.08 Capacity building at Ports of Consultant CQS 15 Jun 2021 15 Jul 2022 a Entry – Training 22 2.08 Capacity Building at Ports of Goods/ICT RFQ (National) 15 Aug 2020 15 Dec 2021 b Entry – Equipment Finalization and Implementation of the 2.09 national health disaster Consultant CQS 15 Jan 2021 15 Jun 2022 a management plan – Consultancy on Comm. 23 Finalization and implementation of the 2.10 national health disaster Goods/ICT RFQ (National) 15 Mar 2021 15 Jun 2022 b management plan – Equipment 25 2.11 Hearse Goods/ICT RFQ (National) 15 Feb 2020 15Apr 2021 Caribbean Field Epidemiology RFQ (National) and Laboratory Training 15 Feb 2022 Goods/ICT 15 Feb 2020 Programme (Cr-FELTP) Frontline Training Caribbean Field Epidemiology Goods/ICT RFQ (National) 15 Feb 2020 15 Feb 2022 and Laboratory Training Type of Contract Ref. Selection Me Contract Signing . Activity Description Procurem Completion Date No. thod Date (Planned) ent (Planned) Programme (Cr-FELTP) Level 1 Training Project Management 26 3.01 Operational Expensed NA NA Total project cost 2. Procurement Plan for the Project- OECS Commission Re Type of Contract Contract f. Selection Me No Activity Description Procurem Signing Date Completion Date No thod ent (Planned) (Planned) . Consultancy for Health Facilities Inventory- Inventory of All Emergency/ Urgent Care Facilities in Consultant 1.1 CQS 22-Feb-20 18-Nov-20 four Countries and Emergency and Services Critical Care Services- Procurement of Software for 1.2 Database of Inventory and for GIS Goods RFQ 8-Feb-20 08-May-20 Mapping Lab Transport System Assessment and Action Plan for implementation of Consultant 1.3 IC 16-Oct-19 12-Apr20 agreements, policy and legislation Services (PPA Activity) Development and Implementation of Lab transportation Agreements and Consultant 1.4 QCBS 13-Nov-20 8-Nov-21 Policies Services OECS Pharmaceutical Facility - Support for Existing Software Direct 1.5 Goods 8-Feb-20 08-May-20 Development Selection Re Type of Contract Contract f. Selection Me No Activity Description Procurem Signing Date Completion Date No thod ent (Planned) (Planned) . Initiative for implementation of policy Consultant Direct 1.7 10-Mar-20 5-Mar-21 and legislation - CMLF Services Selection Development of Resource budgets and plans for Countries to meet LQMS Consultant Direct 1.8 7-Oct-19 5-Jan-20 Tier 1 and Tier 2 Requirements – Services Selection CMLF (PPA Activity) Development of relevant Policies and Legislation to facilitate the OECS Consultant 2.1 CQS 26-May-20 21-May-21 Unique ID Services Regional Public Education Campaign Risk Assessment and Action Plan for Implementation of OECS Unique ID Consultant 2.2 CQS 26-Oct-19 24-Jan-20 linked to a Unique Health Identifier Services (PPA Activity) Complete Risk Assessment and Develop and Action Plan for OECS Consultant 2.3 CQS 28-Mar-21 26-Jul-21 Health Emergency Services Services Coordinating Mechanism Prepositioned contract development Consultant 2.4 CQS 26-Jan-20 24-Jun-20 assignment Services Re Type of Contract Contract f. Selection Me No Activity Description Procurem Signing Date Completion Date No thod ent (Planned) (Planned) . Procurement of software to manage 2.5 Goods RFB 15-Mar-20 05-Nov-20 pre-positioned contracts Consultancy for Assessment of Registration Process and Requirement Consultant 2.6 ICS 1-Apr-20 30-Jun-20 for Software to Facilitate Services Harmonisation Web-based platform for registration 2.7 of Health Professional (Consultancy to Goods RFB 12-Oct-20 9-Feb-21 undertake assessment $48,000) Training 2.8 Training NA Meeting for harmonization of 2.9 Registration Requirements for Health Workshop NA professional PIU Staff (Project Manager, IC / Direct Procurement Officer, Accountant, Consultant Selection 3.1 1-Nov-19 30-Oct-22 Project Assistant) Services Multiple 3.2 Procurement of Office Equipment Goods RFQ 8-Sep-19 6-Jan-20 Re Type of Contract Contract f. Selection Me No Activity Description Procurem Signing Date Completion Date No thod ent (Planned) (Planned) . 3.3 Procurement of Office Furniture Goods RFQ 8-Sep-19 6-Jan-20 Procurement of Office Supplies 3.4 Goods RFQ 8-Sep-19 6-Jan-20 Retrofitting of existing office building 3.5 Works RFQ 8-Sep-19 7-Dec-19 Procurement of Audit Firm to Consultant 3.6 undertake Project Audit LCS 20-Nov-20 4-Jan-21 Services Operating Expenses 3.7 NA NA NA NA Total 3. Procurement Plan for the Project- Dominica No Re Activity Description Type of Selection Contract Contract Completion Date . f. Procure Signing Date (Planned) Method No ment (Planned) . 1 Upgrade works for 3 health centres - Castle Bruce (800k) + St Joseph ($700k) + Wesley ($500k): -Extension of physical structure & construction of additional rooms (Wesley only) Design/supervision Consulta CQS 15-Dec-19 30-Apr-22 ncy Works Works RFB 15-Apr-20 15-Apr-21 (National) Furniture/equipment Goods RFQ 15-Mar-21 15-Apr-21 (National) 2 Community outreach, printed Goods RFQ TBD TBD material, rental of PA System, etc. (National) 3 Biomedical Waste Management; Goods RFQ TBD TBD improvement for resiliency: (Internatio nal) Purchase of waste management vehicle to transport biomedical waste No Re Activity Description Type of Selection Contract Contract Completion Date . f. Procure Signing Date (Planned) Method No ment (Planned) . 4 Biomedical Waste Management; Goods RFQ TBD TBD improvement for resiliency: (National) Improve Storage of Biomedical Waste at sites including purchase refrigerators 5 Biomedical Waste Management; Training TBD improvement for resiliency: Training of medical staff to handle biomedical waste management 6 Upgrade laboratory facility and Goods RFQ TBD TBD capacity by equipping district (National) hospital lab in Portsmouth, Marigot, La Plaine & Grand Bay Expand testing and support with diagnostic capacity (procurement of Purchase analyzers to include handheld systems e.g. i-stat 7 Strengthen laboratory data Goods/IC RFQ TBD TBD management system – Supply and T (National) Installation of additional components of existing Lab Information System (Schuylab); Schuylab Remote Printing, Schuylab web base No Re Activity Description Type of Selection Contract Contract Completion Date . f. Procure Signing Date (Planned) Method No ment (Planned) . 8 Ensure adequate transportation Goods RFQ TBD TBD of laboratory specimen: (National) • Purchase solar refrigerators (2) and regular refrigerators - Main Lab and Portsmouth • sturdy Icebox coolers – Type 3 District Health Centers (7) transportation of samples • shipping containers – Main lab (for shipping samples overseas) 9 Training for managing essential Training TBD Laboratory functions 10 Consultant to Develop and Consulta IC TBD TBD implement Quality Management ncy national System 11 Mapping of prevalence of Goods/IC RFQ TBD TBD communicable diseases - including T (National) vector borne diseases and leptospirosis. Mapping i.e. geocode of No Re Activity Description Type of Selection Contract Contract Completion Date . f. Procure Signing Date (Planned) Method No ment (Planned) . all health facilities and towns/villages/hamlets •Equipment – GPS device (Garmin eTrex 20x GPS), 5qty. •GIS software 12 Training of Mapping i.e. geocode of Training all health facilities and towns/villages/hamlets on the Island 13 Set up and equip situation room Goods/IC RFQ TBD TBD Command Centre Communication T (National) Equipment to include 14 Set up and equip situation Goods/IC RFQ TBD TBD Room/HEOCs/Emergency Command T (National) Centre 15 Strengthen health information Goods/IC RFQ TBD TBD system. Equipment for Health T (National) Information Unit 16 Strengthening public health system Consulta TBD TBD by improving public health ncy IC emergency response to control (Internatio disease outbreaks and surveillance nal) systems No Re Activity Description Type of Selection Contract Contract Completion Date . f. Procure Signing Date (Planned) Method No ment (Planned) . 17 Health Emergency Preparedness plan Consulta IC National TBD TBD ncy 18 Project Officer for implementation Consulta IC TBD TBD (duration of the project) ncy National 19 Short Service Contracts in: Consulta IC National TBD TBD ncy • Procurement (when required) • Audit (annually) • Environmental safeguard Multiple (during retrofitting) TOTAL 4. Procurement Plan for the Project- St. Vincent Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) COMPONENT 1 Upgrade works for priority health facilities based on PAHO Smart Hospital criteria including Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) renovations, and retrofitting, furniture & equipment Design/supervision Consultancy CQS 15-Dec-19 30-Apr-22 Upgrade Works- Works RFB (National) 15-Apr-20 15-Apr-21 Furniture/equipment Goods RFQ (National) 15-Mar-21 15-Apr-21 Lab Equipment Goods RFQ (National) 15-Mar-21 15-Apr-21 Construction/Create a Public Health Laboratory Design/supervision - 50000 Consultancy CQS 15-Dec-19 30-Apr-22 Works - 1475000 Works RFB (National) 15-Apr-20 15-Apr-22 Public health Laboratory Equipment Goods/ICT RFQ (National) 15-May-21 15-May-22 300000 Furniture & Equipment - 100000 Goods/ICT RFQ (National) 15-May-21 15-May-22 Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) Strengthened laboratory data management systems - Lab Goods/ICT RFQ (National) 15-May-21 15-May-22 Information System with Health Information System (HIS) Improve the transportation system for laboratory specimens - Cold Goods/ICT RFQ (National) 15-Jul-21 15-Jul-22 chain and laboratory specimen transportation vehicle Strengthen Local capacity to utilize an enhanced regional reference Consultancy CQS 15-Jul-21 15-Jul-22 laboratory Training in Modern Laboratory Technology, Food Safety, Consultancy CQS 15-Jun-21 15-Jun-22 Entomology etc. Implement a regional quality assurance program and develop Consultancy CQS 15-Jun-21 15-Jun-22 common standards for National Laboratories, SVG. Provide training to ensure sufficient human resource capacity for Consultancy CQS 15-May-21 15-May-22 managing essential laboratory functions Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) Regional Accreditation of laboratories with quality standards Consultancy CQS 15-May-21 15-May-22 and development of quality assurance programs COMPONENT 2 Update/develop protocols (including development of an active case- Consultancy CQS 15-Mar-21 15-Sep-21 finding protocol for vector-borne diseases and clinical protocols) Strengthen health information systems for collection of incidence and prevalence data (HIS) ICT Equipment Goods/ICT RFQ (National) 15-Aug-21 15-Aug-23 Consultancy for ICT assessment, Consultancy CQS 15-Aug-21 15-Aug-23 training - Roll-out Field Epidemiology and Laboratory Training Program Consultancy CQS 15-Nov-19 15-Nov-20 (FELTP) among field-level epidemiologists (as needed) Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) Develop procedures on disease surveillance and information sharing with regard to infectious disease Consultancy CQS 15-Jan-20 15-Jan-21 protocols - microcephaly testing and confirmation in pregnant women suspected to be Zika infected Develop regional information and communications technology platform for surveillance and Consultancy CQS management, including Geographic Information Systems (GIS) 15-Jan-20 15-Jan-21 Renovation of Health Emergency Disaster Management Unit facility Design and supervision - Consultancy CQS 15-Dec-19 30-Apr-22 Works Works RFB (National) 15-Apr-20 15-Apr-21 EOC Equipment Goods/ICT RFB (National) 15-Apr-20 15-Apr-21 Disaster Supplies &Equipment- Goods/ICT RFB (National) 15-Apr-20 15-Apr-21 Furniture & Fixtures Goods/ICT RFB (National) 15-Apr-20 15-Apr-21 Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) Emergency Response Equipment Goods/ICT RFB (National) 15-Apr-20 15-Apr-21 Pickup truck (4ton) retrofitted with Goods/ICT RFB (National) 15-Apr-20 15-Apr-21 trailer truck Create external monitoring and assessment of core public health capacities of national structures to Consultancy meet International Health Regulations CQS 15-Jun-20 15-Dec-20 Plan and conduct simulation exercises and training on joint outbreak investigations as part of Consultancy CQS an early warning and response system 15-Jun-20 15-Dec-20 Develop/upgrade curriculum for training of country level health workforce in surveillance and Consultancy response for priority infectious diseases CQS 15-Dec-20 15-May-21 Component 3 Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) Project Financial Specialist Consultancy IC 1-Feb-20 1-Feb-24 Procurement Specialist Consultancy IC 1-Feb-20 1-Feb-24 Fiduciary capacity building for implementation - MOHWE staff Training trained to an enhanced fiduciary level NA 1-Oct-19 1-Oct-21 Project Monitoring and evaluation of Consultancy project activities IC 1-Oct-19 2-Oct-21 Project Audit Consultancy LCS 1-Feb-20 1-Feb-24 Biohazard Waste Management Plan Consultancy IC 1-Feb-20 1-Feb-23 Environmental and Social Consultancy Management Framework (ESMF) CQS 1-Feb-20 1-Feb-23 Office set up Goods DS 1-Sep-19 1-Dec-19 Operational Expenses N/A N/A TOTAL 5. Procurement Plan for the Project- CARPHA Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Laboratory 1 - 2.1 G RFB 30-Sep-19 30-Nov-19 Equipment 1 - 2.1.6 Reagents G Single Source 30-Sep-19 29-Sep-24 Shipping 1 - 4.2.2 G RFQ 31-Jul-19 30-Sep-19 materials 2- Stationery and G RFQ 30-Sep-19 29-Sep-24 1.1.10 printing costs 2- Promotional G RFQ 27-Jul-20 30-Sep-20 1.1.11 materials 2- 3.3d/3.3 IT Goods G RFQ 30-Oct-19 29-Oct-20 f IT equipment for CARPHA; 2 - 1.1.9 country training G RFQ 29-May-20 31-Jul-20 and field projects Maintenance of Laboratory Equi 1 - 2.1.7 30-Sep-19 29-Sep-24 p-ment (New & Existing) NCS RFB Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Proficiency testing (PT) programme for OECS 1- (including TR NA 30-Sep-19 30-Sep-24 3.1.1a standards, monitoring and supportive interventions) Perform PT at CARPHA to ensure that the 1- quality of testing NCS Single Source 30-Sep-19 29-Sep-24 3.1.1c services is being maintained and monitored Provide broadband service to 2 - 3.3e NCS RFQ 1-Oct-19 29--aug-24 support increased internet capacity Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Establishment of a regional system for 1 1 - 1.2.5 CS Single Source 30-Sep-19 14-Oct-19 validation of equipment and methods Software: Inform ation management 2 1 - 2.2.1 capacity for 25-Aug-21 integrated surveillance approaches CS FBS 26-Feb-21 Support mechanism for 3 1 - 2.2.2 inter-country 29-Jun-21 technical collaboration CS FBS 30-Jun-20 LIMS 4 1 - 2.2.3 Consultant/Deve 29-Oct-21 loper CS CQS 30-Jun-20 Building CARPHA 5 1 - 2.2.4 CS 30-Sep-19 29-Mar-22 LIMS capacity CQS 6 1-6 Communication CS CQS 30-Oct-20 30-Jul-22 products for Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment laboratory services Level III training 7 2 - 1.1.2 curriculum CS CQS 31-Aug-20 30-Apr-21 development "Train the trainers" progra m to increase 8 2 - 1.1.3 country capacity TR NA 31-Aug-20 30-Apr-21 for FELTP - Hire Training Consultant Upgrade and maintain 9 2 - 1.1.5 capacity for CS CQS 30-Sep-19 29-Sep-24 eLearning Platform - Contracts for 10 2 - 1.1.6 Subject Matter CS CQS 30-Jun-20 31-Aug-21 Experts (SMEs) - Contract for Training 11 2 - 1.1.6 CS CQS 30-Sep-19 31-Aug-20 Development consultant Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Independent peer review/assessm ent of CARPHA’s existing 12 2 - 2.1b surveillance CS CQS 30-Jul-19 30-Nov-19 system and its adequacy to fulfil its public health surveillance role In-country support to developing routine reporting structures for 13 2 - 2.1d populating CS CQS 30-Oct-20 29-Oct-22 yearly ministerial report, also known as CMO Report Update and produce CARPHA 14 2 - 2.2a Data CS CQS 30-Oct-19 29-Oct-20 Appreciation and M&E manuals, Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment materials and tools to support public health surveillance Develop and roll out ICD-11 selection of underlying 15 2 - 2.6 cause of death CS IC 4-Jan-21 30-Oct-21 training towards the strengthening of mortality data Upgrade (to ICD- 11) and enhance, 16 2 - 2.8 CS CQS 2-Mar-21 30-Jun-21 mortality data capture tool (MORTBASE) Morbidity coding training 17 2 - 2.9a workshop to CS IC 1-Nov-20 30-Jun-22 improve morbidity data 18 2 - 3.1a IT Gap analysis, CS CQS 30-Jan-20 30-Mar-20 needs Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment assessment and architecture design to support CARPHA Regional Surveillance system Draft CARPHA's surveillance platform (using DHIS2) to integrate GIS 19 2 - 3.1 b CS CQS 30-Sep-21 2-Jan-22 and data visualization to enhance real time reporting and feedback DHIS2 platform 20 2 - 3.3a Maintenance of CS CQS 1-Oct-19 29--aug-24 service contract Improve IT capacity at 21 2 - 3.3b CARPHA to host CS CQS 1-Jun-20 30-Nov-20 DHIS-2 installation Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Gap analysis on Data sharing interoperability between the selected CMS 22 2 - 3.4 CS CQS 30-Sep-20 29-Oct-21 using CARPHA LIMS and automatically importing data into DHIS2. Development of a mobile app for public health 23 2 - 3.5 alerts and CS CQS 30-Oct-20 29-Oct-21 dissemination of public health information Knowledge 24 2 - 3.6 CS CQS 30-Oct-19 29-Sep-22 Management Development of the action plan 25 2 - 4.2 for regional CS IC 30-Oct-20 30-Jun-21 preparedness and response 26 2 - 4.6 Simulation CS CQS 30-Sep-21 29-Sep-24 Exercise on Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment responding to public health emergencies Continued Implementation of 27 2 - 5.1 CS CQS 31-Jul-20 31-Jan-21 Communication and Marketing Plan Development of country-level National Action 28 2 - 6 CS QCBS 30-Aug-23 Pan for Health Security (NAPHS) 1-Sep-21 Regional level 29 2 - 7 workshop on JEE TR TR 29-Sep-20 self-evaluation 30-Sep-19 Development and Implementation 30 3 - 3.2.6 of CS CQS Communication Strategy for Increased 30-Sep-19 30-Aug-24 Visibility of Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Grant, its outputs and outcomes 31 3 - 3.2.1 Project Officer CS IC 1-Oct-19 30-Sep-24 32 3 - 3.2.1 M&E officer CS IC 1-Oct-19 30-Sep-24 33 3 - 3.2.1 Finance Officer CS IC 1-Oct-19 30-Sep-24 Procurement 34 CS IC Officer 1-Oct-19 30-Sep-24 Total Amount 6. Procurement Plan for the Project- Grenada Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . Procurement of upgrade works at 1 Mount Gay Psychiatric Works RFB 4-Jul-20 31-Jul-23 Hospital Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . Consultancy to conduct situational analysis to establish Consultan 2 CQS 4-Nov-19 1-Mar-20 baseline for Child & cy Geriatric Mental health Services Procurement of upgrades and refurbishment to the 3 Works RFB 1-Nov-21 29-Jul-22 Isolation Room, ICU of the General Hospital and Rathdune Expansion of 5 Sauteaurs Health Works RFB 1-Mar-22 31-Aug-22 Centre Expansion of St. 6 David's Health Centre Works RFB 11-Jan-21 28-Apr-22 Consultancy to Implement critical Consultan 7 CQS 2-Mar-20 31-Dec-21 health system cy upgrades Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . Procurement of equipment for the 9 Goods DS 1-Nov-19 30-Jun-20 upgrade of laboratory facilities Consultancy to Consultan 10 strengthen laboratory IC 1-Nov-19 31-Dec-20 cy information system Procurement of 11 equipment to Goods RFQ (National) 2-Mar-20 31-Dec-20 strengthen LIS Procurement of equipment to improve 12 Goods RFB 2-Mar-20 31-Dec-20 efficiency of lab operations Design and Supervision for the refurbishment of Mount Gay Hospital, Consultan 13 QCBS 5-Apr-20 31-Dec-24 General Hospital cy (Rathdune), Sauteurs and St. David's Health Centres Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . Procurement of Furniture and 14 Goods RFB 1-Mar-22 31-Aug-23 Equipment for refurbished buildings Training in 13 Procurement for Staff Training TR 11-Mar-19 31-Jan-20 (Biomedical) Consultancy to provide Short Term IC 1-Jan-20 31-Dec-20 Training for New Lab Consultan 14 Technicians cy Consultancy to provide national training programme DS 1-Sep-20 1-Dec-23 for laboratory Consultan 14 technicians cy Consultancy to strengthen Consultan DS 15 surveillance systems cy 6-Jul-20 1-Jun-23 Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . Strengthen Surveillance Systems TR 16 FELTP Training 1 & 2 Training 1-Sep-20 31-Jul-24 Consultancy to provide morbidity and Consultan DS 17 mortality Surveillance cy 1-Feb-21 31-Dec-22 Procurement of Hardware and RFQ software for chronic 18 disease registry Goods 1-Jul-20 31-Dec-20 Consultancy to guide in the development of Consultan IC 19 HEOC cy 1-Jan-20 30-Apr-20 Consultancy and implementation of Consultan IC 20 desktop simulation cy 1-Jan-24 31-Aug-24 Consultancy for the Training of emergency Consultan CQS 21 technicians cy 1-Jan-20 31-Jul-21 Procurement of ambulances, and RFB emergency response 22 vehicles Goods 1-Jan-21 31-Dec-21 Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . Procurement of communications RFQ 23 equipment for HEOC Goods 1-Oct-20 30-Jul-21 Procurement of RFQ 24 Computer Equipment Goods 1-Oct-20 30-Jul-21 Procurement of Personal Protective RFQ 25 Equipment Goods 1-Oct-20 31-Dec-21 Training in TR 26 Psychological First Aid Training 1-Sep-20 30-Sep-21 Consultan IC 27 Project Coordinator cy 11-Nov-19 31-Dec-24 Procurement of RFQ 28 Project Vehicle Goods 11-Nov-19 31-Jan-20 Procurement of Computer and RFQ Acceories for Project 29 Office Goods 11-Nov-19 31-Jul-20 Project Operating Cost NA NA NA NA Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . 30 Project Visibility NCS RFQ 1-Feb-20 4-Feb-20 Consultan IC 31 Project M & E Officer cy 1-Jan-21 31-Dec-21 Capacity Building for TR 32 Staff Training September,2020 1-Dec-22 Total PROCUREMENT OECS Countries : OECS Regional Health Project PLAN General Information Country: OECS Countries 2020-04-17 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P168539 GPN Date: 2020-05-21 Project Name: OECS Regional Health Project Loan / Credit No: IDA / 64810 Ministry of Health of SVG Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - SVGRHP-W-RFB-1 / Construc Strengthening Public Health Single Stage - One E Small Works SPD Pending Imp 2022-08-2 tion/upgrades of Selected He IDA / 64810 Surveillance and Emergency Post Request for Bids Open - National 500,000.00 0.00 2021-11-08 2021-11-13 2021-12-25 2022-01-24 2022-02-28 nvelope (1 envelope proce lementation 7 alth Facilities Management ss) SVGRHP-W - DC-3C / Electric Contingency Emergency Res Other (with field f Pending Imp 2022-05-2 al and plumbing connection t IDA / 64810 Post Direct Selection Direct 1,006.00 0.00 2022-04-18 2022-04-23 2022-05-14 ponse Component (CERC) or explanation) lementation 8 o laboratory container at Uni on Island. SVGRHP-W-DC-1A / Construc Contingency Emergency Res 2020-12-1 IDA / 64810 Post Direct Selection Direct 100,000.00 0.00 Canceled 2020-05-04 2020-05-09 2020-06-13 tion of Isolation staff hostel ponse Component (CERC) 0 SVGRHP-W-DC-1B / Isolation Contingency Emergency Res 2020-12-1 IDA / 64810 Post Direct Selection Direct 350,000.00 0.00 Canceled 2020-05-04 2020-05-09 2020-06-13 Facility ponse Component (CERC) 0 SVGRHP-W-DC-1C / Ancillary Contingency Emergency Res 2020-12-1 IDA / 64810 Post Direct Selection Direct 160,000.00 0.00 Canceled 2020-05-04 2020-05-09 2020-06-13 Buildings for Isolation Facility ponse Component (CERC) 0 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SVGRHP-G-RFQ-1 / Purchase Improved Health Facilities a Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Limited 50,000.00 0.00 2020-04-19 2020-04-28 2020-06-14 2020-12-11 of vehicle nd Laboratory Capacity tions nvelope mentation SVGRHP-G-DC-6 / QPCR Rea Contingency Emergency Res Pending Impl IDA / 64810 Post Direct Selection Direct 200,000.00 0.00 2020-04-20 2020-04-25 2020-05-30 2020-11-26 gents and Consumables ponse Component (CERC) ementation SVGRHP-G-DC-5 / Supportin Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 20,000.00 0.00 2020-04-20 2020-05-12 2020-04-25 2020-05-12 2020-05-30 2020-11-26 g Equipment - PRC System ponse Component (CERC) mentation SVGRHP-G-DC-4 / Q PRC Sys Contingency Emergency Res IDA / 64810 Post Direct Selection Direct 62,000.00 16,458.10 Signed 2020-04-20 2021-01-11 2020-04-25 2020-03-20 2020-05-30 2020-05-13 2020-11-26 tem ponse Component (CERC) SVGRHP-G-DC-3 / Mobile Isol Contingency Emergency Res IDA / 64810 Post Direct Selection Direct 2,500,000.00 256,241.31 Signed 2020-04-20 2020-11-30 2020-04-25 2020-02-14 2020-05-30 2020-04-02 2020-11-26 ation Units and Tents ponse Component (CERC) SVGRHP-G-DC-2 / Mobile Isol Contingency Emergency Res IDA / 64810 Post Direct Selection Direct 335,000.00 294,976.24 Signed 2020-04-20 2020-11-30 2020-04-25 2020-03-03 2020-05-30 2020-12-01 2020-11-26 ation Chambers and Tents ponse Component (CERC) SVGRHP-G-DC-1 / Isolation F Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 500,000.00 0.00 2020-04-22 2020-11-30 2020-04-27 2020-06-01 2020-11-28 acility - Equipment & Furnishi ponse Component (CERC) mentation ng SVGRHP-G-RFB-1 / Supply of Improved Health Facilities a Single Stage - One E Goods - Lab equipment: Com IDA / 64810 Post Request for Bids Open - National 135,000.00 149,327.66 Signed 2020-07-31 2020-11-06 2020-08-05 2020-09-16 2020-12-11 2020-10-16 2021-01-27 2020-11-20 2021-07-09 2021-05-19 nd Laboratory Capacity nvelope munity Level SVGRHP-G-RFQ-2 / Supply of Institutional Capacity Buildin Request for Quota Single Stage - One E Under Imple Goods, furniture and equipm IDA / 64810 g, Project Management and Post Open - National 10,000.00 0.00 2020-09-23 2020-11-18 2021-05-17 tions nvelope mentation ent Coordination SVGRHP-G-DC-11A / Equipm Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 5,000.00 0.00 2020-11-24 2021-02-02 2020-11-29 2020-07-24 2021-01-03 2021-07-02 ent to assist in data gatherin ponse Component (CERC) mentation g -laptops SVGRHP-G-DC-11B / COVID - Contingency Emergency Res Under Imple 19 Response - Equipment to IDA / 64810 Post Direct Selection Direct 5,000.00 0.00 2020-11-24 2021-02-02 2020-11-29 2020-07-24 2021-01-03 2021-07-02 ponse Component (CERC) mentation assist in data gathering - Lap tops SVGRHP-G-DC-10 / COVID-1 Contingency Emergency Res Pending Impl 9 Response - Consumables - IDA / 64810 Post Direct Selection Direct 120,000.00 0.00 2020-11-24 2020-11-29 2021-01-03 2021-07-02 ponse Component (CERC) ementation Personal Protective Equipme nt SVGRHP-G-DC-9 / COVID-19 Response - Supporting Equip Contingency Emergency Res Under Revie IDA / 64810 Prior Direct Selection Direct 350,000.00 0.00 2020-11-24 2021-04-28 2020-11-29 2021-01-03 2021-07-02 ment and consumables - Aut ponse Component (CERC) w omated extraction equipmen t SVGRHP-G-DC-8 / COVID-19 Contingency Emergency Res Under Imple Response - Supporting Equip IDA / 64810 Post Direct Selection Direct 200,000.00 0.00 2020-11-24 2021-02-02 2020-11-29 2020-07-08 2021-01-03 2021-07-02 ponse Component (CERC) mentation ment and consumables - Swa bs SVGRHP-G-DC-7 / COVID-19 Contingency Emergency Res Pending Impl Response - Supporting Equip IDA / 64810 Post Direct Selection Direct 325,000.00 0.00 2020-11-24 2020-11-29 2021-01-03 2021-07-02 ponse Component (CERC) ementation ment and consumables - Gen eral Items SVGRHP-G-RFB-2 / Procurem Contingency Emergency Res Single Stage - One E Pending Impl IDA / 64810 Post Request for Bids Open - National 15,000.00 0.00 2021-01-08 2021-01-13 2021-02-24 2021-03-26 2021-04-30 2021-10-27 ent of Supplies: Rape and HI ponse Component (CERC) nvelope ementation V rapid kits SVGRHP-G-DC-17 / Procurem Contingency Emergency Res ent of Acrylic Partitions at Ar IDA / 64810 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-01-19 2021-01-08 2021-01-24 2021-01-08 2021-02-28 2021-08-27 ponse Component (CERC) gyle Isolation Facility SVGRHP-G-DC-14 / COVID-1 Contingency Emergency Res Under Imple 9 Response - Consumables - IDA / 64810 Post Direct Selection Direct 30,000.00 0.00 2021-01-18 2021-02-02 2021-01-23 2022-12-09 2021-02-27 2021-08-26 ponse Component (CERC) mentation GeneXpert Machine Page 1 SVGRHP-G-DC-13 / COVID-1 Contingency Emergency Res Pending Impl 9 Response - Consumables - IDA / 64810 Post Direct Selection Direct 150,000.00 0.00 2021-01-18 2021-01-23 2021-02-27 2021-08-26 ponse Component (CERC) ementation Medical supplies for Isolation units SVGRHP-G-DC-12 / COVID-1 Contingency Emergency Res 9 Response - Consumables - IDA / 64810 Post Direct Selection Direct 300,000.00 174,374.00 Signed 2021-01-18 2021-02-04 2021-01-23 2021-01-13 2021-02-27 2021-04-20 2021-08-26 ponse Component (CERC) Containerized Laboratory an d Storage SVGRHP-G-DC-20 / COVID-1 Contingency Emergency Res Under Imple 9 Response - Consumables - IDA / 64810 Post Direct Selection Direct 147,600.00 0.00 2021-08-27 2021-09-03 2021-09-01 2021-04-12 2021-10-06 2022-04-04 ponse Component (CERC) mentation Testing supplies. SVGRHP-G-DC-23 / COVID-1 Contingency Emergency Res Request for Quota Single Stage - One E 9 Response - Equipment and IDA / 64810 Post Open - National 14,722.00 0.00 Canceled 2021-09-07 2021-11-02 2022-05-01 ponse Component (CERC) tions nvelope Furnishing for Isolation Facilit y - CCTV SVGRHP-W-RFQ-2 / COVID-1 9 Response - Containerized S Contingency Emergency Res Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Open - National 10,000.00 0.00 2021-09-08 2021-11-03 2022-05-02 torage - Retrofitting works fo ponse Component (CERC) tions nvelope mentation r two (2) containers. SVGRHP-G-DC-18 / COVID-1 Contingency Emergency Res Pending Impl 9 Response - Containerized S IDA / 64810 Post Direct Selection Direct 3,720.00 0.00 2021-09-03 2021-09-08 2021-10-13 2022-04-11 ponse Component (CERC) ementation torage - 20ft Shipping Contai ners. SVGRHP-G-DC-24 / COVID-1 9 Response - Equipment and Contingency Emergency Res Under Imple Furnishing for Isolation Facilit IDA / 64810 Post Direct Selection Direct 176,100.00 0.00 2021-09-07 2021-09-08 2021-09-12 2021-09-02 2021-10-17 2022-04-15 ponse Component (CERC) mentation y - Medical Equipment - Argyl e Isolation Facility - BPF. SVGRHP-G-RFQ-9 / Equipme Contingency Emergency Res Request for Quota Single Stage - One E Pending Impl nt: Royal St. Vincent and the IDA / 64810 Post Open - National 10,000.00 0.00 2021-09-22 2021-11-17 2022-05-16 ponse Component (CERC) tions nvelope ementation Grenadines Police Force Sexu al Offenders Unit. SVGRHP-G-DC-21 / COVID-1 Contingency Emergency Res 9 Response - Consumables - IDA / 64810 Post Direct Selection Direct 250,000.00 432,050.00 Signed 2021-09-03 2021-09-09 2021-09-08 2021-09-02 2021-10-13 2021-09-10 2022-04-11 ponse Component (CERC) testing supplies SVGRHP-G-DC-26 / COVID-1 Contingency Emergency Res IDA / 64810 Post Direct Selection Direct 262,717.50 271,114.00 Signed 2021-11-03 2021-11-01 2021-11-08 2021-10-14 2021-12-13 2021-11-09 2022-06-11 9 Testing Supplies ponse Component (CERC) SVGRHP-G-DC-26(A) / COVID Contingency Emergency Res IDA / 64810 Post Direct Selection Direct 144,486.00 0.00 Canceled 2021-10-14 2021-11-09 2021-10-19 2021-11-23 2022-05-22 -19 Testing Supplies ponse Component (CERC) SVGRHP-G-DC-27 / Goods an Contingency Emergency Res Under Imple d Related Services for Servici IDA / 64810 Post Direct Selection Direct 15,009.00 0.00 2021-10-14 2021-11-09 2021-10-19 2021-11-11 2021-11-23 2022-05-22 ponse Component (CERC) mentation ng & Maintenance of QPCR M achine SVGRHP-RFQ-4 / COVID-19 R Contingency Emergency Res Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Open - National 350,000.00 0.00 2021-08-24 2021-10-19 2022-04-17 esponse - PPE's. ponse Component (CERC) tions nvelope mentation SVGRHP-G-RFQ-26 (B) / COVI D-19 Response - Testing Sup Contingency Emergency Res Request for Quota Single Stage - One E IDA / 64810 Post Limited 262,717.50 0.00 Canceled 2021-11-08 2021-12-20 2022-02-28 plies (Extraction kits, Sample ponse Component (CERC) tions nvelope collections devices - VTMs et c.) SVGRHP-G-RFQ-4 / Personal Protective Equipment - for us Contingency Emergency Res Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Limited 350,000.00 0.00 2021-11-15 2022-01-07 2021-12-30 2022-03-30 e in the Health Sector toward ponse Component (CERC) tions nvelope mentation s COVID-19 response. SVGRHP-G-DC-22 / Medical E Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 100,000.00 0.00 2021-11-10 2021-09-20 2021-11-15 2021-01-18 2021-12-09 2022-02-07 quipment - Mobile X-Ray ponse Component (CERC) mentation SVGRHP-G-RFQ-5 / Medical E Contingency Emergency Res Request for Quota Single Stage - One E IDA / 64810 Post Limited 361,184.40 0.00 Canceled 2021-12-27 2022-01-07 2022-02-10 2022-05-11 quipment, furniture and fittin ponse Component (CERC) tions nvelope gs SVGRHP-G-DC-26B / COVID- 19 Response - Testing Suppli Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 262,717.50 0.00 2022-01-10 2022-01-10 2022-01-15 2022-02-19 2022-08-18 es (Extraction kits, Sample c ponse Component (CERC) mentation ollections devices - VTMs etc. ) SVGRHP-G-RFQ-23 / COVID-1 Contingency Emergency Res Request for Quota Single Stage - One E Pending Impl 9 Response - Equipment and IDA / 64810 Post Open - National 14,722.00 0.00 2022-02-20 2022-04-17 2022-10-14 ponse Component (CERC) tions nvelope ementation Furnishing for Isolation Facilit y - CCTV SVGRHP-G-DC-26-C / COVID- Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 70,000.00 0.00 2022-01-04 2021-12-15 2022-01-09 2021-12-16 2022-02-13 2022-08-12 19 Testing Supplies ponse Component (CERC) mentation SVGRHP-G-DC-28 / COVID19 Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 50,000.00 0.00 2022-04-20 2022-04-24 2022-04-25 2022-05-30 2022-11-26 Response: GeneXpert Testin ponse Component (CERC) mentation g Kits SVGRHP-G-RFQ-29 / PCR Co Contingency Emergency Res Request for Quota Single Stage - One E Pending Impl IDA / 64810 Post Limited 14,950.00 0.00 2022-06-04 2022-07-05 2022-09-03 nsumables (Molecular Grade ponse Component (CERC) tions nvelope ementation Ethanol) SVGRHP-G-DC-30 / Testing S upplies (Modular SARS-CoV-2 Contingency Emergency Res Pending Impl IDA / 64810 Post Direct Selection Direct 22,500.00 0.00 2022-05-30 2022-06-04 2022-06-12 2022-08-11 RdRp 530,LightMix SabeccoV ponse Component (CERC) ementation E-gene plus EAV control) SVGRHP-G-RFQ-5B / Comput Contingency Emergency Res Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Limited 4,400.00 0.00 2022-07-25 2022-10-04 2022-08-22 2022-10-21 er Equipment ponse Component (CERC) tions nvelope mentation Contingency Emergency Res Request for Quota Single Stage - One E Pending Impl SVGRHP-G-DC-5C / AC Units IDA / 64810 Post Limited 15,200.00 0.00 2022-07-29 2022-08-21 2022-10-20 ponse Component (CERC) tions nvelope ementation SVGRHP-G-RFG-5D / Office F Contingency Emergency Res Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Limited 6,516.00 0.00 2022-08-05 2022-10-04 2022-08-28 2022-10-27 urniture and Equipment ponse Component (CERC) tions nvelope mentation SVGRHP-G-DC-5E / Refrigera Contingency Emergency Res Pending Impl IDA / 64810 Post Direct Selection Direct - National 3,240.00 0.00 2022-07-22 2022-08-05 2022-08-26 2022-10-25 tors ponse Component (CERC) ementation SVGRHP-G-RFQ-5A / Medical Contingency Emergency Res Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Open - National 369,184.40 0.00 2022-07-29 2022-09-21 2022-12-20 Equipment ponse Component (CERC) tions nvelope mentation SVGRHP-G-FRQ-32 / Testing Contingency Emergency Res Request for Quota Single Stage - One E Pending Impl IDA / 64810 Post Limited 40,000.00 0.00 2022-09-02 2022-10-07 2022-12-06 Supplies and reagents ponse Component (CERC) tions nvelope ementation Page 2 SVGRHP-G-FRQ-31 / Laborat Contingency Emergency Res Request for Quota Single Stage - One E Pending Impl IDA / 64810 Post Limited 7,600.00 0.00 2022-09-11 2022-10-13 2022-10-19 ory Refrigerator ponse Component (CERC) tions nvelope ementation SVGRHP-G-DC- 30A / Covid-1 Contingency Emergency Res Pending Impl IDA / 64810 Post Direct Selection Direct - National 5,000.00 0.00 2022-11-25 2022-11-27 2022-12-06 2022-12-26 9 Testing Supplies ponse Component (CERC) ementation SVGRHP-G-RFQ-8 / Supply of Contingency Emergency Res Request for Quota Single Stage - One E IDA / 64810 Post Open - National 10,000.00 0.00 Canceled 2021-09-20 2021-11-15 2022-05-14 goods: Sexual assault kits. ponse Component (CERC) tions nvelope SVGRHP-G-RFQ-6 / COVID-19 Contingency Emergency Res Request for Quota Single Stage - One E Response - Decontamination IDA / 64810 Post Open - National 30,000.00 0.00 Canceled 2021-08-23 2021-10-18 2022-04-16 ponse Component (CERC) tions nvelope Equipment. SVGRHP-G-DC-25 / COVID-1 9 Response - Supporting Equi Contingency Emergency Res IDA / 64810 Post Direct Selection Direct 9,899.18 0.00 Canceled 2021-09-22 2021-09-27 2021-11-01 2022-04-30 pment, Bryden and Stokes (R ponse Component (CERC) eimbursement). SVGRHP-G-DC-16 / Procurem Institutional Capacity Buildin ent of Items for use in Project IDA / 64810 g, Project Management and Post Direct Selection Direct 4,500.00 0.00 Canceled 2021-01-11 2021-01-16 2021-02-20 2021-08-19 Office in response to Local C Coordination ovid019 spread. SVGRHP-G-RFQ-7 / COVID-19 Contingency Emergency Res Request for Quota Single Stage - One E IDA / 64810 Post Open - National 45,600.00 0.00 Canceled 2021-08-16 2021-10-11 2022-04-09 Response - Electrical Generat ponse Component (CERC) tions nvelope or SVGRHP-G-RFQ-26D / COVID Contingency Emergency Res Request for Quota Single Stage - One E IDA / 64810 Post Open - National 44,486.00 0.00 Canceled 2022-01-19 2022-03-16 2022-09-12 -19 Testing Supplies ponse Component (CERC) tions nvelope SVGRHP-G-DC-38 / Water Fil Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct - National 9,350.00 0.00 2023-05-31 2023-06-27 2023-06-04 2023-06-09 2023-06-29 ter System ponse Component (CERC) mentation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SVGRHP-NCS-RFQ-5 / Monito Institutional Capacity Buildin ring and evaluation- Allotme Request for Quota Single Stage - One E Pending Impl IDA / 64810 g, Project Management and Post Open - National 21,000.00 0.00 2020-08-05 2020-09-30 2021-03-29 nt for PIU/MOH staff training i tions nvelope ementation Coordination n fiduciary (WB etc.) SVGRHP-NCS-TR-1 / Conduct Strengthening Public Health Request for Quota Single Stage - One E Pending Impl Basic Field Epidemiology Trai IDA / 64810 Surveillance and Emergency Post Limited 5,000.00 0.00 2021-08-21 2021-10-16 2022-04-14 tions nvelope ementation ning Programme / Conduct M Management entorship FELTP SVGRHP-NCS-DC-1 / COVID- Contingency Emergency Res Pending Impl 19 Response - Consumables - IDA / 64810 Post Direct Selection Direct 20,400.00 0.00 2021-09-08 2021-09-13 2021-10-18 2022-04-16 ponse Component (CERC) ementation Inland Transportation for Con tainerized Lab. SVGRHP-NCS-DC-2 / COVID- Contingency Emergency Res Pending Impl 19 Response - Consumables - IDA / 64810 Post Direct Selection Direct 20,400.00 0.00 2021-09-08 2021-09-13 2021-10-18 2022-04-16 ponse Component (CERC) ementation Inland Transportation for Con tainerized Lab. SVGRHP-NCS-DC-4 / COVID- 19 Response - Transporting o Contingency Emergency Res Pending Impl IDA / 64810 Post Direct Selection Direct - National 485.00 0.00 2022-11-15 2022-11-20 2022-12-02 2022-12-05 f Laboratory Container to loc ponse Component (CERC) ementation ation in Canouan SVGRHP-NCS-DC-35 A / COVI Contingency Emergency Res Pending Impl D-19 Response - GBV Rental IDA / 64810 Post Direct Selection Direct - National 3,000.00 0.00 2022-11-25 2022-11-30 2022-12-07 2023-01-04 ponse Component (CERC) ementation of Venue of Community Cons ultations SVGRHP-NCS-DC-35B / COVI Contingency Emergency Res Pending Impl D-19 Response GBV - Comm IDA / 64810 Post Direct Selection Direct - National 2,000.00 0.00 2022-11-25 2022-11-30 2022-12-07 2022-12-27 ponse Component (CERC) ementation unity Consultations Provision of Refreshment SVGRHP-NCS-RFQ-4 / Activit Strengthening Public Health Request for Quota Single Stage - One E y to address weakness in co IDA / 64810 Surveillance and Emergency Post Open - National 30,000.00 0.00 Canceled 2020-12-01 2021-01-26 2021-07-25 tions nvelope mpliance with the 2005 IHR, i Management ncluding training SVGRHP-NCS-RFQ-1 / Frontli Strengthening Public Health Request for Quota Single Stage - One E ne & Basic Field Epidemiolog IDA / 64810 Surveillance and Emergency Post Limited 1,000.00 0.00 Canceled 2020-07-20 2020-09-14 2021-03-13 tions nvelope y Training Programme Management Strengthening Public Health SVGRHP-NCS-RFQ-2 / Condu Request for Quota Single Stage - One E IDA / 64810 Surveillance and Emergency Post Limited 3,000.00 0.00 Canceled 2020-07-18 2020-09-12 2021-03-11 ct Level 1 FELTP tions nvelope Management SVGRHP-NCS-RFQ-3 / Condu Strengthening Public Health Request for Quota Single Stage - One E ct Frontline Field Epidemiolo IDA / 64810 Surveillance and Emergency Post Limited 6,200.00 0.00 Canceled 2020-08-10 2020-10-05 2021-04-03 tions nvelope gy Training Program Management CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SVGRHP-C-CQS-1 / Feasibilit Improved Health Facilities a Consultant Qualifi y study of the existing Public IDA / 64810 Post Open - National 50,000.00 0.00 Canceled 2020-08-05 2020-08-26 2020-10-09 2020-11-08 2020-12-13 2021-06-11 nd Laboratory Capacity cation Selection Health Laboratory system SVGRHP-C-LCS-1 / Design an d Supervision for the constru Improved Health Facilities a Least Cost Selecti Under Implement IDA / 64810 Post Open - National 300,000.00 0.00 2020-12-15 2022-07-07 2021-01-05 2022-07-14 2021-02-18 2022-10-07 2021-03-18 2022-11-11 2021-04-17 2023-01-03 2021-05-22 2023-01-10 2021-06-26 2021-12-23 ction of the National Public H nd Laboratory Capacity on ation ealth building (to also house the EOC) SVGRHP-C-CQS-2 / TA to upd Strengthening Public Health Consultant Qualifi Pending Impleme ate and finalise communicabl IDA / 64810 Surveillance and Emergency Post Open - National 50,000.00 0.00 2020-08-05 2020-08-26 2020-10-09 2020-11-08 2020-12-13 2021-06-11 cation Selection ntation e disease preparedness & res Management ponse plans . SVGRHP-C-CQS - 3 / Establis Strengthening Public Health Consultant Qualifi hment of Isolation Facilities a IDA / 64810 Surveillance and Emergency Post Open - National 150,000.00 0.00 Signed 2020-07-31 2020-11-24 2020-08-21 2020-12-28 2020-10-04 2021-04-20 2020-11-03 2022-02-03 2020-12-08 2021-06-06 cation Selection t identified locations Management Page 3 SVGRHP-C-CQS-5 / Activity f or the Management of Biome Strengthening Public Health Consultant Qualifi dical waste - TA waste dispos IDA / 64810 Surveillance and Emergency Post Open - National 10,000.00 0.00 Canceled 2020-11-11 2020-12-02 2021-01-15 2021-02-14 2021-03-21 2021-09-17 cation Selection al system & Procurement of Management Decontaminated equipment Institutional Capacity Buildin SVGRHP-C-LCS-4 / Project Fi Least Cost Selecti Pending Impleme IDA / 64810 g, Project Management and Post Open - National 30,000.00 0.00 2021-02-05 2021-02-26 2021-04-11 2021-05-09 2021-06-08 2021-07-13 2021-08-17 2022-02-13 nancial Audit on ntation Coordination SVHRHP-C-CQS-4 / TA to Co mplete Depth Assessment of Improved Health Facilities a Consultant Qualifi Open - Internationa Pending Impleme IDA / 64810 Post 10,000.00 0.00 2021-09-06 2021-09-27 2021-11-10 2021-12-10 2022-01-14 2022-07-13 Health Facilities and Final Sc nd Laboratory Capacity cation Selection l ntation oring of Upgraded Facilities SVGRHP-C-LCS-6 / TA for the Improved Health Facilities a Least Cost Selecti Design and Supervision of Se IDA / 64810 Post Open - National 100,000.00 162,306.27 Signed 2021-08-09 2021-08-23 2021-08-30 2021-09-08 2021-10-13 2022-01-03 2021-11-10 2022-02-18 2021-12-10 2022-05-03 2022-01-14 2022-06-14 2022-02-18 2022-07-15 2022-08-17 nd Laboratory Capacity on lected Facilities to be Upgrad ed SVGRHP-C-CQS-6 / Improve t Strengthening Public Health Consultant Qualifi Open - Internationa he Information Base for Surv IDA / 64810 Surveillance and Emergency Post 50,000.00 0.00 Canceled 2021-08-16 2021-09-06 2021-10-20 2021-11-19 2021-12-24 2022-06-22 cation Selection l eillance - Training and invest Management ments in HIS SVGRHP-C-CQS-7 / Consulta Strengthening Public Health ncy to update Existing Food Consultant Qualifi Open - Internationa Pending Impleme IDA / 64810 Surveillance and Emergency Post 30,000.00 0.00 2021-09-15 2021-10-06 2021-11-19 2021-12-19 2022-01-23 2022-07-22 Safety, Port Health SOPs, Pro cation Selection l ntation Management tocols and supporting regulat ions INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Institutional Capacity Buildin SVGRHP-C-IC-1 / TA for Proc Individual Consult IDA / 64810 g, Project Management and Post Open 140,000.00 0.00 Under Review 2020-08-31 2020-11-03 2020-10-19 2020-11-09 2020-12-14 2021-06-12 urement assistant ant Selection Coordination SVGRHP-C-IC-3 / Safeguard c onsultancies and Gender Bas Contingency Emergency Res Individual Consult Pending Impleme ed Violence Service Providers IDA / 64810 Post Limited 25,000.00 0.00 2021-01-11 2021-01-16 2021-02-06 2021-03-13 2021-09-09 ponse Component (CERC) ant Selection ntation : TA for the Development of t he protocol and training Institutional Capacity Buildin SVGRHP-C-IC-4 / Contract M Individual Consult Pending Impleme IDA / 64810 g, Project Management and Post Open 21,000.00 0.00 2021-08-09 2021-09-27 2021-10-18 2021-11-22 2022-05-21 anagement Assistant ant Selection ntation Coordination SVGRHP-C-IC-9 / Consultanc Strengthening Public Health Under Implement y for the Updating National O IDA / 64810 Surveillance and Emergency Post Direct Selection Direct 42,000.00 0.00 2022-04-08 2022-04-04 2022-04-18 2022-03-24 2022-06-22 2022-12-19 ation ne Health All Hazards Manag Management ement Plan SVGRHP-IC-DC-35 / COVID-1 Contingency Emergency Res Pending Impleme 9 Response - GBV Communit IDA / 64810 Post Direct Selection Direct - National 1,550.00 0.00 2022-11-25 2022-12-02 2022-12-08 2022-12-10 ponse Component (CERC) ntation y Consultations SVGRHP-C-DC-1 / Improve th Strengthening Public Health e Information Base for Survei IDA / 64810 Surveillance and Emergency Post Direct Selection Direct 70,000.00 0.00 Canceled 2022-05-02 2022-05-12 2022-07-16 2023-01-12 llance - Training and investm Management ents in HIS Institutional Capacity Buildin SVGRHP-C-IC-5 / Environmen Individual Consult IDA / 64810 g, Project Management and Post Open 21,000.00 0.00 Canceled 2021-08-09 2021-09-29 2021-09-27 2021-10-18 2021-11-22 2022-05-21 tal & Safeguards Officer ant Selection Coordination SVGRHP-C-IC-7 / TA for the d Contingency Emergency Res Individual Consult IDA / 64810 Post Open 10,000.00 0.00 Canceled 2021-09-13 2021-11-01 2021-11-22 2021-12-27 2022-06-25 evelopment of the protocol a ponse Component (CERC) ant Selection nd training. SVGRHP-C-IC-8 / TOR - Traini Contingency Emergency Res Individual Consult IDA / 64810 Post Open 20,000.00 0.00 Canceled 2021-09-13 2021-11-01 2021-11-22 2021-12-27 2022-06-25 ng manual and training on G ponse Component (CERC) ant Selection BV SOP. Institutional Capacity Buildin SVGRHP-C-IC-2 / TA for Fina Individual Consult IDA / 64810 g, Project Management and Post Open 80,000.00 0.00 Canceled 2020-07-31 2020-11-04 2020-09-18 2020-10-09 2020-11-13 2021-05-12 ncial assistant ant Selection Coordination SVGRHP-C-IC-6 / Consultanc Strengthening Public Health y for the Development of Hea Individual Consult IDA / 64810 Surveillance and Emergency Post Open 30,000.00 0.00 Canceled 2021-09-12 2021-09-09 2021-10-31 2021-12-17 2021-11-21 2021-12-26 2022-06-24 lth Care Waste Management ant Selection Management System (HWMS) SVGRHP-C-IC-6A / Consultan Strengthening Public Health Direct - Internation Under Implement cy for Health Care Waste Ma IDA / 64810 Surveillance and Emergency Post Direct Selection 35,000.00 0.00 2023-05-17 2023-06-20 2023-05-28 2023-07-06 2024-03-04 al ation nagement System Management SVGRHP-C-IC-10 / National H Strengthening Public Health Individual Consult Pending Impleme ealth Multi-Hazard Incident M IDA / 64810 Surveillance and Emergency Post Limited 32,500.00 0.00 2023-06-12 2023-06-17 2023-07-25 2023-09-02 2024-03-30 ant Selection ntation anagement Plan Management Page 4 PROCUREMENT PLAN (Textual Part) Project information: Mauritania Social Safety Net Project II (P171125) Project Implementation agency: Delegation Générale Taazour Date of the Procurement Plan: March 17th, 2020 Period covered by this Procurement Plan: 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: “Not Applicable” Works: “Not Applicable” Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. “Not Applicable” Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Mauritania : Social Safety Net System Project II PLAN General Information Country: Mauritania 2020-03-18 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171125 GPN Date: Project Name: Social Safety Net System Project II Loan / Credit No: IDA / D5680, COFN / C1950 Social Safety Net System Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual National Proc MR-SSNS-304769-CW-RFQ / Component 1: Updating and urement Doc Request for Quota Single Stage - One E Pending Imp 2023-07-0 Aménagements des Bureaux IDA / D5680 enhancing the Social Registr Post Limited ument - 1 En 0.00 2022-11-08 2023-01-03 tions nvelope lementation 2 RS, Coord et TK y velope proce ss (Non Bank -SPD) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-SSNS-178803-GO-RFB / Acquisition 9 véhiculeS (4x4) Component 1: Updating and : Lot 1 (4 pour le RS, 1 pour l Single Stage - One E Pending Impl IDA / D5680 enhancing the Social Registr Post Request for Bids Open - National 0.00 2020-06-10 2020-06-15 2020-07-27 2020-08-26 2020-09-30 2021-03-29 e PFSRC et 2 pour Tekavoul) nvelope ementation y Lot 2 (1 véhicule pour le RS) Lot 3 (1 véhicule pour Tekav oul) TEK/RS/PFSRC MR-SSNS-211604-GO-RFB / Component 1: Updating and Single Stage - One E Matériel Informatique (TEK,R IDA / D5680 enhancing the Social Registr Post Request for Bids Open - National 23,939.74 Signed 2020-12-31 2021-07-08 2021-01-05 2021-02-16 2021-08-09 2021-03-18 2021-08-12 2021-04-22 2021-11-09 2021-10-19 nvelope S,PFSRC,Coord.) y MR-SSNS-211605-GO-RFQ / Component 1: Updating and Mobilier et équipements de b Request for Quota Single Stage - One E IDA / D5680 enhancing the Social Registr Post Limited 74,363.65 Terminated 2021-01-09 2021-09-13 2021-03-06 2021-10-13 2021-09-02 ureaux (bureaux, mobiliers, t tions nvelope y éléphones, climatiseurs…) T EK,RS,PFSRC,Coord. MR-SSNS-211968-GO-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Under Imple Consommable informatique IDA / D5680 enhancing the Social Registr Post Limited 0.00 2021-01-25 2021-09-13 2021-03-22 2021-09-18 tions nvelope mentation & fournitures de bureau TEK, y RS,PFSRC,Coord MR-SSNS-211973-GO-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Equipement Promotion Social IDA / D5680 e socio-economic inclusion o Post Limited 32,831.89 Completed 2021-01-25 2021-03-09 2021-03-22 2021-06-24 2021-09-18 2021-08-27 tions nvelope e + Dialogue Familiale (form f poor households ation) TEK MR-SSNS-212002-GO-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Kits équipes mobiles (nattes, IDA / D5680 enhancing the Social Registr Post Limited 12,548.12 Signed 2021-01-25 2021-08-03 2021-03-22 2021-08-31 2021-09-18 tions nvelope torches, lits picots…) TEK,RS y MR-SSNS-212017-GO-RFB / Production outils de commun ication (images, brochures, s Component 1: Updating and Single Stage - One E Under Imple pots radio, vidéo sur les réali IDA / D5680 enhancing the Social Registr Post Request for Bids Open - National 0.00 2021-02-10 2021-09-06 2021-02-15 2021-09-30 2021-03-29 2021-04-28 2021-06-02 2021-11-29 nvelope mentation sations du prog, postres, pan y neau, depliant rollup, bander ol gadgets, casquette, gilet, f oulard) TEK/RS MR-SSNS-212049-GO-RFQ / Component 4: Project Coordi Request for Quota Single Stage - One E IDA / D5680 Post Limited 3,650.64 Completed 2021-01-25 2021-08-03 2021-03-22 2021-08-23 2021-09-18 2021-09-04 Matériels de protection Covid nation and Management tions nvelope 19 Coord MR-SSNS-212283-GO-RFB / Component 1: Updating and Single Stage - Two E Pending Impl IDA / D5680 Post Request for Bids Open - National 0.00 2021-02-22 2021-02-27 2021-04-10 2021-06-23 2021-07-28 2022-01-24 Acquisition de 2 Véhicules 4X enhancing the Social Registr nvelope ementation 4 RS/ TK y MR-SSNS-219273-GO-RFB / Acquisition 6 véhicules 4x4: Component 1: Updating and Lot 1 ( (04) véhicules 4X4 Pic Open - Internationa Single Stage - One E Pending Impl IDA / D5680 enhancing the Social Registr Post Request for Bids 0.00 2021-03-17 2021-03-22 2021-05-03 2021-06-02 2021-07-07 2022-01-03 k up : 3 pour Tekavoul et 1 p l nvelope ementation y our MAOUNA) Lot 2 ( (02) vé hicules 4X4 1 pour la Coordi nation et 1 pour RS) MR-SSNS-257197-GO-RFQ / Component 4: Project Coordi Request for Quota Single Stage - One E Under Imple Acquisition et installation sys IDA / D5680 Post Limited 0.00 2021-10-23 2021-09-16 2021-12-18 2022-06-16 nation and Management tions nvelope mentation tème de surveillance MR-SSNS-257213-GO-RFB / Component 1: Updating and Single Stage - One E Pending Impl Acquisition 03 véhicules lég IDA / D5680 enhancing the Social Registr Post Request for Bids Open - National 0.00 2021-11-28 2021-12-03 2022-01-14 2022-02-13 2022-03-20 2022-09-16 nvelope ementation ers pour service y MR-SSNS-257229-GO-RFQ / I Component 2: Enhancing th Request for Quota Single Stage - One E mpression des cartes de mén IDA / D5680 e socio-economic inclusion o Post Limited 4,688.99 Signed 2021-10-18 2021-04-21 2021-12-13 2021-06-17 2022-06-11 tions nvelope ages TK et ELMAOUNA f poor households MR-SSNS-257223-GO-RFQ / Component 1: Updating and Request for Quota Single Stage - One E IDA / D5680 Post Limited 41,135.78 Signed 2021-10-17 2021-04-13 2021-12-12 2021-06-12 2022-06-10 Acquisition des tablettes enhancing the Social Registr tions nvelope y MR-SSNS-212037-GO-RFQ / Component 1: Updating and Acquisition, installation et mi Request for Quota Single Stage - One E IDA / D5680 enhancing the Social Registr Post Limited 9,743.25 Signed 2021-01-26 2022-01-28 2021-03-23 2022-02-19 2021-09-19 se en service des équipemen tions nvelope y ts d’une sale de de vidéoconf érence MR-SSNS-276742-GO-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Pending Impl IDA / D5680 Post Limited 0.00 2022-05-03 2022-06-28 2022-12-25 Matériels de protection COVI enhancing the Social Registr tions nvelope ementation D 2022 y MR-SSNS-276743-GO-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Under Imple Téléphone de service pour le IDA / D5680 enhancing the Social Registr Post Limited 0.00 2022-06-28 2022-03-14 2022-08-23 2023-02-19 tions nvelope mentation s Directeurs y MR-SSNS-276747-GO-RFB / Component 1: Updating and Single Stage - One E Pending Impl IDA / D5680 Post Request for Bids Open - National 0.00 2022-07-07 2022-07-12 2022-08-23 2022-09-22 2022-10-27 2023-04-25 Acquisition des véhicules lég enhancing the Social Registr nvelope ementation ers y Page 1 MR-SSNS-276758-GO-RFQ / Component 1: Updating and Acquisition d’un système d’a Request for Quota Single Stage - One E IDA / D5680 enhancing the Social Registr Post Limited 0.00 Canceled 2022-06-27 2022-08-22 2023-02-18 rchivage numérique et gestio tions nvelope y n électronique des document s MR-SSNS-276767-GO-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Pending Impl IDA / D5680 Post Limited 0.00 2022-03-14 2022-05-09 2022-11-05 Système d'un contrôle d'accè enhancing the Social Registr tions nvelope ementation s y MR-SSNS-276896-GO-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Pending Impl Licences logiciels et certificat IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2022-03-05 2022-04-30 2022-10-27 tions nvelope ementation s (Toad for SQL Server, SSL) f poor households Component 2: Enhancing th MR-SSNS-276901-GO-RFQ / Request for Quota Single Stage - One E Pending Impl IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2022-04-26 2022-06-21 2022-12-18 Téléphones Thuraya tions nvelope ementation f poor households MR-SSNS-276944-GO-DIR / I Component 4: Project Coordi nstallation Liaison fibre optiq IDA / D5680 Post Direct Selection Direct 20,031.62 Signed 2022-02-15 2022-01-20 2022-02-20 2021-09-22 2022-03-27 2022-02-14 2022-09-23 nation and Management ue pour la sale de vidéo conf érence MR-SSNS-279333-GO-DIR / A Component 2: Enhancing th Pending Impl chat des cartes de crédit (TK- IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 0.00 2022-03-09 2022-03-14 2022-04-18 2022-10-15 ementation DF motivation couples) f poor households MR-SSNS-279334-GO-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Pending Impl Achat des bouteilles d'eau (r IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2022-03-13 2022-05-08 2022-11-04 tions nvelope ementation afraichissement couples) TK- f poor households DF MR-SSNS-291581-GO-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Pending Impl Achat des cartes de crédit (T IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2022-05-02 2022-06-27 2022-12-24 tions nvelope ementation K-DF motivation couples) f poor households MR-SSNS-304699-GO-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Pending Impl Acquisition KITS et Matériel d IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2022-10-02 2022-11-27 2023-05-26 tions nvelope ementation e formation et Projection DF f poor households + PS MR-SSNS-276916-GO-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Kits et matériel de formation IDA / D5680 e socio-economic inclusion o Post Limited 0.00 Canceled 2022-04-04 2021-04-12 2022-05-30 2022-11-26 tions nvelope et de Projection DT + PS f poor households MR-SSNS-276583-GO-RFQ / Component 1: Updating and Kit équipes mobiles du RS et Request for Quota Single Stage - One E Pending Impl IDA / D5680 enhancing the Social Registr Post Limited 0.00 2022-04-10 2022-06-05 2022-12-02 TK (moustiquaires, nattes, lit tions nvelope ementation y picot, torches, couvertures, e tc.) MR-SSNS-276585-GO-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Pending Impl IDA / D5680 Post Limited 0.00 2022-04-23 2022-06-18 2022-12-15 Fourniture de bureau et cons enhancing the Social Registr tions nvelope ementation ommables y MR-SSNS-276591-GO-RFQ / Component 1: Updating and Request for Quota Single Stage - One E IDA / D5680 Post Limited 0.00 Canceled 2022-04-17 2022-06-12 2022-12-09 Mobilier de bureau enhancing the Social Registr tions nvelope y MR-SSNS-276936-GO-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Under Imple Acquisition Groupe Electrogè IDA / D5680 enhancing the Social Registr Post Limited 0.00 2022-03-20 2022-10-14 2022-05-15 2022-11-11 tions nvelope mentation ne Coord-TK-RS y MR-SSNS-304772-GO-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Pending Impl Acquisition du Matériels infor IDA / D5680 enhancing the Social Registr Post Limited 0.00 2022-11-09 2023-01-04 2023-07-03 tions nvelope ementation matiques RS 2022 y MR-SSNS-304773-GO-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Pending Impl Acquisition d'un Système de IDA / D5680 enhancing the Social Registr Post Limited 0.00 2022-08-09 2022-10-04 2023-04-02 tions nvelope ementation vidéo surveillance RS y MR-SSNS-304918-GO-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Pending Impl Acquisition des tablettes et d IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2022-11-06 2023-01-01 2023-06-30 tions nvelope ementation es portables Extension PS Juil f poor households let 2022 MR-SSNS-304971-GO-RFQ / Component 2: Enhancing th Acquisition d'un Système de Request for Quota Single Stage - One E Pending Impl IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2022-11-08 2023-01-03 2023-07-02 suivi des véhicules (GPS et tr tions nvelope ementation f poor households aking) TK, Ext PS et Coord MR-SSNS-304978-GO-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Pending Impl Acquisition du Mobilier et éq IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2022-11-08 2023-01-03 2023-07-02 tions nvelope ementation uipements pour Extension TK f poor households Juillet 2022 MR-SSNS-315456-GO-RFB / Component 1: Updating and Acquisition de 12 véhicule 4X Single Stage - One E IDA / D5680 enhancing the Social Registr Post Request for Bids Open - National 0.00 Canceled 2022-09-15 2022-10-03 2022-09-20 2022-10-04 2022-11-01 2022-11-01 2022-12-01 2023-01-05 2023-07-04 4 et 5 véhicules légers de liai nvelope y son pour le PASYFIS II 2022 e n deux lots MR-SSNS-325413-GO-RFQ / Acquisition de véhicules en d Component 1: Updating and Request for Quota Single Stage - One E Under Imple eux lots : 12 véhicules 4x4 pi IDA / D5680 enhancing the Social Registr Post Limited 0.00 2022-11-26 2022-11-21 2023-01-21 2023-07-20 tions nvelope mentation ckup et 5 véhicules légers de y liaison pour le PASYFIS II 202 2 MR-SSNS-339424-GO-RFQ / Component 1: Updating and Acquisition de Mobilier de bu Request for Quota Single Stage - One E Pending Impl COFN / C1950 enhancing the Social Registr Post Limited 0.00 2023-09-09 2023-11-04 2024-11-03 reau pour toutes les compos tions nvelope ementation y antes (RS, Tek, Elmaou et la Coordination) MR-SSNS-339425-GO-RFQ / Acquisition de fournitures de Component 1: Updating and Request for Quota Single Stage - One E Pending Impl bureau et consommables inf IDA / D5680 enhancing the Social Registr Post Limited 0.00 2023-09-09 2023-11-04 2024-11-03 tions nvelope ementation ormatique pour toutes les co y mposantes (RS, Tek, El maou na et la coordination) MR-SSNS-304974-GO-RFQ / Acquisition de matériels d'ar Component 1: Updating and Request for Quota Single Stage - One E Pending Impl chivage numérique Soft et H IDA / D5680 enhancing the Social Registr Post Limited 0.00 2022-09-06 2022-11-01 2023-04-30 tions nvelope ementation ard et de Gestion electroniqu y e de document en deux lots ( RS et Coor) 2023 MR-SSNS-339426-GO-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Pending Impl Acqui sition de Kits et matéri IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2023-09-09 2023-11-04 2024-11-03 tions nvelope ementation el de formation et de Projecti f poor households on EX, DF et PS Page 2 MR-SSNS-344182-GO-RFB / Component 1: Updating and Acquisition de Véhicules en d Single Stage - One E Under Imple COFN / C1950 enhancing the Social Registr Post Request for Bids Open - National 0.00 2023-02-28 2023-04-03 2023-03-05 2023-03-26 2023-04-05 2023-05-10 2023-08-08 eux lots: deux (02) véhicules nvelope mentation y legers et (14) quatorze véhic ules 4x4 Pickup MR-SSNS-363007-GO-RFB / Component 1: Updating and Acquisition du materiel infor Single Stage - One E Pending Impl IDA / D5680 enhancing the Social Registr Post Request for Bids Open - National 0.00 2023-08-09 2023-08-14 2023-09-25 2023-10-25 2023-11-29 2024-05-27 matique pour toutes les com nvelope ementation y posantes (RS, Tek, El Maouna et la Coordination) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-SSNS-165047-NC-RFB / S ELECTION D’UN OU PLUSIEU RS OPERATEURS DE PAIEMEN Component 2: Enhancing th Open - Internationa Single Stage - One E T POUR LA REALISATION DE IDA / D5680 e socio-economic inclusion o Prior Request for Bids 0.00 Signed 2020-03-20 2020-09-15 2020-03-25 2020-09-16 2020-05-06 2021-02-17 2020-06-05 2022-10-18 2020-07-10 2021-01-06 l nvelope TRANSFERTS MONETAIRES E f poor households LECTRONIQUES AU PROFIT D ES MENAGES PAUVRES (5 lot s) - Accord Cadre 2 ans et de mi -PNTS MR-SSNS-196334-NC-RFB / S élection d'un ou plusieurs op érateurs dans le cadre d'un d Component 3: Strengthening euxième passage de distribut the shock response system f Request for Quota Single Stage - One E Under Imple IDA / D5680 Post Limited 0.00 2020-10-10 2020-12-05 2021-06-03 ion de cash transfer au profit or households vulnerable to tions nvelope mentation de 210 000 ménages bénéfic climate-shocks iaires en réponse au COVID 1 9 (Financement: BAD, BM et Etat Mauritanien) MR-SSNS-211963-NC-RFB / I Component 1: Updating and Single Stage - One E Pending Impl MPRESSION cartes de ménag IDA / D5680 enhancing the Social Registr Post Request for Bids Open - National 0.00 2021-02-08 2021-02-13 2021-03-27 2021-04-26 2021-05-31 2021-11-27 nvelope ementation es TEK/RS/PFSRC y MR-SSNS-211978-NC-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Maintenance matériels infor IDA / D5680 e socio-economic inclusion o Post Limited 21,894.74 Signed 2021-01-25 2021-11-01 2021-03-22 2021-12-15 2021-09-18 tions nvelope matiques et de froid Coord/T f poor households EK MR-SSNS-211982-NC-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Entretien et réparation des v IDA / D5680 enhancing the Social Registr Post Limited 46,779.07 Signed 2021-01-25 2021-10-28 2021-03-22 2021-11-17 2021-09-18 tions nvelope éhicules TEK,RS,PFSRC,Coord y MR-SSNS-211958-NC-RFB / L Component 1: Updating and Single Stage - One E IDA / D5680 Post Request for Bids Open - National 0.00 Canceled 2021-01-05 2021-02-15 2021-01-10 2021-02-21 2021-03-23 2021-04-27 2021-10-24 ocation Véhicules TEK/RS/PFS enhancing the Social Registr nvelope RC y MR-SSNS-212229-NC-RFQ / P Component 2: Enhancing th Request for Quota Single Stage - One E Under Imple roduction des émissions Radi IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2021-01-25 2021-04-22 2021-03-22 2021-09-18 tions nvelope mentation o TEK f poor households MR-SSNS-212285-GO-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Location de Véhicules (Contr IDA / D5680 enhancing the Social Registr Post Limited 0.00 Canceled 2021-01-31 2021-03-28 2021-09-24 tions nvelope at de 3mois) TEK Coord RS y MR-SSNS-218651-NC-DIR / L Component 1: Updating and ocation de véhicules pour le Under Imple IDA / D5680 enhancing the Social Registr Prior Direct Selection Direct 0.00 2021-02-10 2021-03-10 2021-02-15 2022-09-08 2021-03-22 2021-09-18 PASyFIS (contrat de 3 mois r mentation y enouvelable 1 fois) MR-SSNS-275308-NC-DIR / U Component 1: Updating and n Accord cadre de 24 mois p IDA / D5680 enhancing the Social Registr Post Direct Selection Direct 558,806.00 Signed 2022-01-27 2022-01-25 2022-02-01 2022-02-03 2022-03-08 2022-03-06 2022-09-04 our la location de véhicules 2 y 022 par Entente Directe MR-SSNS-276588-NC-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Under Imple IDA / D5680 Post Limited 0.00 2022-04-20 2021-10-28 2022-06-15 2022-12-12 Entretien véhicules enhancing the Social Registr tions nvelope mentation y MR-SSNS-276898-NC-RFQ / P Component 2: Enhancing th Request for Quota Single Stage - One E Pending Impl roduction épisodes radio Tek IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2022-03-28 2022-05-23 2022-11-19 tions nvelope ementation avoul f poor households MR-SSNS-276904-NC-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Pending Impl Maintenance Matériel inform IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2022-03-14 2022-05-09 2022-11-05 tions nvelope ementation atique TK f poor households MR-SSNS-276918-NC-RFQ / F Component 3: Strengthening ilm vidéo sur le circuit de mis the shock response system f Request for Quota Single Stage - One E Pending Impl IDA / D5680 Post Limited 0.00 2022-04-24 2022-06-19 2022-12-16 e en œuvre et fonctionneme or households vulnerable to tions nvelope ementation nt des organes du DCAN /EL climate-shocks MAOUNA MR-SSNS-276926-NC-RFQ / Component 4: Project Coordi Request for Quota Single Stage - One E Under Imple Maintenance Matériel inform IDA / D5680 Post Limited 0.00 2022-02-28 2021-10-27 2022-04-25 2022-10-22 nation and Management tions nvelope mentation atique et froids nouveaux bur eau / Coord MR-SSNS-276929-NC-RFQ / Component 4: Project Coordi Request for Quota Single Stage - One E Pending Impl Contrat de nettoyage nouvea IDA / D5680 Post Limited 0.00 2022-03-05 2022-04-30 2022-10-27 nation and Management tions nvelope ementation u local pour la coordination MR-SSNS-276932-NC-RFQ / Component 4: Project Coordi Request for Quota Single Stage - One E Pending Impl Contrat de maintenance de l IDA / D5680 Post Limited 0.00 2022-03-01 2022-04-26 2022-10-23 nation and Management tions nvelope ementation a salle vidéo conférence MR-SSNS-276939-NC-RFQ / Component 4: Project Coordi Request for Quota Single Stage - One E Maintenance Groupes Electro IDA / D5680 Post Limited 0.00 Canceled 2022-09-20 2022-11-15 2023-05-14 nation and Management tions nvelope gènes/ Coord MR-SSNS-276941-NC-RFQ / Component 4: Project Coordi Request for Quota Single Stage - One E Pending Impl IDA / D5680 Post Limited 0.00 2022-04-24 2022-06-19 2022-12-16 Maintenance Système de sur nation and Management tions nvelope ementation veillance MR-SSNS-276950-NC-DIR / C Component 2: Enhancing th ontrat clientèle ED pour l’imp IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 77,681.00 Signed 2022-02-07 2022-02-07 2022-02-12 2022-02-04 2022-03-19 2022-02-10 2022-09-15 ression des cartes de ménag f poor households e du TK-PASyFiS II. MR-SSNS-276933-GO-DIR / A Component 4: Project Coordi Pending Impl ssistance Technique Logiciel IDA / D5680 Post Direct Selection Direct 0.00 2022-04-20 2022-04-25 2022-05-30 2022-11-26 nation and Management ementation TOMPRO (Multi sites, Multi pr ojets) Page 3 MR-SSNS-276586-NC-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Pending Impl IDA / D5680 Post Limited 0.00 2022-04-27 2022-06-22 2022-12-19 Réparation des véhicules enhancing the Social Registr tions nvelope ementation y MR-SSNS-304768-NC-RFQ / Component 1: Updating and Request for Quota Single Stage - One E Pending Impl IDA / D5680 Post Limited 0.00 2022-09-06 2022-11-01 2023-04-30 Nettoyage local RS enhancing the Social Registr tions nvelope ementation y MR-SSNS-304838-NC-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Nettoyage nouveau local de IDA / D5680 e socio-economic inclusion o Post Limited 0.00 Canceled 2022-09-07 2022-11-02 2023-05-01 tions nvelope TEKAVOUL1 Juillet 2022 f poor households MR-SSNS-304979-NC-RFB / R ecrutement des operateurs d Component 2: Enhancing th e payement 2023-2025 POU Open - Internationa Single Stage - One E Under Imple IDA / D5680 e socio-economic inclusion o Prior Request for Bids 0.00 2022-08-05 2022-10-26 2022-08-10 2023-02-06 2022-09-21 2023-02-14 2022-10-21 2023-03-23 2022-11-25 2023-05-24 R LA REALISATION DE TRANS l nvelope mentation f poor households FERTS MONETAIRES ELECTR ONIQUES AU PROFIT DES ME NAGES PAUVRES (5 Lots) MR-SSNS-322727-NC-RFQ / Recrutement d’un opérateur de paiement pour la réalisati Component 2: Enhancing th on de transferts monétaires Request for Quota Single Stage - One E IDA / D5680 e socio-economic inclusion o Post Limited 0.00 Canceled 2022-11-19 2023-01-21 2025-07-29 électroniques par le PASyFiS tions nvelope f poor households II au profit des ménages pau vres dans la wilaya de Nouak chott Ouest (2 744 ménages bénéficiaires) MR-SSNS-322728-NC-RFQ / Recrutement d’un opérateur de paiement pour la réalisati Component 2: Enhancing th on de transferts monétaires Request for Quota Single Stage - One E IDA / D5680 e socio-economic inclusion o Post Limited 0.00 Canceled 2022-11-19 2023-01-21 2025-07-29 électroniques par le PASyFiS tions nvelope f poor households II au profit des ménages pau vres dans la wilaya de Nouak chott Nord (4 199 ménages b énéficiaires). MR-SSNS-322729-NC-RFQ / Recrutement d’un opérateur de paiement pour la réalisati Component 2: Enhancing th on de transferts monétaires Request for Quota Single Stage - One E IDA / D5680 e socio-economic inclusion o Post Limited 0.00 Canceled 2022-11-19 2023-01-21 2025-07-29 électroniques par le PASyFiS tions nvelope f poor households II au profit des ménages pau vres dans la wilaya de Nouak chott Sud (7 220 ménages bé néficiaires). MR-SSNS-339433-NC-RFQ / Component 1: Updating and Selection d'un prestataire de Request for Quota Single Stage - One E Pending Impl IDA / D5680 enhancing the Social Registr Post Limited 0.00 2023-06-10 2023-08-05 2024-08-04 services pour le nettoyage d tions nvelope ementation y e locaux : RS, TEK et Coordin ation MR-SSNS-339440-NC-RFQ / Component 4: Project Coordi Request for Quota Single Stage - One E Pending Impl Contrat de maintenance de l COFN / C1950 Post Limited 0.00 2023-11-06 2024-01-01 2024-12-31 nation and Management tions nvelope ementation a salle vidéo conférence Coor dination MR-SSNS-339441-NC-RFQ / Component 4: Project Coordi Request for Quota Single Stage - One E Pending Impl Maintenance Système de sur IDA / D5680 Post Limited 0.00 2023-09-09 2023-11-04 2024-11-03 nation and Management tions nvelope ementation veillance, RS, Tek et la Coord ination MR-SSNS-339443-NC-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Pending Impl Maintenance materiel inform IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2023-04-01 2023-05-27 2023-07-02 tions nvelope ementation atique et froids (Tek et Coord f poor households ination) MR-SSNS-339683-NC-RFQ / Component 2: Enhancing th Request for Quota Single Stage - One E Pending Impl Medias (Production et diffusi IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2023-02-25 2023-04-22 2024-04-21 tions nvelope ementation on audiovisuelle) f poor households MR-SSNS-342207-NC-RFB / S élection d’un ou Plusieurs Op erateur des Paiements Mobil Component 2: Enhancing th es dans le cadre de réalisatio Single Stage - One E Under Imple IDA / D5680 e socio-economic inclusion o Post Request for Bids Open - National 0.00 2023-02-20 2023-03-08 2023-02-25 2023-03-09 2023-03-18 2023-04-01 2023-04-18 2025-09-30 n des transferts monétaires a nvelope mentation f poor households u profit du ménages inscrit (1 4 193 ménages) dans les Wil ayas de Nouakchott Nord, Su d et Ouest, en trois (03) lots MR-SSNS-342246-NC-DIR / C Component 4: Project Coordi Pending Impl ontrat de maintenace du Sys IDA / D5680 Post Direct Selection Direct - National 0.00 2023-03-27 2023-04-01 2023-05-06 2024-05-05 nation and Management ementation teme TOMPRO MR-SSNS-339448-NC-RFP / S élection d’un Prestataire (Ca Component 1: Updating and Request for Quota Single Stage - One E Pending Impl binet médical) pour la réalisa IDA / D5680 enhancing the Social Registr Post Limited 0.00 2023-04-04 2023-05-30 2023-11-26 tions nvelope ementation tion de visites et examens m y édicaux au profit du personn el du Projet PASyFiS II MR-SSNS-363005-NC-RFB / s élection d’un prestataire de s ervice dans le cadre d’un acc Component 1: Updating and Single Stage - One E Pending Impl ord cadre de 24 mois pour la IDA / D5680 enhancing the Social Registr Post Request for Bids Open - National 0.00 2023-06-01 2023-06-06 2023-07-18 2023-08-17 2023-09-21 2024-03-19 nvelope ementation location de véhicules tout ter y rain pour le Projet d’Appui au Système des Filets Sociaux II (PASyFiS II). CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-SSNS-196264-CS-LCS / A uditeur Externe pour les exer Component 4: Project Coordi Least Cost Selecti Open - Internationa Under Implement IDA / D5680 Prior 0.00 2020-09-28 2020-09-25 2020-10-19 2020-10-13 2020-12-02 2021-01-19 2020-12-30 2021-03-09 2021-01-29 2021-06-15 2021-03-05 2021-04-09 2021-10-06 cices 2020, 2021 et 2022 - U nation and Management on l ation nité de Coordination MR-SSNS-212039-CS-CQS / Développement d’une API d’ Component 1: Updating and accès externe et d’un systèm Consultant Qualifi Open - Internationa IDA / D5680 enhancing the Social Registr Post 0.00 Canceled 2021-02-15 2021-03-08 2021-04-21 2021-05-21 2021-06-25 2021-12-22 e de collecte des retours et d cation Selection l y es activités des utilisateurs d es données du Registre socia l RS Page 4 MR-SSNS-212041-CS-CQS / Création d'une plateforme w eb pour l'accès et la gestion Component 1: Updating and Consultant Qualifi sécurisées de données ména IDA / D5680 enhancing the Social Registr Post Open - National 0.00 Canceled 2021-02-17 2021-03-10 2021-04-23 2021-05-23 2021-06-27 2021-12-24 cation Selection ges inscrits (Développement y d’une interface et tableau de bord dynamique des donnée s du registre social) RS MR-SSNS-212042-CS-CQS / Component 1: Updating and Consultant Qualifi Analyse des profils ménages IDA / D5680 enhancing the Social Registr Post Open - National 0.00 Canceled 2021-02-23 2021-03-16 2021-04-29 2021-05-29 2021-07-03 2021-12-30 cation Selection enregistrés dans la base de d y onnées RS MR-SSNS-212044-CS-CQS / Component 1: Updating and Création d'un système de gé Consultant Qualifi Pending Impleme IDA / D5680 enhancing the Social Registr Post Open - National 0.00 2021-03-01 2021-03-22 2021-05-05 2021-06-04 2021-07-09 2022-01-05 nération et de lecture autom cation Selection ntation y atique des cartes de ménage s RS MR-SSNS-211981-CS-CQS / T Component 4: Project Coordi Consultant Qualifi raduction de documents du P IDA / D5680 Post Open - National 0.00 Canceled 2021-01-20 2021-02-10 2021-03-26 2021-04-25 2021-05-30 2021-11-26 nation and Management cation Selection aSyFiS II Coord. MR-SSNS-219081-CS-CQS / Component 2: Enhancing th Consultant Qualifi Under Implement Bureau pour l'élaboration de IDA / D5680 e socio-economic inclusion o Post Open - National 0.00 2021-02-22 2021-03-15 2021-03-15 2021-04-28 2021-03-09 2021-05-28 2022-04-22 2021-07-02 2021-12-29 cation Selection ation l'enquête de suivi Spotcheck f poor households du PASYFIS II MR-SSNS-276762-CS-CQS / Component 1: Updating and Consultant Qualifi Pending Impleme Analyse des profils ménages IDA / D5680 enhancing the Social Registr Post Open - National 0.00 2022-07-07 2022-07-28 2022-09-10 2022-10-10 2022-11-14 2023-05-13 cation Selection ntation enregistrés dans la base de d y onnées RS MR-SSNS-276764-CS-CQS / Création d'une plateforme w eb pour l'accès et la gestion Component 1: Updating and Consultant Qualifi Under Implement sécurisées de données ména IDA / D5680 enhancing the Social Registr Post Open - National 0.00 2022-04-29 2022-06-30 2022-05-20 2022-08-29 2022-07-03 2022-08-21 2022-08-02 2022-09-05 2022-09-06 2023-03-05 cation Selection ation ges inscrits (Développement y d’une interface et tableau de bord dynamique des donnée s du registre social) MR-SSNS-266009-CS-QCBS / Recrutement des structures d’accompagnement AGR pou Component 2: Enhancing th r la mise en œuvre du progra Quality And Cost- Under Implement IDA / D5680 e socio-economic inclusion o Post Open - National 0.00 2022-01-03 2021-12-13 2022-01-24 2022-03-09 2022-07-28 2022-04-06 2022-09-06 2022-05-06 2022-10-17 2022-06-10 2022-10-31 2022-07-15 2023-07-15 mme d’accompagnement de Based Selection ation f poor households s ménages bénéficiaires du p aquet de services d’inclusion économique dans le cadre de la sous composante 2.2. du P ASyFiSII MR-SSNS-292496-CS-CQS / Component 4: Project Coordi Consultant Qualifi Under Implement IDA / D5680 Post Open - National 0.00 2022-03-10 2022-04-04 2022-03-31 2022-05-14 2022-08-15 2022-06-13 2022-08-29 2022-07-18 2023-01-14 Audit RH /Coord nation and Management cation Selection ation MR-SSNS-276923-CS-QCBS / Component 4: Project Coordi Quality And Cost- Under Implement Audit Protection des données IDA / D5680 Post Open - National 0.00 2022-02-14 2022-07-14 2022-03-07 2022-08-23 2022-04-20 2022-05-18 2022-06-17 2022-07-22 2022-08-26 2023-08-26 nation and Management Based Selection ation et sécurité des systèmes MR-SSNS-276765-CS-CQS / Développement d’une API d’ Component 1: Updating and accès externe et d’un systèm Consultant Qualifi Pending Impleme IDA / D5680 enhancing the Social Registr Post Open - National 0.00 2023-04-28 2023-05-19 2023-07-02 2023-08-01 2023-09-05 2024-03-03 e de collecte des retours et d cation Selection ntation y es activités des utilisateurs d es données du Registre socia l MR-SSNS-339431-CS-CQS / S ÉLECTION D’UN CONSULTAN Component 3: Strengthening T (FIRME) INFORMATIQUE / D the shock response system f Consultant Qualifi Under Implement IDA / D5680 Post Open - National 0.00 2023-02-20 2023-03-01 2023-03-13 2023-04-26 2023-05-26 2023-06-30 2023-12-27 ÉVELOPPEUR or households vulnerable to cation Selection ation INTERNATIONAL POUR LE DÉ climate-shocks VELOPPEMENT DE LA PLATEF ORME D’INFORMATION DE L’ OSA MR-SSNS-212022-CS-CQS / Component 1: Updating and Acquisition d’un système d’a Consultant Qualifi IDA / D5680 enhancing the Social Registr Post Open - National 0.00 Canceled 2021-02-08 2021-03-01 2021-04-14 2021-05-14 2021-06-18 2021-12-15 rchivage numérique et gestio cation Selection y n elecronique des documents RS INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-SSNS-199379-CS-CDS / E Component 2: Enhancing th nquête d'Evaluation d'Impact IDA / D5680 e socio-economic inclusion o Prior Direct Selection Direct 449,184.00 Signed 2020-10-13 2020-10-13 2020-10-23 2019-11-12 2020-12-27 2020-11-10 2021-06-25 (midline) f poor households MR-SSNS-212051-CS-INDV / Component 4: Project Coordi Individual Consult Pending Impleme IDA / D5680 Post Open 0.00 2021-02-16 2021-04-06 2021-04-27 2021-06-01 2021-11-28 Secretaire Coord nation and Management ant Selection ntation MR-SSNS-212052-CS-INDV / Component 4: Project Coordi Individual Consult Pending Impleme IDA / D5680 Post Open 0.00 2021-02-10 2021-03-31 2021-04-21 2021-05-26 2021-11-22 Assistant SE (02) Coord nation and Management ant Selection ntation MR-SSNS-212057-CS-INDV / Component 2: Enhancing th Individual Consult Pending Impleme 2 Facilitateurs/trices Dialogu IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-02-18 2021-04-08 2021-04-29 2021-06-03 2021-11-30 ant Selection ntation e Familiale TEK f poor households MR-SSNS-212061-CS-INDV / 7 superviseurs pour les Moug Component 2: Enhancing th Individual Consult Pending Impleme hataas du Hodh Chargui ( Ti IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-02-02 2021-03-23 2021-04-13 2021-05-18 2021-11-14 ant Selection ntation mbedra, Nema, Bassiknou, N' f poor households Beiket Lehwach, Oualata, Am ourj, Djiguenni) TEK MR-SSNS-212064-CS-INDV / 13 animateurs (2 à Timbedra Component 2: Enhancing th Individual Consult Pending Impleme , 2 à Nema, 1 à Bassiknou, 1 IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-03-09 2021-04-27 2021-05-18 2021-06-22 2021-12-19 ant Selection ntation à N'Beiket Lehwach, 1 à Oula f poor households ta, 3 à Amourj et 3 à Djiguen ni) TEK MR-SSNS-212221-CS-INDV / Component 2: Enhancing th Individual Consult Under Implement 12 Enquêteurs de suivi spot c IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2021-01-20 2021-01-25 2021-02-15 2021-03-22 2021-09-18 ant Selection ation heck T4 2020, et T1/T2/T3 20 f poor households 21 TEK MR-SSNS-212231-CS-INDV / Component 2: Enhancing th Individual Consult Pending Impleme Traducteur pour l'unité Dialo IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2021-01-20 2021-01-25 2021-02-15 2021-03-22 2021-09-18 ant Selection ntation gue et Ressources Familiales f poor households TEK Page 5 MR-SSNS-212233-CS-INDV / Component 2: Enhancing th Individual Consult Pending Impleme Prestation graphiste pour ad IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2021-03-30 2021-04-04 2021-04-25 2021-05-30 2021-11-26 ant Selection ntation aptation du manuel (dessin; f poor households graphiques) TEK MR-SSNS-212241-CS-INDV / Component 4: Project Coordi Individual Consult Under Implement IDA / D5680 Post Open 0.00 2021-01-20 2020-04-10 2021-03-10 2021-02-24 2021-03-31 2021-03-11 2021-05-05 2021-11-01 Aide comptable Coord nation and Management ant Selection ation MR-SSNS-212244-CS-INDV / Component 1: Updating and Individual Consult Under Implement IDA / D5680 Post Open 0.00 2021-01-20 2021-05-18 2021-03-10 2021-09-06 2021-03-31 2021-09-06 2021-05-05 2021-11-01 Assistant Communication RS enhancing the Social Registr ant Selection ation y MR-SSNS-212245-CS-INDV / Component 1: Updating and Individual Consult Under Implement IDA / D5680 Post Open 0.00 2021-01-20 2021-05-18 2021-03-10 2021-03-31 2021-05-05 2021-11-01 Assistant archivage RS enhancing the Social Registr ant Selection ation y Component 2: Enhancing th MR-SSNS-212284-CS-INDV / Individual Consult Pending Impleme IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-02-15 2021-04-05 2021-04-26 2021-05-31 2021-11-27 Animateur Teintan TK ant Selection ntation f poor households MR-SSNS-212004-CS-INDV / Component 4: Project Coordi Individual Consult Pending Impleme Consultant chargé de la gesti IDA / D5680 Post Limited 0.00 2021-02-16 2021-02-21 2021-03-14 2021-04-18 2021-10-15 nation and Management ant Selection ntation on de l'infrastructure informa tique Coord MR-SSNS-212046-CS-INDV / Component 1: Updating and Individual Consult Under Implement Responsable Administratif et IDA / D5680 enhancing the Social Registr Prior Open 0.00 2021-02-08 2021-02-17 2021-03-29 2021-03-30 2021-04-19 2021-04-15 2021-05-24 2021-11-20 ant Selection ation Moyens Généraux Coordinati y on MR-SSNS-212236-CS-INDV / Component 2: Enhancing th Individual Consult Pending Impleme Responsable Promotion Socia IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-01-04 2021-02-22 2021-03-15 2021-04-19 2021-10-16 ant Selection ntation le TEK. f poor households MR-SSNS-212237-CS-INDV / Component 2: Enhancing th Individual Consult Under Implement Responsable Développement IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-01-20 2021-06-02 2021-03-10 2021-03-31 2021-05-05 2021-11-01 ant Selection ation Plateforme TEK f poor households MR-SSNS-212238-CS-INDV / Component 4: Project Coordi Individual Consult Under Implement IDA / D5680 Prior Open 0.00 2021-01-20 2021-03-25 2021-03-10 2021-03-31 2021-05-05 2021-11-01 Expert Point Focal Bassiknou nation and Management ant Selection ation Coord MR-SSNS-212287-CS-CDS / E Component 1: Updating and Pending Impleme xpert informatique et base d IDA / D5680 enhancing the Social Registr Post Direct Selection Direct 0.00 2021-01-13 2021-01-23 2021-03-29 2021-09-25 ntation e données RS y MR-SSNS-212288-CS-CDS / E Component 1: Updating and Pending Impleme IDA / D5680 Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 xpert mobilisation sociale RS enhancing the Social Registr ntation y MR-SSNS-212228-CS-INDV / Component 2: Enhancing th Individual Consult Pending Impleme Production films primoadopta IDA / D5680 e socio-economic inclusion o Post Direct 0.00 2021-01-20 2021-01-30 2021-02-20 2021-03-27 2021-09-23 ant Selection ntation nts TEK f poor households MR-SSNS-212289-CS-CDS / E Component 1: Updating and Pending Impleme IDA / D5680 Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 xpert Collecte de Données R enhancing the Social Registr ntation S y MR-SSNS-212290-CS-CDS / Component 1: Updating and Pending Impleme Gestionnaire / médiateur récl IDA / D5680 enhancing the Social Registr Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ntation amations RS y MR-SSNS-212291-CS-CDS / Component 1: Updating and Pending Impleme IDA / D5680 Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Assistant administratif RS enhancing the Social Registr ntation y MR-SSNS-212292-CS-CDS / Component 1: Updating and Pending Impleme Assistant informatique et ba IDA / D5680 enhancing the Social Registr Post Direct Selection 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ntation se de données RS y MR-SSNS-212296-CS-CDS / S Component 1: Updating and Pending Impleme IDA / D5680 Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ecrétaire (1) RS enhancing the Social Registr ntation y MR-SSNS-212298-CS-CDS / Component 2: Enhancing th Pending Impleme Coordinateur du programme IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ntation transferts sociaux TK f poor households MR-SSNS-212299-CS-CDS / Component 2: Enhancing th Pending Impleme Responsable supervision pai IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ntation ements TK f poor households MR-SSNS-212300-CS-CDS / Component 2: Enhancing th Pending Impleme Responsable du système d'in IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ntation formation TK f poor households MR-SSNS-212302-CS-CDS / Component 2: Enhancing th Pending Impleme Responsable promotion dial IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ntation ogue et Ressource Familiale f poor households TK MR-SSNS-212306-CS-CDS / Component 2: Enhancing th Pending Impleme Gestionnaire des réclamation IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ntation s TEK f poor households Component 2: Enhancing th MR-SSNS-212307-CS-CDS / S Pending Impleme IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ecrétaire TK ntation f poor households MR-SSNS-212309-CS-CDS / S Component 4: Project Coordi Pending Impleme pécialiste en passation des m IDA / D5680 Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 nation and Management ntation archés Coord MR-SSNS-212235-CS-INDV / Component 4: Project Coordi Individual Consult Under Implement IDA / D5680 Prior Limited 0.00 2021-01-20 2021-03-05 2021-01-25 2021-03-11 2021-02-15 2021-03-25 2021-03-22 2021-09-18 Responsable Communication nation and Management ant Selection ation Coord. MR-SSNS-212303-CS-CDS / Component 2: Enhancing th Pending Impleme Adjoint au RSI Developpeme IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ntation nt SI TK f poor households Component 2: Enhancing th MR-SSNS-212304-CS-CDS / Pending Impleme IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Adjoint au Resp PS TK ntation f poor households Component 2: Enhancing th MR-SSNS-212305-CS-CDS / Pending Impleme IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Assistante de DirectionTK ntation f poor households Page 6 MR-SSNS-212310-CS-CDS / Component 4: Project Coordi Pending Impleme IDA / D5680 Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Auditeur interne Coord nation and Management ntation MR-SSNS-212311-CS-CDS / Component 4: Project Coordi Under Implement IDA / D5680 Post Direct Selection Direct 0.00 2021-01-12 2021-11-09 2021-01-22 2021-03-28 2021-09-24 Responsable Suivi Evaluation nation and Management ation Coor MR-SSNS-212312-CS-CDS / Component 4: Project Coordi Pending Impleme IDA / D5680 Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Responsable de communicati nation and Management ntation on Coor MR-SSNS-212313-CS-CDS / Component 4: Project Coordi Pending Impleme IDA / D5680 Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Assistant Comptable et Finan nation and Management ntation cier Coord MR-SSNS-212314-CS-CDS / Component 4: Project Coordi Pending Impleme Assistant Moyens Généraux e IDA / D5680 Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 nation and Management ntation t logistique Coord MR-SSNS-212315-CS-CDS / Component 4: Project Coordi Pending Impleme IDA / D5680 Post Direct Selection Direct 0.00 2021-01-05 2021-01-15 2021-03-21 2021-09-17 Assistant RH Coord nation and Management ntation MR-SSNS-212316-CS-CDS / Component 4: Project Coordi Pending Impleme IDA / D5680 Post Direct Selection Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Consultant informatique Coor nation and Management ntation MR-SSNS-219094-CS-INDV / Component 3: Strengthening Consultant international pour the shock response system f Individual Consult Pending Impleme IDA / D5680 Post Open 0.00 2021-02-26 2021-04-16 2021-05-07 2021-06-11 2021-12-08 la mise en place de la stratég or households vulnerable to ant Selection ntation ie de financement de la répo climate-shocks nse MR-SSNS-219102-CS-INDV / Component 3: Strengthening Consultant National pour la the shock response system f Individual Consult Pending Impleme IDA / D5680 Post Open 0.00 2021-02-24 2021-04-14 2021-05-05 2021-06-09 2021-12-06 mise en place de la stratégie or households vulnerable to ant Selection ntation de financement de la répons climate-shocks e MR-SSNS-219204-CS-INDV / Component 2: Enhancing th Individual Consult Under Implement Illustrateur pour l'unité Dialo IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-02-25 2021-05-22 2021-04-15 2021-05-06 2021-06-10 2021-12-07 ant Selection ation gue et Ressources Familiales f poor households MR-SSNS-219206-CS-INDV / Component 1: Updating and Individual Consult Pending Impleme IDA / D5680 Post Open 0.00 2021-02-25 2021-04-15 2021-05-06 2021-06-10 2021-12-07 Assistant SIG RS enhancing the Social Registr ant Selection ntation y MR-SSNS-219207-CS-INDV / Component 1: Updating and Individual Consult Pending Impleme IDA / D5680 Post Open 0.00 2021-02-24 2021-04-14 2021-05-05 2021-06-09 2021-12-06 2 Superviseurs mobilisation s enhancing the Social Registr ant Selection ntation ociale y Component 3: Strengthening MR-SSNS-219213-CS-INDV / the shock response system f Individual Consult Under Implement Expert en sécurité alimentair IDA / D5680 Post Open 0.00 2021-02-24 2021-07-26 2021-04-14 2021-11-05 2021-05-05 2021-11-05 2021-06-09 2021-12-06 or households vulnerable to ant Selection ation e climate-shocks Component 3: Strengthening MR-SSNS-219215-CS-INDV / the shock response system f Individual Consult Pending Impleme IDA / D5680 Post Open 0.00 2021-02-25 2021-04-15 2021-05-06 2021-06-10 2021-12-07 Coordinateur de la Réponse or households vulnerable to ant Selection ntation climate-shocks Component 3: Strengthening MR-SSNS-219216-CS-INDV / the shock response system f Individual Consult Pending Impleme IDA / D5680 Post Open 0.00 2021-02-25 2021-04-15 2021-05-06 2021-06-10 2021-12-07 Amélioration du site Web or households vulnerable to ant Selection ntation climate-shocks MR-SSNS-219256-CS-INDV / Component 2: Enhancing th Individual Consult Pending Impleme Responsable appui à l’enrôle IDA / D5680 e socio-economic inclusion o Post Direct 0.00 2021-12-08 2021-12-18 2022-01-08 2022-02-12 2022-08-11 ant Selection ntation ment à l'Etat civil f poor households MR-SSNS-219258-CS-INDV / Component 2: Enhancing th Individual Consult Pending Impleme Responsable mesure inclusio IDA / D5680 e socio-economic inclusion o Post Direct 0.00 2021-12-08 2021-12-18 2022-01-08 2022-02-12 2022-08-11 ant Selection ntation n économique f poor households MR-SSNS-219261-CS-INDV / Component 2: Enhancing th Individual Consult Under Implement 1 adjoint au RSI Base de don IDA / D5680 e socio-economic inclusion o Post Direct 0.00 2021-12-16 2020-04-10 2021-12-26 2022-01-16 2022-02-20 2022-08-19 ant Selection ation nées f poor households Component 2: Enhancing th MR-SSNS-219264-CS-INDV / Individual Consult Pending Impleme IDA / D5680 e socio-economic inclusion o Post Direct 0.00 2021-12-13 2021-12-23 2022-01-13 2022-02-17 2022-08-16 Adjoint au Resp PS ant Selection ntation f poor households MR-SSNS-219266-CS-INDV / Component 2: Enhancing th Individual Consult Pending Impleme Adjoint au Resp paiement (0 IDA / D5680 e socio-economic inclusion o Post Direct 0.00 2021-12-15 2021-12-25 2022-01-15 2022-02-19 2022-08-18 ant Selection ntation 2) f poor households MR-SSNS-219268-CS-INDV / Component 2: Enhancing th Individual Consult 6 Facilitateurs "promotion di IDA / D5680 e socio-economic inclusion o Post Direct 0.00 Canceled 2021-12-15 2021-12-25 2022-01-15 2022-02-19 2022-08-18 ant Selection alogue familial" f poor households MR-SSNS-219269-CS-INDV / Component 4: Project Coordi Individual Consult Pending Impleme IDA / D5680 Post Direct 0.00 2021-12-15 2021-12-25 2022-01-15 2022-02-19 2022-08-18 Responsable Financier et Co nation and Management ant Selection ntation mptable MR-SSNS-219270-CS-INDV / Component 4: Project Coordi Individual Consult Pending Impleme IDA / D5680 Post Direct 0.00 2021-12-16 2021-12-26 2022-01-16 2022-02-20 2022-08-19 Responsable Social et genre nation and Management ant Selection ntation MR-SSNS-219271-CS-INDV / Component 4: Project Coordi Individual Consult IDA / D5680 Post Direct 0.00 Canceled 2021-12-08 2021-12-18 2022-01-08 2022-02-12 2022-08-11 Assistant Passation des Marc nation and Management ant Selection hés MR-SSNS-219272-CS-INDV / Component 4: Project Coordi Individual Consult Pending Impleme IDA / D5680 Post Direct 0.00 2021-12-16 2021-12-26 2022-01-16 2022-02-20 2022-08-19 Assistant communication nation and Management ant Selection ntation MR-SSNS-254473-CS-CDS / Conception et la production d Component 1: Updating and es cartes graphiques pour les IDA / D5680 enhancing the Social Registr Post Direct Selection Direct 22,211.81 Signed 2021-09-22 2021-09-24 2021-10-02 2021-09-30 2021-12-06 2021-10-14 2022-06-04 districts de recensement des y neuves communes de Nouak chott Component 2: Enhancing th MR-SSNS-254598-CS-INDV / Individual Consult Under Implement IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-09-22 2021-09-12 2021-11-10 2021-12-01 2022-01-05 2022-07-04 Animateur Tintane ant Selection ation f poor households MR-SSNS-254603-CS-INDV / Component 1: Updating and Individual Consult Under Implement IDA / D5680 Post Open 0.00 2021-09-22 2021-09-21 2021-11-10 2021-12-01 2022-01-05 2022-07-04 Deux 2 animateurs pour le R enhancing the Social Registr ant Selection ation S y MR-SSNS-254606-CS-INDV / Component 1: Updating and Individual Consult Pending Impleme IDA / D5680 Post Open 0.00 2021-09-22 2021-11-10 2021-12-01 2022-01-05 2022-07-04 Assistant RSI enhancing the Social Registr ant Selection ntation y Page 7 Component 2: Enhancing th MR-SSNS-254613-CS-INDV / Individual Consult Under Implement IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-09-27 2021-09-29 2021-11-15 2021-12-06 2022-01-10 2022-07-09 Superviseur Koubeni ant Selection ation f poor households Component 3: Strengthening MR-SSNS-219214-CS-INDV / the shock response system f Individual Consult Under Implement Assistant technique du progr IDA / D5680 Post Open 0.00 2021-02-25 2021-06-24 2021-04-15 2021-10-14 2021-05-06 2021-10-14 2021-06-10 2021-12-07 or households vulnerable to ant Selection ation amme ELMAOUNA climate-shocks MR-SSNS-219217-CS-INDV / Component 1: Updating and Individual Consult Under Implement IDA / D5680 Post Open 0.00 2021-02-24 2021-05-18 2021-04-14 2021-05-05 2021-06-09 2021-12-06 Assistant mise à jour du RS enhancing the Social Registr ant Selection ation y MR-SSNS-219103-CS-INDV / Component 3: Strengthening Consultant International App the shock response system f Individual Consult Pending Impleme IDA / D5680 Post Open 0.00 2021-02-25 2021-04-15 2021-05-06 2021-06-10 2021-12-07 ui à la mise en place d'un ca or households vulnerable to ant Selection ntation dre permanent de réponse a climate-shocks ux chocs Component 3: Strengthening MR-SSNS-219193-CS-INDV / the shock response system f Individual Consult Under Implement IDA / D5680 Post Open 0.00 2021-02-24 2021-01-28 2021-04-14 2021-04-20 2021-05-05 2021-04-20 2021-06-09 2021-12-06 Statisticien junior OSA or households vulnerable to ant Selection ation climate-shocks MR-SSNS-254621-CS-CDS / Component 2: Enhancing th Contractualisation avec la Fir IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 0.00 Canceled 2021-09-22 2021-10-28 2021-10-02 2021-12-06 2022-06-04 me internationale AGR Inclus f poor households ion Economique Tekavoul Component 3: Strengthening MR-SSNS-257123-CS-INDV / the shock response system f Individual Consult Under Implement Assistant chargé de la mise e IDA / D5680 Post Open 0.00 2021-10-11 2021-07-13 2021-11-29 2021-12-20 2022-01-24 2022-07-23 or households vulnerable to ant Selection ation n œuvre du dispositif climate-shocks Component 3: Strengthening MR-SSNS-257215-CS-INDV / the shock response system f Individual Consult Under Implement Informaticien développeur (O IDA / D5680 Post Open 0.00 2021-12-16 2022-02-08 2022-02-03 2022-02-24 2022-03-31 2022-09-27 or households vulnerable to ant Selection ation SA) climate-shocks Component 2: Enhancing th MR-SSNS-257227-CS-INDV / Individual Consult Pending Impleme IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-10-13 2021-12-01 2021-12-22 2022-01-26 2022-07-25 3 Animateur Kaédi ant Selection ntation f poor households MR-SSNS-257218-CS-INDV / Component 1: Updating and Individual Consult Under Implement IDA / D5680 Post Open 0.00 2021-10-12 2021-04-22 2021-11-30 2021-10-14 2021-12-21 2021-10-14 2022-01-25 2022-07-24 Responsable de qualité RS enhancing the Social Registr ant Selection ation y MR-SSNS-257210-CS-INDV / Component 4: Project Coordi Individual Consult Under Implement IDA / D5680 Post Open 0.00 2021-11-17 2021-11-04 2022-01-05 2022-01-26 2022-03-02 2022-08-29 Responsable SE nation and Management ant Selection ation MR-SSNS-257195-CS-INDV / Component 4: Project Coordi Individual Consult Under Implement IDA / D5680 Post Open 0.00 2021-10-09 2021-07-30 2021-11-27 2021-11-16 2021-12-18 2021-11-30 2022-01-22 2022-07-21 Consultant Formateur NES nation and Management ant Selection ation Component 2: Enhancing th MR-SSNS-260197-CS-INDV / Individual Consult Under Implement IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-10-28 2021-10-27 2021-12-16 2022-02-08 2022-01-06 2022-02-24 2022-02-10 2022-08-09 1 Facilitateur H ant Selection ation f poor households Component 2: Enhancing th MR-SSNS-260198-CS-INDV / Individual Consult Under Implement IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-10-28 2021-10-27 2021-12-16 2022-02-11 2022-01-06 2022-02-24 2022-02-10 2022-08-09 3 Facilitateurs P ant Selection ation f poor households MR-SSNS-263939-CS-INDV / Component 2: Enhancing th Individual Consult Under Implement 1 Gestionnaire de Réclamatio IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-11-19 2021-11-04 2022-01-07 2022-02-14 2022-01-28 2022-02-14 2022-03-04 2022-08-31 ant Selection ation n TEKAVOUL f poor households MR-SSNS-263941-CS-INDV / Component 2: Enhancing th Individual Consult Under Implement Assistant Responsable Systè IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-11-19 2021-11-04 2022-01-07 2022-02-11 2022-01-28 2022-02-25 2022-03-04 2022-08-31 ant Selection ation me d'Information TEKAVOUL f poor households MR-SSNS-263945-CS-INDV / Component 4: Project Coordi Individual Consult Under Implement IDA / D5680 Post Open 0.00 2021-11-19 2021-11-04 2022-01-07 2022-01-28 2022-03-04 2022-08-31 Spécialiste Passation de Marc nation and Management ant Selection ation hés Component 2: Enhancing th MR-SSNS-263947-CS-INDV / Individual Consult Under Implement IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-11-19 2021-11-15 2022-01-07 2022-01-28 2022-03-04 2022-08-31 Superviseur Ghabou ant Selection ation f poor households Component 2: Enhancing th MR-SSNS-263949-CS-INDV / Individual Consult Under Implement IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-11-19 2021-11-15 2022-01-07 2022-01-28 2022-03-04 2022-08-31 Superviseur Sélibaby ant Selection ation f poor households MR-SSNS-264045-CS-CDS / Component 2: Enhancing th Contractualisation avec la Fir Under Implement IDA / D5680 e socio-economic inclusion o Prior Direct Selection Direct 0.00 2021-12-02 2022-12-21 2021-12-12 2023-01-26 2022-02-15 2022-08-14 me internationale AGR Inclus ation f poor households ion Economique Tekavoul Component 2: Enhancing th MR-SSNS-264051-CS-INDV / Individual Consult Under Implement IDA / D5680 e socio-economic inclusion o Post Open 0.00 2021-11-26 2021-11-15 2022-01-14 2022-02-04 2022-03-11 2022-09-07 2 Animateurs Selibaby ant Selection ation f poor households MR-SSNS-264052-CS-INDV / Component 4: Project Coordi Individual Consult Under Implement IDA / D5680 Post Open 0.00 2021-11-19 2021-11-15 2022-01-07 2022-01-28 2022-03-04 2022-08-31 Responsable Financier et Co nation and Management ant Selection ation mptable MR-SSNS-264055-CS-INDV / Component 4: Project Coordi Individual Consult Under Implement IDA / D5680 Post Open 0.00 2021-11-19 2021-11-15 2022-01-07 2022-01-28 2022-03-04 2022-08-31 Responsable Genre et Social nation and Management ant Selection ation Component 3: Strengthening MR-SSNS-264056-CS-INDV / the shock response system f Individual Consult Under Implement IDA / D5680 Post Open 0.00 2021-11-19 2021-11-15 2022-01-07 2022-01-28 2022-03-04 2022-08-31 Assistant SI El Maouna or households vulnerable to ant Selection ation climate-shocks MR-SSNS-267846-CS-CDS / P Component 2: Enhancing th roduction films primoadoptan IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 42,282.63 Signed 2021-12-14 2021-01-11 2021-12-24 2021-01-29 2022-02-27 2022-01-12 2022-08-26 ts TEK f poor households MR-SSNS-276749-CS-INDV / Component 1: Updating and Individual Consult Pending Impleme Expert Gestionnaire / médiat IDA / D5680 enhancing the Social Registr Post Open 0.00 2022-03-17 2022-05-05 2022-05-26 2022-06-30 2022-12-27 ant Selection ntation eur réclamations RS y MR-SSNS-276752-CS-INDV / Component 1: Updating and Individual Consult IDA / D5680 Post Open 0.00 Canceled 2022-03-16 2022-05-04 2022-05-25 2022-06-29 2022-12-26 Refonte du site web du Regis enhancing the Social Registr ant Selection tre CI y Page 8 MR-SSNS-276768-CS-INDV / Component 2: Enhancing th Individual Consult Under Implement Animateurs 'Tekavoul" (53) p IDA / D5680 e socio-economic inclusion o Post Open 0.00 2022-02-16 2022-02-15 2022-04-06 2022-04-27 2022-06-01 2022-11-28 ant Selection ation our 48 000 ménages f poor households MR-SSNS-276772-CS-INDV / Component 2: Enhancing th Individual Consult Under Implement Superviseur de Terrain 'Teka IDA / D5680 e socio-economic inclusion o Post Open 0.00 2022-02-17 2022-02-07 2022-04-07 2022-04-28 2022-06-02 2022-11-29 ant Selection ation voul" (5) f poor households MR-SSNS-276914-CS-INDV / Component 2: Enhancing th Individual Consult Pending Impleme Prestation traducteurs (10 jo IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2022-03-23 2022-03-28 2022-04-18 2022-05-23 2022-11-19 ant Selection ntation urs) TK / DF f poor households MR-SSNS-276920-CS-INDV / Component 4: Project Coordi Individual Consult Pending Impleme IDA / D5680 Post Limited 0.00 2022-04-05 2022-04-10 2022-05-01 2022-06-05 2022-12-02 Consultant junior (3) Coord nation and Management ant Selection ntation MR-SSNS-276925-CS-INDV / Component 4: Project Coordi Individual Consult Pending Impleme Consultant pour le calcul des IDA / D5680 Post Open 0.00 2022-03-28 2022-05-16 2022-06-06 2022-07-11 2023-01-07 nation and Management ant Selection ntation quotas RS et TEK MR-SSNS-276948-CS-INDV / Component 3: Strengthening Assistant en rédaction et co the shock response system f Individual Consult Pending Impleme IDA / D5680 Post Open 0.00 2022-04-19 2022-06-07 2022-06-28 2022-08-02 2023-01-29 mmunication Elmaaouna (OS or households vulnerable to ant Selection ntation A Observatoire de la Sécurité climate-shocks Alimentaire) MR-SSNS-282215-CS-INDV / Component 2: Enhancing th Recrutement de six (6) Gardi Individual Consult Pending Impleme IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2022-03-08 2022-03-13 2022-04-03 2022-05-08 2022-11-04 ens pour maisons (M'Bout, K ant Selection ntation f poor households ank, Selib, Aioun, Néma et M aghama) Component 2: Enhancing th MR-SSNS-283268-CS-INDV / Individual Consult Under Implement IDA / D5680 e socio-economic inclusion o Post Open 0.00 2022-03-22 2022-03-03 2022-05-10 2022-05-31 2022-07-05 2023-01-01 Animateur GHABOU ant Selection ation f poor households Component 2: Enhancing th MR-SSNS-283269-CS-INDV / Individual Consult Pending Impleme IDA / D5680 e socio-economic inclusion o Post Limited 0.00 2022-03-22 2022-03-27 2022-04-17 2022-05-22 2022-11-18 Planton/coursier TK ant Selection ntation f poor households MR-SSNS-289042-CS-CDS / Component 2: Enhancing th Recrutement d'un consultant IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 25,674.31 Signed 2022-04-08 2022-02-22 2022-04-18 2022-06-30 2022-06-22 2022-07-01 2022-12-19 pour initier les animateurs su f poor households r les modules d'inclusion éco nomique Tekavoul MR-SSNS-291583-CS-INDV / Component 4: Project Coordi Individual Consult Under Implement IDA / D5680 Post Limited 0.00 2022-04-21 2022-04-25 2022-04-26 2022-05-17 2022-06-21 2022-12-18 Assistant Comptable nation and Management ant Selection ation MR-SSNS-291584-CS-INDV / Component 4: Project Coordi Individual Consult IDA / D5680 Post Open 15,000.00 Signed 2022-04-25 2022-04-20 2022-06-13 2022-07-04 2022-07-04 2022-07-27 2022-08-08 2022-08-11 2023-02-04 Assistant Passation des Marc nation and Management ant Selection hés Component 2: Enhancing th MR-SSNS-291586-CS-INDV / Individual Consult Under Implement IDA / D5680 e socio-economic inclusion o Post Open 0.00 2022-04-25 2022-06-24 2022-06-13 2022-07-04 2022-08-08 2023-02-04 Assistant Promotion Sociale ant Selection ation f poor households MR-SSNS-292480-CS-INDV / Component 4: Project Coordi Individual Consult Under Implement Deux Assistants pour l'unité IDA / D5680 Post Limited 0.00 2022-04-29 2022-04-26 2022-05-04 2022-05-25 2022-06-29 2022-12-26 nation and Management ant Selection ation d'audit interne MR-SSNS-292501-CS-INDV / Component 4: Project Coordi Individual Consult Under Implement Responsable Financier et Co IDA / D5680 Post Limited 0.00 2022-05-11 2022-06-01 2022-05-16 2022-06-06 2022-07-11 2023-01-07 nation and Management ant Selection ation mptable (CI/Comp-CV) MR-SSNS-292503-CS-INDV / Component 4: Project Coordi Individual Consult Pending Impleme Responsable Social et genre IDA / D5680 Post Limited 0.00 2022-05-11 2022-05-16 2022-06-06 2022-07-11 2023-01-07 nation and Management ant Selection ntation (CI/Comp-CV) MR-SSNS-276771-CS-INDV / Component 2: Enhancing th Individual Consult Chauffeur (15) ( 13 pour TK e IDA / D5680 e socio-economic inclusion o Post Open 0.00 Canceled 2022-05-26 2022-07-14 2022-08-04 2022-09-08 2023-03-07 ant Selection t 2 pour CSA) f poor households Component 2: Enhancing th MR-SSNS-212308-CS-CDS / IDA / D5680 e socio-economic inclusion o Post Direct Selection Direct 0.00 Canceled 2021-02-15 2021-02-25 2021-05-01 2021-10-28 Chauffeurs (03) TK f poor households MR-SSNS-257047-CS-INDV / Component 2: Enhancing th Recrutement d'un consultant Individual Consult IDA / D5680 e socio-economic inclusion o Post Open 0.00 Canceled 2022-03-01 2022-04-19 2022-05-10 2022-06-14 2022-12-11 pour initier les animateurs su ant Selection f poor households r les modules d'inclusion éco nomique Tekavoul MR-SSNS-304770-CS-INDV / Recrutement de Neuf (9) Gar Component 1: Updating and Individual Consult Pending Impleme diens (2 pour RS, 3 pour TK, IDA / D5680 enhancing the Social Registr Post Limited 0.00 2022-08-05 2022-08-10 2022-08-31 2022-10-05 2023-04-03 ant Selection ntation 1 pour Coord, 1 pour Baskno y u, 1 pour Néma, 1 pour Magh ama) Juillet 2022 MR-SSNS-304831-CS-INDV / Recrutement de Onze (11) a Component 1: Updating and Individual Consult Pending Impleme nimateurs (remplacement: d IDA / D5680 enhancing the Social Registr Post Open - National 0.00 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2023-06-13 ant Selection ntation e1 pour RS et 3 TK ((Koubeni, y Mbout et Amourje)) et 7 pour Mberra) juillet 2022 MR-SSNS-304834-CS-INDV / Component 2: Enhancing th Recrutement d'un Supervise Individual Consult Pending Impleme IDA / D5680 e socio-economic inclusion o Post Open - National 0.00 2022-10-12 2022-11-30 2022-12-21 2023-01-25 2023-07-24 ur de Terrain 'Tekavoul" Mbe ant Selection ntation f poor households rra (01) Juillet 2022 MR-SSNS-304972-CS-INDV / Component 4: Project Coordi Individual Consult Pending Impleme Recrutement d'un Assistant IDA / D5680 Post Open - National 0.00 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2023-06-13 nation and Management ant Selection ntation Archive Coord Juillet 2022 MR-SSNS-212005-CS-INDV / Component 1: Updating and Recrutement de 28 Chauffeu Individual Consult Pending Impleme IDA / D5680 enhancing the Social Registr Post Limited 0.00 2021-01-20 2021-01-25 2021-02-15 2021-03-22 2021-09-18 rs (pour TK (8 TK; 1 Mbera, 9 ant Selection ntation y Extention), 2 ELMAOUNA, 6 R S, Coord 2) Juillet 2022 MR-SSNS-304976-CS-CDS / Component 4: Project Coordi Under Implement Recrutement d'un Avocat ou IDA / D5680 Post Direct Selection Direct - National 0.00 2022-07-26 2022-07-28 2022-08-05 2022-10-09 2023-04-07 nation and Management ation Conseiller juridique MR-SSNS-319327-CS-INDV / Component 3: Strengthening Recrutement d'un consultant the shock response system f Individual Consult Open - Internationa IDA / D5680 Post 0.00 Canceled 2022-10-05 2022-10-29 2022-11-19 2022-12-24 2023-12-19 international chargé d'appuiy or households vulnerable to ant Selection l er la mise en oeuvre du disp climate-shocks ositif du DCAN Page 9 MR-SSNS-325447-CS-INDV / Recrutement d'un responsabl Component 4: Project Coordi Individual Consult Pending Impleme IDA / D5680 Post Open - National 0.00 2022-11-07 2022-12-10 2022-12-15 2023-01-03 2023-12-29 e passation des marchés (RP nation and Management ant Selection ntation M) au profit de l'UCP PASyFiS II MR-SSNS-315465-CS-INDV / Component 4: Project Coordi Individual Consult Under Implement Consultant chargé de la revu IDA / D5680 Post Direct - National 0.00 2022-10-17 2022-12-15 2022-10-27 2022-12-15 2022-11-17 2022-12-19 2022-12-22 2023-02-20 nation and Management ant Selection ation e à mi-parcours pour le PSYFI S II MR-SSNS-334753-CS-CDS / Component 3: Strengthening Consultant chargé de l'organi the shock response system f Direct - Internation IDA / D5680 Post Direct Selection 0.00 Canceled 2023-01-09 2022-12-08 2023-01-16 2022-12-08 2023-01-19 2023-02-03 sation d'une formation sur le or households vulnerable to al PNR/DCAN climate-shocks MR-SSNS-339690-CS-INDV / Component 2: Enhancing th Individual Consult Under Implement Recutement de Cinq (05) Fac IDA / D5680 e socio-economic inclusion o Post Open - National 0.00 2023-03-31 2023-02-02 2023-05-19 2023-06-09 2023-07-14 2024-07-13 ant Selection ation ilitateurs Promotion DF f poor households MR-SSNS-339693-CS-INDV / Component 2: Enhancing th Individual Consult Under Implement Recrutement d'un Supervise IDA / D5680 e socio-economic inclusion o Post Open - National 0.00 2023-03-31 2023-02-02 2023-05-19 2023-06-09 2023-07-14 2024-07-13 ant Selection ation ur de terrain DF f poor households MR-SSNS-339694-CS-INDV / Component 1: Updating and Individual Consult Pending Impleme IDA / D5680 Post Open - National 0.00 2023-03-31 2023-05-19 2023-06-09 2023-07-14 2024-07-13 Recrutement d'un Animateur enhancing the Social Registr ant Selection ntation RS y MR-SSNS-339695-CS-INDV / Component 1: Updating and Individual Consult Under Implement Eecrutement d'un Assistant A COFN / C1950 enhancing the Social Registr Post Open - National 0.00 2023-03-31 2023-02-02 2023-05-19 2023-06-09 2023-07-14 2024-07-13 ant Selection ation rchivage RS y MR-SSNS-339696-CS-INDV / Component 2: Enhancing th Individual Consult Under Implement Recrutement de cinq (05) Ani IDA / D5680 e socio-economic inclusion o Post Open - National 0.00 2023-03-31 2023-03-02 2023-05-19 2023-06-09 2023-07-14 2024-07-13 ant Selection ation mateurs Tekavoul f poor households Component 3: Strengthening MR-SSNS-339699-CS-INDV / the shock response system f Individual Consult Pending Impleme Recrutement d'un Expert Sta IDA / D5680 Post Open - National 0.00 2023-03-31 2023-05-19 2023-06-09 2023-07-14 2024-07-13 or households vulnerable to ant Selection ntation tisticien OSA climate-shocks MR-SSNS-339705-CS-INDV / Component 4: Project Coordi Individual Consult Pending Impleme Recrutement d'un Assistant IDA / D5680 Post Open - National 0.00 2023-04-28 2023-06-16 2023-07-07 2023-08-11 2024-08-10 nation and Management ant Selection ntation Administratif et Comptable ( Coordination) MR-SSNS-339707-CS-INDV / Component 2: Enhancing th Recrutement de cinq (05) gar Individual Consult Pending Impleme COFN / C1950 e socio-economic inclusion o Post Limited 0.00 2023-03-31 2023-04-05 2023-04-26 2023-05-31 2024-05-30 diens (M'Bout, Kank, Selib, Ai ant Selection ntation f poor households oun et Bassiknou) MR-SSNS-339710-CS-INDV / Component 1: Updating and Individual Consult Pending Impleme Recrutement de vingt-un (21 COFN / C1950 enhancing the Social Registr Post Limited 0.00 2023-06-30 2023-07-05 2023-07-26 2023-08-30 2024-08-29 ant Selection ntation ) Chauffeurs pour toutes les c y omposantes MR-SSNS-342206-CS-INDV / Component 4: Project Coordi Individual Consult Under Implement Recrutement d'un Assistant P IDA / D5680 Post Open - National 0.00 2023-03-13 2023-02-02 2023-05-01 2023-05-22 2023-06-26 2024-06-25 nation and Management ant Selection ation assation de Marchés au profit du PASyFiS II MR-SSNS-339449-CS-CDS / Contractualisation avec un b ureau pour la realisation d'un Component 4: Project Coordi Under Implement e formation sur la passation IDA / D5680 Post Direct Selection Direct - National 0.00 2023-02-20 2023-02-27 2023-03-02 2023-05-06 2023-11-02 nation and Management ation de marchés (Procedures de l a Banque Mondiale) au profit des membres de la CPMP-Ta azour et le SPM du PASyFiS II MR-SSNS-339706-CS-INDV / Component 4: Project Coordi Individual Consult Pending Impleme Recrutement d'un Assistant IDA / D5680 Post Open - National 0.00 2023-04-28 2023-06-16 2023-07-07 2023-08-11 2024-08-10 nation and Management ant Selection ntation Auditeur interne (Coordinatio n) MR-SSNS-362971-CS-INDV / Component 3: Strengthening Recrutement d'un consultatio the shock response system f Individual Consult Pending Impleme n pour l appui à la la mise en IDA / D5680 Post Open - National 0.00 2023-06-05 2023-07-24 2023-08-14 2023-09-18 2024-03-16 or households vulnerable to ant Selection ntation place du système de suivi év climate-shocks aluation des Plans Nationaux de Réponse (PNR) Page 10 PROCUREMENT PLAN (Textual Part) Project Country: Kyrgyz Republic information Full Project Name: TAX ADMINISTRATION AND STATISTICAL SYSTEM MODERNIZATION PROJECT (TASSMP) Total Finance ($): USD 35,000,000 Project Number: P163711 Project Implementation agency State Tax Service KR (STS) National Statistical Committee KR (NSC) Date of the Procurement Plan January 20, 2020 Period covered by this Procurement September 2020 – September 30, Plan: 2025 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), procurement under World Bank financed operations may be carried out in accordance with “Single-Stage Bidding” method set forth in the Public Procurement Law of the Kyrgyz Republic dated April 3, 2015 № 72 (the “PPL”) with amendments dated November 18, 2016 No. 182, December 10, 2016 No. 195, February 14, 2017 No. 25, May 30, 2017 No. 93, March 29, 2018 No. 32, January 11, 2019 No. 4, June 26, 2019 No. 76, provided that such arrangements continue to meet requirements of the paragraph 5.4 of the Procurement Regulations and the following conditions: • The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; • Bidding documents, including contract forms, acceptable to the Bank shall be used. Bidding documents shall include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social, health and safety (“ESHS”) risks and impacts. • The Bidding process shall not be cancelled solely on the reason that minimum bid price is larger than the amount allocated by procuring entity for the procurement. • There shall be no preference applied during procurement of goods and works. • Implementing agency shall have an option to publish procurement notice without disclosing cost estimate. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Other national procurement arrangements such as “Simplified Method” (Request for Quotation) may be applied on the same conditions stated above for procuring limited quantities of readily available off-the-shelf goods or simple civil works of small value. In addition, not less than three quotations shall be requested to ensure competition. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable. PROCUREMENT Kyrgyz Republic : Tax Administration and Statistical System Modernization Project PLAN General Information Country: Kyrgyz Republic 2021-01-10 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163711 GPN Date: 2020-12-04 Project Name: Tax Administration and Statistical System Modernization Project Loan / Credit No: IDA / 65460, IDA / D5660 National Statistical Committee of the Kyrgyz Republic Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TASSMP/G/RFQ/C5-1 / Accou Component 5. Project Man Request for Quota Single Stage - One E IDA / 65460 Post Open - National 7,441.07 Completed 2020-10-06 2020-12-01 2021-02-10 2021-05-30 2021-05-11 nting Software (1C) agement tions nvelope TASSMP/G/RFB/C4-2-1 / Prim Component 4. NSC Data Dev Open - Internationa Single Stage - One E Pending Impl ary Modular Data Center, LA IDA / 65460 Post Request for Bids 0.00 2021-01-01 2021-01-29 2021-03-30 2021-04-29 2021-06-03 2022-12-03 elopment l nvelope ementation N and Call Center Equipment TASSMP/G/RFB/C3-2-2 / Elect Component 3. NSC Institut Single Stage - One E Pending Impl IDA / 65460 Post Request for Bids Open - National 0.00 2022-04-15 2022-05-13 2022-06-24 2022-07-24 2022-08-28 2024-02-27 ronic Archiving ional Development nvelope ementation TASSMP/G/RFB/C4-2-2 / Seco ndary and Backup Data Cent er Equipment, Data and Net Component 4. NSC Data Dev Open - Internationa Single Stage - One E Pending Impl IDA / D5660 Prior Request for Bids 0.00 2023-01-01 2023-01-29 2023-03-12 2023-04-11 2023-05-16 2024-11-14 work Security Software, Vide elopment l nvelope ementation o Surveilance Equipment, Da ta Warehouse Software; Oper ations and Maintenance TASSMP/G/RFB/C4-2-3 / Wor kstations, Laptops, Office sof tware and related computer Component 4. NSC Data Dev Open - Internationa Single Stage - One E Under Imple Equipment for NSC at the Ce IDA / 65460 Prior Request for Bids 0.00 2024-03-01 2023-02-09 2024-03-29 2023-02-14 2024-05-10 2023-03-29 2024-06-09 2024-07-07 2024-12-04 elopment l nvelope mentation ntral, Regional and Rayon lev els; Hyperconverged Server Solution for Primary Data Ce nter; and Data Analysis Softw are Packages TASSMP/G/RFQ/C5-2 / Furnit Component 5. Project Man Request for Quota Single Stage - One E ure, Office and Computer Eq IDA / D5660 Post Open - National 19,528.72 Completed 2021-02-16 2021-03-09 2021-04-13 2021-03-18 2021-05-11 agement tions nvelope uipment for PMU TASSMP/G/RFB/C4-2-4 / Dist ance Learning system incl. cl assroom equipment for NSC I Component 4. NSC Data Dev Open - Internationa Single Stage - One E IDA / 65460 Post Request for Bids 0.00 Signed 2022-09-22 2022-09-27 2022-09-29 2022-09-27 2022-10-29 2022-10-28 2022-11-12 2022-11-18 2022-11-29 2023-06-27 nstitute, Office Equipment for elopment l nvelope NSC staff at the local level (f urniture for improvement of working conditions) TASSMP/G/RFQ/C4-2-5 / Proc Component 3. NSC Institut Request for Quota Single Stage - One E Under Imple IDA / 65460 Post Open - National 0.00 2023-05-26 2023-06-21 2023-06-26 2023-08-25 urement of air conditioners f ional Development tions nvelope mentation or NSC KR NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TASSMP/CS/QCBS/C3-C4/2 / Firm to prepare the detailed Component 3. NSC Institut Quality And Cost- Open - Internationa Under Implement IDA / D5660 Prior 0.00 2020-11-06 2021-12-24 2021-05-06 2022-01-26 2021-06-19 2022-08-05 2021-07-24 2022-09-09 2021-08-14 2022-12-23 2021-09-04 2023-02-08 2021-10-09 2026-02-03 design of and development o ional Development Based Selection l ation f tender documentation for s oftware and hardware TASSMP/CS/QCBS/C3-C4/3 / Software for administrative d Component 3. NSC Institut Quality And Cost- Open - Internationa Pending Impleme ata exchange and collection, IDA / D5660 Prior 0.00 2022-05-02 2022-06-01 2022-07-15 2022-08-19 2022-09-08 2022-10-06 2022-10-20 2024-04-20 ional Development Based Selection l ntation Statistical Data Quality Mana gement and Improvement of Municipal Statistics TASSMP/CS/LCS/C5/1 / Proje Component 5. Project Man Least Cost Selecti Open - Internationa IDA / D5660 Post 53,000.00 Signed 2021-08-10 2021-10-29 2021-09-01 2021-11-01 2021-10-15 2021-12-01 2021-11-05 2021-12-29 2021-11-25 2022-01-24 2021-12-16 2022-03-01 2022-01-13 2022-03-23 2026-01-12 ct Audit agement on l TASSMP/CS/QCBS/C3-C4/1 / Component 3. NSC Institut Quality And Cost- Open - Internationa IDA / D5660 Prior 0.00 Signed 2021-02-16 2021-10-05 2021-03-11 2021-10-12 2021-05-08 2022-02-15 2021-05-28 2022-04-12 2021-06-25 2022-08-19 2021-07-30 2022-10-19 2021-08-20 2024-09-05 Twinning Partnership ional Development Based Selection l TASSMP/CS/CQS/C3-C4/3-3 / Component 3. NSC Institut Consultant Qualifi Pending Impleme Improvement and Developm IDA / D5660 Post Open - National 0.00 2022-10-17 2022-11-07 2022-12-21 2023-01-20 2023-02-24 2023-10-12 ional Development cation Selection ntation ent of HR Management INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TASSMP/CS/IC/C3-C4/3-2 / Lo Component 3. NSC Institut Individual Consult IDA / D5660 Post Open 16,115.70 Terminated 2021-02-16 2021-05-07 2021-04-06 2021-06-14 2021-04-22 2021-07-30 2021-05-11 2021-08-27 2024-12-22 cal IT Coordinator ional Development ant Selection Page 1 TASSMP/CS/IC/C3-C4/3-1 / Lo Component 3. NSC Institut Individual Consult IDA / D5660 Post Open 8,793.16 Completed 2021-02-16 2021-05-07 2021-03-25 2021-06-14 2021-04-08 2021-08-09 2021-04-29 2021-08-27 2024-12-10 2022-06-04 cal lawyer ional Development ant Selection TASSMP/CS/IC/C3-C4/3-2/1 / Component 3. NSC Institut Individual Consult IDA / D5660 Post Open 7,497.12 Signed 2022-01-04 2022-02-14 2022-01-24 2022-03-25 2022-01-31 2022-03-31 2022-02-13 2022-04-19 2022-12-15 Local IT Coordinator ional Development ant Selection TASSMP/CS/IC/C3-C4/3-4 / sp Component 3. NSC Institut Individual Consult ecialist in the development o IDA / 65460 Post Open - National 3,492.96 Signed 2022-08-16 2022-08-17 2022-09-07 2022-09-16 2022-09-14 2022-09-16 2022-09-27 2022-10-06 2022-12-26 ional Development ant Selection f an online course TASSMP/CS/IC/C3-C4/3-1/1 / Component 3. NSC Institut Individual Consult IDA / D5660 Post Open - National 0.00 Signed 2022-09-22 2022-09-27 2022-10-15 2022-11-18 2022-10-22 2022-11-18 2022-11-08 2023-09-04 Local lawyer ional Development ant Selection TASSMP/CS/IC/C3-C4/3-5 / IC Component 3. NSC Institut Individual Consult IDA / D5660 Post Limited 0.00 Signed 2023-02-17 2023-02-16 2023-02-24 2023-02-22 2023-02-28 2023-02-22 2023-03-05 2023-06-05 T Consultant ional Development ant Selection Page 2 Procurement Plan Sustainable Rural Water Supply and Sanitation Project PROCUREMENT Kyrgyz Republic : Sustainable Rural Water Supply and Sanitation Project PLAN General Information Country: Kyrgyz Republic 2017-02-08 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P154778 GPN Date: Project Name: Sustainable Rural Water Supply and Sanitation Project Loan / Credit No: IDA / D1380, IDA / 59070, IDA / D2040, TF / A1605, IDA / 60880 Community Development and Investment Agency Executing Agency(ies): WORKS Activity Reference No. Procurem Actual A Bid Evaluation Repo Loan / Credit Market Approa Procurement Pr Prequalificatio High SEA/SH Process Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Contract Compl / Description Component Review Type Method ent Docu mount ( rt and Recommenda Signed Contract No. ch ocess n (Y/N) Risk Status n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes etion ment Typ US$) tion for Award e Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planne Actua d l IDA-SRWSSDP-CW-17-1 / Single Stage - On 414,322.0 Complete 2016-12-3 2017-01-0 2017-02-1 2017-04-1 2017-04-2 2017-05-1 2017-06-0 2017-11- 2019- Rehabilitation of water sup IDA / 59070 Water Supply Investments Prior Request for Bids Open - National e Envelope 1 d 0 4 5 1 7 6 5 12 08-30 ply system in Togotoi IDA-SRWSSDP-CW-2017-2 Single Stage - On 3,484,396 Complete 2017-05-1 2017-05-0 2017-05-2 2017-07-0 2017-06-0 2017-08-0 2017-07-2 2017-09-0 2017-08-2 2018-03- 2019- / Rehabilitation of water su IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope .44 d 6 5 1 2 5 1 0 5 9 04 05-31 pply system in Kyrgyz-Ata (5 lots) IDA-SRWSSDP-CW-2017-3 Single Stage - On 2,300,631 Complete 2017-05-1 2017-04-2 2017-05-2 2017-07-0 2017-05-2 2017-08-0 2017-07-2 2017-09-0 2017-08-2 2018-03- 2020- / Rehabilitation of water su IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope .35 d 6 8 1 2 9 1 0 5 9 04 06-30 pply system in Sultan (3lo ts) IDA-SRWSSDP-CW-2017-4 Single Stage - On 2,476,062 Complete 2017-05-1 2017-05-0 2017-05-2 2017-07-0 2017-06-0 2017-08-0 2017-07-2 2017-09-0 2017-08-2 2018-03- 2019- / Rehabilitation of water su IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope .26 d 6 5 1 2 5 1 1 5 9 04 05-31 pply system in Panfilovka (3 lots) IDA-SRWSSDP-CW-2017-6 Single Stage - On 1,582,371 Complete 2017-12-0 2018-02-0 2017-12-0 2018-01-1 2018-03-1 2018-02-1 2018-04-2 2018-03-2 2018-05-2 2018-09- 2020- / Rehabilitation of water su IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope .95 d 1 9 6 7 3 6 0 3 8 19 06-30 pply system in Alekseevk a IDA-SRWSSDP-CW-2018-7 Single Stage - On 943,824.6 Complete 2018-01-2 2018-05-0 2018-02-0 2018-03-1 2018-06-1 2018-04-1 2018-07-1 2018-05-2 2018-08-2 2018-11- 2019- / Rehabilitation of water su IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope 7 d 9 4 3 7 9 6 1 1 7 17 10-28 pply system in Kyzyl-Tuu IDA-SRWSSDP-CW-2018-8 Single Stage - On 1,311,126 Complete 2018-01-2 2018-05-0 2018-02-0 2018-03-1 2018-06-0 2018-04-1 2018-07-1 2018-05-2 2018-08-2 2018-11- 2021- / Rehabilitation of water su IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope .88 d 9 4 3 7 7 6 1 1 7 17 06-03 pply system in Kun-Tuu IDA-SRWSSDP-CW-2018-9 Single Stage - On 480,923.0 Terminate 2018-07-0 2018-09-0 2018-07-0 2018-08-1 2018-10-1 2018-09-1 2019-01-2 2018-10-2 2019-03-0 2019-04- / Rehabilitation of water su IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope 8 d 1 7 6 7 8 6 5 1 1 19 pply system in Darkan IDA-SRWSSDP-CW-2018-1 Single Stage - On 509,569.5 Complete 2018-07-0 2018-09-0 2018-07-0 2018-08-1 2018-10-1 2018-09-1 2019-01-2 2018-10-2 2019-03-0 2019-04- 2019- 0 / Rehabilitation of water IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope 0 d 1 3 6 7 8 6 5 1 1 19 12-11 supply system in Chelpek IDA-SRWSSDP-CW-2018-1 Single Stage - On 403,830.4 Complete 2018-08-2 2019-07-2 2018-09-0 2018-10-1 2019-09-0 2018-11-1 2019-10-1 2018-12-1 2019-11-2 2019-06- 2021- 1 / Rehabilitation of water IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope 2 d 9 6 3 5 4 4 5 9 2 17 08-31 supply system in Sary-Tas h IDA-SRWSSDP-CW-2018-1 Single Stage - On 527,664.6 Complete 2018-08-2 2019-07-2 2018-09-0 2018-10-1 2019-09-0 2018-11-1 2019-10-1 2018-12-1 2019-11-2 2019-06- 2021- 2 / Rehabilitation of water IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope 0 d 9 6 3 5 4 4 5 9 0 17 09-30 supply system in Achyk-S uu IDA-SRWSSDP-CW-2018-1 Under Imp Single Stage - On 2018-08-2 2018-09-0 2018-10-1 2018-11-1 2018-12-1 2019-06- 3 / Rehabilitation of water IDA / 59070 Water Supply Investments Post Request for Bids Open - National 0.00 lementati e Envelope 9 3 5 4 9 17 supply system in Gulbar on IDA-SRWSSDP-CW-2018-1 Pending I Single Stage - On 2018-08-2 2018-09-0 2018-10-1 2018-11-1 2018-12-1 2019-06- 4 / Rehabilitation of water IDA / D2040 Water Supply Investments Post Request for Bids Open - National 0.00 mplement e Envelope 9 3 5 4 9 17 supply system in Otuz Ady ation r IDA-SRWSSDP-CW-2018-1 Single Stage - On 368,970.7 Complete 2018-03-0 2018-02-0 2018-03-0 2018-04-1 2018-03-1 2018-05-1 2018-04-2 2018-06-2 2018-05-2 2018-12- 2019- 6 / Rehabilitation of water IDA / D2040 Water Supply Investments Post Request for Bids Open - National e Envelope 3 d 2 7 7 8 3 8 0 2 8 19 07-31 supply system in Tolok SRWSSDP-SHOPPING-WO Institutional Strengthenin Request for Quo Single Stage - On Complete 2018-04-3 2018-06-2 2018-04-2 2018-12- 2018- IDA / D1380 Post Open - National 2,807.86 RKS-2018-1 / Renovation g tations e Envelope d 0 5 7 22 06-22 work for DWWSD IDA-SRWSSDP-SW-2018-1 / Rehabiltation of public co Request for Quo Single Stage - On 104,536.8 Complete 2018-06-1 2018-06-2 2018-08-1 2018-09-1 2019-02- 2019- IDA / 59070 Sanitation Development Post Limited nveniences in schools (int tations e Envelope 0 d 5 9 0 3 06 06-28 ernal toilets) in Osh oblast IDA-SRWSSDP-SW-2018-2 / Rehabiltation of public co Request for Quo Single Stage - On Complete 2018-06-1 2018-11-2 2018-08-1 2019-02-1 2019-02- 2019- IDA / D1380 Sanitation Development Post Limited 66,563.69 nveniences in schools of C tations e Envelope d 5 0 0 6 06 09-16 huy oblast (inner toilets) IDA-SRWSSDP-AF-CW-201 Single Stage - On 481,348.4 Complete 2018-09-0 2019-08-2 2018-09-1 2018-10-2 2019-09-2 2018-11-2 2019-10-2 2018-12-3 2019-11-2 2019-12- 2021- 8-15 / Rehabilitation of wa IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope 1 d 6 3 4 6 5 5 9 0 9 30 05-10 ter supply system in Tamg a IDA-SRWSSDP-AF-CW-19- Single Stage - On 990,872.0 Complete 2019-02-1 2019-02-1 2019-02-2 2019-04-0 2019-03-1 2019-05-0 2019-05-1 2019-06-0 2019-07-0 2019-12- 2021- 18 / Rehabilitation of wate IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope 0 d 5 5 0 3 9 3 4 7 3 04 08-31 r supply system in Korul (2 Lots) IDA-SRWSSDP-AF-CW-18- Single Stage - On 481,621.3 2019-06-0 2019-07-2 2019-06-1 2019-07-1 2019-09-0 2019-08-1 2019-10-1 2019-09-2 2019-11-2 2020-09- 18 / Rehabilitation of wate IDA / 59070 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 7 3 6 7 7 4 6 5 0 9 19 r supply system in Ak-Bula k IDA-SRWSSDP-AF-CW-201 Single Stage - On 2018-09-1 2019-02-1 2018-09-2 2018-11-0 2019-03-1 2018-12-0 2019-01-0 2020-01- 8-17 / Rehabilitation of wa IDA / 59070 Water Supply Investments Post Request for Bids Open - National 0.00 Canceled e Envelope 1 5 1 2 9 2 6 06 ter supply system in Ichke- Bulun IDA-SRWSSDP-AF-CW-202 Single Stage - On 232,976.3 2020-01-2 2020-01-3 2020-02-0 2020-03-1 2020-03-0 2020-04-1 2020-05-0 2020-05-2 2020-05-3 2021-05- 0-19 / Rehabilitation of wa IDA / 59070 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 8 7 0 3 6 3 5 7 0 0 20 ter supply system in Belek IDA-SRWSSDP-AF-CW-202 Single Stage - On 298,422.6 Complete 2020-01-2 2020-01-3 2020-02-0 2020-03-1 2020-03-0 2020-04-1 2020-05-0 2020-05-2 2020-05-3 2021-05- 2021- 0-20 / Rehabilitation of wa IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope 6 d 7 0 3 6 3 5 7 0 0 20 10-26 ter supply system in Shalt a IDA-SRWSSDP-SW-2018-4 Request for Quo Single Stage - On Complete 2018-06-1 2018-12-1 2018-08-1 2019-02-1 2019-02- 2019- / Rehabilitation SES of Tok IDA / D1380 Sanitation Development Post Limited 2,226.08 tations e Envelope d 5 1 0 6 06 03-18 mok rayon Chui oblast IDA-SRWSSDP-SW-2018-3 Request for Quo Single Stage - On Complete 2018-06-1 2018-11-2 2018-08-1 2019-01-3 2019-02- 2019- / Rehabilitation SES of Ala IDA / D1380 Sanitation Development Post Limited 1,296.78 tations e Envelope d 5 0 0 1 06 03-04 y rayon Osh oblast IDA-SRWSSDP-SW-2018-5 Request for Quo Single Stage - On Complete 2018-06-0 2019-07-1 2018-08-0 2019-09-1 2019-01- 2019- / Rehabilitation SES of Ak- IDA / D1380 Sanitation Development Post Limited 1,492.53 tations e Envelope d 8 2 3 3 30 10-12 Suu rayon Issyk-Kul oblast IDA-SRWSSDP-SW-2018-6 Request for Quo Single Stage - On Complete 2018-06-0 2018-11-2 2018-08-0 2019-02-0 2019-01- 2019- / Rehabilitation SES of Jeti- IDA / D1380 Sanitation Development Post Limited 1,902.71 tations e Envelope d 8 0 3 1 30 03-04 Oguz rayon Issyk-Kul oblas t IDA-SRWSSDP-SW-2018-7 Request for Quo Single Stage - On Complete 2018-06-0 2018-11-2 2018-08-0 2019-01-3 2019-01- 2019- / Rehabilitation SES of Sok IDA / D1380 Sanitation Development Post Limited 2,799.35 tations e Envelope d 8 0 3 1 30 02-28 uluk rayon Chui oblast IDA-SRWSSDP-SW-2018-1 Request for Quo Single Stage - On Complete 2018-06-0 2018-12-1 2018-08-0 2019-02-1 2019-01- 2019- 0 / Rehabilitation SES of P IDA / D1380 Sanitation Development Post Limited 2,172.64 tations e Envelope d 8 1 3 6 30 03-18 anfilov rayon Chui oblast IDA-SRWSSDP-SW-2018-8 Request for Quo Single Stage - On Complete 2018-06-0 2018-12-1 2018-08-0 2019-02-1 2019-01- 2019- / Rehabilitation SES of Mos IDA / D1380 Sanitation Development Post Limited 2,044.16 tations e Envelope d 8 1 3 6 30 03-18 kva rayon Chui oblast IDA-SRWSSDP-SW-2018-9 Request for Quo Single Stage - On Complete 2018-06-0 2018-12-1 2018-08-0 2019-02-1 2019-01- 2019- / Rehabilitation SES of Jayil IDA / D1380 Sanitation Development Post Limited 2,757.38 tations e Envelope d 8 1 3 6 30 03-18 rayon Chui oblast IDA-SRWSSDP-SW-2019-1 Request for Quo Single Stage - On Complete 2019-05-0 2019-05-2 2019-07-0 2019-08-3 2019-12- 2020- / Rehabiltation of public co IDA / D1380 Sanitation Development Post Limited 92,102.52 tations e Envelope d 8 9 3 0 30 07-01 nveniences in schools in C hui oblast (2nd phase) IDA-SRWSSDP-SW-2019-2 / Rehabiltation of public co Request for Quo Single Stage - On Complete 2019-05-0 2019-05-2 2019-07-0 2019-08-2 2019-12- 2019- IDA / D1380 Sanitation Development Post Limited 48,414.87 nveniences in schools in Is tations e Envelope d 8 9 3 7 30 12-26 syk-Kul oblast (2nd phase) IDA-SRWSSDP-AF-CW-202 Single Stage - On 190,853.9 2020-02-1 2020-02-2 2020-02-2 2020-04-0 2020-05-1 2020-05-0 2020-06-0 2020-06-0 2020-07-1 2021-06- 0-21 / Rehabilitation of wa IDA / 59070 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 9 8 0 3 5 2 5 4 9 6 09 ter supply system in Chon -Daly IDA-SRWSSDP-DC-CW-20- 1 / Extra works for rehabili 2020-03-1 2020-03-2 2020-03-2 2020-03-2 2020-05-0 2020-05-0 2020-09- IDA / 59070 Water Supply Investments Post Direct Selection Direct 80,908.48 Signed tation of water supply syst 8 5 3 6 2 7 01 em in Kyrgyz-Ata subproje ct IDA-SRWSSDP-DC-CW-20- 2 / Direct contract fo comp 414,547.4 Complete 2020-04-1 2020-04-2 2020-04-1 2020-04-2 2020-05-1 2020-05-3 2020-11- 2020- IDA / 59070 Water Supply Investments Post Direct Selection Direct letion of works in subproje 6 d 0 8 7 9 8 0 14 12-01 ct Darkhan, Jeti-Oguz, Issy k-Kul IDA-SRWSSDP-AF-CW-202 Single Stage - On 453,181.9 Complete 2020-04-3 2020-04-2 2020-05-0 2020-06-1 2020-06-0 2020-07-1 2020-06-2 2020-08-1 2020-07-1 2021-11- 2021- 0-22 / Rehabilitation of wa IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope 7 d 0 9 1 2 2 2 9 6 6 19 10-15 ter supply system in Chaic hy IDA-SRWSSDP-AF-CW-202 Single Stage - On 501,808.1 2020-06-1 2020-06-0 2020-06-1 2020-07-3 2020-07-0 2020-08-3 2020-08-2 2020-10-0 2020-09-2 2021-10- 0-23 / Rehabilitation of wa IDA / 59070 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 4 2 4 9 1 7 0 6 4 5 04 ter supply system in Kene sh IDA-SRWSSDP-AF-CW-202 Single Stage - On 201,497.9 2020-06-1 2020-06-0 2020-06-1 2020-07-2 2020-07-0 2020-08-2 2020-08-1 2020-10-0 2020-09-0 2021-05- 0-24 / Rehabilitation of wa IDA / 59070 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 5 0 9 7 9 8 8 4 2 9 30 ter supply system in Kara- dobo IDA-SRWSSDP-AF-CW-202 Single Stage - On 326,383.1 Complete 2020-07-0 2020-07-0 2020-07-1 2020-08-2 2020-08-0 2020-09-2 2020-09-0 2020-10-3 2020-10-0 2022-02- 2022- 0-25 / Rehabilitation of wa IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope 1 d 1 2 5 6 4 5 8 0 7 02 01-06 ter supply system in Kene sh Osh oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 238,324.8 Complete 2020-07-0 2020-07-0 2020-07-1 2020-08-2 2020-08-0 2020-09-2 2020-09-0 2020-10-3 2020-10-0 2022-02- 2022- 0-26 / Rehabilitation of wa IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope 6 d 1 2 5 6 4 5 8 0 7 02 01-06 ter supply system in Por IDA-SRWSSDP-AF-CW-202 Single Stage - On 497,949.8 2020-11-1 2020-08-1 2020-11-2 2021-01-0 2020-09-1 2021-02-0 2020-09-2 2021-03-1 2020-10-2 2022-06- 0-29 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 2 1 4 5 6 1 5 2 2 1 15 ter supply system in Gorn aya Maevka IDA-SRWSSDP-AF-CW-202 Single Stage - On 347,104.8 2020-11-1 2020-10-1 2020-11-2 2021-01-0 2020-11-1 2021-02-0 2020-12-1 2021-03-1 2021-01-2 2022-06- 0-30 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 2 1 5 5 6 7 5 8 2 8 15 ter supply system in Beish eke IDA-SRWSSDP-AF-CW-202 Single Stage - On 666,380.9 2020-11-2 2020-11-1 2020-12-0 2021-01-1 2020-12-1 2021-02-1 2021-01-2 2021-03-2 2021-03-0 2022-06- 0-31 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 7 0 2 4 5 5 4 2 1 6 24 ter supply system in Ken- Bulun IDA-SRWSSDP-AF-CW-18- Single Stage - On 365,328.7 Complete 2019-07-1 2019-07-1 2019-07-2 2019-09-0 2019-08-0 2019-10-0 2019-09-0 2019-11-1 2019-09-0 2020-11- 2020- 17 / Rehabilitation of wate IDA / 59070 Water Supply Investments Post Request for Bids Open - National e Envelope 2 d 9 2 8 8 9 8 2 2 7 11 09-16 r supply system in Ichke-B ulun IDA-SRWSSDP-SW-2020-1 1 / Rehabiltation of public Request for Quo Single Stage - On 129,549.4 2020-05-2 2020-07-1 2020-09-3 2021-01- IDA / 60880 Sanitation Development Post Open - National Signed conveniences in schools in tations e Envelope 6 0 5 0 11 Chui oblast (1st phase) IDA-SRWSSDP-SW-2020-9 / Rehabiltation of public co Request for Quo Single Stage - On 2020-05-2 2020-07-1 2020-09-2 2021-01- IDA / 60880 Sanitation Development Post Open - National 45,124.23 Signed nveniences in schools in Is tations e Envelope 0 5 9 11 syk-Kul oblast (1st phase) IDA-SRWSSDP-SW-2020-1 Request for Quo Single Stage - On 2020-05-2 2020-07-1 2020-10-0 2021-01- 0 / Rehabiltation of public IDA / 60880 Sanitation Development Post Open - National 31,496.41 Signed tations e Envelope 0 5 1 11 conveniences in schools in Osh oblast (1st phase) Page 1 IDA-SRWSSDP-SW-2020-2 Request for Quo Single Stage - On 2020-06-1 2020-08-1 2020-10-0 2021-02- / Rehabilitation SES of Issy IDA / 60880 Sanitation Development Post Open - National 1,598.85 Signed tations e Envelope 7 2 1 08 k-Ata rayon Chui oblast IDA-SRWSSDP-SW-2020-3 Request for Quo Single Stage - On 2020-06-1 2020-08-1 2020-10-0 2021-02- / Rehabilitation SES of Cho IDA / 60880 Sanitation Development Post Open - National 856.84 Signed tations e Envelope 7 2 1 08 n-Alai rayon Osh oblast IDA-SRWSSDP-SW-2020-4 Request for Quo Single Stage - On 2020-09-0 2020-11-0 2020-11-1 2021-05- / Rehabilitation SES of Ton IDA / 60880 Sanitation Development Post Open - National 2,157.80 Signed tations e Envelope 9 4 7 03 rayon Issyk-Kul oblast IDA-SRWSSDP-SW-2020-5 Request for Quo Single Stage - On 2020-09-0 2020-11-0 2020-11-1 2021-05- / Rehabilitation SES of Ke IDA / 60880 Sanitation Development Post Open - National 2,633.52 Signed tations e Envelope 9 4 7 03 min rayon Chui oblast IDA-SRWSSDP-SW-2020-6 Under Imp Request for Quo Single Stage - On 2020-06-1 2020-08-1 2021-02- / Rehabilitation SES of Kar IDA / 60880 Sanitation Development Post Open - National 0.00 lementati tations e Envelope 7 2 08 a-Suu rayon Osh oblast on IDA-SRWSSDP-SW-2020-1 Request for Quo Single Stage - On 2020-09-0 2020-11-0 2020-11-1 2021-05- / Rehabilitation SES of Issy IDA / 60880 Sanitation Development Post Open - National 2,408.66 Signed tations e Envelope 9 4 7 03 k-Kul rayon Issyk-Ku oblast IDA-SRWSSDP-SW-2020-7 Request for Quo Single Stage - On 2020-06-1 2020-08-1 2020-10-0 2021-02- / Rehabilitation SES of Ara IDA / 60880 Sanitation Development Post Open - National 1,898.71 Signed tations e Envelope 7 2 1 08 van rayon Osh oblast IDA-SRWSSDP-SW-2020-8 Request for Quo Single Stage - On 2020-09-0 2020-11-0 2020-11-1 2021-05- / Rehabilitation SES of Ala IDA / 60880 Sanitation Development Post Open - National 1,939.93 Signed tations e Envelope 9 4 7 03 mudun rayon Chui oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 711,498.4 2021-01-0 2021-01-0 2021-01-0 2021-02-1 2021-02-0 2021-03-1 2021-05-2 2021-04-2 2021-07-0 2022-04- 1-1 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 1 1 7 6 7 9 9 1 3 1 23 er supply system in Kara-J igach Chui oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 2022-01-1 2022-12-0 2022-01-2 2022-12-0 2022-03-0 2022-12-3 2022-04-0 2023-03-2 2022-05-0 2023-05- 2-1 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 Signed e Envelope 5 2 0 2 3 0 2 4 7 07 er supply system in Kayr ma Chui oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 2022-01-1 2022-08-2 2022-01-2 2022-08-2 2022-03-0 2022-09-2 2022-04-0 2022-11-1 2022-05-0 2023-05- 2-2 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 Signed e Envelope 5 5 0 5 3 3 2 1 7 07 er supply system in Vasile v Chui oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 2021-09-0 2022-08-2 2021-09-0 2022-08-2 2021-10-1 2022-09-2 2021-11-1 2022-11-1 2021-12-2 2022-12- 1-2 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 Signed e Envelope 1 5 6 5 8 3 7 1 2 22 er supply system in Komso molskoe Chui oblast IDA-SRWSSDP-AF-CW-202 Pending I Single Stage - On 2021-09-0 2021-09-0 2021-10-1 2021-11-1 2021-12-2 2022-12- 1-3 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 mplement e Envelope 1 6 8 7 2 22 er supply system in Bokso ation -Jol Chui oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 1,630,213 2021-09-0 2021-11-0 2021-09-0 2021-11-0 2021-10-1 2021-12-0 2021-11-1 2022-01-2 2021-12-2 2022-02-2 2022-12- 1-4 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National Signed e Envelope .88 1 5 6 5 8 7 7 7 2 7 22 er supply system in Sosno vka Chui oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 778,341.9 2021-01-0 2021-02-0 2021-01-0 2021-02-0 2021-02-1 2021-03-1 2021-03-1 2021-05-3 2021-04-2 2021-07-1 2022-04- 1-5 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 5 1 4 6 4 7 0 9 1 3 0 23 er supply system in Ivano vka station Chui oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 2022-01-1 2022-12-2 2022-01-2 2022-12-2 2022-03-0 2023-01-2 2022-04-0 2023-03-2 2022-05-0 2023-05- 2-3 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 Signed e Envelope 5 3 0 6 3 4 2 4 7 07 er supply system in Kurpu ldok Chui oblast IDA-SRWSSDP-AF-CW-202 Pending I Single Stage - On 2022-01-1 2022-01-2 2022-03-0 2022-04-0 2022-05-0 2023-05- 2-4 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 mplement e Envelope 5 0 3 2 7 07 er supply system in Kum- ation Aryk Chui oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 2022-01-1 2022-12-0 2022-01-2 2022-03-0 2023-01-1 2022-04-0 2023-03-2 2022-05-0 2023-05- 2-5 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 Signed e Envelope 5 9 0 3 0 2 8 7 07 er supply system in Orto- Aryk Chui oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 397,761.3 2021-09-0 2021-09-2 2021-09-0 2021-09-2 2021-10-1 2021-10-2 2021-11-1 2021-12-0 2021-12-2 2021-12-1 2022-12- 1-6 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 5 1 4 6 4 8 6 7 2 2 1 22 er supply system in Kaind y Chui oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 467,510.5 2021-09-0 2021-05-1 2021-09-0 2021-05-1 2021-10-1 2021-06-0 2021-11-1 2021-07-0 2021-12-2 2021-08-0 2022-12- 1-7 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 3 1 1 6 1 8 9 7 2 2 8 22 er supply system in Borol doi Chui oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 2021-09-0 2022-06-0 2021-09-0 2022-06-2 2021-10-1 2022-07-1 2021-11-1 2022-08-1 2021-12-2 2022-12- 1-8 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 Signed e Envelope 1 3 6 8 8 3 7 9 2 22 er supply system in Bulolu u Osh oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 2021-09-0 2022-10-2 2021-09-0 2022-10-2 2021-10-1 2022-11-2 2021-11-1 2023-03-0 2021-12-2 2022-12- 1-9 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 Signed e Envelope 1 8 6 8 8 9 7 2 2 22 er supply system in Toloik on Osh oblast IDA-SRWSSDP-AF-CW-202 Under Imp Single Stage - On 2021-09-0 2022-06-0 2021-09-0 2022-06-0 2021-10-1 2022-07-0 2021-11-1 2022-08-1 2021-12-2 2022-12- 1-10 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 lementati e Envelope 1 3 6 3 8 5 7 9 2 22 ter supply system in Erkin on -Too Osh oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 2021-09-0 2022-12-2 2021-09-0 2022-12-2 2021-10-1 2023-01-2 2021-11-1 2023-03-0 2021-12-2 2022-12- 1-11 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 Signed e Envelope 1 3 6 6 8 4 7 2 2 22 ter supply system in Kyzyl -Bairak Osh oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 2021-09-0 2022-01-2 2021-09-0 2022-01-2 2021-10-1 2022-02-2 2021-11-1 2022-04-1 2021-12-2 2022-12- 1-12 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 Signed e Envelope 1 5 6 5 8 2 7 4 2 22 ter supply system in Kaby k Osh oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 2021-09-0 2022-06-1 2021-09-0 2022-06-1 2021-10-1 2022-07-1 2021-11-1 2022-09-0 2021-12-2 2022-12- 1-13 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 Signed e Envelope 1 0 6 0 8 2 7 2 2 22 ter supply system in Enchi lesh Issyk-Kul oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 974,367.2 2021-06-0 2021-06-1 2021-06-0 2021-06-1 2021-07-1 2021-07-1 2021-08-1 2021-08-0 2021-09-2 2021-09-1 2022-09- 1-14 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 5 1 1 6 1 8 3 7 5 1 1 21 ter supply system in Jeti-O guz Issyk-Kul oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 267,037.1 2021-06-0 2021-03-0 2021-06-0 2021-03-0 2021-07-1 2021-04-0 2021-08-1 2021-04-2 2021-09-2 2021-05-1 2022-09- 1-15 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 0 1 2 6 2 8 1 7 0 1 9 21 ter supply system in Boz- Beshik Issyk-Kul oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 2021-09-0 2022-04-0 2021-09-0 2022-04-0 2021-10-1 2022-04-2 2021-11-1 2022-07-0 2021-12-2 2022-12- 1-16 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 Canceled e Envelope 1 1 6 1 8 9 7 5 2 22 ter supply system in Barb ulak Issyk-Kul oblast IDA-SRWSSDP-AF-CW-202 Pending I Single Stage - On 2021-09-0 2021-09-0 2021-10-1 2021-11-1 2021-12-2 2022-12- 1-17 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 mplement e Envelope 1 6 8 7 2 22 ter supply system in Kurm ation ontu Issyk-Kul oblast IDA-SRWSSDP-AF-CW-202 Pending I Single Stage - On 2021-09-0 2021-09-0 2021-10-1 2021-11-1 2021-12-2 2022-12- 1-18 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 mplement e Envelope 1 6 8 7 2 22 ter supply system in Kichi ation -Oruktuu Issyk-Kul oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 2021-09-0 2022-04-2 2021-09-0 2022-04-2 2021-10-1 2022-05-2 2021-11-1 2022-06-2 2021-12-2 2022-12- 1-19 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 Signed e Envelope 1 2 6 2 8 0 7 8 2 22 ter supply system in Jyluu -Bulak Issyk-Kul oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 2021-06-0 2022-11-1 2021-06-0 2022-11-1 2021-07-1 2022-12-1 2021-08-1 2023-03-3 2021-09-2 2022-09- 1-20 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 Signed e Envelope 1 1 6 1 8 3 7 1 1 21 ter supply system in Grigo revka Issyk-Kul oblast IDA-SRWSSDP-AF-CW-202 Pending I Single Stage - On 2021-06-0 2021-06-0 2021-07-1 2021-08-1 2021-09-2 2022-09- 1-21 / Rehabilitation of wa IDA / 60880 Water Supply Investments Post Request for Bids Open - National 0.00 mplement e Envelope 1 6 8 7 1 21 ter supply system in Karo ation ol-Dobo Issyk-Kul oblast IDA-SRWSSDP-AF-CW-202 Single Stage - On 204,124.6 2020-11-2 2020-11-2 2020-12-1 2021-01-2 2020-12-2 2021-02-2 2021-04-1 2021-03-2 2021-05-2 2022-07- 0-27-RT-1 / Rehabilitation IDA / 60880 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 8 7 6 1 2 9 1 6 8 0 01 of water supply system in Kyzyl-Jar IDA-SRWSSDP-AF-CW-202 Single Stage - On 373,946.3 2020-11-2 2020-11-2 2020-12-1 2021-01-2 2020-12-2 2021-02-2 2021-04-1 2021-03-2 2021-05-2 2022-07- 0-28-RT-1 / Rehabilitation IDA / 60880 Water Supply Investments Post Request for Bids Open - National Signed e Envelope 6 7 7 1 2 9 1 6 8 0 01 of water supply system in Koo-Chaty IDA-SRWSSDP-AF-CW-202 Single Stage - On 2020-08-1 2020-08-2 2020-08-3 2020-10-1 2020-09-2 2020-11-1 2020-12-1 2022-03- 0-27 / Rehabilitation of wa IDA / 59070 Water Supply Investments Post Request for Bids Open - National 0.00 Canceled e Envelope 7 0 1 2 2 1 6 21 ter supply system in Kyzyl -Jar IDA-SRWSSDP-AF-CW-202 Single Stage - On 2020-08-1 2020-08-2 2020-08-3 2020-10-1 2020-09-2 2020-11-1 2020-12-1 2022-03- 0-28 / Rehabilitation of wa IDA / 59070 Water Supply Investments Post Request for Bids Open - National 0.00 Canceled e Envelope 7 1 1 2 2 1 6 21 ter supply system in Koo- Chaty National Pr IDA-SRWSSDP-NCB-SW-20 ocurement 22-1 / Rehabiltation of out Document Pending I Single Stage - On 2022-08-1 2022-08-1 2022-09-1 2022-10-1 2022-11-1 2023-04- door public conveniences i IDA / D1380 Sanitation Development Post Request for Bids Open - National - 1 Envelop 0.00 mplement e Envelope 0 7 4 4 8 17 n schools in Chui, Issyk-Kul e process ( ation and Osh oblasts 1st phase Non Bank-S (3 lots) PD) National Pr IDA-SRWSSDP-AW-2022-1 ocurement Under Imp / Additional works for reha Single Stage - On Document 2022-08-1 2022-09-0 2022-08-1 2022-09-0 2022-09-3 2023-01-1 2022-10-3 2023-03-3 2022-12-0 2023-06- IDA / 59070 Water Supply Investments Post Request for Bids Open - National 0.00 lementati bilitation of water supply s e Envelope - 1 Envelop 7 2 9 2 0 0 0 1 4 02 on ystem in Sultan subproject e process ( Non Bank-S PD) National Pr IDA-SRWSSDP-AF-CW-202 ocurement 1-16-2 / Rehabilitation of Single Stage - On 2022-08-2 2022-09-0 2022-09-0 2022-09-0 2022-10-2 2022-09-3 2022-11-2 2022-11-2 2022-12-2 2024-03- IDA / 60880 Water Supply Investments Post Request for Bids Open - National Document 0.00 Signed water supply system in Ba e Envelope 8 2 9 2 1 0 0 1 5 24 - 1 Envelop rbulak Issyk-Kul oblast e process ( Non Bank-S Request for IDA-SRWSSDP-SW-2023-1 PD) Bids - Smal Pending I / Rehabiltation of public co Single Stage - On 2023-04-1 2023-04-1 2023-05-0 2023-06-0 2023-06-0 2023-10- IDA / D1380 Sanitation Development Post Request for Bids Open - National l Works SP 0.00 mplement nveniences in schools in O e Envelope 4 8 2 1 3 01 D (1 envelo ation sh oblast 2nd Phase (4 lot pe process) s) Request for IDA-SRWSSDP-AF-CW-202 Bids - Smal Pending I Single Stage - On 2023-05-0 2023-05-1 2023-06-2 2023-07-2 2023-08-2 2024-08- 3-1 / Rehabilitation of wat IDA / 60880 Water Supply Investments Post Request for Bids Open - National l Works SP 0.00 mplement e Envelope 5 0 1 1 5 24 er supply system in Kichi- D (1 envelo ation Buloluu pe process) Request for IDA-SRWSSDP-AF-SW-202 Pending I Request for Quo Single Stage - On Quotations 2023-06-1 2023-08-0 2023-11- 3-1 / Rehabiltation of publi IDA / D1380 Sanitation Development Post Open - National 0.00 mplement tations e Envelope (Non Bank- 4 7 05 c conveniences in schools ation SPD) in Chuy oblast (2 lots) IDA-SRWSSDP-AF-SW-202 Request for Pending I 3-2 / Rehabiltation of publi Request for Quo Single Stage - On Quotations 2023-06-1 2023-08-0 2023-11- IDA / D1380 Sanitation Development Post Open - National 0.00 mplement c conveniences in schools tations e Envelope (Non Bank- 4 7 05 ation in Osh oblast Kara-Suu ray SPD) on Kyzyl-Suu а/а Request for IDA-SRWSSDP-СW-2023-1 Bids - Smal Pending I -RT1 / Rehabiltation of pub Single Stage - On 2023-06-1 2023-06-2 2023-07-0 2023-08-0 2023-08-0 2023-12- IDA / D1380 Sanitation Development Post Request for Bids Open - National l Works SP 0.00 mplement lic conveniences in schools e Envelope 6 0 4 3 5 03 D (1 envelo ation in Osh oblast 2nd Phase ( pe process) 4 lots) GOODS Activity Reference No. Bid Evaluation Repo Loan / Credit Market Approa Procurement Pr Prequalificatio Actual Amoun Process S Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission / Description Component Review Type Method rt and Recommenda Signed Contract Contract Completion No. ch ocess n (Y/N) t (US$) tatus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes tion for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-SRWSSDP-GOODS-20 Institutional Strengthenin Request for Quo Single Stage - On 2017-01-2 2017-03-2 2017-03-1 2017-09-1 2017-05-1 IDA / D1380 Post Open - National 36,405.43 Completed 17-1 / Purchase of vehicle g tations e Envelope 3 0 0 6 0 for DWWSD IDA-SRWSSDP-GOODS-20 Request for Quo Single Stage - On 2017-02-0 2017-04-0 2017-03-2 2017-10-0 2017-04-2 17-2 / Supply of computer IDA / D1380 Project Management Post Open - National 27,439.86 Completed tations e Envelope 7 4 8 1 7 equipment for ARIS IDA-SRWSSDP-G-2018-11 Institutional Strengthenin Request for Quo Single Stage - On 2018-08-0 2018-09-2 2018-08-2 2019-03-2 2018-11-1 / Supply of computer equi IDA / D1380 Post Open - National 47,378.98 Completed g tations e Envelope 3 8 7 7 1 pment 13 for billing syste m IDA-SRWSSDP-G-2019-13 Institutional Strengthenin Request for Quo Single Stage - On 2019-07-0 2019-08-2 2019-01-2 2020-02-2 2019-03-1 / Purchase of goods for C IDA / 59070 Post Open - National 23,040.88 Completed g tations e Envelope 4 9 9 5 9 DWUUs for 13 sub-projects IDA-SRWSSDP-G-2019-14 Pending Im / Purchase of goods for 27 Institutional Strengthenin Request for Quo Single Stage - On 2019-07-0 2019-08-2 2020-02-2 IDA / 59070 Post Open - National 0.00 plementati CDWUUs on competion ba g tations e Envelope 4 9 5 on sis (multiple contracts) Page 2 IDA-SRWSSDP-G-2019-15 Institutional Strengthenin Single Stage - On 2019-05-0 2019-05-0 2019-06-1 2019-07-1 2019-08-2 2020-02-1 / Purchase of special mach IDA / 59070 Post Request for Bids Open - National 0.00 Canceled g e Envelope 1 6 7 7 1 7 inery for Ayil Okmotu IDA-SRWSSDP-GOODS-20 Institutional Strengthenin Request for Quo Single Stage - On 2018-04-3 2018-06-2 2018-04-2 2018-12-2 2018-05-3 18-6_1 / Purchase of auto IDA / D1380 Post Open - National 1,144.71 Completed g tations e Envelope 0 5 4 2 1 matic telephone system f or DWWSD IDA-SRWSSDP-GOODS-20 Request for Quo Single Stage - On 2018-07-0 2018-07-0 2018-09-0 2018-08-2 2019-03-0 2018-11-0 18-7 / Supply of Computer IDA / 59070 Sanitation Development Post Limited 39,021.28 Completed tations e Envelope 8 6 2 8 1 7 equipment for SES IDA-SRWSSDP-NCB-G-201 Single Stage - On 2018-09-0 2019-02-0 2018-09-1 2018-10-2 2019-02-2 2018-11-2 2019-03-2 2018-12-2 2019-06-2 2019-06-2 2019-07-2 8-9 / Purchase of waterme IDA / D2040 Water Supply Investments Post Request for Bids Open - National 185,827.43 Completed e Envelope 6 1 1 3 8 2 9 7 8 5 3 ters for Sultan, Kurama an d Kyrgyz-Ata. IDA-SRWSSDP-NCB-G-201 Single Stage - On 2018-08-3 2019-03-2 2018-09-0 2018-10-1 2019-04-1 2018-11-1 2019-08-2 2018-12-2 2019-11-2 2019-06-2 2020-02-2 8-6 / Supply of laboratory IDA / 59070 Sanitation Development Post Request for Bids Open - National 175,835.38 Completed e Envelope 1 2 7 9 9 8 1 3 9 1 9 equipment for rayon SES IDA-SRWSSDP-G-SIASAR-2 Institutional Strengthenin Request for Quo Single Stage - On 2019-02-1 2019-02-0 2019-04-1 2019-04-1 2019-10-0 2019-05-1 019-1 / Supply of comput TF / A1605 Post Limited 6,742.31 Completed g tations e Envelope 3 1 0 2 7 0 er equipment for SIASAR t eam IDA-SRWSSDP-G-2018-10 / Purchase of watermeters Institutional Strengthenin Request for Quo Single Stage - On 2018-07-2 2018-09-1 2019-03-1 IDA / 59070 Post Open - National 0.00 Canceled Sary-Tash, Achyk-Suu, Kun g tations e Envelope 0 4 3 -tuu, Alekseevka, Kyzyl-Tu u, Tolok IDA-SRWSSDP-GOODS-20 18-10 / Purchase of water Institutional Strengthenin Single Stage - On 2019-05-0 2019-05-1 2019-05-0 2019-06-1 2019-06-2 2019-07-1 2019-06-2 2019-08-2 2019-08-0 2020-02-1 2019-12-1 IDA / D1380 Post Request for Bids Open - National 154,007.32 Completed meters Kun-tuu, Alekseevk g e Envelope 1 6 8 9 8 9 8 3 7 9 6 a, Kyzyl-Tuu, Tolok, Korul and Ichke-Bulun IDA-SRWSSDP-GOODS-20 Request for Quo Single Stage - On 2018-05-1 2018-05-0 2018-07-1 2018-06-1 2018-09-0 2018-08-0 IDA / 59070 Project Management Post Limited 20,499.19 Completed 18-6 / Supply of technical tations e Envelope 5 8 0 9 8 1 equipment IDA-SRWSSDP-GOODS-20 Institutional Strengthenin Request for Quo Single Stage - On 2017-11-0 2017-11-0 2018-01-0 2018-01-1 2018-06-3 2018-05-1 IDA / D1380 Post Limited 10,971.16 Completed 17-5 / Purchase of waterm g tations e Envelope 6 8 1 0 0 7 eters for Togotoi IDA-SRWSSDP-GOODS-20 Request for Quo Single Stage - On 2017-04-1 2017-04-2 2017-06-1 2017-05-3 2017-12-0 2017-08-2 IDA / 59070 Project Management Post Limited 22,012.83 Completed 17-3 / Supply of 2 piece au tations e Envelope 7 4 2 0 9 2 to for ARIS IDA-SRWSSDP-GOODS-RF Q-20-1 / Purchase of chlori Request for Quo Single Stage - On 2020-04-1 2020-04-1 2020-05-2 2020-05-0 2020-06-2 2020-05-0 IDA / 59070 Sanitation Development Post Limited 25,503.94 Completed ne for disinfection of publi tations e Envelope 3 5 1 1 0 7 c/social institutions and pu blic places IDA-SRWSSDP-G-2020-1 / Institutional Strengthenin Request for Quo Single Stage - On 2020-06-0 2020-08-0 2020-07-3 2020-08-3 2020-08-2 Supply of computer equip IDA / D1380 Post Open - National 9,637.33 Completed g tations e Envelope 6 1 1 1 2 ment 12 for billing system IDA-SRWSSDP-G-2020-3 / Purchase of watermeters f Institutional Strengthenin Request for Quo Single Stage - On 2020-06-2 2020-08-1 2020-10-2 2020-11-1 2020-12-2 IDA / D1380 Post Open - National 33,272.37 Completed or Darkan and Chelpek su g tations e Envelope 3 8 9 6 3 bprojects Issyk-Kul oblast IDA-SRWSSDP-G-2020-4 / Institutional Strengthenin Request for Quo Single Stage - On 2020-06-2 2020-08-1 2020-11-1 Purchase of goods for CD IDA / 59070 Post Open - National 0.00 Canceled g tations e Envelope 3 8 6 WUUs of WSS sub-projects IDA-SRWSSDP-G-2021-2 / Request for Quo Single Stage - On 2021-07-0 2021-09-0 2021-04-2 2022-02-2 2021-05-2 Supply of computer equip IDA / 60880 Sanitation Development Post Open - National 16,201.71 Completed tations e Envelope 7 1 8 8 7 ment for 14 rayons SES IDA-SRWSSDP-G-2021-3 / Institutional Strengthenin Request for Quo Single Stage - On 2021-07-0 2021-09-0 2021-04-2 2022-02-2 2021-05-2 Supply of computer equip IDA / 60880 Post Open - National 13,531.05 Completed g tations e Envelope 7 1 8 8 7 ment 30 for billing system IDA-SRWSSDP-G-2021-4 / Pending Im Institutional Strengthenin Single Stage - On 2022-01-1 2022-01-1 2022-02-2 2022-03-2 2022-05-0 2022-10-2 Purchase of goods for CD IDA / 60880 Post Request for Bids Open - National 0.00 plementati g e Envelope 0 5 6 8 2 9 WUUs for 42 sub-projects ( on multiple contracts) IDA-SRWSSDP-G-2022-1 / Institutional Strengthenin Single Stage - On 2022-09-0 2022-09-0 2022-10-1 2022-11-1 2022-12-2 2023-06-2 Purchase of special machi IDA / 60880 Post Request for Bids Open - National 0.00 Canceled g e Envelope 1 6 8 7 2 0 nery for Ayil Okmotu IDA-SRWSSDP-G-2022-2 / Institutional Strengthenin Request for Quo Single Stage - On 2022-09-0 2022-11-0 2023-04-3 IDA / 60880 Post Open - National 0.00 Canceled Purchase of goods for DW g tations e Envelope 6 1 0 WSD IDA-SRWSSDP-G-2022-3 / Institutional Strengthenin Single Stage - On 2022-09-0 2022-09-0 2022-10-1 2022-11-1 2022-12-2 2023-06-2 IDA / 60880 Post Request for Bids Open - National 0.00 Canceled Goods for Training Center g e Envelope 1 6 8 7 2 0 IDA-SRWSSDP-G-2021-5 / Request for Quo Single Stage - On Pending Im 2021-09-0 2021-11-0 2022-05-0 IDA / 60880 Project Management Post Open - National 0.00 Technical-engineering equ tations e Envelope plementati 7 2 1 ipment for ARIS on IDA-SRWSSDP-G-2021-6 / Pending Im Request for Quo Single Stage - On 2021-09-0 2021-11-0 2022-05-0 Supply of computer and o IDA / 60880 Project Management Post Open - National 0.00 plementati tations e Envelope 7 2 1 ffice equipment for ARIS on IDA-SRWSSDP-G-2020-2 / Supply of computer equip Request for Quo Single Stage - On 2020-07-0 2020-06-1 2020-08-2 2020-09-2 ment for Republican cent IDA / D1380 Sanitation Development Post Open - National 0.00 Canceled tations e Envelope 1 9 6 5 er for health promotion an d mass communication un der GOKR IDA-SRWSSDP-G-2020-4-R Institutional Strengthenin Request for Quo Single Stage - On 2021-02-1 2021-03-0 2021-04-0 2021-07-0 T-1 / Purchase of goods for IDA / 59070 Post Open - National 0.00 Canceled g tations e Envelope 0 1 7 6 CDWUUs of WSS sub-proje cts IDA-SRWSSDP-G-2021-1 / Single Stage - On 2021-02-0 2021-02-1 2021-03-2 2021-04-2 2021-05-2 2021-11-2 Supply of laboratory equip IDA / 59070 Sanitation Development Post Request for Bids Open - National 0.00 Canceled e Envelope 5 0 4 3 8 4 ment for 11 rayons 2 Lots IDA-SRWSSDP-G-2020-2-R T-1 / Supply of computer e Request for Quo Single Stage - On 2020-07-0 2020-08-3 2020-12-0 2021-02-2 2020-12-1 quipment for Republican c IDA / 60880 Sanitation Development Post Open - National 2,350.90 Completed tations e Envelope 6 1 4 7 8 enter for health promotion and mass communication under GOKR IDA-SRWSSDP-G-2019-16 Institutional Strengthenin Single Stage - On 2023-08-0 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-05-1 / Purchase of watermeters IDA / 59070 Post Request for Bids Open - National 0.00 Canceled g e Envelope 1 6 7 7 1 9 for Otuz Adyr, Gulbar IDA-SRWSSDP-G-2020-4-R Institutional Strengthenin Request for Quo Single Stage - On 2021-08-2 2021-10-2 2021-09-2 2022-01-2 2021-10-1 T-2 / Purchase of goods fo IDA / 59070 Post Open - National 70,319.55 Completed g tations e Envelope 0 9 1 7 7 r CDWUUs of WSS sub-proj ects IDA-SRWSSDP-G-2021-7 / Institutional Strengthenin Request for Quo Single Stage - On 2021-09-2 2021-11-2 2021-11-2 2022-02-2 2021-12-2 Purchase of goods for 19 C IDA / 59070 Post Open - National 65,782.63 Completed g tations e Envelope 0 9 4 7 1 DWUUs of WSS sub-project s IDA-SRWSSDP-RFQ-GOOD Institutional Strengthenin Request for Quo Single Stage - On 2022-03-0 2022-05-0 2022-07-0 2023-03-3 S-2022-1 / Purchase of spe IDA / 60880 Post Open - National 0.00 Completed g tations e Envelope 9 5 4 0 cial machinery for Sultan s ubproject IDA-SRWSSDP-AF-G-2022- Institutional Strengthenin Request for Quo Single Stage - On 2022-02-2 2022-03-3 2022-04-1 2022-05-0 4 / Purchase of furniture fo IDA / D2040 Post Open - National 0.00 Completed g tations e Envelope 3 0 3 8 r DWWSD conference-roo m IDA-SRWSSDP-AF-G-2021- Institutional Strengthenin Request for Quo Single Stage - On 2021-09-2 2021-12-3 2022-01-0 2022-03-0 1 / Purchase of conference IDA / D2040 Post Open - National 20,558.94 Signed g tations e Envelope 4 1 1 1 equipment for DWWSD IDA-SRWSSDP-G-2021-1-R Single Stage - On 2022-03-1 2022-03-1 2022-03-1 2022-03-1 2022-04-1 2022-04-1 2022-05-1 2022-06-2 2022-12-1 T-2 / Supply of laboratory IDA / 59070 Sanitation Development Post Request for Bids Open - National 0.00 Canceled e Envelope 0 1 8 1 7 2 7 1 8 equipment for 11 rayons IDA-SRWSSDP-G-2021-1-R Single Stage - On 2021-08-0 2021-08-0 2021-08-1 2021-09-1 2021-09-1 2021-10-1 2021-11-1 2022-05-1 T-1 / Supply of laboratory IDA / 59070 Sanitation Development Post Request for Bids Open - National 0.00 Canceled e Envelope 6 2 3 0 4 0 4 3 equipment for 11 rayons IDA-SRWSSDP-RFQ-GOOD Institutional Strengthenin Request for Quo Single Stage - On 2022-04-1 2022-06-1 2022-08-1 2022-08-1 S-2022-1-RT-1 / Purchase IDA / 60880 Post Open - National 0.00 Completed g tations e Envelope 6 2 1 3 of special machinery for S ultan subproject IDA-SRWSSDP-G-2022-4 / Supply of computer equip Institutional Strengthenin Request for Quo Single Stage - On 2022-08-2 2022-10-1 2022-09-1 2022-11-2 2022-10-1 IDA / 60880 Post Open - National 9,814.29 Completed ment for 14 municipal wat g tations e Envelope 0 5 5 9 2 er unit (MWU) system in C hui, Issyk Kul and Osh obla sts. IDA-SRWSSDP-G-2021-1-R Pending Im Single Stage - On 2023-03-2 2023-03-2 2023-05-1 2023-06-0 2023-07-1 2024-01-1 T-3 / Supply of laboratory IDA / 59070 Sanitation Development Post Request for Bids Open - National 0.00 plementati e Envelope 4 9 0 9 4 0 equipment for 11 rayons on IDA-SRWSSDP-G-2023-1 / Institutional Strengthenin Request for Quo Single Stage - On Pending Im 2023-05-3 2023-07-2 2023-08-2 IDA / D1380 Post Open - National 0.00 Computer equipment for g tations e Envelope plementati 0 5 4 WMU on IDA-SRWSSDP-G-2023-3 / Pending Im Institutional Strengthenin Request for Quo Single Stage - On 2023-06-1 2023-08-1 2023-11-0 Purchase of goods for CD IDA / 59070 Post Open - National 0.00 plementati g tations e Envelope 4 0 8 WUUs for 15 sub-projects on NON CONSULTING SERVICES Activity Reference No. Bid Evaluation Repo Loan / Credit Market Approa Procurement Pr Prequalificatio Actual Amoun Process S Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission / Description Component Review Type Method rt and Recommenda Signed Contract Contract Completion No. ch ocess n (Y/N) t (US$) tatus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes tion for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. Short List and Draft Combined Evaluatio Loan / Credit Market Approa Contract Type Actual Amount Process Statu Expression of Intere Request for Proposal Opening of Technica Evaluation of Techn / Description Component Review Type Method Terms of Reference Request for Proposal n Report and Draft N Signed Contract Contract Completion No. ch (US$) s st Notice s as Issued l Proposals / Minutes ical Proposal s egotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SRWSSDP-QCBS-2016-2 / Quality And Cos Open - Internatio 2016-12-0 2016-12-2 2017-02-1 2017-03-2 2017-03-1 2017-05-0 2017-04-1 2017-05-1 2017-05-1 2017-05-2 2017-06-1 2017-05-3 2018-06-1 2018-04-1 Preparation of detailed des IDA / 59070 Water Supply Investments Post t-Based Selectio 161,171.72 Completed 2016-12-08 nal 5 9 1 8 1 3 0 2 5 5 9 0 9 0 igns for WSS sub-projects i n n Chui oblast SRWSSDP-CQ-2017-3 / Ba Consultant Qual 2017-02-2 2017-01-2 2017-03-0 2017-04-2 2017-04-0 2017-05-3 2017-05-1 2017-05-3 2017-11-0 2017-12-2 IDA / D1380 Project Management Post Open - National 34,049.99 Completed 2017-01-03 seline Survey ification Selecti 1 4 9 0 8 1 3 1 9 0 on SRWSSDP-QCBS-2016-1 / Quality And Cos Open - Internatio 2016-12-2 2017-02-1 2017-03-1 2017-04-1 2017-05-1 2017-06-1 2018-06-1 Preparation of detailed des IDA / 59070 Water Supply Investments Post t-Based Selectio 0.00 Canceled 2016-12-08 nal 9 1 1 0 5 9 9 igns for WSS sub-projects i n n Osh oblast SRWSSDP-CQ-2017-4 / Pr Consultant Qual 2017-08-2 2017-09-0 2017-08-2 2017-10-2 2017-10-1 2017-11-1 2017-12-0 2017-12-2 2017-12-0 2018-06-2 2019-08-3 eparation of detailed desig IDA / D1380 Water Supply Investments Post ification Selecti Open - National 184,576.00 Completed 2017-08-16 2 6 2 0 7 9 1 4 4 2 0 ns for WSS sub-projects in on Osh oblast ARIS-AUDIT-LCS-2017-1 / Least Cost Selec Open - Internatio 2017-10-0 2017-11-0 2018-03-1 2017-12-2 2018-03-2 2018-01-1 2018-04-1 2018-02-1 2018-04-1 2018-03-2 2018-04-2 2018-04-2 2018-04-2 2018-10-2 IDA / D1380 Project Management Post 53,521.44 Signed 2017-10-17 Audit of project funds tion nal 9 7 2 1 8 8 8 7 8 4 3 8 7 5 IDA-SRWSSDP-CQ-2017-8 Consultant Qual / Preparation of designs an 2017-11-0 2018-01-3 2018-03-1 2018-01-0 2018-04-1 2018-04-2 2018-05-2 2018-04-2 2018-11-1 2020-12-3 IDA / 59070 Sanitation Development Post ification Selecti Open - National 26,005.01 Completed 2018-01-10 d author supervision of su 3 1 6 8 5 4 0 7 6 0 on b-projects for out side toile ts IDA-SRWSSDP-CQ-2017-6 Consultant Qual / Creative Agency 2017-09-2 2017-10-2 2017-12-0 2017-11-1 2018-01-0 2017-12-1 2018-02-0 2017-12-1 2018-08-0 2019-05-3 IDA / 59070 Sanitation Development Post ification Selecti Open - National 139,285.00 Completed 2017-10-02 Development of a Sector- 5 3 6 3 5 5 9 8 8 1 on Wide WASH communicatio n campaign IDA-SRWSSDP-CQ-2018-9 / Consultant for design an Consultant Qual Institutional Strengthenin 2018-02-2 2018-04-0 2018-05-0 2018-06-0 2018-12-0 d development of Manage IDA / 59070 Post ification Selecti Open - National 0.00 Canceled 2018-01-30 g 0 5 5 9 6 ment Information System f on or improvement of sector performance monitoring s ystem IDA-SRWSSDP-CQ-AF-201 Consultant Qual 2019-02-2 2018-10-2 2019-03-2 2018-12-0 2019-05-2 2019-01-0 2019-07-0 2019-02-1 2019-08-1 IDA / D1380 Project Management Post Open - National 0.00 Canceled 2018-10-05 8-1 / Baseline Survey ification Selecti 7 6 3 9 2 8 1 2 1 on IDA-AF-SRWSSDP-QCBS-2 019-1 / Selection of Consul Quality And Cos Open - Internatio 2019-02-1 2019-03-0 2019-02-1 2019-04-1 2019-05-2 2019-05-1 2019-06-2 2019-06-1 2019-07-0 2019-07-1 2019-07-2 2019-08-2 2019-08-0 2020-08-2 2021-01-0 tant for Detailed Design of IDA / D2040 Water Supply Investments Post t-Based Selectio 150,612.74 Completed 2019-02-11 nal 3 4 3 7 4 5 5 4 4 9 6 3 7 2 1 Village Water Supply Infra n structure in Chui Oblast (6 sub-projects)-1 package Page 3 IDA-AF-SRWSSDP-QCBS-2 018-1 / Selection of Consul Quality And Cos tant for Detailed Design of Open - Internatio 2018-07-0 2018-06-2 2018-08-1 2018-09-0 2018-10-0 2018-11-1 2018-12-1 2019-12-1 IDA / D2040 Water Supply Investments Post t-Based Selectio 0.00 Canceled 2018-06-07 Village Water Supply Infra nal 5 8 1 8 8 2 7 7 n structure in Osh, Chui and Issyk-Kul Oblasts (10 subp rojects) -1 package IDA-AF-SRWSSDP-QCBS-2 018-2 / Selection of Consul Quality And Cos tant for Detailed Design of Open - Internatio 2018-07-0 2018-07-0 2018-08-1 2018-09-1 2018-10-1 2018-11-1 2018-12-2 2019-12-2 IDA / D2040 Water Supply Investments Post t-Based Selectio 0.00 Canceled 2018-06-10 Village Water Supply Infra nal 5 1 4 1 1 5 0 0 n structure in Osh, Chui and Issyk-Kul Oblasts (10 sub- projects)-2 package IDA-SRWSSDP-CQ-2017-5 Consultant Qual / Revisions to Interpersona 2017-10-2 2017-12-0 2018-01-0 2018-02-0 2018-08-0 IDA / 59070 Sanitation Development Post ification Selecti Open - National 0.00 Canceled 2017-10-02 l Communication Package 3 6 5 9 8 on and School WASH material s IDA-SRWSSDP-CQS-2017- Consultant Qual 5 / Revisions to Interperso 2017-09-2 2017-03-0 2017-04-1 2017-11-1 2017-05-1 2017-12-1 2017-06-2 2017-12-1 2017-12-1 2019-07-3 IDA / 59070 Sanitation Development Post ification Selecti Open - National 53,299.24 Signed 2017-02-10 nal Communication Packa 5 3 6 3 6 8 0 8 7 1 on ge and School WASH mate rials IDA-SRWSSDP-QCBS-2019 -1 / Consulting Firm to assi st in review of Design and Quality And Cos Open - Internatio 2019-08-0 2019-08-2 2019-08-2 2019-10-0 2020-03-0 2019-11-0 2020-05-2 2019-12-0 2021-10-2 2020-01-0 2020-02-1 2021-12-3 Estimate Documents and T IDA / D1380 Water Supply Investments Prior t-Based Selectio 0.00 Canceled 2019-07-25 nal 2 2 6 3 4 7 7 5 4 2 0 1 echnical Supervision of civ n il works for water supply s ystems rehabilitation in su bprojects of Chui, Osh and Issyk-Kul Oblasts IDA-SRWSSDP-AF-QCBS-2 019-2 / Consultant for Prep Quality And Cos aration of Feasibility Study Open - Internatio 2019-03-1 2019-03-2 2019-04-0 2019-05-1 2019-06-0 2019-07-0 2019-08-1 2019-09-1 2020-09-1 IDA / 59070 Water Supply Investments Prior t-Based Selectio 0.00 Canceled 2019-03-08 and Preliminary Designs fo nal 4 9 5 2 9 9 3 7 6 n r Water Supply Systems in 31 Sub-projects in Chui, O sh and Issyk-Kul Oblasts IDA-SRWSSDP-CQ-2017-7 / Consultant for updating a Consultant Qual Institutional Strengthenin 2017-10-1 2017-12-2 2018-02-0 2017-12-1 2018-03-0 2018-01-2 2018-04-0 2018-02-1 2018-10-0 2019-03-3 nd extending of training m IDA / 59070 Post ification Selecti Open - National 34,009.44 Completed 2017-11-30 g 7 1 3 3 5 9 9 0 6 1 odules for training of Aiyl on Okmotu/CDWUU and other operators IDA-SRWSSDP-QCBS-FS-2 020-1 / Preparation of Fea Quality And Cos sibility Study and Prelimin Open - Internatio Under Impleme 2020-03-2 2020-04-1 2020-04-1 2020-05-1 2020-06-1 2020-07-1 2020-08-1 2020-09-1 2021-03-3 IDA / 59070 Water Supply Investments Post t-Based Selectio 0.00 2020-03-20 ary Designs for Water Sup nal ntation 0 0 3 5 4 4 1 5 0 n ply Systems in the regions of Otuz-Adyr and Gulbaar villages, Osh oblast IDA-AF-SRWSSDP-QCBS-2 019-2 / Selection of Consul Quality And Cos Open - Internatio 2019-10-2 2019-09-2 2019-11-0 2019-12-1 2019-12-0 2020-01-1 2020-01-0 2020-01-1 2020-02-0 2020-01-2 2020-03-1 2020-02-0 2021-03-1 tant for Detailed Design of IDA / 59070 Water Supply Investments Post t-Based Selectio 118,506.99 Signed 2019-09-02 nal 4 3 6 9 4 0 3 7 7 9 3 1 3 Village Water Supply Infra n structure in Chui Oblast-2 package IDA-SRWSSDP-CQS-COMP 2-2020-1 / Company on pr Consultant Qual oducing of social informati 2020-06-1 2020-06-2 2020-08-1 2020-09-1 2020-10-1 2021-04-1 IDA / D1380 Sanitation Development Post ification Selecti Open - National 0.00 Canceled 2020-06-08 onal and educational video 5 9 2 1 6 4 on clips on prevention the spr ead of COVID-19 virus in t he Kyrgyz Republic IDA-SRWSSDP-CQS-COMP 2-2020-2 / Company on pr oducing a video training o Consultant Qual 2020-06-1 2020-06-2 2020-08-1 2020-09-1 2020-10-1 2021-04-1 n preventing the spread of IDA / D1380 Sanitation Development Post ification Selecti Open - National 0.00 Canceled 2020-06-08 5 9 2 1 6 4 COVID-19 virus for a wide on range of people working w ith the population after qu arantine (for field activists ) IDA-SRWSSDP-CQS-COMP Consultant Qual 3-2020-2 / Сompany for su Institutional Strengthenin 2020-08-0 2020-07-0 2020-08-2 2021-03-1 2020-09-2 2021-05-3 2020-10-2 2021-06-0 2021-05-2 IDA / D1380 Post ification Selecti Open - National 73,634.03 Signed 2020-06-18 pporting to Institutional De g 5 9 2 1 1 1 6 2 4 on velopment Plan for the DD WSWD IDA-SRWSSDP-CQS-COMP 3-2020-3 / Company for th Consultant Qual e Supporting to Water Sup Institutional Strengthenin 2020-09-0 2020-07-0 2020-08-2 2020-12-0 2020-09-2 2021-06-1 2020-10-2 2021-06-2 2021-07-2 IDA / D1380 Post ification Selecti Open - National 190,872.51 Signed 2020-06-18 ply and Sanitation Sector P g 3 9 2 4 1 8 6 6 3 on rofessional and Vocational Development Program in t he Kyrgyz Republic IDA-SRWSSDP-CQS-COMP 3-2020-1 / Company for th Consultant Qual Institutional Strengthenin 2020-09-0 2020-07-0 2020-08-2 2020-12-0 2020-09-2 2021-01-1 2020-10-2 2021-02-1 2021-04-2 e development of Legal R IDA / D1380 Post ification Selecti Open - National 35,780.01 Signed 2020-06-18 g 3 9 2 4 1 8 6 3 4 egulatory Acts for Water S on upply and Wastewater Dis posal Sector IDA-SRWSSDP-CQS-COMP 2-2020-3 / Company for Pr Consultant Qual 2020-07-2 2020-07-3 2020-09-1 2020-09-1 2020-10-1 2020-09-1 2020-11-1 2020-10-0 2021-11-1 2020-11-1 oduction Social and Educa IDA / D1380 Sanitation Development Post ification Selecti Open - National 15,326.40 Completed 2020-07-10 0 1 3 4 3 8 7 2 7 7 tional Videos on preventio on n of COVID-19 spread in th e Kyrgyz Republic IDA-SRWSSDP-AF-CQS-20 Consultant Qual 19-4 / Preparation of detail Pending Imple 2019-10-1 2019-11-2 2019-12-2 2020-02-0 2021-02-0 IDA / 60880 Water Supply Investments Post ification Selecti Open - National 0.00 2019-09-25 ed designs for WSS sub-pr mentation 6 9 9 2 1 on ojects in Osh oblast (1 pha se) IDA-SRWSSDP-AF-QCBS-D Quality And Cos DE-2020-1 / Preparation of Under Impleme 2020-01-1 2020-07-2 2020-09-0 2020-10-0 2020-10-3 2020-12-0 2021-01-0 2022-01-0 IDA / 60880 Water Supply Investments Post t-Based Selectio Open - National 0.00 2020-06-30 detailed designs for WSS s ntation 5 1 3 1 1 5 9 9 n ub-projects in Osh oblast ( 2 Phase) IDA-AF-SRWSSDP-QCBS-2 Quality And Cos 020-3 / Preparation of deta Pending Imple 2020-03-2 2020-05-0 2020-06-0 2020-07-0 2020-08-0 2020-09-1 2021-09-1 IDA / 60880 Water Supply Investments Post t-Based Selectio Open - National 0.00 2020-03-01 iled designs for WSS sub-p mentation 2 5 2 2 6 0 0 n rojects in Chui oblast (3 Ph ase) IDA-SRWSSDP-AF-CQS-20 Consultant Qual 19-3 / Preparation of detail Pending Imple 2019-10-2 2019-12-0 2020-01-0 2020-02-1 2020-08-0 IDA / 60880 Water Supply Investments Post ification Selecti Open - National 0.00 2019-10-03 ed designs for WSS sub-pr mentation 4 7 6 0 8 on ojects in IK oblast (1 Phase ) IDA-SRWSSDP-AF-QCBS-D Quality And Cos DE-2020-2 / Preparation of 2020-03-1 2020-03-2 2020-05-0 2020-07-3 2020-06-0 2020-09-0 2020-07-0 2020-10-3 2020-08-0 2020-11-1 2020-09-1 2020-12-0 2021-09-1 IDA / 60880 Water Supply Investments Post t-Based Selectio Open - National 127,488.68 Signed 2020-03-01 detailed designs for WSS s 6 2 5 0 2 2 2 0 6 7 0 2 0 n ub-projects in IK oblast (2 Phase) IDA-SRWSSDP-AF-CQS-19- Consultant Qual 2019-02-2 2019-03-2 2019-05-0 2019-05-2 2019-06-0 2019-07-0 2019-07-0 2019-07-0 2020-01-0 2020-02-0 1 / Baseline Survey and Im IDA / 60880 Project Management Post ification Selecti Open - National 35,671.67 Completed 2019-02-27 7 0 3 2 2 1 7 2 3 1 pact Assesment on IDA-SRWSSDP-AF-CQS-20 Consultant Qual 21-1 / Technical Supervisio 2021-06-0 2021-05-2 2021-06-1 2021-07-0 2022-05-1 2021-07-2 2022-08-1 2021-08-0 2022-09-0 2023-08-0 IDA / D1380 Water Supply Investments Post ification Selecti Open - National 98,658.58 Signed 2021-04-26 n of Civil Works for Constr 4 4 1 5 6 6 9 9 1 9 on uction of Rural Water Supp ly and Sanitation Systems ARIS-AUDIT-LCS-2021-1 / Least Cost Selec Open - Internatio Under Impleme 2021-08-1 2021-08-2 2021-09-2 2021-09-1 2021-10-0 2021-10-1 2021-11-0 2021-11-2 2023-12-3 IDA / 60880 Project Management Post 0.00 2021-08-06 Audit tion nal ntation 6 0 4 7 8 5 5 6 1 IDA-SRWSSDP-AF-CQS-EIA -2021 / Consulting compan Consultant Qual y for Engineering, Environ 2021-05-0 2021-05-2 2021-06-1 2021-06-2 2021-10-0 2021-07-0 2021-07-1 2021-09-2 IDA / D2040 Water Supply Investments Post ification Selecti Open - National 0.00 Canceled 2021-05-07 mental and Sanitary Safet 7 8 1 5 8 2 6 4 on y Review in subprojects Iv anovka Station, Kara-Jygac h, Sosnovka, Komsomol’sk oe and Kurmontu IDA-SRWSSDP-CQS-2022- Consultant Qual 2022-08-1 2022-09-0 2022-10-1 2022-10-0 2022-11-1 2022-11-1 2022-12-2 2023-06-2 1 / Preparation of detailed IDA / D1380 Water Supply Investments Post ification Selecti Open - National 0.00 Signed 2022-08-15 1 5 9 4 8 5 3 1 designs for Otuz-Adyr WSS on sub-project IDA-SRWSSDP-CQS-2022- Consultant Qual 2022-08-1 2022-09-0 2022-10-1 2022-10-0 2022-11-1 2022-11-1 2022-12-2 2023-06-2 2 / Preparation of detailed IDA / D1380 Water Supply Investments Post ification Selecti Open - National 0.00 Signed 2022-08-15 1 5 9 4 8 5 3 1 designs for Gulbar WSS su on b-project IDA-SRWSSDP-AF-CQS-20 22-11 / Development of So Consultant Qual cial Video Tutorials on Rul Under Impleme 2023-03-1 2023-01-3 2023-03-1 2023-04-1 2023-05-2 2023-06-1 IDA / D2040 Sanitation Development Post ification Selecti Open - National 0.00 2023-01-10 es for Construction of Outd ntation 3 1 6 5 0 9 on oor Latrines With Improve d Ventilation and Septic Ta nks at Rural Households RWSSP3-PPG-CQ-2016-1 / Consultant Qual Consultants for Detailed D Open - Internatio 2016-04-1 2016-04-1 TF / A1605 Water Supply Investments Prior ification Selecti 125,290.67 Signed esign of Village Water Sup nal 5 9 on ply Infrastructure in Chui a nd Osh Oblasts INDIVIDUAL CONSULTANTS Activity Reference No. Loan / Credit Market Approa Actual Amount Process Statu Invitation to Identifie Draft Negotiated Co Component Review Type Method Contract Type Teams of Reference Signed Contract Contract Completion / Description No. ch (US$) s d/Selected Consulta ntract Planned Actual Planned nt Actual Planned Actual Planned Actual Planned Actual IDA-SRWSSDP-IC-2017-2 / Institutional Strengthenin 2016-12-0 2016-12-0 2016-12-2 2016-12-3 2016-12-2 2017-06-2 IDA / D1380 Post Direct Selection Direct 17,028.70 Terminated 2016-12-09 Institutional specialist g 1 9 6 0 6 8 IDA-SRWSSDP-IC-2017-3 / 2016-12-0 2016-12-0 2016-12-2 2016-12-3 2016-12-2 2017-06-2 IDA / 59070 Water Supply Investments Post Direct Selection Direct 12,392.86 Signed 2016-12-09 Infrastructure engineer (1 1 9 6 0 6 8 position) IDA-SRWSSDP-IC-2017-1 / 2016-12-1 2016-12-0 2016-12-2 2016-12-3 2016-12-2 2017-06-2 2017-11-1 IDA / D1380 Sanitation Development Post Direct Selection Direct 60,000.00 Signed 2016-12-09 Sanitation and hygene spe 9 9 1 0 6 8 3 cialist SRWSSDP-CS-SSS-2017-1 / Preparation of detailed d Under Impleme 2017-06-0 2017-04-0 2017-06-2 2017-04-2 2017-10-2 IDA / 59070 Water Supply Investments Post Direct Selection Direct 0.00 2017-04-03 esigns for WSS sub-project ntation 5 3 1 4 1 s in Issyk-Kul oblast (Chelp ek, Darkhan) IDA-SRWSSDP-IC-2017-6 / Institutional Strengthenin Individual Cons 2017-03-3 2017-04-1 2017-05-2 2017-04-1 2017-05-2 2017-05-0 2017-10-2 Social mobilisation on insti IDA / D1380 Post Open 0.00 Canceled 2017-04-11 g ultant Selection 0 1 5 1 5 2 9 tutional strengthening IDA-SRWSSDP-2017-7 / So Institutional Strengthenin Individual Cons 2017-04-0 2017-04-1 2017-05-2 2017-04-1 2017-05-2 2017-05-0 2017-06-0 2017-10-2 2020-01-0 cial mobilisation expert o IDA / D1380 Post Open 13,784.43 Completed 2017-04-11 g ultant Selection 3 1 2 1 9 2 2 9 1 n institutional strengtheni ng IDA-SRWSSDP-IC-2017-5 / Institutional Strengthenin Individual Cons Under Impleme 2017-04-0 2017-05-3 2017-05-2 2017-06-2 2017-05-2 2017-07-2 2018-01-2 Local experts on social mo IDA / D1380 Post Open 0.00 2017-04-11 g ultant Selection ntation 3 0 2 0 9 5 1 bilization and institutional development IDA-SRWSSDP-IC-2017-8 / Institutional Strengthenin Individual Cons 2017-04-0 2017-04-1 2017-05-2 2017-04-1 2017-05-2 2017-05-0 2017-06-0 2017-10-2 2020-01-0 Local social mobilisation e IDA / D1380 Post Open 17,190.99 Completed 2017-04-11 g ultant Selection 3 1 2 1 9 2 2 9 1 xpert on institutional stren gthening IDA-RWSSDP-CS-IC-2017- Individual Cons Under Impleme 2019-04-1 2017-07-0 2017-06-1 2017-07-2 2017-06-1 2017-09-0 2018-02-2 3 / Field technical supervis IDA / 59070 Water Supply Investments Post Open 0.00 2017-05-19 ultant Selection ntation 0 7 9 8 9 1 8 ion engineer in Togotoi IDA-SRWSSDP-CS-IC-2017 Individual Cons Under Impleme 2017-05-1 2017-07-0 2017-07-2 2017-09-0 2018-02-2 -8 / Field technical supervi IDA / 59070 Water Supply Investments Post Open 0.00 2017-05-19 ultant Selection ntation 9 7 8 1 8 sion engineer Kurama IDA-SRWSSDP-CS-IC-2017 Individual Cons 2017-07-0 2017-07-2 2017-09-0 2018-02-2 IDA / 59070 Water Supply Investments Post Open 0.00 Canceled 2017-05-19 -9 / Assistant of field engin ultant Selection 7 8 1 8 eer in Togotoi IDA-SRWSSDP-CS-IC-2017 Individual Cons 2017-07-0 2017-07-2 2017-09-0 2018-02-2 IDA / 59070 Water Supply Investments Post Open 0.00 Canceled 2017-05-19 -10 / Assistant of field engi ultant Selection 7 8 1 8 neer in Sultan IDA-SRWSSDP-2017-11 / Individual Cons 2018-08-0 2017-07-0 2018-09-0 2017-07-2 2018-09-0 2017-09-0 2018-09-0 2018-02-2 2019-04-3 IDA / 59070 Water Supply Investments Post Open 3,932.44 Completed 2017-05-19 Assistant of field engineer ultant Selection 1 7 6 8 6 1 7 8 0 in Kyrgyz Ata IDA-SRWSSDP-CS-IC-2017 Individual Cons 2017-07-0 2017-07-2 2017-09-0 2018-02-2 -12 / Assistant of field engi IDA / 59070 Water Supply Investments Post Open 0.00 Canceled 2017-05-19 ultant Selection 7 8 1 8 neer in Kurama SRWSSDP-DS-2017-1 / Pre paration of detailed design 2017-06-0 2017-06-2 2017-06-2 2017-09-0 2017-09-1 2018-03-0 2018-11-3 IDA / 59070 Water Supply Investments Post Direct Selection Direct 53,560.16 Completed 2017-06-19 s for WSS sub-projects in I 2 9 1 2 3 1 0 K oblast: Chelpek, Darkha n IDA-SRWSSDP-IC-2017-9 / Institutional Strengthenin Individual Cons 2017-07-2 2017-08-1 2017-09-2 2018-03-2 IDA / 59070 Prior Open 0.00 Canceled 2017-06-08 International contract sup g ultant Selection 7 7 1 0 ervision Page 4 IDA-SRWSSDP-IC-2017-11 Individual Cons Under Impleme 2017-08-2 2017-10-0 2017-12-0 2017-10-2 2018-01-1 2017-11-2 2018-05-2 IDA / D1380 Water Supply Investments Prior Open 0.00 2017-08-16 / International contract su ultant Selection ntation 3 4 4 5 9 9 8 pervision IDA-SRWSSDP-IC-2017-12 Individual Cons 2017-07-1 2017-10-1 2016-09-2 2017-11-0 2017-10-3 2017-12-0 2017-10-3 2018-06-0 2018-09-3 / Consultant for review th IDA / 59070 Water Supply Investments Post Open 50,000.00 Completed 2017-08-16 ultant Selection 2 3 6 3 0 8 1 6 0 e designs for sub-projects IDA-SRWSSDP-IC-2017-13 Institutional Strengthenin Individual Cons 2017-10-1 2017-10-3 2017-12-0 2018-06-0 IDA / 59070 Post Open 0.00 Canceled 2017-08-22 / Hydrogeologist g ultant Selection 0 1 5 3 IDA-SRWSSDP-CW-2017-5 Individual Cons 2017-07-0 2017-07-2 2017-09-0 2018-02-2 / Field technical supervisio IDA / 59070 Water Supply Investments Post Open 0.00 Canceled 2017-05-19 ultant Selection 7 8 1 8 n engineer in Sultan IDA-SRWSSDP-IC-2017-4 / Individual Cons 2016-12-0 2017-01-2 2016-12-2 2017-02-1 2016-12-2 2017-03-2 2016-12-3 2017-09-2 2018-06-3 IDA / 59070 Water Supply Investments Post Open 8,577.56 Completed 2016-12-09 Infrastructure engineer 2 ultant Selection 5 7 9 7 9 4 0 0 0 IDA-SRWSSDP-SSS-17-5 / 2017-07-2 2017-06-1 2017-06-1 2017-08-1 2017-06-1 2018-02-1 2019-09-3 IDA / 59070 Water Supply Investments Post Direct Selection Direct 20,711.54 Completed 2017-06-01 Author supervision 6 1 3 5 5 1 0 IDA-SRWSSDP-IC-2017-29 Institutional Strengthenin Individual Cons 2017-03-3 2017-12-0 2017-10-1 2017-12-2 2017-10-1 2018-01-2 2017-10-1 2018-07-2 2019-12-3 / Social mobilisation on ins IDA / 59070 Post Open 15,648.99 Completed 2017-10-13 g ultant Selection 1 1 3 2 3 6 3 5 1 titutional strengthening IDA-SRWSSDP-IC-2017-30 Institutional Strengthenin Individual Cons 2018-03-3 2017-12-0 2017-10-1 2017-12-2 2017-10-1 2018-01-2 2017-10-1 2018-07-2 2018-06-3 / Social mobilisation on ins IDA / 59070 Post Open 6,015.04 Completed 2017-10-13 g ultant Selection 0 1 3 2 3 6 3 5 0 titutional strengthening IDA-SRWSSDP-IC-2017-31 Institutional Strengthenin Individual Cons 2017-10-3 2017-12-0 2017-10-1 2017-12-2 2017-10-1 2018-01-2 2017-10-1 2018-07-2 2019-12-3 / Social mobilisation on ins IDA / 59070 Post Open 13,892.03 Completed 2017-10-13 g ultant Selection 0 1 3 2 3 6 3 5 1 titutional strengthening IDA-SRWSSDP-IC-2017-32 Institutional Strengthenin Individual Cons 2017-03-3 2017-12-0 2017-10-1 2017-12-2 2017-10-1 2018-01-2 2017-10-1 2018-07-2 2019-12-3 / Social mobilisation on ins IDA / 59070 Post Open 14,499.97 Completed 2017-10-13 g ultant Selection 0 1 3 2 3 6 3 5 1 titutional strengthening IDA-SRWSSDP-IC-2017-33 Individual Cons 2017-05-1 2017-11-1 2017-09-2 2017-12-1 2017-09-2 2018-01-1 2017-09-2 2018-07-1 2019-03-3 / Junior field technical supe IDA / 59070 Water Supply Investments Post Open 6,015.04 Completed 2017-10-01 ultant Selection 2 9 0 0 1 4 1 3 1 rvision engineer IDA-SRWSSDP-IC-2017-34 Individual Cons 2017-05-1 2017-11-1 2017-09-2 2017-12-1 2017-09-2 2018-01-1 2017-09-2 2018-07-1 2018-06-3 / Junior field technical supe IDA / 59070 Water Supply Investments Post Open 6,015.04 Completed 2017-10-01 ultant Selection 2 9 0 0 1 4 1 3 0 rvision engineer IDA-SRWSSDP-IC-17-5 / S Institutional Strengthenin Individual Cons 2017-03-3 2017-07-2 2017-05-2 2017-08-1 2017-05-2 2017-09-1 2017-06-0 2018-03-1 2018-06-3 ocial mobilisation on instit IDA / 59070 Post Open 6,874.33 Completed 2017-06-01 g ultant Selection 0 0 5 0 5 4 1 3 0 utional strengthening IDA-SRWSSDP-IC-17-6 / S Institutional Strengthenin Individual Cons 2017-07-2 2017-08-1 2017-09-1 2018-03-1 ocial mobilisation on instit IDA / 59070 Post Open 0.00 Canceled 2017-06-01 g ultant Selection 0 0 4 3 utional strengthening IDA-SRWSSDP-IC-17-7 / S Institutional Strengthenin Individual Cons Under Impleme 2017-03-3 2017-07-2 2017-05-2 2017-08-1 2017-05-2 2017-09-1 2018-03-1 ocial mobilisation on instit IDA / 59070 Post Open 0.00 2017-06-01 g ultant Selection ntation 1 0 5 0 5 4 3 utional strengthening IDA-SRWSSDP-IC-17-8 / S Institutional Strengthenin Individual Cons 2017-03-3 2017-07-2 2017-05-2 2017-08-1 2017-05-2 2017-09-1 2018-03-1 ocial mobilisation on instit IDA / 59070 Post Open 0.00 Canceled 2017-06-01 g ultant Selection 1 0 5 0 5 4 3 utional strengthening IDA-SRWSSDP-IC-17-9 / Fi Individual Cons Under Impleme 2017-05-1 2017-08-0 2017-08-2 2017-10-0 2018-03-3 IDA / 59070 Water Supply Investments Post Open 0.00 2017-06-19 eld technical supervision e ultant Selection ntation 9 7 8 2 1 ngineer IDA-SRWSSDP-IC-17-10 / F Individual Cons Under Impleme 2017-05-1 2017-09-0 2017-07-1 2017-09-2 2017-07-1 2017-10-3 2018-04-2 IDA / 59070 Water Supply Investments Post Open 0.00 2017-07-17 ield technical supervision ultant Selection ntation 2 4 3 5 3 0 8 engineer IDA-SRWSSDP-IC-17-12 / Individual Cons 2019-04-1 2017-10-1 2017-08-2 2017-11-0 2017-08-2 2017-12-0 2017-08-2 2018-06-0 2018-08-3 IDA / 59070 Water Supply Investments Post Open 15.57 Completed 2017-08-24 Hydrogeologist ultant Selection 1 2 3 2 4 7 4 5 1 IDA-SRWSSDP-IC-17-13 / F Individual Cons Under Impleme 2017-05-1 2017-10-2 2017-08-2 2017-11-1 2017-09-0 2017-12-1 2018-06-1 IDA / 59070 Water Supply Investments Post Open 0.00 2017-09-04 ield technical supervision ultant Selection ntation 2 3 9 3 4 8 6 engineer IDA-SRWSSDP-IC-17-14 / F Individual Cons Under Impleme 2019-04-1 2017-10-1 2017-07-3 2017-11-0 2017-08-2 2017-12-0 2018-06-0 IDA / 59070 Water Supply Investments Post Open 0.00 2017-08-25 ield technical supervision ultant Selection ntation 0 3 1 3 4 8 6 engineer IDA-SRWSSDP-IC-17-15 / F Individual Cons 2019-04-1 2017-10-2 2017-07-3 2017-11-1 2017-09-0 2017-12-1 2017-09-0 2018-06-1 2018-02-1 IDA / 59070 Water Supply Investments Post Open 2,571.61 Completed 2017-09-04 ield technical supervision ultant Selection 0 3 1 3 4 8 4 6 5 engineer IDA-SRWSSDP-IC-17-36 / Individual Cons 2017-10-0 2018-01-0 2017-11-1 2018-01-2 2017-11-1 2018-02-2 2017-11-1 2018-08-2 2018-12-3 IDA / 59070 Sanitation Development Post Open 9,292.35 Completed 2017-11-14 Sanitation & Hygiene Spec ultant Selection 3 2 0 3 3 7 4 6 1 ialist IDA-SRWSSDP-IC-2017-37 Individual Cons Under Impleme 2017-05-1 2018-01-1 2017-11-3 2018-02-0 2017-11-3 2018-03-1 2018-09-1 / Junior field technical supe IDA / 59070 Water Supply Investments Post Open 0.00 2017-12-01 ultant Selection ntation 2 9 0 9 0 6 2 rvision engineer IDA-SRWSSDP-IC-2017-38 Individual Cons Under Impleme 2017-12-0 2018-01-1 2018-02-0 2018-03-1 2018-09-1 / Junior field technical supe IDA / 59070 Water Supply Investments Post Open 0.00 2017-12-01 ultant Selection ntation 1 9 9 6 2 rvision engineer IDA-SRWSSDP-IC-2017-39 Individual Cons 2018-11-0 2017-03-3 2017-12-2 2017-04-2 2017-12-2 2017-05-2 2018-01-0 2017-11-2 2018-07-3 / PR consultant for commu IDA / 59070 Sanitation Development Post Open 41,876.99 Completed 2017-02-10 ultant Selection 2 1 9 1 9 6 4 2 1 nication strategy IDA-SRWSSDP-IC-2017-44 / Local consultant for supp Institutional Strengthenin Individual Cons Pending Imple 2018-01-1 2018-02-0 2018-03-1 2018-09-1 IDA / 59070 Post Open 0.00 2017-11-30 orting CDWUU in financial g ultant Selection mentation 8 8 5 1 planning and developmen t of tarifs IDA-SRWSSDP-IC-2017-45 Institutional Strengthenin Individual Cons 2018-01-1 2018-02-0 2018-03-1 2018-09-1 IDA / 59070 Post Open 0.00 Canceled 2017-11-30 / Billing system consultant g ultant Selection 8 8 5 1 IDA-SRWSSDP-IC-2018-4 / Consultant for supporting of advanced financing of t Institutional Strengthenin Individual Cons 2018-12-2 2019-01-1 2019-02-1 2019-08-1 he sector, including planni IDA / 59070 Post Open 0.00 Canceled 2018-11-01 g ultant Selection 0 0 4 3 ng of investments, financi al modelling, regulation, m onitoring, survey of tarifs ( international consulatnt) IDA-SRWSSDP-IC-2018-5 / Consultant for developme Institutional Strengthenin Individual Cons 2017-12-2 2018-01-1 2018-02-1 2018-08-1 IDA / 59070 Post Open 0.00 Canceled 2017-11-01 nt and piloting of new mo g ultant Selection 0 0 4 3 dels of services managem ent (international) IDA-SRWSSDP-IC-2018-6 / Consultant for developme Institutional Strengthenin Individual Cons 2019-03-0 2019-03-2 2019-04-3 2019-10-2 IDA / 59070 Post Open 0.00 Canceled 2019-01-15 nt of institutional support g ultant Selection 5 6 0 7 plan for DWSS (internation al) IDA-SRWSSDP-IC-2018-36 Institutional Strengthenin Individual Cons 2018-01-1 2018-02-0 2018-03-1 2018-09-1 / Consultant for developm IDA / 59070 Post Open 0.00 Canceled 2017-12-01 g ultant Selection 9 9 6 2 ent of legal acts in WSS sp here IDA-SRWSSDP-IC-2017-17 Individual Cons 2017-03-3 2017-11-1 2017-08-1 2017-12-1 2017-10-0 2018-01-1 2017-10-0 2018-07-1 2018-05-3 IDA / 59070 Sanitation Development Post Open 5,053.84 Completed 2017-10-01 / Trеiner-facilitator ultant Selection 0 9 0 0 3 4 3 3 1 IDA-SRWSSDP-IC-2017-18 Individual Cons 2017-03-3 2017-11-1 2017-08-1 2017-12-1 2017-09-2 2018-01-1 2017-10-0 2018-07-1 2018-05-3 IDA / 59070 Sanitation Development Post Open 5,050.94 Completed 2017-10-01 / Trеiner-facilitator ultant Selection 0 9 0 0 9 4 3 3 1 IDA-SRWSSDP-IC-2017-19 Individual Cons 2017-03-3 2017-11-1 2017-08-1 2017-12-1 2017-09-2 2018-01-1 2017-10-0 2018-07-1 2018-05-3 IDA / 59070 Sanitation Development Post Open 5,053.84 Completed 2017-10-01 / Trеiner-facilitator ultant Selection 0 9 0 0 9 4 3 3 1 IDA-SRWSSDP-IC-2017-20 Individual Cons 2017-03-3 2017-11-1 2017-08-1 2017-12-1 2017-09-2 2018-01-1 2017-10-0 2018-07-1 2018-05-3 IDA / 59070 Sanitation Development Post Open 5,053.84 Completed 2017-10-01 / Trеiner-facilitator ultant Selection 0 9 0 0 9 4 3 3 1 IDA-SRWSSDP-IC-2017-21 Individual Cons 2017-03-3 2017-11-1 2017-08-1 2017-12-1 2017-09-2 2018-01-1 2017-10-0 2018-07-1 2018-05-3 IDA / 59070 Sanitation Development Post Open 5,053.84 Completed 2017-10-01 / Trеiner-facilitator ultant Selection 0 9 0 0 9 4 3 3 1 IDA-SRWSSDP-IC-2017-22 Individual Cons 2017-03-3 2017-11-1 2017-08-1 2017-12-1 2017-09-2 2018-01-1 2017-10-0 2018-07-1 2018-05-3 IDA / 59070 Sanitation Development Post Open 5,053.84 Completed 2017-10-01 / Trеiner-facilitator ultant Selection 0 9 0 0 9 4 3 3 1 IDA-SRWSSDP-IC-2017-23 Individual Cons 2017-03-3 2017-11-1 2017-08-1 2017-12-1 2017-09-2 2018-01-1 2017-10-0 2018-07-1 2018-05-3 IDA / 59070 Sanitation Development Post Open 5,050.94 Completed 2017-10-01 / Trеiner-facilitator ultant Selection 0 9 0 0 9 4 3 3 1 IDA-SRWSSDP-IC-2017-24 Individual Cons 2017-03-3 2017-11-1 2017-08-1 2017-12-1 2017-09-2 2018-01-1 2017-10-0 2018-07-1 2018-05-3 IDA / 59070 Sanitation Development Post Open 5,050.94 Completed 2017-10-01 / Trеiner-facilitator ultant Selection 0 9 0 0 9 4 3 3 1 IDA-SRWSSDP-IC-2017-25 Individual Cons 2017-03-3 2017-11-1 2017-08-1 2017-12-1 2017-09-2 2018-01-1 2017-10-0 2018-07-1 2018-05-3 IDA / 59070 Sanitation Development Post Open 5,050.94 Completed 2017-10-01 / Trеiner-facilitator ultant Selection 0 9 0 0 9 4 3 3 1 IDA-SRWSSDP-IC-2017-26 Individual Cons 2017-03-3 2017-11-1 2017-08-1 2017-12-1 2017-09-2 2018-01-1 2017-10-0 2018-07-1 2018-05-3 IDA / 59070 Sanitation Development Post Open 5,050.94 Completed 2017-10-01 / Trеiner-facilitator ultant Selection 0 9 0 0 9 4 3 3 1 IDA-SRWSSDP-IC-2017-27 Individual Cons 2017-03-3 2017-11-1 2017-08-1 2017-12-1 2017-09-2 2018-01-1 2017-10-0 2018-07-1 2018-05-3 IDA / 59070 Sanitation Development Post Open 5,050.94 Completed 2017-10-01 / Trеiner-facilitator ultant Selection 0 9 0 0 9 4 3 3 1 IDA-SRWSSDP-IC-2017-28 Individual Cons 2017-03-3 2017-11-1 2017-08-1 2017-12-1 2017-09-2 2018-01-1 2017-10-0 2018-07-1 2018-05-3 IDA / 59070 Sanitation Development Post Open 5,050.94 Completed 2017-10-01 / Trеiner-facilitator ultant Selection 0 9 0 0 9 4 3 3 1 IDA-SRWSSDP-IC-2017-35 Individual Cons 2017-03-3 2017-12-2 2017-08-1 2018-01-1 2017-09-2 2018-02-1 2017-11-0 2018-08-1 2018-05-3 IDA / 59070 Sanitation Development Post Open 4,417.04 Completed 2017-11-01 / Trеiner-facilitator ultant Selection 0 0 0 0 9 4 1 3 1 IDA-SRWSSDP-IC-2017-42 Institutional Strengthenin Individual Cons 2018-01-1 2018-02-0 2018-03-1 2018-09-0 / Trainer for capacity build IDA / 59070 Post Open 0.00 Canceled 2017-11-28 g ultant Selection 6 6 3 9 ing of WSS sector institutio ns IDA-SRWSSDP-IC-2018-2 / Institutional Strengthenin Individual Cons 2018-02-2 2018-03-2 2018-04-2 2018-10-2 GIS consultant and IT cons IDA / 59070 Post Open 0.00 Canceled 2018-01-10 g ultant Selection 8 1 5 2 ultant (1 person) IDA-SRWSSDP-DS-2018-1 2018-02-1 2018-03-1 2018-03-2 2018-05-1 2018-05-0 2018-11-1 / Preparation of detailed d IDA / 59070 Water Supply Investments Post Direct Selection Direct 19,990.19 Signed 2018-03-01 4 1 2 5 2 1 esigns for WSS sub-project s in Oshoblast: Korul IDA-SRWSSDP-DS-2018-2 / Preparation of detailed d 2018-02-1 2018-03-1 2018-03-2 2018-05-1 2018-05-0 2018-11-1 2018-10-2 esigns for WSS sub-project IDA / 59070 Water Supply Investments Post Direct Selection Direct 57,004.80 Completed 2018-03-01 4 1 2 5 2 1 9 s in IK and Chui oblasts: Ta mga, Ichke-Bulun, Gornay a Maevka. IDA-SRWSSDP-DS-2018-3 2018-02-1 2018-03-1 2018-03-2 2018-05-1 2018-05-0 2018-11-1 / Preparation of detailed d IDA / 59070 Water Supply Investments Post Direct Selection Direct 13,624.20 Signed 2018-03-01 4 1 2 5 2 1 esigns for WSS sub-project s in IK oblast: Ak-Bulak IDA-SRWSSDP-IC-2018-13 / Coordinator of a Team fo Institutional Strengthenin Individual Cons 2018-03-0 2018-06-0 2018-03-2 2018-06-2 2018-03-2 2018-07-3 2018-04-0 2019-12-3 2018-12-3 r development and imple IDA / D1380 Post Open 21,779.99 Completed 2018-04-25 g ultant Selection 2 5 9 6 9 1 2 1 1 mentation of Rural Water Supply and Sanitation Info rmation System (SIASAR) IDA-SRWSSDP-IC-2018-12 / Web Developer Specialist Institutional Strengthenin Individual Cons 2018-03-0 2018-06-1 2018-04-1 2018-07-0 2018-04-2 2018-08-1 2018-04-2 2019-12-3 2018-12-3 IDA / D1380 Post Open 11,118.28 Completed 2018-04-27 Information System for Ru g ultant Selection 2 5 3 6 0 0 4 1 1 ral Water Supply and Sanit ation (SIASAR) IDA-SRWSSDP-IC-2018-14 Institutional Strengthenin Individual Cons Under Impleme 2018-03-0 2018-06-1 2018-03-2 2018-07-0 2018-04-2 2018-08-1 2019-12-3 / IT-System Specialist for R IDA / D1380 Post Open 0.00 2018-04-27 g ultant Selection ntation 2 5 9 6 3 0 1 ural Water Supply and San itation (SIASAR) IDA-SRWSSDP-IC-2018-11 / Sector Monitoring Special Institutional Strengthenin Individual Cons 2018-03-0 2018-06-1 2018-03-2 2018-07-0 2018-03-2 2018-08-0 2018-04-0 2019-12-3 ist for development and im IDA / D1380 Post Open 21,522.85 Signed 2018-04-25 g ultant Selection 2 3 9 4 9 8 2 1 plementation of Informatio n System for Rural Water Supply and Sanitation (SIA SAR) IDA-SRWSSDP-IC-2017-40 / Consultant for rehabilitati Individual Cons 2018-11-2 2018-01-2 2018-02-1 2018-03-2 2018-09-1 on of indoor sanitary facilit IDA / 59070 Sanitation Development Post Open 0.00 Canceled 2017-12-06 ultant Selection 8 4 4 1 7 ies in schools of Osh oblas t with survey, preparation of BoQ and drawings IDA-SRWSSDP-IC-2017-41 / Consultant for rehabilitati Individual Cons 2018-11-2 2018-01-2 2018-02-1 2018-03-2 2018-09-1 on of indoor sanitary facilit IDA / 59070 Sanitation Development Post Open 0.00 Canceled 2017-12-06 ultant Selection 8 4 4 1 7 ies in schools of Chuy obla st with survey, preparation of BoQ and drawings Page 5 IDA-SRWSSDP-SSS-18-6 / Under Impleme 2019-04-2 2019-02-2 2019-05-1 2019-04-2 2019-10-2 Author supervision of Kun- IDA / 59070 Water Supply Investments Post Direct Selection Direct 0.00 2019-02-11 ntation 0 1 4 7 4 Tuu, Kyzyl-Tuu, Tolok and Alekseevka subprojects IDA-SRWSSDP-IC-2018-40 / Consultant for rehabilitati on of indoor sanitary facilit Individual Cons 2019-02-1 2019-04-0 2017-12-1 2019-04-2 2017-12-2 2019-05-2 2018-01-0 2019-11-2 2018-06-0 IDA / 59070 Sanitation Development Post Open 11,354.54 Completed 2019-02-11 ies in schools and SES of C ultant Selection 3 1 1 2 5 7 4 3 3 hui, Issyk-Kul oblasts with survey, preparation of BoQ and drawings. (1st Phase) IDA-SRWSSDP-IC-2018-29 / Consultant for rehabilitati on of indoor sanitary facilit Individual Cons 2019-02-1 2019-04-0 2018-07-2 2019-04-2 2018-07-2 2019-05-2 2018-07-2 2019-11-2 2019-01-2 IDA / 59070 Sanitation Development Post Open 13,095.72 Completed 2019-02-11 ies in schools and SES of C ultant Selection 3 1 3 2 3 7 4 3 4 hui, Issyk-Kul oblasts with survey, preparation of BoQ and drawings. (2st phase) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2019-02-1 2019-04-0 2019-03-1 2019-04-2 2019-03-2 2019-05-2 2019-03-2 2020-06-3 2021-03-0 TF / A1605 Post Open 13,784.66 Completed 2019-02-11 2019-1 / Validation Consul g ultant Selection 3 1 3 2 2 7 2 0 1 tant ( # 1) IDA-SRWSSDP-DS-2018-4 / Consultants for Author su 2019-02-1 2019-02-2 2019-03-0 2019-04-2 2019-03-0 2019-10-2 2019-08-3 pervision for rehabilitation IDA / 59070 Sanitation Development Post Direct Selection Direct 5,191.15 Completed 2019-02-11 3 1 1 7 4 4 0 of indoor sanitary facilities in schools and SES of Chui, Issyk-Kul oblasts (1st pha se). IDA-SRWSSDP-IC-2018-41 / Consultant for rehabilitati on of indoor sanitary facilit Individual Cons 2019-02-1 2019-04-0 2017-12-1 2019-04-2 2017-12-2 2019-05-2 2018-01-0 2019-11-2 2018-06-0 IDA / 59070 Sanitation Development Post Open 11,487.34 Completed 2019-02-11 ies in schools and SES of O ultant Selection 3 1 1 2 5 7 4 3 3 sh oblast with survey, prep aration of BoQ and drawin gs. (1st phase) IDA-SRWSSDP-DS-2018-5 / Consultants for Author su 2019-02-1 2019-02-2 2019-05-0 2019-04-2 2019-03-0 2019-10-2 2019-08-3 pervision for rehabilitation IDA / 59070 Sanitation Development Post Direct Selection Direct 5,014.66 Completed 2019-02-11 3 1 1 7 4 4 0 of indoor sanitary facilities in schools and SES of Osh oblast (1st phase). IDA-SRWSSDP-IC-2018-30 / Consultant for rehabilitati on of indoor sanitary facilit Individual Cons 2019-02-1 2019-04-0 2018-07-1 2019-04-2 2018-07-2 2019-05-2 2018-07-2 2019-11-2 2019-01-2 IDA / 59070 Sanitation Development Post Open 17,016.71 Completed 2019-02-11 ies in schools and SES of O ultant Selection 3 1 8 2 3 7 4 3 4 sh oblast with survey, prep aration of BoQ and drawin gs. (2st phase) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2019-02-1 2019-04-0 2019-03-1 2019-04-2 2019-03-2 2019-05-2 2019-03-2 2020-06-3 2021-03-0 TF / A1605 Post Open 10,202.42 Completed 2019-02-11 2019-2 / Validation Consul g ultant Selection 3 1 3 2 2 7 3 0 2 tant ( # 2) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2019-02-1 2019-04-0 2019-03-1 2019-04-2 2019-03-2 2019-05-2 2019-03-2 2020-06-3 2021-02-0 TF / A1605 Post Open 10,202.42 Completed 2019-02-11 2019-3 / Validation Consul g ultant Selection 3 1 3 2 2 7 3 0 2 tant ( # 3) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2019-02-1 2019-04-0 2019-03-1 2019-04-2 2019-03-2 2019-05-2 2019-03-2 2020-06-3 2020-11-0 TF / A1605 Post Open 9,658.29 Completed 2019-02-11 2019-4 / Validation Consul g ultant Selection 3 1 3 2 2 7 3 0 1 tant ( # 4) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2019-02-1 2019-04-0 2019-03-1 2019-04-2 2019-03-2 2019-05-2 2019-03-2 2020-06-3 2021-03-0 TF / A1605 Post Open 9,658.29 Completed 2019-02-11 2019-5 / Validation Consul g ultant Selection 3 1 3 2 2 7 3 0 2 tant ( # 5) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2019-02-1 2019-04-0 2019-03-2 2019-04-2 2019-03-2 2019-05-2 2019-03-2 2020-06-3 2021-03-3 TF / A1605 Post Open 15,933.25 Completed 2019-02-11 2019-6 / Validation Consul g ultant Selection 3 1 2 2 2 7 2 0 1 tant ( # 6) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2019-02-1 2019-04-0 2019-03-2 2019-04-2 2019-03-2 2019-05-2 2019-03-2 2020-06-3 2021-03-3 TF / A1605 Post Open 15,933.25 Completed 2019-02-11 2019-7 / Validation Consul g ultant Selection 3 1 2 2 2 7 2 0 1 tant ( # 7) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2019-02-1 2019-04-0 2019-03-2 2019-04-2 2019-03-2 2019-05-2 2019-03-2 2020-06-3 2021-03-3 TF / A1605 Post Open 15,933.25 Completed 2019-02-11 2019-8 / Validation Consul g ultant Selection 3 1 2 2 2 7 2 0 1 tant ( # 8) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2019-02-1 2019-04-0 2019-03-2 2019-04-2 2019-03-2 2019-05-2 2019-03-2 2020-06-3 2021-03-3 TF / A1605 Post Open 15,939.04 Completed 2019-02-11 2019-9 / Validation Consul g ultant Selection 3 1 2 2 2 7 2 0 1 tant ( # 9) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2019-02-1 2019-04-0 2019-03-2 2019-04-2 2019-03-2 2019-05-2 2019-03-2 2020-06-3 2021-03-3 TF / A1605 Post Open 15,939.04 Completed 2019-02-11 2019-10 / Validation Cons g ultant Selection 3 1 2 2 2 7 2 0 1 ultant ( # 10) IDA-SRWSSDP-IC-2019-9 / Technical Supervisor for El Individual Cons 2019-02-2 2019-03-1 2019-04-0 2019-04-0 2019-04-0 2019-05-0 2019-04-1 2019-11-0 2019-06-1 IDA / 59070 Water Supply Investments Post Limited 1,679.74 Completed 2019-03-08 ectrical Installation, Pre-co ultant Selection 8 3 5 3 9 8 3 4 4 mmissioning and Electricit y Supply IDA-SRWSSDP-IC-2017-16 Individual Cons 2017-03-3 2017-11-1 2017-08-1 2017-12-1 2017-09-2 2018-01-1 2017-10-0 2018-07-1 IDA / 59070 Sanitation Development Post Open 5,050.95 Terminated 2017-10-01 / Trеiner-facilitator in Kura ultant Selection 0 9 0 0 9 4 3 3 ma IDA-SRWSSDP-IC-2019-8 / Individual Cons 2019-12-2 2019-04-0 2020-06-3 2019-04-2 2020-06-3 2019-05-3 2020-07-0 2019-11-2 IDA / 59070 Water Supply Investments Post Open 29,538.31 Signed 2019-02-15 Quality Assurance Enginee ultant Selection 5 5 0 6 0 1 1 7 r IDA-SRWSSDP-IC-2019-31 Institutional Strengthenin Individual Cons 2019-04-0 2019-04-1 2019-04-1 2019-05-0 2019-06-1 2022-06-0 / Senior Institutional Devel TF / A1605 Prior Limited 0.00 Canceled 2019-04-12 g ultant Selection 4 7 0 8 2 8 opment Advisor IDA-SRWSSDP-IC-2019-32 Individual Cons 2019-06-2 2019-04-1 2019-07-2 2019-05-0 2019-08-0 2019-06-1 2019-08-0 2019-12-0 2019-12-3 IDA / 59070 Water Supply Investments Post Limited 2,500.00 Completed 2019-04-12 / Supervision Engineer/Hy ultant Selection 0 7 9 8 6 2 6 9 1 drogeologist IDA-SRWSSDP-IC-2019-33 Individual Cons 2019-04-1 2019-04-1 2020-03-1 2019-05-0 2020-04-3 2019-06-1 2020-05-1 2020-06-0 2021-01-0 / Field technical supervisio IDA / 59070 Water Supply Investments Post Limited 7,050.02 Completed 2019-04-12 ultant Selection 0 7 6 8 0 2 1 6 1 n for Ichke-Bulun subproje ct IDA-SRWSSDP-IC-2019-34 Individual Cons 2019-04-1 2019-04-1 2019-07-0 2019-05-0 2019-07-0 2019-06-1 2019-07-2 2020-06-0 2020-01-0 / Field technical supervisio IDA / 59070 Water Supply Investments Post Limited 8,513.23 Completed 2019-04-12 ultant Selection 0 7 1 8 8 2 3 6 1 n for Korul subproject IDA-SRWSSDP-IC-2019-35 Individual Cons 2019-04-1 2019-04-1 2020-03-1 2019-05-0 2020-04-3 2019-06-1 2020-05-1 2020-06-0 2021-09-3 / Junior field technical supe IDA / 59070 Water Supply Investments Post Limited 7,944.02 Completed 2019-04-12 ultant Selection 0 7 6 8 0 2 1 6 0 rvision for Korul subproject IDA-SRWSSDP-IC-2019-36 Individual Cons 2019-04-1 2019-04-1 2019-05-0 2019-06-1 2020-06-0 / Junior field technical supe IDA / 59070 Water Supply Investments Post Limited 0.00 Canceled 2019-04-12 ultant Selection 0 7 8 2 6 rvision for Ichke-Bulun sub project IDA-SRWSSDP-IC-2019-37 / Local expert on social mo Institutional Strengthenin Individual Cons 2019-04-1 2019-04-1 2020-01-1 2019-05-0 2020-01-1 2019-06-1 2021-06-0 IDA / 59070 Post Limited 0.00 Canceled 2019-04-12 bilization and institutional g ultant Selection 0 7 0 8 3 2 1 development in Ichke-Bulu n subproject IDA-SRWSSDP-IC-2019-38 / Local expert on social mo Institutional Strengthenin Individual Cons 2019-04-1 2019-04-1 2020-01-0 2019-05-0 2020-01-1 2019-06-1 2021-06-0 IDA / 59070 Post Limited 0.00 Canceled 2019-04-12 bilization and institutional g ultant Selection 0 7 8 8 0 2 1 development in Korul subp roject IDA-SRWSSDP-IC-2019-29 / Local expert on social mo Institutional Strengthenin Individual Cons 2019-04-1 2019-04-1 2019-03-1 2019-05-0 2019-03-1 2019-06-1 2019-03-2 2021-06-0 2019-12-3 IDA / 59070 Post Limited 5,902.25 Completed 2019-04-12 bilization and institutional g ultant Selection 0 7 1 8 2 2 2 1 1 development in Chelpek s ubproject IDA-SRWSSDP-IC-2019-30 / Local expert on social mo Institutional Strengthenin Individual Cons 2019-04-1 2019-04-1 2019-03-1 2019-05-0 2019-03-1 2019-06-1 2019-03-2 2021-06-0 2019-12-3 IDA / 59070 Post Limited 5,493.86 Completed 2019-04-12 bilization and institutional g ultant Selection 0 7 1 8 2 2 2 1 1 development in Darkan su bproject IDA-SRWSSDP-IC-2019-10 Individual Cons 2019-04-1 2019-04-1 2019-03-1 2019-05-0 2019-03-2 2019-06-1 2019-03-2 2020-06-0 2019-12-3 / Field technical supervisio IDA / 59070 Water Supply Investments Post Limited 12,857.14 Completed 2019-04-12 ultant Selection 0 7 2 8 0 2 2 6 1 n for Chelpek subproject IDA-SRWSSDP-IC-2019-11 Individual Cons 2019-04-1 2019-04-1 2019-03-1 2019-05-0 2019-03-2 2019-06-1 2019-03-2 2020-06-0 2020-11-3 / Field technical supervisio IDA / 59070 Water Supply Investments Post Limited 17,420.81 Completed 2019-04-12 ultant Selection 0 7 2 8 2 2 2 6 0 n for Darkan subproject IDA-SRWSSDP-IC-2019-12 Individual Cons 2019-04-1 2019-04-1 2019-03-1 2019-05-0 2019-03-2 2019-06-1 2019-03-2 2020-06-0 2019-12-3 / Junior field technical supe IDA / 59070 Water Supply Investments Post Limited 5,560.41 Completed 2019-04-12 ultant Selection 0 7 2 8 0 2 2 6 1 rvision for Chelpek subproj ect IDA-SRWSSDP-IC-2019-13 Individual Cons 2019-04-1 2019-04-1 2019-03-1 2019-05-0 2019-03-2 2019-06-1 2019-03-2 2020-06-0 2020-10-3 / Junior field technical supe IDA / 59070 Water Supply Investments Post Limited 10,430.21 Completed 2019-04-12 ultant Selection 0 7 2 8 0 2 2 6 1 rvision for Darkan subproj ect IDA-SRWSSDP-IC-2018-15 / Consultant Development of the training manual and Individual Cons 2018-02-0 2018-02-0 2018-03-2 2018-02-2 2018-04-0 2018-04-0 2018-04-0 2018-10-0 2019-03-3 IDA / 59070 Sanitation Development Post Limited 11,670.24 Completed 2018-02-02 related materials for the R ultant Selection 8 7 2 8 2 4 2 1 1 esult-Based Sanitation Gra nts for household sanitatio n improvements IDA-SRWSSDP-SSS-19-1 / Consulting company for de 2019-08-2 2019-08-1 2019-08-2 2019-09-0 2020-01-0 sign development / adapta IDA / D1380 Water Supply Investments Post Direct Selection Direct 0.00 Canceled 2019-07-31 1 0 1 8 6 tion for rural water supply subproject Chaichy, Osh O blast IDA-SRWSSDP-IC-2019-17 Individual Cons 2019-08-2 2019-08-3 2020-01-2 2019-09-2 2020-01-3 2019-10-1 2020-02-0 2020-10-1 2020-11-0 / PR consultant for commu IDA / D1380 Sanitation Development Post Limited 8,645.58 Completed 2019-08-23 ultant Selection 3 0 8 0 0 8 4 7 1 nication strategy IDA-SRWSSDP-IC-2019-14 Individual Cons 2019-01-1 2019-01-2 2019-03-1 2019-02-1 2019-03-1 2019-03-2 2019-03-2 2019-12-1 2019-12-3 IDA / D1380 Sanitation Development Post Limited 5,822.71 Completed 2019-01-10 / Field sanitation officer in ultant Selection 4 4 4 4 5 1 2 6 1 schools #1 IDA-SRWSSDP-IC-2019-15 Individual Cons 2019-01-1 2019-01-2 2019-03-1 2019-02-1 2019-03-1 2019-03-2 2019-03-2 2019-12-1 2020-01-0 IDA / D1380 Sanitation Development Post Limited 5,822.71 Completed 2019-01-10 / Field sanitation officer in ultant Selection 4 4 4 4 5 1 3 6 1 schools #2 IDA-SRWSSDP-IC-2019-16 Individual Cons 2019-01-1 2019-01-1 2019-03-1 2019-02-0 2019-03-1 2019-03-1 2019-03-2 2019-12-0 2020-01-0 IDA / D1380 Sanitation Development Post Limited 5,822.71 Completed 2019-01-10 / Field sanitation officer in ultant Selection 4 5 4 5 5 2 3 7 1 schools #3 IDA-SRWSSDP-IC-19-17 / F Individual Cons 2019-01-1 2019-01-2 2019-03-1 2019-02-1 2019-03-1 2019-03-2 2019-03-2 2019-12-1 2020-01-0 IDA / D1380 Sanitation Development Post Limited 5,822.71 Completed 2019-01-10 ield sanitation officer in sc ultant Selection 4 4 4 4 5 1 3 6 1 hools #4 IDA-SRWSSDP-IC-2019-18 Individual Cons 2019-01-1 2019-01-2 2019-03-1 2019-02-1 2019-03-1 2019-03-2 2019-03-2 2019-12-1 2019-12-3 IDA / D1380 Sanitation Development Post Limited 5,826.72 Completed 2019-01-10 / Field sanitation officer in ultant Selection 4 4 5 4 8 1 2 6 1 schools #5 IDA-SRWSSDP-IC-2019-19 Individual Cons 2019-01-1 2019-01-1 2019-03-1 2019-02-0 2019-03-1 2019-03-1 2019-03-2 2019-12-0 2019-12-3 IDA / D1380 Sanitation Development Post Limited 5,826.72 Completed 2019-01-10 / Field sanitation officer in ultant Selection 4 7 5 7 8 4 2 9 1 schools #6 IDA-SRWSSDP-IC-2019-20 Individual Cons 2019-01-1 2019-01-2 2019-03-1 2019-02-1 2019-03-1 2019-03-2 2019-03-2 2019-12-1 2019-12-3 / Field sanitation officer in IDA / D1380 Sanitation Development Post Limited 5,823.51 Completed 2019-01-10 ultant Selection 4 4 4 4 5 1 2 6 1 communities #1 IDA-SRWSSDP-IC-2019-21 Individual Cons 2019-01-1 2019-01-2 2019-03-1 2019-02-1 2019-03-1 2019-03-2 2019-03-2 2019-12-1 2019-12-3 / Field sanitation officer in IDA / D1380 Sanitation Development Post Limited 5,823.51 Completed 2019-01-10 ultant Selection 4 4 4 4 5 1 2 6 1 communities #2 IDA-SRWSSDP-IC-2019-22 Individual Cons 2019-01-1 2019-01-2 2019-03-1 2019-02-1 2019-03-1 2019-03-2 2019-03-2 2019-12-1 2020-01-0 / Field sanitation officer in IDA / D1380 Sanitation Development Post Limited 5,823.51 Completed 2019-01-10 ultant Selection 4 4 4 4 5 1 3 6 1 communities #3 IDA-SRWSSDP-IC-2019-23 Individual Cons 2019-01-1 2019-01-2 2019-03-1 2019-02-1 2019-03-1 2019-03-2 2019-03-2 2019-12-1 2020-01-0 / Field sanitation officer in IDA / D1380 Sanitation Development Post Limited 5,823.51 Completed 2019-01-10 ultant Selection 4 4 4 4 5 1 3 6 1 communities #4 IDA-SRWSSDP-IC-2019-24 Individual Cons 2019-01-1 2019-01-2 2019-03-1 2019-02-1 2019-03-1 2019-03-2 2019-03-2 2019-12-1 2019-12-3 / Field sanitation officer in IDA / D1380 Sanitation Development Post Limited 5,822.71 Completed 2019-01-10 ultant Selection 4 4 4 4 5 1 2 6 1 communities #5 IDA-SRWSSDP-IC-2019-25 Individual Cons 2019-01-1 2019-01-2 2019-03-1 2019-02-1 2019-03-1 2019-03-2 2019-03-2 2019-12-1 2020-01-0 / Field sanitation officer in IDA / D1380 Sanitation Development Post Limited 5,823.51 Completed 2019-01-10 ultant Selection 4 4 4 4 5 1 3 6 1 communities #6 IDA-SRWSSDP-IC-2019-26 Individual Cons 2019-01-1 2019-01-2 2019-03-1 2019-02-1 2019-03-1 2019-03-2 2019-03-2 2019-12-1 2019-12-3 / Field sanitation officer in IDA / D1380 Sanitation Development Post Limited 5,826.72 Completed 2019-01-10 ultant Selection 4 4 5 4 8 1 2 6 1 communities #7 IDA-SRWSSDP-IC-2019-27 Individual Cons 2019-01-1 2019-01-2 2019-03-1 2019-02-1 2019-03-1 2019-03-2 2019-03-2 2019-12-1 2019-12-3 / Field sanitation officer in IDA / D1380 Sanitation Development Post Limited 5,826.72 Completed 2019-01-10 ultant Selection 4 4 5 4 8 1 2 6 1 communities #8 IDA-SRWSSDP-IC-2019-28 Individual Cons 2019-01-1 2019-01-2 2019-03-1 2019-02-1 2019-03-1 2019-03-2 2019-03-2 2019-12-1 2019-12-3 / Field sanitation officer in IDA / D1380 Sanitation Development Post Limited 5,826.72 Completed 2019-01-10 ultant Selection 4 4 5 4 8 1 2 6 1 communities #9 IDA-SRWSSDP-AF-IC-2019 -39 / Independent Verificat ion Agent (IVA) for Househ Individual Cons 2019-12-1 2019-12-2 2020-01-2 2020-01-1 2020-01-2 2020-02-1 2020-02-0 2021-02-1 2020-02-2 IDA / D1380 Sanitation Development Post Limited 466.07 Completed 2019-12-13 old Sanitary Facilities in Ak ultant Selection 3 3 1 3 7 7 4 6 2 -Bulak and Kotormo pilot v illages Kyrgyz-Ata subproj ect Osh Oblast Page 6 IDA-SRWSSDP-IC-INST-20 Institutional Strengthenin Individual Cons Under Impleme 2020-01-3 2020-02-2 2020-03-2 2023-04-0 20-1-RT1 / Senior Institutio TF / A1605 Post Limited 0.00 2020-01-24 g ultant Selection ntation 1 1 7 1 nal Development Advisor IDA-SRWSSDP-IC-19-10 / Individual Cons 2019-05-2 2019-01-2 2019-06-2 2019-02-1 2019-06-2 2019-03-2 2019-07-0 2020-03-2 2020-01-0 Consultant on promoting IDA / D1380 Sanitation Development Post Limited 4,535.57 Completed 2019-01-10 ultant Selection 7 4 6 4 8 1 2 0 1 WASH in schools and ISH i n communities IDA-SRWSSDP-IC-2019-18 Individual Cons 2019-06-0 2019-06-0 2019-08-2 2019-06-2 2019-08-2 2019-08-0 2019-09-0 2019-08-0 IDA / D1380 Sanitation Development Post Limited 20,413.39 Signed 2019-06-03 -AF / Sanitation Subsidy Co ultant Selection 3 8 3 9 6 3 3 6 nsultant IDA-SRWSSDP-IC-СOMP2- 2020-1 / Consultant for Tra ining of Trainers in “Active Individual Cons Under Impleme 2020-05-0 2020-02-2 2020-03-1 2020-04-1 2021-04-1 legal regulatory acts in dri IDA / D1380 Sanitation Development Post Limited 0.00 2020-02-07 ultant Selection ntation 1 1 3 7 7 nking water supply and sa nitation for strengthening the management (supervis ion) of water safety and qu ality in the Kyrgyz Republi IDA-SRWSSDP-IC-СOMP2- c” 2020-2 / Consultant for Tra Individual Cons Under Impleme 2020-05-0 2020-02-2 2020-03-1 2020-04-1 2020-05-2 IDA / D1380 Sanitation Development Post Limited 0.00 2020-02-07 ining in Water Quality Mon ultant Selection ntation 1 1 3 7 3 itoring Software in SES Rai on Offices IDA-SRWSSDP-IC-СOMP2- 2020-3 / Consultant for De Individual Cons 2020-05-0 2020-02-2 2020-05-2 2020-03-1 2020-05-2 2020-04-1 2020-06-0 2021-04-1 2021-04-0 velopment of Basic Regula IDA / D1380 Sanitation Development Post Limited 4,727.20 Completed 2020-02-07 ultant Selection 1 1 5 3 7 7 2 7 1 tory Document for Constru ction of Household Sanitati on Facilities IDA-SRWSSDP-IC-TRNG-20 20-8 / Consultant-trainers f Institutional Strengthenin Individual Cons 2020-02-1 2020-03-2 2020-06-1 2020-04-1 2020-08-0 2020-05-2 2020-08-1 2020-11-1 2022-01-0 IDA / D1380 Post Open 1,815.53 Completed 2020-02-07 or LSGB, CDWUU and othe g ultant Selection 0 7 2 7 3 2 9 8 1 r rural water services provi ders’ staff training (# 8) IDA-SRWSSDP-IC-TRNG-20 20-9 / Consultant-trainers f Institutional Strengthenin Individual Cons 2020-02-1 2020-02-1 2020-06-1 2020-03-0 2020-08-0 2020-04-0 2020-08-1 2020-10-0 2021-08-2 IDA / D1380 Post Limited 3,135.92 Completed 2020-02-07 or LSGB, CDWUU and othe g ultant Selection 0 2 2 4 3 8 9 5 0 r rural water services provi ders’ staff training (# 9) IDA-SRWSSDP-IC-TRNG-20 20-10 / Consultant-trainers Institutional Strengthenin Individual Cons 2020-02-1 2020-02-1 2020-06-1 2020-03-0 2020-08-0 2020-04-0 2020-08-1 2020-10-0 2022-01-0 IDA / D1380 Post Limited 1,815.53 Completed 2020-02-07 for LSGB, CDWUU and oth g ultant Selection 0 2 2 4 3 8 9 5 1 er rural water services pro viders’ staff training (# 10 ) IDA-SRWSSDP-IC-TRNG-20 20-11 / Consultant-trainers Institutional Strengthenin Individual Cons 2020-02-1 2020-02-2 2020-06-1 2020-03-1 2020-08-0 2020-04-1 2020-08-1 2020-10-1 2022-01-0 IDA / D1380 Post Limited 2,900.14 Completed 2020-02-07 for LSGB, CDWUU and oth g ultant Selection 0 1 2 3 3 7 9 4 1 er rural water services pro viders’ staff training (# 11 ) IDA-SRWSSDP-IC-TRNG-20 20-12 / Consultant-trainers Institutional Strengthenin Individual Cons 2020-02-1 2020-02-1 2020-06-1 2020-03-0 2020-08-0 2020-04-0 2020-08-1 2020-10-0 2022-01-0 IDA / D1380 Post Limited 3,135.92 Completed 2020-02-07 for LSGB, CDWUU and oth g ultant Selection 0 2 2 4 3 8 9 5 1 er rural water services pro viders’ staff training (# 12 ) IDA-SRWSSDP-IC-TRNG-20 20-13 / Consultant-trainers Institutional Strengthenin Individual Cons 2020-02-1 2020-02-1 2020-06-1 2020-03-0 2020-08-0 2020-04-0 2020-08-1 2020-10-0 2022-01-0 IDA / D1380 Post Limited 1,815.53 Completed 2020-02-07 for LSGB, CDWUU and oth g ultant Selection 0 2 2 4 3 8 9 5 1 er rural water services pro viders’ staff training (# 13 ) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2020-02-0 2020-03-2 2020-05-2 2020-04-1 2020-06-1 2020-05-2 2020-06-1 2021-05-2 2021-03-0 IDA / D1380 Post Open 5,969.46 Completed 2020-02-07 2020-11 / Validation Cons g ultant Selection 3 7 1 7 0 2 7 2 1 ultant ( # 11) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2020-02-0 2020-03-2 2020-05-2 2020-04-1 2020-06-1 2020-05-2 2020-06-1 2020-06-2 2021-04-0 IDA / D1380 Post Open 5,543.63 Completed 2020-02-07 2020-12 / Validation Cons g ultant Selection 3 7 1 7 0 2 7 7 1 ultant ( # 12) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2020-02-0 2020-03-2 2020-05-2 2020-04-1 2020-06-1 2020-05-2 2020-06-1 2021-05-2 2021-03-0 IDA / D1380 Post Open 5,542.48 Completed 2020-02-07 2020-13 / Validation Cons g ultant Selection 3 7 1 7 0 2 7 2 1 ultant ( # 13) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2020-02-0 2020-03-2 2020-05-2 2020-04-1 2020-06-1 2020-05-2 2020-06-1 2021-05-2 2021-01-0 IDA / D1380 Post Open 5,129.13 Completed 2020-02-07 2020-14 / Validation Cons g ultant Selection 3 7 1 7 0 2 7 2 1 ultant ( # 14) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2020-02-0 2020-03-2 2020-05-2 2020-04-1 2020-06-1 2020-05-2 2020-06-1 2020-06-2 2021-03-0 IDA / D1380 Post Open 5,541.72 Completed 2020-02-07 2020-15 / Validation Cons g ultant Selection 3 7 1 7 0 2 7 7 1 ultant ( # 15) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2020-02-0 2020-03-2 2020-05-2 2020-04-1 2020-06-1 2020-05-2 2020-06-1 2021-05-2 2021-01-0 IDA / D1380 Post Open 5,128.23 Completed 2020-02-07 2020-16 / Validation Cons g ultant Selection 3 7 1 7 0 2 7 2 1 ultant ( # 16) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2020-02-0 2020-03-2 2020-05-2 2020-04-1 2020-06-1 2020-05-2 2020-06-1 2021-05-2 2021-03-0 IDA / D1380 Post Open 5,128.23 Completed 2020-02-07 2020-17 / Validation Cons g ultant Selection 3 7 1 7 0 2 7 2 1 ultant ( # 17) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2020-02-0 2020-03-2 2020-05-2 2020-04-1 2020-06-1 2020-05-2 2020-06-1 2021-05-2 2021-04-0 IDA / D1380 Post Open 6,022.19 Completed 2020-02-07 2020-18 / Validation Cons g ultant Selection 3 7 1 7 0 2 7 2 1 ultant ( # 18) IDA-SRWSSDP-IC-SIASAR- Institutional Strengthenin Individual Cons 2020-02-0 2020-03-2 2020-05-2 2020-04-1 2020-06-1 2020-05-2 2020-06-1 2021-05-2 2021-04-0 IDA / D1380 Post Open 6,022.19 Completed 2020-02-07 2020-19 / Validation Cons g ultant Selection 3 7 1 7 0 2 7 2 1 ultant ( # 19) IDA-SRWSSDP-IC-2019-41 / Trainer on conducting tra Individual Cons 2019-09-0 2019-09-0 2019-10-1 2019-09-2 2019-10-1 2019-11-0 2019-10-1 2020-04-3 2022-01-0 IDA / D1380 Sanitation Development Post Limited 1,866.04 Completed 2019-09-02 inings for sanitation field o ultant Selection 2 7 0 8 0 2 1 0 1 fficers on WASH in Schools Methodology IDA-SRWSSDP-IC-2019-42 / Trainer on conducting tra Individual Cons 2019-09-0 2019-09-0 2019-10-1 2019-09-2 2019-10-0 2019-11-0 2019-10-1 2020-04-3 2022-01-0 inings for sanitation field o IDA / D1380 Sanitation Development Post Limited 1,866.04 Completed 2019-09-02 ultant Selection 2 7 0 8 9 2 2 0 1 fficers on Household Sanit ation Improvement Metho dology IDA-SRWSSDP-IC-FIDS-20 20-1 / Local expert on soci Institutional Strengthenin Individual Cons 2019-10-0 2019-11-1 2020-01-0 2019-12-0 2020-01-1 2020-01-1 2020-01-1 2021-01-0 IDA / D1380 Post Limited 11,950.97 Signed 2019-11-01 al mobilization and institut g ultant Selection 7 5 8 6 0 0 4 9 ional development in Sary- Tash subproject IDA-SRWSSDP-IC-FIDS-20 20-2 / Local expert on soci Institutional Strengthenin Individual Cons 2019-10-0 2019-11-1 2020-01-0 2019-12-0 2020-01-1 2020-01-1 2020-01-1 2021-01-0 IDA / D1380 Post Limited 7,304.50 Signed 2019-11-01 al mobilization and institut g ultant Selection 7 5 8 6 0 0 4 9 ional development in Achy k-Suu subproject IDA-SRWSSDP-AF-IC-FIDS- 2020-2 / Local expert on s Institutional Strengthenin Individual Cons 2019-10-0 2019-11-1 2020-01-1 2019-12-0 2020-01-1 2020-01-1 2020-01-1 2020-07-0 IDA / D1380 Post Limited 11,463.69 Signed 2019-11-01 ocial mobilization and insti g ultant Selection 7 5 0 6 2 0 7 8 tutional development in Ak -Bulak subproject IDA-SRWSSDP-AF-IC-FIDS- 2020-4 / Local expert on s Institutional Strengthenin Individual Cons 2019-10-0 2019-11-1 2020-01-1 2019-12-0 2020-01-1 2020-01-1 2020-01-1 2021-01-0 2021-10-0 IDA / D1380 Post Limited 10,050.10 Completed 2019-11-01 ocial mobilization and insti g ultant Selection 7 5 0 6 2 0 7 9 1 tutional development in Ta mga subproject IDA-SRWSSDP-IC-TS-2020 Individual Cons 2019-10-0 2019-11-1 2020-03-1 2019-12-0 2020-04-3 2020-01-1 2020-05-1 2021-01-0 2021-12-0 -3 / Field technical supervi IDA / D1380 Water Supply Investments Post Limited 12,421.67 Completed 2019-11-01 ultant Selection 7 5 6 6 0 0 2 9 1 sion engineer for Sary-Tas h subproject IDA-SRWSSDP-IC-TS-2020 Individual Cons 2019-10-0 2019-11-1 2020-03-1 2019-12-0 2020-04-3 2020-01-1 2020-05-1 2021-01-0 2021-12-0 -4 / Field technical supervi IDA / D1380 Water Supply Investments Post Limited 12,307.58 Completed 2019-11-01 ultant Selection 7 5 6 6 0 0 2 9 1 sion engineer for Achyk-Su u subproject IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2019-10-0 2019-11-1 2019-12-2 2019-12-0 2019-12-3 2020-01-1 2020-01-0 2021-01-0 2021-05-0 020-1 / Field technical sup IDA / D1380 Water Supply Investments Post Limited 11,712.22 Completed 2019-11-01 ultant Selection 7 5 7 6 0 0 1 9 1 ervision engineer for Tamg a subproject IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2019-10-0 2019-11-1 2019-12-3 2019-12-0 2020-01-2 2020-01-1 2020-02-2 2021-01-0 2021-09-0 020-2 / Field technical sup IDA / D1380 Water Supply Investments Post Limited 12,941.96 Completed 2019-11-01 ultant Selection 7 5 1 6 2 0 9 9 1 ervision engineer for Ak-B ulak subproject IDA-SRWSSDP-IC-2019-2 / Consultant-trainers for LS Institutional Strengthenin Individual Cons 2018-07-0 2019-01-0 2018-08-1 2019-01-1 2018-12-1 2019-01-3 2019-01-1 2019-07-3 2019-06-1 IDA / D1380 Post Limited 955.16 Completed 2019-01-03 GB, CDWUU and other rur g ultant Selection 2 7 0 4 0 1 6 0 6 al water services providers ’ staff training (# 2) IDA-SRWSSDP-IC-2019-6 / Consultant-trainers for LS Institutional Strengthenin Individual Cons 2018-07-0 2019-01-0 2018-08-1 2019-01-1 2018-12-1 2019-01-3 2019-01-1 2019-07-3 2019-06-1 IDA / D1380 Post Limited 567.12 Completed 2019-01-03 GB, CDWUU and other rur g ultant Selection 2 7 0 4 0 1 6 0 6 al water services providers ’ staff training (# 6) IDA-SRWSSDP-IC-2019-1 / Consultant-trainers for LS Institutional Strengthenin Individual Cons 2018-07-0 2019-01-0 2018-08-1 2019-01-1 2018-12-1 2019-01-3 2019-01-1 2019-07-3 2019-06-1 IDA / D1380 Post Limited 955.16 Completed 2019-01-03 GB, CDWUU and other rur g ultant Selection 2 7 0 4 0 1 6 0 6 al water services providers ’ staff training (# 1) IDA-SRWSSDP-IC-2019-5 / Consultant-trainers for LS Institutional Strengthenin Individual Cons 2018-07-0 2019-01-0 2018-08-1 2019-01-1 2018-12-1 2019-01-3 2019-01-1 2019-07-3 2019-06-1 IDA / D1380 Post Limited 596.98 Completed 2019-01-03 GB, CDWUU and other rur g ultant Selection 2 7 0 4 0 1 6 0 6 al water services providers ’ staff training (# 5) IDA-SRWSSDP-IC-2019-4 / Consultant-trainers for LS Institutional Strengthenin Individual Cons 2018-07-0 2019-01-0 2018-08-1 2019-01-1 2018-12-1 2019-01-3 2019-01-1 2019-07-3 2019-06-1 IDA / D1380 Post Limited 363.16 Completed 2019-01-03 GB, CDWUU and other rur g ultant Selection 2 7 0 4 0 1 6 0 6 al water services providers ’ staff training (# 4) IDA-SRWSSDP-IC-2019-3 / Consultant-trainers for LS Institutional Strengthenin Individual Cons 2018-07-0 2019-01-1 2018-08-1 2019-01-2 2018-12-1 2019-02-1 2019-01-1 2019-08-1 2019-06-1 IDA / D1380 Post Limited 567.13 Completed 2019-01-03 GB, CDWUU and other rur g ultant Selection 2 0 0 4 0 7 6 6 6 al water services providers ’ staff training (# 3) IDA-SRWSSDP-IC-2019-7 / Consultant-trainers for LS Institutional Strengthenin Individual Cons 2018-07-0 2019-01-0 2018-08-1 2019-01-1 2018-12-1 2019-01-3 2019-01-1 2019-07-3 2019-06-1 IDA / D1380 Post Limited 955.16 Completed 2019-01-03 GB, CDWUU and other rur g ultant Selection 2 7 0 4 0 1 6 0 6 al water services providers ’ staff training (# 7) IDA-SRWSSDP-CS-IC-2017 Individual Cons 2017-07-0 2017-07-2 2017-09-0 2018-02-2 -6 / Field technical supervi IDA / 59070 Water Supply Investments Post Open 0.00 Canceled 2017-05-19 ultant Selection 7 8 1 8 sion engineer in Kyrgyz At a IDA-SRWSSDP-IC-2019-31 Institutional Strengthenin Individual Cons 2020-01-0 2019-04-1 2020-03-0 2019-05-0 2020-03-0 2019-06-1 2020-03-1 2022-06-0 -2 / Senior Institutional De IDA / D1380 Post Limited 24,314.68 Signed 2019-04-12 g ultant Selection 6 7 5 8 6 2 1 8 velopment Advisor IDA-SRWSSDP-IC-2019-11 -1 / Consultant for rehabilit ation of indoor sanitary fac Individual Cons 2019-05-0 2019-06-0 2019-06-2 2019-06-2 2019-06-1 2019-08-0 2019-07-2 2020-07-3 2020-01-0 IDA / 59070 Sanitation Development Post Limited 8,703.29 Completed 2019-05-27 ilities in schools and SES o ultant Selection 1 6 0 7 8 1 0 1 1 f Chui and Osh oblasts wit h survey, preparation of B oQ and drawings. (3rd pha se) IDA-SRWSSDP-IC-2019-12 -1 / Consultant for rehabilit ation of indoor sanitary fac Individual Cons 2019-05-0 2019-06-0 2019-06-2 2019-06-2 2019-07-1 2019-08-0 2019-07-2 2020-07-3 2020-01-0 IDA / 59070 Sanitation Development Post Limited 9,191.97 Completed 2019-05-27 ilities in schools and SES o ultant Selection 1 6 0 7 9 1 0 1 1 f Chui and Issyk-Kul oblast s with survey, preparation of BoQ and drawings. (3rd phase) IDA-SRWSSDP-IC-TS-2020 Individual Cons 2020-04-0 2020-05-2 2020-05-2 2020-06-0 2020-05-2 2020-06-1 2020-06-0 2020-11-1 2021-01-0 -5 / Field technical supervi IDA / D1380 Water Supply Investments Post Open 5,057.95 Completed 2020-04-28 ultant Selection 6 4 5 3 7 5 2 5 1 sion for extra works of Kyr gyz-Ata subproject IDA-SRWSSDP-IC-2018-28 Individual Cons 2018-05-3 2018-06-1 2018-06-1 2018-07-1 2018-06-1 2018-08-1 2018-06-2 2019-08-1 2019-07-0 / Field technical supervisio IDA / D1380 Water Supply Investments Post Open 9,143.60 Completed 2018-05-01 ultant Selection 1 9 8 0 9 4 1 4 1 n engineer in Sultan (seco nd) IDA-SRWSSDP-IC-2018-25 Individual Cons 2018-04-0 2018-06-1 2018-05-2 2018-07-1 2018-06-1 2018-08-1 2018-06-2 2019-08-1 2020-07-0 / Field technical supervisio IDA / D1380 Water Supply Investments Post Open 20,378.78 Completed 2018-05-01 ultant Selection 9 9 5 0 1 4 1 4 1 n engineer in Alekseevka IDA-SRWSSDP-IC-2018-22 Individual Cons 2018-05-1 2018-06-1 2018-06-1 2018-07-1 2018-06-1 2018-08-1 2018-06-2 2019-08-1 2020-01-0 / Field technical supervisio IDA / D1380 Water Supply Investments Post Open 17,519.13 Completed 2018-05-01 ultant Selection 4 9 9 0 9 4 1 4 1 n engineer in Kun-Tuu IDA-SRWSSDP-IC-2018-23 Individual Cons 2018-05-0 2018-06-1 2018-06-1 2018-07-1 2018-06-1 2018-08-1 2018-06-2 2019-08-1 2019-10-2 / Field technical supervisio IDA / D1380 Water Supply Investments Post Open 15,490.68 Completed 2018-05-01 ultant Selection 1 9 9 0 9 4 1 4 9 n engineer in Kyzyl-Tuu IDA-SRWSSDP-IC-2018-10 Individual Cons 2017-12-0 2018-01-1 2018-01-1 2018-02-0 2018-01-1 2018-03-1 2018-01-1 2018-10-0 2018-06-0 IDA / D1380 Sanitation Development Post Open 2,721.99 Completed 2017-12-01 / Trеiner-facilitator ultant Selection 1 9 6 9 6 6 8 2 1 IDA-SRWSSDP-IC-2018-9 / Individual Cons 2017-12-0 2018-01-1 2018-01-1 2018-02-0 2018-01-1 2018-03-1 2018-01-1 2018-10-0 2018-06-0 IDA / D1380 Sanitation Development Post Open 2,721.99 Completed 2017-12-01 Trеiner-facilitator ultant Selection 1 9 6 9 6 6 8 2 1 IDA-SRWSSDP-IC-2018-8 / Individual Cons 2017-12-0 2018-01-1 2018-01-1 2018-02-0 2018-01-1 2018-03-1 2018-01-1 2018-10-0 2018-06-0 IDA / D1380 Sanitation Development Post Open 2,721.99 Completed 2017-12-01 Trеiner-facilitator ultant Selection 1 9 6 9 6 6 8 2 1 IDA-SRWSSDP-IC-2018-18 Individual Cons 2018-04-0 2018-06-1 2018-05-2 2018-07-1 2018-05-2 2018-08-1 2018-05-3 2019-08-1 2020-01-0 / Junior field technical supe IDA / D1380 Water Supply Investments Post Open 9,079.22 Completed 2018-05-01 ultant Selection 9 9 5 0 8 4 0 4 1 rvision engineer in Aleksee vka Page 7 IDA-SRWSSDP-IC-2018-33 Individual Cons 2018-05-1 2018-10-2 2018-09-2 2018-11-1 2018-09-3 2018-12-1 2018-10-0 2019-12-1 2021-01-0 / Junior field technical supe IDA / D1380 Water Supply Investments Post Open 13,230.23 Completed 2018-09-03 ultant Selection 4 2 4 2 0 7 4 7 1 rvision engineer in Kyzyl-T uu IDA-SRWSSDP-IC-2018-26 Individual Cons 2018-05-1 2018-06-1 2018-06-1 2018-07-1 2018-06-1 2018-08-1 2018-06-2 2019-08-1 / Junior field technical supe IDA / D1380 Water Supply Investments Post Open 8,759.57 Terminated 2018-05-01 ultant Selection 4 9 5 0 8 4 1 4 rvision engineer in Kun-Tu u IDA-SRWSSDP-DC-2019-2 / Consultants for Author su Individual Cons 2019-07-0 2019-06-1 2019-07-1 2019-07-0 2019-07-1 2019-08-0 2019-07-2 2020-02-0 2020-01-0 pervision for rehabilitation IDA / D1380 Sanitation Development Post Direct 2,492.73 Completed 2019-06-03 ultant Selection 1 3 2 4 9 8 0 4 1 of indoor sanitary facilities in schools and SES of Issyk -Kul oblast (2nd phase). IDA-SRWSSDP-DC-2019-1 / Consultants for Author su Individual Cons 2019-07-0 2019-06-1 2019-07-1 2019-07-0 2019-07-1 2019-08-0 2019-07-2 2020-08-0 2020-01-0 pervision for rehabilitation IDA / D1380 Sanitation Development Post Direct 2,217.47 Completed 2019-06-03 ultant Selection 1 3 2 4 9 8 0 7 1 of indoor sanitary facilities in schools and SES of Osh and Chui oblast (2nd phas e). IDA-SRWSSDP-SSS-18-7 / 2019-07-0 2019-06-1 2019-07-0 2019-08-1 2019-07-0 2020-08-1 Author supervision for WS IDA / D1380 Water Supply Investments Post Direct Selection Direct 7,859.40 Signed 2019-06-03 1 3 2 7 6 6 S sub-projects in IK oblast: Chelpek, Darkhan IDA-SRWSSDP-SSS-18-8 / 2019-06-2 2019-06-2 2019-07-0 2019-08-2 2019-07-0 2020-08-2 Author supervision for Kor IDA / D1380 Water Supply Investments Post Direct Selection Direct 5,459.77 Signed 2019-06-03 4 0 1 4 4 3 ul WSS sub-project in Oshl oblast IDA-SRWSSDP-SSS-18-9 / Author supervision for Ta 2019-12-0 2019-06-2 2019-11-0 2019-08-2 2020-01-0 2020-08-2 IDA / D1380 Water Supply Investments Post Direct Selection Direct 15,813.46 Signed 2019-06-03 mga, Ichke Bulun WSS sub 2 0 8 4 9 3 -projects in Issyk-Kul oblas t IDA-SRWSSDP-AF-IC-FIDS- 2020-3 / Local expert on s Institutional Strengthenin Individual Cons 2019-10-0 2019-11-2 2020-01-1 2019-12-1 2020-01-1 2020-01-2 2020-01-1 2021-01-1 2021-01-0 IDA / D1380 Post Open 6,347.73 Completed 2019-10-07 ocial mobilization and insti g ultant Selection 7 5 0 6 0 0 7 9 1 tutional development in Ic hke-Bulun subproject IDA-SRWSSDP-AF-IC-FIDS- 2020-1 / Local expert on s Institutional Strengthenin Individual Cons 2019-10-0 2019-11-2 2020-01-0 2019-12-1 2020-01-0 2020-01-2 2020-01-1 2021-01-1 2021-12-0 IDA / D1380 Post Open 12,641.55 Completed 2019-10-07 ocial mobilization and insti g ultant Selection 7 5 8 6 9 0 4 9 1 tutional development in Ko rul subproject IDA-SRWSSDP-IC-FSS-202 0-2 / Consultants on activit Individual Cons 2019-10-0 2019-11-2 2019-12-3 2019-12-1 2020-01-0 2020-01-2 2020-01-1 2021-01-1 2020-11-0 IDA / D1380 Sanitation Development Post Open 6,135.59 Completed 2019-10-07 ies with communities and ultant Selection 7 5 0 6 6 0 4 9 1 householders in Achyk-Suu subproject IDA-SRWSSDP-AF-IC-FSS-2 020-5 / Consultants on acti Individual Cons 2019-10-0 2019-11-2 2019-12-3 2019-12-1 2020-01-1 2020-01-2 2020-01-1 2021-01-1 2020-11-0 IDA / D1380 Sanitation Development Post Open 5,243.60 Completed 2019-10-07 vities with communities a ultant Selection 7 5 0 6 3 0 7 9 1 nd householders in Ak-Bul ak subproject IDA-SRWSSDP-AF-IC-FSS-2 020-1 / Consultants on acti Individual Cons 2019-10-0 2019-11-2 2019-12-3 2019-12-1 2020-01-0 2020-01-2 2020-01-1 2021-01-1 2020-11-0 IDA / D1380 Sanitation Development Post Open 5,334.01 Completed 2019-10-07 vities with communities a ultant Selection 7 5 0 6 6 0 4 9 1 nd householders in Korul s ubproject #1 IDA-SRWSSDP-IC-FSS-202 0-1 / Consultants on activit Individual Cons 2019-10-0 2019-11-2 2019-12-3 2019-12-1 2020-01-0 2020-01-2 2020-01-1 2021-01-1 2020-11-0 IDA / D1380 Sanitation Development Post Open 5,334.01 Completed 2019-10-07 ies with communities and ultant Selection 7 5 0 6 6 0 4 9 1 householders in Sary-Tash subproject IDA-SRWSSDP-AF-IC-FSS-2 020-2 / Consultants on acti Individual Cons 2019-10-0 2019-11-2 2019-12-3 2019-12-1 2020-01-0 2020-01-2 2020-01-1 2021-01-1 2020-11-0 IDA / D1380 Sanitation Development Post Open 5,334.01 Completed 2019-10-07 vities with communities a ultant Selection 7 5 0 6 6 0 4 9 1 nd householders in Korul s ubproject #2 IDA-SRWSSDP-AF-IC-FSS-2 020-6 / Consultants on acti Individual Cons 2019-10-0 2019-11-2 2019-12-3 2019-12-1 2020-01-2 2020-01-2 2020-01-2 2021-01-1 2020-11-0 IDA / D1380 Sanitation Development Post Open 4,881.97 Completed 2019-10-07 vities with communities a ultant Selection 7 5 0 6 0 0 8 9 1 nd householders in Ichke-B ulun subproject IDA-SRWSSDP-AF-IC-FSS-2 020-4 / Consultants on acti Individual Cons 2019-10-0 2019-11-2 2019-12-3 2019-12-1 2020-01-1 2020-01-2 2020-01-1 2021-01-1 2020-11-0 IDA / D1380 Sanitation Development Post Open 5,243.60 Completed 2019-10-07 vities with communities a ultant Selection 7 5 0 6 3 0 7 9 1 nd householders in Tamga subproject IDA-SRWSSDP-AF-IC-FSS-2 020-3 / Consultants on acti Individual Cons 2019-10-0 2019-11-2 2019-12-3 2019-12-1 2020-01-1 2020-01-2 2020-01-2 2021-01-1 2020-11-0 IDA / D1380 Sanitation Development Post Open 4,894.69 Completed 2019-10-07 vities with communities a ultant Selection 7 5 0 6 3 0 8 9 1 nd householders in Korul s ubproject #3 IDA-SRWSSDP-IC-2018-21 / Local expert on social mo Institutional Strengthenin Individual Cons 2018-05-2 2018-07-0 2018-06-1 2018-07-3 2018-06-1 2018-09-0 2018-06-1 2019-09-0 2020-01-0 IDA / D1380 Post Open 10,027.78 Completed 2018-05-21 bilization and institutional g ultant Selection 1 9 4 0 5 3 9 3 1 development Kun-Tuu sub project IDA-SRWSSDP-IC-2018-16 / Local expert on social mo Institutional Strengthenin Individual Cons 2018-04-0 2018-05-2 2018-04-3 2018-06-1 2018-05-1 2018-07-2 2018-05-2 2019-07-2 2020-01-0 IDA / D1380 Post Open 10,505.29 Completed 2018-04-09 bilization and institutional g ultant Selection 9 8 0 8 5 3 3 3 1 development Kyrgyz-Ata s ubproject ARIS-IDA-SRWSSDP-IC-20 18-24 / Local expert on so Institutional Strengthenin Individual Cons Under Impleme 2018-06-0 2018-07-2 2018-06-2 2018-08-1 2018-06-2 2018-09-1 2019-09-1 IDA / D1380 Post Open 0.00 2018-06-04 cial mobilization and instit g ultant Selection ntation 4 3 0 3 0 7 7 utional development Kura ma subproject IDA-SRWSSDP-IC-2018-19 / Local expert on social mo Institutional Strengthenin Individual Cons 2018-04-0 2018-05-2 2018-05-1 2018-06-1 2018-05-2 2018-07-2 2018-06-0 2019-07-2 2020-01-0 IDA / D1380 Post Open 10,278.83 Completed 2018-04-09 bilization and institutional g ultant Selection 9 8 6 8 8 3 6 3 1 development Alekseevka s ubproject IDA-SRWSSDP-IC-2018-20 / Local expert on social mo Institutional Strengthenin Individual Cons 2018-04-0 2018-05-2 2018-05-1 2018-06-1 2018-06-1 2018-07-2 2018-06-2 2019-07-2 2020-01-0 IDA / D1380 Post Open 9,789.36 Completed 2018-04-09 bilization and institutional g ultant Selection 9 8 6 8 1 3 1 3 1 development Tolok subpro ject IDA-SRWSSDP-IC-COMP2- 2020-4 / Consultant for the development of instruction Individual Cons 2020-06-0 2020-07-2 2020-09-0 2020-08-1 2020-09-1 2020-09-1 2020-09-2 2021-03-1 2020-10-1 on preventing the spread IDA / D1380 Sanitation Development Post Open 712.80 Completed 2020-06-02 ultant Selection 5 1 1 1 5 5 3 4 3 of COVID-19 virus for a wid e range of people working with the population after q uarantine (for field activist s) IDA-SRWSSDP-IC-COMP2- 2020-5 / Consultant for the Individual Cons 2020-06-0 2020-07-2 2020-07-1 2020-08-1 2020-08-1 2020-09-1 2020-08-2 2021-03-1 2020-09-2 development of informatio IDA / D1380 Sanitation Development Post Open 709.46 Completed 2020-06-02 ultant Selection 5 1 7 1 4 5 1 4 2 n-educational materials to prevent the spread of COV ID-19 virus in the Kyrgyz R epublic IDA-SRWSSDP-IC-COMP2- 2020-6 / Consultant for the development of designs fo Individual Cons 2020-06-0 2020-07-2 2020-07-1 2020-08-1 2020-08-0 2020-09-1 2020-08-1 2021-03-1 2020-10-3 IDA / D1380 Sanitation Development Post Open 712.80 Completed 2020-06-02 r information-educational ultant Selection 5 1 7 1 3 5 1 4 1 materials to prevent the s pread of COVID-19 virus in the Kyrgyz Republic (first) IDA-SRWSSDP-IC-COMP2- 2020-7 / Consultant for the development of designs fo Individual Cons 2020-06-0 2020-07-2 2020-08-1 2020-09-1 2021-03-1 IDA / D1380 Sanitation Development Post Open 0.00 Canceled 2020-06-02 r information-educational ultant Selection 5 1 1 5 4 materials to prevent the s pread of COVID-19 virus in the Kyrgyz Republic (seco nd) ARIS-IDA-SRWSSDP-SSS-1 8-8 / Preparation/revisiono Under Impleme 2019-08-2 2020-06-1 2020-08-1 2021-02-1 IDA / D1380 Water Supply Investments Post Direct Selection Direct 0.00 2020-06-02 f detailed designs for Chai ntation 1 2 6 2 chi WSS sub-project in Osh oblast IDA-SRWSSDP-HO-IC-2018 Institutional Strengthenin Individual Cons 2017-11-3 2018-01-1 2017-12-2 2018-02-0 2017-12-2 2018-03-1 2017-12-3 2019-03-1 2019-01-0 IDA / D1380 Post Open 17,969.04 Completed 2017-11-27 -5 / Institutional specialist g ultant Selection 0 5 0 5 5 2 1 2 1 IDA-SRWSSDP-IC-2018-17 Individual Cons 2018-04-0 2018-05-2 2018-05-2 2018-06-1 2018-05-2 2018-07-1 2018-05-3 2019-07-1 2019-08-0 / Junior field technical supe IDA / D1380 Water Supply Investments Post Open 6,274.04 Completed 2018-04-02 ultant Selection 9 1 5 1 8 6 0 6 1 rvision engineer in Tolok ARIS-IDA-SRWSSDP-IC-18- Individual Cons 2018-04-0 2018-06-1 2018-05-2 2018-07-1 2018-06-0 2018-08-1 2018-06-2 2019-08-1 2019-01-0 IDA / D1380 Water Supply Investments Post Open 6,220.79 Completed 2018-05-01 7 / Infrastructure engineer ultant Selection 9 9 5 0 4 4 0 4 1 HO 3 ARIS-IDA-SRWSSDP-IC-20 Individual Cons 2019-01-2 2019-05-2 2019-04-1 2019-06-1 2019-05-0 2019-07-1 2019-05-1 2020-07-1 2020-01-0 IDA / D1380 Water Supply Investments Post Open 10,420.39 Completed 2019-04-01 19-12 / Infrastructure engi ultant Selection 1 0 9 0 6 5 4 4 1 neer HO 4 ARIS-IDA-SRWSSDP-IC-20 Individual Cons 2019-01-2 2019-05-2 2019-04-1 2019-06-1 2019-05-0 2019-07-1 2019-05-1 2020-07-1 2020-01-0 IDA / D1380 Water Supply Investments Post Open 7,547.97 Completed 2019-04-01 19-11 / Infrastructure engi ultant Selection 1 0 9 0 6 5 4 4 1 neer HO 5 IDA-SRWSSDP-IC-2018-24 Individual Cons 2018-04-0 2018-06-1 2018-05-2 2018-07-1 2018-06-1 2018-08-1 2018-06-2 2019-02-1 2019-08-0 / Field technical supervisio IDA / D1380 Water Supply Investments Post Open 9,814.16 Completed 2018-05-01 ultant Selection 9 9 5 0 1 4 1 0 1 n engineer in Tolok IDA-SRWSSDP-AF-IC-FSS-2 020-7 / Consultants on acti Individual Cons 2020-02-0 2020-02-1 2020-05-2 2020-03-1 2020-05-2 2020-04-1 2020-06-0 2021-04-1 2021-05-0 IDA / D1380 Sanitation Development Post Open 5,186.84 Completed 2020-01-01 vities with communities a ultant Selection 3 9 1 1 7 5 2 5 1 nd householders in Shalta subproject IDA-SRWSSDP-AF-IC-FSS-2 020-8 / Consultants on acti Individual Cons 2020-02-0 2020-02-1 2020-05-2 2020-03-1 2020-05-2 2020-04-1 2020-06-0 2021-04-1 2021-03-0 IDA / D1380 Sanitation Development Post Open 4,976.25 Completed 2020-01-01 vities with communities a ultant Selection 3 9 1 1 7 5 2 5 1 nd householders in Belek s ubproject IDA-SRWSSDP-AF-IC-FIDS- 2020-7 / Local expert on s Institutional Strengthenin Individual Cons 2020-02-0 2020-02-1 2020-07-2 2020-03-1 2020-07-2 2020-04-1 2020-08-0 2021-04-1 IDA / D1380 Post Open 12,181.31 Signed 2020-01-01 ocial mobilization and insti g ultant Selection 3 9 7 1 9 5 4 5 tutional development in Sh alta subproject IDA-SRWSSDP-AF-IC-FIDS- 2020-6 / Local expert on s Institutional Strengthenin Individual Cons 2020-02-0 2020-02-1 2020-07-2 2020-03-1 2020-07-2 2020-04-1 2020-08-0 2021-04-1 IDA / D1380 Post Open 12,156.27 Signed 2020-01-01 ocial mobilization and insti g ultant Selection 3 9 7 1 9 5 4 5 tutional development in B elek subproject IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2020-05-0 2020-06-2 2020-06-0 2020-07-1 2020-06-1 2020-08-1 2020-07-0 2021-08-1 2021-07-0 020-5 / Field technical sup IDA / D1380 Water Supply Investments Post Open 9,300.17 Completed 2020-05-05 ultant Selection 1 3 8 4 5 8 2 8 1 ervision engineer in Shalta IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2020-05-0 2020-06-2 2020-06-0 2020-07-1 2020-06-1 2020-08-1 2020-06-2 2021-08-1 2021-07-0 020-6 / Field technical sup IDA / D1380 Water Supply Investments Post Open 9,575.06 Completed 2020-05-05 ultant Selection 1 3 8 4 5 8 3 8 1 ervision engineer in Belek IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2020-05-0 2020-06-2 2020-07-2 2020-07-1 2020-07-3 2020-08-1 2020-08-0 2021-08-1 2021-10-0 020-7 / Field technical sup IDA / D1380 Water Supply Investments Post Open 10,180.60 Completed 2020-05-05 ultant Selection 5 3 8 4 0 8 4 8 1 ervision engineer in Chon- Daly IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2020-08-0 2020-06-2 2020-11-1 2020-07-1 2020-11-2 2020-08-1 2020-12-0 2021-08-1 2021-12-0 020-8 / Field technical sup IDA / D1380 Water Supply Investments Post Open 8,216.10 Completed 2020-05-05 ultant Selection 3 3 6 4 5 8 2 8 1 ervision engineer in Kenes h IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2020-07-0 2020-06-2 2020-08-2 2020-07-1 2020-08-2 2020-08-1 2020-09-0 2021-08-1 2021-11-0 020-9 / Field technical sup IDA / D1380 Water Supply Investments Post Open 9,579.26 Completed 2020-05-05 ultant Selection 1 3 5 4 7 8 2 8 1 ervision engineer in Kara- Dobo IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2020-06-1 2020-06-2 2020-07-2 2020-07-1 2020-07-2 2020-08-1 2020-08-0 2021-08-1 020-10 / Field technical su IDA / D1380 Water Supply Investments Post Open 15,756.59 Signed 2020-05-05 ultant Selection 5 3 7 4 9 8 4 8 pervision engineer in Chai chi IDA-SRWSSDP-CS-SSS-20 Under Impleme 2020-05-1 2020-05-2 2020-06-0 2020-12-0 20-3 / Author supervision f IDA / 59070 Water Supply Investments Post Direct Selection Direct 0.00 2020-05-18 ntation 5 3 5 4 or Ak-Bulak WSS sub-proje ct in Issyk-Kul oblast IDA-SRWSSDP-CS-SSS-20 20-1 / Author supervision f Under Impleme 2020-04-0 2020-04-1 2020-04-1 2020-04-2 2021-02-2 IDA / D1380 Water Supply Investments Post Direct Selection Direct 0.00 2020-04-01 or Sary-Tash, Achyk-Suu W ntation 1 1 6 8 8 SS sub-projects in Osh obl ast IDA-SRWSSDP-CS-SSS-20 20-2 / Author supervision f Under Impleme 2020-05-1 2020-05-2 2020-06-0 2020-10-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 0.00 2020-05-18 or extra works Kyrgyz-Ata ntation 5 3 5 3 WSS sub-project in Osh obl ast IDA-SRWSSDP-SSS-COMP 3-2020-1 / Company for re Institutional Strengthenin Under Impleme 2020-09-0 2020-06-2 2020-09-0 2021-09-0 view and Improvement of IDA / D1380 Post Direct Selection Direct 0.00 2020-06-18 g ntation 3 8 1 1 Design and Construction S tandards and Regulations f or Water Supply and Sanit ation Sector Page 8 IDA-SRWSSDP-SIASAR-SS S-2020-2 / Server Support Consultant for the Depart Institutional Strengthenin Under Impleme 2020-06-1 2020-06-2 2020-08-1 2021-03-0 ment of Development of D IDA / D1380 Post Direct Selection Direct 0.00 2020-06-18 g ntation 9 8 1 9 rinking Water Supply and Wastewater Disposal of St ate Water Resources Agen cy under the Government of Kyrgyz Republic IDA-SRWSSDP-IC-FIDS-20 20-7 / Local expert in socia Institutional Strengthenin 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 2020-07-0 IDA / D1380 Post Direct Selection Direct 3,083.76 Completed 2019-12-23 l mobilization and instituti g 3 2 7 7 1 7 1 onal development sub-proj ect Sultan IDA-SRWSSDP-IC-FIDS-20 20-4 / Local expert in socia Institutional Strengthenin 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 2020-07-0 IDA / D1380 Post Direct Selection Direct 3,083.76 Completed 2019-12-23 l mobilization and instituti g 3 2 7 7 1 7 1 onal development under t he project in kun-Tuu IDA-SRWSSDP-IC-TS-2020 2019-12-3 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 -2 / Field technical supervi IDA / D1380 Water Supply Investments Post Direct Selection Direct 14,376.10 Signed 2019-12-23 1 2 5 7 1 7 sion engineer Korul ARIS-IDA-SRWSSDP-HO-1 Institutional Strengthenin 2018-12-2 2019-01-0 2018-12-2 2019-03-0 2019-01-0 2020-03-0 2020-01-0 IDA / D1380 Post Direct Selection Direct 19,863.82 Completed 2018-12-23 9-10 / Institutional speciali g 4 2 7 8 1 7 1 st IDA-SRWSSDP-IC-2020-3 / Institutional Strengthenin 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 IDA / D1380 Post Direct Selection Direct 34,786.48 Signed 2019-12-23 Institutional specialist g 3 2 6 7 1 7 IDA-SRWSSDP-HO-IC-18-6 2017-12-2 2018-01-0 2017-12-2 2018-03-0 2017-12-3 2019-03-0 2019-01-0 IDA / D1380 Sanitation Development Post Direct Selection Direct 17,082.54 Completed 2017-12-23 / Sanitation and hygene sp 5 2 6 8 1 8 1 ecialist ARIS-IDA-SRWSSDP-HO-1 2018-12-2 2019-01-0 2018-12-2 2019-03-0 2019-01-0 2020-03-0 2020-01-0 IDA / D1380 Sanitation Development Post Direct Selection Direct 20,824.36 Completed 2018-12-23 9-11 / Sanitation and hyge 4 2 6 8 1 7 1 ne specialist IDA-SRWSSDP-IC-2020-4 / 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 IDA / D1380 Sanitation Development Post Direct Selection Direct 36,731.93 Signed 2019-12-23 Sanitation and hygene spe 3 2 7 7 1 7 cialist IDA-SRWSSDP-IC-FIDS-20 20-10 / Local expert on so Institutional Strengthenin 2019-12-2 2020-01-0 2019-12-2 2020-02-1 2020-01-0 2021-02-1 2020-07-0 IDA / D1380 Post Direct Selection Direct 2,843.36 Completed 2019-12-23 cial mobilization and instit g 3 2 7 1 1 0 1 utional development in Ch elpek subproject IDA-SRWSSDP-AF-IC-2020 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 2021-01-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 12,144.79 Completed 2019-12-23 -1 / Infrastructure enginee 3 2 5 7 1 7 1 r HO 5 ARIS-IDA-SRWSSDP-IC-HO 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 -AF-2020-13 / Infrastructur IDA / D1380 Water Supply Investments Post Direct Selection Direct 12,831.68 Signed 2019-12-23 3 2 6 7 1 7 e engineer HO 4 IDA-SRWSSDP-AF-IC-2020 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 -6 / Consultant on promoti IDA / D1380 Sanitation Development Post Direct Selection Direct 26,518.06 Signed 2019-12-23 3 2 7 7 1 7 ng WASH in schools and IS H in communities IDA-SRWSSDP-IC-2020-8 / Pending Imple 2020-01-0 2020-03-0 2021-03-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 0.00 2019-12-23 Electrical and mechanical mentation 2 7 7 engineer IDA-SRWSSDP-IC-FIDS-20 20-3 / Local expert on soci Institutional Strengthenin 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 2021-01-0 IDA / D1380 Post Direct Selection Direct 6,881.40 Completed 2019-12-23 al mobilization and institut g 3 2 7 7 1 7 1 ional development Kun-Tu u subproject IDA-SRWSSDP-IC-FIDS-20 20-6 / Local expert on soci Institutional Strengthenin 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 2020-07-0 IDA / D1380 Post Direct Selection Direct 3,083.76 Completed 2019-12-23 al mobilization and institut g 3 2 7 7 1 7 1 ional development Tolok s ubproject IDA-SRWSSDP-IC-FIDS-20 20-5 / Local expert on soci Institutional Strengthenin 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 2020-10-0 IDA / D1380 Post Direct Selection Direct 5,233.52 Completed 2019-12-23 al mobilization and institut g 3 2 7 7 1 7 1 ional development Aleksee vka IDA-SRWSSDP-IC-FIDS-20 20-11 / Local expert on so Institutional Strengthenin 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 2021-01-0 IDA / D1380 Post Direct Selection Direct 6,894.55 Completed 2019-12-23 cial mobilization and instit g 3 2 7 7 1 7 1 utional development in Da rkan subproject IDA-SRWSSDP-IC-2020-9 / 2019-12-2 2020-01-0 2020-03-0 2021-03-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 0.00 Under Review 2019-12-23 Supervision Engineer/Hydr 3 2 7 7 ogeologist IDA-SRWSSDP-IC-FIDS-20 2O-8 / Local expert in soci Institutional Strengthenin Under Impleme 2019-12-2 2020-01-0 2020-03-0 2021-03-0 IDA / D1380 Post Direct Selection Direct 0.00 2019-12-23 al mobilization and institut g ntation 3 2 7 7 ional development sub-pro ject Sultan IDA-SRWSSDP-HO-IC-18-8 2017-12-2 2018-01-0 2017-12-2 2018-03-0 2017-12-3 2019-03-0 2019-01-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 18,425.07 Completed 2017-12-23 / Infrastructure engineer 5 2 6 8 1 8 1 ARIS-IDA-SRWSSDP-HO-1 2018-12-2 2019-01-0 2018-12-2 2019-03-0 2019-01-0 2020-03-0 2020-01-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 18,177.15 Completed 2018-12-23 9-7 / Infrastructure engine 4 2 5 8 1 7 1 er ARIS-IDA-SRWSSDP-HO-2 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 2021-01-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 11,881.19 Completed 2019-12-23 020-8 / Infrastructure engi 3 2 6 7 1 7 1 neer ARIS-IDA-SRWSSDP-HO-1 2018-12-2 2019-01-0 2018-12-2 2019-03-0 2019-01-0 2020-03-0 2020-01-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 17,252.28 Completed 2018-12-23 9-9 / Infrastructure engine 4 2 6 8 1 7 1 er HO 3 ARIS-IDA-SRWSSDP-HO-2 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 2021-01-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 10,100.73 Completed 2019-12-23 020-7 / Infrastructure engi 3 2 5 7 1 7 1 neer HO 3 IDA-SRWSSDP-IC-FIDS-20 20-12 / Local expert in soci Institutional Strengthenin 2019-12-3 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 2020-07-0 IDA / D1380 Post Direct Selection Direct 3,576.74 Completed 2019-12-23 al mobilization and institut g 1 2 7 7 1 7 1 ional development sub-pro ject Kyrgyz-Ata IDA-SRWSSDP-IC-2018-7 / Individual Cons 2018-01-0 2018-02-1 2018-01-1 2018-03-0 2018-02-2 2018-04-0 2018-01-1 2019-04-0 2018-03-0 IDA / D1380 Water Supply Investments Post Open 4,419.96 Completed 2017-12-23 Infrastructure engineer as ultant Selection 8 0 7 3 6 7 9 7 1 sistant ARIS-IDA-SRWSSDP-IC-20 2018-02-0 2018-01-0 2018-02-1 2018-03-0 2018-03-0 2019-03-0 2019-01-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 11,049.90 Completed 2017-12-23 18-13 / Infrastructure engi 5 2 9 8 2 8 1 neer assistant ARIS-IDA-SRWSSDP-HO-1 2018-12-2 2019-01-0 2018-12-2 2019-03-0 2019-01-0 2020-03-0 2020-01-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 12,559.95 Completed 2018-12-23 9-8 / Infrastructure engine 4 2 5 8 1 7 1 er assistant IDA-SRWSSDP-IC-2020-2 / 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 17,115.06 Signed 2019-12-23 Infrastructure engineer as 3 2 6 7 1 7 sistant ARIS-IDA-SRWSSDP-HO-2 Individual Cons Under Impleme 2018-01-0 2018-02-1 2018-03-0 2018-04-0 2019-04-0 IDA / D1380 Water Supply Investments Post Open 0.00 2017-12-23 018-14 / Assistant of safeg ultant Selection ntation 1 0 3 7 7 uards specialist ARIS-IDA-SRWSSDP-HO-1 2018-12-2 2019-01-0 2018-12-2 2019-03-0 2019-01-0 2020-03-0 2020-01-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 5,443.94 Completed 2018-12-23 9-5 / Assistant of safeguar 4 2 5 8 1 7 1 ds specialist IDA-SRWSSDP-IC-2020-5 / 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 IDA / D1380 Water Supply Investments Post Direct Selection Direct 14,680.58 Signed 2019-12-23 Assistant of safeguards sp 3 2 7 7 1 7 ecialist IDA-SRWSSDP-IC-2020-7 / Sector Monitoring Speciali Institutional Strengthenin 2019-12-2 2020-01-0 2019-12-3 2020-03-0 2020-01-0 2021-03-0 st for development and im IDA / D1380 Post Direct Selection Direct 25,342.72 Signed 2019-12-23 g 3 2 0 7 1 7 plementation of Informatio n System for Rural Water Supply and Sanitation (SIA SAR) IDA-SRWSSDP-IC-2020-12 / Web Developer Specialist Institutional Strengthenin 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 IDA / D1380 Post Direct Selection Direct 31,207.05 Signed 2019-12-23 Information System for Ru g 3 2 7 7 1 7 ral Water Supply and Sanit ation (SIASAR) IDA-SRWSSDP-IC-FIDS-20 20-8 / Local expert in socia Institutional Strengthenin 2019-12-2 2020-01-0 2019-12-2 2020-03-0 2020-01-0 2021-03-0 2020-07-0 IDA / D1380 Post Direct Selection Direct 3,136.19 Completed 2019-12-23 l mobilization and instituti g 3 2 5 7 1 7 1 onal development sub-proj ect Sultan IDA-SRWSSDP-IC-2O19-12 / Web Developer Specialist Institutional Strengthenin 2018-12-2 2019-01-0 2018-12-2 2019-03-0 2019-01-0 2020-03-0 2020-01-0 IDA / D1380 Post Direct Selection Direct 13,728.66 Completed 2018-12-23 Information System for Ru g 7 2 8 8 1 7 1 ral Water Supply and Sanit ation (SIASAR) IDA-SRWSSDP-AF-IC-FSS-2 020-9 / Consultants on acti Individual Cons 2020-06-0 2020-04-1 2020-07-2 2020-05-1 2020-07-3 2020-06-1 2020-08-0 2021-06-1 2021-05-0 IDA / 59070 Sanitation Development Post Open 4,251.63 Completed 2020-03-01 vities with communities an ultant Selection 8 9 7 0 0 4 4 4 1 d householders in Chon-Da ly subproject IDA-SRWSSDP-AF-IC-FSS-2 020-10 / Consultants on ac Individual Cons 2020-06-2 2020-04-1 2020-07-2 2020-05-1 2020-07-3 2020-06-1 2020-08-0 2021-06-1 2021-05-0 IDA / 59070 Sanitation Development Post Open 4,251.62 Completed 2020-03-01 tivities with communities a ultant Selection 9 9 8 0 0 4 4 4 1 nd householders in Chaichi subproject IDA-SRWSSDP-AF-IC-FSS-2 020-11 / Consultants on ac Individual Cons 2020-06-0 2020-04-1 2020-07-2 2020-05-1 2020-07-3 2020-06-1 2020-08-0 2021-06-1 2021-03-0 IDA / 59070 Sanitation Development Post Open 4,251.63 Completed 2020-03-01 tivities with communities a ultant Selection 8 9 7 0 0 4 4 4 2 nd householders in Kenesh subproject IDA-SRWSSDP-AF-IC-FSS-2 020-12 / Consultants on ac Individual Cons 2020-06-0 2020-04-1 2020-07-2 2020-05-1 2020-07-3 2020-06-1 2020-08-0 2021-06-1 2021-05-0 IDA / 59070 Sanitation Development Post Open 4,251.63 Completed 2020-03-01 tivities with communities a ultant Selection 8 9 7 0 0 4 4 4 1 nd householders in Kara-D obo subproject IDA-SRWSSDP-AF-IC-FSS-2 020-13 / Consultants on ac Individual Cons 2021-03-2 2020-04-1 2021-06-2 2020-05-1 2021-06-3 2020-06-1 2021-07-0 2021-06-1 IDA / D2040 Sanitation Development Post Open 4,243.92 Signed 2020-03-01 tivities with communities a ultant Selection 1 9 8 0 0 4 2 4 nd householders in Kenesh subproject Osh oblast IDA-SRWSSDP-AF-IC-FSS-2 020-14 / Consultants on ac Individual Cons 2021-03-2 2020-04-1 2021-06-2 2020-05-1 2021-06-3 2020-06-1 2021-07-0 2021-06-1 IDA / 59070 Sanitation Development Post Open 4,243.92 Signed 2020-03-01 tivities with communities a ultant Selection 1 9 8 0 0 4 2 4 nd householders in Por su bproject IDA-SRWSSDP-AF-IC-FIDS- 2020-8 / Local expert on s Institutional Strengthenin Individual Cons 2020-06-2 2020-04-1 2020-07-2 2020-05-1 2020-07-3 2020-06-1 2020-08-0 2021-06-1 2021-01-0 IDA / 59070 Post Open 2,357.87 Completed 2020-03-01 ocial mobilization and insti g ultant Selection 2 9 7 0 1 4 4 4 1 tutional development in C hon-Daly subproject IDA-SRWSSDP-AF-IC-FIDS- 2020-9 / Local expert on s Institutional Strengthenin Individual Cons 2020-06-2 2020-04-1 2020-07-2 2020-05-1 2020-07-3 2020-06-1 2020-08-0 2021-06-1 2022-01-0 IDA / 59070 Post Open 5,187.32 Completed 2020-03-01 ocial mobilization and insti g ultant Selection 2 9 7 0 1 4 4 4 1 tutional development in C haichi subproject IDA-SRWSSDP-AF-IC-FIDS- 2020-10 / Local expert on Institutional Strengthenin Individual Cons 2020-06-2 2020-04-1 2020-07-2 2020-05-1 2020-07-3 2020-06-1 2020-08-0 2021-06-1 IDA / 59070 Post Open 8,423.40 Signed 2020-03-01 social mobilization and ins g ultant Selection 2 9 7 0 1 4 4 4 titutional development in Kenesh subproject IDA-SRWSSDP-AF-IC-FIDS- 2020-11 / Local expert on Institutional Strengthenin Individual Cons 2020-03-0 2020-04-1 2020-07-2 2020-05-1 2020-07-3 2020-06-1 2020-08-0 2021-06-1 IDA / 59070 Post Open 11,978.28 Signed 2020-03-01 social mobilization and ins g ultant Selection 9 9 9 0 1 4 4 4 titutional development in Kara-Dobo subproject IDA-SRWSSDP-AF-IC-FIDS- 2020-12 / Local expert on Institutional Strengthenin Individual Cons 2021-03-0 2020-04-1 2021-04-2 2020-05-1 2021-04-2 2020-06-1 2021-05-0 2021-06-1 IDA / 59070 Post Open 6,601.92 Signed 2020-03-01 social mobilization and ins g ultant Selection 1 9 0 0 6 4 1 4 titutional development in Kenesh subproject Osh obl ast IDA-SRWSSDP-AF-IC-FIDS- 2020-13 / Local expert on Institutional Strengthenin Individual Cons 2021-03-0 2020-04-1 2021-05-2 2020-05-1 2021-06-0 2020-06-1 2021-06-0 2021-06-1 IDA / 59070 Post Open 6,044.60 Signed 2020-03-01 social mobilization and ins g ultant Selection 1 9 0 0 3 4 8 4 titutional development in P or subproject IDA-SRWSSDP-SIASAR-SS S-2020-1 / Programmer Co nsultant for the Departme Institutional Strengthenin 2020-06-1 2020-06-2 2020-08-1 2020-11-0 nt of Development of Drin IDA / D1380 Post Direct Selection Direct 0.00 Canceled 2020-06-18 g 9 8 1 9 king Water Supply and Wa stewater Disposal of State Water Resources Agency u nder the Government of K yrgyz Republic IDA-SRWSSDP-SIASAR-SS S-2020-1/2 / Programmer Consultant for the Depart Institutional Strengthenin 2020-11-0 2020-11-1 2020-11-0 2021-01-0 2020-11-1 2021-04-0 ment of Development of D IDA / D1380 Post Direct Selection Direct 2,475.87 Signed 2020-11-09 g 8 9 9 2 3 2 rinking Water Supply and Wastewater Disposal of St ate Water Resources Agen cy under the Government of Kyrgyz Republic Page 9 IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2021-03-2 2021-04-1 2021-06-2 2021-05-1 2021-06-2 2021-06-1 2021-07-0 2022-06-1 021-1 / Field technical sup IDA / 60880 Water Supply Investments Post Open 8,204.92 Signed 2021-03-01 ultant Selection 1 9 8 0 9 4 2 4 ervision engineer in Kara-Ji gach Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2023-03-3 2022-05-0 2023-05-1 2022-05-2 2023-05-1 2022-06-2 2023-06-2 022-1 / Field technical sup IDA / 60880 Water Supply Investments Post Open 0.00 Signed 2022-03-15 ultant Selection 1 3 1 4 8 8 8 ervision engineer in Kayrm a Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Pending Imple 2022-05-0 2022-05-2 2022-06-2 2023-06-2 022-2 / Field technical sup IDA / 60880 Water Supply Investments Post Open 0.00 2022-03-15 ultant Selection mentation 3 4 8 8 ervision engineer in Vasile v Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Pending Imple 2021-12-2 2022-01-1 2022-02-1 2023-02-1 021-2 / Field technical sup IDA / 60880 Water Supply Investments Post Open 0.00 2021-11-01 ultant Selection mentation 0 0 4 4 ervision engineer in Koms omolskoe Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Under Impleme 2023-03-3 2021-12-2 2022-01-1 2022-02-1 2023-02-1 021-3 / Field technical sup IDA / 60880 Water Supply Investments Post Open 0.00 2021-11-01 ultant Selection ntation 1 0 0 4 4 ervision engineer in Bokso -Jol Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2022-02-2 2021-12-2 2022-04-1 2022-01-1 2022-04-2 2022-02-1 2023-02-1 021-4 / Field technical sup IDA / 60880 Water Supply Investments Post Open 0.00 Signed 2021-11-01 ultant Selection 1 0 9 0 5 4 4 ervision engineer in Sosno vka Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2021-03-2 2021-04-1 2021-07-2 2021-05-1 2021-07-2 2021-06-1 2021-08-0 2022-06-1 021-5 / Field technical sup IDA / 60880 Water Supply Investments Post Open 7,521.18 Signed 2021-03-01 ultant Selection 9 9 6 0 8 4 2 4 ervision engineer in Ivanov ka station Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Under Impleme 2023-03-3 2022-05-0 2023-05-1 2022-05-2 2023-05-1 2022-06-2 2023-06-2 022-3 / Field technical sup IDA / 60880 Water Supply Investments Post Open 0.00 2022-03-15 ultant Selection ntation 1 3 1 4 8 8 8 ervision engineer in Kurpul dok Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Under Impleme 2023-03-3 2022-05-0 2022-05-2 2022-06-2 2023-06-2 022-4 / Field technical sup IDA / 60880 Water Supply Investments Post Open 0.00 2022-03-15 ultant Selection ntation 1 3 4 8 8 ervision engineer in Kum-A ryk Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Under Impleme 2023-03-3 2022-05-0 2023-05-1 2022-05-2 2023-05-1 2022-06-2 2023-06-2 022-5 / Field technical sup IDA / 60880 Water Supply Investments Post Open 0.00 2022-03-15 ultant Selection ntation 1 3 1 4 8 8 8 ervision engineer in Orto-A ryk Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2022-02-0 2021-12-2 2022-02-1 2022-01-1 2022-02-2 2022-02-1 2023-02-1 021-6 / Field technical sup IDA / 60880 Water Supply Investments Post Open 0.00 Signed 2021-11-01 ultant Selection 7 0 7 0 3 4 4 ervision engineer in Kaind y Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2021-05-2 2021-12-2 2021-11-1 2022-01-1 2021-11-2 2022-02-1 2021-11-3 2023-02-1 021-7 / Field technical sup IDA / 60880 Water Supply Investments Post Open 4,786.20 Signed 2021-11-01 ultant Selection 6 0 6 0 5 4 0 4 ervision engineer in Borold oi Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2023-04-0 2021-12-2 2022-07-2 2022-01-1 2022-08-0 2022-02-1 2022-08-1 2022-03-2 021-8 / Field technical sup IDA / 60880 Water Supply Investments Post Open 1,827.70 Signed 2021-11-01 ultant Selection 6 0 7 0 9 4 0 2 ervision engineer in Bulolu u Osh oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2021-12-2 2022-01-1 2022-02-1 2023-02-1 021-9 / Field technical sup IDA / 60880 Water Supply Investments Post Open 0.00 Canceled 2021-11-01 ultant Selection 0 0 4 4 ervision engineer in Toloik on Osh oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2022-06-2 2021-12-2 2022-07-2 2022-01-1 2022-08-0 2022-02-1 2022-08-1 2023-02-1 021-10 / Field technical su IDA / 60880 Water Supply Investments Post Open 1,827.70 Signed 2021-11-01 ultant Selection 7 0 7 0 9 4 0 4 pervision engineer in Erkin -Too Osh oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Under Impleme 2023-03-3 2021-12-2 2023-05-0 2022-01-1 2023-05-1 2022-02-1 2023-02-1 021-11 / Field technical su IDA / 60880 Water Supply Investments Post Open 0.00 2021-11-01 ultant Selection ntation 1 0 3 0 1 4 4 pervision engineer in Kyzyl -Bairak Osh oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2022-03-0 2021-12-2 2022-04-1 2022-01-1 2022-04-2 2022-02-1 2023-02-1 021-12 / Field technical su IDA / 60880 Water Supply Investments Post Open 0.00 Signed 2021-11-01 ultant Selection 1 0 9 0 5 4 4 pervision engineer in Kaby k Osh oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Under Impleme 2022-06-2 2021-12-2 2022-10-1 2022-01-1 2022-10-2 2022-02-1 2023-02-1 021-13 / Field technical su IDA / 60880 Water Supply Investments Post Open 0.00 2021-11-01 ultant Selection ntation 7 0 9 0 4 4 4 pervision engineer in Ench ilesh Issyk-Kul oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Pending Imple 2021-09-1 2021-10-1 2021-11-1 2022-11-1 021-14 / Field technical su IDA / 60880 Water Supply Investments Post Open 0.00 2021-08-01 ultant Selection mentation 9 0 4 4 pervision engineer in Jeti- Oguz Issyk-Kul oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2021-03-0 2021-09-1 2021-05-2 2021-10-1 2021-05-2 2021-11-1 2021-06-0 2022-11-1 021-15 / Field technical su IDA / 60880 Water Supply Investments Post Open 8,888.81 Signed 2021-08-01 ultant Selection 2 9 6 0 8 4 2 4 pervision engineer in Boz- Beshik Issyk-Kul oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2022-04-2 2021-12-2 2022-06-2 2022-01-1 2022-07-0 2022-02-1 2022-07-1 2023-02-1 021-16 / Field technical su IDA / 60880 Water Supply Investments Post Open 729.05 Signed 2021-11-01 ultant Selection 6 0 9 0 1 4 0 4 pervision engineer in Barb ulak Issyk-Kul oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Pending Imple 2021-12-2 2022-01-1 2022-02-1 2023-02-1 021-17 / Field technical su IDA / 60880 Water Supply Investments Post Open 0.00 2021-11-01 ultant Selection mentation 0 0 4 4 pervision engineer in Kurm ontu Issyk-Kul oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Pending Imple 2021-10-2 2021-11-1 2021-12-1 2022-12-1 021-18 / Field technical su IDA / 60880 Water Supply Investments Post Open 0.00 2021-09-01 ultant Selection mentation 0 0 5 5 pervision engineer in Kichi -Oruktuu Issyk-Kul oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Under Impleme 2023-03-3 2021-10-2 2023-05-0 2021-11-1 2023-05-0 2021-12-1 2022-12-1 021-19 / Field technical su IDA / 60880 Water Supply Investments Post Open 0.00 2021-09-01 ultant Selection ntation 1 0 2 0 3 5 5 pervision engineer in Jyluu -Bulak Issyk-Kul oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2021-07-2 2021-08-1 2021-09-1 2022-09-1 021-20 / Field technical su IDA / 60880 Water Supply Investments Post Open 0.00 Canceled 2021-06-01 ultant Selection 0 0 4 4 pervision engineer in Grig orevka Issyk-Kul oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Pending Imple 2021-07-2 2021-08-1 2021-09-1 2022-09-1 021-21 / Field technical su IDA / 60880 Water Supply Investments Post Open 0.00 2021-06-01 ultant Selection mentation 0 0 4 4 pervision engineer in Karo ol-Dobo Issyk-Kul oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2020-08-1 2020-09-2 2020-12-2 2020-10-1 2020-12-2 2020-11-2 2021-01-0 2021-11-2 020-11 / Field technical su IDA / 60880 Water Supply Investments Post Open 13,172.42 Signed 2020-08-10 ultant Selection 0 8 1 9 5 3 1 3 pervision engineer in Gorn aya Maevka Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2021-03-2 2021-02-2 2021-02-2 2021-03-2 2021-02-2 2021-04-2 2021-03-0 2022-04-2 021-22 / Field technical su IDA / 60880 Water Supply Investments Post Open 10,940.10 Signed 2021-01-10 ultant Selection 9 8 4 1 5 5 2 5 pervision engineer in Beis heke Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2021-03-0 2021-03-3 2021-05-2 2021-04-2 2021-05-2 2021-05-2 2021-06-0 2022-05-2 2022-01-0 021-23 / Field technical su IDA / 60880 Water Supply Investments Post Open 4,786.35 Completed 2021-02-10 ultant Selection 2 1 4 1 8 6 2 6 1 pervision engineer in Ken- Bulun Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 021-1 / Consultants on acti Individual Cons 2021-03-2 2021-04-1 2021-04-2 2021-05-1 2021-04-2 2021-06-1 2021-05-0 2022-03-1 IDA / 60880 Sanitation Development Post Open 6,183.07 Signed 2021-03-01 vities with communities an ultant Selection 1 9 7 0 9 4 1 5 d householders in Kara-Jig ach Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 022-1 / Consultants on acti Individual Cons Under Impleme 2023-03-0 2022-05-0 2023-06-1 2022-05-2 2023-06-1 2022-06-2 2023-03-2 IDA / 60880 Sanitation Development Post Open 0.00 2022-03-15 vities with communities an ultant Selection ntation 6 3 2 4 9 8 9 d householders in Kayrma Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 022-2 / Consultants on acti Individual Cons Pending Imple 2022-05-0 2022-05-2 2022-06-2 2023-03-2 IDA / 60880 Sanitation Development Post Open 0.00 2022-03-15 vities with communities an ultant Selection mentation 3 4 8 9 d householders in Vasilev Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 021-2 / Consultants on acti Individual Cons Pending Imple 2021-12-2 2022-01-1 2022-02-1 2022-11-1 IDA / 60880 Sanitation Development Post Open 0.00 2021-11-01 vities with communities an ultant Selection mentation 0 0 4 5 d householders in Komsom olskoe Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 021-3 / Consultants on acti Individual Cons Pending Imple 2021-12-2 2022-01-1 2022-02-1 2022-11-1 IDA / 60880 Sanitation Development Post Open 0.00 2021-11-01 vities with communities an ultant Selection mentation 0 0 4 5 d householders in Bokso-Jo l Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 021-4 / Consultants on acti Individual Cons 2022-02-1 2021-12-2 2022-04-2 2022-01-1 2022-04-2 2022-02-1 2022-11-1 IDA / 60880 Sanitation Development Post Open 0.00 Signed 2021-11-01 vities with communities an ultant Selection 8 0 0 0 5 4 5 d householders in Sosnovk a Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 021-5 / Consultants on acti Individual Cons 2021-03-2 2021-04-1 2021-04-2 2021-05-1 2021-04-2 2021-06-1 2021-05-0 2022-03-1 2022-01-0 IDA / 60880 Sanitation Development Post Open 4,244.22 Completed 2021-03-01 vities with communities an ultant Selection 1 9 7 0 9 4 1 5 1 d householders in Ivanovk a station Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 022-3 / Consultants on acti Individual Cons Under Impleme 2023-03-0 2022-05-0 2022-05-2 2022-06-2 2023-03-2 IDA / 60880 Sanitation Development Post Open 0.00 2022-03-15 vities with communities an ultant Selection ntation 6 3 4 8 9 d householders in Kurpuld ok Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 022-4 / Consultants on acti Individual Cons 2022-05-0 2022-05-2 2022-06-2 2023-03-2 IDA / 60880 Sanitation Development Post Open 0.00 Canceled 2022-03-15 vities with communities an ultant Selection 3 4 8 9 d householders in Kum-Ary k Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 022-5 / Consultants on acti Individual Cons Under Impleme 2023-03-0 2022-05-0 2022-05-2 2022-06-2 2023-03-2 IDA / 60880 Sanitation Development Post Open 0.00 2022-03-15 vities with communities an ultant Selection ntation 6 3 4 8 9 d householders in Orto-Ary k Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 021-6 / Consultants on acti Individual Cons 2022-02-2 2021-12-2 2022-04-2 2022-01-1 2022-04-2 2022-02-1 2022-11-1 IDA / 60880 Sanitation Development Post Open 0.00 Signed 2021-11-01 vities with communities an ultant Selection 1 0 0 0 5 4 5 d householders in Kaindy Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 021-7 / Consultants on acti Individual Cons 2021-06-0 2021-12-2 2021-08-2 2022-01-1 2021-08-2 2022-02-1 2021-09-0 2022-11-1 IDA / 60880 Sanitation Development Post Open 4,244.01 Signed 2021-11-01 vities with communities an ultant Selection 1 0 5 0 5 4 2 5 d householders in Boroldoi Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 021-8 / Consultants on acti Individual Cons 2022-06-2 2021-12-2 2022-07-2 2022-01-1 2022-08-0 2022-02-1 2022-08-1 2022-11-1 IDA / 60880 Sanitation Development Post Open 1,267.09 Signed 2021-11-01 vities with communities an ultant Selection 7 0 7 0 9 4 8 5 d householders in Buloluu Osh oblast IDA-SRWSSDP-AF-IC-FSS-2 021-9 / Consultants on acti Individual Cons Under Impleme 2023-03-0 2021-12-2 2023-06-1 2022-01-1 2023-06-1 2022-02-1 2022-11-1 IDA / 60880 Sanitation Development Post Open 0.00 2021-11-01 vities with communities an ultant Selection ntation 6 0 2 0 9 4 5 d householders in Toloikon Osh oblast IDA-SRWSSDP-AF-IC-FSS-2 021-10 / Consultants on ac Individual Cons 2022-06-2 2021-12-2 2022-07-2 2022-01-1 2022-08-0 2022-02-1 2022-08-1 2022-11-1 IDA / 60880 Sanitation Development Post Open 1,260.48 Signed 2021-11-01 tivities with communities a ultant Selection 7 0 7 0 9 4 0 5 nd householders in Erkin-T oo Osh oblast IDA-SRWSSDP-AF-IC-FSS-2 021-11 / Consultants on ac Individual Cons Under Impleme 2023-03-0 2021-12-2 2023-06-1 2022-01-1 2023-06-1 2022-02-1 2022-11-1 IDA / 60880 Sanitation Development Post Open 0.00 2021-11-01 tivities with communities a ultant Selection ntation 6 0 2 0 9 4 5 nd householders in Kyzyl-B airak Osh oblast IDA-SRWSSDP-AF-IC-FSS-2 021-12 / Consultants on ac Individual Cons Under Impleme 2022-03-0 2021-12-2 2022-04-1 2022-01-1 2022-04-2 2022-02-1 2022-11-1 IDA / 60880 Sanitation Development Post Open 0.00 2021-11-01 tivities with communities a ultant Selection ntation 1 0 5 0 5 4 5 nd householders in Kabyk Osh oblast IDA-SRWSSDP-AF-IC-FSS-2 021-13 / Consultants on ac Individual Cons 2022-06-2 2021-12-2 2022-09-3 2022-01-1 2022-10-0 2022-02-1 2022-11-1 IDA / 60880 Sanitation Development Post Open 0.00 Signed 2021-11-01 tivities with communities a ultant Selection 7 0 0 0 5 4 5 nd householders in Enchile sh Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FSS-2 021-14 / Consultants on ac Individual Cons 2021-03-2 2021-09-1 2021-05-3 2021-10-1 2021-06-0 2021-11-1 2021-06-0 2022-08-1 2022-03-0 IDA / 60880 Sanitation Development Post Open 4,158.27 Completed 2021-08-01 tivities with communities a ultant Selection 1 9 1 0 3 4 8 5 1 nd householders in Jeti-Og uz Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FSS-2 021-15 / Consultants on ac Individual Cons 2021-03-2 2021-09-1 2021-05-3 2021-10-1 2021-06-0 2021-11-1 2021-06-0 2022-08-1 2022-03-0 IDA / 60880 Sanitation Development Post Open 4,158.27 Completed 2021-08-01 tivities with communities a ultant Selection 1 9 1 0 3 4 8 5 1 nd householders in Boz-Be shik Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FSS-2 021-16 / Consultants on ac Individual Cons 2022-04-2 2021-12-2 2022-06-0 2022-01-1 2022-06-0 2022-02-1 2022-06-0 2022-11-1 IDA / 60880 Sanitation Development Post Open 3,360.56 Signed 2021-11-01 tivities with communities a ultant Selection 6 0 6 0 6 4 8 5 nd householders in Barbul ak Issyk-Kul oblast Page 10 IDA-SRWSSDP-AF-IC-FSS-2 021-17 / Consultants on ac Individual Cons 2021-12-2 2022-01-1 2022-02-1 2022-11-1 IDA / 60880 Sanitation Development Post Open 0.00 Canceled 2021-11-01 tivities with communities a ultant Selection 0 0 4 5 nd householders in Kurmo ntu Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FSS-2 021-18 / Consultants on ac Individual Cons 2021-10-2 2021-11-1 2021-12-1 2022-09-1 IDA / 60880 Sanitation Development Post Open 0.00 Canceled 2021-09-01 tivities with communities a ultant Selection 0 0 5 5 nd householders in Kichi-O ruktuu Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FSS-2 021-19 / Consultants on ac Individual Cons 2022-06-2 2021-10-2 2022-09-3 2021-11-1 2022-10-0 2021-12-1 2022-09-1 IDA / 60880 Sanitation Development Post Open 0.00 Signed 2021-09-01 tivities with communities a ultant Selection 7 0 0 0 5 5 5 nd householders in Jyluu-B ulak Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FSS-2 021-20 / Consultants on ac Individual Cons Under Impleme 2023-03-0 2021-07-2 2021-08-1 2021-09-1 2022-06-1 IDA / 60880 Sanitation Development Post Open 0.00 2021-06-01 tivities with communities a ultant Selection ntation 6 0 0 4 5 nd householders in Grigor evka Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FSS-2 021-21 / Consultants on ac Individual Cons 2021-07-2 2021-08-1 2021-09-1 2022-06-1 IDA / 60880 Sanitation Development Post Open 0.00 Canceled 2021-06-01 tivities with communities a ultant Selection 0 0 4 5 nd householders in Karool- Dobo Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FSS-2 020-15 / Consultants on ac Individual Cons 2021-03-2 2020-09-2 2021-04-2 2020-10-1 2021-04-2 2020-11-2 2021-05-0 2021-08-2 IDA / 60880 Sanitation Development Post Open 6,167.20 Signed 2020-08-10 tivities with communities a ultant Selection 9 8 7 9 9 3 1 4 nd householders in Gornay a Maevka Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 021-22 / Consultants on ac Individual Cons 2021-03-2 2021-02-2 2021-04-2 2021-03-2 2021-04-2 2021-04-2 2021-05-0 2022-01-2 2022-02-0 IDA / 60880 Sanitation Development Post Open 4,244.12 Completed 2021-01-10 tivities with communities a ultant Selection 1 8 7 1 9 5 1 4 1 nd householders in Beishe ke Chui oblast IDA-SRWSSDP-AF-IC-FSS-2 021-23 / Consultants on ac Individual Cons 2021-03-2 2021-03-3 2021-04-2 2021-04-2 2021-04-2 2021-05-2 2021-05-0 2022-02-2 IDA / 60880 Sanitation Development Post Open 2,692.96 Terminated 2021-02-10 tivities with communities a ultant Selection 1 1 7 1 9 6 1 4 nd householders in Ken-Bu lun Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-1 / Local expert on s Institutional Strengthenin Individual Cons 2021-03-0 2021-04-1 2021-04-2 2021-05-1 2021-04-2 2021-06-1 2021-05-0 2022-06-1 IDA / 60880 Post Open 6,601.92 Signed 2021-03-01 ocial mobilization and insti g ultant Selection 1 9 0 0 6 4 1 4 tutional development in Ka ra-Jigach Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2022-1 / Local expert on s Institutional Strengthenin Individual Cons Under Impleme 2023-03-1 2022-05-0 2022-05-2 2022-06-2 2023-06-2 IDA / 60880 Post Open 0.00 2022-03-15 ocial mobilization and insti g ultant Selection ntation 3 3 4 8 8 tutional development in Ka yrma Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2022-2 / Local expert on s Institutional Strengthenin Individual Cons Pending Imple 2022-05-0 2022-05-2 2022-06-2 2023-06-2 IDA / 60880 Post Open 0.00 2022-03-15 ocial mobilization and insti g ultant Selection mentation 3 4 8 8 tutional development in V asilev Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-2 / Local expert on s Institutional Strengthenin Individual Cons Pending Imple 2021-12-2 2022-01-1 2022-02-1 2023-02-1 IDA / 60880 Post Open 0.00 2021-11-01 ocial mobilization and insti g ultant Selection mentation 0 0 4 4 tutional development in Ko msomolskoe Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-3 / Local expert on s Institutional Strengthenin Individual Cons Pending Imple 2021-12-2 2022-01-1 2022-02-1 2023-02-1 IDA / 60880 Post Open 0.00 2021-11-01 ocial mobilization and insti g ultant Selection mentation 0 0 4 4 tutional development in B okso-Jol Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-4 / Local expert on s Institutional Strengthenin Individual Cons 2022-02-1 2021-12-2 2022-04-1 2022-01-1 2022-04-2 2022-02-1 2023-02-1 IDA / 60880 Post Open 0.00 Signed 2021-11-01 ocial mobilization and insti g ultant Selection 8 0 8 0 5 4 4 tutional development in So snovka Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-5 / Local expert on s Institutional Strengthenin Individual Cons 2021-03-0 2021-04-1 2021-04-1 2021-05-1 2021-04-1 2021-06-1 2021-04-2 2022-06-1 IDA / 60880 Post Open 6,826.51 Signed 2021-03-01 ocial mobilization and insti g ultant Selection 1 9 6 0 9 4 0 4 tutional development in Iv anovka station Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2022-3 / Local expert on s Institutional Strengthenin Individual Cons 2023-03-1 2022-05-0 2023-06-0 2022-05-2 2023-06-0 2022-06-2 2023-06-2 IDA / 60880 Post Open 0.00 Signed 2022-03-15 ocial mobilization and insti g ultant Selection 3 3 6 4 7 8 8 tutional development in K urpuldok Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2022-4 / Local expert on s Institutional Strengthenin Individual Cons Pending Imple 2022-05-0 2022-05-2 2022-06-2 2023-06-2 IDA / 60880 Post Open 0.00 2022-03-15 ocial mobilization and insti g ultant Selection mentation 3 4 8 8 tutional development in K um-Aryk Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2022-5 / Local expert on s Institutional Strengthenin Individual Cons 2023-03-1 2022-05-0 2023-06-0 2022-05-2 2023-06-0 2022-06-2 2023-06-2 IDA / 60880 Post Open 0.00 Signed 2022-03-15 ocial mobilization and insti g ultant Selection 3 3 6 4 7 8 8 tutional development in Or to-Aryk Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-6 / Local expert on s Institutional Strengthenin Individual Cons 2022-01-0 2021-12-2 2022-03-2 2022-01-1 2022-03-3 2022-02-1 2023-02-1 IDA / 60880 Post Open 0.00 Signed 2021-11-01 ocial mobilization and insti g ultant Selection 5 0 9 0 1 4 4 tutional development in Ka indy Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-7 / Local expert on s Institutional Strengthenin Individual Cons 2021-05-2 2021-12-2 2021-08-2 2022-01-1 2021-08-2 2022-02-1 2021-09-0 2023-02-1 IDA / 60880 Post Open 2,263.50 Signed 2021-11-01 ocial mobilization and insti g ultant Selection 4 0 7 0 7 4 2 4 tutional development in B oroldoi Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-8 / Local expert on s Institutional Strengthenin Individual Cons 2022-06-2 2021-12-2 2022-07-2 2022-01-1 2022-08-0 2022-02-1 2022-08-1 2023-02-1 IDA / 60880 Post Open 1,267.09 Signed 2021-11-01 ocial mobilization and insti g ultant Selection 7 0 7 0 9 4 0 4 tutional development in B uloluu Osh oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-9 / Local expert on s Institutional Strengthenin Individual Cons Under Impleme 2023-03-1 2021-12-2 2023-06-0 2022-01-1 2023-06-0 2022-02-1 2023-02-1 IDA / 60880 Post Open 0.00 2021-11-01 ocial mobilization and insti g ultant Selection ntation 3 0 6 0 7 4 4 tutional development in To loikon Osh oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-10 / Local expert on Institutional Strengthenin Individual Cons 2022-06-2 2021-12-2 2022-07-2 2022-01-1 2022-08-0 2022-02-1 2022-08-1 2023-02-1 IDA / 60880 Post Open 1,260.48 Signed 2021-11-01 social mobilization and ins g ultant Selection 7 0 7 0 9 4 9 4 titutional development in Erkin-Too Osh oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-11 / Local expert on Institutional Strengthenin Individual Cons 2023-03-1 2021-12-2 2023-06-0 2022-01-1 2023-06-0 2022-02-1 2023-02-1 IDA / 60880 Post Open 0.00 Signed 2021-11-01 social mobilization and ins g ultant Selection 3 0 6 0 7 4 4 titutional development in Kyzyl-Bairak Osh oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-12 / Local expert on Institutional Strengthenin Individual Cons 2022-03-0 2021-12-2 2022-04-1 2022-01-1 2022-04-2 2022-02-1 2023-02-1 IDA / 60880 Post Open 0.00 Signed 2021-11-01 social mobilization and ins g ultant Selection 1 0 8 0 5 4 4 titutional development in Kabyk Osh oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-13 / Local expert on Institutional Strengthenin Individual Cons 2022-06-2 2021-12-2 2022-09-2 2022-01-1 2022-10-0 2022-02-1 2023-02-1 IDA / 60880 Post Open 0.00 Signed 2021-11-01 social mobilization and ins g ultant Selection 7 0 0 0 3 4 4 titutional development in Enchilesh Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-14 / Local expert on Institutional Strengthenin Individual Cons 2021-03-0 2021-09-1 2021-05-2 2021-10-1 2021-05-2 2021-11-1 2021-06-0 2022-11-1 IDA / 60880 Post Open 7,253.53 Signed 2021-08-01 social mobilization and ins g ultant Selection 1 9 0 0 5 4 8 4 titutional development in J eti-Oguz Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-15 / Local expert on Institutional Strengthenin Individual Cons 2021-03-0 2021-09-1 2021-05-2 2021-10-1 2021-05-2 2021-11-1 2021-06-0 2022-11-1 IDA / 60880 Post Open 6,951.30 Signed 2021-08-01 social mobilization and ins g ultant Selection 1 9 0 0 5 4 8 4 titutional development in Boz-Beshik Issyk-Kul oblas t IDA-SRWSSDP-AF-IC-FIDS- 2021-16 / Local expert on Institutional Strengthenin Individual Cons 2022-04-2 2021-12-2 2022-06-0 2022-01-1 2022-06-0 2022-02-1 2022-06-0 2023-02-1 IDA / 60880 Post Open 3,360.56 Signed 2021-11-01 social mobilization and ins g ultant Selection 6 0 6 0 6 4 8 4 titutional development in Barbulak Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-17 / Local expert on Institutional Strengthenin Individual Cons Pending Imple 2021-12-2 2022-01-1 2022-02-1 2023-02-1 IDA / 60880 Post Open 0.00 2021-11-01 social mobilization and ins g ultant Selection mentation 0 0 4 4 titutional development in Kurmontu Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-18 / Local expert on Institutional Strengthenin Individual Cons Pending Imple 2021-10-2 2021-11-1 2021-12-1 2022-12-1 IDA / 60880 Post Open 0.00 2021-09-01 social mobilization and ins g ultant Selection mentation 0 0 5 5 titutional development in Kichi-Oruktuu Issyk-Kul obl ast IDA-SRWSSDP-AF-IC-FIDS- 2021-19 / Local expert on Institutional Strengthenin Individual Cons 2022-06-2 2021-10-2 2022-10-0 2021-11-1 2022-10-1 2021-12-1 2022-12-1 IDA / 60880 Post Open 0.00 Signed 2021-09-01 social mobilization and ins g ultant Selection 7 0 1 0 2 5 5 titutional development in J yluu-Bulak Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-20 / Local expert on Institutional Strengthenin Individual Cons 2023-03-1 2021-07-2 2023-06-0 2021-08-1 2023-06-0 2021-09-1 2022-09-1 IDA / 60880 Post Open 0.00 Signed 2021-06-01 social mobilization and ins g ultant Selection 3 0 6 0 7 4 4 titutional development in Grigorevka Issyk-Kul oblas t IDA-SRWSSDP-AF-IC-FIDS- 2021-21 / Local expert on Institutional Strengthenin Individual Cons Pending Imple 2021-07-2 2021-08-1 2021-09-1 2022-09-1 IDA / 60880 Post Open 0.00 2021-06-01 social mobilization and ins g ultant Selection mentation 0 0 4 4 titutional development in Karool-Dobo Issyk-Kul obla st IDA-SRWSSDP-AF-IC-FIDS- 2020-14 / Local expert on Institutional Strengthenin Individual Cons 2021-03-0 2020-09-2 2021-04-2 2020-10-1 2021-04-2 2020-11-2 2021-05-0 2021-11-2 IDA / 60880 Post Open 6,602.55 Signed 2020-08-10 social mobilization and ins g ultant Selection 2 8 0 9 6 3 1 3 titutional development in Gornaya Maevka Chui obla st IDA-SRWSSDP-AF-IC-FIDS- 2021-22 / Local expert on Institutional Strengthenin Individual Cons 2021-03-0 2021-02-2 2021-04-1 2021-03-2 2021-04-1 2021-04-2 2021-04-2 2022-04-2 IDA / 60880 Post Open 3,997.23 Signed 2021-01-10 social mobilization and ins g ultant Selection 1 8 6 1 6 5 0 5 titutional development in Beisheke Chui oblast IDA-SRWSSDP-AF-IC-FIDS- 2021-23 / Local expert on Institutional Strengthenin Individual Cons 2021-03-0 2021-03-3 2021-04-1 2021-04-2 2021-04-1 2021-05-2 2021-04-2 2022-05-2 IDA / 60880 Post Open 6,826.51 Signed 2021-02-10 social mobilization and ins g ultant Selection 1 1 6 1 9 6 0 6 titutional development in Ken-Bulun Chui oblast IDA-SRWSSDP-IC-TRNG-20 20-14 / Consultant-trainers Institutional Strengthenin Individual Cons 2020-02-1 2020-03-0 2020-04-0 2020-10-0 IDA / D1380 Post Limited 0.00 Canceled 2020-02-07 for LSGB, CDWUU and oth g ultant Selection 2 4 8 5 er rural water services pro viders’ staff training (# 14 ) IDA-SRWSSDP-CS-SSS-20 2022-11-0 2021-06-1 2021-08-1 2022-08-1 21-2 / Author supervision f IDA / 60880 Water Supply Investments Post Direct Selection Direct 0.00 Under Review 2021-06-01 8 1 5 5 or 5 WSS sub-projects in O sh oblast (2 Phase) IDA-SRWSSDP-CS-SSS-20 21-1 / Author supervision f Pending Imple 2021-04-1 2021-06-1 2022-06-1 IDA / 60880 Water Supply Investments Post Direct Selection Direct 0.00 2021-04-01 or 4 WSS sub-projects in Is mentation 1 5 5 syk-Kul oblast (1 Phase) IDA-SRWSSDP-CS-SSS-20 21-3 / Author supervision f Under Impleme 2022-10-1 2021-11-1 2022-01-1 2023-01-1 IDA / 60880 Water Supply Investments Post Direct Selection Direct 0.00 2021-11-01 or 5 WSS sub-projects in Is ntation 9 1 5 5 syk-Kul oblast (2 Phase) IDA-SRWSSDP-CS-SSS-20 Pending Imple 2020-12-1 2021-02-1 2022-02-1 20-5 / Author supervision f IDA / 60880 Water Supply Investments Post Direct Selection Direct 0.00 2020-12-01 mentation 1 4 4 or 4 WSS sub-projects in O sh oblast (1 Phase) IDA-SRWSSDP-CS-SSS-20 Pending Imple 2020-08-2 2020-10-3 2021-10-3 20-4 / Author supervision f IDA / 60880 Water Supply Investments Post Direct Selection Direct 0.00 2020-08-17 mentation 7 1 1 or 10 WSS sub-projects in Chui oblast (1 Phase) IDA-SRWSSDP-CS-SSS-20 Pending Imple 2021-11-1 2022-01-1 2023-01-1 21-4 / Author supervision f IDA / 60880 Water Supply Investments Post Direct Selection Direct 0.00 2021-11-01 mentation 1 5 5 or 5 WSS sub-projects in C hui oblast (3 Phase) IDA-SRWSSDP-CS-SSS-20 Under Impleme 2023-03-2 2021-11-1 2022-01-1 2023-01-1 21-5 / Author supervision f IDA / 60880 Water Supply Investments Post Direct Selection Direct 0.00 2021-11-01 ntation 8 1 5 5 or 5 WSS sub-projects in C hui oblast (2 Phase) IDA-SRWSSDP-AF-IC-EIA-2 021 / Consultant for Engin eering, Environmental and Individual Cons 2021-02-2 2021-02-2 2021-03-0 2021-03-0 2021-04-1 Sanitary Safety Review (as IDA / D2040 Water Supply Investments Post Open 0.00 Canceled 2021-02-03 ultant Selection 4 7 2 6 0 sess and forecast the impa ct of the water supply proj ect and prepared designs on utilities, environmental and sanitary safety) Page 11 IDA-SRWSSDP-AF-IC-FSS-2 020-2-RT1 / Consultants o Individual Cons 2020-05-0 2020-06-1 2020-06-1 2020-07-1 2020-06-1 2020-08-1 2020-06-2 2021-02-1 2020-11-0 IDA / 60880 Sanitation Development Post Open 2,061.39 Completed 2020-05-01 n activities with communiti ultant Selection 1 9 5 0 8 4 0 0 1 es and householders in Ko rul subproject #2 IDA-SRWSSDP-IC-COMP2- 2020-5/1 / Consultant for t he development of inform Individual Cons 2020-06-0 2020-07-2 2020-07-1 2020-08-1 2020-08-1 2020-09-2 2020-08-2 2021-03-2 2020-09-2 IDA / 60880 Sanitation Development Post Open 709.46 Completed 2020-06-09 ation-educational material ultant Selection 5 8 7 8 4 2 1 1 2 s to prevent the spread of COVID-19 virus in the Kyrg yz Republic (second) IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2020-08-0 2020-09-1 2020-11-1 2020-10-1 2020-11-2 2020-11-1 2020-12-0 2021-11-0 2022-01-0 020-13 / Field technical su IDA / 60880 Water Supply Investments Post Open 8,229.75 Completed 2020-08-01 ultant Selection 1 9 7 0 5 4 2 9 1 pervision engineer in Por Osh oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2020-08-0 2020-09-1 2020-11-1 2020-10-1 2020-11-2 2020-11-1 2020-12-0 2021-11-0 020-12 / Field technical su IDA / 60880 Water Supply Investments Post Open 12,323.87 Signed 2020-08-01 ultant Selection 1 9 7 0 5 4 2 9 pervision engineer in Kene sh Osh oblast IDA-SRWSSDP-AF-IC-2019 -40 / Consultant on verific ation of household sanitat Individual Cons 2020-09-1 2020-10-2 2020-11-2 2020-11-1 2020-11-2 2020-12-2 2020-12-0 2021-06-2 2021-02-0 IDA / 60880 Sanitation Development Post Open 1,414.19 Completed 2020-09-10 ion facilities in pilot village ultant Selection 0 9 5 9 6 4 1 2 1 s Ak-Bulak and Kotormo K yrgyz-Ata ayil okmotu, No okat district, Osh oblast. IDA-SRWSSDP-DC-2020-1 / Аuthor supervision of sub 2020-09-0 2020-09-1 2020-09-1 2020-11-1 2020-10-0 2021-05-1 IDA / 59070 Sanitation Development Post Direct Selection Direct 7,029.95 Signed 2020-09-01 -projects for outside toilets 1 1 6 5 2 4 in Chui and Osh oblasts (3 rd phase) IDA-SRWSSDP-DC-2020-2 / Аuthor supervision of sub Under Impleme 2020-09-1 2020-11-1 2021-05-1 IDA / 59070 Sanitation Development Post Direct Selection Direct 0.00 2020-09-01 -projects for outside toilets ntation 1 5 4 in Chui and Issuk-Kul obla sts (3rd phase) IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2021-04-3 2021-05-1 2021-05-2 2021-05-3 2021-06-0 2021-06-1 2021-06-0 2022-06-1 020-11-1 / Junior field tech IDA / 60880 Water Supply Investments Post Limited 5,283.80 Signed 2021-04-26 ultant Selection 0 0 4 1 3 4 8 4 nical supervision engineer in Gornaya Maevka IDA-SRWSSDP-AF-IC-2021 Individual Cons 2021-04-3 2021-05-1 2021-06-2 2021-05-3 2021-07-0 2021-06-1 2021-07-0 2022-06-1 -20 / Sanitation Subsidy Co IDA / D2040 Sanitation Development Post Limited 6,982.22 Signed 2021-04-26 ultant Selection 0 0 5 1 5 4 8 4 nsultant of Chuy oblast IDA-SRWSSDP-AF-IC-2021 Individual Cons 2021-04-3 2021-05-1 2021-06-2 2021-05-3 2021-07-0 2021-06-1 2021-07-0 2022-06-1 -21 / Sanitation Subsidy Co IDA / D2040 Sanitation Development Post Limited 3,586.97 Signed 2021-04-26 ultant Selection 0 0 5 1 5 4 8 4 nsultant of Issyk-Kul oblast IDA-SRWSSDP-AF-IC-FIDS- 2020-27 / Local expert on Institutional Strengthenin Individual Cons 2021-05-0 2021-06-2 2021-06-2 2021-07-1 2021-06-2 2021-08-1 2021-07-0 2022-08-1 IDA / 60880 Post Open 5,658.65 Signed 2021-05-04 social mobilization and ins g ultant Selection 3 2 1 3 8 7 2 7 titutional development in Kyzyl Zhar subproject IDA-SRWSSDP-AF-IC-FIDS- 2020-28 / Local expert on Institutional Strengthenin Individual Cons 2021-05-0 2021-06-2 2021-07-2 2021-07-1 2021-07-2 2021-08-1 2021-08-0 2022-08-1 IDA / 60880 Post Open 5,187.09 Signed 2021-05-04 social mobilization and ins g ultant Selection 3 2 0 3 8 7 2 7 titutional development in Koo Chaty subproject IDA-SRWSSDP-AF-IC-FSS-2 020-27 / Consultants on ac Individual Cons 2021-03-3 2021-06-2 2021-06-2 2021-07-1 2021-06-2 2021-08-1 2021-07-0 2022-05-1 IDA / 60880 Sanitation Development Post Open 4,244.12 Signed 2021-05-04 tivities with communities a ultant Selection 0 2 8 3 9 7 2 8 nd householders in Kyzyl Z har subproject IDA-SRWSSDP-AF-IC-FSS-2 020-28 / Consultants on ac Individual Cons 2021-03-3 2021-06-2 2021-06-2 2021-07-1 2021-06-2 2021-08-1 2021-07-0 2022-05-1 IDA / 60880 Sanitation Development Post Open 4,244.12 Signed 2021-05-04 tivities with communities a ultant Selection 0 2 8 3 9 7 2 8 nd householders in Koo Ch aty subproject IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2021-04-0 2021-06-2 2021-05-2 2021-07-1 2021-06-0 2021-08-1 2021-06-1 2022-08-1 020-27 / Field technical su IDA / 60880 Water Supply Investments Post Open 7,241.60 Signed 2021-05-04 ultant Selection 5 2 7 3 9 7 5 7 pervision engineer Kyzyl Z har IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2021-04-0 2021-06-2 2021-05-2 2021-07-1 2021-06-0 2021-08-1 2021-06-1 2022-08-1 020-28 / Field technical su IDA / 60880 Water Supply Investments Post Open 7,241.60 Signed 2021-05-04 ultant Selection 5 2 7 3 9 7 5 7 pervision engineer Koo Ch aty IDA-SRWSSDP-IC-MWU-20 21 / Consultant on Perform Institutional Strengthenin Individual Cons 2021-07-2 2021-07-2 2021-09-2 2021-08-0 2021-09-2 2021-08-1 2021-10-0 2024-02-0 ance Improvement of Wat IDA / D2040 Post Limited 2,546.46 Signed 2021-06-28 g ultant Selection 7 8 7 4 9 8 2 4 er Supply Utilities, Operati on and Maintenance of Rur al Water Supply Systems IDA-SRWSSDP-IC-2021-1 / Individual Cons 2021-09-1 2021-10-1 2021-11-1 2022-11-1 IDA / D1380 Water Supply Investments Post Open 0.00 Canceled 2021-08-01 Infrastructure engineer as ultant Selection 9 0 4 4 sistant IDA-SRWSSDP-AF-IC-FSS-2 020-15-1 / Consultants on Individual Cons 2021-03-2 2021-05-1 2021-05-2 2021-05-3 2021-06-2 2021-07-0 2021-07-0 2022-04-0 2022-01-0 activities with communitie IDA / 60880 Sanitation Development Post Open 2,829.28 Completed 2021-03-29 ultant Selection 9 0 4 1 2 5 2 1 1 s and householders in Gor naya Maevka subproject (s econd) IDA-SRWSSDP-AF-IC-FSS-2 021-23-1 / Consultants on Individual Cons 2021-03-2 2021-05-1 2021-04-2 2021-05-3 2021-04-2 2021-07-0 2021-05-0 2022-04-0 2022-02-0 IDA / 60880 Sanitation Development Post Open 4,244.05 Completed 2021-03-29 activities with communitie ultant Selection 4 0 7 1 8 5 1 1 1 s and householders in Ken Bulun subproject (second) IDA-SRWSSDP-AF-IC-FSS-2 021-5-1 / Consultants on a Individual Cons 2021-03-2 2021-05-1 2021-05-2 2021-05-3 2021-06-0 2021-07-0 2021-06-0 2022-04-0 2022-03-0 ctivities with communities IDA / 60880 Sanitation Development Post Open 4,158.19 Completed 2021-03-29 ultant Selection 3 0 0 1 2 5 8 1 1 and householders in Ivano vka Station subproject (se cond) IDA-SRWSSDP-AF-IC-FIDS- 2020-14-1 / Local expert o Institutional Strengthenin Individual Cons 2021-03-0 2021-05-1 2021-05-2 2021-05-3 2021-06-2 2021-07-0 2021-07-0 2022-06-3 n social mobilization and i IDA / 60880 Post Open 5,658.56 Signed 2021-03-29 g ultant Selection 2 0 0 1 2 5 2 0 nstitutional development i n Gornaya Maevka subproj ect (second) IDA-SRWSSDP-AF-IC-IVA-2 021-2 / Independent Verifi Individual Cons 2021-11-0 2021-12-2 2022-01-2 2022-01-1 2022-03-0 2022-02-1 2022-08-1 IDA / 60880 Sanitation Development Post Open 0.00 Signed 2021-11-02 cation Agent (IVA) for Hou ultant Selection 3 1 0 1 1 5 4 sehold Sanitation Facilities in Chuy oblast IDA-SRWSSDP-AF-IC-IVA-2 021-3 / Independent Verifi Individual Cons Under Impleme 2021-11-0 2021-12-2 2022-01-1 2022-02-1 2022-08-1 IDA / 60880 Sanitation Development Post Open 0.00 2021-11-02 cation Agent (IVA) for Hou ultant Selection ntation 3 1 1 5 4 sehold Sanitation Facilities in Issyk-Kul oblast IDA-SRWSSDP-AF-IC-IVA-2 021-1 / Independent Verifi Individual Cons 2021-11-0 2021-12-2 2022-01-2 2022-01-1 2022-03-0 2022-02-1 2022-08-1 IDA / 60880 Sanitation Development Post Open 0.00 Signed 2021-11-03 cation Agent (IVA) for Hou ultant Selection 3 2 0 2 1 6 5 sehold Sanitation Facilities in Osh oblast IDA-SRWSSDP-AF-IC-TS-2 021-5-1 / Field technical s Individual Cons 2021-03-2 2021-12-2 2021-07-2 2022-01-1 2021-08-1 2022-02-1 2021-10-0 2023-02-1 IDA / 60880 Water Supply Investments Post Open 6,153.69 Signed 2021-11-03 upervision engineer in Iva ultant Selection 9 2 6 2 7 6 2 6 novka station Chui oblast ( second) IDA-SRWSSDP-IC-2021-2 / Institutional Strengthenin Individual Cons 2021-11-2 2022-01-1 2022-01-2 2022-02-0 2022-01-2 2022-03-0 2022-01-2 2024-12-3 Senior Field Specialist for I IDA / 59070 Post Open 2,829.28 Terminated 2021-11-24 g ultant Selection 6 2 0 2 6 9 9 1 nstitutional Development i n Osh oblast IDA-SRWSSDP-IC-2021-3 / Institutional Strengthenin Individual Cons 2021-11-2 2022-01-1 2022-01-1 2022-02-0 2022-01-2 2022-03-0 2022-02-0 2024-12-3 Senior Field Specialist for I IDA / 59070 Post Open 2,829.28 Signed 2021-11-24 g ultant Selection 6 2 8 2 6 9 8 1 nstitutional Development i n Issyk-Kul oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Under Impleme 2022-02-2 2022-01-1 2022-02-0 2022-03-1 2023-03-1 021-23-RT-1 / Field technic IDA / 60880 Water Supply Investments Post Open 0.00 2021-12-01 ultant Selection ntation 4 9 9 6 6 al supervision engineer in Ken-Bulun Chui oblast IDA-SRWSSDP-AF-IC-TRNG -2022-1 / Consultant for tr Institutional Strengthenin Individual Cons 2022-03-0 2022-04-0 2022-05-2 2022-04-2 2022-05-2 2022-06-0 2022-05-2 2022-11-2 aining of local self-governa IDA / 60880 Post Open 4,081.37 Signed 2022-02-17 g ultant Selection 7 7 3 8 3 2 5 9 nce bodies, CDWUU and ot her rural water supply utili ties #1 IDA-SRWSSDP-AF-IC-TRNG -2022-2 / Consultant for tr Institutional Strengthenin Individual Cons 2022-03-0 2022-04-0 2022-05-2 2022-04-2 2022-05-2 2022-06-0 2022-06-0 2022-11-2 2023-01-1 aining of local self-governa IDA / 60880 Post Open 4,081.37 Completed 2022-02-17 g ultant Selection 7 7 3 8 3 2 3 9 0 nce bodies, CDWUU and ot her rural water supply utili ties #2 IDA-SRWSSDP-AF-IC-TRNG -2022-3 / Consultant for tr Institutional Strengthenin Individual Cons 2022-03-0 2022-04-0 2022-05-2 2022-04-2 2022-05-2 2022-06-0 2022-05-2 2022-11-2 aining of local self-governa IDA / 60880 Post Open 4,081.37 Signed 2022-02-17 g ultant Selection 7 7 3 8 3 2 5 9 nce bodies, CDWUU and ot her rural water supply utili ties #3 IDA-SRWSSDP-AF-IC-TRNG -2022-4 / Consultant for tr Institutional Strengthenin Individual Cons 2022-03-0 2022-04-0 2022-05-2 2022-04-2 2022-05-2 2022-06-0 2022-05-2 2022-11-2 aining of local self-governa IDA / 60880 Post Open 4,081.37 Signed 2022-02-17 g ultant Selection 7 7 3 8 3 2 5 9 nce bodies, CDWUU and ot her rural water supply utili ties #4 IDA-SRWSSDP-AF-IC-TRNG -2022-5 / Consultant for tr Institutional Strengthenin Individual Cons 2022-03-0 2022-04-0 2022-05-2 2022-04-2 2022-05-2 2022-06-0 2022-06-0 2022-11-2 2023-01-1 aining of local self-governa IDA / 60880 Post Open 4,081.37 Completed 2022-02-17 g ultant Selection 7 7 3 8 3 2 3 9 0 nce bodies, CDWUU and ot her rural water supply utili ties #5 IDA-SRWSSDP-AF-IC-FIDS- 2020-8-RT1 / Local expert Institutional Strengthenin Individual Cons 2021-03-0 2022-04-1 2021-04-1 2022-05-0 2021-04-1 2022-06-0 2021-04-2 2023-06-0 IDA / 60880 Post Open 6,812.33 Signed 2022-02-24 on social mobilization and g ultant Selection 3 4 6 5 6 9 0 9 institutional development i n Chon-Daly subproject IDA-SRWSSDP-AF-CS-SSS- 2021-10 / Consultant for s Under Impleme 2021-07-2 2021-08-0 2021-12-3 urvey, preparation of BoQ IDA / D2040 Sanitation Development Post Direct Selection Direct 0.00 2021-07-12 ntation 2 2 1 and drawings for rehabilita tion of indoor sanitary facil ities in schools of Chaichi s ubproject IDA-SRWSSDP-IC-TRNG-20 22-1 / Trainer on conducti Individual Cons 2022-03-1 2022-05-0 2022-05-2 2022-05-2 2022-05-2 2022-06-2 2022-05-2 2023-06-2 IDA / D1380 Sanitation Development Post Open 2,577.57 Signed 2022-03-14 ng trainings for sanitation ultant Selection 0 2 3 3 3 7 5 7 field officers on WASH in S chools Methodology IDA-SRWSSDP-IC-TRNG-20 22-2 / Trainer on conducti Individual Cons Under Impleme 2022-03-1 2022-03-1 2022-04-0 2022-05-1 2023-05-1 ng trainings for sanitation IDA / D1380 Sanitation Development Post Limited 0.00 2022-03-14 ultant Selection ntation 0 9 9 4 4 field officers on Household Sanitation Improvement M ethodology IDA-SRWSSDP-IC-2021-2- Institutional Strengthenin Individual Cons 2022-03-2 2022-03-1 2022-01-1 2022-04-0 2022-03-2 2022-05-1 2023-05-1 RT-1 / Senior Field Speciali IDA / D2040 Post Limited 0.00 Signed 2022-03-14 g ultant Selection 3 9 8 9 8 4 4 st for Institutional Develop ment in Osh oblast IDA-SRWSSDP-AF-DS-EIA- 2022 / Consultant for Engi neering, Environmental an 2022-03-2 2022-03-2 2022-04-0 2022-04-0 2022-04-0 2022-06-1 d Sanitary Safety Review i IDA / D2040 Water Supply Investments Post Direct Selection Direct 3,731.78 Signed 2022-03-25 3 7 5 1 7 0 n Subprojects Ivanovka St ation, Kara-Zhygach, Ken- Bulun, Sosnovka, Komsom ol’skoe, Kurmontu, Bokso- Zhol, Kayirma IDA-SRWSSDP-AF-IC-2022 Individual Cons Under Impleme 2022-06-0 2022-06-2 2022-08-0 2023-08-0 -1 / Supervision Engineer/ IDA / 59070 Water Supply Investments Post Open 0.00 2022-04-20 ultant Selection ntation 8 9 3 3 Hydrogeologist in Osh obla st IDA-SRWSSDP-AF-IC-2022 Individual Cons 2022-06-2 2022-06-0 2022-06-2 2022-06-2 2022-06-3 2022-08-0 2023-08-0 -2 / Supervision Engineer/ IDA / 59070 Water Supply Investments Post Open 0.00 Signed 2022-04-20 ultant Selection 9 8 9 9 0 3 3 Hydrogeologist in Chui and Issyk kul oblast IDA-SRWSSDP-AF-IC-2022 Individual Cons 2022-04-1 2022-06-2 2022-05-3 2022-07-1 2022-05-3 2022-08-2 2024-08-2 -5 / Sanitation Subsidy Con IDA / D2040 Sanitation Development Post Open 0.00 Signed 2022-05-10 ultant Selection 8 8 1 9 1 3 2 sultant of Chui oblast IDA-SRWSSDP-AF-IC-2022 Individual Cons 2022-04-2 2022-06-2 2022-06-0 2022-07-1 2022-06-0 2022-08-2 2022-06-0 2024-08-2 -6 / Sanitation Subsidy Con IDA / D2040 Sanitation Development Post Open 3,360.56 Signed 2022-05-10 ultant Selection 6 8 6 9 6 3 8 2 sultant of Issyk-Kul oblast IDA-SRWSSDP-AF-IC-2022 Individual Cons 2022-05-3 2022-06-2 2022-05-2 2022-07-1 2022-06-1 2022-08-2 2024-08-2 IDA / D2040 Sanitation Development Post Open 0.00 Signed 2022-05-10 -7 / Sanitation Subsidy Con ultant Selection 0 8 7 9 7 3 2 sultant of Osh IDA-SRWSSDP-AF-IC-2022 Individual Cons 2022-04-2 2022-06-2 2022-05-3 2022-07-1 2022-05-3 2022-08-2 2022-06-1 2024-08-2 IDA / D2040 Sanitation Development Post Open 6,805.14 Signed 2022-05-10 -4 / Sanitation Engineer ultant Selection 7 8 0 9 0 3 6 2 Page 12 IDA-SRWSSDP-AF-IC-2022 Individual Cons 2022-04-2 2022-06-2 2022-07-2 2022-07-1 2022-08-0 2022-08-2 2022-08-1 2024-08-2 IDA / D2040 Sanitation Development Post Open 1,494.00 Signed 2022-05-10 -3 / Public Relations Specia ultant Selection 6 8 5 9 1 3 0 2 list IDA-SRWSSDP-AF-IC-FIDS- 2022-1-RT-1 / Local expert Institutional Strengthenin Individual Cons 2022-06-1 2022-08-1 2022-07-2 2022-09-0 2022-08-0 2022-10-0 2022-08-1 2023-04-0 on social mobilization and IDA / 60880 Post Open 2,490.01 Signed 2022-07-01 g ultant Selection 7 9 5 2 1 7 1 5 institutional development i n Kenesh and Chon Daly s ubproject IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2022-06-2 2022-08-1 2022-07-2 2022-09-0 2022-07-2 2022-10-1 2023-04-1 021-4-1 / Junior field techn IDA / 60880 Water Supply Investments Post Open 0.00 Signed 2022-07-01 ultant Selection 3 9 5 9 7 4 2 ical supervision for Sosnov ka subproject IDA-SRWSSDP-AF-IC-FSS-2 021-4-1 / Consultants on a Individual Cons 2022-06-1 2022-07-2 2022-04-2 2022-08-1 2022-04-2 2022-09-1 2023-06-1 IDA / 60880 Sanitation Development Post Open 0.00 Signed 2022-06-03 ctivities with communities ultant Selection 7 2 0 2 5 6 7 and householders in Sosno vka subproject IDA-SRWSSDP-СS-SSS-20 2022-05-1 2022-06-1 2022-05-2 2022-08-1 2023-08-1 22-3 / Author supervision f IDA / 60880 Water Supply Investments Post Direct Selection Direct 0.00 Signed 2022-06-02 0 2 3 6 6 or 4 WSS sub-projects in C hui oblast ARIS-IDA-SRWSSDP-HO-2 Individual Cons 2022-06-2 2022-08-1 2022-08-0 2022-09-0 2022-08-1 2022-10-1 2023-04-1 IDA / D1380 Water Supply Investments Post Open 0.00 Signed 2022-07-01 022-1 / Assistant of safegu ultant Selection 4 9 8 9 5 4 2 ards specialist IDA-SRWSSDP-AF-IC-IVA-2 022-1 / Independent Verifi Individual Cons Pending Imple 2023-02-1 2023-03-1 2023-04-1 2023-12-2 IDA / D2040 Sanitation Development Post Open - National 0.00 2023-01-01 cation Agent (IVA) for Hou ultant Selection mentation 9 2 6 2 sehold Sanitation Facilities in Chuy and Issyk-Kul obla sts. IDA-SRWSSDP-AF-IC-IVA-2 022-2 / Independent Verifi Individual Cons Pending Imple 2023-02-2 2023-03-2 2023-04-2 2023-12-3 IDA / D2040 Sanitation Development Post Open - National 0.00 2023-01-10 cation Agent (IVA) for Hou ultant Selection mentation 8 1 5 1 sehold Sanitation Facilities in Osh oblast IDA-SRWSSDP-AF-IC-ENG- 2022-1 / Consultant for pr Individual Cons Under Impleme 2023-03-2 2023-02-2 2023-05-1 2023-03-2 2023-05-1 2023-04-2 2023-12-3 eparation of BoQ and draw IDA / D2040 Sanitation Development Post Open - National 0.00 2023-01-10 ultant Selection ntation 9 8 0 1 9 5 1 ings for rehabilitation of in ternal sanitary units and fa cilities of kindergartens in Osh region IDA-SRWSSDP-AF-IC-ENG- 2022-2 / Consultant for pr eparation of BoQ and draw Individual Cons Under Impleme 2023-05-0 2023-02-2 2023-05-1 2023-03-2 2023-05-1 2023-04-2 2023-12-3 IDA / D2040 Sanitation Development Post Open - National 0.00 2023-01-10 ings for rehabilitation of in ultant Selection ntation 2 8 0 1 9 5 1 ternal sanitary units and fa cilities of kindergartens in Chui and Issyk-Kul region IDA-SRWSSDP-AF-IC-2023 Individual Cons Under Impleme 2023-04-1 2023-05-2 2023-06-0 2023-06-1 2023-06-0 2023-07-2 2024-01-1 -1 / Consultant on sanitary IDA / D2040 Sanitation Development Post Open - National 0.00 2023-04-06 ultant Selection ntation 2 5 1 5 7 0 6 subsidies for Osh region (E ngineer) IDA-SRWSSDP-IC-2023-1 / Senior Field Specialist for I Institutional Strengthenin Individual Cons Under Impleme 2023-04-1 2023-06-0 2023-06-0 2023-06-1 2023-06-0 2023-06-2 2025-09-0 IDA / D2040 Post Open - National 0.00 2023-04-14 nstitutional Development i g ultant Selection ntation 8 1 6 1 7 6 3 n Subprojects of Chui Obla st IDA-SRWSSDP-IC-2023-2 / Institutional Strengthenin Individual Cons Under Impleme 2023-04-1 2023-05-2 2023-06-0 2023-06-0 2023-06-0 2023-06-2 2025-08-3 IDA / D2040 Post Open - National 0.00 2023-04-11 Institutional Development g ultant Selection ntation 8 9 6 8 7 3 1 Assistant IDA-SRWSSDP-AF-IC-TRNG Institutional Strengthenin Individual Cons Pending Imple 2023-07-0 2023-07-0 2023-07-1 2024-07-0 -2023-1 / Treiner for Aiyl O IDA / 60880 Post Open - National 0.00 2023-06-06 g ultant Selection mentation 4 9 2 6 kmotu and CDWUUs (#19) IDA-SRWSSDP-AF-IC-TRNG Institutional Strengthenin Individual Cons Pending Imple 2023-07-0 2023-07-1 2023-07-1 2024-07-0 -2023-2 / Treiner for Aiyl O IDA / 60880 Post Open - National 0.00 2023-06-06 g ultant Selection mentation 5 0 4 8 kmotu and CDWUUs (#20) IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Under Impleme 2023-04-2 2023-05-2 2023-05-1 2023-06-1 2023-05-1 2023-06-1 2024-07-2 021-4/2 / Field technical su IDA / 60880 Water Supply Investments Post Open - National 0.00 2023-04-23 ultant Selection ntation 1 1 1 3 8 8 2 pervision engineer in Sosn ovka Chui oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Pending Imple 2023-05-2 2023-05-2 2023-05-2 2024-05-2 021-19/1 / Field technical s IDA / 60880 Water Supply Investments Post Open - National 0.00 2023-04-25 ultant Selection mentation 4 6 8 2 upervision engineer in Jylu u-Bulak Issyk-Kul oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Pending Imple 2023-09-0 2023-09-1 2023-09-2 2025-02-0 023-1 / Field technical sup IDA / 60880 Water Supply Investments Post Open - National 0.00 2023-08-06 ultant Selection mentation 4 0 6 7 ervision engineer in Kichi- Bulolu Osh oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Pending Imple 2024-01-0 2024-01-1 2024-01-1 2025-06-0 023-2 / Field technical sup IDA / 60880 Water Supply Investments Post Open - National 0.00 2023-12-11 ultant Selection mentation 9 1 9 2 ervision engineer in Gulba ar Osh oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Pending Imple 2024-01-1 2024-01-1 2024-01-1 2025-05-3 023-3 / Field technical sup IDA / 60880 Water Supply Investments Post Open - National 0.00 2023-12-11 ultant Selection mentation 0 4 6 0 ervision engineer in Otuz- Adyr Osh oblast IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2024-01-1 2024-01-1 2024-01-1 2025-05-2 023-4 / Field technical sup IDA / 60880 Water Supply Investments Post Open - National 0.00 Canceled 2023-12-11 ultant Selection 0 2 5 9 ervision engineer in Kum-A ryk Chui oblast IDA-SRWSSDP-AF-IC-TS-2 023-5 / Field technical sup Individual Cons Under Impleme 2023-04-2 2023-06-0 2023-06-0 2023-06-1 2024-10-2 IDA / 60880 Water Supply Investments Post Open - National 0.00 2023-05-05 ervision engineer in Sultan ultant Selection ntation 5 8 9 2 4 for additional work Chui ob last IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Under Impleme 2023-05-1 2023-06-0 2023-06-0 2023-07-1 2024-11-2 023-6 / Junior field technic IDA / 60880 Water Supply Investments Post Open - National 0.00 2023-05-05 ultant Selection ntation 8 8 9 5 6 al supervision for Kurpuldo k subproject IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Under Impleme 2023-05-1 2023-06-0 2023-06-0 2023-07-0 2024-09-2 023-7 / Junior field technic IDA / 60880 Water Supply Investments Post Open - National 0.00 2023-05-05 ultant Selection ntation 8 8 9 2 4 al supervision for Orto-Ary k subproject IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Under Impleme 2023-05-1 2024-01-1 2024-01-1 2024-02-0 2025-05-0 023-8 / Junior field technic IDA / 60880 Water Supply Investments Post Open - National 0.00 2023-12-11 ultant Selection ntation 8 4 5 7 2 al supervision for Kum-Ary k subproject IDA-SRWSSDP-AF-IC-TS-2 Individual Cons Under Impleme 2023-05-1 2023-10-0 2023-10-0 2023-11-0 2025-01-2 023-9 / Junior field technic IDA / 60880 Water Supply Investments Post Open - National 0.00 2023-09-04 ultant Selection ntation 8 8 9 1 4 al supervision for Bokso-Jol subproject IDA-SRWSSDP-AF-IC-TS-2 Individual Cons 2023-05-2 2023-05-3 2023-06-2 2024-09-1 023-10 / Field technical su IDA / 60880 Water Supply Investments Post Open - National 0.00 Canceled 2023-04-25 ultant Selection 9 0 2 4 pervision engineer in Kaiyr ma Chui oblast IDA-SRWSSDP-СS-DS-202 Pending Imple 2024-01-0 2024-01-1 2025-04-1 3-1 / Author supervision fo IDA / 60880 Water Supply Investments Post Direct Selection Direct - National 0.00 2023-12-12 mentation 1 6 0 r Gulbaar WSS sub-project s in Osh oblast IDA-SRWSSDP-СS-DS-202 Pending Imple 2023-08-2 2023-09-0 2024-11-2 3-2 / Author supervision fo IDA / 60880 Water Supply Investments Post Direct Selection Direct - National 0.00 2023-08-11 mentation 1 5 8 r Kichi Bulolu WSS sub-proj ects in Osh oblast IDA-SRWSSDP-СS-DS-202 Pending Imple 2023-12-2 2024-01-1 2025-04-1 3-3 / Author supervision fo IDA / 60880 Water Supply Investments Post Direct Selection Direct - National 0.00 2023-12-12 mentation 7 6 7 r Otuz-Adyr WSS sub-proje cts in Osh oblast IDA-SRWSSDP-AF-IC-2-20 23-1 / Consultant on proje Individual Cons Pending Imple 2023-06-2 2023-06-2 2023-07-0 2024-06-3 IDA / D2040 Sanitation Development Post Open - National 0.00 2023-06-06 ct development and autho ultant Selection mentation 6 8 6 0 r's supervision of subproje cts IDA-SRWSSDP-AF-IC-2-20 Individual Cons Pending Imple 2023-08-1 2023-08-2 2023-09-1 2024-09-1 23-2 / Sanitation Subsidy IDA / D2040 Sanitation Development Post Open - National 0.00 2023-07-11 ultant Selection mentation 9 2 6 0 Consultant of Osh oblast #2 IDA-SRWSSDP-AF-IC-2-20 Individual Cons Pending Imple 2023-07-2 2023-07-2 2023-07-3 2024-07-2 23-3 / Sanitation Subsidy IDA / D2040 Sanitation Development Post Open - National 0.00 2023-06-11 ultant Selection mentation 0 2 0 4 Consultant of Issyk-Kul obl ast #2 IDA-SRWSSDP-AF-IC-FSS-2 -2023-1 / Consultant on ac Individual Cons Pending Imple 2023-10-1 2023-10-1 2023-10-2 2024-10-1 tivities with communities a IDA / 60880 Sanitation Development Post Open - National 0.00 2023-09-09 ultant Selection mentation 3 6 1 5 nd householders in subproj ect “Kurmontu” (Field san itation officer) IDA-SRWSSDP-AF-IC-FSS-2 -2023-2 / Consultant on ac Individual Cons Pending Imple 2024-01-1 2024-01-2 2024-01-2 2025-01-2 tivities with communities a IDA / 60880 Sanitation Development Post Open - National 0.00 2023-12-15 ultant Selection mentation 8 0 6 0 nd householders in subproj ect “Kum-Aryk” (Field sani tation officer) IDA-SRWSSDP-AF-IC-FSS-2 -2023-3 / Consultant on ac Individual Cons Pending Imple 2023-09-1 2023-09-1 2023-09-1 2024-09-1 tivities with communities a IDA / 60880 Sanitation Development Post Open - National 0.00 2023-08-08 ultant Selection mentation 1 4 9 3 nd householders in subproj ect “Bokso-Jol” (Field sani tation officer) IDA-SRWSSDP-AF-IC-FSS-2 -2023-4 / Consultant on ac Individual Cons Pending Imple 2023-10-1 2023-10-1 2023-10-1 2024-10-1 tivities with communities a IDA / 60880 Sanitation Development Post Open - National 0.00 2023-09-07 ultant Selection mentation 1 4 9 3 nd householders in subproj ect “Kichi-Oruktuu” (Field sanitation officer) IDA-SRWSSDP-AF-IC-FSS-2 -2023-5 / Consultant on ac Individual Cons Pending Imple 2023-10-1 2023-10-1 2023-10-2 2024-10-1 tivities with communities a IDA / 60880 Sanitation Development Post Open - National 0.00 2023-09-07 ultant Selection mentation 0 2 0 4 nd householders in subproj ect “Karool-Dobo” (Field s anitation officer) IDA-SRWSSDP-AF-IC-FSS-2 -2023-6 / Consultant on ac Individual Cons Pending Imple 2024-01-1 2024-01-2 2024-01-2 2025-01-2 tivities with communities a IDA / 60880 Sanitation Development Post Open - National 0.00 2023-12-15 ultant Selection mentation 8 1 8 2 nd householders in subproj ect “Gulbar” (Field sanitat ion officer) #1 IDA-SRWSSDP-AF-IC-FSS-2 -2023-7 / Consultant on ac Individual Cons Pending Imple 2024-01-1 2024-01-2 2024-02-1 2025-02-2 tivities with communities a IDA / 60880 Sanitation Development Post Open - National 0.00 2023-12-15 ultant Selection mentation 8 1 5 5 nd householders in subproj ect “Gulbar” (Field sanitat ion officer) #2 IDA-SRWSSDP-AF-IC-FSS-2 -2023-8 / Consultant on ac Individual Cons Pending Imple 2024-01-1 2024-01-2 2024-01-2 2025-01-2 tivities with communities a IDA / 60880 Sanitation Development Post Open - National 0.00 2023-12-15 ultant Selection mentation 8 1 8 2 nd householders in subproj ect “Gulbar” (Field sanitat ion officer) #3 IDA-SRWSSDP-AF-IC-FSS-2 -2023-9 / Consultant on ac Individual Cons Pending Imple 2024-01-1 2024-01-2 2024-02-1 2025-02-0 tivities with communities a IDA / 60880 Sanitation Development Post Open - National 0.00 2023-12-15 ultant Selection mentation 8 1 5 9 nd householders in subproj ect “Gulbar” (Field sanitat ion officer) #4 IDA-SRWSSDP-AF-IC-FSS-2 -2023-10 / Consultant on a Individual Cons Pending Imple 2024-01-1 2024-01-2 2024-02-1 2025-02-0 ctivities with communities IDA / 60880 Sanitation Development Post Open - National 0.00 2023-12-15 ultant Selection mentation 8 1 5 9 and householders in subpr oject “Gulbar” (Field sanit ation officer) #5 IDA-SRWSSDP-AF-IC-FSS-2 -2023-11 / Consultant on a Individual Cons Pending Imple 2024-01-1 2024-01-2 2024-02-1 2025-02-0 ctivities with communities IDA / 60880 Sanitation Development Post Open - National 0.00 2023-12-15 ultant Selection mentation 8 1 5 9 and householders in subpr oject “Otuz-Adyr” (Field s anitation officer) #1 IDA-SRWSSDP-AF-IC-FSS-2 -2023-12 / Consultant on a Individual Cons Pending Imple 2024-01-1 2024-01-2 2024-02-1 2025-02-0 ctivities with communities IDA / 60880 Sanitation Development Post Open - National 0.00 2023-12-15 ultant Selection mentation 8 1 5 9 and householders in subpr oject “Otuz-Adyr” (Field s anitation officer) #2 IDA-SRWSSDP-AF-IC-FSS-2 -2023-13 / Consultant on a Individual Cons Pending Imple 2024-01-1 2024-01-2 2024-02-1 2025-02-0 ctivities with communities IDA / 60880 Sanitation Development Post Open - National 0.00 2023-12-15 ultant Selection mentation 8 1 5 9 and householders in subpr oject “Otuz-Adyr” (Field s anitation officer) #3 IDA-SRWSSDP-AF-IC-FSS-2 -2023-14 / Consultant on a Individual Cons Pending Imple 2024-01-1 2024-01-2 2024-02-0 2025-02-0 ctivities with communities IDA / 60880 Sanitation Development Post Open - National 0.00 2023-12-15 ultant Selection mentation 8 0 8 2 and householders in subpr oject “Otuz-Adyr” (Field s anitation officer) #4 Page 13 IDA-SRWSSDP-AF-IC-FSS-2 -2023-15 / Consultant on a Individual Cons Pending Imple 2024-01-1 2024-01-2 2024-02-1 2025-02-0 ctivities with communities IDA / 60880 Sanitation Development Post Open - National 0.00 2023-12-15 ultant Selection mentation 8 1 5 9 and householders in subpr oject “Otuz-Adyr” (Field s anitation officer) #5 IDA-SRWSSDP-AF-IC-2-20 23-4 / Individual consultan Individual Cons Pending Imple 2023-07-1 2023-07-1 2023-07-2 2024-07-1 t to update drinking water IDA / 60880 Sanitation Development Post Open - National 0.00 2023-06-06 ultant Selection mentation 0 2 0 4 quality control software in support of the Department of SES. IDA-SRWSSDP-AF-IC-FSS-2 -2023-16 / Consultant on a Individual Cons Under Impleme 2023-05-1 2023-06-2 2023-06-1 2023-07-1 2023-06-1 2023-08-2 2024-05-2 ctivities with communities IDA / 60880 Sanitation Development Post Open - National 0.00 2023-05-10 ultant Selection ntation 5 8 2 9 9 3 3 and householders in subpr oject “Kyzyl-Bairak” of the Osh Oblast #2 IDA-SRWSSDP-AF-IC-FSS-2 -2023-17 / Consultant on a Individual Cons Under Impleme 2023-05-1 2023-06-2 2023-06-1 2023-07-1 2023-06-2 2023-08-2 2024-05-2 ctivities with communities IDA / 60880 Sanitation Development Post Open - National 0.00 2023-05-10 ultant Selection ntation 5 8 2 9 7 3 3 and householders in subpr oject “Toloikon” of the Osh Oblast #2 IDA-SRWSSDP-СS-DS-202 2023-06-2 2023-06-2 2023-07-0 2024-09-2 3-4 / Author supervision fo IDA / 60880 Water Supply Investments Post Direct Selection Direct - National 0.00 Under Review 2023-06-14 3 9 6 8 r Grigorevka WSS sub-proj ect in Issyk-Kul oblast IDA-SRWSSDP-СS-DS-202 3-5 / Author supervision fo Pending Imple 2023-09-1 2023-09-2 2024-12-1 IDA / 60880 Water Supply Investments Post Direct Selection Direct - National 0.00 2023-09-04 r Karool-Dobo WSS sub-pr mentation 9 6 9 oject in Issyk-Kul oblast RWSSP3-PPG-IC-2016-1 / Selection of Consultant for Individual Cons 2016-09-1 2016-09-1 TF / A1605 Water Supply Investments Prior Open 17,052.22 Signed Review of Detailed Design ultant Selection 5 9 s for Water Supply Infrastr ucture Page 14 Sample Procurement Plan Governance and Policy Project for Khyber Pakhtunkhwa (P156412) I. General 1. Bank’s approval Date of the procurement Plan Original: June 2,2016: Revision 3 of Updated Procurement Plan, February 5,2017 2. Date of General Procurement Notice: June 2016 3. Period covered by this procurement plan: The procurement period of project covered, 24 months II. Goods and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Expenditure Contract Value Procurement Contracts Subject to Category (Threshold) Method Prior Review US $ US$ thousand 1.Civil Works Not applicable 2. Goods >600,000 ICB First contract by all entities <600,000 NCB First contract by all entities <100,000 Shopping First contract by all entities Regardless of value Direct Contracting All 2. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Project as per Financing Agreement 3. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 July 9, 2010 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contrac (Works) t for Prior Review Summary 1.86 4 No Post 1st of the NCB contrac (Goods) t for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) II. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: 3. Consulting All ToRs and training Services programs to be reviewed by the World Bank’s task team leader (A) Firms >500,000 QCBS, QBS,FBS,LCS, First contract by any process <500,000 CQS, First CQS contract July 9, 2010 Regardless of value SSS All (B) Individual Up to 200,000 Under Section V (i) First contract Consultants and; (ii) Procurement Specialist regardless of value >200,000 Under Section V All Regardless of value SSS First > 15,000 SSS All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts July 9, 2010 that will be let under other methods III. Selection of Consultants 2. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule July 9, 2010 PROCUREMENT Pakistan : Governance and Policy Program for Khyber Pakhtunkhwa (KP) PLAN General Information Country: Pakistan 2017-05-29 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P156410 GPN Date: 2020-10-14 Project Name: Governance and Policy Program for Khyber Pakhtunkhwa (KP) Loan / Credit No: TF / A3361, TF / B3385 Governance and Policy Project Khyber Pakhtunkhwa Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-GPP KPK-26344-GO-RFQ / Hiring of Potential Supplier f Improving public investment or office partition,interior ren Request for Quota Single Stage - One E TF / A3361 management and accountab Post Limited 95,852.00 94,810.56 Signed 2017-09-01 2017-09-11 2017-10-10 2017-09-19 2017-11-24 ovations, furniture and fixtur tions nvelope ility in public services es to establish Secretariat for District Judiciary Peshawar Hi gh Court. PK-GPP KPK-26348-GO-RFQ / Hiring of potential supplier fo r procurement of office equip Improving public investment Request for Quota Single Stage - One E ment including installation, w TF / A3361 management and accountab Post Limited 37,756.00 37,478.55 Signed 2017-09-01 2017-09-11 2017-09-26 2017-09-19 2017-11-10 tions nvelope iring, networking ,electrificati ility in public services on to establish Secretariat of District Judiciary Peshawar Hi gh Court. PK-GPP KPK-26716-GO-RFQ / Framework Agreement for Pr Improving public investment Request for Quota Single Stage - One E ocurement of Information Te TF / A3361 management and accountab Post Open - National 100,000.00 100,000.00 Signed 2017-09-13 2018-01-09 2017-11-13 2018-03-01 2018-11-13 tions nvelope chnology IT Equipment and a ility in public services llied accessories under GPP K P Component-II PK-GPP KPK-26717-GO-RFQ / Framework Agreement for Pr Increasing capacity for reve Request for Quota Single Stage - One E ocurement of Information Te TF / A3361 nue mobilization and the pu Post Open - National 100,000.00 100,000.00 Signed 2017-09-13 2018-01-09 2017-11-13 2018-03-01 2018-11-13 tions nvelope chnology IT Equipment and a blic financial management llied accessories under GPP K P Component-I PK-GPP KPK-26718-GO-RFQ / Improving public investment Framework Agreement for Pr Request for Quota Single Stage - One E TF / A3361 management and accountab Post Open - National 100,000.00 100,000.00 Signed 2017-09-13 2018-01-03 2017-11-13 2018-02-12 2018-11-13 ocurement of Furniture and F tions nvelope ility in public services ixture under GPP KP Compon ent-II PK-GPP KPK-26722-GO-RFQ / Increasing capacity for reve Framework Agreement for Pr Request for Quota Single Stage - One E TF / A3361 nue mobilization and the pu Post Open - National 100,000.00 100,000.00 Signed 2017-09-13 2018-01-03 2017-11-13 2018-02-12 2018-11-13 ocurement of Furniture and F tions nvelope blic financial management ixture under GPP KP Compon ent-I PK-GPP KPK-26723-GO-RFQ / Improving public investment Framework Agreement for Pr Request for Quota Single Stage - One E TF / A3361 management and accountab Post Open - National 100,000.00 100,000.00 Signed 2017-09-13 2018-01-09 2017-11-13 2018-03-01 2018-11-13 ocurement of Office Equipme tions nvelope ility in public services nt under GPP KP Component- II PK-GPP KPK-26725-GO-RFQ / Increasing capacity for reve Framework Agreement for Pr Request for Quota Single Stage - One E TF / A3361 nue mobilization and the pu Post Open - National 100,000.00 100,000.00 Signed 2017-09-13 2018-01-09 2017-11-13 2018-03-01 2018-11-13 ocurement of Office Equipme tions nvelope blic financial management nt under GPP KP Component- I PK-GPP KPK-146027-GO-RFQ Increasing capacity for reve / Procurement of Goods (Offi Request for Quota Single Stage - One E Under Imple TF / A3361 nue mobilization and the pu Post Open - National 150,000.00 0.00 2019-11-27 2019-12-28 2020-01-27 2021-01-26 ce Equipment) under Govern tions nvelope mentation blic financial management ance and Policy Project Khyb er Pakhtunkhwa PK-GPP KPK-146029-GO-RFQ Increasing capacity for reve / Procurement of Goods ( IT E Request for Quota Single Stage - One E Under Imple TF / A3361 nue mobilization and the pu Post Open - National 150,000.00 0.00 2019-11-27 2019-12-28 2020-01-27 2021-01-26 quipment) under Governance tions nvelope mentation blic financial management and Policy Project Khyber Pak htunkhwa PK-GPP KPK-146031-GO-RFQ Increasing capacity for reve / Procurement of Goods (Furn Request for Quota Single Stage - One E TF / A3361 nue mobilization and the pu Post Open - National 150,000.00 77,394.42 Signed 2019-11-27 2019-12-28 2020-01-27 2020-07-22 2021-01-26 iture and Fixture) Under Gov tions nvelope blic financial management ernance and Policy Project K hyber Pakhtunkhwa Increasing capacity for reve PK-GPP KPK-231008-GO-RFQ Request for Quota Single Stage - One E Under Imple TF / B3385 nue mobilization and the pu Post Open - National 55,000.00 0.00 2021-05-24 2021-06-30 2021-08-14 / Furniture and Fixtures tions nvelope mentation blic financial management PK-GPP KPK-243308-GO-RFB Increasing capacity for reve Single Stage - One E Under Imple / Framework Agreement for p TF / B3385 nue mobilization and the pu Post Request for Bids Open - National 290,000.00 0.00 2021-07-16 2021-08-09 2021-07-21 2021-08-11 2021-09-01 2021-10-01 2021-11-05 2022-06-30 nvelope mentation rocurement of IT Equipment f blic financial management or GPP-KP PK-GPP KPK-243313-GO-RFB Increasing capacity for reve Single Stage - One E Under Imple / Framework Agreement for P TF / B3385 nue mobilization and the pu Post Request for Bids Open - National 290,000.00 0.00 2021-07-16 2021-08-09 2021-07-21 2021-08-11 2021-09-01 2021-10-01 2021-11-05 2022-06-30 nvelope mentation rocurement of Office Equipm blic financial management ent for GPP-KP PK-GPP KPK-243315-GO-RFB Increasing capacity for reve / Framework Agreement for p Single Stage - One E Under Imple TF / B3385 nue mobilization and the pu Post Request for Bids Open - National 290,000.00 0.00 2021-07-16 2021-08-09 2021-07-21 2021-08-11 2021-09-01 2021-10-01 2021-11-05 2022-06-30 rocurement of Furniture and nvelope mentation blic financial management Fixture for GPP-KP PK-GPP KPK-260332-GO-DIR Increasing capacity for reve / E-Stamping System in Khyb TF / B3385 nue mobilization and the pu Post Direct Selection Direct 282,000.00 0.00 Signed 2021-11-02 2021-11-05 2021-11-07 2021-11-05 2021-11-29 2022-05-31 er Pakhtunkhwa blic financial management PK-GPP KPK-364636-GO-DIR Increasing capacity for reve / Inventory Management Syst TF / B3385 nue mobilization and the pu Post Direct Selection Direct - National 17,900.00 0.00 Signed 2023-06-02 2023-06-06 2023-06-07 2023-06-06 2023-06-13 2023-06-30 em for Manual Stamp Papers blic financial management for KP Board of Revenue Page 1 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-GPP KPK-15383-CS-CQS / Hiring of International Institut Improving public investment Consultant Qualifi Open - Internationa e/Academia for Capacity Buil TF / A3361 management and accountab Post 147,020.00 0.00 Canceled 2017-05-17 2017-06-07 2017-05-30 2017-07-21 2017-08-25 2017-08-20 2017-09-24 2018-03-23 cation Selection l ding of Government Officer o ility in public services f Khyber Pakhtunkhwa Pakist an PK-GPP KPK-15393-CS-CQS / Hiring of International Acade Improving public investment mia/Institute for "Establishm Consultant Qualifi Open - Internationa TF / A3361 management and accountab Prior 120,289.00 0.00 Canceled 2017-05-17 2017-06-07 2017-05-31 2017-07-21 2017-08-24 2017-08-20 2017-09-24 2018-03-23 ent of M&E Center of Excelle cation Selection l ility in public services nce and Establishment of Eco nomic Research Developmen t Institute". PK-GPP KPK-21783-CS-CQS / Hiring of Consulting Firm for Increasing capacity for reve Consultant Qualifi Up-gradation of Khyber Pakht TF / A3361 nue mobilization and the pu Post Open - National 38,462.00 53,037.06 Signed 2017-08-04 2017-07-17 2017-08-25 2017-08-23 2017-09-23 2017-12-04 2017-10-23 2018-08-17 2017-11-27 2018-08-17 2019-11-27 cation Selection unkhwa Public Procurement blic financial management Regulatory Authority KP-PPR A web portal. PK-GPP KPK-25826-CS-CQS / Integrated Grievance Redres Improving public investment sal System (IGRS) Consultant Qualifi TF / A3361 management and accountab Post Open - National 28,846.00 194,963.99 Signed 2017-08-23 2017-08-28 2017-09-13 2017-10-25 2017-10-27 2017-11-28 2017-11-26 2018-03-07 2017-12-31 2018-03-16 2018-06-29 Khyber Pakhtunkhwa,At Righ cation Selection ility in public services t to Services Commission, Kh yber Pakhtunkhwa PK-GPP KPK-41439-CS-QCBS / Hiring of firm for Public Fina Increasing capacity for reve Quality And Cost- ncial Management for Streng TF / A3361 nue mobilization and the pu Prior Open - National 1,000,000.00 0.00 Canceled 2017-12-28 2018-01-25 2018-01-18 2018-02-26 2018-03-03 2018-07-06 2018-03-31 2018-08-08 2018-04-30 2018-09-24 2018-06-04 2018-07-09 2019-07-09 Based Selection thening accountability in pub blic financial management lic financial management (PF M) PK-GPP KPK-107911-CS-CQS Increasing capacity for reve Consultant Qualifi / Hiring of communication fir TF / A3361 nue mobilization and the pu Post Open - National 192,300.00 112,023.59 Signed 2019-03-27 2019-03-27 2019-04-17 2019-03-29 2019-05-31 2019-05-17 2019-06-30 2019-07-17 2019-08-04 2019-07-24 2020-01-31 cation Selection m for Khyber Pakhtunkhwa R blic financial management evenue Authority PK-GPP KPK-115588-CS-CQS / Hiring of firm for Developm Increasing capacity for reve ent of Strategic Plan for Khyb Consultant Qualifi TF / A3361 nue mobilization and the pu Post Open - National 76,925.00 0.00 Canceled 2019-06-10 2019-07-01 2019-08-14 2019-08-29 2019-10-03 2020-06-30 er Pakhtunkhwa Revenue Aut cation Selection blic financial management hority under Governance & P olicy Project Khyber Pakhtun khwa PK-GPP KPK-129731-CS-CQS / Hiring of Communication Fir Improving public investment Consultant Qualifi m for the Planning & Develop TF / A3361 management and accountab Post Open - National 43,750.00 0.00 Canceled 2019-09-06 2019-09-03 2019-09-27 2019-11-10 2019-12-10 2020-01-14 2021-01-13 cation Selection ment Department (P&DD) Go ility in public services vernment of Khyber Pakhtun khwa PK-GPP KPK-129736-CS-CQS / Hiring of Consultancy Firm/ Academia to conduct “Citize Improving public investment Consultant Qualifi Under Implement ns’ Perception Survey in relat TF / A3361 management and accountab Post Open - National 62,500.00 0.00 2019-09-09 2019-09-03 2019-09-30 2019-11-13 2019-12-13 2020-01-17 2021-01-16 cation Selection ation ion to service provided by Ri ility in public services ghts to Services Commission (RTS), Govt. of Khyber Pakht unkhwa” PK-GPP KPK-150890-CS-CQS / Consultancy Firm/Academia Improving public investment to conduct Baseline Study to Consultant Qualifi Under Implement TF / A3361 management and accountab Post Open - National 46,000.00 0.00 2019-12-25 2020-03-20 2020-01-15 2020-06-10 2020-02-28 2020-03-29 2020-05-03 2020-10-30 support the government of K cation Selection ation ility in public services hyber Pakhtunkhwa in imple mentation of KP Women Emp owerment Policy PK-GPP KPK-150889-CS-QCB S / The hiring of Consulting fi Increasing capacity for reve Quality And Cost- rm to assist the establishmen TF / A3361 nue mobilization and the pu Post Open - National 400,000.00 0.00 Canceled 2020-01-15 2020-01-31 2020-02-05 2020-03-20 2020-04-17 2020-05-17 2020-06-21 2020-07-26 2021-07-26 Based Selection t of Centre of Excellence (Co blic financial management E) in Procurement in Khyber Pakhtunkhwa PK-GPP KPK-158137-CS-CQS Increasing capacity for reve / Consulting firm to develop a Consultant Qualifi Under Implement TF / A3361 nue mobilization and the pu Post Open - National 300,000.00 0.00 2020-02-12 2020-02-24 2020-03-04 2020-02-26 2020-04-17 2020-05-17 2020-06-21 2020-12-18 nd support procurement func cation Selection ation blic financial management tions in Khyber Pakhtunkhwa PK-GPP KPK-158142-CS-CQS Increasing capacity for reve Consultant Qualifi / Firm for Pension Manageme TF / A3361 nue mobilization and the pu Post Open - National 300,000.00 72,452.88 Signed 2020-02-20 2020-02-28 2020-03-12 2020-03-03 2020-04-25 2020-06-19 2020-05-25 2020-08-18 2020-06-29 2020-08-25 2020-12-26 cation Selection nt for Finance Department blic financial management PK-GPP KPK-158149-CS-CQS Increasing capacity for reve Consultant Qualifi / Consulting firm to assist in TF / A3361 nue mobilization and the pu Post Open - National 300,000.00 0.00 Canceled 2020-02-12 2020-02-08 2020-03-04 2020-04-17 2020-05-17 2020-06-21 2020-12-18 cation Selection public procurement in Khybe blic financial management r Pakhtunkhwa PK-GPP KPK-158592-CS-CQS Increasing capacity for reve Consultant Qualifi Under Implement / Consulting firm to assist wit TF / A3361 nue mobilization and the pu Post Open - National 300,000.00 0.00 2020-02-10 2020-02-11 2020-03-02 2020-04-15 2020-05-15 2020-06-19 2020-12-16 cation Selection ation h Public Procurement in Khyb blic financial management er Pakhtunkhwa PK-GPP KPK-161883-CS-CQS / Third-Party Validation (TPV) Increasing capacity for reve Consultant Qualifi of Recruitment Process of Int TF / A3361 nue mobilization and the pu Post Open - National 60,000.00 4,617.87 Signed 2020-02-28 2020-03-02 2020-03-20 2020-03-03 2020-05-03 2020-05-11 2020-06-02 2020-06-01 2020-07-07 2020-06-13 2021-01-03 cation Selection ernal Support Unit (ISU) in Fi blic financial management nance Department Governm ent of Khyber Pakhtunkhwa PK-GPP KPK-163988-CS-CQS Increasing capacity for reve Consultant Qualifi Under Implement / Communication Firms for G TF / A3361 nue mobilization and the pu Post Open - National 300,000.00 0.00 2020-03-16 2020-03-18 2020-04-06 2020-05-20 2020-06-19 2020-07-24 2021-01-20 cation Selection ation PP implementation partners blic financial management Page 2 PK-GPP KPK-168294-CS-CQS Improving public investment / Development of Grievance Consultant Qualifi TF / A3361 management and accountab Post Open - National 98,000.00 0.00 Canceled 2020-04-16 2020-04-15 2020-05-07 2020-06-20 2020-07-20 2020-08-24 2021-08-19 Redressal Mechanism(GRM) cation Selection ility in public services Khyber Pakhtunkhwa Ombud sperson’s Office PK-GPP KPK-189164-CS-CQS / Procurement of Services for Improving public investment Consultant Qualifi Under Implement Integration of Management I TF / A3361 management and accountab Post Open - National 135,000.00 0.00 2020-08-20 2020-08-29 2020-09-10 2020-08-31 2020-10-24 2020-09-18 2020-11-23 2020-10-13 2020-12-28 2021-12-23 cation Selection ation nformation Systems for effec ility in public services tive Public Investment Manag ement for P&D Department PK-GPP KPK-203143-CS-CQS Improving public investment / Hiring Firm to Develop Gen Consultant Qualifi Under Implement TF / A3361 management and accountab Post Open - National 135,000.00 0.00 2020-11-16 2020-12-09 2020-12-07 2020-12-11 2020-12-26 2021-03-08 2020-12-31 2021-07-15 2021-01-26 2021-11-06 der & Social protection Mana cation Selection ation ility in public services gement Information System ( GSMIS) for P&DD PK-GPP KPK-233222-CS-CQS Improving public investment Consultant Qualifi / Impact Assessment of IT Pr TF / B3385 management and accountab Post Open - National 150,000.00 0.00 Signed 2021-05-19 2021-06-08 2021-06-03 2021-09-20 2021-06-22 2021-12-14 2021-06-27 2021-12-31 2021-07-07 2022-01-03 cation Selection ojects’ Interventions Govern ility in public services ment of KP PK-GPP KPK-251843-CS-CQS Improving public investment Consultant Qualifi Under Implement / PPP Advisory Consulting Ser TF / B3385 management and accountab Post Open - National 190,000.00 0.00 2021-09-07 2021-09-03 2021-09-28 2021-09-06 2021-10-17 2021-10-24 2021-11-08 2022-06-30 cation Selection ation vices ility in public services PK-GPP KPK-251845-CS-CQS Improving public investment / Hiring of firm for Technical Consultant Qualifi Under Implement TF / B3385 management and accountab Post Open - National 95,000.00 0.00 2021-09-07 2021-09-10 2021-09-28 2021-09-13 2021-10-17 2021-10-24 2021-11-08 2022-06-30 Assistance in Establishment cation Selection ation ility in public services and Operationalization of Del ivery Unit, P&DD PK-GPP KPK-253481-CS-CQS Improving public investment / Hiring of firm for Developm Consultant Qualifi Under Implement TF / B3385 management and accountab Post Open - National 93,750.00 0.00 2021-09-30 2021-10-01 2021-10-21 2021-10-07 2021-11-09 2021-11-16 2021-12-01 2022-06-30 ent of Inquiry & Complaint M cation Selection ation ility in public services anagement System (ICMS) fo r ACE GoKP PK-GPP KPK-257057-CS-CQS Increasing capacity for reve Consultant Qualifi Under Implement / Hiring of firm for Developm TF / B3385 nue mobilization and the pu Post Open - National 62,500.00 0.00 2021-10-12 2021-10-28 2021-11-02 2021-11-03 2021-11-21 2021-11-28 2021-12-13 2022-06-30 cation Selection ation ent of Digitization Strategy K blic financial management P-PPRA PK-GPP KPK-257064-CS-CQS Improving public investment / Engagement of Academia/T Consultant Qualifi Under Implement TF / B3385 management and accountab Post Open - National 62,500.00 0.00 2021-10-12 2021-10-28 2021-11-02 2021-11-03 2021-11-21 2021-11-28 2021-12-13 2022-06-30 raining Institute training of P cation Selection ation ility in public services ublic Information Officers for RTI Commission KP PK-GPP KPK-273714-CS-CQS Improving public investment Consultant Qualifi Under Implement / Engagement of Training Ins TF / B3385 management and accountab Post Open - National 62,500.00 0.00 2022-01-25 2022-02-15 2022-02-09 2022-03-25 2022-02-21 2022-02-28 2022-03-15 2022-06-27 cation Selection ation titute for Training of District ility in public services Officers for RTPS PK-GPP KPK-277402-CS-CQS / Citizens' Perception Survey Improving public investment Consultant Qualifi (Round-II) For Selected Notifi TF / B3385 management and accountab Post Open - National 93,750.00 0.00 Signed 2022-02-10 2022-02-15 2022-02-25 2022-03-04 2022-03-09 2022-06-02 2022-03-16 2022-12-19 2022-03-31 2022-06-30 cation Selection ed Services under Right to Pu ility in public services blic Services Commission KP PK-GPP KPK-277405-CS-CQS / Engagement of Training Ins Improving public investment Consultant Qualifi titute for Training of District TF / B3385 management and accountab Post Open - National 31,250.00 0.00 Canceled 2022-02-10 2022-02-25 2022-03-09 2022-03-16 2022-03-31 2022-06-30 cation Selection Officers for Khyber Pakhtunk ility in public services hwa Right To Public Services Commission PK-GPP KPK-279112-CS-CQS Increasing capacity for reve / Hiring of firm Business Proc Consultant Qualifi Under Implement TF / B3385 nue mobilization and the pu Post Open - National 95,000.00 0.00 2022-02-17 2022-02-28 2022-03-04 2022-03-31 2022-03-16 2022-05-17 2022-03-23 2022-05-30 2022-04-02 2022-06-30 ess Re-engineering of Select cation Selection ation blic financial management ed Services in Khyber Pakhtu nkhwa for KPITB PK-GPP KPK-231013-CS-CQS Increasing capacity for reve Consultant Qualifi / Survey for Sales Tax on Ser TF / B3385 nue mobilization and the pu Post Open - National 68,000.00 0.00 Canceled 2021-04-28 2021-05-27 2021-05-13 2021-06-07 2021-06-02 2021-06-12 2021-07-01 2021-12-28 cation Selection vices in Mardan & Bannu Reg blic financial management ions PK-GPP KPK-158140-CS-CQS Increasing capacity for reve Consultant Qualifi / Investment and Tax advisor TF / A3361 nue mobilization and the pu Post Open - National 300,000.00 0.00 Canceled 2020-02-12 2020-03-04 2020-04-17 2020-05-17 2020-06-21 2020-12-18 cation Selection y Firm blic financial management PK-GPP KPK-126423-CS-CQS / Hiring of Legal Advisory Fir Improving public investment Consultant Qualifi m Planning & Development D TF / A3361 management and accountab Post Open - National 100,000.00 0.00 Canceled 2019-08-16 2019-08-16 2019-09-06 2019-08-19 2019-10-20 2019-11-19 2019-12-24 2020-06-30 cation Selection epartment (P&DD) Governme ility in public services nt of Khyber Pakhtunkhwa PK-GPP KPK-347369-CS-CQS Providing effective support f Consultant Qualifi / Consulting firm for End of Pr TF / B3385 or the coordination of gover Post Open - National 180,000.00 0.00 Signed 2023-03-31 2023-04-03 2023-04-15 2023-04-05 2023-04-27 2023-05-11 2023-05-04 2023-05-19 2023-05-19 2023-06-30 cation Selection oject Evaluation GPP nance reforms and operatio nal management INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-GPP KPK-5798-CS-INDV / Hiring of Public Private Partn Providing effective support f ership Specialist Governance or the coordination of gover Individual Consult TF / A3361 Post Open 75,600.00 32,841.52 Terminated 2017-05-18 2017-07-06 2017-10-10 2017-07-27 2017-10-11 2017-08-31 2017-11-01 2018-08-30 Reforms Support Unit (GSRU) nance reforms and operatio ant Selection , Governance and Policy Proj nal management ect Khyber Pakhtunkhwa-Pak istan PK-GPP KPK-5800-CS-INDV / Providing effective support f Hiring of Learning & Gender or the coordination of gover Individual Consult Specialist, Operational Suppo TF / A3361 Post Open 75,600.00 30,636.13 Signed 2017-05-18 2017-07-06 2017-10-10 2017-07-27 2017-10-23 2017-08-31 2017-10-23 2018-08-30 nance reforms and operatio ant Selection rt Unit, Governance & Policy nal management Project Khyber Pakhtunkhwa- Pakistan PK-GPP KPK-15396-CS-CDS / Hiring of International Consul Improving public investment ting Firm to Develop New Pu TF / A3361 management and accountab Prior Direct Selection Direct 96,154.00 323,077.83 Signed 2017-05-17 2017-05-27 2017-05-30 2017-07-31 2017-10-16 2018-01-27 blic Investment Management ility in public services Framework for Khyber Pakht unkhwa Pakistan PK-GPP KPK-15406-CS-INDV Providing effective support f / Hiring of Contract Administr or the coordination of gover Individual Consult ation Specialist-Operational S TF / A3361 Post Open 75,600.00 32,841.52 Signed 2017-05-18 2017-07-06 2017-10-10 2017-07-27 2017-10-11 2017-08-31 2017-10-13 2018-08-30 nance reforms and operatio ant Selection upport Unit -Governance & P nal management olicy Project, Khyber Pakhtun khwa-Pakistan Page 3 PK-GPP KPK-15408-CS-INDV / Hiring of Citizen Engageme Providing effective support f nt & Social Sector Specialist- or the coordination of gover Individual Consult Governance & Policy Project- TF / A3361 Post Open 75,600.00 32,841.52 Signed 2017-05-18 2017-07-06 2017-10-10 2017-07-27 2017-10-11 2017-08-31 2017-10-17 2018-08-30 nance reforms and operatio ant Selection Governance Reforms Support nal management Unit-Planning & Development Department, Khyber Pakhtun khwa-Pakistan PK-GPP KPK-21633-CS-INDV Increasing capacity for reve / Hiring of Lead Business Inte Individual Consult TF / A3361 nue mobilization and the pu Post Open 48,077.00 23,927.51 Signed 2017-08-09 2017-08-15 2017-09-12 2018-11-26 2017-10-03 2018-11-26 2017-11-07 2018-12-13 2018-02-15 lligence Expert-KPRA for Incr ant Selection blic financial management easing capacity for revenue mobilization. PK-GPP KPK-30536-CS-INDV / Hiring of Integrity Specialist Improving public investment Individual Consult for Establishment of Peshawa TF / A3361 management and accountab Post Open 33,972.00 0.00 Canceled 2017-10-05 2017-11-08 2017-12-07 2017-11-29 2018-01-03 2019-01-03 ant Selection r High Court Secretariat for D ility in public services istrict Judiciary Performance Management-SDJPM PK-GPP KPK-30541-CS-INDV / Hiring of Knowledge Manag Improving public investment ement & IT Specialist for Esta Individual Consult TF / A3361 management and accountab Post Open 22,642.00 32,549.72 Signed 2017-10-05 2017-11-08 2017-12-07 2017-11-29 2017-12-08 2018-01-03 2017-12-08 2019-01-03 blishment of Peshawar High ant Selection ility in public services Court Secretariat for District J udiciary Performance Manag ement-SDJPM PK-GPP KPK-30542-CS-INDV / Hiring of Strategic Manage Improving public investment ment Specialist for Establish Individual Consult TF / A3361 management and accountab Post Open 22,642.00 32,549.72 Signed 2017-10-05 2017-11-08 2017-12-07 2017-11-29 2017-12-08 2018-01-03 2017-12-08 2019-01-03 ment of Peshawar High Court ant Selection ility in public services Secretariat for District Judicia ry Performance Management -SDJPM PK-GPP KPK-30545-CS-INDV / Hiring of Human Resource S Improving public investment pecialist for Establishment of Individual Consult TF / A3361 management and accountab Post Open 33,972.00 46,055.91 Signed 2017-10-10 2017-11-13 2017-12-07 2017-12-04 2018-01-01 2018-01-08 2018-01-01 2019-01-08 Peshawar High Court Secreta ant Selection ility in public services riat for District Judiciary Perfo rmance Management-SDJPM PK-GPP KPK-30537-CS-INDV / Hiring of Internal Audit Spec Improving public investment Individual Consult ialist for Establishment of Pes TF / A3361 management and accountab Post Open 33,972.00 48,824.59 Signed 2017-10-10 2017-11-13 2017-12-07 2017-12-04 2017-12-08 2018-01-08 2017-12-08 2019-01-08 ant Selection hawar High Court Secretariat ility in public services for District Judiciary Performa nce Management-SDJPM PK-GPP KPK-30540-CS-INDV / Hiring of Financial Manage Improving public investment ment Specialist for Establish Individual Consult TF / A3361 management and accountab Post Open 33,972.00 48,758.49 Signed 2017-10-10 2017-10-09 2017-11-13 2017-12-07 2017-12-04 2017-12-11 2018-01-08 2017-12-11 2019-01-08 ment of Peshawar High Court ant Selection ility in public services Secretariat for District Judicia ry Performance Management -SDJPM PK-GPP KPK-21621-CS-INDV Increasing capacity for reve / Hiring of Lead Sales Tax Ex Individual Consult TF / A3361 nue mobilization and the pu Post Open 48,077.00 0.00 Canceled 2017-08-07 2017-08-15 2017-09-10 2017-10-01 2017-11-05 2018-04-04 pert-KPRA fir Increasing capa ant Selection blic financial management city for revenue mobilization PK-GPP KPK-21637-CS-INDV / Hiring of Lead HR Expert-KP Increasing capacity for reve Individual Consult RA for Increasing capacity for TF / A3361 nue mobilization and the pu Post Open 43,260.00 0.00 Canceled 2017-08-11 2017-08-18 2017-09-14 2017-10-05 2017-11-09 2018-11-09 ant Selection revenue mobilization and the blic financial management public financial management . PK-GPP KPK-35977-CS-INDV Increasing capacity for reve / Hiring of Lead Sales Tax Ex Individual Consult TF / A3361 nue mobilization and the pu Post Limited 48,077.00 0.00 Canceled 2017-11-08 2017-08-18 2017-11-13 2017-11-18 2017-11-28 2018-11-28 pert-KPRA fir Increasing capa ant Selection blic financial management city for revenue mobilization PK-GPP KPK-35983-CS-INDV / Hiring of Lead HR Expert-KP Increasing capacity for reve Individual Consult RA for Increasing capacity for TF / A3361 nue mobilization and the pu Post Limited 43,260.00 40,632.08 Signed 2017-11-08 2017-08-18 2017-11-13 2018-01-04 2017-11-18 2018-01-10 2017-11-28 2018-01-10 2018-11-28 ant Selection revenue mobilization and the blic financial management public financial management . PK-GPP KPK-48098-CS-INDV / Hiring of Lead Consultant fo Improving public investment Individual Consult r Development of "Sustainabl TF / A3361 management and accountab Post Limited 52,381.00 36,548.52 Signed 2018-02-08 2018-02-23 2018-02-18 2019-01-07 2018-02-28 2019-01-06 2018-03-14 2019-01-10 2018-06-22 ant Selection e Development Strategy and ility in public services Implementation Framework 2 018-2023 PK-GPP KPK-48308-CS-INDV / Hiring of Reforms Coordinat Increasing capacity for reve Individual Consult or for Establishment of Tax P TF / A3361 nue mobilization and the pu Post Open 42,857.00 24,352.62 Signed 2018-02-09 2017-11-30 2018-03-30 2018-07-18 2018-04-20 2018-08-15 2018-05-25 2018-09-03 2019-05-25 ant Selection olicy Unit at Finance Depart blic financial management ment Khyber Pakhtunkhwa PK-GPP KPK-48310-CS-INDV / Hiring of Debt Managment Increasing capacity for reve Individual Consult Specialist for Establishment o TF / A3361 nue mobilization and the pu Post Open 60,000.00 25,737.26 Signed 2018-02-09 2017-11-30 2018-03-30 2018-07-18 2018-04-20 2018-10-16 2018-05-25 2018-10-19 2019-05-25 ant Selection f Debt Management Unit at Fi blic financial management nance Department Khyber Pa khtunkhwa PK-GPP KPK-48311-CS-INDV / Hiring of Financial Analyst f Increasing capacity for reve Individual Consult or Establishment of Debt Ma TF / A3361 nue mobilization and the pu Post Open 34,286.00 9,651.47 Signed 2018-02-09 2017-11-30 2018-03-30 2018-07-18 2018-04-20 2018-10-31 2018-05-25 2018-11-06 2019-05-25 ant Selection nagement Unit at Finance De blic financial management partment Khyber Pakhtunkh wa PK-GPP KPK-48312-CS-INDV / Hiring of Financial Analyst f Increasing capacity for reve Individual Consult or Establishment of Debt Ma TF / A3361 nue mobilization and the pu Post Open 34,286.00 14,611.57 Signed 2018-02-09 2017-11-30 2018-03-30 2018-08-15 2018-04-20 2018-08-15 2018-05-25 2018-09-07 2019-05-25 ant Selection nagement Unit at Finance De blic financial management partment Khyber Pakhtunkh wa PK-GPP KPK-48313-CS-INDV / Hiring of Head of Corporate Governance Regulations and Increasing capacity for reve Individual Consult Compliance for Establishmen TF / A3361 nue mobilization and the pu Post Open 60,000.00 36,518.58 Signed 2018-02-09 2017-11-30 2018-03-30 2018-07-18 2018-04-20 2018-08-15 2018-05-25 2018-08-28 2019-05-25 ant Selection t of Corporate Governance R blic financial management egulatory & Compliance Unit at Finance Department Khyb er Pakhtunkhwa Page 4 PK-GPP KPK-48314-CS-INDV / Hiring of Performance and Increasing capacity for reve Monitoring Specialist for Esta Individual Consult TF / A3361 nue mobilization and the pu Post Open 60,000.00 29,214.86 Signed 2018-02-09 2017-11-30 2018-03-30 2018-07-18 2018-04-20 2018-08-15 2018-05-25 2018-08-16 2019-05-25 blishment of Corporate Gove ant Selection blic financial management rnance Regulatory & Complia nce Unit at Finance Departm ent Khyber Pakhtunkhwa PK-GPP KPK-48315-CS-INDV / Hiring of Learning and Com Increasing capacity for reve munication Coordinator for E Individual Consult TF / A3361 nue mobilization and the pu Post Open 60,000.00 24,352.62 Signed 2018-02-09 2017-11-30 2018-03-30 2018-07-18 2018-04-20 2018-08-15 2018-05-25 2018-08-17 2019-05-25 stablishment of Corporate Go ant Selection blic financial management vernance Regulatory & Comp liance Unit at Finance Depart ment Khyber Pakhtunkhwa PK-GPP KPK-48316-CS-INDV / Hiring of Research and Data Increasing capacity for reve Analyst for Establishment of Individual Consult TF / A3361 nue mobilization and the pu Post Open 68,572.00 7,366.67 Signed 2018-02-09 2017-11-30 2018-03-30 2018-07-18 2018-04-20 2018-08-15 2018-05-25 2018-08-17 2019-05-25 Corporate Governance Regul ant Selection blic financial management atory & Compliance Unit at Fi nance Department Khyber Pa khtunkhwa PK-GPP KPK-48303-CS-INDV / Hiring of Senior Analyst and Improving public investment Content Compiler for Develo Individual Consult TF / A3361 management and accountab Post Limited 19,048.00 14,092.38 Signed 2018-02-26 2018-02-15 2018-03-03 2019-01-07 2018-03-08 2019-01-07 2018-03-18 2019-01-10 2018-09-14 pment of "Sustainable Devel ant Selection ility in public services opment Strategy and Implem entation Framework 2018-20 23 PK-GPP KPK-48299-CS-INDV / Hiring of Institutional Expert Improving public investment Individual Consult for Development of "Sustaina TF / A3361 management and accountab Post Limited 38,096.00 18,797.00 Signed 2018-02-26 2018-02-15 2018-03-03 2019-01-07 2018-03-08 2019-01-07 2018-03-18 2019-01-10 2018-09-14 ant Selection ble Development Strategy an ility in public services d Implementation Framework 2018-2023 PK-GPP KPK-48300-CS-INDV / Hiring of Lead Researcher f Improving public investment Individual Consult or Development of "Sustaina TF / A3361 management and accountab Post Limited 34,286.00 24,167.57 Signed 2018-02-26 2018-02-15 2018-03-03 2019-01-06 2018-03-08 2019-01-06 2018-03-18 2019-01-10 2018-09-14 ant Selection ble Development Strategy an ility in public services d Implementation Framework 2018-2023 PK-GPP KPK-48309-CS-INDV / Hiring of Research Analyst-I Increasing capacity for reve Individual Consult for Establishment of Tax Polic TF / A3361 nue mobilization and the pu Post Open 34,286.00 11,350.17 Signed 2018-02-26 2017-11-30 2018-04-16 2018-07-18 2018-05-07 2018-08-15 2018-06-11 2018-08-16 2019-06-11 ant Selection y Unit at Finance Department blic financial management Khyber Pakhtunkhwa PK-GPP KPK-51239-CS-INDV / Hiring of Research Analyst-I Increasing capacity for reve Individual Consult I for Establishment of Tax Pol TF / A3361 nue mobilization and the pu Post Open 34,286.00 13,393.94 Signed 2018-02-26 2017-11-30 2018-04-16 2018-07-18 2018-05-07 2018-08-15 2018-06-11 2018-08-17 2019-06-11 ant Selection icy Unit at Finance Departme blic financial management nt Khyber Pakhtunkhwa PK-GPP KPK-51241-CS-INDV / Hiring of Research Analyst-I Increasing capacity for reve Individual Consult II for Establishment of Tax Po TF / A3361 nue mobilization and the pu Post Open 34,286.00 19,482.10 Signed 2018-02-26 2018-02-15 2018-04-16 2018-07-18 2018-05-07 2018-08-15 2018-06-11 2018-08-16 2019-06-11 ant Selection licy Unit at Finance Departm blic financial management ent Khyber Pakhtunkhwa PK-GPP KPK-48320-CS-INDV / Hiring of Sector Expert The matic Area-Governance and Improving public investment Individual Consult Resource Mobilization Expert TF / A3361 management and accountab Post Limited 20,000.00 3,537.09 Signed 2018-03-15 2018-10-17 2018-03-25 2019-02-12 2018-04-04 2019-02-12 2018-04-18 2019-02-26 2018-09-28 ant Selection for (Cross Cutting Issues) for ility in public services Development of Sustainable Development Strategy 2018- 2023 PK-GPP KPK-48317-CS-INDV / Hiring of Sector Expert The Improving public investment Individual Consult matic Area-Energy Security f TF / A3361 management and accountab Post Limited 20,000.00 4,602.32 Signed 2018-03-15 2018-10-17 2018-03-25 2019-02-12 2018-04-04 2019-02-12 2018-04-18 2019-02-21 2018-09-28 ant Selection or Development of Sustainab ility in public services le Development Strategy 201 8-2023. PK-GPP KPK-48318-CS-INDV / Hiring of Sector Expert The Improving public investment matic Area-Economic Growth Individual Consult TF / A3361 management and accountab Post Limited 20,000.00 5,585.34 Signed 2018-03-15 2018-10-17 2018-03-25 2019-02-12 2018-04-04 2019-02-12 2018-04-18 2019-02-21 2018-09-28 and Employment Opportuniti ant Selection ility in public services es for Development of Sustai nable Development Strategy 2018-2023 PK-GPP KPK-54292-CS-INDV / Hiring of Sector Expert for T Improving public investment hematic Area-Food Security a Individual Consult TF / A3361 management and accountab Post Limited 20,000.00 5,540.66 Signed 2018-03-15 2018-10-17 2018-03-25 2019-02-12 2018-04-04 2019-02-12 2018-04-18 2019-02-21 2018-09-28 nd Safe Environment for Dev ant Selection ility in public services elopment of Sustainable Dev elopment Strategy 2018-202 3. PK-GPP KPK-54294-CS-INDV / Hiring of Sector Expert The Improving public investment Individual Consult matic Area-Good Health and TF / A3361 management and accountab Post Limited 20,000.00 5,254.69 Signed 2018-03-15 2018-10-17 2018-03-25 2019-02-12 2018-04-04 2019-02-12 2018-04-18 2019-02-18 2018-09-28 ant Selection Well-Being for Development ility in public services of Sustainable Development Strategy 2018-2023. PK-GPP KPK-54295-CS-INDV / Hiring of Sector Expert The Improving public investment matic Area-Quality Education Individual Consult TF / A3361 management and accountab Post Limited 20,000.00 7,372.65 Signed 2018-03-15 2018-10-17 2018-03-25 2019-02-12 2018-04-04 2019-02-12 2018-04-18 2019-02-18 2018-09-28 and Lifelong Learning for Dev ant Selection ility in public services elopment of Sustainable Dev elopment Strategy 2018-202 3. PK-GPP KPK-54296-CS-INDV / Hiring of Sector Expert The Improving public investment Individual Consult matic Area-Urban Developme TF / A3361 management and accountab Post Limited 20,000.00 8,936.55 Signed 2018-03-15 2018-10-17 2018-03-25 2019-02-12 2018-04-04 2019-02-12 2018-04-18 2019-02-18 2018-09-28 ant Selection nt for Development of Sustai ility in public services nable Development Strategy 2018-2023. PK-GPP KPK-54297-CS-INDV / Hiring of Sector Expert The Improving public investment Individual Consult matic Area-Peace and Rule of TF / A3361 management and accountab Post Limited 20,000.00 2,393.21 Signed 2018-03-15 2018-10-17 2018-03-25 2019-02-12 2018-04-04 2019-02-12 2018-04-18 2019-02-18 2018-09-28 ant Selection Law for Development of Sust ility in public services ainable Development Strateg y 2018-2023. PK-GPP KPK-78608-CS-INDV / Hiring of Private Sector Exp Improving public investment ert (Commercial Water Use & Individual Consult TF / A3361 management and accountab Post Limited 10,000.00 0.00 Canceled 2018-09-19 2018-09-19 2018-09-29 2018-10-09 2018-10-23 2018-12-22 Investment) for Formulation ant Selection ility in public services of Integrated Water Resource Management (IWRM) Strateg y Khyber Pakhtunkhwa Page 5 PK-GPP KPK-78610-CS-INDV / Hiring of Domestic Drinking Improving public investment & Sanitation Expert for Form Individual Consult TF / A3361 management and accountab Post Limited 10,000.00 0.00 Canceled 2018-09-19 2018-09-19 2018-09-29 2018-10-09 2018-10-23 2018-12-22 ulation of Integrated Water R ant Selection ility in public services esource Management (IWRM) Strategy Khyber Pakhtunkhw a PK-GPP KPK-78612-CS-INDV / Hiring of Technical Expert E Improving public investment nergy & Hydro Power for For Individual Consult TF / A3361 management and accountab Post Limited 20,000.00 0.00 Canceled 2018-09-19 2018-09-19 2018-09-29 2018-10-09 2018-10-23 2019-04-21 mulation of Integrated Water ant Selection ility in public services Resource Management (IWR M)Strategy Khyber Pakhtunk hwa PK-GPP KPK-78617-CS-INDV / Hiring of Website Developer Improving public investment Individual Consult for Public Private Partnership TF / A3361 management and accountab Post Limited 10,000.00 0.00 Canceled 2018-09-19 2019-11-05 2018-09-24 2018-10-15 2018-11-19 2019-06-17 ant Selection (PPP) Unit Under Planning an ility in public services d Development Department Khyber Pakhtunkhwa PK-GPP KPK-82423-CS-INDV Improving public investment / Hiring the Services of Legal Individual Consult TF / A3361 management and accountab Post Limited 20,000.00 35,000.00 Signed 2018-10-22 2018-10-22 2018-10-27 2018-12-06 2018-11-11 2018-12-07 2018-12-01 2018-12-07 2019-05-30 Advisor fro Planning and Dev ant Selection ility in public services elopment Department Khybe r Pakhtunkhwa. PK-GPP KPK-94027-CS-INDV Improving public investment / HIRING OF DONORS EXPERT Individual Consult TF / A3361 management and accountab Post Limited 15,000.00 0.00 Canceled 2019-01-14 2019-07-29 2019-01-19 2020-06-29 2019-01-29 2019-02-18 2020-02-18 FOR FOREIGN AID SECTION, ant Selection ility in public services P&D DEPARTMENT KHYBER P AKHTUNKHWA. PK-GPP KPK-48307-CS-INDV / Hiring of Tax Policy Econom Increasing capacity for reve Individual Consult ist for Establishment of Tax P TF / A3361 nue mobilization and the pu Post Open 60,000.00 0.00 Canceled 2018-02-09 2017-11-30 2018-03-30 2018-04-20 2018-05-25 2019-05-25 ant Selection olicy Unit at Finance Depart blic financial management ment Khyber Pakhtunkhwa PK-GPP KPK-110302-CS-IND V / Hiring of HEAD, INVESTME Increasing capacity for reve NT CLIMATE for Tax Policy Un Individual Consult TF / A3361 nue mobilization and the pu Post Limited 60,000.00 55,520.52 Signed 2019-04-24 2019-04-24 2019-04-29 2019-06-10 2019-05-09 2019-06-10 2019-05-26 2019-06-12 2020-05-25 it, Khyber Pakhtunkhwa Reve ant Selection blic financial management nue Authority under Finance Department Khyber Pakhtun khwa PK-GPP KPK-110303-CS-IND Increasing capacity for reve V / Hiring of Organization De Individual Consult TF / A3361 nue mobilization and the pu Post Limited 30,000.00 18,636.25 Signed 2019-04-25 2019-07-09 2019-05-04 2019-07-04 2019-05-11 2019-07-29 2019-05-21 2019-08-07 2019-06-30 velopment Expert (OD) for K ant Selection blic financial management hyber Pakhtunkhwa Revenue Authority- KP-PRA PK-GPP KPK-115577-CS-CQS / Hiring of Communication Ex Increasing capacity for reve Individual Consult pert for Khyber Pakhtunkhwa TF / A3361 nue mobilization and the pu Post Open 36,000.00 28,427.04 Signed 2019-07-01 2019-07-01 2019-08-19 2019-10-16 2019-09-09 2019-10-24 2019-09-24 2019-10-26 2020-06-30 ant Selection Revenue Authority under Go blic financial management vernance and Policy Project K hyber Pakhtunkhwa PK-GPP KPK-115582-CS-CQS / Hiring of Legal/Fiscal Law E Increasing capacity for reve Individual Consult xpert for Khyber Pakhtunkhw TF / A3361 nue mobilization and the pu Post Open 36,000.00 20,467.47 Signed 2019-07-01 2019-07-01 2019-07-30 2019-10-16 2019-08-14 2019-10-24 2019-09-07 2019-10-26 2020-06-30 ant Selection a Revenue Authority under G blic financial management overnance & Policy Project K hyber Pakhtunkhwa PK-GPP KPK-115587-CS-CQS / Hiring of Information and Co Increasing capacity for reve mmunication Technology (IC Individual Consult TF / A3361 nue mobilization and the pu Post Open 36,000.00 41,692.99 Signed 2019-07-01 2019-07-01 2019-07-30 2019-10-16 2019-08-14 2019-10-24 2019-09-18 2019-10-26 2020-06-30 T) Expert for Khyber Pakhtun ant Selection blic financial management khwa Revenue Authority und er Governance & Policy Proje ct Khyber Pakhtunkhwa PK-GPP KPK-121220-CS-IND V / Hiring of Institutional Exp ert to Conduct Diagnostic Stu Improving public investment Individual Consult dy for Strengthening and Res TF / A3361 management and accountab Post Limited 26,000.00 0.00 Canceled 2019-07-16 2019-07-26 2019-08-05 2019-08-15 2019-10-14 ant Selection tructuring of Anti-Corruption ility in public services Establishment Khyber Pakhtu nkhwa under Governance an d Policy Project Khyber Pakht unkhwa PK-GPP KPK-122216-CS-IND V / Hiring of Short-Term Indiv Improving public investment idual Consultant to review an Individual Consult TF / A3361 management and accountab Post Limited 10,000.00 7,654.28 Signed 2019-07-17 2019-07-17 2019-07-22 2019-07-24 2019-08-01 2019-08-20 2019-08-16 2019-08-29 2019-09-30 d finalize “Public Investment ant Selection ility in public services Management (PIM) Action Pla n for Khyber Pakhtunkhwa” G overnment of Khyber Pakhtu nkhwa PK-GPP KPK-124373-CS-IND V / The hiring of Institutional Development Consultant to C Improving public investment onduct Diagnostic Study for Individual Consult TF / A3361 management and accountab Post Open 26,000.00 16,993.97 Signed 2019-08-01 2019-08-01 2019-09-19 2019-10-03 2019-10-10 2019-10-03 2019-11-14 2019-10-04 2020-05-12 Strengthening and Restructu ant Selection ility in public services ring of Anti-Corruption Establ ishment Khyber Pakhtunkhw a under Governance and Poli cy Project Khyber Pakhtunkh wa. PK-GPP KPK-128284-CS-IND V / The hiring of Short-Term HR & Operation Management Improving public investment Individual Consult Consultant for revision of Op TF / A3361 management and accountab Post Limited 10,000.00 7,399.14 Signed 2019-08-27 2019-08-23 2019-09-01 2019-09-26 2019-09-11 2019-10-01 2019-09-28 2019-10-08 2019-11-12 ant Selection erational and Financial Mana ility in public services gement Manuals of Governan ce and Policy Project Khyber Pakhtunkhwa PK-GPP KPK-128294-CS-IND V / HIRING OF INVESTMENT F ACILITATION SPECIALIST PLA Improving public investment Individual Consult NNING AND DEVELOPMENT D TF / A3361 management and accountab Post Limited 20,000.00 0.00 Canceled 2019-08-28 2019-08-23 2019-09-02 2019-09-12 2019-09-29 2020-09-28 ant Selection EPARTMENT KHYBER PAKHTU ility in public services NKHWA UNDER GOVERNANC E AND POLICY PROJECT KHYB ER PAKHTUNKHWA PK-GPP KPK-128302-CS-IND V / Hiring of Information Tech Increasing capacity for reve nology Specialist for Finance Individual Consult TF / A3361 nue mobilization and the pu Post Limited 15,000.00 3,986.61 Signed 2019-08-29 2019-08-23 2019-09-03 2019-08-29 2019-09-13 2019-08-30 2019-09-30 2019-08-30 2019-12-29 Department Khyber Pakhtun ant Selection blic financial management khwa under Governance and Policy Project Khyber Pakhtu nkhwa Page 6 PK-GPP KPK-133009-CS-IND V / The hiring of Team Leade Increasing capacity for reve r – Corporate Governance Un Individual Consult TF / A3361 nue mobilization and the pu Post Open 37,500.00 0.00 Canceled 2019-09-20 2019-09-20 2019-10-29 2019-11-08 2019-12-02 2020-06-30 it, Finance Department Khyb ant Selection blic financial management er Pakhtunkhwa under Gover nance and Policy Project Khy ber Pakhtunkhwa PK-GPP KPK-133010-CS-IND V / The hiring of Performance & Monitoring Specialist – Cor Increasing capacity for reve Individual Consult porate Governance Unit, Fina TF / A3361 nue mobilization and the pu Post Open 26,250.00 0.00 Canceled 2019-09-20 2019-09-20 2019-10-29 2019-11-08 2019-12-02 2020-06-30 ant Selection nce Department Khyber Pakh blic financial management tunkhwa under Governance a nd Policy Project Khyber Pak htunkhwa PK-GPP KPK-133013-CS-IND V / Hiring of Financial Manag Increasing capacity for reve ement Expert – Corporate Go Individual Consult TF / A3361 nue mobilization and the pu Post Open 26,252.00 26,381.92 Signed 2019-09-20 2019-09-20 2019-10-29 2020-02-08 2019-11-08 2020-02-08 2019-12-02 2020-02-11 2020-06-30 vernance Unit, Finance Depa ant Selection blic financial management rtment Khyber Pakhtunkhwa under Governance and Policy Project Khyber Pakhtunkhwa PK-GPP KPK-133015-CS-IND V / The hiring of Financial Ma nagement Research Analyst Increasing capacity for reve Individual Consult – Corporate Governance Unit, TF / A3361 nue mobilization and the pu Post Open 15,000.00 0.00 Canceled 2019-09-20 2019-09-20 2019-10-29 2019-11-08 2019-12-02 2020-06-30 ant Selection Finance Department Khyber blic financial management Pakhtunkhwa under Governa nce and Policy Project Khyber Pakhtunkhwa PK-GPP KPK-133016-CS-IND V / The hiring of Performance Monitoring Research Analyst Increasing capacity for reve Individual Consult – Corporate Governance Unit, TF / A3361 nue mobilization and the pu Post Open 15,000.00 15,075.38 Signed 2019-09-20 2019-09-20 2019-10-29 2020-02-08 2019-11-08 2020-02-08 2019-12-02 2020-02-11 2020-06-30 ant Selection Finance Department Khyber blic financial management Pakhtunkhwa under Governa nce and Policy Project Khyber Pakhtunkhwa PK-GPP KPK-142552-CS-IND Increasing capacity for reve V / The hiring of Economist fo Individual Consult TF / A3361 nue mobilization and the pu Post Open 40,000.00 0.00 Canceled 2019-11-01 2019-10-31 2019-12-20 2020-01-10 2020-02-14 2021-02-13 r Khyber Pakhtunkhwa Reven ant Selection blic financial management ue Authority (KPRA) PK-GPP KPK-142555-CS-IND Increasing capacity for reve V / The Hiring of Sociologist f Individual Consult TF / A3361 nue mobilization and the pu Post Open 40,000.00 0.00 Canceled 2019-11-01 2019-10-31 2019-12-20 2020-01-10 2020-02-14 2021-02-13 or Khyber Pakhtunkhwa Reve ant Selection blic financial management nue Authority (KPRA) PK-GPP KPK-142556-CS-IND Increasing capacity for reve V / The Hiring of Statistician f Individual Consult TF / A3361 nue mobilization and the pu Post Open 16,000.00 0.00 Canceled 2019-11-01 2019-11-27 2019-12-20 2020-01-10 2020-02-14 2021-02-13 or Khyber Pakhtunkhwa Reve ant Selection blic financial management nue Authority (KPRA) PK-GPP KPK-150887-CS-IND Improving public investment Individual Consult V / The hiring of Short Term P TF / A3361 management and accountab Post Limited 15,000.00 0.00 Canceled 2019-12-23 2019-12-28 2020-01-18 2020-02-22 2020-04-07 ant Selection lanning Expert for P&D for de ility in public services velopment of PC-I PK-GPP KPK-153217-CS-IND Improving public investment Individual Consult V / The hiring of Planning Exp TF / A3361 management and accountab Post Limited 24,000.00 11,306.54 Signed 2020-01-15 2020-01-14 2020-01-20 2020-01-17 2020-02-10 2020-01-28 2020-03-16 2020-02-02 2021-03-11 ant Selection ert for P&DD ility in public services Improving public investment PK-GPP KPK-156376-CS-IND Individual Consult TF / A3361 management and accountab Post Limited 20,000.00 10,770.39 Signed 2020-02-11 2020-02-07 2020-02-16 2020-02-11 2020-03-08 2020-02-25 2020-04-12 2020-02-27 2020-10-09 V / Policy Expert P&DD ant Selection ility in public services PK-GPP KPK-158130-CS-IND Increasing capacity for reve V / Lead Investment Climate Individual Consult TF / A3361 nue mobilization and the pu Post Limited 40,000.00 16,155.59 Signed 2020-02-10 2020-02-18 2020-02-15 2020-02-19 2020-03-07 2020-03-05 2020-04-11 2020-03-10 2020-10-08 for Ease of doing Business-Fi ant Selection blic financial management nance Department Improving public investment PK-GPP KPK-158145-CS-IND Individual Consult TF / A3361 management and accountab Post Limited 40,000.00 35,901.30 Signed 2020-02-12 2020-02-27 2020-02-17 2020-03-09 2020-03-09 2020-03-11 2020-04-13 2020-03-14 2020-10-10 V / PIM Training Expert ant Selection ility in public services PK-GPP KPK-158898-CS-IND Increasing capacity for reve Individual Consult Under Implement V / Team Lead CGU FinanceD TF / A3361 nue mobilization and the pu Post Limited 40,000.00 0.00 2020-02-13 2020-02-18 2020-02-18 2020-03-10 2020-04-14 2021-04-09 ant Selection ation epartment KP blic financial management PK-GPP KPK-158899-CS-IND Increasing capacity for reve Individual Consult Under Implement V / Performance & Monitoring TF / A3361 nue mobilization and the pu Post Limited 28,000.00 0.00 2020-02-13 2020-02-17 2020-02-18 2020-03-10 2020-04-14 2021-04-09 ant Selection ation Specialist CGU Finance Depa blic financial management rtment KP PK-GPP KPK-158900-CS-IND Increasing capacity for reve Individual Consult Under Implement V / Financial Management Re TF / A3361 nue mobilization and the pu Post Limited 16,000.00 0.00 2020-02-13 2020-02-17 2020-02-18 2020-03-10 2020-04-14 2021-04-09 ant Selection ation search Analyst CGU Finance blic financial management Department KP PK-GPP KPK-160944-CS-IND Improving public investment Individual Consult V / Media & Communication TF / A3361 management and accountab Post Limited 16,000.00 13,331.33 Signed 2020-02-26 2020-02-24 2020-03-02 2020-03-09 2020-03-23 2020-03-18 2020-04-27 2020-03-21 2020-10-24 ant Selection Expert P&DD ility in public services PK-GPP KPK-160942-CS-IND Increasing capacity for reve Individual Consult V / Actuary Expert Finance D TF / A3361 nue mobilization and the pu Post Limited 95,000.00 0.00 Canceled 2020-02-26 2020-03-02 2020-03-23 2020-04-27 2020-10-24 ant Selection epartment KP blic financial management PK-GPP KPK-165238-CS-IND Improving public investment Individual Consult V / E-Government Advisor for TF / A3361 management and accountab Post Limited 20,000.00 0.00 Canceled 2020-03-20 2020-03-26 2020-03-25 2020-04-15 2020-05-20 2020-11-16 ant Selection P&D Department KP ility in public services PK-GPP KPK-172337-CS-IND Improving public investment Individual Consult V / Communication Advisor fo TF / A3361 management and accountab Post Limited 15,000.00 0.00 Canceled 2020-05-12 2020-05-11 2020-05-17 2020-06-07 2020-07-12 2021-01-08 ant Selection r P & D Department KP ility in public services PK-GPP KPK-188265-CS-IND Increasing capacity for reve Individual Consult V / Team Leader Corporate G TF / A3361 nue mobilization and the pu Post Open 40,000.00 0.00 Canceled 2020-08-17 2020-08-26 2020-09-25 2020-10-05 2020-10-29 2021-10-24 ant Selection overnance Unit Finance Depa blic financial management rtment KP PK-GPP KPK-188266-CS-IND Increasing capacity for reve V / Performance & Monitoring Individual Consult Under Implement TF / A3361 nue mobilization and the pu Post Limited 30,000.00 0.00 2020-08-17 2020-08-26 2020-08-22 2020-09-12 2020-10-17 2021-10-12 Specialist Corporate Governa ant Selection ation blic financial management nce Unit Finance Department KP Page 7 PK-GPP KPK-188263-CS-CDS / Engagement of Academia f Improving public investment or Integration of MIS for Effec TF / A3361 management and accountab Post Direct Selection Direct 135,000.00 0.00 Canceled 2020-08-17 2020-08-27 2020-10-31 2021-04-29 tive Public Investment Manag ility in public services ement for P&D Department K P PK-GPP KPK-189169-CS-IND Increasing capacity for reve Individual Consult Under Implement V / Lead Advisor PFM for Fina TF / A3361 nue mobilization and the pu Post Open 45,000.00 0.00 2020-08-20 2020-08-28 2020-10-08 2020-10-29 2020-12-03 2021-11-28 ant Selection ation nce Department blic financial management PK-GPP KPK-197622-CS-IND Improving public investment Individual Consult Under Implement V / Short Term ICT Consultan TF / A3361 management and accountab Post Open 6,700.00 0.00 2020-10-20 2020-10-22 2020-12-08 2020-12-29 2021-02-02 2021-06-02 ant Selection ation t for KP RTI Commission ility in public services PK-GPP KPK-194316-CS-IND Improving public investment Individual Consult V / Short Term Consultant for TF / A3361 management and accountab Post Open 7,000.00 0.00 Canceled 2020-09-21 2020-11-09 2020-11-30 2021-01-04 2021-04-04 ant Selection revamping of Website of P&D ility in public services Department PK-GPP KPK-203137-CS-IND Increasing capacity for reve Individual Consult Under Implement V / Financial Management Ex TF / A3361 nue mobilization and the pu Post Open 25,000.00 0.00 2020-11-16 2020-11-17 2020-12-10 2020-12-15 2021-01-10 2021-06-30 ant Selection ation pert CGU Finance Departmen blic financial management t PK-GPP KPK-203138-CS-IND Increasing capacity for reve Individual Consult Under Implement V / Performance & Monitoring TF / A3361 nue mobilization and the pu Post Open 15,000.00 0.00 2020-11-16 2020-11-17 2020-12-10 2020-12-15 2021-01-10 2021-06-30 ant Selection ation Research Analyst CGU Financ blic financial management e Department PK-GPP KPK-204937-CS-IND Improving public investment Individual Consult Under Implement V / Institutional Development TF / A3361 management and accountab Post Open 10,000.00 0.00 2020-11-20 2020-11-27 2020-12-14 2020-12-19 2021-01-03 2021-03-04 ant Selection ation Expert (Water Act 2020) P&D ility in public services D PK-GPP KPK-204939-CS-IND Improving public investment Individual Consult Under Implement V / Legal Consultant (Water A TF / A3361 management and accountab Post Open 10,000.00 0.00 2020-11-20 2020-11-27 2020-12-14 2020-12-19 2021-01-03 2021-03-04 ant Selection ation ct 2020), P&DD ility in public services PK-GPP KPK-208118-CS-IND Improving public investment Individual Consult Under Implement V / Public Investment Manag TF / A3361 management and accountab Post Open 36,000.00 0.00 2020-12-10 2020-12-08 2021-01-03 2021-01-08 2021-01-23 2021-12-31 ant Selection ation ement (PIM) Technical Adviso ility in public services r P&DD PK-GPP KPK-209228-CS-IND Increasing capacity for reve Individual Consult Under Implement V / Public Financial Managem TF / A3361 nue mobilization and the pu Post Open 12,000.00 0.00 2020-12-16 2020-12-14 2021-01-09 2021-01-14 2021-01-29 2022-01-28 ant Selection ation ent Expert for Finance Depar blic financial management tment KP PK-GPP KPK-209230-CS-IND Increasing capacity for reve Individual Consult Under Implement V / Short-Term Consultant GR TF / A3361 nue mobilization and the pu Post Open 12,000.00 0.00 2020-12-16 2020-12-14 2021-01-09 2021-01-14 2021-01-29 2021-07-31 ant Selection ation M for KPPRA blic financial management PK-GPP KPK-222498-CS-IND Improving public investment Individual Consult Under Implement V / Coordination Expert P&D TF / B3385 management and accountab Post Open 25,000.00 0.00 2021-03-08 2021-03-05 2021-04-01 2021-04-08 2021-04-22 2022-04-22 ant Selection ation Department KP ility in public services PK-GPP KPK-228870-CS-IND Improving public investment Individual Consult Under Implement V / PIM Advisor-II for PIM Unit TF / B3385 management and accountab Post Open 30,000.00 0.00 2021-04-15 2021-04-22 2021-05-09 2021-05-16 2021-05-30 2022-05-30 ant Selection ation P&D Department ility in public services PK-GPP KPK-228872-CS-IND Improving public investment Individual Consult Under Implement V / PIM Advisor-I for PIM Unit TF / B3385 management and accountab Post Open 30,000.00 0.00 2021-04-15 2021-04-22 2021-05-09 2021-05-16 2021-05-30 2022-05-30 ant Selection ation P&D Department ility in public services PK-GPP KPK-233219-CS-CDS Increasing capacity for reve / Digitization of Urban Immov Under Implement TF / B3385 nue mobilization and the pu Post Direct Selection Direct 335,000.00 0.00 2021-05-07 2021-05-31 2021-05-17 2021-06-19 2021-12-16 able Property (UIP) Tax data ation blic financial management of Peshawar District PK-GPP KPK-247643-CS-IND Increasing capacity for reve Individual Consult V / MRS Consultant Finance TF / B3385 nue mobilization and the pu Post Open 30,000.00 0.00 Signed 2021-08-13 2021-08-13 2021-09-06 2021-09-23 2021-09-11 2021-09-23 2021-09-26 2022-06-30 ant Selection Department GoKP blic financial management PK-GPP KPK-253482-CS-IND Increasing capacity for reve V / Hiring of Senior Financial Individual Consult Under Implement TF / B3385 nue mobilization and the pu Post Open 25,000.00 0.00 2021-09-17 2021-10-01 2021-10-11 2021-10-16 2021-10-31 2022-06-30 Analyst for Risk Management ant Selection ation blic financial management Unit Finance Department KP PK-GPP KPK-253483-CS-IND Increasing capacity for reve V / Hiring of Financial Analyst Individual Consult Under Implement TF / B3385 nue mobilization and the pu Post Open 16,000.00 0.00 2021-09-17 2021-10-01 2021-10-11 2021-10-16 2021-10-31 2022-06-30 -I for Risk Management Unit ant Selection ation blic financial management Finance Department KP PK-GPP KPK-253484-CS-IND Increasing capacity for reve V / Hiring of Financial Analyst Individual Consult Under Implement TF / B3385 nue mobilization and the pu Post Open 16,000.00 0.00 2021-09-17 2021-10-01 2021-10-11 2021-10-16 2021-10-31 2022-06-30 -II for Risk Management Unit ant Selection ation blic financial management Finance Department KP PK-GPP KPK-253485-CS-IND Increasing capacity for reve V / Hiring of Senior Financial Individual Consult Under Implement TF / B3385 nue mobilization and the pu Post Open 25,000.00 0.00 2021-09-17 2021-10-01 2021-10-11 2021-10-16 2021-10-31 2022-06-30 Analyst Debt Management U ant Selection ation blic financial management nit Finance Department KP PK-GPP KPK-257062-CS-IND Improving public investment Individual Consult V / M&E Framework Expert P TF / B3385 management and accountab Post Open 43,750.00 0.00 Signed 2021-10-12 2021-10-28 2021-11-30 2022-02-07 2021-12-21 2022-02-15 2022-01-25 2022-05-31 ant Selection &DD ility in public services PK-GPP KPK-259923-CS-IND Improving public investment Individual Consult Under Implement V / Social Protection & Gende TF / B3385 management and accountab Post Open 22,500.00 0.00 2021-11-02 2021-11-15 2021-11-26 2021-12-01 2021-12-16 2022-06-30 ant Selection ation r Expert-I ility in public services PK-GPP KPK-259927-CS-IND Improving public investment Individual Consult Under Implement V / Social Protection & Gende TF / B3385 management and accountab Post Open 22,500.00 0.00 2021-11-02 2021-11-15 2021-11-26 2021-12-01 2021-12-16 2022-06-30 ant Selection ation r Expert-II ility in public services PK-GPP KPK-269601-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Team Leader(Sr TF / B3385 nue mobilization and the pu Post Open 15,300.00 0.00 Canceled 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection um/Canban/XP for KPITB blic financial management PK-GPP KPK-269609-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Research & Syst TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Canceled 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection em Analyst for KPITB blic financial management PK-GPP KPK-269610-CS-IND Increasing capacity for reve Individual Consult V / Hiring of System Administ TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Signed 2021-12-31 2022-03-01 2022-01-24 2022-03-10 2022-01-29 2022-04-12 2022-02-13 2022-06-30 ant Selection rator (Linux and Windows) fo blic financial management r KPITB Page 8 PK-GPP KPK-269611-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Network Enginee TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Signed 2021-12-31 2022-03-01 2022-01-24 2022-03-10 2022-01-29 2022-04-12 2022-02-13 2022-06-30 ant Selection r for KPITB blic financial management PK-GPP KPK-269612-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Graphics Design TF / B3385 nue mobilization and the pu Post Open 7,000.00 0.00 Signed 2021-12-31 2022-03-01 2022-01-24 2022-03-10 2022-01-29 2022-04-25 2022-02-13 2022-06-30 ant Selection er for KPITB blic financial management PK-GPP KPK-269613-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Digital Marketing TF / B3385 nue mobilization and the pu Post Open 7,000.00 0.00 Canceled 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection Specialist for KPITB blic financial management PK-GPP KPK-269614-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Video Animator f TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Canceled 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection or KPITB blic financial management PK-GPP KPK-269615-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Content Writer f TF / B3385 nue mobilization and the pu Post Open 8,750.00 0.00 Signed 2021-12-31 2022-03-01 2022-01-24 2022-03-10 2022-01-29 2022-04-15 2022-02-13 2022-06-30 ant Selection or KPITB blic financial management PK-GPP KPK-269616-CS-IND Increasing capacity for reve Individual Consult Under Implement V / Hiring of Head of Digital G TF / B3385 nue mobilization and the pu Post Open 15,300.00 0.00 2021-12-31 2022-03-01 2022-01-24 2022-04-11 2022-01-29 2022-04-14 2022-02-13 2022-06-30 ant Selection ation overnance Support Unit for K blic financial management PITB PK-GPP KPK-269617-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Cyber Security S TF / B3385 nue mobilization and the pu Post Open 15,300.00 0.00 Canceled 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection pecialist for KPITB blic financial management PK-GPP KPK-269618-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Two Junior Softw TF / B3385 nue mobilization and the pu Post Open 14,000.00 0.00 Signed 2021-12-31 2022-01-01 2022-01-24 2022-03-10 2022-01-29 2022-04-12 2022-02-13 2022-06-30 ant Selection are Quality Assurance Engine blic financial management er for KPITB PK-GPP KPK-269619-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Senior Software TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Signed 2021-12-31 2022-03-01 2022-01-24 2022-03-10 2022-01-29 2022-04-12 2022-02-13 2022-06-30 ant Selection Quality Assurance Engineer f blic financial management or KPITB PK-GPP KPK-269604-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Web Application TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Signed 2021-12-31 2022-03-01 2022-01-24 2022-03-10 2022-01-29 2022-04-13 2022-02-13 2022-06-30 ant Selection Developer-I (Codeigniter Fra blic financial management mework) for KPITB PK-GPP KPK-269603-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Web Application TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Under Review 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection Developer-I (ASP. Net Frame blic financial management work) for KPITB PK-GPP KPK-269605-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Web Application TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Canceled 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-04-30 ant Selection Developer-I (Laravel PHP Fra blic financial management mework) for KPITB PK-GPP KPK-269608-CS-IND Increasing capacity for reve Individual Consult V / Hiring of Cross Platform M TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Signed 2021-12-31 2022-03-01 2022-01-24 2022-04-11 2022-01-29 2022-04-12 2022-02-13 2022-06-30 ant Selection obile App Developer-I (Flutter blic financial management ) for KPITB PK-GPP KPK-270621-CS-IND Increasing capacity for reve Individual Consult V / Hiring Web Application De TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Canceled 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection veloper-II (Codeigniter Frame blic financial management work)-KPITB PK-GPP KPK-270625-CS-IND Increasing capacity for reve Individual Consult V / Hiring Web Application De TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Canceled 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection veloper-II (ASP.NET Framewo blic financial management rk) for KPITB PK-GPP KPK-270643-CS-IND Increasing capacity for reve Individual Consult V / Hiring of web Application TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Under Review 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection Developer-III (ASP.NET Frame blic financial management work) for KPITB PK-GPP KPK-270645-CS-IND Increasing capacity for reve Individual Consult V / Hiring Web Application De TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Canceled 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection veloper-IV (ASP.NET Framew blic financial management ork) for KPITB PK-GPP KPK-270646-CS-IND Increasing capacity for reve Individual Consult V / Hiring Web Application De TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Canceled 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection veloper-V (ASP.NET Framewo blic financial management rk) for KPITB PK-GPP KPK-270647-CS-IND Increasing capacity for reve Individual Consult V / Hiring Web Application De TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Canceled 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection veloper-VI (ASP.NET Framew blic financial management ork) for KPITB PK-GPP KPK-270649-CS-IND Increasing capacity for reve Individual Consult V / Hiring Web Application De TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Canceled 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection veloper-II (Laravel PHP Fram blic financial management ework) for KPITB PK-GPP KPK-270652-CS-IND Increasing capacity for reve Individual Consult V / Hiring Cross Platform Mob TF / B3385 nue mobilization and the pu Post Open 13,125.00 0.00 Under Review 2021-12-31 2022-03-01 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection ile App Developer-II (Flutter) blic financial management for KPITB PK-GPP KPK-270655-CS-IND Increasing capacity for reve Individual Consult Under Implement V / Hiring of NFC Consultant f TF / B3385 nue mobilization and the pu Post Open 15,000.00 0.00 2021-12-31 2022-01-10 2022-01-24 2022-01-29 2022-02-13 2022-06-30 ant Selection ation or Finance Department KP blic financial management PK-GPP KPK-272807-CS-IND Improving public investment Individual Consult Under Implement V / Institutional and Policy Ex TF / B3385 management and accountab Post Limited 20,000.00 0.00 2022-01-25 2022-02-07 2022-01-30 2022-02-06 2022-02-16 2022-05-17 ant Selection ation pert for Mine & Mineral Depa ility in public services rtment KP PK-GPP KPK-277392-CS-IND Improving public investment Individual Consult Under Implement V / Hiring of PPP Specialist for TF / B3385 management and accountab Post Open 10,000.00 0.00 2022-02-10 2022-02-17 2022-03-06 2022-03-11 2022-03-26 2022-06-30 ant Selection ation PPP Unit P&D Department KP ility in public services PK-GPP KPK-277394-CS-IND Improving public investment Individual Consult Under Implement V / Hiring of Finance Specialis TF / B3385 management and accountab Post Open 10,000.00 0.00 2022-02-10 2022-02-17 2022-03-06 2022-03-11 2022-03-26 2022-06-30 ant Selection ation t for PPP Unit P&DD KP ility in public services PK-GPP KPK-277395-CS-IND Improving public investment Individual Consult Under Implement V / Hiring of Legal & Contract TF / B3385 management and accountab Post Open 10,000.00 0.00 2022-02-10 2022-02-17 2022-03-06 2022-03-11 2022-03-26 2022-06-30 ant Selection ation Expert for PPP Unit P&DD KP ility in public services Increasing capacity for reve PK-GPP KPK-257055-CS-IND Individual Consult TF / B3385 nue mobilization and the pu Post Open 15,000.00 0.00 Canceled 2021-10-12 2021-10-28 2021-11-15 2021-11-20 2021-12-05 2022-06-30 V / Sector Expert KPPPRA ant Selection blic financial management Page 9 PK-GPP KPK-156379-CS-IND Providing effective support f Individual Consult V / Public Investment Manag TF / A3361 or the coordination of gover Post Open 80,000.00 0.00 Canceled 2020-01-31 2020-02-06 2020-03-20 2020-04-10 2020-05-15 2021-05-10 ant Selection ement (PIM) Specialist nance reforms and operatio nal management PK-GPP KPK-286767-CS-IND Increasing capacity for reve V / Short-term Individual Con Individual Consult TF / B3385 nue mobilization and the pu Post Open 9,500.00 0.00 Signed 2022-04-03 2022-06-05 2022-04-29 2022-11-15 2022-05-04 2022-11-25 2022-05-19 2022-08-18 sultant for Development of S ant Selection blic financial management BDs/Guidelines for disposal o f assets for KP-PPRA Providing effective support f PK-GPP KPK-299030-CS-IND Individual Consult Under Implement TF / B3385 or the coordination of gover Post Direct 42,000.00 0.00 2022-06-12 2022-06-13 2022-06-19 2022-06-15 2022-06-24 2022-07-01 2023-06-30 V / Coordinator OSU GPP KP ant Selection ation nance reforms and operatio nal management PK-GPP KPK-299033-CS-IND Providing effective support f Individual Consult Under Implement V / Governance Specialist OS TF / B3385 or the coordination of gover Post Direct 41,500.00 0.00 2022-06-12 2022-06-13 2022-06-19 2022-06-15 2022-06-24 2022-07-01 2023-06-30 ant Selection ation U GPP KP nance reforms and operatio nal management PK-GPP KPK-299034-CS-IND Providing effective support f Individual Consult Under Implement V / Procurement Managemen TF / B3385 or the coordination of gover Post Direct 41,000.00 0.00 2022-06-12 2022-06-13 2022-06-19 2022-06-15 2022-06-24 2022-07-01 2023-06-30 ant Selection ation t Specialist OSU GPP KP nance reforms and operatio nal management PK-GPP KPK-299038-CS-IND Providing effective support f Individual Consult Under Implement V / Monitoring & Evaluation S TF / B3385 or the coordination of gover Post Direct 41,000.00 0.00 2022-06-12 2022-06-13 2022-06-19 2022-06-15 2022-06-24 2022-07-01 2023-06-30 ant Selection ation pecialist OSU GPP KP nance reforms and operatio nal management PK-GPP KPK-299053-CS-IND Providing effective support f Individual Consult Under Implement V / Communication Specialist TF / B3385 or the coordination of gover Post Direct 41,000.00 0.00 2022-06-12 2022-06-13 2022-06-19 2023-06-15 2022-06-24 2022-07-01 2023-06-30 ant Selection ation OSU GPP KP nance reforms and operatio nal management PK-GPP KPK-299057-CS-IND Providing effective support f Individual Consult Under Implement V / MIS & ICT Specialist OSU TF / B3385 or the coordination of gover Post Direct 41,000.00 0.00 2022-06-12 2022-06-13 2022-06-19 2023-06-15 2022-06-24 2022-07-01 2023-06-30 ant Selection ation GPP KP nance reforms and operatio nal management PK-GPP KPK-299060-CS-IND V / Legal Consultant-Framing Improving public investment Rules and Regulations for Fu Individual Consult Under Implement TF / B3385 management and accountab Post Limited 16,000.00 0.00 2022-06-12 2023-04-06 2022-06-19 2022-06-26 2022-07-06 2022-10-10 nctioning of the KP Water Re ant Selection ation ility in public services source Commission and KP W ater Resource Regulatory Aut hority PK-GPP KPK-301364-CS-IND Improving public investment V / Hiring of PIM Technical Ad Individual Consult TF / B3385 management and accountab Post Open 25,000.00 0.00 Signed 2022-06-28 2022-06-28 2022-07-22 2022-07-27 2022-07-29 2022-08-01 2022-08-12 2023-06-30 visor for PIM Unit P&D Depart ant Selection ility in public services ment Khyber Pakhtunkhwa PK-GPP KPK-319198-CS-IND Providing effective support f Individual Consult V / Financial Management Sp TF / B3385 or the coordination of gover Post Open - National 25,000.00 0.00 Canceled 2022-10-06 2022-11-09 2022-11-14 2022-12-01 2023-06-30 ant Selection ecialist OSU GPP KP nance reforms and operatio nal management PK-GPP KPK-347373-CS-IND Improving public investment V / Short Term Individual Con Individual Consult Under Implement TF / B3385 management and accountab Post Limited 2,000.00 0.00 2023-03-13 2023-03-17 2023-03-18 2023-04-08 2023-05-13 2023-06-30 sultant for Replication and D ant Selection ation ility in public services eployment of CMS-1334 at W SSC Bannu PK-GPP KPK-353675-CS-IND Providing effective support f Individual Consult V / Short Term Individual Con TF / B3385 or the coordination of gover Post Open - National 9,800.00 0.00 Canceled 2023-03-31 2023-04-27 2023-04-29 2023-05-09 2023-06-30 ant Selection sultant for Project Result Eval nance reforms and operatio uation of GPP nal management PK-GPP KPK-348636-CS-IND Increasing capacity for reve V / Short Term Individual Con Individual Consult TF / B3385 nue mobilization and the pu Post Limited 6,000.00 0.00 Signed 2023-03-31 2023-03-30 2023-04-05 2023-05-03 2023-04-12 2023-05-10 2023-04-22 2023-06-30 sultant for Training Need Ass ant Selection blic financial management essment and Training Plan fo r KPRA PK-GPP KPK-360625-CS-IND V / Short Term Individual Con sultant Integration of Plannin Improving public investment Individual Consult Under Implement g Commission Form Manage TF / B3385 management and accountab Post Limited 2,350.00 0.00 2023-05-10 2023-05-10 2023-05-17 2023-05-15 2023-05-22 2023-05-29 2023-05-28 2023-06-30 ant Selection ation ment System (PCFMS) and C ility in public services hief Minister’s Delivery Unit ( CMDU) Tracking System P&D Department PK-GPP KPK-363675-CS-IND Improving public investment V / Short Term Individual Con Individual Consult TF / B3385 management and accountab Post Limited 2,050.00 0.00 Signed 2023-05-26 2023-05-31 2023-05-31 2023-06-05 2023-06-03 2023-06-13 2023-06-10 2023-06-30 sultant for Report Writing of ant Selection ility in public services RTPS Commission Annual Re port Page 10 Appendix to Annex 3 Procurement Plan I. General 1. Project Information Country : India Borrower : Government of India Project Name : National Hydrology Project Loan Credit No. : 2. Bank’s Approval Date of the Procurement Plan : 3. Date of General Procurement Notice : 4. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services Thresholds for Method of Procurement for procurement of goods, works and non- consulting services Procurement of Goods, Information technology and non consultancy services: Method of Procurement Thresholds for Methods International Competitive Bidding (ICB) > US Dollars 3 million Limited Competitive Bidding (LIB) Must meet the requirements as per Para 3.2 of the Procurement Guidelines, and with prior agreement in PP with the Bank National Competitive Bidding (NCB) > USD 100,000 and up to USD 3 million Shopping Up to USD 100,000 (INR 6.5 m) Direct Must meet the requirements as per Para 3.7 of the Procurement Guidelines, and with prior agreement in PP with the Bank Framework Agreement Must meet the requirements as per Para 3.6 of the Procurement Guidelines, and with prior agreement in PP with the Bank Procurement of Works: Method of Procurement Thresholds for Methods International Competitive Bidding (ICB) > US Dollars 40 million National Competitive Bidding (NCB) > USD 100,000 and up to USD 40 million Comparison of three quotations / Up to USD 100,000 (INR 6.5 m) Shopping Force Account Must meet the requirements as per Para 3.9 of the Procurement Guidelines, and with prior agreement in PP with the Bank Prior Review Thresholds: The following would be subject to Prior review of the Bank regardless of the Method of selection: (a) Works: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 10 million (b) Goods: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 2 million; and The Prior Review Thresholds will be reviewed and updated during the implementation of the project, and modified based on the risk assessment. 1. In the case of contracts subject to prior review, Project Implementing Entity shall seek the Bank’s no objection before granting/agreeing to (a) an extension of the stipulated time for performance of a contract that either increases the contract price or has an impact on the planned completion of the project; (b) any substantial modification of the scope of works, goods, non-consulting services or consulting services, other significant changes to the terms and conditions of such that the contract,; (c) any variation order or amendment (except in cases of extreme urgency) which singly or combined with all variation orders or amendments previously issued, increase the original contract amount by more than 15 percent; or (d) the proposed termination of the contract.. A copy of all amendments to the contract shall be furnished to the Bank for its record. 2. Prequalification Not Applicable Domestic Preference: The provision of domestic preference is applicable in the evaluation of Goods only. 3. Reference to Procurement Manual The procurement manual for the project is presently under preparation. SBDs agreed between the Project and Bank will be used for all works, goods, and non consultancy procurements. 4. Any Other Special Procurement Arrangements The National bidding method for procurement and goods and works according to the above value thresholds will be conducted in accordance with paragraphs 3.3 and 3.4 of the Bank’s Procurement Guidelines and the following provisions: (a) Only the model bidding documents for NCB agreed with the GOI task force (and as amended for time to time) shall be used for bidding. (b)Invitations to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily, among others, giving the website/electronic portal details from which the details of the invitation to bid can be downloaded) at least 30 days before the deadline for the submission of bids. (c) No special preferences will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state- owned enterprises, small-scale enterprises, or enterprises from any given state. (d)Extension of bid validity shall not be allowed with reference to contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by the Bank only in cases of force majeure and circumstances beyond the control of the purchaser/employer). (e) Rebidding shall not be carried out with reference to contracts subject to Bank prior review without the prior concurrence of the Bank. The system of rejecting bids outside a predetermined margin or ‘bracket’ of prices shall not be used in the project. (f) Rate contracts entered into by the DGS&D will not be acceptable as a substitute for NCB procedures unless incorporation of right to audit and fraud corruption clauses. DGS&D contracts will be acceptable, however, for any procurement under the shopping procedures. (g)Two or three envelope system will not be used (except when using the e- procurement system assessed and agreed by the Bank). (h)No negotiations are conducted even with the lowest evaluated responsive bidders. 5. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Procurement methods of procurement of Consultants' Services (Firms) Method of Procurement Thresholds for Methods Quality and Cost Based Selection (QCBS) Quality Based Selection (QBS) Must meet the requirements as per Para 3..2 to 3.4 of the Consultant Guidelines Selection based on a Fixed Budget Must meet the requirements as per (FBS) Para 3.5 of the Consultant Guidelines, Selection Based on Least Cost Basis Must meet the requirements as per (LCS) Para 3.6 of the Consultant Guidelines, Selection based on Consultant’s Estimated not to exceed USD Qualification (CQ) 300,000, and must meet the requirements as per Para 3.7 of the Consultant Guidelines. Single Source Selection (SSS) Must meet the requirements as per Para 3.8 to 3.11 of the Consultant Guidelines, and with prior agreement in PP with the Bank. Procurement methods for Selection of Individual Consultants (IC) Method of Procurement Thresholds for Methods Competitive Selection Must meet the requirements of Section V, Para 5.1 to 5.5 of the Consultant Guidelines. Single Source Selection (SSS) Must meet the requirements of Section V, Para 5.6 of the Consultant Guidelines and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Consultant Guidelines Prior Review Thresholds: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.3 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. Note: The Prior Review Thresholds will be reviewed during the implementation of the project and modified. 1. In the case of contracts subject to prior review, before agreeing to: (a) an extension of the stipulated time for performance of a contract; (b) any substantial modification of the scope of services, substitutions of key experts, or other significant changes to the terms and conditions of the contract; or (c) the proposed termination of the contract, the Borrower shall seek the Bank’s no objection. A copy of all amendments to the contract shall be furnished to the Bank for its record. 2. Short List comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than USD 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. The Request for Expression of Interest for consultancy services estimated to cost above USD 300,000 equivalent per contract for firms shall be advertised in UNDB online and World Bank external Website and in accordance with other provisions of Para 2.5 of the Consultant Guidelines 4. Any other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable] I. Implementing Agency Capacity Building Activities with Time Schedule No Expected Outcome/Activity Description Estimated Date Duration ASCI training on Procurement Procedures arranged for Executive, Assistant Engineers 1. 2 weeks Continuous who are responsible for Procurement – multiple trainings Contract management training – multiple 2. 2 weeks Continuous trainings Customized training on Procurement Procedures arranged for Executive, Assistant 3. 1 week Continuous Engineers who are responsible for Procurement – multiple trainings PROCUREMENT India : National Hydrology Project PLAN General Information Country: India 2017-11-24 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P152698 GPN Date: 2022-06-17 Project Name: National Hydrology Project Loan / Credit No: IBRD / 87250 Chhattisgarh Surface Water Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-CHHATTISGARH SW-2922 2-CW-RFQ / Renovation of Su Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 2018-07-0 IBRD / 87250 Post Limited 32,307.69 0.00 2017-11-11 2018-07-11 2018-01-06 b divisional Data Center & off System tions nvelope mentation 5 ice building 2 nos. NHP-2018-2019-CGSW-4175 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 2019-05-0 85-CW-SH-QU / Renovation o IBRD / 87250 Post Limited 30,769.23 0.00 2018-09-15 2018-12-29 2018-11-10 System tions nvelope mentation 9 f state Data Centre NHP-2019-2020-CG-851714 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 2020-12-2 / Renovation of State data Ce IBRD / 87250 Post Limited 92,307.69 0.00 2020-05-03 2020-11-11 2020-06-28 System tions nvelope mentation 5 nter, Raipur NHP-2020-2021-CG-441635 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 2021-03-1 / Renovation of existing Data IBRD / 87250 Post Limited 33,846.15 0.00 2020-07-20 2021-09-29 2020-09-14 System tions nvelope mentation 3 Centre- SDDPC Raipur Request for Quota NHP-2021-2022-CG-241399 Water Resources Monitoring Request for Quota Single Stage - One E tions - Small Work Under Imple 2022-02-2 / Server Room for Real Time IBRD / 87250 Post Limited 10,769.23 0.00 2021-06-30 2021-09-08 2021-08-25 System tions nvelope s (Emergency) SP mentation 1 Data Acquisition System (RT D -Competitive DAS) NHP-2021-2022-CG-596220 Request for Quota Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 2022-11-2 / Renovation of existing Sub IBRD / 87250 Post Limited tions (Non Bank-S 2,739.73 0.00 2022-04-04 2022-06-02 2022-05-30 System tions nvelope mentation 6 Divisional Data Center Raipur PD) NHP-2022-2023-CG-330191 Request for Quota / Survey on RTDAS AWLR sta Water Resources Monitoring Request for Quota Single Stage - One E Pending Imp 2023-11-2 IBRD / 87250 Post Limited tions (Non Bank-S 9,589.04 0.00 2023-04-02 2023-05-28 tions including cross section, System tions nvelope lementation 4 PD) gauge marking with GTS leve l at Jagdalpur Zone NHP-2022-2023-CG-731006 Request for Quota / Survey on RTDAS AWLR sta Water Resources Monitoring Request for Quota Single Stage - One E Pending Imp 2023-11-2 IBRD / 87250 Post Limited tions (Non Bank-S 13,698.63 0.00 2023-04-02 2023-05-28 tions including cross section, System tions nvelope lementation 4 PD) gauge marking with GTS leve l at Ambikapur Zone NHP-2022-2023-CG-815108 Request for Quota / Survey on RTDAS AWLR sta Water Resources Monitoring Request for Quota Single Stage - One E Pending Imp 2023-11-2 IBRD / 87250 Post Limited tions (Non Bank-S 6,164.38 0.00 2023-04-02 2023-05-28 tions including cross section, System tions nvelope lementation 4 PD) gauge marking with GTS leve l at Bilaspur Zone NHP-2022-2023-CG-934916 Request for Quota / Survey on RTDAS AWLR sta Water Resources Monitoring Request for Quota Single Stage - One E Pending Imp 2023-11-2 IBRD / 87250 Post Limited tions (Non Bank-S 9,589.04 0.00 2023-04-02 2023-05-28 tions including cross section, System tions nvelope lementation 4 PD) gauge marking with GTS leve l at Raipur Zone GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-CHHATTISGARH SW-2914 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 6-GO-RFQ / Procurement of S IBRD / 87250 Post Limited 4,615.38 0.00 2017-11-04 2017-12-30 2017-12-30 2018-06-28 System tions nvelope mentation tandard Raingauge. IN-CHHATTISGARH SW-2914 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 9-GO-DIR / Procurement of Ai IBRD / 87250 Post Limited 11,538.46 0.00 2017-11-04 2017-12-30 2018-06-28 System tions nvelope mentation rconditioners. IN-CHHATTISGARH SW-2915 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 2-GO-DIR / Procurement of O IBRD / 87250 Post Limited 10,769.23 0.00 2017-11-04 2017-12-30 2018-06-28 System tions nvelope mentation nline UPS 15 KVA. IN-CHHATTISGARH SW-2920 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 6-GO-RFQ / Procurement 0f fl IBRD / 87250 Post Limited 3,846.15 0.00 2017-11-04 2018-02-02 2017-12-30 2018-06-28 System tions nvelope mentation oor scrubber machine. IN-CHHATTISGARH SW-2921 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 1,538.46 0.00 2017-11-04 2017-12-30 2018-06-28 6-GO-DIR / Procurement of L System tions nvelope mentation CD Projetor. IN-CHHATTISGARH SW-2921 Institutional Capacity Enhan Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 12,307.69 0.00 2017-10-11 2017-09-01 2017-12-06 2018-06-04 9-GO-DIR / Procurement of 1 cement tions nvelope mentation no Vehicle. IN-CHHATTISGARH SW-2846 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 9-GO-DIR / Procurement of 8 IBRD / 87250 Post Limited 9,864.15 0.00 2017-12-25 2018-02-19 2018-08-18 System tions nvelope mentation nos Desktop computer. IN-CHHATTISGARH SW-2885 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 2,769.23 0.00 2017-12-26 2018-02-20 2018-08-19 0-GO-DIR / Procurement of 3 System tions nvelope mentation nos Laptop. IN-CHHATTISGARH SW-2885 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 1-GO-DIR / Procurement of 1 IBRD / 87250 Post Limited 1,846.15 0.00 2017-12-26 2018-02-20 2018-08-19 System tions nvelope mentation 0 nos A4 printer. IN-CHHATTISGARH SW-2885 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 553.84 0.00 2017-12-26 2018-02-20 2018-08-19 5-GO-DIR / Procurement of sc System tions nvelope mentation anner. IN-CHHATTISGARH SW-2922 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 1-GO-DIR / Procurement of Ar IBRD / 87250 Post Limited 38,461.54 0.00 2018-02-03 2018-03-31 2018-09-27 System tions nvelope mentation C GIS software 1no. Page 1 IN-CHHATTISGARH SW-2885 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 3-GO-DIR / procurement of Di IBRD / 87250 Post Limited 3,076.92 0.00 2017-12-26 2018-02-20 2018-08-19 System tions nvelope mentation gital copier multifunctional 1 no. NHP-2018-2019-CGSW-3140 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 02-GO-SH-QU / Airconditioner IBRD / 87250 Post Limited 11,538.46 0.00 2019-01-31 2019-01-15 2019-03-28 2019-09-24 System tions nvelope mentation for data centre NHP-2018-2019-CGSW-5798 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 29-GO-SH-QU / Desktop Com IBRD / 87250 Post Limited 7,384.62 0.00 2018-07-28 2019-02-04 2018-09-22 2019-03-21 System tions nvelope mentation puter (IT equipment for data centre) NHP-2018-2019-CGSW-9329 36-GO-SH-QU / Digital Copier Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 3,076.92 0.00 2018-09-08 2018-11-03 2019-05-02 Multifunctional (IT equpiment System tions nvelope mentation for data centre) NHP-2018-2019-CGSW-4354 Institutional Capacity Enhan Request for Quota Single Stage - One E Under Imple 02-GO-SH-QU / Plotter (IT eq IBRD / 87250 Post Limited 15,384.62 0.00 2018-09-08 2018-11-03 2019-05-02 cement tions nvelope mentation uipment for data centre) NHP-2019-2020-CGSW-9386 Water Resources Monitoring Single Stage - Two E 10 / RTDAS - ARG,AWLR,AWS IBRD / 87250 Prior Request for Bids Open - National 2,747,861.54 0.00 Canceled 2019-08-30 2019-11-13 2019-09-04 2020-01-22 2019-10-16 2019-12-29 2020-02-02 2020-07-31 System nvelope and Gate sensor & Civil work s for RTDAS NHP-2019-2020-CG-380360_ _1 / SUPPLY, INSTALLATION, TESTING, COMMISSIONING A Water Resources Monitoring Single Stage - Two E ND MAINTENANCE OF REAL T IBRD / 87250 Prior Request for Bids Open - National 2,489,916.92 1,867,742.44 Signed 2020-03-05 2020-03-05 2020-03-10 2020-03-07 2020-04-21 2020-05-11 2020-07-04 2020-09-20 2020-08-08 2020-12-13 2021-02-04 System nvelope IME DATA ACQUISITION SYST EM (RTDAS) of CHHATTISGAR H UNDER NATIONAL HYDROL OGY PROJECT NHP-2020-2021-CG-123694 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple / Hand held Radar Gun for m IBRD / 87250 Post Limited 23,076.92 0.00 2020-07-30 2021-01-29 2020-09-24 2021-03-23 System tions nvelope mentation easurement of surface veloci ty - 4 nos. NHP-2020-2021-CG-100144 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 21,538.46 0.00 2020-07-30 2021-01-28 2020-09-24 2021-03-23 / LED Screen 86" - 2 nos. System tions nvelope mentation NHP-2020-2021-CG-544145 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 10,769.23 0.00 2020-07-30 2021-01-28 2020-09-24 2021-03-23 / Digital Podium System tions nvelope mentation NHP-2020-2021-CG-331776 / Electronic display system, 5 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 33,846.15 0.00 2020-09-19 2021-03-27 2020-11-14 2021-05-13 5" Full HD ( 4 Nos ), led PANE System tions nvelope mentation L based video wall - 1 no. NHP-2020-2021-CG-127419 Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Limited 1,153.85 1,070.37 Completed 2020-07-18 2021-02-17 2020-09-12 2021-03-20 2021-03-11 2021-04-09 / Television System tions nvelope NHP-2020-2021-CG-894508 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple / Desktop Work Station Comp IBRD / 87250 Post Limited 17,692.31 0.00 2020-07-20 2021-05-13 2020-09-14 2021-03-13 System tions nvelope mentation uter - 4 nos. NHP-2020-2021-CG-338378 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 14,092.31 0.00 2020-07-20 2021-02-16 2020-09-14 2021-03-13 / Desktop Computer - 14 nos. System tions nvelope mentation NHP-2020-2021-CG-494824 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 2,153.85 0.00 2020-07-27 2021-01-13 2020-09-21 2021-03-20 / Colour printer A3 System tions nvelope mentation NHP-2020-2021-CG-183404 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 4,615.38 0.00 2020-07-27 2021-02-17 2020-09-21 2021-03-20 / MS office - 15 nos. System tions nvelope mentation NHP-2020-2021-CG-688940 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 24,615.38 0.00 2020-08-20 2021-06-11 2020-10-15 2021-04-13 / Office Furniture System tions nvelope mentation NHP-2021-2022-CG-181165 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 10,769.23 0.00 2021-07-31 2022-03-31 2021-09-25 2022-03-24 / All in one Desktop Compute System tions nvelope mentation r- 4 Nos. NHP-2021-2022-CG-584479 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 3,076.92 0.00 2021-06-30 2023-02-13 2021-08-25 2022-02-21 / Airconditioner - 4 Nos. System tions nvelope mentation NHP-2021-2022-CG-927864 / Water Quality Equipment, Fi Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Limited 6,153.85 0.00 2021-07-31 2022-03-20 2021-09-25 2022-03-24 eld Pocket Tester for Field Pa System tions nvelope mentation rameters (Surface Water) - 8 Nos. NHP-2021-2022-CG-749502 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple / Online UPS 5kVA (2nos.) for IBRD / 87250 Post Limited 6,849.32 0.00 2022-03-03 2022-03-29 2022-04-28 2022-10-25 System tions nvelope mentation data processing cell of RTDA S NHP-2021-2022-CG-375787 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple / Diesel Power Generator Set IBRD / 87250 Post Limited 19,178.08 0.00 2022-03-03 2022-03-04 2022-04-28 2022-10-25 System tions nvelope mentation 100kVA for State Data Centr e -RTDAS Server NHP-2021-2022-CG-300123 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple / Video Conference arrangem IBRD / 87250 Post Limited 3,424.66 0.00 2022-03-03 2022-02-25 2022-04-28 2022-10-25 System tions nvelope mentation ent at State Data Centre NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NHP-2020-2021-CG-196413 Water Resources Operations Single Stage - Two E Under Imple IBRD / 87250 Post Request for Bids Open - National 461,538.46 0.00 2020-07-30 2021-02-09 2020-08-04 2020-09-15 2021-03-18 2020-11-28 2021-01-02 2021-07-01 / Reservoir sediment survey - and Planning System nvelope mentation 24 nos. NHP-2020-2021-CG-409223 Institutional Capacity Enhan Single Stage - Two E Pending Impl IBRD / 87250 Post Request for Bids Open - National 600,000.00 0.00 2020-07-30 2020-08-04 2020-09-15 2020-11-28 2021-01-02 2021-07-01 / Hiring of Technical and Offic cement nvelope ementation e staff CONSULTING FIRMS Page 2 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 6-Months Procurement Plan for OGSTEP PPA General: Project Information:. OGUN STATE ECONOMIC TRANSFORMATION PROJECT (OGSTEP) Project Implementation Agency: UNDER THE SUPERVISION OF MINISTRY OF BUDGET AND PLANNING Date of the Procurement Plan: June 16, 2020 Period covered by this Procurement Plan: April to September 2020 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers”, July 2016 (Revised November 2017) (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. III. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Nigeria Public Procurement Act 2007 and the Regulations, 2016, such arrangements shall be subject to paragraph 5.3 and 5.4 of the Procurement Regulations and the following conditions: o There should be no mandatory requirements for inclusion of local experts and firms for the consulting assignments; o There should be no exclusive preference based on threshold prescribed in PPA and credit and its Regulations; o Negotiations with the lowest evaluated bidder to reduce price in the case of goods, works and non-consulting services where competitive methods have been used shall not be allowed; 1 o The fixed budget method shall not be used for goods, works and non- consulting services; o Established and approved procurement standards by the government may be used, provided that they are not restrictive When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. IV. Prequalification: Applicable (May be applicable at the Federal for high value Consultant Assignments V. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable VI. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable VII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Domestic preference is not applicable for National Open Competitive Procurement VIII. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is: Not Applicable IX. Other Relevant Procurement Information: Not Applicable 2 3 X. Threshold for Prior Review, Procurement Approaches and Methods – Goods, Works and Non- Consulting Services Procurement Approaches and Methods (US$ millions) Category Open Open National Request for Quotation International (RfQ) Works, Turnkey, and ≥5 <5 ≤ 0.2 S&I of Plant and Equipment Goods, IT, and non- ≥5 <0.5 ≤ 0.1 consulting services Post Review: All contracts not subject to prior review shall be subject to post review. XI. Summary of the procurement packages for Goods, Works and Non-Consulting Services: S Contract Implem Estimate Revie Market Selecti Evaluati Procurem Prequ Domest Expect Expect r. Description enting d Cost w by Approa on on ent alifica ic ed ed N Agency (US$) Bank ch Metho Options Process tion Prefere date date of o (Prior (Open- d (Most (Single (Yes/ nce of bid/ Contra / Nationa (RFP, Advanta stage- No) (Yes/No propos ct Post) l/ RFB, geous single ) al Signat Limited RFQ, Bid, envelope openin ure etc.) DS BAFO, etc.) g etc.) Rated Criteria etc.) GOODS 1 Procurement of OGSTEP 61,508.33 Post Limited RFQ Most Single No No 20-06- 20-06-25 laptops, Advanta stage- 04 modems, ext geous single HDD, USB Bid envelope drives, modems, desktops, software, UPS and stabilizers, Color LaserJet printers, 4 S Contract Implem Estimate Revie Market Selecti Evaluati Procurem Prequ Domest Expect Expect r. Description enting d Cost w by Approa on on ent alifica ic ed ed N Agency (US$) Bank ch Metho Options Process tion Prefere date date of o (Prior (Open- d (Most (Single (Yes/ nce of bid/ Contra / Nationa (RFP, Advanta stage- No) (Yes/No propos ct Post) l/ RFB, geous single ) al Signat Limited RFQ, Bid, envelope openin ure etc.) DS BAFO, etc.) g etc.) Rated Criteria etc.) LaserJet printers, muti- media projectors with screen, Photocopiers, Electronic Interactive Boards, Android tablets 2 Procurement of OGSTEP 8,083.33 Post Limited RFQ Most Single No No 20-07- 20-08-03 4 No. 1.5HP Advanta stage- 13 split unit air geous single conditioners, 6 Bid envelope No. 2Tons standing air conditioners, 5 No. fridge, 4 No. Standing fan 3 Televisions, OGSTEP 26,888.89 Post Limited RFQ Most Single No No 20-07- 20-08-10 Satellite Advanta stage- 20 Television geous single decoder (DSTV Bid envelope or its equivalent) plus installation and 6 months subscription, PABX - Inter- comm for the one floor, CCTV - Securtity 5 S Contract Implem Estimate Revie Market Selecti Evaluati Procurem Prequ Domest Expect Expect r. Description enting d Cost w by Approa on on ent alifica ic ed ed N Agency (US$) Bank ch Metho Options Process tion Prefere date date of o (Prior (Open- d (Most (Single (Yes/ nce of bid/ Contra / Nationa (RFP, Advanta stage- No) (Yes/No propos ct Post) l/ RFB, geous single ) al Signat Limited RFQ, Bid, envelope openin ure etc.) DS BAFO, etc.) g etc.) Rated Criteria etc.) Camera + installation, Internet Services, virtual meeting platform 4 Procurement of OGSTEP 27,777.78 Post Limited RFQ Most Single No No 20-06- 20-06-23 1no 100KVA Advanta stage- 02 Diesel geous single Generator Bid envelope (super silent) for PIU 5 Procurement of OGSTEP 277777.7 Post Limited RFQ Most Single No No 20-06- 20-06-23 4no Project 8 Advanta stage- 02 Vehicles 8no geous single 4x4 wheel Bid envelope drive (1PIU, 1 AGRIC, 2 BEE&IPA) 6 Procurement of OGSTEP 40,541.67 Post Limited RFQ Most Single No No 20-08- 20-08-24 office furniture Advanta stage- 03 for PIU and geous single other sectors Bid envelope 7 *Procurement OGSTEP 10,000 Post Limited DIR BAFO Single No No 20-07- 20-08-10 of IPA E- stage- 27 Learning tool single (single source) envelope 8 *Procurement OGSTEP 6,000 Post Limited DIR BAFO Single No No 20-08- 20-08-26 of CRM (single stage- 05 source) and single training envelope 9 Procure OGSTEP 21,311.47 Post Limited RFQ Most Single No No 20-07- 20-08-03 storage Advanta stage- 13 6 S Contract Implem Estimate Revie Market Selecti Evaluati Procurem Prequ Domest Expect Expect r. Description enting d Cost w by Approa on on ent alifica ic ed ed N Agency (US$) Bank ch Metho Options Process tion Prefere date date of o (Prior (Open- d (Most (Single (Yes/ nce of bid/ Contra / Nationa (RFP, Advanta stage- No) (Yes/No propos ct Post) l/ RFB, geous single ) al Signat Limited RFQ, Bid, envelope openin ure etc.) DS BAFO, etc.) g etc.) Rated Criteria etc.) solutions for geous single Deeds & Lands Bid envelope Registry and Archives Records 1 Upgrade of IT OGSTEP 20,582.24 Post Limited RFQ Most Single No No 20-07- 20-08-10 0 infrastructure Advanta stage- 20 in Budget and geous single Planning Bid envelope 1 Printing of IPA OGSTEP 1,315.79 Post Limited RFQ Most Single No No 20-08- 20-09-09 1 Law Advanta stage- 19 geous single Bid envelope 1 Production of OGSTEP 49,180.33 Post Limited RFQ Most Single No No 20-08- 20-09-11 2 revised Rules & Advanta stage- 28 Regulations for geous single BLS Bid envelope Total Goods 550,967 .61 *These two were merged into a package before, but because it has now become very clear that they cannot be executed at the same time, I had to separate them. WORKS Total works NON-CONSULTING SERVICES 7 S Contract Implem Estimate Revie Market Selecti Evaluati Procurem Prequ Domest Expect Expect r. Description enting d Cost w by Approa on on ent alifica ic ed ed N Agency (US$) Bank ch Metho Options Process tion Prefere date date of o (Prior (Open- d (Most (Single (Yes/ nce of bid/ Contra / Nationa (RFP, Advanta stage- No) (Yes/No propos ct Post) l/ RFB, geous single ) al Signat Limited RFQ, Bid, envelope openin ure etc.) DS BAFO, etc.) g etc.) Rated Criteria etc.) Note: Based on Liberia’s specific needs and circumstances, shopping threshold for the purchase of vehicles and fuel may be increased up to US$500,000. Thresholds for Prior Review, Selection Approaches and Methods – Consulting Services Category Prior Review Short List of National Consultants (US$ millions) Consulting Engineering and Construction Supervision Services Consultants (Firms) ≥ 0.5 ≤ 0.1 ≤ 0.2 Individual Consultants ≥ 0.2 n.a. n.a. Note: Consultancy services estimated to cost equivalent to US$ 300,000 and above per contract shall be advertised in the United Nations Development Business (UNDB) online in addition to advertising in national newspaper(s) of wide circulation and/or regional newspaper. XI. Summary of the procurement packages for Consulting Services -Planned for the first 18 months after project effectiveness): Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) 8 Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) 1 MTEF Preparation OGSTEP 40,131.58 Post Open National LCBS YES 20-08-11 20-09-15 including data gathering and validation, current state assessment, sectorial stakeholder consultation, framework design and a validation workshop 2 Design, hosting OGSTEP 26,315.79 Post Limited INDV No 20-08-10 20-09-15 and maintenance of OGSTEP website and mobile application 3 Conduct of OGSTEP 104,955.2 Post Open National CQS Yes 20-05-27 20-06-24 baseline study, 6 needs assessment and foundation skills for STEM teachers 4 Consultancy on OGSTEP 27,631.58 Post Open National LCBS Yes 20-10-28 21-01-04 assessment for the rehabilitation of Technical Colleges 5 Feasibility studies OGSTEP 91,313.42 Post Open National LCBS Yes 20-05-27 20-06-24 and baseline survey for non- formal and traditional apprenticeship Development program 6 Assessment of OGSTEP 83,947.37 Post Open National LCBS Yes 20-10-02 21-01-09 EMIS at State, LGA and school level and improved 9 Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) design outline 7 Recruitment of OGSTEP 42,174.30 Post Open National CQS Yes 20-09-30 20-11-20 Business Environment Expert Consultant to conduct process maps and roadmaps 8 Recruitment of OGSTEP 53,846.43 Post Open National CQS Yes 20-09-16 20-11-06 Consultant to create regulatory framework for OGBEC/BES 9 Engagement of OGSTEP 121,393.4 Post Open National LCBS Yes 20-03-19 20-05-08 Consultant to 5 Conduct Benchmarking Exercise 10 Engagement of OGSTEP 23,809.54 Post Open National LCBS Yes 20-10-14 21-01-22 Consultant for the Capacity building of staff (Ministry of Industry, Trade & Investment and OgunInvest) 11 Recruitment of OGSTEP 8,084.13 Post Open National INDV Yes 20-08-18 20-09-29 Ogun Invest Board trainer, Delivery of training to Ogun Invest Board 12 Technical Training OGSTEP 7,000 Post Open National INDV Yes 20-07-13 20-08-31 for OgunInvest - Business and Investment Research & Reporting and Industry value chain analysis 10 Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) 13 Recruit and OGSTEP 24,584.13 Post Open National INDV Yes 20-09-01 20-10-13 appoint Baseline Survey Consultant 14 Recruitment of OGSTEP 34,961.19 Post Open National INDV Yes 20-08-28 20-10-09 Legal Policy Consultant 15 Recruitment of OGSTEP 18,568 Post Open National INDV Yes 20-07-18 20-08-29 Physical Planning Law review consultant 16 Diagnostic Lands OGSTEP 84,142 Post Open National LCBS Yes 20-09-30 21-01-08 Compensation & Analysis, Review, of Current Land Administration/Pro cess Flow, Current Cost, Recommendation and Implementation of Improved Land Administration 17 Review of Current OGSTEP 36,494 Post Open National INDV Yes 20-07-25 20-09-07 Survey Administration/Pro cess Flow, Current Cost, Recommendation and Implementation of Improved Land Administration 18 Assessment of OGSTEP 52,174 Post Open National LCBS Yes 20-09-28 21-01-05 existing gaps and areas of potential improvement in the investment legal & regulatory 11 Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) framework 19 Sector Scan OGSTEP 9,000 Post Open National INDV Yes 20-10-07 20-11-13 Validation 20 Analysis of growth OGSTEP 49,000 Post Open National INDV Yes 20-10-05 20-11-11 potential and investment landscape in key economic sectors 21 Recruitment of OGSTEP 52,174.30 Post Open National INDV Yes 20-07-20 20-08-31 Communication Strategy Consultant for IPA 22 Transaction OGSTEP 190,300.0 Prior Open National CQS Yes 20-11-03 20-12-28 Advisor to prepare 0 competitive selection of private industrial development and management 23 Farm & farmers OGSTEP 94,736.84 Post Open National CQS Yes 20-07-21 20-09-10 registration, including Geo- tagging using digital tools & database development 24 Engagement of OGSTEP 47,368.42 Post Open National CQS Yes 20-07-23 20-09-15 Consultant for In- depth analysis of priority value chains 25 Engagement of OGSTEP 47,368.42 Post Open National CQS Yes 20-07-24 20-09-16 Consultant for Verification for Agric. Clusters, Roads Etc 26 Engagement of OGSTEP 94,736.84 Post Open National LCBS Yes 20-09-28 21-01-05 Consultant for 12 Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) Baseline Studies - Agric 27 Engagement of OGSTEP 9,210.53 Post Open National LCBS Yes 20-10-23 21-01-05 External Auditor 28 Engagement of OGSTEP 47,368.42 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (PIU) - Environmental Safeguard Specialist 29 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (PIU) - Social Safeguard Specialist 30 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (PIU) - Gender Specialist 31 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (PIU) - Procurement Specialist 32 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (PIU) - M&E Specialist 33 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (Agric – Sector Technical Team) - Agribusiness Specialist - Senior level 34 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / 13 Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) Consultants (Agric – Sector Technical Team) - Environmental Specialist 35 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (Agric – Sector Technical Team) - Social Specialist 36 Engagement of OGSTEP 47,368.42 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (Agric – Sector Technical Team) - FRILIA Specialist (FIRM) 37 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (Skills Development – Sector Technical Team) - Skills Development Specialist 38 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (Skills Development – Sector Technical Team) - TVET Specialist 39 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (Business Environment – Sector Technical 14 Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) Team) - Industrial Estate Specialist 40 Engagement of OGSTEP 47,368.42 Post Open National CQS Yes 20-05-04 20-06-09 key project staff / Consultants (Business Environment – Sector Technical Team) - Business Environment Specialist (FIRM) 41 Engagement of OGSTEP 47,368.42 Post Open National CQS Yes 20-05-04 20-06-09 key project staff / Consultants (Business Environment – Sector Technical Team) - Consultant for the assessment of the Survey Department (FIRM) 42 Engagement of OGSTEP 61,666.67 Post Open National CQS Yes 20-09-16 20-11-06 Value Chain Development Firms (VCDF) - AGRIC 43 Engagement of OGSTEP 5,263.00 Post Open National INDV Yes 20-09-07 20-10-19 Media consultant for the production of Jingles on Radio and TV, Interviews - AGRIC 44 Engagement of OGSTEP 29,000.00 Post Open National INDV Yes 20-08-31 20-10-20 Consultant for Investor expansion survey 45 Deep dives OGSTEP 20,000.00 Post Open National INDV Yes 20-08-22 20-10-03 15 Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) Total 2,096,61 4.37 16 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank- financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub- 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 17 contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 18 Title of the person signing the Letter: 19 PROCUREMENT Nigeria : Ogun State Economic Transformation Project PLAN General Information Country: Nigeria 2020-06-23 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164031 GPN Date: Project Name: Ogun State Economic Transformation Project Loan / Credit No: IDA / V1860, IDA / 65240 OGSTEP Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Results based financing to i OG/CW/PSR/01/2021 / Office mprove the business-enablin Request for Quota Request for Quota Single Stage - One E Under Imple 2022-07-2 Rehabilitation of the Bureau IDA / 65240 g environment and foster pri Post Limited tions (Non Bank-S 90,000.00 0.00 2021-11-27 2022-01-22 tions nvelope mentation 1 of Public Procurement vate sector participation in t PD) he agri-f ood and skills secto rs GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual OG/GO/PPA/02/2020 / Procur Strengthening the capacity ement of Office equipment - of the government to imple Request for Quota Single Stage - One E 4 No. 1.5HP split unit air con IDA / V1860 Post Limited 8,083.33 0.00 Canceled 2020-06-27 2020-08-22 2021-02-18 ment the State’s economic t tions nvelope ditioners, 6 No. 2Tons standi ransformation agenda ng air conditioners, 5 No. frid ge, 4 No. Standing fan OG/GO/PPA/03/2020 / Procur ement of 7 No. Televisions, 2 No. Satelite Television decod Strengthening the capacity er (DSTV or its equivalent) pl of the government to imple Request for Quota Single Stage - One E IDA / V1860 Post Limited 26,888.89 0.00 Canceled 2020-07-04 2020-08-29 2021-02-25 us installation and 6 months ment the State’s economic t tions nvelope subscription, PABX - Inter-co ransformation agenda mm for one floor, CCTV - Sec urtity Camera + installation, I nternet Services, virtual mee ting platform Strengthening the capacity OG/GO/PPA/06/2020 / Procur of the government to imple Request for Quota Single Stage - One E ement of office furniture for IDA / V1860 Post Limited 40,541.67 0.00 Canceled 2020-07-18 2020-09-12 2021-03-11 ment the State’s economic t tions nvelope PIU and other sectors ransformation agenda Results based financing to i OG/GO/PPA/09/2020 / Procur mprove the business-enablin e storage solutions for Deeds Request for Quota Single Stage - One E IDA / V1860 g environment and foster pri Post Limited 21,311.47 0.00 Canceled 2020-06-29 2020-08-24 2021-02-20 & Lands Registry and Archive tions nvelope vate sector participation in t s Records he agri-f ood and skills secto rs Strengthening the capacity OG/GO/PPA/10/2020 / Upgra of the government to imple Request for Quota Single Stage - One E de of IT infrastructure in Bud IDA / V1860 Post Limited 20,582.24 0.00 Canceled 2020-07-06 2020-08-31 2021-02-27 ment the State’s economic t tions nvelope get and Planning ransformation agenda Results based financing to i mprove the business-enablin OG/GO/PPA/11/2020 / Printin Request for Quota Single Stage - One E IDA / V1860 g environment and foster pri Post Limited 1,315.79 0.00 Canceled 2020-08-05 2020-09-30 2021-03-29 g of IPA Law tions nvelope vate sector participation in t he agri-f ood and skills secto rs Results based financing to i OG/GO/PPA/12/2020 / Produ mprove the business-enablin Request for Quota Single Stage - One E ction of revised Rules & Regu IDA / V1860 g environment and foster pri Post Limited 49,180.33 0.00 Canceled 2020-08-15 2020-10-10 2021-04-08 tions nvelope lations for BLS vate sector participation in t he agri-f ood and skills secto rs Results based financing to i OG/GO/PPA/08/2020 / Procur mprove the business-enablin ement of CRM (single source IDA / V1860 g environment and foster pri Post Direct Selection Direct 6,000.00 0.00 Canceled 2020-07-29 2020-06-04 2020-08-03 2020-09-04 2020-09-07 2021-03-06 ) and hands-on training vate sector participation in t he agri-f ood and skills secto rs Results based financing to i OG/GO/PPA/07/2020 / Procur mprove the business-enablin ement of IPA E-Learning tool IDA / V1860 g environment and foster pri Post Direct Selection Direct 10,000.00 0.00 Canceled 2020-07-20 2020-07-25 2020-08-29 2021-02-25 (single source) vate sector participation in t he agri-f ood and skills secto rs OG/GO/SDS/02/2021 / Suppl Results based financing to i y, install and commissioning mprove the business-enablin of EMIS equipment including g environment and foster pri Single Stage - One E Pending Impl IDA / 65240 Post Request for Bids Limited 1,100,000.00 0.00 2021-08-29 2021-09-03 2021-10-15 2021-11-14 2021-12-19 2022-06-17 capacity building on EMIS (In vate sector participation in t nvelope ementation cluding equipment for EMIS s he agri-f ood and skills secto ystem servers laptops hubs n rs etwork devices etc Results based financing to i OG/GO/SDS/01/2021 / Suppl mprove the business-enablin y, Installation and Commissio Single Stage - One E Pending Impl IDA / 65240 g environment and foster pri Post Request for Bids Open - National 700,000.00 0.00 2021-12-01 2021-12-06 2022-01-17 2022-02-16 2022-03-23 2022-09-19 ning of SMART Classroom Eq nvelope ementation vate sector participation in t uipment for STEM Teaching he agri-f ood and skills secto rs OG/GO/PIU/04/2021 / Supply Results based financing to i of Office Furniture, office ele mprove the business-enablin Single Stage - One E Under Imple ctronics and equipment for st IDA / 65240 g environment and foster pri Post Request for Bids Open - National 500,000.00 0.00 2021-12-01 2022-03-01 2021-12-06 2022-05-06 2022-01-17 2022-04-08 2022-02-16 2022-05-15 2022-03-23 2022-09-19 nvelope mentation aff and consultants of the PIU vate sector participation in t and the 3 sectors (Agric, Skill he agri-f ood and skills secto s and BEE) rs Results based financing to i OG/GO/PIU/02/2021 / Procur mprove the business-enablin Request for Quota Single Stage - One E Pending Impl ement of 20 motorcycles for IDA / 65240 g environment and foster pri Post Limited 40,000.00 0.00 2023-04-10 2023-06-05 2023-12-02 tions nvelope ementation Agric Sector vate sector participation in t he agri-f ood and skills secto rs OG/GO/PIU/01/2021 / Procur Results based financing to i ement of 13 Project Operatio mprove the business-enablin Under Imple nal Vehicles for the PIU and IDA / 65240 g environment and foster pri Post Direct Selection Direct - National 1,300,000.00 0.00 2023-04-09 2023-04-06 2023-04-14 2023-04-06 2023-05-19 2023-11-15 mentation all the Sectors within the Proj vate sector participation in t ect Double Cabin Pick-Up Va he agri-f ood and skills secto n rs Page 1 OG/GO/PIU/04/2022 / Procur Results based financing to i ement of Office Furniture, Off mprove the business-enablin Request for Quota Single Stage - One E Under Imple ice Electronics and Equipmen IDA / 65240 g environment and foster pri Post Limited 100,000.00 0.00 2023-04-25 2023-01-21 2023-06-20 2023-12-17 tions nvelope mentation t for the Bureau of Public Pro vate sector participation in t curement (BPP) he agri-f ood and skills secto rs Results based financing to i OG/GO/PIU/03/2021 / Supply mprove the business-enablin , installation and 1yr mainten Request for Quota Single Stage - One E Under Imple IDA / 65240 g environment and foster pri Post Limited 100,000.00 0.00 2023-05-02 2022-09-19 2023-06-27 2023-12-24 ance of a 200 KvA Electricity tions nvelope mentation vate sector participation in t Generator he agri-f ood and skills secto rs OG/GO/PIU/01/2021A / Procu Results based financing to i rement of 10 Project Operati mprove the business-enablin Under Imple onal Vehicles for the PIU and IDA / 65240 g environment and foster pri Post Direct Selection Direct - National 680,000.00 0.00 2023-04-27 2022-11-10 2023-05-02 2022-11-29 2023-06-06 2023-12-03 mentation all the Sectors within the Proj vate sector participation in t ect: Buses, Cars, Double Cabi he agri-f ood and skills secto n Pick-Up Van rs Results based financing to i OG/GO/PIU/02/2022 / Procur mprove the business-enablin ement of Office Furniture and Request for Quota Single Stage - One E Pending Impl IDA / 65240 g environment and foster pri Post Limited 100,000.00 0.00 2023-05-27 2023-07-22 2024-01-18 Equipment for Ogun Invest O tions nvelope ementation vate sector participation in t ffice he agri-f ood and skills secto rs NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Results based financing to i OG/NC/PIU/01/2021 / Procur mprove the business-enablin ement of Flexible Accounting Request for Quota Single Stage - One E Under Imple IDA / 65240 g environment and foster pri Post Limited 40,000.00 0.00 2021-08-24 2021-10-08 2022-04-06 Software for Project Financial tions nvelope mentation vate sector participation in t Management he agri-f ood and skills secto rs OG/GO/PSR/01/2021 / Devel Results based financing to i opment and deployment of t mprove the business-enablin he Management Information g environment and foster pri Request for Quota Single Stage - One E Pending Impl IDA / 65240 Post Limited 110,000.00 0.00 2023-05-16 2023-07-11 2024-01-07 System (MIS) for effective co vate sector participation in t tions nvelope ementation ordination, management an he agri-f ood and skills secto d reporting of all developmen rs t interventions and program mes CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual OG/CS/PPA/01/2020 / MTEF P reparation includng data gat Strengthening the capacity hering and validation, curren of the government to imple Consultant Qualifi IDA / V1860 Post Limited 40,131.58 0.00 Canceled 2020-06-28 2020-07-12 2020-08-11 2020-09-15 2021-03-14 t state assessment, sectorial ment the State’s economic t cation Selection stakeholder consultantion, fr ransformation agenda amework design and a valida tion workshop OG/CS/PPA/04/2020 / Consul Strengthening the capacity tancy on assessment for the of the government to imple Least Cost Selecti IDA / V1860 Post Open - National 27,631.58 0.00 Canceled 2020-07-27 2020-08-17 2020-09-30 2020-10-28 2020-11-27 2021-01-01 2021-02-05 2021-08-04 rehabilitation of Technical Co ment the State’s economic t on lleges ransformation agenda OG/CS/PPA/06/2020 / Assess Strengthening the capacity ment of EMIS at State, LGA a of the government to imple Least Cost Selecti IDA / V1860 Post Open - National 83,947.37 0.00 Canceled 2020-06-30 2020-07-20 2020-07-21 2020-09-02 2020-09-03 2021-04-15 2020-10-01 2020-10-31 2020-12-05 2021-01-09 2021-07-08 nd school level and improved ment the State’s economic t on design outline ransformation agenda Results based financing to i OG/CS/PPA/07/2020 / Recruit mprove the business-enablin ment of Business Environme Consultant Qualifi IDA / V1860 g environment and foster pri Post Open - National 42,174.30 0.00 Canceled 2020-07-13 2020-07-20 2020-08-03 2020-09-02 2020-09-16 2020-06-16 2020-10-16 2020-11-20 2021-05-19 nt Expert to conduct process cation Selection vate sector participation in t maps and roadmaps he agri-f ood and skills secto rs Results based financing to i OG/CS/PPA/08/2020 / Recruit mprove the business-enablin ment of Consultant to create Consultant Qualifi Under Implement IDA / V1860 g environment and foster pri Post Open - National 53,846.43 0.00 2020-06-29 2020-07-20 2020-07-20 2020-09-02 2020-09-02 2020-10-02 2020-11-06 2021-05-05 regulatory framework for OG cation Selection ation vate sector participation in t BEC/BES he agri-f ood and skills secto rs OG/CS/PPA/10/2020 / Engag Results based financing to i ement of Consultant for the mprove the business-enablin Least Cost Selecti Capacity building of staff (Mi IDA / V1860 g environment and foster pri Post Open - National 23,809.54 0.00 Canceled 2020-07-13 2020-08-03 2020-09-16 2020-10-14 2020-11-13 2020-12-18 2021-01-22 2021-07-21 on nistry of Industry, Trade & In vate sector participation in t vestment and OgunInvest) he agri-f ood and skills secto rs OG/CS/PPA/16/2020 / Diagno Results based financing to i stic Lands Compensation & A mprove the business-enablin nalysis, Review, of Current L g environment and foster pri Least Cost Selecti IDA / V1860 Post Open - National 84,141.52 0.00 Canceled 2020-06-29 2020-07-20 2020-07-20 2020-09-02 2020-09-30 2020-10-30 2020-12-04 2021-01-08 2021-07-07 and Administration/Process Fl vate sector participation in t on ow, Current Cost, Recommen he agri-f ood and skills secto dation and Implementation o rs f Improved Land Administrati on OG/CS/PPA/18/2020 / Assess Results based financing to i ment of existing gaps and ar mprove the business-enablin Least Cost Selecti eas of potential improvement IDA / V1860 g environment and foster pri Post Open - National 52,174.30 0.00 Canceled 2020-06-26 2020-07-17 2020-08-30 2020-09-27 2020-10-27 2020-12-01 2021-01-05 2021-07-04 on in the investment legal & reg vate sector participation in t ulatory framework he agri-f ood and skills secto rs OG/CS/PPA/23/2020 / Farm Results based financing to i & farmers registration, includ mprove the business-enablin Consultant Qualifi Under Implement ing Geo-tagging using digital IDA / V1860 g environment and foster pri Post Limited 94,736.84 0.00 2020-06-23 2020-07-20 2020-07-07 2021-04-14 2020-08-06 2020-09-10 2021-03-09 cation Selection ation tools & database developme vate sector participation in t nt he agri-f ood and skills secto rs Results based financing to i OG/CS/PPA/24/2020 / Engag mprove the business-enablin ement of Consultant for In-de Consultant Qualifi Under Implement IDA / V1860 g environment and foster pri Post Limited 47,368.42 0.00 2020-06-25 2020-07-20 2020-07-09 2021-03-04 2020-08-08 2020-09-12 2021-03-11 pth analysis of priority value cation Selection ation vate sector participation in t chains he agri-f ood and skills secto rs Results based financing to i OG/CS/PPA/25/2020 / Engag mprove the business-enablin ement of Consultant for Verifi Consultant Qualifi Under Implement IDA / V1860 g environment and foster pri Post Limited 47,368.42 0.00 2020-06-25 2020-07-20 2020-07-09 2021-04-14 2020-08-08 2020-09-12 2021-03-11 cation for Agric. Clusters, Ro cation Selection ation vate sector participation in t ads Etc he agri-f ood and skills secto rs Page 2 Results based financing to i OG/CS/PPA/26/2020 / Engag mprove the business-enablin Least Cost Selecti Under Implement ement of Consultant for Base IDA / V1860 g environment and foster pri Post Open - National 94,736.84 0.00 2020-06-25 2020-07-20 2020-07-16 2020-09-02 2020-08-29 2020-09-26 2020-10-26 2020-11-30 2021-01-04 2021-07-03 on ation line Studies - Agric vate sector participation in t he agri-f ood and skills secto rs Strengthening the capacity OG/CS/PPA/27/2020 / Engag of the government to imple Least Cost Selecti Under Implement IDA / V1860 Post Open - National 9,210.53 0.00 2020-06-22 2020-07-20 2020-07-13 2020-08-26 2020-09-23 2020-10-23 2020-11-27 2021-01-01 2021-06-30 ement of External Auditor ment the State’s economic t on ation ransformation agenda Results based financing to i OG/CS/PPA/43/2020 / Engag mprove the business-enablin Consultant Qualifi Under Implement ement of Value Chain Develo IDA / V1860 g environment and foster pri Post Open - National 61,666.67 0.00 2020-06-29 2020-07-20 2020-07-20 2020-09-02 2020-09-02 2020-10-02 2020-11-06 2021-05-05 cation Selection ation pment Firms (VCDF) vate sector participation in t he agri-f ood and skills secto rs OG/CS/PPA/22/2020 / Transa Results based financing to i ction Advisor to prepare com mprove the business-enablin Consultant Qualifi Under Implement petitive selection of private i IDA / V1860 g environment and foster pri Post Open - National 190,300.00 0.00 2020-08-17 2020-09-08 2020-09-07 2022-01-16 2020-10-21 2020-11-20 2020-12-25 2021-06-23 cation Selection ation ndustrial development and m vate sector participation in t anagement he agri-f ood and skills secto rs OG/CS/PPA/47/2020 / Engag Strengthening the capacity ement of Independent Verific of the government to imple Consultant Qualifi Under Implement ation Agency to undertake in IDA / V1860 Post Open - National 47,368.42 0.00 2020-07-20 2020-07-20 2020-08-10 2020-09-02 2020-09-23 2021-01-15 2020-10-23 2020-11-27 2021-05-26 ment the State’s economic t cation Selection ation dependent verification of OG ransformation agenda STEP program disbursement l inked indicators (DLIs) Results based financing to i OG/CS/AGR/01/2021 / Consu mprove the business-enablin ltancy for the engagement of Consultant Qualifi IDA / 65240 g environment and foster pri Post Open - National 300,000.00 0.00 Canceled 2021-08-29 2021-10-28 2021-09-28 2022-01-15 2021-11-11 2021-12-11 2022-01-15 2022-07-14 four (4) VCDFs for 2022, 2nd cation Selection vate sector participation in t batch he agri-f ood and skills secto rs OG/CS/AGR/03/2021 / Consu Results based financing to i ltancy to carry out feasibility mprove the business-enablin studies including ESIA on con g environment and foster pri Consultant Qualifi Under Implement IDA / 65240 Post Open - National 150,000.00 0.00 2021-08-02 2021-10-28 2021-08-23 2022-01-15 2021-10-06 2021-11-05 2021-12-10 2022-06-08 struction of 1,000 ha of small vate sector participation in t cation Selection ation -scale irrigation land and reh he agri-f ood and skills secto abilitation of 40km feeder ro rs ad. Results based financing to i OG/CS/AGR/05/2021 / Consu mprove the business-enablin ltancy to support and provide Consultant Qualifi Under Implement IDA / 65240 g environment and foster pri Post Open - National 100,000.00 0.00 2021-08-30 2021-10-28 2021-09-20 2022-01-15 2021-11-03 2021-12-03 2022-01-07 2022-07-06 Technical Assistance for the cation Selection ation vate sector participation in t Project on Agriculture FRILIA he agri-f ood and skills secto rs OG/CS/SDS/02/2021 / Consul Results based financing to i tancy to Develop Competenc mprove the business-enablin Consultant Qualifi Pending Impleme e-Based Curriculum for 10 Ne IDA / 65240 g environment and foster pri Post Limited 107,628.00 0.00 2021-08-12 2021-08-26 2021-09-25 2021-10-30 2022-04-28 cation Selection ntation w Courses for 8 Technical Co vate sector participation in t lleges in Ogun State he agri-f ood and skills secto rs OG/CS/SDS/03/2021 / Consul tancy for the development of Results based financing to i recruitment policy and practi mprove the business-enablin ces for the Ogun State Techn g environment and foster pri Consultant Qualifi Under Implement ical and Vocational Education IDA / 65240 Post Open - National 106,000.00 0.00 2021-08-27 2021-10-29 2021-09-17 2022-01-15 2021-10-31 2022-03-04 2021-11-30 2022-01-04 2022-07-03 vate sector participation in t cation Selection ation Board (OGTVEB), developme he agri-f ood and skills secto nt of Human Resources Polic rs y for Ogun Skills Fund and de velopment of governing polic y for the Ogun State Tec OG/CS/PIU/02/2021 / Consult Results based financing to i ancy to Hire Community-bas mprove the business-enablin Consultant Qualifi Under Implement ed NGO(s) as third-party serv IDA / 65240 g environment and foster pri Post Open - National 150,000.00 0.00 2021-11-19 2022-01-15 2021-12-10 2022-01-16 2022-01-23 2022-02-22 2022-03-29 2022-09-25 cation Selection ation ice providers on GBV/SEA/SH vate sector participation in t issues he agri-f ood and skills secto rs Results based financing to i OG/CS/PSR/01/2021 / Consul mprove the business-enablin tancy to conduct household s Consultant Qualifi Pending Impleme IDA / 65240 g environment and foster pri Post Limited 85,000.00 0.00 2021-11-29 2021-12-13 2022-01-12 2022-02-16 2022-08-15 urveys to support the creatio cation Selection ntation vate sector participation in t n of core welfare indicators he agri-f ood and skills secto rs OG/CS/BEE/04/2021 / Consul tancy to perform Reform an Results based financing to i d Interoperability of Ogun GI mprove the business-enablin S and LAMS, including baseli g environment and foster pri Quality And Cost- IDA / 65240 Post Open - National 1,100,000.00 0.00 Canceled 2021-12-16 2022-01-15 2022-01-06 2022-01-16 2022-02-19 2022-03-19 2022-04-18 2022-05-23 2022-06-27 2023-06-27 ne survey of BLS, Spatial Dat vate sector participation in t Based Selection a Collection for BLS and Syst he agri-f ood and skills secto ematic Titling Program to sup rs port the increase in the issua nce of titling in Ogun State INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual OG/CS/PPA/02/2020 / Design Strengthening the capacity , hosting and maintenance of of the government to imple Individual Consult IDA / V1860 Post Limited 26,315.79 0.00 Canceled 2020-07-13 2020-07-18 2020-08-08 2020-09-12 2021-03-11 OGSTEP website and mobile ment the State’s economic t ant Selection application ransformation agenda Results based financing to i OG/CS/PPA/11/2020 / Recruit mprove the business-enablin ment of Ogun Invest Board tr Individual Consult IDA / V1860 g environment and foster pri Post Limited 8,084.13 0.00 Canceled 2020-07-27 2020-08-01 2020-08-22 2020-09-26 2021-03-25 ainer, Delivery of training to ant Selection vate sector participation in t Ogun Invest Board he agri-f ood and skills secto rs OG/CS/PPA/12/2020 / Techni Results based financing to i cal Training for OgunInvest - mprove the business-enablin Individual Consult Business and Investment Res IDA / V1860 g environment and foster pri Post Limited 7,000.00 0.00 Canceled 2020-06-30 2020-07-05 2020-07-26 2020-08-30 2021-02-26 ant Selection earch & Reporting and Indust vate sector participation in t ry value chain analysis he agri-f ood and skills secto rs Results based financing to i OG/CS/PPA/13/2020 / Recruit mprove the business-enablin Individual Consult and appoint Baseline Survey IDA / V1860 g environment and foster pri Post Open 24,584.13 0.00 Canceled 2020-06-30 2020-08-18 2020-09-08 2020-10-13 2021-04-11 ant Selection Consultant vate sector participation in t he agri-f ood and skills secto rs Page 3 Results based financing to i OG/CS/PPA/14/2020 / Recruit mprove the business-enablin Individual Consult ment of Legal Policy Consulta IDA / V1860 g environment and foster pri Post Open 34,961.19 0.00 Canceled 2020-06-26 2020-07-20 2020-08-14 2020-09-04 2020-10-09 2021-04-07 ant Selection nt vate sector participation in t he agri-f ood and skills secto rs OG/CS/PPA/17/2020 / Review Results based financing to i of Current Survey Administra mprove the business-enablin Individual Consult tion/Process Flow, Current Co IDA / V1860 g environment and foster pri Post Limited 36,494.30 0.00 Canceled 2020-07-06 2020-07-11 2020-08-01 2020-09-05 2021-03-04 ant Selection st, Recommendation and Imp vate sector participation in t lementation of Improved Lan he agri-f ood and skills secto d Administration rs Results based financing to i mprove the business-enablin OG/CS/PPA/19/2020 / Sector Individual Consult IDA / V1860 g environment and foster pri Post Open 9,000.00 0.00 Canceled 2020-07-31 2020-09-18 2020-10-09 2020-11-13 2021-05-12 Scan Validation ant Selection vate sector participation in t he agri-f ood and skills secto rs Results based financing to i OG/CS/PPA/20/2020 / Analysi mprove the business-enablin s of growth potential and inv Individual Consult IDA / V1860 g environment and foster pri Post Open 49,000.00 0.00 Canceled 2020-08-03 2020-09-21 2020-10-12 2020-11-16 2021-05-15 estment landscape in key ec ant Selection vate sector participation in t onomic sectors he agri-f ood and skills secto rs OG/CS/PPA/44/2020 / Engag Results based financing to i ement of Media consultant fo mprove the business-enablin Individual Consult r the production of Jingles on IDA / V1860 g environment and foster pri Post Limited 5,263.00 0.00 Canceled 2020-06-29 2020-07-04 2020-07-25 2020-08-29 2021-02-25 ant Selection Radio and TV, Interviews - A vate sector participation in t GRIC he agri-f ood and skills secto rs Results based financing to i OG/CS/PPA/21/2020 / Recruit mprove the business-enablin Individual Consult ment of Communication Strat IDA / V1860 g environment and foster pri Post Limited 52,174.30 0.00 Canceled 2020-06-30 2020-07-20 2020-07-05 2020-07-26 2020-08-30 2021-02-26 ant Selection egy Consultant for IPA vate sector participation in t he agri-f ood and skills secto rs Results based financing to i OG/CS/PPA/45/2020 / Engag mprove the business-enablin Individual Consult ement of Consultant for Inve IDA / V1860 g environment and foster pri Post Limited 29,000.00 0.00 Canceled 2020-08-17 2020-08-22 2020-09-12 2020-10-17 2021-04-15 ant Selection stor expansion survey vate sector participation in t he agri-f ood and skills secto rs Results based financing to i mprove the business-enablin OG/CS/PPA/46/2020 / Deep d Individual Consult IDA / V1860 g environment and foster pri Post Limited 20,000.00 0.00 Canceled 2020-08-03 2020-08-08 2020-08-29 2020-10-03 2021-04-01 ives ant Selection vate sector participation in t he agri-f ood and skills secto rs OG/CS/PPA/35/2020 / Engag Results based financing to i ement of key project staff / C mprove the business-enablin Individual Consult onsultants (Agric – Sector Te IDA / V1860 g environment and foster pri Post Open 31,578.95 0.00 Canceled 2020-07-20 2020-03-02 2020-09-07 2020-09-28 2020-11-02 2021-05-01 ant Selection chnical Team) - Environment vate sector participation in t al Specialist he agri-f ood and skills secto rs OG/CS/PPA/36/2020 / Engag Results based financing to i ement of key project staff / C mprove the business-enablin Individual Consult onsultants (Agric – Sector Te IDA / V1860 g environment and foster pri Post Open 31,578.95 0.00 Canceled 2020-07-20 2020-03-02 2020-09-07 2020-09-28 2020-11-02 2021-05-01 ant Selection chnical Team) - Social Specia vate sector participation in t list he agri-f ood and skills secto rs OG/CS/PPA/37/2020 / Engag Results based financing to i ement of key project staff / C mprove the business-enablin Individual Consult onsultants (Agric – Sector Te IDA / V1860 g environment and foster pri Post Open 31,578.95 0.00 Canceled 2020-07-20 2020-04-06 2020-09-07 2021-04-15 2020-09-28 2020-11-02 2021-05-01 ant Selection chnical Team) - FRILIA Specia vate sector participation in t list he agri-f ood and skills secto rs OG/CS/PPA/40/2020 / Engag Results based financing to i ement of key project staff / C mprove the business-enablin Individual Consult onsultants (Business Environ IDA / V1860 g environment and foster pri Post Open 31,578.95 0.00 Canceled 2020-07-20 2020-03-26 2020-09-07 2020-09-28 2020-11-02 2021-05-01 ant Selection ment – Sector Technical Tea vate sector participation in t m) - Industrial Estate Speciali he agri-f ood and skills secto st rs OG/CS/PPA/31/2020 / Engag Strengthening the capacity ement of key project staff / C of the government to imple Individual Consult Under Implement IDA / V1860 Prior Open 31,578.95 0.00 2020-07-20 2020-08-26 2020-09-07 2020-09-28 2020-11-02 2021-05-01 onsultants (PIU) - Procureme ment the State’s economic t ant Selection ation nt Specialist ransformation agenda OG/CS/PPA/32/2020 / Engag Strengthening the capacity ement of key project staff / C of the government to imple Individual Consult IDA / V1860 Prior Open 31,578.95 0.00 Under Review 2020-07-20 2020-09-02 2020-09-07 2021-01-25 2020-09-28 2020-11-02 2021-05-01 onsultants (PIU) - Procureme ment the State’s economic t ant Selection nt Reform Specialist ransformation agenda Results based financing to i OG/CS/PPA/15/2020 / Recruit mprove the business-enablin Individual Consult ment of Physical Planning La IDA / V1860 g environment and foster pri Post Limited 18,567.74 0.00 Canceled 2020-06-29 2020-07-04 2020-07-25 2020-08-29 2021-02-25 ant Selection w review consultant vate sector participation in t he agri-f ood and skills secto rs Results based financing to i OG/CS/PPA/52/2020 / Engag mprove the business-enablin Individual Consult ement of Project Manager - A IDA / V1860 g environment and foster pri Post Open 75,000.00 0.00 Canceled 2021-01-14 2021-01-15 2021-03-03 2021-03-09 2021-04-13 2021-10-10 ant Selection griculture vate sector participation in t he agri-f ood and skills secto rs Results based financing to i OG/CS/PPA/53/2020 / Engag mprove the business-enablin Individual Consult Under Implement ement of Project Manager - S IDA / V1860 g environment and foster pri Post Open 75,000.00 0.00 2021-01-14 2021-01-15 2021-02-27 2021-03-05 2021-04-09 2021-10-06 ant Selection ation kills Development vate sector participation in t he agri-f ood and skills secto rs Results based financing to i OG/CS/PPA/54/2020 / Engag mprove the business-enablin ement of Project Manager - B Individual Consult IDA / V1860 g environment and foster pri Post Open 75,000.00 0.00 Canceled 2021-01-14 2021-01-15 2021-03-03 2021-03-09 2021-04-13 2021-10-10 usiness Enabling Environmen ant Selection vate sector participation in t t (BEE) he agri-f ood and skills secto rs OG/CS/PPA/48/2020 / Consul Results based financing to i tancy to prepare the Stakeho mprove the business-enablin Individual Consult Under Implement lder Engagement Plan (SEP) IDA / V1860 g environment and foster pri Post Open 80,000.00 0.00 2021-01-18 2021-01-18 2021-03-10 2021-04-15 2021-03-24 2021-04-26 2021-08-31 ant Selection ation and Grievance Redress Mech vate sector participation in t anism (GRM) he agri-f ood and skills secto rs Results based financing to i OG/CS/AGR/06/2021 / Recrui mprove the business-enablin Individual Consult Under Implement tment of Project Manager for IDA / 65240 g environment and foster pri Post Open 60,000.00 0.00 2021-08-18 2021-10-28 2021-10-06 2022-01-18 2021-10-27 2022-03-15 2021-12-01 2022-05-30 ant Selection ation the Agric Sector vate sector participation in t he agri-f ood and skills secto rs Page 4 Results based financing to i OG/CS/BEE/01/2021 / Recruit mprove the business-enablin Individual Consult Under Implement ment of Project Manager for t IDA / 65240 g environment and foster pri Post Open 60,000.00 0.00 2021-08-18 2022-01-15 2021-10-06 2021-10-27 2021-12-01 2022-05-30 ant Selection ation he BEE Sector vate sector participation in t he agri-f ood and skills secto rs Results based financing to i OG/CS/PIU/05/2021 / Engage mprove the business-enablin Individual Consult ment of Gender Assitant sup IDA / 65240 g environment and foster pri Post Open 33,000.00 0.00 Canceled 2021-08-23 2021-10-11 2021-11-01 2021-12-06 2022-06-04 ant Selection port Specialist vate sector participation in t he agri-f ood and skills secto rs OG/CS/SDS/01/2021 / Consul Results based financing to i tancy for the Development of mprove the business-enablin Under Implement Modified PMI-PSI STEM Teach IDA / 65240 g environment and foster pri Post Direct Selection Direct 400,000.00 0.00 2021-11-18 2022-01-15 2021-11-28 2022-01-16 2022-02-01 2022-07-31 ation ing Package and Training of vate sector participation in t Trainer (ToT) for STEM Teach he agri-f ood and skills secto ers rs OG/CS/BEE/07/2021 / Consul Results based financing to i tancy to create the Regulator mprove the business-enablin Individual Consult y Framework of the Business IDA / 65240 g environment and foster pri Post Open 54,500.00 54,912.95 Signed 2021-11-22 2022-01-15 2022-01-10 2022-04-12 2022-01-31 2022-04-12 2022-03-07 2022-03-02 2022-09-03 ant Selection Environment Council in Ogun vate sector participation in t State he agri-f ood and skills secto rs OG/CS/SDS/05/2021 / Consul Results based financing to i tancy to conduct NOS Review mprove the business-enablin Individual Consult Under Implement for 10 trades plus Entreprene IDA / 65240 g environment and foster pri Post Limited 115,000.00 0.00 2021-11-23 2022-01-15 2021-11-28 2022-05-13 2021-12-19 2022-01-23 2022-07-22 ant Selection ation urship, Leadership and Litera vate sector participation in t cy skills he agri-f ood and skills secto rs OG/CS/PSR/03/2021 / Consul Results based financing to i tancy to conduct M&E Baseli mprove the business-enablin Individual Consult Under Implement ne Survey to determine basel IDA / 65240 g environment and foster pri Post Limited 150,000.00 0.00 2021-11-22 2022-05-05 2021-11-27 2021-05-28 2021-12-18 2022-01-22 2022-07-21 ant Selection ation ine statistical data for all Mini vate sector participation in t stries, Departments and Age he agri-f ood and skills secto ncies in Ogun State rs OG/NC/PIU/02/2021 / Consult Results based financing to i ancy for 2 Documentaries on mprove the business-enablin Individual Consult Under Implement SEA/SH educating parents on IDA / 65240 g environment and foster pri Post Limited 40,000.00 0.00 2021-11-24 2022-01-15 2021-11-29 2022-05-24 2021-12-20 2022-08-31 2022-01-24 2022-07-23 ant Selection ation Boy-child abuse in schools an vate sector participation in t d Girl Child Education he agri-f ood and skills secto rs OG/CS/PIU/07/2021 / Consult Results based financing to i ancy to design, develop, and mprove the business-enablin Individual Consult deploy Websites and Social IDA / 65240 g environment and foster pri Post Limited 25,000.00 0.00 Canceled 2021-11-22 2021-11-27 2021-12-18 2022-01-22 2022-07-21 ant Selection Media platforms for the Skill vate sector participation in t Sector he agri-f ood and skills secto rs OG/CS/PIU/08/2021 / Recruit Results based financing to i ment of Project Coordinator mprove the business-enablin Individual Consult Under Implement Consultant for the Ogun Stat IDA / 65240 g environment and foster pri Post Direct 90,000.00 0.00 2022-05-05 2022-05-05 2022-05-06 2022-05-05 2022-05-06 2022-05-06 2022-05-08 2022-11-04 ant Selection ation e Economic Transformation P vate sector participation in t roject (OGSTEP) he agri-f ood and skills secto rs Results based financing to i OG/CS/PSR/04/2021 / Recruit mprove the business-enablin Under Implement ment of Procurement Reform IDA / 65240 g environment and foster pri Post Direct Selection Direct 44,000.00 0.00 2022-05-27 2022-05-27 2022-05-30 2022-06-24 2022-06-24 2022-12-21 ation Specialist for the BPP vate sector participation in t he agri-f ood and skills secto rs Results based financing to i OG/CS/PIU/01/2022 / Recruit mprove the business-enablin ment of Social Safeguard Spe Individual Consult Under Implement IDA / 65240 g environment and foster pri Post Limited 40,000.00 0.00 2023-04-28 2022-10-25 2023-05-03 2022-10-26 2023-05-24 2023-02-08 2023-06-28 2023-12-25 cialist for the Project Implem ant Selection ation vate sector participation in t entation Unit he agri-f ood and skills secto rs Results based financing to i OG/CS/PIU/02/2022 / Recruit mprove the business-enablin ment of Environmental Safeg Individual Consult IDA / 65240 g environment and foster pri Post Limited 40,000.00 0.00 Under Review 2023-04-28 2022-10-25 2023-05-03 2023-05-24 2023-06-28 2023-12-25 uard Specialist for the Project ant Selection vate sector participation in t Implementation Unit he agri-f ood and skills secto rs Results based financing to i OG/CS/SDS/01/2022 / Consul mprove the business-enablin tancy to Develop Communica Individual Consult Under Implement IDA / V1860 g environment and foster pri Post Limited 50,000.00 0.00 2023-04-29 2022-09-19 2023-05-04 2022-09-19 2023-05-25 2023-05-03 2023-06-29 2023-12-26 tion Strategy and Materials f ant Selection ation vate sector participation in t or Ogun State Skills Fund he agri-f ood and skills secto rs Results based financing to i OG/CS/SDS/07/2022 / Recrui mprove the business-enablin Under Implement tment of Project Manager for IDA / 65240 g environment and foster pri Post Direct Selection Direct - National 54,000.00 0.00 2023-05-04 2022-11-27 2023-05-14 2023-07-18 2024-01-14 ation the Skills vate sector participation in t he agri-f ood and skills secto rs Results based financing to i OG/CS/BEE/01/2022 / Recruit mprove the business-enablin ment of Land Admin. Consult Individual Consult IDA / 65240 g environment and foster pri Post Limited 40,000.00 0.00 Under Review 2023-05-23 2022-09-19 2023-05-28 2023-06-18 2023-07-23 2024-01-19 ant for the Business Enabling ant Selection vate sector participation in t Environment (BEE) he agri-f ood and skills secto rs Page 5 PROCUREMENT PLAN(Textual Part) Project information: INDIA, Assam Agribusiness and Rural Transformation Project (APART) Project Implementation agency: Assam Rural Infrastructure and Agricultural Services Society (ARIASS)is the main agency. Date of the Procurement Plan (Textual Part) : February 03, 2022 Period covered by this Procurement Plan:Until publication of next version of the Procurement Plan (Textual Part). Preamble In accordance with paragraph5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”)the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plansand conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEPconstitute the Procurement Plan for the Project.The following conditionsapply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. Procurement for the project will be carried out in accordance with the World Bank’s Procurement Regulations for IPF Borrowers, July 2016, applicable to Investment Project Financing (IPF). The project will be subject to the World Bank’s Anticorruption Guidelines, dated October 15, 2006, as revised in January 2011 and July 2016. The table below describes various procurement methods to be used for activities financed by the loan. The thresholds (Table 1) indicated will govern the procurement approach and methods; Table 1: Procurement Thresholds Procurement Approaches and Methods Thresholds (US$ equivalent) Open international (works – including turnkey, Any value activity supply and installation of plant and equipment and PPP) Open national (works – including turnkey, supply Below 40 million and installation of plant and equipment and PPP) Open international (goods, IT system, and non- Any value activity consulting services) Open national (goods, IT system, and non- Below 10 million consulting services) National request for quotation (goods and Up to 100,000 works) Direct selection No threshold; For works, goods, non-consulting services and IT system procurement: According to paragraphs 6.8– 6.10 of the Regulations; For consultants: According to paragraphs 7.13–7.15 of the Regulations Shortlist of national consultants Up to 2,000,000 Procurement prior-review thresholds. The World Bank will prior review the following contracts: 1. Works (including turnkey, supply and installation of plant and equipment and PPP): All contracts more than US$ 15 million equivalent 2. Goods, IT system and Non-consulting services: All contracts more than US$4 million equivalent 3. Consultants: All contracts >US$2 million equivalent for firms and >US$400,000 equivalent for individuals 4. There is no automatic requirement to undertake prior review for direct selection for value less than these thresholds 5. Additional provisions as mentioned at paragraph 2.2, 2.3, 2.4 & 2.5 of Annex I (Mandatory Procurement Prior Review Thresholds) under Bank Procedure (Effective August 01, 2018), “Procurement in IPF and Other Operational Procurement Matters” will also apply. National Procurement Arrangements:National competition for the procurement of works, goods, IT system procurement and non-consulting services according to the established thresholds will be conducted in accordance with paragraphs 5.3–5.5 of Section V of the Regulations and the following provisions: 1. Only the model bidding documents for National Competitive Procurement (NCP) agreed with the GOI Task Force (and as amended for time to time), shall be used for bidding. 2. Invitations to bid shall be advertised on a widely used website or electronic portal with free open access at least 30 days prior to the deadline for the submission of bids, unless otherwise agreed in the approved procurement plan. 3. No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprises from any given State. 4. Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder. 5. Government e-Marketplace (GeM) set-up by Ministry of Commerce, Government of India will be acceptable for procurement under Request for Quotations (RFQ) method. 6. At the Borrower’s request, the Bank may agree to the Borrower’s use, in whole or in part, of its electronic procurement system, provided that the Bank is satisfied with the adequacy of such system. 7. Procurement will be open to eligible firms from any country. This eligibility shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 8. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals include a signed acceptance in the bid, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 9. The Borrower shall use an effective complaints mechanism for handling procurement related complaints in a timely manner. 10. Procurement Documents will include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts. Domestic preference-The provision of domestic preference will be applied in the evaluation of bids in accordance with Annex VI of the Regulations. Procurement of Works, Goods (Supply and Installation; and IT Equipment), Non-Consultancy Services and Consultancy Services – As per procurement plan approved in STEP. PROCUREMENT India : Assam Agribusiness and Rural Transformation Project PLAN General Information Country: India 2019-05-21 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P155617 GPN Date: Project Name: Assam Agribusiness and Rural Transformation Project Loan / Credit No: IBRD / 87800 Assam Agricultural University Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-OPIU-AAU-220708-CW-RF Request for Bids - B / Civil works for newly setu Component C: Fostering Mar Single Stage - Two E Small Works SPD 2023-04-1 p Agricultural Market Intellig IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 178,571.42 152,693.81 Signed 2021-06-08 2021-10-01 2021-06-13 2022-03-15 2021-07-25 2021-11-02 2021-10-07 2022-01-03 2021-11-11 2022-02-11 nvelope (2 envelope proce 6 ence unit office building at A ence Enhancement ss) ssam Agricultural University, Jorhat, Assam, India IN-OPIU-AAU-231642-CW-RF Q / Minor Civil works related t Component C: Fostering Mar Request for Quota Request for Quota Single Stage - One E 2022-02-0 o setting up of Farmer Produ IBRD / 87800 ket-led Production and Resili Post Open - National tions (Non Bank-S 50,328.58 42,587.56 Signed 2021-06-13 2022-03-24 2021-08-08 2022-05-08 tions nvelope 4 cer Company Coordination ce ence Enhancement PD) ntre at Assam Agricultural Un iversity, Jorhat IN-OPIU-AAU-266883-CW-RF Component C: Fostering Mar Request for Quota Request for Quota Single Stage - One E 2022-01-2 Q / Construction of low cost i IBRD / 87800 ket-led Production and Resili Post Open - National tions (Non Bank-S 26,613.33 24,904.13 Completed 2021-12-22 2021-12-17 2022-01-09 2021-10-09 tions nvelope 6 nsect proof net house 12 nos ence Enhancement PD) . IN-OPIU-AAU-304487-CW-RF Q / Construction of Shed for s afe keeping of farm machiner y 7 nos. at the following AAU Component C: Fostering Mar Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-10-2 stations KVK Kamrup, KVK Ba IBRD / 87800 ket-led Production and Resili Post Open - National tions (Non Bank-S 26,305.49 0.00 2022-08-02 2022-09-27 tions nvelope lementation 7 rpeta, KVK Nagaon, KVK Soni ence Enhancement PD) tpur, KVK Kokrajhar, KVK Mor igaon and KVK Jorhat 1 US$ = Rs. 79.83 IN-OPIU-AAU-310859-CW-RF Q / Construction of 10 nos. lo Component C: Fostering Mar Request for Quota Request for Quota Single Stage - One E 2022-12-0 w cost insect proof net house IBRD / 87800 ket-led Production and Resili Post Open - National tions (Non Bank-S 31,305.80 0.00 Completed 2022-09-10 2022-12-13 2022-10-12 tions nvelope 1 with sprinkler/drip irrigation s ence Enhancement PD) ystem. 1$ = Rs. 79.61 IN-OPIU-AAU-326474-CW-RF B / Different Works for Devel National Procure opment of Fisheries Based In Component C: Fostering Mar ment Document - Single Stage - Two E Pending Imp 2023-11-0 tegrated Farming System Mo IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 2 Envelope proce 259,518.22 0.00 2022-12-01 2022-12-06 2023-01-17 2023-04-01 2023-05-06 nvelope lementation 2 dels for Livelihood and Incom ence Enhancement ss (Non Bank-SPD e Generation of Farmers at C ) VSc., AAU, Khanapara, Guwa hati-781022, Assam National Procure IN-OPIU-AAU-358498-CW-RF Component C: Fostering Mar ment Document - B / Establishment of one (1) F Single Stage - Two E Pending Imp 2024-03-3 IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 2 Envelope proce 279,878.76 0.00 2023-05-10 2023-05-15 2023-06-26 2023-09-08 2023-10-02 arm Machinery Training Cent nvelope lementation 0 ence Enhancement ss (Non Bank-SPD ers at Assam Agricultural Uni ) versity, Jorhat, Assam IN-OPIU-AAU-358501-CW-RF National Procure B / Establishment of two (2) F Component C: Fostering Mar ment Document - arm Machinery Training Cent Single Stage - Two E Pending Imp 2024-03-3 IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 2 Envelope proce 508,919.26 0.00 2023-05-10 2023-05-15 2023-06-26 2023-09-08 2023-10-02 ers at KVK-Nagoan and Sarat nvelope lementation 0 ence Enhancement ss (Non Bank-SPD Chandra Singha College of A ) griculture, Dhubri under Assa m Agricultural University, Jor hat. IN-OPIU-AAU-362895-CW-RF B / Title: Development of Fish eries Based Integrated Farmi Request for Bids - ng System Models for Livelih Component C: Fostering Mar Single Stage - Two E Small Works SPD Pending Imp 2023-12-2 ood and Income Generation IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 166,910.90 0.00 2023-05-29 2023-06-03 2023-06-13 2023-06-22 2023-06-26 nvelope (2 envelope proce lementation 3 of Farmers at College of Vete ence Enhancement ss) rinary Science. AAU, Guwaha ti. Tendering for the above work was divided into two (2) pack ages. Package 1 and Packag eIN-OPIU-AAU-363142-CW-RF 2 B / Title: Development of Fish eries Based Integrated Farmi National Procure ng System Models for Livelih Component C: Fostering Mar ment Document - Single Stage - Two E Pending Imp 2023-12-2 ood and Income Generation IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 2 Envelope proce 81,308.30 0.00 2023-05-29 2023-06-03 2023-06-13 2023-06-22 2023-06-26 nvelope lementation 3 of Farmers at College of Vete ence Enhancement ss (Non Bank-SPD rinary Science. AAU, Guwaha ) ti. Tendering for the above w ork was divided into two (2) packages. Package 1 and Pac kage 2 National Procure IN-OPIU-AAU-363158-CW-RF Component C: Fostering Mar ment Document - B / Title: Development of Mo Single Stage - Two E Pending Imp 2023-12-2 IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 2 Envelope proce 72,848.00 0.00 2023-05-29 2023-06-03 2023-06-13 2023-06-22 2023-06-26 del Seed bank at College of F nvelope lementation 3 ence Enhancement ss (Non Bank-SPD isheries, RAHA, Nagoan. ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-OPIU-AAU-114957-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU : Procurement of Co IBRD / 87800 Post Open - National 14,286.00 17,682.65 Completed 2019-06-29 2020-06-19 2019-08-24 2019-07-30 2019-10-23 2020-05-20 Enterprise Development tions nvelope mbine Harvester (Mini) IN-OPIU-AAU-114966-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU Procurement : Recir IBRD / 87800 Post Open - National 10,000.00 0.00 Canceled 2019-06-29 2019-08-24 2019-10-23 Enterprise Development tions nvelope culating Batch Dryer IN-OPIU-AAU-114971-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU Procurement : Indent IBRD / 87800 Post Open - National 11,429.00 11,453.62 Completed 2019-06-29 2020-06-19 2019-08-24 2019-07-30 2019-10-23 2019-11-15 Enterprise Development tions nvelope - cylinder Separator Page 1 IN-OPIU-AAU-114973-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU Procurement : Rice IBRD / 87800 Post Open - National 26,000.00 22,027.60 Completed 2019-06-29 2020-06-20 2019-08-24 2019-07-21 2019-10-23 2019-08-31 Enterprise Development tions nvelope Transplantor IN-OPIU-AAU-114972-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU, Procurement of Port IBRD / 87800 Post Open - National 17,143.00 18,795.72 Completed 2019-06-29 2020-06-20 2019-08-24 2019-07-30 2019-10-23 2020-02-18 Enterprise Development tions nvelope able Rice Mill. IN-OPIU-AAU-114974-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU Procurement : Power IBRD / 87800 Post Open - National 12,500.00 13,704.80 Completed 2019-06-29 2020-08-24 2019-08-24 2019-07-30 2019-10-23 2020-03-01 Enterprise Development tions nvelope Tiller Inclined plate planter IN-OPIU-AAU-114975-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU, Procurement of Mus IBRD / 87800 Post Open - National 10,714.00 0.00 Canceled 2019-06-29 2019-08-24 2019-10-23 Enterprise Development tions nvelope tard Seed Drill 2 Row IN-OPIU-AAU-114976-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU Procurement : Power IBRD / 87800 Post Open - National 19,643.00 11,684.97 Completed 2019-06-29 2020-08-24 2019-08-24 2019-07-30 2019-10-23 2020-01-07 Enterprise Development tions nvelope Paddy Weeder IN-OPIU-AAU-114978-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU, Procurement of Maiz IBRD / 87800 Post Open - National 27,143.00 0.00 Canceled 2019-06-29 2019-08-24 2019-10-23 Enterprise Development tions nvelope e Planter (Power Tiller Operat ed). IN-OPIU-AAU-114982-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 18,571.00 13,620.24 Completed 2019-06-29 2020-06-19 2019-08-24 2019-07-30 2019-10-23 2020-02-20 Q / AAU Procurement : Potato Enterprise Development tions nvelope Planter IN-OPIU-AAU-118782-NC-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of GIS Softw IBRD / 87800 Post Open - National 12,811.42 8,008.36 Completed 2019-06-28 2020-12-24 2019-08-23 2020-02-02 2019-10-22 2020-03-14 Enterprise Development tions nvelope are, AAU Jorhat IN-OPIU-AAU-118780-GO-RF Q / Procurement of Computer Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 14,285.71 20,305.94 Completed 2019-06-28 2020-12-29 2019-08-23 2020-01-07 2019-10-22 2020-02-21 servers for satellite data proc Enterprise Development tions nvelope essing, AAU Jorhat, Through GeM . IN-OPIU-AAU-118783-NC-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of Image pr IBRD / 87800 Post Open - National 23,714.28 8,551.30 Completed 2019-06-28 2020-12-23 2019-08-23 2019-11-02 2019-10-22 2020-02-18 Enterprise Development tions nvelope ocessing software, AAU Jorha t IN-OPIU-AAU-122187-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of agricultur IBRD / 87800 Post Open - National 19,304.30 18,605.56 Completed 2019-07-16 2020-02-03 2019-08-09 2018-12-11 2019-08-15 2019-03-30 Enterprise Development tions nvelope al machine Reaper for AAU, J orhat IN-OPIU-AAU-122192-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of agricultur IBRD / 87800 Post Open - National 23,373.90 2,371.08 Completed 2019-07-16 2020-05-11 2019-08-09 2018-12-11 2019-08-15 2019-03-20 Enterprise Development tions nvelope al machine Axial Flow Thresh er for AAU, Jorhat IN-OPIU-AAU-122194-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of agricultur IBRD / 87800 Post Open - National 10,898.60 1.24 Completed 2019-07-16 2019-08-09 2018-12-11 2019-08-15 2019-03-20 Enterprise Development tions nvelope al goods Super Bag for AAU, J orhat. IN-OPIU-AAU-122197-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of agricultur IBRD / 87800 Post Open - National 15,550.70 14,673.50 Signed 2019-07-16 2021-01-02 2019-08-09 2018-12-11 2019-08-15 Enterprise Development tions nvelope al product RCC Ring Bin for A AU, Jorhat. IN-OPIU-AAU-122205-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of agricultur IBRD / 87800 Post Open - National 43,478.30 3,959.54 Completed 2019-07-16 2020-05-11 2019-08-09 2018-12-11 2019-08-15 2019-03-21 Enterprise Development tions nvelope al machine Portable Rice Mill for AAU, Jorhat. IN-OPIU-AAU-122207-GO-RF Q / Procurement of agricultur Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 18,724.60 16,997.66 Completed 2019-07-16 2020-05-19 2019-08-09 2018-12-11 2019-08-15 2019-03-21 al machine Seed cum Fertiliz Enterprise Development tions nvelope er Drill for AAU, Jorhat IN-OPIU-AAU-122213-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of agricultur IBRD / 87800 Post Open - National 10,898.60 9,958.16 Completed 2019-07-16 2020-05-19 2019-08-09 2018-12-11 2019-08-15 2019-03-21 Enterprise Development tions nvelope al machine Power weeder for AAU, Jorhat. IN-OPIU-AAU-122214-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of agricultur IBRD / 87800 Post Open - National 14,492.80 13,198.04 Completed 2019-07-16 2020-05-18 2019-08-09 2018-12-11 2019-08-15 2019-03-21 Enterprise Development tions nvelope al machine Drum Seeder for AAU, Jorhat. IN-OPIU-AAU-122217-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of agricultur IBRD / 87800 Post Open - National 25,869.60 3,354.80 Completed 2019-07-16 2020-05-18 2019-08-09 2018-12-11 2019-08-15 2019-03-20 Enterprise Development tions nvelope al machine Rice Transplanter for AAU, Jorhat IN-OPIU-AAU-157433-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Combine Harvest IBRD / 87800 Post Open - National 16,856.30 18,209.13 Completed 2020-02-19 2020-12-08 2020-04-15 2020-02-02 2020-10-12 2020-05-20 Enterprise Development tions nvelope er (Mini) for Assam Agricultur al University under APART pr oject. IN-OPIU-AAU-157434-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Re-circulating Bat IBRD / 87800 Post Open - National 9,832.84 0.00 Canceled 2020-02-19 2020-04-15 2020-10-12 Enterprise Development tions nvelope ch Dryer for Assam Agricultur al University under APART pr oject. IN-OPIU-AAU-157437-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Portable Rice Mill IBRD / 87800 Post Open - National 37,926.67 0.00 Canceled 2020-02-19 2020-04-15 2020-10-12 Enterprise Development tions nvelope for Assam Agricultural Univer sity under APART project. IN-OPIU-AAU-157442-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Indent-Cylinder S IBRD / 87800 Post Open - National 11,237.53 3,001.86 Terminated 2020-02-19 2020-12-30 2020-04-15 2020-06-04 2020-10-12 Enterprise Development tions nvelope eparator for Assam Agricultur al University under APART pr oject. IN-OPIU-AAU-157444-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 11,237.53 0.00 Canceled 2020-02-19 2020-04-15 2020-10-12 al Rice Flake Machine for Ass Enterprise Development tions nvelope am Agricultural University un der APART project. IN-OPIU-AAU-157447-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Rice Transplanter IBRD / 87800 Post Open - National 25,284.45 0.00 Canceled 2020-02-19 2020-04-15 2020-10-12 Enterprise Development tions nvelope for Assam Agricultural Univer sity under APART project. Page 2 IN-OPIU-AAU-157449-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Power Paddy We IBRD / 87800 Post Open - National 13,485.04 8,068.99 Completed 2020-02-19 2020-12-29 2020-04-15 2020-06-04 2020-10-12 2020-10-11 Enterprise Development tions nvelope eder for Assam Agricultural U niversity under APART projec t. IN-OPIU-AAU-157450-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 22,475.06 18,556.93 Completed 2020-02-19 2020-12-30 2020-04-15 2020-06-04 2020-10-12 2020-12-15 al Machine Seed Drill for Ass Enterprise Development tions nvelope am Agricultural University un der APART project. IN-OPIU-AAU-157451-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 14,046.91 7,838.94 Completed 2020-02-19 2020-12-30 2020-04-15 2020-06-04 2020-10-12 2020-11-14 al Machine Drum Seeder for Enterprise Development tions nvelope Assam Agricultural University under APART project. IN-OPIU-AAU-157452-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Battery Operated IBRD / 87800 Post Open - National 16,856.30 4,034.49 Terminated 2020-02-19 2020-12-30 2020-04-15 2020-06-04 2020-10-12 Enterprise Development tions nvelope Power Sprayer for Assam Agr icultural University under AP ART project. IN-OPIU-AAU-157453-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Axial Flow Thresh IBRD / 87800 Post Open - National 20,227.56 19,648.51 Completed 2020-02-19 2020-12-30 2020-04-15 2020-06-04 2020-10-12 2021-03-27 Enterprise Development tions nvelope er for Assam Agricultural Uni versity under APART project. IN-OPIU-AAU-157467-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 21,070.37 18,420.48 Completed 2020-02-19 2020-12-30 2020-04-15 2020-06-04 2020-10-12 2020-10-08 al Reaper Machine for Assam Enterprise Development tions nvelope Agricultural University under APART project. IN-OPIU-AAU-157469-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Solar Bubble Drye IBRD / 87800 Post Open - National 9,832.84 8,716.13 Completed 2020-02-19 2020-12-30 2020-04-15 2020-06-04 2020-10-12 2021-01-01 Enterprise Development tions nvelope r for Assam Agricultural Univ ersity under APART project. IN-OPIU-AAU-157470-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 11,799.41 11,271.13 Completed 2020-02-19 2020-12-30 2020-04-15 2020-06-04 2020-10-12 2021-01-01 al Super Bag for Assam Agric Enterprise Development tions nvelope ultural University under APAR T project. IN-OPIU-AAU-157473-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 10,394.71 0.00 Canceled 2020-02-19 2020-04-15 2020-10-12 al RCC Ring Bin for Assam Ag Enterprise Development tions nvelope ricultural University under AP ART project. IN-OPIU-AAU-157476-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 11,237.53 4,666.70 Completed 2020-02-19 2020-05-13 2020-04-15 2018-12-11 2020-10-12 2019-03-21 al Dry Grinding Machine for A Enterprise Development tions nvelope ssam Agricultural University under APART project. IN-OPIU-AAU-171158-GO-RF Q / Procurement of Gas Chro Component C: Fostering Mar Request for Quota Single Stage - One E matography for IRRI supporte IBRD / 87800 ket-led Production and Resili Post Open - National 37,500.00 35,538.27 Completed 2020-05-06 2020-12-23 2020-05-24 2020-05-27 2020-06-23 2021-01-23 tions nvelope d activity under APART at Ass ence Enhancement am Agricultural University, Jo rhat IN-OPIU-AAU-161173-GO-DIR / Procurement of Power Tiller Component C: Fostering Mar Operated Inclined Plate Briq Under Imple IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct 714.28 0.00 2020-05-04 2020-01-10 2020-05-09 2020-01-10 2020-06-13 2020-07-13 uette Drill Cum Weeder for IR mentation ence Enhancement RI supported activity under A PART for Assam Agricultural University, Jorhat. IN-OPIU-AAU-170713-GO-DIR Component C: Fostering Mar / Procurement of Paddy seed IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct 41,871.42 32,979.07 Completed 2020-05-04 2020-05-05 2020-05-09 2020-05-05 2020-05-18 2020-05-07 2020-06-17 2020-09-29 Ranjit Sub-1 for Kharif 2020 ence Enhancement under APART project for IRRI supported activities. IN-OPIU-AAU-170721-GO-DIR Component C: Fostering Mar / Procurement of Paddy Seed IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct 16,392.85 13,550.58 Completed 2020-05-04 2020-05-05 2020-05-09 2020-05-05 2020-05-18 2020-05-07 2020-06-17 2020-11-10 Bahadur Sub-1 for Kharif 202 ence Enhancement 0 under APART project for IR RI supported activities. IN-OPIU-AAU-170726-GO-DIR Component C: Fostering Mar / Procurement of paddy seed IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct 9,150.00 6,640.95 Completed 2020-05-04 2020-05-05 2020-05-09 2020-05-05 2020-05-18 2020-05-07 2020-06-17 2020-11-10 Swarna Sub-1 for Kharif 2020 ence Enhancement under APART project for IRRI supported activities. IN-OPIU-AAU-170729-GO-DIR Component C: Fostering Mar / Procurement of paddy seed IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct 14,914.28 12,359.34 Completed 2020-05-04 2020-05-05 2020-05-09 2020-05-05 2020-05-18 2020-05-07 2020-06-17 2020-11-10 Bina Dhan-11 for Kharif 2020 ence Enhancement under APART project for IRRI supported activities. IN-OPIU-AAU-170768-GO-DIR / Procurement of paddy seed Component C: Fostering Mar Joha Rice (Kola/Keteki/Boku) f IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct 160.71 1,824.44 Completed 2020-05-04 2020-05-05 2020-05-09 2020-05-05 2020-05-18 2020-05-07 2020-06-17 2020-11-10 or Kharif 2020 under APART ence Enhancement project for IRRI supported act ivities. IN-OPIU-AAU-118787-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Laptop, A IBRD / 87800 ket-led Production and Resili Post Open - National 12,214.28 8,071.85 Completed 2021-02-20 2021-02-10 2021-03-12 2019-08-08 2021-03-17 2019-11-12 tions nvelope AU Jorhat through GeM ence Enhancement IN-OPIU-AAU-212813-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Construction of low cost i IBRD / 87800 ket-led Production and Resili Post Open - National 27,771.42 26,697.61 Completed 2021-03-02 2021-02-18 2021-03-10 2020-11-13 2021-03-11 2020-12-30 tions nvelope nsect proof net house under ence Enhancement APART project IN-OPIU-AAU-220372-GO-RF Component C: Fostering Mar Q / Procurement of Refrigera Request for Quota Single Stage - One E IBRD / 87800 ket-led Production and Resili Post Open - National 10,714.50 10,341.90 Completed 2021-03-05 2021-02-22 2021-03-27 2020-10-23 2021-03-29 2021-01-28 tor Shaker Incubator for Bana tions nvelope ence Enhancement na Tissue Culture Lab. under APART project. IN-OPIU-AAU-220378-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Portable IBRD / 87800 ket-led Production and Resili Post Open - National 38,571.43 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 tions nvelope Rice Mill under APART Project ence Enhancement . IN-OPIU-AAU-220383-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Rice Tran IBRD / 87800 ket-led Production and Resili Post Open - National 68,571.43 60,338.75 Completed 2021-03-05 2021-08-03 2021-04-30 2021-08-04 2021-10-27 2021-11-27 tions nvelope splanter under APART Project ence Enhancement . Page 3 IN-OPIU-AAU-220387-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Mine Com IBRD / 87800 ket-led Production and Resili Post Open - National 17,142.86 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 tions nvelope bine Harvester under APART ence Enhancement project. IN-OPIU-AAU-220392-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Rice Flak IBRD / 87800 ket-led Production and Resili Post Open - National 11,428.57 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 tions nvelope e Machine under APART Proje ence Enhancement ct. IN-OPIU-AAU-220396-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Re-Circul IBRD / 87800 ket-led Production and Resili Post Open - National 10,000.00 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 tions nvelope ating Batch Dryer under APA ence Enhancement RT project. IN-OPIU-AAU-220398-GO-RF Q / Procurement of network Component C: Fostering Mar Request for Quota Single Stage - One E accessories for internet conn IBRD / 87800 ket-led Production and Resili Post Open - National 18,550.03 17,319.37 Completed 2021-03-05 2021-07-20 2021-04-30 2020-12-22 2021-05-20 2021-04-01 tions nvelope ectivity in the OPIU_APART GI ence Enhancement S lab and office room under APART project. IN-OPIU-AAU-231638-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Paddy se IBRD / 87800 ket-led Production and Resili Post Open - National 34,370.27 24,172.33 Completed 2021-06-13 2021-07-16 2021-07-25 2021-05-22 2021-08-24 2021-10-05 tions nvelope ed variety Ranjit Sub 1 an a ence Enhancement mount of 42390 Kg IN-OPIU-AAU-231636-GO-RF Component C: Fostering Mar Q / Procurement of Paddy se Request for Quota Single Stage - One E IBRD / 87800 ket-led Production and Resili Post Open - National 15,008.10 11,175.97 Completed 2021-06-13 2021-07-16 2021-07-25 2021-05-22 2021-08-24 2021-10-05 ed variety Bahadur Sub 1 an tions nvelope ence Enhancement amount of 18510 kg. IN-OPIU-AAU-250472-GO-RF B / Procurement of 21 nos. of Component C: Fostering Mar Mini track-type Combine Har Single Stage - Two E IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 469,286.00 462,590.67 Signed 2021-09-06 2021-12-14 2021-09-11 2022-03-08 2021-09-13 2022-01-29 2021-10-25 2022-02-19 2021-11-05 2022-03-08 2021-12-05 vester for 7 newly establishe nvelope ence Enhancement d training centres and alread y established KVKs stations u nder APART IN-OPIU-AAU-250474-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 2 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 31,428.60 24,582.90 Completed 2021-09-11 2021-11-29 2021-10-29 2021-11-27 2021-11-13 tions nvelope Re-circulating Batch Dryer un ence Enhancement der APART. IN-OPIU-AAU-250477-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 16 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 73,571.40 82,760.65 Completed 2021-09-11 2021-11-29 2021-10-29 2021-11-16 2021-11-13 2022-04-23 tions nvelope Portable Rice Mill under APAR ence Enhancement T IN-OPIU-AAU-250478-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 8 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 21,142.90 21,067.24 Completed 2021-09-11 2021-11-27 2021-10-29 2021-11-16 2021-11-13 2022-03-30 tions nvelope Rice Puffing Machine under A ence Enhancement PART IN-OPIU-AAU-250480-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 2 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 21,428.60 17,917.25 Completed 2021-09-11 2021-11-29 2021-10-29 2021-11-16 2021-11-13 2022-09-01 tions nvelope Rice Flake Machine under AP ence Enhancement ART IN-OPIU-AAU-250483-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 11 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 24,857.10 17,957.25 Completed 2021-09-11 2021-11-29 2021-10-29 2021-11-16 2021-11-13 2022-03-30 tions nvelope Reaper under APART ence Enhancement IN-OPIU-AAU-250485-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 22 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 12,571.40 10,389.33 Completed 2021-09-11 2021-11-24 2021-10-29 2021-11-27 2021-11-13 2022-12-19 tions nvelope Open Drum Thresher under A ence Enhancement PART IN-OPIU-AAU-250487-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 8 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 29,714.30 27,744.25 Completed 2021-09-11 2021-11-26 2021-10-29 2021-11-16 2021-11-13 2022-03-30 tions nvelope Paddy Transplanter under AP ence Enhancement ART IN-OPIU-AAU-250490-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 8 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 13,714.30 7,874.85 Completed 2021-09-11 2021-11-27 2021-10-29 2021-11-16 2021-11-13 2022-04-01 tions nvelope Multi crop Planter under APA ence Enhancement RT IN-OPIU-AAU-250493-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 9 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 23,142.90 23,409.94 Completed 2021-09-11 2021-11-27 2021-10-29 2021-11-16 2021-11-30 2022-01-01 tions nvelope Axial Flow Thresher under AP ence Enhancement ART IN-OPIU-AAU-250494-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 15 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 10,714.30 4,574.36 Completed 2021-09-11 2021-11-29 2021-10-29 2021-11-16 2021-11-13 2022-03-31 tions nvelope Dry Grinding Machine under ence Enhancement APART IN-OPIU-AAU-250495-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 5 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 42,857.10 18,111.50 Completed 2021-09-11 2021-11-29 2021-10-29 2021-11-16 2021-11-13 2022-04-01 tions nvelope Laser Land Leveler ence Enhancement IN-OPIU-AAU-250496-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 3 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 85,714.30 79,963.74 Signed 2021-09-11 2021-11-29 2021-10-29 2021-11-16 2021-11-13 tions nvelope Small Seed Processing Unit u ence Enhancement nder APART IN-OPIU-AAU-256787-GO-RF Q / Procurement of 4 nos. of Component C: Fostering Mar Request for Quota Single Stage - One E Rice Transplanter each for K IBRD / 87800 ket-led Production and Resili Post Open - National 26,780.32 26,806.20 Completed 2021-10-24 2021-11-26 2021-10-29 2021-08-04 2021-11-03 2021-09-16 tions nvelope VK, Lakhimpur and RARS, La ence Enhancement khimpur as directed by SPD, ARIAS Society. IN-OPIU-AAU-266880-GO-RF Q / Procurement of Paddy Se Component C: Fostering Mar Request for Quota Single Stage - One E ed BINA Dhan 11 (12400 kg) IBRD / 87800 ket-led Production and Resili Post Open - National 12,640.00 12,597.09 Completed 2021-12-22 2022-02-12 2022-01-11 2021-12-31 2022-01-31 2022-03-30 tions nvelope and DRR Dhan 44 (3400 kg) f ence Enhancement or BORO season under AWP 2021-22. IN-OPIU-AAU-266886-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Laptop 16 IBRD / 87800 ket-led Production and Resili Post Open - National 10,666.66 9,419.17 Completed 2021-12-22 2021-12-22 2022-01-10 2021-12-04 2022-01-26 2021-12-22 tions nvelope nos. ence Enhancement IN-OPIU-AAU-266888-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Network IBRD / 87800 ket-led Production and Resili Post Open - National 22,666.66 19,397.32 Completed 2021-12-22 2021-12-23 2022-01-02 2021-10-09 2022-01-31 2022-02-11 tions nvelope Attach Storage Drive 2 nos. ence Enhancement IN-OPIU-AAU-267155-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Field Spe IBRD / 87800 ket-led Production and Resili Post Open - National 39,333.33 0.00 Canceled 2021-12-22 2022-01-31 2022-05-31 tions nvelope ctroradiometer 1 no. ence Enhancement Page 4 IN-OPIU-AAU-267162-GO-RF Q / Drone 1 no. includes : i Drone with compatibility to change payload sensor. Component C: Fostering Mar ii Multi-spectral and thermal Request for Quota Single Stage - One E IBRD / 87800 ket-led Production and Resili Post Open - National 30,986.66 0.00 Canceled 2021-12-22 2022-02-16 2022-05-31 sensors. tions nvelope ence Enhancement iii Software for drone data pr ocessing. iv License renewal and maint enance cost. IN-OPIU-AAU-272689-GO-RF Component C: Fostering Mar Q / For supply and installatio Request for Quota Single Stage - One E IBRD / 87800 ket-led Production and Resili Post Open - National 25,361.82 24,749.53 Completed 2022-01-29 2022-01-21 2022-02-23 2021-06-29 2022-02-26 2021-12-10 n of GI PVC cages, Fish Seeds tions nvelope ence Enhancement , Fish Feeds, Medicine etc. in Beels at APART districts. IN-OPIU-AAU-272766-GO-RF Q / Supply of Fish Seeds, Fish Component C: Fostering Mar Request for Quota Single Stage - One E Feeds, Fertilizers, Lime etc. f IBRD / 87800 ket-led Production and Resili Post Open - National 25,361.82 561.85 Signed 2022-01-26 2022-06-07 2022-03-26 2022-04-17 2022-08-23 tions nvelope or Multiple stocking and Multi ence Enhancement ple Harvesting of Fish at diffe rent APART districts. 7(245.1)/APART/2018-19/CIP Component C: Fostering Mar Request for Quota Single Stage - One E /30923-33 / 2 nos. of Potato IBRD / 87800 ket-led Production and Resili Post Open - National 14,592.73 4,710.87 Completed 2022-02-28 2022-03-04 2022-04-25 2022-03-03 2022-05-25 2022-05-21 tions nvelope Grader. ence Enhancement 1$ = INR 75.38 IN-OPIU-AAU-304328-GO-RF Component C: Fostering Mar Q / Procurement of 3 nos. of Request for Quota Single Stage - One E IBRD / 87800 ket-led Production and Resili Post Open - National 11,273.78 0.00 Completed 2022-08-02 2022-11-03 2022-09-17 2022-10-17 2023-01-06 Solar Bubble Dryer tions nvelope ence Enhancement 1 US$ = Rs. 79.83 IN-OPIU-AAU-304486-GO-RF Component C: Fostering Mar Q / 2 nos. of Ticker Board for Request for Quota Single Stage - One E IBRD / 87800 ket-led Production and Resili Post Open - National 10,021.14 0.00 Completed 2022-08-12 2022-10-14 2022-10-03 2022-11-02 AMIU tions nvelope ence Enhancement 1 US$ = Rs. 79.83 IN-OPIU-AAU-312152-GO-RF Q / Procurement of Fish Seed Component C: Fostering Mar s, Fish Feeds, Lime, Fertilizer Request for Quota Single Stage - One E Pending Impl IBRD / 87800 ket-led Production and Resili Post Open - National 17,531.25 0.00 2022-09-10 2022-10-25 2023-04-23 s etc. for Multiple Stocking a tions nvelope ementation ence Enhancement nd Multiple Harvesting of Fis h under APART. 1 US$ = Rs. 79.86 IN-OPIU-AAU-304086-GO-RF Q / Procurement of 18 nos. of Component C: Fostering Mar Request for Quota Single Stage - One E Tablet for data collection to A IBRD / 87800 ket-led Production and Resili Post Open - National 10,042.62 8,894.78 Completed 2022-07-31 2022-09-08 2022-08-19 2022-07-27 2022-09-08 2022-08-31 tions nvelope MIU FDEs. ence Enhancement 1 US$ = Rs. 79.66 IN-OPIU-AAU-330903-GO-DIR Component C: Fostering Mar / Procurement of 3 nos. of El Under Imple IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 16,925.50 0.00 2023-02-08 2023-02-13 ectric Motor operated Briquet mentation ence Enhancement te Making FDP Machine. IN-OPIU-AAU-330904-GO-DIR / Procurement of 10 nos. of D Component C: Fostering Mar irect Seeder for Rice 11 Rows Pending Impl IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 35,513.22 0.00 2022-12-22 2022-12-27 2023-01-09 2023-02-08 FDP ZERO TILL DRILL With U ementation ence Enhancement SG Fertilizer Briquette Deep Placement applicator attach ment 5 Rows FDP Machine. IN-OPIU-AAU-337292-GO-RF Q / Procurement of Workstati Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl on computers for Satellite Da IBRD / 87800 ket-led Production and Resili Post Open - National 18,441.00 0.00 2023-02-01 2023-03-19 2023-09-15 tions nvelope ementation ta Processing under Phase II I ence Enhancement RRI Supported Activities Obj. 1 AWP 2022-23 IN-OPIU-AAU-340395-GO-RF Q / Procurement of Mapping Component C: Fostering Mar Request for Quota Single Stage - One E Under Imple Drone with Multispectral Sen IBRD / 87800 ket-led Production and Resili Post Open - National 43,028.08 0.00 2023-02-15 2023-03-30 2023-04-25 2023-10-22 tions nvelope mentation sor, Thermal Sensors and Sof ence Enhancement tware for Drone image proce ssing IN-OPIU-AAU-340401-GO-RF Component C: Fostering Mar Q / Procurement of Mapping Request for Quota Single Stage - One E Under Imple IBRD / 87800 ket-led Production and Resili Post Open - National 24,420.02 0.00 2023-02-15 2023-05-03 2023-04-25 2023-10-22 Drone with Multispectral Sen tions nvelope mentation ence Enhancement sor and software for Drone i mage processing. IN-OPIU-AAU-340403-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Field Spe IBRD / 87800 ket-led Production and Resili Post Open - National 68,376.06 0.00 Canceled 2023-02-15 2023-03-31 2023-04-25 2023-10-22 tions nvelope ctroradiometer ence Enhancement IN-OPIU-AAU-347315-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl Q / Procurement of 1 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 71,757.58 0.00 2023-03-19 2023-05-03 2023-10-30 tions nvelope ementation Multi Seed Processing unit ence Enhancement IN-OPIU-AAU-347317-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl Q / Procurement of 5 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 73,346.76 0.00 2023-03-19 2023-05-03 2023-10-30 tions nvelope ementation Laser Land Leveler with tract ence Enhancement or IN-OPIU-AAU-347318-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl Q / Procurement of 5 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 15,891.80 0.00 2023-03-19 2023-05-03 2023-10-30 tions nvelope ementation Mechanical Transplanter (Wa ence Enhancement lk-behind type) IN-OPIU-AAU-348012-GO-RF Component C: Fostering Mar Single Stage - Two E Pending Impl B / Procurement of 17 nos. of IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 124,689.50 0.00 2023-03-18 2023-03-23 2023-05-04 2023-07-02 2023-08-06 2023-11-04 nvelope ementation Reaper-Cum-Binder ence Enhancement IN-OPIU-AAU-347321-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl Q / Procurement of 5 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 30,561.15 0.00 2023-03-19 2023-05-03 2023-10-30 tions nvelope ementation Rice Puff Machine. ence Enhancement IN-OPIU-AAU-347323-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl Q / Procurement of 5 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 61,122.30 0.00 2023-03-19 2023-05-03 2023-10-30 tions nvelope ementation Rice Flake machine ence Enhancement IN-OPIU-AAU-347324-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl Q / Procurement of 17 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 41,563.17 0.00 2023-03-19 2023-05-03 2023-10-30 tions nvelope ementation Cocoon ence Enhancement IN-OPIU-AAU-348010-GO-RF Component C: Fostering Mar Single Stage - Two E Pending Impl B / Procurement of 6 nos. of IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 183,366.91 0.00 2023-03-18 2023-03-23 2023-05-04 2023-07-02 2023-08-06 2024-02-02 nvelope ementation LSU or Batch Dryer ence Enhancement Page 5 IN-OPIU-AAU-348009-GO-RF Component C: Fostering Mar Single Stage - Two E Pending Impl B / Procurement of 8 nos. of IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 97,795.69 0.00 2023-03-18 2023-03-23 2023-05-04 2023-07-02 2023-08-06 2023-11-04 nvelope ementation Mechanical Transplanter (4-w ence Enhancement heel type) IN-OPIU-AAU-348008-GO-RF Component C: Fostering Mar Single Stage - Two E Pending Impl B / Procurement of 13 nos. of IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 158,917.99 0.00 2023-03-18 2023-03-23 2023-05-04 2023-07-02 2023-08-06 2023-11-04 nvelope ementation Flatbed Dryer ence Enhancement IN-OPIU-AAU-361443-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Under Imple Q / Procurement of 4 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 9,742.14 0.00 2023-05-25 2023-06-12 2023-06-17 2023-06-27 tions nvelope mentation Chlorophyll Meter ence Enhancement IN-OPIU-AAU-361926-GO-DIR / Direct procurement of foun dation/breeder seed of Ranjit Component C: Fostering Mar Pending Impl Sub-1, Swarna Sub-1, Bahad IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 38,576.70 0.00 2023-05-23 2023-05-28 2023-06-03 2023-07-03 ementation ur Sub-1 and BINA Dhan-11 f ence Enhancement or the production of Paddy th rough the FPC Shankar Azan, Nagaon. IN-OPIU-AAU-361930-GO-DIR / Direct procurement of foun Component C: Fostering Mar dation/breeder seed of Ranjit Pending Impl IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 22,940.85 0.00 2023-05-23 2023-05-28 2023-06-03 2023-07-03 Sub-1, Swarna Sub-1 and Ba ementation ence Enhancement hadur Sub-1 for the productio n of Paddy through the FPC Poohar, Morigaon. IN-OPIU-AAU-361931-GO-DIR / We need to go for direct pro curement of foundation/bree Component C: Fostering Mar der seed of Ranjit Sub-1 and Pending Impl IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 17,407.70 0.00 2023-05-23 2023-05-28 2023-06-03 2023-07-03 Bahadur Sub-1 for the produ ementation ence Enhancement ction of Paddy through the se lected FPC Tetelia, Kamrup w hich has been earmarked in t he AWP 2023-24. IN-OPIU-AAU-364922-GO-DIR / Procurement of 2 nos. of Tr Component C: Fostering Mar ansplanter Mounted 4 Rows Pending Impl IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 14,261.50 0.00 2023-06-22 2023-06-27 2023-08-01 2023-09-30 with FDP Applicator ementation ence Enhancement 1US$ = INR 82.39 IN-OPIU-AAU-367108-GO-RF B / Establishing a Seed Testin Component C: Fostering Mar Single Stage - Two E Pending Impl g Laboratory in the Departm IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 79,500.00 0.00 2023-06-22 2023-06-27 2023-07-27 2023-10-09 2023-11-13 2024-03-27 nvelope ementation ent of Plant Breeding and Ge ence Enhancement netics at AAU, Jorhat-13 IN-OPIU-AAU-361311-GO-RF Q / Procurement of Tensiom Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl eter for10 nos. experiment (8 IBRD / 87800 ket-led Production and Resili Post Open - National 9,746.10 0.00 2023-06-25 2023-07-18 2023-07-28 tions nvelope ementation nos. of Tensiometer per expe ence Enhancement riment i.e; 80 nos. of Tensio meter) IN-OPIU-AAU-367650-GO-RF B / Procurement of feed testi Component C: Fostering Mar ng laboratory equipments at Single Stage - Two E Pending Impl IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 134,293.74 0.00 2023-06-29 2023-07-04 2023-08-15 2023-10-28 2023-12-02 2024-03-31 Department of Animal Nutriti nvelope ementation ence Enhancement on, College of Veterinary Scie nce, AAU, Khanapara, Guwah ati-781022 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-OPIU-AAU-118785-NC-DIR / Procurement of data sets fo Component A: Enabling Agri IBRD / 87800 Post Direct Selection Direct 20,957.14 0.00 Canceled 2019-06-23 2019-06-28 2019-08-02 2019-10-01 r Development of Spatial dat Enterprise Development abase for extrapolation doma ins IN-OPIU-AAU-118786-NC-DIR / Procurement of Acquisition Component A: Enabling Agri IBRD / 87800 Post Direct Selection Direct 15,814.28 0.00 Canceled 2019-06-23 2019-06-28 2019-08-02 2019-10-01 planning for satellite data for Enterprise Development extrapolation domain. IN-OPIU-AAU-161469-NC-RF Q / Printing of brochures, sta Component C: Fostering Mar Request for Quota Single Stage - One E ndees, stand calendar, traini IBRD / 87800 ket-led Production and Resili Post Open - National 28,357.14 25,467.83 Completed 2020-05-09 2020-12-22 2020-07-04 2020-06-12 2020-08-03 2022-03-31 tions nvelope ng manual, booklet and fact ence Enhancement sheets under APART AAU, Jor hat. IN-OPIU-AAU-213008-NC-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / E-tendering for Rice Know IBRD / 87800 ket-led Production and Resili Post Open - National 78,571.42 34,157.89 Completed 2021-02-20 2021-07-26 2021-04-18 2021-07-27 2021-10-15 2022-09-29 tions nvelope ledge Bank video production. ence Enhancement IN-OPIU-AAU-220406-NC-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Printing of Outreach Mate IBRD / 87800 ket-led Production and Resili Post Open - National 70,857.14 30,620.21 Completed 2021-03-05 2021-08-18 2021-04-30 2021-08-25 2021-10-27 2023-05-31 tions nvelope rials under APART Project ence Enhancement IN-OPIU-AAU-267168-NC-RF Q / Development, framework and design of web GIS and re lated decision tools includes: i. Pre-planning and prototype Component C: Fostering Mar Request for Quota Single Stage - One E development IBRD / 87800 ket-led Production and Resili Post Open - National 30,266.66 20,897.27 Completed 2021-12-22 2022-03-14 2022-02-16 2022-03-12 2022-08-15 tions nvelope ii. Technical feasibility assess ence Enhancement ment iii. Web services database an d coding iv. Support for any bug fixing , app crash etc. IN-OPIU-AAU-304481-NC-RF Q / Printing of ATLAS, brochu Component C: Fostering Mar res, booklets, and standees u Request for Quota Single Stage - One E IBRD / 87800 ket-led Production and Resili Post Open - National 30,313.94 0.00 Completed 2022-07-31 2022-10-17 2022-09-16 2022-12-15 nder APART project tions nvelope ence Enhancement 1 US$ = Rs. 79.83 IN-OPIU-AAU-310872-NC-RF Component C: Fostering Mar Request for Quota Single Stage - One E Under Imple Q / Printing of Crop Suitabilit IBRD / 87800 ket-led Production and Resili Post Open - National 10,017.86 0.00 2022-09-10 2022-10-14 2022-11-13 tions nvelope mentation y ATLAS ence Enhancement 1US$ = Rs. 79.86 Page 6 IN-OPIU-AAU-337296-NC-RF Q / Procurement of GIS Softw are for establishment of GIS f Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl acilities at multiple locations IBRD / 87800 ket-led Production and Resili Post Open - National 18,441.00 0.00 2023-02-01 2023-03-19 2023-09-15 tions nvelope ementation as sub-units within GIS lab. a ence Enhancement t AAU colleges under Phase II IRRI Supported activity Objec tive 1 AWP 2022-23 IN-OPIU-AAU-337298-NC-RF Q / Procurement of Image Pr ocessing Software for establi Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl shment of GIS facilities at mu IBRD / 87800 ket-led Production and Resili Post Open - National 31,349.89 0.00 2023-02-01 2023-03-19 2023-09-15 tions nvelope ementation ltiple locations as sub-units w ence Enhancement ithin GIS lab at AAU colleges under Phase II IRRI Supporte d activities AWP 2022-23 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 7 18 MONTHS PROCUREMENT PLAN-IRISE PROJECT Project information: Liberia Improving Results in Secondary Education Project - P164932 Project Implementation Agency: Ministry of Education, Liberia Date of the Procurement Plan: June 2019 Period covered by this Procurement Plan: June 2019 to January 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement and Concessions Act, 2010 of the Republic of Liberia, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right 1 to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable for those contracts identified in the Procurement Plan tables; Works: Not Applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not Applicable. Other Relevant Procurement Information: - (a). Prior Procurement Arrangements: The Procurement Arrangements as indicated in the below table and within the thresholds indicated in the below tables will be used. The thresholds for the Bank’s prior review requirements are also provided in the table below: Table: Thresholds*, Procurement Arrangements, and Prior Review (The table below depicts the Thresholds and Procurement Methods to be used under the REDISSE II project): Thresholds*, Procurement Methods, and Prior Review for Substantial Risk Thresholds for Expenditure Procurement Procurement Contracts Subject to No Category Methods* [eq. Method Prior Review /[eq. US$] USD] All contracts at or above Open Competition USD10,000,000 are subject to International Market international advertising and the C ≥ 5,000,000 Approach and Direct use of the Bank’s SPDs (or other Contracting documents agreed with the 1 Works Bank). Open Competition National Market 200,000 < C < 5,000,000 None Approach 2 Thresholds for Expenditure Procurement Procurement Contracts Subject to No Category Methods* [eq. Method Prior Review /[eq. US$] USD] C ≤ 200,000 RfQ None All contracts at or above Open Competition USD2,000,000 are subject to International Market international advertising and the C ≥ 500,000 Approach and Direct use of the Bank’s SPDs (or other Goods, IT and Contracting documents agreed with the 2 non-consulting Bank). services Open Competition National Market 100,000 < C < 500,000 None Approach C ≤ 100,000 RfQ None All contracts at or above USD500,000 are subject to for international advertising and the C < 100,000 Consulting Services use of the Bank’s SPDs (or other National documents agreed with the shortlist for Bank). 3 selection of All contracts at or above consultant firms for USD500,000 are subject to Engineering and international advertising and the C ≤ 200,000 Construction use of the Bank’s SPDs (or other Supervision documents agreed with the Bank). Selection of All values ≥ 300,000 4 Individual All Approaches consultants Training, Based on approved Workshops, This line activity is not subject 5 All Values Annual Work Plan & Study Tours to procurement Review. Budgets (AWPB) by TTL (Special procurement arrangements like us of: Direct Selection. It is not expected that there will need for prequalification in the procurement arrangements under Liberia Secondary Education Teaching for Results Project) *These thresholds are for the purposes of the initial procurement plan for the first 18 months. The thresholds will be revised periodically based on re-assessment of risks. All contracts not subject to prior review will be post-reviewed. Prequalification. Not expected for the works/goods packages in the procurement plan. Proposed Procedures for CDD Components: Not Applicable Reference to (if any) Project Operational/Procurement Manual: The MoE team will prepare Procurement manuals. The Procurement Plan will also form part of the Project Implementation Manual. Any Other Special Procurement Arrangements: None 3 Procurement Packages/Plan with Procurement Arrangements and Time Schedule: as per the table below: b) PROCUREMENT PLAN Works 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procureme Prequ National Review Expected Expected Comme No. (Description) Cost nt Method/ alifica Prefere by bid Contract nts US$ Arrangeme tion nce Bank opening Signature million nt (yes/n (yes/no) (Prior / date Date o) Post) 1. Refurbishment 5,000.00 Limited Post No Post Oct-1, Oct- 30, of offices and National 2019 2019 facilities for the RFQ PDT 2. Construction of 3 3,300,000. Open, Post No Post Jul-30, Oct-30, new high 00 National, 2020 2020 schools RFB 3. Expansion of 23 4,025,000. Open, Post No Post Jul-30, Oct-30, junior high 00 National, 2020 2020 schools in rural RFB areas 4. Expansion of 2 350,000 CDD Post No Post Jul-30, Oct-30, junior high 2020 2020 schools in rural areas as demonstration schools using community development- driven approach 5. School 6,005,000. Community- Post No Post Oct-2020 Dec-21, This may rehabilitation 00 driven 2020 be and renovation Developme determin nt (CDD) ed after a mid- term review of the project Goods and Non-Consulting Services 1 2 3 4 5 6 7 8 9 Ref. Contract Estimate Procurem Prequali National Review Expected Expected Comme No. (Description) d ent fication Prefere by bid Contract nts Cost Method/ (yes/no) nce Bank opening Signatur US$ Arrangem (yes/no) (Prior / date e Date million ent Post) 1. Procurement of 7,000.00 Limited, Post No Post Oct-15, Nov-5, office furniture National 2019 2019 for the PDT RFQ 4 2. Procurement of 10,000.0 Limited, Post No Post Oct-15, Nov-5, office 0 National 2019 2019 equipment for RFQ the PDT Consultancy Services 1 2 3 4 5 6 7 8 Ref. No. Description of Assignment Estimate Selection Review Expected Expected Comme d Method/ by date of Contract nts Cost Arrangeme Bank proposal Signature US$ nt (Prior / submissio Date Post) n 1. Consulting services for 150,000.0 Limited, Post Nov-15, Jan-15, 2020 developing design standards, 0 National, 2019 drawings, specifications as well CQS as bills of quantity (national school construction strategy) 2. Consulting services for the 750,000.0 Open , Post Oct-16, Dec-16, 2020 construction supervision 0 National 2020 QCBS 3. Consulting services to support 100,000.0 Limited, Post Nov-11, Dec-10, 2019 girls’ education interventions 0 National 2019 to remove barriers to transition INDV and completion (design girls’ scholarship program, define the role of female guidance counsellors and develop training modules and set up community engagement framework and operational plan). 4. Consulting services for 720,000.0 Open, Post Dec-16, Feb-20, 2020 development of the feedback- 0 National, 2019 based training system, in QCBS particular the development and delivery of the training materials and program 5. Consulting services for the 750,000.0 Open, Post Aug- Oct-30,2019 hiring of an Independent 0 National, 1,2019 Verification Agency QCBS 6. Consulting services to review 400,000.0 Open, Post Nov- Jan-20,2020 and revamp the existing pre- 0 National, 20,2019 service teacher training QCBS program at University of Liberia 7. Consulting services to develop 100,000.0 Open, Post Mar-9, May-4, 2020 a teaching workforce planning 0 National, 2020 and management system CQS 8. Consulting services to develop 150,000.0 Open, Post Dec-16, Feb-20, 2020 a textbook management 0 National, 2019 system and build capacity at CQS the Center for Curriculum and Textbook Research to maintain the system 5 9. Consulting services to develop 150,000.0 Open, Post Sept-10, Nov-10, 2020 a textbook application and 0 National, 2020 digital platform for making CQS textbooks available online and building capacity of the MoE to maintain the platform 10. Consulting services to support 1,250,000 Open, Prior Nov-15, Jan-6, 2020 development of textbooks for .00 Internation 2019 five subject areas (Math, al, QCBS English, Physics, Chemistry and Biology) for grades 10, 11 and 12. 11. Consulting services to develop 200,000.0 Open, Post Nov-26, Jan-27, 2020 an ICT strategy for the 0 National, 2019 integration of digital CQS technology in education 12. Consulting services to conduct 500,000.0 Open, Post Sep-16, Nov-18, 2019 a feasibility study of capacity- 0 Internation 2019 building needs of MoE and al, QCBS education institutions involved in the project implementation and developing programs to address the identified capacity gaps. 13. Hiring of an International 180,000.0 Open, Prior Aug-15, Oct-15, 2019 Procurement Specialist 0 International, 2019 INDV 14. Hiring of a National Contract 48,000.00 Limited, Post Apr-15, Jun-30, 2020 Management Specialist National 2020 INDV Training and Workshop (Training & Workshop activities are subject to TTL clearance) Estimat Estimated Expected Comment Ref. Training, workshop and study s ed Cost Duration Training/work No. tours (US$) (Days) shop Date 1. 15,000.0 TBA TBA Project launch workshop 0 3. Training in Selection and 30,000.0 TBA TBA Employment of Consultants and 0 Contract Management GENERAL NOTES 1. Training and capacity building: Training workshops (including training material and support), conference attendance and study tours, will be carried out based on approved annual training and allied activities plan by the TTL. The beneficiaries, after the training, will be requested to submit a brief report indicating what skills have been acquired and how these skills will contribute to enhance their performance and contribute to the attainment of the Project’s development objective. 2. Operational Costs: 6 These are expenditures incurred by the Recipient to finance: (i) the salaries of locally contracted support staff of the Project entities and units involved in Project implementation (excluding civil servants) and state contributions thereon; (ii) per diem and travel expenses of the operational staff performing their responsibilities under the Project; (iii) fuel and vehicle maintenance and insurance; (iv) communication technology (including, without limitation, internet and telephone) and maintenance of equipment; (v) rental expenses and utilities; (vi) building security and maintenance; (vii) translations services, photocopies and publications; (viii) bank commissions; and (ix) utilities and office supplies as defined in the FA. Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official 1Guidelineson Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 7 regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 8 We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 9 PROCUREMENT Liberia : Improving Results in Secondary Education (IRISE) PLAN General Information Country: Liberia 2019-11-06 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164932 GPN Date: 2019-11-11 Project Name: Improving Results in Secondary Education (IRISE) Loan / Credit No: IDA / D5030 Ministry of Education Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned LR-MOE-138143-GO-RFQ / R Capacity building, technical Request for Quota Single Stage - One E 2021-01-0 efurbishment of offices and f IDA / D5030 assistance, project coordinat Post Limited 5,000.00 0.00 Canceled 2020-08-11 2020-09-18 2020-10-06 tions nvelope 4 acilities for the PDT ion, and monitoring and eval uation LR-MOE-138240-CW-CDD / S Improving access and learni Community Drive 2022-05-1 chool rehabilitation and reno IDA / D5030 ng environment at the senio Post Limited 6,005,000.00 0.00 Canceled 2021-01-25 2021-01-30 2021-03-13 2021-04-12 2021-05-17 n Development 7 vation r secondary level LR-MOE-138239-CW-RFB / E Improving access and learni Community Drive Pending Imp 2022-09-0 xpansion of 2 junior high sch IDA / D5030 ng environment at the senio Post Limited 350,000.00 0.00 2021-05-14 2021-05-19 2021-06-30 2021-07-30 2021-09-03 n Development lementation 3 ools in rural areas as demons r secondary level tration schools LR-MOE-138237-CW-RFB / C Improving access and learni Single Stage - One E Under Imple 2022-09-1 onstruction of 3 new high sch IDA / D5030 ng environment at the senio Post Request for Bids Open - National 3,300,000.00 0.00 2021-05-21 2022-04-14 2021-05-26 2022-05-16 2021-07-07 2022-06-28 2021-08-06 2022-08-08 2021-09-10 nvelope mentation 0 ools r secondary level Request for Bids - LR-MOE-138238-CW-RFB / E Improving access and learni Single Stage - One E Small Works SPD Under Imple 2022-09-1 xpansion of 23 junior high sc IDA / D5030 ng environment at the senio Post Request for Bids Open - National 4,025,000.00 0.00 2021-05-21 2022-05-04 2021-05-26 2022-05-04 2021-07-07 2022-06-14 2021-08-06 2022-08-02 2021-09-10 nvelope (1 envelope proce mentation 0 hools r secondary level ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MOE-138792-GO-RFQ / Pr Capacity building, technical Request for Quota Single Stage - One E ocurement of office furniture IDA / D5030 assistance, project coordinat Post Limited 7,000.00 5,970.00 Signed 2019-12-23 2020-01-08 2020-02-17 2020-01-28 2020-08-15 tions nvelope for the PDT ion, and monitoring and eval uation LR-MOE-138793-GO-RFQ / Pr Capacity building, technical Request for Quota Single Stage - One E ocurement of office equipme IDA / D5030 assistance, project coordinat Post Limited 10,000.00 11,730.00 Signed 2019-12-18 2019-12-20 2020-02-12 2020-01-28 2020-08-10 tions nvelope nt for the PDT ion, and monitoring and eval uation LR-MOE-173177-GO-RFQ / Pr Capacity building, technical Request for Quota Single Stage - One E ocurement of 2No. Cross-Cou IDA / D5030 assistance, project coordinat Post Limited 100,000.00 90,600.00 Completed 2020-06-10 2020-06-04 2020-08-05 2020-07-21 2021-02-01 2020-11-28 tions nvelope ntry Vehicles for Monitoring ion, and monitoring and eval uation LR-MOE-180979-GO-RFQ / S upply and Delivery of Medical Contingency Emergency Res Request for Quota Single Stage - One E IDA / D5030 Post Limited 662,000.00 0.00 Canceled 2020-06-29 2020-06-24 2020-08-24 2021-02-20 and Non medical materials fo ponse Component (CERC) tions nvelope r Private Schools 12 graders- CERC LR-MOE-200331-GO-DIR / Fo r the Delivery of Outputs -Su Contingency Emergency Res IDA / D5030 Prior Direct Selection Direct 1,500,000.00 1,212,318.35 Signed 2020-10-22 2020-11-05 2020-10-27 2020-11-09 2020-12-01 2020-11-21 2021-05-30 pply And Delivery Of Health ponse Component (CERC) Kits To 3400 private Schools I n Liberia LR-MOE-223779-GO-RFQ / Pr ocurement of Laptop Comput Capacity building, technical ers, Printers and Other Office assistance, project coordinat Request for Quota Single Stage - One E Equipment to replace damag IDA / D5030 Post Limited 8,000.00 11,002.00 Completed 2021-04-17 2021-05-12 2021-06-12 2021-07-20 2021-12-09 2021-10-26 ion, and monitoring and eval tions nvelope ed equipment and to resourc uation e MOE Procurement and Fina nce Offices to deliver on the I RISE Project LR-MOE-295704-GO-RFB / A daptation and Supply of Exist ing Textbooks and Teacher G Improving quality and releva uides in 5 Subjects (English Open - Internationa Single Stage - Two E IDA / D5030 nce of senior secondary edu Prior Request for Bids 4,608,000.00 0.00 Signed 2022-05-23 2022-06-29 2022-05-28 2022-06-29 2022-07-09 2022-09-21 2022-09-21 2023-02-02 2022-10-26 2023-03-09 2023-04-24 Language, Mathematics, Biol l nvelope cation ogy Chemistry and Physics) a nd creation of Digital Content of Textbooks for Grades 10-1 2 for Public Schools in Liberia LR-MOE-295707-GO-RFB / Su Improving quality and releva pply, Delivery, Installation an Open - Internationa Single Stage - One E IDA / D5030 nce of senior secondary edu Post Request for Bids 2,106,000.00 0.00 Canceled 2022-05-29 2023-05-05 2022-06-03 2022-07-15 2022-08-14 2022-09-18 2023-03-17 d commissioning of Smart Bo l nvelope cation xes in 156 Public Schools in L iberia LR-MOE-309624-GO-DIR / Pr Increasing opportunities for ocurement of 2000 Mobile ph girls to transition to and com ones and 3,000 SIM cards for IDA / D5030 Post Direct Selection Direct - National 113,000.00 113,480.00 Signed 2022-08-18 2022-08-16 2022-08-23 2022-08-18 2022-09-27 2022-09-09 2023-03-26 plete senior secondary educ the Girls Scholarship Progra ation m in Senior Secondary Schoo ls in Liberia LR-MOE-305115-GO-RFB / Pr Increasing opportunities for ocurement of 160 Laptop Co girls to transition to and com Single Stage - One E mputers and 160 Printers for IDA / D5030 Post Request for Bids Open - National 272,000.00 0.00 Signed 2022-08-10 2022-09-21 2022-08-15 2022-09-25 2022-09-26 2022-11-07 2022-10-26 2023-01-10 2022-11-30 2023-05-29 plete senior secondary educ nvelope the IRISE Guidance Counselin ation g Service in Senior Secondar y School in Liberia. LR-MOE-357726-GO-RFQ / Pr Capacity building, technical Request for Quota Single Stage - One E Under Imple ocurement of 2No Cross-Cou IDA / D5030 assistance, project coordinat Post Limited 100,000.00 0.00 2023-04-30 2023-05-17 2023-06-25 2023-12-22 tions nvelope mentation ntry Vehicles for Monitoring ion, and monitoring and eval uation LR-MOE-358862-GO-DIR / Su pply and delivery of addition Increasing opportunities for al 165No. mobile phones and girls to transition to and com Under Imple IDA / D5030 Post Direct Selection Direct - National 12,000.00 0.00 2023-05-26 2023-05-17 2023-05-31 2023-07-05 2024-01-01 165No. registered sim cards, plete senior secondary educ mentation and other auxiliary services f ation or the Girls Scholarship Progr am Page 1 LR-MOE-363159-GO-RFQ / Pr Capacity building, technical ocurement of 12No Laptop C assistance, project coordinat Request for Quota Single Stage - One E Under Imple omputers, 3No Desktop Com IDA / D5030 Post Open - National 35,000.00 0.00 2023-06-04 2023-07-30 2024-01-26 ion, and monitoring and eval tions nvelope mentation puters, and 1No Smart TV (D uation ashboard) for EMIS Staff Trai ning LR-MOE-369481-GO-RFB / Su pply, Delivery, Installation, a nd Commissioning of Digital Improving quality and releva Learning Platform (Hardware Open - Internationa Single Stage - One E Under Imple IDA / D5030 nce of senior secondary edu Prior Request for Bids 3,883,300.68 0.00 2023-07-05 2023-06-28 2023-07-10 2023-06-29 2023-08-21 2023-09-20 2023-10-25 2024-04-22 & Software Solution), and Sol l nvelope mentation cation ar Power in 156 Public School s in Liberia (Grades 10-12) o n Service-Oriented Architectu re (SOA) and Open Standard Architecture NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MOE-181088-NC-RFQ / Pr Contingency Emergency Res Request for Quota Single Stage - One E inting of IEC, Posters and Pro IDA / D5030 Post Limited 30,000.00 0.00 Canceled 2020-07-29 2020-06-24 2020-09-23 2021-03-22 ponse Component (CERC) tions nvelope tocols for private schools 12 graders CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MOE-138734-CS-CQS / Co Improving access and learni nsulting services for developi Consultant Qualifi IDA / D5030 ng environment at the senio Post Open - National 150,000.00 287,304.35 Signed 2019-12-30 2019-12-06 2020-01-20 2020-02-12 2020-03-04 2020-04-13 2020-04-03 2020-07-13 2020-05-08 2020-08-11 2021-05-08 ng design standards, drawing cation Selection r secondary level s, specifications as well as bil ls of quantity LR-MOE-138249-CS-CQS / Co Improving quality and releva nsulting services to develop Consultant Qualifi IDA / D5030 nce of senior secondary edu Post Open - National 200,000.00 115,781.05 Signed 2020-02-02 2020-06-05 2020-02-23 2020-06-27 2020-04-07 2020-09-27 2020-05-07 2021-02-01 2020-06-11 2021-02-26 2021-06-11 an ICT strategy for the integr cation Selection cation ation of digital technology in education LR-MOE-138737-CS-QCBS / Improving access and learni Quality And Cost- Hiring of TA for construction IDA / D5030 ng environment at the senio Post Open - National 750,000.00 0.00 Canceled 2019-12-30 2020-01-20 2020-03-04 2020-04-01 2020-05-01 2020-06-05 2020-07-10 2021-07-10 Based Selection supervision r secondary level LR-MOE-138790-CS-QCBS / Capacity building, technical Quality And Cost- Hire Independent Verification IDA / D5030 assistance, project coordinat Post Open - National 750,000.00 0.00 Canceled 2019-12-20 2019-11-14 2020-01-10 2019-11-20 2020-02-23 2020-01-02 2020-03-22 2020-04-21 2020-05-26 2020-06-30 2021-06-30 Based Selection Agency ion, and monitoring and eval uation LR-MOE-138244-CS-QCBS / Consulting services to review Improving quality and releva Quality And Cost- Open - Internationa and revamp the existing pre- IDA / D5030 nce of senior secondary edu Prior 400,000.00 258,549.41 Signed 2020-08-30 2020-09-10 2020-09-20 2020-10-07 2020-11-03 2021-03-02 2020-12-01 2021-03-24 2020-12-31 2021-06-17 2021-02-04 2021-09-14 2021-03-11 2021-10-08 2022-03-11 Based Selection l service teacher training prog cation ram at University of Liberia LR-MOE-173181-CS-CQS / Te Increasing opportunities for chnical Assistance for Suppor girls to transition to and com Consultant Qualifi IDA / D5030 Post 150,000.00 0.00 Canceled 2020-10-15 2020-11-05 2020-12-19 2021-01-18 2021-02-22 2021-08-21 ting Safer Learning Environm plete senior secondary educ cation Selection ent - Female Guidance & Cou ation nseling Program LR-MOE-138728-CS-CQS / Hi Improving access and learni Consultant Qualifi re Technical Assistant (TA)-Ar IDA / D5030 ng environment at the senio Post Open - National 30,000.00 0.00 Canceled 2020-08-16 2020-09-06 2020-10-20 2020-11-19 2020-12-24 2021-12-24 cation Selection chetecture Firm r secondary level LR-MOE-173173-CS-CQS / Hi Improving quality and releva Consultant Qualifi re Technical Assistant for Saf IDA / D5030 nce of senior secondary edu Post Open - National 150,000.00 0.00 Canceled 2020-08-25 2020-09-15 2020-10-29 2020-11-28 2021-01-02 2021-07-01 cation Selection eguards under School Constr cation uction LR-MOE-173175-CS-CQS / Co Improving access and learni nsulting Services for Integrati Consultant Qualifi Open - Internationa IDA / D5030 ng environment at the senio Post 150,000.00 0.00 Canceled 2020-06-30 2020-06-29 2020-07-21 2020-07-07 2020-09-03 2020-10-03 2020-11-07 2021-05-06 ng digital technology to teac cation Selection l r secondary level hing and learning at the Univ ersity of Liberia LR-MOE-138245-CS-CQS / Co Improving quality and releva nsulting services to develop Consultant Qualifi Under Implement IDA / D5030 nce of senior secondary edu Post Open - National 100,000.00 0.00 2020-10-30 2020-12-17 2020-11-20 2021-01-25 2021-01-03 2021-04-05 2021-02-02 2021-03-09 2022-03-09 a teaching workforce plannin cation Selection ation cation g and management strategy LR-MOE-159316-CS-QCBS / Improving quality and releva Hire a firm to develop a conti Quality And Cost- Open - Internationa Under Implement IDA / D5030 nce of senior secondary edu Prior 720,000.00 0.00 2020-11-15 2020-12-07 2020-12-06 2021-01-25 2021-01-19 2021-04-14 2021-02-16 2021-06-01 2021-03-18 2021-04-22 2021-05-27 2022-05-27 nuous professional developm Based Selection l ation cation ent feedback-based training program LR-MOE-173192-CS-QCBS / P Capacity building, technical Quality And Cost- Open - Internationa rocurement Services for Inde IDA / D5030 assistance, project coordinat Post 750,000.00 0.00 Canceled 2020-05-20 2020-06-03 2020-06-10 2020-06-18 2020-07-24 2020-08-21 2020-09-20 2020-10-25 2020-11-29 2021-11-29 Based Selection l pendent Verification Agency ion, and monitoring and eval uation Improving access and learni LR-MOE-190690-CS-CDS / Ex Least Cost Selecti IDA / D5030 ng environment at the senio Post Open - National 30,000.00 0.00 Canceled 2020-09-15 2020-09-29 2020-10-06 2020-11-19 2020-12-17 2021-01-16 2021-02-20 2021-03-27 2021-09-23 ternal Audit Services on r secondary level LR-MOE-159314-CS-QCBS / Improving access and learni Quality And Cost- Open - Internationa Hiring of TA for construction IDA / D5030 ng environment at the senio Prior 720,000.00 639,160.00 Signed 2020-12-08 2021-03-24 2020-12-29 2021-03-29 2021-02-11 2021-09-28 2021-03-11 2021-11-12 2021-04-10 2021-12-17 2021-05-15 2022-03-11 2021-06-19 2022-04-08 2022-06-19 Based Selection l supervision r secondary level LR-MOE-208225-CS-CQS / Pr Improving quality and releva ocurement of ICT Services to Consultant Qualifi Open - Internationa IDA / D5030 nce of senior secondary edu Post 150,000.00 0.00 Canceled 2020-12-11 2021-05-14 2021-01-01 2021-08-02 2021-02-14 2021-03-16 2021-04-20 2021-10-17 develop Textbooks applicatio cation Selection l cation n and digital platform LR-MOE-190733-CS-CQS / Co Improving access and learni nsulting Services for integrati Consultant Qualifi IDA / D5030 ng environment at the senio Post Open - National 150,000.00 284,216.00 Signed 2020-09-30 2021-03-17 2020-10-21 2021-03-23 2020-12-04 2021-05-13 2021-01-03 2021-08-18 2021-02-07 2021-09-28 2021-08-06 ng digital technology to teac cation Selection r secondary level hing and learning at the Univ ersity of Liberia Page 2 LR-MOE-208224-CS-CQS / Co nsulting services to conduct a feasibility study of capacity Capacity building, technical -building needs of MoE and e assistance, project coordinat Consultant Qualifi Open - Internationa IDA / D5030 Post 100,000.00 111,975.00 Signed 2020-12-15 2021-01-03 2021-01-05 2021-01-25 2021-02-18 2021-04-05 2021-03-20 2021-06-29 2021-04-24 2021-07-23 2021-10-21 ducation institutions involved ion, and monitoring and eval cation Selection l in the project implementatio uation n and developing correspond ing programs to address the i dentified capacity gap. LR-MOE-173188-CS-CQS / Te Increasing opportunities for chnical Assistance for Promot girls to transition to and com Consultant Qualifi IDA / D5030 Post Open - National 50,000.00 0.00 Canceled 2020-05-15 2020-06-27 2020-06-05 2020-07-21 2020-07-19 2020-08-18 2020-09-22 2021-03-21 ing Community Engagement plete senior secondary educ cation Selection to Empower Girls, School & C ation ommunity LR-MOE-138248-CS-QCBS / Consulting services to suppor Improving quality and releva t identification and adaptatio Quality And Cost- Open - Internationa IDA / D5030 nce of senior secondary edu Prior 750,000.00 0.00 Canceled 2020-12-11 2021-01-01 2021-02-14 2021-03-14 2021-04-13 2021-05-18 2021-06-22 2022-06-22 n of textbooks for five subjec Based Selection l cation t areas Math, English, Physic s, Chemistry and Biology) for grades 10, 11 and 12. LR-MOE-138246-CS-CQS / Co nsulting services to review a Improving quality and releva Consultant Qualifi nd revise MoE’s existing text IDA / D5030 nce of senior secondary edu Post Open - National 150,000.00 0.00 Canceled 2020-11-30 2021-05-08 2020-12-21 2021-02-03 2020-12-16 2021-03-05 2021-04-09 2022-04-09 cation Selection book guidelines and build ca cation pacity at the Center for Curri culum and Textbook Researc h LR-MOE-236513-CS-CQS / Co Improving quality and releva nsulting Services to Review a Consultant Qualifi Open - Internationa IDA / D5030 nce of senior secondary edu Post 150,000.00 0.00 Canceled 2021-05-30 2021-06-10 2021-06-20 2021-06-15 2021-08-03 2021-09-02 2021-10-07 2022-04-05 nd Revise Ministry of Educati cation Selection l cation on’s Existing Textbook Mana gement Guidelines LR-MOE-255042-CS-QCBS / Improving quality and releva Consultancy services for Dev Quality And Cost- Open - Internationa IDA / D5030 nce of senior secondary edu Post 1,350,000.00 0.00 Under Review 2021-10-27 2022-02-10 2021-11-17 2021-12-31 2022-01-28 2022-02-27 2022-04-03 2022-05-08 2023-05-08 elopment of Textbooks for Gr Based Selection l cation ades 10 – 12 in 5 subjects LR-MOE-363156-CS-CQS / Te chnical Assistance for Providi Capacity building, technical ng Training for Education Ma assistance, project coordinat Consultant Qualifi Under Implement IDA / D5030 Post Open - National 63,000.00 0.00 2023-05-30 2023-06-20 2023-06-20 2023-06-27 2023-08-03 2023-09-02 2023-10-07 2024-04-04 nagement Information Syste ion, and monitoring and eval cation Selection ation m (EMIS) Staffs in Statics, th uation e Use of Spreadsheets, and P ython/R for Data Analyses INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MOE-138791-CS-INDV / H Capacity building, technical Individual Consult ire International Procurement IDA / D5030 assistance, project coordinat Prior Open 180,000.00 376,710.00 Signed 2019-12-10 2019-12-17 2020-01-28 2020-03-27 2020-02-18 2020-04-14 2020-03-24 2020-05-05 2021-03-24 ant Selection Specialist ion, and monitoring and eval uation LR-MOE-138778-CS-INDV / H Capacity building, technical Individual Consult ire Deputy Project Coordinato IDA / D5030 assistance, project coordinat Post Open 147,000.00 171,875.00 Signed 2020-02-10 2020-02-10 2020-03-30 2020-05-27 2020-04-20 2020-06-01 2020-05-25 2020-06-22 2021-05-25 ant Selection r ion, and monitoring and eval uation Capacity building, technical LR-MOE-138789-CS-INDV / H Individual Consult IDA / D5030 assistance, project coordinat Post Open 52,500.00 40,250.00 Signed 2020-02-10 2020-02-12 2020-03-30 2020-09-28 2020-04-20 2020-11-08 2020-05-25 2020-12-23 2020-11-21 ire Administrative Assistant ant Selection ion, and monitoring and eval uation LR-MOE-138767-CS-INDV / C Increasing opportunities for Individual Consult onsulting services to support IDA / D5030 girls to transition to and com Post Open 50,000.00 42,515.00 Signed 2020-08-20 2020-06-27 2020-10-08 2020-11-20 2020-10-29 2021-01-27 2020-12-03 2021-02-18 2021-06-01 ant Selection girls’ Scholarship Program plete senior secondary educ ation LR-MOE-181599-CS-INDV / T Improving quality and releva echnical Assistant for support Individual Consult IDA / D5030 nce of senior secondary edu Post Open 50,000.00 32,738.75 Signed 2020-07-15 2020-06-27 2020-09-02 2020-12-30 2020-09-23 2021-01-27 2020-10-28 2021-02-18 2021-04-26 ing Safer Learning Environm ant Selection cation ent-Female guidance & Coun selling program Capacity building, technical LR-MOE-202576-CS-INDV / R Individual Consult IDA / D5030 assistance, project coordinat Post Limited 144,000.00 53,760.00 Signed 2020-12-15 2020-12-20 2020-12-20 2021-02-28 2021-01-10 2021-03-17 2021-02-14 2021-04-01 2023-12-27 ecruitment of M&E Specialist ant Selection ion, and monitoring and eval uation LR-MOE-198064-CS-CDS / Pr Capacity building, technical ocurement Services for Indep IDA / D5030 assistance, project coordinat Prior Direct Selection Direct 150,000.00 142,684.20 Signed 2020-11-27 2021-02-18 2020-12-07 2021-03-03 2021-02-10 2021-05-11 2021-08-09 endent Verification Agency(I ion, and monitoring and eval VA) uation LR-MOE-179028-CS-INDV / C Capacity building, technical Individual Consult onsultancy Services for Envir IDA / D5030 assistance, project coordinat Post Open 96,000.00 97,920.00 Signed 2020-12-11 2021-01-27 2021-01-29 2021-05-11 2021-02-19 2021-05-20 2021-03-26 2021-06-09 2021-09-22 ant Selection onmental & Social Safeguard ion, and monitoring and eval s Specialist uation LR-MOE-138251-CS-INDV / H Improving access and learni Individual Consult iring of a National Contract M IDA / D5030 ng environment at the senio Post Open 48,000.00 0.00 Canceled 2021-04-27 2021-06-08 2021-06-15 2021-09-13 2021-07-06 2021-08-10 2022-02-06 ant Selection anagement Specialist r secondary level LR-MOE-234067-CS-INDV / T Increasing opportunities for echnical Assistance for Prom girls to transition to and com Individual Consult IDA / D5030 Post Open 50,000.00 0.00 Under Review 2021-05-21 2021-10-06 2021-07-09 2021-07-30 2021-09-03 2022-03-02 oting Community Engageme plete senior secondary educ ant Selection nt to Empower Girls, Schools ation and Communities. LR-MOE-234613-CS-INDV / H Capacity building, technical Individual Consult ire Project Controls Specialist IDA / D5030 assistance, project coordinat Post Open 60,000.00 0.00 Canceled 2021-05-20 2021-06-05 2021-07-08 2021-07-22 2021-07-29 2021-09-02 2022-03-01 ant Selection . ion, and monitoring and eval uation LR-MOE-234626-CS-INDV / H Capacity building, technical ire Technical Support Speciali assistance, project coordinat Individual Consult Under Implement IDA / D5030 Post Open 60,000.00 0.00 2021-05-21 2021-07-08 2021-07-09 2021-07-30 2021-09-03 2022-03-02 st to assist fast track implem ion, and monitoring and eval ant Selection ation entation of Sub-component 3 uation .1B Capacity building, technical LR-MOE-205342-CS-CDS / Ex IDA / D5030 assistance, project coordinat Prior Direct Selection Direct 30,000.00 0.00 Canceled 2020-11-27 2021-01-05 2020-12-07 2021-01-06 2021-02-10 2021-08-09 ternal Audit Services ion, and monitoring and eval uation LR-MOE-241169-CS-INDV / H Capacity building, technical ire National Procurement Spe assistance, project coordinat cialist to provide procuremen IDA / D5030 Post Direct Selection Direct 66,000.00 56,712.00 Terminated 2021-07-06 2021-07-07 2021-07-16 2021-07-09 2021-09-19 2021-08-21 2022-03-18 ion, and monitoring and eval t support to the World Bank E uation ducation Portfolio Projects for 2 years. Page 3 LR-MOE-225961-CS-CDS / Ex Capacity building, technical ternal Financial Audit of the I assistance, project coordinat IDA / D5030 Post Direct Selection Direct 113,000.00 0.00 Canceled 2021-04-12 2021-05-18 2021-04-22 2021-06-09 2021-06-26 2021-12-23 RISE Project for the period Jul ion, and monitoring and eval y 1, 2020 - November 30, 20 uation 23 LR-MOE-234630-CS-CDS / Co nsulting services to support i Improving quality and releva dentification and adaptation IDA / D5030 nce of senior secondary edu Post Direct Selection Direct 1,200,000.00 0.00 Canceled 2021-06-09 2021-06-11 2021-06-19 2021-07-05 2021-08-23 2022-02-19 of textbooks for five subject cation areas Math, English, Physics, Chemistry and Biology) for gr ades 10, 11 and 12. LR-MOE-255041-CS-INDV / T Improving quality and releva echnical Assistance to review Individual Consult IDA / D5030 nce of senior secondary edu Post Limited 100,000.00 161,764.71 Signed 2021-10-22 2021-12-17 2021-10-27 2022-04-11 2021-11-17 2022-04-11 2021-12-22 2022-04-29 2022-06-20 and Revise Ministry of Educat ant Selection cation ion’s Existing Textbook Mana gement Guidelines Capacity building, technical LR-MOE-274636-CS-INDV / P Individual Consult IDA / D5030 assistance, project coordinat Post Limited 60,000.00 45,600.00 Signed 2022-02-21 2022-03-18 2022-02-26 2022-05-07 2022-03-19 2022-05-20 2022-04-23 2022-06-09 2022-10-20 roject Controls Specialist ant Selection ion, and monitoring and eval uation LR-MOE-274651-CS-INDV / S Capacity building, technical Individual Consult chool Construction Program IDA / D5030 assistance, project coordinat Post Open 60,000.00 39,456.00 Signed 2022-02-25 2022-04-12 2022-04-15 2022-06-13 2022-05-06 2022-07-27 2022-06-10 2022-07-28 2022-12-07 ant Selection Manager ion, and monitoring and eval uation LR-MOE-274664-CS-INDV / T Improving quality and releva Individual Consult A for Teaching Workforce Ma IDA / D5030 nce of senior secondary edu Post Limited 50,000.00 50,000.00 Signed 2022-02-23 2022-02-20 2022-02-28 2022-05-10 2022-03-21 2022-05-25 2022-04-25 2022-06-18 2022-10-22 ant Selection nagement Strategy cation LR-MOE-295706-CS-INDV / H ire a National Procurement S Capacity building, technical pecialist who will work with t assistance, project coordinat Individual Consult IDA / D5030 Post Open 36,800.00 28,200.00 Signed 2022-05-25 2022-06-05 2022-07-13 2022-08-12 2022-08-03 2022-08-22 2022-09-07 2022-09-19 2023-03-06 he International Procurement ion, and monitoring and eval ant Selection Specialist to provide procure uation ment support to the IRISE Pro ject implementation. LR-MOE-295709-CS-INDV / H ire an IT Expert in Education Improving quality and releva Individual Consult Under Implement to support the implementatio IDA / D5030 nce of senior secondary edu Post Open 50,000.00 0.00 2022-06-15 2022-11-04 2022-08-03 2023-02-09 2022-08-24 2023-03-02 2022-09-28 2023-03-27 ant Selection ation n of Subcomponent 3.1A and cation 3.3 of the IRISE Project LR-MOE-336810-CS-CDS / Int Capacity building, technical Direct - Internation Under Implement ernational Procurement Spec IDA / D5030 assistance, project coordinat Post Direct Selection 20,000.00 0.00 2023-01-31 2023-01-29 2023-02-10 2023-04-16 2023-10-13 al ation ialist ion, and monitoring and eval uation LR-MOE-338298-CS-CDS / Re vamping of Bachelor Degree Improving quality and releva Direct - Internation Curricula in Secondary Educa IDA / D5030 nce of senior secondary edu Post Direct Selection 200,000.00 0.00 Signed 2023-01-31 2023-05-17 2023-02-10 2023-06-01 2023-04-16 2023-10-13 al tion University of Liberia (UL) cation and Tubman University (TU) Page 4 Republic of Malawi Ministry of Education, Science and Technology Private Bag 328 Lilongwe 3 PROCUREMENT PLAN For PROJECT PREPARATORY ADVANCE (PPA) Name of Project: Skills for A Vibrant Economy (SAVE) Loan No./Credit No./Grant No.: P172627 Financiers: World Bank Implementing Agency: Ministry of Education, Science & Technology Beneficiary Institutions: Ministry of Education, Science & Technology Ministry of Labour Ministry of Youth TEVETA NCHE Ministry of Gender Selected Public Universities SAVE PROJECT PPA PROCUREMENT PLAN I. General 1.Project information Country: Malawi Project Name: Skills for A Vibrant Economy (SAVE) Project ID: P172627 2.Project Implementation Agency: Ministry of Education Science and Technology 3.Date of the Procurement Plan: June 22, 2020 4.Period covered by this Procurement Plan: June 2020 to November 2021 II. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. III. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. IV. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in The Public Procurement and Disposal of Assets Act, 2017 and its subsidiary instruments namely: The Public Procurement Regulations, 2004, Desk Instructions (2005), Standard bidding Documents and Circulars for the Public Procurement and Disposal of Assets (PPDA) Authority such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations under the following conditions: o Provision of “set-asides” contracts for small enterprises shall not be applied. o Criteria such as environmental aspect, extent of local content, technology transfer, and managerial, scientific & operational skills development shall not be used in the evaluation of bids unless specifically agreed by the Bank on case to case basis. o Procurement Documents include provisions, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. V. Prequalification: Not expected for works/goods packages in the procurement plan. VI. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable VII. Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. VIII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable for those contracts identified in the Procurement Plan tables; Works: Not Applicable for those contracts identified in the Procurement Plan tables. IX. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not Applicable. X. Proposed Procedures for CDD Components: Not Applicable XI. Other Relevant Procurement Information: None XII. Reference to (if any) Project Operational/Procurement Manual: The Ministry of Education Science and Technology (MoEST) team will prepare Procurement manual. The Procurement Plan will also form part of the Project Implementation Manual. XIII. Procurement Approach and Prior Review Thresholds: The Procurement Arrangements as indicated in the below table will be used. The thresholds for the Bank’s prior review requirements are also provided in the table: Prior-review Thresholds for Procurement Methods Thresholds Procurem Substanti Works Goods, IT & Non-Consulting Shortlist of National ent al Services Consultants Type Risk ($`000) Works 10,000 Open Request Request Engineerin Internatio for for Open Open Open Consultin g& nal or Quotatio Quotatio National internatio National g Constructio n or n or or NCB nal or ICB or NCB Services n ICB National National ($'000) ($'000) ($'000) ($'000) Supervision ($'000 Shopping Shopping ($'000) ($'000) ($'000) Goods, IT 2,000 & Non- Consulting ≧ < ≦ ≧ < ≦ < ≦ Services Consultan 1,000 ts (Firms) 7,000 7,000 200 1,000 1,000 100 200 300 Individual 300 Consultan ts *These prior review thresholds are for the purposes of the initial procurement plan for the first 18 months. The thresholds will be revised periodically based on re-assessment of risks. All contracts not subject to prior review will be post-reviewed. Procurement Packages/Plan with Procurement Arrangements and Time Schedule: as per the table below: b) PROCUREMENT PLAN A. Works There are no envisaged works under the PPA. 1 2 3 4 5 6 7 8 9 10 Ref. Contract Estimat Market Selecti Prequ Domesti Revie Expect Expecte No. Description ed Approa on alifica c w ed bid d Cost ch Method tion Prefere by openin Contrac US$ (yes/n nce Bank g date t o) (yes/no) (Prior Signatu / Post) re Date 1. N/A B. Goods and Non-Consulting Services 1 2 3 4 5 6 7 8 9 10 Ref. Contract Estimat Market Selecti Prequ Domesti Revie Expect Expecte No. Description ed Approa on alifica c w ed bid d Cost ch Method tion Prefere by openin Contrac US$ (yes/n nce Bank g date t o) (yes/no) (Prior Signatu / Post) re Date 1. Procurement of 1 motor 75,000.0 Limited RFQ No No Post 21-Jul- 21-Aug- vehicle (4 x 4 Twin Cab 0 20 20 Vehicles) for the PIU 2. Procurement of various 85,500.0 Limited RFQ No No Post 21-Jul- 21-Aug- ICT Items: Computer 0 20 20 laptops, Computer Desktops, Photocopier, printers, cameras, Flash discs, Anti-virus, MS package, Extension cables, Extension cables 3. Procurement of 187,000. Open RFB No No Post 1-Aug- 1-Oct-20 Teleconferencing 00 National 20 equipment and licences under COVID- 19 support 4. Procurement of 14,500.0 Limited RFQ No No Post 1-Aug- 31-Aug- Internet modems 0 20 20 devices under COVID- 19 support 5. Procurement of Hand 7,000.00 Limited RFQ No No Post 1-Aug- 31-Aug- sanitizers, face 20 20 masks/shields and gloves under COVID-19 support C. Consultancy Services 1 2 3 4 5 6 7 8 9 10 Ref. Contract Estimat Market Selecti Evalua Shortli Review Review Expecte No. Description ed Approa on tion sting by by Bank d bid Cost ch Method Option (yes/n Bank (Prior / opening US$ o) (Prior / Post) date Post) 1. Consultancy service to 46,000. Open INDV No No Post 1-Aug-20 7-Sep-20 develop Project 00 Implementation Manual 2. Consultancy service to 86,000. Open CQS Rated No Post 1-Aug-20 7-Sep-20 carry out Environmental 00 National Social Safeguard studies-ESMF, SEP, ESMCP, P4R (Firm) 3. Hiring of Project 64,000. Open INDV No No Post 1-Aug-20 7-Sep-20 Manager 00 4. Hiring of Financial 48,000. Open INDV No No Post 1-Aug-20 7-Sep-20 Management Specialist 00 5. Hiring of Procurement 48,000. Open INDV No No Post 1-Aug-20 7-Sep-20 Specialist 00 6. Hiring of M & E Specialist 48,000. Open INDV No Post 1-Aug-20 7-Sep-20 00 7. Hiring of 48,000. Open INDV No Post 1-Aug-20 7-Sep-20 Communications 00 Specialist 8. Hiring of Social 48,000. Open INDV No Post 1-Oct-20 15-Nov- Safeguards Specialist 00 20 9. Hiring of Environmental 48,000. Open INDV No Post 31-Jan- 15-Mar- Specialist 00 21 21 10. Consultancy Service to 92,000. Open CQS Rated No Post 28-Feb- 15-Apr- conduct a Skills Needs 00 National 21 21 Assessment (Firm) 11. Consultancy to 60,000. Open CQS Rated No Post 1-Oct-20 15-Nov- conceptualize a holistic, 00 National 20 integrated ICT-based structure that details elements related to M&E (including EMIS), labor market information and integration platform, communications channels, and mobile- based activities (Firm) 12. Consultant on Dual 53,000. Open CQS Rated No Post 28-Feb- 15-Apr- Learning -Engage, 00 National 21 21 Inception reports, sensitization meetings and advertisements, Engage Partner organizations to participate in the programme, Engage and Train Master Trainers, Build capacity of the key staff in the project, Benchmark Dual Learning, Pilot Dual learning with STC, LTC, MZTC (Firm) 13. Consultancy Service to 75,000. Open CQS Rated No Post 21-Oct- 28-Nov- conduct assessment of 00 National 20 20 ODeL requirements (infrastructure for Higher Education Institutions (HEI) and Technical and Vocational Education) in TEVET institutions (Firm) 14. Consultancy Services on 33,000. Open INDV No Post 1-Aug-20 22-Sep- proposal development 00 20 for tertiary institutions such as TEVET Providers, Nalikule and DCE 15. RFQ – Request for Quotations; CQS - Consultant’s Qualification-based Selection; QCBS – Quality and Cost-based Selection and; INDV - Individual Consultant Selection. Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. Title of the person signing the Letter: PROCUREMENT Malawi : Skills for A Vibrant Economy Project PLAN General Information Country: Malawi 2020-10-23 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172627 GPN Date: 2021-09-24 Project Name: Skills for A Vibrant Economy Project Loan / Credit No: IDA / V3480, IDA / 68910 Ministry of Education Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MW-MOE-315604-CW-RFQ / Supporting Increase in Acces Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-11-0 Rehabilitation of Automobile IDA / 68910 s to TEVET Skills Developme Post Limited tions (Non Bank-S 50,236.00 0.00 2023-08-06 2023-09-03 tions nvelope lementation 2 workshop – Mzuzu Technical nt PD) College MW-MOE-315274-CW-RFB / Tender for various constructi Request for Bids - on works in all 7 National Tec Supporting Increase in Acces Single Stage - One E Works (without pr Pending Imp 2024-12-2 hnical Colleges packaged in IDA / 68910 s to TEVET Skills Developme Post Request for Bids Open - National 4,416,685.00 0.00 2023-07-07 2023-07-17 2023-08-16 2023-09-30 2023-11-04 nvelope equalification) SP lementation 8 3 Lots: Lot 1: Mzuzu and Livi nt D ngstonia TCs; Lot 2: Lilongwe , Namitete and Salima TCs a nd Lot 3: Soche and Nasawa TCs GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-MOE-224891-GO-RFQ / Tertiary Education System S Request for Quota Single Stage - One E Procurement of 1 motor vehi IDA / V3480 trengthening, Project Manag Post Limited 75,000.00 59,224.75 Signed 2021-03-28 2021-03-29 2021-05-09 2021-04-24 2021-06-23 tions nvelope cle (4 x 4 Twin Cab Vehicles) ement, M&E, and Communic for the PIU ations MW-MOE-224893-GO-RFQ / Tertiary Education System S Request for Quota Single Stage - One E Procurement of Internet mod IDA / V3480 trengthening, Project Manag Post Limited 8,000.00 7,446.09 Signed 2021-03-31 2021-04-19 2021-05-26 2021-06-05 2021-06-02 tions nvelope ems devices under COVID-19 ement, M&E, and Communic support ations MW-MOE-224897-GO-RFQ / Tertiary Education System S Procurement of COVID-19 su trengthening, Project Manag Request for Quota Single Stage - One E IDA / V3480 Post Limited 75,000.00 75,101.16 Completed 2021-03-31 2021-03-31 2021-05-26 2021-04-20 2021-06-02 2021-04-30 pport materials (Hand sanitiz ement, M&E, and Communic tions nvelope ers, Masks/Face shields and ations Gloves) MW-MOE-224895-GO-RFQ / Tertiary Education System S Request for Quota Single Stage - One E Procurement of tents to supp IDA / V3480 trengthening, Project Manag Post Limited 58,000.00 114,313.29 Terminated 2021-03-31 2021-03-31 2021-05-26 2021-06-04 2021-06-25 tions nvelope ort learning for Tertiary Instit ement, M&E, and Communic utions ations Tertiary Education System S MW-MOE-258160-GO-DIR / V IDA / 68910 trengthening, Project Manag Post Direct Selection Direct 2,300.00 2,229.45 Completed 2021-10-22 2021-10-18 2021-10-23 2021-10-12 2021-10-30 2021-10-23 2021-11-06 2021-10-27 ehicle Canopy for MG607AN ement, M&E, and Communic ations MW-MOE-258706-GO-DIR / S Tertiary Education System S upply, Installation, Commissi trengthening, Project Manag IDA / V3480 Post Direct Selection Direct 70,000.00 112,000.00 Signed 2021-10-22 2021-10-18 2021-10-24 2021-10-20 2021-11-16 2022-03-16 2021-11-30 oning and after-sales service ement, M&E, and Communic of TOMPRO Accounting Packa ations ge MW-MOE-224900-GO-RFB. / Procurement of various ICT It Tertiary Education System S ems: Computer laptops, Com trengthening, Project Manag Single Stage - One E IDA / V3480 Post Request for Bids Open - National 160,500.00 189,268.33 Completed 2021-03-26 2021-04-06 2021-03-31 2021-04-30 2021-04-30 2021-05-21 2021-07-05 2021-06-18 2021-07-06 2021-08-02 2021-11-03 puter Desktops, Photocopier, ement, M&E, and Communic nvelope printers, cameras, Flash disc ations s, Anti-virus, MS package, Ex tension cables, Extension cab les MW-MOE-224915-GO-RFB. / Tertiary Education System S Procurement of Teleconferen trengthening, Project Manag Single Stage - One E IDA / V3480 Post Request for Bids Open - National 207,500.00 167,797.97 Completed 2021-03-26 2021-03-26 2021-03-31 2021-04-30 2021-04-30 2021-05-21 2021-05-10 2021-06-18 2021-07-03 2021-08-02 2021-10-14 cing equipment and licences ement, M&E, and Communic nvelope under COVID-19 support ations MW-MOE-224900-GO-RFB / P rocurement of various ICT Ite Tertiary Education System S ms: Computer laptops, Comp trengthening, Project Manag Single Stage - One E IDA / V3480 Post Request for Bids Open - National 160,500.00 0.00 Canceled 2021-03-26 2021-03-27 2021-03-31 2021-03-31 2021-04-30 2021-09-10 2021-05-21 2021-06-18 2021-08-02 uter Desktops, Photocopier, p ement, M&E, and Communic nvelope rinters, cameras, Flash discs, ations Anti-virus, MS package, Exte nsion cables, Extension cable s MW-MOE-224915-GO-RFB / P Tertiary Education System S rocurement of Teleconferenci trengthening, Project Manag Single Stage - One E IDA / V3480 Post Request for Bids Open - National 207,500.00 0.00 Canceled 2021-03-26 2021-03-31 2021-03-31 2021-03-31 2021-04-30 2021-04-30 2021-05-21 2021-06-18 2021-08-02 ng equipment and licences u ement, M&E, and Communic nvelope nder COVID-19 support ations MW-MOE-283565-GO-RFQ / Tertiary Education System S Supply and Delivery of 9 x la trengthening, Project Manag Request for Quota Single Stage - One E IDA / V3480 Post Limited 28,000.00 32,663.21 Completed 2022-03-16 2022-03-04 2022-05-11 2022-03-29 2022-06-10 2022-04-12 ptops, 4 x Cell phones/tablet ement, M&E, and Communic tions nvelope s and 2 x 58A Toner ations MW-MOE-299531-GO-RFQ / Tertiary Education System S Request for Quota Single Stage - One E Procurement of Furniture for IDA / V3480 trengthening, Project Manag Post Limited 54,500.00 35,214.14 Completed 2022-06-15 2022-06-20 2022-08-03 2022-07-23 2022-08-24 2022-07-31 tions nvelope SAVE Project PIU ement, M&E, and Communic ations MW-MOE-304579-GO-RFQ / Tertiary Education System S Request for Quota Single Stage - One E Design and printing of banne IDA / 68910 trengthening, Project Manag Post Limited 3,000.00 0.00 Completed 2022-08-17 2022-08-22 2022-09-24 2022-10-15 2022-10-08 tions nvelope rs ement, M&E, and Communic ations MW-MOE-311621-GO-RFQ / Tertiary Education System S Request for Quota Single Stage - One E Under Imple Supply and Fitting of special IDA / 68910 trengthening, Project Manag Post Limited 4,500.00 0.00 2022-08-26 2022-10-21 2022-11-04 tions nvelope mentation size wooden filing cabinets ement, M&E, and Communic ations MW-MOE-316051-GO-RFB / P rocurement of 8 x motor vehi cles as follows: 3 x SAVE PIU Supporting Increase in Acces Single Stage - One E (4x4), 1 x DoDeL (4x4), 1 x Li IDA / 68910 s to TEVET Skills Developme Post Request for Bids Open - National 600,000.00 0.00 Signed 2022-09-20 2022-10-14 2022-09-25 2022-10-14 2022-10-25 2022-11-15 2022-11-08 2022-11-16 2022-11-29 2022-12-29 nvelope vingstonia TC (4x4), 1 x Nam nt itete TC (30 seater bus), 1 x Soche TC (30 seater bus) and 1 x Nasawa TC (30 seater bu s). Page 1 MW-MOE-315276-GO-RFQ / Supporting Increase in Acces Request for Quota Single Stage - One E Pending Impl Procurement of Furniture and IDA / 68910 s to TEVET Skills Developme Post Limited 65,000.00 0.00 2023-02-06 2023-03-27 2023-05-26 tions nvelope ementation Office Equipment - Mzuzu TC nt MW-MOE-316036-GO-RFQ / Supporting Increase in Acces Request for Quota Single Stage - One E Pending Impl Procurement of PPE for stude IDA / 68910 s to TEVET Skills Developme Post Limited 10,600.00 0.00 2022-11-05 2022-12-10 2022-12-24 tions nvelope ementation nts - Mzuzu Technical College nt MW-MOE-316089-GO-RFB / P Supporting Increase in Acces rocurement of Plant and Equi Single Stage - One E Pending Impl IDA / 68910 s to TEVET Skills Developme Post Request for Bids Open - National 190,362.00 0.00 2023-04-01 2023-04-06 2023-05-06 2023-05-20 2023-06-04 2023-06-10 pment Machinery - Lilongwe nvelope ementation nt Technical College MW-MOE-315279-GO-RFQ / Supporting Increase in Acces Request for Quota Single Stage - One E Pending Impl Procurement of Generator - L IDA / 68910 s to TEVET Skills Developme Post Limited 40,000.00 0.00 2023-02-06 2023-03-27 2023-06-10 tions nvelope ementation ivingstonia Technical College nt MW-MOE-316086-GO-RFQ / Supporting Increase in Acces Request for Quota Single Stage - One E Pending Impl Procurement of technical boo IDA / 68910 s to TEVET Skills Developme Post Limited 20,122.00 0.00 2023-03-04 2023-04-01 2023-04-15 tions nvelope ementation ks - Soche Technical College nt MW-MOE-316057-GO-RFQ / Procurement of ICT equipme Tertiary Education System S nt (Desktop computers, Serv trengthening, Project Manag Request for Quota Single Stage - One E IDA / 68910 Post Limited 30,000.00 0.00 Signed 2022-11-14 2022-11-29 2022-12-18 2023-01-08 ers, UPSes, Colour printer, M ement, M&E, and Communic tions nvelope ulti-functional printer, Anti-vi ations rus, LCD projectors and Scre ens, DSLR Cameras and Anti- virus) MW-MOE-315608-GO-RFQ / Tertiary Education System S Request for Quota Single Stage - One E Procurement of Office Equip IDA / 68910 trengthening, Project Manag Post Limited 8,500.00 0.00 Signed 2022-11-13 2022-11-14 2022-12-21 2023-01-11 tions nvelope ment and Welfare items/facili ement, M&E, and Communic ties ations MW-MOE-315995-GO-RFB / P rocurement of various Tools and Equipment (Automobile, Supporting Increase in Acces Open - Internationa Single Stage - One E Pending Impl Plumbing, Welding and Fabri IDA / 68910 s to TEVET Skills Developme Post Request for Bids 1,886,858.00 0.00 2022-11-01 2022-11-08 2022-12-20 2023-01-10 2023-02-14 2023-05-15 l nvelope ementation cation, Solar Photovoltaic, El nt ectrical, General Fitting and Bricklaying) for all 7 x Techni cal Colleges MW-MOE-315281-GO-RFB / P rocurement of Digital infrastr ucture (ICT for ODeL, etc) for Supporting Increase in Acces Open - Internationa Single Stage - One E Pending Impl MoE DODeL,HESLGB, Mzuzu IDA / 68910 s to TEVET Skills Developme Post Request for Bids 1,081,312.00 0.00 2022-12-01 2022-12-06 2023-01-20 2023-02-10 2023-03-17 2023-06-09 l nvelope ementation TC, Salima TC,Lilongwe TC, Li nt vingstonia TC, Soche TC ,and Nasawa TC categorized in lot s of respective approved bud gets MW-MOE-315275-GO-RFQ / Supporting Increase in Acces Request for Quota Single Stage - One E Pending Impl Procurement of Tank and wat IDA / 68910 s to TEVET Skills Developme Post Limited 12,000.00 0.00 2023-08-15 2023-09-26 2023-10-26 tions nvelope ementation er pump - Namitete Technica nt l College MW-MOE-315630-GO-RFQ / Supporting Increase in Acces Request for Quota Single Stage - One E Pending Impl Procurement of Kitchen Elect IDA / 68910 s to TEVET Skills Developme Post Limited 19,250.00 0.00 2023-08-08 2023-09-05 2023-09-26 tions nvelope ementation ric Pots - Namitete Technical nt College MW-MOE-315902-GO-RFQ / Supply and installation of sol Supporting Increase in Acces Request for Quota Single Stage - One E Pending Impl ar powered water supply sys IDA / 68910 s to TEVET Skills Developme Post Limited 50,000.00 0.00 2023-02-15 2023-03-29 2023-05-10 tions nvelope ementation tem and lighting systems at t nt wo campuses of Nasawa Tec hnical College MW-MOE-315613-GO-RFQ / Tertiary Education System S Procurement of Industrial Ta trengthening, Project Manag Request for Quota Single Stage - One E IDA / 68910 Post Limited 88,000.00 0.00 Signed 2022-11-16 2022-11-14 2022-12-17 2023-01-07 blets for GEMs for SAVE Proje ement, M&E, and Communic tions nvelope ct participating institutions ations MW-MOE-325328-GO-RFQ / Supporting Increase in Acces Request for Quota Single Stage - One E Supply and Delivery of office IDA / 68910 s to TEVET Skills Developme Post Limited 12,000.00 0.00 Signed 2022-11-23 2022-11-21 2023-01-11 2023-02-08 tions nvelope stationery and tools for SAVE nt PIU office MW-MOE-333299-GO-RFQ / Supply and Delivery of Educa tion and Informationand Com Supporting Increase in Acces munication (EIC) materials fo Request for Quota Single Stage - One E Pending Impl IDA / 68910 s to TEVET Skills Developme Post Limited 20,000.00 0.00 2023-01-01 2023-01-29 2023-02-28 r Lilongwe Technical College. tions nvelope ementation nt They include fliers, fishing ja ckest, branded golf shirts, br anded pens, branded diaries, posters, banners and rain co ats MW-MOE-333305-GO-RFQ / Supporting Increase in Acces Supply and delivery of variou Request for Quota Single Stage - One E Under Imple IDA / 68910 s to TEVET Skills Developme Post Limited 7,000.00 0.00 2023-01-02 2023-01-30 2023-02-13 s stationery items and office tions nvelope mentation nt accessories for Lilongwe Tec hnical college MW-MOE-336193-GO-RFQ / Tertiary Education System S Supply and installation of 12 trengthening, Project Manag Request for Quota Single Stage - One E Pending Impl IDA / 68910 Post Limited 12,000.00 0.00 2023-01-24 2023-03-07 2023-04-04 KVA power backup system fo ement, M&E, and Communic tions nvelope ementation r SAVE Project office ations MW-MOE-339765-GO-RFQ / Supply and Delivery of Griev Tertiary Education System S ance Redress Mechanism Re trengthening, Project Manag Request for Quota Single Stage - One E Under Imple IDA / 68910 Post Limited 3,000.00 0.00 2023-02-11 2023-03-25 2023-04-24 gisters (books) and Log and ement, M&E, and Communic tions nvelope mentation Resolution Forms for environ ations mental, gender and social saf eguards management MW-MOE-344323-GO-RFQ / Tertiary Education System S Supply, delivery and installati trengthening, Project Manag Request for Quota Single Stage - One E Pending Impl IDA / 68910 Post Limited 60,000.00 0.00 2023-04-21 2023-05-19 2023-06-09 on of office networks for Loc ement, M&E, and Communic tions nvelope ementation al Area Network (LAN) for SA ations VE PIU offices MW-MOE-347631-GO-RFQ / Supporting Increased Access Supply and delivery of ICT eq Request for Quota Single Stage - One E Pending Impl IDA / 68910 to Skills Development Progra Post Limited 18,000.00 0.00 2023-04-23 2023-06-11 2023-07-02 uipment, fittings and materia tions nvelope ementation ms in Higher Education ls for HESLGB and NCHE MW-MOE-357020-GO-RFQ / Supporting Increased Access Request for Quota Single Stage - One E Pending Impl Supply and Delivery of speci IDA / 68910 to Skills Development Progra Post Limited 65,000.00 0.00 2023-04-26 2023-06-21 2023-07-21 tions nvelope ementation alized laptops for HEMIS ms in Higher Education NON CONSULTING SERVICES Page 2 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-MOE-328783-NC-DIR / In Supporting Increase in Acces Pending Impl stallation of 7 teleconferenci IDA / 68910 s to TEVET Skills Developme Post Direct Selection Direct - National 10,000.00 0.00 2022-12-16 2022-12-21 2023-01-18 2023-02-08 ementation ng equipment in selected ins nt titutions CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-MOE-201088-CS-CQS / C Tertiary Education System S onsultancy service to carry o trengthening, Project Manag Consultant Qualifi IDA / V3480 Post Limited 86,000.00 0.00 Canceled 2020-10-26 2020-11-15 2020-11-02 2020-12-02 2020-12-19 2021-06-17 ut Environmental Social Safe ement, M&E, and Communic cation Selection guard studies-ESMF, SEP, ES ations MCP, P4R (Firm) MW-MOE-224906-CS-CQS / C Tertiary Education System S Consultant Qualifi onsultancy Service to conduc IDA / V3480 trengthening, Project Manag Post Open - National 92,000.00 86,332.08 Signed 2021-03-26 2021-03-26 2021-04-02 2021-04-15 2021-04-25 2021-08-26 2021-05-23 2021-11-18 2021-05-28 2021-12-08 2021-09-25 cation Selection t a Skills Needs Assessment ( ement, M&E, and Communic Firm) ations MW-MOE-224919-CS-CQS / C onsultancy to conceptualize a holistic, integrated ICT-bas Tertiary Education System S ed structure that details ele trengthening, Project Manag Consultant Qualifi IDA / V3480 Post Open - National 60,000.00 0.00 Canceled 2021-04-09 2021-04-10 2021-04-16 2021-05-09 2021-06-06 2021-06-11 2021-10-09 ments related to M&E (includ ement, M&E, and Communic cation Selection ing EMIS), labor market infor ations mation and integration platfo rm, communications channel s, and mobile-based activitie s (Firm) MW-MOE-224917-CS-CQS / c Tertiary Education System S onsultancy service to assess trengthening, Project Manag Consultant Qualifi IDA / V3480 Post Open - National 50,000.00 0.00 Canceled 2021-04-09 2021-05-21 2021-04-16 2021-05-09 2021-06-06 2021-06-11 2021-10-09 physical and operational nee ement, M&E, and Communic cation Selection ds of the selected training in ations stitutions MW-MOE-224916-CS-CQS / C onsultancy Service to conduc Tertiary Education System S t assessment of ODeL requir trengthening, Project Manag Consultant Qualifi ements (infrastructure for Hi IDA / V3480 Post Open - National 75,000.00 0.00 Canceled 2021-03-26 2021-03-26 2021-04-02 2021-04-25 2021-05-23 2021-05-28 2021-09-25 ement, M&E, and Communic cation Selection gher Education Institutions ( ations HEI) and Technical and Vocat ional Education) in TEVET ins titutions (Firm) MW-MOE-283566-CS-QCBS / Hiring of an Independent Veri Tertiary Education System S fication Agency (IVA) - a third trengthening, Project Manag Quality And Cost- Open - Internationa Under Implement IDA / V3480 Post 585,000.00 0.00 2022-03-22 2022-06-27 2022-04-12 2022-08-19 2022-05-10 2022-11-28 2022-06-21 2022-07-05 2022-07-19 2022-08-23 2023-08-23 -party firm to conduct verific ement, M&E, and Communic Based Selection l ation ation of achieved results and ations processes provided in the SA VE project results framework. MW-MOE-316031-CS-CQS / C onsultancy service to carry o Tertiary Education System S ut a study on constraints and trengthening, Project Manag Consultant Qualifi Pending Impleme IDA / 68910 Post Open - National 91,000.00 0.00 2023-11-30 2023-12-14 2024-01-11 2024-01-25 2024-02-22 2024-04-22 strategies to improve equity i ement, M&E, and Communic cation Selection ntation n access to higher education ations and improve outcomes for all students MW-MOE-316080-CS-CQS / C Tertiary Education System S onsultancy on Gender Based trengthening, Project Manag Consultant Qualifi Pending Impleme IDA / 68910 Post Open - National 50,000.00 0.00 2023-05-01 2023-05-15 2023-06-12 2023-06-13 2023-07-11 2023-07-15 violence, abuse, and harass ement, M&E, and Communic cation Selection ntation ment in Higher Education Ins ations titutions MW-MOE-315926-CS-CQS / C Tertiary Education System S onsulting Services to carry o trengthening, Project Manag Consultant Qualifi Pending Impleme IDA / 68910 Post Open - National 96,000.00 0.00 2023-03-01 2023-03-22 2023-04-19 2023-05-03 2023-05-31 2023-07-30 ut a Study on Intellectual pro ement, M&E, and Communic cation Selection ntation perty, copyright, and fair use ations in higher education MW-MOE-315277-CS-CQS / C Tertiary Education System S onsulting Services to develop trengthening, Project Manag Consultant Qualifi Pending Impleme a Strategy for integrating pra IDA / 68910 Post Open - National 70,000.00 0.00 2023-08-01 2023-08-22 2023-09-26 2023-10-10 2023-11-07 2024-02-05 ement, M&E, and Communic cation Selection ntation ctical education and value ad ations dition programs in higher ed ucation MW-MOE-316055-CS-CQS / C Tertiary Education System S Consultant Qualifi Pending Impleme onsulting Services to develop IDA / 68910 trengthening, Project Manag Post Open - National 82,000.00 0.00 2023-02-01 2023-02-15 2023-03-15 2023-03-29 2023-04-26 2023-06-10 cation Selection ntation Staffing Norms for Higher Ed ement, M&E, and Communic ucation Staff ations MW-MOE-325326-CS-QCBS / Supporting Increase in Acces Consultancy for design and c Quality And Cost- IDA / 68910 s to TEVET Skills Developme Post Open - National 147,000.00 0.00 Canceled 2022-11-11 2022-11-25 2022-12-30 2023-01-29 2023-02-19 2023-03-19 2023-04-16 2023-06-30 onstruction supervision at Lil Based Selection nt ongwe, Namitete and Salima Technical Colleges MW-MOE-326273-CS-CQS / C Supporting Increase in Acces onsultancy for design and co Consultant Qualifi Under Implement IDA / 68910 s to TEVET Skills Developme Post Open - National 70,000.00 0.00 2022-11-16 2023-01-03 2022-11-30 2023-01-11 2023-01-11 2023-01-25 2023-03-01 2023-04-30 nstruction supervision at Livi cation Selection ation nt ngstonia and Mzuzu Technica l Colleges MW-MOE-326272-CS-CQS / C Supporting Increase in Acces onsultancy for design and su Consultant Qualifi Under Implement IDA / 68910 s to TEVET Skills Developme Post Open - National 57,100.00 0.00 2022-11-16 2023-01-03 2022-12-07 2023-01-11 2023-01-11 2023-01-25 2023-03-01 2023-04-30 pervision of construction at S cation Selection ation nt oche and Nasawa Technical Colleges MW-MOE-326274-CS-CQS / C onsultancy service for design Supporting Increase in Acces Consultant Qualifi Under Implement and supervision of constructi IDA / 68910 s to TEVET Skills Developme Post Open - National 147,000.00 0.00 2022-11-16 2023-01-03 2022-12-07 2023-01-11 2023-01-11 2023-01-25 2023-03-01 2023-04-30 cation Selection ation on works for Lilongwe, Namit nt ete and Salima Techical Colle ges Tertiary Education System S MW-MOE-315928-CS-CQS / Consultant Qualifi IDA / 68910 trengthening, Project Manag Post Open - National 65,000.00 0.00 Canceled 2022-11-14 2022-11-28 2022-12-26 2023-01-09 2023-02-13 2023-03-30 Hiring of an External Auditor cation Selection ement, M&E, and Communic ations MW-MOE-360428-CS-CQS / C Tertiary Education System S onsultancy service - Recruit trengthening, Project Manag Consultant Qualifi Pending Impleme ment of a consulting law firm IDA / 68910 Post Limited 30,000.00 0.00 2023-05-10 2023-05-24 2023-06-23 2023-07-28 2023-09-26 ement, M&E, and Communic cation Selection ntation to review the Higher Educati ations on Students Loans and Grant s (HESLG) Board Act INDIVIDUAL CONSULTANTS Page 3 Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Tertiary Education System S MW-MOE-201067-CS-INDV / Individual Consult IDA / V3480 trengthening, Project Manag Prior Limited 48,000.00 0.00 Canceled 2020-10-26 2020-11-09 2020-11-23 2020-12-14 2021-12-14 Procurement Specialist ant Selection ement, M&E, and Communic ations Tertiary Education System S MW-MOE-223031-CS-INDV / Individual Consult IDA / V3480 trengthening, Project Manag Prior Open 48,000.00 38,216.57 Signed 2021-03-12 2021-03-10 2021-05-09 2021-08-02 2021-05-10 2021-09-10 2021-06-03 2021-08-13 2021-07-12 Procurement Specialist ant Selection ement, M&E, and Communic ations Tertiary Education System S MW-MOE-224899-CS-INDV / Individual Consult IDA / V3480 trengthening, Project Manag Post Open 64,000.00 51,445.38 Signed 2021-03-26 2021-03-25 2021-05-14 2021-08-17 2021-06-04 2021-08-20 2021-06-25 2021-09-28 2026-06-24 Hiring of Project Manager ant Selection ement, M&E, and Communic ations MW-MOE-224907-CS-INDV / Tertiary Education System S Individual Consult Hiring of Financial Managem IDA / V3480 trengthening, Project Manag Post Open 48,000.00 44,096.04 Signed 2021-03-26 2021-03-25 2021-05-14 2021-08-26 2021-06-04 2021-08-30 2021-06-25 2021-10-28 2026-06-24 ant Selection ent Specialist ement, M&E, and Communic ations MW-MOE-224912-CS-INDV / Tertiary Education System S Individual Consult Hiring of Communications Sp IDA / V3480 trengthening, Project Manag Post Open 48,000.00 44,096.04 Signed 2021-03-26 2021-03-25 2021-05-14 2021-09-14 2021-06-04 2021-11-26 2021-06-25 2021-12-23 2026-06-24 ant Selection ecialist ement, M&E, and Communic ations MW-MOE-224911-CS-INDV / Tertiary Education System S Individual Consult Hiring of Social Safeguards S IDA / V3480 trengthening, Project Manag Post Open 48,000.00 44,096.04 Signed 2021-03-26 2021-03-25 2021-05-14 2021-11-14 2021-06-04 2021-11-26 2021-06-25 2021-12-23 2026-06-24 ant Selection pecialist ement, M&E, and Communic ations MW-MOE-224909-CS-INDV / Tertiary Education System S Individual Consult Hiring of Environmental Spec IDA / V3480 trengthening, Project Manag Post Open 48,000.00 44,096.04 Signed 2021-03-26 2021-03-25 2021-05-14 2021-06-07 2021-06-04 2021-11-26 2021-06-25 2021-12-23 2026-06-24 ant Selection ialist ement, M&E, and Communic ations MW-MOE-224898-CS-INDV / Tertiary Education System S Individual Consult Consultancy service to devel IDA / V3480 trengthening, Project Manag Post Open 46,000.00 42,499.99 Completed 2021-03-26 2021-03-26 2021-04-30 2021-06-14 2021-05-14 2021-06-17 2021-06-04 2021-07-03 2021-07-19 2022-05-01 ant Selection op Project Implementation M ement, M&E, and Communic anual ations Tertiary Education System S MW-MOE-224908-CS-INDV / Individual Consult IDA / V3480 trengthening, Project Manag Post Open 48,000.00 44,096.04 Signed 2021-05-21 2021-05-21 2021-07-09 2021-09-14 2021-07-30 2021-11-26 2021-08-20 2021-12-23 2026-08-19 Hiring of M & E Specialist ant Selection ement, M&E, and Communic ations MW-MOE-264089-CS-INDV / Tertiary Education System S Individual Consult Under Implement Hiring of Procurement Specia IDA / 68910 trengthening, Project Manag Prior Open 48,000.00 0.00 2021-11-24 2021-12-09 2022-01-12 2022-05-04 2022-02-02 2022-09-14 2022-03-09 2023-03-09 ant Selection ation list II ement, M&E, and Communic ations Tertiary Education System S MW-MOE-263972-CS-INDV / Individual Consult Under Implement IDA / 68910 trengthening, Project Manag Post Open 30,000.00 0.00 2021-11-24 2021-12-09 2022-01-12 2022-08-23 2022-02-02 2022-08-23 2022-03-09 2023-03-09 Hiring of Accountant ant Selection ation ement, M&E, and Communic ations MW-MOE-308821-CS-INDV / Tertiary Education System S Individual Consult Consultancy services to deve IDA / 68910 trengthening, Project Manag Post Open - National 40,000.00 0.00 Signed 2022-07-21 2022-09-12 2022-08-18 2022-11-07 2022-09-01 2022-11-07 2022-09-29 2023-01-27 ant Selection lop website for the SAVE Proj ement, M&E, and Communic ect ations MW-MOE-315245-CS-INDV / Supporting Increased Access Individual Consult Under Implement Consulting services for the re IDA / 68910 to Skills Development Progra Post Open - National 30,000.00 0.00 2022-11-07 2023-02-12 2022-12-12 2022-12-26 2023-01-23 2023-03-24 ant Selection ation view of the HESLG Act - HESL ms in Higher Education G MW-MOE-315633-CS-INDV / Hiring of a training consultan Supporting Increase in Acces Individual Consult Pending Impleme t on Gender Based Violence a IDA / 68910 s to TEVET Skills Developme Post Open - National 5,000.00 0.00 2022-11-07 2022-12-19 2023-01-02 2023-01-23 2023-02-22 ant Selection ntation nd sexual reproductive healt nt h - Mzuzu Technical College MW-MOE-315628-CS-INDV / Supporting Increase in Acces Individual Consult Pending Impleme Hiring a training consultant o IDA / 68910 s to TEVET Skills Developme Post Open - National 5,000.00 0.00 2023-06-01 2023-07-06 2023-07-20 2023-08-17 2023-09-16 ant Selection ntation n use of ODeL - Mzuzu Techni nt cal College MW-MOE-328778-CS-INDV / Supporting Increase in Acces Consultancy for Developmen Individual Consult IDA / 68910 s to TEVET Skills Developme Post Limited 12,000.00 0.00 Signed 2022-12-02 2022-11-30 2022-12-07 2022-12-20 2022-12-28 2023-03-07 2023-01-25 2023-03-26 t of ESMPs for Livingstonia an ant Selection nt d Mzuzu Technical Colleges MW-MOE-328779-CS-INDV / Supporting Increase in Acces Consultancy for Developmen Individual Consult IDA / 68910 s to TEVET Skills Developme Post Limited 18,000.00 0.00 Signed 2022-12-02 2022-11-30 2022-12-07 2022-12-20 2022-12-28 2023-03-07 2023-01-25 2023-03-26 t of ESMPs for Lilongwe, Nam ant Selection nt itete and Salima Technical C olleges MW-MOE-328780-CS-INDV / Supporting Increase in Acces Consultancy for Developmen Individual Consult IDA / 68910 s to TEVET Skills Developme Post Limited 12,000.00 0.00 Signed 2022-12-02 2022-11-30 2022-12-07 2022-12-20 2022-12-28 2023-03-06 2023-01-25 2023-03-26 t of ESMPs for Soche and Nas ant Selection nt awa Technical Colleges MW-MOE-325226-CS-INDV / Development of Environment Supporting Increase in Acces Individual Consult al and Social Management Pl IDA / 68910 s to TEVET Skills Developme Post Open - National 12,000.00 0.00 Canceled 2022-11-11 2022-11-13 2022-12-30 2023-01-13 2023-02-10 2023-04-11 ant Selection ans (ESMP) for Soche and Na nt sawa Technical Schools MW-MOE-325219-CS-INDV / Development of Environment Supporting Increase in Acces Individual Consult al and Social Management Pl IDA / 68910 s to TEVET Skills Developme Post Open - National 12,000.00 0.00 Canceled 2022-11-11 2022-11-13 2022-12-30 2023-01-13 2023-02-10 2023-04-11 ant Selection ans (ESMP) for Livingstonia a nt nd Mzuzu Technical Colleges MW-MOE-325225-CS-INDV / Development of Environment Supporting Increase in Acces Individual Consult al and Social Management Pl IDA / 68910 s to TEVET Skills Developme Post Open - National 18,000.00 0.00 Canceled 2022-11-11 2022-11-13 2022-12-30 2023-01-13 2023-02-10 2023-04-11 ant Selection ans (ESMP) for Namitete, Lilo nt ngwe and Salima Technical S chools MW-MOE-333296-CS-INDV / Supporting Increase in Acces Consultancy service to devel Individual Consult Under Implement IDA / 68910 s to TEVET Skills Developme Post Open - National 30,000.00 0.00 2022-12-28 2023-01-06 2023-02-15 2023-03-08 2023-04-05 2023-06-04 op a Gender and Sexual Hara ant Selection ation nt ssment Policy for Technical C olleges MW-MOE-336191-CS-INDV / Tertiary Education System S Consultancy service for Deve trengthening, Project Manag Individual Consult Under Implement lopment of an Application Pro IDA / 68910 Post Limited 9,000.00 0.00 2023-01-16 2023-04-13 2023-01-19 2023-03-20 2023-01-29 2023-05-08 2023-02-12 2023-03-14 ement, M&E, and Communic ant Selection ation gramming Interface (API) End ations point for National Council for Higher Education (NCHE) Page 4 MW-MOE-340819-CS-INDV / Tertiary Education System S Individual Consult Under Implement Recruitment of construction IDA / 68910 trengthening, Project Manag Prior Open - National 58,500.00 0.00 2023-02-10 2023-02-28 2023-04-09 2023-05-09 2023-06-13 2024-06-12 ant Selection ation engineer for SAVE PIU ement, M&E, and Communic ations MW-MOE-340825-CS-INDV / Tertiary Education System S Individual Consult Under Implement Recruitment of Communicati IDA / 68910 trengthening, Project Manag Prior Open - National 48,000.00 0.00 2023-02-10 2023-04-25 2023-04-09 2023-05-09 2023-06-29 2024-06-28 ant Selection ation ons Specialist for SAVE Proje ement, M&E, and Communic ct ations MW-MOE-360425-CS-INDV / Tertiary Education System S Consultancy service - Recruit trengthening, Project Manag Individual Consult Pending Impleme IDA / 68910 Post Open - National 144,000.00 0.00 2023-05-15 2023-07-08 2023-07-29 2023-09-02 2024-09-01 ment of an Environmental Sa ement, M&E, and Communic ant Selection ntation feguards Specialist (ESS) for ations SAVE Project MW-MOE-360427-CS-INDV / Tertiary Education System S Consultancy service - Recruit trengthening, Project Manag Individual Consult Under Implement IDA / 68910 Post Open - National 162,000.00 0.00 2023-05-15 2023-06-04 2023-07-08 2023-07-29 2023-09-02 2024-09-01 ment of Financial Manageme ement, M&E, and Communic ant Selection ation nt Specialist (FMS) for SAVE P ations roject PIU MW-MOE-363177-CS-INDV / Tertiary Education System S Individual Consult Under Implement Consultancy - Individual Cons IDA / 68910 trengthening, Project Manag Post Open - National 76,000.00 0.00 2023-05-29 2023-05-28 2023-07-17 2023-08-07 2023-09-11 2025-09-10 ant Selection ation ultant to develop software fo ement, M&E, and Communic r HEMIS ations Page 5 Procurement Plan I. General 1. Project Information Country : Kenya Recipient : Republic of Kenya Project Name : National Agriculture and Rural Inclusive Growth Loan Credit No. : IDA 59000 2. Date of General Procurement Notice : 9th February 2018 3. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services 1. Thresholds for the Method of Procurement: Method of Procurement Thresholds for Method (US$ equivalent) Open International (Goods) Equal to or more than 3 million Open National ( Goods) – Open < $3 million Tender as per PPDA 2015 RFQ (Goods) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Open International (Works) Equal to or more than 15 million Open National (Works) - Open Less than 15 million Tender as per PPDA 2015 RFQ (works) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Method of Procurement Thresholds for Method (US$ equivalent) Open International (Non-consulting Equal to or More than 3 million Services) Open National (Non-consulting Less than 3 million Services) - Open Tender as per PPDA 2015 Direct Contracting No threshold; meet requirements of Bank’s Procurement Regulations Prior Review: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection (Project Procurement Risk Rating is “High”): (a) Goods, information technology and Non-consulting Services: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1.5 million (b) Works (including turnkey, supply & installation of plant and equipment and PPP); First procurement under the project irrespective of value and all procurements estimated to cost more than USD 5 million and The prior review thresholds will be reviewed during the implementation of the project and modified, based on the risk assessment. 2. For contracts subject to prior review, the Borrower shall seek the Bank’s no objection before agreeing to: a. an extension of the stipulated time for execution of a contract that has an impact on the planned completion of the project; b. any material modification of the scope of the Works, Goods, Non- consulting services or Consulting Services, or other significant changes to the terms and conditions of the contract; c. any variation order or contract amendment (except in cases of extreme urgency), including due to extension of time, that singly or combined with all previous variation orders or amendments, increases the original contract amount by more than 15% (fifteen percent); or d. the proposed termination of the contract. The Borrower / IA shall provide a copy of all amendments to the contract to the Bank for its records. 3. Prequalification Not Applicable Domestic Preference. The provision of domestic preference shall be applied in the procurement of goods following international market approach in accordance with Annex VI of the Regulations. Domestic preference shall not apply in the procurement of works. 4. Reference to Standard Procurement Documents Bank’s Standard RFB Goods and RFP Consulting Services dated July 2016 will be used as a base and incorporating suitable modifications and the same would be agreed with the Bank subject international competition. 5. Any Other Special Procurement Arrangements A. Procurement approach under CDD Approach by Communities: Applicable if stipulated in the PAD. B. When approaching the national market, as agreed in the Procurement Plan, the Open Tender procedure of Public Procurement and Asset Disposal Act 2015 and Regulations 2017 may be used. The specific Requirements for national open competitive procurement include the following: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. Other national procurement arrangements (other than national open competitive procurement), that may be applied by the Borrower (such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti-Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. In all cases, the national procurement procedures to be used shall give due attention to quality aspects. 6. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Selection methods of procurement of Consultants' Services (Firms): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Quality and Cost Based As per requirements of para 7.3 of the Selection (QCBS) Regulations Quality Based Selection As per requirements of para 7.8 to 7.10 (QBS) of the Regulations Selection based on a Fixed As per requirements of para 7.4 and 7.5 of the Budget (FBS) Regulations Selection Based on Least As per requirements of para 7.6 and 7.7 of the Cost Basis (LCS) Regulations Selection based on As per requirements of para 7.11 and 7.12 of Consultant’s Qualification the Regulations (CQ) Direct Must meet the requirements of Para 7.13 to 7.15 of the Regulations, and with prior agreement in PP with the Bank. The short list may consist of all National consultants in case the estimated cost is less than USD 300,000 Procurement methods for Selection of Individual Consultants (IC): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Open Competitive As per requirements of para 7.36 and 7.37 of Selection the Regulations Limited Competitive As per requirements of para 7.38 of the Selection Regulations Direct Must meet the requirements of Para 7.39 of the Regulations, and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Regulations Prior Review Thresholds: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 0.5 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.2 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. PROCUREMENT Kenya : National Agricultural and Rural Inclusive Growth Project PLAN General Information Country: Kenya 2019-12-01 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153349 GPN Date: 2018-02-09 Project Name: National Agricultural and Rural Inclusive Growth Project Loan / Credit No: IDA / 59000 Vihiga County Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-VIHIGA COUNTY-145191- CW-RFB / EMABUNGO - WEMI Supporting Community-Driv Single Stage - One E 2020-07-1 LABI AND CENTRAL BUNYOR IDA / 59000 Post Request for Bids Open - National 588,235.30 0.00 Completed 2019-11-18 2021-12-22 2019-12-02 2022-12-05 2019-12-16 2022-01-05 2019-12-23 2022-01-13 2020-01-13 en Development nvelope 1 E INTEGRATED LANDSCAPE MANAGEMENT AND IRRIGATI ON PROJECT KE-VIHIGA COUNTY-172540- Project Coordination and Ma Request for Quota Single Stage - One E 2020-08-0 IDA / 59000 Post Limited 8,000.00 6,734.75 Completed 2020-05-23 2021-06-08 2020-07-07 2021-06-24 CW-RFQ / OFFICE REFURBISH nagement tions nvelope 6 MENT KE-VIHIGA COUNTY-315165- CW-RFQ / Establishment of b Strengthening Producer Org Request for Quota anana aggregation, ripening Request for Quota Single Stage - One E Pending Imp 2023-05-1 IDA / 59000 anizations and Value Chain Post Open - National tions (Non Bank-S 94,513.00 0.00 2022-09-21 2022-11-19 and marketing center for Ha tions nvelope lementation 8 Development PD) misi Banana Farmers' Cooper ative Society in Hamisi Sub C ounty of Vihiga County KE-VIHIGA COUNTY-315142- CW-RFQ / Construction of ha y barn at Sabatia Sub County Strengthening Producer Org Request for Quota Diry Farmers' Cooperative So Request for Quota Single Stage - One E Under Imple 2023-05-1 IDA / 59000 anizations and Value Chain Post Open - National tions (Non Bank-S 139,343.00 0.00 2022-09-21 2023-05-26 2022-11-19 ciety. The project entails con tions nvelope mentation 8 Development PD) struction of a hay store meas uring (21*12*4.35) M to be st ocked with 10,000 hay bales of size 0.6m by 0.45m by 0.3 5m KE-VIHIGA COUNTY-315150- CW-RFQ / Construction of a b anana processing plant to val Strengthening Producer Org Request for Quota Request for Quota Single Stage - One E Under Imple 2023-05-1 ue-add banana and its by-pro IDA / 59000 anizations and Value Chain Post Open - National tions (Non Bank-S 165,986.00 0.00 2022-09-20 2023-06-20 2022-11-18 tions nvelope mentation 7 ducts into banana flakes, ban Development PD) ana flour sweetener and tend erizer by Sabatia Banana Far mers' Cooperative Society National Procure KE-VIHIGA COUNTY-354798- ment Document - CW-RFQ / SUPPLY ,DELIVERY Supporting County Communi Request for Quota Single Stage - One E Under Imple 2023-12-0 IDA / 59000 Post Limited 1 Envelope proce 90,225.56 0.00 2023-04-09 2023-04-14 2023-06-04 AND INSTALLATION OF FARM ty-Led Development tions nvelope mentation 1 ss (Non Bank-SPD PONDS MATERIALS ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-VIHIGA COUNTY-139253- Project Coordination and Ma Request for Quota Single Stage - One E GO-RFQ / PURCHASE OF OFF IDA / 59000 Post Limited 12,932.60 0.00 Signed 2019-11-18 2020-02-27 2019-12-28 2020-02-26 nagement tions nvelope ICE FURNITURE FOR CPCU OF FICES KE-VIHIGA COUNTY-170190- GO-RFQ / PROCUREMENT OF Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 78,431.00 54,508.76 Completed 2020-05-01 2020-05-21 2020-06-26 2020-07-01 2020-07-26 2020-09-01 TWENTY (20)No. MOTORCYCL nagement tions nvelope ES OF ENGINE DISPLACEMENT 1 25cc KE-VIHIGA COUNTY-172520- Project Coordination and Ma Request for Quota Single Stage - One E Under Imple GO-RFQ / PROCUREMENT OF IDA / 59000 Post Limited 8,000.00 0.00 2020-05-18 2020-05-20 2020-06-29 2020-07-29 nagement tions nvelope mentation 5(FIVE)No. LAPTOPS FOR CPC U KE-VIHIGA COUNTY-172533- Supporting County Communi Request for Quota Single Stage - One E GO-RFQ / PROCUREMENT OF IDA / 59000 Post Limited 8,900.00 0.00 Signed 2020-05-20 2021-06-15 2020-07-02 2020-07-23 ty-Led Development tions nvelope SURVEY TOOLS KE-VIHIGA COUNTY-172525- CW-RFQ / SUPPLY, INSTALL, T Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 73,000.00 0.00 Signed 2020-05-23 2021-06-08 2020-07-14 2020-08-14 EST AND COMMISSION VIRTU nagement tions nvelope AL MEETINGS AND COMMUNI CATION EQUIPMENT KE-VIHIGA COUNTY-230057- Supporting County Communi Request for Quota Single Stage - One E GO-RFQ / Real time kinemati IDA / 59000 Post Limited 33,619.00 30,013.63 Completed 2021-05-01 2021-06-08 2021-06-26 2021-06-22 2021-12-23 2021-06-26 ty-Led Development tions nvelope c survey machine KE-VIHIGA COUNTY-230063- Supporting County Communi Request for Quota Single Stage - One E GO-RFQ / purchase of soil tes IDA / 59000 Post Limited 6,000.00 0.00 Signed 2021-05-01 2021-06-08 2021-06-26 2021-12-23 ty-Led Development tions nvelope ting equipment KE-VIHIGA COUNTY-231727- GO-RFQ / PROCUREMENT OF Supporting County Communi Request for Quota Single Stage - One E Under Imple IDA / 59000 Post Limited 21,238.10 0.00 2021-06-12 2021-06-07 2021-07-09 2021-10-07 TERRACE STABLIZATION MAT ty-Led Development tions nvelope mentation ERIALS FOR EMABUNGO MCI KE-VIHIGA COUNTY-233163- Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 1,305.36 0.00 Canceled 2021-06-12 2021-07-01 2021-07-11 GO-RFQ / PURCHASE OF ONE ty-Led Development tions nvelope LAPTOP KE-VIHIGA COUNTY-354566- GO-RFQ / PROCUREMENT FO Supporting County Communi Request for Quota Single Stage - One E Under Imple IDA / 59000 Post Limited 54,799.94 0.00 2023-04-09 2023-04-14 2023-06-04 2023-12-01 R SEEDLINGS FOR SUSTAINA ty-Led Development tions nvelope mentation BLE LAND MANAGEMENT PR OJECT SITES KE-VIHIGA COUNTY-362945- Strengthening Producer Org GO-RFQ / Procurement of 20 Request for Quota Single Stage - One E Under Imple IDA / 59000 anizations and Value Chain Post Limited 21,770.68 0.00 2023-05-28 2023-07-23 2024-01-19 desktop computers and 20 pr tions nvelope mentation Development inters for SACCOs automatio n Page 1 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-VIHIGA COUNTY-346064- NC-DIR / Procurement of Lice Strengthening Producer Org nce for proprietary software Under Imple IDA / 59000 anizations and Value Chain Post Direct Selection Direct - National 11,041.00 0.00 2023-02-27 2023-03-24 2023-03-04 2023-04-17 2023-04-08 2023-10-05 copyrighted by Amtech Tech mentation Development nologies for the Digitization o f SACCOs and POs operations under DAT III. KE-VIHIGA COUNTY-346069- Strengthening Producer Org NC-DIR / Procurement of lice Pending Impl IDA / 59000 anizations and Value Chain Post Direct Selection Direct - National 11,041.00 0.00 2023-02-27 2023-03-04 2023-04-08 2023-10-05 nce for ACS by AMTEC Techn ementation Development ologies DAT III Cohort for digi tization of SACCOs/POs KE-VIHIGA COUNTY-346074- NC-DIR / Procurement of lice Supporting Community-Driv Under Imple IDA / 59000 Post Direct Selection Direct - National 9,463.00 0.00 2023-02-27 2023-03-24 2023-03-04 2023-04-17 2023-04-08 2023-10-05 nce for MShamba DAT III Coh en Development mentation ort Farmer Marketing Platfor m Software KE-VIHIGA COUNTY-346080- NC-DIR / Procurement of lice nce for Kuza Biashara DAT III Supporting Community-Driv Under Imple Cohort Farmer Training, Mark IDA / 59000 Post Direct Selection Direct - National 15,643.00 0.00 2023-02-27 2023-03-24 2023-03-04 2023-04-17 2023-04-08 2023-10-05 en Development mentation eting and Input/Output Aggre gation Platform Software and Associated Instructional Mate rial; mini-projector and andro id tablets KE-VIHIGA COUNTY-346089- NC-DIR / Procurement of serv ices for the development of c Supporting Community-Driv Under Imple IDA / 59000 Post Direct Selection Direct - National 8,366.00 0.00 2023-06-21 2023-04-17 2023-06-25 2023-05-18 2023-07-30 2024-01-26 ustom built geo-referenced d en Development mentation ashboards for visualization of project investments in the co mmunities CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-VIHIGA COUNTY-144919- CS-QCBS / CAPACITY BUILDIN G OF COMMON INTEREST GR Supporting Community-Driv Quality And Cost- Pending Impleme IDA / 59000 Post Open - National 196,078.43 0.00 2019-12-10 2019-12-31 2020-02-13 2020-03-12 2020-04-11 2020-05-16 2020-06-20 2021-06-20 OUPS / VULNERABLE AND MA en Development Based Selection ntation RGINALIZED GROUPS ALONG THE 4(FOUR) PRIORITIZED V ALUE CHAINS KE-VIHIGA COUNTY-179009- CS-CQS / RECRUITMENT OF S Supporting Community-Driv Consultant Qualifi Under Implement IDA / 59000 Post Open - National 49,505.00 0.00 2020-06-21 2020-09-28 2020-07-05 2023-05-25 2020-07-19 2020-09-08 2020-07-26 2020-08-16 2021-12-31 ERVICE PROVIDER FOR BANA en Development cation Selection ation NA VALUE CHAIN ADVISORY SERVICES KE-VIHIGA COUNTY-179010- CS-CQS / RECRUITMENT OF S Supporting Community-Driv Consultant Qualifi Under Implement IDA / 59000 Post Open - National 49,505.00 0.00 2020-06-21 2020-09-28 2020-07-06 2020-07-20 2020-09-08 2020-07-27 2020-08-17 2021-12-31 ERVICE PROVIDER FOR CHIC en Development cation Selection ation KEN VALUE CHAIN ADVISORY SERVICES KE-VIHIGA COUNTY-179012- CS-CQS / RECRUITMENT OF S Supporting Community-Driv Consultant Qualifi Under Implement IDA / 59000 Post Open - National 49,505.00 0.00 2020-06-21 2020-09-28 2020-07-06 2020-07-20 2020-07-27 2020-08-17 2021-12-31 ERVICE PROVIDER FOR DAIRY en Development cation Selection ation COW MILK ADVISORY SERVIC ES KE-VIHIGA COUNTY-179013- CS-CQS / RECRUITMENT OF S Supporting Community-Driv Consultant Qualifi Under Implement IDA / 59000 Post Open - National 49,505.00 0.00 2020-06-21 2020-09-28 2020-07-06 2020-07-20 2020-09-08 2020-07-27 2020-08-17 2021-12-31 ERVICE PROVIDER FOR LOCA en Development cation Selection ation L VEGETABLE VALUE CHAIN A DVISORY SERVICES INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 PROCUREMENT PLAN (Textual Part) Project information: Sao Tome and Principe - WACA Resilience Investment Project - P162337 Project Implementation agency: Ministry of Public Works and Natural Resources, Directorate General of Environment Date of the Procurement Plan: July 2017 Period covered by this Procurement Plan: July 1st 2017 to June 30th, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Regulamento de Licitação e Contratações Publicas such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information.: Not Applicable PROCUREMENT Western and Central Africa : West Africa Coastal Areas Resilience Investment Project PLAN General Information Country: Western and Central Africa 2018-10-04 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162337 GPN Date: 2017-12-29 Project Name: West Africa Coastal Areas Resilience Investment Project Loan / Credit No: IDA / D2880, IDA / 62150, IDA / D2860 Ministry of Environment and Sustainable Development Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MR-MEDD-74186-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2019-07-0 Mise en place d'une clôture g IDA / D2880 National Physical and Social Post Limited 40,000.00 36,168.67 Completed 2018-11-10 2019-11-08 2019-01-05 2019-11-14 tions nvelope 4 rillagée autour de la marre à Investments Spartines MR-MEDD-74202-CW-RFQ / T Component 3: Strengthening ravaux d'entretien des couloi Request for Quota Single Stage - One E 2019-08-2 IDA / D2880 National Physical and Social Post Limited 5,000.00 0.00 Canceled 2018-12-30 2019-02-24 rs de pare-feux du Typha au tions nvelope 3 Investments niveau de Diawling MR-MEDD-74205-CW-RFB / C Component 4: National Coor Single Stage - Two E 2019-08-0 onstruction des sièges de l'O IDA / D2880 Post Request for Bids Open - National 120,000.00 0.00 Canceled 2018-09-03 2018-09-08 2018-10-20 2019-01-02 2019-02-06 dination nvelope 5 bservatoire et de l'UGP MR-MEDD-75955-CW-RFB / C Component 3: Strengthening Single Stage - One E 2019-08-2 olmatage des brèches du litt IDA / D2880 National Physical and Social Post Request for Bids Open - National 400,000.00 0.00 Canceled 2018-11-05 2018-11-10 2018-12-22 2019-01-21 2019-02-25 nvelope 4 oral de NKTT Investments MR-MEDD-75986-CW-RFQ / T Component 3: Strengthening Request for Quota Single Stage - One E Pending Imp 2019-05-3 ravaux pour la fixation des d IDA / D2880 National Physical and Social Post Limited 40,000.00 0.00 2018-10-06 2018-12-01 tions nvelope lementation 0 unes au niveau de Chami Investments MR-MEDD-76006-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Pending Imp 2019-07-1 Restauration des éco-systèm IDA / D2880 National Physical and Social Post Limited 40,000.00 0.00 2018-11-20 2019-01-15 tions nvelope lementation 4 es du Parc National d'Awleiga Investments tt (PNA) MR-MEDD-115356-CW-RFQ / Réalisation de clôture grillag Component 3: Strengthening Request for Quota Single Stage - One E 2019-07-2 ée autour du périmètre de 15 IDA / D2880 National Physical and Social Post Limited 40,000.00 36,467.31 Completed 2019-05-25 2019-06-13 2019-06-10 2019-06-22 tions nvelope 0 ha de fixation mécanique et Investments biologique du cordon dunaire de Nouakchott MR-MEDD-115655-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2019-08-1 Fixation de 15 ha de dunes d IDA / D2880 National Physical and Social Post Limited 40,000.00 36,984.27 Completed 2019-06-01 2019-06-12 2019-06-11 2019-06-29 tions nvelope 0 u littoral de Nouakchott Investments MR-MEDD-115657-CW-RFQ / Component 3: Strengthening Travaux d'entretien de couloi Request for Quota Single Stage - One E 2019-07-1 IDA / D2880 National Physical and Social Post Limited 40,000.00 27,601.13 Signed 2019-05-30 2021-05-19 2019-06-12 2021-05-29 rs de pare-feus pour la resta tions nvelope 2 Investments uration des mangroves au ni veau de Diawling MR-MEDD-115659-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2019-07-2 Réalisation de pépinières de IDA / D2880 National Physical and Social Post Limited 40,000.00 34,921.07 Completed 2019-06-08 2019-07-19 2019-06-21 2019-08-02 tions nvelope 1 mangroves au Diawling Investments MR-MEDD-124501-CW-RFQ / Component 3: Strengthening mise en place d'une cloture Request for Quota Single Stage - One E 2020-04-1 IDA / D2880 National Physical and Social Post Limited 10,000.00 8,464.35 Completed 2019-08-26 2019-07-25 2019-10-21 2019-08-03 de protectionsur les 2 ha de tions nvelope 8 Investments dunes fixées au PND MR-MEDD-124500-GO-RFQ / Component 3: Strengthening mise en place de clotures po Request for Quota Single Stage - One E Pending Imp 2020-04-1 IDA / D2880 National Physical and Social Post Limited 42,000.00 0.00 2019-09-07 2019-10-19 ur abriter les pépinières de m tions nvelope lementation 6 Investments angroves au PND MR-MEDD-129309-CW-RFQ / Component 3: Strengthening Clôture grillagée pour la prot Request for Quota Single Stage - One E 2020-04-3 IDA / D2880 National Physical and Social Post Limited 40,000.00 36,983.98 Completed 2019-09-07 2019-09-13 2019-11-02 2019-09-18 ection d'une fixation de dune tions nvelope 0 Investments s de 15 ha du littoral de Nou akchott MR-MEDD-137084-CW-RFQ / Component 1: Strengthening Request for Quota Single Stage - One E 2019-11-1 Mise en place de couloirs de IDA / D2880 Post Limited 30,000.00 28,650.24 Completed 2019-10-06 2020-03-13 2019-10-16 2020-03-07 Regional Integration tions nvelope 5 pare-feux de Typha au nivea u du Diawling MR-MEDD-137891-CW-DIR / Component 3: Strengthening Renforcement de la résilienc 2020-01-0 IDA / D2880 National Physical and Social Post Direct Selection Direct 42,000.00 0.00 Canceled 2019-10-02 2019-10-04 2019-10-04 e des communautés et des é 2 Investments cosystèmes de Ndiago. MR-MEDD-156359-CW-RFQ / Mise en place d'une clôture g Component 3: Strengthening Request for Quota Single Stage - One E Pending Imp 2020-04-1 rillagée autour de la marre à IDA / D2880 National Physical and Social Post Limited 38,500.00 0.00 2020-02-10 2020-03-05 tions nvelope lementation 9 Spartine à la Baie de l'Etoile Investments de Nouadhibou (phase II) MR-MEDD-170442-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2020-11-0 Construction de Loges des ag IDA / D2880 National Physical and Social Post Limited 30,000.00 24,963.37 Completed 2020-05-13 2019-09-19 2020-07-08 2019-09-28 tions nvelope 5 ents de surveillance Investments MR-MEDD-170443-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2020-11-0 Travaux de fixation des dune IDA / D2880 National Physical and Social Post Limited 40,000.00 37,972.83 Signed 2020-06-13 2019-04-01 2020-08-08 2019-04-17 tions nvelope 6 s au diawling Investments MR-MEDD-170445-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Pending Imp 2020-10-1 Clôture grillagée fixation du IDA / D2880 National Physical and Social Post Limited 40,000.00 0.00 2020-05-14 2020-07-09 tions nvelope lementation 7 nes au Diawling Investments MR-MEDD-170447-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2021-02-1 Travaux de coupe de typha a IDA / D2880 National Physical and Social Post Limited 40,000.00 33,708.59 Completed 2020-06-24 2020-03-05 2020-08-19 2020-03-24 tions nvelope 5 u Parc National du Diawling Investments Page 1 MR-MEDD-170449-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2020-10-0 Mise en place de pépinière d IDA / D2880 National Physical and Social Post Limited 35,000.00 29,996.09 Completed 2020-06-24 2020-03-10 2020-08-19 2020-03-26 tions nvelope 3 e mangroves au Diawling Investments MR-MEDD-170453-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2020-11-1 clôture pour protéger les pla IDA / D2880 National Physical and Social Post Limited 38,000.00 24,131.97 Completed 2020-06-13 2020-06-05 2020-08-08 2020-06-24 tions nvelope 6 ntations de mangroves au Di Investments awling Component 3: Strengthening MR-MEDD-170456-CW-RFQ / Request for Quota Single Stage - One E 2020-11-0 IDA / D2880 National Physical and Social Post Limited 30,000.00 14,446.54 Completed 2020-07-16 2020-07-10 2020-09-10 2020-07-25 Plantation de mangroves tions nvelope 9 Investments MR-MEDD-170457-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2020-10-0 Travaux d’entretien des coul IDA / D2880 National Physical and Social Post Limited 32,000.00 22,783.70 Completed 2020-05-15 2021-07-08 2020-07-10 2021-07-30 tions nvelope 8 oirs et de coupe de Typha dé Investments jà réalisés MR-MEDD-178901-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2020-07-2 Entretien des claies et du reb IDA / D2880 National Physical and Social Post Limited 20,000.00 16,815.78 Completed 2020-06-15 2020-06-23 2020-06-28 2020-07-11 tions nvelope 8 oisement (au niveau du PND) Investments MR-MEDD-200677-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2021-02-2 Construction d’un poste de s IDA / D2880 National Physical and Social Post Limited 40,000.00 34,654.84 Signed 2020-11-15 2020-10-26 2021-01-10 2020-12-12 tions nvelope 4 urveillance au PND Investments MR-MEDD-200725-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2021-04-1 Mise en place d’une pépinièr IDA / D2880 National Physical and Social Post Limited 20,000.00 16,021.62 Completed 2020-11-22 2020-10-26 2021-01-17 2020-11-12 tions nvelope 7 e d’Acacias Investments MR-MEDD-200729-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2021-05-1 Entretien des travaux et coul IDA / D2880 National Physical and Social Post Limited 32,000.00 30,347.33 Completed 2020-12-21 2020-05-13 2021-02-15 2020-04-07 tions nvelope 6 oirs déjà réalisés Investments MR-MEDD-200730-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2021-04-2 Entretien de 15 ha coupés en IDA / D2880 National Physical and Social Post Limited 20,000.00 18,441.49 Completed 2020-11-25 2020-10-23 2021-01-20 2020-11-12 tions nvelope 0 2020 Investments MR-MEDD-200733-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Pending Imp 2021-05-2 Coupe de 50 ha de Typha da IDA / D2880 National Physical and Social Post Limited 40,000.00 0.00 2020-12-26 2021-02-20 tions nvelope lementation 1 ns le bassin de BELL Investments MR-MEDD-225606-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Pending Imp 2021-06-3 Entretien des sites de pépini IDA / D2880 National Physical and Social Post Limited 35,000.00 0.00 2021-03-27 2021-05-16 tions nvelope lementation 0 ères mangroves Investments MR-MEDD-225608-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2021-06-0 Clôture de plantations de ma IDA / D2880 National Physical and Social Post Limited 38,000.00 57,763.54 Completed 2021-04-03 2021-03-26 2021-05-09 2021-04-02 tions nvelope 8 ngroves Investments MR-MEDD-225609-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2021-06-0 Reboisement des zones de m IDA / D2880 National Physical and Social Post Limited 30,000.00 15,365.45 Completed 2021-04-10 2021-06-10 2021-05-30 2020-07-25 tions nvelope 2 angroves Investments MR-MEDD-170569-CW-RFB / Component 3: Strengthening Open - Internationa Single Stage - One E 2022-01-2 Travaux pour le colmatage d IDA / D2880 National Physical and Social Post Request for Bids 600,000.00 0.00 Canceled 2020-10-12 2020-10-17 2020-11-28 2020-12-28 2021-02-01 l nvelope 9 es brèches Investments MR-MEDD-170571-CW-RFB / Travaux pour la réalisation d Component 3: Strengthening Single Stage - One E 2021-09-0 e passages de franchissemen IDA / D2880 National Physical and Social Post Request for Bids Open - National 100,000.00 0.00 Canceled 2020-11-16 2020-11-21 2021-01-02 2021-02-01 2021-03-08 nvelope 4 t du cordon dunaire et équip Investments ement des passages piétons MR-MEDD-75953-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2019-08-1 Mise en place de de bacs à fl IDA / D2880 National Physical and Social Post Limited 35,000.00 0.00 Canceled 2018-12-17 2019-02-11 tions nvelope 0 eurs pour la sécurisation du li Investments ttoral MR-MEDD-74188-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2019-07-1 Aménagement du site de l'éc IDA / D2880 National Physical and Social Post Limited 24,000.00 0.00 Canceled 2018-11-20 2019-01-15 tions nvelope 4 o-loge Investments MR-MEDD-75993-CW-RFQ / T ravaux de restauration des p Component 3: Strengthening Request for Quota Single Stage - One E 2019-07-2 aysages des carrières de coq IDA / D2880 National Physical and Social Post Limited 35,000.00 0.00 Canceled 2018-12-05 2019-01-30 tions nvelope 9 uillages en frange continenta Investments le du cordon dunaire du littor al MR-MEDD-74189-CW-RFQ / T Component 3: Strengthening Request for Quota Single Stage - One E 2019-10-0 ravaux de construction de l'é IDA / D2880 National Physical and Social Post Limited 35,000.00 0.00 Canceled 2019-02-09 2019-04-06 tions nvelope 3 co-loge Investments MR-MEDD-82725-CW-RFQ / Component 2: Strengthening mise en place d'une pépinièr Request for Quota Single Stage - One E 2019-06-2 IDA / D2880 the Policy and Institutional F Post Limited 40,000.00 0.00 Canceled 2018-10-27 2018-12-22 e pour les besoins de la fixati tions nvelope 0 ramework on des dunes du littoral MR-MEDD-200772-CW-RFB / Component 3: Strengthening Single Stage - One E 2022-04-2 Travaux de construction du si IDA / D2880 National Physical and Social Post Request for Bids Open - National 300,570.00 0.00 Canceled 2020-12-30 2021-01-04 2021-02-15 2021-03-17 2021-04-21 nvelope 1 ège de l'Observatoire Nation Investments al du Littoral MR-MEDD-170440-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E 2020-09-1 Confection et mise en place IDA / D2880 National Physical and Social Post Limited 35,000.00 0.00 Canceled 2020-05-26 2020-07-21 tions nvelope 9 de bacs pour la sécurisation Investments du littoral MR-MEDD-75951-CW-RFQ / T Component 3: Strengthening Request for Quota Single Stage - One E 2019-09-0 ravaux pour passages de piét IDA / D2880 National Physical and Social Post Limited 40,000.00 0.00 Canceled 2019-01-15 2019-03-12 tions nvelope 8 ons sur le cordon dunaire de Investments NKTT MR-MEDD-232482-CW-RFQ / Component 3: Strengthening Request for Quota Request for Quota Single Stage - One E Pending Imp 2021-12-1 Entretenir les claies de fixati IDA / D2880 National Physical and Social Post Limited tions (Non Bank-S 40,000.00 0.00 2021-07-17 2021-09-11 tions nvelope lementation 0 ons des dunes et les bacs de Investments PD) protection MR-MEDD-232486-CW-RFQ / Component 3: Strengthening Request for Quota Faire une clôture grillagée au Request for Quota Single Stage - One E 2021-12-0 IDA / D2880 National Physical and Social Post Limited tions (Non Bank-S 40,000.00 37,285.56 Completed 2021-07-10 2021-06-22 2021-09-04 2021-06-30 tour des sites fixés (fixation b tions nvelope 3 Investments PD) iologique) du cordon dunaire MR-MEDD-232488-CW-RFQ / Component 3: Strengthening Request for Quota Request for Quota Single Stage - One E 2021-10-2 Reboisement de 10000 plant IDA / D2880 National Physical and Social Post Limited tions (Non Bank-S 30,000.00 24,081.68 Signed 2021-06-27 2021-07-29 2021-08-22 2021-08-07 tions nvelope 1 s d’Acacia tortilles au PND Investments PD) Page 2 Request for Bids - MR-MEDD-232508-CW-RFB / Component 3: Strengthening Single Stage - One E Works (without pr 2023-03-0 Réaliser les travaux de colma IDA / D2880 National Physical and Social Post Request for Bids Open - National 360,000.00 337,223.98 Signed 2021-11-15 2021-06-28 2021-11-20 2022-01-01 2021-07-30 2022-01-31 2021-08-17 2022-03-07 2021-10-26 nvelope equalification) SP 7 tage des 3 brèches (9, 13 et Investments D 16) MR-MEDD-232510-CW-RFB / Request for Bids - Réaliser les travaux pour le p Component 3: Strengthening Single Stage - One E Small Works SPD 2023-03-0 assage de franchissement du IDA / D2880 National Physical and Social Post Request for Bids Open - National 150,000.00 0.00 Canceled 2021-11-15 2021-11-20 2022-01-01 2022-01-31 2022-03-07 nvelope (1 envelope proce 7 cordon dunaire et équipemen Investments ss) t pour le passage piéton MR-MEDD-232489-CW-RFQ / Component 3: Strengthening Request for Quota Entretenir les travaux, les co Request for Quota Single Stage - One E 2021-12-1 IDA / D2880 National Physical and Social Post Limited tions (Non Bank-S 45,000.00 18,689.53 Signed 2021-07-19 2021-07-08 2021-09-13 2021-07-15 uloirs de pare-feu, les claies tions nvelope 2 Investments PD) et le reboisement réalisés en 2020 au PND National Procure MR-MEDD-232511-CW-RFB / Component 3: Strengthening ment Document - Réhabiliter les bacs existants Single Stage - One E 2023-01-0 IDA / D2880 National Physical and Social Post Request for Bids Open - National 1 Envelope proce 140,000.00 0.00 Canceled 2021-09-16 2021-09-21 2021-11-02 2021-12-02 2022-01-06 et faire l'extension pour la sé nvelope 3 Investments ss (Non Bank-SPD curisation du cordon dunaire ) du littoral MR-MEDD-75980-CW-RFQ / T Component 3: Strengthening Request for Quota Single Stage - One E 2019-06-1 ravaux de fixation de dunes IDA / D2880 National Physical and Social Post Limited 42,000.00 0.00 Canceled 2018-10-20 2018-12-15 tions nvelope 3 du littoral de NKTT sur un pre Investments mier site pilote National Procure MR-MEDD-232506-CW-RFB / Component 2: Strengthening ment Document - Single Stage - One E 2023-02-0 Construire le siège de l'obser IDA / D2880 the Policy and Institutional F Post Request for Bids Open - National 1 Envelope proce 144,570.00 0.00 Canceled 2021-10-15 2021-10-20 2021-12-01 2021-12-31 2022-02-04 nvelope 1 vatoire du littoral ramework ss (Non Bank-SPD ) MR-MEDD-262950-CW-RFQ / Component 3: Strengthening Request for Quota Request for Quota Single Stage - One E 2022-03-0 Travaux de fixation des dune IDA / D2880 National Physical and Social Post Limited tions (Non Bank-S 40,000.00 39,933.80 Signed 2021-11-27 2021-11-17 2022-01-16 2021-12-26 tions nvelope 2 s du Parc National de Diawlin Investments PD) g (Année 2021) Request for Bids - MR-MEDD-315492-CW-RFB / Component 3: Strengthening Single Stage - One E Works (without pr Pending Imp 2023-06-1 Réalisation des travaux pour IDA / D2880 National Physical and Social Post Request for Bids Open - National 100,000.00 0.00 2022-10-25 2022-10-30 2022-12-11 2023-01-10 2023-02-14 nvelope equalification) SP lementation 4 la fixation des dunes du littor Investments D al MR-MEDD-232485-CW-RFQ / Component 3: Strengthening Request for Quota Request for Quota Single Stage - One E 2021-11-1 Réaliser les travaux de fixati IDA / D2880 National Physical and Social Post Limited tions (Non Bank-S 40,000.00 0.00 Canceled 2021-06-27 2021-08-16 tions nvelope 4 on des dunes Investments PD) MR-MEDD-170567-CW-RFB / Component 2: Strengthening Open - Internationa Single Stage - One E 2022-05-0 IDA / D2880 Post Request for Bids 120,000.00 0.00 Canceled 2021-01-04 2021-01-19 2021-03-02 2021-04-01 2021-05-06 Travaux de fixation de dunes the Policy and Institutional F l nvelope 3 du littoral ramework MR-MEDD-170572-CW-RFB / Component 3: Strengthening Travaux de réhabilitation et e 2021-05-2 IDA / D2880 National Physical and Social Post Request for Bids Open - National 120,000.00 0.00 Canceled 2020-08-10 2020-09-09 2020-10-09 2020-10-29 2020-11-28 xtension de la digue Nord du 7 Investments Parc National du Diawling (P ND) Request for Quota MR-MEDD-315487-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E tions - Small Work 2023-07-0 Mise en place des couloirs d IDA / D2880 National Physical and Social Post Open - National 20,000.00 0.00 Canceled 2022-11-08 2023-01-03 tions nvelope s (Emergency) SP 2 e pares feux dans le typha a Investments D -Competitive u PND (2km) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74169-GO-RFQ / A Component 2: Strengthening cquisition d'équipements de Request for Quota Single Stage - One E IDA / D2880 the Policy and Institutional F Post Limited 30,000.00 1,680.00 Completed 2018-10-06 2019-07-22 2018-12-01 2019-07-25 2019-05-30 2019-08-30 bureaux au profit de l'Autorit tions nvelope ramework é de la Zone franche de NDB MR-MEDD-74201-GO-RFQ / A Component 3: Strengthening cquisition de matériel pour la Request for Quota Single Stage - One E IDA / D2880 National Physical and Social Post Limited 5,000.00 0.00 Canceled 2018-12-01 2019-01-26 2019-07-25 surveillance des investissem tions nvelope Investments ents physiques pour Diawling MR-MEDD-74203-GO-RFQ / A Component 3: Strengthening cquisition d'équipement pour Request for Quota Single Stage - One E Pending Impl IDA / D2880 National Physical and Social Post Limited 10,000.00 0.00 2018-10-06 2018-12-01 2019-05-30 l'observatoire ornithologique tions nvelope ementation Investments au niveau de Diawling MR-MEDD-74204-GO-RFB / A Component 4: National Coor Single Stage - One E IDA / D2880 Post Request for Bids Open - National 140,000.00 91,573.20 Signed 2018-08-30 2018-12-27 2018-09-04 2018-10-16 2019-02-07 2018-11-15 2019-02-20 2018-12-20 2020-06-21 2019-06-18 chat de véhicule dination nvelope MR-MEDD-75977-GO-RFQ / A Component 2: Strengthening cquisition d'équipements de Request for Quota Single Stage - One E IDA / D2880 the Policy and Institutional F Post Limited 40,000.00 0.00 Canceled 2018-10-30 2018-12-25 2019-06-23 surveillance et de secourism tions nvelope ramework e au profit de la Direction de la Protection Civile MR-MEDD-75990-GO-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Mise en place de pépinières IDA / D2880 National Physical and Social Post Limited 40,000.00 0.00 Canceled 2018-11-10 2019-01-05 2019-07-04 tions nvelope de mangroves à Nouamghar Investments MR-MEDD-75995-GO-RFQ / A Component 2: Strengthening cquisition d'équipements pou Request for Quota Single Stage - One E Pending Impl IDA / D2880 the Policy and Institutional F Post Limited 30,000.00 0.00 2018-12-10 2019-02-04 2019-08-03 r le réseau des Parlementaire tions nvelope ementation ramework s et élus locaux de l'environn ement MR-MEDD-75997-GO-RFQ / A Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl cquisition de matériel pour la IDA / D2880 the Policy and Institutional F Post Limited 20,000.00 0.00 2018-12-04 2019-01-29 2019-07-28 tions nvelope ementation coordination du Master Gaed ramework MR-MEDD-75998-GO-RFQ / A Component 2: Strengthening cquisition d'équipements pou Request for Quota Single Stage - One E Pending Impl IDA / D2880 the Policy and Institutional F Post Limited 30,000.00 0.00 2018-11-04 2018-12-30 2019-06-28 r l'opérationnalisation de la b tions nvelope ementation ramework ase de données du MEED MR-MEDD-76001-GO-RFQ / A Component 2: Strengthening cquisition d'équipements pou Request for Quota Single Stage - One E IDA / D2880 the Policy and Institutional F Post Limited 30,000.00 26,828.15 Completed 2018-11-04 2020-08-17 2018-12-30 2020-10-02 2019-06-28 2021-01-14 r le laboratoire des études en tions nvelope ramework vironnementales et de géogr aphie (LEERG) MR-MEDD-76866-GO-RFQ / A Component 3: Strengthening Request for Quota Single Stage - One E cquisition de matériel pour le IDA / D2880 National Physical and Social Post Open - National 40,000.00 0.00 Canceled 2018-10-15 2018-12-10 2019-06-08 tions nvelope s AGR Investments Page 3 MR-MEDD-124789-GO-RFQ / impression de cartes de distri Component 3: Strengthening Request for Quota Single Stage - One E butions des formations de m IDA / D2880 National Physical and Social Post Limited 20,000.00 16,666.67 Completed 2019-08-26 2019-12-09 2019-10-21 2019-12-18 2020-04-18 2020-01-14 tions nvelope angroves du BAS DELTA DU F Investments LEUVE SENEGAL rive droite. MR-MEDD-170370-GO-RFQ / Component 2: Strengthening Équipements au profit des D Request for Quota Single Stage - One E IDA / D2880 the Policy and Institutional F Post Limited 20,000.00 0.00 Canceled 2020-05-15 2020-07-10 2020-08-09 élégations Régionales de l'En tions nvelope ramework vironnement (littoral) MR-MEDD-170397-GO-RFQ / Component 2: Strengthening Acquisition d'équipement de Request for Quota Single Stage - One E Pending Impl IDA / D2880 the Policy and Institutional F Post Limited 10,000.00 0.00 2020-08-25 2020-10-20 2020-12-04 bureau au profit de l'autorité tions nvelope ementation ramework de la zone franche MR-MEDD-170462-GO-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E Acquisition d'équipements au IDA / D2880 the Policy and Institutional F Post Limited 40,000.00 34,879.93 Completed 2020-08-23 2020-08-24 2020-10-18 2020-09-09 2021-04-16 2020-09-15 tions nvelope profit de la DAPL/MEDD ramework MR-MEDD-172830-GO-DIR / l Component 4: National Coor IDA / D2880 Post Direct Selection Direct 15,000.00 9,469.23 Signed 2020-08-10 2021-08-06 2020-08-15 2021-07-28 2020-09-19 2021-07-29 2020-09-28 ogiciel gestion suivi-évaluatio dination n (RUCH) MR-MEDD-200669-GO-RFQ / Acquisition d’équipements a Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl u profit de la Délégation Gé IDA / D2880 the Policy and Institutional F Post Limited 14,286.00 0.00 2020-11-10 2021-01-05 2021-02-19 tions nvelope ementation nérale de la Sécurité Civile et ramework de la Gestion des Crises au M IDEC MR-MEDD-200671-GO-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl Acquisition d’équipements a IDA / D2880 the Policy and Institutional F Post Limited 40,000.00 0.00 2020-11-10 2021-01-05 2021-02-19 tions nvelope ementation u profit de l’ONM ramework MR-MEDD-200683-GO-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E Acquisition de matériel optiq IDA / D2880 the Policy and Institutional F Post Limited 40,000.00 35,730.93 Completed 2020-11-28 2020-10-26 2021-01-23 2020-11-12 2021-03-09 2020-12-16 tions nvelope ue pour l’Observatoire du PN ramework D MR-MEDD-200687-GO-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl Acquisition d’un Drone équip IDA / D2880 the Policy and Institutional F Post Limited 2,500.00 0.00 2020-11-28 2021-01-23 2026-01-01 tions nvelope ementation é au profit du PND ramework MR-MEDD-221606-GO-RFQ / Acquisition de deux zodiacs é Component 3: Strengthening Request for Quota Single Stage - One E quipés de tous ses accessoir IDA / D2880 National Physical and Social Post Limited 16,000.00 9,675.19 Signed 2021-02-28 2021-03-04 2021-03-21 2021-03-09 2021-04-20 2021-03-17 tions nvelope es, gonflables, avec moteur à Investments bord capable de transporter 5 personnes MR-MEDD-221613-GO-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Acquisition de deux drones é IDA / D2880 National Physical and Social Post Limited 5,000.00 8,016.59 Completed 2021-02-28 2021-03-04 2021-03-21 2021-03-09 2021-04-11 2021-03-17 tions nvelope quipés au profit du PND Investments MR-MEDD-225619-GO-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E Equipement de la salle de ré IDA / D2880 the Policy and Institutional F Post Limited 30,000.00 350,844.75 Completed 2021-04-04 2021-02-01 2021-05-24 2021-02-13 2021-07-08 2021-03-16 tions nvelope union du MEDD ramework MR-MEDD-172827-GO-RFB / Component 2: Strengthening Acquisition d'équipements de Open - Internationa Single Stage - One E IDA / D2880 the Policy and Institutional F Post Request for Bids 100,000.00 0.00 Canceled 2020-08-18 2020-08-23 2020-10-04 2020-11-03 2020-12-08 2021-06-06 surveillance et de secourism l nvelope ramework e au profit de la Direction de la Protection Civile MR-MEDD-200771-GO-RFB / Acquisition d'une ambulance Component 2: Strengthening Single Stage - One E équipée au Profit de la Délég IDA / 62150 the Policy and Institutional F Post Request for Bids Open - National 85,714.00 0.00 Canceled 2020-11-30 2020-12-05 2021-01-16 2021-02-15 2021-03-22 2021-03-26 nvelope ation Générale de la sécurité ramework Civile et de la Gestion des cr ises au MIDEC MR-MEDD-200663-GO-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E Acquisition d’équipements a IDA / D2880 the Policy and Institutional F Post Limited 40,000.00 0.00 Canceled 2020-11-04 2020-12-30 2021-02-13 tions nvelope u profit de la Police Environn ramework ementale MR-MEDD-75959-GO-RFQ / A Component 2: Strengthening cquisition d'équipements pou Request for Quota Single Stage - One E IDA / D2880 the Policy and Institutional F Post Limited 20,000.00 0.00 Canceled 2018-12-10 2019-02-04 2019-08-03 r l'observatoire national du lit tions nvelope ramework toral mauritanien MR-MEDD-170405-GO-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E Acquisition de matériel pour l IDA / D2880 the Policy and Institutional F Post Limited 5,000.00 0.00 Canceled 2020-06-16 2020-08-11 2020-09-25 tions nvelope a coordination du Master GA ramework ED MR-MEDD-75978-GO-RFQ / A Component 2: Strengthening Request for Quota Single Stage - One E cquisition d'équipements au IDA / D2880 the Policy and Institutional F Post Limited 40,000.00 0.00 Canceled 2018-10-20 2018-12-15 2019-06-13 tions nvelope profit de l'ONM ramework MR-MEDD-75988-GO-RFQ / A Component 3: Strengthening Request for Quota Single Stage - One E cquisition d'équipements pou IDA / D2880 National Physical and Social Post Limited 20,000.00 0.00 Canceled 2018-11-20 2019-01-15 2019-07-14 tions nvelope r la fixation des dunes au niv Investments eau de Chami MR-MEDD-74196-GO-RFQ / A Component 3: Strengthening Request for Quota Single Stage - One E chat de plants pour la fixatio IDA / D2880 National Physical and Social Post Limited 40,000.00 0.00 Canceled 2018-11-25 2019-01-20 2019-07-19 tions nvelope n biologique du cordon dunai Investments re de Diawling MR-MEDD-200674-GO-RFQ / Component 2: Strengthening Acquisition d’équipements a Request for Quota Single Stage - One E IDA / D2880 the Policy and Institutional F Post Limited 20,000.00 0.00 Canceled 2020-11-15 2021-01-10 2021-07-09 u profit du Port Autonome de tions nvelope ramework Nouakchott, dit Port de l’Amit ié (PAN – PA) MR-MEDD-74193-GO-RFQ / A Component 3: Strengthening cquisition d'équipements et d Request for Quota Single Stage - One E IDA / D2880 National Physical and Social Post Limited 40,000.00 0.00 Canceled 2018-10-13 2018-12-08 2019-06-06 e matériels de protection du tions nvelope Investments cordon dunaire de Diawling MR-MEDD-75979-GO-RFQ / A Component 2: Strengthening Request for Quota Single Stage - One E cquisition d'équipements pou IDA / D2880 the Policy and Institutional F Post Limited 40,000.00 0.00 Canceled 2018-11-20 2019-01-15 2019-07-14 tions nvelope r l'opérationnalisation du pla ramework n POLMAR MR-MEDD-75952-GO-RFQ / E Component 3: Strengthening quipements pour passages d Request for Quota Single Stage - One E IDA / D2880 National Physical and Social Post Limited 30,000.00 0.00 Canceled 2019-01-20 2019-03-17 2019-09-13 e franchissement du cordon tions nvelope Investments dunaire de NKTT Page 4 MR-MEDD-200694-GO-RFQ / Component 2: Strengthening Acquisition de stations de me Request for Quota Single Stage - One E IDA / D2880 the Policy and Institutional F Post Limited 25,000.00 0.00 Canceled 2020-11-28 2021-01-23 2021-03-09 sures topographiques et de G tions nvelope ramework PS différentiels au profit de la DPREM MR-MEDD-170352-GO-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E Équipement du centre de doc IDA / D2880 the Policy and Institutional F Post Limited 20,000.00 0.00 Canceled 2020-07-01 2020-08-26 2020-10-10 tions nvelope umentation électronique de l ramework a CNOEZA MR-MEDD-232476-GO-RFQ / Acquisition des équipements Component 2: Strengthening Request for Quota Single Stage - One E pour les Délégations Régiona IDA / D2880 the Policy and Institutional F Post Limited 40,000.00 35,818.73 Completed 2021-06-20 2021-07-05 2021-08-09 2021-07-09 2021-08-12 2021-09-02 tions nvelope les de l'Environnement (NDB, ramework INCHIRI, NKTT NORD ET TRA RZA) MR-MEDD-238152-CW-RFQ / Component 2: Strengthening panneaux de signalisation su Request for Quota Single Stage - One E IDA / D2880 the Policy and Institutional F Post Limited 20,000.00 19,304.00 Completed 2021-08-15 2021-05-17 2021-10-10 2021-05-25 2022-04-08 2021-05-25 r les principaux sites du proje tions nvelope ramework t au niveau du littoral de Nouakch ott MR-MEDD-232502-GO-RFB / Acquisition de 7 véhicules au Component 2: Strengthening Single Stage - One E profit des Délégations Région IDA / D2880 the Policy and Institutional F Post Request for Bids Open - National 300,000.00 0.00 Canceled 2021-07-20 2021-07-25 2021-09-05 2021-10-05 2021-11-09 2022-03-09 nvelope ales de l'environnement : ND ramework B, INCHIRI, NKTT ET TRARZA, et du Cabinet du MEDD MR-MEDD-249413-GO-RFB / Component 2: Strengthening Acquisition d'une station mét Single Stage - One E IDA / D2880 the Policy and Institutional F Post Request for Bids Open - National 180,000.00 0.00 Signed 2021-10-12 2021-10-27 2021-10-17 2021-11-28 2021-11-30 2021-12-28 2021-12-29 2022-02-01 2022-06-01 éorologique au profit de l'Offi nvelope ramework ce National de la Météorologi e MR-MEDD-249415-GO-RFQ / Component 3: Strengthening Acquisition d'un groupe élect Request for Quota Single Stage - One E IDA / D2880 National Physical and Social Post Limited 50,000.00 37,313.33 Signed 2021-10-23 2021-09-01 2021-12-18 2021-09-23 2022-03-18 rogène pour la base de vie d tions nvelope Investments u Parc National de Diawling ( PND) MR-MEDD-249410-GO-DIR / Acquisition de 7 véhicules au Component 2: Strengthening profit des Délégations Région IDA / D2880 the Policy and Institutional F Post Direct Selection Direct 300,000.00 195,982.29 Signed 2021-09-22 2021-11-04 2021-09-27 2021-09-09 2021-11-01 2021-11-17 2021-12-16 ales de l'environnement : ND ramework B, INCHIRI, NKTT ET TRARZA, et du Cabinet du MEDD MR-MEDD-267607-GO-RFQ / Component 2: Strengthening Acquisition des équipements Request for Quota Single Stage - One E IDA / D2880 the Policy and Institutional F Post Limited 40,000.00 0.00 Canceled 2022-01-22 2022-03-19 2022-05-18 pour la Direction Régionale d tions nvelope ramework e l'Environnement et du Dév eloppement Durable MR-MEDD-315486-GO-RFB / Acquisition de matériels info rmatiques et de mobiliers de Component 2: Strengthening Single Stage - One E Pending Impl bureau en deux lots distincts IDA / D2880 the Policy and Institutional F Post Request for Bids Open - National 43,000.00 0.00 2022-10-17 2022-10-22 2022-12-03 2023-01-02 2023-02-06 2023-05-07 nvelope ementation pour deux délégations région ramework ales de l'Environnement : (D REDD NCHIRI et TRARZA), et le MEDD MR-MEDD-315580-GO-RFQ / Acquisition d'équipements d Component 2: Strengthening Request for Quota Single Stage - One E e GPS, appareils photos, jum IDA / D2880 the Policy and Institutional F Post Limited 15,000.00 0.00 Completed 2022-11-19 2022-10-31 2023-01-14 2023-03-15 2023-02-17 tions nvelope elles, matraques, bottes de s ramework écurité pour le Bureau de Sur veillance du littoral MR-MEDD-317823-GO-RFQ / Achat de mobilier et matériel Component 4: National Coor Request for Quota Single Stage - One E IDA / D2880 Post Limited 17,500.00 0.00 Signed 2022-10-15 2022-11-30 2022-12-10 2023-01-24 de bureau pour l'Unité de Ge dination tions nvelope stion du Projet WACA-MR MR-MEDD-249412-GO-RFB / Component 2: Strengthening Single Stage - One E Pending Impl Acquisition des équipements IDA / D2880 the Policy and Institutional F Post Request for Bids Open - National 60,000.00 0.00 2023-06-12 2023-06-17 2023-07-29 2023-08-28 2023-10-02 2023-12-01 nvelope ementation pour la police environnement ramework ale MR-MEDD-315478-GO-RFQ / Acquisition des moyens de m Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl obilité ( 4 quads et 4 VTT) po IDA / D2880 National Physical and Social Post Open - National 45,000.00 0.00 2023-05-30 2023-08-14 2023-09-28 tions nvelope ementation ur le bureau de surveillance Investments du littoral (Nouakchott) MR-MEDD-315482-GO-RFB / Component 2: Strengthening Acquisition de cinq (05) lod Single Stage - One E IDA / D2880 the Policy and Institutional F Post Request for Bids Open - National 55,000.00 0.00 Canceled 2022-10-17 2022-10-22 2022-12-03 2023-01-02 2023-02-06 2023-06-06 ges équipées au profit du bur nvelope ramework eau de Surveillance du littora l de Nouakchott NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74195-NC-RFQ / C Component 3: Strengthening ollecte et transport sur sites Request for Quota Single Stage - One E IDA / D2880 National Physical and Social Post Limited 40,000.00 0.00 Canceled 2018-11-13 2019-04-02 2019-01-08 2019-07-07 de matériaux de fixation méc tions nvelope Investments anique de dunes au niveau d e Diawling MR-MEDD-170490-NC-RFQ / Component 4: National Coor Request for Quota Single Stage - One E IDA / D2880 Post Limited 25,000.00 18,116.74 Signed 2020-05-15 2020-03-05 2020-07-10 2020-03-12 2021-07-07 Maintenance et suivi informa dination tions nvelope tique MR-MEDD-200678-NC-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E IDA / D2880 Post Limited 38,000.00 0.00 Canceled 2020-11-28 2021-01-23 2021-03-09 Nettoyage de 35 villages au the Policy and Institutional F tions nvelope PND ramework MR-MEDD-232496-NC-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Recruter une ONG facilitatric IDA / D2880 National Physical and Social Post Open - National 35,000.00 0.00 Canceled 2021-07-28 2021-10-22 2022-10-19 tions nvelope e du MGP Investments MR-MEDD-170472-NC-DIR / Component 3: Strengthening Opérationnalisation du méca IDA / D2880 National Physical and Social Post Direct Selection Direct 34,000.00 0.00 Canceled 2020-06-23 2020-07-08 2020-08-12 2021-02-08 nisme de gestion de plaintes Investments (MGP) MR-MEDD-315579-CS-INDV / Component 3: Strengthening La traduction, multiplication Request for Quota Single Stage - One E Pending Impl IDA / D2880 National Physical and Social Post Limited 2,000.00 0.00 2022-10-22 2022-12-11 2023-01-10 et mise à disposition des outi tions nvelope ementation Investments ls (référentiel et fiches) en ar abe et français Page 5 MR-MEDD-351201-NC-RFQ / Un prestataire de service pou Component 4: National Coor Request for Quota Single Stage - One E Pending Impl IDA / D2880 Post Limited 5,800.00 0.00 2023-06-10 2023-08-05 2024-08-04 r la Maintenance informatiqu dination tions nvelope ementation e du Projet WACA-MR CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74182-CS-QCBS / Component 2: Strengthening Consultant Qualifi Elaboration de la directive d' IDA / D2880 the Policy and Institutional F Post Open - National 40,000.00 0.00 Canceled 2018-09-25 2018-10-16 2018-11-29 2018-12-29 2019-02-02 2019-08-01 cation Selection aménagement du littoral de ramework NDB MR-MEDD-74184-CS-QCBS / Component 2: Strengthening Consultant Qualifi Etude sur le classement de la IDA / D2880 the Policy and Institutional F Post Open - National 40,000.00 38,055.67 Signed 2018-09-20 2018-10-08 2018-10-11 2018-11-24 2018-10-16 2018-12-24 2019-10-19 2019-01-28 2018-10-21 2019-07-27 cation Selection Baie de l'Etoile de NDB ramework MR-MEDD-74207-CS-QCBS / Analyse du rapport EIE du pr Component 2: Strengthening Consultant Qualifi ojet Ahmeyin/Guembeul pour IDA / D2880 the Policy and Institutional F Post Open - National 35,000.00 0.00 Canceled 2018-09-05 2018-09-26 2018-11-09 2018-12-09 2019-01-13 2019-07-12 cation Selection la production de gaz offshore ramework en Mauritanie et au Sénégal MR-MEDD-75957-CS-QCBS / Component 2: Strengthening Consultant Qualifi Evaluation des risques liés au IDA / D2880 the Policy and Institutional F Post Open - National 40,000.00 0.00 Canceled 2018-09-20 2018-10-11 2018-11-24 2018-12-24 2019-01-28 2019-07-27 cation Selection x inondations de la ville de N ramework KTT MR-MEDD-75958-CS-QCBS / Component 2: Strengthening Consultant Qualifi Elaboration de la directive d' IDA / D2880 the Policy and Institutional F Post Open - National 40,000.00 0.00 Canceled 2018-09-28 2018-10-19 2018-12-02 2019-01-01 2019-02-05 2019-08-04 cation Selection aménagement du littoral de ramework NKTT MR-MEDD-75960-CS-QCBS / Component 2: Strengthening Consultant Qualifi Elaboration d'une stratégie d IDA / D2880 the Policy and Institutional F Post Open - National 40,000.00 0.00 Canceled 2018-09-21 2018-10-12 2018-11-25 2018-12-25 2019-01-29 2019-07-28 cation Selection e gestion intégrée du littoral ramework mauritanien MR-MEDD-75970-CS-QCBS / Component 2: Strengthening Consultant Qualifi Evaluation du capital sédime IDA / D2880 the Policy and Institutional F Post Open - National 40,000.00 0.00 Canceled 2018-09-20 2018-10-11 2018-11-24 2018-12-24 2019-01-28 2019-07-27 cation Selection ntologique de la ville de NKT ramework T MR-MEDD-115364-CS-CQS / Component 3: Strengthening Etude de faisabilité pour la ré Consultant Qualifi IDA / D2880 National Physical and Social Post Limited 40,000.00 0.00 Canceled 2019-05-27 2020-04-27 2019-06-03 2019-06-07 2019-06-14 2019-07-24 habilitation et l'extension de cation Selection Investments la digue de protection au niv eau du Diawling MR-MEDD-115676-CS-CQS / Component 3: Strengthening Consultant Qualifi Etude technique pour le colm IDA / D2880 National Physical and Social Post Limited 42,000.00 39,243.19 Completed 2018-06-15 2018-06-15 2018-06-29 2018-08-01 2018-07-13 2018-08-02 2018-08-10 2018-08-03 2018-09-24 2018-09-20 cation Selection atage des brèches du littoral Investments de Nouakchott MR-MEDD-117326-CS-QCBS / recrutement d'un cabinet d Component 4: National Coor Quality And Cost- Pending Impleme 'audit pour audit extezrne du IDA / D2880 Post Open - National 40,000.00 0.00 2019-05-29 2019-05-31 2019-06-08 2019-06-11 2019-06-14 2019-06-20 2019-06-23 2019-07-13 dination Based Selection ntation projet pour les années 2018 2019 2020 et 2021. MR-MEDD-124791-CS-INDV / etude sur la mise en place du système Waves pour le littor Component 2: Strengthening al et l'espace maritime : eval Quality And Cost- Open - Internationa IDA / D2880 the Policy and Institutional F Post 128,000.00 0.00 Canceled 2019-09-12 2019-10-03 2019-11-16 2019-12-14 2020-01-13 2020-02-17 2020-03-23 2021-03-23 uation des ecosystèmes phys Based Selection l ramework iqueset monetaire pour la sel ection des comptes du capital natur el côtier . MR-MEDD-135519-CS-QCBS Component 2: Strengthening / Etude environnementale str Quality And Cost- Open - Internationa IDA / D2880 the Policy and Institutional F Post 200,000.00 0.00 Canceled 2019-10-04 2019-10-06 2019-10-09 2019-10-14 2019-10-29 2019-11-03 2019-11-13 2019-12-13 atégique pour l'exploitation d Based Selection l ramework u sable noir sur le littoral ma uritanien MR-MEDD-157694-CS-CQS / Component 2: Strengthening Etude environnementale stra Consultant Qualifi Open - Internationa IDA / D2880 the Policy and Institutional F Post 200,000.00 171,889.76 Signed 2020-02-11 2020-02-06 2020-02-26 2020-04-10 2020-04-07 2020-05-10 2020-08-05 2020-06-14 2020-08-15 2020-12-11 tégique pour l'exploitation du cation Selection l ramework sable noir sur le littoral mauri tanien MR-MEDD-170561-CS-CQS / Component 2: Strengthening Élaboration des directives d’ Consultant Qualifi Open - Internationa IDA / D2880 the Policy and Institutional F Post 250,000.00 0.00 Canceled 2020-05-11 2020-10-19 2020-06-01 2021-02-03 2020-07-15 2020-08-14 2020-09-18 2020-12-17 aménagement du littoral de cation Selection l ramework Nouakchott de Nouadhibou MR-MEDD-170480-CS-INDV / Action pilote de recherche (in Component 3: Strengthening Consultant Qualifi troduction de plantes aquatiq IDA / D2880 National Physical and Social Post Open - National 29,000.00 0.00 Canceled 2020-07-15 2020-08-05 2020-09-18 2020-10-18 2020-11-22 2021-01-21 cation Selection ues, atténuation du PH de l’e Investments au,…) de la mare de Riyad MR-MEDD-170427-CS-CQS / Component 2: Strengthening Consultant Qualifi Open - Internationa Etude impact environnement IDA / D2880 the Policy and Institutional F Post 40,000.00 0.00 Canceled 2020-10-12 2020-08-03 2020-10-27 2020-12-10 2021-01-09 2021-02-13 2021-05-04 cation Selection l al et social ( colmatage de br ramework èches ) MR-MEDD-182813-CS-CQS / Réalisation de l'étude sur la c Component 3: Strengthening Consultant Qualifi Open - Internationa Pending Impleme aractérisation des déchets ur IDA / D2880 National Physical and Social Post 40,000.00 0.00 2020-09-23 2020-10-14 2020-11-27 2020-12-27 2021-01-31 2021-03-17 cation Selection l ntation bains à Nouadhibou et propo Investments sition d'un système de gestio n approprié MR-MEDD-200765-CS-CQS / accompagnement de l'UGP e t des structures beneficiaires Component 4: National Coor Consultant Qualifi IDA / D2880 Post Limited 40,000.00 39,845.23 Signed 2020-05-04 2021-05-24 2020-05-18 2020-06-10 2020-06-17 2021-06-22 2020-07-22 2020-07-04 2021-01-18 dans la mise en oeuvre des a dination cation Selection ctivitesd investissement(iden tification des sites screening environnemental reporting...) MR-MEDD-182699-CS-CQS / accompagnement de l'UGP e Component 2: Strengthening t des structures beneficiaires Consultant Qualifi IDA / D2880 the Policy and Institutional F Post Limited 40,000.00 0.00 Canceled 2020-07-01 2020-07-15 2020-08-14 2020-09-18 2020-12-17 dans la mise en oeuvre des a cation Selection ramework ctivitesd investissement(iden tification des sites screening environnemental reporting...) Page 6 MR-MEDD-228916-CS-CQS / Recrutement d'un cabinet po Component 3: Strengthening Consultant Qualifi Under Implement ur le choix d’un site d’Enfoui IDA / D2880 National Physical and Social Post Limited 40,000.00 0.00 2021-04-06 2021-06-17 2021-04-20 2021-05-20 2021-06-24 2021-12-21 cation Selection ation ssement Technique et de trai Investments tement des ordures ménagèr es à Nouakchott MR-MEDD-170566-CS-CQS / Étude pour la détermination Component 2: Strengthening du trait de côte du littoral ma Consultant Qualifi IDA / D2880 the Policy and Institutional F Post Open - National 100,000.00 0.00 Canceled 2020-06-15 2020-07-06 2020-08-19 2020-09-18 2020-10-23 2021-04-21 uritanien par images satellita cation Selection ramework ires avec quelques relevés d u terrain par GNSS de N’Diag o au Cap blanc MR-MEDD-170564-CS-CQS / Component 2: Strengthening Etude pour l’évaluation des ri Consultant Qualifi Open - Internationa IDA / D2880 the Policy and Institutional F Post 150,000.00 0.00 Canceled 2020-06-15 2020-07-06 2020-08-19 2020-09-18 2020-10-23 2021-10-20 sques liés aux inondations de cation Selection l ramework Nouakchott et Nouadhibou MR-MEDD-192591-CS-CQS / Component 2: Strengthening Consultant Qualifi Open - Internationa Etude de la bathymétrie et d IDA / D2880 the Policy and Institutional F Post 38,000.00 0.00 Canceled 2020-09-15 2020-09-30 2020-10-15 2020-10-30 2020-12-04 2021-06-02 cation Selection l e l'hydrométrie au PNBA ramework MR-MEDD-76863-CS-QBS / él Component 2: Strengthening aboration de plans de dévelo Quality Based Sel IDA / D2880 the Policy and Institutional F Post Open - National 20,000.00 0.00 Canceled 2018-09-26 2018-10-17 2018-11-30 2018-12-28 2019-01-27 2019-02-26 2019-04-02 2020-04-01 ppement communaux pour T ection ramework evragh Zeine ,sebkha et Elmi na MR-MEDD-76873-CS-QCBS / Component 2: Strengthening Quality And Cost- Open - Internationa Etude sur les pressions et enj IDA / D2880 the Policy and Institutional F Post 70,000.00 0.00 Canceled 2018-10-08 2018-10-29 2018-12-12 2019-01-09 2019-02-08 2019-03-15 2019-04-19 2020-04-18 Based Selection l eux exercés sur l'espace vital ramework du PNBA MR-MEDD-170392-CS-INDV / Component 2: Strengthening Consultant Qualifi Open - Internationa Etude de faisabilité sur la dél IDA / D2880 the Policy and Institutional F Post 40,000.00 0.00 Canceled 2020-05-20 2020-05-20 2020-06-10 2020-07-24 2020-08-23 2020-09-27 2020-12-26 cation Selection l ocalisation du site d'orpaillag ramework e de Chami MR-MEDD-170573-CS-CQS / Component 3: Strengthening Consultant Qualifi Open - Internationa Activités de renforcement de IDA / D2880 National Physical and Social Post 300,000.00 0.00 Canceled 2020-05-11 2020-07-06 2020-06-01 2020-07-15 2020-08-14 2020-09-18 2021-09-15 cation Selection l la résilience des populations Investments de N’Diago MR-MEDD-232494-CS-CQS / Élaborer une enquête statisti que sur le nombre de ménag Component 4: National Coor Consultant Qualifi es situés sur le littoral ayant IDA / D2880 Post Open - National 40,000.00 0.00 Canceled 2021-08-10 2021-08-31 2021-10-14 2021-11-13 2021-12-12 2022-03-12 dination cation Selection accès à des activités de subs tances améliorées et sur le s core du niveau de satisfactio n des populations du littoral MR-MEDD-232505-CS-CQS / Recrutement d’un Cabinet po ur Faire une modélisation de Component 2: Strengthening la dynamique du littoral au ni Consultant Qualifi Open - Internationa IDA / D2880 the Policy and Institutional F Post 150,000.00 0.00 Canceled 2021-10-14 2021-08-13 2021-11-04 2021-12-18 2022-01-17 2022-02-21 2022-08-20 veau du Port de N'Diago pour cation Selection l ramework mieux comprendre la problé matique actuelle de l’érosion constatée et les mesures à p rendre MR-MEDD-232481-CS-CQS / Component 3: Strengthening Recrutement d’un bureau de Consultant Qualifi IDA / D2880 National Physical and Social Post Open - National 40,000.00 39,629.82 Signed 2021-06-21 2021-06-21 2021-07-12 2021-08-25 2021-09-07 2021-09-24 2021-09-07 2021-10-29 2021-09-23 2022-04-27 contrôle et de suivi des trava cation Selection Investments ux de colmatage des 3 brèch es (9, 13 et 16) MR-MEDD-200679-CS-INDV / Component 2: Strengthening Recrutement d'un formateur Consultant Qualifi IDA / D2880 the Policy and Institutional F Post Open - National 35,000.00 0.00 Canceled 2020-12-17 2021-01-07 2021-02-20 2021-03-22 2021-04-26 2021-05-26 pour la formation des institu cation Selection ramework teurs en éducation environne mentale au PND MR-MEDD-239559-CS-CQS / Component 3: Strengthening Recrutement d'un consultent Consultant Qualifi IDA / D2880 National Physical and Social Post Open - National 42,000.00 41,182.86 Signed 2021-08-05 2021-06-08 2021-08-26 2021-10-09 2021-08-04 2021-11-08 2021-08-09 2021-12-13 2021-08-10 2022-06-11 pour élaborer le dossier tech cation Selection Investments nique pour la fixation de dun e de littoral. MR-MEDD-246147-CS-CQS / Recrutement d’ ONGs pour a ssurer la formation des ONG Component 3: Strengthening Consultant Qualifi Under Implement porteuses de Projet et le suiv IDA / D2880 National Physical and Social Post Limited 37,000.00 0.00 2021-08-09 2021-09-01 2021-08-23 2021-09-07 2021-10-06 2021-12-05 cation Selection ation i des Projets Investments dans les communes littorales de Nktt: Sebkha ,ElMina et Te vraghZeine. MR-MEDD-249823-CS-CQS / Recrutement d'un Bureau d'é Component 4: National Coor Consultant Qualifi tude pour le contrôle et le sui IDA / D2880 Post Open - National 20,000.00 35,802.72 Signed 2021-09-27 2021-10-01 2021-10-18 2021-12-01 2021-11-22 2021-12-31 2021-11-22 2022-02-04 2021-12-07 2023-02-01 dination cation Selection vi des travaux de la construc tion du siège de l'Observatoi re du Littoral Mauritanien MR-MEDD-74256-CS-CQS / E Component 3: Strengthening Consultant Qualifi tude pour le franchissement IDA / D2880 National Physical and Social Post Limited 20,000.00 0.00 Canceled 2018-10-08 2018-10-22 2018-11-21 2018-12-26 2019-06-24 cation Selection du cordon dunaire de NKTT Investments MR-MEDD-232512-CS-CQS / Élaborer une étude de faisabi Component 2: Strengthening lité (technique et financière) Consultant Qualifi Open - Internationa IDA / D2880 the Policy and Institutional F Post 300,000.00 0.00 Canceled 2021-07-20 2021-08-10 2021-09-23 2021-10-23 2021-11-27 2022-05-26 pour la construction d'un Cen cation Selection l ramework tre d'Enfouissement Techniq ue des déchets solides urbai ns de Nouakchott MR-MEDD-234406-CS-CQS / Component 3: Strengthening Recrutement d’une ONG pou Consultant Qualifi IDA / D2880 National Physical and Social Post Limited 9,000.00 0.00 Canceled 2021-07-15 2021-07-29 2021-08-28 2021-10-02 2021-12-31 r le suivi de Projets Sociaux e cation Selection Investments t AGR dans la Communes d’E l Mina MR-MEDD-234410-CS-CQS / Component 3: Strengthening Recrutement d’une ONG pou Consultant Qualifi IDA / D2880 National Physical and Social Post Limited 7,000.00 0.00 Canceled 2021-06-15 2021-06-29 2021-07-29 2021-09-02 2021-11-01 r le suivi de Projets Sociaux e cation Selection Investments t AGR dans la Communes de Tevragh Zeina MR-MEDD-232514-CS-CQS / Recrutement d’un bureau po ur Mener les études prioritair es nécessaires pour (i) suivre Component 2: Strengthening Consultant Qualifi Open - Internationa l’impact du changement clim IDA / D2880 the Policy and Institutional F Post 85,000.00 0.00 Canceled 2021-06-15 2021-07-06 2021-08-19 2021-09-18 2021-10-23 2022-01-21 cation Selection l atique sur le littoral, (ii) faire ramework une analyse historique de l’é volution du trait de côte et (ii i) fournir les données essenti elles aux évalu Page 7 MR-MEDD-232480-CS-CQS / Recrutement d’un Cabinet po Component 2: Strengthening Consultant Qualifi ur réaliser un état des connai IDA / D2880 the Policy and Institutional F Post Limited 42,000.00 0.00 Canceled 2021-06-14 2021-06-28 2021-07-13 2021-08-17 2021-11-15 cation Selection ssances et des données disp ramework onibles sur le système côtier (situation de référence MR-MEDD-232513-CS-CQS / Recrutement d’un bureau po Component 2: Strengthening ur Elaborer une EIES pour la Consultant Qualifi IDA / D2880 the Policy and Institutional F Post Open - National 100,000.00 0.00 Canceled 2021-09-15 2021-10-06 2021-11-19 2021-12-19 2022-01-23 2022-07-22 construction d'un Centre d'E cation Selection ramework nfouissement Technique des déchets de la ville de Nouakc hott MR-MEDD-211477-CS-CQS / Component 3: Strengthening Consultant Qualifi Recrutement d'un cabinet po IDA / D2880 National Physical and Social Post Open - National 30,000.00 0.00 Canceled 2021-02-05 2021-02-26 2021-04-11 2021-05-11 2021-06-15 2021-08-14 cation Selection ur le Suivi des travaux de la Investments Digue Nord MR-MEDD-234411-CS-CQS / Component 3: Strengthening Recrutement d’une ONG pou Consultant Qualifi IDA / D2880 National Physical and Social Post Limited 12,000.00 0.00 Canceled 2021-07-15 2021-07-29 2021-08-28 2021-10-02 2021-12-01 r le suivi de Projets Sociaux e cation Selection Investments t AGR dans la Communes de Sebkha MR-MEDD-267101-CS-CQS / Component 3: Strengthening Recrutement d’un Consultant Consultant Qualifi Open - Internationa IDA / D2880 National Physical and Social Post 120,000.00 0.00 Canceled 2021-12-15 2021-12-13 2021-12-30 2022-01-28 2022-02-12 2022-03-19 2022-06-17 (cabinet) pour l’élaboration d cation Selection l Investments ’un avant-Projet de loi relatif au littoral MR-MEDD-267604-CS-LCS / Component 4: National Coor Least Cost Selecti Open - Internationa Under Implement Recrutement d'un cabinet d' IDA / D2880 Post 30,000.00 0.00 2021-12-20 2021-12-12 2022-01-10 2022-02-23 2022-03-23 2022-04-22 2022-05-27 2022-06-11 2024-11-27 dination on l ation audit pour les exercices 2021 -2022-2023 MR-MEDD-267605-CS-QCBS / Recrutement d'un cabinet p Component 3: Strengthening Quality And Cost- Open - Internationa Under Implement our l'élaboration des Directiv IDA / D2880 National Physical and Social Post 400,000.00 0.00 2022-10-10 2023-01-19 2022-10-31 2023-01-26 2022-12-14 2023-01-11 2023-02-10 2023-03-17 2023-04-21 2023-10-18 Based Selection l ation es d'Aménagements Littoral Investments es de Nouakchott et Nouadhi bou MR-MEDD-315488-CS-CQS / Component 3: Strengthening Recrutement d’un Cabinet po Consultant Qualifi Pending Impleme IDA / D2880 National Physical and Social Post Open - National 40,000.00 0.00 2022-10-24 2022-11-14 2022-12-28 2023-01-27 2023-03-03 2023-06-01 ur l'étude technique de colm cation Selection ntation Investments atage des 6 brèches MR-MEDD-315489-CS-CQS / Recrutement d’un Cabinet po Component 3: Strengthening Consultant Qualifi Pending Impleme ur l'étude d’impact environne IDA / D2880 National Physical and Social Post Open - National 47,000.00 0.00 2022-10-17 2022-11-07 2022-12-21 2023-01-20 2023-02-24 2023-08-23 cation Selection ntation mentale et sociale (EIES) du Investments colmatage des 6 brèches MR-MEDD-259720-CS-QCBS / Recrutement d’un cabinet p Component 3: Strengthening Quality And Cost- Open - Internationa our l’élaboration du Plan Nati IDA / D2880 National Physical and Social Post 300,000.00 0.00 Canceled 2021-12-06 2021-11-04 2021-12-27 2021-11-15 2022-02-09 2022-03-09 2022-04-08 2022-05-13 2022-06-17 2022-12-14 Based Selection l onal de Gestion des Déchets Investments Solides en Mauritanie MR-MEDD-315547-CS-CQS / Recrutement d’un Cabinet po Component 4: National Coor Consultant Qualifi Under Implement ur la révision du Manuel des IDA / D2880 Post Open - National 50,000.00 0.00 2022-09-28 2022-10-24 2022-10-19 2022-12-02 2023-01-01 2023-02-05 2023-05-06 dination cation Selection ation Procédures Administratifs, Fi nanciers, de Passation des M archés MR-MEDD-315554-CS-CQS / Component 3: Strengthening Recrutement d’une ONG pou Consultant Qualifi IDA / D2880 National Physical and Social Post Limited 16,000.00 0.00 Signed 2022-11-07 2022-11-24 2022-11-21 2023-01-13 2022-12-21 2023-02-13 2023-01-25 2023-04-25 r le Suivi des SPS/AGRs pour cation Selection Investments la commune de Nouadhibou MR-MEDD-315556-CS-CQS / Component 3: Strengthening Recrutement d’une ONG pou Consultant Qualifi IDA / D2880 National Physical and Social Post Limited 16,000.00 0.00 Signed 2022-10-17 2022-12-01 2022-10-31 2023-03-02 2022-11-30 2023-03-06 2023-01-04 2023-04-04 r le Suivi des SPS/AGRs pour cation Selection Investments la commune de Chami MR-MEDD-315559-CS-CQS / Component 3: Strengthening Recrutement d’une ONG pou Consultant Qualifi Under Implement IDA / D2880 National Physical and Social Post Limited 16,000.00 0.00 2022-10-10 2023-04-03 2022-10-24 2022-11-23 2022-12-28 2023-03-28 r le Suivi des SPS/AGRs pour cation Selection ation Investments la commune de Keurmecen MR-MEDD-315568-CS-CQS / Component 3: Strengthening Recrutement d’une ONG pou Consultant Qualifi Under Implement IDA / D2880 National Physical and Social Post Limited 16,000.00 0.00 2022-09-26 2023-04-03 2022-10-10 2022-11-09 2022-12-08 2023-03-08 r le Suivi des SPS/AGRs pour cation Selection ation Investments la commune de Tiguinte MR-MEDD-315570-CS-CQS / Component 3: Strengthening Recrutement d’une ONG pou Consultant Qualifi IDA / D2880 National Physical and Social Post Limited 16,000.00 0.00 Signed 2022-10-03 2022-11-24 2022-10-17 2023-01-10 2022-11-16 2023-02-13 2022-12-15 2023-03-15 r le Suivi des SPS/AGRs pour cation Selection Investments la commune de Benichab MR-MEDD-232504-CS-CQS / Recrutement d’un cabinet po Component 2: Strengthening Consultant Qualifi Open - Internationa ur réaliser un audit environn IDA / D2880 the Policy and Institutional F Post 140,000.00 0.00 Canceled 2021-09-15 2021-08-11 2021-10-06 2021-09-21 2021-11-19 2021-12-19 2022-01-23 2022-07-22 cation Selection l emental des usines de farine ramework de poisson le long du littoral MR-MEDD-249756-CS-CQS / Recrutement d'un bureau d'é Component 2: Strengthening Consultant Qualifi tude pour l'élaboration d'un c IDA / D2880 the Policy and Institutional F Post Open - National 20,000.00 0.00 Canceled 2021-10-13 2021-08-27 2021-11-03 2021-12-17 2022-01-16 2022-02-20 2022-04-21 cation Selection ahier des charges environne ramework mentales des usines d'orpaill ages MR-MEDD-267614-CS-CQS / Recrutement d’ une ONG pou Component 2: Strengthening r assurer la formation des ON Consultant Qualifi IDA / D2880 the Policy and Institutional F Post Limited 35,000.00 0.00 Canceled 2022-01-10 2022-01-24 2022-02-23 2022-03-30 2022-06-28 G porteuses de Projet et le su cation Selection ramework ivi des Projets dans la Comm une Littorale de Nouadhinou MR-MEDD-249750-CS-CQS / Recrutement d'une ONG char gée de la mise en œuvre du Component 2: Strengthening Consultant Qualifi programme de sensibilisation IDA / D2880 the Policy and Institutional F Post Open - National 40,000.00 0.00 Canceled 2021-09-15 2021-10-06 2021-11-19 2021-12-19 2022-01-23 2022-04-23 cation Selection sur les risques liés à l’utilisati ramework on des produits chimiques da ns l’extraction artisanale de l ’or pour le Wilaya Nouadhibo u Page 8 MR-MEDD-232491-CS-CQS / Component 3: Strengthening Recruter un bureau pour ass Consultant Qualifi IDA / D2880 National Physical and Social Post Open - National 10,000.00 0.00 Canceled 2021-07-13 2021-08-03 2021-09-16 2021-10-16 2021-11-14 2022-02-12 urer le contrôle et le suivi de cation Selection Investments s travaux de la digue MR-MEDD-315491-CS-QCBS / Recrutement d’un cabinet p Component 2: Strengthening our élaborer une étude de fai Quality And Cost- Open - Internationa Pending Impleme IDA / D2880 the Policy and Institutional F Post 280,000.00 0.00 2022-10-24 2022-11-14 2022-12-28 2023-01-25 2023-02-24 2023-03-31 2023-05-05 2023-09-02 sabilité pour la construction Based Selection l ntation ramework d'un Centre d'Enfouissement Technique des déchets solide s urbains de Nouakchott MR-MEDD-339276-CS-CQS / Recrutement d’un Cabinet po Component 2: Strengthening ur l'élaboration d'un état de li Consultant Qualifi Under Implement IDA / D2880 the Policy and Institutional F Post Open - National 80,000.00 0.00 2023-02-13 2023-05-30 2023-02-28 2023-03-29 2023-04-28 2023-06-02 2023-08-31 eux/trait de côtes dans le sec cation Selection ation ramework teur transfrontalier Mauritani e-Sénégal (Ségement cotier Mauritanien) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74127-CS-INDV / Diagnostic et évaluation de l Component 2: Strengthening Individual Consult Under Implement a capacité de tous les organi IDA / D2880 the Policy and Institutional F Post Limited 20,000.00 0.00 2018-08-17 2019-03-28 2018-08-22 2018-09-12 2018-10-17 2019-04-15 ant Selection ation smes concernés avec l'OLM (i ramework nclus consultations, séminair es, ateliers) MR-MEDD-74130-CS-INDV / Component 2: Strengthening Individual Consult Elaboration des plans de résil IDA / D2880 the Policy and Institutional F Post Limited 30,000.00 13,532.13 Signed 2018-08-20 2018-10-17 2018-08-25 2019-10-18 2018-09-15 2018-10-19 2018-10-20 2019-03-28 2019-04-18 ant Selection ience de N'Diago ramework MR-MEDD-74133-CS-INDV / I dentification des actions prio Component 2: Strengthening Individual Consult Pending Impleme ritaires de l'antenne national IDA / D2880 the Policy and Institutional F Post Limited 20,000.00 0.00 2018-10-10 2018-10-15 2018-11-05 2018-12-10 2019-06-08 ant Selection ntation e de la MOLOA (inclus consul ramework tations, ateliers, séminaires) MR-MEDD-74135-CS-INDV / Component 3: Strengthening Individual Consult Elaboration de textes juridiqu IDA / D2880 National Physical and Social Post Limited 20,000.00 14,000.00 Completed 2018-11-02 2019-02-05 2018-11-07 2019-02-02 2018-11-28 2019-01-02 2019-02-26 2019-07-01 2020-02-11 ant Selection es relatifs aux principes pollu Investments eur-payeurs MR-MEDD-74137-CS-INDV / Conception et mise en place d'une plateforme de gestion Component 2: Strengthening Individual Consult environnementale relative à l IDA / D2880 the Policy and Institutional F Post Limited 30,000.00 0.00 Canceled 2018-09-03 2018-09-08 2018-09-29 2018-11-03 2019-05-02 ant Selection 'évaluation des activités et le ramework suivi de leurs impacts enviro nnementaux sur le littoral m auritanien MR-MEDD-74141-CS-INDV / Component 2: Strengthening Analyse du cadre foncier rela Individual Consult IDA / D2880 the Policy and Institutional F Post Limited 30,000.00 28,445.10 Signed 2018-10-15 2020-12-16 2018-10-20 2021-04-06 2018-11-10 2021-04-07 2018-12-15 2021-04-09 2019-06-13 tif au littoral (inclus consultat ant Selection ramework ions, séminaires, ateliers) MR-MEDD-74152-CS-INDV / Component 2: Strengthening Individual Consult Pending Impleme Elaboration de guide des act IDA / D2880 the Policy and Institutional F Post Limited 30,000.00 0.00 2018-11-01 2018-11-06 2018-11-27 2019-01-01 2019-06-30 ant Selection ntation eurs et des métiers du littora ramework l mauritanien MR-MEDD-74153-CS-INDV / Component 2: Strengthening Revue et amendement du sy Individual Consult IDA / D2880 the Policy and Institutional F Post Limited 40,000.00 36,000.00 Signed 2018-10-01 2020-02-11 2018-10-06 2020-05-30 2018-10-27 2020-06-02 2018-12-01 2020-07-01 2019-05-30 stème des études d'impact e ant Selection ramework nvironnemental en Mauritani e MR-MEDD-74164-CS-INDV / Component 2: Strengthening Recrutement d'un assistant t Individual Consult Pending Impleme IDA / D2880 the Policy and Institutional F Post Open 18,500.00 0.00 2018-09-13 2018-11-01 2018-11-22 2018-12-27 2019-06-25 echnique au profit de l'Autori ant Selection ntation ramework té de la Zone franche de NDB MR-MEDD-74175-CS-INDV / Component 2: Strengthening Individual Consult Etat des lieux de l'environne IDA / D2880 the Policy and Institutional F Post Limited 25,000.00 23,548.85 Signed 2018-11-01 2018-12-20 2018-11-06 2018-12-04 2018-11-27 2018-12-12 2019-01-01 2018-12-18 2019-06-30 ant Selection ment au niveau de la Zone fr ramework anche de NDB MR-MEDD-74194-CS-INDV / Component 3: Strengthening Individual Consult Under Implement Etudes de faisabilité des trav IDA / D2880 National Physical and Social Post Limited 10,000.00 0.00 2018-10-01 2018-11-24 2018-10-06 2018-10-27 2018-12-01 2019-05-30 ant Selection ation aux de fixation du cordon du Investments naire de Diawling MR-MEDD-74199-CS-INDV / Component 3: Strengthening Recrutement d'un consultant Individual Consult IDA / D2880 National Physical and Social Post Limited 10,000.00 9,240.00 Completed 2018-11-05 2019-03-28 2018-11-10 2019-03-28 2018-12-01 2019-01-05 2019-03-29 2019-07-04 2019-04-03 pour le suivi et le contrôle de ant Selection Investments s travaux du cordon dunaire de Diawling MR-MEDD-74200-CS-INDV / Component 3: Strengthening Individual Consult Elaboration d'une carte d'occ IDA / D2880 National Physical and Social Post Limited 20,000.00 17,280.00 Completed 2018-11-15 2019-03-28 2018-11-20 2019-03-28 2018-12-11 2019-01-15 2019-03-29 2019-07-14 2019-05-16 ant Selection upation des éco-systèmes de Investments mangroves MR-MEDD-75945-CS-INDV / Component 3: Strengthening Individual Consult Under Implement Etude pour le franchissement IDA / D2880 National Physical and Social Post Limited 20,000.00 0.00 2018-10-01 2019-02-12 2018-10-06 2018-10-27 2018-12-01 2019-05-30 ant Selection ation du cordon dunaire de NKTT Investments MR-MEDD-75972-CS-INDV / Component 2: Strengthening Individual Consult Conception et mise en place IDA / D2880 the Policy and Institutional F Post Limited 20,000.00 13,545.94 Signed 2018-11-05 2019-03-20 2018-11-10 2019-03-28 2018-12-01 2019-03-28 2019-01-05 2019-03-29 2019-07-04 ant Selection d'un site web pour l'OLM ramework MR-MEDD-76422-CS-INDV / Component 4: National Coor Individual Consult Under Implement IDA / D2880 Post Limited 6,000.00 0.00 2018-09-12 2018-09-17 2018-10-08 2018-11-12 2019-05-11 Recrutement d'un auditeur in dination ant Selection ation terne MR-MEDD-76867-CS-INDV / Component 3: Strengthening Individual Consult Mise à jour du SIG de la Régi IDA / D2880 National Physical and Social Post Open 20,000.00 0.00 Canceled 2018-12-04 2019-01-22 2019-02-12 2019-03-19 2019-09-15 ant Selection on de Nouakchott Investments MR-MEDD-76868-CS-INDV / Component 3: Strengthening Individual Consult Adaptation du fonds d'Investi IDA / D2880 National Physical and Social Post Open 20,000.00 0.00 Canceled 2018-12-04 2019-01-22 2019-02-12 2019-03-19 2019-09-15 ant Selection ssement communal (région d Investments e NKTT) Page 9 MR-MEDD-82701-CS-INDV / r ecrutement d'un consultant n Component 2: Strengthening Individual Consult Pending Impleme ational pour l'appui à l'étude IDA / D2880 the Policy and Institutional F Post Limited 35,000.00 0.00 2018-10-29 2018-11-03 2018-11-24 2018-12-29 2019-06-27 ant Selection ntation de faisabilité du projet WACA ramework -CCA en Mauritanie MR-MEDD-82704-CS-INDV / r Component 2: Strengthening Individual Consult Pending Impleme éalisation d'un documentaire IDA / D2880 the Policy and Institutional F Post Limited 20,000.00 0.00 2018-10-19 2018-10-24 2018-11-14 2018-12-19 2019-06-17 ant Selection ntation sur la baie de l'étoile ramework MR-MEDD-82731-CS-INDV / Component 4: National Coor Individual Consult IDA / D2880 Post Limited 20,000.00 0.00 Canceled 2018-11-19 2018-11-24 2018-12-15 2019-01-03 2019-07-02 Maintenance et suivi informa dination ant Selection tique MR-MEDD-82737-CS-INDV / accompagnement de l'UGP e Component 3: Strengthening t des structures beneficiaires Individual Consult IDA / D2880 National Physical and Social Post Limited 37,000.00 0.00 Canceled 2018-11-15 2018-11-20 2018-12-11 2019-01-15 2019-07-14 dans la mise en oeuvre des a ant Selection Investments ctivitesd investissement(iden tification des sites screening environnemental reporting...) MR-MEDD-76859-CS-NPO / M Component 3: Strengthening Individual Consult ise en place d'un système de IDA / D2880 National Physical and Social Post Limited 38,000.00 33,664.91 Signed 2018-11-01 2019-09-02 2018-11-06 2019-10-02 2018-11-27 2019-10-02 2019-01-01 2019-10-03 2019-06-30 ant Selection Gestion de plaintes Investments MR-MEDD-76166-CS-INDV / Component 2: Strengthening Individual Consult Recrutement d'un Responsab IDA / D2880 the Policy and Institutional F Post Limited 10,320.00 9,600.00 Signed 2018-09-05 2019-03-18 2018-09-10 2018-07-26 2018-10-01 2018-11-05 2019-08-01 2019-05-04 ant Selection le de Suivi-Evaluation ramework MR-MEDD-76167-CS-INDV / Component 2: Strengthening Individual Consult Pending Impleme Recrutement d'un Spécialiste IDA / D2880 the Policy and Institutional F Post Open 21,000.00 0.00 2018-09-05 2018-10-24 2018-11-14 2018-12-19 2019-06-17 ant Selection ntation en communication ramework MR-MEDD-76173-CS-INDV / Component 2: Strengthening Individual Consult Recrutement en Développem IDA / D2880 the Policy and Institutional F Post Open 12,000.00 9,600.00 Signed 2018-09-05 2019-07-25 2018-10-24 2019-07-25 2018-11-14 2018-12-19 2019-08-02 2019-06-17 ant Selection ent Institutionnel ramework MR-MEDD-76168-CS-INDV / Component 2: Strengthening Recrutement d'un Spécialiste Individual Consult Pending Impleme IDA / D2880 the Policy and Institutional F Post Open 21,000.00 0.00 2018-09-03 2018-10-22 2018-11-12 2018-12-17 2019-06-15 en Développement Social, sa ant Selection ntation ramework uvegarde sociale et genre MR-MEDD-76158-CS-INDV / Component 2: Strengthening Individual Consult Recrutement Coordinateur d IDA / D2880 the Policy and Institutional F Post Limited 60,000.00 4,320.00 Signed 2018-08-29 2017-09-28 2018-09-03 2017-09-28 2018-09-24 2017-09-28 2018-10-29 2020-01-03 2019-04-27 ant Selection u Projet WACA ramework MR-MEDD-76160-CS-INDV / Component 2: Strengthening Individual Consult Recrutement d'un Coordinate IDA / D2880 the Policy and Institutional F Post Limited 50,000.00 3,520.00 Signed 2018-08-29 2018-02-01 2018-09-03 2018-02-01 2018-09-24 2018-10-29 2018-05-03 2019-04-27 ant Selection ur-Adjoint juriste pour le Proj ramework et WACA MR-MEDD-76162-CS-INDV / Component 2: Strengthening Individual Consult Recrutement d'un Responsab IDA / D2880 the Policy and Institutional F Post Limited 20,600.00 1,600.00 Signed 2018-08-29 2018-06-28 2018-09-03 2018-06-28 2018-09-24 2018-10-29 2018-08-03 2019-04-27 ant Selection le de Passation des Marchés ramework MR-MEDD-115334-CS-INDV / Elaboration des TDR de l'étu Component 2: Strengthening Individual Consult Under Implement de de détermination du trait IDA / D2880 the Policy and Institutional F Post Open 10,000.00 0.00 2019-05-30 2019-10-01 2019-06-12 2019-06-14 2019-06-18 2019-07-08 ant Selection ation de côte du Littoral mauritani ramework en par GNSS de N'Diago au C ap blanc MR-MEDD-115272-CS-INDV / Component 2: Strengthening Etude pour l'élaboration d'un Individual Consult IDA / D2880 the Policy and Institutional F Post Open 30,000.00 23,826.67 Completed 2019-05-30 2019-06-07 2019-06-13 2019-06-13 2019-06-15 2019-06-18 2019-06-21 2019-06-28 2019-08-05 2019-09-06 e stratégie et d'un plan de co ant Selection ramework mmunication pour le Projet MR-MEDD-115327-CS-INDV / Component 3: Strengthening L'élaboration d'une étude d'i Individual Consult IDA / D2880 National Physical and Social Post Open 30,000.00 21,493.34 Completed 2019-05-30 2019-06-12 2019-06-11 2019-06-13 2019-06-13 2019-06-17 2019-06-28 2019-07-27 2019-09-06 dentification de sous-projets ant Selection Investments dans les communes littorales MR-MEDD-115350-CS-INDV / Elaboration de cahier de pres Component 3: Strengthening Individual Consult criptions techniques pour le c IDA / D2880 National Physical and Social Post Open 40,000.00 7,466.67 Signed 2019-05-30 2019-10-02 2019-06-12 2019-06-13 2019-06-17 2019-06-18 2019-06-20 2019-06-28 2019-07-16 ant Selection olmatage des brèches du cor Investments don dunaire de Nouakchott MR-MEDD-115371-CS-CDS / Component 2: Strengthening Etat des lieux du foncier du li Individual Consult IDA / D2880 the Policy and Institutional F Post Open 40,000.00 24,773.34 Completed 2019-05-30 2019-10-01 2019-06-11 2019-09-05 2019-06-13 2019-09-05 2019-06-17 2019-09-10 2019-08-16 2019-11-22 ttoral de N'Diago et de la Zon ant Selection ramework e Franche de Nouadhibou MR-MEDD-124792-CS-INDV / Inventaire des textes juridiqu Component 2: Strengthening Individual Consult es relatifs à la gestion des zo IDA / D2880 the Policy and Institutional F Post Limited 20,000.00 0.00 Canceled 2019-08-21 2019-08-26 2019-09-16 2019-10-21 2020-04-18 ant Selection nes côtières et marines et ra ramework tifications des protocoles de l a convention d'Abidjan. MR-MEDD-74150-CS-INDV / Component 2: Strengthening Analyse et révision de l'ordon Individual Consult IDA / D2880 the Policy and Institutional F Post Open 40,000.00 0.00 Canceled 2019-10-22 2019-11-15 2019-11-20 2019-11-30 2020-01-09 nance relative au littoral et él ant Selection ramework aboration des textes d'applic ation MR-MEDD-149021-CS-INDV / Recrutement d'un consultant pour une mission d'assistanc Component 1: Strengthening Individual Consult Pending Impleme e pour la saisie, sur le STEP, IDA / D2880 Post Limited 6,000.00 0.00 2019-12-09 2019-12-11 2019-12-13 2019-12-17 2020-01-01 Regional Integration ant Selection ntation de l’ensemble des marchés p assés par les Projets PGDP et WACA/Mauritanie au cours d e l’exercice 2019. MR-MEDD-170446-CS-INDV / Component 3: Strengthening Individual Consult Under Implement suivi des travaux de fixation IDA / D2880 National Physical and Social Post Limited 15,000.00 0.00 2020-05-29 2020-06-24 2020-06-13 2020-07-04 2020-08-08 2020-09-22 ant Selection ation des dunes au Diawling Investments MR-MEDD-170469-CS-INDV / Elaboration de l’étude d’impa Component 3: Strengthening Individual Consult ct environnemental ou de no IDA / D2880 National Physical and Social Post Open 35,000.00 28,914.58 Signed 2020-07-06 2020-11-11 2020-08-24 2021-05-26 2020-09-14 2021-05-26 2020-10-19 2021-06-11 2021-04-17 ant Selection tice d’impact environnement Investments al pour l’extension de la digu e Nord du PND MR-MEDD-170488-CS-INDV / Component 4: National Coor Individual Consult Spécialiste en sauvegarde e IDA / D2880 Post Open 23,000.00 14,250.17 Signed 2020-06-22 2020-05-20 2020-08-10 2020-08-04 2020-08-31 2020-08-04 2020-10-05 2020-11-03 2021-01-03 dination ant Selection nvironnementalement Page 10 MR-MEDD-170410-CS-INDV / Component 2: Strengthening Individual Consult IDA / D2880 Post Open 25,000.00 0.00 Canceled 2020-08-17 2021-08-05 2020-10-05 2020-10-26 2020-11-30 2021-01-29 Révision de l'ordonnance du l the Policy and Institutional F ant Selection ittoral ramework MR-MEDD-170431-CS-INDV / Component 3: Strengthening Élaboration APS, APD et DAO Individual Consult IDA / D2880 National Physical and Social Post Open 30,000.00 28,721.26 Signed 2020-10-13 2020-09-10 2020-12-01 2021-06-01 2020-12-22 2021-06-02 2021-01-26 2021-06-17 2021-04-26 pour passage de franchissem ant Selection Investments ent du cordon dunaire MR-MEDD-170466-CS-INDV / Component 3: Strengthening Elaboration des études (APS, Individual Consult IDA / D2880 National Physical and Social Post Open 35,000.00 26,669.01 Signed 2020-07-20 2020-05-08 2020-09-07 2020-06-02 2020-09-28 2020-06-02 2020-11-02 2020-06-25 2021-05-01 APD, DAO) de l’extension de l ant Selection Investments a digue Nord du PND MR-MEDD-170408-CS-INDV / Component 2: Strengthening Individual Consult IDA / D2880 Post Open 40,000.00 31,898.11 Signed 2020-05-11 2020-06-23 2020-06-29 2020-08-24 2020-07-20 2020-09-02 2020-08-24 2020-09-18 2020-10-08 Analyse de l'ordonnance du l the Policy and Institutional F ant Selection ittoral ramework MR-MEDD-170478-CS-INDV / Component 3: Strengthening Individual Consult Elaboration du Plan de gestio IDA / D2880 National Physical and Social Post Open 33,000.00 27,409.48 Signed 2020-08-17 2021-05-24 2020-10-05 2021-05-17 2020-10-26 2021-05-24 2020-11-30 2021-06-11 2021-05-29 ant Selection n et d’exploitation de la mare Investments de Riyad MR-MEDD-170476-CS-INDV / Réalisation de l’étude sur la c Component 3: Strengthening Individual Consult aractérisation des déchets ur IDA / D2880 National Physical and Social Post Open 20,000.00 0.00 Canceled 2020-08-10 2020-06-03 2020-09-28 2020-10-19 2020-11-23 2021-01-22 ant Selection bains à NDB et proposition d’ Investments un système de gestion appro prié MR-MEDD-183319-CS-CDS / Component 3: Strengthening Complément à l'étude relativ Pending Impleme IDA / D2880 National Physical and Social Post Direct Selection Direct 4,100.00 0.00 2020-07-08 2020-07-18 2020-07-28 2020-08-04 e à l'identification de sous-pr ntation Investments ojets sociaux dans les comm unes littorales MR-MEDD-192575-CS-INDV / Component 3: Strengthening Individual Consult Etude impact environnemen IDA / D2880 National Physical and Social Post Limited 40,000.00 37,558.58 Signed 2020-09-21 2020-09-22 2020-09-26 2020-11-05 2020-10-11 2020-10-22 2020-11-15 2020-11-11 2020-12-30 ant Selection tal et social (colmatage de br Investments èches) MR-MEDD-170422-CS-INDV / Component 2: Strengthening Individual Consult Etude de la bathymétrie et d IDA / D2880 the Policy and Institutional F Post Open 38,000.00 0.00 Canceled 2020-08-18 2020-09-05 2020-10-06 2020-10-27 2020-12-01 2021-03-01 ant Selection e l'hydrométrie au PNBA ramework MR-MEDD-200735-CS-INDV / Component 2: Strengthening Recrutement d’un Expert d’a Individual Consult Pending Impleme IDA / D2880 the Policy and Institutional F Post Limited 10,500.00 0.00 2020-12-25 2020-12-30 2021-01-20 2021-02-24 2021-04-10 ppui pour la restauration et l ant Selection ntation ramework a valorisation des Mangroves et du Sporobolus MR-MEDD-200747-CS-INDV / Component 2: Strengthening Recrutement d'un Expert Inte Individual Consult IDA / D2880 the Policy and Institutional F Post Open 40,000.00 23,197.94 Signed 2020-12-15 2020-11-24 2021-02-02 2021-04-19 2021-02-23 2021-09-14 2021-03-30 2021-09-30 2021-07-28 rnational en gestion du Littor ant Selection ramework al pour un appui à la DPREM MR-MEDD-200770-CS-CDS / Recrutement d’un Consultant Component 4: National Coor Pending Impleme IDA / D2880 Post Direct Selection Direct 8,700.00 0.00 2020-09-15 2020-09-25 2020-10-20 2020-12-04 pour la formation sur STEP a dination ntation vec une assistance pour STE P MR-MEDD-203246-CS-INDV / Component 4: National Coor Individual Consult IDA / D2880 Post Limited 48,000.00 43,744.69 Signed 2020-09-10 2020-04-23 2020-09-15 2020-10-19 2020-10-06 2020-10-23 2020-11-10 2020-11-17 2021-05-09 Recrutement d’un Coordinat dination ant Selection eur Adjoint MR-MEDD-207334-CS-INDV / Component 3: Strengthening Etude de faisabilité de la rest Individual Consult IDA / D2880 National Physical and Social Post Limited 30,000.00 23,474.11 Signed 2020-12-04 2020-12-14 2020-12-09 2021-03-05 2020-12-19 2021-03-09 2021-01-14 2021-03-24 2021-02-13 auration et de la valorisation ant Selection Investments de mangroves au PND MR-MEDD-209747-CS-INDV / Recrutement de consultant ( e) individuel (le) pour la réali Component 2: Strengthening Individual Consult sation d’une Notice d’Impact IDA / D2880 the Policy and Institutional F Post Limited 30,000.00 18,710.25 Signed 2020-12-22 2020-12-23 2020-12-27 2020-01-20 2021-01-17 2021-01-29 2021-02-21 2021-03-17 2021-04-22 ant Selection Environnemental et Social (N ramework IES) pour la construction du b âtiment devant abriter l’Obs ervatoire du Littoral mauritan ien (OLM). MR-MEDD-211476-CS-INDV / Component 4: National Coor Individual Consult Recrutement d'un Chef com IDA / D2880 Post Open 20,000.00 0.00 Canceled 2021-01-15 2021-03-05 2021-03-26 2021-04-30 2022-04-27 dination ant Selection ptable pour le Projet WACA - Mauritanie Component 3: Strengthening MR-MEDD-217842-CS-INDV / Individual Consult IDA / D2880 National Physical and Social Post Direct 2,649.00 1,380.83 Signed 2021-02-09 2021-02-15 2021-02-11 2021-02-24 2021-02-16 2021-02-25 2021-02-20 2021-02-02 2021-05-21 Comptable du PGDP ant Selection Investments MR-MEDD-217844-CS-INDV / Component 3: Strengthening Individual Consult Under Implement Conseiller technique du Coor IDA / D2880 National Physical and Social Post Direct 3,090.00 0.00 2021-02-09 2021-02-15 2021-02-11 2021-01-28 2021-02-13 2021-02-01 2021-02-16 2021-05-17 ant Selection ation dinateur du PGDP Investments Component 3: Strengthening MR-MEDD-217850-CS-INDV / Individual Consult IDA / D2880 National Physical and Social Post Direct 2,649.00 2,560.06 Signed 2021-02-09 2021-02-15 2021-02-11 2021-01-31 2021-02-14 2021-02-02 2021-02-19 2021-02-03 2021-05-20 Expert SIG du PGDP ant Selection Investments MR-MEDD-218369-CS-INDV / Component 4: National Coor Individual Consult Recrutement de l'Expert en s IDA / D2880 Post Direct 29,486.00 2,375.03 Signed 2021-02-15 2021-05-23 2021-02-17 2021-02-15 2021-02-20 2021-02-01 2021-02-24 2021-02-02 2022-02-24 dination ant Selection uivi/évaluation MR-MEDD-218371-CS-INDV / Component 4: National Coor Individual Consult IDA / D2880 Post Direct 29,486.00 2,375.03 Signed 2021-02-15 2021-05-23 2021-02-17 2021-02-26 2021-02-19 2021-02-01 2021-02-23 2021-02-02 2022-02-23 Recrutement de l'Auditeur In dination ant Selection terne MR-MEDD-218374-CS-INDV / Component 4: National Coor Individual Consult Recrutement du Spécialiste d IDA / D2880 Post Direct 29,486.00 0.00 Canceled 2021-02-15 2021-05-24 2021-02-17 2021-02-19 2021-02-23 2022-02-23 dination ant Selection e Passation des Marchés MR-MEDD-218375-CS-INDV / Component 4: National Coor Individual Consult Recrutement de l'assistant e IDA / D2880 Post Direct 10,600.00 853.35 Signed 2021-02-15 2021-02-15 2021-02-17 2021-02-16 2021-02-19 2021-02-26 2021-02-23 2021-02-02 2022-02-23 dination ant Selection n passation de marchés MR-MEDD-218377-CS-INDV / Recrutement du spécialiste e Component 4: National Coor Individual Consult IDA / D2880 Post Direct 29,486.00 2,375.03 Signed 2021-02-15 2021-02-15 2021-02-17 2021-02-25 2021-02-19 2021-02-26 2021-02-23 2021-02-02 2022-02-23 n Sauvegarde Sociale, Sociét dination ant Selection é Civile et Genre MR-MEDD-218381-CS-INDV / Component 4: National Coor Individual Consult Recrutement d'un Spécialiste IDA / D2880 Post Direct 29,486.00 2,375.03 Signed 2021-02-15 2021-05-24 2021-02-17 2021-02-01 2021-02-19 2021-06-10 2021-02-23 2021-02-02 2022-02-23 dination ant Selection en Communication Page 11 MR-MEDD-218382-CS-INDV / Component 4: National Coor Individual Consult Under Implement Recrutement de Coordinateu IDA / D2880 Post Direct 55,600.00 0.00 2021-02-15 2021-02-15 2021-02-17 2021-02-19 2021-02-23 2022-02-23 dination ant Selection ation r (ce) du Projet MR-MEDD-219143-CS-INDV / Component 4: National Coor Individual Consult Recrutement d'un comptable IDA / D2880 Post Limited 30,000.00 20,016.68 Signed 2021-02-11 2021-03-19 2021-02-16 2021-02-25 2021-03-09 2021-02-01 2021-04-13 2021-02-02 2021-10-10 dination ant Selection en chef pour l'UGP MR-MEDD-225611-CS-INDV / Recrutement d'un Consultant Component 4: National Coor Individual Consult Individuel pour le dérouleme IDA / D2880 Post Direct 10,000.00 9,941.98 Signed 2021-03-22 2021-03-23 2021-04-01 2021-03-18 2021-04-22 2021-03-18 2021-05-21 2021-03-23 2021-06-20 dination ant Selection nt sur STEP des activités du P rojet PGDP pour les exercice s 2019,2018 et 2017. MR-MEDD-200742-CS-INDV / Component 2: Strengthening Recrutement d’un consultant Individual Consult IDA / D2880 the Policy and Institutional F Post Limited 15,000.00 0.00 Canceled 2020-12-25 2020-12-30 2021-01-20 2021-02-24 2021-04-25 pour compléter l’étude sur la ant Selection ramework Baie de l’Etoile MR-MEDD-74185-CS-INDV / Component 2: Strengthening Actualisation du plan d'amén Individual Consult IDA / D2880 the Policy and Institutional F Post Open 29,500.00 0.00 Canceled 2018-09-20 2018-11-08 2018-11-29 2019-01-03 2019-07-02 agement et de gestion de la ant Selection ramework Baie de l'Etoile de NDB MR-MEDD-200710-CS-INDV / Component 2: Strengthening Recrutement d’un Consultant Individual Consult IDA / D2880 the Policy and Institutional F Post Limited 30,000.00 0.00 Canceled 2020-11-23 2020-11-28 2020-12-19 2021-01-23 2021-03-24 pour compléter le guide des ant Selection ramework acteurs et métiers du littoral MR-MEDD-170414-CS-INDV / Component 2: Strengthening Élaboration du décret portant Individual Consult IDA / D2880 the Policy and Institutional F Post Limited 10,000.00 0.00 Canceled 2020-05-11 2020-05-16 2020-06-06 2020-07-11 2020-10-09 modalités du fonctionnement ant Selection ramework de l'observatoire du littoral MR-MEDD-170415-CS-INDV / Component 2: Strengthening Individual Consult Révision du décret portant cr IDA / D2880 the Policy and Institutional F Post Limited 10,000.00 0.00 Canceled 2020-05-18 2020-05-23 2020-06-13 2020-07-18 2020-09-01 ant Selection éation du conseil consultatif ramework du littoral MR-MEDD-74187-CS-INDV / Component 3: Strengthening Individual Consult Etude relative à la mise en pl IDA / D2880 National Physical and Social Post Open 21,000.00 0.00 Canceled 2018-09-18 2018-11-06 2018-11-27 2019-01-01 2019-06-30 ant Selection ace de l'éco-loge Investments MR-MEDD-170403-CS-INDV / Component 2: Strengthening Élaboration du Plan de Gestio Individual Consult IDA / D2860 the Policy and Institutional F Post Open 25,000.00 0.00 Canceled 2020-05-25 2020-07-13 2020-08-03 2020-09-07 2020-11-06 n Environnementale et Social ant Selection ramework e de la Zone Franche de Nou adhibou MR-MEDD-74191-CS-INDV / Component 2: Strengthening Individual Consult Elaboration d'une carte de po IDA / D2880 the Policy and Institutional F Post Limited 30,000.00 0.00 Canceled 2018-11-13 2018-11-18 2018-12-09 2019-01-13 2019-07-12 ant Selection tentialités de la Zone franche ramework de NDB MR-MEDD-170401-CS-INDV / Component 2: Strengthening Individual Consult Élaboration d'une carte de po IDA / D2880 the Policy and Institutional F Post Open 30,000.00 0.00 Canceled 2020-08-25 2020-10-13 2020-11-03 2020-12-08 2021-06-06 ant Selection tentialités pour la zone Franc ramework he de NDB MR-MEDD-170174-CS-INDV / Recrutement d'une assistanc Component 2: Strengthening Individual Consult e technique pour l'intégratio IDA / D2880 the Policy and Institutional F Post Open 25,000.00 0.00 Canceled 2020-07-15 2020-09-02 2020-09-23 2020-10-28 2020-12-27 ant Selection n de la dimension résilience ramework climatique dans l'ensemble d es stratégies du littoral MR-MEDD-74190-CS-INDV / Component 3: Strengthening Elaboration d'un plan de gest Individual Consult IDA / D2880 National Physical and Social Post Open 34,500.00 0.00 Canceled 2018-09-19 2018-11-07 2018-11-28 2019-01-02 2019-07-01 ion environnementale et soci ant Selection Investments ale du site de l'éco-loge MR-MEDD-170425-CS-INDV / Etude sur l'état des lieux et l Component 2: Strengthening Individual Consult e mapping des bases de don IDA / D2880 the Policy and Institutional F Post Open 20,000.00 0.00 Canceled 2020-07-20 2020-09-07 2020-09-28 2020-11-02 2021-05-01 ant Selection nées et systèmes géographi ramework ques des zones côtières de l a Mauritanie MR-MEDD-74174-CS-INDV / Component 2: Strengthening Individual Consult Actualisation du schéma opé IDA / D2880 the Policy and Institutional F Post Limited 25,500.00 0.00 Canceled 2018-12-03 2018-12-08 2018-12-29 2019-02-02 2019-08-01 ant Selection rationnel de la Zone franche ramework de NDB MR-MEDD-200714-CS-INDV / Recrutement d’un Consultant pour l’élaboration du décret Component 3: Strengthening Individual Consult portant modalités du fonctio IDA / D2880 National Physical and Social Post Limited 20,000.00 0.00 Canceled 2020-11-30 2020-12-05 2020-12-26 2021-01-30 2021-02-05 ant Selection nnement de l’Observatoire d Investments u Littoral et la révision du dé cret portant création du Cons eil Consultatif du Littoral MR-MEDD-124785-CS-INDV / etude sur l'état des lieux et l Component 2: Strengthening Individual Consult e mapping des bases de don IDA / D2880 the Policy and Institutional F Post Limited 20,000.00 0.00 Canceled 2019-08-05 2019-08-10 2019-08-15 2019-09-12 2019-10-12 ant Selection nees et SIG des zones côtière ramework s et arides de la mauritanie. MR-MEDD-74154-CS-INDV / Rédaction des termes de réfé Component 2: Strengthening Individual Consult rence de l'étude relative aux IDA / D2880 the Policy and Institutional F Post Limited 12,000.00 0.00 Canceled 2018-10-03 2018-10-08 2018-10-29 2018-12-03 2019-06-01 ant Selection plans de résilience de N'Diag ramework o (inclus consultations, atelie rs, séminaires) MR-MEDD-137101-CS-INDV / Component 3: Strengthening sélection d'un consultant pou Individual Consult IDA / D2880 National Physical and Social Post Limited 30,000.00 0.00 Canceled 2019-10-08 2019-10-13 2019-10-20 2019-10-23 2019-12-22 r préparer le dossier relatif a ant Selection Investments ux fixations des dunes du litt oral MR-MEDD-200737-CS-INDV / Component 2: Strengthening Recrutement d’un consultant Individual Consult IDA / D2880 the Policy and Institutional F Post Limited 20,000.00 0.00 Canceled 2020-12-24 2020-12-29 2021-01-19 2021-02-23 2021-04-24 pour adapter le guide de bon ant Selection ramework nes pratiques /pestes et pesti cides MR-MEDD-74192-CS-INDV / Component 3: Strengthening Individual Consult Evaluation des risques d'inon IDA / D2880 National Physical and Social Post Limited 29,000.00 0.00 Canceled 2018-12-17 2018-12-22 2019-01-12 2019-02-16 2019-08-15 ant Selection dations pour la ville de NBD Investments Page 12 MR-MEDD-170396-CS-INDV / Component 2: Strengthening Etat de lieu de la pollution m Individual Consult IDA / D2880 the Policy and Institutional F Post Open 40,000.00 0.00 Canceled 2020-09-15 2020-11-03 2020-11-24 2020-12-29 2021-06-27 étallique dans le milieu littor ant Selection ramework al de la baie du Lévrier MR-MEDD-158682-CS-INDV / Component 2: Strengthening étude de faisabilité de la dél Individual Consult IDA / D2880 the Policy and Institutional F Post Open 40,000.00 0.00 Canceled 2020-02-13 2020-04-02 2020-04-23 2020-05-28 2020-11-24 ocalisation du Centre de trait ant Selection ramework ement de l'or de Chami MR-MEDD-74172-CS-INDV / Component 2: Strengthening Individual Consult Analyse du schéma opération IDA / D2880 the Policy and Institutional F Post Open 22,500.00 0.00 Canceled 2020-01-29 2020-02-10 2020-03-18 2020-04-08 2020-05-13 2020-07-12 ant Selection nel de la Zone franche de ND ramework B MR-MEDD-82696-CS-INDV / r Component 2: Strengthening ecrutement d'un consultant p Individual Consult IDA / D2880 the Policy and Institutional F Post Limited 25,000.00 0.00 Canceled 2018-10-31 2018-11-20 2018-11-05 2018-11-26 2018-12-31 2019-06-29 our appuyer la cellule Chang ant Selection ramework ement Climatique MR-MEDD-170400-CS-INDV / Etude pour réaliser un état d Component 2: Strengthening es lieux des capacités des usi Individual Consult IDA / D2880 the Policy and Institutional F Post Open 20,000.00 0.00 Canceled 2020-07-15 2020-08-18 2020-09-02 2020-09-23 2020-10-28 2021-01-26 nes de production de farine d ant Selection ramework e poisson d'Elbountiya en ma tière de gestion environneme ntale MR-MEDD-157985-CS-INDV / Component 2: Strengthening Etude de faisabilité de la dél Individual Consult IDA / D2880 the Policy and Institutional F Post Limited 42,000.00 0.00 Canceled 2020-02-10 2020-02-19 2020-02-15 2020-02-26 2020-03-11 2020-04-10 ocalisation du centre de trait ant Selection ramework ement de l'or à Chami MR-MEDD-232477-CS-INDV / Component 4: National Coor Individual Consult Pending Impleme Recrutement d’un spécialiste IDA / D2880 Post Open 30,900.00 0.00 2021-05-25 2021-07-13 2021-08-03 2021-09-07 2022-09-04 dination ant Selection ntation en développement institution nel MR-MEDD-232478-CS-INDV / Component 2: Strengthening Individual Consult Recrutement d’un juriste en IDA / D2880 the Policy and Institutional F Post Limited 12,000.00 49,709.88 Signed 2021-06-15 2021-07-19 2021-06-20 2021-08-06 2021-07-11 2021-08-16 2021-08-15 2021-09-02 2022-02-11 ant Selection appui au MEDD ramework MR-MEDD-232495-CS-INDV / Component 4: National Coor Individual Consult Recrutement d’un Consultant IDA / D2880 Post Open 40,000.00 3,997.78 Signed 2021-08-10 2021-06-21 2021-09-28 2021-09-09 2021-10-19 2021-09-09 2021-11-17 2021-09-10 2022-02-15 dination ant Selection pour l’évaluation à mi-parcou rs MR-MEDD-232498-CS-INDV / Component 2: Strengthening Un Consultant Individuel pou Individual Consult Pending Impleme IDA / D2880 the Policy and Institutional F Post Open 30,000.00 0.00 2021-07-20 2021-09-07 2021-09-28 2021-11-02 2022-01-31 r Définir les objectifs, le cadr ant Selection ntation ramework e et le contenu de l’Observat oire du Littoral MR-MEDD-236658-CS-INDV / Recrutement du Spécialiste d Component 4: National Coor Individual Consult IDA / D2880 Post Open 30,000.00 27,174.73 Signed 2021-06-04 2021-06-02 2021-07-23 2021-08-11 2021-08-13 2021-08-04 2021-09-17 2021-08-17 2022-09-14 e Passation des Marchés du P dination ant Selection rojet WACA-Mauritanie MR-MEDD-200718-CS-INDV / Component 3: Strengthening Recrutement d’un Consultant Individual Consult IDA / D2880 National Physical and Social Post Limited 20,000.00 0.00 Canceled 2020-11-30 2021-06-10 2020-12-05 2020-12-26 2021-01-30 2021-03-31 pour l’élaboration du dossier ant Selection Investments technique pour la fixation de s dunes du Littoral MR-MEDD-249821-CS-INDV / RECRUTEMENT D’UN CONSU Component 2: Strengthening LTANT INTERNATIONAL INDIV Individual Consult IDA / D2880 the Policy and Institutional F Post Direct 23,000.00 25,000.00 Signed 2021-09-15 2021-10-21 2021-09-25 2021-11-10 2021-10-16 2021-11-12 2021-11-20 2021-11-16 2022-01-04 IDUEL POUR L’ELABORATION ant Selection ramework D’UNE LOI SUR L’EVALUATIO N D’IMPACT ENVIRONNEMEN TAL EN MAURITANIE MR-MEDD-249825-CS-INDV / Recrutement d'un Consultant Component 2: Strengthening Individuel pour l'élaboration Individual Consult IDA / D2880 the Policy and Institutional F Post Open 30,000.00 0.00 Canceled 2021-09-15 2021-11-03 2021-11-03 2021-11-24 2021-12-29 2022-03-29 d'une Notice d'Impact et Envi ant Selection ramework ronnementale Sociale pour l' addiction de l'eau potable du Parc National de Diawling (P ND) MR-MEDD-170430-CS-INDV / Component 3: Strengthening Individual Consult Etude pour la préparation du IDA / D2880 National Physical and Social Post Open 20,000.00 0.00 Canceled 2020-06-22 2020-08-10 2020-08-31 2020-10-05 2021-01-03 ant Selection dossier technique pour la fixa Investments tion des dunes MR-MEDD-232492-CS-INDV / Component 3: Strengthening Individual Consult Élaborer un plan genre pour l IDA / D2880 National Physical and Social Post Open 20,000.00 0.00 Canceled 2021-07-20 2021-09-07 2021-09-28 2021-10-27 2022-01-25 ant Selection e projet Investments MR-MEDD-232493-CS-INDV / Component 3: Strengthening Individual Consult faire une évaluation environn IDA / D2880 National Physical and Social Post Open 20,000.00 0.00 Canceled 2021-07-19 2021-09-06 2021-09-27 2021-11-01 2022-01-30 ant Selection ementale et sociale des sous Investments projets sociaux MR-MEDD-232497-CS-INDV / Evaluer les besoins (études, Component 3: Strengthening données à acquérir) et défini Individual Consult IDA / D2880 National Physical and Social Post Limited 10,000.00 0.00 Canceled 2021-09-14 2021-09-19 2021-10-10 2021-11-14 2022-01-13 r les indicateurs de suivi pour ant Selection Investments une meilleure compréhensio n de l’évolution du littoral MR-MEDD-170486-CS-INDV / Expert en système de gestio Component 3: Strengthening Individual Consult n de l'information environne IDA / D2880 National Physical and Social Post Open 50,000.00 0.00 Canceled 2020-06-15 2020-08-18 2020-08-04 2020-08-25 2020-09-29 2020-12-28 ant Selection mentale pour le littoral (Syst Investments ème de données et d'informa tion) MR-MEDD-170484-CS-INDV / Component 3: Strengthening Individual Consult Expert Côtier (gestion intégr IDA / D2880 National Physical and Social Post Open 50,000.00 0.00 Canceled 2020-05-15 2020-07-09 2020-07-03 2020-07-24 2020-08-28 2021-08-25 ant Selection ée des zones costières ) Investments MR-MEDD-170420-CS-INDV / Component 2: Strengthening Individual Consult Révision du décret portant cr IDA / D2880 the Policy and Institutional F Post Open 15,000.00 0.00 Canceled 2020-06-08 2020-07-27 2020-08-17 2020-09-21 2020-11-05 ant Selection éation du FIE ramework MR-MEDD-129310-CS-CQS / Component 3: Strengthening Opérationalisation et Mise en IDA / D2880 National Physical and Social Post Direct Selection Direct 40,000.00 0.00 Canceled 2019-09-24 2019-10-01 2019-09-27 2019-10-02 2020-03-30 place d'un système de gestio Investments n de plaintes pour le Projet W ACA MR-MEDD-76164-CS-INDV / Component 2: Strengthening Individual Consult Recrutement d'un Comptable IDA / D2880 the Policy and Institutional F Post Open 18,000.00 0.00 Canceled 2018-08-31 2018-10-19 2018-11-09 2018-12-14 2019-06-12 ant Selection pour le Projet ramework Page 13 MR-MEDD-267098-CS-INDV / Recrutement d'un responsabl Component 4: National Coor Individual Consult IDA / D2880 Post Open 28,000.00 0.00 Signed 2021-12-15 2021-12-11 2022-01-04 2022-09-07 2022-01-25 2022-09-13 2022-02-09 2022-08-08 e Administratif et Financier dination ant Selection pour le Projet WACA-MR MR-MEDD-315538-CS-INDV / Recrutement d’un consultant Component 3: Strengthening Individual Consult Pending Impleme individuel pour faire le contrô IDA / D2880 National Physical and Social Post Open - National 40,000.00 0.00 2022-10-24 2022-12-12 2023-01-02 2023-02-06 2023-06-06 ant Selection ntation le et le suivi des travaux de fi Investments xation des dunes du littoral MR-MEDD-267611-CS-INDV / Recrutement d'un Consultant Individuel pour réaliser l'étud Component 2: Strengthening Individual Consult e sur l'état de lieux, Diagnost IDA / D2880 the Policy and Institutional F Post Limited 40,000.00 0.00 Canceled 2022-01-24 2022-01-29 2022-02-19 2022-03-26 2023-06-24 ant Selection ic des études existantes sur l ramework es dynamiques et évolutions du littoral dans le Secteur Tr ansfrontalier Sénégalo-Maurit anien MR-MEDD-315544-CS-INDV / Recrutement d’un consultant Component 3: Strengthening Individual Consult individuel pour suivre le trait IDA / D2880 National Physical and Social Post Open - National 40,000.00 0.00 Canceled 2022-10-18 2022-12-06 2022-12-27 2023-01-31 2023-05-01 ant Selection de côtes dans le secteur tran Investments sfrontalier Mauritanie-Sénéga l MR-MEDD-315577-CS-INDV / Component 3: Strengthening Recrutement d’un consultant Individual Consult Under Implement IDA / D2880 National Physical and Social Post Open - National 16,000.00 0.00 2022-10-20 2022-12-15 2022-12-08 2022-12-29 2023-01-27 2023-03-28 individuel pour L’élaboration ant Selection ation Investments du plan d’engagement des p arties prenantes MR-MEDD-315583-CS-INDV / Component 4: National Coor Individual Consult Pending Impleme Recrutement d’un Consultant IDA / D2880 Post Open - National 10,850.00 0.00 2022-10-24 2022-12-12 2023-01-02 2023-02-06 2023-03-23 dination ant Selection ntation Individuel pour le Site Web d u Projet MR-MEDD-232484-CS-INDV / Component 3: Strengthening Un Consultant Individuel pou Individual Consult IDA / D2880 National Physical and Social Post Limited 14,500.00 0.00 Canceled 2021-06-28 2021-07-03 2021-07-24 2021-08-28 2022-02-24 r assurer le suivi des travaux ant Selection Investments de franchissement et de cons truction de bacs MR-MEDD-232483-CS-INDV / Recrutement d’un consultant Component 3: Strengthening Individual Consult Individuel pour Faire le contr IDA / D2880 National Physical and Social Post Limited 15,000.00 0.00 Canceled 2021-07-14 2021-07-19 2021-08-09 2021-09-13 2021-12-12 ant Selection ôle et le suivi des travaux de Investments fixation des dunes du littoral MR-MEDD-315490-CS-INDV / Recrutement d’un consultant Component 2: Strengthening Individual Consult Open - Internationa individuel pour l’étude sur l' IDA / D2880 the Policy and Institutional F Post 50,000.00 0.00 Signed 2022-10-17 2022-10-09 2022-12-05 2022-12-13 2022-12-26 2022-12-21 2023-01-30 2023-03-31 ant Selection l organisation et le fonctionne ramework ment de l'Observatoire du Lit toral MR-MEDD-335938-CS-INDV / Component 4: National Coor Individual Consult Under Implement Recrutement d'un Auditeur I IDA / D2880 Post Limited 17,000.00 0.00 2023-01-16 2023-01-26 2023-01-21 2023-01-26 2023-02-10 2024-02-10 dination ant Selection ation nterne à mi-temps pour le Pr ojet WACA-MR MR-MEDD-315582-CS-INDV / Component 2: Strengthening Un expert juriste en appui à l Individual Consult IDA / D2880 the Policy and Institutional F Post Open - National 16,000.00 0.00 Canceled 2022-11-14 2023-01-02 2023-01-23 2023-02-27 2023-06-27 a Direction Réglementaire et ant Selection ramework des Accords Multilatéraux (DI RAM) MR-MEDD-351063-CS-INDV / Component 2: Strengthening Recrutement d’un consultant Individual Consult Open - Internationa Pending Impleme IDA / D2880 the Policy and Institutional F Post 50,000.00 0.00 2023-07-17 2023-08-20 2023-09-04 2023-10-09 2024-01-07 individuel pour Élaborer un p ant Selection l ntation ramework rojet de loi relatif au littoral MR-MEDD-351069-CS-INDV / Component 2: Strengthening Recruter un expert en appui Individual Consult IDA / D2880 the Policy and Institutional F Post Limited 17,000.00 0.00 Canceled 2023-06-05 2023-06-10 2023-07-01 2023-07-30 2024-07-29 au volet communication / Ca ant Selection ramework binet de la Ministre (MEDD) MR-MEDD-363185-CS-INDV / Un expert juriste en appui au Component 2: Strengthening Individual Consult Ministère de l’environnement IDA / D2880 the Policy and Institutional F Post Limited 25,000.00 0.00 Canceled 2023-06-19 2023-06-24 2023-07-09 2023-08-13 2023-11-11 ant Selection et du Développement Durabl ramework e et au Projet WACA-MR Page 14 PROCUREMENT PLAN (Textual Part) Project information: [Vietnam] [JSDF - STRENGTHENING PREPAREDNESS AND RESPONSE TO COVID-19 AT THE GRASSROOTS LEVEL IN VIETNAM] [P174401] Project Implementation agency: [Institute for Social Development Studies] Date of the Procurement Plan: [April 27, 2022] Period covered by this Procurement Plan: [April 2022 – December 2022] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Vietnam Public Procurement Law dated 2013 and the regulations guiding its implementation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations, ensuring compliance with the core principles of the WB’s Procurement Regulations and using sample procurement documents acceptable to the WB. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable]; Works: [is not applicable] Hands-on Expanded Implementation Support (HEIS): Not Applicable. PROCUREMENT Vietnam : JSDF - Strengthening Preparedness and Response to COVID-19 at the Grassroots level in Vietnam PLAN General Information Country: Vietnam Bank’s Approval Date of the Original Procurement Plan: 2022-04-28 Revised Plan Date(s): (comma delineated, leave blank if 2023-05-24 none) Project ID: P174401 GPN Date: 2022-04-08 Project Name: JSDF - Strengthening Preparedness and Response to COVID-19 at the Grassroots level in Vietnam Loan / Credit No: TF / B6532 Institute for Social Development Studies Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Project Management and Ad G-1 / Office Equipment 202 Request for Quota Single Stage - One E TF / B6532 ministration, Monitoring and Post Open - National 20,400.00 0.00 Signed 2022-07-05 2022-07-28 2022-08-27 2 tions nvelope Evaluation, and Knowledge Dissemination Building capacities at the gr assroots level in Preparedne G-2 / Office Equipment 202 Request for Quota Single Stage - One E Pending Impl TF / B6532 ss for, Response to, Recover Post Open - National 16,000.00 0.00 2023-06-04 2023-06-28 2023-07-28 3 tions nvelope ementation y and Resilience from COVID -19 and ot her health emerg encies NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Project Management and Ad CQS-1 / Consultant firm to c Consultant Qualifi TF / B6532 ministration, Monitoring and Post Open - National 25,000.00 23,955.15 Signed 2022-04-28 2022-05-13 2022-05-18 2022-05-30 2022-06-30 2022-07-11 2022-08-10 2022-07-14 2022-08-21 2022-10-12 onduct baseline survey cation Selection Evaluation, and Knowledge Dissemination Project Management and Ad Consultant Qualifi Under Implement CQS-2 / Recruit Audit firm TF / B6532 ministration, Monitoring and Post Open - National 15,000.00 0.00 2022-10-10 2022-12-22 2022-10-12 2022-11-16 2022-12-31 2023-01-05 2025-06-20 cation Selection ation Evaluation, and Knowledge Dissemination INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Building capacities at the gr assroots level in Preparedne CSI-1 / Senior Project Officer Individual Consult TF / B6532 ss for, Response to, Recover Prior Limited 76,800.00 75,477.42 Signed 2022-04-27 2022-04-29 2022-04-28 2022-04-29 2022-05-12 2022-05-10 2022-05-16 2022-05-12 2024-12-31 Cum Procurement Specialist ant Selection y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne Individual Consult CSI-2 / Project Officer TF / B6532 ss for, Response to, Recover Post Limited 54,400.00 53,471.47 Signed 2022-04-28 2022-04-29 2022-04-29 2022-05-05 2022-05-06 2022-05-06 2022-05-11 2022-05-07 2024-12-31 ant Selection y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-3 / Chief Technical Mana Individual Consult TF / B6532 ss for, Response to, Recover Post Limited 47,520.00 46,260.69 Signed 2022-04-28 2022-04-29 2022-05-06 2022-04-29 2022-05-09 2022-06-06 2022-05-16 2022-05-07 2025-01-12 ger working for CPMU ant Selection y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-4.2 / Recruiting coordina Individual Consult TF / B6532 ss for, Response to, Recover Post Limited 32,000.00 31,398.55 Signed 2022-04-28 2022-04-29 2022-05-06 2022-04-29 2022-05-10 2022-05-10 2022-05-16 2022-05-13 2024-12-31 tor for Khanh Hoa ant Selection y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-4.1 / Recruiting coordina Individual Consult TF / B6532 ss for, Response to, Recover Post Limited 32,000.00 31,398.55 Terminated 2022-04-28 2022-04-29 2022-05-06 2022-04-29 2022-05-10 2022-05-10 2022-05-17 2022-05-12 2024-12-31 tor for Vinh Phuc ant Selection y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-4.3 / Recruiting coordina Individual Consult TF / B6532 ss for, Response to, Recover Post Limited 32,000.00 31,398.55 Signed 2022-04-28 2022-04-29 2022-05-06 2022-04-29 2022-05-08 2022-05-10 2022-05-11 2022-05-12 2024-12-31 tor for Long An ant Selection y and Resilience from COVID -19 and ot her health emerg encies Project Management and Ad CSI-5 / Communication Speci Individual Consult TF / B6532 ministration, Monitoring and Post Open 18,000.00 0.00 Signed 2022-06-27 2023-06-20 2022-07-23 2022-07-28 2022-07-25 2022-07-29 2022-07-26 2024-12-31 alist ant Selection Evaluation, and Knowledge Dissemination Developing and piloting mod CSI-6 / Network Operation T els to support the most vuln Individual Consult TF / B6532 Post Open - National 59,850.00 0.00 Signed 2022-08-08 2022-08-09 2022-08-19 2022-08-18 2022-08-22 2022-08-19 2022-08-24 2022-12-31 echnical Specialist erable groups in the prepare ant Selection dness and response to COVI D-19 Page 1 Building capacities at the gr CSI-7 / Consultant to develo assroots level in Preparedne Individual Consult p intersectoral collaboration TF / B6532 ss for, Response to, Recover Post Open - National 7,500.00 7,070.78 Signed 2022-08-08 2023-01-11 2022-08-19 2022-08-18 2022-08-22 2022-08-19 2022-08-24 2022-08-29 2022-12-31 ant Selection plan y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr CSI-8 / Consultant to develo assroots level in Preparedne p guideline on infection prev Individual Consult TF / B6532 ss for, Response to, Recover Post Open - National 4,050.00 3,872.10 Signed 2022-08-08 2023-05-19 2022-08-19 2022-08-18 2022-08-22 2022-08-19 2022-08-24 2022-09-29 2022-12-31 ention and control inside co ant Selection y and Resilience from COVID mmunity health stations -19 and ot her health emerg encies CSI-9 / Consultant to develo Building capacities at the gr p Guideline on provision of e assroots level in Preparedne Individual Consult ssential healthcare services TF / B6532 ss for, Response to, Recover Post Open - National 9,150.00 8,754.30 Signed 2022-08-08 2023-06-20 2022-08-19 2022-08-18 2022-08-22 2022-08-19 2022-08-24 2022-08-29 2022-12-31 ant Selection and patient management, tre y and Resilience from COVID atment support and patient r -19 and ot her health emerg eferral during pandemics encies Raising awareness and know CSI-10 / Consultant to devel ledge towards changing attit Individual Consult op Guideline on risk commun TF / B6532 Post Open - National 7,600.00 7,239.14 Signed 2022-08-08 2022-08-09 2022-08-19 2022-08-25 2022-08-22 2022-08-26 2022-08-24 2022-09-08 2022-12-31 udes and behavior of the co ant Selection ication mmunity through risk comm unication CSI-11 / Consultant to upgra Project Management and Ad Individual Consult Under Implement de website for establishment TF / B6532 ministration, Monitoring and Post Open - National 2,000.00 0.00 2022-11-14 2022-11-14 2022-11-25 2022-11-26 2022-12-01 2022-12-31 ant Selection ation and operation of an informati Evaluation, and Knowledge on hub Dissemination Building capacities at the gr CSI-4.1.1 / Vinh Phuc Provinc assroots level in Preparedne ial Project Coordinator (Termi Individual Consult Under Implement TF / B6532 ss for, Response to, Recover Post Limited 19,000.00 0.00 2023-05-04 2023-05-04 2023-05-11 2023-05-12 2023-05-15 2024-12-31 nate contract CSI-4.1/2022, r ant Selection ation y and Resilience from COVID ecruit new person on board) -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne Individual Consult Under Implement CSI-12 / Project Assistant TF / B6532 ss for, Response to, Recover Post Open - National 20,000.00 0.00 2023-06-01 2023-05-22 2023-06-22 2023-06-24 2023-06-26 2024-12-31 ant Selection ation y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-13 / Midterm review con Individual Consult Pending Impleme TF / B6532 ss for, Response to, Recover Post Open - National 7,000.00 0.00 2023-06-01 2023-06-27 2023-06-30 2023-07-05 2023-09-01 sultant ant Selection ntation y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-14 / Community develop Individual Consult Under Implement TF / B6532 ss for, Response to, Recover Post Open - National 24,000.00 0.00 2023-06-15 2023-06-20 2023-06-29 2023-06-30 2023-07-01 2024-12-31 ment Specialist ant Selection ation y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-15.1 / Vinh Phuc Provinci Individual Consult Under Implement TF / B6532 ss for, Response to, Recover Post Limited 5,000.00 0.00 2023-06-21 2023-06-22 2023-06-28 2023-06-30 2023-07-03 2024-12-31 al Project Assistant ant Selection ation y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-15.2 / Khanh Hoa Provin Individual Consult Under Implement TF / B6532 ss for, Response to, Recover Post Limited 5,000.00 0.00 2023-06-21 2023-06-22 2023-06-28 2023-06-30 2023-07-03 2024-12-31 cial Project Assistant ant Selection ation y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-15.3 / Long An Provincial Individual Consult Under Implement TF / B6532 ss for, Response to, Recover Post Limited 5,000.00 0.00 2023-06-21 2023-06-22 2023-06-28 2023-06-30 2023-07-03 2024-12-31 Project Assistant ant Selection ation y and Resilience from COVID -19 and ot her health emerg encies Page 2 Procurement Plan I. General 1. Project Information Country : Kenya Recipient : Republic of Kenya Project Name : National Agriculture and Rural Inclusive Growth Loan Credit No. : IDA 59000 2. Date of General Procurement Notice : 9th February 2018 3. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services 1. Thresholds for the Method of Procurement: Method of Procurement Thresholds for Method (US$ equivalent) Open International (Goods) Equal to or more than 3 million Open National ( Goods) – Open < $3 million Tender as per PPDA 2015 RFQ (Goods) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Open International (Works) Equal to or more than 15 million Open National (Works) - Open Less than 15 million Tender as per PPDA 2015 RFQ (works) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Method of Procurement Thresholds for Method (US$ equivalent) Open International (Non-consulting Equal to or More than 3 million Services) Open National (Non-consulting Less than 3 million Services) - Open Tender as per PPDA 2015 Direct Contracting No threshold; meet requirements of Bank’s Procurement Regulations Prior Review: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection (Project Procurement Risk Rating is “High”): (a) Goods, information technology and Non-consulting Services: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1.5 million (b) Works (including turnkey, supply & installation of plant and equipment and PPP); First procurement under the project irrespective of value and all procurements estimated to cost more than USD 5 million and The prior review thresholds will be reviewed during the implementation of the project and modified, based on the risk assessment. 2. For contracts subject to prior review, the Borrower shall seek the Bank’s no objection before agreeing to: a. an extension of the stipulated time for execution of a contract that has an impact on the planned completion of the project; b. any material modification of the scope of the Works, Goods, Non- consulting services or Consulting Services, or other significant changes to the terms and conditions of the contract; c. any variation order or contract amendment (except in cases of extreme urgency), including due to extension of time, that singly or combined with all previous variation orders or amendments, increases the original contract amount by more than 15% (fifteen percent); or d. the proposed termination of the contract. The Borrower / IA shall provide a copy of all amendments to the contract to the Bank for its records. 3. Prequalification Not Applicable Domestic Preference. The provision of domestic preference shall be applied in the procurement of goods following international market approach in accordance with Annex VI of the Regulations. Domestic preference shall not apply in the procurement of works. 4. Reference to Standard Procurement Documents Bank’s Standard RFB Goods and RFP Consulting Services dated July 2016 will be used as a base and incorporating suitable modifications and the same would be agreed with the Bank subject international competition. 5. Any Other Special Procurement Arrangements A. Procurement approach under CDD Approach by Communities: Applicable if stipulated in the PAD. B. When approaching the national market, as agreed in the Procurement Plan, the Open Tender procedure of Public Procurement and Asset Disposal Act 2015 and Regulations 2017 may be used. The specific Requirements for national open competitive procurement include the following: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. Other national procurement arrangements (other than national open competitive procurement), that may be applied by the Borrower (such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti-Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. In all cases, the national procurement procedures to be used shall give due attention to quality aspects. 6. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Selection methods of procurement of Consultants' Services (Firms): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Quality and Cost Based As per requirements of para 7.3 of the Selection (QCBS) Regulations Quality Based Selection As per requirements of para 7.8 to 7.10 (QBS) of the Regulations Selection based on a Fixed As per requirements of para 7.4 and 7.5 of the Budget (FBS) Regulations Selection Based on Least As per requirements of para 7.6 and 7.7 of the Cost Basis (LCS) Regulations Selection based on As per requirements of para 7.11 and 7.12 of Consultant’s Qualification the Regulations (CQ) Direct Must meet the requirements of Para 7.13 to 7.15 of the Regulations, and with prior agreement in PP with the Bank. The short list may consist of all National consultants in case the estimated cost is less than USD 300,000 Procurement methods for Selection of Individual Consultants (IC): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Open Competitive As per requirements of para 7.36 and 7.37 of Selection the Regulations Limited Competitive As per requirements of para 7.38 of the Selection Regulations Direct Must meet the requirements of Para 7.39 of the Regulations, and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Regulations Prior Review Thresholds: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 0.5 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.2 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. PROCUREMENT Kenya : National Agricultural and Rural Inclusive Growth Project PLAN General Information Country: Kenya 2019-12-01 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153349 GPN Date: 2018-02-09 Project Name: National Agricultural and Rural Inclusive Growth Project Loan / Credit No: IDA / 59000 Homabay County Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-HOMABAY COUNTY-1465 Project Coordination and Ma Request for Quota Single Stage - One E 2019-07-0 IDA / 59000 Post Limited 20,000.00 17,252.28 Completed 2018-11-10 2019-05-10 2019-01-05 2019-06-27 07-CW-RFQ / Office Refurbish nagement tions nvelope 4 ment KE-HOMABAY COUNTY-2767 Strengthening Producer Org Request for Quota 93-CW-RFQ / CONSTRUCTION Request for Quota Single Stage - One E 2022-04-0 IDA / 59000 anizations and Value Chain Post Limited tions (Non Bank-S 7,500.00 5,758.48 Completed 2022-02-12 2022-06-30 2022-03-06 2022-07-22 OF TWO IN ONE TRACTOR S tions nvelope 5 Development PD) HED WITH A SMALL STORE. KE-HOMABAY COUNTY-2768 Strengthening Producer Org Request for Quota Request for Quota Single Stage - One E 2022-04-0 58-CW-RFQ / Construction of IDA / 59000 anizations and Value Chain Post Limited tions (Non Bank-S 7,500.00 6,017.21 Completed 2022-02-16 2022-06-06 2022-03-10 2022-07-08 tions nvelope 9 two in one tractor shade with Development PD) a small store Request for Bids - KE-HOMABAY COUNTY-3015 Supporting County Communi Single Stage - One E Small Works SPD Under Imple 2023-04-2 45-CW-RFB / REHABILITATIO IDA / 59000 Post Request for Bids Open - National 207,743.19 0.00 2022-08-08 2022-09-09 2022-08-22 2022-12-13 2022-09-21 2022-09-26 2022-10-05 2022-10-05 2022-10-26 ty-Led Development nvelope (1 envelope proce mentation 4 N OF KOPANA -SOMBRO EAR ss) TH DAM GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-HOMABAY COUNTY-1465 Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 15,000.00 12,968.44 Completed 2019-05-01 2019-05-10 2019-06-26 2019-06-26 2019-12-23 2019-10-01 02-GO-RFQ / Office Furniture nagement tions nvelope KE-HOMABAY COUNTY-1680 Project Coordination and Ma Request for Quota Single Stage - One E 35-GO-RFQ / 20 Number, Mo IDA / 59000 Post Limited 80,000.00 50,437.84 Completed 2020-05-31 2020-07-10 2020-07-05 2020-08-07 2020-10-03 2021-01-20 nagement tions nvelope torcycles 100cc-130cc (Field bikes) KE-HOMABAY COUNTY-1680 44-GO-RFQ / 5 Number, Lapt op computers Processor and Core Logic- Int el® Core i7-8705G with Rad Project Coordination and Ma Request for Quota Single Stage - One E eon RX Vega M GL Graphics IDA / 59000 Post Limited 8,000.00 1,335.56 Completed 2020-05-31 2020-07-10 2020-06-24 2020-11-17 2020-09-22 2021-05-22 nagement tions nvelope System memory- 16GB RAM, upgradeable to 32GB Operating System - Windows 10-64 bit Ultimate/Profession al/IoT Core Edition KE-HOMABAY COUNTY-1828 Project Coordination and Ma Request for Quota Single Stage - One E 06-GO-RFQ / Audio Visual Tel IDA / 59000 Post Limited 73,000.00 62,215.87 Completed 2020-08-14 2020-08-25 2020-09-06 2020-09-29 2020-10-06 2020-10-28 nagement tions nvelope econference facility KE-HOMABAY COUNTY-2179 Supporting County Communi Request for Quota Single Stage - One E 97-GO-RFQ / Purchase of 8 (e IDA / 59000 Post Limited 3,669.60 0.00 Canceled 2021-02-09 2021-02-25 2021-03-25 ty-Led Development tions nvelope ight) number handheld GPS KE-HOMABAY COUNTY-2365 19-GO-RFQ / High value trees Supporting County Communi Request for Quota Single Stage - One E Pending Impl IDA / 59000 Post Limited 16,380.00 0.00 2021-08-06 2021-09-29 2021-10-29 eg. mangoes and pixies for t ty-Led Development tions nvelope ementation he multi community investm ents KE-HOMABAY COUNTY-2365 27-GO-RFQ / HDPE geo mem Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 37,260.00 28,959.74 Completed 2021-08-06 2021-04-23 2021-08-29 2021-10-01 2021-09-30 2021-10-27 brane ( dam liner) thickness ty-Led Development tions nvelope 0.61mm roll size 7m x100m( 700m)2 KE-HOMABAY COUNTY-2387 05-GO-RFQ / supply and deliv Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 41,400.00 36,078.44 Completed 2021-12-15 2022-01-06 2022-01-07 2022-01-22 2022-02-06 2022-03-24 ery of 46 number solar water ty-Led Development tions nvelope pumps sf2 for 46 farm ponds. KE-HOMABAY COUNTY-2685 04-GO-RFQ / Supply and deli Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 15,858.00 13,395.15 Completed 2022-01-18 2022-01-26 2022-02-22 2022-02-15 2022-03-24 2022-03-02 very of fencing materials for ty-Led Development tions nvelope sustainable land manageme nt for 46 Farm ponds KE-HOMABAY COUNTY-2040 Supporting County Communi Request for Quota Single Stage - One E 84-GO-RFQ / TOTAL STATION IDA / 59000 Post Limited 18,348.00 0.00 Canceled 2021-02-09 2021-02-25 2021-03-25 ty-Led Development tions nvelope (GEODETIC RFK) I NUMBER KE-HOMABAY COUNTY-2040 Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 5,505.40 0.00 Canceled 2021-02-09 2021-02-25 2021-03-25 86-GO-RFQ / Soil Testing Sca ty-Led Development tions nvelope nner KE-HOMABAY COUNTY-2040 Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 6,880.50 0.00 Canceled 2021-02-09 2021-02-25 2021-03-25 73-GO-RFQ / Mobile mapper ty-Led Development tions nvelope KE-HOMABAY COUNTY-2763 51-GO-RFQ / One(1) 8-ton tra Strengthening Producer Org Request for Quota Single Stage - One E ctor trailer,Two(2) tractors75 IDA / 59000 anizations and Value Chain Post Limited 92,300.00 0.00 Canceled 2022-03-15 2022-04-07 2022-05-07 tions nvelope HP 4WD each mounted with Development 3- disc plough and 18-disc ha rrow . KE-HOMABAY COUNTY-2040 Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 6,896.55 0.00 Canceled 2022-08-09 2022-08-31 2022-09-30 86-GO-RFQ-2 / SOIL SCANNE ty-Led Development tions nvelope R KE-HOMABAY COUNTY-2040 Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 31,896.55 0.00 Canceled 2022-08-09 2022-08-31 2022-09-30 84-GO-RFQ-2 / TOTAL STATIO ty-Led Development tions nvelope N Page 1 KE-HOMABAY COUNTY-3071 Supporting County Communi Request for Quota Single Stage - One E 15-GO-RFQ / VARIOUS FARM IDA / 59000 Post Limited 12,448.28 0.00 Canceled 2022-08-09 2022-08-31 2022-09-30 ty-Led Development tions nvelope TOOLS EQUIPMENTS KE-HOMABAY COUNTY-3301 Project Coordination and Ma Under Imple 75-GO-DIR / 6 No.Digital soil IDA / 59000 Post Direct Selection Direct - National 17,017.10 0.00 2023-02-01 2023-01-26 2023-02-03 2023-05-22 2023-02-15 2023-03-17 nagement mentation testing kits . KE-HOMABAY COUNTY-3302 70-GO-DIR / Acquisition and I Project Coordination and Ma Under Imple IDA / 59000 Post Direct Selection Direct - National 6,519.97 0.00 2023-02-01 2023-01-26 2023-02-03 2023-05-22 2023-02-15 2023-03-17 nstallation of 20 No.Tracking nagement mentation Devices and 20 No. Licenses. KE-HOMABAY COUNTY-3302 77-GO-DIR / SUPPLY AND DEL IVERY OF; Project Coordination and Ma Under Imple IDA / 59000 Post Direct Selection Direct - National 12,933.00 0.00 2023-02-01 2023-01-26 2023-02-03 2023-05-22 2023-02-15 2023-03-17 1. TABLETS 12 No. nagement mentation 2. SMART PROJECTORS 12 No . 3. SOFTWARE LICENSES 12 N o. .KE-HOMABAY COUNTY-3302 Project Coordination and Ma Under Imple 72-GO-DIR / Acquisition for 1 IDA / 59000 Post Direct Selection Direct - National 22,819.90 0.00 2023-02-01 2023-01-26 2023-02-03 2023-05-22 2023-02-15 2023-03-17 nagement mentation 0 No. software and 10 No. lic enses KE-HOMABAY COUNTY-3632 26-GO-RFQ / SUPPLY AND DE Supporting Community-Driv Request for Quota Single Stage - One E Pending Impl LIVERY OF : - IDA / 59000 Post Limited 23,913.04 0.00 2023-05-29 2023-06-26 2023-07-26 en Development tions nvelope ementation 1. 22 NO. COMPUTERS . 2. 22 NO. PRINTERS . NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-HOMABAY COUNTY-1721 80-CS-CQS / consultancy ser Supporting Community-Driv Consultant Qualifi Under Implement IDA / 59000 Post Open - National 50,000.00 0.00 2020-05-24 2020-08-06 2020-05-31 2022-12-07 2020-06-21 2020-07-13 2020-07-05 2020-12-15 2020-07-26 2021-12-31 vices for chicken value chain en Development cation Selection ation service provider KE-HOMABAY COUNTY-1721 44-CS-CQS / Consultancy ser Supporting Community-Driv Consultant Qualifi Under Implement IDA / 59000 Post Open - National 50,000.00 0.00 2020-05-24 2020-08-06 2020-05-31 2023-05-25 2020-06-21 2020-11-25 2020-07-05 2020-12-15 2020-07-26 2021-12-31 vices for banana value chain en Development cation Selection ation service provider KE-HOMABAY COUNTY-1721 Supporting Community-Driv Consultant Qualifi Under Implement 75-CS-CQS / consultancy ser IDA / 59000 Post Open - National 50,000.00 0.00 2020-05-24 2020-08-06 2020-05-31 2022-12-08 2020-06-21 2020-07-07 2020-07-05 2020-11-25 2020-07-26 2021-12-31 en Development cation Selection ation vices for cotton value chain s ervice provider KE-HOMABAY COUNTY-1722 Supporting Community-Driv Consultant Qualifi Under Implement 19-CS-CQS / Consultancy ser IDA / 59000 Post Open - National 50,000.00 0.00 2020-05-24 2020-08-06 2020-05-31 2023-05-25 2020-06-21 2020-11-25 2020-07-05 2020-11-25 2020-07-26 2021-12-31 en Development cation Selection ation vices for dairy value chain se rvice provider INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 18-MONTH PROCUREMENT PLAN Project information: Phase I of Improved Child Survival Program for Human Capital MPA- P167156-- Immunization Plus and Malaria Progress by Accelerating Coverage and Transforming Services (IMPACT) Project Project Implementation Agencies: Federal Ministry of Health (NMEP and NPHCDA) Date of the Procurement Plan: January 1, 2020 Period covered by this Procurement Plan: January 2020 to June 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016), revised on November 1, 2017 and on August 1, 2018 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Nigeria Public Procurement Act 2007, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [15% is applicable for those contracts identified in the Procurement Plan tables]; Works: [ 7.5% is applicable for those contracts identified in the Procurement Plan tables] I. Threshold for Prior Review – Goods, Works, Non-Consulting Services and Consulting Services Prior-review Thresholds Thresholds for Procurement Methods High Substanti Moderate Low Risk Goods, IT & Non-Consulting Shortlist of National Procurement Type Risk al Risk Risk Works ($'000) ($'000) ($'000) ($'000) Services Consultants Request Request Engineering Open for for Open Open Open Consultin & Quotatio Quotatio 10,0 15,0 20,0 Internatio National internatio National g Constructio Works n or n or 5,000 00 00 00 nal or ICB or NCB National nal or ICB or NCB National Services n ($'000) ($'000) ($'000) ($'000) ($'000) Supervision Shopping Shopping ($'000) ($'000) ($'000) Goods, IT & Non- 2,0 4,0 6,0 Consulting Services 1,500 00 00 00 ≧ < ≦ ≧ < ≦ < ≦ Consultants 1,0 2,0 4,0 20,0 20,0 5,0 5,0 1 3 5 200 (Firms) 500 00 00 00 00 00 00 00 00 00 00 Post Review: All contracts not subject to prior review shall be subject to post review. Summary of the procurement packages for Goods, Works and Non-Consulting Services (Planned for the first 18 months after project effectiveness): Selec Evaluation Market tion Options Approa Review Meth (Most Expected ch Prequal- Domestic Expected by od Advantageo date of Sr. Contract Estimated (Open- ification Preferenc date of Bank (RFP, us Bid, bid/ No Description Cost (US$) Nation (Yes/ e Contract (Prior/ RFB, BAFO, proposal al/ No) (Yes/No) Signature Post) RFQ, Rated opening Limited DS Criteria etc.) etc.) etc.) Nigeria Malaria Elimination Programme (NMEP) GOODS Procurement of Long Lasting Open- Insecticide Internati Most Treated Nets 45,852,523 3rd Feb 13th July 1 Prior onal RFB Advantageou No Yes (Mass .29 2020 2020 s Bid Campaign & Routine Distribution) Procurement of Artemisinin based Open - Most National 3rd Feb 13th July 2 Combination Post 2,381,472 RFB Advantageou No No 2020 2020 Therapy (ACT)- s Bid (Public and Private) Procurement of Open- Most Rapid National 3rd Feb 13th July 3 Post 1,960,202 RFB Advantageou No No Diagnostics 2020 2020 s Bid Tests (RDTs) Most Artesunate Open- 3rd Feb 13th July 4 Post 420,881.89 RFB Advantageou No No Injection National 2020 2020 s Bid Sulphodoxine/P Most Open - 3rd Feb 13th July 5 yrimethamine_I Post 612,322 RFB Advantageou No No National 2020 2020 PTp s Bid Amodiaquine/Su Most lphodoxine/Pyri 2,990,781. Open - 3rd Feb 13th July 6 Post RFB Advantageou No No methamine 47 National 2020 2020 s Bid (SPAQ) Most Open - 3rd Feb 13th July 7 Sharp Boxes Post 152,122,43 RFB Advantageou No No National 2020 2020 s Bid Most Microscope Open - 3rd Feb 13th July 8 Post 491,031 RFB Advantageou No No commodities National 2020 2020 s Bid NON-CONSULTING SERVICES - NMEP State Malaria Elimination MOU/P Programme erform 10th 2,250,000. 9th July 1 (SMEP) Prior Limited ance Rated Criteria No NA February 00 2020 Performance Contra 2020 Contract and ct Operations National Malaria Elimination MOU/P Programme erform 10th 1,500,000. 9th July 2 (NMEP) Prior Limited ance Rated Criteria No NA February 00 2020 Performance Contra 2020 Contract and ct Operations National Primary Health Care Development Agency (NPHCDA) GOODS Procurement of Most vaccines and 61,380,767 5th Feb 13th July 1 Prior UN RFB Advantageou No No devices for .00 2020 2020 s Bid immunization Procurement and maintenance of Most UN 5th Feb 13th July 2 Generators and Post 900,000.00 RFB Advantageou No No System 2020 2020 Cold Chain s Bid Equipment (CCEs) Procurement and installation of Cold Chain Most 4,500,000. 5th Feb 13th July 3 Hubs (3 Prior UN RFB Advantageou No No 00 2020 2020 walking-in cold s Bid rooms) in Lagos Procurement of Emergency Transport 5th Feb 13th July 4 Service (ETS) Post 45,101.72 Limited RFQ Rated Criteria No No 2020 2020 vouchers, handbooks, and logbooks Procurement of Most Open- 5th Feb 13th July 5 equipment for Post 281,969.00 RFB Advantageou No No National 2020 2020 call centre s Bid Most Procurement of Open- 5th Feb 13th July 6 Post 969,529.00 RFB Advantageou No No 14 vehicles National 2020 2020 s Bid Procurement of 5th Feb 13th July 7 14 computer Post 14,000 Limited RFQ Rated Criteria No No 2020 2020 sets II. Summary of the procurement packages for Consulting Services -Planned for the first 18 months after project effectiveness): Selection Market Method Review Approach Expected Expected Estimate (QCBS, Shortlisti Sr. by Bank (Open - date of bid/ date of Contract Description d Cost FBS, ng No (Prior/ International proposal Contract (US$) LCBS, (Yes/ No) Post) / National/ opening Signature QBS, CQS, etc.) DS etc.) Nigeria Malaria Elimination Programme (NMEP) NGOs Service Contract (for 5 11,525,51 Open 10th Feb 31st Aug 1 Prior QCBS Yes states) 1.00 International 2020 2020 Technical Assistance to SMEP in 5 participating states, 630,000.0 10th Feb 31st July 2 Prior Limited INDV No multiple contracts by 0 2020 2020 different consultants Technical Assistance to NMEP (including procurement 150,000.0 10th Feb 31st July 3 Post Limited INDV No consultant), multiple 0 2020 2020 contracts. Independent Verification 300,000.0 Open- 10th Feb 31st July 4 Post CQS No Agents (IVA) for NGOs 0 National 2020 2020 Social and Behavioral Change 3,000,000. Open 10th Feb 31st Aug 5 Prior QCBS Yes Communication (SBCC) 00 International 2020 2020 Operations research on 2,131,148. Open 10th Feb 31st Aug 6 Prior QCBS Yes disease vector mapping 00 International 2020 2020 Operations research on entomological surveillance by 655,738.0 10th Feb 31st July 7 Prior Direct DS No Nigeria Institute of 0 2020 2020 Medical Research (NIMR) Operations research on therapeutic efficacy by 655,738.0 10th Feb 31st July 8 Prior Direct CDS No Nigeria Institute of 0 2020 2020 Medical Research (NIMR) Consultancy on warehouse 10th Feb 31st July 9 Post 32,131.00 Limited INDV No assessment 2020 2020 Programme Management Training (case management, 2,000,000. 10th Feb 31st July 10 Prior Limited INDV No M&E, IVM etc.) Multiple 00 2020 2020 Contracts National Primary Health Care Development Agency (NPHCDA) Technical assistance support 9,869,000. 10th Feb 31st July 1 to government for polio Prior UN CDS No 00 2020 2020 surveillance Technical assistance support to government for polio 15,301,00 10th Feb 31st July 2 Supplemental Immunization Prior UN CDS No 0.00 2020 2020 Activities (SIAs) surveillance through WHO Technical assistance support to government for polio 4,830,000. 10th Feb 31st July 3 logistics and social Prior UN CDS No 00 2020 2020 mobilization for polio through UNICEF Procurement of consultant for 10th Feb 31st July 4 Post 20,000.00 Limited INDV No landscape survey (SQUATS) 2020 2020 Technical assistance support 837,673.1 10th Feb 31st July 5 Prior Open-National INDV No to 12 SPHCDA PIU 3 2020 2020 Technical assistance support 10th Feb 31st July 6 Post 89,750.63 Limited INDV No to NPHCDA PIU 2020 2020 Procurement of Emergency Transport Services (ETS), MOU with National Union of 530,794.3 10th Feb 31st July 7 Prior Direct CDS No Road Transport Workers 9 2020 2020 (NURTW) and NACTOROMAS Training of ETS service providers, MOU with Federal 207,672.0 10th Feb 31st July 8 Post Direct CDS No Road Safety Commission 0 2020 2020 (FRSC) Conduct PAPA – Lot Quality Assurance Sampling, MOU 2,213,850. 10th Feb 31st July 9 Prior Limited CDS No with National Bureau of 00 2020 2020 Statistics (NBS) Consultancy for RCT research 1,902,356. 10th Feb 31st Aug 10 services with Nigerian Prior Open-National QCBS Yes 00 2020 2020 Universities Procurement of operations 1,689,751. Open- 10th Feb 31st Aug 11 Prior QCBS Yes research services 00 International 2020 2020 Support to Cold Chain Equipment (CCE) 23,000,00 10th Feb 31st July 12 Prior UN CDS No optimization platform 0.00 2020 2020 through UNICEF Technical assistance to 1,553,185. 10th Feb 31st July 13 LGHAs (89 total), multiple Post Open-National INDV No 50 2020 2020 contracts Technical assistance 310,076.0 10th Feb 31st July 14 Post Open-National QCBS Yes management firm 0 2020 2020 10th Feb 31st July 15 IVA for performance contract Post 300,000 Open-National CQS No 2020 2020 Procurement of services 3,203,345 Open- 10th Feb 31st Aug 16 for GIS imagery and Prior QCBS Yes .45 International 2020 2020 microplanning Procurement of Social Behaviour Change Open- 10th Feb 31st Aug 17 Prior 5,000,000 QCBS Yes Communication (SBCC) International 2020 2020 services Contracting of direct 2,000,000. Open- 10th Feb 31st Aug 18 Prior QCBS Yes facility financing firms 00 International 2020 2020 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a 1Guidelineson Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Nigeria : Nigeria Improved Child Survival Program for Human Capital MPA PLAN General Information Country: Nigeria 2021-01-08 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167156 GPN Date: Project Name: Nigeria Improved Child Survival Program for Human Capital MPA Loan / Credit No: IDA / 65390 NPHCDA - MPA Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - NG-NPHCDA-MPA-287348-C Component 2: Immunization Single Stage - One E Small Works SPD 6,748,637.0 2024-01-0 W-DIR / Construction of NPHC IDA / 65390 Post Request for Bids Limited 7,700,000.00 Signed 2022-04-07 2022-04-08 2022-04-07 2022-04-07 2022-04-07 2022-04-07 2022-04-07 2022-04-07 2022-04-12 2022-04-06 Plus nvelope (1 envelope proce 5 2 DA Lagos Hub (Cold & Dry St ss) ores) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-NPHCDA-MPA-211614-G O-RFB / Procurement and inst allation of Cold Chain Equipm Component 2: Immunization Single Stage - One E Pending Impl ent (3 units of 500 cubic met IDA / 65390 Post Request for Bids Open - National 4,500,000.00 0.00 2020-09-08 2020-09-13 2020-10-25 2020-11-24 2020-12-29 2021-06-27 Plus nvelope ementation re walking-in cold rooms), ge nerators with UPS, transform ers, solar power system for t he Lagos Hub NPHCDA/IMPACT-MPA/GO/RF Q/04 / Procurement of Emerg Component 2: Immunization Request for Quota Single Stage - One E Pending Impl IDA / 65390 Post Limited 45,102.00 0.00 2020-10-25 2020-12-20 2021-06-18 ency Transport Service (ETS) Plus tions nvelope ementation vouchers, handbooks, and lo gbooks NPHCDA/IMPACT-MPA/GO/RF Component 2: Immunization Single Stage - One E Pending Impl B/05 / Procurement of equip IDA / 65390 Post Request for Bids Open - National 281,969.00 0.00 2021-04-12 2021-04-17 2021-05-29 2021-06-28 2021-08-02 2022-01-29 Plus nvelope ementation ment for call centre NPHCDA/IMPACT-MPA/GO/RF Component 2: Immunization Request for Quota Single Stage - One E Pending Impl IDA / 65390 Post Open - National 969,529.00 0.00 2020-07-14 2020-09-08 2021-03-07 B/06 / Procurement of 14 veh Plus tions nvelope ementation icles NG-NPHCDA-MPA-237396-G Component 2: Immunization Under Imple O-UN / Procurement of Vacci IDA / 65390 Prior Direct Selection Direct 110,669,536.00 0.00 2021-07-21 2021-08-23 2021-07-26 2022-01-19 2021-08-30 2022-02-26 Plus mentation nes and Devices for immuniz ation NG-NPHCDA-MPA-211618-G Component 2: Immunization UN Agencies (Dire O-UN / Procurement of vaccin IDA / 65390 Prior Direct 61,380,767.00 0.00 Canceled 2020-07-21 2021-04-15 2020-07-26 2020-08-30 2021-02-26 Plus ct) es and devices for immunizat ion NG-NPHCDA-MPA-211629-G O-RFQ / Procurement of Flexi Component 2: Immunization Request for Quota Single Stage - One E IDA / 65390 Post Limited 15,584.00 0.00 Canceled 2021-03-06 2021-05-01 2021-10-28 ble Accounting Software for P Plus tions nvelope roject Financial Management NG-NPHCDA-MPA-346707-G Component 2: Immunization Request for Quota Single Stage - One E Under Imple O-RFQ / Printing of PHC Quali IDA / 65390 Post Limited 43,793.70 0.00 2023-03-25 2023-06-19 2023-05-20 2023-11-16 Plus tions nvelope mentation ty of Care Guidelines and Tra ining Manual NPHCDA/IMPACT-MPA/GO/RF Q/07 / Procurement of 14 co Component 2: Immunization Request for Quota Single Stage - One E Under Imple IDA / 65390 Post Limited 150,000.00 0.00 2023-04-26 2023-05-08 2023-05-12 2023-05-19 mputer sets, video teleconfer Plus tions nvelope mentation encing facilities and other off ice equipment NG-NPHCDA-MPA-357814-G Component 2: Immunization Request for Quota Single Stage - One E Pending Impl IDA / 65390 Post Limited 55,000.00 0.00 2023-04-27 2023-05-27 2023-06-26 O-RFQ / Procurement of Offic Plus tions nvelope ementation e Furniture NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-NPHCDA-MPA-211613-N C-RFQ / Procurement of LTA Component 2: Immunization Request for Quota Single Stage - One E Pending Impl based services of maintenan IDA / 65390 Post Limited 900,000.00 0.00 2020-08-08 2020-10-03 2021-04-01 Plus tions nvelope ementation ce firms for Generators and C old Chain Equipment (CCEs) NPHCDA/IMPACT-MPA/NCS/D IR/01 / Procurement of Emer Component 2: Immunization Pending Impl gency Transport Services (ET IDA / 65390 Post Direct Selection Direct 530,794.00 0.00 2021-05-10 2021-05-15 2021-06-19 2021-12-16 Plus ementation S), MOU with National Union of Road Transport Workers ( NURTW) NPHCDA/IMPACT-MPA/NCS/D IR/02 / Re-engagement of Fir Component 2: Immunization IDA / 65390 Post Direct Selection Direct 1,500,000.00 0.00 Canceled 2021-01-18 2021-01-23 2021-02-27 2021-08-26 ms for Haulage of Vaccines a Plus nd Injection Devices NG-NPHCDA-MPA-325263-N Component 2: Immunization Request for Quota Single Stage - One E C-RFQ / Renting of IMPACT Pr IDA / 65390 Prior Limited 113,658.20 0.00 Canceled 2022-11-07 2022-11-07 2022-11-28 2024-11-27 Plus tions nvelope oject Office Accommodation NG-NPHCDA-MPA-325337-N C-RFP / Engagement of firms Component 2: Immunization Request for Propo Single Stage - Two E Under Imple IDA / 65390 Prior Open - National 4,500,000.00 0.00 2022-11-07 2023-03-27 2023-01-07 2023-01-07 2022-11-11 2023-04-05 2023-01-17 2023-02-26 2023-04-02 2024-09-23 for Haulage of Vaccines and I Plus sals nvelope mentation njection Devices NG-NPHCDA-MPA-333321-N Component 2: Immunization Request for Quota Single Stage - One E C-RFQ / Renting of IMPACT Pr IDA / 65390 Prior Limited 150,000.00 0.00 Signed 2022-12-23 2023-01-17 2023-01-14 2025-01-13 Plus tions nvelope oject Office Accommodation Page 1 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NPHCDA/IMPACT-MPA/CS/CD Component 2: Immunization UN Agencies (Dire S/01 / Technical assistance s IDA / 65390 Prior Direct 9,869,000.00 0.00 Canceled 2020-10-25 2021-04-23 Plus ct) upport to government for pol io surveillance NPHCDA/IMPACT-MPA/CS/CD S/02 / Technical assistance s Component 3: Knowledge fo UN Agencies (Dire upport to government for pol IDA / 65390 Prior Direct 15,301,000.00 0.00 Canceled 2020-10-25 2021-04-23 r Change ct) io Supplemental Immunizatio n Activities (SIAs) surveillanc e through WHO NPHCDA/IMPACT-MPA/CS/CD S/03 / Technical assistance s Component 2: Immunization UN Agencies (Dire Under Implement upport to government for pol IDA / 65390 Prior Direct 4,830,000.00 0.00 2020-10-25 2021-04-23 Plus ct) ation io logistics and social mobiliz ation for polio through UNICE F NPHCDA/IMPACT-MPA/CS/QC Component 3: Knowledge fo Quality And Cost- Pending Impleme BS/09 / Consultancy for RCT r IDA / 65390 Post Open - National 1,902,356.00 0.00 2021-04-15 2021-05-06 2021-06-19 2021-07-17 2021-08-16 2021-09-20 2021-10-25 2022-10-25 r Change Based Selection ntation esearch services with Nigeria n Universities NPHCDA/IMPACT-MPA/CS/QC Component 3: Knowledge fo Quality And Cost- Pending Impleme BS/10 / Procurement of opera IDA / 65390 Post Open - National 1,689,751.00 0.00 2021-06-09 2021-06-30 2021-08-13 2021-09-10 2021-10-10 2021-11-14 2021-12-19 2022-12-19 r Change Based Selection ntation tions research services NPHCDA/IMPACT-MPA/CS/CD S/11 / Support to Cold Chain Component 2: Immunization UN Agencies (Dire IDA / 65390 Prior Direct 23,000,000.00 23,000,000.00 Signed 2021-05-25 2021-04-30 2021-11-21 Equipment (CCE) optimizatio Plus ct) n platform through UNICEF NPHCDA/IMPACT-MPA/CS/QC Component 2: Immunization Quality And Cost- Pending Impleme BS/13 / Technical assistance IDA / 65390 Post Open - National 310,076.00 0.00 2021-04-22 2021-05-13 2021-06-26 2021-07-24 2021-08-23 2021-09-27 2021-11-01 2022-11-01 Plus Based Selection ntation management firm NPHCDA/IMPACT-MPA/CS/CQ Component 2: Immunization Consultant Qualifi Pending Impleme IDA / 65390 Post Open - National 300,000.00 0.00 2021-03-29 2021-04-19 2021-06-02 2021-07-02 2021-08-06 2022-02-02 S/14 / IVA for performance co Plus cation Selection ntation ntract NPHCDA/IMPACT-MPA/CS/QC Component 3: Knowledge fo Quality And Cost- Pending Impleme BS/15 / Procurement of servi IDA / 65390 Post Open - National 3,203,345.00 0.00 2021-07-06 2021-07-27 2021-09-09 2021-10-07 2021-11-06 2021-12-11 2022-01-15 2023-01-15 r Change Based Selection ntation ces for GIS imagery and micr oplanning NPHCDA/IMPACT-MPA/CS/QC BS/17 / Contracting of short-t Component 2: Immunization Quality And Cost- IDA / 65390 Prior Open - National 2,000,000.00 0.00 Canceled 2021-10-11 2022-10-26 2021-11-01 2022-11-10 2021-12-15 2022-01-12 2022-02-11 2022-03-18 2022-04-22 2023-04-22 erm individual consultants to Plus Based Selection support DFF training and roll- out. NG-NPHCDA-MPA-211612-CS Component 2: Immunization Quality And Cost- Pending Impleme -QCBS / Engagement of 2 con IDA / 65390 Post Open - National 7,792.00 0.00 2021-03-15 2021-04-05 2021-05-19 2021-06-16 2021-07-16 2021-08-20 2021-09-24 2022-09-24 Plus Based Selection ntation sultants to support targeted t rainings NG-NPHCDA-MPA-287349-CS Component 2: Immunization Consultant Qualifi -CDS / Supervision of Constru IDA / 65390 Post Limited 300,000.00 0.00 Signed 2022-04-07 2022-04-07 2022-04-07 2022-04-07 2022-04-07 2021-02-05 2022-04-12 2024-12-27 Plus cation Selection ction of Lagos Hub (Cold and Dry Stores) NG-NPHCDA-MPA-287346-N C-RFB / Engagement of Firms Component 2: Immunization Quality And Cost- IDA / 65390 Prior Open - National 6,000,000.00 0.00 Canceled 2022-04-21 2022-05-12 2022-06-25 2022-07-23 2022-08-22 2022-09-26 2022-10-31 2023-10-31 for Haulage of Vaccines and I Plus Based Selection njection Devices NG-NPHCDA-MPA-315721-CS Component 2: Immunization Consultant Qualifi Under Implement -CQS / Engagement of Extern IDA / 65390 Post Limited 10,981.50 0.00 2022-09-19 2023-02-08 2022-10-03 2023-05-31 2022-11-02 2023-06-01 2022-12-07 2023-06-05 Plus cation Selection ation al Auditor for IMPACT Project (Component 2) NPHCDA/IMPACT-MPA/CS/QC BS/16 / Procurement of Socia l Behaviour Change Commun Component 3: Knowledge fo Quality And Cost- Under Implement ication (SBCC) services - TA F IDA / 65390 Post Open - National 200,000.00 0.00 2023-03-23 2023-05-19 2023-04-13 2023-05-27 2023-06-24 2023-07-24 2023-08-28 2023-10-02 2024-10-01 r Change Based Selection ation IRM to Conduct Formative Re search on Social Behavioural Change Communication (SBC C) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NPHCDA/IMPACT-MPA/CS/IN Component 3: Knowledge fo Individual Consult Pending Impleme DV/04 / Procurement of cons IDA / 65390 Post Open 20,000.00 0.00 2021-06-14 2021-08-02 2021-08-23 2021-09-27 2022-03-26 r Change ant Selection ntation ultant for landscape survey ( SQUATS) NPHCDA/IMPACT-MPA/CS/IN Component 2: Immunization Individual Consult Under Implement DV/05 / Technical assistance IDA / 65390 Prior Open 837,673.00 0.00 2021-04-26 2022-10-26 2021-06-14 2021-07-05 2021-08-09 2022-02-05 Plus ant Selection ation support to 12 SPHCDA PIU NPHCDA/IMPACT-MPA/CS/IN Component 2: Immunization Individual Consult Under Implement DV/06 / Technical assistance IDA / 65390 Post Open 89,751.00 0.00 2021-05-17 2022-08-11 2021-07-05 2021-07-26 2021-08-30 2022-02-26 Plus ant Selection ation support to NPHCDA PIU NPHCDA/IMPACT-MPA/CS/CD S/07 / Training of ETS service Component 2: Immunization Pending Impleme IDA / 65390 Post Direct Selection Direct 207,672.00 0.00 2021-03-29 2021-04-08 2021-06-12 2021-12-09 providers, MOU with Federal Plus ntation Road Safety Commission (FR SC) NPHCDA/IMPACT-MPA/CS/CD S/08 / Conduct PAPA – Lot Qu Component 3: Knowledge fo Pending Impleme IDA / 65390 Post Direct Selection Direct 2,213,850.00 0.00 2021-04-15 2021-04-25 2021-06-29 2021-12-26 ality Assurance Sampling, M r Change ntation OU with National Bureau of S tatistics (NBS) NPHCDA/IMPACT-MPA/CS/IN Component 2: Immunization Individual Consult Under Implement DV/12 / Technical assistance IDA / 65390 Prior Open 1,553,186.00 0.00 2021-04-22 2022-09-28 2021-06-10 2021-07-01 2021-08-05 2022-02-01 Plus ant Selection ation to LGHAs (89 total), multiple contracts Page 2 NG-NPHCDA-MPA-284949-CS -CDS / Technical Assistance t Component 2: Immunization Under Implement o Government for Polio suppl IDA / 65390 Prior Direct Selection Direct 25,170,000.00 0.00 2022-03-21 2022-04-26 2022-03-31 2022-06-07 2022-06-04 2022-12-01 Plus ation emental immunization activit ies (SIAs) through WHO NG-NPHCDA-MPA-325336-CS -CDS / Procurement of Flexibl Component 2: Immunization Under Implement IDA / 65390 Post Direct Selection Direct - National 15,584.00 0.00 2022-11-08 2022-11-10 2022-11-18 2023-01-09 2023-01-22 2023-07-21 e Accounting Software for Pr Plus ation oject Financial Management NG-NPHCDA-MPA-333319-CS -INDV / Technical Assistance Component 2: Immunization Individual Consult Under Implement IDA / 65390 Prior Open - National 5,000,000.00 0.00 2022-12-23 2023-02-07 2023-02-10 2023-03-03 2023-04-07 2023-10-04 Support to Finance Officers a Plus ant Selection ation nd Officers-In-Charge of PHC facilities in Nigeria NG-NPHCDA-MPA-333496-CS -INDV / Contracting of short-t erm Consultant to support th Component 2: Immunization Individual Consult Under Implement IDA / 65390 Post Direct - National 3,500.00 0.00 2022-12-29 2023-01-06 2023-01-08 2023-01-16 2023-01-30 2023-05-02 e editing, formatting and des Plus ant Selection ation igning of DFF User manual, tr aining manual and training s lides NG-NPHCDA-MPA-344183-CS -INDV / Engagement of Cons ultant for Environmental and Component 2: Immunization Individual Consult Under Implement IDA / 65390 Post Limited 21,737.24 0.00 2023-02-24 2023-03-01 2023-03-01 2023-03-16 2023-04-01 2023-07-01 Social Management Plan (ES Plus ant Selection ation MP) for the Renovation of Pri mary Healthcare facilities acr oss 14 States in Nigeria NG-NPHCDA-MPA-344508-CS Component 2: Immunization Individual Consult Under Implement -INDV / Engagement of a Gen IDA / 65390 Post Limited 26,058.63 0.00 2023-02-24 2023-03-07 2023-03-01 2023-03-16 2023-03-31 2024-03-30 Plus ant Selection ation der Based Violence (GBV) Co nsultant NG-NPHCDA-MPA-350160-CS -INDV / Contracting of Short-t Component 2: Immunization Individual Consult Under Implement erm Individual Consultants to IDA / 65390 Post Limited 18,900.00 0.00 2023-03-16 2023-03-24 2023-03-20 2023-04-05 2023-03-29 2023-05-08 2023-04-17 2023-10-16 Plus ant Selection ation support DFF training and roll- out - DFF Master Trainer for t he IMPACT Project NG-NPHCDA-MPA-350163-CS -INDV / Contracting of Short-t Component 2: Immunization Individual Consult Under Implement erm Individual Consultants to IDA / 65390 Post Limited 47,218.13 0.00 2023-03-16 2023-03-24 2023-03-20 2023-04-05 2023-03-29 2023-04-16 2023-10-16 Plus ant Selection ation support DFF training and roll- out - DFF National Consultant s for the IMPACT Project NG-NPHCDA-MPA-363274-CS -INDV / Contracting of short-t Component 2: Immunization Individual Consult Under Implement erm individual consultants to IDA / 65390 Post Direct - National 47,218.13 0.00 2023-05-24 2023-05-25 2023-05-27 2023-06-03 2023-06-13 2023-12-13 Plus ant Selection ation support DFF training and roll- out - DFF National Consultant s for the IMPACT Project Page 3 PROCUREMENT PLAN Project information: SOLOMON ISLANDS COVID-19 EMERGENCY RESPONSE PROJECT (P173933) Project Implementation agency: Ministry of Health and Medical Services (MHMS) Ministry of Infrastructure and Development (MID) Date of the Procurement Plan: 1815 DecemberOctober 2020 Period covered by this Procurement Plan: 01 November February 202120 to 30 AugustApril 20212 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020July 2016, Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) Only the model bidding documents acceptable to the World Bank shall be used for all national open competitive procurement. 2) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations; 3) The request for bids/request for proposals document shall require that Bidders/ Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the 1 Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 5) There shall be no negotiations of contract price at post contract stage or termination of the contract - on grounds of operation of Price Adjustment stipulated in a signed contract exceeding a specified percentage. 6) No preference of any kind shall be given to national bidders in the bidding process. When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. HEIS is recommended for this project. Other Relevant Procurement Information. Since this is an emergency response project there will be no prior review for all procurement during the relief phase. Procurement of items for emergency requirements will follow methods of Direct Contracting, Procurement from UN Agencies, Limited bidding, etc. This project will also have higher value threshold for shopping and National procurement, as applicable in emergency projects. 2 3 Ministry of Health and Medical Services (MHMS) Project Name: SI COVID-19 Emergency Response Project (P173933) Period Covered: from 01 November 2020 to 30 April 2022 (18 Months) N Description Ref Procurem Procurem Estimated Bank Revie Planned o. . ent ent Amount Financ w Start No. Category Method US$ ed % Type Date (Must be in YYYY/MM / DD format) 1 Personal GO UN or DIR 200,000.00 100 Post 20210/02 Protective 12/151 Equipment, Test Kits, Lab Consumables 2 Renovation of CW DIR 500,000.00 100 Post 20210/02 Quarantine 12/15 Facilities (by MID) 3 Renovation of CW DIR 200,000.00 100 Post 2021/021/ Isolation Units - 1530 Church Health Facilities 4 Waste GO DIR 300,000.00 100 Post 20210/02 Management 11/1530 Trucks (4 units) 5 Renovation CW RFP 1,400,000. 100 Post 2021/02/2 Provincial 00 8 Hospitals 6 Procurement of GO RFP 300,000.00 100 Post 2021/04/3 Incinerators 0 7 Refurbish of CW RFP 400,000.00 100 Post 2021/05/0 Zome into 1 National Hospital Emergency Center (NHEC) 8 Refurbish CW RFP 600,000.00 100 Post 2021/06/0 National Medical 1 Store (NMS) 9 Project CS INDV 45,000.00 100 Post 20210/02 Manager/Coordin 11/15 ator (Level 12) 10 Procurement CS INDV 35,000.00 100 Post 20210/02 Officer (Level 10) 11/15 11 Finance Officer CS INDV 35,000.00 100 Post 20210/02 (Level 10) 11/15 12 Safeguards CS INDV 35,000.00 100 Post 20210/02 Officer (Level 10) 11/15 13 Monitoring and CS INDV 35,000.00 100 Post 20210/02 Evaluation Officer 11/15 (Level 10) 14 Training NCS CDS 150,000.00 100 Post 2021/04/3 warehouse 0 and management) beyond thereafter 15 TA for COVID-19 CS INDV 80,000 100 Post 2021/021/ 1501 4 5 PROCUREMENT Solomon Islands : Solomon Islands COVID-19 Emergency Response Project PLAN General Information Country: Solomon Islands 2021-03-10 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173933 GPN Date: Project Name: Solomon Islands COVID-19 Emergency Response Project Loan / Credit No: IDA / D6280, IDA / 66330, IDA / E0250 Ministry of Health and Medical Services Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Quota SB-MHMS-247403-CW-DIR / Emergency COVID-19 Prepar Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-03-0 Renovation of Helena Goldie IDA / 66330 Post Open - National 725,000.00 0.00 2023-07-14 2023-09-08 edness and Response tions nvelope s (Emergency) SP lementation 6 Hospital Western Province D -Competitive Request for Quota SB-MHMS-247406-CW-DIR / Emergency COVID-19 Prepar Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-06-0 Refurbish National Medical St IDA / 66330 Post Open - National 600,000.00 0.00 2022-10-08 2022-12-03 edness and Response tions nvelope s (Emergency) SP mentation 1 ore (NMS) D -Competitive Request for Quota SB-MHMS-247398-CW-DIR / tions - Small Work Emergency COVID-19 Prepar Pending Imp 2023-10-1 Renovation of Isolation Unit - IDA / 66330 Post Direct Selection Direct - National s (Emergency) SP 100,000.00 0.00 2023-03-13 2023-03-18 2023-04-22 edness and Response lementation 9 Church Health Facility 1. Atoi D -Non Competiti fi Hospital. ve Request for Quota SB-MHMS-306758-CW-DIR / tions - Small Work Renovation of Isolation Unit - Emergency COVID-19 Prepar Pending Imp 2023-10-1 IDA / 66330 Post Direct Selection Direct - National s (Emergency) SP 100,000.00 0.00 2023-03-13 2023-03-18 2023-04-22 Church Health facility 2. Goo edness and Response lementation 9 D -Non Competiti d Samaritan Hospital. ve Request for Quota SB-MHMS-247402-CW-DIR / Emergency COVID-19 Prepar Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-03-0 Renovation Tulagi Provincial IDA / 66330 Post Open - National 725,000.00 0.00 2023-07-14 2023-09-08 edness and Response tions nvelope s (Emergency) SP lementation 6 Hospitals D -Competitive Request for Quota SB-MHMS-247397-CW-DIR / Emergency COVID-19 Prepar Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-11-0 Renovation of Quarantine Fa IDA / 66330 Post Limited 500,000.00 0.00 2023-03-18 2023-05-13 edness and Response tions nvelope s (Emergency) SP lementation 9 cility for Nila, Shortland. D -Competitive Request for Quota SB-MHMS-320706-CW-RFQ / Emergency COVID-19 Prepar Request for Quota Single Stage - One E tions - Small Work 2023-06-2 Survey for Civil work sites an IDA / D6280 Post Open - National 60,000.00 0.00 Signed 2022-11-02 2023-03-05 2022-12-28 edness and Response tions nvelope s (Emergency) SP 6 d incinerator site preparation D -Competitive . Request for Quota SB-MHMS-320707-CW-RFQ / Emergency COVID-19 Prepar Request for Quota Single Stage - One E tions - Small Work 2023-06-2 UXO for Civil work sites and I IDA / D6280 Post Open - National 70,000.00 0.00 Signed 2022-11-02 2023-03-05 2022-12-28 edness and Response tions nvelope s (Emergency) SP 6 ncinerator sites. D -Competitive Request for Quota SB-MHMS-320709-CW-RFQ / Emergency COVID-19 Prepar Request for Quota Single Stage - One E tions - Small Work 2023-06-2 GEOTECH for Civil work sites IDA / D6280 Post Open - National 110,000.00 0.00 Signed 2022-11-02 2023-03-05 2022-12-28 edness and Response tions nvelope s (Emergency) SP 6 and Incinerator sites. D -Competitive Request for Quota SB-MHMS-306760-CW-RFQ / Health Systems Strengtheni Request for Quota Single Stage - One E tions - Small Work 2024-03-0 IDA / E0250 Post Open - National 600,000.00 0.00 Canceled 2023-07-14 2023-09-08 Renovation for Taro Hospital. ng tions nvelope s (Emergency) SP 6 D -Competitive SB-MHMS-247405-CW-DIR / Request for Quota Refurbishment of Zome into Health Systems Strengtheni Request for Quota Single Stage - One E tions - Small Work Pending Imp 2022-04-2 IDA / 66330 Post Open - National 400,000.00 0.00 2021-08-30 2021-10-25 national Hospital Emergency ng tions nvelope s (Emergency) SP lementation 3 Centre (NHEC) (Reallocate to D -Competitive MHMS - NHEOC). Request for Quota SB-MHMS-306761-CW-RFQ / Health Systems Strengtheni Request for Quota Single Stage - One E tions - Small Work 2024-03-0 Renovation of Wagina Hospit IDA / E0250 Post Open - National 400,000.00 0.00 Canceled 2023-07-14 2023-09-08 ng tions nvelope s (Emergency) SP 6 al. D -Competitive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SB-MHMS-247387-GO-DIR / Emergency COVID-19 Prepar Personnel Protective Equipm IDA / 66330 Post Direct Selection Direct 66,000.00 46,869.09 Completed 2021-08-10 2021-11-16 2021-08-15 2021-12-21 2021-09-19 2022-02-11 2022-03-18 2022-03-01 edness and Response ent's for COVID19 activities SB-MHMS-247396-GO-DIR / L Emergency COVID-19 Prepar IDA / 66330 Post Direct Selection Direct 68,000.00 68,472.24 Signed 2021-08-10 2021-11-18 2021-08-15 2021-11-18 2021-09-19 2022-05-26 2022-03-18 ab consumables edness and Response SB-MHMS-247400-GO-DIR / Emergency COVID-19 Prepar IDA / 66330 Prior Direct Selection Direct 300,000.00 0.00 Canceled 2021-08-10 2021-10-27 2021-08-15 2021-09-19 2022-03-18 Four waste Management Tru edness and Response cks SB-MHMS-247394-GO-DIR / Emergency COVID-19 Prepar Test Kits for COVID19 emerg IDA / 66330 Post Direct Selection Direct 66,000.00 66,770.23 Completed 2021-08-10 2021-11-16 2021-08-15 2021-12-21 2021-09-19 2022-05-26 2022-03-18 2022-06-01 edness and Response ency activities SB-MHMS-247404-GO-DIR / Emergency COVID-19 Prepar Request for Quota Open - Internationa Single Stage - One E IDA / 66330 Post 300,000.00 274,095.84 Signed 2021-08-29 2022-05-17 2021-10-24 2022-08-19 2022-04-22 Procurement of incinerators edness and Response tions l nvelope SB-MHMS-247410-GO-DIR / Project Implementation Man Request for Quota Single Stage - One E Procurement of office Equip IDA / 66330 agement, Monitoring and Ev Post Limited 100,000.00 8,901.75 Completed 2021-09-25 2021-08-16 2021-11-20 2021-08-24 2022-05-19 2021-09-03 tions nvelope ment's (Laptops etc.) aluation SB-MHMS-250136-GO-RFQ / Emergency COVID-19 Prepar Request for Quota Single Stage - One E IDA / 66330 Post Limited 200,000.00 35,568.00 Completed 2021-09-27 2021-09-08 2021-11-22 2022-04-18 2022-05-21 2023-04-17 Vehicle for Project Managem edness and Response tions nvelope ent Unit SB-MHMS-260470-GO-DIR / Emergency COVID-19 Prepar Seven Waste Disposal Manag IDA / 66330 Post Direct Selection Direct 300,000.00 297,137.57 Completed 2021-10-29 2021-12-20 2021-11-03 2021-12-19 2021-12-08 2021-11-20 2022-06-06 2022-01-01 edness and Response ement Trucks. SB-MHMS-284386-GO-DIR / Supply and Installation of Eig ht new 70kw ducted Daikin A Health Systems Strengtheni IDA / D6280 Post Direct Selection Direct 250,000.00 216,268.95 Completed 2022-04-06 2022-05-11 2022-04-11 2022-05-20 2022-05-16 2022-04-28 2022-11-12 2022-05-06 ir Condition to National Medic ng al Store, Ranadi - Ministry of Health and Medical Services. Page 1 SB-MHMS-302763-GO-RFQ / Twenty Boats and Outboard Emergency COVID-19 Prepar Request for Quota Single Stage - One E IDA / E0250 Post Limited 200,000.00 0.00 Signed 2022-08-05 2022-10-11 2022-09-30 2023-03-29 motors to support COVID-19 edness and Response tions nvelope Vaccine Deployment. SB-MHMS-301565-GO-DIR / Emergency COVID-19 Prepar National Public Health Lab Re IDA / E0250 Post Direct Selection Direct - National 75,000.00 0.00 Signed 2022-07-15 2022-08-26 2022-07-20 2022-09-13 2022-08-24 2023-02-20 edness and Response agents and Consumables. SB-MHMS-301867-GO-RFQ / Emergency COVID-19 Prepar Request for Quota Single Stage - One E Twenty one Outboard Motors IDA / E0250 Post Limited 200,000.00 0.00 Canceled 2022-08-05 2022-09-30 2023-03-29 edness and Response tions nvelope for COVID-19 Vaccine Deploy ment. SB-MHMS-320491-GO-RFQ / Emergency COVID-19 Prepar Request for Quota Single Stage - One E Vehicles to support vaccine d IDA / E0250 Post Open - National 600,000.00 0.00 Signed 2022-10-22 2023-02-08 2022-12-17 2023-06-15 edness and Response tions nvelope eployment SB-MHMS-300810-GO-DIR / Emergency COVID-19 Prepar Direct - Internation NRH Lab Reagents and Cons IDA / E0250 Post Direct Selection 75,000.00 0.00 Canceled 2022-07-26 2022-08-22 2022-07-31 2022-09-13 2022-09-04 2023-03-03 edness and Response al umables for COVID-19 operat ion. SB-MHMS-362567-GO-RFQ / Emergency COVID-19 Prepar Request for Quota Open - Internationa Single Stage - One E Under Imple NRH Lab Reagents and Cons IDA / E0250 Post 75,000.00 0.00 2023-05-31 2023-07-26 2024-01-22 edness and Response tions l nvelope mentation umables (New) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SB-MHMS-247408-NC-DIR / T Emergency COVID-19 Prepar rainings (Warehouse manage IDA / 66330 Post Direct Selection Direct 150,000.00 0.00 Canceled 2021-08-10 2021-08-15 2021-09-19 2022-03-18 edness and Response ment, IPC, Surveillance and GBV CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SB-MHMS-362569-NC-RFQ / Project Implementation Man Consultant Qualifi IDA / D6280 Post Open - National 45,000.00 0.00 Under Review 2023-05-26 2023-06-26 2023-06-16 2023-07-30 2023-08-29 2023-10-03 2024-03-31 Financial Audit agement, Monitoring and Ev cation Selection aluation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SB-MHMS-223460-CS-INDV / Project Implementation Man Individual Consult IDA / D6280 Post Open 40,000.00 45,000.00 Terminated 2021-04-01 2021-04-12 2021-05-20 2022-03-02 2021-06-10 2022-03-02 2021-07-15 2021-08-20 2022-01-11 Program manager full time agement, Monitoring and Ev ant Selection aluation SB-MHMS-233128-CS-INDV / Emergency COVID-19 Prepar Individual Consult IDA / 66330 Post Open 20,000.00 20,000.00 Signed 2021-06-14 2021-10-29 2021-08-02 2022-05-23 2021-08-23 2022-06-23 2021-09-27 2022-05-30 2022-03-26 International Safeguard Spec edness and Response ant Selection ialist SB-MHMS-228757-CS-INDV / Project Implementation Man Individual Consult IDA / 66330 Post Open 35,000.00 35,000.00 Signed 2021-08-03 2021-04-12 2021-09-21 2022-03-02 2021-10-12 2022-03-09 2021-11-16 2021-08-26 2022-05-15 Financial Management Office agement, Monitoring and Ev ant Selection r aluation SB-MHMS-228758-CS-INDV / Project Implementation Man Individual Consult IDA / 66330 Post Open 35,000.00 35,000.00 Signed 2021-08-03 2021-04-12 2021-09-21 2022-05-23 2021-10-12 2022-05-23 2021-11-16 2021-09-11 2022-05-15 Procurement Officer agement, Monitoring and Ev ant Selection aluation SB-MHMS-228760-CS-INDV / Project Implementation Man Individual Consult IDA / 66330 Post Open 35,000.00 35,000.00 Completed 2021-08-03 2021-04-12 2021-09-21 2022-03-02 2021-10-12 2022-03-03 2021-11-16 2021-08-26 2022-05-15 2023-01-11 Safeguard Officer (Local) agement, Monitoring and Ev ant Selection aluation SB-MHMS-228761-CS-INDV / Project Implementation Man Individual Consult IDA / 66330 Post Open 35,000.00 35,000.00 Completed 2021-08-03 2021-04-12 2021-09-21 2022-03-02 2021-10-12 2022-03-11 2021-11-16 2021-10-22 2022-05-15 2023-01-11 Monitoring & Evaluation Offic agement, Monitoring and Ev ant Selection er aluation SB-MHMS-240686-CS-INDV / Emergency COVID-19 Prepar Individual Consult IDA / D6280 Post Open 35,000.00 81,979.07 Signed 2021-08-03 2021-04-12 2021-09-21 2022-05-23 2021-10-12 2022-05-26 2021-11-16 2022-06-14 2022-05-15 Infrastructure Officer (local) edness and Response ant Selection SB-MHMS-301855-CS-CDS / I Emergency COVID-19 Prepar Individual Consult nternational Technical Assist IDA / E0250 Prior Direct - National 441,850.00 0.00 Completed 2022-08-25 2022-11-10 2022-09-04 2021-10-01 2022-09-25 2023-01-25 2022-10-30 2023-04-28 2023-02-19 edness and Response ant Selection ance for Covid-19 SB-MHMS-320487-CS-INDV / Project Implementation Man Individual Consult IDA / D6280 Post Open - National 40,000.00 0.00 Signed 2022-10-11 2022-10-25 2022-11-29 2022-11-19 2022-12-20 2022-11-22 2023-01-24 2023-07-23 Project Manager - New agement, Monitoring and Ev ant Selection aluation SB-MHMS-339434-CS-INDV / Emergency COVID-19 Prepar Individual Consult Under Implement IDA / 66330 Post Open - National 52,000.00 0.00 2023-02-10 2023-02-13 2023-03-31 2023-06-14 2023-04-21 2023-06-15 2023-05-26 2023-11-22 Safeguard Officer Local (New edness and Response ant Selection ation ) SB-MHMS-339436-CS-INDV / Emergency COVID-19 Prepar Individual Consult IDA / 66330 Post Open - National 52,000.00 0.00 Signed 2023-02-10 2023-02-14 2023-03-31 2023-04-05 2023-04-21 2023-04-06 2023-05-26 2023-11-22 Monitoring & Evaluation Offic edness and Response ant Selection er (New) SB-MHMS-362562-CS-INDV / Project Implementation Man Computer Aided Drafting and Individual Consult Under Implement IDA / D6280 agement, Monitoring and Ev Post Direct - National 13,143.23 0.00 2023-05-24 2023-06-15 2023-06-03 2023-06-26 2023-06-24 2023-07-29 2024-01-25 Design (CADD) Technician - I ant Selection ation aluation nfrastructure Supporting offic er. SB-MHMS-362565-CS-INDV / Project Implementation Man Individual Consult Under Implement Civil/Structural Engineer Con IDA / D6280 agement, Monitoring and Ev Post Direct - National 38,253.51 0.00 2023-05-24 2023-06-15 2023-06-03 2023-06-26 2023-06-24 2023-06-26 2023-07-29 2024-01-25 ant Selection ation sultant - Infrastructure suppo aluation rting officer Page 2 PLAN DE PASSATION DE MARCHES Information sur le Projet : Tchad/Projet : Projet d’Amélioration des Résultats d’Apprentissage de l’Education de Base (PARAEB) – Financement IDA P175803 Agence d’exécution du Projet : Ministère de l'Education Nationale et de la Promotion Civique (MENPC) Date du plan de passation des marchés : février 2022 Période couverte par ce plan de passation des marchés : 18 mois Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016) (“Règlement de Passation des Marchés”) le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marchés se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus de STEP), les procédures nationales de passation des marchés du Tchad pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans les DECRETS : n° 2130/PR/2020 Portant Code des Marchés Publics du Tchad, n°2499/PR/2020 fixant les seuils de passation, de contrôle et d’approbation des marchés publics et n°2500/PR/2020 portant procédure simplifiée de la Commande Publique. Ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : 1 Les dispositions à respecter pour un appel d’offres/à propositions ouvert national sont les suivantes : a. le dossier d’appel d’offres/à propositions oblige le Soumissionnaire/Proposant présentant une Offre/Proposition à déposer un agrément signé, qui sera joint à tout contrat éventuel, pour confirmer qu’il applique et respecte les Directives de la Banque pour la lutte contre la corruption, y compris sans limitation, le droit de la Banque de sanctionner et les droits de la Banque pour l’inspection et l’audit ; b. Les documents de passation des marchés incluent des dispositions, convenues avec la Banque, destinées à atténuer de manière adéquate les risques et impacts environnementaux, sociaux (y compris l'exploitation et les abus sexuels et la violence basée sur le genre), l’hygiène et la sécurité (« ESHS ») ; c. les droits de la Banque d’examiner le dossier et les activités de passation des marchés ; d. l’existence d’un mécanisme efficace d’examen des plaintes ; et e. la gestion et l’archivage des dossiers relatifs au Processus de la Passation des Marchés. Les autres modalités nationales de passation des marchés (autres que sous forme d’appel d’offres/à propositions national ouvert) qui pourraient être appliquées par l’Emprunteur (appel d’offres limité/restreint, demande de prix/consultation de fournisseurs, entente directe) doivent être conformes avec les Principes Fondamentaux de Passation des Marchés de la Banque et garantir que les Directives de la Banque contre la corruption, son Cadre de Sanctions et les recours contractuels visés dans l’Accord Juridique s’appliquent. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). - Fournitures : ne s’applique pas - Travaux : ne s’applique pas 2 L’Assistance directe à la mise en œuvre (sigle HEIS en anglais) tel que précisée aux paragraphes 3.10 et 3.11 du Règlement de Passation des marchés s’applique. « Sans objet » Autres informations pertinentes sur la passation des marchés « Sans objet » 3 % Date de Catégori Montant Numéro financ démarrag e de Approche du Méthode de estimé Type de de é par e prévue Description passatio marché/ passation de (Dollars revue Référen la (jj/mm/aa n de Compétition marché US) ce Banqu aa) marché e Fournitures Fournitures de bureau pour F1 Fournitur Nationale/ Demande de 10 000 100 A Postériori 11/04/2022 l’UGP et l’EPP es ouverte Cotation Acquisition équipements salles F2 Fournitur Nationale/ Appel d’Offres 306 500 100 A Postériori 30/05/2022 multimédias es ouverte National Acquisition tablettes F3 Fournitur Entente Directe UNOPS 13 809 960 100 A Priori 20/06/2022 es Acquisition de moyens roulants F4 Fournitur nationale/ Appel d’Offres 816 667 100 A Postériori 25/05/2022 es ouverte National Acquisition de matériels F5 Fournitur nationale/ Appel d’Offres 45 000 100 A Postériori 25/05/2022 informatiques es ouverte National Acquisition de mobiliers de F6 Fournitur nationale/ Appel d’Offres 40 000 100 A Postériori 25/05/2022 bureau es ouverte National Impression et distribution de S1 Service nationale/ Appel d’Offres 1 100 000 100 A Postériori 25/08/2022 manuels ouverte National Services de consultants Recrutement d’un Consultant C1 nationale/ Consultant 3000 100 A Postériori pour la Traduction de ouverte Individuel 15/04/2022 documents 4 % Date de Catégori Montant Numéro financ démarrag e de Approche du Méthode de estimé Type de de é par e prévue Description passatio marché/ passation de (Dollars revue Référen la (jj/mm/aa n de Compétition marché US) ce Banqu aa) marché e Recrutement d’un Consultant C2 Services nationale Sélection de 33 333 100 A Posteriori pour une évaluation de /ouverte Consultants 29/04/2022 Environnementale du projet consultan Individuels ts Recrutement d’un consultant C3 Services Nationale Sélection de 27 000 100 A Postériori pour une évaluation de la de Ouverte Consultants situation de référence (baseline) consultan Individuels des indicateurs du cadre de ts 25/05/2022 résultats du projet et l’élaboration de la section de suivi évaluation du manuel d’exécution du projet Recrutement d’un consultant C4 Services Nationale Sélection de 18 000 100 A Postériori 15/04/2022 pour l’élaboration du Manuel de de Ouverte Consultants procédures administratives, consultan Individuels Financières et Comptables ts Recrutement d’un consultant C5 Services Nationale Sélection de 27 000 100 A Postériori pour l’élaboration du Manuel de Ouverte Consultants 25/04/2022 d’exécution du projet (Project consultan Individuels implementation Manual) ts Recrutement d’un consultant C6 Services Internationale SFQC 570 000 100 A Posteriori (cabinet) pour un appui au de ouverte recensement général des consultan 20/05/2022 établissements scolaires du ts Tchad (pré-scolaire, primaire et secondaire) Recrutement d’un consultant C7 Services Nationale SQC 15 000 100 A Posteriori pour une assistance en matière de /ouverte 20/04/2022 de communication consultan 5 % Date de Catégori Montant Numéro financ démarrag e de Approche du Méthode de estimé Type de de é par e prévue Description passatio marché/ passation de (Dollars revue Référen la (jj/mm/aa n de Compétition marché US) ce Banqu aa) marché e ts Recrutement d’un cabinet pour C8 Services SQC 12 500 100 A Posteriori 11/04/2022 le recrutement du personnel clé de Nationale du projet (Coordonnateur consultan /ouverte national, RAF, SPM, RSE) ts Recrutement d’un consultant C9 Services ouverte Sélection de 18 000 100 A Posteriori 31/05/2022 pour l’élaboration du plan de Consultants stratégique des ENIB en consultan Individuels mettant en évidence les besoins ts en manuels et matériels de formation et les livres à mettre à disposition des élèves maîtres. Recrutement d’un consultant C10 Services Nationale SFQC 200 000 100 A Posteriori (cabinet) pour une enquête de de ouverte base sur l’observation de consultan classes au niveau du primaire ts en mettant en évidence les modules, les besoins en matière 25/05/2022 didactiques, manuels en cours d’emploi existants et l’identification des sites de construction de salles de classes (utilisant l’outil TEACH) Recrutement d’un consultant C11 Services Nationale SFQC 75 000 100 A Posteriori (cabinet) pour la préparation, de ouverte 20/05/2022 l’élaboration de stratégie, et ou consultan 6 % Date de Catégori Montant Numéro financ démarrag e de Approche du Méthode de estimé Type de de é par e prévue Description passatio marché/ passation de (Dollars revue Référen la (jj/mm/aa n de Compétition marché US) ce Banqu aa) marché e pilotage de programmes ts comme la remédiation, la lecture à la maison, paiement basé sur la performance des écoles communautaires, enseignants communautaires, construction communautaire, etc. Recrutement d’un cabinet pour C12 Services Internationale SFQC 8 744 000 100 A Priori la géolocalisation des écoles de ouverte 29/04/2022 consultan ts TRAVAUX Construction salles de classes et T1 travaux Internationale/ Appel d’Offres 17 124 545 100 A priori blocs de latrine en milieu urbain ouverte 30/06/2022 (Lots à définir) Construction salles de classes et T2 travaux *Approche Appel d’Offres 20 356 364 100 A postériori blocs de latrine en milieu rural communautaire National local (multiples lots suivant la nationale 30/09/2022 définition des zones/écoles d’intervention) Construction des espaces T3 travaux Nationale/ouver Appel d’Offres 4 080 000 100 A postériori 30/06/2022 couverts (lots à déterminer) te National 67 431 869 7 * Approche communautaire pourrait être : ouverte/limitée/directe/ (locale/Régionale /Nationale) suivant les zones d’interventions. 8 PROCUREMENT Chad : CHAD Improving Learning Outcomes Project PLAN General Information Country: Chad 2022-08-05 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175803 GPN Date: Project Name: CHAD Improving Learning Outcomes Project Loan / Credit No: IDA / V4050, IDA / E0180 Ministry of National Education- Chad Improving Learning Outcomes Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - TD-CILOP-338584-CW-RFB / Component 4: Capacity buil Single Stage - One E Works (without pr Pending Imp 2023-09-0 Travaux de réhabilitation et e IDA / E0180 ding, project management, Post Request for Bids Open - National 250,000.00 0.00 2023-01-31 2023-02-05 2023-03-07 2023-03-28 2023-05-11 nvelope equalification) SP lementation 8 xtension des bureaux du Proj monitoring and evaluation D et PARAEB National Procure TD-CILOP-343405-CW-RFB / ment Document - Component 2: Improving acc Single Stage - One E Pending Imp 2024-02-0 Construction de 500 espaces IDA / E0180 Post Request for Bids Open - National 1 Envelope proce 522,184.00 0.00 2023-04-17 2023-04-22 2023-06-03 2023-07-03 2023-08-07 ess to learning nvelope lementation 3 couverts par l'approche com ss (Non Bank-SPD munautaire ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TD-CILOP-342666-GO-RFQ / Fourniture de sucre, café et a Component 4: Capacity buil Request for Quota Single Stage - One E Pending Impl utres produits pour les burea IDA / V4050 ding, project management, Post Limited 8,294.00 0.00 2023-03-08 2023-03-18 2023-03-25 tions nvelope ementation ux du personnel du PARAEB monitoring and evaluation pour une période d'un an. TD-CILOP-342695-GO-RFQ / Component 4: Capacity buil Achat des palettes d'eau et Request for Quota Single Stage - One E Pending Impl IDA / V4050 ding, project management, Post Limited 11,795.00 0.00 2023-03-11 2023-05-06 2023-11-02 autres boissons non alcoolisé tions nvelope ementation monitoring and evaluation es pour les bureaux du PARA EB TD-CILOP-342903-GO-RFQ / Component 4: Capacity buil Request for Quota Single Stage - One E Under Imple Achat des fournitures de bur IDA / E0180 ding, project management, Post Limited 34,130.00 0.00 2023-03-13 2023-05-08 2023-11-04 tions nvelope mentation eau pour le personnel du PAR monitoring and evaluation AEB TD-CILOP-342972-GO-RFQ / Component 4: Capacity buil Request for Quota Single Stage - One E Under Imple Acquisition des Matériels et IDA / E0180 ding, project management, Post Limited 67,154.00 0.00 2023-03-06 2023-02-23 2023-03-31 2023-04-07 tions nvelope mentation Mobiliers de bureau du PARA monitoring and evaluation EB TD-CILOP-343359-GO-RFQ / Component 4: Capacity buil Achat de gasoil pour le group Request for Quota Single Stage - One E Pending Impl IDA / E0180 ding, project management, Post Limited 29,850.00 0.00 2023-03-10 2023-03-20 2024-03-19 e et les dotations en carbura tions nvelope ementation monitoring and evaluation nt des Consultants du PARAE B TD-CILOP-343501-GO-RFQ / Fournitures et installation de Component 4: Capacity buil Request for Quota Single Stage - One E Pending Impl deux téléviseurs de 50"+aba IDA / E0180 ding, project management, Post Limited 3,413.00 0.00 2023-04-10 2023-06-05 2023-12-02 tions nvelope ementation ndonnement tout canal d'un monitoring and evaluation an d'un cout unitaire de 1706 USD. TD-CILOP-343520-GO-RFQ / Component 4: Capacity buil Acquisition , installation et M Request for Quota Single Stage - One E Pending Impl IDA / E0180 ding, project management, Post Limited 33,447.00 0.00 2023-04-02 2023-05-28 2023-11-24 aintenance d'un générateur tions nvelope ementation monitoring and evaluation 100Kwa pour le PARAEB TD-CILOP-343786-GO-DIR / Component 3: Strengthening Acquisition des tablettes, Enr Direct - Internation Pending Impl IDA / E0180 recruitment and financing of Post Direct Selection 421,502.00 0.00 2023-04-15 2023-04-20 2023-05-25 2023-11-21 egistreurs et Accumulateurs al ementation teachers d'énergie pour la géolocalisat ion des MC TD-CILOP-345474-GO-RFB / I Component 3: Strengthening mpression des fiches de lect Single Stage - One E Pending Impl IDA / E0180 recruitment and financing of Post Request for Bids Open - National 307,167.00 0.00 2023-06-22 2023-06-27 2023-08-08 2023-09-07 2023-10-12 2024-04-09 ure pour le préscolaire et la p nvelope ementation teachers remière année du primaire (C P 1) TD-CILOP-342957-GO-RFB / Component 4: Capacity buil Acquisition des moyens roula Single Stage - One E Under Imple IDA / E0180 ding, project management, Post Request for Bids Open - National 688,566.00 0.00 2023-03-28 2023-05-04 2023-04-10 2023-05-04 2023-05-22 2023-05-15 2023-06-21 2023-07-26 2024-01-22 nts pour le Projet PARAEB et l nvelope mentation monitoring and evaluation es Responsables des Sous- C omposantes TD-CILOP-343262-GO-RFQ / Component 4: Capacity buil Acquisition des Equipements Single Stage - One E Under Imple IDA / V4050 ding, project management, Post Request for Bids Open - National 114,483.00 0.00 2023-03-28 2023-02-24 2023-04-02 2023-05-05 2023-05-14 2023-03-09 2023-06-13 2023-07-18 2024-01-14 Informatiques pour le PARAE nvelope mentation monitoring and evaluation B et les Sous Composantes NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TD-CILOP-342641-NC-DIR / L Component 4: Capacity buil oyer bureau PARAEB pour un Request for Quota Single Stage - One E Pending Impl IDA / V4050 ding, project management, Post Limited 71,672.00 0.00 2023-02-17 2023-03-01 2024-02-29 e période d'un an, du 1er Ma tions nvelope ementation monitoring and evaluation rs 2023 au 28 Février 2024 TD-CILOP-342648-NC-RFQ / Component 4: Capacity buil Request for Quota Single Stage - One E Pending Impl Assurance maladie du person IDA / V4050 ding, project management, Post Limited 52,218.00 0.00 2023-03-09 2023-03-19 2024-03-18 tions nvelope ementation nel PARAEB année 2023 monitoring and evaluation TD-CILOP-342662-NC-RFQ / Component 4: Capacity buil Request for Quota Single Stage - One E Pending Impl Assurance tous risques véhic IDA / V4050 ding, project management, Post Limited 25,256.00 0.00 2023-07-08 2023-08-21 2024-08-20 tions nvelope ementation ules PARAEB monitoring and evaluation TD-CILOP-343369-NC-RFQ / Component 4: Capacity buil Request for Quota Single Stage - One E Pending Impl Frais d'entretien du Groupe d IDA / E0180 ding, project management, Post Limited 3,072.00 0.00 2023-04-08 2023-04-29 2024-04-28 tions nvelope ementation e PARAEB pour une période d monitoring and evaluation e 12 mois. Page 1 TD-CILOP-343591-NC-RFQ / Achat des Routeurs, des créd Component 4: Capacity buil Request for Quota Single Stage - One E Pending Impl its d'appel et de connexion in IDA / E0180 ding, project management, Post Limited 64,096.00 0.00 2023-03-11 2023-03-25 2024-03-24 tions nvelope ementation ternet pour le personnel du P monitoring and evaluation ARAEB et les Responsables d es Sous- Composantes TD-CILOP-343644-NC-RFQ / Component 4: Capacity buil Achat de deux logiciels (TOM Request for Quota Single Stage - One E Pending Impl IDA / V4050 ding, project management, Post Limited 33,348.00 0.00 2023-02-25 2023-03-07 2023-03-14 2PRO et TOM2Monitoring; pa tions nvelope ementation monitoring and evaluation ramétrage et formation des u tilisateurs TD-CILOP-345470-NC-DIR / T Component 2: Improving acc Pending Impl est physico-chimique et bact IDA / E0180 Post Direct Selection Direct - National 34,130.00 0.00 2023-04-03 2023-04-08 2023-05-13 2023-11-09 ess to learning ementation ériologique dans un laboratoi re TD-CILOP-346693-NC-RFQ / Component 4: Capacity buil Frais de gardiennage des loc Request for Quota Single Stage - One E Pending Impl IDA / E0180 ding, project management, Post Limited 4,808.00 0.00 2023-03-01 2023-03-01 2023-05-30 aux du PARAEB pour une péri tions nvelope ementation monitoring and evaluation ode de trois (3) mois. TD-CILOP-346760-NC-RFQ / Component 4: Capacity buil Request for Quota Single Stage - One E Pending Impl Nettoyage des bureaux du P IDA / E0180 ding, project management, Post Limited 1,536.00 0.00 2023-03-02 2023-03-02 2023-05-31 tions nvelope ementation ARAEB pour trois mois monitoring and evaluation CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TD-CILOP-337670-CS-CQS / Recrutement d'un consultant Component 4: Capacity buil pour l'élaboration du manuel Consultant Qualifi Pending Impleme IDA / V4050 ding, project management, Post Limited 27,000.00 0.00 2022-08-14 2022-08-28 2022-08-29 2022-09-27 2022-10-27 des procédures administrativ cation Selection ntation monitoring and evaluation es, financières, comptables e t de la passation des marché s TD-CILOP-337667-CS-CQS / Component 4: Capacity buil Consultant Qualifi Pending Impleme Recrutement d'un consultant IDA / V4050 ding, project management, Post Limited 34,130.00 0.00 2022-08-14 2022-08-28 2022-09-27 2022-11-01 2023-04-30 cation Selection ntation pour l'élaboration du manuel monitoring and evaluation d'exécution TD-CILOP-342917-CS-QCBS / Recrutement d'un cabinet po Component 3: Strengthening Quality And Cost- Pending Impleme ur l'élaboration de la politiqu IDA / E0180 recruitment and financing of Post Open - National 136,519.00 0.00 2023-03-20 2023-04-10 2023-05-24 2023-06-21 2023-07-21 2023-08-25 2023-09-29 2024-09-28 Based Selection ntation e/plan budgétisé pour l'intégr teachers ations des MC à la paie (CCB P1 TD-CILOP-338586-CS-CQS / Component 4: Capacity buil Recrutement d'un Consultant Consultant Qualifi Pending Impleme IDA / V4050 ding, project management, Post Limited 30,000.00 0.00 2022-08-14 2022-08-28 2022-09-11 2022-10-10 2022-11-09 pour l'élaboration du Plan de cation Selection ntation monitoring and evaluation Gestion de Sécurité (PGS) TD-CILOP-342901-CS-QCBS / Recrutement d'un Consultant Component 2: Improving acc Consultant Qualifi Pending Impleme IDA / E0180 Post Open - National 18,430.00 0.00 2023-04-10 2023-04-15 2023-04-18 2023-05-11 2023-06-04 2023-12-01 pour la conception d'un mod ess to learning cation Selection ntation èle d'enseignement au nivea u TD-CILOP-342684-CS-QCBS / Component 1: Strengthening Consultant Qualifi Pending Impleme Recrutement d'un Cabinet po IDA / E0180 Post Open - National 18,430.00 0.00 2023-04-10 2023-05-01 2023-06-14 2023-07-14 2023-08-18 2024-02-14 the quality of teaching cation Selection ntation ur la révision du curricula TD-CILOP-342694-CS-QCBS / Recrutement d'un cabinet afi Component 1: Strengthening Consultant Qualifi Pending Impleme IDA / E0180 Post Limited 18,430.00 0.00 2023-04-17 2023-05-01 2023-05-31 2023-07-05 2024-01-01 n de renforcer les politiques the quality of teaching cation Selection ntation , le contenu et les procédure s existantes TD-CILOP-342899-CS-QCBS / Component 1: Strengthening Consultant Qualifi Pending Impleme Recrutement d'un bureau de IDA / E0180 Post Limited 37,543.00 0.00 2023-07-03 2023-07-17 2023-08-16 2023-09-20 2024-03-18 the quality of teaching cation Selection ntation contrôle de la qualité des tra vaux TD-CILOP-342985-CS-CDS / Component 4: Capacity buil Consultant Qualifi Pending Impleme Audit des comptes du fonds IDA / E0180 ding, project management, Post Limited 10,239.00 0.00 2023-04-03 2023-04-10 2023-04-17 2023-04-25 2023-05-25 cation Selection ntation de préparation monitoring and evaluation TD-CILOP-342725-CS-QCBS / Recrutement d'un OSC pour l Component 1: Strengthening Quality And Cost- Pending Impleme IDA / E0180 Post Open - National 153,584.00 0.00 2023-04-21 2023-05-12 2023-06-25 2023-07-23 2023-08-22 2023-09-26 2023-10-31 2024-10-30 'organisation une campagne the quality of teaching Based Selection ntation de mobilisation sociale en fa veur de la lecture TD-CILOP-363298-CS-CQS / Recrutement d’un (e) Consult ant(e) international(e) en cha Component 1: Strengthening Consultant Qualifi Open - Internationa Pending Impleme rge d’appuyer le Comité Nati IDA / E0180 Post 18,430.00 0.00 2023-05-24 2023-06-14 2023-07-28 2023-08-27 2023-10-01 2024-03-29 the quality of teaching cation Selection l ntation onal Technique de Littératie pour l’élaboration et l’expéri mentation d’un paquet curric ulaire TD-CILOP-367212-CS-CQS / Recrutement d'un Consultant Component 4: Capacity buil Consultant Qualifi Pending Impleme en appui au Ministère de la P IDA / E0180 ding, project management, Post Limited 30,716.00 0.00 2023-06-14 2023-06-28 2023-07-28 2023-09-01 2024-02-28 cation Selection ntation rospective Economique et de monitoring and evaluation s Partenariats Internationaux INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TD-CILOP-292270-CS-CDS / Component 4: Capacity buil Recrutement d'un cabinet po Under Implement IDA / V4050 ding, project management, Post Direct Selection Direct 25,000.00 0.00 2022-04-25 2022-08-12 2022-05-05 2022-06-09 2022-07-09 ur le recrutement du personn ation monitoring and evaluation el de l’Unité de Gestion du P AREAB TD-CILOP-342991-CS-CDS / Component 4: Capacity buil Recrutement d'un Cabinet po Pending Impleme IDA / E0180 ding, project management, Post Direct Selection Direct - National 11,945.00 0.00 2023-03-10 2023-03-20 2023-05-24 2023-11-20 ur le recrutement du personn ntation monitoring and evaluation el additionnel du PARAEB Page 2 TD-CILOP-343021-CS-CDS / Component 4: Capacity buil Assistance technique nationa Pending Impleme IDA / E0180 ding, project management, Post Direct Selection Direct - National 13,652.00 0.00 2023-05-02 2023-05-12 2023-07-16 2024-01-12 le pour le renforcement de c ntation monitoring and evaluation apacité des partenaires TD-CILOP-343025-CS-CDS / Recrutement d'un consultant pour l'évaluation de la situati Component 4: Capacity buil on de référence (Baseline) de Pending Impleme IDA / E0180 ding, project management, Post Direct Selection Direct - National 23,038.00 0.00 2023-06-01 2023-06-11 2023-08-15 2024-02-11 s indicateurs du Cadre de Ré ntation monitoring and evaluation sultats du Projet et élaboratio n de la section de suivi-évalu ation du manuel d'exécution du projet. TD-CILOP-343138-CS-CDS / Recrutement d'un Consultant Component 4: Capacity buil pour l'évaluation des équipe IDA / E0180 ding, project management, Post Direct Selection Direct - National 14,932.00 0.00 Under Review 2023-06-01 2023-06-13 2023-06-11 2023-08-15 2024-02-11 ments pour l'installation intr monitoring and evaluation anet au sein MENPC pour con necter tous les services au ni veau central TD-CILOP-360244-CS-CDS / Recensement de tous les éta blissements scolaires publics, Component 3: Strengthening communautaires et privés du Pending Impleme IDA / E0180 recruitment and financing of Prior Direct Selection Direct - National 2,901,024.00 0.00 2023-05-15 2023-05-25 2023-07-29 2024-01-25 Préscolaire, du Primaire, du S ntation teachers econdaire et de l’Enseignem ent Technique et Professionn elle y compris les entités liée s aux établissements Page 3 Projet SUD PLAN DE PASSATIO N DE MARCHES SIMPLIFIE PROJET SUD : PID : PPA SUD N# : DA PRO TE RAPP OUV JET DAT ME Coût TER DEMA OU ORT ERT DAT DE E TH estim MES NDE JUSTIF VE D'EV URE Caté LISTE E CON SIG Ré Descripti Rev OD Appr atif DE DE ICATI RT ALUA DES comp gori AMI REST INVI TRA NAT f on ue E oche (en REF PROP ON UR TION PLIS e REINT TATI T URE P. miller ERE OSITI SED E TECH FINA E ON NEG CON M. s US$) NCE ON DE NIQU NCIE OCI TRA S E RS E T PLI S Appui techniq ue à la cellule 141. de 00 prépara tion Recrutem SU ent 30 D- Cons 11 15 03 02 31 29 28 27 31 Economis Ouver 1 01 Jan. - De - PP post ultan CI Dec. 4 Dec. Jan. # Jan. # # Dec. Dec. # Dec. # Dec. 4 Dec. A- te en t te 15.000 19 19 9 20 20 20 19 1 c. 1 19 19 19 19 développ 19 C-1 ement local et inclusif Recrutem SU ent D- Spécialist Cons 11 16 05 05 05 05 05 05 05 10 2 05 Jan. PP e en post ultan CI Ouver 15.000 Dec. 5 Dec. 0 Jan. 0 Jan. 0 20 0 Jan. 0 Jan. 0 Jan. 0 Jan. 0 Jan. 5 Jan. A- Passation t te 19 19 20 20 20 20 20 20 20 20 C-2 de Marché Recrutem SU ent D- Cons 11 16 05 05 06 07 08 09 09 14 Spécialist Ouver 2 06 Jan. PP post ultan CI Dec. 5 Dec. Jan. 0 Jan. 1 0 Jan. 1 Jan. 1 Jan. 1 Jan. 0 Jan. 5 Jan. A- e en t te 15.000 19 19 0 20 20 20 20 20 20 20 20 20 C-3 Gestion financière Recrutem SU ent D- Spécialist Cons 11 16 05 05 07 09 11 13 13 18 2 07 Jan. PP e en post ultan CI Ouver 15.000 Dec. 5 Dec. 0 Jan. 0 Jan. 2 20 0 Jan. 2 Jan. 2 Jan. 2 Jan. 0 Jan. 5 Jan. A- gestion t te 19 19 20 20 20 20 20 20 20 20 C-4 environne mentale Recrutem SU ent D- Spécialist Cons 20 26 16 17 21 24 27 30 31 06 2 20 Jan. PP e en suivi post ultan CI Ouver 15.000 Dec. 6 Dec. 1 Jan. 1 Jan. 3 20 1 Jan. 3 Jan. 3 Jan. 3 Jan. 1 Jan. 6 Feb. A- et t te 19 19 20 20 20 20 20 20 20 20 C-5 évaluatio n Recrutem SU ent D- Cons 20 27 18 20 26 30 03 07 09 16 Spécialist 2 24 Jan. PP post ultan CI Ouver Dec. 7 Dec. Jan. 2 Jan. 4 2 Jan. 4 Jan. 4 Feb. 4 Feb. 2 Feb. 7 Feb. A- e en t te 15.000 19 19 2 20 20 20 20 20 20 20 20 20 C-6 communi cation SU Recrutem D- Cons 20 28 20 23 31 05 10 15 18 26 ent 2 28 Jan. PP post ultan CI Ouver Dec. 8 Dec. Jan. 3 Jan. 5 3 Jan. 5 Feb 5 Feb. 5 Feb. 3 Feb. 8 Feb. A- Spécialist t te 15.000 19 19 3 20 20 20 20 . 20 20 20 20 20 C-7 e en SIG Recrutem SU ent Appui D- Cons 05 14 07 11 17 21 27 04 10 14 23 technique 2 PP post ultan CI Ouver Jan. 9 Jan. Feb. 4 Feb. 6 Feb. 4 Feb. 6 Feb 6 Mar. 6 Mar. 4 Mar. 9 Mar. A- auprès t te 36.000 20 20 4 20 20 20 20 . 20 20 20 20 20 C-8 des trois régions Recrutem SU ent D- Cons 11 20 13 17 27 02 08 14 18 27 Spécialist Ouver 2 23 Jan. PP post ultan CI Dec. 9 Dec. Jan. 4 Jan. 6 4 Jan. 6 Feb 6 Feb. 6 Feb. 4 Feb. 9 Feb. A- e en t te 15.000 19 19 4 20 20 20 20 . 20 20 20 20 20 C-9 gestion Sociale Etude prépara 190. toire 00 SU Etudes D- Cons 15 20 09 12 12 19 05 13 20 01 environne SQ Ouver 2 12 Jan. 3 1 1 PP post ultan 100.00 Dec. 5 Dec. Jan. 3 Jan. 0 0 Jan. Feb Mar. 8 Mar. 7 Mar. Apr. mentales C te 0 20 8 5 2 A- t 0 19 19 20 20 20 . 20 20 20 20 20 et sociales C-9 Développe ment et SU mise en D- œuvre de Cons 15 20 09 12 12 12 21 05 13 20 02 PP SQ Ouver 2 3 1 1 la stratégie post ultan Jan. 5 Jan. Feb. 3 Feb. 0 Feb. 0 Feb. Mar Apr. 8 Apr. 7 Apr. May. A- C te 50.000 0 8 5 2 de t 20 20 20 20 20 20 . 20 20 20 20 20 C- communic 10 ation du Projet SU Etude sur D- la Cons 31 05 25 28 28 28 06 21 29 06 18 PP mobilisatio SQ Ouver 2 3 1 1 post ultan Jan. 5 Feb. Feb. 3 Feb. 0 Feb. 0 Feb. Apr Apr. 8 Apr. 7 May. May. A- n C te 10.000 0 8 5 2 t 20 20 20 20 20 20 . 20 20 20 20 20 C- communau 11 taire et l’engagem ent citoyen Elaboration de Manuels SU d’exécutio D- n du Projet Cons 15 20 09 12 12 19 05 13 20 01 PP (opération SQ Ouver 2 12 Jan. 3 1 1 post ultan Dec. 5 Dec. Jan. 3 Jan. 0 0 Jan. Feb Mar. 8 Mar. 7 Mar. Apr. A- nel, C te 30.000 0 20 8 5 2 t 19 19 20 20 20 . 20 20 20 20 20 C- gestion 12 financière, passation de marché) Renforc ement de 110. capacit 00 é du MID Formation SU de D- montage Cons 20 25 14 17 17 17 26 10 18 25 07 PP Ouver 2 3 1 1 et gestion post ultan CI Jan. 5 Jan. Feb. 3 Feb. 0 Feb. 0 Feb. Mar Apr. 8 Apr. 7 Apr. May. A- te 30.000 0 8 5 2 de Projet t 20 20 20 20 20 20 . 20 20 20 20 20 C- dans 3 13 Regions Equipe ment et 30.0 logistiq 0 ues Acquisition SU de D- matériels Four 15 20 09 12 12 27 30 02 07 09 Ouver 2 12 Jan. 1 PP informatiq post nitur DC Dec. 5 Dec. Jan. 3 Jan. 0 0 Jan. Jan. 3 Jan. 3 Feb. 5 Feb. 2 Feb. te 15.000 0 20 5 A- ues en e 19 19 20 20 20 20 20 20 20 20 F-1 plusieurs lots SU Acquisition D- de Four 15 20 09 09 11 11 11 11 16 21 2 09 Jan. PP matériel et post nitur DC Ouver Dec. 5 Dec. Jan. 0 Jan. 0 2 Jan. 0 Jan. 0 Jan. 0 Jan. 5 Jan. 5 Jan. 10.000 0 20 A- mobilier de e te 19 19 20 20 20 20 20 20 20 20 F-2 bureau SU Acquisition D- Four 15 20 09 09 11 11 11 11 16 21 de Ouver 2 09 Jan. PP post nitur DC Dec. 5 Dec. Jan. 0 Jan. 0 2 Jan. 0 Jan. 0 Jan. 0 Jan. 5 Jan. 5 Jan. fourniture te 5.000 0 20 A- e 19 19 20 20 20 20 20 20 20 20 de bureau F-3 Servi SU ce D- Location autre 20 25 25 25 28 28 28 28 02 02 Ouver 27 Jan. PP de post que DC Jan. 5 Jan. 0 Jan. 0 Jan. 2 1 Jan. 0 Jan. 0 Jan. 0 Jan. 5 Feb. 0 Feb. te 20.000 20 A- véhicules Cons 20 20 20 20 20 20 20 20 20 20 F-4 ultan t Activité s Pilotes 600. du 00 Projet Assistance Technique pour la mobilisatio n, SU formations, D- planificatio Cons 31 05 25 25 25 27 27 27 27 03 08 PP SF Ouver 2 n et post ultan 600.00 Jan. 5 Feb. Feb. 0 Feb. 0 Feb. 2 Feb. 0 Feb 0 Feb. 0 Feb. 5 Mar. 5 Mar. A- QC te 0 priorisation t 0 20 20 20 20 20 20 . 20 20 20 20 20 C- des 14 demandes (après le ciblage des communes ) Atelier 75.0 0 Servi ce autre 05 10 30 02 02 02 22 22 22 29 12 restre 2 2 1 Atelier post que DC Jan. 5 Jan. Jan. 3 Feb. 0 Feb. 0 Feb. Feb 0 Feb. 0 Feb. 7 Feb. Mar. inte 75.000 0 0 2 Cons 20 20 20 20 20 20 . 20 20 20 20 20 ultan t TOTAL GENERAL (en Tota 1,11 millions l 6.00 US$) PROCUREMENT Madagascar : Support for resilient livelihoods in the South of Madagascar PLAN General Information Country: Madagascar 2020-02-04 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171056 GPN Date: 2021-10-08 Project Name: Support for resilient livelihoods in the South of Madagascar Loan / Credit No: IDA / D7510, / , IDA / V3060, IDA / D9320 MID- SOUTH PROJECT Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MG-MID-SOUTH PROJECT-4.A Request for Quota Implementation Support and Request for Quota Single Stage - One E 2022-06-0 .09.011-CW-RFQ / Travaux d IDA / D7510 Post Open - National tions (Non Bank-S 7,500.00 18,790.74 Signed 2022-03-07 2022-06-04 2022-05-02 2022-09-10 knowledge learning tions nvelope 1 e cloisonnement bureau UNG PD) P MG-MID-SOUTH PROJECT-2.B Request for Bids - .01.008-CW-RFB / Travaux de Open - Internationa Single Stage - One E Works French Civi Pending Imp 2024-11-2 IDA / D9320 Resiliency infrastructure Post Request for Bids 8,605,883.00 0.00 2023-09-01 2023-09-06 2023-10-21 2023-11-11 2023-12-02 renforcement et d'extension l nvelope l Law (French) SP lementation 6 des deux pipelines D MG-MID-SOUTH PROJECT-2.B Request for Bids - .01.007-CW-RFB / Travaux de Open - Internationa Single Stage - One E Works French Civi Under Imple 2024-06-2 IDA / D9320 Resiliency infrastructure Post Request for Bids 3,097,000.00 0.00 2023-06-01 2023-03-08 2023-06-06 2023-06-06 2023-07-21 2023-08-11 2023-09-01 réhabilitation du pipeline Ma l nvelope l Law (French) SP mentation 7 ndrare-Sampona D Request for Bids - MG-MID-SOUTH PROJECT-3.C Strengthening decentralized Single Stage - One E Works French Civi Pending Imp 2024-10-1 .4C.1.B.2-CW-RFB / Réhabilit IDA / D7510 local governments, participa Post Request for Bids Open - National 639,231.00 0.00 2024-04-01 2024-04-06 2024-05-06 2024-05-27 2024-06-17 nvelope l Law (French) SP lementation 5 ation de bâtiments répartis e tory planning and social resil D n plusieurs lots. ience MG-MID-SOUTH PROJECT-3.C Request for Bids - .1.2.1-CW-RFB / Construction Supporting Resilient liveliho Single Stage - One E Works French Civi Pending Imp 2024-08-1 IDA / D9320 Post Request for Bids Open - National 1,500,000.00 0.00 2024-02-01 2024-02-06 2024-03-07 2024-03-28 2024-04-18 d'un Centre Régional de Rec ods nvelope l Law (French) SP lementation 6 herche du FOFIFA avec Banq D ue de semence MG-MID-SOUTH PROJECT-3.C Request for Quota Supporting Resilient liveliho Request for Quota Single Stage - One E Pending Imp 2024-09-2 .02.002-CW-RFQ / Constructi IDA / D9320 Post Open - National tions (Non Bank-S 150,000.00 0.00 2024-02-06 2024-04-02 ods tions nvelope lementation 9 on d’un Centre Multiplicateur PD) des Géniteurs MG-MID-SOUTH PROJECT-3.C Request for Bids - .02.005-CW-RFB / Constructi Supporting Resilient liveliho Single Stage - One E Works French Civi Pending Imp 2024-08-1 IDA / D9320 Post Request for Bids Open - National 362,400.00 0.00 2024-02-01 2024-02-06 2024-03-07 2024-03-28 2024-04-18 on et mise à disposition de fe ods nvelope l Law (French) SP lementation 6 rme pilote d'embouche, pour D les petits ruminants. MG-MID-SOUTH PROJECT-2C 02009-CS-CDS / Recrutement d'un entreprise pour la réalis Request for Quota Supporting Resilient liveliho Request for Quota Single Stage - One E 2024-09-2 ation de 10 échelles de crues IDA / D9320 Post Open - National tions (Non Bank-S 10,000.00 0.00 Canceled 2024-02-06 2024-04-02 ods tions nvelope 9 sur le fleuve de Mandrare à A PD) ndabolava dans la commune Mahaly, District Amboasary, Région Anosy MG-MID-SOUTH PROJECT-3.B .01.002.5-CW-RFB / Travaux Request for Bids - de réhabilitation du périmètr Single Stage - One E Works French Civi Pending Imp 2024-05-2 IDA / D7510 Resiliency infrastructure Post Request for Bids Open - National 1,530,000.00 0.00 2023-11-01 2023-11-06 2023-12-18 2024-01-17 2024-02-21 e irrigué d'Amboboky, Comm nvelope l Law (French) SP lementation 1 une Rurale de Beapombo II, D District Betroka, Région Anos y MG-MID-SOUTH PROJECT-3.B .01.002.8-CW-RFB / Travaux de réhabilitation des périmèt Request for Bids - res irrigués de : Betsintsy, Co Single Stage - One E Works French Civi Pending Imp 2024-05-2 IDA / D7510 Resiliency infrastructure Post Request for Bids Open - National 280,800.00 0.00 2023-11-01 2023-11-06 2023-12-18 2024-01-17 2024-02-21 mmune Rurale d'Andoharano nvelope l Law (French) SP lementation 1 , Kitara, Ampilofilo, D - Androka, Commune Rurale I manombo, District Ambovom be, Région Androy MG-MID-SOUTH PROJECT-3.B .01.002.9-CW-RFB / Travaux d'aménagement des périmèt re irrigué de : Request for Bids - - Andrampa, Single Stage - One E Works French Civi Pending Imp 2024-05-2 IDA / D7510 Resiliency infrastructure Post Request for Bids Open - National 250,200.00 0.00 2023-11-01 2023-11-06 2023-12-18 2024-01-17 2024-02-21 - Antehita, nvelope l Law (French) SP lementation 1 - Berombindiho, D - Tanimainty, - Berenty, Commune Rurale Andalatanosy, District Ambov ombe, Région Androy MG-MID-SOUTH PROJECT-3.B .01.002.3-CW-RFB / Travaux de réhabilitation des périmè Request for Bids - tre irrigué : Single Stage - One E Works French Civi Pending Imp 2024-05-2 IDA / D7510 Resiliency infrastructure Post Request for Bids Open - National 1,143,000.00 0.00 2023-11-01 2023-11-06 2023-12-18 2024-01-17 2024-02-21 - Ianabinda Aval, Commune nvelope l Law (French) SP lementation 1 Rurale Ianabinda, D - Bekorobo, Commune Rurale de Bekorobo, District Betroka , Région Anosy MG-MID-SOUTH PROJECT-3.B Request for Bids - .01.002.0-CW-RFB / Travaux Single Stage - One E Works French Civi Pending Imp 2024-05-2 de réhabilitation du périmètr IDA / D7510 Resiliency infrastructure Post Request for Bids Open - National 1,260,000.00 0.00 2023-11-01 2023-11-06 2023-12-18 2024-01-17 2024-02-21 nvelope l Law (French) SP lementation 1 e irrigué d'Isoanala, Commun D e Rurale Isoanala, District Be troka, Région Anosy MG-MID-SOUTH PROJECT-33. B.01.2.6.-CW-RFB / Travaux d e réhabilitation des périmètr National Procure e irrigués de : ment Document - - Antanimarina, Commune Ru Single Stage - One E Pending Imp 2024-05-2 IDA / D7510 Resiliency infrastructure Post Request for Bids Open - National 1 Envelope proce 1,080,000.00 0.00 2023-11-01 2023-11-06 2023-12-18 2024-01-17 2024-02-21 rale de Benato Toby, nvelope lementation 1 ss (Non Bank-SPD - Ambondrokidy, Commune R ) urale d'Andriandampy, - Riandampy, Commune Rura le Mahabo, District Betroka, Région Anosy MG-MID-SOUTH PROJECT-3D. Request for Quota 4.1.8-CW-RFQ / Travaux de c Supporting Resilient liveliho Request for Quota Single Stage - One E Pending Imp 2024-05-3 IDA / D9320 Post Open - National tions (Non Bank-S 77,090.00 0.00 2023-10-07 2023-12-02 onstruction de bureau pour l ods tions nvelope lementation 0 PD) es Cantonnements Page 1 MG-MID-SOUTH PROJECT- 4C .1.2.1. -CW-RFQ / Constructio Request for Quota Implementation Support and Request for Quota Single Stage - One E Pending Imp 2024-10-1 n de 03 centres opérationnel IDA / D9320 Post Open - National tions (Non Bank-S 200,000.00 0.00 2024-02-20 2024-04-16 knowledge learning tions nvelope lementation 3 s moderne réparti en trois lot PD) s: Anosy, Androy, Atsimo And refana National Procure MG-MID-SOUTH PROJECT-36 ment Document - 3096-CW-RFQ / Travaux pour Implementation Support and Request for Quota Single Stage - One E Pending Imp 2023-08-3 IDA / D7510 Post Open - National 1 Envelope proce 10,000.00 0.00 2023-05-29 2023-07-31 le renforcement de la sécurit knowledge learning tions nvelope lementation 0 ss (Non Bank-SPD é du bureau de l'UNGP ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-MID-SOUTH PROJECT-01- Strengthening decentralized RFQ / Acquisition de matériel local governments, participa Request for Quota Single Stage - One E IDA / V3060 Post Limited 20,000.00 8,312.23 Signed 2020-09-26 2020-09-25 2020-11-21 2020-11-05 2021-05-20 s, consommables informatiqu tory planning and social resil tions nvelope es et matériels techniques ience MG-MID-SOUTH PROJECT-02- Strengthening decentralized Request for Quota Single Stage - One E RFQ / Acquisition de smartph IDA / V3060 local governments, participa Post Limited 4,500.00 2,581.94 Signed 2020-09-26 2020-11-10 2020-11-21 2020-11-20 2021-05-20 tions nvelope one pour l'équipe du projet tory planning and social resil ience MG-MID-SOUTH PROJECT-03- Strengthening decentralized Request for Quota Single Stage - One E RFQ / Acquisition de mobilier IDA / V3060 local governments, participa Post Limited 37,000.00 14,184.18 Signed 2020-09-26 2020-10-30 2020-11-21 2020-12-22 2021-05-20 tions nvelope de bureau pour l'équipe du p tory planning and social resil rojet ience MG-MID-SOUTH PROJECT-04- Strengthening decentralized Request for Quota Single Stage - One E RFQ / Acquisition de fournitur IDA / V3060 local governments, participa Post Limited 12,200.00 4,059.51 Signed 2020-09-26 2020-11-03 2020-11-21 2020-11-25 2021-05-20 tions nvelope es de bureau tory planning and social resil ience MG-MID-SOUTH PROJECT-03 Strengthening decentralized 1-GO-DIR / Achat de logiciel T IDA / V3060 local governments, participa Post Direct Selection Direct 25,000.00 28,893.43 Signed 2020-10-22 2020-11-10 2020-10-27 2020-11-04 2020-12-01 2021-03-05 2021-03-01 OM2PRO et FORMATION tory planning and social resil ience MG-MID-SOUTH PROJECT-00 Strengthening decentralized Request for Quota Single Stage - One E 2-GO-RFQ / Acquisition de 6 IDA / V3060 local governments, participa Post Limited 14,000.00 18,479.66 Signed 2020-10-27 2020-10-27 2020-12-22 2020-11-26 2021-01-06 tions nvelope desktop et 6 Imprimante tory planning and social resil ience MG-MID-SOUTH PROJECT-00 Strengthening decentralized Request for Quota Single Stage - One E 3-GO-RFQ / Acquisition de vid IDA / V3060 local governments, participa Post Limited 1,500.00 0.00 Canceled 2020-10-27 2020-12-22 2021-01-06 tions nvelope eo projecteur tory planning and social resil ience MG-MID-SOUTH PROJECT-00 Strengthening decentralized Request for Quota Single Stage - One E 4-GO-RFQ / Achat photocopie IDA / V3060 local governments, participa Post Limited 14,000.00 3,907.44 Signed 2020-10-27 2020-11-05 2020-12-22 2020-12-08 2021-01-06 tions nvelope use de 2 photocopieuses tory planning and social resil ience MG-MID-SOUTH PROJECT-4.A Implementation Support and Request for Quota Single Stage - One E .09.16-PPA-GO / Acquisition d IDA / V3060 Post Limited 25,000.00 48,921.10 Signed 2021-02-06 2021-02-04 2021-04-03 2021-03-10 2021-06-02 knowledge learning tions nvelope e matériels informatique et a uxiliaires MG-MID-SOUTH PROJECT-4.A .08.03-PPA-DC / Acquisition d Implementation Support and Request for Quota Single Stage - One E IDA / D7510 Post Limited 140,000.00 158,383.56 Signed 2021-02-06 2021-01-20 2021-04-03 2021-03-17 2021-04-23 e deux voitures pour le Coor knowledge learning tions nvelope donnateur et pour l'équipe d e l'UNGP MG-MID-SOUTH PROJECT-4.A Implementation Support and Request for Quota Single Stage - One E .08.04-PPA-DC / Achat de 29 IDA / V3060 Post Limited 9,000.00 12,490.31 Signed 2021-02-13 2021-04-14 2021-04-10 2021-06-08 2021-04-20 knowledge learning tions nvelope smartphones MG-MID-SOUTH PROJECT-22 7586-GO-DIR / Acquisition de Implementation Support and Request for Quota Single Stage - One E IDA / D7510 Post Limited 3,700.00 5,044.10 Signed 2021-05-05 2021-09-20 2021-06-30 2021-11-17 2021-07-14 licence du logiciel Microsoft 3 knowledge learning tions nvelope 65 (comprenant l'application TEAMS) MG-MID-SOUTH PROJECT-00 2 CERC-GO-RFQ / Acquisition Contingent Emergency Resp Request for Quota Single Stage - One E IDA / D7510 Post Limited 2,300.00 7,166.77 Signed 2021-05-22 2021-08-30 2021-07-17 2021-12-07 2021-08-06 de matériels informatiques et onse Component tions nvelope accessoires pour l'équipe de suivi CERC MG-MID-SOUTH PROJECT-00 Contingent Emergency Resp Request for Quota Single Stage - One E 1 CERC-GO-RFQ / Achat de m IDA / D7510 Post Limited 900.00 0.00 Canceled 2021-05-22 2021-06-29 2021-07-19 onse Component tions nvelope obilier de bureau pour l'équip e suivi CERC MG-MID-SOUTH PROJECT-4.A Implementation Support and Request for Quota Single Stage - One E .09.005-GO-RFQ / Acquisition IDA / V3060 Post Open - National 8,170.00 935.99 Signed 2021-08-15 2021-10-10 2021-11-16 2021-10-30 knowledge learning tions nvelope de fournitures de bureau et c achet MG-MID-SOUTH PROJECT-4A Implementation Support and Request for Quota Single Stage - One E 07001-GO-RFQ / Acquisition IDA / V3060 Post Open - National 92,105.00 0.00 Canceled 2021-08-15 2021-10-10 2021-10-25 knowledge learning tions nvelope de mobilier de bureau MG-MID-SOUTH PROJECT-4.A .09.011-GO-RFQ / Acquisition Implementation Support and Request for Quota Single Stage - One E de matériels informatiques et IDA / V3060 Post Open - National 92,000.00 23,380.15 Signed 2021-08-17 2021-11-05 2021-10-12 2021-12-07 2021-11-11 knowledge learning tions nvelope auxiliaires pour l’équipe de l’ UNGP/MIONJO répartie en Se pt (07) Lots MG-MID-SOUTH PROJECT-4.A Implementation Support and Single Stage - One E .07.003-GO-RFB / Acquisition IDA / D7510 Post Request for Bids Open - National 500,000.00 432,454.46 Signed 2021-09-28 2021-10-08 2021-10-03 2021-11-08 2021-11-02 2021-11-15 2021-12-02 2021-12-23 2022-01-06 2021-12-15 2022-04-06 knowledge learning nvelope de six (06) voitures MG-MID-SOUTH PROJECT-C1 Strengthening decentralized MAT COM-GO-RFQ / Acquisiti local governments, participa Request for Quota Single Stage - One E IDA / D7510 Post Open - National 61,000.00 49,118.17 Signed 2022-01-18 2022-03-22 2022-05-03 2022-04-21 on de matériels de communi tory planning and social resil tions nvelope cation et équipement ience MG-MID-SOUTH PROJECT-C1 Strengthening decentralized MAT INFO-GO-RFQ / Acquisiti local governments, participa Single Stage - One E on de matériels informatique IDA / D7510 Post Request for Bids Open - National 276,744.00 283,653.19 Signed 2022-01-13 2022-02-07 2022-01-18 2022-02-19 2022-03-01 2022-03-07 2022-03-31 2022-05-19 2022-05-05 2022-07-20 2022-06-04 tory planning and social resil nvelope s et auxiliaires pour les régio ience ns, districts et communes MG-MID-SOUTH PROJECTC1 Strengthening decentralized Request for Quota Single Stage - One E MATDID-GO-RFQ / Acquisition IDA / D7510 local governments, participa Post Open - National 37,358.00 0.00 Canceled 2022-01-18 2022-06-10 2022-03-22 2022-04-21 tions nvelope de matériels didactiques tory planning and social resil ience Page 2 MG-MID-SOUTH PROJECT-C.1 Strengthening decentralized Single Stage - One E MMB-GO-RFQ / Acquisition de IDA / D7510 local governments, participa Post Request for Bids Open - National 138,950.00 49,103.24 Signed 2022-01-26 2022-02-08 2022-01-31 2022-02-19 2022-03-14 2022-03-07 2022-04-13 2022-05-20 2022-05-18 2022-07-09 2022-11-14 nvelope mobiliers de bureau tory planning and social resil ience MG-MID-SOUTH PROJECT-1.A Strengthening decentralized Request for Quota Single Stage - One E .005-GO-RFQ / Acquisition de IDA / D7510 local governments, participa Post Open - National 50,000.00 0.00 Canceled 2022-02-26 2022-07-12 2022-04-23 2022-05-23 tions nvelope panneaux solaires tory planning and social resil ience MG-MID-SOUTH PROJECT-4.. Implementation Support and 07-GO-DIR / Acquisition de m IDA / D7510 Post Direct Selection Direct 23,000.00 0.00 Canceled 2022-03-03 2022-03-14 2022-03-08 2022-04-10 2022-05-10 knowledge learning atériels informatique pour l'é quipe UNGP MG-MID-SOUTH PROJECT-4.A 07.001 / Acquisition laptops Implementation Support and Request for Quota Single Stage - One E IDA / D7510 Post Open - National 22,044.23 44,916.09 Signed 2022-05-16 2022-05-30 2022-07-25 2022-07-21 2022-08-24 professionnels et accessoires knowledge learning tions nvelope pour le personnel du Projet M ionjo MG-MID-SOUTH PROJECT-4.C Implementation Support and Request for Quota Single Stage - One E .5.2.102 / Acquisition mobilie IDA / V3060 Post Open - National 7,083.33 0.00 Signed 2022-05-16 2022-05-30 2022-07-26 2022-08-10 knowledge learning tions nvelope rs de bureau pour l'UNGP/MI ONJO MG-MID-SOUTH PROJECT-4A. 07.01.1-GO-RFQ / ACQUISITI ON DE DIVERS EQUIPEMENT UNGP, répartie en (03) TROIS LOTS. Implementation Support and Request for Quota Single Stage - One E Under Imple IDA / D7510 Post Open - National 30,600.00 0.00 2022-06-12 2022-09-16 2022-07-27 2022-08-26 Lot N°01 : Matériels de vidéo knowledge learning tions nvelope mentation conférence Lot N°02 : Matériels de prése ntation et d'édition Lot N°03 : Equipements rése au et électrique MG-MID-SOUTH PROJECT-2.C Single Stage - One E 02.005.0001 / Acquisition de IDA / D9320 Resiliency infrastructure Post Request for Bids Open - National 495,000.00 0.00 Signed 2022-07-04 2022-07-26 2022-07-09 2022-08-31 2022-08-08 2022-09-02 2022-09-07 2022-10-04 2022-11-20 2023-02-18 nvelope voiture répartie en 3 lots MG-MID-SOUTH PROJECT-2C 020050001-GO-RFQ / Acquisi Request for Quota Single Stage - One E IDA / D9320 Resiliency infrastructure Post Open - National 81,500.00 0.00 Signed 2022-07-05 2022-08-01 2022-08-30 2022-10-29 tion de matériels informatiqu tions nvelope es répartie en 2 lots MG-MID-SOUTH PROJECT-30 4897-GO-RFB / Acquisition de Single Stage - One E IDA / D9320 Resiliency infrastructure Post Request for Bids Open - National 387,000.00 0.00 Signed 2022-07-19 2022-08-19 2022-07-24 2022-09-19 2022-08-23 2022-09-20 2022-09-22 2022-10-06 2022-10-20 2022-12-19 matériel roulant répartie en nvelope 2 lots (lot 1: motos et lot 2: B icyclettes) MG-MID-SOUTH PROJECT-30 Strengthening decentralized 6596-GO-RFQ / Acquisition d local governments, participa Request for Quota Single Stage - One E e téléphone mobile android r IDA / D7510 Post Open - National 125,000.00 0.00 Signed 2022-08-06 2022-12-19 2022-10-01 2022-11-30 tory planning and social resil tions nvelope épartie en 3 lots (Lot 1 : Télé ience phone 1, Lot 2 : Téléphone 2, Lot 3 : Téléphone 3) MG-MID-SOUTH PROJECT-4.C Strengthening decentralized .5.3-GO-RFQ / Acquisition de local governments, participa Request for Quota Single Stage - One E téléphones portables pour Pe IDA / D9320 Post Open - National 5,128.21 0.00 Signed 2022-08-30 2022-09-16 2022-10-25 2022-11-09 tory planning and social resil tions nvelope rsonnel Financement Additio ience nnel Régional et National MG-MID-SOUTH PROJECT-C.1 Strengthening decentralized MAT ROUL-GO-RFQ / Acquisiti local governments, participa Request for Quota Single Stage - One E IDA / D7510 Post Open - National 31,438.00 0.00 Canceled 2022-01-02 2022-03-15 2022-04-14 on de moto et bicyclette pour tory planning and social resil tions nvelope les districts et communes ience MG-MID-SOUTH PROJECT-1A 0207-4C-GO-RFQ / Acquisitio Strengthening decentralized n de matériels didactiques ré local governments, participa Request for Quota Single Stage - One E partie en 5 lots: IDA / D7510 Post Open - National 94,650.00 0.00 Signed 2022-09-24 2022-12-01 2022-11-06 2023-01-05 tory planning and social resil tions nvelope Lot 1 : Tableau mou, Lot 2 : T ience ableau blanc, Lot 3 : Tableau d'affichage avec trépieds, Lot 4 : Flip stand, Lot 5 : Rouleau x flip chart MG-MID-SOUTH PROJECT-3D. Request for Quota Single Stage - One E Under Imple 4.1.5-GO-RFQ / Acquisition d IDA / D9320 Resiliency infrastructure Post Open - National 87,179.00 0.00 2022-09-24 2023-04-25 2022-11-05 2022-12-05 tions nvelope mentation e drone mapping MG-MID-SOUTH PROJECT-3C- 3DD-4C-GO-RFQ / Acquisition Request for Quota Single Stage - One E de matériels techniques répa IDA / D9320 Resiliency infrastructure Post Open - National 36,700.00 0.00 Signed 2022-09-24 2022-11-05 2022-12-05 tions nvelope rtie en 2 lots: Lot 1: GPS, lot 2: Capteur biométrique MG-MID-SOUTH PROJECT-1A. Strengthening decentralized Request for Quota Single Stage - One E 02-4C-GO-RFQ / Acquisition d IDA / D7510 local governments, participa Post Open - National 21,800.00 0.00 Signed 2022-09-24 2022-11-14 2022-11-08 2022-11-28 tions nvelope e boite à doléances tory planning and social resil ience MG-MID-SOUTH PROJECT-1A Strengthening decentralized 02-05-GO-RFQ / Acquisition d local governments, participa Single Stage - One E Under Imple e matériels de secours électri IDA / D7510 Post Request for Bids Open - National 370,000.00 0.00 2022-11-25 2022-11-11 2022-11-30 2022-11-16 2023-01-11 2022-12-15 2023-02-10 2023-01-27 2023-03-17 2023-05-16 tory planning and social resil nvelope mentation ques répartie en 3 lots : Ond ience uleur, power bank et Kit géné rateur MG-MID-SOUTH PROJECT-1A. Strengthening decentralized 02.05-4C-GO-RFQ / Acquisitio local governments, participa Single Stage - One E IDA / D9320 Post Request for Bids Open - National 230,000.00 0.00 Signed 2022-12-01 2022-11-11 2022-12-06 2022-11-18 2023-01-17 2022-12-14 2023-02-16 2023-01-26 2023-03-23 2023-06-21 n d'imprimantes répartie en tory planning and social resil nvelope 3 lots (A4, A3 et A0) ience MG-MID-SOUTH PROJECT-31 Strengthening decentralized Direct - Internation 5272-GO-DIR / Acquisition de IDA / D9320 local governments, participa Post Direct Selection 1,415,640.00 0.00 Signed 2022-11-01 2022-12-08 2022-11-06 2022-10-13 2022-11-25 2023-11-20 al voiture 4x4 tory planning and social resil ience MG-MID-SOUTH PROJECT-1.A Strengthening decentralized Single Stage - One E .04_4.C-GO-RFQ / Acquisition IDA / D7510 local governments, participa Post Request for Bids Open - National 110,000.00 0.00 Signed 2022-11-01 2022-11-11 2022-11-06 2022-11-14 2022-12-18 2022-12-15 2023-01-17 2023-01-07 2023-02-21 2023-05-22 nvelope de tablettes tory planning and social resil ience MG-MID-SOUTH PROJECT-1A 05-02-GO-RFB / Acquisition d Strengthening decentralized e divers mobiliers de bureau local governments, participa Open - Internationa Single Stage - One E Under Imple IDA / D7510 Post Request for Bids 582,094.00 0.00 2022-09-19 2023-03-06 2022-09-24 2022-11-08 2022-11-23 2022-12-14 2023-02-12 x répartie en 4 lots. Lot 1: Ta tory planning and social resil l nvelope mentation ble de réunion, Lot 2 : Armoir ience e de rangement, Lot 3: Table de bureau lots, Lot 4: Chaise s Page 3 MG-MID-SOUTH PROJECT-1A Strengthening decentralized 2C 4C-GO-DIR / Acquisition d local governments, participa Direct - Internation e matériels informatiques en IDA / D9320 Post Direct Selection 1,339,936.00 0.00 Signed 2022-10-28 2022-12-08 2022-11-02 2022-10-13 2022-11-12 2023-03-12 tory planning and social resil al 4 lots (Laptop, Desktop, serv ience eurs, vidéo projecteur) MG-MID-SOUTH PROJECT-4.A Implementation Support and Request for Quota Single Stage - One E Under Imple .03.08-GO-RFQ / Acquisition IDA / D7510 Post Open - National 7,760.00 0.00 2022-11-05 2022-11-14 2022-12-31 2023-01-03 knowledge learning tions nvelope mentation d’équipements de protection MG-MID-SOUTH PROJECT-4.A .03-GO-RFB / Opérationnalisa Implementation Support and Request for Quota Single Stage - One E IDA / D7510 Post Open - National 20,930.00 0.00 Canceled 2023-01-21 2023-03-18 2023-05-17 tion de numéros vert pour le knowledge learning tions nvelope mécanisme de gestion des pl aintes du Projet MG-MID-SOUTH PROJECT-4C. Supporting Resilient liveliho Request for Quota Single Stage - One E 3-GO-RFQ / Acquisition de Kit IDA / D9320 Post Open - National 13,000.00 0.00 Canceled 2022-12-05 2023-01-30 2023-07-29 ods tions nvelope s d'entretien des matériels in formatiques MG-MID-SOUTH PROJECT-1.B .006.1-GO-RFQ / Acquisition de divers matériels répartis e Implementation Support and Request for Quota Single Stage - One E Under Imple n 3 lots: lot 1: matériel pour f IDA / D7510 Post Open - National 32,000.00 0.00 2023-04-15 2023-04-30 2023-05-30 2023-06-29 knowledge learning tions nvelope mentation ormation en coiffure, lot 2 m atériel pour formation en art culinaire, lot 3: mobilier de ra ngement MG-MID-SOUTH PROJECT-4C. Implementation Support and Request for Quota Single Stage - One E Pending Impl 3.1.5.-GO-RFQ / Acquisition d IDA / D9320 Post Open - National 10,000.00 0.00 2024-04-06 2024-06-01 2024-07-01 knowledge learning tions nvelope ementation e papier pour presse numériq ue MG-MID-SOUTH PROJECT-1.B Strengthening decentralized Request for Quota Single Stage - One E Under Imple .04.003-GO-RFQ / Acquisition IDA / D9320 local governments, participa Post Open - National 1,200.00 0.00 2023-05-08 2023-05-22 2023-06-19 2023-07-19 tions nvelope mentation de Sono Portable tory planning and social resil ience MG-MID-SOUTH PROJECT-4C. 1.4.1-GO-RFQ / Acquisition d Implementation Support and Request for Quota Single Stage - One E Under Imple IDA / D9320 Post Open - National 50,000.00 0.00 2023-05-08 2023-05-22 2023-07-03 2023-07-24 e matériels et équipements d knowledge learning tions nvelope mentation e SAP aux Communes et Fok ontany d'intervention MG-MID-SOUTH PROJECT-4A 07001RELAN-GO-RFQ / Acqui Implementation Support and Request for Quota Single Stage - One E Pending Impl IDA / D7510 Post Open - National 4,000.00 0.00 2024-02-10 2024-03-26 2024-04-09 sition de matériels de présen knowledge learning tions nvelope ementation tation : écran et vidéo projec teur MG-MID-SOUTH PROJECT- 4C Implementation Support and Single Stage - One E Pending Impl 2.4C3.-GO-RFB / Acquisition IDA / D9320 Post Request for Bids Open - National 173,513.00 0.00 2023-09-04 2023-09-09 2023-10-09 2023-11-08 2023-12-06 2024-02-04 knowledge learning nvelope ementation d'Imprimante et services rés eaux MG-MID-SOUTH PROJECT-3D. 4.2.2-GO-RFQ / Acquisition d Supporting Resilient liveliho Request for Quota Single Stage - One E Under Imple IDA / D9320 Post Open - National 22,500.00 0.00 2023-05-08 2023-05-22 2023-06-19 2023-07-04 e matériels de lutte contre le ods tions nvelope mentation s feux (citernes, pochettes d' eau, gants,…) MG-MID-SOUTH PROJECT-1.A Strengthening decentralized Request for Quota Single Stage - One E Pending Impl .10-GO-RFQ / Acquisition de f IDA / D7510 local governments, participa Post Open - National 45,390.00 0.00 2023-07-15 2023-08-26 2023-09-10 tions nvelope ementation ourniture pour les formations tory planning and social resil ience MG-MID-SOUTH PROJECT-3.A Supporting Resilient liveliho Single Stage - One E Pending Impl .01.005.4-GO-RFB / Acquisitio IDA / D7510 Post Request for Bids Open - National 256,000.00 0.00 2023-06-15 2023-06-20 2023-07-20 2023-08-19 2023-09-16 2023-11-15 ods nvelope ementation n des intrants et petits matér iels agricoles MG-MID-SOUTH PROJECT-3.C Supporting Resilient liveliho Request for Quota Single Stage - One E Under Imple .03.007-GO-RFQ / Achats de IDA / D7510 Post Open - National 40,000.00 0.00 2023-05-08 2023-05-22 2023-06-19 2023-07-04 ods tions nvelope mentation 04 Stations total (matériels t opographiques) MG-MID-SOUTH PROJECT-4C. Implementation Support and Request for Quota Single Stage - One E Pending Impl 1.1.1-GO-RFQ / Acquisition d IDA / D9320 Post Open - National 2,140.00 0.00 2023-10-14 2023-11-25 2023-12-10 knowledge learning tions nvelope ementation e fournitures de nettoyage MG-MID-SOUTH PROJECT-3.A Supporting Resilient liveliho Single Stage - One E Pending Impl .01.006.2-GO-RFB / Acquisitio IDA / D7510 Post Request for Bids Open - National 500,000.00 0.00 2023-06-15 2023-06-20 2023-07-20 2023-08-19 2023-09-16 2023-12-15 ods nvelope ementation n d'un structure de transform ation agricoles MG-MID-SOUTH PROJECT-3.A .01.006.4-GO-RFB / Acquisitio Supporting Resilient liveliho Single Stage - One E Pending Impl IDA / D7510 Post Request for Bids Open - National 404,000.00 0.00 2023-09-04 2023-09-09 2023-10-09 2023-11-08 2023-12-06 2024-03-05 n d'intrants faisant partie des ods nvelope ementation paquets d’appui aux ménage s vulnérables MG-MID-SOUTH PROJECT-3.C Supporting Resilient liveliho Pending Impl .02.002.0-GO-DIR / Fournitur IDA / D9320 Post Direct Selection Direct - National 150,000.00 0.00 2023-09-01 2023-09-06 2023-09-27 2023-11-26 ods ementation e de semences commerciales MG-MID-SOUTH PROJECT-3.A .01.006-GO-RFB / Acquisition Supporting Resilient liveliho Open - Internationa Single Stage - One E Pending Impl IDA / D9320 Post Request for Bids 1,020,000.00 0.00 2023-09-01 2023-09-06 2023-10-21 2023-11-20 2023-12-18 2024-02-16 de matériels agricoles réparti ods l nvelope ementation en plusieurs lots MG-MID-SOUTH PROJECT-1.A Implementation Support and Request for Quota Single Stage - One E Pending Impl .1.B-GO-RFQ / Acquisition de IDA / D9320 Post Open - National 50,284.00 0.00 2023-07-08 2023-09-02 2023-10-02 knowledge learning tions nvelope ementation Stocks d'encre rechargeable MG-MID-SOUTH PROJECT-4A. 4C-NC-DIR / Acquisition de lic ences, de logiciels, héberge ment, Logiciel ARCGIS Server Implementation Support and Open - Internationa Single Stage - One E Pending Impl IDA / D9320 Post Request for Bids 707,099.00 0.00 2024-02-01 2024-02-06 2024-03-19 2024-04-18 2024-05-23 2024-06-22 + SQL Server pour le fonctio knowledge learning l nvelope ementation nnement hybride du serveur géospatial, Microsoft serveur et Clients Power BI Server de reporting, Logiciel de planific ation territoriale MG-MID-SOUTH PROJECT-4C. 1.4. -GO-RFB / Acquisition du panneau signalétique en dur Implementation Support and Request for Quota Single Stage - One E Pending Impl pour l'affichage des indicatio IDA / D9320 Post Open - National 14,872.00 0.00 2024-02-06 2024-04-02 2024-07-01 knowledge learning tions nvelope ementation ns et informations concernan t la situation météorologique à jour dans 100 Communes li ttorales MG-MID-SOUTH PROJECT-1A. Strengthening decentralized Request for Quota Single Stage - One E Pending Impl 1B.2A.4-GO-RFQ / Acquisition IDA / D9320 local governments, participa Post Open - National 80,000.00 0.00 2023-11-06 2023-12-18 2024-01-02 tions nvelope ementation de machine d'imprimerie tory planning and social resil ience Page 4 MG-MID-SOUTH PROJECT-4.A Implementation Support and Request for Quota Single Stage - One E Pending Impl .03-GO-RFQ / Multiplication d IDA / D9320 Post Open - National 50,000.00 0.00 2023-09-17 2023-10-29 2023-11-13 knowledge learning tions nvelope ementation e documents MG-MID-SOUTH PROJECT-3D. 03.03-GO-RFQ / Acquisition d Supporting Resilient liveliho Request for Quota Single Stage - One E Pending Impl IDA / D7510 Post Open - National 12,000.00 0.00 2023-09-28 2023-11-09 2023-11-30 'équipements de réseau et a ods tions nvelope ementation bonnement internet MG-MID-SOUTH PROJECT-1.B .006-GO-RFQ / Acquisition de Implementation Support and Request for Quota Single Stage - One E Under Imple divers articles de visibilités r IDA / D7510 Post Open - National 15,000.00 0.00 2023-11-20 2023-05-10 2024-01-04 2024-02-03 knowledge learning tions nvelope mentation épartis en deux lots : lots 1 : article en tissu, lot 2: Kit de d ignité MG-MID-SOUTH PROJECT-35 3929-GO-RFQ / Acquisition d Implementation Support and Request for Quota Single Stage - One E Under Imple e divers matériels réparti en IDA / D7510 Post Open - National 25,000.00 0.00 2023-04-23 2023-05-10 2023-06-07 2023-07-07 knowledge learning tions nvelope mentation 2 lots : lot 1 matériel d'anima tion sportive ; lot 2: matériel d'animation culturelle MG-MID-SOUTH PROJECT-4.C Implementation Support and Request for Quota Single Stage - One E Pending Impl .51.303-GO-RFQ / Acquisition IDA / D9320 Post Open - National 4,615.00 0.00 2023-11-07 2023-12-19 2024-01-18 knowledge learning tions nvelope ementation de matériels de prévention C ovid-19 MG-MID-SOUTH PROJECT-1.B Strengthening decentralized Request for Quota Single Stage - One E Pending Impl .04- 4C.2.GO-RFB / Acquisitio IDA / D9320 local governments, participa Post Open - National 23,285.00 0.00 2023-11-07 2024-01-02 2024-03-02 tions nvelope ementation n de caméra professionnel av tory planning and social resil ec pieds ience MG-MID-SOUTH PROJECT-4.A .03.006-GO-RFQ / Acquisition Implementation Support and Request for Quota Single Stage - One E Pending Impl IDA / D7510 Post Open - National 33,102.00 0.00 2023-11-07 2023-12-19 2024-01-03 de matériels de sauvegarde knowledge learning tions nvelope ementation environnementale et sociale MG-MID-SOUTH PROJECT-4A. Supporting Resilient liveliho Single Stage - One E Pending Impl 4C.3D-GO-RFB / Acquisition d IDA / D9320 Post Request for Bids Open - National 331,153.00 0.00 2023-11-02 2023-11-07 2023-12-07 2024-01-06 2024-02-03 2024-04-03 ods nvelope ementation e matériels techniques, élect roniques MG-MID-SOUTH PROJECT-4C. Implementation Support and Request for Quota Single Stage - One E Pending Impl 1.2GO-RFB / Acquisition stati IDA / D9320 Post Open - National 27,000.00 0.00 2023-11-07 2024-01-02 2024-04-01 knowledge learning tions nvelope ementation ons pluviométriques automat iques MG-MID-SOUTH PROJECT-4.A Implementation Support and Pending Impl .05.002.2-GO-DIR / Acquisitio IDA / D7510 Post Direct Selection Direct - National 30,000.00 0.00 2023-11-02 2023-11-07 2023-12-12 2024-01-02 knowledge learning ementation n de fond de carte de Madag ascar NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-MID-SOUTH PROJECT-4.A Implementation Support and Request for Quota Single Stage - One E .09.17-PPA-NC / Recrutement IDA / V3060 Post Limited 12,000.00 3,236.04 Signed 2021-02-20 2021-02-09 2021-04-17 2021-03-26 2025-02-25 knowledge learning tions nvelope Société de nettoyage MG-MID-SOUTH PROJECT-4.A .08-NC-RFQ / Prestation d'ass urances répartie en deux lots Implementation Support and Request for Quota Single Stage - One E : IDA / V3060 Post Limited 11,000.00 0.00 Canceled 2021-08-15 2021-10-10 2022-10-05 knowledge learning tions nvelope - lot 01 : assurance accident et assurance vie des personn els, - lot 02 : assurance santé du personnel et famille MG-MID-SOUTH PROJECT-FA Contingent Emergency Resp O-NC-DIR / Assistance techni IDA / D9320 Prior Direct Selection Direct 6,810,870.00 6,810,870.00 Signed 2022-01-25 2022-01-27 2022-01-30 2022-01-28 2022-03-06 2022-02-08 2022-09-02 onse Component que FAO. Lutte antiacridienn e MG-MID-SOUTH PROJECT-2.C .1 UNICEF-NC-DIR / Assistanc IDA / D9320 Resiliency infrastructure Prior Direct Selection Direct 24,251,450.00 0.00 Signed 2022-03-07 2022-05-18 2022-03-12 2022-05-22 2022-04-10 2023-05-28 2024-04-09 e technique UNICEF MG-MID-SOUTH PROJECT-2B 01005-NC-DIR / Frais d'évalu IDA / D7510 Resiliency infrastructure Post Direct Selection Direct - National 11,728.00 8,178.25 Terminated 2022-07-14 2022-07-22 2022-07-19 2022-07-22 2022-07-29 2022-08-26 2022-11-26 ation ONE de l'EIE du pipelin e Mandrare Sampona MG-MID-SOUTH PROJECT-4A. 02.04-GO-RFQ / Acquisition a Implementation Support and Request for Quota Single Stage - One E IDA / D7510 Post Open - National 25,225.00 0.00 Canceled 2022-02-05 2022-03-21 2022-04-20 rticle de visibilités réparties e knowledge learning tions nvelope n 2 lots : impression goodies sur tissu et autres MG-MID-SOUTH PROJECT-32 Supporting Resilient liveliho 1435-NC-DIR / Relance agrico IDA / D9320 Prior Direct Selection Direct - National 9,906,524.00 0.00 Canceled 2023-02-06 2023-02-11 2023-03-18 2024-03-12 ods le avec FAO MG-MID-SOUTH PROJECT-4C. 1.1.3D-GO-RFB / Confection d Supporting Resilient liveliho Single Stage - One E Pending Impl IDA / D9320 Post Request for Bids Open - National 361,321.00 0.00 2023-10-02 2023-10-07 2023-10-10 2023-11-09 2023-12-14 2024-03-13 'outil de communication sur ods nvelope ementation plusieurs supports MG-MID-SOUTH PROJECT-4.A Supporting Resilient liveliho Request for Quota Single Stage - One E Pending Impl .04.012-GO-RFB / Edition du IDA / D7510 Post Open - National 20,000.00 0.00 2024-02-10 2024-04-06 2024-06-05 ods tions nvelope ementation Magazine Mionjo MG-MID-SOUTH PROJECT-4C. Implementation Support and Request for Quota Single Stage - One E Pending Impl 5.5.3.5-NC-NULL / Conceptio IDA / D9320 Post Open - National 5,000.00 0.00 2023-10-07 2023-11-18 2023-12-18 knowledge learning tions nvelope ementation n d’émissions/Tv et films d'a nimation MG-MID-SOUTH PROJECT-1A. Strengthening decentralized Single Stage - One E Pending Impl 2B.3C.4D-NC-RFB / Location IDA / D9320 local governments, participa Post Request for Bids Open - National 300,800.00 0.00 2024-02-05 2024-02-10 2024-03-11 2024-04-10 2024-05-15 2025-11-13 nvelope ementation de salle et restauration tory planning and social resil ience MG-MID-SOUTH PROJECT-1A. Strengthening decentralized Single Stage - One E Pending Impl 1B.1C-NC-RFB / Location de v IDA / D9320 local governments, participa Post Request for Bids Open - National 405,982.00 0.00 2023-12-04 2023-12-09 2024-01-08 2024-02-07 2024-03-13 2025-09-11 nvelope ementation oiture tory planning and social resil ience CONSULTING FIRMS Page 5 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-MID-SOUTH PROJECT-00 Strengthening decentralized Consultant Qualifi 1-CS-CQS / Etudes environne IDA / D7510 local governments, participa Post Open - National 100,000.00 43,793.13 Signed 2020-02-04 2019-12-16 2020-02-19 2020-02-21 2020-03-07 2020-05-25 2020-03-27 2020-05-25 2020-04-13 2020-05-16 2021-04-13 cation Selection mentales et sociales tory planning and social resil ience MG-MID-SOUTH PROJECT-00 5-CS-CQS / Développement e Consultant Qualifi / Post Open - National 50,000.00 0.00 Canceled 2020-02-04 2020-02-19 2020-03-25 2020-04-24 2020-05-06 2020-11-02 t mise en œuvre de la straté cation Selection gie de communication du Pro jet MG-MID-SOUTH PROJECT-16- Strengthening decentralized Consultant Qualifi CS-CQS / Pipeline technique IDA / V3060 local governments, participa Post Open - National 100,000.00 87,054.90 Signed 2020-09-03 2020-09-03 2020-09-24 2020-11-07 2020-10-05 2020-12-07 2021-02-09 2021-01-11 2021-02-10 2021-07-10 cation Selection d'audit Sampona tory planning and social resil ience MG-MID-SOUTH PROJECT-15- Strengthening decentralized CS-CQS / Etudes sur la resso local governments, participa Consultant Qualifi urce en eau au niveau des de IDA / V3060 Post Open - National 180,000.00 208,529.53 Signed 2020-09-03 2020-09-03 2020-09-24 2020-11-07 2020-12-23 2020-12-07 2021-04-21 2021-01-11 2021-05-15 2021-07-10 tory planning and social resil cation Selection s points de captage des pipel ience ines Sampona et Ampotaka MG-MID-SOUTH PROJECT-17- CS-SFQC / Étude des ressour Strengthening decentralized ces en eau et de la situation local governments, participa Quality And Cost- de référence des périmètres i IDA / V3060 Post Open - National 100,000.00 40,235.89 Signed 2020-09-07 2020-09-10 2020-09-28 2020-11-11 2020-12-03 2020-12-09 2021-01-18 2021-01-08 2021-02-22 2021-02-12 2021-03-01 2021-03-19 2021-04-27 2022-03-19 tory planning and social resil Based Selection rrigués au niveau des bassin ience s versants des Districts de Be troka, d'Ambovombe et d'An kazoabo MG-MID-SOUTH PROJECT-03 Strengthening decentralized 0-CS-CQS / Recrutement d'un local governments, participa Consultant Qualifi IDA / V3060 Post Limited 20,000.00 23,358.82 Signed 2020-10-28 2020-11-10 2020-11-11 2020-11-10 2020-12-11 2020-11-24 2021-01-15 2020-11-25 2021-01-21 Cabinet pour l'élaboration du tory planning and social resil cation Selection manuel d'opération du Projet ience MG-MID-SOUTH PROJECT-4.A Strengthening decentralized .03.01-PPA-SQC / Élaboration local governments, participa Consultant Qualifi IDA / V3060 Post Open - National 30,000.00 21,358.94 Signed 2021-03-15 2021-09-09 2021-04-05 2021-10-15 2021-05-19 2022-01-15 2021-06-18 2022-04-28 2021-07-23 2022-06-08 2021-09-21 et mise en œuvre de la Str tory planning and social resil cation Selection atégie de communication du ience Projet MG-MID-SOUTH PROJECT-C1 1-CS-QCBS / Etude sur la mo Quality And Cost- IDA / V3060 Post Open - National 10,000.00 0.00 Canceled 2020-07-29 2020-08-12 2020-08-08 2020-08-14 2020-08-21 2020-08-24 2020-09-08 2020-09-18 2021-09-18 bilisation communautaire et l Based Selection ’engagement citoyen MG-MID-SOUTH PROJECT-00 4 CERC-CS-CDS / Recruteme Contingent Emergency Resp Consultant Qualifi nt d’une agence événementi IDA / D7510 Post Limited 27,500.00 0.00 Canceled 2021-05-17 2021-06-22 2021-05-31 2021-10-06 2021-06-30 2022-03-08 2021-08-04 2022-01-31 onse Component cation Selection elle pour le lancement officiel des activités CERC et du Proj et MG-MID-SOUTH PROJECT-4.A .11.001A-CS-CQS / Recrutem ent de partenaires relais rép Implementation Support and Quality And Cost- Open - Internationa IDA / V3060 Prior 5,330,120.00 0.00 Signed 2021-05-17 2021-07-20 2021-06-28 2021-08-13 2021-08-02 2022-03-14 2021-08-30 2022-04-29 2021-09-29 2022-07-12 2021-10-29 2022-11-14 2021-12-03 2025-03-17 arti en 3 Lots. Lot 1: pour la r knowledge learning Based Selection l égion Anosy, Lot 2: pour la ré gion Androy et Lot 3 : pour la région Atsimo Andrefana. MG-MID-SOUTH PROJECT-4A 05001-CS-INDV / Recrutemen Implementation Support and Consultant Qualifi t d'un cabinet pour la mise e IDA / V3060 Post Open - National 75,000.00 0.00 Canceled 2021-08-10 2021-08-31 2021-10-14 2021-11-13 2021-12-18 2022-06-16 knowledge learning cation Selection n place de la plateforme de c onnaissances géospatiales et la formation du personnel MG-MID-SOUTH PROJECT-2.B .01.003-CS-QBS / Etude de s Consultant Qualifi auvegarde environnementale IDA / V3060 Resiliency infrastructure Post Open - National 170,000.00 96,867.50 Signed 2021-08-10 2021-09-20 2021-08-31 2021-10-14 2021-10-14 2021-12-08 2021-11-13 2022-02-02 2021-12-18 2022-05-10 2022-03-18 cation Selection et sociale pour la réhabilitati on du pipeline de Mandrare-S ampona MG-MID-SOUTH PROJECT-2.B .01.006-CS-QCBS / Recrutem ent du cabinet en vue du con trôle et surveillance des trav Quality And Cost- Open - Internationa aux de réhabilitation et de l’E IDA / V3060 Resiliency infrastructure Prior 1,078,500.00 0.00 Canceled 2021-12-30 2022-10-26 Based Selection l tudes, contrôle et surveillanc e pour le renforcement et l'e xtension des deux pipelines du grand sud : Mandrare-Sa mpona et Ampotaka-Tsihomb e MG-MID-SOUTH PROJECT-2.B .01.06-CS-QCBS / Recruteme nt du cabinet en vue du contr ôle et surveillance des travau Quality And Cost- Open - Internationa x de réhabilitation et de l'Etu IDA / D7510 Resiliency infrastructure Prior 1,078,500.00 0.00 Canceled 2022-01-05 2024-03-25 Based Selection l des, contrôle et surveillance pour le renforcement et l'ext ension des deux pipelines du grand sud : Mandrare-Sampo na et Ampotaka-Tsihombe MG-MID-SOUTH PROJECT-4.B .01.001-CS-LCS / Recrutemen Implementation Support and Least Cost Selecti IDA / D7510 Post Open - National 16,000.00 16,796.42 Signed 2021-09-22 2021-09-27 2021-10-13 2021-11-26 2021-10-20 2021-12-24 2021-11-22 2022-01-23 2022-01-26 2022-02-27 2022-05-17 2022-04-03 2022-04-22 2022-08-01 t cabinet d'Audit exercices p knowledge learning on our 2021/2021, 2022, 2023 MG-MID-SOUTH PROJECT-2.B .01.6-CS-QCBS / Recrutemen t de cabinet pour le contrôle et surveillance des travaux d Quality And Cost- Open - Internationa Under Implement e réhabilitation et de l'Etudes IDA / D7510 Resiliency infrastructure Prior 1,078,500.00 0.00 2021-09-22 2021-10-25 2021-10-13 2021-11-08 2021-11-26 2022-05-30 2021-12-24 2022-06-30 2022-01-23 2022-11-25 2022-02-27 2022-04-03 2025-07-16 Based Selection l ation , contrôle et surveillance pou r le renforcement et l'extensi on des deux pipelines du gra nd sud : Mandrare-Sampona et Ampotaka-Tsihombe MG-MID-SOUTH PROJECT-26 4585-CS-CQS / Recrutement Implementation Support and Consultant Qualifi IDA / D7510 Post Open - National 20,000.00 28,223.00 Signed 2021-11-25 2021-12-12 2021-12-16 2022-01-11 2022-01-29 2022-03-14 2022-02-28 2022-06-07 2022-04-04 2022-08-02 2022-05-19 Cabinet pour l'élaboration du knowledge learning cation Selection Manuel de procédure et d'op ération FA Page 6 MG-MID-SOUTH PROJECT-3B. O1.001-CS-CQS / Recruteme nt de bureaux d’études pour l’étude technique, environne Quality And Cost- IDA / D7510 Resiliency infrastructure Post Open - National 924,000.00 0.00 Signed 2022-01-31 2022-02-14 2022-02-21 2022-03-17 2022-04-06 2022-05-10 2022-05-04 2022-06-08 2022-06-03 2022-08-16 2022-07-08 2022-09-13 2022-08-12 2022-11-10 mentale, contrôle et surveilla Based Selection nce sur la réhabilitation du p érimètre irrigué pour la régio n Androy et Anosy , répartis en six lots MG-MID-SOUTH PROJECT-2.B Consultant Qualifi Under Implement .01.04-CS-QCBS / Etude d'im IDA / D7510 Resiliency infrastructure Post Open - National 140,000.00 0.00 2022-02-18 2022-04-08 2022-03-11 2022-05-02 2022-04-24 2022-11-07 2022-05-24 2022-06-28 2022-11-25 cation Selection ation pact environnemental et soci al MG-MID-SOUTH PROJECT-C.3 B.01-CS-QCBS / Recrutement d'un Cabinet pour l'Etude tec hnique, environnementale, c Supporting Resilient liveliho Quality And Cost- IDA / D7510 Post Open - National 210,000.00 0.00 Canceled 2021-12-28 2022-01-18 2022-03-03 2022-03-31 2022-04-30 2022-06-04 2022-07-09 2022-12-06 ontrôle et surveillance des tr ods Based Selection avaux de réhabilitation du pé rimètre irrigué d'Isoanala, Co mmune Rurale Isoanala, Dist rict Betroka, Région Anosy MG-MID-SOUTH PROJECT-3D. 01.001 -CS-CQS / Recruteme nt d’un cabinet pour l’élabor ation d’un plan d’aménagem Consultant Qualifi IDA / D9320 Resiliency infrastructure Post Open - National 69,231.00 0.00 Signed 2022-04-18 2022-04-15 2022-05-09 2022-04-22 2022-06-22 2022-06-08 2022-07-22 2022-07-07 2022-08-26 2023-02-22 ent et la réalisation de l’étud cation Selection e environnementale et social e (PGES) dans le cadre des a ctivités de renforcement des infrastructures vertes du Proj et Mionjo MG-MID-SOUTH PROJECT-3C 01 02 04-CS-CQS / Recrutem Supporting Resilient liveliho Consultant Qualifi ent d’un Cabinet pour l’évalu IDA / D9320 Post Open - National 150,000.00 0.00 Signed 2022-05-19 2022-05-20 2022-06-09 2022-05-30 2022-07-07 2022-11-07 2022-07-21 2023-03-31 2022-08-25 2022-12-23 ods cation Selection ation de la sécurité des seme nces dans le Grand Sud pour le Projet Mionjo MG-MID-SOUTH PROJECT-1.A .03.02-PPA-NCS / Recruteme Strengthening decentralized nt des Partenaires facilitateur local governments, participa Consultant Qualifi s pour accompagner les SLC, IDA / V3060 Post Open - National 850,000.00 0.00 Canceled 2021-02-15 2021-03-01 2021-03-08 2021-04-21 2021-05-21 2021-06-25 2025-05-05 tory planning and social resil cation Selection AD et, Commune. Répartis e ience n trois lots: - lot 1 : région Anosy, - lot 2: Androy, lot 3 : Atsimo Andrea fana MG-MID-SOUTH PROJECT-2C 020020001-CS-QCBS / Recrut ement d’un consultant charg Quality And Cost- Open - Internationa Under Implement IDA / D9320 Resiliency infrastructure Post 250,000.00 0.00 2022-06-30 2022-06-30 2022-07-21 2022-08-29 2022-09-03 2022-10-06 2022-10-01 2022-12-22 2022-10-31 2023-04-05 2022-12-05 2023-01-09 2023-09-06 é de l’étude des ressources e Based Selection l ation n eau au niveau des points d e captage pour le pipeline de Bemamba Antaritarika MG-MID-SOUTH PROJECT-4.A .05.001-CS-CQS / RECRUTEM ENT D'UN CONSULTANT NATI Consultant Qualifi Open - Internationa Under Implement ONAL OU INTERNATIONAL PO IDA / D7510 Resiliency infrastructure Post 73,076.92 0.00 2022-08-25 2022-09-05 2022-09-15 2022-10-11 2022-10-29 2023-01-17 2022-11-28 2023-01-02 2023-07-01 cation Selection l ation UR L’OPERATIONNALISATION DE LA PLATEFORME DE CON NAISSANCES GEOSPATIALES ET LA FORMATION DU PERSO NNEL MG-MID-SOUTH PROJECT-4.A .01.001-CS-CQS / Team buildi Implementation Support and Consultant Qualifi IDA / D7510 Post Limited 10,200.00 0.00 Canceled 2021-12-08 2022-06-06 2021-12-23 2022-01-07 2022-01-26 2022-02-05 ng annuel et renforcement d knowledge learning cation Selection e capacité de l'équipe MG-MID-SOUTH PROJECT-3.B .04-CS-CQS / Recrutement d' Implementation Support and Consultant Qualifi Under Implement un cabinet pour l'étude d’im IDA / D9320 Post Open - National 80,000.00 0.00 2023-04-03 2022-10-17 2023-04-17 2023-01-06 2023-05-22 2023-06-05 2023-06-24 2023-12-21 knowledge learning cation Selection ation pact environnemental des pé rimètres irrigués à risques su bstantiels MG-MID-SOUTH PROJECT-3D. 4.1.9-CS-CQS / Études techni Supporting Resilient liveliho Consultant Qualifi Under Implement que, environnementale et so IDA / D9320 Post Open - National 35,400.00 0.00 2023-03-15 2023-05-30 2023-03-29 2022-11-22 2023-05-03 2023-05-17 2023-06-05 2023-09-03 ods cation Selection ation ciale pour la construction de bureau pour les cantonneme nts MG-MID-SOUTH PROJECT-4.A .10.002 -CS-CQS / Recruteme nt d'un cabinet chargé de la Implementation Support and Consultant Qualifi Open - Internationa Under Implement IDA / D9320 Post 600,000.00 0.00 2022-10-04 2022-10-20 2022-10-18 2022-11-18 2022-12-01 2023-02-07 2022-12-15 2023-04-17 2023-01-12 2023-07-11 collecte de données pour eff knowledge learning cation Selection l ation ectuer des enquêtes de perc eption sur les réalisations de s sous-composantes MG-MID-SOUTH PROJECT-32 4370-CS-QCBS / Relance étu de préliminaire et caractérisa Quality And Cost- Open - Internationa IDA / D9320 Resiliency infrastructure Post 660,000.00 0.00 Canceled 2022-11-07 2022-11-03 2022-11-22 2022-11-18 2022-12-12 2022-12-27 2023-01-11 2023-02-04 2023-03-11 2023-06-09 tion de 1100 points d'eau rép Based Selection l arties en trois lots: Lot 1 : rég ion Anosy, région : Androy, r égion : Atsimo Andrefana MG-MID-SOUTH PROJECT-4.A .05-CS-CQS / Recrutement d' Implementation Support and Consultant Qualifi un cabinet en vue de la mise IDA / D9320 Post Open - National 190,077.00 0.00 Canceled 2023-03-15 2022-10-06 2023-03-29 2023-05-03 2023-05-17 2023-06-05 2023-12-02 knowledge learning cation Selection en place de la plateforme de connaissances géospatiales MG-MID-SOUTH PROJECT-3.B .01.001-CS-QCBS / Recrutem ent d'un cabinet pour les étu des techniques, environneme Quality And Cost- IDA / D7510 Resiliency infrastructure Prior Open - National 1,061,600.00 0.00 Canceled 2022-08-25 2022-09-02 2022-09-15 2022-10-29 2022-11-26 2022-12-26 2023-01-30 2023-03-06 2023-07-04 ntale, contrôle et surveillanc Based Selection e des travaux d'aménageme nt et de réhabilitation des pé rimètres irriguées financés p ar le Projet Mionjo, repartie e n 02 lots MG-MID-SOUTH PROJECT-2.C .1-CS-QCBS / Etude prélimina ire et caractérisation de 1100 Quality And Cost- Open - Internationa IDA / D9320 Resiliency infrastructure Post 660,000.00 0.00 Canceled 2022-02-23 2022-03-07 2022-03-10 2022-03-17 2022-03-30 2022-05-06 2022-04-14 2022-06-08 2022-04-29 2022-07-07 2022-05-23 2022-06-27 2022-09-25 points d'eau réparties en troi Based Selection l s lots: Lot 1 : région Anosy, r égion : Androy, région : Atsi mo Andrefana MG-MID-SOUTH PROJECT-4.C Implementation Support and Consultant Qualifi .5-CS-CQS / Mise en place d'u IDA / D9320 Post Open - National 82,500.00 0.00 Canceled 2023-03-15 2023-03-29 2023-05-03 2023-05-17 2023-06-05 2023-12-02 knowledge learning cation Selection n système de Suivi et évaluat ion Page 7 MG-MID-SOUTH PROJECT--3. B.01.001CS-QCBS / Recrutem ent d’un cabinet pour les étu des techniques, environneme Quality And Cost- Open - Internationa IDA / D7510 Resiliency infrastructure Prior 1,061,600.00 0.00 Under Review 2023-01-12 2023-03-06 2023-02-02 2023-03-20 2023-03-18 2023-04-15 2023-05-15 2023-06-19 2023-07-24 2024-07-23 ntale, contrôle et surveillanc Based Selection l e des travaux d’aménageme nt et de réhabilitation des pé rimètres irriguées financés p ar le Projet Mionjo, repartie e n 02 lots MG-MID-SOUTH PROJECT-3.B .04.002-CS-CQS / Recruteme Supporting Resilient liveliho Consultant Qualifi nt d'un cabinet pour l'étude IDA / D9320 Post Open - National 80,000.00 0.00 Canceled 2023-03-20 2023-04-03 2023-05-08 2023-05-22 2023-06-10 2023-12-07 ods cation Selection d’impact environnemental de s périmètres irrigués à risque s substantiels MG-MID-SOUTH PROJECT-3.C Supporting Resilient liveliho Consultant Qualifi Pending Impleme .01.002-CS-CQS / Etude sur l IDA / D9320 Post Open - National 150,000.00 0.00 2024-02-05 2024-02-19 2024-04-03 2024-04-17 2024-05-15 2024-09-12 ods cation Selection ntation a situation semencière dans l e Sud. MG-MID-SOUTH PROJECT-4C. 5-CS-CQS / Recrutement d’un Implementation Support and Consultant Qualifi Pending Impleme IDA / D9320 Post Open - National 90,000.00 0.00 2024-02-05 2024-02-19 2024-03-25 2024-04-08 2024-04-27 2025-02-21 cabinet pour la collecte, suivi knowledge learning cation Selection ntation et gestion des données des b énéficiaires du FA MG-MID-SOUTH PROJECT-4C. 1.5.1-CS-CQS / Recrutement d'un consultant communauta Implementation Support and Consultant Qualifi Pending Impleme IDA / D9320 Post Open - National 41,051.00 0.00 2024-01-15 2024-01-29 2024-03-04 2024-03-18 2024-04-06 2024-10-03 ire pour recueil des feed-bac knowledge learning cation Selection ntation k de la population et évaluati on des besoins en communic ation et formation MG-MID-SOUTH PROJECT-4.A .03.001-CS-CQS / Recruteme nt d'un organisme pour la for Implementation Support and Consultant Qualifi Pending Impleme IDA / D9320 Post Open - National 26,316.00 0.00 2023-08-14 2023-08-28 2023-10-02 2023-10-16 2023-11-04 2024-05-02 mation sur le cadre de gestio knowledge learning cation Selection ntation n environnementale et social e et l'étude d'impact environ nemental et social MG-MID-SOUTH PROJECT-4.A .C-CS-CQS / Recrutement d'u n consultant pour la mise à jo Implementation Support and Consultant Qualifi Pending Impleme IDA / D9320 Post Open - National 53,410.00 0.00 2023-08-07 2023-08-21 2023-09-25 2023-10-09 2023-10-28 2024-04-25 ur du manuel de procédure e knowledge learning cation Selection ntation t d'opération et l'élaboration du manuel de gestion des pla intes du Projet MG-MID-SOUTH PROJECT-4.B .03-CS-CQS / Recrutement d' Implementation Support and Consultant Qualifi Pending Impleme un consultant pour la réalisat IDA / D7510 Post Open - National 100,000.00 0.00 2023-11-15 2023-11-29 2024-01-03 2024-01-17 2024-02-05 2024-08-03 knowledge learning cation Selection ntation ion d'une étude sectorielle p our la préparation de la phas e 2 du Projet MG-MID-SOUTH PROJECT-2.C .02.004-CS-CQS / Etude de la Consultant Qualifi Under Implement IDA / D9320 Resiliency infrastructure Post Open - National 100,000.00 0.00 2024-01-15 2023-05-19 2024-01-29 2024-03-04 2024-03-18 2024-04-06 2024-10-03 mise en gestion des infrastru cation Selection ation ctures d'eau potable MG-MID-SOUTH PROJECT-2.C .02.002.0-CS-CQS / Recrutem Consultant Qualifi Pending Impleme ent d'un cabinet pour l'étude IDA / D9320 Resiliency infrastructure Post Open - National 140,000.00 0.00 2024-02-05 2024-02-19 2024-03-25 2024-04-08 2024-04-27 2024-10-24 cation Selection ntation et actualisation des études antérieures sur la protection berges MG-MID-SOUTH PROJECT-2.C .02.003-CS-QCBS / Etudes de Quality And Cost- Open - Internationa Pending Impleme IDA / D9320 Resiliency infrastructure Prior 2,481,000.00 0.00 2023-11-15 2023-12-30 2024-02-26 2024-02-28 2024-03-27 2024-04-13 2024-05-02 2024-10-29 faisabilités techniques et Ela Based Selection l ntation boration du Plan Directeur Ea u Sud MG-MID-SOUTH PROJECT-2.C Implementation Support and Consultant Qualifi Open - Internationa Pending Impleme .02.004.0-CS-CQS / Etude ins IDA / D9320 Post 150,000.00 0.00 2024-02-12 2024-02-26 2024-04-10 2024-04-24 2024-05-22 2024-07-21 knowledge learning cation Selection l ntation titutionnelle sur le devenir de l'AES MG-MID-SOUTH PROJECT-3.B .03.001-CS-CQS / Recruteme nt d'un cabinet pour l'Etude Supporting Resilient liveliho Consultant Qualifi Pending Impleme IDA / D9320 Post Open - National 160,000.00 0.00 2024-02-05 2024-02-19 2024-04-03 2024-04-17 2024-05-15 2024-08-13 technique, environnementale ods cation Selection ntation , contrôle et surveillance sur les systèmes d'irrigation à fai ble coût MG-MID-SOUTH PROJECT-3.C .01.002.0-CS-CQS / Etude tec Supporting Resilient liveliho Consultant Qualifi Open - Internationa Pending Impleme hnique et environnementale IDA / D9320 Post 250,000.00 0.00 2023-11-15 2023-12-06 2024-01-19 2024-02-18 2024-03-24 2024-09-20 ods cation Selection l ntation sur la Création d’un Centre R égional de Recherche du FOF IFA MG-MID-SOUTH PROJECT-2.C .02.002-CS-CQS / Recruteme Consultant Qualifi Pending Impleme nt d'un cabinet pour l'étude s IDA / D9320 Resiliency infrastructure Post Open - National 125,000.00 0.00 2023-11-15 2023-11-29 2024-01-03 2024-01-17 2024-02-05 2024-08-03 cation Selection ntation ur le sauvegarde environnem ental et social pipeline Bema mba Antaritarika MG-MID-SOUTH PROJECT-2.C .02.004--CS-QCBS / Etude de Quality And Cost- Under Implement IDA / D9320 Resiliency infrastructure Post Open - National 600,000.00 0.00 2023-06-12 2023-07-03 2023-08-16 2023-09-13 2023-10-13 2023-11-17 2023-12-22 2024-12-21 la mise en gestion des infrast Based Selection ation ructures d'eau potable MG-MID-SOUTH PROJECT-4C. 5.4.001-CS-CQS / Recruteme Implementation Support and Consultant Qualifi Pending Impleme IDA / D9320 Post Open - National 30,000.00 0.00 2023-11-02 2023-11-16 2023-12-21 2024-01-04 2024-01-23 2024-07-21 nt d'un cabinet pour la mise knowledge learning cation Selection ntation à jour des documents cadres de sauvegarde E&S INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-MID-SOUTH PROJECT-00 Strengthening decentralized Individual Consult 2-CS-INDV / Recrutement Sp IDA / D7510 local governments, participa Post Limited 22,500.00 15,938.37 Signed 2020-02-04 2020-03-19 2020-02-09 2020-06-05 2020-02-19 2020-07-01 2020-03-04 2020-07-28 2021-08-31 ant Selection écialiste en Passation de Mar tory planning and social resil ché ience MG-MID-SOUTH PROJECT-00 Strengthening decentralized Individual Consult 3-CS-INDV / Recrutement Sp IDA / D7510 local governments, participa Post Limited 22,500.00 86,376.07 Signed 2020-02-04 2020-03-18 2020-02-09 2020-06-05 2020-02-19 2020-07-01 2020-03-04 2020-09-25 2021-08-31 ant Selection écialiste en Gestion financièr tory planning and social resil e ience Page 8 MG-MID-SOUTH PROJECT-00 Individual Consult 4-CS-INDV / Recrutement Sp IDA / V3060 Post Limited 15,000.00 16,024.64 Signed 2020-04-29 2020-05-25 2020-05-04 2020-06-19 2020-05-25 2020-09-18 2020-06-29 2020-09-22 2020-12-26 ant Selection écialiste en gestion environn ementale MG-MID-SOUTH PROJECT-00 Strengthening decentralized Individual Consult 9-CS-INDV / Recrutement de IDA / V3060 local governments, participa Post Open 15,000.00 14,318.10 Signed 2020-04-29 2020-05-25 2020-06-09 2020-09-08 2020-06-19 2020-10-08 2020-06-29 2020-10-13 2020-08-04 ant Selection Spécialiste en gestion sociale tory planning and social resil ience MG-MID-SOUTH PROJECT-25- Strengthening decentralized Individual Consult CS-INDV / Elaboration de ma IDA / V3060 local governments, participa Post Limited 20,000.00 0.00 Canceled 2020-10-12 2020-11-10 2020-10-17 2020-11-07 2020-12-12 2021-06-10 ant Selection nuel de procédure du projet tory planning and social resil ience MG-MID-SOUTH PROJECT-21- Strengthening decentralized Individual Consult CS-INDV / Responsable Progr IDA / V3060 local governments, participa Post Limited 18,000.00 71,120.70 Signed 2020-10-28 2020-10-30 2020-11-02 2021-02-11 2020-11-23 2021-02-22 2020-12-28 2021-03-23 2021-12-23 ant Selection ammation Suivi et Evaluation tory planning and social resil ience MG-MID-SOUTH PROJECT-23- Strengthening decentralized Individual Consult CS-INDV / Assistant en passa IDA / V3060 local governments, participa Post Limited 12,000.00 28,990.62 Terminated 2020-10-28 2020-10-30 2020-11-02 2020-12-16 2020-11-23 2020-12-17 2020-12-28 2021-01-05 2021-12-23 ant Selection tion de marché tory planning and social resil ience MG-MID-SOUTH PROJECT-02 Strengthening decentralized Individual Consult 5-CS-INDV / Recrutement Ass IDA / V3060 local governments, participa Post Limited 12,000.00 28,056.86 Signed 2020-11-03 2020-11-10 2020-11-08 2021-01-06 2020-11-29 2021-02-11 2021-01-03 2021-03-12 2021-12-29 ant Selection istant(e) du Coordonnateur tory planning and social resil ience MG-MID-SOUTH PROJECT-02 Strengthening decentralized 4-CS-INDV / Recrutement Res local governments, participa Individual Consult IDA / V3060 Post Limited 18,000.00 71,201.70 Signed 2020-11-03 2020-11-10 2020-11-08 2020-12-09 2020-11-29 2020-12-28 2021-01-03 2021-03-06 2021-12-29 ponsable Gouvernance locale tory planning and social resil ant Selection et de la participation citoyen ience ne MG-MID-SOUTH PROJECT-01 Strengthening decentralized Individual Consult 9-CS-INDV / Recrutement d'u IDA / V3060 local governments, participa Post Limited 28,000.00 0.00 Canceled 2020-10-28 2020-11-02 2020-11-23 2020-12-28 2021-12-23 ant Selection n Coordonnateur National du tory planning and social resil Projet ience MG-MID-SOUTH PROJECT-02 Strengthening decentralized Individual Consult 6-CS-INDV / Recrutement Co IDA / V3060 local governments, participa Post Direct 112,000.00 126,669.97 Signed 2020-11-16 2020-12-14 2020-11-26 2020-12-16 2020-12-17 2021-01-15 2021-01-21 2021-01-26 2024-12-31 ant Selection ordonnateur National tory planning and social resil ience MG-MID-SOUTH PROJECT-22- Strengthening decentralized Individual Consult CS-INDV / Associé de progra IDA / V3060 local governments, participa Post Limited 60,000.00 0.00 Canceled 2020-11-27 2020-12-02 2020-12-23 2021-01-27 2025-01-06 ant Selection mme tory planning and social resil ience MG-MID-SOUTH PROJECT-02 Strengthening decentralized 7-CS-INDV / Recrutement d'u local governments, participa Individual Consult IDA / V3060 Post Limited 72,000.00 50,024.05 Signed 2020-11-30 2021-07-28 2020-12-05 2021-10-14 2020-12-26 2021-12-02 2021-01-30 2021-12-17 2025-01-09 n(e) Responsable en résilienc tory planning and social resil ant Selection e sociale et développement l ience ocale MG-MID-SOUTH PROJECT-02 Strengthening decentralized 8-CS-INDV / Recrutement d'u local governments, participa Individual Consult IDA / V3060 Post Limited 72,000.00 64,081.53 Terminated 2020-11-30 2020-12-03 2020-12-05 2020-12-14 2020-12-26 2021-02-26 2021-01-30 2021-03-10 2025-01-09 n(e) Responsable de la com tory planning and social resil ant Selection munication et information ience MG-MID-SOUTH PROJECT-02 Strengthening decentralized Individual Consult 9-CS-INDV / Recrutement ass IDA / V3060 local governments, participa Post Limited 48,000.00 21,529.34 Terminated 2020-11-30 2020-12-03 2020-12-05 2020-12-09 2020-12-26 2020-12-21 2021-01-30 2021-01-26 2025-01-09 ant Selection istant(e) financier tory planning and social resil ience MG-MID-SOUTH PROJECT-03 Strengthening decentralized Individual Consult 1-CS-INDV / Recrutement co IDA / V3060 local governments, participa Post Limited 48,000.00 39,259.39 Signed 2020-11-30 2020-11-23 2020-12-05 2020-12-09 2020-12-26 2020-12-21 2021-01-30 2021-01-26 2025-01-09 ant Selection mptable tory planning and social resil ience MG-MID-SOUTH PROJECT-03 Strengthening decentralized Individual Consult 2-CS-INDV / Recrutement d'u IDA / V3060 local governments, participa Post Limited 48,000.00 38,080.90 Terminated 2020-11-30 2020-12-15 2020-12-05 2020-12-16 2020-12-26 2020-12-16 2021-01-30 2020-12-18 2025-01-09 ant Selection n Chargée d'appui à la passa tory planning and social resil tion de marchés ience MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult .02.15-PPA-CS / Recrutement IDA / V3060 Post Open 57,500.00 16,949.25 Signed 2021-02-15 2021-06-28 2021-04-05 2021-10-04 2021-04-26 2021-10-13 2021-05-31 2021-11-03 2025-03-11 knowledge learning ant Selection Auditeur interne MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult .02.05-PPA-CS / Recrutement IDA / V3060 Post Open 65,200.00 57,771.65 Signed 2021-02-15 2021-02-11 2021-04-05 2021-04-05 2021-04-26 2021-04-08 2021-05-31 2021-04-09 2025-03-11 knowledge learning ant Selection Responsable du volet irrigati on MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult .02.16-PPA-CS / Recrutement IDA / V3060 Post Limited 43,000.00 23,856.24 Signed 2021-02-01 2021-02-11 2021-02-06 2021-01-26 2021-02-27 2021-02-01 2021-04-03 2021-03-06 2024-10-14 knowledge learning ant Selection Assistant en Passation de ma rches MG-MID-SOUTH PROJECT-4.A .02.04-PPA-CS / Recrutement Implementation Support and Individual Consult IDA / V3060 Post Open 65,200.00 58,336.13 Signed 2021-02-15 2021-04-06 2021-04-05 2021-05-03 2021-04-26 2021-05-11 2021-05-31 2021-06-02 2025-03-11 d'un responsable du volet ea knowledge learning ant Selection u, assainissement et hygiène MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult .03.026-PPA-CS / Recrutemen IDA / V3060 Post Open 2,700.00 0.00 Canceled 2021-03-01 2021-04-19 2021-05-10 2021-06-14 2021-07-14 knowledge learning ant Selection t consultant pour le concepti on du logo MG-MID-SOUTH PROJECT-4.A .02.06-PPA-CS / Recrutement Implementation Support and Individual Consult IDA / V3060 Post Open 65,200.00 59,698.30 Signed 2021-02-15 2021-02-11 2021-04-05 2021-04-05 2021-04-26 2021-05-14 2021-05-31 2021-06-11 2025-03-11 du Responsable du développ knowledge learning ant Selection ement agricole MG-MID-SOUTH PROJECT-4.A .02.09-PPA-CS / Recrutement Implementation Support and Individual Consult IDA / V3060 Post Limited 66,500.00 64,232.19 Signed 2021-02-01 2021-02-11 2021-02-06 2021-02-03 2021-02-27 2021-03-01 2021-04-03 2021-03-06 2025-02-11 du Responsable des opératio knowledge learning ant Selection ns et de la gestion des conna issances MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult .02.10-PPA-CS / Recrutement IDA / V3060 Post Limited 43,000.00 19,687.17 Signed 2021-02-22 2021-04-06 2021-04-12 2021-07-14 2021-05-03 2021-07-16 2021-06-07 2021-08-03 2025-03-18 knowledge learning ant Selection Assistant Gouvernance locale MG-MID-SOUTH PROJECT-4.A .02.10-CS-INDV / Responsabl e en prévention et accompag Implementation Support and Individual Consult IDA / D7510 Post Open 63,750.00 50,637.53 Terminated 2021-04-15 2021-04-28 2021-06-03 2021-07-14 2021-06-24 2021-07-20 2021-07-29 2021-08-19 2025-04-09 nement des VBG (Violence B knowledge learning ant Selection asée sur le Genre) et des VC E (Violence contre les Enfant s) MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult .02.27-CS-IND / Assistant(e) IDA / D7510 Post Open 45,000.00 20,930.75 Signed 2021-04-15 2021-04-28 2021-06-03 2021-06-07 2021-06-24 2021-07-27 2021-07-29 2021-08-20 2025-04-09 knowledge learning ant Selection en programmation et suivi-év aluation Page 9 MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult .02.12-CS-INDV / Responsabl IDA / D7510 Post Open 63,750.00 58,278.99 Signed 2021-04-15 2021-04-28 2021-06-03 2021-07-01 2021-06-24 2021-07-21 2021-07-29 2021-08-20 2025-04-09 knowledge learning ant Selection e Système d'Information Nu mérique MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult IDA / D7510 Post Open 56,250.00 30,726.11 Terminated 2021-04-15 2021-04-28 2021-06-03 2021-11-29 2021-06-24 2021-11-29 2021-07-29 2021-12-21 2025-04-09 .02.18-CS-INDV / Comptable_ knowledge learning ant Selection 2 MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult IDA / D7510 Post Open 56,250.00 31,444.01 Terminated 2021-04-15 2021-04-28 2021-06-03 2021-12-29 2021-06-24 2021-12-03 2021-07-29 2021-12-21 2025-04-09 .02.19-CS-INDV / Comptable_ knowledge learning ant Selection 3 MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult .02.20-CS-INDV / Informaticie IDA / D7510 Post Open 56,250.00 34,493.38 Signed 2021-04-15 2021-04-28 2021-06-03 2021-06-28 2021-06-24 2021-07-15 2021-07-29 2021-08-13 2025-04-09 knowledge learning ant Selection n spécialiste en SIG MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult .02.11-PPA-CS / Recrutement IDA / V3060 Post Open 47,000.00 19,699.54 Signed 2021-04-15 2021-04-28 2021-06-03 2021-07-14 2021-06-24 2021-07-15 2021-07-29 2021-08-03 2025-06-08 knowledge learning ant Selection Infographiste Designer MG-MID-SOUTH PROJECT-03 Strengthening decentralized Individual Consult 0-CS-INDV / Recrutement Sigi IDA / V3060 local governments, participa Post Limited 48,000.00 0.00 Canceled 2020-11-25 2021-04-28 2020-11-30 2020-12-21 2021-01-25 2025-01-04 ant Selection ste tory planning and social resil ience MG-MID-SOUTH PROJECT-00 2-UNICEF-CS-CDS / Assistanc Contingent Emergency Resp e technique de l' UNICEF, fac IDA / D7510 Post Direct Selection Direct 2,000,000.00 2,000,000.00 Signed 2021-04-28 2021-05-31 2021-05-03 2021-04-26 2021-05-09 2021-06-22 2022-10-31 onse Component e aux besoins d'urgence suit e à la crise alimentaire et sèc heresse dans le Sud MG-MID-SOUTH PROJECT-00 1-FAO-CS-CDS / Assistante te Contingent Emergency Resp chnique de FAO face aux bes IDA / D7510 Post Direct Selection Direct 10,000,000.00 10,000,000.00 Signed 2021-04-28 2021-06-29 2021-05-03 2021-04-21 2021-05-09 2021-06-25 2022-05-04 onse Component oins d'urgence suite à la cris e alimentaire dans le sud et à la sècheresse MG-MID-SOUTH PROJECT-01 CERC-CS-INDV / Recrutement Contingent Emergency Resp Individual Consult IDA / D7510 Post Open 34,000.00 32,792.48 Signed 2021-05-27 2021-06-22 2021-07-15 2021-09-13 2021-08-05 2021-10-04 2021-09-09 2021-12-04 2023-03-03 d’un Responsable de la coord onse Component ant Selection ination des activités de la co mposante CERC MG-MID-SOUTH PROJECT-00 2 CERC-CS-INDV / Recruteme Contingent Emergency Resp Individual Consult IDA / D7510 Post Open 11,000.00 841.16 Signed 2021-05-27 2021-06-22 2021-07-15 2021-12-02 2021-08-05 2021-12-08 2021-09-09 2021-12-28 2023-03-03 nt d’un(e) Assistant(e) de co onse Component ant Selection ordination des activités de la composante CERC MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult .02.08-CS-INDV / Recrutemen IDA / D7510 Post Limited 27,000.00 19,219.06 Signed 2021-07-01 2021-06-28 2021-07-06 2021-07-15 2021-07-27 2021-08-18 2021-08-31 2021-09-02 2025-02-11 knowledge learning ant Selection t chargé d'Appui Passation d e marchés MG-MID-SOUTH PROJECT-4.A .04-CS-INDV / Recrutement d Implementation Support and Individual Consult IDA / D7510 Post Open 20,000.00 39,506.49 Signed 2021-07-30 2021-09-16 2021-09-17 2022-04-04 2021-10-08 2022-03-30 2021-11-12 2022-04-27 2022-02-10 ’un consultant pour l’élaborat knowledge learning ant Selection ion d’un plan de gestion de s écurité MG-MID-SOUTH PROJECT-4.A .02.08.A-CS-INDV / Recrutem Implementation Support and Individual Consult IDA / D7510 Post Limited 52,000.00 37,168.46 Terminated 2021-08-10 2020-12-15 2021-08-15 2021-06-29 2021-09-05 2021-07-08 2021-10-10 2021-10-11 2025-01-22 ent de deux Chargés d'Appui knowledge learning ant Selection à la passation de marchés MG-MID-SOUTH PROJECT-2.A .01.01-CS-INDV / Recrutemen Individual Consult t d’un consultant national po IDA / D7510 Resiliency infrastructure Post Open 11,053.00 8,040.49 Signed 2021-09-14 2021-09-30 2021-11-02 2022-06-03 2021-11-23 2022-06-07 2021-12-28 2022-07-07 2022-02-16 ant Selection ur la mise à jour du guide de maîtrise d'ouvrage communa le (MOC) MG-MID-SOUTH PROJECT-5.A .02.001-CS-CDS / Recruteme Contingent Emergency Resp nt Cabinet pour la mis à jour IDA / D7510 Post Direct Selection Direct 30,000.00 16,135.44 Signed 2021-09-17 2021-09-22 2021-09-27 2021-10-14 2021-12-01 2021-11-16 2021-12-31 onse Component des documents cadre Sauveg arde Environnementale MG-MID-SOUTH PROJECT-25 Implementation Support and Individual Consult IDA / D7510 Post Open 39,000.00 0.00 Canceled 2021-09-27 2021-10-04 2021-11-15 2021-12-06 2022-01-10 2025-03-25 5065-CS-INDV / Gestionnaire knowledge learning ant Selection de contrat MG-MID-SOUTH PROJECT-2.A .01.001-CS-INDV / Recruteme Individual Consult nt d’un consultant national p IDA / V3060 Resiliency infrastructure Post Open 11,053.00 0.00 Canceled 2021-07-30 2021-09-17 2021-10-08 2021-11-12 2022-01-01 ant Selection our la mise à jour du guide d e maîtrise d'ouvrage commu nale (MOC) MG-MID-SOUTH PROJECT-4A 08.01-1-CS-INDV / Recrutem Implementation Support and Individual Consult IDA / D7510 Post Open 56,200.00 45,454.39 Signed 2021-10-06 2021-10-06 2021-11-09 2022-01-11 2021-11-30 2022-01-18 2022-01-04 2022-03-04 2025-02-17 ent d’un Responsable de la P knowledge learning ant Selection révention et de l’Accompagn ement des VBG/VCE MG-MID-SOUTH PROJECT-AT Supporting Resilient liveliho FAO-CS-CDS / Assistance tec IDA / D9320 Prior Direct Selection Direct 6,810,870.00 0.00 Canceled 2021-12-23 2021-12-28 2022-01-03 2022-12-29 ods hnique FAO. Lutte antiacridiè ne MG-MID-SOUTH PROJECT-4.A .5.1.2-CS-INDV / Recrutemen Implementation Support and Individual Consult IDA / D9320 Post Open 68,000.00 48,156.29 Terminated 2022-02-17 2022-04-08 2022-04-07 2022-08-26 2022-04-28 2022-08-26 2022-06-02 2022-09-26 2025-01-17 t Responsable de la Coordina knowledge learning ant Selection tion régionale du projet Andr oy MG-MID-SOUTH PROJECT-4.A .5.1.2.A-CS-INDV / Recrutem Implementation Support and Individual Consult IDA / D9320 Post Open 68,000.00 0.00 Signed 2022-02-17 2022-04-08 2022-04-07 2022-08-24 2022-04-28 2022-09-16 2022-06-02 2025-01-17 ent Responsable de la Coordi knowledge learning ant Selection nation du Projet Mionjo, Régi on Atsimo Andrefana MG-MID-SOUTH PROJECT-4.A .5.1.2B-CS-INDV / Recruteme Implementation Support and Individual Consult IDA / D9320 Post Open 22,000.00 0.00 Signed 2022-02-17 2022-04-08 2022-04-07 2022-11-23 2022-04-28 2022-12-08 2022-06-02 2025-01-17 nt d'un Assistant de Coordina knowledge learning ant Selection tion Régionale du Projet, Rég ion Atsimo Andrefana MG-MID-SOUTH PROJECT-4.A .5.1.2C-CS-INDV / Recruteme Implementation Support and Individual Consult IDA / D9320 Post Open 22,000.00 0.00 Signed 2022-02-17 2022-04-08 2022-04-07 2022-11-23 2022-04-28 2022-12-01 2022-06-02 2025-01-17 nt d'un Assistant de Coordina knowledge learning ant Selection tion Régionale du Projet, Rég ion Anosy MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult .08.01AF-CS-INDV / Recrutem IDA / D9320 Post Open 11,076.00 15,344.29 Terminated 2022-02-17 2022-04-08 2022-04-07 2022-06-03 2022-04-28 2022-06-13 2022-06-02 2022-08-06 2025-01-17 knowledge learning ant Selection ent d'un Assistant Financier d u Projet Mionjo Page 10 MG-MID-SOUTH PROJECT-25 Implementation Support and Individual Consult 5065-CS-INDV-2 / Recruteme IDA / D7510 Prior Open 38,000.00 0.00 Canceled 2022-03-03 2022-04-06 2022-04-20 2022-05-25 2025-10-16 knowledge learning ant Selection nt Gestionnaire de Contrat MG-MID-SOUTH PROJECT-28 Implementation Support and Individual Consult 4604-CS-INDV / Recrutement IDA / D7510 Prior Open 38,000.00 0.00 Signed 2022-03-16 2022-04-20 2022-04-19 2022-08-19 2022-05-03 2022-10-10 2022-05-13 2024-12-31 knowledge learning ant Selection Gestionnaire de Contrat MG-MID-SOUTH PROJECT-1B. 06.003-CS-INDV / Recruteme Strengthening decentralized nt d'un consultant individuel local governments, participa Individual Consult en vue de la capitalisation de IDA / D7510 Post Open 13,000.00 30,916.79 Signed 2022-03-31 2022-04-11 2022-05-19 2022-06-24 2022-06-09 2022-08-10 2022-07-14 2022-08-06 2022-08-13 tory planning and social resil ant Selection s études diagnostiques et de ience s actions d'intégration du Vol et Genre réalisées dans le Gr and Sud et cartographie des acteurs MG-MID-SOUTH PROJECT-28 7674-CS-INDV / Recrutement Implementation Support and Individual Consult d’un Consultant pour le dével IDA / V3060 Post Open 2,500.00 200,210.76 Signed 2022-03-31 2022-04-07 2022-04-08 2022-08-03 2022-04-13 2022-04-04 2022-04-29 2022-04-06 2022-10-26 knowledge learning ant Selection oppement de la performance collective de l’UNGP MG-MID-SOUTH PROJECT-11. 001 -CS-SED / Recrutement d e Prestataires d’appui aux Co mmunes chargés d’accompa Implementation Support and IDA / D7510 Post Direct Selection Direct 77,000.00 98,705.87 Signed 2022-04-14 2022-04-15 2022-04-24 2022-05-02 2022-06-28 2022-05-18 2022-12-25 gner et de renforcer la capac knowledge learning ité des Communes dans la mi se en œuvre des projets d’inf rastructures par maîtrise d’o uvrage communale MG-MID-SOUTH PROJECT-4.C Implementation Support and Individual Consult .5.2.201-CS-INDV / Recrutem IDA / D9320 Post Open 8,769.00 919.11 Signed 2022-04-25 2022-04-25 2022-05-30 2022-07-19 2022-05-31 2022-07-21 2022-06-21 2022-09-03 2024-12-07 knowledge learning ant Selection ent de chef comptable pour l' UNGP MIONJO MG-MID-SOUTH PROJECT-1.B .03.003 -CS-INDV / Recrutem ent d’un Consultant pour l’él Strengthening decentralized aboration de la Stratégie de local governments, participa Individual Consult IDA / D7510 Post Open 25,000.00 30,918.09 Signed 2022-04-26 2022-05-10 2022-05-29 2022-07-21 2022-06-03 2022-07-21 2022-06-24 2022-08-31 2022-10-22 mise en place et d’opération tory planning and social resil ant Selection nalisation d’un Système Com ience munautaire d’Alerte Précoce et de Réponse (SCAPR) au ni veau des Communes du Proj et Mionjo MG-MID-SOUTH PROJECT-4C. 5-CS-INDV / Recrutement d'u Implementation Support and Individual Consult IDA / D7510 Post Open 39,000.00 0.00 Signed 2022-04-27 2022-08-03 2022-05-31 2022-08-25 2022-06-21 2022-08-25 2022-07-26 2025-09-08 n Responsable des infrastruc knowledge learning ant Selection tures vertes et des paysages résilients PROJET MG-MID-SOUTH-4.A. Implementation Support and Individual Consult 02.08.A-CS-INDV / Recrutem IDA / D7510 Prior Open 12,307.69 0.00 Signed 2022-05-11 2022-05-18 2022-06-29 2022-10-13 2022-07-20 2022-11-21 2022-08-24 2024-12-31 knowledge learning ant Selection ent Secrétaire en passation d e marchés MG-MID-SOUTH PROJECT-4A 10006-CS-INDV / Recrutemen Implementation Support and Individual Consult t d’un consultant chargé de l IDA / D7510 Post Open 82,500.00 0.00 Signed 2022-05-19 2022-07-21 2022-06-21 2022-09-09 2022-07-05 2022-12-19 2022-07-20 2023-07-15 knowledge learning ant Selection a mise en place du Système de suivi-évaluation du Projet MG-MID-SOUTH PROJECT-2B 01009-CS-CDS / Recrutement d'un Cabinet pour l'assistanc IDA / D7510 Resiliency infrastructure Post Direct Selection Direct 20,000.00 18,935.19 Signed 2022-05-11 2022-05-24 2022-05-21 2022-05-25 2022-06-01 2022-08-31 2022-07-01 e à la maitrise d'ouvrage dél éguée dans le cadre de la ré habilitation du pipeline de Ma ndrare Sampona MG-MID-SOUTH PROJECT-3D 02-CS-CDS / Assistance techn Supporting Resilient liveliho ique dans le cadre de la mise IDA / D9320 Prior Direct Selection Direct 7,900,000.00 0.00 Canceled 2022-05-11 2022-05-21 2022-07-25 2025-03-11 ods en œuvre des activités de cei ntures vertes avec Tany Mev a MG-MID-SOUTH PROJECT-3D 05-CS-CDS / Assistance techn Supporting Resilient liveliho ique dans le cadre de la mise IDA / D9320 Prior Direct Selection Direct 11,006,671.00 0.00 Canceled 2022-05-11 2022-05-21 2022-07-25 2025-03-11 ods en œuvre des activités de cei ntures vertes avec CRS MG-MID-SOUTH PROJECT-4.A .02.28-CS-INDV / Recrutemen Implementation Support and Individual Consult t d'un (e) Assistant(e) en sau IDA / D7510 Post Open 56,250.00 0.00 Canceled 2021-05-10 2021-09-07 2021-06-28 2021-07-19 2021-08-23 2025-02-03 knowledge learning ant Selection vegarde environnementale e t sociale région Anosy MG-MID-SOUTH PROJECT-4.A .02.34-CS-INDV / Recrutemen Implementation Support and Individual Consult t d'un (e) Assistant(e) en sau IDA / D7510 Post Open 56,250.00 0.00 Canceled 2021-05-10 2021-09-07 2021-06-28 2021-07-19 2021-08-23 2025-02-03 knowledge learning ant Selection vegarde environnementale e t sociale région Atsimo Andre fana MG-MID-SOUTH PROJECT-4.A .02.35-CS-INDV / Recrutemen Implementation Support and Individual Consult t d'un (e) Assistant(e) en sau IDA / D7510 Post Open 56,250.00 0.00 Canceled 2021-05-10 2021-09-07 2021-06-28 2021-07-19 2021-08-23 2025-02-03 knowledge learning ant Selection vegarde environnementale e t sociale région Androy MG-MID-SOUTH PROJECT-3 D 02 -CS-CDS / Recrutement A GEX pour la MO des activités de fixation des dunes, mise e Supporting Resilient liveliho n place de pépinière perman IDA / D9320 Prior Direct Selection Direct 8,475,803.00 0.00 Signed 2022-05-27 2022-06-24 2022-06-06 2022-07-18 2022-07-25 2025-03-11 ods entes et temporaires, reboise ment à vocation multiple et r estauration des fôret naturell es dans les districts de Moro mbe, Toliara II, Betioky, Belo ha, Bekily MG-MID-SOUTH PROJECT-3 D 05-CS-CDS / Recrutement AG EX pour la MO des activités d e fixation des dunes, de brise Supporting Resilient liveliho s vent, mise en place de pépi IDA / D9320 Prior Direct Selection Direct 11,433,329.00 0.00 Signed 2022-05-27 2022-06-24 2022-06-06 2022-07-18 2022-06-30 2025-02-14 ods nière permanentes et tempor aires, reboisement à vocatio n multiple et restauration de s grands bassins versant dan s les districts de d’Ambovom be, Tsihombe, Page 11 MG-MID-SOUTH PROJECT-3C. 01.003 -CS-CDS / Recruteme nt d'un cabinet pour l'Assista Supporting Resilient liveliho IDA / D9320 Prior Direct Selection Direct 3,250,000.00 0.00 Signed 2022-06-20 2022-08-23 2022-06-30 2022-09-28 2022-07-11 2023-06-08 2025-03-31 nce technique pour la promot ods ion de la production et transf ormation de patates douces à chair orange MG-MID-SOUTH PROJECT-3C. 01.004 -CS-CDS / Recruteme nt d'un consultant pour l'assi stance technique pour la mis IDA / D9320 Resiliency infrastructure Prior Direct Selection Direct 3,250,000.00 0.00 Signed 2022-06-20 2022-07-26 2022-06-30 2022-08-03 2022-07-11 2024-12-31 e en œuvre de projet de cant ine scolaire basé sur les acha ts locaux -Home Grown Scho ol Meals (HGSM) MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult .08.001-CS-INDV / Recruteme IDA / D7510 Post Open - National 17,000.00 0.00 Signed 2022-08-01 2022-08-04 2022-09-19 2022-11-12 2022-10-10 2023-01-26 2022-11-14 2023-05-13 knowledge learning ant Selection nt d'un Chargé en Passation de Marchés MG-MID-SOUTH PROJECT-4.A Implementation Support and Individual Consult .08.01-CS-INDV / Recrutemen IDA / D7510 Post Open - National 46,102.00 0.00 Signed 2022-08-01 2022-08-04 2022-09-19 2023-01-27 2022-10-10 2023-02-01 2022-11-14 2025-03-03 knowledge learning ant Selection t de deux comptables MG-MID-SOUTH PROJECT-4A Implementation Support and Individual Consult 08.001-CS-INDV / Recruteme IDA / D7510 Post Open - National 49,256.41 0.00 Signed 2022-08-12 2022-08-25 2022-09-30 2022-11-25 2022-10-21 2022-12-01 2022-11-06 2025-02-23 knowledge learning ant Selection nt d'un Responsable en Gesti on Financière MG-MID-SOUTH PROJECT-4.A Strengthening decentralized .10.008-CS-INDV / Recruteme local governments, participa Individual Consult nt d'un consultant chargé de IDA / D7510 Post Open - National 20,000.00 0.00 Signed 2022-08-25 2022-08-30 2022-10-13 2022-12-12 2022-11-03 2023-03-16 2022-12-08 2023-01-22 tory planning and social resil ant Selection l'évaluation à mi-parcours de ience s prestations de l'UNICEF et d e la FAO MG-MID-SOUTH PROJECT-4.A .01.01-CS-INDV / Recrutemen Implementation Support and Individual Consult IDA / D7510 Post Open - National 20,000.00 0.00 Canceled 2023-06-01 2023-07-01 2023-07-08 2023-07-27 2023-09-25 t d'un consultant pour le Coa knowledge learning ant Selection ching des team buildings du Projet MG-MID-SOUTH PROJECT-4.C .04-CS-CDS / Assistant Techn Implementation Support and IDA / D9320 Post Direct Selection Direct - National 32,000.00 0.00 Signed 2022-10-03 2022-10-07 2022-10-13 2022-10-06 2022-11-06 2023-01-25 ique non permanent auprès knowledge learning de l’UNGP Mionjo MG-MID-SOUTH PROJECT-33 5419-CS-INDV / RECRUTEME Implementation Support and Individual Consult IDA / D7510 Post Open - National 34,500.00 0.00 Canceled 2023-01-12 2023-01-12 2023-03-02 2023-03-23 2023-04-20 2025-03-20 NT D’UN/UNE RESPONSABLE knowledge learning ant Selection PRINCIPAL DU VOLET AGRICU LTURE MG-MID-SOUTH PROJECT-33 5805-CS-INDV / Recrutement Implementation Support and Individual Consult IDA / D7510 Post Open - National 14,500.00 0.00 Signed 2023-01-16 2023-02-08 2023-03-06 2023-04-06 2023-03-27 2023-04-11 2023-05-01 2025-04-20 d'un(e) assistant(e) en passa knowledge learning ant Selection tion de marchés MG-MID-SOUTH PROJECT-2.C .02.006-CS-INDV / Recruteme Individual Consult Pending Impleme IDA / D9320 Resiliency infrastructure Post Open - National 15,000.00 0.00 2024-01-08 2024-02-07 2024-02-14 2024-03-04 2024-05-03 nt d'un consultant pour l'Etud ant Selection ntation e sur la réhabilitation locaux DREAH (3) MG-MID-SOUTH PROJECT-34 Implementation Support and Individual Consult Under Implement 3650-CS-INDV / Recrutement IDA / D7510 Post Open - National 20,000.00 0.00 2023-02-22 2023-04-18 2023-03-29 2023-04-28 2023-04-12 2023-05-03 2023-04-26 2024-12-16 knowledge learning ant Selection ation d'un(e) Gestionnaire de contr at MG-MID-SOUTH PROJECT-32 Implementation Support and Individual Consult 1327-CS-INDV / Recrutement IDA / D9320 Prior Open - National 27,000.00 0.00 Canceled 2022-11-28 2022-12-19 2023-01-16 2023-02-06 2023-03-13 2025-05-01 knowledge learning ant Selection Spécialiste en Passation de marchés MG-MID-SOUTH PROJECT-4.A .5.1-CS-INDV / Recrutement Implementation Support and Individual Consult Under Implement IDA / D9320 Post Open - National 37,206.00 0.00 2023-02-21 2023-03-18 2023-04-11 2023-04-25 2023-05-23 2025-01-12 d'un(e) responsable de la Co knowledge learning ant Selection ation ordination Androy MG-MID-SOUTH PROJECT-3.C .06.001-CS-QCBS / Etude des Supporting Resilient liveliho Under Implement ressources en eau et de la sit IDA / D9320 Post Direct Selection Direct - National 100,000.00 0.00 2023-03-06 2023-03-24 2023-03-16 2023-04-05 2023-05-20 2023-07-19 ods ation uation de référence dans les Districts de Bekily Ampanihy et Benenitra MG-MID-SOUTH PROJECT-32 1327-CS-INDV-2 / Relance re Implementation Support and Individual Consult Under Implement IDA / D9320 Prior Open - National 19,000.00 0.00 2023-03-15 2023-03-28 2023-05-03 2023-05-31 2023-05-24 2023-06-28 2025-02-17 crutement spécialiste en pas knowledge learning ant Selection ation sation de marchés MG-MID-SOUTH PROJECT-34 Implementation Support and Individual Consult Under Implement 8231-CS-INDV / Recrutement IDA / D9320 Post Open - National 29,000.00 0.00 2023-03-13 2023-03-28 2023-05-01 2023-05-22 2023-06-26 2025-02-15 knowledge learning ant Selection ation du Responsable de la ressour ce Humaine MG-MID-SOUTH PROJECT-4A Strengthening decentralized 04 MO-CS-CQS / Mise en œuv local governments, participa Under Implement IDA / V3060 Post Direct Selection Direct - National 157,431.00 0.00 2023-03-31 2023-05-30 2023-04-10 2023-06-14 2023-12-11 re de la stratégie de commun tory planning and social resil ation ication et organisation atelier ience MG-MID-SOUTH PROJECT- 4C .5.6.3. -CS-INDV / Recruteme Implementation Support and Individual Consult Pending Impleme nt d'un consultant pour la Ca IDA / D9320 Post Open - National 7,500.00 0.00 2024-03-04 2024-04-03 2024-04-10 2024-04-29 2024-06-28 knowledge learning ant Selection ntation pitalisation et retour d'expéri ences des activités du FA. MG-MID-SOUTH PROJECT-4C. 1.2.1-CS-INDV / Recrutement d’un consultant pour la budg Implementation Support and Individual Consult Pending Impleme IDA / D9320 Post Open - National 3,600.00 0.00 2024-02-05 2024-03-06 2024-03-13 2024-04-01 2024-05-31 étisation et l’élaboration du p knowledge learning ant Selection ntation lan du centre de constructio n centre opérationnel moder ne à Atsimo Andrefana MG-MID-SOUTH PROJECT-4C. 5.6.1-CS-INDV / Recrutement Implementation Support and Individual Consult Pending Impleme d'un consultant pour l'enquêt IDA / D9320 Post Open - National 25,000.00 0.00 2024-01-08 2024-02-07 2024-02-14 2024-03-04 2024-05-03 knowledge learning ant Selection ntation e périodique de perception et de satisfaction des parties pr enantes MG-MID-SOUTH PROJECT-4C. 5.5.3.1-CS-INDV / Recruteme Implementation Support and Individual Consult Pending Impleme IDA / D9320 Post Open - National 4,100.00 0.00 2024-02-05 2024-03-06 2024-03-13 2024-04-01 2024-05-31 nt d'un animateur local pour knowledge learning ant Selection ntation l'atelier de sensibilisation de 200 personnes Page 12 MG-MID-SOUTH PROJECT-4C. 1.2.3-CS-INDV / Recrutement Supporting Resilient liveliho Individual Consult Pending Impleme d'un consultant pour la Mise IDA / D9320 Post Open - National 5,000.00 0.00 2024-01-08 2024-02-07 2024-02-14 2024-03-04 2024-05-03 ods ant Selection ntation en place d'un mécanisme de suivi des personnes déplacée s dans le Sud MG-MID-SOUTH PROJECT-1.A Strengthening decentralized .09.001-CS-INDV / Recruteme local governments, participa Individual Consult Pending Impleme nt d'un consultant pour la fin IDA / D7510 Post Open - National 6,579.00 0.00 2023-12-04 2024-01-03 2024-01-10 2024-01-29 2024-03-29 tory planning and social resil ant Selection ntation alisation du Plan Régional de ience Développement Androy MG-MID-SOUTH PROJECT-4C. 5.3.3.1-CS-INDV / Recruteme Implementation Support and Individual Consult Pending Impleme IDA / D9320 Post Open - National 21,000.00 0.00 2024-02-15 2024-03-16 2024-03-23 2024-04-11 2024-06-10 nt d'un consultant intégrateu knowledge learning ant Selection ntation r en système d'identification biométrique MG-MID-SOUTH PROJECT-4C. 2.1.3.0-CS-INDV / Recruteme nt d'un consultant pour la for Implementation Support and Individual Consult Pending Impleme IDA / D9320 Post Open - National 21,000.00 0.00 2024-02-15 2024-03-16 2024-03-23 2024-04-11 2024-06-10 mation dans l'exploitation de knowledge learning ant Selection ntation s outils et collecte, analyse e t synchronisation des donnée s MG-MID-SOUTH PROJECT-4C. 5.5.1.1 -CS-INDV / Recruteme Implementation Support and Individual Consult Pending Impleme IDA / D9320 Post Open - National 9,230.00 0.00 2024-02-15 2024-03-16 2024-03-23 2024-04-11 2024-06-10 nt d'un Animateur local pour knowledge learning ant Selection ntation l'atelier de mobilisation des l eaders d'opinions. MG-MID-SOUTH PROJECT-4.A .05-CS-CDS / Etude prospecti Supporting Resilient liveliho Pending Impleme ve pour l'identification de be IDA / D7510 Post Direct Selection Direct - National 50,000.00 0.00 2024-02-15 2024-02-25 2024-04-30 2024-10-27 ods ntation soin futur en digitalisation de s services à destination de la population MG-MID-SOUTH PROJECT-4.A .04.009 -CS-INDV / Recrutem ent d'un consultant pour le Implementation Support and Individual Consult Pending Impleme renforcement de capacités e IDA / D7510 Post Open - National 15,000.00 0.00 2024-02-15 2024-04-04 2024-04-25 2024-05-30 2024-11-26 knowledge learning ant Selection ntation n communication (journalism e et multimédia) aux respons ables des Région-Districts-Co mmunes. MG-MID-SOUTH PROJECT-35 Implementation Support and Under Implement 8588-CS-CDS / Recrutement IDA / D9320 Post Direct Selection Direct - National 32,000.00 0.00 2023-04-27 2023-05-11 2023-05-07 2023-05-19 2023-05-31 2023-08-19 knowledge learning ation assistant technique sénior MG-MID-SOUTH PROJECT-4C. 1.1.5.0-CS-INDV / Recruteme nt d'un consultant pour la mi Implementation Support and Individual Consult Pending Impleme IDA / D9320 Post Open - National 18,000.00 0.00 2022-10-10 2022-11-09 2022-11-16 2022-12-05 2023-02-03 se en place de l'outil numériq knowledge learning ant Selection ntation ue de gestion de flux des info rmations, du SAP et de l'annu aire digital. Page 13 18 MONTHS PROCUREMENT PLAN Project information: P166570 - Uganda: Project Implementation agency: Ministry of Education and Sports Date of the Procurement Plan: March 2020 Period covered by this Procurement Plan: 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: Paragraph 5.3 of the Procurement Regulations will not apply. When approaching the national market, the country’s own procurement procedures shall not be used due to restrictions on eligibility of otherwise eligible firms to participate in NCB. The Procurement Regulations shall apply. However, the Borrower may use its own procurement arrangements as set forth in the Public Procurement and Disposal Act, 2003 for Request for Quotation such arrangements shall be subject to permitting universal eligibility and paragraph 5.4 of the Procurement Regulations and the following conditions: In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods : Applicable for those contracts identified in the Procurement Plan tables Works: applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information:- (a). Prior Procurement Arrangements: The Procurement Arrangements as indicated in the below table and within the thresholds indicated in the below tables will be used. The thresholds for the Bank’s prior review requirements are also provided in the table below: Table: Thresholds*, Procurement Arrangements, and Prior Review (The table below depicts the Thresholds and Procurement Methods to be used under the IWMDP ): Thresholds for Procurement Methods Contract (C) Expenditure Value No Procurement Method Category Threshold* [eq. USD] Open Competition International C ≥ 10,000,000 Market Approach Open Competition National Market 200,000 < C < 1 Works Approach 10,000,000 C ≤ 200,000 RfQ Open Competition International C ≥ 2,000,000 Goods, IT and Market Approach non- 2 Open Competition National Market consulting 100,000 < C < Approach services 2,000,000 C ≤ 100,000 RfQ selection of Open Competition International 3 consultant C < 300,000 Market Approach firms Selection of Individual Consultant Selection Any value 4 Individual through open competition, limited consultants competition and Direct Selection Direct Any category and 5 Selection Subject to justification value Contract (C) Expenditure Value No Procurement Method Category Threshold* [eq. USD] Training, Workshops, Based on approved Annual Work 6 All Values Study Tours Plan & Budgets (AWPB) by TTL * All contracts not subject to prior review will be post-reviewed. ** Short lists of consultants for services estimated to cost less US$300,000 equivalent per contract may be composed entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. However, if foreign firms have expressed interest, they will not be excluded from consideration. Prior review Thresholds High Substantial Procurement Type Risk Risk Works 5.0 10.0 Goods, It & Non-Consulting 1.5 2.0 Services Consultants (Firms) 0.5 1.0 Individual Consultants 0.2 0.3 Prequalification. Not expected for any works or goods packages in the procurement plan. Proposed Procedures for CDD Components: Not Applicable Reference to (if any) Project Operational/Procurement Manual: the IWMDP team will prepare a Procurement manuals, which will also be part of the Project Implementation Manual. Any Other Special Procurement Arrangements: None Procurement Packages/PLAN with Procurement Arrangements and Time Schedule: as per the Table below: Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Uganda : Uganda Secondary Education Expansion Project PLAN General Information Country: Uganda 2020-12-15 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166570 GPN Date: 2020-12-03 Project Name: Uganda Secondary Education Expansion Project Loan / Credit No: IDA / D7010, IDA / 67540 Ministry of Education and Sports Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MOES-329208-CW-RFB / Construction of 10 new secon Request for B dary schools in 4 lots; Lot 1: ids - Small W Nkungu SS & Rugando SS, Lo Expansion of Lower Seconda Single Stage - One E Under Imple 2024-06-1 IDA / D7010 Prior Request for Bids Open - National orks SPD (1 e 0.00 2022-12-20 2022-12-30 2023-02-10 2023-03-12 2023-04-16 t 2:Buluguyi SS & St. Andrew ry Education nvelope mentation 4 nvelope proc SS, Lot 3:Kanseera SS, Nabis ess) weera SS & Alangi SS and Lot 4: Katenga SS, Mugombwa S S & Nyamwamba SS GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MOES-226166-GO-RFB / Procurement of 1300 Laptop Improving Teachers Support Open - Internationa Single Stage - One E s and 1300 Projectors for Sci IDA / D7010 and Strategy Development Post Request for Bids 0.00 Canceled 2021-06-21 2021-06-26 2021-08-07 2021-09-06 2021-10-11 2022-04-09 l nvelope ence Teachers to be Trained Nationally from 1300 Government Scho ols UG-MOES-312191-GO-RFQ / Project Management, Monito Request for Quota Single Stage - One E Under Imple Procurement of Office Station IDA / 67540 Post Limited 0.00 2022-09-06 2022-11-01 2023-04-30 ring and Evaluation tions nvelope mentation ery for 18 months for USEEP PCU UG-MOES-312204-GO-RFQ / Supply and delivery of Photo copier A3 Heavy Duty-Colore Project Management, Monito Request for Quota Single Stage - One E Pending Impl d 1No., Laptops 20No., Projec IDA / 67540 Post Limited 0.00 2022-09-28 2022-11-23 2023-05-22 ring and Evaluation tions nvelope ementation tors 2No., Video conferencing equipment 1No., Digital Cam era 1No., Photocopier A3 Hea vy Duty 1No. for USEEP PCU UG-MOES-312206-GO-RFQ / Supply and delivery of one E xecutive Conference Table, 2 0 Conference Chairs, 12 Orth Project Management, Monito Request for Quota Single Stage - One E Pending Impl opedic Office Chairs, 2 execu IDA / 67540 Post Limited 0.00 2022-09-30 2022-11-25 2023-05-24 ring and Evaluation tions nvelope ementation tive round meeting tables, 12 Office Desks, 1 Reception De sk, 1 reception Chair, two 2-s eater work stations, 20 Filing Cabinets and 1 Credenza UG-MOES-320354-GO-RFQ / Supply and Delivery of 400 3 -seater desks, 20 Teachers' C Hosting Community and Ref Request for Quota Single Stage - One E Pending Impl IDA / D7010 Post Limited 0.00 2022-11-16 2023-01-11 2023-07-10 hairs, 20 Teachers' Tables, 2 ugee Education Support tions nvelope ementation 0 Shelves & 20 Black boards for learners and teachers in 5 AEP centers (2 classes per le vel) UG-MOES-339842-GO-RFB / Expansion of Lower Seconda Single Stage - One E Under Imple Procurement of 12 Motor Veh IDA / D7010 Post Request for Bids Open - National 0.00 2023-02-06 2023-04-25 2023-02-11 2023-05-26 2023-03-25 2023-04-24 2023-05-29 2023-11-25 ry Education nvelope mentation icles for USEEP Project UG-MOES-363289-GO-RFB / Supply and delivery of 3,300 Laptops with software license Improving Teachers Support , 100 Multipurpose printers, 1 Open - Internationa Single Stage - One E Under Revie IDA / D7010 and Strategy Development Prior Request for Bids 0.00 2023-05-29 2023-06-03 2023-07-15 2023-08-14 2023-09-18 2024-03-16 ,400 projectors and network l nvelope w Nationally equipment for 100 cluster ce nters and science teachers to be trained from 1,300 Gover nment schools, separated int o 2 lots. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MOES-206978-NC-DIR / Project Management, Monito IDA / D7010 Post Direct Selection Direct 0.00 Canceled 2021-02-19 2021-03-12 2021-04-30 2021-10-27 Hire of Office Space for PCU f ring and Evaluation or 5 years UG-MOES-296534-NC-RFQ / Project Management, Monito Request for Quota Single Stage - One E Under Imple Hire of Office Space for USEE IDA / 67540 Post Limited 0.00 2022-06-11 2022-08-06 2023-02-02 ring and Evaluation tions nvelope mentation P Project Coordination Unit fo r two years UG-MOES-323141-NC-RFB / Procurement of firms to dev Hosting Community and Ref Single Stage - One E Under Imple elop, design and produce ma IDA / D7010 Post Request for Bids Open - National 0.00 2022-10-28 2022-10-27 2022-11-02 2023-05-26 2022-12-14 2023-01-13 2023-02-17 2023-08-16 ugee Education Support nvelope mentation terials into digitalized adapta ble materials for specials nee ds students UG-MOES-312210-NC-RFP / Procurement of a firm to dev Hosting Community and Ref Single Stage - One E elop, design and produce ma IDA / D7010 Post Request for Bids Open - National 0.00 Canceled 2022-09-06 2022-09-11 2022-10-23 2022-11-22 2022-12-27 2023-06-25 ugee Education Support nvelope terials into digitalized adapta ble materials for specials nee ds students UG-MOES-320333-NC-RFP / Procurement of service provi ders to implement Accelerate Hosting Community and Ref Single Stage - One E d Education Programme (AEP IDA / D7010 Post Request for Bids Open - National 0.00 Canceled 2022-10-31 2022-11-10 2022-11-05 2022-12-17 2023-01-16 2023-02-20 2025-09-10 ugee Education Support nvelope ) in 5 Centers in 2 lots - Lot 1 : Yumbe, Obongi and Terego Districts and Lot 2: Isingiro a nd Lamwo Districts Page 1 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MOES-226172-CS-CQS / Improving Teachers Support Consultancy services (firm) f Consultant Qualifi Under Implement IDA / D7010 and Strategy Development Post Limited 0.00 2021-06-14 2022-09-26 2021-06-28 2021-07-28 2021-09-01 2022-02-28 or the development of the Na cation Selection ation Nationally tional Teacher Retention Stra tegy UG-MOES-206733-CS-QCBS / Project Management, Monito Consultant Qualifi Consultancy for independent IDA / D7010 Post Limited 0.00 Canceled 2020-12-16 2021-11-18 2020-12-30 2021-01-29 2021-03-05 2021-09-01 ring and Evaluation cation Selection verification of project results (DLI) UG-MOES-226170-CS-CQS / Consultancy services to Cond uct Baseline studies under th Improving Teachers Support Consultant Qualifi e refugee host communities ( IDA / D7010 and Strategy Development Post Limited 0.00 Canceled 2021-06-07 2021-06-21 2021-07-21 2021-08-25 2022-02-21 cation Selection Baseline, Mid and end time t Nationally o determine the number of r efugees and their needs (Soc ial support, AEP, Learning aid s) UG-MOES-257846-CS-CQS / Consultancy services to deve Hosting Community and Ref Consultant Qualifi lop, design and produce mat IDA / D7010 Post Limited 0.00 Canceled 2022-04-24 2022-05-08 2022-06-07 2022-07-12 2023-01-08 ugee Education Support cation Selection erials into digitalized adapta ble materials for specials nee ds students UG-MOES-296544-CS-CQS / Consulting services to undet Project Management, Monito Consultant Qualifi ake Independent Verification IDA / 67540 Post Limited 0.00 Canceled 2021-11-25 2021-12-09 2022-01-08 2022-02-12 2022-08-11 ring and Evaluation cation Selection of Project Results under the Uganda Secondary Education Expansion Project (USEEP) UG-MOES-312180-CS-QCBS / Consultancy services for inde Project Management, Monito Quality And Cost- pendent verification of projec IDA / D7010 Prior Open - National 0.00 Canceled 2022-08-29 2022-09-18 2022-10-16 2022-10-30 2022-11-20 2022-12-25 2023-01-16 2025-01-15 ring and Evaluation Based Selection t results (DLI) for the Uganda Teacher and School Effective ness Project (USEEP) UG-MOES-316931-CS-QCBS / Consultancy services for inde Project Management, Monito Quality And Cost- Under Implement pendent verification of projec IDA / D7010 Prior Open - National 0.00 2022-09-25 2022-11-01 2022-10-15 2022-11-17 2022-11-12 2023-02-21 2022-11-26 2023-03-21 2022-12-17 2023-05-30 2023-01-21 2023-02-12 2025-02-11 ring and Evaluation Based Selection ation t results (DLI) under the Uga nda Secondary Education Ex pansion Project (USEEP) UG-MOES-320328-CS-CQS / Improving Teachers Support Consultancy services (firm) f Consultant Qualifi Under Implement IDA / D7010 and Strategy Development Post Limited 0.00 2022-10-31 2022-11-17 2022-11-14 2022-12-14 2023-01-18 2023-07-17 or the development of the Na cation Selection ation Nationally tional School Construction St rategy UG-MOES-226173-CS-CQS / Improving Teachers Support Consultancy services (firm) f Consultant Qualifi IDA / D7010 and Strategy Development Post Limited 0.00 Canceled 2021-06-14 2021-11-30 2021-06-28 2021-07-28 2021-09-01 2022-02-28 or the development of the Na cation Selection Nationally tional School Construction St rategy UG-MOES-333711-CS-QCBS / Procurement of NGOs to und ertake Violence Against Child ren (VAC) survey and various Expansion of Lower Seconda Quality And Cost- Open - Internationa Under Implement activities to deliver safe scho IDA / D7010 Prior 0.00 2022-12-29 2023-01-19 2023-03-04 2023-04-01 2023-05-01 2023-06-05 2023-07-10 2024-07-09 ry Education Based Selection l ation ols in 326 secondary schools divided into 5 lots; Lot 1:68 s chools, Lot 2:64 schools, Lot 3: 93 schools, Lot 4: 93 scho ols, Lot 5: 7 schools UG-MOES-359642-CS-QCBS / Procurement of NGOs to und ertake Violence Against Child ren (VAC) survey and various Expansion of Lower Seconda Quality And Cost- Open - Internationa Under Implement IDA / D7010 Post 0.00 2023-05-11 2023-06-01 2023-07-15 2023-08-12 2023-09-11 2023-10-16 2023-11-20 2024-11-19 activities to deliver safe scho ry Education Based Selection l ation ols under Lot 1 in 68 schools located 39 districts in East C entral, Elgon, Teso, Lango an d Acholi sub regions UG-MOES-359694-CS-QCBS / Procurement of NGOs to und ertake Violence Against Child Expansion of Lower Seconda Quality And Cost- Open - Internationa Under Implement ren (VAC) survey and various IDA / D7010 Post 0.00 2023-05-05 2023-05-26 2023-07-09 2023-08-06 2023-09-05 2023-10-10 2023-11-14 2024-11-13 ry Education Based Selection l ation activities to deliver safe scho ols under Lot 2 in 64 schools located in 26 districts in Sout h Western and Central region s UG-MOES-359684-CS-QCBS / Procurement of NGOs to und ertake Violence Against Child Expansion of Lower Seconda Quality And Cost- Open - Internationa Under Implement ren (VAC) survey and various IDA / D7010 Post 0.00 2023-05-11 2023-06-01 2023-07-15 2023-08-12 2023-09-11 2023-10-16 2023-11-20 2024-11-19 ry Education Based Selection l ation activities to deliver safe scho ols under Lot 3 in 93 schools located in 16 Districts in Wes tern region UG-MOES-359675-CS-QCBS / Procurement of NGOs to und ertake Violence Against Child Expansion of Lower Seconda Quality And Cost- Open - Internationa Under Implement ren (VAC) survey and various IDA / D7010 Post 0.00 2023-05-11 2023-06-01 2023-07-15 2023-08-12 2023-09-11 2023-10-16 2023-11-20 2024-11-19 ry Education Based Selection l ation activities to deliver safe scho ols under Lot 4 in 93 schools located in 11 Districts in Wes t Nile sub region UG-MOES-359658-CS-CQS / Procurement of NGOs to und ertake Violence Against Child Expansion of Lower Seconda Consultant Qualifi Under Implement IDA / D7010 Post Limited 0.00 2023-05-11 2023-05-25 2023-06-24 2023-07-29 2024-01-25 ren (VAC) survey and various ry Education cation Selection ation activities to deliver safe scho ols in 7 schools in 5 Districts i n Karamoja sub region UG-MOES-360180-CS-CQS / Improving Teachers Support Procurement of a firm to pre Consultant Qualifi IDA / D7010 and Strategy Development Post Limited 0.00 Under Review 2023-05-12 2023-05-26 2023-06-25 2023-07-30 2024-01-26 pare a background paper on cation Selection Nationally the Private Education and Tr aining Policy Page 2 UG-MOES-359582-CS-QCBS / Procurement of service provi ders to implement Accelerate d Education Programme (AEP Hosting Community and Ref Quality And Cost- Open - Internationa Under Implement ) in 5 Centres: Lot 1: Yumbe - IDA / D7010 Prior 0.00 2023-05-26 2023-06-16 2023-07-30 2023-08-27 2023-09-26 2023-10-31 2023-12-05 2025-12-04 ugee Education Support Based Selection l ation Yoyo Secondary School, Obo ngi -Itula SSS and Terego-Im vepi SSS & Lot 2: Isingiro-Na kivale Secondary School and Lamwo- Palabek secondary S chool UG-MOES-366089-CS-QCBS / Consultancy services for desi gn review, approval and doc Expansion of Lower Seconda Quality And Cost- Under Implement IDA / D7010 Prior Open - National 0.00 2023-06-15 2023-07-06 2023-08-19 2023-09-16 2023-10-16 2023-11-20 2023-12-25 2024-12-24 umentation for schools to be ry Education Based Selection ation constructed under Uganda S econdary Education Expansio n Project INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MOES-209515-CS-INDV / Recruitment of a secondary E Project Management, Monito Individual Consult Under Implement IDA / D7010 Prior Open 0.00 2021-02-19 2022-06-05 2021-04-09 2021-04-30 2021-06-04 2022-12-04 ducation Specialist under US ring and Evaluation ant Selection ation EEIP for 2 years UG-MOES-209502-CS-INDV / Project Management, Monito Individual Consult Under Implement Recruitment of a Monitoring IDA / D7010 Prior Open 0.00 2021-02-19 2022-03-15 2021-04-09 2021-04-30 2021-06-04 2022-12-04 ring and Evaluation ant Selection ation and Evaluation Specialist for 2 years UG-MOES-209509-CS-INDV / Project Management, Monito Individual Consult Under Implement Recruitment of a communica IDA / D7010 Prior Open 0.00 2021-02-19 2022-04-29 2021-04-09 2021-04-30 2021-06-04 2022-12-04 ring and Evaluation ant Selection ation tion specialist under USEEIP f or 2 years UG-MOES-209512-CS-INDV / Project Management, Monito Individual Consult Recruitment of five (5) Projec IDA / D7010 Prior Open 0.00 Canceled 2021-03-24 2022-04-24 2021-05-12 2021-06-02 2021-07-07 2023-01-06 ring and Evaluation ant Selection t Engineers under USEEIP for two years UG-MOES-226161-CS-INDV / Project Management, Monito Individual Consult Under Implement Recruitment of 60 Clerks of IDA / D7010 Prior Open 0.00 2021-06-14 2022-04-25 2021-08-02 2021-08-23 2021-09-27 2022-03-26 ring and Evaluation ant Selection ation Works to oversee 60 sites UG-MOES-209480-CS-CDS / Recruitment of Ms. Jane Fran Project Management, Monito IDA / D7010 Post Direct Selection Direct 0.00 Canceled 2021-03-24 2021-04-03 2021-06-07 2022-12-07 ces Nansamba as Deputy Pro ring and Evaluation ject Coordinator for USEEP fo r 2 years UG-MOES-290579-CS-INDV / Recruitment of a Deputy Proj Project Management, Monito Individual Consult Under Implement IDA / 67540 Post Open 0.00 2022-04-24 2022-06-12 2022-07-03 2022-08-07 2024-07-27 ect Coordinator under USEEP ring and Evaluation ant Selection ation for a period of 2 years UG-MOES-259645-CS-CDS / Procurement of NGOs to impl Hosting Community and Ref IDA / D7010 Prior Direct Selection Direct 0.00 Canceled 2022-04-24 2022-05-04 2022-07-08 2023-01-04 ement Accelerated Education ugee Education Support Program (AEP) in 12 centers UG-MOES-209525-CS-INDV / Recruitment of an Environme Project Management, Monito Individual Consult IDA / D7010 Prior Open 0.00 Canceled 2021-02-19 2022-05-02 2021-04-09 2021-04-30 2021-06-04 2022-12-04 ntal Safe Guard specialist for ring and Evaluation ant Selection 2 years under USEEIP UG-MOES-296513-CS-CDS / Recruitment of Mr. Alex Winy Project Management, Monito IDA / 67540 Post Direct Selection Direct 0.00 Canceled 2022-05-29 2022-06-08 2022-08-12 2023-02-08 i Kiiza as Environmental Safe ring and Evaluation guards Specialist under USEE P for two years UG-MOES-209484-CS-CDS / Recruitment of Ms. Irene Aol Project Management, Monito IDA / D7010 Prior Direct Selection Direct 0.00 Canceled 2021-03-24 2022-03-21 2021-04-03 2021-06-07 2022-12-07 Pollicky Procurement Speciali ring and Evaluation st under USEEIP for 2 years UG-MOES-304345-CS-INDV / Recruitment of an Environme Project Management, Monito Individual Consult Under Implement IDA / D7010 Post Open - National 0.00 2022-08-05 2022-09-23 2022-10-07 2022-11-04 2024-11-03 ntal Safeguards Specialist un ring and Evaluation ant Selection ation der USEEP for 2 years UG-MOES-304362-CS-INDV / Project Management, Monito Individual Consult Under Implement Recruitment of a Procuremen IDA / D7010 Post Open - National 0.00 2022-08-05 2022-09-23 2022-10-07 2022-11-04 2024-11-03 ring and Evaluation ant Selection ation t Specialist under USEEP for 2 years UG-MOES-312212-CS-INDV / Procurement of 2 Environme ntal Safeguards Assistants to Expansion of Lower Seconda Individual Consult Under Implement IDA / D7010 Post Open - National 0.00 2022-09-06 2023-04-12 2022-10-25 2022-11-15 2022-12-20 2023-06-18 support the consultant on En ry Education ant Selection ation vironmental management du ring construction of schools f or 2 years UG-MOES-312217-CS-CDS / Procurement of 2 short term Expansion of Lower Seconda Under Implement Social safeguards consultant IDA / D7010 Post Direct Selection Direct - National 0.00 2022-09-06 2022-09-26 2022-09-16 2022-11-20 2023-05-19 ry Education ation s to prepare Project Briefs for Phase 2 & 3 sites covering 11 7 schools UG-MOES-312764-CS-CDS / Procurement of 2 short term Expansion of Lower Seconda Under Implement Environmental safeguards co IDA / D7010 Post Direct Selection Direct - National 0.00 2022-09-06 2022-09-26 2022-09-16 2022-11-20 2023-05-19 ry Education ation nsultants to prepare Project Briefs for Phase 2 & 3 sites c overing 117 schools UG-MOES-312769-CS-INDV / Procurement of 2 Social Safe Expansion of Lower Seconda Individual Consult Under Implement guards Assistants to support IDA / D7010 Post Open - National 0.00 2022-09-06 2023-04-12 2022-10-25 2022-11-15 2022-12-20 2023-06-18 ry Education ant Selection ation the consultant on social risk management during construc tion of schools for 2 years UG-MOES-226175-CS-INDV / Improving Teachers Support Individual consultancy Servi Individual Consult IDA / D7010 and Strategy Development Post Limited 0.00 Canceled 2021-06-14 2021-06-19 2021-07-10 2021-08-14 2022-02-10 ces to support the developm ant Selection Nationally ent of Private Education prov ision Policy Page 3 UG-MOES-226177-CS-INDV / Improving Teachers Support Procure individual consultant Individual Consult IDA / D7010 and Strategy Development Post Limited 0.00 Canceled 2021-06-14 2021-06-19 2021-07-10 2021-08-14 2022-02-10 s for the development of the ant Selection Nationally Universal Secondary Educati on Policy UG-MOES-351358-CS-INDV / Project Management, Monito Individual Consult Under Implement Recruitment of nine (9) Proje IDA / D7010 Prior Open - National 0.00 2022-04-24 2022-12-05 2022-12-26 2023-04-25 2025-04-24 ring and Evaluation ant Selection ation ct Engineers under USEEP for two years UG-MOES-209512-CS-INDV-2 Project Management, Monito Individual Consult Pending Impleme / Recruitment of 2 Project En IDA / D7010 Post Open - National 0.00 2023-06-26 2023-08-14 2023-09-04 2023-10-09 2025-04-09 ring and Evaluation ant Selection ntation gineers under USEEP for 24 months UG-MOES-367728-CS-INDV / Project Management, Monito Individual Consult Pending Impleme Recruitment of an Architect u IDA / D7010 Post Open - National 0.00 2023-06-23 2023-08-11 2023-09-01 2023-10-06 2025-04-06 ring and Evaluation ant Selection ntation nder USEEP for 24 months UG-MOES-209519-CS-INDV / Project Management, Monito Individual Consult Recruitment of a Social Devel IDA / D7010 Post Open 0.00 Canceled 2021-02-19 2022-03-17 2021-04-09 2021-04-30 2021-06-04 2022-12-04 ring and Evaluation ant Selection opment Specialist for 2 years under USEEIP UG-MOES-209519-CS-INDV-2 / Recruitment of a Social Dev Project Management, Monito Individual Consult IDA / D7010 Post Open - National 0.00 Under Review 2023-06-23 2023-08-11 2023-09-01 2023-10-06 2025-06-30 elopment Development Speci ring and Evaluation ant Selection alist under USEEP for 24 mon ths UG-MOES-209515-CS-INDV-2 / Recruitment of a Secondary Project Management, Monito Individual Consult IDA / D7010 Post Open - National 0.00 Under Review 2023-06-23 2023-08-11 2023-09-01 2023-10-06 2025-04-06 Education Specialist under U ring and Evaluation ant Selection SEEP for 24 months Page 4 TEXTUAL PART OF THE PROCUREMENT PLAN Turkey Climate Smart and Competitive Project information: Agricultural Growth Project (TUCSAP) (P175011) Project Implementation Ministry of Agriculture and Forestry Agency: Date of the Procurement February 7, 2022 Plan: Period covered by this February 7, 2022 – August 7, 2023 Procurement Plan: I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. Any procurement activity under the Project shall not be initiated before it is approved by the Bank through STEP. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Project Implementing Agency will select in STEP if the relevant procurement activity’s cost estimate will be published or not in the external web-site of the World Bank. II. Goods, Works and Non-Consulting Services Prior Review Procurement Threshold Procurement Method Method Threshold (at or above the threshold) RFB/Open International No procurement Works US$10,000,000 method threshold Contracts valued less RFB/Open National than US$10,000,000 Works US$ 30,000,000 RFB/Open International Goods, Information No procurement Technology and Non- US$2,000,000 method threshold consulting Services RFB/Open National Goods, Information Contracts valued less Technology and Non- No prior review than US$ 2,000,000 consulting Services 1 / 26 Contracts less than RFQ-Works No prior review US$200,000 RFQ-Goods, Information Contracts less than Technology /Non- No prior review US$100,000 consulting Services III. Selection of Consultants Prior Review Selection Method Threshold Selection Method Threshold (at or above the threshold) Quality and Cost Based No selection method US$1,000,000 Selection (QCBS) threshold Selection Based on Contracts valued less than Consultants Qualification No prior review $300,000 (CQS) Individual Consultants No selection method US$300,000 (INDV) threshold The terms of references of any financial management, audit, procurement or legal consultants financed by the project shall be sent to the Bank for its comments. IV. Special Arrangements 1. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. For the procurements not subject to international competitive selection the procurement documents agreed by the Bank shall be used. When approaching the national market, bidding documents accepted by the World Bank shall be used. 2. Advance Procurement: Advance procurement will be considered under the project, subject to the conditions defined in paragraph 5.1 of the Procurement Regulations for Borrowers. 3. Review Procedure: The procurements under the project are subject to the Bank’s prior review as stipulated in above Paragraphs II and III and also as specified in the procurement schedule given below in Section V, and in STEP. 4. Procurement of Second-Hand Goods: Not Applicable. 5. Domestic preference (as specified under paragraph 5.51 of the Procurement Regulations): Not applicable. 6. Operational costs will not be considered under World Bank procurement implementation. V. Procurement Packages with Methods and Time Schedule The estimated costs in the attached tables (sheets) (including VAT) 2 / 26 3 / 26 Estimate Signed d Contra Procurement Estimated Revie procurem Contract Activity Reference No. / Market ct Reference No Selection Amount w ent Completion Description: Approach (Plann Method (US$) Metho Notice/ (Planned Date) ed d Invitatio Date) n Date Subcomponent 1.1: Narrowing information gaps to enhance soil health and land-use planning/management Non-Consulting Services Group I Soil Surveys and Classification; Laboratory Analysis; Production of digital detailed soil maps (1:5000) Request for Bids NCS.TRGM.CS1.1 - Open - 8,486,000 1 (Kırklareli, Edirne, Çanakkale, (RFB) Small Prior May.22 Jul.22 Jan.24 01 National Tekirdağ, Balıkesir, Bursa Aydın, Works İzmir, Manisa & Yalova) (Multiple Contracts - tbd) (Average Lot size would be about 1.9 M USD) Group II Soil Surveys and Classification; Laboratory Analysis; Production of digital detailed soil maps (1:5000) Request for Bids (Afyonkarahisar, Antalya, Bilecik, NCS.TRGM.CS1.1 - Open - 2 (RFB) Small 8,587,000 Post Jan.23 Mar.23 Sep.24 Burdur, Denizli, Eskişehir, Isparta, 02 National Works Kocaeli, Kütahya, Muğla, Sakarya & Usak) (Multiple Contracts - tbd) (Average Lot size would be about 1.7 M USD) Group III Soil Surveys and Classification; Laboratory Analysis; Production of digital detailed soil maps (1:5000) Request for Bids NCS.TRGM.CS1.1 - Open - 3 (Ankara, Bartın, Bolu, Düzce İstanbul, (RFB) Small 9,300,000 Post Jan.24 Mar.24 Sep.25 03 National Karabük, Karaman, Konya, Mersin & Works Zonguldak) (Multiple Contracts - tbd) (Average Lot Size would be about 2.3 M USD) Group IV Soil Surveys and Classification; Laboratory Analysis; Production of digital detailed soil maps (1:5000) (Aksaray, Çankırı, Request for Bids NCS.TRGM.CS1.1 - Open - 4 Çorum, Kastamonu, Kırıkkale (RFB) Small 7,541,000 Post Nov.24 Jan.25 Jul.26 04 National Kırşehir, Nevşehir, Niğde, Sinop & Works Yozgat)(Multiple Contracts - tbd) (Average Lot size would be about 1.7 M USD) 4 / 26 Group V Soil Surveys and Classification; Laboratory Analysis; Production of digital detailed soil maps (1:5000) Request for Bids NCS.TRGM.CS1.1 - Open - 5 (Adana, Adıyaman, Gaziantep, (RFB) Small 8,174,000 Post May.25 Jul.25 Jan.27 05 National Hatay, Kahramanmaraş, Kayseri, Works Malatya, Kilis, Osmaniye & Sivas) (Multiple Contracts - tbd) (Average Lot Size would be about 2.2 M USD) Group VI Soil Surveys and Classification; Laboratory Analysis; Production of digital detailed soil maps (1:5000) Request for Bids NCS.TRGM.CS1.1 - Open - 6 (Amasya, Artvin, Bayburt, Giresun, (RFB) Small 4,207,000 Post Nov.25 Jan.26 Jul.27 06 National Gümüşhane, Ordu, Rize, Samsun, Works Tokat & Trabzon) (Multiple Contracts - tbd) (Average Lot Size would be about 1.3 M USD) Group VII Soil Surveys and Classification; Laboratory Analysis; Production of digital detailed soil maps (1:5000) Request for Bids NCS.TRGM.CS1.1 - Open - 7 (Batman, Bingöl, Diyarbakır, Elazığ, (RFB) Small 9,089,000 Post Apr.26 Jun.26 Dec.27 07 National Erzincan, Erzurum, Mardin, Muş, Works Şanlıurfa & Tunceli)(Multiple Contracts - tbd) (Average Lot Size would be about 2.3 M USD) Group VIII Soil Surveys and Classification; Laboratory Analysis; Production of digital detailed soil Request for Bids maps (1:5000) NCS.TRGM.CS1.1 - Open - 8 (RFB) Small 3,696,000 Post May.26 Jul.26 Jan.28 (Ağrı, Ardahan, Bitlis, Hakkari, Iğdır, 08 National Works Kars, Siirt, Şırnak & Van) (Multiple Contracts - tbd) (Average Lot size would be about 1.6 M USD) Logistical & Organizational Services NCS.TRGM.CS1.1 - Limited - Request for 9 for workshops, seminars and etc. 200,000 Post TBD TBD TBD 09 National Quotations (RFB) (Multiple contracts) 5 / 26 Subtotal Non-Consulting Services 59,280,000 Consulting Services Group I Preparing Plans/Notes and Open - Quality and Cost- Land Classification (Kırklareli, Edirne, 1 CS.TRGM.CS1.1-01 Internation based Selection 9,107,000 Prior Sep.22 May.23 May.25 Çanakkale, Tekirdağ, Balıkesir, Bursa al (QCBS) Aydın, İzmir, Manisa & Yalova) Group II Preparing Plans/Notes and Land Classification (Afyonkarahisar, Open - Quality and Cost- 2 Antalya, Bilecik, Burdur, Denizli, CS.TRGM.CS1.1-02 Internation based Selection 12,210,000 Prior Mar.23 Nov.23 Nov.25 Eskişehir, Isparta, Kocaeli, Kütahya, al (QCBS) Muğla, Sakarya & Usak) Group III Preparing Plans/Notes and Land Classification (Ankara, Bartın, Open - Quality and Cost- 3 Bolu, Düzce, İstanbul, Karabük, CS.TRGM.CS1.1-03 Internation based Selection 12,088,000 Prior Sep.23 May.24 May.26 Karaman, Konya, Mersin & al (QCBS) Zonguldak) Group IV Preparing Plans/Notes and Land Classification (Aksaray, Çankırı, Open - Quality and Cost- 4 Çorum, Kastamonu, Kırıkkale CS.TRGM.CS1.1-04 Internation based Selection 8,659,000 Prior Mar.24 Nov.24 Nov.26 Kırşehir, Nevşehir, Niğde, Sinop & al (QCBS) Yozgat) Group V Preparing Plans/Notes and Land Classification (Adana, Open - Quality and Cost- 5 Adıyaman, Gaziantep, Hatay, CS.TRGM.CS1.1-05 Internation based Selection 11,409,000 Prior Sep.24 May.25 May.27 Kahramanmaraş, Kayseri, Malatya, al (QCBS) Kilis, Osmaniye & Sivas) Group VI Preparing Plans/Notes and Open - Quality and Cost- Land Classification (Amasya, Artvin, 6 CS.TRGM.CS1.1-06 Internation based Selection 6,675,000 Prior Mar.25 Nov.25 Nov.27 Bayburt, Giresun, Gümüşhane, Ordu, al (QCBS) Rize, Samsun, Tokat & Trabzon) Group VII Preparing Plans/Notes and Land Classification (Batman, Bingöl, Open - Quality and Cost- 7 Diyarbakır, Elazığ, Erzincan, CS.TRGM.CS1.1-07 Internation based Selection 12,289,000 Prior Aug.25 Apr.26 Apr.28 Erzurum, Mardin, Muş, Şanlıurfa & al (QCBS) Tunceli) 6 / 26 Group VIII Preparing Plans/Notes and Open - Quality and Cost- Land Classification (Ağrı, Ardahan, 8 CS.TRGM.CS1.1-08 Internation based Selection 8,282,000 Prior Aug.25 Apr.26 Apr.28 Bitlis, Hakkari, Iğdır, Kars, Siirt, al (QCBS) Şırnak & Van) Consultant’s Training on modelling, mapping, Open - Qualification- 9 CS.TRGM.CS1.1-09 300,000 Post May.22 Aug.22 Apr.28 harmonization and etc. national based Selection (CQS) Recruitment of a Consulting Firm for conducting survey/s, feasibility Consultant’s studies; Preparation of detailed Open - Qualification- 10 designs and Bidding Documents CS.TRGM.CS1.1-10 200,000 Post May.22 Aug.22 Mar.23 National based Selection including technical (CQS) specifications/BoQs for the National Soil Archive Facility Open – Individual Development/Strengthening of Data National/ 11 CS.TRGM.CS1.1-11 Consultants 20,000 Post Jun.22 Jul.22 Dec.22 Sharing and Use Policy Internation (INDV) al 81,239,000 Subtotal Consulting Services Goods Procurement of Information Systems for Identification of a soil monitoring sites and Establishment of National Soil Monitoring Sub-system for selected indicators; National Soil Request for Bids Profile Database, Dynamic 1,850,000 (GO.TRGM.CS1.1- Open - (RFB) 1 Modelling/Mapping System; Soil-land Prior Jan.23 Apr.23 Apr.28 01) National (Information SDI and National Soil Land System) Information System and Decision Support System (DSS) -the Pilot Applications Production of soil property and thematic maps; Subtotal Goods 1,850,000 Works Request for Bids Construction Works for the National Open - 1 W.TRGM.CS1.1-01 (RFB) Small 1,220 Post Apr.23 Jun.23 Dec.25 Soil Archive Facility National Works Subtotal Works 1,220,000 7 / 26 Estimated Estimate procurem Signed Contract Market Procurement d Review ent Contract Completion Activity Description: Reference No Approach Selection Method Amount Method Notice/ (Planned (Planned (US$) Invitation Date) Date) Date Subcomponent 2.1: Strengthening the capacity of animal health institutes Works Group 1- Design, Supply and Installation of BSL 2 and BSL 3 Request for Bids 3,813,000 Labs in Adana VCI Plant Open - (Design, Supply and W.GKGM.CS2.1-01 Post Mar.23 May.23 Nov.25 National Installation Single Group 2- Design, Supply and Stage without Installation of BSL 2 and BSL 3 3,813,000 Prequalification) Labs in Konya VCI 7,625,00 Subtotal 1st Bid 0 Group 1- Design, Supply and Installation of BSL 2 and BSL 3 3,813,000 Labs in Elazig VCI Request for Bids Plant Group 2- Design, Supply and Open - (Design, Supply and Installation of BSL 2 and BSL 3 W.GKGM.CS2.1-02 4,313,000 Prior May.23 Jul.23 Jan.26 National Installation Single Labs in Erzurum VCI Stage without Prequalification) Group 3- Design, Supply and Installation of BSL 2 and BSL 3 3,813,000 Labs in Samsun VCI 11,938,0 Subtotal 2nd Bid 00 Group 1 - Design, Supply and Request for Bids Installation of BSL 2 and BSL 3 Plant 3,813,000 Labs in Istanbul Pendik VCI Open - (Design, Supply and W.GKGM.CS2.1-03 Post Aug.23 Oct.23 Apr.26 National Installation Single Group 2 - Design, Supply and Stage without Installation of BSL 2 and BSL 3 Prequalification) 3,813,000 Labs in Izmir Bornova VCI 7,625,00 Subtotal 3rd Bid 0 8 / 26 27,188,0 Subtotal Works 00 Consulting Services Consultancy Services for conducting the Preparatory Consultant’s Studies, Design Review & Open - CS.GKGM.CS2.1-01 Qualification-based 300,000 Post July.22 Sep.22 Dec.25 Supervision of Design, Supply National Selection (CQS) & Installation (DSI) Contract of Adana and Konya VCIs. Consultancy Services for conducting the Preparatory Studies, Design Review & Consultant’s Open - Supervision of Design, Supply CS.GKGM.CS2.1-02 Qualification-based 300,000 Post Sep.22 Nov.22 Feb.26 National & Installation (DSI) Contract Selection (CQS) of Erzurum, Elazig and Samsun VCIs Consultancy Services for conducting the Preparatory Consultant’s Studies, Design Review & Open - CS.GKGM.CS2.1-03 Qualification-based 300,000 Post Dec.22 Feb.23 May.26 Supervision of Design, Supply National Selection (CQS) & Installation (DSI) Contract of Pendik and Bornova VCIs. Consultancy Services for Consultant’s Preparing Training Material/s, CS.GKGM.CS2.1-04a, Open Qualification-based 300,000 Post TBD TBD TBD Training on Biosafety and etc. b, c….. National Selection (CQS) (Multiple Contracts) Consultancy Services for Evaluation and distribution of national reference services on Consultant’s Open the basis of disease, re- CS.GKGM.CS2.1-05 Qualification-based 70,000 Post Jan.23 Mar.23 Dec.23 National determination of norm Selection (CQS) positions and areas of responsibility Short Term Experts on Open Technical Assistance, M&E, CS.GKGM.CS2.1-06a, Individual National/ 315,000 Post TBD TBD TBD Training and etc. (Multiple b, c...... Consultants (INDV) International Contracts) 1,585,00 Subtotal Consulting Services 0 Non-Consulting Services 9 / 26 Logistical & Organizational Services for Seminar/s, NCS.GKGM.CS2.1- Requests for meeting/s, training/s on Open national 450,000 Post TBD TBD TBD 01a, b, c….. Quotations (RFQ) necropsy and etc. (Multiple Contracts) Subtotal Non-Consulting Services 450,000 Goods Procurement of Necropsy sampling and preparation G.GKGM.CS2.1.-01a, Open - Request for Bids equipment, necropsy clothing 1,935,000 Post TBD TBD TBD b, c….. National (RFB) and material storage bags (Multiple Contracts) Procurement of Sample G.GKGM.CS2.1.-02 a, Open - Request for transport containers (Multiple 105,000 Post TBD TBD TBD b, ….. National Quotations (RFQ) Contracts) 2,040,00 Subtotal Goods 0 10 / 26 Estimated Procurem Approach Selection procurement Signed Contract Method Market Estimated Review Notice/ Contract Completion ent Activity Description: Reference No Amount Method Invitation (Planned (Planned (USD ) Date Date) Date) Subcomponent 2.2: Strengthening and improving veterinary medicine product control of animal infectious and vector-borne diseases and zoonoses Consulting Services Recruitment of a Consultancy Firm for Quality and Open - conducting the Preparatory Studies, CS.GKGM.CS2. Cost-based Internation 1,500,000 Prior Dec.22 Mar.23 Jul.27 Design Review & Supervision of the 2-01 Selection al DSI Contract of VETKOM (QCBS) Open – Short Term Consultants on Legislation CS.GKGM.CS2. Individual National/ Studies, internal procedurals and etc. 2-02a, b, Consultants 500,000 Post TBD TBD TBD Internation (Multiple-Contracts) c……. (INDV) al Subtotal Consulting Services 2,000,000 Works Request for Bids Plant Open - Design, Supply & Installation W.GKGM.CS2.2 (Design, Supply Internation 48,000,000 Prior Oct.23 Dec.23 Jun.27 Contract for VETKOM -01 and Installation al Single Stage without Prequalification) Subtotal Works 48,000,000 11 / 26 Estimate d Contract Procureme Signed Estimated procurem Completi Market nt Review Contract Activity Description: Reference No Amount ent on Approach Selection Method (Planned (US$) Notice/ (Planned Method Date) Invitatio Date) n Date Subcomponent 3.1: Strengthening climate resilience, productivity, and resource-use efficiency in horticultural production Consulting Services Recruitment of a Consulting Firm for Developing Business Models for Geo-thermal Consultant’s Greenhouse Clusters; Qualificatio Preparation a National Open - 1 CS.TRGM.CS3.1-01 n-based 300,000 Post Jun.22 Sep.22 Sep.23 Geothermal Strategy for National Selection Agricultural Production and (CQS) Identifying Suitable Areas for Geothermal Greenhouse Cultivation Consultant’s Recruitment of a Consulting Qualificatio Firm for preparation of Open - 2 CS.TRGM.CS3.1-02 n-based 150,000 Post Jun.22 Sep.22 Sep.23 Environmental & Social Impact National Selection Assessment (CQS) Consultant’s Organization Consultancy Qualificatio Open - 3 Service within the Scope of CS.TRGM.CS3.1-03 n-based 250,000 Post TBD TBD TBD National Education and Sector Research Selection (CQS) Recruitment of Consulting Firm for Design / Design Review, Quality & Preparation of Bidding Open - Cost-Based 4 Documents, Provision of CS.TRGM.CS3.1-04 1,000,000 Prior Jun.22 Feb.23 Feb.26 National Selection Technical Assistance in Bid (QCBS) Evaluation/s & Supervision Services Subtotal Consulting Services 1,700,000 Non-Consulting Services 12 / 26 Logistical & Organizational Services for Dissemination and Outreach Activities to Target Request for Partnerships, Staff Training/s on Limited - 1 NCS.TRGM.CS3.1-01 Quotations 300,000 Post TBD TBD TBD Geothermal Greenhouse National (RFQ) Cultivation and Investors’ Training/s on Operation of Clusters (Multiple Contracts) Subtotal Consulting Services 300,000 Works Construction Works for Geothermal Heating System Geothermal drillings, Installation and Commissioning of the Well Equipment, Request for Open - 1 Geothermal pipelines and the W.TRGM.CS3.1-01 Bids (RFB) 9,000,000 Post Sep.23 Nov.23 Nov.25 National Heating Plant) for Pilot Project Small Works in Specialized Greenhouse Industrial Zones Based on Agriculture (Geothermal Sourced) Infrastructure Works (Irrigation, Sewerage and Rainwater Networks, Road Construction, Electricity, Telecommunication Request for and Natural Gas Networks and Open - 2 W.TRGM.CS3.1-02 Bids (RFB) 19,000,000 Prior Jan.24 Mar.24 Sep.25 etc.) for Pilot Project in National Small Works Specialized Greenhouse Industrial Zones Based on Agriculture (Geothermal Sourced) Subtotal Works 28,000,000 13 / 26 Estimate d Signed Contract Procurement Estimated procurem Activity Reference No. Market Contract Completion Reference No Selection Amount Review ent / Description: Approach (Planned (Planned Method (US$) Method Notice/ Date) Date) Invitatio n Date Subcomponent 3.2: Promoting the adoption of CSA technologies/practices across relevant crops Consulting Services Recruitment of a Consultant’s Consulting Firm for Quick Open - Qualification- 1 Assessment of the Smart CS.TRGM.CS3.2-01 300,000 Post May.22 Jul.22 Jan.23 National based Selection Technology Landscape (CQS) and Identification of Pilot Consultant’s Recruitment of a Firm for Open - Qualification- 2 Communication and CS.TRGM.CS3.2-02 300,000 Post Jun.22 Aug.22 Mar.23 National based Selection Visibility Activities (CQS) Recruitment of a Consulting Firm for Consultant’s Specific trainings Open – CS.TRGM.CS3.2-03a, b, Qualification- 3 activities on Smart National/ 750,000 Post TBD TBD TBD c… based Selection Farming for project staff International (CQS) and beneficiaries (Multiple Contracts) Recruitment of Individual Consultants for On-site Individual CS.TRGM.CS3.2-04a, b, Open - 4 monitoring of MG Consultants 600,000 Post Jul.23 Aug.23 Dec.27 c… National beneficiaries (Multiple (INDV) Contracts) Recruitment of Individual Consultant/s for Individual CS.TRGM.CS3.2-05a, b, Open - 5 Evaluation and knowledge Consultants 650,000 Post Jul.23 Aug.23 Dec.27 c… National sharing (Multiple (INDV) Contracts) Recruitment of Individual Consultants for Provision Open – Individual CS.TRGM.CS3.2 -06a, b, 6 of Technical Support to National/ Consultants 650,000 Post Jul.23 Aug.23 Dec.27 c… cooperatives (Multiple International (INDV) Contracts) 14 / 26 Recruitment of a Consulting Firm for Consultant’s Physical and Commercial Open – Qualification- 7 CS.TRGM.CS3.2 -07 300,000 Post May.23 Aug.23 Dec.27 Review of Beneficiary National based Selection Investments under (CQS matching grants Subtotal Consulting Services 3,550,000 Non-Consulting Services Logistical & Organizational Services for Stakeholder Requests for NCS.TRGM.CS3.2-01a, b, Open - 1 Engagement, Printing & Quotations 350,000 Post Feb.23 Mar.23 May.23 c… National Distribution of Outreach (RFQ) Materials (Multiple Contracts) Logistical & Requests for Organizational Services NCS.TRGM.CS3.2-02a, b, Open - 2 Quotations 850,000 Post TBD TBD TBD for Technology Demos and c… National (RFQ) Fairs (Multiple Contracts) Logistical & Organizational Services for Specific trainings Requests for NCS.TRGM.CS3.2-03a, b, Open - 3 activities on Smart Quotations 250,000 Post TBD TBD TBD c… National Farming for project staff (RFQ) and beneficiaries (Multiple Contracts) Subtotal Non-Consulting Services 1,450,000 Goods Procurement of Request for Information System for Open - Bids (RFB) 1 GO.TRGM.CS3.2-01 300,000 Post Aug.22 Nov.22 Dec.24 establishment of Smart National (Information Technology Platform System) Procurement of Goods for Capacity Enhancement of GO.TRGM.CS3.2-02a, b, Open - Request for 2 Smart Technology Hub 1,500,000 Post TBD TBD TBD c… National Bids under the Test Center (Multiple Contracts) Subtotal 1,800,000 Matching Grants 15 / 26 Matching Grants for Coops/Associations/Union Open - Commercial 1 s/ Agribusinesses/Service Matching Grants 33,000,000 Post TBD TBD TBD National Practice (CS) Providers (Multiple Contracts) Subtotal Matching Grants 33,000,000 16 / 26 Estimate d Procureme Signed Contract Estimat procurem Market nt Contract Completion Activity Reference No. / Description1: Reference No ed Review ent Approach Selection (Planned (Planned Amount Method Notice/ Method Date) Date) (US) Invitatio n Date Subcomponent 3.3 Reducing animal production pressures on water pollution and GHG emissions Consulting Services Consultant’s Recruitment of a Consulting Firm for Qualification- Open - 1 Preparation of Detailed Job Description CS.TRGM.CS3.3-01 based 50,000 Post Jun.22 Sep.22 Mar.23 National and Needs Analysis Report Selection (CQS) Consultant’s Recruitment of a Consulting Firm for Qualification- Open - 2 Establishment of Stakeholder Knowledge CS.TRGM.CS3.3-02 based 150,000 Post Oct.22 Jan.23 Jan.24 National Network Selection (CQS) Consultant’s Recruitment of a Consulting firm for Qualification- Preparing Preparatory Studies, Design Open - 3 CS.TRGM.CS3.3-03 based 200,000 Post Mar.23 Jun.23 May.26 Review and Supervision of Construction National Selection Works for Units (CQS) Consultant’s Recruitment of an Individual Consultant to Qualification- Open - 4 Develop and Validate Tools to Support CS.TRGM.CS3.3-04 based 100,000 Post Dec.22 Jan.23 Jan.24 National Technical Experts and Farmers Selection (CQS) Consultant’s Recruitment of Consulting Firm for Qualification- Open - 5. Environmental Impact Assessment CS.TRGM.CS3.3-05 based 75,000 Post May 23 August 23 Jan 24 National Process Selection (CQS) Subtotal Consulting Services 575,000 Non-Consulting Services 1 The Procurement Plan on Subcomponent 3.3. will be revised to cover the procurements for Field Demonstrations for Implementation of GAP Code (Land & Pasture Management, Fertilization Management, Irrigation Management, Pesticide Utilization Management and Preventive Farming Practices) through PPSD update/s when the subject activities become due. 17 / 26 Logistical & Organizational Services for Request for NCS.TRGM.CS3.3-01a, Open - 1 Trainings on Enhancing Capacities of Quotations 150,000 Post TBD TBD TBD b, c… National Professionals (Multiple Contracts) (RFQ) Logistical & Organizational Services for Request for NCS.TRGM.CS3.3-02a, Open - 2 Raising Awareness of Farmers and the Quotations 350,000 Post TBD TBD TBD b, c… National Public, Field Days (Multiple Contracts) (RFQ) Subtotal Consulting Services 500,000 Goods Procurement of vehicles for manure Request for Open - 1,980,00 1 collection/transportation GO.TRGM.CS3.3-01 Bids (RFB) Post Nov.22 Feb.23 Apr.25 National 0 Goods Lot 1. Procurement of Solid Fertilizer 330,000 Trailer (manure trailer) Lot 2. Procurement of Underground Injection Liquid Fertilizer Application Request for 600,000 Equipment (liquid manure injection Open - 2 GO.TRGM.CS3.3-02 Bids (RFB) Post Jan.23 Apr.23 Jun.25 machinery/equipment) National Goods Lot 3. Procurement of Solid Fertilizer 450,000 Application Loader Lot 4. Procurement of Stubble Seeder (no- 375,000 till seeder) 3,735,0 Subtotal Goods 00 Works Request for Bids Plant (Design, Design, Supply & Installation of Biogas Open - Supply and 1 Unit, Energy Production Unit and Fertilizer W.TRGM.CS3.3-01 6,720,00 Post Jan.24 Apr.24 Apr.26 National Installation Production Plant 0 Single Stage without Prequalificati on) 6,720,0 Subtotal Works 00 18 / 26 Estimate Signed d Contract Contra Procurement Estimated procurem Completi Market Review ct Activity Description: Reference No Selection Amount ent on Approach Method (Plann Method (USD) Notice/ (Planned ed Invitatio Date) Date) n Date Subcomponent 3.4: Research and innovations to support CSA Soil and Water Resources Research Department Goods Procurement of Lab & Research equipment and materials for GO.TAGEM/SWRR.CS3.4 -01 International Agricultural 400,000 Group 1 a, b, c… Research and Training Center (Multiple Contracts) Procurement of Lab & Research equipment and materials for GO.TAGEM/SWRR.CS3.4 -01 Open - Request for Bids 1 Transitional Zone Agricultural 300,000 Post Feb.23 Apr.23 Dec.27 Group 2 a, b, c… National (RFB) Goods Research Institute (Multiple Contracts) Procurement of Lab & Research equipment and materials for GO.TAGEM/SWRR.CS3.4 -01 Soil Fertilizer and Water 600,000 Group 3 a, b, c… Resources Central Research Institute (Multiple Contracts) Procurement of Lab & Research equipment and materials for GO.TAGEM/SWRR.CS3.4 -02 West Mediterranean 400,000 Group 1a, b, c… Agricultural Research Institute (Multiple Contracts) Open - Request for Bids 2 Post Jul.23 Sep.23 Dec.27 National (RFB) Goods Procurement of Lab & Research equipment and materials for GO.TAGEM/SWRR.CS3.4 -02 300,000 Black Sea Agricultural Research Group 2 a, b, c… Institute (Multiple Contracts) Procurement of the mobile hybrid milking machine for GO.TAGEM/SWRR.CS3.4 -03 100,000 UTAEM and GAP Regional Group 1 Research Institute Open - Request for Bids 3 Post Sep.23 Nov.23 Jan.26 Procurement of the Electric National (RFB) Tractor Prototype in 65 HP for GO.TAGEM/SWRR.CS3.4 -03 350,000 UTAEM and GAP Regional Group 2 Research Institute 19 / 26 Procurement of installation of Solar Mobile Irrigation for GO.TAGEM/SWRR.CS3.4 -03 100,000 UTAEM and GAP Regional Group 3 Research Institute Procurement of Laptop/s Open - Requests for October 4 GO.TAGEM/SWRR.CS3.4 -04 85,000 Post Sept 22 Dec 22 including GPS hardware National Quotations (RFQ) 22 Procurement of equipment to measure carbon emissions, Open - Request for Bids 5 GO.TAGEM/SWRR.CS3.4 -05 940,000 Post Feb 23 May 23 August 23 irrigation system, fertilizer/s and National (RFB) chemicals Procurement of equipment for GO.TAGEM/SWRR.CS3.4 -06a, Open - Requests for 6 irrigation system, fertilizer/s and 210,000 Post TBD TBD TBD b, c… National Quotations (RFQ) chemicals (Multiple Contracts) Procurement of Goods for Enhancing the R&D Innovation GO.TAGEM/SWRR.CS3.4 -07a, Open - Requests for 7 800,000 Post TBD TBD TBD Capacity for Water Efficiency b, c… National Quotations (RFQ) UTAEM (Multiple Contracts) Subtotal Goods 4,585,000 Works Request for Bids Construction & Renovation of Plant the Agricultural Mechanization (Design, Supply R&D and Innovation Center 1 W.TAGEM/SWRR.CS3.4-01 Open National and Installation 1,750,000 Post Jan.23 Mar.23 Sep.25 (incl. Laboratory Equipment; Single Stage Research Equipment; IT without Equipment) Prequalification) Procurement of small renovation works for Soil W.TAGEM/SWRR.CS3.4-02a, b, Open - Requests for 2 Fertilizer and Water Resources 400,000 Post Aug.22 Sep.22 Dec.27 c…. National Quotations (RFQ) Central Research Institute (Multiple Contracts) Procurement of small renovation works for W.TAGEM/SWRR.CS3.4-03 a, Open - Requests for 3 International Agricultural 200,000 Post Aug.22 Sep.22 Dec.27 b, c…. National Quotations (RFQ) Research and Training Center (Multiple Contracts) Procurement of small W.TAGEM/SWRR.CS3.4-04 a, Open - Requests for 4 renovation works for West 200,000 Post Aug.22 Sep.22 Dec.27 b, c…. National Quotations (RFQ) Mediterranean Agricultural 20 / 26 Research Institute (Multiple Contracts) Procurement of small renovation works for W.TAGEM/SWRR.CS3.4-05 a, Open - Requests for 5 Transitional Zone Agricultural 200,000 Post Aug.22 Sep.22 Dec.27 b, c…. National Quotations (RFQ) Research Institute (Multiple Contracts) Procurement of small renovation works for Black sea W.TAGEM/SWRR.CS3.4-06 a, Open - Requests for 6 200,000 Post Aug.22 Sep.22 Dec.27 Agricultural Research Institute b, c…. National Quotations (RFQ) (Multiple Contracts) Subtotal Works 2,950,000 Consulting Services Recruitment of a Consulting Consultant’s Firm for Concept Design, Open - Qualification- 1 Bidding Documents, Design CS.TAGEM/SWRR.CS3.4-01 100,000 Post May.22 Jul.22 Sep.25 National based Selection Review and Supervision of (CQS) Construction Works Recruitment of a Consulting Firm for Training, Field Consultant’s Application, Uploading of SHARP Open - Qualification- 2 Application & CS.TAGEM/SWRR.CS3.4-02 70,000 Post May.22 Aug.22 Dec.24 National based Selection Preparation/Information (CQS) Dissemination of Guidelines for adapting Climate Change Recruitment of a Consulting Consultant’s Firm for Conducting SHARP Open - Qualification- 3 surveys for Climate Change CS.TAGEM/SWRR.CS3.4-03 45,000 Post June 23 Sept 23 May 24 National based Selection Awareness Assessment and (CQS) Capacity (SHARP). Consultant’s Recruitment of a Consulting Open - Qualification- 4 Firm training for Carbon CS.TAGEM/SWRR.CS3.4-04 200,000 Post August .22 Nov.22 Dec.23 National based Selection Footprint Assessment (CQS) Consultant’s Recruitment of a Consulting Open - Qualification- 5 CS.TAGEM/SWRR.CS3.4-05 250,000 Post Feb 27 May 27 Dec 27 Firm for Product Certification/s National based Selection (CQS) Individual Short-Term Individual CS.TAGEM/SWRR.CS3.4-06a, Open - 6 Consultants on training of Consultant 200,000 Post TBD TBD TBD b, c… National trainers on the Fertilizer use and (INDV) 21 / 26 other subjects (Multiple Contracts) Subtotal Consulting Services 865,000 Non-Consulting Services Printing/Shooting/Distribution of Training materials (Brochure/s, Leaflet/s, Poster/s, Short Film/s and etc.), Organizational & NCS.TAGEM/SWRR.CS3.4-01a, Limited – Request for 1 300,000 Post TBD TBD TBD Logistical Services for Training b, c…. National Quotation (RFQ) Activities for Trainers, Meeting/s and field day/s (Multiple Contracts) Subtotal Non-Consulting Services 300,000 Crop Health Research Department Goods Procurement of Lab & Research equipment and materials for GO.TAGEM/CHR.CS3.4-01 Agricultural fauna and 1,000,000 Group 1a, b, c… microflora center (Multiple Contracts) Procurement of Lab & Research equipment and materials for GO.TAGEM/CHR.CS3.4-01 1,000,000 Soil borne pathogens center Group 2a, b, c… Open - Request for Bids 1 Post Feb.23 Apr.23 Dec.27 (Multiple Contracts) National (RFB) Goods Procurement of Lab & Research equipment and materials for Plant Protection Central GO.TAGEM/CHR.CS3.4-01 Research Institute in Ankara Group 3a, b, c… 950,000 (Multiple Contracts) Mass production of microbial pesticides Subtotal Goods 2,950,000 Works Procurement of Works for Insect Production Rooms and Climate Request for Bids Open - 1 Chambers for Bornova W.TAGEM/CHR.CS3.4-01 (RFB) Small 750,000 Post Feb.23 Apr.23 Dec.27 National Biotechnical Control Research Works Center Procurement of Refurbishment Open - Request for Bids 2 Works for Adana Biological W.TAGEM/CHR.CS3.4-02 750,000 Post Feb.23 Apr.23 Dec.27 National (RFB) Control and Research Center 22 / 26 Procurement of Small Works for Labs for Agricultural Fauna and W.TAGEM/CHR.CS3.4-03a, b, Open - Requests for 3 500,000 Post Apr.23 Jul.23 Dec.27 Microflora Center (Multiple c… National Quotations (RFQ) Contracts) Procurement of Small Works for W.TAGEM/CHR.CS3.4-04a, b, Open - Requests for 4 Labs for Soil Borne Pathogens 500,000 Post May.23 Aug.23 Dec.27 c… National Quotations (RFQ) Center (Multiple Contracts) Procurement of Small Works for Labs for Plant Protection Central Research Institute in Ankara W.TAGEM/CHR.CS3.4-05a, b, Open - Requests for 5 500,000 Post Jun.23 Sep.23 Dec.27 (Multiple Contracts) Mass c… National Quotations (RFQ) production of microbial pesticides Subtotal Works 3,000,000 Consulting Services Individual Short-Term Consultants on Mass production Open – Individual CS.TAGEM/CHR.CS3.4-01a, b, 1 of microbial pesticides and National/ Consultant 50,000 Post June.23 July.23 Dec.27 c… other subjects (Multiple International- (INDV) Contracts) Subtotal Consulting Services 50,000 23 / 26 Estimate d Contract Signed Procurement Revie procurem Completi Market Estimated Contract Activity Description Reference No Selection w ent on Approach Amount (Planned Method Metho Notice/ (Planned (USD) Date) d Invitation Date) Date Component 4: Project Management, Monitoring, and Evaluation Consulting Services Individual Open- 1 Project Coordinator CS.EU&FA.CS4-01 Consultant 216,000 Post May.22 Jun.22 Apr.28 National (INDV) Individual Senior Financial Management Open- 2 CS.EU&FA.CS4-02 Consultant 180,000 Post May.22 Jun.22 Apr.28 Specialist National (INDV) Individual Open- 3 Financial Management Specialist CS.EU&FA.CS4-03 Consultant 144,000 Post May.22 Jun.22 Apr.28 National (INDV) Individual Open- 4 Senior M&E Specialist CS.EU&FA.CS4-04 Consultant 180,000 Post May.22 Jun.22 Apr.28 National (INDV) Individual Open- 5 Translators (2 persons) CS.EU&FA.CS4-05a, b Consultant 216,000 Post May.22 Jun.22 Apr.28 National (INDV) Individual Open- 6 Communication Specialist CS.EU&FA.CS4-06 Consultant 180,000 Post Mar.22 Aug.22 Apr.28 National (INDV) Individual Open- 7 Senior Procurement Expert CS.EU&FA.CS4-07 Consultant 180,000 Post May.22 Jun.22 Apr.28 National (INDV) Individual M&E and Reporting Expert/s (2 Open- 8 CS.EU&FA.CS4-08a, b Consultant 288,000 Post Jun.22 Jul.22 Apr.28 persons) National (INDV) Individual Open- 9 Procurement Expert/s (3 persons) CS.EU&FA.CS4-09a, b, c Consultant 432,000 Post May.22 Jun.22 Apr.28 National (INDV) 24 / 26 Individual Senior Environmental Specialist for Open- Consultant 10 infrastructure works of GKGM & CS.EU&FA.CS4-10 180,000 Post May.22 Jun.22 Apr.28 National (INDV) TRGM, Individual Senior Social Specialist for Open- Consultant 11 infrastructure works of GKGM & CS.EU&FA.CS4-11 180,000 Post May.22 Jun.22 Apr.28 National (INDV) TRGM Individual Environmental Specialist/s (2 Open- Consultant 12 persons) CS.EU&FA.CS4-12a, b 288,000 Post May.22 Jun.22 Apr.28 National (INDV) Individual Social Specialists (2 persons) Open- Consultant 13 CS.EU&FA.CS4-13a, b 288,000 Post May.22 Jun.22 Apr.28 National (INDV) Individual Individual Expert for preparation of Limited- Consultant 14 CS.EU&FA.CS4-14 40,000 Post Jun.25 Jul.25 Dec.25 Mid-Term Review Report National (INDV) Individual Individual Expert for preparation of Limited- Consultant 15 CS.EU&FA.CS4-15 40,000 Post Oct.27 Nov.27 Apr.28 Implementation Completion Report National (INDV) Individual Specific Technical Support (Multiple CS.EU&FA.CS4-16a, b, Open/Limit Consultant 16 100,000 Post TBD TBD TBD Contracts) c……. ed-National (INDV) Recruitment of Individual Individual CS.EU&FA.CS4-17 a, b, Open/Limit 17 Consultant/s for Capacity Building Consultant 100,000 Post TBD TBD TBD c… ed-National (Multiple Contracts) (INDV) Consultant’s Qualification- Recruitment of Consulting Firm/s for CS.EU&FA.CS4-18 a, b, Open- 18 based 150,000 Post TBD TBD TBD Capacity Building (Multiple Contracts) c… National Selection (CQS) Consultant’s Recruitment of a Consulting Firm for Qualification- Open- 19 Establishment of Grievance and CS.EU&FA.CS4-19 based 300,000 Post Jun.22 Sep.22 Dec.24 National Redress Mechanism Selection (CQS) Consultant’s Recruitment of a Consulting Firm for Qualification- Open- 20 Visibility Materials and Outreach CS.EU&FA.CS4-20 based 300,000 Post Jun.22 Sep.22 Dec.24 National Package Selection (CQS) Subtotal Consulting Services 3,982,000 25 / 26 Goods Requests for Procurement of Office Furniture for Limited - 1 GO.EU&FA.CS4-01 Quotations 100,000 Post May.22 Jun.22 Jul.22 PCU and PIUs National (RFQ) Procurement of Laptops & Requests for Limited - 2 Printers/Photocopy Machine for PCU GO.EU&FA.CS4-02 Quotations 130,000 Post May.22 Jun.22 Jul.22 National and PIUs (RFQ) Requests for Procurement of FM software Tool for Limited - 3 GO.EU&FA.CS4-03 Quotations 20,000 Post May.22 Jun.22 Jul.22 PCU National (RFQ) Procurement of Hardware and Requests for Limited - 4 Software for Establishment of M&E GO.EU&FA.CS4-04 Quotations 100,000 Post May.22 Jun.22 Dec.27 National System (RFQ) Subtotal Goods 350,000 Non-Consulting Services Requests for Logistical & Organizational Services Limited - 1 NCS.EU&FA.CS4-01 Quotations 20,000 Post May.22 Jun.22 Aug.22 for Project Opening Ceremony National (RFQ) Requests for Logistical & Organizational Services Limited - 2 NCS.EU&FA.CS4-02 Quotations 20,000 Post Jan.28 Feb.28 Mar.28 for Project Closing Ceremony National (RFQ) Logistical & Organizational for Requests for NCS.EU&FA.CS4-03a, b, Limited - 3 Commissioning Ceremonies (Multiple Quotations 300,000 Post Aug.22 Sep.22 Dec.26 c… National Contracts) (RFQ) Logistical & Organizational for AWPB Requests for NCS.EU&FA.CS4-04a, b, Limited - 4 Annual Work Plan and Budget Quotations 180,000 Post Oct.22 Nov.22 Nov.27 c… National Meetings (Multiple Contracts) (RFQ) Logistical & Organizational Request for Services/Printing, Open/Limit Bids (RFB) / NCS.EU&FA.CS4-05a, b, 5 Production/Distribution of Visibility ed - Requests for 1,200,000 Post May.22 Jun.22 Nov.27 c… Materials and Outreach Package for National Quotations Subcomponents (Multiple Contracts) (RFQ) Logistical & Organizational Services Limited- 6 NCS.EU&FA.CS4-06 RFQ 100,000 Post Mar.23 May.23 Apr.28 for Information Dissemination National Subtotal Non-Consulting Services 1,820,000 26 / 26 PROCUREMENT Turkiye : Turkey Climate Smart and Competitive Agricultural Growth Project (TUCSAP) PLAN General Information Country: Turkiye 2022-07-07 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175011 GPN Date: 2022-04-29 Project Name: Turkey Climate Smart and Competitive Agricultural Growth Project (TUCSAP) Loan / Credit No: IBRD / 93720 Ministry of Agriculture and Forestry, General Directorate of EU and Foreign Relations Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GO.EU&FA.CS4-02 / Procure Component 4: Project Manag Request for Quota Single Stage - One E Under Imple ment of Laptops & Printers/P IBRD / 93720 ement, Monitoring, and Eval Post Limited 0.00 2023-03-06 2023-04-05 2023-05-01 2023-10-28 tions nvelope mentation hotocopy Machine for PCU an uation. d PIUs NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NCS.ABDGM.CS4-01 / Logisti Component 4: Project Manag Request for Quota Single Stage - One E Under Imple cs & Organization Services fo IBRD / 93720 ement, Monitoring, and Eval Post Limited 0.00 2023-06-03 2023-06-15 2023-06-30 tions nvelope mentation r the Project Opening Cerem uation. ony CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS.EU&FA.CS4-01 / Recruitm Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Terminated 2022-07-22 2022-07-22 2022-09-17 2022-11-22 2022-09-24 2022-11-24 2022-10-01 2023-10-01 ent of Project Coordinator ement, Monitoring, and Eval ant Selection uation. CS.EU&FA.CS4-12B / Recruit Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-11-29 2022-09-24 2022-10-01 2023-10-01 ment of Environmental Speci ement, Monitoring, and Eval ant Selection alist uation. CS.EU&FA.CS4-02 / Recruitm Component 4: Project Manag Individual Consult ent of Lead Financial Manage IBRD / 93720 ement, Monitoring, and Eval Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-11-22 2022-09-24 2022-10-01 2023-10-01 ant Selection ment Specialist uation. CS.EU&FA.CS4-12A / Recruit Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-18 2022-09-17 2022-11-29 2022-09-24 2022-10-01 2023-10-01 ment of Environmental Speci ement, Monitoring, and Eval ant Selection alist uation. CS.EU&FA.CS4-07 / Recruitm Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-11-22 2022-09-24 2022-10-01 2023-10-01 ent of Lead Procurement Spe ement, Monitoring, and Eval ant Selection cialist uation. CS.EU&FA.CS4-09C / Recruit Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-11-25 2022-09-24 2022-10-01 2023-10-01 ment of Procurement Speciali ement, Monitoring, and Eval ant Selection st uation. CS.EU&FA.CS4-05B / Recruit Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2023-01-23 2022-09-24 2023-01-19 2022-10-01 2023-10-01 ment of Translator ement, Monitoring, and Eval ant Selection uation. CS.EU&FA.CS4-09B / Recruit Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-11-22 2022-09-24 2022-11-25 2022-10-01 2023-10-01 ment of Procurement Speciali ement, Monitoring, and Eval ant Selection st uation. CS.EU&FA.CS4-09A / Recruit Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-11-22 2022-09-24 2022-11-24 2022-10-01 2023-10-01 ment of Procurement Speciali ement, Monitoring, and Eval ant Selection st uation. CS.EU&FA.CS4-11 / Recruitm Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-11-22 2022-09-24 2022-12-21 2022-10-01 2023-10-01 ent of Lead Social Specialist ement, Monitoring, and Eval ant Selection uation. CS.EU&FA.CS4-10 / Recruitm Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-12-23 2022-09-24 2022-12-23 2022-10-01 2023-10-01 ent of Lead Environmental Sp ement, Monitoring, and Eval ant Selection ecialist uation. CS.EU&FA.CS4-08A / Recruit Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-11-25 2022-09-24 2022-11-28 2022-10-01 2023-10-01 ment of M&E and Reporting S ement, Monitoring, and Eval ant Selection pecialist uation. CS.EU&FA.CS4-13A / Recruit Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-11-22 2022-09-24 2022-11-22 2022-10-01 2023-10-01 ment of Social Specialists ement, Monitoring, and Eval ant Selection uation. CS.EU&FA.CS4-08B / Recruit Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-12-08 2022-09-24 2022-12-08 2022-10-01 2023-10-01 ment of M&E and Reporting S ement, Monitoring, and Eval ant Selection pecialist uation. CS.EU&FA.CS4-06 / Recruitm Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-18 2022-09-17 2022-11-22 2022-09-24 2022-11-22 2022-10-01 2023-10-01 ent of Communication Specia ement, Monitoring, and Eval ant Selection list uation. CS.EU&FA.CS4-05A / Recruit Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-11-24 2022-09-24 2022-11-24 2022-10-01 2023-10-01 ment of Translator ement, Monitoring, and Eval ant Selection uation. CS.EU&FA.CS4-03 / Recruitm Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-11-22 2022-09-24 2022-11-24 2022-10-01 2023-10-01 ent of Financial Management ement, Monitoring, and Eval ant Selection Specialist uation. Page 1 CS.EU&FA.CS4-13B / Recruit Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-11-29 2022-09-24 2022-11-29 2022-10-01 2023-10-01 ment of Social Specialists ement, Monitoring, and Eval ant Selection uation. CS.EU&FA.CS4-04 / Recruitm Component 4: Project Manag Individual Consult IBRD / 93720 Post Open 0.00 Canceled 2022-07-22 2022-07-22 2022-09-17 2022-11-22 2022-09-24 2022-11-22 2022-10-01 2023-10-01 ent of Lead M&E Specialist ement, Monitoring, and Eval ant Selection uation. CS.EU&FA.CS4.09B / Recruit Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2022-11-25 2022-11-25 2022-11-25 2022-11-25 2022-12-23 2023-12-31 ment of Procurement Expert ement, Monitoring, and Eval ant Selection ation uation. CS.EU&FA.CS4.09A / Recruit Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2022-11-22 2022-11-22 2022-11-22 2022-11-22 2022-12-23 2023-12-31 ment of Procurement Expert ement, Monitoring, and Eval ant Selection ation uation. CS.EU&FA.CS4.05A / Recruit Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2023-01-19 2022-11-22 2023-01-19 2022-11-22 2023-02-03 2023-12-31 ment of Translator ement, Monitoring, and Eval ant Selection ation uation. CS.EU&FA.CS4.05B / Recruit Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2022-11-22 2023-01-19 2022-11-22 2023-01-19 2022-12-23 2023-12-31 ment of Translator ement, Monitoring, and Eval ant Selection ation uation. CS.EU&FA.CS4.04 / Recruitm Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2022-11-22 2022-11-22 2022-11-22 2022-11-22 2022-12-26 2023-12-31 ent of Senior M&E Specialist ement, Monitoring, and Eval ant Selection ation uation. CS.EU&FA.CS4.08A / Recruit Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2022-11-25 2022-11-25 2022-11-25 2022-11-25 2022-12-23 2023-12-31 ment of M&E and Reporting E ement, Monitoring, and Eval ant Selection ation xpert uation. CS.EU&FA.CS4.08B / Recruit Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2022-12-08 2022-12-08 2022-12-08 2022-12-08 2022-12-23 2023-12-31 ment of M&E and Reporting E ement, Monitoring, and Eval ant Selection ation xpert uation. CS.EU&FA.CS4.10 / Recruitm Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2022-12-23 2022-12-23 2022-12-23 2022-12-23 2022-12-30 2024-01-15 ent of Senior Environmental ement, Monitoring, and Eval ant Selection ation Specialist uation. CS.EU&FA.CS4.11 / Recruitm Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2022-11-22 2022-11-22 2022-11-22 2022-11-22 2022-12-23 2023-12-31 ent of Senior Social Specialist ement, Monitoring, and Eval ant Selection ation uation. CS.EU&FA.CS4.13A / Recruit Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2022-11-22 2022-11-22 2022-11-22 2022-11-22 2022-12-23 2023-12-31 ment of Social Specialists ement, Monitoring, and Eval ant Selection ation uation. CS.EU&FA.CS4.13B / Recruit Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2022-11-29 2022-12-21 2022-11-29 2022-11-29 2022-12-23 2023-12-31 ment of Social Specialists ement, Monitoring, and Eval ant Selection ation uation. CS.EU&FA.CS4.03 / Recruitm Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2022-11-22 2022-11-22 2022-11-22 2022-11-22 2022-12-23 2023-12-31 ent of Financial Management ement, Monitoring, and Eval ant Selection ation Specialist uation. CS.EU&FA.CS4.06 / Recruitm Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2022-11-22 2022-11-22 2022-11-22 2022-11-22 2022-12-26 2023-12-31 ent of Communication Specia ement, Monitoring, and Eval ant Selection ation list uation. CS.EU&FA.CS4.01 / Recruitm Component 4: Project Manag Individual Consult Under Implement IBRD / 93720 Post Open - National 0.00 2022-07-22 2022-07-22 2022-11-22 2022-11-22 2022-11-22 2022-11-22 2022-12-23 2023-12-31 ent of Project Coordinator ement, Monitoring, and Eval ant Selection ation uation. Page 2 WATER AND SANITATION DEVELOPMENT PROJECT (WSDP) SUMMARY PROCUREMENT PLAN (first eighteen months) I. General The following procurement plan has been developed for project implementation during the first eighteen months and provides the basis for the procurement methods and bank prior/post review thresholds. It covers the three categories, namely, Works; Consultancies; and Goods. The plan will be updated when need arises to reflect the actual project implementation needs. 1. Project information: Country / Borrower: Republic of Kenya Project: Water and Sanitation Development Project (WSDP) IDA Credit No. 6029 & 6030 Project Implementing Agencies: (a) Ministry of Water and Irrigation, (b) WaSREB, (c) Water Service Providers: Kilifi-Mariakani Water and Sewerage Company (Kimawasco),; Taita-Voi Water and Sewerage Company (Tavevo); Mombasa Water Supply and Sanitation Company (Mowassco); Kwale Water and Sewerage Company (Kwawasco); Garissa Water and Sewerage Company (Gawasco); Wajir Water and Sewerage Company (Wajwasco); and Malindi Water and Sewerage Company; and (d) Counties: Kilifi; Taita Taveta; Mombasa; Kwale; Garissa; and Wajir 2. Bank’s approval Date of the First Eighteen Months’ Procurement Plan: June 15, 2017 3. Date of General Procurement Notice: June 14, 2017 4. Period covered by this procurement plan: June 2017 to December 2018 II: Works, Goods and Consultancy Services: Thresholds for Procurement Methods and Bank’s Prior Review The Table below provides the details of Thresholds for Procurement Methods and Bank’s Prior Review for Works, Goods and Consultancy Services Page 1 of 2 Contract Value (Threshold) Procurement Expenditure Contract Subject to Category (US$ 000) Method Prior Review 1. Works 15,000 or more ICB Contracts above $5 million Below 15,000 NCB First contract per entity and Contracts above $5 million Below or equal Shopping None unless contract 200 specified in the PP No threshold Direct As specified in PP Contracting 2. Goods 1,000 or more ICB First contract per entity and Contracts above $1.5 million Below 1,000 NCB First contract per entity Below or equal Shopping None unless contract to 100 specified in the PP No threshold Direct As specified in PP Contracting 3. Consultancy Firms* QCBS,LCS,FBS, First contract per Services QBS entity and Contracts above $0.5 million Firms* CQS First contract per (Estimated cost entity less than $300,000) Individual IC (at least 3 All contract of CVs) estimated cost above $200,000 and more No threshold Single Source All *Assignments whose estimated cost is less $300,000 could be Open-National (Shortlist could comprise of all national firms) NB: All terms of reference for consulting services will be subject to IDA’s prior review. Page 2 of 2 PROCUREMENT Kenya : Water and Sanitation Development Project PLAN General Information Country: Kenya 2018-08-22 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P156634 GPN Date: 2017-06-13 Project Name: Water and Sanitation Development Project Loan / Credit No: IDA / 60300 kWALE WATER AND SEWERAGE COMPANY LTD Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component 1: Rehabilitation KE-KWAWASCO-200410-CW- and expansion of urban wat RFB / construction of a sludg Single Stage - One E Pending Imp 2021-12-2 IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 590,000.00 0.00 2020-11-05 2020-11-10 2020-12-22 2021-01-21 2021-02-25 e handling facility at Ukunda nvelope lementation 2 vices in the coastal region ( town US$176 of w hich IDA-SUF U S$160 million). Component 1: Rehabilitation KE-KWAWASCO-201675-CW- and expansion of urban wat RFB / construction of four nu Single Stage - One E 2021-12-2 IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 600,000.00 683,807.01 Signed 2020-11-12 2021-11-18 2020-11-17 2021-11-18 2020-12-29 2021-12-15 2021-01-28 2022-01-19 2021-03-04 2022-02-16 mber ablution blocks for Kwa nvelope 9 vices in the coastal region ( le town US$176 of w hich IDA-SUF U S$160 million). Component 1: Rehabilitation KE-KWAWASCO-203531-CW- and expansion of urban wat RFB / Laying of distribution li Single Stage - One E 6,765,852.4 2022-06-0 IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 8,505,374.00 Signed 2020-11-17 2020-12-11 2020-11-22 2020-12-11 2021-01-03 2021-01-14 2021-02-02 2021-02-22 2021-03-09 2021-09-15 nes from Mabokoni reservoir nvelope 6 2 vices in the coastal region ( to Ukunda town and environs US$176 of w hich IDA-SUF U S$160 million). Component 1: Rehabilitation KE-KWAWASCO-203535-CW- and expansion of urban wat RFB / Construction of Admini Single Stage - One E 2022-06-0 IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 859,318.00 766,275.76 Signed 2020-11-17 2020-12-15 2020-11-22 2020-12-11 2021-01-03 2021-01-14 2021-02-02 2021-02-26 2021-03-09 2021-09-15 stration building,laboratory,w nvelope 2 vices in the coastal region ( orkshop and store US$176 of w hich IDA-SUF U S$160 million). Component 1: Rehabilitation KE-KWAWASCO-203571-CW- and expansion of urban wat RFB / Construction of six num Single Stage - One E 2021-12-3 IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 900,000.00 970,314.43 Signed 2020-11-13 2021-10-18 2020-11-18 2021-11-18 2020-12-30 2021-12-15 2021-01-29 2022-01-19 2021-03-05 2022-02-16 ber ablution blocks for Ukund nvelope 0 vices in the coastal region ( a town US$176 of w hich IDA-SUF U S$160 million). KE-KWAWASCO-74619-CW-R Component 1: Rehabilitation FB / Construction of immedia and expansion of urban wat Single Stage - One E 2019-08-0 te urgent sanitation works(4 IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 1,100,000.00 0.00 Canceled 2018-10-18 2018-10-23 2018-12-04 2019-01-03 2019-02-07 nvelope 6 No. Ablution blocks and sludg vices in the coastal region ( e handling facilities) for Kwal US$176 of w hich IDA-SUF U e town S$160 million). KE-KWAWASCO-74613-CW-R Component 1: Rehabilitation FB / Construction of immedia and expansion of urban wat Single Stage - One E 2019-06-2 te urgent sanitation works (6 IDA / 60300 er supply and sanitation ser Prior Request for Bids Open - National 1,690,000.00 0.00 Canceled 2018-09-10 2018-09-15 2018-10-27 2018-11-26 2018-12-31 nvelope 9 No.Ablution blocks and sludg vices in the coastal region ( e handling facilities for Ukun US$176 of w hich IDA-SUF U da town) S$160 million). KE-KWAWASCO-114987-CW- Component 1: Rehabilitation RFB / Construction of the pro and expansion of urban wat posed phase one of the wate er supply and sanitation ser Open - Internationa Single Stage - One E 15,500,000.0 2021-03-1 IDA / 60300 Prior Request for Bids 0.00 Canceled 2019-05-31 2019-06-05 2019-07-17 2019-08-16 2019-09-20 r supply improvement works vices in the coastal region ( l nvelope 0 3 for Ukunda , US$176 of w hich IDA-SUF U WSP head office building, Sto S$160 million). re and Fencing. KE-KWAWASCO-206973-CW- Component 1: Rehabilitation RFB / Construction of collecto and expansion of urban wat Open - Internationa Single Stage - One E 6,274,775.6 2022-06-1 r and transmission lines, bore IDA / 60300 er supply and sanitation ser Post Request for Bids 6,085,308.00 Signed 2020-12-04 2020-12-26 2020-12-09 2020-12-26 2021-01-20 2021-01-29 2021-02-19 2021-03-18 2021-03-26 2021-09-15 l nvelope 0 9 hole drilling, equipping and a vices in the coastal region ( uxiliary facilities US$176 of w hich IDA-SUF U S$160 million). GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Rehabilitation KE-KWAWASCO-63985-GO-R and expansion of urban wat Single Stage - One E FB / Procurement of 2 No. Mo IDA / 60300 er supply and sanitation ser Prior Request for Bids Open - National 140,000.00 0.00 Canceled 2018-08-24 2019-06-14 2018-08-29 2019-07-11 2018-10-10 2019-08-15 2018-11-09 2018-12-14 2019-06-12 nvelope tor vehicles vices in the coastal region ( US$176 of w hich IDA-SUF U S$160 million). KE-KWAWASCO-74578-GO-R Component 1: Rehabilitation FB / Purchase of 650 No. cold and expansion of urban wat water meters,individual cust er supply and sanitation ser Single Stage - One E IDA / 60300 Post Request for Bids Open - National 300,000.00 356,616.01 Completed 2018-09-14 2019-08-05 2018-09-19 2019-08-05 2018-10-31 2019-09-05 2018-11-30 2019-10-03 2019-01-04 2020-01-28 2019-07-03 2020-12-08 omer and bulk meters for rep vices in the coastal region ( nvelope lacement to AMR enabled of US$176 of w hich IDA-SUF U DN15mm-40mm,50mm-200 S$160 million). mm Component 1: Rehabilitation KE-KWAWASCO-74584-GO-R and expansion of urban wat Request for Quota Single Stage - One E FQ / Procurement of 10 No. M IDA / 60300 er supply and sanitation ser Post Open - National 61,500.00 35,590.72 Completed 2018-09-16 2019-07-26 2018-11-11 2020-01-23 2019-05-10 2020-04-02 tions nvelope otor cycles vices in the coastal region ( US$176 of w hich IDA-SUF U S$160 million). Component 1: Rehabilitation KE-KWAWASCO-74587-GO-R and expansion of urban wat FQ / Procurement of a repair Single Stage - One E IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 100,000.00 97,408.78 Completed 2018-09-04 2019-07-15 2018-09-09 2019-07-15 2018-10-21 2019-08-22 2018-11-20 2019-09-12 2018-12-25 2020-01-28 2019-06-23 2020-08-12 kit for critical tools and fitting nvelope vices in the coastal region ( s US$176 of w hich IDA-SUF U S$160 million). Component 1: Rehabilitation KE-KWAWASCO-74600-GO-R and expansion of urban wat Single Stage - One E FQ / Procurement of office eq IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 100,000.00 62,724.82 Completed 2018-09-20 2019-07-18 2018-09-25 2019-07-18 2018-11-06 2019-08-22 2018-12-06 2019-09-16 2019-01-10 2020-01-23 2019-07-09 2020-04-02 nvelope uipment and furniture vices in the coastal region ( US$176 of w hich IDA-SUF U S$160 million). Page 1 Component 1: Rehabilitation KE-KWAWASCO-126395-GO- and expansion of urban wat RFB / Procurement of 4 No.M Single Stage - One E IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 245,000.00 152,489.13 Completed 2019-08-23 2019-12-17 2019-08-28 2019-12-18 2019-09-27 2020-01-16 2019-10-27 2020-02-10 2019-12-01 2020-03-14 2020-01-30 2021-04-23 eter testing kit,service bay a nvelope vices in the coastal region ( nd 2No. Water leak detectors US$176 of w hich IDA-SUF U S$160 million). Component 1: Rehabilitation KE-KWAWASCO-157936-GO- and expansion of urban wat RFB / Supply and delivery of Single Stage - One E IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 275,000.00 249,085.86 Completed 2020-02-18 2020-04-02 2020-02-23 2020-04-02 2020-04-05 2020-05-11 2020-05-05 2020-05-26 2020-06-09 2020-07-03 2020-12-06 2021-07-16 Two (2No.) water bowsers of nvelope vices in the coastal region ( 10M3 tank each US$176 of w hich IDA-SUF U S$160 million). Component 1: Rehabilitation KE-KWAWASCO-157940-GO- and expansion of urban wat RFB / Supply and delivery of Single Stage - One E IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 275,000.00 249,953.72 Completed 2020-02-18 2020-04-02 2020-02-23 2020-04-02 2020-04-05 2020-05-11 2020-05-05 2020-05-26 2020-06-09 2020-07-01 2020-12-06 2021-01-19 Two (2 No.) Exhausters of 8 nvelope vices in the coastal region ( M3 tank each US$176 of w hich IDA-SUF U S$160 million). Component 1: Rehabilitation KE-KWAWASCO-173715-GO- and expansion of urban wat Request for Quota Single Stage - One E RFQ / Supply and delivery of IDA / 60300 er supply and sanitation ser Post Limited 13,126.00 19,731.11 Completed 2020-05-20 2020-05-19 2020-07-15 2020-07-28 2020-09-13 2020-12-04 tions nvelope emergency ICT equipment vices in the coastal region ( US$176 of w hich IDA-SUF U S$160 million). Component 1: Rehabilitation KE-KWAWASCO-188520-GO- and expansion of urban wat RFB / Supply and delivery of Single Stage - One E IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 184,268.00 162,077.01 Completed 2020-08-24 2020-09-05 2020-08-29 2020-09-05 2020-10-10 2020-10-09 2020-10-19 2020-10-18 2020-11-08 2020-11-20 2021-01-22 2021-05-15 2No. double cabin Motor vehi nvelope vices in the coastal region ( cles US$176 of w hich IDA-SUF U S$160 million). Component 1: Rehabilitation KE-KWAWASCO-203572-GO- and expansion of urban wat RFB / Supply and delivery of Single Stage - One E IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 143,000.00 143,898.03 Completed 2020-11-16 2020-11-17 2020-11-21 2020-11-17 2021-01-02 2020-12-24 2021-02-01 2021-01-07 2021-03-08 2021-02-23 2021-05-07 2021-08-07 One number Water bowser 1 nvelope vices in the coastal region ( 0 M3 tank capacity US$176 of w hich IDA-SUF U S$160 million). Component 1: Rehabilitation KE-KWAWASCO-281406-GO- and expansion of urban wat RFQ / Procurement of furnitur Request for Quota Single Stage - One E IDA / 60300 er supply and sanitation ser Post Limited 15,331.00 12,880.03 Terminated 2022-03-30 2022-03-28 2022-05-25 2022-05-29 2022-09-22 e and office Equipment (ICT tions nvelope vices in the coastal region ( equipment lot2) US$176 of w hich IDA-SUF U S$160 million). KE-KWAWASCO-358910-GO- Component 1: Rehabilitation RFQ / Supply and delivery of and expansion of urban wat Single Stage - One E Under Imple office furniture and equipme IDA / 60300 er supply and sanitation ser Post Request for Bids Open - National 98,507.30 0.00 2023-05-30 2023-06-07 2023-06-04 2023-06-07 2023-07-04 2023-08-03 2023-09-07 2024-01-05 nvelope mentation nt for the proposed Utility ad vices in the coastal region ( ministration building US$176 of w hich IDA-SUF U S$160 million). NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-KWAWASCO-74622-CS-L Component 1: Rehabilitation CS / Provision of consultancy and expansion of urban wat for community awareness an er supply and sanitation ser Least Cost Selecti IDA / 60300 Post Open - National 200,000.00 364,315.64 Completed 2018-11-26 2019-08-19 2018-12-17 2019-10-11 2019-01-30 2020-01-06 2019-02-27 2020-03-02 2019-03-29 2020-03-30 2019-05-03 2020-04-09 2019-06-07 2020-07-21 2019-12-04 2022-06-29 d mobilization for owner upgr vices in the coastal region ( on ade of urban household sanit US$176 of w hich IDA-SUF U ation facilities(Ukunda,Kwale S$160 million). and Kombani) KE-KWAWASCO-105286-CS- Component 1: Rehabilitation QCBS / consultancy services and expansion of urban wat for the design review and co er supply and sanitation ser Quality And Cost- IDA / 60300 Post Open - National 280,000.00 454,364.90 Signed 2019-04-15 2021-02-06 2019-05-06 2021-02-26 2019-06-19 2021-08-24 2019-07-17 2021-09-27 2019-08-16 2021-10-12 2019-09-20 2021-10-25 2019-10-25 2021-11-18 2020-10-24 nstruction supervision for the vices in the coastal region ( Based Selection immediate urgent sanitation US$176 of w hich IDA-SUF U works for Ukunda and Kwale S$160 million). towns KE-KWAWASCO-161466-CS- Component 1: Rehabilitation CDS / consultancy for constr and expansion of urban wat Quality And Cost- Open - Internationa uction supervision for the pro IDA / 60300 er supply and sanitation ser Prior 1,200,000.00 615,252.02 Signed 2020-05-15 2020-06-26 2020-06-05 2020-08-20 2020-07-19 2021-02-16 2020-08-16 2021-03-25 2020-09-15 2021-06-26 2020-10-20 2021-08-31 2020-11-24 2021-09-08 2023-01-13 Based Selection l posed Ukunda urban water s vices in the coastal region ( upply improvement works US$176 of w hich IDA-SUF U S$160 million). INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-KWAWASCO-74605-CS-IN Component 1: Rehabilitation DV / Consultancy services for and expansion of urban wat the design review and constr er supply and sanitation ser Individual Consult IDA / 60300 Prior Limited 180,000.00 0.00 Canceled 2018-10-08 2018-10-13 2018-11-03 2018-12-08 2019-06-06 uction supervision for the im vices in the coastal region ( ant Selection mediate urgent sanitation wo US$176 of w hich IDA-SUF U rks for Ukunda and Kwale to S$160 million). wns Component 1: Rehabilitation KE-KWAWASCO-188574-CS-I and expansion of urban wat Individual Consult NDV / Hiring of a consultant P IDA / 60300 er supply and sanitation ser Post Open 39,600.00 36,032.75 Signed 2020-11-11 2021-02-09 2020-12-30 2021-07-02 2021-01-20 2021-07-26 2021-02-24 2021-09-01 2021-12-21 ant Selection roject Engineer vices in the coastal region ( US$176 of w hich IDA-SUF U S$160 million). Component 1: Rehabilitation KE-KWAWASCO-225728-CS-I and expansion of urban wat NDV / Hiring of an environm Individual Consult IDA / 60300 er supply and sanitation ser Post Open 27,000.00 49,157.93 Signed 2021-04-02 2021-04-26 2021-05-21 2021-08-04 2021-06-11 2021-09-06 2021-07-16 2021-09-07 2022-10-09 ent and social safe guards sp ant Selection vices in the coastal region ( ecialist US$176 of w hich IDA-SUF U S$160 million). Page 2 AGRO-CLIMATIC RESILIENCE IN SEMI -ARID LANDSCAPES (ACReSAL) PROJECT PROCUREMENT STRATEGY FOR DEVELOPMENT 1 PROJECT OVERVIEW Country: NIGERIA Full Project Name: AGRO-CLIMATIC RESILIENCE IN SEMI -ARID LANDSCAPES (ACReSAL) Total Finance ($): USD 700 MILLION Project Number: P175237 Summary of Project The Project Development Objective (PDO) is to increase the adoption of climate resilient landscape Development Objectives management practices and enhance livelihoods in targeted arid/semi-arid watersheds in Northern Nigeria. PROJECT COST COMPONENTS ESTMATE OBJECTIVES OF EACH (USD) COMPONENT Component A: 299.6m This component aims to prepare and Desertification Control implement investments to arrest and Landscape desertification and improve the Management sustainable productivity of land in targeted watersheds (about 1,000,000 ha area of degraded and desert landscapes out of 4,000,000 (25%) Government program). Component B: 293.4m This component aims to support Community communities with improved capacity Livelihoods and and investments to improve Resilience sustainable livelihoods. Component C: 107.6m This component aims to strengthen Institutional capacities of institutions at various levels (e.g., national, selected states) Strengthening and to modernize their work for the Project Management longer-term on integrated multi- sectoral planning, information management, and building systems for improving land and water management and sustainable agricultural productivity in northern Nigeria. Component D: 0m This will finance a Contingency Contingency Emergency Response Component Emergency Response (CERC) for landscape and community Components (CERC): resilience in response to extreme weather, land movement events and other emergencies. LIST OF PROCUREMENT ACTIVITIES The project is designed as framework project and therefore investments and the participating states (the major investments will be implemented by the participating states) are not fully known yet. In the table below are the activities that already known, and implementation can commence immediately. The PPSD will be updated during implementation as the investments and participating states become more defined. These investments include gully erosion control, rehabilitation of irrigation and dams. S/N ACTIVITIES COST CUMMULATIVE % of ESTIMATE COST TOTAL (USD) ESTIMATE COST (USD) ESTIMATE 1 Technical assistance for 10,000,000 10,000,000 28% landscape restoration services 2 Extension services technical 9,900,000 19,900,000 57% assistance 3 Implementation support 9,500,000 29,400,000 84% consultancy 4 Long-term framework and 2,500,000 31,900,000 91% policy support 5 Development of strategic 1,600,000 33,500,000 95% catchment plan 4 Monitoring Information 600,000 34,100,000 97% System (MIS) and maintenances 5 Others ICT Equipment and 400,000 34,500,000 98% connectivity, cloud services, others general services Desktops & Laptops 300,000 34,800,000 99% Data collection and analysis at 168,000 34,968,000 100% State/federal Level Production of Manuals (PIM ) 90,000 35,058,000 100% Design and hosting of 56,000 35,114,000 100% interactive website TOTAL 35,114,000 Strategic Assessment of Operating Context and Borrower Capability Operational Context Nigeria experiences a diverse climate that ranges from arid in the north to tropical in much of the country and is listed among the countries most exposed to climate risks. The country faces a high water-scarcity hazard level, with droughts expected to occur on average every five years, with potential increased frequency due to climate change. Focusing on drylands management, ACReSAL will be implemented in the states of northern Nigeria. The agricultural sector is the major economic driver of northern Nigeria. Many projects and initiatives have been undertaken in northern Nigeria over the past decades to combat the growing crisis of desertification. The FGN is thus increasingly moving toward an integrated and multisectoral approach to address the challenges of dryland management. (a) Governance Aspects: There are security challenges in almost all the states in the northern Nigeria where the project will be implemented. The Government of Nigeria is making some progress in addressing these security challenges. The security situation may reduce the interest of major players, especially for Component A to participate in the procurement process and those that choose to participate may add a premium to the bid prices to take of the additional security arrangement they want to put in place during contract execution in case of an award. (b) Economic Aspects: Nigeria has just come out of an economic recession because of CIVID 19 pandemic and a fall in crude oil price in the world market. The country is contending with high inflation and exchange rate volatility. The high inflation and exchange rate volatility has made the prices of the major construction materials such as iron rods and cement to be volatile. Substantial proportion of the Component consist of civil works with locally available inputs (labour and materials). The effect of the exchange volatility will be minimal since bidders expecting to incur expenditures in other currencies for inputs to the Works supplied from outside the country can quote for such inputs in up to three different foreign currencies in their bids. Serious bottleneck exists in the main seaport where goods to be imported from abroad will be discharged. This has led to delay in the custom clearance of good from the port with the resulting demurrage payment and delay in contract execution. The government is working on policy that will remove the bottlenecks. (c) Sustainability Aspects: The government environmental and social standards requires that Environmental and Social Impact Assessment be carried on all major works project before the commencement of such works. ESIA will apply to this project and will be reflected in the solicitation documents and contracts for civil works under the project. (d) Technological Aspects: Kaduna, Niger, Kogi, Jigawa, Borno, Kano and Gombe States that will likely participate in the project have an e-Procurement system which is being used in some of the MDAs. Sokoto State is in the final stages of their e- Procurement implementation. The systems so deployed will be used for procurement under the project. This will further improve value for money, transparency, economy, efficiency, effectiveness, integrity, and openness of procurement process under the project. The country is covered substantially by GSM, part of which is through extensive fiber optic cabling leading to increased networking and internet availability. The availability of reasonable internet access will facilitate the use of the World Bank Systematic Tracking of Exchanges in Procurement (STEP) which is mandatory requirement in the processing all procurement activities under the World Bank Procurement Regulations. Key Conclusions: The security challenges in the country especially in the northern states that will participate in the project may reduce the participation of foreign firms and firms from other parts of the in the procurement process for the project. The current high inflation and exchange rate volatility in the country will affect the costing of the various procurement packages in the project. The use of eProcurement for by the participating states and the FPMU will improve value for money, transparency, economy, efficiency, effectiveness, integrity, and openness of procurement process under the project Assessment of Borrower previous Experience, Capability and Project Implementation Unit (PIU) The project will be implemented using the existing NEWMAP PMUs at both Federal and State levels that are implementing NEWMAP and the NEWMAP AF that will close on June 30, 2022. The implementation arrangement is similar to that of NEWMAP. Each state will be responsible for the procurement of its own activities including contract management and administration. The FPMU and the states that are implementing NEWMAP have experience in World Bank Procurement Regulations. The procurement officers have received sufficient training in procurement under World Bank funded project. The gaps that were observed in the implementation of NEWMAP especially in contract management will be addressed under ACReSAL. Training will be provided on contract management, application of price adjustment, contract monitoring and supervision as soon as the project is effective. Market Analysis The summary of the procurement activities under the project are as follows • Civil works: o gully erosion control, o flood and sedimentation control, o construction of firebreaks, o rehabilitation and construction of small dams, o small scale irrigation infrastructure, o small buildings There are several players both national and international in the marketplace for these activities. International open competitive procurement approach will be used for high value, high risk gully erosion control and construction of dams and firebreaks. The other low value, low risk procurement will follow national open competition or limited competition as may be appropriate. • Goods: o fire control equipment, o vehicles, o farm inputs (seeds, fertilizers), o post-production equipment, o computers, furniture They are locally available and be supplied by several suppliers and the procurement approach will be national open/limited completion as may be appropriate. The approach for the procurement of farm inputs (seeds, fertilizer) will limited competition between the well-known producers/suppliers of these goods. • Consulting services: The major consulting services includes engineering design and supervision of the major civil works like gully erosion control and rehabilitation of dams. The firms that offer this service are available in the local and international markets. Due to the criticality of this consulting assignment to the overall delivery of the major works contracts, the procurement will be designed to attract best consulting firms to express interest in this assignment. Procurement Risk Analysis Market Risk Description of Risk Owner /Contract Description Mitigation Title Description Construction of Designs may no A consultant will be State PMU and shovel ready longer be valid by the hired to update the World Bank gully erosion contracts during design before the control site contract execution commencement of the procurement process Expansion of the Provisions for State PMUs gullies between physical bidding and contract contingencies will signature made in the signed contract. Expansion of gullies Proper drainage on Contractor during construction the site must be due to poor drainage maintained during resulting from construction and the construction of the Contractor shall be works held responsible for any flood damage to life and properties due to his work in this Contract. The Contractor shall allow in his rates, inter alia, for all costs to maintain or divert flow in drains, ditches, open channels and watercourses during construction and other drainage work. No claims for additional payment will be considered in this regard. Construction Poor supervision of supervision the works contracts consultancy Procurement of Delay in port All the necessary PMUs goods to be clearance documentation and imported from waivers will be outside the processed speedily country (delfino ploughs, tractors, etc) General (for all High inflation and Price adjustment to PMUs contracts) exchange rate applied to most even volatility if they duration is less than 18 months. Procurement Objective • To a minimum of 8 qualified consultants to participate in the selection process for the engineering design and supervision consultancy for the major works contracts. • To take advantage of the dry season for the construction contracts by aligning the commencement of the works with the dry season in the project areas. • Value for money and integrity in the procurement process using electronic procurement system. • To have not less than six qualified firms submit bids for the major works contracts. • Procurement Approach Options and Recommendation The following will be a draft zero of the procurement approach options and recommendations. This is because the major investments are not yet known. This section will be updated once the investments are finalized. • Contract and Estimated Cost: Landscape investments (many packages)– USD236 million • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Specifications Conformance Details design for shovel- ready investments from NEWMAP are available. Engineering firm will be hired to provide detail designs for other investments. Sustainability No All the safeguard studies Requirements will be carried out separately and cost implications will be included in the bidding document. Contract Type Traditional Pricing and costing Schedule of mechanism Rates/Admeasurement Price Adjustments None/Percentage Form of Contract (Terms and Conditions) Selection Method Request for Bids (RFB) Selection Arrangement N/A Market Approach Open International/National Pre/Post Qualification Post Evaluation Selection Least Cost Based Method Selection (LCS) Evaluation of Costs Adjusted Bid Price Domestic Preference No Rated Criteria N/A • Contract and Estimated Cost: Development of strategic catchment plan – USD1,600,000 • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Sustainability N/A Requirements Contract Type Traditional Pricing and costing Lump Sum mechanism Price Adjustments None Form of Contract (Terms N/A and Conditions) Selection Method Request for Proposals (RFP) Selection Arrangement N/A Market Approach Open International Pre/Post Qualification Pre-Qualification Evaluation Selection Quality Cost Based Method Selection (QCBS) Evaluation of Costs N/A Domestic Preference N/A Rated Criteria Mandatory • Contract and Estimated Cost: Long-term framework and policy support – USD2,500,000 • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Sustainability N/A Requirements Contract Type Traditional Pricing and costing Time and Materials mechanism Price Adjustments ????? Form of Contract (Terms ????? and Conditions) Selection Method Request for Proposals (RFP) Selection Arrangement N/A Market Approach Open International, Two Envelopes Pre/Post Qualification Pre-Qualification Evaluation Selection Quality Cost Based Method Selection (QCBS) Evaluation of Costs Adjusted Bid Price Domestic Preference No Rated Criteria • Specific experience • Methodology and workplan • Qualification and experience of key experts • Contract and Estimated Cost: Implementation support consultancy – USD9,900,000 • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Sustainability N/A Requirements Contract Type Traditional Pricing and costing Lump Sum mechanism Price Adjustments None Form of Contract (Terms N/A and Conditions) Selection Method Request for Proposals (RFP) Selection Arrangement N/A Market Approach Open International Pre/Post Qualification Pre-Qualification Evaluation Selection Quality Cost Based Method Selection (QCBS) Evaluation of Costs N/A Domestic Preference N/A Rated Criteria Mandatory • Contract and Estimated Cost: Development of strategic catchment plan – USD1,600,000 • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Sustainability N/A Requirements Contract Type Traditional Pricing and costing Lump Sum mechanism Price Adjustments None Form of Contract (Terms and Conditions) Selection Method Request for Proposals (RFP) Selection Arrangement N/A Market Approach Open International, Two Envelopes Pre/Post Qualification Pre-Qualification Evaluation Selection Quality Cost Based Method Selection (QCBS) Evaluation of Costs Adjusted Bid Price Domestic Preference No Rated Criteria • Specific experience • Methodology and workplan • Qualification and experience of key experts Preferred arrangement for low value, low activities Contract Category Estimated cost Procurement Arrangement and Method Desktops & Goods 300,000 Open National Laptops Others ICT Goods 400,000 Open National Equipment and connectivity, cloud services, others general services Production of Goods 90,000 Limited RFQ Manuals (PIM Monitoring Consultancy 600,000 Open National Information System (MIS) and maintenances Design and hosting Consultancy 56,000 Limited CQS of interactive website Data collection and Consultancy 168,000 Limited CQS analysis at State/federal Level Summary of PPSD to be inform the Bank’s preparation of the PAD The project is designed as framework project and therefore investments and the participating states (the major investments will be implemented by the participating states) are not fully known yet. The security challenges in the country especially in the northern states that will participate in the project may reduce the participation of foreign firms and firms from other parts of the in the procurement process for the project. The current high inflation and exchange rate volatility in the country will affect the costing of the various procurement packages in the project. The use of eProcurement for by the participating states and the FPMU will improve value for money, transparency, economy, efficiency, effectiveness, integrity, and openness of procurement process under the project. The FPMU and the states that are implementing NEWMAP have experience in World Bank Procurement Regulations. The procurement officers have received sufficient training in procurement under World Bank funded project. The gaps that were observed in the implementation of NEWMAP especially in contract management will be addressed under ACReSAL. A sufficiently large numbers of firms are available locally and international for most of the procurement packages under the project, therefore competitive procurement can readily be used to achieved value for value during procurement implementation. The design of the gully erosion sites already cleared under NEWMAP that will be transferred to project will be updated prior to the launching of the procurement processes for the construction of such sites. The PPSD will be regularly updated as there are clear pictures on the participating states and the procurement activities that will be implemented by the states and the FPMU. Contract Estimat Bank Procurement Selecti Evaluati Title, ed Cost Oversig Approach/Competi on on Description US$ and ht tion Method Method and Risk Category Rating Implementati 9,500,00 Prior International SPD Rated on support0 (RFP) Criteria consultancy Substanti (VfM) al Long-term 2.500,00 Prior International SPD Rated framework 0, (RFP) Criteria and policy Substanti (VfM) support al Development 1,600,00 Prior International SPD Rated of strategic 0, (RFP) Criteria catchment Substanti (VfM) plan al Monitoring 600,000, Post International SPD Rated Information Moderate (RFP) Criteria System (MIS) (VfM) and maintenance s Others ICT 400,000, Post National RFB Lowest Equipment Moderate Evaluated and Cost connectivity, cloud services, others general services Desktops & 300,000, Post National RFB Lowest Laptops Low Evaluated Cost Data 168,000, Post National CQS Negotiati collection Moderate on and analysis at State/federal Level Production of 90,000, Post National RFQ Lowest Manuals Low Evaluated (PIM) Design and 56,000, Post National CQS Negotiati hosting of Moderate on interactive website PROCUREMENT Nigeria : Agro-Climatic Resilience in Semi-Arid Landscapes (ACReSAL) PLAN General Information Country: Nigeria 2023-01-05 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175237 GPN Date: Project Name: Agro-Climatic Resilience in Semi-Arid Landscapes (ACReSAL) Loan / Credit No: IDA / 70150 Benue State ACReSAL Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure NG-BENUE STATE ACRESAL- ment Document - 338114-CW-RFB / Rehabilitati Component A: Dryland Mana Single Stage - One E Pending Imp 2023-07-2 IDA / 70150 Post Request for Bids Open - National 1 Envelope proce 150,000.00 0.00 2023-03-16 2023-03-21 2023-04-04 2023-04-11 2023-04-25 on/ Renovation of Benue ACR gement nvelope lementation 4 ss (Non Bank-SPD eSAL office complex ) NG-BENUE STATE ACRESAL- Component C: Institutional S Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-10-1 360123-CW-RFQ / Rehabilitat IDA / 70150 trengthening and Project Ma Post Limited tions (Non Bank-S 150,000.00 0.00 2023-06-16 2023-07-21 tions nvelope lementation 9 ion/ Renovation of Bnu ACRe nagement PD) SAL Office NG-BENUE STATE ACRESAL- 363441-CW-RFQ / Establishm Request for Quota Component A: Dryland Mana Request for Quota Single Stage - One E Under Imple 2023-12-2 ent of Fully Functional Plant IDA / 70150 Post Limited tions (Non Bank-S 100,000.00 0.00 2023-09-07 2023-09-29 gement tions nvelope mentation 8 Nurseries and Green Houses PD) in 3 LGAs (Otukpo, Makurdi a nd Vandeikya) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-BENUE STATE ACRESAL- Component C: Institutional S 337999-GO-RFQ / Procureme Request for Quota Single Stage - One E Under Imple IDA / 70150 trengthening and Project Ma Post Limited 200,000.00 0.00 2023-03-23 2023-03-31 2023-05-11 2023-07-10 nt of 1No. operational Vehicl tions nvelope mentation nagement e and 1No. 14-Seater Bus for project activities NG-BENUE STATE ACRESAL- Component C: Institutional S 338019-GO-RFQ / Printing of Request for Quota Single Stage - One E Under Imple IDA / 70150 trengthening and Project Ma Post Limited 35,000.00 0.00 2023-03-14 2023-04-12 2023-04-18 2023-06-17 IEC materials (T-shirts, Flyers tions nvelope mentation nagement , Newsletters, Jingles, etc) NG-BENUE STATE ACRESAL- Component C: Institutional S 338221-GO-RFQ / supply and Request for Quota Single Stage - One E Under Imple IDA / 70150 trengthening and Project Ma Post Limited 100,000.00 0.00 2023-04-04 2023-05-02 2023-05-23 2023-07-22 installation of solar power sy tions nvelope mentation nagement stem for Benue ACReSAL offi ce NG-BENUE STATE ACRESAL- 309342-GO-RFQ / Procureme Component C: Institutional S nt of GRM Tools (Compliant b Request for Quota Single Stage - One E Under Imple IDA / 70150 trengthening and Project Ma Post Limited 100,000.00 0.00 2023-02-13 2023-03-27 2023-03-27 2023-04-26 ox, Toll free lines and Grieva tions nvelope mentation nagement nce log book, Softwares/App, etc) and Refreshers Trainnin g for GRM Officer NG-BENUE STATE ACRESAL- 309470-GO-RFB / Establishe ment of Data Management C entre including GIS and Rem Component C: Institutional S Single Stage - One E Under Imple ote Sensing Laboratory, Sur IDA / 70150 trengthening and Project Ma Post Request for Bids Open - National 250,000.00 0.00 2023-03-16 2023-03-30 2023-03-23 2023-04-25 2023-04-06 2023-04-20 2023-05-11 2023-05-17 nvelope mentation vey Equipment, ICT/MIS Equi nagement pment including Laptops, Ph oto Copying Machines, Video Conferencing tools, Projector s, Digital Cameras, etc NG-BENUE STATE ACRESAL- 309452-GO-RFB / Renewable Energy Use Scheme; Provisio n of 500 No. Solar Powered Ir Component B: Community Cl Single Stage - One E Pending Impl IDA / 70150 Post Request for Bids Open - National 220,000.00 0.00 2023-03-30 2023-04-04 2023-04-18 2023-05-02 2023-05-23 2023-08-21 rigation Pumps for Small Scal imate Resilience nvelope ementation e Farmers/Interest Groups in Communities (Apa, Otukpo, Makurdi, Gboko, Logo and Va ndeikya, LGAs) NG-BENUE STATE ACRESAL- Component C: Institutional S 341441-GO-RFQ / Supply and Request for Quota Single Stage - One E Under Imple IDA / 70150 trengthening and Project Ma Post Limited 100,000.00 0.00 2023-04-03 2023-05-02 2023-05-22 2023-07-21 Installation of Solar Power sy tions nvelope mentation nagement stem for the SPMU NG-BENUE STATE ACRESAL- 363183-GO-RFB / Provision of Component C: Institutional S Single Stage - One E Under Imple 6 No. Solar Powered Borehol IDA / 70150 trengthening and Project Ma Post Request for Bids Open - National 300,000.00 0.00 2023-08-16 2023-05-30 2023-08-18 2023-06-25 2023-09-15 2023-09-29 2023-10-16 2024-01-17 nvelope mentation es for Communities in 3 LGAs nagement receiving Interventions NG-BENUE STATE ACRESAL- 363476-GO-RFQ / PROCUREM Component C: Institutional S Request for Quota Single Stage - One E Under Imple ENT OF ICT EQUIPMENTS. LA IDA / 70150 trengthening and Project Ma Post Limited 95,000.00 0.00 2023-07-03 2023-06-01 2023-08-09 2023-09-08 tions nvelope mentation PTOP, DESKTOPS, PRINTERS, nagement SCANNERS, PHOTCOPIERS ET C NG-BENUE STATE ACRESAL- Component C: Institutional S 363483-GO-RFQ / PROCUREM Request for Quota Single Stage - One E Under Imple IDA / 70150 trengthening and Project Ma Post Limited 86,500.00 0.00 2023-09-04 2023-06-01 2023-09-25 2023-10-26 ENT AND INSTALLATION OF O tions nvelope mentation nagement FFICE FURNITURE FOR BENU E ACReSAL PIU NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Page 1 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-BENUE STATE ACRESAL- 309468-CS-CQS / Engage a C onsultant to Assess Needs fo r Efficient Energy Cooking S Component B: Community Cl Consultant Qualifi Pending Impleme ources, Solar Powered Boreh IDA / 70150 Post Open - National 100,000.00 0.00 2023-03-15 2023-03-22 2023-04-19 2023-04-20 2023-05-04 2023-07-03 imate Resilience cation Selection ntation oles and Solar Powered Irriga tion Pumps for Distribution a nd Use in Communities (Apa , Otukpo, Makurdi, Gboko, Lo go and Vandeikya, LGAs) NG-BENUE STATE ACRESAL- 309471-CS-CQS / Engageme nt of Consultant for the Desig Component A: Dryland Mana Consultant Qualifi Pending Impleme n of Agro-Forestry Models, 2, IDA / 70150 Post Open - National 120,000.00 0.00 2023-03-27 2023-04-10 2023-05-01 2023-05-08 2023-05-22 2023-08-20 gement cation Selection ntation 000HAs; 333.33HAs each in 6 LGAs (Oju, Otukpo, Makurdi , Vandeikya, Gboko and Gwer West ) NG-BENUE STATE ACRESAL- 309349-CS-CQS / Consultanc y for Conducting Monitoring Component B: Community Cl Consultant Qualifi Pending Impleme and Evaluation Baseline Stud IDA / 70150 Post Open - National 100,000.00 0.00 2023-02-16 2023-02-23 2023-03-16 2023-03-23 2023-04-13 2023-06-12 imate Resilience cation Selection ntation ies including use of GIS Surv ey and Mapping of the Water sheds in the Initial Interventi on Sites. NG-BENUE STATE ACRESAL- 338028-CS-CQS / Engageme nt of a Consultant to Design Component A: Dryland Mana Quality And Cost- Pending Impleme IDA / 70150 Post Open - National 450,000.00 0.00 2023-06-23 2023-07-14 2023-08-25 2023-10-06 2023-11-06 2023-12-04 2024-12-19 2025-09-18 Stormwater and Gully Erosio gement Based Selection ntation n Control structures in Ogbad ibo, Gboko, Vandeikya, Kons hisha, Makurdi and Otukpo L GAs INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 PROCUREMENT PLAN (Textual Part) Project information: EL Salvador Growing Up and Learning Together: Comprehensive Early Childhood Development P171316 Project Implementation agency: Ministerio de Educación, Ciencia y Tecnología Date of the Procurement Plan: December 6, 2021 Period covered by this Procurement Plan: December 6, 2021 – December 31, 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. PROCUREMENT El Salvador : Growing Up and Learning Together: Comprehensive Early Childhood Development in El Salvador PLAN General Information Country: El Salvador Bank’s Approval Date of the Original Procurement Plan: 2021-12-16 Revised Plan Date(s): (comma delineated, leave blank if 2023-05-26 none) Project ID: P171316 GPN Date: Project Name: Growing Up and Learning Together: Comprehensive Early Childhood Development in El Salvador Loan / Credit No: IBRD / 90670 Ministry of Education Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned 0-3.3.1.1. / Rehabilitación de Request for Bids - 200 centros educativos para Upgrading ECCE Physical Le Single Stage - One E Small Works SPD Pending Imp 2024-03-1 IBRD / 90670 Post Request for Bids Open - National 7,009,627.74 0.00 2023-04-11 2023-04-16 2023-05-28 2023-06-27 2023-08-01 satisfacer las necesidades rel arning Environments nvelope (1 envelope proce lementation 1 ativas al acceso al agua, san ss) eamiento e higiene O-3.3.1.1.1. / Rehabilitación Request for Bids - de 283 centros educativos pa Upgrading ECCE Physical Le Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2024-07-0 ra satisfacer las necesidades IBRD / 90670 Post Request for Bids 9,918,623.26 0.00 2023-09-01 2023-09-06 2023-10-18 2023-11-17 2023-12-22 arning Environments l nvelope (1 envelope proce lementation 1 relativas al acceso al agua, s ss) aneamiento e higiene O-3.1.1.1. / Mejoramiento de Request for Bids - infraestructura de 40 centros Upgrading ECCE Physical Le Open - Internationa Single Stage - One E Small Works SPD 37,581,178.8 Pending Imp 2024-08-0 IBRD / 90670 Prior Request for Bids 0.00 2023-08-18 2023-08-23 2023-10-04 2023-11-03 2023-12-08 educativos públicos que atie arning Environments l nvelope (1 envelope proce 0 lementation 4 nden primera infancia (Grupo ss) 1) 0-3.1.1.2 / Mejoramiento de i Request for Bids - nfraestructura de 31 centros Upgrading ECCE Physical Le Open - Internationa Single Stage - One E Small Works SPD 29,125,413.2 Pending Imp 2024-04-1 IBRD / 90670 Prior Request for Bids 0.00 2023-06-28 2023-07-03 2023-08-14 2023-09-13 2023-10-18 educativos públicos que atie arning Environments l nvelope (1 envelope proce 6 lementation 5 nden primera infancia (Grupo ss) 2) O-3.1.1.3 / Mejoramiento de Request for Bids - infraestructura de 40 centros Upgrading ECCE Physical Le Open - Internationa Single Stage - One E Small Works SPD 39,581,178.4 Pending Imp 2024-03-0 IBRD / 90670 Prior Request for Bids 0.00 2023-05-19 2023-05-24 2023-07-05 2023-08-04 2023-09-08 educativos públicos que atie arning Environments l nvelope (1 envelope proce 0 lementation 6 nden primera infancia (Grupo ss) 3) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual B-1.2.5 / Dotar recursos didá Ensuring ECCE Structural Qu Open - Internationa Single Stage - One E Pending Impl cticos para bibliotecas de Ce IBRD / 90670 ality Standards and Curricul Prior Request for Bids 5,500,000.00 0.00 2022-12-30 2023-01-04 2023-02-15 2023-03-17 2023-04-21 2023-11-30 l nvelope ementation ntros Educativos Públicos de um Nationwide PI. (Kit de libros) B-1.2.5.1 / Dotar de recursos didácticos para la implement Ensuring ECCE Structural Qu ación del currículo (Kit de ani Open - Internationa Single Stage - One E Pending Impl IBRD / 90670 ality Standards and Curricul Prior Request for Bids 20,936,212.00 0.00 2023-07-03 2023-07-08 2023-08-19 2023-09-18 2023-10-23 2024-06-30 males y objetos, motricidad, l nvelope ementation um Nationwide educación fisica, material se nsorial, expresión musical) B-01.2.6.3 / Material didáctic Ensuring ECCE Structural Qu Request for Quota Single Stage - One E Pending Impl o, gastable y lúdico, para las IBRD / 90670 ality Standards and Curricul Post Open - National 240,000.00 0.00 2023-01-21 2023-03-18 2024-12-21 tions nvelope ementation cunas Nahuath para estudian um Nationwide tes 4-7 años B-1.2.2. / Adquisición de Mat Ensuring ECCE Structural Qu Request for Quota Single Stage - One E Pending Impl eriales para impresión en sist IBRD / 90670 ality Standards and Curricul Post Open - National 100,000.00 0.00 2023-05-07 2023-07-02 2023-12-02 tions nvelope ementation ema braile del currículo ajust um Nationwide ado. B-03.2.3.1 / Dotar de mobilia rio escolar (para centros edu Upgrading ECCE Physical Le Open - Internationa Single Stage - One E Pending Impl IBRD / 90670 Prior Request for Bids 5,928,000.00 0.00 2023-06-01 2023-06-06 2023-07-18 2023-08-17 2023-09-21 2024-11-21 cativos a intervenir PI) (1er. arning Environments l nvelope ementation Grupo) (2do. Grupo) (3er. Gr upo) B.3.3.2.1.2.3 / Adquisición d e equipo para nutrición escol Upgrading ECCE Physical Le Request for Quota Single Stage - One E Pending Impl ar para reducir condiciones d IBRD / 90670 Post Open - National 375,000.00 0.00 2023-07-08 2023-09-02 2024-10-01 arning Environments tions nvelope ementation e vulnerabilidad en los centr os educativos (1er grupo ) (2 do grupo) (3er grupo) B-04.1.7.12 / Adquisición de equipo informático, licencias, software, central telefónica Institutional Strengthening f y equipo de oficina para la Di Request for Quota Single Stage - One E Pending Impl IBRD / 90670 or the Management of the E Post Open - National 181,250.00 0.00 2022-12-20 2023-02-15 2023-06-30 rección nacional de Evaluació tions nvelope ementation ducation Sector n Educativa y para las unidad es ejecutoras del proyecto (l aptop y equipo de video p/co nferencia) B-4.1.7.13 Y 4.2.4.1.1 / Adq uisición de 10 Pick Up doble Institutional Strengthening f cabina, 4 para la Dirección N Request for Quota Single Stage - One E Pending Impl IBRD / 90670 or the Management of the E Post Open - National 350,730.00 0.00 2023-11-06 2024-01-18 2024-05-15 acional de Evaluación Educat tions nvelope ementation ducation Sector iva y 6 para uso de la Direc ción de Infraestructura y Am bientes Educativos B-04.2.4.1.1 / Adquisición de Institutional Strengthening f Request for Quota Single Stage - One E 6 Pick Up doble cabina para IBRD / 90670 or the Management of the E Post Open - National 194,780.00 0.00 Canceled 2022-02-03 2022-03-31 2022-09-27 tions nvelope uso del proyecto. ducation Sector B-04.2.4.1.4 / Adquisicion de 80 Licencias de Project; 28 Institutional Strengthening f Request for Quota Single Stage - One E Pending Impl de Autocad para 5 años, par IBRD / 90670 or the Management of the E Post Open - National 294,624.00 0.00 2022-12-06 2023-01-31 2023-05-31 tions nvelope ementation a ser utilizadas por las unida ducation Sector des involucradas en la gestió n del proyecto B-4.2.4.1.4 / Reactivación de Institutional Strengthening f Pending Impl Mantenimiento de Licencia d IBRD / 90670 or the Management of the E Post Direct Selection Direct - National 1,994.00 0.00 2022-12-01 2022-12-06 2023-01-10 2023-03-15 ementation e ArcGIS for Desktop Basic. ducation Sector Page 1 B-2.1.5.7 / Adquisición de eq Strengthening Professional Open - Internationa Single Stage - One E Pending Impl uipo informático para Docent IBRD / 90670 Development of Teachers an Prior Request for Bids 2,800,000.00 0.00 2023-02-15 2023-02-20 2023-04-03 2023-05-03 2023-06-07 2024-02-29 l nvelope ementation es (8000 laptop) d Principals at ECCE Official Centers GO-04.2.4.1.2 / Adquisicion Institutional Strengthening f de equipo informatico para la Request for Quota Single Stage - One E Under Imple IBRD / 90670 or the Management of the E Post Open - National 184,500.00 0.00 2022-12-20 2023-04-11 2023-02-14 2023-06-30 s Unidades Ejecutoras del Pro tions nvelope mentation ducation Sector yecto (laptop y equipo de vid eo para conferencia) B-1.2.7.1 / Adquisición de so Ensuring ECCE Structural Qu Request for Quota Single Stage - One E ftware educativo para desarr IBRD / 90670 ality Standards and Curricul Post Open - National 5,000.00 0.00 Canceled 2022-02-20 2022-04-17 2022-08-15 tions nvelope ollar la conciencia fonológica um Nationwide B-04.2.4.1.6 / Adquisicion de Institutional Strengthening f Request for Quota Single Stage - One E Pending Impl IBM SPSS Statistics. Base v2 IBRD / 90670 or the Management of the E Post Open - National 29,200.00 0.00 2022-12-17 2023-02-11 2023-06-11 tions nvelope ementation 6 (4 licencias individuales) ducation Sector B-2.1.4.3; 2.1.4.4 ; 2.1.5.4; 2 .2.4.2.3 / Adquisición de mat eriales (audiovisuales, impre Strengthening Professional sos, kits, etc.) para la formaci Development of Teachers an Open - Internationa Single Stage - One E Pending Impl IBRD / 90670 Prior Request for Bids 17,619,400.00 0.00 2023-02-06 2023-02-11 2023-03-25 2023-04-24 2023-05-29 2024-09-03 ón docente ECPI e incluye dis d Principals at ECCE Official l nvelope ementation eño y elaboración de 8 video Centers s, 8300 libros dossieres, 830 0 kits didácticos, 8300 kits lú dicos y para la formación dir ectiva. B-04.2.6.2 / Adquisición de Institutional Strengthening f Request for Quota Single Stage - One E Pending Impl materiales (extensiones eléct IBRD / 90670 or the Management of the E Post Open - National 19,995.00 0.00 2022-12-17 2023-02-11 2023-06-30 tions nvelope ementation ricas, USB, DVD y material g ducation Sector astable GO-04.2.4.1.3 / Adquisición de escritorios modulares y sil Institutional Strengthening f Request for Quota Single Stage - One E las ergonómicas, así como A IBRD / 90670 or the Management of the E Post Open - National 102,352.00 0.00 Canceled 2022-02-20 2022-04-17 2022-09-14 tions nvelope dquisición de material didácti ducation Sector co y mobiliario escolar ( 4.2. 6.1) B-4-2-4-1-3 / Adquisición de sillas ergonómicas y escritori os modulares para el person Institutional Strengthening f Request for Quota Single Stage - One E Under Imple al técnico de la Dirección de IBRD / 90670 or the Management of the E Post Open - National 51,352.00 0.00 2023-02-18 2023-04-11 2023-04-15 2023-07-14 tions nvelope mentation Educación de Primera Infanci ducation Sector a en el Marco de la Política N acional de apoyo al Desarroll o temprano “CRECER JUNTOS ” NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SNC-1.1.2.1 / Servicios de I mpresión del sistema de cer Ensuring ECCE Structural Qu Request for Quota Single Stage - One E Pending Impl tificación y la normativa de l IBRD / 90670 ality Standards and Curricul Post Open - National 150,000.00 0.00 2023-04-08 2023-06-03 2023-10-16 tions nvelope ementation os estándares estructurales um Nationwide de calidad a centros educativ os públicos y privados SNC-1.1.2.2 / Servicios de C Ensuring ECCE Structural Qu apacitación a los equipos De Single Stage - One E Pending Impl IBRD / 90670 ality Standards and Curricul Post Request for Bids Open - National 480,000.00 0.00 2023-04-03 2023-04-08 2023-05-20 2023-06-19 2023-07-24 2023-11-03 partamentales y personal ext nvelope ementation um Nationwide erno (ONGS incluye logística ) SNC-1.2.2 .2 / Servicio de im Ensuring ECCE Structural Qu Single Stage - One E Pending Impl presión de documentos currí IBRD / 90670 ality Standards and Curricul Post Request for Bids Open - National 600,000.00 0.00 2024-06-03 2024-06-08 2024-07-20 2024-08-19 2024-09-23 2025-04-02 nvelope ementation culo ajustado um Nationwide SNC-1.2.3 / Servicio de Logís Ensuring ECCE Structural Qu tica para eventos regionales Request for Quota Single Stage - One E Pending Impl IBRD / 90670 ality Standards and Curricul Post Open - National 255,000.00 0.00 2024-05-12 2024-07-07 2025-06-06 para presentar y entregar el tions nvelope ementation um Nationwide curriculum a los docentes Ensuring ECCE Structural Qu SNC-1.2.6 / Reproducción de Single Stage - One E Pending Impl IBRD / 90670 ality Standards and Curricul Post Request for Bids Open - National 350,000.00 0.00 2024-01-15 2024-01-20 2024-03-02 2024-04-01 2024-05-06 2024-11-15 material en Braille nvelope ementation um Nationwide SNC-1.2.7.1 / Servicios de el aboración de foros y talleres Ensuring ECCE Structural Qu Request for Quota Single Stage - One E Pending Impl para concientizar a personal IBRD / 90670 ality Standards and Curricul Post Open - National 25,000.00 0.00 2023-03-11 2023-05-06 2024-12-12 tions nvelope ementation de currículo, sobre equidad um Nationwide de género y prevención de la violencia SNC-1.2.9.1 / Diseño, edició n, diagramación e impresión Ensuring ECCE Structural Qu de manual para la transición Single Stage - One E Pending Impl IBRD / 90670 ality Standards and Curricul Post Request for Bids Open - National 410,000.00 0.00 2024-02-26 2024-03-02 2024-04-13 2024-05-13 2024-06-17 2025-01-24 de parvularia 6 a primer grad nvelope ementation um Nationwide o , de tercero a cuarto grado y de sexto a séptimo grado y entrega a docentes SNC-04-2.3.1 / Curso avanza Institutional Strengthening f do de Stata versión 14.; Gráfi Request for Quota Single Stage - One E Pending Impl IBRD / 90670 or the Management of the E Post Open - National 14,000.00 0.00 2022-12-20 2023-02-14 2023-07-31 cos estadísticos usando Stata tions nvelope ementation ducation Sector ; Introducción a la programac ión de Stata Institutional Strengthening f NC-04.2.4.1 / Servicio de im Request for Quota Single Stage - One E Pending Impl IBRD / 90670 or the Management of the E Post Open - National 12,000.00 0.00 2022-12-20 2023-02-14 2025-06-30 presión y escaneo de planos tions nvelope ementation ducation Sector NC-01.2.7.3 / Adquisición de Ensuring ECCE Structural Qu programas de radio y televisi Request for Quota Single Stage - One E IBRD / 90670 ality Standards and Curricul Post Open - National 8,000.00 0.00 Canceled 2022-02-20 2022-04-17 2022-08-16 ón con su diseño para desarr tions nvelope um Nationwide ollar la conciencia fonológica NC-01.2.7.4 / Servicio de Im Ensuring ECCE Structural Qu Request for Quota Single Stage - One E presión de guías y situacione IBRD / 90670 ality Standards and Curricul Post Open - National 64,800.00 0.00 Canceled 2022-02-20 2022-04-17 2025-04-01 tions nvelope s de aprendizajes para prime um Nationwide r grado NC-1-2-7.2 / Adquisición de s Ensuring ECCE Structural Qu ervicios para el diseño e impr Request for Quota Single Stage - One E IBRD / 90670 ality Standards and Curricul Post Open - National 38,880.00 0.00 Canceled 2022-02-20 2022-04-17 2025-02-10 esión de documentos para i tions nvelope um Nationwide mplementar el programa Ley endo en casa. Page 2 SNC-1.2.7.2 / Impresión de l Ensuring ECCE Structural Qu os materiales de apoyo al pr Request for Quota Single Stage - One E IBRD / 90670 ality Standards and Curricul Post Open - National 116,800.00 0.00 Canceled 2022-12-20 2023-02-14 2023-07-07 oceso de lectoescritura en la tions nvelope um Nationwide transición de parvularia a 1er . Grado. SNC-1.2.7.3 / Entrega técnic a de materiales de apoyo par a el proceso de transición de Ensuring ECCE Structural Qu Request for Quota Single Stage - One E lectoescritura en 1er. Grado, IBRD / 90670 ality Standards and Curricul Post Open - National 23,448.32 0.00 Canceled 2022-12-20 2023-02-14 2023-04-28 tions nvelope dirigida a docentes, equipos um Nationwide de asesoramiento educativos , y equipos técnicos del MINE DUCYT. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SC-01-2.2.1. / Revisar y Dis Ensuring ECCE Structural Qu eñar el Curriculo asi como la Quality And Cost- Under Implement IBRD / 90670 ality Standards and Curricul Post Open - National 414,000.00 0.00 2022-01-29 2022-11-29 2022-02-19 2022-04-04 2022-05-02 2022-06-01 2022-07-06 2022-08-10 2024-03-02 Implementacion del Plan de Based Selection ation um Nationwide Validación del Currículo. SC-04-1.1.2. / Definir y valid ar los estándares estructural Institutional Strengthening f es de calidad (Asistencia tec Quality And Cost- Under Implement IBRD / 90670 or the Management of the E Post Open - National 370,000.00 0.00 2022-02-15 2022-08-22 2022-03-08 2022-04-21 2022-05-19 2022-06-18 2022-07-23 2022-08-27 2023-08-27 nica, validación, edicion, diag Based Selection ation ducation Sector ramacion e impresión de do cumentos standares, asi com o logística para la difusión) SC-01.1.3.1 / Consultoria par Ensuring ECCE Structural Qu a investigar el nivel de desar Consultant Qualifi Under Implement IBRD / 90670 ality Standards and Curricul Post Open - National 75,000.00 0.00 2022-02-15 2022-08-29 2022-03-08 2022-04-21 2022-05-21 2022-06-25 2022-12-22 rollo de LESSA que incluya ár cation Selection ation um Nationwide eas de fortalecimiento. SC-01-2.1.1 / Consultoria par Strengthening Professional a el Diseño, Servicio y Logísti Development of Teachers an Consultant Qualifi IBRD / 90670 Post Open - National 50,000.00 0.00 Canceled 2022-02-15 2022-08-29 2022-03-08 2022-04-21 2022-05-21 2022-06-25 2022-12-22 ca de difusión de los estánda d Principals at ECCE Official cation Selection res de desarrollo y aprendiza Centers je SCI-1.1.1.1 / Consultoría par Ensuring ECCE Structural Qu a diseñar proceso y mecanis Consultant Qualifi Pending Impleme IBRD / 90670 ality Standards and Curricul Post Open - National 85,000.00 0.00 2023-03-31 2023-04-21 2023-06-04 2023-07-04 2023-08-08 2023-11-30 mos único de certificación y cation Selection ntation um Nationwide Desarrollo de Sofware para c ertificación SC-1-2.4.1 / Consultoría para el diseño, edición, diagramac Ensuring ECCE Structural Qu ión de materiales para las fa Quality And Cost- Open - Internationa Pending Impleme IBRD / 90670 ality Standards and Curricul Post 750,000.00 0.00 2023-07-03 2023-07-24 2023-09-06 2023-10-04 2023-11-03 2023-12-08 2024-01-12 2024-06-06 milias: cuadernillos, fascículo Based Selection l ntation um Nationwide s, trípticos, dípticos, asi como la impresión y distribución. CS-1.2.4.3 A LA 1.2.4.11 / Di Ensuring ECCE Structural Qu Quality And Cost- Open - Internationa Pending Impleme señar materiales educativos IBRD / 90670 ality Standards and Curricul Post 1,983,200.00 0.00 2024-01-15 2024-02-05 2024-03-20 2024-04-17 2024-05-17 2024-06-21 2024-07-26 2024-11-15 Based Selection l ntation para las familias y docentes um Nationwide SC-1.2.5.1 Y 1.2.6.1 / Consul toría para la adecuación de l Ensuring ECCE Structural Qu a literatura seleccionada de Consultant Qualifi Pending Impleme IBRD / 90670 ality Standards and Curricul Post Open - National 45,000.00 0.00 2023-03-06 2023-03-27 2023-05-10 2023-06-09 2023-07-14 2023-12-31 diferentes formatos de difusi cation Selection ntation um Nationwide ón y estrategia para promov er la producción local de liter atura infantil. SC-1.2.8.1 / Consultoría para el diseño e implementación d Ensuring ECCE Structural Qu e los módulo formativo de le Consultant Qualifi Pending Impleme IBRD / 90670 ality Standards and Curricul Post Open - National 130,000.00 0.00 2023-07-19 2023-08-09 2023-09-22 2023-10-22 2023-11-26 2024-07-18 ctoescritura online que incluy cation Selection ntation um Nationwide e audio libros para difundir p or radio y micrositio MINEDU CYT y su entrega técnica. SC-1.2.7.4 / Seguimiento y M onitoreo a la Implementación Ensuring ECCE Structural Qu de la Estrategia que funda el Consultant Qualifi Pending Impleme IBRD / 90670 ality Standards and Curricul Post Open - National 56,862.88 0.00 2022-12-15 2023-01-05 2023-02-18 2023-03-20 2023-04-24 2023-07-03 uso de los materiales de apo cation Selection ntation um Nationwide yo al proceso de transición d e lectoescritura en primer gr ado SC-2.1.5.3; 2.2.5.3 / Consult Strengthening Professional oría para diseño e implement Development of Teachers an Quality And Cost- Open - Internationa Pending Impleme IBRD / 90670 Post 1,613,200.00 0.00 2023-05-08 2023-05-29 2023-07-12 2023-08-09 2023-09-08 2023-10-13 2023-11-17 2026-05-29 ación de monitoreo para la fo d Principals at ECCE Official Based Selection l ntation rmación de docentes y direct Centers ores ECPI SC-2.2.2.1; 2.2.2.2; 2.2.3.1; Strengthening Professional 2.2.4.1.; / Consultoría para di Development of Teachers an Quality And Cost- Open - Internationa Pending Impleme seño e implementación de la IBRD / 90670 Prior 7,055,500.00 0.00 2022-12-15 2023-01-05 2023-02-18 2023-03-18 2023-04-17 2023-05-22 2023-06-26 2024-05-31 d Principals at ECCE Official Based Selection l ntation formación directiva-Educació Centers n y cuidados de la Primera In fancia (ECPI) SC-2.3.1.1 Y 02.3.1.2 / Cons Strengthening Professional ultoría para actualización e i Development of Teachers an Quality And Cost- Open - Internationa Pending Impleme mplementación de plan de F IBRD / 90670 Prior 2,248,900.00 0.00 2023-07-17 2023-08-07 2023-09-20 2023-10-18 2023-11-17 2023-12-22 2024-01-26 2026-06-30 d Principals at ECCE Official Based Selection l ntation ormación Inicial Docente en Centers Parvularia y Primera Infancia SC-2.3.3.1 Y 2.3.3.2 / Consul Strengthening Professional toría para el diseño e implem Development of Teachers an Quality And Cost- Pending Impleme IBRD / 90670 Post Open - National 221,400.00 0.00 2023-07-17 2023-08-07 2023-09-20 2023-10-18 2023-11-17 2023-12-22 2024-01-26 2025-01-07 entación del programa de for d Principals at ECCE Official Based Selection ntation mación para formadores IES Centers en primera infancia SC-3.1.3.1 / Consultoría para elaborar una regulación para los espacios físicos de los ce Upgrading ECCE Physical Le Consultant Qualifi Pending Impleme IBRD / 90670 Post Open - National 78,500.00 0.00 2022-12-15 2023-01-05 2023-02-18 2023-03-20 2023-04-24 2024-04-23 ntros educativos con base en arning Environments cation Selection ntation los estándares de infraestruc tura. (elaboración, reproducc ión y difusión) SC-3.2.4.1 / Servicios de Con sultoría para la elaboración d Upgrading ECCE Physical Le Quality And Cost- Open - Internationa Pending Impleme e Planes mantenimiento de i IBRD / 90670 Post 714,000.00 0.00 2023-10-02 2023-10-23 2023-12-06 2024-01-03 2024-02-02 2024-03-08 2024-04-12 2025-03-04 arning Environments Based Selection l ntation nfraestructura en versión am igable con sus aplicaciones i nformáticas Page 3 SC-2.2.1.1. / Diseñar un plan Strengthening Professional de formación Semipresencia Development of Teachers an Quality And Cost- l de formadores e Implement IBRD / 90670 Post Open - National 255,000.00 0.00 Canceled 2022-02-15 2022-03-08 2022-04-21 2022-05-19 2022-06-18 2022-07-23 2022-08-27 2023-08-27 d Principals at ECCE Official Based Selection ar plan de formación Semipr Centers esencial de formadores para directores. SC-4.1.11 / Servicios de Audi Institutional Strengthening f Consultant Qualifi Pending Impleme toria Externa de la Subvenció IBRD / 90670 or the Management of the E Post Open - National 20,000.00 0.00 2023-02-19 2023-03-12 2023-04-25 2023-05-25 2023-06-29 2026-06-30 cation Selection ntation n Multiplicadora (Financiamie ducation Sector nto Adicional) SC-4.1.7.1 / Consultoría para Institutional Strengthening f Consultant Qualifi Pending Impleme Diseño de un sistema de gest IBRD / 90670 or the Management of the E Post Open - National 60,000.00 0.00 2023-03-01 2023-03-22 2023-05-05 2023-06-04 2023-07-09 2024-06-03 cation Selection ntation ión de la infraestructura edu ducation Sector cativa SC-4.1.7.2 / Consultoría para Institutional Strengthening f Quality And Cost- Open - Internationa Pending Impleme Realización del inventario de IBRD / 90670 or the Management of the E Post 1,000,000.00 0.00 2023-01-09 2023-01-30 2023-03-15 2023-04-12 2023-05-12 2023-06-16 2023-07-21 2023-12-08 Based Selection l ntation la infraestructura educativa a ducation Sector nivel nacional SC-4.1.7.3 / Consultoría para Institutional Strengthening f elaboración del plan de inver Consultant Qualifi Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 35,000.00 0.00 2024-01-08 2024-01-29 2024-03-13 2024-04-12 2024-05-17 2024-07-08 sión para la infraestructura e cation Selection ntation ducation Sector ducativa basada en el invent ario CS-04.1.2.1. / Definir los Est ándares de Formación y Des Institutional Strengthening f Quality And Cost- Pending Impleme empeño para docentes de PI, IBRD / 90670 or the Management of the E Post Open - National 230,000.00 0.00 2023-01-16 2023-02-06 2023-03-22 2023-04-19 2023-05-19 2023-06-23 2023-07-28 2024-06-24 Based Selection ntation a partir del curriculo ajustado ducation Sector , para Directores, para la for mación inicial docente en PI CS-02.1.6.1 / Diseño del com ponente de formación docent e en Diseño Universal para el Strengthening Professional Aprendizaje (DUA), en servici Development of Teachers an Quality And Cost- Open - Internationa IBRD / 90670 Post 2,430,000.00 0.00 Canceled 2022-11-03 2022-11-24 2023-01-07 2023-02-04 2023-03-06 2023-04-10 2023-05-15 2025-11-30 o sobre identidad cultural y a d Principals at ECCE Official Based Selection l prendizaje de idiomas vivos ( Centers refiere idiomas de pueblos in dígenas) e Implementación d el plan de formación de doce ntes. SC-03-1.2.2 / Formulación d Upgrading ECCE Physical Le Quality And Cost- IBRD / 90670 Post Open - National 1,200,000.00 0.00 Canceled 2023-03-01 2023-03-22 2023-05-05 2023-06-02 2023-07-02 2023-08-06 2023-09-10 2024-05-07 e 40 carpetas técnicas (2do. arning Environments Based Selection bloque) SC-2.3.2.1 / Revisar, ajustar e implementar el plan de est Strengthening Professional udios de formación inicial de Development of Teachers an Quality And Cost- Open - Internationa docentes en educación inicial IBRD / 90670 Post 1,190,000.00 0.00 Canceled 2022-06-16 2022-07-07 2022-08-20 2022-09-17 2022-10-17 2022-11-21 2022-12-26 2026-12-25 d Principals at ECCE Official Based Selection l y parvularia. (incluye el plan Centers de estudios, diseño, reprodu ccion de materiales, Acredita cion e implementacion del pl an) SC-03-1.2.1 / Formulación d Upgrading ECCE Physical Le Quality And Cost- IBRD / 90670 Post Open - National 1,200,000.00 0.00 Canceled 2022-01-28 2022-02-18 2022-04-03 2022-05-01 2022-05-31 2022-07-05 2022-08-09 2023-04-06 e 40 carpetas técnicas (1er, arning Environments Based Selection bloque) SC-2.2.3.1 / Diseño de un pl an de formación semipresenc ial de Directores e implemen Strengthening Professional tación de un plan de formaci Development of Teachers an Quality And Cost- Open - Internationa ón semipresencial de Directo IBRD / 90670 Prior 5,259,000.00 0.00 Canceled 2022-02-15 2022-03-08 2022-04-21 2022-05-19 2022-06-18 2022-07-23 2022-08-27 2023-08-27 d Principals at ECCE Official Based Selection l res (que incluye adquisición Centers de materiales de mentoría, a compañamiento virtual a Dir ectores, elaboración e impre sión de materiale CS-02.1.2.1 / Diseño de plan Strengthening Professional de formación de formadores Development of Teachers an Quality And Cost- e implementación de un pla IBRD / 90670 Post Open - National 585,000.00 0.00 Canceled 2022-02-15 2022-03-08 2022-04-21 2022-05-19 2022-06-18 2022-07-23 2022-08-27 2023-04-24 d Principals at ECCE Official Based Selection n de formación virtual de for Centers madores-mentores fase 1 y 2 . CS-04.1.5.1. / Definición de estándares de aprendizaje y Institutional Strengthening f Quality And Cost- Open - Internationa Pending Impleme desarrollo de educación bási IBRD / 90670 or the Management of the E Post 1,139,300.00 0.00 2022-01-29 2022-02-19 2022-04-04 2022-05-02 2022-06-01 2022-07-06 2022-08-10 2024-08-09 Based Selection l ntation ca y media (formulación, vali ducation Sector dación y publicación) SC-4.1.9.1 A LA 4.1.14.1 / C onsultoría para Diseño, pilot aje y aplicación de rondas de Institutional Strengthening f evaluaciones nacionales esta Quality And Cost- Open - Internationa Pending Impleme IBRD / 90670 or the Management of the E Prior 4,850,000.00 0.00 2022-12-15 2023-01-05 2023-02-18 2023-03-18 2023-04-17 2023-05-22 2023-06-26 2026-06-30 ndarizadas de lenguaje y mat Based Selection l ntation ducation Sector emáticas en tercero, sexto y noveno grado; así como la di vulgación y uso de resultado s en el MINEDUCYT SC-4.1.15.1 A LA 4.1.15.6 / Institutional Strengthening f Consultoria para capacitació Quality And Cost- Open - Internationa Pending Impleme IBRD / 90670 or the Management of the E Post 1,110,000.00 0.00 2022-12-15 2023-01-05 2023-02-18 2023-03-18 2023-04-17 2023-05-22 2023-06-26 2026-06-30 n del personal técnico sobre Based Selection l ntation ducation Sector nuevas tendencias de evalua ción. SC-01-2.2.3. / Consultoría p Ensuring ECCE Structural Qu ara el diseño, edición y diagr Quality And Cost- Pending Impleme IBRD / 90670 ality Standards and Curricul Post Open - National 300,000.00 0.00 2023-03-27 2023-04-17 2023-05-31 2023-06-28 2023-07-28 2023-09-01 2023-10-06 2024-07-05 amación de versión impresa Based Selection ntation um Nationwide e interactiva, e incluye versió n inclusiva SC-04.1.16.1 AL 4.1.8.5 ; Y 4 .1.17.1 AL4 / Consultoría par a la adecuación y pilotaje de Institutional Strengthening f un instrumento para la evalu Quality And Cost- Open - Internationa Pending Impleme IBRD / 90670 or the Management of the E Post 525,000.00 0.00 2022-12-15 2023-01-05 2023-02-18 2023-03-18 2023-04-17 2023-05-22 2023-06-26 2026-06-30 ación de los aprendizajes en Based Selection l ntation ducation Sector el último año del ciclo parvul aria (Kinder 6) y evaluación d el proceso de gestión educati va en educación de la primer a infancia. SC-4.1.15.7 AL 4.1.15.11 / Consultoría para Diseño, elab Institutional Strengthening f oración y mantenimiento de Quality And Cost- Open - Internationa Pending Impleme IBRD / 90670 or the Management of the E Post 381,400.00 0.00 2022-12-15 2023-01-05 2023-02-18 2023-03-18 2023-04-17 2023-05-22 2023-06-26 2026-06-30 un sistema para evaluacione Based Selection l ntation ducation Sector s estandarizadas en linea; así como su website, audivisuale s y call center. SC-4.1.6.1. / Revisión y Redi Institutional Strengthening f Consultant Qualifi Pending Impleme seño de la Estructura Organiz IBRD / 90670 or the Management of the E Post Open - National 150,000.00 0.00 2023-01-31 2023-02-21 2023-04-06 2023-05-06 2023-06-10 2023-12-31 cation Selection ntation acional de las Departamental ducation Sector es Page 4 SC-01-2.6.6 / Caracterizar y sistematizar resultados de in Ensuring ECCE Structural Qu ventario cultural sobre los pu Consultant Qualifi Pending Impleme IBRD / 90670 ality Standards and Curricul Post Open - National 100,000.00 0.00 2022-12-15 2023-01-05 2023-02-18 2023-03-20 2023-04-24 2023-11-30 eblos Chortis, Lencas, Kakawi cation Selection ntation um Nationwide ra, Náhuatl y afrodescendien te en el territorio nacional. SC-4.1.4.1 A LA 4.1.4.4 / Con sultoría para el diseño de Est Institutional Strengthening f Consultant Qualifi Open - Internationa Pending Impleme ándares de Desempeño y For IBRD / 90670 or the Management of the E Post 300,000.00 0.00 2022-12-15 2023-01-05 2023-02-18 2023-03-20 2023-04-24 2024-01-09 cation Selection l ntation mación para Docentes y Dire ducation Sector ctores de Primera Infancia CS-04.1.9.4 / Consultoria par a la elaboracion de un sofwar Institutional Strengthening f Consultant Qualifi e para el "Monitorio de desar IBRD / 90670 or the Management of the E Post Open - National 30,000.00 0.00 Canceled 2022-01-26 2022-02-16 2022-04-01 2022-05-01 2022-06-05 2022-12-07 cation Selection rollo de habilidades comunic ducation Sector ativas en niñas y niños de pri mer grado " SC- 1.2.7.3 / Consultoría par a la Formación docente para Ensuring ECCE Structural Qu Consultant Qualifi atender la transición y el fort IBRD / 90670 ality Standards and Curricul Post Open - National 75,000.00 0.00 Canceled 2022-02-15 2022-03-08 2022-04-21 2022-05-21 2022-06-25 2022-12-22 cation Selection alecimiento de las habilidade um Nationwide s comunicativas con metodol ogía globalizadora. CS-04.2.6.1 / Estrategia de c omunicaciones y consulta del Proyecto sobre EAS: Eventos Institutional Strengthening f Consultant Qualifi Pending Impleme de divulgación y consulta per IBRD / 90670 or the Management of the E Post Open - National 96,000.00 0.00 2022-11-30 2022-12-21 2023-02-03 2023-03-05 2023-04-09 2027-03-07 cation Selection ntation iódica con la comunidad edu ducation Sector cativa (PPI) donde se esté im plementando el proyecto y s obre el MGAS SC-04.2.6.5 / Evaluación de r Institutional Strengthening f Consultant Qualifi Pending Impleme esultado cultural generado p IBRD / 90670 or the Management of the E Post Open - National 50,000.00 0.00 2022-12-15 2023-01-05 2023-02-18 2023-03-20 2023-04-24 2024-10-31 cation Selection ntation or el proyecto a los pueblos i ducation Sector ndigenas SC-04.1.8.2. / Implementaci Institutional Strengthening f Consultant Qualifi Pending Impleme ón de mecanismos de gestió IBRD / 90670 or the Management of the E Post Open - National 55,000.00 0.00 2023-03-03 2023-03-24 2023-05-07 2023-06-06 2023-07-11 2023-10-30 cation Selection ntation n de quejas y participación vi ducation Sector nculado a EAS SC-04.2.5.2 / Auditoría del pr oyecto “Proyecto "Crecer y A prender Juntos: Desarrollo Int Institutional Strengthening f egral de la Primera Infancia e Least Cost Selecti Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 180,000.00 0.00 2022-12-15 2023-01-05 2023-02-18 2023-03-18 2023-04-17 2023-05-22 2023-06-26 2026-06-30 n El Salvador” financiado con on ntation ducation Sector Préstamo del BM, por el perio do del 1 de enero al 31 de di ciembre de los años 2021, 20 22 y 2023 SC-02.1.5.6 / Monitoreo y se Strengthening Professional Quality And Cost- guimiento de la formación (D IBRD / 90670 Development of Teachers an Post Open - National 120,000.00 0.00 Canceled 2022-10-21 2022-11-11 2022-12-25 2023-01-22 2023-02-21 2023-03-28 2023-05-02 2025-05-01 Based Selection ocentes y Directores) d Principals at ECCE Official Centers SC-4.1.6.1 / Reorganizar la e structura territorial del Minist erio de Educación ( revisión y Institutional Strengthening f rediseño de la estructura org Quality And Cost- Open - Internationa IBRD / 90670 or the Management of the E Prior 1,395,000.00 0.00 Canceled 2022-02-15 2022-03-08 2022-04-21 2022-05-19 2022-06-18 2022-07-23 2022-08-27 2023-08-27 anizacional de las Departam Based Selection l ducation Sector entales, revisión de principal es procesos de gestión y coo rdinación, así como la formac ión de talento humano. SC-01-1.1.1 / Diseño e Impl ementacion de los mecanis mos de acreditación de instit Ensuring ECCE Structural Qu uciones públicas y privadas, Quality And Cost- IBRD / 90670 ality Standards and Curricul Post Open - National 715,000.00 0.00 Canceled 2022-06-24 2022-07-15 2022-08-28 2022-09-25 2022-10-25 2022-11-29 2023-01-03 2024-01-03 bajo el cumplimiento de está Based Selection um Nationwide ndares estructurales de calid ad de primera infancia, (Dise ño, software, capacitacion de los equipos e impr) SC-1.1.1.1.1 / Diseñar el pro ceso y los mecanismos de ce Ensuring ECCE Structural Qu rtificación de Instituciones pú Consultant Qualifi Pending Impleme IBRD / 90670 ality Standards and Curricul Post Open - National 110,000.00 0.00 2023-03-31 2023-04-21 2023-06-04 2023-07-04 2023-08-08 2024-01-05 blicas y privadas bajo el cum cation Selection ntation um Nationwide plimiento de estándares estr ucturales de Primera Infancia . SC-2.1.7.1 / Evaluación del r Strengthening Professional esultado de la formación doc Development of Teachers an Quality And Cost- ente, (Diagnóstico muestral IBRD / 90670 Post Open - National 435,000.00 0.00 Canceled 2022-07-01 2022-07-22 2022-09-04 2022-10-02 2022-11-01 2022-12-06 2023-01-10 2024-01-10 d Principals at ECCE Official Based Selection de prácticas docentes de cap Centers acidades y Evaluación final d e docentes.) SC-2.3.3.1 / Diseñar un siste ma de acreditación, certifica ción y habilitación que respo Strengthening Professional nda a la diversidad de docent Development of Teachers an Quality And Cost- IBRD / 90670 Post Open - National 255,000.00 0.00 Canceled 2022-06-20 2022-07-11 2022-08-24 2022-09-21 2022-10-21 2022-11-25 2022-12-30 2023-12-30 es incluyendo mecanismos p d Principals at ECCE Official Based Selection or el cumplimiento de estánd Centers ares. Formar capacidades p ara la evaluación de estánda res de formación inicial de do centes. SC-04-4.1.1.3 / Costear las b rechas basadas en estándare s estructurales de calidad. Di Institutional Strengthening f señar los mecanismos para r Quality And Cost- IBRD / 90670 or the Management of the E Post Open - National 175,000.00 0.00 Canceled 2022-02-24 2022-03-17 2022-04-30 2022-05-28 2022-06-27 2022-08-01 2022-09-05 2023-03-06 educir las brechas. Diseñar y Based Selection ducation Sector validar la regulación de los e stándares estructurales de c alidad para centros educativ os existentes y nuevos. SC-02.1.1.1 / Selección de fo Strengthening Professional Consultant Qualifi rmadores de docentes y de D IBRD / 90670 Development of Teachers an Post Open - National 45,000.00 0.00 Canceled 2022-02-15 2022-03-08 2022-04-21 2022-05-21 2022-06-25 2022-12-22 cation Selection irectores d Principals at ECCE Official Centers SC-03-1.1.2 / Supervisión de Upgrading ECCE Physical Le Consultant Qualifi 2do (40 CE) y 3er bloque (34 IBRD / 90670 Post Open - National 69,930.00 0.00 Canceled 2022-02-15 2022-03-08 2022-04-21 2022-05-21 2022-06-25 2022-12-22 arning Environments cation Selection CE) de perfiles de inversión SC-01.2.6.5 / Asistencia Téc nica para desarrollar las Cun Ensuring ECCE Structural Qu Consultant Qualifi Pending Impleme as Náhuatl para estudiantes IBRD / 90670 ality Standards and Curricul Post Open - National 120,000.00 0.00 2022-12-15 2023-01-05 2023-02-18 2023-03-20 2023-04-24 2023-11-30 cation Selection ntation de 4-7 años, población indige um Nationwide na de otros territorios y pobl ación afrodescendientes Page 5 SC-03-1.1.1 / Elaboración del Upgrading ECCE Physical Le Quality And Cost- segundo bloque de perfiles d IBRD / 90670 Post Open - National 666,000.00 0.00 Canceled 2022-02-15 2022-03-08 2022-04-21 2022-05-19 2022-06-18 2022-07-23 2022-08-27 2023-02-23 arning Environments Based Selection e inversión (74 perfiles) /1 SC-2.3.1.1. / Consultoría par a el Diseño e Implementació Strengthening Professional n de un plan de formación y Development of Teachers an Quality And Cost- Open - Internationa Pending Impleme IBRD / 90670 Post 525,000.00 0.00 2023-01-09 2023-01-30 2023-03-15 2023-04-12 2023-05-12 2023-06-16 2023-07-21 2025-02-28 un curso de alfabetización co d Principals at ECCE Official Based Selection l ntation n diferentes actores para el c Centers onocimiento y fortalecimient o de la lengua de señas Institutional Strengthening f CS-04.2.5.1 / Evaluación de I Quality And Cost- Open - Internationa Pending Impleme IBRD / 90670 or the Management of the E Post 430,081.00 0.00 2023-06-28 2023-07-19 2023-09-01 2023-09-29 2023-10-29 2023-12-03 2024-01-07 2026-04-08 mpacto del proyecto Based Selection l ntation ducation Sector SC-03.2.2.1 / Supervisión del Upgrading ECCE Physical Le Quality And Cost- Open - Internationa diseño y Mejoramiento de IBRD / 90670 Prior 2,596,491.23 0.00 Canceled 2022-11-30 2022-12-21 2023-02-03 2023-03-03 2023-04-02 2023-05-07 2023-06-11 2024-04-01 arning Environments Based Selection l 40 centros educativos (1er. G rupo) SC-3.2.2.2 / Supervisión del Upgrading ECCE Physical Le Quality And Cost- Open - Internationa diseño y Mejoramiento de 4 IBRD / 90670 Prior 2,569,491.23 0.00 Canceled 2023-03-01 2023-03-22 2023-05-05 2023-06-02 2023-07-02 2023-08-06 2023-09-10 2024-08-01 arning Environments Based Selection l 0 centros educativos (2do. Gr upo) SC-3.2.2.3 / Supervisión del Upgrading ECCE Physical Le Quality And Cost- Open - Internationa diseño y Mejoramiento de 3 IBRD / 90670 Prior 2,207,017.54 0.00 Canceled 2023-07-03 2023-07-24 2023-09-06 2023-10-04 2023-11-03 2023-12-08 2024-01-12 2025-01-10 arning Environments Based Selection l 4 centros educativos (3er. Gr upo) SC-3.2.2.1 AL 3.2.2.3 / Cons ultoría para la Supervisión d Upgrading ECCE Physical Le Quality And Cost- Open - Internationa IBRD / 90670 Prior 6,369,589.53 0.00 Canceled 2023-01-05 2023-01-26 2023-03-11 2023-04-08 2023-05-08 2023-06-12 2023-07-17 2024-07-16 el Diseño y Construcción de arning Environments Based Selection l 111 centros educativos SC-1.2.7.1 / Elaboración, Dis Ensuring ECCE Structural Qu eño y Diagramación de Mater Consultant Qualifi IBRD / 90670 ality Standards and Curricul Post Open - National 31,320.00 0.00 Canceled 2022-12-15 2023-01-05 2023-02-18 2023-03-20 2023-04-24 2023-07-03 iales de apoyo para el proces cation Selection um Nationwide o de transición de lecto escrit ura en primer grado SC-1.2.7.1; 1.2.7.2 Y 1.2.7.3 / Consultoría para la elaborac ión de materiales para el pro Ensuring ECCE Structural Qu ceso de transición de lectroe Consultant Qualifi Under Implement IBRD / 90670 ality Standards and Curricul Post Open - National 161,631.20 0.00 2023-02-10 2023-02-16 2023-03-03 2023-04-16 2023-05-16 2023-06-20 2023-12-17 scritura de parvularia 6 años cation Selection ation um Nationwide a primer grado de educación básica, formación de docente s , equipos técnicos y validac ión de uso de los materiales” SC-2.1.1.1; 2.2.1.1; 2.1.6.1 Y 2.2.6.1 / Consultoría para ela Strengthening Professional boración de línea base, diagn Development of Teachers an Quality And Cost- Open - Internationa IBRD / 90670 Post 600,000.00 0.00 Canceled 2023-10-03 2023-10-24 2023-12-07 2024-01-04 2024-02-03 2024-03-09 2024-04-13 2025-06-30 óstico, evaluación de impact d Principals at ECCE Official Based Selection l o y evaluación de resultados Centers en la formación de docentes y directores ECPI SC-2.1.1.1 Y 2.2.1.1 / Consul toría para el Diseño e Imple mentación de un Diagnostico Ensuring ECCE Structural Qu Consultant Qualifi Under Implement y Caracterización de Conoci IBRD / 90670 ality Standards and Curricul Post Open - National 230,000.00 0.00 2023-02-10 2023-03-24 2023-03-03 2023-04-16 2023-05-16 2023-06-20 2023-10-18 cation Selection ation mientos y Competencias de um Nationwide ECPI de Docentes, Directores , Agentes Educativos y ATPI e n servicio” SC-3.2.2.1 / Supervisión de o bras al mejoramiento de infr Upgrading ECCE Physical Le Quality And Cost- Open - Internationa Pending Impleme aestructura de 40 centros ed IBRD / 90670 Prior 2,254,870.56 0.00 2023-05-19 2023-06-09 2023-07-23 2023-08-20 2023-09-19 2023-10-24 2023-11-28 2024-06-10 arning Environments Based Selection l ntation ucativos públicos que atiend en primera infancia (Grupo 1 ) SC-0.3.2.2.2 / Supervisión de obras al mejoramiento de inf Upgrading ECCE Physical Le Quality And Cost- Open - Internationa Pending Impleme raestructura de 31 centros e IBRD / 90670 Prior 1,747,524.87 0.00 2023-06-28 2023-07-19 2023-09-01 2023-09-29 2023-10-29 2023-12-03 2024-01-07 2024-07-20 arning Environments Based Selection l ntation ducativos públicos que atien den primera infancia (Grupo 2) SC-O.3.2.2.3 / Supervisión d e obras al mejoramiento de i Upgrading ECCE Physical Le Quality And Cost- Open - Internationa Pending Impleme IBRD / 90670 Prior 2,374,870.70 0.00 2023-08-18 2023-09-08 2023-10-22 2023-11-19 2023-12-19 2024-01-23 2024-02-27 2024-11-08 nfraestructura de 40 centros arning Environments Based Selection l ntation educativos públicos que atie nden primera infancia CS-2.1.6.1. Y 2.2.6.1. / Con sultoría para la realización de Strengthening Professional una línea de base y evaluaci Development of Teachers an Quality And Cost- Open - Internationa Pending Impleme IBRD / 90670 Post 550,000.00 0.00 2023-06-12 2023-07-03 2023-08-16 2023-09-13 2023-10-13 2023-11-17 2023-12-22 2025-07-14 ón de impacto del resultado d Principals at ECCE Official Based Selection l ntation de la formación de docentes Centers y directores de Educación y Cuidados de la Primera Infan cia. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-04.2.1.1.3 / Especialista T Institutional Strengthening f Individual Consult Under Implement écnico en Infraestructura y G IBRD / 90670 or the Management of the E Post Open 132,840.00 0.00 2022-01-14 2022-06-29 2022-03-04 2022-03-25 2022-04-29 2026-06-30 ant Selection ation estión de Proyectos ducation Sector CI-04.2.2.1.3.3 / Contratació Institutional Strengthening f Individual Consult Under Implement n de Técnico Especialista en IBRD / 90670 or the Management of the E Post Open 122,040.00 0.00 2022-01-29 2022-05-11 2022-03-19 2022-04-09 2022-05-14 2026-06-30 ant Selection ation currículo en Ciencia ducation Sector CI-04.2.2.1.3.5 / Contratació Institutional Strengthening f Individual Consult Under Implement n de Técnico Especialista en IBRD / 90670 or the Management of the E Post Open 122,040.00 0.00 2022-01-29 2022-05-11 2022-03-19 2022-04-09 2022-05-14 2026-06-30 ant Selection ation currículo en Materno Infanti ducation Sector l. CI-04.2.2.1.3.6 / Contratació Institutional Strengthening f Individual Consult Under Implement n de Técnico Especialista en IBRD / 90670 or the Management of the E Post Open 122,040.00 0.00 2022-01-29 2022-05-11 2022-03-19 2022-04-09 2022-05-14 2026-06-30 ant Selection ation currículo en Educación Espe ducation Sector cial. CI-04.2.2.1.3.7 / Contratació Institutional Strengthening f Individual Consult Under Implement n de Técnico Especialista en IBRD / 90670 or the Management of the E Post Open 122,040.00 0.00 2022-01-29 2022-05-11 2022-03-19 2022-04-09 2022-05-14 2026-06-30 ant Selection ation currículo en Educación Inici ducation Sector al. Page 6 CI-04.2.1.1.7 / Especialista Institutional Strengthening f Individual Consult Under Implement de Infraestructura en Monitor IBRD / 90670 or the Management of the E Post Open 132,840.00 0.00 2022-01-14 2022-06-29 2022-03-04 2022-03-25 2022-04-29 2026-06-30 ant Selection ation eo y Evaluación de Proyectos ducation Sector CI-04.2.2.1.8.1 / Contratació n de Especialista (1) de Adqu Institutional Strengthening f isiciones para apoyar los pro Individual Consult Under Implement IBRD / 90670 or the Management of the E Prior Open 135,000.00 0.00 2022-01-28 2022-05-19 2022-03-18 2022-04-08 2022-05-13 2026-09-29 cesos de Adquisición y Contr ant Selection ation ducation Sector atación de Obras, Bienes, Ser vicios de No Consultoría y Co nsultorías , con fondos-BIRF. CI-04.2.2.1.8.2 / Contratació n de Especialista (2) de Adqu Institutional Strengthening f isiciones para apoyar los pro Individual Consult Under Implement IBRD / 90670 or the Management of the E Prior Open 135,000.00 0.00 2022-01-28 2022-03-18 2022-04-08 2022-05-13 2026-09-29 cesos de Adquisición y Contr ant Selection ation ducation Sector atación de Obras, Bienes, Ser vicios de No Consultoría y Co nsultorías , con fondos-BIRF. CI-04.2.2.1.8.3 / Contratació n de Especialista (3) de Adqu Institutional Strengthening f isiciones para apoyar los pro Individual Consult Under Implement IBRD / 90670 or the Management of the E Prior Open 135,000.00 0.00 2022-01-28 2022-05-27 2022-03-18 2022-04-08 2022-05-13 2026-09-29 cesos de Adquisición y Contr ant Selection ation ducation Sector atación de Obras, Bienes, Ser vicios de No Consultoría y Co nsultorías , con fondos-BIRF. CI-04.2.1.1.1 / Coordinador T Institutional Strengthening f Individual Consult écnico para la Ejecución de l IBRD / 90670 or the Management of the E Post Open 216,000.00 0.00 Canceled 2022-01-14 2021-12-22 2022-03-04 2022-03-25 2022-04-29 2026-06-30 ant Selection os Proyectos ducation Sector CI-04.2.1.1.9 / “CONSULTORÍ Institutional Strengthening f A DE TÉCNICO EN ADQUISICI Individual Consult Under Implement IBRD / 90670 or the Management of the E Prior Open 118,080.00 0.00 2022-04-19 2022-04-27 2022-06-07 2022-08-30 2022-06-28 2022-08-02 2026-10-03 ONES PARA LA UNIDAD GEST ant Selection ation ducation Sector ORA DE PROYECTOS (UGP)” CI-04.2.1.1.2 / “CONSULTORI A DE TÉCNICO EN EDUCACIÓ Institutional Strengthening f Individual Consult Under Implement N Y GESTIÓN DE PROYECTOS IBRD / 90670 or the Management of the E Post Open 118,080.00 0.00 2022-01-14 2022-04-21 2022-03-04 2022-03-25 2022-04-29 2026-06-30 ant Selection ation PARA LA UNIDAD GESTORA D ducation Sector E PROYECTOS (UGP)” CI-04.2.1.1.4 / “CONSULTORÍ Institutional Strengthening f A DE TÉCNICO AMBIENTAL PA Individual Consult Under Implement IBRD / 90670 or the Management of the E Post Open 118,080.00 0.00 2022-01-14 2022-04-21 2022-03-04 2022-06-13 2022-03-25 2022-06-02 2022-04-29 2026-06-30 RA LA UNIDAD GESTORA DE ant Selection ation ducation Sector PROYECTOS (UGP).” CI-04.2.1.1.6 / “CONSULTORI Institutional Strengthening f A- TECNICO EN SEGUIMIENTO Individual Consult Under Implement IBRD / 90670 or the Management of the E Post 118,080.00 0.00 2022-01-14 2022-04-21 2022-03-04 2022-03-25 2022-04-29 2026-06-30 DEL AREA DE EDUCACIÓN PA ant Selection ation ducation Sector RA LA UNIDAD GESTORA DE PROYECTOS (UGP)” CI-04.2.1.1.10 / “CONSULTO Institutional Strengthening f RÍA DE TÉCNICO FINANCIERO Individual Consult Under Implement IBRD / 90670 or the Management of the E Post Open 118,080.00 0.00 2022-01-14 2022-04-21 2022-03-04 2022-05-26 2022-03-25 2022-06-28 2022-04-29 2026-06-30 PARA LA UNIDAD GESTORA D ant Selection ation ducation Sector E PROYECTOS (UGP)” Institutional Strengthening f CI-04.2.1.1.8 / Coordinador F Individual Consult IBRD / 90670 or the Management of the E Post Open 216,000.00 0.00 Canceled 2022-01-20 2022-01-21 2022-03-10 2022-03-31 2022-05-05 2026-07-06 iduciario de los Proyectos ant Selection ducation Sector CI-04.2.1.1.11 / COORDINAD Institutional Strengthening f Individual Consult OR FIDUCIARIO DE LOS PROY IBRD / 90670 or the Management of the E Prior Open 192,000.00 0.00 Canceled 2022-05-13 2022-06-30 2022-07-01 2022-07-22 2022-08-26 2026-06-30 ant Selection ECTOS-UGP ducation Sector CI-04.2.1.1.12 / COORDINAD Institutional Strengthening f Individual Consult OR TECNICO PARA LA EJECUC IBRD / 90670 or the Management of the E Post Open 192,000.00 0.00 Canceled 2022-05-13 2022-06-30 2022-07-01 2022-07-22 2022-08-26 2026-06-30 ant Selection IÓN DE LOS PROYECTOS (UG ducation Sector P) CI-04.2.2.1.3.1 / Contratació Institutional Strengthening f Individual Consult n de Técnico Especialista en IBRD / 90670 or the Management of the E Post Open 122,040.00 0.00 Canceled 2022-01-29 2022-05-12 2022-03-19 2022-04-09 2022-05-14 2026-06-30 ant Selection currículo en Arte/Música. ducation Sector CI-04.2.2.1.3.1-2 / CONTRAT Institutional Strengthening f ACION DE TECNICO ESPECIAL Individual Consult Under Implement IBRD / 90670 or the Management of the E Post Open 108,480.00 0.00 2022-06-02 2022-06-01 2022-07-21 2022-08-11 2022-09-15 2026-06-30 ISTA EN CURRICULO DE EDU ant Selection ation ducation Sector CACIÓN PARVULARIA CI-04.2.2.1.3.2 / Contratació Institutional Strengthening f Individual Consult n de Técnico Especialista en IBRD / 90670 or the Management of the E Post Open 122,040.00 0.00 Canceled 2022-01-29 2022-05-12 2022-03-19 2022-04-09 2022-05-14 2026-06-30 ant Selection currículo en Literatura/Ingle ducation Sector s. CI-04.2.1.1.5 / “CONSULTORI Institutional Strengthening f Individual Consult A DE TÉCNICO SOCIAL PARA IBRD / 90670 or the Management of the E Post Open 118,080.00 0.00 Canceled 2022-01-14 2022-04-21 2022-03-04 2022-03-25 2022-04-29 2026-06-30 ant Selection LA UNIDAD GESTORA DE PRO ducation Sector YECTOS (UGP)” CI-04.2.1.1.2.1 / “CONSULTO RÍA-DE TECNICO EN EDUCACI Institutional Strengthening f Individual Consult Under Implement ÓN Y GESTIÓN DE PROYECTO IBRD / 90670 or the Management of the E Post Open 115,620.00 0.00 2022-06-29 2022-06-30 2022-08-17 2022-09-07 2022-10-12 2026-06-30 ant Selection ation S PARA LA UNIDAD GESTORA ducation Sector DE PROYECTOS (UGP) (SEGU NDA CONVOCATORIA)” CI-04.2.1.1.5.1 / CONSULTO Institutional Strengthening f RÍA DE TECNICO SOCIAL PAR Individual Consult Under Implement IBRD / 90670 or the Management of the E Post Open 115,620.00 0.00 2022-06-29 2022-06-30 2022-08-17 2022-09-07 2022-10-12 2026-06-30 A LA UNIDAD GESTORA DE P ant Selection ation ducation Sector ROYECTOS (UGP) (SEGUNDA CONVOCATORIA)" CI-04.2.1.1.6.1 / CONTRATA CIÓN DE TÉCNICO EN SEGUI Institutional Strengthening f Individual Consult Under Implement MIENTO DEL AREA DE EDUCA IBRD / 90670 or the Management of the E Post Open 115,620.00 0.00 2022-06-29 2022-06-30 2022-08-17 2022-09-07 2022-10-12 2026-06-30 ant Selection ation CIÓN PARA LA UNIDAD GEST ducation Sector ORA DE PROYECTOS (UGP) (S EGUNDA CONVOCATORIA) CI-04.2.2.1.3.4.1 / CONTRAT ACIÓN DE TECNICO ESPECIA Institutional Strengthening f Individual Consult Under Implement LISTA EN CURRÍCULO DE EDU IBRD / 90670 or the Management of the E Post Open - National 101,700.00 0.00 2022-08-29 2022-09-09 2022-10-17 2022-11-07 2022-12-12 2026-06-30 ant Selection ation CACIÓN BÁSICA CON EXPERI ducation Sector ENCIA EN MATEMÁTICA (SEG UNDA CONVOCATORIA) CI-04.2.2.1.3.2-2 / CONTRAT Institutional Strengthening f Individual Consult ACIÓN DE TÉCNICO ESPECIAL IBRD / 90670 or the Management of the E Post Open 108,480.00 0.00 Canceled 2022-06-02 2022-06-01 2022-07-21 2022-08-11 2022-09-15 2026-06-30 ant Selection ISTA EN CURRÍCULO ESPECIA ducation Sector LIDAD LENGUAJE Page 7 CI-04.2.2.1.3.4 / Contratació Institutional Strengthening f Individual Consult n de Técnico Especialista en IBRD / 90670 or the Management of the E Post Open 122,040.00 0.00 Canceled 2022-01-29 2022-05-11 2022-03-19 2022-04-09 2022-05-14 2026-06-30 ant Selection currículo en Matemática. ducation Sector CI 04-2.2.1.3.2.2.1 / CONTRA TACION DE TECNICO ESPECIA Institutional Strengthening f Individual Consult Under Implement LISTA EN CURRICULO, ESPECI IBRD / 90670 or the Management of the E Post Open - National 101,700.00 0.00 2022-09-12 2022-09-09 2022-10-31 2022-11-21 2022-12-26 2026-06-30 ant Selection ation ALIDAD DE LENGUAJE Y LITE ducation Sector RATURA (SEGUNDA CONVOC ATORIA) CI-4.1.1.1 / Evaluar las condi Upgrading ECCE Physical Le Individual Consult Pending Impleme ciones que faciliten o dificult IBRD / 90670 Post Open - National 25,000.00 0.00 2023-03-30 2023-05-18 2023-06-08 2023-07-13 2023-09-30 arning Environments ant Selection ntation en elevar los estándares de c alidad CI-04.2.2.1.1.1 / Contratació n de Coordinador especialist Institutional Strengthening f Individual Consult Pending Impleme as (1) en certificación de est IBRD / 90670 or the Management of the E Post Open - National 94,920.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 ant Selection ntation ándares y seguimiento a la f ducation Sector ormación de docente para la s DDE CI-04.2.2.1.1.2 / Contratació n de Coordinador especialist Institutional Strengthening f Individual Consult Pending Impleme as (2) en certificación de est IBRD / 90670 or the Management of the E Post Open - National 94,920.00 0.00 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection ntation ándares y seguimiento a la f ducation Sector ormación de docente para la s DDE CI-04.2.2.1.1.3 / Contratació n de Coordinador especialist Institutional Strengthening f Individual Consult Pending Impleme as (3) en certificación de est IBRD / 90670 or the Management of the E Post Open - National 94,920.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 ant Selection ntation ándares y seguimiento a la f ducation Sector ormación de docente para la s DDE CI-04.2.2.1.2.1 / Contratació Institutional Strengthening f n de Especialista (1) en certi Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ficación de estándares y seg ant Selection ntation ducation Sector uimiento a la formación de d ocente para las DDE CI-04.2.2.1.2.2 / Contratacio Institutional Strengthening f n de Especialista (2) en certi Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ficación de estándares y seg ant Selection ntation ducation Sector uimiento a la formación de d ocente para las DDE CI-04.2.2.1.2.3 / Contratació Institutional Strengthening f n de Especialista (3) en certi Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 ficación de estándares y seg ant Selection ntation ducation Sector uimiento a la formación de d ocente para las DDE CI-04.2.2.1.2.4 / Contratació Institutional Strengthening f n de Especialista (4) en certi Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 ficación de estándares y seg ant Selection ntation ducation Sector uimiento a la formación de d ocente para las DDE CI-04.2.2.1.2.5 / Contratació Institutional Strengthening f n de Especialista (5) en certi Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 ficación de estándares y seg ant Selection ntation ducation Sector uimiento a la formación de d ocente para las DDE CI-04.2.2.1.2.6 / Contratació Institutional Strengthening f n de Especialista (6) en certi Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 ficación de estándares y seg ant Selection ntation ducation Sector uimiento a la formación de d ocente para las DDE CI-04.2.2.1.2.7 / Contratació Institutional Strengthening f n de Especialista (7) en certi Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ficación de estándares y seg ant Selection ntation ducation Sector uimiento a la formación de d ocente para las DDE CI-04.2.2.1.2.8 / Contratació Institutional Strengthening f n de Especialista (8) en certi Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 ficación de estándares y seg ant Selection ntation ducation Sector uimiento a la formación de d ocente para las DDE CI-04.2.2.1.2.9 / Contratació Institutional Strengthening f n de Especialista (9) en certi Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 ficación de estándares y seg ant Selection ntation ducation Sector uimiento a la formación de d ocente para las DDE CI-04.2.2.1.2.10 / Contrataci Institutional Strengthening f ón de Especialista (10) en ce Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 rtificación de estándares y se ant Selection ntation ducation Sector guimiento a la formación de docente para las DDE CI-04.2.2.1.2.11 / Contrataci Institutional Strengthening f ón de Especialista (11) en ce Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 rtificación de estándares y se ant Selection ntation ducation Sector guimiento a la formación de docente para las DDE CI-04.2.2.1.2.12 / Contrataci Institutional Strengthening f ón de Especialista (12) en ce Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 rtificación de estándares y se ant Selection ntation ducation Sector guimiento a la formación de docente para las DDE CI-04.2.2.1.2.13 / Contrataci Institutional Strengthening f ón de Especialista (13) en ce Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 rtificación de estándares y se ant Selection ntation ducation Sector guimiento a la formación de docente para las DDE CI-04.2.2.1.2.14 / Contrataci Institutional Strengthening f ón de Especialista (14) en ce Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 63,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2027-04-29 rtificación de estándares y se ant Selection ntation ducation Sector guimiento a la formación de docente para las DDE CI-04.2.2.1.4.1 / Contratació n de Técnico Especialista (1) Institutional Strengthening f en educación con experienci Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 96,600.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 a en formación docente y ma ant Selection ntation ducation Sector nejo de plataformas virtuales para coordinación técnica de las formaciones y evaluacion es Page 8 CI-04.2.2.1.4.2 / Contratació n de (1) especialista en educ ación con experiencia en for Institutional Strengthening f Individual Consult Pending Impleme mación docente y manejo de IBRD / 90670 or the Management of the E Post Open - National 96,600.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 ant Selection ntation plataformas virtuales para ad ducation Sector ministración de recurso hum ano y del monitoreo del proy ecto formativo. CI-04.2.2.1.4.3 / Contratació n de (1) especialista en educ Institutional Strengthening f ación con experiencia en for Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 96,600.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 mación docente y manejo de ant Selection ntation ducation Sector plataformas virtuales para ap oyo y seguimiento de la form ación docente. CI-04.2.2.1.4.4 / Contratació n de (1) especialista en educ Institutional Strengthening f ación con experiencia en for Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 96,000.00 0.00 2021-10-29 2021-12-17 2022-01-07 2022-02-11 2026-06-30 mación docente y manejo de ant Selection ntation ducation Sector plataformas virtuales para ap oyo y seguimiento de la form ación directiva. CI-04.2.2.1.4.5 / Contratació n de (1) especialista en educ Institutional Strengthening f ación con experiencia en for Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 96,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 mación docente y manejo de ant Selection ntation ducation Sector plataformas virtuales. para a poyo y seguimiento de la for mación inicial docente CI-04.2.2.1.5 / Contratación Institutional Strengthening f Individual Consult Pending Impleme aalista cuantitativo en el áre IBRD / 90670 or the Management of the E Post Open - National 84,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 ant Selection ntation a de estadística (compartido) ducation Sector CI-04.2.6.4.1.1 / Contratació Institutional Strengthening f n de servicios profesionales d Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 49,140.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 e enseñanza de lengua indíg ant Selection ntation ducation Sector ena (1er. enseñante) CI-04.2.6.4.1.2 / Contratació Institutional Strengthening f n de servicios profesionales d Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 49,140.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 e enseñanza de lengua indíg ant Selection ntation ducation Sector ena (2do enseñante) CI-04.2.6.4.1.3 / Contratació Institutional Strengthening f n de servicios profesionales d Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 49,140.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 e enseñanza de lengua indíg ant Selection ntation ducation Sector ena (3er. enseñante) CI-04-2.6.4.2 / Servicios prof Institutional Strengthening f Individual Consult Pending Impleme esionales de coordinación de IBRD / 90670 or the Management of the E Post Open - National 49,140.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2023-09-26 ant Selection ntation enseñanza de lengua indígen ducation Sector a (profesor) CI-04.2.6.7. / Contratación d e consultor Individual para el " Estudio de medición de la s Institutional Strengthening f Individual Consult Pending Impleme atisfacción de las partes inte IBRD / 90670 or the Management of the E Post Open - National 14,116.00 0.00 2022-11-30 2023-01-18 2023-02-08 2023-03-15 2026-06-30 ant Selection ntation resadas respecto a la implem ducation Sector entación del proyecto " (se r ealizará en dos partes año 20 22 y año 2026) CI-04.2.6.9 / Consultor Indivi dual para la "Asistencia técni Institutional Strengthening f ca para la atención a pueblo Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 58,500.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2027-08-13 s indígenas (nahuablantes y ant Selection ntation ducation Sector otras lenguas vivas para gar antizar proceso de calidad y pertinencia) " (para los 6 año s) CI-04.2.6.10 / Consultor Indi Institutional Strengthening f vidual para la "Asistencia téc Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 58,500.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-04-10 nica- Especialista en gestión ant Selection ntation ducation Sector cultural " (para los 6 años) CI-3.1.4.1 Y 3.1.5.1 / Servicio de consultoría para la capaci tación de normativa ambient al y para la capacitación sob Upgrading ECCE Physical Le Individual Consult Pending Impleme IBRD / 90670 Post Open - National 40,000.00 0.00 2023-01-09 2023-02-27 2023-03-20 2023-04-24 2023-08-15 re elaboración de los planes arning Environments ant Selection ntation de gestión ambiental y social (PGAS)dirigido a contratistas, perosnal de las Direcciones D epartamentales y nivel centr al CI-3.1.5.1.1 / Servicio de con sultoría para capacitación d e organismos, instituciones g Upgrading ECCE Physical Le Individual Consult Pending Impleme ubernamentales, etc. En lo re IBRD / 90670 Post Open - National 20,000.00 0.00 2024-10-14 2024-12-02 2024-12-23 2025-01-27 2025-07-26 arning Environments ant Selection ntation lacionado con la correcta inte rpretación y aplicación de la regulación para la infraestruc tura educativa. CI-04.2.2.1.6.1.5 / Contrataci Institutional Strengthening f ón de 1 especialista en formu Individual Consult IBRD / 90670 or the Management of the E Post Open - National 31,200.00 0.00 Canceled 2023-10-02 2023-11-20 2023-12-11 2024-01-15 2024-12-31 lacion y gestión de proyectos ant Selection ducation Sector de Infraestructura Educativa. CI-04.2.2.1.6.1.10 / Contrata ción de 1 Arquitecto para la Institutional Strengthening f Individual Consult Unidad de Infraestructura Ed IBRD / 90670 or the Management of the E Post Open - National 25,764.00 0.00 Canceled 2023-10-02 2023-11-20 2023-12-11 2024-01-15 2024-12-31 ant Selection ucativa del Ministerio de Obr ducation Sector as Públicas y de Transporte CI-04.2.2.1.6.1.12 / Contrata ción del Sub- Coordinador A Institutional Strengthening f Individual Consult mbiental y Social de la Unid IBRD / 90670 or the Management of the E Post Open - National 76,275.00 0.00 Canceled 2022-12-12 2023-01-30 2023-02-20 2023-03-27 2024-12-31 ant Selection ad de Infraestructura Educati ducation Sector va del Ministerio de Obras Pú blicas y de Transporte. CI-04.2.2.1.6.1.13 / Contrata ción del Asistente de Monitor Institutional Strengthening f Individual Consult eo y Evaluación de la Unidad IBRD / 90670 or the Management of the E Post Open - National 48,700.00 0.00 Canceled 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 ant Selection de Infraestructura Educativa ducation Sector del Ministerio de Obras Públic as y de Transporte. Page 9 CI-04.2.2.1.6.1.14 / Contrata ción del Especialista Ambient Institutional Strengthening f Individual Consult al de la Unidad de Infraestruc IBRD / 90670 or the Management of the E Post Open - National 61,500.00 0.00 Canceled 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2024-12-31 ant Selection tura Educativa del Ministerio ducation Sector de Obras Públicas y deTtrans porte CI-04.2.2.1.6.1.15 / Contrata ción del Especialista Social d Institutional Strengthening f Individual Consult e la Unidad de Infraestructur IBRD / 90670 or the Management of the E Post Open - National 61,500.00 0.00 Canceled 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2024-12-31 ant Selection a Educativa del Ministerio de ducation Sector Obras Públicas y de Transpor te. CI-04.2.6.8.1 / Consultor Indi vidual para la Implementaci Institutional Strengthening f ón del Plan de Gestión de la Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 120,000.00 0.00 2023-01-16 2023-03-06 2023-03-27 2023-05-02 2025-01-23 Continuidad Educativa y Reu ant Selection ntation ducation Sector bicación Temporal de Estudia ntes para los años del 2022 a l 2024 CI-4.2.6.8.2 / Consultoría par Institutional Strengthening f Individual Consult Pending Impleme a Evaluación de resultados d IBRD / 90670 or the Management of the E Post Open - National 12,000.00 0.00 2024-11-01 2024-12-20 2025-01-10 2025-02-14 2025-09-08 ant Selection ntation e la aplicación del MGAS ducation Sector SC-04.1.18.1 / Consultoría p Institutional Strengthening f Individual Consult Pending Impleme ara la verificación y cumplimi IBRD / 90670 or the Management of the E Post Open - National 12,000.00 0.00 2023-02-19 2023-04-09 2023-04-30 2023-06-04 2024-02-19 ant Selection ntation ento de indicadores del proy ducation Sector ecto CI-04.2.2.1.6.16 / Contrataci Institutional Strengthening f Individual Consult ón de Especialistas Junior (1) IBRD / 90670 or the Management of the E Post Open - National 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector arquitectónico. CI-1.2.7.2 / Consultoría para el diseño de guías y situacio Ensuring ECCE Structural Qu Individual Consult nes de aprendizaje para prim IBRD / 90670 ality Standards and Curricul Post Open 6,752.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-10 2022-08-08 ant Selection er grado con orientaciones d um Nationwide e asistencia técnica para doc entes y familias CI-04.2.2.1.6.1.16 / Contrata Institutional Strengthening f Individual Consult Pending Impleme ción de Asesor Jurídico de la IBRD / 90670 or the Management of the E Post Open - National 168,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 ant Selection ntation Unidad Gestora de Proyectos ducation Sector (UGP) CI-04.2.2.1.6.2 / Contratació Institutional Strengthening f Individual Consult n de Especialistas Junior (2) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector Estructuritas. CI-04.2.2.1.6.1 / Contratació Institutional Strengthening f Individual Consult n de Especialistas Junior (1) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector Estructuritas. CI-04.2.2.1.6.3 / Contratació Institutional Strengthening f Individual Consult n de Especialistas Junior (3) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector eléctrico. CI-04.2.2.1.6.6 / Contratació Institutional Strengthening f Individual Consult n de Especialistas Junior (1) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector hidráulico. CI-04.2.2.1.6.7 / Contratació Institutional Strengthening f Individual Consult n de Especialistas Junior (2) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector hidráulico. CI-04.2.2.1.6.9 / Contratació Institutional Strengthening f Individual Consult n de Especialistas Junior (4) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector hidráulico. CI-04.2.2.1.6.10 / Contrataci Institutional Strengthening f Individual Consult ón de Especialistas Junior (5) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector hidráulico. CI-04.2.2.1.6.14 / Contrataci Institutional Strengthening f Individual Consult ón de Especialistas Junior (4) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector eléctrico. CI-04.2.2.1.6.11 / Contrataci Institutional Strengthening f Individual Consult ón de Especialistas Junior (1) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector eléctrico. CI-04.2.2.1.6.12 / Contrataci Institutional Strengthening f Individual Consult ón de Especialistas Junior (2) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector eléctrico. CI-04.2.2.1.6.13 / Contrataci Institutional Strengthening f Individual Consult ón de Especialistas Junior (3) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector eléctrico. CI-04.2.2.1.6.15 / Contrataci Institutional Strengthening f Individual Consult ón de Especialistas Junior (5) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector eléctrico. CI-04.2.2.1.6.17 / Contrataci Institutional Strengthening f Individual Consult ón de Especialistas Junior (2) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector arquitectónico. CI-04.2.2.1.6.18 / Contrataci Institutional Strengthening f Individual Consult ón de Especialistas Junior (3) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector arquitectónico. CI-04.2.2.1.6.19 / Contrataci Institutional Strengthening f Individual Consult ón de Especialistas Junior (4) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector arquitectónico. CI-04.2.2.1.6.20 / Contrataci Institutional Strengthening f Individual Consult ón de Especialistas Junior (5) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector arquitectónico. CI-04.2.2.1.6.8 / Contratació Institutional Strengthening f Individual Consult n de Especialistas Junior (3) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector hidráulico. Page 10 CI-04.2.2.1.6.5 / Contratació Institutional Strengthening f Individual Consult n de Especialistas Junior (5) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector Estructuritas. CI-04.2.2.1.6.4 / Contratació Institutional Strengthening f Individual Consult n de Especialistas Junior (4) IBRD / 90670 or the Management of the E Post Open 163,836.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ant Selection en Seguimiento especialidad ducation Sector Estructuritas. CI-04.2.2.1.7.4 / Contratació n de Especialistas Senior (4) Institutional Strengthening f en Soporte técnico especiali Individual Consult IBRD / 90670 or the Management of the E Post Open 156,600.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 zado (Estructurista, hidráulic ant Selection ducation Sector o, eléctrico, arquitectónico, c onstrucción o supervisión o a mbientalista) Strengthening Professional SC-2.2.2.1 / Selección de ca Individual Consult IBRD / 90670 Development of Teachers an Post Open 18,000.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2022-11-27 ndidatos a formadores ant Selection d Principals at ECCE Official Centers CI-04.2.6.8 / Consusltor Indiv idual para la "Implementació n de mecanismos del MGAS Institutional Strengthening f Individual Consult para la intervención de Infrae IBRD / 90670 or the Management of the E Post Open 120,000.00 0.00 Canceled 2022-01-29 2022-03-19 2022-04-09 2022-05-14 2026-06-30 ant Selection structura en el desplazamien ducation Sector to de estudiantes en los Cent ros Educativos seleccionados . " (para los años, 2022 al 20 24) CI-3.1.6.2 / Servicio de cons ultoria para la Capacitación Institutional Strengthening f Individual Consult sobre elaboración del PGAS d IBRD / 90670 or the Management of the E Post Open 20,000.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2022-11-27 ant Selection e subproyectos para formula ducation Sector dores de carpetas técnicas CI-04.2.2.1.7.1 / Contratació n de especialistas Senior (1) Institutional Strengthening f en soporte técnico especializ Individual Consult IBRD / 90670 or the Management of the E Post Open 156,600.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 ado (Estructurista, hidráulico, ant Selection ducation Sector eléctrico, arquitectónico, con strucción o supervisión o am bientalista) CI-04.2.2.1.7.2 / Contratació n de Especialistas Senior (2) Institutional Strengthening f en Soporte técnico especiali Individual Consult IBRD / 90670 or the Management of the E Post Open 156,600.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 zado (Estructurista, hidráulic ant Selection ducation Sector o, eléctrico, arquitectónico, c onstrucción o supervisión o a mbientalista) CI-04.2.2.1.7.3 / Contratació n de Especialistas Senior (3) Institutional Strengthening f en Soporte técnico especiali Individual Consult IBRD / 90670 or the Management of the E Post Open 156,600.00 0.00 Canceled 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2026-06-30 zado (Estructurista, hidráulic ant Selection ducation Sector o, eléctrico, arquitectónico, c onstrucción o supervisión o a mbientalista) CI-04.2.2.1.6.1.2 / Contrataci Institutional Strengthening f ón de 5 especialistas para la Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 312,000.00 0.00 2023-01-13 2023-03-03 2023-03-24 2023-04-28 2024-12-31 Dirección de Infraestructura ant Selection ntation ducation Sector y Ambientes Educativos. CI-04.2.2.1.6.1.1 / Contrataci Institutional Strengthening f ón de 7 especialistas para la Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 455,000.00 0.00 2022-12-01 2023-01-19 2023-02-09 2023-03-16 2024-12-31 Dirección de Infraestructura ant Selection ntation ducation Sector y Ambientes Educativos CI-04.2.2.1.6.1.3 / Contrataci Institutional Strengthening f ón de 4 especialistas para la Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 124,800.00 0.00 2023-09-14 2023-11-02 2023-11-23 2024-01-03 2024-12-31 Dirección de Infraestructura ant Selection ntation ducation Sector y Ambientes Educativos CI-04.2.2.1.6.1.4 / Contrataci Institutional Strengthening f ón de 2 especialistas para la Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 127,400.00 0.00 2023-01-16 2023-03-06 2023-03-27 2023-05-02 2024-12-31 Dirección de Infraestructura ant Selection ntation ducation Sector y Ambientes Educativos. CI-04.2.2.1.6.1.6 / Contrataci ón de 4 Coordinadores de Co Institutional Strengthening f Individual Consult ntrato para la Unidad de Infr IBRD / 90670 or the Management of the E Post Open - National 282,500.00 0.00 Canceled 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2024-11-28 ant Selection aestructura Educativa del Mi ducation Sector nisterio de Obras Públicas y de Transporte. CI-04.2.2.1.6.1.7 / Contrataci ón de 3 Coordinadores de Co Institutional Strengthening f Individual Consult ntrato para la Unidad de Infr IBRD / 90670 or the Management of the E Post Open - National 203,400.00 0.00 Canceled 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2024-12-31 ant Selection aestructura Educativa del Mi ducation Sector nisterio de Obras Públicas y de Transporte CI-4.2.2.1.6.1.8 / Contratació n de 2 Coordinadores de Con Institutional Strengthening f Individual Consult trato para la Unidad de Infrae IBRD / 90670 or the Management of the E Post Open - National 67,800.00 0.00 Canceled 2023-10-02 2023-11-20 2023-12-11 2024-01-15 2024-12-31 ant Selection structura Educativa del Minis ducation Sector terio de Obras Públicas y de Transporte CI-04.2.2.1.6.1.9 / Contrataci Institutional Strengthening f ón de 3 Arquitectos para la U Individual Consult IBRD / 90670 or the Management of the E Post Open - National 161,025.00 0.00 Canceled 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2024-12-31 nidad de Infraestrucura Educ ant Selection ducation Sector ativa del Ministerio de Obras Públicas y de Transporte CI-04.2.2.1.6.1.11 / Contrata ción de dos (2) arquitecto pa ra la Unidad de Infraestructur Institutional Strengthening f Individual Consult a Educativa del MOP enfocad IBRD / 90670 or the Management of the E Post Open - National 72,980.00 0.00 Canceled 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2024-07-31 ant Selection os en los centros educativos ducation Sector a intervenir para atender nec esidades de agua, saneamie nto e higiene. CI-04.2.2.1.2.15 / Contrataci Institutional Strengthening f ón de Asesor/a para la Estrat Individual Consult Under Implement IBRD / 90670 or the Management of the E Post Open - National 210,000.00 0.00 2023-02-06 2023-02-13 2023-03-27 2023-04-17 2023-05-22 2026-06-30 egia del Diseño Curricular de ant Selection ation ducation Sector la Primera Infancia para el MI NEDUCYT CI-4.2.2.1.2.14 / Contratació Institutional Strengthening f n de dos (2) consultores con Individual Consult IBRD / 90670 or the Management of the E Post Open - National 352,000.00 0.00 Canceled 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2026-06-30 especialidad en Educación de ant Selection ducation Sector Primera Infancia. Page 11 CI-04.2.2.1.6.1.17 / Contrata ción de Coordinador técnico Institutional Strengthening f Individual Consult para la Unidad de Infraestruc IBRD / 90670 or the Management of the E Post Open - National 129,950.00 0.00 Canceled 2023-03-09 2023-03-21 2023-04-27 2023-05-18 2023-06-22 2025-03-31 ant Selection tura Educativa del MOPT (Pré ducation Sector stamo BIRF-9067-SV, del MIN EDUCYT) CI-04.2.2.1.6.1.12.1 / Contra tación del subcoordinador A Institutional Strengthening f Individual Consult Under Implement mbiental y Social de la Unida IBRD / 90670 or the Management of the E Post Open - National 70,150.00 0.00 2023-03-09 2023-03-21 2023-04-27 2023-05-18 2023-06-22 2025-03-31 ant Selection ation d de Infraestructura Educativ ducation Sector a del MOPT (Préstamo BIRF-9 067-SV, del MINEDUCYT) CI-04.2.2.1.6.1.15.1 / Contra tación de Técnico con especi Institutional Strengthening f alidad en gestión social para Individual Consult Under Implement IBRD / 90670 or the Management of the E Post Open - National 64,975.00 0.00 2023-03-09 2023-03-21 2023-04-27 2023-05-18 2023-06-22 2025-03-31 la Unidad de Infraestructura ant Selection ation ducation Sector Educativa del MOPT (Préstam o BIRF-9067-SV, del MINEDU CYT) CI-04.2.2.1.6.1.14.1 / Contra tación de Técnico con especi Institutional Strengthening f alidad en gestión ambiental Individual Consult Under Implement IBRD / 90670 or the Management of the E Post Open - National 64,975.00 0.00 2023-03-09 2023-03-21 2023-04-27 2023-05-18 2023-06-22 2025-03-25 para la Unidad de Infraestruc ant Selection ation ducation Sector tura Educativa del MOPT (Pré stamo BIRF-9067-SV, del MIN EDUCYT) CI-04.2.2.1.6.1.13.1 / Contra tación del asistente de Monit Institutional Strengthening f Individual Consult Under Implement oreo y Evaluación de la Unid IBRD / 90670 or the Management of the E Post Open - National 44,850.00 0.00 2023-03-09 2023-03-21 2023-04-27 2023-05-18 2023-06-22 2025-03-31 ant Selection ation ad de Infraestructura Educati ducation Sector va del MOPT (Préstamo BIRF- 9067-SV, del MINEDUCYT) CI-04.2.2.1.6.1.9.1 / Contrat ación de 5 arquitectos para l Institutional Strengthening f Individual Consult Under Implement a Unidad de Infraestructura E IBRD / 90670 or the Management of the E Post Open - National 247,250.00 0.00 2023-03-09 2023-03-21 2023-04-27 2023-05-18 2023-06-22 2025-03-31 ant Selection ation ducativa del MOPT (Préstamo ducation Sector BIRF-9067-SV, del MINEDUCY T) CI-04.2.2.1.6.1.6.1 / Contrat ación de 3 administradores d Institutional Strengthening f Individual Consult Pending Impleme e Contrato para la Unidad de IBRD / 90670 or the Management of the E Post Open - National 161,025.00 0.00 2023-05-12 2023-06-30 2023-07-21 2023-08-25 2025-03-31 ant Selection ntation Infraestructura Educativa del ducation Sector MOPT (Préstamo BIRF-9067-S V, del MINEDUCYT) CI-04.2.2.1.6.1.7.1 / Contrat ación de 3 administradores d Institutional Strengthening f Individual Consult Pending Impleme e Contrato para la Unidad de IBRD / 90670 or the Management of the E Post Open - National 152,550.00 0.00 2023-06-13 2023-08-01 2023-08-22 2023-09-26 2025-03-31 ant Selection ntation Infraestructura Educativa del ducation Sector MOPT (Préstamo BIRF-9067-S V, del MINEDUCYT) CI-04.2.2.1.6.1.8.1 / Contrat ación de 3 administradores d Institutional Strengthening f Individual Consult Pending Impleme e Contrato para la Unidad de IBRD / 90670 or the Management of the E Post Open - National 135,600.00 0.00 2023-07-13 2023-08-31 2023-09-21 2023-10-26 2025-03-31 ant Selection ntation Infraestructura Educativa del ducation Sector MOPT (Préstamo BIRF-9067-S V, del MINEDUCYT) CI-04.2.2.1.6.1.18 / Contrata ción de Coordinador técnico Institutional Strengthening f Individual Consult Under Implement para la Unidad de Infraestruc IBRD / 90670 or the Management of the E Post Limited 129,950.00 0.00 2023-03-24 2023-03-28 2023-03-29 2023-04-19 2023-05-24 2025-03-31 ant Selection ation tura Educativa del MOPT, (Pr ducation Sector éstamo BIRF-9067-SV., del MI NEDUCYT) CI-04.2.6.11 / Contratación d Institutional Strengthening f e Coordinador para el Área E Individual Consult Under Implement IBRD / 90670 or the Management of the E Post Open - National 148,000.00 0.00 2023-05-03 2023-05-03 2023-06-21 2023-07-12 2023-08-16 2026-07-30 ducativa de la Unidad Imple ant Selection ation ducation Sector mentadora de Proyecto (UIP) CI-04.2.6.12 / Contratación d Institutional Strengthening f e Especialista Técnico de For Individual Consult Under Implement IBRD / 90670 or the Management of the E Post Open - National 111,000.00 0.00 2023-05-03 2023-05-03 2023-06-21 2023-07-12 2023-08-16 2026-06-30 mación Docente, para la Uni ant Selection ation ducation Sector dad Implementadora de Proy ecto (UIP) CI-04.2.6.13 / Contratación d Institutional Strengthening f e Especialista Técnico de Cur Individual Consult Under Implement IBRD / 90670 or the Management of the E Post Open - National 111,000.00 0.00 2023-05-03 2023-05-03 2023-06-21 2023-07-12 2023-08-16 2026-06-30 rículo para la Unidad Implem ant Selection ation ducation Sector entadora de Proyecto (UIP) CI-04.2.2.1.8.5 / Contratació n de Especialista (5) de Adqu Institutional Strengthening f isiciones para apoyar los pro Individual Consult IBRD / 90670 or the Management of the E Post Open - National 135,000.00 0.00 Canceled 2022-01-28 2022-03-18 2022-04-08 2022-05-13 2026-09-29 cesos de Adquisición y Contr ant Selection ducation Sector atación de Obras, Bienes, Ser vicios de No Consultoría y Co nsultorías , con fondos-BIRF. CI-04.2.2.1.8.4 / Contratació n de Especialista ( Nos 2,4 y 5) de Adquisiciones para apo Institutional Strengthening f Individual Consult yar los procesos de Adquisici IBRD / 90670 or the Management of the E Post Open - National 375,000.00 0.00 Canceled 2022-12-15 2023-05-03 2023-02-02 2023-02-23 2023-03-30 2026-06-30 ant Selection ón y Contratación de Obras, ducation Sector Bienes, Servicios de No Cons ultoría y Consultorías , con fo ndos-BIRF. CI-04.2.2.1.8.2, 4 Y 5 / Contr atación de Especialista (Nos 2, 4 y 5) de Adquisiciones pa Institutional Strengthening f Individual Consult Under Implement ra apoyar los procesos de Ad IBRD / 90670 or the Management of the E Prior Open - National 277,500.00 0.00 2023-05-26 2023-06-02 2023-07-14 2023-08-04 2023-09-08 2026-06-30 ant Selection ation quisición y Contratación de O ducation Sector bras, Bienes, Servicios de No Consultoría y Consultorías, c on fondos- BIRF CI-04.2.2.1.6.1.5.1 / Contrat ación de dos (2) especialistas en Formulación y Gestión de Institutional Strengthening f Individual Consult Pending Impleme proyectos de Infraestructura IBRD / 90670 or the Management of the E Post Open - National 147,600.00 0.00 2023-06-26 2023-08-14 2023-09-04 2023-10-09 2025-12-31 ant Selection ntation Educativa para apoyar la lab ducation Sector or de la Dirección de Infraest ructura y Ambientes Educativ os (DIAE) CI-04.2.2.1.6.21 / Contrataci ón de tres (3) especialistas S Institutional Strengthening f Individual Consult Pending Impleme enior en Diseño eléctrico par IBRD / 90670 or the Management of the E Post Open - National 225,000.00 0.00 2023-06-26 2023-08-14 2023-09-04 2023-10-09 2025-12-31 ant Selection ntation a apoyo a la Dirección de Inf ducation Sector raestructura y Ambientes Ed ucativos (DIAE) Page 12 CI-04.2.2.1.6.22 / Contrataci Institutional Strengthening f ón de seis (6) arquitectos jun Individual Consult Pending Impleme IBRD / 90670 or the Management of the E Post Open - National 270,000.00 0.00 2023-06-26 2023-08-14 2023-09-04 2023-10-09 2025-12-31 ior para apoyo a la Dirección ant Selection ntation ducation Sector de Infraestructura y Ambient es Educativos (DIAE) CI-04.2.2.1.6.23 / Contrataci ón de seis (6) especialistas s Institutional Strengthening f Individual Consult Pending Impleme enior en diseño arquitectónic IBRD / 90670 or the Management of the E Post Open - National 468,000.00 0.00 2023-06-26 2023-08-14 2023-09-04 2023-10-09 2025-12-31 ant Selection ntation o para apoyo a la Dirección d ducation Sector e Infraestructura y Ambiente s Educativos (DIAE) CI-04.2.2.1.6.24 / Contrataci ón de un (1) especialista en e Institutional Strengthening f Individual Consult Pending Impleme structuras para apoyo a la Di IBRD / 90670 or the Management of the E Post Open - National 105,000.00 0.00 2023-06-26 2023-08-14 2023-09-04 2023-10-09 2025-12-31 ant Selection ntation rección de Infraestructura y ducation Sector Ambientes Educativos (DIAE) CI-04.2.2.1.6.25 / Contrataci ón de un (1) especialista en Institutional Strengthening f Individual Consult Pending Impleme diseño hidraulico Senior para IBRD / 90670 or the Management of the E Post Open - National 105,000.00 0.00 2023-06-26 2023-08-14 2023-09-04 2023-10-09 2025-12-31 ant Selection ntation apoyo a la Dirección de Infra ducation Sector estructura y Ambientes Educ ativos Page 13 PROCUREMENT PLAN (Textual Part) Project information: Papua New Guinea (PNG), Urban Youth Employment Project II, P-166420 Project Implementation agency: National Capital Development Commission (NCDC); and Lae City Authority (LCA) Date of the Procurement Plan: February 20, 2020 Period covered by this Procurement Plan: February 2020 – to August 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the National Procurement Act 2018, No. 12 of 2018, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. National preferences Eligibility: Eligibility to participate in a procurement process for and to be awarded a Bank financed contract shall be as defined under paragraphs 3.21-3.23 of the Procurement Regulations; accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in the said paragraphs. Foreign bidders shall be eligible to participate in bidding under the same conditions as national bidders. No domestic preference shall be granted in bid evaluation on the basis of bidder’s nationality, origin of goods or services, and/or preferential programs. Registration of bidders as Registration of bidders: condition for bidding Registration shall not be used to assess bidders’ qualifications. A foreign bidder shall not be required to register as a condition for submitting its bid, and a foreign bidder recommended for contract award shall be given a reasonable opportunity to register, with the reasonable cooperation of the Recipient, prior to contract signing. Procurement documents Procurement Documents: Templates of procurement documents, including contract forms, acceptable to the Association shall be used for all procurement financed by the Project. Document Fees Bidding Document Fees: A fee for bidding documents if applied must be reasonable and is to be used to offset the actual costs associated with reproduction of large bidding documents and associated plans and drawings. It is not to be used to generate revenue, or to limit or restrict participation in procurement processes. Bidding document fees are not to be charged for the procurement of consulting services (firms and individual), non-consulting services, or goods. Fraud and Corruption Fraud and Corruption: The procurement documents shall require that bidders submitting bids present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. Negotiations and Cancellation of all bids: cancellation of All bids (or the sole bid if only one bid is procurement process received) shall not be rejected, the procurement process shall not be cancelled, and new bids shall not be solicited without the Bank’s prior written concurrence. Complaints Handling Complaints Review Mechanism: The Recipient shall establish and implement an effective, fair and timely complaints review mechanism allowing bidders to complain and to have their complaints handled in a timely manner. Until an adequate complaints review mechanism (as assessed by the Bank) is established the Bank’s review mechanism as set out in the Procurement Regulations will apply. Contract Award Notice Publication of Contract Award Notice: For purposes of Article 36(5) of the Act, within one month from award, a notice of all procurement contract awards shall include, at a minimum as relevant and applicable for each procurement method (a) the name of each bidder that submitted a bid; (b) bid prices as read out at bid opening; (c) evaluated prices of each bid that was evaluated; (d) the names of bidders whose bids were either rejected as nonresponsive or not meeting qualification criteria, or not evaluated, with the reasons thereof; and (e) the name of the winning bidder, the final total contract price, as well as the duration and a summary of the scope of the contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. The above captioned conditions also apply when approaching the international market. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable; Works: Not Applicable PROCUREMENT Papua New Guinea : Urban Youth Employment Project II PLAN General Information Country: Papua New Guinea 2019-09-17 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166420 GPN Date: Project Name: Urban Youth Employment Project II Loan / Credit No: IDA / 64050 National Capital District Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure PG-NCDC-337416-CW-RFQ / Request for Quota Single Stage - One E ment Document - 2023-10-0 NCDC Works Contract (Wards IDA / 64050 Youth Job Corps Post Open - National 162,242.00 0.00 Signed 2023-02-11 2023-02-06 2023-04-08 tions nvelope 1 Envelope proce 5 1 & 4) ss (Non Bank-SPD ) PG-NCDC-362766-CW-RFQ / Request for Quota URBAN WORKS -Construction Request for Quota Single Stage - One E Under Imple 2024-01-2 IDA / 64050 Youth Job Corps Post Limited tions (Non Bank-S 220,000.00 0.00 2023-06-03 2023-05-24 2023-07-29 of 1250 m Footpath of 1.8 m tions nvelope mentation 5 PD) wide and 0.15 m depth in Wa igani PG-NCDC-369113-CW-RFQ / National Procure Construction of Vendor Benc ment Document - Request for Quota Single Stage - One E Pending Imp 2024-02-2 hes and upgrading Walkway/ IDA / 64050 Youth Job Corps Post Limited 1 Envelope proce 155,000.00 0.00 2023-07-05 2023-08-30 tions nvelope lementation 6 Markert seating area along C ss (Non Bank-SPD hinsurah Drive, Foodland. ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-NCDC-319084-GO-RFQ / I Request for Quota Single Stage - One E IDA / 64050 Project Management Post Limited 100,000.00 0.00 Signed 2022-10-17 2022-10-11 2022-12-12 2023-06-10 T & Office Equipment tions nvelope PG-NCDC-335156-GO-RFQ / I Request for Quota Single Stage - One E IDA / 64050 Skills Training Post Limited 435,974.00 0.00 Signed 2023-02-04 2023-02-08 2023-04-01 2023-09-28 T Equipment tions nvelope PG-NCDC-335155-GO-RFQ / Request for Quota Single Stage - One E IDA / 64050 Project Management Post Limited 132,060.00 0.00 Completed 2023-02-04 2023-02-07 2023-04-01 2023-09-28 2023-04-07 Vehicles tions nvelope PG-NCDC-335154-GO-RFQ / Request for Quota Single Stage - One E Basic Life Skills Training Cons IDA / 64050 Youth Job Corps Post Limited 52,667.00 0.00 Canceled 2023-02-06 2023-04-03 2023-09-30 tions nvelope umable Materials PG-NCDC-335153-GO-RFQ / Request for Quota Single Stage - One E IDA / 64050 Youth Job Corps Post Limited 498,000.00 0.00 Signed 2023-04-06 2023-03-20 2023-06-01 2024-05-26 Personal Protective Equipme tions nvelope nt NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-NCDC-320311-NC-RFQ / Request for Quota Single Stage - One E Project Implementation Supp IDA / 64050 Youth Job Corps Post Limited 499,231.00 0.00 Canceled 2023-03-05 2022-11-16 2023-04-30 2023-10-27 tions nvelope ort Personnel (PISP) PG-NCDC-347310-NC-RFQ / Request for Quota Single Stage - One E IDA / 64050 Youth Job Corps Post Limited 366,000.00 0.00 Signed 2023-03-18 2023-03-27 2023-05-13 2023-11-09 Youth Facilitators tions nvelope PG-NCDC-347309-NC-RFQ / Request for Quota Single Stage - One E Project Implementation Supp IDA / 64050 Project Management Post Limited 351,780.53 0.00 Canceled 2023-03-18 2023-05-13 2025-05-02 tions nvelope ort Personnel - 2 PG-NCDC-363605-NC-DIR / S Under Imple IDA / 64050 Project Management Post Direct Selection Direct - National 50,000.00 0.00 2023-05-29 2023-05-28 2023-06-03 2023-05-30 2023-07-08 2024-01-04 AGE Support mentation CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-NCDC-340532-CS-CQS / Referral Services and Monito Consultant Qualifi BASELINE SURVEY TO SUPPO IDA / 64050 Post Open - National 70,000.00 0.00 Signed 2023-02-15 2023-02-12 2023-03-08 2023-04-21 2023-04-17 2023-05-21 2023-05-12 2023-06-25 2023-10-23 ring and Evaluation cation Selection RT IMPACT EVALUATION INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-NCDC-116613-CS-INDV / Community Engagement & S IDA / 64050 Youth Job Corps Post Direct Selection Direct 78,781.93 115,480.78 Signed 2019-09-18 2019-07-24 2019-09-28 2019-06-27 2019-12-02 2019-08-05 2020-05-30 urvey Coordinator PG-NCDC-116614-CS-INDV / Team Leader - Basic Life Skill IDA / 64050 Youth Job Corps Post Direct Selection Direct 116,357.83 184,638.54 Signed 2019-09-18 2019-07-24 2019-09-28 2019-06-27 2019-12-02 2019-08-05 2020-05-30 s Training PG-NCDC-116623-CS-CDS / IDA / 64050 Project Management Post Direct Selection Direct 112,888.85 179,133.87 Signed 2019-09-18 2019-07-24 2019-09-28 2019-06-27 2019-12-02 2019-08-05 2020-05-30 Senior Project Accountant PG-NCDC-116624-CS-CDS / IDA / 64050 Project Management Post Direct Selection Direct 46,805.34 68,599.34 Signed 2019-09-18 2019-07-24 2019-09-28 2019-06-27 2019-12-02 2019-08-05 2020-05-30 Accounts Officer Page 1 PG-NCDC-116625-CS-CDS / IDA / 64050 Project Management Post Direct Selection Direct 36,888.91 54,121.35 Signed 2019-09-18 2019-07-24 2019-09-28 2019-06-27 2019-12-02 2019-08-05 2020-05-30 Accounts & Payroll Officer PG-NCDC-116626-CS-CDS / IDA / 64050 Project Management Post Direct Selection Direct 51,142.71 74,320.54 Signed 2019-09-18 2019-07-23 2019-09-28 2019-06-27 2019-12-02 2019-08-05 2020-05-30 Procurement Officer PG-NCDC-116628-CS-CDS / IDA / 64050 Project Management Post Direct Selection Direct 165,814.38 263,102.87 Signed 2019-09-18 2019-07-24 2019-09-28 2019-06-27 2019-12-02 2019-08-05 2020-05-30 Program Coordination Manag er PG-NCDC-116631-CS-CDS / IDA / 64050 Project Management Post Direct Selection Direct 13,394.20 20,366.85 Signed 2019-09-18 2019-07-24 2019-09-28 2019-06-27 2019-12-02 2019-08-05 2020-05-30 Driver - CS-033A PG-NCDC-253903-CS-INDV / Individual Consult IDA / 64050 Youth Job Corps Post Open 77,942.00 0.00 Canceled 2021-10-18 2021-12-06 2021-12-27 2022-01-31 2022-07-30 Public Works Engineer ant Selection PG-NCDC-263493-CS-INDV / Individual Consult IDA / 64050 Project Management Post Open 164,695.00 0.00 Canceled 2021-11-17 2021-12-06 2022-01-05 2022-01-26 2022-03-02 2022-08-29 NCD-CS-026 NCDC Project ant Selection Manager PG-NCDC-150850-CS-CDS / Individual Consult IDA / 64050 Skills Training Post Open 78,994.80 0.00 Canceled 2021-10-18 2021-12-06 2021-12-27 2022-01-31 2022-07-30 Skills Development Team Lea ant Selection der PG-NCDC-253901-CS-CDS / NCD-CS- 009 Senior Public w IDA / 64050 Youth Job Corps Post Direct Selection Direct 144,724.00 506,738.12 Completed 2021-09-20 2021-12-08 2021-09-30 2022-01-14 2021-12-04 2022-01-26 2022-06-02 2022-05-10 orks Engineer - Team Leader PG-NCDC-258046-CS-CDS / NCD-116630-CS-020 Informa IDA / 64050 Project Management Post Direct Selection Direct 83,556.00 162,224.29 Signed 2021-10-13 2022-01-11 2021-10-23 2022-01-14 2021-12-27 2022-01-26 2022-06-25 tion Communication Technol ogy(ICT) Management Inform ation Coordinator PG-NCDC-280497-CS-INDV / Individual Consult IDA / 64050 Project Management Post Open 167,000.00 109,114.00 Signed 2022-03-04 2022-03-14 2022-04-22 2022-06-23 2022-05-13 2022-08-10 2022-06-17 2022-08-06 2022-12-14 NCD-CS-035- Procurement S ant Selection pecialist PG-NCDC-283286-CS-INDV / Individual Consult IDA / 64050 Project Management Prior Open 660,625.00 0.00 Signed 2022-03-10 2022-03-30 2022-04-28 2022-09-20 2022-05-19 2022-10-19 2022-06-23 2022-12-20 NCD-CS-026 Project Manager ant Selection PG-NCDC-319081-CS-INDV / Individual Consult IDA / 64050 Project Management Post Open - National 55,000.00 0.00 Signed 2022-10-05 2022-10-13 2022-11-23 2023-04-16 2022-12-14 2023-04-10 2023-01-18 2025-12-30 Media & Communication Offi ant Selection cer PG-NCDC-319083-CS-INDV / Individual Consult Direct - Internation IDA / 64050 Project Management Post 60,000.00 0.00 Signed 2022-10-11 2022-10-14 2022-10-21 2022-10-17 2022-11-11 2022-10-18 2022-12-16 2025-12-20 MIS Specialist ant Selection al PG-NCDC-317976-CS-INDV / Individual Consult IDA / 64050 Skills Training Post Open - National 100,000.00 0.00 Signed 2022-10-24 2022-10-14 2022-12-12 2023-02-28 2023-01-02 2023-03-01 2023-02-06 2025-11-02 NCD BLST Lead Trainer ant Selection PG-NCDC-282161-CS-CDS / IDA / 64050 Youth Job Corps Post Direct Selection Direct 29,577.00 0.00 Canceled 2022-03-03 2022-03-13 2022-05-17 2022-11-13 NCD-C-008A BLST Support As sistant PG-NCDC-282164-CS-CDS / IDA / 64050 Youth Job Corps Post Direct Selection Direct 29,577.00 0.00 Canceled 2022-03-03 2022-03-13 2022-05-17 2022-11-13 NCD-CS012A Junior Works Su pervisor 1 PG-NCDC-282166-CS-CDS / NCD-CS-012B Junior Works S IDA / 64050 Youth Job Corps Post Direct Selection Direct 29,577.00 0.00 Canceled 2022-03-03 2022-03-13 2022-05-17 2022-11-13 upervisor 2 PG-NCDC-335142-CS-INDV / Individual Consult Senior Public Works Engineer IDA / 64050 Youth Job Corps Prior Limited 570,000.00 0.00 Under Review 2023-01-13 2023-01-17 2023-01-18 2023-01-20 2023-02-08 2023-02-10 2023-03-15 2023-03-06 2025-07-02 ant Selection Team Leader PG-NCDC-335143-CS-INDV / Individual Consult Under Implement IDA / 64050 Youth Job Corps Post Limited 119,712.00 0.00 2023-01-13 2023-04-20 2023-01-18 2023-03-27 2023-02-08 2023-03-15 2025-07-02 Public Works Engineer ant Selection ation PG-NCDC-335145-CS-INDV / Individual Consult Under Implement IDA / 64050 Skills Training Post Limited 134,912.00 0.00 2023-01-23 2023-02-12 2023-01-28 2023-02-18 2023-03-25 2025-07-12 Skills Development Team Lea ant Selection ation der PG-NCDC-335151-CS-INDV / Individual Consult Under Implement Gender and Inclusion Speciali IDA / 64050 Project Management Post Open - National 120,505.00 0.00 2023-01-30 2023-02-12 2023-03-20 2023-04-10 2023-05-15 2025-09-01 ant Selection ation st Team Leader PG-NCDC-335152-CS-INDV / Individual Consult IDA / 64050 Project Management Prior Limited 594,236.00 0.00 Signed 2023-01-16 2023-01-17 2023-01-21 2023-03-08 2023-02-11 2023-04-03 2023-03-18 2023-04-15 2025-07-05 Senior Project Accountant ant Selection PG-NCDC-335144-CS-INDV / Individual Consult Under Implement IDA / 64050 Youth Job Corps Post Open - National 121,436.00 0.00 2023-01-23 2023-02-12 2023-03-13 2023-04-30 2023-04-03 2023-05-08 2025-08-25 Works Supervisors ant Selection ation PG-NCDC-335148-CS-INDV / Individual Consult Under Implement IDA / 64050 Skills Training Post Open - National 58,106.00 0.00 2023-04-03 2023-04-24 2023-05-22 2023-06-12 2023-07-17 2025-11-03 Employment Officer ant Selection ation PG-NCDC-335147-CS-INDV / Individual Consult IDA / 64050 Skills Training Post Open - National 119,712.00 0.00 Signed 2023-04-03 2023-04-10 2023-05-22 2023-05-25 2023-06-12 2023-05-25 2023-07-17 2025-11-03 Referrals Desk Coordinator ant Selection PG-NCDC-335146-CS-INDV / Individual Consult Interships & Vocational Traini IDA / 64050 Skills Training Post Open - National 119,712.00 0.00 Signed 2023-04-03 2023-04-06 2023-05-22 2023-05-15 2023-06-12 2023-05-17 2023-07-17 2025-11-03 ant Selection ng Coordinator PG-NCDC-335150-CS-INDV / Individual Consult Under Implement IDA / 64050 Skills Training Post Open - National 58,106.00 0.00 2023-04-03 2023-04-06 2023-05-22 2023-06-12 2023-07-01 2025-10-18 Micro-enterprise Officer ant Selection ation PG-NCDC-349820-CS-INDV / Individual Consult Direct - Internation Financial Management Syste IDA / 64050 Project Management Post 120,000.00 0.00 Signed 2023-03-20 2023-03-16 2023-03-30 2023-03-02 2023-04-20 2023-04-03 2023-05-25 2023-11-21 ant Selection al ms Consultant PG-NCDC-354554-CS-INDV / Individual Consult Social Safeguards/Occupatio IDA / 64050 Project Management Post Limited 119,712.00 0.00 Signed 2023-04-06 2023-04-03 2023-04-11 2023-05-15 2023-05-02 2023-05-15 2023-06-06 2023-12-03 ant Selection nal Health & Safety Specialist PG-NCDC-335149-CS-INDV / Individual Consult Under Implement IDA / 64050 Skills Training Post Open - National 58,106.00 0.00 2023-04-24 2023-04-19 2023-06-12 2023-07-03 2023-08-07 2025-11-24 Training Officer ant Selection ation PG-NCDC-356290-NC-RFQ / Individual Consult Under Implement IDA / 64050 Skills Training Post Open - National 99,760.00 0.00 2023-04-30 2023-06-18 2023-07-09 2023-08-13 2024-02-09 Training Quality Audit Officer ant Selection ation Page 2 PROCUREMENT PLAN (Textual Part) Project information: Papua New Guinea (PNG), PNG Agriculture Commercialization and Diversification Strategy, P-166222 Project Implementation agency: Department of Agriculture and Livestock (DAL); Cocoa Board (CB); and Coffee Industry Corporation (CIC) Date of the Procurement Plan: February 13, 2020 Period covered by this Procurement Plan: February 2020 – to August 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the National Procurement Act 2018, No. 12 of 2018, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. National preferences Eligibility: Eligibility to participate in a procurement process for and to be awarded a Bank financed contract shall be as defined under paragraphs 3.21-3.23 of the Procurement Regulations; accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in the said paragraphs. Foreign bidders shall be eligible to participate in bidding under the same conditions as national bidders. No domestic preference shall be granted in bid evaluation on the basis of bidder’s nationality, origin of goods or services, and/or preferential programs. Registration of bidders as Registration of bidders: condition for bidding Registration shall not be used to assess bidders’ qualifications. A foreign bidder shall not be required to register as a condition for submitting its bid, and a foreign bidder recommended for contract award shall be given a reasonable opportunity to register, with the reasonable cooperation of the Recipient, prior to contract signing. Procurement documents Procurement Documents: Templates of procurement documents, including contract forms, acceptable to the Association shall be used for all procurement financed by the Project. Document Fees Bidding Document Fees: A fee for bidding documents if applied must be reasonable and is to be used to offset the actual costs associated with reproduction of large bidding documents and associated plans and drawings. It is not to be used to generate revenue, or to limit or restrict participation in procurement processes. Bidding document fees are not to be charged for the procurement of consulting services (firms and individual), non-consulting services, or goods. Fraud and Corruption Fraud and Corruption: The procurement documents shall require that bidders submitting bids present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. Negotiations and Cancellation of all bids: cancellation of All bids (or the sole bid if only one bid is procurement process received) shall not be rejected, the procurement process shall not be cancelled, and new bids shall not be solicited without the Bank’s prior written concurrence. Complaints Handling Complaints Review Mechanism: The Recipient shall establish and implement an effective, fair and timely complaints review mechanism allowing bidders to complain and to have their complaints handled in a timely manner. Until an adequate complaints review mechanism (as assessed by the Bank) is established the Bank’s review mechanism as set out in the Procurement Regulations will apply. Contract Award Notice Publication of Contract Award Notice: For purposes of Article 36(5) of the Act, within one month from award, a notice of all procurement contract awards shall include, at a minimum as relevant and applicable for each procurement method (a) the name of each bidder that submitted a bid; (b) bid prices as read out at bid opening; (c) evaluated prices of each bid that was evaluated; (d) the names of bidders whose bids were either rejected as nonresponsive or not meeting qualification criteria, or not evaluated, with the reasons thereof; and (e) the name of the winning bidder, the final total contract price, as well as the duration and a summary of the scope of the contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. The above captioned conditions also apply when approaching the international market. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable; Works: Not Applicable PROCUREMENT Papua New Guinea : PNG Agriculture Commercialization and Diversification Project PLAN General Information Country: Papua New Guinea 2021-07-23 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166222 GPN Date: 2020-12-12 Project Name: PNG Agriculture Commercialization and Diversification Project Loan / Credit No: IDA / 64660 Cocoa Board Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure PG-CB-365240-CW-RFQ / Co Institutional Capacity Buildin Request for Quota Single Stage - One E ment Document - Pending Imp 2024-02-2 IDA / 64660 Post Open - National 800,000.00 0.00 2023-07-08 2023-09-02 coa Board Office Extension g tions nvelope 1 Envelope proce lementation 9 ss (Non Bank-SPD ) Request for Bids - PG-CB-365241-CW-RFB / RE Single Stage - One E Small Works SPD Pending Imp 2024-04-1 HABILITATION OF TEHOBUIN- IDA / 64660 Agriculture Feeder Roads Post Request for Bids Open - National 1,400,000.00 0.00 2023-06-26 2023-07-01 2023-08-12 2023-09-11 2023-10-16 nvelope (1 envelope proce lementation 3 SIPOTAVAI FEEDER ROAD ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-CB-236465-CS-INDV / Se Project Management and Mo Individual Consult IDA / 64660 Post Open 180,000.00 95,473.98 Signed 2021-06-01 2021-12-03 2021-07-20 2022-03-09 2021-08-10 2022-04-03 2021-09-14 2022-04-06 2022-03-13 nior Procurement Officer, Coc nitoring and Evaluation ant Selection oa PMU PG-CB-236457-CS-INDV / Pro Project Management and Mo Individual Consult IDA / 64660 Prior Open 1,200,000.00 0.00 Canceled 2021-06-01 2021-07-20 2021-08-10 2021-09-14 2022-03-13 ject Manager, Cocoa PMU nitoring and Evaluation ant Selection PG-CB-236483-CS-INDV / Mo Project Management and Mo Individual Consult nitoring, Evaluation and Surv IDA / 64660 Post Open 220,000.00 0.00 Signed 2021-06-01 2021-12-02 2021-07-20 2022-04-21 2021-08-10 2022-04-25 2021-09-14 2022-03-13 nitoring and Evaluation ant Selection ey Officer (MESO) PG-CB-236466-CS-INDV / Pro Individual Consult ductive Partnership Coordina IDA / 64660 Productive Partnerships Prior Open 360,000.00 162,547.92 Signed 2021-06-01 2021-12-02 2021-07-20 2022-07-13 2021-08-10 2022-08-09 2021-09-14 2022-09-06 2022-03-13 ant Selection tor, Cocoa PMU PG-CB-248924-CS-INDV / En Project Management and Mo Individual Consult IDA / 64660 Post Open 210,000.00 102,862.53 Terminated 2021-08-18 2021-12-03 2021-10-06 2022-03-10 2021-10-27 2022-03-10 2021-12-01 2022-03-15 2022-05-30 vironmental and Social Office nitoring and Evaluation ant Selection r PG-CB-255259-CS-INDV / Pro Project Management and Mo Individual Consult ject Manager, Cocoa Project IDA / 64660 Prior Open 540,000.00 0.00 Canceled 2021-09-28 2021-11-16 2021-12-07 2022-01-11 2022-07-10 nitoring and Evaluation ant Selection Management Unit PG-CB-260469-CS-INDV / Pro Project Management and Mo Individual Consult ject Manager, Cocoa Project IDA / 64660 Prior Open 424,000.00 0.00 Signed 2021-10-29 2021-11-10 2021-12-17 2022-08-16 2022-01-07 2022-09-07 2022-02-11 2023-05-21 2022-08-10 nitoring and Evaluation ant Selection Management Unit PG-CB-236464-CS-INDV / Se Project Management and Mo Individual Consult IDA / 64660 Prior Open 420,000.00 0.00 Canceled 2021-08-05 2021-09-23 2021-10-14 2021-11-18 2022-05-17 nior Finance Officer, Cocoa P nitoring and Evaluation ant Selection MU PG-CB-266764-CS-INDV / Se Project Management and Mo Individual Consult IDA / 64660 Post Open 240,000.00 105,303.92 Signed 2021-12-07 2021-12-07 2022-01-25 2022-03-01 2022-02-15 2022-02-28 2022-03-22 2022-03-01 2025-12-01 nior Finance Officer, Cocoa P nitoring and Evaluation ant Selection MU PG-CB-236467-CS-INDV / Se Individual Consult IDA / 64660 Agriculture Feeder Roads Prior Open 377,000.00 0.00 Canceled 2021-08-05 2021-09-23 2021-10-14 2021-11-18 2022-05-17 nior Engineer, Cocoa PMU ant Selection PG-CB-266765-CS-INDV / Co Individual Consult Under Implement IDA / 64660 Agriculture Feeder Roads Post Open 295,000.00 0.00 2021-12-08 2022-11-21 2022-01-26 2022-02-16 2022-03-23 2025-12-02 coa PMU Senior Engineer ant Selection ation PG-CB-300445-CS-INDV / Pro Project Management and Mo Individual Consult ductive Partnerships Officer- IDA / 64660 Post Open - National 120,000.00 0.00 Signed 2022-08-01 2022-07-31 2022-09-19 2023-01-17 2022-10-10 2023-02-28 2022-11-14 2024-11-03 nitoring and Evaluation ant Selection PMU Madang PG-CB-300446-CS-INDV / Par Project Management and Mo Individual Consult IDA / 64660 Post Open - National 90,000.00 0.00 Canceled 2022-08-01 2022-09-19 2022-10-10 2022-11-14 2024-11-03 tnership Finance Officer nitoring and Evaluation ant Selection PG-CB-300447-CS-INDV / MI Project Management and Mo Individual Consult IDA / 64660 Post Open - National 167,000.00 0.00 Signed 2022-08-01 2022-08-02 2022-09-19 2023-02-14 2022-10-10 2023-02-28 2022-11-14 2024-11-03 S Officer PMU Kokopo nitoring and Evaluation ant Selection PG-CB-300227-CS-INDV / Ad Project Management and Mo Individual Consult IDA / 64660 Post Open - National 49,308.00 0.00 Signed 2022-08-01 2022-08-17 2022-09-19 2023-01-17 2022-10-10 2023-02-02 2022-11-14 2024-11-03 ministrative Assistant nitoring and Evaluation ant Selection Page 1 PG-CB-300444-CS-INDV / Pro ductive Partnership Officer-E Project Management and Mo Individual Consult IDA / 64660 Post Open - National 143,000.00 0.00 Signed 2022-08-01 2022-08-17 2022-09-19 2023-01-17 2022-10-10 2023-02-28 2022-11-14 2024-11-03 ast New Britain Province (EN nitoring and Evaluation ant Selection B), Autonomous Region of Bo ugainville (ARoB) PG-CB-317954-CS-INDV / En Project Management and Mo Individual Consult vironmental and Social Office IDA / 64660 Post Open - National 200,000.00 0.00 Signed 2022-09-30 2022-11-20 2022-11-18 2023-05-15 2022-12-09 2023-05-30 2023-01-13 2025-01-02 nitoring and Evaluation ant Selection r Cocoa PMU PG-CB-330713-CS-INDV / Fin Project Management and Mo Individual Consult IDA / 64660 Post Open - National 86,614.00 0.00 Canceled 2022-12-08 2023-01-26 2023-02-16 2023-03-23 2023-09-19 ance Assistant nitoring and Evaluation ant Selection PG-CB-344966-CS-INDV / MS Individual Consult Under Implement IDA / 64660 Productive Partnerships Post Open - National 143,136.00 0.00 2023-02-23 2023-03-31 2023-04-13 2023-05-04 2023-06-08 2023-12-05 ME Development Officer ant Selection ation PG-CB-344968-CS-INDV / Inf Project Management and Mo Individual Consult IDA / 64660 Post Open - National 240,000.00 0.00 Canceled 2023-02-23 2023-03-30 2023-04-13 2023-05-04 2023-06-08 2023-12-05 ormation Communications Of nitoring and Evaluation ant Selection ficer PG-CB-363608-CS-INDV / Inf Project Management and Mo Individual Consult Pending Impleme IDA / 64660 Post Limited 240,000.00 0.00 2023-05-29 2023-06-03 2023-06-24 2023-07-29 2024-01-25 ormation Communications Of nitoring and Evaluation ant Selection ntation ficer PG-CB-363610-CS-INDV / Fin Project Management and Mo Individual Consult Pending Impleme IDA / 64660 Post Limited 86,614.00 0.00 2023-06-30 2023-07-05 2023-07-26 2023-08-30 2024-02-26 ance Assistant nitoring and Evaluation ant Selection ntation PG-CB-363611-CS-INDV / Par Individual Consult Pending Impleme IDA / 64660 Productive Partnerships Post Limited 90,000.00 0.00 2023-08-01 2023-08-06 2023-08-27 2023-10-01 2024-03-29 tnership Finance Officer ant Selection ntation Page 2 18-MONTH PROCUREMENT PLAN Project information: Phase I of Improved Child Survival Program for Human Capital MPA- P167156-- Immunization Plus and Malaria Progress by Accelerating Coverage and Transforming Services (IMPACT) Project Project Implementation Agencies: Federal Ministry of Health (NMEP and NPHCDA) Date of the Procurement Plan: January 1, 2020 Period covered by this Procurement Plan: January 2020 to June 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016), revised on November 1, 2017 and on August 1, 2018 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Nigeria Public Procurement Act 2007, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [15% is applicable for those contracts identified in the Procurement Plan tables]; Works: [ 7.5% is applicable for those contracts identified in the Procurement Plan tables] I. Threshold for Prior Review – Goods, Works, Non-Consulting Services and Consulting Services Prior-review Thresholds Thresholds for Procurement Methods High Substanti Moderate Low Risk Goods, IT & Non-Consulting Shortlist of National Procurement Type Risk al Risk Risk Works ($'000) ($'000) ($'000) ($'000) Services Consultants Request Request Engineering Open for for Open Open Open Consultin & Quotatio Quotatio 10,0 15,0 20,0 Internatio National internatio National g Constructio Works n or n or 5,000 00 00 00 nal or ICB or NCB National nal or ICB or NCB National Services n ($'000) ($'000) ($'000) ($'000) ($'000) Supervision Shopping Shopping ($'000) ($'000) ($'000) Goods, IT & Non- 2,0 4,0 6,0 Consulting Services 1,500 00 00 00 ≧ < ≦ ≧ < ≦ < ≦ Consultants 1,0 2,0 4,0 20,0 20,0 5,0 5,0 1 3 5 200 (Firms) 500 00 00 00 00 00 00 00 00 00 00 Post Review: All contracts not subject to prior review shall be subject to post review. Summary of the procurement packages for Goods, Works and Non-Consulting Services (Planned for the first 18 months after project effectiveness): Selec Evaluation Market tion Options Approa Review Meth (Most Expected ch Prequal- Domestic Expected by od Advantageo date of Sr. Contract Estimated (Open- ification Preferenc date of Bank (RFP, us Bid, bid/ No Description Cost (US$) Nation (Yes/ e Contract (Prior/ RFB, BAFO, proposal al/ No) (Yes/No) Signature Post) RFQ, Rated opening Limited DS Criteria etc.) etc.) etc.) Nigeria Malaria Elimination Programme (NMEP) GOODS Procurement of Long Lasting Open- Insecticide Internati Most Treated Nets 45,852,523 3rd Feb 13th July 1 Prior onal RFB Advantageou No Yes (Mass .29 2020 2020 s Bid Campaign & Routine Distribution) Procurement of Artemisinin based Open - Most National 3rd Feb 13th July 2 Combination Post 2,381,472 RFB Advantageou No No 2020 2020 Therapy (ACT)- s Bid (Public and Private) Procurement of Open- Most Rapid National 3rd Feb 13th July 3 Post 1,960,202 RFB Advantageou No No Diagnostics 2020 2020 s Bid Tests (RDTs) Most Artesunate Open- 3rd Feb 13th July 4 Post 420,881.89 RFB Advantageou No No Injection National 2020 2020 s Bid Sulphodoxine/P Most Open - 3rd Feb 13th July 5 yrimethamine_I Post 612,322 RFB Advantageou No No National 2020 2020 PTp s Bid Amodiaquine/Su Most lphodoxine/Pyri 2,990,781. Open - 3rd Feb 13th July 6 Post RFB Advantageou No No methamine 47 National 2020 2020 s Bid (SPAQ) Most Open - 3rd Feb 13th July 7 Sharp Boxes Post 152,122,43 RFB Advantageou No No National 2020 2020 s Bid Most Microscope Open - 3rd Feb 13th July 8 Post 491,031 RFB Advantageou No No commodities National 2020 2020 s Bid NON-CONSULTING SERVICES - NMEP State Malaria Elimination MOU/P Programme erform 10th 2,250,000. 9th July 1 (SMEP) Prior Limited ance Rated Criteria No NA February 00 2020 Performance Contra 2020 Contract and ct Operations National Malaria Elimination MOU/P Programme erform 10th 1,500,000. 9th July 2 (NMEP) Prior Limited ance Rated Criteria No NA February 00 2020 Performance Contra 2020 Contract and ct Operations National Primary Health Care Development Agency (NPHCDA) GOODS Procurement of Most vaccines and 61,380,767 5th Feb 13th July 1 Prior UN RFB Advantageou No No devices for .00 2020 2020 s Bid immunization Procurement and maintenance of Most UN 5th Feb 13th July 2 Generators and Post 900,000.00 RFB Advantageou No No System 2020 2020 Cold Chain s Bid Equipment (CCEs) Procurement and installation of Cold Chain Most 4,500,000. 5th Feb 13th July 3 Hubs (3 Prior UN RFB Advantageou No No 00 2020 2020 walking-in cold s Bid rooms) in Lagos Procurement of Emergency Transport 5th Feb 13th July 4 Service (ETS) Post 45,101.72 Limited RFQ Rated Criteria No No 2020 2020 vouchers, handbooks, and logbooks Procurement of Most Open- 5th Feb 13th July 5 equipment for Post 281,969.00 RFB Advantageou No No National 2020 2020 call centre s Bid Most Procurement of Open- 5th Feb 13th July 6 Post 969,529.00 RFB Advantageou No No 14 vehicles National 2020 2020 s Bid Procurement of 5th Feb 13th July 7 14 computer Post 14,000 Limited RFQ Rated Criteria No No 2020 2020 sets II. Summary of the procurement packages for Consulting Services -Planned for the first 18 months after project effectiveness): Selection Market Method Review Approach Expected Expected Estimate (QCBS, Shortlisti Sr. by Bank (Open - date of bid/ date of Contract Description d Cost FBS, ng No (Prior/ International proposal Contract (US$) LCBS, (Yes/ No) Post) / National/ opening Signature QBS, CQS, etc.) DS etc.) Nigeria Malaria Elimination Programme (NMEP) NGOs Service Contract (for 5 11,525,51 Open 10th Feb 31st Aug 1 Prior QCBS Yes states) 1.00 International 2020 2020 Technical Assistance to SMEP in 5 participating states, 630,000.0 10th Feb 31st July 2 Prior Limited INDV No multiple contracts by 0 2020 2020 different consultants Technical Assistance to NMEP (including procurement 150,000.0 10th Feb 31st July 3 Post Limited INDV No consultant), multiple 0 2020 2020 contracts. Independent Verification 300,000.0 Open- 10th Feb 31st July 4 Post CQS No Agents (IVA) for NGOs 0 National 2020 2020 Social and Behavioral Change 3,000,000. Open 10th Feb 31st Aug 5 Prior QCBS Yes Communication (SBCC) 00 International 2020 2020 Operations research on 2,131,148. Open 10th Feb 31st Aug 6 Prior QCBS Yes disease vector mapping 00 International 2020 2020 Operations research on entomological surveillance by 655,738.0 10th Feb 31st July 7 Prior Direct DS No Nigeria Institute of 0 2020 2020 Medical Research (NIMR) Operations research on therapeutic efficacy by 655,738.0 10th Feb 31st July 8 Prior Direct CDS No Nigeria Institute of 0 2020 2020 Medical Research (NIMR) Consultancy on warehouse 10th Feb 31st July 9 Post 32,131.00 Limited INDV No assessment 2020 2020 Programme Management Training (case management, 2,000,000. 10th Feb 31st July 10 Prior Limited INDV No M&E, IVM etc.) Multiple 00 2020 2020 Contracts National Primary Health Care Development Agency (NPHCDA) Technical assistance support 9,869,000. 10th Feb 31st July 1 to government for polio Prior UN CDS No 00 2020 2020 surveillance Technical assistance support to government for polio 15,301,00 10th Feb 31st July 2 Supplemental Immunization Prior UN CDS No 0.00 2020 2020 Activities (SIAs) surveillance through WHO Technical assistance support to government for polio 4,830,000. 10th Feb 31st July 3 logistics and social Prior UN CDS No 00 2020 2020 mobilization for polio through UNICEF Procurement of consultant for 10th Feb 31st July 4 Post 20,000.00 Limited INDV No landscape survey (SQUATS) 2020 2020 Technical assistance support 837,673.1 10th Feb 31st July 5 Prior Open-National INDV No to 12 SPHCDA PIU 3 2020 2020 Technical assistance support 10th Feb 31st July 6 Post 89,750.63 Limited INDV No to NPHCDA PIU 2020 2020 Procurement of Emergency Transport Services (ETS), MOU with National Union of 530,794.3 10th Feb 31st July 7 Prior Direct CDS No Road Transport Workers 9 2020 2020 (NURTW) and NACTOROMAS Training of ETS service providers, MOU with Federal 207,672.0 10th Feb 31st July 8 Post Direct CDS No Road Safety Commission 0 2020 2020 (FRSC) Conduct PAPA – Lot Quality Assurance Sampling, MOU 2,213,850. 10th Feb 31st July 9 Prior Limited CDS No with National Bureau of 00 2020 2020 Statistics (NBS) Consultancy for RCT research 1,902,356. 10th Feb 31st Aug 10 services with Nigerian Prior Open-National QCBS Yes 00 2020 2020 Universities Procurement of operations 1,689,751. Open- 10th Feb 31st Aug 11 Prior QCBS Yes research services 00 International 2020 2020 Support to Cold Chain Equipment (CCE) 23,000,00 10th Feb 31st July 12 Prior UN CDS No optimization platform 0.00 2020 2020 through UNICEF Technical assistance to 1,553,185. 10th Feb 31st July 13 LGHAs (89 total), multiple Post Open-National INDV No 50 2020 2020 contracts Technical assistance 310,076.0 10th Feb 31st July 14 Post Open-National QCBS Yes management firm 0 2020 2020 10th Feb 31st July 15 IVA for performance contract Post 300,000 Open-National CQS No 2020 2020 Procurement of services 3,203,345 Open- 10th Feb 31st Aug 16 for GIS imagery and Prior QCBS Yes .45 International 2020 2020 microplanning Procurement of Social Behaviour Change Open- 10th Feb 31st Aug 17 Prior 5,000,000 QCBS Yes Communication (SBCC) International 2020 2020 services Contracting of direct 2,000,000. Open- 10th Feb 31st Aug 18 Prior QCBS Yes facility financing firms 00 International 2020 2020 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a 1Guidelineson Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Nigeria : Nigeria Improved Child Survival Program for Human Capital MPA PLAN General Information Country: Nigeria 2022-08-22 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167156 GPN Date: Project Name: Nigeria Improved Child Survival Program for Human Capital MPA Loan / Credit No: IDA / 65390 Lagos MPA Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-LAGOS MPA-362330-GO- Component 1:Malaria Contro Request for Quota Single Stage - One E Under Imple IDA / 65390 Post Limited 4,737.00 0.00 2023-06-21 2023-08-16 2024-02-12 RFQ / Procurement of Office l tions nvelope mentation Equipment NG-LAGOS MPA-362342-GO- RFQ / Procurement of ICT offi Component 1:Malaria Contro Request for Quota Single Stage - One E Under Imple ce equipment’s and other Ac IDA / 65390 Post Limited 43,331.00 0.00 2023-06-06 2023-08-01 2024-01-28 l tions nvelope mentation cessories for 11 PIUs membe rs (PIUs) & 20 Focal Persons i n LGAs NG-LAGOS MPA-310290-GO- RFQ / Procurement of 18 Sea Component 1:Malaria Contro Request for Quota Single Stage - One E IDA / 65390 Post Limited 65,789.47 0.00 Canceled 2022-08-24 2022-10-19 2023-04-17 ter Bus Passanger for Project l tions nvelope Operational Vehicle NG-LAGOS MPA-310295-GO- Component 1:Malaria Contro Request for Quota Single Stage - One E RFQ / Procurement of Office IDA / 65390 Post Limited 6,944.72 0.00 Canceled 2022-08-24 2022-10-19 2023-04-17 l tions nvelope Equipment and Furnitures NG-LAGOS MPA-311425-GO- RFQ / Procurement of ICT offi Component 1:Malaria Contro Request for Quota Single Stage - One E IDA / 65390 Post Limited 38,834.21 0.00 Canceled 2022-09-16 2022-11-11 2023-05-10 ce equipment’s and other Ac l tions nvelope cessories for project operatio ns NG-LAGOS MPA-311431-GO- RFQ / Procurement of workin Component 1:Malaria Contro Request for Quota Single Stage - One E IDA / 65390 Post Limited 20,236.84 0.00 Canceled 2022-09-26 2022-11-21 2023-05-20 g tools for project operation l tions nvelope and monitoring within 20 LG As for focal persons NG-LAGOS MPA-362346-GO- Component 1:Malaria Contro Request for Quota Single Stage - One E Pending Impl RFQ / Procurement of 18-Sea IDA / 65390 Post Limited 97,577.00 0.00 2023-06-05 2023-07-31 2024-01-27 l tions nvelope ementation ter Bus for Project Operation s NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LAG-IMPACT-QCBS-RFP-01/2 3 / Engagement of NON State Actors/NGOs to carryout full Component 1:Malaria Contro Quality And Cost- Under Implement IDA / 65390 Prior Open - National 3,658,331.00 0.00 2023-05-19 2023-06-01 2023-06-09 2023-06-01 2023-07-23 2023-06-02 2023-08-20 2023-09-19 2023-10-24 2023-11-28 2024-11-27 scale implementation of the l Based Selection ation Malaria Interventions Service s Using Performance Based C ontract INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 PROCUREMENT PLAN (Textual Part) Project Country: Kyrgyz Republic information Full Project Name: Enhancing the Foundation of Learning Total Finance ($): USD 4,800,000 Project Number: P173601 Project Implementation agency Ministry of education and science of the Kyrgyz Republic Date of the Procurement Plan June 15, 2021 Period covered by this Procurement July 2021 – February 1, 2025 Plan: Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), procurement of goods under World Bank financed operations may be carried out in accordance with “Single-Stage Bidding” method set forth in the Public Procurement Law of the Kyrgyz Republic dated April 3, 2015 № 72 (the “PPL”) with amendments dated November 18, 2016 No. 182, December 10, 2016 No. 195, February 14, 2017 No. 25, May 30, 2017 No. 93, March 29, 2018 No. 32, January 11, 2019 No. 4, June 26, 2019 No. 76, 20 April 2020 No. 48, December 18, 2020 No. 8, March 5, 2021 No. 28, provided that such arrangements continue to meet requirements of the paragraph 5.4 of the Procurement Regulations and the following conditions: • The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; • Bidding documents, including contract forms, acceptable to the Bank shall be used. Bidding documents shall include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social, health and safety (“ESHS”) risks and impacts. • The Bidding process shall not be cancelled solely on the reason that minimum bid price is larger than the amount allocated by procuring entity for the procurement. • There shall be no preference applied during procurement of goods and works. • Implementing agency shall have an option to publish procurement notice without disclosing cost estimate. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Other national procurement arrangements such as “Simplified Method” (Request for Quotation) may be applied on the same conditions stated above for procuring limited quantities of readily available off-the-shelf goods or simple civil works of small value. In addition, not less than three quotations shall be requested to ensure competition. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable. PROCUREMENT Kyrgyz Republic : Enhancing the Foundation of Learning PLAN General Information Country: Kyrgyz Republic 2021-10-28 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173601 GPN Date: 2022-04-12 Project Name: Enhancing the Foundation of Learning Loan / Credit No: / , TF / B6138 Ministry of Education and Science of the Kyrgyz Republic Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - Component 1: Expanding pr KG/GPE/CW/RFB-01 / Sanitar Single Stage - One E Small Works SPD 2023-07-2 / eschool education for under- Post Request for Bids Open - National 1,110,000.00 0.00 Canceled 2022-10-31 2022-11-05 2022-12-17 2023-01-16 2023-02-20 y facilities nvelope (1 envelope proce 0 served children ss) Request for Bids - Component 1: Expanding pr KG/GPE/CW/RFB-02 / Renova Single Stage - One E Small Works SPD 2023-06-2 / eschool education for under- Post Request for Bids Open - National 732,000.00 0.00 Canceled 2022-10-31 2022-11-05 2022-12-17 2023-01-16 2023-02-20 tion nvelope (1 envelope proce 0 served children ss) Request for Bids - Component 1: Expanding pr KG/GPE/CW/RFB-03 / Renova Single Stage - One E Small Works SPD Under Imple 2023-10-0 TF / B6138 eschool education for under- Post Request for Bids Open - National 1,842,000.00 0.00 2023-02-15 2023-02-22 2023-02-20 2023-04-03 2023-04-10 2023-05-03 2023-06-07 tion and Sanitary facilities nvelope (1 envelope proce mentation 5 served children ss) Request for Bids - KG/GPE/CW/RFB-03A / Renov Component 1: Expanding pr Single Stage - One E Small Works SPD Pending Imp 2024-03-1 ation and Sanitary facilities f TF / B6138 eschool education for under- Post Request for Bids Open - National 796,772.00 0.00 2023-05-31 2023-06-05 2023-07-17 2023-08-16 2023-09-20 nvelope (1 envelope proce lementation 8 or 31 CbKs served children ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG/GPE/G/RFQ-02 / Guidanc Component 1: Expanding pr Request for Quota Single Stage - One E Pending Impl e for parents on story books r / eschool education for under- Post Open - National 9,400.00 0.00 2023-01-05 2023-03-02 2023-04-01 tions nvelope ementation eading served children Component 1: Expanding pr KG/GPE/G/RFQ-03 / Story bo Request for Quota Single Stage - One E Pending Impl / eschool education for under- Post Open - National 76,930.00 0.00 2023-01-04 2023-03-01 2023-05-30 oks tions nvelope ementation served children KG/GPE/G/RFQ-05 / Replicati Component 2: Improving pol Request for Quota Single Stage - One E Pending Impl on of materials on pre-school / icy & finance for the system Post Open - National 4,000.00 0.00 2022-01-05 2022-03-02 2022-04-01 tions nvelope ementation teacher competencies frame effectiveness work KG/GPE/G/RFQ-06 / Replicati Component 3: Ensuring citiz Request for Quota Single Stage - One E Pending Impl on of state standards, Balaly / ens’ engagement and imple Post Open - National 77,000.00 0.00 2022-01-05 2022-03-02 2022-05-01 tions nvelope ementation k programs, etc. mentation support Component 3: Ensuring citiz KG/GPE/G/RFQ-07 / Compute Request for Quota Single Stage - One E Pending Impl / ens’ engagement and imple Post Open - National 5,000.00 0.00 2021-11-05 2021-12-31 2022-01-30 r equipment for PIU tions nvelope ementation mentation support Component 3: Ensuring citiz KG/GPE/G/RFQ-08 / Vehicle f Request for Quota Single Stage - One E TF / B6138 ens’ engagement and imple Post Open - National 27,000.00 0.00 Signed 2021-11-05 2021-12-31 2022-01-30 or PIU tions nvelope mentation support Component 3: Ensuring citiz KG/GPE/G/RFQ-09 / Compute Request for Quota Single Stage - One E TF / B6138 ens’ engagement and imple Post Open - National 15,000.00 0.00 Signed 2022-04-20 2022-06-15 2022-07-15 r equipment for PIU tions nvelope mentation support Component 3: Ensuring citiz KG/GPE/G/RFQ-10 / Furniture Request for Quota Single Stage - One E TF / B6138 ens’ engagement and imple Post Open - National 15,000.00 0.00 Signed 2022-04-20 2022-06-15 2022-07-15 for PIU tions nvelope mentation support KG/GPE/G/RFB-04 / Box with Component 1: Expanding pr Single Stage - One E Pending Impl sample of learning materials TF / B6138 eschool education for under- Post Request for Bids Open - National 152,000.00 0.00 2022-12-29 2023-01-03 2023-02-14 2023-03-16 2023-04-20 2023-07-19 nvelope ementation for inclusive education served children Component 1: Expanding pr Request for Quota Single Stage - One E KG/GPE/G/RFQ-01 / Carpets / eschool education for under- Post Open - National 50,400.00 0.00 Canceled 2023-02-05 2023-04-02 2023-07-01 tions nvelope served children KG-MES KR-G-RFB-2023-6B / Component 1: Expanding pr Open - Internationa Single Stage - One E Pending Impl Carpets for 500 CbKs (LFP) a TF / B6138 eschool education for under- Post Request for Bids 50,400.00 0.00 2023-02-28 2023-03-05 2023-04-16 2023-05-16 2023-06-20 2023-12-17 l nvelope ementation nd 60 CbKs (EFL) served children KG-MES KR-G-RFB-2023-5 / Component 1: Expanding pr Open - Internationa Single Stage - One E Pending Impl A package of development to TF / B6138 eschool education for under- Post Request for Bids 30,000.00 0.00 2023-02-28 2023-03-05 2023-04-16 2023-05-16 2023-06-20 2023-10-18 l nvelope ementation ys for 335 CbKs (LFF) and 60 served children CbKs (EFL) Component 1: Expanding pr KG/GPE/G/RFB-01 / Furniture Open - Internationa Single Stage - One E / eschool education for under- Post Request for Bids 108,000.00 0.00 Canceled 2022-11-30 2022-12-05 2023-01-16 2023-02-15 2023-03-22 2023-09-18 for 60 CbKs l nvelope served children KG-MES KR-G-RFB-2023-4 / F Component 1: Expanding pr Open - Internationa Single Stage - One E Under Imple urniture for 335 CbKs (LFP) a TF / B6138 eschool education for under- Post Request for Bids 108,000.00 0.00 2023-02-28 2023-03-10 2023-03-05 2023-04-16 2023-04-25 2023-05-16 2023-06-20 2023-12-17 l nvelope mentation nd 60 CbKs (EFL) served children KG-MES KR-G-RFB_2023-3 / Component 1: Expanding pr Open - Internationa Single Stage - One E Under Imple Playgrounds for 335 CbKs (L TF / B6138 eschool education for under- Post Request for Bids 270,000.00 0.00 2023-02-28 2023-03-10 2023-03-05 2023-04-16 2023-04-24 2023-05-16 2023-06-20 2023-12-17 l nvelope mentation FF) and 60 CbKs (EFL) served children Component 1: Expanding pr KG/GPE/G/RFB-02 / Teacher' Single Stage - One E Pending Impl TF / B6138 eschool education for under- Post Request for Bids Open - National 135,600.00 0.00 2023-03-31 2023-04-05 2023-05-17 2023-06-16 2023-07-21 2023-09-09 s Learning materials nvelope ementation served children NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Page 1 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Expanding pr KG/GPE/CS/CQS-02 / Technic Consultant Qualifi Under Implement / eschool education for under- Post Open - National 90,000.00 0.00 2022-10-31 2023-02-09 2022-11-21 2023-01-04 2023-02-03 2023-03-10 2023-08-07 hal supervision cation Selection ation served children KG/GPE/CS/CQS-05 / Revisio Component 2: Improving pol Consultant Qualifi Pending Impleme n of PCF model developed un / icy & finance for the system Post Open - National 25,000.00 0.00 2021-12-31 2022-01-21 2022-03-06 2022-04-05 2022-05-10 2022-08-08 cation Selection ntation der KEEP GPE effectiveness Component 3: Ensuring citiz KG/GPE/CS/CQS-06 / Evaluati Consultant Qualifi Pending Impleme / ens’ engagement and imple Post Open - National 80,000.00 0.00 2024-12-01 2024-12-22 2025-02-04 2025-03-06 2025-04-10 2025-07-09 on of the project impact cation Selection ntation mentation support Component 1: Expanding pr KG/GPE/CS/CQS-03 / Commu Consultant Qualifi / eschool education for under- Post Open - National 60,000.00 0.00 Canceled 2021-10-31 2021-11-21 2022-01-04 2022-02-03 2022-03-10 2022-06-08 nity mobilization cation Selection served children KG/GPE/CS/CQS-08 / Design Component 1: Expanding pr Consultant Qualifi Under Implement of a digital format of the trai TF / B6138 eschool education for under- Post Open - National 35,500.00 0.00 2022-04-28 2022-09-15 2022-05-19 2022-07-02 2022-08-01 2022-09-05 2023-03-04 cation Selection ation ning course served children KG/GPE/CS/CQS-07 / Implem entation of a normative finan cing model (training of distric Component 2: Improving pol Consultant Qualifi Under Implement t educational institutions, dir TF / B6138 icy & finance for the system Post Open - National 120,000.00 0.00 2022-05-30 2022-10-10 2022-06-20 2022-08-03 2022-09-02 2022-10-07 2023-09-07 cation Selection ation ectors of educational instituti effectiveness ons, a / o, consultations on st atistical planning and manag ement, budgeting) KG/GPE/CS/QCBS-01 / Traini ngs for teachers of full-time k indergartens, teachers of uni Component 1: Expanding pr Quality And Cost- Open - Internationa Under Implement versities / secondary schools TF / B6138 eschool education for under- Prior 619,450.00 0.00 2022-06-30 2022-09-21 2022-07-21 2022-10-17 2022-09-03 2023-04-19 2022-10-01 2023-05-25 2022-10-31 2022-12-05 2023-01-09 2023-05-09 Based Selection l ation and RIPPC / OIPK and teacher served children s of the RayED (inclusion, chi ld development monitoring, c ollaborative reading techniqu es) KG/GPE/CS/CQS-01 / Develo Component 1: Expanding pr Consultant Qualifi pment of design and estimat / eschool education for under- Post Open - National 120,000.00 0.00 Canceled 2022-02-28 2022-03-21 2022-05-04 2022-06-03 2022-07-08 2022-11-05 cation Selection e documentation served children Component 3: Ensuring citiz KG/GPE/CS/LCS-01 / Project Least Cost Selecti Open - Internationa / ens’ engagement and imple Post 70,000.00 0.00 Canceled 2021-10-31 2021-11-21 2022-01-04 2022-02-01 2022-03-03 2022-04-07 2022-05-12 2025-09-13 Audit on l mentation support INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG/GPE/CS/IC-10 / Local con Component 2: Improving pol sultant for the development Individual Consult Pending Impleme TF / B6138 icy & finance for the system Post Open 3,500.00 0.00 2022-04-29 2022-06-17 2022-07-08 2022-08-12 2022-12-10 and implementation of an ele ant Selection ntation effectiveness ctronic application for digital EDI observation KG/GPE/CS/IC-5A / Local con sultant on the development o Component 2: Improving pol f public management mecha Individual Consult TF / B6138 icy & finance for the system Post Open 6,000.00 0.00 Under Review 2022-05-30 2022-12-05 2022-07-18 2022-08-08 2022-09-12 2023-03-26 nisms (NPA) for the impleme ant Selection effectiveness ntation of public-private part nerships in the preschool edu cation sector KG/GPE/CS/IC-01B / Local co nsultant to finalize training m odules on safe environments, Component 1: Expanding pr Individual Consult Under Implement ensuring acceptable behavio TF / B6138 eschool education for under- Post Open 2,000.00 0.00 2022-05-30 2022-10-26 2022-07-18 2022-08-08 2022-09-12 2022-11-26 ant Selection ation r for disease prevention after served children the COVID-19 crisis (includin g hygiene issues, efficient us e of space, etc.) KG/GPE/CS/IC-07 / Local con sultant for the development Component 1: Expanding pr Individual Consult Under Implement of methodological recommen TF / B6138 eschool education for under- Post Open 3,500.00 0.00 2022-05-30 2022-09-01 2022-07-18 2022-08-08 2022-09-12 2022-12-26 ant Selection ation dations for differentiated inst served children ruction of preschool children KG/GPE/CS/IC-06A / Local co Component 2: Improving pol nsultant for the development Individual Consult Under Implement TF / B6138 icy & finance for the system Post Open 3,000.00 0.00 2022-05-30 2022-09-21 2022-07-18 2022-08-08 2022-09-12 2022-12-26 of a partial modular program ant Selection ation effectiveness for STEM education for presc hoolers KG/GPE/CS/IC-05B / Local co nsultant on the development Component 2: Improving pol of mechanisms and a system Individual Consult TF / B6138 icy & finance for the system Post Open 6,000.00 0.00 Under Review 2022-05-30 2022-10-28 2022-07-18 2022-08-08 2022-09-12 2023-03-26 of measures to improve the e ant Selection effectiveness fficiency of organizational, m anagerial and financial and e conomic mechanisms of PPP KG/GPE/CS/IC-04 / Internatio Component 2: Improving pol nal consultant on the develo Individual Consult Under Implement TF / B6138 icy & finance for the system Post Open 16,000.00 0.00 2022-05-30 2022-10-28 2022-07-18 2022-08-08 2022-09-12 2023-01-02 pment of PPP mechanisms in ant Selection ation effectiveness the preschool education sect or KG/GPE/CS/IC-01A / Local co nsultant for training course r Component 1: Expanding pr Individual Consult Under Implement evision (gender, family readi TF / B6138 eschool education for under- Post Open 3,000.00 0.00 2022-06-22 2022-06-24 2022-08-10 2022-08-31 2022-10-05 2023-01-18 ant Selection ation ng and differentiated learnin served children g and monitoring of child dev elopment) KG/GPE/CS/IC-09 / Local con sultant for the development Component 1: Expanding pr Individual Consult Under Implement of the content and structurin TF / B6138 eschool education for under- Post Open 3,500.00 0.00 2022-06-22 2022-06-24 2022-08-10 2022-08-31 2022-10-05 2023-01-18 ant Selection ation g of the framework of compe served children tencies for early childhood e ducators Page 2 KG/GPE/CS/IC-08 / Local con sultant for the development of guidelines and training ma Component 1: Expanding pr terials on competency levels Individual Consult Under Implement TF / B6138 eschool education for under- Post Open 3,000.00 0.00 2022-06-30 2022-09-05 2022-08-18 2022-09-08 2022-10-13 2023-01-26 for implementation in the tea ant Selection ation served children ching practice of Universities , colleges in the preparation of specialists and professiona l development for preschool t eachers KG/GPE/CS/SSS-01 / Develop Component 1: Expanding pr Under Implement ment of design and estimate TF / B6138 eschool education for under- Post Direct Selection Direct - National 120,000.00 0.00 2022-09-15 2022-09-21 2022-09-25 2022-09-22 2022-11-29 2023-01-28 ation documentation for 60SbKs served children Component 3: Ensuring citiz KG/GPE/CS/DC-01 / Project A Direct - Internation Under Implement TF / B6138 ens’ engagement and imple Post Direct Selection 70,000.00 0.00 2023-02-28 2023-03-10 2023-05-14 2025-09-30 udit al ation mentation support Page 3 TEXTUAL PART OF THE PROCUREMENT PLAN Support for Transition to Labor Market Project Project information: (P171471) Ministry of Labor and Social Security (MoLSS) Project Implementation The Turkish Employment Agency (ISKUR) Agencies: Turkish Red Crescent (TRC) Date of the Procurement 10 January 2022 Plan: Period covered by this 01 March 2022 - 31 December 2022 Procurement Plan: I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” November 2020 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. Any procurement activity under the Project shall not be initiated before it is approved by the Bank through STEP. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Goods, Works and Non-Consulting Services Procurement Method Procurement Method Threshold RFB/Open Default Method (No procurement method threshold) International Goods, Works and Non-consulting Services RFB/Open National Contracts less than US$2,000,000 Goods, Works and Non-Consulting Services RFQ Contracts less than US$400,000 Direct Selection No threshold III. Selection of Consultants Selection Method Selection Method Threshold Quality and Cost Based No selection method threshold Selection (QCBS) Least Cost Selection No selection method threshold (LCS) Quality Based Selection No selection method threshold (QBS) Selection Based on Consultants Contracts valued less than $600,000 Qualification (CQS) Individual Consultants No selection method threshold (IC) Direct Selection No selection method threshold The terms of references of any audit, procurement or legal consultants financed by the project shall be sent to the Bank for its comments. IV. Special Arrangements 1. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. For the procurements not subject to international competitive selection the procurement documents agreed by the Bank shall be used. 2. Review Procedure: All the procurements under the project are subject to the Bank’s ex-post review unless otherwise specified in the procurement schedule given below in Section V. 3. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. Mandatory Provisions for Procurement under Bank-Financed Contracts Subject to National Procurement Procedures: The procedures to be followed for National Open Competitive Bidding will be those set forth in the Public Procurement Law of the Borrower (Law No. 4734), as amended from time to time, with the latest amendment dated December 30, 2020, notwithstanding anything to the contrary in the Borrower’s Law on Public Procurement Contracts (Law No. 4735), as amended from time to time, with the latest amendment dated December 02, 2020, and subject to the following provisions: A. Eligibility i. Bidder eligibility will be determined as per the specifications under Section III of the Procurement Regulations; accordingly, no bidder or potential bidder will be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. ii. Bidding will not be restricted to domestic bidders. There will be no restrictions in respect to eligibility to participate in bidding for contracts on the basis of the nationality of the bidder and/or the origin of goods other than those set forth in paragraph 3.23 of the Procurement Regulations. There will be no restriction of any kind on foreign bidders who wish to submit a bid. iii. Bidding will not be restricted to pre-registered firms, and foreign bidders will not be required to be registered with the local authorities as a prerequisite for submitting bids. iv. Participation will be allowed from joint ventures on the condition that such joint venture partners will be jointly and severally liable under the contract. The Project Implementing Agencies shall use the bidding documents agreed by the Bank. B. Fraud and Corruption The request for bids/request for proposals document will require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation, the Bank’s right to sanction and the Bank’s inspection and audit rights. C. Debarment The Bank may recognize, if requested by the Borrower, exclusion from participation as a result of debarment under the national system, provided that the debarment is for offenses involving fraud and corruption, and further provided that the Bank confirms that the particular debarment procedure afforded due process, and the debarment decision is final. 4. Procurement of Second-Hand Goods: Not Applicable. 5. Domestic preference (as specified under paragraph 5.51 of the Procurement Regulations): Not applicable. 6. Operational costs will not be considered under WB procurement implementation. V. Procurement Packages with Methods and Time Schedule The estimated costs in the attached tables (sheets) (excluding deductible VAT). PROCUREMENT Turkiye : Support for Transition to Labor Market Project PLAN General Information Country: Turkiye 2022-07-25 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171471 GPN Date: 2022-06-30 Project Name: Support for Transition to Labor Market Project Loan / Credit No: TF / B7814 Turkish Red Crescent (Turk Kızılayı) Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TR-TRC-350573-GO-RFQ / Pu rchase of Computers & Equip Component 2. Support for D ment (printer, projectors, ca Request for Quota Single Stage - One E TF / B7814 elivery of Employment Servi Post Limited 73,646.22 0.00 Completed 2023-03-22 2023-03-28 2023-04-05 2023-04-20 2023-04-30 mera, mobile phone and etc.) tions nvelope ces selected Project Community Centers (in separate lots) TR-TRC-350617-GO-RFQ / Of Component 2. Support for D fice Furniture for TRC HQ & s Request for Quota Single Stage - One E TF / B7814 elivery of Employment Servi Post Limited 25,644.66 0.00 Completed 2023-03-22 2023-03-28 2023-04-09 2023-05-09 2023-05-22 elected Project Community C tions nvelope ces enters (in separate lots) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TR-TRC-338794-NC-RFQ / Or Component 2. Support for D Request for Quota Single Stage - One E ganizational Services for Coo TF / B7814 elivery of Employment Servi Post Limited 2,890.68 0.00 Canceled 2023-01-31 2023-02-09 2023-02-10 tions nvelope rdination Meetings for field st ces aff TR-TRC-346348-NC-RFQ / Po Component 1. Support for C ster, booklet, brochure, etc. f Request for Quota Single Stage - One E TF / B7814 ounseling Services and Empl Post Limited 36,124.66 0.00 Completed 2023-03-06 2023-03-07 2023-03-20 2023-04-03 or the visibility of the project. tions nvelope oyment Support Printing and Publication of M aterials TR-TRC-347900-NC-RFQ / Or Component 2. Support for D Request for Quota Single Stage - One E ganizational Services for Coo TF / B7814 elivery of Employment Servi Post Limited 3,368.61 0.00 Completed 2023-03-09 2023-03-09 2023-03-16 2023-03-17 2023-03-26 tions nvelope rdination Meetings for field st ces aff. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TR-TRC-305591-CS-LCS / Re cruitment of a Procurement A Component 1. Support for C Least Cost Selecti gent to carry out the Selectio TF / B7814 ounseling Services and Empl Post Open - National 67,741.00 0.00 Completed 2022-07-27 2022-07-27 2022-08-09 2022-08-14 2022-08-23 2022-08-29 2022-09-07 2022-09-02 2022-09-07 2022-09-16 2022-09-30 2022-09-22 2022-11-11 2022-11-29 on n of Individuals to carry out T oyment Support RC’s project related activities . TR-TRC-363427-CS-CQS / Tr Component 1. Support for C Consultant Qualifi Under Implement ainer training consultancy se TF / B7814 ounseling Services and Empl Post Open - National 23,522.67 0.00 2023-05-24 2023-05-31 2023-07-06 2023-07-10 2023-07-14 2023-10-14 cation Selection ation rvice oyment Support INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TR-TRC-315002-CS-CDS / Re cruitment of Deputy Coordin ator Support Services in orde Component 1. Support for C r to coordinate the procurem TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 8,915.00 0.00 Signed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 ent, financial affairs and hum oyment Support an resources processes to be carried out within the scope of the Project. TR-TRC-315023-CS-CDS / Re cruitment of Deputy Coordin Component 1. Support for C ator Operations Services in o TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 8,915.00 0.00 Signed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 rder to ensure overall coordi oyment Support nation within the scope of th e project. TR-TRC-315024-CS-CDS / Wi thin the scope of the Project, Component 1. Support for C Programmer Manager recruit TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 7,038.00 0.00 Signed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 ment in order to managing a oyment Support nd coordinating of operation al, financial and M&E process es of the project. TR-TRC-315027-CS-CDS / Wi thin the scope of the Project, Component 1. Support for C Project Manager recruitment TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 5,938.00 0.00 Signed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 in order to coordination and s oyment Support upervision of field staff to en sure reach the targets accord ing to indicators of the projec t. Page 1 TR-TRC-315029-CS-CDS / Wi thin the scope of the project, Component 1. Support for C the recruitment of Logistic Of TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 4,444.00 0.00 Signed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 ficer in order to plan the proc oyment Support urement processes of the pro ject and to ensure the realiza tion of the purchases. TR-TRC-315030-CS-CDS / Wi thin the scope of the project, Component 1. Support for C Budget and Reporting Officer TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 4,428.00 0.00 Signed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 recruitment to ensure the bu oyment Support dget follow-up and financial r eporting of the project. TR-TRC-315033-CS-CDS / Wi thin the scope of the project, Component 1. Support for C recruitment of Reporting and TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 4,428.00 0.00 Completed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 2023-01-07 M&E Officers for the purpose oyment Support of monitoring and evaluating the realization of the project TR-TRC-315053-CS-CDS / To ensure the coordination of th e staff who will work within t Component 1. Support for C he scope of the project in the TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 7,031.00 0.00 Signed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 Kocaeli field and to follow the oyment Support implementation and reportin g processes regarding the pr oject activities. TR-TRC-315056-CS-CDS / To ensure the coordination of th e staff who will work within t Component 1. Support for C he scope of the project in the TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 7,031.00 0.00 Signed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 Konya field and to follow the oyment Support implementation and reportin g processes regarding the pr oject activities. TR-TRC-315057-CS-CDS / To ensure the coordination of th e staff who will work within t Component 1. Support for C he scope of the project in the TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 7,031.00 0.00 Signed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 Adana field and to follow the oyment Support implementation and reportin g processes regarding the pr oject activities. TR-TRC-315060-CS-CDS / To ensure the coordination of th e staff who will work within t Component 1. Support for C he scope of the project in the TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 7,031.00 0.00 Signed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 İstanbul/Anatolian Side field oyment Support and to follow the implementa tion and reporting processes regarding the project activiti es. TR-TRC-315061-CS-CDS / To ensure the coordination of th e staff who will work within t Component 1. Support for C he scope of the project in the TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 7,031.00 0.00 Signed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 Bursa field and to follow the i oyment Support mplementation and reporting processes regarding the proj ect activities. TR-TRC-315062-CS-CDS / To ensure the coordination of th e staff who will work within t Component 1. Support for C he scope of the project in the TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 7,031.00 0.00 Signed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 Antep field and to follow the i oyment Support mplementation and reporting processes regarding the proj ect activities. TR-TRC-315063-CS-CDS / To ensure the coordination of th e staff who will work within t Component 1. Support for C he scope of the project in the TF / B7814 ounseling Services and Empl Post Direct Selection Direct - National 7,031.00 0.00 Signed 2022-09-08 2022-09-08 2022-09-18 2022-09-18 2022-10-01 2022-12-31 İzmir field and to follow the i oyment Support mplementation and reporting processes regarding the proj ect activities. Component 1. Support for C TR-TRC-319517-CS-INDV / A Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,958.00 0.00 Signed 2022-10-05 2022-10-07 2022-10-21 2022-11-24 2022-10-31 2022-12-02 2022-11-01 2022-12-31 ccounting Officer selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319521-CS-INDV / A Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,479.00 0.00 Canceled 2022-10-05 2022-10-06 2022-10-25 2022-12-08 2022-11-08 2022-12-01 2022-12-31 ccounting Officer Selection. ant Selection oyment Support TR-TRC-319522-CS-INDV / B Component 1. Support for C Individual Consult udget and Reporting Assistan TF / B7814 ounseling Services and Empl Post Open - National 1,171.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-18 2022-11-08 2022-12-27 2022-12-01 2022-12-31 ant Selection t Selection. oyment Support TR-TRC-319528-CS-INDV / C Component 1. Support for C Individual Consult ommunication Officer Selecti TF / B7814 ounseling Services and Empl Post Open - National 2,952.00 0.00 Terminated 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-01 2022-11-01 2022-12-31 ant Selection on oyment Support TR-TRC-319531-CS-INDV / C Component 1. Support for C Individual Consult ommunication Officer Selecti TF / B7814 ounseling Services and Empl Post Open - National 1,476.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-13 2022-11-08 2023-01-31 2022-12-01 2022-12-31 ant Selection on. oyment Support Component 1. Support for C TR-TRC-319532-CS-INDV / H Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,952.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-12-08 2022-10-31 2022-12-20 2022-11-01 2022-12-31 R Officer Selection ant Selection oyment Support Component 1. Support for C TR-TRC-319533-CS-INDV / H Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,476.00 0.00 Canceled 2022-10-05 2022-10-05 2022-10-25 2022-12-08 2022-11-08 2022-12-01 2022-12-31 R Officer Selection ant Selection oyment Support Component 1. Support for C TR-TRC-319562-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-23 2022-11-08 2023-04-10 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319564-CS-INDV / In Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 2022-10-05 2022-10-25 2022-11-08 2022-12-01 2022-12-31 terpreter Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319566-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-21 2022-11-08 2022-12-22 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Page 2 Component 1. Support for C TR-TRC-319567-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-25 2022-11-08 2023-04-11 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319568-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-04 2022-11-08 2023-04-13 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319569-CS-INDV / In Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 terpreter Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319570-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-21 2022-11-08 2023-01-31 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319571-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-23 2022-11-08 2023-01-31 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319572-CS-INDV / In Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 terpreter Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319575-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-09 2022-11-08 2023-04-10 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319576-CS-INDV / In Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 terpreter Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319577-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-06 2022-11-08 2023-04-10 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319578-CS-INDV / In Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 2022-10-05 2022-10-06 2022-10-25 2023-01-11 2022-11-08 2023-04-10 2022-12-01 2022-12-31 terpreter Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319580-CS-INDV / In Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 terpreter Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319581-CS-INDV / In Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 2022-10-05 2022-10-06 2022-10-25 2023-01-10 2022-11-08 2023-04-10 2022-12-01 2022-12-31 terpreter Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319582-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-12 2022-11-08 2023-04-10 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319583-CS-INDV / In Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 2022-10-05 2022-10-25 2022-11-08 2022-12-01 2022-12-31 terpreter Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319584-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-13 2022-11-08 2023-04-10 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319585-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-03-13 2022-11-08 2023-04-10 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319587-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-18 2022-11-08 2023-04-10 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319588-CS-INDV / In Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 terpreter Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319589-CS-INDV / In Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 terpreter Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319591-CS-INDV / In Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 terpreter Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319592-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-25 2022-11-08 2023-04-13 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319593-CS-INDV / In Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-23 2022-11-08 2023-04-12 2022-12-01 2022-12-31 terpreter Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319600-CS-INDV / In Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 terpreter Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319603-CS-INDV / In Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,180.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 terpreter Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319604-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-05 2022-10-21 2022-11-23 2022-10-31 2022-12-06 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319606-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-23 2022-10-31 2022-12-05 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319607-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-12-09 2022-10-31 2023-01-31 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319609-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-23 2022-10-31 2022-12-06 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Page 3 Component 1. Support for C TR-TRC-319611-CS-INDV / Li Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 2022-10-05 2022-10-21 2022-10-31 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319613-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-23 2022-10-31 2022-12-06 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319614-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-06 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319616-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-05 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319617-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-26 2022-10-31 2022-12-05 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319618-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-06 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319620-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-06 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319621-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-07 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319622-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-25 2022-10-31 2022-12-06 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319623-CS-INDV / Li Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 2022-10-05 2022-10-06 2022-10-21 2022-10-31 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319624-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-25 2022-10-31 2022-12-06 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319625-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-23 2022-10-31 2022-12-06 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319626-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-06 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319627-CS-INDV / Li Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 2022-10-05 2022-10-06 2022-10-21 2022-10-31 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319628-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-27 2022-10-31 2022-12-27 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319630-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-12-13 2022-10-31 2023-01-31 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319631-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-06 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319632-CS-INDV / Li Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 2,442.00 0.00 2022-10-05 2022-10-06 2022-10-21 2022-10-31 2022-11-01 2022-12-31 velihood Assistant Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319634-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-07 2022-11-08 2023-01-31 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319640-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-11-23 2022-11-08 2022-12-06 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319641-CS-INDV / Li Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319643-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-11-23 2022-11-08 2022-12-06 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319644-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-08 2022-11-08 2023-01-31 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319645-CS-INDV / Li Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319647-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-11-24 2022-11-08 2022-12-05 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319648-CS-INDV / Li Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319649-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-18 2022-11-08 2023-01-31 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319650-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-11-24 2022-11-08 2022-12-27 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Page 4 Component 1. Support for C TR-TRC-319651-CS-INDV / Li Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319652-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-19 2022-11-08 2023-01-31 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319655-CS-INDV / Li Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319656-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-11-24 2022-11-08 2022-12-06 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319657-CS-INDV / Li Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,221.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 velihood Assistant Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319658-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,532.00 0.00 Terminated 2022-10-05 2022-10-06 2022-10-25 2022-12-14 2022-11-08 2023-01-31 2022-12-01 2022-12-31 velihood Officer Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319661-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,064.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-23 2022-10-31 2022-12-05 2022-11-01 2022-12-31 velihood Officer Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319662-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,064.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-23 2022-10-31 2022-12-05 2022-11-01 2022-12-31 velihood Officer Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319663-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,064.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-05 2022-11-01 2022-12-31 velihood Officer Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319664-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,064.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-25 2022-10-31 2022-12-05 2022-11-01 2022-12-31 velihood Officer Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319665-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,064.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-23 2022-10-31 2022-12-05 2022-11-01 2022-12-31 velihood Officer Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319666-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,064.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-23 2022-10-31 2022-12-02 2022-11-01 2022-12-31 velihood Officer Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319667-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,064.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-02 2022-11-01 2022-12-31 velihood Officer Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319668-CS-INDV / Li Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,064.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-23 2022-10-31 2022-12-05 2022-11-01 2022-12-31 velihood Officer Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319674-CS-INDV / Lo Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,432.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-26 2022-10-31 2022-12-27 2022-11-01 2022-12-31 gistic Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319675-CS-INDV / Lo Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,432.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-02 2022-11-01 2022-12-31 gistic Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319677-CS-INDV / Lo Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,432.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-23 2022-10-31 2022-12-02 2022-11-01 2022-12-31 gistic Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319678-CS-INDV / Lo Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,432.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-23 2022-10-31 2022-12-02 2022-11-01 2022-12-31 gistic Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319679-CS-INDV / Lo Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,432.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-02 2022-11-01 2022-12-31 gistic Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319680-CS-INDV / Lo Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,432.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-02 2022-11-01 2022-12-31 gistic Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319684-CS-INDV / Lo Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,432.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-02 2022-11-01 2022-12-31 gistic Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319693-CS-INDV / Ps Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,434.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-19 2022-11-08 2023-04-11 2022-12-01 2022-12-31 ychologist Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319694-CS-INDV / Ps Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,434.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-17 2022-11-08 2023-04-11 2022-12-01 2022-12-31 ychologist Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319695-CS-INDV / Ps Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,434.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-10 2022-11-08 2023-01-13 2022-12-01 2022-12-31 ychologist Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319696-CS-INDV / Ps Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,434.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-11 2022-11-08 2023-02-02 2022-12-01 2022-12-31 ychologist Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319697-CS-INDV / Ps Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,434.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-12 2022-11-08 2023-04-11 2022-12-01 2022-12-31 ychologist Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319698-CS-INDV / Ps Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,434.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-19 2022-11-08 2023-04-11 2022-12-01 2022-12-31 ychologist Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319700-CS-INDV / Ps Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,434.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ychologist Selection. ant Selection ation oyment Support Page 5 Component 1. Support for C TR-TRC-319701-CS-INDV / Ps Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,868.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-27 2022-10-31 2022-12-05 2022-11-01 2022-12-31 ychologist Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319702-CS-INDV / Ps Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,868.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-29 2022-10-31 2022-12-05 2022-11-01 2022-12-31 ychologist Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319710-CS-INDV / Q Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 4,454.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-01 2022-11-01 2022-12-31 uality Manager Selection ant Selection oyment Support Component 1. Support for C TR-TRC-319714-CS-INDV / R Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,476.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 eporting Oficcer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319717-CS-INDV / S Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,952.00 0.00 Completed 2022-10-05 2022-10-06 2022-10-21 2022-11-23 2022-10-31 2022-12-05 2022-11-01 2022-12-31 2023-03-02 ector Expert Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319718-CS-INDV / S Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,064.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-02 2022-11-01 2022-12-31 ocial Impact Expert Selection ant Selection oyment Support Component 1. Support for C TR-TRC-319719-CS-INDV / S Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,064.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-23 2022-10-31 2022-12-02 2022-11-01 2022-12-31 ocial Impact Expert Selection ant Selection oyment Support Component 1. Support for C TR-TRC-319720-CS-INDV / S Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,064.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-27 2022-10-31 2022-12-28 2022-11-01 2022-12-31 ocial Impact Expert Selection ant Selection oyment Support Component 1. Support for C TR-TRC-319721-CS-INDV / S Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,064.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-12-21 2022-10-31 2023-01-31 2022-11-01 2022-12-31 ocial Impact Expert Selection ant Selection oyment Support Component 1. Support for C TR-TRC-319722-CS-INDV / S Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 3,064.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-27 2022-10-31 2022-12-27 2022-11-01 2022-12-31 ocial Impact Expert Selection ant Selection oyment Support Component 1. Support for C TR-TRC-319723-CS-INDV / S Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,532.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-23 2022-11-08 2022-12-28 2022-12-01 2022-12-31 ocial Impact Expert Selection ant Selection oyment Support Component 1. Support for C TR-TRC-319725-CS-INDV / S Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,532.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-21 2022-11-08 2023-01-31 2022-12-01 2022-12-31 ocial Impact Expert Selection ant Selection oyment Support Component 1. Support for C TR-TRC-319726-CS-INDV / S Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,532.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-22 2022-11-08 2023-01-31 2022-12-01 2022-12-31 ocial Impact Expert Selection ant Selection oyment Support Component 1. Support for C TR-TRC-319727-CS-INDV / S Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,532.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-23 2022-11-08 2022-12-28 2022-12-01 2022-12-31 ocial Impact Expert Selection ant Selection oyment Support Component 1. Support for C TR-TRC-319729-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-12-18 2022-11-08 2023-04-12 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319730-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319732-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2023-02-02 2022-11-08 2023-04-12 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319737-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319739-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319740-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2023-01-27 2022-11-08 2023-04-12 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319743-CS-INDV / Tr Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-27 2022-11-08 2023-04-12 2022-12-01 2022-12-31 ainer Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319744-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319745-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319747-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319748-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319749-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319750-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319751-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Page 6 Component 1. Support for C TR-TRC-319754-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319755-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319757-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319758-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319759-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2023-02-17 2022-11-08 2023-04-12 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319760-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319761-CS-INDV / Tr Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 2022-10-05 2022-10-06 2022-10-25 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection ation oyment Support TR-TRC-319670-CS-INDV / Lo Component 1. Support for C Individual Consult gistic Assistant and Administr TF / B7814 ounseling Services and Empl Post Open - National 1,216.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2022-12-08 2022-11-08 2023-02-02 2022-12-01 2022-12-31 ant Selection ative Affairs Assistant Selecti oyment Support on. TR-TRC-319689-CS-INDV / Lo Component 1. Support for C Individual Consult gistic Managert and Administ TF / B7814 ounseling Services and Empl Post Open - National 4,360.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-02 2022-11-01 2022-12-31 ant Selection rative Affairs Manager Selecti oyment Support on. TR-TRC-319525-CS-INDV / C Component 1. Support for C Individual Consult ommunity Center Manager S TF / B7814 ounseling Services and Empl Post Open - National 2,344.00 0.00 Canceled 2022-10-05 2022-10-06 2022-10-25 2023-01-11 2022-11-08 2022-12-01 2022-12-31 ant Selection election./ İstanbul TM. oyment Support Component 1. Support for C TR-TRC-319688-CS-INDV / Lo Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 2,432.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-02 2022-11-01 2022-12-31 gistic Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319715-CS-INDV / S Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,476.00 0.00 Canceled 2022-10-05 2022-10-06 2022-10-25 2022-12-13 2022-11-08 2022-12-01 2022-12-31 afeguard Oficcer Selection. ant Selection oyment Support TR-TRC-319690-CS-INDV / S Component 1. Support for C Individual Consult ocioeconomic Empowerment TF / B7814 ounseling Services and Empl Post Open - National 2,952.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-21 2022-11-24 2022-10-31 2022-12-05 2022-11-01 2022-12-31 ant Selection Project Officer Selection. oyment Support TR-TRC-319691-CS-INDV / S Component 1. Support for C Individual Consult ocioeconomic Empowerment TF / B7814 ounseling Services and Empl Post Open - National 1,476.00 0.00 Canceled 2022-10-05 2022-10-06 2022-10-25 2022-12-08 2022-11-08 2022-12-08 2022-12-01 2022-12-31 ant Selection Project Officer Selection. oyment Support Component 1. Support for C TR-TRC-319716-CS-INDV / S Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,476.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-27 2022-11-08 2023-01-31 2022-12-01 2022-12-31 afeguard Oficcer Selection. ant Selection oyment Support TR-TRC-319527-CS-INDV / C Component 1. Support for C Individual Consult ommunity Center Manager S TF / B7814 ounseling Services and Empl Post Open - National 2,344.00 0.00 Canceled 2022-10-05 2022-10-06 2022-10-25 2022-12-08 2022-11-08 2022-12-01 2022-12-31 ant Selection election. / Şanlıurfa TM. oyment Support TR-TRC-319692-CS-INDV / S Component 1. Support for C Individual Consult ocioeconomic Empowerment TF / B7814 ounseling Services and Empl Post Open - National 1,476.00 0.00 Signed 2022-10-05 2022-10-06 2022-10-25 2023-01-30 2022-11-08 2023-01-31 2022-12-01 2022-12-31 ant Selection Project Officer Selection. oyment Support TR-TRC-345547-CS-INDV / C Component 1. Support for C Individual Consult Under Implement ommunication Officer Selecti TF / B7814 ounseling Services and Empl Post Open - National 19,233.76 0.00 2023-02-24 2023-02-24 2023-03-21 2023-03-28 2023-04-17 2023-12-31 ant Selection ation on oyment Support Component 1. Support for C TR-TRC-345577-CS-INDV / H Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 19,233.76 0.00 2023-02-24 2023-02-24 2023-03-21 2023-03-28 2023-04-17 2023-12-31 R Officer Selection ant Selection ation oyment Support Component 1. Support for C TR-TRC-345584-CS-INDV / M Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 19,233.76 0.00 2023-02-24 2023-02-24 2023-03-21 2023-03-28 2023-04-17 2023-12-31 &E Officer ant Selection ation oyment Support Component 1. Support for C TR-TRC-345587-CS-INDV / A Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 19,233.76 0.00 2023-02-24 2023-02-24 2023-03-21 2023-03-28 2023-04-17 2023-12-31 ccounting Officer Selection. ant Selection ation oyment Support TR-TRC-345590-CS-INDV / S Component 1. Support for C Individual Consult Under Implement ocioeconomic Empowerment TF / B7814 ounseling Services and Empl Post Open - National 19,233.76 0.00 2023-02-24 2023-02-24 2023-03-21 2023-03-28 2023-04-17 2023-12-31 ant Selection ation Project Officer Selection. oyment Support Component 1. Support for C TR-TRC-345593-CS-INDV / S Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 19,233.76 0.00 2023-02-24 2023-02-24 2023-03-21 2023-03-28 2023-04-17 2023-12-31 afeguard Officer Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-345599-CS-INDV / S Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 15,626.48 0.00 2023-02-24 2023-02-24 2023-03-21 2023-03-28 2023-04-17 2023-12-31 upply and Logistics Assistant ant Selection ation oyment Support TR-TRC-345603-CS-INDV / Is Component 1. Support for C Individual Consult Under Implement tanbul/European Side CC Ma TF / B7814 ounseling Services and Empl Post Open - National 13,905.97 0.00 2023-02-24 2023-02-24 2023-03-21 2023-03-28 2023-04-17 2023-12-31 ant Selection ation nager oyment Support Component 1. Support for C TR-TRC-345609-CS-INDV / Ş Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 13,905.97 0.00 2023-02-24 2023-02-24 2023-03-21 2023-03-28 2023-04-17 2023-12-31 anlıurfa CC Manager ant Selection ation oyment Support Component 1. Support for C TR-TRC-319673-CS-INDV / Lo Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,216.00 0.00 Canceled 2022-10-05 2022-10-06 2022-10-25 2022-11-25 2022-11-08 2022-12-27 2022-12-01 2022-12-31 gistic Assistant Selection. ant Selection oyment Support Component 1. Support for C TR-TRC-319736-CS-INDV / Tr Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 1,209.00 0.00 Canceled 2022-10-05 2022-10-06 2022-10-25 2022-12-18 2022-11-08 2022-12-01 2022-12-31 ainer Selection. ant Selection oyment Support Page 7 Component 1. Support for C TR-TRC-319673/2-CS-INDV / Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 20,302.11 0.00 2022-10-05 2022-10-07 2022-10-25 2022-11-25 2022-11-08 2022-12-27 2022-12-01 2022-12-31 Logistic Assistant Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-319736/2-CS-INDV / Individual Consult TF / B7814 ounseling Services and Empl Post Open - National 17,842.86 0.00 Signed 2022-10-05 2022-10-07 2022-10-25 2022-12-18 2022-11-08 2023-02-28 2022-12-01 2022-12-31 Trainer Selection ant Selection oyment Support TR-TRC-319528/2-CS-INDV / Component 1. Support for C Individual Consult Communication Officer Selec TF / B7814 ounseling Services and Empl Post Open - National 5,575.58 0.00 Signed 2022-10-05 2022-10-07 2022-10-21 2022-11-24 2022-10-31 2022-11-30 2022-11-01 2022-12-31 ant Selection tion oyment Support Component 1. Support for C TR-TRC-361737-CS-INDV / K Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 9,854.62 0.00 2023-05-15 2023-05-15 2023-06-05 2023-06-12 2023-07-01 2023-12-31 ocaeli Side CC Manager ant Selection ation oyment Support TR-TRC-361751-CS-INDV / S Component 1. Support for C Individual Consult Under Implement ocioeconomic Empowerment TF / B7814 ounseling Services and Empl Post Open - National 13,630.22 0.00 2023-05-15 2023-05-15 2023-06-05 2023-06-12 2023-07-01 2023-12-31 ant Selection ation Project Officer Selection. oyment Support TR-TRC-361753-CS-INDV / S Component 1. Support for C Individual Consult Under Implement ocioeconomic Empowerment TF / B7814 ounseling Services and Empl Post Open - National 13,630.22 0.00 2023-05-15 2023-05-15 2023-06-05 2023-06-12 2023-07-01 2023-12-31 ant Selection ation Project Officer Selection. oyment Support Component 1. Support for C TR-TRC-361754-CS-INDV / Ps Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 13,019.51 0.00 2023-05-15 2023-05-15 2023-06-05 2023-06-12 2023-07-01 2023-12-31 ychologist Selection. ant Selection ation oyment Support Component 1. Support for C TR-TRC-361756-CS-INDV / Li Individual Consult Under Implement TF / B7814 ounseling Services and Empl Post Open - National 13,630.22 0.00 2023-05-15 2023-05-15 2023-06-05 2023-06-12 2023-07-01 2023-12-31 velihood Officer Selection. ant Selection ation oyment Support Page 8 Procurement Plan I. General 1. Project Information Country : Kenya Recipient : Republic of Kenya Project Name : National Agriculture and Rural Inclusive Growth Loan Credit No. : IDA 59000 2. Date of General Procurement Notice : 9th February 2018 3. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services 1. Thresholds for the Method of Procurement: Method of Procurement Thresholds for Method (US$ equivalent) Open International (Goods) Equal to or more than 3 million Open National ( Goods) – Open < $3 million Tender as per PPDA 2015 RFQ (Goods) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Open International (Works) Equal to or more than 15 million Open National (Works) - Open Less than 15 million Tender as per PPDA 2015 RFQ (works) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Method of Procurement Thresholds for Method (US$ equivalent) Open International (Non-consulting Equal to or More than 3 million Services) Open National (Non-consulting Less than 3 million Services) - Open Tender as per PPDA 2015 Direct Contracting No threshold; meet requirements of Bank’s Procurement Regulations Prior Review: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection (Project Procurement Risk Rating is “High”): (a) Goods, information technology and Non-consulting Services: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1.5 million (b) Works (including turnkey, supply & installation of plant and equipment and PPP); First procurement under the project irrespective of value and all procurements estimated to cost more than USD 5 million and The prior review thresholds will be reviewed during the implementation of the project and modified, based on the risk assessment. 2. For contracts subject to prior review, the Borrower shall seek the Bank’s no objection before agreeing to: a. an extension of the stipulated time for execution of a contract that has an impact on the planned completion of the project; b. any material modification of the scope of the Works, Goods, Non- consulting services or Consulting Services, or other significant changes to the terms and conditions of the contract; c. any variation order or contract amendment (except in cases of extreme urgency), including due to extension of time, that singly or combined with all previous variation orders or amendments, increases the original contract amount by more than 15% (fifteen percent); or d. the proposed termination of the contract. The Borrower / IA shall provide a copy of all amendments to the contract to the Bank for its records. 3. Prequalification Not Applicable Domestic Preference. The provision of domestic preference shall be applied in the procurement of goods following international market approach in accordance with Annex VI of the Regulations. Domestic preference shall not apply in the procurement of works. 4. Reference to Standard Procurement Documents Bank’s Standard RFB Goods and RFP Consulting Services dated July 2016 will be used as a base and incorporating suitable modifications and the same would be agreed with the Bank subject international competition. 5. Any Other Special Procurement Arrangements A. Procurement approach under CDD Approach by Communities: Applicable if stipulated in the PAD. B. When approaching the national market, as agreed in the Procurement Plan, the Open Tender procedure of Public Procurement and Asset Disposal Act 2015 and Regulations 2017 may be used. The specific Requirements for national open competitive procurement include the following: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. Other national procurement arrangements (other than national open competitive procurement), that may be applied by the Borrower (such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti-Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. In all cases, the national procurement procedures to be used shall give due attention to quality aspects. 6. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Selection methods of procurement of Consultants' Services (Firms): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Quality and Cost Based As per requirements of para 7.3 of the Selection (QCBS) Regulations Quality Based Selection As per requirements of para 7.8 to 7.10 (QBS) of the Regulations Selection based on a Fixed As per requirements of para 7.4 and 7.5 of the Budget (FBS) Regulations Selection Based on Least As per requirements of para 7.6 and 7.7 of the Cost Basis (LCS) Regulations Selection based on As per requirements of para 7.11 and 7.12 of Consultant’s Qualification the Regulations (CQ) Direct Must meet the requirements of Para 7.13 to 7.15 of the Regulations, and with prior agreement in PP with the Bank. The short list may consist of all National consultants in case the estimated cost is less than USD 300,000 Procurement methods for Selection of Individual Consultants (IC): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Open Competitive As per requirements of para 7.36 and 7.37 of Selection the Regulations Limited Competitive As per requirements of para 7.38 of the Selection Regulations Direct Must meet the requirements of Para 7.39 of the Regulations, and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Regulations Prior Review Thresholds: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 0.5 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.2 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. PROCUREMENT Kenya : National Agricultural and Rural Inclusive Growth Project PLAN General Information Country: Kenya 2019-10-03 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153349 GPN Date: 2018-02-09 Project Name: National Agricultural and Rural Inclusive Growth Project Loan / Credit No: IDA / 59000 Nakuru County Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-NAKURU COUNTY-14903 Project Coordination and Ma Request for Quota Single Stage - One E 2020-08-1 4-CW-RFQ / RENOVATION OF IDA / 59000 Post Limited 24,070.86 0.00 Canceled 2019-12-25 2020-02-19 nagement tions nvelope 7 OFFICE SPACE KE-NAKURU COUNTY-21482 8-CW-RFQ / EXCAVATION OF Supporting County Communi Request for Quota Single Stage - One E 2021-04-2 IDA / 59000 Post Limited 54,471.17 53,095.34 Signed 2021-02-07 2021-04-22 2021-03-10 2021-05-27 20 ( NO) FARM PONDS OF 10 ty-Led Development tions nvelope 4 0M3 IN NJORO SIGOTIK SLM I N NJORO SUB COUNTY KE-NAKURU COUNTY-21483 5-CW-RFQ / EXCAVATION OF Supporting County Communi Request for Quota Single Stage - One E 2021-04-2 20 (NO) FARM PONDS OF 100 IDA / 59000 Post Limited 54,471.18 55,377.23 Signed 2021-02-08 2021-04-20 2021-03-11 2021-05-17 ty-Led Development tions nvelope 5 M3 EACH FOR CFRATER STR EAM SLM IN BAHATI SUB COU NTY KE-NAKURU COUNTY-21649 6-CW-RFB / REHABILITATION Supporting County Communi Single Stage - One E 2021-11-2 IDA / 59000 Post Request for Bids Open - National 158,362.93 180,377.04 Signed 2021-02-05 2021-06-03 2021-02-10 2021-03-24 2021-06-18 2021-04-23 2021-07-01 2021-05-28 2021-08-09 OF WANYORORO DAM FOR C ty-Led Development nvelope 4 RATER STREAM IN BAHATI SU B COUNTY KE-NAKURU COUNTY-21664 3-CW-RFQ / PROPOSED RENO Project Coordination and Ma Request for Quota Single Stage - One E 2021-06-0 VATION OF MINISTRY OF AGR IDA / 59000 Post Limited 20,477.16 19,688.53 Signed 2021-02-05 2021-02-05 2021-03-03 2021-03-02 nagement tions nvelope 1 ICULTURE,LIVESTOCK AND FI SHERIES OFFICE BLOCK NAK URU. KE-NAKURU COUNTY-14903 8-CW-FCA / Proposed Baraka Supporting County Communi 2020-08-2 IDA / 59000 Post Force Account Direct 361,955.35 0.00 Canceled 2020-01-15 2020-01-20 2020-02-24 Ridge Integrated Landscape ty-Led Development 2 Management and Water Reh abilitation Project KE-NAKURU COUNTY-30629 3-CW-RFQ / Proposed constru Strengthening Producer Org Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-01-0 ction of a perimeter wall for IDA / 59000 anizations and Value Chain Post Limited tions (Non Bank-S 83,533.35 0.00 2022-09-08 2022-10-11 tions nvelope lementation 9 potato cold store Project at M Development PD) uchorwe in Turi Ward Molo S ub County KE-NAKURU COUNTY-31475 5-CW-RFQ / Proposed Boreho le Drilling and Equipping with Strengthening Producer Org Request for Quota Solar Powered Energy; piping Request for Quota Single Stage - One E Under Imple 2023-01-0 IDA / 59000 anizations and Value Chain Post Limited tions (Non Bank-S 72,735.30 0.00 2022-09-13 2022-09-13 2022-10-10 network;placing of a 10 mete tions nvelope mentation 8 Development PD) r cubic plastic tank on a 12M high on a steel structure at t he Agricultural Training Cent er in London Ward Nakuru S ub County. KE-NAKURU COUNTY-31772 7-CW-RFQ / Proposed Constr Strengthening Producer Org Request for Quota Request for Quota Single Stage - One E 2022-12-3 uction and Equipping of two IDA / 59000 anizations and Value Chain Post Limited tions (Non Bank-S 127,737.09 0.00 Canceled 2022-09-28 2022-10-31 tions nvelope 0 Hay Burns with a capacity of Development PD) 40,000 bales for fodder cons ervation. KE-NAKURU COUNTY-31768 National Procure 6-CW-RFB / Proposed Constru Strengthening Producer Org ment Document - ction,Installation,Testing Co Single Stage - One E 2023-02-1 IDA / 59000 anizations and Value Chain Post Request for Bids Open - National 1 Envelope proce 414,660.23 0.00 Canceled 2022-10-07 2022-11-30 2022-10-12 2023-01-09 2022-11-11 2022-12-14 2022-11-18 2022-12-22 2022-12-16 mmissioning and Operanizati nvelope 4 Development ss (Non Bank-SPD on of 500 Metric Tonnes Pota ) to cold store at Muchorwe in Turi Ward Molo Sub County . KE-NAKURU COUNTY-34953 Strengthening Producer Org Request for Quota 8-CW-RFQ / CONSTRUCTION Request for Quota Single Stage - One E Pending Imp 2023-09-1 IDA / 59000 anizations and Value Chain Post Limited tions (Non Bank-S 35,855.50 0.00 2023-03-19 2023-04-17 OF A CUT OFF DRAINS AT MU tions nvelope lementation 4 Development PD) CHORWE IN TURI WARD MOL O SUB COUNTY KE-NAKURU COUNTY-31769 9-CW-RFB / Construction of a Strengthening Producer Org Request for Quota Request for Quota Single Stage - One E 2023-09-2 Chicken Slaughter house wit IDA / 59000 anizations and Value Chain Post Limited tions (Non Bank-S 103,159.82 0.00 Canceled 2023-03-19 2023-04-30 tions nvelope 7 h a capacity of 300(No) birds Development PD) per day in Bahati Ward in Ba hati Sub County KE-NAKURU COUNTY-33571 0-CW-RFB / PROPOSED CONS National Procure TRUCTION, INSTALLATION, T Strengthening Producer Org ment Document - Single Stage - One E 2023-06-3 ESTING COMMISSIONING AN IDA / 59000 anizations and Value Chain Post Request for Bids Open - National 1 Envelope proce 414,660.23 0.00 Canceled 2023-01-11 2023-01-17 2023-01-31 2023-02-01 2023-02-22 nvelope 0 D OPERATIONALIZATION OF Development ss (Non Bank-SPD 500 METRIC TONNES POTAT ) O COLD STORE AT MUCHOR WE IN TURI WARD MOLO SUB COUNTY. KE-NAKURU COUNTY-31775 0-CW-RFQ / PROPOSED CONS TRUCTION OF 15(No) 100 CU Request for Quota Supporting County Communi Request for Quota Single Stage - One E 2023-01-2 BIC METER FARM PONDS AN IDA / 59000 Post Limited tions (Non Bank-S 39,332.84 0.00 Canceled 2022-09-28 2022-10-31 ty-Led Development tions nvelope 9 D SIGNAGE AT KAPKEMBU SU PD) STAINABLE LAND MANAGEME NT SITE AT MAUCHE WARD N JORO SUB COUNTY GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-NAKURU COUNTY-13853 Supporting County Communi Single Stage - One E IDA / 59000 Post Request for Bids Open - National 5,000.00 0.00 Canceled 2019-10-03 2019-10-08 2019-11-07 2019-11-28 2019-12-26 2020-01-25 5-GO-RFB / Procurement of m ty-Led Development nvelope otorcycles Page 1 KE-NAKURU COUNTY-13854 Supporting Community-Driv Single Stage - One E IDA / 59000 Post Request for Bids Open - National 500,000.00 0.00 Canceled 2019-10-03 2019-10-04 2019-10-05 2019-10-04 2019-11-04 2019-09-30 2019-11-06 2019-12-11 2020-01-10 2-GO-RFB / procurement of en Development nvelope motorcycle KE-NAKURU COUNTY-13855 Supporting County Communi Single Stage - One E IDA / 59000 Post Request for Bids Open - National 5,000.00 0.00 Canceled 2019-10-03 2019-10-08 2019-11-07 2019-11-28 2019-12-26 2020-01-25 4-GO-RFB / Purchase of moto ty-Led Development nvelope rcycle KE-NAKURU COUNTY-14943 4-GO-RFQ / Procurement of t Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 9,842.37 12,654.75 Completed 2020-01-20 2020-05-11 2020-03-16 2020-06-04 2020-09-12 2020-07-18 wo (2No) Soil testing and Wa ty-Led Development tions nvelope ter conservation tools KE-NAKURU COUNTY-14944 Project Coordination and Ma Request for Quota Single Stage - One E 2-GO-RFQ / Purchase of Offic IDA / 59000 Post Limited 24,070.00 9,311.91 Completed 2019-12-25 2020-03-19 2020-02-19 2020-03-28 2020-08-17 2020-03-31 nagement tions nvelope e Furniture and Fittings KE-NAKURU COUNTY-14943 7-GO-RFQ / Purchase of two ( 2No) Total station equipment this is a precision instrument Supporting County Communi Request for Quota Single Stage - One E used for determining horizon IDA / 59000 Post Limited 3,936.95 36,148.95 Completed 2020-01-20 2020-05-20 2020-02-26 2020-06-16 2020-03-27 2020-10-03 ty-Led Development tions nvelope tal and vertical distances in s urveying,to be used during i mplementation of Sustainabl e Land Management activitie s at the sub-Counties level KE-NAKURU COUNTY-14904 Project Coordination and Ma Request for Quota Single Stage - One E 9-GO-RFQ / Purchase of five ( IDA / 59000 Post Limited 5,905.42 0.00 Canceled 2019-10-26 2019-12-21 2020-06-18 nagement tions nvelope 5No) Laptops KE-NAKURU COUNTY-14905 Supporting County Communi Request for Quota Single Stage - One E 3-GO-RFQ / Purchase of nine IDA / 59000 Post Limited 4,429.07 0.00 Canceled 2020-01-20 2020-03-16 2020-09-12 ty-Led Development tions nvelope (9No) hand held GPS tools KE-NAKURU COUNTY-14944 Supporting County Communi Request for Quota Single Stage - One E 1-GO-RFQ / Purchase of two ( IDA / 59000 Post Limited 5,902.42 0.00 Canceled 2020-01-20 2020-03-16 2020-09-12 ty-Led Development tions nvelope 2No) mobile mappers KE-NAKURU COUNTY-19402 0-GO-RFQ / PROCUREMENT O Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 11,000.00 14,056.58 Completed 2020-10-05 2020-11-10 2020-10-30 2020-12-08 2020-11-06 2021-02-27 F 5NO LAPTOP COMPUTERS A nagement tions nvelope ND A NET WORK ROUTER KE-NAKURU COUNTY-19399 1-CW-RFQ / IP BASED AUDIO- Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 70,000.00 56,702.14 Signed 2020-10-05 2020-11-10 2020-11-03 2020-11-07 2020-11-30 2021-01-25 VISUAL TELECONFERENCE SY nagement tions nvelope STEM AND A NETWORK FIRE WALL KE-NAKURU COUNTY-20463 6-GO-RFQ / Supply and deliv Supporting County Communi Request for Quota Single Stage - One E ery of pears and grevillea tre IDA / 59000 Post Limited 29,309.00 46,039.12 Completed 2020-06-03 2020-04-07 2020-07-29 2020-04-28 2021-01-25 2020-06-07 ty-Led Development tions nvelope e seedlings for Baraka Ridge SLM in Kamara/Sirikwa Ward in Kuresoi North Sub County KE-NAKURU COUNTY-20464 0-GO-RFQ / supply and delive Supporting County Communi Request for Quota Single Stage - One E ry of plums tree seedlings for IDA / 59000 Post Limited 10,991.00 13,090.91 Signed 2020-05-03 2020-04-07 2020-06-28 2020-04-29 2020-12-25 ty-Led Development tions nvelope Baraka Ridge SLM in Kamara/ Sirikwa Ward in Kuresoi Nort h Sub County. KE-NAKURU COUNTY-20463 7-GO-RFQ / Supply and deliv Supporting County Communi Request for Quota Single Stage - One E ery of avocado tree seedlings IDA / 59000 Post Limited 76,937.00 80,430.87 Completed 2020-04-07 2020-04-02 2020-06-02 2020-05-01 2020-11-29 2020-05-08 ty-Led Development tions nvelope for Baraka Ridge SLM in Kam ara/Sirikwa Ward in Kuresoi North Sub County KE-NAKURU COUNTY-20463 8-GO-RFQ / Supply and deliv Supporting County Communi Request for Quota Single Stage - One E ery of Bracharia splits for Bar IDA / 59000 Post Limited 18,318.00 89,605.70 Signed 2020-04-10 2020-05-12 2020-06-05 2020-05-22 2020-12-02 2020-07-02 ty-Led Development tions nvelope aka Ridge SLM in Kamara/Siri kwa Ward in Kuresoi North S ub County KE-NAKURU COUNTY-20463 Project Coordination and Ma Request for Quota Single Stage - One E 9-GO-RFQ / Supply and Deliv IDA / 59000 Post Limited 2,849.00 2,894.14 Completed 2020-03-21 2020-05-04 2020-05-16 2020-05-30 2020-11-12 2020-05-30 nagement tions nvelope ery of office Furniture KE-NAKURU COUNTY-21483 4-GO-RFQ / SUPPLY AND DELI Supporting County Communi Request for Quota Single Stage - One E VERY OF 6,450 (NO) HIGH VA IDA / 59000 Post Limited 11,711.30 11,916.55 Signed 2021-02-08 2021-05-02 2021-03-08 2021-02-27 2021-04-22 ty-Led Development tions nvelope LUE AGROFORESTRY TREE S EEDLINGS FOR NJORO SIGOTI K IN NJORO SUB COUNTY KE-NAKURU COUNTY-21650 7-GO-RFQ / SUPPLY AND DELI VERY OF 13,730 (NO) HIGH V Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 24,940.96 25,386.38 Completed 2021-02-11 2021-02-05 2021-04-05 2021-02-27 2021-05-20 2021-03-04 ALUE AGROFORESTRY TREE ty-Led Development tions nvelope SEEDLINGS FOR CRATER STR EAM IN BAHATI SUB COUNTY KE-NAKURU COUNTY-21680 7-GO-RFQ / SUPPLY AND DELI VERY OF HARD WARE KITS T Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 9,931.91 9,965.82 Completed 2021-02-07 2021-02-05 2021-03-31 2021-02-19 2021-04-14 2021-03-25 O ENHANCE DISTRUCTIVE AG ty-Led Development tions nvelope RICULTURAL TECHNOLOGIIES TO SUPPORT SMALL HOLDER FARMERS KE-NAKURU COUNTY-21681 4-GO-RFQ / SUPPLY AND DELI VERY OF AI KITS,VIDEOGRAP HY KIT AND MOBILE PHONES Supporting County Communi Request for Quota Single Stage - One E TO ENHANCE SERVICE DELIV IDA / 59000 Post Limited 6,945.07 7,662.95 Signed 2021-02-05 2021-02-05 2021-03-05 2021-02-20 2021-04-19 ty-Led Development tions nvelope ERY THROUGH DISRUPTIVE A GRICULTURAL TECHNOLOGY PLATFORM LINKING SMALL LI VESTOCK OWNERS TO VETE RINARY AND ARTIFICIAL INSE MINATION SERVICES KE-NAKURU COUNTY-27701 Project Coordination and Ma Request for Quota Single Stage - One E 4-GO-RFQ / Supply and deliv IDA / 59000 Post Limited 528.08 0.00 Signed 2022-03-05 2022-03-23 2022-04-02 2022-07-01 nagement tions nvelope ery of speakers KE-NAKURU COUNTY-27701 8-GO-RFQ / Supply and deliv Supporting Community-Driv Request for Quota Single Stage - One E IDA / 59000 Post Limited 9,661.84 0.00 Signed 2022-03-08 2022-03-21 2022-04-05 2022-07-22 ery of furniture for the 20 Ad en Development tions nvelope ministrative Assistants Page 2 KE-NAKURU COUNTY-27701 9-GO-RFQ / Supply and deliv Supporting Community-Driv Request for Quota Single Stage - One E Under Imple IDA / 59000 Post Limited 10,540.18 0.00 2022-03-06 2022-03-21 2022-04-04 2022-07-03 ery of ICT Equipment for the en Development tions nvelope mentation 20 Administrative Assistants KE-NAKURU COUNTY-27691 1-GO-RFQ / Supply and Deliv Project Coordination and Ma Request for Quota Single Stage - One E ery of 20 (NO) Mobile based IDA / 59000 Post Limited 6,159.96 0.00 Canceled 2022-03-05 2022-04-03 2022-07-02 nagement tions nvelope mechanization which help tra ctor owners manage their eq uipment. KE-NAKURU COUNTY-27690 3-GO-RFQ / Supply and deliv Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 3,378.80 0.00 Canceled 2022-03-08 2022-04-06 2022-07-05 ery of (8 No) Mobile phones nagement tions nvelope and 4 (No) digital projectors KE-NAKURU COUNTY-30248 9-GO-RFQ / SUPPLY AND DEL Supporting Community-Driv Request for Quota Single Stage - One E Under Imple IDA / 59000 Post Limited 67,911.71 0.00 2022-07-20 2022-09-06 2022-08-31 2023-03-29 IVERY OF 20 MOTOR CYCLES en Development tions nvelope mentation FOR THE TWENTY IMPLEMEN TING WARDS KE-NAKURU COUNTY-31444 Supporting County Communi Request for Quota Single Stage - One E Under Imple 9-GO-RFQ / Provision of 140 L IDA / 59000 Post Limited 3,695.56 0.00 2022-09-06 2022-07-17 2022-10-10 2022-11-09 ty-Led Development tions nvelope mentation icenses for Market Technolog y with Mshamba KE-NAKURU COUNTY-31680 9-GO-RFQ / Supply and Deliv Supporting County Communi Request for Quota Single Stage - One E Pending Impl IDA / 59000 Post Limited 3,379.00 0.00 2022-09-08 2022-10-05 2022-11-04 ery of 8 (No) mobile Phones ty-Led Development tions nvelope ementation and 4(No) Digital Projectors KE-NAKURU COUNTY-31681 1-GO-RFQ / Supply and Deliv Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 6,160.00 0.00 Signed 2022-09-09 2022-07-17 2022-10-07 2022-11-06 ery of 20 (No) Mobile based t ty-Led Development tions nvelope racking devices for mechaniz ation KE-NAKURU COUNTY-31770 0-GO-RFQ / Supply,Delivery,I Strengthening Producer Org nstallation Testing and Com Request for Quota Single Stage - One E IDA / 59000 anizations and Value Chain Post Limited 96,920.52 0.00 Canceled 2022-09-28 2022-10-31 2022-11-30 missioning of Chicken Slaugh tions nvelope Development terhouse Equipment Iin Baha ti Ward in Bahati Sub County KE-NAKURU COUNTY-31775 7-GO-RFQ / SUPPLY AND DELI Supporting County Communi Request for Quota Single Stage - One E Under Imple IDA / 59000 Post Limited 8,762.76 0.00 2022-09-28 2022-09-28 2022-11-23 2023-05-22 VERY OF HIGH VALUE AGRO ty-Led Development tions nvelope mentation FOREST TREE SEEDLINGS KE-NAKURU COUNTY-31681 2-GO-RFB / Supply, Delivery and commissioning of Agricul Strengthening Producer Org Single Stage - One E Pending Impl tural Mechanization Equipme IDA / 59000 anizations and Value Chain Post Request for Bids Open - National 252,268.76 0.00 2022-10-07 2022-10-11 2022-11-10 2022-11-17 2022-12-15 2023-02-13 nvelope ementation nt for Nakuru Potato Cooper Development ative Union at the Agricultura l Mechanization Services in L ondon Ward Nakuru West Su b County KE-NAKURU COUNTY-31520 0-GO-RFQ / Supply, Delivery, Strengthening Producer Org Installation ,Equipping and C Request for Quota Single Stage - One E Under Imple IDA / 59000 anizations and Value Chain Post Limited 42,763.16 0.00 2022-09-12 2022-09-12 2022-10-09 2023-01-07 ommissioning of a greenhou tions nvelope mentation Development se at the Agricultural Trainin g Center in London Ward Na kuru West Sub County KE-NAKURU COUNTY-34989 8-GO-RFQ / SUPPLY AND DELI Supporting Community-Driv Request for Quota Single Stage - One E Under Imple IDA / 59000 Post Limited 17,424.83 0.00 2023-03-20 2023-04-14 2023-05-29 VERY OF 20 DESKTOPS FOR T en Development tions nvelope mentation HE 20 CDDC WARDS KE-NAKURU COUNTY-27701 5-GO-RFQ / Supply and deliv Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 660.11 0.00 Canceled 2022-03-08 2022-04-06 2022-07-05 ery of Advertising Materials ( nagement tions nvelope T-Shirts, Fliers, Brochures) KE-NAKURU COUNTY-36361 6-GO-RFQ / SUPPLY AND DELI Strengthening Producer Org Request for Quota Single Stage - One E Pending Impl VERY OF (8 NO) DESKTOP CO IDA / 59000 anizations and Value Chain Post Limited 8,683.07 0.00 2023-05-28 2023-06-28 2023-09-26 tions nvelope ementation MPUTERS AND ACCESSORIES Development FOR THE CDDC REGISTERE D SACCOS NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-NAKURU COUNTY-18071 2-CS-CQS / RECRUITMENT OF Supporting Community-Driv Consultant Qualifi IDA / 59000 Post Open - National 50,000.00 23,156.56 Signed 2020-06-22 2020-09-14 2020-07-13 2020-08-26 2020-11-25 2020-09-25 2021-01-27 2020-10-30 2021-02-13 2022-01-04 SERVICE PROVIDER FOR BEE en Development cation Selection KEEPING VALUE CHAIN KE-NAKURU COUNTY-18071 5-CS-CQS / RECRUITMENT OF Supporting Community-Driv Consultant Qualifi IDA / 59000 Post Open - National 50,000.00 23,066.99 Signed 2020-06-22 2020-09-14 2020-07-13 2020-08-26 2020-11-25 2020-09-25 2021-02-12 2020-10-30 2021-02-13 2022-01-04 SERVICE PROVIDERS FOR DAI en Development cation Selection RY VALUE CHAIN KE-NAKURU COUNTY-18121 4-CS-CQS / RECRUITMENT OF Supporting Community-Driv Consultant Qualifi IDA / 59000 Post Open - National 50,000.00 23,075.76 Signed 2020-06-22 2020-09-14 2020-07-09 2020-08-22 2020-11-25 2020-09-21 2021-02-22 2020-10-26 2021-03-12 2021-12-31 SERVICE PROVIDERS FOR IRI en Development cation Selection SH POTATOES VALUE CHAIN KE-NAKURU COUNTY-18122 9-CS-CQS / RECRUITMENT OF Supporting Community-Driv Consultant Qualifi IDA / 59000 Post Open - National 50,000.00 23,048.51 Signed 2020-06-22 2020-09-14 2020-07-13 2020-08-26 2020-11-25 2020-09-25 2021-02-12 2020-10-30 2021-02-13 2021-12-31 SERVICE PROVIDERS FOR PO en Development cation Selection ULTRY VALUE CHAIN Page 3 KE-NAKURU COUNTY-14937 1-CS-QCBS / Consultancy Ser Supporting Community-Driv Quality And Cost- IDA / 59000 Post Open - National 199,765.50 0.00 Canceled 2019-03-19 2019-04-09 2019-05-23 2019-06-20 2019-07-20 2019-08-24 2019-09-28 2020-09-27 vice for the four selected pri en Development Based Selection ority value chains under val ue chain development INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-NAKURU COUNTY-27692 Project Coordination and Ma 2-CS-CDS / Provision of 8(No) IDA / 59000 Post Direct Selection Direct 8,537.79 0.00 Under Review 2022-03-01 2021-03-01 2022-03-13 2022-04-10 2022-07-02 nagement licenses and 1 (No) data anal ytics KE-NAKURU COUNTY-27700 Project Coordination and Ma Under Implement 2-CS-CDS / Provision of 3(No IDA / 59000 Post Direct Selection Direct 9,238.89 0.00 2022-03-01 2022-03-01 2022-03-09 2022-06-17 2022-04-17 2022-07-16 nagement ation ) hand held soil sensor equip ment KE-NAKURU COUNTY-27694 5-CS-CDS / Provision of 3 (No Project Coordination and Ma Under Implement IDA / 59000 Post Direct Selection Direct 5,543.33 0.00 2022-03-01 2022-05-25 2022-03-08 2022-03-31 2022-06-30 ) ACS System Licence and 3 ( nagement ation No) ACS Server Set Up Page 4 PROCUREMENT PLAN (Textual Part) Project information: P176767: Timor-Leste COVID-19 Response and Health System Preparedness Project Project Implementation agency: Ministry of Health Date of the Procurement Plan: September 18, 2022 Period covered by this Procurement Plan: October 1, 2022 – December 31, 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Government Procurement legislation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. • The procurement is open to eligible firms from any country; • The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; • Right for the Bank to review procurement documentation and activities; • Maintenance of records of the Procurement process; • Procurement Documents acceptable to the Bank shall be used; • Bids shall be evaluated using only post-qualification for procurement of goods, works and non-consulting services. • Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health safety ("ESHS") risks impacts. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Timor-Leste : Timor-Leste COVID-19 Response and Health System Preparedness Project PLAN General Information Country: Timor-Leste 2022-09-30 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P176767 GPN Date: Project Name: Timor-Leste COVID-19 Response and Health System Preparedness Project Loan / Credit No: / , TF / B9704 Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Strengthen h TL-HERPT/GO-01 / 4 units, Pr ealth system capacities for h Request for Quota Open - Internationa Single Stage - One E Under Imple / Post 172,000.00 0.00 2022-10-22 2022-12-17 2023-06-15 oject Operational Vehicles ealth emergency preparedn tions l nvelope mentation ess and delivery of essential health servic es Component 2: Strengthen h TL-HERPT/GO-02 / 6 units, A ealth system capacities for h Request for Quota Open - Internationa Single Stage - One E Under Imple dvance Multifunction Vehicle / Post 382,800.00 0.00 2022-10-22 2022-12-17 2023-06-15 ealth emergency preparedn tions l nvelope mentation s ess and delivery of essential health servic es Component 2: Strengthen h TL-HERPT/GO-03 / 30 units, ealth system capacities for h Request for Quota Open - Internationa Single Stage - One E / Post 47,500.00 0.00 Canceled 2022-10-29 2022-12-24 2023-06-22 Laptop for Surveillance ealth emergency preparedn tions l nvelope ess and delivery of essential health servic es Component 2: Strengthen h TL-HERPT/GO-04 / 80 units, ealth system capacities for h Request for Quota Open - Internationa Single Stage - One E Under Imple Desktop Computers for Surve / Post 80,000.00 0.00 2022-10-29 2022-12-24 2023-06-22 ealth emergency preparedn tions l nvelope mentation illance ess and delivery of essential health servic es Component 2: Strengthen h TL-HERPT/GO-05 / 100 units, ealth system capacities for h Request for Quota Open - Internationa Single Stage - One E Under Imple / Post 258,750.00 0.00 2022-10-22 2022-12-17 2023-06-15 Motorbikes for Surveillance ealth emergency preparedn tions l nvelope mentation ess and delivery of essential health servic es TL-HERPT/GO-06 / ICT equip Component 2: Strengthen h ment ((3 Scanners, 3 Printers ealth system capacities for h Request for Quota Open - Internationa Single Stage - One E Under Imple / Post 50,000.00 0.00 2022-10-29 2022-12-24 2023-06-22 , 2 Projectors & 3 Photocopie ealth emergency preparedn tions l nvelope mentation r Machines) ess and delivery of essential health servic es Component 2: Strengthen h TL-HERPT/GO-07 / Office fur ealth system capacities for h Request for Quota Open - Internationa Single Stage - One E Pending Impl niture (10 filing cabinets,10 / Post 20,000.00 0.00 2022-11-05 2022-12-31 2023-06-29 ealth emergency preparedn tions l nvelope ementation office tables & 10 chairs) ess and delivery of essential health servic es Component 2: Strengthen h TL-HERPT/GO-03A / Five Lap ealth system capacities for h Pending Impl tops for Project Management TF / B9704 Post Direct Selection Direct - National 7,920.00 0.00 2023-05-07 2023-05-12 2023-06-16 2023-12-13 ealth emergency preparedn ementation and Monitoring ess and delivery of essential health servic es Component 2: Strengthen h TL-HERPT/GO-03B / 25 units, ealth system capacities for h Request for Quota Single Stage - One E Pending Impl TF / B9704 Post Open - National 39,580.00 0.00 2023-05-12 2023-07-07 2024-01-03 Laptop for Surveillance ealth emergency preparedn tions nvelope ementation ess and delivery of essential health servic es NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TP-MOH-001-CS-INDV / Proje Component 3: Project mana Individual Consult Pending Impleme TF / B9704 Post Open - National 144,000.00 0.00 2023-05-29 2023-07-17 2023-08-07 2023-09-11 2024-03-09 ct Manager SPMU gement, monitoring and eva ant Selection ntation luation TP-MOH-002-CS-INDV / Proc Component 3: Project mana Pending Impleme TF / B9704 Post Direct Selection Direct - National 108,000.00 0.00 2023-05-29 2023-06-08 2023-08-12 2024-02-08 urement Officer gement, monitoring and eva ntation luation TP-MOH-003-CS-INDV / Finan Component 3: Project mana Pending Impleme TF / B9704 Post Direct Selection Direct - National 54,000.00 0.00 2023-05-29 2023-06-08 2023-08-12 2024-02-08 cial Management officer gement, monitoring and eva ntation luation Page 1 Procurement Plan I. General 1. Project Information Country : Kenya Recipient : Republic of Kenya Project Name : National Agriculture and Rural Inclusive Growth Loan Credit No. : IDA 59000 2. Date of General Procurement Notice : 9th February 2018 3. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services 1. Thresholds for the Method of Procurement: Method of Procurement Thresholds for Method (US$ equivalent) Open International (Goods) Equal to or more than 3 million Open National ( Goods) – Open < $3 million Tender as per PPDA 2015 RFQ (Goods) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Open International (Works) Equal to or more than 15 million Open National (Works) - Open Less than 15 million Tender as per PPDA 2015 RFQ (works) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Method of Procurement Thresholds for Method (US$ equivalent) Open International (Non-consulting Equal to or More than 3 million Services) Open National (Non-consulting Less than 3 million Services) - Open Tender as per PPDA 2015 Direct Contracting No threshold; meet requirements of Bank’s Procurement Regulations Prior Review: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection (Project Procurement Risk Rating is “High”): (a) Goods, information technology and Non-consulting Services: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1.5 million (b) Works (including turnkey, supply & installation of plant and equipment and PPP); First procurement under the project irrespective of value and all procurements estimated to cost more than USD 5 million and The prior review thresholds will be reviewed during the implementation of the project and modified, based on the risk assessment. 2. For contracts subject to prior review, the Borrower shall seek the Bank’s no objection before agreeing to: a. an extension of the stipulated time for execution of a contract that has an impact on the planned completion of the project; b. any material modification of the scope of the Works, Goods, Non- consulting services or Consulting Services, or other significant changes to the terms and conditions of the contract; c. any variation order or contract amendment (except in cases of extreme urgency), including due to extension of time, that singly or combined with all previous variation orders or amendments, increases the original contract amount by more than 15% (fifteen percent); or d. the proposed termination of the contract. The Borrower / IA shall provide a copy of all amendments to the contract to the Bank for its records. 3. Prequalification Not Applicable Domestic Preference. The provision of domestic preference shall be applied in the procurement of goods following international market approach in accordance with Annex VI of the Regulations. Domestic preference shall not apply in the procurement of works. 4. Reference to Standard Procurement Documents Bank’s Standard RFB Goods and RFP Consulting Services dated July 2016 will be used as a base and incorporating suitable modifications and the same would be agreed with the Bank subject international competition. 5. Any Other Special Procurement Arrangements A. Procurement approach under CDD Approach by Communities: Applicable if stipulated in the PAD. B. When approaching the national market, as agreed in the Procurement Plan, the Open Tender procedure of Public Procurement and Asset Disposal Act 2015 and Regulations 2017 may be used. The specific Requirements for national open competitive procurement include the following: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. Other national procurement arrangements (other than national open competitive procurement), that may be applied by the Borrower (such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti-Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. In all cases, the national procurement procedures to be used shall give due attention to quality aspects. 6. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Selection methods of procurement of Consultants' Services (Firms): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Quality and Cost Based As per requirements of para 7.3 of the Selection (QCBS) Regulations Quality Based Selection As per requirements of para 7.8 to 7.10 (QBS) of the Regulations Selection based on a Fixed As per requirements of para 7.4 and 7.5 of the Budget (FBS) Regulations Selection Based on Least As per requirements of para 7.6 and 7.7 of the Cost Basis (LCS) Regulations Selection based on As per requirements of para 7.11 and 7.12 of Consultant’s Qualification the Regulations (CQ) Direct Must meet the requirements of Para 7.13 to 7.15 of the Regulations, and with prior agreement in PP with the Bank. The short list may consist of all National consultants in case the estimated cost is less than USD 300,000 Procurement methods for Selection of Individual Consultants (IC): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Open Competitive As per requirements of para 7.36 and 7.37 of Selection the Regulations Limited Competitive As per requirements of para 7.38 of the Selection Regulations Direct Must meet the requirements of Para 7.39 of the Regulations, and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Regulations Prior Review Thresholds: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 0.5 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.2 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. PROCUREMENT Kenya : National Agricultural and Rural Inclusive Growth Project PLAN General Information Country: Kenya 2019-10-02 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153349 GPN Date: 2018-02-09 Project Name: National Agricultural and Rural Inclusive Growth Project Loan / Credit No: IDA / 59000 Embu County Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-EMBU COUNTY-137530-C Project Coordination and Ma Request for Quota Single Stage - One E 2020-06-0 IDA / 59000 Post Limited 21,734.84 17,788.64 Completed 2019-10-21 2019-12-02 2019-12-07 2019-12-20 W-RFQ / Maintenance of buil nagement tions nvelope 4 ding KE-EMBU COUNTY-137568-C Supporting County Communi Single Stage - One E 2020-08-0 W-RFB / Civil works for Rupin IDA / 59000 Post Request for Bids Open - National 801,719.03 0.00 Canceled 2019-10-30 2019-11-04 2019-12-04 2020-01-03 2020-02-07 ty-Led Development nvelope 5 gazi - weru Irrigation Scheme KE-EMBU COUNTY-173636-C Supporting County Communi Single Stage - One E 1,146,846.8 2021-06-3 W-RFB / Civil works for Rupin IDA / 59000 Post Request for Bids Open - National 1,490,000.00 Signed 2020-05-22 2020-06-02 2020-05-28 2020-06-16 2020-06-23 2020-06-21 2020-07-17 2020-06-29 2020-09-05 ty-Led Development nvelope 9 0 gazi - Weru Irrigation Sche me. KE-EMBU COUNTY-192245-C Supporting County Communi Single Stage - One E 2021-04-2 W-RFB / Procurement for the IDA / 59000 Post Request for Bids Open - National 160,000.00 0.00 Canceled 2020-09-08 2020-12-17 2020-09-11 2021-03-09 2020-09-30 2020-10-08 2020-10-29 ty-Led Development nvelope 7 disilting of Gitinangugu conc rete dam. KE-EMBU COUNTY-222788-C Supporting Community-Driv Request for Quota Single Stage - One E Under Imple 2021-10-0 W-RFQ / Construction of ITIIR IDA / 59000 Post Limited 140,000.00 0.00 2021-03-08 2021-05-20 2021-04-05 en Development tions nvelope mentation 2 A-KAGUMORI EARTH DAM KE-EMBU COUNTY-222776-C W-RFQ / Proposed desilting o Supporting Community-Driv Request for Quota Single Stage - One E Under Imple 2021-10-2 IDA / 59000 Post Limited 140,000.00 0.00 2021-03-05 2021-03-31 2021-04-24 f Gitinangugu Reinforced con en Development tions nvelope mentation 1 crete dam at Mbeere south KE-EMBU COUNTY-233017-C Request for Quota W-RFQ / Construction of 15 N Supporting Community-Driv Request for Quota Single Stage - One E tions - Small Work Under Imple 2021-09-0 IDA / 59000 Post Limited 45,000.00 0.00 2021-05-10 2021-06-07 o Farm ponds 1000m3 for SL en Development tions nvelope s (Emergency) SP mentation 5 M activities in Gitinangugu ca D -Competitive tchments KE-EMBU COUNTY-251847-C Request for Quota W-RFQ / Construction of 10 N Supporting County Communi Request for Quota Single Stage - One E tions - Small Work Under Imple 2022-01-0 IDA / 59000 Post Limited 30,000.00 0.00 2021-09-09 2021-10-11 o Farm ponds 100m3 for SLM ty-Led Development tions nvelope s (Emergency) SP mentation 9 activities at ITIIRA-Kagumori D -Competitive catchments Request for Quota KE-EMBU COUNTY-302549-C Supporting Community-Driv Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-02-2 W-RFQ / Desilting and rehabil IDA / 59000 Post Limited 124,928.69 0.00 2022-08-01 2022-08-26 en Development tions nvelope s (Emergency) SP mentation 2 itation of Kangondo water pa D -Competitive n KE-EMBU COUNTY-346922-C Request for Quota W-RFQ / Construction of 10N Supporting County Communi Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-06-2 IDA / 59000 Post Limited 39,000.00 0.00 2023-03-08 2023-03-27 o Farm ponds 100m3 for SLM ty-Led Development tions nvelope s (Emergency) SP mentation 5 Activities at kangondo in Em D -Competitive bu County . GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-EMBU COUNTY-137430-G Project Coordination and Ma Request for Quota Single Stage - One E O-RFQ / purchase of office fur IDA / 59000 Post Limited 18,820.39 16,964.75 Completed 2019-10-19 2019-10-23 2019-12-05 2019-11-22 2020-06-02 2020-02-27 nagement tions nvelope niture and fittings KE-EMBU COUNTY-137945-G Supporting County Communi Request for Quota Single Stage - One E Under Imple O-RFB / Agricultural material IDA / 59000 Post Limited 61,005.73 0.00 2020-01-27 2020-07-27 2020-02-21 2020-05-31 ty-Led Development tions nvelope mentation s supplies and small Equipme nt KE-EMBU COUNTY-172311-G Project Coordination and Ma Request for Quota Single Stage - One E Under Imple O-RFQ / Supply , delivery and IDA / 59000 Post Limited 90,000.00 0.00 2020-05-13 2020-06-09 2020-05-29 2020-06-03 nagement tions nvelope mentation Installation of of I.C.T Equip ment KE-EMBU COUNTY-180187-G Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 80,000.00 0.00 Signed 2020-09-04 2020-11-23 2020-09-19 2020-10-19 O-RFQ / procurement of moto nagement tions nvelope rcycles KE-EMBU COUNTY-207853-G Supporting Community-Driv Request for Quota Single Stage - One E Under Imple O-RFQ / supply and delivery IDA / 59000 Post Limited 10,000.00 0.00 2020-12-10 2020-10-01 2020-12-11 2021-01-10 en Development tions nvelope mentation of filling cabinets for CDDC KE-EMBU COUNTY-233187-G Strengthening Producer Org O-RFQ / Procurement of pick- Request for Quota Single Stage - One E Under Imple IDA / 59000 anizations and Value Chain Post Limited 49,000.00 0.00 2021-05-10 2021-06-04 2021-09-02 up for aggregation of milk at tions nvelope mentation Development Kawanjara Commercial Villag e. KE-EMBU COUNTY-239078-G O-RFQ / Supply , delivery an Supporting County Communi Request for Quota Single Stage - One E Under Imple d marking of CDDC computer IDA / 59000 Post Limited 14,200.00 0.00 2021-06-14 2021-06-29 2021-09-27 ty-Led Development tions nvelope mentation /printer/office furniture(office desk &chair) in 20 wards KE-EMBU COUNTY-252094-G O-RFQ / Procurement of farm Strengthening Producer Org Request for Quota Single Stage - One E Under Imple tractor,subsoiler ,Ripper and IDA / 59000 anizations and Value Chain Post Limited 51,000.00 0.00 2021-09-20 2021-11-15 2022-02-13 tions nvelope mentation trailer for mweka farmers co Development operative society limited KE-EMBU COUNTY-272593-G O-RFQ / procurement of man Strengthening Producer Org Request for Quota Single Stage - One E agement information manag IDA / 59000 anizations and Value Chain Post Limited 35,845.00 0.00 Signed 2022-01-19 2022-09-14 2022-02-11 2022-04-30 tions nvelope ement system for mburugu f Development armers cooperative society Page 1 KE-EMBU COUNTY-297248-G O-DIR / Procurement of soil s Strengthening Producer Org Under Imple canner for soil sampling and IDA / 59000 anizations and Value Chain Post Direct Selection Direct 8,500.00 0.00 2022-06-22 2022-06-22 2022-06-29 2022-08-08 2022-11-06 mentation analysis for greengrams,man Development go and dairy value chains KE-EMBU COUNTY-297267-G Strengthening Producer Org O-RFQ / Procurement of bran Request for Quota Single Stage - One E Pending Impl IDA / 59000 anizations and Value Chain Post Limited 12,700.00 0.00 2022-06-22 2022-07-23 2022-10-21 ded materials and public add tions nvelope ementation Development ress system for DAT cohort KE-EMBU COUNTY-297278-G Strengthening Producer Org Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of agric IDA / 59000 anizations and Value Chain Post Limited 4,030.00 0.00 2022-06-20 2022-07-15 2022-10-15 tions nvelope ementation ultural Materials for DAT co Development hort KE-EMBU COUNTY-355395-G O-DIR / Supply and Delivery Project Coordination and Ma Under Imple of Digital Kits /software licens IDA / 59000 Post Direct Selection Direct - National 15,868.80 0.00 2023-04-17 2023-04-17 2023-04-18 2023-05-03 2023-06-17 nagement mentation e, Tabs and smart projectors . for the 12 trainers by Kuza Biashara. KE-EMBU COUNTY-363632-G O-RFQ / Supply and delivery Supporting Community-Driv Request for Quota Single Stage - One E Pending Impl IDA / 59000 Post Limited 10,853.84 0.00 2023-05-29 2023-06-29 2023-09-27 of 10No Desktop computers en Development tions nvelope ementation and 10No printers for SACCO s NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-EMBU COUNTY-355326-N Project Coordination and Ma Under Imple C-DIR / Provision of technolo IDA / 59000 Post Direct Selection Direct - National 18,021.60 0.00 2023-04-14 2023-04-14 2023-04-14 2023-04-29 2023-06-28 nagement mentation gical services to farmers CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-EMBU COUNTY-175743-C Supporting Community-Driv Consultant Qualifi S-CQS / Recruitment of servic IDA / 59000 Post Open - National 50,000.00 0.00 Canceled 2020-05-24 2020-06-10 2020-05-27 2020-06-19 2020-06-22 2020-06-29 2021-09-30 en Development cation Selection e provider for Dairy Value ch ain . KE-EMBU COUNTY-175744-C Supporting Community-Driv Consultant Qualifi S-CQS / Recruitment of servi IDA / 59000 Post Open - National 50,000.00 0.00 Canceled 2020-05-24 2020-06-10 2020-05-27 2020-06-19 2020-06-22 2020-06-29 2021-09-30 en Development cation Selection ce provider for greengram va lue chain KE-EMBU COUNTY-175745-C Supporting Community-Driv Consultant Qualifi S-CQS / Recruitment of servic IDA / 59000 Post Open - National 50,000.00 0.00 Canceled 2020-05-24 2020-06-10 2020-05-27 2020-06-19 2020-06-22 2020-06-29 2021-09-30 en Development cation Selection e provider for mango value c hain KE-EMBU COUNTY-175747-C Supporting Community-Driv Consultant Qualifi S-CQS / Recruitment of servic IDA / 59000 Post Open - National 50,000.00 0.00 Canceled 2020-05-24 2020-06-10 2020-05-27 2020-06-19 2020-06-22 2020-07-16 2021-10-03 en Development cation Selection e provider for local chicken v alue chain INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 Armenia Social Investment and Local Development Project (P148836) Procurement Plan I. General 1. Date of General Procurement Notice: December 2, 2014 2. Period covered by this procurement plan: from January 2015 to December, 2019 The TOR of consulting assignments (individual and firm) and technical specifications of packages are subject of prior agreement with the TTL. All cancellation of selection process and/or re-invitation shall be subject to Bank’s prior review. All the contracts whose cost estimation was below the Bank’s prior review threshold are subject to prior review if the financial offer of the selected firm exceeds such threshold at the proposals evaluation stage. . Irrespective of the thresholds the selection of all consultants (firm and individuals) hired for legal work or for procurement activities as well as the individual hired for long-term technical assistance or advisory services for duration of the Project (or most of it) are subject to prior review. In case of a slice and package arrangement, the prior review threshold is determined based on the aggregate value of individual contracts to be awarded under such arrangement. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. NCB (Goods) packages > US$ 200,000 and All the contracts (< USD 100,000 and < USD first 2 contracts subject to 500,000) irrespective of retroactive estimation financing 2. NCB (Works) packages > US$ 500,000 and (< USD 200,000 and < USD first 2 contracts 4,000,000) irrespective of estimation 3. Shopping (Goods) packages All the contracts (≤USD 100,000 ) subject to First 2 contracts retroactive financing 4. Shopping (Minor Works) packages First 3 contracts (≤ USD 200,000 ) 5. Direct contracting (Goods and All the contracts Works) All the contracts subject to irrespective of retroactive estimation financing 2. Prequalification. No prequalification is envisaged. 3. Proposed Procedures for Community participation in Procurement (as per paragraph. 3.19 of the Guidelines: implementation procedures of procurement of Goods, Works and Non- Consulting services and selection of Consulting services to be followed by the communities are described in detail in the POM. 4. Reference to (if any) Project Operational/Procurement Manual: Operational Manual for Social Investment and Local Development Project to be approved by the Bank. 5. Any Other Special Procurement Arrangements: Some furniture for schools and kindergartens totaling USD 70000 (Shopping) equivalent may be procured in accordance with the provisions of paragraph 1.11 of the procurement Guidelines 6. Procurement Packages with Methods and Time Schedule On the later stage the details (description of packages, schedule, methods etc.) should be provided. 1 2 3 4 5 6 7 Estimate Revie d Domesti Envisage w Cost Numbe Ref c d start of by US$ r of . Description Prefere procurem Bank Million packag No. nce ent (Prior (tax es (yes/no) process / inclusive Post) amount) Summary of the NCB Prior / (Goods) 1.8 12 NO Jul.2015 Post packages Summary of the NCB Prior / (Works) 27.46 115 NO May.2015 Post packages Summary of the Shopping Prior / (Goods) 0.76 9 NO Feb.2015 Post packages Summary of the Shopping Prior / (Minor Works) 5.4 30 NO May.15 Post packages Total 35.42 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments >US$ 100,000 and first 2 contracts under each 1. Competitive Methods (Firms) method of selection All the irrespective of estimation contracts All the contracts 2. Single Source subject to irrespective of estimation retroactive > US$ 50,000 and first 2 3. Individual financing contracts All the contracts 4. Sole source selection irrespective of estimation 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $200,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Consultants’ Services, including Training, up to an aggregate amount not exceed $400,000 equivalent may be procured in accordance with the provisions of paragraph 1.14 of the Consultant Guidelines. 4. Consultancy Assignments with Selection Methods and Time Schedule On the later stage the details (description of packages, schedule, methods etc.) should be provided. 1 2 3 4 5 6 Envisage Re Estimat Selecti d start f. Description of ed Review on of No Assignment Cost by Bank Metho procure . US$ (Prior / Post) d ment million process May.2015 Technical Supervision of Construction (9 contracts) 0.65 CQ (3 Prior / Post contracts) Architectural Design and Jan.2015 Author Supervision (21 1.6 CQ (4 Prior / Post contracts) contracts) Jan.2015 Expertise of Architectural Design (5 contracts) 0.08 CQ (1 Prior / Post contract) Expertise of Buildings and Jan.2015 Constructions (6 0.1 CQ (1 Prior / Post contracts) contract) Local Government Jul.2015 Financial Training (3 0.27 CQ (1 Prior / Post contracts) contract) Apr.2016 Beneficiary and Impact Assessment (2 contracts) 0.09 CQ (1 Prior / Post contract) Quality of civil works assessment 0.02 CQ Sep.2016 Prior / Post Study Tours, Staff Trainings and Seminars 0.12 SOE Jul.2015 Activities to support the transition from ASIF to 0.3 TDF Total Consultant and Training Services 3.23 PROCUREMENT Armenia : Armenia Social Investment and Local Development Project PLAN General Information Country: Armenia 2017-12-07 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P148836 GPN Date: Project Name: Armenia Social Investment and Local Development Project Loan / Credit No: IBRD / 84830, IBRD / 90600 Armenian Territorial Development Fund Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned TTV-14 / Reconstruction of t ASIF Institutional Strengthen Request for Quota Single Stage - One E 2018-09-1 he Drinking Water Supply Sy IBRD / 84830 Post Limited 121,140.00 117,044.39 Completed 2018-01-30 2018-02-02 2018-03-06 2018-03-01 ing and Project Management tions nvelope 7 stem in Varagavan, marz of T avush TSQ-14 / Reconstruction of t ASIF Institutional Strengthen Single Stage - One E 2019-08-0 he Kindergarten in Village Te IBRD / 84830 Post Request for Bids Open - National 412,665.00 316,541.82 Completed 2018-01-29 2018-01-29 2018-01-30 2018-01-31 2018-02-27 2018-02-22 2018-04-13 2018-03-15 2018-05-26 2018-05-04 ing and Project Management nvelope 9 gh, marz of Syunik TAR-08 AND TAT-09 / Recon struction of the Kindergarden ASIF Institutional Strengthen Single Stage - One E 2019-10-0 in Metsamor, Marz of Armavir IBRD / 84830 Post Request for Bids Open - National 808,162.00 591,539.50 Completed 2018-03-06 2018-03-05 2018-03-11 2018-03-06 2018-04-08 2018-04-03 2018-05-23 2018-04-11 2018-07-04 2018-05-14 ing and Project Management nvelope 2 and Reconstruction of the Kin dergarden in Aygavan, Marz of Ararat (with 2 lots) TTV-17 / Reconstruction of t ASIF Institutional Strengthen Single Stage - One E 2019-07-0 he External Water Supply Sys IBRD / 84830 Post Request for Bids Open - National 319,194.00 264,640.70 Completed 2018-04-03 2018-05-07 2018-04-10 2018-05-11 2018-05-08 2018-06-08 2018-06-22 2018-06-25 2018-08-03 2018-07-06 ing and Project Management nvelope 9 tem in Tsaghkavan, marz of Tavush TAN-13 / Renovation of the K indergarten Area in Village A ASIF Institutional Strengthen Request for Quota Single Stage - One E 2018-08-0 IBRD / 84830 Post Limited 38,551.00 38,127.02 Completed 2018-04-10 2018-04-06 2018-06-01 2018-04-25 ghdzq and Construction of th ing and Project Management tions nvelope 5 e External Engineering Nets, marz of Aragatsotn TAT-11 / Reconstruction of o ASIF Institutional Strengthen Single Stage - One E 2020-04-1 ne building of Yeraskh school IBRD / 84830 Post Request for Bids Open - National 296,410.00 243,112.08 Completed 2019-02-13 2019-02-25 2019-02-15 2019-03-05 2019-03-15 2019-04-02 2019-04-14 2019-04-19 2019-05-26 2019-05-20 ing and Project Management nvelope 0 into kindergarten, marz of Ar arat TVZ-09 / Reconstruction of K Support to Socio-Economic Request for Quota Single Stage - One E 2019-12-1 hndzorut water source and dr IBRD / 84830 Development and Capacity Post Open - National 33,000.00 33,737.31 Completed 2019-08-31 2019-09-04 2019-10-05 2019-09-24 tions nvelope 4 inking water line Building at the Local Level TTV-18 / Reconstruction of t Support to Socio-Economic Single Stage - One E 2021-01-2 he Drinking Water Distributin IBRD / 84830 Development and Capacity Post Request for Bids Open - National 391,000.00 325,626.73 Completed 2019-11-14 2019-11-12 2019-11-19 2019-11-13 2019-12-17 2019-12-10 2020-01-16 2019-12-20 2020-02-27 2020-02-07 nvelope 2 g Network of Paravakar Building at the Local Level TSH-21 / Construction of "St. Support to Socio-Economic Single Stage - One E 2021-07-1 Mariam" Kindergarten in Gyu IBRD / 84830 Development and Capacity Post Request for Bids Open - National 412,000.00 353,035.83 Completed 2020-03-10 2020-03-10 2020-03-15 2020-03-10 2020-04-12 2020-04-07 2020-05-12 2020-04-20 2020-06-23 2020-06-04 nvelope 8 mri Building at the Local Level TSQ-16 / Construction of the Support to Socio-Economic Single Stage - One E 2021-11-0 drinking water pipeline in Kh IBRD / 84830 Development and Capacity Post Request for Bids Open - National 177,000.00 0.00 Canceled 2020-12-25 2020-12-23 2020-12-30 2020-12-23 2021-02-03 2021-01-27 2021-03-05 2021-04-07 nvelope 3 natsakh community Building at the Local Level TLR-13 / Reconstruction of t Support to Socio-Economic Single Stage - One E 2022-05-2 he second building of kinderg IBRD / 84830 Development and Capacity Post Request for Bids Open - National 364,000.00 265,250.60 Signed 2021-03-17 2021-03-15 2021-03-24 2021-03-16 2021-04-21 2021-04-12 2021-05-21 2021-04-26 2021-07-02 2021-05-21 nvelope 8 arten No. 11 in Vanadzor Building at the Local Level Support to Socio-Economic TSH-22 / "Zangak" kindegart Single Stage - One E 2022-08-0 IBRD / 84830 Development and Capacity Post Request for Bids Open - National 443,000.00 841,967.18 Signed 2021-04-27 2021-04-16 2021-05-04 2021-04-16 2021-06-01 2021-05-14 2021-07-01 2021-06-16 2021-08-12 2021-07-16 en construction of Gyumri nvelope 7 Building at the Local Level Support to Socio-Economic TSH-23 / Reconstruction of t Single Stage - One E 2022-04-0 IBRD / 84830 Development and Capacity Post Request for Bids Open - National 311,000.00 265,690.20 Signed 2021-04-27 2021-04-16 2021-05-02 2021-04-16 2021-05-30 2021-05-14 2021-06-29 2021-06-09 2021-08-10 2021-07-01 he kindegarten of Panik nvelope 7 Building at the Local Level Support to Socio-Economic TSH-19 / Construction of kin Single Stage - One E 2022-08-0 IBRD / 84830 Development and Capacity Post Request for Bids Open - National 407,000.00 374,000.87 Signed 2021-04-27 2021-04-19 2021-05-04 2021-04-19 2021-06-01 2021-05-17 2021-07-01 2021-06-16 2021-08-12 2021-07-16 degarten of Horom nvelope 7 Building at the Local Level TSQ-16-2 / Construction of t Support to Socio-Economic Single Stage - One E 2022-03-1 he drinking water pipeline in IBRD / 84830 Development and Capacity Post Request for Bids Open - National 160,000.00 159,702.94 Signed 2021-04-30 2021-04-20 2021-05-05 2021-04-20 2021-06-02 2021-05-18 2021-07-02 2021-06-02 2021-08-13 2021-06-25 nvelope 1 Khnatsakh Building at the Local Level W-27.29 / Lot 1 "W-27, Cons truction and repair of irrigati on system in Byureghavan e Request for Bids - nlarged community" Support to Intercommunity S Single Stage - One E Small Works SPD 2022-06-2 Lot 2 "W-29, Construction an IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 805,000.00 552,259.96 Completed 2021-06-10 2021-06-01 2021-06-15 2021-06-01 2021-07-13 2021-06-29 2021-08-12 2021-07-26 2021-09-23 2021-08-31 nvelope (1 envelope proce 0 d repair of a gravity irrigation ment Initiatives ss) system in Hoghmik, Goghovit , and Torosgyugh settlement s of Sarapat community" AFT-TV-01 / Construction of pumping station, drinking wa Request for Bids - Support to Socio-Economic ter supply pipeline and daily Single Stage - One E Small Works SPD 2022-08-3 IBRD / 90600 Development and Capacity Post Request for Bids Open - National 361,000.00 360,928.87 Signed 2021-06-21 2021-06-21 2021-06-26 2021-06-21 2021-07-24 2021-07-19 2021-08-23 2021-08-05 2021-10-04 2021-09-07 regulation reservoir (DRR), re nvelope (1 envelope proce 0 Building at the Local Level construction of the distributio ss) n network of Archis settleme nt W-29 / Construction and rep Support to Intercommunity S air of a gravity irrigation syst Single Stage - One E 2022-05-0 IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 285,000.00 0.00 Canceled 2021-04-27 2021-04-19 2021-05-04 2021-04-19 2021-06-01 2021-05-17 2021-07-01 2021-08-12 em in Hoghmik, Goghovit, an nvelope 9 ment Initiatives d Torosgyugh settlements of Sarapat community AFT-TV-02 / Construction of pumping station, drinking wa Request for Bids - Support to Socio-Economic ter supply pipeline and daily Single Stage - One E Small Works SPD 2022-06-2 IBRD / 90600 Development and Capacity Post Request for Bids Open - National 240,000.00 0.00 Canceled 2021-06-10 2021-06-01 2021-06-15 2021-06-01 2021-07-13 2021-06-29 2021-08-12 2021-09-23 regulation reservoir (DRR), re nvelope (1 envelope proce 0 Building at the Local Level construction of the distributio ss) n network of Lchkadzor settle ment Page 1 AFT-TV-02-2/TV-03 / Constru Request for Bids - Support to Socio-Economic ction and Expansion of drinki Single Stage - One E Small Works SPD 2022-08-0 IBRD / 90600 Development and Capacity Post Request for Bids Open - National 383,000.00 296,825.31 Signed 2021-07-27 2021-07-22 2021-08-01 2021-07-22 2021-08-29 2021-08-19 2021-09-28 2021-09-24 2021-11-09 2021-10-22 ng water supply systems of L nvelope (1 envelope proce 6 Building at the Local Level chkadzor and Movses settle ss) ments W-29-2 / Construction and re Request for Bids - Support to Intercommunity S pair of a gravity irrigation sys Single Stage - One E Small Works SPD 2022-06-1 IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 310,000.00 0.00 Canceled 2021-08-06 2021-08-03 2021-08-13 2021-08-03 2021-09-10 2021-08-31 2021-10-10 2021-09-17 2021-11-21 tem in Hoghmik, Goghovit, a nvelope (1 envelope proce 9 ment Initiatives nd Torosgyugh settlements o ss) f Sarapat community W-29-3 / Construction and re Request for Bids - Support to Intercommunity S pair of a gravity irrigation sys Single Stage - One E Small Works SPD 2022-09-0 IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 310,000.00 0.00 Canceled 2021-10-21 2021-10-07 2021-10-28 2021-10-07 2021-11-25 2021-11-11 2021-12-25 2021-11-22 2022-02-05 tem in Hoghmik, Goghovit, a nvelope (1 envelope proce 3 ment Initiatives nd Torosgyugh settlements o ss) f Sarapat community AFT-TV-03-2 / Expansion of Request for Bids - Movses settlement water sup Support to Socio-Economic Single Stage - One E Small Works SPD 2022-07-1 ply system: construction of p IBRD / 90600 Development and Capacity Post Request for Bids Open - National 138,000.00 0.00 Canceled 2021-10-29 2021-10-19 2021-11-03 2021-10-19 2021-12-01 2021-11-16 2021-12-31 2021-11-22 2022-02-12 nvelope (1 envelope proce 2 umping station and pumping Building at the Local Level ss) pipeline, repair of a daily reg ulation reservoir (DRR). W-36/W-37 / Construction of Request for Bids - Support to Intercommunity S parking lots in the enlarged c Single Stage - One E Small Works SPD 2022-12-0 IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 302,000.00 0.00 Canceled 2021-12-20 2021-12-15 2021-12-27 2021-12-16 2022-01-24 2022-01-26 2022-02-23 2022-04-06 ommunities of Akunk, Kotayk nvelope (1 envelope proce 2 ment Initiatives marz and Geghamasar, Gegh ss) arkunik marz of RA AFT-TV-03-3 / Expansion of Request for Bids - Movses settlement water sup Support to Socio-Economic Single Stage - One E Small Works SPD 2022-11-0 ply system: construction of p IBRD / 90600 Development and Capacity Post Request for Bids Open - National 178,000.00 0.00 Canceled 2022-03-09 2022-04-12 2022-03-14 2022-04-12 2022-04-11 2022-05-10 2022-05-11 2022-06-21 2022-06-22 nvelope (1 envelope proce 4 umping station and pumping Building at the Local Level ss) pipeline, repair of a daily reg ulation reservoir (DRR). W-29-4 / Construction and re Request for Bids - Support to Intercommunity S pair of a gravity irrigation sys Single Stage - One E Small Works SPD 2023-03-2 IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 301,000.00 0.00 Canceled 2022-03-09 2022-03-16 2022-04-13 2022-05-13 2022-06-24 tem in Hoghmik, Goghovit, a nvelope (1 envelope proce 1 ment Initiatives nd Torosgyugh settlements o ss) f Sarapat community W-36-2/W-37-2 / Constructio Request for Bids - n of parking lots in the enlarg Support to Intercommunity S Single Stage - One E Small Works SPD 2022-11-2 ed communities of Akunk, Ko IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 301,000.00 0.00 Canceled 2022-02-11 2022-02-07 2022-02-18 2022-03-06 2022-03-18 2022-03-07 2022-04-17 2022-05-29 nvelope (1 envelope proce 5 tayk marz and Geghamasar, ment Initiatives ss) Gegharkunik marz of RA Request for Bids - WAFT-KQ-01 / Construction Support to Intercommunity S Single Stage - One E Small Works SPD 2023-03-2 of parking lot in the enlarged IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 203,000.00 256,679.97 Signed 2022-05-30 2022-05-02 2022-06-06 2022-05-02 2022-07-04 2022-05-30 2022-08-03 2022-08-04 2022-09-28 2022-09-10 nvelope (1 envelope proce 7 community of Akunk, Kotayk ment Initiatives ss) marz of RA Request for Bids - AFT-GQ-01 / Renovation of t Support to Socio-Economic Single Stage - One E Small Works SPD 2023-01-2 he wrestling hall in the Hous IBRD / 90600 Development and Capacity Post Request for Bids Open - National 67,000.00 0.00 Canceled 2022-05-30 2022-04-27 2022-06-06 2022-04-27 2022-07-04 2022-05-25 2022-08-03 2022-09-28 nvelope (1 envelope proce 6 e of Culture of the Akunk co Building at the Local Level ss) mmunity WAFT-SH-02 / Construction a Request for Bids - nd repair of a gravity irrigatio Support to Intercommunity S Single Stage - One E Small Works SPD 2023-04-2 n system in Hoghmik, Gogho IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 313,000.00 0.00 Canceled 2022-05-30 2022-05-03 2022-06-06 2022-05-03 2022-07-04 2022-05-31 2022-08-03 2022-08-04 2022-09-28 nvelope (1 envelope proce 6 vit, and Torosgyugh settleme ment Initiatives ss) nts of Sarapat community WAFT-GQ-01 / Construction Request for Bids - Support to Intercommunity S of a parking lot in the enlarg Single Stage - One E Small Works SPD 2023-04-1 IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 150,000.00 147,067.76 Signed 2022-06-20 2022-06-27 2022-06-27 2022-06-27 2022-07-25 2022-07-25 2022-08-24 2022-08-29 2022-10-19 2022-10-03 ed community of Geghamasa nvelope (1 envelope proce 7 ment Initiatives r, Gegharkunik marz of RA. ss) AFT-LR-02 / Replacement of Request for Quota aluminum stained glass wind Support to Intercommunity S Request for Quota Single Stage - One E tions - Small Work 2022-12-1 ows and renovation of bathro IBRD / 84830 ocial and Economic Develop Post Open - National 83,000.00 83,033.81 Signed 2022-07-26 2022-07-25 2022-09-13 2022-09-13 tions nvelope s (Emergency) SP 2 oms of Stepanavan "Culture ment Initiatives D -Competitive and Entertainment Center" Request for Quota AFT-SH-03 / Overhaul of the Support to Intercommunity S Request for Quota Single Stage - One E tions - Small Work 2023-03-0 balcony and gymnasium of G IBRD / 84830 ocial and Economic Develop Post Open - National 122,000.00 0.00 Canceled 2022-08-24 2022-09-08 2022-10-19 tions nvelope s (Emergency) SP 3 yumri school No. 1 ment Initiatives D -Competitive Request for Bids - AFT-LR-01 / Reconstruction o Support to Intercommunity S Single Stage - One E Small Works SPD 2023-07-1 f the Lori Berd community ce IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 328,000.00 0.00 Canceled 2022-08-19 2022-09-15 2022-08-26 2022-09-15 2022-09-23 2022-10-13 2022-10-23 2022-12-18 nvelope (1 envelope proce 6 nter, with the construction of ment Initiatives ss) the second floor AFT-TV-03-4 / Expansion of Request for Bids - Movses settlement water sup Support to Socio-Economic Single Stage - One E Small Works SPD 2023-06-0 ply system: construction of p IBRD / 90600 Development and Capacity Post Request for Bids Open - National 208,000.00 0.00 Canceled 2022-09-23 2022-09-28 2022-10-26 2022-11-25 2023-01-06 nvelope (1 envelope proce 5 umping station and pumping Building at the Local Level ss) pipeline, repair of a daily reg ulation reservoir (DRR). WAFT-SH-01/WAFT-SH-02-2 / Lot 1 "Reconstruction of the I rrigation System in Amasia C Request for Bids - Support to Intercommunity S onsolidated Community ", Lo Single Stage - One E Small Works SPD 2023-11-1 IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 952,000.00 0.00 Signed 2022-10-04 2022-10-06 2022-10-09 2022-10-06 2022-11-06 2022-11-03 2022-12-06 2022-12-20 2023-01-17 t 2 "Construction and repair nvelope (1 envelope proce 3 ment Initiatives of a gravity irrigation system ss) in Hoghmik, Goghovit, and T orosgyugh settlements of Sar apat community" AFT-TV-03-4/AFT-TV-04 / Lot 1, Expansion of Movses settl ement water supply system: Request for Bids - construction of pumping stati Support to Socio-Economic Single Stage - One E Small Works SPD 2024-05-1 on and pumping pipeline, rep IBRD / 90600 Development and Capacity Post Request for Bids Open - National 946,000.00 0.00 Canceled 2022-10-04 2022-09-29 2022-10-09 2022-09-29 2022-11-06 2022-10-27 2022-12-06 2022-11-21 2023-01-17 nvelope (1 envelope proce 1 air of a daily regulation reser Building at the Local Level ss) voir (DRR), Lot 2, Construction of Drinkin g Water Line and Springs Int akes of Getahovit Settlement AFT-GQ-01-2/AFT-AN-02 / Lo t 1, "Renovation of the wrestl Request for Bids - Support to Socio-Economic ing hall in the House of Cultu Single Stage - One E Small Works SPD 2024-03-1 IBRD / 90600 Development and Capacity Post Request for Bids Open - National 937,000.00 0.00 Signed 2022-10-04 2022-10-17 2022-10-09 2022-10-17 2022-11-06 2022-11-14 2022-12-06 2022-12-08 2023-01-17 re of the Akunk community", nvelope (1 envelope proce 2 Building at the Local Level Lot 2, "Construction of the Al ss) agyaz Community Center"․ Request for Bids - AFT-LR-01-2 / Reconstructio Support to Intercommunity S Single Stage - One E Small Works SPD 2023-09-2 n of the Lori Berd community IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 331,000.00 0.00 Canceled 2022-11-01 2022-11-01 2022-11-08 2022-11-01 2022-12-06 2022-11-15 2023-01-05 2023-03-02 nvelope (1 envelope proce 8 center, with the construction ment Initiatives ss) of the second floor Page 2 AFT-VZ-02 / Construction of Request for Bids - Support to Intercommunity S a Sewerage System and Bio-t Single Stage - One E Small Works SPD 2024-01-2 IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 691,000.00 0.00 Signed 2023-01-17 2023-01-17 2023-01-24 2023-01-17 2023-02-21 2023-02-14 2023-03-21 2023-03-06 2023-05-02 reatment Facility in Nor Avan nvelope (1 envelope proce 7 ment Initiatives District of Yeghegnadzor City ss) Request for Bids - AFT-LR-01-3 / Reconstructio Support to Intercommunity S Single Stage - One E Small Works SPD Under Imple 2023-12-0 n of the Lori Berd community IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 337,000.00 0.00 2023-01-24 2023-01-26 2023-01-31 2023-01-26 2023-02-28 2023-02-23 2023-03-28 2023-04-21 2023-05-09 nvelope (1 envelope proce mentation 5 center, with the construction ment Initiatives ss) of the second floor Request for Bids - Support to Intercommunity S Single Stage - One E Small Works SPD 2023-11-1 TEST / TEST IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 1.00 0.00 Canceled 2023-01-18 2022-12-01 2023-01-23 2023-01-18 2023-03-06 2023-01-18 2023-04-05 2023-01-18 2023-05-17 nvelope (1 envelope proce 3 ment Initiatives ss) AFT-GQ-01-3 / Renovation of Request for Quota Support to Intercommunity S the Wrestling Hall Located in Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-11-2 IBRD / 90600 ocial and Economic Develop Post Open - National 85,000.00 0.00 2023-06-04 2023-06-01 2023-07-30 the House of Culture of Akun tions nvelope s (Emergency) SP mentation 7 ment Initiatives k Community of Gegharkunik D -Competitive Marz of RoA Request for Bids - AFT-TV-05 / Renovation of th Support to Intercommunity S Single Stage - One E Small Works SPD Under Imple 2024-06-0 e kindergarten in Khashtarak IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 547,000.00 0.00 2023-05-30 2023-06-01 2023-06-04 2023-06-01 2023-07-02 2023-06-29 2023-08-01 2023-09-12 nvelope (1 envelope proce mentation 8 settlement of Tavush marz of ment Initiatives ss) RoA Request for Quota AFT-SH-03-4 / Overhaul of th Support to Socio-Economic Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-01-2 e balcony and gymnasium of IBRD / 84830 Development and Capacity Post Open - National 135,000.00 0.00 2023-06-29 2023-05-30 2023-08-24 tions nvelope s (Emergency) SP mentation 1 Gyumri School No. 1, Shirak Building at the Local Level D -Competitive marz, RA AFT-TV-04-2 / Construction o Request for Bids - Support to Socio-Economic f external water line and spri Single Stage - One E Small Works SPD Under Imple 2024-12-2 IBRD / 90600 Development and Capacity Post Request for Bids Open - National 796,000.00 0.00 2023-06-07 2023-06-08 2023-06-12 2023-06-08 2023-07-10 2023-07-24 2023-09-04 ng connections of Getahovit nvelope (1 envelope proce mentation 7 Building at the Local Level community, Tavush marz, RA ss) Request for Bids - AFT-SH-01 / Construction of Support to Intercommunity S Single Stage - One E Small Works SPD Under Imple 2024-12-2 a kindergarten in the Nor Kny IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 1,202,000.00 0.00 2023-06-28 2023-06-22 2023-07-05 2023-06-22 2023-08-02 2023-08-16 2023-09-27 nvelope (1 envelope proce mentation 0 ak community of Shirank mar ment Initiatives ss) z, RA AFT-AR-01 / Procurement of Request for Bids - Support to Intercommunity S Construction of the Sports Gr Single Stage - One E Small Works SPD 2024-01-0 IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 123,000.00 0.00 Canceled 2023-05-25 2023-05-29 2023-05-30 2023-05-29 2023-06-27 2023-06-26 2023-07-27 2023-09-07 ound of the Myasnikyan Settl nvelope (1 envelope proce 5 ment Initiatives ement School of Armavir Mar ss) z of RoA AFT-AR-01-2 / Procurement Request for Quota Support to Intercommunity S of Construction of the Sports Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-01-0 IBRD / 90600 ocial and Economic Develop Post Open - National 123,000.00 0.00 2023-07-15 2023-09-09 Ground of the Myasnikyan Se tions nvelope s (Emergency) SP lementation 7 ment Initiatives ttlement School of Armavir M D -Competitive arz of RoA TSQ-01 / Reconstruction of H Support to Socio-Economic Request for Quota Open - Internationa ouse-museum after Sero Kha IBRD / 84830 Development and Capacity Prior 0.00 145,640.22 Signed 2015-10-06 tions l nzadyan in Goris, Marz of Sy Building at the Local Level uniq TTV-02 / Reconstruction of t Support to Socio-Economic Request for Quota Open - Internationa he third building of N2 kinder IBRD / 84830 Development and Capacity Prior 0.00 138,337.21 Signed 2015-09-19 tions l garten in Berd, Marz of Tavo Building at the Local Level ush TAT-01 / Reinforcement, ove Support to Socio-Economic Request for Quota Open - Internationa rhaul of ambulatory in the vill IBRD / 84830 Development and Capacity Prior 0.00 78,366.58 Signed 2015-09-29 tions l age of Norashen, Marz of Ara Building at the Local Level rat TSH-01 / Construction of a s Support to Socio-Economic Single Stage - One E chool for 100 pupils in the vill IBRD / 84830 Development and Capacity Prior Request for Bids Open - National 0.00 386,367.08 Signed 2015-11-10 2015-11-30 nvelope age of Vardaqar, Marz of Shir Building at the Local Level ak TVZ-01 / Reinforcement, rec Support to Socio-Economic onstruction of the kindergart Single Stage - One E IBRD / 84830 Development and Capacity Prior Request for Bids Open - National 0.00 294,656.01 Signed 2015-11-23 2015-12-24 en in the village of Zaritap, M nvelope Building at the Local Level arz of Vayots Dzor GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-11 / Supply of furniture f ASIF Institutional Strengthen Request for Quota Single Stage - One E IBRD / 84830 Post Limited 96,700.00 96,365.03 Completed 2018-03-11 2018-03-07 2018-05-06 2018-03-26 2018-07-15 2018-08-23 or kindergartens for marzes ing and Project Management tions nvelope of RA TG-12 / Supply of goods for kindergartens, schools and c ASIF Institutional Strengthen Single Stage - One E IBRD / 84830 Post Request for Bids Open - National 184,000.00 150,596.63 Completed 2018-08-06 2018-08-14 2018-08-11 2018-08-15 2018-09-08 2018-09-12 2018-10-08 2018-09-28 2018-11-19 2018-10-05 2019-02-02 2019-02-21 ommunity centers in the mar ing and Project Management nvelope zes of RA (consisted of 3 Lots ) TIIG-01 / Procurement of Ve Support to Intercommunity S Single Stage - One E hicles, Equipment and Trash IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 924,950.00 806,891.39 Completed 2018-10-24 2018-10-24 2018-10-29 2018-11-08 2018-11-26 2018-11-27 2018-12-26 2018-12-14 2019-02-06 2019-01-11 2019-05-07 2019-05-08 nvelope Bins for Communities ment Initiatives TG-13 / Procurement of furni ASIF Institutional Strengthen Request for Propo Single Stage - One E ture for the kindergartens of IBRD / 84830 Post Limited 45,115.00 30,222.32 Completed 2018-11-15 2018-11-12 2018-11-20 2018-11-14 2018-11-27 2018-11-21 2018-12-07 2018-11-22 2018-12-21 2018-11-30 2019-01-15 2018-12-25 ing and Project Management sals nvelope the regions of the RoA TIIG-02 / Procurement of Ve Support to Intercommunity S Single Stage - One E hicles and Equipment for Co IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 933,970.00 492,656.34 Completed 2019-03-28 2019-04-03 2019-04-02 2019-04-04 2019-04-30 2019-05-02 2019-05-30 2019-06-19 2019-07-11 2019-06-26 2019-10-09 2019-09-13 nvelope mmunities ment Initiatives TG-14 / Supply of furniture f ASIF Institutional Strengthen Request for Quota Single Stage - One E or schools and kindergartens IBRD / 84830 Post Open - National 89,000.00 56,070.85 Completed 2019-04-08 2019-04-18 2019-06-03 2019-05-22 2019-10-01 2019-10-29 ing and Project Management tions nvelope for marzes of RoA TIIG-03 / Procurement of Ve Support to Intercommunity S Single Stage - One E hicles and Equipment for Co IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 933,460.00 920,649.72 Completed 2019-05-24 2019-05-31 2019-05-29 2019-06-04 2019-06-26 2019-07-02 2019-07-26 2019-07-18 2019-09-06 2019-08-16 2019-12-05 2019-12-14 nvelope mmunities ment Initiatives Support to Intercommunity S TIIG-04 / Procurement of 4 M Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 377,000.00 272,097.79 Completed 2019-06-24 2019-06-25 2019-06-29 2019-07-31 2019-07-27 2019-07-31 2019-08-26 2019-08-06 2019-10-07 2019-08-27 2019-12-21 2019-12-18 ultifunctional Excavators nvelope ment Initiatives TIIG-05 / Procurement of Ve Support to Intercommunity S Single Stage - One E hicles and Equipment for Co IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 893,080.00 741,001.05 Completed 2019-08-05 2019-08-15 2019-08-10 2019-08-29 2019-09-07 2019-09-13 2019-09-08 2019-09-27 2019-10-20 2019-11-01 2020-01-18 2020-01-21 nvelope mmunities consisted of 9 Lot ment Initiatives s Page 3 TIIG-06 / Procurement of Ve Support to Intercommunity S Single Stage - One E hicles and Equipment for Co IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 685,995.00 416,500.74 Completed 2019-09-10 2019-09-11 2019-09-15 2019-09-13 2019-09-17 2019-10-17 2019-10-17 2019-11-01 2019-11-28 2019-11-26 2020-02-26 2019-12-13 nvelope mmunities ment Initiatives Support to Intercommunity S TIIG-07 / Procurement of 4 M Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 378,000.00 369,714.75 Completed 2019-11-06 2019-10-31 2019-11-11 2019-11-01 2019-12-09 2019-11-29 2020-01-08 2019-12-04 2020-02-19 2019-12-18 2020-05-04 2020-06-03 ultifunctional Excavators nvelope ment Initiatives TG-15 / Supply of furniture f ASIF Institutional Strengthen Request for Quota Single Stage - One E or kindergartens, schools an IBRD / 84830 Post Open - National 34,850.00 26,899.28 Signed 2019-12-07 2019-12-26 2020-01-19 2020-01-18 2020-03-04 2020-02-29 ing and Project Management tions nvelope d cultural centers for the ma rzes of RoA Support to Intercommunity S TIIG-06/8 / TIIG-06/8 Contrac IBRD / 84830 ocial and Economic Develop Post Direct Selection Direct 2,310.00 1,775.45 Completed 2020-01-08 2020-01-09 2020-01-08 2019-09-12 2020-01-08 2019-12-04 2020-01-08 2019-12-16 t "1 Hydraulic Twist Bucket" ment Initiatives TIIG-08 / Procurement of 500 ASIF Institutional Strengthen Request for Quota Single Stage - One E IBRD / 84830 Post Open - National 93,025.00 72,076.69 Completed 2020-03-02 2020-02-28 2020-04-13 2020-04-16 2020-06-12 2020-06-19 Metal Trash Bins ing and Project Management tions nvelope TIIG-09 / Procurement of co Support to Intercommunity S mmunal equipment for Areni, Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 916,000.00 862,774.43 Completed 2020-03-15 2020-03-17 2020-03-20 2020-03-18 2020-04-17 2020-04-15 2020-05-17 2020-05-06 2020-06-28 2020-06-11 2020-09-26 2020-09-11 Sisian, Akhtala, Gladzor, Egh nvelope ment Initiatives egis communities TIIG-10 / Procurement of Agr Support to Intercommunity S icultural Equipment for Shno Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 949,585.00 0.00 Canceled 2020-03-29 2020-04-01 2020-04-03 2020-04-01 2020-05-01 2020-05-31 2020-07-12 2020-10-10 gh, Akhtala, Eghegis, Sarcha nvelope ment Initiatives pet, Ani, Eghvard Communiti es TIIG-11 / Procurement of Agr Support to Intercommunity S icultural Heavy Equipment fo Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 812,000.00 678,871.19 Completed 2020-04-29 2020-05-08 2020-05-04 2020-05-08 2020-06-01 2020-06-05 2020-07-01 2020-06-22 2020-08-12 2020-08-13 2020-11-10 2020-11-14 r Shnogh, Akhtala, Yeghegis, nvelope ment Initiatives Sarchapet, Ani, Yeghvard Co mmunities TIIGS-01 / Procurement of a Support to Intercommunity S Request for Quota Single Stage - One E Motor Cultivator for Akhtala IBRD / 84830 ocial and Economic Develop Post Open - National 5,000.00 5,059.10 Completed 2020-05-04 2020-05-09 2020-06-29 2020-06-18 2020-08-28 2020-08-12 tions nvelope Community ment Initiatives TIIGS-02 / Procurement of A Support to Intercommunity S Request for Quota Single Stage - One E gricultural Sprayers for Shno IBRD / 84830 ocial and Economic Develop Post Open - National 21,000.00 7,059.79 Completed 2020-05-04 2020-05-09 2020-06-29 2020-06-18 2020-08-28 2020-07-24 tions nvelope gh, Akhtala and Sarchapet C ment Initiatives ommunities TIIGS-03 / Procurement of Se Support to Intercommunity S Request for Quota Single Stage - One E ed Drills for Shnogh, Akhtala IBRD / 84830 ocial and Economic Develop Post Open - National 53,000.00 37,834.27 Completed 2020-05-04 2020-05-09 2020-06-29 2020-06-18 2020-08-28 2020-08-05 tions nvelope and Sarchapet Communities ment Initiatives TIIGS-04 / Procurement of B Support to Intercommunity S Request for Quota Single Stage - One E aling Machines for Yeghegis IBRD / 84830 ocial and Economic Develop Post Open - National 32,000.00 23,671.07 Completed 2020-05-04 2020-05-09 2020-06-29 2020-06-18 2020-08-28 2020-07-18 tions nvelope and Yeghvard Communities ment Initiatives TIIGS-05 / Procurement of Gr Support to Intercommunity S Request for Quota Single Stage - One E ass-Mowing Machines for Akh IBRD / 84830 ocial and Economic Develop Post Open - National 6,500.00 3,426.08 Completed 2020-05-04 2020-05-09 2020-06-29 2020-06-18 2020-08-28 2020-08-15 tions nvelope tala, Yeghegis and Yeghvard ment Initiatives Communities TIIGS-06 / Procurement of Pl Support to Intercommunity S oughs, Harrows and Cultivato Request for Quota Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Open - National 73,000.00 53,397.79 Completed 2020-05-04 2020-05-09 2020-06-29 2020-06-18 2020-08-28 2020-08-15 rs for Shnogh, Yeghegis, Sarc tions nvelope ment Initiatives hapet and Yeghvard Commu nities TIIG-12 / Procurement of co Support to Intercommunity S mmunal equipment for Shog Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 983,000.00 831,467.34 Completed 2020-05-22 2020-05-27 2020-05-27 2020-06-28 2020-06-24 2020-06-29 2020-07-24 2020-08-04 2020-09-04 2020-09-09 2020-12-03 2021-02-11 hakat, Akhtala, Gladzor, Yegh nvelope ment Initiatives egis, Sarchapet, Ani, Yeghvar d Communities TIIG-13 / Procurement of Agr Support to Intercommunity S icultural Heavy Equipment fo Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 483,000.00 410,152.86 Completed 2020-06-22 2020-06-29 2020-06-27 2020-07-06 2020-07-25 2020-07-27 2020-08-24 2020-08-17 2020-10-05 2020-09-29 2021-01-03 2020-12-15 r Kapan, Metsavan, Akunq, G nvelope ment Initiatives eghamasar, Alaverdi Commu nities TIIG-14 / Procurement of Co Support to Intercommunity S Single Stage - One E mmunal Equipment for Kapa IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 957,000.00 780,364.18 Completed 2020-07-13 2020-07-10 2020-07-18 2020-07-13 2020-08-15 2020-08-13 2020-09-14 2020-09-14 2020-10-26 2020-10-21 2021-02-23 2021-03-18 nvelope n, Metsavan, Marmashen Co ment Initiatives mmunities TIIG-15 / Procurement of Co Support to Intercommunity S Single Stage - One E mmunal Equipment for Gegh IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 771,550.00 585,502.29 Completed 2020-08-19 2020-08-21 2020-08-24 2020-08-24 2020-09-21 2020-09-22 2020-10-21 2020-09-30 2020-12-02 2020-11-06 2021-04-01 2021-03-10 nvelope amasar, Akunq, Alaverdi Co ment Initiatives mmunities TG-16 / Procurement of Com ASIF Institutional Strengthen Request for Quota Single Stage - One E IBRD / 84830 Post Open - National 21,000.00 20,982.30 Signed 2020-09-30 2020-09-29 2020-11-25 2020-10-24 2021-02-03 puter equipment for ATDF ing and Project Management tions nvelope Support to Intercommunity S TIIGS-07 / Procurement of a Request for Quota Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Open - National 70,000.00 65,740.35 Completed 2020-10-03 2020-09-28 2020-11-28 2020-10-24 2021-02-26 2020-12-18 Bus for Ani community tions nvelope ment Initiatives TIIGS-08 / Procurement of a Support to Intercommunity S Request for Quota Single Stage - One E Mini-loader for Yeghvard com IBRD / 84830 ocial and Economic Develop Post Open - National 54,000.00 0.00 Canceled 2020-10-03 2020-09-28 2020-11-28 2021-02-26 tions nvelope munity ment Initiatives Support to Intercommunity S TIIGS-10 / Procurement of 1 Request for Quota Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Open - National 53,000.00 47,780.97 Completed 2020-10-26 2020-10-20 2020-12-21 2020-11-14 2021-04-20 2020-12-19 Mini-loader tions nvelope ment Initiatives TIIGS-09 / Procurement of 2 Support to Intercommunity S Request for Quota Single Stage - One E technical assistance cars wit IBRD / 84830 ocial and Economic Develop Post Open - National 51,000.00 50,998.75 Completed 2020-10-26 2020-10-20 2020-12-21 2020-11-14 2021-04-20 2021-02-10 tions nvelope h attachments ment Initiatives Support to Intercommunity S TIIGS-11 / Procurement of 25 Request for Quota Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Open - National 18,000.00 45,127.49 Completed 2020-10-26 2020-11-10 2020-12-21 2020-12-08 2021-02-19 2020-12-16 0 Garbage Container tions nvelope ment Initiatives TIIG-16 / Procurement of Co Support to Intercommunity S Single Stage - One E mmunal Equipment for Jrvez IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 288,000.00 274,664.33 Completed 2020-11-13 2020-11-12 2020-11-18 2020-12-02 2020-12-16 2020-12-21 2021-01-15 2020-12-29 2021-02-26 2021-02-12 2021-06-26 2021-05-21 nvelope h Community ment Initiatives TIIG-17 / Supply and installat Support to Intercommunity S ion of solar photovoltaic stati Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 191,600.00 160,964.78 Completed 2020-11-20 2021-04-12 2020-11-25 2021-04-12 2020-12-23 2021-05-10 2021-01-22 2021-05-27 2021-03-05 2021-06-30 2021-06-03 2022-01-28 ons on the territories of muni nvelope ment Initiatives cipal organizations in Charen tsavan Page 4 TG-17 / Procurement of a hy ASIF Institutional Strengthen Request for Quota Single Stage - One E IBRD / 84830 Post Open - National 2,500.00 2,047.05 Completed 2020-12-24 2021-01-18 2021-01-26 2021-02-06 2021-04-06 2021-03-02 brid portable computer for A ing and Project Management tions nvelope TDF TIIG-18 / Supply and installat Support to Intercommunity S Single Stage - One E ion of a solar photovoltaic sta IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 69,000.00 56,726.58 Completed 2021-07-22 2021-07-21 2021-07-27 2021-07-22 2021-08-24 2021-08-18 2021-09-23 2021-09-17 2021-11-04 2021-09-30 2022-02-02 2022-02-12 nvelope tion of Meghradzor communit ment Initiatives y. TIIG-19 / Procurement of Co Support to Intercommunity S mmunal and Agricultural Hea Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 940,000.00 825,122.95 Signed 2021-10-27 2021-10-25 2021-11-01 2021-10-26 2021-11-29 2021-11-23 2021-12-29 2021-12-13 2022-01-26 2022-01-19 2022-04-26 2022-04-17 vy Equipment for Ijevan, Meg nvelope ment Initiatives hradzor and Lermontovo Co mmunities TIIGS-12 / Procurement of 35 Support to Intercommunity S Request for Quota Single Stage - One E 0 Garbage Containers for Ijev IBRD / 84830 ocial and Economic Develop Post Open - National 58,500.00 0.00 Canceled 2021-11-01 2021-10-22 2021-12-27 2022-03-07 tions nvelope an Community ment Initiatives TG-18 / Supply of furniture f Support to Socio-Economic Request for Quota Single Stage - One E or St. Mariam kindergarten in IBRD / 84830 Development and Capacity Post Open - National 12,000.00 0.00 Canceled 2021-10-18 2021-10-01 2021-12-06 2022-01-15 tions nvelope Gyumri, Marz of Shirak Building at the Local Level TG-18-2 / Supply of furniture Support to Socio-Economic Request for Quota Single Stage - One E for St. Mariam kindergarten i IBRD / 84830 Development and Capacity Post Open - National 12,000.00 12,653.64 Completed 2021-11-05 2021-10-27 2021-12-24 2021-12-01 2022-02-22 2022-02-02 tions nvelope n Gyumri, Marz of Shirak Building at the Local Level TIIGS-13 / Procurement of 35 Support to Socio-Economic Request for Quota Single Stage - One E 0 Plastic Garbage Containers IBRD / 84830 Development and Capacity Post Open - National 64,500.00 54,051.12 Completed 2021-12-27 2021-12-21 2022-02-14 2022-02-09 2022-04-25 2022-05-24 tions nvelope for Ijevan Community Building at the Local Level TIIG-20 / Supply and installat Support to Intercommunity S ion of solar photovoltaic stati Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 212,000.00 180,863.60 Signed 2022-03-21 2022-03-17 2022-03-26 2022-03-17 2022-04-23 2022-04-14 2022-05-23 2022-04-29 2022-07-04 2022-05-26 2022-11-01 ons in Akunk, Lermontovo, B nvelope ment Initiatives yuregavan, Kapan communiti es. TG-19 / Supply of Computer ASIF Institutional Strengthen Request for Quota Single Stage - One E IBRD / 84830 Post Open - National 20,630.00 20,100.55 Signed 2022-03-26 2022-03-28 2022-05-21 2022-04-27 2022-07-30 equipment for ATDF ing and Project Management tions nvelope TIIG-21 / Supply and installat Support to Intercommunity S Single Stage - One E ion of solar photovoltaic stati IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 66,500.00 96,420.15 Signed 2022-05-10 2022-04-29 2022-05-15 2022-04-29 2022-06-12 2022-05-27 2022-07-12 2022-06-10 2022-08-23 2022-07-01 2022-12-21 nvelope ons in Tashir community ment Initiatives TIIG-22 / Supply and installat ion of solar photovoltaic stati Support to Intercommunity S Single Stage - One E ons in Sarchapet, Akhtala co IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 190,400.00 214,508.15 Signed 2022-06-03 2022-05-30 2022-06-08 2022-05-30 2022-07-06 2022-06-27 2022-08-05 2022-07-20 2022-09-16 2022-08-28 2023-01-14 nvelope mmunities of Lori marz and Y ment Initiatives eghegis of Vayots Dzor marz of RA TIIG-23 / Procurement of Equ Support to Intercommunity S Single Stage - One E ipment for Ground Road Main IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 385,100.00 390,748.04 Signed 2022-06-26 2022-06-28 2022-06-29 2022-06-28 2022-07-27 2022-07-26 2022-08-10 2022-08-08 2022-09-12 2022-09-01 2022-12-21 nvelope tenance ment Initiatives Support to Intercommunity S TIIG-24 / Procurement of Min Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 375,000.00 215,305.13 Signed 2022-06-26 2022-06-28 2022-06-29 2022-06-28 2022-07-27 2022-07-26 2022-08-10 2022-08-08 2022-09-12 2022-09-01 2022-12-21 i-Loaders nvelope ment Initiatives TIIG-25 / Procurement of Equ Support to Intercommunity S Single Stage - One E ipment for Public Service Pro IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 553,500.00 54,133.86 Signed 2022-06-26 2022-06-29 2022-06-29 2022-06-29 2022-07-27 2022-07-27 2022-08-10 2022-08-08 2022-09-12 2022-08-25 2022-12-21 nvelope vision ment Initiatives Support to Intercommunity S TIIG-26 / Procurement of Exc Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 695,200.00 486,279.54 Signed 2022-06-26 2022-06-29 2022-06-29 2022-06-29 2022-07-27 2022-07-27 2022-08-10 2022-08-08 2022-09-12 2022-09-13 2022-12-21 avator-Loaders nvelope ment Initiatives TIIG-27 / Supply and installat ion of solar photovoltaic stati Support to Intercommunity S ons in communities Stepanav Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 200,000.00 217,625.17 Signed 2022-07-06 2022-06-30 2022-07-11 2022-06-30 2022-08-08 2022-07-28 2022-09-07 2022-08-24 2022-10-19 2022-10-03 2023-02-16 an, Metsavan of Lori marz, Gl nvelope ment Initiatives adzor of Vayots Dzor marz, a nd Tsaghkahovit of Aragatsot ni marz of RA TIIG-28 / Supply and installat ion of solar photovoltaic stati Support to Intercommunity S Single Stage - One E ons in communities of Lori Be IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 119,000.00 12,102.90 Signed 2022-08-17 2022-08-29 2022-08-17 2022-08-29 2022-08-31 2022-09-12 2022-09-14 2022-09-19 2022-09-29 2022-10-08 2022-12-28 nvelope rd, Odzun of Lori marz, and S ment Initiatives hoghakat of Gegharkunik ma rz of RA TIIG-29 / Communal Equipm Support to Intercommunity S Single Stage - One E ent for Public Service Provisio IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 516,500.00 0.00 Signed 2022-08-15 2022-08-31 2022-08-17 2022-08-31 2022-08-31 2022-09-14 2022-09-07 2022-09-28 2022-09-23 2022-12-22 nvelope n2 ment Initiatives TG-20 / Supply of furniture f Support to Socio-Economic Request for Quota Single Stage - One E or Vanadzor N 1 and Panik ki IBRD / 84830 Development and Capacity Post Open - National 53,600.00 0.00 Signed 2022-09-16 2022-09-07 2022-10-17 2022-12-16 tions nvelope ndergartens Building at the Local Level SILD-AFG-01 / Procurement Support to Socio-Economic of Communal Equipment for Single Stage - One E IBRD / 90600 Development and Capacity Post Request for Bids Open - National 910,000.00 0.00 Canceled 2022-10-27 2022-12-28 2022-11-01 2022-12-29 2022-11-29 2023-01-31 2022-12-20 2023-01-17 2023-04-17 Ashtarak, Garni, Martuni, Sev nvelope Building at the Local Level an Communities SILD-AFG-02 / Procurement Support to Intercommunity S of 8 Dump Trucks for Abovya Single Stage - One E IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 920,000.00 0.00 Canceled 2023-01-17 2023-01-16 2023-01-22 2023-01-16 2023-02-19 2023-02-13 2023-03-12 2023-04-23 2023-08-01 n, Garni, Martuni, Metsamor, nvelope ment Initiatives Spitak and Pambak communi ties SILD-AFG-03 / Procurement Support to Intercommunity S Single Stage - One E of Garbage Trucks for Ashtar IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 937,000.00 0.00 Canceled 2023-01-29 2023-01-24 2023-02-03 2023-01-24 2023-03-03 2023-02-24 2023-03-24 2023-05-05 2023-08-13 nvelope ak and Metsamor Communiti ment Initiatives es SILD-AFG-04 / Procurement Support to Intercommunity S of Multifunctional Utility Vehi Single Stage - One E IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 930,000.00 0.00 Canceled 2023-02-06 2023-01-30 2023-02-11 2023-01-30 2023-03-11 2023-02-27 2023-04-01 2023-05-13 2023-08-21 cles for Ashtarak, Abovyan, N nvelope ment Initiatives or Hachn, Spitak, Metsamor Communities SILD-AFG-05 / Procurement Support to Intercommunity S of Garbage Containters for S Single Stage - One E Under Imple IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 471,500.00 0.00 2023-05-24 2023-05-25 2023-05-29 2023-05-25 2023-06-26 2023-06-22 2023-07-26 2023-09-06 2024-01-04 pitak, Vayk, Pambak, Vedi, Ar nvelope mentation ment Initiatives mavir and Metsamor Commu nities of RoA SILD-AFG-06 / Procurement Support to Intercommunity S of Technical Assistance Cars Single Stage - One E Under Imple IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 205,500.00 0.00 2023-05-24 2023-05-25 2023-05-29 2023-05-25 2023-06-28 2023-06-23 2023-07-28 2023-09-08 2024-01-06 for Ashtarak, Artik and Garni nvelope mentation ment Initiatives Communities of RoA Page 5 SILD-AFG-07 / Procurement Support to Intercommunity S Single Stage - One E Under Imple of Minibuses for Ashotsq, Mar IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 338,500.00 0.00 2023-05-24 2023-05-25 2023-05-29 2023-05-25 2023-06-30 2023-06-26 2023-07-30 2023-09-10 2023-12-19 nvelope mentation tuni, Nor Hachn and Vedi Co ment Initiatives mmunities of RoA SILD-AFG-08 / Procurement Support to Intercommunity S Single Stage - One E Under Imple of Graders for Armavir, Gava IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 668,000.00 0.00 2023-05-24 2023-05-25 2023-05-29 2023-05-25 2023-07-03 2023-06-27 2023-08-02 2023-09-13 2024-01-11 nvelope mentation r, Metsamor and Sevan Com ment Initiatives munities of RoA SILD-AFG-09 / Procurement Support to Intercommunity S of Excavators and a Mini-load Single Stage - One E Under Imple IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 961,500.00 0.00 2023-06-06 2023-05-30 2023-06-11 2023-05-30 2023-07-09 2023-08-08 2023-09-19 2024-01-17 er for Abovyan, Metsamor, P nvelope mentation ment Initiatives ambak, Nor Hachn, and Seva n Communities SILD-AFG-10 / Procurement of Multifunctional Excavators Support to Socio-Economic for Ashtarak, Garni, Martuni, Single Stage - One E Under Imple IBRD / 90600 Development and Capacity Post Request for Bids Open - National 953,000.00 0.00 2023-06-05 2023-06-01 2023-06-08 2023-06-01 2023-06-29 2023-06-23 2023-07-13 2023-08-24 2023-12-22 Sevan Communities, and Pro nvelope mentation Building at the Local Level curement of a Multifunctional Mini-Loader for Ashtarak Co mmunity SILD-AFG-11 / Procurement Support to Intercommunity S Single Stage - One E Under Imple of Garbage Trucks for Ashtar IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 962,000.00 0.00 2023-06-09 2023-06-01 2023-06-14 2023-06-01 2023-07-05 2023-06-22 2023-07-19 2023-08-30 2023-12-28 nvelope mentation ak and Metsamor Communiti ment Initiatives es SILD-AFG-12 / Procurement Support to Intercommunity S of Dump Trucks for Abovyan, Single Stage - One E Under Imple IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 940,000.00 0.00 2023-06-09 2023-06-01 2023-06-14 2023-06-01 2023-07-06 2023-06-26 2023-07-20 2023-08-31 2023-12-29 Garni, Martuni, Metsamor, Sp nvelope mentation ment Initiatives itak and Pambak communitie s SILD-AFG-13 / Procurement Support to Intercommunity S of Multifunctional Utility Vehi Single Stage - One E Under Imple IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 995,000.00 0.00 2023-06-09 2023-06-01 2023-06-14 2023-06-01 2023-07-06 2023-06-27 2023-07-20 2023-08-31 2023-12-29 cles for Ashtarak, Abovyan, N nvelope mentation ment Initiatives or Hachn, Spitak, Metsamor Communities SILD-AFG-21-SH / Procureme Support to Intercommunity S Request for Quota Single Stage - One E Pending Impl nt of Semi-Trucks for Vaghar IBRD / 90600 ocial and Economic Develop Post Open - National 49,000.00 0.00 2023-06-23 2023-08-11 2023-12-09 tions nvelope ementation shapat Community ment Initiatives SILD-AFG-SOL-01 / Supply a nd installation of solar photo Support to Intercommunity S Request for Quota Single Stage - One E Pending Impl voltaic plants in the communi IBRD / 90600 ocial and Economic Develop Post Open - National 166,000.00 0.00 2023-07-03 2023-08-28 2023-12-26 tions nvelope ementation ties of Masis and Ararat, Arar ment Initiatives at Marz, RA, and Tsaghkadzo r, Kotayk Marz, RA. Support to Socio-Economic TG-04-2 / Procurement of 2 c Single Stage - One E IBRD / 84830 Development and Capacity Prior Request for Bids Open - National 0.00 33,912.43 Signed 2016-05-19 2016-05-30 ompact SUV Cars nvelope Building at the Local Level Support to Socio-Economic TG-04-1 / Procurement of 5 Single Stage - One E IBRD / 84830 Development and Capacity Prior Request for Bids Open - National 0.00 62,761.66 Signed 2016-05-21 2016-05-30 Sedan Cars- Lot 1 nvelope Building at the Local Level Support to Socio-Economic TG-03 / Procurement of IT eq Request for Quota Open - Internationa IBRD / 84830 Development and Capacity Prior 0.00 9,473.65 Signed 2015-12-28 uipment tions l Building at the Local Level Support to Socio-Economic TG-04-3 / Procurement of 1 Single Stage - One E IBRD / 84830 Development and Capacity Prior Request for Bids Open - National 0.00 61,421.28 Canceled 2016-05-19 SUV Car nvelope Building at the Local Level Support to Socio-Economic TG-02 / Procurement of furni Request for Quota Open - Internationa IBRD / 84830 Development and Capacity Prior 0.00 7,841.45 Signed 2016-05-27 ture for ATDF tions l Building at the Local Level NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SSS-01 / Procurement of hot el services in Jermuk commu ASIF Institutional Strengthen IBRD / 84830 Post Direct Selection Direct 1,200.00 1,088.35 Completed 2021-09-30 2021-09-24 2021-09-30 2021-10-01 2021-10-04 2021-10-02 2021-10-07 2021-10-08 nity for the training participa ing and Project Management nts’ accommodation CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AUD-17 / AUDIT OF THE ARM ENIAN TERRITORIAL DEVELO PMENT FUND and OF THE SO ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 10,400.00 16,723.84 Completed 2018-01-31 2018-02-06 2018-02-07 2018-02-06 2018-03-07 2018-02-26 2018-03-28 2018-03-12 2018-04-18 2018-03-12 2018-05-15 2018-06-30 CIAL INVESTMENT AND LOCA ing and Project Management cation Selection L DEVELOPMENT (SILD) PROJ ECT FOR THE YEAR ENDED D ECEMBER 31, 2017 AUD-18 / AUDIT OF THE ARM ENIAN TERRITORIAL DEVELO PMENT FUND and OF THE SO ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 6,691.00 24,294.41 Completed 2018-11-29 2018-11-23 2018-12-04 2018-12-27 2018-12-30 2018-12-24 2019-01-20 2018-12-27 2019-02-08 2018-12-28 2019-02-26 2019-06-27 CIAL INVESTMENT AND LOCA ing and Project Management cation Selection L DEVELOPMENT (SILD) PROJ ECT FOR THE YEAR ENDED D ECEMBER 31, 2018 TPD-31 / Design and Author' s Supervision for Constructio ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 10,500.00 7,842.11 Completed 2019-08-05 2019-08-07 2019-08-19 2019-08-15 2019-10-02 2019-08-30 2019-10-09 2019-09-11 2019-11-13 2019-09-11 2020-02-26 2020-05-06 n of the kindergarten after "S ing and Project Management cation Selection aint Maryam" in Gyumri TBA-01 / BENEFICIARIES ASS ESSMENT OF SOCIAL INVEST ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 50,000.00 32,629.20 Completed 2019-10-30 2019-10-30 2019-11-20 2019-12-09 2020-01-01 2019-11-26 2020-01-15 2019-12-17 2020-02-12 2019-12-18 2020-06-03 2020-07-24 MENT AND LOCAL DEVELOPM ing and Project Management cation Selection ENT PROJECT IMPACT Page 6 TCWA-01 / Assessment of CI VIL WORKS QUALITY, COST A ND MAINTENANCE of infrastr ASIF Institutional Strengthen Consultant Qualifi uctures rehabilitated in fram IBRD / 84830 Post Open - National 30,000.00 0.00 Canceled 2019-10-30 2019-10-30 2019-11-20 2019-12-09 2020-01-01 2020-01-15 2020-02-12 2020-05-06 ing and Project Management cation Selection es of the Component 1 of Social Investment and Local Development Project TS-09 / Technical Supervisio ASIF Institutional Strengthen Consultant Qualifi n of Reconstruction of the Dri IBRD / 84830 Post Open - National 5,860.00 6,622.88 Completed 2019-12-25 2019-12-23 2020-01-15 2019-12-24 2020-02-28 2020-02-05 2020-03-29 2020-02-24 2020-05-03 2020-02-25 2021-03-29 2021-06-10 ing and Project Management cation Selection nking Water Distributing Net work of Paravakar. TPD-33 / Design and Author' s Supervision for Reconstruct ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 20,870.00 14,178.31 Signed 2020-02-27 2020-03-05 2020-03-18 2020-03-11 2020-05-01 2020-04-06 2020-05-08 2020-04-20 2020-06-12 2020-04-21 2020-09-25 2020-12-25 ion of the second building of ing and Project Management cation Selection the Kindergarten N 11 in Van adzor, marz of Lori . TPD-34 / Design and Author' s Supervision for Constructio ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 12,620.00 0.00 Canceled 2020-02-27 2020-03-18 2020-05-01 2020-05-08 2020-06-12 2020-09-10 n of the potable water pipelin ing and Project Management cation Selection e of Khnatsakh, marz of Syun ik TEX-12 / Survey the technica ASIF Institutional Strengthen Consultant Qualifi l condition of the Kindergarte IBRD / 84830 Post Open - National 625.00 620.48 Completed 2020-02-27 2020-03-05 2020-03-19 2020-03-11 2020-05-02 2020-04-10 2020-06-01 2020-05-06 2020-07-06 2020-05-07 2021-01-02 2020-05-23 ing and Project Management cation Selection n N 11 in Vanadzor, marz of Lori . AUD-19 / AUDIT OF THE ARM ENIAN TERRITORIAL DEVELO PMENT FUND and AUDIT OF T ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 30,918.00 23,973.29 Completed 2020-03-10 2020-03-04 2020-03-15 2020-03-18 2020-04-19 2020-04-10 2020-05-10 2020-05-05 2020-05-29 2020-05-07 2020-09-06 2020-07-29 HE SOCIAL INVESTMENT AND ing and Project Management cation Selection LOCAL DEVELOPMENT (SILD) PROJECT FOR THE YEAR END ED DECEMBER 31, 2019 TS-10 / Technical supervisio ASIF Institutional Strengthen Consultant Qualifi n for Construction of the kind IBRD / 84830 Post Open - National 6,280.00 7,277.72 Completed 2020-04-07 2020-04-01 2020-04-28 2020-04-23 2020-06-11 2020-05-15 2020-07-11 2020-05-21 2020-08-15 2020-05-27 2021-09-09 2021-05-13 ing and Project Management cation Selection ergarten after "Saint Mariam " in Gyumri. TCWA-02 / Assessment of Ci vil Works Quality, Cost and M aintenance of Infrastructures ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 30,000.00 34,292.85 Completed 2020-05-04 2020-07-10 2020-05-25 2020-08-04 2020-07-06 2020-08-31 2020-07-20 2020-11-13 2020-08-17 2020-11-14 2020-11-09 2021-08-21 Rehabilitated in Frames of Co ing and Project Management cation Selection mponent 1 of Social Investm ent and Local Development P roject TPD-35 / Modification and sit ing of Design, Author's Super ASIF Institutional Strengthen Consultant Qualifi vision for construction of the IBRD / 84830 Post Open - National 17,775.00 16,832.17 Signed 2020-06-24 2020-06-18 2020-07-24 2020-06-22 2020-09-06 2020-07-27 2020-09-13 2020-08-07 2020-10-18 2020-08-14 2021-10-18 2021-03-21 ing and Project Management cation Selection Horom community and Gyum ri community "Zangak" kinde rgartens, marz of Shirak. TPD-36 / Design and Author' s Supervision for the Reconst ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 19,735.00 18,647.11 Signed 2020-07-10 2020-07-06 2020-08-09 2020-07-21 2020-09-22 2020-08-14 2020-09-29 2020-09-01 2020-11-03 2020-09-04 2021-10-04 2021-04-01 ruction of Panik community k ing and Project Management cation Selection indergarten, marz of Shirak. TEX-13 / Survey the technica l condition for the Reconstruc ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 735.00 699.59 Completed 2020-06-24 2020-06-18 2020-07-24 2020-06-22 2020-09-06 2020-07-27 2020-10-06 2020-08-08 2020-11-10 2020-08-11 2020-11-25 2020-09-04 tion of Panik community kind ing and Project Management cation Selection ergarten, marz of Shirak. TPD-37 / Design and author’ s supervision of Construction and repair of irrigation syste m in Byureghavan enlarged c ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 40,850.00 40,204.35 Signed 2020-08-10 2020-08-04 2020-08-31 2020-09-02 2020-10-14 2020-09-29 2020-11-13 2020-10-12 2020-12-18 2020-10-18 2021-12-18 2021-05-01 ommunity and of Constructi ing and Project Management cation Selection on and repair of gravity irriga tion system in Hoghmik, Gog hovit and Torosgyugh settle ments included in Sarapat co mmunity. TEX-14 / Expertise of Archite ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 7,720.00 6,998.00 Completed 2020-10-26 2020-10-19 2020-11-16 2020-11-04 2020-12-30 2020-11-26 2021-01-29 2020-12-11 2021-03-05 2020-12-17 2022-03-05 2022-05-04 ctural Design (8 micro-projec ing and Project Management cation Selection ts). TS-11 / Technical supervisio Support to Socio-Economic Consultant Qualifi n of "Construction of the dri IBRD / 84830 Development and Capacity Post Open - National 3,100.00 4,081.83 Signed 2021-03-11 2021-03-11 2021-03-25 2021-04-02 2021-04-22 2021-05-10 2021-05-06 2021-07-01 2021-05-25 2021-07-02 2021-05-30 cation Selection nking water pipeline in Khnat Building at the Local Level sakh" TPD-39 / Design and author’ Support to Intercommunity S Consultant Qualifi s supervision of Construction IBRD / 84830 ocial and Economic Develop Post Open - National 8,000.00 8,331.49 Signed 2021-03-12 2021-03-11 2021-03-26 2021-03-12 2021-04-23 2021-04-09 2021-05-07 2021-07-06 2021-05-17 2021-07-07 2022-03-13 2021-11-10 cation Selection of a car park in Akunk comm ment Initiatives unity TS-12 / Technical supervisio Support to Socio-Economic n of "Reconstruction of the s Consultant Qualifi IBRD / 84830 Development and Capacity Post Open - National 5,700.00 6,918.81 Signed 2021-03-24 2021-03-18 2021-04-14 2021-04-09 2021-05-12 2021-04-30 2021-05-19 2021-05-21 2021-06-07 2021-05-25 2022-05-03 econd building of kindergarte cation Selection Building at the Local Level n No. 11 in Vanadzor" AUD-20 / "AUDIT OF THE AR MENIAN TERRITORIAL DEVEL OPMENT FUND and AUDIT OF ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 42,000.00 58,612.64 Completed 2021-03-29 2021-03-22 2021-04-12 2021-04-01 2021-05-10 2021-04-30 2021-05-15 2021-05-14 2021-05-25 2021-05-15 2021-07-09 2021-08-05 THE SOCIAL INVESTMENT AN ing and Project Management cation Selection D LOCAL DEVELOPMENT (SIL D) PROJECT FOR THE YEAR E NDED DECEMBER 31, 2020" TS-13 / Technical Supervisio n of 3 projects: "Constructio Support to Socio-Economic n of kindergarten of Horom", Consultant Qualifi IBRD / 84830 Development and Capacity Post Open - National 18,000.00 18,459.55 Signed 2021-05-13 2021-05-07 2021-06-03 2021-05-24 2021-07-01 2021-06-15 2021-07-08 2021-07-01 2021-07-27 2021-07-05 2022-07-22 ""Zangak" kindergarten cons cation Selection Building at the Local Level truction of Gyumri", "Reconst ruction of the kindergarten of Panik" TS-14 / Technical supervisio n of "Construction and repair Support to Intercommunity S Consultant Qualifi of a gravity irrigation system IBRD / 84830 ocial and Economic Develop Post Open - National 4,400.00 0.00 Canceled 2021-05-13 2021-05-07 2021-06-03 2021-07-01 2021-07-08 2021-07-27 2022-02-22 cation Selection in Hoghmik, Goghovit, and T ment Initiatives orosgyugh settlements of Sar apat community" TS-15 / Technical supervisio n of "W-29, Construction and repair of a gravity irrigation s Support to Intercommunity S ystem in Hoghmik, Goghovit, Consultant Qualifi IBRD / 84830 ocial and Economic Develop Post Open - National 12,100.00 12,243.75 Signed 2021-07-05 2021-06-21 2021-07-26 2021-07-08 2021-08-23 2021-08-06 2021-08-30 2021-08-31 2021-09-18 2021-09-01 2022-07-15 and Torosgyugh settlements cation Selection ment Initiatives of Sarapat community, W-27 , Construction and repair of ir rigation system in Byureghav an enlarged community" Page 7 AFT-TS-01 / Technical super vision of three projects: Cons truction of the pumping stati Support to Socio-Economic on and drinking water supply Consultant Qualifi IBRD / 90600 Development and Capacity Post Open - National 13,100.00 13,370.34 Signed 2021-07-05 2021-06-21 2021-07-26 2021-07-16 2021-08-23 2021-08-20 2021-08-30 2021-09-02 2021-09-18 2021-09-03 2022-08-14 pipeline, major renovation of cation Selection Building at the Local Level the DRRs and reconstruction of the distribution network of Archis, Lchkadzor and Movse s of Tavush region TPD-40 / Design and author’ Support to Intercommunity S s supervision of Construction Consultant Qualifi IBRD / 84830 ocial and Economic Develop Post Open - National 7,600.00 7,250.51 Signed 2021-07-16 2021-06-21 2021-08-06 2021-07-14 2021-09-19 2021-07-29 2021-10-19 2021-08-13 2021-11-23 2021-08-22 2022-11-18 2021-11-15 of the parking area in Gegha cation Selection ment Initiatives masar community AFT-PD-01 / Designing and a uthor’s supervision of the Re Support to Socio-Economic Consultant Qualifi construction of the communit IBRD / 90600 Development and Capacity Post Open - National 7,680.00 0.00 Canceled 2021-08-13 2021-08-12 2021-08-20 2021-10-03 2021-11-02 2021-11-12 2022-09-23 cation Selection y center by constructing the Building at the Local Level second floor in Lori-Berd, ma rz of Lori. AFT-PD-04 / Design and auth or’s supervision of the Constr Support to Socio-Economic Consultant Qualifi uction of external water pipel IBRD / 90600 Development and Capacity Post Open - National 24,700.00 23,952.12 Signed 2021-09-07 2021-09-02 2021-09-21 2021-09-09 2021-11-04 2021-10-05 2021-12-04 2021-10-12 2022-01-08 2021-10-14 2023-07-02 cation Selection ine and capping in the comm Building at the Local Level unity of Getahovit of Tavush region. TPD-41 / Design and author’ s supervision of reconstructio Support to Intercommunity S Consultant Qualifi n of the irrigation system in c IBRD / 84830 ocial and Economic Develop Post Open - National 18,980.00 17,116.62 Signed 2021-09-09 2021-09-28 2021-09-30 2021-09-28 2021-11-13 2021-10-22 2021-12-13 2021-10-29 2022-01-17 2021-11-03 2022-12-23 cation Selection onsolidated community in A ment Initiatives masia, marz of Shirak. AFT-PD-05 / Design and auth Support to Socio-Economic or’s supervision of the Constr Consultant Qualifi IBRD / 90600 Development and Capacity Post Open - National 28,000.00 24,163.66 Signed 2021-10-22 2021-09-30 2021-11-12 2021-10-01 2021-12-10 2021-10-22 2021-12-24 2021-11-10 2022-01-03 2021-11-16 2023-08-16 uction of the Alagyaz Commu cation Selection Building at the Local Level nity Center of region Aragats otn AFT-PD-01/1 / Designing and author’s supervision of the R Support to Socio-Economic Consultant Qualifi econstruction of the commun IBRD / 90600 Development and Capacity Post Open - National 10,960.00 10,607.96 Signed 2021-11-15 2021-11-09 2021-12-06 2021-12-01 2022-01-03 2021-12-30 2022-01-17 2022-01-19 2022-01-27 2022-01-27 2022-12-23 cation Selection ity center by constructing the Building at the Local Level second floor in Lori-Berd, ma rz of Lori. AFT-EX-01 / Reviewing and E valuation of the technical st Support to Socio-Economic ate of the Building of reconst Consultant Qualifi IBRD / 90600 Development and Capacity Post Open - National 1,330.00 1,265.20 Signed 2021-12-10 2021-12-30 2021-12-31 2022-01-27 2022-02-06 2022-02-25 2022-02-27 2022-03-16 2022-03-13 2022-03-17 2022-04-02 ruction of the kindergarten in cation Selection Building at the Local Level Ushi and renovation of the ki ndergarten in Khashtarak, m arz of Aragatsotn. AFT-PD-06 / Design and auth or’s supervision of the Recon Support to Socio-Economic Consultant Qualifi struction of the kindergarten IBRD / 90600 Development and Capacity Post Open - National 42,060.00 40,717.20 Signed 2021-12-14 2021-12-21 2021-12-28 2021-12-28 2022-02-10 2022-02-02 2022-03-03 2022-03-01 2022-03-13 2022-03-02 2023-08-05 cation Selection in Ushi and Renovation of the Building at the Local Level kindergarten in Khashtarak, marz of Aragatsotn. AFT-PD-07 / Design and auth Support to Socio-Economic or’s supervision of the Constr Consultant Qualifi IBRD / 90600 Development and Capacity Post Open - National 36,700.00 38,654.85 Signed 2022-02-22 2022-02-24 2022-02-23 2022-02-28 2022-04-08 2022-03-28 2022-05-08 2022-04-21 2022-06-05 2022-04-22 2022-11-17 uction of the kindergarten in cation Selection Building at the Local Level Nor Kyanq, marz of Shirak. AFT-EX-02 / Expertise of Arc Support to Socio-Economic Consultant Qualifi hitectural Design (10 project IBRD / 90600 Development and Capacity Post Open - National 16,090.00 16,499.77 Signed 2022-02-23 2022-03-10 2022-03-16 2022-03-25 2022-04-22 2022-04-28 2022-05-13 2022-05-12 2022-05-27 2022-05-13 2023-05-27 cation Selection s). Building at the Local Level TS-16 / "Construction of park Support to Intercommunity S ing lots in the enlarged com Consultant Qualifi IBRD / 84830 ocial and Economic Develop Post Open - National 5,800.00 0.00 Canceled 2022-04-11 2022-05-02 2022-05-30 2022-06-06 2022-06-25 2022-11-22 munities of Akunk, Kotayk m cation Selection ment Initiatives arz and Geghamasar, Geghar kunik marz of RA" AFT-PD-08 / Design and auth Support to Socio-Economic or’s supervision of the Constr Consultant Qualifi IBRD / 90600 Development and Capacity Post Open - National 4,930.00 0.00 Canceled 2022-05-03 2022-04-27 2022-05-17 2022-05-27 2022-06-23 2022-07-23 2022-08-13 2022-10-27 uction of the sports area of t cation Selection Building at the Local Level he school in Myasnikyan Villa ge, marz of Armavir. AFT-TS-02 / Technical super vision of "Renovation of the wrestling hall located in the Support to Socio-Economic Consultant Qualifi Culture House of Akunq com IBRD / 90600 Development and Capacity Post 5,000.00 0.00 Canceled 2022-05-03 2022-05-17 2022-06-14 2022-07-05 2022-07-26 2023-01-22 cation Selection mnunity, Gegharkunik marz Building at the Local Level of RoA", and "Construction of parking lots in Akunk, Kotayk marz of RoA". AFT-TS-02-1 / Technical sup ervision of "Renovation of th e wrestling hall located in the Support to Socio-Economic Culture House of Akunq com Consultant Qualifi IBRD / 84830 Development and Capacity Post Open - National 8,220.00 8,343.28 Signed 2022-06-21 2022-06-28 2022-07-05 2022-07-26 2022-08-11 2022-09-01 2022-09-01 2022-09-14 2022-09-15 2022-09-23 2023-03-14 munity", "Construction of a p cation Selection Building at the Local Level arking lot in Geghamasar co mmunity, Gegharkunik marz of RoA", "Construction of par king lots in Akunk, Kotayk m arz of RoA". AFT-PD-09 / Design and auth or’s supervision of the Constr uction of the kindergarden in Support to Socio-Economic Consultant Qualifi Under Implement Aknashen Village Araqs Com IBRD / 90600 Development and Capacity Post Open - National 34,500.00 0.00 2022-08-01 2022-09-05 2022-08-15 2022-09-12 2022-09-21 2022-10-13 2022-10-21 2022-11-17 2022-11-04 2023-04-03 cation Selection ation munity, marz of Aragacotn a Building at the Local Level nd of the Construction of the sports area of the school in M yasnikyan Village, marz of Ar mavir. AFT-PD-10 / Design and Auto Support to Socio-Economic r's supervision of Constructio Consultant Qualifi IBRD / 90600 Development and Capacity Post Open - National 45,500.00 0.00 Signed 2022-10-26 2022-10-25 2022-11-09 2022-11-15 2022-12-16 2022-12-20 2023-01-06 2023-05-18 2023-01-20 2024-03-15 n of the new physical educati cation Selection Building at the Local Level on school in Paraqar commu nity, marz of Armavir. AFT-TS-03 / Technical super Support to Socio-Economic Consultant Qualifi Under Implement vision of the civil works (3 pr IBRD / 84830 Development and Capacity Post Open - National 18,900.00 0.00 2022-10-26 2022-10-25 2022-11-09 2022-12-02 2022-12-16 2022-12-23 2023-01-06 2023-01-20 2024-03-15 cation Selection ation ojects). Building at the Local Level AFT-TS-04 / Technical super vision of the Reconstruction Support to Socio-Economic Consultant Qualifi Under Implement of the irrigation system in th IBRD / 84830 Development and Capacity Post Open - National 9,200.00 0.00 2022-10-26 2022-10-25 2022-11-09 2023-01-20 2022-12-16 2023-03-20 2023-01-06 2023-04-27 2023-01-20 2023-11-16 cation Selection ation e enlarged rural community Building at the Local Level of Amasia, Shirak Marz, RA. Page 8 AFT-TS-05 / Technical super vision of the Construction of Support to Socio-Economic Consultant Qualifi Under Implement external water line and sprin IBRD / 84830 Development and Capacity Post Open - National 10,600.00 0.00 2022-10-26 2022-10-25 2022-11-09 2022-11-01 2022-12-16 2023-01-30 2023-01-06 2023-03-06 2023-01-20 2024-05-14 cation Selection ation g connections of Getahovit c Building at the Local Level ommunity" of Tavush Region, RA. AFT-TS-06 / Technical super vision of the Construction of Support to Socio-Economic Consultant Qualifi Under Implement a Sewerage System and Bio-t IBRD / 84830 Development and Capacity Post Open - National 10,250.00 0.00 2023-02-08 2023-04-27 2023-02-22 2023-05-10 2023-03-31 2023-05-31 2023-04-21 2023-06-22 2023-05-05 2024-01-30 cation Selection ation reatment Facility in Nor Avan Building at the Local Level District of Yeghegnadzor City . AUD-22 / AUDIT OF THE SILD PROJECT FOR THE YEAR ENDI NG DECEMBER 31, 2022 (ALS O COVERING THE GRACE PER ASIF Institutional Strengthen Consultant Qualifi Under Implement IBRD / 84830 Post Open - National 20,000.00 0.00 2023-03-16 2023-03-16 2023-03-23 2023-03-22 2023-04-13 2023-04-10 2023-04-18 2023-04-28 2023-04-28 2023-12-24 IOD) and AUDIT OF THE ADDI ing and Project Management cation Selection ation TIONAL FINANCING FOR THE SILD PROJECT FOR THE PERI OD FROM DECEMBER 8, 2020 TO DECEMBER 31, 2022. AFT-TS-07 / Technical super Support to Socio-Economic vision of the Construction of t Consultant Qualifi Under Implement IBRD / 84830 Development and Capacity Post Open - National 2,500.00 0.00 2023-06-07 2023-06-09 2023-06-14 2023-06-12 2023-07-12 2023-08-02 2023-08-16 2023-12-14 he Sports Ground of the Mya cation Selection ation Building at the Local Level snikyan Settlement School of Armavir Marz of RoA. AFT-TS-08 / Technical super Support to Socio-Economic vision of the renovation of th Consultant Qualifi Under Implement IBRD / 84830 Development and Capacity Post Open - National 8,200.00 0.00 2023-06-12 2023-06-12 2023-06-26 2023-06-20 2023-08-02 2023-08-23 2023-09-06 2024-06-02 e kindergarten in Khashtarak cation Selection ation Building at the Local Level settlement of Tavush marz of RoA. TPD -01 / Architectural Desig Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 51,254.80 Signed 2015-06-30 2015-06-30 cation Selection l tion, Renovation & Reconstru Building at the Local Level ction of Buildings TPD-05-1 / Author Supervisio Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 4,848.52 Signed 2015-07-30 2015-07-31 cation Selection l tion, Renovation& Reconstru Building at the Local Level ction of Buildings TEX-02 / Expertise of Archite Support to Socio-Economic Consultant Qualifi Open - Internationa ctural Design (12 micro-proje IBRD / 84830 Development and Capacity Prior 0.00 17,902.25 Signed 2015-07-08 2015-07-08 cation Selection l cts) Building at the Local Level TBD-04 / Architectural Desig Support to Socio-Economic n for Construction, Rehabilita Consultant Qualifi Open - Internationa IBRD / 84830 Development and Capacity Prior 0.00 31,145.69 Signed 2015-06-30 2015-06-30 tion, Renovation & Reconstru cation Selection l Building at the Local Level ction of Buildings (two micro- projects) TPD-02 / Architectural Desig Support to Socio-Economic n for Construction, Rehabilita Consultant Qualifi Open - Internationa IBRD / 84830 Development and Capacity Prior 0.00 18,929.73 Signed 2015-06-30 2015-06-30 tion, Renovation & Reconstru cation Selection l Building at the Local Level ction of Buildings (two micro- projects) TEX-01 / Expertise of buildin Support to Socio-Economic gs stability, ventilation, powe Consultant Qualifi Open - Internationa IBRD / 84830 Development and Capacity Prior 0.00 12,145.80 Signed 2015-06-30 2015-06-30 r and water supplies and drai cation Selection l Building at the Local Level nage systems (8 mictro-proje cts) TPD-03 / Architectural Desig Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 45,112.36 Signed 2015-06-30 2015-06-30 cation Selection l tion, Renovation & Reconstru Building at the Local Level ction of Buildings TPD-06-1 / Author Supervisio Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 3,877.33 Signed 2015-07-30 2015-07-31 cation Selection l tion, Renovation& Reconstru Building at the Local Level ction of Buildings TPD-02-1 / Author Supervisio Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 2,665.23 Signed 2015-07-30 2015-07-31 cation Selection l tion, Renovation& Reconstru Building at the Local Level ction of Buildings TPD-03-1 / Author Supervisio Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 4,623.95 Signed 2015-07-30 2015-07-31 cation Selection l tion, Renovation& Reconstru Building at the Local Level ction of Buildings TPD-04-1 / Author Supervisio Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 5,012.55 Canceled 2015-08-17 cation Selection l tion, Renovation& Reconstru Building at the Local Level ction of Buildings TPD 06 / Architectural Desig Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 27,397.79 Signed 2015-06-30 2015-06-30 cation Selection l tion, Renovation & Reconstru Building at the Local Level ction of Buildings TPD-05 / Architectural Desig Support to Socio-Economic n for Construction, Rehabilita Consultant Qualifi Open - Internationa IBRD / 84830 Development and Capacity Prior 0.00 36,498.39 Signed 2015-06-30 2015-06-30 tion, Renovation & Reconstru cation Selection l Building at the Local Level ction of Buildings (two micro- projects) TPD-01-1 / Author Supervisio Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 6,892.20 Signed 2015-07-30 2015-07-31 cation Selection l tion, Renovation& Reconstru Building at the Local Level ction of Buildings INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TPD-32 / Authors supervision for Renovation of the Kinderg ASIF Institutional Strengthen arden Area in Village Aghdzq IBRD / 84830 Post Direct Selection Direct 240.00 0.00 Canceled 2018-04-26 2018-04-20 2018-05-06 2018-04-20 2018-06-03 2018-08-07 ing and Project Management and Construction of the Exter nal Engineering Nets, Marz of Aragatsotn TIIC-01 / Selection of Estimat Support to Intercommunity S Individual Consult or for providing consulting se IBRD / 84830 ocial and Economic Develop Post Open 10,740.00 0.00 Canceled 2018-10-30 2018-10-23 2018-12-02 2018-12-09 2018-12-30 2020-08-21 ant Selection rvices ment Initiatives TPD-38/1 / Author's supervisi Support to Socio-Economic on of Construction of drinkin IBRD / 84830 Development and Capacity Post Direct Selection Direct 1,000.00 1,054.75 Signed 2021-02-17 2021-02-15 2021-02-27 2021-03-24 2021-03-10 2021-05-08 2021-10-06 g water pipeline for Khnatsak Building at the Local Level h Page 9 AFT-PD-02 / Author’s supervi sion of the Construction of th e pumping station and drinki Support to Socio-Economic ng water supply pipeline, re IBRD / 90600 Development and Capacity Post Direct Selection Direct 2,340.00 0.00 Canceled 2021-08-26 2021-08-26 2021-09-05 2021-10-19 2022-07-16 novation of the DRRs and rec Building at the Local Level onstruction of the distributio n network of Lchkadzor and Movses of Tavush region. AFT-PD-03 / Author’s supervi sion of the Construction of th e pumping station and drinki Support to Socio-Economic ng water supply pipeline, maj IBRD / 90600 Development and Capacity Post Direct Selection Direct 2,290.00 0.00 Canceled 2021-08-26 2021-08-26 2021-09-05 2021-10-19 2022-09-14 or renovation of the DRRs an Building at the Local Level d reconstruction of the distri bution network of Archis settl ement of Tavush Marz. AFT-PD-02/1 / Author’s super vision of the Construction of t he pumping station and drink Support to Socio-Economic ing water supply pipeline, re IBRD / 90600 Development and Capacity Post Direct Selection Direct 3,090.00 0.00 Canceled 2021-09-09 2021-09-02 2021-09-19 2021-09-03 2021-11-02 2022-09-28 novation of the DRRs and rec Building at the Local Level onstruction of the distributio n network of Archis and Movs es settlements of Tavush regi on. AFT-PD-03/1 / Author’s super vision of the Construction of t he pumping station and drink Support to Socio-Economic ing water supply pipeline, re IBRD / 90600 Development and Capacity Post Direct Selection Direct 1,510.00 1,543.46 Signed 2021-09-09 2021-09-02 2021-09-19 2021-09-03 2021-11-02 2021-10-22 2022-07-30 novation of the DRRs and rec Building at the Local Level onstruction of the distributio n network of Lchkadzor settle ment of Tavush region. Support to Intercommunity S AFT-IC-01 / Individual Consul Individual Consult Under Implement IBRD / 90600 ocial and Economic Develop Post Open - National 18,900.00 0.00 2022-10-06 2022-10-07 2022-11-08 2022-10-21 2022-11-15 2022-10-24 2022-12-06 2023-12-06 tant /Power Engineer ant Selection ation ment Initiatives AFT-PD-11/1 / Authors super vision of the Construction of Support to Socio-Economic Under Implement a Sewerage System and Bio-t IBRD / 84830 Development and Capacity Post Direct Selection Direct - National 4,100.00 0.00 2023-05-09 2023-05-15 2023-05-19 2023-05-18 2023-06-28 2024-03-24 ation reatment Facility in Nor Avan Building at the Local Level District of Yeghegnadzor City . AFT-PD-12/1 / Authors super vision of the "Renovation of t Support to Socio-Economic Under Implement he wrestling hall located in th IBRD / 84830 Development and Capacity Post Direct Selection Direct - National 500.00 0.00 2023-05-22 2023-05-17 2023-06-01 2023-05-18 2023-07-11 2023-11-08 ation e Culture House of Akunq co Building at the Local Level mmunity", Gegharkunik marz of RoA. Page 10 PROCUREMENT PLAN (Mandatory Requirements) Sustainable Enterprise project Project Implementation agency: Palli Karma-Sahayak Foundation (PKSF) Period covered by this Procurement Plan: Entire Project Period Preamble In accordance with paragraph 5.9 of the World Bank Procurement Regulations for IPF Borrowers, July 2016 revised November 2017 (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to record all procurement actions for the Project, including preparing, updating and clearing its Procurement Plan, and seeking and receiving the Bank’s review and No-objection to procurement actions as required. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents (SPDs) shall be used for goods, works and non- consulting services where international competition is required and for all consulting services, including their respective forms of contract. National Procurement Arrangements: In accordance with paragraph 5.3 of the World Bank Procurement Regulations, when approaching the national market, as agreed in the Procurement Plan, the country’s own procurement procedures may be used. These procurement procedures shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti- Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Act 2006 and the Public Procurement Rules 2008, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: i. Lottery in award of contracts shall not be allowed; ii. Bidders’ qualification[s]/experience requirement[s] shall be mandatory; iii. Bids shall not be rejected based on percentage above or below the estimated cost; iv. Model Bidding Documents agreed with the Bank shall be used for all national open competitive procurement; v. The eligibility of bidders shall be as defined under Section III of the World Bank Procurement Regulations for IPF Borrowers: accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. When the Borrower uses other national procurement arrangements (other than national open competitive procurement), such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), such arrangements shall be consistent with the above requirements. As per paragraph 5.4 of the Procurement Regulations, the “Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework” as attached to this document shall form part of the Model Bidding Documents. Leased Assets: Not Applicable. Procurement of Second Hand Goods: Not Applicable. Domestic preference: as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works) as follows: Goods: Applicable; Works: Not applicable. Hands-on Expanded Implementation Support (HEIS): Not Applicable. Bank’s Procurement Prior Review Thresholds: contracts at or above the thresholds set out in table 1 below are subject to the Bank’s procurement prior review. Table 1: Procurement Prior Review Thresholds (US$ millions) Type of High risk Substantial Moderate Low risk procurement risk risk Works (including 5 10 15 20 turnkey, supply & installation of plant and equipment, and PPP) Goods, information 1.5 2 4 6 technology and non-consulting services Consulting 0.5 1 2 4 services: firms Consulting 0.2 0.3 0.4 0.5 services: Individual Notes: 1. These thresholds apply to all procurement activities regardless of their procurement/selection methods. There is no automatic requirement to undertake prior review for direct selection for value less than these thresholds. Consultant services covers a range of services that are of an advisory or professional nature. 2. In addition to the provisions of Table 1 above, and irrespective of the contract value, the following procurement activities are subject to the Bank’s procurement prior review: (a) procurement processes involving contract negotiations, as described in Section VI, paragraphs 6.34-36, of the Procurement Regulations; (b) competitive dialogue; (c) sustainable procurement; (d) selection of probity assurance providers, as described in Section III, paragraph 3.3 of the Procurement Regulations; and (e) best and final offer. 3. The determination of whether a contract meets the procurement prior review threshold is based on the estimated value of the contract or the package -when the selection document contains more than one lot/slice- , including all taxes and duties payable under the contract. Bid/ Proposal Evaluation Committee: formation and alteration of the bid/proposal evaluation committee shall be subject to Bank’s no objection. Fraud and Corruption (F&C) Checklist: Fraud and Corruption (F&C) checklist, as developed and provided by the Bank, shall be properly filled in during the evaluation and be attached with the evaluation report in case of contracts following national competitive procurement and request for quotations. Attachment 1 Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Bangladesh : Sustainable Enterprise Project PLAN General Information Country: Bangladesh 2018-11-08 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163250 GPN Date: Project Name: Sustainable Enterprise Project Loan / Credit No: IDA / 62090 Palli Karma-Sahayak Foundation Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PKSF/SEP/G-04 / Procuremen Project Management, Comm Single Stage - One E t of data center with firewall, IDA / 62090 unication and Knowledge Ma Post Request for Bids Open - National 87,500.00 103,142.89 Completed 2018-12-23 2019-07-23 2018-12-28 2019-02-08 2019-08-20 2019-03-10 2019-10-21 2019-04-14 2019-11-26 2019-10-11 2020-09-02 nvelope WiFi system and related acce nagement and Monitoring & ssories Evaluation PKSF/SEP/G-02 / Procuremen Project Management, Comm t of Laptops/Desktop Comput unication and Knowledge Ma Single Stage - One E IDA / 62090 Post Request for Bids Open - National 78,750.00 0.00 Canceled 2018-10-30 2018-12-27 2018-11-06 2018-11-27 2019-01-21 2018-12-27 2019-02-07 2019-01-24 2019-03-25 ers, Tabs and Modems, Printe nagement and Monitoring & nvelope rs and related accessories Evaluation PKSF/SEP/G-03 / Procuremen Project Management, Comm Request for Quota Single Stage - One E t of Photocopy Machine and r IDA / 62090 unication and Knowledge Ma Post Limited 12,500.00 15,622.23 Completed 2018-11-20 2019-02-10 2019-01-01 2019-03-25 2019-02-15 2019-05-28 tions nvelope elated accessories nagement and Monitoring & Evaluation Project Management, Comm PKSF/SEP/G-06 / Procuremen Request for Quota Single Stage - One E IDA / 62090 unication and Knowledge Ma Post Limited 12,500.00 7,286.29 Completed 2018-11-10 2019-03-25 2019-01-05 2019-05-14 2019-02-04 2019-08-19 t of Furniture and fixtures tions nvelope nagement and Monitoring & Evaluation Project Management, Comm PKSF/SEP/G-01 / Procuremen Request for Quota Single Stage - One E IDA / 62090 unication and Knowledge Ma Post Limited 7,500.00 2,943.57 Completed 2018-11-06 2017-11-20 2019-01-01 2017-12-07 2019-01-31 2018-03-07 t of office equipment tions nvelope nagement and Monitoring & Evaluation PKSF/SEP/E-GP/G-02 / Procur Project Management, Comm ement of Laptop-Desktop Co unication and Knowledge Ma Single Stage - One E IDA / 62090 Post Request for Bids Open - National 78,750.00 83,851.12 Completed 2019-03-13 2019-03-07 2019-03-14 2019-04-04 2019-03-28 2019-06-03 2019-05-07 2019-07-01 2019-06-01 2019-08-30 2019-10-25 mputer, Tab & Modem, Printe nagement and Monitoring & nvelope r & Related Accessories. Evaluation PKSF/SEP/G-05 / Procuremen Project Management, Comm t of training equipment (Digit unication and Knowledge Ma Single Stage - One E IDA / 62090 Post Request for Bids Open - National 43,750.00 48,875.61 Completed 2020-02-02 2020-03-09 2020-02-09 2021-02-18 2020-03-10 2020-07-20 2020-04-13 2020-09-20 2020-05-18 2020-10-16 2020-11-15 2021-09-17 al board, camera, multimedia nagement and Monitoring & nvelope and related accessories) Evaluation Project Management, Comm PKSF/SEP/G-07 / Procuremen Request for Quota Single Stage - One E IDA / 62090 unication and Knowledge Ma Post Limited 12,500.00 6,988.53 Completed 2021-06-15 2021-06-13 2021-06-24 2021-07-04 2021-06-30 2021-10-13 t of Furniture and Fixture tions nvelope nagement and Monitoring & Evaluation PKSF/SEP/G-08 / Procuremen Project Management, Comm Single Stage - One E Under Imple t of equipment for distance le IDA / 62090 unication and Knowledge Ma Post Request for Bids Open - National 206,250.00 0.00 2022-03-20 2022-04-07 2022-03-27 2022-05-08 2022-05-12 2022-06-05 2022-07-10 2022-10-08 nvelope mentation arning and related accessori nagement and Monitoring & es Evaluation PKSF/SEP/G-09 / Procuremen Project Management, Comm t of Equipment (tab and othe unication and Knowledge Ma Single Stage - One E IDA / 62090 Post Request for Bids Open - National 162,500.00 80,077.35 Signed 2022-04-03 2022-04-27 2022-04-10 2022-05-09 2022-05-22 2022-06-02 2022-06-19 2022-06-21 2022-07-24 2022-07-13 2022-10-22 r accessories) for results bas nagement and Monitoring & nvelope ed monitoring system develo Evaluation pment PKSF/SEP/G-10 / Procuremen t of Equipment (Laptop, TV S Enhancing Services and Ena Single Stage - One E Under Imple creen, Video Conference We IDA / 62090 Post Request for Bids Open - National 252,950.00 0.00 2022-12-29 2023-02-28 2023-01-05 2023-02-02 2023-03-02 2023-04-06 2023-07-05 bling Systems nvelope mentation bcam, and Portable Trolley S peaker- 64 sets) for Distance Learning System PKSF/SEP/G-11 / Procuremen Project Management, Comm t of Interactive flat panels, A unication and Knowledge Ma Single Stage - One E Under Imple IDA / 62090 Post Request for Bids Open - National 125,500.00 0.00 2023-01-05 2023-03-13 2023-01-12 2023-02-09 2023-03-09 2023-04-13 2023-07-12 ndroid 4K TV/ Digital display nagement and Monitoring & nvelope mentation boards, Laser Printers, and la Evaluation ptops for PKSF PKSF/SEP/G-12 / Supply and Project Management, Comm installation of data center eq unication and Knowledge Ma Single Stage - One E Pending Impl IDA / 62090 Post Request for Bids Open - National 302,000.00 0.00 2023-06-01 2023-06-08 2023-07-06 2023-08-17 2023-09-21 2024-01-19 uipment with accessories for nagement and Monitoring & nvelope ementation extension of PKSF Data Cent Evaluation er PKSF/SEP/G-13 / Lot-1: Suppl y and installation of Server, Data backup storage, and Ne twork devices with related ac Project Management, Comm cessories for PKSF Data Cent unication and Knowledge Ma Single Stage - One E Pending Impl IDA / 62090 Post Request for Bids Open - National 1,489,550.00 0.00 2023-06-04 2023-06-11 2023-07-09 2023-08-27 2023-10-01 2024-01-29 er (DC) & Disaster Recovery nagement and Monitoring & nvelope ementation Site (DRS) Evaluation Lot-2: Supply and installation of Security and Monitoring So ftware for PKSF DC & DRS NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PKSF/SEP/NS-01 / Procureme Project Management, Comm nt of co-location services wit unication and Knowledge Ma Pending Impl IDA / 62090 Post Direct Selection Direct - National 36,500.00 0.00 2023-08-01 2023-08-08 2023-10-03 2023-10-17 h fiber connectivity from Nati nagement and Monitoring & ementation onal Data Center (NDC) Evaluation CONSULTING FIRMS Page 1 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PKSF/SEP/S-07 / Selection of Project Management, Comm Consultant Qualifi Consultant for project web de IDA / 62090 unication and Knowledge Ma Post Limited 25,000.00 29,513.58 Signed 2018-11-25 2019-01-08 2018-12-09 2019-01-20 2019-01-08 2019-04-17 2019-02-12 2019-06-30 2023-06-30 cation Selection velopment nagement and Monitoring & Evaluation Project Management, Comm PKSF/SEP/S-6 / Selection of C Consultant Qualifi IDA / 62090 unication and Knowledge Ma Post Limited 172,500.00 0.00 Canceled 2022-12-01 2022-12-15 2023-01-12 2023-02-16 2023-05-27 onsultant for Final Evaluation cation Selection nagement and Monitoring & Evaluation PKSF/SEP/S-28 / Selection of Project Management, Comm Consultant Qualifi consultant for Fiduciary audit IDA / 62090 unication and Knowledge Ma Post Limited 8,000.00 0.00 Canceled 2021-04-05 2021-06-04 2021-07-04 2021-08-01 2021-11-29 cation Selection firm ( Y-3) nagement and Monitoring & Evaluation PKSF/SEP/S-18 / Selection of Project Management, Comm Consultant Qualifi Consultant for Awareness Bui IDA / 62090 unication and Knowledge Ma Post Limited 62,500.00 0.00 Canceled 2022-10-01 2022-11-30 2022-12-14 2023-01-11 2023-06-10 cation Selection lding Activities ( Phase-3 ) nagement and Monitoring & Evaluation PKSF/SEP/S-20 / Selection of Project Management, Comm Consultant for digital Trainin unication and Knowledge Ma Consultant Qualifi IDA / 62090 Post Limited 50,000.00 0.00 Canceled 2021-01-05 2021-03-07 2021-04-05 2021-05-03 2021-08-31 g Module development (Web nagement and Monitoring & cation Selection and mobile based apps) Phas Evaluation e-02 PKSF/SEP/S-29 / Selection of Project Management, Comm Consultant Qualifi consultant for Fiduciary audit IDA / 62090 unication and Knowledge Ma Post Limited 8,000.00 0.00 Canceled 2022-01-05 2022-03-06 2022-04-05 2022-05-03 2022-08-31 cation Selection firm ( Y-4) nagement and Monitoring & Evaluation PKSF/SEP/S-27 / Selection of Project Management, Comm Consultant Qualifi consultant for Fiduciary audit IDA / 62090 unication and Knowledge Ma Post Limited 8,000.00 0.00 Canceled 2021-04-20 2021-06-19 2021-07-19 2021-08-16 2021-11-14 cation Selection firm ( Y-2) nagement and Monitoring & Evaluation PKSF/SEP/S-30 / Selection of Project Management, Comm Consultant Qualifi consultant for Fiduciary audit IDA / 62090 unication and Knowledge Ma Post Limited 8,000.00 0.00 Canceled 2022-09-15 2022-11-14 2022-12-12 2023-01-09 2023-04-09 cation Selection firm ( Y-5) nagement and Monitoring & Evaluation PKSF/SEP/S-21 / Selection of Project Management, Comm Consultant for Digital Trainin unication and Knowledge Ma Consultant Qualifi IDA / 62090 Post Limited 25,000.00 0.00 Canceled 2022-10-20 2022-12-19 2023-01-16 2023-02-13 2023-06-13 g Module Development ( we nagement and Monitoring & cation Selection b and mobile based apps) ( P Evaluation hase -3 ) PKSF/SEP/S-19 / Selection of Project Management, Comm Consultant for Digital Trainin unication and Knowledge Ma Consultant Qualifi IDA / 62090 Post Limited 50,000.00 0.00 Canceled 2020-03-05 2020-03-19 2020-04-19 2020-05-25 2020-09-22 g Module Development (Web nagement and Monitoring & cation Selection and mobile based apps)- Pha Evaluation se-01 PKSF/SEP/S-26 / Selection of Project Management, Comm Consultant Qualifi consultant for Fiduciary audit IDA / 62090 unication and Knowledge Ma Post Limited 8,000.00 0.00 Canceled 2019-02-05 2019-02-19 2019-03-21 2019-04-25 2019-08-23 cation Selection firm ( Y-1) nagement and Monitoring & Evaluation PKSF/SEP/S-04 / Selection of Project Management, Comm Consultant Qualifi Consultant for Mid-term Revi IDA / 62090 unication and Knowledge Ma Post Limited 110,000.00 93,755.54 Completed 2020-02-20 2020-07-29 2020-11-15 2020-11-03 2020-12-16 2020-12-28 2021-01-20 2021-01-15 2021-07-21 2022-07-19 cation Selection ew (Phase-01) nagement and Monitoring & Evaluation PKSF/SEP/S-5 / Selection of C Project Management, Comm Consultant Qualifi onsultant for Mid-term Revie IDA / 62090 unication and Knowledge Ma Post Limited 110,000.00 0.00 Canceled 2021-04-01 2021-05-31 2021-06-30 2021-07-28 2021-09-26 cation Selection w (Phase-2) nagement and Monitoring & Evaluation PKSF/SEP/S-22 / Selection of Project Management, Comm Consultant Qualifi Consultant for Digital RBM ( IDA / 62090 unication and Knowledge Ma Post Limited 75,000.00 66,041.64 Signed 2020-01-15 2020-08-10 2020-11-26 2021-01-20 2020-12-25 2021-04-13 2021-01-22 2021-05-23 2021-05-22 cation Selection Web and mobile apps based nagement and Monitoring & RBM) Evaluation PKSF/SEP/S-19 (1) / Develop Project Management, Comm a Digital Training Module (W unication and Knowledge Ma Consultant Qualifi IDA / 62090 Post Limited 125,000.00 0.00 Canceled 2020-11-15 2020-11-29 2020-12-29 2021-02-02 2021-08-01 eb and mobile based apps) f nagement and Monitoring & cation Selection or establish a online based tr Evaluation aining platform PKSF/SEP/S-19(R) / Develop Project Management, Comm a Digital Training Module (We unication and Knowledge Ma Quality And Cost- IDA / 62090 Post Open - National 125,000.00 74,145.35 Signed 2021-01-24 2020-10-14 2021-02-07 2021-04-06 2021-03-23 2021-10-05 2021-04-20 2021-11-04 2021-05-20 2022-02-02 2021-06-24 2022-03-20 2021-08-05 2022-05-30 2022-02-01 b and mobile-based apps) to nagement and Monitoring & Based Selection establish an online-based trai Evaluation ning platform PKSF/SEP/S-05(R) / Selection Project Management, Comm Quality And Cost- of Consultant for Mid-term Re IDA / 62090 unication and Knowledge Ma Post Open - National 110,000.00 0.00 Canceled 2021-04-01 2021-04-22 2021-06-05 2021-07-03 2021-08-02 2021-09-06 2021-10-11 2022-04-09 Based Selection view (Phase-2) nagement and Monitoring & Evaluation PKSF/SEP/S-14.7(R) / Selecti Project Management, Comm Quality And Cost- Under Implement on of consulting firm for studi IDA / 62090 unication and Knowledge Ma Post Open - National 62,500.00 0.00 2021-10-14 2021-10-31 2021-11-04 2022-02-10 2021-12-18 2022-05-18 2022-01-15 2022-06-30 2022-02-14 2022-03-21 2022-04-25 2023-04-25 Based Selection ation es on Enterprise Developmen nagement and Monitoring & t Evaluation PKSF/SEP/S-14.8(R) / Selecti Project Management, Comm Quality And Cost- Under Implement on of Consulting firm for stud IDA / 62090 unication and Knowledge Ma Post Open - National 43,750.00 0.00 2021-10-14 2021-10-31 2021-11-04 2022-02-11 2021-12-18 2022-04-25 2022-01-15 2022-06-30 2022-02-14 2022-03-21 2022-04-25 2023-04-25 Based Selection ation ies on MEs Risk Assessment nagement and Monitoring & Evaluation PKSF/SEP/S-12 / Selection of Project Management, Comm Quality And Cost- Consultant for Making Docu IDA / 62090 unication and Knowledge Ma Post Open - National 125,000.00 0.00 Canceled 2022-07-24 2022-08-14 2022-09-18 2022-10-16 2022-11-06 2022-12-04 2023-01-01 2023-06-30 Based Selection mentary ( Phase -2 ) nagement and Monitoring & Evaluation PKSF/SEP/S-16 / Selection of Project Management, Comm Quality And Cost- Consultant for awareness bui IDA / 62090 unication and Knowledge Ma Post Open - National 62,500.00 0.00 Canceled 2021-12-26 2022-01-16 2022-02-27 2022-03-27 2022-04-24 2022-05-29 2022-07-03 2022-12-30 Based Selection lding activities (Phase-01) nagement and Monitoring & Evaluation PKSF/SEP/S-17 / Selection of Project Management, Comm Quality And Cost- Consultant for Awareness Bui IDA / 62090 unication and Knowledge Ma Post Open - National 62,500.00 0.00 Canceled 2022-04-24 2022-05-15 2022-06-19 2022-07-17 2022-08-07 2022-09-04 2022-10-09 2023-06-30 Based Selection lding Activities ( Phase-2 ) nagement and Monitoring & Evaluation PKSF/SEP/S-24 / Selection of Project Management, Comm Consultant for media campai unication and Knowledge Ma Quality And Cost- IDA / 62090 Post Open - National 75,000.00 0.00 Canceled 2021-12-28 2022-01-18 2022-02-22 2022-03-22 2022-04-12 2022-05-10 2022-06-14 2023-06-14 gn (tools development, clips nagement and Monitoring & Based Selection & teaser development etc.) P Evaluation hase-01 PKSF/SEP/S-25 / Selection of Project Management, Comm Consultant for Media Campai unication and Knowledge Ma Quality And Cost- IDA / 62090 Post Open - National 50,000.00 0.00 Canceled 2022-07-03 2022-07-24 2022-08-28 2022-09-25 2022-10-16 2022-11-13 2022-12-18 2023-06-30 gn ( tools development clips, nagement and Monitoring & Based Selection teaser etc. ) ( Phase-2) Evaluation PKSF/SEP/S-08 / Selection of Project Management, Comm consultant for development o unication and Knowledge Ma Quality And Cost- Under Implement IDA / 62090 Post Open - National 375,000.00 0.00 2021-10-14 2021-12-01 2021-11-04 2021-12-18 2022-05-08 2022-01-15 2022-06-20 2022-02-14 2022-03-21 2022-04-25 2023-04-25 f marketing and branding str nagement and Monitoring & Based Selection ation ategies for food processing S Evaluation ub-sector under SEP Page 2 PKSF/SEP/S-08.1 / Selection Project Management, Comm of consultant for developmen unication and Knowledge Ma Quality And Cost- Under Implement t of marketing and branding IDA / 62090 Post Open - National 187,500.00 0.00 2021-10-14 2021-12-01 2021-11-04 2021-12-18 2022-05-08 2022-01-15 2022-06-20 2022-02-14 2022-03-21 2022-04-25 2023-04-25 nagement and Monitoring & Based Selection ation strategies for mini textile and Evaluation Leather product subsectors u nder SEP PKSF/SEP/S-09 / Selection of Project Management, Comm consultant for the implement unication and Knowledge Ma Quality And Cost- Under Implement ation of marketing and brand IDA / 62090 Post Open - National 343,750.00 0.00 2022-03-20 2022-05-08 2022-04-10 2022-05-22 2022-07-03 2022-08-14 2022-09-18 2022-10-30 2023-06-27 nagement and Monitoring & Based Selection ation ing strategies for Crafts and Evaluation Electric Products sub-sectors under SEP PKSF/SEP/S-10 / Selection of Project Management, Comm consultant for the implement unication and Knowledge Ma Quality And Cost- Under Implement ation of marketing and brand IDA / 62090 Post Open - National 250,000.00 0.00 2022-03-20 2022-05-08 2022-04-10 2022-05-22 2022-07-03 2022-08-14 2022-09-18 2022-10-23 2023-06-20 nagement and Monitoring & Based Selection ation ing strategies for Agricultural Evaluation products sub-sectors under S EP PKSF/SEP/S-11 / Selection of Project Management, Comm consultant for awareness and unication and Knowledge Ma Quality And Cost- Under Implement IDA / 62090 Post Open - National 500,000.00 0.00 2021-12-26 2022-07-27 2022-01-16 2022-02-27 2022-03-27 2022-04-24 2022-05-29 2022-07-03 2022-12-30 media campaign activities an nagement and Monitoring & Based Selection ation d making Documentary unde Evaluation r SEP PKSF/SEP/S-23 / Selection of Project Management, Comm Consultant Qualifi Under Implement Consultant for GIS based sub IDA / 62090 unication and Knowledge Ma Post Limited 62,500.00 0.00 2022-04-03 2022-05-08 2022-06-02 2022-08-01 2022-06-30 2022-08-04 2023-05-31 cation Selection ation -sector trace-ability nagement and Monitoring & Evaluation PKSF/SEP/S-06(R) / Selection Project Management, Comm Quality And Cost- Under Implement of Consulting Firm for the Fin IDA / 62090 unication and Knowledge Ma Post Open - National 172,500.00 0.00 2023-02-12 2023-03-09 2023-03-05 2023-04-09 2023-05-07 2023-05-28 2023-07-02 2023-08-13 2024-02-09 Based Selection ation al Evaluation of SEP project nagement and Monitoring & Evaluation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Project Management, Comm PKSF/SEP/S-01 / Baseline Stu IDA / 62090 unication and Knowledge Ma Post Direct Selection Direct 45,000.00 38,126.09 Completed 2018-10-14 2017-08-20 2018-10-24 2017-08-20 2018-12-21 2017-09-07 2019-06-19 2018-03-20 dy ( Firm ) nagement and Monitoring & Evaluation Project Management, Comm PKSF/SEP/S-02 / Selection of Individual Consult IDA / 62090 unication and Knowledge Ma Post Limited 5,000.00 4,717.26 Signed 2018-10-14 2017-08-24 2018-10-19 2017-08-24 2018-11-09 2017-10-01 2018-12-14 2017-10-15 2019-06-12 Consultant - GIS ant Selection nagement and Monitoring & Evaluation PKSF/SEP/S-03 / Selection of Project Management, Comm Individual Consult Communication and Knowled IDA / 62090 unication and Knowledge Ma Post Limited 5,000.00 4,717.26 Completed 2018-10-14 2017-08-24 2018-10-19 2017-08-24 2018-11-09 2017-10-01 2018-12-14 2017-10-15 2019-06-12 2018-04-26 ant Selection ge Management ( C & KnM) S nagement and Monitoring & pecialist Evaluation PKSF/SEP/S-31 / Selection of Project Management, Comm Individual Consult Procurement Specialist (Cons IDA / 62090 unication and Knowledge Ma Post Limited 125,000.00 47,002.93 Terminated 2018-10-07 2018-07-19 2018-10-14 2019-07-21 2018-11-02 2018-09-13 2018-12-04 2018-10-11 2023-06-30 ant Selection ultant) nagement and Monitoring & Evaluation PKSF/SEP/S-13/2 / Selection Project Management, Comm Individual Consult of consultant for studies - Ve IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 17,510.65 Completed 2018-11-20 2019-01-24 2018-11-26 2019-02-20 2018-12-26 2019-06-20 2019-01-30 2019-06-27 2019-04-30 2020-10-01 ant Selection getables (Phase-01) nagement and Monitoring & Evaluation PKSF/SEP/S-13/3 / Selection Project Management, Comm Individual Consult of consultant for studies- Pisc IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 0.00 Canceled 2018-11-20 2019-01-24 2018-11-26 2018-12-26 2019-01-30 2019-04-30 ant Selection iculture and Fish Hatchery (P nagement and Monitoring & hase-01) Evaluation PKSF/SEP/S-13/4 / Selection Project Management, Comm Individual Consult of consultant for studies- Pou IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 0.00 Canceled 2018-11-20 2019-01-24 2018-11-26 2018-12-26 2019-01-30 2019-04-30 ant Selection ltry Firm (Phase-01) nagement and Monitoring & Evaluation PKSF/SEP/S-13/5 / Selection Project Management, Comm Individual Consult of consultant for studies- Frui IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 17,519.97 Completed 2018-11-20 2019-01-24 2018-11-26 2019-02-20 2018-12-26 2019-06-20 2019-01-30 2019-06-27 2019-04-30 2020-02-01 ant Selection ts (Phase-01) nagement and Monitoring & Evaluation PKSF/SEP/S-13/6 / Selection Project Management, Comm Individual Consult of consultant for studies- Min IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 0.00 Canceled 2018-11-20 2019-01-24 2018-11-26 2018-12-26 2019-01-30 2019-04-30 ant Selection i Garments, Looms and Hosie nagement and Monitoring & ry (Phase-01) Evaluation PKSF/SEP/S-13/7 / Selection Project Management, Comm Individual Consult of consultant for studies- Aut IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 0.00 Canceled 2018-11-20 2019-01-24 2018-11-26 2018-12-26 2019-01-30 2019-04-30 ant Selection omobile Workshop (Phase-01 nagement and Monitoring & ) Evaluation PKSF/SEP/S-13/8 / Selection Project Management, Comm Individual Consult of consultant for studies- Imit IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 0.00 Canceled 2018-11-20 2019-01-24 2018-11-26 2018-12-26 2019-01-30 2019-04-30 ant Selection ation Jewelry (Phase-01 nagement and Monitoring & Evaluation PKSF/SEP/S-13/9 / Selection Project Management, Comm Individual Consult of consultant for studies- Plas IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 17,638.35 Completed 2018-11-20 2019-01-24 2018-11-26 2019-02-20 2018-12-26 2019-06-20 2019-01-30 2019-06-27 2019-04-30 2020-09-13 ant Selection tic Factory (Phase-01) nagement and Monitoring & Evaluation PKSF/SEP/S-13/10 / Selection Project Management, Comm of consultant for studies- App unication and Knowledge Ma Individual Consult ropriate registration system IDA / 62090 Post Limited 18,750.00 17,460.78 Completed 2018-11-20 2019-02-20 2018-11-26 2019-02-20 2018-12-26 2019-06-20 2019-01-30 2019-06-27 2019-04-30 2020-08-12 nagement and Monitoring & ant Selection and product quality certificati Evaluation on for micro enterprise (Phas e-01) PKSF/SEP/S-13/1/1 / Selectio Project Management, Comm Individual Consult n of Consultant for Studies-B IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 17,634.18 Completed 2019-01-01 2019-02-20 2019-01-11 2019-02-20 2019-02-10 2019-06-20 2019-03-17 2019-06-27 2019-06-15 2020-04-01 ant Selection eef fattening and Dairy farm- nagement and Monitoring & ( Phase 1) Evaluation PKSF/SEP/S-13/1 / Selection Project Management, Comm Individual Consult of Consultant for studies - Da IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 17,571.79 Completed 2019-01-01 2019-02-20 2019-01-07 2019-02-20 2019-02-06 2019-06-20 2019-03-13 2019-06-28 2019-06-11 2020-03-16 ant Selection iry Product (Phase-01) nagement and Monitoring & Evaluation PKSF/SEP/S-13/3(R) / Selecti Project Management, Comm Individual Consult on of consultant for studies- IDA / 62090 unication and Knowledge Ma Post Open 18,750.00 17,100.07 Completed 2019-10-30 2019-10-31 2020-02-20 2020-09-17 2020-03-12 2020-09-22 2020-04-16 2020-10-16 2020-08-14 2022-01-18 ant Selection Pisciculture and Fish Hatcher nagement and Monitoring & y (Phase-01) Evaluation PKSF/SEP/S-13/8 (R) / Selecti Project Management, Comm Individual Consult on of consultant for studies- I IDA / 62090 unication and Knowledge Ma Post Open 18,750.00 16,534.78 Completed 2019-10-30 2019-10-31 2020-02-20 2020-08-26 2020-03-12 2020-08-31 2020-04-16 2020-09-28 2020-08-14 2022-06-06 ant Selection mitation Jewelry (Phase-01) nagement and Monitoring & Evaluation Page 3 PKSF/SEP/S-13/6 (R) / Selecti Project Management, Comm on of consultant for studies- unication and Knowledge Ma Individual Consult IDA / 62090 Post Open 18,750.00 15,920.75 Completed 2019-10-30 2019-08-19 2020-02-20 2020-07-08 2020-03-12 2020-07-13 2020-04-16 2020-09-01 2020-08-14 2022-04-01 Mini Garments, Looms and H nagement and Monitoring & ant Selection osiery (Phase-01) Evaluation PKSF/SEP/S-13/7(R) / Selecti Project Management, Comm Individual Consult on of consultant for studies- IDA / 62090 unication and Knowledge Ma Post Open 18,750.00 0.00 Canceled 2019-10-30 2020-02-20 2020-03-12 2020-04-16 2020-08-14 ant Selection Automobile Workshop (Phase nagement and Monitoring & -01) Evaluation PKSF/SEP/S-13/4(R) / Selecti Project Management, Comm Individual Consult on of consultant for studies- IDA / 62090 unication and Knowledge Ma Post Open 18,750.00 16,510.41 Completed 2020-01-27 2019-10-31 2020-02-20 2020-07-08 2020-03-12 2020-07-13 2020-04-16 2020-09-01 2020-08-14 2022-01-14 ant Selection Poultry Firm (Phase-01) nagement and Monitoring & Evaluation PKSF/SEP/S-32 / Selection of Project Management, Comm Individual Consult Food Technologist (Consultan IDA / 62090 unication and Knowledge Ma Post Limited 93,750.00 0.00 Canceled 2020-02-16 2020-02-23 2020-03-13 2020-04-19 2023-06-30 ant Selection t) nagement and Monitoring & Evaluation PKSF/SEP/S-33 / Selection of Project Management, Comm Individual Consult Textile and Fashion Specialis IDA / 62090 unication and Knowledge Ma Post Limited 93,750.00 0.00 Canceled 2020-02-16 2020-02-23 2020-03-13 2020-04-19 2023-06-30 ant Selection t (Consultant) nagement and Monitoring & Evaluation PKSF/SEP/S-34 / Selection of Project Management, Comm Individual Consult Light Engineering (Consultan IDA / 62090 unication and Knowledge Ma Post Limited 93,750.00 0.00 Canceled 2020-02-16 2020-02-23 2020-03-13 2020-04-17 2023-06-30 ant Selection t) nagement and Monitoring & Evaluation PKSF/SEP/S-14/1 / Selection Project Management, Comm Individual Consult of Consultant for studies on C IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 20,638.01 Completed 2020-02-16 2020-02-06 2020-02-23 2020-12-21 2020-03-15 2021-01-04 2020-04-19 2021-01-15 2020-10-16 2022-07-08 ant Selection ommunication Strategy nagement and Monitoring & Evaluation PKSF/SEP/S-35 / Selection of Project Management, Comm Individual Consult Specialist for Brand Develop IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 17,453.86 Completed 2020-02-16 2020-03-16 2020-02-23 2020-12-07 2020-03-15 2020-11-19 2020-04-19 2020-12-11 2020-10-16 2021-12-01 ant Selection ment Strategy (Consultant) nagement and Monitoring & Evaluation PKSF/SEP/S-14 / Selection of Project Management, Comm Individual Consult Consultant for Different Studi IDA / 62090 unication and Knowledge Ma Post Limited 131,250.00 0.00 Canceled 2020-07-05 2020-07-20 2020-08-10 2020-09-14 2020-12-13 ant Selection es ( Phase -2 ) nagement and Monitoring & Evaluation PKSF/SEP/S-14/2 / Selection Project Management, Comm Individual Consult of Consultant for studies on E IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 17,100.07 Completed 2020-02-16 2020-03-25 2020-02-23 2020-11-16 2020-03-15 2020-11-16 2020-04-19 2020-12-16 2020-10-16 2022-06-01 ant Selection co-Friendly Material and Tech nagement and Monitoring & nology Evaluation PKSF/SEP/S-14/3 / Selection Project Management, Comm Individual Consult of Consultant for studies on IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 16,332.25 Signed 2021-02-11 2021-01-13 2021-02-25 2021-06-30 2021-04-08 2021-11-10 2021-05-20 2021-12-13 2021-09-17 ant Selection Dry Fish Processing nagement and Monitoring & Evaluation PKSF/SEP/S-14/4 / Selection Project Management, Comm Individual Consult of Consultant for studies on E IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 16,667.64 Signed 2021-02-11 2021-02-23 2021-02-25 2021-06-30 2021-04-08 2021-11-16 2021-05-20 2021-12-20 2021-09-17 ant Selection cological Farming nagement and Monitoring & Evaluation PKSF/SEP/S-14/5 / Selection Project Management, Comm Individual Consult of Consultant for studies on IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 13,979.50 Signed 2021-02-11 2021-02-17 2021-02-25 2021-06-30 2021-04-08 2021-11-16 2021-05-20 2021-12-14 2021-09-17 ant Selection Machinery and Equipment nagement and Monitoring & Evaluation PKSF/SEP/S-14/6 / Selection Project Management, Comm Individual Consult of Consultant for studies on S IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 16,317.97 Signed 2021-02-11 2021-02-17 2021-02-25 2021-06-30 2021-04-08 2021-11-10 2021-05-20 2021-12-14 2021-09-17 ant Selection treet Food nagement and Monitoring & Evaluation PKSF/SEP/S-14/8 / Selection Project Management, Comm Individual Consult of Consultant for studies on IDA / 62090 unication and Knowledge Ma Post Limited 18,750.00 0.00 Canceled 2021-02-11 2021-02-23 2021-02-25 2021-04-08 2021-05-20 2021-09-17 ant Selection ME Risk Assessment nagement and Monitoring & Evaluation PKSF/SEP/S-14/7 / Selection Project Management, Comm Individual Consult of Consultant for studies on E IDA / 62090 unication and Knowledge Ma Post Limited 37,500.00 0.00 Canceled 2021-02-11 2021-02-23 2021-02-25 2021-04-08 2021-05-20 2021-09-17 ant Selection nterprise Development nagement and Monitoring & Evaluation PKSF/SEP/S-15.3 / Selection Project Management, Comm of consultant for conducting ‘ unication and Knowledge Ma Individual Consult A study on determining the s IDA / 62090 Post Limited 18,750.00 17,009.67 Signed 2021-11-14 2021-12-09 2021-12-14 2022-03-01 2022-01-04 2022-04-27 2022-02-08 2022-05-25 2022-06-08 nagement and Monitoring & ant Selection ub-sectors under service sect Evaluation or and scope of the activities of selected sub-sectors’ PKSF/SEP/S-15.4 / Selection Project Management, Comm of consultant for conducting unication and Knowledge Ma Individual Consult IDA / 62090 Post Limited 18,750.00 14,849.14 Signed 2022-05-29 2022-05-09 2022-06-28 2022-06-09 2022-07-19 2022-08-03 2022-08-30 2022-08-18 2022-11-28 study on OHS risk assessmen nagement and Monitoring & ant Selection t of Micro-Enterprise (ME) sec Evaluation tor PKSF/SEP/S-36 / Selection of Project Management, Comm individual consultant to assis unication and Knowledge Ma Individual Consult t, monitor and supervise the IDA / 62090 Post Open 50,000.00 0.00 Canceled 2022-03-31 2022-04-28 2022-05-19 2022-09-04 2022-05-26 2022-06-30 2023-06-30 nagement and Monitoring & ant Selection branding and marketing of pr Evaluation oducts and services of micro- enterprises (ME) under SEP PKSF/SEP/S-37 / Selection of consultant to assist, monitor, Project Management, Comm and supervise the implement unication and Knowledge Ma Individual Consult IDA / 62090 Post Open 50,000.00 0.00 Canceled 2022-03-24 2022-08-30 2022-05-19 2022-06-02 2022-06-30 2023-06-30 ation of awareness and medi nagement and Monitoring & ant Selection a campaign related activities Evaluation of the micro-enterprises (MEs ) under SEP PKSF/SEP/S-15.2 / Selection Project Management, Comm of consultant for documentat unication and Knowledge Ma Individual Consult Under Implement ion of the best practices and IDA / 62090 Post Open - National 18,750.00 0.00 2023-04-25 2023-04-26 2023-06-04 2023-06-18 2023-07-02 2023-12-29 nagement and Monitoring & ant Selection ation lessons learned in the Sustai Evaluation nable Enterprise Project (SEP ) PKSF/SEP/S-15.6 / Selection of consulting firm for determi Project Management, Comm ning appropriate service-char unication and Knowledge Ma Under Implement IDA / 62090 Post Direct Selection Direct - National 45,000.00 0.00 2023-04-25 2023-05-23 2023-05-09 2023-06-20 2023-09-18 ge rate and cost structure an nagement and Monitoring & ation alysis for the microenterprise Evaluation s, investment analysis, and s ustainability of microenterpri ses Page 4 Procurement Plan of Maputo Metropolitan Area Urban Mobility Project - Project Preparation Advance I. General Project information Country: Mozambique Project Name: Maputo Metropolitan Area Urban Mobility Project (P171048). Project Implementing Agencies: Ministry of Transport and Communication World Bank’s approval date for the procurement plan: February 15th, 2021 Date of General Procurement Notice: (after Board approval) Period covered by this procurement plan: Project Preparation Advance February 2021 to June 2022 II. Goods, Works and Non-Consulting Services Procurement Packages with Methods and Time Schedule Domesti Estimat Procurem World Expecte Ref. c Contract description ed Cost ent P-Q Bank d Bid No. Prefere (US$) Method Review Opening nce 1. GOODS Purchase of office Shopping/ 30/05/20 1 20,000 No No POST equipment: IT equipment RFQ 21 Purchase of office Shopping/ 30/05/20 2 40,000 No No POST equipment: furniture RFQ 21 TOTAL 60,000 III. Selection of Consultants Prior Review Threshold: Selection decisions subject to Prior Review by the World Bank, as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Contract amount Subject to Prior (US$ equivalent) Review Quality and Cost-Based Selection (QCBS) /Quality Based Above or equal to All above 1. Selection/Fixed Budget/Least 300,000 $500,000 Cost Consultant’s Qualifications 2. below 300,000 None (firms) 3. Single Source (SS) / Firms NA 4. Individual Consultants (IC) NA All above 1 $200,000 All ToRs regardless of the value of the contract are subject to IDA prior review. 1. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $200,000 equivalent per contract, may comprise entirely of national consultants in accordance with this procurement plan 2. Any Other Special Selection Arrangements: N/A Consultancy Assignments with Selection Methods and Time Schedule Estimat Revie Selecti Sour ed w by Expected on ce of No. Description of Assignment Cost the Proposal Metho fund World Submission USD d s Bank Feasibility study of integrated investments to improve Urban 2,000,00 01st August 1 Transport in the project specific area, QCBS YES WB 0 2021 preparation of detailed designs and bidding documents Hiring an Individual consultant to Development of PMUMM Environmental and Social 30th May 2 200,000 IC NO WB Instruments(ESMF, RPF, SEP and 2021 ESCP and other safeguard plans and instruments) Hiring a consulting firm to carry out 01st August 3 the EIA, EAS, ESMP, RAP and other 400,000 QCBS NO WB 2021 safeguard plans and instruments Hiring a consulting firm to conduct NO 30th May 4 Stakeholder Engagement Plan on 200,000 CQS WB 2021 urban transport (12 months) Hiring a consulting firm to conduct a study to increase private NO 30th May 5 participation opportunities in public 150,000 CQS WB 2021 transport and the role of FTC to attract funding (6 months) Hiring a consulting firm to support NO 01st July 6 the development of data capabilities 200,000 CQS WB 2021 in urban transport (12 months) Hiring a consultant to Support project NO 30th May 7 120,000 IC WB management (12 months) 2021 Hiring an engineer consultant to NO provide Technical Support to the 30th May 8 75,000 IC WB Project Preparation Unit during 2021 project preparation. (12 months) 2 Hiring an urban planner consultant to NO provide Technical Support to the 30th May 9 75,000 IC WB Steering Committee during project 2021 preparation (12 months) Hiring social safeguard officer NO consultants to provide Technical 30th May 10 Support to the Steering Committee 75,000 IC WB 2021 during project preparation. (12 months) Hiring environmental safeguard NO officer consultants to provide 30th May 11 Technical Support to the Steering 75,000 IC WB 2021 Committee during project preparation (12 months) Hiring consultant to do fiduciary NO 12 40,000 IC 01st July2021 WB support activities (PPSD) 3,610,0 Total 00 Training and Workshops No Description of Assignment Estimated Cost USD . 1 Individual Consultant to elaborate the Strategy for strengthen institutions in planning and management of 30,000 Urban Transport 2 Training on specific targeted courses 50,000 Total Cost 80,000 SUMMARY OF THE PLAN USD($) GOODS 60,000 CONSULTANCY 3,610,000 TRAINING & WORKSHOPS 80,000 OPERATING COST 100,000 TOTAL PROJECT PREPARATION ADVANCE COST 3,850,000 3 PROCUREMENT Mozambique : Maputo Metropolitan Area Urban Mobility Project PLAN General Information Country: Mozambique 2021-06-04 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175322 GPN Date: 2022-05-05 Project Name: Maputo Metropolitan Area Urban Mobility Project Loan / Credit No: IDA / V3740, / , IDA / E0660 Ministry of Transport and Communications Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Request for B Component 1: Urban Transp MZ-MTC-302049-CW-RFB / P ids - Small W ort Institutional and Regulat Single Stage - One E Under Imple 2023-05-0 roject office building rehabilit IDA / V3740 Post Request for Bids Open - National orks SPD (1 e 0.00 2022-07-17 2022-12-08 2022-07-22 2022-12-09 2022-09-02 2023-01-11 2022-10-02 2023-06-08 2022-11-06 ory Strengthening and Publi nvelope mentation 5 ation nvelope proc c Transport Industry Professi ess) onalization Request for B MZ-MTC-302043-CW-RFB / C Component 1: Urban Transp ids - Works ( onstruction of BRT Running w ort Institutional and Regulat after prequali ays, (including running way i Open - Internationa Single Stage - One E Pending Imp 2025-06-2 IDA / V3740 ory Strengthening and Publi Prior Request for Bids fication) SPD 0.00 2023-06-01 2023-08-17 2023-08-17 2023-06-06 2023-10-26 2023-11-25 2023-12-30 nfrastructure: junctions upgr l nvelope lementation 2 c Transport Industry Professi - Applying co ades in BRT corridor; parking onalization ntractor disq management in BRT corridor; ualificiation NMT in BRT corridor), Works 10/W/MMAUMP/22 / RAMBLA ” Pedestrian Streets Project: Request for B Pedestrianization of Rua de B Component 3: Comprehensi ids - Works ( agamoyo connecting Praça d ve Improvements for Safe A Single Stage - One E Pending Imp 2024-02-0 IDA / V3740 Post Request for Bids Open - National without preq 0.00 2022-10-17 2022-10-22 2022-12-03 2023-01-02 2023-02-06 a Independência, Praça 25 d ccess to Neighborhoods and nvelope lementation 5 ualification) e Junho and Praça dos Trabal Corridor Integration SPD hadores and construction of a wall protecting pedestrian zone. Request for B Component 3: Comprehensi 15/W/MMAUMP/22 / Paving o ids - Small W ve Improvements for Safe A Single Stage - One E Under Imple 2024-03-1 f 3 roads: Khongolote / Mulu IDA / V3740 Post Request for Bids Open - National orks SPD (1 e 0.00 2022-11-28 2023-03-28 2022-12-03 2023-03-28 2023-01-14 2023-05-10 2023-02-13 2023-03-20 ccess to Neighborhoods and nvelope mentation 8 mbela 2km nvelope proc Corridor Integration ess) Request for B Component 3: Comprehensi 13/W/MMAUMP/22 / Road Re ids - Small W ve Improvements for Safe A Single Stage - One E Under Imple 2024-03-1 habilitation: Bosquisso/Intaka IDA / V3740 Post Request for Bids Open - National orks SPD (1 e 0.00 2022-11-25 2023-03-28 2022-11-30 2023-03-28 2023-01-11 2023-05-10 2023-02-10 2023-03-17 ccess to Neighborhoods and nvelope mentation 7 , 8.7km nvelope proc Corridor Integration ess) Request for B Component 3: Comprehensi 14/W/MMAUMP/22 / Road Pa ids - Small W ve Improvements for Safe A Single Stage - One E Under Imple 2024-03-1 ving Matlemele - Matibjana IDA / V3740 Post Request for Bids Open - National orks SPD (1 e 0.00 2022-11-25 2023-03-28 2022-11-30 2023-03-28 2023-01-11 2023-05-10 2023-02-10 2023-03-17 ccess to Neighborhoods and nvelope mentation 7 5.5Km nvelope proc Corridor Integration ess) Request for B Component 3: Comprehensi 16/W/MMAUMP/22 / Landwor ids - Small W ve Improvements for Safe A Single Stage - One E Under Imple 2023-09-1 k and Construction of the DE IDA / V3740 Post Request for Bids Open - National orks SPD (1 e 0.00 2022-11-30 2023-03-28 2022-12-05 2023-03-28 2023-01-16 2023-04-28 2023-02-15 2023-03-22 ccess to Neighborhoods and nvelope mentation 8 POT fence nvelope proc Corridor Integration ess) 19/W/MMAUMP/23 / Rehabilit Request for B ation of Avenida 24 de Julho Component 3: Comprehensi ids - Small W between Praça 16 de Junho a ve Improvements for Safe A Single Stage - One E Under Imple 2025-07-2 IDA / V3740 Post Request for Bids Open - National orks SPD (1 e 0.00 2023-04-03 2023-04-06 2023-04-08 2023-04-06 2023-05-20 2023-05-09 2023-06-19 2023-07-24 nd Av. da Zambia, including ccess to Neighborhoods and nvelope mentation 4 nvelope proc Av. da Tânzania to Praça 21 Corridor Integration ess) de Outubro and the relocatio n of the Eduardo Statue / 3,2 km 20/W/MMAUMP/23 / Rehabilit Request for B Component 3: Comprehensi ation of Avenida da ONU and ids - Small W ve Improvements for Safe A Single Stage - One E Under Imple 2025-07-2 improvement of its interface IDA / V3740 Post Request for Bids Open - National orks SPD (1 e 0.00 2023-04-03 2023-04-06 2023-04-08 2023-04-06 2023-05-20 2023-05-09 2023-06-19 2023-07-24 ccess to Neighborhoods and nvelope mentation 4 with Avenidas Fernão de Mag nvelope proc Corridor Integration alhães and 25 de Setembro/A ess) v. of the Resorts 1,7km GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Urban Transp MZ-MTC-236275-GO-RFQ / P ort Institutional and Regulat Request for Quota Single Stage - One E urchase of office equipment: IDA / E0660 Post Limited 17,701.00 Signed 2021-06-25 2022-05-05 2021-08-20 2022-08-08 2022-02-16 ory Strengthening and Publi tions nvelope IT equipment c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-236305-GO-RFQ / P ort Institutional and Regulat Request for Quota Single Stage - One E urchase of office equipment: IDA / V3740 Post Limited 0.00 Signed 2021-06-25 2022-09-01 2021-08-20 2022-02-16 ory Strengthening and Publi tions nvelope Furniture c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301952-CW-RFB / B ort Institutional and Regulat Single Stage - One E Pending Impl IDA / V3740 Prior Request for Bids Open - National 0.00 2023-07-20 2023-07-25 2023-09-05 2023-10-05 2023-11-09 2024-05-07 RT Control Center ory Strengthening and Publi nvelope ementation c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301941-GO-RFB / Pr ort Institutional and Regulat Single Stage - One E ocurement of 9 vehicles for P IDA / V3740 Post Request for Bids Open - National 0.00 Signed 2022-07-20 2022-10-17 2022-07-25 2022-10-17 2022-09-05 2022-11-14 2022-10-05 2022-12-26 2022-11-09 2023-05-08 ory Strengthening and Publi nvelope CU/PTUs c Transport Industry Professi onalization 21/G/MMAUMP/23 / IT Equip Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl IDA / V3740 Post Limited 0.00 2023-04-25 2023-06-20 2023-12-17 ment's ement, Monitoring and Evalu tions nvelope ementation ation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Page 1 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-MTC-235079-CS-CQS / Hi Component 1: Urban Transp ring a consulting firm to cond ort Institutional and Regulat uct a study to increase privat Consultant Qualifi Open - Internationa IDA / V3740 ory Strengthening and Publi Post 0.00 Signed 2021-06-30 2021-08-24 2021-07-21 2021-09-13 2021-09-03 2022-01-03 2021-10-03 2022-10-13 2021-11-07 2022-05-06 e participation opportunities i cation Selection l c Transport Industry Professi n public transport and the rol onalization e of the transport and comm unications fund MZ-MTC-235098-CS-QCBS / Component 1: Urban Transp Feasibility study of integrate ort Institutional and Regulat d investiments to improve ur Quality And Cost- Open - Internationa IDA / V3740 ory Strengthening and Publi Prior 0.00 Canceled 2021-07-04 2021-08-11 2021-07-25 2021-08-16 2021-09-07 2021-11-25 2021-10-05 2022-01-10 2021-11-04 2022-02-28 2021-12-09 2022-01-13 2023-01-13 ban transport in the project s Based Selection l c Transport Industry Professi pecific area, preparation of d onalization etailed designs and bidding d ocuments Component 1: Urban Transp MZ-MTC-267066-CS-QCBS / ort Institutional and Regulat Quality And Cost- Open - Internationa Under Implement Strategic Environmental and IDA / V3740 Post 0.00 2021-12-08 2021-12-22 2021-12-29 2022-02-01 2022-02-11 2022-03-11 2022-04-10 2022-05-15 2022-06-19 2023-06-19 ory Strengthening and Publi Based Selection l ation Social Assessment (SESA) c Transport Industry Professi onalization MZ-MTC-235076-CS-CQS / Hi ring a consulting firm to cond Consultant Qualifi Open - Internationa / Post 0.00 Canceled 2021-06-20 2021-07-11 2021-08-24 2021-09-23 2021-10-28 2022-04-26 uct stakeholder engagement cation Selection l plan on urban transport MZ-MTC-235081-CS-CQS / Hi ring a consulting firm to supp Consultant Qualifi Open - Internationa / Post 0.00 Canceled 2021-06-15 2021-07-06 2021-08-19 2021-09-18 2021-10-23 2022-04-21 ort the development of data cation Selection l capabilities in urban transpor t MZ-MTC-235074-CS-QCBS / Component 1: Urban Transp Hiring a consulting firm to ca ort Institutional and Regulat Quality And Cost- Open - Internationa Pending Impleme IDA / V3740 Post 0.00 2022-05-10 2022-05-31 2022-07-14 2022-08-11 2022-09-10 2022-10-15 2022-11-19 2023-11-19 rry out the EIA, EAS, ESMP, R ory Strengthening and Publi Based Selection l ntation AP and other safeguard plans c Transport Industry Professi and instruments onalization MZ-MTC-300140-CS-QCBS / Component 1: Urban Transp Feasibility Study of Integrate ort Institutional and Regulat d Investments to Improve Ur Quality And Cost- Open - Internationa IDA / V3740 ory Strengthening and Publi Prior 0.00 Signed 2022-06-24 2022-06-29 2022-07-15 2022-08-28 2022-07-20 2022-09-25 2022-08-30 2022-10-25 2023-04-07 2022-11-29 2023-04-17 2023-01-03 2023-06-20 2024-01-03 ban Transport in the Project s Based Selection l c Transport Industry Professi pecific Areas, Preparation of onalization Detailed Designs and Bidding Documents MZ-MTC-301970-CS-QCBS / Component 1: Urban Transp Enhancement of the Instituti ort Institutional and Regulat Quality And Cost- Open - Internationa Pending Impleme IDA / V3740 Prior 0.00 2022-08-15 2022-09-05 2022-10-19 2022-11-16 2022-12-16 2023-01-20 2023-02-24 2024-02-24 onal Framework for Urban M ory Strengthening and Publi Based Selection l ntation obility in the Maputo Metropo c Transport Industry Professi litam Area onalization MZ-MTC-301977-CS-QCBS / Component 1: Urban Transp Enhancement of the regulato ort Institutional and Regulat Quality And Cost- Open - Internationa Pending Impleme IDA / V3740 Prior 0.00 2022-08-15 2022-09-05 2022-10-19 2022-11-16 2022-12-16 2023-01-20 2023-02-24 2024-02-24 ry framework of public transp ory Strengthening and Publi Based Selection l ntation ort c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-302017-CS-QCBS / ort Institutional and Regulat Quality And Cost- Open - Internationa Pending Impleme Development of Social Mana IDA / V3740 Prior 0.00 2022-09-15 2022-10-06 2022-11-19 2022-12-17 2023-01-16 2023-02-20 2023-03-27 2024-03-26 ory Strengthening and Publi Based Selection l ntation gement Plan c Transport Industry Professi onalization MZ-MTC-302024-CS-QCBS / Component 1: Urban Transp Preparation of pedestrian, cy ort Institutional and Regulat Quality And Cost- Open - Internationa Pending Impleme IDA / V3740 Prior 0.00 2023-01-05 2023-01-26 2023-03-11 2023-04-08 2023-05-08 2023-06-12 2023-07-17 2024-07-16 cling, mobility, and parking ory Strengthening and Publi Based Selection l ntation management plans c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-302030-CS-QCBS / ort Institutional and Regulat Quality And Cost- Open - Internationa Pending Impleme Development of traffic mana IDA / V3740 Prior 0.00 2022-12-01 2022-12-22 2023-02-04 2023-03-04 2023-04-03 2023-05-08 2023-06-12 2024-06-11 ory Strengthening and Publi Based Selection l ntation gement improvement plan c Transport Industry Professi onalization MZ-MTC-301984-CS-QCBS / Component 1: Urban Transp Assistance in developing and ort Institutional and Regulat Quality And Cost- Open - Internationa Pending Impleme IDA / V3740 Prior 0.00 2022-10-02 2022-10-23 2022-12-06 2023-01-03 2023-02-02 2023-03-09 2023-04-13 2024-04-12 implementing capacity buildi ory Strengthening and Publi Based Selection l ntation ng for public transport sector c Transport Industry Professi staff onalization Component 1: Urban Transp MZ-MTC-302035-CS-QCBS / ort Institutional and Regulat Quality And Cost- Open - Internationa Pending Impleme Supervision of BRT constructi IDA / V3740 Prior 0.00 2023-01-01 2023-01-22 2023-03-07 2023-04-04 2023-05-04 2023-06-08 2023-07-13 2024-07-12 ory Strengthening and Publi Based Selection l ntation on c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-303531-CS-LCS / Ex ort Institutional and Regulat Least Cost Selecti IDA / V3740 Post Open - National 0.00 Canceled 2022-10-01 2022-10-22 2022-12-05 2023-01-02 2023-02-01 2023-03-08 2023-04-12 2024-04-11 ternal Auditor ory Strengthening and Publi on c Transport Industry Professi onalization 04/CONS/MMAUMP/22 / Dev Component 1: Urban Transp elopment and implementatio ort Institutional and Regulat Quality And Cost- Open - Internationa Pending Impleme IDA / V3740 Prior 0.00 2022-10-10 2022-10-31 2022-12-14 2023-01-11 2023-02-10 2023-03-17 2023-04-21 2025-04-20 n of Young Professionals Prog ory Strengthening and Publi Based Selection l ntation ram in Urban Mobility c Transport Industry Professi onalization 05/CONS/MMAUMP/22 / Prep Component 1: Urban Transp aration and implementation ort Institutional and Regulat Quality And Cost- Open - Internationa Pending Impleme of a professionalization progr IDA / V3740 ory Strengthening and Publi Prior 0.00 2022-10-17 2022-11-07 2022-12-21 2023-01-18 2023-02-17 2023-03-24 2023-04-28 2024-04-27 Based Selection l ntation am of existing formal and inf c Transport Industry Professi ormal operators along the pr onalization oject corridor 11/CONS/MMAUMP/22 / Supe Component 3: Comprehensi rvision of road improvement ve Improvements for Safe A Quality And Cost- Open - Internationa Under Implement IDA / V3740 Prior 0.00 2022-09-26 2023-01-26 2022-10-17 2023-02-14 2022-11-30 2022-12-28 2023-01-27 2023-03-03 2023-04-07 2024-04-06 contracts in Maputo and Mat ccess to Neighborhoods and Based Selection l ation ola Municipalities (quick-win) Corridor Integration Component 3: Comprehensi 12/CONS/MMAUMP/22 / Supe ve Improvements for Safe A Quality Based Sel Under Implement rvision woks of the office buil IDA / V3740 Post Open - National 0.00 2022-09-30 2022-11-25 2022-10-21 2023-02-08 2022-12-04 2023-01-01 2023-01-31 2023-03-02 2023-04-06 2024-04-05 ccess to Neighborhoods and ection ation ding rehabilitation Corridor Integration 24/CONS/MMAUP/23 / Suppo Component 3: Comprehensi rt AMT to establish a compre ve Improvements for Safe A Quality And Cost- Open - Internationa Pending Impleme hensive data collection and IDA / V3740 Prior 0.00 2023-07-03 2023-07-24 2023-09-06 2023-10-04 2023-11-03 2023-12-08 2024-01-12 2025-01-11 ccess to Neighborhoods and Based Selection l ntation management system for urb Corridor Integration an mobility planning and tran sit management. Page 2 23/CONS/MMAUMP/23 / Recr Component 4: Project Manag Quality Based Sel uitment of Service Provider f IDA / V3740 ement, Monitoring and Evalu Post Open - National 0.00 Under Review 2023-06-01 2023-05-30 2023-06-22 2023-08-05 2023-09-02 2023-10-02 2023-11-01 2023-12-06 2025-12-05 ection or GBV/EAS/AS ation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-MTC-234889-CS-CQS / Hi Component 1: Urban Transp ring a consultant to develop ort Institutional and Regulat Individual Consult ment of PMUMM environment IDA / V3740 ory Strengthening and Publi Post Open 179,838.96 Signed 2021-06-15 2021-06-10 2021-08-03 2021-10-08 2021-08-24 2021-10-18 2021-09-28 2021-10-23 2022-03-27 ant Selection al and social instruments ( ES c Transport Industry Professi MF, RPF, SEP and ESCP and o onalization ther safeguard plans MZ-MTC-235033-CS-INDV / h Component 1: Urban Transp iring social safeguard officer ort Institutional and Regulat Individual Consult consultants to provide techni IDA / V3740 ory Strengthening and Publi Post Open 60,500.00 Signed 2021-06-15 2021-06-14 2021-08-03 2021-12-17 2021-08-24 2021-12-17 2021-09-28 2021-12-18 2022-03-27 ant Selection cal support to the steering co c Transport Industry Professi mmittee during project prepa onalization ration MZ-MTC-235071-CS-INDV / H Component 1: Urban Transp iring environmental safeguar ort Institutional and Regulat Individual Consult d officer consultants to provi IDA / V3740 ory Strengthening and Publi Post Open 60,500.00 Signed 2021-06-15 2021-06-14 2021-08-03 2021-12-03 2021-08-24 2022-01-05 2021-09-28 2022-01-22 2022-03-27 ant Selection de technical support to the st c Transport Industry Professi eering committee during proj onalization ect preparation MZ-MTC-235092-CS-INDV / H iring an engineer consultant t Individual Consult Under Implement o provide technical support t / Post Open 0.00 2021-06-20 2021-12-23 2021-08-08 2021-08-29 2021-10-03 2022-04-01 ant Selection ation o the project preparation unit during project preparation MZ-MTC-235096-CS-INDV / H iring an urban planner consul Individual Consult Under Implement tant to provide technical sup / Post Open 0.00 2021-06-30 2021-12-08 2021-08-18 2022-05-04 2021-09-08 2021-10-13 2022-04-11 ant Selection ation port to the steering committe e during project preparation MZ-MTC-235097-CS-INDV / H Component 1: Urban Transp iring a consultancy service f ort Institutional and Regulat Individual Consult IDA / V3740 Prior Open 29,843.75 Signed 2021-06-25 2021-08-24 2021-08-13 2021-12-13 2021-09-03 2022-01-10 2021-10-08 2022-01-27 2022-04-06 or the preparation of the pro ory Strengthening and Publi ant Selection curement Strategies ( PPSD) c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-267215-CS-INDV / P ort Institutional and Regulat Individual Consult IDA / V3740 Prior Open 90,000.00 Signed 2021-12-08 2021-12-23 2022-01-23 2022-06-17 2022-01-28 2022-07-11 2022-02-07 2022-07-05 2022-10-31 rocurement Specialist ory Strengthening and Publi ant Selection c Transport Industry Professi onalization MZ-MTC-275341-CS-INDV / I Component 1: Urban Transp ndividual Consultant to Elabo ort Institutional and Regulat Individual Consult rate the Strategy for Strengt IDA / V3740 ory Strengthening and Publi Post Open 0.00 Terminated 2022-01-31 2022-06-05 2022-03-21 2022-10-13 2022-04-11 2022-09-27 2022-05-16 2022-11-12 ant Selection hen Institutions in Planning a c Transport Industry Professi nd Management of Urban Tra onalization nsport Component 1: Urban Transp MZ-MTC-235091-CS-INDV / H ort Institutional and Regulat Individual Consult iring a consultant to support IDA / V3740 Post Open 0.00 Signed 2021-06-15 2022-06-24 2021-08-03 2022-11-08 2021-08-24 2022-11-29 2021-09-28 2022-03-27 ory Strengthening and Publi ant Selection project management c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-290333-CS-INDV / C ort Institutional and Regulat Individual Consult IDA / V3740 Post Open 0.00 Signed 2022-04-22 2022-06-06 2022-06-10 2022-10-21 2022-07-01 2022-11-14 2022-08-05 2023-02-01 ommunication Specialist ory Strengthening and Publi ant Selection c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-300286-CS-INDV / F ort Institutional and Regulat Individual Consult IDA / V3740 Post Open 0.00 Signed 2022-11-15 2022-06-24 2023-01-03 2022-10-11 2023-01-24 2022-10-20 2023-02-28 2023-08-27 inancial Manager ory Strengthening and Publi ant Selection c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-300485-CS-INDV / ort Institutional and Regulat Individual Consult Monitoring & Evaluation Spec IDA / V3740 Post Open 0.00 Signed 2022-11-10 2022-09-16 2022-12-29 2023-05-24 2023-01-19 2023-05-28 2023-02-23 2023-08-22 ory Strengthening and Publi ant Selection ialist c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-300489-CS-INDV / T ort Institutional and Regulat Individual Consult Under Implement IDA / V3740 Post Open 0.00 2022-11-15 2022-11-02 2023-01-03 2023-01-24 2023-02-28 2023-08-27 ransport Planner ory Strengthening and Publi ant Selection ation c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-300490-CS-INDV / A ort Institutional and Regulat Individual Consult IDA / V3740 Post Open 0.00 Signed 2022-11-15 2022-07-08 2023-01-03 2022-11-29 2023-01-24 2022-12-26 2023-02-28 2023-08-27 dministrative Assistant ory Strengthening and Publi ant Selection c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301020-CS-INDV / L ort Institutional and Regulat Individual Consult Under Implement IDA / V3740 Prior Open 0.00 2022-07-10 2022-12-07 2022-08-28 2022-09-18 2022-10-23 2023-04-21 awyer ory Strengthening and Publi ant Selection ation c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301642-CS-INDV / S ort Institutional and Regulat Individual Consult ocial and Resettlement Speci IDA / V3740 Post Open 0.00 Signed 2022-08-06 2022-07-08 2022-09-24 2022-11-29 2022-10-15 2022-12-14 2022-11-19 2023-05-18 ory Strengthening and Publi ant Selection alist c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301646-CS-INDV / E ort Institutional and Regulat Individual Consult IDA / V3740 Post Open 0.00 Signed 2022-08-06 2022-08-16 2022-09-24 2023-02-13 2022-10-15 2023-02-17 2022-11-19 2023-05-18 nvironmental Specialist ory Strengthening and Publi ant Selection c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301654-CS-INDV / H ort Institutional and Regulat Individual Consult Under Implement IDA / V3740 Post Open 0.00 2022-09-10 2022-08-05 2022-10-29 2022-11-19 2022-12-24 2023-06-22 ealth and Safety Specialist ory Strengthening and Publi ant Selection ation c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301697-CS-INDV / S ort Institutional and Regulat Individual Consult ocial and Resettlement Speci IDA / V3740 Post Open 0.00 Signed 2022-07-15 2022-07-08 2022-09-02 2022-11-29 2022-09-23 2022-12-15 2022-10-28 2023-04-26 ory Strengthening and Publi ant Selection alist (Matola) c Transport Industry Professi onalization Page 3 Component 1: Urban Transp MZ-MTC-301699-CS-INDV / E ort Institutional and Regulat Individual Consult Under Implement nvironmental, Health and Saf IDA / V3740 Post Open 0.00 2022-08-15 2023-03-06 2022-10-03 2022-10-24 2022-11-28 2023-05-27 ory Strengthening and Publi ant Selection ation ety Specialist c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301705-CS-INDV / ort Institutional and Regulat Individual Consult Gender Based Violence, Exp IDA / V3740 Post Open 0.00 Signed 2022-07-15 2022-07-08 2022-09-02 2023-03-29 2022-09-23 2023-04-06 2022-10-28 2023-04-26 ory Strengthening and Publi ant Selection ert c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301889-CS-INDV / C ort Institutional and Regulat Individual Consult Pending Impleme IDA / V3740 Post Open 0.00 2022-09-05 2022-10-24 2022-11-14 2022-12-19 2023-06-17 ontract Manager ory Strengthening and Publi ant Selection ntation c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301905-CS-INDV / C ort Institutional and Regulat Individual Consult Under Implement IDA / V3740 Post Open 0.00 2022-09-05 2023-06-22 2022-10-24 2022-11-14 2022-12-19 2023-06-17 apacity Building Specialist ory Strengthening and Publi ant Selection ation c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301909-CS-INDV / U ort Institutional and Regulat Individual Consult Under Implement IDA / V3740 Post Open 0.00 2022-09-05 2022-10-20 2022-10-24 2022-11-14 2022-12-19 2023-06-17 rban Transport Specialist ory Strengthening and Publi ant Selection ation c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301912-CS-INDV / S ort Institutional and Regulat Individual Consult Under Implement IDA / V3740 Post Open 0.00 2022-08-15 2022-08-01 2022-10-03 2022-10-24 2022-11-28 2023-05-27 enior Civil Engineer ory Strengthening and Publi ant Selection ation c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301927-CS-INDV / E ort Institutional and Regulat Individual Consult Pending Impleme IDA / V3740 Post Open 0.00 2022-08-05 2022-09-23 2022-10-14 2022-11-18 2023-05-17 lectronic Engineer ory Strengthening and Publi ant Selection ntation c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301932-CS-INDV / S ort Institutional and Regulat Individual Consult Under Implement IDA / V3740 Post Open 0.00 2022-08-15 2022-08-01 2022-10-03 2022-10-24 2022-11-28 2023-05-27 enior Civil Engineer ory Strengthening and Publi ant Selection ation c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-303291-CS-INDV / P ort Institutional and Regulat Individual Consult Pending Impleme IDA / V3740 Prior Open 0.00 2022-07-11 2022-08-29 2022-09-19 2022-10-24 2023-10-24 rocurement Assistant ory Strengthening and Publi ant Selection ntation c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-303293-CS-INDV / P ort Institutional and Regulat Individual Consult IDA / V3740 Prior Open 0.00 Signed 2022-07-15 2022-09-28 2022-09-02 2023-03-09 2022-09-23 2023-04-17 2022-10-28 2023-10-28 rocurement Officer ory Strengthening and Publi ant Selection c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301917-CS-INDV / A ort Institutional and Regulat Individual Consult Under Implement IDA / V3740 Post Open 0.00 2022-08-01 2022-10-11 2022-09-19 2022-10-10 2022-11-14 2023-11-14 rchitect and Physical Planner ory Strengthening and Publi ant Selection ation c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301650-CS-INDV / ort Institutional and Regulat Individual Consult Pending Impleme Gender Based Violence Exper IDA / V3740 Post Open 0.00 2022-07-13 2022-08-31 2022-09-21 2022-10-26 2023-10-26 ory Strengthening and Publi ant Selection ntation t c Transport Industry Professi onalization 07/CONS/MMAUMP/22 / Proje Component 4: Project Manag Individual Consult IDA / V3740 Post Limited 0.00 Signed 2022-09-23 2022-10-04 2022-09-28 2022-11-22 2022-10-10 2022-12-08 2022-10-24 2022-12-23 ct Implementation Manual (PI ement, Monitoring and Evalu ant Selection M). ation 09/CONS/MMAUMP/22 / Gen Component 4: Project Manag Individual Consult IDA / V3740 Post Open - National 0.00 Signed 2022-09-20 2022-10-18 2022-11-08 2023-05-26 2022-11-29 2023-06-01 2023-01-03 2025-01-02 der Based Violence, ement, Monitoring and Evalu ant Selection ation 08/CONS/MMAUMP/22 / Soci Component 4: Project Manag IDA / V3740 Post Direct Selection Direct - National 0.00 Signed 2022-09-30 2022-11-19 2022-10-10 2023-02-07 2022-12-14 2024-12-13 al Safeguard Specialist ement, Monitoring and Evalu ation 06/CONS/MMAUMP/22 / Tech Component 1: Urban Transp nical support for defining and ort Institutional and Regulat Individual Consult Pending Impleme IDA / V3740 Post Open - National 0.00 2022-11-16 2023-01-04 2023-01-25 2023-03-01 2025-02-28 procurement of buses and bu ory Strengthening and Publi ant Selection ntation s depot c Transport Industry Professi onalization Component 1: Urban Transp 03/CONS/MMAUMP/22 / Tran ort Institutional and Regulat Individual Consult Under Implement IDA / V3740 Post Open - National 0.00 2022-10-05 2022-10-11 2022-11-23 2022-12-14 2023-02-16 2025-02-16 sport Economist ory Strengthening and Publi ant Selection ation c Transport Industry Professi onalization 02/CONS/MMAUMP/22 / Tech Component 1: Urban Transp nical support for defining and ort Institutional and Regulat Individual Consult Pending Impleme IDA / V3740 Post Open - National 0.00 2022-10-12 2022-11-30 2022-12-21 2023-01-25 2025-01-27 implementing of BRT Control ory Strengthening and Publi ant Selection ntation Center c Transport Industry Professi onalization 13/CONS/MMMAUMP/22. / En Component 4: Project Manag Individual Consult IDA / V3740 Post Open - National 0.00 Canceled 2022-10-18 2022-12-06 2022-12-27 2023-01-31 2025-01-30 vironmental Specialist ement, Monitoring and Evalu ant Selection ation 16/CONS/MMAUMP/22 / Gen Component 4: Project Manag Individual Consult Under Implement IDA / V3740 Post Open - National 0.00 2022-11-21 2022-11-22 2023-01-09 2023-01-30 2023-03-06 2025-03-17 der Based Violence, ement, Monitoring and Evalu ant Selection ation ation 17/CONS/MMAUMP/23 / Envir Component 4: Project Manag IDA / V3740 Post Direct Selection Direct - National 0.00 Signed 2023-02-15 2023-03-06 2023-02-25 2023-03-15 2023-05-01 2025-04-30 onmental Specialist ement, Monitoring and Evalu ation 22/CONS/MMAUMP/23 / Proje Component 4: Project Manag Individual Consult Under Implement IDA / V3740 Post Open - National 0.00 2023-04-28 2023-05-23 2023-06-16 2023-07-07 2023-08-11 2025-08-10 ct Accountant ement, Monitoring and Evalu ant Selection ation ation Component 1: Urban Transp MZ-MTC-300499-CS-INDV / I ort Institutional and Regulat Individual Consult IDA / V3740 Post Open 0.00 Canceled 2022-11-15 2022-07-08 2023-01-03 2023-01-24 2023-02-28 2023-08-27 T Specialist ory Strengthening and Publi ant Selection c Transport Industry Professi onalization Component 1: Urban Transp MZ-MTC-301618-CS-INDV / F ort Institutional and Regulat Individual Consult IDA / V3740 Post Open 0.00 Canceled 2022-07-15 2022-07-12 2022-09-02 2022-09-23 2022-10-28 2023-04-26 inancial Manager Junior ory Strengthening and Publi ant Selection c Transport Industry Professi onalization 25/CONS/MMAUP/23 / Devel Component 4: Project Manag Individual Consult Pending Impleme op technical standards for bu IDA / V3740 ement, Monitoring and Evalu Post Open - National 0.00 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 ant Selection ntation s stops within AMM ation 28/CONS/MMUAP/23 / Projec Component 4: Project Manag Individual Consult Under Implement IDA / V3740 Post Open - National 0.00 2023-05-10 2023-06-22 2023-06-28 2023-07-19 2023-08-23 2025-08-22 t Community Engagement Of ement, Monitoring and Evalu ant Selection ation ficer ation Page 4 Component 1: Urban Transp 01/CONS/MMAUMP/22 / Instit ort Institutional and Regulat Individual Consult utional and Implementation IDA / V3740 Post Open - National 0.00 Canceled 2022-07-11 2022-11-15 2022-09-11 2022-10-02 2022-11-30 2024-11-30 ory Strengthening and Publi ant Selection Advisor c Transport Industry Professi onalization 28/CONS/MMAUP/23 / Imple Component 4: Project Manag Individual Consult Under Implement IDA / V3740 Post Open - National 0.00 2023-05-30 2023-05-23 2023-07-18 2023-08-08 2023-09-12 2025-09-11 mentation Advisor ement, Monitoring and Evalu ant Selection ation ation 26/CONS/MMAUP/23 / Carry out an assessment of Famba Component 5: Contingency Individual Consult Under Implement as the e-ticketing solution for IDA / V3740 Post Open - National 0.00 2023-06-20 2023-06-22 2023-08-08 2023-08-29 2023-10-03 2024-03-31 and Emergency Response ant Selection ation AMM and characterize and co mpare options for cashless ( mobile) payment schemes. 27/CONS/MMAUP/23 / Projec Component 4: Project Manag Individual Consult Under Implement IDA / V3740 Post Limited 0.00 2023-06-15 2023-06-01 2023-06-20 2023-07-11 2023-08-15 2025-08-14 t Civil Engineer ement, Monitoring and Evalu ant Selection ation ation Page 5 PROCUREMENT PLAN Project information: Country: Bangladesh Project Name: Bangladesh COVID-19 Emergency Preparedness and Response Project P-number: P173757 Project Implementation agency: (i) Ministry of Health and Family Welfare (MoHFW) (ii) Central Medical Stores Depot (CMSD) (iii) Public Works Department (PWD) Period covered by this Procurement Plan: Entire Project Period Preamble In accordance with paragraph 5.9 of the World Bank Procurement Regulations for IPF Borrowers, July 2016, revised November 2017 and August 2018 (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to record all procurement actions for the Project, including preparing, updating and clearing its Procurement Plan, and seeking and receiving the Bank’s review and No-objection to procurement actions as required. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents (SPDs) shall be used for goods, works and non- consulting services where international competition is required and for consulting services, including their respective forms of contract. National Procurement Arrangements: In accordance with paragraph 5.3 of the World Bank Procurement Regulations, when approaching the national market, as agreed in the Procurement Plan, the country’s own procurement procedures may be used. These procurement procedures shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti- Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Act 2006 and the Public Procurement Rules 2008, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: i. Lottery in award of contracts shall not be allowed; ii. Bidders’ qualification[s]/experience requirement[s] shall be mandatory; iii. Bids shall not be rejected based on percentage above or below the estimated cost; iv. Model Bidding Documents agreed with the Bank shall be used for all national open competitive procurement; v. The eligibility of bidders shall be as defined under Section III of the World Bank Procurement Regulations for IPF Borrowers: accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. vi. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. vii. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. As per paragraph 5.4 of the Procurement Regulations, the “Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework” as attached to this document shall form part of the Model Bidding Documents. Leased Assets: Not Applicable. Procurement of Second-Hand Goods: as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables - Applicable” Domestic preference: as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works) as follows: Goods: Applicable; Works: Not applicable. Hands-on Expanded Implementation Support (HEIS): as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Bank’s Procurement Prior Review Thresholds: As this is an emergency response project, there will be no prior review for all procurement during the immediate response period. The project will also have increased threshold for Request for Quotations (RFQ) and national procurement, as applicable in emergency projects. Fraud and Corruption (F&C) Checklist: Fraud and Corruption (F&C) checklist, as developed and provided by the Bank, shall be properly filled in during the evaluation and be attached with the evaluation report in case of contracts following national competitive procurement and request for quotations. Attachment 1 Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. Title of the person signing the Letter: PROCUREMENT Bangladesh : COVID-19 Emergency Response and Pandemic Preparedness Project PLAN General Information Country: Bangladesh 2020-05-25 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173757 GPN Date: 2020-07-21 Project Name: COVID-19 Emergency Response and Pandemic Preparedness Project Loan / Credit No: IDA / 66050, COFN / C1850, IDA / 68460 Directorate General of Health Services Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PACKAGE GD-1 / Procuring o Component 1: Emergency C f Personal Protective Equipm IDA / 66050 Post Direct Selection Direct 3,762,489.51 3,760,684.62 Signed 2020-05-16 2020-04-07 2020-05-16 2020-04-12 2020-05-21 2020-05-20 2020-05-28 OVID-19 Response ent (PPE), KN95, N95 Mask a nd Hand Gloves PACKAGE GD-2 / Supplying P Component 1: Emergency C IDA / 66050 Post Direct Selection Direct 2,849,835.56 2,826,523.20 Signed 2020-05-16 2020-04-08 2020-05-16 2020-04-12 2020-05-21 2020-05-20 2020-05-30 PE for Corona Pandemic OVID-19 Response PACKAGE GD-5 / Procuring N Component 1: Emergency C IDA / 66050 Post Direct Selection Direct 441,606.75 412,201.30 Signed 2020-05-18 2020-04-08 2020-05-18 2020-04-12 2020-05-23 2020-04-18 2020-06-21 95 Masks for Using Corona P OVID-19 Response andemic PACKAGE GD-6 / Supplying P Component 1: Emergency C ulse Oxymeter for Measure C IDA / 66050 Post Direct Selection Direct 370,000.00 370,000.00 Signed 2020-05-17 2020-05-04 2020-05-18 2020-05-04 2020-05-21 2020-05-10 2020-06-30 OVID-19 Response ritical Patient through Masim o PACKAGE GD-10 / Procurem ent of Automated Modern IC Component 1: Emergency C Request for Quota IDA / 66050 Post 1,913,629.25 0.00 Canceled 2020-05-21 2020-05-27 2020-06-18 U Bed (Adult+Paedi) Strengt OVID-19 Response tions hening Patient Management PACKAGE GD-15 / Supplying Component 1: Emergency C Emergency Ventilator with all IDA / 66050 Post Direct Selection Direct 6,206,046.86 2,320,104.46 Signed 2020-05-18 2020-05-04 2020-05-19 2020-05-05 2020-05-27 2020-05-28 2020-06-18 OVID-19 Response Standard Accessories PACKAGE GD-16 / Supplying Component 2: Supporting N Compact Gas Powered Ventil IDA / 66050 ational and Sub-national, Pre Post Direct Selection Direct 2,349,347.91 2,343,658.82 Signed 2020-05-19 2020-05-06 2020-05-20 2020-05-07 2020-05-28 2020-05-28 2020-06-24 ator for Patient Monitoring vention and Preparedness PACKAGE GD-13 / Procurem Component 2: Supporting N ent of Five & Three Functions IDA / 66050 ational and Sub-national, Pre Post Direct Selection Direct 587,800.00 584,736.99 Signed 2020-05-25 2020-05-20 2020-05-26 2020-05-21 2020-05-30 2020-05-29 2020-06-06 Electric Hospital Bed vention and Preparedness PACKAGE GD_3 / Purchasing Component 1: Emergency C IDA / 66050 Post Direct Selection Direct 1,177,554.00 2,291,839.23 Signed 2020-06-20 2020-05-14 2020-06-21 2020-05-17 2020-06-28 2020-05-21 2020-07-15 rt-PCR Kit Using for Test Labs OVID-19 Response PACKAGE GD-24 / Procuring Component 1: Emergency C UN Agencies (Dire IDA / 66050 Post Direct 647,709.70 0.00 Canceled 2020-05-30 2020-06-01 2020-06-07 2020-06-30 Oxygen Concentrator throug OVID-19 Response ct) h UNICEF PACKAGE GD-8 / Supplying I Component 1: Emergency C nfrared Thermometer and KN IDA / 66050 Post Direct Selection Direct 1,089,270.98 1,085,740.91 Signed 2020-05-18 2020-04-09 2020-05-18 2020-04-12 2020-05-24 2020-04-20 2020-05-25 OVID-19 Response 95 Masks for Corona Pandem ic PACKAGE GD-3 / Purchasing Component 1: Emergency C IDA / 66050 Post Direct Selection Direct 1,177,554.00 0.00 Canceled 2020-05-24 2020-05-15 2020-05-25 2020-05-17 2020-06-02 2020-06-30 rt-PCR Kit Using for Test Labs OVID-19 Response PACKAGE GD-29 / Managem Component 1: Emergency C UN Agencies (Dire ent of COVID-19 Cases throu IDA / 66050 Post Direct 18,035,117.00 10,852,290.65 Signed 2020-07-22 2020-06-18 2020-07-28 2020-06-30 2020-09-02 2020-11-27 2021-03-01 OVID-19 Response ct) gh Upgradtion of Oxygen Sup ply System PACKAGE GD-28 / Procuring Component 1: Emergency C UN Agencies (Dire Medical goods through World IDA / 66050 Post Direct 2,923,851.00 2,923,951.00 Signed 2020-06-10 2020-05-18 2020-06-10 2020-05-20 2020-07-13 2020-06-09 2020-12-31 OVID-19 Response ct) Health Organization PACKAGE GD24 / Procuring Component 1: Emergency C UN Agencies (Dire Oxygen Concentrator and ot IDA / 66050 Post Direct 10,000,000.00 9,164,927.51 Signed 2020-06-21 2020-05-04 2020-06-22 2020-06-03 2020-07-16 2020-06-09 2021-01-12 OVID-19 Response ct) her Emergency Medical Good s through UNICEF PACKAGE GD-7 / Purchasing Component 1: Emergency C Request for Quota Single Stage - One E Medicines for Treatment of C IDA / 66050 Post Limited 1,177,634.00 0.00 Canceled 2020-05-19 2020-05-25 2020-11-28 OVID-19 Response tions nvelope OVID Patients PACKAGE GD-23 / Supplying Component 3: Implementati Request for Quota Single Stage - One E computer and related service IDA / 66050 on Management and Monitor Post Limited 353,296.20 0.00 Canceled 2020-06-02 2020-06-08 2020-06-30 tions nvelope for office operation ing and Evaluation PACKAGE GD-21 / Procuring Component 1: Emergency C rtPCR Machine with accessori IDA / 66050 Post Direct Selection Direct 2,355,208.00 0.00 Canceled 2020-05-27 2020-05-28 2020-06-01 2020-06-29 OVID-19 Response es for Identified COVID Patie nt BD-DGHS-234145-GO-DIR / P Component 1: Emergency C rocurement of Modern Micro IDA / 66050 Prior Direct Selection Direct 4,822,133.00 0.00 Canceled 2021-05-20 2021-07-14 2021-05-25 2021-10-05 2021-07-06 2023-06-30 OVID-19 Response biology Lab with RT-PCR BD-DGHS-234723-GO-DIR / I Component 1: Emergency C nstallation of ICU of 10 Medic IDA / 66050 Prior Direct Selection Direct 3,185,910.90 0.00 Canceled 2021-05-16 2021-05-20 2021-06-28 2021-12-25 OVID-19 Response al College Hospital DGHS/ERPP/AF/GD-46/182/2 Component 1: Emergency C 021 / Procuring Antigen Test COFN / C1850 Prior Direct Selection Direct 3,000,000.00 0.00 Canceled 2021-07-13 2021-07-27 2021-07-14 2021-07-29 2022-08-30 OVID-19 Response Kits for COVID-19 Page 1 DGHS/ERPP/AF/PACKAGE GD -60/136 / Strengthening of V Component 1: Emergency C COFN / C1850 Prior Direct Selection Direct 2,381,556.00 2,264,993.00 Signed 2021-07-29 2021-10-04 2021-08-01 2021-10-05 2021-08-31 2021-12-31 2023-06-30 accine Testing Laboratory un OVID-19 Response der National Control Laborato ry of DGDA DGHS/ERPP/AF/PACKAGE GD -20.3/158/2021 / Procuremen Component 1: Emergency C COFN / C1850 Prior Direct Selection Direct 2,173,857.00 0.00 Canceled 2021-08-02 2021-08-04 2021-08-29 2023-06-30 t of Equipment for 10 Bed Cri OVID-19 Response tical Care Unit at 7 Medical C ollege Hospitals DGHS/ERPP/AF/PACKAGE GD -61/201 / Procurement of Aut Component 1: Emergency C IDA / 68460 Prior Direct Selection Direct 7,863,421.00 7,765,912.50 Signed 2021-09-14 2021-09-16 2021-10-10 2021-10-07 2021-10-20 2021-11-04 2023-06-30 o Disable (AD) Syringe for Va OVID-19 Response ccination Program BD-DGHS-227379-GD34-GO- Component 1: Emergency C UN Agencies (Dire UN / Strengthening of Nation IDA / 68460 Prior Direct 2,737,415.25 0.00 Canceled 2021-04-06 2021-06-13 2021-04-11 2021-06-20 2021-05-16 2023-06-30 OVID-19 Response ct) al Control Laboratory of DGD A BD-DGHS-235881-GO-DIR / P Component 1: Emergency C IDA / 68460 Prior Direct Selection Direct 203,030,883.48 0.00 Canceled 2021-12-14 2021-12-30 2022-02-23 2022-06-30 urchase Vaccine for COVID-1 OVID-19 Response 9 DGHS/ERPP/BSMMU/AF/PACK AGE GD-59 / Procuring Emer Component 1: Emergency C COFN / C1850 Prior Direct Selection Direct 2,598,571.00 0.00 Canceled 2021-07-28 2021-07-29 2021-08-19 2023-06-29 gency Medical Equipment & OVID-19 Response MSR for BSMMU COVID-19 Fi eld Hospital DGHS/COVID-19 ERPP/PACK Component 1: Emergency C AGE:GD-30/2022 / Purchasin IDA / 68460 Prior Direct Selection Direct 120,000,000.00 0.00 Canceled 2022-01-12 2022-01-30 2022-03-21 2023-06-30 OVID-19 Response g COVID Vaccine DGHS/ERPP/GD-65/269/2022 Component 1: Emergency C IDA / 68460 Prior Direct Selection Direct 120,000,000.00 120,000,000.00 Signed 2022-01-19 2022-01-20 2022-01-26 2022-02-02 2022-02-23 2020-12-14 2022-08-22 / Procurement of COVID-19 V OVID-19 Response accine DGHS/ERPP/GD-20WB/263/2 022 / Procurement of Equipm Component 1: Emergency C Single Stage - One E Pending Impl COFN / C1850 Post Request for Bids Open - National 250,026.52 0.00 2022-01-19 2022-01-24 2022-01-25 2022-02-01 2022-03-01 2022-08-28 ent for 05 Bed Critical Care U OVID-19 Response nvelope ementation nit at BITID, Chattogram & I DH, Dhaka DGHS/ERPP/GD-20.3.1/266/2 022 / Procurement of Equipm Component 1: Emergency C Single Stage - One E COFN / C1850 Post Request for Bids Open - National 2,139,636.37 1,848,403.06 Signed 2022-01-19 2022-03-20 2022-01-24 2022-02-07 2022-03-31 2022-02-14 2022-04-24 2022-03-14 2022-05-23 2022-09-10 ent for 10 Bed Critical Care U OVID-19 Response nvelope nit at 7 Medical College Hosp itals DGHS/ERPP/GD-30/164/2021 Component 1: Emergency C IDA / 68460 Prior Direct Selection Direct 390,000,000.00 390,000,000.00 Signed 2022-02-14 2022-02-16 2022-02-19 2022-02-22 2022-03-26 2021-08-15 2022-09-22 / Procuring COVID-19 Vaccine OVID-19 Response DGHS/COVID-19/ERPP/COLD/ Component 1: Emergency C 156/2021 / Cold Chain for CO IDA / 68460 Prior Direct Selection Direct 5,810,245.00 0.00 Canceled 2022-02-28 2022-03-05 2022-04-09 2022-10-06 OVID-19 Response VID-19 Vaccine DGHS/ERPP/GD-66/274/2022 Component 1: Emergency C Single Stage - One E / Procurement of rt-PCR Test COFN / C1850 Post Request for Bids Open - National 200,000.00 1,598,365.15 Signed 2022-03-01 2022-03-20 2022-03-06 2022-06-09 2022-04-17 2022-03-31 2022-05-17 2022-05-26 2022-06-21 2022-06-13 2022-12-18 OVID-19 Response nvelope Kit for Omicron Variant DGHS/ERPP/GD-30.1/COLD/1 Component 1: Emergency C 56/2021 / Cold Chain for COV IDA / 68460 Prior Direct Selection Direct 4,287,524.00 0.00 Canceled 2022-04-07 2022-06-02 2022-04-12 2022-05-17 2022-11-13 OVID-19 Response ID-19 Vaccine DGHS/ERPP/GD-31/268/2022 Component 1: Emergency C / Refilling of Liquid Medical O COFN / C1850 Post Direct Selection Direct 574,842.50 486,543.03 Signed 2022-05-10 2022-05-17 2022-05-15 2022-04-18 2022-06-19 2022-07-06 2022-12-16 OVID-19 Response xygen Plant in 30 Health Faci lities DGHS/ERPP/GD-20.2.1/327/2 022 / Procurement of Equipm Component 1: Emergency C Open - Internationa Single Stage - One E Pending Impl COFN / C1850 Prior Request for Bids 3,902,954.00 0.00 2022-08-21 2022-08-26 2022-10-07 2022-10-28 2022-12-30 2023-04-29 ent for 10 Bed Critical Care U OVID-19 Response l nvelope ementation nit in 14 District Hospitals DGHS/ERPP/GD-35.1/328/20 22 / Procurement of Equipme Component 1: Emergency C Open - Internationa Single Stage - One E Under Imple COFN / C1850 Prior Request for Bids 3,000,000.00 0.00 2022-09-05 2023-03-22 2022-09-11 2023-03-26 2022-10-23 2022-11-22 2023-01-03 2023-04-03 nt for Modern Microbiology L OVID-19 Response l nvelope mentation aboratory with rt-PCR DGHS/ERPP/GD-31.1/335/20 Component 1: Emergency C Single Stage - One E Pending Impl 22 / Liquid Medical Oxygen r COFN / C1850 Post Request for Bids Open - National 736,842.00 0.00 2022-09-11 2022-09-15 2022-10-13 2022-11-05 2022-12-17 2023-06-15 OVID-19 Response nvelope ementation efilling in 30 health facilities DGHS/ERPP/GD-30.1/332/20 Component 1: Emergency C Open - Internationa Single Stage - One E Under Imple IDA / 68460 Prior Request for Bids 5,607,476.00 0.00 2023-02-28 2023-03-22 2023-03-03 2023-05-10 2023-04-14 2023-05-21 2023-05-14 2023-06-25 2023-09-23 22 / Cold Chain for COVID-19 OVID-19 Response l nvelope mentation Vaccine NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PACKAGE NCS-4 / Appointing C&F Agent for clearing emer Component 1: Emergency C IDA / 66050 Post Direct Selection Direct 471,803.60 36,826.69 Signed 2020-08-16 2020-08-24 2020-08-17 2020-09-03 2020-08-25 2020-09-14 2020-10-29 gency medical goods importe OVID-19 Response d through UNICEF, WHO & M asimo DGHSCOVID-19ERPPNCS-5 / HR and Transport Hiring for C Component 1: Emergency C UN Agencies (Dire IDA / 66050 Prior Direct 14,135,868.00 0.00 Canceled 2021-02-18 2021-03-09 2021-02-21 2021-03-14 2021-05-30 2022-12-30 OVID-19 Emergency Respons OVID-19 Response ct) e through UN Agency Component 3: Implementati DGHS/COVID-19/ERPP/NCS-9 Request for Quota Single Stage - One E IDA / 66050 on Management and Monitor Post Limited 3,546.00 3,065.86 Signed 2021-06-09 2021-06-20 2021-06-24 2021-07-06 2021-08-30 / Vehicle Rental for PIU tions nvelope ing and Evaluation DGHS/COVID-19/ERPP/PACK Component 1: Emergency C AGE-NCS-11/VR / Vehicle Ren COFN / C1850 Post Direct Selection Direct 23,603.00 20,651.22 Signed 2021-06-26 2021-06-27 2021-06-26 2021-06-27 2021-06-28 2021-06-29 2021-08-31 OVID-19 Response t for COVID-19 Emergency DGHS/COVID-19ERPP/NCS-1 Component 1: Emergency C Single Stage - One E COFN / C1850 Post Request for Bids Open - National 142,468.00 0.00 Canceled 2021-06-24 2021-06-27 2021-07-15 2021-07-20 2021-08-10 2022-05-30 0 / Rental Vehicle for Lab Call OVID-19 Response nvelope Centre Page 2 DGHS/COVID-19ERPP/NCS-8 Component 1: Emergency C Request for Quota Single Stage - One E / Vehicle Rental for COVID-19 COFN / C1850 Post Limited 5,859.00 0.00 Canceled 2021-06-10 2021-06-28 2021-08-31 OVID-19 Response tions nvelope Emergency DGHS/ERPP/AF/PACKAGE NC S-13/189/2021 / Vehicle Rent Component 1: Emergency C Single Stage - One E COFN / C1850 Post Request for Bids Open - National 211,510.00 0.00 Canceled 2021-08-03 2021-08-08 2021-08-04 2021-08-10 2021-08-16 2021-08-23 2021-08-22 2021-08-30 2023-06-30 al for Sample Collection of E OVID-19 Response nvelope mergency Service DGHS/ERPP/NCS-19/256/202 Component 1: Emergency C 2 / Emergency Transport Hiri COFN / C1850 Post Direct Selection Direct 8,500.00 7,681.55 Signed 2022-01-12 2022-01-17 2022-01-17 2022-01-17 2022-02-21 2022-01-27 2022-08-20 OVID-19 Response ng for IEDCR DGHS/ERPP/NCS-18/246/202 Component 1: Emergency C Single Stage - One E COFN / C1850 Post Request for Bids Open - National 420,000.00 335,664.26 Signed 2022-02-06 2022-02-17 2022-02-08 2022-02-22 2022-02-27 2022-03-01 2022-03-07 2022-04-05 2022-03-23 2023-03-31 1 / Transport Hiring for Conta OVID-19 Response nvelope ct Tracing DGHS/ERPP/NCS-15/273/202 Component 1: Emergency C COFN / C1850 Post Direct Selection Direct 13,796.22 10,320.24 Signed 2022-05-10 2022-05-10 2022-05-15 2022-05-11 2022-06-19 2022-06-08 2022-12-16 2 / Hiring C&F agent OVID-19 Response DGHS/ERPP/NCS-16/378/202 Component 1: Emergency C Single Stage - One E Pending Impl COFN / C1850 Post Request for Bids Open - National 468,437.00 0.00 2023-05-10 2023-05-14 2023-05-28 2023-06-04 2023-07-16 2024-01-28 3 / Appointment of C&F Agen OVID-19 Response nvelope ementation t CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PACKAGE SD-1 / Developme Component 3: Implementati nt of CoronaBD Mobile App a IDA / 66050 on Management and Monitor Post Direct Selection Direct 571,144.73 559,651.59 Signed 2020-05-18 2020-04-10 2020-05-20 2020-04-10 2020-05-28 2020-04-16 2020-06-28 nd National Corona Care Syst ing and Evaluation em Central Web Application PACKAGE SD -2 / Develop TV Component 1: Emergency C C for awareness, education, r IDA / 66050 Post Direct Selection Direct 68,759.25 68,655.95 Signed 2020-05-20 2020-04-12 2020-05-21 2020-04-12 2020-05-25 2020-04-16 2020-05-31 OVID-19 Response isk communication & counter misinformation Component 3: Implementati PACKAGE SD-3 / Procuremen Individual Consult IDA / 66050 on Management and Monitor Post Direct 112,699.11 112,735.19 Signed 2020-05-20 2020-04-22 2020-05-22 2020-04-23 2020-05-22 2020-04-30 2020-05-28 2020-05-01 2022-05-02 t Specialist ant Selection ing and Evaluation PACKAGE SD-6 / Risk Comm Component 3: Implementati unication and Community En IDA / 66050 on Management and Monitor Post Direct Selection Direct 58,789.50 0.00 Canceled 2020-05-24 2020-05-28 2020-06-05 2020-06-30 gagement ing and Evaluation PACKAGE SD-7 / Awareness Component 2: Supporting N Building TVC Regarding Disp IDA / 66050 ational and Sub-national, Pre Post Direct Selection Direct 88,324.05 100,251.21 Signed 2020-05-22 2020-05-04 2020-05-23 2020-05-05 2020-05-25 2020-05-14 2020-06-15 osal of COVID-19 Dead Bodie vention and Preparedness s PACKAGE SD-4 / AI Based Su Component 3: Implementati rveillance and Contact Tracin IDA / 66050 on Management and Monitor Post Direct Selection Direct 58,880.90 0.00 Canceled 2020-05-20 2020-05-22 2020-05-25 2020-06-30 g ing and Evaluation PACKAGE SD-8 / Program for Eid-ul-Fitar to Raise Mass Aw Component 1: Emergency C IDA / 66050 Post Direct Selection Direct 62,356.67 0.00 Canceled 2020-05-23 2020-05-23 2020-05-24 2020-05-31 areness of COVID-19 using M OVID-19 Response ainstreaming Media including Social Media PACKAGE SD-15 / ICS- Junior Component 1: Emergency C Individual Consult IDA / 66050 Post Direct 33,974.76 0.00 Canceled 2020-07-28 2021-01-25 2020-08-16 2020-08-23 2020-09-27 2021-03-26 Financial Management OVID-19 Response ant Selection DGHSCOVID-19ERPPCSD-5 / Component 1: Emergency C Individual Consult Selection of Environmental M IDA / 66050 Post Direct 28,370.23 7,554.93 Signed 2021-01-31 2021-01-25 2021-02-01 2021-02-03 2021-02-04 2021-02-09 2021-02-10 2021-02-11 2021-05-30 OVID-19 Response ant Selection anagement Specialist DGHSCOVID-19ERPPCSD6 / Component 1: Emergency C Individual Consult Selection of Social Developm IDA / 66050 Post Direct 28,370.23 5,466.13 Signed 2021-01-31 2021-01-25 2021-02-03 2021-02-08 2021-02-10 2021-02-10 2021-02-25 2021-02-12 2021-06-30 OVID-19 Response ant Selection ent Specialist DGHSCOVID-19ERPPSD-08 / Component 1: Emergency C Individual Consult IDA / 66050 Post Direct 85,110.70 86,799.15 Signed 2021-01-31 2020-06-08 2021-02-09 2020-06-09 2021-02-09 2020-06-14 2021-02-25 2020-06-15 2022-06-30 Selection of M&E Specialist OVID-19 Response ant Selection DGHS/COVID-19/ERPP/PACK Component 1: Emergency C Individual Consult AGE CS-7 / Financial Manage IDA / 66050 Post Direct 11,794.84 9,304.80 Signed 2021-02-08 2021-01-25 2021-02-10 2021-01-25 2021-02-11 2021-02-03 2021-02-14 2021-02-09 2021-08-31 OVID-19 Response ant Selection ment Specialist (Jr.) PACKAGE SD-9 / Procuremen Component 1: Emergency C Individual Consult IDA / 66050 Post Direct 112,792.16 0.00 Canceled 2020-07-22 2020-07-25 2020-08-01 2020-09-08 2022-09-07 t Consultant OVID-19 Response ant Selection PACKAGE SD-5 / Operational Component 3: Implementati and Epidemiological Researc IDA / 66050 on Management and Monitor Post Direct Selection Direct 58,690.90 0.00 Canceled 2020-05-21 2020-05-22 2020-05-26 2020-06-23 h ing and Evaluation PACKAGE SD-11 / Financial Component 1: Emergency C Individual Consult IDA / 66050 Post Direct 112,792.16 0.00 Canceled 2020-06-25 2020-06-29 2020-07-05 2020-07-12 2022-07-11 Management Specialist OVID-19 Response ant Selection BD-DGHS-227366-CS-6.1IND Component 1: Emergency C Individual Consult IDA / 66050 Post Open 27,716.18 25,115.32 Terminated 2021-04-04 2021-04-07 2021-05-05 2022-01-04 2021-05-16 2021-09-02 2021-06-01 2022-02-15 2022-03-31 V / Social Development Speci OVID-19 Response ant Selection alist BD-DGHS-227361-CS-INDV / Component 1: Emergency C Individual Consult IDA / 66050 Post Open 165,117.68 100,998.52 Signed 2021-04-04 2021-04-12 2021-05-04 2021-09-02 2021-05-14 2021-09-05 2021-06-30 2021-11-03 2023-05-31 Financial Management Speci OVID-19 Response ant Selection alist BD-DGHS-227363-CS-5.1IND Component 1: Emergency C Individual Consult V / Environmental Manageme IDA / 66050 Post Open 20,050.00 21,962.04 Signed 2021-04-04 2021-04-07 2021-06-07 2021-08-31 2021-06-10 2021-09-02 2021-06-20 2021-10-29 2021-12-17 OVID-19 Response ant Selection nt Specialist DGHS/ERPP/PACKAGE CS-7.1 Component 1: Emergency C Individual Consult /AF/166 / Junior Financial Man COFN / C1850 Post Direct 56,260.00 37,454.84 Signed 2021-08-30 2021-09-09 2021-09-08 2021-09-12 2021-09-20 2021-10-07 2021-10-03 2021-10-12 2023-08-31 OVID-19 Response ant Selection agement Specialist Page 3 Component 3: Implementati DGHS/ERPP/CS-3.1/248/2022 Individual Consult COFN / C1850 on Management and Monitor Prior Open 74,213.31 62,549.91 Signed 2022-01-19 2022-01-26 2022-02-16 2022-04-07 2022-02-23 2022-04-13 2022-03-30 2022-04-18 2022-09-26 / Procurement Specialist ant Selection ing and Evaluation DGHS/ERPP/CS-60.1/283/202 2 / Capacity Building for Vacc Component 1: Emergency C Pending Impleme IDA / 68460 Post Direct Selection Direct 352,733.85 0.00 2022-04-06 2022-04-16 2022-06-20 2022-12-17 ine Testing Laboratory Perso OVID-19 Response ntation nnel under National Control L aboratory of DGDA DGHS/ERPP/CS-4.1 / Selectio Component 1: Emergency C Individual Consult COFN / C1850 Post Limited 31,579.00 0.00 Signed 2022-09-01 2022-07-27 2022-09-04 2022-09-22 2022-09-08 2022-09-25 2022-09-18 2023-06-30 n of Monitoring & Evaluation OVID-19 Response ant Selection Specialist DGHS/ERPP/CS-7 / Selection Component 1: Emergency C Individual Consult Under Implement COFN / C1850 Post Limited 25,263.00 0.00 2022-09-01 2022-07-27 2022-09-04 2022-09-22 2022-09-08 2022-09-25 2022-09-18 2023-06-30 of Research & Development OVID-19 Response ant Selection ation Consultant DGHS/ERPP/CS-6.2 / Selectio Component 1: Emergency C Individual Consult Under Implement COFN / C1850 Post Limited 19,962.00 0.00 2022-10-04 2022-10-06 2022-10-07 2022-11-17 2022-10-11 2022-11-20 2022-10-21 2023-06-30 n of Social Development Spe OVID-19 Response ant Selection ation cialist Component 3: Implementati DGHS/ERPP/CS-3.2/376/2023 Individual Consult Under Implement COFN / C1850 on Management and Monitor Post Open - National 30,450.00 0.00 2023-04-12 2023-04-10 2023-06-01 2023-06-22 2023-07-27 2023-12-31 / Procurement Specialist ant Selection ation ing and Evaluation DGHS/ERPP/CS-1.1/377/2023 Component 3: Implementati Individual Consult Under Implement / Financial Management Spec COFN / C1850 on Management and Monitor Post Open - National 30,450.00 0.00 2023-04-12 2023-04-10 2023-05-31 2023-06-21 2023-07-26 2023-12-31 ant Selection ation ialist ing and Evaluation DGHS/ERPP/CS-7.2/383/2023 Component 1: Emergency C Individual Consult Pending Impleme / Financial Management Spec COFN / C1850 Post Limited 11,091.57 0.00 2023-06-11 2023-06-16 2023-07-07 2023-08-11 2024-02-07 OVID-19 Response ant Selection ntation ialist (Junior) Page 4 PROCUREMENT PLAN (Mandatory Requirements) Emergency Multi-Sector Rohingya Crisis Response Project (EMRCRP) Project Implementation Agencies: Ministry of Disaster Management and Relief (MoDMR) Department of Public Health Engineering (DPHE) Local Government Engineering Department (LGED) Period covered by this Procurement Plan: Entire Project Period Preamble In accordance with paragraph 5.9 of the World Bank Procurement Regulations for IPF Borrowers, July 2016 revised November 2017 (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to record all procurement actions for the Project, including preparing, updating and clearing its Procurement Plan, and seeking and receiving the Bank’s review and No-objection to procurement actions as required. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents (SPDs) shall be used for goods, works and non- consulting services where international competition is required and for all consulting services, including their respective forms of contract. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Act 2006 and the Public Procurement Rules 2008, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) Lottery in award of contracts shall not be allowed; 2) Bidders’ qualification[s]/experience requirement[s] shall be mandatory; 3) Bids shall not be rejected based on percentage above or below the estimated cost; 4) Model Bidding Documents agreed with the Bank shall be used for all national open competitive procurement; 5) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations; 6) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 7) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts When the Borrower uses other national procurement arrangements (other than national open competitive procurement), such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), such arrangements shall be consistent with the above requirements. As per paragraph 5.4 of the Procurement Regulations, the “Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework” as attached to this document shall form part of the Model Bidding Documents. Leased Assets: Not Applicable. Procurement of Second Hand Goods: Not Applicable. Domestic preference: as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works) as follows: Goods: Applicable; Works: Not applicable. Hands-on Expanded Implementation Support (HEIS): Not Applicable. Bank’s Procurement Prior Review Thresholds: contracts at or above the thresholds set out in table 1 below are subject to the Bank’s procurement prior review. Table 1: Procurement Prior Review Thresholds (US$ millions) Type of High risk Substantial Moderate Low risk procurement risk risk Works (including 5 10 15 20 turnkey, supply & installation of plant and equipment, and PPP) Goods, information 1.5 2 4 6 technology and non-consulting services Consulting 0.5 1 2 4 services: firms Consulting 0.2 0.3 0.4 0.5 services: Individual Notes: 1. These thresholds apply to all procurement activities regardless of their procurement/selection methods. There is no automatic requirement to undertake prior review for direct selection for value less than these thresholds. Consultant services covers a range of services that are of an advisory or professional nature. 2. In addition to the provisions of Table 1 above, and irrespective of the contract value, the following procurement activities are subject to the Bank’s procurement prior review: (a) procurement processes involving contract negotiations, as described in Section VI, paragraphs 6.34-36, of the Procurement Regulations; (b) competitive dialogue; (c) sustainable procurement; (d) selection of probity assurance providers, as described in Section III, paragraph 3.3 of the Procurement Regulations; and (e) best and final offer. 3. The determination of whether a contract meets the procurement prior review threshold is based on the estimated value of the contract or the package -when the selection document contains more than one lot/slice- , including all taxes and duties payable under the contract. Bid/ Proposal Evaluation Committee: formation and alteration of the bid/proposal evaluation committee shall be subject to Bank’s no objection. Fraud and Corruption (F&C) Checklist: Fraud and Corruption (F&C) checklist, as developed and provided by the Bank, shall be properly filled in during the evaluation and be attached with the evaluation report in case of contracts following national competitive procurement and request for quotations. Attachment 1 Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: PROCUREMENT Bangladesh : Emergency Multi-Sector Rohingya Crisis Response Project PLAN General Information Country: Bangladesh 2019-02-17 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167762 GPN Date: Project Name: Emergency Multi-Sector Rohingya Crisis Response Project Loan / Credit No: / , IDA / D4190, IDA / D5900 Local Government Engineering Department Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component 1: Strengthening EMCRP/W3 / Relief Administr Delivery of Basic Services, R ation and Distribution Center Single Stage - One E 2021-04-1 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 240,000.00 228,105.67 Signed 2019-07-01 2020-03-01 2019-07-06 2019-07-21 2020-03-25 2019-08-30 2020-04-21 2019-10-11 2020-05-18 in Ukhya Upazial of Cox's Baz nvelope 3 gency Response, and Gende ar District. r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W7 / Construction of Delivery of Basic Services, R Single Stage - One E 2020-11-0 Field Office (EE Cox's Bazar) IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 180,000.00 155,966.98 Signed 2019-07-25 2019-10-16 2019-07-30 2019-08-14 2019-11-12 2019-09-23 2019-11-24 2019-11-04 2019-12-11 nvelope 3 extension with renovation gency Response, and Gende r-Based Viol ence Prevention EMCRP/W10 / Construction o Component 1: Strengthening f 12 nos. new School cum Dis Delivery of Basic Services, R Single Stage - One E 2021-09-1 aster shelter buildings in Ukh IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 6,020,000.00 347,830.11 Signed 2019-06-01 2019-10-01 2019-06-06 2019-06-21 2019-10-31 2019-07-31 2019-07-30 2019-09-11 2019-09-12 nvelope 0 ya Upazial of Cox's Bazar Dis gency Response, and Gende trict. r-Based Viol ence Prevention EMCRP/W13 / Improvement Component 1: Strengthening of 8 Access Road to different Delivery of Basic Services, R Single Stage - One E 2,088,894.6 2021-05-1 camps of forcibly displaced IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,180,000.00 Signed 2019-08-01 2019-11-03 2019-08-06 2019-08-21 2019-12-04 2019-09-30 2019-12-24 2019-11-11 2020-01-30 nvelope 1 4 Myanmar nationals under Co gency Response, and Gende x's Bazar District: r-Based Viol ence Prevention EMCRP/W14 / Improvement Component 1: Strengthening of 7 Access Road to different Delivery of Basic Services, R Single Stage - One E 1,752,754.7 2021-05-2 camps of forcibly displaced IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,160,000.00 Signed 2019-08-10 2019-10-27 2019-08-15 2019-08-30 2019-11-27 2019-10-09 2019-12-04 2019-11-20 2020-01-15 nvelope 7 3 Myanmar nationals under Co gency Response, and Gende x's Bazar District: r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W15 / Construction o Delivery of Basic Services, R Single Stage - One E 2,205,379.1 2022-07-1 f 4 RCC roads under Cox's Ba IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 3,270,000.00 Signed 2020-09-20 2020-10-16 2020-09-24 2020-10-29 2020-11-23 2020-11-25 2021-02-01 2021-01-06 2021-03-11 nvelope 2 0 zar District: gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W16 / Construction o Delivery of Basic Services, R Single Stage - One E 1,433,552.2 2022-07-1 f 4 RCC roads under Cox's Ba IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,860,000.00 Signed 2020-09-20 2020-10-16 2020-09-25 2020-10-30 2020-11-23 2020-11-26 2021-02-01 2021-01-07 2021-03-11 nvelope 0 1 zar District: gency Response, and Gende r-Based Viol ence Prevention EMCRP/W19 / Improvemento Component 1: Strengthening f 10 roads roads and constru Delivery of Basic Services, R Single Stage - One E 2022-07-1 ction of culverts with side dra IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 3,220,000.00 191,767.13 Signed 2020-09-10 2020-07-23 2020-09-14 2020-10-15 2020-08-26 2020-11-29 2020-09-06 2021-01-10 2020-11-05 nvelope 4 ins under Cox's Bazar Distri gency Response, and Gende ct: r-Based Viol ence Prevention EMCRP/W21 / Improvement Component 1: Strengthening of 17 roads roads and constr Delivery of Basic Services, R Single Stage - One E 3,263,471.5 2022-12-2 uction of culverts with side dr IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 3,190,000.00 Signed 2021-02-25 2021-03-18 2021-03-01 2021-04-05 2021-05-03 2021-05-15 2021-05-30 2021-06-26 2021-07-20 nvelope 4 8 ains under Cox's Bazar Distr gency Response, and Gende ict: r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W6 / Rehabiliation of Delivery of Basic Services, R blocked hilly chorra with exc Single Stage - One E 2021-09-2 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 60,000.00 0.00 Canceled 2021-03-30 2021-04-03 2021-04-24 2021-05-19 2021-06-30 avation of canalin Ukhya Upa nvelope 8 gency Response, and Gende zial of Cox's Bazar District. r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W8 / Construction of Delivery of Basic Services, R 6 RCC Girder bridges at differ Single Stage - One E 1,409,281.9 2023-01-1 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,780,000.00 Signed 2020-09-20 2020-10-19 2020-09-24 2020-10-29 2020-11-23 2020-12-04 2021-02-01 2021-01-15 2021-03-11 ent roads under Cox's Distric nvelope 6 5 gency Response, and Gende t. r-Based Viol ence Prevention EMCRP/W20 / Improvement Component 1: Strengthening of 11 roads roads and constr Delivery of Basic Services, R Single Stage - One E 3,308,124.3 2022-08-1 uction of culverts with side dr IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 3,400,000.00 Signed 2020-10-20 2021-01-28 2020-10-24 2020-11-28 2021-03-02 2020-12-30 2021-03-16 2021-02-10 2021-04-14 nvelope 9 4 ains under Cox's Bazar Distr gency Response, and Gende ict: r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W24 / Improvement Delivery of Basic Services, R Single Stage - One E 2,207,925.9 2023-01-2 of 7 roads under Cox's Bazar IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 3,350,000.00 Signed 2021-03-25 2021-03-18 2021-03-29 2021-05-03 2021-05-03 2021-06-12 2021-06-05 2021-07-24 2021-07-20 nvelope 6 5 District: gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W22 / Improvement Delivery of Basic Services, R 15 Roads with culverts and si Single Stage - One E 2,796,624.6 2023-02-2 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,770,000.00 Signed 2021-04-20 2021-03-18 2021-04-24 2021-05-29 2021-05-03 2021-07-08 2021-06-05 2021-08-19 2021-07-20 de drain under Cox's Bazar D nvelope 3 0 gency Response, and Gende istrict r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W9 / Construction of Delivery of Basic Services, R 4 RCC Girder bridges at differ Single Stage - One E 1,278,919.1 2023-01-1 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,410,000.00 Signed 2020-09-20 2020-10-19 2020-09-24 2020-10-30 2020-11-23 2020-12-04 2021-02-01 2021-01-15 2021-03-11 ent roads under Cox's Distric nvelope 6 5 gency Response, and Gende t. r-Based Viol ence Prevention EMCRP/W11 / Construction o Component 1: Strengthening f 11 nos. new School cum Dis Delivery of Basic Services, R Single Stage - One E 4,988,485.3 2022-11-2 aster shelter buildings in Uk IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 5,520,000.00 Signed 2020-07-24 2020-07-21 2020-07-28 2020-09-02 2020-09-22 2020-10-12 2020-10-08 2020-11-23 2020-12-14 nvelope 3 3 hya (9 nos.) and Teknaf (2no gency Response, and Gende s) Upazial of Cox's Bazar Dist r-Based Viol ence Prevention rict. Page 1 Component 1: Strengthening EMCRP/W23 / Improvement Delivery of Basic Services, R 18 Roads with culverts and si Single Stage - One E 4,510,585.3 2023-02-2 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 3,190,000.00 Signed 2021-04-20 2020-10-16 2021-04-24 2021-05-29 2020-11-23 2021-07-08 2021-03-04 2021-08-19 2021-04-30 de drain under Cox's Bazar D nvelope 5 0 gency Response, and Gende istrict r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W25 / Strengthening Delivery of Basic Services, R Single Stage - One E 1,774,351.5 2023-03-2 and widening of 10 roads un IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,020,000.00 Signed 2021-05-26 2021-01-28 2021-05-30 2021-07-04 2021-03-02 2021-08-13 2021-03-16 2021-09-24 2021-04-16 nvelope 0 8 der Cox's Bazar Districts gency Response, and Gende r-Based Viol ence Prevention EMCRP/W18 / Improvement Component 1: Strengthening of 8 roads roads and constru Delivery of Basic Services, R Single Stage - One E 2,055,922.9 2022-08-1 ction of culverts with side dra IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 3,230,000.00 Signed 2020-10-20 2020-10-16 2020-10-24 2020-11-29 2020-11-23 2020-12-30 2021-02-01 2021-02-10 2021-03-11 nvelope 3 4 ins under Cox's Bazar Distri gency Response, and Gende ct: r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W1 / Improvement fo Delivery of Basic Services, R Single Stage - One E 2021-12-3 6 nos. Hat Bazar under Cox's IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 360,000.00 732,124.33 Signed 2021-03-10 2021-12-23 2021-03-14 2021-04-13 2022-01-31 2021-05-23 2022-03-03 2021-07-04 2022-04-29 nvelope 1 Bazar Districts: gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W17 / Improvement Delivery of Basic Services, R of 8 roads and construction Single Stage - One E 2,236,005.8 2022-08-1 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,890,000.00 Signed 2020-10-20 2020-10-16 2020-10-24 2020-11-29 2020-11-23 2020-12-30 2021-02-01 2021-02-10 2021-03-11 of culverts with side drains u nvelope 1 4 gency Response, and Gende nder Cox's Bazar District: r-Based Viol ence Prevention Component 1: Strengthening National Procure EMCRP/W26 / Improvement Delivery of Basic Services, R ment Document - Single Stage - One E 1,981,314.3 2023-04-1 of 09 nos Roads under Cox's IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,514,400.00 Signed 2021-08-11 2021-03-18 2021-08-14 2021-09-04 2021-05-03 2021-09-11 2021-06-05 2021-10-16 2021-07-20 nvelope 7 4 Bazar District gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W18 / Strengtheni Delivery of Basic Services, R ment Document - ng and widening of Gorakgha Single Stage - One E 4,926,653.7 2023-07-0 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 5,617,300.00 Signed 2021-10-05 2021-10-11 2021-10-11 2021-11-08 2021-11-10 2021-11-29 2021-12-26 2022-01-10 2022-02-11 ta - Shaplapur Janata Bazar R nvelope 9 9 gency Response, and Gende ss (Non Bank-SPD oad r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W8 / Building Con Delivery of Basic Services, R ment Document - struction for Fire Service Civil Single Stage - One E 2023-05-2 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 3,000,000.00 0.00 Signed 2022-02-28 2022-06-16 2022-03-05 2022-04-02 2022-07-20 2022-04-23 2022-08-08 2022-05-28 Defense (FSCD) at Cox's Baz nvelope 8 gency Response, and Gende ss (Non Bank-SPD ar r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W15 / Improveme Delivery of Basic Services, R ment Document - nt of road by RCC pavement Single Stage - One E 2023-09-0 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 629,328.00 665,315.72 Signed 2021-12-23 2021-12-27 2021-12-28 2022-01-25 2022-01-31 2022-02-08 2022-03-03 2022-03-15 2022-04-27 in Mirakata from Ch. 00-200 nvelope 6 gency Response, and Gende ss (Non Bank-SPD 0m in Kutubdia r-Based Viol ence Prevention ) Component 1: Strengthening EMCRP/W4 / Construction of Delivery of Basic Services, R Multipurpose Community and Single Stage - One E 2022-09-2 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 3,434,667.00 0.00 Canceled 2020-11-20 2021-06-27 2020-11-25 2020-12-30 2021-07-27 2021-02-06 2021-03-20 Service Center in Ukhya Upa nvelope 1 gency Response, and Gende zial of Cox's Bazar District. r-Based Viol ence Prevention EMCRP/W4-A / Construction Component 1: Strengthening National Procure of 12 nos Multipurpose Com Delivery of Basic Services, R ment Document - Single Stage - One E 2,935,355.9 2023-01-3 munity and Service Center in IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 3,091,262.00 Signed 2021-12-05 2021-12-23 2021-12-10 2022-01-07 2022-01-31 2022-01-21 2022-03-03 2022-01-30 2022-04-20 nvelope 0 0 Ukhya Upazila in Cox's Bazar gency Response, and Gende ss (Non Bank-SPD district r-Based Viol ence Prevention ) EMCRP/W4. / Construction of Component 1: Strengthening National Procure 10 nos Multipurpose Commu Delivery of Basic Services, R ment Document - Single Stage - One E 2,773,534.0 2023-02-2 nity and Service Center in U IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,773,067.00 Signed 2021-12-05 2021-12-23 2021-12-10 2022-01-07 2022-01-31 2022-01-21 2022-03-03 2022-02-25 2022-04-29 nvelope 7 5 khya Upazila in Cox's Bazar gency Response, and Gende ss (Non Bank-SPD District r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W11 / Constructio Delivery of Basic Services, R ment Document - Single Stage - One E 8,158,856.2 2023-10-0 n of 14 nos. new School cum IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 9,690,000.00 Signed 2022-01-16 2022-01-17 2022-01-21 2022-02-18 2022-02-24 2022-03-11 2022-03-13 2022-04-15 2022-05-18 nvelope 0 7 Disaster Shelter Buildings gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) EMCRP/AF/W11-A / Construct Component 1: Strengthening National Procure ion of New 03 nos School cu Delivery of Basic Services, R ment Document - Single Stage - One E 1,962,622.7 2023-10-0 m Disaster Shelter Buildings IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,280,000.00 Signed 2022-01-16 2022-02-01 2022-01-21 2022-02-18 2022-03-07 2022-03-11 2022-03-29 2022-04-15 2022-05-12 nvelope 0 7 and associated 1.90 Km conn gency Response, and Gende ss (Non Bank-SPD ecting roads r-Based Viol ence Prevention ) EMCRP/W2 / Construction of Component 1: Strengthening National Procure warehouse for firefighting eq Delivery of Basic Services, R ment Document - Single Stage - One E 1,021,518.0 2024-01-0 uipment and Satellite fire sta IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 1,089,150.00 Signed 2022-03-30 2022-03-29 2022-04-04 2022-05-02 2022-05-10 2022-05-23 2022-05-24 2022-07-04 2022-06-29 nvelope 9 5 tions in Ukhya Upazial of Cox gency Response, and Gende ss (Non Bank-SPD 's Bazar District. r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W4 / Improvemen Delivery of Basic Services, R ment Document - t of Gorokghata Jetty in Mohe Single Stage - One E 2024-05-2 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 4,358,068.00 0.00 Canceled 2022-08-16 2022-08-25 2022-08-21 2022-09-18 2022-09-27 2022-10-16 2022-11-27 skhali and Darbarghat Jetty i nvelope 5 gency Response, and Gende ss (Non Bank-SPD n Kutubdia r-Based Viol ence Prevention ) Component 1: Strengthening National Procure Delivery of Basic Services, R ment Document - EMCRP/AF/W5 / Improvemen Single Stage - One E Pending Imp 2024-03-2 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 117,785.00 0.00 2022-12-15 2022-12-20 2023-01-10 2023-02-07 2023-03-21 t of two Jettis at Teknaf nvelope lementation 0 gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) EMCRP/W5 / Construction of Component 1: Strengthening National Procure internal road, footpath, drain Delivery of Basic Services, R ment Document - Single Stage - One E Pending Imp 2023-08-2 age and side slope protection IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,150,000.00 0.00 2022-12-01 2022-12-06 2022-12-27 2023-01-17 2023-02-28 nvelope lementation 7 in Ukhya Upazial of Cox's Baz gency Response, and Gende ss (Non Bank-SPD ar District. r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W7 / Improvemen Delivery of Basic Services, R ment Document - Single Stage - One E Pending Imp 2023-12-0 t of Existing Fire Service Offic IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 913,910.00 0.00 2022-09-15 2022-09-20 2022-10-18 2022-11-01 2022-12-06 nvelope lementation 6 e at Ukhiya and Teknaf gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) Page 2 Component 1: Strengthening National Procure EMCRP/AF/W9 / LGED Buildin Delivery of Basic Services, R ment Document - Single Stage - One E Pending Imp 2023-11-0 g Improvement at Cox's Baza IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 150,766.00 0.00 2022-08-25 2022-08-30 2022-09-13 2022-09-27 2022-11-01 nvelope lementation 1 r gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W10 / Training Fa Delivery of Basic Services, R ment Document - Single Stage - One E 2023-11-2 cility Construction for LGED a IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 1,896,350.00 0.00 Signed 2022-08-25 2022-11-14 2022-08-30 2022-09-27 2022-12-21 2022-10-18 2023-01-26 2022-11-22 nvelope 2 t Cox's Bazar gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W14 / "Constructi Delivery of Basic Services, R ment Document - on of 7 RCC roads under Cox' Single Stage - One E Pending Imp 2024-06-2 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 1,695,276.00 0.00 2022-10-13 2022-10-18 2022-11-15 2022-11-29 2023-01-03 s Bazar District including culv nvelope lementation 6 gency Response, and Gende ss (Non Bank-SPD ert and drain r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W16 / Improveme Delivery of Basic Services, R ment Document - Single Stage - One E Under Imple 2024-06-1 nt of 4 roads roads under Co IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,127,962.00 0.00 2022-10-01 2023-03-09 2022-10-06 2022-11-03 2023-04-12 2022-11-17 2023-04-12 2022-12-22 nvelope mentation 4 x's Bazar District gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W17 / Improveme Delivery of Basic Services, R ment Document - Single Stage - One E 2024-04-2 nt of 5 roads roads under Co IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 1,118,103.00 0.00 Signed 2022-08-16 2022-08-10 2022-08-21 2022-09-18 2022-09-15 2022-10-02 2022-10-13 2022-11-06 nvelope 9 x's Bazar District gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) EMCRP/W12 / Rehabiltiation Component 1: Strengthening National Procure of 12 camp connecting roads Delivery of Basic Services, R ment Document - Single Stage - One E Pending Imp 2024-03-0 around/within forcibly displac IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 1,920,000.00 0.00 2022-11-01 2022-11-05 2022-12-10 2023-01-19 2023-03-02 nvelope lementation 1 ed Myanmar nations under C gency Response, and Gende ss (Non Bank-SPD ox's Bazar District r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W2 / Improvemen Delivery of Basic Services, R ment Document - t of Baro Junchari Rubber Da Single Stage - One E 2024-01-2 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 242,420.00 0.00 Signed 2022-11-06 2023-02-09 2022-11-11 2022-12-02 2023-03-06 2022-12-23 2023-03-13 2023-01-27 m in Ramu under Additional f nvelope 7 gency Response, and Gende ss (Non Bank-SPD inancing for EMCRP r-Based Viol ence Prevention ) EMCRP/AF/.W4 / Improveme Component 1: Strengthening National Procure nt of Gorokghata Jetty in Moh Delivery of Basic Services, R ment Document - Single Stage - One E Pending Imp 2024-06-2 eskhali Upazila & Darbarhat J IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 4,358,068.00 0.00 2022-12-15 2022-12-20 2023-01-10 2023-02-07 2023-02-23 nvelope lementation 2 etty in Kutubdia upazila in C gency Response, and Gende ss (Non Bank-SPD ox’s Bazar District r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/W10-A / Construction Delivery of Basic Services, R ment Document - of 03 nos new School cum Di Single Stage - One E Pending Imp 2024-06-0 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 1,766,780.00 0.00 2023-03-05 2023-03-10 2023-04-07 2023-05-05 2023-06-09 sater Shelter Building in Cox' nvelope lementation 8 gency Response, and Gende ss (Non Bank-SPD s Bazar District r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/W11-A / Construction Delivery of Basic Services, R ment Document - of 04 nos New School cum Di Single Stage - One E Pending Imp 2024-06-0 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,355,700.00 0.00 2023-03-05 2023-03-10 2023-04-07 2023-05-05 2023-06-09 saster Shelter Building in Cox nvelope lementation 8 gency Response, and Gende ss (Non Bank-SPD 's Bazar District. r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W1 / Improvemen Delivery of Basic Services, R ment Document - t of Joarianala Sonachari Rub Single Stage - One E Pending Imp 2024-03-0 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 191,500.00 0.00 2022-12-01 2022-12-06 2022-12-27 2023-01-24 2023-03-07 ber Dam at Ramu in Cox'sBa nvelope lementation 6 gency Response, and Gende ss (Non Bank-SPD zar District r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W3 / Improvemen Delivery of Basic Services, R ment Document - t of Monirjheel Sonachari Rub Single Stage - One E Pending Imp 2024-03-0 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 53,500.00 0.00 2022-12-01 2022-12-06 2022-12-27 2023-01-24 2023-03-07 ber Dam at Ramu in Cox's B nvelope lementation 6 gency Response, and Gende ss (Non Bank-SPD azar district. r-Based Viol ence Prevention ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthening EMCRP/G-04 / Procurement Delivery of Basic Services, R Single Stage - One E of 10000 + 1000 Liter water / esilient Infrastructure, Emer Post Request for Bids Open - National 2,408,000.00 0.00 Canceled 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-07-02 2019-04-21 2019-05-26 2019-09-23 nvelope tender for FSCD gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-05 / Procurement Delivery of Basic Services, R Single Stage - One E of Fire and Rescue Vehicle IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,744,000.00 2,654,506.42 Completed 2019-02-20 2019-05-28 2019-02-25 2019-03-12 2019-07-02 2019-04-21 2019-08-20 2019-05-26 2019-10-10 2019-09-23 2019-10-10 nvelope (medium) for FSCD gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-06 / Procurement Delivery of Basic Services, R of Towing Vehicle ( Pick up ty Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,974,000.00 3,014,898.23 Signed 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-07-02 2019-04-21 2019-07-09 2019-05-26 2019-10-10 2019-09-23 2019-10-10 pe with CAF and Water ) for F nvelope gency Response, and Gende SCD r-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-07 / Procurement Delivery of Basic Services, R Single Stage - One E of Fire Fighting portable pum IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 397,000.00 372,622.94 Completed 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-06-25 2019-04-21 2019-07-30 2019-05-26 2019-09-12 2019-09-23 2020-06-25 nvelope p ( Small) for FSCD gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-10 / Procurement Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 361,000.00 349,065.04 Completed 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-07-02 2019-04-21 2019-07-30 2019-05-26 2019-09-12 2019-09-23 2019-09-12 of Ambulance for FSCD nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-11 / Procurement Single Stage - One E / esilient Infrastructure, Emer Post Request for Bids Open - National 1,499,000.00 0.00 Canceled 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-07-02 2019-04-21 2019-05-26 2019-09-23 of Rescue Boat for FSCD nvelope gency Response, and Gende r-Based Viol ence Prevention Page 3 Component 1: Strengthening EMCRP/G-12 / Procurement Delivery of Basic Services, R Single Stage - One E of Fire Fighting Turn Table fo IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,746,000.00 0.00 Canceled 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-07-02 2019-04-21 2019-05-26 2019-09-23 nvelope r FSCD gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-08 / Procurement Delivery of Basic Services, R Single Stage - One E of Fire Service Command Ve IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 255,000.00 189,293.33 Completed 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-06-25 2019-04-21 2019-08-30 2019-05-26 2019-09-12 2019-09-23 2019-09-12 nvelope hicle for FSCD gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-01 / Procurement Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 81,000.00 0.00 Canceled 2019-07-01 2019-07-06 2019-07-21 2019-08-30 2019-10-11 2020-02-08 of Motorcycles nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-02 / Procurement Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,075,000.00 70,758.90 Signed 2019-07-10 2019-04-30 2019-07-15 2019-05-29 2019-07-30 2019-05-30 2019-09-08 2019-07-30 2019-10-20 2019-08-22 2020-04-17 of Solar Street Light nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-03 / Supply and in Delivery of Basic Services, R stallation of Early Steamer E Single Stage - One E / esilient Infrastructure, Emer Post Request for Bids Open - National 2,239,000.00 0.00 Canceled 2019-07-13 2019-07-18 2019-08-02 2019-09-11 2019-10-23 2020-04-20 mission Lightening Protection nvelope gency Response, and Gende System r-Based Viol ence Prevention EMCRP/G-03A / Supply and i Component 1: Strengthening nstallation of 90 nos. Early St Delivery of Basic Services, R Single Stage - One E eamer Emission Lightening P IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 537,314.00 411,717.06 Signed 2019-04-25 2019-04-30 2019-04-30 2019-05-29 2019-05-24 2019-05-30 2019-06-23 2019-07-11 2019-08-04 2019-07-31 2020-08-03 nvelope rotection System in Rohingya gency Response, and Gende Camps r-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-12A / Procurement Delivery of Basic Services, R Single Stage - One E of 1 no. Fire Fighting Turn Ta IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,746,000.00 1,638,365.11 Signed 2019-07-30 2019-10-28 2019-08-04 2019-08-24 2019-11-20 2019-10-03 2019-12-26 2019-11-07 2020-02-03 2020-05-05 nvelope ble for FSCD gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-04A / Procurement Delivery of Basic Services, R Single Stage - One E of 5 nos. 10000 +1000 Liter IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,408,000.00 2,350,486.60 Completed 2019-07-30 2019-07-27 2019-08-04 2019-08-24 2019-08-20 2019-10-03 2019-10-07 2019-11-07 2019-11-04 2020-05-05 2019-11-04 nvelope Water Tender gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-11A / Procurement Delivery of Basic Services, R Single Stage - One E of 6 nos. Rescue Boat for FSC IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,499,000.00 0.00 Canceled 2019-07-30 2019-09-03 2019-08-04 2019-08-24 2019-11-26 2019-10-03 2019-11-07 2020-05-05 nvelope D gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-1 / Procurement of IDA / D4190 esilient Infrastructure, Emer Post Direct Selection Direct 68,823.00 68,688.89 Completed 2020-06-07 2018-12-11 2020-06-12 2020-01-13 2020-07-19 2020-06-21 2020-10-17 2020-06-21 34 Motorcycle under EMCRP gency Response, and Gende r-Based Viol ence Prevention EMCRP/COVID19/G-22 / Proc Component 1: Strengthening urement of soap, hand saniti Delivery of Basic Services, R zer and disinfectant spray for IDA / D4190 esilient Infrastructure, Emer Post Direct Selection Direct 5,978.00 4,660.05 Completed 2020-05-27 2020-05-19 2020-05-30 2020-05-31 2020-07-04 2020-06-01 2020-07-19 2020-08-31 prevention of COVID-19 infec gency Response, and Gende tions in cyclone shelters in C r-Based Viol ence Prevention ox's Bazar District. Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-16 / Procurement Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 60,000.00 0.00 Canceled 2020-11-30 2020-12-04 2020-12-24 2021-01-14 2021-02-25 2021-04-26 of Stationery nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-11B / Procurement Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,499,000.00 0.00 Canceled 2020-10-15 2020-10-08 2020-10-18 2020-11-22 2021-01-04 2021-01-09 2021-02-20 2021-08-19 of 6 rescue boats for FSCD nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-09 / Procurement Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 255,000.00 0.00 Canceled 2020-08-15 2020-08-27 2020-08-20 2020-09-24 2020-09-21 2020-11-03 2020-10-05 2020-12-15 2021-06-28 of Command Vehicle nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-09_ / Procurement Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 255,000.00 187,462.92 Signed 2020-10-30 2020-10-21 2020-11-04 2020-11-22 2020-11-05 2020-12-07 2020-12-30 2021-01-11 2021-01-15 2021-07-10 of two command vehicles nvelope gency Response, and Gende r-Based Viol ence Prevention EMCRP/G-03B / Supply and I Component 1: Strengthening nstallation of 268 nos Early S Delivery of Basic Services, R Single Stage - One E teamer Emission Lightening IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,764,240.00 0.00 Canceled 2021-09-14 2021-12-16 2021-09-19 2021-10-17 2022-01-25 2021-11-07 2021-12-12 2022-12-12 nvelope Protection System in differen gency Response, and Gende t Rohingya camps r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/G-17 / Supply & In Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,766,485.00 0.00 Canceled 2021-12-12 2021-12-12 2021-12-16 2022-01-13 2022-01-25 2022-02-03 2022-03-10 2022-07-08 stallation of Solar Light nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-18 / Supply and Delivery of Basic Services, R Single Stage - One E Installation of Solar PV Nano IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,750,000.00 0.00 Canceled 2021-12-14 2022-01-18 2021-12-19 2022-01-16 2022-03-10 2022-02-06 2022-03-13 2022-12-08 nvelope Grid gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/G-07 / Supply of S Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 66,928.00 0.00 Canceled 2022-01-24 2022-01-26 2022-02-09 2022-02-23 2022-03-30 2022-07-28 preader nvelope gency Response, and Gende r-Based Viol ence Prevention Page 4 Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/G-08 / Supply of R Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 35,877.00 0.00 Canceled 2022-01-24 2022-01-26 2022-02-09 2022-02-23 2022-03-30 2022-07-28 am Jack nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-13 / Procurement Single Stage - One E Under Imple IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 6,000.00 0.00 2022-03-30 2022-06-08 2022-04-04 2022-04-19 2022-05-03 2022-06-14 2022-08-13 of Computer and accessories nvelope mentation gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-14 / Printers and P Single Stage - One E Under Imple IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 18,000.00 0.00 2022-03-30 2022-06-08 2022-04-04 2022-04-19 2022-05-03 2022-06-14 2022-08-13 hotocopy Machines nvelope mentation gency Response, and Gende r-Based Viol ence Prevention EMCRP/AF/G-03 / Supply of Component 1: Strengthening 08 nos Smoke Ejector, 08 no Delivery of Basic Services, R Single Stage - One E s Power chain saw, 04 nos P IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 167,255.00 0.00 Canceled 2022-01-24 2022-03-29 2022-01-26 2022-02-09 2022-04-21 2022-02-23 2022-03-30 2022-07-28 nvelope ower cutter, 08 nos Spreader gency Response, and Gende and 04 nos Ram Jack r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-01 / Supply of Delivery of Basic Services, R Single Stage - One E Water Vehicle, Toying Vehicl IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,521,320.00 1,226,172.26 Signed 2022-04-03 2022-03-27 2022-04-03 2022-05-01 2022-04-28 2022-05-15 2022-07-17 2022-06-19 2022-09-09 2022-10-17 nvelope e and Portable Pump gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-02 / Supply of Delivery of Basic Services, R Delivery hose, Hand control Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 59,835.00 0.00 Canceled 2022-04-03 2022-03-29 2022-04-05 2022-04-19 2022-04-21 2022-05-03 2022-06-07 2022-10-05 branch pipe and Foam makin nvelope gency Response, and Gende g branch pipe r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-04 / Supply of B Delivery of Basic Services, R reathing apparatus, Diving a Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 270,906.00 0.00 Canceled 2022-04-03 2022-03-28 2022-04-05 2022-04-19 2022-04-24 2022-05-03 2022-06-07 2022-10-05 pparatus, Heat protective sui nvelope gency Response, and Gende t and Fireman suit r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-05 / Supply of Delivery of Basic Services, R Single Stage - One E Gas detector, Stretcher and IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 86,925.00 0.00 Canceled 2022-04-03 2022-03-28 2022-04-05 2022-04-19 2022-04-21 2022-05-03 2022-05-31 2022-09-28 nvelope Extension ladder gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/G-06 / Supply of T Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 65,960.00 0.00 Canceled 2022-04-03 2022-03-28 2022-04-05 2022-04-26 2022-04-21 2022-05-10 2022-06-14 2022-10-12 hermal Imaging Camera nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/G-09 / Supply of L Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 200,000.00 0.00 Canceled 2022-04-03 2022-03-28 2022-04-05 2022-04-19 2022-04-21 2022-05-03 2022-06-06 2022-10-04 ife detecting device nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/G-10 / Supply of Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 23,887.00 0.00 Canceled 2022-04-03 2022-03-28 2022-04-05 2022-04-19 2022-04-21 2022-05-03 2022-06-07 2022-10-05 Helmet nvelope gency Response, and Gende r-Based Viol ence Prevention EMCRP/G-03B. / Supply and I Component 1: Strengthening nstallation of 268 Nos. Early Delivery of Basic Services, R Streamer Emission Lightning Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Prior Request for Bids Open - National 1,764,240.00 0.00 Canceled 2022-04-05 2022-05-24 2022-04-08 2022-06-05 2022-04-29 2022-07-19 2022-05-20 2022-10-18 2022-06-24 2023-03-21 Protection System at differen nvelope gency Response, and Gende t Rohingya camps under Ukhi r-Based Viol ence Prevention ya & Teknaf Upazila in Cox's Bazar district under EMCRP EMCRP/AF/G-17. / Supply an Component 1: Strengthening d Installation of 2500 sets Sol Delivery of Basic Services, R Single Stage - One E ar Street Light at different Ro IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,766,485.00 0.00 Canceled 2022-04-05 2022-04-18 2022-04-08 2022-04-29 2022-05-11 2022-05-20 2022-06-24 2022-10-22 nvelope hingya camps under Ukhiya gency Response, and Gende & Teknaf Upazila in Cox’s Ba r-Based Viol ence Prevention zar District Component 1: Strengthening EMCRP/AF/G-18. / Supply an Delivery of Basic Services, R Single Stage - One E d installation of Solar PV Nan IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,750,000.00 0.00 Signed 2022-06-19 2022-06-07 2022-06-24 2022-07-21 2022-06-30 2022-08-11 2022-08-21 2022-09-22 2023-06-19 nvelope o Grid gency Response, and Gende r-Based Viol ence Prevention EMCRP/AF/.G-17 / Supply an Component 1: Strengthening d Installation of 2500 set Sol Delivery of Basic Services, R Single Stage - One E ar Street Light at different Ro IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,766,485.00 0.00 Signed 2022-08-07 2022-08-22 2022-08-12 2022-09-02 2022-09-15 2022-09-30 2023-01-01 2022-11-11 2023-08-08 nvelope hingya camps under Ukhia & gency Response, and Gende Teknaf Upazila in Coxs Bazar r-Based Viol ence Prevention District . Component 1: Strengthening EMCRP/AF/.G-02 / Supply of Delivery of Basic Services, R Delivery Hose, Hand Control Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 59,835.00 0.00 Signed 2022-08-07 2022-08-22 2022-08-12 2022-09-02 2022-09-12 2022-09-23 2023-01-03 2022-11-04 2023-03-04 Branch Pipe and Foam Makin nvelope gency Response, and Gende g Branch Pipe r-Based Viol ence Prevention EMCRP/AF/.G-03 / Supply of Component 1: Strengthening 8 Nos Ejector, 8 Nos Power C Delivery of Basic Services, R Single Stage - One E hain Saw, 4 Nos Hydraulic Po IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 167,255.00 0.00 Signed 2022-08-07 2022-08-22 2022-08-12 2022-09-02 2022-09-12 2022-09-23 2023-01-05 2022-11-04 2023-03-04 nvelope wer Cutter, 8 Nos Hydraulic S gency Response, and Gende preader and 4 Nos Ram Jack r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/.G-04 / Supply of Delivery of Basic Services, R Breathing Apparatus, Diving Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 270,906.00 0.00 Signed 2022-08-07 2022-08-22 2022-08-12 2022-09-02 2022-09-12 2022-09-04 2023-01-03 2022-10-16 2023-02-13 Apparatus, Heat Protective s nvelope gency Response, and Gende uit and Fireman suit r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/.G-05 / Supply of Delivery of Basic Services, R Single Stage - One E Gas Detector, Stretcher and IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 86,925.00 0.00 Signed 2022-08-07 2022-08-22 2022-08-12 2022-09-02 2022-09-12 2022-09-23 2023-01-05 2022-11-04 2023-03-04 nvelope Extension Ladder, gency Response, and Gende r-Based Viol ence Prevention Page 5 Component 1: Strengthening EMCRP/AF/.G-06 / Supply of Delivery of Basic Services, R Single Stage - One E Thermal Imaging Camera (TI IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 65,960.00 0.00 Canceled 2022-08-07 2022-08-22 2022-08-12 2022-09-02 2022-09-12 2022-09-23 2022-11-04 2023-03-04 nvelope C) gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/.G-09 / Supply of Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 200,000.00 0.00 Signed 2022-08-07 2022-08-22 2022-08-12 2022-09-02 2022-09-12 2022-09-23 2023-01-01 2022-11-04 2023-03-04 Life Detecting Device nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/.G-10 / Supply of Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 23,687.00 0.00 Signed 2022-08-07 2022-08-22 2022-08-12 2022-09-02 2022-09-12 2022-09-23 2023-01-03 2022-11-04 2023-03-04 Helmet nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-11 / Supply and Delivery of Basic Services, R Installation of Emergency Op Open - Internationa Single Stage - One E Pending Impl IDA / D5900 esilient Infrastructure, Emer Prior Request for Bids 4,000,000.00 0.00 2022-12-01 2022-12-11 2023-01-22 2023-02-21 2023-04-04 2023-10-01 eration System for Fire Servi l nvelope ementation gency Response, and Gende ce Civil Defense r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/G-12 / ICT Equipm Single Stage - One E Pending Impl IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 353,357.00 0.00 2023-01-01 2023-01-06 2023-01-27 2023-02-10 2023-03-17 2023-07-15 ent for LGED Training Facility nvelope ementation gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-15 / Supply & In Delivery of Basic Services, R stallation of 300 nos of Early Single Stage - One E Under Imple IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,413,427.00 0.00 2022-09-15 2023-01-15 2022-09-20 2022-10-18 2023-02-23 2022-11-08 2022-12-13 2023-08-10 Steamer Emission Lightening nvelope mentation gency Response, and Gende Protection System r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-16 / Supply & In Delivery of Basic Services, R stallation of 300 nos of Earl Single Stage - One E Pending Impl IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,413,427.00 0.00 2022-12-15 2022-12-20 2023-01-17 2023-02-07 2023-03-14 2023-11-09 y Steamer Emission Lighteni nvelope ementation gency Response, and Gende ng Protection System r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-19 / Supply and Delivery of Basic Services, R Single Stage - One E Installation of Solar PV Nano IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,750,000.00 0.00 Signed 2022-09-15 2022-11-16 2022-09-20 2022-10-18 2022-12-21 2022-11-08 2023-01-18 2022-12-13 2023-09-09 nvelope Grid gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-20 / Supply and Delivery of Basic Services, R Single Stage - One E Pending Impl Installation of Solar PV Nano IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,500,000.00 0.00 2022-11-15 2022-11-20 2022-12-18 2023-01-08 2023-02-12 2023-11-09 nvelope ementation Grid gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-15 / Office Furnitur Single Stage - One E Pending Impl IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 12,000.00 0.00 2023-03-01 2023-03-06 2023-03-21 2023-04-04 2023-05-16 2023-07-15 e nvelope ementation gency Response, and Gende r-Based Viol ence Prevention EMCRP/ G-03B / Supply and I Component 1: Strengthening nstallation of 268 nos Early S Delivery of Basic Services, R teamer Emission Lightning Pr Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,764,240.00 0.00 Signed 2022-11-10 2022-11-13 2022-11-15 2022-12-13 2022-12-07 2023-01-10 2023-01-10 2023-02-14 2023-11-11 otection System at different nvelope gency Response, and Gende Rohingya Camps under Ukhiy r-Based Viol ence Prevention a & Teknaf Upazila in Cox's B azar under EMCRP Component 1: Strengthening EMCRP/AF/ G-06 / Supply of Delivery of Basic Services, R Single Stage - One E Under Imple Thermal Imaging Camera (TI IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 65,960.00 0.00 2023-02-22 2023-03-01 2023-02-25 2023-03-11 2023-03-20 2023-03-25 2023-04-29 2023-08-27 nvelope mentation C) gency Response, and Gende r-Based Viol ence Prevention EMCRP./G-11A / Supply of Fir Component 1: Strengthening e Rescue Command Tender ( Delivery of Basic Services, R Single Stage - One E Pending Impl Heavy), Fire Rescue Comman IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,611,940.00 0.00 2023-04-30 2023-05-05 2023-06-02 2023-06-23 2023-07-28 2023-11-25 nvelope ementation d Tender (medium), Fire Res gency Response, and Gende cue Command Tender (light), r-Based Viol ence Prevention Portable Fire Pump NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthening EMCRP/GBV/S2 / Gender Bas Delivery of Basic Services, R UN Agencies (Dire ed Violance Management Fir IDA / D4190 esilient Infrastructure, Emer Prior Direct 8,480,000.00 7,999,951.00 Signed 2019-08-01 2019-07-11 2019-08-06 2019-10-16 2019-10-07 2019-11-17 2021-11-30 ct) m gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/NS-01 / Transport re Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 180,000.00 159,525.23 Signed 2019-06-01 2019-11-28 2019-06-06 2019-07-06 2020-01-02 2019-08-05 2020-01-15 2019-09-16 2020-02-05 2022-02-01 ntal expenses nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/NS-01 / Transport Delivery of Basic Services, R Single Stage - One E Rental Services ( Hiring of ve IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 294,460.00 0.00 Canceled 2021-12-05 2021-12-10 2021-12-24 2022-01-03 2022-01-31 2024-01-31 nvelope hicles ) gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/NS-01. / Transpor Delivery of Basic Services, R t Rental Services (Hiring of V IDA / D5900 esilient Infrastructure, Emer Post Direct Selection Direct 294,460.00 287,585.97 Signed 2022-01-05 2022-01-09 2022-01-10 2022-01-12 2022-01-30 2022-01-28 2024-06-30 ehicles) gency Response, and Gende r-Based Viol ence Prevention CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 6 Component 1: Strengthening EMCRP/ME/S2 / Monitoring a Delivery of Basic Services, R Consultant Qualifi nd Evaluation Consultancy S IDA / D4190 esilient Infrastructure, Emer Post Open - National 480,000.00 621,765.16 Signed 2019-02-13 2019-05-23 2019-03-06 2019-05-22 2019-04-19 2019-08-19 2019-05-19 2019-12-10 2019-06-30 2019-12-16 2021-12-16 cation Selection ervices gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/CIA/S3 / Cumulative I Delivery of Basic Services, R Consultant Qualifi mpact Assessment Consultan IDA / D4190 esilient Infrastructure, Emer Post Open - National 490,000.00 483,492.42 Signed 2019-02-13 2019-06-15 2019-03-06 2019-07-17 2019-04-19 2019-12-31 2019-05-19 2020-01-29 2019-06-30 2020-03-04 2020-03-26 cation Selection cy Services gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/CA/S5 / Communicati Delivery of Basic Services, R Consultant Qualifi on and Awareness Consultan IDA / D4190 esilient Infrastructure, Emer Post Open - National 360,000.00 353,785.40 Signed 2019-02-13 2019-06-15 2019-03-06 2019-07-17 2019-04-19 2019-10-28 2019-05-19 2020-01-29 2019-06-30 2020-03-06 2021-12-16 cation Selection cy Services gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/FS/S7 / Consultan Delivery of Basic Services, R cy Services for Feasibility Stu Quality And Cost- Open - Internationa IDA / D4190 esilient Infrastructure, Emer Prior 3,396,000.00 2,429,875.88 Signed 2020-09-15 2020-09-15 2020-10-15 2020-09-17 2020-12-28 2021-04-27 2021-01-27 2021-03-02 2021-03-28 2021-05-10 2021-05-11 2021-07-27 2021-06-22 2021-09-08 2022-02-17 dy of Resilient Infrastructure Based Selection l gency Response, and Gende Development Project (RIDP) r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/IA/S4 / Appointment Consultant Qualifi IDA / D4190 esilient Infrastructure, Emer Post Open - National 20,000.00 0.00 Canceled 2022-11-01 2022-08-25 2022-11-22 2023-01-01 2023-01-31 2023-03-14 2023-06-12 of Internal Audit Firm cation Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/IA/.S4 / Selection of I Consultant Qualifi Under Implement IDA / D4190 esilient Infrastructure, Emer Post Limited 20,000.00 0.00 2022-11-10 2022-11-02 2022-11-17 2022-12-08 2023-01-05 2023-03-06 nternal Audit firm cation Selection ation gency Response, and Gende r-Based Viol ence Prevention INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthening EMCRP/DS/S1 / Design and S Delivery of Basic Services, R upervision Consultancy Servi IDA / D4190 esilient Infrastructure, Emer Prior Direct Selection Direct 1,650,000.00 1,616,870.20 Signed 2019-02-13 2019-05-23 2019-02-23 2019-05-05 2019-04-19 2019-10-23 2022-01-31 ce for EMCRP gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/SPS/S2 / Senior Proc Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Limited 240,000.00 205,711.06 Signed 2019-03-25 2019-05-01 2019-04-04 2019-05-01 2019-04-25 2019-06-16 2019-06-06 2019-06-27 2022-02-15 urement Specialist ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/SDS/S4 / Social Deve Individual Consult / esilient Infrastructure, Emer Post Limited 70,000.00 59,102.76 Signed 2019-04-10 2019-05-01 2019-04-20 2019-05-03 2019-05-11 2019-05-26 2019-06-22 2019-06-30 2021-11-30 lopment Specialist ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/FSDS/S5 / Field Level Delivery of Basic Services, R Individual Consult Social Development Speciali IDA / D4190 esilient Infrastructure, Emer Post Limited 50,000.00 41,100.11 Signed 2019-07-30 2020-01-23 2019-08-09 2020-02-04 2019-08-30 2019-06-10 2019-10-11 2020-03-25 2021-11-30 ant Selection st gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/FENS/S7 / Field Level Individual Consult / esilient Infrastructure, Emer Post Limited 50,000.00 39,629.07 Signed 2019-08-01 2019-05-01 2019-08-11 2019-05-03 2019-09-01 2019-05-26 2019-10-13 2019-06-30 2021-11-30 Environment Specialist ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/GS/S8 / Gender Speci Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Limited 60,000.00 70,941.25 Signed 2019-08-25 2019-08-01 2019-09-04 2019-09-05 2019-09-25 2019-10-20 2019-11-06 2019-10-20 2021-11-30 alist ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/CS/S10 / Communica Individual Consult / esilient Infrastructure, Emer Post Limited 60,000.00 30,034.25 Signed 2019-06-01 2019-05-01 2019-06-11 2019-05-03 2019-07-02 2019-05-26 2019-08-13 2019-06-30 2021-11-30 tion Specialist ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/DCCS/S11 / Disaster Individual Consult / esilient Infrastructure, Emer Post Limited 40,000.00 34,796.15 Signed 2019-05-01 2019-05-01 2019-05-11 2019-05-03 2019-06-01 2019-05-26 2019-07-13 2019-06-30 2021-11-30 & Climate Change Specialis ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/IPP/INT-1/S12 / Procu Delivery of Basic Services, R Individual Consult rement Panel International M IDA / D4190 esilient Infrastructure, Emer Post Direct 80,000.00 80,190.00 Completed 2019-04-01 2019-05-01 2019-04-11 2019-05-03 2019-05-02 2019-05-18 2019-06-06 2019-04-30 2019-12-03 2021-01-20 ant Selection ember-1 gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/IPP/NAT-1/S14 / Proc Delivery of Basic Services, R Individual Consult urement Panel National Mem IDA / D4190 esilient Infrastructure, Emer Post Direct 20,000.00 18,246.05 Completed 2019-04-01 2019-05-01 2019-04-11 2019-05-03 2019-05-02 2019-05-20 2019-06-06 2019-04-30 2019-12-03 2021-01-20 ant Selection ber-3 gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/GISE/S15 / GIS Exper Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Limited 40,000.00 58,380.21 Signed 2019-08-30 2019-05-30 2019-09-09 2019-06-11 2019-09-30 2019-08-20 2019-11-11 2019-10-20 2021-10-31 t ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/MIS/S5A / Individual Delivery of Basic Services, R Consultancy Services of a MI Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Direct 1,176.00 12,657.94 Signed 2020-02-16 2020-01-15 2020-02-26 2020-02-04 2020-03-02 2020-03-15 2020-04-06 2020-03-30 2020-10-03 S Specialist for RAP Preparati ant Selection gency Response, and Gende on r-Based Viol ence Prevention Page 7 Component 1: Strengthening EMCRP/IPP/NAT-1/S14A / Me Delivery of Basic Services, R mber, National of 2-member I Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Direct 28,236.00 25,014.58 Completed 2020-03-01 2020-01-20 2020-03-09 2020-02-02 2020-03-14 2020-03-01 2020-03-24 2020-03-05 2020-05-28 2021-02-10 ndependent Procurement Pa ant Selection gency Response, and Gende nel r-Based Viol ence Prevention Component 1: Strengthening EMCRP/IPP/INT-1/12A / Chair Delivery of Basic Services, R man, 2-member Procurement Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Direct 120,565.00 120,565.00 Completed 2020-03-01 2020-01-20 2020-03-09 2020-02-02 2020-03-14 2020-03-01 2020-03-24 2020-03-05 2020-05-28 2021-02-10 Panel Expert, International E ant Selection gency Response, and Gende xpert r-Based Viol ence Prevention Component 1: Strengthening EMCRP/STS/S1 / Senior Proje Delivery of Basic Services, R Individual Consult ct Management Specialist/Se IDA / D4190 esilient Infrastructure, Emer Post Limited 240,000.00 0.00 Canceled 2020-11-07 2020-11-12 2020-11-26 2021-01-07 2023-02-25 ant Selection nior Technical Specialist gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/FGS/S9 / Field Level Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Limited 50,000.00 0.00 Canceled 2020-08-10 2020-08-12 2020-08-26 2020-10-07 2022-10-27 Gender Specialist ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/SENS/S6 / Senior Env Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Limited 70,000.00 0.00 Canceled 2020-08-25 2020-08-31 2020-09-21 2020-11-02 2023-01-27 ironment Specialist ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/SFMS/S3 / Senior Fin Delivery of Basic Services, R Individual Consult ancial Management Specialis IDA / D4190 esilient Infrastructure, Emer Post Limited 170,000.00 0.00 Canceled 2020-07-30 2021-01-19 2020-08-02 2020-08-16 2020-09-20 2023-03-10 ant Selection t gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/ICT/INT/S17 / Indi Delivery of Basic Services, R Individual Consult vidual Consultancy Services f IDA / D4190 esilient Infrastructure, Emer Post Limited 200,720.00 0.00 Canceled 2020-09-25 2020-09-28 2020-10-19 2020-11-16 2022-11-06 ant Selection or ICT Specialist International gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/ICT/S18 / Individu Delivery of Basic Services, R Individual Consult al Consultancy Services for I IDA / D4190 esilient Infrastructure, Emer Post Limited 72,000.00 0.00 Canceled 2020-09-25 2020-09-28 2020-10-19 2020-11-16 2022-11-06 ant Selection CT Specialist-Local gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/ES/S16 / Consulta Delivery of Basic Services, R Individual Consult ncy Services for Energy Speci IDA / D4190 esilient Infrastructure, Emer Post Limited 65,000.00 0.00 Canceled 2021-03-15 2021-02-10 2021-03-20 2021-04-04 2021-04-26 2023-10-13 ant Selection alist (Individual Consultant) gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/D&S/S1 / Design Delivery of Basic Services, R and Supervision Consulting S IDA / D4190 esilient Infrastructure, Emer Prior Direct Selection Direct 2,356,000.00 0.00 Canceled 2021-02-15 2021-02-25 2021-05-01 2024-01-16 ervices of EMCRP under addit gency Response, and Gende ional financing. r-Based Viol ence Prevention Component 1: Strengthening EMCRP/SPS/S2A / Individual Delivery of Basic Services, R Individual Consult Consultancy Services for Seni IDA / D4190 esilient Infrastructure, Emer Post Limited 76,900.00 95,579.82 Signed 2021-02-28 2021-02-22 2021-03-03 2021-03-15 2021-03-18 2021-03-22 2021-04-22 2021-05-04 2023-04-22 ant Selection or Procurement Specialist gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/ES/S16. / Consult Delivery of Basic Services, R ancy Services for Energy Spe Individual Consult IDA / D5900 esilient Infrastructure, Emer Post Limited 65,000.00 64,294.41 Signed 2021-09-01 2021-09-01 2021-09-06 2021-09-06 2021-09-20 2021-09-22 2021-10-18 2021-09-27 2024-04-15 cialist (Individual Consultant) ant Selection gency Response, and Gende . r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/ICT/INT./S17 / Con Delivery of Basic Services, R sultancy Services for Internat Individual Consult Under Implement IDA / D5900 esilient Infrastructure, Emer Post Limited 198,000.00 0.00 2021-10-05 2021-10-18 2021-10-13 2021-11-18 2021-12-31 2024-01-01 ional ICT Specialist (Individua ant Selection ation gency Response, and Gende l Consultant). r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/ICT/S18. / Consult Delivery of Basic Services, R Individual Consult Under Implement ancy Services for ICT Speciali IDA / D5900 esilient Infrastructure, Emer Post Limited 70,700.00 0.00 2021-10-05 2021-10-03 2021-10-10 2021-10-31 2021-12-02 2023-12-01 ant Selection ation st (Individual Consultant). gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/D&S./S1 / Design Delivery of Basic Services, R & Supervision Consulting Ser IDA / D4190 esilient Infrastructure, Emer Prior Direct Selection Direct 2,356,000.00 2,206,757.23 Signed 2021-11-02 2021-12-09 2021-11-10 2021-12-12 2021-12-23 2022-03-21 2024-06-30 vices of EMCRP under additio gency Response, and Gende nal financing r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/FS/S19 / Consulta Delivery of Basic Services, R Individual Consult ncy services for Forestry Spe IDA / D5900 esilient Infrastructure, Emer Post Limited 55,000.00 53,231.55 Signed 2021-11-14 2021-12-26 2021-11-19 2021-12-27 2021-12-03 2022-01-26 2021-12-31 2022-01-31 2023-12-31 ant Selection cialist (Individual Consultant) gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/M&E./S2 / Monitor Delivery of Basic Services, R ing and Evaluation Consultan IDA / D5900 esilient Infrastructure, Emer Post Direct Selection Direct 824,450.00 803,590.77 Signed 2021-12-08 2021-12-13 2021-12-18 2021-12-22 2022-01-30 2022-01-20 2024-05-29 t gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/SDS/S4 / Individu Delivery of Basic Services, R al Consultancy services for S Individual Consult IDA / D5900 esilient Infrastructure, Emer Post Direct 57,300.00 56,805.01 Signed 2021-12-05 2021-12-09 2021-12-13 2021-12-27 2021-12-18 2021-12-28 2021-12-30 2021-12-30 2023-12-30 enior Social Development Sp ant Selection gency Response, and Gende ecialist r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/FENS/S7 / Individ Delivery of Basic Services, R Individual Consult ual Consultancy services for IDA / D5900 esilient Infrastructure, Emer Post Direct 38,700.00 38,208.68 Signed 2021-12-05 2021-12-09 2021-12-13 2022-01-02 2021-12-18 2022-01-03 2021-12-30 2022-01-04 2023-12-30 ant Selection Environment Specialist gency Response, and Gende r-Based Viol ence Prevention Page 8 Component 1: Strengthening EMCRP/AF/GS/S8 / Individual Delivery of Basic Services, R Individual Consult Consultancy services for Gen IDA / D5900 esilient Infrastructure, Emer Post Direct 77,550.00 70,056.04 Signed 2021-12-05 2021-12-09 2021-12-13 2021-12-27 2021-12-18 2021-12-28 2021-12-30 2021-12-30 2023-12-30 ant Selection der Specialist gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/GIS/S15 / Individu Delivery of Basic Services, R Individual Consult al Consultancy services for GI IDA / D5900 esilient Infrastructure, Emer Post Direct 63,825.00 58,059.06 Signed 2021-12-05 2021-12-09 2021-12-13 2021-12-23 2021-12-18 2021-12-28 2021-12-30 2021-12-30 2023-12-30 ant Selection S Expert gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/IPP/INT-1/S12 / Co Delivery of Basic Services, R nsultancy Services of Procure Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Direct 86,000.00 0.00 Canceled 2021-02-28 2021-03-06 2021-03-13 2021-03-27 2021-05-26 ment Panel Member (Internat ant Selection gency Response, and Gende ional) r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/IPP/NAT-1/S14 / C Delivery of Basic Services, R onsultancy Services of Procur Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Direct 25,000.00 0.00 Canceled 2021-02-28 2021-03-06 2021-03-13 2021-03-27 2021-05-26 ement Panel Member (Nation ant Selection gency Response, and Gende al) r-Based Viol ence Prevention EMCRP/AF/M&E/S2 / Consulti Component 1: Strengthening ng Services for Monitoring a Delivery of Basic Services, R nd Evaluation under EMCRP- IDA / D4190 esilient Infrastructure, Emer Post Direct Selection Direct 857,500.00 0.00 Canceled 2021-02-15 2021-02-25 2021-05-01 2024-01-16 AF under additional Financin gency Response, and Gende g. r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/CS/S10.A / Individ Delivery of Basic Services, R Individual Consult ual Consultancy services for IDA / D5900 esilient Infrastructure, Emer Post Direct 28,430.00 28,069.68 Signed 2021-12-05 2021-12-09 2021-12-13 2021-12-23 2021-12-18 2021-12-28 2021-12-30 2021-12-30 2023-12-30 ant Selection Communication Specialist gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/SFMS/S3 / Individ Delivery of Basic Services, R ual Consultancy services for Individual Consult IDA / D5900 esilient Infrastructure, Emer Post Limited 109,620.00 0.00 Signed 2022-05-10 2022-08-25 2022-05-20 2022-08-11 2022-06-10 2022-09-11 2022-07-01 2024-06-30 Senior Financial Management ant Selection gency Response, and Gende Specialist r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/CA./S5 / Communi Delivery of Basic Services, R cation and Awareness Consul IDA / D5900 esilient Infrastructure, Emer Post Direct Selection Direct - National 505,300.00 0.00 Signed 2022-09-15 2022-10-23 2022-09-25 2022-12-27 2022-11-29 2024-06-17 tant gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/IPP./NAT-1/S14 / C Delivery of Basic Services, R onsultancy services for Procu Pending Impleme IDA / D5900 esilient Infrastructure, Emer Post Direct Selection Direct - National 17,000.00 0.00 2022-10-01 2022-10-11 2022-11-25 2023-11-25 rement Panel Member (Natio ntation gency Response, and Gende nal) r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/IPP./INT-1./S12 / C Delivery of Basic Services, R onsultancy services for Procu Direct - Internation Pending Impleme IDA / D5900 esilient Infrastructure, Emer Post Direct Selection 57,500.00 0.00 2022-10-01 2022-10-11 2022-11-19 2023-11-19 rement Panel Member (Intern al ntation gency Response, and Gende ational) r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/SRRD/S10 / Senio Individual Consult Pending Impleme IDA / D5900 esilient Infrastructure, Emer Post Limited 34,500.00 0.00 2022-10-20 2022-10-25 2022-11-15 2022-12-20 2023-08-17 r Engineer (Rubber Dam) ant Selection ntation gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/STS./S1 / Senior Proj Delivery of Basic Services, R Individual Consult ect Management/Senior Tech IDA / D4190 esilient Infrastructure, Emer Post Limited 71,650.00 0.00 Signed 2022-10-20 2022-11-02 2022-10-25 2022-11-17 2022-11-15 2022-11-27 2022-12-27 2023-12-27 ant Selection nical Specialist gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/SPS/S2 / Selection IDA / D5900 esilient Infrastructure, Emer Prior Direct Selection Direct - National 28,000.00 0.00 Canceled 2023-02-19 2023-03-08 2023-02-25 2023-04-02 2023-04-16 2023-10-13 of Sr. Procurement Specialist gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/CA/S5 / Communi Delivery of Basic Services, R cation and Awareness consul IDA / D5900 esilient Infrastructure, Emer Post Direct Selection Direct 505,300.00 0.00 Canceled 2022-06-01 2022-06-11 2022-07-18 2024-07-17 tant gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/IPP/INT-1./S12 / C Delivery of Basic Services, R onsultancy services for Procu Individual Consult IDA / D5900 esilient Infrastructure, Emer Post Direct 57,500.00 0.00 Canceled 2022-01-09 2022-01-19 2022-02-09 2022-03-09 2023-03-09 rement Panel Member (Intern ant Selection gency Response, and Gende ational) r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/IPP/NAT-1./S14 / C Delivery of Basic Services, R onsultancy services for Procu Individual Consult IDA / D5900 esilient Infrastructure, Emer Post Direct 17,000.00 0.00 Canceled 2022-01-09 2022-01-19 2022-02-09 2022-03-09 2023-03-09 rement Panel Member (Natio ant Selection gency Response, and Gende nal) r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF./SPS/S2 / Individu Delivery of Basic Services, R Individual Consult Under Implement al Consulting Services as a 'S IDA / D5900 esilient Infrastructure, Emer Prior Limited 57,500.00 0.00 2023-05-18 2023-05-31 2023-05-21 2023-06-07 2023-06-04 2023-06-22 2023-06-30 2024-06-30 ant Selection ation enior Procurement Specialist' gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/SERC/S20 / Indivi Delivery of Basic Services, R dual Consulting Services as a Individual Consult Pending Impleme IDA / D5900 esilient Infrastructure, Emer Post Limited 35,300.00 0.00 2023-05-15 2023-05-20 2023-06-03 2023-06-18 2025-07-18 'Senior Emergency Response ant Selection ntation gency Response, and Gende Specialist' r-Based Viol ence Prevention Page 9 PROCUREMENT PLAN Project information: Lao PDR: Health and Nutrition Service Access Project (HANSA) Project Implementation agency: Department of Planning and Cooperation, Ministry of Health Date of the Procurement Plan: January 7, 2020 Period covered by this Procurement Plan: at least 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Law and the Instruction on Implementation Public Procurement Law, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. a) The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; b) Information related to award of contract including reasons for rejection of unsuccessful bidders shall be published on the implementing agency websites and/or newspaper of wide circulation. c) All complaints on procurement related matters including complaints arising from procurement under Bank financed Projects whilst using National Procurement Procedures shall be dealt with in accordance with Article 46 of the Public Procurement Law. Borrower shall put in place an effective complaints review mechanism for dealing with procurement related complaints, and shall disclose the details in all 1 the bidding documents. All complaints shall be recorded by the Borrower in the appropriate tracking and monitoring system, as agreed between the Bank and the Borrower. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information. I. Works and Goods and Non-Consultant Services 1.1.Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Annex II of the Procurement Regulations: Procurement Method Prior Review Thresholds Thresholds Category Applicable Applicable thresholds Remarks thresholds Remarks (in US$) (in US$) Works RFB through ≥ 2.0 million – ≥ 15 million This has not been Open foreseen at the International project preparation market stage. approach RFB through ≥ 200,000 - < – None - Open National 2.0 million market approach Request for < 200,000 – None – Quotation Direct Selection None No threshold; Same as for This has not been meet competitive foreseen at the requirements of selection project preparation regulations stage. 7.13-7.15 Goods and Non-Consulting Services 2 RFB through ≥ 0.6 million – ≥ 4 million This has not been Open foreseen at the International project preparation market stage. approach RFB through ≥ 100,000 - < - None Risk-based approach Open National 0.6 million market approach Request for < 100,000 None Quotation Direct Selection None No threshold; Same as for This has not been meet competitive foreseen at the requirements of selection project preparation regulations stage. 7.13-7.15 1.2 Procurement packages for Works, Goods and Non- Consulting Services (prior and post reviews) with method and Time Schedule Ref. Contract Estimat Procurem Revi Expect Comment No. ed Cost ent ew ed s (Descriptio (US$) Method by Contra n) Bank ct Signin g (Prio Date r/ Post) Component 3: Adaptive Learning and Project Management: C3/G/0 Extension 80,000 DS Post 4-Jan- Continuati 1 contract for 21 on. Maintain Competitiv internet e selection connectivity under HGNDP C3/G/0 Procurement 99,600 RFQ Post 25-Jan- 2 of Tablets 21 Total Works and 179,60 Goods 0 Notes: DS: Direct Selection RFQ: Request for Quotations II. Selection of Consultants 2.1 Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Annex II of the Procurement Regulations: 3 Procurement Method Thresholds Prior Review Thresholds Applicable Applicable Category thresholds Remarks thresholds Remarks (in US$) (in US$) QCBS, QBS, ≥ 300,000 Methods for consulting ≥ 4.0 million Risk-based FBS, LCS (Using services are specified approach the most in paragraph 7.3 to appropriate 7.12, Section VII of the market Procurement approach) Regulations. CQS (Open or < 300,000 QCBS, QBS, FBS, LCS) None limited can be applied for competition contracts with value through national under US$300,000 or international market approach, specified in the PP and agreed with the Bank. Direct Selection None No threshold; meet Same as for This has not of firms requirements of competitive been foreseen regulations 7.13-7.15 selection at the project preparation stage. Individual N/A Essential individual ≥ 400,000 and Risk-based Consultants depending on assignments will be for the positions approach nature of defined in the as specified in services Procurement Plan the PP agreed agreed with the Bank with the Bank and in line with regulations 7.34-7.39 using the most appropriate market approach 2.2 Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$ 200,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 7.1, Section VII of the Procurement Regulations. 2.3 Consultancy Assignments with Selection Methods and Time Schedule Ref. No. Description of Estimat Revie Expected Selecti Comments Assignment ed Cost w by on Proposal (US$) Bank Metho s (Prior / Submissi d Post) on Date Component 3: Adaptive Learning and Project Management: C3/DS/01 Extension of 500,000 DS Post 4-Jan-21 Continuatio contract for n. Supporting the Competitiv Operation and e selection Management of 4 Ref. No. Description of Estimat Selecti Revie Expected Comments Assignment ed Cost on w by Proposal (US$) Metho Bank s d (Prior / Submissi Post) on Date HMIS and under DHIS2 HGNDP C3/CQS/01 Independence 700,000 QCBS Post 30-Mar-21 verification on QPS and DLI C3/DS/02 Project 40,000 DS Post 4-Jan-21 Financial Statements Audit C3/IC/01 Project 30,000 IC Post 4-Jan-21 Manager C3/IC/02 Assistant to 24,000 IC Post 4-Jan-21 Project Director for comp. 1&2 C3/IC/03 Assistant to 24,000 IC Post 4-Jan-21 Project Director for comp. 3&4 C3/DS/03 Procurement 24,000 DS Post 4-Jan-21 Continuatio Consultant n. Competitiv e selection under HGNDP C3/IC/04 Procurement 12,000 IC Post 26-Feb-21 Assistant C3/ IC /05 Office 24,000 IC Post 4-Jan-21 Administration C3/ IC /06 Cashier 12,000 IC Post 4-Jan-21 C3/ IC /07 Financial 30,000 IC Post 4-Jan-21 Management Consultant C3/ IC /08 National Project 18,000 IC Post 4-Jan-21 Accountant C3/ IC /09 M&E 18,000 IC Post 4-Jan-21 C3/ IC Provincial DLI 18,000 IC Post 4-Jan-21 /10.1 Program Support 1 C3/ IC Provincial DLI 18,000 IC Post 4-Jan-21 /10.2 Program Support 2 C3/ IC /12 Senior Project 54,000 IC Post 4-Jan-21 Advisor C3/ DS IT staff to 24,000 DS Post 4-Jan-21 Continuatio /04.1 support n. DHIS2(1) Competitiv e selection under HGNDP 5 Ref. No. Description of Estimat Selecti Revie Expected Comments Assignment ed Cost on w by Proposal (US$) Metho Bank s d (Prior / Submissi Post) on Date C3/DS/04. IT staff to 18,000 DS Post 4-Jan-21 Continuatio 2 support n. DHIS2(2) Competitiv e selection under HGNDP C3/IC/13 Safeguard 24,000 IC Post 4-Jan-21 Consultant C3/IC/14 Gender 24,000 IC Post 4-Jan-21 Consultant Total consulting services 1,636,0 00 Total Works, Goods and 1,815,6 Consulting Services 00 Notes: DS: Direct Selection QCBS: Quality and Cost-Based Selection IC: Individual Consultant 6 PROCUREMENT Lao People's Democratic Republic : Health and Nutrition Services Access Project PLAN General Information Country: Lao People's Democratic Republic Bank’s Approval Date of the Original Procurement Plan: 2020-08-27 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166165 GPN Date: 2022-05-26 Project Name: Health and Nutrition Services Access Project Loan / Credit No: IDA / 65570, TF / B2043 Department of Planning and Cooperation, Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C3/G/01 / Extension contract Component 3: Adaptive Lear for Maintain internet connecti IDA / 65570 ning and Project Manageme Post Direct Selection Direct 46,000.00 35,213.67 Signed 2020-11-05 2021-12-06 2020-11-10 2021-12-20 2020-12-15 2022-01-16 2021-06-13 vity(148 points) nt C3/G/02 / Extension contract Component 3: Adaptive Lear for Maintain internet connecti IDA / 65570 ning and Project Manageme Post Direct Selection Direct 57,000.00 34,447.80 Signed 2020-11-05 2022-01-04 2020-11-10 2022-07-28 2020-12-15 2022-08-02 2021-06-13 vity(182 points) nt CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C3/CQS/01 / Independence v Component 3: Adaptive Lear Quality And Cost- IDA / 65570 Post Open - National 1,656,000.00 0.00 Canceled 2020-11-05 2020-12-18 2020-11-26 2021-01-09 2021-02-06 2021-03-08 2021-04-12 2021-05-17 2022-05-17 erification on QPS and DLI ning and Project Manageme Based Selection nt C3/CQS/01.1 / Independence Component 3: Adaptive Lear Consultant Qualifi IDA / 65570 Post Open - National 300,000.00 0.00 Canceled 2021-03-11 2021-03-19 2021-04-01 2021-05-15 2021-06-14 2021-07-19 2022-01-15 verification on QPS ning and Project Manageme cation Selection nt C3/CQS/01.2 / Independence Component 3: Adaptive Lear Consultant Qualifi IDA / 65570 Post Open - National 250,000.00 0.00 Canceled 2021-03-11 2021-03-18 2021-04-01 2021-03-18 2021-05-15 2021-06-14 2021-07-19 2022-01-15 verification on DLI ning and Project Manageme cation Selection nt C3/CQS/01-2 / Independence Component 3: Adaptive Lear Consultant Qualifi Open - Internationa IDA / 65570 Post 250,000.00 1,355,990.00 Signed 2021-03-18 2021-03-20 2021-04-08 2021-05-22 2021-05-14 2021-06-21 2021-07-22 2021-07-26 2021-07-17 2022-01-22 verification on DLIs ning and Project Manageme cation Selection l nt C3/CQS/01-1 / Independence Component 3: Adaptive Lear Consultant Qualifi Open - Internationa IDA / 65570 Post 300,000.00 349,734.00 Signed 2021-03-19 2021-03-18 2021-04-09 2021-05-23 2021-05-14 2021-06-22 2021-07-14 2021-07-27 2021-07-20 2022-01-23 verification on QPS ning and Project Manageme cation Selection l nt C3/CQS/01-2.2 / Independen Component 3: Adaptive Lear Consultant Qualifi Open - Internationa Under Implement TF / B2043 Post 300,000.00 0.00 2023-04-04 2023-05-11 2023-04-25 2023-06-08 2023-07-08 2023-08-12 2024-02-08 ce verification on DLIs for ye ning and Project Manageme cation Selection l ation ar3 nt INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C3/DS/01 / Extension of cont Component 3: Adaptive Lear ract for Supporting the Opera IDA / 65570 ning and Project Manageme Post Direct Selection 600,000.00 0.00 Canceled 2020-11-05 2020-11-05 2020-11-05 2020-11-05 tion and Management of HMI nt S and DHIS2 C3/DS/02 / Project Financial Component 3: Adaptive Lear IDA / 65570 Post Direct Selection Direct 122,000.00 50.00 Signed 2020-11-05 2021-07-08 2020-11-15 2021-07-19 2021-01-19 2021-11-02 2021-07-18 Statements Audit ning and Project Manageme nt C3/DS/03 / Project admin Ma Component 3: Adaptive Lear IDA / 65570 Post Direct Selection 91,000.00 19,692.00 Signed 2020-11-05 2021-07-08 2020-11-05 2021-07-01 2020-11-05 2021-08-03 2020-11-05 nager ning and Project Manageme nt C3/DS/04 / Project administr Component 3: Adaptive Lear IDA / 65570 Post Direct Selection Direct 33,400.00 1.14 Signed 2020-11-05 2021-07-08 2020-11-10 2021-07-01 2021-01-14 2021-08-03 2021-07-13 ators ning and Project Manageme nt Component 3: Adaptive Lear C3/DS/05 / Cashier IDA / 65570 Post Direct Selection Direct 29,800.00 10,044.00 Signed 2020-11-05 2021-12-29 2020-11-15 2021-12-27 2021-01-19 2022-01-02 2021-07-18 ning and Project Manageme nt C3/ DS/06 / National Project Component 3: Adaptive Lear IDA / 65570 Post Direct Selection Direct 65,800.00 21,996.00 Signed 2020-11-05 2021-12-29 2020-11-15 2021-12-27 2021-01-19 2022-01-02 2021-07-18 Accountant ning and Project Manageme nt C3/ DS/07.1 / M&E Officer1 ( Component 3: Adaptive Lear DLI support implementation: IDA / 65570 ning and Project Manageme Post Direct Selection Direct 54,000.00 17,280.00 Signed 2020-11-05 2021-07-08 2020-11-15 2021-07-01 2021-01-19 2021-08-03 2021-07-18 Governance and quality of he nt alth care at HC) C3/DS /07.2 / M&E Officer2 ( Component 3: Adaptive Lear DLI support implementation: IDA / 65570 ning and Project Manageme Post Direct Selection Direct 54,000.00 17,280.00 Signed 2020-11-05 2021-07-08 2020-11-15 2021-07-01 2021-01-19 2021-08-03 2021-07-18 Hygiene and health promotio nt n) C3/ DS /07.3 / M&E Officer3 Component 3: Adaptive Lear (DLI support implementation: IDA / 65570 ning and Project Manageme Post Direct Selection Direct 54,000.00 14,292.00 Signed 2020-11-05 2021-07-08 2020-11-15 2021-07-01 2021-01-19 2021-08-03 2021-07-18 communicable diseases cont nt rol) Page 1 C3/ DS /08 / DHIS2 expert 1 Component 3: Adaptive Lear IDA / 65570 Post Direct Selection Direct 45,000.00 21,600.00 Signed 2020-11-05 2021-01-11 2020-11-15 2020-12-25 2021-01-19 2021-01-02 2021-07-18 (TB and HIV) ning and Project Manageme nt C3/ DS /09 / DHIS2 expert 2 Component 3: Adaptive Lear IDA / 65570 Post Direct Selection Direct 45,000.00 21,600.00 Signed 2020-11-05 2021-01-11 2020-11-15 2020-12-25 2021-01-19 2021-01-02 2021-07-18 (Surveillance and Malaria) ning and Project Manageme nt C3/ DS /10 / DHIS2 expert 3 Component 3: Adaptive Lear IDA / 65570 Post Direct Selection Direct 45,000.00 15,948.00 Signed 2020-11-05 2021-07-08 2020-11-15 2021-07-01 2021-01-19 2021-08-03 2021-07-18 (MCH and EPI) ning and Project Manageme nt C3/ DS /11 / DHIS2 expert 4 Component 3: Adaptive Lear IDA / 65570 Post Direct Selection Direct 45,000.00 24,504.00 Signed 2020-11-05 2021-07-08 2020-11-10 2021-07-01 2021-01-14 2021-08-03 2021-07-13 (NHI/EMR and Finance) ning and Project Manageme nt C3/ DS /12 / Safeguard Cons Component 3: Adaptive Lear IDA / 65570 Post Direct Selection Direct 73,000.00 0.00 Completed 2020-11-05 2022-02-09 2020-11-15 2022-07-01 2021-01-19 2021-07-18 2022-12-05 ultant ning and Project Manageme nt C3/ DS /13 / Procurement Co Component 3: Adaptive Lear IDA / 65570 Post Direct Selection Direct 73,000.00 24,504.00 Signed 2020-11-05 2021-07-08 2020-11-15 2021-07-01 2021-01-19 2021-08-02 2021-07-18 nsultant1 ning and Project Manageme nt C3/LIC /01 / Procurement Co Component 3: Adaptive Lear Individual Consult IDA / 65570 Post Open 73,000.00 100.00 Signed 2020-11-05 2020-12-18 2020-12-24 2021-01-22 2021-01-14 2021-04-05 2021-02-18 2021-04-06 2021-08-17 nsultant 2 ning and Project Manageme ant Selection nt C3/LIC /02 / Financial Manag Component 3: Adaptive Lear Individual Consult IDA / 65570 Post Open 127,000.00 33,600.00 Signed 2020-11-05 2020-12-18 2020-12-24 2021-01-12 2021-01-14 2021-02-19 2021-02-18 2021-02-24 2021-08-17 ement Consultant ning and Project Manageme ant Selection nt C3/LIC /03 / Lead M&E speci Component 3: Adaptive Lear Individual Consult IDA / 65570 Post Open 127,000.00 36,000.00 Signed 2020-11-05 2020-12-18 2020-12-24 2021-01-07 2021-01-14 2021-03-09 2021-02-18 2021-03-10 2021-08-17 alist ning and Project Manageme ant Selection nt C3/ LIC /04.2 / QPS Specialist Component 3: Adaptive Lear Individual Consult IDA / 65570 Post Open 48,000.00 0.00 Canceled 2020-11-05 2020-12-24 2021-01-14 2021-02-18 2021-08-17 s2 (M&E) ning and Project Manageme ant Selection nt Component 3: Adaptive Lear Individual Consult C3/IC/14 / Gender consultant IDA / 65570 Post Open 54,000.00 24,000.00 Signed 2020-08-31 2021-12-06 2020-10-19 2021-12-13 2020-11-09 2022-01-31 2020-12-14 2022-02-02 2021-06-12 ning and Project Manageme ant Selection nt C3-DS-01 / Supporting the O Component 3: Adaptive Lear peration and Management of IDA / 65570 ning and Project Manageme Post Direct Selection Direct 978,000.00 997,735.00 Signed 2021-05-14 2021-05-18 2021-05-24 2021-04-06 2021-07-28 2021-01-05 2022-01-24 HMIS and DHIS2 nt C3/LIC /04.1 / QPS Specialist Component 3: Adaptive Lear Individual Consult IDA / 65570 Post Open 48,000.00 15,600.00 Signed 2020-11-05 2022-02-01 2020-12-24 2022-03-11 2021-01-14 2022-05-25 2021-02-18 2022-05-26 2021-08-17 s1 (M&E) ning and Project Manageme ant Selection nt C3/ IC /05. / Data Manageme Component 3: Adaptive Lear Individual Consult IDA / 65570 Post Open 48,000.00 21,600.00 Signed 2020-11-05 2022-02-01 2020-12-24 2021-09-13 2021-01-14 2022-01-31 2021-02-18 2022-02-02 2021-08-17 nt Consultant. ning and Project Manageme ant Selection nt C3/ IC /06 / Provincial Safegu Component 3: Adaptive Lear Individual Consult IDA / 65570 Post Open 52,000.00 51,600.00 Signed 2022-02-07 2022-02-28 2022-03-28 2022-03-09 2022-04-18 2022-04-19 2022-05-23 2022-05-10 2022-11-19 ard Coordinator ning and Project Manageme ant Selection nt C3/ DS /14 / Firm to conduct Component 3: Adaptive Lear midline Survey in the 12 Dist IDA / 65570 ning and Project Manageme Post Direct Selection Direct - National 333,000.00 0.00 Signed 2022-07-29 2022-08-01 2022-08-08 2022-07-28 2022-10-12 2023-04-10 ricts in 4 Northern Provinces nt of Lao PDR C3/ DS /15 / National Enviro Component 3: Adaptive Lear Individual Consult IDA / 65570 Post Direct - National 18,000.00 0.00 Signed 2023-02-21 2023-02-22 2023-03-03 2023-02-27 2023-03-24 2023-02-28 2023-04-28 2023-10-25 nmental & Social Consultant ning and Project Manageme ant Selection nt C3/ DS /12.2 / Safeguard Co Component 3: Adaptive Lear Individual Consult Under Implement IDA / 65570 Post Open - National 24,000.00 0.00 2023-05-11 2023-05-31 2023-06-29 2023-07-20 2023-08-24 2024-02-20 nsultant ning and Project Manageme ant Selection ation nt Page 2 PROCUREMENT PLAN (Textual Part) Project information: Nigeria Fiscal Governance and Institutions Project (FGIP) P163540 Project Implementation agency: Bureau of Public Procurement Date of the Procurement Plan: September 20, 2019 Period covered by this Procurement Plan: 2019 - 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Public Procurement Act, 2007, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable for those contracts identified in the Procurement Plan tables] Other Relevant Procurement Information. Not Applicable PROCUREMENT Nigeria : Fiscal Governance and Institutions Project PLAN General Information Country: Nigeria 2020-01-09 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163540 GPN Date: Project Name: Fiscal Governance and Institutions Project Loan / Credit No: IDA / 62880 Federal Ministry of of Finance FGIP Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-FMF FGIP-156300-GO-RF Request for Quota Single Stage - One E IDA / 62880 Implementation Support Post Limited 19,934.42 11,956.55 Signed 2020-05-03 2020-05-08 2020-06-28 2020-07-03 2020-12-25 Q / Furnishing of FGIP PCU/PI tions nvelope U Office NG-FMF FGIP-164221-GO-RF Request for Quota Single Stage - One E IDA / 62880 Implementation Support Post Limited 3,934.43 0.00 Canceled 2020-05-26 2020-07-21 2021-01-17 Q / Office Consumables tions nvelope NG-FMF FGIP-164428-GO-RF Request for Quota Q / Office Equipment (Photoc IDA / 62880 Implementation Support Post 23,868.85 0.00 Canceled 2020-05-22 2020-05-22 2020-05-22 tions opier Medium, Laptops, Desk top Computers) NG-FMF FGIP-176154-GO-RF Request for Quota Single Stage - One E IDA / 62880 Implementation Support Post Limited 23,868.85 22,881.50 Signed 2020-06-03 2022-07-22 2020-07-29 2022-09-07 2021-01-25 Q / Office Equipment tions nvelope NG-FMF FGIP-189191-GO-DI IDA / 62880 Implementation Support Post Direct Selection Direct 30,000.00 0.00 Canceled 2021-06-29 2021-07-04 2021-08-08 2022-02-04 R / Accounting Software NG-FMF FGIP-300128-GO-RF Strengthening Controls, Tran Request for Quota Single Stage - One E Q / Procurement of Office Fur IDA / 62880 sparency and Accountability Post Limited 23,758.02 22,037.52 Signed 2022-06-28 2022-07-01 2022-08-23 2022-09-07 2023-02-19 tions nvelope niture to support implementa in the Use of Public Funds tion of FCSSIP NG-FMF FGIP-300135-GO-RF Strengthening Controls, Tran Request for Quota Single Stage - One E Q / Provision of Office Equip IDA / 62880 sparency and Accountability Post Limited 43,006.55 40,284.78 Signed 2022-06-28 2022-07-01 2022-08-23 2022-09-07 2023-02-19 tions nvelope ment (alternative power sup in the Use of Public Funds ply) for OHCSF Strengthening Controls, Tran NG-FMF FGIP-302552-GO-RF Single Stage - One E IDA / 62880 sparency and Accountability Post Request for Bids Open - National 450,243.43 0.00 Signed 2022-07-07 2022-08-18 2022-07-12 2022-08-18 2022-08-23 2022-09-29 2022-09-22 2022-10-27 2022-10-27 2023-04-25 B / Computer and Peripherals nvelope in the Use of Public Funds NG-FMF FGIP-306111-GO-RF Strengthening Controls, Tran Request for Quota Single Stage - One E Q / Production of 2,000 copie IDA / 62880 sparency and Accountability Post Limited 21,000.00 0.00 Signed 2022-08-10 2022-08-19 2022-10-05 2023-04-03 tions nvelope s of FCSSIP Booklets in the Use of Public Funds NG-FMF FGIP-309300-GO-RF Request for Quota Single Stage - One E IDA / 62880 Implementation Support Post Limited 10,000.00 0.00 Canceled 2022-08-23 2022-10-18 2023-04-16 Q / Office Consumable tions nvelope NG-FMF FGIP-368554-GO-RF Request for Quota Single Stage - One E Pending Impl Q / Purchase of Office Consu IDA / 62880 Implementation Support Post Limited 37,500.00 0.00 2023-07-05 2023-08-30 2024-02-26 tions nvelope ementation mables for PCU NG-FMF FGIP-368632-GO-RF Request for Quota Single Stage - One E Pending Impl Q / Purchase of Office Equip IDA / 62880 Implementation Support Post Limited 62,800.00 0.00 2023-07-05 2023-08-30 2024-02-26 tions nvelope ementation ment for PCU and OAGF NG-FMF FGIP-368638-GO-RF Request for Quota Single Stage - One E Pending Impl IDA / 62880 Implementation Support Post Limited 54,500.00 0.00 2023-07-05 2023-08-30 2024-02-26 Q / Office furniture for PCU a tions nvelope ementation nd TSD NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-FMF FGIP-164448-NC-RF Request for Quota Single Stage - One E Q / Printing of Letter Head, Fi IDA / 62880 Implementation Support Post Limited 1,639.34 0.00 Canceled 2020-05-25 2021-03-01 2020-07-20 2021-01-16 tions nvelope le Jackets e.t.c. NG-FMF FGIP-170518-NC-RF Request for Propo Single Stage - Two E P / FGIP Web-site Developme IDA / 62880 Implementation Support Post Limited 8,196.72 0.00 Canceled 2020-09-23 2020-09-28 2020-11-09 2021-02-26 2021-08-25 sals nvelope nt/Maintenance NG-FMF FGIP-244178-NC-RF Request for Quota Single Stage - One E IDA / 62880 Implementation Support Post Limited 25,000.00 24,545.68 Signed 2021-09-04 2021-09-09 2021-10-30 2022-02-11 2022-04-28 Q / Accounting Software tions nvelope CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-FMF FGIP-170050-CS-CQ Consultant Qualifi IDA / 62880 Implementation Support Post Open - National 70,000.00 0.00 Canceled 2020-05-29 2020-06-19 2020-08-02 2020-09-01 2020-10-06 2021-04-04 S / Independent Verification cation Selection Agent (IVA) NG-FMF FGIP-239227-CS-CQ Consultant Qualifi IDA / 62880 Implementation Support Post Limited 30,000.00 0.00 Canceled 2021-06-16 2021-06-29 2021-06-30 2021-07-30 2021-09-03 2022-03-02 S / External Auditor cation Selection NG-FMF FGIP-251503-CS-LC Least Cost Selecti IDA / 62880 Implementation Support Post Open - National 180,000.00 0.00 Canceled 2021-09-21 2021-10-07 2021-10-12 2021-11-25 2021-12-23 2022-01-22 2022-02-26 2022-04-02 2022-09-29 S / Domestic Tax Study on Page 1 NG-FMF FGIP-251506-CS-LC Least Cost Selecti IDA / 62880 Implementation Support Post Open - National 200,000.00 0.00 Canceled 2021-09-21 2021-10-07 2021-10-12 2021-11-25 2021-12-23 2022-01-22 2022-02-26 2022-04-02 2022-09-29 S / International Tax Study on NG-FMF FGIP-251508-CS-LC Least Cost Selecti S / Assessment and Guideline IDA / 62880 Implementation Support Post Open - National 150,000.00 0.00 Canceled 2021-10-05 2021-10-26 2021-12-09 2022-01-06 2022-02-05 2022-03-12 2022-04-16 2022-10-13 on s on Public-Private-Partnershi p NG-FMF FGIP-189194-CS-CQ Consultant Qualifi IDA / 62880 Implementation Support Post Limited 70,000.00 0.00 Canceled 2020-08-21 2021-01-27 2020-09-04 2021-04-21 2020-10-04 2020-11-08 2021-05-07 S / Independent Verification cation Selection Agent (IVA) NG-FMF FGIP-280304-CS-CQ Consultant Qualifi IDA / 62880 Implementation Support Post Open - National 70,000.00 0.00 Signed 2022-03-03 2022-03-03 2022-03-24 2022-04-04 2022-05-07 2022-08-18 2022-06-06 2022-11-10 2022-07-11 2023-01-07 S / Independent Verification cation Selection Agent NG-FMF FGIP-251480-CS-LC Least Cost Selecti S / Training on Understandin IDA / 62880 Implementation Support Post Open - National 60,000.00 0.00 Canceled 2021-09-14 2021-09-28 2021-10-05 2021-11-18 2021-12-16 2022-01-15 2022-02-19 2022-03-26 2022-09-22 on g and Computing Tax Expend iture Analysis NG-FMF FGIP-246348-CS-LC Least Cost Selecti S / Training on Understandin IDA / 62880 Implementation Support Post Open - National 60,000.00 0.00 Canceled 2021-08-16 2021-09-06 2021-10-20 2021-11-17 2021-12-17 2022-01-21 2022-02-25 2022-08-24 on g Tax Expenditure Analysis a nd Reporting NG-FMF FGIP-286069-CS-CQ Strengthening Revenue Man Consultant Qualifi Open - Internationa S / Trade Taxation and Custo IDA / 62880 Post 280,000.00 0.00 Signed 2022-03-29 2022-04-07 2022-04-19 2022-05-19 2022-06-02 2022-09-08 2022-07-02 2022-12-28 2022-08-06 2023-02-02 agement cation Selection l ms Policy Study NG-FMF FGIP-286340-CS-CQ Strengthening Revenue Man Consultant Qualifi Under Implement IDA / 62880 Post Open - National 180,000.00 0.00 2022-03-29 2022-04-07 2022-04-19 2022-05-19 2022-06-02 2022-07-02 2022-08-06 2023-02-02 S / Domestic Tax Study agement cation Selection ation NG-FMF FGIP-293728-CS-CQ Strengthening Revenue Man Consultant Qualifi Open - Internationa Under Implement S / Assessment, Guidelines a IDA / 62880 Post 315,000.00 0.00 2022-06-27 2022-05-20 2022-07-18 2022-07-14 2022-08-31 2022-09-30 2022-09-30 2022-12-22 2022-11-04 2023-05-03 agement cation Selection l ation nd Training on Public Private Partnership NG-FMF FGIP-293733-CS-CQ S / Capacity Building for Tax Strengthening Revenue Man Consultant Qualifi Open - Internationa IDA / 62880 Post 86,000.00 0.00 Signed 2022-06-13 2022-05-20 2022-07-04 2022-07-14 2022-08-17 2022-09-30 2022-09-16 2022-10-31 2022-10-21 2023-04-19 Policy Analysis including Inte agement cation Selection l rnational Tax Cooperation on Transfer Pricing NG-FMF FGIP-293741-CS-CQ Strengthening Revenue Man Consultant Qualifi Open - Internationa IDA / 62880 Post 160,000.00 0.00 Signed 2022-05-11 2022-05-20 2022-06-01 2022-07-14 2022-07-15 2022-10-28 2022-08-14 2022-10-31 2022-09-18 2023-03-17 S / Domestic Tax Training Pa agement cation Selection l ckage NG-FMF FGIP-300141-CS-CQ Consultant Qualifi Open - Internationa S / Audit of Public Private Par IDA / 62880 Implementation Support Post 450,000.00 0.00 Signed 2022-06-28 2022-06-29 2022-07-19 2022-08-09 2022-09-01 2022-09-26 2022-10-01 2022-11-28 2022-11-05 2023-05-04 cation Selection l tnership Concession Contract s NG-FMF FGIP-300154-CS-CQ S / Development of Organizat Consultant Qualifi Open - Internationa Under Implement IDA / 62880 Implementation Support Post 450,000.00 0.00 2022-06-28 2022-09-29 2022-07-19 2022-08-09 2022-09-01 2022-08-31 2022-10-01 2022-11-28 2022-11-05 2023-05-04 ional and Strategic Plan for M cation Selection l ation inistry of Finance Incorporate d NG-FMF FGIP-300320-CS-CQ S / Development of a Frame Consultant Qualifi Open - Internationa IDA / 62880 Implementation Support Post 450,000.00 0.00 Signed 2022-06-30 2022-06-30 2022-07-21 2022-08-09 2022-09-03 2022-09-26 2022-10-03 2022-11-28 2022-11-07 2023-05-06 work for a Modernized Integr cation Selection l ated Public Financial Manage ment Information System NG-FMF FGIP-300340-CS-CQ Consultant Qualifi Open - Internationa Under Implement S / Strategic Plan for the Mini IDA / 62880 Implementation Support Post 350,000.00 0.00 2022-06-30 2022-06-30 2022-07-21 2022-08-09 2022-09-03 2022-09-26 2022-10-03 2022-11-28 2022-11-07 2023-05-06 cation Selection l ation stry of Finance Training Instit ute INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-FMF FGIP-153273-CS-CD S / Preparation of Project Pro IDA / 62880 Implementation Support Prior Direct Selection Direct 39,000.00 45,899.10 Signed 2020-01-09 2020-01-10 2020-01-19 2020-01-14 2020-03-24 2020-01-16 2020-09-20 curement Strategy for Devel opment NG-FMF FGIP-173205-CS-CQ Individual Consult S / Senior Technical Coordina IDA / 62880 Implementation Support Post Limited 50,000.00 38,733.71 Signed 2020-05-29 2020-06-05 2020-06-03 2020-07-20 2020-06-24 2020-10-28 2020-07-29 2021-01-21 2021-01-25 ant Selection ting Consultant NG-FMF FGIP-169189-CS-IND Individual Consult IDA / 62880 Implementation Support Post Open 37,377.05 0.00 Canceled 2020-05-29 2020-07-17 2020-08-07 2020-09-11 2021-03-10 V / Communication Specialist ant Selection NG-FMF FGIP-189199-CS-IND Individual Consult IDA / 62880 Implementation Support Post Limited 50,000.00 0.00 Canceled 2020-08-26 2021-01-26 2020-08-31 2020-09-21 2020-10-26 2021-04-24 V / M & E Specialist ant Selection NG-FMF FGIP-189202-CS-IND Individual Consult IDA / 62880 Implementation Support Post Limited 50,000.00 0.00 Canceled 2020-09-07 2021-01-26 2020-09-12 2020-10-03 2020-11-07 2021-05-06 V / Project Associate ant Selection NG-FMF FGIP-170027-CS-IND Individual Consult IDA / 62880 Implementation Support Post Open 50,000.00 0.00 Canceled 2020-05-29 2020-07-17 2020-08-07 2020-09-11 2021-03-10 V / M & E Specialist ant Selection NG-FMF FGIP-170681-CS-IND Individual Consult IDA / 62880 Implementation Support Post Open 50,000.00 0.00 Canceled 2020-05-29 2020-07-17 2020-08-07 2020-09-11 2021-03-10 V / Project Associate ant Selection NG-FMF FGIP-238345-CS-CD Individual Consult IDA / 62880 Implementation Support Post Direct 95,000.00 88,821.25 Signed 2021-07-30 2021-08-31 2021-08-09 2021-08-11 2021-08-30 2021-08-16 2021-10-04 2021-09-23 2022-04-02 S / Special Assistant to the H ant Selection MFBNP NG-FMF FGIP-238351-CS-CD S / Consultant to Integrated P IDA / 62880 Implementation Support Post Direct Selection Direct 66,600.00 62,043.80 Signed 2021-08-02 2021-08-16 2021-08-12 2021-09-27 2021-10-16 2021-11-14 2022-04-14 ayroll and Personnel Informat ion System HR-OHCSF NG-FMF FGIP-250082-CS-IND Individual Consult V / Preparatory Training of St IDA / 62880 Implementation Support Post Limited 11,800.00 11,678.83 Signed 2021-08-27 2021-08-30 2021-09-01 2021-09-03 2021-09-22 2021-09-29 2021-10-27 2021-10-29 2022-04-25 ant Selection aff on the Excel Software NG-FMF FGIP-270602-CS-CD IDA / 62880 Implementation Support Post Direct Selection Direct 30,000.00 20,030.80 Signed 2021-12-30 2022-01-05 2022-01-09 2022-02-09 2022-03-15 2022-04-17 2022-09-11 S / External Auditor NG-FMF FGIP-306136-CS-IND Strengthening Controls, Tran Individual Consult V / FCSSIP 25 Programme Ma IDA / 62880 sparency and Accountability Post Limited 58,536.59 0.00 Signed 2022-08-01 2022-08-05 2022-08-03 2022-08-19 2022-08-24 2022-09-30 2022-09-28 2023-03-27 ant Selection nagement Consultant in the Use of Public Funds Page 2 NG-FMF FGIP-309272-CS-IND Individual Consult IDA / 62880 Implementation Support Post 8,500.00 0.00 Canceled 2022-08-17 2022-10-05 2022-10-26 2022-11-30 2023-05-29 V / Project Assistant ant Selection NG-FMF FGIP-312592-CS-IND Individual Consult IDA / 62880 Implementation Support Post Limited 12,400.00 0.00 Signed 2022-08-31 2022-09-06 2022-09-05 2022-09-07 2022-09-26 2022-09-21 2022-10-31 2023-04-29 V / Project Assistant ant Selection NG-FMF FGIP-318807-CS-IND Strengthening Controls, Tran V / Consultant to support inst Individual Consult IDA / 62880 sparency and Accountability Post Limited 48,000.00 0.00 Canceled 2022-10-06 2022-10-12 2022-10-11 2022-11-01 2022-12-06 2023-06-04 itutionalization of Performanc ant Selection in the Use of Public Funds e Management System in the Public Service NG-FMF FGIP-318816-CS-IND V / Consultant to support Perf Strengthening Controls, Tran Individual Consult ormance Management Syste IDA / 62880 sparency and Accountability Post Limited 36,000.00 0.00 Canceled 2022-10-06 2022-10-12 2022-10-11 2022-11-01 2022-12-06 2023-06-04 ant Selection m hand holding exercises for in the Use of Public Funds MDAs in the Social Services s ector NG-FMF FGIP-318823-CS-IND V / Consultant to support Perf Strengthening Controls, Tran Individual Consult ormance Management Syste IDA / 62880 sparency and Accountability Post Limited 36,000.00 0.00 Canceled 2022-10-06 2022-10-12 2022-10-11 2022-11-01 2022-12-06 2023-06-04 ant Selection m hand holding exercise for in the Use of Public Funds MDAs in the Economy Sector NG-FMF FGIP-319217-CS-IND V / Consultant to support Perf Strengthening Controls, Tran Individual Consult ormance Management Syste IDA / 62880 sparency and Accountability Post Limited 36,000.00 0.00 Canceled 2022-10-06 2022-10-12 2022-10-11 2022-11-01 2022-12-06 2023-06-04 ant Selection m hand holding exercises for in the Use of Public Funds MDAs in the Infrastructure se ctor NG-FMF FGIP-319224-CS-IND V / Consultant to support Perf Strengthening Controls, Tran Individual Consult ormance Management Syste IDA / 62880 sparency and Accountability Post Limited 36,000.00 0.00 Canceled 2022-10-06 2022-10-12 2022-10-11 2022-11-01 2022-12-06 2023-06-04 ant Selection m hand holding exercises for in the Use of Public Funds MDAs in the Administrative a nd Governance sector NG-FMF FGIP-349970-CS-IND Strengthening Revenue Man Individual Consult Under Implement V / Appointment of Consultan IDA / 62880 Post Limited 10,975.61 0.00 2023-03-24 2023-03-17 2023-03-29 2023-04-19 2023-05-24 2023-08-24 agement ant Selection ation t for Production of Training M aterials NG-FMF FGIP-350591-CS-IND Strengthening Controls, Tran Individual Consult Open - Internationa Under Implement V / Appointment of Consultan IDA / 62880 sparency and Accountability Post 41,000.00 0.00 2023-03-31 2023-03-28 2023-05-19 2023-06-09 2023-07-14 2023-09-14 ant Selection l ation t on GIFMIS Security Enhance in the Use of Public Funds ment NG-FMF FGIP-361310-CS-IND V / Consultant to support Perf Strengthening Controls, Tran Individual Consult Under Implement ormance Management Syste IDA / 62880 sparency and Accountability Post Limited 36,000.00 0.00 2023-05-11 2023-06-15 2023-05-16 2023-06-06 2023-07-11 2024-01-07 ant Selection ation m hand holding exercises for in the Use of Public Funds MDAs in the Infrastructure se ctor. NG-FMF FGIP-363683-CS-IND V / Consultant to support Perf Strengthening Controls, Tran Individual Consult Under Implement ormance Management Syste IDA / 62880 sparency and Accountability Post Limited 36,000.00 0.00 2023-05-30 2023-06-15 2023-06-04 2023-06-25 2023-07-30 2024-01-26 ant Selection ation m hand holding exercises for in the Use of Public Funds MDAs in the Administrative a nd Governance sector NG-FMF FGIP-363686-CS-IND Strengthening Controls, Tran V / Consultant to support inst Individual Consult Under Implement IDA / 62880 sparency and Accountability Post Limited 48,000.00 0.00 2023-05-30 2023-06-15 2023-06-04 2023-06-25 2023-07-30 2024-01-26 itutionalization of Performanc ant Selection ation in the Use of Public Funds e Management System in the Public Service NG-FMF FGIP-363687-CS-IND V / Consultant to support Perf Strengthening Controls, Tran Individual Consult Under Implement ormance Management Syste IDA / 62880 sparency and Accountability Post Limited 36,000.00 0.00 2023-05-30 2023-06-15 2023-06-04 2023-06-25 2023-07-30 2024-01-26 ant Selection ation m hand holding exercise for in the Use of Public Funds MDAs in the Economy Sector NG-FMF FGIP-363690-CS-IND V / Consultant to support Perf Strengthening Controls, Tran Individual Consult Under Implement ormance Management Syste IDA / 62880 sparency and Accountability Post Limited 36,000.00 0.00 2023-05-30 2023-06-15 2023-06-04 2023-06-25 2023-07-30 2024-01-26 ant Selection ation m hand holding exercises for in the Use of Public Funds MDAs in the Social Services s ector NG-FMF FGIP-367239-CS-CD Under Implement IDA / 62880 Implementation Support Post Direct Selection Direct - National 43,917.62 0.00 2023-06-20 2023-06-19 2023-06-30 2023-08-15 2023-12-20 S / Engagement of External A ation uditor Page 3 TEXTUAL PART of PROCUREMENT PLAN EU/IPA Energy Sector Technical Assistance Project information: Program – Phase 4 Project (P179235) Project Implementation MENR/ Directorate General Foreign Relations Agency: Date of the Procurement 13 March 2023 Plan: Period covered by this 13 March 2023 – 13 September 2024 Procurement Plan: Date of General TBD Procurement Notice: I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. Any procurement activity under the Project shall not be initiated before it is approved by the Bank through STEP. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Goods, Works and Non-Consulting Services Procurement Procurement Method Prior Review Threshold Method Threshold Preferred Method for Good, Contract valued ≥ USD RFB (International Works and Non-consulting 15M Works and ≥ USD 4M Open Competition) Services (No selection for Goods and Non- method threshold) Consulting Services Contracts valued < USD Contracts valued ≥ USD RFB (National Open 30M for Works and < USD 15M for Works and ≥ USD Competition) 4M for Goods and Non- 4M for Goods and Non- Consulting Services Consulting Services Works Contracts valued < USD200,000 – Goods and No prior review RFQ Non-consulting Services Contracts valued < USD100,000 III. Selection of Consultants Selection Method Selection Method Prior Review Threshold Threshold Quality and Cost Default Method (No Contract valued ≥ USD Based Selection selection method 2M (QCBS) threshold) 4 Selection Based on Contracts valued < No prior review Consultants USD300,000 Qualification (CQS) Least Cost Selection No selection Method Contract valued ≥ USD (LCS) threshold 2M Direct Selection (DIR) No selection method Contract valued ≥ USD threshold 2M Justification is required at the PP approval Individual Consultants No selection method Contracts valued ≥ (INDV) threshold USD400,000 The terms of references of any audit, procurement or legal consultants financed by the project shall be sent to the Bank for its comments. IV. Special Arrangements 1. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. For the procurements not subject to international competitive selection, Turkish translation of the Bank’s Standard Procurement Documents (SPD) with minor modifications will be used as to fit for purpose or the procurement documents agreed by the Bank shall be used. 2. Review Procedure: The procurements under the project are subject to the Bank’s prior review as stipulated in above Paragraphs II and III and also as specified in the procurement schedule given below in Section V, and in STEP. 3. Procurement of Second-Hand Goods: Not Applicable. 4. Domestic preference (as specified under paragraph 5.51 of the Procurement Regulations): Not applicable. V. Procurement Packages with Methods and Time Schedule The estimated costs in the attached tables (sheets) (including VAT) 4 PROCUREMENT Turkiye : Türkiye - EU IPA Energy Sector Program Phase IV Project - Offshore Wind Support PLAN General Information Country: Turkiye 2023-05-03 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P179235 GPN Date: 2023-05-02 Project Name: Türkiye - EU IPA Energy Sector Program Phase IV Project - Offshore Wind Support Loan / Credit No: / Ministry of Energy Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NCS01 / Non-Consulting Ser vices for Geological, Geophys Offshore Wind Energy Site D Open - Internationa Single Stage - Two E Pending Impl ical and Geotechnical Sea-Be / Prior Request for Bids 5,050,000.00 0.00 2024-09-07 2024-11-02 2025-05-01 evelopment Studies l nvelope ementation d Survey Studies for Offshore Wind Site Investigation in Tür kiye CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS02 / Consulting Services f or Environmental and Social Environmental and Social Co Consultant Qualifi Under Implement / Post Open - National 300,000.00 0.00 2023-04-10 2023-06-14 2023-05-01 2023-06-23 2023-06-14 2023-07-14 2023-08-18 2024-02-14 Constraints Analysis for Offsh nstraints Analysis cation Selection ation ore Wind Site Investigation in Türkiye CS01 / Consulting Services f or Met Ocean and Wind Meas Offshore Wind Energy Site D Quality And Cost- Open - Internationa / Prior 3,400,000.00 0.00 Canceled 2023-05-04 2023-05-17 2023-05-25 2023-07-08 2023-08-05 2023-09-04 2023-10-09 2023-11-13 2025-05-30 urement Studies for Offshore evelopment Studies Based Selection l Wind Site Investigation in Tür kiye CS01A / Consulting Services for Met Ocean and Wind Mea Offshore Wind Energy Site D Quality And Cost- Open - Internationa Under Implement / Prior 3,400,000.00 0.00 2023-05-26 2023-05-30 2023-06-05 2023-06-01 2023-07-19 2023-08-16 2023-09-15 2023-10-20 2023-11-24 2025-05-31 surement Studies for Offshor evelopment Studies Based Selection l ation e Wind Site Investigation in T ürkiye INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 Strengthening Pedagogy and Governance (P176105) Requesting Unit: LCC7C, Responsible Unit: HLCED/LCRVP Lending Instrument: Investment Project Financing Net commitment: 40 M PROCUREMENT Uruguay : Strengthening Pedagogy and Governance in Uruguayan Public Schools Project PLAN General Information Country: Uruguay 2022-08-17 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P176105 GPN Date: 2022-07-13 Project Name: Strengthening Pedagogy and Governance in Uruguayan Public Schools Project Loan / Credit No: IBRD / 93310 National administration of Public Education Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ESCUELA 114 RIVERA 30614 3-CW-RFB 2022 / Escuela qui Component 3: Improving Infr Request for Quota ntil 2. Construcción de 3 aula Single Stage - One E Under Imple 2024-03-3 IBRD / 93310 astructure and Complement Post Request for Bids Open - National tions (Non Bank-S 1,200,000.00 0.00 2022-09-01 2023-01-27 2022-09-01 2022-10-01 2022-10-31 2023-03-31 s, rehabilitación de 6 aulas, c nvelope mentation 1 ary Services PD) omedor, cocina, dirección y s shh en la Escuela 114 Depart amento de Rivera ESCUELA 2 RÍO NEGRO -306 144-CW-RFB 2022 / Escuela Component 3: Improving Infr Request for Quota quintil 2. Ampliación de 1 aul Single Stage - One E Under Imple 2024-03-3 IBRD / 93310 astructure and Complement Post Request for Bids Open - National tions (Non Bank-S 1,500,000.00 0.00 2022-11-01 2022-11-28 2022-11-01 2022-12-01 2022-12-28 2022-12-31 2023-01-20 2023-05-02 a, rehabilitación de 5 aulas, c nvelope mentation 1 ary Services PD) omedor, cocina, dirección y s shh en la Escuela 2 Departa mento de Río Negro ESCUELA 301 CANELONES-3 06147-CW-RFB 2022 / Escuel Component 3: Improving Infr Request for Quota Single Stage - One E Under Imple 2023-10-3 a quintil 2. Ampliación 7 aula IBRD / 93310 astructure and Complement Post Request for Bids Open - National tions (Non Bank-S 750,000.00 0.00 2022-11-01 2022-11-28 2022-11-01 2022-12-01 2022-12-28 2022-12-31 2023-01-20 2023-05-02 nvelope mentation 1 s en la Escuela 301 de la loca ary Services PD) lidad de Marindia, Departam ento de Canelones ESCUELA 68 DURAZNO 3061 49-CW-RFB 2022 / Escuela q National Procure uintil 2. Ampliación de 3 aula Component 3: Improving Infr ment Document - Single Stage - One E Pending Imp 2024-06-3 s, comedor, cocina y rehabilit IBRD / 93310 astructure and Complement Post Request for Bids Open - National 1 Envelope proce 1,500,000.00 0.00 2023-03-01 2023-03-01 2023-03-31 2023-04-30 2023-09-01 nvelope lementation 0 ación de 6 aulas, dirección y ary Services ss (Non Bank-SPD sala de maestros en la Escue ) la 68 del Departamento de D urazno PBC ESC 4 MTDEO-305968-C W-RFQ / Mantenimiento corre Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E 2023-02-0 ctivo - pavimentos en aula y IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 62,000.00 0.00 Signed 2022-09-10 2022-11-15 tions nvelope 3 reforma aula en Planta Alta. ary Services PD) Escuela n° 4 de Mdeo. PBC ESC. 183 MDEO-2023- 3 Component 3: Improving Infr Request for Quota 05971-CW-RFQ / Mantenimie Request for Quota Single Stage - One E Pending Imp 2023-08-1 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 15,000.00 0.00 2023-06-06 2023-07-07 nto correctivo - Conexión ga tions nvelope lementation 1 ary Services PD) s por cañería en la escuela n ° 183 de Montevideo. PBC ESC 29 ROCHA-305966- Component 3: Improving Infr Request for Quota CW-RFQ / Mantenimiento cor Request for Quota Single Stage - One E 2023-03-2 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 171,000.00 0.00 Signed 2022-09-12 2022-12-18 rectivo Ampliación para aloja tions nvelope 4 ary Services PD) r aulas inicial en la escuela n ° 29 de Rocha. PBC ESC 88 RIVERA -305970 Component 3: Improving Infr Request for Quota -CW-RFQ / Mantenimiento cor Request for Quota Single Stage - One E 2023-04-0 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 150,000.00 0.00 Signed 2022-09-09 2022-12-11 rectivo. Reforma baño, const tions nvelope 7 ary Services PD) rucción de rampa y muro en Esc. 88 Rivera PBC ESC. 20 MONTEVIDEO- 305973-CW-RFQ / Mantenimi Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-12-0 ento correctivo. Adecuación i IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 150,000.00 0.00 2023-05-07 2023-08-04 tions nvelope lementation 4 nstalación eléctrica en la esc ary Services PD) uela n° 20 de Montevideo. PBC ESC. 53 MONTEVIDEO- 305943-CW-RFQ / Mantenimi Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-05-2 ento correctivo - Reparación IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 25,000.00 0.00 2023-03-07 2023-04-08 tions nvelope lementation 6 filtraciones en cocina y aulas ary Services PD) . Escuela n° 53 de Montevide o. PBC ESC. 371 MDEO-2023- 3 Component 3: Improving Infr Request for Quota 05983-CW-RFQ / Mantenimie Request for Quota Single Stage - One E Pending Imp 2024-01-0 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 122,000.00 0.00 2023-06-09 2023-09-05 nto Correctivo.Ampliación co tions nvelope lementation 3 ary Services PD) cina, escuela n° 371 de Mont evideo. PBC ESC. 42 MALDONADO 3 05981-CW-RFQ / Mantenimie Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-12-2 nto correctivo - Ampliación d IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 244,000.00 0.00 2023-05-08 2023-08-20 tions nvelope lementation 9 e cocina y comedor en la esc ary Services PD) uela n° 42 de Maldonado. PBC ESC. 126 COLONIA 3059 Component 3: Improving Infr Request for Quota 67-CW-RFQ / Mantenimiento Request for Quota Single Stage - One E Pending Imp 2023-04-0 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 170,000.00 0.00 2022-10-07 2023-01-11 correctivo. Adecuación del sa tions nvelope lementation 5 ary Services PD) neamiento. Escuela n° 126 d e Colonia. PBC ESC. 75 ROCHA -30595 Component 3: Improving Infr Request for Quota 4-CW-RFQ / Mantenimiento c Request for Quota Single Stage - One E Pending Imp 2023-01-1 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 86,000.00 0.00 2022-09-06 2022-11-15 orrectivo Reparación parcial tions nvelope lementation 6 ary Services PD) de filtraciones en la escuela n° 75 de Rocha. PBC ESC. 72 ROCHA- 30595 2-CW-RFQ / Mantenimiento c Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-10-1 orrectivo . Impermeabilizació IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 32,000.00 0.00 2023-06-09 2023-08-22 tions nvelope lementation 7 n de cubiertas y pintura en la ary Services PD) escuela n° 72 de Rocha PBC ESC. 156 CANELONES- 305960-CW-RFQ / Mantenimi Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E 2023-03-3 ento correctivo Adecuación IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 10,000.00 0.00 Signed 2023-02-07 2023-03-12 tions nvelope 1 de la Instalación Sanitaria - R ary Services PD) ed primaria . Escuela n° 156 de Canelones Page 1 PBC ESC. 24 RIVERA 305994 -CW-RFQ / Mantenimiento cor Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E 2023-03-2 rectivo. Sustitución de pisos IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 49,000.00 0.00 Signed 2022-11-11 2023-02-07 tions nvelope 0 en aulas prefabricadas. Escu ary Services PD) ela n° 24 de Vichadero - Rive ra. PBC ESC. 9 COLONIA -30596 Component 3: Improving Infr Request for Quota 2-CW-RFQ / Mantenimiento c Request for Quota Single Stage - One E Pending Imp 2023-11-0 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 122,000.00 0.00 2023-04-07 2023-07-02 orrectivo -. Saneamiento y re tions nvelope lementation 5 ary Services PD) forma de cocina en la escuel a n° 9 de Colonia. PBC ESC 278 CANELONES 30 Component 3: Improving Infr Request for Quota 5949-CW-RFQ / Mantenimien Request for Quota Single Stage - One E Pending Imp 2023-02-1 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 110,000.00 0.00 2022-09-13 2022-12-02 to correctivo. Impermeabiliza tions nvelope lementation 5 ary Services PD) ción azotea, Esc. 278 El Dora do, Canelones PBC ESC. 80 TACUAREMBÓ- Component 3: Improving Infr Request for Quota 305958-CW-RFQ / Mantenimi Request for Quota Single Stage - One E Pending Imp 2023-10-0 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 100,000.00 0.00 2023-03-06 2023-06-09 ento correctivo. Sustitución d tions nvelope lementation 2 ary Services PD) e techos en la escuela n° 80 de Tacuarembo. PBC ESC 183 MTDEO- 2022- 305959-CW-RFQ / Mantenimi Component 3: Improving Infr Request for Quota ento correctivo. Impermeabili Request for Quota Single Stage - One E Pending Imp 2022-12-3 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 61,000.00 0.00 2022-09-19 2022-11-25 zación de Tanque , adecuaci tions nvelope lementation 0 ary Services PD) ón sistema bombeo y tanque inferiores, reparación dintele s- Escuela n° 183 de Montevi deo. PBC ESC 112 CERRO LARGO -305957-CW-RFQ / Mantenim Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E 2022-12-0 iento correctivo - Adecuació IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 37,000.00 0.00 Signed 2022-09-06 2022-10-04 tions nvelope 2 n cubierta , Impermeabilizac ary Services PD) ión . Esc. 112, Melo, Cerro La rgo PBC ESC 285 CANELONES-3 05982-CW-RFQ / Mantenimie Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-11-1 nto correctivo - Reparación IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 24,500.00 0.00 2022-09-12 2022-10-11 tions nvelope lementation 1 muros de contención, escuel ary Services PD) a n° 285, Toledo, Canelones PBC ESC 27 FLORES--30598 Component 3: Improving Infr Request for Quota 6-CW-RFQ / Mantenimiento c Request for Quota Single Stage - One E 2022-10-3 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 24,500.00 0.00 Signed 2022-09-08 2022-09-23 orrectivo. Acondicionamiento tions nvelope 1 ary Services PD) de Salón en la escuela n° 27 de Trinidad, Flores PBC ESC.359 Y 361 DE MDE O- 305956-CW-RFQ / Manteni miento correctivo. Imperme Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E 2023-01-1 abilización techo en la escuel IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 60,000.00 0.00 Signed 2022-09-06 2022-11-18 tions nvelope 8 a n° 359 de Montevideo e im ary Services PD) permeabiización por filtracio nes cañería abastecimiento e n la escuela n° 361 PBC ESC 14 PAY 3 RIO NEGR O 305946-CW-RFQ / Manteni miento correctivo. .- Repara Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Under Imple 2023-04-0 ción cubierta liviana en escu IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 12,500.00 0.00 2023-02-07 2023-03-12 tions nvelope mentation 9 ela n° 14 de Paysandu. y rep ary Services PD) aración techo cocina e imper meabilización en la escuela 3 de Rio Negro. PBC ESC. 87 CERRO LARGO- 305961-CW-RFQ / Mantenimi Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-06-0 ento correctivo. Refacción In IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 25,000.00 0.00 2023-04-07 2023-05-02 tions nvelope lementation 2 stalación Sanitaria, desagüe ary Services PD) s de primaria. Escuela n° 87 de Cerro Largo PBC ESC 213/186 CANELONE S 312896-CW-RFQ / Manteni miento correctivo . Escuela 2 Component 3: Improving Infr Request for Quota 13 Jardines de Pando: trabajo Request for Quota Single Stage - One E Pending Imp 2024-02-2 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 180,000.00 0.00 2023-09-02 2023-12-15 s en la fosa séptica - pozo b tions nvelope lementation 3 ary Services PD) ombeo y en la Escuela 186 P arque del Plata: trabajos en l a Red Primaria - nivelación te rreno, portón con entrada ve hículos PBC ESC 6 SORIANO 312900 -CW-RFQ / Mantenimiento cor Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2024-03-0 rectivo Escuela 6 Soriano por IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 150,000.00 0.00 2023-09-02 2023-11-30 tions nvelope lementation 4 trabajos tratamiento más em ary Services PD) isor hacia curso de agua PBC ESC 268 PINAR 312907- Component 3: Improving Infr Request for Quota CW-RFQ / Mantenimiento cor Request for Quota Single Stage - One E Pending Imp 2024-02-2 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 180,000.00 0.00 2023-09-02 2023-12-22 rectivo Escuela 268 Pinar Nor tions nvelope lementation 0 ary Services PD) te, Canelones: trabajos en la planta tratamiento PBC ESC 100 SAN JOSE 3129 Component 3: Improving Infr Request for Quota 09-CW-RFQ / Mantenimiento Request for Quota Single Stage - One E Pending Imp 2023-11-2 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 15,000.00 0.00 2023-09-02 2023-10-01 correctivo Escuela 100 de Sa tions nvelope lementation 4 ary Services PD) n José re ejecución de muro medianero PBC ESC 74 ROCHA -312911 -CW-RFQ / Mantenimiento cor Component 3: Improving Infr Request for Quota rectivo Esc 74 Chuy, Rocha. Request for Quota Single Stage - One E Pending Imp 2023-05-2 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 245,000.00 0.00 2022-09-02 2022-11-28 Reacondicionamiento y refac tions nvelope lementation 9 ary Services PD) ción de 2 aulas, SSHH, despe nsa cocina, depósito, ilumina ción y pintura. PBC ESC.153 MONTEVIDEO- 305978-CW-RFQ / Mantenimi Component 3: Improving Infr Request for Quota ento correctivo.. Ajuste eléctr Request for Quota Single Stage - One E Pending Imp 2023-03-2 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 4,000.00 0.00 2023-02-07 2023-03-10 ica cocina, comedor y dos au tions nvelope lementation 7 ary Services PD) las e iluminación exterior en el local de la escuela n° 153 de Montevideo PBC ESC. 291 CANELONES-3 43143-CW-RFQ / Mantenimie nto correctivo. Retiro de equi Component 3: Improving Infr Request for Quota pamiento y luminarias. Demo Request for Quota Single Stage - One E 2023-03-2 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 5,300.00 0.00 Signed 2023-02-24 2023-03-17 lición revoques fondo losa y li tions nvelope 7 ary Services PD) mpieza. Re colocación lumin arias y equipamiento en el lo cal de la Escuela N° 291 de C anelones Page 2 ESC.36 PINTADO-350338-C Component 3: Improving Infr Request for Quota W-RFQ / Obras de Conexión d Request for Quota Single Stage - One E 2023-04-1 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 3,800.00 0.00 Signed 2023-03-22 2023-03-31 e aulas pre fabricadas e insta tions nvelope 0 ary Services PD) lación de iluminación exterior . Escuela Quintil 1. Request for Quota PBC OBRA ESC. 98 SORIANO Component 3: Improving Infr tions - Small Work 351478-CW-DIR / Reparación Pending Imp 2023-06-1 IBRD / 93310 astructure and Complement Post Direct Selection Direct - National s (Emergency) SP 6,000.00 0.00 2023-03-26 2023-03-31 2023-05-22 de canalón sobre fachada de lementation 1 ary Services D -Non Competiti Escuela N° 98 de Soriano ve National Procure OBRA ESC 190 MTDEO -351 Component 3: Improving Infr ment Document - 489-CW-RFB / Obra Nueva (c Single Stage - One E Pending Imp 2025-05-2 IBRD / 93310 astructure and Complement Post Request for Bids Open - National 1 Envelope proce 2,350,000.00 0.00 2023-10-23 2023-10-23 2023-11-22 2023-12-22 2024-05-21 omedor, 2 aulas y cocina) y nvelope lementation 1 ary Services ss (Non Bank-SPD Reciclaje (9 aulas, administra ) ción y SSHH) PBC- ESC 113 MDEO -35795 Component 3: Improving Infr Request for Quota 9-CW-RFQ / Mantenimiento c Request for Quota Single Stage - One E 2023-05-1 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 6,000.00 0.00 Signed 2023-04-26 2023-05-11 orrectivo - Obras en la Escuel tions nvelope 9 ary Services PD) a n° 113 de Mdeo , abasteci miento de agua. OBRAS ESC 317 MDEO -358 384-CW-RFQ / OBRAS DE MA Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-05-1 NTENIMIENTO INSTALACIÓN IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 3,800.00 0.00 2023-05-03 2023-05-15 tions nvelope lementation 9 DE GAS EN LA ESCUELA 317 ary Services PD) DE MONTEVIDEO- ESCUELA QUINTIL 1 PBC ESC. 186 CANELONES-3 59767-CW-RFQ / Mantenimie Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-07-1 nto Correctivo Esc. 186 Parq IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 5,000.00 0.00 2023-05-09 2023-05-21 tions nvelope lementation 9 ue del Plata, Canelones. Trab ary Services PD) ajos Instalacion Electrica National Procure OBRA ESC. 9 MDEO.-361867 Component 3: Improving Infr ment Document - -CW-RFB / Obra de rehabilita Single Stage - One E Pending Imp 2023-06-3 IBRD / 93310 astructure and Complement Post Request for Bids Open - National 1 Envelope proce 1,300,000.00 0.00 2021-06-22 2021-06-27 2021-08-08 2021-09-07 2021-10-12 ción en Escuela 9 La Teja, De nvelope lementation 0 ary Services ss (Non Bank-SPD partamento de Montevideo ) SO ESC 6 TACUAREMBO-361 Component 3: Improving Infr Request for Bids - 872-CW-RFB / Obras de refac Single Stage - One E Pending Imp 2023-06-3 IBRD / 93310 astructure and Complement Post Request for Bids Open - National Works SPD (after 1,500,000.00 0.00 2021-10-20 2021-10-25 2021-12-06 2022-01-05 2022-02-09 ción y ampliación en la Escue nvelope lementation 0 ary Services prequalification) la 6 Departamento de Tacuar embó PBC OBRA ESC. 292 MDEO. 363682-CW-RFQ / Obra en Es Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-09-0 cuela N° 292 de Montevideo. IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 38,000.00 0.00 2023-06-04 2023-08-03 tions nvelope lementation 7 Impermeabilización tanque s ary Services PD) uperior, suministro tanque in ferior y bomba. PBC OBRA ESC. 187 CANEL. Component 3: Improving Infr Request for Quota - 363685-CW-RFQ / Obra Esc Request for Quota Single Stage - One E Pending Imp 2023-08-3 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 25,000.00 0.00 2023-06-07 2023-08-06 uela N° 187 de Canelones Im tions nvelope lementation 1 ary Services PD) permeabilización tanque de agua. PBC OBRA ESC.108 CANELO NES 368083-CW-RFQ / Mante Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-07-2 nimiento Correctivo, obra res IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 6,000.00 0.00 2023-06-28 2023-07-12 tions nvelope lementation 1 paldo PBC - Esc. 108 de Can ary Services PD) elones. Tanque bombeo para cocina PBC OBRA ESC. 327 MDEO.- 368224-CW-RFQ / Mantenimi Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-10-2 ento correctivo Esc. 327 de IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 38,000.00 0.00 2023-06-28 2023-09-04 tions nvelope lementation 1 Montevideo. Recomposición ary Services PD) de revoques de cielorrasos y jardineras. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOB. DIR. Y MAESTROS 306 885-GO-RFB / Adquisición de mobiliario para docentes. Esc Component 3: Improving Infr Single Stage - One E Pending Impl ritorios y sillas para maestros IBRD / 93310 astructure and Complement Post Request for Bids Open - National 81,000.00 0.00 2022-10-07 2022-10-12 2022-11-11 2022-11-25 2023-02-17 2023-05-19 nvelope ementation y directores de escuelas de T ary Services iempo Completo , mesas par a sala de reuniones y bibliote cas. MOBILIARIO ESCOLAR 30665 9-GO-RFB / Adquisición de m Component 3: Improving Infr Single Stage - One E esas y sillas para aulas de ed IBRD / 93310 astructure and Complement Post Request for Bids Open - National 430,580.00 0.00 Signed 2023-02-13 2022-11-29 2023-02-18 2023-03-20 2022-12-28 2023-04-03 2023-01-20 2023-06-26 2023-10-24 nvelope ucación inicial y primaria, en ary Services Escuelas de Tiempo Complet o. VAJILLA Y ALUMINIO 306661- Component 3: Improving Infr GO-RFB / Adquisición de vajill Single Stage - One E Pending Impl IBRD / 93310 astructure and Complement Post Request for Bids Open - National 68,000.00 0.00 2023-05-08 2023-05-10 2023-06-05 2023-06-19 2023-09-08 2024-01-07 a para comedores escolares nvelope ementation ary Services y equipamiento de menage p ara cocinas de ETC. ELECTRODOMÉSTICOS 3066 Component 3: Improving Infr 66-GO-RFB / Adquisición de h Single Stage - One E Pending Impl IBRD / 93310 astructure and Complement Post Request for Bids Open - National 87,500.00 0.00 2023-04-03 2023-04-05 2023-05-02 2023-05-16 2023-07-31 2023-10-02 eladeras, freezers, licuadoras nvelope ementation ary Services , batidoras para ETC EQUIP. SEMI INDUSTRIAL 30 Component 3: Improving Infr 6667-GO-RFQ / Adquisición d Request for Quota Single Stage - One E Pending Impl IBRD / 93310 astructure and Complement Post Open - National 24,300.00 0.00 2023-04-05 2023-05-15 2023-07-15 e equipamiento semi industri tions nvelope ementation ary Services al cocinas, hornos y anafes, P ara ETC CORTINAS PARA ETC UY-ANE P-321164-GO-RFB / Confecci Component 3: Improving Infr Single Stage - One E ón y colocación de cortinas c IBRD / 93310 astructure and Complement Post Request for Bids Open - National 112,000.00 0.00 Signed 2022-11-04 2022-12-14 2022-11-07 2022-12-02 2022-12-14 2022-12-09 2022-12-29 2023-02-13 2024-12-31 nvelope on barrotes o rieles en Escuel ary Services as de Tiempo Completo LIBROS COLECC. ANDARIEG A 343436-GO-RFQ / Libros pa Component 3: Improving Infr Request for Quota Single Stage - One E Under Imple ra biblioteca de colección an IBRD / 93310 astructure and Complement Post Open - National 2,400.00 0.00 2023-03-06 2023-03-21 2023-04-02 tions nvelope mentation dariega, creación de espacio ary Services lúdico recreativo en escuela N° 6 de Tacuarembó Page 3 EQUIP AUDIVISUALES DSPE- Component 1: Improving Te Request for Quota Single Stage - One E Under Imple 347492-GO-RFQ / Equipamie IBRD / 93310 acher Training and Pedagogi Post Open - National 8,500.00 0.00 2023-03-13 2023-04-19 2023-07-19 tions nvelope mentation nto Audiovisual para streami cal Content ng para la DSPE LIC. ZOOM EDUCATIVO 2023 -357617-GO-DIR / Renovació Component 4: Strengthening n de 23 licencias de Zoom Ed Under Imple IBRD / 93310 Evaluation Systems and Proj Post Direct Selection Direct - National 2,525.00 0.00 2023-04-23 2023-04-25 2023-04-23 2023-04-25 2023-05-23 2024-05-23 ucativo que permitan cumplir mentation ect Management con la planificación de los cur sos de Formación en servicio para el 2023 EQUIP. AUDIOVISUAL 30668 Component 3: Improving Infr 2-GO-RFQ / Adquisición de eq Request for Quota Single Stage - One E Under Imple IBRD / 93310 astructure and Complement Post Open - National 15,000.00 0.00 2023-04-28 2023-05-22 2023-08-21 uip. audiovisual. parlantes, p tions nvelope mentation ary Services royectores, para Escuelas de Tiempo Completo. DSPE EQUIP. SALA STREAMI NG 361828-GO-RFQ / Nuevo Component 1: Improving Te Request for Quota Single Stage - One E Pending Impl Solicitud de Cotización para l IBRD / 93310 acher Training and Pedagogi Post Open - National 6,250.00 0.00 2023-05-23 2023-06-26 2023-09-25 tions nvelope ementation a compra de equipamiento a cal Content udiovisual para sala de strea ming para la DSPE. PIZARRAS MÓVILES PARA ET Component 3: Improving Infr Single Stage - One E Pending Impl C 363486-GO-RFB / Adquisici IBRD / 93310 astructure and Complement Post Request for Bids Open - National 80,000.00 0.00 2023-06-01 2023-06-06 2023-06-18 2023-06-22 2023-08-21 2023-11-19 nvelope ementation ón de pizarrones móviles par ary Services a ETC EQUIP PSICOMOTRICIDAD-36 3524-GO-RFB / Adquisición M Component 3: Improving Infr aterial didáctico para salas d Single Stage - One E Pending Impl IBRD / 93310 astructure and Complement Post Request for Bids Open - National 85,280.00 0.00 2023-05-29 2023-05-30 2023-06-14 2023-06-23 2023-08-28 2023-11-27 e psicomotricidad, juego y m nvelope ementation ary Services ovimientos. Se equipara apro ximadamente 40 escuelas . MOBILIARIO 10 Y 11 AÑOS-3 66129-GO-RFB / Adquisición Component 3: Improving Infr Single Stage - One E Pending Impl de sillas y mesas educación IBRD / 93310 astructure and Complement Post Request for Bids Open - National 240,000.00 0.00 2023-06-14 2023-06-15 2023-07-17 2023-07-21 2023-10-02 2023-12-29 nvelope ementation primaria de 10 y 11 años par ary Services a Escuelas de Tiempo Compl eto LIBROS C.ANDARIEGA - 3683 03-GO-RFQ / Adquisicion Libr os Coleccion Andariega para Component 3: Improving Infr Request for Quota Single Stage - One E Pending Impl las Esc. 9 y 190 de Montevi IBRD / 93310 astructure and Complement Post Open - National 5,200.00 0.00 2023-07-03 2023-07-20 2023-08-31 tions nvelope ementation deo , Esc 5 de Cerro Largo y ary Services completar libros que quedaro n desierto en llamado ID 343 436 (Esc. 6 de Tacuarembó) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONGRESO CEIBAL 2023-30 6197-NC-RFQ / Congreso CEI Component 1: Improving Te Request for Quota Single Stage - One E Pending Impl BAL, Noviembre 2023. 200 p IBRD / 93310 acher Training and Pedagogi Post Open - National 24,000.00 0.00 2023-08-13 2023-09-23 2023-11-13 tions nvelope ementation articipantes por día, (Alojami cal Content ento, cena, almuerzo y 2 coff ee break) JORN. FORM. INSP.2023 DSP E 306198-NC-RFQ / Jornada d e formación para inspectores de la Dir. Sec. de Planificació Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IBRD / 93310 Post Open - National 18,000.00 0.00 2023-07-28 2023-09-01 2023-10-26 n Educ. 7 sedes: Salto, Coloni Management Teams tions nvelope ementation a, Durazno, Maldonado, Cane lones y 2 en Montevideo. dos encuentros en set y nov de 2 023 alojamiento y alimentaci ón IMPRESION LIBRO FS 2022-3 Component 1: Improving Te 06368-NC-RFQ / PAEPU - Imp Request for Quota Single Stage - One E Pending Impl IBRD / 93310 acher Training and Pedagogi Post Open - National 5,900.00 0.00 2023-03-11 2023-04-28 2023-05-29 resión Libro "Formación en S tions nvelope ementation cal Content ervicio 2022", 2000 ejemplar es FORM.Y COORD 2023- PAEP U -306375-NC-RFQ / Jornada Component 1: Improving Te Request for Quota Single Stage - One E Pending Impl de Formadores y Coordinado IBRD / 93310 acher Training and Pedagogi Post Open - National 2,900.00 0.00 2023-06-09 2023-10-02 2023-11-22 tions nvelope ementation res 2023, 2 dias, 180 particip cal Content antes (Desayuno y coffee Bre ak) SEMINARIO 2023- PAEPU-30 Component 1: Improving Te 6376-NC-RFQ / Seminario Do Request for Quota Single Stage - One E Pending Impl IBRD / 93310 acher Training and Pedagogi Post Open - National 42,200.00 0.00 2023-08-07 2023-10-27 2023-11-27 centes 2023. Dos dias, 260 p tions nvelope ementation cal Content articipantes (Alojamiento, ali mentación y sala) JORNADA TUTORES 2023- D SPE-307160-NC-RFQ / Jornad Component 2: Strengthening Request for Quota Single Stage - One E a con Tutores de la Dirección IBRD / 93310 Post Open - National 2,000.00 0.00 Signed 2023-08-20 2023-09-09 2023-10-30 Management Teams tions nvelope Sectorial de Planificación Edu cativa 60 participantes. Alim entación INSPEC Y DIRECT 2023-PAEP U-306373-NC-RFQ / Jornada d Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl e Inspectores y Directores 20 IBRD / 93310 Post Open - National 2,300.00 0.00 2023-07-08 2023-08-18 2023-10-08 Management Teams tions nvelope ementation 23, un dia, 55 participantes ( desayuno, coffee break, alm uerzo y sala) DSPE IMPRESION LIB 306899 -GO-RFQ 2023 / Impresión lib Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl rillos para Inspectores y Dire IBRD / 93310 Post Open - National 10,000.00 0.00 2023-08-09 2023-09-05 2023-10-05 Management Teams tions nvelope ementation ctores solicitados por la Direc ción Sectorial de Planificació n Estratégica DSPE JORNADA MENTORES - 335388-NC-RFQ / Jornada a r Component 2: Strengthening Request for Quota Single Stage - One E Under Imple ealizarse en 2 instancias de 3 IBRD / 93310 Post Open - National 30,500.00 0.00 2023-01-13 2023-01-26 2023-03-03 Management Teams tions nvelope mentation días. 150 participantes por d ia. Alojamiento, alimentación y traslados. DSPE JORNADA INSP. ZONA 335389-NC-RFQ / Jornada de Inspectores de zona de la DG Component 2: Strengthening Request for Quota Single Stage - One E Under Imple IBRD / 93310 Post Open - National 10,500.00 0.00 2023-01-13 2023-01-26 2023-02-09 EIP a realizarse el 9 de febrer Management Teams tions nvelope mentation o de 2023. 260 participantes. Alojamiento, Alimentación y t raslado Page 4 DSPE JORNADA INSP/MENTO RES 343442-NC-RFQ / Alimen Component 2: Strengthening Pending Impl tación y hospedaje para insp IBRD / 93310 Post Direct Selection Direct - National 2,800.00 0.00 2023-02-17 2023-02-17 2023-03-01 2023-03-03 Management Teams ementation ectores participantes en la Jo rnada de Mentores del 3 de marzo de 2023 EDICIÓN LIBRO F.S. 2022 - 3 Component 1: Improving Te Request for Quota Single Stage - One E Pending Impl 47804-NC-RFQ / Edición de li IBRD / 93310 acher Training and Pedagogi Post Open - National 2,000.00 0.00 2023-03-24 2023-05-07 2023-07-06 tions nvelope ementation bro "Formación en servicio 2 cal Content 022- PAEPU " IMPRESIÓN LIBRO 349293-N Component 1: Improving Te C-DIR / Impresión de 500 eje Pending Impl IBRD / 93310 acher Training and Pedagogi Post Direct Selection Direct - National 2,800.00 0.00 2023-03-20 2023-03-21 2023-03-28 2023-04-27 mplares del libro "Un camino ementation cal Content recorrido y nuevas expectati vas". JORNADA TRANSF CURRICUL AR-363702-NC-RFQ / Encuent Component 1: Improving Te Request for Quota Single Stage - One E Pending Impl ro en territorio. jornada Tran IBRD / 93310 acher Training and Pedagogi Post Open - National 2,500.00 0.00 2023-06-01 2023-06-13 2023-06-30 tions nvelope ementation sformación Curricular- Logísti cal Content ca necesaria para dicha Jorna da. DSPE JORNADA FORM INSP. 365048-NC-RFQ / Primera edi ción del curso correspondient Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl e al Programa de formación e IBRD / 93310 Post Open - National 12,500.00 0.00 2023-06-08 2023-06-20 2023-06-30 Management Teams tions nvelope ementation n gestión para Inspectores d e la ANEP (2023 - 2024).. Ser vicio de Alimentación y aloja miento para 300 participante s. DIEE IMPLE.O. T. CURRICULA 368081-NC-RFQ / Contratació n de Empresa consultora par Component 4: Strengthening Request for Quota Single Stage - One E a realizar grupos de discusió IBRD / 93310 Evaluation Systems and Proj Post Open - National 18,300.00 0.00 Canceled 2023-07-03 2023-08-04 2023-12-29 tions nvelope n con docentes de la ANEP e ect Management n el marco de las actividades del Observatorio de la Transf ormación Curricular Integral. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DIEE-IMPLEMENTACIÓN. OTI -368967-CS-FBS / CONTRATA CIÓN DE UNA CONSULTORÍA Component 4: Strengthening PARA REALIZAR GRUPOS DE Fixed Budget Sele Pending Impleme IBRD / 93310 Evaluation Systems and Proj Post Open - National 18,300.00 0.00 2023-06-26 2023-06-28 2023-07-05 2023-07-11 2023-07-24 2023-07-28 2023-08-30 2024-10-31 DISCUSIÓN CON DOCENTES ction ntation ect Management DE LA ANEP EN EL MARCO D E LAS ACTIVIDADES DEL OBS ERVATORIO DE LA TRANSFO RMACIÓN CURRICULAR INTE GRAL INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AGRIM. 68 DURAZNO -30616 Component 3: Improving Infr 8-CS-INDV 2022 / Consultoría Individual Consult Under Implement IBRD / 93310 astructure and Complement Post Limited 1,500.00 0.00 2022-08-10 2022-08-16 2022-08-20 2022-10-01 2022-11-01 Agrimensura para la Escuela ant Selection ation ary Services 68 Departamento de Durazn o CIVIL ESC 68 DURAZNO 306 Component 3: Improving Infr 215-CS-INDV 2022 / Consulto Individual Consult Under Implement IBRD / 93310 astructure and Complement Post Limited 6,000.00 0.00 2022-11-11 2022-11-17 2022-11-21 2023-01-02 2023-02-01 ría Proyecto de Estructura pa ant Selection ation ary Services ra la Escuela 68 Departamen to de Durazno ELECT ESC 68 DURAZNO 30 Component 3: Improving Infr 6216-CS-INDV 2022 / Consult Individual Consult IBRD / 93310 astructure and Complement Post Limited 5,000.00 0.00 Canceled 2022-11-11 2022-11-17 2022-11-21 2023-01-02 2023-02-01 oría Eléctrica para la Escuela ant Selection ary Services 68 Departamento de Durazn o METRAJE 68 DURAZNO 3062 Component 3: Improving Infr 17-CS-INDV 2022 / Consultorí Individual Consult Under Implement IBRD / 93310 astructure and Complement Post Limited 2,500.00 0.00 2022-12-11 2022-12-17 2022-12-21 2023-02-01 2023-03-03 a Metraje para la Escuela 68 ant Selection ation ary Services Departamento de Durazno SANITAR 68 DURAZNO -306 Component 3: Improving Infr 221-CS-INDV 2022 / Consulto Individual Consult IBRD / 93310 astructure and Complement Post Limited 3,500.00 0.00 Canceled 2022-11-11 2022-11-17 2022-11-21 2023-01-02 2023-02-01 ría Sanitaria para la Escuela ant Selection ary Services 68 Departamento de Durazn o BOMBEROS 68 DURAZNO 30 Component 3: Improving Infr 6223-CS-INDV 2022 / Consult Individual Consult Under Implement IBRD / 93310 astructure and Complement Post Limited 2,500.00 0.00 2022-11-11 2022-11-17 2022-11-21 2023-01-02 2023-02-01 oría Bomberos para la Escuel ant Selection ation ary Services a 68 Departamento de Duraz no CIVIL 301 CANELONES 3062 Component 3: Improving Infr 24-CS-INDV 2022 / Consultorí Individual Consult IBRD / 93310 astructure and Complement Post Limited 3,000.00 0.00 Canceled 2022-08-10 2022-08-16 2022-08-20 2022-10-01 2022-10-31 a Poyecto Esctructura para la ant Selection ary Services Escuela 301 Departamento d e Canelones METRAJ 301 CANELONES 30 Component 3: Improving Infr 6225-CS-INDV 2022 / Consult Individual Consult IBRD / 93310 astructure and Complement Post Limited 1,500.00 0.00 Canceled 2022-08-10 2022-08-16 2022-08-20 2022-10-01 2022-10-31 oría Metraje para la Escuela ant Selection ary Services 301 Departamento de Canelo nes CIVIL ESC 42 AIGUA 306230- Component 3: Improving Infr CS-INDV 2022 / Consultoría P Individual Consult Pending Impleme IBRD / 93310 astructure and Complement Post Limited 4,000.00 0.00 2022-12-11 2022-12-17 2022-12-21 2023-02-01 2023-03-03 royecto Estructura para la Es ant Selection ntation ary Services cuela 42 Aiguá, Departament o de Maldonado UEP EXPERTO TECNICO OBR Component 4: Strengthening AS-305386-CS-INDV / Contrat Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 207,000.00 0.00 2022-08-18 2022-12-01 2022-08-28 2022-11-04 2022-12-30 2027-06-30 acion de un Experto Técnico ant Selection ation ect Management 40hrs Area Obras del 1/1/23 al 30/6/27 UEP EXP. B AREA PROYECTO Component 4: Strengthening Individual Consult Under Implement S-305353-CS-INDV / Contrata IBRD / 93310 Evaluation Systems and Proj Post Direct - National 170,000.00 0.00 2022-08-18 2022-12-01 2022-08-28 2022-11-04 2022-12-30 2027-06-30 ant Selection ation ción de 1 Experto "B" 40 hrs ect Management - Área Proyecto Page 5 UEP EXP TEC PLANIFICACION Component 4: Strengthening -305371-CS-INDV / Contratac Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 207,000.00 0.00 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 ión -de un Experto Técnico 4 ant Selection ation ect Management 0 hrs Planificación Planta Físi ca del 1/1/23 al 30/6/27 UEP EXPERTO B - OBRAS 30 Component 4: Strengthening 5389-CS-INDV / Contratación Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 170,000.00 0.00 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 de 1 Experto "B" 40 hrs Obra ant Selection ation ect Management s del 1/1/23 al 30/6/27 UEP EXP B ADQUISICIONES 3 Component 4: Strengthening 05612-CS-INDV / Contratació Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 170,000.00 0.00 Under Review 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 n de 1 Experto B 40 hrs para ant Selection ect Management el Área Adquisiciones del 1/1 /23 al 30/6/27 UEP 2 EXPERTOS A ADQUIS- Component 4: Strengthening 305405-CS-INDV / Contrataci Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 380,000.00 0.00 Under Review 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 on 2 Expertos "A" 40hrs Are ant Selection ect Management a Adquisiciones del 1/1/23 al 30/6/27 UEP EXP B MANTENIMIENTO- 306892-CS-INDV / Contrataci Component 4: Strengthening Individual Consult Under Implement ón de 1 Exp B área de Opera IBRD / 93310 Evaluation Systems and Proj Post Direct - National 170,000.00 0.00 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 ant Selection ation ciones y Mantenimiento - Pla ect Management nta Fisica. Del 1/1/23 al 30/6/ 27 METRAJE ESC 42 AIGUA 306 232-CS-INDV 2022 / Consulto Component 3: Improving Infr Individual Consult Pending Impleme r Arquitecto Metrajista para IBRD / 93310 astructure and Complement Post Limited 1,500.00 0.00 2023-01-08 2023-01-14 2023-01-18 2023-03-01 2023-03-31 ant Selection ntation Obra en la Escuela 42 Aiguá, ary Services Departamento de Maldonad o D.O. ESC 114 MDEO 306234 Component 3: Improving Infr Pending Impleme -CS-CDS 2022 / Dirección de IBRD / 93310 astructure and Complement Post Direct Selection Direct - National 14,500.00 0.00 2023-02-08 2023-02-19 2023-04-01 2024-05-02 ntation Obra Escuela 114 de Montevi ary Services deo UEP EXP. TEC AREA PROYEC Component 4: Strengthening TO-305347-CS-IND / Contrata Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 207,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ción de un Experto Técnico ant Selection ation ect Management 40 hrs para Área de Proyecto el 1/1/23 al 30/6/27 UEP EXP TEC INFORMATICO Component 4: Strengthening 305624-CS-INDV / Contrataci Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 104,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ón de 1 Experto Técnico 20 ant Selection ation ect Management hrs Área Informática del 1/1/ 23 al 30/6/27 UEP 2 EXPERTOS A OBRA-30 Component 4: Strengthening 5922-CS-INDV / Contratación Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 380,000.00 0.00 2022-08-18 2022-12-01 2022-08-28 2022-11-04 2022-12-30 2027-06-30 de 2 Expertos "A" en Área Ob ant Selection ation ect Management ras del 1/1/23 al 30/6/27 UEP DIRECTOR TEC ADQUISI .-305403-CS-INDV / Contrata Component 4: Strengthening Individual Consult ción de 1 Director Técnico 4 IBRD / 93310 Evaluation Systems and Proj Post Direct - National 223,000.00 0.00 Under Review 2022-08-18 2022-12-01 2022-08-28 2022-11-04 2022-12-30 2027-06-30 ant Selection 0 hrs- Coordinador Área Adq ect Management uisiciones del 1/1/23 al 30/6/ 27 UEP 2 EXP. A PROYECTOS-30 5352-CS-INDV / Contratación Component 4: Strengthening Individual Consult Under Implement de 2 Expertos A 40 hrs- Arq IBRD / 93310 Evaluation Systems and Proj Post Direct - National 380,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ant Selection ation uitectos para el área de Proy ect Management ectos - del 1/1/23 al 30/6/27 UEP EXP. TECNICO PPP-ANEP Component 4: Strengthening -305659-CS-INDV / Contratac Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 207,000.00 0.00 Under Review 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ion Experto Tecnico 40hrs - ant Selection ect Management PPP del 1/1/23 al 30/6/27 UEP EXP. C -DIEE-ANEP-3059 45-CS-INDV / Contratación de Component 4: Strengthening Individual Consult Under Implement 1 Experto "C" 20 hs - para tr IBRD / 93310 Evaluation Systems and Proj Post Direct - National 78,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ant Selection ation abajar junto al equipo de la ect Management DIEE - ANEP del 1/1/23 al 30/ 6/27 UEP EXP C EQUIPAMIENTO 3 05617-CS-INDV / Contratació Component 4: Strengthening Individual Consult Under Implement n DE 1 Experto "C" 40 hrs p IBRD / 93310 Evaluation Systems and Proj Post Direct - National 155,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ant Selection ation ara el área de Planificación ect Management y Equipamiento del 1/1/23 al 30/6/27 UEP EXP TEC MONITOREO 3 Component 4: Strengthening 05618-CS-INDV / Contratació Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 104,000.00 0.00 Under Review 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 n de 1 Experto Técnico 20 h ant Selection ect Management rs para el Área Monitoreo del 1/1/23 al 30/6/27 UEP EXPERTO A INFORMATIC Component 4: Strengthening A 305625-CS-INDV / Contrata Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 190,000.00 0.00 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 ción de 1 Experto "A" 40 hrs ant Selection ation ect Management en el Área Informática del 1/1/23 al 30/6/27 UEP EXP. B PLANIFICACION 3 Component 4: Strengthening 05384-CS-INDV / Contratació Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 170,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 n de 1 Experto "B" 40 hrs Pl ant Selection ation ect Management anificación Planta Física del 1 /1/23 al 30/6/27 UEP EXP TEC MANTENIMIENT O 305392-CS-IND / Contratac Component 4: Strengthening Individual Consult Under Implement ión de un Experto Técnico 40 IBRD / 93310 Evaluation Systems and Proj Post Direct - National 207,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ant Selection ation hrs Area de Operaciones y M ect Management antenimiento del 1/1/23 al 30 /6/27 UEP EXP A EQUIPAMIENTO 3 05615-CS-INDV / Contratació Component 4: Strengthening Individual Consult Under Implement n de 1 Experto "A" 40 hrs Ár IBRD / 93310 Evaluation Systems and Proj Post Direct - National 190,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ant Selection ation ea de Planificación y Equipa ect Management miento del 1/1/23 al 30/6/27 UEP COORD. GRAL-305342- Component 4: Strengthening CS-INDV / Contratación de C Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 250,000.00 0.00 Under Review 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 oordinador General 40 hrs de ant Selection ect Management l 1/1/23 al 30/6/27 Page 6 UEP DIR TEC JURIDICA 305 Component 4: Strengthening 655-CS-IND / Contratación d Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 167,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 e 1 Director Técnico 30 hrs ant Selection ation ect Management Asesoría Jurídica del 1/1/23 al 30/6/27 UEP EXP.TECN EQUIPAMIEN TO 305614-CS-IND / Contrata Component 4: Strengthening Individual Consult Under Implement ción de 1 Experto Técnico 4 IBRD / 93310 Evaluation Systems and Proj Post Direct - National 207,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ant Selection ation 0 hrs Área Planificación y Eq ect Management uipamiento del 1/1/23 al 30/6 /27 UEP EXP A MONITOREO 305 Component 4: Strengthening 620-CS-INDV / Contratación Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 190,000.00 0.00 Under Review 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 de 1 Experto "A" 40 hrs Área ant Selection ect Management Monitoreo del 1/!/23 al 30/6/ 27 UEP EXP B OPERAC Y MANTE N-305400-CS-INDV / Contrata Component 4: Strengthening Individual Consult Under Implement cion de 1 Expertos "B" 40 hrs IBRD / 93310 Evaluation Systems and Proj Post Direct - National 170,000.00 0.00 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 ant Selection ation Area Operaciones y Manteni ect Management miento del 1/1/23 al 30/6/27 UEP 2 EXP A MANTENI 3053 Component 4: Strengthening 96-CS-INDV / Contratación de Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 380,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 2 Expertos "A" 40 hrs Área O ant Selection ation ect Management peraciones y Mantenimiento del 1/1/23 al 30/6/27 UEP 2 EXP.A PLANIFICACION Component 4: Strengthening 305381-CS-INDV / Contrataci Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 380,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ón de 2 Expertos "A" 40 hrs ant Selection ation ect Management Área Planificación Planta Físi ca de 1/1/23 al 30/6/27 UEP ASIST TEC A INFORM 3 Component 4: Strengthening 05652-CS-INDV / Contratació Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 132,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 n de 1 Asistente Técnico "A ant Selection ation ect Management " 40 hrs Área Informática del 1/1/23 al 30/6/27 UEP EXPERTO A INFORMATIC Component 4: Strengthening A 305653-CS-INDV / Contrata Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 95,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ción de Experto "A" 20 hrs Ár ant Selection ation ect Management ea Informática del 1/1/23 al 3 0/6/27 D.O. SORIANO/COLONIA -31 1367-CS-CDS / Confección de Recaudos y Dirección de obr a para la Escuela N°65 Merce Component 3: Improving Infr Under Implement des. Dirección de Obra en la IBRD / 93310 astructure and Complement Post Direct Selection Direct - National 8,000.00 0.00 2022-08-29 2022-08-30 2022-10-17 2023-12-29 ation Esc. N° 9 La Paz y n° 126 Nu ary Services eva Helvecia de Colonia y rec uados y DO planes de mante nimiento en aprox 10 Escuel as de Colonia y 10 de Sorian o DGEIP EVALUACION EDUCAT . 312919-CS-INDV / Asesor e Component 4: Strengthening Individual Consult Pending Impleme n el campo de la Evaluación IBRD / 93310 Evaluation Systems and Proj Post Open - National 190,000.00 0.00 2022-09-26 2022-11-04 2022-12-09 2022-12-23 2027-06-30 ant Selection ntation Educativa, para la División d ect Management e Planeamiento Educativo de la DGEIP - ANEP DGEIP INVESTIG EDUCATIVA -312920-CS-INDV / Asesor en Component 4: Strengthening el campo de investigación ed Individual Consult Pending Impleme IBRD / 93310 Evaluation Systems and Proj Post Open - National 190,000.00 0.00 2022-09-12 2022-11-07 2022-12-09 2022-12-23 2027-06-30 ucativa que trabajara compa ant Selection ntation ect Management rtido entre la División de Plan eamiento Educativo de la DG EIP - ANEP y el PAEPU UEP DIRECTOR TEC FINANZA S 305613-CS-INDV / Contrata Component 4: Strengthening Individual Consult Under Implement ción de 1 Director Técnico 4 IBRD / 93310 Evaluation Systems and Proj Post Direct - National 223,000.00 0.00 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 ant Selection ation 0 hrs - Coordinador Área Fina ect Management nzas del 1/1/23 al 30/6/27 ARQ DIR OBRA 2022-27-300 884-CS-INDV / Contratación Directores de Obras 2022 - 2 027 , 50 D.O. de Construcció Component 3: Improving Infr Individual Consult Under Implement n y/o rehabilitación , 60 D.O. IBRD / 93310 astructure and Complement Post Open - National 350,000.00 0.00 2022-08-26 2022-12-21 2022-12-22 2023-02-10 2027-06-30 ant Selection ation obras de mantenimiento pre ary Services ventivo y correctivo en locale s escolares de Tiempo Pedag ógico ampliado ( T.C.,T. ext., Jardines de Jornada Completa , Aprender) AS TEC ADQUISICIONES -319 Component 4: Strengthening 052-CS-INDV / Contratación d Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 218,000.00 0.00 2022-09-30 2022-10-10 2022-12-16 2023-02-10 2027-06-30 e 1 Experto "B" 40 hrs Área A ant Selection ation ect Management dquisiciones Vigencia 1/1/23 al 30/6/27 DIEE – ASIST CCSS -319059- CS-INDV / Contratación de u Component 4: Strengthening n Asistente CCSS - Técnico " Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 29,000.00 0.00 Canceled 2022-09-30 2022-10-10 2022-11-16 2023-01-02 2023-12-31 A" 40 hrs para la Dirección d ant Selection ect Management e Investigación Evaluación E ducativa – ANEP del 1/1/23 al 31/12/2023 DIEE - ASIST COMUNIC -3190 64-CS-INDV / Contratación de un Asistente Comunicación Component 4: Strengthening Individual Consult Pending Impleme Experto "C" 20 hrs para la Di IBRD / 93310 Evaluation Systems and Proj Post Direct - National 8,000.00 0.00 2022-09-30 2022-10-10 2022-11-16 2023-01-02 2023-12-31 ant Selection ntation rección de Investigación Eval ect Management uación Educativa – ANEP. Vig encia 6 meses: del 1/4/23 al 31/8/2023 DO ESC 74 Y 29 ROCHA -321 165-CS-INDV / Director de Ob Component 3: Improving Infr Individual Consult Under Implement ra para la Escuela n° 74 de la IBRD / 93310 astructure and Complement Post Open - National 9,500.00 0.00 2022-10-17 2022-10-18 2022-11-28 2022-12-02 2023-03-31 ant Selection ation Barra del Chuy y Esc 29 La C ary Services oronilla - Departamento de R ocha PONENTE EVAL, COMPETENC IA-332229-CS-INDV / Contrat ación consultor para el coloq uio interactivo con Formació Component 2: Strengthening Under Implement IBRD / 93310 Post Direct Selection Direct - National 580.00 0.00 2022-12-27 2022-12-27 2023-02-17 2023-02-27 n en Servicio del PAEPU, el dí Management Teams ation a 27 de febrero, actividad qu e es parte de una propuesta coordinada con autoridades de la ANEP- DGEIP Y CFP . Page 7 D.O. ESC. 80 TACUAREMBÓ 341291-CS-CDS / Confección de recaudos y dirección de o bra de la Escuela N° 80 de Ta Component 3: Improving Infr Under Implement cuarembó, en base a la lista IBRD / 93310 astructure and Complement Post Direct Selection Direct - National 3,200.00 0.00 2023-02-13 2023-02-20 2023-03-22 2023-09-18 ation de prelación de Directores de ary Services Obra por región en todo el Ur uguay, resultado de una llam ado abierto y homologado po r el CODICEN del año 2019. DIEE - PROF CCSS 319055-C S-INDV / Dos profesionales d e las Ciencias Sociales Senior para el análisis y el reporte d Component 4: Strengthening Individual Consult e resultados con experiencia IBRD / 93310 Evaluation Systems and Proj Post Direct - National 68,000.00 0.00 Canceled 2022-09-30 2022-10-10 2022-11-16 2023-01-02 2024-01-03 ant Selection en procesar información y el ect Management aboración de informes para l a Dirección de Investigación Evaluación Educativa - ANEP Experto C 40 horas. DIEE ANALISTA ESTAD-3190 62-CS-INDV / Contratación de Component 4: Strengthening un Analista Estadístico Exper Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 34,000.00 0.00 Canceled 2022-09-30 2022-10-10 2022-11-16 2023-01-02 2023-12-31 to "C" 40 hrs para la Direcci ant Selection ect Management ón de Investigación Evaluaci ón Educativa – ANEP del 1/1/ 23 al 31/12/2023 DIEE - PROF. CCSS 341374-C S-INDV / Dos profesionales d e las Ciencias Sociales Senior para el análisis y el reporte d Component 4: Strengthening Individual Consult Under Implement e resultados con experiencia IBRD / 93310 Evaluation Systems and Proj Post Open - National 72,000.00 0.00 2023-02-20 2023-03-29 2023-03-29 2023-05-02 2024-04-30 ant Selection ation en procesamiento de informa ect Management ción y elaboración de inform es para la Dirección de Inves tigación y Evaluación Educati va - ANEP Experto C 40 horas . TUTORES CURSO INSP. 3413 01-CS-CQS / Llamado a aspir antes para la Contratación d Component 2: Strengthening Individual Consult Under Implement IBRD / 93310 Post Open - National 165,000.00 0.00 2023-02-09 2023-03-17 2023-03-11 2023-04-01 2023-07-03 2024-12-31 e 10 tutores para cursos de F Management Teams ant Selection ation ormación de Inspectores de ANEP. Por tres períodos de 6 meses, renovables hasta 202 4 ESP. MODULO 1 COHORTE 2 - 349681-CS-CDS / DSPE-ANE P, Doc. Especialista a cargo del Módulo Centro educativo, Component 2: Strengthening Under Implement familia y comunidad, para el IBRD / 93310 Post Direct Selection Direct - National 800.00 0.00 2023-03-19 2023-03-28 2023-03-22 2023-04-21 2023-04-29 Management Teams ation 2do Cohorte a llevarse a cab o en abril de 2023, del curso correspondiente al Programa de formación en gestión para directores de los centros edu cativos CONSULTOR VERIFICADOR - 351846-CS-INDV / Consultori Component 4: Strengthening Individual Consult Under Implement a Individual para verificación IBRD / 93310 Evaluation Systems and Proj Post Limited 1,300.00 0.00 2023-03-27 2023-03-31 2023-04-14 2023-05-19 2023-06-05 ant Selection ation de Indicadores con Condicion ect Management es basadas en desempeño DIEE ANALISTA ESTD-34135 1-CS-INDV / Llamado para la contratación de dos analistas estadístico para la muestra y Component 4: Strengthening Individual Consult Under Implement el procesamiento de informa IBRD / 93310 Evaluation Systems and Proj Post Open - National 72,000.00 0.00 2023-03-31 2023-05-19 2023-05-19 2023-06-22 2024-06-20 ant Selection ation ción con conocimiento de R y ect Management tecnica de Muestreo para la Dirección de Investigación y Evaluación Educativa. Contra tación por un año. DIEE ENAP E y Sea+ DSPE MÓD. GEST. EDUC.202 3-357783-CS-CDS / Contratac ión Docente especializado p ara el módulo Gestión Educat Component 2: Strengthening Under Implement iva orientada por datos para l IBRD / 93310 Post Direct Selection Direct - National 2,200.00 0.00 2023-04-23 2023-05-03 2023-06-11 2023-08-31 Management Teams ation a toma de decisiones, para el 3er. Cohorte del Programa d e Formación Directores y 1er cohorte para el Programa de Formación de Inspectores. DSPE MÓD HERR GESTIÓN-2 3 357787-CS-CDS / Contratac ión consultor Mag. Mora Pode stá Docente especializada pa Component 2: Strengthening Under Implement IBRD / 93310 Post Direct Selection Direct - National 8,700.00 0.00 2023-04-23 2023-05-03 2023-06-11 2023-09-28 ra el módulo herramientas p Management Teams ation ara la gestión educativa 2do. y 3er. cohorte PFD y 1er. coh orte PFI y Formación en Servi cio Centros María Espínola UEP TEC SANITARIO--357956 Component 4: Strengthening -CS-INDV / Contratación de u Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Open - National 150,000.00 0.00 2023-04-26 2023-05-24 2023-06-23 2023-08-01 2027-06-30 n Exp C - Técnico Sanitario p ant Selection ation ect Management ara el componente Planta Fí sica del PAEPU. UEP TEC ELECTRICISTA-3579 Component 4: Strengthening 58-CS-INDV / Contrato de un Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Open - National 150,000.00 0.00 Canceled 2023-04-26 2023-04-26 2023-05-27 2023-06-26 2023-08-04 2027-06-30 Técnico Electricista para el c ant Selection ect Management omponente Planta Física del PAEPU DSPE CONS LIC. COMUNICAC IO-359768-CS-CDS / LLamad o Consultor Licenciado en Co Component 2: Strengthening Individual Consult municación, Experto "B", 24h IBRD / 93310 Post Open - National 100,000.00 0.00 Canceled 2023-05-22 2023-06-19 2023-06-23 2023-07-31 2027-06-30 Management Teams ant Selection rs., como apoyo desde una p erspectiva de comunicación al Proceso de Transformació n Educativa. CIVIL ESC. 190 MTDEO-3617 92-CS-INDV / Consultoría par Component 3: Improving Infr Individual Consult Pending Impleme a realizar el proyecto de calc IBRD / 93310 astructure and Complement Post Limited 9,800.00 0.00 2023-05-19 2023-05-25 2023-05-29 2023-07-10 2023-08-09 ant Selection ntation ulo estructural de la obra en l ary Services a Escuela N°190 de Montevi deo SANITARIA ESC. 190 MTDEO- 361796-CS-INDV / Consultorí Component 3: Improving Infr Individual Consult Pending Impleme a para llevar a cabo el proy IBRD / 93310 astructure and Complement Post Limited 3,700.00 0.00 2023-05-19 2023-05-25 2023-05-29 2023-07-10 2023-08-09 ant Selection ntation ecto de la Instalación Sanitari ary Services o para las obras en la Esc. 1 90 de Montevideo Page 8 ELECTRICISTA ESC 190 MTD E-361798-CS-INDV / Consulto Component 3: Improving Infr Individual Consult Pending Impleme ría para realizar proyecto de l IBRD / 93310 astructure and Complement Post Limited 7,400.00 0.00 2023-05-19 2023-05-25 2023-05-29 2023-07-10 2023-08-09 ant Selection ntation a Instalación Eléctrica para l ary Services a obra a realizarse en la Esc. 190 de Montevideo. BOMBERO ESC. 190 MTDEO- 361799-CS-INDV / Consultarí Component 3: Improving Infr Individual Consult Pending Impleme a para proyecto de Instalació IBRD / 93310 astructure and Complement Post Limited 2,200.00 0.00 2023-05-19 2023-05-25 2023-05-29 2023-07-10 2023-08-09 ant Selection ntation n protección contra incendio ary Services , para Esc. 190 de Montevide o METRAJISTA ESC. 190 MTDE O-361800-CS-INDV / Consulta Component 3: Improving Infr Individual Consult Pending Impleme ría para realizar el Metraje y IBRD / 93310 astructure and Complement Post Limited 2,200.00 0.00 2023-05-19 2023-05-25 2023-05-29 2023-07-10 2023-08-09 ant Selection ntation presupuesto de la obra en la ary Services Esc. 190 de Montevideo DSPE ESP LIDERAZGO COHO R 3-361853-CS-CDS / DSPE-A NEP . Docente Especialista a Component 2: Strengthening Individual Consult IBRD / 93310 Post Direct - National 1,100.00 0.00 Under Review 2023-05-22 2023-05-23 2023-06-16 2023-07-12 2023-08-31 cargo del Módulo Liderazgo e Management Teams ant Selection ducativo, para el 3er Cohorte a llevarse a cabo en el 2023 DSPE ESP GESTION CURRIC.- 361856-CS-CDS / DSPE-ANEP . Docente Especialista a carg o del Módulo Gestión curricul Component 2: Strengthening Individual Consult IBRD / 93310 Post Direct - National 2,200.00 0.00 Under Review 2023-05-22 2023-05-24 2023-05-29 2023-07-03 2023-10-31 ar del centro educativo: apoy Management Teams ant Selection o en la gestión para la transf ormación curricular, para el 3 er Cohorte a llevarse a cabo en 2023, DSPE ESP CENTRO COMUNID AD-361857-CS-INDV / Docent e Especialista a cargo del Mó Component 2: Strengthening Individual Consult dulo Centro educativo, famili IBRD / 93310 Post Open - National 1,100.00 0.00 Under Review 2023-05-19 2023-06-25 2023-06-25 2023-07-28 2023-10-31 Management Teams ant Selection a y comunidad del Programa de formación en gestión de c entros educativos de la ANEP - 3ER COHORTE AÑO 2023. DIEE ASIST. CCSS 361864-C S-INDV / Un Profesional Asist ente de las Ciencias Sociales Component 4: Strengthening Individual Consult para el análisis y el reporte d IBRD / 93310 Evaluation Systems and Proj Post Open - National 45,500.00 0.00 Under Review 2022-11-21 2023-01-09 2023-01-30 2023-03-06 2024-12-31 ant Selection e resultados para la Direcció ect Management n de Investigación Evaluació n Educativa – ANEP. Técnico A 40 hs ASIS. TEC. ADQUISICIONES-3 61871-CS-INDV / Consultor E xperto B para cumplir funcio Component 4: Strengthening nes en el área de Adquisicion Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Prior Open - National 185,000.00 0.00 2022-10-01 2023-06-15 2022-11-19 2022-12-10 2023-01-14 2027-06-30 es del PAEPU. Con experienc ant Selection ation ect Management ia en normativa local y del B anco Mundial para la contrat ación de Bienes, Obras y Ser vicios de Consultoría y No Co nsultoría. AGRIMENSOR- ESC 190 Y 27 7-361865-CS-INDV / Consulto Component 3: Improving Infr Individual Consult Under Implement ria para el proyecto de agri IBRD / 93310 astructure and Complement Post Limited 7,400.00 0.00 2023-05-19 2023-05-25 2023-05-29 2023-07-10 2023-09-11 ant Selection ation mensura para las Escuelas ary Services 190 de Montevideo y 277 de Canelones UEP DIR. TÉC. F.S. 363512-C Component 4: Strengthening S-INDV / Contratación de 1 Di Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 223,000.00 0.00 Under Review 2023-05-24 2023-06-03 2023-08-10 2023-10-05 2027-06-30 rector Técnico Coordinador d ant Selection ect Management e Formación en Servicio. D.O. ESC. 301 CANELONES - Component 3: Improving Infr 363691-CS-INDV / Arquitecto Individual Consult Pending Impleme IBRD / 93310 astructure and Complement Post Direct - National 40,000.00 0.00 2023-05-26 2023-05-29 2023-05-29 2023-06-13 2024-06-29 Director de Obra para la Escu ant Selection ntation ary Services ela 301 de Montevideo UEP DIREC TEC P. FISICA-36 Component 4: Strengthening 3507-CS-INDV / Contratación Individual Consult Pending Impleme IBRD / 93310 Evaluation Systems and Proj Post Direct - National 201,964.00 0.00 2023-05-31 2023-06-10 2023-06-10 2023-07-01 2027-06-30 1 Director Técnico 40hrs . Co ant Selection ntation ect Management ordinador Area Planta Física del 1/7/23 al 30/6/27 DSPE LIC. COMUNICACIÓN -3 65049-CS-INDV / Consultor Li cenciado en Comunicación, c Component 2: Strengthening Individual Consult Pending Impleme IBRD / 93310 Post Limited 13,200.00 0.00 2023-06-12 2023-06-13 2023-06-23 2023-08-01 2023-12-29 omo apoyo desde una perspe Management Teams ant Selection ntation ctiva de comunicación al Pro ceso de Transformación Educ ativa. ESPEC GESTION CENTRO ED UC-365392-CS-INDV / Contra tación Especialista en Gestió n de Centros Educativos para Component 2: Strengthening Individual Consult Pending Impleme participar como Ponente en e IBRD / 93310 Post Direct - National 800.00 0.00 2023-06-09 2023-06-09 2023-06-12 2023-07-04 2023-08-31 Management Teams ant Selection ntation l 3er cohorte del Curso Corre spondiente al Programa de fo rmación en gestión para Dire ctores de los Centros Educati vos en todos los niveles. UEP TEC ELECTRICISTA--365 Component 4: Strengthening 398-CS-INDV / Contratación T Individual Consult Pending Impleme IBRD / 93310 Evaluation Systems and Proj Post Open - National 150,000.00 0.00 2023-06-12 2023-07-13 2023-08-12 2023-09-20 2027-06-30 écnico Electricista para el Co ant Selection ntation ect Management mponente Planta Física de PA EPU UEP ARQ SUP OBRAS 36613 Component 4: Strengthening 0-CS-INDV / Arq. Supervisor d Individual Consult Pending Impleme IBRD / 93310 Evaluation Systems and Proj Post Direct - National 120,000.00 0.00 2023-06-16 2023-06-16 2023-06-21 2023-07-24 2027-06-30 e Obras - Consultor Experto ant Selection ntation ect Management A 40 horas, para la UEP - PAE PU Page 9 1. Prior Review Threshold. Procurement decisions subject to prior review by the Bank as stated in Appendix 1 in the Procurement Guidelines. Table A.2.4 Prior Review Threshold Prior Review Threshold Procurement Method (US$) Procurement Method Threshold (US$) MODERATE RISK PROJECT Works 1. ICB > 7,000,000 > 15,000,000 2. NCB > 200,000–< 7000,000 As per Procurement Plan 3.. Shopping (small contracts) < 200,000 As per Procurement Plan 4. Direct contracting n.a. All Goods and non-consulting services (excluding consultants services) 1. ICB > 1,000,000 > 3,000,000 2. NCB >100,000 – <1,000,000 As per Procurement Plan 3. Shopping <100,000 As per Procurement Plan 4. Direct contracting n.a All 2. Procurement Packages Subject to World Bank Prior and Post Review with Selection Methods and Time Table A2.5. Procurement Packages Subject to World Bank Prior and Post Review Revie Estimate w Expected Procurem Approac Bid- Ref Contract d by ent h to Opening No. (Description) Cost Bank Method market Date (US$) (Prior/ Post) WORKS 1 Masunga MC - Sowa Water Request for Open Prior March 16,650,00 Supply Master Plan Bids Internatio 2019 0 (connection to Nata Cluster) nal 2 Lobatse MC - Mmathethe Request for Open Prior December Water Supply 8,100,000 Bids Internatio 2017 nal 3 Lobatse MC -Mokatako Water Request for Open Post June 2017 Supply 270,000 Proposals National 4 Selebi Phikwe MC -Selibi Request for Open Prior June 2017 18,000,00 Phikwe - Serule Water Bids Internatio 0 Transfer Scheme nal 5 Masunga MC - North Request for Open Prior June 2017 19,800,00 East/Tutume Water Transfer Bids Internatio 0 Scheme nal 6 Letlhakane MC - Boteti Request for Open Prior June 2017 18,000,00 Southern and Central Cluster Bids Internatio 0 Villages Water Supply Scheme nal 7 Letlhakane MC – Mosu, Request for Open Post June 2017 Mokubilo and Mmea Villages 270,000 Proposals National Water Supply 8 Ghanzi MC - Ghanzi Township Request for Open Prior November Water Supply Expansion 7,560,000 Bids National 2017 Revie Estimate w Expected Procurem Approac Bid- Ref Contract d by ent h to Opening No. (Description) Cost Bank Method market Date (US$) (Prior/ Post) 8 Ghanzi MC - Kuke Water Request for Open Post November Supply Master Plan Project 1,710,000 Bids National 2017 10 Ghanzi MC – Bere Settlement Request for Open Post November Water Supply Augmentation 630,000 Bids National 2017 11 Kanye MC - Kanye/Moshupa Request for Open Post April 2018 2,700,000 Water supply Project Bids National 12 Molepolole MC - - Request for Open Prior April 2018 Malwelwe/Molepolole/Thamag 9,000,000 Bids Internatio a Thebephatswa (Phase 2) nal 13 Francistown MC - Mambo Request for Open Prior July 2017 14,400,00 Waste Water Treatment Plant Proposals Internatio 0 Rehabilitation nal 14 Lobatse MC - Lobatse Waste Request for Open Post April 2018 Water Treatment Plant 585,000 Proposals National Rehabilitation 15 Letlhakane MC – Letlhakane Request for Open Post April 2018 Waste Water Treatment ponds 4,500,000 Proposals National expansion GOODS Request for Open Water quality monitoring April 2017 1 1,200,000 Bids Internatio Post equipment (WUC) nal Request for Open Ground water monitoring April 2017 2 460,000 Bids Internatio Post equipment (WUC) nal Request for Open November IWRM Equipment for surface 3 2,000,000 Bids Internatio Prior 2017 and groundwater monitoring nal Request for Open November Equipment for Operational 4 2,600,000 Bids Internatio Prior 2017 Forecasting and Early Warning nal NONCONSULTING SERVICES Request for Open Loss reduction support April 2017 1,450,000 Bids Internatio Prior program nal 3. Selection of Consultants 4. Prior Review Threshold. Selection decisions subject to prior review by World Bank as stated in appendix 1 to the Guidelines Selection and Employment of Consultants. Table A2.6. Prior Review Threshold for Consultants Prior Review Threshold Selection Method MODERATE RISK Selection Method Threshold (US$) PROJECT (US$) 1. QCBS and QBS ≥ $300,000 >1m 2. FBS, QBS, LCS, and CQS < $300,000 >1m 3. Single Source (Firms) n.a. All 4. Individual Consultants n.a. >300,000 5. Single Source (Individual n.a. All Consultants) Note: QCBS = Quality-and-Cost-Based Selection (Section II of the Consultants’ Guidelines); LCS = Least-Cost Selection (Para 3.6, of the Guidelines); CQS = Selection based on the Consultants’ Qualifications (Para 3.7 of the Guidelines); FBS= Selection under a Fixed Budget (Para 3.5 of the Guidelines); QBS = Quality-Based Selection (Para 3.2 of the Guidelines) 5. Short list comprising entirely of national consultants. Short list of consultants for services, estimated to cost less than US$300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of Paragraph 2.7 of the Consultant Guidelines. All terms of reference irrespective of the value of the consultancy assignment are subject to prior review. Table A2.7 Consultancy Assignments with Selection Methods and Time Schedule Estimat Prior Expected Re Procurem ed Approac or Proposal f ent/Select Description Amoun h to Post Submissi No ion t market Revie on/Openi . Method (US$) w ng Date Review and Roll out of Non-Revenue Open Water Strategy (WUC) QCBS Internatio Prior June 2018 900,000 nal Review of Billing and Collection Open strategies, including benchmarking CQS National Post June 2018 (WUC) 100,000 Review of water supply and Open January (sanitation) wastewater manual CQS National Post 2018 (WUC) 200,000 Energy reduction Strategy – with Open focus on climate change mitigation, National January CQS Post 2018 solar pumping and biogas utilization (WUC) 100,000 Engineering Services for Masunga MC Open - Sowa Water Supply Master Plan 1,850,0 QCBS Internatio Prior June 2018 (connection to Nata Cluster)(WUC) 00 nal Engineering Services for Lobatse MC - Open October Mmathethe Water Supply (WUC) QCBS Internatio Prior 2017 900,000 nal Engineering Services for Lobatse MC - Open Mayy Mokatako Water Supply (WUC) CQS National Post 2017 30,000 Engineering Services for Selebi- Open Phikwe MC - Selibi Phikwe - Serule 2,000,0 QCBS Internatio Prior May 2017 Water Transfer Scheme (WUC) 00 nal Engineering Services for Masunga MC Open Mayy - North East/Tutume Water Transfer 2,200,0 QCBS Internatio Prior 2017 Scheme (WUC) 00 nal Engineering Services for Letlhakane Open MC - Boteti Southern and Central 2,000,0 QCBS Internatio Prior May 2017 Cluster Water Supply (WUC) 00 nal Engineering Services for Letlhakane Open MC - Mosu Water Supply (WUC) CQS National Post May 2017 30,000 Engineering Services for Ghanzi MC - Open Ghanzi Township Water Supply QCBS Internatio Prior July 2017 Expansion(WUC) 840,000 nal Engineering Services for Ghanzi MC – Open Kuke Water Supply Master Plan CQS National Post May 2017 project (WUC) 190,000 Engineering Services for Ghanzi MC – Open Bere Water Supply Augmentation CQS National Post May 2017 (WUC) 70,000 Engineering Services for Kanye MC - Open Kanye/Moshupa Water Supply (WUC) CQS National Post July 2017 300,000 Engineering Services for Molepolole Open MC - Malwelwe/Molepolole/Thamaga July 2017 QCBS Internatio Prior Thebephatswa Water Supply (Phase 1,000,0 nal 2) (WUC) 00 Engineering Services for Francistown Open August - Mambo Waste Water Treatment 1,600,0 QCBS Internatio Prior 2017 Plant Refurbishment (WUC) 00 nal Engineering Services for Lobatse Open November Waste Water Treatment Ponds CQS National Post 2017 Rehabilitation (WUC) 65,000 Engineering Services for Letlhakane Open November Waste Water Treatment Ponds QCBS National Prior 2017 Expansion (WUC) 500,000 Water and Sanitation Policy IC Open dissemination program (MLWS)/DWA) National Post June 2017 50,000 Water Act Training and outreach IC Open December facilitator and dissemination program National Post 2017 (MLWS)/DWA) 50,000 National Conservation strategy IC Open November advisory and technical assistance National Post 2018 (MLWS)/DWA) 50,000 Update of the 1968 Water Act, CQS Open including alignment/amendment of National June 2017 Post related pieces of statutes (MLWS)/DWA) 50,000 Finalization and dissemination of CQS Open National Water Conservation and National December Post 2017 Demand Management Study (MLWS)/DWA) 50,000 Development of water abstraction QCBS Open December and pricing strategy (MLWS)/DWA) Internatio Prior 2017 450,000 nal Regulatory Capacity Building QCBS Open December (MLWS)/DWA) Internatio Prior 2017 500,000 nal Water quality monitoring programs QCBS Open December (MLWS)/DWA) National Post 2017 300,000 Demarcation of catchment areas CQS Open November study (MLWS)/DWA) National Post 2018 200,000 Study and design of aquifer recharge QCBS Open December options (MLWS)/DWA) Internatio Prior 2017 400,000 nal Study and design of saline QCBS Open December groundwater use options Internatio Prior 2017 (MLWS)/DWA) 400,000 nal Support for implementation of QCBS Open December Institutional Strengthening (WUC) Internatio Prior 2017 300,000 nal Development of WSS capital QCBS investment book, business strategy, Open Septembe financial recovery plan, and WSS Internatio Prior r 2017 services strategies (including stand nal posts, sanitation), (WUC) 800,000 Optimization of WSS treatment QCBS Open November processes (WUC) 1,350,0 Internatio Prior 2017 00 nal Support for development of Public CQS Open November Private Partnerships (WUC) Internatio Post 2017 280,000 nal Western Region Master Plans - QCBS Open November Tsabong, Ghanzi and Maun (WUC) 1,800,0 Internatio Prior 2017 00 nal Pre-feasibility studies and technical QCBS Open November assistance for Chobe-Zambesi Internatio Prior 2017 Transfer Scheme (MLWS) 525,000 nal Pre-feasibility studies and technical QCBS Open November assistance for Lesotho-Botswana Internatio Prior 2017 Transfer Scheme (MLWS) 525,000 nal Study on Effluent Reuse options at CQS Open December institutional level (MLWS)/DWA) 200,000 Internatio Post 2018 nal Groundwater desalination options CQS Open December and feasibility study (MLWS)/DWA) Internatio Post 2018 200,000 nal PPP technical implementation QCBS Open support, transaction advice (WUC) Internatio Prior June 2017 800,000 nal Audits (technical, financial, LC Open December procurement) National Post 2017 100,000 Economic and financial review IC Open consultant National Post June 2017 100,000 Project Operational Manual IC Open March consultant National Post 2017 10,000 Project procurement systems IC Open consultant National Prior June 2017 50,000 Financial management systems IC Open consultant National Prior June 2017 50,000 Environmental and Social Safeguards IC Open instruments, Resettlement Policy Internatio June 2017 Prior Framework Dam Safety Action Plan nal monitoring (WUC) 450,000 Project monitoring, reporting and ICR IC Open January consultant National Post 2021 100,000 Communication consultant (WUC) IC Open October National Post 2017 200,000 Community consultation and CQS Open development of Grievance National Post June 2017 Management Systems (WUC) 100,000 Project Management (WUC and DWA) IC Open 3,000,0 National Prior June 2017 00 PROCUREMENT Botswana : Emergency Water Security and Efficiency Project PLAN General Information Country: Botswana 2018-03-28 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160911 GPN Date: 2017-08-23 Project Name: Emergency Water Security and Efficiency Project Loan / Credit No: IBRD / 87190 Department of Water Affairs Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned BW-DWA-183219-CW-RFP / Geophysical Borehole Explor ation, Drilling, Logging, Const Component 3: Sector Refor Single Stage - One E 2021-05-2 ruction, Development, Rehab IBRD / 87190 m and Institutional Strength Post Request for Bids Open - National 750,000.00 778,082.23 Signed 2020-08-06 2021-03-16 2020-08-11 2020-09-03 2020-09-22 2020-09-09 2020-10-22 2021-09-14 2020-11-26 2021-01-09 nvelope 5 ilitation and Test Pumping / I ening njection of Boreholes at Palla Road Wellfield, Central Distri ct, Botswana BW-DWA-243278-CW-RFB / Request for Bids - REHABILITATION, DRILLING, Component 3: Sector Refor Single Stage - One E Small Works SPD 1,791,038.6 2022-05-1 DEVELOPMENT, AND TEST PU IBRD / 87190 m and Institutional Strength Post Request for Bids Limited 1,500,000.00 Signed 2021-07-16 2021-07-21 2021-07-30 2021-08-18 2021-09-10 2021-10-29 2021-10-10 2022-01-13 2021-11-14 2022-05-04 nvelope (1 envelope proce 1 3 MPING OF BOREHOLES IN KG ening ss) ALAGADI SOUTH, KGALAGADI DISTRICT, BOTSWANA GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BW-DWA-99568-GO-RFB / Su Component 3: Sector Refor pply and delivery of assorted Open - Internationa Single Stage - One E IBRD / 87190 m and Institutional Strength Post Request for Bids 1,500,000.00 234,356.56 Signed 2019-03-04 2019-11-12 2019-03-18 2019-03-07 2019-04-29 2019-04-17 2019-05-29 2019-11-19 2019-07-08 2019-11-11 2019-10-07 equipment for Department of l nvelope ening Water and Sanitation Lots 1 t o5 BW-DWA-183225-GO-RFB / A Component 3: Sector Refor Single Stage - One E IBRD / 87190 Post Request for Bids Open - National 800,000.00 0.00 Canceled 2020-07-19 2020-08-26 2020-07-24 2020-08-26 2020-08-25 2020-10-05 2020-11-09 2021-06-04 ssorted Equipment for DWS m and Institutional Strength nvelope ening BW-DWA-205459-GO-RFB / p Component 3: Sector Refor Open - Internationa Single Stage - One E rocurement of assorted equi IBRD / 87190 m and Institutional Strength Post Request for Bids 800,000.00 0.00 Canceled 2020-11-20 2020-12-15 2020-11-25 2020-12-15 2021-01-06 2021-02-05 2021-03-12 2021-09-08 l nvelope pment for DWS ening BW-DWA-205459-GO-RFB-2 / Supply and delivery of geoph Component 3: Sector Refor Single Stage - One E ysics equipment, borehole ca IBRD / 87190 m and Institutional Strength Post Request for Bids Open - National 800,000.00 0.00 Canceled 2022-05-30 2022-05-30 2022-06-04 2022-08-23 2022-07-16 2022-08-11 2022-08-15 2022-09-19 2023-03-18 nvelope mera and multi parameter w ening ater quality meter: Lots 1 to 5. BW-DWA-363700-GO-RFB / S Component 3: Sector Refor Single Stage - Two E Pending Impl upply & Installation of Water IBRD / 87190 m and Institutional Strength Prior Request for Bids Limited 2,000,000.00 0.00 2023-06-30 2023-07-05 2023-08-05 2023-10-30 2023-12-04 2024-07-31 nvelope ementation Resource Monitoring Equipm ening ent BW-DWA-363618-GO-RFB / P Component 3: Sector Refor Single Stage - One E Pending Impl rocurement of Computers for IBRD / 87190 m and Institutional Strength Post Request for Bids Open - National 120,000.00 0.00 2023-07-31 2023-08-05 2023-09-08 2023-11-10 2023-12-15 2024-06-12 nvelope ementation Modelling Purposes ening NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BW-DWA-56312-CS-QCBS / c Component 3: Sector Refor onsultancy services for the d Quality And Cost- Open - Internationa IBRD / 87190 m and Institutional Strength Prior 450,000.00 292,229.88 Signed 2018-03-28 2018-05-15 2018-04-13 2018-11-09 2018-06-08 2019-02-13 2018-07-06 2019-06-24 2018-08-17 2019-07-18 2018-10-05 2019-09-23 2018-11-09 2019-11-21 2019-11-09 evelopment of raw water abs Based Selection l ening traction and pricing strategy BW-DWA-56327-CS-INDV / c onsultancy services for the fi Component 3: Sector Refor Consultant Qualifi nalization and dissemination IBRD / 87190 m and Institutional Strength Post Open - National 50,000.00 0.00 Canceled 2018-03-28 2018-03-29 2018-04-18 2018-06-13 2018-07-13 2018-08-17 2019-08-16 cation Selection of national water conservatio ening n and demand management study BW-DWA-61064-CS-QCBS / c onsultancy services for the fi Component 3: Sector Refor Quality And Cost- Open - Internationa nalization and dissemination IBRD / 87190 m and Institutional Strength Prior 50,000.00 449,830.00 Signed 2018-05-02 2018-05-07 2018-05-23 2018-11-09 2018-07-06 2019-04-05 2018-08-03 2019-06-24 2018-09-02 2019-07-18 2018-10-07 2019-10-03 2018-11-11 2019-10-29 2019-11-11 Based Selection l of national water conservatio ening n and demand management strategy BW-DWA-81629-CS-QCBS / Component 3: Sector Refor Quality And Cost- Open - Internationa Managed Aquifer Recharge F IBRD / 87190 m and Institutional Strength Prior 400,000.00 1,035,410.44 Signed 2018-10-12 2018-11-09 2018-11-02 2019-01-16 2019-01-21 2019-04-18 2019-02-18 2019-06-25 2019-03-20 2019-07-18 2019-04-24 2019-09-23 2019-05-29 2019-10-28 2020-05-28 Based Selection l easibility Study ening BW-DWA-117243-CS-QCBS / Component 3: Sector Refor review of water related legisl Quality And Cost- Open - Internationa IBRD / 87190 m and Institutional Strength Post 950,000.00 1,057,744.71 Signed 2019-06-03 2019-06-24 2019-07-02 2019-07-31 2019-08-15 2021-01-13 2019-09-12 2021-01-13 2019-10-12 2021-01-13 2019-11-16 2021-03-16 2019-12-21 2020-10-05 2021-12-31 ation and full assessment of Based Selection l ening water regulatory authority BW-DWA-56360-CS-CQS / co Component 3: Sector Refor Consultant Qualifi nsultancy services for the stu IBRD / 87190 m and Institutional Strength Post Open - National 200,000.00 0.00 Canceled 2018-03-28 2018-03-29 2018-04-18 2018-11-09 2018-06-13 2018-07-13 2018-08-17 2019-08-16 cation Selection dy of demarcation of catchm ening ent areas. Page 1 BW-DWA-122053-CS-QCBS / Component 3: Sector Refor a consultancy service the stu Quality And Cost- IBRD / 87190 m and Institutional Strength Post Open - National 200,000.00 818,609.68 Signed 2019-07-12 2019-07-13 2019-08-02 2019-09-15 2019-07-15 2019-10-13 2019-07-15 2019-11-12 2019-07-15 2019-12-17 2019-11-01 2020-01-21 2019-10-09 2021-01-20 dy of demarcation of catchm Based Selection ening ent management areas BW-DWA-104017-CS-QCBS / Component 3: Sector Refor Detailed Assessment and Pri Quality And Cost- Open - Internationa IBRD / 87190 m and Institutional Strength Post 305,000.00 0.00 Canceled 2019-03-08 2019-03-31 2019-05-19 2019-06-16 2019-07-16 2019-08-20 2019-09-24 2021-05-24 oritization and Plan for Long t Based Selection l ening erm Water Security. BW-DWA-123391-CS-QCBS / Component 3: Sector Refor Detailed Assessment and Pri Quality And Cost- Open - Internationa IBRD / 87190 m and Institutional Strength Prior 3,000,000.00 0.00 Canceled 2019-07-19 2019-09-23 2019-08-23 2019-10-23 2019-10-06 2020-08-28 2019-11-03 2019-12-03 2020-01-07 2020-02-11 2022-02-10 oritization and Plan for Long t Based Selection l ening erm Water Security. BW-DWA-124085-CS-QCBS / Component 3: Sector Refor consultancy services for the Quality And Cost- Open - Internationa IBRD / 87190 m and Institutional Strength Post 1,200,000.00 690,055.00 Signed 2019-09-06 2019-09-26 2019-09-30 2019-11-01 2019-11-26 2021-03-18 2019-12-25 2021-03-18 2020-01-09 2021-03-18 2020-03-01 2021-03-18 2020-04-05 2020-12-19 2021-04-05 development of National Sani Based Selection l ening tation Management Strategy BW-DWA-64125-CS-FBS / stu Component 3: Sector Refor Quality And Cost- Open - Internationa dy and design of saline groun IBRD / 87190 m and Institutional Strength Prior 400,000.00 0.00 Canceled 2018-05-28 2018-10-11 2018-06-22 2018-11-09 2018-09-14 2019-02-13 2018-10-26 2019-07-17 2018-11-26 2019-07-18 2018-12-31 2019-02-04 2021-02-04 Based Selection l d water use options ening BW-DWA-136661-CS-QCBS / Component 3: Sector Refor Quality And Cost- Open - Internationa study and design of saline gr IBRD / 87190 m and Institutional Strength Prior 2,500,000.00 1,028,787.57 Signed 2019-10-02 2019-10-09 2019-10-23 2019-12-06 2019-10-31 2020-01-03 2019-10-31 2020-02-02 2019-11-01 2020-03-08 2019-11-06 2020-04-12 2019-11-19 2021-04-12 Based Selection l ound water use options ening BW-DWA-183222-CS-CQS / E Component 3: Sector Refor .I.A for the Study and Design Consultant Qualifi IBRD / 87190 m and Institutional Strength Post Open - National 350,000.00 472,909.79 Signed 2020-07-29 2020-08-05 2020-08-19 2020-08-24 2020-10-02 2021-07-12 2020-11-01 2021-07-13 2020-12-06 2020-12-06 2021-06-04 of Saline/Brackish Groundwat cation Selection ening er Reuse Options BW-DWA-295551-CS-QCBS / Consultancy Service for Desi gn and Supervision - Installat Component 3: Sector Refor Quality And Cost- ion and Commissioning of W IBRD / 87190 m and Institutional Strength Post Open - National 700,000.00 0.00 Canceled 2022-05-20 2023-02-24 2022-06-17 2022-07-31 2022-09-09 2022-10-09 2022-11-13 2022-12-18 2024-08-19 Based Selection ater Resources Monitoring Eq ening uipment and Associated Tele metry System for Water Reso urces Management in Botswa na BW-DWA-295552-CS-QCBS / Consultancy Service for the Component 3: Sector Refor Quality And Cost- Under Implement Development of Botswana’s IBRD / 87190 m and Institutional Strength Post Open - National 900,000.00 0.00 2022-05-20 2022-05-30 2022-06-10 2022-07-26 2022-07-24 2023-03-31 2022-09-02 2022-10-02 2022-11-06 2022-12-11 2023-12-11 Based Selection ation Water Resources Drought Pre ening paredness and Management Plan towards Early Warning BW-DWA-348692-CS-CQS / F Component 3: Sector Refor Consultant Qualifi Open - Internationa inalizing The Sanitation Mana IBRD / 87190 m and Institutional Strength Post 150,000.00 0.00 Canceled 2023-03-31 2023-05-12 2023-07-12 2023-08-11 2023-09-15 2024-03-13 cation Selection l gement Framework ening BW-DWA-348669-CS-QCBS / Component 3: Sector Refor Finalizing The Development Consultant Qualifi Open - Internationa IBRD / 87190 m and Institutional Strength Post 250,000.00 0.00 Canceled 2023-03-31 2023-05-12 2023-07-12 2023-08-11 2023-09-15 2024-03-13 of On-Site Sanitation Technol cation Selection l ening ogies and Faecal Sludge Man agement Guidelines BW-DWA-363660-CS-QCBS / Consultancy Services for the Component 3: Sector Refor Consultant Qualifi Pending Impleme Design and Supervision for th IBRD / 87190 m and Institutional Strength Post Limited 50,000.00 0.00 2023-06-30 2023-07-31 2023-08-30 2023-10-04 2024-07-31 cation Selection ntation e Refurbishment of the Librar ening y and Conference Facilities INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BW-DWA-256879-CS-INDV / f Component 3: Sector Refor Individual Consult IBRD / 87190 Post Direct 290,000.00 23,280.99 Signed 2021-10-11 2021-11-17 2021-10-21 2021-12-06 2021-11-11 2022-07-26 2021-12-16 2022-05-11 2022-06-14 inance Specialist m and Institutional Strength ant Selection ening BW-DWA-363706-CS-CDS / D Component 3: Sector Refor Direct - Internation Pending Impleme IBRD / 87190 Post Direct Selection 800,000.00 0.00 2023-06-20 2023-07-15 2023-09-18 2024-10-31 evelopment of Subsidiary Re m and Institutional Strength al ntation gulations ening Page 2 PROCUREMENT PLAN (Textual Part) Project information: Health Sector Reform (P145174) Project Implementation agency: Ministry of Health, Management Unit of the World Bank financed project Date of the Procurement Plan: February 2019 Applicable Guidelines: Guidelines: Selection and Employment of Consultants under IBRD Loans and IDA Credits and Grants by World Bank Borrowers, dated January 2011 and Guidelines: Procurement of Goods, Works and Non-Consulting Services under IBRD Loans and IDA Credits and Grants by World Bank Borrowers, dated January 2011. Prior Review Thresholds for Goods, Works, Non-Consulting and Consulting Services: USD EUR equivalent as per November 15, 2018 Works, Turnkey, S&I of 10.0 8,870,000 Plant & Equipment and PPP Goods, IT and Non- 2.0 1,770,000 Consultant Services Consultant (Firms) 1.0 890,000.00 Consultant (Individuals) 0.3 270,000.00 Procurement Method Thresholds (US$ Million) ICB NCB SH Nationa l Consult ant Ceiling Goods Works Goods Works Good Works s ≥2 ≥20 <2 <20 ≤0.1 ≤0.2 <0.5 ≥1,77 ≥17,75 <1,77 <17,75 ≤0.09 ≤0.18 <0.44 EUR Equivalent ICB – International Competitive Bidding NCB – National Competitive Bidding SH - Shopping PROCUREMENT Romania : Health Sector Reform PLAN General Information Country: Romania 2018-10-25 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P145174 GPN Date: 2022-01-18 Project Name: Health Sector Reform Loan / Credit No: IBRD / 83620, IBRD / 92530 Ministry of Health Project Management Unit Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CW/A/2 / Complex building i n Timisoara that will include I Hospital Network Rationaliza Open - Internationa Single Stage - One E 60,077,199.6 Under Imple 2024-06-0 CU, burn center and emerge IBRD / 83620 Prior Request for Bids 0.00 2020-12-03 2021-12-14 2021-01-21 2022-01-21 2021-03-04 2022-06-07 2021-04-03 2023-01-23 2021-05-28 tion l nvelope 4 mentation 9 ncy room and rehabilitation o f operating room in the existi ng location CW/A/1 / PROCUREMENT OF CIVIL WORKS - “Building a b urn center and reorganizatio Request for Bids - n of the medical flows of the Hospital Network Rationaliza Open - Internationa Single Stage - One E Works (without pr 51,784,212.9 Under Imple 2024-12-3 IBRD / 92530 Prior Request for Bids 0.00 2022-03-10 2022-05-10 2022-04-09 2022-06-01 2022-05-29 2022-11-01 2022-06-28 2023-06-06 2022-09-05 hospital in order to better co tion l nvelope equalification) SP 6 mentation 1 nnect the ER, ICU and surger D y departments” for “Grigore Alexandrescu” Children’s Em ergency Clinical Hospital CW/A/2 AF / Civil works for c Request for Bids - onstruction of the complex b Hospital Network Rationaliza Open - Internationa Single Stage - One E Works (without pr 61,409,593.0 Under Imple 2024-12-3 IBRD / 92530 Prior Request for Bids 0.00 2022-12-31 2023-03-01 2023-01-20 2023-03-09 2023-03-21 2023-05-29 2023-05-05 2023-05-29 uilding at Targu Mures Count tion l nvelope equalification) SP 4 mentation 1 y Emergency Clinical Hospita D l GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RO-MOH PMU-103436-GO-RF B / ICB G/A/3.1Radiotherapy equipment and related civil works for 5 hospitals - Oncolo Health Sector Governance a Open - Internationa Single Stage - One E Under Imple gical Institute Bucharest, Elia IBRD / 83620 nd Stewardship Improvemen Prior Request for Bids 33,528,680.00 0.00 2019-02-28 2019-03-05 2019-04-16 2019-05-16 2019-06-20 2019-12-17 l nvelope mentation s Emergency University Hosp t ital, Baia Mare Emergency Co unty Hospit, Galati Emergenc y Hospit and Constanta Emer gency County Hospit - Phase I RO-MOH PMU-103443-GO-RF Health Sector Governance a Open - Internationa Single Stage - One E Under Revie B / ICB G/A/21 - Equipment fo IBRD / 83620 nd Stewardship Improvemen Prior Request for Bids 10,988,400.00 6,765,681.21 2019-02-28 2019-03-05 2019-04-16 2019-05-16 2019-05-28 2019-06-20 2019-06-12 2019-10-18 l nvelope w r Burn Units - Phase I t RO-MOH PMU-173047-GO-DI R / Procurement of 25000 det Hospital Network Rationaliza ection kits in order to strengt IBRD / 83620 Post Direct Selection Direct 146,394.00 146,183.48 Signed 2020-05-11 2020-03-20 2020-05-12 2020-03-21 2020-05-15 2020-04-04 2020-05-16 tion hen the Government's respo nse to the COVID - 19 outbre ak. RO-MOH PMU-172375-GO-DI R / procurement of 45000 ext racting kits, 20000 detection Hospital Network Rationaliza IBRD / 83620 Post Direct Selection Direct 515,035.00 536,582.33 Signed 2020-05-06 2020-03-20 2020-05-07 2020-03-21 2020-05-20 2020-04-04 2020-05-26 kits, 20 termo shaker in orde tion r to strengthen the Governm ent's response to the COVID - 19. RO-MOH PMU-174228-GO-DI Hospital Network Rationaliza R / procurement of 20000 kit IBRD / 83620 Post Direct Selection Direct 113,205.00 115,659.64 Completed 2020-05-18 2020-03-20 2020-05-19 2020-03-25 2020-05-22 2020-04-15 2020-05-23 2020-05-20 tion s of collection boxes RO-MOH PMU-174229-GO-DI Hospital Network Rationaliza R / procurement of 25000 col IBRD / 83620 Post Direct Selection Direct 126,724.00 130,805.54 Completed 2020-05-18 2020-03-20 2020-05-19 2020-03-25 2020-05-22 2020-04-22 2020-05-23 2020-04-22 tion lection boxes RO-MOH PMU-174230-GO-DI R / procurement of 400 piece Hospital Network Rationaliza IBRD / 83620 Post Direct Selection Direct 1,980,000.00 2,040,778.60 Signed 2020-05-19 2020-03-20 2020-05-20 2020-03-26 2020-05-23 2020-04-11 2020-05-24 s of Console 3 automated inj tion ection + 1 infusomat RO-MOH PMU-174233-GO-DI R / procurement of 600 piece s of Monitors, 120 pieces of Hospital Network Rationaliza IBRD / 83620 Post Direct Selection Direct 8,213,000.00 9,810,894.16 Completed 2020-05-19 2020-03-20 2020-05-20 2020-03-27 2020-05-23 2020-04-15 2020-05-24 2021-04-01 Optional Cardiac debit Modul tion e, 75 pieces of Central monit oring Patient Information Cen ter iX RO-MOH PMU-178990-GO-DI Hospital Network Rationaliza R / Procurement of 400 ICU h IBRD / 83620 Post Direct Selection Direct 7,968,957.85 8,388,435.51 Completed 2020-06-10 2020-03-20 2020-06-10 2020-03-31 2020-06-13 2020-04-24 2020-06-14 2020-12-16 tion ospital beds - COVID - 19 Co mponent RO-MOH PMU-178993-GO-DI R / Procurement of 200 Ventil Hospital Network Rationaliza ators carescape R860, 4000 IBRD / 83620 Post Direct Selection Direct 7,308,560.55 7,594,424.59 Completed 2020-06-10 2020-03-20 2020-06-11 2020-05-07 2020-06-14 2020-05-26 2020-06-15 2020-12-16 tion pcs of Flexible circuite, 3200 pcs ofHME filters - COVID -19 Component RO-MOH PMU-178994-GO-DI R / procurement of 150 Ventil Hospital Network Rationaliza ator Puritan Bannet 980, 300 IBRD / 83620 Post Direct Selection Direct 5,442,710.44 5,655,594.38 Completed 2020-06-10 2020-03-20 2020-06-10 2020-04-08 2020-06-13 2020-05-26 2020-06-14 2020-12-16 tion 00 pcs of Flexible circuite, 60 000 pcs of HME filters- COVID -19 Component RO-MOH PMU-178995-GO-DI Hospital Network Rationaliza R / procurement of equipmen IBRD / 83620 Post Direct Selection Direct 559,276.23 555,808.54 Completed 2020-06-10 2020-03-20 2020-06-10 2020-04-27 2020-06-13 2020-07-04 2020-06-14 2020-09-01 tion t - RT - PCR (COBAS 6800) - C OVID - 19 Page 1 RO-MOH PMU-178987-GO-DI R / Procurement of 40 Ventil Hospital Network Rationaliza ators Carescape R860, 800 p IBRD / 83620 Post Direct Selection Direct 1,468,790.28 1,518,884.73 Completed 2020-06-10 2020-03-20 2020-06-10 2020-04-07 2020-06-13 2020-05-20 2020-06-14 2020-12-16 tion cs of Flexible circuit, 640 pcs of HME filters - COVID -19 Co mponent RO-MOH PMU-182937-GO-DI Hospital Network Rationaliza R / Procurement of 60000 pc IBRD / 83620 Post Direct Selection Direct 179,148.12 181,512.63 Completed 2020-07-07 2020-07-16 2020-07-08 2020-07-16 2020-07-11 2020-08-14 2020-07-12 2021-02-01 tion s of collection boxes sample RO-MOH PMU-182940-GO-DI Hospital Network Rationaliza R / procurement of 210000 p IBRD / 83620 Post Direct Selection Direct 639,814.73 760,855.02 Completed 2020-07-07 2020-07-16 2020-07-08 2020-07-16 2020-07-11 2020-08-14 2020-07-12 2021-02-01 tion cs collection boxes sample. RO-MOH PMU-182944-GO-DI Hospital Network Rationaliza R / Procurement of 210000 p IBRD / 83620 Post Direct Selection Direct 640,628.90 649,883.71 Completed 2020-07-07 2020-07-16 2020-07-08 2020-07-16 2020-07-11 2020-08-14 2020-07-12 2021-02-01 tion cs of collection boxes sample RO-MOH PMU-182971-GO-DI R / procurement of RT - PCR ( Hospital Network Rationaliza QuantStudio™ 7 Flex Real-Ti IBRD / 83620 Post Direct Selection Direct 101,380.92 0.00 Canceled 2020-07-07 2020-04-27 2020-07-07 2020-04-27 2020-07-10 2020-12-15 tion me PCR System -1 pcs) for "C antacuzino" National Institut e Research RO-MOH PMU-184711-GO-DI R / procurement of 10 Evita V Hospital Network Rationaliza IBRD / 83620 Post Direct Selection Direct 519,735.61 547,853.69 Completed 2020-07-17 2020-07-09 2020-07-17 2020-07-09 2020-07-20 2020-07-10 2020-07-21 2020-12-16 50, 4000 pcs Flexible circuit tion MP02607, 8000 pcs HME filte rs MP01790 RO-MOH PMU-196296-GO-DI R / procurement of 60pcs of Hospital Network Rationaliza ventilators Evita V50, 48.000 IBRD / 83620 Post Direct Selection Direct 3,908,348.38 2,917,238.57 Completed 2020-09-25 2020-10-22 2020-09-26 2020-10-22 2020-09-29 2020-10-23 2020-12-15 2021-01-16 tion pcs of flexible circuit MP0260 7; 14.000 pcs of HME filters MP01790. RO-MOH PMU-200107-GO-DI Hospital Network Rationaliza R / 8 pcs of CFX 96 Real Time IBRD / 83620 Post Direct Selection Direct 264,302.00 267,215.04 Completed 2020-10-16 2020-11-02 2020-10-17 2020-11-02 2020-10-20 2020-11-24 2020-12-15 2021-02-01 tion PCR Detection System RO-MOH PMU-200780-GO-DI Hospital Network Rationaliza R ICU 2 / Procurement of ICU IBRD / 83620 Post Direct Selection Direct 21,224,856.00 0.00 Canceled 2020-10-20 2021-04-12 2020-10-21 2020-10-24 2020-12-15 tion equipments for COVID19 ph ase 2 RO-MOH PMU-203449-GO-DI R / procurement of 2 pcs of R T - PCR QuantStudio 7 PRO d Hospital Network Rationaliza estinated to Cantacuzino" Na IBRD / 83620 Post Direct Selection Direct 240,349.43 240,279.42 Completed 2020-11-06 2020-10-12 2020-11-07 2020-10-13 2020-11-10 2020-11-12 2020-12-15 2020-12-16 tion tional Institute Research and Regional Center for Medical Genetics Dolj (part of the Cra iova Emergency County Hosp ital) RO-MOH PMU-204054-GO-DI R / Procurement of 8 pcs of a Hospital Network Rationaliza uthomatic extractor Nextract IBRD / 83620 Post Direct Selection Direct 250,334.96 257,037.99 Completed 2020-11-10 2020-11-12 2020-11-11 2020-11-16 2020-11-14 2020-12-03 2020-12-14 2021-01-16 tion or NX-48S and 15.360 extrac tion tests (96 extraction tests = 1 extraction kit) RO-MOH PMU-204057-GO-DI R / procurement of 8 pcs of a Hospital Network Rationaliza uthomatic extractor Nextract IBRD / 83620 Post Direct Selection Direct 249,827.88 256,516.81 Completed 2020-11-10 2020-11-12 2020-11-11 2020-11-16 2020-11-14 2020-12-03 2020-12-14 2021-01-16 tion or NX-48S and 15360 pcs of extraction tests (96 extractio n tests = 1 extraction kit) ICB G/A/3.4 / Radiotherapy e quipment and related civil w orks for 7 hospitals - Timișoar Hospital Network Rationaliza Open - Internationa Single Stage - One E a, Mureș, Baia Mare, Galati, IBRD / 83620 Prior Request for Bids 18,900,000.00 13,305,904.50 Signed 2020-11-26 2020-12-24 2020-12-02 2021-01-13 2021-01-13 2021-03-24 2021-02-12 2021-05-24 2021-03-19 2021-07-20 2021-11-14 tion l nvelope OIB, OICN and IROI (linear ac celerators, CT simulators, TP S/CS, R&V, dosimetry system s) - Phase III RO-MOH PMU-212218-GO-DI R / Procurement of 9 pcs of h Hospital Network Rationaliza igh capacity automatic extra IBRD / 83620 Post Direct Selection Direct 995,725.97 946,016.56 Completed 2021-01-04 2021-01-18 2021-01-11 2021-01-26 2021-02-02 2021-03-27 2021-02-27 2021-05-12 tion ctor (96 tests/run) and extrac tion kits (1 extraction kit = 2 0000 tests) RO-MOH PMU-228841-GO-DI R / procurement of 300 pcs o Hospital Network Rationaliza IBRD / 83620 Prior Direct Selection Direct 2,124,856.00 0.00 Canceled 2021-04-12 2021-04-16 2021-06-05 2021-08-04 f non Invasive ventilators (hi tion gh flow therapy system with i ntegrated humidifier) RO-MOH PMU-233922-GO-DI R / procurement of Intravasc Hospital Network Rationaliza IBRD / 83620 Post Direct Selection Direct 660,448.87 0.00 Canceled 2021-05-10 2021-05-14 2021-06-10 2021-09-30 ular Temperature Manageme tion nt system based - 10 pcs RO-MOH PMU-234482-GO-DI R / procurement of complex platform of 100 pcs of videofi Hospital Network Rationaliza IBRD / 83620 Post Direct Selection Direct 7,180,431.37 0.00 Canceled 2021-05-17 2021-05-22 2021-06-26 2021-12-23 brobronhoscop made up of 1 tion 00 pcs of video laryngoscope and 100 pcs of flexible fibro bronhoscop RO-MOH PMU-241630-GO-DI Hospital Network Rationaliza R / procurement of 100 pcs o IBRD / 83620 Post Direct Selection Direct 4,808,631.00 0.00 Canceled 2021-06-28 2021-07-01 2021-08-01 2021-12-09 tion f videolaryngoscope RO-MOH PMU-241632-GO-DI R / procurement of 10 pcs of Hospital Network Rationaliza IBRD / 83620 Post Direct Selection Direct 1,918,643.00 0.00 Canceled 2021-06-28 2021-07-03 2021-07-27 2021-12-04 extracorporeal membrane ox tion ygenation (ECMO) RO-MOH PMU-248169-GO-RF Q / procurement of complex Strenthening Public Health E platform of 75 pcs of videofib Request for Quota Single Stage - One E Under Imple IBRD / 83620 mergency Response to COVI Post Open - National 5,242,378.20 0.00 2021-09-07 2021-10-27 2022-02-24 robronhoscop made up of 75 tions nvelope mentation D-19 pcs of video laryngoscope an d 75 pcs of flexible fibrobron hoscop RO-MOH PMU-248174-GO-RF Strenthening Public Health E Q / Procurement of 300 pcs o Request for Quota Single Stage - One E IBRD / 83620 mergency Response to COVI Post Open - National 2,096,951.78 1,633,804.51 Completed 2021-09-16 2021-11-01 2022-02-10 2022-03-01 2022-07-01 f non Invasive ventilators (hi tions nvelope D-19 gh flow therapy system with i ntegrated humidifier) Page 2 RO-MOH PMU-248177-GO-RF Strenthening Public Health E Request for Quota Single Stage - One E Pending Impl Q / procurement of 40 pcs of IBRD / 83620 mergency Response to COVI Post Open - National 1,509,804.92 0.00 2021-09-09 2021-10-25 2022-02-22 tions nvelope ementation invasive ventilators D-19 RO-MOH PMU-248171-GO-RF Strenthening Public Health E Request for Quota Single Stage - One E Q / Procurement of 75 pcs of IBRD / 83620 mergency Response to COVI Post Open - National 3,564,817.18 0.00 Signed 2021-09-08 2021-10-22 2022-02-19 tions nvelope video laryngoscopes D-19 RO-MOH PMU-248178-GO-RF Strenthening Public Health E Request for Quota Single Stage - One E Q / procurement of 30 pcs of IBRD / 83620 mergency Response to COVI Post Open - National 3,585,786.69 0.00 Canceled 2021-09-09 2021-10-27 2022-02-24 tions nvelope mobile digital radiography de D-19 vice RO-MOH PMU-248181-GO-RF Strenthening Public Health E Request for Quota Single Stage - One E Under Imple Q / Procurement of 52 pcs of IBRD / 83620 mergency Response to COVI Post Open - National 2,776,922.68 0.00 2021-09-12 2021-10-30 2022-02-27 tions nvelope mentation ultrasound with four probes D-19 RO-MOH PMU-248172-GO-RF Strenthening Public Health E Q / Procurement of 8 pcs of i Request for Quota Single Stage - One E IBRD / 83620 mergency Response to COVI Post Open - National 514,452.05 0.00 Canceled 2021-09-07 2021-10-25 2022-01-23 ntravascular temperature ma tions nvelope D-19 nagement system RO-MOH PMU-248170-GO-RF Strenthening Public Health E Q / procurement of 6 pcs of e Request for Quota Single Stage - One E IBRD / 83620 mergency Response to COVI Post Open - National 1,132,353.69 859,645.29 Signed 2021-09-07 2021-10-28 2022-02-16 2022-02-25 xtra corporeal membrane ox tions nvelope D-19 ygenation (ECMO) RO-MOH PMU-248176-GO-RF Strenthening Public Health E Request for Quota Single Stage - One E Q / Procurement of 500 pcs o IBRD / 83620 mergency Response to COVI Post Open - National 698,983.76 345,800.52 Signed 2021-09-07 2021-10-22 2022-08-05 2022-02-19 tions nvelope f forced air patient heating bl D-19 anket ICB G/C1/3.3 / Radiotherapy equipment and related civil Hospital Network Rationaliza Open - Internationa Single Stage - One E works for 2 hospitals (linear a IBRD / 83620 Prior Request for Bids 5,000,000.00 0.00 Canceled 2019-06-18 2019-06-26 2019-06-23 2019-06-28 2019-08-04 2019-09-09 2019-09-03 2019-10-08 2020-04-05 tion l nvelope ccelerators, TPS/CS, R&V, do simetry systems) - Phase III RO-MOH PMU-201198-GO-DI Hospital Network Rationaliza R / Training equipment for si IBRD / 83620 Post Direct Selection Direct 1,634,000.00 0.00 Canceled 2020-10-23 2020-07-06 2020-10-24 2021-06-03 2020-10-27 2020-12-15 tion mulation centers G/A/2 / Procurement of equi Hospital Network Rationaliza Open - Internationa Single Stage - One E pment for emergency teleme IBRD / 92530 Prior Request for Bids 4,950,000.00 0.00 Canceled 2022-03-21 2022-04-11 2022-04-05 2022-05-12 2022-05-17 2022-07-14 2022-06-16 2022-08-01 2023-01-28 tion l nvelope dicine system for national co verage G/D/25.2.5 / ICU Simulation Strenthening Public Health E IBRD / 83620 Post Direct Selection Direct 135,199.84 130,859.51 Completed 2022-03-18 2020-07-06 2022-03-18 2021-06-03 2022-03-18 2021-11-05 2022-03-18 2022-02-09 Equipment: Lot 10 - Laptop 2 mergency Response to COVI -in-1 D-19 G/D/25.2.2 / ICU Simulation Equipment: Lot 4 - Simulator Strenthening Public Health E for mechanical ventilation ha IBRD / 83620 mergency Response to COVI Post Direct Selection Direct 566,923.39 548,723.43 Completed 2022-03-18 2020-07-06 2022-03-18 2021-06-03 2022-03-18 2021-11-05 2022-03-18 2021-12-16 rdware software and Lot 8 - A D-19 udio-video recording and deb riefing system G/D/25.2.1 / ICU Simulation Equipment: Lot 1 - Virtual pla tform for mechanical ventilat Strenthening Public Health E ion; Lot 2 - Virtual platform fo IBRD / 83620 mergency Response to COVI Post Direct Selection Direct 514,572.41 498,053.08 Completed 2022-03-18 2020-07-06 2022-03-18 2021-06-03 2022-03-18 2021-11-05 2022-03-18 2022-01-20 r ECMO simulation; Lot 3 - Vir D-19 tual platform for hemodynam ic simulation; Lot 6 - Vital fun ction monitor and Lot 9 - Bro nchial endoscopy sim. G/D/25.2.3 / ICU Simulation Equipment: Lot 5 - Abdomina Strenthening Public Health E l and thoracic, transesophag IBRD / 83620 mergency Response to COVI Post Direct Selection Direct 437,386.55 423,345.12 Completed 2022-03-18 2020-07-06 2022-03-18 2021-06-03 2022-03-18 2021-11-05 2022-03-18 2022-01-28 eal cardiac (TEE) and transth D-19 oracic (TTE) ultrasound simul ator G/D/25.2.4 / ICU Simulation Strenthening Public Health E Equipment: Lot 7 - Eco-guide IBRD / 83620 mergency Response to COVI Post Direct Selection Direct 36,561.72 35,387.98 Completed 2022-03-18 2020-07-06 2022-03-18 2021-06-03 2022-03-18 2021-11-05 2022-03-18 2022-02-09 d central venous catheter ins D-19 ertion simulator G/A/3 / Equipment for region al cervical cancer screening c Hospital Network Rationaliza Open - Internationa Single Stage - One E Under Imple IBRD / 92530 Prior Request for Bids 11,549,066.00 0.00 2022-03-25 2022-06-30 2022-04-19 2022-05-31 2022-06-30 2022-08-04 2023-01-01 enters and for the local cervi tion l nvelope mentation cal cancer screening units RO-MOH PMU-248172-GO-RF Strenthening Public Health E Q-2 / procurement of 8 pcs of Request for Quota Single Stage - One E Pending Impl IBRD / 83620 mergency Response to COVI Post Open - National 630,000.00 0.00 2022-05-31 2022-06-27 2022-08-31 Intravascular Temperature M tions nvelope ementation D-19 anagement System (IVTM) G/A/3.5 / Upgrading and inte gration the treatment planni Hospital Network Rationaliza ng systems for 5 radiotherap IBRD / 83620 Prior Direct Selection Direct - National 2,568,511.47 0.00 Signed 2022-08-22 2022-08-24 2022-08-24 2022-09-02 2022-09-10 2024-04-07 tion y centers (OIB, Galati ECCH, Craiova ECCH, CNOI and IROI ) G/A/3.6 / Upgrade and licens es for the Elekta linear accel erators for modern technics ( Hospital Network Rationaliza IBRD / 83620 Post Direct Selection Direct - National 1,619,099.20 0.00 Signed 2022-08-22 2022-08-22 2022-08-24 2022-05-18 2022-09-15 2024-04-12 XVI/IMRT/VMAT) for 4 radioth tion erapy centers (Baia Mare EC H, Constanta ECCH, Galati EC CH and Oradea ECCH) G/A/3.7 / CT Simulator for OI B and dosimetry equipment f or XVI/IMRT/VMAT treatment Hospital Network Rationaliza Open - Internationa Single Stage - One E technics for 7 radiotherapy c IBRD / 83620 Post Request for Bids 1,552,301.11 0.00 Signed 2022-09-15 2022-11-07 2022-09-20 2022-11-09 2022-11-01 2022-12-09 2022-12-01 2022-12-21 2023-01-05 2025-08-02 tion l nvelope enters (OIB, Baia Mare ECH, Constanta ECCH, Galati ECC H, Craiova ECCH, Oradea EC CH and CNOI) G/A/3.8 / Set of immobilizati Hospital Network Rationaliza on devices for Bucharest Onc IBRD / 83620 Post Direct Selection Direct - National 74,629.71 0.00 Completed 2023-01-09 2023-01-18 2023-01-12 2023-01-09 2023-01-29 2023-05-29 2023-05-17 tion ological Institute - CT Simulat or G/A/3.9 / Radiotherapy equip ment (2 linear accelerators, TPS/CS, R&V, immobilization Hospital Network Rationaliza Open - Internationa Single Stage - One E Under Revie IBRD / 83620 Prior Request for Bids 4,766,623.32 0.00 2023-06-06 2023-06-29 2023-06-20 2023-08-04 2023-09-18 2023-10-24 2024-06-20 devices and dosimetry syste tion l nvelope w ms) and related civil works fo r Ploiesti Municipal Hospital Page 3 G/A/2-2 / Procurement of eq Hospital Network Rationaliza Open - Internationa Single Stage - One E Under Revie uipment for emergency tele IBRD / 92530 Prior Request for Bids 9,210,342.63 0.00 2023-06-26 2023-07-11 2023-08-22 2023-10-06 2023-11-25 2024-08-21 tion l nvelope w medicine system for national coverage G/C1/1.2 / Procurement of e Hospital Network Rationaliza Open - Internationa Single Stage - One E IBRD / 83620 Prior Request for Bids 0.00 5,701,584.41 Signed 2017-06-27 2017-08-08 quipment for Emergency Roo tion l nvelope m (12 lots) G/C1/1.1 / Procurement of e Hospital Network Rationaliza Open - Internationa Single Stage - One E IBRD / 83620 Prior Request for Bids 5,000,000.00 4,018,076.74 Signed 2015-12-24 2016-02-11 2016-03-27 2016-05-05 2016-05-11 2016-06-27 2016-10-08 quipment for emergency roo tion l nvelope m G/C1/5.1 / Procurement of a Hospital Network Rationaliza Open - Internationa Single Stage - One E nesthesia workstations for th IBRD / 83620 Prior Request for Bids 0.00 6,535,033.90 Signed 2017-03-21 2017-05-05 tion l nvelope e Anesthesia and Intensive C are Units (3 lots) G/C1/3.2 / Procurement of ra Hospital Network Rationaliza Open - Internationa Single Stage - One E IBRD / 83620 Prior Request for Bids 0.00 6,509,865.60 Signed 2017-12-26 2018-02-14 diotherapy equipment (3 lots tion l nvelope ) G/C1/5.2 / Procurement of e Hospital Network Rationaliza Open - Internationa Single Stage - One E IBRD / 83620 Prior Request for Bids 0.00 25,329,690.46 Signed 2018-01-15 2018-03-14 quipment for Intensive Care tion l nvelope Units (ICU) G/C1/2.1 / Procurement of di Hospital Network Rationaliza Open - Internationa Single Stage - One E IBRD / 83620 Prior Request for Bids 24,808,500.00 25,960,867.72 Signed 2017-05-04 2017-08-01 2017-09-15 2017-12-01 2017-10-27 2018-01-09 2018-03-26 agnostic imaging medical eq tion l nvelope uipment NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Hospital Network Rationaliza Request for Quota Open - Internationa PM/8 / Advertising services IBRD / 83620 Prior 0.00 39,407.08 Signed 2015-12-22 tion tions l CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS/A/29 / Consultancy servic es for Project Management of construction works for Count Hospital Network Rationaliza Quality And Cost- Open - Internationa IBRD / 83620 Prior 4,285,760.00 0.00 Canceled 2021-06-04 2021-06-25 2021-07-30 2021-08-27 2021-09-16 2021-10-01 2021-10-25 2024-03-23 y Emergency Clinical Hospita tion Based Selection l l "Pius Brînzeu" Timisoara (E mergency, Intensive Care, Su rgery and Burn Center) CS/A/29.1 / Consultancy serv ices for Project Management of construction works for Cou Hospital Network Rationaliza Quality And Cost- Open - Internationa IBRD / 83620 Prior 4,285,760.00 0.00 Under Review 2021-06-10 2021-06-08 2021-06-24 2021-06-23 2021-07-21 2021-11-18 2021-08-18 2021-12-14 2021-09-07 2022-03-11 2021-09-22 2022-09-30 2021-10-27 2024-03-28 nty Emergency Clinical Hospi tion Based Selection l tal "Pius Brînzeu" Timisoara ( Emergency, Intensive Care, S urgery and Burn Center) CS/A/1 / Consultancy service s - Contract Management an d Supervision of construction works - Building a burn cente Hospital Network Rationaliza Quality And Cost- Open - Internationa Under Implement IBRD / 92530 Prior 3,892,401.00 0.00 2021-09-16 2021-09-15 2021-10-01 2021-09-17 2021-10-31 2021-11-04 2021-11-28 2022-01-20 2021-12-18 2022-03-29 2022-01-06 2023-02-16 2022-02-06 2024-08-31 r and reorganization of the m tion Based Selection l ation edical flows of the hospital in order to better position and c onnect ER, ICU and surgery d epartments for Grigore Alexa ndre CS/A/2 / Consultancy service s for Contract Management a nd Supervision of constructio n works for “Building a burn Hospital Network Rationaliza Quality And Cost- Open - Internationa Under Implement IBRD / 92530 Prior 4,712,329.73 0.00 2021-09-30 2021-09-21 2021-10-10 2021-10-12 2021-11-09 2022-02-09 2021-12-07 2022-03-30 2022-01-01 2023-05-08 2022-01-20 2022-02-20 2024-09-30 center and reorganization of tion Based Selection l ation the medical flows of the hosp ital in order to better position and connect the ER, ICU and surgery dep.” for Targu Mure s CS/B/48.2 / Assistance to out line and implement a pricing Health Sector Governance a and reimbursement system f Consultant Qualifi Open - Internationa Under Implement IBRD / 83620 nd Stewardship Improvemen Post 191,148.28 0.00 2022-03-10 2022-03-31 2022-03-31 2022-05-04 2022-04-20 2022-12-22 2022-04-30 2022-05-11 2023-05-11 or all pharmaceutical product cation Selection l ation t s with clear governance, proc ess, and accountability rules CS/B/51-2 / Technical Assista Health Sector Governance a nce to Support the Health Te Consultant Qualifi Open - Internationa Under Implement IBRD / 83620 nd Stewardship Improvemen Post 235,395.00 0.00 2022-04-07 2022-04-07 2022-04-28 2022-05-13 2022-05-28 2022-06-12 2022-07-02 2022-12-29 chnology Assessment Develo cation Selection l ation t pment and Implementation i n Romania CS/B/53 - 4 / Technical Assis Health Sector Governance a tance to conduct an Analysis Consultant Qualifi Under Implement IBRD / 83620 nd Stewardship Improvemen Post Open - National 24,573.00 0.00 2022-05-08 2022-05-09 2022-05-24 2022-06-22 2022-06-27 2022-07-17 2022-08-16 of Medical Waste Manageme cation Selection ation t nt Guidelines and develop an Action Plan CS/B/2 / Consultancy service s for developing communicati Health Sector Governance a on strategy, public relations Quality And Cost- Open - Internationa Under Implement IBRD / 92530 nd Stewardship Improvemen Post 808,241.00 0.00 2022-07-18 2022-07-12 2022-08-08 2022-07-15 2022-09-11 2023-01-11 2022-10-11 2023-02-13 2022-11-10 2022-12-10 2023-01-14 2024-12-31 and awareness campaign for Based Selection l ation t Health Sector Reform Project and Romania Health Program -for-Results CS/1/8.1 / Technical Expertis e and Design services for im plementing the mixed invest ment obj. -Reorg. and extens Hospital Network Rationaliza Quality And Cost- Open - Internationa IBRD / 83620 Prior 440,000.00 1,575,473.49 Signed 2017-05-03 2017-06-08 2017-07-17 2017-07-31 2017-09-08 2018-07-20 2017-09-22 2018-08-06 2018-05-22 . of burn depart. of Grigore Al tion Based Selection l exandrescu Children Emerg. Clinic. Hospital and for Reorg . of Burn Center within Bagda sar-Arseni Emerg. Clinical Ho spital CS/1/2 / Technical Expertise and Design Services for - Ne w building on the site of the Hospital Network Rationaliza Quality And Cost- Open - Internationa Targu Mures Emergency Clini IBRD / 83620 Prior 715,000.00 1,074,612.48 Signed 2017-05-02 2017-05-31 2017-07-12 2017-07-26 2017-08-24 2018-05-29 2017-09-12 2018-06-20 2018-06-12 tion Based Selection l cal County Hospital to includ e an anaesthesia and intensi ve care ward an operating th eatre and a Burn Centre Page 4 CS/3/24 / TECHNICAL ASSIST ANCE FOR INSTITUTIONAL BU ILDING OF HEALTH TECHNOL Hospital Network Rationaliza Quality And Cost- Open - Internationa IBRD / 83620 Prior 815,000.00 871,960.00 Signed 2015-10-07 2015-10-26 2015-11-30 2015-12-14 2016-01-19 2016-10-14 2016-02-08 2016-12-07 2018-01-28 OGY ASSESSMENT STRUCTU tion Based Selection l RE INCLUDING TRAINING FOR NATIONAL AGENCY FOR MEDI CINES AND MEDICAL DEVICE S CS/1/3 / DESIGN SERVICES F OR THE MIXED INVESTMENT PROJECT/OBJECTIVE - REORG ANIZATION AND MODERNIZA Hospital Network Rationaliza Quality And Cost- Open - Internationa TION OF THE EXISTING SURG IBRD / 83620 Prior 0.00 1,472,148.91 Signed 2017-04-27 2017-06-02 2017-07-08 2017-08-02 2017-08-18 2018-08-03 2017-09-01 2018-09-12 2018-05-01 tion Based Selection l ICAL FLOOR ON THE PREMISE S OF THE -PIUS BRINZEU- EM ERGENCY CLINICAL COUNTY HOSPITAL OF TIMISOARA AN D CONSTRUCTION OF A NEW BUILDING CS/3/37 / PERFORMANCE AU Hospital Network Rationaliza Quality And Cost- Open - Internationa DITING SERVICES OF PUBLIC IBRD / 83620 Prior 330,000.00 685,430.40 Signed 2015-10-06 2015-10-30 2015-12-11 2016-01-10 2016-01-29 2016-05-23 2016-02-12 2016-09-14 2016-08-10 tion Based Selection l HOSPITALS WITH ARREARS INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS/A/45 / TA for verification Hospital Network Rationaliza Individual Consult Under Implement of technical project by licens IBRD / 83620 Post Open 77,000.00 0.00 2019-08-14 2019-10-25 2019-10-02 2019-10-23 2019-11-27 2020-12-15 tion ant Selection ation ed expert/supervisor RO-MOH PMU-173045-CS-IN Hospital Network Rationaliza Individual Consult Pending Impleme IBRD / 83620 Post Open 15,500.00 0.00 2020-05-14 2020-05-21 2020-05-22 2020-06-13 2020-12-15 DV / PMU staff - procurement tion ant Selection ntation expert RO-MOH PMU-173040-CS-IN Hospital Network Rationaliza Individual Consult Pending Impleme DV / PMU stat - accountant (F IBRD / 83620 Post Open 15,500.00 0.00 2020-05-11 2020-05-14 2020-05-15 2020-05-17 2020-12-15 tion ant Selection ntation inancial department) RO-MOH PMU-174456-CS-IN DV / Consultancy services for Hospital Network Rationaliza Individual Consult Pending Impleme IBRD / 83620 Post Open 357,840.00 0.00 2020-05-19 2020-05-22 2020-05-24 2020-05-27 2020-06-26 verification of the technical d tion ant Selection ntation esign by authorized experts RO-MOH PMU-191089-CS-CD Hospital Network Rationaliza S / Procurement consultancy IBRD / 83620 Post Direct Selection Direct 14,000.00 120,380.73 Signed 2020-08-29 2020-08-26 2020-08-31 2020-08-26 2020-09-03 2020-09-14 2020-12-15 tion services - Individual Consulta nt RO-MOH PMU-202633-CS-CD Health Sector Governance a S / Direct Selection of an Assi IBRD / 83620 nd Stewardship Improvemen Post Direct Selection Direct 9,000.00 0.00 Canceled 2020-11-03 2020-11-05 2020-11-05 2020-11-08 2020-12-15 stant of the Coordinator t RO-MOH PMU-206139-CS-CD Project Management, and M S / Procurement of consultan IBRD / 83620 Post Direct Selection Direct 14,000.00 0.00 Canceled 2020-11-26 2020-11-26 2020-11-28 2020-12-05 2020-12-01 2021-03-31 onitoring and Evaluation cy services - Project Advisor f or the WBPMU RO-MOH PMU-226490-CS-IN DV / Consultancy services - “ Environmental safeguards sp Project Management, and M Individual Consult IBRD / 83620 Post Open 163,189.34 131,030.98 Signed 2021-04-02 2021-04-11 2021-05-08 2021-05-19 2021-05-10 2021-05-20 2021-05-19 2021-06-03 2024-12-31 ecialist” under Health Sector onitoring and Evaluation ant Selection Reform - Improving Health Sy stem Quality and Efficiency P roject RO-MOH PMU-226494-CS-IN DV / Consultancy services - “ Project Management, and M Individual Consult Social specialist” under the H IBRD / 83620 Post Open 163,189.34 144,929.33 Signed 2021-04-02 2021-04-06 2021-05-09 2021-05-19 2021-05-15 2021-05-19 2021-05-26 2021-06-05 2024-12-31 onitoring and Evaluation ant Selection ealth Sector Reform - Improvi ng Health System Quality an d Efficiency Project RO-MOH PMU-211841-CS-IN DV / Project Coordinator for R Health Sector Governance a Individual Consult omania Health Program-for-R IBRD / 83620 nd Stewardship Improvemen Post Open 54,611.00 0.00 Canceled 2020-12-30 2020-12-29 2021-02-01 2021-02-03 2021-02-10 2021-03-31 ant Selection esults Project (Loan agreeme t nt no. 9005-RO – P169927) RO-MOH PMU-229584-CS-IN Health Sector Governance a DV / Coordinator for Health S Individual Consult IBRD / 83620 nd Stewardship Improvemen Prior Open 327,277.83 288,344.27 Signed 2021-04-21 2021-04-19 2021-05-28 2021-06-09 2021-05-31 2021-06-24 2021-06-10 2021-06-23 2024-12-31 ector Reforms and Program-f ant Selection t or-Results Project C/CS/49.1 / Consultancy serv Hospital Network Rationaliza Individual Consult IBRD / 83620 Post Open 52,464.78 79,848.16 Signed 2021-05-06 2021-05-09 2020-01-23 2021-05-10 2020-02-24 2021-05-12 2020-03-10 2021-05-13 ices for procurement activitie tion ant Selection s - IC CS/C/50 / Civil Works Techni cal Consultant for Ministry of Health - Project Management Project Management, and M Individual Consult IBRD / 83620 Post Direct 126,653.00 183,699.41 Signed 2021-05-06 2019-02-09 2021-05-06 2019-02-25 2021-05-06 2019-03-27 2021-05-06 2019-04-06 2024-12-31 Unit (WBPMU) for the Health onitoring and Evaluation ant Selection Sector Reform - Improving H ealth System Quality and Effi ciency Project CS/B/49 / Public Health Speci alist (Individual Consultant, N ational) Health Sector Governance a Individual Consult Scope of work - increase the IBRD / 83620 nd Stewardship Improvemen Post Open 36,271.21 0.00 Canceled 2021-09-05 2021-10-13 2021-09-29 2022-03-30 2021-10-09 2021-10-29 2022-03-18 ant Selection capacity of the Ministry of He t alth to assess patient satisfa ction and improve institution al responsiveness to patient needs. CS/B/50 / Sociologist (individ ual consultant, national) - inc Health Sector Governance a rease the capacity of the Min Individual Consult Under Implement IBRD / 83620 nd Stewardship Improvemen Post Open 29,637.53 0.00 2021-09-05 2021-09-29 2021-10-04 2021-10-24 2022-03-18 istry of Health to assess pati ant Selection ation t ent satisfaction and improve institutional responsiveness t o patient needs CS/B/51 / Technical assistan ce to support Romanian relev Health Sector Governance a ant authorities – MoH, NAMM Individual Consult IBRD / 83620 nd Stewardship Improvemen Post Open 126,203.64 0.00 Canceled 2021-09-06 2021-10-05 2021-10-10 2021-10-13 2022-05-11 D, NHIH and the MoH-establis ant Selection t hed HTA Taskforce – to updat e/improve HTA methodology for medicines Page 5 CS/B/48.3 / Technical Assista Health Sector Governance a nce for National Data Analyti Individual Consult IBRD / 83620 nd Stewardship Improvemen Post Open 61,500.00 0.00 Canceled 2021-11-18 2021-12-12 2021-12-14 2021-12-24 2022-06-22 cs Masterplan & Policy Frame ant Selection t work Development CS/B/54.1 / eHealth Specialis Health Sector Governance a Individual Consult t for National Health Data An IBRD / 83620 nd Stewardship Improvemen Post Open 82,693.00 0.00 Signed 2022-02-10 2022-02-11 2022-03-02 2022-12-13 2022-03-07 2023-01-06 2022-03-19 2023-03-19 ant Selection alytics Master Plan Developm t ent CS/B/54,2 / Health Data Polic Health Sector Governance a Individual Consult y Specialist for National Healt IBRD / 83620 nd Stewardship Improvemen Post Open 122,431.00 0.00 Signed 2022-02-11 2022-02-11 2022-03-03 2022-12-13 2022-03-08 2023-01-06 2022-03-20 2023-03-20 ant Selection h Data Analytics Master Plan t Development CS/C/50.1 / Civil works techn Project Management, and M Individual Consult IBRD / 83620 Post Open 201,365.00 0.00 Canceled 2022-03-15 2022-03-17 2022-04-13 2022-04-18 2022-05-03 2024-12-26 ical consultant onitoring and Evaluation ant Selection RO-MOH PMU-126309-CS-IN Project Management, and M Individual Consult DV / CS/C/53 - Procurement A IBRD / 83620 Post Open 22,200.00 0.00 Canceled 2019-08-07 2019-08-08 2019-09-25 2019-10-16 2019-11-20 2021-03-19 onitoring and Evaluation ant Selection ssistant (Individual Consultan t, national) RO-MOH PMU-246716-CS-IN DV / “Communication Coordi Project Management, and M Individual Consult nator for Health Sector Refor IBRD / 83620 Post Open 197,495.03 0.00 Canceled 2021-08-12 2021-08-08 2021-09-07 2021-09-09 2021-09-30 2024-12-31 onitoring and Evaluation ant Selection ms and Program-for-Results” (Individual Consultant, Natio nal) CS/B/53.3 / Analysis of Medic Health Sector Governance a Individual Consult al Waste Management Guidel IBRD / 83620 nd Stewardship Improvemen Post Open 7,500.00 0.00 Canceled 2021-11-01 2021-10-30 2021-11-25 2021-11-25 2021-12-10 2022-03-29 ant Selection ines - Environmental Speciali t st CS/B/53.2 / Analysis of Medic Health Sector Governance a Individual Consult al Waste Management Guidel IBRD / 83620 nd Stewardship Improvemen Post Open 7,500.00 0.00 Canceled 2021-11-01 2021-10-30 2021-11-25 2021-11-25 2021-12-12 2022-03-31 ant Selection ines - Legal expert t CS/B/53.1 / Analysis of Medic Health Sector Governance a Individual Consult al Waste Management Guidel IBRD / 83620 nd Stewardship Improvemen Post Open 7,500.00 0.00 Canceled 2021-11-01 2021-10-30 2021-11-25 2021-11-27 2021-12-12 2022-03-31 ant Selection ines - Health expert t CS/B/49.1 / Public Health Sp ecialist (Individual Consultant , National) Scope of work - in Health Sector Governance a Individual Consult Under Implement crease the capacity of the Mi IBRD / 83620 nd Stewardship Improvemen Post Open 36,271.21 0.00 2022-04-21 2022-04-18 2022-05-21 2022-05-31 2022-06-12 2022-10-30 ant Selection ation nistry of Health to assess pat t ient satisfaction and improve institutional responsiveness t o patient needs. CS/C/51 / Technical expert f Project Management, and M Individual Consult or procurement of constructi IBRD / 83620 Post Direct - National 31,000.00 0.00 Signed 2022-11-08 2022-10-08 2022-11-08 2022-10-11 2022-11-08 2022-10-17 2022-11-08 2023-04-30 onitoring and Evaluation ant Selection on works - installations CS/C/52 / Technical expert f Project Management, and M Individual Consult or procurement of constructi IBRD / 83620 Post Direct - National 31,000.00 0.00 Signed 2022-11-08 2022-10-08 2022-11-08 2022-10-11 2022-11-08 2022-10-17 2022-11-08 2023-04-30 onitoring and Evaluation ant Selection on works - installations CS/C/53 / Technical expert f Project Management, and M Individual Consult or procurement of constructi IBRD / 83620 Post Direct - National 31,000.00 0.00 Signed 2022-11-08 2022-10-08 2022-11-08 2022-10-11 2022-11-08 2022-10-17 2022-11-08 2023-04-30 onitoring and Evaluation ant Selection on works - installations CS/B/55 / Technical assistan Health Sector Governance a ce for “Development of a pra Under Implement IBRD / 83620 nd Stewardship Improvemen Post Direct Selection Direct - National 16,500.00 0.00 2023-01-26 2023-02-02 2023-02-01 2023-02-09 2023-03-11 2023-03-20 ctical guide in the field of he ation t althcare mediation” Page 6 PROCUREMENT PLAN (Textual Part) Project information: Philippines, Metro Manila Flood Management Project P153814 Project Implementation agency: Department of Public Works and Metro Manila Development Authority Date of the Procurement Plan: 13 April 2018 Period covered by this Procurement Plan: April 16, 2018 to October 15, 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Government Procurement Reform Act (RA9184), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1. The procurement is open to all eligible firms from any country; 2. The request for bids/request for proposals document shall require the Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting signed contracts, confirming application of, and compliance with, the Bank's Anti- Corruption Guidelines, including without limitation the Bank's right to sanction and the Bank's inspection and audit rights; 3. Rights for the Bank to review procurement documentation and activities; and 4. An effective complaints mechanism. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Work) Goods: 15%; Works: is not applicable. PROCUREMENT Philippines : Metro Manila Flood Management Project PLAN General Information Country: Philippines 2018-04-19 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153814 GPN Date: 2018-03-15 Project Name: Metro Manila Flood Management Project Loan / Credit No: IBRD / 87840, COFN / C1450 Metro Manila Development Authority Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PH-MMDA-CO203-4 / Design and Construction of Warehou se for Solid Waste Managem ent Tools and Equipment wit 2. Minimizing Solid Waste in Single Stage - One E 2022-02-0 IBRD / 87840 Post Request for Bids Open - National 480,292.40 421,060.43 Signed 2021-04-16 2021-04-19 2021-04-21 2021-06-02 2021-05-27 2021-07-02 2021-10-20 2021-08-06 2021-10-28 h Office and Quarters at Laba Waterways nvelope 2 san PS. This will be a solid str ucture where we will store to ols and equipment for the im plementation of the project. PH-MMDA-230683-CW-RFB / National Procure Fabrication of Conveyor, Mod ment Document - 2. Minimizing Solid Waste in 2021-08-0 ification of Existing Conveyor IBRD / 87840 Post Direct Selection Direct 1 Envelope proce 50,000.00 45,378.31 Completed 2021-04-30 2021-05-11 2021-05-05 2021-05-13 2021-06-09 2021-09-14 Waterways 8 and Civil Works on Staging Ar ss (Non Bank-SPD ea and Perimeter Fence. ) PH-MMDA-238497-CW-RFB / National Procure Design and Construction of T ment Document - 2. Minimizing Solid Waste in Single Stage - One E 2023-04-0 rash Traps on Selected Sites IBRD / 87840 Post Request for Bids Open - National 1 Envelope proce 585,717.00 555,002.03 Signed 2021-10-15 2021-10-28 2021-10-22 2021-12-03 2021-12-07 2022-01-02 2021-12-27 2022-02-06 2022-01-01 Waterways nvelope 2 of Estero de Paco and San Ju ss (Non Bank-SPD an River and its Tributary ) National Procure PH-MMDA-268996-CW-RFB / ment Document - 2. Minimizing Solid Waste in Single Stage - One E 2022-11-2 Design and Construction of IBRD / 87840 Post Request for Bids Open - National 1 Envelope proce 420,315.00 0.00 Canceled 2021-12-28 2021-12-20 2022-01-09 2022-02-20 2022-03-22 2022-04-26 Waterways nvelope 2 Water Hyacinth Processing F ss (Non Bank-SPD acility ) PH-MMDA-303624-CW-RFB / National Procure Design and Build Services for ment Document - 2. Minimizing Solid Waste in Single Stage - One E Under Imple 2023-05-2 the Neighbourhood Upgradin COFN / C1450 Post Request for Bids Open - National 1 Envelope proce 553,900.00 0.00 2022-08-15 2022-08-20 2022-09-19 2022-10-19 2022-11-23 Waterways nvelope mentation 2 g: Beautification of Waterway ss (Non Bank-SPD s and Easements in Brgy. Sa ) n Miguel Pasig City PH-MMDA-323006-CW-RFB / National Procure Design and Build Services for ment Document - the Neighborhood Upgrading 2. Minimizing Solid Waste in Single Stage - One E 2023-07-2 IBRD / 87840 Post Request for Bids Open - National 1 Envelope proce 636,716.00 0.00 Signed 2022-10-01 2022-10-01 2022-10-06 2022-11-17 2022-12-26 2022-12-17 2022-12-27 2023-01-21 Project: Beautification of Wat Waterways nvelope 0 ss (Non Bank-SPD erways and Easements in Tri ) pa de Gallina Creek, Brgy. Sa n Isidro, Makati City GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PH-MMDA-58579-GO-RFB / T rucks/Loader/Vehicle Packag e to include garbage compac tor truck, rear end loading g 2. Minimizing Solid Waste in Open - Internationa Single Stage - One E IBRD / 87840 Prior Request for Bids 2,177,788.00 0.00 Canceled 2018-04-23 2018-04-28 2018-06-09 2018-07-09 2018-08-13 2019-02-09 arbage compactor, garbage Waterways l nvelope bins, hook lift loader truck, fo rk lift, hook lift container, du mp truck, wheel pay loader, service vehicle PH-MMDA-59025-GO-RFQ / S olid Waste Management Tool s that will be used for the im plementation of community- 2. Minimizing Solid Waste in Request for Quota Single Stage - One E IBRD / 87840 Post Open - National 96,154.00 0.00 Canceled 2018-10-06 2018-12-01 2019-05-30 based management program Waterways tions nvelope (buggy, push carts, trolley bi ns, shovel, rakes, broomstick s, dust pans, plastic bags, glo ves, face masks, rubber coat s, raincoats) PH-MMDA-63617-GO-RFQ / Multi-purpose Vehicle (MPV) t 4. Project Management and Request for Quota Single Stage - One E hat will be used for project m IBRD / 87840 Post Open - National 57,692.31 0.00 Canceled 2018-05-30 2018-07-25 2019-01-21 Coordination tions nvelope onitoring, site inspections, fil ed visits and coordination me etings PH-MMDA-63620-GO-RFB / T ruck/Loader package to inclu de garbage compactor truck 2. Minimizing Solid Waste in Open - Internationa Single Stage - One E , rear end loading garbage co IBRD / 87840 Prior Request for Bids 2,120,096.15 2,095,970.98 Signed 2018-05-25 2018-07-13 2018-05-30 2018-07-16 2018-07-11 2018-08-10 2019-03-28 2018-09-14 2019-04-29 2019-03-13 Waterways l nvelope mpactor, garbage bins, hook lift loader truck, fork lift, hoo k lift container, dump truck a nd wheel pay loader PH-MMDA-144289-GO-RFB / Sound Trucks will be utilized as a modern and interactive approach in the community-b 2. Minimizing Solid Waste in Single Stage - One E ased education & communic COFN / C1450 Post Request for Bids Open - National 214,384.00 223,435.91 Completed 2019-11-15 2019-11-20 2019-11-20 2020-01-01 2019-12-11 2020-01-31 2020-03-30 2020-03-06 2020-11-07 2020-09-02 2021-03-16 Waterways nvelope ations campaign of proper So lid Waste Management at the barangay level as laid out in the MMFMP-Component 2. T wo sound trucks will be purc hased. PH-MMDA-144305-GO-RFB / Mobile Material Recovery Fac ilities (MRFs) are trucks oper ated by the MMDA-SWMO tha 2. Minimizing Solid Waste in Single Stage - One E t will roam around different b COFN / C1450 Post Request for Bids Open - National 178,602.21 177,071.22 Completed 2019-11-15 2019-11-20 2019-11-20 2020-01-01 2019-12-11 2020-01-31 2019-12-26 2020-03-06 2019-12-27 2020-09-02 2020-02-28 Waterways nvelope arangays involved in MMFMP- Component 2 and collect rec yclable materials in exchang e of basic necessities. Three trucks will be purchased. Page 1 PH-MMDA-145500 / The Geo graphic Information Systems (GIS) is a computer platform 4. Project Management and for mapping/visual represent COFN / C1450 Post Direct Selection Direct 32,030.65 0.00 Canceled 2019-09-26 2019-09-23 2019-10-01 2019-11-05 2020-05-03 Coordination ation and will be used for gat hering and analyzing existing /supplementary data in the p umping stations and nearby areas. PH-MMDA-145501 / The Soli d Waste Granulator is a uniq ue technology that prolongs t he service life of landfills thro 2. Minimizing Solid Waste in COFN / C1450 Prior Direct Selection Direct 492,332.25 517,212.75 Completed 2019-10-22 2020-02-15 2019-10-27 2020-08-21 2019-12-01 2019-12-28 2020-05-29 2020-07-02 ugh reduction of solid waste Waterways volume dumped along water ways/drainage areas. Bio-wa stes and plastics will be refin ed and converted into by-pro ducts. PH-MMDA-63617 / The Multi- Purpose Vehicle (MPV) will be used for project monitoring, s 4. Project Management and Request for Quota Single Stage - One E COFN / C1450 Post Open - National 49,414.50 49,096.63 Signed 2019-05-30 2019-07-25 2019-06-17 2020-01-21 ite inspections, filed visits, an Coordination tions nvelope d coordination meetings. Two (2) units will be purchased. PH-MMDA-63622 / Miscellan eous SWM Tools & Equipmen t (in units) as part of MMFMP 2. Minimizing Solid Waste in Request for Quota Single Stage - One E Phase 1 - Component 2: Push COFN / C1450 Post Open - National 98,882.90 102,709.50 Terminated 2019-03-19 2019-05-14 2019-12-31 2019-11-10 Waterways tions nvelope carts (75), Bicycle Bell Rings (75), Boats (30), Buggies/Wh eelbarrows (30), Tribikes (80) , and Rolling Bins (160). PH-MMDA-2019202 / Water bottles and canvas bags to s upport the Information, Educ ation & Communications (IEC 2. Minimizing Solid Waste in Request for Quota Single Stage - One E COFN / C1450 Post Limited 10,590.00 0.00 Canceled 2019-10-15 2019-12-10 2020-06-07 ) campaigns to raise awarene Waterways tions nvelope ss and encourage behavior c hange for improved solid was te management at the indivi dual and household levels. PH-MMDA-2019204 / Shirts f or the 2019 Solid Waste Man agement (SWM) Summit to ki 2. Minimizing Solid Waste in Request for Quota Single Stage - One E ckoff and support the IEC ca COFN / C1450 Post Limited 2,940.00 1,496.50 Completed 2019-11-03 2019-10-14 2019-12-29 2019-12-04 2020-06-26 2020-01-28 Waterways tions nvelope mpaigns, engage barangay o fficials, and introduce the co ncept of circular resource ma nagement through interactiv e activities. PH-MMDA-144308-GO-RFB / CCTV cameras/infra will be in stalled at strategic locations i n MM barangays to monitor 2. Minimizing Solid Waste in Single Stage - One E waste disposal activities alon COFN / C1450 Prior Request for Bids Open - National 536,640.00 510,021.13 Completed 2019-11-15 2020-11-15 2019-11-20 2020-01-01 2021-01-04 2020-01-31 2021-06-06 2020-03-06 2021-06-14 2020-09-02 2022-11-07 Waterways nvelope g/beside creeks and esteros ( estuaries). CCTV control & m onitoring systems/rooms will also be provided in the respe ctive Barangay Halls. PH-MMDA-CO201-7 / Purcha se of ICT equipment for priori ty barangays as part of com 2. Minimizing Solid Waste in Request for Quota Single Stage - One E IBRD / 87840 Post Open - National 11,472.53 15,187.90 Completed 2020-11-08 2021-01-03 2020-12-30 2021-07-02 2021-01-13 munity quarantine implemen Waterways tions nvelope tation during the COVID-19 p andemic. This is under the im plementation of Component 2. PH-MMDA-CO202-4 / Signag 2. Minimizing Solid Waste in Request for Quota Single Stage - One E Pending Impl IBRD / 87840 Post Open - National 1,346.15 0.00 2020-11-08 2021-01-03 2021-07-02 es for Heavy Equipment and Waterways tions nvelope ementation Vehicles PH-MMDA-CO202-5 / Washa ble Overall PPEs for Garbage Collectors, Landfill Staff, and FCSMO Staff - Procurement o 2. Minimizing Solid Waste in Request for Quota Single Stage - One E IBRD / 87840 Post Open - National 19,903.85 16,803.98 Completed 2020-11-08 2021-01-03 2021-08-06 2021-07-02 2021-10-30 f personal protective equipm Waterways tions nvelope ent for the waste manageme nt and pumping stations pers onnel as part of COVID-10 pa ndemic response under the C omponent 2 PH-MMDA-CO204-3 / MPV - 2 2. Minimizing Solid Waste in Request for Quota Single Stage - One E COFN / C1450 Post Open - National 65,384.62 81,197.19 Completed 2020-11-08 2021-01-03 2020-12-30 2021-07-02 2021-04-29 1 seater (MPV 5, 6) Waterways tions nvelope PH-MMDA-CO204-2 / MPV - 7 seater (MPV 3, 4) - Procurem 2. Minimizing Solid Waste in Request for Quota Single Stage - One E ent of vehicles to be utilized IBRD / 87840 Post Open - National 73,076.92 76,070.07 Completed 2020-11-08 2021-01-03 2020-10-02 2021-07-02 2020-12-08 Waterways tions nvelope by project team for the imple mentation of Component 2 PH-MMDA-CO205-2 / GNSS R TK System with CORS - Procu 2. Minimizing Solid Waste in Request for Quota Single Stage - One E rement of scanning system f IBRD / 87840 Post Open - National 66,250.00 70,805.21 Completed 2020-11-08 2021-01-03 2020-12-30 2021-07-02 2021-02-05 Waterways tions nvelope or immediate data collection within the catchment areas o f pumping stations PH-MMDA-CO42-3 / Project Management Office Operatio 4. Project Management and Request for Quota Single Stage - One E ns, Manpower, Supplies, Equi COFN / C1450 Post Open - National 8,076.92 15,852.17 Completed 2020-11-08 2021-01-03 2021-08-04 2021-07-02 2021-09-02 Coordination tions nvelope pment, Furniture and Meetin g (Operations - Additional Off ice Furniture) PH-MMDA-CO204-4 / Payloa der - Procurement of vehicles to be utilized by project team 2. Minimizing Solid Waste in Request for Quota Single Stage - One E COFN / C1450 Post Open - National 94,230.77 0.00 Canceled 2020-11-08 2021-01-03 2021-07-02 for the collection of waste in Waterways tions nvelope the pumping stations as part of the implementation of Co mponent 2 PH-MMDA-200986-GO-RFB-2 / Miscellaneous SWM Tools a nd Equipment - - as part of MMFMP Phase 1 - Component 2. Minimizing Solid Waste in Single Stage - One E IBRD / 87840 Post Request for Bids Open - National 98,882.90 0.00 Canceled 2019-03-14 2019-03-19 2019-04-30 2019-05-30 2019-07-04 2019-12-31 2: Pushcarts (75), Bicycle Waterways nvelope Bell Rings (75), Boats (30), B uggies/Wheelbarrows (30), Tribikes (80), and Rolling Bin s (160) PH-MMDA-CO205-3 / Scanni 2. Minimizing Solid Waste in Single Stage - One E COFN / C1450 Post Request for Bids Open - National 137,500.00 122,714.05 Completed 2020-11-03 2020-07-22 2020-11-08 2020-12-20 2020-08-17 2021-01-19 2020-12-10 2021-02-23 2020-12-30 2021-08-22 2021-02-20 ng Station Waterways nvelope Page 2 PH-MMDA-CO204-6 / Payloa 2. Minimizing Solid Waste in Single Stage - One E COFN / C1450 Post Request for Bids Open - National 182,692.31 187,156.32 Completed 2020-11-03 2020-11-03 2020-11-08 2020-12-20 2020-12-22 2021-01-19 2020-12-29 2021-02-23 2020-12-30 2021-08-22 2021-02-20 der Waterways nvelope PH-MMDA-CO42-7 / Project Management Office Operatio 4. Project Management and Single Stage - One E IBRD / 87840 Post Request for Bids Open - National 154,086.19 153,994.05 Completed 2020-11-03 2021-04-21 2020-11-08 2020-12-20 2021-09-27 2021-01-19 2021-12-14 2021-02-23 2022-01-01 2021-08-22 2022-06-03 ns, Manpower, Supplies, Equi Coordination nvelope pment, Furniture and Meetin g (ICT Year 3 EQUIPMENT) PH-MMDA-CO42-8 / Project Management Office Operatio ns, Manpower, Supplies, Equi pment, Furniture and Meetin 4. Project Management and Request for Quota Single Stage - One E IBRD / 87840 Post Limited 31,200.40 31,316.40 Completed 2020-11-08 2021-02-27 2021-01-03 2021-05-18 2021-07-02 2021-06-11 g (ICT Year 3- SOFTWARE) - Coordination tions nvelope Microsoft Office and AutoCAD for ICT YR 3 Equipment that will be distributed to MMDA o ffices that takes part in the p roject PH-MMDA-2019201 / Posters and flyers to suppor the Infor mation, Education & Commu nications (IEC) campaigns to 2. Minimizing Solid Waste in Request for Quota Single Stage - One E COFN / C1450 Post Limited 9,095.00 0.00 Canceled 2019-10-15 2019-11-15 2019-12-10 2020-06-07 raise awareness and encoura Waterways tions nvelope ge behavior change for impr oved solid waste manageme nt at the individual and hous ehold levels. PH-MMDA-200986-GO-RFQ-3 / Miscellaneous SWM Tools a nd Equipment - - as part of M 2. Minimizing Solid Waste in Request for Quota Single Stage - One E MFMP Phase 1 - Component IBRD / 87840 Post Open - National 96,153.84 100,848.94 Signed 2020-03-19 2020-05-14 2019-12-31 2020-11-10 Waterways tions nvelope 2: Pushcarts (75), Bicycle Bel l Rings (75), Boats (30), Bugg ies/Wheelbarrows (30), Tribik es (80), and Rolling Bins (160 ) PH-MMDA-230214-GO-RFB / The Supply, Fabrication, and Delivery of SWM Equipment 2. Minimizing Solid Waste in Single Stage - One E IBRD / 87840 Post Request for Bids Open - National 650,464.00 623,781.96 Signed 2021-04-30 2021-06-02 2021-05-14 2021-06-25 2021-06-23 2021-07-25 2021-10-25 2021-08-29 2022-01-01 2022-03-27 and Tools will strengthen the Waterways nvelope capacity of both MMDA and t he barangays on regular ope rations. PH-MMDA-234925-GO-RFQ / 2. Minimizing Solid Waste in Request for Quota Single Stage - One E 45 Composite Tumbler with IBRD / 87840 Post Open - National 24,930.00 23,396.12 Completed 2021-06-04 2021-07-30 2021-07-20 2021-10-28 2021-10-15 Waterways tions nvelope Manual Sieve with Tools & Eq uipment. PH-MMDA-CO205-4 / Other S 2. Minimizing Solid Waste in Single Stage - One E urvey Equipment, Software a IBRD / 87840 Post Request for Bids Open - National 251,400.00 246,064.95 Completed 2020-11-03 2020-11-03 2020-11-08 2020-12-20 2021-09-27 2021-01-19 2021-12-03 2021-02-23 2022-01-12 2021-08-22 2022-08-26 Waterways nvelope nd Accessories PH-MMDA-CO207 / Staff Unif 2. Minimizing Solid Waste in Request for Quota Single Stage - One E COFN / C1450 Post Open - National 23,480.77 6,076.75 Completed 2020-11-08 2021-01-03 2021-07-14 2021-07-02 2021-08-12 orm (PMO) Waterways tions nvelope PH-MMDA-257290-GO-RFQ / Service Vehicles for PMO, SW MO and FCSMO Pick-Up Car - 2 Units 2. Minimizing Solid Waste in Single Stage - One E IBRD / 87840 Post Request for Bids Open - National 151,121.00 0.00 Completed 2021-10-19 2021-11-03 2021-10-24 2021-12-05 2022-01-24 2022-01-04 2022-06-28 2022-02-08 2022-04-09 2022-10-12 8 - Seater Multi-purpose vehi Waterways nvelope cle - 1 Unit 16 - Seater Multi-purpose ve hicle - 1 Unit PH-MMDA-241874-GO-RFQ / Water Hyacinth Equipment in 2. Minimizing Solid Waste in Single Stage - One E cluding Multi-purpose Shredd IBRD / 87840 Post Request for Bids Open - National 564,195.00 549,604.41 Completed 2021-10-29 2021-11-22 2021-11-03 2021-12-15 2021-12-13 2022-01-29 2021-12-27 2022-03-05 2022-01-01 2022-05-04 2022-05-31 Waterways nvelope er, Dryer, Grinder, Mixer, Car bonizer, Extruding machine a nd Bio-Gas Digester PH-MMDA-278828-GO-RFB / Installation of an Organic Ma 2. Minimizing Solid Waste in Single Stage - One E gnetic Pyrolysis Energy Conv IBRD / 87840 Post Request for Bids Open - National 604,000.00 620,785.21 Signed 2022-02-18 2022-03-08 2022-02-21 2022-04-04 2022-04-04 2022-05-19 2022-05-26 2022-06-23 2022-07-05 2022-09-21 Waterways nvelope ersion Equipment for the Res idual Waste in Vitas Pumping Station PH-MMDA-278831-GO-RFQ / 2. Minimizing Solid Waste in Request for Quota Single Stage - One E Fabrication, Supply and Deliv IBRD / 87840 Post Open - National 97,852.00 0.00 Signed 2022-02-22 2022-06-17 2023-04-13 Waterways tions nvelope ery of Mobile Materials Recov ery Storage PH-MMDA-278850-GO-RFB / Procurement of Solid Waste Management Tools and Equip ment for the Implementation 2. Minimizing Solid Waste in Single Stage - One E IBRD / 87840 Post Request for Bids Open - National 445,045.00 0.00 Signed 2022-02-25 2022-02-25 2022-03-04 2022-04-15 2022-04-04 2022-05-30 2022-06-28 2022-07-04 2022-12-01 of the Planning and Demonst Waterways nvelope ration of the Community-Bas ed Solid Waste Management Initiatives to Catchment Area s for Year 1 PH-MMDA-296130-GO-RFB / Brand New Generator Set wit 2. Minimizing Solid Waste in Single Stage - One E IBRD / 87840 Post Request for Bids Open - National 200,000.00 0.00 Signed 2022-05-20 2022-06-07 2022-05-25 2022-07-06 2022-06-27 2022-08-05 2022-10-03 2022-09-09 2023-03-08 h Mobile Trailer and Double C Waterways nvelope ab Truck with Boom Crane Dr op Side MT PH-MMDA-298509-GO-RFB / Supply, Delivery, Installation 2. Minimizing Solid Waste in Single Stage - One E COFN / C1450 Post Request for Bids Open - National 105,000.00 0.00 Signed 2022-06-30 2022-08-10 2022-07-05 2022-08-16 2022-09-05 2022-09-15 2022-10-06 2022-10-20 2023-03-19 and Commissioning of Plastic Waterways nvelope Processing Equipment PH-MMDA-298523-GO-RFB / 2. Minimizing Solid Waste in Single Stage - One E Supply, Delivery, Installation COFN / C1450 Post Request for Bids Open - National 908,500.00 0.00 Signed 2022-06-30 2022-08-10 2022-07-05 2022-08-16 2022-09-05 2022-09-15 2022-10-27 2022-10-20 2023-03-19 Waterways nvelope and Commissioning of Pyroly sis Equipment PH-MMDA-298529-GO-RFB / 4. Project Management and Single Stage - One E Under Imple Supply and Delivery of ICT Eq COFN / C1450 Post Request for Bids Open - National 250,300.00 0.00 2022-06-30 2022-08-10 2022-07-05 2022-08-16 2022-09-15 2022-10-20 2022-12-04 Coordination nvelope mentation uipment and Software Year 4 PH-MMDA-303625-GO-RFB / Supply and Delivery of Moder 2. Minimizing Solid Waste in Single Stage - One E COFN / C1450 Post Request for Bids Open - National 2,653,691.25 0.00 Signed 2022-08-15 2022-08-15 2022-08-20 2022-09-19 2022-12-07 2022-11-03 2022-12-27 2022-12-08 2023-03-08 n Heavy Equipment for Effici Waterways nvelope ent Solid Waste Collection PH-MMDA-307648-GO-RFB / Information, Education and C ommunication (IEC) Campaig 2. Minimizing Solid Waste in Single Stage - One E Under Imple COFN / C1450 Post Request for Bids Open - National 210,300.00 0.00 2022-08-15 2022-08-04 2022-08-20 2022-10-01 2022-10-31 2022-12-05 2023-04-04 n Materials for Component 2: Waterways nvelope mentation Minimizing Solid Waste in Wa terways of the Metro Manila Flood Management Project Page 3 PH-MMDA-298500-GO-DIR / 2. Minimizing Solid Waste in Supply, Delivery, Installation COFN / C1450 Post Direct Selection Direct - National 628,000.00 0.00 Signed 2022-08-09 2022-08-09 2022-08-23 2022-08-12 2022-10-20 2023-03-19 Waterways and Commissioning of Solid Waste Granulator PH-MMDA-323005-GO-RFB / 2. Minimizing Solid Waste in Single Stage - One E Pending Impl Mobile Materials Recovery Fa IBRD / 87840 Post Request for Bids Open - National 701,284.00 0.00 2022-10-01 2022-10-06 2022-11-17 2022-12-17 2023-01-21 2023-07-20 Waterways nvelope ementation ciity for LGUs PH-MMDA-CO42-4 / PMO Op erations, Manpower, Supplies 4. Project Management and Request for Quota Single Stage - One E IBRD / 87840 Post Open - National 4,807.69 0.00 Canceled 2020-11-08 2021-01-03 2021-07-02 , Equipment, Furniture and M Coordination tions nvelope eeting (Operations - Office A ppliances) PH-MMDA-CO204-5 / Conduc t of Operation and Maintenan ce for Solid Waste Granulator 2. Minimizing Solid Waste in Request for Quota Single Stage - One E IBRD / 87840 Post Open - National 19,230.76 0.00 Canceled 2020-11-08 2021-01-03 2021-07-02 - Procurement of additional p Waterways tions nvelope arts and accessories for a mo re effective utilization of Soli d Waste Granulator PH-MMDA-2019203 / LED W all Rental for the 2019 Solid Waste Management (SWM) S ummit to kickoff and support 2. Minimizing Solid Waste in Request for Quota Single Stage - One E COFN / C1450 Post Limited 4,410.00 0.00 Canceled 2019-11-03 2019-11-15 2019-12-29 2020-06-26 the IEC campaigns, engage b Waterways tions nvelope arangay officials, and introdu ce the concept of circular res ource management through i nteractive activities. PH-MMDA-CO201-1 / Pilot Ba rangay-Based SWM Technolo gies - Procurement of propos 2. Minimizing Solid Waste in Request for Quota Single Stage - One E COFN / C1450 Post Open - National 24,306.81 0.00 Canceled 2020-11-08 2021-01-03 2021-07-02 ed Solid Waste Collection Tec Waterways tions nvelope hnologies and installation in t he pilot barangays for the im plementation of Component 2 PH-MMDA-323004-GO-RFQ / 2. Minimizing Solid Waste in Request for Quota Single Stage - One E Pending Impl Fabrication and Installation o IBRD / 87840 Post Open - National 10,072.00 0.00 2022-10-06 2022-12-01 2023-05-30 Waterways tions nvelope ementation f Hydraulic Cylinder PH-MMDA-323003-GO-RFQ / Customized T-Shirts for the S 2. Minimizing Solid Waste in Request for Quota Single Stage - One E Pending Impl IBRD / 87840 Post Open - National 14,243.00 0.00 2022-08-06 2022-10-01 2023-03-30 ynchronized Clean-up Drive i Waterways tions nvelope ementation n Selected Waterways PH-MMDA-323007-GO-RFQ / 2. Minimizing Solid Waste in Request for Quota Single Stage - One E Pending Impl Supply and Delivery of Materi IBRD / 87840 Post Open - National 10,028.00 0.00 2022-08-06 2022-10-01 2023-03-30 Waterways tions nvelope ementation als for the Brick Making Facili ty PH-MMDA-323008-GO-RFQ / 2. Minimizing Solid Waste in Request for Quota Single Stage - One E Pending Impl Materials for the Vermicomp IBRD / 87840 Post Open - National 6,000.00 0.00 2022-10-06 2022-12-01 2023-05-30 Waterways tions nvelope ementation osting Facility in Vitas PS NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PH-MMDA-CO201-2 / Barang ay-based Waste Collection fr om Waterways-Enforcement 2. Minimizing Solid Waste in Request for Quota Single Stage - One E Pending Impl IBRD / 87840 Post Open - National 14,198.60 0.00 2020-11-08 2021-01-03 2021-07-02 of Solid Waste Management Waterways tions nvelope ementation system in barangays for the i mplementation of Componen t2 PH-MMDA-CO201-8 / Capacit y Building for Barangays- Kno wledge enhancement initiativ 2. Minimizing Solid Waste in Request for Quota Single Stage - One E Pending Impl e for barangays in the adopti COFN / C1450 Post Open - National 19,592.31 0.00 2020-11-08 2021-01-03 2021-07-02 Waterways tions nvelope ementation on of improved solid waste m anagement system under Co mponent 2 programs and pro jects PH-MMDA-200985-NC-RFQ / Audio Visual Presentation for 2. Minimizing Solid Waste in Request for Quota Single Stage - One E IBRD / 87840 Post Open - National 57,692.30 52,026.13 Completed 2019-10-15 2019-12-10 2019-12-28 2020-06-07 2020-09-24 IEC-BCC campaigns of the M Waterways tions nvelope MFMP Component 2 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PH-MMDA-59028-CS-QCBS / Services of Consultancy Firm 2. Minimizing Solid Waste in Quality And Cost- Open - Internationa that will develop the Commu IBRD / 87840 Prior 769,231.00 1,458,471.24 Signed 2018-04-23 2018-10-12 2018-05-14 2019-01-21 2018-06-27 2020-01-29 2018-07-25 2020-03-09 2018-08-24 2020-10-14 2018-09-28 2020-11-23 2018-11-02 2020-12-29 2019-11-02 Waterways Based Selection l nity-based Management Syst em under Component 2 PH-MMDA-59026-CS-QCBS / Procurement of consulting fir 2. Minimizing Solid Waste in Quality And Cost- Open - Internationa IBRD / 87840 Prior 1,153,846.00 1,120,732.95 Signed 2018-04-23 2018-06-22 2018-05-14 2018-08-09 2018-06-27 2019-06-05 2018-07-25 2019-08-15 2018-08-24 2020-02-18 2018-09-28 2020-10-05 2018-11-02 2020-12-02 2019-11-02 m services that will develop t Waterways Based Selection l he Metro Manila Solid Waste Master Plan PH-MMDA-257297-GO-RFQ / Consultancy Services for Des 2. Minimizing Solid Waste in Quality And Cost- Open - Internationa IBRD / 87840 Post 836,700.00 0.00 Signed 2021-11-14 2021-10-28 2021-12-05 2021-11-05 2022-01-18 2022-03-21 2022-02-15 2022-05-05 2022-03-17 2022-05-19 2022-04-21 2022-05-05 2022-05-26 2023-05-26 ign and Development of Man Waterways Based Selection l agement Information System (MIS) PH-MMDA-268998-CS-QCBS / Consulting Services for the 2. Minimizing Solid Waste in Quality And Cost- Open - Internationa IBRD / 87840 Post 550,335.00 0.00 Signed 2021-12-27 2022-03-09 2022-01-17 2022-04-26 2022-03-02 2022-07-17 2022-03-30 2022-09-19 2022-04-29 2022-11-14 2022-06-03 2022-11-30 2022-07-08 2023-04-04 Conduct of Waste Analysis a Waterways Based Selection l nd Characterisation Study (W ACS) for Metro Manila Page 4 PH-MMDA-268999-CS-QCBS / Consultancy Services to con duct Feasibility Study on the 2. Minimizing Solid Waste in Quality And Cost- Open - Internationa IBRD / 87840 Post 360,510.00 0.00 Signed 2021-12-27 2022-03-08 2022-01-17 2022-04-18 2022-03-02 2022-07-17 2022-03-30 2022-11-25 2022-04-29 2022-11-15 2022-06-03 2022-11-30 2022-07-08 2023-07-08 Establishment of a Treatmen Waterways Based Selection l t/Processing Technology, Faci lity and System to Manage H ousehold Health Care Waste PH-MMDA-279254-CS-QCBS / CONSULTING SERVICES FOR PLANNING AND DEMONSTRA 2. Minimizing Solid Waste in Quality And Cost- Open - Internationa Pending Impleme IBRD / 87840 Prior 2,988,850.00 0.00 2022-02-28 2022-03-21 2022-05-04 2022-06-08 2022-07-23 2022-09-03 2022-10-08 2024-09-27 TION OF COMMUNITY-BASED Waterways Based Selection l ntation SOLID WASTE MANAGEMENT INITIATIVES FOR YEAR 3 PROJ ECT DRAINAGE AREAS PH-MMDA-279919-CS-CQS / Consultancy Services for the 2. Minimizing Solid Waste in Consultant Qualifi Under Implement IBRD / 87840 Post Open - National 80,000.00 0.00 2022-02-25 2022-02-15 2022-03-18 2022-05-01 2022-06-15 2022-07-20 2023-07-15 Development and Production Waterways cation Selection ation of Audio-Visual Presentation PH-MMDA-279920-CS-CQS / Consultancy Services for the Conceptualisation and Prepar 2. Minimizing Solid Waste in Consultant Qualifi ation of Detailed Engineering IBRD / 87840 Post Open - National 144,000.00 0.00 Signed 2022-03-04 2022-03-08 2022-03-25 2022-04-18 2022-05-08 2022-07-17 2022-06-07 2022-12-07 2022-07-12 2022-12-09 Waterways cation Selection Design for the Construction o f the Children's Solid Waste Management Ecological Hub (ECOHUB) in Taguig Pumping Station PH-MMDA-CO202-1 / Waste Analysis and Characterizatio n Study for the LGUs of Metr 2. Minimizing Solid Waste in Quality And Cost- Open - Internationa o Manila- Study to be conduc IBRD / 87840 Post 311,538.46 0.00 Canceled 2020-11-03 2020-11-24 2021-01-07 2021-02-04 2021-03-06 2021-04-10 2021-05-15 2022-05-15 Waterways Based Selection l ted for the purposes of data r efinement and validation und er the implementation of Co mponent 2. PH-MMDA-327114-CS-QCBS / Procurement of Consultancy Services for the Developmen 2. Minimizing Solid Waste in Quality And Cost- Open - Internationa Under Implement t, Production, Curation and P IBRD / 87840 Post 1,066,800.53 0.00 2022-11-18 2023-02-20 2022-12-09 2022-12-13 2023-01-22 2023-03-31 2023-02-19 2023-03-21 2023-04-25 2023-05-30 2024-05-29 Waterways Based Selection l ation ublication of MMFMP Commu nication and Social Media Col laterals and the Creation of t he MMFMP Website PH-MMDA-CO202-2 / Procure 2. Minimizing Solid Waste in Quality And Cost- Open - Internationa ment of Consultancy Service IBRD / 87840 Prior 2,842,204.42 0.00 Canceled 2020-11-03 2021-05-12 2020-11-24 2021-07-20 2021-01-07 2022-02-10 2021-02-04 2021-12-03 2021-03-06 2022-05-04 2021-04-10 2021-05-15 2022-05-15 Waterways Based Selection l s for the CBSWMP Year 2 PH-MMDA-358266-CS-QCBS / Consulting Services for the 2. Minimizing Solid Waste in Consultant Qualifi Open - Internationa Under Implement IBRD / 87840 Post 185,185.00 0.00 2023-05-26 2023-04-10 2023-06-16 2023-06-22 2023-07-21 2023-08-20 2023-10-10 2024-03-08 Conduct of Rapid Cumulative Waterways cation Selection l ation Impact Assessment (RCIA) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PH-MMDA-59027-CS-INDV / Project Management Speciali 4. Project Management and Individual Consult st (PMS) who shall oversee a IBRD / 87840 Post Open 85,000.00 87,785.49 Signed 2018-04-16 2018-05-21 2018-06-04 2018-09-03 2018-06-25 2018-10-08 2018-07-30 2018-10-16 2019-01-26 Coordination ant Selection nd manage the over-all techn ical, administrative and docu ment control of the project PH-MMDA-64559-CS-INDV / Additional Project Manageme nt Specialist (PMS) who shall oversee and manage technic 4. Project Management and Individual Consult IBRD / 87840 Post Open 85,000.00 15,563.58 Signed 2018-06-04 2019-08-01 2018-07-23 2019-06-10 2018-08-13 2019-07-01 2018-09-17 2019-08-02 2019-03-16 al, administrative and docum Coordination ant Selection ent control of the project and shall head a group of speciali sts with the actual communit y-based SWM activities. PH-MMDA-122170-CS-INDV- 1 / The Project Manager shall oversee and manage the ove 4. Project Management and Individual Consult COFN / C1450 Post Open 101,923.00 23,943.97 Signed 2019-05-28 2019-05-28 2019-07-16 2019-12-11 2019-08-06 2020-01-23 2019-09-10 2020-03-13 2020-03-08 rall day-to-day technical, ad Coordination ant Selection ministrative, and document c ontrol in MMDA’s Project Man agement Office (PMO). PH-MMDA-110488-CS-INDV- 1 / The Project Officer shall s erve as the substitute of the Project Manager to oversee a 4. Project Management and Individual Consult COFN / C1450 Post Open 86,634.62 20,365.38 Completed 2019-07-30 2019-07-30 2019-09-17 2019-09-09 2019-10-08 2019-09-13 2019-11-12 2019-12-24 2020-05-10 2022-06-01 nd manage the overall techni Coordination ant Selection cal, administrative, and docu ment control of the project in consultation with the MMDA Project Management Office ( PMO). PH-MMDA-110487-CS-INDV- 1 / The Procurement Speciali st shall manage the overall p 4. Project Management and Individual Consult COFN / C1450 Post Open 86,634.62 20,365.38 Completed 2019-04-29 2019-04-29 2019-06-17 2019-09-18 2019-07-08 2019-09-23 2019-08-12 2019-11-26 2020-02-08 2020-10-14 rocurement activity of the pr Coordination ant Selection oject in consultation with the MMDA Project Management Office (PMO). PH-MMDA-119346-CS-INDV- 1 / The Finance Management Specialist shall oversee and manage the overall financial 4. Project Management and Individual Consult COFN / C1450 Post Open 86,634.62 20,365.38 Signed 2019-04-29 2019-04-29 2019-06-17 2019-10-23 2019-07-08 2019-10-28 2019-08-12 2019-11-14 2020-02-08 management aspect includin Coordination ant Selection g technical, administrative, a nd document controls of the project in consultation with t he MMDA Project Manageme nt Office (PMO). PH-MMDA-148143-CS-INDV / Additional Community Devel opment Specialist (CDS) who shall be responsible for coord 2. Minimizing Solid Waste in Individual Consult inating and monitoring the c COFN / C1450 Post Open 65,000.00 16,114.71 Signed 2019-12-02 2019-12-02 2020-01-20 2020-09-21 2020-02-10 2020-09-30 2020-03-16 2020-10-08 2020-09-12 Waterways ant Selection ommunity development aspe cts of Component 2 of MMFM P. The CDS shall support the Project Management Office a nd Solid Waste Management Office. Page 5 PH-MMDA-122171-CS-INDV- 1 / The Community Develop ment Specialist (CDS) shall b 4. Project Management and Individual Consult COFN / C1450 Post Open 66,250.00 0.00 Canceled 2019-06-20 2019-06-20 2019-08-08 2019-08-29 2019-10-03 2020-03-31 e responsible for coordinatin Coordination ant Selection g and monitoring the commu nity development aspects of the Component 2 of MMFMP. PH-MMDA-205051-CS-INDV / The Procurement Specialist s hall manage the overall proc 4. Project Management and Individual Consult COFN / C1450 Post Open 60,480.76 20,084.67 Signed 2020-11-17 2020-11-17 2021-01-05 2021-01-18 2021-01-26 2021-03-08 2021-03-02 2021-03-17 2021-08-29 urement activity of the proje Coordination ant Selection ct in consultation with the M MDA Project Management Off ice (PMO) PH-MMDA-122171-INDV-2 / T he Community Development Specialist (CDS) shall be resp 4. Project Management and Individual Consult COFN / C1450 Post Open 66,250.00 15,374.61 Signed 2019-11-30 2020-11-30 2020-01-18 2020-11-18 2020-02-08 2021-02-08 2020-03-14 2021-02-23 2020-09-10 onsible for coordinating and Coordination ant Selection monitoring the community d evelopment aspects of the C omponent 2 of MMFMP. PH-MMDA-216929-CS-INDV / Individual Consultancy Servic 4. Project Management and Individual Consult IBRD / 87840 Post Open 61,837.50 20,105.26 Signed 2021-01-04 2021-01-04 2021-02-22 2021-03-01 2021-03-15 2021-03-12 2021-04-19 2021-03-16 2021-10-16 es/Monitoring & Evaluation ( Coordination ant Selection M&E) Specialist PH-MMDA / Individual Consul 4. Project Management and Individual Consult tancy Services/PMO Internal IBRD / 87840 Post Open 3,557.69 0.00 Canceled 2021-01-04 2021-01-04 2021-02-22 2021-03-15 2021-04-19 2021-10-16 Coordination ant Selection Midterm Assessment Consult ant PH-MMDA-220061-CS-INDV / Individual Consultancy Servic 4. Project Management and Individual Consult IBRD / 87840 Post Direct 3,557.69 3,678.01 Signed 2021-01-04 2021-01-04 2021-01-14 2021-02-19 2021-02-04 2021-02-19 2021-03-11 2021-03-06 2021-09-07 es/PMO Internal Midterm Ass Coordination ant Selection essment Consultant PH-MMDA-229420-CS-INDV / The overall function covers maintaining and facilitating p 4. Project Management and Individual Consult IBRD / 87840 Post Open 1,300.00 15,175.10 Signed 2021-04-16 2021-04-19 2021-06-04 2021-10-29 2021-06-25 2021-11-07 2021-07-30 2021-11-10 2022-07-30 ositive relationships between Coordination ant Selection the public and other organiza tions often using media outle ts. PH-MMDA-298539-CS-INDV / 4. Project Management and Individual Consult COFN / C1450 Post Open 59,700.00 0.00 Signed 2022-06-26 2022-06-26 2022-07-15 2022-07-01 2022-07-22 2022-07-18 2022-08-12 2023-08-12 Project Officer Coordination ant Selection PH-MMDA-CO41-2 / Project Management Office Operatio 4. Project Management and Individual Consult IBRD / 87840 Post Open 125,673.08 0.00 Canceled 2020-01-01 2020-02-19 2020-03-11 2020-04-15 2020-10-12 ns - (Manpower - PMO Consul Coordination ant Selection tants Renumeration) Page 6 Procurement Plan (For Contracts not yet initiated – to be entered in STEP) I. General 1. Project Information Country: Malawi Project Name: Southern Africa Tuberculosis & Health Systems Support Project Project ID: P155658 2. Project Implementation Agency: Ministry of Health – National TB Control Programme 3. Date of the Procurement Plan: June 2017 4. Period Covered by this procurement plan: 24 Months II. Thresholds for Prior Review, Procurement Approaches and Methods A. Goods, Works and Non-Consulting Services Procurement Approaches and Methods Prior Review (US$ millions) Category (US$ Open Open Request for millions) International National Quotation (RfQ) Works ≥5 ≥5 >0.1- <0.1 <5 Goods, IT, and > 0.1 - non-consulting ≥1 ≥1 <0.1 <5 services B. Consulting Services Category Prior Review Short List of National Consultants (US$ (US$ million) millions) Consulting Engineering and Services Construction Supervision Consultants ≥ 0.2 < 0.2 ≥ 0.3 (Firms) Individual ≥ 0.1 NA. NA. Consultants 1 [Overall Project Procurement Risk is SUBSTANTIAL] Notes: Terms of Reference: Terms of Reference for all contracts shall be cleared by the Bank, regardless of whether the assignment is for prior or post review. Advertisement: Consultancy Service for Contracts estimated to cost US$ 300,000 equivalent and above per contract shall be advertised in UNDB online in addition to advertising in National News Paper(s) of wide circulation and/or Regional News Paper(s). 2 III. Packages for Goods, Works and Non-Consulting Services Component 1: Prevention Detection and Treatment of TB Goods Activity Contract Description Estimate Review Market Selection Evaluatio Procureme Prequ Domes Expect Expecte No d Cost by Approach Method n Options nt Process: alifica tic ed d date (US$) Bank (Open- (RFP, (BAFO, (Single/Mul tion Prefere date of of (Prior/P National/ RFB, Rated tiple (Yes/ nce bid/ Contract ost) Internation RFQ, DS Criteria Stages; No) (Yes/N propos Signatur al/ Limited etc.) etc.) One/Two o) al e etc.) Envelopes openin etc) g 1.2.1.1.5 Procure standard equipment 94,444 Post Limited RFQ Single No No 31st 30th for pre-in and post-service August Septem medical examinations for 2017 ber occupational health and safety. 2017 1.2.1.1.4 Procure Inspection Equipment 97,083 Post Limited RFQ Single No No 31st 30th for Ministry of Labour and August Septem Department of Mines 2017 ber 2017 1.1.1.4.4 Procure Motorcycles to support 63,300 Post Limited RFQ Single No No 31st 30th sputum sample collection August Septem points/supervision 2017 ber 2017 1.1.2.6.3 Personal protective materials 12,660 Post Limited RFQ Single No No 31st 30th for TB Laboratory Personnel August Septem (TB infection control) 2017 ber 2017 Stationery 19,305.4 Post Limited RFQ Single No No 31st 30th 9 August Septem 2017 ber 2017 Sub-Total 286,792 .49 3 Works Activity Contract Description Estimate Review Market Selection Evaluatio Procureme Prequ Domes Expect Expecte No d Cost by Approach Method n Options nt Process: alifica tic ed d date (US$) Bank (Open- (RFP, (BAFO, (Single/Mul tion Prefere date of of (Prior/P National/ RFB, Rated tiple (Yes/ nce bid/ Contract ost) Internation RFQ, DS Criteria Stages; No) (Yes/N propos Signatur al Limited etc.) etc.) One/Two o) al e etc.) Envelopes openin etc) g 1.1.3.3.1 Renovations (MDR TB Centres) 33,333 Post Limited RFQ Single No No 31st 30th August Septem 2017 ber 2017 1.1.2.6.2 Identify and Refurbishment of 41,667 Post Limited RFQ Single No No 31st 30th TB Isolation Rooms at selected August Septem facilities 2017 ber 2017 2.2.2.7.3 Renovations and Furnish Labs 108,333 Post Open- RFB Single No No 31st 30th National August Septem 2017 ber 2017 Sub-Total 183,333 4 Component 2: Regional Capacity for Disease Surveillance, Diagnostics Management of TB and Occupational Health Packages for Consulting Services Activity Contract Description Estimate Review Market Selectio Shortlis Expected date of bid/ Expected No d Cost by Approach n ting proposal opening date of (US$) Bank (Open- Method (Yes/ Contract (Prior/P National/ (QCBS, No) Signature ost) Internatio FBBS, nal LCBS, Limited QBS, etc.) CQS, DS etc.) 2.3.1.1.1 Consultant to draft/review the 18,950 Prior Open - CQS Yes 31st August 2017 30th Mines Safety Act/Public Health National September Act/Occupational Safety Health 2017 and Welfare Act and Regulations. Sub-Total 18,950 Goods 5 Activity Contract Description Estimated Review Market Selection Evaluati Procureme Prequ Domes Expect Expecte No Cost (US$) by Approach Method on nt Process: alifica tic ed d date Bank (Open- (RFP, RFB, Options (Single/Mul tion Prefere date of of (Prior/P National/ RFQ, DS (BAFO, tiple (Yes/ nce bid/ Contract ost) Internation etc.) Rated Stages; No) (Yes/N propos Signatur al Limited Criteria One/Two o) al e etc.) etc.) Envelopes openin etc) g 2.2.2.5.1 Procure Microscopes and Lab 53,932 Post Open- RFB Single No No 12 31 July Supplies National June 2017 2017 2.2.2.5.1 Procurement of Lab 20,000 Post Limited RFQ Single No No 31st 30th Information System, August Septem Computers and Printers 2017 ber 2017 2.2.2.6.1 Procure Xray Machines 888,889 Post Open- RFB Single No No 12 31 July National June 2017 2017 2.1.1.1.1 Procure Laptops for Regional 5352 Post Limited RFQ Single No No 31st 30th Field Epidemiology Training August Septem Program , 2017 ber 2017 2.2.2.4.1 Procure GeneXpert and 200,000 Post Limited RFB Single No No 31st 30th expand Xpert facilities August Septem 2017 ber 2017 Sub-Total 1,168,173 .00 Component 3: Learning, Knowledge and Innovation Packages for Consulting Services Activity Contract Description Estimate Review Market Selectio Shortlis Expected date of bid/ Expected No d Cost by Approach n ting proposal opening date of (US$) Bank (Open- Method (Yes/ Contract (Prior/P National/ (QCBS, No) Signature 6 ost) Internatio FBBS, nal LCBS, Limited QBS, etc.) CQS, DS etc.) 3.1.1.3.3 Consultant to conduct Baseline 108,410 Prior Open- DS Yes 28th February 2017 1st April Assessment for TB in Mines National 2017 3.1.1.4.3 Consultant to conduct E-Health 464409 Prior Open- DS Yes 8th March 2017 10th April for Community Intervention National 2017 3.1.31 IT Specialist - Consultant 36000 Post Open- DS Yes 11th May 2017 1st July National 2017 Sub-Total 608,819 7 Goods Activity Contract Description Estimate Review Market Selection Evaluatio Procureme Prequ Domes Expect Expecte No d Cost by Approach Method n Options nt Process: alifica tic ed d date (US$) Bank (Open- (RFP, (BAFO, (Single/Mul tion Prefere date of of (Prior/P National/ RFB, Rated tiple (Yes/ nce bid/ Contract ost) Internation RFQ, DS Criteria Stages; No) (Yes/N propos Signatur al Limited etc.) etc.) One/Two o) al e etc.) Envelopes openin etc) g 3.1.1.4.3 Procure E-Health for 125,000 Post Open- RFB Single No No 12 31 July Community Intervention National June 2017 Server, Computers, Networking 2017 and Tablets 3..3.43 Procure Geographical 4000 Post Limited RFQ Single No No Information System (GIS) Tool 3.4.1.1.1 Maintenance of Motor Vehicles 33,333 Post Limited RFQ Single No No 31st 30th 3 August Septem 2017 ber 2017 3.4.1.2.3 Purchase of Stationery 32,777 Post Limited RFQ Single No No 31st 30th August Septem 2017 ber 2017 3.4.1.2.1 Procurement of IT Equipment 105,000 Post Open- RFB Single No No 31st 30th (Video Conference National August Septem Facilities,Laptops and 2017 ber Communication 2017 Sub-Total 300,110 8 PROCUREMENT Eastern and Southern Africa : AFR RI-Southern Africa Tuberculosis and Health Systems Support Project PLAN General Information Country: Eastern and Southern Africa 2017-05-31 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P155658 GPN Date: Project Name: AFR RI-Southern Africa Tuberculosis and Health Systems Support Project Loan / Credit No: IDA / 58220, IDA / 58230, IDA / 66950 Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SATBHSS/MOH/W-003 / Upgr Regional Capacity for Diseas ading of NTRL including Repa e Surveillance, and Diagnost Request for Quota Single Stage - One E 2017-11-2 ir of roofing, ceiling and floori IDA / 58220 ics and Management of TB a Post Open - National 170,000.00 110,024.93 Signed 2017-08-07 2017-11-07 2017-08-11 2017-09-01 2018-04-19 2017-09-15 2017-11-24 2017-09-29 2017-11-28 tions nvelope 8 ng, prefabricated panels, repl nd Occupational Lung Disea acement of doors etc. ses SATBHSS/MOH/W-004 / Repa Regional Capacity for Diseas ir of Negative Pressure Syste e Surveillance, and Diagnost Request for Quota Single Stage - One E Pending Imp 2017-11-1 IDA / 58220 Post Open - National 40,000.00 0.00 2017-08-12 2017-10-07 ms at National TB Reference ics and Management of TB a tions nvelope lementation 6 Laboratory nd Occupational Lung Disea ses SATBHSS/MOH/W-005 / Rem Regional Capacity for Diseas oval and Re installation and e Surveillance, and Diagnost Pending Imp 2018-05-1 IDA / 58220 Post Direct Selection Direct 15,000.00 0.00 2017-11-10 2017-11-15 2017-12-20 Calibration of 3 BD Bactet M ics and Management of TB a lementation 9 GIT Machines for Preperation nd Occupational Lung Disea NTRL Renovation ses SATBHSS/MOH/W-006 / Relo Regional Capacity for Diseas cation, Re installation and Ca e Surveillance, and Diagnost Pending Imp 2018-05-1 IDA / 58220 Post Direct Selection Direct 14,000.00 0.00 2017-11-10 2017-11-15 2017-12-20 libration of 4 Bio safety cabi ics and Management of TB a lementation 9 nets at NTRL nd Occupational Lung Disea ses SATBHSS/MOH/W / Construct ion works for Extension and Renovation of Correctional fa Innovative Prevention, Detec Single Stage - One E 2019-10-2 IDA / 58220 Post Request for Bids Open - National 678,558.00 0.00 Canceled 2018-10-01 2018-10-06 2018-11-17 2018-12-03 2018-12-24 cilities to establish isolation c tion and Treatment of TB nvelope 0 ells and renovation of Moteb ang Lab to establish TB Labo ratory. SATBHSS/MOH/W-002 / Upgr Regional Capacity for Diseas ading of Leribe laboratory - n e Surveillance, and Diagnost Request for Quota Single Stage - One E 2019-08-0 IDA / 58220 Post Open - National 106,000.00 0.00 Canceled 2018-12-08 2019-02-05 egative pressure and infrastr ics and Management of TB a tions nvelope 7 uctural renovations of existin nd Occupational Lung Disea g laboratory ses SATBHSS/MOH/W-002/2019 / Payment for the contractor fo Regional Capacity for Diseas r Motebang renovations (Ext e Surveillance, and Diagnost Single Stage - One E Under Imple 2020-01-2 ension on one side of the lab, IDA / 58220 ics and Management of TB a Post Request for Bids Open - National 559,382.48 0.00 2019-02-11 2018-12-02 2019-02-16 2019-03-30 2019-04-29 2019-06-03 nvelope mentation 9 Opening, move X-ray to a ne nd Occupational Lung Disea w location, Renovations to cr ses eate culture room, microscop y and anteroom) SATBHSS/MOH/W-001 / Expa Innovative Prevention, Detec Request for Quota Single Stage - One E 2020-02-0 nsion and renovation of isola IDA / 58220 Post Open - National 79,560.00 0.00 Canceled 2018-12-08 2019-02-05 tion and Treatment of TB tions nvelope 5 tion cells for Maseru Central Prison Only SATBHSS/MOH/W-001/2019 / National Procure Procurement of works for ren ment Document - Innovative Prevention, Detec 1,599,577.4 2020-11-1 ovation and establishment of IDA / 58220 Post Request for Bids 1 Envelope proce 1,312,877.28 Signed 2019-02-04 2018-12-20 2019-02-09 2019-03-23 2019-02-28 2019-04-22 2019-04-12 2019-05-27 2021-01-16 tion and Treatment of TB 3 7 the isolation cells at Maseru ss (Non Bank-SPD central Correctional Facility ) Regional Capacity for Diseas SATBHSS/MOH/W-004/2019 / Request for Quota e Surveillance, and Diagnost Pending Imp 2019-10-3 Upgrade NTRL Mechanical Sy IDA / 58220 Post Direct Selection Direct tions (Non Bank-S 50,000.00 0.00 2019-03-25 2019-03-30 2019-05-04 ics and Management of TB a lementation 1 stems PD) nd Occupational Lung Disea ses SATBHSS/MOH/W-003/2019 / Regional Capacity for Diseas Procure storage container at e Surveillance, and Diagnost Request for Quota Request for Quota Single Stage - One E Pending Imp 2019-08-2 NTRL Container turned into s IDA / 58220 ics and Management of TB a Post Open - National tions (Non Bank-S 41,151.50 0.00 2019-03-30 2019-05-25 tions nvelope lementation 3 torage including partitioning, nd Occupational Lung Disea PD) air conditioning and shelving ses mounted on a slab. LS-MOH-333101-CW-RFQ-SA TBHSSAF-2023 / Procure pref Request for Quota abricated structures and sha Innovative Prevention, Detec Request for Quota Single Stage - One E Under Imple 2023-09-1 IDA / 66950 Post Open - National tions (Non Bank-S 200,000.00 0.00 2023-01-20 2023-03-17 des for Maluti and Ntshekhe f tion and Treatment of TB tions nvelope mentation 3 PD) or OPD waiting, procure basi c Furnishings for Maluti and Ntshekhe OPD waiting LS-MOH-333149-CW-RFB-SA Regional Capacity for Diseas Request for Bids - TBHSSAF-2023 / Procuremen e Surveillance, and Diagnost Single Stage - One E Small Works SPD Under Imple 2024-01-1 t of a contractors for constru IDA / 66950 ics and Management of TB a Post Request for Bids Open - National 480,468.00 0.00 2023-04-02 2023-03-01 2023-04-07 2023-05-19 2023-04-12 2023-06-18 2023-07-23 nvelope (1 envelope proce mentation 9 ctions of 10 Solid screening nd Occupational Lung Disea ss) structures for the hospitals. ses GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WB/MOH/G-012 / Supply and Delivery of X-ray Equipment Regional Capacity for Diseas and Transportation Vehicle fo e Surveillance, and Diagnost r the National TB Program un Open - Internationa Single Stage - One E IDA / 58220 ics and Management of TB a Prior Request for Bids 900,000.00 1,053,788.36 Signed 2017-05-16 2017-05-21 2017-06-15 2017-06-15 2017-07-15 2017-11-02 2017-08-19 2017-11-20 2018-02-15 der Lot 1 and Lot 2 l nvelope nd Occupational Lung Disea Lot 1: Two Mobile X-ray Mach ses ines Lot 2: Mobile X-ray Machine, X-ray Generator and Mobile X -ray Transportation Vehicle SATBHSS/MOH/G-003 / Procu rement and Supply of Equip Innovative Prevention, Detec Request for Quota Single Stage - One E Pending Impl IDA / 58220 Post Open - National 5,347.98 0.00 2017-06-24 2017-07-24 2017-09-02 ment for Occupational Health tion and Treatment of TB tions nvelope ementation Services for Two Hospitals. Page 1 SATBHSS/MOH/G-022 / Procu rement and Supply of 3 Com Innovative Prevention, Detec Request for Quota Single Stage - One E Pending Impl IDA / 58220 Post Open - National 4,500.00 0.00 2017-06-30 2017-08-18 2017-09-27 puters for the Database to m tion and Treatment of TB tions nvelope ementation aintain Statistics of accidents and Incidences. SATBHSS/MOH/G-004 / Procu rement and Supply of Tablets Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 58220 Post Open - National 5,839.42 0.00 Canceled 2017-06-29 2017-08-18 2019-08-18 for Inspection System Applic tion and Treatment of TB tions nvelope ation for Two Districts Mafete ng and Leribe SATBHSS/MOH/G-006 / Procu Innovative Prevention, Detec Request for Quota Single Stage - One E Pending Impl rement and Supply of Project IDA / 58220 Post Open - National 2,000.00 0.00 2017-06-29 2017-08-17 2017-09-16 tion and Treatment of TB tions nvelope ementation or for OSH Training SATBHSS/MOH/G-010 / Procu Regional Capacity for Diseas rement and Supply of Laptop e Surveillance, and Diagnost Request for Quota Single Stage - One E Under Imple IDA / 58220 Post Open - National 15,000.00 0.00 2017-06-29 2017-08-04 2017-09-03 s for Strengthening Laborator ics and Management of TB a tions nvelope mentation y Electronic Systems. nd Occupational Lung Disea ses SATBHSS/MOH/G-005 / Procu Innovative Prevention, Detec Request for Quota Single Stage - One E Pending Impl rement and Supply of Dust S IDA / 58220 Post Open - National 4,866.16 0.00 2017-06-24 2017-08-10 2017-09-19 tion and Treatment of TB tions nvelope ementation ampling machine for Labour SATBHSS/MOH/G-013 / Procu Regional Capacity for Diseas rement and Supply of Pull Up e Surveillance, and Diagnost Request for Quota Single Stage - One E Pending Impl IDA / 58220 Post Open - National 2,403.00 0.00 2017-06-29 2017-08-04 2017-09-03 Banners for 9 Designated Por ics and Management of TB a tions nvelope ementation ts of Entry nd Occupational Lung Disea ses SATBHSS/MOH/G-014 / Procu Regional Capacity for Diseas rement and Supply of Identifi e Surveillance, and Diagnost Request for Quota Single Stage - One E Pending Impl IDA / 58220 Post Open - National 864.00 0.00 2017-06-30 2017-08-10 2017-09-09 cation Reflector Coats for 9 D ics and Management of TB a tions nvelope ementation esignated Ports of Entry nd Occupational Lung Disea ses Regional Capacity for Diseas SATBHSS/MOH/G-015 / Procu e Surveillance, and Diagnost Request for Quota Single Stage - One E Pending Impl rement and Supply of Protect IDA / 58220 Post Open - National 15,440.00 0.00 2017-06-30 2017-08-03 2017-09-02 ics and Management of TB a tions nvelope ementation ive Clothing (Freezers Suit) nd Occupational Lung Disea ses SATBHSS/MOH/G-016 / Procu Regional Capacity for Diseas rement and Supply of Waste e Surveillance, and Diagnost Request for Quota Single Stage - One E Pending Impl IDA / 58220 Post Open - National 43,480.00 0.00 2017-06-30 2017-08-04 2017-09-13 Management and Infection C ics and Management of TB a tions nvelope ementation ontrol nd Occupational Lung Disea ses SATBHSS/MOH/G-017 / Procu Regional Capacity for Diseas rement, Supply and Installati e Surveillance, and Diagnost Request for Quota Single Stage - One E Pending Impl IDA / 58220 Post Open - National 20,199.00 0.00 2017-06-30 2017-08-10 2017-10-09 on of Biosafety Cabinet for M ics and Management of TB a tions nvelope ementation afeteng inclusive of Service a nd Occupational Lung Disea nd Maintenance. ses SATBHSS/MOH/G-019 / Procu Regional Learning and Innov Request for Quota Single Stage - One E rement and Supply of Station IDA / 58220 ation, and Project Managem Post Open - National 2,000.00 0.00 Canceled 2017-06-30 2017-08-04 2017-09-03 tions nvelope ary for PIU ent SATBHSS/MOH/G-009 / Printi Regional Capacity for Diseas ng of National TB Laboratory e Surveillance, and Diagnost Request for Quota Single Stage - One E Pending Impl IDA / 58220 Post Open - National 405.50 0.00 2017-08-11 2017-09-20 2017-10-20 External Quality Assurance G ics and Management of TB a tions nvelope ementation uidelines nd Occupational Lung Disea ses SATBHSS/MOH/G-021 / Procu rement and Supply of (Nutriti Innovative Prevention, Detec Open - Internationa Single Stage - One E Under Imple IDA / 58220 Post Request for Bids 288,409.56 0.00 2017-08-14 2019-03-14 2017-08-19 2017-10-05 2017-11-09 2017-11-04 2017-12-18 2017-12-09 2018-01-18 onal) Therapeutic Feeding co tion and Treatment of TB l nvelope mentation mmodities for TB Patients. Regional Capacity for Diseas SATBHSS/MOH/G-023 / Procu e Surveillance, and Diagnost Request for Quota Single Stage - One E Pending Impl rement of Access Control eq IDA / 58220 Post Open - National 40,000.00 0.00 2017-08-06 2017-09-10 2017-10-20 ics and Management of TB a tions nvelope ementation uipment and Installation nd Occupational Lung Disea ses SATBHSS/MOH/G-024 / Procu rement of OI Drugs and Cosu Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 58220 Post Open - National 9,562.53 11,334.08 Completed 2017-11-06 2017-12-05 2019-06-12 2018-01-04 2019-07-12 mables including Gloves and tion and Treatment of TB tions nvelope N95 Masks for TEBA POCs SATBHSS/MOH/G-025 / Procu rement of 3 bio safety Cabin Innovative Prevention, Detec Request for Quota Single Stage - One E Pending Impl IDA / 58220 Post Open - National 17,031.63 0.00 2017-11-08 2017-12-01 2018-12-01 ets for TEBA POCs as part of tion and Treatment of TB tions nvelope ementation Environmental and Social saf eguards. SATBHSS/MOH/G-026 / Procu Regional Learning and Innov rement of Office Equipment f Request for Quota Single Stage - One E Pending Impl IDA / 58220 ation, and Project Managem Post Open - National 6,547.28 0.00 2017-11-08 2017-12-03 2018-01-02 or PIU and NTP Staff. tions nvelope ementation ent 4 Printers and 4 Laptops. SATBHSS/MOH/G-012 / Procu Regional Capacity for Diseas rement, Supply and Erection e Surveillance, and Diagnost Request for Quota Single Stage - One E Under Imple of 7 Prefabricated Park home IDA / 58220 ics and Management of TB a Post Open - National 210,000.00 0.00 2017-11-10 2018-01-07 2018-03-08 tions nvelope mentation s to establish Disease Surveil nd Occupational Lung Disea lance offices at the Borders ses SATBHSS/MOH/G-011 / Procu Regional Capacity for Diseas rement and Supply of Compu e Surveillance, and Diagnost Request for Quota Single Stage - One E Pending Impl IDA / 58220 Post Open - National 57,711.68 0.00 2017-11-09 2017-12-12 2018-01-21 ters for Cross Border Disease ics and Management of TB a tions nvelope ementation Surveillance nd Occupational Lung Disea ses SATBHSS/MOH/G-027 / Procu Regional Learning and Innov Request for Quota Single Stage - One E Pending Impl rement of Back Packs for Ext IDA / 58220 ation, and Project Managem Post Open - National 2,700.00 0.00 2017-11-07 2017-11-21 2017-12-06 tions nvelope ementation ernal Review ent SATBHSS/MOH/G-013/2018 / Procurement and supply of T Regional Learning and Innov Request for Quota Single Stage - One E Pending Impl wo Door Locker, Filling Cabi IDA / 58220 ation, and Project Managem Post Open - National 1,879.65 0.00 2018-02-17 2018-02-28 2018-03-15 tions nvelope ementation net, Project Camera, Fridge a ent nd Executive Office Chair SATBHSS/MOH/G-012/2018 / Regional Learning and Innov Procurement and Supply of B Request for Quota Single Stage - One E Pending Impl IDA / 58220 ation, and Project Managem Post Open - National 4,875.81 0.00 2018-02-17 2018-03-05 2018-03-20 randed Backpacks for RAC M tions nvelope ementation ent eeting to be held in Maseru 2 018 SATBHSS/MOH/G-014/2018 / Regional Learning and Innov Procurement of Vehicle( bod Request for Quota Single Stage - One E IDA / 58220 ation, and Project Managem Post Open - National 58,000.00 43,165.15 Completed 2018-04-24 2018-06-19 2018-05-19 2018-12-16 2018-06-19 y Type SUV with capacity of tions nvelope ent 5-7 seats) for PIU activities w ith insurance policy. Page 2 SATBHSS/MOH/G-015/2018 / Regional Learning and Innov Procurement and Supply of 2 Request for Quota Single Stage - One E Pending Impl IDA / 58220 ation, and Project Managem Post Open - National 1,900.00 0.00 2018-05-15 2018-07-10 2019-01-06 Laptops and Laptops Bag for tions nvelope ementation ent Debt Department at Ministry of Finance Regional Capacity for Diseas SATBHSS/MOH/G-016/2018 / e Surveillance, and Diagnost Procurement of extra Digital IDA / 58220 Post Direct Selection Direct 600,000.00 0.00 Canceled 2018-09-13 2018-10-01 2018-09-18 2018-10-23 2019-04-21 ics and Management of TB a Mobile X Ray nd Occupational Lung Disea ses SATBHSS/MOH/G-021/2018 / Regional Capacity for Diseas Procurement of Mobile digital e Surveillance, and Diagnost Pending Impl X-ray machines including tra IDA / 58220 ics and Management of TB a Post Direct Selection Direct 525,000.00 0.00 2018-12-10 2018-12-15 2019-01-19 2021-01-18 ementation nsportation vehicle and gene nd Occupational Lung Disea rator (for prevalence survey) ses Regional Capacity for Diseas SATBHSS/MOH/G-005/2018 / e Surveillance, and Diagnost Request for Quota Single Stage - One E Supply and delivery of Dust S IDA / 58220 Post Open - National 4,547.00 28,405.78 Completed 2018-12-13 2018-12-24 2020-12-01 2019-01-23 2021-01-21 ics and Management of TB a tions nvelope ampling Equipment nd Occupational Lung Disea ses Regional Capacity for Diseas SATBHSS/MOH/G-006/2018 / e Surveillance, and Diagnost Request for Quota Single Stage - One E Pending Impl Procurement, Supply and deli IDA / 58220 Post Open - National 3,258.00 0.00 2018-10-24 2018-11-04 2018-12-19 ics and Management of TB a tions nvelope ementation very of Protective Clothing nd Occupational Lung Disea ses SATBHSS/MOH/G-007/2018 / Procurement, supply and deli Innovative Prevention, Detec Request for Quota Single Stage - One E Pending Impl IDA / 58220 Post Open - National 4,030.32 0.00 2018-10-24 2018-11-04 2018-12-04 very of Computers for capturi tion and Treatment of TB tions nvelope ementation ng files for all compensation claims SATBHSS/MOH/G-008 / Procu Innovative Prevention, Detec Request for Quota Single Stage - One E Pending Impl rement and Supply of Protect IDA / 58220 Post Open - National 4,866.12 0.00 2019-09-06 2019-10-14 2019-11-13 tion and Treatment of TB tions nvelope ementation ive Equipment or Clothing SATBHSS/MOH/G-017/2018 / Procurement of 25000 Gene- Innovative Prevention, Detec Pending Impl IDA / 58220 Post Direct Selection Direct 285,060.00 0.00 2018-11-29 2018-12-04 2019-01-08 2019-03-09 Xpert Cartridges for intensifie tion and Treatment of TB ementation d case finding among miners SATBHSS/MOH/G-018/2018 / Procurement of Occupational Health Diagnostic equipment Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 58220 Post Open - National 5,000.00 2,691.97 Completed 2018-12-08 2019-02-02 2018-12-05 2019-08-01 2019-02-14 for Moteng and Nts'ekhe (Dig tion and Treatment of TB tions nvelope ital vitals monitor,Thermome ter, Diagnostic set, Glucomet er and Hb Meter ,) SATBHSS/MOH/G-019/2018 / Regional Capacity for Diseas Procurement of Calibration a e Surveillance, and Diagnost nd verification tools to servic Request for Quota Single Stage - One E IDA / 58220 ics and Management of TB a Post Open - National 2,000.00 0.00 Canceled 2018-12-15 2019-02-09 2019-08-08 e Laboratory equipment( Tac tions nvelope nd Occupational Lung Disea hometer, Reference thermo ses meter, Mass weights and Xpe rt Check) SATBHSS/MOH/G-020/2018 / Regional Learning and Innov Procurement of Public Health Request for Quota Single Stage - One E IDA / 58220 ation, and Project Managem Post Open - National 2,071.00 2,233.82 Completed 2018-12-04 2019-01-29 2018-10-09 2019-02-13 2018-10-18 Advisor Office Equipment ( C tions nvelope ent omputer and Printer) SATBHSS/MOH/G-008/2019 / Procure and supply Printed p Innovative Prevention, Detec Request for Quota Single Stage - One E amphlets with TB messages IDA / 58220 Post Open - National 36,828.24 11,150.87 Completed 2019-05-11 2019-07-06 2019-04-30 2019-08-20 2019-05-22 tion and Treatment of TB tions nvelope and disseminate at communi ty level on World TB day SATBHSS/MOH/G-009/2019 / Innovative Prevention, Detec Request for Quota Single Stage - One E Procure and Supply printed IDA / 58220 Post Open - National 7,459.42 0.00 Canceled 2019-04-06 2019-06-01 2019-07-01 tion and Treatment of TB tions nvelope SOPs (1000 copies) SATBHSS/MOH/G-011/2019 / Regional Capacity for Diseas Procure Pull up banners for p e Surveillance, and Diagnost Request for Quota Single Stage - One E IDA / 58220 Post Open - National 1,023.01 0.00 Canceled 2019-04-06 2019-06-01 2019-07-01 orts of Entry (9 pull up banne ics and Management of TB a tions nvelope rs for 9 ports of Entry) nd Occupational Lung Disea ses Regional Capacity for Diseas SATBHSS/MOH/G-012/2019 / e Surveillance, and Diagnost Request for Quota Single Stage - One E Pending Impl Procure a laptop and a printe IDA / 58220 Post Open - National 1,224.90 0.00 2019-03-23 2019-05-18 2019-06-17 ics and Management of TB a tions nvelope ementation r for an Epidemiologist nd Occupational Lung Disea ses SATBHSS/MOH/G-013/2019 / Regional Capacity for Diseas Procure equipment for TB dia e Surveillance, and Diagnost Request for Quota Open - Internationa Single Stage - One E Pending Impl IDA / 58220 Post 15,913.44 0.00 2019-05-18 2019-07-13 2019-10-11 gnosis for Motebang Laborat ics and Management of TB a tions l nvelope ementation ory nd Occupational Lung Disea ses SATBHSS/MOH/G-014/2019 / Regional Capacity for Diseas 3 biosafety cabinets, Install t e Surveillance, and Diagnost Request for Quota Open - Internationa Single Stage - One E IDA / 58220 Post 60,656.32 25,565.30 Signed 2019-03-16 2019-05-11 2018-06-05 2019-10-08 he mechanical system Upgra ics and Management of TB a tions l nvelope de of the NTRL lab to meet B nd Occupational Lung Disea SL3 standards ses SATBHSS/MOH/G-016/2019 / Regional Capacity for Diseas Procure standards, for NTRL l e Surveillance, and Diagnost ab accreditation (Procure ISO Pending Impl IDA / 58220 ics and Management of TB a Post Direct Selection Direct 1,600.00 0.00 2019-03-18 2019-03-23 2019-04-27 2019-10-24 15189 and ISO15190 Standa ementation nd Occupational Lung Disea rds (for Medical Laboratories ses for NTRL, NRL, Motebang and Mafeteng) SATBHSS/MOH/G-018/2019 / Regional Capacity for Diseas Procure a server for data stor e Surveillance, and Diagnost Request for Quota Single Stage - One E age IDA / 58220 ics and Management of TB a Post Open - National 5,328.16 0.00 Canceled 2019-05-25 2019-07-20 2020-01-16 tions nvelope Install OHASSIS Mining Regul nd Occupational Lung Disea ation compliance monitoring ses and Mine Health surveillance Regional Capacity for Diseas SATBHSS/MOH/G-0019/2019 e Surveillance, and Diagnost Request for Quota Single Stage - One E Pending Impl / Procure Trolley and Water D IDA / 58220 Post Open - National 4,017.50 0.00 2019-03-30 2019-05-25 2019-11-21 ics and Management of TB a tions nvelope ementation istiller for NTRL nd Occupational Lung Disea ses Regional Capacity for Diseas SATBHSS/MOH/G-020/2019 / e Surveillance, and Diagnost Pending Impl Procure Xpert Checks for NTR IDA / 58220 Post Direct Selection Direct 27,000.00 0.00 2019-04-01 2019-04-06 2019-05-11 2019-11-07 ics and Management of TB a ementation L nd Occupational Lung Disea ses Page 3 Regional Capacity for Diseas SATBHSS/MOH/G-021/2019 / e Surveillance, and Diagnost Request for Quota Single Stage - One E IDA / 58220 Post Open - National 37,000.00 0.00 Canceled 2019-03-23 2019-05-18 2019-11-14 Procure Battery Power packs ics and Management of TB a tions nvelope nd Occupational Lung Disea ses Regional Capacity for Diseas SATBHSS/MOH/G-019/2019 / e Surveillance, and Diagnost Request for Quota Single Stage - One E Pending Impl Procurement of Double wate IDA / 58220 Post Open - National 2,205.26 0.00 2019-04-27 2019-06-22 2019-08-21 ics and Management of TB a tions nvelope ementation r Distiller for NTRL nd Occupational Lung Disea ses SATBHSS/MOH/G-022/2019 / Regional Capacity for Diseas Procurement supply, installat e Surveillance, and Diagnost Pending Impl ion and commissioning of Th IDA / 58220 ics and Management of TB a Post Direct Selection Direct 45,000.00 0.00 2019-04-01 2019-04-06 2019-05-11 2019-10-08 ementation ermal Scanner at Mosheosho nd Occupational Lung Disea e I international Airport. ses SATBHSS/MOH/G-006/2019 / Procure (nutritional) Ready t Innovative Prevention, Detec Open - Internationa Single Stage - One E IDA / 58220 Post Request for Bids 268,807.80 238,611.61 Signed 2019-05-06 2019-06-16 2019-05-11 2019-06-22 2019-08-15 2019-07-22 2019-10-10 2019-08-26 2019-10-15 2020-02-22 o Use Therapeutic feeding (R tion and Treatment of TB l nvelope UTF) commodities for TB pati ents SATBHSS/MOH/G-023/2019 / Regional Capacity for Diseas Procure Printed revised Mine e Surveillance, and Diagnost Request for Quota Single Stage - One E IDA / 58220 Post Open - National 5,819.77 0.00 Canceled 2019-04-13 2019-06-08 2019-09-06 Health and safety standards ics and Management of TB a tions nvelope and guidelines nd Occupational Lung Disea ses SATBHSS/MOH/G-024/2019 / Regional Capacity for Diseas Procurement and supply of t e Surveillance, and Diagnost Request for Quota Open - Internationa Single Stage - One E Pending Impl he following LIS Computer, LI IDA / 58220 ics and Management of TB a Post 4,192.00 0.00 2019-05-11 2019-07-06 2019-12-03 tions l nvelope ementation S Net work Points, Label Print nd Occupational Lung Disea er and Printer for results for ses NTRL Regional Capacity for Diseas SATBHSS/MOH/G-025/2019 / e Surveillance, and Diagnost Request for Quota Single Stage - One E Procurement of Laboratory C IDA / 58220 Post Open - National 1,332.40 5,116.70 Completed 2019-04-20 2019-06-15 2021-03-17 2019-09-13 2021-04-17 ics and Management of TB a tions nvelope hairs and Trolley nd Occupational Lung Disea ses SATBHSS/MOH/G-003/2019 / Procurement of Contact traci Innovative Prevention, Detec Request for Quota Single Stage - One E ng slip Booklet(A5 size with h IDA / 58220 Post Open - National 4,163.07 0.00 Canceled 2019-04-06 2019-06-01 2019-07-31 tion and Treatment of TB tions nvelope ard covers, 100 per booklet , perforated and duplicate info rmation) 500 SATBHSS/MOH/G-002/2019 / Procure opportunistic infectio ns Drugs and medical consu Innovative Prevention, Detec Request for Quota Single Stage - One E Pending Impl IDA / 58220 Post Open - National 17,185.66 0.00 2019-04-06 2019-06-01 2019-11-28 mables for TEBA (Various OI tion and Treatment of TB tions nvelope ementation Drugs, consumables, waste management and infection c ontrol consumables, etc) SATBHSS/MOH/G-004/2019 / Procurement of Printing servi Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 58230 Post Open - National 4,364.83 0.00 Canceled 2019-04-13 2019-06-08 2019-08-07 ce and supply of the data im tion and Treatment of TB tions nvelope provement manual (300 man uals) SATBHSS/MOH/G-017/2019 / Regional Capacity for Diseas Procure Personal protective E e Surveillance, and Diagnost Request for Quota Single Stage - One E IDA / 58220 Post Open - National 1,121.54 0.00 Canceled 2019-04-13 2019-06-08 2019-08-07 quipment (PPE) for MOH and ics and Management of TB a tions nvelope DOE personnel nd Occupational Lung Disea ses SATBHSS/MOH/G-007/2019 / Procure and supply revised t Innovative Prevention, Detec Request for Quota Single Stage - One E ools for recording use of the IDA / 58220 Post Open - National 6,926.61 0.00 Canceled 2019-04-20 2019-06-15 2019-12-12 tion and Treatment of TB tions nvelope RUTF for TB patients(300 regi sters and 300 laminated SOP s/Job aids) SATBHSS/MOH/G-010/2019 / Procure and supply Health C are worker wellness center st Innovative Prevention, Detec Request for Quota Single Stage - One E Under Imple IDA / 58220 Post Open - National 66,700.75 0.00 2019-04-13 2019-06-08 2019-08-07 arter packs (Basic equipment tion and Treatment of TB tions nvelope mentation and office furniture for 10 ho spital for phase 1 of the well ness model) SATBHSS/MOH/G-015/2019 / Regional Capacity for Diseas Procure TB culture/ 1st line D e Surveillance, and Diagnost Single Stage - One E Pending Impl IDA / 58220 Post Direct Selection Direct 40,210.98 0.00 2019-04-08 2019-04-23 2019-05-05 2019-07-04 ST reagents and consumable ics and Management of TB a nvelope ementation s (BBL MGIT 7ml tubes,MGIT nd Occupational Lung Disea Supplement Panda) ses SATBHSS/MOH/G-001/2019 / Procurement of Gene-Xpert c Innovative Prevention, Detec Pending Impl IDA / 58220 Post Direct Selection Direct 368,090.61 0.00 2019-04-15 2019-04-20 2019-05-25 2019-11-21 artridges for intensified case tion and Treatment of TB ementation finding among miners (30,00 0.00 units) Regional Capacity for Diseas SATBHSS/MOH/G-026/2019 / e Surveillance, and Diagnost Request for Quota Single Stage - One E Pending Impl Printing and Binding of NTRL IDA / 58220 Post Open - National 1,400.00 0.00 2019-10-16 2019-12-11 2020-06-08 ics and Management of TB a tions nvelope ementation Lab Standards 70 copies nd Occupational Lung Disea ses SATBHSS/MOH/G-027/2019 / Printing and Supply of the Fol Innovative Prevention, Detec Request for Quota Single Stage - One E lowing: Ward Stickers 700 IDA / 58220 Post Open - National 800.00 0.00 Canceled 2019-10-16 2019-11-03 2019-11-28 tion and Treatment of TB tions nvelope Printing and binding with Har d Cover A3 Tally Sheet with 2 00 pages SATBHSS/MOH/G-028/2019 / Procurement of Office equip ment ( Mini Fridge for sputu m collection, Coughing Booth Innovative Prevention, Detec Request for Quota Single Stage - One E Pending Impl IDA / 58220 Post Open - National 1,800.00 0.00 2019-11-13 2019-11-27 2019-12-27 Tent) and stationery for Con tion and Treatment of TB tions nvelope ementation tinuous Quality Improvement (CQI) for 3 Hospitals ( Bots'a belo Health Canter St Joseph s and Quthing Hospital) . SATBHSS/MOH/G-029/2019 / Procurement of Project Coord Regional Learning and Innov Request for Quota Single Stage - One E Pending Impl inator Laptop with Microsoft IDA / 58220 ation, and Project Managem Post Open - National 1,400.00 0.00 2019-12-07 2020-02-01 2020-03-02 tions nvelope ementation office to replace crushed lapt ent op and recovery of data from crushed laptop. SATBHSS/MOH/G-030/2019 / Purchase of Office Furniture ( Regional Learning and Innov U Shaped Office Desk, Ergon Request for Quota Single Stage - One E IDA / 58220 ation, and Project Managem Post Open - National 3,400.00 0.00 Canceled 2019-12-13 2020-02-07 2020-03-08 omic Chair and Glass Filling tions nvelope ent Cabinet) for reallocation Proj ect Coordinator to the new of fice. Page 4 LS-MOH-165092-GO-DIR / Pr Regional Capacity for Diseas ocure, supply and install Med e Surveillance, and Diagnost IDA / 58220 Post Direct Selection Direct 32,000.00 0.00 Canceled 2020-03-29 2020-04-03 2020-05-08 2020-11-04 ical Equipment for ICU ( Venti ics and Management of TB a lator) nd Occupational Lung Disea ses LS-MOH-165094-GO-RFQ / Pr ocurement and supply of Me Regional Capacity for Diseas dical Consumables ( Syringes e Surveillance, and Diagnost Request for Quota Open - Internationa Single Stage - One E , Canulae, Thermometers, BP IDA / 58220 ics and Management of TB a Post 65,000.00 0.00 Canceled 2020-04-05 2020-05-31 2020-11-27 tions l nvelope Machines, ) and Waste Mana nd Occupational Lung Disea gement Consumables (Bins, ses waste plastics, and Sharps C ontainers) LS-MOH-165096-GO-RFQ / Pr Regional Capacity for Diseas ocurement of Medical Equip e Surveillance, and Diagnost Request for Quota Open - Internationa Single Stage - One E IDA / 58220 Post 1,640.00 0.00 Canceled 2020-04-05 2020-05-31 2020-11-27 ment( Examination couch an ics and Management of TB a tions l nvelope d Screens, Drips Stands) nd Occupational Lung Disea ses Regional Capacity for Diseas LS-MOH-165099-GO-DIR / Pr e Surveillance, and Diagnost ocure and supply rapid test k IDA / 58220 Post Direct Selection Direct 50,000.00 0.00 Canceled 2020-03-31 2020-04-05 2020-05-10 2020-11-06 ics and Management of TB a its for COVID -19 nd Occupational Lung Disea ses LS-MOH-165101-GO-RFQ / Pr Regional Capacity for Diseas ocurement and supply of Lab e Surveillance, and Diagnost Request for Quota IDA / 58220 Post 69,000.00 0.00 Canceled 2020-03-29 2020-03-29 2020-03-29 oratory Reagents ( Swabs,tra ics and Management of TB a tions nsport media) nd Occupational Lung Disea ses LS-MOH-168700-GO-UN / Pro Regional Capacity for Diseas curement for Medical Supplie e Surveillance, and Diagnost UN Agencies (Dire Pending Impl s and Personal Protective Eq IDA / 58220 ics and Management of TB a Post Direct 200,000.00 0.00 2020-04-19 2020-04-24 2020-05-29 2020-11-25 ct) ementation uipment to be used by Medic nd Occupational Lung Disea al Staff During COVID 19 Pan ses demic LS-MOH-231904-GO-RFQ-SA TBHSS / Procurement and su pply of Printed SOPs, Job Aids Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 66950 Post Open - National 70,200.00 0.00 Canceled 2021-10-02 2021-11-27 2022-01-06 for TB management includin tion and Treatment of TB tions nvelope g, clinical management , inte grated TB/HIV Screening and Mortality audits LS-MOH-231911-GO-RFB-SA TBHSS / Procure, supply and i nstall Mobile digital X-rays at Innovative Prevention, Detec Open - Internationa Single Stage - One E IDA / 66950 Post Request for Bids 720,000.00 0.00 Canceled 2021-05-09 2021-05-12 2021-06-24 2021-07-24 2021-08-28 2022-02-24 • Lot 1 Three hospitals with tion and Treatment of TB l nvelope preventative maintenance • Lot 2 One Back Pack Mo bile digital X-ray with prevent ative maintenance LS-MOH-231913-GO-RFQ-SA TBHSS / Procure and supply 90 tablets and tablets punch Innovative Prevention, Detec Request for Quota Single Stage - One E for screening points at hospit IDA / 66950 Post Open - National 69,600.00 0.00 Canceled 2021-05-05 2021-06-23 2021-08-22 tion and Treatment of TB tions nvelope als and for the health centres and supply of 76 electronic gadgets for EBS data collecti on: (Tablets and Pouches) LS-MOH-231917-GO-RFB-SA TBHSS / Procure and supply New TB Preventative Therap Innovative Prevention, Detec Open - Internationa Single Stage - One E IDA / 66950 Post Request for Bids 177,000.00 0.00 Canceled 2021-05-02 2021-05-07 2021-06-18 2021-07-18 2021-08-22 2021-11-20 y regimen (3HP) Rifapentine tion and Treatment of TB l nvelope and Isoniazid. • 3HP Drugs 8350 units Ch eck with PC LS-MOH-231944-GO-RFB-SA TBHSS / Procure and supply ( supplementary) Ready to Us e Therapeutic feeding (RUTF) commodities for TB patients, Innovative Prevention, Detec Open - Internationa Single Stage - One E IDA / 66950 Post Request for Bids 314,500.00 0.00 Canceled 2021-05-09 2021-05-14 2021-06-25 2021-07-25 2021-08-29 2021-11-27 • 92g Sachets by150 per c tion and Treatment of TB l nvelope arton by 2,100 quantity for L ot 1. Delivery in September 2 021. • 92g Sachets by150 per c arton by 2,100 quantity for L ot 2, Del LS-MOH-231954-GO-RFB-SA TBHSS / Procurement, supply and installation of Furnishers Innovative Prevention, Detec Single Stage - One E and Equipment for Maseru C IDA / 66950 Post Request for Bids Open - National 202,750.00 0.00 Canceled 2021-11-01 2021-11-06 2021-12-18 2022-01-17 2022-02-21 2022-08-20 tion and Treatment of TB nvelope entral Correctional facility. • Lot 1 Equipment • Lot 2 Furnishers LS-MOH-231960-GO-RFQ-SA TBHSS / Procure and supply basic medical equipment incl Innovative Prevention, Detec Request for Quota Single Stage - One E Pending Impl IDA / 66950 Post Open - National 55,000.00 0.00 2021-11-05 2021-12-31 2022-03-01 uding spirometers, plinths, C tion and Treatment of TB tions nvelope ementation omputer (IMS) including spiro meters, plinths, Computer (I MS) for wellness Centres LS-MOH-231998-GO-RFQ-SA Regional Capacity for Diseas TBHSS / Procure and supply s e Surveillance, and Diagnost Request for Quota Single Stage - One E Pending Impl IDA / 66950 Post Limited 80,000.00 0.00 2021-05-14 2021-06-23 2021-08-22 econd line Drug Susceptibilit ics and Management of TB a tions nvelope ementation y Testing reagents nd Occupational Lung Disea ses LS-MOH-231999-GO-RFQ-SA Regional Capacity for Diseas TBHSS / Procure and supply P e Surveillance, and Diagnost Request for Quota Single Stage - One E Pending Impl IDA / 66950 Post Open - National 64,600.00 0.00 2021-10-01 2021-11-26 2022-01-05 rinted guiding documents for ics and Management of TB a tions nvelope ementation artisanal mining (Guidelines, nd Occupational Lung Disea SOPS) ses LS-MOH-232008-GO-RFB-SA TBHSS / Procure and supply Innovative Prevention, Detec Single Stage - One E below structures separated i IDA / 66950 Post Request for Bids Open - National 174,332.00 0.00 Canceled 2021-06-06 2021-06-11 2021-07-23 2021-08-22 2021-09-26 2021-12-25 tion and Treatment of TB nvelope n lots • 18 Solid screening struct ures for the hospitals LS-MOH-242332-GO-RFQ-AF- Regional Capacity for Diseas SATBHSS / Procurement and e Surveillance, and Diagnost Request for Quota Single Stage - One E IDA / 66950 Post Open - National 6,300.00 7,073.44 Completed 2021-08-11 2021-08-29 2021-09-02 2021-10-10 2021-09-30 supply of 4 Desktops for Mini ics and Management of TB a tions nvelope stry of Labour and Ministry of nd Occupational Lung Disea Mining. ses LS-MOH-246895-GO-RFQ-SA TBHSS-AF / Procurement of M Innovative Prevention, Detec Request for Quota Single Stage - One E Under Imple IDA / 66950 Post Open - National 100,000.00 0.00 2021-12-10 2022-01-21 2022-04-21 edical Equipment for Maseru tion and Treatment of TB tions nvelope mentation Central Correctional Facility Page 5 LS-MOH-247062-GO-RFB-SA Regional Capacity for Diseas TBHSS-P / Procure and suppl e Surveillance, and Diagnost Open - Internationa Single Stage - One E y Three Vehicles Double Cab IDA / 58220 ics and Management of TB a Post Request for Bids 160,000.00 15,653,329.00 Completed 2021-09-05 2021-09-28 2021-09-10 2021-10-22 2021-10-26 2021-11-21 2021-10-29 2021-12-26 2021-11-10 2022-02-24 2022-03-24 l nvelope s 4 by 4 for Community Mobil nd Occupational Lung Disea ization, TB awareness and inf ses ection control LS-MOH-247063-GO-RFQ-SA Regional Capacity for Diseas TBHSS-P / Procurement and s e Surveillance, and Diagnost Request for Quota Open - Internationa Single Stage - One E IDA / 58220 Post 100,000.00 0.00 Signed 2021-09-10 2021-10-15 2021-12-14 upply of Back Pack Digital X r ics and Management of TB a tions l nvelope ay for COE nd Occupational Lung Disea ses LS-MOH-247064-GO-RFQ-SA Regional Capacity for Diseas TBHSS-P / Procure and suppl e Surveillance, and Diagnost Request for Quota Single Stage - One E Pending Impl IDA / 58220 Post Open - National 1,400.00 0.00 2021-09-10 2021-10-15 2021-12-14 y tablets and tablet pouches ics and Management of TB a tions nvelope ementation for Sputum referral and linka nd Occupational Lung Disea ges to care ses LS-MOH-247068-GO-DIR-SAT Regional Capacity for Diseas BHSS-P / Procurement and su e Surveillance, and Diagnost Under Imple IDA / 58220 Post Direct Selection Direct 450,000.00 0.00 2021-09-05 2021-09-22 2021-09-10 2022-04-04 2021-10-15 2021-12-14 pply of Gene Xpert Cartridge ics and Management of TB a mentation s for COE nd Occupational Lung Disea ses Regional Capacity for Diseas LS-MOH-247074-GO-RFQ-SA e Surveillance, and Diagnost Request for Quota Single Stage - One E TBHSS-P / Procurement and s IDA / 58220 Post Open - National 100,000.00 19,929.90 Completed 2021-09-10 2021-10-15 2021-11-06 2021-12-14 2021-12-18 ics and Management of TB a tions nvelope upply of Sputum Jars for COE nd Occupational Lung Disea ses LS-MOH-247075-GO-RFQ-SA Regional Capacity for Diseas TBHSS-P / Procurement and s e Surveillance, and Diagnost Request for Quota Single Stage - One E Pending Impl upply of Camping Equipment IDA / 58220 ics and Management of TB a Post Open - National 15,000.00 0.00 2021-09-10 2021-10-29 2021-12-28 tions nvelope ementation for COE ( Screening Tents ,Fo nd Occupational Lung Disea ldable chairs and Tables ) ses LS-MOH-247077-GO-RFQ-SA Regional Capacity for Diseas TBHSS-AF / Procurement and e Surveillance, and Diagnost Request for Quota Single Stage - One E Pending Impl IDA / 66950 Post Open - National 98,000.00 0.00 2021-10-01 2021-11-19 2022-01-18 supply of Mining Inspection E ics and Management of TB a tions nvelope ementation quipment nd Occupational Lung Disea ses LS-MOH-247078-GO-RFQ-SA Regional Capacity for Diseas TBHSS-P / Procurement and s e Surveillance, and Diagnost upply of Lesotho National Tu Request for Quota Single Stage - One E Pending Impl IDA / 58220 ics and Management of TB a Post Open - National 2,000.00 0.00 2021-08-20 2021-10-01 2021-10-31 berculosis Reference Laborat tions nvelope ementation nd Occupational Lung Disea ory Handbook ( 216 copies) ses Prefect Binding on Glossy co ver LS-MOH-258174-GO-RFQ-SA Regional Learning and Innov Request for Quota Single Stage - One E TBHSS-P / Procurement and S IDA / 58220 ation, and Project Managem Post Open - National 5,000.00 4,529.06 Completed 2021-10-19 2021-12-14 2021-11-06 2022-06-12 2022-03-05 tions nvelope upply of 4 in 1 Printer for PA ent U LS-MOH-258166-GO-RFQ-SA Regional Learning and Innov TBHSS-P / Procurement and S Request for Quota Single Stage - One E IDA / 58220 ation, and Project Managem Post Open - National 4,000.00 3,756.74 Completed 2021-11-12 2022-01-07 2021-11-05 2022-07-06 2021-11-20 upply of Laptops and Laptop tions nvelope ent bags for PIU Staff LS-MOH-260176-GO-RFQ-SA TBHSS- P / supply, delivery a Regional Learning and Innov Request for Quota nd installation of Zippel Linea IDA / 58230 ation, and Project Managem Post 9,200.00 7,900.27 Completed 2021-12-03 2021-12-19 2021-11-06 2022-02-17 2022-03-03 tions Storage for Ministry of Health ent Project Accounting Unit to M OH-HQ LS-MOH-247066-GO-RFQ-SA Regional Capacity for Diseas TBHSS-P / Procurement and P e Surveillance, and Diagnost Request for Quota Single Stage - One E IDA / 58220 Post Open - National 15,000.00 0.00 Canceled 2022-02-18 2022-03-25 2022-05-24 rinting of IEC Material for CO ics and Management of TB a tions nvelope E nd Occupational Lung Disea ses LS-MOH-231910-GO-RFQ-SA TBHSS / Procure and supply P Innovative Prevention, Detec Request for Quota Single Stage - One E Pending Impl rinted IDA / 66950 Post Open - National 11,590.00 0.00 2022-02-18 2022-04-08 2022-05-28 tion and Treatment of TB tions nvelope ementation • Plumpy soy register by 2 50 • Plumpy soy dispensing S OP by 250 LS-MOH-247073-GO-RFQ-SA Regional Capacity for Diseas TBHSS-P / Procurement and s e Surveillance, and Diagnost Request for Quota Single Stage - One E IDA / 58230 Post Open - National 10,000.00 4,934.28 Completed 2021-12-31 2022-02-04 2021-10-16 2022-04-05 2021-12-11 upply of Basic Medical Equip ics and Management of TB a tions nvelope ment for COE Digital X Ray Tr nd Occupational Lung Disea ucks ses LS-MOH-246871-GO-RFB-SA TBHSS-AF / Supply, delivery and commissioning of Digital X Ray with preventative main Innovative Prevention, Detec Open - Internationa Single Stage - One E IDA / 66950 Post Request for Bids 720,000.00 0.00 Canceled 2022-02-27 2022-03-04 2022-04-15 2022-05-15 2022-06-19 2022-12-16 tenance contract at Three Ho tion and Treatment of TB l nvelope spitals Lot 1 One back pack Mobile digital X Ray with preventative main tenance contract Lot 2 LS-MOH-246876-GO-RFQ-SA TBHSS-AF / Procure and supp Innovative Prevention, Detec Request for Quota Single Stage - One E ly 90 tablets and tablets pou IDA / 66950 Post Open - National 40,000.00 33,099.90 Completed 2021-12-17 2022-01-28 2021-08-25 2022-03-29 2021-09-22 tion and Treatment of TB tions nvelope ch for screening points at ho spitals and health centers LS-MOH-242335-GO-RFQ-AF- SATBHSS / Procure and suppl y (supplementary) Ready to Use Therapeutic feeding (RU Innovative Prevention, Detec Request for Quota Open - Internationa Single Stage - One E IDA / 66950 Post 95,000.00 62,852.98 Signed 2021-11-26 2021-12-27 2021-09-16 2022-03-27 TF) commodities for TB patie tion and Treatment of TB tions l nvelope nts, • 92g Sachets by150 per c arton by 1,200 quantity for L ot 1. Delivery in November 2 021. LS-MOH-246894-GO-RFQ-SA TBHSS-AF / supply and install Innovative Prevention, Detec Request for Quota Single Stage - One E ation of furnishers at Maseru IDA / 66950 Post Open - National 98,000.00 52,043.77 Signed 2022-02-11 2022-03-25 2022-04-28 2022-05-24 tion and Treatment of TB tions nvelope Correctional Facility after ren ovations are complete LS-MOH-247018-GO-RFQ-SA TBHSS-AF / Procurement and Innovative Prevention, Detec Request for Quota Single Stage - One E Pending Impl IDA / 66950 Post Open - National 55,000.00 0.00 2022-02-18 2022-04-15 2022-06-14 supply of Basic Medical Equip tion and Treatment of TB tions nvelope ementation ment for 8 Wellness Centers. LS-MOH-247021-GO-RFQ-SA TBHSS-AF / Procure and supp Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 66950 Post Open - National 33,000.00 0.00 Canceled 2022-03-18 2022-04-22 2022-06-21 ly Basic Furnisher for Maluti a tion and Treatment of TB tions nvelope nd Nts'ekhe OPD Waiting are a. Page 6 LS-MOH-247076-GO-RFQ-SA Regional Capacity for Diseas TBHSS-AF / Procurement and e Surveillance, and Diagnost Request for Quota Single Stage - One E Pending Impl IDA / 66950 Post Open - National 80,000.00 0.00 2022-02-11 2022-03-18 2022-05-17 supply of second line Drugs S ics and Management of TB a tions nvelope ementation usceptibility Testing reagents nd Occupational Lung Disea ses LS-MOH-246870-GO-RFQ-SA TBHSS-AF / Procurement and supply of printed SOPs, Job Ai Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 66950 Post Open - National 71,000.00 0.00 Canceled 2022-02-06 2022-03-27 2022-06-25 ds or TB Management includi tion and Treatment of TB tions nvelope ng, clinical Management inte grated TB/HIV screening and Mortality audits LS-MOH-232000-GO-RFQ-SA Regional Capacity for Diseas TBHSS / Procurement and su e Surveillance, and Diagnost Request for Quota Single Stage - One E IDA / 66950 Post Open - National 98,130.00 0.00 Canceled 2022-02-11 2022-04-08 2022-06-07 pply of equipment for inspect ics and Management of TB a tions nvelope ions. nd Occupational Lung Disea ses LS-MOH-232006-GO-RFB-SA Regional Capacity for Diseas TBHSS / Procurement and Su e Surveillance, and Diagnost pply of Open - Internationa Single Stage - One E IDA / 66950 ics and Management of TB a Post Request for Bids 205,100.00 0.00 Canceled 2021-10-11 2021-10-16 2021-11-27 2021-12-27 2022-01-31 2022-05-01 • Lot 1 Hepatitis Test and V l nvelope nd Occupational Lung Disea accines by 2000 units ses For health Care Workers COV ID Wellness LS-MOH-232051-GO-RFQ-SA TBHSS / Procure and supply below structures separated i Innovative Prevention, Detec Request for Quota Single Stage - One E Pending Impl n lots IDA / 66950 Post Open - National 48,800.00 0.00 2022-01-21 2022-03-18 2022-04-27 tion and Treatment of TB tions nvelope ementation • 195 Screening gazebos fo r health centers • 216 Cough gazebos for h ealth facilities LS-MOH-231997-GO-RFQ-SA TBHSS / Procure and supply Innovative Prevention, Detec Request for Quota Single Stage - One E Pending Impl Basic Furnishing for prefabric IDA / 66950 Post Open - National 32,800.00 0.00 2022-03-25 2022-05-06 2022-07-05 tion and Treatment of TB tions nvelope ementation ated Structures and shades f or Maluti and Nts’ekhe for OP D waiting. LS-MOH-247067-GO-DIR-SAT Regional Capacity for Diseas BHSS-P / Procurement and su e Surveillance, and Diagnost IDA / 58220 Post Direct Selection Direct 140,000.00 0.00 Canceled 2022-02-01 2022-02-06 2022-02-20 2022-04-21 pply of CAD 4 TB Software fo ics and Management of TB a r 4 Digital X rays with Images nd Occupational Lung Disea ses LS-MOH-232067-GO-DIR-SAT BHSS / Procure, supply and in stall CAD4 software to digital Innovative Prevention, Detec Pending Impl IDA / 66950 Post Direct Selection Direct 462,000.00 0.00 2022-02-01 2022-02-06 2022-03-13 2022-06-11 X-rays Hardware & Setup to tion and Treatment of TB ementation 18 X-rays. License of CAD4 software to digital X-rays 60000 units LS-MOH-274965-GO-RFQ-SA Regional Learning and Innov TBHSS-2021 / Procurement o Request for Quota Single Stage - One E IDA / 58220 ation, and Project Managem Post Open - National 24,000.00 20,280.28 Completed 2022-02-11 2022-04-08 2022-02-25 2022-05-08 2022-03-24 f Eleven Laptops and Project tions nvelope ent or for NTLP Program officers LS-MOH-288844-GO-RFQ-SA TBHSS-AF / Procurement and Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 66950 Post Open - National 20,000.00 26,671.34 Signed 2022-04-29 2022-06-01 2022-08-10 2022-07-31 supply of Sputum induction e tion and Treatment of TB tions nvelope quipment and accessories LS-MOH-300153-GO-RFQ-AF- 2022 / Procurement and sup Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 66950 Post Open - National 10,000.00 9,649.12 Signed 2022-07-01 2022-08-26 2022-07-08 2022-09-25 ply of 6 Laptops for OSH Offic tion and Treatment of TB tions nvelope ers for Maseru and Mafeteng LS-MOH-288845-GO-RFQ-SA TBHSS-AF / Procurement and Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 66950 Post Open - National 15,000.00 0.00 Signed 2022-07-01 2022-07-25 2022-08-15 supply of branded T Shirts, H tion and Treatment of TB tions nvelope ats, IDs and Backpack for TB Mortality Audit Study LS-MOH-324646-GO-RFQ-SA TBHSS-AF-2022 / Procureme Innovative Prevention, Detec Request for Quota Single Stage - One E Pending Impl nt of desktop computers for IDA / 66950 Post Open - National 3,500.00 0.00 2023-01-20 2023-03-17 2023-04-16 tion and Treatment of TB tions nvelope ementation Occupational Health Clinics a t Mafeteng and Maseru LS-MOH-329645-GO-RFB-SA TBHSSAF-2023 / Procuremen t of Printing and distribution Innovative Prevention, Detec Single Stage - One E Pending Impl of revised Standard Operatin IDA / 66950 Post Request for Bids Open - National 340,000.00 0.00 2023-02-26 2023-03-03 2023-04-14 2023-05-14 2023-06-18 2023-08-17 tion and Treatment of TB nvelope ementation g Procedures (SOPs), Algorith ms and other job AIDs for gui dance along the whole TB ca scade; LS-MOH-329651-GO-RFQ-SA TBHSSAF-2023 / Procuremen Regional Capacity for Diseas t for Printing of Artisanal Mini e Surveillance, and Diagnost Request for Quota Single Stage - One E Pending Impl ng guidelines, standards and IDA / 66950 ics and Management of TB a Post Open - National 70,000.00 0.00 2023-03-05 2023-04-30 2023-06-29 tions nvelope ementation SOPs (500 copies each) nd Occupational Lung Disea And Mines and Health safety ses guideline and SOPs LS-MOH-329656-GO-RFB-SA Regional Capacity for Diseas TBHSSAF-2023 / Procuremen e Surveillance, and Diagnost t of sputum jars and other c Single Stage - One E Pending Impl IDA / 66950 ics and Management of TB a Post Request for Bids Open - National 1,032,000.00 0.00 2023-01-29 2023-02-03 2023-03-17 2023-04-16 2023-05-21 2023-11-17 ommodities for COE Lot 1 an nvelope ementation nd Occupational Lung Disea d equipment and reagents f ses or outbreak investigations - L ab (NTRL and Agric) Lot 2 LS-MOH-329659-GO-RFQ-SA Regional Capacity for Diseas TBHSSAF-2023 / Procuremen e Surveillance, and Diagnost Request for Quota Single Stage - One E Pending Impl t of EQA preparation Materia IDA / 66950 ics and Management of TB a Post Open - National 71,001.90 0.00 2023-01-13 2023-03-10 2023-04-24 tions nvelope ementation l- GeneXpert and Smear Micr nd Occupational Lung Disea oscopy EQA and Transportati ses on LS-MOH-329663-GO-RFB-SA Regional Capacity for Diseas TBHSSAF-2022 / Procure basi e Surveillance, and Diagnost c medical equipment includin Single Stage - One E Pending Impl IDA / 66950 ics and Management of TB a Post Request for Bids Open - National 275,187.00 0.00 2023-02-12 2023-02-17 2023-03-31 2023-04-30 2023-06-04 2023-06-10 g spirometers, plinths, Comp nvelope ementation nd Occupational Lung Disea uter (IMS) for Wellness progr ses am including spirometers, pli nths, Hepatitis test and vacci nes Page 7 LS-MOH-329684-GO-RFQ-SA TBHSSAF-2023 / Procure equi pment for inspections for min e inspectors inclusive of train Innovative Prevention, Detec Request for Quota Single Stage - One E Pending Impl IDA / 66950 Post Open - National 55,000.00 0.00 2023-03-10 2023-05-05 2023-07-04 ing. tion and Treatment of TB tions nvelope ementation Radiation Dosimeters (2) Decibel meters (6) Personal radiation dosimeter s (10) Heat Stress Monitors (2), LS-MOH-329685-GO-RFQ-SA TBHSSAF-2023 / Procure of P Innovative Prevention, Detec Request for Quota Single Stage - One E Pending Impl IDA / 66950 Post Open - National 15,000.00 0.00 2023-01-20 2023-03-17 2023-05-16 PE (Hard hats 26, Shoe 26 pa tion and Treatment of TB tions nvelope ementation irs, Reflector jackets 26) for Mining Inspectors LS-MOH-329686-GO-RFB-SA TBHSSAF-2023 / Procure (sup Innovative Prevention, Detec Single Stage - One E Pending Impl plementary) Ready to Use Th IDA / 66950 Post Request for Bids Open - National 315,315.00 0.00 2023-03-05 2023-03-10 2023-04-21 2023-05-21 2023-06-25 2023-12-22 tion and Treatment of TB nvelope ementation erapeutic feeding (RUTF) co mmodities for TB patients x 6 43500 units LS-MOH-329689-GO-RFQ-SA TBHSSAF-2023 / Procuremen Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 66950 Post Open - National 90,000.00 0.00 Canceled 2023-02-04 2023-04-01 2023-09-28 t of Power Backups for Gene tion and Treatment of TB tions nvelope Xpert machines and installati on LS-MOH-329693-GO-RFB-SA TBHSSAF-2023 / Procuremen Innovative Prevention, Detec Single Stage - One E t and installation of air condit IDA / 66950 Post Request for Bids Open - National 116,766.00 0.00 Canceled 2023-01-08 2023-01-13 2023-02-24 2023-03-26 2023-04-30 2023-10-27 tion and Treatment of TB nvelope ioner with preventative main tenance of 12 months LS-MOH-329696-GO-RFQ-SA Regional Capacity for Diseas TBHSSAF-2023 / Procuremen e Surveillance, and Diagnost t and installation of following Request for Quota Single Stage - One E Pending Impl IDA / 66950 ics and Management of TB a Post Open - National 100,000.00 0.00 2023-04-07 2023-06-02 2023-11-29 equipment to Upgrade situati tions nvelope ementation nd Occupational Lung Disea on (EOC) Room (Room-Scree ses n, camera, Computer & Airco n) LS-MOH-329704-GO-RFQ-SA Regional Capacity for Diseas TBHSSAF-2023 / Procuremen e Surveillance, and Diagnost Request for Quota Single Stage - One E Pending Impl t of computers (Desktops an IDA / 66950 ics and Management of TB a Post Open - National 80,000.00 0.00 2023-01-27 2023-03-24 2023-04-23 tions nvelope ementation d Laptops) and office equipm nd Occupational Lung Disea ent for OHASIS, NTRL and We ses llness Centre LS-MOH-329727-GO-RFQ-SA Regional Learning and Innov TBHSSAF-2023 / Procuremen Request for Quota Single Stage - One E Pending Impl IDA / 66950 ation, and Project Managem Post Open - National 126,666.00 0.00 2023-02-03 2023-03-31 2023-06-29 t and installation of Medical tions nvelope ementation ent Waste Incinerator with enclos ure LS-MOH-329683-GO-DIR-SAT BHSSAF-2023 / Procurement of AI software and (4) digital X-rays - Hardware and softwa re x 25 Innovative Prevention, Detec Direct - Internation Pending Impl IDA / 66950 Post Direct Selection 1,112,945.00 0.00 2023-01-29 2023-02-03 2023-03-10 2023-06-08 AI software to digital X-rays – tion and Treatment of TB al ementation Setup x 25 AI software to digital X-rays – license x 25 X-ray storage back-up (cloud )1 Connectivity software 2 LS-MOH-329655-GO-DIR-SAT Regional Learning and Innov Pending Impl BHSSAF-2023 / Procurement IDA / 66950 ation, and Project Managem Post Direct Selection Direct - National 680,000.00 0.00 2023-01-15 2023-01-20 2023-02-24 2023-08-23 ementation of GeneXpert cartridge (inc. ent COE) LS-MOH-329652-GO-DIR-SAT BHSSAF-2023 / Procurement of 10 colour coded gene Xper Innovative Prevention, Detec Direct - Internation Pending Impl IDA / 66950 Post Direct Selection 26,000.00 0.00 2023-01-31 2023-02-05 2023-03-12 2023-06-10 t machine for diagnosis of XD tion and Treatment of TB al ementation R-TB 4 module machine with 3 years warranty with 3 year s warranty (Xpert NTB XDR) LS-MOH-329722-GO-RFB-SA Regional Capacity for Diseas TBHSSAF-2023 / Procure and e Surveillance, and Diagnost provide appropriate prefabric Single Stage - One E IDA / 66950 ics and Management of TB a Post Request for Bids Open - National 480,468.00 0.00 Canceled 2023-02-19 2023-02-24 2023-04-07 2023-05-07 2023-06-11 2023-08-20 ated infrastructure or identify nvelope nd Occupational Lung Disea appropriate rooms in the hea ses lth facilities for confidential s creening Hospitals LS-MOH-304626-GO-RFQ-SA TBHSS-AF / Supply and delive Innovative Prevention, Detec Request for Quota Single Stage - One E Pending Impl IDA / 66950 Post Open - National 14,500.00 0.00 2023-04-05 2023-05-31 2023-07-30 ry of Personal Protective Clot tion and Treatment of TB tions nvelope ementation hing for Centre of Excellency staff. LS-MOH-362157-GO-RFQ-SA Regional Capacity for Diseas TBHSS-AF-2023 / Procureme e Surveillance, and Diagnost Request for Quota Single Stage - One E Pending Impl nt, supply , distribution and i IDA / 66950 ics and Management of TB a Post Open - National 90,000.00 0.00 2023-06-23 2023-08-18 2023-10-17 tions nvelope ementation nstallation of 49 air conditio nd Occupational Lung Disea ners for mini lab and labs acr ses oss the country LS-MOH-232004-GO-RFQ-SA TBHSS / Procure and supply P Regional Capacity for Diseas rinted (Guideline), e Surveillance, and Diagnost Request for Quota Single Stage - One E • Printing guidelines by 35 IDA / 66950 ics and Management of TB a Post Open - National 95,000.00 0.00 Canceled 2021-10-15 2021-12-13 2022-01-22 tions nvelope 0 nd Occupational Lung Disea • TPT Commodities SOP by ses 350 • TPT Commodities laminat ed Job Aid by 750 LS-MOH-365220-GO-DIR-SAT Regional Learning and Innov BHSS-AF-2023 / Procurement Pending Impl IDA / 66950 ation, and Project Managem Post Direct Selection Direct - National 740,000.00 0.00 2023-06-30 2023-07-05 2023-08-09 2023-12-07 of 7 Landcruiser mounted wit ementation ent h digital X rays and 3 Back P acks Digital X rays LS-MOH-365222-GO-RFQ-SA TBHSS-AF-2023 / Procureme Regional Learning and Innov Request for Quota Single Stage - One E Pending Impl nt of COE Equipment ( Brand IDA / 66950 ation, and Project Managem Post Open - National 40,000.00 0.00 2023-07-05 2023-08-30 2023-10-09 tions nvelope ementation ed Gazebos, Tents for Patient ent s, Foldable Tables and chairs ) LS-MOH-365223-GO-RFQ-SA Regional Learning and Innov TBHSS-AF-2023 / Procureme Request for Quota Single Stage - One E Pending Impl IDA / 66950 ation, and Project Managem Post Open - National 26,000.00 0.00 2023-07-05 2023-08-30 2023-10-09 nt of X Ray Protective equip tions nvelope ementation ent ment ( Dosimeters and Lead Protectors ) Page 8 LS-MOH-365224-GO-RFQ-SA TBHSS-AF-2023 / Procureme Regional Learning and Innov Request for Quota Single Stage - One E Pending Impl nt of Personal Protective Equi IDA / 66950 ation, and Project Managem Post Open - National 63,000.00 0.00 2023-07-05 2023-08-30 2023-09-29 tions nvelope ementation pment and camping equipme ent nt for COE expansion into 8 d istricts LS-MOH-365226-GO-RFQ-SA Regional Learning and Innov TBHSS-AF-2023 / Procureme Request for Quota Single Stage - One E Pending Impl IDA / 66950 ation, and Project Managem Post Open - National 52,000.00 0.00 2023-07-05 2023-08-30 2023-10-09 nt of Medical Equipment and tions nvelope ementation ent consumables for COE expans ion. LS-MOH-365230-GO-RFB-SA Regional Learning and Innov TBHSS-AF-2023 / Procureme Single Stage - One E Pending Impl IDA / 66950 ation, and Project Managem Post Request for Bids Open - National 1,201,333.00 0.00 2023-06-16 2023-06-21 2023-08-02 2023-09-01 2023-09-20 2023-11-19 nt of 32 Standard 4 by 4 Do nvelope ementation ent uble cab with canopy LS-MOH-365315-GO-DIR-SAT BHSS-AF-2023 / Procurement Regional Learning and Innov Direct - Internation Pending Impl and supply of GeneXpert Mac IDA / 66950 ation, and Project Managem Post Direct Selection 118,000.00 0.00 2023-06-30 2023-07-05 2023-08-09 2023-10-08 al ementation hines and GeneXpert Cartrid ent ges for expansion of COE to 8 districts NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SATBHSS/MOH/OC-001 / Co Regional Learning and Innov IDA / 58220 Post Direct Selection Direct 20,280.00 0.00 Canceled 2017-08-02 2017-08-07 2017-09-11 2019-03-13 mmunication For PIU ation, and Project Managem ent SATBHSS/MOH/NC-001 / Tec hnical Support to Point of Car e Clinics(Mafeteng and Lerib Innovative Prevention, Detec Pending Impl e) to miners, ex-miners and t IDA / 58220 Post Direct Selection Direct 252,016.00 0.00 2017-08-04 2017-08-09 2017-08-28 2020-08-27 tion and Treatment of TB ementation heir families AND Improving Patient referral system for cr oss border referrals for activ e miners SATBHSS/MOH/NC-002 / Ad ministration and Human Res ource Management to Point of Care Clinics(Mafeteng and Innovative Prevention, Detec IDA / 58220 Post Direct Selection Direct 163,387.38 1,133,659.89 Signed 2017-09-01 2017-08-01 2017-09-06 2017-11-15 2017-10-11 2017-08-01 2019-06-11 Leribe) to miners, ex-miners tion and Treatment of TB and their families AND Impro ving Patient referral system f or cross border referrals for a ctive miners SATBHSS/MOH/NC-004 / Pro Regional Learning and Innov Request for Quota Single Stage - One E IDA / 58220 Post Open - National 4,750.00 0.00 Canceled 2017-09-10 2017-10-03 2018-10-03 cure Vehicle Insurance ation, and Project Managem tions nvelope ent SATBHSS/MOH/NC-006 / Mon itoring and Evaluation to TEB Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 58220 Post Open - National 2,365.00 0.00 Canceled 2017-09-16 2017-11-11 2020-08-11 A POC sites (at least once ev tion and Treatment of TB tions nvelope ery year for two days supervi sion) SATBHSS/MOH/T-001 / Traini Regional Capacity for Diseas ngs on environmental and s e Surveillance, and Diagnost Request for Quota Single Stage - One E IDA / 58220 Post Open - National 17,480.00 0.00 Canceled 2017-10-03 2017-10-31 2017-11-05 ocial Management Health Ca ics and Management of TB a tions nvelope re Workers and other stakeh nd Occupational Lung Disea olders ses SATBHSS/MOH/T-002 / Inspe Innovative Prevention, Detec Request for Quota Single Stage - One E ction at the Mines and other IDA / 58220 Post Open - National 3,740.40 0.00 Canceled 2017-09-02 2017-09-16 2017-09-21 tion and Treatment of TB tions nvelope high risk Occupational Areas SATBHSS/MOH/T-003 / Natio nal Advisory Committee On L Innovative Prevention, Detec Request for Quota Single Stage - One E abour and stakeholders wor IDA / 58230 Post Open - National 1,610.00 0.00 Canceled 2017-10-04 2017-10-20 2017-10-22 tion and Treatment of TB tions nvelope king sessions (workshop) on updating of the OSH profile SATBHSS/MOH/T-004 / Disse Innovative Prevention, Detec Request for Quota Single Stage - One E mination workshop for the re IDA / 58220 Post Open - National 6,900.00 0.00 Canceled 2017-10-28 2017-11-20 2017-11-27 tion and Treatment of TB tions nvelope vised OSH Profile SATBHSS/MOH/T-005 / Cond uct consultation meetings wit h different stakeholders incl uding parliamentary counsel Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 58220 Post Open - National 15,350.58 0.00 Canceled 2017-09-30 2017-10-28 2017-11-27 and validation workshop for f tion and Treatment of TB tions nvelope ormulating and reviewing pol icies, guidelines and legislati on pertaining to OSH and wor kers compensation SATBHSS/MOH/T-006 / Sensi Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 58220 Post Open - National 3,936.61 0.00 Canceled 2017-09-01 2017-10-01 2017-10-06 tization trainings on OSH in t tion and Treatment of TB tions nvelope he mines SATBHSS/MOH/T-007 / Stake holders meetings during the Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 58220 Post Open - National 2,554.20 0.00 Canceled 2017-09-23 2017-10-16 2017-10-20 development of the OSH info tion and Treatment of TB tions nvelope rmation dissemination tools SATBHSS/MOH/T-008 / Induc tions in 2 districts (Leribe, Ma Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 58220 Post Open - National 13,800.00 0.00 Canceled 2017-10-06 2017-12-11 2019-12-11 feteng) by Labour officers fro tion and Treatment of TB tions nvelope m the Central level SATBHSS/MOH/T-009 / Joint Innovative Prevention, Detec Request for Quota Single Stage - One E educational sessions at the IDA / 58220 Post Open - National 12,000.00 0.00 Canceled 2017-10-28 2017-11-25 2017-11-30 tion and Treatment of TB tions nvelope mines in RSA SATBHSS/MOH/T-010 / Estab Innovative Prevention, Detec Request for Quota Single Stage - One E lish & Train on TB smear and IDA / 58220 Post Open - National 2,160.57 0.00 Canceled 2017-08-18 2017-09-11 2017-09-18 tion and Treatment of TB tions nvelope GeneXpert EQA Regional Capacity for Diseas SATBHSS/MOH/T-011 / Labor e Surveillance, and Diagnost Request for Quota Single Stage - One E IDA / 58220 Post Open - National 10,056.00 0.00 Canceled 2017-09-04 2017-09-24 2017-10-08 atory Study tour ics and Management of TB a tions nvelope nd Occupational Lung Disea ses Page 9 SATBHSS/MOH/T-012 / Traini ng on Management of MDR T Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 58220 Post Open - National 40,869.80 0.00 Canceled 2017-10-07 2017-11-11 2017-11-18 B for Medical Officer and Nur tion and Treatment of TB tions nvelope ses In Country Training. Regional Capacity for Diseas SATBHSS/MOH/T-013 / Annu e Surveillance, and Diagnost Request for Quota Single Stage - One E IDA / 58220 Post Open - National 3,881.00 0.00 Canceled 2018-02-10 2018-03-10 2018-03-31 al IUATLD Conference ics and Management of TB a tions nvelope nd Occupational Lung Disea ses Regional Capacity for Diseas SATBHSS/MOH/T-014 / Regio e Surveillance, and Diagnost Request for Quota Single Stage - One E IDA / 58220 Post Open - National 7,056.00 0.00 Canceled 2017-08-26 2017-09-30 2017-10-10 nal SADC Meeting ics and Management of TB a tions nvelope nd Occupational Lung Disea ses Regional Capacity for Diseas SATBHSS/MOH/T-015 / ASLM e Surveillance, and Diagnost Request for Quota Single Stage - One E IDA / 58220 Post Open - National 3,245.00 0.00 Canceled 2018-02-24 2018-03-31 2018-04-21 Conference ics and Management of TB a tions nvelope nd Occupational Lung Disea ses Regional Capacity for Diseas SATBHSS/MOH//T-016 / TB S e Surveillance, and Diagnost Request for Quota Single Stage - One E ymposium & Launch of the Pr IDA / 58220 Post Open - National 19,929.48 0.00 Canceled 2017-09-05 2017-10-13 2017-10-20 ics and Management of TB a tions nvelope oject nd Occupational Lung Disea ses SATBHSS/MOH/T-017 / Study Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 58220 Post Open - National 3,090.00 0.00 Canceled 2017-08-25 2017-09-14 2017-09-21 Tour South Africa Spoligotypi tion and Treatment of TB tions nvelope ng Regional Capacity for Diseas SATBHSS/MOH/T-018 / Smea e Surveillance, and Diagnost Request for Quota Single Stage - One E r Microscopy and GeneXpert IDA / 58220 Post Open - National 81,913.17 0.00 Canceled 2017-08-23 2017-09-12 2017-09-19 ics and Management of TB a tions nvelope Refresher training nd Occupational Lung Disea ses Regional Capacity for Diseas SATBHSS/MOH/T-019 / Natio e Surveillance, and Diagnost Request for Quota Single Stage - One E nal TB EQA Guidline Review IDA / 58220 Post Open - National 493.44 0.00 Canceled 2017-08-23 2017-09-10 2017-09-12 ics and Management of TB a tions nvelope Meeting nd Occupational Lung Disea ses Regional Capacity for Diseas SATBHSS/MOH/T-20 / Nation e Surveillance, and Diagnost Request for Quota Single Stage - One E al TB Lab EQA Guidelines Dis IDA / 58220 Post Open - National 4,841.20 0.00 Canceled 2017-09-08 2017-09-30 2017-10-03 ics and Management of TB a tions nvelope semination meeting nd Occupational Lung Disea ses Regional Capacity for Diseas SATBHSS/MOH/T-21 / Annual e Surveillance, and Diagnost Request for Quota Single Stage - One E IDA / 58220 Post Open - National 8,878.92 0.00 Canceled 2017-08-25 2017-09-13 2017-09-15 TB Laboratory Meeting ics and Management of TB a tions nvelope nd Occupational Lung Disea ses SATBHSS/MOH/T-022 / Cond Regional Capacity for Diseas uct quarterly supervisions on e Surveillance, and Diagnost Request for Quota Single Stage - One E IDA / 58220 Post Open - National 62,305.60 0.00 Canceled 2017-10-07 2017-11-01 2017-11-08 TB diagnosis including EQA a ics and Management of TB a tions nvelope nd management nd Occupational Lung Disea ses Regional Capacity for Diseas SATBHSS/MOH/T-023 / Cond e Surveillance, and Diagnost Request for Quota Single Stage - One E IDA / 58220 Post Open - National 7,878.72 0.00 Canceled 2017-10-07 2017-10-29 2017-11-01 uct sensitization meetings ics and Management of TB a tions nvelope nd Occupational Lung Disea ses Regional Capacity for Diseas SATBHSS/MOH/T-024 / SAMT e Surveillance, and Diagnost Request for Quota Single Stage - One E RAC for Mining (Mining engin IDA / 58220 Post Open - National 18,648.00 0.00 Canceled 2017-09-23 2017-10-13 2017-10-20 ics and Management of TB a tions nvelope eers) nd Occupational Lung Disea ses SATBHSS/MOH/T-025 / Minin Regional Capacity for Diseas g health and safety course - e Surveillance, and Diagnost Request for Quota Single Stage - One E IDA / 58220 Post Open - National 13,624.00 0.00 Canceled 2017-10-14 2017-11-03 2017-11-10 Tuition fees (GOL reps at the ics and Management of TB a tions nvelope mines) nd Occupational Lung Disea ses Regional Capacity for Diseas SATBHSS/MOH/T-026 / Mine e Surveillance, and Diagnost Request for Quota Single Stage - One E IDA / 58220 Post Open - National 14,718.00 0.00 Canceled 2017-08-30 2017-09-17 2017-10-08 OSH conference in Denmark ics and Management of TB a tions nvelope nd Occupational Lung Disea ses Regional Capacity for Diseas SATBHSS/MOH/T-027 / Nosh e Surveillance, and Diagnost Request for Quota Single Stage - One E com Conference in South Afr IDA / 58220 Post Open - National 8,028.00 0.00 Canceled 2017-09-04 2017-09-22 2017-09-29 ics and Management of TB a tions nvelope ica nd Occupational Lung Disea ses SATBHSS/MOH/T-028 / Train relevant Caregivers and CBO Regional Learning and Innov s to provide advocacy and sc Request for Quota Single Stage - One E IDA / 58220 ation, and Project Managem Post Open - National 71,574.00 0.00 Canceled 2017-11-24 2017-12-23 2018-02-21 reen targeted groups at com tions nvelope ent munity level and link then wi th the mobile disgnostic clini cs (X-rays) SATBHSS/MOH/T-029 / Cond Regional Learning and Innov Request for Quota Single Stage - One E IDA / 58220 Post Open - National 1,705.20 0.00 Canceled 2017-09-24 2017-10-20 2018-02-17 uct NTC quarterly meetings ation, and Project Managem tions nvelope ent SATBHSS/MOH/T-030 / Atten Regional Learning and Innov Request for Quota Single Stage - One E IDA / 58220 Post Open - National 15,282.00 0.00 Canceled 2017-12-08 2018-01-03 2018-01-17 d regional meetings ation, and Project Managem tions nvelope ent SATBHSS/MOH/T-031 / Supp Regional Learning and Innov Request for Quota Single Stage - One E IDA / 58220 Post Open - National 10,000.00 0.00 Canceled 2017-09-09 2017-10-03 2018-01-31 ort the M&E systems - Super ation, and Project Managem tions nvelope visions ent SATBHSS/MOH/T-032 / Annu Regional Learning and Innov Request for Quota Single Stage - One E al joint review plus partial su IDA / 58220 ation, and Project Managem Post Open - National 25,552.00 0.00 Canceled 2017-11-11 2017-12-05 2017-12-12 tions nvelope pport to independent externa ent l review of NTP SATBHSS/MOH/T-033 / Cond Regional Learning and Innov Request for Quota Single Stage - One E IDA / 58220 Post Open - National 19,195.86 0.00 Canceled 2017-12-09 2018-01-20 2018-02-19 uct Regional Project Review ation, and Project Managem tions nvelope meeting ent SATBHSS/MOH/T-034 / Finan Regional Learning and Innov Request for Quota Single Stage - One E cial Management/procureme IDA / 58220 ation, and Project Managem Post Open - National 18,426.00 0.00 Canceled 2017-09-30 2017-11-25 2018-03-25 tions nvelope nt/auditing training - Durban ent South Africa SATBHSS/MOH/T-035 / Outco Regional Learning and Innov Request for Quota Single Stage - One E me based M&E implementati IDA / 58220 ation, and Project Managem Post Open - National 2,697.68 0.00 Canceled 2018-02-03 2018-03-10 2018-04-09 tions nvelope on training ent Page 10 SATBHSS/MOH/NC-005 / Co mmunity based organization Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 58220 Post Open - National 100,000.00 0.00 Canceled 2017-08-26 2017-10-21 2017-12-20 s to intensify case finding ( S tion and Treatment of TB tions nvelope creening) at community level SATBHSS/MOH/NC-035 / Sup Regional Learning and Innov ply, installation and Commiss Request for Quota Single Stage - One E Pending Impl IDA / 58220 ation, and Project Managem Post Open - National 11,974.00 0.00 2018-02-15 2018-02-26 2022-02-25 ioning of Fixed Asset Manage tions nvelope ementation ent ment Software for PIU Staff. SATBHSS/MOH/NC-001/2018 Regional Capacity for Diseas / Provide annual service and e Surveillance, and Diagnost Request for Quota Single Stage - One E Pending Impl maintenance or repairs for La IDA / 58220 ics and Management of TB a Post Open - National 60,000.00 0.00 2018-12-08 2019-02-02 2019-08-01 tions nvelope ementation b equipment at NTRL, Moteb nd Occupational Lung Disea ang,and Leribe Laboratories ses SATBHSS/MOH/NC-001/2019 / Engage a service provider f Regional Capacity for Diseas or electronic System connec e Surveillance, and Diagnost Request for Quota Open - Internationa Single Stage - One E tivity to 36 sites for 50 Gene IDA / 58220 ics and Management of TB a Post 89,513.00 85,834.52 Completed 2019-04-06 2019-06-01 2019-09-25 2020-05-31 2019-11-04 tions l nvelope Xpert Machines(1 year contra nd Occupational Lung Disea ct electronic Connectivity sys ses tem for 36 sites including trai ning costs) Regional Capacity for Diseas SATBHSS/MOH/NC-002/2019 e Surveillance, and Diagnost Request for Quota Open - Internationa Single Stage - One E Pending Impl / Service and maintenance of IDA / 58220 Post 5,283.54 0.00 2019-10-26 2019-12-21 2020-03-20 ics and Management of TB a tions l nvelope ementation Laboratory equipment nd Occupational Lung Disea ses SATBHSS/MOH/NC-004/2019 Regional Learning and Innov Request for Quota Open - Internationa Single Stage - One E / Installation of Microsoft Ho IDA / 58220 ation, and Project Managem Post 10,000.00 10,031.27 Completed 2019-03-16 2019-05-11 2019-04-09 2019-11-07 2019-04-18 tions l nvelope me & Office Software for 50 ent Computers Regional Capacity for Diseas SATBHSS/MOH/NC-003/2019 e Surveillance, and Diagnost Request for Quota Open - Internationa Single Stage - One E / Procure services and maint IDA / 58220 Post 2,100.00 0.00 Canceled 2019-07-20 2019-09-14 2019-10-14 ics and Management of TB a tions l nvelope enance of PCR Work Station nd Occupational Lung Disea ses LS-MOH-168698-NC-RFQ / Pr Regional Capacity for Diseas ocurement of Consultant ser e Surveillance, and Diagnost Request for Quota Single Stage - One E IDA / 58220 Post Open - National 63,000.00 0.00 Canceled 2020-04-24 2020-06-19 2020-12-16 vices for Risk Communication ics and Management of TB a tions nvelope and Community Engagement nd Occupational Lung Disea ses LS-MOH-329734-NC-DIR-SAT BHSSAF-2023 / Service and Innovative Prevention, Detec Direct - Internation Pending Impl IDA / 66950 Post Direct Selection 112,000.00 0.00 2023-02-07 2023-02-12 2023-03-19 2023-05-18 maintenance including repair tion and Treatment of TB al ementation s of the GeneXpert Machines LS-MOH-332051-NC-DIR-SAT BHSSAF-2023 / Engagement Regional Learning and Innov Direct - Internation Pending Impl of Tompro Software Consulta IDA / 66950 ation, and Project Managem Post Direct Selection 40,000.00 0.00 2023-03-05 2023-03-10 2023-04-14 2023-10-11 al ementation nt for Training of 10 officers ent on the use of the system. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SATBHSS/MOH/C-001 / Cons ultancy for design for works i Innovative Prevention, Detec Quality And Cost- n Correctional Facilities - ren IDA / 58220 Post Open - National 30,000.00 0.00 Canceled 2017-07-28 2017-08-31 2017-10-14 2017-11-11 2017-12-11 2018-01-15 2018-02-19 2019-02-19 tion and Treatment of TB Based Selection ovations to establish isolatio n cells within the prisons for TB infection control SATBHSS/MOH/C-007 / Enga Regional Capacity for Diseas ge Consultant to Conduct Ba e Surveillance, and Diagnost Consultant Qualifi Under Implement IDA / 58220 Post Open - National 43,457.32 0.00 2017-08-28 2017-03-31 2017-09-18 2017-11-01 2017-12-01 2018-01-05 2018-04-05 seline study and Mapping ex ics and Management of TB a cation Selection ation ercise. nd Occupational Lung Disea ses SATBHSS/MOH/C008 / Consu ltant to conduct a Study on Regional Learning and Innov Consultant Qualifi Under Implement out-of-pocket expenditures f IDA / 58220 ation, and Project Managem Post Open - National 120,000.00 0.00 2017-08-31 2018-03-12 2017-09-21 2017-11-04 2017-12-04 2018-01-08 2018-04-08 cation Selection ation or TB by households that was ent agreed during the RAC meeti ng SATBHSS/MOH/C-001/2018 / Engagement of a Community Based Organisation or Non G Innovative Prevention, Detec Consultant Qualifi Under Implement overnmental Organisation To IDA / 58220 Post Open - National 37,206.00 0.00 2018-03-29 2018-07-26 2018-04-03 2018-08-10 2018-04-24 2018-05-26 2018-06-05 2018-12-02 tion and Treatment of TB cation Selection ation Track and trace Ex miners w ho submitted their insufficien t claims to facilitate submissi on of missing documents. SATBHSS/MOH/C-003/2018 / Engagement of a consultanc Innovative Prevention, Detec Consultant Qualifi y Firm to Design Motebang L IDA / 58220 Post Open - National 113,567.00 0.00 Canceled 2018-02-14 2018-03-30 2018-02-16 2018-03-25 2018-04-08 2018-04-18 2018-05-28 tion and Treatment of TB cation Selection aboratory Renovation and M aseru Central Correctional Pri sons isolation cells. SATBHSS/MOH/C-006 / Enga Regional Capacity for Diseas ge Consultancy Firm for Desi e Surveillance, and Diagnost Consultant Qualifi gn service for Refurbishment IDA / 58220 ics and Management of TB a Post Open - National 113,567.00 0.00 Canceled 2018-04-12 2018-05-03 2018-06-16 2018-07-16 2018-08-20 2018-10-19 cation Selection of Motebang Hospital TB Lab nd Occupational Lung Disea oratory (Leribe) and Maseru ses Central Correctional Service SATBHSS/MOH/C010/2018 / Regional Capacity for Diseas Engage a local Consultancy F e Surveillance, and Diagnost Consultant Qualifi irm to train the joint Inspecti IDA / 58220 ics and Management of TB a Post Open - National 11,536.00 0.00 Canceled 2018-08-05 2018-08-26 2018-10-02 2018-10-09 2018-10-19 2018-11-28 cation Selection on team and to develop joint nd Occupational Lung Disea inspection guidelines and ch ses eck list for Mines. SATBHSS/MOH/C-007/2018 / Engage an NGO to impliment Regional Learning and Innov Consultant Qualifi Community BAsed Activities i IDA / 58220 ation, and Project Managem Post Open - National 83,576.00 0.00 Canceled 2018-03-26 2018-04-16 2018-05-23 2018-05-30 2018-06-11 2018-08-10 cation Selection n Leribe and Thaba Tseka- Pil ent ot the Centre of Excellence LS-MOH-165005-CS-CQS / En Regional Capacity for Diseas gage a consultancy firm to c e Surveillance, and Diagnost Consultant Qualifi Open - Internationa IDA / 58220 Post 101,244.00 0.00 Canceled 2020-03-22 2020-04-12 2020-05-26 2020-06-25 2020-07-30 2021-01-26 arry out Risk Communication ics and Management of TB a cation Selection l and Community Engagement nd Occupational Lung Disea ses Page 11 LS-MOH-333093-CS-CQS-SA TBHSSAF-2023 / Engage a co Innovative Prevention, Detec Consultant Qualifi Open - Internationa nsultant to Support develop IDA / 66950 Post 33,600.00 0.00 Canceled 2023-02-05 2023-02-26 2023-04-11 2023-05-11 2023-06-15 2023-12-12 tion and Treatment of TB cation Selection l ment of the TB strategic plan and Monitoring and Evaluati on plan. LS-MOH-329732-NC-DIR-SAT BHSSAF-2023 / Engagement Regional Learning and Innov Consultant Qualifi Pending Impleme of Consultancy firm to provid IDA / 66950 ation, and Project Managem Post Open - National 100,000.00 0.00 2023-03-16 2023-04-06 2023-05-20 2023-06-19 2023-07-24 2024-01-20 cation Selection ntation e comprehensive Training of ent 10 Hygienist in Lesotho INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SATBHSS/MOH/C-003 / ICT c onsultant to develop databas Innovative Prevention, Detec Individual Consult IDA / 58220 Post Open 13,500.00 0.00 Canceled 2017-10-09 2017-11-11 2017-11-25 2017-12-23 2018-02-01 e to maintain statistics of acc tion and Treatment of TB ant Selection idents and incidences SATBHSS/MOH/C-005 / Enga ge Consultant to develop an i nformation booklet on occup Innovative Prevention, Detec Individual Consult IDA / 58220 Post Open 13,500.00 0.00 Canceled 2017-08-21 2017-09-23 2017-10-14 2017-11-04 2018-01-03 ational health seeking advice tion and Treatment of TB ant Selection and compensation on occupa tional hazards for Ex miners SATBHSS/MOH/C-016 / Enga Regional Capacity for Diseas ge Consultancy for design for e Surveillance, and Diagnost Individual Consult IDA / 58220 Post Open 30,000.00 0.00 Canceled 2017-08-04 2017-08-16 2017-08-31 2017-10-05 2018-10-05 works, upgrading and superv ics and Management of TB a ant Selection ision on renovation of Nation nd Occupational Lung Disea al TB Reference Lab ses SATBHSS/MOH/C-009 / Staff Regional Learning and Innov Individual Consult salaries for TB diagnosis and IDA / 58220 ation, and Project Managem Post Open 190,350.00 0.00 Canceled 2017-08-27 2017-10-15 2017-11-05 2017-12-10 2019-12-10 ant Selection Management ent SATBHSS/MOH/C-010 / Enga Regional Learning and Innov Individual Consult Pending Impleme IDA / 58220 Post Open 12,600.00 0.00 2017-08-21 2017-09-23 2017-10-14 2017-11-18 2019-11-18 ge Microbiologist for NTRL ation, and Project Managem ant Selection ntation ent SATBHSS/MOH/C-011 / Enga Regional Learning and Innov Individual Consult Under Implement IDA / 58220 Post Open 8,100.00 0.00 2017-08-21 2017-10-09 2017-09-14 2017-10-30 2017-12-04 2019-12-04 ge MDR Focal Person ation, and Project Managem ant Selection ation ent SATBHSS/MOH/C-012 / Enga Regional Learning and Innov Individual Consult IDA / 58220 Post Open 81,000.00 0.00 Canceled 2017-08-21 2017-10-09 2017-10-30 2017-12-04 2019-12-04 ge TB Senior Technical Office ation, and Project Managem ant Selection r ent SATBHSS/MOH/C-013 / Enga Regional Learning and Innov Individual Consult Under Implement IDA / 58220 Post Open 135,000.00 0.00 2017-08-21 2018-01-29 2017-10-09 2017-10-30 2017-12-04 2018-12-04 ge Public Health Advisor ation, and Project Managem ant Selection ation ent SATBHSS/MOH/C-014 / Salari Regional Learning and Innov Individual Consult IDA / 58220 Post Open 129,600.00 0.00 Canceled 2017-08-21 2017-10-09 2017-10-30 2017-12-04 2019-12-04 es For PIU ation, and Project Managem ant Selection ent Regional Capacity for Diseas SATBHSS/MOH/C-019 / Enga e Surveillance, and Diagnost Individual Consult Pending Impleme ge Program Officer Communi IDA / 58220 Post Open 13,626.00 0.00 2017-12-04 2018-01-22 2018-02-12 2018-03-19 2020-03-18 ics and Management of TB a ant Selection ntation ty TB nd Occupational Lung Disea ses Regional Capacity for Diseas SATBHSS/MOH/C-020 / Enga e Surveillance, and Diagnost Individual Consult Pending Impleme ge Program Officer - Peadiatr IDA / 58220 Post Open 13,626.00 0.00 2017-12-04 2018-01-22 2018-02-12 2018-03-19 2020-03-18 ics and Management of TB a ant Selection ntation ic TB and Trainings nd Occupational Lung Disea ses Regional Capacity for Diseas SATBHSS/MOH/C-018 / Enga e Surveillance, and Diagnost Individual Consult Pending Impleme ge the Environmental and So IDA / 58220 Post Open 18,000.00 0.00 2017-12-04 2018-01-22 2018-02-12 2018-03-19 2020-03-18 ics and Management of TB a ant Selection ntation cial Officer nd Occupational Lung Disea ses Regional Capacity for Diseas SATBHSS/MOH/C-022 / Enga e Surveillance, and Diagnost Individual Consult ge Equipment Specialist for 1 IDA / 58220 Post Open 6,000.00 0.00 Canceled 2018-01-08 2018-05-10 2018-01-18 2018-01-20 2018-02-04 2018-02-14 ics and Management of TB a ant Selection 0 days nd Occupational Lung Disea ses SATBHSS/MOH/C-017 / Enga ge Occupational Specialist to Innovative Prevention, Detec Individual Consult IDA / 58220 Prior Open 51,146.00 0.00 Canceled 2018-02-23 2018-06-25 2018-04-15 2018-04-22 2018-05-02 2018-10-29 assist the Ministry of Health t tion and Treatment of TB ant Selection o strengthen the Occupation al Health Program SATBHSS/MOH/C-002 / Enga ge a consultant to update 20 Innovative Prevention, Detec Individual Consult Pending Impleme IDA / 58220 Post Open 18,000.00 0.00 2017-07-31 2017-09-18 2017-10-09 2017-11-13 2018-02-11 08 OSH profile which will inf tion and Treatment of TB ant Selection ntation orm OSH legislation SATBHSS/MOH/C-012/2018 / Regional Capacity for Diseas Engagement of a consultant e Surveillance, and Diagnost Individual Consult Under Implement IDA / 58220 Post Open 26,000.00 0.00 2018-08-12 2018-08-10 2018-09-30 2018-10-21 2018-11-25 2019-05-24 to assist the MOLE to develo ics and Management of TB a ant Selection ation p the OSH policy which will fo nd Occupational Lung Disea rm the basis of the Act. ses SATBHSS/MOH/C-004 / Enga Innovative Prevention, Detec Individual Consult ge Consultant to develop OS IDA / 58220 Post Open 13,500.00 0.00 Canceled 2018-08-26 2017-09-14 2018-09-28 2018-10-19 2018-11-09 2019-01-08 tion and Treatment of TB ant Selection H Information dissemination tools. SATBHSS/MOH/C-013/2018 / Engage an NGO to implemen Regional Learning and Innov Under Implement t Community based activities IDA / 58220 ation, and Project Managem Prior Direct Selection Direct 1,400,000.00 0.00 2018-10-01 2018-10-11 2018-10-29 2018-12-15 2020-12-14 ation in Leribe and Thaba Tseka ( P ent ilot the Centre of Excellence) SATBHSS/MOH/C-002/2018 / Engagement of Consultant to Innovative Prevention, Detec Individual Consult IDA / 58220 Post Open 20,280.69 0.00 Canceled 2019-02-04 2019-04-01 2019-04-15 2019-04-21 2019-06-20 develop IEC Material for Migr tion and Treatment of TB ant Selection ant Miners, Local miners and Ex miners. SATBHSS/MOH/C-011/2018 / Regional Capacity for Diseas Engagement of Data Capture e Surveillance, and Diagnost Individual Consult IDA / 58220 Post Open 9,359.24 0.00 Canceled 2018-10-22 2018-12-10 2018-12-31 2019-02-04 2019-08-03 s for compensation claims for ics and Management of TB a ant Selection Ministry of Labour nd Occupational Lung Disea ses Page 12 SATBHSS/MOH/C-002/2019 / Innovative Prevention, Detec Individual Consult Engage IPC program officer a IDA / 58220 Post Open 28,600.00 0.00 Canceled 2019-03-18 2019-03-28 2019-05-06 2019-05-27 2019-07-01 2021-06-30 tion and Treatment of TB ant Selection t national level Regional Capacity for Diseas SATBHSS/MOH/C-003/2019 / e Surveillance, and Diagnost Individual Consult Employ nursing sisters for 3 IDA / 58220 Post Open 38,362.75 0.00 Canceled 2019-02-28 2019-03-29 2019-04-18 2019-05-09 2019-06-13 2020-06-12 ics and Management of TB a ant Selection designated points of entry nd Occupational Lung Disea ses SATBHSS/MOH/C-004/2019 / Engage Occupational health Innovative Prevention, Detec Individual Consult Under Implement IDA / 58220 Post Open 30,288.80 0.00 2019-03-25 2019-03-29 2019-05-13 2019-06-03 2019-07-08 2021-07-07 and Safety Specialist to work tion and Treatment of TB ant Selection ation with MOM and MOLE SATBHSS/MOH/C-006/2019 / Engage a Consultant to carry out Cost Benefit/Health Impa Regional Learning and Innov ct study on Tuberculosis Infe IDA / 58220 ation, and Project Managem Post Direct Selection Direct 28,580.25 0.00 Canceled 2019-04-15 2019-04-25 2019-06-29 2019-12-26 ction Control in the correctio ent nal facilities. Annex to the on going CBA/HIT study - extend the tool to correctional faciliti es SATBHSS/MOH/C-007/2019 / Regional Learning and Innov Engage a consultant to revie Individual Consult IDA / 58220 ation, and Project Managem Post Open 4,795.34 0.00 Canceled 2019-02-18 2019-04-08 2019-04-29 2019-06-03 2019-10-31 w and update the SATBHSS P ant Selection ent roject Implementation manu al SATBHSS/MOH/C-008/2019 / Regional Capacity for Diseas Engage a consultant to revie e Surveillance, and Diagnost Individual Consult Pending Impleme w the current mine health an IDA / 58220 ics and Management of TB a Post Open 100,000.00 0.00 2019-04-22 2019-06-10 2019-07-01 2019-08-05 2020-02-01 ant Selection ntation d safety legislation and draft nd Occupational Lung Disea an updated legislation for a s ses ix month period SATBHSS/MOH/C-005/2019 / Regional Capacity for Diseas Engage the OSH / legal exper e Surveillance, and Diagnost Individual Consult t to develop drafting instructi IDA / 58220 ics and Management of TB a Post Open 30,476.83 0.00 Canceled 2019-05-20 2019-07-08 2019-07-29 2019-09-02 2020-02-29 ant Selection ons (Engage the consultant f nd Occupational Lung Disea or 30 days to develop draftin ses g instructions) SATBHSS/MOH/C-001/2019 / Outsource supervision and q Regional Capacity for Diseas uality control services from a e Surveillance, and Diagnost consultancy firm for construc IDA / 58220 ics and Management of TB a Post Direct Selection Direct 187,225.98 0.00 Canceled 2019-04-08 2019-05-03 2019-04-18 2019-06-22 2021-01-02 tion of Isolation cell at Maser nd Occupational Lung Disea u Central Prison and Extensio ses n and Renovation of Moteban g Laboratory. SATBHSS/MOH/C-009/2019 / Regional Capacity for Diseas Engage a consultant to revie e Surveillance, and Diagnost Individual Consult w the current mine health an IDA / 58220 ics and Management of TB a Post Open 80,000.00 80,973.92 Completed 2019-05-01 2019-04-22 2019-06-19 2020-11-23 2019-07-10 2021-02-01 2019-08-14 2021-01-29 2020-02-10 2021-09-06 ant Selection d safety legislation and draft nd Occupational Lung Disea an updated legislation for a s ses ix month period Regional Capacity for Diseas LS-MOH-165008-CS-INDV / E e Surveillance, and Diagnost Individual Consult ngage Logistic or Project offic IDA / 58220 Post Open 5,600.00 0.00 Canceled 2020-03-22 2020-05-10 2020-05-31 2020-07-05 2020-10-03 ics and Management of TB a ant Selection er nd Occupational Lung Disea ses LS-MOH-232053-CS-INDV-SA Regional Capacity for Diseas TBHSS / Engage a consultant e Surveillance, and Diagnost Individual Consult Pending Impleme to develop National Occupati IDA / 66950 ics and Management of TB a Post Open 82,000.00 0.00 2021-05-09 2021-06-27 2021-07-18 2021-08-22 2022-02-18 ant Selection ntation onal Health and safety Act fo nd Occupational Lung Disea r Six Months Contract ses LS-MOH-247079-CS-CDS-SA Regional Learning and Innov TBHSS-AF / Engagement of in Under Implement IDA / 66950 ation, and Project Managem Post Direct Selection Direct 90,000.00 0.00 2021-11-21 2021-12-01 2022-02-04 2022-08-03 dividual consultant for Techni ation ent cal Assistance to audit TB Mo rtality. LS-MOH-288843-CS-INDV-SA TBHSS-AF / Engagement of In dividual Consultant to carryo Innovative Prevention, Detec Individual Consult IDA / 66950 Post Open 2,000.00 0.00 Canceled 2022-04-17 2022-05-11 2022-05-16 2022-05-24 2022-06-23 ut transcribing and translatio tion and Treatment of TB ant Selection n services for TB mortality au dit study for a period of 30 d ays. LS-MOH-329742-CS-INDV-SA Regional Capacity for Diseas TBHSSAF-2023 / Engage a co e Surveillance, and Diagnost Individual Consult nsultant to development reg IDA / 66950 ics and Management of TB a Post Open - National 27,000.00 0.00 Signed 2023-01-22 2023-02-23 2023-03-12 2023-04-28 2023-04-02 2023-05-02 2023-05-07 2023-07-06 ant Selection ulations for the newly develo nd Occupational Lung Disea ped National Occupational H ses ealth and safety bill LS-MOH-329749-CS-INDV-SA Regional Capacity for Diseas TBHSSAF-2023 / Engage a co e Surveillance, and Diagnost Individual Consult Under Implement nsultant to Develop or adopt IDA / 66950 ics and Management of TB a Post Open - National 36,000.00 0.00 2023-02-12 2023-05-10 2023-04-02 2023-04-23 2023-05-28 2023-08-26 ant Selection ation guiding documents for artisa nd Occupational Lung Disea nal mining (Guidelines, SOPS ses & Standards) LS-MOH-329752-CS-INDV-SA Regional Learning and Innov Individual Consult Pending Impleme TBHSSAF-2023 / Engage a co IDA / 66950 ation, and Project Managem Post Open - National 16,800.00 0.00 2023-10-31 2023-12-19 2024-01-09 2024-02-13 2024-04-13 ant Selection ntation nsultant for end of project Ev ent aluation LS-MOH-340713-CS-CDS-SA TBHSSAF-2023 / Engage an i Regional Learning and Innov nstitution to train Ministry of Direct - Internation Pending Impleme IDA / 66950 ation, and Project Managem Post Direct Selection 8,400.00 0.00 2023-02-09 2023-02-16 2023-03-25 2023-09-21 Health PIU procurement Offic al ntation ent ers (4) for World Bank’s New Procurement Framework Wor kshop. LS-MOH-340746-CS-INDV-SA Regional Capacity for Diseas TBHSSAF-2023 / Engagement e Surveillance, and Diagnost Individual Consult IDA / 66950 Post Open - National 45,000.00 0.00 Signed 2023-03-17 2023-03-03 2023-05-05 2023-04-28 2023-05-26 2023-05-02 2023-06-24 2024-01-30 of Drug resistant Survey Coor ics and Management of TB a ant Selection dinator for 10 months nd Occupational Lung Disea ses LS-MOH-340741-CS-CDS-SA Regional Learning and Innov TBHSSAF-2023 / Engage a tr Direct - Internation Under Implement IDA / 66950 ation, and Project Managem Post Direct Selection 31,281.00 0.00 2023-03-31 2023-03-03 2023-04-10 2023-06-14 2024-01-30 aining institution to provide al ation ent Data Analysis training for 15 officers twice LS-MOH-363809-CS-INDV-SA Regional Learning and Innov TBHSS-AF-2023 / Engagemen Individual Consult Pending Impleme IDA / 66950 ation, and Project Managem Post Open - National 4,000.00 0.00 2023-05-31 2023-07-19 2023-08-09 2023-09-13 2024-03-11 t of Assistant Procurement Of ant Selection ntation ent ficer for STEP System for a si x month period. Page 13 LS-MOH-365211-CS-INDV-SA Regional Learning and Innov TBHSS-AF-2023 / Engagemen Individual Consult Pending Impleme IDA / 66950 ation, and Project Managem Prior Open - National 530,526.00 0.00 2023-06-30 2023-08-18 2023-09-08 2023-10-13 2024-04-10 t of 120 Nurses for Expansion ant Selection ntation ent of Centre of Excellency for 8 Districts. LS-MOH-365215-CS-INDV-SA TBHSS-AF-2023 / Engagemen Regional Learning and Innov Individual Consult Pending Impleme t of 38 Laboratory Technician IDA / 66950 ation, and Project Managem Post Open - National 127,000.00 0.00 2023-06-30 2023-08-18 2023-09-08 2023-10-13 2024-04-10 ant Selection ntation s for Centre of Excellency Ex ent pansion into 8 districts LS-MOH-365234-CS-CDS-SA Regional Learning and Innov TBHSS-AF-2023 / Engagemen Pending Impleme IDA / 66950 ation, and Project Managem Post Direct Selection Direct - National 121,000.00 0.00 2023-06-30 2023-07-10 2023-09-13 2024-03-11 t of Sputum Collection Servic ntation ent e Provider for 6 months. Page 14 PROCUREMENT PLAN (Textual Part) Project information: Sierra Leone, Sierra Leone Land Administration Project; P177031 Project Implementation agency: Ministry of Lands, Housing and Country Planning Date of the Procurement Plan: October 20, 2021 Period covered by this Procurement Plan: December 2021 – August 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the National Public Procurement Act of 2016, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable. Works: is not applicable. Other Relevant Procurement Information. Not Applicable. Procurement Plan Goods Ref. Contract Estima Procure Prequalific Nation Revi Expect Expec Comme Num ted ment ation al ew ed bid ted nts ber (Descript Method (yes/no) Prefere openin Contr ion) Cost nce by g date act (yes/no Bank Start US$ ) Date (Prio r/ Post ) 4.4 Office IT 50,000 RFQ No No Post Decem Januar Equipmen ber y t 2021 2022 4.5 Office 30,000 RFQ No No Post Decem Januar furniture ber y 2021 2022 4.8 Vehicles 134,00 NCB No No Post Decem Januar and Motor 0 ber y Bikes 2021 2022 Consultancy Services Ref. Contract Estimat Procu Prequ Nation Revi Expec Expec Comme Num ed reme alifica al ew ted ted nts ber (Description) nt tion Prefere bid Contr Cost Meth (yes/n nce by openi act od o) Bank US$ (yes/no (Prio ng Start ) r/ date Date Post ) 1.1 Consultancy for 157,000 CQS No N/A Post the preparation of engineering design and bills of quantities for National and District Land Februa Commission ry March Offices. 2022 2022 1.2 Consultancy for 20,000 IC No N/A Post location analysis for the National Land Commission Head Office and District Land Februa Commission ry March Offices. 2022 2022 1.3 Consultancy 30,000 IC No N/A Post Service for a detailed program Febru for legislative land Januar ary sector reform. y 2022 2022 1.4 Consultancy 50,000 IC No N/A Post Service for the Development of a Training Needs Assesment and Febru Training Plan for Januar ary the land sector. y 2022 2022 2.1 Consultancy 150,000 IC No N/A Post Service for a comprehensive digital Land Records and Archive Febru Management Januar ary Strategy y 2022 2022 2.2 Consultancy 40,000 IC No N/A Post service for business process re-engineering and preparation of system design TOR Febru for the Januar ary development of a y 2022 2022 Land Information Management System 2.3 Consultancy 50,000 IC No N/A Post Service for analysis of existing mapping, index maps and survey plans, and development of requirements and Febru plans for providing Januar ary new base maps. y 2022 2022 2.4 Development of 30,000 CQS No N/A Post technical specifications, cost estimates and timelines for Continuously Operating Febru Reference Stations Januar ary (CORS) y 2022 2022 4.1 Gender Specialist 20,000 IC No N/A Post for Stakeholder Engagement Plan Decem Decem and Gender Action ber ber Plan 2021 2021 4.2 Social Specialist 20,000 IC No N/A Post for Resettlement Policy Framework & social aspects of Environmental and Social Decem Decem Management ber ber Framework 2021 2021 4.3 Environmental 20,000 IC No N/A Post Specialist for Environmental and Social Management Framework and Decem Decem Labor ber ber Management Plan 2021 2021 4.4 Consultancy 10,000 IC No N/A Post Services for development of a Project Febru Implementation Januar ary Manual (PIM) y 2022 2022 Non-Consultancy Services Ref. Contract Estima Procure Prequalific Nationa Revi Expec Expec Comme Num ted ment ation l ew ted ted nts ber (Descript Method (yes/no) Prefere bid Contr ion) Cost nce by openi act (yes/no Bank ng Start US$ ) date Date (Prio r/ Post ) 4.7 MS Office 30,000 RFQ No N/A Post software and conferenc Januar Febru e call y ary software 2022 2022 PROCUREMENT Sierra Leone : Sierra Leone Land Administration Project PLAN General Information Country: Sierra Leone 2023-02-27 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P177031 GPN Date: Project Name: Sierra Leone Land Administration Project Loan / Credit No: IDA / V3980 Ministry of Lands Housing and Country Planning Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SL-MLHCP-344316-GO-RFB / Procurement of ICT equipme nt: (49 Desktop Computers, 6 7 Laptops, 1 Plotter, 5 Printer Land Information System De Single Stage - One E Pending Impl s, 2 Digital Cameras, 5 Micro IDA / V3980 Post Request for Bids Open - National 380,000.00 0.00 2023-03-15 2023-03-20 2023-05-01 2023-05-31 2023-07-05 2024-01-01 velopment nvelope ementation phones, 5 Mega Phones, 2 Sp eakers, 1 Amplifier, 10 printe rs, 3 Television Sets, 1 Projec tor, 20 Monitors, 20 Docking Stations, 20 Tablets). SL-MLHCP-344347-GO-RFQ / Procurement of office furnitur Land Information System De Request for Quota Single Stage - One E Pending Impl IDA / V3980 Post Limited 98,000.00 0.00 2023-03-13 2023-05-08 2023-11-04 e: 60 desks, 80 chairs, 2 Conf velopment tions nvelope ementation erence table & 10 Cabinets. SL-MLHCP-345071-GO-RFB / Single Stage - One E Under Imple IDA / V3980 Project Management Post Request for Bids Open - National 700,000.00 0.00 2023-03-15 2023-05-23 2023-03-20 2023-05-27 2023-05-01 2023-05-31 2023-07-05 2024-01-01 Procurement of Ten (10) vehi nvelope mentation cles SL-MLHCP-345078-GO-RFQ / Request for Quota Single Stage - One E Pending Impl IDA / V3980 Project Management Post Limited 50,000.00 0.00 2023-03-12 2023-05-07 2023-11-03 Procurement of Five (5) Moto tions nvelope ementation rbikes. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SL-MLHCP-345414-NC-RFQ / Request for Quota Single Stage - One E Pending Impl Procurement of Services for IDA / V3980 Project Management Post Limited 20,000.00 0.00 2023-03-26 2023-05-21 2023-11-17 tions nvelope ementation development of Project Webs ite. SL-MLHCP-345416-NC-RFQ / Procurement of Service for d evelopment of M&E system Request for Quota Single Stage - One E Pending Impl with activity tracking tools, & IDA / V3980 Project Management Post Limited 20,000.00 0.00 2023-03-12 2023-05-07 2023-11-03 tions nvelope ementation establishment of Kobo Toolb ox account, installation of Ko bo Collect on tablets and trai ning of staff on the use of too ls. SL-MLHCP-352059-NC-RFB / Procurement of service to de Land Information System De Open - Internationa Single Stage - One E Under Imple sign, supply, and install Conti IDA / V3980 Prior Request for Bids 2,320,000.00 0.00 2023-04-07 2023-04-12 2023-05-24 2023-06-23 2023-07-28 2024-01-24 velopment l nvelope mentation nuously Operating Reference Stations (CORS), Rovers, and related trainings. SL-MLHCP-345415-NC-RFP / Procurement of a Project Man agement, Productivity & Coll Open - Internationa Single Stage - One E Under Imple IDA / V3980 Project Management Post Request for Bids 150,000.00 0.00 2023-04-18 2023-05-26 2023-04-23 2023-05-27 2023-06-04 2023-07-04 2023-08-08 2024-02-04 aborative System (Enterprise l nvelope mentation Resource Planning - ERP), inc luding training, Two year sub scription & service support. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SL-MLHCP-345089-CS-QCBS / Hiring a consulting firm for engineering designs and sup Institutional Development a Quality And Cost- Under Implement IDA / V3980 Post Open - National 307,000.00 0.00 2023-03-15 2023-03-17 2023-04-05 2023-05-19 2023-05-16 2023-06-16 2023-07-16 2023-08-20 2023-09-24 2024-09-23 ervision of construction work nd Legal Reform Based Selection ation s for administrative offices in Freetown, Bo, Makeni, Port-L oko and Kenema. SL-MLHCP-352571-CS-LCS / EXTERNAL AUDIT OF THE FIN ANCIAL STSTEMENTS OF THE Least Cost Selecti Pending Impleme IDA / V3980 Project Management Post Open - National 20,000.00 0.00 2023-03-27 2023-04-17 2023-05-31 2023-06-28 2023-07-28 2023-09-01 2023-10-06 2024-04-03 PROJECT PREPARATORY ADV on ntation ANCE FUNDS 2022 FOR THE SIERRA LEONE LAND ADMINI STRATION PROJECT (P177031 ). SL-MLHCP-355977-CS-CQS / Hiring of a consulting firm to Institutional Development a Consultant Qualifi Open - Internationa Under Implement IDA / V3980 Post 89,000.00 0.00 2023-04-27 2023-05-26 2023-05-18 2023-06-10 2023-07-01 2023-07-31 2023-09-04 2024-03-02 prepare drafting instructions nd Legal Reform cation Selection l ation for new national land laws an d regulations. SL-MLHCP-358145-CS-QCBS / Hiring of a consulting firm f Institutional Development a Quality And Cost- Open - Internationa Under Implement or the preparation of Corpora IDA / V3980 Post 200,000.00 0.00 2023-05-26 2023-04-24 2023-06-16 2023-06-11 2023-07-30 2023-08-27 2023-09-26 2023-10-31 2023-12-05 2024-12-04 nd Legal Reform Based Selection l ation te and migration strategies a s well as Business Plan for th e National Land Commission. Page 1 SL-MLHCP-364429-CS-QCBS / Hiring of a Consulting Firm t Recording and Registration Quality And Cost- Open - Internationa Under Implement IDA / V3980 Prior 2,740,000.00 0.00 2023-05-30 2023-06-26 2023-06-20 2023-06-26 2023-08-03 2023-08-31 2023-09-30 2023-11-04 2023-12-09 2024-12-08 o coordinate the recording a of Land Tenure Rights Based Selection l ation nd registration of land tenure rights. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SL-MLHCP-345181-CS-INDV / Hiring of an Individual Consul tant for development of Regu Institutional Development a Individual Consult Pending Impleme lations for the National Land IDA / V3980 Post Open - National 30,000.00 0.00 2023-03-20 2023-05-08 2023-05-29 2023-07-03 2023-12-30 nd Legal Reform ant Selection ntation Commission Act 2022 & Cust omary Land Rights Act 2022 and the required amendment s to the existing laws. SL-MLHCP-345253-CS-INDV / Procurement of Service to un Individual Consult Under Implement IDA / V3980 Project Management Post Open - National 20,000.00 0.00 2023-03-27 2023-06-12 2023-05-15 2023-06-05 2023-07-10 2024-01-06 dertake M&E studies (baselin ant Selection ation e/ customer satisfaction surv eys) SL-MLHCP-355950-CS-INDV / Hiring of an Individual Consul Institutional Development a Individual Consult Open - Internationa Under Implement tant to support the developm IDA / V3980 Post 20,000.00 0.00 2023-04-27 2023-05-26 2023-06-15 2023-07-06 2023-08-10 2024-02-06 nd Legal Reform ant Selection l ation ent of drafting instructions fo r land title registration land l aws & regulations. SL-MLHCP-355951-CS-INDV / Hiring of an Individual Consul Institutional Development a Individual Consult Open - Internationa Under Implement tant to support the developm IDA / V3980 Post 20,000.00 0.00 2023-04-27 2023-05-26 2023-06-15 2023-07-06 2023-08-10 2024-02-06 nd Legal Reform ant Selection l ation ent of Drafting Instructions fo r survey related land laws. Page 2 Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: February 1,2017]: Revision 1 of Updated Procurement Plan, June 21,2017] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 4. Reference to (if any) Project Operational/Procurement Manual: Project Operations Manual for World Bank Loan Project P158099 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] July 9, 2010 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contrac (Works) t for Prior Review Summary 1.86 4 No Post 1st of the NCB contrac (Goods) t for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 110,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. July 9, 2010 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Pakistan : PK: Punjab Tourism for Economic Growth Project PLAN General Information Country: Pakistan 2017-12-21 Bank’s Approval Date of the Original Procurement Plan: 2023-05-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P158099 GPN Date: 2020-08-11 Project Name: PK: Punjab Tourism for Economic Growth Project Loan / Credit No: IDA / 59820 Punjab Tourism for Economic Growth Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PK-PTEG-40086-CW-RFB / Fa 3. Public Investment Facilit Open - Internationa Single Stage - One E 11,386,666.0 2021-09-3 IDA / 59820 Prior Request for Bids 0.00 Canceled 2018-08-31 2018-09-05 2018-10-17 2018-11-01 2018-11-22 cilities & Amenities up-gradat y l nvelope 0 0 ion at sites PK-PTEG-40077-CW-RFB / Da 3. Public Investment Facilit Single Stage - One E 2019-04-1 rbar sahib road Kartarpur - R IDA / 59820 Prior Request for Bids Open - National 588,219.00 0.00 Canceled 2018-08-06 2018-08-11 2018-09-22 2018-10-07 2018-10-21 y nvelope 9 ehabilitation of secondary & t ertiary roads PK-PTEG-40079-CW-RFB / Ta 3. Public Investment Facilit Single Stage - One E 2019-04-2 xila- Toap Mankila- Mohra - R IDA / 59820 Post Request for Bids Open - National 1,437,133.00 0.00 Canceled 2018-08-13 2018-08-18 2018-09-29 2018-10-14 2018-10-28 y nvelope 6 ehabilitation of roads PK-PTEG-40080-CW-RFB / Na 3. Public Investment Facilit Open - Internationa Single Stage - One E 2019-03-2 nkana Sahib-Farooqabad roa IDA / 59820 Post Request for Bids 5,262,066.00 0.00 Canceled 2018-07-16 2018-07-21 2018-09-01 2018-09-16 2018-09-30 y l nvelope 9 d - Rehabilitation of road PK-PTEG-40081-CW-RFB / E 3. Public Investment Facilit Single Stage - One E 2018-12-1 minabad - Rori roads - Rehab IDA / 59820 Post Request for Bids Open - National 399,228.00 0.00 Canceled 2018-04-04 2018-04-09 2018-05-21 2018-06-05 2018-06-19 y nvelope 6 ilitation of roads PK-PTEG-40084-CW-RFB / Uc 3. Public Investment Facilit Single Stage - One E 2019-04-1 IDA / 59820 Post Request for Bids Open - National 1,199,457.00 0.00 Canceled 2018-08-06 2018-08-11 2018-09-20 2018-10-04 2018-10-18 h Sharif road - Rehabilitation y nvelope 6 of roads PK-PTEG-40085-CW-RFB / Gh 3. Public Investment Facilit Single Stage - One E 2019-03-2 ulam Farid Mithan Kot Rajanp IDA / 59820 Post Request for Bids Open - National 1,024,428.00 0.00 Canceled 2018-07-09 2018-07-14 2018-08-25 2018-09-09 2018-09-23 y nvelope 2 ur - Rehabilitation of roads PK-PTEG-194132-CW-RFB / R 3. Public Investment Facilit Single Stage - One E 4,346,514.4 2021-11-2 oads Rehabilitation in Punjab IDA / 59820 Post Request for Bids Open - National 6,000,000.00 Signed 2020-09-16 2020-09-17 2020-09-18 2020-09-17 2020-10-20 2020-10-20 2020-10-30 2020-11-10 2020-11-20 2020-12-10 y nvelope 3 0 (4 Packages, 6 Roads) PK-PTEG-238517-CW-RFB / R 3. Public Investment Facilit Single Stage - One E Other (with field f Under Imple 2022-08-1 ehabilitation of Roads - Uch S IDA / 59820 Post Request for Bids Open - National 3,300,000.00 0.00 2021-06-08 2021-06-30 2021-06-10 2021-07-14 2021-07-10 2021-08-03 2021-07-25 2021-08-22 y nvelope or explanation) mentation 7 harif & Channan Pir PK-PTEG-269512-CW-RFQ / T Request for Quota 3. Public Investment Facilit Request for Quota Single Stage - One E 2022-08-0 axila Museum - Design & Con IDA / 59820 Post Open - National tions (Non Bank-S 95,000.00 20,833.57 Signed 2021-12-31 2022-03-25 2022-02-04 2022-04-27 y tions nvelope 3 struction of Entrance Gate PD) Request for Bids - PK-PTEG-279723-CW-RFB / C 3. Public Investment Facilit Single Stage - One E Small Works SPD 2023-04-2 onstruction/Rehabilitation of IDA / 59820 Post Request for Bids Open - National 1,950,000.00 0.00 Canceled 2022-02-22 2022-03-25 2022-02-27 2022-03-29 2022-03-29 2022-04-13 2022-04-27 y nvelope (2 envelope proce 2 Toilet facilities at Heritage & ss) Tourist Sites Request for Bids - PK-PTEG-314721-CW-RFB / C 3. Public Investment Facilit Single Stage - One E Small Works SPD 2023-11-1 onstruction/Rehabilitation of IDA / 59820 Post Request for Bids Open - National 1,950,000.00 0.00 Canceled 2022-09-19 2022-09-24 2022-10-24 2022-11-08 2022-11-22 y nvelope (1 envelope proce 7 Toilet Blocks at Tourist sites - ss) Punjab PK-PTEG-330987-CW-RFB / R ehabilitation / Improvement 3. Public Investment Facilit Single Stage - One E Other (with field f Under Imple 2024-02-1 of Metaled Road from Lahore IDA / 59820 Post Request for Bids Open - National 1,000,000.00 0.00 2022-12-12 2023-02-20 2022-12-12 2023-02-24 2023-01-16 2023-03-27 2023-01-26 2023-04-12 2023-02-19 y nvelope or explanation) mentation 9 -Sheikhupura-Sargodha Road to Gurdwara Sucha Soda Dist rict Sheikhupura. PK-PTEG-331277-CW-RFB / R ehabilitation / Improvement 3. Public Investment Facilit Single Stage - One E Other (with field f 2024-02-1 of Metalled Road from Lahore IDA / 59820 Post Request for Bids Open - National 950,000.00 0.00 Canceled 2022-12-12 2023-02-20 2022-12-12 2023-02-24 2023-01-16 2023-01-26 2023-02-19 y nvelope or explanation) 9 -Sheikhupura-Sargodha Road to Mariumabad (Right Side of canal) District Sheikhupura PK-PTEG-331281-CW-RFB / R ehabilitation / Improvement 3. Public Investment Facilit Single Stage - One E Other (with field f 2024-08-1 IDA / 59820 Post Request for Bids Open - National 8,250,000.00 0.00 Signed 2022-12-12 2023-02-20 2022-12-12 2023-02-24 2023-01-16 2023-03-27 2023-01-26 2023-04-10 2023-02-19 of Road from Kallar Kahar to y nvelope or explanation) 7 Manara District Boundary Ch akwal District Chakwal PK-PTEG-331284-CW-RFB / C 3. Public Investment Facilit Single Stage - One E Other (with field f Pending Imp 2024-08-1 onstruction of Rohtas Fort By IDA / 59820 Post Request for Bids Open - National 8,700,000.00 0.00 2022-12-12 2022-12-12 2023-01-16 2023-01-26 2023-02-19 y nvelope or explanation) lementation 7 pass Road District Jhelum. Request for Bids - PK-PTEG-333401-CW-RFB / C 3. Public Investment Facilit Single Stage - One E Small Works SPD Under Imple 2024-03-1 onstruction/Rehabilitation of IDA / 59820 Post Request for Bids Open - National 1,950,000.00 0.00 2022-12-23 2023-03-20 2022-12-28 2023-04-02 2023-02-01 2023-02-11 2023-03-19 y nvelope (1 envelope proce mentation 8 Toilet Blocks at Tourist sites - ss) Punjab Request for Bids - PK-PTEG-360704-CW-RFB / C 2. Private Investment and Single Stage - One E Small Works SPD Under Imple 2024-07-1 onservation & Rehabilitation IDA / 59820 Post Request for Bids Open - National 610,000.00 0.00 2023-05-09 2023-05-17 2023-05-09 2023-05-17 2023-06-03 2023-06-10 2023-06-22 Entrepreneurship Promotion nvelope (1 envelope proce mentation 5 of Buildings/Façade Work on ss) West Side Request for Bids - PK-PTEG-360710-CW-RFB / C 2. Private Investment and Single Stage - One E Small Works SPD Under Imple 2024-07-1 onservation & Rehabilitation IDA / 59820 Post Request for Bids Open - National 780,000.00 0.00 2023-05-09 2023-05-17 2023-05-09 2023-05-17 2023-06-03 2023-06-10 2023-06-22 Entrepreneurship Promotion nvelope (1 envelope proce mentation 5 of Buildings/Façade Work on ss) East Side-1 Request for Bids - PK-PTEG-360711-CW-RFB / C 2. Private Investment and Single Stage - One E Small Works SPD Under Imple 2024-07-1 onservation & Rehabilitation IDA / 59820 Post Request for Bids Open - National 780,000.00 0.00 2023-05-09 2023-05-17 2023-05-09 2023-05-17 2023-06-03 2023-06-10 2023-06-22 Entrepreneurship Promotion nvelope (1 envelope proce mentation 5 of Buildings/Façade Work On ss) East Side-2 PK-PTEG-360715-CW-RFB / C Request for Bids - onservation of Bhatti Gate: 2. Private Investment and Single Stage - One E Small Works SPD Under Imple 2024-07-1 Façade Rehabilitation of Main IDA / 59820 Post Request for Bids Open - National 545,000.00 0.00 2023-05-09 2023-05-17 2023-05-09 2023-05-17 2023-06-03 2023-06-10 2023-06-22 Entrepreneurship Promotion nvelope (1 envelope proce mentation 5 Trail, Relocation of Water Filt ss) ration Plant and Establishme nt of Parking Area Page 1 PK-PTEG-363215-CW-RFB / R ehabilitation / Improvement of Metaled Road from Lahore 2. Private Investment and Single Stage - One E Other (with field f Pending Imp 2024-07-1 IDA / 59820 Post Request for Bids Open - National 950,000.00 0.00 2023-05-23 2023-05-25 2023-06-15 2023-06-25 2023-07-15 -Sheikhupura-Sargodha Road Entrepreneurship Promotion nvelope or explanation) lementation 4 to Mariumabad Length 4.10K M (Right Side of canal) Distri ct Sheikhupura GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PTEG-32430-GO-RFQ / Ve 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 40,000.00 0.00 Canceled 2018-02-05 2018-04-02 2018-09-29 hicles Procurement onitoring and Evaluation tions nvelope PK-PTEG-32431-GO-RFQ / Of 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 58,650.00 23,294.21 Signed 2018-02-04 2018-04-01 2018-05-18 2018-09-28 fice Furniture onitoring and Evaluation tions nvelope PK-PTEG-40059-GO-RFQ / Po 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 9,600.00 6,930.48 Signed 2018-03-03 2018-04-28 2018-06-01 2018-10-25 wer Generator onitoring and Evaluation tions nvelope PK-PTEG-40060-GO-RFQ / Of fice Equipment 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 17,000.00 5,280.80 Signed 2018-01-13 2018-06-30 2018-03-10 2018-06-01 2018-09-06 (Telephone Exchange, CCTV, onitoring and Evaluation tions nvelope Air conditioners, refrigerators etc.) PK-PTEG-40065-GO-RFQ / M 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 600.00 0.00 Canceled 2018-01-24 2018-03-21 2018-09-17 otor Bike onitoring and Evaluation tions nvelope PK-PTEG-40054-GO-RFQ / IT Equipment 4. Project Management, M Request for Quota Single Stage - One E (Laptops, Desktops, Server, P IDA / 59820 Post Open - National 39,000.00 22,115.80 Signed 2017-12-30 2018-02-14 2018-02-24 2018-06-01 2018-08-23 onitoring and Evaluation tions nvelope rinters, Scanner, Multimedia Projector etc.) PK-PTEG-40058-GO-RFQ / Ne 4. Project Management, M Request for Quota Single Stage - One E tworking for IT connectivity & IDA / 59820 Post Open - National 7,000.00 2,693.07 Signed 2018-02-25 2018-04-22 2018-06-01 2018-10-19 onitoring and Evaluation tions nvelope Telephone Exchange PK-PTEG-40067-GO-RFB / Hu 1. Policy, Institutions and Open - Internationa Single Stage - One E IDA / 59820 Post Request for Bids 200,000.00 0.00 Canceled 2018-04-16 2018-04-21 2018-06-02 2018-06-18 2018-07-02 2018-12-29 man Resource Information Sy Governance for Tourism Dev l nvelope stem elopment PK-PTEG-93484-GO-RFB / To 1. Policy, Institutions and Open - Internationa Single Stage - One E IDA / 59820 Prior Request for Bids 3,500,000.00 0.00 Canceled 2019-02-04 2019-02-09 2019-03-23 2019-04-22 2019-05-27 2019-11-23 urism Mobile Application Governance for Tourism Dev l nvelope elopment PK-PTEG-151606-GO-RFQ / P urchase of new IT Equipment and software for project staf 4. Project Management, M Request for Quota Single Stage - One E Pending Impl f. IDA / 59820 Post Open - National 15,000.00 0.00 2019-12-24 2019-12-28 2020-01-31 onitoring and Evaluation tions nvelope ementation 7 Laptops Core i-5 8GB ram 1 3.3" Screen size 256/512 GB HDD Windows 10 + MS Office 1 Tablet PK-PTEG-161181-GO-RFQ / I 4. Project Management, M Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 17,300.00 0.00 2020-03-14 2020-05-09 2020-11-05 T Equipment onitoring and Evaluation tions nvelope ementation PK-PTEG-161189-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 11,800.00 0.00 2020-03-14 2020-05-09 2020-11-05 ffice Equipment onitoring and Evaluation tions nvelope ementation PK-PTEG-161192-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 16,000.00 10,960.00 Signed 2020-03-14 2020-03-17 2020-05-09 2020-03-21 2020-11-05 ffice Furniture onitoring and Evaluation tions nvelope PK-PTEG-186934-GO-RFB / Si 3. Public Investment Facilit Single Stage - One E Under Imple IDA / 59820 Post Request for Bids Open - National 1,000,000.00 0.00 2020-08-13 2020-08-31 2020-08-18 2020-09-03 2020-09-29 2020-10-05 2020-10-14 2020-11-04 2023-10-20 gnboards - Supply and Install y nvelope mentation ation (FA) PK-PTEG-200114-GO-RFQ / P 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Limited 2,500.00 2,580.69 Signed 2020-10-20 2020-10-26 2020-11-05 2020-10-31 2020-11-12 rofessional Camera y tions nvelope PK-PTEG-200602-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 36,000.00 19,551.99 Signed 2020-10-27 2020-10-28 2020-11-26 2020-11-12 2021-02-24 ffice Furniture - Tourism Dep onitoring and Evaluation tions nvelope artment PK-PTEG-200605-GO-RFQ / I 4. Project Management, M Request for Quota Single Stage - One E Under Imple IDA / 59820 Post Open - National 25,200.00 0.00 2020-10-30 2020-10-28 2020-12-11 2021-02-09 T Equipment - Tourism Depar onitoring and Evaluation tions nvelope mentation tment PK-PTEG-200606-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 15,000.00 12,992.20 Signed 2020-10-31 2020-11-19 2020-12-15 2020-12-11 2021-02-13 ffice Equipment - Tourism De onitoring and Evaluation tions nvelope partment PK-PTEG-230268-GO-RFQ / G 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 150,000.00 163,734.37 Signed 2021-04-30 2021-05-07 2021-06-04 2021-06-10 2021-12-01 olf Carts for Heritage Sites y tions nvelope PK-PTEG-230269-GO-RFQ / H 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 70,000.00 34,537.37 Signed 2021-05-01 2021-05-07 2021-06-05 2021-06-23 2021-12-02 eritage Rikshaws y tions nvelope PK-PTEG-230271-GO-RFQ / C 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 100,000.00 80,079.55 Signed 2021-05-01 2021-05-07 2021-06-05 2021-06-08 2021-12-02 oaster - Shuttle Bus y tions nvelope PK-PTEG-228308-GO-RFQ / S 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 95,000.00 38,012.80 Signed 2021-05-01 2021-09-03 2021-06-05 2021-10-29 2021-12-02 MD for Taxila Museum y tions nvelope PK-PTEG-231715-GO-RFB / S 3. Public Investment Facilit Single Stage - One E IDA / 59820 Post Request for Bids Open - National 700,000.00 207,024.82 Terminated 2021-05-05 2021-08-04 2021-05-10 2021-08-05 2021-06-09 2021-09-02 2021-06-23 2021-09-23 2021-07-14 2022-01-02 2022-01-10 olid Waste Management Equi y nvelope pment PK-PTEG-256404-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 35,000.00 34,327.89 Signed 2021-10-15 2021-10-07 2021-11-16 2021-10-27 2022-05-15 ffice Furniture - Tourism Dep onitoring and Evaluation tions nvelope artment PK-PTEG-256408-GO-RFQ / O ffice Equipment - Tourism De 4. Project Management, M Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 24,000.00 0.00 2021-10-15 2021-11-19 2022-05-18 partment onitoring and Evaluation tions nvelope ementation DSLR, AC, Generator 15 KV, Refrigirator, Fax Machine PK-PTEG-256411-GO-RFQ / I T Equipment - Tourism Depar 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 25,000.00 8,175.37 Signed 2021-10-15 2021-10-11 2021-11-19 2021-10-29 2022-05-18 tment onitoring and Evaluation tions nvelope LEDs, Printers, Smart Phones , Video Conferencing System Page 2 PK-PTEG-271627-GO-RFB / S olid Waste Management Equi 3. Public Investment Facilit Single Stage - One E pment IDA / 59820 Post Request for Bids Open - National 200,000.00 148,710.58 Signed 2022-01-05 2022-01-10 2022-01-07 2022-01-13 2022-02-06 2022-02-11 2022-02-13 2022-02-22 2022-02-27 2022-03-25 2022-08-26 y nvelope 10 Mini Tippers 05 Mechanical Sweepers (Tra ctor driven) PK-PTEG-222318-GO-RFB / G 3. Public Investment Facilit Single Stage - One E IDA / 59820 Post Request for Bids Open - National 165,000.00 0.00 Canceled 2021-03-10 2021-03-15 2021-04-14 2021-04-24 2021-05-15 2021-11-11 olf Carts & Heritage Rikshaw y nvelope s PK-PTEG-227444-GO-RFB / S 3. Public Investment Facilit Single Stage - One E olar Power Energy System for IDA / 59820 Post Request for Bids Open - National 410,000.00 0.00 Canceled 2021-04-02 2021-04-06 2021-04-04 2021-04-08 2021-05-06 2021-05-21 2021-06-16 2022-06-11 y nvelope Heritage Sites PK-PTEG-275532-GO-RFB / D 3. Public Investment Facilit Open - Internationa Single Stage - One E IDA / 59820 Prior Request for Bids 3,000,000.00 0.00 Canceled 2022-02-11 2022-05-06 2022-02-16 2022-05-07 2022-04-02 2022-06-20 2022-04-16 2022-08-25 2022-05-21 2022-11-17 ouble Decker Buses - 9 buses y l nvelope PK-PTEG-283628-GO-RFB / P 3. Public Investment Facilit Single Stage - One E re-fabricated Containers for IDA / 59820 Post Request for Bids Open - National 240,000.00 0.00 Canceled 2022-03-18 2022-03-23 2022-04-22 2022-04-29 2022-05-20 2022-11-16 y nvelope Rescue Services - Murree Im plementation Plan PK-PTEG-283630-GO-RFB / R 3. Public Investment Facilit Single Stage - One E ecovery Vehicles for Rescue IDA / 59820 Post Request for Bids Open - National 400,000.00 0.00 Canceled 2022-03-18 2022-03-23 2022-04-22 2022-04-29 2022-05-20 2022-11-16 y nvelope Services - Murree Implement ation Plan PK-PTEG-283631-GO-RFB / A 3. Public Investment Facilit Single Stage - One E mbulances with fabrication R IDA / 59820 Post Request for Bids Open - National 600,000.00 0.00 Canceled 2022-03-18 2022-03-23 2022-04-22 2022-05-06 2022-05-27 2022-11-23 y nvelope escue Services - Murree Impl ementation Plan PK-PTEG-283632-GO-RFB / R 3. Public Investment Facilit Single Stage - One E escue Equipment for Rescue IDA / 59820 Post Request for Bids Open - National 300,000.00 0.00 Canceled 2022-03-18 2022-03-23 2022-04-22 2022-05-06 2022-05-27 2022-11-23 y nvelope Services - Murree Implement ation Plan PK-PTEG-283634-GO-RFQ / R 3. Public Investment Facilit Request for Quota Single Stage - One E ehabilitation of Takht-e-Babri IDA / 59820 Post Open - National 100,000.00 32,388.30 Signed 2022-03-16 2022-03-16 2022-04-16 2022-03-30 2022-06-15 y tions nvelope , Kalar Kahar PK-PTEG-286749-GO-RFQ / A 3. Public Investment Facilit Request for Quota Single Stage - One E rcheological Laboratory Equi IDA / 59820 Post Open - National 68,000.00 47,017.08 Signed 2022-03-30 2022-05-16 2022-05-05 2022-06-21 2022-11-01 y tions nvelope pment - Directorate of Arche ology PK-PTEG-293035-GO-RFB / V 4. Project Management, M Single Stage - One E Pending Impl ehicles for PTEGP (PMU-Touri IDA / 59820 Post Request for Bids Open - National 750,000.00 0.00 2022-05-09 2022-05-14 2022-06-11 2022-06-18 2022-07-02 2023-06-27 onitoring and Evaluation nvelope ementation sm Department and C&W) & IDAP PK-PTEG-295160-GO-RFB / P 3. Public Investment Facilit Single Stage - One E rocurement of Architectural a IDA / 59820 Post Request for Bids Open - National 725,000.00 0.00 Canceled 2022-06-26 2022-07-01 2022-07-31 2022-08-14 2022-09-11 2023-03-10 y nvelope nd Civil Engineering related S oftware PK-PTEG-295161-GO-RFB / P rocurement of Computer Equ 3. Public Investment Facilit Single Stage - One E Pending Impl IDA / 59820 Post Request for Bids Open - National 795,000.00 0.00 2022-06-27 2022-07-02 2022-08-01 2022-08-15 2022-09-19 2023-03-18 ip. Drones, Terrestrial Laser y nvelope ementation Scanner & Total Station for I DAP PK-PTEG-302801-GO-RFQ / S upply of Uniforms and relate 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 70,000.00 0.00 Signed 2022-07-18 2022-07-18 2022-08-20 2023-02-16 d accessories for Tourism Sq y tions nvelope uad - Tourism Department PK-PTEG-302808-GO-RFB / S upply & Installation of Revers 3. Public Investment Facilit Single Stage - One E IDA / 59820 Post Request for Bids Open - National 500,000.00 0.00 Canceled 2022-07-25 2022-08-31 2022-07-30 2022-09-02 2022-08-29 2022-09-12 2022-10-10 2023-04-08 ible Tuck shops & Washroom y nvelope s - Tourist sites Punjab PK-PTEG-302810-GO-RFQ / S 3. Public Investment Facilit Request for Quota Single Stage - One E Pending Impl upply of Garbage Collection IDA / 59820 Post Open - National 72,000.00 0.00 2022-07-23 2022-09-17 2023-03-16 y tions nvelope ementation Carts - Tourist Sites Punjab PK-PTEG-303027-GO-RFQ / S 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple upply & Installation of SMD S IDA / 59820 Post Open - National 50,000.00 0.00 2022-07-20 2022-07-15 2022-08-17 2022-10-16 y tions nvelope mentation creens - Murree District PK-PTEG-317860-GO-RFQ / P unjab Tourism Squad - Procur 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 96,000.00 0.00 Signed 2022-10-05 2022-11-01 2023-01-30 ement of equipment for cap y tions nvelope acity building of PTS PK-PTEG-319157-GO-RFB / S upply & Installation of Solar P ower System (Jahangir Tomb, Lahore, Shal 3. Public Investment Facilit Single Stage - One E amar Gardens, Lahore, Hiran IDA / 59820 Post Request for Bids Open - National 430,000.00 0.00 Canceled 2022-10-03 2022-11-10 2022-10-08 2022-11-11 2022-11-19 2022-12-19 2023-01-23 2023-07-22 y nvelope Minar, Sheikhupura, Rohtas F ort, Jhelum, Taxila Museum, Taxila Rawalpindi, Wah Gard ens Wah Rawalpindi & Harap pa Museum & Site, Sahiwal ) PK-PTEG-324234-GO-RFB / S upply & Installation of Revers 3. Public Investment Facilit Single Stage - One E IDA / 59820 Post Request for Bids Open - National 550,000.00 0.00 Signed 2022-11-01 2022-11-10 2022-11-02 2022-11-11 2022-12-02 2022-12-13 2022-12-05 2022-12-20 2022-12-11 2023-03-11 ible Tuck shops & Washroom y nvelope s - Tourist sites Punjab PK-PTEG-335666-GO-RFB / S 3. Public Investment Facilit Single Stage - One E Under Imple upply & Installation of Solar P IDA / 59820 Post Request for Bids Open - National 500,000.00 0.00 2023-01-16 2023-01-17 2023-01-21 2023-03-04 2023-02-27 2023-04-03 2023-05-08 2023-08-06 y nvelope mentation ower System PK-PTEG-351380-GO-RFB / P 3. Public Investment Facilit Open - Internationa Single Stage - One E Under Imple rocurement of 06-Double De IDA / 59820 Post Request for Bids 2,000,000.00 0.00 2023-03-27 2023-05-01 2023-04-01 2023-05-20 2023-05-13 2023-05-28 2023-06-03 2023-11-30 y l nvelope mentation cker Bus (Diesel Hybrid) PK-PTEG-351387-GO-RFQ / P 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple IDA / 59820 Post Open - National 575,000.00 0.00 2023-03-31 2023-04-28 2023-07-27 rocurement of 05-Coasters ( y tions nvelope mentation Diesel) PK-PTEG-351403-GO-RFQ / P 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple IDA / 59820 Post Open - National 400,000.00 0.00 2023-03-31 2023-04-30 2023-07-29 rocurement of 07-VANS y tions nvelope mentation PK-PTEG-351418-GO-RFQ / F 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple urniture and Inverter Floor St IDA / 59820 Post Open - National 53,000.00 0.00 2023-03-31 2023-04-16 2023-06-15 y tions nvelope mentation anding Cabinet A.C for Lahor e Museum Page 3 PK-PTEG-351405-GO-RFQ / P rocurement of I.T. Equipment for Lahore Museum Lot-1: Desktop Computer, est 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple imated budget=USD$=15,00 IDA / 59820 Post Open - National 50,000.00 0.00 2023-03-31 2023-04-27 2023-07-26 y tions nvelope mentation 0/- Lot-2: Laptop, estimated bud get=USD$=12,00/- Lot-3: Server 96TB storage, e stimated budget=USD$=33, 800/- PK-PTEG-353673-GO-RFQ / P 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple rocurement of Office Equipm IDA / 59820 Post Open - National 15,000.00 0.00 2023-03-29 2023-05-02 2023-07-31 y tions nvelope mentation ent for Lahore Museum PK-PTEG-355575-GO-RFQ / P ROCUREMENT OF EQUIPMEN T FOR AUDIO-VIDEOGRAPHY 3. Public Investment Facilit Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 90,000.00 0.00 2023-04-15 2023-05-10 2023-08-08 STUDIO, PORTABLE PUBLIC A y tions nvelope ementation DDRESS SYSTEM AND WEBIN AR ROOM FOR LAHORE MUSE UM PK-PTEG-363800-GO-RFQ / E QUIPMENT (LED) LIGHTS FOR 2. Private Investment and Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 16,000.00 0.00 2023-05-29 2023-06-29 2023-09-27 ILLUMINATION OF FRONT ELE Entrepreneurship Promotion tions nvelope ementation VATION FOR LAHORE MUSEU M BUILDING PK-PTEG-363804-GO-RFQ / P ROCUREMENT OF GOLF CART 2. Private Investment and Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 95,000.00 0.00 2023-05-29 2023-06-21 2023-09-19 FOR TDCP AT CHANGA MANG Entrepreneurship Promotion tions nvelope ementation A RESORT, LAHORE PK-PTEG-365225-GO-RFB / P 1. Policy, Institutions and rocurement of 11-Seater Golf Single Stage - One E Pending Impl IDA / 59820 Governance for Tourism Dev Post Request for Bids Open - National 300,000.00 0.00 2023-06-05 2023-06-07 2023-07-03 2023-07-08 2023-07-19 2024-01-15 Carts for Walled City Lahore nvelope ementation elopment Authority (WCLA) PK-PTEG-365229-GO-RFQ / P 1. Policy, Institutions and Request for Quota Single Stage - One E Pending Impl rocurement of Coaster for W IDA / 59820 Governance for Tourism Dev Post Open - National 120,000.00 0.00 2023-06-10 2023-07-03 2023-12-30 tions nvelope ementation alled City Lahore Authority ( elopment WCLA) PK-PTEG-365231-GO-RFQ / P 1. Policy, Institutions and Request for Quota Single Stage - One E Pending Impl rocurement of High Roof-VAN IDA / 59820 Governance for Tourism Dev Post Open - National 120,000.00 0.00 2023-06-07 2023-07-01 2023-12-28 tions nvelope ementation S for Walled City Lahore Auth elopment ority (WCLA) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PTEG-48673-NC-RFQ / Ev 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 30,000.00 27,702.75 Signed 2018-02-14 2018-02-15 2018-02-26 2018-02-13 2018-03-08 ent Management Firm - Proje onitoring and Evaluation tions nvelope ct Launch PK-PTEG-91147-NC-RFQ / Su 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 35,000.00 10,591.35 Signed 2019-01-12 2019-02-13 2019-03-09 2019-04-22 2019-09-05 rvey Firm for Data collection onitoring and Evaluation tions nvelope PK-PTEG-103229-NC-RFQ / T 4. Project Management, M Request for Quota Single Stage - One E ourism Sector regulation and IDA / 59820 Post Open - National 20,000.00 0.00 Canceled 2019-03-04 2019-04-29 2019-06-30 onitoring and Evaluation tions nvelope Inspection Mapping Exercise -4 Months PK-PTEG-103234-NC-RFQ / D ocumentary Preparation of K 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 100,000.00 0.00 Canceled 2019-03-10 2019-05-05 2019-06-30 artarpur site (Non Consultanc onitoring and Evaluation tions nvelope y Services) 2-Months PK-PTEG-103260-NC-RFQ / T 4. Project Management, M Request for Quota Single Stage - One E raining need assessment of S IDA / 59820 Post Open - National 100,000.00 0.00 Canceled 2019-03-04 2019-04-29 2019-06-30 onitoring and Evaluation tions nvelope kill training 4-Months PK-PTEG-141301-NC-DIR / Pr 4. Project Management, M Pending Impl ocurement of Planning & Mon IDA / 59820 Post Direct Selection Direct 1,260.00 0.00 2019-10-21 2019-10-26 2019-11-08 2019-11-18 onitoring and Evaluation ementation itoring Software (SMARTSHEE T) PK-PTEG-140344-NC-DIR / H all and Auditorium facility ch 1. Policy, Institutions and arges for conduct of Lahore I IDA / 59820 Governance for Tourism Dev Post Direct Selection Direct 50,000.00 0.00 Canceled 2019-10-23 2019-10-28 2019-12-07 2019-12-28 nternational Tourism Expo (LI elopment TE) at Expo center Lahore PK-PTEG-134818-NC-RFQ / H 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 20,000.00 0.00 Canceled 2019-09-19 2019-09-24 2019-09-27 iring of Firm for Event Manag onitoring and Evaluation tions nvelope ement PK-PTEG-159994-NC-RFQ / E 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 12,000.00 4,442.20 Signed 2020-02-24 2020-02-25 2020-03-18 2020-03-18 2022-03-08 nvironment Laboratory y tions nvelope PK-PTEG-300757-NC-RFQ / T 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple opographic Survey of Archeol IDA / 59820 Post Open - National 100,000.00 0.00 2022-07-01 2022-07-18 2022-08-05 2023-02-01 y tions nvelope mentation ogical Sites PK-PTEG-306845-NC-RFB / Hi 1. Policy, Institutions and ring of Training Service Provi Single Stage - One E IDA / 59820 Governance for Tourism Dev Post Request for Bids Open - National 2,000,000.00 0.00 Canceled 2022-08-04 2022-10-03 2022-08-09 2022-09-08 2022-09-28 2022-10-26 2023-04-24 ders (TSPs) for Skills Develop nvelope elopment ment - Tourism Sector Punja b CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PTEG-32421-CS-QCBS / H 3. Public Investment Facilit UN Agencies (Dire iring of Heritage Firm IDA / 59820 Prior Direct 500,000.00 2,834,843.00 Signed 2018-01-27 2018-02-19 2021-01-29 y ct) UNESCO PK-PTEG-32423-CS-QCBS / H 1. Policy, Institutions and Quality And Cost- Open - Internationa Under Implement iring of firm for Legal & Regul IDA / 59820 Governance for Tourism Dev Prior 750,000.00 0.00 2017-12-25 2018-07-24 2018-01-15 2018-02-28 2018-03-28 2018-04-27 2018-06-01 2018-07-06 2019-07-06 Based Selection l ation atory Review elopment Page 4 PK-PTEG-32425-CS-CQS / Int 4. Project Management, M Least Cost Selecti ernal Audit Firm IDA / 59820 Post Open - National 150,000.00 0.00 Canceled 2017-12-18 2018-01-08 2018-02-21 2018-03-21 2018-04-20 2018-05-25 2018-06-29 2022-12-30 onitoring and Evaluation on Estimated cost for 5 years PK-PTEG-32422-CS-QCBS / Fi 2. Private Investment and Quality And Cost- Open - Internationa IDA / 59820 Post 1,500,000.00 0.00 Canceled 2018-01-31 2018-12-28 2018-02-16 2018-03-09 2018-04-23 2018-05-08 2018-05-22 2018-06-05 2020-10-13 rm Hiring for Skills Developm Entrepreneurship Promotion Based Selection l ent PK-PTEG-32418-CS-QCBS / S 3. Public Investment Facilit Quality And Cost- Open - Internationa upervision & Quality Assuran IDA / 59820 Prior 952,380.00 94,799.46 Signed 2018-01-15 2019-02-11 2018-01-30 2019-02-11 2018-02-27 2020-05-08 2018-04-01 2020-04-15 2018-04-17 2020-05-09 2018-05-08 2020-07-17 2018-05-22 2020-07-09 2020-09-29 y Based Selection l ce Firm Civil Works consultant firm - PISC PK-PTEG-32427-CS-CQS / Up 1. Policy, Institutions and Quality And Cost- Open - Internationa gradation of Existing Institute IDA / 59820 Governance for Tourism Dev Prior 750,000.00 0.00 Canceled 2018-02-01 2018-02-16 2018-03-12 2018-04-24 2018-05-09 2018-05-23 2018-06-06 2019-06-06 Based Selection l s - Hiring of firm elopment PK-PTEG-51948-CS-CQS / Int 4. Project Management, M Consultant Qualifi IDA / 59820 Post Open - National 150,000.00 0.00 Canceled 2018-03-06 2018-05-01 2018-03-26 2018-05-10 2018-05-17 2018-06-14 2023-04-30 ernal Audit Firm - 5 Years Co onitoring and Evaluation cation Selection ntract PK-PTEG-64589-CS-CQS / Up 1. Policy, Institutions and Consultant Qualifi gradation of Existing Institute IDA / 59820 Governance for Tourism Dev Post Open - National 400,000.00 0.00 Canceled 2018-06-11 2018-06-19 2018-07-02 2018-08-15 2018-09-14 2018-10-19 2019-06-28 cation Selection s - Restructuring of TDCP elopment PK-PTEG-93553-CS-QCBS / R 1. Policy, Institutions and Quality And Cost- IDA / 59820 Post Open - National 500,000.00 0.00 Canceled 2019-01-14 2019-01-08 2019-02-04 2019-02-13 2019-03-20 2019-04-17 2019-05-17 2019-06-21 2019-07-26 2020-07-25 e-structuring of TDCP Governance for Tourism Dev Based Selection elopment PK-PTEG-110939-CS-CQS / D 4. Project Management, M Consultant Qualifi Under Implement ocumentary Preparation of K IDA / 59820 Post Open - National 100,000.00 0.00 2019-04-22 2019-05-10 2019-05-13 2019-07-08 2019-06-26 2019-08-21 2019-07-26 2019-08-30 2020-04-30 onitoring and Evaluation cation Selection ation artarpur site PK-PTEG-110942-CS-CQS / T 4. Project Management, M Consultant Qualifi Under Implement IDA / 59820 Post Open - National 100,000.00 0.00 2019-04-22 2019-05-10 2019-05-13 2019-07-08 2019-06-26 2019-07-26 2019-08-30 2020-04-30 raining need assessment of S onitoring and Evaluation cation Selection ation kill training PK-PTEG-128723-CS-LCS / Hi 4. Project Management, M Least Cost Selecti IDA / 59820 Post Open - National 250,000.00 0.00 Canceled 2019-08-25 2020-03-09 2019-09-15 2019-10-29 2019-11-26 2019-12-26 2020-01-30 2020-03-05 2023-03-05 ring of Media Firm onitoring and Evaluation on PK-PTEG-103226-CS-LCS / Hi 4. Project Management, M Least Cost Selecti IDA / 59820 Post Open - National 150,000.00 0.00 Canceled 2019-02-27 2019-03-08 2019-03-20 2019-03-11 2019-05-03 2019-07-19 2019-05-31 2019-08-23 2019-06-30 2019-08-04 2019-09-08 2022-06-30 ring of Internal Audit Firm 5- onitoring and Evaluation on Years PK-PTEG-32414-CS-CQS / Me 2. Private Investment and Consultant Qualifi IDA / 59820 Prior Open - National 2,500,000.00 0.00 Canceled 2017-11-20 2018-09-20 2017-12-11 2018-01-24 2018-02-23 2018-03-30 2020-11-23 dia Firm hiring Entrepreneurship Promotion cation Selection PK-PTEG-163250-CS-QCBS / I 1. Policy, Institutions and Quality And Cost- IDA / 59820 Post Open - National 300,000.00 188,305.86 Signed 2020-03-13 2020-03-09 2020-04-02 2020-03-13 2020-04-19 2020-07-29 2020-05-19 2020-08-31 2020-05-29 2020-09-17 2020-06-15 2020-10-20 2020-07-06 2020-12-17 2021-07-01 SMP Qila Kohna Qasim Bagh Governance for Tourism Dev Based Selection elopment PK-PTEG-164014-CS-QCBS / 1. Policy, Institutions and Quality And Cost- IDA / 59820 Post Open - National 250,000.00 544,997.13 Signed 2020-03-12 2020-03-11 2020-04-02 2020-03-13 2020-05-16 2020-07-13 2020-06-13 2020-08-25 2020-07-13 2020-09-16 2020-08-17 2020-10-05 2020-09-21 2021-02-04 2023-09-06 Media Firm Hiring Governance for Tourism Dev Based Selection elopment PK-PTEG-183974-CS-QCBS / Destination Investment & Ma 1. Policy, Institutions and Quality And Cost- Open - Internationa nagement Plans (DIMPs) Con IDA / 59820 Governance for Tourism Dev Prior 3,000,000.00 614,175.00 Signed 2020-07-16 2020-07-24 2020-07-26 2020-08-28 2020-08-30 2020-11-26 2020-09-27 2021-01-11 2020-10-12 2021-03-03 2020-11-02 2021-03-16 2020-12-07 2021-05-15 2022-12-07 Based Selection l sultancy Services - elopment IDC (Framework contract) PK-PTEG-206682-CS-CQS / E 3. Public Investment Facilit Consultant Qualifi Under Implement nvironment Impact Assessme IDA / 59820 Post Open - National 100,000.00 0.00 2020-12-01 2020-12-15 2020-12-16 2020-12-30 2021-01-06 2021-02-11 2021-01-13 2021-01-25 2022-01-25 y cation Selection ation nt Services PK-PTEG-223666-CS-QCBS / 3. Public Investment Facilit Quality And Cost- Open - Internationa Pending Impleme Taxila Museum Upgradation - IDA / 59820 Post 450,000.00 0.00 2021-03-19 2021-04-03 2021-04-20 2021-05-18 2021-06-01 2021-06-22 2021-07-13 2022-07-13 y Based Selection l ntation Consulting Firm PK-PTEG-228305-CS-CQS / A 3. Public Investment Facilit Consultant Qualifi Pending Impleme rchitectural Firm for Design o IDA / 59820 Post Open - National 100,000.00 0.00 2021-04-11 2021-04-26 2021-05-17 2021-05-24 2021-06-07 2021-12-04 y cation Selection ntation f New Museum at Harappa PK-PTEG-246068-CS-QCBS / 3. Public Investment Facilit Quality And Cost- Under Implement Design Review and Supervisi IDA / 59820 Post Open - National 550,000.00 0.00 2021-08-02 2021-08-02 2021-08-17 2021-09-07 2021-10-05 2021-10-19 2021-11-02 2021-11-23 2022-11-23 y Based Selection ation on Firm (Roads & Buildings) PK-PTEG-267389-CS-CQS / S 3. Public Investment Facilit Consultant Qualifi Under Implement olar Energy - Design & Super IDA / 59820 Post Open - National 45,000.00 0.00 2021-12-13 2021-12-14 2021-12-28 2022-01-20 2022-01-26 2022-04-05 2022-02-09 2022-02-23 2023-02-18 y cation Selection ation vision Firm PK-PTEG-295159-CS-CQS / T 3. Public Investment Facilit Consultant Qualifi Under Implement opographic & Utilities Survey IDA / 59820 Post Open - National 100,000.00 0.00 2022-05-20 2022-05-30 2022-06-04 2022-07-03 2022-07-17 2022-08-14 2023-02-10 y cation Selection ation - IDAP Hiran Minar PK-PTEG-295158-CS-QCBS / Services for Preparation of As 3. Public Investment Facilit Consultant Qualifi Pending Impleme -Built Drawings & Scan-Base IDA / 59820 Post Open - National 175,000.00 0.00 2022-06-26 2022-07-17 2022-08-14 2022-08-28 2022-09-11 2023-03-10 y cation Selection ntation d 3D Models - IDAP Hiran Minar, Rohtas Fort & Ta xila PK-PTEG-320789-CS-CQS / D ESIGN AND RESIDENT SUPER 3. Public Investment Facilit Consultant Qualifi Under Implement VISION OF URBAN REHABILIT IDA / 59820 Post Open - National 150,000.00 0.00 2022-10-12 2022-11-10 2022-10-22 2022-12-28 2022-11-16 2022-12-01 2023-01-05 2024-10-31 y cation Selection ation ATION OF FAÇADE AND ESTA BLISHMENT OF PARKING ARE A - BHATTI GATE PK-PTEG-320794-CS-CQS / D ESIGN AND RESIDENT SUPER 3. Public Investment Facilit Consultant Qualifi Under Implement VISION OF URBAN REHABILIT IDA / 59820 Post Open - National 250,000.00 0.00 2022-10-12 2022-11-10 2022-10-27 2022-12-28 2022-11-20 2022-12-05 2023-01-09 2024-10-31 y cation Selection ation ATION OF INFRASTRUCTURE I MPROVEMENT - BHATTI GATE PK-PTEG-320797-CS-CQS / D ESIGN AND RESIDENT SUPER 3. Public Investment Facilit Consultant Qualifi IDA / 59820 Post Open - National 200,000.00 0.00 Under Review 2022-10-12 2022-11-10 2022-10-27 2022-11-20 2022-12-05 2022-12-25 2024-10-31 VISION FIRM FOR QILA KOHN y cation Selection A QASIM BAGH PROJECT PK-PTEG-330668-CS-QCBS / 3. Public Investment Facilit Quality And Cost- Under Implement Hiring of Firm for Digital Cura IDA / 59820 Post Open - National 600,000.00 0.00 2022-12-13 2022-12-06 2023-01-17 2023-01-02 2023-01-28 2023-03-04 2023-03-14 2023-03-27 2023-04-20 2024-04-19 y Based Selection ation tion of Lahore and Taxila Mus eum INDIVIDUAL CONSULTANTS Page 5 Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PTEG-32377-CS-INDV / So 4. Project Management, M Individual Consult cial Gender Specialist IDA / 59820 Post Open 189,450.00 26,773.76 Signed 2017-10-17 2017-08-01 2017-12-05 2018-01-02 2017-12-26 2018-01-01 2018-01-30 2018-02-01 2018-12-20 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32381-CS-INDV / E 4. Project Management, M Individual Consult nvironmental Specialist IDA / 59820 Post Open 189,450.00 24,361.53 Signed 2017-10-17 2017-07-17 2017-12-05 2017-12-26 2017-12-11 2018-01-30 2018-01-11 2019-01-10 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32410-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Bahawalpur IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-32411-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Rajanpur IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-40044-CS-INDV / R 4. Project Management, M Individual Consult IDA / 59820 Post Open 85,714.00 5,361.93 Signed 2017-12-18 2017-10-02 2018-02-05 2017-10-27 2018-02-26 2017-11-27 2018-04-02 2017-10-27 2018-09-28 esearch Associate onitoring and Evaluation ant Selection PK-PTEG-40046-CS-INDV / R 4. Project Management, M Individual Consult esearch Associate IDA / 59820 Post Open 85,714.00 5,361.93 Signed 2017-12-18 2017-12-04 2018-02-05 2018-01-03 2018-02-26 2018-01-02 2018-04-02 2018-01-08 2019-04-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-32376-CS-INDV / Fi 4. Project Management, M Individual Consult nancial Management Speciali IDA / 59820 Post Open 189,450.00 21,440.76 Signed 2017-10-17 2017-12-05 2017-09-11 2017-12-26 2017-09-13 2018-01-30 2017-09-26 2018-10-10 onitoring and Evaluation ant Selection st Estimated amount for 5 year s PK-PTEG-32398-CS-INDV / M 4. Project Management, M Individual Consult & E Specialist IDA / 59820 Post Open 225,000.00 29,233.84 Signed 2017-10-17 2017-07-01 2017-12-05 2017-09-11 2017-12-26 2017-09-25 2018-01-30 2017-09-26 2018-10-01 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-32389-CS-INDV / Pr 4. Project Management, M Individual Consult oject Director IDA / 59820 Prior Open 600,000.00 0.00 Canceled 2017-10-17 2018-08-16 2017-12-05 2017-12-26 2018-02-19 2019-02-19 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32391-CS-INDV / D 4. Project Management, M Individual Consult eputy Project Director IDA / 59820 Prior Open 370,000.00 0.00 Canceled 2017-10-17 2017-12-05 2017-12-26 2018-01-30 2018-10-25 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-40047-CS-INDV / R 4. Project Management, M Individual Consult esearch Associate - Account/ IDA / 59820 Post Open 85,714.00 14,616.92 Signed 2017-12-18 2017-09-11 2018-01-21 2017-12-08 2018-01-28 2017-12-11 2018-02-19 2017-12-12 2019-01-02 onitoring and Evaluation ant Selection Admin Estimated cost for 5 years PK-PTEG-68956-CS-INDV / Pu 4. Project Management, M Individual Consult IDA / 59820 Post Open 47,000.00 0.00 Canceled 2018-07-16 2018-09-03 2018-09-24 2018-10-29 2019-04-27 blic Sector Development Spe onitoring and Evaluation ant Selection cialist PK-PTEG-73991-CS-INDV / Pr 4. Project Management, M Individual Consult IDA / 59820 Post Open 47,000.00 17,457.63 Signed 2018-08-16 2019-01-14 2018-10-04 2019-09-20 2018-10-25 2019-09-24 2018-11-29 2019-09-24 2019-05-28 ivate Sector Development Sp onitoring and Evaluation ant Selection ecialist PK-PTEG-93482-CS-INDV / To 4. Project Management, M Individual Consult urism Expert IDA / 59820 Post Open 40,000.00 25,119.61 Signed 2019-01-11 2019-09-30 2019-03-01 2020-02-27 2019-03-22 2019-04-26 2020-04-09 2019-10-23 onitoring and Evaluation ant Selection (One year estimated cost) PK-PTEG-103221-CS-INDV / 4. Project Management, M Individual Consult Monitoring & Evaluation Spec IDA / 59820 Post Open 150,000.00 21,524.65 Signed 2019-02-27 2019-05-04 2019-04-17 2019-11-20 2019-05-08 2019-06-12 2019-11-26 2022-06-30 onitoring and Evaluation ant Selection ialist 3-Years and 4 Months PK-PTEG-103232-CS-INDV / P 4. Project Management, M Individual Consult rocurement & Contract Admi IDA / 59820 Post Open 16,000.00 0.00 Canceled 2019-02-27 2019-04-17 2019-05-08 2019-06-12 2020-04-30 onitoring and Evaluation ant Selection nistration Support 1-Year PK-PTEG-32401-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Rawalpindi IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32405-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Gujranwala IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32407-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Sheikhupura IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-136467-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 170,000.00 0.00 Canceled 2019-10-02 2019-10-03 2019-10-28 2019-11-04 2019-11-18 2022-11-16 Hiring of Sr. Procurement Sp onitoring and Evaluation ant Selection ecialist PK-PTEG-136466-CS-INDV / 4. Project Management, M Individual Consult Pending Impleme IDA / 59820 Post Open 4,260.00 0.00 2019-10-03 2019-10-12 2019-10-14 2019-10-19 2020-02-16 Hiring of Graphic Designer onitoring and Evaluation ant Selection ntation PK-PTEG-138460-CS-INDV / 4. Project Management, M Individual Consult Hiring of Monitoring & Evalua IDA / 59820 Post Open 76,600.00 0.00 Canceled 2019-10-03 2019-10-29 2019-11-05 2019-11-13 2022-10-31 onitoring and Evaluation ant Selection tion (M&E) Specialist PK-PTEG-139666-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 170,000.00 0.00 Canceled 2019-10-14 2019-11-16 2019-11-26 2019-12-10 2023-10-31 Hiring of Sr. Communication onitoring and Evaluation ant Selection Specialist PK-PTEG-139667-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 87,500.00 8,612.44 Signed 2019-10-14 2019-12-02 2019-11-09 2020-01-22 2019-11-16 2020-01-23 2019-11-30 2020-01-24 2023-10-30 Hiring of Research Associate onitoring and Evaluation ant Selection PK-PTEG-103217-CS-INDV / 4. Project Management, M Individual Consult Senior Communication Speci IDA / 59820 Prior Open 168,000.00 0.00 Canceled 2019-02-27 2019-03-07 2019-04-17 2019-05-08 2019-06-12 2022-06-30 onitoring and Evaluation ant Selection alist 3-Years and 4 Months PK-PTEG-145106-CS-INDV / P 4. Project Management, M Individual Consult IDA / 59820 Post Limited 150,000.00 26,016.25 Signed 2019-11-11 2019-11-08 2019-11-12 2019-11-08 2019-11-13 2019-11-19 2019-11-14 2019-11-20 2022-09-14 roject Manager onitoring and Evaluation ant Selection PK-PTEG-145603-CS-INDV / P 4. Project Management, M Individual Consult rocurement and Contract Ad IDA / 59820 Post Limited 12,000.00 8,863.64 Signed 2019-11-14 2019-10-15 2019-11-15 2021-02-24 2019-11-15 2021-03-22 2019-11-15 2021-03-23 2020-11-14 onitoring and Evaluation ant Selection ministration Support Assistan t PK-PTEG-145698-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Limited 12,000.00 0.00 Canceled 2019-11-14 2019-11-15 2019-11-15 2019-11-15 2020-02-16 Short Term Media Advisor for onitoring and Evaluation ant Selection YASAT Page 6 PK-PTEG-32372-CS-INDV / Se 4. Project Management, M Individual Consult nior Procurement Specialist IDA / 59820 Prior Open 255,000.00 0.00 Canceled 2017-10-17 2017-12-05 2017-12-26 2018-01-30 2018-10-08 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-103202-CS-INDV / 4. Project Management, M Individual Consult Senior Procurement Specialis IDA / 59820 Prior Open 170,000.00 0.00 Canceled 2019-02-27 2019-02-28 2019-04-17 2019-05-08 2019-06-12 2022-06-30 onitoring and Evaluation ant Selection t-3 Years & 4-Months PK-PTEG-145723-CS-INDV / 1. Policy, Institutions and Individual Consult Pending Impleme Short Term Media Consultant IDA / 59820 Governance for Tourism Dev Post Limited 12,000.00 0.00 2019-11-14 2019-11-15 2019-11-15 2019-11-15 2019-11-24 ant Selection ntation for YASA&T. Demand Driven elopment PK-PTEG-151717-CS-INDV / Estimated cost for Project Off icer -1 for 3 years 4. Project Management, M Individual Consult IDA / 59820 Post Limited 45,000.00 10,762.33 Signed 2019-12-24 2019-12-02 2019-12-29 2020-01-02 2019-12-30 2020-01-03 2020-01-07 2021-01-02 We will use limited competiti onitoring and Evaluation ant Selection on as we will select a candid ate from existing pool of can didates. PK-PTEG-151720-CS-INDV / P roject Officer -2 . Estimated cost for 3 years USD 45,000. 4. Project Management, M Individual Consult IDA / 59820 Post Limited 45,000.00 12,197.30 Signed 2019-12-24 2019-12-02 2019-12-29 2020-01-06 2020-01-03 2020-01-10 2020-01-07 2021-01-09 We will use limited competiti onitoring and Evaluation ant Selection on since we have existing po ol of consultants to select fro m. PK-PTEG-32404-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Chakwal IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-32385-CS-INDV / Se 4. Project Management, M Individual Consult nior Communication Specialis IDA / 59820 Prior Open 252,000.00 0.00 Canceled 2017-10-17 2018-08-31 2017-12-05 2017-12-26 2018-01-30 2019-01-30 onitoring and Evaluation ant Selection t Estimated amount for 5 year s PK-PTEG-153682-CS-INDV / 4. Project Management, M Individual Consult Hiring of Procurement Specia IDA / 59820 Post Limited 170,000.00 22,959.63 Signed 2020-01-14 2020-01-01 2020-01-17 2020-01-10 2020-01-18 2020-02-10 2020-01-20 2020-02-11 2023-01-19 onitoring and Evaluation ant Selection list PTEGP- cost for 3 years PK-PTEG-115815-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 168,000.00 0.00 Canceled 2019-05-21 2019-07-09 2019-07-30 2019-09-03 2022-06-30 Senior Communication Speci onitoring and Evaluation ant Selection alist PK-PTEG-32387-CS-INDV / In 4. Project Management, M Individual Consult frastructure Development Sp IDA / 59820 Post Open 189,450.00 0.00 Canceled 2017-10-17 2019-01-21 2017-12-05 2017-12-26 2018-01-30 2019-03-29 onitoring and Evaluation ant Selection ecialist Estimated amount for 5 year s PK-PTEG-162559-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Limited 100,000.00 18,126.90 Signed 2020-03-09 2020-03-09 2020-03-14 2020-03-06 2020-04-04 2020-03-16 2020-05-09 2020-03-21 2022-04-29 Civil Engineer onitoring and Evaluation ant Selection PK-PTEG-163247-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Limited 15,000.00 11,229.64 Signed 2020-03-10 2020-03-24 2020-03-15 2020-10-03 2020-04-05 2020-12-11 2020-05-10 2020-12-18 2021-05-10 Assistant Civil Engineer onitoring and Evaluation ant Selection PK-PTEG-190459-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 75,000.00 14,972.86 Signed 2020-09-02 2020-09-01 2020-10-21 2020-11-12 2020-11-11 2020-12-03 2020-12-16 2020-12-08 2021-06-14 Social Safeguard & Gender S onitoring and Evaluation ant Selection pecialist PK-PTEG-196847-CS-INDV / 3. Public Investment Facilit Individual Consult IDA / 59820 Post Limited 20,000.00 12,496.10 Signed 2020-10-05 2020-10-09 2020-10-10 2020-10-16 2020-10-24 2020-11-15 2020-11-17 2020-11-17 2022-11-17 Content Writer - Informative y ant Selection Signboards PK-PTEG-197173-CS-INDV / 3. Public Investment Facilit Individual Consult Under Implement IDA / 59820 Post Limited 20,000.00 0.00 2020-10-09 2022-07-19 2020-10-14 2020-11-04 2020-12-09 2021-12-04 Conservation Architect - PCR y ant Selection ation MP PK-PTEG-228307-CS-INDV / P 4. Project Management, M Individual Consult IDA / 59820 Post Open 20,000.00 12,954.55 Signed 2021-04-26 2021-04-26 2021-05-29 2021-06-04 2021-06-05 2021-06-04 2021-06-19 2021-07-08 2022-06-14 roject Officer - 1 onitoring and Evaluation ant Selection PK-PTEG-228310-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 30,000.00 0.00 2021-04-26 2021-09-23 2021-05-29 2021-06-12 2021-06-26 2022-06-21 Architect onitoring and Evaluation ant Selection ation PK-PTEG-232086-CS-INDV / L 4. Project Management, M Individual Consult Under Implement egal Consultant for Tourism IDA / 59820 Post Open 9,500.00 0.00 2021-05-03 2021-04-30 2021-06-05 2021-06-12 2021-06-26 2021-09-24 onitoring and Evaluation ant Selection ation Department PK-PTEG-243329-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 45,000.00 0.00 2021-07-16 2021-07-07 2021-08-18 2021-09-01 2021-09-18 2023-04-30 Environment Specialist onitoring and Evaluation ant Selection ation PK-PTEG-256619-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Limited 23,500.00 0.00 2021-11-21 2022-03-25 2021-11-26 2021-12-03 2021-12-17 2022-06-15 Consultant for Integrated Tou onitoring and Evaluation ant Selection ation rism Plan PK-PTEG-264216-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 20,000.00 0.00 2021-11-28 2021-12-14 2021-12-24 2021-12-31 2022-01-14 2023-01-09 Research Associate - I onitoring and Evaluation ant Selection ation PK-PTEG-264217-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 20,000.00 0.00 2021-11-28 2021-12-14 2021-12-24 2021-12-31 2022-01-14 2023-01-09 Research Associate - II onitoring and Evaluation ant Selection ation PK-PTEG-267380-CS-INDV / P 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 100,000.00 0.00 2021-12-17 2021-12-16 2022-01-26 2022-02-09 2022-02-23 2023-04-30 roject Director onitoring and Evaluation ant Selection ation PK-PTEG-274905-CS-INDV / 4. Project Management, M Individual Consult Under Implement Coordination Officer for Touri IDA / 59820 Post Open 21,000.00 0.00 2022-01-31 2022-01-28 2022-02-26 2022-03-05 2022-03-19 2023-03-14 onitoring and Evaluation ant Selection ation sm Department PK-PTEG-274909-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 14,000.00 0.00 2022-01-31 2022-01-28 2022-02-26 2022-03-05 2022-03-19 2023-03-14 Data Analyst for Tourism Dep onitoring and Evaluation ant Selection ation artment PK-PTEG-274911-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 14,000.00 0.00 2022-01-31 2022-01-28 2022-02-26 2022-03-05 2022-03-19 2023-03-14 Analyst for Tourism Departm onitoring and Evaluation ant Selection ation ent PK-PTEG-279726-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Limited 28,000.00 0.00 Signed 2022-02-22 2022-02-18 2022-02-27 2022-07-21 2022-03-13 2022-08-04 2022-03-27 2023-03-22 Environment Specialist onitoring and Evaluation ant Selection PK-PTEG-279729-CS-INDV / L 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Limited 20,000.00 0.00 2022-02-21 2022-02-18 2022-02-24 2022-03-03 2022-03-17 2023-03-12 iaison Officer onitoring and Evaluation ant Selection ation PK-PTEG-279736-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 21,000.00 0.00 2022-02-21 2022-02-18 2022-03-19 2022-04-02 2022-04-16 2023-04-11 Coordination Officer onitoring and Evaluation ant Selection ation PK-PTEG-286751-CS-INDV / 1. Policy, Institutions and Individual Consult Under Implement Economist - Assessment of e IDA / 59820 Governance for Tourism Dev Post Open 16,000.00 0.00 2022-04-25 2022-04-21 2022-05-21 2022-05-28 2022-06-11 2022-09-09 ant Selection ation conomic impact of the PTEGP elopment Page 7 PK-PTEG-293040-CS-INDV / 3. Public Investment Facilit Individual Consult Pending Impleme IDA / 59820 Post Open 26,000.00 0.00 2022-05-09 2022-06-04 2022-06-11 2022-06-25 2023-06-20 Conservation Specialist y ant Selection ntation PK-PTEG-302813-CS-INDV / P 4. Project Management, M Individual Consult Under Implement rocurement and Contract Ad IDA / 59820 Post Open 12,000.00 0.00 2022-07-18 2023-03-20 2022-08-20 2022-08-27 2022-09-10 2023-04-29 onitoring and Evaluation ant Selection ation ministration Officer PK-PTEG-305507-CS-INDV / P 4. Project Management, M Individual Consult IDA / 59820 Prior Open - National 20,000.00 0.00 Signed 2022-07-25 2022-07-26 2022-08-27 2022-10-21 2022-09-10 2023-05-25 2022-10-01 2023-06-01 2023-04-29 rocurement Specialist onitoring and Evaluation ant Selection PK-PTEG-321724-CS-INDV / 4. Project Management, M Individual Consult Under Implement Hiring of Financial Managem IDA / 59820 Post Open - National 15,000.00 0.00 2022-10-17 2022-10-31 2022-11-07 2023-01-05 2022-11-09 2022-11-12 2023-05-11 onitoring and Evaluation ant Selection ation ent Specialist PK-PTEG-332494-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open - National 12,000.00 0.00 2022-12-19 2022-12-12 2023-01-10 2023-01-15 2023-01-26 2023-04-30 Hiring of Electrical Engineer onitoring and Evaluation ant Selection ation PK-PTEG-347113-CS-INDV / 4. Project Management, M Individual Consult Under Implement Hiring of Digital Media & Com IDA / 59820 Post Open - National 25,000.00 0.00 2023-03-07 2023-03-20 2023-04-11 2023-04-16 2023-04-22 2024-04-21 onitoring and Evaluation ant Selection ation munication Expert PK-PTEG-347155-CS-INDV / 1. Policy, Institutions and Individual Consult Hiring of Museum Educator a IDA / 59820 Governance for Tourism Dev Post Open - National 5,000.00 0.00 Canceled 2023-03-10 2023-03-20 2023-04-08 2023-04-13 2023-04-23 2023-10-20 ant Selection t Lahore Museum elopment PK-PTEG-347167-CS-INDV / 4. Project Management, M Individual Consult Under Implement Hiring of Social Safeguard & IDA / 59820 Post Open - National 31,000.00 0.00 2023-03-10 2023-03-06 2023-04-13 2023-04-18 2023-04-28 2024-04-27 onitoring and Evaluation ant Selection ation Gender Specialist Page 8 IN: Ecosystem Service Improvement Project (ESIP) (P133803) I. General 1. Bank’s approval Date of the procurement Plan: [Original: May 19, 2017] 2. Date of General Procurement Notice: June 9, 2016 3. Period covered by this procurement plan: The procurement period of project covered from year May 19,2017 to November 30, 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 2 million All 2. NCB (Goods) Above US$2 million All 3. ICB (Works) Above US$ 10 million All 4. NCB (Works) Above US$ 10 million All 5. (Non-Consultant Services) Below US$ 2 million All [Add other methods if necessary] Procurement Methods and Threshold Category Method of Threshold (US$ Equivalent) Procurement Goods and Non- ICB >3,000,000 consultant services LIB Wherever agreed by the Bank NCB Up to 3,000,000 (with NCB conditions) Shopping Up to 100,000 DC As per Para 3.7 of the Bank Guidelines Force Account As per Para 3.9 of Guidelines Framework As per Para 3.6 of Guidelines Agreements October 12, 2017 Works ICB >40,000,000 NCB Up to 40,000,000 (with NCB conditions) Shopping Up to 200,000 Force Account As per Para 3.9 of Guidelines DC As per Para 3.7 of Guidelines Community As per Para 3.19 of Guidelines Participation Prior Review by the Bank. The Bank will prior review the following contracts: • Works (including turnkey, Supply & Installation of plant and equipment and PPP): all contracts more than US$ 10 million equivalent; and • Goods (including information technology and non-consulting services): all contracts more than US$ 2 million equivalent. There is no separate prior review threshold for direct contract and therefore, the same review threshold will apply to direct contract for goods, works and non-consulting services. The above prior review thresholds are revised as per the instructions issued while launching of New Procurement Framework (NPF) July 2016. All contracts below the specified prior review threshold value shall be subject to Post Procurement Review (PPR). In addition, Bank shall be entitled to conduct, at any time, Independent Procurement Review (IPR) of all the contracts financed under the Grant. In both the cases, the IAs shall prepare lists of contract and submit it to the Bank for conducting PPR/IPR. The PPR will be conducted on annual basis. All contracts not covered under prior review will be subject to post review during supervision missions, and/or review by consultants to be appointed by the by Bank. 2. Pre-qualification. Note applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.19 of the Guidelines: It is envisaged that there will be some form of community participation activities in this project. If anything of that sort arises, it will be done as per para 3.19 of Procurement guidelines. 4. Reference to (if any) Project Operational/Procurement Manual: The Project has prepared project Operations Manual (OM) that contains a Chapter on Procurement procedures to be adopted for the project. The OM was reviewed and agreed by the Bank to be used as a guidance note while conducting project procurement. All the contracts issued under the project will follow the World Bank’s Guidelines: Bank’s “Guidelines: Procurement under IBRD Loans and IDA Credits” dated October 12, 2017 January 2011and revised in July 2014and “Guidelines: Selection and Employment of Consultants by World Bank Borrowers” dated January 2011 and revised in July 2014. In case of any inconsistencies between the Project Operation Manual and Bank’s Procurement Guidelines, the later shall prevail. 5. Any Other Special Procurement Arrangements: Procurement of goods, works and non-consulting services shall be conducted through state’s e-procurement portal using Bank’s standard biding documents. The e-portal was assessed and cleared by the Bank. International Competitive Bidding (ICB) is the preferred method for procurement of goods, works and non-consulting services. However, it is unlikely that there will be any ICB contract. All National Competitive Bidding (NCB) shall be conducted in accordance with paragraph 3.3 and 3.4 of the Guidelines. In addition, following additional provisions as agreed with GOI task force (as amended from time to time) shall apply: • Only the model bidding documents for NCB as agreed with the GoI Task Force (and as amended from time to time), shall be used for bidding; • Invitation to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily inter-alia giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids; • No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprise from any given State; • Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; • For prior review contracts, extension of bid validity shall not be allowed with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by Bank only in cases of Force Majeure and circumstance beyond the control of the Purchaser/Employer); October 12, 2017 • For prior review contracts, re-bidding shall not be carried out with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank; • The system of rejecting bids outside a pre-determined margin or “bracket” of prices shall not be used in the project; • Rates contract entered into by Directorate General of Supplies and Disposal (DGS & D) will not be acceptable as a substitute for NCB procedures unless agreed with the Bank on case to case basis. Such contracts will be acceptable however, for any procurement under the Shopping procedure; • Two or three envelop system will not be used (expect when suing e-procurement system assessed and agreed by the Bank. To meet the Bank's requirements for right to audit and F&C, these clauses may be included in the Purchase Orders, in case the purchasers are directly placing the purchase orders to DGS&D rate contract holders. On the other hand, if indent is placed through DGS&D, the Purchaser has the option to sign a separate undertaking with DGS&D rate contract holder, where Bank’s right to audit and F&C clauses could be mentioned; 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness: Available in STEP III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comment Threshold 1. Competitive Methods (Firms) Above US$ 1 million All contracts 2. Single Source (Firms) Above US$ 1 million All contracts 3. Individual Above US$ 300,000 All contracts 4 CQS Up to US$ 300,000 All contracts 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None October 12, 2017 4. Consultancy Assignments with Selection Methods and Time Schedule: Available in STEP October 12, 2017 PROCUREMENT India : India Ecosystems Service Improvement Project PLAN General Information Country: India 2018-01-08 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P133803 GPN Date: Project Name: India Ecosystems Service Improvement Project Loan / Credit No: TF / A3990 GIM State Forest Department MP Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-SPIU-MP-43453-CW-RFQ / Request for Quota Single Stage - One E 2018-10-1 TF / A3990 Project Management Post Open - National 75,000.00 71,250.04 Completed 2018-02-20 2018-04-17 2019-03-03 Commercial office maintenan tions nvelope 4 ce . IN-SPIU-MP-78468-CW-RFQ / Investments for Improving F Request for Quota Single Stage - One E 2019-05-0 TF / A3990 Post Limited 10,000.00 7,400.18 Completed 2018-09-29 2018-10-01 2018-11-09 2018-10-05 GREEN HOUSE - 700 SQ. MT. orest Quality in Selected Lan tions nvelope 8 dscapes IN-SPIU-MP-78472-CW-RFQ / Investments for Improving F Request for Quota Single Stage - One E 2019-05-1 TF / A3990 Post Limited 14,300.00 15,227.09 Completed 2018-09-29 2018-10-01 2018-11-13 2018-10-05 Poly house - 700 sq. mt. orest Quality in Selected Lan tions nvelope 2 dscapes IN-SPIU-MP-78473-CW-RFQ / Investments for Improving F Request for Quota Single Stage - One E 2019-05-0 TF / A3990 Post Limited 14,300.00 12,764.53 Completed 2018-09-29 2018-10-01 2018-11-06 2018-10-05 Mist chamber- 500 sq. mt. orest Quality in Selected Lan tions nvelope 5 dscapes IN-SPIU-MP-78474-CW-RFQ / Investments for Improving F Request for Quota Single Stage - One E 2019-05-0 TF / A3990 Post Limited 11,400.00 11,517.56 Completed 2018-09-29 2018-10-01 2018-11-06 2018-10-05 Vermi compost unit- orest Quality in Selected Lan tions nvelope 5 dscapes IN-SPIU-MP-78477-CW-RFQ / Investments for Improving F Request for Quota Single Stage - One E 2019-05-0 TF / A3990 Post Limited 7,100.00 6,707.11 Completed 2018-09-29 2018-10-01 2018-11-06 2019-01-24 Seed treatment plate form- orest Quality in Selected Lan tions nvelope 5 dscapes IN-SPIU-MP-78497-CW-RFQ / Investments for Improving F Request for Quota Single Stage - One E 2019-05-0 TF / A3990 Post Limited 14,300.00 13,398.40 Completed 2018-09-29 2018-10-01 2018-11-06 2020-02-02 Customer/visitor facilities cen orest Quality in Selected Lan tions nvelope 5 ter- dscapes IN-SPIU-MP-78498-CW-RFQ / Investments for Improving F Request for Quota Single Stage - One E 2019-05-2 TF / A3990 Post Limited 2,850.00 2,886.23 Completed 2018-09-29 2019-01-25 2018-11-24 2019-02-23 Toilet orest Quality in Selected Lan tions nvelope 3 dscapes IN-SPIU-MP-78499-CW-RFQ / Investments for Improving F Request for Quota Single Stage - One E 2019-05-2 TF / A3990 Post Limited 5,700.00 5,771.48 Completed 2018-09-29 2019-01-25 2018-11-24 2019-02-23 Labour hut orest Quality in Selected Lan tions nvelope 3 dscapes IN-SPIU-MP-78501-CW-RFQ / Investments for Improving F Request for Quota Single Stage - One E 2019-05-2 TF / A3990 Post Limited 42,850.00 38,933.26 Completed 2018-09-29 2018-10-01 2018-11-24 2018-10-05 C C Bed -200 orest Quality in Selected Lan tions nvelope 3 dscapes IN-SPIU-MP-78502-CW-RFQ / Investments for Improving F Request for Quota Single Stage - One E 2019-05-2 TF / A3990 Post Limited 3,600.00 3,604.08 Completed 2018-09-29 2019-02-23 2018-11-24 2020-02-01 Inner Road of Nursery 500 m orest Quality in Selected Lan tions nvelope 3 t. dscapes IN-SPIU-MP-78503-CW-RFQ / Investments for Improving F Request for Quota Single Stage - One E 2019-05-2 TF / A3990 Post Limited 7,150.00 6,720.45 Completed 2018-09-29 2020-02-19 2018-11-24 2020-03-05 Over head tank orest Quality in Selected Lan tions nvelope 3 dscapes IN-SPIU-MP-81250-CW-RFQ / Investments for Improving F Request for Quota Single Stage - One E 2019-06-1 TF / A3990 Post Limited 14,300.00 13,463.33 Completed 2018-10-20 2020-02-25 2018-12-15 2020-03-05 building construction for see orest Quality in Selected Lan tions nvelope 3 d store dscapes IN-SPIU-MP-93437-CW-RFQ / Investments for Improving F Request for Quota Single Stage - One E 2019-08-3 CCF R&E BHOPAL Irrigation f TF / A3990 orest Quality in Selected Lan Post Limited 5,700.00 5,745.73 Completed 2019-01-06 2019-02-28 2019-03-03 2019-03-06 tions nvelope 0 acility bore well pump, pipe e dscapes tc IN-SPIU-MP-93439-CW-RFQ / Investments for Improving F CCF R&E CIRCLE BHOPAL Fen Request for Quota Single Stage - One E 2019-08-3 TF / A3990 orest Quality in Selected Lan Post Limited 7,140.00 6,710.08 Completed 2019-01-06 2020-02-19 2019-03-03 2020-03-05 cing 500 RMT For Basapura n tions nvelope 0 dscapes ursery unit sehore IN-SPIU-MP-93760-CW-RFQ / Investments for Improving F Betul R&E in its Forest Nurser Request for Quota Single Stage - One E 2019-09-1 TF / A3990 orest Quality in Selected Lan Post Limited 14,285.00 0.00 Canceled 2019-01-26 2019-02-21 2019-03-23 y Khakrapura plans to build a tions nvelope 9 dscapes Poly House having an area of 320 Sq.mt. IN-SPIU-MP-93774-CW-RFQ / Betul R & E Circle MP Plans t Investments for Improving F o create a greenhouse in For Request for Quota Single Stage - One E 2019-09-1 TF / A3990 orest Quality in Selected Lan Post Limited 8,571.00 0.00 Canceled 2019-01-26 2019-02-21 2019-03-23 est Nursery Khakrapura to fa tions nvelope 9 dscapes cilitate the growth of quality seedlings even in non germin ation period IN-SPIU-MP-93848-CW-RFQ / Betul R & E Circle MP Plans t Investments for Improving F o create a greenhouse in For Request for Quota Single Stage - One E 2019-09-1 TF / A3990 orest Quality in Selected Lan Post Limited 5,714.00 0.00 Canceled 2019-01-26 2019-02-21 2019-03-23 est Nursery DHAR to facilitat tions nvelope 9 dscapes e the growth of quality seedli ngs even in non germination period IN-SPIU-MP-100679-CW-RFQ Investments for Improving F / Betul R&E MP Plans to prep Request for Quota Single Stage - One E 2019-12-1 TF / A3990 orest Quality in Selected Lan Post Limited 14,285.00 0.00 Canceled 2019-04-20 2019-06-15 ared vermi compost units in tions nvelope 2 dscapes Khakrapura Nursery Narmad a Unit In Betul IN-SPIU-MP-150225-CW-RFQ Investments for Improving F / chanlink fancing 4000 mtr f Request for Quota Single Stage - One E 2020-09-0 TF / A3990 orest Quality in Selected Lan Post Limited 35,000.00 13,427.42 Completed 2020-01-11 2020-02-20 2020-03-07 2020-02-21 or under the ESIP project in p tions nvelope 3 dscapes lantation site covering IN-SPIU-MP-150258-CW-RFQ Investments for Improving F / Rennovation of khatpura co Request for Quota Single Stage - One E 2020-09-0 TF / A3990 orest Quality in Selected Lan Post Limited 4,000.00 3,382.97 Completed 2020-01-11 2020-02-02 2020-03-07 2020-03-03 mmunity hall in ESIP project tions nvelope 3 dscapes area Range Budhni IN-SPIU-MP-139596-CW-RFQ Investments for Improving F / Ccfre research and extensio Request for Quota Single Stage - One E 2020-10-0 TF / A3990 orest Quality in Selected Lan Post Limited 43,220.00 35,835.13 Completed 2020-02-09 2020-03-17 2020-04-05 2020-04-14 n circle Bhopal 200 cement tions nvelope 2 dscapes concrete bed for basapur nur sery IN-SPIU-MP-139603-CW-RFQ Investments for Improving F Request for Quota Single Stage - One E 2020-10-0 TF / A3990 Post Limited 3,600.00 3,369.95 Completed 2020-02-09 2020-11-23 2020-04-05 2020-12-18 / Ccfre 500 meter inner roa orest Quality in Selected Lan tions nvelope 2 d dscapes Page 1 IN-SPIU-MP-195735-CW-RFQ Investments for Improving F Request for Quota Single Stage - One E 2021-08-1 / ccfre bhopal propose to con TF / A3990 orest Quality in Selected Lan Post Limited 33,333.00 10,935.54 Completed 2020-12-17 2020-12-04 2021-02-11 2020-12-12 tions nvelope 0 struct vermi compost units dscapes IN-SPIU-MP-195745-CW-RFQ Investments for Improving F Request for Quota Single Stage - One E 2021-08-1 / ccfre bhopal propose to con TF / A3990 orest Quality in Selected Lan Post Limited 93,750.00 30,218.67 Completed 2020-12-17 2020-12-04 2021-02-11 2020-12-12 tions nvelope 0 struct cc bed dscapes IN-SPIU-MP-195749-CW-RFQ Investments for Improving F Request for Quota Single Stage - One E 2021-08-1 / ccfre bhopal propose to con TF / A3990 orest Quality in Selected Lan Post Limited 20,833.00 6,836.47 Completed 2020-12-17 2020-12-04 2021-02-11 2020-12-12 tions nvelope 0 struction and installation of dscapes micro sprinkler IN-SPIU-MP-195753-CW-RFQ Investments for Improving F Request for Quota Single Stage - One E 2021-08-1 / ccfre bhopal propose to con TF / A3990 orest Quality in Selected Lan Post Limited 41,667.00 13,685.51 Completed 2020-12-17 2020-12-04 2021-02-11 2020-12-12 tions nvelope 0 struct Seed store dscapes IN-SPIU-MP-195754-CW-RFQ Investments for Improving F Request for Quota Single Stage - One E 2021-08-1 / ccfre bhopal propose to con TF / A3990 orest Quality in Selected Lan Post Limited 20,833.00 6,840.81 Completed 2020-12-17 2020-12-04 2021-02-11 2020-12-12 tions nvelope 0 struct Fencing dscapes IN-SPIU-MP-195756-CW-RFQ Investments for Improving F Request for Quota Single Stage - One E 2021-08-1 / ccfre bhopal propose to con TF / A3990 orest Quality in Selected Lan Post Limited 12,500.00 4,098.47 Completed 2020-12-17 2020-12-04 2021-02-11 2021-01-01 tions nvelope 0 struction and installation of si dscapes nage IN-SPIU-MP-195765-CW-RFQ Investments for Improving F Request for Quota Single Stage - One E 2021-08-1 / ccfre bhopal propose to con TF / A3990 orest Quality in Selected Lan Post Limited 20,833.00 6,717.66 Completed 2020-12-17 2020-12-17 2021-02-11 2021-01-12 tions nvelope 0 struction of Inner Road dscapes IN-SPIU-MP-195977-CW-RFQ Investments for Improving F Request for Quota Single Stage - One E 2021-08-1 / ccfre bhopal propose to co TF / A3990 orest Quality in Selected Lan Post Limited 41,667.00 13,684.78 Completed 2020-12-17 2020-12-04 2021-02-11 2020-12-12 tions nvelope 0 nstruct overhead tank dscapes IN-SPIU-MP-195978-CW-RFQ Investments for Improving F Request for Quota Single Stage - One E 2021-08-1 / ccfre bhopal proposed to c TF / A3990 orest Quality in Selected Lan Post Limited 13,889.00 6,687.68 Completed 2020-12-17 2020-12-04 2021-02-11 2020-12-12 tions nvelope 0 onstruct labour hut dscapes IN-SPIU-MP-195980-CW-RFQ Investments for Improving F Request for Quota Single Stage - One E 2021-08-1 / ccfre bhopal proposes to c TF / A3990 orest Quality in Selected Lan Post Limited 27,778.00 13,478.45 Completed 2020-12-17 2020-12-05 2021-02-11 2020-12-12 tions nvelope 0 onstruct poly-house dscapes IN-SPIU-MP-196002-CW-RFQ Investments for Improving F Request for Quota Single Stage - One E 2021-08-1 / ccfre bhopal proposes to c TF / A3990 orest Quality in Selected Lan Post Limited 2,778.00 2,709.73 Completed 2020-12-17 2020-12-04 2021-02-11 2020-12-12 tions nvelope 0 onstruct gate dscapes IN-SPIU-MP-196006-CW-RFQ Investments for Improving F Request for Quota Single Stage - One E 2021-08-1 / ccfre bhopal proposes to pr TF / A3990 orest Quality in Selected Lan Post Limited 2,778.00 2,737.10 Completed 2020-12-17 2020-12-04 2021-02-11 2021-03-03 tions nvelope 0 ocure and construct cocopit dscapes unit with shed IN-SPIU-MP-203615-CW-RFQ Investments for Improving F / CCFRE Bhopal Mist chamber Request for Quota Single Stage - One E 2021-08-1 TF / A3990 orest Quality in Selected Lan Post Limited 41,667.00 13,685.51 Completed 2020-12-17 2020-12-04 2021-02-11 2020-12-12 s in three nurseries to be con tions nvelope 0 dscapes structed of 120 sqmt each IN-SPIU-MP-203618-CW-RFQ Investments for Improving F / ccfre bhopal propose to con Request for Quota Single Stage - One E 2021-08-1 TF / A3990 orest Quality in Selected Lan Post Limited 5,556.00 2,671.97 Completed 2020-12-17 2020-12-17 2021-02-11 2021-01-12 struction and installation of C tions nvelope 0 dscapes ompost tank 8 nos IN-SPIU-MP-203620-CW-RFQ Request for Quota Single Stage - One E 2021-08-1 / CCFRE Bhopal will carryout TF / A3990 Project Management Post Limited 48,611.00 54,121.06 Completed 2020-12-17 2020-12-05 2021-02-11 2020-12-12 tions nvelope 0 Green India mission office re novation work IN-SPIU-MP-205097-CW-RFQ Investments for Improving F Request for Quota Single Stage - One E 2021-08-1 / ccfre bhopal propose to con TF / A3990 orest Quality in Selected Lan Post Limited 6,944.00 6,721.31 Completed 2020-12-17 2020-12-17 2021-02-11 2021-01-01 tions nvelope 0 struction of Seed treatment dscapes platform IN-SPIU-MP-208098-CW-RFQ Investments for Improving F Request for Quota Single Stage - One E Pending Imp 2021-10-2 / To collect honey and to nurt TF / A3990 orest Quality in Selected Lan Post Limited 21,429.00 0.00 2021-02-28 2021-04-25 tions nvelope lementation 2 ure honey bees, special kits dscapes are required. IN-SPIU-MP-240821-CW-RFQ / Preparation of 400 cc bed i Investments for Improving F Request for Quota Request for Quota Single Stage - One E 2022-05-0 n Imaliya, Bhadabhada and B TF / A3990 orest Quality in Selected Lan Post Limited tions (Non Bank-S 85,714.00 80,921.13 Completed 2021-09-11 2021-08-19 2021-11-06 2021-08-27 tions nvelope 5 adi Nurseries of Bhopal, Rais dscapes PD) en and Sehore landscape un der GIM. IN-SPIU-MP-240826-CW-RFQ / Installation of micro sprinkl Investments for Improving F Request for Quota er for Irrigation in Imaliya, T Request for Quota Single Stage - One E 2022-05-0 TF / A3990 orest Quality in Selected Lan Post Limited tions (Non Bank-S 60,714.00 57,241.28 Completed 2021-09-11 2021-08-19 2021-11-06 2021-08-27 hoona, Bhadabhada, Badi an tions nvelope 5 dscapes PD) d Mudiyakheda Nurseries of Bhopal, Raisen and Sehore la ndscape under GIM. IN-SPIU-MP-240829-CW-RFQ / construction of seed store i Investments for Improving F Request for Quota Request for Quota Single Stage - One E 2022-05-0 n Imaliya, Thoona, Bhadbhad TF / A3990 orest Quality in Selected Lan Post Limited tions (Non Bank-S 57,142.00 53,879.68 Completed 2021-09-11 2021-08-19 2021-11-06 2021-08-27 tions nvelope 5 a Nurseries of Bhopal, Raise dscapes PD) n and Sehore landscape und er GIM. IN-SPIU-MP-240834-CW-RFQ / Construction of inner road i Investments for Improving F Request for Quota Request for Quota Single Stage - One E 2022-05-0 n Imaliya, Thoona, Badi Nurs TF / A3990 orest Quality in Selected Lan Post Limited tions (Non Bank-S 24,286.00 22,960.18 Completed 2021-09-11 2021-08-19 2021-11-06 2021-08-27 tions nvelope 5 eries of Bhopal, Raisen and dscapes PD) Sehore landscape under GIM. IN-SPIU-MP-240836-CW-RFQ / Display and signage in Imal Investments for Improving F Request for Quota Request for Quota Single Stage - One E 2022-05-0 iya, Bhadabhada, Badi Nurse TF / A3990 orest Quality in Selected Lan Post Limited tions (Non Bank-S 16,428.00 15,389.64 Completed 2021-09-11 2021-08-19 2021-11-06 2021-08-27 tions nvelope 5 ries of Bhopal, Raisen and S dscapes PD) ehore landscape under GIM. IN-SPIU-MP-240952-CW-RFQ / Installation of fogger syste Investments for Improving F Request for Quota Request for Quota Single Stage - One E 2022-05-0 m in Imaliya, Bhadabhada, B TF / A3990 orest Quality in Selected Lan Post Limited tions (Non Bank-S 28,571.00 26,932.36 Completed 2021-09-11 2021-08-19 2021-11-06 2021-08-27 tions nvelope 5 adi, Mudiyakheda Nurseries dscapes PD) of Bhopal and Raisen landsc ape under GIM. Page 2 IN-SPIU-MP-240953-CW-RFQ / Installation of borewell with Investments for Improving F Request for Quota Request for Quota Single Stage - One E 2022-05-0 pump for irrigation in Thoona TF / A3990 orest Quality in Selected Lan Post Limited tions (Non Bank-S 17,143.00 16,028.15 Completed 2021-09-11 2021-08-19 2021-11-06 2021-08-27 tions nvelope 5 , Badi and Mudiyakheda Nur dscapes PD) series of Raisen and Sehore l andscape under GIM. IN-SPIU-MP-240957-CW-RFQ Investments for Improving F Request for Quota / Construction of high level fe Request for Quota Single Stage - One E 2022-05-0 TF / A3990 orest Quality in Selected Lan Post Limited tions (Non Bank-S 14,286.00 13,465.88 Completed 2021-09-11 2021-08-19 2021-11-06 2021-08-27 ncing in Bhadabhada Nurse tions nvelope 5 dscapes PD) ry of Bhopal, landscape und er GIM. IN-SPIU-MP-240958-CW-RFQ Investments for Improving F Request for Quota / Construction of poly house i Request for Quota Single Stage - One E 2022-05-0 TF / A3990 orest Quality in Selected Lan Post Limited tions (Non Bank-S 14,286.00 13,470.77 Completed 2021-09-11 2021-08-19 2021-11-06 2021-08-27 n Badi Nursery of Raisen la tions nvelope 5 dscapes PD) ndscape under GIM. IN-SPIU-MP-247835-CW-RFQ Investments for Improving F Request for Quota / Construction of soil testing l Request for Quota Single Stage - One E 2022-05-0 TF / A3990 orest Quality in Selected Lan Post Limited tions (Non Bank-S 18,657.00 16,086.89 Completed 2021-09-11 2021-10-06 2021-11-06 2021-12-01 aboratory at Ahamadpur nur tions nvelope 5 dscapes PD) sery, R&E circle Bhopal IN-SPIU-MP-240837-CW-RFQ / Construction of labour hut Investments for Improving F Request for Quota with toilet and drinking water Request for Quota Single Stage - One E 2022-05-0 TF / A3990 orest Quality in Selected Lan Post Limited tions (Non Bank-S 59,701.40 56,524.30 Completed 2021-09-11 2021-10-06 2021-11-06 2021-10-19 facility in Imaliya, Thoona, Ba tions nvelope 5 dscapes PD) di and Mudiyakheda Nurserie s of Bhopal, Raisen and Seh ore landscape under GIM. IN-SPIU-MP-240830-CW-RFQ / Installation of fencing in Im Investments for Improving F Request for Quota Request for Quota Single Stage - One E 2022-05-0 aliya, Thoona, Badi and Nurs TF / A3990 orest Quality in Selected Lan Post Limited tions (Non Bank-S 32,857.00 31,118.34 Completed 2021-09-11 2021-10-06 2021-11-06 2021-10-19 tions nvelope 5 eries of Bhopal, Raisen and dscapes PD) Sehore landscape under GIM. IN-SPIU-MP-100682-CW-RFQ Investments for Improving F / Betul R&E MP Plans to prep Request for Quota Single Stage - One E 2019-12-1 TF / A3990 orest Quality in Selected Lan Post Limited 14,285.00 0.00 Canceled 2019-04-20 2019-06-15 ared vermi compost units in tions nvelope 2 dscapes Dhar Nursery Dhar Unit In Be tul IN-SPIU-MP-321815-CW-RFQ / Cf Social forestry circle Bho pal Installation of fencing in Investments for Improving F Request for Quota Single Stage - One E Other (with field f 2023-11-0 Ahamadpur, Holipura, Basap TF / A3990 orest Quality in Selected Lan Post Limited 67,164.00 0.00 Canceled 2022-10-19 2022-11-14 2022-10-24 2022-12-05 2023-01-04 2023-02-08 tions nvelope or explanation) 5 ura, Thoona, Amarawad seco dscapes nd, Mudiyakheda and Badi N urseries of Bhopal, Raisen an d Sehore landscape under GI M. IN-SPIU-MP-321823-CW-RFQ / Cf Social Forestry Circle Bho pal Construction of inner roa Investments for Improving F d in Ahamadpur, Bhadbhada, Request for Quota Single Stage - One E Other (with field f Under Imple 2023-06-1 TF / A3990 orest Quality in Selected Lan Post Limited 52,239.00 0.00 2022-10-24 2022-11-16 2022-12-19 Holipura, Basapura, Thoona, tions nvelope or explanation) mentation 7 dscapes Amarawad first, Amarawad s econd Badi Nurseries of Bho pal, Raisen and Sehore lands cape under GIM. IN-SPIU-MP-321826-CW-RFQ / Cf Social Forestry Circle Bho Investments for Improving F pal Construction of labour hu Request for Quota Single Stage - One E Other (with field f Under Imple 2023-06-1 TF / A3990 orest Quality in Selected Lan Post Limited 14,925.00 0.00 2022-10-24 2022-11-16 2022-12-19 t with toilet and drinking wat tions nvelope or explanation) mentation 7 dscapes er facility in Ahamadpur Nurs eries of Bhopal, landscape u nder GIM. IN-SPIU-MP-321828-CW-RFQ / Cf Social Forestry Circle Bho Investments for Improving F Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-06-1 pal Display and signage in A TF / A3990 orest Quality in Selected Lan Post Limited 4,478.00 0.00 2022-10-24 2022-12-19 tions nvelope or explanation) lementation 7 marawad Second Nurseries o dscapes f Raisen landscape under GI M. IN-SPIU-MP-321830-CW-RFQ / Cf Social Forestry Circle Bho Investments for Improving F Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-06-1 pal Construction of Water Ca TF / A3990 orest Quality in Selected Lan Post Limited 59,701.00 0.00 2022-10-24 2022-12-19 tions nvelope or explanation) lementation 7 nal in Ahamadpur Nurseries dscapes of Bhopal, landscape under GIM. IN-SPIU-MP-321832-CW-RFQ / Cf social forestry circle Bho Investments for Improving F Request for Quota Single Stage - One E Other (with field f Under Imple 2023-06-1 pal Construction of high level TF / A3990 orest Quality in Selected Lan Post Limited 5,970.00 0.00 2022-10-24 2022-11-16 2022-12-19 tions nvelope or explanation) mentation 7 fencing in Bhadabhada Nurse dscapes ry of Bhopal, landscape unde r GIM. IN-SPIU-MP-321833-CW-RFQ / Cf Social forestry circle Bho Investments for Improving F pal Construction of Inspectio Request for Quota Single Stage - One E Other (with field f Under Imple 2023-06-1 TF / A3990 orest Quality in Selected Lan Post Limited 20,896.00 0.00 2022-10-24 2022-11-16 2022-12-19 n Path in Bhadbhada, Amara tions nvelope or explanation) mentation 7 dscapes wad Second and Badi Nurseri es of Bhopal and Raisen lan dscape under GIM. IN-SPIU-MP-321834-CW-RFQ / Cf social forestry circle Bho Investments for Improving F pal construction/ Installation Request for Quota Single Stage - One E Other (with field f Under Imple 2023-06-1 TF / A3990 orest Quality in Selected Lan Post Limited 44,776.00 0.00 2022-10-24 2022-11-14 2022-12-19 of Green House Holipura, Tho tions nvelope or explanation) mentation 7 dscapes ona, Amarawad first and Ba di Nurseries of Raisen and S ehore landscape under GIM. IN-SPIU-MP-321944-CW-RFQ / Cf social forestry circle Bho Investments for Improving F Request for Quota Single Stage - One E Other (with field f 2023-06-1 pal Construction of Stop Dam TF / A3990 orest Quality in Selected Lan Post Limited 7,463.00 0.00 Canceled 2022-10-24 2022-11-16 2022-12-19 tions nvelope or explanation) 7 in Thoona Nurseries of Sehor dscapes e, landscape under GIM. IN-SPIU-MP-321946-CW-RFQ / Cf social forestry circle Bho Investments for Improving F pal Construction of Varmi Co Request for Quota Single Stage - One E Other (with field f 2023-06-1 TF / A3990 orest Quality in Selected Lan Post Limited 29,851.00 0.00 Canceled 2022-10-24 2022-11-16 2022-12-19 mpost store room in Amaraw tions nvelope or explanation) 7 dscapes ad first and Badi Nurseries of Raisen, landscape under GI M IN-SPIU-MP-321948-CW-RFQ / Cf social forestry circle Bho Investments for Improving F pal Construction/Instalation Request for Quota Single Stage - One E Other (with field f 2023-06-1 TF / A3990 orest Quality in Selected Lan Post Limited 11,940.00 0.00 Canceled 2022-10-24 2023-01-18 2022-12-19 of Pump house with tower in tions nvelope or explanation) 7 dscapes Amarawad second and Badi Nurseries of Raisen, landsca pe under GIM Page 3 IN-SPIU-MP-321949-CW-RFQ / Cf social forestry circle Bho pal Construction of Varmi Co Investments for Improving F Request for Quota Single Stage - One E Other (with field f 2023-06-1 mpost Unit in Ahamadpur, H TF / A3990 orest Quality in Selected Lan Post Limited 71,642.00 0.00 Canceled 2022-10-24 2022-12-19 tions nvelope or explanation) 7 olipura,Basapura, Thoona, A dscapes marawad first and Badi Nurs eries of Bhopal, Sehore and R aisen, landscape under GIM IN-SPIU-MP-321950-CW-RFQ / Cf social forestry circle Bho Investments for Improving F pal Construction of Water sto Request for Quota Single Stage - One E Other (with field f Under Imple 2023-06-1 TF / A3990 orest Quality in Selected Lan Post Limited 22,388.00 0.00 2022-10-24 2023-01-18 2022-12-19 rage tank with pump and pip tions nvelope or explanation) mentation 7 dscapes e system in Amarawad first a nd Badi Nurseries of Raisen, landscape under GIM IN-SPIU-MP-321793-CW-RFQ / CF Social Forestry Circle B HOPAL Installation of 2300 B Investments for Improving F ed (4/Bed) micro sprinkller I Request for Quota Single Stage - One E Other (with field f Under Imple 2023-06-1 TF / A3990 orest Quality in Selected Lan Post Limited 85,821.00 0.00 2022-10-24 2022-11-14 2022-12-19 n Ahamadpur, Bhadbhada, H tions nvelope or explanation) mentation 7 dscapes olipura, Basapura, Amarawad first, Amrawad second , Mudi yakheda, Badi Nuesery of Bh opal, Raisen and Sehore Lan dscape Under GIM IN-SPIU-MP-321809-CW-RFQ / Cf social forestry circle bho pal Installation of fogger syst Investments for Improving F Request for Quota Single Stage - One E Other (with field f Under Imple 2023-06-1 em in Ahamadpur, Bhadbhad TF / A3990 orest Quality in Selected Lan Post Limited 53,731.00 0.00 2022-10-24 2022-11-14 2022-12-19 tions nvelope or explanation) mentation 7 a, Holipura, Basapur, Amara dscapes wad first Nurseries of Bhopal , Sehore and Raisen landscap e under GIM. IN-SPIU-MP-330166-CW-RFQ / Cf social forestry circle Bho Investments for Improving F Request for Quota Single Stage - One E Other (with field f Under Imple 2023-08-1 pal Construction of RCC open TF / A3990 orest Quality in Selected Lan Post Limited 22,388.00 0.00 2022-12-17 2023-01-18 2023-02-11 tions nvelope or explanation) mentation 0 well in Ahamadpur Nurseries dscapes of Bhopal, landscape under G IM. IN-SPIU-MP-330169-CW-RFQ / Cf social forestry circle Bho Investments for Improving F Request for Quota Single Stage - One E Other (with field f Under Imple 2023-08-1 pal Construction of RCC road TF / A3990 orest Quality in Selected Lan Post Limited 14,925.00 0.00 2022-12-17 2023-01-18 2023-02-11 tions nvelope or explanation) mentation 0 in Ahamadpur Nurseries of B dscapes hopal, landscape under GIM. IN-SPIU-MP-330171-CW-RFQ / Cf social forestry circle Bho Investments for Improving F pal Installation of Water Supp Request for Quota Single Stage - One E Other (with field f Under Imple 2023-08-1 TF / A3990 orest Quality in Selected Lan Post Limited 29,851.00 0.00 2022-12-17 2023-01-18 2023-02-11 ly with Water Lifting System i tions nvelope or explanation) mentation 0 dscapes n Amarawad first Nurseries of Raisen, landscape under G IM. IN-SPIU-MP-330178-CW-RFQ Investments for Improving F / Cf social forestry circle Bho Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-08-1 TF / A3990 orest Quality in Selected Lan Post Limited 2,985.00 0.00 2022-12-17 2023-02-11 pal Installation of Gate in Ga tions nvelope or explanation) lementation 0 dscapes rethiya Nurseries of Bhopal, landscape under GIM. IN-SPIU-MP-344973-CW-RFQ Investments for Improving F / Cf social forestry circle Bho Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-10-2 TF / A3990 orest Quality in Selected Lan Post Limited 2,985.00 0.00 2023-03-01 2023-04-26 pal Installation of Gate in Mu tions nvelope or explanation) lementation 3 dscapes diyakheda Nurseries of Rais en, landscape under GIM. IN-SPIU-MP-344977-CW-RFQ / Cf Social Forestry Circle Bho Investments for Improving F Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-10-2 pal Display and signage in M TF / A3990 orest Quality in Selected Lan Post Limited 1,493.00 0.00 2023-03-01 2023-04-26 tions nvelope or explanation) lementation 3 udiyakheda Nurseries of Rais dscapes en landscape under GIM. IN-SPIU-MP-344980-CW-RFQ / Cf social forestry circle Bho Investments for Improving F Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-10-2 pal Construction of Store roo TF / A3990 orest Quality in Selected Lan Post Limited 7,463.00 0.00 2023-03-01 2023-04-26 tions nvelope or explanation) lementation 3 m in Basapur Nurseries of Se dscapes hore, landscape under GIM IN-SPIU-MP-362243-CW-RFQ / CF social forestry circle Bho Investments for Improving F Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-01-2 pal Construction of RCC road TF / A3990 orest Quality in Selected Lan Post Limited 7,463.00 0.00 2023-06-03 2023-07-29 tions nvelope or explanation) lementation 5 in Bhadbhada Nurseries Bho dscapes pal, landscape under GIM. IN-SPIU-MP-362249-CW-RFQ / Cf social forestry circle Bho Investments for Improving F Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-01-2 pal Construction of Slab for w TF / A3990 orest Quality in Selected Lan Post Limited 5,970.00 0.00 2023-06-03 2023-07-29 tions nvelope or explanation) lementation 5 ater storage at Amarawad fir dscapes st Nurseries Raisen landscape under GIM . GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-SPIU-MP-40456-GO-RFQ / Request for Quota Single Stage - One E Procurement of Office Equip TF / A3990 Project Management Post Open - National 10,000.00 0.00 Canceled 2018-01-20 2018-03-17 2018-09-13 tions nvelope ment (Laptop, Printers, Came ra, Scanner, etc.) IN-SPIU-MP-43450-GO-RFQ / Request for Quota Single Stage - One E Pending Impl Office equipment (file cabine TF / A3990 Project Management Post Open - National 10,000.00 0.00 2018-02-04 2018-04-01 2018-09-28 tions nvelope ementation t , Chair, Tables, Photo Copy Machine ) IN-SPIU-MP-64249-GO-RFQ / procurement of GNSS equip Request for Quota Single Stage - One E TF / A3990 Project Management Post Open - National 45,000.00 0.00 Canceled 2018-06-23 2018-08-18 2019-02-14 ment for collecting field data tions nvelope and procurement of Densito meter. IN-SPIU-MP-76360-GO-RFQ / Strengthen Capacity of Gove Procurement of GNSS device rnment Institutions in Forest Request for Quota Single Stage - One E TF / A3990 Post Limited 42,000.00 46,444.27 Completed 2018-09-12 2018-12-04 2018-11-07 2019-01-28 2019-05-06 2019-03-23 s through RFQ process invitin ry and Land Management Pr tions nvelope g quotations from three kno ograms in Madhya Pradesh a wn suppliers nd Chhattisgarh IN-SPIU-MP-76595-GO-DIR / Under Imple computers printers scanners TF / A3990 Project Management Post Direct Selection Direct 10,000.00 0.00 2018-09-01 2018-09-06 2018-10-16 2018-10-11 2019-04-09 mentation etc. for SPIU MP to be procur ed through GEM Page 4 IN-SPIU-MP-77559-GO-RFQ / Procurement of Desktop Com Request for Quota Single Stage - One E Pending Impl TF / A3990 Project Management Post Limited 2,000.00 0.00 2018-09-22 2018-11-17 2019-05-16 puter for Remote Sensing an tions nvelope ementation d GIS related mapping activit y for SPIU IN-SPIU-MP-80665-GO-RFQ / Investments for Improving F Request for Quota Single Stage - One E TF / A3990 Post Limited 12,850.00 12,955.62 Completed 2018-12-05 2019-01-25 2019-01-30 2019-02-23 2019-07-29 2019-03-22 Solar Pump for Irrigation 7.5 orest Quality in Selected Lan tions nvelope KW dscapes IN-SPIU-MP-81242-GO-RFQ / Investments for Improving F Request for Quota Single Stage - One E TF / A3990 Post Limited 28,500.00 28,862.76 Completed 2018-10-20 2019-01-25 2018-12-15 2019-02-23 2019-06-13 2019-03-04 Root trainer 150 cc and 250 orest Quality in Selected Lan tions nvelope cc-1 lac dscapes IN-SPIU-MP-86731-GO-RFQ / Sehore Forest Division (T) un der Range Budni in the ESIP Investments for Improving F Milli Watersheds has identifie Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 57,445.00 1.15 Completed 2018-12-05 2019-02-08 2019-01-30 2019-03-02 2019-07-29 2021-02-10 d three locations namely, Sa tions nvelope dscapes eedganj, Shahganj and Khatp ura where ten sites are selec ted to carry out plantation ac tivity. 54285 sq.m chain link i s required. IN-SPIU-MP-86784-GO-RFQ / Procurement of chain Link F Investments for Improving F ence 22950 Sq. Meter is to b Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 44,000.00 43,695.93 Completed 2018-12-04 2019-02-02 2019-01-29 2019-06-05 2019-07-28 2019-07-26 e done for 255 hectare plant tions nvelope dscapes ation in Comportment PF 391 , RF 131 and PF 389 under Bhaura Range, North Betul, D ivision IN-SPIU-MP-86789-GO-RFQ / Procurement of RCC Fencing Investments for Improving F Poles 6200 Number is to be Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 19,800.00 19,030.79 Completed 2018-12-04 2019-02-02 2019-01-29 2019-02-26 2019-07-28 2019-05-10 done for 255 hectare plantati tions nvelope dscapes on in Comportment PF 391, R F 131 and PF 389 under Bha ura Range, North Betul, Divisi on IN-SPIU-MP-87150-GO-RFQ / DFO (T) Hoshangabad in thre e Forest Ranges of Banapura Investments for Improving F Request for Quota Single Stage - One E - 300 Ha., Itarsi- 200 Ha. and TF / A3990 orest Quality in Selected Lan Post Limited 35,108.00 22,384.60 Completed 2018-12-11 2018-12-29 2019-02-05 2019-01-08 2019-08-04 2021-04-01 tions nvelope Sukhtawa- 100 Ha., covering dscapes five forest compartments is c arrying out plantations. RCC Poles for the above sites are required. IN-SPIU-MP-87151-GO-RFQ / DFO (T) Hoshangabad in thre e Forest Ranges of Banapura Investments for Improving F - 300 Ha., Itarsi- 200 Ha. and Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 11,401.00 1,153.12 Completed 2018-12-11 2018-12-29 2019-02-05 2019-01-08 2019-08-04 2019-07-01 Sukhtawa- 100 Ha., covering tions nvelope dscapes five forest compartments is c arrying out plantations. Barb ed Wire for the above sites a re required. IN-SPIU-MP-87153-GO-RFQ / DFO (T) Hoshangabad in thre e Forest Ranges of Banapura Investments for Improving F Request for Quota Single Stage - One E - 300 Ha., Itarsi- 200 Ha. and TF / A3990 orest Quality in Selected Lan Post Limited 60,686.00 42,481.95 Completed 2018-12-11 2018-12-29 2019-02-05 2019-01-08 2019-08-04 2019-07-01 tions nvelope Sukhtawa- 100 Ha., covering dscapes five forest compartments is c arrying out plantations. Chai n Link for the above sites are required. IN-SPIU-MP-86723-GO-RFQ / Sehore Forest Division (T) - R ange Budni in the ESIP Milli Investments for Improving F Watersheds has identified 03 Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 68,076.00 3.07 Completed 2018-12-05 2019-02-08 2019-01-30 2019-03-02 2019-07-29 2021-02-10 locations namely, Saeedganj, tions nvelope dscapes Shahganj and Khatpura wher e 10 sites covering 435 Ha. s elected to carry out plantatio ns. 17364 nos RCC Poles req uired for the sites. IN-SPIU-MP-86728-GO-RFQ / Sehore Forest Division (T) - R ange Budni in the ESIP Milli Watersheds has identified 03 Investments for Improving F Request for Quota Single Stage - One E locations namely, Saeedganj, TF / A3990 orest Quality in Selected Lan Post Limited 15,908.00 21,985.31 Completed 2018-12-05 2019-02-08 2019-01-30 2020-03-06 2019-07-29 2021-02-10 tions nvelope Shahganj and Khatpura wher dscapes e 10 sites covering 435 Ha. s elected to carry out plantatio ns. 18095 Kg Iron barbed wir e required for the sites IN-SPIU-MP-86733-GO-RFQ / Sehore Forest Division (T) - R ange Budni in the ESIP Milli Investments for Improving F Watersheds has identified 03 Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 205.00 183.29 Completed 2018-12-05 2019-01-23 2019-01-30 2019-01-24 2019-07-29 2019-01-24 locations namely, Saeedganj, tions nvelope dscapes Shahganj and Khatpura wher e 10 sites covering 435 Ha. s elected to carry out plantatio ns. 210 K.G. binding wire req uired for the sites. IN-SPIU-MP-86735-GO-RFQ / Sehore Forest Division (T) - R ange Budni in the ESIP Milli Watersheds has identified 03 Investments for Improving F Request for Quota Single Stage - One E locations namely, Saeedganj, TF / A3990 orest Quality in Selected Lan Post Limited 11,272.00 12,749.44 Completed 2018-12-05 2019-02-03 2019-01-30 2019-03-31 2019-07-29 2021-02-09 tions nvelope Shahganj and Khatpura wher dscapes e 10 sites covering 435 Ha. s elected to carry out plantatio ns. 3054 cement bags are re quired for the sites. IN-SPIU-MP-86737-GO-RFQ / Sehore Forest Division (T) - R ange Budni in the ESIP Milli Watersheds has identified 03 Investments for Improving F Request for Quota Single Stage - One E locations namely, Saeedganj, TF / A3990 orest Quality in Selected Lan Post Limited 5,623.00 29,244.43 Completed 2018-12-05 2019-02-05 2019-01-30 2019-03-31 2019-07-29 2021-02-09 tions nvelope Shahganj and Khatpura wher dscapes e 10 sites covering 435 Ha. s elected to carry out plantatio ns. 318 CMT. sand required f or the proposed sites. IN-SPIU-MP-86742-GO-RFQ / Sehore Forest Division (T) - R ange Budni in the ESIP Milli Investments for Improving F Watersheds has identified 03 Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 6,931.00 9,016.24 Completed 2018-12-05 2019-02-05 2019-01-30 2019-03-31 2019-07-29 2021-02-09 locations namely, Saeedganj, tions nvelope dscapes Shahganj and Khatpura wher e 10 sites covering 435 Ha. s elected to carry out plantatio ns. 636 CMT. metal 40MM re quired for the sites. Page 5 IN-SPIU-MP-86793-GO-RFQ / Procurement of barbed wire Investments for Improving F 6620 Kg. is to be done for 25 Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 5,750.00 5,938.66 Completed 2018-12-04 2019-02-02 2019-01-29 2019-02-26 2019-07-28 2019-05-09 5 hectare plantation in Comp tions nvelope dscapes ortment PF 391, RF 131 and PF 389 under Bhaura Range , North Betul, Division IN-SPIU-MP-80661-GO-RFQ / Investments for Improving F Request for Quota Single Stage - One E TF / A3990 Post Limited 7,150.00 6,329.22 Completed 2018-10-10 2019-02-23 2018-12-05 2019-03-06 2019-06-03 2019-06-04 Sprinkler set 200 beds orest Quality in Selected Lan tions nvelope dscapes IN-SPIU-MP-93440-GO-RFQ / Investments for Improving F CCF R&E CIRCLE BHOPAL Dri Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 1,420.00 1,443.31 Completed 2019-01-06 2019-02-23 2019-03-03 2019-03-06 2019-08-30 2019-03-20 nking water with R.O. For Bas tions nvelope dscapes apur nursery unit sehore IN-SPIU-MP-93767-GO-RFQ / Investments for Improving F Betul R&E MP Plans to prepar Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 14,285.00 0.00 Canceled 2019-01-26 2019-03-23 2019-09-19 ed vermi compost units in Kh tions nvelope dscapes akrapura Nursery Narmada U nit In Betul IN-SPIU-MP-93771-GO-RFQ / Investments for Improving F Betul R&E circle MP plans to Request for Quota Single Stage - One E Pending Impl TF / A3990 orest Quality in Selected Lan Post Limited 14,285.00 0.00 2019-01-26 2019-03-23 2019-09-19 prepare vermi compost units tions nvelope ementation dscapes in Dhar forest nursery IN-SPIU-MP-93871-GO-RFQ / Investments for Improving F Procurement of Densiometer Request for Quota Single Stage - One E Pending Impl TF / A3990 orest Quality in Selected Lan Post Limited 3,762.00 0.00 2019-01-26 2019-03-23 2019-09-19 for forest density mapping an tions nvelope ementation dscapes d field validation IN-SPIU-MP-102694-GO-DIR / The SPIU MP plans to procure Remote Sensing software ER Strengthen Capacity of Gove DAS Imagine Professional un rnment Institutions in Forest Under Imple der Component 1, Strengthe TF / A3990 ry and Land Management Pr Post Direct Selection Direct 28,600.00 0.00 2019-03-18 2019-05-10 2019-03-23 2019-05-25 2019-04-27 2019-10-24 mentation ning Capacity and Skills of G ograms in Madhya Pradesh a overnment Institutions for Eff nd Chhattisgarh ective Delivery of Forestry an d land Management Program s for Remote Sensing analysi s IN-SPIU-MP-102693-GO-DIR / The SPIU MP plans to procure Strengthen Capacity of Gove GIS software ARC GIS for sup rnment Institutions in Forest port under Component 1, Str Under Imple TF / A3990 ry and Land Management Pr Post Direct Selection Direct 28,600.00 0.00 2019-03-18 2019-05-10 2019-03-23 2019-05-25 2019-04-27 2019-10-24 engthening Capacity and Skil mentation ograms in Madhya Pradesh a ls of Government Institutions nd Chhattisgarh for Effective Delivery of Fores try and land Management Pr ograms. To carry out GIS bas ed analysis IN-SPIU-MP-100498-GO-RFQ / Procurement of RCC Fencin Investments for Improving F g Poles 1500 Number is to be Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 5,000.00 4,780.02 Completed 2019-05-25 2019-05-25 2019-07-20 2019-06-04 2020-01-16 2019-08-13 done for 29 hectare plantatio tions nvelope dscapes n in Comportment PF 400 un der Bhaura Range, North Bet ul, Division IN-SPIU-MP-100507-GO-RFQ / Procurement of Barbed wire Investments for Improving F Request for Quota Single Stage - One E 700 kg is to be done for 29 h TF / A3990 orest Quality in Selected Lan Post Limited 700.00 627.38 Completed 2019-05-25 2019-05-25 2019-07-20 2019-06-04 2020-01-16 2019-08-13 tions nvelope ectare plantation in Comport dscapes ment PF 400 under Bhaura R ange, North Betul, Division IN-SPIU-MP-100504-GO-RFQ / Procurement of Chain Link Investments for Improving F 5200 Sq meter is to be done Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 10,600.00 10,184.10 Completed 2019-05-25 2019-05-25 2019-07-20 2019-06-04 2020-01-16 2019-08-13 for 29 hectare plantation in C tions nvelope dscapes omportment PF 400 under B haura Range, North Betul, Di vision IN-SPIU-MP-150232-GO-RFQ Investments for Improving F / Documentation and publicit Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 8,000.00 12,635.71 Completed 2020-01-11 2020-02-07 2020-03-07 2020-02-08 2020-09-03 2020-02-08 y material development unde tions nvelope dscapes r ESIP Project in Budhni Rang e IN-SPIU-MP-146672-GO-RFQ / DFO (T) Hoshangabad to pr Investments for Improving F Request for Quota Single Stage - One E Under Imple ocure construction materials TF / A3990 orest Quality in Selected Lan Post Limited 50,000.00 0.00 2020-02-09 2020-02-25 2020-04-05 2020-10-02 tions nvelope mentation like bricks, sand,mettle, iron dscapes wire, iron rods, cement etc. IN-SPIU-MP-139576-GO-RFQ Investments for Improving F Request for Quota Single Stage - One E / Ccf research and extension TF / A3990 orest Quality in Selected Lan Post Limited 3,600.00 3,372.35 Completed 2020-02-09 2020-03-16 2020-04-05 2020-04-14 2020-10-02 2020-07-03 tions nvelope circle Bhopal CCTV Computer dscapes etc. IN-SPIU-MP-139582-GO-RFQ Investments for Improving F Request for Quota Single Stage - One E / Ccfre research and extensio TF / A3990 orest Quality in Selected Lan Post Limited 7,200.00 6,725.35 Completed 2020-02-05 2020-07-03 2020-04-01 2020-08-28 2020-09-28 2021-03-16 tions nvelope n circle Bhopal Signage for n dscapes ursery Basapur IN-SPIU-MP-138709-GO-RFQ Investments for Improving F Request for Quota Single Stage - One E / Ccf Research And Circle Bh TF / A3990 orest Quality in Selected Lan Post Limited 1,440.00 1,346.99 Completed 2020-02-09 2020-03-17 2020-04-05 2020-04-14 2020-10-02 2020-05-22 tions nvelope opal Cocopit Plant For Basap dscapes ur Nursery IN-SPIU-MP-146693-GO-RFQ Investments for Improving F Request for Quota Single Stage - One E / DFO (T) Hoshangabad to pr TF / A3990 orest Quality in Selected Lan Post Limited 23,000.00 11,163.81 Completed 2020-02-09 2020-02-25 2020-04-05 2020-03-08 2020-10-02 2021-04-01 tions nvelope ocure 900 nets dscapes IN-SPIU-MP-146689-GO-RFQ Investments for Improving F Request for Quota Single Stage - One E / DFO (T) Hoshangabad to pr TF / A3990 orest Quality in Selected Lan Post Limited 85,000.00 1.44 Completed 2020-02-09 2020-02-18 2020-04-05 2020-03-08 2020-10-02 2021-04-01 tions nvelope ocure fencing chain link mate dscapes rial IN-SPIU-MP-146690-GO-RFQ Investments for Improving F Request for Quota Single Stage - One E / DFO (T) Hoshangabad to pr TF / A3990 orest Quality in Selected Lan Post Limited 55,000.00 3.05 Completed 2020-02-05 2020-02-18 2020-04-01 2020-03-08 2020-09-28 2021-04-01 tions nvelope ocure R.C.C. Poles dscapes IN-SPIU-MP-139588-GO-RFQ Investments for Improving F / Ccfre research and extensio Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 5,760.00 1,373.22 Completed 2020-02-09 2020-07-03 2020-04-05 2020-08-08 2020-10-02 2020-10-15 n circle Bhopal nos 4 Soil tes tions nvelope dscapes ting machine for basapur IN-SPIU-MP-139586-GO-RFQ Investments for Improving F / Ccfre research and extensio Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 1,440.00 1,353.19 Completed 2020-02-09 2020-07-03 2020-04-05 2020-08-28 2020-10-02 2020-09-10 n circle Bhopal Furniture for tions nvelope dscapes Costumer visitor center Page 6 IN-SPIU-MP-139600-CW-RFQ Investments for Improving F / Ccfre research and extensio Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 5,760.00 5,385.69 Completed 2020-02-09 2020-08-19 2020-04-05 2020-09-24 2020-10-02 2020-12-24 n circle Bhopal Nos 04 Shad tions nvelope dscapes for soil testing machine basa pur IN-SPIU-MP-139598-CW-RFQ Investments for Improving F / Ccfre research and extensio Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 7,200.00 6,733.13 Completed 2020-02-09 2020-07-03 2020-04-05 2020-08-28 2020-10-02 2020-09-23 n circle Bhopal Sprinkler set tions nvelope dscapes s for 200 bed Basapur IN-SPIU-MP-138705-GO-RFQ Investments for Improving F Request for Quota Single Stage - One E TF / A3990 Post Limited 2,880.00 2,695.28 Completed 2020-02-09 2020-03-17 2020-04-05 2020-04-14 2020-10-02 2020-05-24 / CCf R&E 08 Nos Solar Light orest Quality in Selected Lan tions nvelope dscapes IN-SPIU-MP-149212-GO-RFQ Investments for Improving F Request for Quota Single Stage - One E TF / A3990 Post Limited 7,400.00 0.93 Completed 2020-02-09 2020-03-13 2020-04-05 2020-03-20 2020-10-02 2021-02-02 / Procurement of Barbed wire orest Quality in Selected Lan tions nvelope 5229 kg. dscapes IN-SPIU-MP-150299-GO-RFQ Investments for Improving F Request for Quota Single Stage - One E TF / A3990 Post Limited 28,300.00 28.06 Completed 2020-02-09 2020-03-13 2020-04-05 2020-03-20 2020-10-02 2021-07-04 / DFO (T) Betul to procure 10 orest Quality in Selected Lan tions nvelope 00 nets dscapes IN-SPIU-MP-100807-GO-RFQ / Procurement of Metal 300 c Investments for Improving F mt for installing RCC Poles is Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 4,264.00 0.00 Canceled 2019-05-25 2019-07-20 2020-01-16 to be done for plantation in C tions nvelope dscapes ompartment PF 391, RF 131 , PF 389 and PF 400 under Bha ura Range, North Betul, Divisi on IN-SPIU-MP-100813-GO-RFQ / Procurement of Cement 150 0 Bags for installing RCC Pole Investments for Improving F Request for Quota Single Stage - One E s is to be done for plantation TF / A3990 orest Quality in Selected Lan Post Limited 6,150.00 0.00 Canceled 2019-05-25 2019-07-20 2020-01-16 tions nvelope in Compartment PF 391, RF 1 dscapes 31 , PF 389 and PF 400 under Bhaura Range, North Betul, D ivision IN-SPIU-MP-100811-GO-RFQ / Procurement of Sand 150 c Investments for Improving F mt for installing RCC Poles is Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 2,352.00 0.00 Canceled 2019-05-25 2019-07-20 2020-01-16 to be done for plantation in C tions nvelope dscapes ompartment PF 391, RF 131 , PF 389 and PF 400 under Bha ura Range, North Betul, Divisi on IN-SPIU-MP-155097-GO-RFQ Request for Quota Single Stage - One E Under Imple TF / A3990 Project Management Post Limited 5,000.00 0.00 2020-02-09 2021-06-21 2020-04-05 2020-10-02 / LCD Display Unit, Laptops, tions nvelope mentation Desk Top IN-SPIU-MP-150209-GO-RFQ Request for Quota Single Stage - One E / In ESIP project for office use TF / A3990 Project Management Post Limited 10,000.00 1,905.98 Completed 2020-01-11 2020-02-07 2020-03-07 2020-02-08 2020-09-03 2020-02-08 tions nvelope (laptop/computer/Stationary etc.) IN-SPIU-MP-149209-GO-RFQ Investments for Improving F / Procurement of chain link F Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 88,922.00 1.52 Completed 2020-03-28 2020-03-13 2020-05-23 2020-03-20 2020-11-19 2021-02-02 ence 54900 Sq. Meter by Nor tions nvelope dscapes th Betul (T.) Division IN-SPIU-MP-149210-GO-RFQ Investments for Improving F Request for Quota Single Stage - One E / Procurement of R.C.C. Fenci TF / A3990 orest Quality in Selected Lan Post Limited 55,516.00 3.49 Completed 2020-03-17 2020-03-13 2020-05-12 2020-03-20 2020-11-08 2021-02-02 tions nvelope ng Poles North Betul (T.) Divi dscapes sion IN-SPIU-MP-201900-GO-RFQ Investments for Improving F / Forest Division Sehore in Bu Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 11,647.00 18,033.53 Completed 2020-12-17 2021-01-20 2021-02-11 2021-02-04 2021-08-10 2021-04-01 dhni Range RCC Poles for cov tions nvelope dscapes ering Plantation Area IN-SPIU-MP-201904-GO-RFQ Investments for Improving F Request for Quota Single Stage - One E / Mahua Net for Forest Divisio TF / A3990 orest Quality in Selected Lan Post Limited 32,143.00 26,672.65 Completed 2020-12-17 2021-03-10 2021-02-11 2021-03-16 2021-08-10 2021-04-01 tions nvelope n Sehore in Budhni Range ES dscapes IP project IN-SPIU-MP-206259-GO-RFQ Investments for Improving F / Procurement of chain link F Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 45,500.00 44,889.29 Completed 2020-12-19 2020-12-31 2021-02-13 2021-01-31 2021-08-12 2021-03-25 ence 22404 Sq. Meter by Nor tions nvelope dscapes th Betul (T.) Division IN-SPIU-MP-206283-GO-RFQ Investments for Improving F / Procurement of P. R.C.C. Fe Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 19,900.00 18,823.87 Completed 2020-12-19 2020-12-31 2021-02-13 2021-01-31 2021-08-12 2021-03-25 ncing Poles 5574 Number by tions nvelope dscapes North Betul (T.) Division IN-SPIU-MP-206292-GO-RFQ Investments for Improving F Request for Quota Single Stage - One E / Procurement of Barbed wire TF / A3990 orest Quality in Selected Lan Post Limited 5,000.00 4,772.59 Completed 2020-12-19 2020-12-31 2021-02-13 2021-01-31 2021-08-12 2021-03-25 tions nvelope 4979 kg. by North Betul (T.) dscapes Division IN-SPIU-MP-206387-GO-RFQ Investments for Improving F Request for Quota Single Stage - One E / Hoshangabad Forest Divisio TF / A3990 orest Quality in Selected Lan Post Limited 3,600.00 2,567.49 Completed 2020-12-17 2020-12-11 2021-02-11 2021-01-06 2021-08-10 2021-02-05 tions nvelope n Procurement of Barbed Wir dscapes e IN-SPIU-MP-206388-GO-RFQ Investments for Improving F Request for Quota Single Stage - One E / Hoshangabad Forest Divisio TF / A3990 orest Quality in Selected Lan Post Limited 3,200.00 2,136.96 Completed 2020-12-17 2020-12-11 2021-02-11 2021-01-06 2021-08-10 2021-02-03 tions nvelope n Procurement of Mettle for fi dscapes xing poles IN-SPIU-MP-206389-GO-RFQ Investments for Improving F Request for Quota Single Stage - One E / Hoshangabad Forest Divisio TF / A3990 orest Quality in Selected Lan Post Limited 3,250.00 2,746.03 Completed 2020-12-17 2020-12-11 2021-02-11 2021-01-06 2021-08-10 2021-02-03 tions nvelope n Procurement of Cement dscapes IN-SPIU-MP-206391-GO-RFQ Investments for Improving F Request for Quota Single Stage - One E / Hoshangabad Forest Divisio TF / A3990 orest Quality in Selected Lan Post Limited 27,850.00 18,734.09 Completed 2020-12-17 2020-12-11 2021-02-11 2021-01-06 2021-08-10 2021-02-03 tions nvelope n Procurement of Chain Link dscapes Fencing IN-SPIU-MP-206392-GO-RFQ Investments for Improving F Request for Quota Single Stage - One E / Hoshangabad Forest Divisio TF / A3990 orest Quality in Selected Lan Post Limited 15,000.00 12,436.61 Completed 2020-12-17 2020-12-18 2021-02-11 2021-01-06 2021-08-10 2021-02-03 tions nvelope n Procurement of R.C.C. Pole dscapes s IN-SPIU-MP-206394-GO-RFQ Investments for Improving F Request for Quota Single Stage - One E / Hoshangabad Forest Divisio TF / A3990 orest Quality in Selected Lan Post Limited 14,300.00 11,732.15 Completed 2020-12-17 2020-12-18 2021-02-11 2021-01-06 2021-08-10 2021-07-06 tions nvelope n Procurement of Mahua Net dscapes s IN-SPIU-MP-201898-GO-RFQ Investments for Improving F / Forest Division Sehore in Bu Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 4,021.00 9,763.45 Completed 2021-03-02 2021-01-19 2021-04-27 2021-01-20 2021-10-24 2021-04-01 dhni Range Barbed wire quan tions nvelope dscapes tity 4113 KG for covering Pla ntation Area Page 7 IN-SPIU-MP-201893-GO-RFQ Investments for Improving F / Forest Division Sehore in Bu Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 25,996.00 39,024.44 Completed 2021-03-02 2021-01-19 2021-04-27 2021-01-20 2021-10-24 2021-04-01 dhni Range chainlink jali qunt tions nvelope dscapes ity 12337 RM for covering pla ntation area IN-SPIU-MP-222793-GO-RFQ / ccfre Bhopal, Establishment Investments for Improving F Request for Quota Single Stage - One E of Soil Testing Laboratory at TF / A3990 orest Quality in Selected Lan Post Limited 11,180.00 10,495.17 Completed 2021-09-11 2021-10-06 2021-11-06 2022-03-09 2022-05-05 2022-03-26 tions nvelope Ahamadpur Nursery, procure dscapes ment of lab equipments IN-SPIU-MP-247772-GO-RFQ Investments for Improving F / Procurement of P.R.C.C. Fen Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 24,350.00 22,039.96 Completed 2021-09-01 2021-09-29 2021-10-27 2021-10-12 2022-04-25 2022-03-16 cing Poles 6820 Number by N tions nvelope dscapes orth Betul (T.) Division IN-SPIU-MP-247782-GO-RFQ Investments for Improving F / Hoshangabad division for p Request for Quota Single Stage - One E Under Imple TF / A3990 orest Quality in Selected Lan Post Limited 39,403.00 0.00 2021-09-11 2021-09-17 2021-11-06 2022-05-05 urchase of Mahua Net in rang tions nvelope mentation dscapes e Sukhatwa, Itarsi and Banap ura IN-SPIU-MP-247777-GO-RFQ Investments for Improving F / Hoshangabad division for p Request for Quota Single Stage - One E Under Imple TF / A3990 orest Quality in Selected Lan Post Limited 42,880.00 0.00 2021-09-11 2021-09-17 2021-11-06 2022-05-05 urchase of chain link fencing tions nvelope mentation dscapes in Sukhatwa, Itarsi and Bana pura IN-SPIU-MP-247779-GO-RFQ Investments for Improving F / Hoshangabad division for p Request for Quota Single Stage - One E Under Imple TF / A3990 orest Quality in Selected Lan Post Limited 25,724.00 0.00 2021-09-11 2021-09-17 2021-11-06 2022-05-05 urchase of RCC Poles for fenc tions nvelope mentation dscapes ing in Sukhatwa, Itarsi and B anapura IN-SPIU-MP-247768-GO-RFQ Investments for Improving F Request for Quota Single Stage - One E / Procurement of Barbed wire TF / A3990 orest Quality in Selected Lan Post Limited 5,550.00 5,465.09 Completed 2021-09-11 2021-09-29 2021-11-06 2021-10-12 2022-05-05 2022-03-18 tions nvelope 5684 kg. by North Betul (T.) dscapes Division IN-SPIU-MP-247774-GO-RFQ Investments for Improving F / Hoshangabad division for P Request for Quota Single Stage - One E Under Imple TF / A3990 orest Quality in Selected Lan Post Limited 6,917.00 0.00 2021-09-11 2021-09-17 2021-11-06 2022-05-05 urchase of Barbed Wire for fe tions nvelope mentation dscapes ncing in range Sukhatwa, Itar si and Banapura IN-SPIU-MP-247770-GO-RFQ Investments for Improving F / Procurement of chain link F Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 51,700.00 51,229.24 Completed 2021-09-11 2021-09-29 2021-11-06 2021-10-12 2022-05-05 2022-02-01 ence 25575 Sq. Meter by Nor tions nvelope dscapes th Betul (T.) Division IN-SPIU-MP-244994-GO-DIR / Investments for Improving F Under Imple Purchase of satellite imagery TF / A3990 orest Quality in Selected Lan Post Direct Selection Direct 54,000.00 0.00 2021-09-20 2021-07-28 2021-09-25 2021-10-30 2022-04-28 mentation & analysis dscapes IN-SPIU-MP-252274-GO-RFQ / Chainlink Jali to be purchas Investments for Improving F Request for Quota Single Stage - One E e for use in 100 hact. Pilikara TF / A3990 orest Quality in Selected Lan Post Limited 24,892.00 20,706.31 Signed 2021-09-12 2021-10-27 2021-11-07 2021-11-10 2022-05-06 tions nvelope r year 2021-22 Sehore Divisi dscapes on Range Budhni under ESIP IN-SPIU-MP-252277-GO-RFQ / Barbed wire to be purchase Investments for Improving F Request for Quota Single Stage - One E for use in 100 hact. Pilikarar TF / A3990 orest Quality in Selected Lan Post Limited 5,840.00 3,987.01 Signed 2021-09-12 2021-10-27 2021-11-07 2021-11-10 2022-05-06 tions nvelope year 2021-22 Sehore Division dscapes Range Budhni under ESIP IN-SPIU-MP-252279-GO-RFQ / Binding wire to be purchase Investments for Improving F Request for Quota Single Stage - One E for use in 100 hact. Pilikarar TF / A3990 orest Quality in Selected Lan Post Limited 184.00 151.06 Signed 2021-09-12 2021-10-27 2021-11-07 2021-11-10 2022-05-06 tions nvelope year 2021-22 Sehore Division dscapes Range Budhni under ESIP IN-SPIU-MP-252429-GO-RFQ / Cement to be purchase for Investments for Improving F Request for Quota Single Stage - One E use in 100 hact. Pilikarar yea TF / A3990 orest Quality in Selected Lan Post Limited 3,830.00 1,582.17 Signed 2021-09-13 2021-09-28 2021-11-08 2021-11-18 2022-05-07 tions nvelope r 2021-22 Sehore Division Ra dscapes nge Budhni under ESIP IN-SPIU-MP-252431-GO-RFQ Investments for Improving F / Sand to be purchase for use Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 857.00 740.24 Signed 2021-09-13 2021-09-28 2021-11-08 2021-11-18 2022-05-07 in 100 hact. Pilikarar year 20 tions nvelope dscapes 21-22 Sehore Division Range Budhni under ESIP IN-SPIU-MP-252432-GO-RFQ Investments for Improving F / Metal to be purchase for us Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 1,516.00 869.73 Signed 2021-09-13 2021-09-28 2021-11-08 2021-11-18 2022-05-07 e in 100 hact. Pilikarar year 2 tions nvelope dscapes 021-22 Sehore Division Rang e Budhni under ESIP IN-SPIU-MP-139594-GO-RFQ Investments for Improving F Request for Quota Single Stage - One E / Ccfre research and extensio TF / A3990 orest Quality in Selected Lan Post Limited 1,440.00 0.00 Canceled 2020-02-05 2020-04-01 2020-09-28 tions nvelope n circle Bhopal Nos 04 Soil t dscapes esting kits IN-SPIU-MP-262773-GO-RFQ Investments for Improving F / Procurement of Oven-gas fir Request for Quota Single Stage - One E Pending Impl TF / A3990 orest Quality in Selected Lan Post Limited 6,500.00 0.00 2021-12-05 2022-01-30 2022-07-29 ed and weight Machine for N tions nvelope ementation dscapes TFP based Bakery by North B etul IN-SPIU-MP-146676-GO-DIR / Investments for Improving F Request for Quota Single Stage - One E DFO (T) Hoshangabad to pro TF / A3990 orest Quality in Selected Lan Post Limited 3,000.00 0.00 Canceled 2020-02-09 2020-04-05 2020-10-02 tions nvelope cure bamboo poles dscapes IN-SPIU-MP-93298-GO-RFQ / DFO (T) Hoshangabad in thre e Forest Ranges of Banapura Investments for Improving F - 300 Ha., Itarsi- 200 Ha. and Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 5,205.00 0.00 Canceled 2019-01-15 2019-03-12 2019-09-08 Sukhtawa- 100 Ha., covering tions nvelope dscapes five forest compartments is c arrying out plantations. Cem ent Bags for the above sites are required. IN-SPIU-MP-146680-GO-RFQ Investments for Improving F / DFO (T) Hoshangabad to pr Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 28,000.00 0.00 Canceled 2020-02-05 2020-04-01 2020-09-28 ocure iron based materials li tions nvelope dscapes ke iron boards, iron gate, roo fin tin material etc. Page 8 IN-SPIU-MP-93317-GO-RFQ / DFO (T) Hoshangabad in thre e Forest Ranges of Banapura Investments for Improving F - 300 Ha., Itarsi- 200 Ha. and Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 2,870.00 0.00 Canceled 2019-01-15 2019-03-12 2019-09-08 Sukhtawa- 100 Ha., covering tions nvelope dscapes five forest compartments is c arrying out plantations. Bam boo Poles two metres in leng th for the above sites are req uired. IN-SPIU-MP-146679-GO-RFQ Investments for Improving F Request for Quota Single Stage - One E / DFO (T) Hoshangabad to pr TF / A3990 orest Quality in Selected Lan Post Limited 30,000.00 0.00 Canceled 2020-02-09 2020-04-05 2020-10-02 tions nvelope ocure compost, bone meal, e dscapes tc. IN-SPIU-MP-93297-GO-RFQ / DFO (T) Hoshangabad in thre e Forest Ranges of Banapura Investments for Improving F - 300 Ha., Itarsi- 200 Ha. and Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 1,400.00 0.00 Canceled 2019-01-15 2019-03-12 2019-09-08 Sukhtawa- 100 Ha., covering tions nvelope dscapes five forest compartments is c arrying out plantations. Bindi ng Wire for the above sites a re required. IN-SPIU-MP-93305-GO-RFQ / DFO (T) Hoshangabad in thre e Forest Ranges of Banapura Investments for Improving F - 300 Ha., Itarsi- 200 Ha. and Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 1,771.00 0.00 Canceled 2019-01-15 2019-03-12 2019-09-08 Sukhtawa- 100 Ha., covering tions nvelope dscapes five forest compartments is c arrying out plantations. 100 CMT sand for the above sites are required. IN-SPIU-MP-93315-GO-RFQ / DFO (T) Hoshangabad in thre e Forest Ranges of Banapura, Itarsi and Sukhtawa, for gend Investments for Improving F Request for Quota Single Stage - One E er based livelihood initiative TF / A3990 orest Quality in Selected Lan Post Limited 18,642.00 0.00 Canceled 2019-01-15 2019-03-12 2019-09-08 tions nvelope plans to distribute sewing ma dscapes chines to poor women. The s ewing machines shall be dist ributed in the villages covere d under the project areas IN-SPIU-MP-93303-GO-RFQ / DFO (T) Hoshangabad in thre e Forest Ranges of Banapura Investments for Improving F - 300 Ha., Itarsi- 200 Ha. and Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 3,000.00 0.00 Canceled 2019-01-15 2019-03-12 2019-09-08 Sukhtawa- 100 Ha., covering tions nvelope dscapes five forest compartments is c arrying out plantations. Metal 191 CMT for the above sites are required. IN-SPIU-MP-93318-GO-RFQ / DFO (T) Hoshangabad in thre e Forest Ranges of Banapura Investments for Improving F - 300 Ha., Itarsi- 200 Ha. and Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 2,859.00 0.00 Canceled 2019-01-15 2019-03-12 2019-09-08 Sukhtawa- 100 Ha., covering tions nvelope dscapes five forest compartments is c arrying out plantations. Tin r oofing materia for the above sites are required. IN-SPIU-MP-206393-GO-RFQ Investments for Improving F Request for Quota Single Stage - One E / Hoshangabad Forest Divisio TF / A3990 orest Quality in Selected Lan Post Limited 1,000.00 0.00 Canceled 2020-12-17 2021-02-11 2021-08-10 tions nvelope n Procurement of Computers dscapes IN-SPIU-MP-252272-GO-RFQ / PRCC Poles to be purchase f Investments for Improving F Request for Quota Single Stage - One E or use in 100 hact. Pilikarar y TF / A3990 orest Quality in Selected Lan Post Limited 11,310.00 7,174.18 Signed 2022-02-01 2022-01-18 2022-03-29 2022-01-19 2022-09-25 tions nvelope ear 2021-22 Sehore Division dscapes Range Budhni under ESIP IN-SPIU-MP-257122-GO-RFQ / Display board for advertisin Investments for Improving F Request for Quota Single Stage - One E Pending Impl g to be purchase for use in S TF / A3990 orest Quality in Selected Lan Post Limited 2,985.00 0.00 2022-02-01 2022-03-29 2022-09-25 tions nvelope ementation ehore Division Range Budhni dscapes year 2021-22 under ESIP IN-SPIU-MP-257070-GO-RFQ Investments for Improving F / Mahua Net to be purchase f Request for Quota Single Stage - One E Under Imple TF / A3990 orest Quality in Selected Lan Post Limited 4,403.00 0.00 2022-01-27 2021-09-15 2022-02-01 2022-03-15 2022-04-14 2022-05-19 2022-11-15 or use Sehore Division Rang tions nvelope mentation dscapes e Budhni year 2021-22 under ESIP IN-SPIU-MP-257079-GO-RFQ / Beehive Box and artificial h Investments for Improving F Request for Quota Single Stage - One E oney collection kit to be purc TF / A3990 orest Quality in Selected Lan Post Limited 4,226.00 11,281.37 Signed 2022-02-01 2021-12-06 2022-03-29 2021-12-22 2022-09-25 tions nvelope hase for use in Sehore Divisi dscapes on Range Budhni year 2021- 22 under ESIP IN-SPIU-MP-283360-GO-RFQ Request for Quota Single Stage - One E TF / A3990 Project Management Post Limited 2,508.00 0.00 Canceled 2022-03-26 2022-05-21 2022-11-17 / Furniture for SPIU M.P. offic tions nvelope e in Bhopal. Strengthen Capacity of Gove IN-SPIU-MP-283357-GO-RFQ rnment Institutions in Forest Request for Quota Single Stage - One E Under Imple / Laptop for GIS monitoring a TF / A3990 Post Limited 3,732.00 0.00 2022-03-26 2022-10-07 2022-05-21 2022-11-17 ry and Land Management Pr tions nvelope mentation nd evaluation. ograms in Madhya Pradesh a nd Chhattisgarh IN-SPIU-MP-208125-GO-RFQ / 104.40 Cmt. Sand with appr Investments for Improving F oximate rate Rs. 997.50 per Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 1,488.00 0.00 Canceled 2021-02-28 2021-04-25 2021-10-22 Cmt. amounting to Rs. 10412 tions nvelope dscapes 9 or 1488 dollar is required t o fix fencing poles to protect plantations of the year 2021- 2022 IN-SPIU-MP-208126-GO-RFQ / 208.78 Cmt. Mettal with ap Investments for Improving F proximate rate Rs. 882 per C Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 2,631.00 0.00 Canceled 2021-02-28 2021-04-25 2021-10-22 mt. amounting to Rs. 184144 tions nvelope dscapes or 2631 dollar is required to f ix fencing poles to protect pl antations of the year 2021-2 022 IN-SPIU-MP-208124-GO-RFQ / Cement 1002 Bags at appro Investments for Improving F ximate rate Rs. 309.76 per b Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 4,434.00 0.00 Canceled 2021-02-28 2021-04-25 2021-10-22 ag amounting to Rs. 310380 tions nvelope dscapes or 4434 dollar is required to f ix fencing poles to protect pl antations of the year 2021-2 022 Page 9 IN-SPIU-MP-329874-GO-RFQ / Mahua Net to be purchased Investments for Improving F Request for Quota Single Stage - One E Under Imple for use in Hoshangabad divisi TF / A3990 orest Quality in Selected Lan Post Limited 67,000.00 0.00 2022-12-20 2022-12-14 2023-02-14 2023-08-13 tions nvelope mentation on Range SUKTAWA , ITARSI dscapes AND BANAPURA for year 202 2-2023 under ESIP. IN-SPIU-MP-330163-GO-RFQ Investments for Improving F / CF Social forestry circle Bho Request for Quota Single Stage - One E Under Imple TF / A3990 orest Quality in Selected Lan Post Limited 1,493.00 0.00 2022-12-17 2023-03-06 2023-02-11 2023-08-10 pal Purchase of laptop for So tions nvelope mentation dscapes cial forestry circle Bhopal, u nder GIM. IN-SPIU-MP-347640-GO-RFQ Investments for Improving F Request for Quota Single Stage - One E Under Imple TF / A3990 Post Limited 6,668.00 0.00 2023-03-20 2023-03-15 2023-05-15 2023-11-11 / DFO (T) Betul to procure 52 orest Quality in Selected Lan tions nvelope mentation 5 nets dscapes IN-SPIU-MP-350335-GO-RFQ Scaling-up Sustainable Land Request for Quota Single Stage - One E Pending Impl / Desk Top for North Betul Di TF / A3990 and Ecosystem Management Post Limited 1,500.00 0.00 2023-03-29 2023-05-24 2023-11-20 tions nvelope ementation vision in Selected Landscapes IN-SPIU-MP-353199-GO-RFQ Investments for Improving F Request for Quota Single Stage - One E / Mahua net purchase for use TF / A3990 orest Quality in Selected Lan Post Limited 22,388.00 0.00 Signed 2023-04-05 2023-01-27 2023-05-31 2023-11-27 tions nvelope in ESIP Project year 2022-23 dscapes IN-SPIU-MP-362202-GO-RFQ / CF Social forestry circle Bho pal Purchase of CCTV Camer Investments for Improving F Request for Quota Single Stage - One E Pending Impl a with Monitor and Wi Fi , 4 TF / A3990 orest Quality in Selected Lan Post Limited 5,970.00 0.00 2023-06-03 2023-07-29 2024-01-25 tions nvelope ementation Nos for Office of Social fores dscapes try circle Bhopal , Bhadbhada Nursery, Amarawad first , an d Badi Nursery under GIM. IN-SPIU-MP-362230-GO-RFQ Investments for Improving F / CF Social forestry circle Bho Request for Quota Single Stage - One E Pending Impl TF / A3990 orest Quality in Selected Lan Post Limited 1,493.00 0.00 2023-06-03 2023-07-29 2024-01-25 pal Purchase of LED Screen f tions nvelope ementation dscapes or Ahamadpur Nursery Bhop al, under GIM. IN-SPIU-MP-362237-GO-RFQ / CF Social forestry circle Bho pal Purchase of Computer Sy Investments for Improving F stem with Printer and Comp Request for Quota Single Stage - One E Pending Impl TF / A3990 orest Quality in Selected Lan Post Limited 7,463.00 0.00 2023-06-03 2023-07-29 2024-01-25 uter Table , Chair for Social tions nvelope ementation dscapes forestry circle Bhopal, Bhopal Unit , Ahamadpur Nursery , B asapur Nursery and Amaraw ad First Nursery 5 Nos. und er GIM. IN-SPIU-MP-362254-GO-RFQ / CF Social forestry circle Bho pal Purchase of Solar street li Investments for Improving F ght for Ahamadpur , Bhadb Request for Quota Single Stage - One E Pending Impl TF / A3990 orest Quality in Selected Lan Post Limited 28,358.00 0.00 2023-06-03 2023-07-29 2024-01-25 hada, Garethiya, Thoona, Am tions nvelope ementation dscapes arawad first, Mudiyakheda, B adi, Holipura, Imaliya Nurseri es for Each 8 nos. and Amara wad second nursery for 4 no s, under GIM. IN-SPIU-MP-365870-GO-RFQ Investments for Improving F Request for Quota Single Stage - One E Pending Impl / Mahua Net for use in ESIP P TF / A3990 orest Quality in Selected Lan Post Limited 73,881.00 0.00 2023-06-20 2023-08-15 2024-02-11 tions nvelope ementation roject BUDHNI Year 2023-24 dscapes IN-SPIU-MP-365925-GO-RFQ / DFO (T) Betul for the ESIP p roject intends to procure 300 Investments for Improving F 0 nets for distribution to fore Request for Quota Single Stage - One E Pending Impl TF / A3990 orest Quality in Selected Lan Post Limited 67,200.00 0.00 2023-06-20 2023-08-15 2024-02-11 st dependent tribal families f tions nvelope ementation dscapes or sustainable collection of M ahua as forest produce under livelihood initiatives from the forest landscape of ESIP IN-SPIU-MP-366024-GO-RFQ Investments for Improving F / DFO (T) Betul for the ESIP p Request for Quota Single Stage - One E Pending Impl TF / A3990 orest Quality in Selected Lan Post Limited 9,725.00 0.00 2023-06-20 2023-08-15 2024-02-11 roject intends to procure 7 K tions nvelope ementation dscapes W solar panel system for Ma hua Bakery Unit NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-SPIU-MP-40458-NC-RFQ / Request for Quota Single Stage - One E Hiring/Renting of Vehicles fo TF / A3990 Project Management Post Open - National 30,000.00 11,500.41 Signed 2018-01-20 2018-03-17 2018-08-20 2019-03-17 tions nvelope r SPIU (Scorpio, Bolero & pool vehicle etc.) IN-SPIU-MP-150230-CS-INDV Strengthen Capacity of Gove / Village/Range/Division level rnment Institutions in Forest Request for Quota Single Stage - One E TF / A3990 Post Limited 19,000.00 0.00 Canceled 2020-01-11 2020-03-07 2020-09-03 awareness workshope for ESI ry and Land Management Pr tions nvelope P Landscapes ograms in Madhya Pradesh a nd Chhattisgarh IN-SPIU-MP-150236-CS-INDV Strengthen Capacity of Gove / Skill development training f rnment Institutions in Forest Request for Quota Single Stage - One E TF / A3990 Post Limited 23,000.00 65,986.66 Completed 2020-01-11 2020-01-13 2020-03-07 2020-01-14 2020-09-03 2020-01-14 or youth in Budhni Range un ry and Land Management Pr tions nvelope der ESIP Project. ograms in Madhya Pradesh a nd Chhattisgarh IN-SPIU-MP-150208-NC-RFQ / Request for Quota Single Stage - One E TF / A3990 Project Management Post Limited 7,000.00 474.39 Signed 2020-02-09 2020-01-08 2020-04-05 2020-03-01 2021-11-26 dfo(T) Sehore field vehicle re tions nvelope nt. IN-SPIU-MP-165054-NC-RFQ / Hiring/Renting of Vehicles for Request for Quota Single Stage - One E Under Imple TF / A3990 Project Management Post Limited 20,000.00 0.00 2020-04-02 2021-06-18 2020-05-28 2021-03-31 SPIU (Scorpio/Bolero/Innova tions nvelope mentation & pool vehicle etc.) IN-SPIU-MP-244511-CW-RFQ / Doccumentary on ESIP Seho Request for Quota Single Stage - One E re, Budhni, Shahganj & other TF / A3990 Project Management Post Limited 1,429.00 1,335.40 Signed 2021-09-11 2021-07-19 2021-11-06 2021-07-21 2022-05-05 tions nvelope areas. Duration 03 Minutes f or social media Awareness. F ormat full HD IN-SPIU-MP-146692-NC-RFQ / Request for Quota Single Stage - One E DFO (T) Hoshangabad to pro TF / A3990 Project Management Post Limited 14,000.00 0.00 Canceled 2020-02-09 2020-04-05 2021-12-01 tions nvelope cure a field vehicle CONSULTING FIRMS Page 10 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-SPIU-MP-100441-CS-CQS / Strengthen Capacity of Gove To develop an IEC strategy a rnment Institutions in Forest Consultant Qualifi Under Implement TF / A3990 Post Open - National 35,000.00 0.00 2019-05-25 2019-07-10 2019-06-15 2019-07-29 2021-06-18 2019-08-28 2019-10-02 2023-02-08 nd implementation plan for t ry and Land Management Pr cation Selection ation he project areas. ograms in Madhya Pradesh a nd Chhattisgarh IN-SPIU-MP-103531-CS-CDS / Sustainable Harvesting Proto cols, Value Addition and Valu e Chain Development to Non- Investments for Improving F Consultant Qualifi Timber Forest Products (NTF TF / A3990 orest Quality in Selected Lan Post Open - National 75,000.00 100,981.99 Signed 2019-05-25 2019-07-10 2019-06-15 2019-07-29 2021-02-11 2019-08-28 2021-06-21 2019-10-02 2021-07-03 2020-03-30 cation Selection P) in Selected Districts of Ma dscapes dhya Pradesh, India under co mponent 2.2 Developing Co mmunity Based Models for S ustainable Utlization of NTFP. IN-SPIU-MP-103730-CS-CDS / selection of an organization f Strengthen Capacity of Gove or consultancy- protocol dev rnment Institutions in Forest Consultant Qualifi elopment for biodiversity me TF / A3990 ry and Land Management Pr Post Open - National 75,000.00 0.00 Canceled 2019-05-25 2019-07-10 2019-06-15 2019-07-29 2019-08-28 2019-10-02 2020-03-30 cation Selection asurements in select location ograms in Madhya Pradesh a s for preparing biodiversity m nd Chhattisgarh anagement plans, especially in corridors. IN-SPIU-MP-268737-CS-CQS / High resolution satellite imag Investments for Improving F Consultant Qualifi Under Implement e processing of forest change TF / A3990 orest Quality in Selected Lan Post Open - National 18,000.00 0.00 2021-12-20 2022-01-12 2022-01-10 2022-02-23 2022-06-29 2022-03-25 2022-04-29 2022-10-26 cation Selection ation and plantation monitoring un dscapes der ESIP treated areas. IN-SPIU-MP-300885-CS-CQS / Investments for Improving F Consultant Qualifi Cost Benefit Analysis of NTFP TF / A3990 orest Quality in Selected Lan Post Open - National 18,000.00 0.00 Canceled 2022-06-30 2022-06-30 2022-07-21 2022-09-03 2022-10-03 2022-11-07 2023-05-06 cation Selection enterprise (Mahua Bakery En dscapes terprise). INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-SPIU-MP-40448-CS-INDV / Strengthen Capacity of Gove Hiring of Individual Consultan rnment Institutions in Forest Individual Consult TF / A3990 Post Open 30,000.00 21,783.90 Completed 2018-01-15 2018-05-03 2018-03-05 2018-08-21 2018-03-26 2018-09-29 2018-04-30 2018-09-30 2019-04-30 2019-10-07 t for Forestry/Ecosystem Serv ry and Land Management Pr ant Selection ice & Knowledge manageme ograms in Madhya Pradesh a nt Specialist nd Chhattisgarh IN-SPIU-MP-40450-CS-INDV / Strengthen Capacity of Gove Hiring of Individual Consultan rnment Institutions in Forest Individual Consult TF / A3990 Post Open 30,000.00 19,154.03 Signed 2018-01-15 2018-01-16 2018-03-05 2018-05-31 2018-03-26 2018-07-03 2018-04-30 2018-06-21 2019-04-30 t for Database and GIS Exper ry and Land Management Pr ant Selection t ograms in Madhya Pradesh a nd Chhattisgarh IN-SPIU-MP-40451-CS-INDV / Strengthen Capacity of Gove Hiring of Individual Consultan rnment Institutions in Forest Individual Consult Under Implement TF / A3990 Post Open 30,000.00 0.00 2018-01-15 2019-11-18 2018-03-05 2021-05-19 2018-03-26 2018-04-30 2019-04-30 t for Social Development/Co ry and Land Management Pr ant Selection ation mmunity Mobilization ograms in Madhya Pradesh a nd Chhattisgarh IN-SPIU-MP-60724-CS-CDS / Strengthen Capacity of Gove selection of consultant for pr rnment Institutions in Forest otocol development for biodi TF / A3990 ry and Land Management Pr Post Direct Selection Direct - National 60,000.00 0.00 Canceled 2018-05-14 2018-05-25 2018-06-25 2019-03-31 versity measurements in sele ograms in Madhya Pradesh a ct locations for preparing bio nd Chhattisgarh diversity management plans, especially in corridors. IN-SPIU-MP-60727-CS-CDS / Strengthen Capacity of Gove selection of consultant for str rnment Institutions in Forest TF / A3990 Post Direct Selection Direct 16,000.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-03-31 engthening JFMCs on Biodive ry and Land Management Pr rsity management as per NB ograms in Madhya Pradesh a A. nd Chhattisgarh IN-SPIU-MP-64230-CS-INDV / Individual Consult Recruitment of Procurement TF / A3990 Project Management Post Open 36,000.00 0.00 Signed 2018-07-24 2018-07-26 2018-09-11 2018-09-24 2018-10-02 2018-09-26 2018-11-06 2020-10-26 ant Selection cum Financial Management C onsultant. IN-SPIU-MP-77399-CS-INDV / Hiring of individual consultan t for Information Education a nd Communication (IEC) Stra Individual Consult TF / A3990 Project Management Post Open 30,000.00 0.00 Canceled 2018-09-18 2018-11-06 2018-11-27 2019-01-01 2019-06-30 tegy & ant Selection Implementation Plan for impl ementing ESIP in the state of Madhya Pradesh in the distric ts, divisions and landscapes s elected to be treated. IN-SPIU-MP-165043-CS-INDV Individual Consult / Hiring of Individual Consulta TF / A3990 Project Management Post Open 35,000.00 1,370.15 Signed 2020-03-28 2020-05-05 2020-05-16 2020-09-26 2020-06-06 2020-10-14 2020-07-11 2020-12-02 2022-05-31 ant Selection nt for Database and GIS Expe rt IN-SPIU-MP-165048-CS-INDV / Hiring of Individual Consulta Individual Consult Under Implement TF / A3990 Project Management Post Open 30,000.00 0.00 2020-03-28 2019-11-14 2020-05-16 2021-05-21 2020-06-06 2020-07-11 2022-03-31 nt for Forestry/Ecosystem Se ant Selection ation rvice & Knowledge managem ent Specialist IN-SPIU-MP-217013-CS-INDV Individual Consult Under Implement / procurement cum financial TF / A3990 Project Management Post Limited 30,000.00 0.00 2021-02-07 2021-02-04 2021-02-12 2021-03-27 2021-03-05 2021-04-09 2021-10-06 ant Selection ation management consultant for s piu mp IN-SPIU-MP-150252-NC-DIR / Individual Consult ESIP project coordinator in B TF / A3990 Project Management Post Limited 9,000.00 0.00 Canceled 2020-02-04 2020-02-09 2020-03-01 2020-04-05 2022-03-06 ant Selection udhni Range Page 11 Somali Integrated Statistics and Economic Capacity Building Project (SISECBP) Final Revised Procurement Plan for PPA Dated: 20 May, 2020 I. Packages for Goods, and Non-Consulting Services Re Contract Estimated Revie Marke Selecti Evalu Procurem Preq Dom Expected Expected f. Description Cost w by t on ation ent ualifi estic date of date of No (US$) Bank Appro Metho Optio Process catio Pref bid/ Contract ach d ns (Single n eren proposal Signature (Prior (Open- (RFP, stage- ce opening / (Yes/ Nation RFB, single (Yes No) Post) al/ RFQ envelope /No) Limite etc.) etc.) d etc.) GOODS Procurement for the PIU and SIHBS of: (a) Ten Most Single Desktop advant G1 30,800 Prior Limited RFQ stage One N/A N/A 15-Jun-20 16-Jul-20 computers (6 ageou - Envelope for PIU and 4 s for SIHBS); 4 laptops for SIHBS; 10 Re Contract Estimated Revie Marke Selecti Evalu Procurem Preq Dom Expected Expected f. Description Cost w by t on ation ent ualifi estic date of date of No (US$) Bank Appro Metho Optio Process catio Pref bid/ Contract ach d ns (Single n eren proposal Signature (Prior (Open- (RFP, stage- ce opening / (Yes/ Nation RFB, single (Yes No) Post) al/ RFQ envelope /No) Limite etc.) etc.) d etc.) Data Entry tablets (b)two Big Printer with copier for NEC and DNS; (c) 1 Laser jet desk printers for PIU (d) Two projectors for SIHBS and PIU (i) Ten anti- virus software (6 for PIU and 4 for SIHBS) Purchase of 2 Most Single motor vehicles advant Stage G2 (one for PIU 80,000 Prior Limited RFQ ageou N/A N/A 15-Jun-20 16-Jul-20 One- and one for s Envelop NEC) Re Contract Estimated Revie Marke Selecti Evalu Procurem Preq Dom Expected Expected f. Description Cost w by t on ation ent ualifi estic date of date of No (US$) Bank Appro Metho Optio Process catio Pref bid/ Contract ach d ns (Single n eren proposal Signature (Prior (Open- (RFP, stage- ce opening / (Yes/ Nation RFB, single (Yes No) Post) al/ RFQ envelope /No) Limite etc.) etc.) d etc.) Office Most furniture and a advant Single refrigerator for ageou G3 7,700 Prior Limited RFQ stage One N/A N/A 30-Jun-20 22-Jul-20 PIU (Chairs, s - Envelope Tables, cabinets) 4 Most Single Anthropometri advant G4 2,000 Prior Limited RFQ stage One N/A N/A 14-July-20 28 July-20 c equipment ageou - Envelope for SIHBS s Total 120,50 Goods 0 Ref Contract Estimated Review Market Selection Shortlist Expected Expected No. Description Cost (US$) by Bank Approach Method ing Date of Bid Date of (Open- (QCBS, (Yes/No) Proposal Contract (Prior/Po National/ LCBCS, Opening Signature st) Limited etc.) QBS, DS Prepare statistics regulations to be used C1 Prior Open INDIV N/A 3-Aug-20 17-Aug-20 along with the revised 20,000 Statistics Act. Hire a consultancy firm for the review the DNS organization C2 structure, develop Prior Open CQS N/A 10-Aug-20 31-Aug-20 96,000 and change management strategy for DNS. Hire consultant to review the C3 preparation of the Prior Limited INDV N/A 10-July-20 24-Jul-20 20,000 project operations manual. Hire consultant for translation of the C4 Prior Limited INDV N/A 15-July-20 31-July-20 Safeguard 10,000 documents. Consultancy firm to provide support to the Open - C5 Prior CQS N/A 29-Sept-20 26-Oct-20 Somali Integrated 240,000 International Household Budget Survey on GIS and cluster mapping, and sampling frame development. Hire consultant to undertake a Training C6 needs assessment of Prior Open INDV N/A 11-Nov-20 30-Nov-20 80,000 all MDAs benefiting from SISECBP. Hire a consultancy firm to undertake ICT C7 needs assessment in Prior Open CQS N/A 17-Nov-20 1-Dec-20 100,000 all MDAs benefiting from the project. Hire consultancy firm to develop an ICT strategy for NSS, including detailed software and database design for data and metadata, C8 data center design, Prior Open CQS N/A 25-Jan-21 16-Feb-21 100,000 specifications of data center hardware and software testing, integration and implementation of the hardware and statistical software Hire 4 Senior M&E consultants for 3 months to assist in Open C9 Prior INDV N/A 8-Oct-20 28-Oct-20 development of a 160,000 international national M&E Framework. Hire consultants to undertake the following key C16 policy research and studies for NEC: C16.1 Hire individual consultant to undertake research 133,000 Prior Open INDV N/A 15-Seot -20 9-Oct-20 on “Fiscal Federalism and Related Issues” – Paper 1. C16.2 Hire individual consultants to undertake research 126,000 Prior Open INDV N/A 5-Oct -20 25-Oct-20 for 6 months on “Regional Economic Cooperation Analysis” Hiring of the C17 following PIU staff C17.1 Project N/A Coordinator for 6 30,810 Prior Open INDV 1-Jun-20 21-June-20 months C17.2 Technical N/A 25,980 Prior Open INDV 15-Jun-20 4-Jul-20 Manager for 6 months C17.3 Procurement 25,980 N/A specialist for 6 Prior Open INDV 8-Jun-20 29-June-20 months C17.4 Financial N/A Management 25,980 Prior Open INDV 1-Jun-20 21-June-20 specialist for 6 months C17.5 Secretary for 6 N/A 13,660 Prior Limited INDV 8-Jun-20 29-June-20 months C17.56ICT Specialist N/A 6,640 Prior Limited INDV 28-Jun-20 19-Jul-20 for 2 months C17.7 M&E Specialist N/A 6,640 Prior Limited INDV 24-Jun-20 16-Jul-20 for 2 months C17.8 Driver N/A 3,900 Prior Limited INDV 15-Jun-20 16-Jul-20 for the first 6 months. Hiring of the C18 following NEC staff. C18.1 Program N/A 68,000 Prior Open INDV 30-July-20 15-Aug-20 Manager for 8 months C18. Sector Economist for N/A 33,000 Prior Open INDV 9-Aug-20 23-Aug-20 2 6 months C18.6 Office Manager N/A for the first 12 27,320 Prior Open INDV 30-July-20 15-Aug-20 months. C18.8 Driver N/A for the first 12 7,800 Prior Limited INDV 9-Aug-20 23-Aug-20 months. Hiring Senior N/A 10 June, C19 Statistician for DNS 58,800 Prior Open INDV 30 June, 2020 2020 for 6 months Total Consulting 1,419,5 Services 10 Grand 1,540,0 Total 10 PROCUREMENT Somalia : Somali Integrated Statistics and Economic Planning Capacity Building PLAN General Information Country: Somalia 2020-07-22 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171160 GPN Date: Project Name: Somali Integrated Statistics and Economic Planning Capacity Building Loan / Credit No: IDA / V3390, IDA / D6660 Ministry of Planning, Investment, and Economic Development Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOPIED-220465-GO-RFQ / Office furniture: Office cabi Component 3: Data utilizat nets, executive chairs, tables Request for Quota IDA / D6660 ion for Monitoring, Evaluatio Prior 56,400.00 48,240.00 Completed 2021-02-27 2021-05-30 2021-04-24 2021-07-07 2021-10-21 2022-11-03 , office decoration, doors, ref tions n, and Planning rigerators, Library office furni shing, and sofa seats for PIU NEC SO-MOPIED-220466-GO-RFQ Component 3: Data utilizat Request for Quota Single Stage - One E / Motor vehicles ( Purchase of IDA / D6660 ion for Monitoring, Evaluatio Prior Limited 80,000.00 78,000.00 Completed 2021-02-27 2021-04-08 2021-04-24 2021-05-19 2021-10-21 2021-07-08 tions nvelope 2 Vehicles ) for PIU and NEC n, and Planning SO-MOPIED-220472-GO-RFQ / Computers and accessories; 14 Desktop and 16 laptop ,3 Component 3: Data utilizat 0 anti-virus software, 2 big pr Request for Quota Single Stage - One E IDA / D6660 ion for Monitoring, Evaluatio Prior Limited 94,560.00 70,570.00 Completed 2021-02-27 2021-04-14 2021-04-24 2021-06-16 2021-10-21 2021-08-19 inter with photocopier, 9-3 in tions nvelope n, and Planning 1 printers, 2 Projector,1TV Sc reen,1 camera, 1VCT, 2 STAT A single user license and 4 M icrosoft Office 365 for PIU an d NEC Component 1: Strengtheni SO-MOPIED-233118-GO-RFQ ng coordination, statistical in Request for Quota Single Stage - One E / Electricity Generator for SN IDA / D6660 Prior Limited 40,000.00 39,800.00 Completed 2021-06-03 2021-05-24 2021-09-04 2021-06-07 2021-10-04 2021-10-27 frastructure and data develo tions nvelope BS pment of the national statist ical syste m Component 1: Strengtheni SO-MOPIED-245430-GO-RFB ng coordination, statistical in Single Stage - One E / SIHBS Survey ICT Equipmen IDA / D6660 Prior Request for Bids Open - National 222,450.00 208,704.00 Signed 2021-08-05 2021-08-09 2021-08-10 2021-08-20 2021-09-21 2021-08-11 2021-10-21 2021-11-07 2021-11-25 2021-12-02 2022-03-25 frastructure and data develo nvelope t pment of the national statist ical syste m Component 1: Strengtheni SO-MOPIED-245431-GO-RFB ng coordination, statistical in Single Stage - One E / Motor vehicles ( Purchase of IDA / D6660 Prior Request for Bids Open - National 120,000.00 145,650.00 Completed 2021-07-30 2021-08-17 2021-08-04 2021-08-18 2021-09-15 2021-10-02 2021-10-15 2021-11-16 2021-11-19 2022-01-02 2022-05-18 2022-02-21 frastructure and data develo nvelope 3Vehicles ) for SNBS and NEC pment of the national statist ical syste m Component 1: Strengtheni SO-MOPIED-282607-GO-RFQ ng coordination, statistical in Request for Quota Single Stage - One E / Office Furniture’s and Decor IDA / D6660 Prior Limited 45,000.00 38,650.00 Signed 2022-03-20 2022-05-08 2022-05-15 2022-07-01 2022-11-11 frastructure and data develo tions nvelope ation for SHBS team pment of the national statist ical syste m SO-MOPIED-295775-GO-RFB Component 2: ICT develop Open - Internationa Single Stage - One E / ICT Equipment for the proje IDA / D6660 ment and equipment of the Prior Request for Bids 670,000.00 0.00 Canceled 2022-05-27 2022-08-04 2022-06-01 2022-08-15 2022-07-13 2022-12-12 2022-08-12 2022-09-16 2023-03-15 l nvelope ct implementing Agencies an national statistical system d MDAs SO-MOPIED-355069-GO-RFB Component 2: ICT develop Open - Internationa Single Stage - One E Under Imple / ICT equipment and data cen IDA / D6660 ment and equipment of the Prior Request for Bids 653,488.00 0.00 2023-04-05 2023-06-12 2023-04-10 2023-06-18 2023-05-22 2023-06-21 2023-07-26 2024-01-22 l nvelope mentation ter for the NSS national statistical system SO-MOPIED-363770-GO-RFQ Component 4: Project man Request for Quota Single Stage - One E Pending Impl IDA / D6660 Prior Limited 50,000.00 0.00 2023-06-16 2023-10-28 2024-04-25 / PIU Motor vehicles agement tions nvelope ementation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOPIED-220477-NC-RFQ Component 4: Project man Request for Quota Single Stage - One E IDA / D6660 Prior Limited 30,000.00 60,000.00 Signed 2021-02-27 2021-04-08 2021-04-24 2021-05-13 2021-10-21 / Office Internet Service for t agement tions nvelope he PIU SO-MOPIED-231804-GO-RFQ Component 3: Data utilizat Request for Quota Single Stage - One E Under Revie / Internet Service for NEC Offi IDA / D6660 ion for Monitoring, Evaluatio Prior Limited 14,400.00 36,000.00 2021-05-24 2021-06-11 2021-08-02 2021-07-11 2022-08-02 tions nvelope w ce n, and Planning Component 1: Strengtheni SO-MOPIED-245432-NC-RFQ ng coordination, statistical in Request for Quota Single Stage - One E / SNBS Website enhancemen IDA / D6660 Prior Limited 29,900.00 29,990.00 Signed 2021-08-10 2021-08-17 2021-10-05 2021-09-17 2022-04-03 frastructure and data develo tions nvelope t pment of the national statist ical syste m SO-MOPIED-257980-NC-RFQ Component 3: Data utilizat Request for Quota Single Stage - One E / First Macroeconomic Workin IDA / D6660 ion for Monitoring, Evaluatio Prior Limited 93,470.00 115,520.00 Signed 2021-10-25 2021-11-10 2021-11-28 2021-12-13 2021-12-28 tions nvelope g Group Workshop Service n, and Planning SO-MOPIED-282608-NC-RFQ Component 1: Strengtheni / Translation, Printing, and Pu ng coordination, statistical in Request for Quota Single Stage - One E IDA / D6660 Prior Limited 68,000.00 0.00 Signed 2022-03-20 2022-05-09 2022-05-15 2023-03-07 2022-11-11 blication Services for the sup frastructure and data develo tions nvelope port of PIU and Project Imple pment of the national statist menting Agencies ical syste m SO-MOPIED-358186-NC-DIR / Component 1: Strengtheni Consultancy service for the i ng coordination, statistical in Direct - Internation Under Imple IDA / D6660 Prior Direct Selection 366,658.00 0.00 2023-04-24 2023-05-03 2023-04-29 2023-06-19 2023-06-03 2024-06-02 mplementation of the Integra frastructure and data develo al mentation ted training plan pment of the national statist ical syste m Page 1 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOPIED-210302-CS-QCB Component 1: Strengtheni S / INSTITUTIONAL DEVELOP ng coordination, statistical in Quality And Cost- IDA / D6660 Prior Open - National 96,000.00 0.00 Canceled 2020-12-27 2021-01-17 2021-03-02 2021-03-30 2021-04-29 2021-06-03 2021-07-08 2021-10-06 MENT CONSULTANCY FOR NB frastructure and data develo Based Selection S pment of the national statist ical syste m Component 2: ICT develop SO-MOPIED-215438-CS-CQS Consultant Qualifi IDA / D6660 ment and equipment of the Prior Open - National 100,000.00 266,512.50 Completed 2021-01-31 2021-02-04 2021-02-21 2021-02-17 2021-04-06 2021-05-10 2021-05-06 2021-10-06 2021-06-10 2021-10-15 2021-09-08 2022-03-20 / ICT needs assessment cation Selection national statistical system Component 1: Strengtheni SO-MOPIED-210418-CS-QCB ng coordination, statistical in Quality And Cost- S / Training Needs Assessme IDA / D6660 Prior Open - National 80,000.00 0.00 Canceled 2020-12-30 2021-01-07 2021-01-20 2021-03-05 2021-04-02 2021-05-02 2021-06-06 2021-07-11 2021-10-29 frastructure and data develo Based Selection nt for all MDS pment of the national statist ical syste m Component 1: Strengtheni SO-MOPIED-216963-CS-CQS ng coordination, statistical in Consultant Qualifi / Institutional Development C IDA / D6660 Prior Open - National 96,000.00 257,500.00 Completed 2021-02-10 2021-03-09 2021-03-03 2021-03-23 2021-04-16 2021-06-23 2021-05-16 2021-09-24 2021-06-20 2021-10-04 2021-12-17 2023-04-19 frastructure and data develo cation Selection onsultancy pment of the national statist ical syste m Component 2: ICT develop SO-MOPIED-210308-CS-QCB Quality And Cost- Open - Internationa IDA / D6660 ment and equipment of the Prior 100,000.00 0.00 Canceled 2020-12-30 2021-01-08 2021-01-20 2021-03-05 2021-04-02 2021-05-02 2021-06-06 2021-07-11 2021-10-09 S / ICT NEEDS ASSESSMENT Based Selection l national statistical system Component 1: Strengtheni SO-MOPIED-231992-CS-CQS ng coordination, statistical in Consultant Qualifi / First User Satisfaction Surve IDA / D6660 Prior Open - National 69,000.00 69,000.00 Completed 2021-05-10 2021-05-04 2021-05-31 2021-05-10 2021-07-30 2021-09-07 2021-08-29 2021-10-26 2021-10-10 2021-10-28 2021-12-09 2022-02-18 frastructure and data develo cation Selection y pment of the national statist ical syste m SO-MOPIED-233119-CS-QCB Component 1: Strengtheni S / Consultancy Firm to supp ng coordination, statistical in Quality And Cost- Open - Internationa IDA / D6660 Prior 3,137,149.00 4,536,999.00 Signed 2021-05-20 2021-05-27 2021-06-09 2021-05-31 2021-10-07 2021-07-23 2021-12-06 2021-08-11 2022-01-05 2021-09-05 2022-04-05 2021-11-10 2022-05-16 2021-11-16 2023-05-16 ort Household Budget Survey frastructure and data develo Based Selection l Implementation pment of the national statist ical syste m SO-MOPIED-320525-CS-CQS Component 3: Data utilizat / Consulting Firm to Conduct Consultant Qualifi IDA / D6660 ion for Monitoring, Evaluatio Prior Open - National 200,000.00 0.00 Signed 2022-10-17 2022-11-07 2022-11-07 2022-11-13 2022-12-21 2023-02-22 2023-01-20 2023-03-24 2023-02-24 2023-04-07 2023-08-23 the Mid-term Review of the N cation Selection n, and Planning ational Development Plan (N DP-9) SO-MOPIED-320639-CS-QCB Component 1: Strengtheni S / Consultancy Firm for Som ng coordination, statistical in Quality And Cost- Open - Internationa Under Implement IDA / D6660 Prior 1,114,344.00 0.00 2022-10-17 2022-11-11 2022-11-07 2022-11-13 2022-12-21 2023-02-11 2023-01-18 2023-03-13 2023-02-17 2023-03-24 2023-04-28 2024-04-27 ali Establishment Census 202 frastructure and data develo Based Selection l ation 2/23 pment of the national statist ical syste m SO-MOPIED-320641-CS-CQS Component 3: Data utilizat Consultant Qualifi Under Implement / Consultancy Firm for the De IDA / D6660 ion for Monitoring, Evaluatio Prior Open - National 200,000.00 0.00 2022-10-17 2022-10-15 2022-11-07 2022-11-13 2022-12-21 2023-01-20 2023-02-24 2023-08-23 cation Selection ation velopment of the M&E Syste n, and Planning m for MoPIED INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOPIED-184787-CS-INDV Component 4: Project man Individual Consult IDA / V3390 Prior Open 30,810.00 167,760.00 Signed 2020-07-20 2020-08-04 2020-09-07 2020-11-23 2020-09-28 2020-12-08 2020-11-02 2020-12-05 2021-11-02 / Project Coordinator agement ant Selection SO-MOPIED-184789-CS-INDV Component 4: Project man Individual Consult IDA / V3390 Prior Open 25,980.00 80,008.00 Completed 2020-07-20 2020-08-04 2020-09-07 2021-02-25 2020-09-28 2021-03-01 2020-11-02 2021-03-14 2021-11-02 2023-05-30 / Technical Manager agement ant Selection SO-MOPIED-184790-CS-INDV Component 4: Project man Individual Consult IDA / V3390 Prior Open 25,980.00 134,880.00 Signed 2020-07-20 2020-08-10 2020-09-07 2020-11-23 2020-09-28 2020-11-28 2020-11-02 2020-12-05 2021-11-02 / Financial Management Spec agement ant Selection ialist SO-MOPIED-184794-CS-INDV Component 4: Project man Individual Consult IDA / V3390 Prior Limited 6,640.00 129,720.00 Signed 2020-07-20 2021-01-05 2020-07-25 2021-02-24 2020-08-15 2021-03-02 2020-09-19 2021-03-16 2021-01-17 / M&E Specialist agement ant Selection SO-MOPIED-184795-CS-INDV Component 4: Project man Individual Consult IDA / V3390 Prior Limited 13,660.00 77,400.00 Signed 2020-07-20 2020-08-10 2020-07-25 2021-02-04 2020-08-15 2021-03-03 2020-09-19 2021-03-16 2021-09-19 / Secretary agement ant Selection SO-MOPIED-184797-CS-INDV Component 4: Project man Individual Consult IDA / V3390 Prior Open 25,980.00 140,640.00 Signed 2020-07-20 2020-08-04 2020-09-07 2020-11-23 2020-09-28 2020-12-08 2020-11-02 2020-12-05 2021-11-02 / Procurement specialist agement ant Selection Component 3: Data utilizat SO-MOPIED-188749-CS-CDS IDA / V3390 ion for Monitoring, Evaluatio Prior Direct Selection Direct 68,000.00 200,920.00 Completed 2020-08-15 2020-08-15 2020-08-25 2020-10-27 2020-10-29 2020-11-20 2021-10-29 2023-05-29 / NEC Program Manager n, and Planning Component 3: Data utilizat SO-MOPIED-188753-CS-CDS IDA / V3390 ion for Monitoring, Evaluatio Prior Direct Selection Direct 33,000.00 132,120.00 Completed 2020-08-15 2020-08-15 2020-08-25 2020-10-27 2020-10-29 2020-11-22 2021-10-29 2023-05-30 / NEC Sector Economist n, and Planning SO-MOPIED-210276-CS-INDV Component 3: Data utilizat Individual Consult / NEC Senior Macroeconomic IDA / D6660 ion for Monitoring, Evaluatio Prior Open 98,400.00 150,180.00 Signed 2020-12-27 2021-01-04 2021-02-14 2021-05-07 2021-03-07 2021-08-24 2021-04-11 2021-09-01 2022-04-11 ant Selection s Specialist n, and Planning Component 3: Data utilizat SO-MOPIED-210284-CS-INDV Individual Consult IDA / D6660 ion for Monitoring, Evaluatio Prior Open 27,320.00 84,780.00 Signed 2020-12-27 2021-01-04 2021-02-14 2021-05-04 2021-03-07 2021-06-11 2021-04-11 2021-06-12 2022-04-11 / NEC Office Manager ant Selection n, and Planning SO-MOPIED-210292-CS-INDV Component 3: Data utilizat Individual Consult / NEC Finance and Accountin IDA / D6660 ion for Monitoring, Evaluatio Prior Open 58,764.00 121,200.00 Under Review 2020-12-27 2021-01-26 2021-02-14 2021-05-04 2021-03-07 2021-06-11 2021-04-11 2021-06-14 2022-04-11 ant Selection g Manager n, and Planning SO-MOPIED-210294-CS-INDV Component 3: Data utilizat Individual Consult / NEC Communication and pu IDA / D6660 ion for Monitoring, Evaluatio Prior Open 45,876.00 102,120.00 Signed 2020-12-27 2021-01-04 2021-02-14 2021-05-04 2021-03-07 2021-05-25 2021-04-11 2021-06-02 2022-04-11 ant Selection blic relations Specialists n, and Planning Component 1: Strengtheni SO-MOPIED-211634-CS-INDV ng coordination, statistical in Individual Consult IDA / D6660 Prior Limited 58,800.00 64,680.00 Completed 2020-12-27 2020-12-30 2021-01-01 2021-02-04 2021-01-22 2021-03-01 2021-02-26 2021-03-14 2022-02-26 2023-05-30 / NBS Senior Statistician frastructure and data develo ant Selection pment of the national statist ical syste m SO-MOPIED-210369-CS-INDV Component 4: Project man Individual Consult IDA / D6660 Prior Limited 51,960.00 134,880.00 Signed 2020-12-27 2021-03-11 2021-01-01 2021-04-07 2021-01-22 2021-05-26 2021-02-26 2021-06-02 2022-02-26 / PIU Communication speciali agement ant Selection st Page 2 SO-MOPIED-211638-CS-INDV Component 4: Project man Individual Consult IDA / D6660 Prior Limited 10,000.00 10,000.00 Completed 2020-12-27 2020-12-30 2021-01-01 2021-02-04 2021-01-22 2021-03-01 2021-02-26 2021-03-11 2021-03-28 2021-04-26 / Safeguard documents transl agement ant Selection ation SO-MOPIED-184791-CS-INDV Component 4: Project man Individual Consult IDA / V3390 Prior Limited 6,640.00 0.00 Canceled 2020-07-20 2020-07-25 2020-08-15 2020-09-19 2021-01-17 / ICT Specialist agement ant Selection Component 1: Strengtheni SO-MOPIED-216960-CS-INDV ng coordination, statistical in Individual Consult / Training Needs Assessment IDA / D6660 Prior Open 80,000.00 45,000.00 Completed 2021-02-04 2021-02-04 2021-03-25 2021-05-04 2021-04-15 2021-05-25 2021-05-20 2021-05-30 2021-11-16 2022-03-01 frastructure and data develo ant Selection Consultant pment of the national statist ical syste m SO-MOPIED-217770-CS-CDS Component 3: Data utilizat / NEC Hawala Systems Exper IDA / D6660 ion for Monitoring, Evaluatio Prior Direct Selection Direct 17,500.00 17,500.00 Signed 2021-02-10 2021-02-09 2021-02-20 2021-02-14 2021-04-26 2021-03-09 2021-10-23 t n, and Planning Component 3: Data utilizat SO-MOPIED-217773-CS-CDS IDA / D6660 ion for Monitoring, Evaluatio Prior Direct Selection Direct 17,500.00 17,500.00 Signed 2021-02-10 2021-02-09 2021-02-20 2021-02-14 2021-04-26 2021-03-09 2021-10-23 / NEC Health Systems Expert n, and Planning SO-MOPIED-217777-CS-CDS Component 3: Data utilizat / NEC Macroeconomist and L IDA / D6660 ion for Monitoring, Evaluatio Prior Direct Selection Direct 22,500.00 22,500.00 Signed 2021-02-10 2021-02-09 2021-02-20 2021-02-14 2021-04-26 2021-03-09 2021-10-23 ead Researcher n, and Planning SO-MOPIED-217783-CS-CDS Component 3: Data utilizat / NEC Remittance Analysis Ex IDA / D6660 ion for Monitoring, Evaluatio Prior Direct Selection Direct 17,500.00 17,500.00 Signed 2021-02-10 2021-02-09 2021-02-20 2021-02-14 2021-04-26 2021-03-09 2021-10-23 pert n, and Planning SO-MOPIED-217786-CS-CDS Component 3: Data utilizat / NEC Healthcare Institutions IDA / D6660 ion for Monitoring, Evaluatio Prior Direct Selection Direct 17,500.00 17,500.00 Signed 2021-02-10 2021-02-09 2021-02-20 2021-02-14 2021-04-26 2021-03-09 2021-10-23 Capacity Development Exper n, and Planning t Component 3: Data utilizat SO-MOPIED-225811-CS-INDV Individual Consult IDA / D6660 ion for Monitoring, Evaluatio Prior Limited 18,000.00 27,480.00 Signed 2021-03-25 2021-05-18 2021-03-30 2021-08-24 2021-04-20 2021-08-30 2021-05-25 2021-09-02 2021-11-21 / NEC IT officer ant Selection n, and Planning SO-MOPIED-225812-CS-INDV Component 3: Data utilizat Individual Consult / NEC Research Analysts (Ma IDA / D6660 ion for Monitoring, Evaluatio Prior Open 18,000.00 14,640.00 Signed 2021-03-25 2021-05-11 2021-05-13 2021-11-20 2021-06-03 2021-12-24 2021-07-08 2021-12-30 2022-01-04 ant Selection cro) n, and Planning SO-MOPIED-225814-CS-INDV Component 3: Data utilizat Individual Consult / NEC Research Analysts (Mic IDA / D6660 ion for Monitoring, Evaluatio Prior Open 18,000.00 14,640.00 Completed 2021-03-25 2021-05-11 2021-05-13 2021-11-20 2021-06-24 2021-12-24 2021-07-29 2021-12-28 2022-01-25 2023-05-30 ant Selection ro) n, and Planning SO-MOPIED-231303-CS-INDV Component 3: Data utilizat / MED Security and rule of la Individual Consult IDA / D6660 ion for Monitoring, Evaluatio Prior Open 33,720.00 0.00 Canceled 2021-04-30 2021-05-10 2021-07-03 2021-07-23 2021-08-23 2022-02-19 w Consultant for M&E Frame ant Selection n, and Planning work Development SO-MOPIED-231301-CS-INDV Component 3: Data utilizat / MED Economic Developmen Individual Consult IDA / D6660 ion for Monitoring, Evaluatio Prior Open 33,720.00 43,940.00 Completed 2021-04-30 2021-05-10 2021-07-03 2021-09-01 2021-07-23 2021-09-03 2021-08-23 2021-09-14 2022-02-19 2022-03-17 t Consultant for M&E Framew ant Selection n, and Planning ork Development SO-MOPIED-231297-CS-INDV Component 3: Data utilizat / MED Social Development Ex Individual Consult IDA / D6660 ion for Monitoring, Evaluatio Prior Open 48,920.00 57,087.00 Completed 2021-04-30 2021-05-10 2021-07-03 2021-08-12 2021-07-23 2021-08-31 2021-08-23 2021-09-14 2022-04-20 2022-05-02 pert and Lead Consultant for ant Selection n, and Planning M&E Framework Developmen t SO-MOPIED-231304-CS-INDV Component 3: Data utilizat Individual Consult / MED inclusive politics Cons IDA / D6660 ion for Monitoring, Evaluatio Prior Open 33,720.00 36,690.00 Completed 2021-04-30 2021-05-10 2021-07-03 2021-08-12 2021-07-24 2021-09-03 2021-08-24 2021-09-14 2022-02-20 2022-03-07 ant Selection ultant for M&E Framework De n, and Planning velopment Component 1: Strengtheni SO-MOPIED-231985-CS-INDV ng coordination, statistical in Individual Consult / SNBS Statistical Compendiu IDA / D6660 Prior Open 60,000.00 54,000.00 Completed 2021-05-10 2021-05-09 2021-07-25 2021-08-07 2021-08-15 2021-08-08 2021-09-26 2021-08-12 2021-12-25 2022-03-01 frastructure and data develo ant Selection m pment of the national statist ical syste m SO-MOPIED-245435-CS-INDV Component 3: Data utilizat / Local Financial Statistician t Individual Consult IDA / D6660 ion for Monitoring, Evaluatio Prior Limited 29,640.00 19,350.00 Completed 2021-08-05 2021-08-24 2021-08-10 2021-11-11 2021-08-31 2021-11-18 2021-10-05 2021-12-13 2022-04-06 2023-05-30 o support budget outlook pap ant Selection n, and Planning er data collection for MOF SO-MOPIED-245436-CS-INDV Component 1: Strengtheni / International Consultant to ng coordination, statistical in Individual Consult IDA / D6660 Prior Open 90,000.00 75,000.00 Signed 2021-09-20 2021-11-23 2021-11-08 2022-02-07 2021-11-29 2022-04-09 2022-01-03 2022-05-03 2022-07-02 prepare SIBES protocol docu frastructure and data develo ant Selection ments for 6 months pment of the national statist ical syste m SO-MOPIED-245439-CS-INDV Component 1: Strengtheni / Consult to conduct administ ng coordination, statistical in Individual Consult IDA / D6660 Prior Open 58,500.00 63,000.00 Signed 2021-08-25 2021-11-07 2021-10-13 2022-01-13 2021-11-03 2022-01-26 2021-12-08 2022-01-28 2022-06-06 rative data and records profil frastructure and data develo ant Selection ing in the selected key MDAs pment of the national statist at Federal level ical syste m SO-MOPIED-245440-CS-CDS Component 3: Data utilizat / NEC -Team Leader and Mac IDA / D6660 ion for Monitoring, Evaluatio Prior Direct Selection Direct 36,000.00 30,000.00 Signed 2021-08-25 2021-08-24 2021-09-04 2021-09-18 2021-11-08 2021-09-29 2022-02-06 roeconomist for Growth and n, and Planning Economic Transformation Str ategy SO-MOPIED-245441-CS-CDS Component 3: Data utilizat / NEC- Expert on Social devel IDA / D6660 ion for Monitoring, Evaluatio Prior Direct Selection Direct 40,000.00 28,000.00 Signed 2021-08-25 2021-08-24 2021-09-04 2021-09-18 2021-11-08 2021-10-01 2022-02-06 opment for Growth and Econ n, and Planning omic Transformation Strateg y SO-MOPIED-245445-CS-CDS Component 3: Data utilizat / NEC - Expert on Environme IDA / D6660 ion for Monitoring, Evaluatio Prior Direct Selection Direct 27,000.00 21,000.00 Signed 2021-08-25 2021-08-24 2021-09-04 2021-09-18 2021-11-08 2021-09-29 2022-02-06 ntal sustainability and huma n, and Planning n resilience for Food Security Study SO-MOPIED-245433-CS-INDV / Consultant to conduct traini Component 4: Project man Individual Consult IDA / D6660 Prior Open 67,560.00 58,500.00 Signed 2021-08-25 2021-08-29 2021-10-13 2021-11-28 2021-11-03 2021-12-08 2021-12-08 2021-12-09 2022-06-06 ng and awareness on GBV an agement ant Selection d CoC for SISEPCB project wo rkers SO-MOPIED-245443-CS-CDS Component 3: Data utilizat / NEC-Expert on Trade and In IDA / D6660 ion for Monitoring, Evaluatio Prior Direct Selection Direct 27,000.00 21,000.00 Signed 2021-08-25 2021-08-24 2021-09-04 2021-09-18 2021-11-08 2021-09-29 2022-02-06 frastructure for Growth and n, and Planning Economic Transformation Str ategy SO-MOPIED-245434-CS-INDV Component 3: Data utilizat Individual Consult / Consultant to undertake bu IDA / D6660 ion for Monitoring, Evaluatio Prior Open 67,500.00 63,000.00 Signed 2021-08-25 2021-08-24 2021-10-13 2021-11-28 2021-11-03 2021-12-16 2021-12-08 2021-12-26 2022-06-06 ant Selection dget outlook paper for MOF n, and Planning Page 3 SO-MOPIED-245438-CS-INDV Component 1: Strengtheni / International Consultant to ng coordination, statistical in Individual Consult IDA / D6660 Prior Open 90,000.00 75,000.00 Signed 2021-08-25 2021-11-17 2021-10-13 2022-04-24 2021-11-03 2022-06-25 2021-12-08 2022-07-02 2022-12-08 support SNBS national accou frastructure and data develo ant Selection nt unit pment of the national statist ical syste m SO-MOPIED-245442-CS-CDS / NEC- Somali institutional an Component 3: Data utilizat d Resource Mobilization Expe IDA / D6660 ion for Monitoring, Evaluatio Prior Direct Selection Direct 30,500.00 24,500.00 Signed 2021-08-25 2021-08-24 2021-09-04 2021-09-18 2021-11-08 2021-09-29 2022-02-06 rt for Growth and Economic n, and Planning Transformation Strategy SO-MOPIED-245444-CS-CDS Component 3: Data utilizat / NEC-Lead Researcher and F IDA / D6660 ion for Monitoring, Evaluatio Prior Direct Selection Direct 28,000.00 28,000.00 Signed 2021-08-25 2021-08-24 2021-09-04 2021-09-19 2021-11-08 2021-09-29 2022-05-07 ood security and agriculture n, and Planning expert for Food Security Stud y SO-MOPIED-249669-CS-INDV Component 3: Data utilizat Individual Consult / NEC Website enhancement IDA / D6660 ion for Monitoring, Evaluatio Prior Limited 10,000.00 10,000.00 Signed 2021-08-30 2021-09-04 2021-09-04 2021-09-14 2021-09-25 2021-09-17 2021-10-30 2021-09-24 2022-04-28 ant Selection and maintenance n, and Planning SO-MOPIED-251340-CS-INDV Component 3: Data utilizat / MED Security and rule of la Individual Consult IDA / D6660 ion for Monitoring, Evaluatio Prior Limited 33,720.00 48,920.00 Completed 2021-09-06 2021-09-01 2021-09-11 2021-10-10 2021-10-02 2021-10-13 2021-11-06 2021-10-20 2022-05-05 2023-05-30 w Consultant for M&E Frame ant Selection n, and Planning work Development SO-MOPIED-254428-CS-CDS / NEC Blue Economy-Team L Component 3: Data utilizat eader and Sustainable Blue E IDA / D6660 ion for Monitoring, Evaluatio Prior Direct Selection Direct 30,000.00 26,250.00 Signed 2021-09-25 2021-10-08 2021-10-05 2021-11-01 2021-12-09 2021-11-14 2022-03-09 conomy Roadmap & Governa n, and Planning nce Framework Researcher SO-MOPIED-254429-CS-CDS Component 3: Data utilizat / NEC Blue Economy- Energy IDA / D6660 ion for Monitoring, Evaluatio Prior Direct Selection Direct 24,500.00 24,500.00 Signed 2021-09-25 2021-10-08 2021-10-05 2021-11-01 2021-12-09 2021-11-14 2022-03-09 Expert n, and Planning SO-MOPIED-254430-CS-CDS Component 3: Data utilizat / NEC Blue Economy-Invest IDA / D6660 ion for Monitoring, Evaluatio Prior Direct Selection Direct 21,000.00 21,000.00 Signed 2021-09-25 2021-10-08 2021-10-05 2021-11-01 2021-12-09 2021-11-17 2022-03-09 ment Expert n, and Planning SO-MOPIED-261143-CS-INDV Component 3: Data utilizat Individual Consult / NEC Research assistant to T IDA / D6660 ion for Monitoring, Evaluatio Prior Limited 6,000.00 6,000.00 Signed 2021-11-10 2021-11-09 2021-11-15 2021-11-22 2021-12-06 2021-12-02 2022-01-10 2021-12-06 2022-04-10 ant Selection eam Leader and Macroecono n, and Planning mist SO-MOPIED-261146-CS-INDV Component 3: Data utilizat / NEC Research Assistant on Individual Consult IDA / D6660 ion for Monitoring, Evaluatio Prior Limited 6,000.00 6,000.00 Signed 2021-11-10 2021-11-09 2021-11-15 2021-11-30 2021-12-06 2021-12-07 2022-01-10 2021-12-09 2022-04-10 Social development (Focus o ant Selection n, and Planning n Youth and Women) SO-MOPIED-261157-CS-INDV Component 3: Data utilizat Individual Consult / NEC Research Assistant on IDA / D6660 ion for Monitoring, Evaluatio Prior Limited 6,000.00 6,000.00 Signed 2021-11-10 2021-11-09 2021-11-15 2021-11-22 2021-12-06 2021-12-02 2022-01-10 2021-12-05 2022-04-10 ant Selection Social development (Health a n, and Planning nd Education) SO-MOPIED-261159-CS-INDV Component 3: Data utilizat / NEC Research Assistant on Individual Consult IDA / D6660 ion for Monitoring, Evaluatio Prior Limited 6,000.00 6,000.00 Completed 2021-11-10 2021-11-15 2021-11-15 2021-12-07 2021-12-06 2021-12-13 2022-01-10 2021-12-22 2022-04-10 2022-02-16 Somali institutional and Res ant Selection n, and Planning ource Mobilization Expert SO-MOPIED-261160-CS-INDV Component 3: Data utilizat Individual Consult / NEC Research Assistant on IDA / D6660 ion for Monitoring, Evaluatio Prior Limited 6,000.00 6,000.00 Completed 2021-11-10 2021-11-15 2021-11-15 2021-11-22 2021-12-06 2021-12-02 2022-01-10 2021-12-07 2022-04-10 2023-05-27 ant Selection Expert on Trade and Infrastru n, and Planning cture SO-MOPIED-261161-CS-INDV Component 3: Data utilizat Individual Consult / NEC Research Assistant on IDA / D6660 ion for Monitoring, Evaluatio Prior Limited 6,000.00 6,000.00 Signed 2021-11-10 2021-11-15 2021-11-15 2021-11-22 2021-12-06 2021-12-02 2022-01-10 2021-12-05 2022-04-10 ant Selection Food and Agriculture n, and Planning SO-MOPIED-261163-CS-INDV Component 3: Data utilizat Individual Consult / NEC Research Assistant on IDA / D6660 ion for Monitoring, Evaluatio Prior Limited 6,000.00 6,000.00 Completed 2021-11-10 2021-11-15 2021-11-15 2021-11-22 2021-12-06 2021-12-01 2022-01-10 2021-12-10 2022-04-10 2022-03-07 ant Selection Environmental sustainability n, and Planning and resilience Component 1: Strengtheni SO-MOPIED-271616-CS-INDV ng coordination, statistical in Individual Consult / SIHBS Jubaland State Coordi IDA / D6660 Prior Limited 29,640.00 26,400.00 Completed 2022-01-10 2022-01-13 2022-01-15 2022-02-16 2022-02-05 2022-03-16 2022-03-12 2022-03-19 2022-09-08 2023-05-30 frastructure and data develo ant Selection nator pment of the national statist ical syste m Component 1: Strengtheni SO-MOPIED-271617-CS-INDV ng coordination, statistical in Individual Consult / SIHBS South West State Co IDA / D6660 Prior Limited 29,640.00 24,960.00 Completed 2022-01-10 2022-01-13 2022-01-15 2022-02-12 2022-02-05 2022-03-14 2022-03-12 2022-03-21 2022-09-08 2023-05-30 frastructure and data develo ant Selection ordinator pment of the national statist ical syste m Component 1: Strengtheni SO-MOPIED-271618-CS-INDV ng coordination, statistical in Individual Consult / SIHBS Galmudug State Coor IDA / D6660 Prior Limited 29,640.00 24,960.00 Completed 2022-01-10 2022-01-13 2022-01-15 2022-02-07 2022-02-05 2022-03-14 2022-03-12 2022-03-19 2022-09-08 2023-05-30 frastructure and data develo ant Selection dinator pment of the national statist ical syste m Component 1: Strengtheni SO-MOPIED-271619-CS-INDV ng coordination, statistical in Individual Consult / SIHBS Hirshabelle State Coo IDA / D6660 Prior Limited 29,640.00 24,960.00 Completed 2022-01-10 2022-01-13 2022-01-15 2022-02-23 2022-02-05 2022-03-29 2022-03-12 2022-03-31 2022-09-08 2023-05-30 frastructure and data develo ant Selection rdinator pment of the national statist ical syste m Component 1: Strengtheni SO-MOPIED-271620-CS-INDV ng coordination, statistical in Individual Consult / SIHBS Jubaland State Qualit IDA / D6660 Prior Limited 23,640.00 24,960.00 Completed 2022-01-10 2022-01-13 2022-01-15 2022-02-16 2022-02-05 2022-03-14 2022-03-12 2022-03-19 2022-09-08 2023-05-30 frastructure and data develo ant Selection y Assurance Coordinator pment of the national statist ical syste m Component 1: Strengtheni SO-MOPIED-271621-CS-INDV ng coordination, statistical in Individual Consult / SIHBS South West State Qu IDA / D6660 Prior Limited 23,640.00 24,960.00 Completed 2022-01-10 2022-01-13 2022-01-15 2022-02-12 2022-02-05 2022-03-17 2022-03-12 2022-03-21 2022-09-08 2023-05-30 frastructure and data develo ant Selection ality Assurance Coordinator pment of the national statist ical syste m Component 1: Strengtheni SO-MOPIED-271623-CS-INDV ng coordination, statistical in Individual Consult / SIHBS Galmudug State Qual IDA / D6660 Prior Limited 23,640.00 24,960.00 Completed 2022-01-10 2022-01-13 2022-01-15 2022-02-07 2022-02-05 2022-03-14 2022-03-12 2022-03-19 2022-09-08 2023-05-30 frastructure and data develo ant Selection ity Assurance Coordinator pment of the national statist ical syste m Component 1: Strengtheni SO-MOPIED-271625-CS-INDV ng coordination, statistical in Individual Consult / SIHBS Hirshabelle State Qu IDA / D6660 Prior Limited 23,640.00 24,960.00 Completed 2022-01-10 2022-01-13 2022-01-15 2022-02-12 2022-02-05 2022-03-14 2022-03-12 2022-03-19 2022-09-08 2023-05-30 frastructure and data develo ant Selection ality Assurance Coordinator pment of the national statist ical syste m Component 1: Strengtheni SO-MOPIED-276131-CS-INDV ng coordination, statistical in Individual Consult / SIHBS Puntland State Qualit IDA / D6660 Prior Limited 23,640.00 24,960.00 Completed 2022-02-10 2022-02-07 2022-02-15 2022-02-23 2022-03-08 2022-03-29 2022-04-12 2022-03-31 2022-10-09 2023-05-30 frastructure and data develo ant Selection y Control-1 pment of the national statist ical syste m Page 4 Component 1: Strengtheni SO-MOPIED-276138-CS-INDV ng coordination, statistical in Individual Consult / SIHBS Puntland State Qualit IDA / D6660 Prior Limited 23,640.00 26,400.00 Completed 2022-02-10 2022-02-07 2022-02-15 2022-02-23 2022-03-08 2022-03-21 2022-04-12 2022-03-25 2022-10-09 2023-05-30 frastructure and data develo ant Selection y Control-2 pment of the national statist ical syste m Component 1: Strengtheni SO-MOPIED-276139-CS-INDV ng coordination, statistical in Individual Consult / SIHBS Puntland State Coord IDA / D6660 Prior Limited 29,640.00 24,960.00 Completed 2022-02-10 2022-02-05 2022-02-15 2022-03-09 2022-03-08 2022-04-21 2022-04-12 2022-04-24 2022-10-09 2023-05-30 frastructure and data develo ant Selection inator pment of the national statist ical syste m Component 1: Strengtheni SO-MOPIED-276150-CS-INDV ng coordination, statistical in Individual Consult IDA / D6660 Prior Limited 23,640.00 24,960.00 Completed 2022-02-10 2022-02-07 2022-02-15 2022-03-09 2022-03-08 2022-03-21 2022-04-12 2022-03-25 2022-10-09 2023-05-30 / SIHBS Quality Control-1 SL frastructure and data develo ant Selection pment of the national statist ical syste m Component 1: Strengtheni SO-MOPIED-276154-CS-INDV ng coordination, statistical in Individual Consult IDA / D6660 Prior Limited 23,640.00 24,960.00 Completed 2022-02-10 2022-02-07 2022-02-15 2022-03-03 2022-03-08 2022-03-22 2022-04-12 2022-03-25 2022-10-09 2023-05-30 / SIHBS Quality Control-2 SL frastructure and data develo ant Selection pment of the national statist ical syste m Component 1: Strengtheni SO-MOPIED-276155-CS-INDV ng coordination, statistical in Individual Consult IDA / D6660 Prior Limited 29,640.00 26,400.00 Completed 2022-02-10 2022-02-05 2022-02-15 2022-03-31 2022-03-08 2022-04-08 2022-04-12 2022-04-11 2022-10-09 2023-05-30 / SIHBS Sate Coordinator-SL frastructure and data develo ant Selection pment of the national statist ical syste m SO-MOPIED-290516-CS-INDV Component 4: Project man Individual Consult IDA / D6660 Prior Open 83,160.00 160,560.00 Signed 2022-04-20 2022-04-24 2022-06-08 2022-07-20 2022-06-29 2022-08-03 2022-08-03 2022-08-02 2023-08-03 / Technical Manager agement ant Selection Component 1: Strengtheni SO-MOPIED-291016-CS-INDV ng coordination, statistical in Individual Consult IDA / D6660 Prior Open 73,380.00 41,880.00 Signed 2022-04-25 2022-05-20 2022-06-13 2022-09-07 2022-07-04 2022-09-19 2022-08-08 2022-09-20 2023-08-08 / SIBES local consultant frastructure and data develo ant Selection pment of the national statist ical syste m SO-MOPIED-297945-CS-INDV Component 3: Data utilizat Individual Consult Under Implement / Inclusive Politics of NDP-9 M IDA / D6660 ion for Monitoring, Evaluatio Prior Open 76,260.00 0.00 2022-06-10 2022-06-14 2022-07-29 2022-08-19 2022-09-23 2023-09-18 ant Selection ation &E Focal Point n, and Planning SO-MOPIED-297948-CS-INDV Component 3: Data utilizat Individual Consult Under Implement / Security& Rule of Law of ND IDA / D6660 ion for Monitoring, Evaluatio Prior Open 76,260.00 0.00 2022-06-10 2022-06-28 2022-07-29 2022-08-19 2022-09-23 2023-09-18 ant Selection ation P-9 M&E Focal Point n, and Planning SO-MOPIED-297951-CS-INDV Component 3: Data utilizat Individual Consult Under Implement / Economic Development - of IDA / D6660 ion for Monitoring, Evaluatio Prior Open 76,260.00 0.00 2022-06-10 2022-06-28 2022-07-29 2022-08-19 2022-09-23 2023-09-18 ant Selection ation NDP-9 M&E Focal Point n, and Planning SO-MOPIED-297953-CS-INDV Component 3: Data utilizat Individual Consult Under Implement / MED Management Informati IDA / D6660 ion for Monitoring, Evaluatio Prior Open 64,680.00 0.00 2022-06-10 2022-06-28 2022-07-29 2022-08-19 2022-09-23 2023-09-18 ant Selection ation on System Consultant n, and Planning SO-MOPIED-297959-CS-INDV Component 3: Data utilizat Individual Consult Under Implement / Social Development of NDP- IDA / D6660 ion for Monitoring, Evaluatio Prior Open 76,260.00 0.00 2022-06-10 2022-06-28 2022-07-29 2022-08-19 2022-09-23 2023-09-18 ant Selection ation 9 M&E Focal Point n, and Planning SO-MOPIED-298565-CS-CDS Component 3: Data utilizat / MED Economic Developmen IDA / D6660 ion for Monitoring, Evaluatio Prior Direct Selection Direct 13,200.00 13,200.00 Completed 2022-06-10 2022-06-14 2022-06-20 2022-06-16 2022-08-24 2022-06-27 2022-11-22 2022-08-27 t Consultant for M&E Framew n, and Planning ork Development Additional Scope SO-MOPIED-298569-CS-CDS Component 3: Data utilizat / MED inclusive politics Cons IDA / D6660 ion for Monitoring, Evaluatio Prior Direct Selection Direct 13,200.00 12,240.00 Completed 2022-06-10 2022-06-15 2022-06-20 2022-06-16 2022-08-24 2022-06-27 2022-11-22 2022-08-27 ultant for M&E Framework De n, and Planning velopment Additional Scope SO-MOPIED-298980-CS-INDV Component 3: Data utilizat Individual Consult / NEC Gender Expert Consult IDA / D6660 ion for Monitoring, Evaluatio Prior Open 28,000.00 0.00 Signed 2022-06-13 2022-06-20 2022-08-01 2022-10-01 2022-08-22 2023-05-28 2022-09-26 2023-06-12 2022-12-25 ant Selection ants for Women Economic E n, and Planning mpowerment SO-MOPIED-298987-CS-INDV Component 3: Data utilizat Individual Consult / NEC Senior Economist Cons IDA / D6660 ion for Monitoring, Evaluatio Prior Open 31,500.00 0.00 Canceled 2022-06-20 2022-06-20 2022-08-08 2022-08-29 2022-10-03 2023-01-01 ant Selection ultants for Women Economic n, and Planning Empowerment SO-MOPIED-299403-CS-INDV Component 3: Data utilizat / NEC Communication Strate Individual Consult IDA / D6660 ion for Monitoring, Evaluatio Prior Open 28,000.00 0.00 Signed 2022-06-20 2022-06-20 2022-08-08 2022-09-22 2022-08-29 2023-02-11 2022-10-03 2023-03-23 2023-01-01 gy Development (Fostering a ant Selection n, and Planning national growth mindset) SO-MOPIED-326215-CS-CDS / Security Assessment Firm f Component 4: Project man IDA / D6660 Prior Direct Selection Direct - National 20,000.00 0.00 Signed 2022-11-20 2023-01-02 2022-11-30 2023-01-22 2023-02-03 2023-04-09 2023-04-04 or the PIU and project imple agement menting agencies. SO-MOPIED-332459-CS-INDV Component 2: ICT develop / SNBS ICT consultant to sup Individual Consult IDA / D6660 ment and equipment of the Prior Open - National 64,680.00 0.00 Signed 2023-01-10 2023-01-16 2023-02-28 2023-03-25 2023-03-21 2023-05-23 2023-04-25 2023-06-14 2024-04-24 port ICT provision and maint ant Selection national statistical system enance for both equipment a nd servers Component 3: Data utilizat SO-MOPIED-260730-CS-CDS IDA / D6660 ion for Monitoring, Evaluatio Post Direct Selection Direct 120,000.00 0.00 Canceled 2021-11-20 2021-12-23 2021-11-26 2021-12-27 2021-12-03 2022-06-01 / NEC executive director n, and Planning Component 1: Strengtheni SO-MOPIED-341806-CS-INDV ng coordination, statistical in Individual Consult / Legal advisor Consultant for IDA / D6660 Prior Open - National 76,260.00 0.00 Canceled 2023-02-20 2023-04-10 2023-05-01 2023-06-05 2024-06-04 frastructure and data develo ant Selection SNBS pment of the national statist ical syste m Component 3: Data utilizat SO-MOPIED-337609-CS-CDS IDA / D6660 ion for Monitoring, Evaluatio Prior Direct Selection Direct - National 120,000.00 0.00 Signed 2023-02-18 2023-03-01 2023-02-28 2023-03-28 2023-05-04 2023-05-14 2024-05-03 / NEC Executive Director n, and Planning SO-MOPIED-349497-CS-CDS Component 3: Data utilizat / NEC-Research Analysts (Ma IDA / D6660 ion for Monitoring, Evaluatio Prior Direct Selection Direct - National 38,700.00 0.00 Signed 2023-03-14 2023-03-16 2023-03-24 2023-03-23 2023-05-28 2023-05-14 2024-05-27 cro) n, and Planning SO-MOPIED-349548-CS-CDS Component 3: Data utilizat / NEC-Research Analysts (Mic IDA / D6660 ion for Monitoring, Evaluatio Prior Direct Selection Direct - National 59,280.00 0.00 Signed 2023-03-14 2023-03-16 2023-03-24 2023-03-23 2023-05-28 2023-05-14 2024-05-27 ro) n, and Planning Component 3: Data utilizat SO-MOPIED-349554-CS-CDS IDA / D6660 ion for Monitoring, Evaluatio Prior Direct Selection Direct - National 80,280.00 0.00 Signed 2023-03-14 2023-03-16 2023-03-24 2023-03-23 2023-05-28 2024-05-27 / NEC-Sector Economist n, and Planning Page 5 Component 1: Strengtheni SO-MOPIED-356311-CS-INDV ng coordination, statistical in Individual Consult Under Implement IDA / D6660 Prior Open - National 86,400.00 0.00 2023-04-12 2023-05-23 2023-05-31 2023-06-21 2023-07-26 2024-07-25 / SNBS Legal Consultant frastructure and data develo ant Selection ation pment of the national statist ical syste m SO-MOPIED-363470-CS-CDS Component 3: Data utilizat Direct - Internation Under Implement / MOF Budget Review Outloo IDA / D6660 ion for Monitoring, Evaluatio Prior Direct Selection 21,000.00 0.00 2023-05-26 2023-06-20 2023-07-06 2023-10-01 2023-12-30 al ation k Paper (BROP 2023) n, and Planning Component 3: Data utilizat SO-MOPIED-363474-CS-INDV Individual Consult Under Implement IDA / D6660 ion for Monitoring, Evaluatio Prior Limited 49,920.00 0.00 2023-05-26 2023-06-20 2023-06-23 2023-08-22 2023-10-01 2024-09-30 / MOF Financial Statistician ant Selection ation n, and Planning Component 1: Strengtheni SO-MOPIED-363478-CS-INDV ng coordination, statistical in Individual Consult Under Implement / SNBS Statistical capacity de IDA / D6660 Prior Open - National 73,380.00 0.00 2023-05-26 2023-06-08 2023-08-25 2023-10-24 2023-11-28 2024-11-27 frastructure and data develo ant Selection ation velopment consultant pment of the national statist ical syste m SO-MOPIED-363771-CS-INDV Component 3: Data utilizat Individual Consult Under Implement / NEC Federal Member States IDA / D6660 ion for Monitoring, Evaluatio Prior Open - National 73,380.00 0.00 2023-05-26 2023-06-16 2023-08-25 2023-10-24 2023-11-28 2024-11-27 ant Selection ation Liaison/Economist n, and Planning Component 3: Data utilizat SO-MOPIED-363772-CS-INDV Individual Consult Under Implement IDA / D6660 ion for Monitoring, Evaluatio Prior Open - National 73,380.00 0.00 2023-05-26 2023-06-16 2023-08-25 2023-10-24 2023-11-28 2024-11-27 / NEC Labour Economist ant Selection ation n, and Planning SO-MOPIED-363773-CS-INDV Component 3: Data utilizat Individual Consult Under Implement / Prime Minister's Liaison Adv IDA / D6660 ion for Monitoring, Evaluatio Prior Open - National 80,280.00 0.00 2023-05-26 2023-06-16 2023-08-25 2023-10-24 2023-11-28 2024-11-27 ant Selection ation isor to NEC n, and Planning Component 3: Data utilizat SO-MOPIED-363845-CS-INDV Individual Consult Under Implement IDA / D6660 ion for Monitoring, Evaluatio Prior Open - National 100,460.00 0.00 2023-05-26 2023-06-16 2023-08-25 2023-10-24 2023-11-28 2024-11-27 / NEC Program Manager ant Selection ation n, and Planning SO-MOPIED-363847-CS-INDV Component 3: Data utilizat Individual Consult Under Implement / NEC Communication Special IDA / D6660 ion for Monitoring, Evaluatio Prior Open - National 64,800.00 0.00 2023-05-26 2023-06-16 2023-08-25 2023-10-24 2023-11-28 2024-11-27 ant Selection ation ist n, and Planning Component 3: Data utilizat SO-MOPIED-363851-CS-INDV Individual Consult Under Implement IDA / D6660 ion for Monitoring, Evaluatio Prior Open - National 52,800.00 0.00 2023-05-26 2023-06-16 2023-08-25 2023-10-24 2023-11-28 2024-11-27 / NEC Office Manager ant Selection ation n, and Planning Page 6 PROCUREMENT PLAN Project information: Higher Education for Economic Transformation Project P166415 Project Implementation agency: ARU, COSTECH, DUCE, HESLB, MJNUAT,MOCU, MUCE, MUHAS,MUST, MZUMBE, MoEST, OUT, SUA, SUZ, TCU, UDOM, UDSM Date of the Procurement Plan: Sep 28, 2021 Period covered by this Procurement Plan: Oct 2021- Oct 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international and national competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: When approaching the national market, as agreed in the Procurement Plan, the country’s own procurement procedures may be used. These procurement procedures shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti- Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. For national open competitive procurement the requirements as per National Procurement Procedure (5.4) of Bank’s Procurement Regulations will apply Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations –Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not applicable Other Relevant Procurement Information. None PROCUREMENT Tanzania : Higher Education for Economic Transformation Project PLAN General Information Country: Tanzania 2023-04-11 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166415 GPN Date: 2021-11-28 Project Name: Higher Education for Economic Transformation Project Loan / Credit No: IDA / 68870 Tanzania Institute of Accountancy Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-TIA-361172-GO-RFB / SU Strengthening the Learning Single Stage - One E Under Imple PPLY AND INSTALLATION OF I IDA / 68870 Environments and Labor Mar Post Request for Bids Open - National 63,772.53 0.00 2023-05-24 2023-05-30 2023-05-26 2023-06-16 2023-06-29 2023-07-24 2023-10-24 nvelope mentation CT EQUIPMENT’S ket Alignment of Priority Pro grams NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-TIA-354392-CS-QCBS / Pr ovision of Consultancy Servic Strengthening the Learning es for Review of design docu Environments and Labor Mar Quality And Cost- Open - Internationa Under Implement ments, preparation of biddin IDA / 68870 Post 481,003.86 0.00 2023-04-14 2023-04-25 2023-05-05 2023-05-25 2023-06-18 2023-07-16 2023-08-15 2023-09-19 2023-10-24 2026-12-07 ket Alignment of Priority Pro Based Selection l ation g document, cost estimates grams and Supervision of Proposed Construction of Academic Blo ck at Singida Campus TZ-TIA-354481-CS-CQS / Pro vision of Consultancy Service s for Review of design docum Strengthening the Learning ents, preparation of bidding Environments and Labor Mar Consultant Qualifi Under Implement IDA / 68870 Post Open - National 292,741.62 0.00 2023-04-14 2023-04-25 2023-05-05 2023-05-25 2023-06-18 2023-07-18 2023-08-22 2026-03-24 document, cost estimates an ket Alignment of Priority Pro cation Selection ation d Supervision of proposed Co grams nstruction of Two hostels (Ma le & Female) at Nyang'homa ngo Mwanza Campus INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 Liberia: Ministry of Commerce & Industry Project Name: Liberia Investment, Finance and Trade (P171997) Loan #: P171997 PROCUREMENT PLAN (Textual Part) Project information: Liberia Investment, Finance and Trade (P171997) (P171997) Project Implementation agency: Ministry of Commerce & Industry Date of the Procurement Plan: November 2021 Period covered by this Procurement Plan: November 2021 to July 2022 ( PPA Procurement Plan) Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (Revised November 2017, August 2018 and November 2021 ) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works).Not Applicable. Goods: is not applicable Works: is not applicable Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Not Applicable Other Relevant Procurement Information. The project may use the CDD procurement under this project. If required, CDD manual will be produced by the project. PROCUREMENT Liberia : Liberia Investment, Finance and Trade Project PLAN General Information Country: Liberia 2022-02-09 Bank’s Approval Date of the Original Procurement Plan: 2023-05-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171997 GPN Date: Project Name: Liberia Investment, Finance and Trade Project Loan / Credit No: IDA / V3830, IDA / D9690 Ministry of Commerce and Industry Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MOCI-276208-GO-RFQ / P Component 1: Investment Cl Request for Quota Single Stage - One E rocurement of PIU Equipment IDA / V3830 Post Open - National 20,000.00 0.00 Canceled 2022-01-12 2022-03-09 2022-09-05 imate and Trade tions nvelope (Computer, Printer , Photoco pier LR-MOCI-276210-GO-RFQ / P Component 1: Investment Cl Request for Quota Single Stage - One E IDA / V3830 Post Open - National 20,000.00 0.00 Canceled 2022-01-12 2022-03-09 2022-09-05 rocurement of PIU Equipment imate and Trade tions nvelope (Funiture) LR-MOCI-276194-GO-RFQ / P Component 1: Investment Cl Request for Quota Single Stage - One E rocurement of Hardware to s IDA / V3830 Post Open - National 92,600.00 0.00 Canceled 2022-01-12 2022-03-09 2022-09-05 imate and Trade tions nvelope afeguard LBR Data LR-MOCI-276175-GO-RFQ / P Component 1: Investment Cl Request for Quota Single Stage - One E IDA / V3830 Post Open - National 50,000.00 0.00 Canceled 2022-03-19 2022-05-14 2022-11-10 rocurmentt of Vehicle imate and Trade tions nvelope LR-MOCI-289791-GO-RFQ / P Component 4: Project Imple Request for Quota Single Stage - One E IDA / V3830 Post Limited 50,000.00 0.00 Signed 2022-03-19 2022-02-28 2022-05-14 2022-11-10 rocurement of Vehicle mentation, M&E and CERC tions nvelope LR-MOCI-289794-GO-RFQ / P Component 4: Project Imple Request for Quota Single Stage - One E rocurement of Hardware to s IDA / V3830 Post Limited 92,600.00 0.00 Signed 2022-01-27 2022-02-28 2022-03-24 2022-09-20 mentation, M&E and CERC tions nvelope afeguard LBR Data LR-MOCI-289789-GO-RFQ / P Component 4: Project Imple Request for Quota Single Stage - One E rocurement of PIU Equipment IDA / V3830 Post Limited 20,000.00 0.00 Signed 2022-01-12 2022-02-28 2022-03-09 2022-09-05 mentation, M&E and CERC tions nvelope (Computer, Printer , Photoco pier LR-MOCI-289790-GO-RFQ / P Component 4: Project Imple Request for Quota Single Stage - One E IDA / V3830 Post Limited 20,000.00 0.00 Signed 2022-01-12 2022-02-28 2022-03-09 2022-09-05 rocurement of PIU Equipment mentation, M&E and CERC tions nvelope (Funiture) LR-MOCI-361340-GO-RFQ / P Component 1: Investment Cl Request for Quota Single Stage - One E Pending Impl rocurement of Vehicles for th IDA / D9690 Post Limited 450,000.00 0.00 2023-06-05 2023-07-31 2024-01-27 imate and Trade tions nvelope ementation e PIU and other TIMAS. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MOCI-355173-CS-QCBS / Consultancy Services to Man Component 2: SME Access t Quality And Cost- Open - Internationa IDA / D9690 Post 266,667.67 0.00 Canceled 2023-04-20 2023-04-10 2023-04-25 2023-04-13 2023-06-09 2023-07-07 2023-08-06 2023-09-10 2023-10-15 2024-10-14 age and Implement SME Tec o Markets and Finance Based Selection l hnical Assistance Program. LR-MOCI-360850-CS-QCBS / Consultancy Services to Man Component 2: SME Access t Quality And Cost- Open - Internationa Under Implement IDA / D9690 Prior 3,000,000.00 0.00 2023-05-31 2023-05-11 2023-06-21 2023-05-12 2023-08-04 2023-09-01 2023-10-01 2023-11-05 2023-12-10 2024-12-09 age and Implement SME Tec o Markets and Finance Based Selection l ation hnical Assistance Program. LR-MOCI-361331-CS-CQS / H iring of Consulting Firm to Up grade, Expand, and Maintain Component 2: SME Access t Consultant Qualifi Open - Internationa Under Implement IDA / D9690 Post 225,000.00 0.00 2023-05-31 2023-06-13 2023-06-21 2023-06-25 2023-08-04 2023-09-03 2023-10-08 2024-04-05 the Liberia’s Concessions Inf o Markets and Finance cation Selection l ation ormation System (CIMS) and automate the National Burea u of Concession's website. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MOCI-276196-CS-INDV / Component 1: Investment Cl Individual Consult IDA / V3830 Post Open 40,000.00 0.00 Canceled 2021-09-07 2021-10-26 2021-11-16 2021-12-21 2022-06-19 ESMF Consultancy Recruitme imate and Trade ant Selection nt LR-MOCI-276173-CS-INDV / Component 1: Investment Cl Individual Consult IDA / V3830 Post Open 20,000.00 0.00 Canceled 2022-01-07 2022-02-25 2022-03-18 2022-04-22 2022-10-19 Recruitment of Project Assist imate and Trade ant Selection ant MOCI-REF-4 / PPSD Consulta Component 1: Investment Cl Individual Consult IDA / V3830 Post Open 9,500.00 0.00 Canceled 2021-11-16 2022-01-04 2022-01-25 2022-03-01 2022-08-28 ncy Recruitment imate and Trade ant Selection LR-MOCI-276198-CS-INDV / Component 1: Investment Cl Individual Consult IDA / V3830 Post Open 42,000.00 0.00 Signed 2021-11-24 2022-03-30 2022-01-12 2022-02-09 2022-02-02 2022-08-10 2022-03-09 2022-09-05 PIU Procurement Specialist R imate and Trade ant Selection ecruitment Page 1 LR-MOCI-276209-CS-INDV / Component 1: Investment Cl Individual Consult IDA / V3830 Post Open 72,000.00 0.00 Signed 2021-11-24 2022-03-30 2022-01-12 2022-06-26 2022-02-02 2022-06-29 2022-03-09 2022-09-05 PIU Project Coordinator Recru imate and Trade ant Selection itment LR-MOCI-276206-CS-INDV / Component 1: Investment Cl Individual Consult IDA / V3830 Post Open 42,000.00 0.00 Signed 2022-01-07 2022-03-30 2022-02-25 2022-09-01 2022-03-18 2022-09-01 2022-04-22 2022-10-19 PIU Finance Officer Recruitm imate and Trade ant Selection ent LR-MOCI-276195-CS-INDV / Component 1: Investment Cl Individual Consult IDA / V3830 Post Open 20,000.00 0.00 Canceled 2022-05-08 2022-06-26 2022-07-17 2022-08-21 2023-02-17 Preparation Loan Administrat imate and Trade ant Selection ion Manual LR-MOCI-276197-CS-INDV / Component 1: Investment Cl Individual Consult Preparation of Detailed Proje IDA / V3830 Post Open 30,000.00 0.00 Canceled 2022-05-08 2022-06-26 2022-07-17 2022-08-21 2023-02-17 imate and Trade ant Selection ct operations Manual LR-MOCI-276199-CS-INDV / Component 1: Investment Cl Individual Consult Consultant to Develop a blue IDA / V3830 Post Open 82,900.00 0.00 Canceled 2022-05-08 2022-06-26 2022-07-17 2022-08-21 2023-02-17 imate and Trade ant Selection print for National single Wind ow LR-MOCI-276204-CS-INDV / Component 1: Investment Cl Individual Consult IDA / V3830 Post Open 20,000.00 0.00 Canceled 2022-05-08 2022-06-26 2022-07-17 2022-08-21 2023-02-17 SME TA Manual imate and Trade ant Selection LR-MOCI-276203-CS-INDV / Procurement of consultancy Component 1: Investment Cl Individual Consult services to carry out prelimin IDA / V3830 Post Open 60,000.00 0.00 Canceled 2022-05-08 2022-06-26 2022-07-17 2022-08-21 2023-02-17 imate and Trade ant Selection ary capacity building for stak eholders of Credit Registry LR-MOCI-276207-CS-INDV / Procurement of consultancy Component 1: Investment Cl Individual Consult IDA / V3830 Post Open 60,000.00 0.00 Canceled 2022-05-08 2022-06-26 2022-07-17 2022-08-21 2023-02-17 services to carry out prelimin imate and Trade ant Selection ary capacity building for stak eholders of the switch LR-MOCI-289797-CS-INDV / Component 4: Project Imple Individual Consult IDA / V3830 Post Limited 9,500.00 0.00 Signed 2021-11-16 2023-03-09 2021-11-21 2021-10-22 2021-12-12 2023-03-14 2022-01-16 2022-07-15 PPSD Consultancy Recruitme mentation, M&E and CERC ant Selection nt LR-MOCI-289795-CS-INDV / Component 4: Project Imple Individual Consult IDA / V3830 Post Limited 40,000.00 0.00 Signed 2021-09-07 2023-03-14 2021-09-12 2022-12-13 2021-10-03 2022-06-15 2021-11-07 2022-05-06 ESMF Consultancy Recruitme mentation, M&E and CERC ant Selection nt LR-MOCI-307953-CS-INDV / Component 4: Project Imple Individual Consult IDA / V3830 Post Open - National 60,000.00 0.00 Signed 2021-09-07 2021-09-19 2021-10-26 2022-08-10 2021-11-16 2022-08-10 2021-12-21 2022-06-19 SME Specialist Recruitment mentation, M&E and CERC ant Selection LR-MOCI-307959-CS-INDV / Component 4: Project Imple Individual Consult IDA / V3830 Post Open - National 42,000.00 0.00 Signed 2021-09-07 2021-09-19 2021-10-26 2022-07-28 2021-11-16 2022-08-12 2021-12-21 2022-06-19 Environmental Specialist Rec mentation, M&E and CERC ant Selection ruitment LR-MOCI-307958-CS-INDV / Component 4: Project Imple Individual Consult IDA / V3830 Post Open - National 42,000.00 0.00 Signed 2021-09-07 2021-09-19 2021-10-26 2022-08-08 2021-11-16 2022-08-08 2021-12-21 2022-06-19 Social Specialist Recruitment mentation, M&E and CERC ant Selection LR-MOCI-307955-CS-INDV / F Component 4: Project Imple Individual Consult inancial Sector Development IDA / V3830 Post Open - National 60,000.00 0.00 Signed 2021-09-07 2021-09-19 2021-10-26 2022-09-01 2021-11-16 2022-09-01 2021-12-21 2022-06-19 mentation, M&E and CERC ant Selection Specialist Recruitment LR-MOCI-345261-CS-INDV / Consultancy Services to Asse Component 3: Digital Financi Individual Consult Direct - Internation ss the National Electronic Pa IDA / V3830 Post 35,000.00 0.00 Signed 2023-02-28 2023-03-20 2023-03-10 2023-04-13 2023-03-31 2023-04-14 2023-05-05 2023-11-01 al Services Infrastructure ant Selection al yment Switch (NEPS) Data C enters at the Central Bank of Liberia LR-MOCI-345265-CS-INDV / Hiring a consultant to conduc t Feasibility Studies and Dev Component 3: Digital Financi Individual Consult Direct - Internation IDA / V3830 Post 35,000.00 0.00 Signed 2023-02-28 2023-02-23 2023-03-10 2023-04-14 2023-03-31 2023-04-14 2023-05-05 2023-11-01 elop Business Case on the N al Services Infrastructure ant Selection al ATIONAL ELECTRONIC PAYME NT SWITCH (NEPS) at the Ce ntral Bank of Liberia (CBL). LR-MOCI-345363-CS-INDV / Component 4: Project Imple Individual Consult Recruitment of Project Procur IDA / D9690 Post Limited 18,000.00 0.00 Signed 2023-03-03 2023-03-06 2023-03-08 2023-06-02 2023-03-29 2023-06-02 2023-04-20 2023-07-01 mentation, M&E and CERC ant Selection ement Assistant for the LIFT PIU. LR-MOCI-348367-CS-INDV / Hiring of Consultant to devel Component 4: Project Imple Individual Consult IDA / D9690 Post Limited 48,000.00 0.00 Signed 2023-03-31 2023-04-14 2023-04-05 2021-09-15 2023-04-26 2021-09-10 2023-05-31 2023-11-27 op Environmental and Social mentation, M&E and CERC ant Selection Management Framework (ES MF) for the LIFT Project. LR-MOCI-358442-CS-INDV / Component 1: Investment Cl Individual Consult Under Implement Hiring of ICT Expert for the L IDA / D9690 Post Open - National 20,000.00 0.00 2023-04-30 2023-04-26 2023-06-18 2023-07-09 2023-08-13 2024-02-09 imate and Trade ant Selection ation abria Business Registry (LBR) . LR-MOCI-358443-CS-INDV / Component 1: Investment Cl Individual Consult Under Implement Hiring of Corporate Lawyer fo IDA / D9690 Post Open - National 12,000.00 0.00 2023-04-30 2023-04-26 2023-06-18 2023-07-09 2023-08-13 2024-02-09 imate and Trade ant Selection ation r the Liberia Business Registr y LR-MOCI-361326-CS-INDV / Consultancy Services to Provi de Technical Assistance on C Component 2: SME Access t Individual Consult Open - Internationa Under Implement IDA / D9690 Post 120,000.00 0.00 2023-05-31 2023-06-13 2023-07-19 2023-08-09 2023-09-13 2024-03-11 oncessions Monitoring, Evalu o Markets and Finance ant Selection l ation ation and Compliance at the National Bureau of Concessio ns. LR-MOCI-363913-CS-INDV / Component 1: Investment Cl Individual Consult Open - Internationa Under Implement Hiring of SME Advisor for the IDA / D9690 Post 120,000.00 0.00 2023-06-15 2023-05-29 2023-08-03 2023-08-24 2023-09-28 2024-03-26 imate and Trade ant Selection l ation Ministry of Commerce and In dustry. LR-MOCI-364199-CS-INDV / Hiring of Consultant to Devel op Request for Bid for the Na Component 3: Digital Financi Individual Consult Open - Internationa tional Electronic Payment Swi IDA / D9690 Post 45,000.00 0.00 Under Review 2023-06-15 2023-05-31 2023-07-19 2023-08-03 2023-08-23 2023-10-22 al Services Infrastructure ant Selection l tch (NEPS), support the revie w of the Bid Documents and selection of the appropriate v endor for the NEPS Implemen tation . Page 2 TOGO PLAN DE PASSATION DES MARCHES SI PROJET : PROJET D’AMELIORATION DE LA QUALITE ET DE L’EQUITE DE L’EDUCATION DE BASE(PAQEEB) No d’identification du projet [P172674] PLAN DE PASSATION DE MARCHES SIMPLIFIE VERSION N° 1 I. GENERAL 1. Informations sur le Projet Emprunteur : République Togolaise Ministère : Ministère des enseignements primaire, Responsable secondaire, technique et de l’artisanat Nom du Projet : PROJET D’AMELIORATION DE LA QUALITE ET DE L’EQUITE DE L’EDUCATION DE BASE Identification : P172674 IDA N° Accord de Crédit/Accord de Don No… Structure chargée Unité de coordination du projet de la mise en œuvre du projet 2. Date d’approbation par la Banque du plan de passation de marchés : 3. Date de publication de l’Avis Général de Passation des Marchés : [A insérer plus tard 4. Période couverte par la Plan de Passation des Marchés : [A insérer dès à présent]…………… 5. Evaluation de risque par P-RAMS (Procurement Risk Assessment and Management System) : Substantiel Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Novembre 2020) (“Règlement de Passation des Marchés”), le Système 2 électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marchés se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus dans STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées.  Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans la loi No 2009-013 du 30 juin 2009 relative aux Marchés Publics et Délégation de Service Public, le Décret Nº 2009-277/PR du 11 novembre 2009 portant Code des Marchés Publics et Délégation de Service Public, et les textes d’application y afférents, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : • Le dossier d’appel d’offres/à propositions oblige le Soumissionnaire/les proposants présentant une Offre/Proposition à déposer un agrément signé, qui sera joint à tout contrat éventuel, pour confirmer qu’il applique et respecte les Directives de la Banque pour la lutte contre la corruption, y compris sans limitation, le droit de la Banque de sanctionner et les droits de la Banque pour l’inspection et l’audit ; • Le droit de la Banque d’examiner le dossier et les activités de passation des marchés. 3  Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). L’Assistance directe à la mise en œuvre (sigle HEIS en anglais) tel que précisée aux paragraphes 3.10 et 3.11 du Règlement de Passation des marchés ne s’applique pas. Seuils pour approches et méthodes de passation des marchés – Travaux, Fournitures, et Services non-consultant ; Approches et méthode de passation des marchés (US$) Catégorie Ouverte Ouverte Demande de Internationale Nationale cotation (DC) (AOI) (AON) Travaux ≥ 5 000 000 <5 000 000 ≤ 200 000 Fournitures et Services ≥ 500 000 <500 000 ≤ 100 000 non-consultant 4 II. TRAVAUX, FOURNITURES ET SERVICES AUTRES QUE LES SERVICES DE CONSULTANTS 1. Dispositions relatives aux seuils de revue préalable : Seuils requis pour les décisions de marchés soumis à la revue préalable de la Banque, tel que prévu dans les paragraphes 3.5 à 3.8 de la Section III, et de l’Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI), en date de Novembre 2020. Montants estimatifs des contrats en Catégories de marchés Observations millions de dollars américains Travaux (incluant clé à main, Fourniture et Installation, et les >= 10 Partenariat Public - Privé -PPP) Biens, Système d’Information et de Services autres que les Services >= 2 intellectuels Travaux (incluant clé à main, Fourniture et Installation, et les >= 10 Les justifications de Contrats à Partenariat Public - l’entente directe passer par Privé -PPP) devront être jointes entente Biens, Système et approuvées avec directe d’Information et de PPM Services autres que >= 2 les Services intellectuels 2. Pré qualification : Sans objet. 3. Dispositions spéciales sur les marchés : Concernant les acquisitions de véhicules et de carburant, en fonction des circonstances et des besoins spécifiques du pays, le seuil pour la consultation de fournisseurs pourrait être porté à la contre- valeur d’USD 500,000 (en prenant soin de consulter tous les principaux concessionnaires de marque ou distributeurs de produits pétroliers). Liste des marchés avec les méthodes de passation et les dates de mise en œuvre : Travaux 1 2 3 4 5 6 7 8 9 Revue de Méthode Date de Comment Ref. la Re Coût de lanceme aires/Fin Com Approche du Banque f. Description estimatif passatio nt de la de pos marché (a priori/a N° (US$) n des procédu prestatio ante posteriori marchés re ns ) Activités à l’étape projet Coût total en US$ 6 Fournitures et services autres que les services de consultants 1 2 3 4 5 6 7 8 9 Revue de Métho la Date de Ref. de de Commenta Coût Banque lancemen Ref. Com passati Approche du ires/Fin de Description estimatif (a t de la N° posa on des marché prestation (US$) priori/a procédur nte march s posterior e és i) Activités à l’étape projet Coût total en US$ III. SÉLECTION DES CONSULTANTS 1. Dispositions relatives aux seuils de revue préalable des marchés Décisions de sélection sujette à la revue préalable de la Banque comme indiqué dans Seuils requis pour les décisions de marchés soumis à la revue préalable de la Banque, tel que prévu dans les paragraphes 3.5 à 3.8 de la Section III, et de l’Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI), en date de Novembre 2020. Seuils de revue a priori Méthode de Montants estimatifs des sélection/Catégories Observations contrats en millions de de marchés dollars américains Méthode compétitive/Firmes de >= 1 consultants Entente Les justifications pour directe/firmes de >= 1 l’entente directe consultants devront être jointes et 7 Entente approuvées avec le directe/Consultants >= 0.3 PPM individuel Méthode Compétitive (Comparaison de CVs) >= 0.3 / Consultants individuels 2. Liste restreinte composée entièrement de firmes nationales : La liste restreinte de consultants pour les prestations d’études d’ingénierie, de contrôle et de surveillance estimées à moins de 300,000 US$ par contrat, et pour tout autre type de prestations, estimées à moins de 100 000 US$ par contrat, peut comporter entièrement de consultants nationaux en conformité avec les dispositions des Règlement de Passation des marchés., et l’Emprunteur ne procède pas à une publication dans UNDB. 3. Autre arrangement spécial de Sélection de consultants : Le seuil pour l’utilisation de la méthode de sélection de consultant fondée sur les qualifications des consultant est déterminé au cas par cas en tenant compte de la nature et de la complexité de la mission ; cependant, ce seuil ne devrait pas dépasser la contre-valeur de USD 300,000 sauf dans des cas exceptionnels telles des situations d’urgence en conformité au Règlement de Passation des marchés. Marchés de Services de Consultants 1. 2. 3. 4. 5. 6. 7. 8. 9. Revue de la Date de Ref Ref. Coût Méthode Banque lancemen Commentaires Approche . Composa Description des missions estimatif de (a t de la /Fin de du marché N° nte (US$) sélection priori/a procédur prestations posterio e ri) Activités à l’étape projet Coût total en US$ Lexique des Sigles et Abréviations PPM : Plan de Passation des Marchés AOI : Appel d’Offres International AON : Appel d’Offres National DC : Demande de Cotations SQC Sélection fondée sur les Qualifications des : Consultants SMC : Sélection au Moindre Coût CI : Consultant Individuel ED : Sélection Directe ou Entente Directe A Revue a posteriori : posteriori A Priori : Revue a priori PPM : Plan de Passation des Marchés DNCMP Direction Nationale de Contrôle des : Marchés Publics ARMP : Autorité de Régulation des Marchés Publics PROCUREMENT Togo : Togo, Improving Quality and Equity of Basic Education Project PLAN General Information Country: Togo 2022-04-12 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172674 GPN Date: 2022-03-20 Project Name: Togo, Improving Quality and Equity of Basic Education Project Loan / Credit No: IDA / D9010, TF / B6287 Project Coordination Unit - PAQEEB Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned TG-PCU-PAQEEB-356614-CW Component 1: Improving Qu Request for Quota -RFQ / Travaux de réfection d Request for Quota Single Stage - One E Pending Imp 2023-10-3 IDA / D9010 ality of Teaching and Learni Post Limited tions (Non Bank-S 313,540.00 0.00 2023-05-30 2023-08-01 es Ecoles Normales de Forma tions nvelope lementation 0 ng PD) tion des Professeurs d’Ecoles (ENFPE) de Notsè TG-PCU-PAQEEB-348838-CW National Procure -RFB / Travaux de réfection d Component 1: Improving Qu ment Document - Request for Quota Single Stage - One E Pending Imp 2023-11-0 es Ecoles Normales de Forma IDA / D9010 ality of Teaching and Learni Post Limited 1 Envelope proce 335,195.00 0.00 2023-05-30 2023-08-08 tions nvelope lementation 6 tion des Professeurs d’Ecoles ng ss (Non Bank-SPD (ENFPE) de Dapaong et de M ) ango TG-PCU-PAQEEB-356605-CW Component 1: Improving Qu Request for Quota -RFQ / Travaux de réfection d Request for Quota Single Stage - One E Pending Imp 2023-08-1 IDA / D9010 ality of Teaching and Learni Post Limited tions (Non Bank-S 248,450.00 0.00 2023-05-30 2023-08-01 es Ecoles Normales de Forma tions nvelope lementation 0 ng PD) tion des Professeurs d’Ecoles (ENFPE) d'Adéta TG-PCU-PAQEEB-356608-CW Component 1: Improving Qu Request for Quota -RFQ / Travaux de réfection d Request for Quota Single Stage - One E Pending Imp 2023-10-3 IDA / D9010 ality of Teaching and Learni Post Limited tions (Non Bank-S 257,770.00 0.00 2023-05-30 2023-08-01 es Ecoles Normales de Forma tions nvelope lementation 0 ng PD) tion des Professeurs d’Ecoles (ENFPE) de Tabligbo TG-PCU-PAQEEB-356613-CW -RFQ / Travaux de réfection d Component 1: Improving Qu Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-10-3 es Ecoles Normales de Forma IDA / D9010 ality of Teaching and Learni Post Limited tions (Non Bank-S 252,895.00 0.00 2023-05-30 2023-08-01 tions nvelope lementation 0 tion des Professeurs d’Ecoles ng PD) (ENFPE) de Sotouboua GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-PCU-PAQEEB-285558-GO -RFB / Acquisition de tablette Component 3: Strengthening s pour les DRE, inspections (i Single Stage - One E IDA / D9010 system management and re Post Request for Bids Open - National 340,000.00 0.00 Signed 2022-06-15 2022-06-20 2022-06-20 2022-07-20 2022-07-19 2022-09-03 2022-09-13 2022-10-15 2023-01-13 nspecteurs, conseillers, char nvelope silience gés de statistique) et aux ca dres des directions centrales et de l'UCP-PAQEEB TG-PCU-PAQEEB-285564-GO -RFB / Acquisition de matériel Component 3: Strengthening Single Stage - One E informatique (vidéo projecte IDA / D9010 system management and re Post Request for Bids Open - National 180,000.00 0.00 Signed 2022-06-15 2022-07-27 2022-06-20 2022-07-20 2022-08-26 2022-09-03 2022-10-05 2023-04-23 2023-07-22 nvelope ur, PC portable) aux inspectio silience ns et DRE, cellule genre, et a ux directions centrales TG-PCU-PAQEEB-285546-GO -RFQ / Acquisition de matérie Component 3: Strengthening Single Stage - One E ls informatiques pour la mise IDA / D9010 system management and re Post Request for Bids Open - National 400,000.00 0.00 Signed 2022-06-15 2022-08-04 2022-06-20 2022-07-20 2022-12-05 2022-09-03 2023-02-15 2022-10-08 2023-02-05 nvelope en place d'une plateforme d' silience enseignement en ligne TG-PCU-PAQEEB-296639-GO -RFQ / Acquisition d'équipem ents (MICROPHONE FILAIRE, Component 2: Improve equit LECTEUR DVD EXTERNE, ÉCO able access to basic educati Request for Quota Single Stage - One E UTEURS INTRA-AURICULAIRE IDA / D9010 Post Limited 40,000.00 0.00 Canceled 2022-06-20 2022-07-29 2022-08-23 2022-11-21 on (primary and lower-secon tions nvelope S, MICRO SANS FIL, KIT ACCE dary) SSOIRES POUR MICROPHONE S, etc.…) pour la salle de pro duction de la plateforme d'en seignement en ligne TG-PCU-PAQEEB-296770-GO -RFQ / Acquisition du matérie Component 1: Improving Qu Request for Quota Single Stage - One E l informatique pour le compt IDA / D9010 ality of Teaching and Learni Post Limited 80,000.00 0.00 Signed 2022-06-15 2022-09-19 2022-08-18 2022-11-16 tions nvelope e de l’INSE, l’ENS d’Atakpam ng é et la Fast de l’Université de Kara TG-PCU-PAQEEB-285554-GO Component 3: Strengthening Open - Internationa Single Stage - One E -RFB / Acquisition de 24 véhi IDA / D9010 system management and re Post Request for Bids 1,056,000.00 0.00 Signed 2022-09-15 2022-10-21 2022-09-20 2022-10-21 2022-11-01 2022-12-01 2022-12-01 2023-02-13 2023-01-31 2023-05-01 l nvelope cules PICKUP pour les inspect silience ions TG-PCU-PAQEEB-328197-GO -RFB / Acquisition d'équipem ents (MICROPHONE FILAIRE, Component 2: Improve equit LECTEUR DVD EXTERNE, ÉCO able access to basic educati Single Stage - One E Under Imple UTEURS INTRA-AURICULAIRE IDA / D9010 Post Request for Bids Open - National 160,000.00 0.00 2022-12-15 2022-12-20 2022-12-20 2023-01-19 2023-01-23 2023-02-27 2023-03-08 on (primary and lower-secon nvelope mentation S, MICRO SANS FIL, KIT ACCE dary) SSOIRES POUR MICROPHONE S, etc.…) pour la salle de pro duction de la plateforme d'en seignement en ligne TG-PCU-PAQEEB-348484-GO -RFB / Acquisition de tablette s pour le personnel d'encadr Component 1: Improving Qu Open - Internationa Single Stage - One E Pending Impl ement, les élèves professeur IDA / D9010 ality of Teaching and Learni Post Request for Bids 1,279,990.00 0.00 2023-03-27 2023-04-03 2023-05-15 2023-06-14 2023-07-26 2023-10-24 l nvelope ementation s d'écoles et les élèves du pri ng maire pour la phase pilote de la numérisation des apprenti ssages au primaire Page 1 TG-PCU-PAQEEB-348501-GO -RFB / Acquisition de matériel s informatiques pour les élèv Component 1: Improving Qu Open - Internationa Single Stage - One E Under Imple es inspecteurs et les conseill IDA / D9010 ality of Teaching and Learni Post Request for Bids 564,560.00 0.00 2023-04-05 2023-05-26 2023-04-12 2023-05-26 2023-05-24 2023-06-23 2023-08-04 2023-08-13 l nvelope mentation ers pédagogiques, pour la Dir ng ection de l'Enseignement Sec ondaire Général (DESG), pou r le CNDP-TICE et l'ENEAS. TG-PCU-PAQEEB-307487-GO Component 3: Strengthening -RFQ / Acquisition d'un véhic Request for Quota Single Stage - One E IDA / D9010 system management and re Post Limited 50,000.00 0.00 Canceled 2022-12-10 2023-01-12 2023-02-12 2023-04-13 ule station wagon pour l'Unit tions nvelope silience é de Coordination du Projet TG-PCU-PAQEEB-353825-GO -RFQ / Acquisition de deux vé Component 3: Strengthening hicules station wagon pour l' Request for Quota Single Stage - One E Under Imple IDA / D9010 system management and re Post Limited 100,000.00 0.00 2023-05-25 2023-06-06 2023-08-03 2023-09-02 unité de coordination du proj tions nvelope mentation silience et et de la Direction de la Pla nification de statistiques et d e suivi-évaluation TG-PCU-PAQEEB-353828-GO Component 2: Improve equit -RFQ / Acquisition et installati able access to basic educati Request for Quota Single Stage - One E Pending Impl IDA / D9010 Post Limited 60,000.00 0.00 2023-05-30 2023-08-15 2023-10-14 on de dispositifs de visioconf on (primary and lower-secon tions nvelope ementation érence dans les 6 ENFPE et l dary) a DPIP TG-PCU-PAQEEB-354335-GO Component 1: Improving Qu Request for Quota Single Stage - One E -RFQ / Acquisition de matérie IDA / D9010 ality of Teaching and Learni Post Limited 17,500.00 0.00 Canceled 2023-04-25 2023-06-20 2023-07-20 tions nvelope l de géométrie au profit des ng ENFPE TG-PCU-PAQEEB-363225-GO -RFB / Acquisition et distribut Component 1: Improving Qu Open - Internationa Single Stage - One E Pending Impl ion des manuels et guides sc TF / B6287 ality of Teaching and Learni Prior Request for Bids 5,000,000.00 0.00 2023-06-05 2023-06-10 2023-07-22 2023-08-21 2023-10-02 2023-12-31 l nvelope ementation olaires pour les préscolaires ng section 1 et 2, et des cours p réparatoires 1 et 2 TG-PCU-PAQEEB-367783-GO Component 1: Improving Qu Request for Quota Single Stage - One E Pending Impl -RFQ / Acquisition de matérie IDA / D9010 ality of Teaching and Learni Post Limited 17,500.00 0.00 2023-07-05 2023-09-06 2024-01-04 tions nvelope ementation l de géométrie au profit des ng ENFPE NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-PCU-PAQEEB-285027-NC- Component 1: Improving Qu Request for Quota Single Stage - One E Pending Impl RFQ / Reproduction des guid TF / B6287 ality of Teaching and Learni Post Limited 17,000.00 0.00 2022-05-30 2022-08-17 2022-10-16 tions nvelope ementation es de cours pour la formation ng des enseignants TG-PCU-PAQEEB-285496-NC- Component 3: Strengthening Request for Quota Single Stage - One E Under Imple RFQ / Reproduction des guid IDA / D9010 system management and re Post Limited 50,000.00 0.00 2022-07-25 2022-07-18 2022-09-19 2023-03-18 tions nvelope mentation es illustrés pour les formatio silience ns FGB TG-PCU-PAQEEB-285005-NC- Component 1: Improving Qu RFQ / Impression des module Request for Quota Single Stage - One E IDA / D9010 ality of Teaching and Learni Post Limited 40,000.00 0.00 Canceled 2022-05-21 2022-07-29 2022-08-08 2022-10-07 s de formation en français et tions nvelope ng en mathématiques du CE2 TG-PCU-PAQEEB-285050-NC- RFQ / Impression du guide si Component 1: Improving Qu mplifié/circulaire de gestion Request for Quota Single Stage - One E IDA / D9010 ality of Teaching and Learni Post Limited 39,500.00 0.00 Signed 2022-07-05 2022-09-01 2022-09-29 2022-11-28 de la subvention et des regis tions nvelope ng tres de gestion aux inspectio ns (IEPP/IESG) et aux DRE po ur le suivi-accompagnement TG-PCU-PAQEEB-285058-NC- RFQ / Reproduction des regis Component 1: Improving Qu Request for Quota Single Stage - One E tres de la tenue de la compt IDA / D9010 ality of Teaching and Learni Post Limited 13,600.00 0.00 Signed 2022-06-25 2022-09-01 2022-09-19 2022-11-18 tions nvelope abilité aux COGEPs /COGERE ng S et aux inspections/DRE TG-PCU-PAQEEB-285547-NC- Component 3: Strengthening RFQ / Assurance maladie-indi Request for Quota Single Stage - One E IDA / D9010 system management and re Post Limited 50,000.00 0.00 Signed 2022-09-20 2022-09-27 2022-11-29 2023-11-29 viduel accident et décès UCP tions nvelope silience -PAQEEB pour une période d e deux (02) ans TG-PCU-PAQEEB-285414-NC- DIR / Acquisition d'un module Component 3: Strengthening supplémentaire de schoolfee IDA / D9010 system management and re Post Direct Selection Direct - National 30,000.00 0.00 Signed 2022-10-18 2022-08-26 2022-10-23 2022-09-05 2022-12-27 2023-03-27 s pour la gestion des dotatio silience ns aux écoles et formation d es chefs sections finance des inspections TG-PCU-PAQEEB-328196-NC- Component 1: Improving Qu RFB / Impression des module Single Stage - One E Under Imple IDA / D9010 ality of Teaching and Learni Post Request for Bids Open - National 160,000.00 0.00 2022-12-15 2022-12-27 2022-12-20 2023-01-19 2023-01-26 2023-03-05 2023-04-09 2023-06-08 s de formation en français et nvelope mentation ng en mathématiques du CE2 TG-PCU-PAQEEB-329090-NC- RFQ / Reproduction et distrib ution des manuels scolaires a ux élèves de préscolaires sec Component 1: Improving Qu Request for Quota Single Stage - One E Under Imple tion 1 et 2, et des cours prép IDA / D9010 ality of Teaching and Learni Prior Limited 5,000,000.00 0.00 2023-01-15 2023-01-13 2023-03-12 2023-04-26 tions nvelope mentation aratoires 1 et 2 en deux lots : ng Lot 1 : préscolaires section 1 et préscolaires 2, Lot 2 : CP1 et CP2 TG-PCU-PAQEEB-348855-NC- RFB / Impression des plans d étaillés de cours pour les ens eignants volontaires, des mo Component 1: Improving Qu Single Stage - One E dules de formation sur l'éval TF / B6287 ality of Teaching and Learni Post Request for Bids Open - National 120,000.00 0.00 Canceled 2023-07-25 2023-07-30 2023-08-29 2023-09-28 2023-11-09 2024-01-08 nvelope uation en APC, reproduction ng des guides de cours pour la f ormation des enseignants et Impression du manuel sur la santé scolaire (SH). TG-PCU-PAQEEB-348503-NC- RFB / Assurances tous risque Component 3: Strengthening Request for Quota Single Stage - One E Under Imple s pour les 24 véhicules pick-u IDA / D9010 system management and re Post Limited 84,000.00 0.00 2023-04-25 2023-05-16 2023-06-27 2024-06-21 tions nvelope mentation p pour les inspections pour u silience ne durée d'une année. Page 2 TG-PCU-PAQEEB-368706-NC- RFQ / Impression des plans d Component 1: Improving Qu Request for Quota Single Stage - One E Pending Impl étaillés de cours pour les ens IDA / D9010 ality of Teaching and Learni Post Limited 60,000.00 0.00 2023-07-18 2023-09-19 2023-11-18 tions nvelope ementation eignants volontaires et des ng modules de formation sur l'é valuation en APC. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-PCU-PAQEEB-285037-CS- Component 1: Improving Qu QCBS / Recrutement d'un édi Quality And Cost- Open - Internationa IDA / D9010 ality of Teaching and Learni Post 300,000.00 0.00 Signed 2022-04-15 2022-06-15 2022-05-06 2022-07-27 2022-06-12 2022-10-25 2022-07-27 2022-11-23 2022-09-10 2022-12-19 2022-10-24 2023-02-14 2022-11-28 2023-05-27 teur pour l'édition des manu Based Selection l ng els et guides du CM1 TG-PCU-PAQEEB-285500-CS- Component 3: Strengthening Quality And Cost- Open - Internationa QCBS / Recrutement d'un Ag IDA / D9010 system management and re Post 400,000.00 0.00 Signed 2022-04-04 2022-07-06 2022-04-18 2022-07-11 2022-05-25 2022-10-19 2022-07-09 2022-11-22 2022-08-23 2022-12-16 2022-09-27 2023-03-30 2022-11-08 2026-10-08 Based Selection l ent Vérificateur Indépendant silience TG-PCU-PAQEEB-285503-CS- Component 3: Strengthening LCS / Recrutement de l'Audit Least Cost Selecti IDA / D9010 system management and re Post Open - National 90,000.00 0.00 Signed 2022-04-15 2022-05-17 2022-05-06 2022-06-12 2022-09-13 2022-07-12 2022-10-12 2022-08-11 2022-11-07 2022-09-08 2022-11-23 2022-10-20 2025-10-19 eur Externe pour les exercice on silience s 2022,2023 et 2024 TG-PCU-PAQEEB-285045-CS- Component 1: Improving Qu CQS / Recrutement d'un édit Consultant Qualifi Open - Internationa IDA / D9010 ality of Teaching and Learni Post 200,000.00 0.00 Signed 2022-06-20 2022-08-10 2022-07-11 2022-08-22 2022-08-28 2022-11-02 2022-09-27 2023-01-05 2022-11-01 2023-04-30 eur pour l'édition des manue cation Selection l ng ls de technologie ( 6ème, 5è me, 4ème, 3ème) TG-PCU-PAQEEB-348826-CS- CQS / Recrutement d'un cons Component 3: Strengthening ultant pour la réalisation de l' Consultant Qualifi Open - Internationa Pending Impleme IDA / D9010 system management and re Post 100,000.00 0.00 2023-05-25 2023-06-08 2023-07-22 2023-08-21 2023-10-02 2023-12-01 enquête sur la transition des cation Selection l ntation silience jeunes diplômés de l'enseign ement supérieur et des EFFP vers la vie active TG-PCU-PAQEEB-348827-CS- Component 3: Strengthening CQS / Recrutement d'un cabi Consultant Qualifi IDA / D9010 system management and re Post Open - National 90,000.00 0.00 Under Review 2023-04-20 2023-04-25 2023-05-04 2023-06-17 2023-07-17 2023-08-28 2023-10-27 net pour l'évaluation des acq cation Selection silience uis scolaires EGMA et EGRA TG-PCU-PAQEEB-348824-CS- Component 3: Strengthening Quality And Cost- Open - Internationa CQS / Recrutement d'un cabi IDA / D9010 system management and re Post 260,000.00 0.00 Canceled 2023-05-15 2023-06-05 2023-07-19 2023-07-23 2023-08-22 2023-10-03 2023-11-14 2023-12-14 Based Selection l net pour la réalisation de l'en silience quête SDI TG-PCU-PAQEEB-361288-CS- CDS / Recrutement d'un cabi Component 3: Strengthening net en formation en gestion Consultant Qualifi Open - Internationa Pending Impleme IDA / D9010 system management and re Post 100,000.00 0.00 2023-06-30 2023-07-14 2023-08-18 2023-09-08 2023-10-13 2024-10-07 a la base (FGB) pour appuyer cation Selection l ntation silience la DPSSE dans la mise en œu vre de l’approche communau taire INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-PCU-PAQEEB-285070-CS- INDV / Recrutement d'un con sultant pour faire l'Etat des li Component 2: Improve equit eux et identification des beso able access to basic educati Individual Consult ins en ressources humaines TF / B6287 Post Open 20,000.00 0.00 Signed 2022-07-20 2022-06-15 2022-09-07 2022-09-26 2022-09-10 2022-10-19 2022-10-22 2022-12-21 on (primary and lower-secon ant Selection et équipement pour le bon fo dary) nctionnement de la cellule ge nre et élaborer une stratégie nationale d’intégration du ge nre dans la planification TG-PCU-PAQEEB-285497-CS- CDS / Recrutement d'un cons ultant par entente directe po Component 3: Strengthening ur la poursuite de l'élaboratio IDA / D9010 system management and re Post Direct Selection Direct 35,600.00 0.00 Signed 2022-09-20 2022-07-20 2022-10-02 2022-07-20 2022-12-06 2023-01-20 n du document de politique n silience ationale d'offre de service d'i nformation et d'orientation s colaires et professionnelles. TG-PCU-PAQEEB-285083-CS- Component 2: Improve equit CDS / Sélection par entente d able access to basic educati IDA / D9010 Post Direct Selection Direct 280,000.00 0.00 Signed 2022-05-20 2022-07-20 2022-05-30 2022-07-20 2022-08-10 2022-11-08 ire de l'IIPE pour l' opérationn on (primary and lower-secon alisation du système de la ca dary) rte scolaire TG-PCU-PAQEEB-285402-CS- CDS / Recrutement d'un cons ultant individuel pour l'élabor Component 3: Strengthening Individual Consult ation du schéma directeur su IDA / D9010 system management and re Post Open 22,000.00 0.00 Signed 2022-06-30 2022-07-13 2022-08-18 2022-10-05 2022-09-17 2022-10-26 2022-10-22 2022-12-21 ant Selection r la mise en œuvre de la for silience mation initiale et continue de les acteurs du système éduc atif TG-PCU-PAQEEB-285412-CS- CDS / Recrutement d'un cons ultant national (coache) pour Component 3: Strengthening Individual Consult accompagner l'équipe des dé IDA / D9010 system management and re Post Open 18,000.00 0.00 Signed 2022-06-15 2022-07-13 2022-08-03 2022-09-15 2022-09-02 2022-10-21 2022-10-07 2023-04-05 ant Selection veloppeurs d'une plateforme silience unique de gestion des notes des élèves de tous les établis sements scolaires TG-PCU-PAQEEB-285409-CS- CDS / Recrutement d'un cons Component 3: Strengthening ultant StatEduc expert SIGE IDA / D9010 system management and re Post Direct Selection Direct - National 40,000.00 0.00 Signed 2022-09-15 2022-09-26 2022-09-25 2022-09-26 2022-11-29 2023-02-27 par entente directe pour l'op silience timisation du du Système d'I nformation de Gestion de l'E ducation (SIGE) TG-PCU-PAQEEB-285020-CS- Component 1: Improving Qu INDV / Recrutement d'un con Individual Consult TF / B6287 ality of Teaching and Learni Post Open 40,000.00 0.00 Canceled 2022-04-15 2022-06-03 2022-07-03 2022-08-07 2022-11-05 sultant pour la mise en œuvr ant Selection ng e de l'outil TEACH Page 3 TG-PCU-PAQEEB-285031-CS- Component 1: Improving Qu INDV / Recrutement d'un con Individual Consult TF / B6287 ality of Teaching and Learni Post Open 30,000.00 0.00 Canceled 2022-05-10 2022-06-28 2022-07-28 2022-09-01 2022-10-31 sultant individuel pour l'élab ant Selection ng oration de la politique des m anuels scolaires TG-PCU-PAQEEB-307500-CS- CDS / Recrutement d'un cabi Component 1: Improving Qu Direct - Internation net par entente directe pour l TF / B6287 ality of Teaching and Learni Post Direct Selection 30,000.00 0.00 Signed 2022-09-15 2022-10-05 2022-09-25 2022-10-07 2022-11-29 2023-01-28 al 'élaboration de la politique d ng es manuels scolaires TG-PCU-PAQEEB-307562-CS- INDV / Recrutement d'un con sultant individuel internation Component 3: Strengthening Individual Consult Open - Internationa Under Implement al en formation en gestion a l IDA / D9010 system management and re Post 50,000.00 0.00 2022-12-05 2022-12-26 2023-01-23 2023-02-22 2023-03-29 2023-06-27 ant Selection l ation a base (FGB) pour appuyer la silience DPSSE dans la mise en œuvr e de l’approche communauta ire TG-PCU-PAQEEB-328193-CS- INDV / Recrutement d'un con Component 3: Strengthening sultant individuel national en Individual Consult Under Implement IDA / D9010 system management and re Post Open - National 50,000.00 0.00 2022-12-15 2022-12-26 2023-02-02 2023-03-04 2023-04-08 2023-10-05 formation en gestion a la bas ant Selection ation silience e (FGB) pour appuyer la DPS SE dans la mise en œuvre de l’approche communautaire TG-PCU-PAQEEB-348831-CS- INDV / Recrutement d'un con Component 3: Strengthening Individual Consult sultant individuel pour la nu IDA / D9010 system management and re Post Open - National 50,000.00 0.00 Under Review 2023-05-25 2023-04-25 2023-07-13 2023-08-03 2023-09-14 2023-10-14 ant Selection mérisation des nouveaux out silience ils de gestion : ETP, IRRP, TIS E, MAGEV, CC TG-PCU-PAQEEB-348841-CS- INDV / Recrutement d'un con Component 1: Improving Qu sultant en ingénierie pédago Individual Consult TF / B6287 ality of Teaching and Learni Post Open - National 16,000.00 0.00 Under Review 2023-05-25 2023-06-16 2023-07-13 2023-08-03 2023-09-14 2023-11-13 gique auprès de la DRH de la ant Selection ng DESG et de la DEPP dans le c adre de la reforme curriculair e TG-PCU-PAQEEB-296779-CS- INDV / Recrutement d’un con Component 3: Strengthening sultant individuel pour la mis Individual Consult IDA / D9010 system management and re Post Open 40,000.00 0.00 Canceled 2022-07-15 2022-07-25 2022-09-02 2022-10-13 2022-10-02 2022-11-06 2023-02-04 e en œuvre des recommanda ant Selection silience tions du rapport de l’évaluati on du pilotage sectoriel de l’ éducation au Togo TG-PCU-PAQEEB-354394-CS- INDV / Recrutement d’un con Component 3: Strengthening Individual Consult sultant pour la formation des IDA / D9010 system management and re Post Direct - National 4,250.00 0.00 Canceled 2023-04-17 2023-04-27 2023-05-18 2023-06-22 2023-07-02 ant Selection cadres de l’ENEAS sur les mé silience thodes quantitatives des don nées TG-PCU-PAQEEB-354341-CS- INDV / Recrutement d’un con Component 3: Strengthening sultant pour la formation des Individual Consult Direct - Internation IDA / D9010 system management and re Post 7,000.00 0.00 Canceled 2023-04-13 2023-04-23 2023-05-14 2023-06-18 2023-06-28 cadres de l’ENEAS sur le pilot ant Selection al silience age et gestion des évaluation s à large échelle internationa le et nationale. TG-PCU-PAQEEB-285499-CS- INDV / Recrutement d'un con Component 3: Strengthening Individual Consult sultant individuel pour le Dia IDA / D9010 system management and re Post Open 30,000.00 0.00 Canceled 2022-06-15 2022-07-19 2022-08-03 2022-09-02 2022-10-14 2022-12-13 ant Selection gnostic institutionnel du syst silience ème national d'évaluation de s apprentissages (SNEA) TG-PCU-PAQEEB-285498-CS- Component 3: Strengthening CDS / Recrutement d'un cons Individual Consult IDA / D9010 system management and re Post Open 30,000.00 0.00 Canceled 2022-06-10 2022-07-29 2022-08-28 2022-10-02 2023-03-31 ultant individuel en ingénieri ant Selection silience e pédagogique auprès de la DF et de la DEPP TG-PCU-PAQEEB-285504-CS- INDV / Recrutement d'un con Component 3: Strengthening sultant pour l'Etude de faisab Individual Consult IDA / D9010 system management and re Post Open 30,000.00 0.00 Canceled 2022-05-30 2022-08-03 2022-08-24 2022-10-05 2022-12-04 ilité pour usage de l'instrume ant Selection silience nt PPP en Education pour la c onstruction d'infrastructures scolaires TG-PCU-PAQEEB-367785-CS- INDV / Recrutement d'un con Component 3: Strengthening sultant individuel pour appuy Individual Consult Pending Impleme IDA / D9010 system management and re Post Open - National 36,000.00 0.00 2023-06-30 2023-08-09 2023-09-08 2023-10-13 2023-12-12 er l'équipe nationale d'évalua ant Selection ntation silience tion des acquis scolaires (EN EAS) pour la réalisation de l'e nquête SDI TG-PCU-PAQEEB-367787-CS- INDV / Recrutement d'un con Component 3: Strengthening sultant individuel pour appuy Individual Consult Pending Impleme IDA / D9010 system management and re Post Open - National 30,000.00 0.00 2023-06-30 2023-08-09 2023-09-08 2023-10-13 2023-12-12 er l'équipe nationale d'évalua ant Selection ntation silience tion des acquis scolaires (EN EAS) pour l'évaluation des ac quis scolaires EGMA et EGRA TG-PCU-PAQEEB-368690-CS- CDS / Recrutement de L’ONG Component 2: Improve equit PLAN INTERNATIONAL TOGO able access to basic educati Pending Impleme pour appuyer la cellule genre TF / B6287 Post Direct Selection Direct - National 24,000.00 0.00 2023-07-10 2023-07-20 2023-09-23 2024-09-17 on (primary and lower-secon ntation dans la réalisation des activit dary) és de promotion de la scolari sation des filles dans le cadre de la mise en œuvre du PAQ EEB Page 4 PROCUREMENT PLAN (Textual Part) Project information: [Vanuatu] [Vanuatu Climate Resilient Transport Project (VCRTP)] [P167382] Project Implementation agency: [Ministry of Infrastructure and Public Utilities ] Date of the Procurement Plan: [November 25, 2019] Period covered by this Procurement Plan: [November 25, 2019 – May 25, 2021] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used.- Not Applicable Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable]; Works: [is not applicable/] Other Relevant Procurement Information. Not Applicable. PROCUREMENT Vanuatu : Vanuatu Climate Resilient Transport Project PLAN General Information Country: Vanuatu 2018-12-20 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167382 GPN Date: 2020-07-21 Project Name: Vanuatu Climate Resilient Transport Project Loan / Credit No: / , IDA / V2530, IDA / 65310 Ministry of Infrastructure and Public Utilities Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - VU-MIPU-258651-CW-RFB / R Component 2: Climate Resili Open - Internationa Single Stage - One E Works (without pr Pending Imp 2023-03-1 epair and Upgrading of Sarak IDA / V2530 Prior Request for Bids 5,466,450.00 0.00 2022-05-31 2022-06-05 2022-07-17 2022-08-16 2022-09-20 ent Infrastructure Solutions l nvelope equalification) SP lementation 9 ata to St. Michael road sectio D n km 5.0 Request for Bids - VU-MIPU-555002-CW-RFB / U Component 2: Climate Resili Open - Internationa Single Stage - One E Works (without pr 55,687,960.0 Pending Imp 2022-10-1 pgrading of Saint Michel–Tas IDA / V2530 Prior Request for Bids 0.00 2021-12-31 2022-01-05 2022-02-16 2022-03-18 2022-04-22 ent Infrastructure Solutions l nvelope equalification) SP 0 lementation 9 siriki section (60.2 km) D National Procure VU-MIPU-555005-CW-RFQ / P ment Document - Component 2: Climate Resili Request for Quota Single Stage - One E Pending Imp 2024-02-2 iloting of multi-year performa IDA / V2530 Post Limited 1 Envelope proce 705,000.00 0.00 2023-07-06 2023-08-31 ent Infrastructure Solutions tions nvelope lementation 7 nce-based maintenance cont ss (Non Bank-SPD racts (65 km) ) Request for Quota VU-MIPU-297737-CW-RFQ / Component 2: Climate Resili Request for Quota Single Stage - One E tions - Small Work 2023-02-0 Urgent Road Maintenance W IDA / V2530 Post Limited 200,000.00 217,983.16 Signed 2022-06-13 2022-06-01 2022-08-08 2022-07-18 ent Infrastructure Solutions tions nvelope s (Emergency) SP 4 orks to the South Santo D -Competitive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual VU-MIPU-555022-GO-RFQ / 2 Component 3: Strengthening Request for Quota Single Stage - One E No. Vehicles for Project Mana IDA / V2530 Post Open - National 60,000.00 93,721.98 Signed 2020-04-18 2020-06-13 2021-08-21 2020-12-10 the Enabling Environment tions nvelope gement Operations NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual VU-MIPU-91761-CS-LCS / Fin Least Cost Selecti Under Implement / Post Open - National 10,000.00 0.00 2019-02-01 2021-06-07 2019-02-22 2019-04-07 2019-05-05 2019-06-04 2019-07-09 2019-11-01 2020-07-31 ancial Audit Services on ation VU-MIPU-91756-CS-QCBS / P Quality And Cost- Open - Internationa / Prior 4,850,000.00 0.00 Canceled 2018-12-17 2019-01-21 2019-02-05 2019-03-06 2019-04-03 2019-05-03 2019-06-07 2019-07-12 2020-03-18 roject Preparation Consultant Based Selection l VU-MIPU-120261-CS-QCBS / Component 2: Climate Resili Quality And Cost- Open - Internationa IDA / V2530 Prior 4,650,000.00 0.00 Canceled 2019-07-15 2019-08-05 2019-09-16 2019-10-14 2019-11-18 2019-12-09 2020-01-13 2024-01-12 Design and Supervision Cons ent Infrastructure Solutions Based Selection l ultant VU-MIPU-91756-CS-QCBS-2 / Consultancy Services for Det ailed Design and Supervision Component 1: Sectoral and Quality And Cost- Open - Internationa Services for the South Santo IDA / V2530 Prior 4,245,410.00 4,017,100.00 Signed 2019-10-24 2019-10-29 2019-11-14 2019-10-30 2019-12-28 2019-12-29 2020-01-25 2020-02-25 2020-02-24 2020-04-16 2020-03-30 2020-07-14 2020-05-04 2020-11-24 2021-05-04 Spatial Planning Tools Based Selection l 66 Kms with services split as follows: Phase 1 – Detailed E ngineering Design and Pha se 2 – Construction Supervisi on. VU-MIPU-555006-CS-QCBS / Consulting Services for MIPU Component 3: Strengthening Quality And Cost- Open - Internationa Pending Impleme Technical Planning, Process S IDA / V2530 Prior 645,000.00 0.00 2020-05-01 2020-05-22 2020-07-05 2020-08-02 2020-09-01 2020-10-06 2020-11-10 2021-11-10 the Enabling Environment Based Selection l ntation trengthening and  Update of Technical Specifications. VU-MIPU-555007-CS-CQS / C onsulting Services for Road C Component 3: Strengthening Consultant Qualifi Open - Internationa Pending Impleme ondition Assesment and Impl IDA / V2530 Post 350,000.00 0.00 2020-06-01 2020-06-22 2020-08-05 2020-09-04 2020-10-09 2021-04-07 the Enabling Environment cation Selection l ntation ementation of the transition plan to put the RAMS into op eration VU-MIPU-555009-CS-CQS / C Component 3: Strengthening Consultant Qualifi Open - Internationa Pending Impleme onsultancy Services for Imple IDA / V2530 Post 400,000.00 0.00 2020-07-01 2020-07-22 2020-09-04 2020-10-04 2020-11-08 2021-05-07 the Enabling Environment cation Selection l ntation mentation of GAP and GBV/V AC strategy VU-MIPU-555023-CS-CQS / Y Component 3: Strengthening Consultant Qualifi Under Implement IDA / V2530 Post Limited 50,000.00 0.00 2020-05-01 2021-06-21 2020-05-15 2023-05-02 2020-06-14 2023-05-03 2020-07-19 2021-01-15 early audits the Enabling Environment cation Selection ation VU-MIPU-555008-CS-CQS / C onsultancy Services for Clima Component 3: Strengthening Consultant Qualifi Open - Internationa Pending Impleme IDA / V2530 Post 125,000.00 0.00 2020-07-01 2020-07-22 2020-09-04 2020-10-04 2020-11-08 2021-05-07 te change capacity building the Enabling Environment cation Selection l ntation within MIPU in collaboration with MCCA VU-MIPU-555001-CS-CQS / C Component 1: Sectoral and Consultant Qualifi Open - Internationa Under Implement onsultancy Services for Devel IDA / V2530 Post 280,000.00 0.00 2020-05-01 2022-08-12 2020-05-22 2022-09-01 2020-07-05 2020-08-04 2020-09-08 2021-03-07 Spatial Planning Tools cation Selection l ation oping of Road Asset Manage ment System INDIVIDUAL CONSULTANTS Page 1 Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual VU-MIPU-91760-CS-INDV / Pr Component 1: Sectoral and Individual Consult IDA / V2530 Post Limited 50,000.00 59,900.00 Signed 2019-01-25 2019-01-30 2019-01-21 2019-02-20 2019-02-12 2019-03-27 2019-03-12 2020-03-26 ocurement Specialist Spatial Planning Tools ant Selection VU-MIPU-119508-CS-INDV / I Component 2: Climate Resili Individual Consult nternational Social Developm IDA / V2530 Post Open 75,000.00 75,000.00 Signed 2019-06-24 2019-06-24 2019-07-17 2019-08-19 2019-07-19 2019-08-19 2019-07-25 2019-08-29 2019-12-22 ent Infrastructure Solutions ant Selection ent Specialist VU-MIPU-119510-CS-INDV / L Component 2: Climate Resili Individual Consult IDA / V2530 Post Open 25,000.00 25,000.00 Signed 2019-06-24 2019-06-24 2019-07-17 2019-09-01 2019-07-19 2019-09-28 2019-08-26 2019-08-29 2020-01-23 ocal Social Development Spe ent Infrastructure Solutions ant Selection cialist VU-MIPU-119511-CS-INDV / L Component 2: Climate Resili Individual Consult ocal Environmental Develop IDA / V2530 Post Open 25,000.00 22,525.40 Signed 2019-06-24 2019-06-24 2019-07-17 2019-08-19 2019-07-19 2019-08-28 2019-07-25 2019-08-29 2019-12-22 ent Infrastructure Solutions ant Selection ment Specialist VU-MIPU-119509-CS-INDV / I Component 2: Climate Resili Individual Consult nternational environmental D IDA / V2530 Post Open 75,000.00 75,000.00 Signed 2019-06-24 2019-06-24 2019-07-17 2019-08-19 2019-07-19 2019-10-17 2019-07-25 2019-08-29 2019-12-22 ent Infrastructure Solutions ant Selection evelopment Specialist VU-MIPU-120077-CS-INDV / Component 2: Climate Resili Individual Consult IDA / V2530 Prior Open 40,000.00 319,810.00 Signed 2019-06-22 2019-06-24 2019-07-15 2019-09-01 2019-07-17 2019-09-01 2019-07-23 2019-08-30 2019-12-20 Procurement Specialist - 2 ent Infrastructure Solutions ant Selection VU-MIPU-555025-CS-INDV / Deputy Head Project Implem Component 3: Strengthening Individual Consult entation Unit- PIU- Internatio IDA / 65310 Post Open 245,000.00 0.00 Canceled 2020-02-17 2020-05-26 2020-04-06 2020-04-27 2020-06-01 2020-11-28 the Enabling Environment ant Selection nal to provide technical and operational support to Head PIU. VU-MIPU-555018-CS-INDV / Component 3: Strengthening Individual Consult IDA / V2530 Prior Open 320,000.00 0.00 Canceled 2020-02-17 2020-04-06 2020-04-27 2020-06-01 2020-11-28 Procurement Specialist (Inter the Enabling Environment ant Selection national) VU-MIPU-555021-CS-INDV / Component 3: Strengthening Individual Consult Social Safeguards Specialist ( IDA / V2530 Post Open 270,000.00 235,200.00 Signed 2020-03-16 2020-05-26 2020-05-04 2021-02-15 2020-05-25 2021-03-01 2020-06-29 2021-03-06 2020-12-26 the Enabling Environment ant Selection International) VU-MIPU-555017-CS-INDV / Component 3: Strengthening Individual Consult Road and Bridge Engineer/PS IDA / V2530 Prior Open 900,000.00 0.00 Canceled 2020-03-16 2020-05-04 2020-05-25 2020-06-29 2020-12-26 the Enabling Environment ant Selection T Coordinator (International) VU-MIPU-555015-CS-INDV / Component 3: Strengthening Individual Consult Pending Impleme IDA / V2530 Post Open 60,000.00 0.00 2020-02-17 2020-04-06 2020-04-27 2020-06-01 2020-11-28 Administrative Officer (Local) the Enabling Environment ant Selection ntation VU-MIPU-555010-CS-INDV / Component 3: Strengthening Individual Consult IDA / V2530 Post Open 110,000.00 0.00 Canceled 2020-03-16 2020-05-26 2020-05-04 2020-05-25 2020-06-29 2020-12-26 Procurement Specialist (Loca the Enabling Environment ant Selection l) VU-MIPU-555020-CS-INDV / Component 3: Strengthening Individual Consult Environmental Safeguards Sp IDA / V2530 Post Open 270,000.00 252,600.00 Signed 2020-03-16 2020-05-26 2020-05-04 2021-02-18 2020-05-25 2021-02-18 2020-06-29 2021-03-03 2020-12-26 the Enabling Environment ant Selection ecialist (International) VU-MIPU-555016-CS-INDV / Component 3: Strengthening Individual Consult IDA / V2530 Post Open 50,000.00 0.00 Signed 2020-03-16 2021-06-01 2020-05-04 2022-09-01 2020-05-25 2022-09-02 2020-06-29 2020-12-26 Team Assistant (Local) the Enabling Environment ant Selection VU-MIPU-555013-CS-INDV / Component 3: Strengthening Individual Consult IDA / V2530 Post Open 95,000.00 139,200.00 Terminated 2020-03-16 2021-08-05 2020-05-04 2022-01-31 2020-05-25 2022-02-01 2020-06-29 2022-02-01 2020-12-26 Gender Specialist (Local) the Enabling Environment ant Selection VU-MIPU-555014-CS-INDV / Component 3: Strengthening Individual Consult IDA / V2530 Post Open 110,000.00 113,100.00 Signed 2020-03-16 2021-02-24 2020-05-04 2021-06-21 2020-05-25 2021-06-29 2020-06-29 2021-07-23 2020-12-26 Project Accountant (Local) the Enabling Environment ant Selection VU-MIPU-555012-CS-INDV / Component 3: Strengthening Individual Consult IDA / V2530 Post Open 165,000.00 164,640.00 Signed 2020-02-17 2021-04-12 2020-04-06 2022-01-11 2020-04-27 2022-01-31 2020-06-01 2022-02-01 2020-11-28 Social Safeguards Specialist ( the Enabling Environment ant Selection Local) VU-MIPU-555011-CS-INDV / Component 3: Strengthening Individual Consult Environmental Safeguards Sp IDA / V2530 Post Open 165,000.00 0.00 Signed 2020-03-16 2021-05-06 2020-05-04 2023-05-03 2020-05-25 2023-05-31 2020-06-29 2020-12-26 the Enabling Environment ant Selection ecialist (Local) VU-MIPU-555019-CS-INDV / F Component 3: Strengthening Individual Consult inancial Management Special IDA / V2530 Post Open 240,000.00 229,400.00 Signed 2020-03-16 2021-06-02 2020-05-04 2022-01-10 2020-05-25 2022-01-31 2020-06-29 2022-02-02 2020-12-26 the Enabling Environment ant Selection ist (International) VU-MIPU-91758-CS-INDV / In Component 3: Strengthening Individual Consult Pending Impleme IDA / 65310 Post Limited 30,000.00 0.00 2020-03-16 2020-03-21 2020-04-11 2020-08-04 2021-08-04 dependent Technical Review the Enabling Environment ant Selection ntation er VU-MIPU-5550251-CS-INDV / Component 3: Strengthening Individual Consult IDA / 65310 Prior Open 415,500.00 339,360.00 Signed 2020-06-09 2020-06-11 2020-07-28 2020-12-03 2020-08-18 2020-12-09 2020-09-22 2020-12-16 2021-03-21 Deputy Head PIU to support the Enabling Environment ant Selection Head PIU VU-MIPU-5550101-CS-INDV / Component 3: Strengthening Individual Consult IDA / V2530 Post Open 96,000.00 71,200.00 Signed 2020-06-09 2020-06-10 2020-07-28 2020-12-02 2020-08-18 2020-12-09 2020-09-22 2021-02-02 2021-03-21 National Procurement Special the Enabling Environment ant Selection ist VU-MIPU-5550171-CS-INDV / Component 3: Strengthening Individual Consult Road and Bridge Engineer/ H IDA / V2530 Prior Open 743,180.00 666,800.00 Signed 2020-06-09 2020-06-11 2020-07-28 2020-12-02 2020-08-18 2021-01-14 2020-09-22 2021-02-01 2021-03-21 the Enabling Environment ant Selection ead Project Support Team (P ST) VU-MIPU-275268-CS-INDV / Consultancy Services for Envi ronmental Safeguards Specia list (International) PHASE 1- Component 3: Strengthening Individual Consult Update of the Environmental IDA / V2530 Post Direct 25,000.00 28,900.00 Signed 2022-01-31 2022-01-28 2022-02-10 2022-03-22 2022-03-03 2022-03-22 2022-04-07 2022-03-23 2022-10-04 the Enabling Environment ant Selection and Social Impact Assessmen t (ESIA) and preparation of E nvironmental and Social Man agement Plans (ESMPs) for S outh Santo Road. VU-MIPU-275270-CS-INDV / Consultancy Services for Soci al Safeguards Specialist (Inte rnational) PHASE 1- Update o Component 3: Strengthening Individual Consult IDA / V2530 Post Direct 25,000.00 60,052.00 Signed 2022-01-31 2022-01-28 2022-02-10 2022-03-30 2022-03-03 2022-03-30 2022-04-07 2022-03-23 2022-10-04 f the Environmental and Soci the Enabling Environment ant Selection al Impact Assessment (ESIA) and preparation of Environm ental and Social Managemen t Plans (ESMPs) for South San to Road. VU-MIPU-280444-CS-INDV / Component 3: Strengthening Individual Consult Pending Impleme Consultancy Services for Roa IDA / V2530 Post Open 30,000.00 0.00 2022-02-22 2022-04-12 2022-05-03 2022-06-07 2022-12-04 the Enabling Environment ant Selection ntation d Safety Advisor Page 2 VU-MIPU-307142-CS-INDV / Consultancy Services for Sett Component 3: Strengthening Individual Consult IDA / V2530 Post Direct - National 10,000.00 0.00 Signed 2022-08-03 2022-08-16 2022-08-13 2023-01-06 2022-09-03 2023-02-08 2022-10-08 2023-04-06 ing up VCRTP Financial Mana the Enabling Environment ant Selection gement Systems in Smart Str eam System VU-MIPU-55501712-CS-INDV / Consulting Services for Roa Component 3: Strengthening Individual Consult Open - Internationa IDA / V2530 Prior 620,000.00 0.00 Canceled 2022-08-04 2023-03-07 2022-09-22 2022-10-13 2022-11-17 2023-05-16 d and Bridge Engineer/ Proje the Enabling Environment ant Selection l ct Support Team Coordinator (International)-2 VU-MIPU-316774-CS-INDV / Consulting Services for Proje Component 3: Strengthening Individual Consult Open - Internationa IDA / 65310 Prior 573,000.00 0.00 Signed 2022-09-20 2022-09-30 2022-11-08 2023-02-06 2022-11-29 2023-02-14 2023-01-03 2023-05-15 2023-07-02 ct Implementation Unit (PIU) the Enabling Environment ant Selection l Deputy Head (International)- 2 VU-MIPU-354420-CS-INDV / Consulting Services for Road Component 3: Strengthening Individual Consult Open - Internationa Under Implement IDA / V2530 Prior 389,950.00 0.00 2023-04-07 2023-04-04 2023-05-26 2023-06-16 2023-07-21 2024-01-17 and Bridge Engineer/ Project the Enabling Environment ant Selection l ation Support Team Coordinator (I nternational) VU-MIPU-364027-CS-INDV / Component 3: Strengthening Individual Consult Under Implement Consultancy Services for Soci IDA / V2530 Post Direct - National 24,950.00 0.00 2023-06-01 2023-06-01 2023-06-11 2023-07-02 2023-08-06 2024-02-02 the Enabling Environment ant Selection ation al Safeguards Specialist (Nati onal)- 2 Page 3 PROCUREMENT PLAN (Textual Part) Project information : Projet Régional de Renforcement des Systèmes de Surveillance des Maladies (REDISSE), PHASE III Niger, Crédit IDA 6230 NIR et Don 3150 (P161163) Project Implémentation agency : Ministère de la Santé Publique Date of the Procurement Plan: 14/11/2018 Period covered by this Procurement Plan: 2018-2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in décret 2016-641/PRN/PM du 1er décembre 2016 portant Code des Marchés Publics et des Délégations de Services Publics, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; 15% Works: is applicable for those contracts identified in the Procurement Plan tables. 7,5% PROCUREMENT Western and Central Africa : Regional Disease Surveillance Systems Enhancement (REDISSE) Phase III PLAN General Information Country: Western and Central Africa 2019-05-13 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161163 GPN Date: 2018-09-26 Project Name: Regional Disease Surveillance Systems Enhancement (REDISSE) Phase III Loan / Credit No: IDA / 62350 Regional Disease Surveillance Systems Enhancement Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ML-REDISSE 3 - MALI-11503 Component 1: Surveillance a Request for Quota Single Stage - One E Pending Imp 2020-02-2 5-CW-RFQ / Réalisation de for IDA / 62350 Post Open - National 130,000.00 0.00 2019-10-04 2019-12-01 nd Information Systems tions nvelope lementation 9 ages équipés à Diboli, Zégou a et Kouri ML-REDISSE 3 - MALI-11504 1-CW-RFQ / Fourniture et pos Component 1: Surveillance a Request for Quota Single Stage - One E Pending Imp 2020-03-0 IDA / 62350 Post Open - National 80,000.00 0.00 2019-10-10 2019-12-07 e de parcs métalliques et de nd Information Systems tions nvelope lementation 6 hangars à Diboli, Zégoua et Kouri ML-REDISSE 3 - MALI-18572 Component 5: Institutional C 2020-10-2 9-CW-DIR / Réhabilitation d'u IDA / 62350 apacity Building, Project Ma Post Direct Selection Direct 134,000.00 0.00 Canceled 2020-07-31 2020-08-05 2020-09-09 4 n bâtiment de l'INSP pour abr nagement, Coordination and iter l'UCP Advocacy Request for Bids - ML-REDISSE 3 - MALI-34006 Component 2: Strengthening Single Stage - One E Works (without pr Under Imple 2023-11-0 0-CW-RFB / Réhabilitation de IDA / 62350 Post Request for Bids Open - National 600,000.00 0.00 2023-03-10 2023-03-02 2023-03-31 2023-04-30 2023-05-15 2023-07-05 of Laboratory Capacity nvelope equalification) SP mentation 4 laboratoires de surveillance ( D LCV, INSP et LVG) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ML-REDISSE 3 - MALI-10244 Component 5: Institutional C 7-GO-RFB / 22 véhicules tout apacity Building, Project Ma Single Stage - One E Under Imple IDA / 62350 Post Request for Bids Open - National 924,000.00 0.00 2019-06-19 2019-06-27 2019-06-24 2019-07-24 2019-09-09 2019-08-08 2019-09-28 2019-11-27 terrain pour les échelons du nagement, Coordination and nvelope mentation système sanitaire-vétérinaire Advocacy et l'UCP ML-REDISSE 3 - MALI-10241 5-GO-DIR / 6 Ambulances mé Component 3: Preparedness Single Stage - One E IDA / 62350 Post Request for Bids Open - National 600,000.00 502,302.71 Completed 2019-06-25 2019-08-19 2019-06-30 2019-07-30 2019-09-24 2019-08-14 2019-09-27 2019-10-04 2020-04-12 2020-01-02 2021-01-08 dicalisées pour le transport s and Emergency Response nvelope écurisé des malades ML-REDISSE 3 - MALI-10244 Component 5: Institutional C 6-GO-RFB / 110 motos tout te apacity Building, Project Ma Single Stage - One E IDA / 62350 Post Request for Bids Open - National 550,000.00 304,930.03 Completed 2019-07-07 2019-06-26 2019-07-12 2019-08-16 2019-08-26 2019-08-31 2019-08-26 2019-10-21 2019-11-14 2020-01-04 2020-04-22 rrain pour les unités de surve nagement, Coordination and nvelope illance de la santé humaine e Advocacy t animale ML-REDISSE 3 - MALI-10244 8-GO-RFB / Fourniture et pos e de 4 incinérateurs moderne Component 2: Strengthening Single Stage - One E s avec accessoires pour le sy IDA / 62350 Post Request for Bids Open - National 170,000.00 170,721.66 Completed 2019-08-18 2019-10-14 2019-08-23 2019-09-22 2020-04-06 2019-10-07 2020-04-06 2019-11-27 2020-09-02 2020-02-25 2021-01-26 of Laboratory Capacity nvelope stème de gestion des déchet s biomédicaux (4 laboratoire s nationaux : INRSP, LCV, CN TS, CNAM) ML-REDISSE 3 - MALI-11486 Component 2: Strengthening Single Stage - One E IDA / 62350 Post Request for Bids Open - National 1,500,000.00 1,567,475.00 Completed 2019-07-01 2019-07-19 2019-07-06 2019-08-05 2019-09-19 2019-08-20 2019-09-23 2019-10-10 2020-05-27 2020-01-08 2021-03-19 2-GO-RFB / 2 laboratoires mo of Laboratory Capacity nvelope biles ML-REDISSE 3 - MALI-10215 8-GO-RFQ / Maldi-TOF pour la Component 2: Strengthening Request for Quota Single Stage - One E caractérisation des souches IDA / 62350 Post Open - National 100,000.00 334,747.83 Completed 2019-07-24 2019-09-19 2020-01-25 2019-12-18 2020-12-01 of Laboratory Capacity tions nvelope au centre de recherche et de contrôle de la résistance anti microbienne de l’INRSP ML-REDISSE 3 - MALI-11488 Component 5: Institutional C 1-GO-RFQ / Matériels informa apacity Building, Project Ma Single Stage - One E tiques pour les échelons des IDA / 62350 Post Request for Bids Open - National 400,000.00 249,949.95 Completed 2019-08-24 2020-09-24 2019-08-29 2019-09-30 2020-11-24 2019-10-30 2020-11-24 2019-12-04 2021-02-13 2020-02-02 2021-04-17 nagement, Coordination and nvelope systèmes (central, régional, Advocacy district, local) sanitaire (hum ain et animal) ML-REDISSE 3 - MALI-15652 8-GO-RFQ / Acquisition d'un v Component 2: Strengthening Request for Quota Single Stage - One E IDA / 62350 Post Open - National 75,000.00 66,641.81 Completed 2020-03-29 2020-05-18 2021-01-08 2020-08-16 2021-02-17 éhicule de traction pour le la of Laboratory Capacity tions nvelope boratoire mobile de la DNAC PN ML-REDISSE 3 - MALI-15953 3-GO-RFQ / F/P d'un groupe é Component 2: Strengthening Request for Quota Single Stage - One E IDA / 62350 Post Limited 41,000.00 25,464.56 Completed 2020-03-07 2020-06-24 2020-04-27 2020-07-29 2020-06-26 2020-08-12 lectrogène avec accessoires of Laboratory Capacity tions nvelope au Laboratoire vétérinaire de Kayes ML-REDISSE 3 - MALI-15953 5-GO-RFQ / F/P d'un transfor Component 2: Strengthening Request for Quota Single Stage - One E IDA / 62350 Post Limited 18,000.00 0.00 Canceled 2020-03-08 2020-04-09 2020-07-08 mateur électrique avec acces of Laboratory Capacity tions nvelope soires au laboratoire vétérina ire de Kayes ML-REDISSE 3 - MALI-11486 7-GO-RFQ / F & P d'un group Component 2: Strengthening Request for Quota Single Stage - One E e électrogène et d'un transfo IDA / 62350 Post Open - National 50,000.00 0.00 Canceled 2019-08-05 2019-10-02 2019-12-16 of Laboratory Capacity tions nvelope rmateur électrique au laborat oire régional vétérinaire de K ayes ML-REDISSE 3 - MALI-16209 Component 2: Strengthening Single Stage - One E 0-GO-RFB / Acquisition d’un IDA / 62350 Post Request for Bids Open - National 340,000.00 240,247.80 Completed 2020-04-06 2020-07-28 2020-04-11 2020-05-11 2020-10-13 2020-05-26 2020-10-14 2020-07-16 2020-12-05 2020-10-14 2021-02-05 of Laboratory Capacity nvelope Maldi-TOF Biotyper System e n faveur du LCV ML-REDISSE 3 - MALI-10244 Component 5: Institutional C Request for Quota Single Stage - One E 2-GO-RFQ / 10 pinasses équi IDA / 62350 apacity Building, Project Ma Post Limited 41,000.00 0.00 Canceled 2019-07-30 2019-09-11 2019-12-10 tions nvelope pées de moteurs nagement, Coordination and Advocacy Page 1 ML-REDISSE 3 - MALI-16697 Component 5: Institutional C 8-GO-RFQ / Acquisition d'éta apacity Building, Project Ma Request for Quota Single Stage - One E IDA / 62350 Post Limited 6,000.00 3,023.33 Completed 2020-09-12 2021-08-23 2020-10-17 2021-09-03 2020-12-01 2021-09-28 gères et de tables en bois art nagement, Coordination and tions nvelope isanales pour l'UCP Advocacy ML-REDISSE 3 - MALI-16884 3-GO-DIR / Acquisition 50 00 Component 3: Preparedness 0 flacons gel-hydro alcooliqu IDA / 62350 Post Direct Selection Direct 620,000.00 673,855.34 Completed 2020-04-21 2020-04-16 2020-04-26 2020-04-16 2020-05-31 2020-06-19 2020-06-21 2020-07-28 and Emergency Response e, 22 900 cartons de savon s olide et 211 950 bidons d'ea u de javel ML-REDISSE 3 - MALI-16891 Component 5: Institutional C 2-GO-DIR / F/P et mise en ser apacity Building, Project Ma IDA / 62350 Post Direct Selection Direct 32,000.00 43,312.55 Completed 2020-04-16 2020-04-16 2020-04-21 2020-04-18 2020-05-26 2020-05-09 2020-06-05 2020-05-22 vice de 3 kits de vidéo confér nagement, Coordination and ence (UCP REDISSE 3, DOU-S Advocacy P et INSP) ML-REDISSE 3 - MALI-16891 6-GO-DIR / Acquisition 100 tu Component 3: Preparedness IDA / 62350 Post Direct Selection Direct 6,500.00 7,577.37 Completed 2020-04-20 2020-04-16 2020-04-25 2020-04-20 2020-05-14 2020-05-01 2020-05-24 2020-05-14 bes (de 1 litre) de savon liqui and Emergency Response de et de 50 000 gants latex ML-REDISSE 3 - MALI-16892 5-GO-DIR / Acquisition de 34 00 Cathéter, 400 Paracetamo Component 3: Preparedness l inj1g, 400 Perfuseurs, 400 P IDA / 62350 Post Direct Selection Direct 9,000.00 3,678.60 Completed 2020-04-20 2020-04-16 2020-04-25 2020-04-22 2020-05-14 2020-05-29 2020-05-19 2020-09-01 and Emergency Response oche à urine 02, 400 Ringer L actate, 400 Sérum glucosé 5 %, 400 Sérum salé 0,9 % et 400 Solumédrol 40mg ML-REDISSE 3 - MALI-16893 0-GO-DIR / Acquisition de 10 Component 3: Preparedness IDA / 62350 Post Direct Selection Direct 680,000.00 462,015.00 Completed 2020-04-22 2020-04-16 2020-04-27 2020-04-20 2020-06-01 2020-06-19 2020-06-22 2020-07-03 000 kits d'équipements de pr and Emergency Response otection individuelle ML-REDISSE 3 - MALI-16895 Component 3: Preparedness 7-GO-DIR / Acquisition de 30 IDA / 62350 Post Direct Selection Direct 15,000.00 40,585.05 Completed 2020-04-22 2020-04-16 2020-04-27 2020-04-22 2020-05-18 2020-04-29 2020-06-01 2020-04-30 and Emergency Response 000 gants chirurgicaux ML-REDISSE 3 - MALI-16895 Component 3: Preparedness 8-GO-DIR / Acquisition de 36 IDA / 62350 Post Direct Selection Direct 10,000.00 9,302.85 Completed 2020-04-20 2020-04-16 2020-04-25 2020-04-20 2020-05-13 2020-04-29 2020-05-20 2020-05-08 and Emergency Response 0 Tests de diagnostique COVI D-19 ML-REDISSE 3 - MALI-16891 8-GO-DIR / Acquisition de cli Component 3: Preparedness matiseurs et de réfrigérateur IDA / 62350 Post Direct Selection Direct 90,000.00 70,429.08 Completed 2020-04-20 2020-04-16 2020-04-25 2020-04-20 2020-05-23 2020-06-19 2020-05-30 2020-07-07 and Emergency Response s pour le COVID, l'UCP et le S ecrétariat permanent de la pl ateforme ML-REDISSE 3 - MALI-16898 Component 5: Institutional C 0-GO-DIR / Acquisition de ma apacity Building, Project Ma tériels informatiques pour l'U IDA / 62350 Post Direct Selection Direct 61,000.00 0.00 Canceled 2020-04-20 2020-04-25 2020-05-30 2020-06-29 nagement, Coordination and CP et le secrétariat permane Advocacy nt de la plateforme one Heat h ML-REDISSE 3 - MALI-16895 6-GO-DIR / Acquisition de 30 Component 3: Preparedness IDA / 62350 Post Direct Selection Direct 150,000.00 161,564.40 Completed 2020-04-20 2020-04-17 2020-04-25 2020-04-20 2020-05-23 2020-06-19 2020-06-13 2020-06-27 00 Dispositifs de lavage des and Emergency Response mains de 100 litres ML-REDISSE 3 - MALI-16898 Component 5: Institutional C 1-GO-DIR / Acquisition de mo apacity Building, Project Ma biliers de bureau pour l'UCP IDA / 62350 Post Direct Selection Direct 27,000.00 32,825.17 Completed 2020-04-24 2020-04-16 2020-04-29 2020-06-08 2020-05-17 2020-07-09 2020-06-16 2020-07-16 nagement, Coordination and et le secrétariat permanent d Advocacy e la plateforme one Heath ML-REDISSE 3 - MALI-16893 1-GO-DIR / Acquisition de 17 Component 3: Preparedness IDA / 62350 Post Direct Selection Direct 90,000.00 96,529.74 Completed 2020-04-20 2020-04-16 2020-04-25 2020-04-20 2020-05-23 2020-06-23 2020-06-13 2020-07-02 84 Dispositifs de lavage des and Emergency Response mains de 100 litres ML-REDISSE 3 - MALI-16921 Component 3: Preparedness 9-GO-DIR / Acquisition de 10 IDA / 62350 Post Direct Selection Direct 50,000.00 739,224.00 Completed 2020-04-20 2020-04-16 2020-04-25 2020-04-20 2020-05-23 2020-06-19 2020-05-30 2020-07-17 and Emergency Response 000 Masques (N95 ou FFP2) ML-REDISSE 3 - MALI-10214 Component 5: Institutional C 1-GO-RFQ / Matériels informa apacity Building, Project Ma Request for Quota Single Stage - One E tiques et de communication IDA / 62350 Post Open - National 75,000.00 0.00 Canceled 2019-06-18 2019-08-14 2019-09-13 nagement, Coordination and tions nvelope pour l'UCP et le secrétariat p Advocacy ermanent de la plateforme o ne Heath ML-REDISSE 3 - MALI-10230 Component 5: Institutional C 0-GO-RFQ / Mobiliers et équi apacity Building, Project Ma Request for Quota Single Stage - One E pements de bureau pour l'UC IDA / 62350 Post Open - National 60,000.00 0.00 Canceled 2019-06-12 2019-08-08 2019-09-07 nagement, Coordination and tions nvelope P et le secrétariat permanent Advocacy de la plateforme one Heath ML-REDISSE 3 - MALI-16968 Component 5: Institutional C 0-GO-DIR / Matériels informat apacity Building, Project Ma iques et de communication p IDA / 62350 Post Direct Selection Direct 68,000.00 74,072.84 Completed 2020-04-21 2020-08-05 2020-04-26 2020-08-21 2020-05-31 2020-11-20 2020-06-30 2020-12-01 nagement, Coordination and our l'UCP et le secrétariat per Advocacy manent de la plateforme one Heath ML-REDISSE 3 - MALI-17004 6-GO-DIR / Acquisition de 20 Component 3: Preparedness IDA / 62350 Post Direct Selection Direct 830,000.00 1,715,585.40 Signed 2020-04-22 2020-04-22 2020-04-27 2020-04-18 2020-05-26 2020-06-23 2020-07-25 respirateurs (ventilateurs) et and Emergency Response de 20 moniteurs multifonctio ns ML-REDISSE 3 - MALI-17004 Component 3: Preparedness 7-GO-DIR / Acquisition de 31 IDA / 62350 Post Direct Selection Direct 26,000.00 31,925.13 Completed 2020-04-22 2020-04-22 2020-04-27 2020-05-14 2020-05-11 2020-05-28 2020-05-16 2020-05-28 and Emergency Response 2 Thermoflash ML-REDISSE 3 - MALI-17264 6-GO-UN / Acquisition d'équi pements, matériels et conso Component 3: Preparedness UN Agencies (Dire IDA / 62350 Prior Direct 3,500,000.00 0.00 Canceled 2020-05-11 2020-05-26 2020-05-16 2020-06-27 2021-06-27 mmables de protection et de and Emergency Response ct) prise en charge dans le cadre de la riposte au COVID 19 ML-REDISSE 3 - MALI-17803 6-GO-UN / Acquisition d'équi pements, matériels et conso Component 3: Preparedness UN Agencies (Dire IDA / 62350 Post Direct 3,500,000.00 3,497,259.00 Signed 2020-06-04 2020-05-06 2020-06-09 2020-05-02 2020-07-21 2020-06-26 2021-01-17 mmables de protection et de and Emergency Response ct) prise en charge dans le cadre de la riposte au COVID 19 Page 2 ML-REDISSE 3 - MALI-17803 9-GO-UN / Acquisition d'équi Component 2: Strengthening UN Agencies (Dire IDA / 62350 Post Direct 3,000,000.00 1,638,800.16 Signed 2020-06-04 2020-04-06 2020-06-09 2020-04-12 2020-07-21 2020-07-02 2021-07-21 pements, matériels, réactifs of Laboratory Capacity ct) et consommables de laborat oires ML-REDISSE 3 - MALI-18572 Component 5: Institutional C Request for Quota Single Stage - One E 7-GO-RFQ / Acquisition d'une IDA / 62350 apacity Building, Project Ma Post Limited 2,700.00 1,596.98 Completed 2020-08-15 2020-10-01 2020-09-05 2020-10-10 2020-09-15 2020-10-15 tions nvelope moto de liaison pour le coursi nagement, Coordination and er de l'UCP Advocacy ML-REDISSE 3 - MALI-18572 8-GO-RFQ / Acquisition et mis Component 3: Preparedness Request for Quota Single Stage - One E e en service d'équipements i IDA / 62350 Post Limited 38,000.00 42,149.69 Completed 2020-08-30 2020-12-03 2020-10-04 2021-01-23 2020-11-04 2021-02-24 and Emergency Response tions nvelope nformatiques et de logiciels pour le centre d'appels d'urg ence du Ministère de la Sant é ML-REDISSE 3 - MALI-18572 6-GO-DIR / Fourniture et pose de 08 caméras thermiques in Component 3: Preparedness IDA / 62350 Post Direct Selection Direct 341,000.00 346,847.60 Completed 2020-08-10 2020-07-23 2020-08-15 2020-08-11 2020-08-29 2020-09-08 2020-10-28 2020-11-12 frarouges avec accessoires a and Emergency Response ux aéroports de Bamako, Kay es, Mopti, Tombouctou et Ga o ML-REDISSE 3 - MALI-20894 4-GO-DIR / Acquisition de réa Component 2: Strengthening ctifs de sécurité transfusionn IDA / 62350 Post Direct Selection Direct 167,000.00 178,929.00 Completed 2020-12-16 2020-12-07 2020-12-21 2021-01-12 2021-01-28 2021-03-11 2021-02-11 2021-03-30 of Laboratory Capacity elle et de consommables de laboratoire en faveur du CNT S ML-REDISSE 3 - MALI-25134 7-GO-RFQ / Acquisition de m atériels-consommables-réacti Component 1: Surveillance a Request for Quota Single Stage - One E fs de labo en faveur du LCV p IDA / 62350 Post Limited 30,000.00 34,471.79 Signed 2021-10-31 2022-03-31 2021-11-28 2022-05-31 2021-12-29 nd Information Systems tions nvelope our la réalisation de l'étude s ur la cartographie des champ s maudits de fièvre charbonn euse au Mali ML-REDISSE 3 - MALI-25136 6-GO-RFQ / Acquisition de GP S de positionnement en fave Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 62350 Post Limited 1,000.00 777.33 Completed 2021-10-05 2022-06-06 2021-11-01 2022-06-15 2021-11-15 2022-06-17 ur du LCV pour la réalisation nd Information Systems tions nvelope de l’étude sur la cartographie des champs maudits de fièvr e charbonneuse au Mali ML-REDISSE 3 - MALI-25137 Component 5: Institutional C Request for Quota Single Stage - One E 2-GO-RFQ / Acquisition de cof IDA / 62350 apacity Building, Project Ma Post Limited 3,300.00 3,623.38 Completed 2021-10-02 2021-11-22 2021-10-29 2021-12-08 2021-11-12 2021-12-11 tions nvelope fres forts en faveur de l'UCP nagement, Coordination and Advocacy ML-REDISSE 3 - MALI-15654 Component 5: Institutional C 8-GO-RFB / Acquisition de 10 apacity Building, Project Ma Single Stage - One E IDA / 62350 Post Request for Bids Open - National 224,000.00 0.00 Canceled 2020-04-20 2020-10-20 2020-04-25 2020-05-25 2020-06-09 2020-07-30 2020-10-28 embarcations avec moteur h nagement, Coordination and nvelope ors-bord d'intervention rapid Advocacy e ML-REDISSE 3 - MALI-16089 Component 3: Preparedness Request for Quota Single Stage - One E 6-GO-RFQ / Acquisition de ra IDA / 62350 Post Open - National 94,000.00 0.00 Canceled 2020-03-29 2020-06-09 2020-08-23 and Emergency Response tions nvelope dios haute fréquence en fave ur du CNOU ML-REDISSE 3 - MALI-16089 9-GO-RFB / Acquisition d'une plateforme de nouvelle génér Component 2: Strengthening Single Stage - One E IDA / 62350 Post Request for Bids Open - National 470,000.00 0.00 Canceled 2020-04-15 2020-04-20 2020-05-20 2020-06-04 2020-07-16 2020-11-13 ation de séquençage (NGS) p of Laboratory Capacity nvelope our la surveillance moléculair e avancée en faveur de l'INS P ML-REDISSE 3 - MALI-11487 5-GO-RFB / Kits d'équipemen Component 3: Preparedness Request for Quota Single Stage - One E IDA / 62350 Post Open - National 100,000.00 0.00 Canceled 2019-08-11 2019-10-08 2019-12-22 ts de protection individuelle and Emergency Response tions nvelope pour agents aux 12 points d' entrées ML-REDISSE 3 - MALI-16564 1-GO-UN / Acquisition d'équi Component 2: Strengthening UN Agencies (Dire IDA / 62350 Prior Direct 3,000,000.00 0.00 Canceled 2020-04-01 2020-04-06 2020-05-18 2020-12-31 pements, matériels, réactifs of Laboratory Capacity ct) et consommables de laborat oires ML-REDISSE 3 - MALI-16089 5-GO-RFQ / Acquisition d'alco olimètre automatique à écra Component 2: Strengthening Request for Quota Single Stage - One E n LCD et d'appareil de déter IDA / 62350 Post Open - National 56,000.00 0.00 Canceled 2020-03-29 2020-06-09 2020-09-07 of Laboratory Capacity tions nvelope mination de l'azote et de prot eine pour l'analyse des alime nts, des eaux et des médica ments en faveur du LNS ML-REDISSE 3 - MALI-16089 7-GO-RFQ / Acquisition d'aut Component 2: Strengthening Request for Quota Single Stage - One E IDA / 62350 Post Open - National 56,000.00 0.00 Canceled 2020-04-05 2020-06-16 2020-09-14 omates de détection avec ac of Laboratory Capacity tions nvelope cessoires en faveur de l'OPV et de l'INSP ML-REDISSE 3 - MALI-10215 6-GO-RFB / Equipements chai Component 2: Strengthening Request for Quota Single Stage - One E nes de froid (ANSSA, CNTS et IDA / 62350 Post Open - National 100,000.00 0.00 Canceled 2019-08-17 2019-10-14 2019-12-13 of Laboratory Capacity tions nvelope INRSP : congélateurs, refrigér ateur, accumulateurs, therm os, ) ML-REDISSE 3 - MALI-29162 3-GO-RFB / Acquisition de réa Component 2: Strengthening Single Stage - One E Under Imple ctifs-consommables de labo IDA / 62350 Post Request for Bids Open - National 292,000.00 0.00 2022-06-06 2022-06-06 2022-06-11 2022-07-11 2022-10-20 2022-07-26 2022-10-20 2022-09-15 2022-11-15 of Laboratory Capacity nvelope mentation et d'EPI en faveur du LCV, de l'INSP et des sites sentinelles de surveillance de la RAM ML-REDISSE 3 - MALI-33006 1-GO-RFB / Acquisition d'équi Component 2: Strengthening Single Stage - One E Under Imple IDA / 62350 Post Request for Bids Open - National 350,000.00 0.00 2023-01-09 2023-01-09 2023-01-14 2023-02-13 2023-02-28 2023-04-20 2023-07-20 pements-réactifs-consomma of Laboratory Capacity nvelope mentation bles de labo et d'EPI en faveu r du LCV ML-REDISSE 3 - MALI-29162 1-GO-RFQ / F/P de 03 incinér Component 2: Strengthening Request for Quota Single Stage - One E IDA / 62350 Post Limited 20,000.00 0.00 Canceled 2022-05-28 2022-07-10 2022-09-09 ateurs type amélioré pour les of Laboratory Capacity tions nvelope CSREF de Koulikoro, Banamb a et Fana ML-REDISSE 3 - MALI-34004 5-GO-RFQ / Acquisition de kit Component 2: Strengthening Request for Quota Single Stage - One E Under Imple s d'analyse des propriétés ph IDA / 62350 Post Open - National 25,000.00 0.00 2023-02-21 2023-03-29 2023-05-17 of Laboratory Capacity tions nvelope mentation ysicochimiques de l'eau des i nstallations d'aquacultures e n faveur de la DNP Page 3 ML-REDISSE 3 - MALI-29162 8-GO-RFQ / Acquisition de 20 Component 2: Strengthening Request for Quota Single Stage - One E kits d'analyse des propriétés IDA / 62350 Post Limited 25,000.00 0.00 Canceled 2022-06-21 2022-08-03 2022-10-03 of Laboratory Capacity tions nvelope physicochimiques de l'eau de s installations d'aquacultures en faveur de la DNP ML-REDISSE 3 - MALI-34004 8-GO-RFB / Acquisition d'équi Component 2: Strengthening Single Stage - One E Under Imple IDA / 62350 Post Request for Bids Open - National 200,000.00 0.00 2023-03-20 2023-02-10 2023-03-25 2023-04-24 2023-05-09 2023-06-29 2023-09-28 pements et de consommable of Laboratory Capacity nvelope mentation s de labo en faveur de l'ANG ESEM ML-REDISSE 3 - MALI-34005 1-GO-RFQ / F/P de kits d'insta Component 1: Surveillance a Request for Quota Single Stage - One E Pending Impl IDA / 62350 Post Limited 25,000.00 0.00 2023-03-20 2023-04-26 2023-06-21 llations solaires au niveau de nd Information Systems tions nvelope ementation s laboratoires ANGESEM de B amako et Mopti ML-REDISSE 3 - MALI-34005 3-GO-RFB / Acquisition d'équi Component 2: Strengthening Single Stage - One E Pending Impl IDA / 62350 Post Request for Bids Open - National 160,000.00 0.00 2023-04-15 2023-04-20 2023-05-20 2023-06-04 2023-07-25 2023-10-17 pements-réactifs-consomma of Laboratory Capacity nvelope ementation bles de labo en faveur de l'O PV ML-REDISSE 3 - MALI-34005 4-GO-RFB / Acquisition d'extr Component 2: Strengthening Single Stage - One E Pending Impl IDA / 62350 Post Request for Bids Open - National 160,000.00 0.00 2023-03-31 2023-04-05 2023-05-05 2023-05-20 2023-07-10 2023-09-18 acteurs d'acide nucléique en of Laboratory Capacity nvelope ementation faveur des hôpitaux de Sikas so, Ségou et Mopti ML-REDISSE 3 - MALI-34006 5-GO-RFB / Acquisition d'équi pements-réactifs-consomma Component 2: Strengthening Single Stage - One E Pending Impl bles de labo en faveur du LN IDA / 62350 Post Request for Bids Open - National 380,000.00 0.00 2023-04-30 2023-05-05 2023-06-09 2023-06-24 2023-08-14 2023-10-23 of Laboratory Capacity nvelope ementation R, d'hôpitaux régionaux, de l aboratoires de districts sanit aires et de sites sentinelles d e surveillance de la RAM ML-REDISSE 3 - MALI-34006 7-GO-DIR / Acquisition de mé Component 3: Preparedness Under Imple IDA / 62350 Post Direct Selection Direct - National 76,000.00 0.00 2023-03-01 2023-02-01 2023-03-06 2023-02-27 2023-05-02 2023-07-01 dicaments pour la gestion de and Emergency Response mentation s épidémies en faveur de la DGSHP/DPM ML-REDISSE 3 - MALI-34444 0-GO-RFB / Acquisition d'équi Component 2: Strengthening Single Stage - One E Pending Impl pements pour la production d IDA / 62350 Post Request for Bids Open - National 121,000.00 0.00 2023-03-20 2023-04-04 2023-05-04 2023-06-03 2023-07-09 2023-10-07 of Laboratory Capacity nvelope ementation e produits sanguins labiles sé curisés en faveur du CNTS ML-REDISSE 3 - MALI-36406 6-GO-RFB / Acquisition d'équi Component 2: Strengthening Single Stage - One E Pending Impl IDA / 62350 Post Request for Bids Open - National 300,000.00 0.00 2023-07-17 2023-07-22 2023-08-21 2023-09-05 2023-10-26 2024-01-25 pements et de réactifs de lab of Laboratory Capacity nvelope ementation o en faveur du Laboratoire v étérinaire de Gao ML-REDISSE 3 - MALI-36406 Component 2: Strengthening Single Stage - One E Pending Impl 7-GO-RFB / Acquisition d'un L IDA / 62350 Prior Request for Bids Open - National 2,600,000.00 0.00 2023-06-18 2023-06-23 2023-07-23 2023-08-07 2023-10-06 2024-02-03 of Laboratory Capacity nvelope ementation yophilisateur en faveur du LC V ML-REDISSE 3 - MALI-36406 Component 2: Strengthening Single Stage - One E Pending Impl 8-GO-RFB / Acquisition d'un IDA / 62350 Post Request for Bids Open - National 420,000.00 0.00 2023-06-24 2023-06-29 2023-07-29 2023-08-13 2023-10-03 2023-12-12 of Laboratory Capacity nvelope ementation Groupe électrogène en faveu r du LCV ML-REDISSE 3 - MALI-36407 2-GO-RFQ / Acquisition d'un s erveur avec accessoires dans Component 1: Surveillance a Request for Quota Single Stage - One E Pending Impl IDA / 62350 Post Limited 12,000.00 0.00 2023-07-30 2023-08-31 2023-10-15 le cadre du Développement d nd Information Systems tions nvelope ementation e l'interopérabilité des systè mes de surveillance et de re porting NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ML-REDISSE 3 - MALI-11486 Component 5: Institutional C Request for Quota Single Stage - One E 5-NC-RFQ / Logiciel de gestio IDA / 62350 apacity Building, Project Ma Post Open - National 48,000.00 49,329.17 Completed 2019-07-18 2019-09-14 2020-05-12 2019-12-23 2020-06-19 tions nvelope n TOMPRO et formation des u nagement, Coordination and tilisateurs UCP Advocacy ML-REDISSE 3 - MALI-11488 Component 4: Human Resou 4-NC-RFQ / Acquisition et mis rce Management for Effectiv Request for Quota Single Stage - One E IDA / 62350 Post Limited 40,000.00 0.00 Canceled 2019-09-04 2019-10-25 2020-01-08 e en service de logiciels de g e Disease Surveillance and E tions nvelope estion du personnel et de co pidemic Preparedness urriers pour les DRH CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ML-REDISSE 3 - MALI-10239 4-CS-LCS / Etudes d'APD et C ontrôle/surveillance des trav Component 2: Strengthening Consultant Qualifi IDA / 62350 Post Open - National 100,000.00 24,903.43 Signed 2019-09-23 2021-08-13 2019-10-08 2019-11-07 2022-02-11 2019-12-07 2022-02-24 2020-01-11 2022-03-15 2020-07-09 aux de réhabilitation-rénovat of Laboratory Capacity cation Selection ion d'infrastructures de l'INR SP, du LCV et de deux encein tes réfrigérées ML-REDISSE 3 - MALI-10231 Component 5: Institutional C 5-CS-QCBS / Audit financier e apacity Building, Project Ma Consultant Qualifi IDA / 62350 Post Open - National 50,000.00 48,984.82 Signed 2019-05-15 2019-04-13 2019-06-05 2019-07-10 2019-11-22 2019-08-09 2020-01-14 2019-09-13 2020-04-22 2022-06-30 t comptable des exercices 20 nagement, Coordination and cation Selection 19-2020 et 2021 du Projet Advocacy ML-REDISSE 3 - MALI-10235 Component 4: Human Resou 6-CS-LCS / Elaboration manu rce Management for Effectiv Least Cost Selecti els de procédures administra IDA / 62350 Post Open - National 75,000.00 0.00 Canceled 2019-03-27 2019-04-11 2019-05-10 2019-06-07 2019-06-22 2019-07-21 2019-08-25 2019-11-23 e Disease Surveillance and E on tives des DRH Santé-Dévelop pidemic Preparedness pement rural-Environnement et formation ML-REDISSE 3 - MALI-11501 6-CS-CQS / Élaboration de la cartographie des risques sani Component 3: Preparedness Consultant Qualifi IDA / 62350 Post Open - National 60,000.00 0.00 Canceled 2019-09-17 2019-10-02 2019-10-31 2019-11-30 2020-01-04 2020-03-04 taires (THIRA) pour Il'identific and Emergency Response cation Selection ation et la priorisation des ris ques et dangers sur l'ensemb le du pays Page 4 ML-REDISSE 3 - MALI-10237 4-CS-CQS / Élaboration du pl Component 3: Preparedness Consultant Qualifi an multirisque basé sur THIR IDA / 62350 Post Open - National 30,000.00 0.00 Canceled 2019-09-11 2019-09-26 2019-10-25 2019-11-24 2019-12-29 2020-02-27 and Emergency Response cation Selection A national de préparation et de réponse aux urgences de santé publique ML-REDISSE 3 - MALI-29163 Component 5: Institutional C 4-CS-QCBS / Audit comptable apacity Building, Project Ma Quality And Cost- Under Implement IDA / 62350 Post Open - National 50,000.00 0.00 2022-07-04 2022-05-24 2022-07-19 2022-08-18 2022-09-15 2022-09-30 2022-11-05 2022-12-11 2024-09-30 et financier des exercices 20 nagement, Coordination and Based Selection ation 22, 2023, 2024 et de clôture Advocacy du Projet ML-REDISSE 3 - MALI-34006 3-CS-CQS / Services de consu ltants pour le contrôle de qua Component 2: Strengthening Consultant Qualifi Pending Impleme IDA / 62350 Post Open - National 17,000.00 0.00 2023-04-24 2023-05-09 2023-06-09 2023-07-09 2023-08-14 2023-11-12 lité externe des laboratoires of Laboratory Capacity cation Selection ntation nationaux et centraux, pour l es diagnostics de maladies à potentiel épidémiologique ML-REDISSE 3 - MALI-34443 0-CS-CQS / Contrôle et Survei Component 2: Strengthening Consultant Qualifi Pending Impleme IDA / 62350 Post Open - National 50,000.00 0.00 2023-03-20 2023-04-10 2023-05-09 2023-06-08 2023-07-13 2023-11-10 llance des Travaux de réhabil of Laboratory Capacity cation Selection ntation itation de labo de surveillanc e (LCV, INSP et LVG) ML-REDISSE 3 - MALI-36407 Component 1: Surveillance a Consultant Qualifi 1-CS-CQS / Elaboration des r IDA / 62350 Post Open - National 24,000.00 0.00 Under Review 2023-06-08 2023-04-06 2023-06-23 2023-07-22 2023-08-21 2023-09-26 2023-11-10 nd Information Systems cation Selection apports de NIES de 3 parcs d e quarantaine INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ML-REDISSE 3 - MALI-10239 Component 5: Institutional C Individual Consult 6-CS-INDV / Coordinateur des IDA / 62350 apacity Building, Project Ma Post Open 120,000.00 60,452.28 Signed 2018-12-03 2018-12-04 2019-01-17 2019-04-10 2019-02-07 2019-04-12 2019-03-07 2019-05-30 2021-03-06 ant Selection activités pour l’UGP nagement, Coordination and Advocacy ML-REDISSE 3 - MALI-10260 Component 5: Institutional C 4-CS-INDV / Fourniture d'assi apacity Building, Project Ma Individual Consult IDA / 62350 Post Direct 7,000.00 6,282.12 Completed 2018-11-16 2018-11-16 2018-11-23 2018-11-19 2018-11-28 2018-11-20 2018-12-10 2018-12-01 2019-03-03 2019-03-07 stance technique dans le cad nagement, Coordination and ant Selection re de la préparation du projet Advocacy APCSU ML-REDISSE 3 - MALI-10261 Component 5: Institutional C 2-CS-INDV / Appui à la mise e apacity Building, Project Ma Individual Consult n place d'un dispositif unique IDA / 62350 Post Direct 8,000.00 8,282.64 Completed 2018-11-30 2018-11-30 2018-12-08 2018-12-03 2018-12-13 2018-12-10 2018-12-27 2018-12-15 2019-01-17 2019-01-01 nagement, Coordination and ant Selection de gestion/coordination des Advocacy projets de santé à financeme nts d'origines multiples ML-REDISSE 3 - MALI-10245 Component 5: Institutional C Individual Consult 1-CS-INDV / Spécialiste en ge IDA / 62350 apacity Building, Project Ma Post Open 100,000.00 47,739.44 Completed 2018-12-06 2018-12-03 2019-03-06 2019-11-13 2019-04-05 2019-11-27 2019-05-17 2020-01-07 2021-05-16 2021-01-06 ant Selection stion financière pour l'UGP nagement, Coordination and Advocacy ML-REDISSE 3 - MALI-10240 Component 5: Institutional C Individual Consult 5-CS-INDV / Spécialiste en pa IDA / 62350 apacity Building, Project Ma Post Open 100,000.00 0.00 Canceled 2018-12-09 2019-04-08 2019-04-29 2019-06-03 2021-06-02 ant Selection ssation de marchés pour l'UG nagement, Coordination and P Advocacy ML-REDISSE 3 - MALI-10244 Component 5: Institutional C Individual Consult 3-CS-INDV / Spécialiste en su IDA / 62350 apacity Building, Project Ma Post Open 100,000.00 234,370.45 Terminated 2018-12-12 2018-12-03 2019-02-25 2019-04-10 2019-03-27 2019-04-12 2019-06-01 2019-06-04 2021-05-31 ant Selection ivi & évaluation pour l'UGP nagement, Coordination and Advocacy ML-REDISSE 3 - MALI-10240 Component 5: Institutional C Individual Consult 7-CS-INDV / Spécialiste en sa IDA / 62350 apacity Building, Project Ma Post Open 100,000.00 175,212.54 Signed 2019-01-02 2018-12-04 2019-03-18 2020-05-14 2019-04-17 2020-05-18 2019-06-07 2020-07-02 2021-06-06 ant Selection nté animale pour l'UGP nagement, Coordination and Advocacy ML-REDISSE 3 - MALI-10238 Component 5: Institutional C Individual Consult 3-CS-INDV / Chargé de comm IDA / 62350 apacity Building, Project Ma Post Open 100,000.00 150,388.93 Signed 2019-01-07 2018-12-04 2019-02-21 2019-01-16 2019-03-14 2019-01-25 2019-05-18 2019-06-18 2021-05-17 ant Selection unication pour l'UGP nagement, Coordination and Advocacy ML-REDISSE 3 - MALI-10243 Component 5: Institutional C Individual Consult 2-CS-INDV / Spécialiste en sa IDA / 62350 apacity Building, Project Ma Post Open 100,000.00 0.00 Canceled 2019-01-09 2018-12-04 2019-03-25 2019-04-15 2019-06-05 2021-06-04 ant Selection nté humaine pour l'UGP nagement, Coordination and Advocacy ML-REDISSE 3 - MALI-10240 Component 5: Institutional C Individual Consult 4-CS-INDV / Spécialiste en sa IDA / 62350 apacity Building, Project Ma Post Open 100,000.00 80,910.26 Signed 2019-01-23 2020-04-18 2019-04-08 2021-01-06 2019-04-29 2021-01-07 2019-06-19 2021-02-02 2021-06-18 ant Selection uvegarde environnementale nagement, Coordination and pour l'UGP Advocacy ML-REDISSE 3 - MALI-11504 Component 5: Institutional C Individual Consult 7-CS-INDV / Spécialiste en sa IDA / 62350 apacity Building, Project Ma Post Open 100,000.00 144,964.21 Signed 2019-07-01 2020-04-18 2019-09-14 2020-07-29 2019-10-05 2020-07-30 2019-11-25 2020-09-01 2021-11-24 ant Selection uvegarde sociale pour l'UGP nagement, Coordination and Advocacy ML-REDISSE 3 - MALI-16564 Component 5: Institutional C Individual Consult 2-CS-INDV / Spécialiste en sa IDA / 62350 apacity Building, Project Ma Post Direct 190,000.00 0.00 Canceled 2020-04-30 2020-05-10 2020-05-26 2020-06-30 2024-03-31 ant Selection nté humaine pour l'UCP nagement, Coordination and Advocacy ML-REDISSE 3 - MALI-16564 Component 5: Institutional C Individual Consult 3-CS-INDV / Spécialiste en pa IDA / 62350 apacity Building, Project Ma Post Direct 190,000.00 199,895.93 Signed 2020-04-30 2020-06-02 2020-05-10 2021-06-23 2020-05-26 2020-06-23 2020-06-30 2020-07-02 2024-03-31 ant Selection ssation de marchés pour l'UC nagement, Coordination and P Advocacy ML-REDISSE 3 - MALI-16564 Component 5: Institutional C Individual Consult 4-CS-INDV / Comptable pour l IDA / 62350 apacity Building, Project Ma Post Direct 113,000.00 106,982.78 Signed 2020-04-24 2020-05-29 2020-05-05 2020-06-23 2020-05-26 2020-06-23 2020-06-30 2020-07-02 2024-03-31 ant Selection 'UCP nagement, Coordination and Advocacy ML-REDISSE 3 - MALI-16564 Component 5: Institutional C Individual Consult 5-CS-INDV / Coordinateur du IDA / 62350 apacity Building, Project Ma Post Direct 235,000.00 241,503.71 Signed 2020-04-06 2020-05-05 2020-04-16 2020-05-26 2020-05-03 2020-05-26 2020-05-31 2020-06-02 2024-03-31 ant Selection projet nagement, Coordination and Advocacy ML-REDISSE 3 - MALI-16780 Component 5: Institutional C 9-CS-INDV / Élaboration du m apacity Building, Project Ma Individual Consult IDA / 62350 Post Direct 15,000.00 13,694.72 Completed 2020-04-06 2020-04-02 2020-04-16 2020-04-05 2020-04-26 2020-04-08 2020-05-17 2020-04-11 2020-06-16 2020-07-07 anuel d'exécution du Projet U nagement, Coordination and ant Selection rgence COVID 19 Advocacy ML-REDISSE 3 - MALI-16896 7-CS-INDV / Élaboration du c adre de gestion environneme Component 3: Preparedness Individual Consult IDA / 62350 Post Direct 100,000.00 38,709.12 Completed 2020-04-20 2020-04-07 2020-04-30 2020-04-21 2020-05-21 2020-05-15 2020-06-25 2020-06-16 2020-09-08 2020-09-24 ntale et sociale et du plan de and Emergency Response ant Selection gestion environnementale et sociale pour le Projet d'interv ention d'urgence COVID 19 M ali Page 5 ML-REDISSE 3 - MALI-16897 0-CS-INDV / Élaboration du pl an de formation du personnel Component 3: Preparedness Individual Consult IDA / 62350 Post Direct 35,000.00 13,904.06 Completed 2020-04-20 2020-04-07 2020-04-30 2020-04-21 2020-05-21 2020-04-23 2020-06-25 2020-04-29 2020-07-25 2020-07-08 employé dans des unités de and Emergency Response ant Selection prise en charge des malades pour le Projet d'intervention d'urgence COVID 19 Mali ML-REDISSE 3 - MALI-16897 2-CS-INDV / Élaboration du m anuel de procédures de gesti Component 3: Preparedness Individual Consult IDA / 62350 Post Direct 25,000.00 13,101.57 Completed 2020-04-20 2020-04-07 2020-04-30 2020-04-20 2020-05-10 2020-04-23 2020-05-31 2020-04-29 2020-06-30 2020-06-12 on de l'emploi et des conditio and Emergency Response ant Selection ns de travail pour le Projet d'i ntervention d'urgence COVID 19 Mali ML-REDISSE 3 - MALI-16897 4-CS-INDV / Élaboration du pl an de prévention et de contr Component 3: Preparedness Individual Consult IDA / 62350 Post Direct 34,000.00 13,773.22 Completed 2020-04-20 2020-04-07 2020-04-30 2020-04-21 2020-05-21 2020-04-29 2020-06-25 2020-05-01 2020-07-25 2020-11-06 ôle des infections et de gesti and Emergency Response ant Selection on des déchets issus des soin s de sante du Projet d'interve ntion d'urgence COVID 19 Ma li ML-REDISSE 3 - MALI-16897 5-CS-INDV / Actualisation du plan de mobilisation des part Component 3: Preparedness Individual Consult ies prenantes et élaboration IDA / 62350 Post Direct 50,000.00 26,124.64 Completed 2020-04-23 2020-04-07 2020-05-03 2020-04-21 2020-05-24 2020-04-23 2020-06-28 2020-04-29 2020-08-27 2020-06-11 and Emergency Response ant Selection du plan de communication su r les risques et participation communautaire du Projet d'i ntervention d'urgence COVID 19 Mali ML-REDISSE 3 - MALI-20894 Component 5: Institutional C 6-CS-INDV / Spécialiste en ge apacity Building, Project Ma Individual Consult IDA / 62350 Post Direct 163,000.00 161,591.54 Signed 2020-12-16 2018-11-15 2020-12-26 2021-01-04 2020-12-31 2021-01-04 2021-01-06 2021-01-07 2024-03-31 stion financière pour le Projet nagement, Coordination and ant Selection (renouvellement) Advocacy ML-REDISSE 3 - MALI-10243 Component 5: Institutional C Individual Consult 2-CS-INDV-2 / Spécialiste en IDA / 62350 apacity Building, Project Ma Post Open 160,000.00 92,154.87 Signed 2020-12-16 2021-02-26 2021-03-01 2021-06-17 2021-03-08 2021-07-12 2021-03-25 2021-10-02 2024-03-31 ant Selection santé humaine pour le Projet nagement, Coordination and Advocacy ML-REDISSE 3 - MALI-27204 Component 5: Institutional C Individual Consult 3-CS-INDV / Evaluation à mi- IDA / 62350 apacity Building, Project Ma Post Open 24,000.00 16,171.84 Signed 2022-01-17 2022-01-17 2022-02-14 2022-03-14 2022-02-17 2022-03-17 2022-02-23 2022-03-22 2022-03-31 ant Selection parcours du Projet nagement, Coordination and Advocacy ML-REDISSE 3 - MALI-11504 Component 5: Institutional C Individual Consult 2-CS-INDV / Assistant en pas IDA / 62350 apacity Building, Project Ma Post Limited 24,000.00 0.00 Canceled 2019-08-04 2019-08-09 2019-08-30 2019-10-01 2020-09-30 ant Selection sation de marchés pour l'UGP nagement, Coordination and Advocacy ML-REDISSE 3 - MALI-10215 Component 5: Institutional C Individual Consult 3-CS-INDV / Comptable pour l IDA / 62350 apacity Building, Project Ma Post Open 60,000.00 0.00 Canceled 2018-12-26 2018-12-04 2019-02-13 2019-03-06 2019-04-10 2021-04-09 ant Selection 'UGP nagement, Coordination and Advocacy ML-REDISSE 3 - MALI-16682 Component 5: Institutional C Individual Consult 3-CS-INDV / Spécialiste en su IDA / 62350 apacity Building, Project Ma Post Direct 190,000.00 0.00 Canceled 2020-05-04 2020-05-18 2020-05-14 2020-06-03 2020-06-30 2024-03-31 ant Selection ivi évaluation du projet nagement, Coordination and Advocacy ML-REDISSE 3 - MALI-29162 0-CS-INDV / Services de cons Component 1: Surveillance a Individual Consult Pending Impleme ultants pour élaborer les SOP IDA / 62350 Post Open 17,000.00 0.00 2022-07-06 2022-08-03 2022-08-06 2022-08-12 2022-09-12 nd Information Systems ant Selection ntation des agents des Points d'Entré e selon le concept One Healt h ML-REDISSE 3 - MALI-29163 1-CS-INDV / Service de consu Component 4: Human Resou ltant pour l'évaluation des di rce Management for Effectiv Individual Consult sparités entre les sexes dans IDA / 62350 Post Open 17,000.00 0.00 Under Review 2022-08-19 2023-05-24 2022-09-16 2022-09-19 2022-09-26 2022-11-26 e Disease Surveillance and E ant Selection les structures impliquées da pidemic Preparedness ns la préparation et les interv entions en cas d'urgence san itaire ML-REDISSE 3 - MALI-29162 4-CS-INDV / Services de cons Component 2: Strengthening Individual Consult Under Implement IDA / 62350 Post Open 17,000.00 0.00 2022-07-22 2022-07-22 2022-08-19 2022-08-22 2022-08-28 2022-09-28 ultant pour la révision du pro of Laboratory Capacity ant Selection ation fil national des produits chimi ques ML-REDISSE 3 - MALI-29162 5-CS-INDV / Service de consu ltants pour adapter et multipl Component 2: Strengthening Individual Consult Pending Impleme IDA / 62350 Post Open 32,000.00 0.00 2022-08-04 2022-09-01 2022-09-04 2022-09-28 2022-11-09 ier les outils d'inventaire des of Laboratory Capacity ant Selection ntation agents pathogènes, toxines o u autres substances dangere uses ML-REDISSE 3 - MALI-30996 Component 5: Institutional C Individual Consult 9-CS-INDV / Coordinateur du IDA / 62350 apacity Building, Project Ma Post Direct - National 97,000.00 0.00 Signed 2022-08-31 2022-08-17 2022-09-10 2022-09-06 2022-09-20 2022-09-06 2022-10-18 2024-03-31 ant Selection Projet nagement, Coordination and Advocacy ML-REDISSE 3 - MALI-33006 Component 5: Institutional C Individual Consult 0-CS-INDV / Spécialiste en su IDA / 62350 apacity Building, Project Ma Post Open - National 60,000.00 0.00 Canceled 2022-12-19 2023-01-10 2023-03-04 2023-03-19 2023-04-08 2024-03-31 ant Selection ivi & évaluation pour le Projet nagement, Coordination and Advocacy ML-REDISSE 3 - MALI-34006 6-CS-INDV / Service de consu ltant pour l'élaboration du pl Component 3: Preparedness Individual Consult IDA / 62350 Post Open - National 17,000.00 0.00 Under Review 2023-06-01 2023-05-11 2023-07-06 2023-07-09 2023-07-16 2023-09-14 an national de préparation et and Emergency Response ant Selection de réponse multirisque aux é vènements de santé publiqu e Page 6 Procurement Plan I. General 1. Project Information Country : Bhutan Borrower : Project Name : Food Security and Agriculture Productivity Project Loan Credit No. : P 1555513 2. Bank’s Approval Date of the Procurement Plan : October 20, 2016 In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. II. Goods, Works and Non consulting Services 1. Prior Review Threshold Method of Thresholds for Method Prior Review Procurement (USD equivalent) Threshold (USD) ICB (Goods) > 200,000 USD All contract above USD 100,000 RFB ( Goods) > USD 30,000 and up to USD 200,000 RFQ (Goods) Up to USD 30,000 ICB (Works) > 1.5 million All contract above RFB (Works) > 50,000 and up to USD USD 300,000 1.5 million RFQ (Works) Up to USD 50,000 ICB (Non- > 200,000 USD All contract above Consulting USD 100,000 Services) RFB (Non- < 200,000 USD Consulting Services) Direct Contracting No Threshold; meet paragraph 6.8, 6.9 and 6.10 of regulations Note: The Prior Review Thresholds will be reviewed during the implementation of the project and modified depending on the risk assessment and implementation of mitigation measures. In the case of contracts subject to prior review, before granting / agreeing to (a) a material extension of the stipulated time for performance of a contract; or (b) any substantial modification or waiver of the scope of services or other significant changes to the terms and conditions of such that the contract, including issuing; or (c) any change variation order or orders under such contract amendment (except in cases of extreme urgency) which would in aggregate, singly or combined with all variation orders or amendments previously issued, increase the original contract amount of the contract by more than 15% (fifteen percent); or (d) the proposed termination of the original price contract, the Borrower shall seek the Bank’s no objection to the proposed extension, modification, or change order. A copy of all amendments to the contract shall be furnished to the Bank for its record. 2. Prequalification Not Applicable 3. Reference to Project operational/Procurement Manual Standard Bidding Documents agreed between Project and Bank will be used for all works, consultancy and goods procurements. 4. Any Other Special Procurement Arrangements: National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. Requirements for national open competitive procurement include the following: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process.. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. II. Domestic Preference. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable The bid evaluation will be carried out as per agreed timeline in the Procurement Activity Schedule III. Selection of Consultant 1. Prior Review Threshold Method of Threshold (USD Prior Review Threshold Procurement Equivalent) (a) Quality and Cost No threshold All Contracts above USD Based Selection 70,000 for Firms; and (b) Quality Based No threshold above USD 50,000 for Selection Individuals (c) Selection Made No threshold Under a Fixed Budget (d) Least Cost Selection No threshold (e) Selection Based on < 100,000 Consultant’s Qualifications (f) Single Source As per Consultant Selection of firms Guidelines Para 3.9 (g) Selection of No threshold Individual Consultants Note: The Prior Review Thresholds will be reviewed during the implementation of the project and modified. In the case of contracts subject to prior review, before agreeing to: (a) an extension of the stipulated time for performance of a contract; (b) any substantial modification of the scope of services, substitutions of key experts, or other significant changes to the terms and conditions of the contract; or (c) the proposed termination of the contract, the Borrower shall seek the Bank’s no objection. A copy of all amendments to the contract shall be furnished to the Bank for its record. 2. Short List comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than USD 200,000 equivalent per contract, may comprise entirely of national consultants. PROCUREMENT Bhutan : Food Security and Agriculture Productivity Project PLAN General Information Country: Bhutan 2016-07-31 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P155513 GPN Date: 2017-11-30 Project Name: Food Security and Agriculture Productivity Project Loan / Credit No: / , TF / A4224, TF / B6044 Policy and Planning Division, Ministry of Agriculture and Forests Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CW6 / Birkulo-Somlachen Irri Component 1:Strengthening Request for Propo Single Stage - One E 2019-02-2 / Prior Open - National 130,000.00 0.00 Canceled 2017-01-31 2017-04-18 2017-04-18 2017-02-05 2017-06-27 2017-07-27 2017-08-31 gation Scheme, Dophuchen, Farmer and Producer Groups sals nvelope 2 Samtse CW5 / Support to NSC Bhur- Component 1:Strengthening Request for Quota Single Stage - One E 2017-09-2 / Post Open - National 15,000.00 0.00 Canceled 2017-02-05 2017-04-02 Cardamom (propagation hou Farmer and Producer Groups tions nvelope 9 se) CW2 / Taray Khola Irrigation Component 1:Strengthening Request for Propo Single Stage - One E 2019-02-2 / Prior Open - National 721,000.00 0.00 Canceled 2017-01-31 2017-04-18 2017-04-18 2017-02-05 2017-06-27 2017-07-27 2017-08-31 Scheme,Norbugang, Samtse Farmer and Producer Groups sals nvelope 2 BT-MOAF-37539-CW-RFB / C Component 2: Enhancing Fa Single Stage - One E 2018-09-1 onstruction of Taraykhola ch TF / A4224 Post Request for Bids Open - National 63,000.00 536,844.52 Completed 2017-11-27 2018-03-30 2017-12-02 2018-06-14 2018-01-13 2018-05-03 2018-02-12 2018-06-13 2018-03-19 2018-07-09 rmer Productivity nvelope 5 annel at Samtse BT-MOAF-48857-CW-RFB / C Component 2: Enhancing Fa Single Stage - One E 2019-01-2 onstruction of Laringkhola Irri TF / A4224 Post Request for Bids Open - National 692,000.00 655,642.35 Completed 2018-04-09 2018-03-30 2018-04-14 2018-06-14 2018-05-26 2018-05-03 2018-06-25 2018-06-13 2018-07-30 2018-07-09 rmer Productivity nvelope 6 gation Scheme at Sarpang CW1 / Ratey Khola Irrigation Component 2: Enhancing Fa Single Stage - One E 2018-12-2 TF / A4224 Post Request for Bids Open - National 540,000.00 468,478.19 Completed 2018-03-06 2018-03-22 2018-03-11 2018-06-14 2018-04-22 2018-04-25 2018-05-22 2018-06-01 2018-06-26 2018-07-09 Scheme, Sarpang rmer Productivity nvelope 3 BT-MOAF-59359-CW-RFB / C onstruction of Irrigation Sche Component 2: Enhancing Fa Single Stage - One E 2019-02-0 TF / A4224 Post Request for Bids Open - National 150,000.00 247,838.63 Completed 2018-04-16 2018-03-30 2018-04-21 2018-06-05 2018-06-02 2018-05-03 2018-07-02 2018-06-13 2018-08-06 2018-07-05 me at Birkhola under Dophuc rmer Productivity nvelope 2 hen Gewog, Samtse Dzongkh ag BT-MOAF-65700-CW-RFB / C Component 2: Enhancing Fa Request for Quota Single Stage - One E 2019-02-1 onstruction/Installation of Ca TF / A4224 Post Open - National 23,000.00 23,349.69 Completed 2018-06-27 2018-06-23 2018-08-22 2018-05-18 rmer Productivity tions nvelope 8 rdamom House at Samtenlin g, Sarpang BT-MOAF-77364-CW-RFQ / C onstruction of Water Harvesti ng Tank for Demonstration fo r demonstration. This plan is Component 2: Enhancing Fa Request for Quota Single Stage - One E 2019-05-2 TF / A4224 Post Open - National 3,500.00 3,078.90 Completed 2018-09-26 2018-11-21 2018-07-10 already approved (plan no.43 rmer Productivity tions nvelope 0 631) and this additional plan is submitted in order to upda te all the procurement activit ies in the STEP System BT-MOAF-99202-CW-RFQ / C onstruction of of water harv Component 2: Enhancing Fa Request for Quota Single Stage - One E 2019-10-2 TF / A4224 Post Limited 3,300.00 0.00 Canceled 2019-03-05 2019-04-30 esting tank for demonstratio rmer Productivity tions nvelope 7 n in Tendu Gewog under Sam tse Dzongkhag. BT-MOAF-93461-CW-RFB / C onstruction of Barbed Wire F Component 2: Enhancing Fa Request for Quota Single Stage - One E 2019-11-2 TF / A4224 Post Open - National 9,000.00 0.00 Canceled 2019-04-07 2019-06-02 encing and Steel Gate at San rmer Productivity tions nvelope 9 gbaykha, Haa Dzongkhag. BT-MOAF-104515-CW-RFQ / Construction of Road side Ma Component 3: Enhancing Ac Request for Quota Single Stage - One E 2019-11-2 rket Shed and Toilet at Delhe TF / A4224 Post Limited 9,200.00 6,228.45 Completed 2019-04-06 2019-04-26 2019-06-01 2019-05-14 cess to Markets tions nvelope 8 ling, Sangacholing Gewog un der Samtse Dzongkhag. BT-MOAF-104519-CW-RFQ / Component 2: Enhancing Fa Request for Quota Single Stage - One E 2019-11-2 Construction of Button Mushr TF / A4224 Post Open - National 15,500.00 17,733.74 Completed 2019-04-06 2019-06-01 2019-05-28 rmer Productivity tions nvelope 8 oom Shed under Chhukha Dz ongkhag. BT-MOAF-130539-CW-RFB / Component 3: Enhancing Ac Single Stage - One E 2020-10-2 Construction of Farmers outl TF / A4224 Post Request for Bids Open - National 40,300.00 26,727.83 Completed 2020-01-09 2020-01-06 2020-01-14 2020-02-25 2020-02-10 2020-03-26 2020-03-09 2020-04-30 2020-04-03 cess to Markets nvelope 7 et at Samtse Dzongkhag. BT-MOAF-130541-CW-RFQ / Construction of Marketing Str Component 3: Enhancing Ac Request for Quota Single Stage - One E 2020-08-2 TF / A4224 Post Open - National 12,000.00 13,477.59 Completed 2019-12-30 2020-02-24 2020-03-31 uctures at Dophuchen Gewo cess to Markets tions nvelope 2 g, Dorokha Drungkhag, Samt se Dzongkhag BT-MOAF-133413-CW-RFB / Component 3: Enhancing Ac Single Stage - One E 2020-09-2 Construction of Farmers outl TF / A4224 Post Request for Bids Open - National 82,000.00 62,077.09 Completed 2019-12-03 2019-08-23 2019-12-08 2020-01-19 2019-10-03 2020-02-18 2019-10-09 2020-03-24 2019-10-26 cess to Markets nvelope 0 et at Samar Gewog under H aa Dzongkhag. BT-MOAF-133608-CW-RFB / Component 3: Enhancing Ac Single Stage - One E 2020-09-2 Construction of Farmer outlet TF / A4224 Post Request for Bids Open - National 81,000.00 80,656.00 Completed 2019-12-03 2020-01-08 2019-12-08 2020-01-19 2020-02-10 2020-02-18 2020-03-16 2020-03-24 2020-07-02 cess to Markets nvelope 0 at Gedu under Chhukha Dzon gkhag. BT-MOAF-134027-CW-RFB / Construction of Farmers outl Component 3: Enhancing Ac Single Stage - One E 2020-10-1 TF / A4224 Post Request for Bids Open - National 46,686.00 34,794.08 Completed 2019-12-25 2020-02-28 2019-12-30 2020-02-10 2020-03-03 2020-03-11 2020-04-06 2020-04-15 2020-04-28 et at Dagapela under Goshi cess to Markets nvelope 2 Gewog, Dagana Dzomngkha g. BT-MOAF-134124-CW-RFB / Construction of farmer oulet Component 3: Enhancing Ac Single Stage - One E 2020-10-1 TF / A4224 Post Request for Bids Open - National 43,000.00 34,308.11 Completed 2019-12-30 2019-12-05 2020-01-04 2020-11-04 2020-02-15 2020-01-09 2020-03-16 2020-02-18 2020-04-20 2020-03-05 atJigmeling under Dekiling, S cess to Markets nvelope 7 arpang Dzongkhag BT-MOAF-141898-CW-RFB / Construction of distribution N etwork for Rateykhola Irrigati Component 2: Enhancing Fa Single Stage - One E 2020-10-1 on scheme under dekiling Ge TF / A4224 Post Request for Bids Open - National 240,891.00 143,623.06 Completed 2019-12-30 2019-12-26 2020-01-04 2020-02-15 2020-01-27 2020-03-16 2020-02-14 2020-04-20 2020-04-10 rmer Productivity nvelope 7 wog, Sarpang Dzongkhag to ensure equal and efficient dis tribution of water among the beneficiary farmers. Page 1 BT-MOAF-141902-CW-RFB / Construction of Distribution N etwork of Laringkhola Irrigati Component 2: Enhancing Fa Single Stage - One E 2020-10-1 on Scheme under Gadkiling TF / A4224 Post Request for Bids Open - National 94,000.00 90,336.07 Completed 2019-12-30 2019-12-26 2020-01-04 2020-02-15 2020-01-27 2020-03-16 2020-02-14 2020-04-20 2020-03-17 rmer Productivity nvelope 7 Gewog, Sarpang Dzongkhag to ensure equal and efficient water distribution among the beneficiary farmers. BT-MOAF-141905-CW-RFB / Construction of Distribution N etwork for Tharaykhola Irriga Component 2: Enhancing Fa Single Stage - One E 2020-10-1 tion scheme under Norbooga TF / A4224 Post Request for Bids Open - National 110,000.00 0.00 Canceled 2019-12-30 2019-12-26 2020-01-04 2020-02-15 2020-01-27 2020-03-16 2020-02-14 2020-04-20 rmer Productivity nvelope 7 ng Gewog, Samtse Dzongkha g to ensure equal and efficie nt distribution of water amon g the beneficiary farmers. BT-MOAF-142481-CW-RFB / Construction of Distribution N Component 2: Enhancing Fa Single Stage - One E 2020-11-0 TF / A4224 Post Request for Bids Open - National 37,000.00 58,003.29 Completed 2020-01-15 2019-12-26 2020-01-20 2020-03-02 2020-01-27 2020-04-01 2020-02-14 2020-05-06 2020-03-17 etwork for Birkhola Irrigation rmer Productivity nvelope 2 Scheme, at Dophuchen Gewo g. BT-MOAF-173655-CW-RFQ / Construction of Distribution N Component 2: Enhancing Fa Single Stage - One E 2021-03-2 etwork for Tharaykhola Irriga TF / A4224 Post Request for Bids Open - National 110,000.00 106,101.00 Completed 2020-06-05 2020-03-17 2020-06-10 2020-07-22 2020-03-31 2020-08-21 2020-06-11 2020-09-25 2020-05-27 rmer Productivity nvelope 4 tion Scheme, Norbugang Ge wog, Samtse Dzongkhag. BT-MOAF-188134-CW-RFB / Construction of Smart Irrigati Component 2: Enhancing Fa Request for Quota Single Stage - One E 2021-06-1 TF / A4224 Post Open - National 55,000.00 49,146.36 Completed 2020-10-20 2020-12-15 2020-03-17 on System for National Citrus rmer Productivity tions nvelope 3 Repository, ARDSC, Tsirang . National Procure BT-MOAF-230361-CW-RFB / ment Document - Construction of Cold Store an Component 3: Enhancing Ac Request for Quota Single Stage - One E 2022-04-1 TF / A4224 Post Open - National 2 Envelope proce 66,780.00 0.00 Canceled 2021-08-17 2021-10-12 d Packing House at Dagapela cess to Markets tions nvelope 0 ss (Non Bank-SPD , Dagana Dzongkhag. ) National Procure BT-MOAF-236738-CW-RFB / ment Document - Component 3: Enhancing Ac Single Stage - Two E 2023-11-0 Construction of Multi-Chamb TF / B6044 Prior Request for Bids Open - National 2 Envelope proce 601,042.00 0.00 Canceled 2022-11-30 2022-12-05 2023-01-16 2023-03-31 2023-05-05 cess to Markets nvelope 1 er Cold Store at Samtse Dzon ss (Non Bank-SPD gkhag. ) BT-MOAF-329318-CW-RFB / Construction of Centralized P Component 3: Enhancing Ac Single Stage - One E Other (with field f Under Imple 2023-10-2 ackhouse with office includin TF / B6044 Post Request for Bids Open - National 76,000.00 0.00 2023-01-31 2022-12-10 2023-02-05 2022-12-11 2023-03-12 2023-01-31 2023-04-01 2023-03-03 2023-04-30 cess to Markets nvelope or explanation) mentation 7 g site development and cons truction of water supply at Sa mtse Dzongkhag (Sl.No. 3.1. 1) BT-MOAF-329319-CW-RFB / Construction of Integrated Co Component 3: Enhancing Ac Single Stage - One E Other (with field f Under Imple 2024-02-1 TF / B6044 Post Request for Bids Open - National 250,000.00 0.00 2023-02-28 2023-03-21 2023-03-05 2023-03-21 2023-04-16 2023-05-16 2023-06-20 ld Storage at Samtse Dzong cess to Markets nvelope or explanation) mentation 5 khag (Sl.No. 3.1.1) BT-MOAF-329321-CW-RFB / Construction of Centralized P ackhouse with office includin Component 3: Enhancing Ac Single Stage - One E Other (with field f 2023-11-1 TF / B6044 Post Request for Bids Open - National 155,000.00 0.00 Signed 2023-01-31 2022-12-10 2023-02-05 2022-12-11 2023-03-19 2023-01-31 2023-04-18 2023-03-03 2023-05-23 g site development and dism cess to Markets nvelope or explanation) 9 antling of existing structure a t Dagana Dzongkhag (Sl.No. 3.1.1) BT-MOAF-329342-CW-RFB / Component 3: Enhancing Ac Single Stage - One E Other (with field f Under Imple 2024-02-1 Construction of Integrated Co TF / B6044 Post Request for Bids Open - National 188,000.00 0.00 2023-02-28 2023-03-21 2023-03-05 2023-03-21 2023-04-16 2023-05-16 2023-06-20 cess to Markets nvelope or explanation) mentation 5 ld Storage at Dagana Dzongk hag (Sl.No. 3.1.1) CW4 / Construction of Farm Component 1:Strengthening Request for Quota Single Stage - One E 2017-09-2 / Post Open - National 20,000.00 0.00 Canceled 2017-02-05 2017-04-02 Shop Farmer and Producer Groups tions nvelope 9 Component 1:Strengthening Request for Quota Single Stage - One E 2017-08-3 CW3 / Micro irrigation / Post Open - National 50,000.00 0.00 Canceled 2017-01-06 2017-03-03 Farmer and Producer Groups tions nvelope 0 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual G6 / Purchase of irrigation d Component 1:Strengthening esign software and surveying / Post Direct Selection Direct 20,000.00 0.00 Canceled 2017-01-31 2017-02-05 2017-03-12 2017-04-26 Farmer and Producer Groups equipments (Total Station & design Software) Component 4: Project Manag Single Stage - Two E G11 / Vehicle TF / A4224 Prior Request for Bids Open - National 150,000.00 0.00 Canceled 2017-01-31 2017-02-05 2017-03-19 2017-06-01 2017-07-06 2018-01-02 ement nvelope BT-MOAF-38468-GO-RFB / C omputers, Printers, Scanners, Component 4: Project Manag Single Stage - One E TF / A4224 Post Request for Bids Open - National 13,009.00 12,269.93 Completed 2017-11-30 2017-12-07 2017-12-05 2018-01-16 2018-06-25 2018-02-15 2018-06-29 2018-03-22 2018-04-24 2018-09-18 2018-12-26 Photocopy Machine, LCD Proj ement nvelope ector, Furniture's, and heater s and Radiators BT-MOAF-39796-GO-RFB / Pr Component 3: Enhancing Ac Single Stage - Two E ocurement of plastic crates, TF / A4224 Post Request for Bids Open - National 12,159.00 14,094.47 Completed 2017-12-15 2018-03-13 2017-12-20 2018-06-24 2018-01-31 2018-04-19 2018-04-15 2018-06-13 2018-05-20 2018-06-25 2018-11-16 2018-08-01 cess to Markets nvelope Digital Weighing Balance and packaging bags BT-MOAF-39904-GO-RFB / Pr Component 2: Enhancing Fa Single Stage - One E TF / A4224 Post Request for Bids Open - National 23,000.00 0.00 Canceled 2017-12-25 2017-12-30 2018-02-10 2018-03-12 2018-04-16 2018-10-13 ocurement of Hardware item rmer Productivity nvelope s BT-MOAF-41103-GO-RFB / Pr Component 4: Project Manag Single Stage - One E ocurement of Agriculture Too TF / A4224 Post Request for Bids Open - National 193,000.00 139,908.59 Completed 2018-01-01 2017-05-30 2018-01-06 2018-02-17 2017-07-27 2018-03-19 2017-08-25 2018-04-23 2017-06-14 2018-10-20 2018-06-25 ement nvelope ls and Equipments (Vegetabl es) BT-MOAF-39905-GO-RFB / Pr Component 2: Enhancing Fa Request for Quota Single Stage - One E ocurement of Construction m TF / A4224 Post Open - National 10,577.00 0.00 Canceled 2018-02-04 2018-04-01 2018-09-28 rmer Productivity tions nvelope aterials, Bajo ARDC BT-MOAF-42255-GO-RFQ / Pr Component 2: Enhancing Fa Request for Quota Single Stage - One E ocurement of Hardware item TF / A4224 Post Open - National 18,500.00 2,678.77 Completed 2018-02-04 2018-06-14 2018-04-01 2017-08-08 2018-09-28 2018-01-09 rmer Productivity tions nvelope s (ARDC, Samtenling) BT-MOAF-43627-GO-RFB / Pr Component 1:Strengthening Single Stage - One E ocurement of Vegetable seed TF / A4224 Post Request for Bids Open - National 7,000.00 2,227.50 Completed 2018-01-30 2017-05-30 2018-02-04 2018-03-18 2017-06-05 2018-04-17 2017-07-31 2018-05-22 2017-11-09 2018-11-18 2018-05-23 Farmer and Producer Groups nvelope s and Tools (Haa Dzongkhag) Page 2 BT-MOAF-43631-GO-RFB / Pr Component 1:Strengthening Single Stage - One E ocurement of Hardware Item TF / A4224 Post Request for Bids Open - National 12,000.00 9,781.32 Completed 2018-01-31 2017-06-05 2018-02-05 2018-03-19 2017-07-28 2018-04-18 2017-07-21 2018-05-23 2017-08-08 2018-11-19 2018-05-31 Farmer and Producer Groups nvelope s and Tools (Samtse Dzongkh ag) BT-MOAF-43634-GO-RFB / Pr Component 1:Strengthening Single Stage - One E ocurement of Agriculture Too TF / A4224 Post Request for Bids Open - National 25,500.00 9,061.87 Completed 2018-01-31 2017-05-24 2018-02-05 2018-03-19 2017-06-28 2018-04-18 2017-08-18 2018-05-23 2018-05-09 2018-11-19 2018-06-06 Farmer and Producer Groups nvelope ls and Hardware Items (Daga na Dzongkhag) BT-MOAF-43663-GO-RFB / Pr Component 1:Strengthening Single Stage - One E ocurement of Agriculture Too TF / A4224 Post Request for Bids Open - National 20,000.00 2,242.12 Completed 2018-03-28 2018-02-20 2018-04-02 2018-05-14 2018-03-23 2018-06-13 2018-03-30 2018-07-18 2018-05-14 2019-01-14 2018-06-29 Farmer and Producer Groups nvelope ls (AMC Paro) BT-MOAF-43629-GO-RFB / Pr Component 1:Strengthening Request for Quota Single Stage - One E ocurement of Vegetable seed TF / A4224 Post Limited 2,000.00 0.00 Canceled 2018-02-25 2017-05-30 2018-04-22 2018-10-19 Farmer and Producer Groups tions nvelope s and Tools (Chukha Dzongk hag) BT-MOAF-42997-GO-RFB / Pr Component 2: Enhancing Fa Request for Quota Single Stage - One E ocurement of Hardware Item TF / A4224 Post Limited 1,000.00 1,606.33 Completed 2018-03-03 2017-06-05 2018-04-28 2017-08-21 2018-10-25 2018-03-06 rmer Productivity tions nvelope s (Sarpang Dzongkhag) BT-MOAF-42257-GO-DIR / Di Component 2: Enhancing Fa rect Purchase of Manures (AR TF / A4224 Post Direct Selection Direct 230.00 0.00 Canceled 2018-01-30 2018-02-04 2018-03-11 2018-09-07 rmer Productivity DC, Samtenling) BT-MOAF-54803-GO-DIR / Pr Component 4: Project Manag Request for Quota Single Stage - One E ocurement of Laptops for PS TF / A4224 Post Limited 12,000.00 0.00 Canceled 2018-05-02 2018-05-02 2018-06-27 2018-12-24 ement tions nvelope C Members and PMU Officials BT-MOAF-52058-GO-DIR / Pr Component 2: Enhancing Fa TF / A4224 Post Direct Selection Direct 10,000.00 0.00 Canceled 2018-03-12 2018-03-17 2018-04-21 2018-10-18 ocurement of Irrigation Desig rmer Productivity n Software BT-MOAF-60199-GO-RFB / Pr ocurement of 5 Units of Dies Component 4: Project Manag Single Stage - One E TF / A4224 Post Request for Bids Open - National 181,888.54 182,628.70 Completed 2018-04-27 2018-05-02 2018-05-02 2018-06-22 2018-06-13 2018-05-04 2018-07-13 2018-06-07 2018-08-17 2018-08-30 2019-02-13 2018-09-05 el Hilux/ Pickup for the Projec ement nvelope t Management Unit, FSAPP. BT-MOAF-37859-GO-DIR / Ve Component 4: Project Manag TF / A4224 Post Direct Selection Direct 181,888.54 0.00 Canceled 2017-11-23 2017-11-28 2017-10-25 2018-01-02 2018-07-01 hicle ement BT-MOAF-40993-GO-RFQ / Pr Component 4: Project Manag Request for Quota Single Stage - One E ocurement of Office Funritur TF / A4224 Post Limited 6,000.00 0.00 Canceled 2018-01-13 2018-01-12 2018-03-10 2018-09-06 ement tions nvelope es and Equipments BT-MOAF-72352-GO-RFQ / Pr ocurement of office furniture' s for the newly established Pr Component 4: Project Manag Request for Quota Single Stage - One E oject Office. Manager Table ( TF / A4224 Post Limited 6,000.00 3,657.59 Completed 2018-08-07 2018-01-26 2018-10-02 2018-04-17 2019-03-31 2018-04-18 ement tions nvelope 12 nos), Bookshelf (5 nos), fil e rack (2 nos), revolving Chai r (9 nos), Guest Chair (12 nos ) and Steel Almirah (2 nos) BT-MOAF-72486-GO-RFB / Pr ocurement of 20 Direct Padd Component 2: Enhancing Fa Single Stage - One E TF / A4224 Post Request for Bids Open - National 2,500.00 2,201.59 Completed 2018-08-10 2018-02-01 2018-08-15 2018-09-26 2018-03-23 2018-10-26 2018-03-29 2018-11-30 2018-05-03 2019-05-29 2018-05-15 y seeders for ARDC, Paro and rmer Productivity nvelope farmers of the 5 Project Distri cts. BT-MOAF-72487-GO-RFB / Pr ocurement of 20 Brush cutter Component 2: Enhancing Fa Single Stage - One E TF / A4224 Post Request for Bids Open - National 8,000.00 7,090.11 Completed 2018-08-10 2018-02-01 2018-08-15 2018-09-26 2018-03-23 2018-10-26 2018-03-30 2018-11-30 2018-05-03 2019-05-29 2018-05-04 s for the farmers of the 5 dis rmer Productivity nvelope tricts of the Project. BT-MOAF-73758-GO-RFB / Pr ocurement of 20 Drip/Micro I Component 2: Enhancing Fa Single Stage - One E rrigation, and 35 sets of gree TF / A4224 Post Request for Bids Open - National 30,000.00 0.00 Canceled 2018-12-13 2018-12-18 2019-01-29 2019-02-28 2019-04-04 2019-10-01 rmer Productivity nvelope n house be issued to the 5 P roject Gewogs (Eusu, Samar, Gadkiling and Sombaykha). BT-MOAF-74417-GO-DIR / Pr ocurement of Cardamom Dry ers for Haa Dzongkhag to be Component 3: Enhancing Ac TF / A4224 Post Direct Selection Direct 5,500.00 3,095.44 Completed 2019-01-10 2019-02-19 2019-01-15 2019-04-18 2019-02-19 2019-04-20 2019-08-18 2019-04-23 further distributed to Project cess to Markets Gewogs to enhance the mark et accessibility of Cardamom. BT-MOAF-74497-GO-RFB / Pr ocurement of 55 Poly house plastic film, 55 poly house ny lon belt, 20- numbers of gree Component 2: Enhancing Fa Single Stage - One E TF / A4224 Post Request for Bids Open - National 17,500.00 13,806.23 Completed 2019-01-31 2018-11-19 2019-02-05 2019-03-19 2018-12-25 2019-04-18 2019-03-11 2019-05-23 2019-04-15 2019-11-19 2019-06-11 n net, 19 sets of drip irrigatio rmer Productivity nvelope n, 100 roll of plastic mulching , 10 numbers of syntax and 1 0 numbers of silpaulin sheet to be issued to the project G ewogs, Chhukha. BT-MOAF-74502-GO-RFB / Di rect procurement of 31 rolls of HDPE pipe from Bhutan Po Component 2: Enhancing Fa TF / A4224 Post Direct Selection Direct 2,000.00 0.00 Canceled 2018-12-14 2018-12-19 2019-01-23 2019-07-22 lythene as per the Directives rmer Productivity of the Ministry of Finance an d issue to the project Gewog s under Chhukha Dzongkhag. BT-MOAF-74504-GO-RFB / Pr ocurement of one set of Quin Component 2: Enhancing Fa Single Stage - One E TF / A4224 Post Request for Bids Open - National 8,000.00 0.00 Canceled 2018-12-20 2018-12-25 2019-02-05 2019-03-07 2019-04-11 2019-10-08 oa processing plant in one of rmer Productivity nvelope the Project Gewogs under Ch hukha Dzongkhag. BT-MOAF-75068-GO-RFB / Pr ocurement of three Stone Pic kers for AMC, Paro. (The proc Component 2: Enhancing Fa Single Stage - One E urement is already done bas TF / A4224 Post Request for Bids Open - National 15,500.00 14,482.86 Completed 2018-08-23 2018-02-20 2018-08-28 2018-10-09 2018-03-23 2018-11-08 2018-03-26 2018-12-13 2018-05-14 2019-06-11 2018-05-14 rmer Productivity nvelope ed on the approved procure ment plan vide ref. no. BT-M OAF-43663-GO-RFB, Procure ment of Agriculture Tools (A MC, Paro)) BT-MOAF-75069-GO-RFB / Pr ocurement of 20 Brush Cutte rs for AMC, Paro to be further distributed to Project District Component 2: Enhancing Fa Single Stage - One E TF / A4224 Post Request for Bids Open - National 8,000.00 2,194.56 Completed 2018-08-23 2018-02-01 2018-08-28 2018-10-09 2018-03-23 2018-11-08 2018-03-26 2018-12-13 2018-05-03 2019-06-11 2018-05-04 s. (The procurement is alread rmer Productivity nvelope y done based on the approve d procurement plan vide ref. no. BT-MOAF-43663-GO-RFB, Procurement of Agriculture T ools (AMC, Paro)) Page 3 BT-MOAF-77883-GO-RFB / Pr ocurement of Argiculture tool s and Equipments -32-sprinkl ers, 4- syntex (5000 litres), 5 Component 2: Enhancing Fa Single Stage - One E -rolls flexible pipes for irrigat TF / A4224 Post Request for Bids Open - National 21,000.00 27,431.33 Completed 2019-01-31 2018-11-19 2019-02-05 2019-03-19 2019-01-01 2019-04-18 2019-03-14 2019-05-23 2019-04-10 2019-11-19 2019-06-15 rmer Productivity nvelope ion, 100- numbers of green h ouse shed, 2-numbers of pref abricated poly house for Nor bugang & Sangacholing, Sam tse Dzongkhag. BT-MOAF-78285-GO-RFB / Pr ocurement of Electric Fencin Component 2: Enhancing Fa Single Stage - One E g materials to be issued to fa TF / A4224 Post Request for Bids Open - National 6,500.00 0.00 Canceled 2018-10-22 2018-08-16 2018-10-27 2018-12-08 2019-01-07 2019-02-11 2019-08-10 rmer Productivity nvelope rmers of Tendruk Gewog (4k m) and Tading Gewog (3km), Samtse Dzongkhag. BT-MOAF-78286-GO-DIR / Pr ocurement of 2010 pakcets o f vegetable seeds, 6500 kgs Component 2: Enhancing Fa of paddy seeds and 12000 kg TF / A4224 Post Direct Selection Direct 11,500.00 11,995.40 Completed 2019-01-31 2018-08-14 2019-02-05 2018-08-14 2019-03-12 2018-08-15 2019-09-08 2019-06-05 rmer Productivity s of seed potato to be issued to the farmers of various proj ect Gewogs under Sarpang D zongkhag. BT-MOAF-78287-GO-RFB / Pr ocurement of 87 numbers of plastic sheets (low cost), 50 numbers of secateurs, 50 nu Component 2: Enhancing Fa Single Stage - One E TF / A4224 Post Request for Bids Open - National 25,500.00 14,293.42 Completed 2019-01-01 2018-11-20 2019-01-06 2019-02-17 2018-12-25 2019-03-19 2019-01-07 2019-04-23 2019-04-17 2019-10-20 2020-06-30 mbers of pruning saw, 20 set rmer Productivity nvelope s of spraying suits, 56-drip se ts, 50-rolls of plastic Mulch to be issued to farmers under S arpang Dzongkhag. BT-MOAF-78288-GO-RFB / Pr ocurement of Electric Fencin Component 2: Enhancing Fa Single Stage - One E g materials for 10 km to be is TF / A4224 Post Request for Bids Open - National 4,500.00 0.00 Canceled 2019-01-03 2019-01-08 2019-02-19 2019-03-21 2019-04-25 2019-10-22 rmer Productivity nvelope sued to one of the project Ge wog under Sarpang Dzongkh ag. BT-MOAF-78294-GO-DIR / Pr ocurement of seeds from Nat ional Seed Centre (Chilli-40 p Component 2: Enhancing Fa TF / A4224 Post Direct Selection Direct 2,000.00 790.00 Completed 2019-01-30 2019-04-19 2019-02-04 2019-04-24 2019-03-11 2019-04-25 2019-09-07 2019-05-16 ackets, Tomato-25 packets, rmer Productivity Cucumber-25 packets and Q uiona-600 kgs) to be used in ARDC, Samtenling, Sarpang. BT-MOAF-78295-GO-RFB / Pr ocurement of general tools s uch as 6 rolls of flexible pipe, Component 2: Enhancing Fa Single Stage - One E 15 roll of plastic mulch, 11 ro TF / A4224 Post Request for Bids Open - National 3,500.00 15,962.28 Completed 2019-01-31 2018-11-16 2019-02-05 2019-03-19 2018-12-25 2019-04-18 2019-01-23 2019-05-23 2019-02-14 2019-11-19 2019-05-02 rmer Productivity nvelope lls of poly house plastic sheet and 11 rolls of pre-fabricated poly house to be used in ARD C, Samtenling, Sarpang. BT-MOAF-78296-GO-RFB / Pr ocurement of 1-unit Quiona Component 2: Enhancing Fa Single Stage - One E TF / A4224 Post Request for Bids Open - National 1,500.00 15,962.28 Completed 2019-01-31 2018-11-20 2019-02-05 2021-02-18 2019-03-19 2018-12-25 2019-04-18 2019-01-23 2019-05-23 2019-02-14 2019-11-19 2019-05-02 Dehusking Machine to be use rmer Productivity nvelope d in ARDC, Samtenling, Sarp ang. BT-MOAF-78297-GO-RFB / Pr ocurement of 1 unit-Farm Mi Component 2: Enhancing Fa Single Stage - One E TF / A4224 Post Request for Bids Open - National 2,500.00 0.00 Canceled 2019-01-31 2019-02-05 2019-03-19 2019-04-18 2019-05-23 2019-11-19 ni- Tiller for Drujaygang Gew rmer Productivity nvelope og on cost sharing basis. BT-MOAF-78298-GO-DIR / Pr ocurement of fertilizers to be Component 2: Enhancing Fa issued to Drujaygang gewog TF / A4224 Post Direct Selection Direct 3,000.00 2,050.26 Completed 2018-12-20 2018-06-07 2018-12-25 2018-06-08 2019-01-29 2018-06-13 2019-07-28 2018-06-20 rmer Productivity 110 bags and Kana Gewog 1 20 bags under Dagana Dzon gkhag. BT-MOAF-78299-GO-DIR / Pr ocurement of seeds from Nat ional Seed Centre to be issue d to Gewogs such as Karmali Component 2: Enhancing Fa TF / A4224 Post Direct Selection Direct 3,900.00 4,868.32 Completed 2018-12-12 2019-03-25 2018-12-17 2019-03-28 2019-01-21 2019-03-29 2019-07-20 2019-06-15 ng-1500 of citrus & 4000 car rmer Productivity damom, Drujaygang 2500 cit rus & 4000 cardamom, and K ana 2000 citrus & 4000 card amom under Dagana Dzongk hag. BT-MOAF-78300-GO-RFB / Pr ocurement of materials for C ardamom Dryer to be issued Component 2: Enhancing Fa Single Stage - One E TF / A4224 Post Request for Bids Open - National 14,000.00 15,429.97 Completed 2018-12-14 2019-02-02 2018-12-19 2019-01-30 2019-02-18 2019-03-01 2019-02-19 2019-04-05 2019-03-22 2019-10-02 2019-03-30 to various gewogs such as Ka rmer Productivity nvelope rmaling 8 sets, Drujaygang 1 0 sets and Kana 12 sets unde r Dagana Dzongkhag. BT-MOAF-80366-GO-RFB / Pr ocurement of protected Agric ulture Inputs ( 1kit) like Polyh ose Plastic film, Polyhouse ny Component 2: Enhancing Fa Single Stage - One E TF / A4224 Post Request for Bids Open - National 35,000.00 0.00 Canceled 2018-10-02 2018-10-07 2018-11-18 2018-12-18 2019-01-22 2019-07-21 lon belt, Prefabricated green rmer Productivity nvelope house, Green shade net, Anti Bird Net, Plastic Mulch, Veget able Transplanter and Knaps ack sprayer for winter vegeta ble program BT-MOAF-80367-GO-RFB / Pr ocurement of Water Use Effic ient Irrigation Inputs (1 kit) fo Component 2: Enhancing Fa Single Stage - One E TF / A4224 Post Request for Bids Open - National 46,000.00 33,718.24 Completed 2018-11-15 2018-09-26 2018-11-20 2019-01-01 2018-10-29 2019-01-31 2018-11-01 2019-03-07 2019-01-31 2019-09-03 2019-05-15 r Vegetable Production like Si rmer Productivity nvelope ntex, Flexible pipes, watering can, drip kits and silpaulin sh eets for winter vegetable. BT-MOAF-86039-GO-DIR / Pr ocurement of 117 bags of fer Component 2: Enhancing Fa TF / A4224 Post Direct Selection Direct 1,000.00 535.72 Completed 2018-12-28 2019-06-24 2019-01-02 2019-06-26 2019-02-06 2019-06-27 2019-08-05 2019-06-27 tilizers to be used in research rmer Productivity Centre, ARDC, Samtenling, S arpang BT-MOAF-86049-GO-DIR / Su pply and Installation of Hydro Component 2: Enhancing Fa TF / A4224 Post Direct Selection Direct 77,000.00 89,035.69 Completed 2018-11-23 2019-01-17 2018-11-28 2019-03-29 2019-01-02 2019-05-02 2019-07-01 2019-09-13 ponics in 3-ARDC's Yusipang, rmer Productivity Bajo and samtenling BT-MOAF-93460-GO-RFQ / Pr ocurement of one Vaccum Cl Component 4: Project Manag Request for Quota Single Stage - One E TF / A4224 Post Limited 1,500.00 0.00 Canceled 2019-01-16 2019-03-13 2019-09-09 eaner, Office Carpet and Five ement tions nvelope Fans for Project Management Unit (PMU) Page 4 BT-MOAF-95025-GO-RFQ / Pr ocurement of construction m aterials for composting syste Component 2: Enhancing Fa Request for Quota Single Stage - One E m for demonstration in 5 Proj TF / A4224 Post Limited 1,500.00 845.27 Completed 2019-03-05 2017-06-12 2019-04-30 2018-01-16 2019-10-27 2018-02-14 rmer Productivity tions nvelope ect Gewogs under Dagana D zongkhag (Karna, Drujeygan g, lhamoizingkha, karmaling and Nichula) BT-MOAF-95030-GO-RFQ / Pr ocurement of materials for Ci trus Potting-150 numbers rub Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / A4224 Post Open - National 1,900.00 928.63 Completed 2019-03-03 2019-04-28 2019-04-30 2019-10-25 2019-05-10 ber barrels, 2-table for chemi rmer Productivity tions nvelope cals and 5-chemical shelfs to used for citrus mother plants in ARDSC, Tsirang, Menchun a. BT-MOAF-98166-GO-RFQ / Pr ocurement of 1-Juicer and 1- Component 2: Enhancing Fa Request for Quota Single Stage - One E Pulper to be used as training TF / A4224 Post Limited 770.00 0.00 Canceled 2019-02-13 2019-04-10 2019-10-07 rmer Productivity tions nvelope material. the Training to b pr ovided by ARDC, Yusipang. BT-MOAF-78301-GO-DIR / Pr ocurement of HDPE pipe for micro Irrigation for three Ge Component 2: Enhancing Fa TF / A4224 Post Direct Selection Direct 45,000.00 5,078.62 Completed 2019-02-12 2020-04-02 2019-02-17 2020-05-01 2019-03-24 2020-05-26 2019-09-20 2020-06-13 wogs viz. Karmaling $12400, rmer Productivity Drujaygang $620 and Kana G ewog $ 33000 under Dagana Dzongkhag. BT-MOAF-99113-GO-DIR / Pr Component 2: Enhancing Fa ocurement of HDPE Pipes an TF / A4224 Post Direct Selection Direct 140.00 7,258.01 Completed 2019-03-05 2018-02-28 2019-03-10 2018-03-02 2019-04-14 2018-04-24 2019-10-11 2018-04-24 rmer Productivity d Flanges directly from Bhuta n Polythene. BT-MOAF-99117-GO-RFQ / Pr ocurement of Cardamom dry Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / A4224 Post Limited 3,500.00 1,446.86 Completed 2019-04-02 2018-05-28 2019-05-28 2018-06-11 2019-11-24 2018-06-30 er for Chhukha Dzongkhag to rmer Productivity tions nvelope be issued to one of the Proje ct Gewog. BT-MOAF-99185-GO-RFB / pr ocurement of 400 hand glove s, 10 knapsack sprayer, 50-p Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / A4224 Post Limited 2,400.00 431.80 Completed 2019-03-03 2018-04-18 2019-04-28 2018-05-07 2019-10-25 2018-05-07 runing loper, 200-pee cap an rmer Productivity tions nvelope d 18- leather tool kits to be is sued to project Gewogs unde r Dagana Dzongkhag. BT-MOAF-99186-GO-RFB / Pr ocurement of 50- secateurs a Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / A4224 Post Limited 3,500.00 3,345.95 Completed 2019-03-05 2017-10-30 2019-04-30 2018-04-27 2019-10-27 2018-06-20 nd 50-pruning saw to be iss rmer Productivity tions nvelope ued to project Gewogs under Dagana Dzongkhag. BT-MOAF-99189-GO-DIR / Pr ocurment of 20 bottles-Chlor opyrifos (to control citrus frui Component 2: Enhancing Fa TF / A4224 Post Direct Selection Direct 140.00 130.67 Completed 2019-02-22 2018-02-12 2019-02-27 2018-01-10 2019-04-03 2018-01-11 2019-09-30 2018-04-16 t drop) and 10- Sandovit (stic rmer Productivity ker) (To control citrus fruit dr op) to be issued to project G ewogs under Danaga Dzongk hag. BT-MOAF-99191-GO-DIR / Pr ocurement of 2303 packets o Component 2: Enhancing Fa f high quality vegetable seed TF / A4224 Post Direct Selection Direct 7,000.00 5,404.28 Completed 2019-02-26 2018-09-05 2019-03-03 2018-11-01 2019-04-07 2018-01-11 2019-10-04 2018-06-22 rmer Productivity s and fertilizers to be issued t o the project Gewogs under Dagana Dzongkhag. BT-MOAF-99194-GO-DIR / Pr ocurement of construction m Component 2: Enhancing Fa aterials like cement and brick TF / A4224 Post Direct Selection Direct 960.00 445.34 Completed 2019-02-21 2017-12-01 2019-02-26 2018-01-03 2019-04-02 2018-01-15 2019-09-29 2018-05-25 rmer Productivity s for vermi composting for pr oject Gewogs under Dagana Dzongkhag. BT-MOAF-95040-GO-RFB / Pr ocurement of materials for e xpansion of azolla production . 25 numbers-Silpaulin sheet Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / A4224 Post Open - National 1,500.00 3,934.35 Completed 2019-03-25 2019-05-20 2018-05-09 2019-11-16 2018-05-10 s and 50 kg- azolla seeds to rmer Productivity tions nvelope used in Project Gewogs (Karn a, Drujeygang, Lhamoizingkh a, Karmaling and Nicgula und er Dagana Dzongkhag. BT-MOAF-95032-GO-RFB / Pr ocurement of materials for el ectric fencing (1km) such as Component 2: Enhancing Fa Request for Quota Single Stage - One E 450-HDPE Poles, 100kg-GI Wi TF / A4224 Post Open - National 5,000.00 0.00 Canceled 2019-03-30 2019-05-25 2019-11-21 rmer Productivity tions nvelope re, 1 set Energizer, 1- energi zer box, 5 -Tarpari tool set et c. To be used in Karna Gewo g under Dagana Dzongkhag. BT-MOAF-95028-GO-RFB / Pr ocurement of martials for wa ter harvesting system 100- si Component 2: Enhancing Fa Request for Quota Single Stage - One E lpaulin sheets for Project Ge TF / A4224 Post Open - National 2,100.00 2,161.28 Completed 2019-04-03 2019-05-29 2018-10-16 2019-11-25 2018-11-08 rmer Productivity tions nvelope wogs such as Karna, Drujecy gang, Lhamoizingkha, karmal ing and Nichula under Dagan a Dzongkhag. BT-MOAF-99115-GO-RFB / Pr ocurement Agriculture Tools/I Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / A4224 Post Open - National 2,950.00 16,800.49 Completed 2019-03-18 2019-05-13 2019-02-13 2019-11-09 2019-05-01 mplements and Equipments f rmer Productivity tions nvelope or ARDC, Samteling. BT-MOAF-99187-GO-RFB / Pr ocurement of 28-safety suits , 2-power chain, black plastic Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / A4224 Post Open - National 1,600.00 1,278.40 Completed 2019-03-31 2019-05-26 2018-05-25 2019-11-22 2018-06-19 bags and plastic grafting tap rmer Productivity tions nvelope e to be issued to project Gew ogs under Dagana Dzongkha g. BT-MOAF-99188-GO-RFB / Pr ocurement of 100 kg-lime for citrus management, CJI Shee Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / A4224 Post Open - National 1,000.00 1,598.79 Completed 2019-04-01 2019-05-27 2018-05-21 2019-11-23 2018-06-19 ts (Vermi Composting), Nails rmer Productivity tions nvelope and wire mesh to be issued t o project Gewogs under Dag ana Dzongkhag. BT-MOAF-99068-GO-RFB / Pr ocurement of Flexible pipes, j Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / A4224 Post Open - National 1,000.00 778.74 Completed 2019-04-07 2019-06-02 2017-08-07 2019-11-29 2018-06-24 ute bag, plastic bags & Agros rmer Productivity tions nvelope hading net for ARDC, Yusipan g. Page 5 BT-MOAF-99098-GO-RFB / Pr Component 2: Enhancing Fa Request for Quota Single Stage - One E ocurement of Pickaxe (5kg), TF / A4224 Post Open - National 3,000.00 3,947.81 Completed 2019-04-03 2019-05-29 2018-06-12 2019-11-25 2018-06-29 rmer Productivity tions nvelope Top Pruner and Poly house. BT-MOAF-99108-GO-RFB / Pr Component 2: Enhancing Fa Request for Quota Single Stage - One E ocurement of Flexible pipes a TF / A4224 Post Open - National 1,000.00 65.06 Completed 2019-04-03 2019-05-29 2017-08-29 2019-11-25 2017-12-19 rmer Productivity tions nvelope nd Silpaulin sheets. BT-MOAF-99179-GO-RFB / Pr ocurement of low cost poly h Component 2: Enhancing Fa Request for Quota Single Stage - One E ouse for winter vegetable to i TF / A4224 Post Open - National 3,000.00 8,401.91 Completed 2019-03-25 2019-05-20 2018-01-15 2019-11-16 2018-06-29 rmer Productivity tions nvelope ssued to project Gewogs und er Chhukha Dzongkhag. BT-MOAF-99180-GO-RFB / Pr ocurement of 150-Plastic Cra Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / A4224 Post Open - National 2,800.00 2,077.34 Completed 2019-04-02 2019-05-28 2018-06-25 2019-11-24 2018-06-29 tes to be issued to Project Ge rmer Productivity tions nvelope wogs under Chhukha Dzongk hag BT-MOAF-99193-GO-RFB / Pr ocurement of Copper Sulphat Component 2: Enhancing Fa Request for Quota Single Stage - One E e (for citrus canopy manage TF / A4224 Post Open - National 1,800.00 0.00 Canceled 2019-03-27 2019-05-22 2019-11-18 rmer Productivity tions nvelope ment) to be issued to the pro ject Gewogs under Dagana D zongkhag. BT-MOAF-99092-GO-RFB / Pr Component 2: Enhancing Fa Request for Quota Single Stage - One E ocurement of Pruning saw an TF / A4224 Post Open - National 100.00 3,814.39 Completed 2019-04-03 2019-05-29 2017-11-18 2019-11-25 2018-01-01 rmer Productivity tions nvelope d Secateurs for citrus progra m. BT-MOAF-99083-GO-RFB / Pr ocurement of Knapsack spra Component 2: Enhancing Fa Request for Quota Single Stage - One E yer, Brush cutter, Sceatuer, TF / A4224 Post Open - National 9,000.00 14,361.66 Completed 2019-04-01 2019-05-27 2017-04-17 2019-11-23 2018-08-23 rmer Productivity tions nvelope Gafting knife, budding knife, screen house and poly house . BT-MOAF-99195-GO-RFB / Pr ocurement of 100-Goggles U Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / A4224 Post Open - National 160.00 151.47 Completed 2019-04-01 2019-05-27 2018-04-02 2019-11-23 2018-06-28 D 46 to be issued to the proj rmer Productivity tions nvelope ect Gewogs under Dagana D zongkhag. BT-MOAF-104516-GO-RFQ / Procurement of 8-mid end La ptops and 2-Desktops to be i ssued to Officials of Departm Component 3: Enhancing Ac Request for Quota Single Stage - One E TF / A4224 Post Open - National 12,400.00 13,148.70 Completed 2019-03-31 2019-05-26 2019-06-13 2019-11-22 2019-08-22 ent of Agricultural Marketing cess to Markets tions nvelope and Cooperatives (DAMC) an d Regional Agricultural Marke ting and Cooperative Office G elephu, under Sarpang Dzon gkhag. BT-MOAF-104518-GO-RFQ / Procurement of one set of Po Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / A4224 Post Limited 1,500.00 0.00 Canceled 2019-04-03 2019-05-29 2019-11-25 tato Fryer to be issued to Bo rmer Productivity tions nvelope ngo Gewog under Chhukha D zongkhag. BT-MOAF-114390-GO-DIR / P rocurement of vegetable see ds Cabbage 64-packets, cauli flower 64-packets, Broccoli 5 Component 2: Enhancing Fa TF / A4224 Post Direct Selection Direct 620.00 4,613.60 Completed 2019-05-30 2018-10-02 2019-06-04 2018-10-03 2019-07-09 2018-10-04 2020-01-05 2018-11-06 9-packets, carrot 64-packets rmer Productivity and lettuce 67-packets to be issued to Bongo, Getena, Sa mphepling, Dungna and Mete kha under Chhukha Dzongkh ang. BT-MOAF-129204-GO-RFQ / Procurement of Agriculture t ools and Equipments- 6 nos- Budding knife, 6 nos-Secateu Component 1:Strengthening Request for Quota Single Stage - One E TF / A4224 Post Open - National 3,300.00 1,980.47 Completed 2020-01-05 2020-03-01 2019-10-23 2020-08-28 2019-12-05 rs, 5 kg-candle wax, 20 nos-g Farmer and Producer Groups tions nvelope rafting tape, 10 roll- cellopha ne grafting tape, 100 nos- wh ite clothes bags, 5 nos-PVC- Tarpaulin and 2 sets- poly ho use. BT-MOAF-130536-GO-RFB / Procurement of 2 nos-Prefabr icated Poly house, 2 nos- Ven tilation & net accessories 10 Component 2: Enhancing Fa Single Stage - One E TF / A4224 Post Request for Bids Open - National 24,000.00 24,047.54 Completed 2019-12-23 2019-11-04 2019-12-28 2020-02-08 2019-12-19 2020-03-09 2020-03-02 2020-04-13 2020-03-21 2020-10-10 2020-05-16 0 nos-Low cost poly/Green h rmer Productivity nvelope ouse with plastic film, 100 no s-Nylon belt for poly house, 1 00 nos-Green Shed Net, 10 n os-Nursery tray and 100 no s-Seedling tray. BT-MOAF-130537-GO-DIR / P rocurement of 30 nos- Sintex tanks (1000ltr & 2000 ltrs) a Component 2: Enhancing Fa TF / A4224 Post Direct Selection Direct 7,400.00 0.00 Canceled 2019-11-20 2019-11-25 2019-12-30 2020-06-27 nd 30 roll of HDPE pipes to b rmer Productivity e issued to the project Gewo gs under Samtse Dzongkhag. BT-MOAF-130538-GO-RFQ / Procurement of materials for Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / A4224 Post Open - National 4,500.00 1,433.17 Completed 2020-01-21 2020-03-17 2020-03-21 2020-09-13 2020-05-12 installation of cardamom dry rmer Productivity tions nvelope er at Samtse Dzongkhag. BT-MOAF-133408-GO-RFB / Procurement of Agriculture In puts, Tools and Equipments ( Component 2: Enhancing Fa Single Stage - One E 38-Gator sparyer, 11-Knapsa TF / A4224 Post Request for Bids Open - National 12,500.00 19,537.01 Completed 2019-12-11 2020-04-30 2019-12-16 2020-01-27 2020-06-01 2020-02-26 2020-06-02 2020-04-01 2020-06-05 2020-09-28 2020-06-12 rmer Productivity nvelope ck Sprsyer, 20-Hand tools, 45 - Flexible pipes, 65-Sprinklers , 2- drip irrigation, 60-low co st ploy house, 20 kg-Wax Ro xin) BT-MOAF-133409-GO-RFQ / Procurement of Agriculture In Component 2: Enhancing Fa Request for Quota Single Stage - One E puts, Tools and Equipments TF / A4224 Post Open - National 10,500.00 0.00 Canceled 2019-12-24 2020-02-18 2020-08-16 rmer Productivity tions nvelope 7 nos- prefabricated polyhou se and 18 nos-hedge cutter. BT-MOAF-133414-GO-RFQ / Procurement of construction Component 3: Enhancing Ac Request for Quota Single Stage - One E materials such as CGI sheet, TF / A4224 Post Open - National 6,000.00 0.00 Canceled 2019-12-15 2020-02-09 2020-08-07 cess to Markets tions nvelope Nails, timbers and sand for c onstruction of Marketing stru ctures under Haa Dzongkhag . Page 6 BT-MOAF-133603-GO-RFQ / Procurement of Agriculture t ools and equipments 41 sets- Component 2: Enhancing Fa Request for Quota Single Stage - One E drip irrigation set, 40 rolls-pl TF / A4224 Post Open - National 17,000.00 218,196.67 Completed 2019-12-21 2020-02-15 2020-03-16 2020-08-13 2020-06-24 rmer Productivity tions nvelope astic mulch, 54 nos-plastic ta nks, 8 nos-watering can, 21 r olls- flexible pipes and 50 set s- low cost poly house (with nylon belt) BT-MOAF-133728-GO-RFQ / Procurement of 122 kg-TMT Bars, 30 nos-CGI sheet, 8 no s -ridging, 5000 meters-GI wi Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / A4224 Post Open - National 11,300.00 2,304.91 Completed 2019-12-17 2020-02-11 2019-09-19 2020-08-09 2019-10-01 re, 15 square meter- Gi sheet rmer Productivity tions nvelope , 22 nos-silpualin sheets and 500 nos-beehive box. To be i ssued to Lhamoizingkha Gew og under Dagana Dzongkhag . BT-MOAF-134019-GO-RFB / Procurement of 46 sets-drip i Component 2: Enhancing Fa Single Stage - One E TF / A4224 Post Request for Bids Open - National 17,172.00 21,670.80 Completed 2019-12-10 2019-12-10 2019-12-15 2020-01-26 2020-01-30 2020-02-25 2020-02-11 2020-03-31 2020-03-21 2020-09-27 2020-05-26 rrigation system, 60 rolls-pla rmer Productivity nvelope stic mulching and 13 nos-pol y house. BT-MOAF-134021-GO-RFQ / Procurement of 13 nos- Mini Component 2: Enhancing Fa Request for Quota Single Stage - One E Power tiller (women friendly) TF / A4224 Post Limited 41,354.00 14,201.47 Completed 2019-12-25 2020-01-16 2020-02-19 2020-03-05 2020-08-17 2020-04-28 rmer Productivity tions nvelope to be issued to project gewog s under Dagana Dzongkhag. BT-MOAF-134120-GO-RFQ / Procurement of 15 sets of fa Component 2: Enhancing Fa Request for Quota Single Stage - One E bricated poly house to be iss TF / A4224 Post Open - National 15,000.00 0.00 Canceled 2019-12-21 2020-02-15 2020-08-13 rmer Productivity tions nvelope ued to the project Geo=wogs under Sarpang dzongkhag. BT-MOAF-134123-GO-RFQ / Procurement of 85 numbers Component 2: Enhancing Fa Request for Quota Single Stage - One E of low cost poly house to be TF / A4224 Post Open - National 11,000.00 22,613.08 Completed 2019-12-18 2020-02-12 2020-01-04 2020-08-10 2020-03-23 rmer Productivity tions nvelope issued to the project Geowgs under Sarpang Dzongkhag. BT-MOAF-134142-GO-RFQ / procurement of Agriculture T ools and Implements: 8 nos- rooting hormone, 1 no. -Quin Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / A4224 Post Open - National 6,000.00 6,322.24 Completed 2020-01-04 2020-02-29 2019-12-26 2020-08-27 2020-06-18 oa machine, 3 nos-Plastic se rmer Productivity tions nvelope aling machine, 100kg - plasti c sheet, 25 nos-copper sulfat e, 50kg-lime, 1 no.-min powe r chain, 21- brush and etc. BT-MOAF-135118-GO-RFQ / Procurement of 100 nos.- pla Component 3: Enhancing Ac Request for Quota Single Stage - One E stic crates and 5 nos.-digital TF / A4224 Post Open - National 3,000.00 0.00 Canceled 2020-01-05 2020-03-01 2020-08-28 cess to Markets tions nvelope weighing balance to be issue d to the schools and instituti on under the project area. BT-MOAF-135137-GO-RFQ / Procurement of Smart Irrigati on Materials such as Drip Irri Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / A4224 Post Open - National 10,500.00 0.00 Canceled 2019-12-16 2020-02-10 2020-08-08 gation sets and pipes to be u rmer Productivity tions nvelope sed during the capacity buildi ng training to the engineers under the Project Dzongkhag s. BT-MOAF-135141-GO-RFQ / Procurement of 5-nos of Gree Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / A4224 Post Open - National 22,500.00 0.00 Canceled 2020-01-01 2020-02-26 2020-08-24 nhouse to be used for Nation rmer Productivity tions nvelope al Citrus Repository. BT-MOAF-140361-GO-RFB / Procurement of value additio n equipment such as 7-Dryer Component 3: Enhancing Ac Single Stage - One E TF / A4224 Post Request for Bids Open - National 27,000.00 0.00 Canceled 2020-01-24 2020-01-29 2020-03-11 2020-04-10 2020-05-15 2020-11-11 s, 7 Visi Coolers, 7-Mini Flour cess to Markets nvelope Mill, 7-Rice milling machine t o be issued to farmer under t he project area. BT-MOAF-141893-GO-RFQ / Procurement of four Laptops Component 4: Project Manag Request for Quota Single Stage - One E to be used by project engine TF / A4224 Post Limited 4,500.00 5,149.15 Completed 2019-12-27 2019-10-22 2020-02-21 2020-02-18 2020-08-19 2020-05-14 ement tions nvelope ers and other officials in Proj ect Management Unit (FSAPP ). BT-MOAF-141921-GO-RFQ / Procurement of construction Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / A4224 Post Limited 3,000.00 0.00 Canceled 2020-01-27 2020-03-23 2020-09-19 materials for cardamom repo rmer Productivity tions nvelope sitory to be installed at ARD SC at Menchuna. BT-MOAF-129203-GO-DIR / P rocurement of 1000 nos- ma Component 1:Strengthening TF / A4224 Post Direct Selection Direct 780.00 680.48 Completed 2020-04-15 2019-09-12 2020-04-20 2019-10-17 2020-05-25 2019-10-18 2020-11-21 2020-06-02 ndarin seedling directly from Farmer and Producer Groups Government Authorized deal ers. BT-MOAF-133725-GO-DIR / P rocurement of 15 meters- 2. 5 kg HDPE pipe, 500 meters- Component 2: Enhancing Fa TF / A4224 Post Direct Selection Direct 5,300.00 415.45 Completed 2019-12-09 2020-06-01 2019-12-14 2020-05-04 2020-01-18 2020-06-09 2020-07-16 2020-07-01 12.5 PN HDPE pipes, 450 Nos rmer Productivity -75 mm HDPE pipes and 400 meters- 12.5 PN HDPE pipes. BT-MOAF-133727-GO-DIR / P rocurement of 1515 cft-sand and 98 cft timbers for constr Component 2: Enhancing Fa TF / A4224 Post Direct Selection Direct 700.00 31.18 Completed 2020-02-06 2019-12-02 2020-02-11 2019-12-02 2020-03-17 2020-01-09 2020-09-13 2020-01-31 uction of bio digester directly rmer Productivity from Natural Resources Deve lopment Corparation Ltd (Go vernment approved rates) BT-MOAF-133410-GO-DIR / P rocurement of seeds and see dlings (3050 packets- summ Component 2: Enhancing Fa TF / A4224 Post Direct Selection Direct 10,000.00 7,504.58 Completed 2019-11-21 2020-01-30 2019-11-26 2020-01-30 2019-12-31 2020-06-03 2020-06-28 2020-07-01 er vegetable seeds, 500kg-u rmer Productivity pland paddy, 1150kg-legume s, 3500 nos-citrus, 1430 pkts - commercial veg. seeds) BT-MOAF-134150-GO-DIR / P rocurement of Quinoa seeds Component 2: Enhancing Fa TF / A4224 Post Direct Selection Direct 600.00 539.59 Completed 2020-01-15 2020-03-02 2020-01-20 2020-03-05 2020-02-24 2020-04-01 2020-08-22 2020-06-12 directly from the farmers to b rmer Productivity e issued to project Gewogs. Page 7 BT-MOAF-133417-GO-DIR / P rocurement of 50 bags-ceme Component 3: Enhancing Ac TF / A4224 Post Direct Selection Direct 100.00 349.77 Completed 2019-11-28 2020-06-02 2019-12-03 2020-06-03 2020-01-07 2020-06-10 2020-07-05 2020-06-10 nt directly from the agent to cess to Markets be used for construction of m arketing structures. BT-MOAF-141919-GO-DIR / D irect procurement of various cardamom seeds: 1 kilogram Component 2: Enhancing Fa TF / A4224 Post Direct Selection Direct 700.00 0.00 Canceled 2020-02-06 2020-02-11 2020-03-17 2020-09-13 Barlangay, 5-Cardamom Suc rmer Productivity ker, 5-Cardamom golsey and 5-cardamom Sawsey to be us ed in ARDSC Menchuna. BT-MOAF-133606-GO-DIR / P rocurement of HDPE pipes: 6 Component 2: Enhancing Fa TF / A4224 Post Direct Selection Direct 8,800.00 6,249.83 Completed 2020-02-10 2020-03-20 2020-02-15 2020-02-14 2020-03-21 2020-04-01 2020-09-17 2020-06-16 80: HDPE pipe (110mm) and rmer Productivity 680m: HDPE pipe (63mm) BT-MOAF-134023-GO-DIR / P rocurement of 3000 nos of bl Component 2: Enhancing Fa ack pepper seedlings directly TF / A4224 Post Direct Selection Direct 736.00 798.29 Completed 2020-05-01 2020-05-11 2020-05-06 2020-05-12 2020-06-10 2020-05-13 2020-12-07 2020-06-16 rmer Productivity from the supplier to further is sue to other farmers under t he project gewogs. BT-MOAF-130542-GO-DIR / P rocurement of seeds 200 pac kets - cabbage, 200 packets- radish, 250 packets-broccoli, Component 2: Enhancing Fa 200 packets-onion, 200 pack TF / A4224 Post Direct Selection Direct 4,500.00 6,795.66 Completed 2019-12-18 2019-09-26 2019-12-23 2019-10-02 2020-01-27 2019-10-15 2020-07-25 2020-06-11 rmer Productivity ets-tomato, 250 packets-pea, 200 packets-chilli, 230 packe st-cauliflower, beans, lettuce, carrot, pumpkin, water melo n and bitter guard. BT-MOAF-188064-GO-RFQ / Procurement of 16 Laptops a Component 4: Project Manag Request for Quota Single Stage - One E TF / A4224 Post Open - National 14,000.00 15,920.56 Completed 2020-11-04 2020-12-30 2020-11-19 2021-06-28 2021-02-02 nd one photocopy machine t ement tions nvelope o be issued to the Project Ge wog Officials. BT-MOAF-129208-GO-RFQ / r ocurement of 3 sets - solar fe nce energizer inclusive of sol Component 1:Strengthening Request for Quota Single Stage - One E TF / A4224 Post Limited 2,300.00 0.00 Canceled 2019-11-27 2020-01-22 2020-07-20 ar fencing wire (3000m) and Farmer and Producer Groups tions nvelope solar power tester to be issu ed to Haa and Chhukha Dzon gkhag Project Gewogs. BT-MOAF-99088-GO-DIR / Di Component 2: Enhancing Fa rect procurement of Vegetabl TF / A4224 Post Direct Selection Direct 600.00 0.00 Canceled 2019-02-22 2019-02-27 2019-04-03 2019-09-30 rmer Productivity e seeds from the National se ed Centre. BT-MOAF-238504-GO-DIR / P rocurement of Vegetable Dry Component 3: Enhancing Ac TF / A4224 Post Direct Selection Direct 13,556.00 5,872.23 Completed 2021-08-05 2020-08-06 2021-08-10 2020-08-06 2021-09-14 2020-08-07 2022-03-13 2021-11-11 ing Facilities to be establishe cess to Markets d at Damchu under Chhukha Dzongkhag. BT-MOAF-254156-GO-RFQ / Procurement of mushroom s Component 2: Enhancing Fa Request for Quota Single Stage - One E pawn production equipment ( TF / B6044 Post Open - National 10,826.00 7,100.52 Completed 2021-11-04 2021-12-14 2021-12-09 2022-06-12 2022-03-28 rmer Productivity tions nvelope 2 autoclaves and 2 laminar ai rflow cabinets) for 2 Districts (Haa and Sarpang) BT-MOAF-254209-GO-RFB / Procurement of drip irrigation sets, HDPE pond lining sheet Component 2: Enhancing Fa Single Stage - One E TF / A4224 Prior Request for Bids Open - National 149,459.00 102,044.97 Completed 2021-11-15 2021-11-26 2021-11-20 2021-12-31 2022-01-01 2022-01-05 2022-01-31 2022-02-09 2022-03-07 2022-03-01 2022-09-03 2022-05-24 and mulching plastic for 5 Pr rmer Productivity nvelope oject Districts (Samtse, Sapa ng, Haa, Chhukha and Dagan a) BT-MOAF-236744-GO-RFB / Procurement of 1000 number Component 2: Enhancing Fa Open - Internationa Single Stage - One E TF / A4224 Prior Request for Bids 1,208,761.00 0.00 Canceled 2021-08-26 2021-08-31 2021-10-12 2021-11-11 2021-12-16 2022-06-14 s of Greenhouse and 1000 dr rmer Productivity l nvelope ip sets to be issued to Project Dzongkhags. BT-MOAF-229396-GO-RFQ / Component 2: Enhancing Fa Request for Quota Single Stage - One E Procurement of Mushroom S TF / A4224 Post Open - National 18,000.00 0.00 Canceled 2021-09-21 2021-11-16 2022-05-15 rmer Productivity tions nvelope pawn Products for Youth Ente rprise. BT-MOAF-229399-GO-RFQ / Procurement of 300 Nos of f Component 3: Enhancing Ac Request for Quota Single Stage - One E TF / A4224 Post Open - National 10,000.00 0.00 Canceled 2021-09-04 2021-10-30 2022-04-28 oldable plastic crates to be s cess to Markets tions nvelope upplied to all the FSAPP Dzon gkhags. BT-MOAF-236274-GO-RFQ / Procurement of 100 numbers Component 3: Enhancing Ac Request for Quota Single Stage - One E TF / A4224 Post Open - National 5,000.00 0.00 Canceled 2021-09-28 2021-11-23 2022-05-22 of Digital Weighing Balance t cess to Markets tions nvelope o be issued to Project Gewog s. BT-MOAF-254207-GO-RFB / Procurement of poly houses f Component 2: Enhancing Fa Single Stage - One E TF / A4224 Prior Request for Bids Open - National 741,577.00 0.00 Canceled 2021-11-15 2021-12-06 2021-11-25 2022-01-10 2022-01-06 2022-01-08 2022-02-05 2022-03-12 2022-09-08 or 5 Project Districts (Samtse rmer Productivity nvelope , Sapang, Haa, Chhukha and Dagana) BT-MOAF-279255-GO-RFB / Procurement of poly houses f Component 2: Enhancing Fa Single Stage - One E TF / A4224 Prior Request for Bids Open - National 741,577.00 744,768.89 Completed 2022-03-02 2022-02-23 2022-03-07 2022-02-25 2022-04-18 2022-04-12 2022-05-18 2022-05-03 2022-06-22 2022-05-30 2022-12-19 2022-12-28 or 5 Project Districts (Samtse rmer Productivity nvelope , Sapang, Haa, Chhukha and Dagana) BT-MOAF-279964-GO-RFQ / Supply of Pulveriser Machine, Component 2: Enhancing Fa Request for Quota Single Stage - One E TF / B6044 Post Open - National 3,900.00 5,207.65 Completed 2022-03-20 2022-05-15 2022-04-28 2022-11-11 2022-08-09 Manual Sealing Machine and rmer Productivity tions nvelope Vacuum Packing Machine to Samtse Dzongkhag BT-MOAF-273403-GO-RFB / Supply of equipment to furni Component 3: Enhancing Ac Request for Quota Single Stage - One E sh the Farmers Sales Outlet ( TF / A4224 Post Open - National 26,500.00 21,027.65 Completed 2022-04-17 2022-05-22 2022-05-26 2022-07-21 2022-07-29 cess to Markets tions nvelope FSO) of project districts (Chh ukha, Haa, Dagana, Samtse and Sarpang) BT-MOAF-229398-GO-RFQ / Component 2: Enhancing Fa Request for Quota Single Stage - One E Procurement of Cropcut Instr TF / A4224 Post Open - National 15,000.00 0.00 Canceled 2021-09-27 2021-11-22 2022-05-21 rmer Productivity tions nvelope uments/GPS to be issued to p roject Gewogs. Page 8 BT-MOAF-293311-GO-DIR / P rocurement of 8 nos of Drum seeder for demonstration of Component 2: Enhancing Fa TF / A4224 Post Direct Selection Direct 1,448.00 1,772.30 Completed 2022-05-31 2022-05-20 2022-06-05 2022-05-20 2022-06-30 2022-05-21 2022-08-14 2022-05-28 direct seeded paddy under S rmer Productivity amtse Dzoongkhag through Agriculture Machinery Center , DOA BT-MOAF-298205-GO-DIR / P rocurement of additional mus hroom spawn production equ Component 2: Enhancing Fa TF / B6044 Post Direct Selection Direct 3,481.00 3,450.52 Completed 2022-06-07 2022-06-07 2022-06-09 2022-06-08 2022-06-17 2022-06-09 2022-07-17 2022-06-21 ipment (1 no. of autoclave an rmer Productivity d 1 no. of laminar airflow cab inet) to build the capacity of National Mushroom Center. BT-MOAF-317975-GO-DIR / P rocurement of HDPE pipe, To p soil, Plastic bags, water tan k, rubber band, cotton and T Component 2: Enhancing Fa ablet/phone for enhancing ca TF / B6044 Post Direct Selection Direct - National 1,375.00 0.00 Completed 2022-11-23 2022-11-29 2022-11-28 2022-11-29 2022-12-19 2023-02-02 2023-02-14 rmer Productivity pacity of the National Mushro om Center by supporting the promotion of ganoderma mu shroom production in project Dzongkhags (Sl.No. 2.2.1) BT-MOAF-317977-GO-RFQ / Procurement of Sensors(Oxy gen,Humidity,Temp,CO2,Soil moisture, Light, Ultronic), Rel Component 2: Enhancing Fa Request for Quota Single Stage - One E lay, Fans,Plastic crates &pipe TF / B6044 Post Limited 2,845.00 0.00 Completed 2022-12-05 2022-12-27 2023-01-30 2023-03-31 2023-05-24 rmer Productivity tions nvelope s,water pump, Micro controll er,Mother board & fogger set to enhance capacity of the N MC for promotion of ganoder ma mushroom production(2. 2.1) BT-MOAF-328868-GO-RFQ / Procurement of materials (el ectro fusion machine, electro Component 2: Enhancing Fa Request for Quota Single Stage - One E fusion couplers & HDPE Pipe) TF / B6044 Post Limited 6,500.00 0.00 Completed 2023-01-04 2022-12-05 2023-02-17 2023-04-03 2023-03-30 rmer Productivity tions nvelope to Put-right activities of Thar eykhola Irrigation Systems u nder Norbuling Gewog, Samt se (Sl.No.2.1.1) BT-MOAF-329343-GO-RFQ / Procurement of Materials req uired for Hydroponic System Component 2: Enhancing Fa Request for Quota Single Stage - One E for evaluation of nutrient for TF / A4224 Post Limited 3,750.00 0.00 Signed 2023-01-04 2022-12-09 2023-03-01 2023-04-30 rmer Productivity tions nvelope mulation and Heavy-duty Pri nter for Soil & Plant Analytica l Laboratory to be issued to N ational Soil Service Center. BT-MOAF-364076-GO-RFB / Procurement of Plastic pallet s, Plastic Crates, Trolleys, Bu Component 3: Enhancing Ac Single Stage - One E Pending Impl bble washing machine, Conv TF / B6044 Post Request for Bids Open - National 76,000.00 0.00 2023-07-15 2023-07-20 2023-08-19 2023-09-18 2023-10-24 2024-01-22 cess to Markets nvelope ementation eyer belt, Drying machine, w ork tables for the Integrated Cold Storage, Centralized pa ckhouse and Field packhouse s. G4 / Green Houses (vegetabl Component 1:Strengthening Request for Quota Single Stage - One E / Post Open - National 20,000.00 0.00 Canceled 2016-11-06 2017-01-01 2017-02-02 es) Farmer and Producer Groups tions nvelope Component 1:Strengthening Request for Quota Single Stage - One E G5 / Electric fencing / Post Open - National 40,000.00 0.00 Canceled 2016-11-06 2017-01-01 2017-02-02 Farmer and Producer Groups tions nvelope G17 / Office equipment/furni Component 1:Strengthening Request for Quota Single Stage - One E TF / A4224 Post Open - National 3,000.00 3,318.27 Completed 2017-02-05 2017-04-02 2018-04-17 2017-05-02 2018-06-11 ture Farmer and Producer Groups tions nvelope G7 / Support to Citrus reposi Component 1:Strengthening Request for Quota Single Stage - One E / Post Open - National 15,000.00 0.00 Canceled 2017-02-05 2017-04-02 2017-05-02 tory RDSC Tsirang (equipmen Farmer and Producer Groups tions nvelope ts) G1 / Equipment and dissemi Component 1:Strengthening Request for Quota Single Stage - One E / Post Open - National 8,005.00 0.00 Canceled 2016-11-01 2016-12-27 2017-01-27 nation of BCC materials Farmer and Producer Groups tions nvelope G9 / Cardamom propogation Component 1:Strengthening Request for Quota Single Stage - One E / Post Open - National 25,000.00 0.00 Canceled 2016-11-06 2017-01-01 2017-02-01 house for farmers (materials Farmer and Producer Groups tions nvelope only) G15 / Photocopier heavy dut Component 1:Strengthening Request for Quota Single Stage - One E TF / A4224 Post Open - National 2,000.00 1,666.14 Completed 2017-02-05 2017-04-02 2018-04-24 2017-05-02 2018-05-11 y Farmer and Producer Groups tions nvelope Component 1:Strengthening Request for Quota Single Stage - One E G3 / Farm machinery / Post Open - National 39,000.00 0.00 Canceled 2016-11-06 2017-01-01 2017-06-30 Farmer and Producer Groups tions nvelope G10 / Cardamom curing hou Component 1:Strengthening Request for Quota Single Stage - One E / Post Open - National 10,000.00 0.00 Canceled 2016-11-06 2017-01-01 2017-02-01 se Farmer and Producer Groups tions nvelope Component 1:Strengthening Request for Quota Single Stage - One E G13 / Printers / Post Open - National 2,400.00 0.00 Canceled 2017-02-05 2017-04-02 2017-05-02 Farmer and Producer Groups tions nvelope Component 1:Strengthening Request for Quota Single Stage - One E G12 / Laptops / Post Open - National 7,000.00 0.00 Canceled 2017-02-05 2017-04-02 2017-05-02 Farmer and Producer Groups tions nvelope G2 / Demonstration of impro Component 1:Strengthening Request for Quota Single Stage - One E / Post Open - National 10,000.00 0.00 Canceled 2016-11-06 2017-01-01 2017-01-31 ved technologies Farmer and Producer Groups tions nvelope Component 1:Strengthening G8 / Seeds and seedlings / Prior Direct Selection Direct 300,000.00 0.00 Canceled 2017-04-20 2017-04-25 2017-05-30 2017-06-30 Farmer and Producer Groups Component 1:Strengthening Request for Quota Single Stage - One E G14 / Scanner / Post Open - National 600.00 0.00 Canceled 2017-02-05 2017-04-02 2017-05-02 Farmer and Producer Groups tions nvelope Component 1:Strengthening Request for Quota Single Stage - One E G16 / Binding machine / Post Open - National 600.00 0.00 Canceled 2017-02-05 2017-04-02 2017-05-02 Farmer and Producer Groups tions nvelope NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 9 BT-MOAF-99086-NC-RFB / Pr Component 2: Enhancing Fa Request for Quota Single Stage - One E ocurement of Quinoa Poster TF / A4224 Post Open - National 1,500.00 3,910.21 Completed 2019-04-07 2019-06-02 2018-02-05 2019-11-29 2018-06-20 rmer Productivity tions nvelope Printing Services for ARDC, Y usipang. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BT-MOAF-66724-CS-QCBS / Hiring of consultant firm to st Component 1:Strengthening Consultant Qualifi TF / A4224 Post Open - National 14,000.00 0.00 Canceled 2018-06-25 2018-06-01 2018-06-29 2018-06-27 2018-08-12 2018-07-02 2018-09-11 2018-09-25 2018-10-16 2019-04-14 udy the Project Baseline Stud Farmer and Producer Groups cation Selection y for the FSAPP, Project. CS3 / Baseline and impact st Component 1:Strengthening Quality And Cost- / Post Open - National 30,000.00 0.00 Canceled 2017-01-31 2018-04-25 2017-02-21 2017-04-06 2018-06-04 2017-05-04 2018-06-18 2017-06-03 2018-06-29 2017-07-08 2017-08-12 2017-12-10 udies for Monitoring and Eval Farmer and Producer Groups Based Selection uation BT-MOAF-75483-CS-CQS / Hi ring of Consultant for Project Baseline Study. The Method f Component 1:Strengthening Consultant Qualifi TF / A4224 Post Open - National 30,000.00 23,927.37 Completed 2018-11-22 2018-09-07 2018-12-13 2019-01-26 2018-09-14 2019-02-25 2018-09-20 2019-04-01 2018-10-03 2019-09-28 2019-04-17 ollowed is Consultant Qualific Farmer and Producer Groups cation Selection ation Selection as the PMU co uld hire a consultant using Q CBS method. BT-MOAF-79529-CS-QCBS / Hiring of Consultant to Carry Component 3: Enhancing Ac Quality And Cost- TF / A4224 Post Open - National 31,000.00 25,753.53 Completed 2018-12-03 2019-04-26 2018-12-24 2019-02-06 2019-06-12 2019-03-06 2019-06-19 2019-04-05 2019-06-25 2019-05-10 2019-07-12 2019-06-14 2019-08-16 2020-06-13 2019-10-16 out Value Chain Studies of th cess to Markets Based Selection e two specified Agriculture C ommodities. BT-MOAF-135133-CS-QCBS / Hiring of consultant to develo Component 4: Project Manag Quality And Cost- p Project Monitoring Informat TF / A4224 Post Open - National 15,000.00 0.00 Canceled 2019-12-15 2020-01-05 2020-02-18 2020-03-17 2020-04-16 2020-05-21 2020-06-25 2021-06-25 ement Based Selection ion System (MIS) to efficientl y monitor the activities under this project (FSAPP). BT-MOAF-135135-CS-QCBS / Procurement of consultancy f Component 4: Project Manag Quality And Cost- TF / A4224 Post Open - National 30,000.00 0.00 Canceled 2020-04-01 2020-04-22 2020-06-05 2020-07-03 2020-08-02 2020-09-06 2020-10-11 2021-10-11 irm to develop the document ement Based Selection for mid term review of the FS APP project. BT-MOAF-140360-CS-QCBS / Hiring of Consultant to devel Component 1:Strengthening Quality And Cost- TF / A4224 Post Open - National 15,000.00 0.00 Canceled 2019-12-26 2020-01-16 2020-02-29 2020-03-28 2020-04-27 2020-06-01 2020-07-06 2021-07-06 op online Farmer Groups and Farmer and Producer Groups Based Selection Cooperatives Registration Sy stem. BT-MOAF-191163-CS-CQS / Hiring of Consultant to produ ce Audio-Visual on Pesticides Component 2: Enhancing Fa Consultant Qualifi TF / A4224 Post Open - National 12,000.00 10,890.54 Completed 2020-11-12 2020-01-24 2020-12-03 2021-01-16 2020-02-13 2021-02-15 2020-02-16 2021-03-22 2020-04-17 2021-09-18 2020-07-01 Management to create aware rmer Productivity cation Selection ness on use of pesticides and its impact on human health. BT-MOAF-236740-CS-CQS / Hiring of consultant to produ Component 1:Strengthening Consultant Qualifi ce a documentary film on Fo TF / A4224 Post Open - National 15,000.00 0.00 Canceled 2021-08-05 2021-12-22 2021-08-26 2021-10-09 2021-11-08 2021-12-13 2022-06-11 Farmer and Producer Groups cation Selection od for Health to create public awareness on Dietary Divers ity. CS4 / Annual Outcome and b Component 1:Strengthening Quality And Cost- / Post Open - National 5,000.00 0.00 Canceled 2017-04-01 2017-04-22 2017-06-05 2017-07-03 2017-08-02 2017-09-06 2017-10-11 2018-01-11 eneficiary surveys Farmer and Producer Groups Based Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1:Strengthening CS7 / FAO TA TF / A4224 Prior Direct Selection Direct 1,222,202.00 1,152,911.00 Signed 2017-01-31 2017-11-21 2017-02-10 2017-05-10 2017-04-16 2017-08-01 2017-10-13 Farmer and Producer Groups BT-MOAF-54815-CS-CDS / Pr Component 1:Strengthening TF / A4224 Prior Direct Selection Direct 14,000.00 0.00 Canceled 2018-03-21 2018-03-31 2018-06-04 2018-12-01 oject Baseline Study (Direct Farmer and Producer Groups Selection) BT-MOAF-60198-CS-INDV / P Component 1:Strengthening Individual Consult TF / A4224 Post Limited 14,000.00 0.00 Canceled 2018-04-26 2018-04-25 2018-05-01 2018-05-21 2018-05-22 2018-06-26 2018-12-23 roject Baseline Study Farmer and Producer Groups ant Selection BT-MOAF-104512-CS-INDV / Hiring of Individual Consultan t to develop the project webi ste to enable the project publ Component 4: Project Manag Individual Consult TF / A4224 Post Limited 1,500.00 1,114.40 Completed 2019-03-20 2019-03-19 2019-03-25 2019-03-22 2019-04-15 2019-04-22 2019-05-20 2018-10-03 2019-11-16 2019-04-17 ish proceedings, annual agric ement ant Selection ulture highlights, Meetings Mi nutes, research papers, broc hures, downloads, Technical i nformation etc. CS6 / Development of materi Component 1:Strengthening Individual Consult als (Digital Green) for Aware / Post Open - National 36,000.00 0.00 Canceled 2017-04-01 2017-05-20 2017-06-10 2017-07-15 2018-01-11 Farmer and Producer Groups ant Selection ness raising for dietray diver sity CS2 / Development and tran Component 1:Strengthening Individual Consult slation of materials for linkin / Post Open - National 5,000.00 0.00 Canceled 2016-12-01 2017-01-19 2017-02-09 2017-03-16 2017-05-16 Farmer and Producer Groups ant Selection g Pos with School meal progr ammes for DDS CS1 / Translation and printin Component 1:Strengthening Individual Consult g of materials for farmer gro / Post Open - National 2,000.00 0.00 Canceled 2016-12-01 2017-01-19 2017-02-09 2017-03-16 2017-09-12 Farmer and Producer Groups ant Selection up formation and strengtheni ng Page 10 PROCUREMENT PLAN (Textual Part) Project information: Republic of Marshall Islands Sustainable Energy Development Project P160096 & P163699 Project Implementation agency: PREP2 PMU, Division of International Development Assistance-Ministry of Finance (DIDA-MOF), and SPC-Pacific Community Date of the Procurement Plan: May 10, 2018 Period covered by this Procurement Plan: May 1, 2018 to Nov 30, 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Code of 1988, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1. The procurement is open to all eligible firms from any country; 2. The request for bids/request for proposals document shall require the Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting signed contracts, confirming application of, and compliance with, the Bank's Anti- Corruption Guidelines, including without limitation the Bank's right to sanction and the Bank's inspection and audit rights; 3. Publication of contract award information; 4. Rights for the Bank to review procurement documentation and activities; and 5. An effective complaints mechanism. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Work) Goods: is not applicable; Works: is not applicable. PROCUREMENT Marshall Islands : Pacific Resilience Project II under the Pacific Resilience Program PLAN General Information Country: Marshall Islands 2018-10-21 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160096 GPN Date: 2018-06-19 Project Name: Pacific Resilience Project II under the Pacific Resilience Program Loan / Credit No: IDA / D1830, IDA / V0410 Project Implementation Unit, PREP II Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MH-PREP II-PIU-83439-CW-R Component 1: Institutional S Request for Quota Open - Internationa Single Stage - One E 2020-07-1 FB / NDMO Building Refurbish IDA / D1830 trengthening, Early Warning Post 750,000.00 0.00 Canceled 2019-11-23 2020-01-18 tions l nvelope 6 ment and Preparedness MH-PREP II-PIU-81920-CW-R Component 2: Strengthening Request for Propo Open - Internationa 35,312,500.0 2023-10-2 IDA / D1830 Prior Multi Stage 0.00 Canceled 2020-12-31 2021-01-05 2021-03-16 2021-06-28 2021-08-02 FP / Coastal Protection Works Coastal Resilience sals l 0 1 MH-PREP II-PIU-119118-CW- Component 1: Institutional S RFQ / Support for NDMO Stre Open - Internationa Single Stage - One E 2021-06-2 IDA / D1830 trengthening, Early Warning Prior Request for Bids 1,050,000.00 0.00 Canceled 2020-09-06 2020-09-11 2020-10-23 2020-11-22 2020-12-27 ngthening as per NDMO Roa l nvelope 5 and Preparedness dmap including NDMO Refurb ishment Works. MH-PREP II-PIU-252921-GO- Component 1: Institutional S RFQ / Support for NDMO Stre Request for Quota Single Stage - One E Other (with field f Under Imple 2024-02-1 IDA / D1830 trengthening, Early Warning Post Open - National 400,000.00 0.00 2023-06-21 2023-08-16 ngthening as per NDMO Roa tions nvelope or explanation) mentation 2 and Preparedness dmap including NDMO Refurb ishment Works MH-PREP II-PIU-356432-CW- Component 1: Institutional S DIR / Installation and Commis Other (with field f Under Imple 2023-11-1 IDA / D1830 trengthening, Early Warning Prior Direct Selection Direct - National 2,300,000.00 0.00 2023-04-13 2023-04-17 2023-04-18 2023-05-01 2023-05-23 sioning of the Emergency Co or explanation) mentation 9 and Preparedness mmunications Network and A ssociated Trainings Request for Bids - MH-PREP II-PIU-239881-CW- Component 2: Strengthening Open - Internationa Single Stage - Two E 36,987,473.0 2024-02-0 IDA / D1830 Prior Request for Bids Works SPD (after 0.00 Canceled 2021-12-01 2022-05-20 2022-02-16 2022-02-16 2021-12-06 2022-07-13 2022-04-27 2022-07-10 2022-08-14 RFB / Coastal Protection Wor Coastal Resilience l nvelope 0 5 prequalification) ks Request for Bids - MH-PREP II-PIU-364075-CW- Works (without pr Component 2: Strengthening Open - Internationa Single Stage - Two E 60,520,000.0 Pending Imp 2027-11-1 RFB / Coastal Protection Wor IDA / D1830 Prior Request for Bids equalification) SP 0.00 2023-06-27 2023-06-29 2023-10-01 2024-05-15 Coastal Resilience l nvelope 0 lementation 5 ks D - Applying contr actor disqualificia tion GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MH-PREP II-PIU-83438-GO-RF Component 4: Project and Pr Request for Quota Single Stage - One E Q / Office Equipment includin IDA / D1830 Post Open - National 61,000.00 0.00 Canceled 2019-08-05 2019-09-30 2020-03-28 ogram Management tions nvelope g Computers MH-PREP II-PIU-252918-GO- Component 4: Project and Pr Request for Quota Single Stage - One E RFQ / Office Equipment inclu IDA / D1830 Post Open - National 61,000.00 0.00 Signed 2021-10-05 2021-11-03 2021-11-30 2022-05-29 ogram Management tions nvelope ding Computers MH-PREP II-PIU-252920-GO- Component 1: Institutional S RFQ / Supply of IT equipment Request for Quota Single Stage - One E IDA / D1830 trengthening, Early Warning Post Open - National 50,000.00 39,155.87 Signed 2021-10-20 2021-11-11 2021-12-15 2022-07-15 2022-06-13 , outdoor equipment & office tions nvelope and Preparedness furniture under the NDMO Ro admap MH-PREP II-PIU-163821-GO- Component 4: Project and Pr Request for Quota Single Stage - One E IDA / D1830 Post Open - National 40,000.00 0.00 Canceled 2020-05-05 2020-06-30 2020-12-27 RFB / Project Vehicle ogram Management tions nvelope MH-PREP II-PIU-301507-GO- Component 4: Project and Pr Request for Quota Single Stage - One E IDA / D1830 Post Open - National 50,000.00 0.00 Signed 2022-07-20 2023-03-02 2022-09-14 2023-03-13 RFQ / Project Vehicle Resubm ogram Management tions nvelope ission MH-PREP II-PIU-83436-GO-RF Component 1: Institutional S Open - Internationa Single Stage - One E Q / Emergency Communicati IDA / D1830 trengthening, Early Warning Prior Request for Bids 1,100,000.00 0.00 Canceled 2022-01-03 2022-01-08 2022-02-19 2022-03-21 2022-04-25 2022-10-22 l nvelope on Equipment Supply & Com and Preparedness mission MH-PREP II-PIU-347314-GO- Component 1: Institutional S Request for Quota Single Stage - One E RFQ / VHF Emergency Comm IDA / D1830 trengthening, Early Warning Prior Limited 218,400.00 0.00 Signed 2023-03-12 2023-04-17 2023-05-07 2023-06-20 2023-11-03 tions nvelope unications Equipment Supply and Preparedness MH-PREP II-PIU-348605-GO- Component 4: Project and Pr Request for Quota Single Stage - One E Under Imple IDA / D1830 Post Open - National 10,000.00 0.00 2023-03-18 2023-05-13 2023-11-09 RFQ / Supply of Office Furnitu ogram Management tions nvelope mentation re for PIU MH-PREP II-PIU-342614-GO- Component 1: Institutional S Request for Quota Open - Internationa Single Stage - One E RFQ / IT Equipment to Suppo IDA / V0410 trengthening, Early Warning Post 48,700.00 0.00 Signed 2023-03-05 2023-03-27 2023-04-30 2023-10-27 tions l nvelope rt NDMO and Preparedness MH-PREP II-PIU-345824-GO- Component 1: Institutional S Request for Quota Open - Internationa Single Stage - One E RFQ / Non-IT Equipment Sup IDA / V0410 trengthening, Early Warning Post 9,900.00 0.00 Signed 2023-03-17 2023-04-09 2023-05-12 2023-11-08 tions l nvelope port to NDMO and Preparedness MH-PREP II-PIU-355664-GO- Component 1: Institutional S Request for Quota Single Stage - One E Under Imple RFQ / HF Communication Equ IDA / D1830 trengthening, Early Warning Prior Limited 666,550.00 0.00 2023-04-24 2023-04-17 2023-06-19 2023-12-16 tions nvelope mentation ipment for Support to EC Roa and Preparedness dmap MH-PREP II-PIU-361450-GO- Component 1: Institutional S RFQ / Procurement of masts Request for Quota Open - Internationa Single Stage - One E IDA / D1830 trengthening, Early Warning Post 235,000.00 0.00 Signed 2023-05-24 2023-05-17 2023-07-19 2024-01-15 and antennas in support of th tions l nvelope and Preparedness e Emergency Communication s Network NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 MH-PREP II-PIU-81923-NC-RF Component 4: Project and Pr Request for Quota Single Stage - One E IDA / D1830 Post Open - National 40,000.00 0.00 Canceled 2019-09-07 2019-11-02 2020-01-31 Q / M and E Satisfaction Surv ogram Management tions nvelope ey MH-PREP II-PIU-81925-NC-RF Component 4: Project and Pr Request for Quota Single Stage - One E IDA / D1830 Post Open - National 150,000.00 26,050.00 Signed 2019-07-05 2019-08-30 2021-10-06 2019-10-29 Q / PIU IT Support ogram Management tions nvelope MH-PREP II-PIU-81924-NC-RF Component 4: Project and Pr Request for Quota Single Stage - One E IDA / D1830 Post Open - National 20,000.00 0.00 Canceled 2019-10-05 2019-11-30 2019-12-30 Q / Translation Services ogram Management tions nvelope MH-PREP II-PIU-81919-NC-RF Component 2: Strengthening Request for Quota Open - Internationa Single Stage - One E IDA / D1830 Post 250,000.00 0.00 Canceled 2020-04-05 2020-05-31 2020-11-27 Q / UXO Removal Services Coastal Resilience tions l nvelope CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MH-PREP II-PIU-83435-CS-QC Component 2: Strengthening Quality And Cost- Open - Internationa BS / Coastal Engineering Desi IDA / D1830 Prior 3,210,000.00 2,897,518.50 Signed 2018-10-30 2019-01-14 2018-11-20 2019-01-30 2019-01-03 2019-11-05 2019-01-31 2020-02-17 2019-03-02 2020-04-06 2019-04-06 2020-09-07 2019-05-11 2020-10-25 2021-04-30 Coastal Resilience Based Selection l gn & Supervision Firm MH-PREP II-PIU-81918-CS-UN Component 1: Institutional S UN Agencies (Dire / Community DRM and Emerg IDA / D1830 trengthening, Early Warning Prior Direct 500,000.00 500,000.00 Signed 2020-01-09 2021-06-06 2021-12-29 ct) ency Communications Traini and Preparedness ng (IOM-UN) Component 1: Institutional S MH-PREP II-PIU-81916-CS-CQ Consultant Qualifi Open - Internationa IDA / D1830 trengthening, Early Warning Post 190,000.00 0.00 Canceled 2018-11-30 2018-12-21 2019-02-03 2018-11-06 2019-03-05 2019-04-09 2019-08-07 S / NDMO Building Design cation Selection l and Preparedness MH-PREP II-PIU-119121-CS-C Component 1: Institutional S Consultant Qualifi Open - Internationa QS / NDMO Structural Analysi IDA / D1830 trengthening, Early Warning Post 190,000.00 0.00 Canceled 2019-06-30 2019-07-21 2019-09-03 2019-10-03 2019-11-07 2020-05-05 cation Selection l s and Refurbishment Design and Preparedness MH-PREP II-PIU-163827-CS-C Component 1: Institutional S Consultant Qualifi QS / NAP Community Consult IDA / D1830 trengthening, Early Warning Prior Limited 500,000.00 0.00 Under Review 2020-05-05 2021-04-11 2020-05-19 2021-09-21 2020-06-18 2022-04-19 2020-07-23 2021-01-19 cation Selection ation and Preparedness MH-PREP II-PIU-110299-CS-C Component 4: Project and Pr Consultant Qualifi IDA / D1830 Post Limited 300,000.00 218,501.11 Signed 2020-04-16 2021-05-31 2020-04-30 2021-09-29 2020-05-30 2022-05-27 2020-07-04 2022-07-26 2020-12-31 QS / Communications and Me ogram Management cation Selection dia Firm MH-PREP II-PIU-217361-CS-Q CBS / Design of New NDMO Component 1: Institutional S Quality And Cost- Open - Internationa Warehouse and Office Accom IDA / D1830 trengthening, Early Warning Prior 550,000.00 0.00 Signed 2021-02-05 2021-09-16 2021-02-26 2021-11-30 2021-04-11 2022-05-01 2021-05-09 2022-06-23 2021-06-08 2022-09-27 2021-07-13 2023-02-12 2021-08-17 2023-03-29 2022-08-17 Based Selection l modation and Structural Anal and Preparedness ysis of the Existing NDMO Bui lding MH-PREP II-PIU-163844-CS-Q Component 1: Institutional S Quality And Cost- Open - Internationa CBS / Vulnerability and Planni IDA / D1830 trengthening, Early Warning Prior 600,000.00 0.00 Canceled 2020-03-17 2020-04-07 2020-05-21 2020-06-18 2020-07-18 2020-08-22 2020-09-26 2021-09-26 Based Selection l ng Consultancy Firm and Preparedness MH-PREP II-PIU-303510-CS-C Component 1: Institutional S Consultant Qualifi Open - Internationa QS / Vulnerability and Planni IDA / D1830 trengthening, Early Warning Prior 500,000.00 0.00 Signed 2022-07-24 2022-07-30 2022-08-14 2022-09-06 2022-09-27 2022-11-09 2022-10-27 2023-04-02 2022-12-01 2023-05-30 cation Selection l ng Consultancy Firm and Preparedness MH-PREP II-PIU-163825-CS-C Component 1: Institutional S Consultant Qualifi Open - Internationa QS / Community Vulnerability IDA / D1830 trengthening, Early Warning Post 250,000.00 0.00 Canceled 2020-05-03 2020-05-24 2020-07-07 2020-08-06 2020-09-10 2021-03-09 cation Selection l Mapping and Training and Preparedness MH-PREP II-PIU-163847-CS-C Component 1: Institutional S Consultant Qualifi Open - Internationa QS / Climate Financing Techn IDA / D1830 trengthening, Early Warning Post 200,000.00 0.00 Canceled 2023-06-01 2023-06-22 2023-08-05 2023-09-04 2023-10-09 2024-04-06 cation Selection l ical Assistance and Preparedness INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MH-PREP II-PIU-81917-CS-CD Component 2: Strengthening S / Coastal Vulnerability Asse IDA / D1830 Prior Direct Selection Direct 500,000.00 592,782.00 Signed 2019-04-04 2019-10-02 2019-04-14 2019-12-10 2019-06-18 2020-03-21 2020-01-10 Coastal Resilience ssment Firm MH-PREP II-PIU-81834-CS-IN Component 1: Institutional S Individual Consult DV / Emergency Communicat IDA / D1830 trengthening, Early Warning Post Open 120,000.00 64,425.00 Terminated 2019-04-30 2019-06-14 2019-06-18 2019-09-19 2019-07-09 2019-11-01 2019-08-13 2019-11-21 2020-06-08 ant Selection ion Specialist and Preparedness MH-PREP II-PIU-81915-CS-CD Component 2: Strengthening IDA / D1830 Prior Direct Selection Direct 50,000.00 0.00 Canceled 2018-11-16 2018-11-26 2019-01-30 2022-11-10 S / Coastal Design Adviser Coastal Resilience Component 1: Institutional S MH-PREP II-PIU-81927-CS-IN Individual Consult IDA / D1830 trengthening, Early Warning Post Open 480,000.00 0.00 Canceled 2018-10-15 2018-12-03 2018-12-24 2019-01-28 2021-01-17 DV / DRM and CCA Adviser ant Selection and Preparedness MH-PREP II-PIU-81928-CS-IN Component 1: Institutional S Individual Consult DV / Disaster and Climate Ris IDA / D1830 trengthening, Early Warning Post Open 202,500.00 0.00 Canceled 2018-10-15 2018-12-03 2018-12-24 2019-01-28 2021-01-17 ant Selection k Governance Adviser and Preparedness MH-PREP II-PIU-81926-CS-IN Component 2: Strengthening Individual Consult IDA / D1830 Post Limited 180,000.00 0.00 Canceled 2018-12-28 2019-01-02 2019-01-23 2019-02-27 2019-08-26 DV / Ebeye Project Represent Coastal Resilience ant Selection ative Component 1: Institutional S MH-PREP II-PIU-109655-CS-I Individual Consult IDA / D1830 trengthening, Early Warning Prior Open 324,000.00 648,000.00 Signed 2018-05-01 2018-01-03 2018-06-19 2018-08-24 2018-07-10 2018-09-27 2018-08-24 2018-10-01 2020-12-31 NDV / DRM&CCA Adviser ant Selection and Preparedness MH-PREP II-PIU-109653-CS-I Component 4: Project and Pr Individual Consult IDA / D1830 Prior Open 720,000.00 790,313.00 Signed 2017-02-14 2016-11-30 2017-03-28 2017-03-24 2017-04-20 2017-05-01 2017-05-01 2017-05-02 2020-05-14 NDV / Project Manager ogram Management ant Selection MH-PREP II-PIU-109656-CS-I Component 2: Strengthening Individual Consult IDA / D1830 Post Open 80,280.00 80,280.00 Completed 2018-04-18 2018-05-31 2018-06-06 2018-05-24 2018-06-27 2018-05-24 2018-07-31 2018-08-04 2020-07-01 2020-01-13 NDV / Ebeye Project Represe Coastal Resilience ant Selection ntative MH-PREP II-PIU-109654-CS-I Component 1: Institutional S Individual Consult NDV / Disaster and Climate R IDA / D1830 trengthening, Early Warning Prior Open 206,750.00 602,200.00 Signed 2018-04-01 2018-02-01 2018-05-20 2019-08-06 2018-06-10 2018-09-14 2018-07-13 2018-09-16 2020-08-31 ant Selection isk Governance Adviser and Preparedness Page 2 MH-PREP II-PIU-81838-CS-IN Component 4: Project and Pr Individual Consult DV / Communications & Medi IDA / D1830 Prior Open 240,000.00 0.00 Canceled 2018-11-30 2019-01-18 2019-02-08 2019-03-15 2021-03-04 ogram Management ant Selection a Specialist MH-PREP II-PIU-110300-CS-I Component 1: Institutional S Individual Consult NDV / Strategic Emergency C IDA / D1830 trengthening, Early Warning Post Open 80,000.00 135,100.00 Signed 2019-07-30 2019-06-14 2019-09-17 2019-09-19 2019-10-08 2019-11-01 2019-11-12 2019-11-25 2020-05-10 2022-07-08 ant Selection ommunications Adviser and Preparedness MH-PREP II-PIU-81832-CS-IN Component 4: Project and Pr Individual Consult IDA / D1830 Post Open 30,000.00 0.00 Canceled 2020-03-01 2020-04-19 2020-05-10 2020-06-14 2020-08-13 DV / Mid-term Reviewer ogram Management ant Selection MH-PREP II-PIU-81841-CS-IN Component 2: Strengthening Individual Consult IDA / D1830 Post Open 150,000.00 0.00 Canceled 2019-09-30 2020-02-18 2019-11-18 2019-12-09 2020-01-13 2020-07-11 DV / Value Engineering Coastal Resilience ant Selection MH-PREP II-PIU-137152-CS-I Component 4: Project and Pr Individual Consult IDA / D1830 Prior Open 480,000.00 13,022.00 Terminated 2020-05-16 2020-02-17 2020-07-04 2020-05-14 2020-07-25 2020-08-02 2020-08-29 2020-08-11 2021-02-25 NDV / Project Manager Post 2 ogram Management ant Selection 020 MH-PREP II-PIU-109652-CS-I Component 2: Strengthening Individual Consult IDA / D1830 Post Open 470,000.00 470,000.00 Signed 2017-10-25 2017-10-31 2017-11-01 2017-11-07 2017-11-19 2017-11-15 2017-12-20 2018-01-10 2020-01-31 NDV / Original Civil Engineeri Coastal Resilience ant Selection ng Advisor MH-PREP II-PIU-160075-CS-C Component 2: Strengthening IDA / D1830 Post Direct Selection Direct 150,000.00 154,975.00 Signed 2020-02-19 2020-03-05 2020-02-24 2020-04-17 2020-04-29 2020-06-21 2021-10-31 DS / Value Engineering Firm Coastal Resilience MH-PREP II-PIU-110298-CS-I Component 4: Project and Pr Individual Consult NDV / Local Communications IDA / D1830 Post Open 230,000.00 112,879.67 Terminated 2020-03-19 2020-05-19 2020-05-07 2020-09-14 2020-05-28 2020-10-15 2020-07-02 2020-11-08 2020-12-29 ogram Management ant Selection and M & E Officer MH-PREP II-PIU-81835-CS-IN Component 2: Strengthening Individual Consult IDA / D1830 Post Open 80,000.00 0.00 Canceled 2020-04-01 2020-05-20 2020-06-10 2020-07-15 2021-07-10 DV / Work Probity Assurance Coastal Resilience ant Selection Provider Component 1: Institutional S MH-PREP II-PIU-163845-CS-I Individual Consult IDA / D1830 trengthening, Early Warning Post Open 100,000.00 0.00 Canceled 2020-05-02 2021-03-23 2020-06-20 2020-07-11 2020-08-15 2021-02-11 NDV / NAP Coordinator ant Selection and Preparedness MH-PREP II-PIU-163848-CS-I Component 1: Institutional S Individual Consult NDV / Donor Coordination Te IDA / D1830 trengthening, Early Warning Prior Open 400,000.00 0.00 Canceled 2020-12-21 2021-02-08 2021-03-01 2021-04-05 2021-10-02 ant Selection chnical Assistance and Preparedness MH-PREP II-PIU-137154-CS-I Component 2: Strengthening Individual Consult NDV / Ebeye Project Represe IDA / D1830 Post Limited 100,000.00 0.00 Canceled 2020-07-01 2020-07-06 2020-07-27 2020-08-31 2021-02-27 Coastal Resilience ant Selection ntative Post 2020 MH-PREP II-PIU-81837-CS-IN Component 4: Project and Pr Individual Consult IDA / D1830 Post Open 180,000.00 0.00 Canceled 2019-07-30 2019-09-23 2019-09-17 2019-10-08 2019-11-12 2023-07-22 DV / Project Officer ogram Management ant Selection MH-PREP II-PIU-135263-CS-I Component 4: Project and Pr Individual Consult IDA / D1830 Post Open 190,000.00 0.00 Canceled 2019-09-27 2019-12-02 2019-11-15 2019-12-06 2020-01-10 2020-07-08 NDV / Implementation Suppo ogram Management ant Selection rt Specialist MH-PREP II-PIU-119120-CS-I Component 1: Institutional S Individual Consult NDV / Civil Engineering Advis IDA / D1830 trengthening, Early Warning Prior Open 470,000.00 0.00 Canceled 2019-08-19 2020-02-10 2019-10-07 2019-10-28 2019-12-02 2020-05-30 ant Selection er and Preparedness MH-PREP II-PIU-165685-CS-I Component 4: Project and Pr Individual Consult IDA / D1830 Post Open 255,000.00 70,000.00 Signed 2020-04-17 2019-12-16 2020-06-05 2020-06-09 2020-06-26 2020-06-09 2020-07-31 2020-06-10 2021-01-27 NDV / Project Officer ogram Management ant Selection MH-PREP II-PIU-165691-CS-I Component 4: Project and Pr Individual Consult IDA / D1830 Post Open 305,000.00 180,000.00 Terminated 2019-12-15 2019-12-01 2020-02-02 2020-01-09 2020-02-23 2020-02-01 2020-03-29 2020-02-15 2020-09-25 NDV / Implementation Suppo ogram Management ant Selection rt Specialist MH-PREP II-PIU-165694-CS-I Component 1: Institutional S Individual Consult NDV / Civil Engineering Advis IDA / D1830 trengthening, Early Warning Prior Open 770,000.00 734,375.00 Signed 2020-03-23 2020-05-06 2020-05-11 2020-04-24 2020-06-01 2020-07-27 2020-07-06 2020-08-05 2021-01-02 ant Selection er and Preparedness MH-PREP II-PIU-163846-CS-I Component 1: Institutional S Individual Consult NDV / Climate Change Adapt IDA / D1830 trengthening, Early Warning Prior Open 300,000.00 303,000.00 Terminated 2020-05-02 2020-05-06 2020-06-20 2020-07-09 2020-07-11 2020-08-11 2020-08-15 2020-08-19 2021-02-11 ant Selection ation Specialist and Preparedness MH-PREP II-PIU-202148-CS-C Component 4: Project and Pr IDA / D1830 Prior Direct Selection Direct 480,000.00 442,000.00 Signed 2020-10-30 2020-11-20 2020-11-03 2020-12-01 2020-11-06 2021-01-12 2022-11-05 DS / PREP II Project Manager ogram Management 2021 MH-PREP II-PIU-205222-CS-C Component 4: Project and Pr DS / Project Management Su IDA / D1830 Prior Direct Selection Direct 86,820.00 82,200.00 Signed 2020-11-20 2020-12-22 2020-11-30 2021-02-09 2020-12-15 2021-03-10 2021-06-13 ogram Management pport Specialist Component 1: Institutional S MH-PREP II-PIU-234808-CS-C IDA / D1830 trengthening, Early Warning Post Direct Selection Direct 100,000.00 83,625.00 Signed 2021-05-22 2021-07-01 2021-06-01 2021-08-23 2021-08-05 2021-09-06 2022-02-01 DS / NAP Coordinator and Preparedness MH-PREP II-PIU-246795-CS-I Component 1: Institutional S Individual Consult NDV / Disaster and Climate R IDA / D1830 trengthening, Early Warning Prior Open 400,000.00 0.00 Signed 2021-08-09 2021-10-11 2021-09-27 2022-03-30 2021-10-18 2022-04-23 2021-11-22 2023-05-21 2022-05-21 ant Selection esilience Donor Coordination and Preparedness Adviser Component 1: Institutional S MH-PREP II-PIU-81836-CS-IN Individual Consult IDA / D1830 trengthening, Early Warning Post Open 60,000.00 0.00 Signed 2019-04-28 2022-06-23 2019-06-16 2023-02-19 2019-07-07 2023-02-19 2019-08-11 2019-11-09 DV / DRM Legislative Drafter ant Selection and Preparedness MH-PREP II-PIU-228529-CS-I Component 1: Institutional S Individual Consult NDV / Donor Coordination Te IDA / D1830 trengthening, Early Warning Prior Direct 400,000.00 0.00 Canceled 2021-04-30 2021-08-16 2021-05-10 2021-05-31 2021-07-05 2022-01-01 ant Selection chnical Assistance and Preparedness MH-PREP II-PIU-257808-CS-I Component 4: Project and Pr Individual Consult NDV / Implementation Suppo IDA / D1830 Post Open 190,000.00 0.00 Signed 2021-10-31 2022-02-03 2021-12-19 2022-11-10 2022-01-09 2022-07-13 2022-02-13 2022-08-12 ogram Management ant Selection rt Specialist 2022 MH-PREP II-PIU-81840-CS-IN Component 2: Strengthening Individual Consult IDA / D1830 Post Open 120,000.00 0.00 Canceled 2019-11-30 2020-01-18 2020-02-08 2020-03-14 2020-09-10 DV / Contracts Disputes Boar Coastal Resilience ant Selection d Member MH-PREP II-PIU-301513-CS-I Component 1: Institutional S NDV / Senior Emergency Co Individual Consult IDA / V0410 trengthening, Early Warning Post Direct 80,000.00 0.00 Signed 2022-07-08 2022-07-14 2022-07-18 2022-08-11 2022-08-08 2022-08-16 2022-09-12 2023-03-11 mmunications Network Com ant Selection and Preparedness missioning Specialist MH-PREP II-PIU-137153-CS-I Component 1: Institutional S Individual Consult NDV / DRM&CCA Adviser pos IDA / D1830 trengthening, Early Warning Prior Open 324,000.00 0.00 Canceled 2021-01-01 2021-02-19 2021-03-12 2021-04-16 2021-10-13 ant Selection t 2020 and Preparedness Page 3 MH-PREP II-PIU-327141-CS-C Component 1: Institutional S Direct - Internation DS / Climate Change Adaptat IDA / D1830 trengthening, Early Warning Post Direct Selection 210,000.00 0.00 Canceled 2022-11-23 2022-12-02 2022-12-03 2022-12-20 2023-02-06 2023-08-05 al ion Specialist 2023 and Preparedness MH-PREP II-PIU-301516-CS-I Component 1: Institutional S NDV / Junior Emergency Com Individual Consult IDA / D1830 trengthening, Early Warning Post Open 50,000.00 0.00 Canceled 2022-10-01 2022-11-19 2022-12-10 2023-01-14 2023-07-13 munications Network Commi ant Selection and Preparedness ssioning Specialist MH-PREP II-PIU-347593-CS-I Component 4: Project and Pr Individual Consult NDV / Communication and M IDA / D1830 Post Open - National 30,000.00 0.00 Canceled 2023-03-07 2023-02-13 2023-04-25 2023-05-02 2023-05-16 2023-06-20 2023-12-17 ogram Management ant Selection onitoring & Evaluations Offic er MH-PREP II-PIU-81831-CS-IN Component 1: Institutional S Individual Consult Open - Internationa DV / Change Management Ad IDA / D1830 trengthening, Early Warning Prior 480,000.00 0.00 Canceled 2018-11-30 2019-01-18 2019-02-08 2019-03-15 2021-03-04 ant Selection l visor and Preparedness MH-PREP II-PIU-327137-CS-C Component 1: Institutional S DS / Disaster and Climate Re Direct - Internation IDA / D1830 trengthening, Early Warning Post Direct Selection 210,000.00 0.00 Canceled 2022-11-23 2022-12-02 2022-12-03 2022-12-19 2023-02-06 2023-08-05 silience Donor Coordination A al and Preparedness dviser (DCR-DCA) 2023 MH-PREP II-PIU-327141-CS-C Component 1: Institutional S Direct - Internation DS-2 / Climate Change Adapt IDA / D1830 trengthening, Early Warning Post Direct Selection 210,000.00 0.00 Signed 2023-03-16 2023-01-17 2023-03-26 2023-01-17 2023-05-30 2023-11-26 al ation Specialist 2023 and Preparedness MH-PREP II-PIU-362384-CS-I Component 4: Project and Pr Individual Consult Under Implement IDA / D1830 Post Open - National 20,000.00 0.00 2023-05-26 2023-05-19 2023-07-14 2023-08-04 2023-09-08 2024-03-06 NDV / Project Officer 2023 ogram Management ant Selection ation MH-PREP II-PIU-362549-CS-I Component 4: Project and Pr Individual Consult Open - Internationa Under Implement IDA / D1830 Post 60,000.00 0.00 2023-05-26 2023-05-19 2023-07-14 2023-08-04 2023-09-08 2024-03-06 NDV / Financial Management ogram Management ant Selection l ation Specialist MH-PREP II-PIU-81839-CS-IN Component 4: Project and Pr Individual Consult Open - Internationa Pending Impleme IDA / D1830 Post 30,000.00 0.00 2023-09-01 2023-10-20 2023-11-10 2023-12-15 2024-06-12 DV / End Term Reviewer ogram Management ant Selection l ntation MH-PREP II-PIU-365763-CS-I Component 1: Institutional S NDV / Junior Emergency Com Individual Consult Open - Internationa Under Implement IDA / D1830 trengthening, Early Warning Post 84,000.00 0.00 2023-06-16 2023-06-20 2023-08-04 2023-08-25 2023-09-29 2024-03-27 munications Network Commi ant Selection l ation and Preparedness ssioning Specialist Page 4 PROCUREMENT PLAN Project information: Papua New Guinea, Energy Utility Performance and Reliability Improvement Project (EUPRIP), P167820 Project Implementation agency: PNG Power Limited (PPL) Date of the Procurement Plan: July 2019 Period covered by this Procurement Plan: July 2019 – December 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in National Procurement Act 2018 (came into operation April 1, 2019) and the Public Finance Management Act (1995 as amended), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable Other Relevant Procurement Information. Not Applicable PROCUREMENT Papua New Guinea : Energy Utility Performance and Reliability Improvement Project PLAN General Information Country: Papua New Guinea 2019-07-22 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167820 GPN Date: 2021-09-02 Project Name: Energy Utility Performance and Reliability Improvement Project Loan / Credit No: IBRD / 92120, / PNG Power Limited Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-PPL-157606-GO-RFB / DE SIGN, SUPPLY, AND INSTALLA Implementation of key comp TION OF ADVANCED METERI Open - Internationa Single Stage - One E Under Imple IBRD / 92120 onents of PPL's Performance Prior Request for Bids 3,000,000.00 0.00 2020-03-17 2020-06-30 2020-03-22 2020-11-09 2020-05-03 2021-06-09 2020-06-02 2022-11-23 2020-07-07 2021-01-03 NG INFRASTRUCTURE (AMI) S l nvelope mentation Improvement Plan YSTEMS TO SUPPORT REVEN UE RECOVERY AND PROTECT ION PROGRAMS NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-PPL-123839-CS-QCBS-01- Project management suppor Quality And Cost- Open - Internationa Pending Impleme 2019 / Owner’s Engineer for r / Prior 500,000.00 0.00 2019-07-30 2019-08-20 2019-10-03 2019-11-15 2019-12-15 2020-01-19 2020-02-23 2021-02-22 t Based Selection l ntation ehabilitation/upgrade of PPL I nfraestructure INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-PPL-123835-CS-INDV-02- Project management suppor Individual Consult 2019 / Financial Management IBRD / 92120 Prior Open 300,000.00 0.00 Canceled 2019-07-22 2019-08-16 2019-09-12 2019-10-03 2019-11-07 2020-11-11 t ant Selection Specialist PG-PPL-123836-CS-INDV-01- Project management suppor Individual Consult Pending Impleme / Prior Open 750,000.00 0.00 2019-07-30 2019-09-07 2019-09-28 2019-11-02 2020-11-11 2019 / Project Manager t ant Selection ntation PG-PPL-123837-CS-INDV-03- Project management suppor Individual Consult IBRD / 92120 Prior Open 300,000.00 0.00 Canceled 2019-07-26 2019-08-16 2019-09-13 2019-10-04 2019-11-08 2020-11-08 2019 / Procurement Specialis t ant Selection t PG-PPL-205423-CS-QCBS / R Implementation of key comp Individual Consult evenue protection program s IBRD / 92120 onents of PPL's Performance Post Open 200,000.00 172,529.83 Signed 2020-11-24 2020-11-25 2021-01-12 2021-05-26 2021-01-17 2021-05-27 2021-01-20 2021-05-29 2022-01-20 ant Selection pecialist Improvement Plan PG-PPL-326341-CS-INDV / En Project management suppor Individual Consult Open - Internationa Under Implement vironmental and Social Safeg IBRD / 92120 Post 250,000.00 0.00 2023-02-10 2023-04-20 2023-03-31 2023-04-14 2023-05-19 2023-11-15 t ant Selection l ation uard Specialist PG-PPL-PROCUREMENT SPEC Project management suppor Individual Consult Open - Internationa Under Implement IBRD / 92120 Post 300,000.00 0.00 2023-02-22 2023-03-14 2023-04-12 2023-05-03 2023-06-07 2024-06-07 -INDV - 2023 / Procurement S t ant Selection l ation pecialist PG-PPL-FMS-CS-INDV - 2023 Project management suppor Individual Consult Open - Internationa IBRD / 92120 Post 300,000.00 0.00 Canceled 2023-02-22 2023-02-27 2023-04-15 2023-05-06 2023-06-10 2024-06-14 / Financial Management Spec t ant Selection l ialist PG-PPL-364107-CS-INDV / Fi Project management suppor Individual Consult Under Implement IBRD / 92120 Post Open - National 210,000.00 0.00 2023-06-04 2023-05-31 2023-07-23 2023-08-13 2023-09-17 2024-09-16 nancial Management Speciali t ant Selection ation st Page 1 Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: February 2020] 2. Period covered by this procurement plan: The procurement period of project covered from year February 2020 till June 2020. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 1.5 All million 2. NCB (Goods) Above US$ 1.5 All million 3. ICB (Works) Above US$ 5 million All 4. NCB (Works) Above US$ 5 million All 2. Prequalification. Bidders for works activities shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 4. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) Refer to PP. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 0.5 million 2. Single Source (Firms) All 3. Individual Above US$ 0.2 million 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods and Time Schedule Refer to PP PROCUREMENT Lebanon : Lebanon Health Resilience Project PLAN General Information Country: Lebanon 2020-02-15 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163476 GPN Date: 2020-06-08 Project Name: Lebanon Health Resilience Project Loan / Credit No: IBRD / 87710 Ministry of Public Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOPH-RFQ-COVID19-001 / Pr Strengthen the Government’ Request for Quota IBRD / 87710 Prior 1,500,000.00 68,815.00 Signed 2019-03-18 2019-03-18 2020-04-28 2019-03-18 ocurement of PPEs s capacity to respond to CO tions VID-19 MOPH-RFQ-COVID19-002 / Pr Strengthen the Government’ Request for Quota IBRD / 87710 Prior 2,000,000.00 1,638,696.38 Signed 2019-03-18 2019-03-18 2020-04-16 2019-03-18 ocurement of Ventilators s capacity to respond to CO tions VID-19 MOPH-DS-COVID19-004 / PR Strengthen the Government’ IBRD / 87710 Post Direct Selection Direct 400,000.00 0.00 Canceled 2020-04-16 2020-04-15 2020-04-21 2020-05-26 2020-11-22 OCUREMEMT OF RAPID TEST s capacity to respond to CO KITS VID-19 LB-MOPH-RFQ005 / Procure Strengthen the Government’ Request for Quota Single Stage - One E ment of Goods for Negative P IBRD / 87710 s capacity to respond to CO Post Open - National 60,000.00 45,065.00 Signed 2020-12-19 2020-12-18 2021-02-13 2021-01-15 2021-08-12 tions nvelope ressure Rooms VID-19 LB-MOPH-RFQ003 / Procure Strengthen the Government’ Request for Quota Single Stage - One E IBRD / 87710 Post Limited 450,000.00 151,766.00 Signed 2020-12-19 2020-12-24 2021-02-13 2020-12-29 2021-08-12 ment of COVID-19 Related Eq s capacity to respond to CO tions nvelope uipment VID-19 LB-MOPH-RFQ004 / Procure Strengthen the Government’ Request for Quota Single Stage - One E IBRD / 87710 Post Limited 450,000.00 74,551.00 Signed 2020-12-19 2021-01-19 2021-02-13 2021-04-15 2021-08-12 ment of COVID-19 Related Eq s capacity to respond to CO tions nvelope uipment VID-19 LB-MOPH-DS001 / Procurem Strengthen the Government’ ent of a UPS system for COVI IBRD / 87710 s capacity to respond to CO Post Direct Selection Direct 20,000.00 79,464.81 Signed 2021-01-08 2021-03-23 2021-01-13 2021-03-23 2021-02-17 2021-04-30 2021-08-16 D-19 unit at Qana Hospital VID-19 LB-MOPH-NP004 / Installatio Strengthen the Government’ n of a Negative Pressure syst IBRD / 87710 s capacity to respond to CO Post Direct Selection Direct 40,000.00 0.00 Canceled 2021-01-19 2021-01-24 2021-02-28 2021-08-27 em at Al Bouwar hospital VID-19 LB-MOPH-PFIZER / Procurem Strengthen the Government’ IBRD / 87710 Prior Direct Selection Direct 18,000,000.00 39,012,960.00 Signed 2021-01-19 2021-02-12 2021-01-24 2021-02-12 2021-02-28 2021-01-18 2021-08-27 ent of COVID-19 Vaccine s capacity to respond to CO VID-19 LB-MOPH-NP001 / Installatio Strengthen the Government’ Request for Quota Single Stage - One E n of a Negative Pressure Syst IBRD / 87710 s capacity to respond to CO Post Limited 40,000.00 185,987.81 Signed 2021-02-01 2021-02-09 2021-03-29 2021-01-28 2021-09-25 tions nvelope em at Baabda Public Hospital VID-19 LB-MOPH-NP002 / Installatio Strengthen the Government’ Request for Quota Single Stage - One E n of a Negative Pressure Syst IBRD / 87710 s capacity to respond to CO Post Limited 20,000.00 178,831.00 Signed 2021-02-01 2021-02-09 2021-03-29 2021-01-29 2021-09-25 tions nvelope em at Jezzin Hospital VID-19 LB-MOPH-SD001 / Rehabilita Strengthen the Government’ Request for Quota Single Stage - One E tion of COVID-19 ICU Unit at IBRD / 87710 s capacity to respond to CO Post Limited 40,000.00 190,890.62 Signed 2021-02-06 2021-03-23 2021-04-03 2021-02-02 2021-09-30 tions nvelope Sir El Donnieh Public Hospital VID-19 LB-MOPH-NP003 / Installatio Strengthen the Government’ Request for Quota Single Stage - One E n of Negative Pressure at Bat IBRD / 87710 s capacity to respond to CO Post Limited 20,000.00 143,216.24 Signed 2021-02-11 2021-02-09 2021-04-08 2021-01-30 2021-10-05 tions nvelope roun Hospital VID-19 LB-MOPH-NP0010 / Installati Strengthen the Government’ Request for Quota Single Stage - One E on of Negative Pressure Syst IBRD / 87710 s capacity to respond to CO Post Limited 40,000.00 145,769.34 Signed 2021-02-11 2021-04-25 2021-04-08 2021-01-29 2021-10-05 tions nvelope em at Mays Al Jabal Hospital VID-19 LB-MOPH-NP005 / Installatio Strengthen the Government’ Request for Quota Single Stage - One E n of Negative Pressure Syste IBRD / 87710 s capacity to respond to CO Post Limited 40,000.00 209,447.08 Signed 2021-02-11 2021-02-09 2021-04-08 2021-01-29 2021-10-05 tions nvelope m at Marjeyoun Hospital VID-19 LB-MOPH-NP006 / Installatio Strengthen the Government’ Request for Quota Single Stage - One E n of Negative Pressure Syste IBRD / 87710 s capacity to respond to CO Post Limited 40,000.00 136,490.26 Signed 2021-02-11 2021-02-16 2021-04-08 2021-02-17 2021-10-05 tions nvelope m at Saida Hospital VID-19 LB-MOPH-NP007 / Installatio Strengthen the Government’ Request for Quota Single Stage - One E n of Negative Pressure Syste IBRD / 87710 s capacity to respond to CO Post Limited 30,000.00 163,133.63 Signed 2021-02-11 2021-02-09 2021-04-08 2021-01-29 2021-10-05 tions nvelope m at Al Chahhar Al Gharbi VID-19 LB-MOPH-NP008 / Installatio Strengthen the Government’ Request for Quota Single Stage - One E n of Negative Pressure Syste IBRD / 87710 s capacity to respond to CO Post Limited 30,000.00 122,087.36 Signed 2021-02-11 2021-02-10 2021-04-08 2021-01-30 2021-10-05 tions nvelope m at Bcharri Hospital VID-19 LB-MOPH-NP009 / Installatio Strengthen the Government’ Request for Quota Single Stage - One E n of Negative Pressure Syste IBRD / 87710 s capacity to respond to CO Post Limited 20,000.00 94,908.03 Signed 2021-02-11 2021-04-25 2021-04-08 2021-02-18 2021-10-05 tions nvelope m at Nabatiye Hospital VID-19 LB-MOPH-RFQ006 / Procure Strengthen the Government’ Request for Quota Open - Internationa Single Stage - One E ment of Pfizer Vaccine Relate IBRD / 87710 s capacity to respond to CO Post 1,000,000.00 675,350.00 Signed 2021-02-22 2021-02-24 2021-04-19 2021-04-28 2021-10-16 tions l nvelope d Accessories VID-19 LB-MOPH-RFQ007 / Procure Strengthen the Government’ Request for Quota Single Stage - One E IBRD / 87710 Post Open - National 500,000.00 520,111.61 Signed 2021-03-07 2021-03-03 2021-05-02 2021-07-27 2021-10-29 ment of Spare Parts for CT Sc s capacity to respond to CO tions nvelope an VID-19 LB-MOPH-RFQ008 / Procure Strengthen the Government’ Request for Quota Single Stage - One E IBRD / 87710 Post Open - National 350,000.00 356,270.00 Signed 2021-03-24 2021-04-06 2021-05-19 2021-06-09 2021-11-15 ment of Oxygen Related Equi s capacity to respond to CO tions nvelope pment VID-19 Page 1 LB-MOPH-RFQ009 / Procure Strengthen the Government’ Request for Quota Open - Internationa Single Stage - One E IBRD / 87710 Post 500,000.00 405,000.00 Signed 2021-04-10 2021-04-06 2021-06-05 2021-05-13 2021-12-02 ment of Accessories for Vacci s capacity to respond to CO tions l nvelope nes VID-19 LB-MOPH-RFQ010 / Installati Strengthen the Government’ Request for Quota Single Stage - One E Under Imple IBRD / 87710 Post Open - National 300,000.00 0.00 2021-04-14 2021-04-12 2021-06-09 2021-12-06 on of Negative Pressure Syst s capacity to respond to CO tions nvelope mentation ems VID-19 LB-MOPH-RFQ011 / Procure Strengthen the Government’ Request for Quota Open - Internationa Single Stage - One E Under Imple ment of CT Scan Spare Parts IBRD / 87710 s capacity to respond to CO Post 50,000.00 0.00 2021-04-30 2021-05-18 2021-06-25 2021-12-22 tions l nvelope mentation for Al Menyeh and Chebaa Pu VID-19 blic Hospitals LB-MOPH-SD002 / Installatio Strengthen the Government’ Request for Quota Single Stage - One E IBRD / 87710 Post Limited 30,000.00 14,740.00 Signed 2021-05-25 2021-02-01 2021-07-20 2021-02-16 2022-01-16 n of Oxygen Related Equipm s capacity to respond to CO tions nvelope ent VID-19 LB-MOPH-DS002 / Procurem Strengthen the Government’ ent of syringes for the vaccin IBRD / 87710 s capacity to respond to CO Post Direct Selection Direct 60,000.00 60,000.00 Signed 2021-08-05 2021-08-09 2021-08-10 2021-08-10 2021-09-14 2021-08-11 2022-03-13 ation process VID-19 LB-MOPH-RFQ012 / Procure Strengthening project mana Request for Quota Open - Internationa Single Stage - One E IBRD / 87710 Post 180,000.00 25,047.74 Signed 2021-09-26 2021-09-20 2021-11-21 2022-04-05 2022-05-20 ment of an accounting softw gement and monitoring tions l nvelope are LB-MOPH-RFQ014 / Procure Strengthening project mana Request for Quota Single Stage - One E Under Imple IBRD / 87710 Post Limited 2,000.00 0.00 2021-11-03 2021-11-23 2021-12-29 2022-06-27 ment of Office Equipment (La gement and monitoring tions nvelope mentation ptops) LB-MOPH-RFQ013 / Procure Strengthen the Government’ Request for Quota Single Stage - One E IBRD / 87710 Post Open - National 100,000.00 43,000.00 Signed 2021-11-03 2021-11-18 2021-12-29 2021-12-08 2022-06-27 ment of Vaccine Accessories s capacity to respond to CO tions nvelope VID-19 LB-MOPH-DS003 / Procurem Strengthen the Government’ IBRD / 87710 Post Direct Selection Direct 40,000.00 22,780.00 Signed 2022-01-31 2022-01-27 2022-02-05 2022-02-21 2022-03-12 2022-03-01 2022-09-08 ent of Spare Parts for Tebnin s capacity to respond to CO e Hospital VID-19 LB-MOPH-RFQ015 / Procure Strengthening project mana Request for Quota Single Stage - One E Pending Impl IBRD / 87710 Post Open - National 2,000.00 0.00 2022-11-06 2023-01-01 2023-06-30 ment of office equipment (La gement and monitoring tions nvelope ementation ptops) LB-MOPH-RFQ016 / Procure Strengthen the Government’ Request for Quota Single Stage - One E Under Imple IBRD / 87710 Post Open - National 30,000.00 0.00 2023-02-06 2023-02-07 2023-04-03 2023-09-30 ment of IT Equipment s capacity to respond to CO tions nvelope mentation VID-19 LB-MOPH-RFQ017 / Procure Strengthening project mana Request for Quota Single Stage - One E Under Imple IBRD / 87710 Post Open - National 25,000.00 0.00 2023-02-06 2023-02-07 2023-04-03 2023-09-30 ment of Helium Tanks gement and monitoring tions nvelope mentation LB-MOPH-RFQ018 / Procure Strengthen the Government’ Request for Quota Single Stage - One E Under Imple ment of Spare Parts for the El IBRD / 87710 s capacity to respond to CO Post Open - National 75,000.00 0.00 2023-03-15 2023-03-15 2023-05-10 2023-11-06 tions nvelope mentation evators at Al Nabatieh Public VID-19 Hospital NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LB-MOPH-164381-NC-UN / Pr Strengthen the Government’ UN Agencies (Dire ocurement of equipment and IBRD / 87710 s capacity to respond to CO Prior Direct 20,000,000.00 0.00 Canceled 2020-03-14 2020-03-19 2020-04-23 2020-10-20 ct) tools to respond to COVID-19 VID-19 LB-MOPH-164382-NC-WHO / Strengthen the Government’ UN Agencies (Dire Procurement of goods in resp IBRD / 87710 s capacity to respond to CO Prior Direct 6,000,000.00 5,562,071.99 Signed 2020-03-31 2020-04-01 2020-04-05 2020-04-01 2020-05-10 2020-04-04 2020-11-06 ct) onse to COVID19 VID-19 LB-MOPH-164385-NC-UNOPS Strengthen the Government’ UN Agencies (Dire / Procurement of PPEs and Eq IBRD / 87710 s capacity to respond to CO Prior Direct 9,500,000.00 5,742,367.72 Signed 2020-03-15 2020-04-01 2020-03-15 2020-04-03 2020-03-15 2020-04-03 2020-03-15 ct) uipments VID-19 LB-MOPH-RFQ019 / Procure Strengthening project mana Request for Quota Single Stage - One E Under Imple IBRD / 87710 Post Open - National 15,000.00 0.00 2023-04-15 2023-04-11 2023-06-10 2023-12-07 ment of an Antivirus Softwar gement and monitoring tions nvelope mentation e LB-MOPH-RFQ020 / Maintena Strengthening project mana Request for Quota Single Stage - One E Under Imple nce, Support and Update of t IBRD / 87710 Post Open - National 30,000.00 0.00 2023-05-27 2023-06-05 2023-07-22 2024-01-18 gement and monitoring tions nvelope mentation he Ministry Mobile Applicatio n LB-MOPH-RFQ021 / Provision Strengthening project mana Request for Quota Single Stage - One E Under Imple IBRD / 87710 Post Open - National 10,000.00 0.00 2023-06-06 2023-06-12 2023-08-01 2024-01-28 of SMS Services gement and monitoring tions nvelope mentation LB-MOPH-RFQ022 / Provision Strengthening project mana Request for Quota Single Stage - One E Pending Impl IBRD / 87710 Post Open - National 20,000.00 0.00 2023-06-12 2023-08-07 2024-02-03 of Landline Internet Services gement and monitoring tions nvelope ementation CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LB-MOPH-159410-CS-QCBS / Strengthening project mana Quality And Cost- Open - Internationa IBRD / 87710 Prior 540,000.00 990,766.00 Signed 2020-02-14 2020-02-17 2020-03-06 2020-02-18 2020-04-19 2020-08-11 2020-05-17 2020-10-28 2020-06-16 2020-11-05 2020-07-21 2021-01-04 2020-08-25 2020-12-30 2021-08-25 Third-party agent gement and monitoring Based Selection l LB-MOPH-197566-CS-LCS / F Strengthening project mana Least Cost Selecti Open - Internationa IBRD / 87710 Post 36,000.00 50,870.00 Signed 2020-10-03 2020-10-02 2020-10-24 2020-10-07 2020-12-07 2021-03-31 2021-01-04 2021-07-02 2021-02-03 2021-06-05 2021-03-10 2021-06-23 2021-04-14 2021-08-13 2021-10-11 inancial Auditor gement and monitoring on l LB-MOPH-ICS-004 / Hiring of Strengthening project mana Consultant Qualifi Under Implement an Environmental and Social IBRD / 87710 Post Limited 18,000.00 0.00 2022-11-01 2022-11-08 2022-11-15 2023-02-01 2022-12-15 2023-01-19 2023-07-18 gement and monitoring cation Selection ation Specialist and Grievance Mec hanism Officer INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HR-001-PROJECT MANAGER / Strengthening project mana IBRD / 87710 Post Direct Selection Direct 42,000.00 42,000.00 Signed 2020-05-14 2020-06-30 2020-05-24 2020-07-14 2020-07-28 2020-07-02 2021-01-24 Project Manager gement and monitoring HR-003-MONITORING AND E Strengthening project mana Individual Consult Under Implement IBRD / 87710 Post Limited 26,400.00 0.00 2020-06-12 2020-07-13 2020-06-17 2020-08-28 2020-07-08 2020-08-28 2020-08-12 2021-02-08 VALUATION / Monitoring and gement and monitoring ant Selection ation evaluation Page 2 HR-004-FINANCIAL OFFICER Strengthening project mana IBRD / 87710 Post Direct Selection Direct 26,400.00 55,440.00 Signed 2020-05-16 2020-07-13 2020-05-26 2020-07-14 2020-07-30 2020-07-02 2021-01-26 / Financial officer gement and monitoring HR-005-TRAINING AND COM Strengthening project mana Individual Consult Under Implement MUNICATION / Training and c IBRD / 87710 Post Limited 21,600.00 0.00 2020-06-12 2020-07-13 2020-06-17 2020-07-08 2020-08-12 2021-02-08 gement and monitoring ant Selection ation ommunication coordinator HR-006-OPERATIONS ASSIST Strengthening project mana Individual Consult IBRD / 87710 Post Limited 21,600.00 43,380.00 Signed 2020-06-12 2020-07-13 2020-06-17 2020-08-04 2020-07-08 2020-08-04 2020-08-12 2020-08-02 2021-02-08 ANT / Operations assistant gement and monitoring ant Selection LB-MOPH-188195-CS-CDS / T Strengthen the Government’ IBRD / 87710 Post Direct Selection Direct 10,000.00 204,620.70 Signed 2020-08-19 2020-09-02 2020-08-29 2020-09-03 2020-11-02 2020-08-27 2021-05-01 echnical audit for covid-19 co s capacity to respond to CO verage VID-19 LB-MOPH-191340-CS-INDV / Strengthening project mana Individual Consult IBRD / 87710 Post Limited 15,600.00 29,900.00 Signed 2020-09-02 2020-09-02 2020-09-07 2020-09-03 2020-09-28 2020-09-03 2020-11-02 2020-09-02 2021-05-01 Administrative Assistant gement and monitoring ant Selection LB-MOPH-191343-CS-INDV / Strengthening project mana Individual Consult IBRD / 87710 Post Limited 20,400.00 20,400.00 Signed 2020-09-02 2020-09-03 2020-09-07 2020-09-03 2020-09-28 2020-09-03 2020-11-02 2020-09-02 2021-05-01 Monitoring and Evaluation gement and monitoring ant Selection LB-MOPH-201928-CS-INDV / Strengthening project mana Individual Consult IBRD / 87710 Post Limited 18,000.00 0.00 Canceled 2020-10-28 2020-11-02 2020-11-02 2020-11-23 2020-12-28 2021-06-26 IT Analyst gement and monitoring ant Selection LB-MOPH-202741-CS-INDV / Strengthening project mana Individual Consult IBRD / 87710 Post Open 18,000.00 0.00 Canceled 2020-11-04 2020-11-05 2020-12-23 2021-01-13 2021-02-17 2021-08-16 IT Analyst gement and monitoring ant Selection LB-MOPH-ICM-001 / Selectio Strengthen the Government’ Pending Impleme IBRD / 87710 Post Direct Selection Direct 2,250.00 0.00 2020-11-27 2020-12-07 2021-02-10 2021-08-09 n of Isolation Center Manager s capacity to respond to CO ntation VID-19 LB-MOPH-ICM-002 / Selectio Strengthen the Government’ Pending Impleme IBRD / 87710 Post Direct Selection Direct 2,250.00 0.00 2020-11-30 2020-12-10 2021-02-13 2021-08-12 n of Isolation Center Manager s capacity to respond to CO ntation VID-19 LB-MOPH-ICM-003 / Selectio Strengthen the Government’ Pending Impleme IBRD / 87710 Post Direct Selection Direct 2,250.00 0.00 2020-11-30 2020-12-10 2021-02-13 2021-08-12 n of Isolation Center Manager s capacity to respond to CO ntation VID-19 LB-MOPH-ICM-004 / Selectio Strengthen the Government’ Pending Impleme IBRD / 87710 Post Direct Selection Direct 2,250.00 0.00 2020-11-30 2020-12-10 2021-02-13 2021-08-12 n of isolation center manager s capacity to respond to CO ntation VID-19 LB-MOPH-ICM-005 / Selectio Strengthen the Government’ Pending Impleme IBRD / 87710 Post Direct Selection Direct 2,250.00 0.00 2020-11-30 2020-12-10 2021-02-13 2021-08-12 n of Isolation Center Manager s capacity to respond to CO ntation VID-19 LB-MOPH-ICM-006 / Selectio Strengthen the Government’ Pending Impleme IBRD / 87710 Post Direct Selection Direct 2,250.00 0.00 2020-11-30 2020-12-10 2021-02-13 2021-08-12 n of Isolation Center Manager s capacity to respond to CO ntation VID-19 LB-MOPH-ICM-007 / Selectio Strengthen the Government’ Pending Impleme IBRD / 87710 Post Direct Selection Direct 2,250.00 0.00 2020-11-30 2020-12-10 2021-02-13 2021-08-12 n of Isolation Center s capacity to respond to CO ntation VID-19 LB-MOPH-ICM-008 / Selectio Strengthen the Government’ Pending Impleme IBRD / 87710 Post Direct Selection Direct 3,000.00 0.00 2020-11-30 2020-12-10 2021-02-13 2021-08-12 n of Isolation Center Manager s capacity to respond to CO ntation VID-19 LB-MOPH-ICS-001 / Selection Strengthening project mana Individual Consult Under Implement IBRD / 87710 Post Open 18,000.00 0.00 2021-01-11 2021-01-11 2021-03-01 2021-03-22 2021-04-26 2021-10-23 of an IT Analyst gement and monitoring ant Selection ation LB-MOPH-ICS-002 / Selection Strengthening project mana Individual Consult IBRD / 87710 Post Open 16,800.00 0.00 Signed 2021-06-08 2021-06-17 2021-07-27 2021-10-11 2021-08-17 2021-10-09 2021-09-21 2022-03-20 of a Financial Assistant gement and monitoring ant Selection HR-007-SENIOR CLINICAL M Strengthen the Government’ ANAGER / Hiring of a Senior T IBRD / 87710 s capacity to respond to CO Post Direct Selection Direct 9,600.00 19,200.00 Signed 2021-09-07 2021-09-14 2021-09-17 2021-10-07 2021-11-21 2021-09-09 2022-05-20 echnical and Clinical Manage VID-19 r for the Pharmacovigilance p rogram HR-008-CLINICAL PV OFFICE Strengthen the Government’ R / Hiring of a Clinical Pharm IBRD / 87710 s capacity to respond to CO Post Direct Selection Direct 8,400.00 16,800.00 Signed 2021-09-07 2021-09-14 2021-09-17 2021-10-07 2021-11-21 2021-09-09 2022-05-20 acovigilance Officer VID-19 HR-009-CLINICAL PV OFFICE Strengthen the Government’ Under Implement R / Hiring of a Clinical Pharm IBRD / 87710 s capacity to respond to CO Post Direct Selection Direct 8,400.00 0.00 2021-09-07 2021-09-14 2021-09-17 2021-11-21 2022-05-20 ation acovigilance Officer VID-19 HR-010-DATA OPERATOR / H Strengthen the Government’ iring of a Data Operator for t IBRD / 87710 s capacity to respond to CO Post Direct Selection Direct 4,800.00 9,600.00 Signed 2021-09-07 2021-09-14 2021-09-17 2021-10-07 2021-11-21 2021-09-09 2022-05-20 he Pharmacovigilance Progra VID-19 m HR-011-DATA OPERATOR / H Strengthen the Government’ iring of a Data Operator for t IBRD / 87710 s capacity to respond to CO Post Direct Selection Direct 4,800.00 9,600.00 Signed 2021-09-07 2021-09-14 2021-09-17 2021-10-07 2021-11-21 2021-09-09 2022-05-20 he Pharmacovigilance Progra VID-19 m LB-MOPH-ICS-003 / Hiring of Strengthening project mana Individual Consult Under Implement an Environmental and Social IBRD / 87710 Post Open 18,000.00 0.00 2022-03-17 2022-03-21 2022-05-05 2022-05-26 2022-06-30 2022-12-27 gement and monitoring ant Selection ation Specialist and Grievance Mec hanism Officer LB-MOPH-DS004 / Provision Strengthen the Government’ Under Implement IBRD / 87710 Post Direct Selection Direct - National 30,000.00 0.00 2022-09-23 2022-09-28 2022-10-03 2022-09-29 2022-12-07 2023-06-05 of Information Security Servi s capacity to respond to CO ation ces VID-19 LB-MOPH-ICS-005 / Hiring of Strengthening project mana Individual Consult Under Implement a Primary Health Care Techni IBRD / 87710 Post Open - National 20,400.00 0.00 2023-05-15 2023-05-16 2023-07-03 2023-07-24 2023-08-28 2024-02-24 gement and monitoring ant Selection ation cal Coordinator Page 3 Procurement Plan I. General 1. Project Information Country: Malawi Project Name: Lilongwe Water and Sanitation Project Project ID: P163794 2. Project Implementation Agency: Lilongwe Water Board 3. Date of the Procurement Plan: 04 August 2017 4. Period Covered by this procurement plan: January 2018 – June 2019 II. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. III. Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. IV. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in The Malawi Public Procurement Act, 2003, and the Public Regulations, 2004, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: o Provision of “set-asides” contracts for small enterprises shall not be applied. 1 o Criteria such as environmental aspect, extent of local content, technology transfer, and managerial, scientific & operational skills development shall not be used in the evaluation of bids unless specifically agreed by the Bank on case to case basis. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. V. Prequalification: Applicable as appropriate VI. Leased Assets: as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable VII. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable VIII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). (a) Goods: Not Applicable (b) Works: Not Applicable Domestic preference is not applicable for National Open Competitive Procurement IX. Other Relevant Procurement Information a. None X. Procurement Prior Review Thresholds (US$ millions) XI. The overall Project procurement Risk is Substantial. The project being a non-emergency project, there would be generally prior reviews of cases unless specifically indicated in the Procurement Plan as a special measure. 2 Post Review: All contacts not subject to prior review shall be subject to post review. XII. Thresholds for Procurement Approaches and Method (US$ millions) Works Goods, IT and Non-consulting Shortlist of National Services Consultants Open Open Request Open Open Request Consulti Engineeri Internatio Nationa for Internatio Nation for ng ng & nal l Quotati nal al Quotati Services Construct on on ion ≥ < ≥ < Supervisi ≤ ≤ on 7 7 0.2 1 1 0.1 0.2 0.3 XIII. Summary of the procurement packages: (Planned for the first 18 months after project effectiveness): 3 Component 2: Network rehabilitation, expansion and NRW reduction Category: Civil Works Sr Contract Description Estimate Review Market Selecti Evaluation Procuremen Prequalifi Domesti Expected Expecte . d Cost by Bank Approach on Options t Process cation c date of d date N (US$) (Prior/ (Open- Method (BAFO, Rated (Single (Yes/ No) Preferen bid/ of o Post) National/ (RFP, Criteria etc.) stage-single ce proposal Contrac Limited RFB, envelope (Yes/No) opening t etc.) QCBS etc.) Signatur etc.) e 1 Priority Network 28,000,0 Prior Open - RFB Qualification Single stage Yes No February June Rehabilitation in Lilongwe 00 Internatio 2019 2019 City (Distribution pipes, nal Transport pipes and Installation of Pressure Reducing Valves). 2 Priority Network 6,750,00 Prior Open - RFB Qualification Single stage No No February June Improvement in Lilongwe 0 Internatio 2019 2019 City – Construction of nal Service Reservoirs and Pumping Stations 4 Component 3: Priority sanitation improvements Category: Goods Sr Contract Description Estimate Review Market Selecti Evaluation Procure- Prequali- Domesti Expected Expecte . d Cost by Bank Approach on Options ment fication c date of d date N (US$) (Prior/ (Open- Method (BAFO, Rated Process (Yes/ No) Preferen bid/ of o Post) National/ (RFP, Criteria etc.) (Single ce proposal Contrac Limited RFB, stage-single (Yes/No) opening t etc.) QCBS envelope Signatur etc.) etc.) e 1 Supply and installation of 70,000.0 Post Open- RFQ Qualification Single No No March May GIS System (with a 0 National stage-single 2018 2018 training component) envelope Category: Civil Works Sr Contract Description Estimate Review Market Selecti Evaluation Procure- Prequali- Domesti Expected Expect . d Cost by Bank Approach on Options ment fication c date of bid/ ed N (US$) (Prior/ (Open- Method (BAFO, Rated Process (Yes/ No) Preferen proposal date of o Post) National/ (RFP, Criteria etc.) (Single ce opening Contra Limited RFB, stage-single (Yes/No) ct etc.) QCBS envelope Signat etc.) etc.) ure 1 Office Refurbishment at 100,000. Post Limited RFQ Qualification Single No No February April Kauma Wastewater 00 stage-single 2018 2018 Treatment Works envelope 2 Construction of improved 300,000. Post Open- RFB Qualification Single No No March May sanitation facilities in 10 00 National stage-single 2018 2018 markets and 10 schools envelope 3 Priority Lilongwe City 12,000,0 Prior Open - RFB Qualification Single stage Yes No February June Sewerage System 00.00 Internatio 2019 2019 Rehabilitation, and nal Expansion and Upgrading of Kauma Wastewater Treatment Plant 4 Construction of 5,000,00 Prior Open - RFB Qualification Single stage Yes No June 2018 Septe substructures for 5,000 0.00 Internatio mber sanitation facilities for the nal 2018 Poorest in Lilongwe City 5 Category: Non-Consultancy Services Sr Contract Description Estimate Review Market Selecti Evaluation Procure- Prequali- Domesti Expected Expect . d Cost by Bank Approach on Options ment Process fication c date of bid/ ed N (US$) (Prior/ (Open- Method (BAFO, (Single (Yes/ No) Preferen proposal date of o Post) National/ (RFP, Rated stage-single ce opening Contra Limited RFB, Criteria etc.) envelope (Yes/No) ct etc.) QCBS etc.) Signat etc.) ure 1 Sanitation Marketing and 500,000. Post Open - RFB Qualification Single stage- No No March June Hygiene Promotion 00 National single 2018 2018 envelope 6 Component 4: Technical Assistance Category: Goods Sr Contract Description Estimated Review by Market Selection Evaluation Procurem Prequ Domest Expect Expect . Cost (US$) Bank Approach Method Options ent ali- ic ed ed N (Prior/ (Open- (RFP, RFB, (BAFO, Process ficatio Prefere date of date of o Post) National/ QCBS etc.) Rated (Single n nce bid/ Contra Limited Criteria stage- (Yes/ (Yes/No propos ct etc.) etc.) single No) ) al Signat envelope openin ure etc.) g 1 Procurement of Motor 800,000.00 Post Open - RFB Qualificatio Single No No Januar March Vehicles for LWB & LCC National n stage y 2018 2018 PIUs 2 Procurement of Office 64,000.00 Post Open - RFB Qualificatio Single No No Januar March Equipment (Laptops, National n stage y 2018 2018 Printer, Copier & Binders) for LWB & LCC PIUs Category: Consultancy Services Sr. Contract Description Estimated Review Market Selection Shortlisting Expected date Expected No Cost (US$) by Bank Approach Method (Yes/ No) of bid/ proposal date of (Prior/Pos (Open- (QCBS, opening Contract t) National/ FBBS, LCS, Signature International QBS, CQS, Limited etc.) DS etc.) 1 Detailed Design and Construction 2,000,000. Prior Open- QCBS Yes March 2018 July 2018 Supervision of Network Rehabilitation and 00 International Expansion and Packaging of a Performance Based Non-Revenue Water Reduction Program 2 Consultancy Service for Preparation of 100,000.00 Post Open-National CQS No March 2019 June 2019 Environmental and Social Management and Monitoring Plans and Abbreviated Resettlement Plans for Distribution Network Expansion 3 Consultancy Service for Development of a 2,000,000. Prior Open- QCBS Yes April 2018 July 2018 Sanitation Master Plan for Lilongwe City 00 International and Design of Priority Sanitation Interventions 4 Construction Supervision of Sanitation 500,000.00 Prior Open- QCBS Yes March 2019 June 2019 Priority Improvements - Sewerage International 7 Sr. Contract Description Estimated Review Market Selection Shortlisting Expected date Expected No Cost (US$) by Bank Approach Method (Yes/ No) of bid/ proposal date of (Prior/Pos (Open- (QCBS, opening Contract t) National/ FBBS, LCS, Signature International QBS, CQS, Limited etc.) DS etc.) 5 Construction Supervision of Sanitation 200,000.00 Prior Open- QCBS Yes March 2018 June 2018 Priority Improvements - On - site International Component 6 Consultancy Service for Preparation of 100,000.00 Post Open- CQS No September November Environmental and Social Management National 2018 2018 and Monitoring Plans and Abbreviated Resettlement Plans for Sanitation Priority Investments 7 Revenue Collection Mechanisms Study 300,000.00 Prior Open- QCBS Yes May 2018 August 2018 and Operationalization of Sanitation Tariff International 8 Consultancy Services for Groundwater 1,000,000. Prior Open- QCBS Yes May 2018 August 2018 Assessment and Mapping, including 00 International groundwater exploratory drilling 9 Baseline Survey for the Lilongwe Water 100,000.00 Post Open- CQS No January 2018 March 2018 and Sanitation Project National 10 Consultancy to develop Standard 200,000.00 Prior Open- QCBS Yes November February Operating Procedures for Lilongwe Water International 2018 2019 Board 11 Development and Implementation of 219,178.00 Prior Open- QCBS Yes February 2018 May 2018 Customer Services Improvement Plan International incl. Customer Communication and Branding. 12 Individual Consultant – Social and 312,150.00 Prior Open- INDV Yes N/A April 2018 Environmental Safeguards National 13 Individual Consultant - Monitoring and 312,150.00 Prior Open- INDV Yes N/A April 2018 Evaluation National 14 Individual Consultant – Sewerage 180,000.00 Prior Open- INDV Yes N/A April 2018 Engineer International 15 Individual Consultant – GIS and Database 180,000.00 Prior Open- INDV Yes N/A April 2018 Engineer International 16 Individual Consultant – 180,000.00 Prior Open- INDV Yes N/A April 2018 Institutional/Financial Development International Specialist 8 Category: Civil Works Sr Contract Description Estimate Review Market Selecti Evaluation Procure- Prequali- Domesti Expected Expect . d Cost by Bank Approach on Options ment fication c date of bid/ ed N (US$) (Prior/ (Open- Method (BAFO, Rated Process (Yes/ No) Preferen proposal date of o Post) National/ (RFP, Criteria etc.) (Single ce opening Contra Limited RFB, stage-single (Yes/No) ct etc.) QCBS envelope Signat etc.) etc.) ure 1 Remodeling of 1 Zone 68,493.0 Post Limited RFQ Qualification Single stage No No February April Office/Service Center 0 2018 2018 Category: Non-Consultancy Services Sr Contract Description Estimate Review Market Selecti Evaluation Procure- Prequali- Domesti Expected Expect . d Cost by Bank Approach on Options ment Process fication c date of bid/ ed N (US$) (Prior/ (Open- Method (BAFO, (Single (Yes/ No) Preferen proposal date of o Post) National/ (RFP, Rated stage-single ce opening Contra Limited RFB, Criteria etc.) envelope (Yes/No) ct etc.) QCBS etc.) Signat etc.) ure 1 Design and piloting of 301,370. Prior Open- QCBS Qualification Single stage No No April 2018 July Incentive Based 00 Internatio 2018 Performance Management nal System 9 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 10 (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff 11 documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 12 PROCUREMENT Malawi : Lilongwe Water and Sanitation Project PLAN General Information Country: Malawi 2017-10-09 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163794 GPN Date: 2017-09-18 Project Name: Lilongwe Water and Sanitation Project Loan / Credit No: IDA / 61720, IDA / D2660, / , IDA / 70070, IDA / D9350 Lilongwe Water and Sanitaton Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MW-LWSP-31334-CW-RFQ / Priority Sanitation Improvem Request for Quota Single Stage - One E 2018-07-0 Office Refurbishment at Kau / Post Open - National 100,000.00 0.00 Canceled 2018-02-07 2018-04-04 ents tions nvelope 3 ma Wastewater Treatment W orks MW-LWSP-64586-CW-RFB / Priority Sanitation Improvem Single Stage - One E 2018-09-3 Office Refurbishment at Kau IDA / D2660 Post Request for Bids Open - National 200,000.00 133,144.64 Completed 2018-05-30 2018-06-05 2018-06-01 2018-07-02 2018-06-29 2018-07-12 2018-07-03 2018-08-01 2018-09-21 ents nvelope 0 ma Wastewater Treatment Pl ant MW-LWSP-31337-CW-RFQ / Institutional Capacity Streng Request for Quota Single Stage - One E 2018-07-3 Remodeling of 1 Zone Office/ / Post Limited 68,493.00 0.00 Canceled 2018-03-07 2018-05-02 thening tions nvelope 1 Service Center at Lilongwe W ater Board MW-LWSP-76634-CW-RFB / Construction of a Customer S Institutional Capacity Streng Single Stage - One E 2019-07-1 IDA / 61720 Post Request for Bids Open - National 205,000.00 117,275.69 Completed 2018-09-28 2018-09-26 2018-10-03 2018-11-14 2019-08-30 2018-12-14 2019-10-07 2019-01-18 2019-11-16 ervice Center for Lilongwe W thening nvelope 7 ater Board at Area 25 MW-LWSP-26083-CW-RFB / P Water Distribution Network Open - Internationa Single Stage - One E 25,000,000.0 27,099,049. 2020-09-0 riority Water Distribution Net IDA / 61720 Rehabilitation, Expansion an Prior Request for Bids Signed 2018-10-12 2018-10-19 2018-12-05 2019-03-05 2018-12-05 2019-04-08 2018-10-17 2018-10-19 2019-01-31 2019-05-24 2019-02-21 2019-07-18 2019-03-14 2019-08-22 l nvelope 0 15 4 work Rehabilitation in Lilong d NRW reduction we City MW-LWSP-31332-CW-RFB / P Water Distribution Network riority Water Transmission N Open - Internationa Single Stage - One E 11,000,000.0 12,694,549. 2020-05-2 IDA / 61720 Rehabilitation, Expansion an Prior Request for Bids Signed 2018-10-31 2018-12-04 2019-02-08 2019-04-07 2019-02-08 2019-04-24 2018-11-28 2018-12-07 2019-03-22 2019-06-14 2019-04-21 2019-07-18 2019-05-26 2019-08-22 etwork and Associated Facilit l nvelope 0 22 5 d NRW reduction ies Rehabilitation in Lilongwe City MW-LWSP-84692-CW-RFB / Priority Sanitation Improvem Single Stage - One E 2020-01-1 Construction of a Perimeter F IDA / D2660 Post Request for Bids Open - National 800,000.00 0.00 Canceled 2019-03-29 2019-04-03 2019-05-15 2019-06-14 2019-07-19 ents nvelope 5 ence at Kauma Waste Water Treatment Plant MW-LWSP-129703-CW-RFB / Water Distribution Network Procurement of works for Dril Single Stage - One E 2020-06-1 IDA / 61720 Rehabilitation, Expansion an Post Request for Bids Open - National 600,000.00 711,624.36 Completed 2019-08-30 2019-08-30 2019-09-04 2019-08-30 2019-10-16 2019-10-01 2019-11-15 2019-10-04 2019-12-20 2020-01-28 ling and Test Pumping of 20 nvelope 7 d NRW reduction Exploratory Boreholes for Lilo ngwe Water Board. MW-LWSP-31331-CW-RFB / Construction of substructures Priority Sanitation Improvem Open - Internationa Single Stage - One E 2022-10-2 IDA / D2660 Post Request for Bids 5,000,000.00 0.00 Canceled 2019-07-05 2019-07-10 2019-08-21 2019-09-20 2019-10-25 for 5,000 sanitation facilities ents l nvelope 4 for the Poorest in Lilongwe Ci ty MW-LWSP-134980-CW-RFB / Priority Lilongwe City Sewera Priority Sanitation Improvem Open - Internationa Single Stage - One E 12,000,000.0 15,006,089. 2021-10-1 ge Network Rehabilitation an IDA / D2660 Prior Request for Bids Signed 2019-12-13 2020-01-20 2019-12-18 2020-01-21 2020-02-12 2020-03-06 2020-03-13 2020-04-09 2020-04-17 2020-05-24 ents l nvelope 0 26 7 d Expansion and Upgrading o f Kauma Wastewater Treatm ent Plant MW-LWSP-104953-CW-RFB / Water Distribution Network Open - Internationa Single Stage - One E 17,000,000.0 14,966,113. 2021-03-2 Water Distribution Network E IDA / 61720 Rehabilitation, Expansion an Prior Request for Bids Signed 2019-11-22 2020-01-17 2019-11-27 2020-01-17 2020-01-22 2020-03-06 2020-02-21 2020-08-06 2020-03-27 2020-09-13 l nvelope 0 19 7 xpansion Investments in Lilo d NRW reduction ngwe City MW-LWSP-154874-CW-RFB / Civil Works for Modernizing o Single Stage - One E 2020-08-1 IDA / 61720 Technical Assistance Post Request for Bids Open - National 150,000.00 290,760.27 Signed 2020-01-24 2020-02-05 2020-01-29 2020-03-11 2020-03-18 2020-04-10 2020-03-30 2020-05-15 2020-06-05 f Hydrological Monitoring Sys nvelope 3 tems in the Lilongwe River B asin MW-LWSP-31327-CW-RFB / Priority Sanitation Improvem Single Stage - One E 2021-01-1 Construction of improved san IDA / D2660 Post Request for Bids Open - National 300,000.00 0.00 Canceled 2020-03-31 2020-04-05 2020-05-17 2020-06-16 2020-07-21 ents nvelope 7 itation facilities in 10 market s and 10 schools MW-LWSP-134533-CW-RFB / Construction of substructures Priority Sanitation Improvem Single Stage - One E 2021-04-1 IDA / D2660 Post Request for Bids Open - National 5,000,000.00 0.00 Canceled 2020-06-25 2020-06-30 2020-08-11 2020-09-10 2020-10-15 for 5,000 sanitation facilities ents nvelope 3 for the Poorest in Lilongwe Ci ty MW-LWSP-202766-CW-RFB / Priority Sanitation Improvem Single Stage - One E 2021-08-1 Construction of Public Toilet IDA / D2660 Post Request for Bids Open - National 750,000.00 743,065.60 Signed 2020-11-06 2020-11-16 2020-11-13 2020-12-02 2020-12-13 2020-12-16 2021-01-12 2021-02-22 2021-02-16 2021-08-03 ents nvelope 5 Blocks for Schools and Marke ts in Lilongwe City MW-LWSP-226469-CW-RFB / Construction of Improved Em Priority Sanitation Improvem Single Stage - One E 3,009,806.8 2023-01-2 IDA / D2660 Post Request for Bids Open - National 2,500,000.00 Signed 2021-04-01 2021-04-08 2021-04-06 2021-05-06 2021-05-07 2021-06-17 2021-06-29 2021-07-22 2021-11-05 ptiable On-Site Sanitation (O ents nvelope 2 1 SS) Facilities in Lilongwe City National Procure MW-LWSP-202766-CW-RFB.. ment Document - / Construction of Public Toilet Priority Sanitation Improvem Single Stage - One E 1,415,992.6 2021-08-1 IDA / D2660 Post Request for Bids Open - National 1 Envelope proce 750,000.00 Terminated 2020-11-06 2020-11-16 2020-11-13 2020-12-13 2020-12-16 2021-01-12 2021-02-22 2021-02-16 2021-08-03 Blocks for Schools and Marke ents nvelope 7 5 ss (Non Bank-SPD ts in Lilongwe City ) National Procure MW-LWSP-202766-CW-RFB… ment Document - ... / Construction of Public Toi Priority Sanitation Improvem Single Stage - One E 1,416,740.9 2021-08-1 IDA / D2660 Post Request for Bids Open - National 1 Envelope proce 750,000.00 Completed 2020-11-06 2020-11-16 2020-11-13 2020-12-13 2020-12-16 2021-01-12 2021-02-22 2021-02-16 2021-08-12 let Blocks for Schools and Ma ents nvelope 0 5 ss (Non Bank-SPD rkets in Lilongwe City ) National Procure MW-LWSP-270167-CW-DIR / ment Document - Erosion Protection Works in H Under Imple 2022-08-0 IDA / 61720 Technical Assistance Post Direct Selection Direct 1 Envelope proce 55,000.00 0.00 2021-12-24 2021-12-21 2021-12-29 2021-12-27 2022-02-02 ydrological Monitoring Statio mentation 1 ss (Non Bank-SPD ns in the Lilongwe River Basi ) n National Procure MW-LWSP-279135-CW-RFB / ment Document - Institutional Capacity Streng Single Stage - One E 2022-12-1 Construction of Area 23 Cust IDA / 70070 Post Request for Bids Open - National 1 Envelope proce 300,000.00 0.00 Signed 2022-02-28 2022-04-25 2022-03-05 2022-04-25 2022-04-16 2022-06-02 2022-05-16 2022-07-22 2022-06-20 thening nvelope 7 omer Service Centre ss (Non Bank-SPD ) Page 1 MW-LWSP-286539-CW-RFB / Request for Bids - Construction of 7,000 Improv Priority Sanitation Improvem Open - Internationa Single Stage - One E Works (without pr 15,000,000.0 2024-08-1 IDA / D9350 Prior Request for Bids 0.00 Canceled 2022-04-22 2022-06-21 2022-04-27 2022-06-23 2022-06-08 2022-08-05 2022-07-08 2022-11-09 2022-08-12 ed Emptiable On-Site Sanitati ents l nvelope equalification) SP 0 1 on (OSS) Facilities in Lilongw D e City Request for Bids - MW-LWSP-297604-CW-RFB / Priority Sanitation Improvem Open - Internationa Single Stage - One E Works (without pr 2023-10-2 Lilongwe City Sewerage Netw IDA / D9350 Prior Request for Bids 9,000,000.00 0.00 Signed 2022-06-30 2022-08-02 2022-07-05 2022-08-10 2022-08-16 2022-09-23 2022-09-15 2022-11-23 2022-10-20 2023-03-19 ents l nvelope equalification) SP 0 ork Expansion (Phase 2) D MW-LWSP-316176-CW-DIR / Priority Lilongwe City Sewera Priority Sanitation Improvem Direct - Internation Other (with field f 2022-12-3 ge Network Rehabilitation an IDA / D9350 Prior Direct Selection 5,000,000.00 0.00 Canceled 2022-09-16 2022-09-22 2022-09-21 2022-09-22 2022-10-26 ents al or explanation) 1 d Expansion and Upgrading o f Kauma Wastewater Treatm ent Plant MW-LWSP-134980-CW-RFB. / Priority Lilongwe City Sewera Priority Sanitation Improvem Direct - Internation Other (with field f 2022-10-1 ge Network Rehabilitation an IDA / D9350 Prior Direct Selection 3,593,833.97 0.00 Signed 2020-01-20 2020-01-20 2020-03-02 2020-05-05 2020-05-20 ents al or explanation) 5 d Expansion and Upgrading o f Kauma Wastewater Treatm ent Plant MW-LWSP-338568-CW-RFQ / CONSTRUCTION OF A TOILET Priority Sanitation Improvem Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-10-0 IDA / D9350 Post Limited 200,000.00 0.00 2023-02-15 2023-04-12 BLOCK AT CHISIYO PRIMARY ents tions nvelope or explanation) lementation 9 SCHOOL (WESTERN BY-PASS ROAD) MW-LWSP-338857-CW-RFB / Design, Supply, Installation a Request for Bids - Institutional Capacity Streng Open - Internationa Single Stage - One E Under Imple 2023-12-0 nd Commissioning of a Packa IDA / 70070 Post Request for Bids Plant SPD (withou 1,500,000.00 0.00 2023-02-17 2023-03-13 2023-02-22 2023-03-13 2023-04-05 2023-05-05 2023-06-09 thening l nvelope mentation 6 ged Water Treatment Plant f t prequalification) or Bunda Water Supply Syste m MW-LWSP-342403-CW-RFB / Request for Bids - Construction of Improved Em Priority Sanitation Improvem Open - Internationa Single Stage - One E Works (without pr 15,000,000.0 Under Imple 2024-09-0 IDA / D9350 Prior Request for Bids 0.00 2023-02-24 2023-03-10 2023-03-01 2023-03-10 2023-04-12 2023-04-28 2023-05-12 2023-06-01 2023-06-16 ptiable On-Site Sanitation (O ents l nvelope equalification) SP 0 mentation 8 SS) Facilities in Lilongwe City D - Phase II MW-LWSP-342448-CW-RFB / Request for Bids - Procurement of Works for Up Priority Sanitation Improvem Single Stage - One E Small Works SPD Under Imple 2024-01-0 IDA / D9350 Post Request for Bids Limited 300,000.00 0.00 2023-03-15 2023-03-12 2023-03-20 2023-05-01 2023-05-31 2023-07-05 grading of Open Pit latrines U ents nvelope (1 envelope proce mentation 1 sing Sato Pans in Lilongwe Ci ss) ty MW-LWSP-348003-CW-RFB / Request for Bids - Connection of Households to Priority Sanitation Improvem Single Stage - One E Small Works SPD Pending Imp 2023-12-2 IDA / D9350 Post Request for Bids Open - National 800,000.00 0.00 2023-03-17 2023-03-22 2023-04-21 2023-05-21 2023-06-25 the Sewerage Network in Lilo ents nvelope (1 envelope proce lementation 2 ngwe City (Areas 47 and 49) ss) Request for Bids - MW-LWSP-351273-CW-RFB / Priority Sanitation Improvem Single Stage - One E Small Works SPD Under Imple 2023-12-2 IDA / D9350 Post Request for Bids Open - National 350,000.00 0.00 2023-03-24 2023-03-24 2023-03-29 2023-03-28 2023-04-28 2023-05-28 2023-07-02 Construction of Kauma Youth ents nvelope (1 envelope proce mentation 9 Centre ss) MW-LWSP-364105-CW-RFB / Design, Supply, Installation a Institutional Capacity Streng Single Stage - One E Other (with field f Pending Imp 2024-03-1 nd Commissioning of Priority IDA / 70070 Post Request for Bids Open - National 2,000,000.00 0.00 2023-06-09 2023-06-14 2023-07-14 2023-08-13 2023-09-17 thening nvelope or explanation) lementation 5 Efficiency Improvement Meas ures for Lilongwe Water Boar d Treatment Works I and II MW-LWSP-364108-CW-RFQ / Completion of Remaining Wo Priority Sanitation Improvem Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-09-2 IDA / D2660 Post Limited 70,000.00 0.00 2023-06-05 2023-07-31 rks for the Construction of Pu ents tions nvelope or explanation) lementation 9 blic Toilets in Schools in Lilon gwe City National Procure MW-LWSP-366364-CW-DIR / Water Distribution Network ment Document - Direct - Internation Pending Imp 2024-04-2 Optimization of Bunda Water IDA / 61720 Rehabilitation, Expansion an Post Direct Selection 1 Envelope proce 2,500,000.00 0.00 2023-06-16 2023-06-21 2023-08-25 al lementation 1 Supply Network d NRW reduction ss (Non Bank-SPD ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-LWSP-31329-GO-RFB / P rocurement of Motor Vehicles Institutional Capacity Streng Single Stage - One E for Lilongwe Water Board an IDA / 61720 Post Request for Bids Open - National 800,000.00 627,481.73 Completed 2018-01-08 2018-05-02 2018-01-13 2018-02-24 2018-05-30 2018-03-26 2018-07-25 2018-04-30 2018-07-23 2018-06-29 2018-10-18 thening nvelope d Lilongwe City Council Proje ct Implementation Units MW-LWSP-28881-GO-RFB / P rocurement of Office Equipm Institutional Capacity Streng Single Stage - One E ent for Lilongwe Water Board / Post Request for Bids Open - National 64,000.00 0.00 Canceled 2018-01-08 2018-01-22 2018-03-05 2018-04-04 2018-05-09 2018-06-08 thening nvelope & Lilongwe City Council Proje ct Implementation Units MW-LWSP-41782-GO-RFB / P rocurement of Office Equipm Institutional Capacity Streng Single Stage - One E ent for Lilongwe Water Board IDA / 61720 Post Request for Bids Open - National 64,000.00 76,986.95 Completed 2018-01-31 2018-05-02 2018-02-05 2018-03-05 2018-08-01 2018-03-19 2018-07-25 2018-04-23 2018-07-23 2018-05-23 2018-10-08 thening nvelope & Lilongwe City Council Proje ct Implementation Units MW-LWSP-31336-GO-RFQ / S upply and Installation of GIS Priority Sanitation Improvem Request for Quota Single Stage - One E IDA / D2660 Post Open - National 100,000.00 32,047.26 Completed 2018-12-21 2019-02-15 2019-03-18 2019-04-16 2019-04-22 Software and GIS Accessories ents tions nvelope to Lilongwe City Council MW-LWSP-87144-GO-DIR / S UPPLY, INSTALLATION, TESTI Institutional Capacity Streng NG AND COMMISSIONING OF IDA / 61720 Post Direct Selection Direct 60,000.00 84,204.00 Completed 2018-12-07 2018-12-14 2018-12-14 2019-01-28 2019-01-25 2019-05-05 2019-04-25 2019-09-18 thening INTEGRATED PROJECT FINAN CIAL MANAGEMENT SYSTEM MW-LWSP-79589-GO-RFB / S upply and Delivery of a Minib Institutional Capacity Streng Single Stage - One E IDA / D2660 Post Request for Bids Open - National 50,000.00 51,415.51 Completed 2018-10-18 2018-10-25 2018-10-23 2018-12-04 2018-11-23 2019-01-03 2018-12-04 2019-02-07 2019-02-28 2019-04-08 2019-08-30 us for the Lilongwe Water an thening nvelope d Sanitation Project MW-LWSP-94870-GO-RFQ / P Water Distribution Network Request for Quota Single Stage - One E rocurement of Pressure Logg IDA / 61720 Rehabilitation, Expansion an Post Open - National 35,000.00 108,225.10 Completed 2019-01-23 2019-03-20 2019-03-15 2019-05-19 2019-04-28 tions nvelope ers for Water Distribution Net d NRW reduction work Monitoring Page 2 MW-LWSP-99578-GO-RFQ / S Institutional Capacity Streng Request for Quota Single Stage - One E upply and Delivery of Protect IDA / 61720 Post Open - National 30,000.00 17,121.85 Completed 2019-02-23 2019-04-20 2019-05-03 2019-10-17 2019-09-06 thening tions nvelope ive Clothing MW-LWSP-139115-GO-RFQ / Institutional Capacity Streng Request for Quota Single Stage - One E Supply and delivery of Office IDA / D2660 Post Limited 30,000.00 29,068.94 Completed 2019-10-20 2019-10-16 2019-12-15 2019-11-29 2020-06-12 2020-04-01 thening tions nvelope Furniture for Kauma Office MW-LWSP-118066-GO-RFQ / Institutional Capacity Streng Request for Quota Single Stage - One E Supply, Delivery and Commis IDA / 61720 Post Limited 60,000.00 0.00 Canceled 2019-06-15 2019-06-19 2019-08-10 2020-02-06 thening tions nvelope sioning of Video Conferencin g MW-LWSP-118066-GO-RFQ-2 Institutional Capacity Streng Request for Quota Single Stage - One E / Supply,Installation and Com IDA / 61720 Post Limited 60,000.00 59,894.96 Completed 2019-06-24 2019-06-19 2019-08-19 2019-08-29 2020-02-15 2020-05-21 thening tions nvelope missioning of Video Conferen cing System MW-LWSP-143676-GO-RFB / Institutional Capacity Streng Single Stage - One E Supply and Delivery of Maint IDA / D2660 Post Request for Bids Open - National 300,000.00 166,977.53 Signed 2020-02-05 2020-02-22 2020-02-10 2020-03-23 2020-04-06 2020-04-22 2020-06-11 2020-05-27 2021-01-13 2020-11-23 2021-07-01 thening nvelope enance Equipment for Lilong we City Council MW-LWSP-154863-GO-RFB / Supply, Delivery, Installation Single Stage - One E and Commissioning of Equip IDA / 61720 Technical Assistance Post Request for Bids Open - National 200,000.00 350,081.50 Signed 2020-01-24 2020-02-05 2020-01-29 2020-03-11 2020-02-05 2020-04-10 2020-03-20 2020-05-15 2020-06-18 2020-09-12 nvelope ment for Modernization of Hy drological Monitoring System s in the Lilongwe River Basin MW-LWSP-81230-GO-RFB / S upply and Installation of Equi pment and Associated Minor Single Stage - One E IDA / 61720 Technical Assistance Post Request for Bids Open - National 150,000.00 0.00 Canceled 2019-12-18 2019-11-19 2019-12-28 2020-01-27 2019-12-18 2020-02-26 2020-04-01 2020-09-28 Civil Works' Construction for nvelope Modernizing of Hydrological Monitoring Systems in the Lil ongwe River Basin. MW-LWSP-172868-GO-DIR / Institutional Capacity Streng Procurement of Prepaid Com IDA / 61720 Post Direct Selection Direct 220,000.00 215,993.68 Signed 2020-05-20 2020-06-01 2020-05-25 2020-06-02 2020-06-29 2020-06-05 2020-12-26 thening munal Water Dispensers MW-LWSP-174310-GO-DIR / Institutional Capacity Streng IDA / 61720 Post Direct Selection Direct 70,000.00 68,642.78 Signed 2020-05-27 2020-06-12 2020-06-01 2020-06-12 2020-07-06 2020-07-23 2021-01-02 Supply and Delivery of a Wat thening er Bowser. MW-LWSP-174386-GO-RFQ / Supply and Delivery of Perso Institutional Capacity Streng Request for Quota Single Stage - One E nal Protective Equipment, Sa IDA / 61720 Post Limited 20,000.00 0.00 Canceled 2020-06-05 2020-07-31 2021-01-27 thening tions nvelope nitizers and Detergents for st aff working on essential servi ces MW-LWSP-118930-GO-RFB / Institutional Capacity Streng Single Stage - One E Supply and Delivery of a Min- IDA / 61720 Post Request for Bids Open - National 70,000.00 0.00 Canceled 2020-08-20 2020-08-25 2020-10-06 2020-11-05 2020-12-10 2021-06-08 thening nvelope bus for Lilongwe Water Board MW-LWSP-183920-GO-RFQ / Institutional Capacity Streng Request for Quota Single Stage - One E Furnishing of Isolation Room IDA / 61720 Post Limited 55,000.00 0.00 Canceled 2020-08-04 2020-09-29 2021-03-28 thening tions nvelope for Covid-19 patients MW-LWSP-225480-GO-RFQ / Institutional Capacity Streng Request for Quota Single Stage - One E Supply and Delivery of a hea IDA / 61720 Post Limited 15,000.00 6,830.74 Signed 2021-03-28 2021-03-31 2021-05-23 2021-05-19 2021-11-19 thening tions nvelope vy Duty Printer MW-LWSP-234465-GO-RFQ / Supply and Delivery of a Mini Institutional Capacity Streng Request for Quota Single Stage - One E IDA / 61720 Post Limited 55,000.00 52,843.62 Signed 2021-05-26 2021-06-02 2021-07-21 2021-08-18 2021-09-19 bus for the Lilongwe Water a thening tions nvelope nd Sanitation Project MW-LWSP-268543-GO-RFB / Water Distribution Network Open - Internationa Single Stage - One E Procurement of Water Conne IDA / 61720 Rehabilitation, Expansion an Post Request for Bids 1,700,000.00 0.00 Signed 2022-01-24 2022-01-24 2022-01-29 2022-01-31 2022-03-12 2022-03-14 2022-04-11 2022-04-19 2022-06-16 2022-12-13 l nvelope ction Materials d NRW reduction MW-LWSP-273787-GO-RFQ / Priority Sanitation Improvem Request for Quota Single Stage - One E IDA / 61720 Post Limited 20,000.00 13,459.76 Signed 2022-02-12 2022-02-13 2022-04-09 2022-04-13 2022-10-06 Supply and Delivery of Lapto ents tions nvelope ps MW-LWSP-279138-GO-RFB / Water Distribution Network Single Stage - One E Under Imple Procurement of Water Conne IDA / 70070 Rehabilitation, Expansion an Post Request for Bids Open - National 700,000.00 0.00 2022-04-22 2022-04-25 2022-04-27 2022-04-25 2022-06-08 2022-05-24 2022-07-08 2022-08-12 2023-02-08 nvelope mentation ction Materials-Phase II d NRW reduction MW-LWSP-298937-GO-RFQ / Procurement of Branded T/Sh Priority Sanitation Improvem Request for Quota Single Stage - One E IDA / D9350 Post Limited 18,000.00 0.00 Signed 2022-07-25 2022-07-18 2022-09-19 2023-03-18 irts, Banners, Motor Vehicle B ents tions nvelope randing Services and Billboar ds MW-LWSP-279129-GO-RFB / Procurement of Equipment fo Priority Sanitation Improvem Single Stage - One E IDA / D2660 Post Request for Bids Open - National 650,000.00 0.00 Canceled 2022-04-08 2022-04-25 2022-04-13 2022-04-25 2022-05-25 2022-07-06 2022-08-10 2023-02-06 r Sewerage and Solid Waste ents nvelope Management Services for Lilo ngwe City MW-LWSP-307450-GO-RFQ / Institutional Capacity Streng Request for Quota Single Stage - One E IDA / 70070 Post Limited 12,000.00 0.00 Canceled 2022-10-05 2022-11-30 2023-05-29 Procurement of Laptops and thening tions nvelope Tablets MW-LWSP-328020-GO-RFB / SUPPLY, DELIVERY AND INST Single Stage - One E Under Imple IDA / 70070 Technical Assistance Post Request for Bids Open - National 100,000.00 0.00 2022-12-05 2022-12-01 2022-12-10 2022-12-01 2023-01-21 2023-01-03 2023-02-20 2023-03-27 2023-09-23 ALLATION OF AUDIT MANAGE nvelope mentation MENT SOFTWARE SYSTEM. MW-LWSP-328014-GO-RFB / Procurement of Equipment fo Priority Sanitation Improvem Single Stage - One E Under Imple IDA / D2660 Post Request for Bids Open - National 650,000.00 0.00 2022-12-05 2022-12-01 2022-12-10 2022-12-01 2023-01-21 2023-01-03 2023-02-20 2023-03-27 2023-09-23 r Sewerage and Solid Waste ents nvelope mentation Management Services in Lilo ngwe City MW-LWSP-338435-GO-DIR / Supply and Delivery of Sato P Priority Sanitation Improvem Direct - Internation IDA / D9350 Post Direct Selection 200,000.00 0.00 Signed 2023-01-31 2022-12-13 2023-02-14 2023-02-06 2023-03-07 2023-04-21 an – Doors and Sato Handwa ents al shing Taps for Lilongwe City Council MW-LWSP-341946-GO-RFQ / Priority Sanitation Improvem Request for Quota Single Stage - One E Under Imple Procurement of Cholera Inter IDA / D9350 Post Limited 45,000.00 0.00 2023-02-28 2023-03-02 2023-04-25 2023-10-22 ents tions nvelope mentation vention Items MW-LWSP-363780-GO-RFB / Institutional Capacity Streng Single Stage - One E Under Imple Supply and Delivery of HDPE IDA / 61720 Post Request for Bids Open - National 500,000.00 0.00 2023-06-15 2023-06-06 2023-06-20 2023-08-01 2023-08-31 2023-10-05 2024-04-02 thening nvelope mentation Pipes, Fittings and PVC Fittin gs Page 3 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-LWSP-31333-NC-RFB / S Priority Sanitation Improvem Single Stage - One E anitation Marketing and Hygi / Post Request for Bids Open - National 500,000.00 0.00 Canceled 2018-01-08 2018-01-13 2018-02-24 2018-03-26 2018-04-30 2021-04-29 ents nvelope ene Promotion MW-LWSP-348451-NC-RFQ / Priority Sanitation Improvem Request for Quota Single Stage - One E Under Imple Desludging of Pit Latrines in IDA / 70070 Post Limited 10,000.00 0.00 2023-03-19 2023-03-10 2023-04-23 2023-05-03 ents tions nvelope mentation Primary schools . MW-LWSP-350214-NC-RFQ / Priority Sanitation Improvem Request for Quota Single Stage - One E Pending Impl Procurement of Miscellaneou IDA / D9350 Post Limited 65,000.00 0.00 2023-04-15 2023-06-10 2023-12-07 ents tions nvelope ementation s Sanitation Marketing Activit ies CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-LWSP-26088-CS-QCBS / Detailed Design and Constru ction Supervision of Network Quality And Cost- Open - Internationa IDA / 61720 Technical Assistance Prior 2,000,000.00 3,702,942.67 Signed 2017-11-06 2017-10-17 2017-12-18 2017-10-18 2018-01-31 2018-04-04 2018-03-14 2018-04-04 2018-06-21 2018-05-30 2019-07-18 2018-07-04 2019-08-04 2021-06-23 Rehabilitation and Expansion Based Selection l and Packaging of a Performa nce Based Non-Revenue Wat er Reduction Program MW-LWSP-31324-CS-QCBS / Consultancy Service for Deve Quality And Cost- Open - Internationa lopment of a Sanitation Mast IDA / D2660 Technical Assistance Prior 2,000,000.00 2,041,008.70 Signed 2018-01-15 2017-11-08 2018-02-26 2017-11-23 2018-04-11 2018-05-30 2018-05-23 2018-07-13 2018-06-22 2018-09-06 2018-07-27 2018-10-19 2018-08-31 2018-11-21 2020-03-01 Based Selection l er Plan for Lilongwe City and Design of Priority Sanitation I nterventions MW-LWSP-31341-CS-CQS / C onsultancy Service for Prepar ation of Environmental and S Consultant Qualifi IDA / 61720 Technical Assistance Post Open - National 100,000.00 0.00 Canceled 2018-05-20 2018-11-15 2018-07-01 2018-08-14 2018-09-13 2018-10-18 2019-01-16 ocial Management and Monit cation Selection oring Plans and Abbreviated Resettlement Plans for Sanit ation Priority Investments MW-LWSP-31342-CS-CQS / C onsultancy Service for Prepar ation of Environmental and S Consultant Qualifi / Technical Assistance Post Open - National 100,000.00 0.00 Canceled 2018-11-16 2018-12-07 2019-01-20 2019-02-19 2019-03-26 2019-06-24 ocial Management and Monit cation Selection oring Plans and Abbreviated Resettlement Plans for Distri bution Network Expansion MW-LWSP-31323-CS-QCBS / Consultancy Services for Gro Quality And Cost- Open - Internationa IDA / 61720 Technical Assistance Prior 1,000,000.00 865,070.23 Signed 2018-01-17 2018-05-29 2018-02-28 2018-05-30 2018-04-20 2018-09-04 2018-06-01 2018-10-23 2018-07-01 2018-12-14 2018-08-05 2019-02-07 2018-09-09 2019-03-24 2019-03-10 undwater Assessment and M Based Selection l apping, including groundwat er exploratory drilling MW-LWSP-28883-CS-QCBS / Quality And Cost- Baseline Survey for the Lilon IDA / 61720 Technical Assistance Post Open - National 100,000.00 111,596.24 Completed 2017-11-20 2018-09-28 2017-12-11 2018-10-09 2018-01-24 2018-11-30 2018-02-21 2018-12-20 2018-03-23 2019-02-06 2018-04-27 2019-04-17 2018-06-01 2019-04-18 2018-07-16 2020-01-02 Based Selection gwe Water and Sanitation Pr oject MW-LWSP-31340-CS-QCBS / Consultancy to develop Stan Institutional Capacity Streng Quality And Cost- Open - Internationa / Prior 200,000.00 0.00 Canceled 2018-07-20 2018-08-31 2018-10-14 2018-11-11 2018-12-11 2019-01-15 2019-02-19 2019-08-18 dard Operating Procedures fo thening Based Selection l r Lilongwe Water Board MW-LWSP-39698-CS-QCBS / Consultancy Services to Dev Institutional Capacity Streng Quality And Cost- Open - Internationa elop Quality Management Sy IDA / 61720 Prior 205,000.00 0.00 Canceled 2017-12-15 2018-04-18 2018-01-26 2018-04-20 2018-03-11 2018-08-15 2018-04-08 2018-09-14 2018-05-08 2018-06-12 2018-07-17 2019-01-15 thening Based Selection l stem and Facilitate Process o f ISO 9000 Certification for Lil ongwe Water Board MW-LWSP-64916-CS-QCBS / Diagnostic and Pre-Feasibility Quality And Cost- Open - Internationa Studies for Resilient Urban D IDA / D2660 Technical Assistance Prior 300,000.00 680,317.00 Signed 2018-06-08 2018-06-07 2018-07-13 2018-06-29 2018-08-10 2018-10-24 2018-09-07 2019-01-07 2018-10-07 2019-03-14 2018-11-11 2019-07-18 2018-12-16 2019-08-19 2019-04-15 Based Selection l evelopment and Service Deli very in Lilongwe City MW-LWSP-75526-CS-QCBS / Priority Sanitation Improvem Quality And Cost- Open - Internationa Consultancy Services for Sani IDA / D2660 Prior 500,000.00 579,611.21 Signed 2018-09-07 2018-10-02 2018-10-05 2018-10-11 2018-11-02 2019-01-30 2018-11-30 2019-03-13 2018-12-28 2019-04-29 2019-02-01 2021-07-27 2019-03-08 2021-08-03 2022-03-07 ents Based Selection l tation Marketing MW-LWSP-76630-CS-QCBS / Consultancy Service for Deve lopment of a Water Supply M Quality And Cost- Open - Internationa asterplan for Lilongwe City (I IDA / 61720 Technical Assistance Prior 1,500,000.00 0.00 Canceled 2018-09-14 2018-10-14 2018-11-27 2018-12-27 2019-01-26 2019-03-02 2019-04-06 2020-03-06 Based Selection l ncluding Investment Framew ork and Design and Develop ment Manual for Lilongwe W ater Board) MW-LWSP-76633-CS-QCBS / Consultancy Services for Dev Institutional Capacity Streng Quality And Cost- Open - Internationa IDA / 61720 Post 200,000.00 0.00 Canceled 2018-09-28 2018-11-21 2018-10-28 2018-12-11 2019-01-08 2019-02-07 2019-03-14 2019-04-18 2019-10-15 elopment of Standard Operat thening Based Selection l ing Procedures for Lilongwe Water Board MW-LWSP-31326-CS-QCBS / CONSULTANCY SERVICES FO R DETAILED ENGINEERING D Quality And Cost- Open - Internationa IDA / D2660 Technical Assistance Post 200,000.00 0.00 Canceled 2018-10-12 2018-11-22 2018-11-23 2019-01-06 2019-02-17 2019-03-19 2019-04-23 2019-05-28 2022-05-27 ESIGN, AND CONSTRUCTION Based Selection l SUPERVISION AND VERIFICAT ION OF HOUSEHOLD SANITAT ION FACILITIES IN LILONGWE MW-LWSP-81232-CS-QCBS / Consultancy Services for Det Quality And Cost- Open - Internationa ermining Environmental and IDA / 61720 Technical Assistance Post 200,000.00 503,591.97 Signed 2018-10-25 2018-11-20 2018-11-15 2018-12-01 2018-12-29 2019-02-22 2019-01-26 2019-04-04 2019-02-25 2019-04-18 2019-04-01 2019-04-10 2019-05-06 2019-10-08 2020-05-05 Based Selection l Social Flow Requirements in Lilongwe River Catchment MW-LWSP-76632-CS-QCBS / Consultancy Services to Facil Institutional Capacity Streng Quality And Cost- Open - Internationa IDA / 61720 Post 200,000.00 0.00 Canceled 2018-09-28 2018-10-06 2018-10-26 2018-12-09 2019-01-06 2019-02-05 2019-03-12 2019-04-16 2021-04-15 itate Development of a Wate thening Based Selection l r Safety Plan for Lilongwe Wa ter Board Page 4 MW-LWSP-88248-CS-CQS / C onsultancy Services for Prep aration of Environment and S Consultant Qualifi IDA / 61720 Technical Assistance Post Limited 100,000.00 181,113.71 Signed 2018-11-30 2018-12-01 2018-12-14 2019-03-12 2019-01-13 2019-10-16 2019-02-17 2019-11-01 2019-08-16 ocial Management and Monit cation Selection oring Plans and Abbreviated Resettlement Plans for Sanit ation Priority Investments. MW-LWSP-88949-CS-QCBS / Technical Assistance to Deve lop Standard Operating Proce Institutional Capacity Streng Quality And Cost- Open - Internationa dures, Establishment of a Qu IDA / 61720 Post 350,000.00 0.00 Canceled 2019-01-11 2019-02-08 2019-03-24 2019-04-21 2019-05-21 2019-06-25 2019-07-30 2020-07-29 thening Based Selection l ality Management System an d Prepare Lilongwe Water Bo ard for ISO 9001:2015 Certifi cation MW-LWSP-31339-CS-QCBS / Revenue Collection Mechanis Institutional Capacity Streng Quality And Cost- Open - Internationa IDA / D2660 Post 300,000.00 0.00 Canceled 2019-06-28 2019-08-09 2019-09-22 2019-10-20 2019-11-19 2019-12-24 2020-01-28 2020-07-26 ms Study and Operationaliza thening Based Selection l tion of Sanitation Tariff MW-LWSP-88954-CS-QCBS / Consultancy Services for Dev Institutional Capacity Streng Quality And Cost- Open - Internationa elopment of Dam Safety Man IDA / 61720 Post 300,000.00 474,758.30 Signed 2019-01-11 2019-08-07 2019-02-10 2019-09-06 2019-03-26 2019-11-13 2019-04-23 2020-01-29 2019-05-23 2020-02-17 2019-06-27 2020-05-19 2019-08-01 2020-06-02 2019-11-29 thening Based Selection l agement Plans for Kamuzu D am 1 and Kamuzu Dam 2 MW-LWSP-31328-CS-QCBS / Quality And Cost- Open - Internationa Construction Supervision of S IDA / D2660 Technical Assistance Post 600,000.00 772,670.00 Signed 2019-02-28 2019-09-11 2019-04-11 2019-09-19 2019-05-25 2019-12-09 2019-06-22 2020-01-31 2019-07-22 2020-03-03 2019-08-26 2020-05-13 2019-09-30 2020-06-02 2021-09-29 Based Selection l anitation Priority Improveme nts - Sewerage MW-LWSP-89090-CS-QCBS / Consultancy Services for Det ailed Engineering Design, an Quality And Cost- Open - Internationa IDA / D2660 Technical Assistance Prior 1,000,000.00 983,529.06 Signed 2018-12-07 2018-12-14 2019-01-06 2018-12-14 2019-02-19 2019-05-07 2019-03-19 2019-07-26 2019-04-18 2019-11-19 2019-05-23 2021-07-20 2019-06-27 2021-08-09 2022-06-26 d Construction Supervision a Based Selection l nd Verification of Household Sanitation Facilities in Lilong we MW-LWSP-115590-CS-QCBS / Consultancy Service to Sup Institutional Capacity Streng Quality And Cost- Open - Internationa IDA / 61720 Prior 1,000,000.00 1,132,615.72 Signed 2019-06-14 2019-09-10 2019-07-05 2019-09-12 2019-08-18 2019-12-06 2019-09-29 2020-01-31 2019-10-29 2020-04-04 2019-12-03 2020-09-24 2020-01-07 2020-10-09 2022-01-06 port Lilongwe Water Board's I thening Based Selection l nstitutional Modernisation Pr ogramme MW-LWSP-115552-CS-QCBS / CONSULTANCY SERVICES F OR REVIEW AND UPDATING OF FEASIBILITY STUDIES FOR Quality And Cost- Open - Internationa DIAMPHWE MULTI-PURPOSE IDA / 61720 Technical Assistance Prior 1,000,000.00 0.00 Canceled 2019-06-28 2019-07-19 2019-09-01 2019-09-29 2019-10-29 2019-12-03 2020-01-07 2020-07-05 Based Selection l SURFACE RAW WATER SOUR CE DEVELOPMENT AND CARR YING OUT FEASIBILITY STUDY FOR LAKE MALAWI WATER S OURCE FOR LILONGWE CITY MW-LWSP-115595-CS-QCBS / CONSULTANCY SERVICES F Water Distribution Network OR NON-REVENUE WATER - R Quality And Cost- Open - Internationa IDA / 61720 Rehabilitation, Expansion an Post 500,000.00 0.00 Canceled 2019-08-23 2019-08-02 2019-09-22 2019-11-05 2019-12-17 2020-01-16 2020-02-20 2020-04-02 2023-04-02 EDUCTION PLAN & PERFORM Based Selection l d NRW reduction ANCE BASED COMPENSATIO N DESIGN AND PROCUREMEN T MW-LWSP-135195-CS-CQS / Consultancy Services for Pre paration of an Environmental Consultant Qualifi and Social Management Plan IDA / 61720 Technical Assistance Post Limited 50,000.00 59,342.43 Signed 2019-10-31 2019-09-30 2019-11-30 2019-12-16 2019-12-30 2020-01-24 2020-02-03 2020-02-08 2020-05-03 cation Selection and Resettlement Action Pla n for the Water Distribution N etwork Expansion Investmen ts in Lilongwe City MW-LWSP-139139-CS-QCBS / Consultancy Services for De Quality And Cost- Open - Internationa IDA / 61720 Technical Assistance Prior 300,000.00 471,669.85 Signed 2019-11-15 2019-12-02 2019-12-16 2019-12-06 2020-01-29 2020-03-06 2020-03-11 2020-05-06 2020-04-10 2020-05-12 2020-05-15 2022-08-25 2020-06-19 2020-09-10 2020-10-17 tailed Design of Lilongwe Wa Based Selection l ter Board Treatment Works II I MW-LWSP-200083-CS-QCBS / REVISION AND UPDATE OF THE ENVIRONMENTAL AND S Water Distribution Network OCIAL IMPACT ASSESSMENT Quality And Cost- Open - Internationa IDA / 61720 Rehabilitation, Expansion an Prior 1,000,000.00 0.00 Canceled 2020-10-23 2020-12-01 2020-11-20 2021-01-17 2021-02-14 2021-03-16 2021-04-20 2021-05-25 2021-12-21 REPORT AND UPDATE OF TH Based Selection l d NRW reduction E RESETTLEMENT ACTION PL AN FOR THE DIAMPHWE MUL TIPURPOSE DAM PROJECT AN D ASSOCIATED STRUCTURES MW-LWSP-200074-CS-QCBS / CONSULTANCY SERVICES F Water Distribution Network OR DESIGN REVIEW AND CO Quality And Cost- Open - Internationa IDA / 61720 Rehabilitation, Expansion an Prior 1,500,000.00 0.00 Canceled 2020-10-23 2020-11-20 2021-01-17 2021-02-14 2021-03-16 2021-04-20 2021-05-25 2021-11-24 NSTRUCTION SUPERVISION O Based Selection l d NRW reduction F DIAMPHWE DAM AND ASSO CIATED STRUCTURES - PHAS EI MW-LWSP-208409-CS-CQS / REVISION AND UPDATE OF T HE ENVIRONMENTAL AND SO Water Distribution Network CIAL IMPACT ASSESSMENT R Consultant Qualifi IDA / 61720 Rehabilitation, Expansion an Prior Limited 1,000,000.00 0.00 Canceled 2020-12-18 2021-01-29 2021-02-28 2021-04-04 2021-10-01 EPORT AND UPDATE OF THE cation Selection d NRW reduction RESETTLEMENT ACTION PLA N FOR THE DIAMPHWE MULTI PURPOSE DAM PROJECT AND ASSOCIATED STRUCTURE MW-LWSP-258633-CS-QCBS Water Distribution Network / Performance Based Contrac Quality And Cost- Open - Internationa Under Implement IDA / 61720 Rehabilitation, Expansion an Prior 2,000,000.00 0.00 2021-10-31 2021-11-18 2021-11-05 2021-11-25 2021-12-19 2022-07-24 2022-01-30 2022-09-19 2022-03-01 2022-11-24 2022-04-05 2023-02-16 2022-05-10 2024-05-09 t (PBC) for Based Selection l ation d NRW reduction Non-Revenue Water (NRW) R eduction in Lilongwe City MW-LWSP-285474-CS-QCBS / CONSULTANCY SERVICES F OR FEASIBILITY STUDIES AND Quality And Cost- Under Implement IDA / D9350 Technical Assistance Post Open - National 450,000.00 0.00 2022-04-15 2022-04-26 2022-05-15 2022-05-04 2022-06-28 2022-08-01 2022-07-28 2022-09-26 2022-08-27 2022-10-12 2022-10-01 2022-11-30 2022-11-05 2023-05-04 DETAILED DESIGN OF CLIMAT Based Selection ation E CHANGE RESILIENT SOLID WASTE MANAGEMENT SYSTE MS IN THE LILONGWE CITY MW-LWSP-285478-CS-QCBS / DEVELOPMENT OF A WATER SUPPLY INVESTMENT PLAN F Quality And Cost- Open - Internationa Under Implement IDA / 70070 Technical Assistance Post 800,000.00 0.00 2022-04-15 2022-04-25 2022-05-15 2022-04-28 2022-06-28 2022-07-27 2022-07-28 2022-08-26 2022-08-27 2022-12-01 2022-10-01 2022-12-12 2022-11-05 2023-05-04 OR LILONGWE CITY AND A FR Based Selection l ation AMEWORK TO GUIDE LILONG WE WATER BOARD IN INVEST MENT PLANNING Page 5 MW-LWSP-297595-CS-QCBS / Consultancy Services for De tailed Design and Constructio Institutional Capacity Streng Quality And Cost- IDA / 70070 Post Open - National 200,000.00 0.00 Signed 2022-06-17 2022-06-07 2022-07-08 2022-06-09 2022-08-21 2022-09-14 2022-09-20 2022-10-26 2022-10-20 2022-11-27 2022-11-24 2022-12-12 2022-12-29 2024-01-28 n Supervision of Main Custo thening Based Selection mer Service Centre for Lilong we Water Board in Southern Zone MW-LWSP-307472-CS-CQS / Consultancy Services for Con Consultant Qualifi Under Implement struction Supervision and Ver IDA / D9350 Technical Assistance Post Limited 350,000.00 0.00 2022-08-19 2022-08-18 2022-09-09 2022-09-30 2022-11-04 2024-05-05 cation Selection ation ification of Household Sanitat ion Facilities in Lilongwe ( Lot 3 and Lot 4) MW-LWSP-307470-CS-CQS / Consultancy Services for Con Consultant Qualifi Under Implement struction Supervision and Ver IDA / D9350 Technical Assistance Post Limited 350,000.00 0.00 2022-08-19 2022-08-11 2022-09-09 2022-10-18 2022-09-30 2022-11-04 2024-05-05 cation Selection ation ification of Household Sanitat ion Facilities in Lilongwe City ( Lot 1 and Lot 2) MW-LWSP-285477-CS-QCBS / FEASIBILITY AND DETAILED Quality And Cost- Open - Internationa IDA / D9350 Technical Assistance Post 500,000.00 0.00 Canceled 2022-04-22 2022-04-13 2022-05-22 2022-07-05 2022-08-19 2022-09-18 2022-10-23 2022-11-27 2023-07-25 DESIGN OF SUSTAINABLE UR Based Selection l BAN MOBILITY SYSTEMS IN T HE LILONGWE CITY MW-LWSP-297599-CS-QCBS / Consultancy Services for Fe Quality And Cost- Open - Internationa asibility Study and Detailed D IDA / 70070 Technical Assistance Post 400,000.00 0.00 Canceled 2022-06-30 2022-06-07 2022-07-21 2022-09-03 2022-10-15 2022-11-14 2022-12-19 2023-01-23 2023-07-22 Based Selection l esign of Groundwater Syste ms for Lilongwe Water Board INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-LWSP-26078-CS-INDV / I Institutional Capacity Streng Individual Consult ndividual Consultant – Social IDA / 61720 Prior Open 312,150.00 283,772.81 Signed 2018-01-15 2018-02-21 2018-03-05 2018-08-01 2018-03-26 2018-08-10 2018-04-30 2018-08-17 2023-04-04 thening ant Selection and Environmental Safeguar ds MW-LWSP-28879-CS-INDV / I Institutional Capacity Streng Individual Consult ndividual Consultant – Monito IDA / 61720 Prior Open 312,150.00 272,139.77 Signed 2018-01-15 2018-02-21 2018-03-21 2018-08-01 2018-04-04 2018-08-09 2018-05-09 2018-08-17 2023-05-08 thening ant Selection ring and Evaluation MW-LWSP-28887-CS-INDV / I Institutional Capacity Streng Individual Consult ndividual Consultant - Sewar IDA / D2660 Prior Open 180,000.00 0.00 Canceled 2017-11-20 2018-03-22 2018-01-15 2018-02-05 2018-03-12 2019-09-11 thening ant Selection age Engineer MW-LWSP-28884-CS-INDV / I Institutional Capacity Streng Individual Consult ndividual Consultant - GIS an IDA / D2660 Prior Open 180,000.00 64,200.00 Signed 2017-11-20 2018-03-27 2018-01-15 2018-06-28 2018-02-05 2018-08-01 2018-03-12 2018-08-01 2019-09-11 thening ant Selection d Database Engineer MW-LWSP-31335-CS-INDV / I Institutional Capacity Streng Individual Consult ndividual Consultant - Institut IDA / D2660 Prior Open 180,000.00 179,560.00 Signed 2018-01-15 2018-03-22 2018-03-19 2018-09-13 2018-04-09 2018-10-20 2018-05-14 2018-10-25 2019-11-13 thening ant Selection ional/Financial Development Specialist MW-LWSP-54990-CS-INDV / Institutional Capacity Streng Individual Consult Procurement Specialist - Indi IDA / 61720 Prior Open 312,150.00 0.00 Canceled 2018-03-30 2018-04-04 2018-05-25 2018-06-15 2018-07-20 2023-07-19 thening ant Selection vidual Consultant MW-LWSP-71239-CS-CDS / C onsultancy Services for Detai IDA / 61720 Technical Assistance Prior Direct Selection Direct 265,370.60 0.00 Canceled 2018-07-27 2018-07-27 2018-07-27 2018-07-27 led Design of Diamphwe Mult ipurpose Dam and Associate d Structures MW-LWSP-73824-CS-CDS / IDA / D2660 Technical Assistance Prior Direct Selection Direct 180,000.00 0.00 Canceled 2018-08-13 2018-08-15 2018-08-17 2018-09-21 2021-09-20 Wastewater Engineer MW-LWSP-76631-CS-CDS / C onsultancy Services for Devel Institutional Capacity Streng opment of Dam Safety Mana IDA / 61720 Post Direct Selection Direct 300,000.00 0.00 Canceled 2018-09-14 2018-10-04 2018-12-08 2019-04-07 thening gement Plans for Kamuzu Da m 1 and Kamuzu Dam 2 MW-LWSP-79454-CS-CDS / P reparation of Environmental and Social Management Plan (ESMP) and Abbreviated Res IDA / 61720 Technical Assistance Post Direct Selection Direct 70,000.00 102,686.32 Completed 2018-10-05 2018-10-06 2018-10-15 2018-10-17 2018-12-12 2018-12-24 2019-01-26 2020-01-24 ettlement Plan (ARAP) for Pri ority Transmission Network R ehabilitation and Updating of ESMP and ARAP for Priority Di stribution Network Rehabilita tion MW-LWSP-82179-CS-INDV / Institutional Capacity Streng Individual Consult IDA / D2660 Prior Open 180,000.00 0.00 Canceled 2018-10-19 2018-11-04 2018-12-05 2019-01-04 2019-02-08 2022-02-07 Sewerage Engineer thening ant Selection MW-LWSP-86924-CS-INDV / I ndependent Expert on Dam S Institutional Capacity Streng Individual Consult IDA / 61720 Post Direct 25,000.00 0.00 Canceled 2018-11-16 2018-11-14 2018-11-26 2018-12-01 2019-01-05 2021-01-04 afety for Kamuzu Dam 1 and thening ant Selection 2 - Dam Specialist MW-LWSP-86933-CS-INDV / I ndependent Expert on Dam S Institutional Capacity Streng Individual Consult IDA / 61720 Post Direct 25,000.00 81,825.00 Signed 2018-11-16 2018-11-14 2018-11-26 2018-12-13 2018-12-01 2019-01-18 2019-01-05 2019-01-22 2021-01-04 afety for Kamuzu Dam 1 and thening ant Selection 2 - Geotechnical Engineering MW-LWSP-86935-CS-INDV / I ndependent Expert on Dam S Institutional Capacity Streng Individual Consult IDA / 61720 Post Direct 25,000.00 0.00 Canceled 2018-11-16 2018-11-14 2018-11-26 2018-12-01 2019-01-05 2021-01-04 afety for Kamuzu Dam 1 and thening ant Selection 2 - Mechanical & Electrical En gineering MW-LWSP-86948-CS-INDV / I ndependent Expert on Dam S Institutional Capacity Streng Individual Consult IDA / 61720 Post Direct 25,000.00 84,862.50 Signed 2018-11-16 2018-11-14 2018-11-26 2018-12-13 2018-12-01 2019-01-18 2019-01-05 2019-01-22 2021-01-04 afety for Kamuzu Dam 1 and thening ant Selection 2 - Hydraulic Engineering MW-LWSP-87905-CS-INDV / Consultancy Service for the Development of a Water Safe Institutional Capacity Streng Individual Consult IDA / 61720 Post Open 200,000.00 0.00 Canceled 2018-11-30 2018-11-26 2019-01-18 2019-02-08 2019-03-15 2019-09-11 ty Plan for Lilongwe City and thening ant Selection Technical Assistance for Lilon gwe Water Board in Implem entation of the Water Safety Plan Page 6 MW-LWSP-92013-CS-INDV / I ndependent Expert on Dam S Institutional Capacity Streng Individual Consult IDA / 61720 Post Direct 25,000.00 75,562.50 Signed 2018-12-19 2018-12-19 2018-12-21 2018-12-13 2019-01-11 2019-01-16 2019-02-15 2019-01-22 2021-02-14 afety for Kamuzu Dam 1 and thening ant Selection 2 - Structural Engineer MW-LWSP-92015-CS-INDV / I ndependent Expert on Dam S Institutional Capacity Streng Individual Consult afety for Kamuzu Dam 1 and IDA / 61720 Post Direct 25,000.00 82,825.00 Signed 2018-12-19 2018-12-19 2018-12-21 2018-12-13 2019-01-11 2019-01-16 2019-02-15 2019-01-22 2021-02-14 thening ant Selection 2 - Dam Instrumentation Spe cialist (Mechanical & Electric al Engineering) MW-LWSP-107846-CS-INDV / Institutional Capacity Streng Individual Consult IDA / D2660 Prior Direct 192,000.00 303,225.84 Signed 2019-03-29 2019-04-01 2019-04-08 2019-04-10 2019-04-29 2019-04-26 2019-06-03 2019-05-19 2021-06-02 Wastewater Engineer thening ant Selection MW-LWSP-109672-CS-CDS / External Audit for the Lilong Institutional Capacity Streng IDA / 61720 Post Direct Selection Direct 10,000.00 14,633.60 Completed 2019-04-12 2019-04-09 2019-04-27 2019-05-27 2019-07-01 2019-08-14 2019-07-31 2020-09-18 we Water and Sanitation Proj thening ect for the Year 2018 - 2019 MW-LWSP-115990-CS-INDV / CONSULTANCY SERVICES FO Individual Consult IDA / D2660 Technical Assistance Post Open 100,000.00 98,377.60 Signed 2019-05-31 2019-06-26 2019-08-02 2019-09-14 2019-08-23 2019-10-05 2019-09-27 2019-12-17 2020-02-24 R SANITATION FINANCING AN ant Selection D COST RECOVERY MODEL MW-LWSP-121218-CS-INDV / CONSULTANCY SERVICES FO Individual Consult IDA / D2660 Technical Assistance Post Open 70,000.00 206,250.00 Signed 2019-07-12 2019-07-24 2019-08-30 2019-09-14 2019-09-20 2019-10-05 2019-10-25 2019-12-17 2021-04-17 R PROVIDING STRATEGIC SU ant Selection PPORT TO LILONGWE CITY C OUNCIL MW-LWSP-165218-CS-CDS / Institutional Capacity Streng Provision of Training for Pres IDA / 61720 Post Direct Selection Direct 12,000.00 0.00 Canceled 2020-05-06 2020-05-16 2020-07-20 2021-01-16 thening sure Data Loggers MW-LWSP-161535-CS-CDS / Sewerage Assets Valuation fo IDA / 61720 Technical Assistance Post Direct Selection Direct 8,500.00 11,532.21 Completed 2020-05-04 2020-03-10 2020-05-14 2020-04-30 2020-07-18 2020-05-20 2021-01-14 2020-11-12 r Lilongwe City MW-LWSP-191420-CS-CDS / Institutional Capacity Streng Consultancy Services for Pro IDA / 61720 Post Direct Selection Direct 16,000.00 15,083.60 Signed 2020-09-08 2020-09-02 2020-09-18 2020-09-07 2020-11-22 2020-09-26 2021-05-21 thening vision of Audit Services MW-LWSP-206140-CS-CDS / CONSULTANCY SERVICES FO Water Distribution Network R DESIGN REVIEW AND AN U IDA / 61720 Rehabilitation, Expansion an Post Direct Selection Direct 700,000.00 0.00 Canceled 2020-11-30 2020-12-02 2020-12-15 2020-12-10 2021-02-18 2021-08-17 PDATE OF DETAILED DESIGN d NRW reduction S FOR DIAMPHWE DAM AND ASSOCIATED STRUCTURES MW-LWSP-223569-CS-INDV / Development and Implement Individual Consult IDA / 61720 Technical Assistance Post Open 50,000.00 0.00 Canceled 2021-03-16 2021-05-04 2021-05-25 2021-06-29 2021-12-26 ation of Culture Change Man ant Selection agement program MW-LWSP-234468-CS-INDV / Institutional Capacity Streng Individual Consult IDA / 61720 Post Open 60,000.00 69,451.26 Signed 2021-05-21 2021-05-13 2021-06-23 2021-10-20 2021-07-07 2021-10-25 2021-08-04 2021-11-08 2022-08-04 Environmental Safeguards Sp thening ant Selection ecialist MW-LWSP-261298-CS-INDV / Independent Verification Exp Water Distribution Network Individual Consult ert for Performance-Based C IDA / 61720 Rehabilitation, Expansion an Post 100,000.00 0.00 Signed 2021-11-30 2021-11-09 2022-02-03 2022-06-20 2022-02-24 2022-07-11 2022-03-31 2024-03-30 ant Selection ontract (PBC) for Non-Revenu d NRW reduction e Water (NRW) Reduction in Lilongwe City MW-LWSP-262339-CS-CDS / Consultancy Services for Pro IDA / 61720 Technical Assistance Post Direct Selection Direct 15,000.00 39,159.40 Signed 2021-11-22 2021-11-19 2021-12-02 2021-11-23 2022-02-05 2021-11-30 2022-08-04 vision of External Audit Servi ces MW-LWSP-285762-CS-CDS / UPDATING OF ENVIRONMENT AL AND SOCIAL IMPACT ASSE IDA / D9350 Technical Assistance Post Direct Selection Direct 70,000.00 0.00 Signed 2022-04-15 2022-03-25 2022-04-30 2022-05-10 2022-07-04 2022-10-02 SSMENT AND RESETTLEMENT ACTION PLAN FOR PRIORITY SEWERAGE REHABILITATION MW-LWSP-285764-CS-CDS / UPDATING OF THE ENVIRON MENTAL AND SOCIAL MANAG IDA / 70070 Technical Assistance Post Direct Selection Direct 70,000.00 0.00 Signed 2022-04-15 2022-03-25 2022-04-30 2022-05-10 2022-07-04 2022-10-02 EMENT PLAN AND RESETTLE MENT ACTION PLAN FOR THE WATER DISTRIBUTION NETW ORK EXPANSION INVESTMEN TS MW-LWSP-304025-CS-CDS / Direct - Internation Provision of Consultancy Serv IDA / 70070 Technical Assistance Post Direct Selection 20,000.00 0.00 Signed 2022-08-30 2022-08-10 2022-09-09 2022-09-01 2022-11-13 2023-05-12 al ices for an Audit of ISO 9001 Certification MW-LWSP-304032-CS-CDS / Activation of Sewer Service i Institutional Capacity Streng Direct - Internation Pending Impleme IDA / 70070 Post Direct Selection 7,000.00 0.00 2022-08-31 2022-09-10 2022-11-14 2023-05-13 n EDAMS Billing and Custom thening al ntation er Information System MW-LWSP-318357-CS-CDS / Construction Supervision of L Direct - Internation Under Implement IDA / D9350 Technical Assistance Post Direct Selection 1,000,000.00 0.00 2022-10-14 2022-10-05 2022-11-11 2022-10-25 2022-12-30 2024-12-29 ilongwe City Sewerage Netw al ation ork Expansion - Priority 2 MW-LWSP-319392-CS-INDV / Priority Sanitation Improvem Individual Consult IDA / D9350 Post Open - National 72,000.00 0.00 Signed 2022-10-07 2022-10-05 2022-12-02 2022-12-09 2022-12-23 2022-12-19 2024-01-06 2024-07-04 Sanitation Marketing Speciali ents ant Selection st Page 7 PROCUREMENT PLAN (Textual Part) Project information: [West Bank and Gaza] [Finance for Jobs II] [P- 159337] Project Implementation agency: [DAI GLOBAL, LLC] Date of the Procurement Plan: [26-Jan-2021] Period covered by this Procurement Plan: [26-Jan- 2021 – to 15-Oct- 2023] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The procurement under the project will be carried out following well- established private sector procurement arrangements or commercial practices, acceptable to the World Bank as specified in Paras 6.46 and 7.26 of the Bank’s Procurement regulations Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods). Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is not Applicable. PROCUREMENT West Bank and Gaza : Finance for Jobs II PLAN General Information Country: West Bank and Gaza 2021-01-26 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P159337 GPN Date: Project Name: Finance for Jobs II Loan / Credit No: TF / A5297, TF / A8159, TF / B5070 DAI Global, LLC Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-DAI GLOBAL-270181-NC- Investment Co-Financing Fac Request for Quota Single Stage - One E TF / A8159 Post Limited 8,000.00 7,308.00 Signed 2021-12-28 2022-01-10 2022-01-20 2022-01-18 2022-04-20 RFQ / ICF promotional Video ility (ICF) tions nvelope CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-DAI GLOBAL-226037-CS-I Investment Co-Financing Fac Quality And Cost- TF / A5297 Post Open - National 300,000.00 48,720.00 Signed 2021-04-28 2021-03-30 2021-05-19 2021-07-02 2021-05-24 2021-07-30 2021-07-06 2021-08-29 2021-07-08 2021-10-03 2021-07-08 2021-11-07 2021-08-25 2022-11-07 NDV / business development ility (ICF) Based Selection services GZ-DAI GLOBAL-340212-CS- QCBS / Financial and Technic Quality And Cost- al Audit for Finance for Jobs P TF / B5070 Project Management Post Open - National 80,000.00 0.00 Signed 2023-02-02 2023-02-06 2023-02-23 2023-02-28 2023-02-06 2023-03-07 2023-02-28 2023-03-21 2023-03-07 2023-04-10 2023-03-20 2023-04-30 2024-05-31 Based Selection roject for work completed fro m 1/1/2022 to 05/31/2024. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-DAI GLOBAL-213097-CS-I Investment Co-Financing Fac Individual Consult NDV / Local Technical Expert TF / A5297 Post Limited 5,000.00 1,400.00 Signed 2021-01-30 2021-03-03 2021-02-04 2021-03-18 2021-02-25 2021-03-14 2021-04-01 2021-03-29 2021-10-30 ility (ICF) ant Selection s – Agricultural Expert for 2 P rojects Gaza GZ-DAI GLOBAL-213170-CS-I NDV / Local Technical Expert Investment Co-Financing Fac Individual Consult TF / A8159 Post Limited 2,500.00 350.00 Signed 2021-02-01 2021-02-14 2021-02-06 2021-03-04 2021-02-27 2021-03-15 2021-04-03 2021-03-16 2021-10-31 s – Agricultural Expert for 1 P ility (ICF) ant Selection roject West Bank GZ-DAI GLOBAL-213172-CS-I NDV / Local Technical Expert Investment Co-Financing Fac Individual Consult TF / A8159 Post Limited 2,500.00 1,400.00 Signed 2021-02-01 2021-03-03 2021-02-06 2021-03-24 2021-02-27 2021-04-04 2021-04-03 2021-04-06 2021-10-31 – Renewal Energy Expert for ility (ICF) ant Selection 1 Project West Bank GZ-DAI GLOBAL-213175-CS-I NDV / Environmental Screeni Investment Co-Financing Fac Individual Consult TF / A8159 Post Direct 1,800.00 1,818.00 Signed 2021-02-01 2021-02-17 2021-02-11 2021-02-21 2021-03-04 2021-02-22 2021-04-08 2021-02-23 2021-10-05 ng and Categorization for Ga ility (ICF) ant Selection za ICF -Shortlisted Projects GZ-DAI GLOBAL-213176-CS-I NDV / Environmental Screeni Investment Co-Financing Fac Individual Consult TF / A8159 Post Direct 2,250.00 2,250.00 Signed 2021-02-01 2021-01-14 2021-02-11 2021-01-17 2021-03-04 2021-01-18 2021-04-08 2021-01-19 2021-10-05 ng and Categorization for We ility (ICF) ant Selection st Bank ICF -Shortlisted Proje cts GZ-DAI GLOBAL-215109-CS-I Individual Consult NDV / Contract Renewal - Pro TF / A5297 Project Management Post Direct 148,566.27 148,566.27 Signed 2021-07-20 2021-01-10 2021-07-20 2021-07-13 2021-07-25 2021-07-13 2021-08-01 2021-07-14 2022-07-31 ant Selection ject Manager GZ-DAI GLOBAL-215111-CS-I Individual Consult NDV / Contract Renewal - Fin TF / A5297 Project Management Post Direct 30,186.75 30,212.38 Signed 2021-07-20 2021-02-10 2021-07-26 2021-07-13 2021-07-27 2021-07-13 2021-08-01 2021-07-14 2022-07-31 ant Selection ancial Management Specialis t GZ-DAI GLOBAL-215112-CS-I Individual Consult NDV / Contract Renewal - Ga TF / A5297 Project Management Post Direct 31,667.22 32,617.22 Signed 2021-07-20 2021-01-01 2021-07-26 2021-08-19 2021-07-27 2021-07-13 2021-08-01 2021-08-01 2022-07-31 ant Selection za Coordinator GZ-DAI GLOBAL-215113-CS-I Individual Consult NDV / Contract Renewal - Co TF / A5297 Project Management Post Direct 20,553.04 20,553.04 Signed 2021-07-20 2021-03-31 2021-07-26 2021-07-13 2021-07-27 2021-07-13 2021-08-01 2021-07-14 2022-07-31 ant Selection mmunication Specialist GZ-DAI GLOBAL-215114-CS-I Individual Consult NDV / Contract Renewal - Pro TF / A5297 Project Management Post Direct 62,719.56 62,719.56 Signed 2021-07-20 2021-04-11 2021-07-26 2021-07-13 2021-07-27 2021-07-13 2021-08-01 2021-07-14 2022-07-31 ant Selection ject Finance & Investment Of ficer GZ-DAI GLOBAL-215116-CS-I Individual Consult NDV / Contract Renewal - Mo TF / A5297 Project Management Post Direct 44,212.47 44,212.47 Terminated 2021-07-20 2021-04-11 2021-07-26 2021-07-13 2021-07-27 2021-07-13 2021-08-01 2021-07-14 2022-07-31 ant Selection nitoring and Evaluation Speci alist Page 1 GZ-DAI GLOBAL-215117-CS-I Individual Consult NDV / Contract Renewal - Offi TF / A5297 Project Management Post Direct 25,110.54 25,863.85 Signed 2021-07-20 2021-02-28 2021-07-26 2021-07-13 2021-07-27 2021-07-13 2021-08-01 2021-07-14 2022-07-31 ant Selection ce Administrator GZ-DAI GLOBAL-222340-CS-I Individual Consult NDV / Project Finance & Inve TF / A5297 Project Management Post Open 65,000.00 30,000.00 Terminated 2021-03-02 2021-02-10 2021-03-19 2021-03-08 2021-04-12 2021-03-28 2021-05-15 2021-03-26 2022-05-15 ant Selection stment Officer GZ-DAI GLOBAL-229871-CS-I NDV / Hiring a consultant to Individual Consult TF / A5297 Project Management Post Limited 20,000.00 20,000.00 Signed 2021-04-25 2021-05-03 2021-04-30 2021-05-27 2021-05-21 2021-06-17 2021-06-25 2021-06-25 2022-03-22 prepare an Implementation C ant Selection ompletion Results Report for Finance for Jobs I GZ-DAI GLOBAL-260871-CS-I NDV / Environmental and Soc Investment Co-Financing Fac Individual Consult TF / A8159 Post Direct 15,750.00 15,750.00 Signed 2021-11-10 2021-11-29 2021-11-15 2021-12-05 2021-11-20 2021-12-05 2021-12-01 2021-12-06 2022-12-01 ial Screening / Audit and Cat ility (ICF) ant Selection egorization for ICF Shortlisted Sub-Projec ts GZ-DAI GLOBAL-263667-CS-I NDV / Technical Due Diligenc Investment Co-Financing Fac Individual Consult TF / B5070 Post Limited 3,200.00 2,400.00 Signed 2021-11-22 2021-11-29 2021-11-27 2021-12-15 2021-12-02 2021-12-27 2021-12-10 2021-12-28 2022-03-10 e for Abu Eita’s Diary Product ility (ICF) ant Selection ion Hub F4J ICF Grant Suppor t GZ-DAI GLOBAL-264346-CS-I NDV / Environmental and Soc Investment Co-Financing Fac Individual Consult TF / B5070 Post Direct 8,750.00 15,190.00 Signed 2021-11-22 2021-11-29 2021-11-24 2021-12-05 2021-11-27 2021-12-05 2021-12-02 2021-12-07 2022-12-02 ial Impact Monitoring for a Gr ility (ICF) ant Selection oup of Selected Subprojects GZ-DAI GLOBAL-264347-CS-I NDV / Environmental and Soc Investment Co-Financing Fac Individual Consult ial Impact Monitoring for BIT TF / B5070 Post Direct 9,750.00 9,000.00 Signed 2021-11-22 2021-11-29 2021-11-28 2021-12-02 2021-12-01 2021-12-05 2021-12-05 2021-12-10 2022-12-05 ility (ICF) ant Selection C Garden for Agricultural Mar keting’s Pickling Facility Proje ct GZ-DAI GLOBAL-270184-CS-I Individual Consult NDV / Contract Renewal - F4J TF / A8159 Project Management Post Direct 31,665.00 31,665.40 Signed 2021-12-21 2021-12-10 2021-12-25 2021-12-12 2021-12-27 2021-12-14 2021-12-31 2021-12-27 2022-12-31 ant Selection Procurement Specialist GZ-DAI GLOBAL-299446-CS-I NDV / Environmental and Soc ial Screening , Environmenta Investment Co-Financing Fac Individual Consult TF / B5070 Post Limited 17,000.00 0.00 Signed 2022-06-13 2022-06-16 2022-06-18 2022-06-21 2022-06-23 2022-06-23 2022-07-03 2023-07-02 l and Social Management Pla ility (ICF) ant Selection n (ESMP)\ Audit , E&S Monit oring for ICF Shortlisted Proj ects GZ-DAI GLOBAL-301874-CS-I Individual Consult NDV / Hiring a new Project Fi TF / A8159 Project Management Post Limited 42,000.00 0.00 Signed 2022-06-28 2022-06-29 2022-07-03 2022-06-29 2022-07-08 2022-08-01 2022-08-03 2023-08-03 ant Selection nance & Investment Officer GZ-DAI GLOBAL-305002-CS- Individual Consult CDS / Monitoring & Evaluatio TF / A8159 Project Management Post Direct - National 8,820.00 0.00 Signed 2022-08-02 2022-08-01 2022-08-04 2022-07-31 2022-08-09 2022-07-31 2022-08-15 2022-11-30 ant Selection n Consultant for F4J project GZ-DAI GLOBAL-316735-CS- CDS / Hiring consultant for E Investment Co-Financing Fac Individual Consult nvironmental and Social Imp TF / A8159 Post Direct - National 12,000.00 0.00 Signed 2022-09-19 2022-09-21 2022-09-23 2022-12-06 2022-09-25 2022-12-06 2022-09-28 2023-09-28 ility (ICF) ant Selection act Monitoring for a Group of Selected ICF Subprojects GZ-DAI GLOBAL-317347-CS-I Individual Consult NDV / Hiring Investment Asso TF / A8159 Project Management Post Open - National 15,600.00 0.00 Signed 2022-09-22 2022-10-02 2022-10-15 2022-11-07 2022-10-25 2022-11-07 2022-11-20 2023-11-20 ant Selection ciate for F4J project GZ-DAI GLOBAL-317348-CS-I Investment Co-Financing Fac Individual Consult Under Implement NDV / Hiring short-term busin TF / A8159 Post Open - National 17,500.00 0.00 2022-10-02 2022-10-02 2022-10-29 2022-11-08 2022-11-24 2023-11-24 ility (ICF) ant Selection ation ess consultant 2 -West Bank GZ-DAI GLOBAL-317350-CS-I Investment Co-Financing Fac Individual Consult NDV / Hiring short-term busin TF / A8159 Post Open - National 17,500.00 0.00 Signed 2022-10-02 2022-10-02 2022-10-29 2022-10-18 2022-11-08 2022-11-07 2022-11-24 2023-11-24 ility (ICF) ant Selection ess consultant - West Bank GZ-DAI GLOBAL-317351-CS-I Investment Co-Financing Fac Individual Consult NDV / Hiring short-term busin TF / A8159 Post Open - National 15,000.00 0.00 Canceled 2022-10-02 2022-10-02 2022-10-29 2022-11-08 2022-11-24 2023-11-24 ility (ICF) ant Selection ess consultant 2 - Gaza GZ-DAI GLOBAL-317352-CS-I Investment Co-Financing Fac Individual Consult NDV / Hiring short-term busin TF / A8159 Post Open - National 15,000.00 0.00 Canceled 2022-10-02 2022-10-02 2022-10-29 2022-11-08 2022-11-24 2023-11-24 ility (ICF) ant Selection ess consultant - Gaza GZ-DAI GLOBAL-318769-CS-I Investment Co-Financing Fac Individual Consult NDV / Environmental and Soc TF / A8159 Post Direct - National 5,400.00 0.00 Signed 2022-10-10 2022-10-02 2022-10-17 2022-10-24 2022-10-21 2022-10-27 2022-10-24 2023-10-24 ility (ICF) ant Selection ial Screening / Audit Consulta nt GZ-DAI GLOBAL-327041-CS-I Investment Co-Financing Fac Individual Consult NDV / Hiring an Investment O TF / A8159 Post Limited 28,900.00 0.00 Canceled 2022-11-17 2022-11-24 2022-11-27 2022-11-07 2022-12-07 2022-12-05 2023-01-01 2024-01-01 ility (ICF) ant Selection fficer/Consultant GZ-DAI GLOBAL-328852-CS-I Investment Co-Financing Fac Individual Consult NDV / Hiring Business Consul TF / A8159 Post Open - National 35,000.00 0.00 Signed 2022-11-28 2022-12-04 2022-12-03 2022-10-17 2022-12-05 2022-12-13 2022-12-08 2023-12-08 ility (ICF) ant Selection tant Expert (1) - Gaza GZ-DAI GLOBAL-328855-CS-I Investment Co-Financing Fac Individual Consult NDV / Hiring Business Consul TF / A8159 Post Open - National 35,000.00 0.00 Signed 2022-11-28 2022-12-04 2022-12-02 2022-10-17 2022-12-04 2022-12-13 2022-12-08 2023-12-08 ility (ICF) ant Selection tant Expert (2) - Gaza GZ-DAI GLOBAL-328856-CS-I NDV / Hiring Direct Jobs Crea tion Verification/validation an Investment Co-Financing Fac Individual Consult TF / A8159 Post Open - National 25,000.00 0.00 Signed 2022-11-28 2022-12-04 2022-12-17 2023-01-11 2022-12-20 2023-01-18 2023-01-13 2023-04-13 d Measurement of Indirect Jo ility (ICF) ant Selection bs of Investment Co-Financin g Facility (ICF) Supported Pro jects GZ-DAI GLOBAL-340195-CS- CDS / Hiring an Environment al and Social Consultant to c arry out: Individual Consult Updating F4J’s ESMF - Develo TF / B5070 Project Management Post Direct - National 12,000.00 0.00 Signed 2023-02-05 2023-02-07 2023-02-13 2023-02-05 2023-02-16 2023-02-09 2023-02-22 2023-06-22 ant Selection ping Environmental and Soci al Commitment Plan (ESCP) - Developing Labor Manageme nt Procedures (LMP) - Develo ping Stakeholder Engagemen t Plan (SEP) Page 2 GZ-DAI GLOBAL-346031-CS-I Individual Consult NDV / Procurement and Oper TF / B5070 Project Management Post Limited 42,000.00 0.00 Signed 2023-02-28 2023-03-05 2023-03-05 2023-03-06 2023-03-26 2023-04-09 2023-04-16 2024-04-15 ant Selection ations Specialist for F4J Proje ct GZ-DAI GLOBAL-346033-CS- CDS / Environmental and Soc Individual Consult ial Screening / Audit and Cat TF / B5070 Project Management Post Direct - National 7,500.00 0.00 Signed 2023-03-07 2023-03-09 2023-03-11 2023-04-25 2023-03-13 2023-04-25 2023-03-17 2023-09-13 ant Selection egorization for ICF Shortliste d Sub-Projects (Gaza) - Cons ultant GZ-DAI GLOBAL-346036-CS- Individual Consult CDS / M&E Consultant Contra TF / B5070 Project Management Post Direct - National 9,450.00 0.00 Signed 2023-03-07 2023-03-01 2023-03-09 2023-03-12 2023-03-10 2023-03-12 2023-03-12 2023-06-10 ant Selection ct Renewal GZ-DAI GLOBAL-351343-CS-I NDV / Environmental and Soc Individual Consult ial Screening / Audit and Cat TF / B5070 Project Management Post Direct - National 6,000.00 0.00 Signed 2023-03-21 2023-03-23 2023-03-28 2023-04-13 2023-03-30 2023-04-13 2023-04-03 2023-09-30 ant Selection egorization for ICF Shortliste d Sub-Projects (West Back) - Consultant GZ-DAI GLOBAL-327041-CS - Investment Co-Financing Fac Individual Consult TF / A8159 Post Open - National 28,900.00 0.00 Signed 2022-11-17 2022-11-17 2022-12-12 2022-11-17 2022-12-17 2022-11-23 2022-12-31 2023-12-31 INDV / Hiring an Investment ility (ICF) ant Selection Officer GZ-DAI GLOBAL-355718-CS-I NDV / Hiring Technical Expert Investment Co-Financing Fac Individual Consult TF / B5070 Post Limited 2,000.00 0.00 Signed 2023-04-10 2023-04-10 2023-04-12 2023-04-25 2023-04-14 2023-04-26 2023-04-20 2023-10-17 to review Silo and steel struc ility (ICF) ant Selection ture design and related biddi ng documentation. GZ-DAI GLOBAL-360971-CS-I NDV / Environmental and Soc Individual Consult TF / B5070 Project Management Post Direct - National 20,700.00 0.00 Signed 2023-05-11 2023-05-15 2023-05-19 2023-05-23 2023-05-23 2023-05-23 2023-05-29 2024-05-28 ial Management Plan (ESMP) ant Selection for ICF Projects in pipeline GZ-DAI GLOBAL-364119-CS-I Individual Consult NDV / M&E Consultant Contra TF / B5070 Project Management Post Direct - National 9,450.00 0.00 Signed 2023-05-31 2023-05-30 2023-06-05 2023-06-05 2023-06-08 2023-06-11 2023-06-12 2023-09-10 ant Selection ct renewal for additional thre e months GZ-DAI GLOBAL-366660-CS-I Investment Co-Financing Fac Individual Consult Under Implement NDV / Environmental and Soc TF / B5070 Post Open - National 45,000.00 0.00 2023-06-18 2023-06-26 2023-07-17 2023-07-29 2023-09-02 2024-08-31 ility (ICF) ant Selection ation ial Specialist Page 3 PROCUREMENT PLAN General 1. Project Information a. Country: Federal Republic of Somalia b. Project Name: Somalia Recurrent Cost and Reform Financing Project – Phase III c. Project Number: P173731 d. Total Finance: USD 68,000,000 2. Project Implementation Agency: Ministry of Finance, Federal Government of Somalia 3. Date of Project Plan: 7 June 2021 4. Period Covered by this Procurement: June 2021 – December 2022 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised November 2017, August 2018 and November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Document: The Bank’s standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified into Procurement Plan tables in STEP III. National Procurement Arrangements: Not applicable IV. Prequalification: Not applicable V. Leased Assets: Not Applicable VI. Procurement of Second-hand Goods: Not Applicable VII. Domestic Preference: Not Applicable 1 VIII. Hands on Expanded Implementation Support (HEIS): Not applicable IX. Other Relevant Procurement Information: Not Applicable X. Thresholds for Procurement Approaches and Method (US$ millions) Based on the risks identified above, the following procurement arrangements are proposed: a) Approach to Market: Based on previous experience and available local market, the following threshold will be used of open national/international and RFQ bidding (all figures in million USD) Table 1.2: Thresholds for procurement approaches and methods Procurement Methods (US$ millions)–Goods, Works, and Non- Consulting Services Open Open Request for Direct Category Internatio National Quotation Selection nal (RfQ) Works ≥ 5.0 <5.0 ≤ 0.2 All Values Goods, IT, and non- ≥ 0.5 <0.5 ≤ 0.1 All Values consultin g services Thresholds for Procurement Approaches and Methods (US$, millions) – Consulting Services Category Short List of National Consultants Consulting Engineering and Services Construction Supervision Consultants (Firms) ≤ 0.1 ≤ 0.2 Individual Consultants N.A. N.A. Direct Selection Consultants (Firms) All Values All Values Individual Consultants All Values All Values 2 3 XI. Table Packages for Goods, Works and Non-Consulting Services (At Negotiations – to be entered in STEP) Market Selecti Procurem Revi Approa on Evaluatio ent ew Expected Expected ch Metho n Options Process Contract Estimat by date of date of Ref. (Open- d (BAFO (Single Descripti ed Cost Bank bid/ Contract No Nation (RFP, Rated stage- on (US$) (Prio proposal Signatur al/ RFB, Criteria single r/ opening e Limited RFQ etc.) envelope Post) etc.) etc.) etc.) Goods Supply of Single Smart Most stage One- Open 02/July/20 30/July/20 G1 Phones 300,000. Prior RFB advantage Envelop National 21 21 with Solar 00 ous Bid System Office Furniture Most Single 28/June/2 25/July/20 Limited G2 for RCRF 22,000.0 Prior RFQ advantage stage One- 021 21 National PIU 0 ous Bid Envelop Offices 322,00 Subtotal (Goods) 0.00 Non-Consulting Services Provision of Most Single 20/June/2 01/July/20 12,000.0 Limited NC1 WhatsApp Prior DS advantage stage One- 021 21 0 National Messagin ous Bid Envelop g Services Translatio Most 50,000.0 Limited Single 20/June/2 10/July/20 NC2 n, Voice Prior RFP advantage 0 National stage One- 021 21 Over ous Bid Envelop 1 Market Selecti Procurem Revi Approa on Evaluatio ent ew Expected Expected ch Metho n Options Process Contract Estimat by date of date of Ref. (Open- d (BAFO (Single Descripti ed Cost Bank bid/ Contract No Nation (RFP, Rated stage- on (US$) (Prio proposal Signatur al/ RFB, Criteria single r/ opening e Limited RFQ etc.) envelope Post) etc.) etc.) etc.) Recording Service Event Most Managem 60,000.0 Limited Single 20/June/2 10/July/20 NC3 Prior RFP advantage ent 0 National stage One- 021 21 ous Bid Services Envelop Subtotal 122,00 (Non-consulting) 0.00 Consulting Services. Market Expected Method Expected Contract Estimate Review by Approach Date of Ref (QCBS, Date of Descriptio d Cost Bank (Open- Bid No. LCBCS, Contract n (US$) (Prior/Post) National/ Proposal QBS, DS Signature Limited etc.) Opening Health 4,300,000. C1 Technical Prior Direct DS 01/March/2 30/March/20 00 Partner 021 21 ICT based Community Engagement 20/June/202 10/July/2021 150,000.0 Limited C2 and Prior CQS 1 0 National Feedback (Call Centre) Service 2 Consulting Services. Market Expected Method Expected Contract Estimate Review by Approach Date of Ref (QCBS, Date of Descriptio d Cost Bank (Open- Bid No. LCBCS, Contract n (US$) (Prior/Post) National/ Proposal QBS, DS Signature Limited etc.) Opening Mass Media Activity for 27/June/202 01/August/2 C3 100,000.0 Prior Open National CQS Citizen 1 021 0 Engagement Community Mobilization 100,000.0 27/June/202 01/August/2 C4 Prior Open National CQS for Citizen 0 1 021 Engagement Procuremen DS 01/March/2 01/April/202 C5 t Specialist 180,000 Prior Direct 021 1 MoH Financial Managemen 14/June/202 1/July/2021 C6 180,000 Prior Direct t Specialist DS 1 MoH HR 20/June/202 15/July/2021 Limited C7 Governance 60,000.00 Prior INDV 1 National Advisor Communicat ion and Open 20/June/202 01/August/2 C8 60,000.00 Prior INDV Reporting International 1 021 Specialist Health 28/June/202 01/August/2 Limited C9 Program 70,000.00 Prior INDV 1 021 National Coordinator Subtotal 5,200,00 Consulting service 0.00 3 Consulting Services. Market Expected Method Expected Contract Estimate Review by Approach Date of Ref (QCBS, Date of Descriptio d Cost Bank (Open- Bid No. LCBCS, Contract n (US$) (Prior/Post) National/ Proposal QBS, DS Signature Limited etc.) Opening Grand Total (Goods+ 5,644,00 Non-consulting + 0.00 Consulting Services) 4 PROCUREMENT Somalia : Somalia Recurrent Cost & Reform Financing Project - Phase 3 PLAN General Information Country: Somalia 2021-06-15 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173731 GPN Date: 2021-06-14 Project Name: Somalia Recurrent Cost & Reform Financing Project - Phase 3 Loan / Credit No: IDA / D6580 Federal Government of Somalia Ministry of Finance Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-239594-GO-RFQ / O Component 5: Project Manag Request for Quota Single Stage - One E IDA / D6580 Prior Limited 22,000.00 23,840.00 Signed 2021-06-22 2021-07-28 2021-07-27 2021-08-15 2021-09-10 ffice Equipment for RCRF PIU ement tions nvelope Offices Component 3: Transfers for SO-MOF-238764-GO-RFB / Pr core government functions a Single Stage - One E ocurement of Android Smart IDA / D6580 nd foundational education h Prior Request for Bids Open - National 300,000.00 213,350.00 Signed 2021-06-16 2021-06-16 2021-06-18 2021-06-17 2021-07-16 2021-07-25 2021-08-05 2021-09-07 2021-08-24 2021-09-30 2021-10-08 nvelope Phones with Solar System ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-240070-GO-RFQ / P core government functions a Request for Quota Single Stage - One E urchase of Vehicle (4x4 Doub IDA / D6580 nd foundational education h Prior Limited 40,000.00 0.00 Canceled 2021-07-01 2021-08-19 2021-10-18 tions nvelope le Cabin Pick Up) for MOH PIU ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-240071-GO-RFQ / P core government functions a Request for Quota Single Stage - One E urchase of Office Furniture fo IDA / D6580 nd foundational education h Prior Limited 40,000.00 0.00 Canceled 2021-07-03 2021-08-21 2021-10-05 tions nvelope r MoH PIU ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-243680-GO-RFQ / P core government functions a Request for Quota Single Stage - One E urchase of Vehicle for MoH PI IDA / D6580 nd foundational education h Prior Limited 40,000.00 40,000.00 Signed 2021-07-22 2021-10-06 2021-09-09 2021-10-22 2021-10-24 tions nvelope U ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-244019-GO-RFQ / P core government functions a Request for Quota Single Stage - One E urchase of Office Furniture fo IDA / D6580 nd foundational education h Prior Limited 28,000.00 27,880.00 Signed 2021-07-21 2021-10-13 2021-08-19 2021-10-25 2021-09-09 tions nvelope r MoH PIU ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-244027-GO-RFQ / Pr core government functions a ocurement of Supply and Del Request for Quota Single Stage - One E IDA / D6580 nd foundational education h Prior Limited 13,000.00 24,050.00 Signed 2021-07-22 2021-10-14 2021-08-20 2021-12-21 2021-09-10 ivery of IT Equipment’s for M tions nvelope ealth service delivery mecha oH PIU nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-253188-GO-RFQ / O core government functions a Request for Quota Single Stage - One E ffice Equipment for Hirshabel IDA / D6580 nd foundational education h Prior Limited 17,300.00 0.00 Canceled 2021-09-20 2021-10-23 2021-11-22 tions nvelope le MoH ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-255298-GO-RFQ / S core government functions a Request for Quota Single Stage - One E upply of ICT and Office Equip IDA / D6580 nd foundational education h Prior Limited 9,050.00 9,740.00 Signed 2021-10-06 2022-01-02 2021-11-02 2022-01-26 2022-05-01 tions nvelope ment for HSS - MoH. ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-255302-GO-RFQ / S core government functions a Request for Quota Single Stage - One E upply of Office Furniture for IDA / D6580 nd foundational education h Prior Limited 8,250.00 8,400.00 Signed 2021-10-07 2022-01-02 2021-11-03 2022-01-26 2022-05-02 tions nvelope Hirshabelle State - MoH. ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-258810-GO-RFQ / S Component 3: Transfers for upply of Office furniture and core government functions a Request for Quota Single Stage - One E Equipment for GSS External IDA / D6580 nd foundational education h Prior Limited 18,890.00 17,890.00 Signed 2021-10-29 2022-01-02 2021-11-23 2022-02-27 2021-12-23 tions nvelope Assistance Fiduciary Section ealth service delivery mecha (EAFS) and the GSS - MOH PI nisms in elig ible Federal Me U offices. mber States (FMS) SO-MOF-258815-GO-RFQ / S Component 3: Transfers for upply of ICT for the GSS MoF core government functions a Request for Quota Single Stage - One E External Assistance Fiduciary IDA / D6580 nd foundational education h Prior Limited 16,090.00 16,250.00 Signed 2021-10-29 2022-01-02 2021-11-25 2022-02-25 2021-12-25 tions nvelope Section (EAFS) and the ealth service delivery mecha MOH PIU offices. nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-268882-GO-RFQ / P core government functions a urchase of 4x4 Seven Seater Request for Quota Single Stage - One E IDA / D6580 nd foundational education h Prior Limited 40,000.00 36,500.00 Signed 2021-12-28 2022-03-28 2022-02-11 2022-05-23 2022-03-28 Station Wagon (Toyota Prado tions nvelope ealth service delivery mecha or Equivalent) nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-274468-GO-RFQ / S core government functions a upply of office furniture and Request for Quota Single Stage - One E IDA / D6580 nd foundational education h Prior Limited 25,000.00 24,930.00 Signed 2022-01-31 2022-04-25 2022-02-18 2022-07-27 2022-08-17 equipment for Ministry of Ed tions nvelope ealth service delivery mecha ucation nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-324962-GO-RFQ / S core government functions a upply of Office Furniture and Request for Quota Single Stage - One E Under Imple IDA / D6580 nd foundational education h Prior Limited 21,000.00 0.00 2022-11-13 2022-12-15 2022-12-01 2023-01-15 Equipment for MoF - South W tions nvelope mentation ealth service delivery mecha est nisms in elig ible Federal Me mber States (FMS) Page 1 SO-MOF-332532-GO-RFQ / S Component 5: Project Manag Request for Quota Single Stage - One E Pending Impl upply of Office Furniture and IDA / D6580 Prior Limited 50,000.00 0.00 2022-12-26 2023-02-03 2023-03-20 ement tions nvelope ementation Equipment for RCRF - PIU Offi ce Component 3: Transfers for SO-MOF-354692-GO-RFB / S core government functions a upply and Delivery of Mobile Single Stage - One E Under Imple IDA / D6580 nd foundational education h Prior Request for Bids Open - National 180,000.00 0.00 2023-04-10 2023-05-09 2023-04-15 2023-06-07 2023-05-27 2023-06-11 2023-06-25 2023-08-09 devices, Tablets and Solar Ch nvelope mentation ealth service delivery mecha arging Solutions nisms in elig ible Federal Me mber States (FMS) SO-MOF-362174-GO-RFQ / O Component 5: Project Manag Request for Quota Single Stage - One E ffice Furniture and renovatio IDA / D6580 Prior Limited 20,000.00 0.00 Canceled 2023-05-25 2023-06-16 2023-07-31 ement tions nvelope n for RCRF Office - FGS Component 3: Transfers for SO-MOF-364142-GO-RFQ / S core government functions a Request for Quota Single Stage - One E Pending Impl upply of ICT and equipment f IDA / D6580 nd foundational education h Prior Limited 10,000.00 0.00 2023-06-05 2023-07-11 2023-08-25 tions nvelope ementation or MOECHE - FGS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-364505-GO-RFQ / P Component 5: Project Manag Request for Quota Single Stage - One E Under Imple urchase of Office Furniture a IDA / D6580 Prior Limited 5,200.00 0.00 2023-06-08 2023-07-14 2023-08-28 ement tions nvelope mentation nd Equipment for RCRF Offic e NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-238775-NC-DIR / W Component 4: Citizen Engag IDA / D6580 Prior Direct Selection Direct 12,000.00 14,652.00 Signed 2021-06-16 2021-06-16 2021-06-19 2021-06-17 2021-07-02 2021-12-13 2022-07-02 hatsApp Messaging Services ement and Feedback SO-MOF-238778-NC-RFQ / Tr Component 4: Citizen Engag Request for Quota Single Stage - One E IDA / D6580 Prior Limited 50,000.00 35,595.00 Signed 2021-06-20 2021-06-29 2021-07-23 2021-08-02 2022-07-23 anslation Voice over Recordi ement and Feedback tions nvelope ng Services SO-MOF-238779-NC-RFQ / E Component 5: Project Manag Request for Quota Single Stage - One E IDA / D6580 Prior Limited 60,000.00 69,125.00 Signed 2021-06-19 2021-06-29 2021-07-20 2021-08-08 2021-08-25 vents Management Services ement tions nvelope Component 3: Transfers for SO-MOF-268864-NC-DIR / Ad core government functions a ditional Work on English-Som IDA / D6580 nd foundational education h Prior Direct Selection Direct 135,000.00 131,980.00 Signed 2021-12-18 2022-01-26 2021-12-23 2022-02-17 2022-01-04 2022-03-30 2022-07-03 ali Somali-English Translation ealth service delivery mecha , Voice -Over Recording nisms in elig ible Federal Me mber States (FMS) SO-MOF-299401-NC-RFQ / W Component 4: Citizen Engag Request for Quota Single Stage - One E Pending Impl ritten Translation of Budget R IDA / D6580 Prior Limited 50,000.00 0.00 2022-06-27 2022-08-11 2023-08-11 ement and Feedback tions nvelope ementation eports and Related Documen ts SO-MOF-362638-NC-DIR / Pr Component 3: Transfers for ocurement of Non Consultin core government functions a g Services for a Health Tech nd foundational education h Direct - Internation Under Imple nical Partner (HTP) to Suppor IDA / D6580 Prior Direct Selection 10,746,208.00 0.00 2023-05-22 2023-06-07 2023-05-27 2023-06-15 2023-07-01 2023-12-28 ealth service delivery mecha al mentation t Implementation of Somalia’ nisms in elig ible Federal Me s Female Health Worker Prog mber States (FMS) ram and Capacity Developm ent in Ministries of Health CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-238785-CS-CQS / C Component 4: Citizen Engag Consultant Qualifi all Centre Service for Citizen IDA / D6580 Prior Limited 150,000.00 156,513.65 Signed 2021-06-17 2021-06-16 2021-07-01 2021-07-23 2021-07-22 2021-10-28 2021-08-19 2021-11-14 2021-09-24 ement and Feedback cation Selection Engagement SO-MOF-238789-CS-CQS / C Component 4: Citizen Engag Consultant Qualifi ommunity Mobilization for Cit IDA / D6580 Prior Open - National 100,000.00 0.00 Canceled 2021-06-18 2021-07-02 2021-08-06 2021-08-07 2021-09-04 2022-09-04 ement and Feedback cation Selection izen Engagement SO-MOF-239596-CS-CQS / M Component 4: Citizen Engag Consultant Qualifi ass Media Activity for Citizen IDA / D6580 Prior Open - National 100,000.00 102,824.90 Signed 2021-06-17 2021-08-18 2021-07-05 2021-08-26 2021-08-08 2021-11-11 2021-09-07 2022-01-10 2021-09-28 2022-01-24 2022-09-28 ement and Feedback cation Selection Engagement SO-MOF-246715-CS-CQS / C Component 4: Citizen Engag Consultant Qualifi ommunity Mobilization for Cit IDA / D6580 Prior Open - National 200,000.00 167,070.12 Signed 2021-08-09 2021-08-16 2021-08-23 2021-08-26 2021-09-27 2021-11-03 2021-10-18 2022-01-04 2021-11-15 2022-01-24 2022-11-15 ement and Feedback cation Selection izen Engagement SO-MOF-290903-CS-LCS / In Component 5: Project Manag Least Cost Selecti Open - Internationa Under Implement dependent Verification Agent IDA / D6580 Prior 100,000.00 0.00 2022-04-24 2022-04-29 2022-05-08 2022-05-03 2022-06-19 2022-11-24 2022-06-20 2023-01-18 2022-07-04 2023-04-18 2022-07-12 2023-06-09 2022-07-26 2023-04-22 ement on l ation for RCRF Expenditure Progra m - 2022/2023 SO-MOF-284926-CS-QCBS / Component 4: Citizen Engag Quality And Cost- Open - Internationa Consultant Services for Impr IDA / D6580 Prior 500,000.00 0.00 Canceled 2022-03-21 2022-04-04 2022-04-21 2022-05-21 2022-06-04 2022-06-18 2022-07-09 2023-12-31 ement and Feedback Based Selection l oving Budget Transparency SO-MOF-299399-CS-CQS / T hink Tank for Policy Briefs on Component 4: Citizen Engag Consultant Qualifi Under Implement IDA / D6580 Prior Open - National 100,000.00 0.00 2022-06-16 2022-06-15 2022-07-07 2022-06-20 2022-08-11 2022-12-24 2022-08-18 2022-09-08 2023-09-08 Budget Cycle: Citizen Engage ement and Feedback cation Selection ation ment and Feedback SO-MOF-299400-CS-CQS / S Component 4: Citizen Engag Consultant Qualifi Under Implement upport for Budget Transpare IDA / D6580 Prior Open - National 200,000.00 0.00 2022-06-16 2022-06-15 2022-06-30 2022-06-20 2022-08-04 2022-10-11 2022-08-25 2023-02-16 2022-09-18 2023-09-18 ement and Feedback cation Selection ation ncy under Citizen Engageme nt and Feedback SO-MOF-348226-CS-LCS / Pr Component 5: Project Manag Least Cost Selecti Open - Internationa Under Implement ojects Audit for WB funded Pr IDA / D6580 Prior 250,000.00 0.00 2023-03-20 2023-04-03 2023-03-22 2023-04-12 2023-04-15 2023-04-22 2023-04-28 2023-05-18 2023-06-02 2024-06-01 ement on l ation ojects for 2022 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 SO-MOF-238781-CS-CDS / H Component 3: Transfers for EALTH TECHNICAL PARTNER core government functions a (HTP) TO SUPPORT IMPLEME nd foundational education h NTATION OF SOMALIA FEMAL IDA / D6580 Prior Direct Selection Direct 4,300,000.00 4,268,149.12 Signed 2021-06-16 2021-06-16 2021-06-22 2021-06-24 2021-07-16 2021-07-01 2022-07-16 ealth service delivery mecha E HEALTH WORKER PROGRA nisms in elig ible Federal Me M & CAPACITY DEVELOPMEN mber States (FMS) T IN MINISTRIES OF HEALTH Component 3: Transfers for SO-MOF-238791-CS-CDS / Pr core government functions a ocurement Specialist Consult IDA / D6580 nd foundational education h Prior Direct Selection Direct 180,000.00 254,400.00 Signed 2021-06-16 2021-06-16 2021-06-24 2021-07-11 2021-07-14 2021-08-02 2021-08-19 ing Services ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-238800-CS-INDV / I core government functions a ndependent Verification Age Individual Consult IDA / D6580 nd foundational education h Prior Limited 15,000.00 14,900.00 Signed 2021-06-16 2021-07-23 2021-06-21 2021-08-22 2021-07-01 2021-08-26 2021-07-15 2021-08-29 2021-08-26 nt for RCRF II Expenditure Pr ant Selection ealth service delivery mecha ogram - Individual Consultant nisms in elig ible Federal Me mber States (FMS) SO-MOF-239592-CS-INDV / H Component 2: Strengthen in uman Resource Governance Individual Consult IDA / D6580 ter-governmental fiscal relat Prior Limited 70,000.00 129,360.00 Signed 2021-06-16 2021-06-16 2021-06-21 2021-07-29 2021-07-05 2021-08-04 2021-07-19 2021-08-06 2022-07-19 Advisor for National Civil Ser ant Selection ions vice Commission Component 3: Transfers for SO-MOF-239593-CS-CDS / Fi core government functions a nancial Management Speciali IDA / D6580 nd foundational education h Prior Direct Selection Direct 200,000.00 0.00 Canceled 2021-06-16 2021-06-16 2021-06-21 2021-07-12 2021-07-12 2022-07-12 st for Ministry of Health ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-240056-CS-CDS / PF Component 5: Project Manag MRCU Financial Management IDA / D6580 Prior Direct Selection Direct 55,000.00 0.00 Canceled 2021-06-19 2021-06-29 2021-08-12 2022-08-12 ement Specialist Services SO-MOF-240057-CS-CDS / S Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 85,000.00 0.00 Canceled 2021-06-19 2021-06-29 2021-07-20 2022-07-20 enior Financial Management ement Consultant Component 3: Transfers for SO-MOF-240062-CS-INDV / S core government functions a Individual Consult enior RCRF Health Focal Poin IDA / D6580 nd foundational education h Prior Open 70,000.00 76,800.00 Signed 2021-06-22 2021-06-29 2021-08-09 2021-11-14 2021-08-23 2022-02-02 2021-09-20 2022-02-23 2022-09-20 ant Selection t ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-240064-CS-INDV / S core government functions a Individual Consult enior Monitoring and Evaluati IDA / D6580 nd foundational education h Prior Open 70,000.00 67,440.00 Signed 2021-06-26 2021-06-28 2021-08-05 2021-10-28 2021-08-26 2021-11-11 2021-09-23 2021-11-29 2022-09-23 ant Selection on Specialist ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-240067-CS-CDS / G Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 55,000.00 121,880.00 Signed 2021-06-20 2021-06-28 2021-06-30 2021-07-20 2021-07-21 2021-08-03 2022-07-21 almudug RCRF Project Manag ement er SO-MOF-240068-CS-CDS / Ex Component 5: Project Manag ternal Financing Coordination IDA / D6580 Prior Direct Selection Direct 50,000.00 104,400.00 Signed 2021-06-19 2021-07-13 2021-06-29 2021-07-20 2021-07-20 2021-07-29 2022-07-20 ement Specialist SO-MOF-241523-CS-CDS / H Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 31,800.00 60,480.00 Signed 2021-06-30 2021-06-30 2021-07-06 2021-07-20 2021-07-28 2021-07-23 2022-07-28 SS Community Health Coordi ement nator SO-MOF-241524-CS-CDS / H Component 5: Project Manag SS Contracts Management a IDA / D6580 Prior Direct Selection Direct 31,800.00 60,480.00 Signed 2021-06-30 2021-06-30 2021-07-10 2021-07-20 2021-07-25 2021-07-20 2022-07-25 ement nd M&E Specialist SO-MOF-244091-CS-CDS / E Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 55,000.00 117,220.00 Signed 2021-07-17 2021-07-28 2021-07-27 2021-08-03 2021-08-18 2021-08-09 2022-08-18 AFS Financial Management C ement onsultant SO-MOF-244094-CS-CDS / R Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 85,000.00 171,960.00 Signed 2021-07-17 2021-07-28 2021-07-27 2021-08-02 2021-08-15 2021-09-03 2021-09-20 CRF Financial Management C ement onsultant SO-MOF-245179-CS-CDS / R Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 88,000.00 174,960.00 Signed 2021-07-27 2021-08-19 2021-08-06 2021-09-06 2021-09-01 2021-09-12 2022-09-01 CRF Project Coordinator ement SO-MOF-246702-CS-CDS / R Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 50,000.00 102,120.00 Signed 2021-08-07 2021-08-17 2021-08-17 2021-08-22 2021-09-12 2021-09-12 2022-09-12 CRF Program Officer ement Component 3: Transfers for SO-MOF-246709-CS-INDV / F core government functions a Individual Consult Under Implement inancial and Accounting Tech IDA / D6580 nd foundational education h Prior Open 50,000.00 0.00 2021-08-09 2021-08-17 2021-09-27 2021-10-11 2021-11-08 2021-12-14 ant Selection ation nical Assistant ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-246711-CS-INDV / H core government functions a Individual Consult R and Administration Technic IDA / D6580 nd foundational education h Prior Open 50,000.00 0.00 Canceled 2021-08-09 2021-08-25 2021-08-30 2021-09-20 2021-10-18 2022-10-18 ant Selection al Assistant ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-246712-CS-INDV / P core government functions a Individual Consult rocurement Technical Assista IDA / D6580 nd foundational education h Prior Open 50,000.00 60,280.00 Signed 2021-08-09 2021-08-17 2021-09-18 2022-01-25 2021-10-09 2022-02-02 2021-11-06 2022-02-07 2022-11-06 ant Selection nt ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-248385-CS-CDS / C core government functions a ommunity Health Coordinato IDA / D6580 nd foundational education h Prior Direct Selection Direct 30,240.00 60,480.00 Signed 2021-08-18 2021-08-19 2021-08-28 2021-08-23 2021-09-19 2021-08-31 2022-09-19 r for Jubbaland State ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-253451-CS-CDS / M core government functions a OH Financial Management Sp IDA / D6580 nd foundational education h Prior Direct Selection Direct 200,000.00 216,000.00 Signed 2021-09-17 2021-10-06 2021-09-25 2021-10-08 2021-10-23 2021-10-28 2022-10-23 ecialist ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-257038-CS-CDS / E Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 55,000.00 110,880.00 Signed 2021-10-11 2021-10-20 2021-10-21 2021-10-27 2021-11-07 2021-11-02 2022-11-07 AFS Financial Management S ement pecialist 1 SO-MOF-257049-CS-CDS / E Component 5: Project Manag Under Implement IDA / D6580 Prior Direct Selection Direct 62,000.00 0.00 2021-10-11 2021-10-20 2021-10-21 2021-11-16 2022-11-16 AFS Financial Management S ement ation pecialist 2 Page 3 Component 3: Transfers for SO-MOF-259508-CS-CDS / Ju core government functions a bbaland Contract Manageme IDA / D6580 nd foundational education h Prior Direct Selection Direct 35,000.00 34,200.00 Signed 2021-10-24 2021-11-01 2021-11-03 2021-11-02 2021-11-24 2021-11-08 2022-11-24 nt, Monitoring & Evaluation S ealth service delivery mecha pecialist nisms in elig ible Federal Me mber States (FMS) SO-MOF-263366-CS-INDV / S Component 5: Project Manag Individual Consult IDA / D6580 Prior Limited 40,000.00 0.00 Canceled 2021-11-22 2021-11-19 2021-11-27 2021-12-11 2022-01-08 2022-07-07 ecurity Risk Management Co ement ant Selection nsultant SO-MOF-264788-CS-CDS / PF Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 80,000.00 73,420.00 Signed 2021-11-30 2021-11-29 2021-12-08 2021-12-07 2021-12-27 2022-01-20 2022-12-27 MRCU Office Secretary ement SO-MOF-264796-CS-CDS / G Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 61,000.00 65,880.00 Signed 2021-11-27 2021-12-22 2021-12-07 2021-12-25 2021-12-24 2022-01-26 2022-12-24 ender Based Violence (GBV) ement Expert SO-MOF-264800-CS-CDS / Fi Component 2: Strengthen in IDA / D6580 Prior Direct Selection Direct 98,980.00 98,980.00 Signed 2021-11-27 2021-12-06 2021-12-07 2022-02-16 2021-12-27 2022-03-08 2022-12-27 scal Federalism Expert ter-governmental fiscal relat ions SO-MOF-264804-CS-CDS / As Component 2: Strengthen in sistant to Extended Credit Fa IDA / D6580 ter-governmental fiscal relat Prior Direct Selection Direct 74,000.00 73,420.00 Signed 2021-11-27 2021-11-29 2021-12-08 2021-12-11 2021-12-26 2022-01-10 2022-12-26 cility Coordinator ions SO-MOF-264807-CS-CDS / S Component 2: Strengthen in ecretary 3 Intergovernmental IDA / D6580 ter-governmental fiscal relat Prior Direct Selection Direct 40,000.00 39,840.00 Signed 2021-11-27 2021-12-01 2021-12-07 2021-12-11 2021-12-27 2022-01-12 2022-12-27 Fiscal Federalism Secretariat ions SO-MOF-264808-CS-CDS / S Component 2: Strengthen in ecretary 1 Intergovernmental IDA / D6580 ter-governmental fiscal relat Prior Direct Selection Direct 40,000.00 39,840.00 Signed 2021-11-27 2021-12-01 2021-12-05 2021-12-11 2021-12-26 2022-01-12 2022-12-26 Fiscal Federalism Secretariat ions SO-MOF-265944-CS-CDS / S Component 5: Project Manag ocial Safeguarding Specialist, IDA / D6580 Prior Direct Selection Direct 15,780.00 18,600.00 Signed 2021-12-04 2021-12-07 2021-12-12 2021-12-08 2021-12-31 2022-01-09 2022-12-31 ement for Jubbaland SO-MOF-266896-CS-CDS / S Component 5: Project Manag ocial Safeguarding Specialist, IDA / D6580 Prior Direct Selection Direct 18,000.00 18,000.00 Signed 2021-12-08 2021-12-07 2021-12-17 2021-12-08 2021-12-31 2021-12-25 2022-12-31 ement for Galnudug State SO-MOF-267657-CS-CDS / S Component 5: Project Manag ocial Safeguard Specialist -So IDA / D6580 Prior Direct Selection Direct 24,000.00 24,000.00 Signed 2021-12-12 2021-12-16 2021-12-20 2021-12-19 2021-12-31 2021-12-24 2022-12-31 ement uthwest State, Somalia Component 3: Transfers for core government functions a SO-MOF-268873-CS-INDV / E Individual Consult IDA / D6580 nd foundational education h Prior Open 65,000.00 61,920.00 Signed 2021-12-20 2022-01-14 2022-02-07 2022-04-14 2022-02-21 2022-04-21 2022-03-17 2022-04-24 2023-03-17 MIS Data Analyst/Specialist ant Selection ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-270404-CS-CDS / S Component 5: Project Manag ocial Safeguards Specialists- IDA / D6580 Prior Direct Selection Direct 18,000.00 18,000.00 Signed 2021-12-23 2021-12-25 2021-12-27 2021-12-28 2022-01-02 2021-12-29 2023-01-02 ement Hirshabelle State of Somalia SO-MOF-272465-CS-CDS / S Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 56,000.00 57,700.00 Signed 2022-01-12 2022-01-11 2022-01-18 2022-01-27 2022-01-31 2022-02-06 2023-01-31 WSS RCRF III Project Manage ement r Component 3: Transfers for SO-MOF-275267-CS-INDV / H core government functions a uman Resource/Civil Service Individual Consult IDA / D6580 nd foundational education h Prior Direct 55,000.00 26,160.00 Signed 2022-02-03 2022-03-02 2022-02-09 2022-03-15 2022-02-14 2022-03-21 2022-02-24 2022-04-18 2023-02-24 Advisor for Civil Service Com ant Selection ealth service delivery mecha mission of FMSs nisms in elig ible Federal Me mber States (FMS) SO-MOF-276050-CS-CDS / Hi Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 55,000.00 51,630.00 Under Review 2022-02-03 2022-02-15 2022-02-08 2022-02-16 2022-02-21 2022-03-05 2023-02-21 rshabelle RCRF III Project Ma ement nager SO-MOF-276052-CS-INDV / S Component 5: Project Manag Individual Consult IDA / D6580 Prior Open 40,000.00 54,700.00 Signed 2022-02-03 2022-02-15 2022-02-27 2022-05-14 2022-03-09 2022-05-20 2022-03-19 2022-06-02 2022-09-15 ecurity Risk Management Co ement ant Selection nsultant SO-MOF-279657-CS-INDV / S Component 5: Project Manag Individual Consult IDA / D6580 Prior Limited 50,000.00 49,920.00 Signed 2022-02-21 2022-03-07 2022-02-26 2022-04-20 2022-03-19 2022-04-29 2022-04-12 2022-05-22 2023-04-12 ocial Safeguard Specialist ement ant Selection SO-MOF-281899-CS-CDS / Ju bbaland RCRF III Project Man ager. The Consultant was co Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 90,480.00 90,480.00 Signed 2022-03-05 2022-03-17 2022-03-10 2022-03-21 2022-03-19 2022-05-18 2023-03-19 ntracted for this position und ement er RCRF II and is being move d to RCRF III under same ter ms and conditions. SO-MOF-284568-CS-CDS / R Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 74,000.00 73,380.00 Signed 2022-03-19 2022-04-13 2022-03-23 2022-04-21 2022-03-30 2022-05-08 2023-03-30 CRF Education Coordinator ement SO-MOF-284574-CS-CDS / S Component 5: Project Manag enior Adviser - Intergovernm IDA / D6580 Prior Direct Selection Direct 72,000.00 71,600.00 Signed 2022-03-19 2022-03-29 2022-03-24 2022-04-03 2022-03-31 2022-04-24 2023-03-31 ement ental Education Forum Com mittee) (IGEFC) SO-MOF-284579-CS-CDS / Pr Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 59,000.00 58,900.00 Signed 2022-03-19 2022-03-21 2022-03-24 2022-04-06 2022-04-04 2022-04-22 2023-04-04 oject Administrative Assistan ement t SO-MOF-284835-CS-CDS / S Component 5: Project Manag ecretary 4, Inter-Government IDA / D6580 Prior Direct Selection Direct 39,840.00 39,840.00 Signed 2022-03-19 2022-03-21 2022-03-29 2022-03-22 2022-04-09 2022-05-15 2023-04-09 ement al Federalism SO-MOF-284840-CS-CDS / E Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 62,800.00 63,240.00 Signed 2022-03-19 2022-03-28 2022-03-25 2022-03-29 2022-04-07 2022-04-22 2022-04-10 AFS Financial Management S ement pecialist SO-MOF-284894-CS-CDS / H Component 3: Transfers for uman Resource and Civil Ser core government functions a vant Advisor for Hirshabelle S IDA / D6580 nd foundational education h Prior Direct Selection Direct 30,000.00 26,160.00 Signed 2022-03-20 2022-03-28 2022-03-30 2022-03-31 2022-04-12 2022-04-17 2022-10-09 tate Civil Service Commissio ealth service delivery mecha n. nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-284921-CS-CDS / H core government functions a ealth Technical Partner for Fe IDA / D6580 nd foundational education h Prior Direct Selection Direct 5,000,000.00 4,700,000.00 Signed 2022-03-21 2022-04-06 2022-03-31 2022-04-13 2022-04-13 2022-06-02 2023-01-08 male Health Worker Program ealth service delivery mecha . nisms in elig ible Federal Me mber States (FMS) SO-MOF-284562-CS-CDS / N Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 67,800.00 65,020.00 Signed 2022-03-19 2022-03-30 2022-03-25 2022-04-03 2022-04-06 2022-04-22 2023-04-06 ational Procurement Speciali ement st Page 4 SO-MOF-284853-CS-CDS / R Component 5: Project Manag IDA / D6580 Post Direct Selection Direct 87,720.00 0.00 Canceled 2022-03-19 2022-03-27 2022-04-09 2022-05-15 CRF Financial Management C ement onsultant Component 3: Transfers for SO-MOF-287023-CS-INDV / C core government functions a Individual Consult ommunity Health Coordinato IDA / D6580 nd foundational education h Prior Direct 30,240.00 30,240.00 Signed 2022-04-02 2022-04-20 2022-04-09 2022-04-26 2022-04-14 2022-05-02 2022-04-22 2022-05-22 2023-04-22 ant Selection r Southwest ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-287027-CS-CDS / C core government functions a ontracts Management and M IDA / D6580 nd foundational education h Prior Direct Selection Direct 30,240.00 30,240.00 Signed 2022-04-02 2022-04-20 2022-04-09 2022-04-26 2022-04-22 2022-05-20 2023-04-22 &E Specialist –MoH SWSS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-287034-CS-CDS / C core government functions a ommunity Health Coordinato IDA / D6580 nd foundational education h Prior Direct Selection Direct 56,000.00 56,520.00 Signed 2022-04-02 2022-04-20 2022-04-12 2022-04-27 2022-04-25 2022-05-21 2023-04-25 r, MoH – FGS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-287219-CS-INDV / A core government functions a Individual Consult Under Implement ssessment of Female particip IDA / D6580 nd foundational education h Prior Limited 15,000.00 0.00 2022-04-02 2022-04-08 2022-04-07 2022-11-14 2022-04-28 2022-11-29 2022-05-26 2022-07-25 ant Selection ation ation in Teaching. ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for core government functions a SO-MOF-288270-CS-CDS / D IDA / D6580 nd foundational education h Prior Direct Selection Direct 43,440.00 43,440.00 Signed 2022-04-06 2022-04-20 2022-04-12 2022-04-27 2022-04-25 2022-05-21 2023-04-25 ata Analyst – MoH – FGS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-288274-CS-CDS / C core government functions a ommunity Health Coordinato IDA / D6580 nd foundational education h Prior Direct Selection Direct 30,240.00 30,240.00 Signed 2022-04-06 2022-04-20 2022-04-12 2022-05-04 2022-04-27 2022-05-26 2023-04-27 r -GSS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-288420-CS-CDS / C Component 5: Project Manag ustoms Automated System L IDA / D6580 Prior Direct Selection Direct 50,000.00 49,970.00 Signed 2022-04-07 2022-04-08 2022-04-13 2022-04-21 2022-04-26 2022-05-23 2022-06-10 ement ead Consultant SO-MOF-288421-CS-CDS / Pu Component 2: Strengthen in blic Financial Management (P IDA / D6580 ter-governmental fiscal relat Prior Direct Selection Direct 55,000.00 50,900.00 Signed 2022-04-07 2022-04-19 2022-04-13 2022-05-05 2022-04-28 2022-06-08 2022-10-25 FM) Reform Expert ions SO-MOF-288422-CS-CDS / Ac Component 2: Strengthen in counting and Financial Mana IDA / D6580 ter-governmental fiscal relat Prior Direct Selection Direct 90,000.00 86,640.00 Signed 2022-04-07 2022-04-12 2022-04-13 2022-04-23 2022-04-28 2022-05-17 2023-04-28 gement Technical Assistant ions Component 3: Transfers for SO-MOF-290902-CS-INDV / H core government functions a uman Resource & Administra Individual Consult IDA / D6580 nd foundational education h Prior Open 50,000.00 0.00 Signed 2022-04-23 2022-04-26 2022-06-07 2022-10-03 2022-06-17 2022-10-11 2022-07-11 2023-06-07 2023-07-11 tion Technical Assistant, Mini ant Selection ealth service delivery mecha stry of Education nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-292062-CS-INDV / C core government functions a ontract Management and M& Individual Consult IDA / D6580 nd foundational education h Prior Open 30,240.00 30,240.00 Signed 2022-04-28 2022-04-29 2022-05-22 2022-08-28 2022-05-23 2022-09-05 2022-06-07 2022-09-02 2023-06-07 E Specialist - Galmudug Stat ant Selection ealth service delivery mecha e of Somalia nisms in elig ible Federal Me mber States (FMS) SO-MOF-284871-CS-CDS / Ac counting and Financial Mana Component 5: Project Manag IDA / D6580 Post Direct Selection Direct 86,640.00 0.00 Canceled 2022-03-20 2022-03-26 2022-04-08 2023-04-08 gement Technical Advisor - O ement ffice of the Accountant Gener al. Component 3: Transfers for SO-MOF-299395-CS-INDV / I core government functions a Individual Consult Under Implement nternal Audit Technical Assist IDA / D6580 nd foundational education h Prior Open 55,000.00 0.00 2022-06-16 2022-06-15 2022-08-04 2022-08-11 2022-09-01 2023-09-01 ant Selection ation ant for MoH - FGS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-299397-CS-INDV / D core government functions a Individual Consult Under Implement igital Health Coordinator for IDA / D6580 nd foundational education h Prior Open 55,000.00 0.00 2022-06-16 2022-06-14 2022-08-04 2022-08-11 2022-09-01 2023-09-01 ant Selection ation MoH, FGS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-257051-CS-INDV / E Component 5: Project Manag Individual Consult IDA / D6580 Prior Open 50,000.00 0.00 Canceled 2021-10-11 2021-10-20 2021-11-20 2021-12-04 2021-12-25 2022-12-25 AFS Risk Management Specia ement ant Selection list SO-MOF-301510-CS-CDS / Pr Component 5: Project Manag ocurement Specialist/Technic IDA / D6580 Post Direct Selection Direct 100,000.00 0.00 Canceled 2022-06-28 2022-07-19 2022-07-06 2022-07-19 2023-07-19 ement al Assistant SO-MOF-312477-CS-INDV / P Component 5: Project Manag Individual Consult Open - Internationa rocurement Specialist/Techni IDA / D6580 Prior 180,000.00 0.00 Signed 2022-09-03 2022-09-23 2022-10-07 2023-02-22 2022-10-12 2023-03-01 2022-10-25 2023-06-07 2023-10-25 ement ant Selection l cal Assistant SO-MOF-299402-CS-INDV / C Component 5: Project Manag Individual Consult Under Implement ommunications Specialist for IDA / D6580 Prior Limited 50,000.00 0.00 2022-09-13 2022-10-24 2022-09-19 2022-09-29 2022-10-14 2023-10-14 ement ant Selection ation RCRF Project SO-MOF-325518-CS-INDV / F Component 2: Strengthen in Individual Consult IDA / D6580 Prior Open - National 70,000.00 0.00 Signed 2022-11-13 2022-11-21 2022-12-12 2023-02-26 2022-12-22 2023-03-01 2023-01-06 2023-06-07 2024-01-06 ederalism Adviser ter-governmental fiscal relat ant Selection ions Component 3: Transfers for SO-MOF-330993-CS-INDV / J core government functions a Individual Consult Under Implement ubbaland Community Health IDA / D6580 nd foundational education h Prior Open - National 30,240.00 0.00 2022-12-14 2022-12-24 2023-01-12 2023-04-13 2023-01-22 2023-04-17 2023-02-04 2024-02-04 ant Selection ation Coordinator ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-330988-CS-INDV / T Component 5: Project Manag Individual Consult Under Implement IDA / D6580 Prior Limited 59,000.00 0.00 2022-12-15 2022-12-14 2022-12-20 2023-02-04 2022-12-30 2023-02-09 2023-01-14 2024-01-14 echnical Administrative Assis ement ant Selection ation tant SO-MOF-330991-CS-INDV / R Component 5: Project Manag Individual Consult eform Reporting and Perform IDA / D6580 Prior Direct - National 74,000.00 0.00 Signed 2022-12-15 2022-12-15 2022-12-25 2022-12-21 2023-01-04 2023-01-11 2023-01-19 2023-06-07 2024-01-19 ement ant Selection ance Specialist Page 5 Component 3: Transfers for SO-MOF-337754-CS-CDS / Hi core government functions a Under Implement rshabelle Social Safeguards S IDA / D6580 nd foundational education h Prior Direct Selection Direct - National 18,000.00 0.00 2023-01-25 2023-01-30 2023-01-29 2023-02-02 2023-02-06 2024-02-06 ation pecialist ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-337757-CS-CDS / S core government functions a Under Implement ocial Safeguards Specialist -S IDA / D6580 nd foundational education h Prior Direct Selection Direct - National 24,000.00 0.00 2023-01-25 2023-01-31 2023-01-29 2023-02-04 2023-02-05 2024-02-05 ation outh West State ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-346749-CS-CDS / IC Component 4: Citizen Engag Under Implement T-Based Call Center Services IDA / D6580 Prior Direct Selection Direct - National 450,000.00 0.00 2023-03-04 2023-03-25 2023-03-11 2023-04-24 2023-04-05 2024-09-26 ement and Feedback ation for Citizen Engagement and Feedback SO-MOF-354687-CS-INDV / S Component 5: Project Manag Individual Consult Under Implement enior Social and Gender Bas IDA / D6580 Prior Open - National 61,000.00 0.00 2023-04-06 2023-04-17 2023-05-01 2023-05-11 2023-05-26 2024-05-25 ement ant Selection ation ed Violence Specialist Component 3: Transfers for SO-MOF-356886-CS-INDV / A core government functions a dmin and Finance Specialist - IDA / D6580 nd foundational education h Prior Direct Selection Direct - National 36,000.00 0.00 Signed 2023-04-27 2023-05-18 2023-05-05 2023-05-27 2023-05-30 2023-06-20 2024-05-29 MoH ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-369294-CS-INDV / P Component 5: Project Manag Individual Consult Under Implement rocurement of Individual Con IDA / D6580 Prior Open - National 60,000.00 0.00 2023-06-30 2023-06-29 2023-08-18 2023-09-08 2023-10-13 2024-04-10 ement ant Selection ation sultant: Security Specialist Page 6 3 MONTHS PROCUREMENT PLAN-MRPLP Project information: Malawi COVID-19 Emergency Response and Health Systems Preparedness Project-P173806 Project Implementation Agency: Ministry of Health and Population Date of the Procurement Plan: April 2020 Period covered by this Procurement Plan: April 2020 to June 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement and Disposal of Public Assets Act, 2017 of the Republic of Malawi, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. In accordance with paragraph 5.4 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. 1 Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable for those contracts identified in the Procurement Plan tables; Works: Not Applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Applicable. Other Relevant Procurement Information: - (a). Thresholds for Request for Quotations Being emergency procurement, thresholds for Requests for Quotations (RFQ) has been increased to US$1 million for goods and services and US$5 million for works. Prequalification. Not expected for the works/goods packages in the procurement plan. Proposed Procedures for CDD Components: Not Applicable Reference to (if any) Project Operational/Procurement Manual: The Ministry of Health and Population team will prepare a Procurement manual. The Procurement Plan will also form part of the Project Implementation Manual. Any Other Special Procurement Arrangements: use of simple and fast procurement and selection methods fit for purpose in emergency situations including procurement from UN Agencies such as UNICEF, WHO and others, enabled and expedited by World Bank procedures and templates for procurement of medicines, medical supplies and equipment for emergency requirements Procurement Packages/Plan with Procurement Arrangements and Time Schedule: as per the table below: b) PROCUREMENT PLAN 1 2 3 4 5 6 7 8 9 10 2 Ref. Contract Title Compone Estimated Procur Procur Bank Expected Sourc Comme No. nt Cost (US$) ement ement Review date for e nts Catego Metho Requir IFBs/EOIs ry d and ement Marke t Appro ach 1. Procurement and 1, 3 2,687,043. GO UN, Post 15-Apr- MoHP distribution of 00 Direct Review 2020 ambulances and motor vehicles, tents for quarantine at ground crossings and IDTCs, medical equipment and supplies. 2. Printing of 50,000 No. 1 5,088.00 GO RFQ, Post 15-Apr- MoHP Health Declaration, Limited Review 2020 Surveillance and Case Management Form 3. Procurement of 1 220,000.0 GO DIR Post 15-Apr- MoHP cartridges for 0 Direct Review 2020 existing GeneXpert machines 4. Procurement of 2 15,000.00 GO RFQ, Post 20-Apr- MoHP computers, Laptops, Limited Review 2020 5. Procurement of 2 6,000.00 GO RFQ, Post 15-Apr- MoHP phones for EOC Limited Review 2020 6. Procurement of 2 50,000.00 NC RFQ, Post 15-Apr- MoHP grievance hotline Limited Review 2020 platform 7. Procurement of 2 1,000.00 GO RFQ, Post 15-Apr- MoHP refrigerator for EOC Limited Review 2020 8. Selection of a 1 5,000.00 CS INDV, Post 17-Apr- MoHP Consulting services Limited Review 2020 to assess minor works and determine scope of work for EOC 9. Selection of 1 562,363.0 CS INDV, Post 17-Apr- MoHP Consultants/Health 0 Direct Review 2020 workers to enhance Surge Capacity Key DIR – Direct Selection RFQ – Request for Quotations INDV – Selection of Individual Consultants Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: 3 Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 5 6 PROCUREMENT Malawi : Malawi COVID-19 Emergency Response and Health Systems Preparedness Project PLAN General Information Country: Malawi 2020-05-12 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173806 GPN Date: 2020-07-23 Project Name: Malawi COVID-19 Emergency Response and Health Systems Preparedness Project Loan / Credit No: IDA / D6200, IDA / D8870, IDA / 71770, TF / B8719 National TB Control Program Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MW-CHSU-244462-CW-RFQ / Request for Quota Renovations of Quarantine U Emergency COVID-19 Respo Request for Quota Single Stage - One E tions - Small Work 2022-04-0 IDA / D6200 Post Limited 21,139.00 0.00 Canceled 2021-08-08 2021-10-03 nits at Point of Entries- Chile nse tions nvelope s (Emergency) SP 1 ka International Airport D -Competitive Request for Quota MW-CHSU-244465-CW-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E tions - Small Work 2022-04-0 Minor renovations of the EO IDA / D6200 Post Limited 15,172.41 0.00 Canceled 2021-08-08 2021-10-03 nse tions nvelope s (Emergency) SP 1 C Office Building D -Competitive MW-CHSU-322292-CW-RFQ / Request for Quota Building of capacity of the E Emergency COVID-19 Respo Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-08-0 IDA / D8870 Post Limited 256,000.00 0.00 2022-12-08 2023-02-09 mergency Operation Centre t nse tions nvelope s (Emergency) SP lementation 8 hough Minor renovations of t D -Competitive he EOC Building Request for Quota MW-CHSU-325572-CW-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-04-0 IDA / 71770 Post Limited 250,000.00 0.00 2023-08-18 2023-10-06 Construction of EPI Fence nse tions nvelope s (Emergency) SP lementation 3 D -Competitive MW-CHSU-322598-CW-RFQ / Request for Quota Refurbishment of X Ray room Emergency COVID-19 Respo Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-03-3 s at Ntchisi Hospital, Chitipa IDA / 71770 Post Limited 60,000.00 0.00 2023-08-08 2023-10-02 nse tions nvelope s (Emergency) SP lementation 0 Hospital, MzuzuCentral Hosp D -Competitive ital Radiology departments Request for Quota MW-CHSU-322267-CW-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-03-0 Renavation of Quarantine Uni IDA / D8870 Post Limited 95,139.00 0.00 2023-07-16 2023-09-06 nse tions nvelope s (Emergency) SP lementation 4 t at Point of Entry D -Competitive Request for Quota MW-CHSU-322600-CW-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-05-2 Rehabilitation of 3 PHC Traini IDA / 71770 Post Limited 900,000.00 0.00 2023-10-29 2023-11-22 nse tions nvelope s (Emergency) SP lementation 0 ng Centres for HSAs D -Competitive Request for Quota MW-CHSU-322607-CW-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-06-2 IDA / 71770 Post Limited 150,000.00 0.00 2023-11-06 2023-12-28 Renovation of laboratories nse tions nvelope s (Emergency) SP lementation 5 D -Competitive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-CHSU-172790-GO-RFQ / Supporting National and Sub Request for Quota Single Stage - One E Procurement of phones for E IDA / D6200 -national, Prevention and Pr Post Limited 6,000.00 5,718.86 Completed 2020-05-26 2020-05-29 2020-06-19 2020-06-27 2020-07-10 2020-07-10 tions nvelope OC eparedness MW-CHSU-172782-GO-RFQ / Supporting National and Sub Request for Quota Single Stage - One E Procurement of computers, L IDA / D6200 -national, Prevention and Pr Post Limited 15,000.00 14,731.45 Completed 2020-05-28 2020-05-29 2020-06-23 2020-06-27 2020-07-14 2020-07-15 tions nvelope aptops eparedness MW-CHSU-177188-GO-UN / P Emergency COVID-19 Respo UN Agencies (Dire rocurement of Ambulances a IDA / D6200 Post Direct 900,000.00 919,471.24 Completed 2020-06-02 2020-05-29 2020-06-07 2020-05-29 2020-06-22 2020-06-06 2020-09-20 2021-01-06 nse ct) nd Rapid response vehicles MW-CHSU-172822-GO-UN / P Emergency COVID-19 Respo UN Agencies (Dire IDA / D6200 Post Direct 550,000.00 0.00 Canceled 2020-05-12 2020-05-19 2020-05-17 2020-06-21 2020-09-04 rocurement of Ambulances nse ct) MW-CHSU-172856-GO-DIR / Emergency COVID-19 Respo Procurement of cartridges for IDA / D6200 Post Direct Selection Direct 220,000.00 0.00 Canceled 2020-05-13 2020-05-19 2020-05-18 2020-06-15 2020-07-30 nse existing GeneXpert machines MW-CHSU-172814-GO-UN / P rocurement and distribution Emergency COVID-19 Respo UN Agencies (Dire of motor vehicles, tents for q IDA / D6200 Post Direct 2,137,043.00 0.00 Canceled 2020-05-15 2020-05-19 2020-05-20 2020-06-10 2020-09-08 nse ct) uarantine at ground crossing s and IDTCs, medical equipm ent and supplies. MW-CHSU-177194-GO-UN / P Emergency COVID-19 Respo UN Agencies (Dire rocurement and distribution IDA / D6200 Post Direct 1,700,000.00 3,568,488.24 Signed 2020-06-02 2020-06-02 2020-06-16 2020-04-07 2020-08-04 2020-08-19 2020-11-02 nse ct) of medical equipment and su pplies. MW-CHSU-172794-GO-RFQ / Supporting National and Sub Request for Quota Single Stage - One E Procurement of fridges, ultra IDA / D6200 -national, Prevention and Pr Post Limited 9,900.00 6,174.79 Completed 2021-05-01 2021-07-22 2021-05-21 2021-07-29 2021-06-11 2021-10-01 tions nvelope freezer and cooler boxes for eparedness PHIM and EOC MW-CHSU-244488-GO-RFQ / Procurement of ICT Equipme Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / D6200 Post Limited 180,623.00 160,656.20 Signed 2021-08-08 2021-07-23 2021-10-03 2021-08-13 2022-04-01 2021-11-30 nt for EOC Capacity building nse tions nvelope and Project Operations. MW-CHSU-257097-GO-DIR / Emergency COVID-19 Respo Procurement of COVID-19 Va IDA / D6200 Prior Direct Selection Direct 17,000,000.00 16,650,737.28 Signed 2021-10-11 2021-10-13 2021-10-16 2022-06-28 2021-10-31 2021-10-30 2023-10-01 nse ccines and related supplies MW-CHSU-281905-GO-RFQ / Procurement of materials an Emergency COVID-19 Respo Request for Quota Single Stage - One E d equipment for Infection Co IDA / D6200 Post Limited 285,000.00 0.00 Canceled 2022-03-20 2022-03-15 2022-04-15 2022-05-15 nse tions nvelope ntrol and Health Care Waste Management for Health Facili ties Page 1 MW-CHSU-283324-GO-RFQ / Procurement of computing d evices/tablets and laptops fo Emergency COVID-19 Respo Request for Quota Single Stage - One E r COVID 19 vaccine tracking IDA / D6200 Post Limited 260,000.00 251,426.65 Signed 2022-05-11 2022-05-30 2022-06-01 2022-06-22 2022-06-29 nse tions nvelope thorough the Electronic vacci ne registry, and Laboratory I nformation Management Syst ems Server MW-CHSU-281905-GO-RFQ. / Supply and delivery of Medic Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / D6200 Post Limited 414,000.00 334,685.49 Completed 2022-03-15 2022-03-15 2022-04-04 2022-04-11 2022-04-06 2022-04-12 al Waste Management items nse tions nvelope and equipment MW-CHSU-305304-GO-RFQ / Supply and delivery of ICT E Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / D6200 Post Limited 15,000.00 43,584.94 Terminated 2022-08-08 2022-08-08 2022-08-26 2022-09-17 2022-10-07 quipment( Laptops and Table nse tions nvelope ts) for Strengthening Online Presence MW-CHSU-293683-GO-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Supply and delivery of Centr IDA / D6200 Post Limited 202,400.00 186,056.87 Signed 2022-08-05 2022-08-08 2022-09-01 2022-08-24 2022-09-29 nse tions nvelope ifuges, Heat Blocks and Pipet tes MW-CHSU-306824-GO-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Supply and delivery of Covid IDA / D6200 Post Limited 203,000.00 122,730.74 Signed 2022-08-05 2022-08-02 2022-08-23 2022-09-08 2022-09-13 nse tions nvelope 19 Personal and Protective E quipment MW-CHSU-305304I-GO-RFQ / Supply and delivery of ICT E Emergency COVID-19 Respo Request for Quota Single Stage - One E Under Imple IDA / D6200 Post Limited 26,000.00 0.00 2022-08-08 2022-08-08 2022-09-07 2022-10-05 quipment ( Laptops and Tabl nse tions nvelope mentation ets) for strengthening Online Presence MW-CHSU-322318-GO-DIR / Procurement of Laboratory Emergency COVID-19 Respo Pending Impl IDA / D8870 Post Direct Selection Direct - National 1,110,000.00 0.00 2022-11-25 2022-11-30 2022-12-31 2023-12-31 Diagnostics equipment, reag nse ementation ents and Covid Test Kits MW-CHSU-322687-GO-DIR / Supply and delivery of essen tial medicines, medical suppli Emergency COVID-19 Respo Pending Impl IDA / 71770 Prior Direct Selection Direct - National 4,470,000.00 0.00 2023-06-11 2023-06-21 2023-07-16 2024-07-15 es and 10 Gene expert machi nse ementation nes, biohazard bags, family p lanning products and birth co ntrols MW-CHSU-322694-GO-DIR / Supply and delivery 0f Rapid Emergency COVID-19 Respo Under Imple IDA / 71770 Post Direct Selection Direct - National 1,700,000.00 0.00 2023-07-16 2023-05-12 2023-07-26 2023-05-31 2023-08-19 2024-02-15 response vehicles and mobile nse mentation vans for 6 districts MW-CHSU-322696-GO-RFB / Supply and delivery of CT Sc anner for KCH, Digital Xray Emergency COVID-19 Respo Open - Internationa Single Stage - One E Under Imple IDA / 71770 Prior Request for Bids 5,950,000.00 0.00 2023-05-07 2023-05-03 2023-05-21 2023-06-20 2023-06-18 2023-07-09 2023-08-02 2023-11-30 Machines, Ultra sound scanni nse l nvelope mentation ng machines and High Thro ughput Sequencer Magnetic Imaging Machines MW-CHSU-322798-GO-RFB / Emergency COVID-19 Respo Single Stage - One E Pending Impl Procurement of push bikes a IDA / 71770 Prior Request for Bids Open - National 2,407,000.00 0.00 2023-01-13 2023-02-03 2023-02-17 2023-03-03 2023-04-07 2023-10-04 nse nvelope ementation nd motor cycles MW-CHSU-322859-GO-DIR / Emergency COVID-19 Respo Pending Impl Procurement of 1 million dos IDA / 71770 Prior Direct Selection Direct - National 7,500,000.00 0.00 2023-03-26 2023-04-02 2023-05-14 2024-05-13 nse ementation es of Vaccine MW-CHSU-322878-GO-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Under Imple Procurement of ultra low tem IDA / 71770 Post Limited 234,900.00 0.00 2022-12-02 2023-03-07 2023-01-09 2023-03-06 nse tions nvelope mentation perature freezer MW-CHSU-322892-GO-RFQ / Procurement of a set of PA s Emergency COVID-19 Respo Request for Quota Single Stage - One E Under Imple IDA / 71770 Post Limited 44,600.00 0.00 2022-12-08 2023-01-19 2023-03-16 ystem, speakers TV screen, nse tions nvelope mentation megaphone and heavy duty printer MW-CHSU-325544-GO-DIR / Supply and delivery of essen Emergency COVID-19 Respo Under Imple TF / B8719 Prior Direct Selection Direct - National 5,000,000.00 0.00 2022-12-01 2022-11-21 2022-12-06 2022-11-22 2022-12-28 2023-12-28 tial medicines to meet the ur nse mentation gent need of Health Sector MW-CHSU-331110-GO-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Under Imple Supply and delivery of ICT E IDA / 71770 Post Limited 400,000.00 0.00 2023-01-11 2023-01-18 2023-03-01 2023-04-26 nse tions nvelope mentation quipment for PIU MW-CHSU-322587I-NC-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Under Imple Procurement of Printing Servi IDA / 71770 Post Limited 139,000.00 0.00 2022-11-18 2022-11-18 2022-12-09 2023-01-05 nse tions nvelope mentation ces for Policies,Guidelines an d SOPs MW-CHSU-354763-GO-RFQ / Supply and delivery of Labor atory supplies ( 2000 petri di Contingent Emergency Resp Request for Quota Single Stage - One E Under Imple shes, 10000 disposable Inocu IDA / 71770 Post Limited 750,000.00 0.00 2023-04-14 2023-05-23 2023-05-06 2023-11-02 onse tions nvelope mentation lating loop, 30 carry blair,30 alkaline peptone water and 2 0 000 cholera RDTs and proc urement of sequencing Rea gents MW-CHSU-354774-GO-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Under Imple Supply and delivery of Medic IDA / 71770 Post Limited 320,000.00 0.00 2023-04-15 2023-05-30 2023-11-26 nse tions nvelope mentation al Waste incinerators MW-CHSU-355126-GO-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Under Imple Supply and delivery of 240 Li IDA / 71770 Post Limited 90,000.00 0.00 2023-04-19 2023-04-17 2023-06-07 2023-09-05 nse tions nvelope mentation tres bins for waste storage a nd bin liners MW-CHSU-356667-GO-RFQ / Supply and delivery of Wate r Testing Kits, Residual Chlor Emergency COVID-19 Respo Request for Quota Single Stage - One E Under Imple IDA / 71770 Post Limited 376,000.00 0.00 2023-05-05 2023-06-09 2023-07-14 ine Testing Kits and Waste M nse tions nvelope mentation anagement Containers for Ch olera Control Activities in Dis trict Councils MW-CHSU-322884-GO-RFB / Emergency COVID-19 Respo Single Stage - One E Pending Impl Procurement of PPE and esse IDA / 71770 Post Request for Bids Open - National 1,300,000.00 0.00 2023-09-24 2023-10-08 2023-11-05 2023-11-19 2023-12-24 2023-12-29 nse nvelope ementation ntial medical equip Page 2 MW-CHSU-322886-GO-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Pending Impl IDA / 71770 Post Limited 110,000.00 0.00 2023-09-06 2023-10-12 2024-04-09 Procurement of IEC Materials nse tions nvelope ementation MW-CHSU-322791-GO-RFB / Supply and delivery of end u Emergency COVID-19 Respo Open - Internationa Single Stage - One E Pending Impl IDA / 71770 Post Request for Bids 1,110,000.00 0.00 2023-09-01 2023-09-15 2023-10-13 2023-10-27 2023-11-24 2024-03-23 ser devices ( Tablets) for vac nse l nvelope ementation cination tracking MW-CHSU-322784-GO-RFB / Emergency COVID-19 Respo Open - Internationa Single Stage - One E Pending Impl Supply and delivery of comp IDA / 71770 Post Request for Bids 1,300,000.00 0.00 2023-09-29 2023-10-09 2023-11-06 2023-12-06 2024-01-03 2024-07-01 nse l nvelope ementation lete setup equipment for 2 D ata Centres MW-CHSU-322810-GO-RFQ / Procurement of Oxygen and Emergency COVID-19 Respo Request for Quota Single Stage - One E Pending Impl IDA / 71770 Post Limited 325,000.00 0.00 2023-08-08 2023-09-22 2023-11-17 installation of Oxygen Manifo nse tions nvelope ementation ld Systems and Oxygen acce ssories MW-CHSU-293687-GO-RFB / Supply, delivery, installation Emergency COVID-19 Respo Single Stage - One E Pending Impl IDA / D6200 Post Request for Bids Limited 1,167,885.00 0.00 2024-01-01 2024-01-08 2024-01-29 2024-02-19 2024-03-11 2024-09-07 and commissioning of oxyge nse nvelope ementation n plant for Zomba Central Ho spital MW-CHSU-317442-GO-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Pending Impl Supply and delivery of Suppl IDA / D6200 Post Limited 152,941.00 0.00 2023-12-02 2024-02-03 2024-08-01 nse tions nvelope ementation y Chain Vehicles MW-CHSU-322808-GO-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Pending Impl Procurement of lab supplies IDA / 71770 Post Limited 40,000.00 0.00 2023-10-08 2023-11-22 2024-01-17 nse tions nvelope ementation and power back up for 15 P OE MW-CHSU-322691-GO-RFQ / Supply and delivery of ICT Eq Emergency COVID-19 Respo Request for Quota Single Stage - One E Pending Impl IDA / 71770 Post Limited 254,100.00 0.00 2022-12-09 2023-01-13 2023-07-12 uipment for EPI ( Desktops, nse tions nvelope ementation Tablets & Protective Covers a nd Printers) MW-CHSU-356666-GO-DIR / Emergency COVID-19 Respo Direct - Internation Under Revie Procurement of Medicines an IDA / 71770 Prior Direct Selection 9,000,000.00 0.00 2023-06-04 2023-05-30 2023-06-09 2023-06-02 2023-07-05 2024-07-04 nse al w d Medicinal Supplies for Chol era Response MW-CHSU-366659-GO-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Pending Impl Supply and delivery of 3 Mo IDA / 71770 Post Limited 300,000.00 0.00 2023-06-24 2023-08-19 2024-02-15 nse tions nvelope ementation bile Vans Units for communit y mobilization NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-CHSU-172855-NC-RFQ / Supporting National and Sub Request for Quota Single Stage - One E Procurement of grievance ho IDA / D6200 -national, Prevention and Pr Post Limited 50,000.00 0.00 Canceled 2020-05-16 2020-06-18 2021-06-18 tions nvelope tline platform eparedness MW-CHSU-245209-NC-DIR / Implementation Managemen Upgrading of Tompro Accou IDA / D6200 t and Monitoring and Evaluat Post Direct Selection Direct 35,000.00 32,833.00 Signed 2021-07-30 2021-07-29 2021-08-04 2020-12-09 2021-08-20 2020-12-16 2022-08-20 nting System ion MW-CHSU-293684-NC-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / D6200 Post Limited 95,260.00 60,168.28 Completed 2022-05-17 2022-05-30 2022-06-17 2022-06-25 2022-07-15 2022-09-03 Printing of Vaccine Publicity nse tions nvelope Materials MW-CHSU-322587-NC-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Procurement of printing serv IDA / D8870 Post Limited 139,000.00 0.00 Canceled 2022-11-23 2022-11-18 2022-12-30 2023-01-02 nse tions nvelope ices of policies, guidelines an d SOPs MW-CHSU-355904-NC-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Pending Impl IDA / 71770 Post Limited 25,000.00 0.00 2023-04-21 2023-05-19 2023-06-09 Printing of EBS reporting too nse tions nvelope ementation ls MW-CHSU-322789-NC-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Pending Impl Provision of services for main IDA / 71770 Post Limited 24,000.00 0.00 2023-07-09 2023-08-23 2024-08-22 nse tions nvelope ementation tenance of Genomic Sequenc ers MW-CHSU-322766-NC-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Pending Impl Service contract for MRI and IDA / 71770 Post Limited 50,000.00 0.00 2023-12-10 2024-01-17 2024-07-15 nse tions nvelope ementation CT Scanners maintenance se rvice MW-CHSU-322809-NC-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Pending Impl Printing of CHBC policy and IDA / 71770 Post Limited 270,000.00 0.00 2023-10-29 2023-12-24 2024-01-21 nse tions nvelope ementation guidelines and COVID 19 PFM Guidelines CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-CHSU-322672-CS-QCBS / Consultancy services for su Emergency COVID-19 Respo Consultant Qualifi Pending Impleme IDA / 71770 Post Open - National 300,000.00 0.00 2023-08-31 2023-09-21 2023-10-12 2023-10-22 2023-11-12 2024-02-10 pervision of construction of nse cation Selection ntation Infectious Disease Wards at QECH MW-CHSU-322662-CS-QCBS / Consultant to supervise re Contingent Emergency Resp Consultant Qualifi Pending Impleme IDA / 71770 Post Open - National 300,000.00 0.00 2023-07-02 2023-07-23 2023-08-20 2023-08-21 2023-09-14 2023-09-23 novation of QECH and Zomba onse cation Selection ntation Central Hospital MW-CHSU-322686-CS-QCBS / Preparation of Detailed desi Emergency COVID-19 Respo Quality And Cost- Pending Impleme IDA / 71770 Post Open - National 500,000.00 0.00 2023-09-24 2023-10-15 2023-11-12 2023-11-26 2023-12-10 2023-12-25 2024-01-14 2024-04-13 gns and BOQ s for the constr nse Based Selection ntation uction of Public Health Institu te MW-CHSU-366951-CS-CQS / Consultancy services to desi Emergency COVID-19 Respo Consultant Qualifi Pending Impleme IDA / 71770 Post Limited 200,000.00 0.00 2023-06-25 2023-07-09 2023-07-23 2023-08-20 2024-02-16 gn and supervise renovation nse cation Selection ntation of Kamuzu Central Hospital Page 3 MW-CHSU-366936-CS-QCBS / Consultancy to Design and Emergency COVID-19 Respo Consultant Qualifi Pending Impleme IDA / 71770 Post Limited 200,000.00 0.00 2023-06-25 2023-07-09 2023-07-23 2023-08-07 2024-02-03 supervise the Renovation of nse cation Selection ntation Mzuzu Central Hospital MW-CHSU-366958-CS-CQS / Consultancy services to Desi Emergency COVID-19 Respo Consultant Qualifi Pending Impleme IDA / 71770 Post Limited 200,000.00 0.00 2023-06-25 2023-07-09 2023-07-23 2023-08-07 2024-02-03 gn and supervise the Rehabil nse cation Selection ntation itaion of Zomba Central Hos pital MW-CHSU-367014-CS-CQS / Consultancy services to sup Emergency COVID-19 Respo Consultant Qualifi Pending Impleme IDA / 71770 Post Limited 200,000.00 0.00 2023-06-25 2023-07-09 2023-07-23 2023-08-20 2024-02-16 ervise the renovation of Que nse cation Selection ntation en Elezabeth Central Hospital INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-CHSU-172857-CS-INDV / Selection of a Consulting ser Emergency COVID-19 Respo Individual Consult IDA / D6200 Post Limited 5,000.00 0.00 Canceled 2020-06-05 2020-06-10 2020-07-01 2020-07-18 2020-08-17 vices to assess minor works nse ant Selection and determine scope of work for EOC MW-CHSU-186787-CS-INDV / Implementation Managemen Individual Consult IDA / D6200 Post Open 36,000.00 23,632.92 Signed 2020-08-04 2020-08-18 2020-08-19 2020-11-25 2020-08-22 2020-12-08 2020-09-01 2020-12-16 2021-09-01 Assistant Procurement Speci t and Monitoring and Evaluat ant Selection alist ion MW-CHSU-186798-CS-INDV / Implementation Managemen Individual Consult Medical Waste Management IDA / D6200 t and Monitoring and Evaluat Post Open 41,000.00 25,208.45 Signed 2020-08-04 2020-08-18 2020-08-19 2020-11-25 2020-08-22 2020-12-08 2020-09-01 2020-12-17 2021-09-01 ant Selection Specialist ion MW-CHSU-186802-CS-INDV / Implementation Managemen Individual Consult IDA / D6200 Post Open 36,000.00 26,783.98 Signed 2020-08-04 2020-08-18 2020-08-19 2020-11-25 2020-08-22 2020-12-08 2020-09-01 2020-12-15 2021-09-01 Project Accountant t and Monitoring and Evaluat ant Selection ion MW-CHSU-186806-CS-INDV / Implementation Managemen Individual Consult Assistant Monitoring and Eval IDA / D6200 t and Monitoring and Evaluat Post Open 36,000.00 23,632.92 Terminated 2020-08-04 2020-08-18 2020-08-19 2020-11-25 2020-08-22 2020-12-08 2020-09-01 2020-12-15 2021-09-01 ant Selection uation Specialist ion MW-CHSU-228548-CS-CDS / Implementation Managemen Provision of Accounting Softw IDA / D6200 t and Monitoring and Evaluat Post Direct Selection Direct 35,000.00 0.00 Canceled 2021-04-20 2021-07-23 2021-04-30 2021-07-04 2021-12-31 are upgrading services ion MW-CHSU-258710-CS-INDV / Implementation Managemen Individual Consult Consulting services for Assist IDA / D6200 t and Monitoring and Evaluat Post Limited 36,000.00 26,130.72 Signed 2021-10-28 2021-11-04 2021-11-18 2021-12-12 2021-11-25 2022-01-11 2021-12-30 2022-01-14 2022-12-30 ant Selection ant Monitoring and Evaluatio ion n Specialist MW-CHSU-325527-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement IDA / D8870 Post Direct - National 16,000.00 0.00 2022-11-18 2023-01-06 2022-11-28 2022-12-03 2022-12-13 2023-06-11 Individual Consultant- Data M nse ant Selection ation anager MW-CHSU-322636-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Individual consultnat- Project IDA / 71770 Post Open - National 190,000.00 0.00 2022-12-01 2022-12-12 2023-01-15 2023-01-22 2023-02-08 2024-02-08 nse ant Selection ation Coordinator MW-CHSU-322640-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Individual Consultant- Monito IDA / 71770 Prior Open - National 162,000.00 0.00 2022-11-25 2023-02-09 2023-01-29 2023-02-05 2023-03-08 2023-04-13 nse ant Selection ation ring and Evaluation Specialis t MW-CHSU-322646-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Individual Consultant- Financ IDA / 71770 Prior Open - National 162,000.00 0.00 2022-11-25 2023-04-05 2023-01-09 2023-01-16 2023-02-02 2024-02-02 nse ant Selection ation e Management Specialist MW-CHSU-322650-CS-INDV / Contingent Emergency Resp Individual Consult Under Implement Individual Consultant- Procur IDA / 71770 Prior Open - National 162,000.00 0.00 2022-11-25 2022-12-13 2023-01-09 2023-01-16 2023-02-02 2023-03-10 onse ant Selection ation ement Specialist MW-CHSU-322651-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Individual Consultant - Enviro IDA / 71770 Prior Open - National 162,000.00 0.00 2022-11-25 2022-12-14 2023-01-09 2023-01-16 2023-01-24 2024-01-24 nse ant Selection ation nmental and Social Specialist MW-CHSU-325524-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Individual Consultant- Data O IDA / D8870 Post Direct - National 12,000.00 0.00 2022-11-28 2022-11-21 2022-12-10 2022-12-15 2022-12-25 2023-06-23 nse ant Selection ation fficer Surveillance MW-CHSU-325526-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Consultancy Services- Data O IDA / D8870 Post Direct - National 12,000.00 0.00 2022-11-28 2022-11-21 2022-12-08 2022-12-13 2022-12-23 2023-06-21 nse ant Selection ation fficer- Case Management MW-CHSU-325528-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Consultancy services for Dat IDA / D8870 Post Direct - National 12,000.00 0.00 2022-11-28 2023-01-05 2022-12-08 2022-12-13 2022-12-23 2023-06-21 nse ant Selection ation a Officer- Laboratory MW-CHSU-327245-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Individual Consultancy- Recr IDA / D8870 Post Direct - National 12,000.00 0.00 2022-11-28 2022-11-21 2022-12-08 2022-12-13 2022-12-23 2023-06-21 nse ant Selection ation uitment of Data Officer- Case Management MW-CHSU-327247-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Individual Consultant- Data O IDA / D8870 Post Direct - National 12,000.00 0.00 2022-11-28 2023-01-05 2022-12-08 2022-12-13 2022-12-23 2023-06-21 nse ant Selection ation fficer Case Management MW-CHSU-327250-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Individual Consultancy Data IDA / D8870 Post Direct - National 12,000.00 0.00 2022-11-28 2023-01-05 2022-12-08 2022-12-13 2022-12-23 2023-06-21 nse ant Selection ation Officer Surveillance MW-CHSU-327251-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Individual Consultancy - Data IDA / D8870 Post Direct - National 12,000.00 0.00 2022-11-28 2022-11-21 2022-12-08 2022-12-13 2022-12-23 2023-06-21 nse ant Selection ation Officer- Surveillance MW-CHSU-327259-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Consultacny Services- Data O IDA / D8870 Post Direct - National 12,000.00 0.00 2022-11-28 2022-11-21 2022-12-08 2022-12-13 2022-12-23 2023-06-21 nse ant Selection ation fficer- Laboratory MW-CHSU-327261-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Consultancy Services Data Of IDA / D8870 Post Direct - National 12,000.00 0.00 2022-11-28 2022-11-21 2022-12-08 2022-12-13 2022-12-23 2023-06-21 nse ant Selection ation ficer- Laboratory Page 4 MW-CHSU-327266-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Consultancy services for Dat IDA / D8870 Post Direct - National 12,000.00 0.00 2022-11-28 2022-11-21 2022-12-08 2022-12-13 2022-12-23 2023-06-21 nse ant Selection ation a Officer- Surveillance MW-CHSU-329216-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Consultancy Services for Acc IDA / D8870 Post Open - National 36,000.00 0.00 2022-12-01 2022-12-21 2023-01-09 2023-01-16 2023-01-24 2023-01-24 nse ant Selection ation ounts Assistant MW-CHSU-344844-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Individual Consultant- Life an IDA / 71770 Post Open - National 105,000.00 0.00 2023-02-28 2023-03-15 2023-04-11 2023-05-02 2023-06-06 2023-12-03 nse ant Selection ation d Fire Safety Specialist MW-CHSU-322677-CS-INDV / Emergency COVID-19 Respo Individual Consult Pending Impleme Consultancy services for Tec IDA / 71770 Post Limited 20,000.00 0.00 2023-07-02 2023-07-09 2023-07-16 2023-08-06 2024-08-05 nse ant Selection ntation hnical assistance to update N DVP MW-CHSU-362881-CS-INDV / Individual Consultancy Servic Emergency COVID-19 Respo Individual Consult Under Implement IDA / 71770 Post Limited 20,000.00 0.00 2023-06-11 2023-06-07 2023-06-18 2023-06-25 2023-07-06 2023-08-15 es to develop COVID 19 Inte nse ant Selection ation rgrated Vaccine Deployment Plan Page 5 Liberia: Ministry of Commerce & Industry Project Name: Liberia Investment, Finance and Trade (P171997) Loan #: P171997 PROCUREMENT PLAN (Textual Part) Project information: Liberia Investment, Finance and Trade (P171997) (P171997) Project Implementation agency: Ministry of Commerce & Industry Date of the Procurement Plan: November 2021 Period covered by this Procurement Plan: November 2021 to July 2022 ( PPA Procurement Plan) Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (Revised November 2017, August 2018 and November 2021 ) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works).Not Applicable. Goods: is not applicable Works: is not applicable Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Not Applicable Other Relevant Procurement Information. The project may use the CDD procurement under this project. If required, CDD manual will be produced by the project. PROCUREMENT Liberia : Liberia Investment, Finance and Trade Project PLAN General Information Country: Liberia 2022-02-09 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171997 GPN Date: Project Name: Liberia Investment, Finance and Trade Project Loan / Credit No: IDA / V3830, IDA / D9690 Ministry of Commerce and Industry Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MOCI-276208-GO-RFQ / P Component 1: Investment Cl Request for Quota Single Stage - One E rocurement of PIU Equipment IDA / V3830 Post Open - National 20,000.00 0.00 Canceled 2022-01-12 2022-03-09 2022-09-05 imate and Trade tions nvelope (Computer, Printer , Photoco pier LR-MOCI-276210-GO-RFQ / P Component 1: Investment Cl Request for Quota Single Stage - One E IDA / V3830 Post Open - National 20,000.00 0.00 Canceled 2022-01-12 2022-03-09 2022-09-05 rocurement of PIU Equipment imate and Trade tions nvelope (Funiture) LR-MOCI-276194-GO-RFQ / P Component 1: Investment Cl Request for Quota Single Stage - One E rocurement of Hardware to s IDA / V3830 Post Open - National 92,600.00 0.00 Canceled 2022-01-12 2022-03-09 2022-09-05 imate and Trade tions nvelope afeguard LBR Data LR-MOCI-276175-GO-RFQ / P Component 1: Investment Cl Request for Quota Single Stage - One E IDA / V3830 Post Open - National 50,000.00 0.00 Canceled 2022-03-19 2022-05-14 2022-11-10 rocurmentt of Vehicle imate and Trade tions nvelope LR-MOCI-289791-GO-RFQ / P Component 4: Project Imple Request for Quota Single Stage - One E IDA / V3830 Post Limited 50,000.00 0.00 Signed 2022-03-19 2022-02-28 2022-05-14 2022-11-10 rocurement of Vehicle mentation, M&E and CERC tions nvelope LR-MOCI-289794-GO-RFQ / P Component 4: Project Imple Request for Quota Single Stage - One E rocurement of Hardware to s IDA / V3830 Post Limited 92,600.00 0.00 Signed 2022-01-27 2022-02-28 2022-03-24 2022-09-20 mentation, M&E and CERC tions nvelope afeguard LBR Data LR-MOCI-289789-GO-RFQ / P Component 4: Project Imple Request for Quota Single Stage - One E rocurement of PIU Equipment IDA / V3830 Post Limited 20,000.00 0.00 Signed 2022-01-12 2022-02-28 2022-03-09 2022-09-05 mentation, M&E and CERC tions nvelope (Computer, Printer , Photoco pier LR-MOCI-289790-GO-RFQ / P Component 4: Project Imple Request for Quota Single Stage - One E IDA / V3830 Post Limited 20,000.00 0.00 Signed 2022-01-12 2022-02-28 2022-03-09 2022-09-05 rocurement of PIU Equipment mentation, M&E and CERC tions nvelope (Funiture) LR-MOCI-361340-GO-RFQ / P Component 1: Investment Cl Request for Quota Single Stage - One E Pending Impl rocurement of Vehicles for th IDA / D9690 Post Limited 450,000.00 0.00 2023-06-05 2023-07-31 2024-01-27 imate and Trade tions nvelope ementation e PIU and other TIMAS. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MOCI-355173-CS-QCBS / Consultancy Services to Man Component 2: SME Access t Quality And Cost- Open - Internationa IDA / D9690 Post 266,667.67 0.00 Canceled 2023-04-20 2023-04-10 2023-04-25 2023-04-13 2023-06-09 2023-07-07 2023-08-06 2023-09-10 2023-10-15 2024-10-14 age and Implement SME Tec o Markets and Finance Based Selection l hnical Assistance Program. LR-MOCI-360850-CS-QCBS / Consultancy Services to Man Component 2: SME Access t Quality And Cost- Open - Internationa Under Implement IDA / D9690 Prior 3,000,000.00 0.00 2023-05-31 2023-05-11 2023-06-21 2023-05-12 2023-08-04 2023-09-01 2023-10-01 2023-11-05 2023-12-10 2024-12-09 age and Implement SME Tec o Markets and Finance Based Selection l ation hnical Assistance Program. LR-MOCI-361331-CS-CQS / H iring of Consulting Firm to Up grade, Expand, and Maintain Component 2: SME Access t Consultant Qualifi Open - Internationa Under Implement IDA / D9690 Post 225,000.00 0.00 2023-05-31 2023-06-13 2023-06-21 2023-06-25 2023-08-04 2023-09-03 2023-10-08 2024-04-05 the Liberia’s Concessions Inf o Markets and Finance cation Selection l ation ormation System (CIMS) and automate the National Burea u of Concession's website. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MOCI-276196-CS-INDV / Component 1: Investment Cl Individual Consult IDA / V3830 Post Open 40,000.00 0.00 Canceled 2021-09-07 2021-10-26 2021-11-16 2021-12-21 2022-06-19 ESMF Consultancy Recruitme imate and Trade ant Selection nt LR-MOCI-276173-CS-INDV / Component 1: Investment Cl Individual Consult IDA / V3830 Post Open 20,000.00 0.00 Canceled 2022-01-07 2022-02-25 2022-03-18 2022-04-22 2022-10-19 Recruitment of Project Assist imate and Trade ant Selection ant MOCI-REF-4 / PPSD Consulta Component 1: Investment Cl Individual Consult IDA / V3830 Post Open 9,500.00 0.00 Canceled 2021-11-16 2022-01-04 2022-01-25 2022-03-01 2022-08-28 ncy Recruitment imate and Trade ant Selection LR-MOCI-276198-CS-INDV / Component 1: Investment Cl Individual Consult IDA / V3830 Post Open 42,000.00 0.00 Signed 2021-11-24 2022-03-30 2022-01-12 2022-02-09 2022-02-02 2022-08-10 2022-03-09 2022-09-05 PIU Procurement Specialist R imate and Trade ant Selection ecruitment Page 1 LR-MOCI-276209-CS-INDV / Component 1: Investment Cl Individual Consult IDA / V3830 Post Open 72,000.00 0.00 Signed 2021-11-24 2022-03-30 2022-01-12 2022-06-26 2022-02-02 2022-06-29 2022-03-09 2022-09-05 PIU Project Coordinator Recru imate and Trade ant Selection itment LR-MOCI-276206-CS-INDV / Component 1: Investment Cl Individual Consult IDA / V3830 Post Open 42,000.00 0.00 Signed 2022-01-07 2022-03-30 2022-02-25 2022-09-01 2022-03-18 2022-09-01 2022-04-22 2022-10-19 PIU Finance Officer Recruitm imate and Trade ant Selection ent LR-MOCI-276195-CS-INDV / Component 1: Investment Cl Individual Consult IDA / V3830 Post Open 20,000.00 0.00 Canceled 2022-05-08 2022-06-26 2022-07-17 2022-08-21 2023-02-17 Preparation Loan Administrat imate and Trade ant Selection ion Manual LR-MOCI-276197-CS-INDV / Component 1: Investment Cl Individual Consult Preparation of Detailed Proje IDA / V3830 Post Open 30,000.00 0.00 Canceled 2022-05-08 2022-06-26 2022-07-17 2022-08-21 2023-02-17 imate and Trade ant Selection ct operations Manual LR-MOCI-276199-CS-INDV / Component 1: Investment Cl Individual Consult Consultant to Develop a blue IDA / V3830 Post Open 82,900.00 0.00 Canceled 2022-05-08 2022-06-26 2022-07-17 2022-08-21 2023-02-17 imate and Trade ant Selection print for National single Wind ow LR-MOCI-276204-CS-INDV / Component 1: Investment Cl Individual Consult IDA / V3830 Post Open 20,000.00 0.00 Canceled 2022-05-08 2022-06-26 2022-07-17 2022-08-21 2023-02-17 SME TA Manual imate and Trade ant Selection LR-MOCI-276203-CS-INDV / Procurement of consultancy Component 1: Investment Cl Individual Consult services to carry out prelimin IDA / V3830 Post Open 60,000.00 0.00 Canceled 2022-05-08 2022-06-26 2022-07-17 2022-08-21 2023-02-17 imate and Trade ant Selection ary capacity building for stak eholders of Credit Registry LR-MOCI-276207-CS-INDV / Procurement of consultancy Component 1: Investment Cl Individual Consult IDA / V3830 Post Open 60,000.00 0.00 Canceled 2022-05-08 2022-06-26 2022-07-17 2022-08-21 2023-02-17 services to carry out prelimin imate and Trade ant Selection ary capacity building for stak eholders of the switch LR-MOCI-289797-CS-INDV / Component 4: Project Imple Individual Consult IDA / V3830 Post Limited 9,500.00 0.00 Signed 2021-11-16 2023-03-09 2021-11-21 2021-10-22 2021-12-12 2023-03-14 2022-01-16 2022-07-15 PPSD Consultancy Recruitme mentation, M&E and CERC ant Selection nt LR-MOCI-289795-CS-INDV / Component 4: Project Imple Individual Consult IDA / V3830 Post Limited 40,000.00 0.00 Signed 2021-09-07 2023-03-14 2021-09-12 2022-12-13 2021-10-03 2022-06-15 2021-11-07 2022-05-06 ESMF Consultancy Recruitme mentation, M&E and CERC ant Selection nt LR-MOCI-307953-CS-INDV / Component 4: Project Imple Individual Consult IDA / V3830 Post Open - National 60,000.00 0.00 Signed 2021-09-07 2021-09-19 2021-10-26 2022-08-10 2021-11-16 2022-08-10 2021-12-21 2022-06-19 SME Specialist Recruitment mentation, M&E and CERC ant Selection LR-MOCI-307959-CS-INDV / Component 4: Project Imple Individual Consult IDA / V3830 Post Open - National 42,000.00 0.00 Signed 2021-09-07 2021-09-19 2021-10-26 2022-07-28 2021-11-16 2022-08-12 2021-12-21 2022-06-19 Environmental Specialist Rec mentation, M&E and CERC ant Selection ruitment LR-MOCI-307958-CS-INDV / Component 4: Project Imple Individual Consult IDA / V3830 Post Open - National 42,000.00 0.00 Signed 2021-09-07 2021-09-19 2021-10-26 2022-08-08 2021-11-16 2022-08-08 2021-12-21 2022-06-19 Social Specialist Recruitment mentation, M&E and CERC ant Selection LR-MOCI-307955-CS-INDV / F Component 4: Project Imple Individual Consult inancial Sector Development IDA / V3830 Post Open - National 60,000.00 0.00 Signed 2021-09-07 2021-09-19 2021-10-26 2022-09-01 2021-11-16 2022-09-01 2021-12-21 2022-06-19 mentation, M&E and CERC ant Selection Specialist Recruitment LR-MOCI-345261-CS-INDV / Consultancy Services to Asse Component 3: Digital Financi Individual Consult Direct - Internation ss the National Electronic Pa IDA / V3830 Post 35,000.00 0.00 Signed 2023-02-28 2023-03-20 2023-03-10 2023-04-13 2023-03-31 2023-04-14 2023-05-05 2023-11-01 al Services Infrastructure ant Selection al yment Switch (NEPS) Data C enters at the Central Bank of Liberia LR-MOCI-345265-CS-INDV / Hiring a consultant to conduc t Feasibility Studies and Dev Component 3: Digital Financi Individual Consult Direct - Internation IDA / V3830 Post 35,000.00 0.00 Signed 2023-02-28 2023-02-23 2023-03-10 2023-04-14 2023-03-31 2023-04-14 2023-05-05 2023-11-01 elop Business Case on the N al Services Infrastructure ant Selection al ATIONAL ELECTRONIC PAYME NT SWITCH (NEPS) at the Ce ntral Bank of Liberia (CBL). LR-MOCI-345363-CS-INDV / Component 4: Project Imple Individual Consult Recruitment of Project Procur IDA / D9690 Post Limited 18,000.00 0.00 Signed 2023-03-03 2023-03-06 2023-03-08 2023-06-02 2023-03-29 2023-06-02 2023-04-20 2023-07-01 mentation, M&E and CERC ant Selection ement Assistant for the LIFT PIU. LR-MOCI-348367-CS-INDV / Hiring of Consultant to devel Component 4: Project Imple Individual Consult IDA / D9690 Post Limited 48,000.00 0.00 Signed 2023-03-31 2023-04-14 2023-04-05 2021-09-15 2023-04-26 2021-09-10 2023-05-31 2023-11-27 op Environmental and Social mentation, M&E and CERC ant Selection Management Framework (ES MF) for the LIFT Project. LR-MOCI-358442-CS-INDV / Component 1: Investment Cl Individual Consult Under Implement Hiring of ICT Expert for the L IDA / D9690 Post Open - National 20,000.00 0.00 2023-04-30 2023-04-26 2023-06-18 2023-07-09 2023-08-13 2024-02-09 imate and Trade ant Selection ation abria Business Registry (LBR) . LR-MOCI-358443-CS-INDV / Component 1: Investment Cl Individual Consult Under Implement Hiring of Corporate Lawyer fo IDA / D9690 Post Open - National 12,000.00 0.00 2023-04-30 2023-04-26 2023-06-18 2023-07-09 2023-08-13 2024-02-09 imate and Trade ant Selection ation r the Liberia Business Registr y LR-MOCI-361326-CS-INDV / Consultancy Services to Provi de Technical Assistance on C Component 2: SME Access t Individual Consult Open - Internationa Under Implement IDA / D9690 Post 120,000.00 0.00 2023-05-31 2023-06-13 2023-07-19 2023-08-09 2023-09-13 2024-03-11 oncessions Monitoring, Evalu o Markets and Finance ant Selection l ation ation and Compliance at the National Bureau of Concessio ns. LR-MOCI-363913-CS-INDV / Component 1: Investment Cl Individual Consult Open - Internationa Under Implement Hiring of SME Advisor for the IDA / D9690 Post 120,000.00 0.00 2023-06-15 2023-05-29 2023-08-03 2023-08-24 2023-09-28 2024-03-26 imate and Trade ant Selection l ation Ministry of Commerce and In dustry. LR-MOCI-364199-CS-INDV / Hiring of Consultant to Devel op Request for Bid for the Na Component 3: Digital Financi Individual Consult Open - Internationa tional Electronic Payment Swi IDA / D9690 Post 45,000.00 0.00 Under Review 2023-06-15 2023-05-31 2023-07-19 2023-08-03 2023-08-23 2023-10-22 al Services Infrastructure ant Selection l tch (NEPS), support the revie w of the Bid Documents and selection of the appropriate v endor for the NEPS Implemen tation . Page 2 Plan de Passation des marchés du Projet d’Appui aux Communautés dépendantes de la Forêt (DGM-DRC) P149049 (TF0A0924). I. Général 1. Date d’élaboration : 8 février 2016 2. Date d’approbation par la Banque du Plan de Passation des Marches : 8 février 2016 - Version négociée 3. Date de l’Avis Général de Passation des marchés: 4. Période couverte par ce Plan : Janvier à Décembre 2016 5. Risque passation des marchés : Substantiel II. Biens et Travaux et services autres que ceux de consultants. 1. Seuil de revue préalable: au-dessus duquel le processus de passation des marchés fait l’objet d’une revue préalable de la Banque mondiale tel que décrit dans l’annexe 1 des Directives pour l’acquisition de biens et de services autres que ceux de consultants. Nature des Méthode de passation Valeur seuil Contrats soumis à dépenses de marchés du marché examen préalable de $EU l’IDA 1. Travaux Entente directe Tout montant Tout contrat supérieur ou égal à US$ 100 000 Demande de cotation – < 200.000 Aucun comparaison d’au moins 3 offres 2. AON ˂1 000.000 Tout contrat supérieur ou Fournitures égal à US$500 000 et services Consultation de < 100.000 Aucun assimilés Fournisseurs Entente directe Tout montant Tout contrat supérieur ou égal à US$ 100 000 N.B. : Toutes les justifications du recours à l’entente directe incluant le montant estimé du contrat sont à soumettre à la revue préalable de la Banque. 2. Liste globale des contrats d’équipement devant être financés sur le don de préparation et le projet. Date Réf. Cout Méthode Préfére prévue Commentai Description Revue No. estimés$ de nce pour res 1 Passatio nationa (Prior / l’ouvertur n des le Post) e des marchés (oui/no offres n) Acquisition de cinq 1 motos de brousse 12.000 CF Non Post 15/06/16 et 32 vélos Service informatique de configuration de 2 15/05/16 logiciels 5,000 CF Non Post spécialisés de comptabilité Assurance du 3 matériel roulant 15/06/16 2,000 ED Non Post (pour 3 ans) Contrat ouvert – tarif Impression et préférentiels duplication des négociés documents du 4 20,000 1/12/16 pour les projet, du Code AC Non Post prestations Forestier et des attendues décrets durant l’année CF= Consultations de Fournisseurs AC = Accord Cadre III. Sélection de Consultants 1. Seuil de revue préalable: au-dessus duquel le processus de sélection fait l’objet d’une revue préalable de la Banque mondiale tel que décrit dans l’annexe 1 des Directives pour la sélection et l’emploi de consultants. Nature de Méthode de Valeur seuil du Contrats soumis à examen dépenses passation de contrat préalable marchés $EU Consultan ≥ 200.000 Tout contrat supérieur ou ts égal à US$ 500 000 Firmes < 200.000 Aucun QC Tout montant Tout contrat supérieur ou égal à US$ 100 000 Entente directe 2 Consultan Tout montant Tout contrat supérieur ou ts Consultant égal à Individuel individuel 200 000 US$ s Entente directe Tout montant Tout contrat supérieur ou égal à US$ 100 000 Tous les TDRs, quelle que soit la valeur du contrat, sont soumis à examen préalable. Toutes les justifications du recours à l’entente directe incluant le montant estimé du contrat sont soumis à l’examen préalable de la Banque. QC = Qualifications du Consultant 2. Listes restreintes comprenant uniquement des candidats nationaux: Les listes restreintes pour les contrats de consultants estimées à un coût inférieur à $100,000 pour les services ordinaires et $200,000 pour les contrats de supervision peuvent être entièrement composées de consultants nationaux, suivant les dispositions du Paragraphe 2.7 des Directives pour l’emploi des Consultants. 1 2 3 4 5 6 7 8 Examen Date Ref. Description Montant Préalable prévue Date Commentaires No. Méthod estimé ou à pour prévue e de ($.US) postériori l’ouvertu pour sélectio par la re des attributio n Banque offres n Opérateur spécialisé Pour les 3 pour le suivi des premières plaintes, 1 ED 200,000 Priori 15/07/16 15/08/16 années – consultation Composante 3b - permanente des REPALEF communautés Réalisation pour 2 chaque APAC de la 1 seule sélection cartographie avec 5 lots de QC 225,000 Post 15/08/16 15/09/16 participative, du 45,000 USD – plan de gestion et du Composante 2b PARAR Opérateur spécialisé Pour 3 ans – 3 QC 45,000 Post 1/03/16 1/04/16 sur la question des Composante 1a – 3 droits fonciers des PA Etudes pour dégager des options susceptibles de 4 renseigner la CI 5,000 Post 15/08/16 15/09/16 Composante 1a réforme foncière sur l'accès des PA à la terre Opérateur spécialisé pour créer des Pour 3 ans - 5 lobbies pour QC 45,000 Post 1/03/16 1/04/16 Composante 1a l'adoption de la loi sur les PA Opérateur spécialisé pour l'appui à la gestion Pour 3 ans - 6 QC 45,000 Post 1/03/16 1/04/16 communautaire de Composante 1a l'affectation des terres (APAC) Opérateurs pour Les lots seront l'alphabétisation des définis après le PACL impliqués dans diagnostic la gestion du projet institutionnel et les former à la initial pour 7 QC 40,000 Post 15/08/16 15/09/16 gestion et à la petite identifier les comptabilité (tenue opérateurs du livre de caisse, locaux et les gestion des entrées besoins - et des sorties, etc) Composante 1b Consultant appui Conservation Communautaire 8 CI 5,000 Post 15/2/16 10/03/16 pour le bilan des expériences existantes Contrat 3 ans 9 Expert Sauvegardes CI 70,000 Post 15/07/16 15/08/16 renouvelable - Composante 3a Appui pour la finalisation - Rédaction du Manuel 10 CI 5,000 Post 1/03/16 1/04/16 pour la mise en de mise en œuvre vigueur - Composante 3a Pour 3 ans - 11 Auditeur externe SMC 45,000 Post 15/07/16 15/08/16 Composante 3a En vue de la Expert technique revue à mi- 12 CI 30,000 Post 15/11/16 15/12/16 indépendant parcours - Composante 3b 4 5 PROCUREMENT Congo, Democratic Republic of : Forest Dependent Communities Support Project PLAN General Information Country: Congo, Democratic Republic of 2018-09-19 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P149049 GPN Date: Project Name: Forest Dependent Communities Support Project Loan / Credit No: TF / A0924, TF / A5550 CARITAS CONGO Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-CARITAS-125539-GO-RF Component 3 - Increase the Q / 40 téléphones (+4) Andro capacity to implement the IP Request for Quota Single Stage - One E TF / A0924 Post Limited 15,600.00 6,783.00 Signed 2019-08-05 2019-10-29 2019-09-30 2020-03-14 2020-03-28 id pour le suivi des indicateur LC development activities a tions nvelope s avec KOBO. nd consolidate feedback NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-CARITAS-83598-NC-RFQ / Contrat - Cadre avec Imprim Component 1 - Reinforce the eurs (plusieurs lots) pour mo participation of the IPLC in fo Request for Quota Single Stage - One E Pending Impl TF / A0924 Post Limited 60,000.00 0.00 2018-11-05 2018-12-31 2019-06-29 dules d'alphabétisation , cod rest and land management tions nvelope ementation e forestier, textes sur le fonci processes related to REDD+ er (40000 documents de taill es diverses) ZR-CARITAS-122739-CS-CDS Component 1 - Reinforce the / Transport et distribution de participation of the IPLC in fo Request for Quota Single Stage - One E Pending Impl s modules dans les territoires TF / A0924 Post Limited 8,000.00 0.00 2019-07-31 2019-09-25 2020-03-23 rest and land management tions nvelope ementation avec AEN ( consultations de processes related to REDD+ trois transporteurs pour dem ande des prixà ZR-CARITAS-83603-NC-RFQ / Component 1 - Reinforce the Transport des documents po participation of the IPLC in fo Request for Quota Single Stage - One E TF / A0924 Post Limited 3,000.00 0.00 Canceled 2018-11-05 2018-12-31 2019-06-29 ur Kisangani, Mbujimayi, Go rest and land management tions nvelope ma, Kanange, Inongo et Mba processes related to REDD+ ndaka ZR-CARITAS-175242-NC-RFQ / Sélection d'un prestataire p Component 2 - Support com Request for Quota Single Stage - One E our la reproduction des docu TF / A0924 munity-based sustainable fo Post Limited 12,750.00 0.00 Canceled 2020-07-25 2020-09-19 2021-03-18 tions nvelope ments sur le foncier, foresteri rest and land management e communautaire et amenag ement du territoire CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3 - Increase the ZR-CARITAS-66039-CS-CDS / capacity to implement the IP Consultant Qualifi Recrutement point focal INO TF / A0924 Post Open - National 18,000.00 0.00 Signed 2018-09-13 2018-09-13 2018-09-18 2023-06-01 2018-10-07 2023-06-05 2018-10-17 2023-06-09 2018-10-27 2019-04-25 LC development activities a cation Selection NGO nd consolidate feedback ZR-CARITAS-241037-CS-QCB Component 3 - Increase the S / Recrutement d'un Cabinet capacity to implement the IP Consultant Qualifi TF / A0924 Post Open - National 6,000.00 8,260.00 Signed 2021-07-14 2021-07-15 2021-07-17 2021-09-10 2021-07-24 2021-07-27 2021-07-29 2021-07-30 2021-08-08 2021-08-11 2021-09-07 d'Audit pour Auditer les Etats LC development activities a cation Selection financiers du Projet DGM exe nd consolidate feedback rcice 2020 ZR-CARITAS-49120-CS-CDS / Component 3 - Increase the CAUDITEC - Recrutement d'u capacity to implement the IP Quality And Cost- n Auditeur externe pour la c TF / A0924 Post Open - National 40,000.00 0.00 Canceled 2018-10-31 2018-10-31 2018-11-21 2019-01-04 2019-02-01 2019-03-03 2019-04-07 2019-05-12 2020-05-11 LC development activities a Based Selection ertification des comptes de l nd consolidate feedback a DGM pour les comptables 2 016, 2017 et 2018 ZR-CARITAS-280030-CS-QCB Component 3 - Increase the S / Recrutement d'un auditeu capacity to implement the IP Quality And Cost- r externe pour la reddition de TF / A0924 Post Open - National 40,000.00 0.00 Signed 2022-03-07 2023-06-12 2022-03-28 2023-06-22 2022-05-11 2023-06-20 2022-06-08 2023-06-20 2022-07-08 2023-06-20 2022-08-12 2023-06-20 2022-09-16 2023-09-16 LC development activities a Based Selection s comptes du projet DGM exe nd consolidate feedback rcices 2016, 2017 et 2018 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3 - Increase the ZR-CARITAS-66157-CS-CDS / capacity to implement the IP Individual Consult TF / A0924 Post Open 22,500.00 0.00 Canceled 2018-10-31 2019-10-01 2018-12-19 2019-01-09 2019-02-13 2019-08-12 PF Sauvegardes KISANGANI LC development activities a ant Selection nd consolidate feedback Component 3 - Increase the ZR-CARITAS-66158-CS-CDS / capacity to implement the IP Individual Consult TF / A0924 Post Open 9,000.00 0.00 Signed 2018-10-31 2019-10-01 2018-12-19 2023-06-05 2019-01-09 2023-06-07 2019-02-13 2019-08-12 PF Sauvegardes GOMA LC development activities a ant Selection nd consolidate feedback Component 3 - Increase the ZR-CARITAS-66159CS-CDS / capacity to implement the IP Individual Consult Under Implement TF / A0924 Post Open 13,500.00 0.00 2018-10-31 2018-10-31 2018-12-19 2019-01-09 2019-02-13 2019-08-12 PF Sauvegardes KANANGA LC development activities a ant Selection ation nd consolidate feedback Page 1 Component 3 - Increase the ZR-CARITAS-66159-CS-CDS / capacity to implement the IP Individual Consult TF / A0924 Post Open 22,500.00 0.00 Signed 2018-10-31 2019-10-01 2018-12-19 2023-06-04 2019-01-09 2023-06-06 2019-02-13 2019-08-12 PF Sauvegardes MBUJIMAYI LC development activities a ant Selection nd consolidate feedback Component 3 - Increase the ZR-CARITAS-83607-CS-INDV capacity to implement the IP Individual Consult Under Implement TF / A0924 Post Open 72,000.00 0.00 2018-10-25 2018-10-25 2018-12-13 2019-01-03 2019-02-07 2019-08-06 / Expert Sauvegardes LC development activities a ant Selection ation nd consolidate feedback Component 3 - Increase the ZR-CARITAS-66156-CS-CDS / capacity to implement the IP Individual Consult TF / A0924 Post Open 18,000.00 0.00 Canceled 2018-10-31 2018-12-19 2019-01-09 2019-02-13 2019-08-12 PF sauvegardes INONGO LC development activities a ant Selection nd consolidate feedback ZR-CARITAS-122805-CS-CDS Component 1 - Reinforce the / Salaire expert sauvegarde e participation of the IPLC in fo Individual Consult nv. et sociale et mission suivi TF / A0924 Post Limited 126,000.00 0.00 Canceled 2019-08-08 2019-08-13 2019-09-03 2019-10-08 2020-04-05 rest and land management ant Selection sauvegarde (respect des cad processes related to REDD+ res de gestion environnemen tale et sociale ZR-CARITAS-62547-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as BUKAVU sur l'Alphabétisat TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-06-22 2020-07-24 2020-07-02 2020-08-03 2020-09-05 2020-08-14 2021-03-04 rest and land management ion Dio BUKAVU, Territoire de processes related to REDD+ KALEHE . Component 1 - Reinforce the ZR-CARITAS-49616-CS-CDS / participation of the IPLC in fo Alphabétisation Dio KANANG TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2019-07-16 2020-07-24 2019-07-26 2020-08-03 2019-09-29 2020-08-25 2020-03-27 rest and land management A, Territoire de DIMBELENGE processes related to REDD+ ZR-CARITAS-62538-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as diocese de MWEKA pour l' TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-06-22 2020-07-24 2020-07-02 2020-08-03 2020-09-05 2020-08-21 2021-03-04 rest and land management éducation de base et l'alphab processes related to REDD+ étisation territoire MWEKA ZR-CARITAS-62540-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as diocese d'INONGO, territoi TF / A0924 Post Direct Selection Direct 18,000.00 18,000.00 Signed 2020-06-25 2020-07-24 2020-07-05 2020-08-06 2020-09-08 2020-08-11 2021-03-07 rest and land management re de KIRI, OSWE et INONGO processes related to REDD+ pour l'éducation de base et l' alphabétisation . ZR-CARITAS-62543-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as diocese d'ISANGI, territoir TF / A0924 Post Direct Selection Direct 12,000.00 12,000.00 Signed 2020-07-20 2020-07-24 2020-07-30 2020-07-27 2020-10-03 2020-08-11 2021-04-01 rest and land management e de YAHUMA et OPALA pour processes related to REDD+ l'éducation de base et l'alpha bétisation ZR-CARITAS-62546-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-07-31 2020-07-24 2020-08-10 2020-08-06 2020-10-14 2020-08-12 2021-04-12 as diocese de MBANDAKA BI rest and land management KORO, territoire de BIKORO processes related to REDD+ Component 1 - Reinforce the ZR-CARITAS-83577-CS-CDS / participation of the IPLC in fo Alphabétisation Dio WAMBA - TF / A0924 Post Direct Selection Direct 12,000.00 12,000.00 Signed 2020-06-26 2020-07-24 2020-07-06 2020-08-03 2020-09-09 2020-08-11 2021-03-08 rest and land management MAMBASA ET BAFWASENDE processes related to REDD+ ZR-CARITAS-175241-CS-CDS Component 3 - Increase the / Renouvelement de contrat capacity to implement the IP avec REPALEF avec les opéra TF / A0924 Post Direct Selection Direct 120,950.00 0.00 Signed 2020-07-27 2016-07-01 2020-08-06 2016-07-11 2020-10-10 2021-04-08 LC development activities a teurs pour le suivi de satifact nd consolidate feedback ion et gestion des plainte 20 20 2022 ZR-CARITAS-62460-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as diocese de KABINDA pour TF / A0924 Post Direct Selection Direct 18,000.00 18,000.00 Signed 2020-06-17 2021-03-17 2020-06-27 2020-07-27 2020-09-15 2020-08-21 2021-03-14 rest and land management l'alphabétisation , Territoire K processes related to REDD+ ABINDA, LUBAO et LUSAMBO ZR-CARITAS-185697-CS-CDS / Contractualisation avec l'O NG FONDATION NSELALA pou Component 2 - Support com r valorisation des initiatives l TF / A0924 munity-based sustainable fo Post Direct Selection Direct 61,000.00 61,000.00 Signed 2020-08-10 2021-03-18 2020-08-20 2020-08-24 2020-09-15 2020-11-11 2021-03-14 ocales des plantations d'arbr rest and land management es dans le secteur entre LUK ENI - LOKORO , Territoire de 0shwe ZR-CARITAS-185700-CS-CDS / Contractualisation avec l'O Component 2 - Support com NG EQUIPE MIKA pour la valo TF / A0924 munity-based sustainable fo Post Direct Selection Direct 61,000.00 66,077.00 Signed 2020-08-10 2021-03-18 2020-08-20 2020-08-24 2020-09-15 2020-11-03 2021-03-14 risation des initiatives locales rest and land management des plantations d'arbres dans le secteur de Penzwa, Territo ire de Kiri ZR-CARITAS-175248-CS-CDS / Renouvelement de contrat Component 1 - Reinforce the avec LINAPYCO pour la Colle participation of the IPLC in fo Under Implement TF / A0924 Post Direct Selection Direct 120,000.00 0.00 2020-07-13 2020-07-13 2020-07-23 2020-07-23 2020-09-26 2021-03-25 cte des données sur les terre rest and land management ation s des PA pour la reconnaissa processes related to REDD+ nce légale et la sécurisation des terres ZR-CARITAS-62535-CS-CDS / Contractualisation avec Carit Component 1 - Reinforce the as diocese de MUJIMAYI , terri participation of the IPLC in fo toire de LUPATAPATA Les Les TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-06-29 2021-03-17 2020-07-09 2020-07-27 2020-09-15 2020-08-21 2021-03-14 rest and land management justificatifs techniques ( note processes related to REDD+ s méthodologiques et cv des alphabétiseurs vous parviend rons par mail. ZR-CARITAS-185701-CS-CDS / Contractualisation avec le C entre National d'appui au Dé veloppement et à la participa Component 2 - Support com tion populaire (CENEDEP) po TF / A0924 munity-based sustainable fo Post Direct Selection Direct 66,000.00 0.00 Canceled 2020-08-10 2020-08-20 2020-09-15 2021-03-14 ur l'amélioration des capacit rest and land management és de 280 ménages PA et CO LO à planter et entretenir les arbres de la forêt MOBOKON DA secteur INONGO ZR-CARITAS-62464-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as diocese de KOLE pour l'éd TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-09-21 2021-03-16 2020-10-01 2020-07-27 2021-11-22 2020-08-21 2022-02-20 rest and land management ucation de base et l'alphabéti processes related to REDD+ sation des PA et COLO Territo ire de DEKESE Page 2 ZR-CARITAS-189907-CS-CDS Component 1 - Reinforce the / Contractualisation avec l'O participation of the IPLC in fo NG CENADEP pour l'élevage TF / A0924 Post Direct Selection Direct 65,000.00 65,416.00 Signed 2020-09-21 2021-03-18 2020-10-01 2020-08-26 2020-12-05 2020-11-06 2021-06-03 rest and land management des porcs à MOMBOKONDA, processes related to REDD+ dans le Territoire d’INONGO ZR-CARITAS-185690-CS-CDS / Contractualisation avec l'O NG Programme d'intégration Component 1 - Reinforce the et du développement des pe participation of the IPLC in fo uples pygmées (PIDP) pour l' TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Signed 2020-09-15 2020-09-08 2020-09-25 2021-09-18 2020-10-21 2021-04-19 rest and land management éducation de base et l'alphab processes related to REDD+ étisation aux peuples autoch tones (PA ) et aux communa utés locales (COLO) pour le T erritoire de Walikale. ZR-CARITAS-62537-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-09-15 2021-03-17 2020-09-25 2020-07-27 2020-12-09 2020-08-21 2021-06-07 as de KISANGANI pour l'éduc rest and land management ation de base et l'alphabétisa processes related to REDD+ tion ZR-CARITAS-62539-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as diocese de TSHUMBE pour TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-09-15 2020-07-10 2020-09-25 2020-07-27 2020-10-28 2020-08-21 2021-04-26 rest and land management l'éducation de base et l'alpha processes related to REDD+ bétisation Territoire de LUBE FU ZR-CARITAS-154570-CS-CDS Component 2 - Support com / Contractualisation avec AN TF / A0924 munity-based sustainable fo Post Direct Selection Direct 80,000.00 0.00 Canceled 2020-07-21 2020-07-31 2020-10-04 2021-04-02 APAC pour l'organisation de r rest and land management éunions avec les peules auto chtones ZR-CARITAS-175245-CS-CDS / Avenant avec ANAPAC pour Component 2 - Support com suivi des dossiers de deman TF / A0924 munity-based sustainable fo Post Direct Selection Direct 12,000.00 0.00 Canceled 2020-07-27 2020-08-06 2020-10-10 2021-04-08 de auprès du Ministère de l'e rest and land management nvironnement et du Gouvern ement ZR-CARITAS-175244-CS-CDS / Renouvellement contrat AN APAC pour organiser des ass Component 2 - Support com emblées communautaires et TF / A0924 munity-based sustainable fo Post Direct Selection Direct 285,000.00 0.00 Canceled 2020-07-21 2020-07-21 2020-07-31 2020-07-31 2020-10-04 2021-04-02 réunions consultatives, d'ide rest and land management ntification, prospection des si tes à : Walikale, Bikoro et fin alisation dossier Mweka, Kiri et Mambasa ZR-CARITAS-196411-CS-CDS Component 1 - Reinforce the / Contractualisation avec DG participation of the IPLC in fo PA pour Suivi des loi au Parle TF / A0924 Post Direct Selection Direct 25,500.00 0.00 Signed 2020-09-28 2020-09-28 2020-10-08 2020-09-08 2020-12-12 2021-06-10 rest and land management ment et lutte contre la discri processes related to REDD+ mination pour les PA ZR-CARITAS-62578-CS-CDS / DIPED: Opérateur pour acco mpagner les communautés d Component 2 - Support com e Walikale dans l'identificatio TF / A0924 munity-based sustainable fo Post Direct Selection Direct 5,800.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 n des idées des microprojets rest and land management et des Opérateurs locaux d'a ppui aux communautés -Com posante 2.a.1 - Consultant ZR-CARITAS-62576-CS-CDS / UEFA: Opérateur pour accom pagner les communautés de Component 2 - Support com Kalehe dans l'identification d TF / A0924 munity-based sustainable fo Post Direct Selection Direct 5,800.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 es idées des microprojets et rest and land management des Opérateurs locaux d'app ui aux communautés -Compo sante 2.a.1 - Consultant ZR-CARITAS-49316-CS-CDS / CAIF- Opérateur pour accom Component 2 - Support com pagner les communautés (m TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,900.00 0.00 Canceled 2018-03-01 2018-03-11 2018-05-15 2018-11-11 icroprojets et des Opérateurs rest and land management locaux d'appui aux communa utés Lubao et Lubefu ZR-CARITAS-62579-CS-CDS / FECOFA: Opérateur pour acc ompagner les communautés Component 2 - Support com de Kabinda et Lusambo dans TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,900.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 l'identification des idées des rest and land management microprojets et des Opérateu rs locaux d'appui aux commu nautés -Composante 2.a.1 - Consultant ZR-CARITAS-62575-CS-CDS / GTF: Opérateur pour accomp agner les communautés de Y Component 2 - Support com ahuma et Opala dans l'identif TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 ication des idées des micropr rest and land management ojets et des Opérateurs locau x d'appui aux communautés -Composante 2.a.1 - Consult ant ZR-CARITAS-62572-CS-CDS / EPAP/RDC: Opérateur pour a ccompagner les communaut Component 2 - Support com és de Lupatapata et Dimbele TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,350.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 nge dans l'identification des i rest and land management dées des microprojets et des Opérateurs locaux d'appui au x communautés -Composant e 2.a.1 - Consultant ZR-CARITAS-62582-CS-CDS / APSVR:Opérateur pour acco mpagner les communautés d Component 2 - Support com e Mweka et Dekese dans l'id TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,700.00 0.00 Canceled 2018-05-14 2019-10-30 2018-05-24 2018-07-28 2019-01-24 entification des idées des mi rest and land management croprojets et des Opérateurs locaux d'appui aux communa utés -Composante 2.a.1 - Co nsultant ZR-CARITAS-62581-CS-CDS / OCEAN: Opérateur pour acco mpagner les communautés d Component 2 - Support com e Banalia, Bafwasende et Ma TF / A0924 munity-based sustainable fo Post Direct Selection Direct 12,950.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 mbasa dans l'identification d rest and land management es idées des microprojets et des Opérateurs locaux d'app ui aux communautés -Compo sante 2.a.1 - Consultant Page 3 ZR-CARITAS-49123-CS-CDS / Consultant Kasongo Kabusa Component 2 - Support com Raphael, chargé d'identificati TF / A0924 munity-based sustainable fo Post Direct Selection Direct 8,000.00 0.00 Canceled 2018-02-05 2018-02-15 2018-04-21 2018-10-18 on des expériences de mise rest and land management en œuvre des microprojets c ommunautaires ZR-CARITAS-125538-CS-CDS Component 1 - Reinforce the / Contrat REPEQ identificatio participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 10,000.00 0.00 Canceled 2019-08-31 2019-09-10 2019-11-14 2020-05-12 n des besoins en renforceme rest and land management nt des capacités processes related to REDD+ ZR-CARITAS-62580-CS-CDS / DIPY: Opérateur pour accom pagner les communautés d'I Component 2 - Support com nongo et Oshwe dans l'identi TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 fication des idées des microp rest and land management rojets et des Opérateurs loca ux d'appui aux communautés -Composante 2.a.1 - Consult ant ZR-CARITAS-49610-CS-CDS / -CIDB: Opérateur d'identificat Component 2 - Support com ion des micros projets et ON TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,600.00 0.00 Canceled 2018-03-01 2018-03-11 2018-05-15 2018-11-11 G locales ( Bikoro et Kiri) AN rest and land management O obtenu 25/09/2017 Component 1 - Reinforce the ZR-CARITAS-122741-CS-CDS participation of the IPLC in fo Individual Consult / Evaluation à mis parcours s TF / A0924 Post Limited 17,500.00 0.00 Canceled 2019-08-10 2019-08-15 2019-09-05 2019-10-10 2020-04-07 rest and land management ant Selection uivi processes related to REDD+ ZR-CARITAS-253078-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocésaine de M participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Under Review 2021-12-08 2020-09-08 2021-12-18 2022-02-21 2022-06-21 BANDAKA pour l'éducation d rest and land management e base et l'alphabétisation, T processes related to REDD+ erritoire de BIKORO composa nte 1b ZR-CARITAS-253085-CS-CDS / Renouvellement avec ANAP AC pour appui à l'élaboration des cartes des droits et d'aff Component 2 - Support com ectation des terres, plans de TF / A0924 munity-based sustainable fo Post Direct Selection Direct 113,500.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2021-12-18 2022-02-21 2022-06-21 sondage, Dépôt des dossiers rest and land management de demande de CFCL, Enquê te de vacance des terres, Ob tention de CFCL à Mweka, Bi ko, Walikale. composante 2b ZR-CARITAS-253091-CS-CDS Component 3 - Increase the / Renouvellement de Contrat capacity to implement the IP avec REPALEF pour le suivi d TF / A0924 Post Direct Selection Direct 40,500.00 0.00 Signed 2021-12-08 2021-12-08 2021-12-18 2021-12-18 2022-02-21 2022-06-21 LC development activities a e satisfaction et gestion des nd consolidate feedback plaintes. composante 3b ZR-CARITAS-253093-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec (CENADEP) pour l'améli participation of the IPLC in fo oration des capacités de 280 TF / A0924 Post Direct Selection Direct 38,045.00 0.00 Signed 2021-12-08 2022-02-28 2021-12-18 2022-03-10 2022-02-21 2022-06-21 rest and land management ménages PA et COLO à plant processes related to REDD+ er et entretenir les arbres de la forêt MOBOKONDA secteur INONGO. composante 2a ZR-CARITAS-253094-CS-CDS / Renouvellement contrat av ec l'ONG ADGRN pour le pro Component 2 - Support com jet de plantation d’arbres su TF / A0924 munity-based sustainable fo Post Direct Selection Direct 71,250.00 73,773.50 Signed 2021-12-08 2021-12-06 2021-12-18 2022-01-31 2022-02-21 2022-01-25 2022-03-05 r 45 ha et de promotion de l’ rest and land management élevage et de l'apiculture da ns les villages de Milela, Toko meka et Tshintu mwanza, Te rritoire de Lupatapata. comp osante 2a ZR-CARITAS-253072-CS-CDS / Renouvellement contrat Ca ritas diocésaine Kabinda po Component 1 - Reinforce the ur le projet d'appui à la prote participation of the IPLC in fo ction du forestière par l'agro TF / A0924 Post Direct Selection Direct 73,960.00 0.00 Signed 2021-12-08 2022-01-14 2021-12-18 2022-01-31 2022-03-08 2022-07-06 rest and land management foresterie et en faveur des p processes related to REDD+ euples autochtones pour les villages de Tulimbi, Ebaala et Kashoko, Territoire de Kabind a composante 2a ZR-CARITAS-253097-CS-CDS / Renouvellement de contrat Component 2 - Support com avec l'ONG SPFA pour le proj TF / A0924 munity-based sustainable fo Post Direct Selection Direct 22,680.00 0.00 Signed 2021-09-30 2021-09-30 2021-10-10 2021-10-10 2021-12-14 2022-04-13 et d'appui à l'agroforesterie e rest and land management t à la pisciculture dans les vill ages Moboyo, Mboli et Iyand a, dans le Territoire de Bikor o ZR-CARITAS-253098-CS-CDS / Renouvellement contrat UE Component 2 - Support com FA projet d'amélioration des TF / A0924 munity-based sustainable fo Post Direct Selection Direct 48,760.00 0.00 Signed 2021-12-08 2021-07-01 2021-12-18 2023-01-01 2022-02-21 2022-06-21 écosystèmes forestiers avec l rest and land management a plantation d'arbres de 17 g roupements du Territoire de Kalehe, composante 2b ZR-CARITAS-253067-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocésaine Kisa participation of the IPLC in fo ngani pour donner l'Educatio TF / A0924 Post Direct Selection Direct 3,000.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2022-03-03 2022-07-01 rest and land management n de base et alphabétisation processes related to REDD+ aux PA et Communautés loca les Territoire BANALIA comp osante 1b ZR-CARITAS-253086-CS-CDS / Renouvellement de contrat avec l'ONG FONDATION NSEL Component 2 - Support com ALA pour valorisation des init TF / A0924 munity-based sustainable fo Post Direct Selection Direct 30,761.00 0.00 Signed 2021-12-08 2021-12-08 2021-12-18 2022-02-07 2022-01-13 2022-05-13 iatives locales des plantation rest and land management s d'arbres dans le secteur en tre LUKENI - LOKORO, Territoi re de 0shwe. composante 2a ZR-CARITAS-253090-CS-CDS / Renouvellement de Contrat Component 1 - Reinforce the avec LINAPYCO pour la Colle participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 61,790.00 0.00 Signed 2021-12-08 2021-12-08 2021-12-18 2021-12-18 2022-02-21 2022-06-21 cte des données sur les terre rest and land management s des PA pour la reconnaissa processes related to REDD+ nce légale et la sécurisation des terres. composante 1a Page 4 ZR-CARITAS-253096-CS-CDS / Renouvellement Contrat av ec l'ONG Programme d'intég Component 1 - Reinforce the ration et du développement participation of the IPLC in fo des peuples pygmées (PIDP) TF / A0924 Post Direct Selection Direct 42,300.00 0.00 Signed 2021-12-08 2016-07-01 2021-12-18 2022-12-09 2022-02-21 2022-06-21 rest and land management pour le projet d'amélioration processes related to REDD+ des capacités de production agropastorale des ménages autochtones pygmées dans l e Territoire de Walikale. com pos 2a ZR-CARITAS-253099-CS-CDS / Renouvellement contrat DG Component 1 - Reinforce the PA pour soutien à la finalisati participation of the IPLC in fo on de 4 concessions : Bondo, TF / A0924 Post Direct Selection Direct 106,636.00 0.00 Signed 2021-09-30 2017-07-17 2021-10-10 2017-07-27 2021-12-14 2022-04-13 rest and land management Kombe, Mitshia, Tongonwena processes related to REDD+ forestières des communauté s locales de TSHIEFU / Territo ire de Dimbelenge. composa nte 2b ZR-CARITAS-253095-CS-CDS / Contractualisation avec CA RITAS Kabinda pour le pro d Component 2 - Support com 'appui à la protection du cou TF / A0924 munity-based sustainable fo Post Direct Selection Direct 71,359.00 0.00 Signed 2022-01-27 2022-01-27 2022-02-06 2022-02-18 2022-04-12 2022-08-10 ver forestier par l'agroforeste rest and land management rie, la porciculture et la picic ulture en faveur des peuples autochtones des villages d'E baala et Kangulube, Territoir e de Lubao. c 2a ZR-CARITAS-253087-CS-CDS / Renouvellement de contrat avec l'ONG EQUIPE MIKA pou Component 2 - Support com r la valorisation des initiative TF / A0924 munity-based sustainable fo Post Direct Selection Direct 12,500.00 0.00 Signed 2021-12-08 2021-12-08 2021-12-18 2021-12-18 2022-01-13 2022-05-13 s locales des plantations d'ar rest and land management bres dans le secteur de Penz wa, Territoire de Kiri. compos ante 2a ZR-CARITAS-280706-CS-CDS / CAIF- Opérateur pour acco Component 2 - Support com mpagner les communautés ( TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-24 2022-12-21 microprojets et des Opérateu rest and land management rs locaux d'appui aux commu nautés Lubao et Lubefu ZR-CARITAS-280677-CS-CDS / EPAP/RDC: Opérateur pour accompagner les communau Component 2 - Support com tés de Lupatapata et Dimbel TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-24 2022-12-21 enge dans l'identification des rest and land management idées des microprojets et des Opérateurs locaux d'appui au x communautés -Composant e 2.a.1 - Consultant ZR-CARITAS-280720-CS-CDS / Recrutement d'un opérateu r spécialisé, chargé d'organis er des assemblées communa Component 2 - Support com utaires et d'accompagner les TF / A0924 munity-based sustainable fo Post Direct Selection Direct 80,000.00 0.00 Canceled 2022-04-10 2022-04-20 2022-06-24 2022-12-21 PA et communautés locales d rest and land management ans le processus de la reconn aissance formelle de leur con cession forestière et de leurs aires de conservation ZR-CARITAS-280674-CS-CDS / APSVR: Opérateur pour acc ompagner les communautés Component 2 - Support com de Mweka et Dekese dans l'i TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-24 2022-12-21 dentification des idées des m rest and land management icroprojets et des Opérateurs locaux d'appui aux communa utés -Composante 2.a.1 - Co nsultant ZR-CARITAS-280683-CS-CDS / OCEAN: Opérateur pour acc ompagner les communautés Component 2 - Support com de Banalia, Bafwasende et M TF / A0924 munity-based sustainable fo Post Direct Selection Direct 12,950.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-24 2022-12-21 ambasa dans l'identification rest and land management des idées des microprojets et des Opérateurs locaux d'app ui aux communautés -Compo sante 2.a.1 - Consultant ZR-CARITAS-280711-CS-CDS / DIPY: Opérateur pour acco mpagner les communautés d Component 2 - Support com 'Inongo et Oshwe dans l'ident TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-24 2022-12-21 ification des idées des micro rest and land management projets et des Opérateurs loc aux d'appui aux communaut és -Composante 2.a.1 – Cons ultant ZR-CARITAS-281043-CS-CDS / Avenant avec ANAPAC pour Component 2 - Support com suivi des dossiers de demand TF / A0924 munity-based sustainable fo Post Direct Selection Direct 27,000.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-12-07 2022-06-24 2022-12-21 e auprès du Ministère de l'en rest and land management vironnement et du Gouverne ment ZR-CARITAS-280020-CS-CDS Component 2 - Support com / Identification des idées des TF / A0924 munity-based sustainable fo Post Direct Selection Direct 5,800.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-24 2022-12-21 micro-projets dans le territoir rest and land management e de Walikale ZR-CARITAS-280023-CS-CDS / UEFA: Opérateur pour acco mpagner les communautés d Component 2 - Support com e Kalehe dans l'identification TF / A0924 munity-based sustainable fo Post Direct Selection Direct 5,800.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-10 2022-12-07 des idées des microprojets et rest and land management des Opérateurs locaux d'app ui aux communautés -Compo sante 2.a.1 - Consultant ZR-CARITAS-280659-CS-CDS / FECOFA: Opérateur pour ac compagner les communauté Component 2 - Support com s de Kabinda et Lusambo à l'i TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Signed 2022-04-10 2022-04-20 2022-04-20 2022-10-12 2022-06-24 2022-12-21 dentification des idées des m rest and land management icroprojets et des Opérateurs locaux d'appui aux communa utés -Composante 2.a.1 - Co nsultant ZR-CARITAS-280688-CS-CDS / Contrat REPEQ renforcemen Component 1 - Reinforce the t des capacités dans le cadre participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 5,000.00 0.00 Signed 2022-04-10 2023-04-10 2022-04-20 2023-06-18 2022-06-24 2022-12-21 du plan d’action pour le déve rest and land management loppement et la promotion d processes related to REDD+ es droits des peuples autocht ones en RDC Page 5 Component 1 - Reinforce the ZR-CARITAS-280724-CS-CDS participation of the IPLC in fo / Evaluation externe à mi-par TF / A0924 Post Direct Selection Direct 20,000.00 0.00 Signed 2022-04-10 2023-06-12 2022-04-20 2023-06-18 2022-06-24 2022-12-21 rest and land management cours du projet PACDF processes related to REDD+ ZR-CARITAS-286914-CS-CDS / GTF: Opérateur pour accom pagner les communautés de Component 2 - Support com Yahuma et Opala dans l'ident Under Implement TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 2022-04-10 2023-06-12 2022-04-20 2023-06-18 2022-06-24 2022-12-21 ification des idées des micro ation rest and land management projets et des Opérateurs loc aux d'appui aux communaut és -Composante 2.a.1 – Cons ultant Component 1 - Reinforce the ZR-CARITAS-279788-CS-CQS participation of the IPLC in fo / Contractualisation avec le c TF / A0924 Post Direct Selection Direct 30,000.00 0.00 Canceled 2022-04-10 2022-04-20 2022-06-24 2022-12-21 rest and land management onsultant DGPA processes related to REDD+ ZR-CARITAS-281039-CS-CDS / ANAPAC: accompagner les PA et les COLO dans le proce ssus de la reconnaissance for Component 2 - Support com melle de leurs concessions fo TF / A0924 munity-based sustainable fo Post Direct Selection Direct 250,000.00 0.00 Signed 2022-05-20 2022-05-20 2022-05-30 2022-05-30 2022-08-03 2023-01-30 restières et des aires de cons rest and land management ervation et patrimoine autoc htone et communautaires da ns les sites de Walikale, Bikor o, Kiri, Mambasa et Mweka ZR-CARITAS-280041-CS-CDS / FECOFA: Opérateur pour ac compagner les communauté Component 2 - Support com s de Kabinda et Lusambo dan TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Canceled 2022-04-10 2022-04-10 2022-04-20 2022-06-24 2022-12-21 s l'identification des idées de rest and land management s microprojets et des Opérat eurs locaux d'appui aux com munautés -Composante 2.a.1 - Consultant ZR-CARITAS-281031-CS-CDS / Renouvèlement de contrat Component 1 - Reinforce the avec LINAPYCO pour la Collec participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 120,000.00 0.00 Canceled 2022-04-10 2022-04-20 2022-06-24 2022-12-21 te des données sur les terres rest and land management des PA pour la reconnaissanc processes related to REDD+ e légale et la sécurisation de s terres ZR-CARITAS-253083-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocésaine de M participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-12-08 2020-09-08 2021-12-18 2022-02-21 2022-06-21 WEKA pour l'éducation de ba rest and land management se et l'alphabétisation, Territ processes related to REDD+ oire MWEKA composante 1b ZR-CARITAS-300093-CS-CQS / POINT FOCAL: Suivi rapproc Component 2 - Support com Individual Consult Under Implement hé environnemental et social TF / A0924 munity-based sustainable fo Post Direct 3,000.00 0.00 2022-06-30 2022-10-11 2022-07-10 2022-07-31 2022-09-04 2023-03-03 ant Selection ation des activités des microprojet rest and land management s dans le territoire de Walikal e ZR-CARITAS-300099-CS-CQS / POINT FOCAL: Suivi rapproc Component 2 - Support com Individual Consult hé environnemental et social TF / A0924 munity-based sustainable fo Post Direct 3,000.00 0.00 Canceled 2022-06-30 2022-10-11 2022-07-10 2022-07-31 2022-09-04 2023-03-03 ant Selection des activités des microprojet rest and land management s dans le territoire de Kahele ZR-CARITAS-300107-CS-CQS / POINT FOCAL: Suivi rapproc hé environnemental et social Component 2 - Support com Individual Consult Under Implement des activités à Mbuji-Mayi da TF / A0924 munity-based sustainable fo Post Direct 9,000.00 0.00 2022-06-30 2022-10-11 2022-07-10 2022-07-31 2022-09-04 2023-03-03 ant Selection ation ns les territoires de Lupatapa rest and land management ta (Tshintumuanza, Tokomek a et Milela), Kabinda (Ebala - Tulimbi) et Lubao (Kangulube ) ZR-CARITAS-319901-CS-CDS Component 3 - Increase the / ADDEC: Recrutement d'une capacity to implement the IP ONG d'appui à la mise en œu TF / A5550 Post Direct Selection Direct - National 99,373.50 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-21 2022-12-25 2023-06-23 LC development activities a vre de microprojet à Kabala, nd consolidate feedback dans le territoire de Dimbele nge ZR-CARITAS-319916-CS-CDS / UNION POUR LE DEVELOPPE MENT DES MINORITES EKON Component 2 - Support com DA: Recrutement d'une ONG TF / A5550 munity-based sustainable fo Post Direct Selection Direct - National 108,749.00 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-22 2022-12-25 2023-06-23 d'appui à la mise en œuvre d rest and land management e microprojet à MPANGOLA, dans le territoire de LUSAMB O ZR-CARITAS-319961-CS-CDS / FODI: Recrutement d'une O Component 2 - Support com NG d'appui à la mise en œuv TF / A5550 munity-based sustainable fo Post Direct Selection Direct - National 104,749.00 0.00 Signed 2022-10-11 2022-10-11 2022-10-20 2022-10-21 2022-12-24 2023-06-22 re de microprojet dans le vill rest and land management age d'Itunga, territoire de Lu befu ZR-CARITAS-319986-CS-CDS / PCF: Recrutement d'une ON Component 1 - Reinforce the G d'appui à la mise en œuvre participation of the IPLC in fo TF / A5550 Post Direct Selection Direct - National 96,509.50 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-21 2022-12-25 2023-06-23 de microprojet à MANGBAUT rest and land management U, KILONDE, et BANANA GITE processes related to REDD+ dans le territoire de MAMBAS A ZR-CARITAS-319996-CS-CDS / CARITAS KABINDA: Recrute Component 2 - Support com ment d'une structure d'appui TF / A5550 munity-based sustainable fo Post Direct Selection Direct - National 72,509.00 0.00 Canceled 2022-10-11 2022-10-11 2022-10-21 2022-12-25 2023-06-23 à la mise en œuvre de micro rest and land management projet à TSHINTU MWANZA, MILELA et TOKOMEKA dans le territoire de LUPATAPATA ZR-CARITAS-320000-CS-CDS / ACODELPY: Recrutement d' Component 2 - Support com une ONG d'appui à la mise e TF / A5550 munity-based sustainable fo Post Direct Selection Direct - National 99,948.50 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-11 2022-12-25 2023-06-23 n œuvre de microprojet à BI rest and land management MELI, dans le territoire de BA FWASENDE Page 6 ZR-CARITAS-300080-CS-CDS / LIMA: Promotion des initiati ves de restauration de la forê t, développement des alterna Component 2 - Support com tives économiques compensa TF / A0924 munity-based sustainable fo Post Direct Selection Direct - National 111,383.50 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-21 2022-12-25 2023-06-23 toires aux efforts de la forêt rest and land management et contribution à la cohésion sociale entre les PA et les CO LO à Bomili dans le territoire de Bafwasende. Com 2a ZR-CARITAS-300070-CS-CDS / CARITAS ISANGI: Contributi on à la réduction de la pressi on sur la forêt par l'améliorat Component 2 - Support com ion de la production, commer TF / A0924 munity-based sustainable fo Post Direct Selection Direct - National 116,220.00 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-12-12 2022-12-25 2023-06-23 cialisation du riz, du manioc, rest and land management du miel et l'artisanat en fave ur des PA et des COLO à Yalo nde et Yasamola dans le terri toire de Yahuma. C 2a ZR-CARITAS-300059-CS-CDS / CARITAS ISANGI: Contributi on à la restauration de la for Component 2 - Support com êt, la croissance économique TF / A0924 munity-based sustainable fo Post Direct Selection Direct - National 83,056.00 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-21 2022-12-25 2023-06-23 de 150 ménages cibles et en rest and land management même temps à l'encouragem ent de la cohésion sociale de s PA et CL à Lieke Lesole dan s le territoire d'Opala. Compo sante 2a ZR-CARITAS-300115-CS-CDS / LIMA: Promotion des initiati ves de restauration de la forê t, développement des alterna Component 2 - Support com tives économiques compensa TF / A0924 munity-based sustainable fo Post Direct Selection Direct - National 111,383.50 0.00 Canceled 2022-10-11 2022-10-21 2022-12-25 2023-06-23 toires aux efforts de la forêt rest and land management et contribution à la cohésion sociale entre les PA et les CO LO à Bangbo dans le territoir e de Banalia. Comp 2a ZR-CARITAS-280716-CS-CDS / Consultant Kasongo Kabusa Component 2 - Support com Individual Consult Raphael, Chargé d’identificat TF / A0924 munity-based sustainable fo Post Direct - National 8,000.00 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-22 2022-11-11 2022-11-11 2022-12-16 2023-06-14 ant Selection ion des expériences de mise rest and land management en œuvre des microprojets c ommunautaires ZR-CARITAS-320534-CS-CDS / CARITAS KOLE: Recrutemen Component 2 - Support com t d'une ONG d'appui à la mis TF / A5550 munity-based sustainable fo Post Direct Selection Direct - National 99,603.00 0.00 Signed 2022-10-12 2022-11-21 2022-10-22 2022-12-01 2022-12-26 2023-06-24 e en œuvre de microprojet à rest and land management ITUNGA dans le territoire de DEKESE. Comp 2a ZR-CARITAS-320537-CS-CDS / CEDAP: Recrutement d'une ONG locale pour la mise en œuvre du projet de restaurat Component 2 - Support com Under Implement ion de la foret d'Itungampen TF / A5550 munity-based sustainable fo Post Direct Selection Direct - National 105,094.00 0.00 2022-10-12 2022-11-21 2022-10-22 2022-12-01 2022-12-26 2023-06-24 ation de à travers la plantation d'a rest and land management rbres et le développement de s alternatives économiques pour lutter contre la dégrada tion de la foret. Comp 2a ZR-CARITAS-320542-CS-IND V / POINT FOCAL: Recruteme Component 2 - Support com nt d'un consultant pour le sui Individual Consult TF / A5550 munity-based sustainable fo Post Direct - National 5,200.00 0.00 Signed 2022-10-12 2022-11-21 2022-10-22 2022-12-01 2022-11-12 2022-12-22 2022-12-17 2023-06-15 vi environnemental et social ant Selection rest and land management dans les territoires de BAFW ASENDE, YAHUMA, OPALA et BANALIA ZR-CARITAS-320547-CS-IND V / POINT FOCAL: Recruteme Component 2 - Support com Individual Consult nt d'un consultant pour le sui TF / A5550 munity-based sustainable fo Post Direct - National 1,000.00 0.00 Signed 2022-10-11 2022-11-21 2022-10-21 2022-11-26 2022-11-11 2022-12-17 2022-12-16 2023-06-14 ant Selection vi environnemental et social rest and land management dans le territoire de MAMBAS A ZR-CARITAS-320549-CS-IND V / POINT FOCAL: Recruteme Component 2 - Support com Individual Consult nt d'un consultant pour le sui TF / A5550 munity-based sustainable fo Post Direct - National 4,200.00 0.00 Signed 2022-10-12 2022-11-21 2022-10-22 2022-12-01 2022-11-12 2022-12-22 2022-12-17 2023-06-15 ant Selection vi environnemental et social rest and land management dans les territoires de MWEK A, DEKESE et DIMBELENGE ZR-CARITAS-320552-CS-IND V / POINT FOCAL: Recruteme Component 2 - Support com Individual Consult nt d'un consultant pour le sui TF / A5550 munity-based sustainable fo Post Direct - National 3,400.00 0.00 Signed 2022-10-12 2022-11-21 2022-10-22 2022-12-01 2022-11-12 2022-12-22 2022-12-17 2023-06-15 ant Selection vi environnemental et social rest and land management dans les territoires de LUSAM BO ET LUBEFU ZR-CARITAS-253070-CS-CDS / Renouvellement contrat Car Component 1 - Reinforce the itas Mbujimayi pour donner l' participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 5,400.00 0.00 Canceled 2021-12-08 2021-07-08 2021-12-18 2022-02-24 2022-06-24 éducation de base et alphab rest and land management étisation aux PA et communa processes related to REDD+ utés locales territoire de LUP ATAPATA composante 1b ZR-CARITAS-253063-CS-CDS / Renouvellement contrat av Component 1 - Reinforce the ec Caritas diocèse Kananga p participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2022-02-21 2022-06-21 our l'Education de base des P rest and land management A et communautés locales Te processes related to REDD+ rritoire de Dimbelenge comp 1b ZR-CARITAS-253084-CS-CDS Component 1 - Reinforce the / Renouvellement contrat av participation of the IPLC in fo ec Caritas diocésaine de WA TF / A0924 Post Direct Selection Direct 12,000.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2022-02-21 2022-06-21 rest and land management MBA Alphabétisation Dio WA processes related to REDD+ MBA - MAMBASA ET BAFWAS ENDE composante 1b ZR-CARITAS-253082-CS-CDS Component 1 - Reinforce the / Renouvellement de contrat participation of the IPLC in fo avec Caritas BUKAVU sur l'Al TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-12-08 2020-09-08 2021-12-18 2020-09-22 2022-02-21 2022-06-21 rest and land management phabétisation Dio BUKAVU, T processes related to REDD+ erritoire de KALEHE composa nte 1b ZR-CARITAS-253089-CS-CDS Component 1 - Reinforce the / Renouvellement de Contrat participation of the IPLC in fo avec DGPA pour Suivi des loi TF / A0924 Post Direct Selection Direct 30,000.00 0.00 Canceled 2021-12-08 2020-09-08 2021-12-18 2022-02-21 2022-06-21 rest and land management au Parlement et lutte contre l processes related to REDD+ a discrimination pour les PA. composante 1a Page 7 ZR-CARITAS-280035-CS-CDS / CAIF- Opérateur pour acco Component 2 - Support com mpagner les communautés à TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,900.00 0.00 Canceled 2022-04-10 2022-04-20 2022-06-24 2022-12-21 l’identification des micro-proj rest and land management ets pour les territoires de Lub ao et Lubefu ZR-CARITAS-253092-CS-CDS / Renouvellement de Contrat avec l'ONG Programme d'inté Component 1 - Reinforce the gration et du développement participation of the IPLC in fo des peuples pygmées (PIDP) TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-12-08 2020-09-08 2021-12-18 2022-01-13 2022-05-13 rest and land management pour l'éducation de base et l' processes related to REDD+ alphabétisation aux peuples autochtones (PA ) et aux com munautés locales (COLO) po ur le Territoire de Walikale. c 1b ZR-CARITAS-253073-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocésaine de d participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2022-05-31 2022-09-28 e KOLE pour l'éducation de b rest and land management ase et l'alphabétisation des P processes related to REDD+ A et COLO Territoire de DEKE SE composante 1b ZR-CARITAS-253088-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocèse d'ISANG participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 12,000.00 0.00 Canceled 2021-12-08 2021-12-27 2021-12-18 2022-01-15 2022-02-21 2022-06-21 I, territoire de YAHUMA et OP rest and land management ALA pour l'éducation de bas processes related to REDD+ e et l'alphabétisation. compo sante 1b ZR-CARITAS-280699-CS-CDS / Identification des idées des Component 2 - Support com microprojets et des organisat TF / A0924 munity-based sustainable fo Post Direct Selection Direct 5,900.00 0.00 Canceled 2022-04-10 2022-04-20 2022-06-24 2022-12-21 ions et site d'implémentation rest and land management du microprojet à Walikale ZR-CARITAS-253081-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocésaine de K participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 18,000.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2022-03-08 2022-07-06 ABINDA pour l'alphabétisatio rest and land management n , Territoire KABINDA, LUBA processes related to REDD+ O et LUSAMBO composante 1 b ZR-CARITAS-294564-CS-CQS Component 3 - Increase the / Recrutement d'un auditeur capacity to implement the IP Individual Consult externe pour la révision du m TF / A0924 Post Direct 3,000.00 0.00 Canceled 2022-06-24 2022-10-11 2022-07-04 2022-07-25 2022-08-29 2023-02-25 LC development activities a ant Selection anuel des procédures admini nd consolidate feedback stratives et financières du pr ojet PACDF ZR-CARITAS-242600-CS-IND Component 3 - Increase the V / Recrutement d'un consult capacity to implement the IP Individual Consult ant individuel pour la révisio TF / A0924 Post Limited 4,000.00 0.00 Canceled 2021-07-30 2021-08-04 2021-08-25 2021-09-29 2021-11-13 LC development activities a ant Selection n du manuel des procédures nd consolidate feedback administratives et financière s du projet PCDF ZR-CARITAS-362380-CS-CDS Component 3 - Increase the / Recrutement d'un Consulta capacity to implement the IP Individual Consult Direct - Internation nt International pour l'évalua TF / A0924 Post 10,000.00 0.00 Canceled 2023-05-30 2023-05-30 2023-06-09 2023-06-04 2023-06-30 2023-08-04 2024-01-31 LC development activities a ant Selection al tion final et la rédaction du r nd consolidate feedback apport d'achèvement du pro jet ZR-CARITAS-362377-CS-CDS Component 3 - Increase the / Recrutement d'un Consulta capacity to implement the IP Individual Consult Under Implement nt National pour l'appui à l'év TF / A0924 Post Direct - National 10,000.00 0.00 2023-05-30 2023-05-30 2023-06-09 2023-06-04 2023-06-30 2023-06-25 2023-08-04 2024-01-31 LC development activities a ant Selection ation aluation finale et à la rédacti nd consolidate feedback on du rapport d'achèvement du projet ZR-CARITAS-253079-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocésaine d'IN participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 18,000.00 0.00 Canceled 2021-12-08 2020-09-08 2021-12-18 2022-02-21 2022-06-21 ONGO, territoire de KIRI, OS rest and land management WE et INONGO pour l'éducat processes related to REDD+ ion de base et l'alphabétisati on. composante 1b ZR-CARITAS-253068-CS-CDS / Renouvellement contrat av Component 1 - Reinforce the ec Caritas diocésaine TSHUM participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2022-01-20 2022-05-20 BE pour Education de Base et rest and land management Alphabétisation aux PA et co processes related to REDD+ mmunautés locales territoire de LUBEFU composante 1b ZR-CARITAS-365668-CS-CDS / CIDB: Identification des idée Component 2 - Support com s des microprojets communa TF / A0924 munity-based sustainable fo Post Direct Selection Direct - National 9,800.00 0.00 Signed 2023-06-06 2023-06-12 2023-06-16 2023-06-18 2023-08-20 2024-02-16 utaires et des opérateurs loc rest and land management aux d'appui aux communaut és à Bikoro-Kiri ZR-CARITAS-365674-NC-DIR / OSAPY: Appuyer l'élaboratio n des cartes des terroirs com Component 1 - Reinforce the munautaires et des plans d'a participation of the IPLC in fo Under Implement TF / A0924 Post Direct Selection Direct - National 150,000.00 0.00 2023-06-12 2023-06-25 2023-06-22 2023-08-26 2024-02-22 ménagement et de gestion si rest and land management ation mplifiée des concessions fore processes related to REDD+ stières des COLO et des aires de patrimoine ou aires de co nservation des PA et des COL O Page 8 PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, Desert Locust Response Project, P173702 Project Implementation agency: Ministry of Agriculture, Ethiopia Date of the Procurement Plan: April 6, 2012 Period covered by this Procurement Plan: April 2020 to March 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Directives of the Federal and Regional Governments of Ethiopia, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. For national open competitive procurement the following requirement apply: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts; e. contracts with an appropriate allocation of responsibilities, risks, and liabilities; f. publication of contract award information; g. rights for the Bank to review procurement documentation and activities; h. an effective complaints mechanism; and i. maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Secondhand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable For national open competitive procurement the following requirement apply: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts; e. contracts with an appropriate allocation of responsibilities, risks, and liabilities; f. publication of contract award information; g. rights for the Bank to review procurement documentation and activities; h. an effective complaints mechanism; and i. maintenance of records of the Procurement Process. cable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. Since the project is an emergency response project the provisions of Procurement in Situations of Urgent Need of Assistance shall apply. PROCUREMENT Eastern and Southern Africa : Emergency Locust Response Program PLAN General Information Country: Eastern and Southern Africa 2022-11-23 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173702 GPN Date: 2020-12-03 Project Name: Emergency Locust Response Program Loan / Credit No: IDA / 66480 Mandera County Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MANDERA COUNTY-3266 56-GO-RFQ / SUPPLY OF 1200 Livelihoods Protection and R Request for Quota Single Stage - One E 0 BALES HAY OF 15KG'S EAC IDA / 66480 Post Limited 80,500.00 0.00 Canceled 2022-12-07 2023-01-03 2023-05-03 ehabilitation tions nvelope H FOR EMERGENCY LIVESTO CK FEEDS FOR DROUGHT MIT IGATION. KE-MANDERA COUNTY-3621 66-GO-RFQ / Supply and Deli very of 1780 bags each 50kg Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66480 Post Limited 64,070.00 0.00 2023-05-19 2023-06-20 2023-10-18 of drought pellets (Range cu ehabilitation tions nvelope ementation bes) livestock feeds supplem ents for Mandera North Sub- county, Mandera county. KE-MANDERA COUNTY-3490 31-GO-RFQ / Supply and Deli very of 1700 bags of (50 kg's Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66480 Post Limited 64,666.00 0.00 2023-03-17 2023-04-14 2023-06-13 ) each drought pellets livesto ehabilitation tions nvelope ementation ck feeds supplement for dro ught mitigation Mandera cou nty. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 PROCUREMENT PLAN (Textual Part) Project information: Mozambique P172657 - Improving Learning and Empowering Girls Project Implementation agency: Ministry of Education Date of the Procurement Plan: June 24, 2020 Period covered by this Procurement Plan: June 2020 – June 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Decree 5/2016 of March 8, 2016, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works): None PROCUREMENT Mozambique : Improving Learning and Empowering Girls in Mozambique PLAN General Information Country: Mozambique 2020-06-24 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172657 GPN Date: 2023-06-09 Project Name: Improving Learning and Empowering Girls in Mozambique Loan / Credit No: / , IDA / V3610, IDA / D7930, TF / B5326 Ministry of Education and Human Development Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual National Proc 123/W/ILEGP/23 / Constructi urement Doc on of new Multimedia Studi Improving learning in primar Single Stage - One E Pending Imp 2024-02-1 IDA / D7930 Post Request for Bids Open - National ument - 1 En 0.00 2023-05-02 2023-05-08 2023-06-19 2023-07-18 2023-08-22 o, in Maputo province ( to be y education nvelope lementation 8 velope proce built by in IEDA plot) ss (Non Bank -SPD) 91/W/ILEGP/22 / Constructio Request for B n of 39 new ED centers in sc ids - Works ( hools, in all provinces (the in Improving learning in primar Single Stage - One E Pending Imp 2024-04-2 IDA / D7930 Prior Request for Bids Open - National without preq 0.00 2023-07-05 2023-07-10 2023-08-21 2023-09-20 2023-10-25 dication of the sites to be bui y education nvelope lementation 2 ualification) lt by IEDA to be provided to SPD DIEE) to be carried out by pr ovinces Request for B 133/W/ILEGP/23 / Constructi ids - Small W on of Support and learning C Improving learning in primar Single Stage - One E Pending Imp 2024-04-2 IDA / D7930 Prior Request for Bids Open - National orks SPD (1 e 0.00 2023-07-04 2023-07-10 2023-08-21 2023-09-20 2023-10-25 anters in Niassa, Cabo Delga y education nvelope lementation 2 nvelope proc do, Nampula, Zambezia and ess) Tete Province Request for B 144/W/ILEGP/23 / Constructi Increasing access and retent ids - Small W on of Support and learning C ion of girls in upper primary Single Stage - One E Pending Imp 2024-04-2 IDA / D7930 Prior Request for Bids Open - National orks SPD (1 e 0.00 2023-07-05 2023-07-10 2023-08-21 2023-09-20 2023-10-25 enters in Sofala, Manica, Inha and lower secondary educati nvelope lementation 2 nvelope proc mbane, Gaza and Maputo Pro on ess) vince Request for B 132/W/ILEGP/23 / Constructi ids - Small W on of 50 pre-primary centers Improving learning in primar Single Stage - One E Pending Imp 2024-04-2 IDA / D7930 Prior Request for Bids Open - National orks SPD (1 e 0.00 2023-07-06 2023-07-12 2023-08-23 2023-09-22 2023-10-27 in Niassa (20) and Cabo Delg y education nvelope lementation 4 nvelope proc ado (30) Province. ess) Request for B 134/W/ILEGP/23 / Constructi ids - Small W Improving learning in primar Single Stage - One E Pending Imp 2024-04-2 on of 50 pre-primary centers IDA / D7930 Prior Request for Bids Open - National orks SPD (1 e 0.00 2023-07-06 2023-07-12 2023-08-23 2023-09-22 2023-10-27 y education nvelope lementation 4 in Nampula (30) and Zambez nvelope proc ia (20) Provinces ess) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-MEDH-206235-GO-RFB / Increasing access and retent Open - Internationa Single Stage - One E Pending Impl Printing 6 million books of 1s / ion of girls in upper primary Prior Request for Bids 0.00 2020-11-25 2020-11-30 2021-01-11 2021-02-10 2021-03-17 2021-09-13 l nvelope ementation t, 2nd and 3rd grades. and lower secondary educati on MZ-MEDH-206915-GO-RFB / Increasing access and retent Printing and Distribution of th ion of girls in upper primary Single Stage - One E Pending Impl e new instrument of SICOLE / Post Request for Bids Open - National 0.00 2020-12-10 2020-12-15 2021-01-26 2021-02-25 2021-04-01 2021-09-28 and lower secondary educati nvelope ementation and printing 5.000 copies of t on he 3rd grade student's book, in Braille. 05/G/ILEGP/21 / Print 3,000, 000 copies of 1st class books Improving learning in primar Open - Internationa Single Stage - One E , 3,000,000 copies of 2nd Cla IDA / D7930 Prior Request for Bids 7,591,283.95 Signed 2021-08-10 2021-08-10 2021-08-15 2021-08-12 2021-09-29 2021-09-28 2021-10-19 2022-01-21 2021-11-17 2022-01-06 2022-02-28 y education l nvelope ss books, x copies of 5th clas s books and 6th class books f or the academic year 2022. 23/G/ILEGP/21 / IT Equipmen t's (Acquisition of computers, Project management, monit Single Stage - One E Pending Impl laptops, scanners and printe IDA / D7930 Post Request for Bids Open - National 0.00 2021-10-04 2021-10-09 2021-11-08 2021-11-23 2021-12-07 2022-06-05 oring and evaluation nvelope ementation rs for the project team includ ing project provincial coordin ators). 27/G/ILEGP/21 / Printing and Strengthening governance t Distribution of Modules of the o improve efficiency and mo Open - Internationa Single Stage - One E Under Imple TF / B5326 Prior Request for Bids 0.00 2021-10-15 2022-07-16 2021-10-20 2022-07-19 2021-12-01 2022-09-16 2021-12-31 2023-01-04 2022-02-04 2022-08-03 Secondary Distance Learning nitoring of education outcom l nvelope mentation Program of the first cycle es progress 33/NCS/ILEGP/22 / Storage o Improving learning in primar Request for Quota Single Stage - One E f Textbooks and Teaching Ma IDA / D7930 Prior Limited 469,794.06 Signed 2022-03-08 2022-07-29 2022-05-03 2022-08-13 2022-10-30 y education tions nvelope terials for year 2022 -Zona N orte 34/G/ILEGP/22 / Printing of t he books for 1st , 2nd , 3rd ( Improving learning in primar Open - Internationa Single Stage - One E Under Imple IDA / D7930 Prior Request for Bids 0.00 2022-03-14 2022-04-26 2022-03-19 2022-05-03 2022-05-03 2022-06-17 2022-06-02 2022-07-07 2023-01-03 mathematics) 5th and 6th g y education l nvelope mentation rade for the academic year 2 023. 51/G/ILEGP/22 / Printing 4,9 Improving learning in primar Open - Internationa Single Stage - One E Under Imple IDA / D7930 Prior Request for Bids 0.00 2022-06-15 2022-08-06 2022-06-20 2022-08-17 2022-08-01 2022-09-22 2022-08-31 2022-12-19 2022-10-05 2023-04-03 00,000 Units Fiches y education l nvelope mentation Increasing access and retent 54/G/ILEGP/22 / Forniture for Single Stage - One E Under Imple TF / B5326 ion of girls in upper primary Post Request for Bids Open - National 0.00 2022-07-13 2022-06-02 2022-07-18 2022-08-29 2022-07-15 2022-09-28 2022-11-02 2023-05-01 DL Center nvelope mentation and lower secondary educati on Increasing access and retent 57/G/ILEGP/22 / Equipment f Request for Quota Single Stage - One E Under Imple IDA / D7930 ion of girls in upper primary Post Open - National 0.00 2022-07-18 2022-09-12 2023-03-11 or Studio tions nvelope mentation and lower secondary educati on 56/G/ILEGP/22 / Print copies of the activities manual for c Increasing access and retent ommunity little school, the or ion of girls in upper primary Single Stage - One E Pending Impl IDA / D7930 Post Request for Bids Open - National 0.00 2022-07-06 2022-07-11 2022-08-22 2022-09-21 2022-10-26 2023-04-24 ientation manual for facilitat and lower secondary educati nvelope ementation ors and printing and layout b on rochures and exercise books for 1st cycle Increasing access and retent 58/G/ILEGP/22 / IT Equipmen Open - Internationa Single Stage - One E Under Revie IDA / D7930 ion of girls in upper primary Prior Request for Bids 0.00 2022-07-28 2022-08-02 2022-09-13 2022-10-13 2022-11-17 2023-05-16 t for IEDA l nvelope w and lower secondary educati on Page 1 62/G/ILEGP/22 / Supply of 15 Strengthening governance t 0 Motobyks including safety o improve efficiency and mo Single Stage - One E Pending Impl IDA / D7930 Post Request for Bids Open - National 0.00 2022-07-15 2022-07-20 2022-08-31 2022-09-30 2022-11-04 2023-05-03 equipment ( gloves and helm nitoring of education outcom nvelope ementation ets) for Coordinators of the L es progress earn Project 61/G/ILEGP/22 / Supply of sp ecific materials for students Increasing access and retent with SEN (10 Braille machine ion of girls in upper primary Single Stage - One E Pending Impl IDA / D7930 Post Request for Bids Open - National 0.00 2022-07-28 2022-08-02 2022-09-13 2022-10-13 2022-11-17 2023-01-16 s, 10 Braille forms and paper, and lower secondary educati nvelope ementation 5050 staves, 50 canes, 50 pu on nches and d 200 Dactilogy m aps in LS Strengthening governance t 70/G/ILEGP/22 / Supply of 75 Open - Internationa Single Stage - One E Under Imple IDA / D7930 o improve efficiency and mo Prior Request for Bids 0.00 2022-07-22 2022-07-27 2022-09-07 2022-10-07 2022-11-11 2023-05-10 Vehicles for the MINEDH l nvelope mentation nitoring of education outcom es progress 71/G/ILEGP/22 / Supply of p Strengthening governance t ersonal protective equipment o improve efficiency and mo Request for Quota Single Stage - One E Pending Impl (EP - Boots, Helmets, T-shirts IDA / D7930 Post Open - National 0.00 2022-07-30 2022-09-24 2022-10-24 nitoring of education outcom tions nvelope ementation , Shirts, Gloves, Glasses, Vest es progress s) for the 30 technicians of th e DIEE 77/G/ILEGP/22 / Illustration, l ayout, Printing and Distributi Increasing access and retent on of 30,000 copies of Broch ion of girls in upper primary Single Stage - One E Pending Impl IDA / D7930 Post Request for Bids Open - National 0.00 2022-08-01 2022-08-06 2022-09-05 2022-09-20 2022-10-25 2023-01-23 ures and exercise books for and lower secondary educati nvelope ementation Reading and writing Exercise on s for the 1st cycle (1st, 2nd a nd 3rd grades) 96/G/ILEGP/22 / Produce and Strengthening governance t Request for Quota Single Stage - One E Pending Impl print data collection maps for IDA / D7930 o improve efficiency and mo Post Open - National 0.00 2022-10-03 2022-11-28 2023-05-27 tions nvelope ementation the 2021 use and 2022 surve nitoring of education outcom y es progress 99/G/ILEGP/22 / Acquisition Increasing access and retent of 3 million calligraphy noteb ion of girls in upper primary Open - Internationa Single Stage - One E Pending Impl IDA / D7930 Prior Request for Bids 0.00 2022-09-28 2022-10-03 2022-11-14 2022-12-14 2023-01-18 2023-07-17 ooks and syllabic charts (1st, and lower secondary educati l nvelope ementation 2nd and 3rd grade) on 101/G/ILEGP/22 / Manuals of Increasing access and retent Single Stage - One E Pending Impl the continuous training strat IDA / D7930 ion of girls in upper primary Post Request for Bids Open - National 0.00 2022-09-27 2022-10-03 2022-11-14 2022-12-14 2023-01-18 2023-07-17 nvelope ementation egy for the Provinces of Nias and lower secondary educati sa and Manica on 95/G/ILEGP/22 / Printing of 2 500 copies of 1st cycle Secon Improving learning in primar Single Stage - One E Pending Impl IDA / D7930 Post Request for Bids Open - National 0.00 2022-10-27 2022-11-01 2022-12-13 2023-01-12 2023-02-16 2023-08-15 dary School Program, and 25 y education nvelope ementation 00 copies of 2nd cycle Secon dary School Program 100/G/ILEGP/22 / One (1) bra Increasing access and retent Request for Quota Single Stage - One E Under Imple ille printer to ensure the tran IDA / D7930 ion of girls in upper primary Post Limited 0.00 2022-10-17 2023-03-30 2022-12-12 2023-06-10 tions nvelope mentation sformation of NEE materials and lower secondary educati on 102/G/ILEGP/22 / Acquire 12 Increasing access and retent Request for Quota Single Stage - One E Under Imple 0 kits of History and Geograp IDA / D7930 ion of girls in upper primary Post Limited 0.00 2022-11-28 2022-11-18 2023-01-23 2023-07-22 tions nvelope mentation hy Maps for 120 schools and lower secondary educati on 105/DC/ILEGP/2022 / Acquisi Increasing access and retent tion of Off the Shelf Stock -Su ion of girls in upper primary Direct - Internation Under Imple IDA / D7930 Post Direct Selection 0.00 2022-11-16 2022-10-06 2022-11-21 2022-10-06 2022-12-26 2023-06-24 pply of Educational Material and lower secondary educati al mentation Textbooks for Grades 3 For S on chool Year 2023 105/G/ILEGP/22 / Acquire 50 Increasing access and retent Single Stage - One E Pending Impl 00 staves, Punches and 200 IDA / D7930 ion of girls in upper primary Post Request for Bids Open - National 0.00 2022-11-16 2022-11-21 2023-01-02 2023-02-01 2023-03-08 2023-09-04 nvelope ementation Dactilogy maps in LS and lower secondary educati on 108/G/ILEGP/22 / Acquire 33 Increasing access and retent Single Stage - One E Pending Impl solar panels to equip 60 DL C IDA / D7930 ion of girls in upper primary Post Request for Bids Open - National 0.00 2023-02-01 2023-02-06 2023-03-20 2023-04-19 2023-05-24 2023-11-20 nvelope ementation enters (CAA) and lower secondary educati on 107/G/ILEGP/22 / Printing of Strengthening governance t Single Stage - One E Pending Impl 2500 copies of 1st cycle Seco IDA / D7930 o improve efficiency and mo Post Request for Bids Open - National 0.00 2022-12-21 2022-12-26 2023-02-06 2023-03-08 2023-04-12 2023-10-09 nvelope ementation ndary School Program nitoring of education outcom es progress 112/G/ILEGP/22 / Reproduce and distribute information, e Increasing access and retent ducation and communication ion of girls in upper primary Single Stage - One E Pending Impl IDA / D7930 Post Request for Bids Open - National 0.00 2022-12-21 2022-12-26 2023-02-06 2023-03-08 2023-04-12 2023-10-09 materials on SRH and HIV & and lower secondary educati nvelope ementation AIDS (posters, leaflets and bo on oklets) in the 335 Programm e schools in the 7 provinces 104/G/ILEGP/22 / Equipment Strengthening governance t for support rooms for inclusiv o improve efficiency and mo Single Stage - One E Pending Impl e education in 10 secondary IDA / D7930 Post Request for Bids Open - National 0.00 2022-12-15 2022-12-20 2023-01-31 2023-03-02 2023-04-06 2023-10-03 nitoring of education outcom nvelope ementation schools to attend to students es progress with disabilities and SEN (4 n ew rooms) 84/G/ILEGP/22 / Print 2000 c Strengthening governance t opies of the activities manual o improve efficiency and mo Request for Quota Single Stage - One E Pending Impl for community school's and 2 IDA / D7930 Post Limited 0.00 2023-03-06 2023-05-01 2023-10-28 nitoring of education outcom tions nvelope ementation 000 of the orientation manua es progress l for facilitators/educators Increasing access and retent 122/G/ILEGP/23 / Forniture d Open - Internationa Single Stage - One E Pending Impl IDA / D7930 ion of girls in upper primary Prior Request for Bids 0.00 2023-05-24 2023-05-29 2023-07-10 2023-08-09 2023-09-13 2024-03-11 or 140 DL Center l nvelope ementation and lower secondary educati on 126/G/ILEGP/23 / Design and Increasing access and retent Single Stage - One E Pending Impl printing of the instruments of IDA / D7930 ion of girls in upper primary Post Request for Bids Open - National 0.00 2023-04-26 2023-05-01 2023-06-12 2023-07-12 2023-08-16 2024-02-12 nvelope ementation the National Evaluation of 20 and lower secondary educati 22 on 34/G/ILEGP/22-R / Printing of the books for 1st , 2nd , 3rd ( Improving learning in primar Open - Internationa Single Stage - One E Under Imple IDA / D7930 Prior Request for Bids 0.00 2023-03-30 2023-06-16 2023-04-04 2023-05-16 2022-06-17 2023-06-15 2023-06-27 2023-07-20 2024-01-16 mathematics) 5th and 6th gr y education l nvelope mentation ade for the academic year 20 23. Strengthening governance t 131/G/ILEGP/23 / Supply of 1 Open - Internationa Single Stage - One E Under Imple IDA / D7930 o improve efficiency and mo Prior Request for Bids 0.00 2023-06-07 2023-06-12 2023-07-24 2023-08-23 2023-09-27 2024-03-25 61 Vehicles for the MINEDH l nvelope mentation nitoring of education outcom es progress 128/G/ILEGP/23 / Acquire an d distribute 5000 hygiene an Improving learning in primar Single Stage - One E Pending Impl d digenite kits for girls in boa IDA / D7930 Post Request for Bids Open - National 0.00 2023-06-28 2023-07-04 2023-08-15 2023-09-14 2023-10-19 2024-04-16 y education nvelope ementation rding schools and homes in a ll the provinces of the countr y Page 2 140/G/ILEGP/23 / Framework Improving learning in primar Open - Internationa Single Stage - One E Under Imple Agreement – Grade 1,2,3 and IDA / D7930 Prior Request for Bids 0.00 2023-06-14 2023-06-19 2023-07-31 2023-08-30 2023-10-04 2024-04-01 y education l nvelope mentation 6 books Quadro 135/G/ILEGP/23 / IT Equipam Strengthening governance t Open - Internationa Single Stage - One E Pending Impl ent for DL Centers and MINE IDA / D7930 o improve efficiency and mo Prior Request for Bids 0.00 2023-06-30 2023-07-05 2023-08-16 2023-09-15 2023-10-20 2024-04-17 l nvelope ementation DH nitoring of education outcom es progress 149/G/ILEGP/23 / Motorcycle Increasing access and retent Single Stage - One E Pending Impl for ZIP Coordinators, teacher IDA / D7930 ion of girls in upper primary Prior Request for Bids Open - National 0.00 2023-07-05 2023-07-10 2023-08-21 2023-09-20 2023-10-25 2024-04-22 nvelope ementation s and mentors and lower secondary educati on 145/G/ILEGP/23 / Print 2000 copies of activity manuals for Improving learning in primar Request for Quota Single Stage - One E Pending Impl the community school and 2 IDA / D7930 Post Limited 0.00 2023-07-10 2023-09-04 2024-03-02 y education tions nvelope ementation 000 copies of guidelines for f acilitators/educators/animato rs NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 27/NCS/ILEGP/21 / Customs Strengthening governance t Single Stage - One E Clearance of Monolingual, Bili IDA / D7930 o improve efficiency and mo Post Request for Bids Open - National 968,918.72 Signed 2021-11-25 2021-12-10 2021-11-30 2021-12-14 2021-12-30 2022-01-11 2022-01-17 2022-02-18 2022-02-07 2022-03-12 2022-08-06 nvelope ngual and Braille Textbooks nitoring of education outcom 2021 and 2022. es progress 28/NCS/ILEGP/21 / Storage o Strengthening governance t Single Stage - One E f Textbooks and Teaching Ma IDA / D7930 o improve efficiency and mo Post Request for Bids Open - National 281,239.97 Signed 2021-12-12 2021-12-21 2021-12-17 2022-01-08 2022-01-28 2022-01-07 2022-02-27 2022-01-24 2022-04-03 2022-02-16 2022-09-30 nvelope terials for year 2022. nitoring of education outcom es progress 29/NCS/ILEGP/21 / Distributi Strengthening governance t Single Stage - One E Under Imple on of Textbooks and Teachin IDA / D7930 o improve efficiency and mo Post Request for Bids Open - National 0.00 2021-12-27 2022-01-06 2022-01-01 2022-01-06 2022-02-12 2022-01-27 2022-03-14 2022-03-28 2022-04-18 2022-10-15 nvelope mentation g Materials for year 2022. nitoring of education outcom es progress 60/NCS/ILEGP/22 / Customs Increasing access and retent Single Stage - One E Clearance of Monolingual, Bili IDA / D7930 ion of girls in upper primary Post Request for Bids Open - National 0.00 Signed 2022-07-12 2022-08-23 2022-07-17 2022-08-28 2022-09-27 2022-09-27 2022-10-14 2022-11-01 2023-04-30 nvelope ngual and Braille Textbooks and lower secondary educati 2023. on 74/NCS/ILEGP/22 / Provision Increasing access and retent Request for Quota Single Stage - One E Pending Impl of production services and in IDA / D7930 ion of girls in upper primary Post Open - National 0.00 2022-08-03 2022-09-28 2022-12-27 tions nvelope ementation sertion of advertising spots f and lower secondary educati or IEDA on 92/NCS/ILEGP/22 / Distributi Increasing access and retent Single Stage - One E Under Imple on of Textbooks and Teachin IDA / D7930 ion of girls in upper primary Post Request for Bids Open - National 0.00 2022-09-28 2022-10-31 2022-10-03 2022-11-04 2022-11-14 2023-01-19 2022-12-14 2023-01-17 2023-01-18 2023-07-17 nvelope mentation g Materials for year 2023. and lower secondary educati on 94/NCS/ILEGP/22 / Storage o Improving learning in primar Single Stage - One E Under Imple f Textbooks and Teaching Ma IDA / D7930 Post Request for Bids Open - National 0.00 2022-09-28 2022-08-26 2022-10-03 2022-11-14 2022-10-14 2022-12-14 2022-11-08 2023-01-18 2023-07-17 y education nvelope mentation terials for year 2023. 76/G/ILEGP/22 / Design, Prin Increasing access and retent ting, transportation and distri ion of girls in upper primary Single Stage - One E IDA / D7930 Post Request for Bids Open - National 0.00 Canceled 2022-07-29 2022-08-03 2022-09-14 2022-10-14 2022-11-18 2023-04-17 bution of the Instruments for and lower secondary educati nvelope the SEACMEQ V Main Study on 98/NCS/ILEGP/22 / Reproduc Increasing access and retent e copies of brochures and co ion of girls in upper primary Request for Quota Single Stage - One E Pending Impl pies of the Guide for the impl IDA / D7930 Post Limited 0.00 2022-10-24 2022-12-19 2023-06-17 and lower secondary educati tions nvelope ementation ementation of the Multi-Sect on oral Mechanism on Denuncia tion 76/NCS/ILEGP/22 / Transport Increasing access and retent Request for Quota Single Stage - One E Pending Impl ation and distribution of the I IDA / D7930 ion of girls in upper primary Post Limited 0.00 2022-10-24 2022-12-19 2023-06-17 tions nvelope ementation nstruments for the SEACMEQ and lower secondary educati V Main Study on 78/NCS/ILEGP/22 / Design, P Increasing access and retent Request for Quota Single Stage - One E Under Imple rinting of the Instruments for IDA / D7930 ion of girls in upper primary Post Limited 0.00 2022-10-17 2022-10-13 2022-12-12 2023-06-10 tions nvelope mentation the SEACMEQ V Main Study and lower secondary educati on 106/NCS/ILEGP/22 / Design, Increasing access and retent printing, transport and distrib ion of girls in upper primary Request for Quota Single Stage - One E Pending Impl IDA / D7930 Post Limited 0.00 2022-11-28 2023-01-23 2023-07-22 ution of the instruments of th and lower secondary educati tions nvelope ementation e National Evaluation of 2022 on 114/NCS/ILEGP/22 / Installati Increasing access and retent Single Stage - One E Pending Impl on of technological equipmen IDA / D7930 ion of girls in upper primary Post Request for Bids Open - National 0.00 2022-12-27 2023-01-03 2023-02-14 2023-03-16 2023-04-20 2023-10-17 nvelope ementation t in the CAAs and lower secondary educati on 113/NCS/ILEGP/22 / Customs Strengthening governance t Clearance of 12,986 Module o improve efficiency and mo Single Stage - One E Pending Impl IDA / D7930 Post Request for Bids Open - National 0.00 2022-12-14 2022-12-19 2023-01-30 2023-03-01 2023-04-05 2023-10-02 Kits of the Secondary Distanc nitoring of education outcom nvelope ementation e Learning Program (PESD) es progress 111/G/NCS/ILEGP/22 / Labor Increasing access and retent Request for Quota Single Stage - One E Pending Impl atory analysis of the 1st to 7t IDA / D7930 ion of girls in upper primary Post Limited 0.00 2023-01-03 2023-02-27 2023-08-26 tions nvelope ementation h grade textbooks. and lower secondary educati on 123/NCS/ILEGP/23 / Connecti Increasing access and retent Single Stage - One E Under Imple vity/internet services to supp IDA / D7930 ion of girls in upper primary Post Request for Bids Open - National 0.00 2023-04-26 2023-04-13 2023-05-01 2023-06-12 2023-07-12 2023-08-16 2024-02-12 nvelope mentation ort 200 Learning Center (CAA and lower secondary educati ) on 125/NCS/ILEGP/23 / Transpor Increasing access and retent Single Stage - One E Under Imple t and distribution of the instr IDA / D7930 ion of girls in upper primary Post Request for Bids Open - National 0.00 2023-04-19 2023-04-05 2023-04-24 2023-06-08 2023-06-05 2023-07-05 2023-08-09 2024-02-05 nvelope mentation uments of the National Evalu and lower secondary educati ation of 2022 on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 22/CONS/ILEGP/21 / Hire a c onsultant for data collection, Improving learning in primar Consultant Qualifi Pending Impleme TF / B5326 Post Open - National 0.00 2021-09-20 2021-10-11 2021-11-15 2021-11-30 2021-12-15 2022-06-13 date entry and processing for y education cation Selection ntation the National Assessment pilo t study. Page 3 Strengthening governance t 25/CONS/ILEGP/21 / Indepen Quality And Cost- Under Implement TF / B5326 o improve efficiency and mo Prior Open - National 0.00 2021-09-17 2022-04-13 2021-10-08 2022-06-03 2021-11-21 2022-09-22 2021-12-19 2022-11-04 2021-12-27 2023-01-03 2022-01-31 2023-03-17 2022-03-07 2023-03-07 dent Verification Agent Based Selection ation nitoring of education outcom es progress Strengthening governance t 24/CONS/ILEGP/2021 / Hiring Least Cost Selecti Open - Internationa Under Implement TF / B5326 o improve efficiency and mo Post 0.00 2021-09-29 2021-12-14 2021-10-20 2022-01-05 2021-12-03 2021-12-31 2022-01-30 2022-03-06 2022-04-10 2022-10-07 of Financial Audit Services on l ation nitoring of education outcom es progress 32/CONS/ILEGP/21 / Consult Strengthening governance t ant Services to Assess Vulner o improve efficiency and mo Consultant Qualifi Under Implement ability and Prepare Executive IDA / D7930 Post Open - National 0.00 2021-12-28 2022-03-10 2022-01-18 2022-02-17 2022-02-15 2022-06-09 2022-03-17 2022-10-24 2022-04-21 2022-10-18 nitoring of education outcom cation Selection ation Projects for the Re-qualificati es progress on of Primary Schools. Zona Norte 30/CONS/ILEGP/21 / Consult Strengthening governance t ant Services to Assess Vulner o improve efficiency and mo Quality And Cost- Under Implement ability and Prepare Executive IDA / D7930 Post Open - National 0.00 2021-12-20 2022-03-10 2022-01-10 2022-02-17 2022-02-23 2022-05-17 2022-03-23 2022-07-12 2022-04-22 2022-08-04 2022-05-27 2022-09-09 2022-07-01 2022-12-30 nitoring of education outcom Based Selection ation Projects for the Requalificatio es progress n of Primary Schools. Zona C entro 31/CONS/ILEGP/21 / Consult Strengthening governance t ant Services to Assess Vulner o improve efficiency and mo Quality And Cost- Under Implement ability and Prepare Executive IDA / D7930 Post Open - National 0.00 2021-12-28 2022-03-10 2022-01-18 2022-02-17 2022-03-03 2022-06-13 2022-03-31 2022-07-12 2022-04-30 2022-06-04 2022-07-09 2023-01-08 nitoring of education outcom Based Selection ation Projects for the Re-qualificati es progress on of Primary Schools. Zona Sul 36/CONS/ILEGP/22 / Consulti Increasing access and retent Quality And Cost- Open - Internationa Under Implement ng service for editorial elabor IDA / D7930 ion of girls in upper primary Prior 0.00 2022-05-02 2022-05-24 2022-05-23 2022-05-26 2022-07-06 2022-11-04 2022-08-03 2022-09-02 2022-10-07 2022-11-11 2023-04-10 Based Selection l ation ation books of grade 7,8 and and lower secondary educati 9 ( Português) on 37/CONS/ILEGP/22 / Consulti Increasing access and retent Quality And Cost- Open - Internationa Under Implement ng service for editorial elabor IDA / D7930 ion of girls in upper primary Post 0.00 2022-05-02 2022-05-23 2022-05-23 2022-05-30 2022-07-06 2022-08-03 2022-09-02 2022-10-07 2022-11-11 2023-04-10 Based Selection l ation ation books of grade 7,8 and and lower secondary educati 9 (Inglês), on 38/CONS/ILEGP/22 / Consulti Increasing access and retent Quality And Cost- Open - Internationa Under Implement ng service for editorial elabor IDA / D7930 ion of girls in upper primary Post 0.00 2022-05-04 2022-05-24 2022-05-25 2022-05-30 2022-07-08 2022-08-05 2022-09-04 2022-10-09 2022-11-13 2023-04-20 Based Selection l ation ation books of grade 7,8 and and lower secondary educati 9 (Francês), on 40/CONS/ILEGP/22 / Consulti Increasing access and retent Quality And Cost- Under Implement ng service for editorial elabor IDA / D7930 ion of girls in upper primary Post Open - National 0.00 2022-05-03 2022-05-24 2022-05-24 2022-05-30 2022-07-07 2022-08-04 2022-09-03 2022-10-08 2022-11-12 2023-04-11 Based Selection ation ation books of grade 7,8 and and lower secondary educati 9 (História), on 41/CONS/ILEGP/22 / Consulti Increasing access and retent Quality And Cost- Under Implement ng service for editorial elabor IDA / D7930 ion of girls in upper primary Post Open - National 0.00 2022-05-04 2022-05-24 2022-05-25 2022-05-30 2022-07-08 2022-08-05 2022-09-04 2022-10-09 2022-11-13 2023-04-12 Based Selection ation ation books of grade 7,8 and and lower secondary educati 9 (Geografia) on 42/CONS/ILEGP/22 / Consulti Increasing access and retent Quality And Cost- Open - Internationa Under Implement ng service for editorial elabor IDA / D7930 ion of girls in upper primary Prior 0.00 2022-05-04 2022-05-23 2022-05-25 2022-06-08 2022-07-08 2022-10-19 2022-08-05 2022-09-04 2022-10-09 2022-11-13 2023-04-12 Based Selection l ation ation books of grade 7,8 and and lower secondary educati 9 (Matemática) on 43/CONS/ILEGP/22 / Consulti Increasing access and retent Quality And Cost- Under Implement ng service for editorial elabor IDA / D7930 ion of girls in upper primary Post Open - National 0.00 2022-05-05 2022-05-24 2022-05-26 2022-05-30 2022-07-09 2022-08-06 2022-09-05 2022-10-10 2022-11-14 2023-04-13 Based Selection ation ation books of grade 7,8 and and lower secondary educati 9 (Quimica) on 44/CONS/ILEGP/22 / Consulti Increasing access and retent Quality And Cost- Under Implement ng service for editorial elabor IDA / D7930 ion of girls in upper primary Post Open - National 0.00 2022-05-05 2022-05-24 2022-05-26 2022-05-30 2022-07-09 2022-08-06 2022-09-05 2022-10-10 2022-11-14 2023-04-13 Based Selection ation ation books of grade 7,8 and and lower secondary educati 9 (Física) on 45/CONS/ILEGP/22 / Consulti Increasing access and retent ng service for editorial elabor ion of girls in upper primary Quality And Cost- Under Implement IDA / D7930 Post Open - National 0.00 2022-05-05 2022-05-24 2022-05-26 2022-05-30 2022-07-09 2022-08-06 2022-09-05 2022-10-10 2022-11-14 2023-04-13 ation books of grade 7,8 and and lower secondary educati Based Selection ation 9 (Educação Visual) on 46/CONS/ILEGP/22 / Consulti Increasing access and retent Quality And Cost- Under Implement ng service for editorial elabor IDA / D7930 ion of girls in upper primary Post Open - National 0.00 2022-05-05 2022-05-24 2022-05-26 2022-05-30 2022-07-09 2022-08-06 2022-09-05 2022-10-10 2022-11-14 2023-04-13 Based Selection ation ation books of grade 7,8 and and lower secondary educati 9 (TIC) on 47/CS/ILEGP/22 / Consulting Strengthening governance t service for editorial elaborati o improve efficiency and mo Quality And Cost- Open - Internationa IDA / D7930 Prior 0.00 Canceled 2022-03-16 2022-04-06 2022-05-20 2022-06-17 2022-07-17 2022-08-19 2022-09-23 2023-09-23 on books of grade 7,8 and 9 nitoring of education outcom Based Selection l (first cycle), Secondary schoo es progress l-INDE 39/CONS/ILEGP/22 / Consulti Increasing access and retent Quality And Cost- Open - Internationa Under Implement ng service for editorial elabor IDA / D7930 ion of girls in upper primary Post 0.00 2022-05-03 2022-05-24 2022-05-24 2022-05-30 2022-07-07 2022-08-04 2022-09-03 2022-10-08 2022-11-12 2023-04-11 Based Selection l ation ation books of grade 7,8 and and lower secondary educati 9 (Biologia) on 59/CONS/ILEGP/22 / Procure Project management, monit Least Cost Selecti Under Implement IDA / D7930 Prior Open - National 0.00 2022-07-15 2022-08-11 2022-08-05 2022-08-16 2022-09-18 2022-10-19 2022-10-16 2022-12-09 2022-11-15 2023-01-03 2022-12-20 2023-04-13 2023-01-24 2023-07-23 ment Audit for years 2021 to oring and evaluation on ation 2023 75/CONS/ILEGP/22 / Technic Increasing access and retent al Assistance for the collectio ion of girls in upper primary Consultant Qualifi Under Implement n, typing, and processing of IDA / D7930 Post Open - National 0.00 2022-07-29 2022-08-09 2022-08-19 2022-09-06 2022-10-02 2022-11-04 2022-11-01 2022-12-06 2023-06-04 and lower secondary educati cation Selection ation data, and the elaboration of t on he report for the SEACMEQ V Main Study 72/CONS/ILEGP/22 / Consulti ng services for conduct a ba Increasing access and retent seline study of girls' and boy ion of girls in upper primary Consultant Qualifi Under Implement s' knowledge and information IDA / D7930 Post Open - National 0.00 2022-07-28 2022-08-23 2022-08-18 2022-10-01 2023-05-11 2022-10-31 2022-12-05 2023-06-03 and lower secondary educati cation Selection ation on SRH in selected schools, i on ncluding an analysis of the ri sk factors associated with GB V in schools 93/NCS/ILEGP/22 / Collection Increasing access and retent , data processing and prepar ion of girls in upper primary Quality And Cost- Open - Internationa ation of the report of the nati IDA / D7930 Prior 0.00 Under Review 2022-08-31 2022-09-24 2022-09-21 2022-10-04 2022-11-04 2023-06-15 2022-12-02 2023-05-26 2023-01-01 2023-02-05 2023-03-12 2024-03-11 and lower secondary educati Based Selection l onal approval of the monolin on gual and bilingual modalities in the revised curriculum 110/CS/ILEGP/22 / Consultan Increasing access and retent cy Service for harmony and r ion of girls in upper primary Consultant Qualifi IDA / D7930 Post Open - National 0.00 Canceled 2023-01-18 2023-03-23 2023-02-08 2023-03-24 2023-04-24 2023-05-29 2023-11-25 evise the program for sexual and lower secondary educati cation Selection health and reproductive and on HIV/SIDA 136/CS/ILEGP/23 / Supervisi Improving learning in primar Quality And Cost- Pending Impleme on of work of 30 pre-primary IDA / D7930 Prior Open - National 0.00 2023-09-06 2023-09-27 2023-11-10 2023-12-08 2024-01-08 2024-02-12 2024-03-18 2025-03-18 y education Based Selection ntation canters in Cabo Delgado Prov ince 137/CS/ILEGP/23 / Supervisi Improving learning in primar Quality And Cost- Pending Impleme on of work of 20 pre-primary IDA / D7930 Prior Open - National 0.00 2023-09-13 2023-10-04 2023-11-17 2023-12-15 2024-01-15 2024-02-19 2024-03-25 2025-03-25 y education Based Selection ntation canters in Niassa Province Page 4 138/CS/ILEGP/23 / Supervisi Improving learning in primar Quality And Cost- Pending Impleme on of work of 30 pre-primary IDA / D7930 Prior Open - National 0.00 2023-09-13 2023-10-04 2023-11-17 2023-12-15 2024-01-15 2024-02-19 2024-03-25 2025-03-25 y education Based Selection ntation canters in Nampula Province 139/CS/ILEGP/23 / Supervisi Improving learning in primar Quality And Cost- Pending Impleme on of work of 20 pre-primary IDA / D7930 Prior Open - National 0.00 2023-09-13 2023-10-04 2023-11-17 2023-12-15 2024-01-15 2024-02-19 2024-03-25 2025-03-25 y education Based Selection ntation canters in Zambezia Province 147-A/CS/ILEGP/23 / Service Increasing access and retent Provider for the implementati ion of girls in upper primary Quality And Cost- Open - Internationa Pending Impleme IDA / D7930 Prior 0.00 2023-06-29 2023-07-20 2023-09-04 2023-10-02 2023-11-01 2023-12-06 2024-01-10 2025-01-09 on of the Multisectoral Mecha and lower secondary educati Based Selection l ntation nism for the Prevention, Den on ouncement, Referral. 147/CS/ILEGP/23 / Service Pr Increasing access and retent ovider for the implementatio ion of girls in upper primary Quality And Cost- IDA / D7930 Post Open - National 0.00 Canceled 2023-06-06 2023-06-27 2023-08-10 2023-09-07 2023-10-07 2023-11-11 2023-12-16 2024-12-15 n of the Multisectoral Mechan and lower secondary educati Based Selection ism for the Prevention, Deno on uncement, Referral. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-MEDH-181667-CS-INDV / Improving learning in primar Individual Consult Under Implement Development of environment / Post Limited 0.00 2020-06-24 2020-06-26 2020-06-29 2020-07-06 2020-07-20 2020-11-02 2020-08-24 2021-02-20 y education ant Selection ation al and social instruments. MZ-MEDH-206281-CS-INDV / Increasing access and retent Consultancy Services for the ion of girls in upper primary Individual Consult Pending Impleme / Post Limited 0.00 2020-11-30 2020-12-05 2020-12-26 2021-01-30 2021-07-29 Preparation of Environmental and lower secondary educati ant Selection ntation and Social studies on MZ-MEDH-206291-CS-INDV / Increasing access and retent Individual Consult Under Implement Gender Specialist and GBV M / ion of girls in upper primary Post Limited 0.00 2020-12-20 2021-11-30 2020-12-25 2021-01-15 2021-02-19 2021-08-18 ant Selection ation atters. and lower secondary educati on Increasing access and retent MZ-MEDH-206286-CS-CDS / / ion of girls in upper primary Prior Direct Selection Direct 0.00 Canceled 2020-12-10 2020-12-20 2021-02-23 2021-08-22 Procuremet Specialist. and lower secondary educati on MZ-MEDH-206246-CS-INDV / Increasing access and retent Individual Consult Pending Impleme Environmental Safeguards Sp / ion of girls in upper primary Post Limited 0.00 2020-12-15 2020-12-20 2021-01-10 2021-02-14 2021-08-13 ant Selection ntation ecialist for DIEE and lower secondary educati on MZ-MEDH-206272-CS-INDV / Increasing access and retent Individual Consult Pending Impleme Project Implementation Manu / ion of girls in upper primary Post Limited 0.00 2020-12-06 2020-12-11 2021-01-01 2021-02-05 2021-08-04 ant Selection ntation al (PIM). and lower secondary educati on MZ-MEDH-206288-CS-CDS / Increasing access and retent Financial management Speci / ion of girls in upper primary Post Direct Selection Direct 0.00 Canceled 2020-12-20 2020-12-30 2021-03-05 2021-09-01 alist and lower secondary educati on MZ-MEDH-206290-CS-CDS / Increasing access and retent Procurement Specialist for Bo / ion of girls in upper primary Prior Direct Selection Direct 0.00 Canceled 2020-12-30 2021-01-09 2021-03-15 2021-09-11 oks and Teaching Materials. and lower secondary educati on MZ-MEDH-206258-CS-CQS / Increasing access and retent Damage and vulnerability as ion of girls in upper primary Individual Consult Pending Impleme sessment of school infrastruc / Post Open 0.00 2020-12-15 2021-02-02 2021-02-23 2021-03-30 2021-09-26 and lower secondary educati ant Selection ntation ture, including sanitation and on water availability in schools MZ-MEDH-206265-CS-INDV / Increasing access and retent Technical Assistance to supp ion of girls in upper primary Individual Consult Under Implement / Post Limited 0.00 2020-12-15 2023-03-27 2020-12-20 2021-01-10 2021-02-14 2021-08-13 ort DIPLAC in statics analysis and lower secondary educati ant Selection ation and evaluation of the educati on on system. MZ-MEDH-206276-CS-INDV / Increasing access and retent Technical Assistance to the P ion of girls in upper primary Individual Consult Under Implement / Post Open 0.00 2020-11-29 2022-08-01 2021-01-17 2021-02-07 2021-03-14 2021-09-10 re-school Department and co and lower secondary educati ant Selection ation ordination with MGCAS. on 01/CONS/ILEGP/21 / Procure Project management, monit Individual Consult Under Implement ment Specialist for Books an IDA / V3610 Prior Open 0.00 2021-03-19 2021-03-15 2021-04-25 2021-05-07 2021-06-03 2022-06-03 oring and evaluation ant Selection ation d Teaching Materials 02/CONS/ILEGP/21 / Procure Project management, monit Individual Consult IDA / V3610 Prior Open 163,200.00 Signed 2021-04-05 2021-03-23 2021-05-12 2021-11-03 2021-05-27 2021-12-20 2021-06-24 2022-01-08 2022-06-24 ment Specialist oring and evaluation ant Selection 03/CON/ILEGP/21 / Financial Project management, monit Individual Consult Under Implement IDA / V3610 Post Open 0.00 2021-04-15 2021-11-30 2021-05-24 2021-06-08 2021-06-30 2022-06-30 Manager Specialist oring and evaluation ant Selection ation 04/CON/ILEGP/21 / Develop Improving learning in primar Individual Consult ment of Environmental and S IDA / V3610 Post Limited 110,500.00 Signed 2021-04-28 2021-04-26 2021-05-03 2020-06-30 2021-05-07 2020-10-15 2021-05-19 2020-10-23 2021-06-30 y education ant Selection ocial Instruments 06/CONS/ILEGP/21 / Project Project management, monit Individual Consult Under Implement IDA / D7930 Post Open 0.00 2021-09-03 2021-11-30 2021-10-09 2021-10-19 2021-11-05 2023-11-06 Coordinator oring and evaluation ant Selection ation 07/CONS/ILEGP/21 / Project Project management, monit Individual Consult Under Implement TF / B5326 Post Open 0.00 2021-09-06 2021-11-30 2021-10-16 2021-10-25 2021-11-08 2023-11-08 Accountant oring and evaluation ant Selection ation 08/CONS/ILEGP/21 / Social D Project management, monit Individual Consult Under Implement IDA / D7930 Post Open 0.00 2021-09-10 2021-09-16 2021-10-15 2021-10-22 2021-11-05 2023-11-06 evelopment Specialist oring and evaluation ant Selection ation 09/CONS/ILEGP/21 / Infrastru Project management, monit Individual Consult Under Implement TF / B5326 Post Open 0.00 2021-09-17 2021-11-30 2021-10-23 2021-10-28 2021-11-08 2023-11-08 cture Development Specialist oring and evaluation ant Selection ation 10/CONS/ILEGP/21 / Project Project management, monit Individual Consult Under Implement Provincial Coordinator - Cabo IDA / D7930 Post Open 0.00 2021-09-30 2021-09-16 2021-11-10 2021-11-25 2021-12-23 2023-12-26 oring and evaluation ant Selection ation Delegado Province 11/CONS/ILGEP/21 / Project Project management, monit Individual Consult Under Implement IDA / D7930 Post Open 0.00 2021-09-30 2021-11-30 2021-11-10 2021-11-25 2021-12-23 2023-12-26 Provincial Coordinator - Niass oring and evaluation ant Selection ation a Province 12/CONS/ILEGP/21 / Project Project management, monit Individual Consult Under Implement Provincial Coordinator - Nam IDA / D7930 Post Open 0.00 2021-09-30 2021-11-30 2021-11-10 2021-11-25 2021-12-23 2023-12-26 oring and evaluation ant Selection ation pula Province Page 5 13/CONS/ILEGP/21 / Project Project management, monit Individual Consult Provincial Coordinator - Zam IDA / D7930 Post Open 0.00 Signed 2021-09-30 2021-11-30 2021-11-10 2023-02-02 2021-11-25 2023-02-02 2021-12-23 2023-12-26 oring and evaluation ant Selection bézia Province 14/CONS/ILEGP/21 / Project Project management, monit Individual Consult Under Implement IDA / D7930 Post Open 0.00 2021-09-30 2021-11-30 2021-11-10 2021-11-25 2021-12-23 2023-12-26 Provincial Coordinator - Tete oring and evaluation ant Selection ation Province 15/CONS/ILEGP/21 / Project Project management, monit Individual Consult IDA / D7930 Post Open 0.00 Signed 2021-09-30 2021-11-30 2021-11-10 2022-06-15 2021-11-25 2022-06-17 2021-12-23 2023-12-26 Provincial Coordinator - Sofal oring and evaluation ant Selection a province 16/CONS/ILEGP/21 / Project Project management, monit Individual Consult Under Implement IDA / D7930 Post Open 0.00 2021-09-30 2021-11-30 2021-11-10 2021-11-25 2021-12-23 2023-12-26 Provincial Coordinator - Mani oring and evaluation ant Selection ation ca Province 17/CONS/ILEGP/21 / Project Project management, monit Individual Consult Under Implement Provincial Coordinator - Inha IDA / D7930 Post Open 0.00 2021-09-30 2021-11-30 2021-11-10 2021-11-25 2021-12-23 2023-12-26 oring and evaluation ant Selection ation mbane Province 18/CONS/ILEGP/21 / Project Project management, monit Individual Consult Under Implement IDA / D7930 Post Open 0.00 2021-09-30 2021-09-16 2021-11-10 2021-11-25 2021-12-23 2023-12-26 Provincial Coordinator - Gaza oring and evaluation ant Selection ation Province 19/CONS/ILEGP/21 / Project Project management, monit Individual Consult Under Implement IDA / D7930 Post Open 0.00 2021-09-30 2021-11-30 2021-11-10 2022-07-19 2021-11-25 2022-07-22 2021-12-23 2023-12-26 Provincial Coordinator - Mapu oring and evaluation ant Selection ation to Province 20/CONS/ILEGP/21 / Project Project management, monit Individual Consult Under Implement IDA / D7930 Post Open 0.00 2021-09-30 2021-11-30 2021-11-10 2021-11-25 2021-12-23 2023-12-26 Provincial Coordinator - Cida oring and evaluation ant Selection ation de de Maputo 35/CONS/ILEGP/22 / Procure Project management, monit Individual Consult IDA / D7930 Prior Direct 64,800.00 Signed 2022-04-04 2022-03-23 2022-04-14 2022-03-28 2022-05-05 2022-04-26 2022-06-09 2022-05-06 2022-12-06 ment Specialist oring and evaluation ant Selection 50/CONS/ILEGP/22 / Consult Improving learning in primar Individual Consult Pending Impleme ant for Publishing (Edition, La IDA / D7930 Post Limited 0.00 2022-05-31 2022-06-05 2022-06-13 2022-06-30 2022-08-29 y education ant Selection ntation yout, Pagination and Ilustrati on); Consultant 1 48/CONS/ILEGP/22 / Consult Improving learning in primar Individual Consult Pending Impleme ant for Publishing (Edition, La IDA / D7930 Post Limited 0.00 2022-05-31 2022-06-05 2022-06-13 2022-06-30 2022-08-29 y education ant Selection ntation yout, Pagination and Ilustrati on); Consultant 2 49/CONS/ILEGP/22 / Consult Improving learning in primar Individual Consult Pending Impleme ant for Publishing (Edition, La IDA / D7930 Post Limited 0.00 2022-05-31 2022-06-05 2022-06-13 2022-06-30 2022-08-29 y education ant Selection ntation yout, Pagination and Ilustrati on); Consultant 3 63/CONS/ILEGP/22 / Speciali Increasing access and retent Individual Consult Under Implement st for Quality Control for file IDA / D7930 ion of girls in upper primary Post Open 0.00 2022-07-18 2022-07-28 2022-09-05 2022-09-26 2022-10-31 2023-04-29 ant Selection ation notes (fichas) for class 7. Co and lower secondary educati nsultant 1 on 64/CONS/ILEGP/22 / Speciali Increasing access and retent Individual Consult Under Implement st for Quality Control for file IDA / D7930 ion of girls in upper primary Post Open 0.00 2022-07-18 2022-07-28 2022-09-05 2022-09-26 2022-10-31 2023-04-29 ant Selection ation notes (fichas) for class 7 Con and lower secondary educati sultant 2 on 65/CONS/ILEGP/22 / Speciali Increasing access and retent Individual Consult Under Implement st for Quality Control for file IDA / D7930 ion of girls in upper primary Post Open 0.00 2022-07-18 2022-07-28 2022-09-05 2022-09-26 2022-10-31 2023-04-29 ant Selection ation notes (fichas) for class 7. Co and lower secondary educati nsultant 3 on 66/CONS/ILEGP/22 / Speciali Increasing access and retent Individual Consult Under Implement st for Quality Control for file IDA / D7930 ion of girls in upper primary Post Open 0.00 2022-07-18 2022-07-28 2022-09-05 2022-09-26 2022-10-31 2023-04-29 ant Selection ation notes (fichas) for class 7 Con and lower secondary educati sultant 4 on 67/CONS/ILEGP/22 / Speciali Increasing access and retent Individual Consult Under Implement st for Quality Control for file IDA / D7930 ion of girls in upper primary Post Open 0.00 2022-07-18 2022-07-28 2022-09-05 2022-09-26 2022-10-31 2023-04-29 ant Selection ation notes (fichas) for class 7. Co and lower secondary educati nsultant 5 on 68/CONS/ILEGP/22 / Speciali Increasing access and retent Individual Consult Under Implement st for Quality Control for file IDA / D7930 ion of girls in upper primary Post Open 0.00 2022-07-18 2022-07-28 2022-09-05 2022-09-26 2022-10-31 2023-04-29 ant Selection ation notes (fichas) for class 7 Con and lower secondary educati sultant 6 on 69/CONS/ILEGP/22 / Speciali Increasing access and retent Individual Consult Under Implement st for Quality Control for file IDA / D7930 ion of girls in upper primary Post Open 0.00 2022-07-18 2022-07-28 2022-09-05 2022-09-26 2022-10-31 2023-04-29 ant Selection ation notes (fichas) for class 7. Co and lower secondary educati nsultant 7 on 73/CONS/ILEGP/22 / Procure Project management, monit Direct - Internation Under Implement IDA / D7930 Prior Direct Selection 0.00 2022-07-22 2022-07-29 2022-08-01 2022-08-04 2022-10-05 2023-04-03 ment Audit for year 2020 oring and evaluation al ation 52/CONS/ILEGP/22 / Procure Project management, monit Individual Consult IDA / D7930 Prior Direct 0.00 Canceled 2022-06-06 2022-06-16 2022-06-20 2022-06-30 2024-06-30 ment Specialist oring and evaluation ant Selection 94/IC/ILEGP/22 / Senior Proc Project management, monit Individual Consult Open - Internationa Under Implement IDA / D7930 Prior 0.00 2022-08-17 2022-08-29 2022-10-05 2023-04-12 2022-10-26 2023-05-24 2022-11-30 2023-05-29 urement Specialist oring and evaluation ant Selection l ation 109/IC/ILEGP/22 / Technical Increasing access and retent Assistance to design the mon ion of girls in upper primary Individual Consult Under Implement IDA / D7930 Post Open - National 0.00 2022-12-14 2022-12-28 2023-02-01 2023-02-22 2023-03-29 2023-09-25 itoring system foe the attend and lower secondary educati ant Selection ation ance, punctuality and attend on ance for teacher’s 103/IC/ILEGP/22 / Individual Consultant for psychometric Project management, monit Individual Consult Under Implement IDA / D7930 Post Open - National 0.00 2023-01-11 2023-02-27 2023-03-01 2023-03-22 2023-04-26 2023-10-23 and data analysis and suppor oring and evaluation ant Selection ation t in the preparation of the 20 22 National 90/IC/ILEGP/22 / Individual C onsultant to support INDE in Project management, monit Individual Consult Pending Impleme IDA / D7930 Post Open - National 0.00 2023-01-25 2023-03-15 2023-04-05 2023-05-10 2023-11-06 the implementation of Large oring and evaluation ant Selection ntation Scale Assessments 81/IC/ILEGP/23 / Senior Acco Project management, monit Individual Consult Under Implement IDA / D7930 Post Limited 0.00 2023-04-03 2023-03-22 2023-04-10 2023-05-01 2023-06-05 2025-05-05 untant I oring and evaluation ant Selection ation 82/IC/ILEGP/23 / Senior Acco Project management, monit Individual Consult Under Implement IDA / D7930 Post Limited 0.00 2023-04-03 2023-03-22 2023-04-10 2023-05-01 2023-06-05 2025-05-05 untant II oring and evaluation ant Selection ation 80/IC/ILEGP/23 / Financer Ma Project management, monit Individual Consult Under Implement IDA / D7930 Post Limited 0.00 2023-04-03 2023-03-22 2023-04-10 2023-05-01 2023-06-05 2025-05-05 nagement oring and evaluation ant Selection ation 83-A/IC/ILEGP/23 / Financial Project management, monit Individual Consult Under Implement IDA / D7930 Post Limited 0.00 2023-04-19 2023-04-06 2023-04-24 2023-05-15 2023-06-19 2023-12-16 Assistant oring and evaluation ant Selection ation 83/IC/ILEGP/23 / Financial As Project management, monit Individual Consult IDA / D7930 Prior Limited 0.00 Canceled 2023-04-03 2023-04-10 2023-05-01 2023-06-05 2025-05-05 sistant oring and evaluation ant Selection Page 6 110/IC/ILEGP/23 / Consultan cy Service for harmony and r Improving learning in primar Individual Consult Pending Impleme IDA / D7930 Post Open - National 0.00 2023-05-02 2023-06-20 2023-07-11 2023-08-15 2024-02-11 evise the program for sexual y education ant Selection ntation health and reproductive and HIV/SIDA 142/IC/ILEGP/23 / Procureme Project management, monit Individual Consult Under Implement IDA / D7930 Prior Open - National 0.00 2023-06-01 2023-06-15 2023-07-24 2023-08-14 2023-09-18 2024-03-16 nt Specialist I oring and evaluation ant Selection ation 143/IC/ILEGP/23 / Procureme Project management, monit Individual Consult Under Implement IDA / D7930 Prior Open - National 0.00 2023-06-01 2023-06-20 2023-07-24 2023-08-14 2023-09-18 2024-03-16 nt Specialist oring and evaluation ant Selection ation Page 7 FEDERAL REPUBLIC OF NIGERIA 18-Months Procurement Plan General: Project Information: Nigeria; REDISSE; P159040. Project Implementation Agency: Nigeria Centre for Disease Control (NCDC) Date of the Procurement Plan: April 2018 Period covered by this Procurement Plan: April 2018 - November, 2019 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers”, July 2016 (Revised November 2017) (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. III. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Nigeria Public Procurement Act 2007 and the Regulations, 2016, such arrangements shall be subject to paragraph 5.3 and 5.4 of the Procurement Regulations and the following conditions: o There should be no mandatory requirements for inclusion of local experts and firms for the consulting assignments; o There should be no exclusive preference based on threshold prescribed in PPA and credit and its Regulations; o Negotiations with the lowest evaluated bidder to reduce price in the case of goods, works and non-consulting services where competitive methods have been used shall not be allowed; 1 o The fixed budget method shall not be used for goods, works and non- consulting services; o Established and approved procurement standards by the government may be used, provided that they are not restrictive When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. IV. Prequalification: Applicable (May be applicable at the Federal for high value Consultant Assignments V. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable VI. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable VII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Domestic preference is not applicable for National Open Competitive Procurement VIII. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is: Not Applicable IX. Other Relevant Procurement Information: Not Applicable 2 3 X. Threshold for Prior Review, Procurement Approaches and Methods – Goods, Works and Non- Consulting Services Procurement Approaches and Methods (US$ millions) Category Open Open National Request for Quotation International (RfQ) Works, Turnkey, and ≥5 <5 ≤ 0.2 S&I of Plant and Equipment Goods, IT, and non- ≥5 <0.5 ≤ 0.1 consulting services Post Review: All contracts not subject to prior review shall be subject to post review. XI. Summary of the procurement packages for Goods, Works and Non-Consulting Services: Sr. Contract Implem Estima Revie Market Selecti Evaluati Procurem Prequ Domesti Expect Expect No Description enting ted w by Approa on on ent alifica c ed ed date Agency Cost Bank ch Metho Options Process tion Prefere date of (US$) (Prior (Open- d (Most (Single (Yes/ nce of bid/ Contra / Nationa (RFP, Advanta stage- No) (Yes/No propo ct Post) l/ RFB, geous single ) sal Signat Limited RFQ, Bid, envelope openin ure etc.) DS BAFO, etc.) g etc.) Rated Criteria etc.) GOODS 1 Procureme NCDC 3,579,1 Post Open, RFB Most Single No No 08-10- 22-10-18 nt of (AH & 39 National Advanta stage- 18 Vehicles HH) geous single (12 Nos. Bid envelope 4WD DC; 6Nos. 4WD Veterinary Ambulatory vehicle; 4 Nos. 4WD 4 SUVs; 1No. 20Tonnes Truck; 75 Motorcycle and 175 Tricycle 2 Procureme NCDC 198,162 Post Open, RFB Most Single No No 20-03- 10-04-19 nt of Office (AH) National Advanta stage- 19 Equipment geous single & Furniture Bid envelope for 37 state Vet. Public Health /Epidemiolo gy Offices 3 Procureme NCDC 97,377 Post Limited RfQ Rated Single No No 17-09- 01-10-18 nt of (AH) Criteria envelope 18 Laptops and Internet Modem for Surveillanc e activities & Non- Android Phones for animal disease informants 4 Procureme NCDC 926,423 Post Open, RFB Most Single No No 08-10- 22-10-18 nt of Lab. (HH) National Advanta envelope 18 Equipt. , geous Reagents & Bid Consumabl es and Biosecurity Materials (4Lots) 5 Procureme NCDC 295,082 Prior DIR DIR Direct Single No No Nov. Nov. nt of (AH) Selection envelope 2018 2021 5 50000/Vial of ARV Vaccine 6 Procureme NCDC 1,067,8 Post Open, RFB Most Single No No 08-10- 22-10-18 nt of (AH 68 National Advanta envelope 18 Veterinary &HH) geous Stockpiles Bid for preventabl e Zoonotic diseases (AH ) & Consumabl e for HEPR Stockpiling (HH) -2 Lots 7 Procureme NCDC 45,015 Post Limited RfQ Rated Single No No 17-09- 01-10-18 nt of Office (AH) Criteria envelope 18 Furniture/E quipment for Crises Manageme nt Centre (AH) 8 Supply of NCDC 75,374 Post Limited RfQ Rated Single No No 17-09- 01-10-18 Office (AH) Criteria envelope 18 Furniture and Equipment for REDISSE Animal Health Component Office (AH) 9 Printing of NCDC 146,787 Post Limited RfQ Rated Single No No 31-10- 14-11-18 IDSR (HH) Criteria envelope 18 Guideline 10 Printing of NCDC 200,164 Post Limited RfQ Rated Single No No 31-10- 14-11-18 IDSR Tools (HH) Criteria envelope 18 6 (Forms 001,002, 003) 11 Printing of NCDC 36,393 Post Limited RfQ Rated Single No No 31-10- 14-11-18 IDSR Policy (HH) Criteria envelope 18 12 Procureme NCDC 819,672 Post Open, RFB Most Single No No 08-10- 22-10-18 nt of (HH) National Advanta envelope 18 Emergency geous Laboratory Bid reagents and consumable s for NRL/CPHL 13 Procureme NCDC 606,557 Post Open, RFB Most Single No No 08-10- 22-10-18 nt of (HH) National Advanta envelope 18 Consumabl geous e and IPC Bid Materials (HH) 14 Supply of NCDC 68,508 Post Limited RfQ Most Single No No 17-09- 01-10-18 Office (HH) Advanta envelope 18 Furniture geous and Bid Equipment for REDISSE PCU Office - (HH) 15 Procureme NCDC 57,172 Post Limited RfQ Rated Single No No 31-10- 14-11-18 nt of Tabs (HH) Criteria envelope 18 (80), Laptops (35) and 2GB/Month USB Internet Service for step-down training for IDSR for HH 7 16 Supply and NCDC 98,361 Post Limited RfQ Rated Single No No 17-09- 01-10-18 Installation (HH) Criteria envelope 18 of 250 KVA Gen. Set and 20 KVAs Solar Panels and Inverters for REDISSE PCU's Office Total Goods 8,318, 954 WORKS 17 Rehabilitati NCDC 110,16 Post Limited RfQ Rated Single No No 21-01- 04-02-19 on of 7 Nos (AH) 4 Criteria envelope 19 State Veterinary Public Health/Epid emiology offices - NW ZONE ( Kaduna, Katsina, Kano, Jigawa,Keb bi, Zamfara & Sokoto) 18 Rehabilitati NCDC 94,426 Post Limited RfQ Rated Single No No 21-01- 04-02-19 on of 6 Nos. (AH) Criteria envelope 19 State Veterinary Public Health/Epid emiology offices- NE ZONE (Bauchi, Borno, 8 Yobe, Adamawa, Gombe & Taraba) 19 Rehabilitati NCDC 110,16 Post Limited RfQ Rated Single No No 21-01- 04-02-19 on of 7 Nos (AH) 4 Criteria envelope 19 State Veterinary Public Health/Epid emiology offices - NC ZONE ( Plateau, Nasarawa, Benue, Niger, Kogi, Kwara & FCT) 20 Rehabilitati NCDC 94,426 Limited Limited RfQ Rated Single No No 21-01- 04-02-19 on of 6 Nos. (AH) Criteria envelope 19 State Veterinary Public Health/Epid emiology offices - SW ZONE (Osun, Oyo, Ogun, Ondo, Lagos & Ekiti) 21 Rehabilitati NCDC 94,426 Limited Limited RfQ Rated Single No No 21-01- 04-02-19 on of 6 Nos. (AH) Criteria envelope 19 State Veterinary Public Health/Epid emiology 9 offices - SS ZONE ( Edo, Delta, Bayelsa, Rivers, Cross- Rivers & Akwa-Ibom) 22 Rehabilitati NCDC 78,688 Post Limited RfQ Rated Single No No 21-01- 04-02-19 on of 5 Nos. (AH) Criteria envelope 19 State Veterinary Public Health/Epid emiology offices - SE ZONE ( Enugu, Ebonyi, Imo, Anambra & Abia) 23 Refurbishm NCDC 75,374 Post Limited RfQ Rated Single No No 21-01- 04-02-19 ent of (HH) Criteria envelope 19 REDISSE Animal Health component office at Headquarte r 24 Renovation NCDC 114,75 Post Limited RfQ Rated Single No No 21-01- 04-02-19 and (HH) 4 Criteria envelope 19 upgrade of 7 Nos. Isolation Centers in NW ZONE ( Kaduna, Katsina, 10 Kano, Jigawa, Kebbi, Zamfara & Sokoto) 25 Renovation NCDC 98,360 Post Limited RfQ Rated Single No No 21-01- 04-02-19 and (HH) Criteria envelope 19 upgrade of 6 Nos. Isolation Centers in NE ZONE (Bauchi, Borno, Yobe, Adamawa, Gombe & Taraba) 26 Renovation NCDC 114,75 Post Limited RfQ Rated Single No No 21-01- 04-02-19 and (HH) 4 Criteria envelope 19 upgrade of 7 Nos. Isolation Centers in NC ZONE ( Plateau, Nasarawa, Benue, Niger, Kogi, Kwara & FCT) 27 Renovation NCDC 98,360 Post Limited RfQ Rated Single No No 21-01- 04-02-19 and (HH) Criteria envelope 19 upgrade of 6 Nos. Isolation Centers in SW ZONE (Osun, Oyo, Ogun, 11 Ondo, Lagos & Ekiti) 28 Renovation NCDC 98,360 Post Limited RfQ Rated Single No No 21-01- 04-02-19 and (HH) Criteria envelope 19 upgrade of 6 Nos. Isolation Centers in SS ZONE ( Edo, Delta, Bayelsa, Rivers, Cross- Rivers & Akwa-Ibom) 29 Renovation NCDC 81,967 Post Limited RfQ Rated Single No No 21-01- 04-02-19 and (HH) Criteria envelope 19 upgrade of 5 Nos. Isolation Centres in SE ZONE ( Enugu, Ebonyi, Imo, Anambra & Abia) 30 Supply and NCDC 606,55 Post Open, RFB Most Single No No 04-03- 25-03-19 Installation (HH) 7 National Advanta envelope 19 of 1No. geous Incinerator Bid in a selected facilty in each of the six geopolitical zones Total works 1,870, 780 12 NON-CONSULTING SERVICES 31 Registration NCDC (AH) 20,492 Post Limited RfQ Rated Single No No 18-12- 02-10-19 of Criteria envelope 18 motorcycles (75 Nos. ) and tricycle (175 Nos.) for AH 32 Registration NCDC (AH) 266,437 Post Limited RfQ Rated Single No No 18-12- 02-10-19 and Insurance Criteria envelope 18 for 9 Nos. 4WD DC vehicles; 2 Nos. 15- Seater Bus; 6 Nos. 4WD Vet. Ambulatory vehicle; 2 Nos. SUVs; and 1No. 20Tonne Truck for AH 33 Registration NCDC 93,098 Post Limited RfQ Rated Single No No 18-12- 02-10-19 and Insurance (HH) Criteria envelope 18 for 3 Nos. 4WD DC vehicles; 2 Nos. SUVs for HH 34 Installation of NCDC 4,049 Post Limited RfQ Rated Single No No 18-12- 02-10-19 tracking (AH) Criteria envelope 18 systems in 9 Nos. 4WD DC vehicles; 2 Nos. 15- Seater Bus; 6 Nos. 4WD Vet. Ambulatory vehicle; 2 Nos. SUV for AH 35 Installation of NCDC 1,066 Post Limited RfQ Rated Single No No 18-12- 02-10-19 tracking (HH) Criteria envelope 18 systems in 3 Nos. 4WD DC vehicles; 2 Nos. SUV for HH 36 Support for NCDC 16,393 Post Limited RfQ Rated Single No No 18-12- 02-10-19 Distribution of (AH) 18 13 Office logistic Criteria envelope and Lab. Materials to 37 state, NVRI and 10 VTHs 37 Procurement NCDC 142,043 Post Limited RfQ Rated Single No No 18-12- 02-10-19 of courier (HH) Criteria envelope 18 service logistics for specimen transportation and pre- positioning of supplies 38 Recruitment NCDC 45,246 Post Limited RfQ Rated Single No No 17-09- 01-10-18 of 17 (AH) Criteria envelope 18 contract/ad hoc staff (AH) Total Non- 588,82 Consulting 5 Services Note: Based on Liberia’s specific needs and circumstances, shopping threshold for the purchase of vehicles and fuel may be increased up to US$500,000. Thresholds for Prior Review, Selection Approaches and Methods – Consulting Services Category Prior Review Short List of National Consultants (US$ millions) Consulting Engineering and Construction Supervision Services Consultants (Firms) ≥ 0.5 ≤ 0.1 ≤ 0.2 Individual Consultants ≥ 0.2 n.a. n.a. Note: Consultancy services estimated to cost equivalent to US$ 300,000 and above per contract shall be advertised in the United Nations Development Business (UNDB) online in addition to advertising in national newspaper(s) of wide circulation and/or regional newspaper. XI. Summary of the procurement packages for Consulting Services -Planned for the first 18 months after project effectiveness): 14 Sr. Contract Implem Estimat Revie Market Selection Shortlist Expected Expected No Description enting ed Cost w by Approach Method ing date of date of Agency (US$) Bank (Open - (QCBS, (Yes/ No) bid/ Contract (Prior/ Internation FBS, LCBS, proposal Signature Post) al/ QBS, CQS, opening National/ DS etc.) etc.) 39 Engagement of NCDC 7,026 Post Limited INDV No 15-10-18 29-10-18 Individual Consultants from relevant Sectors to develop a National Strategy for ONE Health and Workforce strategy 40 Recruitment of NCDC 201,836 Prior Open, INDV No 01-10-18 15-10-18 3 Consultants National to support for 12 months to facilitate NCDC-FETP training and lead redesign of the FETP programme 41 Engagement of NCDC 243,934 Prior Open, INDV No 01-10-18 22-10-18 5 Consultants/ National Specialists in relevant Thematic Areas to support Project Implementatio n 42 Consultancy NCDC 197,871 Post Open, CQS No 15-10-18 29-10-18 for Branding National and corporate 15 communication including development of risk communication strategies for the REDISSE project 43 Consultancy to NCDC 66,953 Post Open, CQS No 15-10-18 29-10-18 develop project National website and project intranet including overhaul and upgrade of NCDC website and development of REDISSE webpages 44 Consultancy NCDC 177,540 Post Open, CQS No 18-03-19 01-04-19 for National Establishing, developing, training, and licensing enterprise management of software for Procurement, Audit and Financial management 45 Engagement of NCDC 11,689 Post Limited INDV No 15-10-18 29-10-18 a Consultant to provide Safeguard, Waste Management 16 and Grievance Support 46 Engagement of NCDC 9,797 Post Limited INDV No 20-02-19 06-03-19 2 Individual Consultants to conduct situational analysis and develop a road map for development of laboratory standards 47 Consultancy to NCDC 80,343 Post Open, CQS No 20-02-19 06-03-19 conduct Needs National assessment and consensus building for human and animal health information systems to develop a plan and road map for an interconnected real-time system for human and animal health including a development of a technical plan data systems integration 48 Consultancy NCDC 106,749 Post Open, CQS No 17-04-19 02-05-19 for a National National Public Health Laboratory 17 Needs Assessment 49 Consultancy to NCDC 7,065 post Limited INDV No 20-02-19 06-03-19 develop strategy and training modules on shipment of samples for diagnosis of) zoonotic and epidemic prone diseases 50 Consultancy NCDC 180,343 Post Open, CQS No 17-04-19 02-05-19 for the National assessment of isolation units in all the state capitals in the country to identify gaps compared to global best practice and develop minimum standards for isolation practice 51 Consultancy NCDC 78,220 Post Open, CQS No 17-04-19 02-05-19 for Situational National Analysis and Development of a Multi- hazard Plans 52 Consultancy to NCDC 71,555 Post Open, CQS No 17-04-19 02-05-19 conduct gap National analysis of the existing surveillance 18 system for Transboundary Animal Diseases and zoonotic diseases 53 Consultancy to NCDC 48,355 Post Limited INDV No 15-11-18 29-11-18 conduct the prioritization of TADs and zoonotic diseases. Review and update priority animal diseases TADs 54 Consultancy to NCDC 64,575 Post Open, CQS No 17-04-19 02-05-19 harmonize and National develop guidelines, protocols and tools for animal disease surveillance and disease reporting processes 55 Consultancy to NCDC 14,942 Post Limited INDV No 17-04-19 02-05-19 develop training manual for Surveillance Agents (AH) 56 Consultancy to NCDC 24,104 Post Limited INDV No 17-04-19 02-05-19 identify and develop the GIS Mapping of Hot-spots in human, Wild and Domestic 19 animals interface(AH) 57 Engagement of NCDC 196,721 Post Open, INDV No 15-10-18 29-10-18 25 National Veterinarians as ad hoc staff (AH) 58 Engagement of NCDC 61,967 Post Open, INDV No 15-10-18 29-10-18 10 ad-hoc National Laboratory Scientists at NRL (HH) 59 Consultancy NCDC 56,429 Post Open, CQS No 14-11-18 28-11-18 for re- National assessment of 37 Veterinary Public Health/ Epidemiology offices, preparation of BOQs and Supervision of Rehabilitation 60 Consultancy NCDC 60,656 Post Open, CQS No 14-11-18 28-11-18 for re- National assessment of 37 Isolation Centers, preparation of BOQs and Supervision of renovation Total Consultancy 1,968,6 Services 70 20 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank- financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub- 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 21 contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 22 Title of the person signing the Letter: 23 PROCUREMENT Western and Central Africa : Regional Disease Surveillance Systems Enhancement (REDISSE) Phase II PLAN General Information Country: Western and Central Africa 2018-09-27 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P159040 GPN Date: Project Name: Regional Disease Surveillance Systems Enhancement (REDISSE) Phase II Loan / Credit No: IDA / 59680 MINISTERE DE LA SANTE Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GW-MS-80385-CW-RFQ / Con Component 2: Strengthening Request for Quota Single Stage - One E 2018-12-0 struction d' un puit de 250 m IDA / 59680 Post Limited 100,000.00 74,894.65 Signed 2018-09-05 2018-11-29 2018-10-08 2018-10-12 of Laboratory Capacity tions nvelope 7 ètres à la direction Générale de l' L'élevage. GW-MS-74646-CW-RFB / Réh abilitation des 3 laboratoires Component 2: Strengthening Single Stage - One E 2019-06-0 IDA / 59680 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2018-10-29 2018-11-13 2018-12-25 2019-01-14 2019-02-07 régionaux (Bissorã, Bafatá et of Laboratory Capacity nvelope 7 Gabú) en vue de les mettre a ux normes. GW-MS-107780-CW-RFB / Co Component 2: Strengthening Single Stage - One E 2020-12-1 nstruction et equipement d' IDA / 59680 Post Request for Bids Open - National 85,000.00 0.00 Canceled 2020-02-10 2020-02-15 2020-03-28 2020-04-27 2020-06-01 of Laboratory Capacity nvelope 8 un laboratoire de type P2 GW-MS-107804-CW-RFB / Co Component 3: Preparedness Single Stage - One E 2021-01-2 nstruction d' un entrepôt nati IDA / 59680 Post Request for Bids Open - National 250,000.00 0.00 Canceled 2020-05-07 2020-05-15 2020-06-15 2020-06-29 2020-07-27 and Emergency Response nvelope 3 onal et 3 régionaux pour rép onses rapides. GW-MS-141370-CW-RFP / Ré Component 5: Institutional C Single Stage - One E 2020-09-0 aménagement du bâtiment IDA / 59680 apacity Building, Project Ma Post Request for Bids Open - National 415,000.00 0.00 Canceled 2020-03-31 2020-04-09 2020-05-11 2020-05-25 2020-06-08 nvelope 6 MINSAP et extension du bure nagement, Coordination and au de l'UGP Advocacy GW-MS-107800-CW-RFQ / Ré habilitation des laboratoires Component 2: Strengthening Request for Quota Single Stage - One E 2020-08-2 IDA / 59680 Post Limited 175,000.00 0.00 Canceled 2020-04-03 2020-04-30 de santé régionaux à Gabu, of Laboratory Capacity tions nvelope 8 Bafata, Canchungo et Bolam a. Request for Bids - GW-MS-74640-CW-RFB / Réh Component 2: Strengthening Single Stage - One E Works (without pr Under Imple 2019-05-2 abilitation du laboratoire vét IDA / 59680 Post Request for Bids Open - National 595,000.00 0.00 2018-11-12 2023-04-03 2018-11-17 2023-04-06 2018-12-17 2023-05-05 2019-01-06 2023-05-18 2019-01-26 of Laboratory Capacity nvelope equalification) SP mentation 6 érinaire Central D GW-MS-339374-CW-RFB / Ré Request for Bids - habilitation de laboratoires d Component 2: Strengthening Single Stage - One E Works (without pr 2023-08-1 IDA / 59680 Post Request for Bids Open - National 238,500.00 0.00 Canceled 2023-04-06 2023-04-13 2023-05-13 2023-05-28 2023-06-18 e santé publique régionaux d of Laboratory Capacity nvelope equalification) SP 7 ans Gabu, Bafata, Canchung D o et Bolama. GW-MS-107781-CW-RFB / Re Request for Quota habilitation des laboratoires Component 2: Strengthening Single Stage - One E Pending Imp 2023-09-1 IDA / 59680 Post Request for Bids Open - National tions (Non Bank-S 204,250.00 0.00 2023-06-12 2023-06-18 2023-07-16 2023-07-23 2023-08-13 véterinaires regionaux (Gabu of Laboratory Capacity nvelope lementation 2 PD) , Bafata et Bissorã) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GW-MS-80383-GO-RFQ / Ach at de vaccin, antibiotiques et Component 2: Strengthening Request for Quota Single Stage - One E IDA / 59680 Post Limited 35,000.00 31,282.18 Signed 2018-09-14 2018-11-30 2018-09-25 2018-09-21 2018-09-28 consommables pour la Direct of Laboratory Capacity tions nvelope ion générale de l' élevage GW-MS-74633-GO-UN / Acha Component 2: Strengthening UN Agencies (Dire Pending Impl IDA / 59680 Post Direct 60,000.00 0.00 2018-10-11 2018-10-16 2018-11-20 2019-05-19 t de 30 motos de 125 cc of Laboratory Capacity ct) ementation Component 5: Institutional C GW-MS-80379-GO-RFQ / Ach Request for Quota Single Stage - One E IDA / 59680 apacity Building, Project Ma Post Limited 45,000.00 39,247.52 Signed 2018-08-30 2018-11-29 2018-09-28 2018-10-04 2018-11-27 at de 2 groupes electrogènes tions nvelope nagement, Coordination and Advocacy GW-MS-74632-GO-RFB / Acq Component 2: Strengthening Open - Internationa Single Stage - One E IDA / 59680 Post Request for Bids 450,000.00 0.00 Canceled 2018-10-02 2018-10-15 2018-11-15 2018-12-10 2019-01-14 2019-02-19 uisition d´un laboratoire de t of Laboratory Capacity l nvelope ype P2 GW-MS-170217-GO-RFQ / Ac Component 1: Surveillance a hat de trois (03) véhicules do IDA / 59680 Post Direct Selection Direct 104,801.92 98,649.56 Completed 2020-05-04 2020-04-28 2020-05-07 2020-04-28 2020-05-29 2020-04-30 2020-06-28 2020-05-30 nd Information Systems uble cabine GW-MS-170218-GO-RFQ / Ac hat des matériels médicaux Component 1: Surveillance a Request for Quota Single Stage - One E pour l'Equipe de Réponse Ra IDA / 59680 Post Limited 269,720.00 37,704.41 Signed 2020-05-11 2020-04-29 2020-06-20 2020-05-12 2020-07-20 nd Information Systems tions nvelope pide (ERR) dans le cadre de l a lutte contre le Covid - 19 GW-MS-170340-GO-RFQ / Ac hat des matériels de protecti Component 1: Surveillance a Request for Quota Single Stage - One E on pour le personnel de la Di IDA / 59680 Post Limited 145,520.00 89,821.33 Signed 2020-05-05 2020-05-05 2020-06-05 2020-05-20 2020-07-05 nd Information Systems tions nvelope rection Générale de l'Elevage et de l'Environnement. GW-MS-170229-GO-DIR / Ac Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 59680 Post Limited 55,129.14 54,929.86 Completed 2020-05-04 2020-05-04 2020-05-15 2020-05-13 2020-06-14 2020-06-28 hats des matériels informatiq nd Information Systems tions nvelope ues GW-MS-170683-GO-UN / Acc ord entre le Gouvernement d e la République de la Guinée Component 3: Preparedness UN Agencies (Dire - Bissau (REDISSE II) et le PN IDA / 59680 Post Direct 3,730,323.71 3,730,323.71 Signed 2020-04-30 2020-04-29 2020-05-04 2020-04-30 2020-05-20 2020-05-02 2020-08-18 and Emergency Response ct) UD pour l'acquisition des mat ériels de protection dans le c adre de la lutte contre le Cov id - 19 GW-MS-170684-GO-DIR / Ac Component 2: Strengthening quisition d'équipements de p IDA / 59680 Post Direct Selection Direct 63,420.00 62,634.64 Completed 2020-04-28 2020-04-28 2020-05-02 2020-04-28 2020-05-23 2020-05-01 2020-06-22 2020-07-23 of Laboratory Capacity rotection (PPE) Page 1 GW-MS-171062-GO-UN / Acc ord entre le Gouvernement d e la République de la Guinée Component 2: Strengthening UN Agencies (Dire - Bissau (REDISSE II) et le PN IDA / 59680 Post Direct 2,377,702.90 2,377,702.90 Completed 2020-04-30 2020-04-29 2020-05-04 2020-04-30 2020-05-20 2020-05-02 2020-08-18 2021-03-07 of Laboratory Capacity ct) UD pour l'acquisition des mat ériels de laboratoire dans le c adre de la lutte contre le Cov id - 19. GW-MS-171089-GO-UN / Acc ord entre le Gouvernement d e la République de la Guinée - Bissau (REDISSE II) et le PN Component 1: Surveillance a UN Agencies (Dire IDA / 59680 Post Direct 410,494.39 410,494.39 Completed 2020-04-30 2020-04-29 2020-05-04 2020-04-30 2020-05-20 2020-05-02 2020-08-18 2021-03-07 UD pour l'acquisition des mat nd Information Systems ct) ériels médicaux et ambulanc es pour l'équipe de réponse r apide (ERR) dans le cadre de la lutte contre le Covid - 19. GW-MS-190254-GO-DIR / Ac quisition des médicaments p Component 3: Preparedness Pending Impl IDA / 59680 Post Direct Selection Direct 90,000.00 0.00 2020-09-01 2020-09-04 2020-09-11 2020-10-11 our le traitement des person and Emergency Response ementation nes infectées par le COVID 1 9. GW-MS-249788-GO-RFB / Ac Component 1: Surveillance a Open - Internationa Single Stage - One E IDA / 59680 Post Request for Bids 300,000.00 0.00 Canceled 2021-09-22 2021-09-27 2021-11-08 2021-12-08 2022-01-19 2022-03-20 quisitions de véhicules 4x4 nd Information Systems l nvelope GW-MS-161942-GO-RFB / Ac Component 5: Institutional C hat des mobiliers de bureau apacity Building, Project Ma Single Stage - One E pour le siege de la Direction IDA / 59680 Post Request for Bids Open - National 150,000.00 0.00 Canceled 2020-11-02 2020-11-12 2020-12-14 2020-12-23 2021-01-04 2021-03-05 nagement, Coordination and nvelope Generale de l´Elevage et des Advocacy repartitions regionales de l´E levage GW-MS-110234-GO-DIR / Ac Component 2: Strengthening Request for Quota Single Stage - One E IDA / 59680 Post Limited 95,000.00 0.00 Canceled 2019-10-15 2019-12-10 2020-06-07 hat réactifs pour le laboratoir of Laboratory Capacity tions nvelope e national GW-MS-107809-GO-RFQ / Ac Component 3: Preparedness Request for Quota Single Stage - One E IDA / 59680 Post Limited 70,000.00 0.00 Canceled 2020-11-19 2020-12-29 2021-02-27 hat equipements pour entrep and Emergency Response tions nvelope ôts GW-MS-107801-GO-RFQ / Ac quisition d' équipement pour Component 2: Strengthening Request for Quota Single Stage - One E la Direction G´nérale de l' Ele IDA / 59680 Post Limited 51,000.00 0.00 Canceled 2020-03-24 2020-04-24 2020-05-24 of Laboratory Capacity tions nvelope vage ( 10 frigos, 5 congélate urs avec panneaux solaires). GW-MS-74631-GO-RFQ / Ach Component 1: Surveillance a Request for Quota Single Stage - One E at d´equipements informatiq IDA / 59680 Post Limited 100,000.00 0.00 Canceled 2019-12-18 2020-01-29 2020-03-14 nd Information Systems tions nvelope ues et logiciel pour RENAVE GW-MS-107782-GO-RFQ / Eq uipement de 3 laboratoires v Component 2: Strengthening Request for Quota Single Stage - One E étérinaires régionaux confor IDA / 59680 Post Limited 25,500.00 0.00 Canceled 2020-09-15 2020-10-13 2020-12-14 of Laboratory Capacity tions nvelope mement aux normes national es et internationales. GW-MS-141382-GO-RFQ / Ac hat de vaccins, antibiotiques Component 2: Strengthening IDA / 59680 Post Direct Selection Direct 62,500.00 0.00 Canceled 2019-10-25 2019-10-30 2019-11-13 2020-05-11 et consommables pour la ca of Laboratory Capacity mpagne nationale contre la r age GW-MS-170219-GO-RFQ / Ac Component 3: Preparedness UN Agencies (Dire IDA / 59680 Post Direct 75,000.00 0.00 Canceled 2020-07-31 2020-08-05 2020-08-31 2020-10-30 quisitions des motos and Emergency Response ct) GW-MS-339272-GO-RFB / Ac hat de matériel et équipeme Component 1: Surveillance a Single Stage - One E Under Imple IDA / 59680 Post Request for Bids Open - National 275,000.00 0.00 2023-01-31 2023-02-02 2023-02-02 2023-02-09 2023-03-06 2023-03-19 2023-04-09 2023-05-09 nt informatique pour l'introdu nd Information Systems nvelope mentation ction des NTIC, pour le DHIS 2 IIC et E-Health GW-MS-249741-GO-RFQ / Ac hat de matériel et équipeme Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 59680 Post Limited 75,000.00 0.00 Canceled 2021-09-02 2021-10-22 2021-11-21 nt informatique pour l'introdu nd Information Systems tions nvelope ction des NTIC, IIC et E-Healt h GW-MS-329414-GO-RFQ / Ac Component 1: Surveillance a Request for Quota Single Stage - One E Under Imple quisitions de matériel roulant IDA / 59680 Post Limited 400,000.00 0.00 2023-02-08 2023-02-08 2023-03-16 2023-04-30 nd Information Systems tions nvelope mentation : Vehicules 4X4 GW-MS-249762-GO-RFB / Ac hat de Consommables et Réa Component 2: Strengthening Single Stage - One E IDA / 59680 Post Request for Bids Open - National 222,000.00 0.00 Canceled 2023-02-06 2023-02-10 2023-03-14 2023-03-29 2023-04-26 2023-05-26 ctifs pour les Laboratoires na of Laboratory Capacity nvelope tionaux de Santé Humaine et Animale GW-MS-249746-GO-RFB / Aq uisition des equipement de p rotection, prelevemenement, Component 1: Surveillance a Single Stage - One E IDA / 59680 Post Request for Bids Open - National 270,000.00 0.00 Canceled 2021-08-31 2021-09-07 2021-10-07 2021-10-22 2021-11-17 2021-12-17 conservation pour renforcer l nd Information Systems nvelope a capacité de surveillance de s epidemies /pandemies et la gestion des déchets GW-MS-339288-GO-RFB / Aq uisition et maintenance d'éq uipement des laboratoires: L Component 2: Strengthening Single Stage - One E IDA / 59680 Post Request for Bids Open - National 200,000.00 0.00 Canceled 2023-03-30 2023-04-06 2023-05-05 2023-05-20 2023-06-10 2023-07-10 NSP, 5 laboratoires des hopit of Laboratory Capacity nvelope aux regionaux, laboratoire V eterinaire Central et (3) regi onaux GW-MS-249786-GO-RFQ / Aq Component 1: Surveillance a Request for Quota Single Stage - One E Pending Impl uisition de matériels pour la s IDA / 59680 Post Limited 50,000.00 0.00 2023-02-06 2023-03-27 2023-04-26 nd Information Systems tions nvelope ementation urveilance de la faune sauva ge GW-MS-249782-GO-RFQ / Aq uisition des frigos et congelat Component 2: Strengthening Request for Quota Single Stage - One E Under Imple IDA / 59680 Post Limited 70,000.00 0.00 2023-02-02 2023-02-15 2023-03-16 2023-04-15 eurs à panneaux solaires et k of Laboratory Capacity tions nvelope mentation its de panneaux solaires GW-MS-339300-GO-RFB / Ac Component 1: Surveillance a Single Stage - One E quisition des vaccins et seru IDA / 59680 Post Request for Bids Open - National 200,000.00 0.00 Canceled 2023-02-16 2023-02-23 2023-03-25 2023-04-09 2023-04-30 2023-05-30 nd Information Systems nvelope m contre la rage. GW-MS-339308-GO-RFB / Ac quisition et installation des m Component 2: Strengthening Single Stage - One E IDA / 59680 Post Request for Bids Open - National 180,000.00 0.00 Canceled 2023-03-09 2023-03-16 2023-04-15 2023-04-30 2023-05-28 2023-07-27 odules pré-fabriqués (3) et 2 of Laboratory Capacity nvelope chambres froides modulaire. Page 2 GW-MS-74627-GO-RFB / Ach Component 1: Surveillance a UN Agencies (Dire at groupé via UNOPS de 5 ve IDA / 59680 Post Direct 250,000.00 0.00 Canceled 2018-10-15 2018-10-20 2018-11-24 2019-05-23 nd Information Systems ct) hicules 4X4 GW-MS-249748-GO-RFQ / Ac quisition de 1 autoclave, mat eriel de sterilisation, unite de metrologie pour le Laboratori Component 2: Strengthening Request for Quota Single Stage - One E IDA / 59680 Post Limited 95,000.00 0.00 Canceled 2021-09-21 2021-11-10 2021-12-10 e National de Sante Publique of Laboratory Capacity tions nvelope (LNSP), materiel d'évaluatio n des risques et 10 boîtes d'e mballage triple pour le sante animale et humaine GW-MS-249771-GO-RFQ / Aq uisition et maintenance d'éq Component 2: Strengthening Request for Quota Single Stage - One E IDA / 59680 Post Limited 100,000.00 0.00 Canceled 2021-10-06 2021-12-01 2022-01-15 uipement des laboratoires du of Laboratory Capacity tions nvelope LNSP et des 5 hopitaux regio naux GW-MS-249784-GO-RFQ / Ac Component 4: Human Resou hat fournitures, équipement rce Management for Effectiv Request for Quota Single Stage - One E IDA / 59680 Post Limited 115,000.00 0.00 Canceled 2021-09-20 2021-11-15 2021-12-15 et matériel pour les déplace e Disease Surveillance and E tions nvelope ments sur le terrain (Appilcat pidemic Preparedness ions) GW-MS-339293-GO-RFB / Ac quisition et installation des é Component 2: Strengthening Single Stage - One E Pending Impl IDA / 59680 Post Request for Bids Open - National 125,000.00 0.00 2023-05-31 2023-06-06 2023-07-04 2023-07-19 2023-08-09 2023-09-23 quipements pour le système of Laboratory Capacity nvelope ementation énergie photovoltaique/ grou pes électrogènes; GW-MS-361590-GO-DIR / Ac hat d'équipement et consom mables pour les laboratoires, Component 1: Surveillance a Direct - Internation Pending Impl IDA / 59680 Post Direct Selection 3,000,000.00 0.00 2023-06-05 2023-06-09 2023-06-23 2023-08-22 d'équipements de protection, nd Information Systems al ementation prelevemenement, d'équipe ments de protection individu elle, de vaccins et serum. GW-MS-249758-GO-RFQ / Ac Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl hats d'incinerateurs de haute IDA / 59680 Post Limited 90,000.00 0.00 2023-06-18 2023-07-23 2023-08-22 of Laboratory Capacity tions nvelope ementation temperature NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GW-MS-74629-NC-RFQ / Pro duction et analyse de rapport Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 59680 Post Limited 10,000.00 0.00 Canceled 2018-11-01 2019-01-01 2019-01-31 s mensuels et hebdomadaire nd Information Systems tions nvelope s (fiches d´analyse) GW-MS-74636-NC-DIR / Acha Component 5: Institutional C t de logiciel de gestion pour l apacity Building, Project Ma Under Imple IDA / 59680 Post Direct Selection Direct 50,000.00 0.00 2019-12-16 2021-02-15 2019-12-18 2020-01-19 2020-07-17 e projet REDISSE II et le Proje nagement, Coordination and mentation t santé Maternelle Advocacy GW-MS-249967-NC-DIR / Ela boration d'un Plan Strategiqu Component 1: Surveillance a IDA / 59680 Post Direct Selection Direct - National 60,000.00 0.00 Canceled 2022-10-03 2022-10-17 2022-11-28 2023-05-27 e des Politiques (Polices) nati nd Information Systems onales pour surveillance pour une santé unique CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GW-MS-74670-CS-CQS / Audi Component 3: Preparedness Consultant Qualifi Open - Internationa Under Implement t externe du projet Exercices IDA / 59680 Post 100,000.00 0.00 2018-11-19 2018-11-08 2018-12-19 2018-11-14 2019-01-17 2019-01-16 2019-01-27 2019-02-08 2021-06-30 and Emergency Response cation Selection l ation 2018/2019/2020 GW-MS-74665-CS-CQS / Act ualisation de la Loi Vétérinai Component 3: Preparedness Consultant Qualifi Open - Internationa IDA / 59680 Post 60,000.00 0.00 Canceled 2018-10-15 2018-11-05 2018-11-20 2018-12-05 2018-12-26 2019-02-24 re et ses Règlements (servic and Emergency Response cation Selection l e consultant national et inter national) GW-MS-74753-CS-CQS / Etu Component 3: Preparedness Consultant Qualifi Open - Internationa de pour l´évaluation de la for IDA / 59680 Post 120,000.00 0.00 Canceled 2018-10-15 2018-10-30 2018-11-19 2018-12-19 2019-01-09 2019-03-10 and Emergency Response cation Selection l ce de travail de la santé publi que GW-MS-74754-CS-CQS / Plan Component 3: Preparedness Consultant Qualifi Open - Internationa National des ressouces huma IDA / 59680 Post 50,000.00 0.00 Canceled 2018-10-21 2018-11-11 2018-12-25 2019-01-04 2019-01-18 2019-03-19 and Emergency Response cation Selection l ines - Secteur Santé GW-MS-74668-CS-CDS / Etu des d'impact pour la constru Component 3: Preparedness Consultant Qualifi Open - Internationa ction d'un laboratoire nationa IDA / 59680 Post 105,000.00 0.00 Canceled 2019-10-28 2019-11-18 2020-01-01 2020-01-31 2020-02-24 2020-04-24 and Emergency Response cation Selection l l de santé publique pour la sa nté humaine et animale GW-MS-249974-CS-CQS / En quête/ Étude de ligne des ba Component 1: Surveillance a Consultant Qualifi ses sur les facteurs de risque IDA / 59680 Post Limited 70,000.00 0.00 Canceled 2021-09-08 2021-09-22 2021-10-22 2021-11-19 2022-03-19 nd Information Systems cation Selection et prévalence de fréquence pour les zoonoses identifié d ans le pays. GW-MS-249976-CS-CQS / Ela Component 1: Surveillance a Consultant Qualifi boration de la Politique Natio IDA / 59680 Post Limited 92,000.00 0.00 Canceled 2021-09-20 2021-10-04 2021-10-25 2021-11-22 2022-02-20 nd Information Systems cation Selection nal de surveillance environne mentale GW-MS-163132-CS-UN / Assi stance Technique de l'OMS p our l'Evaluation des capacité s du systhème national de la Component 2: Strengthening UN Agencies (Dire IDA / 59680 Post Direct 50,000.00 0.00 Canceled 2020-07-31 2021-01-27 boratoire de (santé huamain of Laboratory Capacity ct) e et animale) pour diagnostiq ue et confirmation de maladi es tropicales negligées (DTN S) et d' autres zoonoses. Page 3 GW-MS-107736-CS-CQS / Et ude de ligne de base sur les f Component 1: Surveillance a Consultant Qualifi IDA / 59680 Post Limited 30,000.00 0.00 Canceled 2020-03-31 2020-04-09 2020-04-30 2020-05-11 2020-11-07 acteurs de risque des maladi nd Information Systems cation Selection es tropicales négligées (DTN) et zoonoses. GW-MS-107739-CS-CQS / Ré alisation d' une enquête (étu Component 1: Surveillance a Consultant Qualifi de de prévalence) (vue génér IDA / 59680 Post Limited 30,000.00 0.00 Canceled 2020-03-19 2020-03-26 2020-04-16 2020-04-28 2020-10-25 nd Information Systems cation Selection ale) de fréquence pour le DT N identifié dans le pays. GW-MS-141378-CS-CQS / As sistance technique pour l'éla Component 1: Surveillance a Consultant Qualifi IDA / 59680 Post Limited 75,000.00 0.00 Canceled 2020-03-12 2020-03-19 2020-04-10 2020-04-20 2020-10-17 boration du regime juridique nd Information Systems cation Selection et réglementation des déche ts solides urbains GW-MS-141376-CS-CQS / As sistance technique d'un bure au d'étude et conseils, pour l Component 1: Surveillance a Consultant Qualifi IDA / 59680 Post Limited 75,000.00 0.00 Canceled 2020-05-06 2020-05-13 2020-06-03 2020-06-15 2020-08-14 a préparation du regime jurid nd Information Systems cation Selection ique et reglementation pour l es centres de traitement des déchets chimiques. GW-MS-107733-CS-CQS / En quête (vue générale) sur l' a Component 1: Surveillance a Consultant Qualifi griculture periurbaine et sa r IDA / 59680 Post Limited 20,000.00 0.00 Canceled 2020-03-10 2020-03-16 2020-04-06 2020-04-14 2020-10-11 nd Information Systems cation Selection elation avec les determinants de santé pour la prévention d e zoonoses et d' autres GW-MS-329430-CS-CQS / Ét ude d'Impact Environnement ale et Social (EIES) des tarva Component 2: Strengthening Consultant Qualifi Under Implement ux de Réhabilitation du labor IDA / 59680 Post Limited 50,000.00 0.00 2022-12-07 2023-04-06 2022-12-14 2022-12-21 2023-01-12 2023-02-02 of Laboratory Capacity cation Selection ation atoire vétérinaire Central et des laboratoires vétérinaires régionaux (Gabu, Bafatá et B issorã) GW-MS-339392-CS-CQS / Et udes environnemenatale et s ociale des travaux de réhabili Component 2: Strengthening Consultant Qualifi IDA / 59680 Post Limited 40,000.00 0.00 Canceled 2023-02-06 2023-02-20 2023-03-06 2023-03-27 2023-04-26 tation des laboratoires de sa of Laboratory Capacity cation Selection nté publique régionaux de G abu, Bafata, Canchungo et B olama. Component 5: Institutional C GW-MS-249996-CS-QCBS / A Consultant Qualifi Pending Impleme IDA / 59680 apacity Building, Project Ma Post Limited 50,000.00 0.00 2023-03-24 2023-03-31 2023-04-30 2023-05-21 2023-06-20 udit externe du projet cation Selection ntation nagement, Coordination and Advocacy INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GW-MS-76177-CS-CDS / For Component 5: Institutional C Under Implement mation des nouveaux technic IDA / 59680 apacity Building, Project Ma Post Direct Selection Direct 415,000.00 0.00 2018-10-07 2018-10-07 2018-10-07 2019-10-07 ation iens et médecins vétérinaire nagement, Coordination and s. Advocacy GW-MS-74747-CS-DIR / Eval uation de la capacité des lab Component 3: Preparedness IDA / 59680 Post Direct Selection Direct 20,000.00 0.00 Canceled 2018-10-22 2018-11-01 2019-01-05 2019-07-04 oratoires de service vétérinai and Emergency Response res - Institut Meyrieux- Dakar GW-MS-158209-CS-INDV / R Component 5: Institutional C Individual Consult Pending Impleme ecrutment d'un Coordinateur IDA / 59680 apacity Building, Project Ma Post Open 27,160.00 0.00 2020-02-13 2020-03-16 2020-03-20 2020-03-28 2020-09-24 ant Selection ntation National pour le projet REDIS nagement, Coordination and SE Advocacy GW-MS-158755-CS-INDV / R ecrutement d'un Coordinateu r National Senior, pour la coo Component 5: Institutional C rdination du Projet de renforc apacity Building, Project Ma Individual Consult IDA / 59680 Post Open 31,050.00 0.00 Canceled 2020-02-13 2020-03-12 2020-03-16 2020-03-20 2020-09-16 ement de l'offre de services nagement, Coordination and ant Selection de santé maternelle et infant Advocacy ile en Guinée-Bissau, et le Pr ojet régional de Surveillance épidémiologique. GW-MS-139876-CS-CQS / Em Component 5: Institutional C Individual Consult baucher un spécialiste en sui IDA / 59680 apacity Building, Project Ma Post Limited 34,200.00 0.00 Canceled 2019-10-28 2019-11-02 2019-11-03 2019-11-15 2020-05-13 ant Selection vi et évaluation nagement, Coordination and Advocacy GW-MS-163073-CS-INDV / R Component 5: Institutional C ecrutement d'un Consultant apacity Building, Project Ma Individual Consult IDA / 59680 Post Open 20,000.00 0.00 Canceled 2020-03-12 2020-04-16 2020-04-21 2020-04-30 2020-10-27 Spécialiste en Suivi Évaluatio nagement, Coordination and ant Selection n pour le projet REDISSE Advocacy GW-MS-107770-CS-INDV / Et ude de viabilité pour la const Component 2: Strengthening Individual Consult ruction d' un nouveau bâtime IDA / 59680 Post Open 50,000.00 0.00 Canceled 2019-05-13 2019-07-01 2019-07-22 2019-08-26 2020-02-22 of Laboratory Capacity ant Selection nt pour le laboratoire nation al de santé publique , santé humaine et animale. GW-MS-139877-CS-CDS / Re Component 5: Institutional C crutement d'un Consultant S apacity Building, Project Ma Individual Consult Under Implement IDA / 59680 Post Open 36,000.00 0.00 2020-10-05 2020-06-08 2020-11-09 2021-01-26 2020-11-16 2021-01-29 2020-11-30 2021-05-29 pécialiste en Passation de m nagement, Coordination and ant Selection ation archés pour le projet REDISS Advocacy E II GW-MS-174260-CS-CDS / Lic Component 5: Institutional C Pending Impleme enciatura em enfermagem v IDA / 59680 apacity Building, Project Ma Post Direct Selection Direct 600,000.00 0.00 2020-05-22 2020-05-25 2020-06-18 2023-06-03 ntation eterinaria. nagement, Coordination and Advocacy GW-MS-185758-CS-CDS / Re Component 5: Institutional C crutement de Monsieur Inocê apacity Building, Project Ma Pending Impleme IDA / 59680 Post Direct Selection Direct 32,000.00 0.00 2020-07-27 2020-07-29 2020-08-07 2021-02-03 ncio Lopes pour le poste de C nagement, Coordination and ntation oordinateur du Projet REDISS Advocacy E. GW-MS-217171-CS-INDV / R Component 5: Institutional C Individual Consult ecrutement d'un Consultant IDA / 59680 apacity Building, Project Ma Post Limited 20,000.00 37,621.39 Signed 2021-08-04 2021-01-24 2021-08-09 2021-04-21 2021-08-23 2021-08-07 2021-09-06 2022-09-08 2022-09-06 ant Selection Auditeur Interne pour le proj nagement, Coordination and et REDISSE /SMI Advocacy GW-MS-246781-CS-INDV / R Component 5: Institutional C ecrutement d' un Consultant apacity Building, Project Ma Individual Consult IDA / 59680 Post Limited 24,000.00 24,785.12 Completed 2021-08-09 2021-08-20 2021-08-12 2021-08-26 2021-08-19 2021-09-08 2021-08-24 2021-09-16 2021-12-15 2022-02-23 pour appuyer la Revue à Mi-p nagement, Coordination and ant Selection arcours du Projet Advocacy Page 4 GW-MS-249985-CS-INDV / El Component 3: Preparedness Individual Consult aboration de Plan Stratégiqu IDA / 59680 Post Limited 16,000.00 0.00 Canceled 2021-09-29 2021-10-04 2021-10-18 2021-11-08 2022-01-07 and Emergency Response ant Selection e de lutte contre la rage GW-MS-163096-CS-CDS / Re crutement d'IANPH pour l'Etu de de viabilité pour la constr Component 2: Strengthening IDA / 59680 Post Direct Selection Direct 50,000.00 0.00 Canceled 2020-04-09 2020-04-16 2020-05-19 2020-11-15 uction d' un nouveau bâtime of Laboratory Capacity nt pour le laboratoire nation al de santé publique , santé humaine et animale. GW-MS-136313-CS-CDS / Ph Component 1: Surveillance a ase d'expansion d'un systèm IDA / 59680 Prior Direct Selection Direct 750,000.00 0.00 Canceled 2019-10-30 2019-11-09 2019-12-06 2021-11-25 nd Information Systems e d'information intégré DHIS 2 GW-MS-107766-CS-INDV / Ev aluation des capacités du sys thème national de laboratoir Component 2: Strengthening Individual Consult e de (santé huamaine et ani IDA / 59680 Post Open 50,000.00 0.00 Canceled 2019-10-15 2019-12-03 2019-12-24 2020-01-28 2020-07-26 of Laboratory Capacity ant Selection male) pour diagnostique et c onfirmation de maladies tropi cales negligées (DTNS) et d' autres zoonoses. GW-MS-254790-NC-DIR / For Component 4: Human Resou mation de 10 techniciens en rce Management for Effectiv Direct - Internation IDA / 59680 Post Direct Selection 70,000.00 70,000.00 Signed 2022-09-12 2022-09-12 2022-09-15 2022-09-14 2022-09-23 2022-09-16 2023-04-30 surveillance et épidémiologie e Disease Surveillance and E al FETP (classes intermédiaires pidemic Preparedness de niveau 2) GW-MS-329416-CS-CDS / Ré vision des études et Supervis Component 2: Strengthening Under Implement IDA / 59680 Post Direct Selection Direct - National 150,000.00 0.00 2022-12-09 2023-01-27 2022-12-16 2023-01-05 2023-02-04 ion de travaux de Réhabilitati of Laboratory Capacity ation on du laboratoire vétérinaire Central GW-MS-329509-CS-INDV / E nquête/ Étude de ligne des b Component 1: Surveillance a Individual Consult IDA / 59680 Post Limited 70,000.00 0.00 Canceled 2022-12-05 2022-12-19 2022-12-09 2022-12-23 2023-01-09 2023-02-23 ases sur les facteurs de risqu nd Information Systems ant Selection e et prévalence de fréquenc e pour les zoonoses GW-MS-339381-CS-INDV / El aboration d'un "Plan Strategi que National de la surveillanc Component 1: Surveillance a Individual Consult IDA / 59680 Post Limited 60,000.00 0.00 Canceled 2023-03-30 2023-04-04 2023-04-25 2023-05-30 2023-07-29 e selon l'approche de la Sant nd Information Systems ant Selection é Unique" (et inclus des espè ces de faune sauvage et de l utte contre la rage). GW-MS-339387-CS-INDV / Ev aluation de la Surveillance ba sée sur les événements com Component 1: Surveillance a Individual Consult IDA / 59680 Post Limited 50,000.00 0.00 Canceled 2023-02-06 2023-02-11 2023-03-04 2023-03-18 2023-05-17 munautaires (VBEC) et appui nd Information Systems ant Selection à la fonctionnalité de la VBEC au niveau local et national. GW-MS-339395-CS-INDV / Et udes et Supervision pour la Component 2: Strengthening Individual Consult Under Implement IDA / 59680 Post Limited 35,000.00 0.00 2023-02-03 2023-02-09 2023-02-08 2023-02-18 2023-03-04 2023-04-03 Réhabilitation des laboratoire of Laboratory Capacity ant Selection ation s vétérinaires régionaux (Ga bu, Bafatá et Bissorã) GW-MS-339398-CS-INDV / Et ude et Supervision pour la Ré Component 2: Strengthening Individual Consult habilitation des laboratoires IDA / 59680 Post Limited 35,000.00 0.00 Canceled 2023-02-06 2023-02-09 2023-02-10 2023-02-20 2023-03-06 2023-04-05 of Laboratory Capacity ant Selection de santé publique régionaux dans Gabu, Bafata, Canchun go et Bolama. GW-MS-339399-CS-INDV / R Component 5: Institutional C ecrutement d'un Consultant apacity Building, Project Ma Individual Consult IDA / 59680 Post Limited 35,000.00 0.00 Canceled 2023-02-06 2023-02-11 2023-03-04 2023-03-18 2023-05-02 pour l'élaboration du Joint Ex nagement, Coordination and ant Selection ternal Evaluation (JEE) de la Advocacy Guinée-Bissau GW-MS-249981-CS-INDV / El Component 3: Preparedness Individual Consult aboration du Plan d’Action N IDA / 59680 Post Limited 95,000.00 0.00 Canceled 2021-09-23 2021-09-28 2021-10-12 2021-11-02 2022-01-31 and Emergency Response ant Selection ational de Sécurité Sanitaire Component 5: Institutional C GW-MS-332226-CS-INDV / As Individual Consult Pending Impleme IDA / 59680 apacity Building, Project Ma Post Limited 55,000.00 0.00 2023-03-08 2023-03-15 2023-04-12 2023-04-26 2023-08-30 sistant technique du projet ant Selection ntation nagement, Coordination and Advocacy GW-MS-353739-CS-CDS / RE NFORCEMENT DE CAPACITE Component 1: Surveillance a Direct - Internation Pending Impleme DES ACTEURS CLÉS SUR LA C IDA / 59680 Post Direct Selection 8,500.00 0.00 2023-06-12 2023-06-16 2023-07-07 2023-08-06 nd Information Systems al ntation APTURE DE LA FAUNE DE PET ITE, MOYENNE ET GRANDE T AILLE GW-MS-358425-CS-INDV / C onsultant pour appuyer à la p Component 1: Surveillance a Individual Consult Open - Internationa Under Implement IDA / 59680 Post 65,000.00 0.00 2023-06-05 2023-06-01 2023-07-01 2023-07-08 2023-07-22 2023-08-21 roduction d’un annuaire stati nd Information Systems ant Selection l ation stique de la santé 2022 en G uinée Bissau GW-MS-360632-CS-INDV / D Component 5: Institutional C Individual Consult Pending Impleme éveloppement du site web d IDA / 59680 apacity Building, Project Ma Post Limited 20,000.00 0.00 2023-06-06 2023-06-11 2023-06-25 2023-07-10 2023-08-09 ant Selection ntation e l'UCP nagement, Coordination and Advocacy GW-MS-339385-CS-INDV / El aboration de la Politique Nati Component 1: Surveillance a Individual Consult Pending Impleme IDA / 59680 Post Limited 60,000.00 0.00 2023-06-10 2023-06-15 2023-07-06 2023-07-27 2023-08-26 onal des facteurs et risques e nd Information Systems ant Selection ntation nvironnementaux en matière s de santé public Page 5 PROCUREMENT PLAN (Textual Part) Project information: Nigeria Sustainable Urban and Rural Water Supply, Sanitation and Hygiene Program P170734 Project Implementation Agency: Federal Ministry of Water Resources and Seven (7) States (Ekiti, Delta, Gombe, Imo, Kaduna, Katsina & Plateau Date of the Procurement Plan: 25th November, 2021 Period covered by this Procurement Plan: January 2022 to June 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan Tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable]; Works: [is not applicable] Table 1: Summary of the procurement packages for Goods Market Selectio Evaluation Expect Approa Revie n Options Expected ed ch w by Estimat Method (Most date of date of Sr. Contract (Open- Bank ed Cost (RFP, Advantageo bid/ Contra No Description Nation (Prior/ (US$) RFB, us Bid, proposal ct al/ Post) RFQ, DS BAFO, Rated opening Signat Limited etc.) Criteria etc.) ure etc.) Procurement of Operational Vehicles (6 Nos operational Lowest 25/01/202 01/02/2 1 vehicles: 3 for FPIU, Post 500,000 Limited RFQ 2 022 Evaluated Cost 1 each for CNC, PEWASH and NWRI) Goods Procurement of ICT Equipment (Audio Visual, Internet etc) Open- 08/02/202 01/03/2 2 Post 400,000 RFB for FPIU/FMWR, CNC, National Lowest 2 022 PEWASH, NAP & Evaluated Cost NWRI offices (Goods) Procurement of Office Equipment & Furniture (Laptop, 08/02/202 08/03/2 3 Desktop, Table, Post 100,000 Limited RFQ Lowest 2 022 Chair) for FPIU, CNC, Evaluated Cost PEWASH, NAP, & NWRI (Goods) 1,000,0 Total 00 Table 2: Summary of the procurement packages for Consulting Services Selection Market Method Approach Expected Review (QCBS, Expected Estimat (Open - Shortlisti date of Sr. by Bank FBS, date of Contract Description ed Cost Internation ng bid/ No (Prior/ LCBS, Contract (US$) al/ (Yes/ No) proposal Post) QBS, Signature National/ opening CQS, DS etc.) etc.) 25/01/202 1 Procurement of an M&E Specialist Post 50,000 Limited INDV No 11/01/2022 2 Consultancy Services for Engagement 14/01/202 2 of Environmental Safeguard Post 50,000 Limited INDV No 7/12/2021 1 Specialist Consultancy Services for Engagement 14/01/202 3 Post 50,000 Limited INDV No 7/12/2021 of Social Safeguard Specialist 1 Consultancy Services for Engagement 25/01/202 4 of Technical Assistance for Program Post 50,000 Limited INDV No 11/01/2022 2 Operational Manual Consultancy Services to Support 19/04/202 5 States’ in meeting the Readiness Post 300,000 Limited CQS No 5/04/2022 2 criteria to participate in the project. Consultancy services for review year 17/05/202 6 2000 National Water Supply and Post 300,000 Limited CQS No 3/05/2022 2 Sanitation Policy Consultancy Services for Development of a National Social and 300,000 Limited 22/03/202 7 Post CQS No 8/03/2022 Behaviour Change Communication 2 (SBCC) Strategy Consultancy Services for 29/03/202 8 Development of a National Market- Post 300,000 Limited CQS No 15/03/2022 2 Based Sanitation Strategy Consultancy Services for 9 Post CQS No 22/03/2022 5/04/200 Development of Information, 300,000 Limited Education and Communication (IEC) and Training Materials Consultancy Services for Development of Strategy and Roadmap/Framework for Open- 31/05/202 10 Prior 500,000 QCBS Yes 10/05/2022 Implementation of Water, Sanitation International 2 & Hygiene (WASH) Management Information System (MIS) Consultancy Services for the 5,000,00 Open- 11 engagement of Independent Prior QCBS Yes 15/03/2022 5/04/2022 0 International Verification Agent (IVA) for P4R 7,200,0 Total Consultancy Services 00 PROCUREMENT Nigeria : Nigeria Sustainable Urban and Rural Water Supply, Sanitation and Hygiene Program-for-Results PLAN General Information Country: Nigeria Bank’s Approval Date of the Original Procurement Plan: 2022-06-02 Revised Plan Date(s): (comma delineated, leave blank if 2023-05-31 none) Project ID: P170734 GPN Date: Project Name: Nigeria Sustainable Urban and Rural Water Supply, Sanitation and Hygiene Program-for-Results Loan / Credit No: IDA / 68820 SURWASH KATSINA Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-SURWASH KATSINA-2957 Request for Quota Single Stage - One E Pending Impl 99-GO-RFQ / Procurement of IDA / 68820 Post Limited 208,081.00 0.00 2022-05-31 2022-06-28 2022-07-26 tions nvelope ementation 3no. 4x4WD (Pickup)Van NG-SURWASH KATSINA-2957 91-GO-RFQ / Procurement of Laptop PCs, Desk topPCs, HP Printers, Photocopying Machi Request for Quota Single Stage - One E Under Imple ne, Scanner, Video, Projector, IDA / 68820 Post Limited 40,000.00 0.00 2022-05-30 2022-06-28 2022-07-26 tions nvelope mentation Conferencing system, still ca meras, camcorders, Wifi inter net facilities hard drive( 2TB) splash drives(32 GB) & shred ing merchines NG-SURWASH KATSINA-2957 82-GO-RFQ / Procurement of Office Tables,Exercutive Chai Request for Quota Single Stage - One E Pending Impl rs,Visitors Chairs,15 Seater C IDA / 68820 Post Limited 41,775.00 0.00 2022-05-29 2022-07-05 2022-08-02 tions nvelope ementation onference, Office Cabinet (Fir e Proof) Extention Box and St ablizers, Standing fans, Fridg e, Smart Tv,and water Dispe nser. NG-SURWASH KATSINA-2957 Request for Quota Single Stage - One E Pending Impl 85-GO-RFQ / Procurement of IDA / 68820 Post Limited 10,000.00 0.00 2022-06-25 2022-07-29 2022-08-26 tions nvelope ementation Application Packages and Sof twaeres NG-SURWASH KATSINA-3652 Request for Quota Single Stage - One E Pending Impl 36-GO-RFQ / Procurement of IDA / 68820 Post Limited 109,489.00 0.00 2023-06-10 2023-07-07 2023-08-06 tions nvelope ementation 1 vehicle (2022/2023) for SPI U NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-SURWASH KATSINA-3591 Consultant Qualifi 10-CS-CQS / Engagement of IDA / 68820 Post Limited 45,000.00 0.00 Canceled 2023-05-22 2023-06-05 2023-06-19 2023-07-03 2026-07-02 cation Selection External Auditor for three (3) Years INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-SURWASH KATSINA-3138 98-CS-INDV / Engagement of Individual Consult Pending Impleme IDA / 68820 Post Limited 34,146.00 0.00 2022-09-05 2022-09-12 2022-09-19 2022-09-24 2023-09-24 Technical Assistance Consult ant Selection ntation ant for Social Safeguards NG-SURWASH KATSINA-3139 03-CS-INDV / Engagement of Individual Consult Pending Impleme IDA / 68820 Post Limited 34,146.00 0.00 2022-09-05 2022-09-12 2022-09-19 2022-09-24 2023-09-24 consultant Monitoring and Ev ant Selection ntation aluation Consultancy Service s NG-SURWASH KATSINA-2957 98-CS-INDV / Engagement of Individual Consult IDA / 68820 Post Limited 20,000.00 0.00 Canceled 2022-06-06 2022-06-10 2022-06-17 2022-07-01 2022-09-29 Technical Assistance Consult ant Selection ant for Social Safeguards NG-SURWASH KATSINA-2957 87-CS-INDV / Engagement of Individual Consult IDA / 68820 Post Limited 20,000.00 0.00 Canceled 2022-06-06 2022-06-10 2022-06-17 2022-07-01 2022-09-29 Technical Assistance Consult ant Selection ant for Environmental Safegu ards NG-SURWASH KATSINA-2957 94-CS-INDV / Engagement of Individual Consult IDA / 68820 Post Limited 20,000.00 0.00 Canceled 2022-06-06 2022-06-10 2022-06-17 2022-07-01 2022-09-29 consultant Monitoring and Ev ant Selection aluation Consultancy Service s NG-SURWASH KATSINA-3139 01-CS-INDV / Engagement of Individual Consult Pending Impleme IDA / 68820 Post Limited 34,146.00 0.00 2022-09-05 2022-09-12 2022-09-19 2022-09-24 2023-09-19 Technical Assistance Consult ant Selection ntation ant for Environmental Safegu ards Page 1 NG-SURWASH KATSINA-3620 31-CS-CDS / Engagement of Pending Impleme IDA / 68820 Post Direct Selection Direct - National 45,000.00 0.00 2023-05-29 2023-06-08 2023-06-24 2026-06-08 External Auditor for Three (3) ntation Years as Post Review Activity Page 2 PROCUREMENT PLAN (Textual Part) Project information: [Nigeria] [Innovation Development and Effectiveness in the Acquisition of Skills (IDEAS) Project] [P-166239] Project Implementation Agency: [Federal Ministry of Education] Date of the Procurement Plan: [2109/10/24] Period covered by this Procurement Plan: [October 24, 2019 – April 23, 2020] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017, August 2018 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. - “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables - “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable. Goods: Not Applicable Works: Not Applicable Consultancy: Not Applicable Hands-on Expanded Implementation Support (HEIS): Not Applicable PROCUREMENT Nigeria : Innovation Development and Effectiveness in the Acquisition of Skills (IDEAS) Project PLAN General Information Country: Nigeria 2021-04-29 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166239 GPN Date: Project Name: Innovation Development and Effectiveness in the Acquisition of Skills (IDEAS) Project Loan / Credit No: IDA / 65140 Ekiti IDEAS Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-EKITI IDEAS-232075-CW- Strengthening the regulator Request for Quota RFQ / Upgrading of facilities i y environment and public m Request for Quota Single Stage - One E 2023-03-0 IDA / 65140 Post Limited tions (Non Bank-S 12,500.00 0.00 Signed 2022-07-16 2022-10-31 2022-09-10 n state skills development/SP anagement capacities for m tions nvelope 9 PD) IU offices arket-oriented skills develop ment GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-EKITI IDEAS-231557-GO- Strengthening the regulator RFQ / Provision of teleconfere y environment and public m Request for Quota Single Stage - One E IDA / 65140 Post Limited 20,000.00 0.00 Signed 2022-06-11 2022-10-06 2022-08-06 2023-02-02 ncing facility to SPIU secretar anagement capacities for m tions nvelope iat arket-oriented skills develop ment Strengthening the regulator NG-EKITI IDEAS-231666-GO- y environment and public m Request for Quota Single Stage - One E RFQ / Procurement of project IDA / 65140 Post Limited 65,000.00 77,932.68 Signed 2022-06-18 2022-06-04 2022-08-13 2022-06-22 2023-02-09 anagement capacities for m tions nvelope vehicle for project office arket-oriented skills develop ment Strengthening the regulator NG-EKITI IDEAS-232076-GO- y environment and public m Request for Quota Single Stage - One E RFQ / Procurement of office f IDA / 65140 Post Limited 10,000.00 8,823.46 Signed 2022-05-14 2022-05-26 2022-07-09 2022-06-24 2023-01-05 anagement capacities for m tions nvelope urniture arket-oriented skills develop ment NG-EKITI IDEAS-232077-GO- Strengthening the regulator RFQ / Procurement of 16 Nos y environment and public m Request for Quota Single Stage - One E IDA / 65140 Post Limited 15,000.00 13,770.10 Signed 2022-05-14 2022-06-16 2022-07-09 2022-06-21 2023-01-05 laptops computers and 5 Nos anagement capacities for m tions nvelope printers for SPSC and SPIU m arket-oriented skills develop embers ment Strengthening the regulator NG-EKITI IDEAS-232072-GO- y environment and public m Request for Quota Single Stage - One E RFQ / Procurement of office e IDA / 65140 Post Limited 12,500.00 11,385.35 Signed 2022-05-14 2022-05-26 2022-07-09 2022-06-24 2023-01-05 anagement capacities for m tions nvelope quipment arket-oriented skills develop ment NG-EKITI IDEAS-232104-GO- Strengthening the regulator RFQ / Establishment of Mana y environment and public m Request for Quota Single Stage - One E IDA / 65140 Post Limited 25,000.00 0.00 Canceled 2022-07-16 2022-09-10 2023-03-09 gement Information System ( anagement capacities for m tions nvelope MIS) for State Project Secreta arket-oriented skills develop riat. ment EK/IDEAS/RFQ/01/2023 / Pro Strengthening the regulator curement of 1 no (15 Seater y environment and public m Request for Quota Single Stage - One E IDA / 65140 Post Limited 100,000.00 0.00 Completed 2023-03-15 2023-03-10 2023-05-10 2023-11-06 2023-04-07 Standard Roof) project vehicl anagement capacities for m tions nvelope e for project office. arket-oriented skills develop ment EK/IDEAS/GO/02/2023 / Proc Strengthening the regulator urement of Management Info y environment and public m Request for Quota Single Stage - One E Pending Impl IDA / 65140 Post Limited 40,000.00 0.00 2023-06-06 2023-08-01 2024-01-28 rmation System (EMIS) for tr anagement capacities for m tions nvelope ementation acking of graduates of TVET arket-oriented skills develop ment NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-EKITI IDEAS-231703-CS- Incentivizing partnerships wi CQS / Consultancy for Prepar th industry for enhanced qu ation of Needs Assessment, s Consultant Qualifi IDA / 65140 ality and labour-market orie Post Limited 50,000.00 21,354.75 Signed 2022-04-04 2022-04-23 2022-04-18 2022-05-30 2022-05-18 2022-06-30 2022-06-22 2022-07-24 2022-12-19 tructural/ equipment, specific cation Selection ntation of public Technical C ation, Bill of Quantities and D olleges rawings on selected trades in the 3 GTCs INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strengthening the regulator EK/IDEAS/DS/01/2023 / Enga y environment and public m IDA / 65140 Post Direct Selection Direct - National 5,000.00 0.00 Under Review 2023-03-10 2023-01-24 2023-03-20 2023-05-24 2023-11-20 gement of External Auditor. anagement capacities for m arket-oriented skills develop ment EK/IDEAS/CQS/01/2023 / Eng Incentivizing partnerships wi agement of Project site super th industry for enhanced qu Individual Consult Under Implement visor to oversee the renovati IDA / 65140 ality and labour-market orie Post Limited 17,500.00 0.00 2023-05-15 2023-05-20 2023-06-10 2023-07-15 2024-01-11 ant Selection ation on works at the three Govern ntation of public Technical C ment Technical Colleges. olleges Page 1 Summarized Procurement Plan I. GENERAL Project information: Borrower: Government of Lesotho Project Name: Nutrition and Health Systems Strengthening Project Project ID No: P 170278 Grant No.: Project Implementing Agency: Ministry of Health Bank’s approval Date of the Procurement Plan: Nov 30, 2019 Date of General Procurement Notice: Period covered by this procurement plan: 18 months II. Goods and Works and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by IDA as stated in the Procurement Regulations for IPF Borrowers: Thresholds for Procurement Methods and Prior Review Goods, Works and Non- Consulting Services Procurement Approaches and Methods (US$ Prior millions) Review Category Open Open Request for (US$ millions) International National Quotation (RfQ) Works ≥ 15 ≥7 <7 ≤ 0.2 Goods, IT, and non- ≥4 ≥1 <1 ≤ 0.1 consulting services 2. Reference to (if any) Project Operational/Procurement Manual: The Procurement Plan also forms part of the Project Implementation Manual approved on May 2019. 1 3. Procurement Packages with Methods and Time Schedule Procurement of Goods & Non-consulting Services Summary 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Comments No. Cost Preference by Bank US$ million (yes/no) (Prior / Post) Summary of the ICB Nil Nil NIL Nil (Works) Summary of the NCB Nil Nil NIL Nil NIL (Works) Summary of the ICB NIL NIL NIL NIL NIL (Goods) Summary of the NCB NIL NIL NIL NIL NIL (Goods) Summary of the RfQ 0.042 5 NIL Post Nil (Goods & Non- Consulting Services) Summary of the DC NIL NIL NIL NIL (Non-consulting services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in the Procurement Regulations for IPF Borrowers: Thresholds for Consultants Selection Methods and Prior Review Thresholds for Consultants Selection Methods and Prior Review for Consulting Services Category Prior Short List of National Consultants (US$ million) 2 Review Consulting Engineering and (US$ Services Construction Supervision millions) Consultants (Firms) ≥2 ≤ 0.1 ≤ 0.3 Individual Consultants ≥ 0.4 NA. NA. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of the Procurement Regulations for IPF Borrowers. 3. Terms of Reference (TOR) for all consultancy contracts as well as all direction selections, irrespective of the contract value, will be subject to prior review. 4. Any Other Special Selection Arrangements: N/A 5. Consultancy Assignments with Selection Methods and Time Procurement of Consulting Services Summary 1 2 3 4 5 6 Ref. No. Description of Estimated Package Review Comments Assignment Cost s by Bank (Prior / US$ million Post) Summary of 0.45 1 Post contracts through QCBS Summary of 0.33 3 Post NIL contracts through CQS 3 Summary of 2.7 13 Post NIL contracts through IC 4 PROCUREMENT Lesotho : Lesotho Nutrition and Health System Strengthening Project PLAN General Information Country: Lesotho 2020-02-24 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P170278 GPN Date: Project Name: Lesotho Nutrition and Health System Strengthening Project Loan / Credit No: IDA / V2900, IDA / 69310, TF / B5884 Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-MOH-151702-GO-RFQ / Pr Strengthen Government Ste Request for Quota Single Stage - One E Pending Impl ocurement and supply of PIU IDA / V2900 wardship, Project Manageme Post Open - National 0.00 2020-02-21 2020-03-12 2020-04-26 tions nvelope ementation Office Furnisher nt, and M&E LS-MOH-151703-GO-RFQ / Pr ocurement of computers ( La Strengthen Government Ste Request for Quota Single Stage - One E ptops) installed with OS 10, IDA / V2900 wardship, Project Manageme Post Open - National 12,070.89 Signed 2020-02-21 2020-03-12 2020-06-05 2020-04-21 tions nvelope Microsoft office 2019 and Ant nt, and M&E ivirus supplied with Backpack . LS-MOH-178101-GO-RFQ-LN Strengthen Government Ste HSS / Procurement and suppl Request for Quota Single Stage - One E IDA / V2900 wardship, Project Manageme Post Open - National 0.00 Canceled 2021-07-23 2021-08-21 2021-09-20 y of 6 Laptops, external hard tions nvelope nt, and M&E drives and accossories for PI U Staff under Nutrition LS-MOH-194047-GO-RFQ-LN HSS / Purchasing of Arch File Strengthen Government Ste Request for Quota Single Stage - One E s Storage Shelves and Partiti IDA / V2900 wardship, Project Manageme Post Open - National 11,559.01 Signed 2021-07-30 2021-09-24 2020-10-03 2021-11-23 tions nvelope oning of Store room at procu nt, and M&E rement unit to store project fi les LS-MOH-241141-GO-RFQ-LN Strengthen Government Ste HSS / supply and Delivery of Request for Quota Single Stage - One E IDA / V2900 wardship, Project Manageme Post Open - National 8,763.87 Signed 2021-07-16 2021-08-01 2021-07-08 2021-08-22 four Laptops and accessories tions nvelope nt, and M&E for PIU Staff under Nutrition LS-MOH-151700-GO-RFQ / S District level health system s Request for Quota Single Stage - One E upply and delivery of printed IDA / V2900 Post Open - National 0.00 Canceled 2020-02-14 2020-03-09 2020-04-08 trengthening tions nvelope User Manual for new PBF Mo del LS-MOH-151701-GO-RFQ / Pr Strengthen Government Ste inting of the environmental a Request for Quota Single Stage - One E IDA / V2900 wardship, Project Manageme Post Open - National 0.00 Canceled 2020-04-10 2020-05-04 2020-06-03 nd Social commitment plan a tions nvelope nt, and M&E nd other documents LS-MOH-269356-GO-RFQ-LN Strengthen Government Ste HSS-2022 / Procurement of P Request for Quota Single Stage - One E IDA / 69310 wardship, Project Manageme Post Open - National 0.00 Canceled 2022-11-25 2023-01-20 2023-02-19 rinted QA policy and Strategi tions nvelope nt, and M&E c plan 300 copies LS-MOH-269271-GO-RFB-LN HSS-2022 / Procurement of d Community-Based Health an Single Stage - One E ata capturing tools and SOPs TF / B5884 Post Request for Bids Open - National 0.00 Canceled 2022-05-29 2022-06-03 2022-07-15 2022-08-14 2022-09-18 2023-03-17 d Nutrition Services nvelope (Laminated) for VHW commu nity data monitoring and rec ording tools LS-MOH-269282-GO-RFQ-LN HSS-2022 / Procure Stationer Community-Based Health an Request for Quota Single Stage - One E IDA / 69310 Post Open - National 0.00 Signed 2022-08-12 2022-10-07 2022-12-06 y Extracurricular books and S d Nutrition Services tions nvelope tationery for Peer Educators LS-MOH-269299-GO-RFQ-LN District level health system s Request for Quota Single Stage - One E HSS-2022 / Procure laborator IDA / 69310 Post Open - National 0.00 Canceled 2022-03-18 2022-05-13 2022-07-12 trengthening tions nvelope y equipment for teaching an d learning LS-MOH-269355-GO-RFQ-LN HSS-2022 / Procurement of Strengthen Government Ste Hardware in order to Digitize Request for Quota Single Stage - One E Pending Impl IDA / 69310 wardship, Project Manageme Post Open - National 0.00 2022-04-08 2022-06-03 2022-08-02 M&E system. Use and mainta tions nvelope ementation nt, and M&E in an electronic digitized M& E system in-order to provide real-time information. LS-MOH-269259-GO-RFQ-LN HSS-2022 / Procurement of C Community-Based Health an Request for Quota Open - Internationa Single Stage - One E ovid-19 related supplies-Surv TF / B5884 Post 0.00 Signed 2022-02-04 2022-04-01 2022-05-31 d Nutrition Services tions l nvelope eillance and Case manageme nt for community based inter ventions LS-MOH-269377-GO-RFQ-LN HSS-2022 / procurement and Community-Based Health an Request for Quota Single Stage - One E Pending Impl IDA / 69310 Post Open - National 0.00 2022-04-08 2022-06-03 2022-08-02 supply of Equipment/supplie d Nutrition Services tions nvelope ementation s for functional HRIS LS-MOH-269251-GO-RFQ-LN HSS-2022 / Procurement of p Community-Based Health an Request for Quota Single Stage - One E TF / B5884 Post Open - National 0.00 Canceled 2022-06-05 2022-07-31 2022-09-19 rinting and binding of VWH tr d Nutrition Services tions nvelope aining package (SOP) LS-MOH-269266-GO-RFB-LN HSS-2022 / Procure basic me Community-Based Health an Single Stage - One E Pending Impl TF / B5884 Post Request for Bids Open - National 0.00 2022-01-30 2022-02-04 2022-03-18 2022-04-17 2022-05-22 2022-07-21 dicines for VHWs kit for Com d Nutrition Services nvelope ementation munity interventions Page 1 LS-MOH-269274-GO-RFB-LN HSS-2022 / Procure smart ga dgets for the electronic syste Community-Based Health an Single Stage - One E TF / B5884 Post Request for Bids Open - National 0.00 Canceled 2022-03-27 2022-04-01 2022-05-13 2022-06-12 2022-07-17 2022-09-15 m for community based inter d Nutrition Services nvelope ventions (Phones, Phone cov er and Screen protector, Sola r chargers and8501 Gadgets LS-MOH-269249-GO-RFQ-LN HSS-2022 / Procurement of P Community-Based Health an Request for Quota Single Stage - One E TF / B5884 Post Open - National 0.00 Canceled 2022-05-27 2022-07-22 2022-09-20 rinted training Material for N d Nutrition Services tions nvelope utrition District Trainers LS-MOH-269276-GO-RFQ-LN HSS-2022 / Printing of SOPs Community-Based Health an Request for Quota Single Stage - One E (tools) and SOPs (Laminated) TF / B5884 Post Open - National 0.00 Canceled 2022-08-05 2022-09-30 2022-10-30 d Nutrition Services tions nvelope on how to use the tool, for Vil lage health and Nutrition co mmittees (10,000 copies ) LS-MOH-269288-GO-RFQ-LN HSS-2022 / Procure 2 vehicle Community-Based Health an Request for Quota Single Stage - One E IDA / 69310 Post Open - National 0.00 Canceled 2022-02-11 2022-04-08 2022-06-07 s to support the adolescent p d Nutrition Services tions nvelope rogram as they will be workin g in the community LS-MOH-269302-GO-RFB-LN HSS-2022 / Procurement of e District level health system s Open - Internationa Single Stage - One E Pending Impl IDA / 69310 Post Request for Bids 0.00 2022-09-04 2022-09-09 2022-10-21 2022-11-20 2022-12-25 2023-06-23 quipment for 18 hospitals to trengthening l nvelope ementation enhance the quality of servic es LS-MOH-269265-GO-RFB-LN HSS-2022 / Procurement and Community-Based Health an Open - Internationa Single Stage - One E supply of basic medical equip TF / B5884 Post Request for Bids 0.00 Signed 2022-07-10 2022-07-01 2022-07-15 2022-08-26 2022-08-17 2022-09-25 2022-08-24 2022-10-30 2022-12-25 d Nutrition Services l nvelope ment packed in a Kit for Villa ge Health Workers at Commu nity level. LS-MOH-269263-GO-RFB-LN HSS-2022 / Supply and delive Community-Based Health an Single Stage - One E ry of pharmaceuticals packed TF / B5884 Post Request for Bids Open - National 0.00 Signed 2022-07-18 2022-07-01 2022-07-25 2022-09-05 2022-08-17 2022-10-05 2022-08-24 2022-11-09 2023-01-08 d Nutrition Services nvelope in a Kit for Village health wor kers at Community level. LS-MOH-269363-GO-RFP-LN Community-Based Health an Request for Propo Open - Internationa Single Stage - Two E HSS-2022 / Procure Data Coll IDA / 69310 Post 0.00 Canceled 2022-11-01 2022-11-06 2022-12-18 2023-03-02 2023-04-06 2023-10-03 d Nutrition Services sals l nvelope ection App with annual licens e fees LS-MOH-269285-GO-RFQ-LN Community-Based Health an Request for Quota Single Stage - One E HSS-2022 / Procurement of F IDA / 69310 Post Open - National 0.00 Signed 2022-08-12 2022-10-07 2022-12-06 d Nutrition Services tions nvelope oldable chairs and tables for Peer Educators. LS-MOH-269289-GO-RFQ-LN HSS-2022 / Procurement of P District level health system s Request for Quota Single Stage - One E IDA / 69310 Post Open - National 0.00 Canceled 2022-12-09 2023-02-03 2023-03-05 rinted material, for BFHI guid trengthening tions nvelope elines(SOPs printing and bind ing and Posters ) LS-MOH-361171-GO-RFQ-LN Community-Based Health an Request for Quota Single Stage - One E Pending Impl HSS-2023 / Procurement and IDA / V2900 Post Open - National 0.00 2023-05-23 2023-06-12 2023-09-10 d Nutrition Services tions nvelope ementation Distribution of Peer Educator s PPE LS-MOH-361173-GO-RFQ-LN Community-Based Health an Request for Quota Single Stage - One E Pending Impl HSS-2023 / Procurement of C IDA / V2900 Post Open - National 0.00 2023-05-19 2023-06-04 2023-06-13 d Nutrition Services tions nvelope ementation ustom made Gazebos for Pe er Educators LS-MOH-269297-GO-RFQ-LN District level health system s Request for Quota Single Stage - One E Pending Impl HSS-2022 / Procure Hardwar IDA / 69310 Post Open - National 0.00 2023-08-06 2023-10-01 2023-11-30 trengthening tions nvelope ementation e for Functional LMIS LS-MOH-269277-GO-RFQ-LN HSS-2022 / Procurement of P Community-Based Health an Request for Quota Single Stage - One E Pending Impl IDA / 69310 Post Open - National 0.00 2023-10-06 2023-12-01 2024-01-30 PE for Established herd boys' d Nutrition Services tions nvelope ementation clubs in all the districts LS-MOH-269358-GO-RFQ-LN Strengthen Government Ste Request for Quota Single Stage - One E Pending Impl HSS-2022 / Procurement and IDA / 69310 wardship, Project Manageme Post Open - National 0.00 2023-10-07 2023-12-02 2024-01-01 tions nvelope ementation supply of Printed of 100 AJR nt, and M&E Reports LS-MOH-269258-GO-RFB-LN HSS-2022 / Procure five Doub le Cab 4 by 4 vehicles for Su Community-Based Health an Single Stage - One E Pending Impl TF / B5884 Post Request for Bids Open - National 0.00 2023-08-01 2023-08-06 2023-09-17 2023-10-17 2023-11-21 2024-01-20 pportive Supervision and po d Nutrition Services nvelope ementation st-training follow-up by Distri ct level to the health Centres LS-MOH-269268-GO-RFB-LN HSS-2022 / Procure Nutrition Community-Based Health an Single Stage - One E Pending Impl TF / B5884 Post Request for Bids Open - National 0.00 2023-10-02 2023-10-07 2023-11-18 2023-12-18 2024-01-22 2024-03-22 related commodities for com d Nutrition Services nvelope ementation munity interventions LS-MOH-269269-GO-RFB-LN HSS-2022 / Procure Three Ve Community-Based Health an Single Stage - One E Pending Impl TF / B5884 Post Request for Bids Open - National 0.00 2023-08-01 2023-08-06 2023-09-17 2023-10-17 2023-11-21 2024-05-19 hicles for Community Engage d Nutrition Services nvelope ementation ments with Health Centres NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-MOH-269360-NC-RFQ-LN HSS-2022 / NHTC college we District level health system s Request for Quota Single Stage - One E IDA / 69310 Post Open - National 0.00 Canceled 2022-04-01 2022-05-27 2022-11-23 bsite development including trengthening tions nvelope online Library and research d atabase LS-MOH-269359-NC-RFQ-LN HSS-2022 / Engage an IT Fir District level health system s Request for Quota Single Stage - One E m to Install e-learning platfor IDA / 69310 Post Open - National 0.00 Canceled 2022-02-11 2022-04-08 2022-10-05 trengthening tions nvelope ms: Enterprise resource plan ning system customization a nd system support LS-MOH-269361-NC-RFQ-LN District level health system s Request for Quota Single Stage - One E HSS-2022 / Engage an IT Fir IDA / 69310 Post Open - National 0.00 Canceled 2022-05-27 2022-07-22 2023-01-18 trengthening tions nvelope m to Revamp NHTC ICT infra structure Page 2 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-MOH-151706-CS-CQS / En gage a consultant to carry ou District level health system s Consultant Qualifi Open - Internationa IDA / V2900 Post 0.00 Canceled 2020-03-29 2020-02-27 2020-04-19 2020-02-27 2020-06-02 2020-07-02 2020-08-06 2021-02-02 t Baseline Study on hospital trengthening cation Selection l assessment and equipment g ap assessment LS-MOH-185617-CS-QCBS-L NHSS / Consultant to assist M District level health system s Quality And Cost- Open - Internationa Under Implement inistry of health on analysis o IDA / V2900 Post 0.00 2021-07-25 2020-01-29 2021-08-15 2021-09-28 2020-07-22 2021-10-26 2021-11-25 2021-12-30 2022-02-03 2022-08-02 trengthening Based Selection l ation f Quality and Outcome indica tors for regional and District hospitals in Lesotho LS-MOH-151710-CS-CQS / C onsultancies for Financial ma District level health system s Consultant Qualifi Open - Internationa IDA / V2900 Post 0.00 Canceled 2020-03-08 2020-03-29 2020-05-12 2020-06-11 2020-07-16 2021-01-12 nagement support and strate trengthening cation Selection l gic purchasing of health servi ces for MOH LS-MOH-151704-CS-QCBS / Engage a consultancy firm to Community-Based Health an Quality And Cost- Open - Internationa IDA / V2900 Post 0.00 Canceled 2020-02-23 2020-03-15 2020-04-28 2020-05-26 2020-06-25 2020-07-30 2020-09-03 2020-12-02 develop and implement an el d Nutrition Services Based Selection l ectronic CMIS for VHW ( Link to DHIS2) LS-MOH-269353-CS-CQS-LN District level health system s Consultant Qualifi Pending Impleme HSS-2022 / Engage Consulta IDA / 69310 Post Open - National 0.00 2024-01-01 2024-01-22 2024-03-06 2024-04-05 2024-05-10 2024-11-06 trengthening cation Selection ntation ncy firm for KAP study INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strengthen Government Ste LS-MOH-152162-CS-INDV / P Individual Consult IDA / V2900 wardship, Project Manageme Post Open 0.00 Canceled 2020-01-19 2020-03-08 2020-03-29 2020-05-03 2025-04-07 roject Coordinator ant Selection nt, and M&E Strengthen Government Ste LS-MOH-152163-CS-INDV / P Individual Consult IDA / V2900 wardship, Project Manageme Post Open 0.00 Canceled 2020-01-26 2020-03-15 2020-04-05 2020-05-10 2025-04-14 rocurement Assistant ant Selection nt, and M&E Strengthen Government Ste LS-MOH-152165-CS-INDV / P Individual Consult IDA / V2900 wardship, Project Manageme Post Open 0.00 Canceled 2020-01-19 2020-03-08 2020-03-29 2020-05-03 2025-04-07 rocurement Specialist ant Selection nt, and M&E LS-MOH-152166-CS-INDV / E Strengthen Government Ste Individual Consult nvironmental and Social Safe IDA / V2900 wardship, Project Manageme Post Open 0.00 Canceled 2020-01-19 2020-03-08 2020-03-29 2020-05-03 2025-04-07 ant Selection guard Specialist nt, and M&E Strengthen Government Ste LS-MOH-152194-CS-INDV / E Individual Consult IDA / V2900 wardship, Project Manageme Post Open 0.00 Canceled 2020-02-16 2020-04-05 2020-04-26 2020-05-31 2025-05-05 ngage Heath Economist ant Selection nt, and M&E LS-MOH-152197-CS-INDV / C onsultancy for GBV SEA risk assessment and Action Plan Community-Based Health an Individual Consult IDA / V2900 Post Open 0.00 Signed 2020-03-15 2020-02-27 2020-05-03 2020-08-04 2020-05-24 2020-08-05 2020-06-28 2020-12-25 Training of Affected Stakehol d Nutrition Services ant Selection ders Specialist to conduct inc luding institutional capacity. LS-MOH-230298-CS-INDV-LN HSS / Engage individual Cons Strengthen Government Ste Individual Consult ultant to Develop Project Imp IDA / V2900 wardship, Project Manageme Post Open 0.00 Under Review 2021-07-25 2020-02-03 2021-08-20 2021-08-27 2021-09-08 2021-10-28 ant Selection lementation Manual for Lesot nt, and M&E ho Nutrition health system St rengthening Project LS-MOH-242345-CS-INDV-LN HSS / Engagement of a Cons ultant for Development of a d District level health system s Individual Consult Under Implement IDA / V2900 Post Open 0.00 2021-07-25 2021-07-15 2021-09-12 2021-09-07 2021-09-26 2021-09-20 2021-10-24 2022-01-22 igital application for The Leso trengthening ant Selection ation tho Nutrition and Health Syst em Strengthening Project . LS-MOH-242366-CS-INDV-LN HSS / Engagement of Individ District level health system s Individual Consult ual Consultant to advice and IDA / V2900 Post Open 0.00 Canceled 2021-07-25 2021-07-15 2021-09-03 2021-09-17 2021-10-15 2022-10-15 trengthening ant Selection support towards healthcare q uality grant and bonus mains treaming in Lesotho LS-MOH-152192-CS-INDV-LN Strengthen Government Ste Individual Consult Under Implement HSS / Engage a Nutrition Spe IDA / V2900 wardship, Project Manageme Post Open 0.00 2021-08-01 2020-04-14 2021-09-19 2020-05-12 2021-10-10 2020-05-13 2021-11-14 2023-11-14 ant Selection ation cialist for 24 months nt, and M&E LS-MOH-151709-CS-INDV / C onsultant to help MOH to dev elop or approve or implemen Community-Based Health an Individual Consult IDA / V2900 Post Open 0.00 Canceled 2020-05-05 2020-06-23 2020-07-14 2020-08-18 2020-09-02 t referral guidelines for provi d Nutrition Services ant Selection ders to refer patients across l evels of care and for treatme nt abroad. LS-MOH-151708-CS-INDV / E Strengthen Government Ste Individual Consult ngage Individual Consultant f IDA / V2900 wardship, Project Manageme Post Open 0.00 Canceled 2020-03-31 2020-05-19 2020-06-09 2020-07-14 2020-07-26 ant Selection or Annual Joint Review nt, and M&E LS-MOH-269365-CS-INDV-LN HSS-2022 / Engage consultan District level health system s Individual Consult IDA / 69310 Post Open 0.00 Canceled 2022-05-22 2022-07-10 2022-07-31 2022-09-04 2023-03-03 t to review, update and finali trengthening ant Selection se maternity protection bill r egulations. LS-MOH-269367-CS-INDV-LN HSS-2022 / Engage a consult ant for Development of a we District level health system s Individual Consult IDA / 69310 Post Open 0.00 Canceled 2022-01-30 2021-07-14 2022-03-20 2022-04-10 2022-05-15 2022-11-11 b-based module to report an trengthening ant Selection d track quality payments and indicator results by health fa cilities. Page 3 LS-MOH-269364-CS-INDV-LN HSS-2020 / Engage A consult ant to adapt the design, impl District level health system s Individual Consult IDA / 69310 Post Open 0.00 Canceled 2022-05-01 2022-06-19 2022-07-10 2022-08-14 2022-11-12 ementation, and M&E of both trengthening ant Selection quality and bonus payments while using the recurrent bud get for quality grants LS-MOH-269366-CS-INDV / E ngage consultant to review, District level health system s Individual Consult Under Implement IDA / 69310 Post Open 0.00 2022-03-06 2023-03-02 2022-04-24 2022-05-15 2022-06-19 2022-12-16 update and finalise Code of trengthening ant Selection ation marketing of breastmilk subs titute LS-MOH-269372-CS-INDV-LN Strengthen Government Ste HSS-2022 / Local consultant t Individual Consult IDA / 69310 wardship, Project Manageme Post Open 0.00 Canceled 2022-06-05 2022-07-24 2022-08-14 2022-09-18 2023-03-17 o develop key health and nut ant Selection nt, and M&E rition related SBCC messages LS-MOH-269374-CS-INDV-LN Strengthen Government Ste HSS-2022 / Engage a Techni Individual Consult IDA / 69310 wardship, Project Manageme Post 0.00 Canceled 2022-08-01 2022-09-19 2022-10-10 2022-11-14 2023-05-13 cal Assistant to develop guid ant Selection nt, and M&E elines for strategic purchasin g of health services LS-MOH-269375-CS-INDV-LN Strengthen Government Ste HSS-2022 / Engage a Techni Individual Consult IDA / 69310 wardship, Project Manageme Post Open 0.00 Canceled 2022-05-01 2022-06-19 2022-07-10 2022-08-14 2023-02-10 cal Assistant to structure pay ant Selection nt, and M&E ment mechanism and develo p SOPs LS-MOH-269373-CS-INDV-LN Strengthen Government Ste Individual Consult HSS-2022 / Engage Quality A IDA / 69310 wardship, Project Manageme Post Open 0.00 Canceled 2022-05-16 2023-05-10 2022-07-04 2022-07-25 2022-08-29 2023-02-25 ant Selection ssurance Specialist nt, and M&E LS-MOH-309174-CS-INDV-LN HSS-2022 / Engagement of In dividual Consultant to provid District level health system s Individual Consult IDA / V2900 Post Open - National 0.00 Canceled 2022-09-11 2023-03-06 2022-10-30 2022-11-20 2022-12-25 2023-06-23 e consultancy services on est trengthening ant Selection ablishing and implementing t he Baby-Friendly Hospital Init iatives (BFHI) in Lesotho. LS-MOH-309177-CS-INDV-LN HSS-2022 / Engage Individual District level health system s Individual Consult Consultant to finalize and im IDA / V2900 Post Open - National 0.00 Canceled 2022-08-31 2023-03-06 2022-10-19 2022-11-09 2022-12-14 2023-06-12 trengthening ant Selection plement the code of marketi ng of breast milk substitutes LS-MOH-334384-CS-CDS-LN HSSP-2022 / Training of four Strengthen Government Ste Pending Impleme officers on Monitoring & Eval IDA / 69310 wardship, Project Manageme Post Direct Selection Direct - National 0.00 2023-01-29 2023-02-08 2023-04-14 2023-10-11 ntation uation in the Health Sector s nt, and M&E hort course in South Africa. LS-MOH-334385-CS-INDV-LN HSSP-2022 / Engage an indivi District level health system s Individual Consult Under Implement IDA / 69310 Post Open - National 0.00 2023-01-22 2022-11-10 2023-03-12 2023-02-17 2023-04-02 2023-02-20 2023-05-07 2023-11-03 dual consultant to assist the trengthening ant Selection ation health institutions to review t he Curricula LS-MOH-344860-CS-INDV-LN HSSP-PIU-2023 / Engagement Strengthen Government Ste Individual Consult Under Implement of Social Specialist under Min IDA / V2900 wardship, Project Manageme Post Open - National 0.00 2023-03-10 2023-04-04 2023-04-12 2023-04-15 2023-04-23 2026-04-07 ant Selection ation istry of Health Project Imple nt, and M&E menting Unit for 36 months. LS-MOH-269371-CS-INDV-LN HSS-2022 / International/regi Strengthen Government Ste Individual Consult Open - Internationa Pending Impleme onal consultant to assist FNC IDA / 69310 wardship, Project Manageme Post 0.00 2023-08-01 2023-09-19 2023-10-10 2023-11-14 2024-05-12 ant Selection l ntation O to develop an M&E Plan an nt, and M&E d nutrition information syste ms LS-MOH-269368-CS-INDV-LN HSS-2022 / Engage an IT Con District level health system s Individual Consult Pending Impleme sultant who will support recu IDA / 69310 Post Open - National 0.00 2023-08-01 2023-09-19 2023-10-10 2023-11-14 2024-05-12 trengthening ant Selection ntation rring transitional requirement s of an open source system u nder HRIS. LS-MOH-309176-CS-INDV-LN HSS-2022 / Engagement of In Strengthen Government Ste Individual Consult Open - Internationa Pending Impleme dividual Consultant (Health E IDA / V2900 wardship, Project Manageme Post 0.00 2023-08-01 2023-09-19 2023-10-10 2023-11-14 2024-02-12 ant Selection l ntation conomist) to Support Strategi nt, and M&E c Purchasing of Health Servic es LS-MOH-269369-CS-INDV-LN District level health system s Individual Consult Pending Impleme HSS-2022 / Engage the syst IDA / 69310 Post Open - National 0.00 2022-03-01 2022-04-19 2022-05-10 2022-06-14 2022-12-11 trengthening ant Selection ntation em developer LS-MOH-367141-CS-CDS-LN HSS-2023 / Engagement of a Community-Based Health an Under Implement IDA / V2900 Prior Direct Selection Direct - National 0.00 2023-07-16 2023-07-26 2023-09-29 2025-07-31 n NGO to implement commu d Nutrition Services ation nity level activities. Page 4 PROCUREMENT PLAN (Textual Part) Project information: Khyber Pakhtunkhwa Irrigated Agriculture Improvement Project (P163474) Project Implementation agency: Directorate General of On-Farm Water Management Government of Khyber Pakhtunkhwa Date of the Procurement Plan: September 1, 2020 Period covered by this Procurement Plan: September 2020- June 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Public Procurement Rules 2004 Revised 2020, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 2) For national open competitive procurement, only the model procurement documents acceptable to the World Bank, shall be used. 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 5) Access to procurement opportunities shall not be restricted to firms that have pre-registered and/or paid a registration fee. 6) No preference of any kind shall be given to national bidders in the bidding process. 7) Procurement methods that use two-envelope process and rated criteria shall be subject to Bank’s prior concurrence When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact- finding activities undertaken by the Bank or persons appointed by the Bank to address specific the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Pakistan : Khyber Pakhtunkhwa Irrigated-Agriculture Improvement Project PLAN General Information Country: Pakistan 2020-09-05 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163474 GPN Date: 2020-09-07 Project Name: Khyber Pakhtunkhwa Irrigated-Agriculture Improvement Project Loan / Credit No: IDA / 64560 Directorate General of On-Farm Water Management Government of Khyber Pakhtunkhwa Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-DGOFWM-KP-231231-GO- Project Management and Mo Request for Quota Single Stage - One E IDA / 64560 Post Open - National 10,715.00 9,707.15 Completed 2021-05-08 2021-07-03 2021-05-22 2021-12-30 2021-05-28 RFQ / Renovation of Director nitoring tions nvelope ate (PIU) PK-DGOFWM-KP-233768-GO- Project Management and Mo Request for Quota Single Stage - One E IDA / 64560 Post Open - National 21,428.00 15,138.77 Completed 2021-06-06 2021-11-15 2021-08-01 2021-12-31 2022-01-28 2022-04-20 RFQ / Procurement of Furnitu nitoring tions nvelope re PK-DGOFWM-KP-233767-GO- Project Management and Mo Request for Quota Single Stage - One E IDA / 64560 Post Open - National 1,678,571.00 0.00 Canceled 2021-06-02 2021-07-28 2022-01-24 RFB / procurement of vehicle nitoring tions nvelope s PK-DGOFWM-KP-244288-GO- Project Management and Mo Request for Quota Single Stage - One E IDA / 64560 Post Open - National 1,678,571.00 1,151,063.27 Completed 2021-07-24 2021-09-12 2021-09-07 2022-03-11 2022-05-19 RFQ / Procurement of Vehicle nitoring tions nvelope s PK-DGOFWM-KP-247862-GO- Project Management and Mo Single Stage - One E IDA / 64560 Post Request for Bids Open - National 227,000.00 0.00 Canceled 2021-08-30 2021-09-04 2021-10-16 2021-11-15 2021-12-20 2022-06-18 RFB / Procurement of Survey nitoring nvelope Equipment PK-DGOFWM-KP-248035-GO- RFQ / Procurement of Solaris Project Management and Mo Request for Quota Single Stage - One E IDA / 64560 Post Open - National 28,571.43 18,928.72 Completed 2021-09-04 2022-03-23 2021-10-30 2022-04-26 2022-04-28 2022-06-04 ation and Security System fo nitoring tions nvelope r PIU & Training Centre PK-DGOFWM-KP-248038-GO- RFQ / Complete Set of Qualit Project Management and Mo Request for Quota Single Stage - One E IDA / 64560 Post Open - National 17,857.14 0.00 Canceled 2021-09-06 2021-11-01 2022-04-30 y Testing Laboratory for Trai nitoring tions nvelope ning Centre at DI Khan PK-DGOFWM-KP-253118-GO- RFQ / Procurement of IT Equi pments Lot 1 : Desktop Computer wit h Accessories Project Management and Mo Request for Quota Single Stage - One E IDA / 64560 Post Open - National 87,500.00 0.00 Canceled 2021-10-18 2022-06-02 2021-12-07 2022-02-05 Lot 2 : Laptop Computer nitoring tions nvelope Lot 3 : Software Bundles Lot 4 : Printers Lot 5 : Multimedia Projector Lot 6 : Fax Machine Lot 7 : Work Station (Photo C opier) PK-DGOFWM-KP-253121-GO- RFQ / Procurement of Office Equipments : Lot 1: Water Dispenser Project Management and Mo Request for Quota Single Stage - One E IDA / 64560 Post Open - National 42,035.71 3,829.12 Completed 2021-10-23 2022-06-03 2021-12-12 2022-06-28 2022-01-31 2022-07-09 Lot 2: Air Conditioner nitoring tions nvelope Lot 3: Generator 100 KVA Lot 4: UPS Lot 5: Refrigerator PK-DGOFWM-KP-253122-GO- RFB / Procurement of Field M easurement & Testing Instru Project Management and Mo Single Stage - One E ments : IDA / 64560 Post Request for Bids Open - National 155,892.86 0.00 Canceled 2021-10-15 2021-10-20 2021-11-04 2021-11-25 2021-12-12 2022-03-12 nitoring nvelope Lot 1 Flow Watch Lot 2 Flow Tech/Current Mete r Lot 3 Steel Horse Plate Comp actor PK-DGOFWM-KP-297205-GO- Lot 4 Smith Hammers RFQ / Procurement of Field E Project Management and Mo Request for Quota Single Stage - One E IDA / 64560 Post Open - National 41,142.86 17,123.06 Completed 2022-06-11 2022-06-07 2022-07-23 2022-08-11 2023-01-19 2022-09-26 quipment nitoring tions nvelope "Dumpy Levels" and "Smith Hammers" for district offices PK-DGOFWM-KP-321672-GO- DIR / Procurement of Wheat Contingent Emergency Resp Seeds for Flood Affected Far IDA / 64560 Post Direct Selection Direct - National 1,910,000.00 0.00 Completed 2022-10-17 2022-10-18 2022-10-19 2022-10-19 2022-10-23 2022-12-22 2022-11-26 onse mers of Khyber Pakhtunkhwa from Punjab Seed Corporatio n PK-DGOFWM-KP-323954-GO- RFQ / Fruit Flies Management Contingent Emergency Resp Request for Quota Single Stage - One E IDA / 64560 Post Limited 1.70 0.00 Signed 2022-11-04 2023-01-31 2022-11-16 2023-02-14 practices: onse tions nvelope Procurement of Fruit Fly Trap s along with Chemicals PK-DGOFWM-KP-323958-GO- RFQ / Procurement of Bio Fer Contingent Emergency Resp Request for Quota Single Stage - One E IDA / 64560 Post Limited 0.30 0.00 Canceled 2022-11-04 2022-12-15 2022-11-17 2023-02-15 tilizer: onse tions nvelope (Green Soil) Trichodermaharz ianum Strain (G8) PK-DGOFWM-KP-323985-GO- Contingent Emergency Resp Request for Quota Single Stage - One E Pending Impl RFQ / Procurement of Livesto IDA / 64560 Post Limited 0.34 0.00 2022-11-11 2022-11-22 2023-02-20 onse tions nvelope ementation ck Feed i.e Wheat Straw . PK-DGOFWM-KP-323987-GO- Contingent Emergency Resp Request for Quota Single Stage - One E Pending Impl RFQ / Procurement of Live St IDA / 64560 Post Limited 0.43 0.00 2022-11-11 2022-11-22 2023-02-20 onse tions nvelope ementation ock Feed i.e "Concentrated F eed" PK-DGOFWM-KP-323988-GO- Contingent Emergency Resp Request for Quota Single Stage - One E Pending Impl RFQ / Procurement of Livesto IDA / 64560 Post Limited 1.06 0.00 2022-11-11 2022-11-22 2023-02-20 onse tions nvelope ementation ck Feed i.e "Silage" Page 1 PK-DGOFWM-KP-323992-GO- RFQ / Procurement of Vaccin Contingent Emergency Resp Request for Quota Single Stage - One E Pending Impl es for Lumpy Skin Dieses and IDA / 64560 Post Limited 0.72 0.00 2022-11-23 2022-12-06 2023-03-06 onse tions nvelope ementation accessories including syringe s, storage boxes for vaccines PK-DGOFWM-KP-323993-GO- RFQ / Procurement of Vaccin Contingent Emergency Resp Request for Quota Single Stage - One E Pending Impl es for Foot Mouth Disease of IDA / 64560 Post Limited 1.13 0.00 2022-11-23 2022-12-06 2023-03-06 onse tions nvelope ementation Livestock and accessories (S yringes and Storage Box) PK-DGOFWM-KP-323994-GO- RFQ / Procurement of Livesto Contingent Emergency Resp Request for Quota Single Stage - One E Pending Impl ck Medicines : Control of Inte IDA / 64560 Post Limited 0.54 0.00 2022-11-23 2022-12-06 2023-03-06 onse tions nvelope ementation rnal Parasites for Cows and B uffalos along with drenchers PK-DGOFWM-KP-323998-GO- RFQ / Procurement of Livesto Contingent Emergency Resp Request for Quota Single Stage - One E Pending Impl IDA / 64560 Post Limited 0.32 0.00 2022-11-23 2022-12-06 2023-03-06 ck Medicines for Internal Para onse tions nvelope ementation site of Sheep and Goats alon g with Drenchers PK-DGOFWM-KP-323999-GO- RFQ / Procurement of Live St Contingent Emergency Resp Request for Quota Single Stage - One E Pending Impl ock Medicines for External Pa IDA / 64560 Post Limited 0.08 0.00 2022-11-23 2022-12-06 2023-03-06 onse tions nvelope ementation rasites of Cow, Buffalos, ,She eps and Goats along with Spr ay pumps NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-DGOFWM-KP-321673-NC- Contingent Emergency Resp Request for Quota Single Stage - One E RFQ / Transportation of Whea IDA / 64560 Post Limited 43,000.00 0.00 Completed 2022-10-22 2022-10-19 2022-11-01 2023-01-15 2022-11-26 onse tions nvelope t Seeds and Temporary Stora ge Facility PK-DGOFWM-KP-346466-NC- RFQ / Procurement of Digital Capacity Building and Establ Request for Quota Single Stage - One E Under Imple Financial Management and P IDA / 64560 ishing Knowledge Base for F Post Open - National 26,800.00 0.00 2023-03-08 2023-04-17 2023-10-14 tions nvelope mentation hysical Progress Reporting S uture Inclusive Growth ystem & related Services for KPIAIP CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-DGOFWM-KP-177909-CS- QCBS / Selection of Project S Project Management and Mo Quality And Cost- IDA / 64560 Prior Open - National 5,214,285.00 2,506,894.63 Signed 2020-09-15 2020-09-09 2020-10-06 2021-03-19 2020-11-19 2021-12-29 2020-12-17 2022-02-17 2021-01-16 2022-05-07 2021-02-20 2022-05-31 2021-03-27 2022-06-21 2025-12-31 upervision and Implementati nitoring Based Selection on Assistance Consultants PK-DGOFWM-KP-221723-CS- Project Management and Mo Quality And Cost- Open - Internationa QCBS / Selection of Project M IDA / 64560 Prior 1,071,429.00 0.00 Signed 2021-04-26 2021-09-23 2021-05-17 2021-10-22 2021-06-30 2022-03-21 2021-07-28 2022-05-11 2021-08-27 2022-08-29 2021-10-01 2022-10-12 2021-11-05 2025-06-30 nitoring Based Selection l onitoring and Evaluation Con sultant INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-DGOFWM-KP-190207-CS-I Project Management and Mo Individual Consult IDA / 64560 Post Open 92,571.00 24,554.21 Signed 2020-09-15 2020-10-22 2020-11-03 2021-07-15 2020-11-24 2021-07-15 2020-12-29 2021-08-06 2025-12-31 NDV / Hiring of Procurement nitoring ant Selection Specialist PK-DGOFWM-KP-190219-CS-I Project Management and Mo Individual Consult IDA / 64560 Post Open 92,571.00 24,561.39 Signed 2020-09-15 2020-10-22 2020-11-03 2021-06-03 2020-11-24 2021-08-09 2020-12-29 2021-08-29 2025-12-31 NDV / Hiring of M & E Speciali nitoring ant Selection st PK-DGOFWM-KP-190224-CS-I Project Management and Mo Individual Consult NDV / Hiring of Social and Ge IDA / 64560 Post Open 92,571.00 24,561.39 Signed 2020-09-15 2020-10-22 2020-11-03 2021-06-03 2020-11-24 2021-06-08 2020-12-29 2021-07-09 2025-12-31 nitoring ant Selection nder Specialist PK-DGOFWM-KP-190331-CS-I Project Management and Mo Individual Consult IDA / 64560 Post Open 92,571.00 24,970.26 Signed 2020-09-15 2020-10-22 2020-11-03 2021-06-03 2020-11-24 2021-06-03 2020-12-29 2021-08-06 2025-12-31 NDV / Hiring of Environmenta nitoring ant Selection l specialist PK-DGOFWM-KP-190936-CS-I Project Management and Mo Individual Consult IDA / 64560 Post Open 64,286.00 24,561.39 Signed 2020-09-15 2020-10-22 2020-11-03 2021-06-03 2020-11-24 2021-06-03 2020-12-29 2021-07-09 2025-12-31 NDV / Hiring of IT & MIS Spec nitoring ant Selection ialist PK-DGOFWM-KP-201057-CS-I Project Management and Mo Individual Consult IDA / 64560 Post Open 92,571.00 24,561.39 Signed 2020-10-26 2020-10-28 2020-12-14 2021-06-08 2021-01-04 2021-06-08 2021-02-08 2021-08-06 2022-02-08 NDV / Hiring of Agribusiness nitoring ant Selection Specialist PK-DGOFWM-KP-239533-CS-I Project Management and Mo Individual Consult NDV / Hiring of Communicati IDA / 64560 Post Open 120,000.00 92,231.66 Signed 2021-06-18 2021-10-11 2021-08-06 2022-03-16 2021-08-27 2022-03-16 2021-10-01 2022-04-02 2025-06-30 nitoring ant Selection on Specialist PK-DGOFWM-KP-239472-CS-I Project Management and Mo Individual Consult NDV / Hiring of Financial Man IDA / 64560 Post Open 120,000.00 1,897.53 Signed 2021-10-12 2021-10-11 2021-11-01 2022-03-10 2021-11-04 2022-03-11 2021-11-28 2022-04-02 2025-06-29 nitoring ant Selection agement Specialist PK-DGOFWM-KP-361951-CS-I NDV / Hiring of Individual Co nsultant for CERC Impact Ana Contingent Emergency Resp Individual Consult Under Implement IDA / 64560 Post Direct - National 4,140.00 0.00 2023-05-18 2023-05-30 2023-05-24 2023-05-31 2023-05-29 2023-05-31 2023-07-03 2023-09-30 lysis and Monitoring Under C onse ant Selection ation omponent "E". Contingent E mergency Response Compon ent of the Project KP-IAIP Page 2 PROCUREMENT PLAN (Textual Part) Project Country: Republic of Tajikistan information Full Project Name: TAJIKISTAN RESILIENT IRRIGATION (project preparation) Total Finance ($): USD 0,517 million Project Number: P175356 Project Implementation agency Agency on Land Reclamation and Irrigation Date of the Procurement Plan November 17, 2021 (initial) Period covered by this Procurement Project preparation duration (till Plan: June 30, 2022) Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017, August 2018, and November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), procurement under World Bank financed operations may be carried out in accordance with “Tendering with Unlimited Participation” method set forth in the Law of the Republic of Tajikistan “Оn Public Procurement of Goods, Works and Services”, # 168 dated March 3, 2006 (as amended by Law #815, the “Law of the Republic of Tajikistan on “Introduction of Amendments and Additions to the Law of the Republic of Tajikistan on ‘Public Procurement of Goods, Works and Services’” dated April 16, 2012), provided that such arrangements continue to meet requirements of the paragraph 5.4 of the Procurement Regulations and the following conditions: • The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; • The request for bids/request for proposals document, including contract forms, acceptable to the Bank shall be used. • Borrower shall put in place an effective complaints review mechanism with procurement related complaints, and shall disclose the details in all the bidding documents. All complaints shall be recorded by the Borrower in the appropriate tracking and monitoring system, as agreed between the Bank and the Borrower. • No preference shall be applied under competitive bidding following national market approach. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Other national procurement arrangements such as as tendering with limited participation, request for quotations, direct contracting, may be used on the above stated conditions. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works): “Not Applicable” PROCUREMENT Tajikistan : Tajikistan Strengthening Water and Irrigation Management Project PLAN General Information Country: Tajikistan 2021-11-19 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175356 GPN Date: 2022-08-22 Project Name: Tajikistan Strengthening Water and Irrigation Management Project Loan / Credit No: / , IDA / E0790 Project Management Unit for the “Fergana Valley Water Resources Management Project” Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SWIM-CW-RFQ-01 / Reconstr Request for Quota uction of administrative build Water Sector Reform and Ins Request for Quota Single Stage - One E Pending Imp 2023-09-2 IDA / E0790 Post Open - National tions (Non Bank-S 150,000.00 0.00 2023-02-04 2023-04-01 ings of the Vakhsh , Shuroba titutional Strengthening tions nvelope lementation 8 PD) d scheme organizations and SDLRI in BHC National Procure SWIM-CW-NCB-03 / Canal O Irrigation Scheme Improvem Single Stage - One E ment Document - Pending Imp 2024-06-2 IDA / E0790 Post Request for Bids Open - National 850,000.00 0.00 2023-09-04 2023-09-09 2023-10-21 2023-11-20 2023-12-25 MC ents nvelope 1 Envelope proce lementation 2 ss (Non Bank-SPD ) National Procure SWIM-CW-NCB-04 / Central c Irrigation Scheme Improvem Single Stage - One E ment Document - Pending Imp 2024-07-0 IDA / E0790 Post Request for Bids Open - National 265,000.00 0.00 2023-09-20 2023-09-25 2023-11-06 2023-12-06 2024-01-10 anal system ents nvelope 1 Envelope proce lementation 8 ss (Non Bank-SPD ) National Procure SWIM-CW-NCB-07 / Jilikul Kof Irrigation Scheme Improvem Single Stage - One E ment Document - Pending Imp 2025-02-2 IDA / E0790 Post Request for Bids Open - National 1,340,000.00 0.00 2024-05-06 2024-05-11 2024-06-22 2024-07-22 2024-08-26 ir canal ents nvelope 1 Envelope proce lementation 2 ss (Non Bank-SPD ) Request for Quota SWIM-CW-RFQ-02 / PMU offic Request for Quota Single Stage - One E Pending Imp 2024-08-1 IDA / E0790 Project Management Post Open - National tions (Non Bank-S 65,000.00 0.00 2023-12-20 2024-02-14 e renovation tions nvelope lementation 2 PD) National Procure SWIM-CW-NCB-02 / Rehabilit ment Document - ation of head water intake fa Irrigation Scheme Improvem Single Stage - One E Pending Imp 2025-03-0 IDA / E0790 Post Request for Bids Open - National 1 Envelope proce 800,000.00 0.00 2024-05-20 2024-05-25 2024-07-06 2024-08-05 2024-09-09 cilities at PK33 in the system ents nvelope lementation 8 ss (Non Bank-SPD of Vakhsh, Shurabad main ca ) nals National Procure SWIM-CW-NCB-05 / Rehabilit ment Document - ation of the subsystem of the Irrigation Scheme Improvem Single Stage - One E Pending Imp 2025-02-1 IDA / E0790 Post Request for Bids Open - National 1 Envelope proce 2,175,000.00 0.00 2024-04-29 2024-05-04 2024-06-15 2024-07-15 2024-08-19 Northern branch in the syste ents nvelope lementation 5 ss (Non Bank-SPD m of the Vakhsh main canal ) National Procure SWIM-CW-NCB-06 / Rehabilit ment Document - ation of the subsystem Canal Irrigation Scheme Improvem Single Stage - One E Pending Imp 2025-02-1 IDA / E0790 Post Request for Bids Open - National 1 Envelope proce 1,825,000.00 0.00 2024-04-30 2024-05-05 2024-06-16 2024-07-16 2024-08-20 L-2 Head in the system of the ents nvelope lementation 6 ss (Non Bank-SPD Vakhsh main canal ) Request for Bids - SWIM-CW-ICB-01 / Rehabilita Irrigation Scheme Improvem Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2025-02-1 tion VMK system subsystem IDA / E0790 Post Request for Bids 5,675,000.00 0.00 2024-05-01 2024-05-06 2024-06-17 2024-07-17 2024-08-21 ents l nvelope (1 envelope proce lementation 7 Kumsangir canal ss) National Procure SWIM-CW-NCB-08 / Rehabilit Irrigation Scheme Improvem Single Stage - One E ment Document - Pending Imp 2025-01-2 ation of Shurobad main canal IDA / E0790 Post Request for Bids Open - National 1,215,000.00 0.00 2024-04-10 2024-04-15 2024-05-27 2024-06-26 2024-07-31 ents nvelope 1 Envelope proce lementation 7 system ss (Non Bank-SPD National ) Procure SWIM-CW-NCB-011 / Critical ment Document - Irrigation Scheme Improvem Single Stage - One E Pending Imp 2024-09-1 reconstruction of the Beshke IDA / E0790 Post Request for Bids Open - National 1 Envelope proce 500,000.00 0.00 2023-12-01 2023-12-06 2024-01-17 2024-02-16 2024-03-22 ents nvelope lementation 8 nt hydroelectric complex ss (Non Bank-SPD ) SWIM-CW-NCB-014 / SCADA National Procure system design, supply, install ment Document - Irrigation Scheme Improvem Single Stage - One E Pending Imp 2024-04-2 ation and commissioning of IDA / E0790 Post Request for Bids Open - National 1 Envelope proce 200,000.00 0.00 2023-07-03 2023-07-08 2023-08-19 2023-09-18 2023-10-23 ents nvelope lementation 0 main water intakes, control g ss (Non Bank-SPD ates and pumping stations ) National Procure SWIM-CW-NCB-09 / Rehabilit Irrigation Scheme Improvem Single Stage - One E ment Document - Pending Imp 2024-03-3 ation of the Dangara Main Ca IDA / E0790 Post Request for Bids Open - National 252,000.00 0.00 2023-06-12 2023-06-17 2023-07-29 2023-08-28 2023-10-02 ents nvelope 1 Envelope proce lementation 0 nal (DMK) ss (Non Bank-SPD ) National Procure SWIM-CW-NCB-01 / Reconstr ment Document - uction of mechanical repair/p Irrigation Scheme Improvem Single Stage - One E Pending Imp 2025-11-0 IDA / E0790 Post Request for Bids Open - National 1 Envelope proce 700,000.00 0.00 2025-01-13 2025-01-18 2025-03-01 2025-03-31 2025-05-05 ump shop with installation of ents nvelope lementation 1 ss (Non Bank-SPD equipment in Lower Vakhsh ) and Upper Kafernigan National Procure SWIM-CW-NCB-010 / Rehabil ment Document - Irrigation Scheme Improvem Single Stage - One E Pending Imp 2024-09-2 itation of Dangara Irrigation t IDA / E0790 Post Request for Bids Open - National 1 Envelope proce 1,150,000.00 0.00 2023-12-04 2023-12-09 2024-01-20 2024-02-19 2024-03-25 ents nvelope lementation 1 unnel (DIT) L-13,8 km ss (Non Bank-SPD ) Request for Quota SWIM-CW-RFQ-03 / Renovati Water Sector Reform and Ins Request for Quota Single Stage - One E Pending Imp 2023-10-0 IDA / E0790 Post Open - National tions (Non Bank-S 40,000.00 0.00 2023-02-12 2023-04-09 on the IMIS department in A titutional Strengthening tions nvelope lementation 6 PD) MI SWIM-CW-RFQ-04 / Emergen Request for Quota Irrigation Scheme Improvem Request for Quota Single Stage - One E Pending Imp 2023-12-0 cy works to restore the floati IDA / E0790 Post Open - National tions (Non Bank-S 198,000.00 0.00 2023-04-16 2023-06-11 ents tions nvelope lementation 8 ng platform and gates in DIT PD) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SWIM-G-NCB-03 / Equipment Water Sector Reform and Ins Single Stage - One E Pending Impl IDA / E0790 Post Request for Bids Open - National 150,000.00 0.00 2024-01-08 2024-01-13 2024-02-24 2024-03-25 2024-04-29 2024-10-26 for the ALRI design group titutional Strengthening nvelope ementation SWIM-G-NCB-01 / Procureme nt of office furniture and equi Water Sector Reform and Ins Single Stage - One E Pending Impl IDA / E0790 Post Request for Bids Open - National 150,000.00 0.00 2023-07-10 2023-07-15 2023-08-26 2023-09-25 2023-10-30 2024-04-27 pment for organizations of th titutional Strengthening nvelope ementation e Vakhsh, Shurobad and BHC schemes. SWIM-G-NCB-05 / Procureme nt of heavy equipment for W Water Sector Reform and Ins Single Stage - One E Pending Impl UAs in the Lower Vakhsh and IDA / E0790 Post Request for Bids Open - National 920,000.00 0.00 2025-01-06 2025-01-11 2025-02-22 2025-03-24 2025-04-28 2025-10-25 titutional Strengthening nvelope ementation Upper Vakhsh basins (based on a thorough needs assess ment) Page 1 SWIM-G-NCB-06 / Procureme nt and equipping of instrume nts for measuring/water level Water Sector Reform and Ins Single Stage - One E Pending Impl IDA / E0790 Post Request for Bids Open - National 210,000.00 0.00 2024-04-22 2024-04-27 2024-06-08 2024-07-08 2024-08-12 2025-02-08 (electronic sensors/radar for titutional Strengthening nvelope ementation transmitting water level moni toring data to ISMI, WIS and WUAs) SWIM-G-NCB-07 / Procureme nt of simple drip and sprinkle r irrigation systems, introduc Water Sector Reform and Ins Single Stage - One E Pending Impl IDA / E0790 Post Request for Bids Open - National 160,000.00 0.00 2024-08-05 2024-08-10 2024-09-21 2024-10-21 2024-11-25 2025-05-24 tion of laser leveling and oth titutional Strengthening nvelope ementation er irrigation management me thods for WUA demonstration plots SWIM-G-NCB-08 / Procureme nt of heavy equipment for th Water Sector Reform and Ins Single Stage - One E Pending Impl IDA / E0790 Post Request for Bids Open - National 540,000.00 0.00 2023-05-15 2023-05-20 2023-07-01 2023-07-31 2023-09-04 2024-03-02 e scheme organizations Vakh titutional Strengthening nvelope ementation sh and Shurobad SWIM-RFQ-G-01 / Procureme nt of equipment and furnitur Water Sector Reform and Ins Request for Quota Single Stage - One E Pending Impl e for the WUA support depart IDA / E0790 Post Open - National 10,000.00 0.00 2023-02-06 2023-04-03 2023-09-30 titutional Strengthening tions nvelope ementation ment in AMI (including for th e Сomplaint Investigation Me chanism department) SWIM-RFQ-G-03 / Procureme nt of vehicles for organizatio Water Sector Reform and Ins Request for Quota Single Stage - One E Pending Impl IDA / E0790 Post Open - National 60,000.00 0.00 2024-02-10 2024-04-06 2024-10-03 ns of the level of the Vakhsh titutional Strengthening tions nvelope ementation and Shurabad schemes SWIM-RFQ-G-04 / Procureme nt of office equipment, furnit Water Sector Reform and Ins Request for Quota Single Stage - One E Pending Impl ure for 11 WUAs and tablets f IDA / E0790 Post Open - National 60,000.00 0.00 2024-02-24 2024-04-20 2024-10-17 titutional Strengthening tions nvelope ementation or 66 WUAs (+partial equipm ent for 20 WUAs based on ne eds assessment) SWIM-RFQ-G-05 / Procureme Water Sector Reform and Ins Request for Quota Single Stage - One E Pending Impl nt of furniture and equipmen IDA / E0790 Post Open - National 14,000.00 0.00 2023-04-01 2023-05-27 2023-11-23 titutional Strengthening tions nvelope ementation t for the IMSI department in AMI SWIM-G-NCB-02 / Hardware Water Sector Reform and Ins Single Stage - One E Pending Impl and software for IMIS, integra IDA / E0790 Post Request for Bids Open - National 200,000.00 0.00 2023-07-17 2023-07-22 2023-09-02 2023-10-02 2023-11-06 2024-05-04 titutional Strengthening nvelope ementation ted billing system, call center SWIM-G-NCB-04 / Procureme Single Stage - One E Pending Impl nt of vehicles for PMU and PC IDA / E0790 Project Management Post Request for Bids Open - National 130,000.00 0.00 2022-12-01 2022-12-06 2023-01-17 2023-02-16 2023-03-23 2023-09-19 nvelope ementation U in Bokhtar, WUA support gr oup in AMI SWIM-RFQ-G-06 / Procureme nt of office furniture and equi Request for Quota Single Stage - One E Pending Impl pment for PMU, PCU in Bokht IDA / E0790 Project Management Post Open - National 85,000.00 0.00 2022-12-24 2023-02-18 2023-08-17 tions nvelope ementation ar, PMU representatives in G UMI Zarafshan, Upper Vakhs h and BGK NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SWIM-CS-QCBS-01 / Preparat ion of feasibility study, detail ed engineering designs, envir onmental and social impact a Irrigation Scheme Improvem Quality And Cost- / Post Open - National 500,000.00 0.00 Signed 2022-04-15 2022-07-07 2022-05-06 2022-09-01 2022-06-19 2022-10-11 2022-07-17 2022-11-01 2022-08-16 2022-11-08 2022-09-20 2022-11-22 2022-10-25 2023-10-25 ssessments, and bidding doc ents Based Selection uments for performance impr ovement in the Vakhsh Main Canal (VMC) and Shurobod M ain Canal (ShMC) irrigation sc hemes SWIM-CS-QCBS-02 / Feasibili ty study and design estimate Irrigation Scheme Improvem Quality And Cost- Open - Internationa Under Implement for the rehabilitation of the D IDA / E0790 Post 500,000.00 0.00 2022-10-14 2022-11-11 2022-11-04 2022-12-18 2023-01-15 2023-02-14 2023-03-21 2023-04-25 2024-04-24 ents Based Selection l ation angara tunnel and the Beshk ent hydroelectric complex SWIM-CS-QCBS-07 / Develop ment of a River Basin Manag Water Sector Reform and Ins Quality And Cost- Open - Internationa Pending Impleme IDA / E0790 Post 600,000.00 0.00 2023-04-10 2023-05-01 2023-06-14 2023-07-12 2023-08-11 2023-09-15 2023-10-20 2024-10-19 ement Plan and support for c titutional Strengthening Based Selection l ntation apacity development of Vakh sh RBO SWIM-CS-QCBS-03 / Develop ment of an Irrigation Sector Water Sector Reform and Ins Quality And Cost- Open - Internationa Under Implement Development Strategy (inclu IDA / E0790 Post 1,100,000.00 0.00 2023-07-28 2023-05-16 2023-08-18 2023-10-01 2023-10-29 2023-11-28 2024-01-02 2024-02-06 2025-02-05 titutional Strengthening Based Selection l ation ding an audit of the energy s ector and revision of tariffs a nd subsidies) SWIM-CS-QCBS-04 / Support for the WUA department at A Water Sector Reform and Ins Quality And Cost- Open - Internationa LRI to promote and administ IDA / E0790 Post 500,000.00 0.00 Under Review 2023-01-25 2023-06-29 2023-02-15 2023-03-31 2023-04-28 2023-05-28 2023-07-02 2023-08-06 2024-08-05 titutional Strengthening Based Selection l er the incentive program for targeted WUAs and create a national WUA database SWIM-CS-QCBS-06 / Consulti ng services for institutional, f inancial management and co Water Sector Reform and Ins Quality And Cost- Open - Internationa Pending Impleme IDA / E0790 Post 850,000.00 0.00 2023-01-24 2023-02-14 2023-03-30 2023-04-27 2023-05-27 2023-07-01 2023-08-05 2024-08-04 mmercial capacity building, titutional Strengthening Based Selection l ntation GIS-based inventory and ass et management developmen t for single scheme-base SWIM-CS-QCBS-05 / Constru Irrigation Scheme Improvem Quality And Cost- Open - Internationa Under Implement ction supervision for Vakhsh IDA / E0790 Post 1,196,000.00 0.00 2023-05-05 2023-05-31 2023-05-26 2023-07-09 2023-08-06 2023-09-05 2023-10-10 2023-11-14 2024-11-13 ents Based Selection l ation Main Canal and Shurobod irri gation systems Page 2 SWIM-CS-CQS-012 / Baseline Consultant Qualifi Pending Impleme IDA / E0790 Project Management Post Open - National 30,000.00 0.00 2027-06-01 2027-06-22 2027-08-05 2027-09-04 2027-10-09 2028-04-06 survey cation Selection ntation SWIM-CS-CQS-08 / Survey C Consultant Qualifi Pending Impleme onsulting Services for the Ba IDA / E0790 Project Management Post Open - National 30,000.00 0.00 2023-01-05 2023-01-26 2023-03-11 2023-04-10 2023-05-15 2023-11-11 cation Selection ntation seline Study SWIM-CS-CQS-010 / Preparat ion of design and estimate d ocumentation and architectu ral supervision for the rehabil Water Sector Reform and Ins Consultant Qualifi Under Implement IDA / E0790 Post Open - National 110,000.00 0.00 2023-01-04 2022-12-23 2023-01-25 2023-01-03 2023-03-10 2023-01-20 2023-04-09 2023-01-29 2023-05-14 2023-11-10 itation of a floating platform, titutional Strengthening cation Selection ation a chamber gate for DIT and DMK and inspection after co mpletion of emergency work s in the Dangara irrigation tu nnel SWIM-CS-CQS-01 / Feasibilit y study and DEDs for prioritiz Irrigation Scheme Improvem Consultant Qualifi Pending Impleme IDA / E0790 Post Open - National 90,000.00 0.00 2023-01-20 2023-02-10 2023-03-26 2023-04-25 2023-05-30 2023-11-26 ed small and medium invest ents cation Selection ntation ments in Zarafshon and Upp er Vakhsh basins SWIM-CS-CQS-02 / Advisory services for consultation with the population in Rasht, Tajik Irrigation Scheme Improvem Consultant Qualifi Under Implement IDA / E0790 Post Open - National 15,000.00 0.00 2023-01-03 2023-05-23 2023-01-24 2023-03-09 2023-04-08 2023-05-13 2023-11-09 abad and Lakhsh districts on ents cation Selection ation eligibility criteria for the sele ction of small-scale irrigation schemes SWIM-CS-CQS-011 / Consulti Water Sector Reform and Ins Consultant Qualifi Open - Internationa Pending Impleme IDA / E0790 Post 100,000.00 0.00 2023-01-09 2023-01-30 2023-03-15 2023-04-14 2023-05-19 2023-11-15 ng services for updating the I titutional Strengthening cation Selection l ntation MIS INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TRIP-CS-DC-03 / M&E Consul / Project Management Post Direct Selection Direct 8,500.00 6,208.50 Signed 2021-11-16 2021-12-06 2021-11-26 2021-10-18 2022-01-30 2021-11-02 2022-07-29 tant TRIP-CS-DC-04 / Social Devel / Project Management Post Direct Selection Direct 5,000.00 5,843.29 Signed 2021-11-16 2021-12-06 2021-11-26 2021-10-18 2022-01-30 2021-11-02 2022-07-29 opment Consultant TRIP-CS-DC-05 / Environmen / Project Management Post Direct Selection Direct 3,750.00 1,826.03 Signed 2021-11-16 2021-12-06 2021-11-26 2021-10-18 2022-01-30 2021-11-02 2022-07-29 tal Consultant TRIP-CS-IC-01 / Agro econom Individual Consult / Project Management Post Limited 4,875.00 3,956.40 Signed 2021-11-15 2021-12-06 2021-11-20 2021-11-01 2021-12-11 2021-12-01 2022-01-15 2021-12-10 2022-07-14 ist ant Selection TRIP-CS-IC-02 / Electrical En Individual Consult / Project Management Post Limited 4,500.00 4,382.47 Signed 2021-11-15 2021-12-06 2021-11-20 2021-11-01 2021-12-11 2021-11-22 2022-01-15 2021-12-21 2022-07-14 gineer ant Selection TRIP-CS-IC-03 / Rural Area D Individual Consult / Project Management Post Limited 3,125.00 3,652.06 Signed 2021-11-15 2021-12-06 2021-11-20 2021-11-01 2021-12-11 2021-11-22 2022-01-15 2021-12-15 2022-07-14 evelopment Consultant ant Selection TRIP-CS-IC-04 / WUA Support Individual Consult / Project Management Post Limited 4,063.00 3,043.38 Signed 2021-11-15 2021-12-06 2021-11-20 2021-11-01 2021-12-11 2021-12-07 2022-01-15 2021-12-10 2022-07-14 Consultant ant Selection TRIP-CS-IC-05 / Consultant E Individual Consult Under Implement / Project Management Post Open 3,438.00 0.00 2021-11-15 2021-12-06 2022-01-03 2022-01-24 2022-02-28 2022-08-27 ngineer-Designer ant Selection ation TRIP-CS-IC-06 / Consultant E Individual Consult / Project Management Post Open 3,438.00 0.00 Canceled 2021-11-15 2021-12-06 2022-01-03 2022-01-24 2022-02-28 2022-08-27 ngineer-Estimator ant Selection TRIP-CS-IC-07 / Consultant E Individual Consult / Project Management Post Open 3,438.00 0.00 Canceled 2021-11-15 2021-12-06 2022-01-03 2022-01-24 2022-02-28 2022-08-27 ngineer-Topographer ant Selection TRIP-CS-DC-02 / Procuremen / Project Management Post Direct Selection Direct 6,000.00 5,843.29 Signed 2021-11-23 2021-12-09 2021-12-03 2021-10-18 2022-02-06 2021-12-02 2022-08-05 t Consultant TRIP-CS-DC-01 / Project Prep / Project Management Post Direct Selection Direct 7,000.00 5,112.88 Signed 2021-11-23 2021-12-09 2021-12-03 2021-10-18 2022-01-30 2021-11-02 2022-07-29 aration Manager TRIP-CS-IC-08 / Consultant In Individual Consult / Project Management Post Limited 6,125.00 0.00 Canceled 2021-11-15 2021-12-06 2021-11-20 2021-12-11 2022-01-15 2022-07-14 terpreter/Translator ant Selection SWIM-CS-INT-001 / Internati Irrigation Scheme Improvem Individual Consult Open - Internationa onal Consultant to support irr IDA / E0790 Post 70,000.00 0.00 Under Review 2022-11-14 2022-12-01 2023-01-02 2023-01-23 2023-02-27 2023-08-26 ents ant Selection l igation systems design SWIM-CS-IC-01 / Technical A dvisor for IWRM, technical ex Water Sector Reform and Ins Individual Consult Open - Internationa Pending Impleme IDA / E0790 Post 120,000.00 0.00 2023-02-15 2023-04-05 2023-04-26 2023-05-31 2023-11-27 pert on the development of t titutional Strengthening ant Selection l ntation he basin plan and IWRM SWIM-CS-IC-03 / Internationa Water Sector Reform and Ins Individual Consult Open - Internationa Pending Impleme IDA / E0790 Post 60,000.00 0.00 2023-01-31 2023-03-21 2023-04-11 2023-05-16 2023-11-12 l remote sensing consultant titutional Strengthening ant Selection l ntation SWIM-IC-L-02 / Local GIS Con Water Sector Reform and Ins Individual Consult Under Implement IDA / E0790 Post Open - National 54,000.00 0.00 2023-01-12 2023-04-28 2023-03-02 2023-03-23 2023-04-27 2023-10-24 sultant for IMIS titutional Strengthening ant Selection ation SWIM-IC-L-03 / IMIS local dat Water Sector Reform and Ins Individual Consult Pending Impleme IDA / E0790 Post Open - National 54,000.00 0.00 2023-01-17 2023-03-07 2023-03-28 2023-05-02 2023-10-29 abase consultant titutional Strengthening ant Selection ntation SWIM-IC-L-04 / Local Irrigatio Water Sector Reform and Ins Individual Consult IDA / E0790 Post Open - National 36,000.00 0.00 Under Review 2023-01-18 2023-05-11 2023-03-08 2023-03-29 2023-05-03 2023-10-30 n Engineer/IMIS Consultant titutional Strengthening ant Selection SWIM-CS-IC-012 / Impact ev Individual Consult Open - Internationa Pending Impleme IDA / E0790 Project Management Post 20,000.00 0.00 2023-02-01 2023-03-22 2023-04-12 2023-05-17 2023-11-13 aluation survey ant Selection l ntation SWIM-CS-INT-002 / Internati onal Engineer for feasibility s Irrigation Scheme Improvem Individual Consult Open - Internationa tudies and DEDs for target irr IDA / E0790 Post 30,000.00 0.00 Under Review 2022-12-05 2022-12-08 2023-01-23 2023-02-13 2023-03-20 2023-09-16 ents ant Selection l igation schemes in Lower Va khsh Basin - VMC and ShMC Page 3 SWIM-CS-IC-06 / Advisor to A LRI (international) on asset m Water Sector Reform and Ins Individual Consult Open - Internationa IDA / E0790 Post 84,000.00 0.00 Under Review 2023-02-20 2023-05-16 2023-04-10 2023-05-01 2023-06-05 2023-12-02 anagement, performance mo titutional Strengthening ant Selection l nitoring and capital strategy SWIM-CS-IC-09 / IMIS local d Water Sector Reform and Ins Individual Consult IDA / E0790 Post Open - National 54,000.00 0.00 Under Review 2023-03-27 2023-05-25 2023-05-15 2023-06-05 2023-07-10 2026-07-14 atabase consultant titutional Strengthening ant Selection SWIM-IC-L-01 / Local coordin ator of the Interagency Worki Water Sector Reform and Ins Individual Consult Under Implement ng Group (IWG) on the devel IDA / E0790 Post Open - National 36,000.00 0.00 2023-01-12 2023-02-06 2023-03-02 2023-03-23 2023-04-27 2025-04-16 titutional Strengthening ant Selection ation opment of an irrigation strate gy and overall coordinator of sub-component 1.2 SWIM-CS-IC-011 / ALRI Advis Water Sector Reform and Ins Individual Consult Open - Internationa or for Irrigation Strategy Dev IDA / E0790 Post 150,000.00 0.00 Signed 2025-02-10 2022-12-23 2025-03-31 2023-01-26 2025-04-21 2023-02-26 2025-05-26 2025-11-22 titutional Strengthening ant Selection l elopment and IMIS SWIM-CS-IC-013 / Сonsultant to support ALRI in the develo Water Sector Reform and Ins Individual Consult Open - Internationa IDA / E0790 Post 75,000.00 0.00 Under Review 2023-05-17 2023-06-02 2023-07-05 2023-07-26 2023-08-30 2024-02-26 pment of the irrigation mana titutional Strengthening ant Selection l gement information system ( IMIS) Page 4 Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: May 20, 2017 2. Date of General Procurement Notice: Oct. 10, 2016 3. Period covered by this procurement plan: The whole project period II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) 4 million 2. NCB (Goods) 4 million 3. ICB (Works) 15 million 4. NCB (Works) 15 million 5. (Non-Consultant Services) 4 million [Add other methods if necessary] 2. Prequalification. _Not applicable_. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Not applicable 5. Any Other Special Procurement Arrangements: Advance procurement and retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / July 9, 2010 US$ rence Post) million (yes/ no) Summary 0 0 N/A N/A of the ICB (Works) Summary 0 0 N/A N/A of the ICB (Goods) Summary 150.47 10 No Prior / of the NCB Post (Works) Summary 50.40 12 No Prior / of the NCB Post (Goods) Summary 0 0 N/A N/A of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) US$2 million 2. Single Source (Firms) US$1 million 3. Individual US$0.4 million 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 0.51 1 Post July 9, 2010 of number of contracts that will be let under QCBS Summary 1.82 12 Post of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT China : Three Gorges Modern Logistics Center Infrastructure Project PLAN General Information Country: China 2018-05-18 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153473 GPN Date: Project Name: Three Gorges Modern Logistics Center Infrastructure Project Loan / Credit No: IBRD / 87660 Yi Chang PMO Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GK-C2 / Road, architectural, port, electric, communication Baiyang Port and operations Single Stage - One E 27,220,000.0 21,228,646. 2020-12-2 , water supply & drainage, en IBRD / 87660 Prior Request for Bids Open - National Signed 2019-04-25 2019-05-18 2019-04-30 2019-05-30 2019-06-20 2019-06-06 2019-07-18 2019-07-04 2019-07-16 Area nvelope 0 20 5 vironmental protection works and temporary works in Stor age Yard 7#, 12# and 13#. WL-C3 / Intelligent Cargo Dis tributing Center: 1 Building ( 21,000m2) and electric, com Single Stage - One E 15,998,784. 2020-03-2 IBRD / 87660 Baiyang Logistics Park Post Request for Bids Open - National 9,670,000.00 Signed 2019-06-10 2020-09-15 2019-06-15 2019-07-27 2021-03-11 2019-08-26 2021-03-11 2019-09-30 2021-09-02 munications, water supply & nvelope 73 8 drainage, fire-fighting and en vironmental protection, etc i n Building. DJ-C1 / Roadbed (earthwork & foundation treatment), pav ement (carriageway, sidewal Transport Connection Infrast Single Stage - One E 4,655,609.8 2020-06-0 IBRD / 87660 Prior Request for Bids Open - National 7,400,000.00 Signed 2019-08-16 2020-06-29 2019-08-21 2019-10-02 2016-12-27 2019-11-01 2020-08-06 2019-12-06 2017-05-16 k & auxiliaries), traffic, culver ructure nvelope 7 3 ts, lighting, integrated pipe n etwork and drainage in Guih u Road & 2nd Songgang Roa d. WL-C4 / 1. Containing Devan ing & Loading Warehouse: 2 buildings (10,600m2). 2. Foo dstuff Warehouse: 3 building Single Stage - One E 14,940,000.0 12,435,211. 2020-06-0 IBRD / 87660 Baiyang Logistics Park Prior Request for Bids Open - National Signed 2019-08-15 2020-08-14 2019-08-20 2019-10-01 2017-08-08 2019-10-31 2020-08-21 2019-12-05 2017-11-02 s (19,300m2). 3. Processing nvelope 0 33 2 Factory: 2 buildings (4,600m 2). 4. Parking Lot: Road (12,9 00m2). 5.W1 Container Yard. 6. W1~3# Substation(1800m 2). 7.Earthwor DJ-C2 / Roadbed (earthwork & foundation treatment), pav ement (carriageway, sidewal Baiyang Port and operations Single Stage - One E 11,060,000.0 9,665,753.9 2021-06-0 k & auxiliaries), bridge, retai IBRD / 87660 Post Request for Bids Open - National Signed 2020-08-13 2017-06-02 2020-08-18 2020-09-29 2017-07-04 2020-10-29 2017-07-04 2020-12-03 2017-07-29 Area nvelope 0 0 1 ning wall, traffic, culverts, lig hting, integrated pipe networ k and drainage in Shawan Ro ad Overpass. WL-C3-2020 / Intelligent Car go Distributing Center: 1 Bui lding (21,000m2) and electric Single Stage - One E 18,380,000.0 Under Imple 2021-07-0 IBRD / 87660 Baiyang Logistics Park Prior Request for Bids Open - National 0.00 2020-09-15 2020-10-23 2020-09-20 2020-11-01 2021-03-11 2020-12-01 2021-08-04 2021-01-05 , communications, water sup nvelope 0 mentation 4 ply & drainage, fire-fighting a nd environmental protection, etc in Building. WL-C9 / Earthwork excavatio n and backfilling within 890 Request for Bids - mu of area A and B of Comm Single Stage - One E Works (without pr 13,846,153.0 Under Imple 2022-03-0 IBRD / 87660 Baiyang Logistics Park Post Request for Bids Open - National 0.00 2021-05-20 2021-05-27 2021-05-25 2021-07-06 2021-06-30 2021-08-05 2021-06-30 2021-09-09 erce and trade logistics ,unfi nvelope equalification) SP 0 mentation 8 nished subgrade and pavem D ent and supporting works of Guihu road and 2nd Songgan g road. WL-C5 / 1. Si Cheng apartme nt; 2. number 1: comprehens Request for Bids - ive warehouse (1 building); 3 Single Stage - One E Works (without pr 12,500,000.0 Under Imple 2022-04-0 . Building electrical, commun IBRD / 87660 Baiyang Logistics Park Post Request for Bids Open - National 0.00 2021-06-15 2021-08-05 2021-06-20 2021-08-01 2021-09-07 2021-08-31 2021-09-07 2021-10-05 nvelope equalification) SP 0 mentation 3 ication, water supply and dra D inage, fire protection, enviro nmental protection engineeri ng and earthwork Road site. WL-C2 / The scope of this bi dding mainly covers the civil Request for Bids - works of commercial area B Single Stage - One E Works (without pr 37,094,281.0 2022-06-2 of the world bank loan projec IBRD / 87660 Baiyang Logistics Park Prior Request for Bids Open - National 0.00 Signed 2021-09-09 2021-11-17 2021-09-14 2021-10-26 2021-12-20 2021-11-25 2022-09-02 2021-12-30 nvelope equalification) SP 0 8 t, including 2 processing plan D ts, 2 warehouses, 1 office bui lding, 2 power distribution su bstations and 1 fire pump ho use. WL-C1 / 1. Commercial ware house (3 ); 2. Processing plan t (3 ); 3. Exhibition and tradin Request for Bids - g center (1 ); 4. Office buildin Single Stage - One E Works (without pr 38,460,000.0 2022-09-0 IBRD / 87660 Baiyang Logistics Park Prior Request for Bids Open - National 0.00 Signed 2021-11-15 2022-06-14 2021-11-20 2022-01-01 2022-08-02 2022-01-31 2022-09-07 2022-03-07 g (1 ); 5. Substation (2 sets); nvelope equalification) SP 0 3 6. Roads, storage yards and D parking lots; 7. Underground hydropower, pipe network,el ectrical, communication WL-C2-NEW / The scope of t his bidding mainly covers the Request for Bids - civil works of commercial are Single Stage - One E Works (without pr 37,094,281.0 2023-04-2 a B of the world bank loan pr IBRD / 87660 Baiyang Logistics Park Prior Request for Bids Open - National 0.00 Canceled 2022-07-11 2022-07-16 2022-08-27 2022-09-26 2022-10-31 nvelope equalification) SP 0 9 oject, including 2 processing D plants, 2 warehouses, 1 offic e building, 2 power distributi on substations and 1 fire pu mp house. Request for Bids - XX-C1. / Information Center ( Baiyang Logistics Informatio Single Stage - One E Works (without pr Pending Imp 2024-03-2 IBRD / 87660 Post Request for Bids Open - National 1,428,571.00 0.00 2023-06-07 2023-06-12 2023-07-24 2023-08-23 2023-09-27 Decoration and Construction) n Platform and Facilities nvelope equalification) SP lementation 5 D GK-C1 / Construction Works Baiyang Port and operations Single Stage - One E 12,851,093. for 8#-11# Berths and 7#-11 IBRD / 87660 Prior Request for Bids Open - National 0.00 Signed 2017-11-11 2017-12-08 Area nvelope 41 # Land Territories GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 GK-G6 / 30 Mobile Belt Conv eyors L=15m; 144m Belt Con Baiyang Port and operations Single Stage - One E veyors IBRD / 87660 Post Request for Bids Open - National 734,200.00 0.00 Canceled 2019-07-30 2019-08-27 2019-08-04 2019-09-03 2019-08-27 2019-10-03 2019-08-27 2019-11-07 2020-05-05 Area nvelope B1200, V2.0m/s, 2 electric wi nches 3T GK-C3 / 1360m windproof an Baiyang Port and operations Request for Quota Single Stage - One E IBRD / 87660 Post Open - National 198,200.00 197,816.75 Signed 2019-08-21 2019-10-16 2019-10-01 2020-04-13 d dust suppression net, 8m h Area tions nvelope igh GK-G4 / Port transfer equipm Baiyang Port and operations Single Stage - One E IBRD / 87660 Prior Request for Bids Open - National 4,540,000.00 5,011,254.40 Signed 2020-05-01 2021-03-04 2020-05-06 2020-06-17 2021-04-16 2020-07-17 2021-04-27 2020-08-21 2021-06-08 2021-02-17 ent (Berths#10-#11) Area nvelope GK-G3 / 8 #9# berth:90 × 1 4 m steel Barges, 2 vessels Baiyang Port and operations Single Stage - One E 600t/h circular track loaders, IBRD / 87660 Prior Request for Bids Open - National 8,249,027.00 6,835,909.10 Signed 2021-05-23 2021-06-01 2021-05-28 2021-07-09 2021-08-24 2021-08-08 2021-11-02 2021-09-12 2021-12-08 2022-03-11 Area nvelope 2 sets; belt conveyors, 7 sets , 1584m; 3T electric hoist, 3 sets. GK-G2 / 2 sets of 40t-30m p ortal cranes, 1 set of 16t-30 m portal crane, 1 set of 45t-2 Baiyang Port and operations Single Stage - One E IBRD / 87660 Prior Request for Bids Open - National 8,093,385.00 7,930,883.30 Terminated 2021-05-23 2021-07-09 2021-05-28 2021-07-09 2021-08-25 2021-08-08 2021-11-17 2021-09-12 2021-12-24 2022-03-11 5m quayside container bridg Area nvelope e crane, 2 sets of 40t-30m R ail Gantry Cranes, 4 sets of 1 6t-22.5m bridge cranes GK-G1 / 1 tire crane 50t, 2 ti re cranes 30t; 2 sets of tire c Baiyang Port and operations Single Stage - One E IBRD / 87660 Prior Request for Bids Open - National 6,800,000.00 0.00 Signed 2021-11-05 2022-02-21 2021-11-10 2021-12-22 2022-07-06 2022-01-21 2022-08-31 2022-02-25 2023-04-12 2022-08-24 ranes 16t; 4 container front c Area nvelope ranes and 4 container straddl e carriers WL-G6 / Rail mounted contai Single Stage - One E ner gantry crane 45t-40m fiv IBRD / 87660 Baiyang Logistics Park Prior Request for Bids Open - National 9,230,000.00 0.00 Signed 2021-11-10 2022-02-21 2021-11-15 2021-12-27 2022-07-04 2022-01-26 2022-08-16 2022-03-02 2022-08-29 nvelope e Rail mounted gantry crane 16t-40m two WL-G5 / Rail mounted contai Single Stage - One E ner gantry crane 45t-40m fiv IBRD / 87660 Baiyang Logistics Park Prior Request for Bids Open - National 9,850,000.00 0.00 Signed 2021-11-10 2022-02-21 2021-11-15 2021-12-27 2022-07-05 2022-01-26 2022-08-16 2022-03-02 2022-08-29 nvelope e Rail mounted gantry crane 40t-40m two WL-G1 / Bridge crane 32t-19 .5m eight 16t-28.5m eight 16t-19.5m eight Electric sin Single Stage - One E Under Imple IBRD / 87660 Baiyang Logistics Park Post Request for Bids Open - National 3,730,000.00 0.00 2021-11-12 2021-12-15 2021-11-17 2021-12-29 2022-07-13 2022-01-28 2022-03-04 2022-08-31 gle beam crane 5t-16.5m two nvelope mentation Embedded boarding axle 1 0t seventy-six Electronic tru ck scale 150t seven WL-G2 / Forklift 5t 10 3t 27 2t ,21 Single bucket loader ZL50 ,14 tractor Q45,18 Fla Single Stage - One E t car PC40 36 tractor Q20 IBRD / 87660 Baiyang Logistics Park Prior Request for Bids Open - National 8,170,000.00 0.00 Signed 2021-11-12 2022-02-21 2021-11-17 2021-12-29 2022-07-12 2022-01-28 2022-08-30 2022-03-04 2022-08-31 nvelope 18 Flat car P20 36 ,Contai ner tractor 40 Container se mitrailer 40 feet 20 Dump truck 55t 24. GK-G9 / Two 40t-30m gantry cranes, two 16t-30m gantry c ranes, one 45t-25m quayside Baiyang Port and operations Single Stage - One E container bridge crane, two 4 IBRD / 87660 Prior Request for Bids Open - National 11,540,000.00 0.00 Canceled 2022-09-20 2022-10-15 2022-11-06 2022-12-06 2023-01-10 2023-07-09 Area nvelope 0t-30m Rail Gantry Cranes, o ne multipurpose gantry cran e (45t-30m), and four 16t-22. 5m bridge cranes GK-G9. / includes the manuf acturing, installation, commis sioning, inspection and final delivery of two 40t-30m port Baiyang Port and operations Open - Internationa Single Stage - One E IBRD / 87660 Prior Request for Bids 10,563,380.00 0.00 Canceled 2022-10-15 2022-11-18 2022-10-20 2022-12-01 2022-12-31 2023-02-04 2023-08-03 al cranes, two 16t-30m portal Area l nvelope cranes, one 45t-25m quaysid e container bridge crane, one 45t-30m multi-purpose portal crane, etc. GK-G9-NEW / includes the m anufacturing, installation, co mmissioning, inspection and Baiyang Port and operations Open - Internationa Single Stage - One E Under Imple final delivery of two 40t-30m IBRD / 87660 Prior Request for Bids 9,285,700.00 0.00 2023-01-17 2023-01-19 2023-01-22 2023-03-05 2023-03-10 2023-04-04 2023-04-27 2023-05-09 2023-11-05 Area l nvelope mentation portal cranes, one 45t-25m q uayside container bridge cra ne, one 45t-30m multi-purpo se portal crane, etc. XX-G1 / Information Center ( Baiyang Logistics Informatio Single Stage - One E Under Imple IBRD / 87660 Prior Request for Bids Open - National 9,285,714.00 0.00 2023-06-01 2023-06-02 2023-06-06 2023-07-18 2023-08-17 2023-09-21 2024-03-19 Information Construction) n Platform and Facilities nvelope mentation XX-C1 / Information Center ( Baiyang Logistics Informatio Single Stage - One E IBRD / 87660 Post Request for Bids Open - National 1,428,571.00 0.00 Canceled 2023-06-05 2023-06-10 2023-07-22 2023-08-21 2023-09-25 2024-03-23 Decoration and Construction) n Platform and Facilities nvelope NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NL-S7 / To develop research about "Business Model & Ope Quality And Cost- Open - Internationa IBRD / 87660 Capacity Building Prior 538,000.00 0.00 Signed 2018-07-19 2018-08-09 2018-07-23 2018-08-30 2019-04-10 2018-09-06 2019-05-15 2018-09-13 2019-08-12 2018-09-30 2023-04-17 2018-10-28 2020-04-20 ration Schedule of Baiyang P Based Selection l ort & Logistics Park" INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 NL-S1 / To provide support a bout Architectural Engineerin Individual Consult Pending Impleme IBRD / 87660 Capacity Building Post Open 29,400.00 0.00 2019-06-15 2019-08-03 2019-08-24 2019-09-28 2020-03-26 g to Project Office during imp ant Selection ntation lementation period. NL-S2 / To provide support a bout Port & Harbor Engineeri Individual Consult Pending Impleme IBRD / 87660 Capacity Building Post Open 22,000.00 0.00 2019-06-15 2019-08-03 2019-08-24 2019-09-28 2020-03-26 ng to Project Office during im ant Selection ntation plementation period. Page 3 PROCUREMENT PLAN (Textural Part) Project information Country: Federal Democratic Republic of Ethiopia Project Name: Development Response to Displacement Impacts Project in the Horn of Africa Phase II (DRDIP II) Project ID: P178047 Project Implementation Agency: Ministry of Agriculture (MoA) Date of the Procurement Plan: September 2022 Period covered by this Procurement Plan: September 2022 to December 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” dated November 2020 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Directives of the Federal and Regional Governments of Ethiopia such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations. Goods: Applicable Works: Applicable Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Not Applicable. Proposed Procedures for CDD Components: Applicable Other Relevant Procurement Information: The procurement procedures for Situations in Urgent Need of Assistance or Capacity Constraints described under paragraph 12 of Section III of the World Bank Policy on IPF, which will be applicable to fast track emergency procurements shall not apply. PROCUREMENT Eastern and Southern Africa : Development Response to Displacement Impacts Project in the Horn of Africa Phase II PLAN General Information Country: Eastern and Southern Africa 2023-04-25 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178047 GPN Date: 2022-10-05 Project Name: Development Response to Displacement Impacts Project in the Horn of Africa Phase II Loan / Credit No: IDA / E0590 Amhara National Regional State Bureau of Agriculture Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-ANRSBOA-351332-GO-RF Social and Economic Service Request for Quota Single Stage - One E Pending Impl Q / Procurement of office fur IDA / E0590 Post Limited 25,000.00 0.00 2023-04-07 2023-06-02 2023-11-29 s and Infrastructure tions nvelope ementation niture for ANRSBoA ET-ANRSBOA-350943-GO-RF Q / Procurement of 12 Lapto p computer, 5 desktop comp Social and Economic Service Request for Quota Single Stage - One E Pending Impl uter ,1 all in one printer, 2 LC IDA / E0590 Post Limited 79,000.00 0.00 2023-05-27 2023-07-03 2023-08-13 s and Infrastructure tions nvelope ementation D, 5 printer,2 scanner,5 digit al camera, 9 tablet bag, 13 h ard disk,10 divider, 9 power bank for ANRS BOA ET-ANRSBOA-351965-GO-RF Q / Solar light Demonstration Sustainable Environmental Request for Quota Single Stage - One E Pending Impl IDA / E0590 Post Limited 55,000.00 0.00 2023-05-19 2023-07-14 2024-01-10 to Dabat Woreda,Dabat city Management tions nvelope ementation administration and Refugee camp quantity 450 ET-ANRSBOA-359058-GO-RF Q / shovel 1014, pick axe 30 42, hammers 72, line levels 1 Sustainable Environmental Request for Quota Single Stage - One E Pending Impl IDA / E0590 Post Limited 33,780.00 0.00 2023-05-20 2023-07-15 2024-01-11 20, tape meters 40 and diggi Management tions nvelope ementation ng bar 180 to supply Dabat woreda farmers for soil & wat er conservation activities ET-ANRSBOA-365100-GO-RF Q / Procurement of seed and Pending Impl Fertilizers for farms demonst IDA / E0590 Livelihoods Program Post Direct Selection Direct - National 27,500.00 0.00 2023-06-05 2023-06-07 2023-06-13 2023-06-28 ementation ration for Dabat woreda proc ured by dabat wored office of finance NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 Sample Procurement Plan Regional Disease Surveillance Systems Enhancement (REDISSE)(P154807) I. General 1. Bank’s approval Date of the procurement Plan [Original: July 2016]: Revision 1of Updated Procurement Plan, January 5th 2017 2. Date of General Procurement Notice: Dec 27, 2016 3. Period covered by this procurement plan: The procurement period of project covered from year March to December 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Prior Review Type of procurement Threshold US$ Works (including turnkey, supply & US$ 10 million installation of plant and equipment, and PPP) Goods, information technology and non- US$ 2 million consulting services 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project issued by WAHO 5. Any Other Special Procurement Arrangements: Not applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 4/4/2017 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 0.14 1 No Post of the NCB (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Type of procurement Prior Review Threshold US$ Consultants: firms US$ 1 million Consultants: individuals US$ 0.3 million 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_200,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: not applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comments of ed s by Bank Assignmen Cost (Prior / t US$ Post) million Summary 3.995 2 Prior of number of contracts that will be let under QCB Summary 0.22 2 Post Market of number approach: of Open 4/4/2017 contracts Internatio that will nal be let under CQS 4/4/2017 PROCUREMENT Western and Central Africa : Regional Disease Surveillance Systems Enhancement (REDISSE) PLAN General Information Country: Western and Central Africa 2017-11-30 Bank’s Approval Date of the Original Procurement Plan: 2023-05-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P154807 GPN Date: Project Name: Regional Disease Surveillance Systems Enhancement (REDISSE) Loan / Credit No: IDA / 58830, IDA / D1300 MoH-GUI - PROJET D'AMELIORATION DES SERVICES DE SANTE PRIMAIRES Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GN-PASSP-28085-CW-RFB / Rénovation des locaux des la Component 2: Strengthening Single Stage - One E 2019-03-3 IDA / 58830 Post Request for Bids Open - National 228,000.00 208,518.20 Signed 2018-06-12 2018-12-10 2018-06-17 2018-12-13 2018-07-29 2019-01-06 2018-08-28 2019-04-01 2018-10-02 2019-05-31 boratoires de Fièvres Hémor of Laboratory Capacity nvelope 1 agique et INSP/LNR GN-PASSP-28113-CW-RFB / Component 2: Strengthening Open - Internationa Single Stage - One E Under Imple 2019-08-2 Construction d'un Laboratoir IDA / 58830 Post Request for Bids 1,400,000.00 0.00 2018-05-10 2019-05-09 2018-05-15 2019-05-13 2018-06-26 2018-07-26 2018-08-30 of Laboratory Capacity l nvelope mentation 6 e natioal de diagnostic vétéri naire niveau P2 GN-PASSP-28114-CW-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E 2018-11-1 Construction de cinq (5) Post IDA / 58830 Post Limited 150,000.00 93,205.36 Signed 2018-06-17 2018-12-06 2018-08-12 2019-03-26 of Laboratory Capacity tions nvelope 2 es d'Inspection Frontaliers (PI F) GN-PASSP-42811-CW-RFB / Component 5: Institutional C Recrutement d'une entrepris apacity Building, Project Ma Single Stage - One E Under Imple 2019-02-2 e pour la construction du bâti IDA / 58830 Post Request for Bids Open - National 220,000.00 0.00 2018-04-29 2018-11-20 2018-05-04 2018-11-26 2018-06-15 2018-07-15 2018-08-28 nagement, Coordination, an nvelope mentation 4 ment administratif R+2 pour d Advocacy abriter le siège de l'UGP REDI SSE et PASSP GN-MOH-GUI-172593-CW-RF Q / Travaux de rénovation de Component 2: Strengthening Request for Quota Single Stage - One E 2021-02-2 s locaux du laboratoire de l'I IDA / 58830 Post Limited 65,000.00 55,214.54 Signed 2020-09-29 2020-07-14 2020-11-24 2020-11-13 of Laboratory Capacity tions nvelope 2 NSP (remise en état de la plo mberie sanitaire, de l'électric ité, la peinture, etc. ) GN-MOH-GUI-326595-CW-RF Q / Aménagement et mise à niveau des Postes d'Inspectio Request for Quota n Frontalier (PIF) des Service Component 1: Surveillance a Request for Quota Single Stage - One E Pending Imp 2023-05-1 IDA / 58830 Post Limited tions (Non Bank-S 87,500.00 0.00 2022-12-24 2023-02-18 s Vétérinaire en deux lots : lo nd Information Systems tions nvelope lementation 9 PD) t 1 : Installation de 4 forages solaires et Lot 2 : Installation de 5 latrines de deux blocs c hacun pour les PIF. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GN-PASSP-28033-GO-RFB / A Component 1: Surveillance a Single Stage - One E Under Imple cquisition de neuf (9) véhicul IDA / 58830 Prior Request for Bids Open - National 270,000.00 0.00 2017-10-17 2017-10-22 2017-12-03 2018-01-02 2018-02-15 2018-05-16 nd Information Systems nvelope mentation es 4x4 Pick-up double cabine s GN-PASSP-28034-GO-RFB / A cquisition de quatre-vingt-dix Component 1: Surveillance a Single Stage - One E IDA / 58830 Post Request for Bids Open - National 450,000.00 166,038.69 Completed 2017-10-17 2018-01-08 2017-10-22 2018-02-01 2017-12-03 2018-02-15 2018-01-02 2018-03-02 2018-02-15 2018-05-15 2018-05-16 2018-10-01 (90) motos tout terrain en fa nd Information Systems nvelope veur des Agents du REMAGUI GN-PASSP-28035-GO-RFQ / Component 4: Human Resou Acquisition de matériel infor rce Management for Effectiv Request for Quota Single Stage - One E matique et de reprographie e IDA / 58830 Post Limited 98,000.00 96,595.73 Completed 2017-10-28 2017-12-18 2017-12-23 2018-01-29 2018-01-22 2018-11-23 e Disease Surveillance and E tions nvelope n faveur du personnel de l'U pidemic Preparedness. GP et de la Santé Animale GN-PASSP-28036-GO-RFQ / Component 4: Human Resou Acquisition et installation de rce Management for Effectiv Request for Quota Single Stage - One E IDA / 58830 Post Limited 98,500.00 97,497.48 Completed 2017-10-28 2017-12-18 2017-12-23 2018-01-23 2018-01-22 2017-09-27 mobilier de bureau en faveur e Disease Surveillance and E tions nvelope de l'UGP et la santé animale pidemic Preparedness. GN-PASSP-28043-GO-RFQ / E quipement du Laboratoire pé Component 2: Strengthening Request for Quota Single Stage - One E IDA / 58830 Post Limited 45,000.00 16,750.89 Signed 2017-12-02 2018-04-03 2018-01-27 2018-05-08 2018-02-26 dagogique en matériel de lab of Laboratory Capacity tions nvelope o pour l'Institut vétérinaire d e Dalaba GN-PASSP-28065-GO-RFB / A cquisition du matériel de dia gnostic des maladies à poten Component 2: Strengthening Request for Quota Single Stage - One E Under Imple tiel épimédique d'origine bac IDA / 58830 Post Limited 84,100.00 0.00 2017-12-01 2018-06-21 2018-01-26 2018-03-27 of Laboratory Capacity tions nvelope mentation térienne et virale ainsi que d es consommables et réactif p our les 2 laboratoires de réfé rence (INSP/LNR et LFH GN-PASSP-28081-GO-RFQ / Acquisition de matériels, con Component 2: Strengthening Single Stage - One E sommables et réactif de diag IDA / 58830 Post Request for Bids Open - National 354,400.00 921,516.93 Signed 2017-11-22 2018-10-25 2017-11-27 2018-10-29 2018-01-08 2019-01-25 2018-02-07 2019-03-11 2018-03-14 2019-06-03 2018-06-12 of Laboratory Capacity nvelope nostic pour les laboratoires a u niveau régional, préfectoral et communautaires GN-PASSP-28467-GO-RFQ / P roduction et édition des outil s de gestion pour les centres de surveillance animale et en Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 58830 Post Limited 35,000.00 21,853.48 Completed 2017-12-23 2018-03-25 2018-02-17 2018-06-27 2018-03-19 2018-08-28 vironnementale en (registres nd Information Systems tions nvelope et notification, fiches de notif ication, fiches d'investigation , fiches de suivi, fiches de col lecte des informations/déclar ation, etc.) GN-PASSP-28472-GO-RFB / A cquisition et instalation de h Component 1: Surveillance a Single Stage - One E uit (8) incinérateurs pour les IDA / 58830 Post Request for Bids Open - National 320,000.00 449,180.26 Signed 2018-04-16 2018-09-18 2018-04-21 2018-09-24 2018-06-02 2018-10-30 2018-07-02 2018-12-24 2018-08-15 2019-05-10 2019-02-11 nd Information Systems nvelope établissements de soins (cen tres de santé et hopitaux) Page 1 GN-PASSP-28500-GO-RFB / A chat, transport et installation de 456 kits solaires dont : Component 1: Surveillance a Open - Internationa Single Stage - One E Under Imple IDA / D1300 Prior Request for Bids 1,620,000.00 0.00 2018-08-13 2019-10-08 2018-08-18 2018-09-29 2018-10-29 2018-12-03 2019-06-01 - 410 pour les Centre de sa nd Information Systems l nvelope mentation ntés - 38 pour les DPS et - 8 pour les DRS GN-PASSP-28570-GO-RFB / A cquisition de VSAT pour les b Component 1: Surveillance a Single Stage - One E IDA / 58830 Post Request for Bids Open - National 399,000.00 188,833.15 Completed 2018-05-21 2019-01-21 2018-05-26 2019-01-22 2018-07-07 2019-02-26 2018-08-06 2019-03-07 2018-09-10 2019-07-17 2018-12-09 2020-09-15 ureaux de la Division Prévent nd Information Systems nvelope ion et Lutte contre la Maladie ainsi que les DRS GN-PASSP-28462-GO-RFQ / Achat de kit de surveillance Component 1: Surveillance a Request for Quota Single Stage - One E (vélos, bottes, imperméables IDA / 58830 Post Limited 42,000.00 36,810.15 Signed 2018-05-26 2019-12-20 2018-07-21 2020-03-03 2018-08-20 nd Information Systems tions nvelope , stylos, sac à dos, etc.) pour les Agents Communautaires GN-PASSP-28040-GO-RFQ / Contrat avec VDC Télécom p our la fourniture et l'installati on de connexion Internet et l' Component 1: Surveillance a IDA / 58830 Post Direct Selection Direct 48,000.00 17,099.10 Signed 2018-03-26 2018-03-05 2018-03-31 2018-03-12 2018-05-07 2018-03-26 2018-06-06 assistance technique pour la nd Information Systems Direction Nationale des Servi ces Vétérinaires. VDC est re cruté par le PASSP pour la fo urniture de la connexion Inte rnet de l'UGP. MOF-REF-02 / Acquisition de 9 véhicules 4x4 Pick-up doub le cabines Tout Terrain dont Component 1: Surveillance a Single Stage - One E IDA / 58830 Post Request for Bids Open - National 270,000.00 229,313.12 Completed 2017-12-17 2018-01-08 2017-12-22 2018-02-02 2018-02-15 2018-03-04 2018-03-02 2018-04-08 2018-05-15 2018-07-07 2018-10-01 1 véhicule pour la santé hum nd Information Systems nvelope aine, 7 pour la santé animale et 1 véhicule pour le SE/Unité de Gestion du Projet GN-PASSP-28048-GO-RFB / A chat de 410 tablettes pour l Component 1: Surveillance a Request for Quota Single Stage - One E a suveillance au niveau com IDA / 58830 Post Limited 85,000.00 81,736.20 Signed 2019-01-27 2019-08-06 2019-03-24 2019-10-03 2019-05-23 nd Information Systems tions nvelope munautaire pour la Direction Nationale des Services Vétéri naires (santé animale) GN-PASSP-28108-GO-RFB / A chat de chaîne de froid (solai re) et matériel de prélèveme Component 1: Surveillance a Single Stage - One E Pending Impl IDA / 58830 Post Request for Bids Open - National 250,000.00 0.00 2019-03-26 2019-03-31 2019-05-12 2019-06-11 2019-07-16 2019-09-14 nt pour le renforcement des nd Information Systems nvelope ementation unités mobiles de santé anim ale de Kankan et de Labé, Ki ndia et N'Zérékoré GN-PASSP-65629-GO-RFQ / Acquisition de 4 véhicules Pic k-up double cabines 4x4 dont : 1 véhicule pour le laboratoir Component 1: Surveillance a Single Stage - One E Under Imple IDA / 58830 Post Request for Bids Open - National 120,000.00 0.00 2019-02-14 2019-04-22 2019-02-19 2019-04-30 2019-04-02 2019-05-02 2019-06-06 2019-12-03 e central de diagnostic (sant nd Information Systems nvelope mentation é animale), 2 véhicules pour l a Direction de l'Environneme nt et 1 véhicule pour la super vision des laboratoires du rés eau (INSP). GN-PASSP-79450-GO-RFB / A chat de 410 tablettes en fave Component 1: Surveillance a Single Stage - One E Pending Impl ur des structures déconcentr IDA / 58830 Post Request for Bids Open - National 460,000.00 0.00 2019-03-27 2019-04-01 2019-05-13 2019-06-12 2019-07-17 2020-01-13 nd Information Systems nvelope ementation ées de la Direction Nationale des Services Vétérinaires GN-PASSP-92792-GO-DIR / C ontrat avec MERIAL France p our la fourniture 7000 flacon s de vaccins Aftovax O A SAT Component 1: Surveillance a IDA / 58830 Prior Direct Selection Direct 700,000.00 724,000.00 Signed 2019-01-28 2019-02-07 2019-02-02 2019-04-10 2019-03-09 2019-05-02 2019-09-05 1 SAT2 (souches O manisa, O nd Information Systems 3039, A Saudi 95, SAT1 et SA T2 Eri) en flacons de 50 dose s, soit l'équivalent de 350 00 0 doses pour la fièvre aphteu se GN-PASSP-92796-GO-RFQ / Acquisition de huit (8) chaine Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 58830 Post Limited 65,000.00 50,579.12 Signed 2019-01-27 2019-02-04 2019-03-24 2019-04-25 2019-05-08 s de froids solaires (Réfrigéra nd Information Systems tions nvelope teur-congélateur) pour la fièv re aphteuse GN-PASSP-92949-GO-RFQ / Acquisition de produits vétéri naire dont : 160 Portes vacci Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 58830 Post Limited 55,000.00 52,361.08 Completed 2019-01-27 2019-02-04 2019-03-24 2019-03-29 2019-05-08 2019-06-06 ns genre UNICEF, 165 Sering nd Information Systems tions nvelope ues automatiques, 4 kits de diagnostic 1 kit de 250 tests pour la fièvre aphteuse GN-PASSP-94044-GO-RFQ / P Component 5: Institutional C restataire de service pour l'a apacity Building, Project Ma Request for Quota Single Stage - One E IDA / 58830 Post Limited 40,000.00 2,021.80 Signed 2019-04-05 2018-11-05 2019-05-31 2018-12-24 2021-05-30 cquisition de fournitures de nagement, Coordination, an tions nvelope bureau par marché à comma d Advocacy nde GN-PASSP-115253-GO-RFB / Acquisition de 100 motocycle Component 1: Surveillance a Single Stage - One E Pending Impl IDA / 58830 Post Request for Bids Open - National 230,000.00 0.00 2019-12-23 2019-12-28 2020-02-08 2020-03-09 2020-04-13 2020-06-12 ttes complémentaires pour l nd Information Systems nvelope ementation es Agents du REMAGUI GN-PASSP-115258-GO-RFQ / Acquisition du matériel infor Component 5: Institutional C matique en faveur de la direc apacity Building, Project Ma Request for Quota Single Stage - One E tion de l'OGUIPAR, des 4 UMS IDA / 58830 Post Limited 75,000.00 60,185.82 Terminated 2019-10-05 2020-08-05 2019-11-30 2020-03-28 2020-01-14 nagement, Coordination, an tions nvelope A, de la DNGELM et de la D d Advocacy NSV ainsi que l'acquisition d' un photocopieur grand modè le et une imprimante pour l'U GP GN-PASSP-115277-GO-RFQ / Acquisition de mobilier de bu reau pour de la direction de l' Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 58830 Post Limited 45,000.00 57,124.84 Signed 2019-10-29 2019-09-05 2019-12-24 2019-10-26 2020-01-23 Office Guinéen des Parcs et nd Information Systems tions nvelope Réserves (OGUIPAR), des 4 U nités Mobiles de Santé Anima le (UMSA) GN-PASSP-118159-GO-RFQ / Achat de chaîne de froid (sol aire) et matériel de prélèvem Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 58830 Post Limited 85,000.00 67,872.75 Signed 2019-11-03 2019-10-03 2019-12-29 2019-12-11 2020-02-27 ent pour le renforcement des nd Information Systems tions nvelope unités mobiles de santé anim ale de Kankan et de Labé, Ki ndia et N'Zérékoré Page 2 GN-PASSP-119939-GO-RFQ / Achat de matériel de commu Component 1: Surveillance a Request for Quota Single Stage - One E nication : 300 smartphones p IDA / 58830 Post Limited 95,000.00 85,464.60 Signed 2020-02-17 2019-08-06 2020-04-13 2019-09-30 2020-06-12 nd Information Systems tions nvelope our les Agents du niveau co mmunautaire de la santé ani male GN-PASSP-120478-GO-RFB / Acquisition des kits d'urgenc Component 1: Surveillance a Open - Internationa Single Stage - One E Under Imple e et de riposte dans les quinz IDA / 58830 Prior Request for Bids 575,000.00 0.00 2020-01-23 2019-10-28 2020-01-28 2019-11-04 2020-03-10 2020-04-09 2020-05-14 2020-08-12 nd Information Systems l nvelope mentation e (15) districts sanitaires pou r la santé humaine, animale et environnementale GN-MOH-GUI-141032-GO-DI R / Acquisition d'un véhicule Component 1: Surveillance a IDA / 58830 Post Direct Selection Direct 25,000.00 24,097.19 Signed 2019-11-20 2019-11-11 2019-11-25 2019-11-11 2020-01-04 2019-11-26 2020-02-03 Pick-up double cabines 4x4 t nd Information Systems out terrain en faveur du Mini stère de l'Elevage GN-MOH-GUI-141978-GO-DI R / Accord avec UNOPS pour l Component 1: Surveillance a 'achat de 102 motocyclettes IDA / 58830 Post Direct Selection Direct 305,727.00 305,727.00 Completed 2019-12-10 2019-11-08 2019-12-15 2019-07-19 2020-01-19 2020-02-21 2020-08-08 2021-09-15 nd Information Systems YAMAHA AG 100 complémen taires pour les Agents du RE MAGUI GN-MOH-GUI-165522-GO-UN / Acquisition des équipement Component 1: Surveillance a UN Agencies (Dire s de protection individuelle e IDA / 58830 Prior Direct 1,550,000.00 1,947,962.00 Signed 2020-04-10 2020-03-24 2020-04-15 2020-03-31 2020-05-20 2020-04-08 2020-11-16 nd Information Systems ct) t des kits d'hygiène avec UNI CEF pour l'urgence sanitaire du COVID 19 GN-MOH-GUI-165546-GO-UN / Acquisition de logiciel GO D ATA, du matériel de réanimat Component 2: Strengthening UN Agencies (Dire IDA / 58830 Prior Direct 1,900,000.00 1,600,792.00 Signed 2020-04-13 2020-03-26 2020-04-18 2020-03-30 2020-05-23 2020-04-08 2020-11-19 ion, matériel et intrant de lab of Laboratory Capacity ct) oratoire avec OMS pour l'Urg ence sanitaire du COVID 19 GN-MOH-GUI-167247-GO-UN / Convention pour la fournitur e du matériel roulant (véhicul Component 1: Surveillance a UN Agencies (Dire IDA / 58830 Post Direct 600,000.00 735,197.00 Signed 2020-04-28 2020-04-03 2020-05-03 2020-04-03 2020-06-07 2020-05-06 2020-12-04 es et Ambulances) pour la ré nd Information Systems ct) ponse à la Pandémie de COVI D-19 En République de Guiné e avec UNICEF GN-MOH-GUI-171668-GO-DI R / Acquisition des matériels et consommables pour l'exte Component 1: Surveillance a nsion de deux (2) CT-EPI (Ke IDA / 58830 Post Direct Selection Direct 375,000.00 512,805.31 Completed 2020-05-20 2020-05-04 2020-05-25 2020-05-04 2020-06-29 2020-05-20 2020-08-28 2020-06-09 nd Information Systems nien et Gbessia) de Conakry pour la riposte au COVID 19 en entente directe avec la So ciété 2HK Equipements et Se rvices GN-MOH-GUI-172561-GO-RF Q / Acquisition de kits de sur veillance (registres de notific Component 1: Surveillance a Request for Quota Single Stage - One E ation, Bottes, Imperméables, IDA / 58830 Post Limited 45,000.00 33,157.09 Completed 2020-09-26 2020-06-18 2020-11-21 2020-08-05 2020-12-21 2020-09-03 nd Information Systems tions nvelope Stylos, Sac à dos et torches) pour les 270 conservateurs de la nature pour l'Environne ment GN-MOH-GUI-172563-GO-RF Q / Acquisition et installation de 8 chaînes de froid solaire Component 1: Surveillance a Request for Quota Single Stage - One E en faveur des 3 Direction Pré IDA / 58830 Post Limited 98,000.00 91,960.31 Completed 2020-10-03 2020-07-10 2020-11-28 2020-09-22 2021-01-27 2021-04-21 nd Information Systems tions nvelope fectorales de l'Elevage et Postes d'Inspections Frontali ers (PIFs) GN-MOH-GUI-172567-GO-RF Q / Acquisition de kits de prél èvement dans le cadre de la Component 2: Strengthening Request for Quota Single Stage - One E IDA / 58830 Post Limited 30,000.00 29,555.43 Completed 2020-10-10 2021-01-25 2020-12-05 2021-03-20 2021-03-05 2021-06-23 surveillance des maladies Zo of Laboratory Capacity tions nvelope onotiques par le REMAGUI po ur les 33 Directions Préfector ales de l’Élevage GN-MOH-GUI-172568-GO-RF Q / Acquisition et installation du matériel informatique (34 Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 58830 Post Limited 95,000.00 54,405.30 Completed 2020-10-17 2020-07-02 2020-12-12 2020-09-03 2021-02-10 2020-10-08 ordinateurs fixes et 38 impri nd Information Systems tions nvelope mantes multifonction) pour l es 34 services vétérinaires pr éfectoraux GN-MOH-GUI-172570-GO-UN / Acquisition des équipement s, consommables et réactifs Component 2: Strengthening UN Agencies (Dire Pending Impl pour les laboratoires de l'INS IDA / 58830 Post Direct 686,239.00 0.00 2020-10-20 2020-10-25 2020-11-29 2021-11-29 of Laboratory Capacity ct) ementation P, de LFH, du LCVD, des 3 hô pitaux Nationaux, régionaux, préfectoraux et Centres de s anté en entente directe avec UNICEF GN-MOH-GUI-172573-GO-RF Q / Acquisition de 3 motocyc Component 2: Strengthening Request for Quota Single Stage - One E lettes tout terrain de liaison IDA / 58830 Post Limited 12,000.00 7,890.21 Completed 2020-07-18 2020-05-11 2020-09-12 2020-06-12 2020-10-12 2020-07-22 of Laboratory Capacity tions nvelope pour le transport des échantil lons en faveur du laboratoire de l'INSP GN-MOH-GUI-172581-GO-RF Q / Achat de 13 Ordinateurs portables pour le personnel d Component 5: Institutional C 'Appui dont : 1 Assistante CN apacity Building, Project Ma Request for Quota Single Stage - One E , 3 Secrétaires, 1 APM, 5 Com IDA / 58830 Post Limited 36,000.00 20,943.15 Completed 2020-06-30 2020-05-15 2020-08-25 2020-06-05 2020-10-24 2021-06-16 nagement, Coordination, an tions nvelope ptables, 1 Auditeur Interne, 1 d Advocacy Consultant Communication, 1 Sauvegarde Sociale) et ac cessoires (6 Disque Externe de 1 Téra, 6 Casques, 6 Pack sT GN-MOH-GUI-172584-GO-RF Q / Achat de Kits de Lavage d es Mains et Savons pour la s anté humaine, animale et en Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 58830 Post Limited 10,000.00 10,549.21 Completed 2020-06-30 2020-07-28 2020-08-25 2020-09-10 2020-09-24 2020-11-03 vironnementale (10 000 Kits nd Information Systems tions nvelope 30 000 morceaux de Savons) , Kit de protection individuell e (masque, gel Hydroalcooliq ue) et 50 Thermoflash Page 3 GN-MOH-GUI-172609-GO-RF Q / Acquisition et installation de 2 chambres froides 1 à te Component 2: Strengthening Request for Quota Single Stage - One E IDA / 58830 Post Limited 95,000.00 93,915.12 Completed 2020-11-10 2020-06-22 2021-01-05 2020-08-27 2021-03-06 2021-05-18 mpérature positive et l'autre of Laboratory Capacity tions nvelope à température négative pour le laboratoire de la Direction Nationale de l'Elevage (DNSV ) GN-MOH-GUI-174571-GO-DI R / acquisition des écouvillon s avec milieux de transport e Component 2: Strengthening IDA / 58830 Post Direct Selection Direct 105,000.00 105,000.00 Terminated 2020-06-30 2020-05-25 2020-07-05 2020-05-26 2020-08-09 2020-07-02 2020-09-23 n Turquie avec la Société SE of Laboratory Capacity NTROMER DNA TEKNOLOLEJI LERI Ltd. Sti pour l'urgence s anitaire du COVID 19 GN-MOH-GUI-174841-GO-DI R / Acquisition du matériel ro ulant dont 10 Pick-up 4x4 do uble cabines et 10 Minibus 1 Component 1: Surveillance a IDA / 58830 Post Direct Selection Direct 620,000.00 648,781.95 Terminated 2020-06-07 2020-05-27 2020-06-12 2020-05-28 2020-07-17 2020-07-09 2020-08-16 5 places en faveur de l'Agenc nd Information Systems e Nationale de Sécurité Sanit aire (ANSS) avec ETOILE MOT ORS GUINÉE pour la riposte d u COVID 19 GN-MOH-GUI-190064-GO-DI R / Acquisition des équipeme Component 1: Surveillance a nts de protection individuelle IDA / 58830 Post Direct Selection Direct 1,160,000.00 915,811.30 Completed 2020-09-30 2020-09-04 2020-10-05 2020-09-14 2020-11-09 2020-11-20 2020-12-24 2021-02-25 nd Information Systems et matériels sanitaires en fav eur des CTEPI avec AFRICA H EALTH CARE PHARMA Sarl GN-MOH-GUI-190072-GO-DI R / Acquisition des médicame Component 1: Surveillance a nts, kits d'hygiène et kits de IDA / 58830 Prior Direct Selection Direct 4,300,000.00 3,836,726.37 Signed 2020-09-28 2020-10-14 2020-10-03 2020-11-23 2020-11-07 2021-02-25 2021-02-05 nd Information Systems protection individuelle en fav eur des CTEPI avec la SOGUI PREM GN-MOH-GUI-189601-GO-DI R / Fourniture et installation Component 1: Surveillance a de deux (2) Chapiteaux avec IDA / 58830 Post Direct Selection Direct 509,129.00 497,125.60 Completed 2020-10-19 2020-09-24 2020-10-24 2020-09-24 2020-11-28 2020-11-18 2021-01-27 2021-01-12 nd Information Systems la Pâtisserie 2 Octobre pour l a lutte contre la pandémie de coronavirus en Guinée GN-MOH-GUI-189603-GO-DI R / Achat de 80.000 tests rap Component 1: Surveillance a ides COVID-19 avec le fourni IDA / 58830 Post Direct Selection Direct 879,200.00 899,671.42 Completed 2020-10-19 2020-09-24 2020-10-24 2020-09-30 2020-11-28 2020-11-18 2021-01-12 2021-02-05 nd Information Systems sseur LAMART MD/TT, sis au Quartier Dixinn, Conakry, Ré publique de Guinée GN-PASSP-120447-GO-RFQ / Acquisition des réactifs et co nsommables pour les apparei Component 2: Strengthening Request for Quota Single Stage - One E Under Imple IDA / 58830 Post Limited 85,000.00 0.00 2021-09-29 2022-07-07 2021-11-24 2022-01-08 ls VIDAS des 7 HR dans le ca of Laboratory Capacity tions nvelope mentation dre de la surveillances des M aladies à potentiel épidémiqu e GN-PASSP-28110-GO-RFQ / Acquisition des kits de diagn ostic moléculaire (amorces) d es maladies prioritaires y co Component 2: Strengthening Request for Quota Single Stage - One E IDA / 58830 Post Limited 95,800.00 108,584.46 Signed 2021-10-30 2021-06-07 2021-12-25 2021-12-23 2022-03-25 mpris les zoonoses et équipe of Laboratory Capacity tions nvelope ments (3 chaines Elisa) et ré actifs pour les laboratoires ré gionaux et central vétérinair e et des Kits PCR pour l'ISSM V GN-PASSP-28083-GO-RFQ / Acquisition de deux (2) incin Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl érateurs solaires en faveur d IDA / 58830 Post Limited 45,600.00 0.00 2021-10-05 2021-11-30 2022-01-14 of Laboratory Capacity tions nvelope ementation es hôpitaux préfectoraux de Dalaba et de Macenta é GN-PASSP-28561-GO-RFQ / Achat, transport et installatio n de chaines de froid solaire 8 zones d'élevage: Ditinn (Da Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 58830 Post Limited 98,500.00 106,407.31 Signed 2018-08-25 2021-06-01 2018-10-20 2021-07-17 2019-01-18 laba), Banora (Dinguiraye), K nd Information Systems tions nvelope akony (Gaoual), Sangareya ( Pita), Dabola Centre, Senko ( Beyla), Donghol Sigon (Mali), Macenta Centre GN-PASSP-28580-GO-RFB / A cquisition et installation de m obilier de bureau pour les bur Component 1: Surveillance a Single Stage - One E eaux de tous les niveaux (co IDA / 58830 Post Request for Bids Open - National 663,000.00 0.00 Canceled 2017-12-18 2017-12-23 2018-02-03 2018-03-05 2018-04-09 2018-07-08 nd Information Systems nvelope mmunautaire, sous/préfector al, préfectoral et régional ) e n faveur de la Santé Humain e et de la Santé Animale GN-PASSP-115251-GO-RFQ / Acquisition de kit de surveilla nce (registres de notification, Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 58830 Post Limited 75,000.00 70,618.75 Completed 2019-11-22 2021-05-26 2020-01-17 2021-07-01 2020-02-16 2021-07-20 Bottes, Imperméables, Stylos nd Information Systems tions nvelope , Sac à dos, etc,) en faveur d e 1000 AC de la santé animal e GN-MOH-GUI-227270-GO-RF Q / Achat et installation de 2 2 ordinateurs dont 15 portabl Component 1: Surveillance a Request for Quota Single Stage - One E es et 7 fixes ainsi que l'acqui IDA / 58830 Post Limited 75,000.00 60,834.49 Completed 2021-06-30 2021-05-27 2021-08-25 2021-07-02 2021-10-24 2022-03-04 nd Information Systems tions nvelope sition d'un photocopieur gran d modèle et vidéoprojecteurs en faveur de la DNGE-LM, l' OGUIPAR et de la DNSV GN-MOH-GUI-227273-GO-RF Q / Acquisition de kits d'éner Component 1: Surveillance a Request for Quota Single Stage - One E gie solaire pour le fonctionne IDA / 58830 Post Limited 98,000.00 105,661.41 Signed 2021-06-20 2021-05-28 2021-08-15 2021-08-03 2021-11-13 nd Information Systems tions nvelope ment du matériel informatiqu e en faveur des 33 Directions Préfectorales de l'Elevage GN-MOH-GUI-227274-GO-RF Q / Acquisition de deux (2) vé Component 2: Strengthening Request for Quota Single Stage - One E hicules Pick Up 4 x 4 en fave IDA / 58830 Post Limited 78,500.00 89,927.96 Completed 2021-08-23 2021-05-31 2021-09-29 2021-07-31 2021-12-28 2022-03-09 of Laboratory Capacity tions nvelope ur des laboratoires vétérinair es régionaux de Kankan et L abé GN-MOH-GUI-227277-GO-DI R / Acquisition d'un séquence Component 1: Surveillance a Pending Impl ur de coronavirus en faveur d IDA / 58830 Post Direct Selection Direct 250,000.00 0.00 2021-06-14 2021-06-19 2021-07-24 2021-09-22 nd Information Systems ementation e l'ANSS avec la Maison du M édecin et du Paramédical Page 4 GN-MOH-GUI-297927-GO-RF Q / Doter les 450 AC de la sa nté animale et 205 Conserva Component 1: Surveillance a Request for Quota Single Stage - One E teurs de la nature en kit de s IDA / 58830 Post Limited 85,000.00 0.00 Completed 2022-09-04 2022-07-06 2022-10-30 2022-12-29 nd Information Systems tions nvelope urveillance (registres de notif ication, Bottes, Imperméable s, Stylos, Sac à dos, torches, boites médicales, gants, jum elles) GN-MOH-GUI-297934-GO-RF Q / Acquisition des réactifs et matériel pour l'évaluation ext erne de la qualité des laborat Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 58830 Post Limited 98,500.00 0.00 2022-07-27 2022-09-21 2022-12-20 oires (méningite et Choléra), of Laboratory Capacity tions nvelope ementation de l'étude pour la prévalence de l'arbovirose, la surveillanc e de la RAM et des équipeme nts pour le laboratoire nation al GN-MOH-GUI-326585-GO-RF Q / Fourniture des Kits EPI (m asque de protection, respirat oire de type FFP, gants (M; L; Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 58830 Post Limited 95,000.00 0.00 Completed 2022-12-20 2022-12-12 2023-02-14 2023-04-15 XL et XLL), blouse tyvek, calo nd Information Systems tions nvelope tte, imperméables, bottes et couvre botte) pour la surveill ance active et passive dans l es fermes infestées GN-MOH-GUI-326593-GO-RF B / Acquisition de matériel ro ulant dont :: 390 motos pour la surveillance active en fave Component 1: Surveillance a Direct - Internation Under Imple IDA / 58830 Post Direct Selection 1,300,000.00 0.00 2022-12-27 2022-11-22 2023-01-01 2022-12-01 2023-02-05 2023-08-04 ur des chefs de Poste d'éleva nd Information Systems al mentation ge et conservateurs des sites RAMSAR et 4 véhicules Pick Up TT pour la coordination in tervention avec UNOPS GN-MOH-GUI-326601-GO-RF Q / Acquisition et installation du matériel informatique pou Component 1: Surveillance a Request for Quota Single Stage - One E Pending Impl IDA / 58830 Post Limited 98,500.00 0.00 2023-01-25 2023-03-22 2023-05-21 r la Direction Nationale des S nd Information Systems tions nvelope ementation ervices Vétérinaires , la Direc tion Nationale des Epidémies et l'UGP GN-MOH-GUI-326602-GO-RF Q / Acquisition du matériel d e communication téléphones Component 1: Surveillance a Request for Quota Single Stage - One E Pending Impl IDA / 58830 Post Limited 25,000.00 0.00 2023-01-25 2023-03-22 2023-05-06 et tablettes pour le Service N nd Information Systems tions nvelope ementation ational de la Promotion de la Santé, la Direction National d es Epidémies et l'UGP. GN-MOH-GUI-326605-GO-RF Q / Acquisition et installation de mobiliers de bureaux pour Component 1: Surveillance a Request for Quota Single Stage - One E Pending Impl 28 points focaux de la promo IDA / 58830 Post Limited 75,000.00 0.00 2023-02-28 2023-04-25 2023-10-22 nd Information Systems tions nvelope ementation tion de la santé-communicati on (PFPS) des districts des ré gions de Boké, Conakry, Fara nah, N'Zérékoré, Mamou et L abé. GN-MOH-GUI-326609-GO-RF Q / Acquisition de matériels, Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 58830 Post Limited 62,550.00 0.00 2023-03-04 2023-04-29 2023-07-28 consommables et réactifs de of Laboratory Capacity tions nvelope ementation laboratoire pour le LCVD et l'I NSP GN-MOH-GUI-326612-GO-RF Q / Acquisition des kits de pr Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 58830 Post Limited 70,019.00 0.00 2023-03-26 2023-05-21 2023-07-20 élèvements pour les Unités M of Laboratory Capacity tions nvelope ementation obiles de Surveillance Animal e GN-MOH-GUI-326614-GO-DI R / Acquisition des vaccins an tirabiques et des équipement Component 3: Preparedness Direct - Internation Pending Impl IDA / 58830 Post Direct Selection 525,141.00 0.00 2023-01-06 2023-01-11 2023-02-15 2023-08-14 s connexes pour la santé hu and Emergency Response al ementation maine et animale en entente directe avec une Institution s pécialisée GN-MOH-GUI-349960-GO-DI R / Contrat avec TANE CORP Component 1: Surveillance a Under Imple IDA / 58830 Post Direct Selection Direct - National 72,600.00 0.00 2023-05-10 2023-05-28 2023-05-15 2023-06-09 2023-08-08 ORATION pour l'acquisition d nd Information Systems mentation e 2 véhicules Pick-up Double Cabines Tout Terrain GN-MOH-GUI-364040-GO-DI R / Acquisition de 390 motos pour la surveillance active en Component 1: Surveillance a Pending Impl faveur des chefs de Poste d'é IDA / 58830 Post Direct Selection Direct - National 695,000.00 0.00 2023-06-05 2023-06-07 2023-06-27 2023-08-26 nd Information Systems ementation levage des Communes rurale s et urbaines du pays et les 1 2 conservateurs des sites RA MSAR avec les Ets ABB. GN-MOH-GUI-364792-GO-DI R / Convention avec OMS pou Component 1: Surveillance a Pending Impl r l'achat de vaccins antirabiq IDA / 58830 Post Direct Selection Direct - National 91,782.00 0.00 2023-06-15 2023-06-20 2023-06-30 2023-08-29 nd Information Systems ementation ues humaines en faveur du M inistère de la Santé et de l'Hy giène Publique NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GN-PASSP-28605-NC-DIR / R Component 5: Institutional C ecrutement d'un Prestataire apacity Building, Project Ma Request for Quota Single Stage - One E de Services pour l'entretien e IDA / 58830 Post Limited 15,000.00 14,828.75 Completed 2018-03-18 2018-06-04 2018-05-13 2018-08-09 2018-06-12 2019-01-07 nagement, Coordination, an tions nvelope t la réparation des équipeme d Advocacy nts informatiques de REDISS E et du PASSP GN-PASSP-28609-NC-DIR / C ontrat avec DK Courtage pou r l'assurance du personnel co Component 5: Institutional C ntractuel et le matériel roula apacity Building, Project Ma IDA / 58830 Post Direct Selection Direct 30,000.00 24,463.56 Completed 2018-04-18 2018-04-30 2018-04-23 2018-05-28 2018-09-26 2018-06-27 2018-09-28 nt du REDISSE. DK courtage nagement, Coordination, an est recruté par le PASSP et fo d Advocacy urnira les mêmes services au REDISSE sur la base des mê mes prix unitaires. Page 5 GN-PASSP-115282-NC-RFQ / Edition et production des ma gazines/affiches/spots publici taires sur les maladies à pote Component 1: Surveillance a Request for Quota Single Stage - One E Pending Impl IDA / 58830 Post Limited 62,000.00 0.00 2019-12-03 2020-01-28 2020-03-13 ntiel épidémique pour la sant nd Information Systems tions nvelope ementation é humaine, animale et enviro nnementale et édition des ou tils de gestion pour les centr es de surveillance de la faun e sauvage GN-PASSP-115298-NC-RFQ / Component 5: Institutional C Request for Quota Single Stage - One E Confection des Agendas, Cal IDA / 58830 apacity Building, Project Ma Post Limited 30,000.00 27,320.89 Signed 2019-10-12 2019-11-11 2019-12-07 2019-12-20 2020-01-21 tions nvelope endriers et Cartes de meilleu nagement, Coordination, an rs vœux 2020 d Advocacy GN-PASSP-119934-NC-RFQ / Edition et impression des out Component 5: Institutional C ils de gestion financière pour apacity Building, Project Ma Request for Quota Single Stage - One E Pending Impl les Directions Préfectorales e IDA / 58830 Post Limited 15,000.00 0.00 2020-01-22 2020-03-18 2020-04-17 nagement, Coordination, an tions nvelope ementation t les Directions Régionales d d Advocacy e la Santé (fiche pour la tenu e de la comptabilité des struc tures) GN-MOH-GUI-172571-NC-RF Q / Elaborer des messages cl Component 4: Human Resou és, des outils et des supports rce Management for Effectiv Request for Quota Single Stage - One E Pending Impl IDA / 58830 Post Limited 95,000.00 0.00 2020-09-05 2020-10-31 2020-12-15 de communication accessible e Disease Surveillance and E tions nvelope ementation s aux communautés sur les pidemic Preparedness. maladies à potentiel épidémi ques GN-MOH-GUI-172576-NC-RF Q / Produire des matériels d e communication et d'outils d'engagement communautai Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 58830 Post Limited 85,000.00 37,830.01 Signed 2020-11-21 2021-08-24 2021-01-16 2022-02-08 2021-03-17 res sur les événements de sa nd Information Systems tions nvelope nté humaine, animale et envi ronnementale pour le Chang ement Social et Comporteme nt (CSC) des populations GN-MOH-GUI-172578-NC-RF Component 5: Institutional C Q / Edition et Confection des apacity Building, Project Ma Request for Quota Single Stage - One E IDA / 58830 Post Limited 28,500.00 26,987.36 Completed 2020-09-20 2019-11-11 2020-11-15 2019-12-20 2021-01-14 2021-02-09 Agendas, Calendriers et Cart nagement, Coordination, an tions nvelope es de meilleurs vœux 2021 d Advocacy GN-MOH-GUI-172583-NC-RF Q / Produire des matériels d e Visibilité sur la réponse au COVID 19 en Santé humaine, Component 1: Surveillance a Request for Quota Single Stage - One E Pending Impl IDA / 58830 Post Limited 65,000.00 0.00 2020-11-21 2021-01-16 2021-03-17 animale et environnementale nd Information Systems tions nvelope ementation pour le Bénéficiaire (MS) (Pa nneaux, Affiches, dépliants, Cartable, Kakemono, etc.) po ur renforcer la communicatio n et la visibilité GN-MOH-GUI-172619-NC-DIR / Location de tentes et acces soires (électricité, système d e ventilation et assainisseme Component 1: Surveillance a IDA / 58830 Post Direct Selection Direct 35,000.00 172,380.30 Completed 2020-06-05 2020-05-08 2020-06-10 2020-05-11 2020-07-15 2020-07-07 2020-10-13 2020-07-24 nt) pour servir de sites de pri nd Information Systems se en charge des cas COVID 19 au Centre Pénitencier de Conakry avec ISSA Tapisserie pour 3 mois de location GN-MOH-GUI-297932-NC-RF Q / Prestataire de service po ur la reproduction du Guide S Component 1: Surveillance a Request for Quota Single Stage - One E IMR (Système Intégré des Ma IDA / 58830 Post Limited 25,000.00 0.00 Completed 2022-08-30 2022-09-08 2022-10-25 2022-12-24 nd Information Systems tions nvelope ladies et Riposte) révisé au ni veau du Centre de Santé pou r les régions de Boké, Kindia et Conakry GN-MOH-GUI-297939-CS-IND Component 5: Institutional C V / Recrutement d'un Prestat apacity Building, Project Ma Request for Quota Single Stage - One E Pending Impl aire pour la réalisation d'un fi IDA / 58830 Post Limited 18,000.00 0.00 2022-09-20 2022-11-15 2023-01-14 nagement, Coordination, an tions nvelope ementation lm documentaire de 20 minu d Advocacy tes sur le Projet REDISSE CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GN-PASSP-28115-CS-QCBS / Recrutement d'un bureau d'é tudes d'ingénierie civil pour l Component 1: Surveillance a Quality And Cost- IDA / 58830 Post Open - National 80,000.00 162,233.89 Signed 2017-09-27 2018-01-15 2017-10-18 2018-02-01 2017-12-01 2018-03-05 2017-12-29 2018-04-12 2018-01-28 2018-04-12 2018-03-04 2018-05-09 2018-04-08 2018-06-21 2019-04-08 es études et le contrôle des t nd Information Systems Based Selection ravaux de construction et la r énovation de laboratoires et PIF GN-MOH-GUI-145099-CS-QC BS / Recrutement d'un Cabin Component 5: Institutional C et/Bureau pour l'Audit extern apacity Building, Project Ma Quality And Cost- Open - Internationa e des comptes du Projet Régi IDA / 58830 Post 45,000.00 18,000.00 Signed 2019-12-20 2019-12-04 2020-01-09 2020-01-20 2020-02-12 2020-03-03 2020-03-03 2020-04-14 2020-03-23 2020-04-14 2020-04-21 2020-06-02 2020-05-15 2020-07-29 2022-06-30 nagement, Coordination, an Based Selection l onal d'Amélioration des Syst d Advocacy èmes de Surveillance des Ma ladies en Afrique de l'Ouest ( REDISSE) GN-MOH-GUI-165564-CS-UN / Assistance Technique avec UNICEF pour le recrutement Component 1: Surveillance a UN Agencies (Dire Pending Impleme IDA / 58830 Post Direct 85,000.00 0.00 2020-06-01 2020-11-28 de : 2 Spécialistes Socio Ant nd Information Systems ct) ntation hropologue et 1 Spécialiste e n Communication pour l'urge nce sanitaire du COVID 19 GN-MOH-GUI-165558-GO-UN / Assistance technique avec OMS pour recrutement de six (6) spécialistes : 1 statisticie Component 1: Surveillance a UN Agencies (Dire n, 1 informaticien, 1 technici IDA / 58830 Post Direct 185,000.00 193,670.00 Signed 2020-05-18 2020-05-07 2020-11-14 nd Information Systems ct) en de laboratoire, 1 pneumol ogue, 1 Spécialiste en Réani mation et 1 Expert en Logisti que dans le cadre de l'urgenc e sanitaire du COVID 19 Page 6 GN-MOH-GUI-171996-CS-UN / Assistance Technique en Co mmunication Pour le Dévelop Component 1: Surveillance a UN Agencies (Dire IDA / 58830 Post Direct 409,336.00 409,336.00 Signed 2020-07-04 2020-05-15 2021-07-04 pement et en Socio-Anthropo nd Information Systems ct) logie avec l'UNICEF dans le c adre de l'urgence sanitaire d u COVID 19 GN-MOH-GUI-278076-CS-CQ S / Recrutement d’un Cabinet pour l’élaboration de la Notic e d’Impact Environnemental Component 2: Strengthening Consultant Qualifi Open - Internationa Pending Impleme IDA / 58830 Post 75,000.00 0.00 2022-02-28 2022-03-21 2022-05-04 2022-06-03 2022-07-08 2022-08-07 et Social( NIES) du projet de of Laboratory Capacity cation Selection l ntation construction du laboratoire v étérinaire P2+ dans la Sous- préfecture de Kouriyah (Préfe cture de Coyah) GN-MOH-GUI-297936-CS-QC Component 5: Institutional C BS / Recrutement d'un Cabin apacity Building, Project Ma Quality And Cost- IDA / 58830 Post Open - National 15,000.00 0.00 Canceled 2022-07-15 2022-08-05 2022-09-18 2022-10-16 2022-11-15 2022-12-20 2023-01-24 2024-01-24 et pour l'audit externe des co nagement, Coordination, an Based Selection mptes du REDISSE exercice 2 d Advocacy 022 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GN-PASSP-28094-CS-INDV / Recrutement d'un Consultant National pour l'élaboration d' Component 2: Strengthening Individual Consult IDA / 58830 Post Limited 40,000.00 13,786.64 Signed 2017-11-20 2019-06-24 2017-11-25 2019-07-01 2017-12-16 2020-03-03 2018-01-20 2020-03-31 2018-02-19 un manuel de procédures sta of Laboratory Capacity ant Selection ndads des différentes unités du laboratoire dans l'approch e One Health GN-PASSP-28112-CS-INDV / Recrutement d'un Consultant pour déterminer les caractéri Component 2: Strengthening Individual Consult Under Implement IDA / 58830 Post Open 60,000.00 0.00 2017-10-30 2018-02-01 2017-12-18 2018-01-08 2018-02-12 2018-04-13 stiques techniquqes pour le n of Laboratory Capacity ant Selection ation ouveau laobratoire national d e diagnostic véterinaire nive au P2 GN-PASSP-28493-CS-INDV / Recrutement d'un Consultant Component 1: Surveillance a Individual Consult pour l'actualisation du manu IDA / 58830 Post Limited 20,000.00 13,722.70 Completed 2018-05-21 2019-05-16 2018-05-26 2019-05-05 2018-06-16 2019-07-22 2018-07-21 2019-07-22 2018-08-20 2020-02-05 nd Information Systems ant Selection el de protocole de surveillanc e au niveau des abattoirs des maladies prioritaires GN-PASSP-28496-CS-INDV / Component 5: Institutional C Recrutement d'un Consultant apacity Building, Project Ma Individual Consult International pour l'élaborati IDA / 58830 Post Limited 60,000.00 45,176.00 Completed 2018-06-06 2018-03-27 2018-06-11 2018-04-02 2018-07-02 2018-05-29 2018-08-06 2018-06-21 2018-09-05 2018-09-28 nagement, Coordination, an ant Selection on d'une stratégie de commu d Advocacy nication en santé humaine et animale GN-PASSP-28497-CS-INDV / Recrutement d'un Consultant Component 5: Institutional C National pour appuyer le Co apacity Building, Project Ma Individual Consult IDA / 58830 Post Open 15,000.00 7,390.50 Completed 2018-06-06 2018-05-14 2018-07-25 2018-06-22 2018-08-15 2018-07-10 2018-09-19 2018-07-30 2018-10-19 2019-02-11 nsultant International dans l' nagement, Coordination, an ant Selection élaboration d'une stratégie d d Advocacy e communication en santé h umaine et animale GN-PASSP-71189-CS-INDV / Recrutement d'un Consultant Component 1: Surveillance a Individual Consult IDA / 58830 Post Open 18,000.00 24,000.00 Signed 2019-02-26 2018-12-17 2019-04-16 2019-05-17 2019-05-07 2019-05-22 2019-06-11 2019-06-13 2020-06-05 Conseiller technique (Assista nd Information Systems ant Selection nt à la Coordination Une Seul e Santé) GN-PASSP-82468-CS-INDV / Recrutement d'un Consultant International pour le renforce Component 2: Strengthening Individual Consult ment des capacités des labor IDA / 58830 Post Open 100,000.00 115,350.00 Signed 2018-12-16 2019-06-14 2019-02-03 2019-07-30 2019-02-24 2019-09-11 2019-03-31 2019-09-11 2020-03-31 of Laboratory Capacity ant Selection atoires de Guinée dans le ca dre de la surveillance et de la riposte (plan directeur 2018- 2022) GN-PASSP-119926-CS-CDS / Recruter AFNET (Réseau Afri Component 4: Human Resou cain d’Epidémiologie de Terr rce Management for Effectiv IDA / 58830 Post Direct Selection Direct 148,000.00 148,000.00 Completed 2019-11-20 2019-07-09 2019-11-30 2019-09-04 2020-02-03 2020-02-21 2021-02-02 2021-05-08 ain (African Field Epidemiolo e Disease Surveillance and E gy Network) pour former des pidemic Preparedness. cadres du Ministère de la San té en Épidémiologie de Terrai n GN-MOH-GUI-180928-CS-IND V / Recrutement d'un Consult Component 5: Institutional C ant pour l'évaluation à mi-pa apacity Building, Project Ma Individual Consult IDA / 58830 Post Open 10,000.00 10,586.73 Completed 2020-07-16 2020-07-27 2020-09-03 2020-09-02 2020-09-24 2020-09-08 2020-10-29 2020-09-09 2020-11-28 2020-12-19 rcours du Projet Régional d'A nagement, Coordination, an ant Selection mélioration des Systèmes de d Advocacy Surveillance des Maladies en Afrique de l'Ouest (REDISSE) GN-PASSP-115303-CS-INDV / Recrutement d'un Consultant Component 5: Institutional C National pour Formation en g apacity Building, Project Ma Individual Consult estion de Projet de 20 cadres IDA / 58830 Post Open 10,000.00 0.00 Canceled 2020-01-28 2020-03-17 2020-04-07 2020-05-12 2020-06-11 nagement, Coordination, an ant Selection des 3 ministères (8 Santé, 7 d Advocacy Élevage et 5 Environnement) impliqués dans la mise en oe uvre du Projet GN-PASSP-115304-CS-INDV / Recrutement d'un consultant Component 5: Institutional C National pour l'élaboration d' apacity Building, Project Ma Individual Consult Under Implement IDA / 58830 Post Open 25,000.00 0.00 2021-12-21 2022-04-27 2022-02-08 2022-03-01 2022-04-05 2022-05-05 un manuel de procédures sta nagement, Coordination, an ant Selection ation ndards des différentes unités d Advocacy des laboratoires vétérinaire GN-PASSP-71328-CS-INDV / Recruter un Consultant Natio Component 5: Institutional C nal pour évaluer les impacts apacity Building, Project Ma Individual Consult Under Implement de la communication des risq IDA / 58830 Post Open 45,000.00 0.00 2019-02-26 2022-08-03 2019-04-16 2019-05-07 2019-06-11 2019-07-11 nagement, Coordination, an ant Selection ation ues et d'engagement commu d Advocacy nautaire sur le changement d e comportement en lien avec le coronavirus GN-MOH-GUI-172603-CS-IND Component 5: Institutional C V / Recrutement d'un consult apacity Building, Project Ma Individual Consult Under Implement IDA / 58830 Post Open 30,000.00 0.00 2020-12-28 2021-02-15 2021-03-08 2021-04-12 2021-06-11 ant national pour la réalisatio nagement, Coordination, an ant Selection ation n d'une étude entomologique d Advocacy sur la Fièvre Jaune Page 7 GN-MOH-GUI-227275-CS-IND V / Recrutement d'un consult Component 2: Strengthening Individual Consult Under Implement ant pour élaborer les normes IDA / 58830 Post Open 25,000.00 0.00 2021-11-18 2022-04-27 2022-01-06 2022-01-27 2022-03-03 2022-04-17 of Laboratory Capacity ant Selection ation et procédures de gestion des déchets générés par les activ ités d'élevage GN-MOH-GUI-227276-CS-IND V / Recrutement d'un consult Component 5: Institutional C ant national pour créer une i apacity Building, Project Ma Individual Consult Under Implement nterface entre la Plateforme IDA / 58830 Post Open 35,000.00 0.00 2021-11-30 2022-08-03 2022-01-18 2022-02-08 2022-03-15 2022-05-14 nagement, Coordination, an ant Selection ation DHIS2 et la Plateforme EMPR d Advocacy ES-i utilisée par les services v étérinaires et la formation du personnel GN-MOH-GUI-300112-CS-IND V / Recrutement d'un Consult ant international dans le cadr Component 2: Strengthening Individual Consult Pending Impleme e de l'assurance qualité et de IDA / 58830 Post Open 150,000.00 0.00 2022-09-05 2022-10-24 2022-11-14 2022-12-19 2023-06-17 of Laboratory Capacity ant Selection ntation l'accréditation pour assurer u ne assistance technique à l'In stitut National de Santé Publi que (INSP) GN-PASSP-28499-CS-CDS / C ontrat avec le Cabinet Fiduci Component 5: Institutional C aire de Guinée membre Pwc apacity Building, Project Ma pour l'audit externe des com IDA / 58830 Post Direct Selection Direct 45,000.00 0.00 Canceled 2018-02-12 2018-02-22 2018-04-28 2018-08-26 nagement, Coordination, an ptes du REDISSE. Le Cabinet d Advocacy Pwc est recruté par la PASSP pour l'audit des Projets PASS P, REDISSE et PSRM GN-MOH-GUI-327538-CS-CD S / Recrutement du Groupem ent d’Expertise Comptable & Component 5: Institutional C Conseils (CE2C) et Panafricai apacity Building, Project Ma Direct - Internation IDA / 58830 Post Direct Selection 12,000.00 0.00 Signed 2023-01-16 2023-01-11 2023-01-26 2023-02-22 2023-04-01 2023-05-31 ne nagement, Coordination, an al d’Audit du Burkina (PANAUDI d Advocacy T – BURKINA) pour l'Audit ext erne des comptes du REDISS E (exercices 2022 et 2023) GN-MOH-GUI-349223-CS-IND V / Recrutement de d’un Con Component 4: Human Resou sultants National pour l’évalu rce Management for Effectiv Individual Consult Under Implement ation finale du Projet Régiona IDA / 58830 Post Open - National 25,000.00 0.00 2023-04-21 2023-03-23 2023-06-19 2023-07-10 2023-08-14 2023-09-28 e Disease Surveillance and E ant Selection ation l d'Amélioration des Système pidemic Preparedness. s de Surveillance des Maladie s en Afrique de l'Ouest (REDI SSE) Page 8 Summarized Procurement Plan Table 3.1. Main Works, Goods, and Non-Consulting Services to be Procured Estimated Domestic Ref Prior or Amount in Procureme Preferenc . Contract Description Post US$, nt Method e No. Review thousands (yes/no) OSS upgrade IT equipment (including 1 OSS software and 300 NCB No Post Investors Tracking System) FM software Direct 2 15 No Prior configuration Contracting 3 Vehicles for PCU and IC 500 NCB No Prior 4 Vehicles for API-Mali 180 Shopping No Post Furniture and computer 5 40 Shopping No Post equipment for PCU Rehabilitation of 300 km 6 of rural roads (100km in 7,500 NCB No Prior Sikasso, 200 in Yanfolila) Rehabilitation of three collection facilities (Sikasso) and 7 600 NCB No Post construction of three collection facilities (Yanfolila) Construction of a 8 conditioning and exports 1,000 NCB No Prior facility 9 API-Mali website 70 Shopping No Post Table 3.2. Main Consulting Assignments of the Project Estimat Review ed Selection by Bank Ref. No. Contract Description Amoun Method (Prior/Po t in st) US$ Component 1: Support Agribusiness Diversification through Mango Processing and Investment Promotion 1 TA support to mango nursery QCBS Post 150 Technical training to rural assemblers and TA support to IFM (rural 2 IC Prior 250 assemblers/brokers) and statistical database/geolocation Selection and supervision of cooperatives, 3 traders, and millers with connections to QCBS Prior 490 support contracting and implementation 1 Estimat Review ed Selection by Bank Ref. No. Contract Description Amoun Method (Prior/Po t in st) US$ Support for credit records, warranties, and 4 sources of funding for orchards and QCBS Prior 250 cooperatives Support supply exporters/millers, cooperatives OHADA assistance and legal 5 QCBS Prior 200 assistance contract production partnerships Support to exporters and millers on food 6 QCBS Post 200 safety, certification, and compliance (EU) Comparative studies of trade facilitation 7 QCBS Post 150 and export routes and recommendations Advisory support to exporters and millers 8 on logistics flows and contracting (trucks, IC Post 50 port, airports ) #1 Advisory support to exporters and millers 9 on logistics flows and contracting (trucks, IC Post 50 port, airports ) #2 Advisory support to exporters and millers 10 on logistics flows and contracting (trucks, IC Post 50 port, airports ) #3 Advisory support to exporters and millers 11 on logistics flows and contracting (trucks, IC Post 50 port, airports ) #4 12 Staff 1 API-Mali IC Prior 170 13 Staff 2 API-Mali IC Prior 170 14 Staff 3 API-Mali IC Prior 170 15 Staff 4 API-Mali IC Prior 170 16 Staff 5 API-Mali IC Prior 170 Component 2: Improve Access to Mango Production Areas Consultant for technical studies and specifications of 300 km of rural roads and 17 SSS Prior 500 preparation of bid documents and supervision of works 18 External technical audit of roads quality QCBS Post 150 Consultant for technical studies for the construction and rehabilitation of six 19 QC Post 35 collections facilities, preparation of bid documents, and supervision of works Consultant for technical studies and 20 specifications for the construction of QC Prior 90 conditioning and exports facility Component 3: Foster Animal Feed Production Trainings program for productive alliances 21 QBS Prior 540 consultants – BDS (training of trainers) Trainings program for productive alliances 22 consultants – Extension (training of QBS Prior 540 trainers) 23 TA for pre-investments activities QBS Prior 1,100 2 Estimat Review ed Selection by Bank Ref. No. Contract Description Amoun Method (Prior/Po t in st) US$ Consultant for technical studies for 24 equipment and infrastructure of all QC Prior 320 subprojects and supervision of works Component 4: Strengthen Institutional and Implementation Capacities 25 Procurement assistant IC Prior 150 26 Principal accountant IC Prior 180 27 Assistant accountant IC Prior 125 28 Project director IC Prior 230 29 Project assistant IC Post 40 30 Infrastructure specialist IC Prior 165 31 Financing specialist IC Prior 165 32 Value chains specialist IC Prior 165 33 Update of operations manual IC Prior 20 34 Institutional contractor QBS Prior 1,850 35 External auditor QCBS Prior 40 36 Assistant en suivi et evaluation IC Prior 125 ICB = International Competitive Bidding LIB = Limited International Bidding NCB = National Competitive Bidding Direct Contracting Shopping CQS = Selection Based on Consultants’ Qualifications FBS = Selection under a Fixed Budget LCS = Least-Cost Selection QBS = Quality-Based Selection QCBS = Quality- and Cost-Based Selection SSS = Single-Source Selection IC = Individual Consultant 3 PROCUREMENT Mali : Mali Support to Agroindustrial Competitiveness Project PLAN General Information Country: Mali 2017-10-02 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151449 GPN Date: 2018-03-19 Project Name: Mali Support to Agroindustrial Competitiveness Project Loan / Credit No: IDA / 59190 National Committee for Agricultural Research Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CW-REF-72 / Travaux de réh Component 1: Expand Mang Single Stage - One E Pending Imp 2018-08-0 abilitation /construction de T IDA / 59190 o Processing and Investment Post Request for Bids Open - National 850,000.00 0.00 2018-02-07 2018-02-10 2018-03-12 2018-03-22 2018-04-11 nvelope lementation 9 ubaniso Opportunities CW-REF-1 / Réhabilitation de Component 2: Improve Acce Single Stage - One E Under Imple 2018-06-2 IDA / 59190 Post Request for Bids Open - National 7,500,000.00 0.00 2017-12-20 2017-10-02 2017-12-23 2018-01-22 2017-11-21 2018-02-22 300km de routes rurales ss to Mango Production Area nvelope mentation 2 s CW-REF-3 / Construction et i Component 3: Foster Animal Single Stage - One E Pending Imp 2018-03-1 nstallation d'unités de conditi IDA / 59190 Post Request for Bids Open - National 350,000.00 0.00 2017-09-12 2017-09-17 2017-10-17 2017-10-24 2017-11-10 Feed Production nvelope lementation 0 onnement et d'exportation CW-REF-71 / Travaux d'amé Component 4: Strengthen Pr Request for Quota Single Stage - One E Pending Imp 2018-04-0 nagement des locaux du sièg IDA / 59190 Post Open - National 144,000.00 0.00 2018-02-18 2018-03-17 oject Implementation tions nvelope lementation 1 e du PACAM CW-REF-69 / Travaux de con Component 3: Foster Animal Single Stage - One E 2,100,344.1 2019-12-2 struction de 50 étables et ma IDA / 59190 Post Request for Bids Open - National 682,000.00 Signed 2019-01-24 2019-03-01 2019-02-08 2020-12-09 2019-03-22 2019-05-21 2019-04-21 2019-09-19 2019-05-26 2019-12-20 Feed Production nvelope 8 2 gasins dans le cadre du proje t LAHAM CW-REF-70 / Travaux de 50 f Component 3: Foster Animal Single Stage - One E 1,249,503.5 2019-12-2 orages positifs/ château d'ea IDA / 59190 Post Request for Bids Open - National 850,000.00 Signed 2019-01-24 2019-03-19 2019-02-08 2020-12-14 2019-03-22 2020-05-21 2019-04-21 2019-09-19 2019-05-26 2019-12-20 Feed Production nvelope 1 2 u et pompage solaire pour LA HAM. CW-REF-73 / Recruter de no uvelles entreprises pour réali ser le reste des travaux des l Component 2: Improve Acce Single Stage - One E 1,779,050.3 2021-07-2 ots 3 et 5 (Travaux d'achève IDA / 59190 ss to Mango Production Area Post Request for Bids Open - National 1,473,036.00 Completed 2021-01-20 2021-03-03 2021-01-25 2021-10-04 2021-02-27 2021-04-12 2021-03-20 2021-04-21 2021-04-24 2021-08-05 nvelope 8 3 ment) dans le cadre de la Ré s habilitation de 300 km de pis tes rurales dans les cercles d e Sikasso et Yanfolila. National Procure ML-CNRA-268119-CW-DIR / T ment Document - ravaux d'achèvement de neu Component 3: Foster Animal Single Stage - One E 2022-06-2 IDA / 59190 Post Request for Bids Open - National 1 Envelope proce 240,000.00 245,062.12 Signed 2022-01-17 2022-05-20 2022-01-22 2022-08-03 2022-03-05 2022-06-24 2022-04-04 2022-07-29 2022-05-09 2022-09-14 f (09) étables et neuf magasi Feed Production nvelope 3 ss (Non Bank-SPD ns (finalisation du lot2) ) National Procure ML-CNRA-328015-CW-RFQ / Component 1: Expand Mang ment Document - Travaux de réalisation de qu Request for Quota Single Stage - One E Under Imple 2023-04-0 IDA / 59190 o Processing and Investment Post Limited 1 Envelope proce 210,000.00 0.00 2022-12-10 2023-02-03 2023-02-04 atre forages dans le cercle d tions nvelope mentation 5 Opportunities ss (Non Bank-SPD e Yanfolila lot1 (type AES et ) SHVA) National Procure ML-CNRA-328017-CW-RFQ / Component 1: Expand Mang ment Document - Travaux de réalisation de qu Request for Quota Single Stage - One E Under Imple 2023-04-0 IDA / 59190 o Processing and Investment Post Limited 1 Envelope proce 160,000.00 0.00 2022-12-12 2023-02-06 2023-02-06 atre forages équipés dans le tions nvelope mentation 7 Opportunities ss (Non Bank-SPD cercle de Yanfolila lot2 types ) (AES et PMH). ML-CNRA-328024-CW-RFQ / National Procure Travaux de réalisation quatre Component 1: Expand Mang ment Document - Request for Quota Single Stage - One E Under Imple 2023-04-1 forages équipés communaut IDA / 59190 o Processing and Investment Post Limited 1 Envelope proce 175,000.00 0.00 2022-12-20 2023-03-06 2023-02-14 tions nvelope mentation 5 aires dans le Cercle de Sikas Opportunities ss (Non Bank-SPD so lot3 (AES,SHVA et PMH). ) ML-CNRA-328033-CW-RFQ / National Procure Travaux de réalisation de troi Component 1: Expand Mang ment Document - Request for Quota Single Stage - One E Under Imple 2023-04-1 s forages communautaires é IDA / 59190 o Processing and Investment Post Limited 1 Envelope proce 155,900.00 0.00 2022-12-17 2023-02-03 2023-02-11 tions nvelope mentation 2 quipés dans le cercle de Sika Opportunities ss (Non Bank-SPD sso lot 4 (SHVA et AES). ) National Procure ML-CNRA-328038-CW-RFQ / Component 1: Expand Mang ment Document - Travaux de réalisation de cin Request for Quota Single Stage - One E Under Imple 2023-04-0 IDA / 59190 o Processing and Investment Post Limited 1 Envelope proce 221,000.00 0.00 2022-12-10 2023-02-10 2023-02-04 q forages communautaires é tions nvelope mentation 5 Opportunities ss (Non Bank-SPD quipés dans les Cercles de K ) ati et Koulikoro lot5 ML-CNRA-306077-CW-RFB / National Procure Travaux de réalisation des fo Component 1: Expand Mang ment Document - Single Stage - One E 2023-01-2 rages équipés de pompes sol IDA / 59190 o Processing and Investment Post Request for Bids Open - National 1 Envelope proce 680,000.00 0.00 Canceled 2022-09-05 2022-09-10 2022-10-10 2022-10-20 2022-11-24 nvelope 3 aires pour les coopératives d Opportunities ss (Non Bank-SPD es pépiniéristes et des marai ) chers GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GO-REF-5 / Acquisition de m Component 4: Strengthen Pr Request for Quota Single Stage - One E Under Imple obilier et matériel informatiq IDA / 59190 Post Open - National 40,000.00 0.00 2017-07-17 2017-09-09 2017-10-09 oject Implementation tions nvelope mentation ue pour l'UPC GO-REF-11 / Achat d'équipe Component 3: Foster Animal Request for Quota Single Stage - One E Pending Impl IDA / 59190 Post Open - National 100,000.00 0.00 2017-07-15 2017-09-09 2017-11-08 ment individuels Feed Production tions nvelope ementation GO-REF-8 / Achat de produit s success appat pour le com Component 3: Foster Animal IDA / 59190 Post Direct Selection Direct 418,000.00 555,002.16 Completed 2017-06-21 2017-06-22 2017-07-05 2017-07-10 2017-07-29 2017-05-02 2017-08-02 2017-06-01 pte de l'Interprofession de la Feed Production filière mangue du Mali GO-REF-7 / Achat de produit s Invader B-Lok et M3 fruit Fl Component 3: Foster Animal IDA / 59190 Post Direct Selection Direct 648,000.00 704,635.10 Completed 2017-06-26 2017-06-27 2017-07-01 2017-08-21 2017-04-27 2017-10-05 2017-06-12 y Bait station pour le compte Feed Production de l'Interprofession de la filiè re mangue du Mali Page 1 GO-REF-9 / Equipement en Component 4: Strengthen Pr Request for Quota Single Stage - One E Pending Impl IDA / 59190 Post Open - National 97,000.00 0.00 2018-02-18 2018-03-22 2018-04-06 mobiliers de bureaux du sièg oject Implementation tions nvelope ementation e du PACAM GO-REF-16 / Achat de produi Component 1: Expand Mang ts vinaigre, croissange organi Pending Impl IDA / 59190 o Processing and Investment Post Direct Selection Direct 102,000.00 0.00 2018-02-13 2018-02-18 2018-03-07 2018-04-06 que pour le compte de l'Inter ementation Opportunities profession de la filière mangi e du Mali GO-REF-18 / Acquisition d'Eq Component 2: Improve Acce Request for Quota Single Stage - One E Pending Impl uipements : Bac de lavage, c IDA / 59190 ss to Mango Production Area Post Open - National 59,625.00 0.00 2019-02-22 2019-03-27 2019-04-26 tions nvelope ementation ageots de récolte et autres... s GO-REF-19 / Achat équipem Component 4: Strengthen Pr Request for Quota Single Stage - One E Pending Impl ents et consommables du bu IDA / 59190 Post Open - National 51,107.00 0.00 2019-01-16 2019-02-25 2019-12-22 oject Implementation tions nvelope ementation reau pour l'UCP GO-REF-25 / Accroissement Component 4: Strengthen Pr Request for Quota Single Stage - One E Pending Impl de la notoriété et la visibilité IDA / 59190 Post Limited 13,630.00 0.00 2020-01-20 2020-03-05 2020-12-30 oject Implementation tions nvelope ementation globale du PACAM GO-REF-23 / Acquisition d’éq Component 1: Expand Mang uipements de transformation Request for Quota Pending Impl IDA / 59190 o Processing and Investment Post 68,143.00 0.00 2020-04-18 2020-06-07 2020-09-05 et de production (Unités de tr tions ementation Opportunities ansformation et de productio n de plants) GO-REF-17 / Acquisition et D Component 2: Improve Acce otation de brigades villageois Request for Quota Single Stage - One E Under Imple IDA / 59190 ss to Mango Production Area Post Open - National 85,179.00 0.00 2021-04-14 2021-06-17 2021-09-15 e en équipement d'entretien tions nvelope mentation s et de maintenance GO-REF-26 / Acquisition et D Component 1: Expand Mang otation des sociétés coopérat Request for Quota Single Stage - One E Pending Impl IDA / 59190 o Processing and Investment Post Limited 17,036.00 0.00 2021-03-15 2021-05-10 2021-11-06 ives en matériels d’entretien tions nvelope ementation Opportunities des vergers de mangues GO-REF-24 / Acquisition de Component 3: Foster Animal Request for Quota Single Stage - One E Pending Impl matériels et équipements po IDA / 59190 Post Limited 9,660.00 0.00 2021-02-20 2021-04-10 2021-06-09 Feed Production tions nvelope ementation ur les 49 emboucheurs ML-CNRA-268126-GO-RFQ / Achat de matériels et équipe Component 1: Expand Mang Request for Quota Single Stage - One E Pending Impl ments d'entretien pour les u IDA / 59190 o Processing and Investment Post Limited 80,000.00 0.00 2022-02-06 2022-03-04 2022-04-03 tions nvelope ementation nités de production de mang Opportunities ues et brigades villageois ML-CNRA-268114-GO-DIR / A Component 1: Expand Mang chat des produits et traiteme IDA / 59190 o Processing and Investment Post Direct Selection Direct 800,000.00 0.00 Canceled 2022-01-10 2022-01-15 2022-02-19 2022-04-20 nts phytosanitaires des verg Opportunities ers des bassins de productio n de mangues ML-CNRA-306086-GO-RFQ / Acquisition d'équipements de Component 3: Foster Animal Request for Quota Single Stage - One E Pending Impl IDA / 59190 Post Limited 80,000.00 0.00 2022-08-20 2022-10-15 2022-11-14 broyeurs de pailles et access Feed Production tions nvelope ementation oires pour les emboucheurs ML-CNRA-331398-GO-RFQ / Component 2: Improve Acce Acquisition des matériels d'e Request for Quota Single Stage - One E Pending Impl IDA / 59190 ss to Mango Production Area Post Limited 142,500.00 0.00 2023-01-14 2023-03-11 2023-04-10 ntretien des vergers pour dot tions nvelope ementation s er les producteurs ML-CNRA-331401-GO-RFQ / Component 2: Improve Acce Acquisition d'équipements et Request for Quota Single Stage - One E Pending Impl IDA / 59190 ss to Mango Production Area Post Limited 130,000.00 0.00 2023-01-17 2023-03-14 2023-05-13 matériels de travail pour app tions nvelope ementation s uyer les exportateurs et les p isteurs ML-CNRA-331500-GO-RFQ / Réalisation de supports de co Component 4: Strengthen Pr Request for Quota Single Stage - One E Pending Impl IDA / 59190 Post Limited 8,500.00 0.00 2022-12-24 2023-02-18 2023-03-05 mmunication pour la visibilité oject Implementation tions nvelope ementation des activités (Goodies) ML-CNRA-331542-GO-RFQ / Component 2: Improve Acce Request for Quota Single Stage - One E Pending Impl Dotation des emboucheurs e IDA / 59190 ss to Mango Production Area Post Limited 10,000.00 0.00 2023-01-15 2023-03-12 2023-03-27 tions nvelope ementation n semences de cultures fourr s agères ML-CNRA-338735-GO-RFQ / Component 2: Improve Acce Request for Quota Single Stage - One E Pending Impl Acquisition d'équipements po IDA / 59190 ss to Mango Production Area Post Limited 250,000.00 0.00 2023-02-06 2023-04-03 2023-05-03 tions nvelope ementation ur les Unités de transformati s on . ML-CNRA-338745-GO-RFQ / Acquisition pour les besoins Component 1: Expand Mang Request for Quota Single Stage - One E Pending Impl des matériels et équipement IDA / 59190 o Processing and Investment Post Limited 145,000.00 0.00 2023-02-06 2023-04-03 2023-04-07 tions nvelope ementation s pour les pépiniéristes et pr Opportunities oducteurs ( Kayes, Bamako, Sikasso et Koulikoro) ML-CNRA-338739-GO-RFQ / Dotation pour la modernisati Component 2: Improve Acce Request for Quota Single Stage - One E Pending Impl on et l'innovation en équipe IDA / 59190 ss to Mango Production Area Post Limited 230,000.00 0.00 2023-02-11 2023-04-08 2023-05-08 tions nvelope ementation ments des unités industrielle s s de Bamako, Yanfolila et Sik asso. ML-CNRA-338743-GO-RFQ / Component 1: Expand Mang Achat d'outils pour la profess Request for Quota Single Stage - One E Pending Impl IDA / 59190 o Processing and Investment Post Limited 150,000.00 0.00 2023-02-11 2023-04-08 2023-05-08 ionnalisation des acteurs de l tions nvelope ementation Opportunities a filière mangue (pépiniériste et producteurs) ML-CNRA-338738-GO-RFQ / Component 1: Expand Mang Request for Quota Single Stage - One E Pending Impl Achat de matériels et équipe IDA / 59190 o Processing and Investment Post Limited 140,000.00 0.00 2023-02-11 2023-04-08 2023-05-08 tions nvelope ementation ments pour les pépiniéristes Opportunities et producteurs ML-CNRA-365947-GO-RFQ / Acquisition de motos pour re Component 1: Expand Mang Request for Quota Single Stage - One E Pending Impl nforcer les services techniqu IDA / 59190 o Processing and Investment Post Limited 160,000.00 0.00 2023-06-11 2023-06-21 2023-06-24 tions nvelope ementation es des nouvelles Régions de Opportunities s zones d'intervention du Pro gramme. ML-CNRA-365949-GO-RFQ / Acquisition de matériels infor Component 1: Expand Mang Request for Quota Single Stage - One E Pending Impl matiques pour renforcer les s IDA / 59190 o Processing and Investment Post Limited 161,000.00 0.00 2023-06-09 2023-06-20 2023-06-25 tions nvelope ementation ervices techniques des nouv Opportunities elles Régions des Zones d'int ervention du PACAM Page 2 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NC-REF 1 / Impression du m Component 1: Expand Mang Request for Quota Single Stage - One E Pending Impl atériel de promotion de l'API IDA / 59190 o Processing and Investment Post Open - National 8,520.00 0.00 2017-12-25 2018-02-19 2018-08-18 tions nvelope ementation Mali Opportunities NC-REF-2 / Fourniture et édit Component 4: Strengthen Pr Request for Quota Single Stage - One E Pending Impl ion des bulletins d'informatio IDA / 59190 Post Open - National 17,036.00 0.00 2019-02-24 2019-04-14 2019-10-11 oject Implementation tions nvelope ementation ns trimestriels NC-REF-6 / Accroissement d e la visibilité des réalisations Component 4: Strengthen Pr Request for Quota Single Stage - One E Pending Impl du Projet (réaliser un film ins IDA / 59190 Post Limited 11,925.00 0.00 2021-01-20 2021-03-17 2021-04-16 oject Implementation tions nvelope ementation titutionnelle sous forme de p ubli-reportage et assurer la d iffusion sur les télévisions) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS-REF-1 / Recrutement d'u Component 1: Expand Mang Quality And Cost- Pending Impleme n Assistant Technique pour le IDA / 59190 o Processing and Investment Post Open - National 150,000.00 0.00 2017-07-10 2017-07-20 2017-08-13 2017-09-12 2017-09-19 2017-10-03 2017-10-20 2018-01-18 Based Selection ntation s pépiniéristes de mangues Opportunities CS-REF-5 / Assistance aux e xportateurs/transformateurs, Component 3: Foster Animal Quality And Cost- Pending Impleme coopératives de type OHADA IDA / 59190 Post Open - National 200,000.00 0.00 2017-08-30 2017-09-13 2017-09-27 2017-10-04 2017-10-11 2017-10-25 2017-11-11 2018-01-10 Feed Production Based Selection ntation et l'assistance juridique pour la production contractuelle CS-REF-6 / Récrutement d'u n cabinet pour l'appui aux ex Component 3: Foster Animal Quality And Cost- Pending Impleme portateurs et aux transforma IDA / 59190 Post Open - National 200,000.00 0.00 2017-08-28 2017-09-11 2017-09-25 2017-10-05 2017-10-12 2017-10-26 2017-11-12 2018-01-11 Feed Production Based Selection ntation teurs en matière de sécurité alimentaire, de certification e t de conformité (UE) CS-REF-7 / Etudes comparati ves de la facilitation du com Component 3: Foster Animal Quality And Cost- Pending Impleme IDA / 59190 Post Open - National 150,000.00 0.00 2017-07-20 2017-08-03 2017-08-20 2017-08-30 2017-09-09 2017-09-23 2017-10-15 2018-01-13 merce et des voies d'exporta Feed Production Based Selection ntation tion et des recommandations CS-REF-12 / Cabinet en char Component 1: Expand Mang ge du recrutement des cadre Consultant Qualifi Under Implement IDA / 59190 o Processing and Investment Post Open - National 35,000.00 0.00 2017-07-05 2016-12-13 2017-07-19 2017-08-12 2017-01-20 2017-08-22 2017-09-16 2018-09-16 s de l’Agence pour la Promoti cation Selection ation Opportunities on des Investissements au M ali (API). CS-REF-22 / Audit externe d Component 2: Improve Acce Quality And Cost- Under Implement IDA / 59190 Post Open - National 150,000.00 0.00 2018-03-05 2019-02-03 2018-03-19 2019-04-16 2018-04-02 2018-04-09 2018-04-16 2018-04-30 2018-05-22 2018-09-19 e la qualité des routes ss to Mango Production Area Based Selection ation s CS-REF-24 / Etudes techniqu es pour la construction de l'in Component 3: Foster Animal Consultant Qualifi Pending Impleme IDA / 59190 Post Open - National 90,000.00 0.00 2017-09-12 2017-09-26 2017-10-10 2017-10-17 2017-11-03 2018-01-02 stallation d'unités de conditio Feed Production cation Selection ntation nnement et d'exportation CS-REF-42 / Recrutement d’ Component 1: Expand Mang Consultant Qualifi Pending Impleme un bureau pour la traduction IDA / 59190 o Processing and Investment Post Open - National 12,000.00 0.00 2017-06-23 2017-07-03 2017-07-27 2017-08-06 2017-08-23 2017-09-22 cation Selection ntation des documents de l'API Angla Opportunities is-Français CS-REF-46 / Contrôle et surv Component 2: Improve Acce Quality And Cost- eillance des travaux de 300 k IDA / 59190 ss to Mango Production Area Post Open - National 250,000.00 331,772.47 Completed 2017-06-18 2017-06-20 2017-06-25 2017-07-19 2017-06-23 2017-07-29 2017-07-05 2017-08-08 2017-07-18 2017-08-22 2017-10-26 2017-09-13 2018-03-20 2018-03-12 2019-07-31 Based Selection m de piste PACAM s CS-REF-47 / Recrutement d' un bureau en charge de l'inv entaire, le suivi dans la distri Component 3: Foster Animal Consultant Qualifi Pending Impleme IDA / 59190 Post Open - National 40,000.00 0.00 2017-07-07 2017-07-21 2017-08-04 2017-08-11 2017-08-28 2017-10-27 bution, le contrôle dans l'utili Feed Production cation Selection ntation sation et l'évaluation des pro duits achetés et des method es d'application CS-REF-23 / Etudes techniqu es, DAO de construction et ré Component 2: Improve Acce habilitation de six centres de Consultant Qualifi Pending Impleme IDA / 59190 ss to Mango Production Area Post Open - National 35,000.00 0.00 2017-07-03 2017-07-17 2017-07-31 2017-08-07 2017-08-24 2017-10-23 collecte à Sikassso (3 réhabili cation Selection ntation s tations) et Yanfolila (3 constr uctions) et supervision des tr avaux CS-REF-25 / Formation (form ation des formateurs) pour c Component 3: Foster Animal Quality And Cost- Open - Internationa Pending Impleme IDA / 59190 Post 540,000.00 0.00 2018-01-23 2018-02-13 2018-03-13 2018-03-23 2018-04-02 2018-05-07 2018-05-31 2018-06-30 onsultants en matière d'allia Feed Production Based Selection l ntation nces productives - BDS CS-REF-26 / Formation (form ation des formateurs) pour c Component 3: Foster Animal Quality And Cost- Pending Impleme IDA / 59190 Post Open - National 540,000.00 0.00 2018-01-15 2018-02-05 2018-03-05 2018-03-15 2018-03-25 2018-04-29 2018-06-03 2018-06-18 onsultants en matière d'allia Feed Production Based Selection ntation nces productives - Vulgarisati on CS-REF-27 / Assistance Tech Component 1: Expand Mang Quality And Cost- Open - Internationa Pending Impleme nique pour les activités de pr IDA / 59190 o Processing and Investment Prior 1,100,000.00 0.00 2018-01-30 2018-02-20 2018-03-16 2018-03-26 2018-04-05 2018-05-10 2018-06-03 2019-06-03 Based Selection l ntation é-investissement Opportunities CS-REF-28 / Etudes techniqu es sur le matériel et l'infrastr Component 3: Foster Animal Quality And Cost- Pending Impleme IDA / 59190 Post Open - National 320,000.00 0.00 2017-12-20 2018-01-10 2018-02-07 2018-02-22 2018-03-04 2018-04-08 2018-05-02 2018-06-01 ucture de tous les sous-proje Feed Production Based Selection ntation ts et supervision des travaux CS-REF-40 / Récrutement d' Component 4: Strengthen Pr Quality And Cost- Under Implement un Auditeur externe du PACA IDA / 59190 Post Open - National 40,000.00 0.00 2017-09-12 2017-09-13 2017-09-26 2017-10-10 2017-10-15 2017-10-17 2017-10-24 2017-10-30 2017-11-07 2017-11-10 2017-11-29 2018-11-29 oject Implementation Based Selection ation M pour les exercices 2017, 2 018 et 2019 CS-REF-43 / Recrutement d’ Component 4: Strengthen Pr Consultant Qualifi Under Implement un bureau pour l'élaboration IDA / 59190 Post Open - National 20,000.00 0.00 2017-12-21 2018-02-23 2018-01-11 2018-02-26 2018-02-24 2018-03-26 2018-04-30 2018-06-29 oject Implementation cation Selection ation du manuel de procédure du P ACAM Page 3 CS-REF-66 / Etude et contrôl Component 3: Foster Animal Consultant Qualifi e de 50 étables/magasin/fora IDA / 59190 Post Open - National 154,000.00 189,641.90 Completed 2017-12-20 2018-03-15 2018-01-03 2020-12-16 2018-01-17 2018-07-30 2018-01-24 2018-04-16 2018-02-10 2018-07-31 2018-03-27 2020-12-18 Feed Production cation Selection ges/système solaire du projet LAHAM CS-REF-72 / Recrutement bu Component 3: Foster Animal Consultant Qualifi Pending Impleme reau pour étude du flux de tr IDA / 59190 Post Open - National 43,000.00 0.00 2018-01-24 2018-02-14 2018-03-30 2018-04-29 2018-06-03 2018-11-30 Feed Production cation Selection ntation ansport des mangues pour P ACAM CS-REF-81 / Etude et contrôl Component 1: Expand Mang Quality And Cost- Pending Impleme e des travaux de réhabilitatio IDA / 59190 o Processing and Investment Post Open - National 85,000.00 0.00 2018-01-10 2018-01-24 2018-02-10 2018-02-17 2018-02-27 2018-03-11 2018-03-28 2018-05-12 Based Selection ntation n de Tubaniso Opportunities CS-REF-73 / Etude du systè Component 1: Expand Mang Consultant Qualifi Pending Impleme me orchestration filières/mod IDA / 59190 o Processing and Investment Post Open - National 85,000.00 0.00 2018-01-18 2018-02-08 2018-03-24 2018-04-23 2018-05-28 2018-11-24 cation Selection ntation ernisation pisteurs pour PAC Opportunities AM CS-REF-64-1 / Recrutement Component 1: Expand Mang d'une firme pour la réalisatio Quality And Cost- Open - Internationa Under Implement IDA / 59190 o Processing and Investment Post 170,000.00 0.00 2018-10-29 2018-11-11 2018-11-19 2019-03-19 2019-01-02 2019-01-30 2019-03-01 2019-04-05 2019-05-10 2019-07-09 n du schéma directeur opéra Based Selection l ation Opportunities tionnel de Toubaniso CS-REF-93 / Recrutement d' Component 1: Expand Mang un Cabinet pour l'appui aux c Consultant Qualifi Pending Impleme IDA / 59190 o Processing and Investment Post Open - National 51,107.00 0.00 2019-01-14 2019-02-04 2019-03-11 2019-04-01 2019-04-29 2020-04-23 inq familles de l'IFM en matiè cation Selection ntation Opportunities re de sécurité alimentaire, ce rtification et qualité CS-REF-65 / Recrutement d' Component 1: Expand Mang une firme pour la réalisation Quality And Cost- IDA / 59190 o Processing and Investment Prior Open - National 18,000.00 0.00 Canceled 2017-10-12 2017-10-26 2017-11-05 2017-11-20 2017-11-23 2017-12-08 2017-12-23 2018-01-22 d'un audit environnemental e Based Selection Opportunities t social de tubaniso CS-REF-39-1 / Recrutement Component 3: Foster Animal Quality And Cost- Open - Internationa Under Implement IDA / 59190 Prior 1,850,000.00 0.00 2019-03-12 2019-03-27 2019-04-02 2019-04-29 2019-05-21 2020-01-29 2019-06-18 2020-03-18 2019-07-18 2020-05-04 2019-08-22 2021-01-12 2019-09-26 2022-07-12 d'un Contracteur Institutionn Feed Production Based Selection l ation el CS-REF-106 / Consultant pou r réaliser l'audit environneme Component 3: Foster Animal Consultant Qualifi Pending Impleme ntal, social, sécurité et santé IDA / 59190 Post Open - National 85,180.00 0.00 2020-08-03 2020-08-24 2020-10-07 2020-11-06 2020-12-11 2021-06-09 Feed Production cation Selection ntation de la composante 3 "Amélior ation de l'alimentation anima le" CS-REF-109 / Recrutement d Component 4: Strengthen Pr Quality And Cost- Under Implement u consultant pour la revue IDA / 59190 Post Open - National 42,590.00 0.00 2020-08-06 2020-01-16 2020-08-21 2022-08-09 2020-09-19 2020-10-10 2020-10-25 2020-11-15 2020-11-29 2021-02-27 oject Implementation Based Selection ation mi-parcours du projet. CS-REF-107 / Consultant pou Component 4: Strengthen Pr Quality And Cost- r réaliser l'Audit Externe du P IDA / 59190 Post Open - National 34,072.00 13,978.35 Completed 2020-09-14 2020-09-14 2020-09-29 2020-12-18 2020-10-28 2020-12-15 2020-11-18 2021-03-02 2020-12-02 2021-03-22 2020-12-19 2021-07-16 2021-01-08 2021-07-17 2022-08-31 2022-08-02 oject Implementation Based Selection rojet (Exercices 2020, 2021 e t 2022) ML-CNRA-268187-CS-CQS / Component 4: Strengthen Pr Consultant Qualifi Under Implement Recrutement d'un consultant IDA / 59190 Post Open - National 40,000.00 0.00 2022-03-01 2022-08-04 2022-03-16 2022-04-04 2022-04-09 2022-04-26 2022-05-11 oject Implementation cation Selection ation pour la revue finale du Projet ML-CNRA-306445-CS-CQS / Services de consultant pour l a réalisation de l'étude pour l Component 4: Strengthen Pr Consultant Qualifi IDA / 59190 Post Open - National 108,000.00 0.00 Canceled 2022-08-17 2022-09-07 2022-10-21 2022-10-31 2022-11-19 2023-01-18 a mise en place de Guichet U oject Implementation cation Selection nique virtuel foncier pour les transactions à Bamako, Ségo u et Sikasso ML-CNRA-306124-CS-CQS / Services de consultants pour la réalisation de l'étude d'ide ntification des principales co Component 4: Strengthen Pr Consultant Qualifi IDA / 59190 Post Open - National 67,000.00 0.00 Canceled 2022-08-31 2022-09-15 2022-10-04 2022-10-09 2022-10-19 2022-12-18 ntraintes et défaillances du oject Implementation cation Selection marché pour chacune des ch aines de valeur soutenues et élaborer des plans d'action s ur un ensemble d'interventio ns clés. ML-CNRA-253666-CS-LCS / R ecrutement d'un bureau pour Component 2: Improve Acce la mise en place d'un mécani Least Cost Selecti IDA / 59190 ss to Mango Production Area Post Open - National 140,000.00 0.00 Canceled 2021-09-20 2021-11-01 2021-10-11 2021-11-04 2021-12-02 2021-12-17 2022-01-05 2022-01-29 2022-04-29 sme de suivi des infrastructu on s res et enquête de satisfactio n des bénéficiaires du projet. ML-CNRA-306118-CS-CQS / Services de consultants pour la réalisation de l'étude d'ide Component 4: Strengthen Pr Consultant Qualifi Pending Impleme IDA / 59190 Post Open - National 25,000.00 0.00 2022-09-05 2022-09-20 2022-09-28 2022-10-03 2022-11-07 2023-01-06 ntification des chaines de val oject Implementation cation Selection ntation eur soutenues et les zones g éographiques d'intervention du Projet ML-CNRA-306186-CS-CQS / Services de consultants pour la réalisation de l'audit organ Component 4: Strengthen Pr Consultant Qualifi Pending Impleme isationnel et financier des fili IDA / 59190 Post Open - National 25,000.00 0.00 2022-08-17 2022-09-01 2022-09-25 2022-09-30 2022-10-10 2022-12-09 oject Implementation cation Selection ntation ères ciblées et de renforcem ent des capacités entreprises dans les chaines de valeur so utenues. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS-REF-8 / Appui consultatif aux exportateurs et aux tran Component 3: Foster Animal Individual Consult Pending Impleme sformateurs sur les flux logis IDA / 59190 Post Open 50,000.00 0.00 2017-08-24 2017-09-21 2017-09-28 2017-10-15 2017-12-14 Feed Production ant Selection ntation tiques et la passation des ma rchés (camions, ports, aérop orts) n°1 CS-REF-9 / Appui consultatif aux exportateurs et aux tran Component 1: Expand Mang Individual Consult Pending Impleme sformateurs sur les flux logis IDA / 59190 o Processing and Investment Post Open 50,000.00 0.00 2017-07-24 2017-08-27 2017-09-06 2017-09-23 2017-12-22 ant Selection ntation tiques et la passation des ma Opportunities rchés (camions, ports, aérop orts) n°2 CS-REF-10 / Appui consultati f aux exportateurs et aux tra Component 1: Expand Mang Individual Consult Pending Impleme nsformateurs sur les flux logi IDA / 59190 o Processing and Investment Post Open 50,000.00 0.00 2017-06-22 2017-07-26 2017-08-05 2017-08-22 2017-11-20 ant Selection ntation stiques et la passation des m Opportunities archés (camions, ports, aéro ports) n°3 Page 4 CS-REF-11 / Appui consultati f aux exportateurs et aux tra Component 1: Expand Mang Individual Consult Pending Impleme nsformateurs sur les flux logi IDA / 59190 o Processing and Investment Post Open 50,000.00 0.00 2017-07-12 2017-08-09 2017-08-16 2017-08-26 2017-10-25 ant Selection ntation stiques et la passation des m Opportunities archés (camions, ports, aéro ports) n°4 CS-REF-48 / Récrutement d' Component 1: Expand Mang un expert en communication Individual Consult Under Implement IDA / 59190 o Processing and Investment Post Open 34,072.00 0.00 2017-07-27 2017-07-28 2017-08-24 2017-08-29 2017-08-31 2017-09-17 2018-03-16 pour aider à la préparation d ant Selection ation Opportunities u forum Investir au Mali pour le compte de l'API CS-REF-49 / Récrutement d' Component 1: Expand Mang un expert en évenementiel p Individual Consult Pending Impleme IDA / 59190 o Processing and Investment Post Open 34,072.00 0.00 2017-07-05 2017-08-02 2017-08-09 2017-08-23 2018-02-19 our aider à la préparation du ant Selection ntation Opportunities forum Investir au Mali pour le compte de l'API CS-REF-52 / Récrutement d' un expert chargé des réseau Component 1: Expand Mang Individual Consult Pending Impleme x sociaux pour aider à la pré IDA / 59190 o Processing and Investment Post Open 34,072.00 0.00 2017-06-29 2017-08-17 2017-08-27 2017-09-21 2018-03-20 ant Selection ntation paration du forum Investir au Opportunities Mali pour le compte de l'API CS-REF-53 / Récrutement d' Component 1: Expand Mang un coordinateur technique po Individual Consult Pending Impleme IDA / 59190 o Processing and Investment Post Open 34,072.00 0.00 2017-06-30 2017-07-28 2017-08-04 2017-08-21 2018-02-17 ur aider à la préparation du f ant Selection ntation Opportunities orum Investir au Mali pour le compte de l'API CS-REF-54 / Récrutement d' un expert en comptabilité fin Component 1: Expand Mang Individual Consult Pending Impleme ance pour aider à la préparat IDA / 59190 o Processing and Investment Post Open 34,072.00 0.00 2017-07-05 2017-08-08 2017-08-15 2017-08-29 2017-09-05 ant Selection ntation ion du forum Investir au Mali Opportunities pour le compte de l'API CS-REF-55 / Récrutement d' un expert pour former les for Component 3: Foster Animal Individual Consult Pending Impleme IDA / 59190 Post Open 102,215.00 0.00 2017-07-10 2017-08-07 2017-08-14 2017-08-31 2017-09-30 mateurs pour l'application de Feed Production ant Selection ntation s produits de lutte contre la mouche de fruit CS-REF-56 / Récrutement d' Component 4: Strengthen Pr Individual Consult Pending Impleme un consultant pour l'appui au IDA / 59190 Post Open 51,107.00 0.00 2017-06-29 2017-08-02 2017-08-09 2017-08-29 2018-08-29 oject Implementation ant Selection ntation démarage du projet CS-REF-57 / Récrutement d' Component 4: Strengthen Pr Individual Consult Pending Impleme un consultant en appui à la p IDA / 59190 Post Open 20,442.00 0.00 2017-07-06 2017-08-24 2017-09-03 2017-09-28 2017-11-27 oject Implementation ant Selection ntation assation des marchés CS-REF-58 / Récrutement d' Component 1: Expand Mang Individual Consult Pending Impleme un spécialiste en TIC, commu IDA / 59190 o Processing and Investment Post Open 102,215.00 0.00 2017-07-05 2017-08-13 2017-08-23 2017-09-17 2018-09-17 ant Selection ntation nication et evenementiel Opportunities CS-REF-59 / Récrutement d' Component 3: Foster Animal Individual Consult Pending Impleme un économiste international IDA / 59190 Post Open 42,590.00 0.00 2017-06-22 2017-07-20 2017-07-27 2017-08-10 2017-09-04 Feed Production ant Selection ntation pour la chaine de valeur mon diale CS-REF-60 / Récrutement d' Component 3: Foster Animal Individual Consult Pending Impleme IDA / 59190 Post Open 8,518.00 0.00 2017-07-02 2017-08-05 2017-08-20 2017-09-13 2017-10-28 un économiste national de te Feed Production ant Selection ntation rrain CS-REF-61 / Récrutement d' Component 3: Foster Animal Individual Consult Pending Impleme un assistant de recherche de IDA / 59190 Post Open 8,518.00 0.00 2017-07-03 2017-08-06 2017-08-16 2017-09-10 2017-10-25 Feed Production ant Selection ntation veloppement chaines de vale ur CS-REF-62 / Recrutement d' Component 1: Expand Mang une firme pour la sélection d Under Implement IDA / 59190 o Processing and Investment Post Direct Selection Direct 200,000.00 0.00 2017-10-06 2017-09-04 2017-10-10 2017-10-16 2017-11-01 2018-01-30 es investisseurs dans la zone ation Opportunities office du Niger (PDAIC-ZON) CS-REF-63 / Recrutement d' Component 1: Expand Mang Under Implement une firme pour la réalisation IDA / 59190 o Processing and Investment Post Direct Selection Direct 170,400.00 0.00 2017-10-10 2017-10-13 2017-10-18 2017-10-23 2017-11-05 2018-02-03 ation du plan d'affaires de tubanis Opportunities o CS-REF-64 / Recrutement d' Component 1: Expand Mang Under Implement une firme pour la réalisation IDA / 59190 o Processing and Investment Post Direct Selection Direct 170,000.00 0.00 2017-10-10 2018-02-06 2017-10-18 2017-11-07 2018-02-05 ation du schéma directeur opératio Opportunities nnel de tubaniso CS-REF-29 / Récrutement d' Component 4: Strengthen Pr Individual Consult Pending Impleme IDA / 59190 Post Open 150,000.00 0.00 2017-06-22 2017-07-20 2017-07-27 2017-08-10 2017-08-13 un assistant en passation des oject Implementation ant Selection ntation marchés CS-REF-31 / Récrutement d' Component 4: Strengthen Pr Individual Consult IDA / 59190 Post Open 125,000.00 120,377.64 Signed 2017-06-28 2017-06-27 2017-08-12 2017-08-14 2017-09-02 2017-07-04 2017-09-16 2017-10-10 2018-09-16 un comptable adjoint oject Implementation ant Selection CS-REF-32 / Récrutement d' Component 4: Strengthen Pr Individual Consult IDA / 59190 Post Open 230,000.00 193,672.50 Signed 2017-06-23 2017-06-26 2017-07-21 2017-07-25 2017-07-28 2017-08-02 2017-08-14 2017-03-14 2018-08-14 un directeur technique oject Implementation ant Selection CS-REF-34 / Récrutement d' Component 4: Strengthen Pr Individual Consult IDA / 59190 Post Open 40,000.00 13,646.05 Signed 2017-07-03 2017-07-04 2017-07-31 2017-08-07 2017-08-06 2017-08-24 2017-08-01 2018-08-24 un assistant du projet oject Implementation ant Selection CS-REF-35 / Récrutement d' Component 4: Strengthen Pr Individual Consult IDA / 59190 Post Open 165,000.00 341,775.00 Signed 2017-06-18 2017-06-19 2017-07-16 2017-07-21 2017-07-23 2017-07-31 2017-08-06 2017-05-01 2018-08-06 un spécialiste en infrastructu oject Implementation ant Selection re CS-REF-36 / Récrutement d' Component 4: Strengthen Pr Individual Consult IDA / 59190 Post Open 165,000.00 157,126.20 Signed 2017-06-23 2017-06-26 2017-07-21 2017-07-21 2017-07-28 2017-07-30 2017-08-19 2017-05-01 2018-08-19 un spécialiste en financemen oject Implementation ant Selection t CS-REF-37 / Récrutement d' Component 4: Strengthen Pr Individual Consult IDA / 59190 Post Open 165,000.00 159,495.00 Signed 2017-06-29 2017-06-30 2017-08-17 2017-08-21 2017-08-27 2017-09-01 2017-09-18 2017-05-01 2018-09-18 un spécialiste en filières oject Implementation ant Selection CS-REF-38 / Mise à jour du m Component 4: Strengthen Pr Individual Consult Pending Impleme IDA / 59190 Post Open 20,000.00 0.00 2017-08-10 2017-09-07 2017-09-14 2017-10-01 2017-10-31 anuel opérationnel oject Implementation ant Selection ntation CS-REF-45 / Recrtement d'u Component 4: Strengthen Pr Individual Consult Under Implement n spécialiste en études envir IDA / 59190 Post Open 170,000.00 0.00 2017-06-28 2017-06-29 2017-07-29 2017-08-08 2017-08-25 2018-08-25 oject Implementation ant Selection ation onnementales pour le projet CS-REF-68 / Recrutement d' un consultant individuel/poin Component 3: Foster Animal Individual Consult Pending Impleme IDA / 59190 Post Limited 24,000.00 0.00 2018-01-22 2018-01-27 2018-02-06 2018-02-23 2018-08-22 t focal embouche commercial Feed Production ant Selection ntation e du projet LAHAM CS- REF- 71 / Recrutement d Component 4: Strengthen Pr Individual Consult IDA / 59190 Post Limited 30,000.00 38,409.66 Signed 2017-12-22 2017-12-25 2017-12-25 2017-12-29 2018-01-04 2018-01-10 2018-01-21 2017-11-03 2019-01-21 'un informaticien pour l'UCP oject Implementation ant Selection PACAM Page 5 CS-REF-16 / Recrutement du Component 1: Expand Mang Individual Consult chargé de promotion de l'élé IDA / 59190 o Processing and Investment Post Open 85,000.00 0.00 Canceled 2017-06-30 2017-07-28 2017-08-04 2017-08-21 2018-08-21 ant Selection vage Opportunities CS-REF-51 / Récrutement d' Component 1: Expand Mang un expert en sécurité pour ai Individual Consult IDA / 59190 o Processing and Investment Post Open 34,072.00 0.00 Canceled 2017-06-26 2017-07-24 2017-07-31 2017-08-17 2018-02-13 der à la préparation du forum ant Selection Opportunities Investir au Mali pour le comp te de l'API CS-REF-50 / Récrutement d' un expert en logistique et pr Component 1: Expand Mang Individual Consult otocole pour aider à la prépa IDA / 59190 o Processing and Investment Post Open 34,072.00 0.00 Canceled 2017-07-03 2017-07-31 2017-08-07 2017-08-24 2018-02-20 ant Selection ration du forum Investir au M Opportunities ali pour le compte de l'API CS-REF-21 / Etude APD, élab Component 2: Improve Acce oration des dossiers d'appel IDA / 59190 ss to Mango Production Area Post Direct Selection Direct 120,000.00 109,110.76 Completed 2017-02-03 2017-02-03 2017-02-23 2017-02-22 2017-04-02 2017-01-26 2017-06-01 2017-04-03 d'offre des travaux pour 300 s km de routes rurales CS-REF-41 / Récrutement d' Component 4: Strengthen Pr Individual Consult Under Implement IDA / 59190 Post Open 41,000.00 0.00 2017-07-20 2017-07-21 2017-08-17 2017-08-24 2017-09-07 2017-09-14 un Assistant en suivi et évalu oject Implementation ant Selection ation ation CS-REF-67 / Conception du p lan, des supports de commun Component 1: Expand Mang Individual Consult ication et une application mo IDA / 59190 o Processing and Investment Post Limited 54,500.00 60,772.31 Completed 2017-12-21 2017-12-22 2017-12-26 2017-12-28 2018-01-05 2018-01-07 2018-01-19 2017-11-22 2018-03-05 2018-01-31 ant Selection bile de Tubaniso-Agribusines Opportunities s et innovation center (TAIC) CS-REF-86 / Recrutement d' Component 4: Strengthen Pr Individual Consult Pending Impleme un consultant pour préparati IDA / 59190 Post Open 35,000.00 0.00 2018-03-19 2018-04-12 2018-04-15 2018-04-23 2018-10-20 oject Implementation ant Selection ntation on composante 1 du PDAZAM CS-REF-87 / Recrutement d' Component 4: Strengthen Pr Individual Consult Pending Impleme un consultant en appui à la p IDA / 59190 Post Open 30,000.00 0.00 2018-03-19 2018-04-12 2018-04-15 2018-04-23 2018-10-20 oject Implementation ant Selection ntation réparation de la composante 3 du PDAZAM CS-REF 65-1 / Audit environn Component 1: Expand Mang Individual Consult Pending Impleme emental et social de Toubani IDA / 59190 o Processing and Investment Post Open 18,000.00 0.00 2018-11-13 2018-11-28 2018-12-03 2018-12-13 2019-01-12 ant Selection ntation so Opportunities CS-REF-100 / Consultant sui Component 3: Foster Animal Individual Consult Pending Impleme vi technique (Point focal) Plat IDA / 59190 Post Open 18,038.00 0.00 2019-03-12 2019-03-22 2019-03-26 2019-03-30 2019-09-26 Feed Production ant Selection ntation eforme d'embouche du pilote LAHAM CS-REF-99 / Consultant Busi Component 3: Foster Animal Individual Consult Under Implement IDA / 59190 Post Open 18,038.00 0.00 2019-03-12 2019-02-04 2019-03-22 2019-02-11 2019-03-26 2019-03-30 2019-09-26 ness Plans Projet Pilote LAHA Feed Production ant Selection ation M CS-REF-102 / Consultant sui vi et supervision des travaux (300 km de piste, 6 centres Component 4: Strengthen Pr Individual Consult Under Implement IDA / 59190 Post Limited 25,551.00 0.00 2019-05-11 2019-05-13 2019-05-16 2019-05-20 2019-11-16 de collecte et d'entreposage oject Implementation ant Selection ation et infrastructures d'équipem ents pour alliances productiv es) CS-REF-99-2 / Consultant Bu siness Plans Projet Pilote LAH Component 3: Foster Animal Individual Consult Pending Impleme AM / Suivi et accompagneme IDA / 59190 Post Open 9,020.00 0.00 2019-12-20 2019-12-26 2019-12-28 2020-01-01 2020-05-15 Feed Production ant Selection ntation nt des promoteurs pour l'obt ention de crédit auprès de la BNDA CS-REF-104 / Renforcer les c apacités statistique et straté gique de l’IFM sur le dévelop Component 1: Expand Mang Individual Consult Pending Impleme pement de la filière mangue, IDA / 59190 o Processing and Investment Post Limited 8,518.00 0.00 2020-04-15 2020-04-20 2020-05-04 2020-05-25 2020-06-24 ant Selection ntation et aider la coordination entre Opportunities agriculteurs notamment qua nt à la formalisation en coop érative de type OHADA CS-REF-105 / Former les act eurs sur le compostage, la pr Component 3: Foster Animal Individual Consult Pending Impleme otection de l'environnement IDA / 59190 Post Limited 4,260.00 0.00 2020-03-30 2020-04-04 2020-04-11 2020-04-22 2020-04-29 Feed Production ant Selection ntation et informer/sensibiliser sur l es mesures de sauvegardes s ociales. CS-REF-108 / Recrutement d Component 4: Strengthen Pr Individual Consult Under Implement IDA / 59190 Post Open 34,072.00 0.00 2020-04-06 2020-05-04 2020-05-25 2020-06-08 2020-07-02 2020-12-29 'un consultant chargé de gen oject Implementation ant Selection ation re CS-REF-96 / Recrutement d' Component 1: Expand Mang un Consultant chargé de fair Individual Consult Pending Impleme IDA / 59190 o Processing and Investment Post Open 42,589.00 0.00 2019-03-20 2019-04-23 2019-05-07 2019-06-04 2019-09-02 e des études économiques d ant Selection ntation Opportunities ans le cadre d'un plan d'appu i institutionnel de l'API. CS-REF-91 / Recrutement d' un consultant chargé de For mer les producteurs en techn Component 1: Expand Mang Individual Consult Pending Impleme iques d'évaluation de la prod IDA / 59190 o Processing and Investment Post Open 51,107.00 0.00 2019-04-10 2019-05-13 2019-05-20 2019-06-03 2019-09-01 ant Selection ntation uction de la mangue dans les Opportunities vergers géo référencés et pr oduire des cartes dynamique s à travers la télédétection CS-REF-88 / Recrutement d' un consultant chargé de la C Component 1: Expand Mang apitalisation des résultats en Individual Consult Pending Impleme IDA / 59190 o Processing and Investment Post Open 17,036.00 0.00 2019-03-11 2019-04-14 2019-04-28 2019-05-15 2020-05-09 grangés par le PCDA pour av ant Selection ntation Opportunities ancer dans la démarche de c ertification des jeunes plants de manguier CS-REF-92 / Recrutement d' un consultant chargé d'appu Component 1: Expand Mang yer l'interprofession mangue Individual Consult Pending Impleme IDA / 59190 o Processing and Investment Post Open 8,517.00 0.00 2019-04-28 2019-05-26 2019-06-02 2019-06-16 2019-10-14 pour la collecte et la diffusion ant Selection ntation Opportunities des informations commercial es par SMS à travers la platef orme "Orange Sènèkèla" CS-REF-98 / Recrutement de Component 4: Strengthen Pr Individual Consult Pending Impleme IDA / 59190 Post Direct 128,194.00 0.00 2019-01-24 2019-01-25 2019-01-26 2019-01-27 2022-08-29 l'Auditeur interne du PACAM oject Implementation ant Selection ntation Page 6 CS-REF-97 / Recrutement d' un Consultant Expert en Infra structure pour le suivi et la s Component 2: Improve Acce Individual Consult Pending Impleme upervision des travaux ( 300 IDA / 59190 ss to Mango Production Area Post Open 25,554.00 0.00 2019-01-07 2019-01-23 2019-01-28 2019-02-01 2019-07-31 ant Selection ntation km de piste, 3 centres de coll s ecte et infrastructures et équ ipements pour alliances prod uctives). CS-REF-89 / Recrutement d' un consultant chargé de Renf Component 1: Expand Mang Individual Consult Pending Impleme orcer la capacité des comme IDA / 59190 o Processing and Investment Post Open 8,518.00 0.00 2019-03-27 2019-04-29 2019-05-06 2019-05-20 2019-08-18 ant Selection ntation rçants et transformatrices de Opportunities mangues en gestion et conse rvation de la mangue CS-REF-95 / Recrutement d' un consultant chargé de l'Etu Component 1: Expand Mang de portant sur l'analyse appr Individual Consult Pending Impleme IDA / 59190 o Processing and Investment Post Open 34,072.00 0.00 2019-04-07 2019-05-10 2019-05-17 2019-06-03 2019-10-01 ofondie des avantages et ent ant Selection ntation Opportunities raves aux expéditions par voi es routière, maritime et aérie nne vers l'Europe et le Maghr eb. CS-REF-90 / Recrutement d' Component 1: Expand Mang un consultant chargé de For Individual Consult Pending Impleme IDA / 59190 o Processing and Investment Post Open 5,111.00 0.00 2019-03-11 2019-04-13 2019-04-20 2019-05-04 2019-07-03 mer les pisteurs sur les bonn ant Selection ntation Opportunities es pratiques de récolte et de transport de la mangue.. CS-REF-85 / Recrutement d' Component 4: Strengthen Pr Individual Consult Pending Impleme un assistant technique pour IDA / 59190 Post Open 35,000.00 0.00 2018-03-19 2018-04-08 2018-04-13 2018-04-18 2018-10-15 oject Implementation ant Selection ntation préparation PDAZAM CS-REF-103 / Consultant pou r établir un Plan de compétiti Component 1: Expand Mang Individual Consult vité pour la filière mangue en IDA / 59190 o Processing and Investment Post Limited 11,925.00 12,502.86 Signed 2021-01-28 2021-06-14 2021-02-02 2022-01-06 2021-02-09 2022-01-06 2021-02-21 2022-01-07 2021-04-07 ant Selection tenant compte des facteurs d Opportunities e développement et des goul ots d’étranglement CS-REF-112 / Recrutement d Component 2: Improve Acce 'un Consultant pour la format Individual Consult Pending Impleme IDA / 59190 ss to Mango Production Area Post Limited 8,518.00 0.00 2021-03-02 2021-03-07 2021-03-28 2021-05-02 2021-06-01 ion des brigadiers en matière ant Selection ntation s d'entretien des pistes CS-REF-113 / Service de con Component 2: Improve Acce sultant pour le Contrôle et s Pending Impleme IDA / 59190 ss to Mango Production Area Post Direct Selection Direct 57,324.00 0.00 2021-03-03 2021-03-13 2021-05-17 2021-08-15 uivi supplémentaires des tra ntation s vaux des centres de collecte CS-REF-114 / Services de Co nsultant pour l'appui techniq Component 3: Foster Animal Individual Consult Pending Impleme ue aux emboucheurs et aux IDA / 59190 Post Limited 18,039.00 0.00 2021-01-14 2021-01-17 2021-01-22 2021-02-01 2021-07-31 Feed Production ant Selection ntation mandataires sur les techniqu es d'embouche modernes CS-REF-115 / Service de con sultant (Prise en charge du te Component 3: Foster Animal Pending Impleme mps supplémentaires de suiv IDA / 59190 Post Direct Selection Direct 56,284.00 0.00 2021-01-15 2021-01-25 2021-03-08 2021-06-06 Feed Production ntation i de la réalisation des travaux des étables et magasins par l e Bureau de contrôle). CS-REF-111 / Service de Con Component 2: Improve Acce sultant pour le Contrôle et le Pending Impleme IDA / 59190 ss to Mango Production Area Post Direct Selection Direct 92,315.00 0.00 2021-04-01 2021-04-11 2021-06-15 2021-06-16 suivi des travaux d'achèvem ntation s ent des lots 03 et 05 des pist es rurales. CS-REF-110 / Montage, valid ation et financement de 10 s Component 3: Foster Animal Individual Consult Pending Impleme IDA / 59190 Prior Open 340,716.00 0.00 2020-08-07 2020-09-25 2020-10-16 2020-11-20 2021-05-19 ous projets d'alliances produ Feed Production ant Selection ntation ctives /alimentation bétail. ML-CNRA-234480-CS-INDV / SERVICE DE CONSULTANT PO UR L’ÉVALUATION A MI PARC Component 4: Strengthen Pr Individual Consult IDA / 59190 Post Limited 14,724.00 11,767.58 Completed 2021-05-14 2021-05-03 2021-05-19 2021-05-05 2021-05-24 2021-05-10 2021-05-30 2021-05-11 2021-06-09 2021-06-02 OURS DU PROJET D’APPUI A L oject Implementation ant Selection A COMPETITIVITE AGRO-INDU STRIELLE AU MALI (PACAM) ML-CNRA-243396-CS-INDV / Component 4: Strengthen Pr Individual Consult Recrutement d'un auditeur in IDA / 59190 Post Direct 37,959,390.00 32,741.10 Signed 2021-07-30 2021-08-09 2021-08-01 2021-07-29 2021-08-02 2021-07-29 2021-08-04 2021-07-31 2022-07-30 oject Implementation ant Selection terne du PACAM ML-CNRA-242859-CS-CDS / Component 4: Strengthen Pr Individual Consult Recrutement d'un spécialiste IDA / 59190 Post Direct 48,485,940.00 47,334.28 Signed 2021-07-30 2021-08-09 2021-08-01 2021-07-28 2021-08-02 2021-07-28 2021-08-04 2021-07-31 2022-07-30 oject Implementation ant Selection en passation de marchés du PACAM ML-CNRA-269284-CS-INDV / Component 2: Improve Acce Individual Consult Pending Impleme Recrutement d'un consultant IDA / 59190 ss to Mango Production Area Post Limited 10,000.00 0.00 2022-01-24 2022-01-29 2022-02-19 2022-03-10 2022-03-25 ant Selection ntation pour former les brigadiers s ML-CNRA-269730-CS-INDV / Component 2: Improve Acce Recrutement d'un consultant Individual Consult Under Implement IDA / 59190 ss to Mango Production Area Post Limited 10,000.00 0.00 2022-01-10 2022-08-09 2022-01-15 2022-09-19 2022-01-20 2022-02-24 2022-03-26 individuel pour faire l'audit te ant Selection ation s chnique des pistes rurales du Projet ML-CNRA-306460-CS-INDV / Service de consultant pour la Component 4: Strengthen Pr Individual Consult Pending Impleme IDA / 59190 Post Limited 50,000.00 0.00 2022-08-31 2022-09-05 2022-09-26 2022-10-31 2022-12-30 réalisation d'étude d'identific oject Implementation ant Selection ntation ation des risques pays ML-CNRA-306477-CS-INDV / Services de consultants pour Component 4: Strengthen Pr Individual Consult Pending Impleme IDA / 59190 Post Limited 100,000.00 0.00 2022-08-15 2022-08-20 2022-09-10 2022-10-15 2023-01-13 l'élaboration de la baseline et oject Implementation ant Selection ntation définition des indicateurs ML-CNRA-306487-CS-INDV / Recrutement d'un consultant Component 4: Strengthen Pr Individual Consult Under Implement IDA / 59190 Post Limited 34,000.00 0.00 2022-09-01 2022-10-10 2022-09-06 2022-09-27 2022-11-01 2023-01-15 pour la réalisation de l'enquê oject Implementation ant Selection ation te d'opinion des bénéficiaires ML-CNRA-306492-CS-INDV / Recrutement d'un consultant Component 4: Strengthen Pr Individual Consult Under Implement IDA / 59190 Post Limited 67,000.00 0.00 2022-08-22 2022-12-05 2022-08-27 2022-09-17 2022-10-06 2023-01-04 pour la réalisation de l'audit oject Implementation ant Selection ation environnementale du Projet Page 7 ML-CNRA-306070-CS-CDS / E Component 1: Expand Mang tudes et contrôles des travau IDA / 59190 o Processing and Investment Post Direct Selection Direct - National 50,000.00 0.00 Under Review 2022-09-26 2022-10-06 2022-10-03 2022-10-14 2022-11-28 x de réalisation des forages Opportunities ML-CNRA-306336-CS-QBS / S ervices de consultant pour la Component 4: Strengthen Pr Individual Consult Under Implement réalisation de l'étude pour id IDA / 59190 Post Limited 25,000.00 0.00 2023-01-05 2023-01-09 2023-01-10 2023-01-31 2023-03-07 2023-05-06 oject Implementation ant Selection ation entifier le mécanisme de facil itation du financement du co mmerce. ML-CNRA-252506-CS-INDV / Recrutement d'un consultant Component 1: Expand Mang Individual Consult pour établir un plan de comp IDA / 59190 o Processing and Investment Post Limited 15,000.00 0.00 Canceled 2021-09-15 2021-09-20 2021-09-25 2021-10-10 2021-12-09 ant Selection étitive pour la filière mangue Opportunities et la filière aliment bétail ML-CNRA-331479-CS-INDV / Recrutement d'un consultant Component 4: Strengthen Pr Individual Consult Under Implement pour former les cadres de l'U IDA / 59190 Post Limited 17,000.00 0.00 2023-04-03 2023-03-06 2023-04-08 2023-04-13 2023-05-09 2023-05-19 oject Implementation ant Selection ation CP sur les techniques d'élabo ration du rapport d'achèvem ent du Projet ML-CNRA-331483-CS-INDV / Consultant pour mettre à jou Component 3: Foster Animal Individual Consult Pending Impleme IDA / 59190 Post Limited 17,000.00 0.00 2023-02-06 2023-02-11 2023-02-16 2023-03-09 2023-04-08 r du cadre de gestion environ Feed Production ant Selection ntation nementale et sociale (CGES) ML-CNRA-331485-CS-INDV / Component 2: Improve Acce Consultant pour la mise jour Individual Consult Pending Impleme IDA / 59190 ss to Mango Production Area Post Limited 17,000.00 0.00 2023-02-06 2023-02-11 2023-02-16 2023-02-26 2023-03-28 du cadre de politique de réin ant Selection ntation s stallation de population (CPR P) ML-CNRA-331486-CS-INDV / Component 1: Expand Mang Réalisation par un consultant Individual Consult Under Implement IDA / 59190 o Processing and Investment Post Limited 20,000.00 0.00 2023-01-16 2023-01-09 2023-01-21 2023-01-26 2023-02-05 2023-04-06 des études de faisabilité pour ant Selection ation Opportunities l'identification des marchés p orteurs ML-CNRA-331488-CS-INDV / Réalisation de l'étude sur le f Component 3: Foster Animal Individual Consult IDA / 59190 Post Limited 24,000.00 0.00 Under Review 2023-01-23 2023-01-09 2023-01-28 2023-02-18 2023-03-09 2023-05-08 inancement des filières pour Feed Production ant Selection un fonctionnement pérenne ML-CNRA-331496-CS-INDV / Réalisation par un consultant Component 3: Foster Animal Individual Consult Pending Impleme IDA / 59190 Post Limited 17,000.00 0.00 2023-02-15 2023-02-20 2023-03-13 2023-04-17 2023-10-14 de l'étude pour la numérisati Feed Production ant Selection ntation on des chaines de valeur agri coles en atelier ML-CNRA-331508-CS-INDV / Réalisation par un consultant Component 3: Foster Animal Individual Consult IDA / 59190 Post Limited 17,000.00 0.00 Under Review 2023-01-10 2023-01-09 2023-01-15 2023-02-05 2023-02-24 2023-02-27 de l'étude relative à l'émerge Feed Production ant Selection nce de la finance verte ML-CNRA-331513-CS-INDV / Component 3: Foster Animal Individual Consult Pending Impleme Réalisation par un consultant IDA / 59190 Post Limited 17,000.00 0.00 2023-02-01 2023-02-06 2023-02-27 2023-04-03 2023-05-03 Feed Production ant Selection ntation de l'étude diagnostique des a cteurs ML-CNRA-331536-CS-INDV / Component 2: Improve Acce Individual Consult Pending Impleme Réalisation par un consultant IDA / 59190 ss to Mango Production Area Post Limited 12,000.00 0.00 2023-01-10 2023-01-15 2023-01-25 2023-02-04 2023-04-05 ant Selection ntation du portail pour partager les i s nformations ML-CNRA-331539-CS-INDV / Component 2: Improve Acce Réalisation pour un consulta Individual Consult Pending Impleme IDA / 59190 ss to Mango Production Area Post Limited 12,000.00 0.00 2023-02-15 2023-02-20 2023-03-13 2023-04-17 2023-05-17 nt de la stratégie d'améliorat ant Selection ntation s ion de la visibilité des activit és du Projet ML-CNRA-306176-CS-CQS / Services de consultants pour la réalisation de l'étude d'ide ntification des principales co Component 4: Strengthen Pr Individual Consult Pending Impleme IDA / 59190 Post Limited 25,000.00 0.00 2023-01-16 2023-01-21 2023-02-11 2023-03-02 2023-05-01 ntraintes et défaillances du oject Implementation ant Selection ntation marché pour chacune des ch aines de valeur soutenues et élaborer des plans d'action s ur un ensemble d'interventio ns clés ML-CNRA-306391-CS-INDV / Service de consultant pour la réalisation de l'étude pour la mise en place d'un mécanis Component 4: Strengthen Pr Individual Consult Pending Impleme IDA / 59190 Post Limited 25,000.00 0.00 2023-01-23 2023-01-28 2023-02-18 2023-03-25 2023-05-09 me de subvention avec des c oject Implementation ant Selection ntation ontreparties des acteurs pou r les services communs et m ettre en place les infrastructu res spécialisées ML-CNRA-359889-CS-CDS / Component 4: Strengthen Pr Pending Impleme Recrutement d'un bureau po IDA / 59190 Post Direct Selection Direct - National 5,000.00 0.00 2023-05-22 2023-06-01 2023-07-02 2023-07-12 oject Implementation ntation ur l'audit final du Projet PACA M Page 8 PLAN DE ADQUISICIONES Información del proyecto: IP, Afro and Montubio Devt Project Agencia implementadora del Proyecto: Multiple Fecha del Plan de adquisiciones: Abril 2022 Período cubierto por este Plan de Adquisiciones: 2022 al Cierre del proyecto Preámbulo De conformidad con el párrafo 5.9 de las "Regulaciones de Adquisición del Banco Mundial para prestatarios IPF" ("Regulaciones de Adquisiciones") el Sistema de seguimiento en Adquisiciones (STEP) será utilizado para preparar, aclarar y actualizar los Planes de Adquisiciones y realizar todas las transacciones de adquisiciones para el Proyecto. Esta parte del texto, junto con las tablas del Plan de Adquisiciones en STEP constituyen el Plan de Adquisiciones para el Proyecto. Las siguientes condiciones aplican a todas las actividades de adquisición en el Plan de Adquisiciones. Los otros elementos del Plan de Adquisiciones como se exigen en el apartado 4.4 de las Regulaciones de Adquisiciones se exponen en el STEP. Documentos Estándar de Adquisiciones del Banco: Se utilizarán para todos los contratos sujetos a competencia internacional y los contratos así especificados en las tablas Plan de Adquisiciones de STEP. Disposiciones Nacionales de Adquisición: De conformidad con el párrafo 5.3 de las Regulaciones de Adquisiciones, cuando el enfoque es el mercado nacional (como se especifica en las tablas del Plan de Adquisiciones de STEP), se utilizarán documentos acordados con el Banco Mundial los cuales forman parte del Manual de Operaciones del Proyecto y se aplicarán las Regulaciones de Adquisiciones del Banco Mundial y no la Ley de Contrataciones del Estado de Ecuador. PROCUREMENT Ecuador : Territorial Economic Empowerment for the Indigenous, Afro-Ecuadorians and Montubian Peoples and Nationalities (TEEIPAM) PLAN General Information Country: Ecuador Bank’s Approval Date of the Original Procurement Plan: 2022-04-26 Revised Plan Date(s): (comma delineated, leave blank if 2023-05-24 none) Project ID: P173283 GPN Date: 2022-05-11 Project Name: Territorial Economic Empowerment for the Indigenous, Afro-Ecuadorians and Montubian Peoples and Nationalities (TEEIPAM) Loan / Credit No: IBRD / 91630 Secretary of Management and Development of Peoples and Nationalities Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EC-SGDPN-291347-GO-RFB / Component 4: Project Admin Request for Quota Single Stage - One E Adquisición de mobiliario de IBRD / 91630 istration, Communication, an Post Open - National 20,995.00 0.00 Canceled 2022-09-06 2022-11-01 2023-04-30 tions nvelope oficina para la operación de l d Monitoring and Evaluation as UIP EC-SGDPN-291345-GO-RFB / Component 4: Project Admin Single Stage - One E Pending Impl Adquisición de bienes inform IBRD / 91630 istration, Communication, an Post Request for Bids Open - National 86,000.00 0.00 2023-05-08 2023-05-13 2023-06-12 2023-06-27 2023-07-13 2023-07-28 nvelope ementation áticos para la operación de la d Monitoring and Evaluation s UIP EC-SGDPN-359986-GO-RFQ / Component 4: Project Admin Adquisición de suministros d Request for Quota Single Stage - One E Under Imple IBRD / 91630 istration, Communication, an Post Open - National 12,000.00 0.00 2023-06-03 2023-07-26 2023-08-10 e oficina para la Unidad Impl tions nvelope mentation d Monitoring and Evaluation ementadora del Proyecto- PR OFECPIAM EC-SGDPN-361875-GO-RFQ / Component 4: Project Admin Request for Quota Single Stage - One E Under Imple Adquisición de bienes inform IBRD / 91630 istration, Communication, an Post Open - National 86,000.00 0.00 2023-06-03 2023-07-09 2023-07-28 tions nvelope mentation áticos para la operación de la d Monitoring and Evaluation s UIP NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EC-SGDPN-291377-CS-CQS / Consultoria para el mapeo de Component 4: Project Admin Quality And Cost- los actores relevantes que co IBRD / 91630 istration, Communication, an Post Open - National 600,000.00 0.00 Canceled 2022-09-01 2022-09-26 2022-09-22 2022-11-05 2022-12-03 2023-01-02 2023-02-06 2023-03-13 2024-03-12 Based Selection nformaran las plataformas te d Monitoring and Evaluation rritoriales y diseño del espaci o de diálogo. EC-SGDPN-318858-CS-CQS / Consultoría para la evaluació n de los instrumentos de pla Component 1: Strengthening nificación existentes, oportun Governance and Investment Consultant Qualifi IBRD / 91630 Post Open - National 165,000.00 0.00 Canceled 2022-09-29 2022-10-03 2022-10-20 2022-12-03 2023-01-02 2023-02-06 2023-08-05 idades económicas, barreras Planning for IPAM Developm cation Selection de inclusión financiera, educ ent ación superior y oportunidad es de empleo en el territorio priorizado EC-SGDPN-318859-CS-CQS / Component 1: Strengthening Quality And Cost- Consultoría mapeo de actore IBRD / 91630 Governance and Investment Post Open - National 600,000.00 0.00 Canceled 2022-09-29 2022-10-04 2022-10-20 2022-12-03 2022-12-31 2023-01-30 2023-03-06 2023-04-10 2024-04-09 Based Selection s Planning for IPAM Developm ent EC-SGDPN-291381-CS-CQS / Implementar una estrategia Component 4: Project Admin de información con perspecti Consultant Qualifi IBRD / 91630 istration, Communication, an Post Open - National 70,000.00 0.00 Canceled 2022-11-07 2022-11-28 2023-01-11 2023-02-10 2023-03-17 2023-09-13 va de género para favorecer cation Selection d Monitoring and Evaluation la participación en la Platafor ma de diálogo nacional y sus resultados EC-SGDPN-291382-CS-CQS / Asistencia tecnica y gastos o Component 4: Project Admin perativos para la formulación Consultant Qualifi IBRD / 91630 istration, Communication, an Post Open - National 100,000.00 0.00 Canceled 2022-11-07 2022-11-28 2023-01-11 2023-02-10 2023-03-17 2023-09-13 y consulta de politicas public cation Selection d Monitoring and Evaluation as y sus respectivos reglame ntos priorizados por el espaci o de dialogo Nacional. EC-SGDPN-291379-CS-CQS / Desarrollo de línea de base p Component 4: Project Admin Consultant Qualifi Pending Impleme ara la medición de violencia IBRD / 91630 istration, Communication, an Post Open - National 70,000.00 0.00 2022-11-07 2022-11-28 2023-01-11 2023-02-10 2023-03-17 2023-09-13 cation Selection ntation basada en genero en comuni d Monitoring and Evaluation dades seleccionadas EC-SGDPN-323647-CS-QCBS / CONSULTORÍA PARA LA EVA LUACIÓN DE LOS INSTRUMEN Component 1: Strengthening TOS DE PLANIFICACIÓN Y EL Governance and Investment Quality And Cost- IBRD / 91630 Post Open - National 165,000.00 0.00 Canceled 2022-10-26 2022-10-28 2022-11-16 2022-12-30 2023-01-27 2023-02-26 2023-04-02 2023-05-07 2024-05-06 DIAGNÓSTICO DE BARRERAS Planning for IPAM Developm Based Selection DE INCLUSIÓN FINANCIERA, E ent DUCACIÓN SUPERIOR Y OPO RTUNIDADES DE EMPLEO EN CADA TERRITORIO PRIORIZA DO INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 EC-SGDPN-291313-CS-INDV Component 4: Project Admin Individual Consult / Consultoria para el Gerente IBRD / 91630 istration, Communication, an Post Open 197,384.23 2,937.27 Signed 2022-04-25 2022-05-17 2022-06-13 2022-07-06 2022-07-04 2022-07-18 2022-08-08 2022-07-23 2025-12-31 ant Selection de la UIP Central para la SGD d Monitoring and Evaluation PN EC-SGDPN-291317-CS-INDV Component 4: Project Admin / Consultoría para el Especiali Individual Consult IBRD / 91630 istration, Communication, an Post Open 143,943.79 0.00 Signed 2022-04-25 2022-05-16 2022-06-13 2022-09-07 2022-07-04 2022-09-12 2022-08-08 2023-02-04 sta Financiero de la UIP Centr ant Selection d Monitoring and Evaluation al de la SGDPN EC-SGDPN-291322-CS-INDV Component 4: Project Admin / Consultoría para el Especiali Individual Consult IBRD / 91630 istration, Communication, an Post Open 143,943.79 0.00 Signed 2022-04-25 2022-05-17 2022-06-13 2022-09-07 2022-07-04 2022-09-12 2022-08-08 2025-12-31 sta en Planificación de la UIP ant Selection d Monitoring and Evaluation Central de la SGDPN EC-SGDPN-291324-CS-INDV Component 4: Project Admin / Consultoría para el Especiali Individual Consult IBRD / 91630 istration, Communication, an Post Open 143,943.79 0.00 Signed 2022-04-25 2022-05-17 2022-06-13 2022-09-07 2022-07-04 2022-09-12 2022-08-08 2025-12-31 sta en Monitoreo y Evaluació ant Selection d Monitoring and Evaluation n de la UIP Central de la SGD PN EC-SGDPN-291356-CS-INDV / Consultoría para la evaluaci ón de los instrumentos de pl Component 4: Project Admin anificación existentes, oportu Individual Consult IBRD / 91630 istration, Communication, an Post Open 11,000.00 0.00 Canceled 2022-09-01 2022-09-27 2022-10-20 2022-11-10 2022-12-15 2023-06-13 nidades económicas, barrera ant Selection d Monitoring and Evaluation s de inclusión financiera, edu cación superior y oportunida des de empleo en el territori o priorizado 1. EC-SGDPN-291357-CS-INDV / Consultoría para la evaluaci ón de los instrumentos de pl Component 4: Project Admin anificación existentes, oportu Individual Consult IBRD / 91630 istration, Communication, an Post Open 11,000.00 0.00 Canceled 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2023-06-13 nidades económicas, barrera ant Selection d Monitoring and Evaluation s de inclusión financiera, edu cación superior y oportunida des de empleo en el territori o priorizado 2. EC-SGDPN-291358-CS-INDV / Consultoría para la evaluaci ón de los instrumentos de pl Component 4: Project Admin anificación existentes, oportu Individual Consult IBRD / 91630 istration, Communication, an Post Open 11,000.00 0.00 Canceled 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2023-06-13 nidades económicas, barrera ant Selection d Monitoring and Evaluation s de inclusión financiera, edu cación superior y oportunida des de empleo en el territori o priorizado 3. EC-SGDPN-291359-CS-INDV / Consultoría para la evaluaci ón de los instrumentos de pl Component 4: Project Admin anificación existentes, oportu Individual Consult IBRD / 91630 istration, Communication, an Post Open 11,000.00 0.00 Canceled 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2023-06-13 nidades económicas, barrera ant Selection d Monitoring and Evaluation s de inclusión financiera, edu cación superior y oportunida des de empleo en el territori o priorizado 4. EC-SGDPN-291361-CS-INDV / Consultoría para la evaluaci ón de los instrumentos de pl Component 4: Project Admin anificación existentes, oportu Individual Consult IBRD / 91630 istration, Communication, an Post Open 11,000.00 0.00 Canceled 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2023-06-13 nidades económicas, barrera ant Selection d Monitoring and Evaluation s de inclusión financiera, edu cación superior y oportunida des de empleo en el territori o priorizado 5. EC-SGDPN-291365-CS-INDV / Consultoría para la evaluaci ón de los instrumentos de pl Component 4: Project Admin anificación existentes, oportu Individual Consult IBRD / 91630 istration, Communication, an Post Open 11,000.00 0.00 Canceled 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2023-06-13 nidades económicas, barrera ant Selection d Monitoring and Evaluation s de inclusión financiera, edu cación superior y oportunida des de empleo en el territori o priorizado 6. EC-SGDPN-291367-CS-INDV / Consultoría para la evaluaci ón de los instrumentos de pl Component 4: Project Admin anificación existentes, oportu Individual Consult IBRD / 91630 istration, Communication, an Post Open 11,000.00 0.00 Canceled 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2023-06-13 nidades económicas, barrera ant Selection d Monitoring and Evaluation s de inclusión financiera, edu cación superior y oportunida des de empleo en el territori o priorizado 7. EC-SGDPN-291368-CS-INDV / Consultoría para la evaluaci ón de los instrumentos de pl Component 4: Project Admin anificación existentes, oportu Individual Consult IBRD / 91630 istration, Communication, an Post Open 11,000.00 0.00 Canceled 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2023-06-13 nidades económicas, barrera ant Selection d Monitoring and Evaluation s de inclusión financiera, edu cación superior y oportunida des de empleo en el territori o priorizado 8. EC-SGDPN-291369-CS-INDV / Consultoría para la evaluaci ón de los instrumentos de pl Component 4: Project Admin anificación existentes, oportu Individual Consult IBRD / 91630 istration, Communication, an Post Open 11,000.00 0.00 Canceled 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2023-06-13 nidades económicas, barrera ant Selection d Monitoring and Evaluation s de inclusión financiera, edu cación superior y oportunida des de empleo en el territori o priorizado 9. EC-SGDPN-291370-CS-INDV / Consultoría para la evaluaci ón de los instrumentos de pl Component 4: Project Admin anificación existentes, oportu Individual Consult IBRD / 91630 istration, Communication, an Post Open 11,000.00 0.00 Canceled 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2023-06-13 nidades económicas, barrera ant Selection d Monitoring and Evaluation s de inclusión financiera, edu cación superior y oportunida des de empleo en el territori o priorizado 10. EC-SGDPN-291372-CS-INDV / Consultoría para la evaluaci ón de los instrumentos de pl Component 4: Project Admin anificación existentes, oportu Individual Consult IBRD / 91630 istration, Communication, an Post Open 11,000.00 0.00 Canceled 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2023-06-13 nidades económicas, barrera ant Selection d Monitoring and Evaluation s de inclusión financiera, edu cación superior y oportunida des de empleo en el territori o priorizado 11. Page 2 EC-SGDPN-291373-CS-INDV / Consultoría para la evaluaci ón de los instrumentos de pl Component 4: Project Admin anificación existentes, oportu Individual Consult IBRD / 91630 istration, Communication, an Post Open 11,000.00 0.00 Canceled 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2023-06-13 nidades económicas, barrera ant Selection d Monitoring and Evaluation s de inclusión financiera, edu cación superior y oportunida des de empleo en el territori o priorizado 12. EC-SGDPN-291374-CS-INDV / Consultoría para la evaluaci ón de los instrumentos de pl Component 4: Project Admin anificación existentes, oportu Individual Consult IBRD / 91630 istration, Communication, an Post Open 11,000.00 0.00 Canceled 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2023-06-13 nidades económicas, barrera ant Selection d Monitoring and Evaluation s de inclusión financiera, edu cación superior y oportunida des de empleo en el territori o priorizado 13. EC-SGDPN-291375-CS-INDV / Consultoría para la evaluaci ón de los instrumentos de pl Component 4: Project Admin anificación existentes, oportu Individual Consult IBRD / 91630 istration, Communication, an Post Open 11,000.00 0.00 Canceled 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2023-06-13 nidades económicas, barrera ant Selection d Monitoring and Evaluation s de inclusión financiera, edu cación superior y oportunida des de empleo en el territori o priorizado 14. EC-SGDPN-291376-CS-INDV / Consultoría para la evaluaci ón de los instrumentos de pl Component 4: Project Admin anificación existentes, oportu Individual Consult IBRD / 91630 istration, Communication, an Post Open 11,000.00 0.00 Canceled 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2023-06-13 nidades económicas, barrera ant Selection d Monitoring and Evaluation s de inclusión financiera, edu cación superior y oportunida des de empleo en el territori o priorizado 15. EC-SGDPN-314028-CS-INDV Component 4: Project Admin Individual Consult Under Implement / Especialista Técnico Operat IBRD / 91630 istration, Communication, an Post Open - National 122,352.22 0.00 2022-09-09 2022-09-30 2022-10-28 2022-11-18 2022-12-23 2026-05-17 ant Selection ation ivo Territorial - Imbabura d Monitoring and Evaluation EC-SGDPN-314029-CS-INDV Component 4: Project Admin / Analista Tecnico Ambientale Individual Consult Under Implement IBRD / 91630 istration, Communication, an Post Open - National 89,006.17 0.00 2022-09-09 2022-09-30 2022-10-28 2022-11-18 2022-12-23 2026-05-17 s (Salvaguardas Banco Mundi ant Selection ation d Monitoring and Evaluation al) - Imbabura EC-SGDPN-314030-CS-INDV Component 4: Project Admin Individual Consult Under Implement / Analista Técnico Social - Im IBRD / 91630 istration, Communication, an Post Open - National 89,006.17 0.00 2022-09-09 2022-09-30 2022-10-28 2022-11-18 2022-12-23 2026-05-17 ant Selection ation babura d Monitoring and Evaluation EC-SGDPN-314031-CS-INDV Component 4: Project Admin / Analista Técnico en Gobern Individual Consult Under Implement IBRD / 91630 istration, Communication, an Post Open - National 89,006.17 0.00 2022-09-09 2022-09-30 2022-10-28 2022-11-18 2022-12-23 2026-05-17 anza (Fortalecimiento organi ant Selection ation d Monitoring and Evaluation zativo y comercial) - Imbabur a EC-SGDPN-314032-CS-INDV Component 4: Project Admin Individual Consult Under Implement / Especialista Técnico Operati IBRD / 91630 istration, Communication, an Post Open - National 122,353.22 0.00 2022-09-09 2022-09-30 2022-10-28 2022-11-18 2022-12-23 2026-05-17 ant Selection ation vo Territorial - Guayas d Monitoring and Evaluation EC-SGDPN-314033-CS-INDV Component 4: Project Admin Individual Consult Under Implement / Analista Tecnico Ambientale IBRD / 91630 istration, Communication, an Post Open - National 89,006.17 0.00 2022-09-09 2022-09-30 2022-10-28 2022-11-18 2022-12-23 2026-05-17 ant Selection ation s (Salvaguardas Banco Mundi d Monitoring and Evaluation al) - Guayas EC-SGDPN-314034-CS-INDV Component 4: Project Admin Individual Consult Under Implement / Analista Técnico Social - Gu IBRD / 91630 istration, Communication, an Post Open - National 89,006.17 0.00 2022-09-09 2022-09-30 2022-10-28 2022-11-18 2022-12-23 2026-05-17 ant Selection ation ayas d Monitoring and Evaluation EC-SGDPN-314035-CS-INDV Component 4: Project Admin / Analista Técnico en Gobern Individual Consult Under Implement IBRD / 91630 istration, Communication, an Post Open - National 89,006.17 0.00 2022-09-09 2022-09-30 2022-10-28 2022-11-18 2022-12-23 2026-05-17 anza (Fortalecimiento organi ant Selection ation d Monitoring and Evaluation zativo y comercial) - Guayas EC-SGDPN-314036-CS-INDV Component 4: Project Admin Individual Consult Under Implement / Asistente Administrativa - I IBRD / 91630 istration, Communication, an Post Open - National 45,476.66 0.00 2022-09-09 2022-09-30 2022-10-28 2022-11-18 2022-12-23 2026-05-17 ant Selection ation mbabura d Monitoring and Evaluation EC-SGDPN-314037-CS-INDV Component 4: Project Admin Individual Consult Under Implement / Asistente Administrativa - G IBRD / 91630 istration, Communication, an Post Open - National 45,476.66 0.00 2022-09-09 2022-09-30 2022-10-28 2022-11-18 2022-12-23 2026-05-17 ant Selection ation uayas d Monitoring and Evaluation EC-SGDPN-314038-CS-INDV Component 4: Project Admin Individual Consult Under Implement / Especialista Técnico Operati IBRD / 91630 istration, Communication, an Post Open - National 122,352.22 0.00 2022-09-09 2022-09-29 2022-10-28 2022-11-18 2022-12-23 2026-05-17 ant Selection ation vo Territorial - Azuay d Monitoring and Evaluation EC-SGDPN-314039-CS-INDV Component 4: Project Admin Individual Consult Under Implement / Analista Tecnico Ambientale IBRD / 91630 istration, Communication, an Post Open - National 89,006.17 0.00 2022-09-09 2022-09-29 2022-10-28 2022-11-18 2022-12-23 2026-05-17 ant Selection ation s (Salvaguardas Banco Mundi d Monitoring and Evaluation al) - Azuay EC-SGDPN-314040-CS-INDV Component 4: Project Admin Individual Consult Under Implement / Analista Técnico Social - Az IBRD / 91630 istration, Communication, an Post Open - National 89,006.17 0.00 2022-09-09 2022-09-29 2022-10-28 2022-11-18 2022-12-23 2026-05-17 ant Selection ation uay d Monitoring and Evaluation EC-SGDPN-314041-CS-INDV Component 4: Project Admin / Analista Técnico en Gobern Individual Consult Under Implement IBRD / 91630 istration, Communication, an Post Open - National 89,006.17 0.00 2022-09-09 2022-09-29 2022-10-28 2022-11-18 2022-12-23 2026-05-17 anza (Fortalecimiento organi ant Selection ation d Monitoring and Evaluation zativo y comercial) Azuay EC-SGDPN-314042-CS-INDV Component 4: Project Admin Individual Consult Under Implement / Asistente Administrativa - A IBRD / 91630 istration, Communication, an Post Open - National 45,476.66 0.00 2022-09-09 2022-09-29 2022-10-28 2022-11-18 2022-12-23 2026-05-17 ant Selection ation zuay d Monitoring and Evaluation EC-SGDPN-314043-CS-INDV Component 4: Project Admin Individual Consult Under Implement / Especialista Técnico Operati IBRD / 91630 istration, Communication, an Post Open - National 122,352.22 0.00 2022-09-09 2022-09-30 2022-10-28 2022-11-18 2022-12-23 2026-05-17 ant Selection ation vo Territorial - Manabi d Monitoring and Evaluation EC-SGDPN-314044-CS-INDV Component 4: Project Admin Individual Consult Under Implement / Analista Tecnico Ambientale IBRD / 91630 istration, Communication, an Post Open - National 89,006.17 0.00 2022-09-09 2022-09-30 2022-10-28 2022-11-18 2022-12-23 2026-05-17 ant Selection ation s (Salvaguardas Banco Mundi d Monitoring and Evaluation al) - Manabi EC-SGDPN-314045-CS-INDV Component 4: Project Admin Individual Consult Under Implement / Analista Técnico Social - Ma IBRD / 91630 istration, Communication, an Post Open - National 89,006.17 0.00 2022-09-09 2022-09-30 2022-10-28 2022-11-18 2022-12-23 2026-05-17 ant Selection ation nabi d Monitoring and Evaluation Page 3 EC-SGDPN-314046-CS-INDV Component 4: Project Admin / Analista Técnico en Gobern Individual Consult Under Implement IBRD / 91630 istration, Communication, an Post Open - National 89,006.17 0.00 2022-09-09 2022-09-30 2022-10-28 2022-11-18 2022-12-23 2026-05-17 anza (Fortalecimiento organi ant Selection ation d Monitoring and Evaluation zativo y comercial) - Manabi EC-SGDPN-314047-CS-INDV Component 4: Project Admin Individual Consult Under Implement / Asistente Administrativo - M IBRD / 91630 istration, Communication, an Post Open - National 45,476.66 0.00 2022-09-09 2022-09-30 2022-10-28 2022-11-18 2022-12-23 2026-05-17 ant Selection ation anabi d Monitoring and Evaluation EC-SGDPN-314048-CS-INDV Component 4: Project Admin Individual Consult Under Implement / Especialista Técnico Operati IBRD / 91630 istration, Communication, an Post Open - National 122,353.22 0.00 2022-09-09 2022-09-29 2022-10-28 2022-11-18 2022-12-23 2026-05-17 ant Selection ation vo Territorial - Tungurahua d Monitoring and Evaluation EC-SGDPN-314049-CS-INDV Component 4: Project Admin / Analista Tecnico Ambientale Individual Consult Under Implement IBRD / 91630 istration, Communication, an Post Open - National 89,006.17 0.00 2022-09-09 2022-09-29 2022-10-28 2022-11-18 2022-12-23 2026-05-17 s (Salvaguardas Banco Mundi ant Selection ation d Monitoring and Evaluation al) - Tungurahua EC-SGDPN-314050-CS-INDV Component 4: Project Admin Individual Consult Under Implement / Analista Técnico Social - Tu IBRD / 91630 istration, Communication, an Post Open - National 89,006.17 0.00 2022-09-09 2022-09-29 2022-10-28 2022-11-18 2022-12-23 2026-05-17 ant Selection ation ngurahua d Monitoring and Evaluation EC-SGDPN-314051-CS-INDV Component 4: Project Admin / Analista Técnico en Gobern Individual Consult Under Implement IBRD / 91630 istration, Communication, an Post Open - National 89,006.17 0.00 2022-09-09 2022-09-29 2022-10-28 2022-11-18 2022-12-23 2026-05-17 anza (Fortalecimiento organi ant Selection ation d Monitoring and Evaluation zativo y comercial) - Tungura hua EC-SGDPN-314052-CS-INDV Component 4: Project Admin Individual Consult Under Implement / Asistente Administrativo - T IBRD / 91630 istration, Communication, an Post Open - National 45,476.66 0.00 2022-09-09 2022-09-29 2022-10-28 2022-11-18 2022-12-23 2026-05-17 ant Selection ation ungurahua d Monitoring and Evaluation EC-SGDPN-291319-CS-INDV Component 4: Project Admin / Consultoría para el Analista Individual Consult IBRD / 91630 istration, Communication, an Post Open 104,713.15 0.00 Canceled 2022-04-25 2022-05-17 2022-06-13 2022-07-04 2022-08-08 2025-12-31 Legal de la UIP Central de la ant Selection d Monitoring and Evaluation SGDPN de la SGDPN EC-SGDPN-291315-CS-INDV Component 4: Project Admin / Consultoría para el Especiali Individual Consult IBRD / 91630 istration, Communication, an Post Open 143,943.79 0.00 Canceled 2022-04-25 2022-05-17 2022-06-13 2022-07-04 2022-08-08 2025-12-31 sta Técnico Operativo de la U ant Selection d Monitoring and Evaluation IP Central de la SGDPN EC-SGDPN-291340-CS-INDV Component 4: Project Admin / Consultoría para el Asistent Individual Consult IBRD / 91630 istration, Communication, an Post Open 52,610.25 0.00 Canceled 2022-04-25 2022-05-17 2022-06-13 2022-07-04 2022-08-08 2025-12-31 e Administrativo de la UIP Ce ant Selection d Monitoring and Evaluation ntral de la SGDPN EC-SGDPN-291320-CS-INDV Component 4: Project Admin / Consultoría para el Analista Individual Consult IBRD / 91630 istration, Communication, an Post Open 104,713.15 0.00 Canceled 2022-04-25 2022-05-17 2022-06-13 2022-07-04 2022-08-08 2025-12-31 de Comunicaciones de la UIP ant Selection d Monitoring and Evaluation Central de la SGDPN EC-SGDPN-291338-CS-INDV Component 4: Project Admin / Consultoría para el Analista Individual Consult IBRD / 91630 istration, Communication, an Post Open 104,713.15 0.00 Canceled 2022-04-25 2022-05-17 2022-06-13 2022-07-04 2022-08-08 2025-12-31 de Pueblos y Nacionalidades ant Selection d Monitoring and Evaluation M de la UIP Central de la SGD PN EC-SGDPN-291327-CS-INDV Component 4: Project Admin / Consultoría para el Analista Individual Consult IBRD / 91630 istration, Communication, an Post Open 104,713.15 0.00 Canceled 2022-04-25 2022-05-17 2022-06-13 2022-07-04 2022-08-08 2025-12-31 de Pueblos y Nacionalidades ant Selection d Monitoring and Evaluation PI de la UIP Central de la SGD PN EC-SGDPN-291337-CS-INDV Component 4: Project Admin / Consultoría para el Analista Individual Consult IBRD / 91630 istration, Communication, an Post Open 104,713.15 0.00 Canceled 2022-04-25 2022-05-17 2022-06-13 2022-07-04 2022-08-08 2025-12-31 de Pueblos y Nacionalidades ant Selection d Monitoring and Evaluation A de la UIP Central de la SGD PN EC-SGDPN-291325-CS-INDV Component 4: Project Admin Individual Consult / Consultoría para el Especiali IBRD / 91630 istration, Communication, an Post Open 143,943.79 0.00 Canceled 2022-04-25 2022-05-17 2022-06-13 2022-07-04 2022-08-08 2025-12-31 ant Selection sta Social de la UIP Central d d Monitoring and Evaluation e la SGDPN EC-SGDPN-291326-CS-INDV Component 4: Project Admin / Consultoría para el Especiali Individual Consult IBRD / 91630 istration, Communication, an Post Open 143,943.79 0.00 Canceled 2022-04-25 2022-05-17 2022-06-13 2022-07-04 2022-08-08 2025-12-31 sta Ambiental de la UIP Centr ant Selection d Monitoring and Evaluation al de la SGDPN EC-SGDPN-291321-CS-INDV Component 4: Project Admin Individual Consult / Consultoría para el Analista IBRD / 91630 istration, Communication, an Post Open 85,474.37 0.00 Canceled 2022-04-25 2022-05-17 2022-06-13 2022-09-07 2022-07-04 2022-08-08 2025-12-31 ant Selection de Sistema de la UIP Central d Monitoring and Evaluation de la SGDPN EC-SGDPN-291316-CS-INDV Component 4: Project Admin / Consultoría para el Especiali Individual Consult IBRD / 91630 istration, Communication, an Post Open 143,942.79 0.00 Canceled 2022-04-25 2022-05-20 2022-06-13 2022-09-07 2022-07-04 2022-08-08 2025-12-31 sta en Adquisiciones de la UI ant Selection d Monitoring and Evaluation P Central de la SGDPN EC-SGDPN-291321-CS-INDV- Component 4: Project Admin 2 / Consultoría para el Analist Individual Consult IBRD / 91630 istration, Communication, an Post Open - National 85,474.37 0.00 Signed 2022-09-14 2022-10-03 2022-10-19 2022-11-15 2022-10-24 2022-11-15 2022-10-31 2026-03-25 a de Sistemas de la UIP Centr ant Selection d Monitoring and Evaluation al de la SGDPN EC-SGDPN-291316-CS-INDV- Component 4: Project Admin 2 / Consultoría para el Especi Individual Consult IBRD / 91630 istration, Communication, an Prior Open - National 143,942.79 0.00 Canceled 2022-09-27 2022-10-06 2022-10-16 2022-11-16 2022-10-18 2022-10-24 2026-03-18 alista en Adquisiciones de la ant Selection d Monitoring and Evaluation UIP Central de la SGDPN EC-SGDPN-318359-CS-INDV Component 4: Project Admin / Consultoría para el Analista Individual Consult IBRD / 91630 istration, Communication, an Post Open - National 104,713.15 0.00 Signed 2022-09-28 2022-10-04 2022-10-17 2022-11-15 2022-10-19 2022-11-30 2022-10-25 2026-12-30 Legal de la UIP Central de la ant Selection d Monitoring and Evaluation SGDPN de la SGDPN EC-SGDPN-318855-CS-INDV Component 4: Project Admin / Consultoría para el Especiali Individual Consult IBRD / 91630 istration, Communication, an Post Open - National 143,943.79 0.00 Signed 2022-09-29 2022-10-03 2022-10-18 2022-11-15 2022-10-20 2022-11-15 2022-10-25 2026-12-30 sta Social y de Género de la ant Selection d Monitoring and Evaluation UIP Central de la SGDPN EC-SGDPN-318857-CS-INDV Component 4: Project Admin / Consultoría para el Especiali Individual Consult IBRD / 91630 istration, Communication, an Post Open - National 143,943.79 0.00 Signed 2022-09-29 2022-10-04 2022-10-18 2022-11-15 2022-10-20 2022-11-15 2022-10-25 2026-12-31 sta Ambiental de la UIP Centr ant Selection d Monitoring and Evaluation al de la SGDPN Page 4 EC-SGDPN-318864-CS-INDV Component 4: Project Admin / Consultoría para el Analista Individual Consult IBRD / 91630 istration, Communication, an Post Open - National 104,713.15 0.00 Canceled 2022-09-29 2022-10-03 2022-10-18 2022-10-20 2022-10-25 2026-12-31 de Pueblos y Nacionalidades ant Selection d Monitoring and Evaluation M de la UIP Central de la SGD PN EC-SGDPN-318866-CS-INDV Component 4: Project Admin / Consultoría para el Analista Individual Consult IBRD / 91630 istration, Communication, an Post Open - National 104,713.15 0.00 Signed 2022-09-29 2022-10-04 2022-10-18 2022-11-15 2022-10-20 2022-11-15 2022-10-25 2026-12-31 de Comunicaciones de la UIP ant Selection d Monitoring and Evaluation Central de la SGDPN EC-SGDPN-318867-CS-INDV Component 4: Project Admin / Consultoría para el Asistent Individual Consult IBRD / 91630 istration, Communication, an Post Open - National 52,610.25 0.00 Signed 2022-09-29 2022-10-04 2022-10-18 2022-11-15 2022-10-20 2022-11-15 2022-10-25 2026-12-31 e Administrativo de la UIP Ce ant Selection d Monitoring and Evaluation ntral de la SGDPN EC-SGDPN-318868-CS-INDV Component 4: Project Admin / Consultoría para el Analista Individual Consult IBRD / 91630 istration, Communication, an Post Open - National 104,713.15 0.00 Signed 2022-09-29 2022-10-03 2022-10-18 2022-11-14 2022-10-20 2022-11-14 2022-10-25 2026-12-31 de Pueblos y Nacionalidades ant Selection d Monitoring and Evaluation PI de la UIP Central de la SGD PN EC-SGDPN-318869-CS-INDV Component 4: Project Admin / Consultoría para el Especiali Individual Consult Under Implement IBRD / 91630 istration, Communication, an Post Open - National 143,943.79 0.00 2022-09-29 2022-10-04 2022-10-18 2022-11-11 2022-10-20 2022-11-11 2022-10-25 2026-12-31 sta Técnico Operativo de la U ant Selection ation d Monitoring and Evaluation IP Central de la SGDPN EC-SGDPN-318871-CS-INDV Component 4: Project Admin / Consultoría para el Analista Individual Consult IBRD / 91630 istration, Communication, an Post Open - National 104,713.15 0.00 Canceled 2022-09-29 2022-10-03 2022-10-18 2022-10-20 2022-10-25 2026-12-31 de Pueblos y Nacionalidades ant Selection d Monitoring and Evaluation A de la UIP Central de la SGD PN EC-SGDPN-318871-CS-INDV- Component 4: Project Admin 2 / Consultoría para el Analist Individual Consult Under Implement IBRD / 91630 istration, Communication, an Post Open - National 104,713.15 0.00 2023-05-08 2023-05-29 2023-06-14 2023-06-21 2023-06-26 2026-12-31 a de Pueblos y Nacionalidade ant Selection ation d Monitoring and Evaluation s Afroecuatoriano de la UIP C entral de la SGDPN EC-SGDPN-318864-CS-INDV- Component 4: Project Admin 2 / Consultoría para el Analist Individual Consult Under Implement IBRD / 91630 istration, Communication, an Post Open - National 104,173.15 0.00 2023-05-08 2023-05-29 2023-06-09 2023-06-19 2023-06-24 2026-12-31 a de Pueblos y Nacionalidade ant Selection ation d Monitoring and Evaluation s Montubio de la UIP Central de la SGDPN Page 5 CAMEROUN PROJET D’APPUI AU DEVELOPPEMENT DU SECTEUR DES TRANSPORTS NUMERO D’IDENTIFICATION DU PROJET : P150999 Numéro du crédit : IBRD-86500 PLAN SIMPLIFIE DE PASSATION DES MARCHES I. GENERAL 1. Informations sur le Projet Bénéficiaire : République du Cameroun Ministères Responsables: Ministère des Travaux Publics - Ministère des Transports Nom du Projet : Projet d’appui au Développement du Secteur des Transports (PDST). Agences d’exécutions du Projet : Cellule BAD-BM du MINTP - Cameroon Civil Aviation Authority. 2. Date d’approbation par la Banque du Plan de Passation des Marchés : 09/09/2016 3. Date de publication de l’Avis Général de Passation des Marchés: 01/11/2016 4. Période couverte par le Plan de Passation des Marchés : (Décembre 2016) à (Mai 2018). 5. Evaluation de risque par P-RAMS (Procurement Risk Assessment and Management System): Elevé. II. TRAVAUX, FOURNITURES ET SERVICES NON INTELLECTUELS 1. Dispositions relatives aux seuils de revue préalable : Seuils requis pour les décisions de marchés soumis à la revue préalable de la Banque, tel que prévu dans l’annexe 1 des "Directives de Passation des Marchés de fournitures, de travaux et de services (autres que les services de consultants) par les Emprunteurs de la Banque mondiale dans le cadre des prêts de la BIRD et des crédits de l’AID" et l’Annexe 1 des procédures de la Banque pour les projets d’investissements et les opérations. Page 1 of 12 Catégories de Seuils de revue à Observations marches/Méthode de priori passation des marchés Montants estimatifs des contrats en millions de dollars américains Travaux, Contrats clé en main et Les justifications de Contrats de Fourniture et Montage >= 10 l’entente directe d’Installations accompagnées du PPM Fournitures, Système d’information, sont soumis à la et Services autres que les services de >= 2 Banque Mondiale pour consultants approbation. Travaux, Contrats clé en main et Contrats de Fourniture et >= 10 Contrats à passer Montage d’Installations par entente Fournitures, directe Système d’information, et Services autres >2 que les services de consultants 2. Pré qualification : Les soumissionnaires, en cas de pré-qualification, (voir dans le tableau ci-joints) seront pré qualifiées en accord avec les dispositions des paragraphes 2.9 et 2.10 des directives. 3. Seuils pour les méthodes de passation des marchés : Les seuils de passation des marchés se présentent comme suit au vu des conditions du marché : FOURNITURES ET PRESTATIONS TRAVAUX (US$ équivalent) NON INTELLECTUELLES (US$ équivalent) AOI AON CF AOI AON CF ≥10,000. <10.000. < ≥ < <1.000.000 000 000 200,000 1.000.000 100,000 4. Dispositions spéciales sur les marchés : Concernant les acquisitions de véhicules et de carburant, en fonction des circonstances et des besoins spécifiques du pays, le seuil pour la consultation de fournisseurs pourrait être Page 2 of 12 porté à la contre-valeur de USD 500,000 (en prenant soin de consulter tous les principaux concessionnaires de marque ou distributeurs de produits pétroliers). Page 3 of 12 5. Liste des marchés avec les méthodes de passation et les dates de mise en œuvre Fournitures, Travaux et Services autres que services de consultants Cellule BAD-BM du MINTP 1 2 3 4 5 6 7 8 9 Ref. Description Coût Méthode Pré Préféren Revue de Date Commenta No. estimatif passation qualificati ce la Banque prévue de ires/ Fin (US$) des on national (à priori / à l’ouvertur de marchés (oui/non) e posteriori) e des prestation (oui/non) offres s Acquisition Posterior i 26/02/20 23/05/20 1 fourniture de 20 000 CF NON NON 17 17 bureau 2 Acquisition Posterior 26/02/20 23/05/20 fourniture 80 000 CF NON NON i 17 17 informatique 3 Assurance Posterior 26/02/20 23/05/20 50 000 CF NON NON personnel i 17 17 4 Travaux de réhabilitation de la route BABADJOU- 102 500 29/11/20 23/12/20 BAMENDA (52 000 AOI NON NON Priori 16 19 km) de l'axe Yaoundé - Bafoussam - Bamenda. 5 Travaux de déplacement des Posterior 05/02/20 28/10/201 1 000 000 ED NON NON réseaux d’eau i 17 7 (CAMWATER) 6 Travaux de déplacement des réseaux Posterior 05/02/20 28/10/201 d’électricité 1 200 000 ED NON NON i 17 7 (ENEO) 7 Travaux de déplacement des réseaux Posterior 05/02/20 28/10/201 1 000 000 ED NON NON téléphonique et i 17 7 internet (CAMTEL) 8 Travaux 25/12/20 30/10/201 17 900 000 AOI NON NON Priori 17 9 d’infrastructure Page 4 of 12 socio- économique dans la ZIP Babadjou- Bamenda Coût total en 123 750 - - - - US$ 000 Cameroon Civil Aviation Authority 1 2 3 4 5 6 7 8 9 Ref. Description Coût Méthode Pré Préféren Revue de Date Commenta No. estimatif passation qualificati ce la Banque prévue de ires/ Fin (US$) des on national (à priori / à l’ouvertur de marchés (oui/non) e posteriori) e des prestation (oui/non) offres s Acquisition Posterior i 26/02/20 23/05/20 1 fourniture de 20 000 CF NON NON 17 17 bureau 2 Acquisition Posterior 26/02/20 23/05/20 fourniture 80 000 CF NON NON i 17 17 informatique 3 Assurance Posterior 26/02/20 23/05/20 50 000 CF NON NON personnel i 17 17 4 Travaux de construction de trois (03) centres directeurs des Posterior 28/06/20 30/08/20 opérations 4 400 000 AON NON NON i 17 19 d’urgences à yaoundé, Garoua et Maroua (03 lots) 5 Travaux de réparation de la Posterior 30/05/20 18/07/201 clôture autour de 3 400 000 AON NON NON i 17 9 l’aéroport de Douala 6 -Travaux de bitumage économique de 28/06/20 30/08/201 la route de 10 350 000 AOI NON NON Priori 17 9 patrouille autour de l’aéroport de Douala. Page 5 of 12 -Travaux de bitumage économique d’une route de contournement de l’aéroport de Yaoundé (02 lots) Coût total en 18 300 - - - - US$ 000 Page 6 of 12 III. SÉLECTION DES CONSULTANTS 1. Dispositions relatives aux seuils de revue préalable : Seuils requis pour les décisions des contrats soumis à la revue préalable de la Banque tel que prévu dans l’annexe 1 des Directives de Sélection des Consultants par les Emprunteurs de la Banque Mondiale dans le cadre des Prêts de la BIRD et des Crédits de l’AID et l’Annexe 1 des procédures de la Banque pour les projets d’investissements et les opérations. Méthode de Seuils de revue Observations sélection/Catégories de a priori marchés Montants estimatifs des contrats en millions de dollars américains Méthode compétitive/Firmes >= 1 de consultants Entente directe/firmes de >= 1 Les justifications de l’entente consultants directe accompagnées du PPM Entente directe/Consultants sont soumis à la Banque Mondiale >= 0.3 pour approbation. individuel Méthode Compétitive >= 0.3 (Comparaison de CVs)/ Consultants individuels 2. Liste restreinte composée entièrement de firmes nationales: La liste restreinte de consultants pour les prestations d’études d’ingénierie, de contrôle et de surveillance estimées à moins de 300,000 US$ par contrat, et pour tout autre type de prestations, estimées à moins de 100 000 US$ par contrat, peut comporter entièrement de consultants nationaux selon les dispositions du paragraphe 2.7 des Directives de Sélection et d’Emploi des Consultants, et l’Emprunteur ne procède pas à une publication dans UNDB. 3. Autre arrangement spécial de Sélection de consultants : Le seuil pour l’utilisation de la méthode de sélection de consultant fondée sur les qualifications des consultants est déterminé au cas par cas en tenant compte de la nature et de la complexité de la mission; cependant, ce seuil ne devrait pas dépasser la contre-valeur de USD 300,000 sauf dans des cas exceptionnels prévus au paragraphe 3.7 des directives pour la sélection et l’emploi des consultants par les emprunteurs de la Banque Mondiale dans le cadre des Prêts de la BIRD et des Crédits et Dons de l’AID Page 7 of 12 Page 8 of 12 4. Liste des Consultations, avec les méthodes de sélection et le calendrier de mise œuvre Cellule BAD-BM du MINTP 1 2 3 4 5 6 7 Ref. Description des Coût estimatif Méthode Revue Commenta Date No. Missions ($EU) de de la prévue de ires/ Fin de sélectio Banque soumissio prestation n (à priori s n des /à propositio posterio ns ri) 1 Contrôle et surveillance des travaux de réhabilitation de la route Babadjou- Bamenda (52 KM) 18/10/201 23/12/201 5 900 000 SFQC Priori 6 9 sur l'axe Yaoundé - Bafoussam - Bamenda 2 Etude de faisabilité et technique détaillée pour les Posterior 18/03/201 31/12/201 infrastructures 600 000 SFQC i 7 7 socioéconomiques de la ZIP Babadjou- Bamenda 3 Evaluation des impacts sociaux Posterior 18/03/201 31/09/201 environnementaux 100 000 QC i 7 7 de la ZIP Babadjou- Bamenda 4 Supervision des travaux d’infrastructure 25/12/201 30/11/201 1 400 000 SFQC Priori socio-économiques 7 9 de la ZIP Babadjou- bamenda 5 Posterior Audit financier et i comptable du projet (revue 14/03/201 05/08/201 pour les exercices 150 000 SFQC techniqu 7 9 2017, 2018 et 2019 e de la BM) 6 Recrutement d'un Posterior 14/02/201 31/06/201 consultant individuel 24 000 CI i 7 9 pour les prestations Page 9 of 12 d’assistant comptable du projet 7 Recrutement d'un consultant individuel Posterior pour les prestations i 14/02/201 31/06/201 24 000 CI d’assistant au RAF du 7 9 projet 8 Recrutement de Posterior consultant pour l’audit i 04/05/201 28/12/201 400 000 SFQC technique des travaux 7 8 routiers du projet. 9 Recrutement d’un Posterior consultant individuel i pour les prestations (revue 20/02/201 25/08/201 76 800 CI de spécialiste techniqu 7 9 environnementaliste e de la et social senior BM) Coût total en US$ 8 674 800 - - - - Cameroon Civil Aviation Authority 1 2 3 4 5 6 7 Ref Description des Coût estimatif Méthod Revue Date Comment . Missions ($EU) e de de la prévue aires/ Fin No. sélectio Banque de de n (à priori soumissi prestatio /à on des ns posteri propositi ori) ons 1 Contrôle et surveillance des travaux de Posterior construction de trois i 14/05/201 310 000 SFQC 30/09/19 (03) centres directeurs 7 des opérations d’urgences à yaoundé, Garoua et Maroua 2 Contrôle et 30/08/19 surveillance des Posterior i 29/04/201 travaux de réparation 240 000 SFQC 7 de la clôture autour de l’aéroport de Douala 3 - Contrôle et surveillance des Posterior 14/05/201 05/09/201 travaux de bitumage 725 000 SFQC i 7 9 économique de la route de patrouille Page 10 of 12 autour de l’aéroport de Douala. - Contrôle et surveillance des travaux de bitumage économique d’une route de contournement de l’aéroport de Yaoundé 4 Audit de conformité aux normes de Posterior sécurité aérienne i (revue 14/05/201 10/08/201 575 000 ED et Audit de conformité techniqu 7 9 aux normes de sureté e de la aérienne BM) 5 Posterior Audit financier et i comptable du projet (revue 14/03/201 10/08/201 pour les exercices 150 000 SFQC techniqu 7 9 2017, 2018 et 2019 e de la BM) 6 Recrutement d'un Posterior consultant individuel i pour les prestations (revue 01/11/201 02/06/201 45 000 CI de comptable du techniqu 6 9 projet (02 ans) e de la BM) 7 Recrutement d'un Posterior consultant individuel i pour les prestations (revue 01/11/201 02/06/201 de spécialiste en 86 500 CI techniqu 6 9 passation des marchés du projet (02 e de la ans) BM) 8 Posterior Recrutement d'un i consultant individuel (revue 01/11/201 02/06/201 pour les prestations 72 000 CI techniqu 6 9 d'Auditeur Interne (02 ans) e de la BM) 9 Recrutement d'un consultant individuel Posterior pour la mise en place i 14/03/201 31/08/201 24 000 CI d'un système de 7 7 gestion du projet (02 mois) 10 Recrutement d’un consultant individuel Posterior 28/02/201 13/02/201 pour les prestations 24 000 CI i 7 9 de secrétaires du projet Page 11 of 12 11 Posterior Recrutement d’un i consultant individuel (revue 28/02/201 13/02/201 pour les prestations 72 000 CI techniqu 7 9 d’ingénieur de génie civil e de la BM) 12 Posterior Recrutement d’un i consultant individuel (revue 28/02/201 13/02/201 pour les prestations 72 000 CI techniqu 7 9 d’ingénieur de génie électrique e de la BM) 13 Recrutement d’un Posterior consultant individuel i pour les prestations (revue 28/02/201 13/02/201 96 000 CI d’expert technique en techniqu 7 9 surêté/sécurité e de la aérienne BM) 14 Recrutement d’un Posterior consultant individuel i pour les prestations (revue 28/02/201 25/08/201 76 800 CI de spécialiste techniqu 7 9 environnementaliste e de la et social senior BM) Coût total en US$ 2 568 300 - - - - Lexique des Sigles et Abréviations AOI : Appel d’Offres International AON : Appel d’Offres National CF : Consultation des Fournisseurs SFQC : Sélection Fondée sur la Qualité et le Coût SFQ : Sélection Fondée sur la Qualité QC : Sélection fondée sur les Qualifications des Consultants SMC : Sélection au Moindre Coût CI : Consultant Individuel ED : Entente directe Posteriori : Revue à posteriori Priori : Revue à priori PPM : Plan de Passation des Marchés Page 12 of 12 PROCUREMENT Cameroon : Cameroon Transport Sector Development Project PLAN General Information Country: Cameroon 2017-01-12 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P150999 GPN Date: 2016-11-01 Project Name: Cameroon Transport Sector Development Project Loan / Credit No: IBRD / 86500 CELLULE BAD/BM MINTP Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CM-CELLULE BAD/BM -11822 Road Transport Efficiency Im 1,489,766.7 2017-12-0 -CW-DIR / Travaux de déplac IBRD / 86500 Prior Direct Selection Direct 1,000,000.00 Signed 2017-04-26 2017-12-19 2017-05-01 2018-01-19 2017-06-05 2018-08-03 provement 6 2 ement des réseaux d'eau (CA MWATER) CM-CELLULE BAD/BM -11827 Road Transport Efficiency Im 2017-12-0 -CW-DIR / Travaux de déplac IBRD / 86500 Prior Direct Selection Direct 1,200,000.00 0.00 Canceled 2017-04-26 2018-02-01 2017-05-01 2017-06-05 provement 2 ement des réseaux d'électrici té (ENEO) CM-CELLULE BAD/BM -11828 -CW-DIR / Travaux de déplac Road Transport Efficiency Im 1,768,811.1 2017-12-0 IBRD / 86500 Prior Direct Selection Direct 1,000,000.00 Signed 2017-04-26 2017-12-19 2017-05-01 2018-01-19 2017-06-05 2018-07-09 ement des réseaux téléphoni provement 3 2 que et internet (CAMTEL) CM-CELLULE BAD/BM -49630 -CW-DIR / Aménagement des Road Transport Efficiency Im Request for Quota Single Stage - One E 2019-06-2 autres locaux devant abriter l IBRD / 86500 Post Open - National 70,000.00 0.00 Canceled 2018-11-05 2018-12-31 provement tions nvelope 9 a nouvelle base de données ( Gendarmerie, Police, MINT, A ssurance et ONSP) CM-CELLULE BAD/BM -21785 1-CW-RFB / REALISATION DE S INFRASTRUCTURES SOCIO- Road Transport Efficiency Im Single Stage - One E Pending Imp 2021-12-2 IBRD / 86500 Post Request for Bids Open - National 2,780,000.00 0.00 2021-03-05 2021-03-10 2021-04-21 2021-05-21 2021-06-25 ECONOMIQUES COMPLEMEN provement nvelope lementation 2 TAIRES LE LONG DE LA ROUT E BABADJOU-MATAZEM EN Q UATRE (04) LOTS Request for Bids - CM-CELLULE BAD/BM -24221 Works (without pr 6-CW-RFB / TRAVAUX DE REH Road Transport Efficiency Im Open - Internationa Single Stage - One E equalification) SP 18,269,231.0 19,174,961. 2022-05-2 ABILITATION DE LA SECTION IBRD / 86500 Prior Request for Bids Signed 2021-08-02 2021-10-04 2021-08-07 2021-09-18 2021-12-15 2021-10-18 2022-01-31 2021-11-22 2022-03-02 provement l nvelope D - Applying contr 0 84 1 DE ROUTE BABADJOU-MATAZ actor disqualificia EM DE L’AXE YAOUNDE-BAF tion OUSSAM-BAMENDA CM-CELLULE BAD/BM -24442 Request for Quota Support to Project Implemen 7-CW-RFQ / Entretien et répa Request for Quota Single Stage - One E tions - Small Work 2022-04-0 IBRD / 86500 tation Management and Mon Post Limited 3,352.00 0.00 Canceled 2021-08-09 2021-10-04 ration du bâtiment de la Cell tions nvelope s (Emergency) SP 2 itoring ule PR FC du MINTP D -Competitive CM-CELLULE BAD/BM -26851 National Procure 0-CW-DIR / Réhabilitation de ment Document - la route Babadjou-Bamenda Transport Planning and Capa 17,480,500.0 Under Imple 2022-09-2 IBRD / 86500 Prior Direct Selection Direct 1 Envelope proce 0.00 2022-02-15 2022-03-22 2022-02-20 2022-04-05 2022-03-27 de l’axe Yaoundé-Bafoussam city Building 0 mentation 3 ss (Non Bank-SPD -Bamenda : section Bamenda ) up-hill station by-pass (4,930 km) CM-CELLULE BAD/BM -26850 National Procure 6-CW-DIR / Réhabilitation de ment Document - la route Babadjou-Bamenda Transport Planning and Capa 23,750,700.0 Under Imple 2022-09-2 IBRD / 86500 Prior Direct Selection Direct 1 Envelope proce 0.00 2022-02-15 2022-03-21 2022-02-20 2022-04-05 2022-03-27 de l’axe Yaoundé-Bafoussam city Building 0 mentation 3 ss (Non Bank-SPD -Bamenda : section Mataze ) m-Welcome to Bamenda (18, 050 km) CM-CELLULE BAD/BM -5594- CW-RFB / TRAVAUX DE REHA Road Transport Efficiency Im Open - Internationa Single Stage - One E 102,500,000. 30,014,870. 2017-10-3 BILITATION DE LA ROUTE BA IBRD / 86500 Prior Request for Bids Terminated 2017-01-11 2017-01-25 2017-01-16 2017-02-27 2016-11-29 2017-03-29 2017-06-01 2017-05-03 2017-06-19 provement l nvelope 00 55 0 BADJOU-BAMENDA (52 KM) D E l'AXE YAOUNDE - BAFOUSS AM - BAMENDA. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-CELLULE BAD/BM -49603 -GO-DIR / Fourniture de l'inte rnet à la Gendarmerie (5 bas Road Transport Efficiency Im Single Stage - One E IBRD / 86500 Post Request for Bids Open - National 900,000.00 0.00 Canceled 2018-08-31 2018-09-05 2018-10-17 2018-11-16 2018-12-21 2019-06-19 es), à la Police (Yaoundé et D provement nvelope ouala), au MINT, aux CURY (Y aoundé et Douala), à l'ONSP. CM-CELLULE BAD/BM -49613 -GO-DIR / Fourniture et la pos e du matériel et équipement Road Transport Efficiency Im Single Stage - One E s informatiques dans les nou IBRD / 86500 Post Request for Bids Open - National 330,000.00 0.00 Canceled 2018-07-31 2018-08-05 2018-09-16 2018-10-16 2018-11-20 2019-05-19 provement nvelope velles bases des sonnées cré ées (4 à la Gendarmerie, une aux Assureurs et une à la Poli ce à Douala). CM-CELLULE BAD/BM -89938 -GO-RFQ / ACQUISITION DES Road Transport Efficiency Im Request for Quota Single Stage - One E IBRD / 86500 Post Limited 320,000.00 0.00 Canceled 2019-01-05 2019-03-02 2019-08-29 VEHICULES DU PROJET DE DE provement tions nvelope VELOPPEMENT DU SECTEUR DE TRANSPORT CM-CELLULE BAD/BM -10031 7-GO-RFQ / Acquisition des fo Road Transport Efficiency Im Request for Quota Single Stage - One E IBRD / 86500 Post Limited 40,000.00 0.00 Canceled 2019-03-14 2019-05-16 2021-05-05 urnitures de bureau de la Cel provement tions nvelope lule BAD-BM du Ministère des Travaux publics CM-CELLULE BAD/BM -10031 8-GO-RFQ / Acquisition des c Road Transport Efficiency Im Request for Quota Single Stage - One E onsommables informatiques IBRD / 86500 Post Limited 80,000.00 0.00 Canceled 2019-03-14 2019-05-16 2021-05-05 provement tions nvelope de la cellule BAD-BM du Minis tère des Travaux Publics Page 1 CM-CELLULE BAD/BM -14938 3-GO-RFB / FOURNITURE DE VEHICULES POUR LA POLICE Support to Project Implemen ET LA GENDARMERIE NATION Single Stage - One E Under Imple IBRD / 86500 tation Management and Mon Post Request for Bids Open - National 420,000.00 0.00 2020-01-13 2022-08-08 2020-01-18 2020-02-29 2020-03-30 2020-05-04 2020-10-31 ALE POUR LE RENFORCEMEN nvelope mentation itoring T DE LA SECURITE ROUTIERE SUR LE CORRIDOR YAOUNDE - BAFOUSSAM - BABADJOU - BAMENDA EN DEUX (02) LOT S CM-CELLULE BAD/BM -14035 Support to Project Implemen 8-GO-DIR / ACQUISITION DE Open - Internationa Single Stage - Two E IBRD / 86500 tation Management and Mon Post Request for Bids 150,000.00 0.00 Canceled 2019-10-16 2020-01-14 2019-10-21 2019-12-02 2020-02-14 2020-03-20 2020-09-16 6 RADARS DE MARQUE TRUC l nvelope itoring AM II DANS LE CADRE DU PD ST CM-CELLULE BAD/BM -18720 0-GO-RFB / ACQUISITION DE Road Transport Efficiency Im Open - Internationa Single Stage - One E Under Imple IBRD / 86500 Post Request for Bids 490,000.00 0.00 2020-08-12 2022-08-08 2020-08-17 2020-09-28 2020-10-28 2020-12-02 2021-05-31 SIX(06) RADARS POUR LA GE provement l nvelope mentation NDARMERIE NATIONALE ET L A POLICE CM-CELLULE BAD/BM -21567 3-GO-RFB / Fourniture assura nce maladie pour le personn Road Transport Efficiency Im Single Stage - One E Under Imple el de la Cellule des projets ro IBRD / 86500 Post Request for Bids Open - National 112,000.00 0.00 2021-02-09 2021-02-12 2021-02-14 2021-03-30 2021-03-28 2021-04-19 2021-04-27 2021-06-01 2021-11-28 provement nvelope mentation utiers à financement conjoint du Ministère des Travaux Pub lics ainsi que les membres de leurs familles. CM-CELLULE BAD/BM -22354 5-GO-RFQ / DEMANDE DE CO Support to Project Implemen TATION EN VUE DE LA CONC Request for Quota Single Stage - One E Under Imple IBRD / 86500 tation Management and Mon Post Limited 46,295.00 0.00 2021-03-27 2021-05-04 2021-05-22 2021-11-18 LUSION D’UN ACCORD-CADR tions nvelope mentation itoring E POUR L’ACQUISITION DES F OURNITURES DE BUREAU. CM-CELLULE BAD/BM -24030 5-GO-RFQ / FOURNITURE D'U Support to Project Implemen NE ASSURANCE AUTOMOBILE Request for Quota Single Stage - One E Pending Impl IBRD / 86500 tation Management and Mon Post Limited 3,269.00 0.00 2021-06-30 2021-08-25 2022-02-21 DU PARC DES VEHICULES DE tions nvelope ementation itoring LA CELLULE DES PROJETS RO UTIERS A FINANCEMENT CON JOINT DU MINTP CM-CELLULE BAD/BM -26150 Support to Project Implemen Request for Quota Single Stage - One E Pending Impl 4-GO-RFQ / ACHAT DE MATE IBRD / 86500 tation Management and Mon Post Limited 7,500.00 0.00 2021-11-20 2022-01-15 2022-07-14 tions nvelope ementation RIEL ET DE PRODUIT D'ENTR itoring ETIEN CM-CELLULE BAD/BM -26208 4-GO-RFQ / Fourniture et mis e en place des accessoires p Support to Project Implemen our la location d'une bande p Request for Quota Single Stage - One E Pending Impl IBRD / 86500 tation Management and Mon Post Open - National 63,000.00 0.00 2021-11-27 2022-01-22 2022-07-21 assante internet de 15Mo da tions nvelope ementation itoring ns le bâtiment de la Cellule d es Projets à Financement Co njoint du MINTP pour la pério de de Décembre 2021 à Déc embre 2023 CM-CELLULE BAD/BM -26208 6-GO-RFQ / RENOUVELLEMEN Support to Project Implemen Request for Quota Single Stage - One E Pending Impl T DU PARC INFORMATIQUE D IBRD / 86500 tation Management and Mon Post Open - National 71,000.00 0.00 2021-11-20 2022-01-15 2022-07-14 tions nvelope ementation E LA CELLULE DES PROJETS R itoring OUTIERS A FINANCEMENT CO NJOINT DU MINTP CM-CELLULE BAD/BM -26424 Support to Project Implemen Request for Quota Single Stage - One E Pending Impl 5-GO-RFQ / FOURNITURE DES IBRD / 86500 tation Management and Mon Post Limited 18,000.00 0.00 2021-11-27 2022-01-22 2022-07-21 tions nvelope ementation CONSOMMABLES INFORMATI itoring QUE CM-CELLULE BAD/BM -28298 6-GO-RFQ / FOURNITURE DES Support to Project Implemen EQUIPEMENTS DE BUREAUX Request for Quota Single Stage - One E Under Imple IBRD / 86500 tation Management and Mon Post Limited 40,000.00 0.00 2022-03-19 2022-05-14 2022-11-10 ET SALLES DE COURS POUR L tions nvelope mentation itoring A FORMATION DE MASTER E N PLANIFICATION DES TRANS PORTS AU CAMEROUN CM-CELLULE BAD/BM -28708 7-GO-RFQ / FOURNITURE DES Support to Project Implemen Request for Quota Single Stage - One E Pending Impl CONSOMMABLES INFORMATI IBRD / 86500 tation Management and Mon Post Limited 73,000.00 0.00 2022-04-05 2022-05-31 2022-11-27 tions nvelope ementation QUES A LA CELLULE DES PRO itoring JETS ROUTIERS A FINANCEME NT CONJOINT CM-CELLULE BAD/BM -28937 4-GO-RFQ / ACQUISITION D’U N VEHICULE DANS LE CADRE Support to Project Implemen DU PROJET DE FORMATION D Request for Quota Single Stage - One E Under Imple IBRD / 86500 tation Management and Mon Post Limited 65,000.00 0.00 2022-04-16 2022-06-11 2022-12-08 E NIVEAU MASTER EN PLANIF tions nvelope mentation itoring ICATION DES TRANSPORTS A L’ECOLE NATIONALE SUPERIE URE DES TRAVAUX PUBLICS DE YAOUNDE. CM-CELLULE BAD/BM -35455 Support to Project Implemen 2-GO-RFQ / Fourniture, Install Request for Quota Single Stage - One E Pending Impl IBRD / 86500 tation Management and Mon Post Open - National 67,868.85 0.00 2023-04-19 2023-05-20 2023-06-03 ation du matériel informatiqu tions nvelope ementation itoring e et accessoires de sauvegar de CM-CELLULE BAD/BM -36485 8-GO-RFQ / Sélection d’un pr Support to Project Implemen estataire pour l’acquisition d Request for Quota Single Stage - One E Under Imple IBRD / 86500 tation Management and Mon Post Open - National 76,725.92 0.00 2023-06-13 2023-06-22 2023-07-18 2024-06-20 es Fournitures de Bureau par tions nvelope mentation itoring accord cadre pour la Cellule des Projets Routiers à Financ ement Conjoint CM-CELLULE BAD/BM -36486 0-GO-RFQ / Sélection d’un pr estataire pour la Fourniture d Support to Project Implemen Request for Quota Single Stage - One E Pending Impl e Consommables bureautiqu IBRD / 86500 tation Management and Mon Post Open - National 91,890.64 0.00 2023-06-13 2023-07-18 2024-06-20 tions nvelope ementation es et informatiques par accor itoring d cadre à la cellule des projet s routiers à financement conj oint CM-CELLULE BAD/BM -36488 7-GO-RFQ / Acquisition d'un c Support to Project Implemen opieur professionnel, deux m Request for Quota Single Stage - One E Pending Impl IBRD / 86500 tation Management and Mon Post Open - National 45,333.33 0.00 2023-06-17 2023-07-22 2023-08-21 achines reliure spirale et un tions nvelope ementation itoring onduleur à la Cellule des Proj ets Routiers à Financement C onjoint NON CONSULTING SERVICES Page 2 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-CELLULE BAD/BM -10020 6-NC-RFQ / Fourniture de la c Road Transport Efficiency Im Request for Quota Single Stage - One E IBRD / 86500 Post Limited 40,000.00 50,158.37 Signed 2019-03-14 2019-06-27 2019-05-16 2019-10-02 2021-05-05 onnexion Internet à la Cellule provement tions nvelope BAD-BM du MINTP CM-CELLULE BAD/BM -20587 3-NC-RFQ / SERVICE DE REST Support to Project Implemen AURATION PENDANT LA REV Request for Quota Single Stage - One E Under Imple IBRD / 86500 tation Management and Mon Post Limited 2,540.00 0.00 2020-11-28 2021-01-23 2021-07-22 UE A MI PARCOURS DU PDST tions nvelope mentation itoring (pauses café et déjeuners Le s pauses café et déjeuners ) CM-CELLULE BAD/BM -20932 3-NC-RFQ / PARAMETRAGE D U TABLEAU EMPLOIS/RESSOU Support to Project Implemen Request for Quota Single Stage - One E Under Imple RCES DES ETATS FINANCIERS IBRD / 86500 tation Management and Mon Post Limited 2,550.00 0.00 2020-12-29 2021-02-05 2021-02-23 2021-08-22 tions nvelope mentation BASE ENGAGEMENT SUIVANT itoring LES RECOMMANDATIONS DE L’AUDIT DU PDST EXERCICE 2019 CM-CELLULE BAD/BM -22348 Support to Project Implemen Request for Quota Single Stage - One E Under Imple 4-NC-RFQ / SERVICE DE NETT IBRD / 86500 tation Management and Mon Post Limited 7,400.00 0.00 2021-03-27 2021-05-22 2021-11-18 tions nvelope mentation OYAGE DE LA CELLULE itoring CM-CELLULE BAD/BM -22348 Support to Project Implemen Request for Quota Single Stage - One E Under Imple 7-NC-RFQ / SERVIVE DE GAR IBRD / 86500 tation Management and Mon Post Limited 7,500.00 0.00 2021-03-27 2021-05-22 2021-11-18 tions nvelope mentation DIENNAGE DE LA CPR FC itoring CM-CELLULE BAD/BM -27262 1-GO-RFQ / SOUSCRIPTION D ’UNE POLICE D’ASSURANCE Support to Project Implemen Request for Quota Single Stage - One E Pending Impl MALADIE EN FAVEUR DU PER IBRD / 86500 tation Management and Mon Post Limited 73,000.00 0.00 2022-01-22 2022-03-19 2022-09-15 tions nvelope ementation SONNEL DE LA CELLULE DES itoring PROJETS ROUTIERS A FINANC EMENT CONJOINT ET DE LEU RS FAMILLES CM-CELLULE BAD/BM -36486 6-NC-RFQ / Sélection d’un pr Support to Project Implemen estataire pour la maintenanc Request for Quota Single Stage - One E Pending Impl IBRD / 86500 tation Management and Mon Post Open - National 15,833.33 0.00 2023-06-13 2023-07-18 2024-06-20 e biennale du matériel burea tions nvelope ementation itoring utique par accord cadre à la cellule des projets routiers à financement conjoint CM-CELLULE BAD/BM -36486 9-NC-RFQ / Sélection d’un pr estataire pour la maintenanc Support to Project Implemen Request for Quota Single Stage - One E Pending Impl e biennale du parc des splits IBRD / 86500 tation Management and Mon Post Open - National 11,116.67 0.00 2023-06-13 2023-07-18 2024-06-20 tions nvelope ementation et de climatiseurs, du réseau itoring électrique de la Cellule des P rojets Routiers à Financemen t Conjoint par accord cadre CM-CELLULE BAD/BM -36487 7-NC-RFQ / Sélection d’un pr Support to Project Implemen Request for Quota Single Stage - One E Pending Impl estataire pour la maintenanc IBRD / 86500 tation Management and Mon Post Open - National 91,144.30 0.00 2023-06-13 2023-07-18 2024-06-20 tions nvelope ementation e biennale des véhicules de l itoring a Cellule des Projets Routiers par accord cadre CM-CELLULE BAD/BM -36488 4-NC-RFQ / Sélection d’un pr estataire pour le gardiennag Support to Project Implemen Request for Quota Single Stage - One E Pending Impl e, la surveillance des biens e IBRD / 86500 tation Management and Mon Post Open - National 6,988.12 0.00 2023-06-13 2023-07-18 2024-06-20 tions nvelope ementation t installations et le contrôle d itoring es accès des locaux de la Cel lule des Projets Routiers à Fin ancement Conjoint par accor d cadre CM-CELLULE BAD/BM -5597- NC-RFP / SURVEILLANCE ET C ONTROLE DES TRAVAUX DE Road Transport Efficiency Im Request for Propo Open - Internationa Single Stage - Two E IBRD / 86500 Prior 5,900,000.00 4,055,343.74 Signed 2017-01-11 2017-01-25 2017-03-29 2017-04-27 2017-03-29 2017-06-01 2017-01-16 2017-06-07 2016-10-18 2017-08-20 2017-09-15 2017-09-24 2017-05-13 2019-03-18 REHABILITATION DE LA ROUT provement sals l nvelope E BABADJOU-BAMENDA (52 K M) de l'AXE YAOUNDE - BAFO USSAM - BAMENDA. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-CELLULE BAD/BM -89936 -CS-CQS / EVALUATION SOCI Road Transport Efficiency Im Consultant Qualifi IBRD / 86500 Post Open - National 46,494.00 36,930.80 Completed 2018-12-31 2018-12-27 2019-01-21 2019-03-06 2019-03-25 2019-04-05 2019-05-08 2019-05-10 2020-07-02 2019-11-06 2020-07-15 ALE DU PROJET DE REHABILI provement cation Selection TATION DE LA ROUTE BABAD JOU BAMENDA CM-CELLULE BAD/BM -89939 -CS-CQS / ETUDE D'IMPACT E NVIRONNEMENTAL ET SOCIA Road Transport Efficiency Im Consultant Qualifi IBRD / 86500 Post Open - National 60,000.00 0.00 Canceled 2018-12-31 2019-01-21 2019-03-06 2019-04-05 2019-05-10 2019-11-06 L DES INFRASTRUCTURES CO provement cation Selection MPLEMENTAIRES DU PROJET DE REHABILITATION DE LA R OUTE BABADJOU BAMENDA CM-CELLULE BAD/BM -10031 3-CS-CQS / Selection de cons Road Transport Efficiency Im Consultant Qualifi ultants pour l'estimation des IBRD / 86500 Post Open - National 40,000.00 0.00 Canceled 2019-02-28 2018-12-21 2019-03-21 2019-11-18 2019-05-04 2019-08-09 2019-06-03 2019-07-08 2020-01-04 provement cation Selection coûts socio-économiques des accidents sur les routes au C ameroun CM-CELLULE BAD/BM -14041 Transport Planning and Capa Quality And Cost- Open - Internationa 8-CS-QCBS / RECRUTEMENT IBRD / 86500 Prior 700,000.00 0.00 Canceled 2019-10-15 2019-11-15 2019-11-05 2019-11-22 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2021-04-25 city Building Based Selection l AUDITEUR TECHNIQUE CM-CELLULE BAD/BM -14079 3-CS-QCBS / RECRUTEMENT Support to Project Implemen D'UN CONSULTANT POUR LA Quality And Cost- Open - Internationa Under Implement IBRD / 86500 tation Management and Mon Prior 1,000,000.00 0.00 2019-10-16 2019-11-15 2019-11-06 2020-01-09 2019-12-20 2021-02-01 2020-01-17 2021-03-23 2020-02-16 2021-09-14 2020-03-22 2022-08-31 2020-04-26 2021-04-26 L’ÉVALUATION ENVIRONNEM Based Selection l ation itoring ENTALE ET SOCIALE STRATE GIQUE DU SECTEUR DES TRA NSPORTS AU CAMEROUN Page 3 CM-CELLULE BAD/BM -14079 7-CS-CQS / RECRUTEMENT D' Support to Project Implemen UN CONSULTANT POUR LA R Consultant Qualifi Open - Internationa Under Implement IBRD / 86500 tation Management and Mon Post 150,000.00 0.00 2019-10-16 2019-08-08 2019-11-06 2019-11-15 2019-12-20 2020-01-19 2020-02-23 2020-08-21 EALISATION DE L'AUDIT DU C cation Selection l ation itoring ONTRAT-PLAN ETAT/MATGEN IE ET L'ETUDE DE LA VIABILIT E CM-CELLULE BAD/BM -14080 0-CS-CQS / RECRUTEMENT D' Support to Project Implemen Consultant Qualifi Open - Internationa UN CONSULTANT POUR LA R IBRD / 86500 tation Management and Mon Post 200,000.00 127,024.03 Signed 2019-10-16 2019-08-14 2019-11-06 2019-11-15 2019-12-20 2020-04-03 2020-01-19 2020-07-17 2020-02-23 2021-03-10 2020-08-21 cation Selection l EALISATION DE L'ETUDE DIA itoring GNOSTIQUE DU PORT AUTON OME DE DOUALA CM-CELLULE BAD/BM -14989 5-CS-QCBS / Recrutement d'u n consultant en vue d’élabor Road Transport Efficiency Im Quality And Cost- Open - Internationa er la stratégie nationale d’ad IBRD / 86500 Prior 1,000,000.00 0.00 Canceled 2019-12-11 2020-03-23 2020-01-01 2020-03-23 2020-02-14 2020-11-10 2020-03-13 2021-01-21 2020-04-12 2021-04-27 2020-05-17 2020-06-21 2021-06-21 provement Based Selection l aptation et de résilience des i nfrastructures de transport a ux effets des changements cl imatiques CM-CELLULE BAD/BM -17089 4-CS-CQS / recrutement d’un e ONG chargée du suivi, de l’ opérationnalisation du méca Road Transport Efficiency Im Consultant Qualifi Under Implement IBRD / 86500 Post Open - National 158,000.00 0.00 2020-04-27 2020-07-23 2020-05-18 2020-07-01 2020-08-19 2020-07-31 2021-04-14 2020-09-04 2021-03-03 nisme de prévention et de ge provement cation Selection ation stion des plaintes, de la cond uite des campagnes de sensi bilisation et de communicatio n sociale et du suivi des activ ités d CM-CELLULE BAD/BM -73922 -CS-CQS / Recrutement d'une Road Transport Efficiency Im Consultant Qualifi IBRD / 86500 Post Open - National 300,000.00 0.00 Canceled 2018-09-12 2018-10-03 2018-11-16 2018-12-16 2019-01-20 2019-07-19 ONG pour Mécanisme de Ges provement cation Selection tion des Plaintes CM-CELLULE BAD/BM -18484 1-CS-CQS / Définition d'une s Road Transport Efficiency Im Consultant Qualifi Under Implement IBRD / 86500 Post Open - National 57,000.00 0.00 2020-07-20 2020-08-27 2020-08-10 2020-09-23 2020-10-23 2020-11-27 2021-05-26 tratégie de communication s provement cation Selection ation ur la sécurité routière au Ca meroun CM-CELLULE BAD/BM -18484 2-CS-CQS / Formation aux pr Road Transport Efficiency Im Consultant Qualifi Under Implement IBRD / 86500 Post Open - National 72,500.00 0.00 2020-07-20 2020-07-22 2020-08-10 2020-09-23 2020-10-23 2020-11-27 2021-05-26 emiers sécours des riverains provement cation Selection ation de l'axe routier Yaoundé-Baf oussam-Bamenda CM-CELLULE BAD/BM -20121 6-CS-QCBS / PLAN D’ACTION PRIORITAIRE POUR LA NORM ALISATION DU TRANSPORT R Road Transport Efficiency Im Quality And Cost- Open - Internationa IBRD / 86500 Prior 829,500.00 0.00 Canceled 2020-10-30 2020-11-20 2021-01-03 2021-01-31 2021-03-02 2021-04-06 2021-05-11 2022-05-11 OUTIER ET DE LA SECURITE R provement Based Selection l OUTIERE : PHASE I : REVISIO N, ELABORATION ET ADOPTI ON DES NORMES CAMEROUN AISES RELATIVES A LA SECU RITE ROUTIERE CM-CELLULE BAD/BM -20930 0-CS-QCBS / RECRUTEMENT D’UNE FIRME POUR LA REVISI Road Transport Efficiency Im Quality And Cost- Open - Internationa Under Implement IBRD / 86500 Post 699,000.00 0.00 2020-12-24 2021-02-02 2021-01-14 2021-05-05 2021-02-27 2021-08-09 2021-03-27 2023-01-12 2021-04-26 2023-02-22 2021-05-31 2021-07-05 2022-07-05 ON, L’ELABORATION ET L’AD provement Based Selection l ation OPTION DES NORMES CAMER OUNAISES DANS LE SECTEUR DE LA SECURITE ROUTIERE. CM-CELLULE BAD/BM -73921 -CS-QCBS / Maitrise d'œuvre complète pour l'amélioration Road Transport Efficiency Im Quality And Cost- Open - Internationa IBRD / 86500 Prior 1,200,000.00 0.00 Canceled 2018-09-28 2018-10-19 2018-12-02 2018-12-30 2019-01-29 2019-03-05 2019-04-09 2020-04-08 de 50 km de routes secondai provement Based Selection l res existantes, 25 hangars et la construction de 10 adducti ons d'eau CM-CELLULE BAD/BM -21787 6-CS-QCBS / MAITRISE D’ŒU VRE DES TRAVAUX DE CONS Road Transport Efficiency Im Quality And Cost- Under Implement TRUCTION DES INFRASTRUCT IBRD / 86500 Post Open - National 556,000.00 0.00 2021-02-25 2021-03-01 2021-03-18 2021-05-01 2021-05-29 2021-06-28 2021-08-02 2021-09-06 2022-09-06 provement Based Selection ation URES SOCIO-ECONOMIQUES COMPLEMENTAIRES LE LONG DE LA ROUTE BABADJOU-MA TAZEM EN QUATRE LOTS CM-CELLULE BAD/BM -23664 4-CS-CQS / recrutement d’un e firme chargée de la réalisat ion de l’audit foncier et d’occ Road Transport Efficiency Im Consultant Qualifi Under Implement IBRD / 86500 Post Open - National 93,000.00 0.00 2021-05-28 2021-06-18 2021-06-18 2021-08-01 2021-08-31 2021-10-05 2022-04-03 upation des emprises de la tr provement cation Selection ation aversée urbaine de la ville de Bamenda (12km) dans le cad re du projet de réhabilitation de la route Babadjou - Bame nda CM-CELLULE BAD/BM -23919 0-CS-QCBS / Recrutement d’ un Consultant chargé de réali Road Transport Efficiency Im Quality And Cost- Open - Internationa Under Implement IBRD / 86500 Post 370,000.00 0.00 2021-06-25 2021-06-11 2021-07-16 2021-08-29 2023-01-04 2021-09-26 2023-02-24 2021-10-26 2023-05-15 2021-11-30 2022-01-04 2023-01-04 ser l’étude de faisabilité pou provement Based Selection l ation r la création d’une agence de régulation des transports terr estres CM-CELLULE BAD/BM -24442 6-CS-QCBS / Slélection d’un Consultant en vue d’élaborer Transport Planning and Capa Quality And Cost- Open - Internationa Under Implement la stratégie nationale d’adapt IBRD / 86500 Post 952,000.00 0.00 2021-08-04 2021-09-07 2021-08-25 2021-10-04 2021-10-08 2021-11-05 2021-12-05 2022-01-09 2022-02-13 2023-02-13 city Building Based Selection l ation ation et de résilience des infr astructures de transport aux effets des changements clim atiques CM-CELLULE BAD/BM -28256 4-CS-QCBS / RECRUTEMENT Support to Project Implemen Quality And Cost- Open - Internationa Under Implement D'UN CONSULTANT POUR L’E IBRD / 86500 tation Management and Mon Post 275,000.00 0.00 2022-03-07 2022-03-17 2022-03-28 2022-05-30 2022-05-11 2023-02-09 2022-06-08 2023-04-20 2022-07-08 2023-05-02 2022-08-12 2023-05-30 2022-09-16 2023-09-16 Based Selection l ation TUDE TECHNIQUE DE LA TRA itoring VERSEE URBAINE DE BAMEN DA 11,99 km CM-CELLULE BAD/BM -30273 8-CS-CQS / Conduite de l’Etu de d’Impact Environnemental et Social Détaillée (EIES-D) d e la route Mora – Dabanga – Road Transport Efficiency Im Consultant Qualifi Under Implement IBRD / 86500 Post Open - National 240,000.00 0.00 2022-07-13 2022-07-26 2022-08-03 2022-09-19 2022-09-16 2022-10-16 2022-11-20 2023-05-19 Kousseri pour le PROJET D’A provement cation Selection ation MELIORATION POUR LA CON NECTIVITE, LA RESILIENCE ET L’INCLUSION (PACRI) LE LON G DU CORRIDOR ROUTIER M ORA-DABANGA-KOUSSERI Page 4 CM-CELLULE BAD/BM -30625 7-CS-QCBS / Recrutement d'u ne firme pour l'enquête visan t à établir la situation de réfé Air Transport Safety and Sec Quality And Cost- Open - Internationa Under Implement IBRD / 86500 Post 460,000.00 0.00 2022-07-27 2022-08-08 2022-08-17 2022-09-21 2022-09-30 2023-06-05 2022-10-28 2022-11-27 2023-01-01 2023-02-05 2024-02-05 rence sur la sécurité routière urity Improvement Based Selection l ation en terme de port de ceinture de sécurité, conduite en état d'ivresse, excès de vitesse et port de casques CM-CELLULE BAD/BM -32681 7-CS-QCBS / RECRUTEMENT D’UN CONSULTANT POUR L’ Transport Planning and Capa Quality And Cost- Open - Internationa Under Implement IBRD / 86500 Post 390,000.00 0.00 2022-12-15 2023-02-16 2023-01-05 2023-02-18 2023-03-18 2023-04-17 2023-05-22 2023-06-26 2024-06-25 ELABORATION DE LA STRATE city Building Based Selection l ation GIE LOGISTIQUE NATIONALE DU CAMEROUN ET D’UN PLA N D’ACTION POUR 2025-203 5 CM-CELLULE BAD/BM -32681 6-CS-QCBS / RECRUTEMENT D’UN CONSULTANT POUR LE Support to Project Implemen Quality And Cost- Open - Internationa DEVELOPPEMENT D’UN SYST IBRD / 86500 tation Management and Mon Prior 1,500,000.00 0.00 Under Review 2022-12-02 2023-02-24 2022-12-23 2023-02-05 2023-03-05 2023-04-04 2023-05-09 2023-06-13 2024-06-12 Based Selection l EME DE COLLECTE ET D’ANA itoring LYSE DES DONNEES DES ACC IDENTS DE CIRCULATION AU CAMEROUN CM-CELLULE BAD/BM -34808 9-CS-CQS / Etude d’Impact E Road Transport Efficiency Im Consultant Qualifi Under Implement IBRD / 86500 Post Open - National 80,000.00 0.00 2023-03-09 2023-03-13 2023-03-14 2023-04-27 2023-05-27 2023-07-10 2023-09-08 nvironnemental et Social des provement cation Selection ation travaux de la traversée urbai ne de Bamenda CM-CELLULE BAD/BM -36208 4-CS-CQS / Diagnostic et éval Support to Project Implemen Consultant Qualifi Under Implement uation du réseau, installation IBRD / 86500 tation Management and Mon Post Open - National 6,725.00 0.00 2023-05-22 2023-05-27 2023-06-12 2023-07-10 2023-07-17 2023-08-14 2024-02-10 cation Selection ation et paramétrage du logiciel T itoring OM2PRO sur des nouveaux p ostes de travail INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-CELLULE BAD/BM -11810 -CS-INDV / RECRUTEMENT D' Road Transport Efficiency Im Individual Consult IBRD / 86500 Post Open 120,000.00 0.00 Canceled 2017-04-05 2017-07-20 2017-05-24 2017-06-14 2017-07-19 2019-07-09 UN CONSULTANT INDIVIDUEL provement ant Selection EN SECURITE ROUTIERE CM-CELLULE BAD/BM -34159 Support to Project Implemen -CS-INDV / Recrutement d'un Individual Consult IBRD / 86500 tation Management and Mon Post Open 76,800.00 50,570.11 Signed 2017-10-26 2017-08-29 2017-12-14 2018-03-12 2018-01-04 2018-03-22 2018-02-08 2018-12-31 2018-08-07 2020-11-06 Consultant Individuel pour le ant Selection itoring s prestations de Spécialiste e nvironnementaliste. CM-CELLULE BAD/BM -49634 -CS-CDS / Opérationalisation et pérenisation des bases de Road Transport Efficiency Im IBRD / 86500 Prior Direct Selection Direct 1,000,000.00 0.00 Canceled 2018-09-12 2018-09-22 2018-11-26 2019-05-25 s données des accidents de l provement a circulation et d'un système d'information de la sécurité r outière au Cameroun. CM-CELLULE BAD/BM -34162 -CS-INDV / Recrutement d'un Support to Project Implemen Consultant Individuel pour le Individual Consult IBRD / 86500 tation Management and Mon Post Open 76,800.00 46,712.38 Signed 2019-01-31 2019-02-12 2019-04-30 2019-07-01 2019-05-31 2019-07-04 2019-07-21 2019-10-09 2021-07-10 s prestations de Spécialiste S ant Selection itoring ocial à la Cellule BAD-BM du Ministère des Travaux Public s CM-CELLULE BAD/BM -14027 Support to Project Implemen Individual Consult 1-CS-INDV / SÉLECTION D'UN IBRD / 86500 tation Management and Mon Post Open 120,000.00 81,775.46 Signed 2019-10-14 2019-08-13 2019-12-02 2019-12-30 2019-12-23 2020-01-02 2020-01-27 2020-05-12 2020-07-25 ant Selection CONSULTANT EN SUIVI-EVAL itoring UATION CM-CELLULE BAD/BM -14039 2-CS-INDV / RECRUTEMENT D 'UN CONSULTANT INDIVIDUE Road Transport Efficiency Im Individual Consult IBRD / 86500 Post Limited 58,556.00 40,719.27 Signed 2019-10-22 2019-09-04 2019-10-27 2019-08-19 2019-11-17 2019-11-19 2019-12-22 2019-12-31 2020-06-19 L EN CHARGE DE L'APPUI A L' provement ant Selection ORGANISATION DU FORUM N ATIONAL DE LA SÉCURITÉ RO UTIÈRE CM-CELLULE BAD/BM -14042 Support to Project Implemen 2-CS-INDV / RECRUTEMENT A Individual Consult IBRD / 86500 tation Management and Mon Post Open 72,000.00 68,300.17 Signed 2019-10-18 2019-08-08 2019-12-06 2020-05-12 2019-12-27 2020-05-14 2020-01-31 2020-05-15 2020-07-29 UDITEUR INTERNE A LA CELL ant Selection itoring ULE BAD/BM DU MINTP CM-CELLULE BAD/BM -14058 3-CS-INDV / RECRUTEMENT D Support to Project Implemen Individual Consult 'UN CONSULTANT POUR LA R IBRD / 86500 tation Management and Mon Post Open 28,000.00 24,083.28 Signed 2019-10-15 2019-09-02 2019-12-03 2020-01-28 2019-12-24 2019-11-20 2020-01-28 2020-05-12 2020-07-26 ant Selection ÉALISATION DE L'AUDIT HYGI itoring ÈNE SÉCURITÉ ENVIRONNEM ENTAL CM-CELLULE BAD/BM -14042 3-CS-INDV / RECRUTEMENT D Support to Project Implemen Individual Consult 'UN SPECIALISTE EN PASSATI IBRD / 86500 tation Management and Mon Post Open 120,000.00 0.00 Canceled 2019-10-15 2019-08-14 2019-12-03 2019-12-24 2020-01-28 2020-07-26 ant Selection ON DES MARCHES A LA CELL itoring ULE BAD/BM DU MINTP CM-CELLULE BAD/BM -16212 8-CS-INDV / Recrutement d'u Support to Project Implemen Individual Consult n Consultant Individuel, expe IBRD / 86500 tation Management and Mon Prior Limited 240,000.00 199,616.40 Signed 2020-02-28 2020-03-17 2020-03-04 2019-08-26 2020-03-25 2020-03-17 2020-04-29 2020-04-22 2020-10-26 ant Selection rt en contentieux à la Cellule itoring BAD-BM du Ministère des Tra vaux Publics CM-CELLULE BAD/BM -10021 0-CS-INDV / Recrutement d'u Road Transport Efficiency Im Individual Consult n Consultant Individuel, expe IBRD / 86500 Post Limited 100,000.00 0.00 Canceled 2019-02-28 2019-08-08 2019-03-14 2019-08-26 2019-04-04 2019-05-09 2021-04-28 provement ant Selection rt en contentieux à la Cellule BAD-BM du Ministère des Tra vaux Publics CM-CELLULE BAD/BM -16489 3-CS-INDV / SELECTION D'UN Support to Project Implemen CONSULTANT POUR LES PRE Individual Consult IBRD / 86500 tation Management and Mon Post Direct 36,000.00 28,172.64 Signed 2020-03-17 2021-01-12 2020-03-27 2020-02-24 2020-04-17 2020-03-02 2020-05-22 2020-04-22 2020-11-18 STATIONS DE SPECIALISTE E ant Selection itoring N VIOLENCES BASEES SUR LE GENRE A LA CELLULE BAD-B M CM-CELLULE BAD/BM -16707 Support to Project Implemen Individual Consult IBRD / 86500 Post Limited 26,000.00 27,602.28 Signed 2020-04-27 2020-04-27 2020-05-02 2020-02-24 2020-05-23 2020-03-02 2020-06-27 2020-04-22 2020-12-24 2-GO-RFQ / Recrutement exp tation Management and Mon ant Selection ert VBG itoring Page 5 CM-CELLULE BAD/BM -17252 Road Transport Efficiency Im 3-CS-CDS / OPÉRATIONNALIS IBRD / 86500 Post Direct Selection Direct 141,000.00 274,990.20 Signed 2020-05-07 2020-05-13 2020-05-17 2020-07-24 2020-07-21 2020-12-05 2021-01-17 provement ATION DU THIRD PARTY MON YTORING CM-CELLULE BAD/BM -17018 5-CS-INDV / RECRUTEMENT D 'UN AUDITEUR TECHNIQUE P Road Transport Efficiency Im Individual Consult IBRD / 86500 Post Open 82,000.00 0.00 Canceled 2020-04-23 2020-06-11 2020-07-02 2020-08-06 2021-02-02 OUR LES TRAVAUX DE REHA provement ant Selection BILITATION DES ROUTES MA ROUA-MORA ET BABADJOU-B AMENDA CM-CELLULE BAD/BM -17724 6-CS-CDS / RENOUVELLEMEN Support to Project Implemen T DU CONTRAT DE L'AGENT IBRD / 86500 tation Management and Mon Post Direct Selection Direct 8,700.00 9,643.82 Signed 2020-06-18 2020-06-18 2020-06-28 2020-09-28 2020-09-01 2021-01-21 2021-02-28 DE LIAISON DE LA CELLULE D itoring ES PROJETS ROUTIERS A FINA NCEMENT CONJOINT CM-CELLULE BAD/BM -17724 9-CS-CDS / RENOUVELLEMEN Support to Project Implemen T DU CONTRAT DU COMPTAB IBRD / 86500 tation Management and Mon Post Direct Selection Direct 54,000.00 65,701.01 Signed 2020-06-18 2020-06-18 2020-06-28 2020-09-28 2020-09-01 2021-01-21 2021-02-28 LE N°2 DE LA CELLULE DES P itoring ROJETS A FINANCEMENT CON JOINT CM-CELLULE BAD/BM -17724 7-CS-CDS / RENOUVELLEMEN Support to Project Implemen T DU CONTRAT DU COMPTAB IBRD / 86500 tation Management and Mon Post Direct Selection Direct 45,000.00 59,986.66 Signed 2020-06-18 2020-06-18 2020-06-28 2020-09-28 2020-09-01 2021-01-21 2021-02-28 LE N°1 DE LA CELLULE DES P itoring ROJETS ROUTIERS A FINANCE MENT CONJOINT CM-CELLULE BAD/BM -18893 3-CS-CDS / Conception et mis Transport Planning and Capa IBRD / 86500 Prior Direct Selection Direct 1,636,000.00 1,351,602.57 Signed 2020-09-21 2020-10-07 2020-10-01 2020-12-01 2020-12-05 2021-06-25 2021-06-03 e en œuvre d’un Master en Pl city Building anification des Transports au Cameroun CM-CELLULE BAD/BM -23460 7-CS-INDV / Développement Road Transport Efficiency Im Individual Consult de la Stratégie Logistique Na IBRD / 86500 Post Open 86,000.00 0.00 Canceled 2021-05-31 2021-07-19 2021-08-09 2021-09-13 2022-03-12 provement ant Selection tionale du Cameroun et d’un Plan d’Action pour 2020-203 5 CM-CELLULE BAD/BM -23460 6-CS-INDV / recrutement d’u n Consultant individuel charg é de l’évaluation rapide de la Road Transport Efficiency Im Individual Consult Under Implement mise en œuvre du processus IBRD / 86500 Post Limited 7,740.00 0.00 2021-05-28 2021-05-27 2021-06-02 2021-06-23 2021-07-28 2022-01-24 provement ant Selection ation de libération des emprises su r les sections Babadjou-Welc ome to Bamenda et voie de Contournement de la falaise de Bamenda CM-CELLULE BAD/BM -27268 0-CS-INDV / LE RECRUTEMEN T D'UN CONSULTANT INDIVID Support to Project Implemen Individual Consult UEL SPECIALISTE EN PASSATI IBRD / 86500 tation Management and Mon Post Open 110,000.00 0.00 Canceled 2022-01-13 2022-01-17 2022-03-03 2022-03-24 2022-04-28 2022-10-25 ant Selection ON DES MARCHES A LA CELL itoring ULE DES PROJETS ROUTIERS A FINANCEMENT CONJOINT D U MINISTERE DES TRAVAUX P UBLICS CM-CELLULE BAD/BM -27267 8-CS-INDV / RECRUTEMENT D 'UN CONSULTANT INDIVIDUE Support to Project Implemen Individual Consult L RESPONSABLE ADMINISTRA IBRD / 86500 tation Management and Mon Post Open 110,000.00 0.00 Canceled 2022-01-13 2022-01-17 2022-03-03 2022-03-24 2022-04-28 2022-10-25 ant Selection TIF ET FINANCIER A LA CELL itoring ULE DES PROJETS ROUTIERS A FINANCEMENT CONJOINT D U MINISTERE DES TRAVAUX P UBLICS CM-CELLULE BAD/BM -18484 0-CS-CDS / Enquête visant à établir la situation de référen Road Transport Efficiency Im ce sur la sécurité routière en IBRD / 86500 Post Direct Selection Direct 500,824.00 0.00 Canceled 2020-09-21 2020-10-07 2020-10-01 2020-12-08 2020-12-05 2021-06-03 provement termes de port de ceinture d e sécurité, conduite en état d 'ivresse, excès de vitesse et port du casque. CM-CELLULE BAD/BM -30273 7-CS-CDS / Elaboration des in struments de sauvegardes e nvironnementales et sociales (CPR, CGES, PGRS, PGMO, PM Road Transport Efficiency Im Under Implement IBRD / 86500 Post Direct Selection Direct - National 200,000.00 0.00 2022-07-26 2022-08-08 2022-08-05 2022-10-09 2023-04-07 PP, PEES) pour le PROJET D’ provement ation AMELIORATION POUR LA CO NNECTIVITE, LA RESILIENCE ET L’INCLUSION (PACRI) LE L ONG DU CORRIDOR ROUTIER MORA-DABANGA-KOUSSERI CM-CELLULE BAD/BM -30273 9-CS-CDS / Actualisation des études techniques y compris Road Transport Efficiency Im Under Implement la vulnérabilité de la route M IBRD / 86500 Post Direct Selection Direct - National 500,000.00 0.00 2022-07-26 2022-08-08 2022-08-05 2022-09-13 2022-10-09 2023-04-07 provement ation aroua – Mora – Dabanga – Ko usseri aux effets des change ments climatiques pour le Pr ojet PACRI CM-CELLULE BAD/BM -23229 4-CS-INDV / DEVELOPPEMEN Transport Planning and Capa Individual Consult T DE LA STRATEGIE LOGISTIQ IBRD / 86500 Post Open 86,000.00 0.00 Canceled 2021-05-14 2021-05-26 2021-07-02 2021-07-23 2021-08-27 2022-02-23 city Building ant Selection UE NATIONALE DU CAMEROU N ET D’UN PLAN D’ACTION P OUR 2020-2035 CM-CELLULE BAD/BM -34180 1-CS-CDS / Collecte des donn Road Transport Efficiency Im Pending Impleme ées complémentaires pour la IBRD / 86500 Post Direct Selection Direct - National 30,590.00 0.00 2023-02-09 2023-02-09 2023-02-10 2023-02-15 provement ntation finalisation des instruments d e sauvegarde (PGMO, PMPP, CGES, PGRS, CPR) CM-CELLULE BAD/BM -35188 Road Transport Efficiency Im Under Implement 5-CS-CDS / Mise en œuvre de IBRD / 86500 Post Direct Selection Direct - National 324,618.50 0.00 2023-04-28 2023-05-23 2023-05-08 2023-06-05 2023-06-19 2024-07-13 provement ation Third Party Monitoring (TPG) CM-CELLULE BAD/BM -35187 4-CS-CDS / Opérationnalisati on du mécanisme de prévent ion et de gestion des plaintes Road Transport Efficiency Im Under Implement IBRD / 86500 Post Direct Selection Direct - National 828,400.00 0.00 2023-04-28 2023-05-23 2023-05-08 2023-06-05 2023-06-05 2024-06-23 , de la conduite des campagn provement ation es de sensibilisation et de co mmunication sociale, de suivi des activités de violences ba sées sur le genre Page 6 Integrated Habitat and Housing Project (P159929) Argentina, IBRD/IDA Team Leader(s): Catherine Lynch, John Morton , PROCUREMENT Argentina : Integrated Habitat and Housing Project PLAN General Information Country: Argentina 2018-01-29 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P159929 GPN Date: 2018-04-26 Project Name: Integrated Habitat and Housing Project Loan / Credit No: IBRD / 87120 Ministry of Territorial Development and Habitat Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned AR-MININTERIOR-123537-C Integrated Habitat Improve Single Stage - One E 1,977,975.9 2020-12-0 W-RFB / Programa de Mejora IBRD / 87120 Post Request for Bids Open - National 4,402,758.25 Signed 2019-08-19 2019-08-15 2019-08-24 2019-10-05 2019-12-06 2019-11-04 2020-10-16 2019-12-09 2021-02-10 ment nvelope 0 3 miento Barrial Villa El Liberta dor, Córdoba AR-MININTERIOR-130302-C Integrated Habitat Improve Single Stage - One E 5,181,516.7 2021-12-3 W-RFB / Proyecto Integral La IBRD / 87120 Post Request for Bids Open - National 8,568,105.87 Signed 2019-09-20 2019-09-26 2019-09-25 2019-11-06 2019-10-31 2019-12-06 2020-09-01 2020-01-10 2020-10-30 ment nvelope 7 0 Favorita – 5° Etapa, Prov. Me ndoza AR-MININTERIOR-145719-C W-RFB / Proyecto de Mejora miento Barrial. Barrio Villa Ba nana, Rosario - Sector 2, entr Integrated Habitat Improve Single Stage - One E 3,418,753.8 2022-02-1 IBRD / 87120 Post Request for Bids Open - National 4,393,724.00 Signed 2020-11-02 2021-03-16 2020-11-07 2020-12-19 2021-06-02 2021-01-18 2021-07-27 2021-02-22 2021-12-07 e las calles Servando Bayo, G ment nvelope 7 7 alvez , Avellaneda y Virasoro / Sector 3, entre las calles Se rvando Bayo, Virasoro, Avella neda y Rueda AR-MININTERIOR-145718-C W-RFB / Proyecto de Mejora Integrated Habitat Improve Single Stage - One E 1,811,497.8 2022-07-1 IBRD / 87120 Post Request for Bids Open - National 2,909,217.26 Signed 2020-10-01 2020-09-23 2020-10-06 2020-11-17 2020-11-25 2020-12-17 2021-03-17 2021-01-21 2021-06-02 miento Barrial. Barrio Villa Ba ment nvelope 0 5 nana, Rosario - Sector 1 AR-MININTERIOR-207070-C W-RFB / Construcción de “Inf raestructura Básica de Servic Integrated Habitat Improve Single Stage - One E 2,394,457.6 2022-07-0 IBRD / 87120 Post Request for Bids Open - National 1,837,630.00 Signed 2021-03-04 2021-01-04 2021-03-05 2021-04-05 2021-04-21 2021-05-20 2021-08-10 2021-06-19 2021-12-01 ios, Equipamiento Urbano y ment nvelope 4 5 Obras de Mitigación Ambiental. EL TRO PEZÓN”, Córdoba AR-MININTERIOR-142823-C Integrated Habitat Improve Single Stage - One E 2,332,469.9 2022-07-0 W-RFB / Proyecto B° Congres IBRD / 87120 Post Request for Bids Open - National 4,092,715.70 Signed 2021-02-26 2021-02-05 2021-03-31 2021-04-30 2021-05-17 2021-05-30 2021-07-27 2021-07-04 2021-11-30 ment nvelope 5 4 o y Progreso ETAPA II - Mend oza AR-MININTERIOR-218983-C W-RFB / “Construcción de Inf raestructura Pública, Equipa Integrated Habitat Improve Single Stage - One E 1,906,910.0 2022-07-1 IBRD / 87120 Post Request for Bids Open - National 1,835,444.00 Signed 2021-03-24 2021-03-25 2021-03-29 2021-04-28 2021-05-17 2021-06-12 2021-07-28 2021-07-17 2021-12-02 miento Urbano y ment nvelope 9 7 Comunitario – Barrio Flores y Olivares – Etapa 2” ciudad d e Mendoza, Provincia de Men doza AR-MININTERIOR-225693-C Integrated Habitat Improve Single Stage - One E 2,053,639.0 2022-07-0 IBRD / 87120 Post Request for Bids Open - National 2,394,114.00 Signed 2021-03-26 2021-03-12 2021-03-31 2021-04-30 2021-05-17 2021-06-14 2021-07-28 2021-07-14 2021-11-20 W-RFB / PERDRIEL NORTE ET ment nvelope 8 9 APA 1 AR-MININTERIOR-223172-C W-RFB / Obras de infraestruc Integrated Habitat Improve Single Stage - One E 3,350,941.6 2022-07-2 tura, saneamiento y espacio IBRD / 87120 Post Request for Bids Open - National 3,400,897.00 Signed 2021-03-19 2021-03-20 2021-04-01 2021-05-01 2021-05-26 2021-06-15 2021-09-10 2021-07-13 2021-10-14 ment nvelope 6 9 público en el sector Noroeste de la Ciudad de Santa Fe. AR-MININTERIOR-202142-C Integrated Habitat Improve Single Stage - One E 5,634,397.3 2022-06-1 W-RFB / Proyecto Rumy-Lom IBRD / 87120 Post Request for Bids Open - National 3,466,463.00 Signed 2021-01-18 2021-01-04 2021-03-05 2021-04-05 2021-04-05 2021-05-20 2021-06-28 2021-06-19 2021-12-01 ment nvelope 2 4 a de la Cruz, La Calera Córdo ba National Procure AR-MININTERIOR-201160-C ment Document - W-RFB / Proyecto Confluenci Integrated Habitat Improve Single Stage - One E 4,450,150.0 2022-10-2 IBRD / 87120 Post Request for Bids Open - National 1 Envelope proce 4,540,759.64 Signed 2021-02-25 2021-05-21 2021-04-22 2021-05-22 2021-07-26 2021-06-21 2021-10-04 2021-07-31 2021-11-20 a Lote Z1-Neuquén - Etapa 1: ment nvelope 9 4 ss (Non Bank-SPD Red cloacal y completamient ) o red de gas National Procure AR-MININTERIOR-201346-C ment Document - Integrated Habitat Improve Single Stage - One E 2,088,241.9 2022-11-0 W-RFB / Proyecto Confluenci IBRD / 87120 Post Request for Bids Open - National 1 Envelope proce 2,296,896.91 Signed 2021-02-23 2021-03-31 2021-04-22 2021-05-22 2021-05-12 2021-07-06 2021-10-01 2021-07-28 2021-11-20 ment nvelope 7 5 a. Toma la Familia-Neuquén ss (Non Bank-SPD ) AR-MININTERIOR-142607-C Integrated Habitat Improve Single Stage - One E 2022-06-2 W-RFB / Proyecto integral As IBRD / 87120 Post Request for Bids Open - National 1,365,563.00 0.00 Canceled 2020-11-09 2021-03-29 2020-11-16 2020-12-16 2021-02-14 2021-03-31 ment nvelope 4 entamiento Papa Francisco - Catamarca National Procure AR-MDTH-237083-CW-RFB / ment Document - Proyecto Integral Asentamien Integrated Habitat Improve Single Stage - One E 1,596,104.9 2022-11-2 IBRD / 87120 Post Request for Bids Open - National 1 Envelope proce 1,257,560.00 Signed 2021-06-03 2021-07-08 2021-06-08 2021-06-29 2021-09-14 2021-07-29 2021-09-14 2021-08-31 2021-12-11 to Papa Francisco - Catamarc ment nvelope 8 4 ss (Non Bank-SPD a (Segundo Llamado) ) National Procure AR-MININTERIOR-202138-C Integrated Habitat Improve Single Stage - One E ment Document - 5,696,856.3 2022-12-2 W-RFB / Proyecto Argüello- C IBRD / 87120 Post Request for Bids Open - National 5,599,055.00 Signed 2021-02-26 2021-01-04 2021-03-08 2021-03-25 2021-03-25 2021-05-09 2021-07-01 2021-06-08 2021-12-01 ment nvelope 1 Envelope proce 3 1 órdoba ss (Non Bank-SPD ) National Procure AR-MININTERIOR-146775-C Integrated Habitat Improve Single Stage - One E ment Document - Under Imple 2023-01-2 IBRD / 87120 Post Request for Bids Open - National 1,924,335.08 0.00 2021-03-31 2021-08-12 2021-10-12 2021-11-04 2021-11-04 2021-11-04 2022-03-10 2022-01-05 W-RFB / Proyecto La Chola ment nvelope 1 Envelope proce mentation 1 ss (Non Bank-SPD ) National Procure AR-MDTH-244869-CW-RFB / ment Document - Integrated Habitat Improve Single Stage - One E Under Imple 2023-05-3 Proyecto Integral de Hábitat IBRD / 87120 Post Request for Bids Open - National 1 Envelope proce 2,560,772.14 0.00 2021-12-15 2021-12-31 2022-03-04 2022-03-25 2022-03-31 2022-04-15 2022-08-09 2022-05-15 ment nvelope mentation 1 Villa Evita 1° etapa. ss (Non Bank-SPD ) National Procure AR-MDTH-334774-CW-RFB / ment Document - Integrated Habitat Improve Single Stage - One E Pending Imp 2024-11-3 Proyecto Integral Asentamien IBRD / 87120 Post Request for Bids Open - National 1 Envelope proce 1,465,600.00 0.00 2023-05-24 2023-06-14 2023-07-18 2023-09-15 2023-11-03 ment nvelope lementation 0 to Papa Francisco Etapa II ss (Non Bank-SPD ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 AR-MDTH-327945-GO-RFB / Single Stage - One E Pending Impl Adquisición de Equipamiento IBRD / 87120 Institutional Strengthening Post Request for Bids Open - National 1,870,000.00 0.00 2023-05-15 2023-05-20 2023-06-19 2023-08-02 2023-09-06 2023-12-05 nvelope ementation Informático, Multimedia, Soft ware y Licencias NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-MININTERIOR-116118-NC Request for Quota Single Stage - One E IBRD / 87120 Institutional Strengthening Post Limited 2,130.00 1,455.53 Signed 2019-05-27 2019-05-24 2019-06-03 2019-05-31 2019-06-13 -RFQ / Foro de Vivienda Sust tions nvelope entable AR-MININTERIOR-125960-NC -RFQ / Provisión de servicio d Request for Quota Single Stage - One E IBRD / 87120 Institutional Strengthening Post Limited 600.00 1,345.89 Signed 2019-08-02 2019-08-02 2019-08-06 2019-08-07 2019-08-11 e catering. Capacitación Mejo tions nvelope r Hogar Sustentable AR-MININTERIOR-135200-NC -RFQ / Servicio de cobertura Request for Quota Single Stage - One E audiovisual - Capacitación Si IBRD / 87120 Institutional Strengthening Post Limited 1,300.00 740.65 Signed 2019-09-26 2019-09-30 2019-10-03 2019-10-10 2019-10-10 tions nvelope stema Solar Térmico en Propi edad Horizontal y Beneficios Fiscales AR-MININTERIOR-142274-NC Request for Quota Single Stage - One E -RFQ / Capacitación Sello de IBRD / 87120 Institutional Strengthening Post Limited 1,800.00 679.57 Signed 2019-10-25 2019-10-25 2019-10-29 2019-11-07 2019-11-03 tions nvelope Vivienda Sustentable AR-MININTERIOR-146762-NC -RFQ / Contratación servicio Request for Quota Single Stage - One E IBRD / 87120 Institutional Strengthening Post Limited 2,500.00 1,633.44 Signed 2019-11-23 2019-11-07 2019-11-27 2019-11-15 2019-12-02 de catering - Sello Vivienda tions nvelope Sustentable Mendoza AR-MININTERIOR-140568-NC Request for Quota Single Stage - One E -RFQ / Impresión de publicaci IBRD / 87120 Institutional Strengthening Post Limited 5,900.00 0.00 Canceled 2019-10-26 2019-11-02 2019-11-09 tions nvelope ones Secretaría de Vivienda AR-MDTH-343425-NC-RFQ / Contratación de un servicio i ntegral de eventos para la re Request for Quota Single Stage - One E Under Imple alización de la “MINURVI 202 IBRD / 87120 Institutional Strengthening Post Open - National 93,800.00 0.00 2023-03-07 2023-03-31 2023-04-11 tions nvelope mentation 3 - Reunión Ministerial: Finan ciamiento para la mitigación del cambio climático en los a sentamientos urbanos. AR-MDTH-364713-NC-RFQ / Request for Quota Single Stage - One E Pending Impl Contratación de Servicio de I IBRD / 87120 Institutional Strengthening Post Limited 8,500.00 0.00 2023-06-03 2023-07-03 2023-12-31 tions nvelope ementation nterpretación de Conferencia s CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-UEC-60404-CS-QCBS / Fo Quality And Cost- Open - Internationa rmulación Proyectos Ejecutiv IBRD / 87120 Institutional Strengthening Prior 5,600,000.00 244,188.38 Signed 2018-04-30 2018-05-15 2018-05-01 2018-06-28 2018-12-06 2018-07-26 2019-01-25 2018-08-25 2019-02-26 2018-09-29 2019-03-29 2018-11-03 2019-04-17 2020-11-02 Based Selection l os Integrales AR-UEC-40792-CS-QCBS / Se Quality And Cost- rvicio de Consultoría para el IBRD / 87120 Institutional Strengthening Post Open - National 360,000.00 224,659.55 Signed 2018-05-15 2018-05-30 2018-06-05 2018-07-19 2019-01-15 2018-08-16 2019-02-15 2018-10-15 2019-04-17 2018-11-19 2019-05-08 2018-12-24 2019-06-24 2019-09-20 Based Selection Apoyo a la Implementación d el SIGEBE AR-UEC-58982-CS-CQS / Ser Consultant Qualifi vicio de Consultoría para Faci IBRD / 87120 Institutional Strengthening Post Open - National 20,800.00 0.00 Canceled 2018-04-25 2018-04-03 2018-05-16 2018-08-14 2018-08-29 2018-10-13 2020-10-12 cation Selection litación de Mesa de Diálogo AR-MININTERIOR-103445-CS -CQS / Capacitación a Técnic Quality And Cost- os Diagnosticadores y Susten IBRD / 87120 Institutional Strengthening Post Open - National 100,500.00 0.00 Canceled 2019-03-07 2019-03-01 2019-03-28 2019-05-11 2019-06-08 2019-07-08 2019-08-12 2019-09-16 2020-09-15 Based Selection tabilizadores del Plan Nacion al de Sustentabilización de Vi viendas AR-MININTERIOR-103429-CS Quality And Cost- -CQS / Capacitación de Técni IBRD / 87120 Institutional Strengthening Post Open - National 150,000.00 0.00 Canceled 2019-03-07 2019-03-01 2019-03-28 2019-05-11 2019-06-08 2019-07-08 2019-08-12 2019-09-16 2020-09-15 Based Selection cos y funcionarios en Gestión de Suelo AR-MININTERIOR-116378-CS -QCBS / Evaluación del Progr Quality And Cost- IBRD / 87120 Institutional Strengthening Post Open - National 125,000.00 0.00 Canceled 2019-05-30 2019-06-20 2019-08-03 2019-08-31 2019-09-30 2019-11-04 2019-12-09 2020-12-03 ama Mejor Hogar Gas - Secre Based Selection taría de Vivienda AR-MININTERIOR-103434-CS Quality And Cost- -QCBS / Formulación de Proy IBRD / 87120 Institutional Strengthening Post Open - National 350,000.00 0.00 Canceled 2019-03-11 2019-03-01 2019-04-01 2019-05-15 2019-06-12 2019-07-12 2019-08-25 2019-09-29 2021-09-18 Based Selection ectos Ejecutivos de Desarroll o Urbano AR-MININTERIOR-103499-CS -CQS / Evaluación de Resulta Quality And Cost- IBRD / 87120 Institutional Strengthening Post Open - National 156,500.00 0.00 Canceled 2019-03-07 2019-03-01 2019-03-28 2019-05-11 2019-10-15 2019-06-08 2019-11-22 2019-07-08 2019-08-12 2019-09-16 2020-09-15 dos en Hogares Beneficiarios Based Selection de Proyectos de Vivienda Soc ial INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-UEC-40795-CS-INDV / Co nsultor para Proyectos PPP- Individual Consult IBRD / 87120 Institutional Strengthening Post Limited 40,500.00 14,311.74 Terminated 2018-05-02 2018-04-11 2018-05-03 2018-04-13 2018-05-07 2018-04-25 2018-05-15 2018-05-01 2019-05-15 Especialista para Evaluación ant Selection Socio- Económico AR-UEC-60577-CS-INDV / Co Individual Consult IBRD / 87120 Institutional Strengthening Post Limited 17,223.40 29,023.38 Signed 2018-04-25 2018-02-19 2018-04-26 2018-02-21 2018-04-27 2018-03-28 2018-05-02 2018-04-01 2018-12-31 nsultor Especialista Ambienta ant Selection l AR-UEC-60581-CS-INDV / Co Individual Consult Pending Impleme IBRD / 87120 Institutional Strengthening Post Limited 12,100.60 0.00 2018-04-25 2018-04-26 2018-04-27 2018-05-02 2018-12-31 nsultor Especialista Obra ant Selection ntation Page 2 AR-UEC-60585-CS-INDV / Co Individual Consult Pending Impleme IBRD / 87120 Institutional Strengthening Post Limited 27,112.15 0.00 2018-04-25 2018-04-26 2018-04-27 2018-05-02 2018-12-31 nsultor Especialista Contable ant Selection ntation AR-UEC-60602-CS-INDV / Co Individual Consult Pending Impleme IBRD / 87120 Institutional Strengthening Post Limited 12,100.60 0.00 2018-04-25 2018-04-26 2018-04-27 2018-05-02 2018-12-31 nsultor Especialista Evaluació ant Selection ntation n AR-UEC-40794-CS-INDV / Co Individual Consult IBRD / 87120 Institutional Strengthening Post Limited 23,000.00 33,732.61 Terminated 2018-02-09 2018-01-23 2018-02-10 2018-01-25 2018-02-14 2018-02-26 2018-03-01 2018-03-01 2018-12-31 nsultor para el CAT ant Selection AR-UEC-40796-CS-INDV / Co Individual Consult Pending Impleme IBRD / 87120 Institutional Strengthening Post Limited 23,000.00 0.00 2018-02-09 2018-02-10 2018-02-14 2018-03-01 2018-12-31 nsultor Especialista Ambienta ant Selection ntation l AR-UEC-60614-CS-CDS / Eva luación Integral de Programa IBRD / 87120 Institutional Strengthening Post Direct Selection Direct 270,000.00 196,166.21 Signed 2018-05-02 2018-04-09 2018-05-14 2018-07-12 2018-07-12 2018-11-16 2019-04-08 de la Secretaria de Vivienda AR-UEC-44113-CS-INDV / Co Individual Consult nsultor para la Ley Nacional IBRD / 87120 Institutional Strengthening Post Limited 20,000.00 0.00 Canceled 2018-01-19 2018-02-09 2018-02-16 2018-03-01 2018-10-31 ant Selection de Vivienda - Arquitecto Urba nista Senior AR-UEC-44112-CS-INDV / Co nsultor para la Ley Nacional Individual Consult IBRD / 87120 Institutional Strengthening Post Limited 20,000.00 0.00 Canceled 2018-01-19 2018-02-09 2018-02-16 2018-03-01 2018-10-31 de Vivienda - Abogado de De ant Selection recho Urbanístico Senior AR-UEC-60620-CS-INDV / Co Individual Consult Under Implement nsultor para Proyectos PPP- E IBRD / 87120 Institutional Strengthening Post Limited 37,125.00 0.00 2018-06-01 2018-04-06 2018-06-02 2018-06-06 2018-06-15 2019-05-11 ant Selection ation specialista para Evaluación fi nanciera AR-UEC-44114-CS-INDV / Es Integrated Habitat Improve Individual Consult IBRD / 87120 Post Limited 23,000.00 45,819.21 Signed 2018-05-15 2018-01-23 2018-05-20 2018-01-25 2018-05-23 2018-02-26 2018-05-28 2018-03-01 2019-04-23 pecialista en Ingeniería Hidrá ment ant Selection ulica AR-UEC-44800-CS-CDS / Con sultoría para la Construcción IBRD / 87120 Institutional Strengthening Post Direct Selection Direct 100,000.00 100,000.00 Signed 2018-04-27 2018-04-03 2018-05-06 2018-07-13 2018-06-26 2019-02-07 2018-12-23 del Índice Multidimensional d el Hábitat AR-UEC-66562-CS-CDS / Ser vicio de Consultaría para Faci IBRD / 87120 Institutional Strengthening Post Direct Selection Direct 20,800.00 14,672.00 Signed 2018-06-18 2018-04-09 2018-06-28 2018-07-12 2018-09-01 2018-12-17 2019-02-28 litación de Mesa de Diálogo AR-UEC-67616-CS-INDV / Re sponsable Técnico estructura Individual Consult IBRD / 87120 Institutional Strengthening Post Limited 50,000.00 37,932.41 Signed 2018-06-21 2018-07-03 2018-06-25 2018-07-04 2018-06-26 2018-07-05 2018-07-02 2018-07-10 2018-12-31 ción de proyectos con Partici ant Selection pación Público Privada AR-UEC-67617-CS-INDV / Es pecialista Legal para la elabo Individual Consult IBRD / 87120 Institutional Strengthening Post Limited 47,000.00 24,190.22 Completed 2018-06-22 2018-07-03 2018-06-25 2018-07-04 2018-06-26 2018-07-05 2018-07-02 2018-07-10 2018-12-31 2019-12-31 ración, implementación y seg ant Selection uimiento de la Ley Nacional d e Vivienda AR-UEC-67618-CS-INDV / Es Individual Consult IBRD / 87120 Institutional Strengthening Post Limited 47,000.00 36,415.49 Completed 2018-06-22 2018-07-03 2018-06-25 2018-07-04 2018-06-26 2018-07-04 2018-07-02 2018-07-10 2018-12-31 2019-12-31 pecialista en Comunicación I ant Selection nstitucional AR-UEC-67619-CS-INDV / Re Individual Consult sponsable Técnico Compone IBRD / 87120 Institutional Strengthening Post Limited 38,000.00 31,787.33 Signed 2018-06-22 2018-07-03 2018-06-26 2018-07-04 2018-06-27 2018-07-05 2018-07-02 2018-07-10 2018-12-31 ant Selection ntes 1 y 3 del Préstamo BIRF 8712-AR AR-UEC-67620-CS-INDV / Es Individual Consult pecialista en marketing digit IBRD / 87120 Institutional Strengthening Post Limited 36,000.00 10,135.54 Terminated 2018-06-22 2018-07-03 2018-06-25 2018-07-04 2018-06-26 2018-07-05 2018-07-02 2018-07-09 2018-12-31 ant Selection al y comunicación AR-UEC-67621-CS-INDV / Re Individual Consult sponsable de Seguimiento y IBRD / 87120 Institutional Strengthening Post Limited 31,000.00 7,845.02 Completed 2018-06-22 2018-07-03 2018-06-25 2018-07-04 2018-06-26 2018-07-05 2018-07-02 2018-08-01 2018-12-31 2018-12-31 ant Selection Control de Proyectos de Vivie nda Social AR-UEC-69404-CS-INDV / An Individual Consult IBRD / 87120 Project Management Post Limited 82,363.69 31,785.28 Signed 2018-07-12 2018-07-09 2018-07-13 2018-07-10 2018-07-14 2018-07-12 2018-07-16 2018-07-16 2021-12-31 alista de Planificación de Pro ant Selection gramas AR-UEC-69406-CS-INDV / Asi Individual Consult stente en Gestión y Administ IBRD / 87120 Project Management Post Limited 58,459.89 25,868.82 Signed 2018-07-12 2018-07-09 2018-07-13 2018-07-10 2018-07-14 2018-07-12 2018-07-16 2018-07-16 2021-12-31 ant Selection ración de Recursos Humanos AR-UEC-69415-CS-INDV / Au Individual Consult IBRD / 87120 Project Management Post Open 51,590.50 11,073.86 Signed 2018-07-12 2018-07-09 2018-07-13 2018-07-10 2018-07-14 2018-07-12 2018-07-16 2018-07-16 2021-12-31 xiliar Administrativo ant Selection AR-UEC-69429-CS-INDV / Asi Individual Consult IBRD / 87120 Project Management Post Open 55,282.21 8,042.01 Terminated 2018-07-12 2018-07-09 2018-07-13 2018-07-10 2018-07-14 2018-07-12 2018-07-16 2018-07-16 2021-12-31 stente Administrativo ant Selection AR-UEC-69431-CS-INDV / Es Individual Consult pecialista en Formulación y E IBRD / 87120 Project Management Post Limited 82,777.89 28,556.23 Signed 2018-07-12 2018-07-09 2018-07-13 2018-07-10 2018-07-14 2018-07-12 2018-07-16 2018-07-16 2021-12-31 ant Selection jecución de Proyectos AR-UEC-69436-CS-INDV / Es pecialista en métodos cuali/c Individual Consult IBRD / 87120 Project Management Post Limited 71,483.00 27,852.11 Signed 2018-07-17 2018-07-21 2018-07-23 2018-07-22 2018-08-01 2018-08-01 2021-12-31 uantitativos de monitorio y e ant Selection valuación del proyectos AR-UEC-69442-CS-INDV / An Individual Consult alista de Planificación y Monit IBRD / 87120 Project Management Post Limited 68,928.00 35,298.72 Terminated 2018-07-17 2018-07-09 2018-07-21 2018-07-10 2018-07-22 2018-07-11 2018-08-01 2018-07-16 2021-12-31 ant Selection oreo de contratos AR-UEC-69448-CS-INDV / Au Integrated Habitat Improve Individual Consult Pending Impleme IBRD / 87120 Post Limited 14,375.00 0.00 2018-07-17 2018-07-23 2018-07-25 2018-08-01 2019-12-31 xiliar Social ment ant Selection ntation AR-UEC-69428-CS-INDV / Co Individual Consult nsultor de Apoyo en Adquisic IBRD / 87120 Project Management Post Limited 72,759.43 29,967.99 Signed 2018-07-12 2018-07-09 2018-07-13 2018-07-10 2018-07-14 2018-07-11 2018-07-16 2018-07-16 2021-12-31 ant Selection iones. Normativa Nacional AR-UEC-69677-CS-INDV / Au Individual Consult xiliar Contable. Consultor de IBRD / 87120 Project Management Post Limited 14,923.00 4,056.29 Terminated 2018-07-17 2018-07-23 2018-07-23 2018-07-25 2018-07-25 2018-08-01 2018-08-01 2019-12-31 ant Selection Apoyo - Normativa Nacional AR-UEC-69427-CS-INDV / Co Individual Consult nsultor de Apoyo en Adquisic IBRD / 87120 Project Management Post Limited 88,460.89 31,510.70 Signed 2018-07-12 2018-07-09 2018-07-13 2018-07-10 2018-07-14 2018-07-11 2018-07-16 2018-07-16 2021-12-31 ant Selection iones. Normativa Nacional Page 3 AR-UEC-71736-CS-CDS / Inc orporación de la perspectiva Integrated Habitat Improve de género en la planificación IBRD / 87120 Post Direct Selection Direct 68,000.00 73,740.00 Signed 2018-07-26 2018-04-09 2018-08-03 2018-08-02 2018-08-18 2018-08-31 2019-02-14 ment urbana y el diseño de espaci os públicos en comunidades vulnerables en Argentina AR-UEC-76004-CS-INDV / Au Individual Consult IBRD / 87120 Institutional Strengthening Post Direct 41,300.00 15,846.77 Signed 2018-12-06 2018-12-09 2018-12-11 2018-12-15 2018-09-01 2021-12-31 xiliar en Comunicación ant Selection AR-UEC-76011-CS-INDV / Au Individual Consult IBRD / 87120 Institutional Strengthening Post Direct 32,400.00 14,160.82 Signed 2018-12-06 2018-12-09 2018-12-11 2018-12-15 2018-12-15 2021-12-31 xiliar Administrativo ant Selection AR-UEC-76013-CS-INDV / Au Individual Consult IBRD / 87120 Institutional Strengthening Post Direct 36,200.00 17,095.19 Signed 2018-12-06 2018-12-09 2018-12-11 2018-12-15 2018-09-01 2021-12-31 xiliar Administrativo ant Selection AR-UEC-76023-CS-INDV / Au Individual Consult IBRD / 87120 Institutional Strengthening Post Direct 38,900.00 18,652.94 Signed 2018-12-06 2018-12-10 2018-09-01 2018-12-12 2018-09-01 2018-12-15 2018-12-15 2021-12-31 xiliar Legal ant Selection AR-UEC-86872-CS-CDS / Con sultoría para la Identificación de los Usos del Suelo Formal IBRD / 87120 Institutional Strengthening Post Direct Selection Direct 18,852.46 30,491.93 Signed 2018-12-17 2018-09-17 2018-12-30 2019-01-10 2019-02-22 2019-08-26 2019-04-23 e Informal en los Principales Áreas Urbanas de Argentina mediante Imágenes Satelital es AR-UEC-75983-CS-INDV / An Individual Consult IBRD / 87120 Project Management Post Direct 61,900.00 26,045.06 Signed 2018-12-17 2018-12-19 2018-12-20 2018-12-22 2018-08-01 2022-01-07 alista en Planificación de Pro ant Selection gramas AR-UEC-69444-CS-INDV / Es Individual Consult IBRD / 87120 Project Management Post Limited 82,020.00 0.00 Canceled 2018-07-17 2018-07-21 2018-07-23 2018-07-22 2018-08-01 2021-12-31 pecialista Legal ant Selection AR-MININTERIOR-105964-CS -CDS / Servicio de consultoría IBRD / 87120 Institutional Strengthening Post Direct Selection Direct 50,000.00 34,786.12 Signed 2019-04-01 2019-03-19 2019-04-10 2019-05-14 2019-05-31 2019-08-09 2019-09-28 para el Asesoramiento en Dis eño de Programas de Alquiler Social AR-MININTERIOR-107017-CS -CDS / Identificación de Mejor IBRD / 87120 Institutional Strengthening Post Direct Selection Direct 80,000.00 50,855.92 Signed 2019-04-05 2019-03-20 2019-04-14 2019-04-11 2019-06-07 2019-05-16 2019-11-04 es Prácticas - SIU AR-MININTERIOR-110911-CS Individual Consult -INDV / Responsable de Segu IBRD / 87120 Institutional Strengthening Post Limited 15,000.00 17,463.21 Signed 2019-04-17 2019-04-15 2019-04-22 2019-03-07 2019-04-27 2019-03-20 2019-05-01 2019-05-02 2019-12-31 ant Selection imiento de cartera de proyec tos de Vivienda AR-MININTERIOR-123534-CS Individual Consult Pending Impleme -INDV / Refuerzo Administrati IBRD / 87120 Institutional Strengthening Post Limited 12,500.00 0.00 2019-07-24 2019-07-29 2019-07-30 2019-08-01 2021-01-22 ant Selection ntation vo UEM Cordoba AR-MININTERIOR-123538-CS Integrated Habitat Improve Individual Consult -INDV / Promotores Ambienta IBRD / 87120 Post Limited 25,000.00 0.00 Under Review 2019-07-24 2021-03-16 2019-07-27 2019-07-29 2019-08-01 2021-01-22 ment ant Selection les - Córdoba AR-MININTERIOR-123541-CS Integrated Habitat Improve Individual Consult IBRD / 87120 Post Limited 25,000.00 0.00 Under Review 2019-07-24 2021-03-16 2019-07-27 2019-07-29 2019-08-01 2021-01-22 -INDV / Inspectores de Obra - ment ant Selection Córdoba AR-MININTERIOR-123543-CS Integrated Habitat Improve Individual Consult IBRD / 87120 Post Limited 25,000.00 0.00 Under Review 2019-07-24 2021-03-17 2019-07-27 2019-07-29 2019-08-01 2021-01-22 -INDV / Promotores Sociales - ment ant Selection Córdoba AR-MININTERIOR-123544-CS Integrated Habitat Improve Individual Consult IBRD / 87120 Post Limited 12,500.00 0.00 Under Review 2019-07-24 2021-03-17 2019-07-27 2019-07-29 2019-08-01 2021-01-22 -INDV / Promotor Urbano - Có ment ant Selection rdoba AR-MININTERIOR-130310-CS Integrated Habitat Improve Individual Consult IBRD / 87120 Post Limited 12,500.00 0.00 Under Review 2019-09-17 2020-12-10 2019-09-20 2019-09-25 2019-10-01 2021-09-20 -INDV / Inspector de Obra - U ment ant Selection EM Mendoza AR-MININTERIOR-130311-CS Integrated Habitat Improve Individual Consult -INDV / Promotor ambiental - IBRD / 87120 Post Limited 12,500.00 0.00 Under Review 2019-09-17 2020-12-10 2019-09-20 2019-09-25 2019-10-01 2021-09-20 ment ant Selection UEM Mendoza AR-MININTERIOR-142827-CS Integrated Habitat Improve Individual Consult Pending Impleme IBRD / 87120 Post Open 12,500.00 0.00 2020-03-02 2020-04-20 2020-05-11 2020-06-15 2020-12-12 -INDV / Promotor urbano UEP ment ant Selection ntation - Mendoza AR-MININTERIOR-146780-CS Integrated Habitat Improve Individual Consult Pending Impleme -INDV / Promotor Urbano UE IBRD / 87120 Post Open 12,000.00 0.00 2020-03-02 2020-04-20 2020-05-11 2020-06-15 2020-12-12 ment ant Selection ntation P - Corrientes AR-MININTERIOR-142825-CS Integrated Habitat Improve Individual Consult Pending Impleme -INDV / Promotor ambiental U IBRD / 87120 Post Open 12,500.00 0.00 2020-03-02 2020-04-20 2020-05-11 2020-06-15 2020-12-12 ment ant Selection ntation EP - Mendoza AR-MININTERIOR-142829-CS Integrated Habitat Improve Individual Consult Pending Impleme IBRD / 87120 Post Open 12,500.00 0.00 2020-03-02 2020-04-20 2020-05-11 2020-06-15 2020-12-12 -INDV / Promotor Legal UEP - ment ant Selection ntation Mendoza AR-MININTERIOR-142833-CS Integrated Habitat Improve Individual Consult Pending Impleme IBRD / 87120 Post Open 12,500.00 0.00 2020-03-02 2020-04-20 2020-05-11 2020-06-15 2020-12-12 -INDV / Promotor Social UEP - ment ant Selection ntation Mendoza AR-MININTERIOR-142610-CS Integrated Habitat Improve Individual Consult Pending Impleme IBRD / 87120 Post Open 12,500.00 0.00 2020-03-02 2020-04-20 2020-05-11 2020-06-15 2020-12-12 -INDV / Promotor social UEP - ment ant Selection ntation Catamarca AR-MININTERIOR-142609-CS Integrated Habitat Improve Individual Consult Pending Impleme -INDV / Promotor ambiental U IBRD / 87120 Post Open 12,500.00 0.00 2020-03-02 2020-04-20 2020-05-11 2020-06-15 2020-12-12 ment ant Selection ntation EP - Catamarca AR-MININTERIOR-142608-CS Integrated Habitat Improve Individual Consult Pending Impleme -INDV / Inspector de Obra UE IBRD / 87120 Post Open 12,500.00 0.00 2020-03-02 2020-04-20 2020-05-11 2020-06-15 2020-12-12 ment ant Selection ntation P - Catamarca AR-MININTERIOR-142611-CS Integrated Habitat Improve Individual Consult Under Implement IBRD / 87120 Post Open 12,500.00 0.00 2020-03-02 2021-03-29 2020-04-20 2020-05-11 2020-06-15 2020-12-12 -INDV / Promotor legal UEP - ment ant Selection ation Catamarca AR-MININTERIOR-142612-CS Integrated Habitat Improve Individual Consult Pending Impleme -INDV / Promotor Urbano UEP IBRD / 87120 Post Open 12,500.00 0.00 2020-03-02 2020-04-20 2020-05-11 2020-06-15 2020-12-12 ment ant Selection ntation - Catamarca AR-MININTERIOR-146778-CS Integrated Habitat Improve Individual Consult Pending Impleme IBRD / 87120 Post Open 12,000.00 0.00 2020-03-02 2020-04-20 2020-05-11 2020-06-15 2020-12-12 -INDV / Promotor Social UEP ment ant Selection ntation - Corrientes Page 4 AR-MININTERIOR-146781-CS Integrated Habitat Improve Individual Consult Pending Impleme -INDV / Inspector de Obra UE IBRD / 87120 Post Open 12,000.00 0.00 2020-03-02 2020-04-20 2020-05-11 2020-06-15 2020-12-12 ment ant Selection ntation P - Corrientes AR-MININTERIOR-146777-CS Integrated Habitat Improve Individual Consult Pending Impleme IBRD / 87120 Post Open 12,000.00 0.00 2020-03-02 2020-04-20 2020-05-11 2020-06-15 2020-12-12 -INDV / Promotor Legal UEP - ment ant Selection ntation Corrientes AR-MININTERIOR-146776-CS Integrated Habitat Improve Individual Consult Pending Impleme -INDV / Promotor Ambiental IBRD / 87120 Post Open 12,000.00 0.00 2020-03-02 2020-04-20 2020-05-11 2020-06-15 2020-12-12 ment ant Selection ntation UEP - Corrientes AR-MDTH-255575-CS-INDV / Integrated Habitat Improve Individual Consult Pending Impleme Promotor Urbano - UEM Cord IBRD / 87120 Post Limited 2,856.66 0.00 2021-12-15 2021-12-20 2022-01-10 2022-02-14 2022-07-14 ment ant Selection ntation oba, B° Villa Libertador AR-MDTH-260660-CS-INDV / Integrated Habitat Improve Individual Consult Inspector de Obra - Mendoza IBRD / 87120 Post Limited 11,313.13 0.00 Under Review 2021-12-29 2022-04-04 2022-01-03 2022-01-24 2022-02-28 2023-06-23 ment ant Selection - Perdriel Norte Lujan de Cuy o. AR-MDTH-268225-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Urbano- UEM Córd IBRD / 87120 Post Limited 2,856.65 0.00 Under Review 2021-12-29 2021-08-02 2022-01-03 2022-01-24 2022-02-28 2022-07-28 ment ant Selection oba Villa El Libertador AR-MININTERIOR-130313-CS Integrated Habitat Improve Individual Consult -INDV / Inspector de Obras Lo IBRD / 87120 Post Limited 12,500.00 0.00 Under Review 2019-09-17 2020-12-10 2019-09-20 2019-09-25 2019-10-01 2021-09-20 ment ant Selection te 5 - UEM Mendoza La favori ta AR-MDTH-266029-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Ambiental - Mendo IBRD / 87120 Post Limited 11,313.13 0.00 Under Review 2021-12-29 2021-12-13 2022-01-03 2022-01-24 2022-02-28 2023-06-23 ment ant Selection za- Perdriel Norte Lujan de cu yo AR-MININTERIOR-130314-CS Integrated Habitat Improve Individual Consult -INDV / Promotor Ambiental L IBRD / 87120 Post Limited 12,500.00 0.00 Under Review 2019-09-17 2020-12-10 2019-09-20 2019-09-25 2019-10-01 2021-09-20 ment ant Selection ote 5 - UEM Mendoza La Favo rita AR-MDTH-255997-CS-INDV / Integrated Habitat Improve Individual Consult Under Implement Promotor Urbano- UEP Corrie IBRD / 87120 Post Limited 14,322.25 0.00 2021-12-29 2021-12-01 2022-01-03 2022-01-24 2022-02-28 2023-10-21 ment ant Selection ation ntes, B° La Chola AR-MDTH-255597-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Social - UEP Catam IBRD / 87120 Post Limited 17,546.00 0.00 Under Review 2021-12-29 2021-04-12 2022-01-03 2022-01-24 2022-02-07 2024-01-28 ment ant Selection arca, B° Papa Francisco AR-MDTH-255598-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Ambiental - UEP Ca IBRD / 87120 Post Limited 17,546.00 0.00 Under Review 2021-12-29 2021-04-12 2022-01-03 2022-01-24 2022-02-07 2024-01-28 ment ant Selection tamarca, B° Papa Francisco AR-MDTH-255616-CS-INDV / Integrated Habitat Improve Individual Consult Inspector de Obra - UEP Neu IBRD / 87120 Post Limited 15,670.00 0.00 Under Review 2021-12-29 2021-08-27 2022-01-03 2022-01-24 2022-02-07 2023-10-30 ment ant Selection quén, B° Belgrano, Sector La Familia AR-MDTH-255606-CS-INDV / Integrated Habitat Improve Individual Consult IBRD / 87120 Post Limited 27,423.00 0.00 Under Review 2021-12-29 2021-08-27 2022-01-03 2022-01-24 2022-02-07 2023-10-30 Promotor Social - UEP Neuqu ment ant Selection én AR-MDTH-256004-CS-INDV / Integrated Habitat Improve Individual Consult Inspector de Obra- UEP Corri IBRD / 87120 Post Limited 14,322.25 0.00 Under Review 2021-12-29 2022-06-29 2022-01-03 2022-01-24 2022-02-28 2023-10-21 ment ant Selection entes, B° La Chola AR-MDTH-260659-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Urbano - Mendoza - IBRD / 87120 Post Limited 11,313.13 0.00 Under Review 2021-12-29 2021-12-13 2022-01-03 2022-01-24 2022-02-28 2023-06-23 ment ant Selection Congreso y Progreso. AR-MDTH-260669-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Social - Mendoza - IBRD / 87120 Post Limited 11,313.13 0.00 Under Review 2021-12-29 2021-12-13 2022-01-03 2022-01-24 2022-02-28 2023-06-23 ment ant Selection Perdriel Norte Lujan de Cuyo. AR-MDTH-260673-CS-INDV / Integrated Habitat Improve Individual Consult Pending Impleme Promotor Ambiental - Mendo IBRD / 87120 Post Limited 11,313.13 0.00 2021-12-29 2022-01-03 2022-01-24 2022-02-28 2023-06-23 ment ant Selection ntation za - Lujan Cuyo. AR-MDTH-255956-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Ambiental-UEP Corr IBRD / 87120 Post Limited 14,322.25 0.00 Under Review 2021-12-29 2022-06-01 2022-01-03 2022-01-24 2022-02-28 2023-10-21 ment ant Selection ientes, B° La Chola AR-MDTH-260674-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Legal - Mendoza - IBRD / 87120 Post Limited 11,313.13 0.00 Under Review 2021-12-29 2021-12-13 2022-01-03 2022-01-24 2022-02-28 2023-06-23 ment ant Selection Perdriel Norte Lujan de Cuyo. AR-MDTH-260675-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Urbano - Mendoza - IBRD / 87120 Post Limited 11,313.13 0.00 Under Review 2021-12-29 2021-12-13 2022-01-03 2022-01-24 2022-02-28 2023-06-23 ment ant Selection Perdriel Norte Lujan de Cuyo . AR-MDTH-260645-CS-INDV / Integrated Habitat Improve Individual Consult Inspector de obra - Mendoza IBRD / 87120 Post Limited 11,313.13 0.00 Under Review 2021-12-29 2021-12-13 2022-01-03 2022-01-24 2022-02-28 2023-06-23 ment ant Selection - Flores y Olivares. AR-MDTH-260646-CS-INDV / Integrated Habitat Improve Individual Consult Under Implement Inspector de obra - Mendoza IBRD / 87120 Post Limited 11,313.13 0.00 2021-12-29 2021-12-01 2022-01-03 2022-01-24 2022-02-28 2023-06-23 ment ant Selection ation - Flores y Olivares. AR-MDTH-260647-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Social - Mendoza - IBRD / 87120 Post Limited 11,313.13 0.00 Under Review 2021-12-29 2022-04-01 2022-01-03 2022-01-24 2022-02-28 2023-06-23 ment ant Selection Flores y Olivares. AR-MDTH-260651-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Urbano - Mendoza - IBRD / 87120 Post Limited 11,313.13 0.00 Under Review 2021-12-29 2021-12-13 2022-01-03 2022-01-24 2022-02-28 2023-06-23 ment ant Selection Flores y Olivares. AR-MDTH-260654-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Social - Mendoza - IBRD / 87120 Post Limited 11,313.13 0.00 Under Review 2021-12-29 2021-12-13 2022-01-03 2022-01-24 2022-02-28 2023-06-23 ment ant Selection Congreso y Progreso. AR-MDTH-260656-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Ambiental - Mendo IBRD / 87120 Post Limited 11,313.13 0.00 Under Review 2021-12-29 2021-12-13 2022-01-03 2022-01-24 2022-02-28 2023-06-23 ment ant Selection za - Congreso y Progreso. Page 5 AR-MDTH-260657-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Legal - Mendoza - C IBRD / 87120 Post Limited 11,313.13 0.00 Under Review 2021-12-29 2021-12-13 2022-01-03 2022-01-24 2022-02-28 2023-06-23 ment ant Selection ongreso y Progreso. AR-MDTH-256464-CS-INDV / Integrated Habitat Improve Individual Consult Pending Impleme Sobrestante de Obra -UEP C IBRD / 87120 Post Limited 14,322.24 0.00 2021-12-29 2022-01-03 2022-01-24 2022-02-28 2023-10-21 ment ant Selection ntation orrientes, B° La Chola AR-MDTH-255588-CS-INDV / Integrated Habitat Improve Individual Consult Inspector de Obra - UEM Sant IBRD / 87120 Post Limited 7,835.00 0.00 Under Review 2022-02-15 2021-08-02 2022-02-20 2022-03-13 2022-04-17 2023-04-12 ment ant Selection a Fe Sector Noroeste AR-MDTH-255579-CS-INDV / Integrated Habitat Improve Individual Consult Inspector de Obra - UEM Sant IBRD / 87120 Post Limited 7,835.00 0.00 Under Review 2021-12-29 2021-08-02 2022-01-03 2022-01-24 2022-02-28 2023-02-23 ment ant Selection a Fe Sector Noroeste AR-MDTH-255604-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Social - UEP Neuqu IBRD / 87120 Post Limited 27,423.00 0.00 Under Review 2021-12-29 2021-08-27 2022-01-03 2022-01-24 2022-02-07 2023-10-30 ment ant Selection én, B° Belgrano, Sector La Fa milia AR-MDTH-255612-CS-INDV / Promotor Urbano - UEP Neuq Integrated Habitat Improve Individual Consult IBRD / 87120 Post Limited 13,712.00 0.00 Under Review 2021-12-29 2021-10-12 2022-01-03 2022-01-24 2022-02-07 2023-10-30 uén, Sector Z1: B° 2 y 7 de M ment ant Selection ayo , Peumayen, Nueva Jerus alén AR-MDTH-255585-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Social - UEM Santa IBRD / 87120 Post Limited 6,856.00 0.00 Under Review 2021-12-29 2021-08-02 2022-01-03 2022-01-24 2022-02-28 2023-02-23 ment ant Selection Fe Sector Noroeste AR-MDTH-255591-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Ambiental - UEM Sa IBRD / 87120 Post Limited 6,856.00 0.00 Under Review 2021-12-29 2021-08-02 2022-01-03 2022-01-24 2022-02-28 2023-02-23 ment ant Selection nta Fe Sector Noroeste AR-MDTH-255594-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Urbano - UEM Sant IBRD / 87120 Post Limited 6,856.00 0.00 Under Review 2021-12-29 2021-08-02 2022-01-03 2022-01-24 2022-02-28 2023-02-23 ment ant Selection a Fe Sector Noroeste AR-MDTH-255596-CS-INDV / Integrated Habitat Improve Individual Consult Inspector de Obra - UEP Cata IBRD / 87120 Post Limited 17,546.00 0.00 Under Review 2021-12-29 2021-04-12 2022-01-03 2022-01-24 2022-02-07 2024-01-28 ment ant Selection marca, B° Papa Francisco AR-MDTH-255599-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Urbano - UEP Cata IBRD / 87120 Post Limited 17,456.00 0.00 Under Review 2021-12-29 2021-04-12 2022-01-03 2022-01-24 2022-02-07 2024-01-28 ment ant Selection marca, B° Papa Francisco AR-MDTH-255600-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Legal - UEP Catama IBRD / 87120 Post Limited 17,456.00 0.00 Under Review 2021-12-29 2021-04-12 2022-01-03 2022-01-24 2022-02-07 2024-01-28 ment ant Selection rca, B° Papa Francisco AR-MDTH-255607-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Urbano - UEP Neuq IBRD / 87120 Post Limited 13,712.00 0.00 Under Review 2021-12-29 2021-08-27 2022-01-03 2022-01-24 2022-02-07 2023-10-30 ment ant Selection uén, B° Belgrano, Sector La F amilia AR-MDTH-255615-CS-INDV / Promotor Ambiental - UEP Ne Integrated Habitat Improve Individual Consult IBRD / 87120 Post Limited 13,712.00 0.00 Under Review 2021-12-29 2021-10-12 2022-01-03 2022-01-24 2022-02-07 2023-10-30 uquén, Sector Z1: B° 2 y 7 de ment ant Selection Mayo , Peumayen, Nueva Jer usalén AR-MDTH-255592-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Legal - UEM Santa IBRD / 87120 Post Limited 6,856.00 0.00 Under Review 2021-12-29 2021-08-02 2022-01-03 2022-01-24 2022-02-28 2023-02-23 ment ant Selection Fe Sector Noroeste AR-MDTH-255608-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Legal - UEP Neuqué IBRD / 87120 Post Limited 13,712.00 0.00 Under Review 2021-12-29 2021-08-27 2022-01-03 2022-01-24 2022-02-07 2023-10-30 ment ant Selection n ,B° Belgrano, Sector La Fa milia AR-MDTH-255609-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Ambiental - UEP Ne IBRD / 87120 Post Limited 13,712.00 0.00 Under Review 2021-12-29 2021-08-27 2022-01-03 2022-01-24 2022-02-07 2023-10-30 ment ant Selection uquén, B° Belgrano ,Sector L a Familia AR-MDTH-255620-CS-INDV / Inspector de Obra - UEP Neu Integrated Habitat Improve Individual Consult IBRD / 87120 Post Limited 31,340.00 0.00 Under Review 2021-12-29 2021-10-12 2022-01-03 2022-01-24 2022-02-07 2023-10-30 quén, Sector Z1: B° 2 y 7 de ment ant Selection Mayo , Peumayen, Nueva Jer usalén AR-MDTH-260653-CS-INDV / Integrated Habitat Improve Individual Consult Inspector de obra - Mendoza IBRD / 87120 Post Limited 11,313.13 0.00 Under Review 2021-12-29 2021-12-13 2022-01-03 2022-01-24 2022-02-28 2023-06-23 ment ant Selection - Congreso y Progreso. AR-MDTH-255990-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Social -UEP Corrien IBRD / 87120 Post Limited 14,322.25 0.00 Under Review 2021-12-29 2022-06-06 2022-01-03 2022-01-24 2022-02-28 2023-10-21 ment ant Selection tes, B° La Chola AR-MDTH-260649-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Ambiental - Mendo IBRD / 87120 Post Limited 11,313.13 0.00 Under Review 2021-12-29 2022-06-03 2022-01-03 2022-01-24 2022-02-28 2023-06-23 ment ant Selection za - Flores y Olivares. AR-MDTH-260650-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Legal - Mendoza - F IBRD / 87120 Post Limited 11,313.13 0.00 Under Review 2021-12-29 2021-12-13 2022-01-03 2022-01-24 2022-02-28 2023-06-23 ment ant Selection lores y Olivares. AR-MDTH-260652-CS-INDV / Integrated Habitat Improve Individual Consult Inspector de obra - Mendoza IBRD / 87120 Post Limited 11,313.13 0.00 Under Review 2021-12-29 2021-12-13 2022-01-03 2022-01-24 2022-02-28 2023-06-23 ment ant Selection - Congreso y Progreso. AR-MDTH-255999-CS-INDV / Integrated Habitat Improve Individual Consult Promotor Legal - UEP Corrien IBRD / 87120 Post Limited 14,322.25 0.00 Under Review 2021-12-29 2022-06-06 2022-01-03 2022-01-24 2022-02-28 2023-10-21 ment ant Selection tes, B° La Chola AR-MDTH-255614-CS-INDV / Promotor Legal - UEP Neuqué Integrated Habitat Improve Individual Consult IBRD / 87120 Post Limited 13,712.00 0.00 Under Review 2021-12-29 2021-10-12 2022-01-03 2022-01-24 2022-02-07 2023-10-30 n, Sector Z1: B° 2 y 7 de May ment ant Selection o , Peumayen, Nueva Jerusal én AR-MDTH-255619-CS-INDV / Inspector de Obra - UEP Neu Integrated Habitat Improve Individual Consult IBRD / 87120 Post Limited 31,340.00 0.00 Under Review 2021-12-29 2021-05-03 2022-01-03 2022-01-24 2022-02-07 2023-10-30 quén, Sector Z1: B° 2 y 7 de ment ant Selection Mayo , Peumayen, Nueva Jer usalén Page 6 AR-MDTH-255611-CS-INDV / Promotor Social - UEP Neuqu Integrated Habitat Improve Individual Consult IBRD / 87120 Post Limited 13,712.00 0.00 Under Review 2021-12-29 2021-10-12 2022-01-03 2022-01-24 2022-02-07 2023-10-30 én, Sector Z1 : B° 2 y 7 de M ment ant Selection ayo,Peumayen,Nueva Jerusal én AR-MININTERIOR-130312-CS Integrated Habitat Improve Individual Consult -INDV / Promotor social Lote IBRD / 87120 Post Limited 12,500.00 0.00 Under Review 2019-09-17 2020-12-10 2019-09-20 2019-09-25 2019-10-01 2021-09-20 ment ant Selection 2 y 3 - UEM Mendoza La Favo rita AR-MDTH-275422-CS-INDV / Individual Consult Pending Impleme IBRD / 87120 Institutional Strengthening Post Direct 7,267.00 0.00 2022-01-27 2022-02-06 2022-02-27 2022-04-03 2022-08-31 Jurídico Auxiliar ant Selection ntation AR-MININTERIOR-142828-CS Integrated Habitat Improve Individual Consult -INDV / Inspector de Obras Lo IBRD / 87120 Post Open 12,500.00 0.00 Under Review 2020-03-02 2020-12-10 2020-04-20 2020-05-11 2020-06-15 2020-12-12 ment ant Selection te 1 - UEM Mendoza La Favor ita 2021 AR-MDTH-302104-CS-INDV / Integrated Habitat Improve Individual Consult Pending Impleme IBRD / 87120 Post Limited 4,730.57 0.00 2022-06-28 2022-06-29 2022-06-30 2022-07-04 2023-01-30 Promotor Ambiental - UEM Sa ment ant Selection ntation nta Fe AR-MDTH-308263-CS-INDV / Integrated Habitat Improve Individual Consult Pending Impleme Promotor Ambiental - UEP Me IBRD / 87120 Post Limited 3,698.14 0.00 2022-08-08 2022-08-09 2022-08-10 2022-08-12 2023-02-08 ment ant Selection ntation ndoza B° Flores y Olivares AR-MDTH-322535-CS-INDV / Promotora Social - UEP Neuq Integrated Habitat Improve Individual Consult Pending Impleme IBRD / 87120 Post Limited 3,093.61 0.00 2022-10-19 2022-10-20 2022-10-21 2022-11-28 2023-04-27 uén, Sector Z1: B° 2 y 7 de M ment ant Selection ntation ayo , Peumayen, Nueva Jerus alén AR-MDTH-331871-CS-INDV / Integrated Habitat Improve Individual Consult Pending Impleme Inspector de obra- UEM Gral. IBRD / 87120 Post Limited 13,982.99 0.00 2022-12-14 2022-12-16 2022-12-16 2023-01-02 2023-12-28 ment ant Selection ntation Pueyrredón B° Villa Evita AR-MDTH-331874-CS-INDV / Integrated Habitat Improve Individual Consult Pending Impleme Promotor Social- UEM Gral. P IBRD / 87120 Post Limited 12,429.33 0.00 2022-12-14 2022-12-16 2022-12-16 2023-01-02 2023-12-28 ment ant Selection ntation ueyrredón B° Villa Evita AR-MDTH-331878-CS-INDV / Integrated Habitat Improve Individual Consult Pending Impleme Promotor Legal- UEM Gral. Pu IBRD / 87120 Post Limited 12,429.33 0.00 2022-12-14 2022-12-16 2022-12-16 2023-01-02 2023-12-28 ment ant Selection ntation eyrredón B° Villa Evita AR-MDTH-331879-CS-INDV / Integrated Habitat Improve Individual Consult Pending Impleme Promotor Urbano- UEM Gral. IBRD / 87120 Post Limited 12,429.33 0.00 2022-12-14 2022-12-14 2022-12-14 2023-01-02 2023-12-28 ment ant Selection ntation Pueyrredón B° Villa Evita AR-MDTH-331880-CS-INDV / Integrated Habitat Improve Individual Consult Pending Impleme Promotor Ambiental- UEM Gr IBRD / 87120 Post Limited 12,429.33 0.00 2022-12-14 2022-12-16 2022-12-16 2023-01-02 2023-12-28 ment ant Selection ntation al. Pueyrredón B° Villa Evita AR-MDTH-353044-CS-INDV / Integrated Habitat Improve Individual Consult Pending Impleme Promotor Legal - UEM Santa IBRD / 87120 Post Limited 5,901.24 0.00 2023-03-27 2023-03-29 2023-03-29 2023-03-30 2023-09-26 ment ant Selection ntation Fe Sector Noroeste AR-MDTH-361555-CS-INDV / Contratación de consultoría i Individual Consult Pending Impleme IBRD / 87120 Institutional Strengthening Post Limited 13,500.00 0.00 2023-05-31 2023-06-02 2023-06-04 2023-06-15 2023-12-31 ndividual "Servicio de Traduc ant Selection ntation tor/a y Clases de Lengua Extr anjera" AR-MDTH-364680-CS-INDV / Asesor para el apoyo a la coo rdinación del Foro de Ministr Individual Consult Pending Impleme IBRD / 87120 Institutional Strengthening Post Limited 8,100.00 0.00 2023-05-31 2023-06-02 2023-06-04 2023-06-15 2023-12-31 os y Máximas Autoridades de ant Selection ntation Vivienda y Urbanismo en Am érica Latina y el Caribe - MIN URVI 2023 AR-MDTH-364701-CS-INDV / Informe de Evaluación Final d Individual Consult Pending Impleme IBRD / 87120 Project Management Post Limited 15,500.00 0.00 2023-05-31 2023-06-05 2023-06-20 2023-07-01 2023-11-28 el Proyecto Integral de Hábit ant Selection ntation at y Vivienda (BIRF Nº8712-A R). Page 7 PROCUREMENT PLAN (Textual Part) Project information: GUYANA – GUYANA COVID – 19 EMERGENCY RESPONSE PROJECT – ID No. P175268 Project Implementation agency: Ministry of Health Date of the Procurement Plan: April 9, 2021 Period covered by this Procurement Plan: April – December 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used, in which case the Bank will have to be satisfied that the procurement procedures and bidding documents are acceptable to the Bank When the Borrower uses its own national open competitive procurement arrangements as set forth in Guyana Procurement Act 2003, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations, in which case the Bank will have to be satisfied that the procurement procedures and bidding documents are acceptable to the Bank. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations, in which case the Bank will have to be satisfied that the procurement procedures and bidding documents are acceptable to the Bank. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works): Not Applicable Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information: Not Applicable. PROCUREMENT Guyana : Guyana COVID-19 Emergency Response Project PLAN General Information Country: Guyana 2021-04-15 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175268 GPN Date: 2021-05-19 Project Name: Guyana COVID-19 Emergency Response Project Loan / Credit No: IDA / 68020, TF / B6163, IDA / 69750 Guyana COVID-19 FTO Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GY-G-COVID FTO-228610-GO Component 1. Emergency R Request for Quota Single Stage - One E Pending Impl -RFQ / Supply and Delivery of IDA / 68020 Post Open - National 202,712.00 0.00 2021-05-07 2021-07-02 2021-12-29 esponse to COVID-19 tions nvelope ementation Laboratory Equipment GY-G-COVID FTO-228612-GO Component 1. Emergency R Request for Quota Single Stage - One E Pending Impl -RFQ / Supply and Delivery of IDA / 68020 Post Open - National 373,000.00 0.00 2021-05-07 2021-07-02 2021-12-29 esponse to COVID-19 tions nvelope ementation Laboratory Supplies GY-G-COVID FTO-228615-GO Component 1. Emergency R Request for Quota Single Stage - One E Pending Impl -RFQ / Supply and Delivery of IDA / 68020 Post Open - National 15,400.00 0.00 2021-05-22 2021-07-17 2022-01-13 esponse to COVID-19 tions nvelope ementation Refrigerators(B) GY-G-COVID FTO-228616-GO Component 1. Emergency R Request for Quota Single Stage - One E Pending Impl -RFQ / Supply and Delivery of IDA / 68020 Post Open - National 35,200.00 0.00 2021-05-22 2021-07-17 2022-01-13 esponse to COVID-19 tions nvelope ementation Freezers (C ) GY-G-COVID FTO-228620-GO -RFQ / Supply and Delivery of Component 1. Emergency R Request for Quota Single Stage - One E IDA / 68020 Post Open - National 40,000.00 46,271.47 Signed 2021-05-31 2021-07-26 2021-10-30 2022-01-22 One Motor Vehicle (4x4 Doub esponse to COVID-19 tions nvelope le Cab Pick Up Type Vehicle) GY-G-COVID FTO-228623-GO Component 1. Emergency R Request for Quota Single Stage - One E -RFQ / Supply and Delivery of IDA / 68020 Post Open - National 125,000.00 189,236.86 Signed 2021-06-12 2021-08-12 2021-08-07 2022-01-26 2022-02-03 esponse to COVID-19 tions nvelope All Terrain Vehicles (ATV's) GY-G-COVID FTO-228624-GO Component 1. Emergency R Request for Quota Single Stage - One E Under Imple -RFQ / Supply and Delivery of IDA / 68020 Post Open - National 75,000.00 0.00 2021-05-30 2021-11-16 2021-07-25 2022-01-21 esponse to COVID-19 tions nvelope mentation One Cold Storage Truck GY-G-COVID FTO-228627-GO -RFQ / Supply and Delivery of Component 1. Emergency R Request for Quota Single Stage - One E IDA / 68020 Post Open - National 100,000.00 110,813.99 Completed 2021-05-15 2021-06-24 2021-07-10 2021-10-10 2022-01-06 2022-02-12 Computers, Tablets, Servers esponse to COVID-19 tions nvelope and Accessories GY-G-COVID FTO-228614-GO Component 1. Emergency R Request for Quota Single Stage - One E Pending Impl -RFQ / Supply and Delivery of IDA / 68020 Post Open - National 121,990.00 0.00 2021-05-15 2021-07-10 2022-01-06 esponse to COVID-19 tions nvelope ementation Hospital Supplies GY-G-COVID FTO-228622-GO -RFQ / Supply and Delivery of Component 1. Emergency R Request for Quota Single Stage - One E Under Imple IDA / 68020 Post Open - National 125,000.00 0.00 2021-06-19 2022-04-08 2021-08-14 2022-02-10 Two (2) Aluminum Boats Wi esponse to COVID-19 tions nvelope mentation th 40 HP Engines GY-G-COVID FTO-228613-GO Component 1. Emergency R UN Agencies (Dire -UN / Supply and Delivery of IDA / 68020 Post Direct 1,699,888.00 0.00 Canceled 2021-05-24 2021-05-29 2021-07-03 2021-12-30 esponse to COVID-19 ct) Hospital Equipment GY-G-COVID FTO-278175-GO Component 1. Emergency R Pending Impl -DIR / Supply and Delivery of IDA / 68020 Post Direct Selection Direct 210,000.00 0.00 2021-10-15 2021-10-20 2021-11-24 2022-05-23 esponse to COVID-19 ementation Hospital Beds GY-G-COVID FTO-278186-GO Component 1. Emergency R Pending Impl -DIR / Supply and Delivery of IDA / 68020 Post Direct Selection Direct 140,000.00 0.00 2021-10-15 2021-10-20 2021-11-24 2022-05-23 esponse to COVID-19 ementation Laryngoscope GY-G-COVID FTO-278187-GO -DIR / Supply and Delivery of Component 1. Emergency R Pending Impl Infusion Pumps, Syringe Pum IDA / 68020 Post Direct Selection Direct 405,000.00 0.00 2021-10-15 2021-10-20 2021-11-24 2022-05-23 esponse to COVID-19 ementation ps, Vital Signs Monitor, Defibr illator and Physiologic monito r GY-G-COVID FTO-278161-GO Component 1. Emergency R Pending Impl -DIR / Supply and Delivery of IDA / 68020 Post Direct Selection Direct 900,000.00 0.00 2021-10-15 2021-10-20 2021-11-24 2022-05-23 esponse to COVID-19 ementation Ventilators and Ultrasound M achines GY-G-COVID FTO-278132-GO Component 1. Emergency R -DIR / Supply and Delivery of IDA / 68020 Post Direct Selection Direct 40,000.00 37,110.00 Signed 2021-10-15 2021-11-09 2021-10-20 2021-11-22 2021-11-24 2022-01-08 2022-05-23 esponse to COVID-19 Ventilators GY-G-COVID FTO-278171-GO Component 1. Emergency R Pending Impl -DIR / Supply and Delivery of IDA / 68020 Post Direct Selection Direct 40,000.00 0.00 2021-10-15 2021-10-20 2021-11-24 2022-05-23 esponse to COVID-19 ementation Suction Units GY-G-COVID FTO-281188-GO Component 1. Emergency R Pending Impl -DIR / Supply and Delivery of IDA / 68020 Post Direct Selection Direct 7,000.00 0.00 2021-10-15 2021-10-20 2021-11-24 2022-05-23 esponse to COVID-19 ementation Laryngoscopes and Otoscope s GY-G-COVID FTO-278196-GO Component 1. Emergency R Pending Impl -DIR / Supply and Delivery of IDA / 68020 Post Direct Selection Direct 40,000.00 0.00 2021-10-15 2021-10-20 2021-11-24 2022-05-23 esponse to COVID-19 ementation Oxygen Concentrator and Ve ntilator GY-G-COVID FTO-278202-GO Component 1. Emergency R Pending Impl -DIR / Supply and Delivery of IDA / 68020 Post Direct Selection Direct 340,000.00 0.00 2021-10-15 2021-10-20 2021-11-24 2022-05-23 esponse to COVID-19 ementation X-ray machine Page 1 GY-G-COVID FTO-278205-GO Component 1. Emergency R Pending Impl -DIR / Supply and Delivery of IDA / 68020 Post Direct Selection Direct 30,000.00 0.00 2021-10-15 2021-10-20 2021-11-24 2022-05-23 esponse to COVID-19 ementation Humidifiers and Accessories GY-G-COVID FTO-278942-GO Component 1. Emergency R -DIR / Supply and Delivery of IDA / 68020 Post Direct Selection Direct 150,000.00 131,868.11 Signed 2022-02-10 2022-02-15 2022-02-15 2022-02-01 2022-03-22 2022-04-12 2022-09-18 esponse to COVID-19 2 No. Road Ambulances GY-G-COVID FTO-281199-GO Component 1. Emergency R Single Stage - One E Pending Impl -RFB / Supply and Delivery of IDA / 68020 Post Request for Bids Open - National 75,000.00 0.00 2022-03-29 2022-04-03 2022-05-15 2022-06-14 2022-07-19 2023-01-15 esponse to COVID-19 nvelope ementation One Infectious Waste Dispos al Vehicle GY-G-COVID FTO-281196-GO Component 1. Emergency R Request for Quota Single Stage - One E Under Imple -RFQ / Supply and Delivery of IDA / 68020 Post Open - National 100,000.00 0.00 2022-03-27 2022-04-08 2022-05-22 2022-11-18 esponse to COVID-19 tions nvelope mentation One 4x4 Motor Vehicle GY-G-COVID FTO-296098-GO Component 1. Emergency R -DIR / Supply and Delivery of IDA / 69750 Post Direct Selection Direct 1,500,000.00 0.00 Signed 2021-05-15 2021-06-11 2021-05-20 2021-06-03 2021-06-24 2021-12-21 esponse to COVID-19 COVID-19 Vaccines GY-G-COVID FTO-228629-GO Component 1. Emergency R Request for Quota Single Stage - One E -RFQ / Supply and Delivery of IDA / 68020 Post Open - National 150,000.00 0.00 Canceled 2021-08-20 2021-10-15 2022-04-13 esponse to COVID-19 tions nvelope Cloth Masks GY-G-COVID FTO-228617-GO Component 1. Emergency R Request for Quota Single Stage - One E -RFQ / Supply and Delivery of IDA / 68020 Post Open - National 24,970.00 0.00 Canceled 2021-05-11 2021-07-06 2022-01-02 esponse to COVID-19 tions nvelope Quarantine equipment GY-G-COVID FTO-228626-GO -RFQ / Supply and Delivery of Component 1. Emergency R Request for Quota Single Stage - One E IDA / 68020 Post Open - National 28,000.00 0.00 Canceled 2021-05-31 2021-07-26 2022-01-22 Eight Isolation Pods for trans esponse to COVID-19 tions nvelope porting COVID-19 patients GY-G-COVID FTO-228625-GO Component 1. Emergency R Request for Quota Single Stage - One E -RFQ / Supply and Delivery of IDA / 68020 Post Open - National 4,800.00 0.00 Canceled 2021-05-21 2021-07-16 2022-01-12 esponse to COVID-19 tions nvelope Twelve Bicycles GY-G-COVID FTO-228618-GO Component 1. Emergency R Request for Quota Single Stage - One E -RFQ / Supply and Delivery of IDA / 68020 Post Open - National 8,000.00 0.00 Canceled 2022-04-16 2022-06-11 2022-12-08 esponse to COVID-19 tions nvelope Waste Receptacle for Schools GY-G-COVID FTO-228628-GO Component 1. Emergency R Request for Quota Single Stage - One E -RFQ / Supply and Delivery of IDA / 68020 Post Open - National 286,000.00 0.00 Canceled 2021-05-29 2021-07-24 2022-01-20 esponse to COVID-19 tions nvelope IT Software GY-G-COVID FTO-325831-GO Component 1. Emergency R Direct - Internation Pending Impl -DIR / Supply and Delivery of IDA / 68020 Post Direct Selection 4,000,000.00 0.00 2021-06-15 2021-06-20 2021-07-25 2022-01-21 esponse to COVID-19 al ementation Additional Hospital Equipmen t GY-G-COVID FTO-228619-GO -UN / Supply and Delivery of Component 1. Emergency R Request for Quota Open - Internationa Single Stage - One E Pending Impl IDA / 68020 Post 225,000.00 0.00 2022-03-05 2022-04-30 2022-10-27 (3) Ambulances, 1 Road and esponse to COVID-19 tions l nvelope ementation 2 off road ambulances GY-G-COVID FTO-325830-GO Component 1. Emergency R Direct - Internation Pending Impl -DIR / Supply and Delivery of IDA / 68020 Post Direct Selection 400,000.00 0.00 2021-03-15 2021-03-20 2021-04-24 2021-10-21 esponse to COVID-19 al ementation Cold Chain Equipment GY-G-COVID FTO-362338-GO Component 1. Emergency R Single Stage - One E Pending Impl -RFB / Procurement of Dental IDA / 69750 Post Request for Bids Open - National 315,000.00 0.00 2023-05-21 2023-05-26 2023-07-07 2023-08-06 2023-09-10 2023-12-09 esponse to COVID-19 nvelope ementation Equipment GY-G-COVID FTO-362350-GO Component 1. Emergency R Open - Internationa Single Stage - One E Pending Impl -RFB / Procurement of Spiro IDA / 69750 Post Request for Bids 220,000.00 0.00 2023-05-21 2023-05-26 2023-07-07 2023-08-06 2023-09-10 2023-12-09 esponse to COVID-19 l nvelope ementation metry Equipment and Access ories GY-G-COVID FTO-362356-GO Component 1. Emergency R Open - Internationa Single Stage - One E Pending Impl -RFB / Procurement of Equip IDA / 69750 Post Request for Bids 400,000.00 0.00 2023-05-21 2023-05-26 2023-07-07 2023-08-06 2023-09-10 2023-12-09 esponse to COVID-19 l nvelope ementation ment for Simulation Lab and Centre GY-G-COVID FTO-362355-GO Component 1. Emergency R Request for Quota Single Stage - One E Pending Impl -RFB / Procurement of Eye Ca IDA / 69750 Post Open - National 100,000.00 0.00 2023-06-05 2023-07-31 2023-10-29 esponse to COVID-19 tions nvelope ementation re Equipment GY-G-COVID FTO-361592-GO Component 1. Emergency R Direct - Internation Under Revie -DIR / Procurement of Pathol IDA / 69750 Prior Direct Selection 2,140,000.00 0.00 2023-05-15 2023-06-07 2023-05-20 2023-06-21 2023-06-24 2023-12-21 esponse to COVID-19 al w ogy Equipment NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3. Supporting N GY-G-COVID FTO-286132-NC ational and Sub-national, Pre Direct - Internation Pending Impl TF / B6163 Post Direct Selection 150,000.00 0.00 2022-08-09 2022-08-14 2022-09-18 2023-03-17 -RFQ / One Health Training vention and Preparedness a al ementation nd Health System Resilience CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3. Supporting N GY-G-COVID FTO-285818-CS ational and Sub-national, Pre Consultant Qualifi Under Implement -CDS / National Focal Point C TF / B6163 Post Open - National 60,000.00 0.00 2022-03-22 2022-03-25 2022-04-12 2022-05-26 2022-06-25 2022-07-30 2023-01-26 vention and Preparedness a cation Selection ation onsulancy nd Health System Resilience INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 GY-G-COVID FTO-228632-CS Component 2. Implementati Pending Impleme IDA / 68020 Post Direct Selection Direct 4,221.00 0.00 2021-05-10 2021-05-20 2021-07-24 2022-01-20 -CDS / Health Systems Speci on Management and M&E ntation alist GY-G-COVID FTO-228633-CS Component 2. Implementati Pending Impleme IDA / 68020 Post Direct Selection Direct 4,221.00 0.00 2021-04-09 2021-04-19 2021-06-23 2021-12-20 -CDS / Procurement Specialis on Management and M&E ntation t GY-G-COVID FTO-228634-CS Component 2. Implementati Individual Consult Pending Impleme IDA / 68020 Post Open 26,355.00 0.00 2021-05-02 2021-06-20 2021-07-11 2021-08-15 2022-02-11 -INDV / Procurement Assistan on Management and M&E ant Selection ntation t GY-G-COVID FTO-228635-CS Component 2. Implementati Individual Consult IDA / 68020 Post Open 28,237.00 26,264.84 Completed 2021-05-02 2021-06-15 2021-06-20 2021-07-12 2021-07-11 2021-07-21 2021-08-15 2021-08-10 2022-02-11 2022-02-15 -INDV / Finance Officer on Management and M&E ant Selection GY-G-COVID FTO-228636-CS Component 2. Implementati Individual Consult Pending Impleme IDA / 68020 Post Direct 2,014.00 0.00 2021-04-09 2021-04-19 2021-05-10 2021-06-14 2021-12-11 -INDV / M&E Specialist on Management and M&E ant Selection ntation GY-G-COVID FTO-228637-CS Component 2. Implementati Individual Consult Under Implement IDA / 68020 Post Open 18,825.00 0.00 2021-04-09 2021-05-03 2021-05-28 2021-12-15 2021-06-18 2021-07-23 2022-01-19 -INDV / E&S Specialist on Management and M&E ant Selection ation GY-G-COVID FTO-228638-CS -INDV / Social Consultant to C Component 2. Implementati Individual Consult Pending Impleme IDA / 68020 Post Open 12,000.00 0.00 2021-06-07 2021-07-26 2021-08-16 2021-09-20 2022-03-19 onduct Seminars on Domesti on Management and M&E ant Selection ntation cs Violence , Childs Abuse et c. Component 3. Supporting N GY-G-COVID FTO-286130-CS ational and Sub-national, Pre Pending Impleme -CDS / Joint External Evaluati TF / B6163 Post Direct Selection Direct 150,000.00 0.00 2022-03-31 2022-04-10 2022-06-14 2022-12-11 vention and Preparedness a ntation on nd Health System Resilience Component 3. Supporting N GY-G-COVID FTO-286131-CS ational and Sub-national, Pre Pending Impleme -CDS / Performance Veterinar TF / B6163 Post Direct Selection Direct 150,000.00 0.00 2022-04-26 2022-05-06 2022-07-10 2023-01-06 vention and Preparedness a ntation y Service nd Health System Resilience GY-G-COVID FTO-358791-CS Component 2. Implementati Pending Impleme -CDS / Hire of Part-time Proc IDA / 68020 Post Direct Selection Direct - National 1,500.00 0.00 2023-04-26 2023-04-28 2023-05-01 2023-06-30 on Management and M&E ntation urement Specialist Page 3 Himachal Pradesh Horticulture Development Project Project ID : P151744 Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan : Original: March 22, 2016 2. Date of General Procurement Notice: May 19, 2015 3. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Table 1: Procurement Methods Category Method of Threshold (US$ Procurement Equivalent) Goods and non- ICB >3,000,000 consulting LIB Wherever agreed by the services (including World Bank IT contracts) NCB Up to 3,000,000 (with NCB conditions) Shopping Up to 100,000 From UN Agencies As per para 3.10 of Guidelines DC As per para 3.7 of Guidelines Force Account As per para 3.9 of Guidelines Framework As per para 3.6 of Guidelines Agreements Works ICB >40,000,000 NCB Up to 40,000,000 (with NCB conditions) Shopping Up to 100,000 DC As per para 3.7 of Guidelines Force Account As per para 3.9 of Guidelines  Prior Review by the Bank : The World Bank will prior review all Terms of Reference and the following contracts: March 22, 2015 • Works: All contracts more than US$15.0 million equivalent; • Goods: All contracts more than US$3.0 million equivalent; • Non-Consulting Services: All contracts more than US$3.0 million equivalent;  The HPHDS will prior review the first contract issued by each implementing entity, if the estimates of those contracts are below the prior review threshold value. The Bank will conduct prior review for only those contracts whose estimates fall in the prior review threshold value. In addition, justifications for all contracts to be issued on Limited International Bidding (LIB), direct contracting or single sourcing (>US$100,000) basis will be subject to prior review by the World Bank. These thresholds are set for the initial 18 months of project implementation and are based on the procurement performance of the project, and may be modified. In addition, the Bank will carry out an annual ex post procurement review of the procurement falling below the prior review threshold mentioned above.  All contracts below the specified prior review threshold value will be subject to Post Procurement Review (PPR). The implementing agency will prepare a list of contracts and submit it to the World Bank for this purpose. The PPR will be conducted on an annual basis. 2. Prequalification. Not applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by 5. Any Other Special Procurement Arrangements:  International Competitive Bidding (ICB) is the preferred method for procurement of goods, works and non-consulting services using the World Bank’s standard bidding document. In addition, the following methods may be adopted depending upon size and complexity of subprojects in accordance with Procurement Guidelines, and as agreed in the Procurement Plan: (a) Limited International Bidding (LIB), (b) National Competitive Bidding (NCB), (c) Shopping, (d) Framework Agreements, (e) Direct Contracting, (f) Force Account, and (g) Procurement of UN agencies. Limited International Bidding is essentially ICB by direct invitation, is used only under exceptional circumstances, and will be March 22, 2015 adopted only for packages that are specifically agreed by the World Bank to be procured following LIB.  National Competitive Bidding (NCB) for procurement of goods and works will be conducted in accordance with paragraphs 3.3 and 3.4 of the Procurement Guidelines and the following provisions: (i) Only the model bidding documents for NCB as agreed with the GoI Task Force (and as amended from time to time), will be used for bidding. (ii) Invitation to bid will be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids. (iii) No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, government-owned enterprises, small-scale enterprises or enterprise from any given regional government; (iv) Except with the prior concurrence of the World Bank, there will be no negotiation of price with the bidders, even with the lowest evaluated bidder; (v) For prior review contracts, extension of bid validity will not be allowed without the prior concurrence of the World Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by the World Bank only in cases of Force Majeure and circumstance beyond the control of the Purchaser/Employer); (vi) For prior review contracts, re-bidding will not be carried out without the prior concurrence of the World Bank; (vii) The system of rejecting bids outside a pre-determined margin or “bracket” of prices will not be used in the Project; (viii) Rates contracts entered into by the Directorate General of Supplies and Disposal (DGS & D) will not be acceptable as a substitute for NCB procedures unless agreed with the World Bank on a case-by- case basis. Such contracts will be acceptable however, for any procurement under the shopping procedure; (ix) The two or three envelop system will not be used (expect when using the e-procurement system assessed and agreed by the World Bank). March 22, 2015  Shopping. Procurement of goods, works and non-consulting services may be carried out using the shopping method (paragraph 3.5 of the Procurement Guidelines) for readily available, off-the-shelf products, or simple civil works valued at less than US$100,000 and which do not require tailor made designs as agreed with the World Bank or concerned expert agencies. Such method, if any, will be agreed in the Procurement Plan. The implementing agency and entities will solicit at least three price quotations for the purchase of goods, materials, small works, or services (non-consulting), to formulate a cost comparison report. If agreed by the World Bank, under exceptional circumstances, (such as design sensitivity due to location near a monument or appropriate technology), International Shopping may be used wherein quotations will be solicited from at least three suppliers in two different countries. Goods that otherwise qualify for shopping could be procured directly from UN agencies. In specific cases agreed with the World Bank, procurement may be made from UN agencies as per paragraph 3.10 of the Procurement Guidelines.  Direct Contracting. Direct contracting for the procurement of civil works and goods (paragraph 3.7 of the Procurement Guidelines) may be used to extend an existing contract or award a new contract. For such contracting to be justified, the World Bank must agree that the price is reasonable and that no advantage could be obtained by further competition. Direct contracting can be used to procure from the private sector, UN agencies/programs (for goods), or contractors or NGOs that are already mobilized and working in the target areas.  Force Account. When contractors/suppliers are unlikely to bid at reasonable prices because of the location and risk associated with the subproject or a certain government agency has exclusive rights to a certain type of works/supply, the borrower may use its own department’s personnel and equipment or government owned construction units, provided that the borrower has sufficient managerial capacity and possesses the required technical and financial controls to report to the World Bank on expenditure, as per paragraph 3.9 of the Procurement Guidelines.  Framework Agreements. Directorate General of Supplies and Disposal rate contracts will be acceptable as framework agreements for the procurement of goods. Regional government level rate contracts will be examined by the World Bank and if agreed upon, may also be used as framework agreements. Implementing entities also have the option to set up new framework agreements as per paragraph 3.6 of the Procurement Guidelines. March 22, 2015  Use of government institutions and enterprise. Government owned enterprise or institutions in India may be hired based on their unique and exceptional nature if their participation is considered critical to the Project implementation. In such cases, the conditions given in clauses 1.13 of the Consultant Guidelines will be satisfied and each case will be subject to prior review by the World Bank. 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness : Available in separate Excel file III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Table 2: Procurement Methods Category Method of Threshold (US$ Procurement Equivalent) Consultants’ QCBS As per Section II of Guidelines services CQS Up to 300,000 SSS As per para 3.8-3.11 of Guidelines Individuals As per Section V of Guidelines LCS As per para 3.6 of Guidelines QBS As per para 3.2 of Guidelines FBS As per para 3.5 of Guidelines (i) International >800,000 shortlist Up to 800,000 (ii) Shortlist may comprise national consultants only  The World Bank will prior review all Terms of Reference and the following contracts: • All contracts more than US$1.0 million equivalent for firm; and • All contracts more US$300,000 equivalent for individuals. The HPHDS will prior review the first contract issued by each implementing entity, if the estimates of those contracts are below the March 22, 2015 prior review threshold value. The Bank will conduct prior review for only those contracts whose estimates fall in the prior review threshold value. In addition, justifications for all contracts to be issued on direct contracting or single sourcing (>US$100,000) basis will be subject to prior review by the World Bank. These thresholds are set for the initial 18 months of project implementation and are based on the procurement performance of the project, and may be modified. In addition, the Bank will carry out an annual ex post procurement review of the procurement falling below the prior review threshold mentioned above. All contracts below the specified prior review threshold value will be subject to Post Procurement Review (PPR). The implementing agency will prepare a list of contracts and submit it to the World Bank for this purpose. The PPR will be conducted on an annual basis. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US $ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements:  Selection of Consultants—Quality and Cost Based Selection: Consultant Services may be procured under contracts awarded on the basis of Quality- and Cost-based Selection in accordance with the provisions of Section II of Consultant Guidelines using the World Bank’s Standard RFP. In addition, the following selection methods may be adopted depending upon size and complexity of tasks and as agreed in the Procurement Plan: • Quality Based Selection (QBS) • Selection under Fixed Budget (FBS) • Least Cost Selection (LCS) • Single Source Selection (SSS) • Individual Consultant (IC) Single-Source Selection of consulting firms or individual experts may be used only if it presents a clear advantage over competition for the required consulting services in accordance with paragraph 3.8 of the World Bank’s Consultant Guidelines. Selection of consulting firms based on Consultants’ Qualifications (CQS) may be appropriate for assignments estimated to cost up to US$300,000 or equivalent in accordance with paragraph 3.7 of the Consultant Guidelines. Advertisement for expression of interest may be limited to the regional level for assignments estimated to cost less than US$100,000. For assignments that are estimated to cost less than US$50,000, March 22, 2015 advertisement is not mandatory as long as a shortlist of at least three proven qualified firms is established. Shortlists of consultants for services estimated to cost less than US$800,000 or the equivalent per contract may be composed entirely of national consultants (paragraph 2.7 of Consultant Guidelines). Services for assignments that meet the requirements set forth in paragraph 5.1 of the Consultant Guidelines may be procured under contracts awarded to individual consultants in accordance with the provisions of paragraphs 5.2 to 5.5 of the Consultant Guidelines. Under the circumstances described in paragraph 5.6 of the Consultant Guidelines, such contracts may be awarded to individual consultants on a sole source basis. 4. Consultancy Assignments with Selection Methods and Time Schedule: Available in separate Excel file. March 22, 2015 PROCUREMENT India : Himachal Pradesh Horticulture Development Project PLAN General Information Country: India 2017-09-12 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151744 GPN Date: 2017-04-03 Project Name: Himachal Pradesh Horticulture Development Project Loan / Credit No: IDA / 58380 Dr Y S Parmar University of Horticulture and Forestry, Nauni, Solan Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned HPHDP PIU UHF WORKS 2 / Providing solar fencing, estab Component A: Horticulture P Request for Quota Single Stage - One E 2018-09-1 lishment of metrological obse IDA / 58380 Post Open - National 280,000.00 0.00 Canceled 2018-01-20 2018-03-17 roduction and Diversification tions nvelope 3 rvatories, supply and erectio n of training structure for tre es HPHDP PIU UHF WORKS 3 / Construction, Upgradation an Component A: Horticulture P Single Stage - Two E 2018-08-1 IDA / 58380 Post Request for Bids Open - National 510,000.00 0.00 Canceled 2017-09-14 2017-09-19 2017-10-31 2018-01-13 2018-02-17 d renovation of Laboratories, roduction and Diversification nvelope 6 sitting space, renovation of P IU Cell WORKS PACKAGE-2 / Creatin Component A: Horticulture P Request for Quota Single Stage - One E 2019-05-2 IDA / 58380 Post Limited 769.00 0.00 Canceled 2018-10-05 2018-11-30 g of HP-HDP Cell for PIU at U roduction and Diversification tions nvelope 9 H&F,Nauni WORKS PACKAGE-6 / Constr Component A: Horticulture P Request for Quota Single Stage - One E 2020-05-2 uction of sample digestion fa IDA / 58380 Post Limited 76,000.00 39,034.94 Signed 2019-10-02 2019-12-23 2019-11-27 2020-05-14 roduction and Diversification tions nvelope 5 cility under HPHDP IN-UNIVERSITY HORTICULT-1 19676-CW-RFQ / Renovation of culture room, Laboratory a Component A: Horticulture P Request for Quota Single Stage - One E 2020-03-1 IDA / 58380 Post Limited 17,457.00 17,246.09 Completed 2019-07-27 2017-06-30 2019-09-21 2017-11-12 nd sitting space etc. for the d roduction and Diversification tions nvelope 9 epartment of plant pathology at main campus nauni, Solan IN-UNIVERSITY HORTICULT-1 19686-CW-RFQ / Renovation/ Scaling up of Bio-control unit Component A: Horticulture P Request for Quota Single Stage - One E 2020-03-1 IDA / 58380 Post Limited 25,169.00 24,761.60 Completed 2019-07-27 2018-02-12 2019-09-21 2018-06-09 for the department of Entom roduction and Diversification tions nvelope 9 ology at main campus Nauni, Solan. SH: Civil works along with module lab IN-UNIVERSITY HORTICULT-1 19701-CW-RFQ / Renovation and strengthening of laborat Component A: Horticulture P Request for Quota Single Stage - One E 2020-03-2 ory and sitting space for the IDA / 58380 Post Limited 28,810.00 29,429.74 Completed 2019-07-28 2017-08-17 2019-09-22 2017-10-05 roduction and Diversification tions nvelope 0 department of Fruit Science at main campus Nauni, Solan . SH:Civil work along with mod ule lab WORKS PACKAGE-1 / Supply Component A: Horticulture P Request for Quota Single Stage - One E 2020-04-1 and erection of training struc IDA / 58380 Post Limited 40,000.00 33,859.96 Signed 2019-08-27 2018-05-26 2019-10-22 2018-06-20 roduction and Diversification tions nvelope 9 tures for training of trees und er HPHDP WORKS PACKAGE-3 / Purcha Component A: Horticulture P Request for Quota Single Stage - One E 2020-03-2 se and installation of Drip Irri IDA / 58380 Post Limited 10,000.00 1,349.89 Signed 2019-08-04 2017-07-24 2019-09-29 2017-08-29 roduction and Diversification tions nvelope 7 gation Facilities WORKS PACKAGE-8 / Develo pment of culture room and h Component A: Horticulture P Request for Quota Single Stage - One E 2020-04-2 IDA / 58380 Post Limited 20,000.00 0.00 Canceled 2019-09-03 2019-10-29 umidity maintenance and mo roduction and Diversification tions nvelope 6 nitoring system WORKS PACKAGE-7 / Constr uction of building for creating Component A: Horticulture P Single Stage - Two E 2020-07-2 IDA / 58380 Post Request for Bids Open - National 230,000.00 116,316.60 Signed 2019-08-22 2020-06-03 2019-08-27 2020-06-04 2019-10-08 2020-07-07 2019-12-21 2020-09-21 2020-01-25 2020-12-16 facilities for queen productio roduction and Diversification nvelope 3 n and bumble bee rearing WORKS PACKAGE-5 / Develo pment of water supply faciliti Component A: Horticulture P Single Stage - Two E 2020-08-1 IDA / 58380 Post Request for Bids Open - National 126,000.00 0.00 Canceled 2019-09-16 2019-09-21 2019-11-02 2020-01-15 2020-02-19 es and water harvesting stru roduction and Diversification nvelope 7 ctures under HPHDP PACKAGE-19 / Supply and In Component A: Horticulture P Request for Quota Single Stage - One E 2021-08-1 stallation of Drip Irrigation Sy IDA / 58380 Post Limited 11,000.00 0.00 Canceled 2020-12-20 2021-02-14 roduction and Diversification tions nvelope 3 stem for new Fruit Orchards WORKS PACKAGE-4 / Providi Component A: Horticulture P Request for Quota Single Stage - One E 2021-08-1 ng Solar Fencing of Experime IDA / 58380 Post Limited 70,000.00 142,063.20 Signed 2020-12-20 2021-05-18 2021-02-14 2021-08-02 roduction and Diversification tions nvelope 3 ntal Area under HPHDP PACKAGE-20 / Creation of w Component A: Horticulture P Request for Quota Single Stage - One E 2021-09-0 ater facilities under new com IDA / 58380 Post Limited 27,000.00 0.00 Canceled 2021-01-08 2021-03-05 roduction and Diversification tions nvelope 1 ponent gene bank Request for Quota PACKAGE -19 / Supply and In Component A: Horticulture P Request for Quota Single Stage - One E 2022-01-3 IDA / 58380 Post Limited tions (Non Bank-S 70,000.00 32,548.72 Signed 2021-06-08 2021-05-20 2021-08-03 2021-08-18 stallation of Drip Irrigation Sy roduction and Diversification tions nvelope 0 PD) stem. CONSTRUCTION OF FIELD LA BORATARY / Construction of f Request for Quota Component A: Horticulture P Request for Quota Single Stage - One E 2023-01-1 ield laboratory under HP-HDP IDA / 58380 Post Limited tions (Non Bank-S 34,929.00 0.00 Canceled 2022-05-25 2022-07-20 roduction and Diversification tions nvelope 6 for the deptt. of SS&WM at m PD) ain campus nauni, Solan IN-UNIVERSITY HORTICULT-3 14494-CW-RFQ / construction Request for Quota Component A: Horticulture P Request for Quota Single Stage - One E Under Imple 2023-05-2 of field laboratory under HPH IDA / 58380 Post Limited tions (Non Bank-S 31,043.00 0.00 2022-10-01 2022-10-06 2022-11-26 roduction and Diversification tions nvelope mentation 5 DP for the deptt of SS&WM (S PD) oil Science and Water manag ement) (Civil Works only) Page 1 FURNISHING OF APICULTURE BUILDING / Furnishing of Apic Request for Bids - ulture building under sub co Component A: Horticulture P Single Stage - Two E Small Works SPD 2023-06-1 IDA / 58380 Post Request for Bids Open - National 134,125.00 0.00 Canceled 2022-09-22 2022-09-27 2022-10-27 2022-11-20 2022-12-12 mponent Managed pollinatio roduction and Diversification nvelope (2 envelope proce 0 n for the department of Ento ss) mology (providing module la boratories and refrigeration u nit) IN-UNIVERSITY HORTICULT-3 14495-CW-RFQ / Constructio Request for Quota Component A: Horticulture P Request for Quota Single Stage - One E Under Imple 2023-05-2 n of 3 no 1 lakh liter capacity IDA / 58380 Post Limited tions (Non Bank-S 29,413.00 0.00 2022-09-28 2022-10-06 2022-11-23 roduction and Diversification tions nvelope mentation 2 water tanks at main campus PD) nauni for the deptt of Fruit sc ience WORKS-CONSTRUCTION OF Request for Quota Component A: Horticulture P Request for Quota Single Stage - One E Under Imple 2023-06-2 FIELD STORE / Construction o IDA / 58380 Post Limited tions (Non Bank-S 17,152.00 0.00 2022-10-30 2021-12-15 2022-12-25 roduction and Diversification tions nvelope mentation 3 f Field Store/Propagation lab PD) at Kandaghat UHF/HPHDP/WORKS/GENEBA NK/RENO/2022 / Renovation Request for Quota of PI//CO-PI Chamber at RHR Component A: Horticulture P Request for Quota Single Stage - One E Under Imple 2023-06-2 IDA / 58380 Post Open - National tions (Non Bank-S 23,420.00 0.00 2023-02-25 2023-04-15 &TS Mashobra under HPHDP roduction and Diversification tions nvelope mentation 9 PD) Research component Gene B ank ,department of Fruit Scie nce PIU UHF Nauni Solan UHF/DR/HP-HDP/FURNISHIN Request for Quota G/ MP/- / Furnishing of apicult Component A: Horticulture P Request for Quota Single Stage - One E Under Imple 2023-10-1 IDA / 58380 Post Open - National tions (Non Bank-S 38,065.00 0.00 2023-04-28 2023-06-13 ure building by providing mo roduction and Diversification tions nvelope mentation 1 PD) dule laboratory, furnitureetc UHF/HPHDP/PIU/WORKS/GEN Request for Quota EBANK/RENO/2022 / Renovat Component A: Horticulture P Request for Quota Single Stage - One E Pending Imp 2023-10-0 IDA / 58380 Post Open - National tions (Non Bank-S 19,675.00 0.00 2023-05-26 2023-07-06 ion of CO-PI Chamber for the roduction and Diversification tions nvelope lementation 4 PD) department of Fruit Science GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HPHDP PIU UHF COM SOFT Component A: Horticulture P Request for Quota Single Stage - One E PROC / Purchase of Compute IDA / 58380 Post Open - National 110,000.00 18,304.44 Completed 2018-01-06 2018-03-03 2018-03-16 2018-08-30 2018-04-18 roduction and Diversification tions nvelope r software Weather Station GOODS PACKAGE 2 / Procur Component A: Horticulture P Request for Quota Single Stage - One E IDA / 58380 Post Open - National 85,077.00 11,237.52 Signed 2018-07-12 2018-09-06 2018-12-14 2019-03-05 ement of Silent Gensets 4 roduction and Diversification tions nvelope HPHDP PIU UHF FARM MACH Component A: Horticulture P Request for Quota Single Stage - One E / Procurement of Farm Machi IDA / 58380 Post Open - National 50,000.00 0.00 Canceled 2017-08-21 2017-10-16 2018-04-14 roduction and Diversification tions nvelope neries and Tools HPHDP PIU UHF GEN PURCH Component A: Horticulture P Request for Quota Single Stage - One E IDA / 58380 Post Open - National 80,000.00 0.00 Canceled 2017-09-25 2017-11-20 2018-05-19 / Purchase of Generator roduction and Diversification tions nvelope IN-UNIVERSITY HORTICULT-6 1535-GO-RFB / Procurement Component A: Horticulture P Single Stage - Two E of Transmission Electron Micr IDA / 58380 Post Request for Bids Open - National 770,000.00 0.00 Canceled 2018-07-25 2019-01-02 2018-07-30 2018-09-10 2019-02-05 2018-11-23 2018-12-28 2019-06-26 roduction and Diversification nvelope oscope and Ultra Microtome Upgradable to Cryo with Acc essories GOODS PACKAGE-8 / AC-5, Deep Freezer-5, Digital temp erature & RH Recorder-10, Fl ame Photometer-1, Fume Ho Component A: Horticulture P Request for Quota Single Stage - One E ods-1, GPS-9, Hot Plate-2, Hy IDA / 58380 Post Limited 1,523.00 0.00 Canceled 2018-09-29 2018-11-24 2019-05-23 roduction and Diversification tions nvelope grometer-5, Incubator-cum-s haker-6, Microwave-2, Mixing machine & trays-1, Media pu mp with tank, mixer-grinder, pressure tester-1, etc. GOODS PACKAGE-7 / Autocla ve-5, BOD Incubator-9, Centri fuge-2, CHNS Analyzer-1, Ca nopy Analyzer-1, CO2 Analyz Component A: Horticulture P Single Stage - Two E IDA / 58380 Post Request for Bids Open - National 4,154.00 0.00 Canceled 2018-09-17 2018-09-22 2018-11-03 2019-01-16 2019-02-20 2019-08-19 er, Dehumidifer-1, Hot air ov roduction and Diversification nvelope en-7, leaf area meter-2, Lami nar Air Flow-5, Mite brushing and Counting Machine-1, Mic rocentrifuge-2 etc. GOODS PACKAGE-5 / Procur ement of Scientific Equipmen ts (Atomic Absorption Spectr ophotometer-1, Deionizer-1, Component A: Horticulture P Single Stage - Two E Electrophoresis apparatus-2, IDA / 58380 Post Request for Bids Open - National 8,615.00 0.00 Canceled 2018-09-17 2018-09-22 2018-11-03 2019-01-16 2019-02-20 2019-08-19 roduction and Diversification nvelope Fermenter-1, Gas Chromatog raph-1, Gel Documentation S ystem-1, ICAP-1, KD Pro Ther mal Imager-1, LCMS-1, Micro wave digestion system-1 etc. GOODS PACKAGE-13 / Procu Component A: Horticulture P Request for Quota Single Stage - One E rement of software and softw IDA / 58380 Post Limited 308.00 0.00 Canceled 2018-09-22 2018-11-17 2019-05-16 roduction and Diversification tions nvelope are development charges GOODS PACKAGE 5 / Gel doc umentation, Inductively Coup led, UV Spectrophotometer, Root Length Scanner, Soil Mo Component A: Horticulture P Single Stage - Two E IDA / 58380 Post Request for Bids Open - National 560,000.00 130,872.33 Signed 2019-09-26 2019-01-02 2019-10-01 2019-11-12 2019-02-14 2020-01-25 2019-07-17 2020-02-29 2019-12-04 2020-08-27 isture Meter, KD Pro-3, Press roduction and Diversification nvelope ure Plate Apparatus, Electrop horesis Unit, Spectrometer, D eionizer, Nano Pico drop, Mic reowave Digestion System et c. GOODS PACKAGE 7 / Labora tory and Field Equipment (Le af Area Mater, Plant Canopy Component A: Horticulture P Single Stage - Two E Analyzer, Laminar Air Flow, B IDA / 58380 Post Request for Bids Open - National 270,000.00 93,898.33 Signed 2019-08-23 2019-01-02 2019-08-28 2019-10-09 2019-02-07 2019-12-22 2019-07-03 2020-01-26 2019-08-30 2020-07-24 2019-11-30 roduction and Diversification nvelope OD Incubator, Autoclave, Rea l Time PCR, Dehumidifier, Ho t Air Oven, Centrifuge,CHNS Analyzer etc.) Page 2 GOODS PACKAGE-4 / Micros copes and Cameras ( Stereoz Component A: Horticulture P Single Stage - Two E oom , Binocular, Fluorescent, IDA / 58380 Post Request for Bids Open - National 120,000.00 2,925.19 Signed 2019-09-19 2019-01-02 2019-09-24 2019-11-05 2019-01-29 2020-01-18 2019-02-21 2020-02-22 2019-08-08 2020-08-20 roduction and Diversification nvelope Phase Contrast Microscopes and video & digital cameras) IN-UNIVERSITY HORTICULT-6 8678-GO-RFQ / Procurement of computer systems (Deskto Component A: Horticulture P Request for Quota Single Stage - One E IDA / 58380 Post Open - National 17,290.00 0.00 Canceled 2018-07-12 2018-08-20 2019-02-16 ps-04, Laptops-7, Printer-cu roduction and Diversification tions nvelope m-Scanner-8, UPS-5, MS Offic e 2016-11 Nos.) through GeM GOODS PACKAGE-6 / Procur ement of Scientific Equipme nt: GPS, High Precision Weig hing, Microwave, Deep Freez Component A: Horticulture P Request for Quota Single Stage - One E er, Refrigerator, Air Condition IDA / 58380 Post Open - National 99,000.00 24,967.98 Signed 2019-02-16 2019-04-13 2019-11-29 2019-10-10 roduction and Diversification tions nvelope er, Vacuum Cleaner, Thermo meter, Water Bath, Digital Re fractometer, Mixer-cum- Gri nder, Hot Plate, Mixing Machi ne Flame Photometer etc IN-UNIVERSITY HORTICULT-1 19690-GO-RFQ / Establishme nt of Soil and and Plant testin g laboratories in existing trai Component A: Horticulture P Request for Quota Single Stage - One E ning hall building for the dep IDA / 58380 Post Limited 57,806.00 56,494.76 Signed 2019-07-28 2017-10-21 2019-09-22 2018-01-09 2020-03-20 roduction and Diversification tions nvelope artment of Soil Science and Water Management (SSWM) at main campus Nauni, Solan . SH: Civil work along with Mod ule labs GOODS PACKAGE 8 / Farm M Component A: Horticulture P Request for Quota Single Stage - One E achinery ( Tractor with Acces IDA / 58380 Post Limited 29,200.00 20,894.89 Completed 2019-09-30 2019-06-14 2019-11-25 2019-07-04 2020-05-23 2019-08-09 roduction and Diversification tions nvelope sories, Rotavator, Power Tille r, Power Sprayer) GOODS PACKAGE -11 / Porta ble Photosynthesis System, D eep Freezers, Vortex Multipur Component D: Project Mana pose, Shaking Water Bath, H Single Stage - Two E IDA / 58380 gement, Monitoring and Lea Post Request for Bids Open - National 273,000.00 243,172.14 Signed 2020-01-28 2020-01-20 2020-02-02 2020-03-15 2020-02-17 2020-05-28 2020-07-20 2020-07-02 2020-07-21 2020-12-29 ot Air Oven, CHNS Analyzer, nvelope rning Orbital Shaker, Centrifuge, S pectronic 20D, GPS, Elisa Plat e Reader, Fluorescent micros cope, Mite Brushing & Counti ng Machine, etc PACKAGE-14(TEM-GOODS) / Component A: Horticulture P Single Stage - Two E Procurement of Transmission IDA / 58380 Post Request for Bids Open - National 700,000.00 0.00 Canceled 2020-07-30 2020-09-04 2020-08-04 2020-10-07 2020-09-15 2020-11-12 2020-11-28 2021-01-02 2021-07-01 roduction and Diversification nvelope Electron Microscope under co mponent A1.7e PACKAGE-15 ( ULTRAMICRO Component A: Horticulture P Single Stage - Two E TOME-GOODS) / Procurement IDA / 58380 Post Request for Bids Open - National 169,500.00 0.00 Canceled 2020-07-30 2020-09-04 2020-08-04 2020-10-07 2020-09-15 2020-11-12 2020-11-28 2021-01-02 2021-07-01 roduction and Diversification nvelope of Ultramicrotome under Co mponent A1.7e PACKAGE-16 / Procurement Component A: Horticulture P Request for Quota Single Stage - One E Pending Impl of Farm Tool Under Gene Ban IDA / 58380 Post Limited 12,000.00 0.00 2020-12-12 2021-02-06 2021-08-05 roduction and Diversification tions nvelope ementation k and other components (ne ed based) PACKAGE-17 / Procurement Component A: Horticulture P Request for Quota Single Stage - One E IDA / 58380 Post Limited 3,500.00 5,298.70 Signed 2020-12-11 2021-02-11 2021-02-05 2021-04-24 2021-08-04 of Minor Farm Tools roduction and Diversification tions nvelope PACKAGE-18 / Procurement Component A: Horticulture P Request for Quota Single Stage - One E of Various Scientific Equipme IDA / 58380 Post Limited 60,000.00 0.00 Canceled 2020-12-11 2021-02-05 2021-08-04 roduction and Diversification tions nvelope nts under HPHDP PACKAGE-14(RETENDER) TE M-GOODS / Procurement of T Component A: Horticulture P Single Stage - Two E IDA / 58380 Post Request for Bids Open - National 700,000.00 674,229.27 Signed 2021-02-01 2021-02-03 2021-02-06 2021-03-20 2021-03-09 2021-06-02 2021-03-09 2021-07-07 2021-03-21 2022-01-03 ransmission Electron Microsc roduction and Diversification nvelope ope under component A1.7e PACKAGE-15 (RETENDER) UL TRA MICROTOME / Procurem Component A: Horticulture P Single Stage - Two E IDA / 58380 Post Request for Bids Open - National 169,500.00 336,968.99 Signed 2021-02-01 2021-02-03 2021-02-06 2021-03-20 2021-03-09 2021-06-02 2021-03-09 2021-07-07 2021-03-26 2022-01-03 ent of Ultra microtome under roduction and Diversification nvelope component A1.7e N.UHF/HPHDP/PIU/ EQUIPME Component A: Horticulture P Single Stage - Two E NTA/2020 / Purchase of vario IDA / 58380 Post Request for Bids Open - National 120,000.00 0.00 Canceled 2022-05-20 2022-05-21 2022-05-25 2022-06-03 2022-07-06 2022-09-18 2022-10-23 2023-04-21 roduction and Diversification nvelope us scientific instruments GOODS- PURCHASE OF EXPE RT SYSTEM / Installation of E Component A: Horticulture P Request for Quota Single Stage - One E IDA / 58380 Post Limited 12,500.00 0.00 Signed 2022-10-30 2022-01-13 2022-12-25 2023-06-23 xpert System along with soft roduction and Diversification tions nvelope ware for diseases prediction i n Apple. PACKAGE 21 (GOODS) / Proc Component A: Horticulture P Single Stage - Two E Pending Impl urement of various scientific IDA / 58380 Post Request for Bids Open - National 130,000.00 0.00 2023-04-24 2023-04-26 2023-05-24 2023-06-11 2023-06-28 2023-07-28 roduction and Diversification nvelope ementation equipment's NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON-CONSULTING SERVICE Component A: Horticulture P Single Stage - Two E PACKAGE-1 / Engagement of IDA / 58380 Post Request for Bids Open - National 140,000.00 0.00 Canceled 2019-03-11 2019-03-16 2019-04-27 2019-07-10 2019-08-14 2020-02-10 roduction and Diversification nvelope Contractual Labourers (Labo ur Agency) HPHDP PIU UHF NON CONS Component A: Horticulture P Request for Propo Single Stage - Two E UL / Engagement of Contract IDA / 58380 Post Open - National 780,000.00 0.00 Canceled 2017-10-12 2017-10-17 2017-11-28 2018-02-10 2018-03-17 2018-09-13 roduction and Diversification sals nvelope ual Labourers Labour Agency CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 HPHDP PIU UHF CONSULTAN CY / Consultancy services for Component A: Horticulture P Quality And Cost- Open - Internationa IDA / 58380 Post 320,000.00 0.00 Canceled 2019-09-25 2019-10-16 2019-11-29 2019-12-27 2020-01-26 2020-03-01 2020-04-05 2021-04-05 providing international best p roduction and Diversification Based Selection l ractices for rearing of bumbl e bees INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTANCY PACKAGE-3 / Component A: Horticulture P Individual Consult Hiring of individual consultan IDA / 58380 Post Open 72,000.00 0.00 Canceled 2019-01-31 2019-03-21 2019-04-11 2019-05-16 2019-11-12 roduction and Diversification ant Selection t services of Senior Reserch F ellows CONSULTANT PACKAGE-2 / Component A: Horticulture P Individual Consult Hiring of individual consultan IDA / 58380 Post Open 13,000.00 0.00 Canceled 2019-01-31 2019-03-21 2019-04-11 2019-05-16 2019-11-12 roduction and Diversification ant Selection t services of Research Associ ate CONSULTANT PACKAGE-4 / Hiring of individual consultan t services of Technical Assist Component A: Horticulture P Individual Consult IDA / 58380 Post Open 37,000.00 0.00 Canceled 2019-02-15 2019-04-05 2019-04-26 2019-05-31 2019-11-27 ants, Field Assistant, Trained roduction and Diversification ant Selection Pruners, Farm Tool Operators , Technicians, Bee Keeper, D ata Entry Operator etc. Page 4 PROCUREMENT PLAN (Textual Part) Project information: Rwanda, Nile Cooperation for Climate Resilience P- 172848 Project Implementation agency: Nile Equatorial Strategic Action Plan (NELSAP) Date of the Procurement Plan: April 19, 2021 Period covered by this Procurement Plan: April 2021–April 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Nile Basin Procurement and Disposal Manual (for NELSAP, NILE-SEC & ENTRO), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other own procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable. Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] PROCUREMENT Eastern and Southern Africa : Nile Cooperation for Climate Resilience PLAN General Information Country: Eastern and Southern Africa 2021-05-05 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172848 GPN Date: 2021-06-30 Project Name: Nile Cooperation for Climate Resilience Loan / Credit No: TF / B4716 Nile Basin Initiative/Nile Equatorial Lakes Subsidiary Program - Coordination Unit Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-NELSAP-CU-229288-GO- Component 2: Improving Me Request for Quota Single Stage - One E RFQ / Power Backup Uninterr TF / B4716 chanisms for Cooperation in Post Limited 60,000.00 0.00 Canceled 2021-11-02 2021-12-07 2022-02-05 tions nvelope uptible Power Supply the NEL Region Component 2: Improving Me RW-NELSAP-CU-229292-GO- Request for Quota Single Stage - One E TF / B4716 chanisms for Cooperation in Post Limited 39,042.00 0.00 Canceled 2021-12-08 2022-01-26 2022-02-25 RFQ / Furniture/Partitions tions nvelope the NEL Region RW-NELSAP-CU-269734-GO- Component 2: Improving Me Request for Quota Single Stage - One E RFQ / Supply of high end cam TF / B4716 chanisms for Cooperation in Post Limited 8,000.00 0.00 Signed 2022-01-31 2023-03-17 2022-03-07 2022-04-06 tions nvelope era the NEL Region RW-NELSAP-CU-229282-GO- RFB / Supply of Desktops, L aptops, Servers, Data backu Component 2: Improving Me Single Stage - One E p storage, Power Backup stor TF / B4716 chanisms for Cooperation in Post Request for Bids Open - National 213,500.00 172,827.76 Signed 2022-01-26 2022-02-17 2022-02-25 2022-03-11 2022-03-23 2022-03-25 2022-04-03 2022-04-22 2022-08-18 2022-06-21 2022-10-01 nvelope age, Video Conferencing facil the NEL Region ity and Touch Screens/Touch Tables/Decision Theatre, Sca nners/Digitizer/Plotter and a Projector. RW-NELSAP-CU-269738-GO- Component 2: Improving Me Request for Quota Single Stage - One E RFQ / Supply of LAN/WAN/Ro TF / B4716 chanisms for Cooperation in Post Limited 25,000.00 0.00 Signed 2022-03-28 2023-03-17 2022-05-02 2022-06-01 tions nvelope uters/switches for NELSAP CU the NEL Region RW-NELSAP-CU-229297-GO- Component 2: Improving Me Request for Quota Single Stage - One E Under Imple RFQ / IT equipment Maintena TF / B4716 chanisms for Cooperation in Post Limited 50,000.00 0.00 2022-03-07 2023-03-31 2022-04-11 2023-04-11 tions nvelope mentation nce the NEL Region Component 2: Improving Me RW-NELSAP-CU-229295-GO- Request for Quota Single Stage - One E Pending Impl TF / B4716 chanisms for Cooperation in Post Limited 20,000.00 0.00 2022-02-04 2022-03-11 2022-04-10 RFQ / IT/Office Consumables tions nvelope ementation the NEL Region RW-NELSAP-CU-229278-GO- Component 2: Improving Me RFQ / Purchase of Matlab sof Request for Quota Single Stage - One E Pending Impl TF / B4716 chanisms for Cooperation in Post Limited 37,500.00 0.00 2022-03-23 2022-04-27 2022-06-26 tware Licenses and ERDAS I tions nvelope ementation the NEL Region mage Licensing renewal RW-NELSAP-CU-229290-GO- Component 2: Improving Me Request for Quota Single Stage - One E Pending Impl RFQ / Software License (Digit TF / B4716 chanisms for Cooperation in Post Limited 20,000.00 0.00 2022-03-23 2022-04-27 2022-06-26 tions nvelope ementation al archiving & workflow man the NEL Region agement system) RW-NELSAP-CU-332173-GO- Component 2: Improving Me Request for Quota Single Stage - One E RFQ / Supply of multi-functio TF / B4716 chanisms for Cooperation in Post Limited 10,000.00 0.00 Signed 2023-02-21 2023-03-24 2023-03-21 2023-04-11 tions nvelope nal copier the NEL Region RW-NELSAP-CU-332175-GO- Component 2: Improving Me RFQ / Supply and installation Request for Quota Single Stage - One E TF / B4716 chanisms for Cooperation in Post Limited 15,000.00 0.00 Signed 2023-02-21 2023-03-17 2023-03-21 2023-04-11 of Air conditioner in NELSAP- tions nvelope the NEL Region CU Boardroom and Regional Coordinator's office RW-NELSAP-CU-332178-GO- Component 2: Improving Me Request for Quota Single Stage - One E RFQ / NELSAP-CU Boardroom TF / B4716 chanisms for Cooperation in Post Limited 2,000.00 0.00 Signed 2023-02-21 2023-03-17 2023-03-21 2023-04-11 tions nvelope Lighting the NEL Region RW-NELSAP-CU-332179-GO- Component 2: Improving Me Request for Quota Single Stage - One E Pending Impl RFQ / supply and installation TF / B4716 chanisms for Cooperation in Post Limited 3,000.00 0.00 2023-02-21 2023-03-21 2023-04-11 tions nvelope ementation of curtains in NELSAP-CU Boa the NEL Region rdroom NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Improving Me RW-NELSAP-CU-229284-NC- Request for Quota Single Stage - One E TF / B4716 chanisms for Cooperation in Post Limited 40,000.00 0.00 Canceled 2021-11-17 2021-12-25 2022-02-23 RFQ / Cloud Services tions nvelope the NEL Region RW-NELSAP-CU-229070-NC- Component 2: Improving Me DIR / Installation of IFMIS, Da TF / B4716 chanisms for Cooperation in Post Direct Selection Direct 44,000.00 31,400.00 Signed 2021-07-21 2021-09-28 2021-08-04 2021-12-27 2021-09-04 2022-03-07 2022-09-04 ta Migration and software lic the NEL Region ensing RW-NELSAP-CU-229072-NC- Component 2: Improving Me DIR / Development of IPSAS - TF / B4716 chanisms for Cooperation in Post Direct Selection Direct 20,000.00 0.00 Canceled 2021-07-14 2021-07-28 2021-09-01 2022-02-28 General Purpose Financial st the NEL Region atements RW-NELSAP-CU-229368-NC- RFQ / Production/printing/ pu Component 2: Improving Me blication of knowledge produ Request for Quota Single Stage - One E Pending Impl TF / B4716 chanisms for Cooperation in Post Limited 5,000.00 0.00 2021-12-12 2022-01-16 2022-02-15 cts under all thematic areas ( tions nvelope ementation the NEL Region flood & drought risk mitigatio n, dam safety & water qualit y) Page 1 RW-NELSAP-CU-269736-NC- Component 2: Improving Me RFQ / Supply and installation Request for Quota Single Stage - One E TF / B4716 chanisms for Cooperation in Post Limited 8,000.00 0.00 Signed 2022-02-28 2022-09-20 2022-04-04 2022-05-04 of software licences(Office pr tions nvelope the NEL Region oductivity,MS teams,Antiviru s,Adobe) RW-NELSAP-CU-229370-NC- RFQ / Develop/brand corpora Component 2: Improving Me te communication products ( Request for Quota Single Stage - One E Pending Impl TF / B4716 chanisms for Cooperation in Post Limited 15,000.00 0.00 2022-03-07 2022-04-11 2022-06-10 Newsletters, quarterly Projec tions nvelope ementation the NEL Region t briefs, posters, fliers and ba nners) under Platform for Co operation. RW-NELSAP-CU-229364-NC- Component 2: Improving Me Request for Quota Single Stage - One E Pending Impl RFQ / Internet Upgrade at NE TF / B4716 chanisms for Cooperation in Post Limited 36,000.00 0.00 2023-06-26 2023-08-07 2023-09-06 tions nvelope ementation LSAP-CU offices the NEL Region CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-NELSAP-CU-228689-CS- QCBS / Rapid mapping of fre quent flash flood prone areas Component 2: Improving Me in the Nile Basin, Flash Flood Quality And Cost- Open - Internationa TF / B4716 chanisms for Cooperation in Post 528,000.00 396,174.45 Signed 2021-04-30 2021-05-10 2021-05-21 2021-07-16 2021-12-16 2021-07-30 2022-03-16 2021-08-13 2022-03-29 2021-09-06 2022-04-27 2021-09-27 2022-06-08 2024-03-25 Assessment & development Based Selection l the NEL Region of the early warning system and integration of flash flood warning information into IKP (iv) Capacity Building. RW-NELSAP-CU-228692-CS- QCBS / Consultancy services for basin-wide survey of dam Component 2: Improving Me Quality And Cost- Open - Internationa s and preparation of a Nile B TF / B4716 chanisms for Cooperation in Post 506,000.00 416,892.00 Signed 2021-04-25 2021-05-10 2021-05-16 2021-07-11 2022-02-02 2021-07-25 2022-03-25 2021-08-08 2022-04-02 2021-08-29 2022-04-28 2021-09-12 2022-06-08 2024-09-11 Based Selection l asin dam database, Prelimina the NEL Region ry Classification for all Identif ied Dams and Data Analysis & synthesis. RW-NELSAP-CU-229056-CS- Component 2: Improving Me QCBS / Identification of Inves Quality And Cost- Open - Internationa Pending Impleme TF / B4716 chanisms for Cooperation in Post 220,000.00 0.00 2023-09-12 2023-10-03 2023-11-28 2023-12-12 2023-12-26 2024-01-16 2024-02-06 2025-08-04 tment Options for Improved F Based Selection l ntation the NEL Region &D Management RW-NELSAP-CU-229077-CS-L Component 2: Improving Me CS / Consultancy services for Least Cost Selecti TF / B4716 chanisms for Cooperation in Post Open - National 30,000.00 0.00 Canceled 2021-06-02 2021-06-23 2021-08-06 2021-08-13 2021-08-27 2021-09-17 2021-10-15 2021-12-14 external audit of IPSAS - Ge on the NEL Region neral Purpose Financial State ments RW-NELSAP-CU-229078-CS-L Component 2: Improving Me Least Cost Selecti Under Implement CS / External Audit for the NC TF / B4716 chanisms for Cooperation in Post Open - National 20,000.00 0.00 2021-08-11 2022-07-19 2021-09-01 2021-09-29 2022-09-20 2021-10-06 2022-10-25 2021-10-13 2022-11-09 2021-10-27 2021-11-15 2021-12-06 on ation CR Project the NEL Region RW-NELSAP-CU-229075-CS- Component 2: Improving Me CQS / Consultancy services f Consultant Qualifi TF / B4716 chanisms for Cooperation in Post Limited 10,000.00 0.00 Canceled 2021-07-14 2021-07-28 2021-08-27 2021-10-01 2022-03-30 or assets valuation of IPSAS cation Selection the NEL Region - General Purpose Financial S tatements RW-NELSAP-CU-332170-CS- QCBS / First Year Priority trai Component 2: Improving Me Quality And Cost- Open - Internationa nings and Development of Lo TF / B4716 chanisms for Cooperation in Post 81,000.00 0.00 Canceled 2021-07-17 2021-08-07 2021-09-20 2021-10-18 2021-11-17 2021-12-22 2022-01-26 2023-01-26 Based Selection l ng-term dam safety training the NEL Region program for Nile Equatorial L akes Region. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-NELSAP-CU-228696-CS-I NDV / Consultant 1 to undert ake priority trainings based o n the dam safety capacity ga Component 2: Improving Me Individual Consult ps existing in the region and TF / B4716 chanisms for Cooperation in Post Open 88,000.00 81,000.00 Signed 2021-04-27 2021-05-10 2021-06-06 2021-12-31 2021-06-20 2022-02-11 2021-07-18 2022-02-17 2023-04-14 ant Selection development of a longer ter the NEL Region m dam safety training progra m for the NEL Region that wil l be informed by the training needs and capacity assessm ent RW-NELSAP-CU-228698-CS-I NDV / Consultant 2 to undert ake priority trainings based o n the dam safety capacity ga Component 2: Improving Me Individual Consult Under Implement ps existing in the region and TF / B4716 chanisms for Cooperation in Post Open 88,000.00 0.00 2021-04-27 2023-04-05 2021-06-06 2021-06-20 2021-07-18 2023-04-14 ant Selection ation development of a longer ter the NEL Region m dam safety training progra m for the NEL Region that wil l be informed by the training needs and capacity assessm ent RW-NELSAP-CU-228701-CS-I NDV / Assessment of the stat e of dam safety oversight in t Component 2: Improving Me he Seven (7) Nile Equatorial Individual Consult TF / B4716 chanisms for Cooperation in Post Open 220,000.00 115,500.00 Signed 2021-05-03 2021-05-10 2021-06-12 2022-01-04 2021-06-26 2022-03-01 2021-07-24 2022-03-02 2023-07-24 Lakes countries and develop ant Selection the NEL Region ment of DSUs implementatio n guide, a mechanism for est ablishment of DSUs & a strat egy on strengthening of the DSUs. RW-NELSAP-CU-229052-CS-I Component 2: Improving Me NDV / Individual Consultant 2 Individual Consult Under Implement TF / B4716 chanisms for Cooperation in Post Open 66,000.00 0.00 2022-09-19 2021-05-10 2022-10-29 2022-11-12 2022-12-10 2024-09-05 for carrying out practical trai ant Selection ation the NEL Region ning based on DSUs capacity building strategy. RW-NELSAP-CU-228705-CS-I Component 2: Improving Me NDV / Individual Consultant 1 Individual Consult Under Implement TF / B4716 chanisms for Cooperation in Post Open 66,000.00 0.00 2022-09-12 2021-05-10 2022-10-15 2022-10-29 2022-11-26 2024-08-22 for carrying out practical trai ant Selection ation the NEL Region ning based on DSUs capacity building strategy. RW-NELSAP-CU-229063-CS-I Component 2: Improving Me NDV / TA/ Individual Consulta Individual Consult TF / B4716 chanisms for Cooperation in Post Open 211,000.00 183,800.00 Signed 2021-05-10 2021-05-21 2021-06-19 2022-01-05 2021-07-03 2022-02-14 2021-07-31 2022-02-17 2024-07-30 nt - Water Quality Specialist f ant Selection the NEL Region or carrying out Multicriteria A nalysis (MCA) Page 2 RW-NELSAP-CU-229064-CS-I Component 2: Improving Me NDV / TA/ Individual Consulta Individual Consult TF / B4716 chanisms for Cooperation in Post Open 105,600.00 0.00 Signed 2021-05-03 2021-05-21 2021-06-12 2022-10-11 2021-06-26 2022-10-18 2021-07-24 2024-07-23 nt – Modeller for carrying ou ant Selection the NEL Region t Multicriteria Analysis (MCA) RW-NELSAP-CU-229066-CS-I Component 2: Improving Me Individual Consult NDV / Hire of the Regional Da TF / B4716 chanisms for Cooperation in Post Open 300,000.00 45,600.00 Signed 2021-04-22 2021-05-10 2021-06-01 2021-10-20 2021-06-15 2021-11-01 2021-07-13 2021-11-02 2026-07-12 ant Selection m Safety Coordinator the NEL Region RW-NELSAP-CU-229068-CS-I Component 2: Improving Me Individual Consult NDV / Hire of NELSAP Project TF / B4716 chanisms for Cooperation in Post Open 97,272.00 32,000.00 Signed 2021-04-30 2021-05-11 2021-06-14 2021-10-20 2021-06-21 2021-11-01 2021-07-19 2021-11-02 2024-07-18 ant Selection Officer-Mara-RBM the NEL Region RW-NELSAP-CU-229069-CS-I Component 2: Improving Me Individual Consult NDV / Hire of NELSAP Project TF / B4716 chanisms for Cooperation in Post Open 97,272.00 30,000.00 Signed 2021-04-30 2021-05-11 2021-06-14 2021-10-20 2021-06-28 2021-11-01 2021-07-19 2021-11-02 2024-07-18 ant Selection Officer-Kagera-RBM the NEL Region RW-NELSAP-CU-235715-CS-I Component 2: Improving Me Individual Consult NDV / Hire of social safeguar TF / B4716 chanisms for Cooperation in Post Direct 31,710.00 38,052.00 Signed 2021-06-25 2021-07-12 2021-07-05 2021-05-20 2021-07-26 2021-06-01 2021-08-30 2021-06-02 2022-08-30 ant Selection ds specialist the NEL Region RW-NELSAP-CU-240737-CS- Component 2: Improving Me CDS / Project Officer-SMM RB TF / B4716 chanisms for Cooperation in Post Direct Selection Direct 97,272.00 30,000.00 Signed 2021-03-26 2021-11-18 2021-04-05 2021-11-18 2021-05-12 2021-03-06 2024-05-11 M the NEL Region RW-NELSAP-CU-240599-CS- Component 2: Improving Me CDS / Communication Officer TF / B4716 chanisms for Cooperation in Post Direct Selection Direct 109,044.00 33,330.00 Signed 2021-03-26 2021-11-18 2021-04-05 2021-11-18 2021-06-09 2021-09-22 2021-12-06 for NELSAP-CU the NEL Region RW-NELSAP-CU-240594-CS- Component 2: Improving Me CDS / Information, Communic TF / B4716 chanisms for Cooperation in Post Direct Selection Direct 107,020.00 43,500.00 Signed 2021-03-26 2021-11-18 2021-04-05 2021-11-18 2021-06-09 2021-05-27 2021-12-06 ation and Technology Officer the NEL Region for NELSAP-CU RW-NELSAP-CU-240602-CS- Component 2: Improving Me CDS / Water Resources Engin TF / B4716 chanisms for Cooperation in Post Direct Selection Direct 328,090.00 49,956.00 Signed 2021-03-26 2021-11-18 2021-04-05 2021-12-27 2021-06-09 2021-03-20 2026-06-08 eer for NELSAP-CU the NEL Region RW-NELSAP-CU-240736-CS- Component 2: Improving Me CDS / Procurement Specialist TF / B4716 chanisms for Cooperation in Post Direct Selection Direct 159,974.00 63,439.00 Signed 2021-03-26 2021-11-18 2021-04-05 2021-11-18 2021-06-09 2021-03-09 2024-06-08 for NELSAP-CU the NEL Region RW-NELSAP-CU-240744-CS- Component 2: Improving Me CDS / Finance and Administr TF / B4716 chanisms for Cooperation in Post Direct Selection Direct 169,172.00 61,140.00 Signed 2021-03-26 2021-11-18 2021-04-05 2021-11-18 2021-05-31 2020-07-02 2024-05-30 ation Manager for NELSAP-C the NEL Region U RW-NELSAP-CU-240734-CS- Component 2: Improving Me CDS / Program Officer-Water TF / B4716 chanisms for Cooperation in Post Direct Selection Direct 295,692.00 0.00 Canceled 2021-03-26 2021-04-05 2021-06-09 2024-06-08 Resources Management & D the NEL Region evelopment for NELSAP-CU RW-NELSAP-CU-240607-CS- Component 2: Improving Me CDS / Senior Economist/M&E TF / B4716 chanisms for Cooperation in Post Direct Selection Direct 165,256.00 0.00 Canceled 2021-03-26 2021-04-05 2021-06-09 2024-06-08 Specialist for NELSAP-CU the NEL Region RW-NELSAP-CU-240738-CS- Component 2: Improving Me CDS / Water Resources Office TF / B4716 chanisms for Cooperation in Post Direct Selection Direct 328,090.00 0.00 Canceled 2021-03-26 2021-04-05 2021-05-12 2026-05-11 r-GIS/Modeller for NELSAP-CU the NEL Region RW-NELSAP-CU-242964-CS-I Component 2: Improving Me Individual Consult NDV / Senior Economist/M&E TF / B4716 chanisms for Cooperation in Post Open 165,256.00 81,520.00 Signed 2021-01-09 2021-11-18 2021-02-27 2021-06-22 2021-03-20 2021-07-18 2021-04-24 2021-08-06 2022-04-24 ant Selection Specialist for NELSAP-CU the NEL Region RW-NELSAP-CU-242965-CS-I Component 2: Improving Me Individual Consult NDV / Water Resources Offic TF / B4716 chanisms for Cooperation in Post Open 131,236.32 66,609.00 Signed 2021-09-22 2021-08-31 2021-11-10 2022-02-14 2021-12-01 2022-03-13 2022-01-05 2022-03-23 2024-01-05 ant Selection er-GIS/Modeller for NELSAP-C the NEL Region U RW-NELSAP-CU-242966-CS-I Component 2: Improving Me NDV / Program Officer-Water Individual Consult TF / B4716 chanisms for Cooperation in Post Open 118,276.56 76,426.00 Signed 2021-01-09 2021-11-18 2021-02-27 2021-06-23 2021-03-20 2021-07-01 2021-04-24 2021-07-12 2023-04-24 Resources Management & D ant Selection the NEL Region evelopment for NELSAP-CU RW-NELSAP-CU-280271-CS-I Component 2: Improving Me Individual Consult Under Implement NDV / Media Relations Traine TF / B4716 chanisms for Cooperation in Post Open 3,870.00 0.00 2022-03-06 2022-03-04 2022-04-01 2022-04-08 2022-05-06 2022-05-20 ant Selection ation r for Journalists the NEL Region RW-NELSAP-CU-280273-CS-I Component 2: Improving Me Individual Consult Under Implement NDV / Media Relations Traini TF / B4716 chanisms for Cooperation in Post Open 3,870.00 0.00 2022-03-06 2022-03-04 2022-04-01 2022-04-08 2022-04-29 2022-05-13 ant Selection ation ng for NELSAP Staff the NEL Region Component 2: Improving Me RW-NELSAP-CU-280276-CS-I Individual Consult TF / B4716 chanisms for Cooperation in Post Open 3,570.00 0.00 Canceled 2022-03-06 2022-03-04 2022-04-01 2022-04-08 2022-04-23 2022-05-07 NDV / Info Graphics training ant Selection the NEL Region RW-NELSAP-CU-312968-CS-I Component 2: Improving Me NDV / Consultancy services f Individual Consult TF / B4716 chanisms for Cooperation in Post Open - National 10,000.00 0.00 Signed 2022-09-16 2022-09-08 2022-10-12 2022-11-23 2022-10-19 2022-11-27 2022-11-09 2022-12-09 or assets valuation of IPSAS - ant Selection the NEL Region General Purpose Financial St atements RW-NELSAP-CU-332171-CS-I Component 2: Improving Me Individual Consult Open - Internationa Pending Impleme NDV / Recruitment of NELSAP TF / B4716 chanisms for Cooperation in Post 170,000.00 0.00 2022-01-22 2022-03-12 2022-04-02 2022-05-07 2023-05-07 ant Selection l ntation -CU Finance and Administrati the NEL Region on Manager Page 3 1 Procurement plan. Textual part Preamble 1. In accordance with Para.5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (Fourth Edition, dated November 2020) (Procurement Regulations), the Bank's Systematic Tracking and Exchange in Procurement (STEP) system will be used to prepare, finalize and update the Procurement Plans, and conduct all procurement transactions for the Project. 2. This textual partalong with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as requiredunder paragraph 4.4 of the Procurement Regulations are set forth in STEP . 3. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive eprocurement and those contracts as specified in the Procurement Plan tables in STEP. National procurement arrangements 4. In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), procurement under the World Bank financed operations may be carried out in accordance with the “ Tendering with Unlimited Participation” method set forth in the Law of the Republic of Tajikistan "On Public Procurement of Goods, Works and Services", No. 168, dated March 3, 2006 (as amended by Law No. 815, the Law of the Republic of Tajikistan " Introduction of Amendments and Additions to the Law of the Republic of Tajikistan on ‘Public Procurement of Goods, Works and Services", dated April 16, 2012), provided that such arrangements continue to meet requirements of the paragraph 5.4 of the Procurement Regulations and the following conditions: • The request for bids/request for proposals document shall require that bidders/proposes submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, World Bank Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; • The request for bids/request for proposals document, including contract forms acceptable to the Bank shall be used; • The request for bids/request for proposals document and the contract shall provide the right to the Bank to review procurement documentation and activities; • Borrower shall put in place an effective complaints review mechanism and shall disclose the details in all the bidding documents. All complaints shall be recorded by the Borrower in the appropriate tracking and monitoring system, as agreed between the Bank and the Borrower; • No preference shall be applied under competitive following national market approach. 5. Other national procurement arrangements such as tendering with limited participation, request for quotations, direct contracting, may be used on the above stated conditions. 6. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: "Not Applicable". 7. Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations "Not Applicable". 8. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works): "Not Applicable". Procurement plan for the project duration Procurement plan Procure ment Select for the project Estimat Bank Approac ion Evaluation Start/Com ed cost oversig durationContract Title, (in USD) ht h/ Metho Method pletion Description and Competit d Category ion GOODS & NCS Upgrading and expanding 3,100,00 Direct I-2022 – Prior Direct DS the ITMIS functionality 0 Selection IV-2025 Expansion of the Contact Direct I-2022 – Center functionality and its 30,000 Post Direct DS Selection III-2022 integration with ITMIS Substantial Accounting system for small 2,400,00 Internatio RFB compliance I-2022 – and medium-sized Prior 0 nal Open and the lowest IV-2023 businesses estimated cost Substantial SIM-based EDS system 885,000. Internatio compliance II-2022 – Post RFB integrated into ITMIS 00 nal Open and the lowest III-2023 estimated cost Substantial Internatio compliance II-2022 – Electronic labeling of goods 200,000 Post RFB nal Open and the lowest III-2023 estimated cost Substantial Module for end-to-end Internatio compliance III-2024 – monitoring of the gambling 195,000 Post RFB nal Open and the lowest II-2025 business entities estimated cost Procurement plan Procure ment Select for the project Estimat Bank Approac ion Evaluation Start/Com ed cost oversig durationContract Title, (in USD) ht h/ Metho Method pletion Description and Competit d Category ion GOODS & NCS Substantial Training module for the tax Internatio compliance III-2022 – 300,000 Post RFB officials and taxpayers nal Open and the lowest II-2023 estimated cost Substantial Multilingual electronic Tax National compliance III-2021 – 60,000 Post RFQ Code Open and the lowest IV-2022 estimated cost Substantial Development of a discussion National compliance III-2021 – 30,000 Post RFQ platform for taxpayers Open and the lowest IV-2022 estimated cost Development and implementation of Substantial "Taxpayer", an interactive Internatio compliance III-2022 – 400,000 Post RFB electronic application for nal Open and the lowest IV-2023 mobile devices based on estimated cost Android and IOS platforms On the side of the Ministry of Finance, development of a unified inter-agency Substantial information and analysis 1,163,00 Internatio compliance III-2022 – Post RFB system for automation of 0 nal Open and the lowest IV-2023 accounting, forecasting and estimated cost analysis of government revenues Hardware and software Substantial supply for an analytical National compliance III-2022 – 200,000 Post RFB system based on big data Open and the lowest IV-2023 analysis estimated cost 8,963,0 Total: 00 Procure ment Contract Title, Estimat Bank Selecti Approac Evaluation Start/Com Description and ed cost oversig on h/ Method pletion Category (in USD) ht Method Competit ion CONSULTANTS - FIRMS Development of requirements to a SIM-based Internatio Based on IV-2021 – electronic digital signature 100,000 Post nal CQS qualifications I 2022 (EDS) system integrated into Open ITMIS Preparation of strategy and Internatio requirements for the Based on IV-2021 – 75,000 Post nal CQS implementation of electronic qualifications I 2022 Open labeling Procure ment Contract Title, Estimat Bank Selecti Approac Evaluation Start/Com Description and ed cost oversig on h/ Method pletion Category (in USD) ht Method Competit ion CONSULTANTS - FIRMS Development of approaches and requirements to the Internatio continuous training and Based on I-2022 – 45,000 Post nal CQS advanced training of the Tax qualifications II-2022 Open Committee employees and taxpayers Development of requirements to the Internatio Based on IV-2021 – accounting system for small 100,000 Post nal CQS qualifications I 2022 and medium-sized Open enterprises Development of requirements to the integraed modules, customized API for the Internatio Based on IV-2021 – purpose of integrating 60,000 Post nal CQS qualifications I 2022 electronic services and data Open exchange module, taking into account data security requirements Internatio Based on IV-2022 – Taxpayer Survey 100,000 Post nal CQS qualifications IV - 2025 Open Block I-2022 – Financial Audit of the Project 75,000 Post LCS Block audit audit I-2027 Internatio DLI/DLR achievement Based on IV-2022 – 75,000 Post nal CQS verification agent qualifications IV-2024 Open Total: 630,000 Procurem Review ent Select Contract Title, Estimat by the Approach ion Evaluation Start and Description and ed cost World / Metho Method End Category (in USD) Bank Competiti d on INDIVIDUAL CONSULTANTS Supporting the integration of continuous and advanced Internatio Based on III-2022 – training system of 7,000 Post nal IC qualifications II-2023 employees and taxpayers Open and HRMIS Procurem Review ent Select Contract Title, Estimat by the Approach ion Evaluation Start and Description and ed cost World / Metho Method End Category (in USD) Bank Competiti d on INDIVIDUAL CONSULTANTS Development of training modules for continuous and National Based on advanced training of 50,000 Post IC Open qualifications employees based on the needs and training strategy Development of training National Based on modules for the taxpayers’ 50,000 Post IC Open qualifications distance learning Development of requirements to the creation Internatio Based on of a multilingual electronic 10,000 Post nal IC III-2021 qualifications Tax Code and the taxpayers Open discussion platform Development of requirements to the unified inter-agency information and Internatio analysis system for Based on I-2022 – 30,000 Post nal IC automation of accounting, qualifications III-2022 Open forecasting and analysis of government revenues Analysis and consolidation of Direct III-2021 – requirements to the 200,000 Post Direct1 DS Selection- IV-2024 information systems Internatio International IT Procurement Based on I-2022 – 60,000 Post nal IC Consultant qualifications III-2023 Open Total: 407,000 1 Mr. Aare Lapynin was involved in drafting the requirements and the implementation of ITMIS and the call-center under TARP. In addition, this expert is a certified TADAT specialist and was directly involved in the implementation of the tax information system in Estonia, as well as in other former Soviet Union countries and of the Eastern Europe. This combination of international and local experience and knowledge is of exceptional value for the Project and meeting the specific requirements for the upgrade of existing information systems, especially when providing remote services in the event of possible restrictions of movement and/or quarantine caused by a pandemic. Mr. Aare Lapynin was selected on a competitive basis and demonstrated the high quality of services. PROCUREMENT Tajikistan : Tax Reform Operation PLAN General Information Country: Tajikistan 2022-07-13 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171892 GPN Date: 2022-07-11 Project Name: Tax Reform Operation Loan / Credit No: IDA / D8350 Tax Committee of the Republic of Tajikistan Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TRO/D8350/RFB/2022/01 / A Open - Internationa Single Stage - One E Pending Impl ccounting system for small a IDA / D8350 Prior Request for Bids 2,400,000.00 0.00 2022-08-22 2022-08-29 2022-10-10 2022-11-09 2022-12-14 2023-01-09 l nvelope ementation nd medium-sized businesses TRO/D8350/DS/2022/02 / Ex Direct - Internation Pending Impl pansion of the Contact Cente IDA / D8350 Post Direct Selection 30,000.00 0.00 2022-07-20 2022-07-25 2022-08-29 2022-10-28 al ementation r functionality and its integra tion with ITMIS TRO/D8350/DS/2022/01 / Up Direct - Internation grading and expanding the IT IDA / D8350 Prior Direct Selection 3,100,000.00 0.00 Signed 2022-07-20 2022-07-28 2022-07-25 2022-10-10 2022-08-29 2025-07-14 al MIS functionality TRO/D8350/RFB/2022/02 / Pr Open - Internationa Single Stage - One E Pending Impl ocurement of SIM-based EDS IDA / D8350 Post Request for Bids 885,000.00 0.00 2022-10-03 2022-10-08 2022-11-19 2022-12-19 2023-01-23 2023-07-22 l nvelope ementation system integrated into ITMIS TRO/D8350/RFB/2023/03 / Pr Open - Internationa Single Stage - One E Pending Impl ocurement of Electronic label IDA / D8350 Post Request for Bids 200,000.00 0.00 2022-10-17 2022-10-22 2022-12-03 2023-01-02 2023-02-06 2023-10-24 l nvelope ementation ing of goods TRO/D8350/RFB/2023/04 / Pr ocurement of Module for end Open - Internationa Single Stage - One E Pending Impl IDA / D8350 Post Request for Bids 195,000.00 0.00 2023-01-16 2023-01-21 2023-03-04 2023-04-03 2023-05-08 2024-01-23 -to-end monitoring of the ga l nvelope ementation mbling business entities TRO/D8350/RFB/2023/05 / Pr Open - Internationa Single Stage - One E Pending Impl ocurement of training modul IDA / D8350 Post Request for Bids 300,000.00 0.00 2023-04-20 2023-04-25 2023-06-06 2023-07-06 2023-08-10 2024-04-26 l nvelope ementation e for the tax officials and tax payers TRO/D8350/RFQ/2023/06 / P Request for Quota Single Stage - One E Pending Impl rocurement of Multilingual el IDA / D8350 Post Open - National 60,000.00 0.00 2023-05-03 2023-06-28 2024-03-14 tions nvelope ementation ectronic Tax Code TRO/D8350/RFQ/2023/07 / D Request for Quota Single Stage - One E Pending Impl evelopment of a discussion p IDA / D8350 Post Open - National 30,000.00 0.00 2023-05-03 2023-06-28 2023-06-30 tions nvelope ementation latform for taxpayers TRO/D8350/RFB/2023/08 / D evelopment and implementa Open - Internationa Single Stage - One E Pending Impl tion of "Taxpayer", an interac IDA / D8350 Post Request for Bids 400,000.00 0.00 2023-06-02 2023-06-07 2023-07-19 2023-08-18 2023-09-22 2024-06-08 l nvelope ementation tive electronic application for mobile devices based on And roid and IOS platforms TRO/D8350/RFB/2022/09 / O n the side of the Ministry of F inance, development of a uni Open - Internationa Single Stage - One E Pending Impl fied inter-agency information IDA / D8350 Post Request for Bids 1,163,000.00 0.00 2023-04-28 2023-05-03 2023-06-14 2023-07-14 2023-08-18 2024-05-04 l nvelope ementation and analysis system for auto mation of accounting, foreca sting and analysis of govern ment revenues TRO/D8350/RFB/2023/10 / H ardware and software supply Single Stage - One E Pending Impl IDA / D8350 Post Request for Bids Open - National 200,000.00 0.00 2023-06-29 2023-07-04 2023-08-15 2023-09-14 2023-10-19 2024-07-05 for an analytical system base nvelope ementation d on big data analysis TRO/D8350/RFB/2023/01 / H Request for Quota Single Stage - One E Under Imple IDA / D8350 Post Limited 18,756.00 0.00 2023-06-14 2023-06-09 2023-08-09 2024-02-05 ard disks the data storage sy tions nvelope mentation stem NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TRO/D8350/CQS/2022/01-01 Consultant Qualifi / DLI/DLR achievement verific IDA / D8350 Post Open - National 17,000.00 0.00 Canceled 2022-11-03 2022-11-21 cation Selection ation agent 2.1 and 2.2 TRO/D8350/CQS/2022/02 / D evelopment of requirements Consultant Qualifi Open - Internationa Pending Impleme IDA / D8350 Post 100,000.00 0.00 2022-09-15 2022-10-06 2022-11-19 2022-12-19 2023-01-23 2023-10-20 to a SIM-based electronic digi cation Selection l ntation tal signature (EDS) system in tegrated into ITMIS Page 1 TRO/D8350/CQS/2022/03 / P reparation of strategy and re Consultant Qualifi Open - Internationa Pending Impleme IDA / D8350 Post 75,000.00 0.00 2022-09-25 2022-10-16 2022-11-29 2022-12-29 2023-02-02 2023-10-30 quirements for the implemen cation Selection l ntation tation of electronic labeling TRO/D8350/CQS/2022/04 / D evelopment of approaches a nd requirements to the conti Consultant Qualifi Open - Internationa Pending Impleme IDA / D8350 Post 45,000.00 0.00 2022-10-03 2022-10-24 2022-12-07 2023-01-06 2023-02-10 2023-08-09 nuous training and advanced cation Selection l ntation training of the Tax Committe e employees and taxpayers TRO/D8350/CQS/2022/05 / D evelopment of requirements Consultant Qualifi Open - Internationa Pending Impleme IDA / D8350 Post 100,000.00 0.00 2022-10-10 2022-10-31 2022-12-14 2023-01-13 2023-02-17 2023-08-16 to the accounting system for cation Selection l ntation small and medium-sized ente rprises TRO/D8350/CQS/2022/06 / D evelopment of requirements to the integraed modules, cu Consultant Qualifi Open - Internationa Pending Impleme stomized API for the purpose IDA / D8350 Post 60,000.00 0.00 2022-10-25 2022-11-15 2022-12-29 2023-01-28 2023-03-04 2023-08-31 cation Selection l ntation of integrating electronic servi ces and data exchange modu le, taking into account data s ecurity requirements TRO/D8350/CQS/2022/07 / T Consultant Qualifi Open - Internationa IDA / D8350 Post 100,000.00 0.00 Signed 2022-09-22 2022-11-02 2022-10-13 2022-11-04 2022-11-26 2023-02-17 2022-12-26 2023-03-06 2023-01-30 2025-09-16 axpayer Survey cation Selection l TRO/D8350/CQS/2022/01-01 Consultant Qualifi Open - Internationa A / DLI/DLR achievement veri IDA / D8350 Post 17,000.00 0.00 Completed 2022-11-21 2023-02-01 2022-12-12 2023-01-25 2022-02-14 2023-02-24 2022-03-11 2023-03-31 2023-09-27 cation Selection l fication agent 2.1 and 2.2 TRO/D8350/CQS/2022/01-02 Consultant Qualifi Open - Internationa / DLI/DLR achievement verific IDA / D8350 Post 30,000.00 0.00 Completed 2022-11-21 2023-02-01 2022-12-12 2023-01-25 2022-11-11 2023-02-24 2022-11-25 2023-03-31 2023-09-27 2023-03-12 cation Selection l ation agent 6.1 and 7.1 TRO/D8350/CQS/2022/01 / D Consultant Qualifi IDA / D8350 Post Open - National 28,000.00 0.00 Canceled 2023-09-22 2027-01-02 LI/DLR achievement verificati cation Selection on agent TRO/D8350/CQS/2023/08 / tr aining for Tax Committee em Consultant Qualifi Under Implement IDA / D8350 Post Open - National 30,000.00 0.00 2023-06-16 2023-06-23 2023-07-07 2023-08-20 2023-09-19 2023-10-24 2024-04-21 ployees (Tax monitoring; Tra cation Selection ation nsfer pricing; Risks) TRO/D8350/CQS/2023/01 / D Consultant Qualifi Under Implement IDA / D8350 Post Open - National 28,000.00 0.00 2023-06-05 2023-06-21 2023-06-26 2023-08-09 2023-09-08 2023-10-13 2026-12-30 LI/DLR achievement verificati cation Selection ation on agent INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TRO/D8350/IC/2022/001 / Int Individual Consult Open - Internationa IDA / D8350 Post 60,000.00 0.00 Signed 2022-07-24 2022-11-01 2022-09-11 2023-03-03 2022-10-02 2023-03-03 2022-11-06 2024-01-30 ernational IT Procurement Co ant Selection l nsultant TRO/D8350/IC/2022/002 / D evelopment of requirements to the unified inter-agency in Individual Consult Open - Internationa Pending Impleme IDA / D8350 Post 30,000.00 0.00 2022-09-15 2022-11-03 2022-11-24 2022-12-29 2023-04-28 formation and analysis syste ant Selection l ntation m for automation of accounti ng, forecasting and analysis of government revenues TRO/D8350/IC/2022/003 / An Individual Consult Direct - Internation Pending Impleme alysis and consolidation of re IDA / D8350 Post 200,000.00 0.00 2022-10-31 2022-11-10 2022-12-01 2023-01-05 2024-11-05 ant Selection al ntation quirements to the informatio n systems TRO/D8350/IC/2022/004 / D evelopment of requirements Individual Consult Open - Internationa Pending Impleme to the creation of a multiling IDA / D8350 Post 10,000.00 0.00 2022-11-01 2022-12-20 2023-01-10 2023-02-14 2023-05-15 ant Selection l ntation ual electronic Tax Code and t he taxpayers discussion platf orm TRO/D8350/IC/2022/005 / D evelopment of training modu Individual Consult Pending Impleme les for continuous and advan IDA / D8350 Post Open - National 50,000.00 0.00 2022-10-25 2022-12-13 2023-01-03 2023-02-07 2023-08-06 ant Selection ntation ced training of employees ba sed on the needs and trainin g strategy TRO/D8350/IC/2022/006 / D Individual Consult Pending Impleme evelopment of training modu IDA / D8350 Post Open - National 50,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2023-07-28 ant Selection ntation les for the taxpayers’ distanc e learning TRO/D8350/IC/2022/007 / Su pporting the integration of co Individual Consult Open - Internationa Pending Impleme IDA / D8350 Post 7,000.00 0.00 2022-11-21 2023-01-09 2023-01-30 2023-03-06 2023-04-08 ntinuous and advanced traini ant Selection l ntation ng system of employees and taxpayers and HRMIS Page 2 PLAN DE PASSATION DE MARCHÉS Projet : Projet pour promouvoir l’offre de logements abordables dans l’espace UEMOA - assistance technique pour soutenir les politique d’offre de logements - Composante 3 Agence d’exécution du Projet : Commission de l’UEMOA Date du plan de passation des marchés : 15 Mars 2018 Période couverte par ce plan de passation des marchés : 2018-2019 Preambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016) (“Règlement de Passation des Marchés”) l’Emprunteur utilise les outils électroniques de planification et de suivi de la passation des marchés (STEP) pour préparer, valider et actualiser ses plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Cette partie textuelle ainsi que les tableaux du plan de passation des marchés dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types d’appel d’offres publiés par la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale ainsi que pour tous les autres contrats spécifiés dans les tableaux du plan de passation des marchés inclus dans STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, au cas où la procédure de passation des marchés est retenue (telle que spécifiée dans les tableaux du plan de passation des marchés inclus dans STEP), les procédures de passation de marchés du pays considéré peuvent être appliquées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans le code des marchés publics (règlement d’exécution N° 008/2014/ COM/UEMOA relatif aux règles de passation, d’exécution et de réception des marchés des organes de l’UEMOA), ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés. Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués dans le Plan de passation des marchés. « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas Travaux : ne s’applique pas Autres informations pertinentes sur la passation des marchés « Sans objet ». PROCUREMENT Western and Central Africa : WAEMU Affordable Housing Finance PLAN General Information Country: Western and Central Africa 2018-05-27 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161658 GPN Date: 2018-03-13 Project Name: WAEMU Affordable Housing Finance Loan / Credit No: IDA / D2360 Caisse Regionale de Refinancement Hypothecaire Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-CRRH-214356-GO-RFQ / Technical Assistance for Non ACQUISITION DE MATERIEL E Request for Quota Single Stage - One E IDA / D2360 -Bank Financial Institutions a Post Limited 80,000.00 0.00 Canceled 2021-02-08 2021-04-12 2021-06-11 T AMENAGEMENT D’UNE SAL tions nvelope nd CRRH LE INFORMATIQUE POUR LA CRRH-UEMOA TG-CRRH-214356-GO-RFQ-2 / Acquisition de matériels inf Technical Assistance for Non Request for Quota Single Stage - One E ormatiques, d'un robot de sa IDA / D2360 -Bank Financial Institutions a Post Limited 77,000.00 109,627.91 Signed 2022-03-25 2022-04-14 2022-05-20 2022-06-14 2022-07-19 tions nvelope uvegarde plus les accessoire nd CRRH s (y compris les services aprè s-vente) TG-CRRH-283645-GO-RFQ / Technical Assistance for Non Fourniture et installation de Request for Quota Single Stage - One E IDA / D2360 -Bank Financial Institutions a Post Limited 20,000.00 0.00 Canceled 2022-03-25 2022-05-20 2022-07-19 Caméra de vidéosurveillance tions nvelope nd CRRH et contrôle d’accès par badg e et empreinte digitale TG-CRRH-283643-GO-RFQ / Aménagement de la salle inf Technical Assistance for Non ormatique de la CRRH-UEMO Request for Quota Single Stage - One E Under Imple IDA / D2360 -Bank Financial Institutions a Post Limited 50,000.00 0.00 2022-03-25 2022-03-16 2022-05-20 2022-07-19 A : achat et installation de cli tions nvelope mentation nd CRRH matiseurs, porte coupe-feu, f aux plancher, extincteur, gr oupe électrogène et onduleu r TG-CRRH-362764-GO-RFQ / FOURNITURE ET INSTALLATIO Technical Assistance for Non Request for Quota Single Stage - One E Under Imple N D’UN SYSTEME DE CONTR IDA / D2360 -Bank Financial Institutions a Post Open - National 27,000.00 0.00 2023-05-30 2023-07-25 2023-08-24 tions nvelope mentation ÔLE D’ACCES ET DE VIDEOSU nd CRRH RVEILLANCE A LA CRRH-UEM OA NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-CRRH-63754-NC-DIR / Un e Agence conseil en commun Participating Banks Mortgag Request for Quota Single Stage - One E IDA / D2360 Post Limited 58,613.00 39,209.04 Completed 2018-08-25 2018-06-04 2018-10-20 2018-07-03 2019-04-18 2018-09-26 ication pour la préparation d e Refinancing tions nvelope u lancement du projet Banqu e mondiale/UEMOA TG-CRRH-58272-NC-DIR / 1 s oftware pour adapter le syste me comptable IBIS aux nouv Participating Banks Mortgag IDA / D2360 Post Direct Selection Direct 81,500.00 77,688.07 Completed 2018-06-24 2018-06-24 2018-06-29 2018-07-10 2018-08-03 2018-10-30 2019-01-30 2018-11-09 elles réformes BCEAO (Bâle 2 e Refinancing /3 et PCB révisé) et à la gesti on du projet Banque mondial e/UEMOA TG-CRRH-116117-NC-DIR / R Affordable Housing Policies T éalisation d'une Vidéo utilisat IDA / D2360 Post Direct Selection Direct 11,000.00 8,862.78 Completed 2019-05-23 2019-05-24 2019-05-28 2019-05-27 2019-07-02 2019-06-03 2019-12-29 2019-12-09 echnical Assistance eurs pour la CRRH-UEMOA TG-CRRH-127286-NC-DIR / O RGANISATION DE LA CONFER Affordable Housing Policies T ENCE CRRH-UEMOA/BANQUE IDA / D2360 Post Direct Selection Direct 6,000.00 5,888.23 Completed 2019-08-23 2019-08-27 2019-08-23 2019-08-30 2019-09-20 2019-09-02 2020-03-18 2019-10-11 echnical Assistance MONDIALE SUR LES POLITIQU ES DE L’HABITAT ET LA CROI SSANCE ECONOMIQUE TG-CRRH-241473-NC-DIR / O RGANISATION DE LA CAMPAG NE DE PROMOTION DU REFIN ANCEMENT DES SFD, AVEC L Affordable Housing Policies T IDA / D2360 Post Direct Selection Direct 40,000.00 37,518.62 Completed 2021-07-12 2021-06-23 2021-07-12 2021-06-25 2021-07-20 2021-07-03 2022-01-16 2022-01-13 A PREMIERE SIGNATURE D’U echnical Assistance N CONTRAT DE REFINANCEM ENT AVEC UN SFD AU SENEG AL ET LA RENCONTRE AVEC L ES SFD DU SENEGAL TG-CRRH-333807-NC-RFQ / I Technical Assistance for Non MPLEMENTATION ET SECURIS Request for Quota Single Stage - One E IDA / D2360 -Bank Financial Institutions a Post Limited 40,000.00 0.00 Signed 2023-01-07 2023-01-09 2023-01-27 2023-02-26 ATION D’UNE NOUVELLE ARC tions nvelope nd CRRH HITECTURE RESEAU POUR LA CRRH-UEMOA TG-CRRH-364709-NC-RFQ / Technical Assistance for Non PRESTATION DE MAINTENAN Request for Quota Single Stage - One E Pending Impl IDA / D2360 -Bank Financial Institutions a Post Open - National 37,000.00 0.00 2023-06-17 2023-07-29 2023-12-08 CE DU PARC INFORMATIQUE tions nvelope ementation nd CRRH ET SUIVI DU SYSTEME RESEA U DE LA CRRH-UEMOA CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 TG-CRRH-58265-CS-QCBS / 1 firme de consultant pour fa ire l'état des lieux du finance ment du logement par les SF Participating Banks Mortgag Quality And Cost- Open - Internationa D, identifier des SFD éligibles IDA / D2360 Post 400,000.00 89,738.00 Completed 2018-06-28 2018-08-12 2018-07-19 2018-08-24 2018-09-01 2018-11-20 2018-09-29 2019-01-08 2018-10-29 2019-03-13 2018-12-03 2019-06-14 2019-01-07 2019-07-18 2020-01-07 2020-04-14 e Refinancing Based Selection l , et structurer la fenêtre d'ac cès au refinancement des SF D - critères, conditions d'éligi bilité, coût ... + rédiger tous les documents TG-CRRH-58292-CS-CQS / 1 bureau d'études pour conduir Participating Banks Mortgag Quality And Cost- Open - Internationa e des ateliers sur le risque en IDA / D2360 Post 200,000.00 157,289.16 Completed 2018-06-26 2018-08-03 2018-07-17 2018-09-04 2018-08-30 2018-11-20 2018-09-27 2019-01-03 2018-10-27 2019-02-06 2018-12-01 2019-03-06 2019-01-05 2019-04-15 2020-01-05 2021-05-04 e Refinancing Based Selection l vironnemental et social et for mer les institutions financier es sur ce risque TG-CRRH-58348-CS-CQS / 1 firme de consultants pour 1.E valuer la faisabilité d'un prod Technical Assistance for Non uit de garantie régional et fai Quality And Cost- Open - Internationa IDA / D2360 -Bank Financial Institutions a Post 400,000.00 416,976.50 Completed 2018-06-25 2019-03-05 2018-07-16 2019-03-11 2018-08-29 2019-05-23 2018-09-26 2019-06-24 2018-10-26 2019-08-08 2018-11-30 2019-12-23 2019-01-04 2020-03-27 2020-01-04 2021-09-10 re des propositions d'options Based Selection l nd CRRH 2.rédiger la structure, gouver nance et pricing de ce produi t et le plan d'affaires après u n atelier afin de choisir la me illeure opt TG-CRRH-73025-CS-QCBS / Technical Assistance for Non Assistant à Maîtrise d'ouvrag Quality And Cost- Open - Internationa IDA / D2360 -Bank Financial Institutions a Post 58,500.00 175,049.81 Signed 2018-08-07 2018-08-03 2018-08-28 2018-09-03 2018-10-11 2018-11-20 2018-11-08 2019-01-03 2018-12-08 2019-01-14 2019-01-12 2019-01-31 2019-02-16 2019-04-08 2020-02-16 e (AMOA) pour la nouvelle ap Based Selection l nd CRRH plication de gestion des refin ancements TG-CRRH-102015-CS-QCBS / Technical Assistance for Non Quality And Cost- Open - Internationa Etude d'impact sur les financ IDA / D2360 -Bank Financial Institutions a Post 200,000.00 246,415.83 Completed 2019-04-01 2019-04-02 2019-04-22 2019-04-04 2019-06-05 2019-07-15 2019-07-03 2019-08-26 2019-08-02 2019-09-06 2019-09-06 2020-02-21 2019-10-11 2020-03-19 2020-10-10 2021-02-25 Based Selection l ements sur ressources de ma nd CRRH rché TG-CRRH-102022-CS-QCBS / Technical Assistance for Non Quality And Cost- Open - Internationa IDA / D2360 Post 150,000.00 233,740.50 Signed 2019-03-15 2019-05-23 2019-04-05 2019-07-08 2019-05-19 2019-09-09 2019-06-16 2019-10-09 2019-07-16 2020-01-23 2019-08-20 2020-03-11 2019-09-24 2020-05-13 2020-09-23 Etude sur le crédit-bail immo -Bank Financial Institutions a Based Selection l bilier nd CRRH TG-CRRH-101905-CS-CQS / 1 firme de consultant pour acc Technical Assistance for Non ompagner les SFD presenties Consultant Qualifi Open - Internationa IDA / D2360 -Bank Financial Institutions a Post 225,000.00 0.00 Canceled 2019-04-30 2019-05-21 2019-07-04 2019-08-03 2019-09-07 2020-03-05 pour accéder à la fenetre de cation Selection l nd CRRH refinancement et respecter l es conditions d'éligiblité, not amment prudentielle TG-CRRH-101908-CS-QCBS / 1 firme de consultant pour ac compagner les SFD a dévelo Technical Assistance for Non Quality And Cost- Open - Internationa pper des méthodes de crédit IDA / D2360 -Bank Financial Institutions a Post 228,000.00 0.00 Canceled 2019-04-30 2019-05-21 2019-07-04 2019-08-01 2019-08-31 2019-10-05 2019-11-09 2020-11-08 Based Selection l pour le secteur informel (not nd CRRH amment numériques) , et ren forcer leur capacité de gestio n du risque TG-CRRH-101909-CS-QCBS / Une firme de consultant pour accompagner la mise en plac Design of Regional Guarante Quality And Cost- Open - Internationa e du produit de garantie : arr IDA / D2360 Post 400,000.00 0.00 Canceled 2019-04-15 2019-05-06 2019-06-19 2019-07-17 2019-08-16 2019-09-20 2019-10-25 2020-10-24 e Product for Housing Loans Based Selection l angements contractuels, règl es et procédures, sensibilisat ion et renforcement des capa cités des bénéficiaires TG-CRRH-72930-CS-QCBS / Technical Assistance for Non Quality And Cost- Open - Internationa Un software pour la gestion d IDA / D2360 -Bank Financial Institutions a Post 200,000.00 0.00 Canceled 2018-08-22 2018-08-02 2018-09-12 2018-09-03 2018-10-26 2018-11-20 2018-11-23 2019-01-03 2018-12-23 2019-06-04 2019-01-27 2019-03-03 2020-03-02 Based Selection l es refinancements des banqu nd CRRH es et des SFD TG-CRRH-102031-CS-CQS / Technical Assistance for Non Accompagnement CRRH-UEM Consultant Qualifi Open - Internationa IDA / D2360 -Bank Financial Institutions a Post 60,000.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-05 2019-08-09 2020-02-05 OA vers une notation financi cation Selection l nd CRRH ère internationale TG-CRRH-102020-CS-QCBS / Technical Assistance for Non Quality And Cost- Open - Internationa Etude d'impact sur les financ IDA / D2360 -Bank Financial Institutions a Post 200,000.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-10-10 Based Selection l ements sur ressources conce nd CRRH ssionnelles TG-CRRH-72930-CS-QCBS-2 Technical Assistance for Non / MISE EN PLACE D'UNE APPLI Quality And Cost- Open - Internationa IDA / D2360 -Bank Financial Institutions a Post 450,000.00 484,946.91 Signed 2019-12-18 2019-12-17 2020-01-08 2019-12-23 2020-02-21 2020-03-06 2020-03-20 2020-04-10 2020-04-19 2020-05-12 2020-05-24 2020-05-25 2020-06-28 2020-09-01 2020-12-25 CATION DE GESTION DES RE Based Selection l nd CRRH FINANCEMENTS DES BANQUE S ET SFD TG-CRRH-181721-CS-CQS / RECRUTEMENT D’UN CABINE Technical Assistance for Non T CONSEIL POUR LE DIAGNO Consultant Qualifi IDA / D2360 -Bank Financial Institutions a Post Limited 200,000.00 125,920.35 Signed 2020-07-21 2020-07-22 2020-07-28 2020-08-21 2020-08-04 2020-12-04 2020-08-18 2020-12-15 2021-08-18 STIC DES BESOINS D’ASSIST cation Selection nd CRRH ANCE TECHNIQUE AUX SFD R EFINANCES PAR LA CRRH-UE MOA TG-CRRH-254898-CS-CQS / UN SWAP ADVISOR POUR LA MISE EN PLACE D’UN SWAP D Affordable Housing Policies T Consultant Qualifi OLLAR/EURO DANS LE CADR IDA / D2360 Post Limited 120,000.00 39,469.50 Completed 2021-09-27 2021-09-23 2021-10-11 2021-10-13 2021-10-25 2021-10-15 2021-11-15 2021-10-19 2022-03-15 2022-04-26 echnical Assistance cation Selection E DE L’OPERATION D’EMISSI ON OBLIGATAIRE DE LA CRR H-UEMOA SUR LE MARCHE FI NANCIER AMERICAIN TG-CRRH-263296-CS-CQS / F ORMATION DU PERSONNEL D Affordable Housing Policies T Consultant Qualifi E LA CRHH-UEMOA SUR LA G IDA / D2360 Post Limited 30,000.00 0.00 Canceled 2021-11-18 2021-12-10 2021-12-02 2022-01-01 2022-02-05 2022-08-04 echnical Assistance cation Selection ESTION DU SWAP DE COUVE RTURE DE RISQUE DE CHANG E TG-CRRH-101905-CS-CQS-2 / UN CABINET CONSEIL POUR LE DIAGNOSTIC DES BESOIN Technical Assistance for Non Consultant Qualifi Open - Internationa S EN ASSISTANCE TECHNIQU IDA / D2360 -Bank Financial Institutions a Post 290,000.00 0.00 Signed 2021-11-22 2021-11-25 2022-01-10 2021-11-26 2022-03-11 2022-05-23 2022-04-01 2022-09-12 2022-05-13 2023-05-08 cation Selection l E DES SFD ET DES BANQUES nd CRRH ACTIONNAIRES REFINANCEES DE LA CRRH-UEMOA ET POUR LEUR ACCOMPAGNEMENT TG-CRRH-271802-CS-CQS / RECRUTEMENT D’UN CONSU Affordable Housing Policies T Consultant Qualifi LTANT POUR L’EVALUATION IDA / D2360 Post Limited 100,000.00 87,531.40 Signed 2022-01-11 2022-01-18 2022-01-21 2022-04-14 2022-02-05 2022-05-20 2022-02-15 2022-07-08 2022-05-16 echnical Assistance cation Selection DES NORMES PRUDENTIELLE S APPLICABLES A LA CRRH-U EMOA Page 2 TG-CRRH-352156-CS-CQS / UN CONSULTANT (AMOA) PO UR ASSISTER LA CRRH-UEMO A DANS LA REDACTION DES Technical Assistance for Non TERMES DE REFERENCE POU Consultant Qualifi IDA / D2360 -Bank Financial Institutions a Post Limited 90,000.00 0.00 Canceled 2023-04-24 2023-05-08 2023-05-22 2023-05-27 2023-06-26 R LES PRESTATIONS DE SERV cation Selection nd CRRH ICES INFORMATIQUES ET L’EL ABORATION DES SPECIFICATI ONS TECHNIQUES POUR LES ACQUISITIONS DE MATERIELS ET LOGICIELS INFORMATIQUE S TG-CRRH-363684-CS-CQS / UN CONSULTANT (AMOA) PO UR ASSISTER LA CRRH-UEMO A DANS LA REDACTION DES Technical Assistance for Non TERMES DE REFERENCE POU Consultant Qualifi Open - Internationa Under Implement IDA / D2360 -Bank Financial Institutions a Post 90,000.00 0.00 2023-06-07 2023-06-07 2023-06-22 2023-06-08 2023-07-13 2023-07-20 2023-07-30 2023-09-13 R LES PRESTATIONS DE SERV cation Selection l ation nd CRRH ICES INFORMATIQUES ET L’EL ABORATION DES SPECIFICATI ONS TECHNIQUES POUR LES ACQUISITIONS DE MATERIELS ET LOGICIELS INFORMATIQUE S TG-CRRH-364705-CS-CQS / Technical Assistance for Non UN CONSULTANT POUR LA C Consultant Qualifi Under Implement IDA / D2360 -Bank Financial Institutions a Post Open - National 40,000.00 0.00 2023-06-12 2023-06-01 2023-06-27 2023-07-18 2023-07-25 2023-08-04 2023-10-03 ONCEPTION ET LA MISE EN LI cation Selection ation nd CRRH GNE DU SITE WEB DE LA CRR H-UEMOA INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-CRRH-58281-CS-CQS / 1 consultant pour mettre en pl Participating Banks Mortgag Individual Consult ace la fenêtre SFD, former le IDA / D2360 Prior Open 250,000.00 76,164.00 Signed 2018-06-21 2018-08-13 2018-08-09 2018-11-30 2018-08-30 2019-02-18 2018-10-04 2019-03-08 2019-04-02 e Refinancing ant Selection personnel gérant la ligne et s uperviser son évolution TG-CRRH-58357-CS-INDV / U Technical Assistance for Non Individual Consult n consultant pour la passatio IDA / D2360 -Bank Financial Institutions a Post Open 25,000.00 58,893.42 Signed 2018-06-27 2018-06-29 2018-08-15 2018-09-04 2018-09-05 2018-10-30 2018-10-10 2018-11-19 2019-04-08 ant Selection n des marches et la gestion d nd CRRH u projet (1 an). TG-CRRH-101911-CS-INDV / Un consultant pour le renforc Design of Regional Guarante Individual Consult ement des capacités de la C IDA / D2360 Prior Open 300,000.00 0.00 Canceled 2019-04-15 2019-06-03 2019-06-24 2019-07-29 2020-01-25 e Product for Housing Loans ant Selection RRH-UEMOA pour la gestion du produit relatif au fonds de garantie et de la ligne SFD TG-CRRH-129521-CS-INDV / Recrutement d'un Juriste spé Participating Banks Mortgag Individual Consult IDA / D2360 Post Limited 25,000.00 54,012.50 Completed 2019-09-04 2019-09-04 2019-09-09 2020-01-20 2019-09-19 2020-03-04 2019-09-27 2020-03-06 2019-11-26 2020-12-10 cialiste des systèmes financi e Refinancing ant Selection ers décentralisés (SFD) TG-CRRH-139861-CS-CDS / Accompagnement de la CRR H-UEMOA vers une notation f Technical Assistance for Non inancière internationale : IDA / D2360 -Bank Financial Institutions a Post Direct Selection Direct 120,000.00 0.00 Canceled 2019-10-28 2019-10-24 2019-11-06 2019-11-13 2019-12-18 2020-04-16 - Lot 1 : sélection de l'agenc nd CRRH e Fitch - Lot 2 : sélection de l'agenc e Moody's TG-CRRH-162377-CS-INDV / RECRUTEMENT D’UN CONSU Technical Assistance for Non Individual Consult LTANT ANALYSTE FINANCIER IDA / D2360 -Bank Financial Institutions a Post Limited 54,000.00 76,740.93 Completed 2020-03-02 2020-03-03 2020-03-07 2020-03-06 2020-03-17 2020-03-16 2020-04-01 2020-03-18 2020-06-30 2020-12-10 ant Selection SENIOR SPECIALISTE DES SY nd CRRH STEMES FINANCIERS DECENT RALISES (SFD) TG-CRRH-171696-CS-INDV / CONSULTANT POUR L’ASSIST ANCE DES BANQUES REFINA Technical Assistance for Non Individual Consult NCEES DANS LA MISE EN PLA IDA / D2360 -Bank Financial Institutions a Post Limited 30,000.00 168,874.33 Signed 2020-05-07 2020-05-07 2020-05-12 2020-06-24 2020-05-27 2020-08-24 2020-06-08 2020-09-13 2020-09-06 ant Selection CE D’UN SYSTEME DE GESTI nd CRRH ON DU RISQUE ENVIRONNEM ENTAL ET SOCIAL SPECIFIQU E AUX PRETS A L’HABITAT TG-CRRH-220474-CS-INDV / RECRUTEMENT D'UN SECON D CONSULTANT POUR L'ASSI Technical Assistance for Non STANCE DES BANQUES ET SF IDA / D2360 -Bank Financial Institutions a Post Direct Selection Direct 65,000.00 105,872.94 Signed 2021-03-01 2021-03-05 2021-03-11 2021-04-07 2021-05-15 2021-07-11 2022-05-15 D REFINACES DANS LA MISE nd CRRH EN PLACE D'UN SYSTEME DE GESTION DU RISQUE ENVIRO NNEMENATL ET SOCIAL SPEC IFIQUE AUX PRETS A L'HABIT AT TG-CRRH-254889-NC-DIR / D éveloppement d’un module i nterface entre la nouvelle ap Affordable Housing Policies T IDA / D2360 Post Direct Selection Direct 45,000.00 37,843.87 Completed 2021-09-27 2021-09-09 2021-10-02 2021-09-14 2021-10-17 2021-10-06 2021-12-16 2022-03-24 plication de gestion des refin echnical Assistance ancements et l’application co mptable IBIS de la CRRH-UE MOA TG-CRRH-272750-CS-CDS / S ELECTION D'UN CONSULTAN T POUR LA REALISATION DE L Affordable Housing Policies T IDA / D2360 Post Direct Selection Direct 260,000.00 236,585.84 Signed 2022-01-14 2022-01-18 2022-01-17 2022-01-19 2022-01-25 2022-02-09 2022-01-28 ’ETUDE D’IMPACT DES REFIN echnical Assistance ANCEMENTS DE LA CRRH-UE MOA SUR LES RESSOURCES CONCESSIONNELLES TG-CRRH-316608-CS-CDS / Technical Assistance for Non REVUE DES ETATS FINANCIE IDA / D2360 -Bank Financial Institutions a Post Direct Selection Direct - National 50,000.00 0.00 Signed 2022-09-16 2022-08-31 2022-09-26 2022-08-31 2022-10-29 2022-11-28 RS 2019, 2020 et 2021 DE LA nd CRRH CRRH-UEMOA ETABLIS SELO N LES NORMES IFRS TG-CRRH-319061-CS-CDS / S ELECTION D’UN CABINET PO Technical Assistance for Non UR LA FORMATION DES BAN Direct - Internation Under Implement IDA / D2360 -Bank Financial Institutions a Post Direct Selection 25,000.00 0.00 2022-09-30 2022-10-11 2022-10-10 2022-10-12 2022-11-12 2022-12-12 QUES ET SFD DE LA CRRH-UE al ation nd CRRH MOA SUR LA NOUVELLE APPL ICATION DE GESTION DES RE FINANCEMENTS CARTHAGO Page 3 TG-CRRH-359247-CS-CDS / E TUDE DE FAISABILITE POUR L A MISE EN PLACE D’UNE SOL Affordable Housing Policies T Direct - Internation Under Implement UTION DE GARANTIE FNANCI IDA / D2360 Post Direct Selection 200,000.00 0.00 2023-05-15 2023-05-18 2023-05-30 2023-11-01 echnical Assistance al ation ERE DE PRETS AU LOGEMENT EN APPUI AUX INSTITUTIONS FINANCIERES DANS LA ZONE UEMOA TG-CRRH-362753-CS-CDS / UNE FIRME POUR LE DEVELO Technical Assistance for Non PPEMENT ET L’INSTALLATION Direct - Internation IDA / D2360 -Bank Financial Institutions a Post Direct Selection 395,000.00 0.00 Under Review 2023-05-29 2023-06-01 2023-06-13 2023-09-11 D’UNE APPLICATION CARTHA al nd CRRH GO MOYENS GENERAUX ET C OMPTABILITE GENERALE A LA CRRH-UEMOA Page 4 PROCUREMENT PLAN (Textual Part) Project information: [West Bank and Gaza] [Advancing Sustainability in Performance, Infrastructure, and Reliability of the Energy Sector (ASPIRE)] [P-170928] Project Implementation agency: [Palestinian Energy and Natural Resources Authority] Date of the Procurement Plan: [29-June-2020] Period covered by this Procurement Plan: [29-June-2020 – 28- December-2028] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [Domestic preference is not applicable for those contracts identified in the Procurement Plan tables]; Works: [Domestic preference is not applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is not Applicable. PROCUREMENT West Bank and Gaza : Advancing Sustainability in Performance, Infrastructure, and Reliability of the Energy Sector in the West Bank and Gaza PLAN General Information Country: West Bank and Gaza Bank’s Approval Date of the Original Procurement Plan: 2020-08-31 Revised Plan Date(s): (comma delineated, leave blank if 2023-05-26 none) Project ID: P170928 GPN Date: 2020-10-25 Project Name: Advancing Sustainability in Performance, Infrastructure, and Reliability of the Energy Sector in the West Bank and Gaza Loan / Credit No: TF / B3036, TF / B3015 Palestinian Energy and Natural Resources Authority Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GZ-PENRA-176003-GO-RFB / Component 1: Improving Infr Upgrade of MV lines in SELC astructure for Regional Elect Open - Internationa Single Stage - One E 2022-12-0 TF / B3015 Post Request for Bids 1,000,000.00 0.00 Canceled 2021-12-15 2021-12-20 2022-02-18 2022-04-19 2022-06-09 O to supply additional electri ricity Interconnections in the l nvelope 6 city from IEC (Phase #1) West Bank and Gaza GZ-PENRA-174777-GO-RFB / Component 1: Improving Infr Request for Bids - Upgrade of MV lines in TEDC astructure for Regional Elect Open - Internationa Single Stage - One E Works (without pr 2023-02-1 TF / B3015 Post Request for Bids 1,000,000.00 0.00 Canceled 2022-02-15 2022-02-20 2022-04-21 2022-06-20 2022-08-17 O to Supply Additional Electri ricity Interconnections in the l nvelope equalification) SP 3 city from IEC (Phase #1) West Bank and Gaza D GZ-PENRA-176009-GO-RFB / Component 1: Improving Infr Design, Supply, and Installati astructure for Regional Elect Open - Internationa Single Stage - One E 2024-04-2 TF / B3015 Post Request for Bids 2,500,000.00 0.00 Canceled 2021-12-12 2021-12-17 2022-01-16 2022-03-17 2022-05-05 on of MV line and infrastructu ricity Interconnections in the l nvelope 4 re between Jericho & Ramalla West Bank and Gaza h GZ-PENRA-279288-CW-RFB / Request for Bids - Expansion and Upgrade of T Component 3: Enabling Priv Single Stage - One E Works (without pr 2024-03-0 DECO MV Networks to Absor TF / B3015 ate Sector Engagement in R Post Request for Bids Open - National 1,900,000.00 0.00 Canceled 2022-10-25 2022-10-30 2022-12-14 2023-03-14 2023-05-11 nvelope equalification) SP 6 b more PV Generation in Tub enewable Energy D as District Electricity co (TDE CO) Request for Propo Component 1: Improving Infr sal Engineering Pr GZ-PENRA-317192-CW-RFP / astructure for Regional Elect Request for Propo Open - Internationa Single Stage - Two E ocurement and C 2024-08-1 Expansion of Sarra & Tarqum TF / B3015 Post 5,500,000.00 0.00 Canceled 2023-03-21 2023-03-26 2023-05-07 2023-09-18 2023-10-23 ricity Interconnections in the sals l nvelope onstruction/Turnk 8 ia 161/33 kV substation West Bank and Gaza ey - Works SPD (S ingle-Stage) Component 1: Improving Infr GZ-PENRA-339526-CW-RFB / Request for Bids - astructure for Regional Elect Open - Internationa Single Stage - One E 2024-06-2 Expansion of Sarra & Tarqum TF / B3015 Post Request for Bids Plant SPD (withou 5,500,000.00 0.00 Canceled 2023-03-15 2023-02-05 2023-03-20 2023-02-05 2023-05-01 2023-04-26 2023-07-30 2023-05-18 2023-09-03 ricity Interconnections in the l nvelope 9 ia 161/33 kV substation t prequalification) West Bank and Gaza Component 1: Improving Infr GZ-PENRA-362790-CW-RFB / Request for Bids - astructure for Regional Elect Open - Internationa Single Stage - One E Under Imple 2024-10-0 Expansion of Sarra & Tarqum TF / B3015 Post Request for Bids Plant SPD (withou 5,500,000.00 0.00 2023-06-15 2023-06-12 2023-06-20 2023-06-12 2023-08-04 2023-11-02 2023-12-07 ricity Interconnections in the l nvelope mentation 2 ia 161/33 kV substation t prequalification) West Bank and Gaza GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-PENRA-176007-GO-DIR / Component 1: Improving Infr Rehabilitation of Tarqumia S astructure for Regional Elect TF / B3036 Post Direct Selection Direct 950,000.00 819,123.69 Completed 2020-05-28 2019-11-11 2020-06-02 2020-03-04 2020-07-07 2020-05-22 2021-01-03 2020-06-05 ubstation ricity Interconnections in the DS-PETL-EM-WB-20 West Bank and Gaza GZ-PENRA-213250-GO-RFB / Component 1: Improving Infr Upgrade of MV lines in NEDC astructure for Regional Elect Single Stage - One E TF / B3015 Post Request for Bids Open - National 500,000.00 566,217.52 Completed 2021-09-15 2021-08-15 2021-09-20 2021-08-17 2021-11-19 2021-10-27 2022-01-18 2021-12-14 2022-02-22 2022-02-06 2022-08-21 2022-11-15 O to Supply Additional Electri ricity Interconnections in the nvelope city from IEC West Bank and Gaza Component 1: Improving Infr GZ-PENRA-251671-GO-RFB / astructure for Regional Elect Open - Internationa Single Stage - One E TF / B3015 Post Request for Bids 1,200,000.00 1,028,762.69 Completed 2021-09-30 2021-12-23 2021-10-05 2022-01-04 2021-11-16 2022-02-14 2022-01-15 2022-02-23 2022-03-12 2022-05-27 2022-07-10 2022-11-09 Supply of MV Cables ricity Interconnections in the l nvelope West Bank and Gaza GZ-PENRA-174760-GO-RFB / Supply of Smart Meters for E Component 2: Improving Su DISCOs in Gaza, including A stainability of Service Delive Open - Internationa Single Stage - One E dvanced Metering Infrastruct TF / B3036 Prior Request for Bids 3,000,000.00 0.00 Canceled 2022-06-01 2022-07-01 2022-08-30 2022-10-29 2023-01-27 2023-07-26 ry in West Bank and Gaza DI l nvelope ure (AMI) comprising commu SCOs nication devices, software (M DMS) and a Metering Control Center (MCC) - (Phase #2) GZ-PENRA-174554-GO-RFB / Component 2: Improving Su Open - Internationa Single Stage - One E Under Revie Supply of Smart Meters for E TF / B3036 stainability of Service Delive Prior Request for Bids 7,000,000.00 0.00 2022-08-31 2023-01-15 2022-09-30 2023-02-14 2022-12-29 2023-04-12 2023-04-28 2023-06-25 2024-02-20 l nvelope w DISCOs in West Bank & Gaza ry in West Bank and Gaza DI (Phase II) SCOs GZ-PENRA-174774-GO-RFB / Component 3: Enabling Priv Supply and Installation of roo TF / B3015 ate Sector Engagement in R Prior Request for Bids 2,000,000.00 0.00 Canceled 2021-12-30 2022-01-04 2022-02-18 2022-04-19 2022-06-09 2022-12-06 ftop solar systems in Gaza enewable Energy GZ-PENRA-279279-GO-RFB / Component 1: Improving Infr Upgrade of MV Lines in SELC astructure for Regional Elect Open - Internationa Single Stage - One E TF / B3015 Post Request for Bids 1,000,000.00 0.00 Signed 2022-06-30 2022-07-26 2022-07-14 2022-07-27 2022-09-08 2022-09-07 2022-12-07 2022-10-16 2023-02-03 2023-08-02 O to Supply Additional Electri ricity Interconnections in the l nvelope city form IEC (Phase I) West Bank and Gaza GZ-PENRA-326693-GO-RFB / Expansion and Upgrade of T Component 3: Enabling Priv Open - Internationa Single Stage - One E DECO MV Networks to Absor TF / B3015 ate Sector Engagement in R Post Request for Bids 1,900,000.00 0.00 Signed 2022-12-25 2022-12-07 2022-12-30 2022-12-07 2023-02-10 2023-01-25 2023-04-11 2023-03-26 2023-06-01 2024-03-27 l nvelope b more PV Generation in Tub enewable Energy as District Electricity co (TDE CO) Component 1: Improving Infr GZ-PENRA-338253-GO-RFB / astructure for Regional Elect Open - Internationa Single Stage - One E Expansion of Sarra & Tarqum TF / B3015 Prior Request for Bids 5,500,000.00 0.00 Canceled 2023-03-20 2023-03-25 2023-05-06 2023-08-04 2023-09-08 2024-07-04 ricity Interconnections in the l nvelope ia 161/33 kV substation West Bank and Gaza GZ-PENRA-174770-GO-RFB / Component 3: Enabling Priv Supply and Installation of roo Open - Internationa Single Stage - One E TF / B3015 ate Sector Engagement in R Post Request for Bids 1,500,000.00 0.00 Canceled 2023-02-28 2023-03-05 2023-04-19 2023-06-18 2023-08-08 2025-01-29 ftop solar systems in West B l nvelope enewable Energy ank (Revolving Fund) Page 1 Component 1: Improving Infr GZ-PENRA-279301-GO-RFB / astructure for Regional Elect Open - Internationa Single Stage - One E Supply of MV Line between Je TF / B3015 Post Request for Bids 1,500,000.00 0.00 Canceled 2023-04-02 2023-04-07 2023-06-02 2023-08-31 2023-10-28 2024-04-25 ricity Interconnections in the l nvelope richo & Ramallah West Bank and Gaza GZ-PENRA-279290-GO-RFB / Component 1: Improving Infr Upgrade of MV Lines in HEPC astructure for Regional Elect Open - Internationa Single Stage - One E Under Imple TF / B3015 Post Request for Bids 1,000,000.00 0.00 2023-04-10 2023-03-29 2023-04-15 2023-04-05 2023-05-27 2023-05-24 2023-08-25 2023-09-29 2024-07-25 O to Supply Additional Electri ricity Interconnections in the l nvelope mentation city from IEC West Bank and Gaza GZ-PENRA-314425-GO-RFB / Component 3: Enabling Priv Supply & Installation of Solar Open - Internationa Single Stage - One E Under Revie TF / B3015 ate Sector Engagement in R Prior Request for Bids 800,000.00 0.00 2023-06-20 2023-06-25 2023-08-06 2023-10-05 2023-11-09 2024-09-04 Systems & Energy Efficiency l nvelope w enewable Energy Technology for Health Sector in West Bank GZ-PENRA-317012-GO-RFB / Component 3: Enabling Priv Supply and Installation of Ro Open - Internationa Single Stage - One E Under Imple TF / B3015 ate Sector Engagement in R Prior Request for Bids 3,500,000.00 0.00 2023-06-30 2023-06-07 2023-07-05 2023-06-12 2023-08-16 2023-11-14 2023-12-19 2025-12-18 oftop Solar system in West B l nvelope mentation enewable Energy ank (Revolving Fund) GZ-PENRA-361232-GO-RFB / Component 1: Improving Infr Supply and install Medium vo astructure for Regional Elect Open - Internationa Single Stage - One E Pending Impl ltage lines from Jarad 33/11 k TF / B3036 Post Request for Bids 500,000.00 0.00 2023-08-15 2023-08-20 2023-10-01 2023-12-30 2024-02-03 2024-08-01 ricity Interconnections in the l nvelope ementation V substation to Beit Jala Junct West Bank and Gaza ion to improve electricity sup ply. GZ-PENRA-367112-GO-RFB / Component 1: Improving Infr Supply and Installation of 17 astructure for Regional Elect Open - Internationa Single Stage - One E Pending Impl TF / B3015 Prior Request for Bids 2,500,000.00 0.00 2023-10-10 2023-10-15 2023-11-26 2024-02-24 2024-03-30 2024-10-26 Km double circuit medium vo ricity Interconnections in the l nvelope ementation ltage line from Beit Ula subst West Bank and Gaza ation to Hebron city. GZ-PENRA-331017-GO-RFQ / Component 4: Technical Assi Request for Quota Single Stage - One E Pending Impl Supply of one vehicle for PM TF / B3015 stance, Capacity Building an Post Limited 40,000.00 0.00 2023-08-05 2023-10-07 2024-04-04 tions nvelope ementation U d Project Management GZ-PENRA-338309-GO-RFB / Upgrade of NEDCO MV Netw Component 3: Enabling Priv Open - Internationa Single Stage - One E Pending Impl orks to Absorb more PV Gene TF / B3015 ate Sector Engagement in R Post Request for Bids 1,500,000.00 0.00 2023-09-10 2023-09-15 2023-10-27 2024-01-25 2024-02-29 2024-12-25 l nvelope ementation ration and Expansion of Elect enewable Energy ricity System in the North an d East Part of Nablus City. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-PENRA-221765-CS-QCBS / Assessment of Sustainable Component 4: Technical Assi Quality And Cost- Lead Acid Battery (ULAB) Dis TF / B3036 stance, Capacity Building an Post Open - National 80,000.00 0.00 Canceled 2021-03-25 2021-04-04 2021-04-15 2021-05-20 2021-05-29 2021-06-26 2021-07-26 2021-08-30 2021-10-04 2022-04-02 Based Selection posal, Collection and Recycli d Project Management ng Scheme, Gaza Strip – Pale stine GZ-PENRA-232079-CS-QCBS / Consultancy Services to the Component 4: Technical Assi Palestinian Energy & Natural Quality And Cost- Open - Internationa TF / B3015 stance, Capacity Building an Post 250,000.00 0.00 Canceled 2021-05-10 2021-04-29 2021-05-31 2021-07-30 2021-08-29 2021-09-28 2021-10-15 2021-12-03 2022-06-01 Resources Authority for the n Based Selection l d Project Management egotiation of a Gas Purchase Agreement for G4G Project Component 1: Improving Infr GZ-PENRA-233459-CS-LCS / astructure for Regional Elect Quality And Cost- Design for PETL NCC SCADA TF / B3015 Post Open - National 35,000.00 101,900.00 Completed 2021-05-19 2021-07-04 2021-06-09 2021-07-12 2021-08-08 2021-09-29 2021-09-05 2021-12-08 2021-10-05 2022-01-19 2021-11-09 2022-01-17 2021-12-14 2022-04-07 2022-06-12 2023-01-20 ricity Interconnections in the Based Selection system’s development West Bank and Gaza GZ-PENRA-237250-CS-CQS / Consultancy Services to the Component 4: Technical Assi Palestinian Energy & Natural Consultant Qualifi TF / B3015 stance, Capacity Building an Post Limited 250,000.00 250,000.00 Signed 2021-06-06 2021-05-31 2021-06-20 2021-07-05 2021-07-20 2021-09-27 2021-08-24 2021-10-11 2022-02-20 Resources Authority for the n cation Selection d Project Management egotiation of a Gas Purchase Agreement for G4G Project GZ-PENRA-241162-CS-QCBS / Technical and Financial Fea Component 4: Technical Assi Quality And Cost- sibility Assessment and Cost TF / B3015 stance, Capacity Building an Post Open - National 50,000.00 0.00 Canceled 2021-07-15 2021-09-09 2021-08-05 2021-09-18 2021-11-03 2021-12-03 2022-01-07 2022-02-11 2022-04-12 Based Selection Estimate for Photovoltaic Sys d Project Management tems on the Health Sector in West Bank (Palestine). GZ-PENRA-249761-CS-QCBS Component 4: Technical Assi Quality And Cost- / Technical & Financial Audit TF / B3015 stance, Capacity Building an Post Open - National 60,000.00 0.00 Canceled 2021-08-31 2021-08-31 2021-09-21 2021-11-04 2021-12-02 2022-01-01 2022-02-05 2022-03-12 2023-03-12 Based Selection of ASPIRE Project d Project Management GZ-PENRA-253713-CS-QCBS Component 4: Technical Assi Quality And Cost- / Technical & Financial Audit TF / B3015 stance, Capacity Building an Post Open - National 60,000.00 0.00 Signed 2021-09-20 2021-09-19 2021-10-11 2021-11-24 2021-10-12 2021-12-22 2021-11-11 2022-01-21 2021-12-15 2022-02-25 2022-01-13 2022-04-01 2024-03-31 Based Selection of ASPIRE Project d Project Management GZ-PENRA-264432-CS-CQS / Technical and Financial Feasi Component 4: Technical Assi bility assessment and cost es Consultant Qualifi TF / B3015 stance, Capacity Building an Post Open - National 50,000.00 49,880.00 Completed 2021-11-22 2021-11-22 2021-12-13 2022-01-26 2022-01-05 2022-02-25 2022-03-16 2022-04-01 2022-03-21 2022-09-28 2022-10-25 timate for Photovoltaic Syste cation Selection d Project Management ms and Energy Efficiency Me asures on the Health Sector i n West Bank (Palestine). GZ-PENRA-278832-CS-CQS / Component 4: Technical Assi Consultant Qualifi Review and Assess PETL’s Cu TF / B3036 stance, Capacity Building an Post Open - National 11,000.00 0.00 Signed 2022-02-20 2022-03-07 2022-03-13 2022-04-26 2022-05-19 2022-05-26 2022-06-15 2022-06-30 2022-12-27 cation Selection rrent Financial System. d Project Management GZ-PENRA-279903-CS-CQS / Component 4: Technical Assi Consultant Qualifi Open - Internationa Green Corridor” Transmissio TF / B3036 stance, Capacity Building an Post 100,000.00 0.00 Signed 2022-04-20 2022-07-27 2022-05-11 2022-08-01 2022-07-24 2022-10-12 2022-08-23 2022-12-21 2022-09-27 2023-03-26 cation Selection l n Line and VREG Integration d Project Management Study Page 2 GZ-PENRA-307109-CS-CQS / Consultancy Services for "De Component 4: Technical Assi signing and Supervising a Re Consultant Qualifi Open - Internationa TF / B3036 stance, Capacity Building an Post 50,000.00 0.00 Signed 2022-08-07 2022-08-10 2022-08-28 2022-08-17 2022-10-11 2022-10-25 2022-11-10 2022-12-07 2022-12-15 2023-06-13 placement MV Switchgear, N cation Selection l d Project Management ew Operational Program & Ci vil Works for Gaza West Subs tation (GWS)" GZ-PENRA-326672-CS-QCBS / Assessment of Sustainable Component 4: Technical Assi Quality And Cost- Open - Internationa Under Implement Lead Acid Battery (ULAB) Dis TF / B3036 stance, Capacity Building an Post 250,000.00 0.00 2022-12-15 2023-03-13 2023-01-05 2023-03-27 2023-04-05 2023-05-08 2023-05-20 2023-07-19 2023-08-23 2023-09-27 2024-09-26 Based Selection l ation posal, Collection and Recycli d Project Management ng Scheme, Gaza Strip – Pale stine GZ-PENRA-176013-CS-QCBS Component 4: Technical Assi / Assessment for the Pipeline Quality And Cost- Open - Internationa Pending Impleme TF / B3036 stance, Capacity Building an Post 250,000.00 0.00 2023-08-31 2023-09-30 2023-12-29 2024-02-23 2024-05-23 2024-07-22 2024-09-18 2024-12-17 of the Energy Sector Projects Based Selection l ntation d Project Management in West Bank & Gaza GZ-PENRA-348512-CS-QCBS / Technical Assistance to the Component 4: Technical Assi Quality And Cost- Open - Internationa Development of Liquidity Sup TF / B3015 stance, Capacity Building an Post 250,000.00 0.00 Canceled 2023-03-15 2023-03-13 2023-04-05 2023-03-14 2023-05-19 2023-06-16 2023-08-15 2023-09-19 2023-10-24 2024-10-23 Based Selection l port Account and Payment S d Project Management ystem (LSAPS)- Legal Suppor t and Advice GZ-PENRA-349990-CS-CQS / Technical Assistance to the D Component 4: Technical Assi Consultant Qualifi Under Implement evelopment of Liquidity Supp TF / B3015 stance, Capacity Building an Post Limited 250,000.00 0.00 2023-03-20 2023-03-21 2023-04-03 2023-05-10 2023-05-03 2023-06-07 2023-12-04 cation Selection ation ort Account and Payment Sys d Project Management tem (LSAPS)- Legal Support a nd Advice GZ-PENRA-367166-CS-QCBS Component 4: Technical Assi Quality And Cost- Open - Internationa Pending Impleme / Consultancy Services for pr TF / B3015 stance, Capacity Building an Post 300,000.00 0.00 2023-06-30 2023-07-21 2023-10-19 2023-11-16 2024-01-15 2024-02-19 2024-03-25 2024-10-21 Based Selection l ntation eparation Palestine Grid Cod d Project Management e GZ-PENRA-368404-CS-QCBS Component 4: Technical Assi / Consultancy services to des Quality And Cost- Open - Internationa Pending Impleme TF / B3015 stance, Capacity Building an Post 500,000.00 0.00 2023-07-20 2023-08-10 2023-11-08 2023-12-06 2024-02-04 2024-03-10 2024-04-14 2024-10-11 ign Five (5) substations for P Based Selection l ntation d Project Management alestinian Electricity Transmi ssion Ltd. (PETL) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-PENRA-211416-CS-INDV Component 4: Technical Assi Individual Consult / Project Execution Consultan TF / B3015 stance, Capacity Building an Post Direct 40,000.00 40,000.00 Completed 2021-01-20 2021-01-13 2021-01-27 2021-01-13 2021-01-29 2021-01-17 2021-02-03 2021-03-02 2022-02-03 2022-03-02 ant Selection t for PENRA PMU d Project Management GZ-PENRA-213086-CS-INDV Component 4: Technical Assi Individual Consult / Liquidity Support Fund Desi TF / B3015 stance, Capacity Building an Post Direct 40,000.00 50,000.00 Signed 2021-01-20 2021-01-13 2021-01-30 2021-01-13 2021-02-20 2021-01-25 2021-03-27 2021-02-02 2021-09-23 ant Selection gn Consultant d Project Management GZ-PENRA-221741-CS-INDV / Consulting Management Ser vices for Preparation of Gene Component 4: Technical Assi ric & Site-Specific Environme Individual Consult TF / B3015 stance, Capacity Building an Post Direct 15,000.00 15,000.00 Completed 2021-03-15 2021-03-28 2021-03-25 2021-03-31 2021-04-15 2021-04-05 2021-05-20 2021-04-05 2021-07-19 2021-11-29 ntal and Social Instruments f ant Selection d Project Management or the Sub-project “Supply & Installation of 3 Medium Volt age Lines from Qusin-Sarra J unction to Qusin-Bet Iba Junc tion “ GZ-PENRA-228054-CS-INDV Component 4: Technical Assi Individual Consult / Liquidity Support Fund – Fin TF / B3015 stance, Capacity Building an Post Direct 30,000.00 30,044.00 Signed 2021-04-06 2021-04-07 2021-04-16 2021-04-12 2021-05-07 2021-04-20 2021-06-11 2021-04-22 2021-12-08 ant Selection ancial/Technical Support – Lo d Project Management cal GZ-PENRA-259795-CS-CDS / Consultancy Service for upda Component 4: Technical Assi ting Environmental and Socia TF / B3015 stance, Capacity Building an Post Direct Selection Direct 25,000.00 31,320.00 Signed 2021-11-08 2021-11-01 2021-11-18 2021-11-07 2022-01-22 2021-11-19 2022-07-21 l Impact Assessment (ESIA) f d Project Management or “The medium voltage singl e circuit overhead line betwe en Jericho and Ramallah” GZ-PENRA-264768-CS-CQS / Consultancy Service for a Pre Component 4: Technical Assi Individual Consult liminary Environmental and S TF / B3036 stance, Capacity Building an Post Limited 7,000.00 7,000.00 Completed 2021-11-30 2021-11-24 2021-12-05 2021-12-23 2021-12-26 2021-12-27 2022-01-30 2022-01-03 2022-07-29 2022-03-24 ant Selection ocial Impact Assessment (P-E d Project Management SIA) for 2 MV underground in terventions in Gaza. GZ-PENRA-261335-CS-CDS / Component 4: Technical Assi Review and assess PETL’s cu TF / B3015 stance, Capacity Building an Post Direct Selection Direct 5,000.00 0.00 Canceled 2021-11-07 2021-11-08 2021-11-17 2022-01-21 2022-07-20 rrent Financial System d Project Management GZ-PENRA-267682-NC-DIR / Component 4: Technical Assi Experts Basic Local Support TF / B3036 stance, Capacity Building an Post Direct Selection Direct 20,000.00 20,880.00 Signed 2022-01-10 2022-01-25 2022-01-20 2022-03-20 2022-03-26 2022-04-01 2022-09-22 on the Financial Managemen d Project Management t Information System "FMIS"- Olive Tree GZ-PENRA-271560-CS-CDS / Component 4: Technical Assi Individual Consult Environment and Social Scre TF / B3036 stance, Capacity Building an Post Direct 7,000.00 0.00 Canceled 2022-01-20 2022-02-15 2022-01-30 2022-02-20 2022-03-27 2022-09-23 ant Selection ening for the revolving fund d Project Management beneficiaries. GZ-PENRA-276449-CS-CDS / Consultancy Service for Prep Component 4: Technical Assi aring Environmental and Soci TF / B3036 stance, Capacity Building an Post Direct Selection Direct 11,000.00 0.00 Canceled 2022-02-10 2022-02-10 2022-02-20 2022-04-26 2022-10-23 al Management Plan (ESMP) f d Project Management or "Upgrade of MV lines in SE LCO to supply additional elec tricity from IEC" . GZ-PENRA-284045-CS-INDV Component 4: Technical Assi Individual Consult / Project Execution Consultan TF / B3015 stance, Capacity Building an Post Direct 50,000.00 50,000.00 Signed 2022-04-04 2022-05-09 2022-04-14 2022-05-10 2022-05-05 2022-05-11 2022-06-09 2022-05-27 2023-06-09 ant Selection t for PENRA PMU d Project Management GZ-PENRA-288728-CS-INDV Component 3: Enabling Priv / Consultancy Service for Scr Individual Consult TF / B3036 ate Sector Engagement in R Post Direct 7,000.00 7,000.00 Completed 2022-04-14 2022-04-21 2022-04-24 2022-06-22 2022-05-15 2022-07-07 2022-06-19 2022-07-13 2022-12-16 2022-11-10 eening and Data collection of ant Selection enewable Energy the sites for the revolving fun d beneficiaries Page 3 GZ-PENRA-283972-CS-INDV / Consulting Management Se Component 4: Technical Assi rvices for Preparation of of S Individual Consult TF / B3015 stance, Capacity Building an Post Limited 40,000.00 0.00 Canceled 2022-08-31 2022-09-14 2022-10-14 2022-11-27 2023-05-26 ite Specific Environment and ant Selection d Project Management Social Instrument for the Sup ply and Install Rooftop Solar systems in West Bank. GZ-PENRA-283971-CS-INDV / Consulting Management Ser Component 4: Technical Assi vices for Preparation of Site S Individual Consult TF / B3015 stance, Capacity Building an Post Limited 20,000.00 0.00 Canceled 2022-10-16 2022-10-30 2022-11-29 2023-01-12 2023-07-11 pecific Environmental & Soci ant Selection d Project Management al Instruments for the Supply & Installation of Six Health Fa cilities in the West Bank. GZ-PENRA-365186-CS-INDV Component 4: Technical Assi / Liquidity Support Account a Individual Consult Pending Impleme TF / B3015 stance, Capacity Building an Post Direct - National 18,000.00 0.00 2023-06-22 2023-07-02 2023-07-23 2023-08-27 2024-02-23 nd Payment System (LSAPS) ant Selection ntation d Project Management consultant for ASPIRE. Page 4 AGRO-CLIMATIC RESILIENCE IN SEMI -ARID LANDSCAPES (ACReSAL) PROJECT PROCUREMENT STRATEGY FOR DEVELOPMENT 1 PROJECT OVERVIEW Country: NIGERIA Full Project Name: AGRO-CLIMATIC RESILIENCE IN SEMI -ARID LANDSCAPES (ACReSAL) Total Finance ($): USD 700 MILLION Project Number: P175237 Summary of Project The Project Development Objective (PDO) is to increase the adoption of climate resilient landscape Development Objectives management practices and enhance livelihoods in targeted arid/semi-arid watersheds in Northern Nigeria. PROJECT COST COMPONENTS ESTMATE OBJECTIVES OF EACH (USD) COMPONENT Component A: 299.6m This component aims to prepare and Desertification Control implement investments to arrest and Landscape desertification and improve the Management sustainable productivity of land in targeted watersheds (about 1,000,000 ha area of degraded and desert landscapes out of 4,000,000 (25%) Government program). Component B: 293.4m This component aims to support Community communities with improved capacity Livelihoods and and investments to improve Resilience sustainable livelihoods. Component C: 107.6m This component aims to strengthen Institutional capacities of institutions at various levels (e.g., national, selected states) Strengthening and to modernize their work for the Project Management longer-term on integrated multi- sectoral planning, information management, and building systems for improving land and water management and sustainable agricultural productivity in northern Nigeria. Component D: 0m This will finance a Contingency Contingency Emergency Response Component Emergency Response (CERC) for landscape and community Components (CERC): resilience in response to extreme weather, land movement events and other emergencies. LIST OF PROCUREMENT ACTIVITIES The project is designed as framework project and therefore investments and the participating states (the major investments will be implemented by the participating states) are not fully known yet. In the table below are the activities that already known, and implementation can commence immediately. The PPSD will be updated during implementation as the investments and participating states become more defined. These investments include gully erosion control, rehabilitation of irrigation and dams. S/N ACTIVITIES COST CUMMULATIVE % of ESTIMATE COST TOTAL (USD) ESTIMATE COST (USD) ESTIMATE 1 Technical assistance for 10,000,000 10,000,000 28% landscape restoration services 2 Extension services technical 9,900,000 19,900,000 57% assistance 3 Implementation support 9,500,000 29,400,000 84% consultancy 4 Long-term framework and 2,500,000 31,900,000 91% policy support 5 Development of strategic 1,600,000 33,500,000 95% catchment plan 4 Monitoring Information 600,000 34,100,000 97% System (MIS) and maintenances 5 Others ICT Equipment and 400,000 34,500,000 98% connectivity, cloud services, others general services Desktops & Laptops 300,000 34,800,000 99% Data collection and analysis at 168,000 34,968,000 100% State/federal Level Production of Manuals (PIM ) 90,000 35,058,000 100% Design and hosting of 56,000 35,114,000 100% interactive website TOTAL 35,114,000 Strategic Assessment of Operating Context and Borrower Capability Operational Context Nigeria experiences a diverse climate that ranges from arid in the north to tropical in much of the country and is listed among the countries most exposed to climate risks. The country faces a high water-scarcity hazard level, with droughts expected to occur on average every five years, with potential increased frequency due to climate change. Focusing on drylands management, ACReSAL will be implemented in the states of northern Nigeria. The agricultural sector is the major economic driver of northern Nigeria. Many projects and initiatives have been undertaken in northern Nigeria over the past decades to combat the growing crisis of desertification. The FGN is thus increasingly moving toward an integrated and multisectoral approach to address the challenges of dryland management. (a) Governance Aspects: There are security challenges in almost all the states in the northern Nigeria where the project will be implemented. The Government of Nigeria is making some progress in addressing these security challenges. The security situation may reduce the interest of major players, especially for Component A to participate in the procurement process and those that choose to participate may add a premium to the bid prices to take of the additional security arrangement they want to put in place during contract execution in case of an award. (b) Economic Aspects: Nigeria has just come out of an economic recession because of CIVID 19 pandemic and a fall in crude oil price in the world market. The country is contending with high inflation and exchange rate volatility. The high inflation and exchange rate volatility has made the prices of the major construction materials such as iron rods and cement to be volatile. Substantial proportion of the Component consist of civil works with locally available inputs (labour and materials). The effect of the exchange volatility will be minimal since bidders expecting to incur expenditures in other currencies for inputs to the Works supplied from outside the country can quote for such inputs in up to three different foreign currencies in their bids. Serious bottleneck exists in the main seaport where goods to be imported from abroad will be discharged. This has led to delay in the custom clearance of good from the port with the resulting demurrage payment and delay in contract execution. The government is working on policy that will remove the bottlenecks. (c) Sustainability Aspects: The government environmental and social standards requires that Environmental and Social Impact Assessment be carried on all major works project before the commencement of such works. ESIA will apply to this project and will be reflected in the solicitation documents and contracts for civil works under the project. (d) Technological Aspects: Kaduna, Niger, Kogi, Jigawa, Borno, Kano and Gombe States that will likely participate in the project have an e-Procurement system which is being used in some of the MDAs. Sokoto State is in the final stages of their e- Procurement implementation. The systems so deployed will be used for procurement under the project. This will further improve value for money, transparency, economy, efficiency, effectiveness, integrity, and openness of procurement process under the project. The country is covered substantially by GSM, part of which is through extensive fiber optic cabling leading to increased networking and internet availability. The availability of reasonable internet access will facilitate the use of the World Bank Systematic Tracking of Exchanges in Procurement (STEP) which is mandatory requirement in the processing all procurement activities under the World Bank Procurement Regulations. Key Conclusions: The security challenges in the country especially in the northern states that will participate in the project may reduce the participation of foreign firms and firms from other parts of the in the procurement process for the project. The current high inflation and exchange rate volatility in the country will affect the costing of the various procurement packages in the project. The use of eProcurement for by the participating states and the FPMU will improve value for money, transparency, economy, efficiency, effectiveness, integrity, and openness of procurement process under the project Assessment of Borrower previous Experience, Capability and Project Implementation Unit (PIU) The project will be implemented using the existing NEWMAP PMUs at both Federal and State levels that are implementing NEWMAP and the NEWMAP AF that will close on June 30, 2022. The implementation arrangement is similar to that of NEWMAP. Each state will be responsible for the procurement of its own activities including contract management and administration. The FPMU and the states that are implementing NEWMAP have experience in World Bank Procurement Regulations. The procurement officers have received sufficient training in procurement under World Bank funded project. The gaps that were observed in the implementation of NEWMAP especially in contract management will be addressed under ACReSAL. Training will be provided on contract management, application of price adjustment, contract monitoring and supervision as soon as the project is effective. Market Analysis The summary of the procurement activities under the project are as follows • Civil works: o gully erosion control, o flood and sedimentation control, o construction of firebreaks, o rehabilitation and construction of small dams, o small scale irrigation infrastructure, o small buildings There are several players both national and international in the marketplace for these activities. International open competitive procurement approach will be used for high value, high risk gully erosion control and construction of dams and firebreaks. The other low value, low risk procurement will follow national open competition or limited competition as may be appropriate. • Goods: o fire control equipment, o vehicles, o farm inputs (seeds, fertilizers), o post-production equipment, o computers, furniture They are locally available and be supplied by several suppliers and the procurement approach will be national open/limited completion as may be appropriate. The approach for the procurement of farm inputs (seeds, fertilizer) will limited competition between the well-known producers/suppliers of these goods. • Consulting services: The major consulting services includes engineering design and supervision of the major civil works like gully erosion control and rehabilitation of dams. The firms that offer this service are available in the local and international markets. Due to the criticality of this consulting assignment to the overall delivery of the major works contracts, the procurement will be designed to attract best consulting firms to express interest in this assignment. Procurement Risk Analysis Market Risk Description of Risk Owner /Contract Description Mitigation Title Description Construction of Designs may no A consultant will be State PMU and shovel ready longer be valid by the hired to update the World Bank gully erosion contracts during design before the control site contract execution commencement of the procurement process Expansion of the Provisions for State PMUs gullies between physical bidding and contract contingencies will signature made in the signed contract. Expansion of gullies Proper drainage on Contractor during construction the site must be due to poor drainage maintained during resulting from construction and the construction of the Contractor shall be works held responsible for any flood damage to life and properties due to his work in this Contract. The Contractor shall allow in his rates, inter alia, for all costs to maintain or divert flow in drains, ditches, open channels and watercourses during construction and other drainage work. No claims for additional payment will be considered in this regard. Construction Poor supervision of supervision the works contracts consultancy Procurement of Delay in port All the necessary PMUs goods to be clearance documentation and imported from waivers will be outside the processed speedily country (delfino ploughs, tractors, etc) General (for all High inflation and Price adjustment to PMUs contracts) exchange rate applied to most even volatility if they duration is less than 18 months. Procurement Objective • To a minimum of 8 qualified consultants to participate in the selection process for the engineering design and supervision consultancy for the major works contracts. • To take advantage of the dry season for the construction contracts by aligning the commencement of the works with the dry season in the project areas. • Value for money and integrity in the procurement process using electronic procurement system. • To have not less than six qualified firms submit bids for the major works contracts. • Procurement Approach Options and Recommendation The following will be a draft zero of the procurement approach options and recommendations. This is because the major investments are not yet known. This section will be updated once the investments are finalized. • Contract and Estimated Cost: Landscape investments (many packages)– USD236 million • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Specifications Conformance Details design for shovel- ready investments from NEWMAP are available. Engineering firm will be hired to provide detail designs for other investments. Sustainability No All the safeguard studies Requirements will be carried out separately and cost implications will be included in the bidding document. Contract Type Traditional Pricing and costing Schedule of mechanism Rates/Admeasurement Price Adjustments None/Percentage Form of Contract (Terms and Conditions) Selection Method Request for Bids (RFB) Selection Arrangement N/A Market Approach Open International/National Pre/Post Qualification Post Evaluation Selection Least Cost Based Method Selection (LCS) Evaluation of Costs Adjusted Bid Price Domestic Preference No Rated Criteria N/A • Contract and Estimated Cost: Development of strategic catchment plan – USD1,600,000 • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Sustainability N/A Requirements Contract Type Traditional Pricing and costing Lump Sum mechanism Price Adjustments None Form of Contract (Terms N/A and Conditions) Selection Method Request for Proposals (RFP) Selection Arrangement N/A Market Approach Open International Pre/Post Qualification Pre-Qualification Evaluation Selection Quality Cost Based Method Selection (QCBS) Evaluation of Costs N/A Domestic Preference N/A Rated Criteria Mandatory • Contract and Estimated Cost: Long-term framework and policy support – USD2,500,000 • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Sustainability N/A Requirements Contract Type Traditional Pricing and costing Time and Materials mechanism Price Adjustments ????? Form of Contract (Terms ????? and Conditions) Selection Method Request for Proposals (RFP) Selection Arrangement N/A Market Approach Open International, Two Envelopes Pre/Post Qualification Pre-Qualification Evaluation Selection Quality Cost Based Method Selection (QCBS) Evaluation of Costs Adjusted Bid Price Domestic Preference No Rated Criteria • Specific experience • Methodology and workplan • Qualification and experience of key experts • Contract and Estimated Cost: Implementation support consultancy – USD9,900,000 • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Sustainability N/A Requirements Contract Type Traditional Pricing and costing Lump Sum mechanism Price Adjustments None Form of Contract (Terms N/A and Conditions) Selection Method Request for Proposals (RFP) Selection Arrangement N/A Market Approach Open International Pre/Post Qualification Pre-Qualification Evaluation Selection Quality Cost Based Method Selection (QCBS) Evaluation of Costs N/A Domestic Preference N/A Rated Criteria Mandatory • Contract and Estimated Cost: Development of strategic catchment plan – USD1,600,000 • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Sustainability N/A Requirements Contract Type Traditional Pricing and costing Lump Sum mechanism Price Adjustments None Form of Contract (Terms and Conditions) Selection Method Request for Proposals (RFP) Selection Arrangement N/A Market Approach Open International, Two Envelopes Pre/Post Qualification Pre-Qualification Evaluation Selection Quality Cost Based Method Selection (QCBS) Evaluation of Costs Adjusted Bid Price Domestic Preference No Rated Criteria • Specific experience • Methodology and workplan • Qualification and experience of key experts Preferred arrangement for low value, low activities Contract Category Estimated cost Procurement Arrangement and Method Desktops & Goods 300,000 Open National Laptops Others ICT Goods 400,000 Open National Equipment and connectivity, cloud services, others general services Production of Goods 90,000 Limited RFQ Manuals (PIM Monitoring Consultancy 600,000 Open National Information System (MIS) and maintenances Design and hosting Consultancy 56,000 Limited CQS of interactive website Data collection and Consultancy 168,000 Limited CQS analysis at State/federal Level Summary of PPSD to be inform the Bank’s preparation of the PAD The project is designed as framework project and therefore investments and the participating states (the major investments will be implemented by the participating states) are not fully known yet. The security challenges in the country especially in the northern states that will participate in the project may reduce the participation of foreign firms and firms from other parts of the in the procurement process for the project. The current high inflation and exchange rate volatility in the country will affect the costing of the various procurement packages in the project. The use of eProcurement for by the participating states and the FPMU will improve value for money, transparency, economy, efficiency, effectiveness, integrity, and openness of procurement process under the project. The FPMU and the states that are implementing NEWMAP have experience in World Bank Procurement Regulations. The procurement officers have received sufficient training in procurement under World Bank funded project. The gaps that were observed in the implementation of NEWMAP especially in contract management will be addressed under ACReSAL. A sufficiently large numbers of firms are available locally and international for most of the procurement packages under the project, therefore competitive procurement can readily be used to achieved value for value during procurement implementation. The design of the gully erosion sites already cleared under NEWMAP that will be transferred to project will be updated prior to the launching of the procurement processes for the construction of such sites. The PPSD will be regularly updated as there are clear pictures on the participating states and the procurement activities that will be implemented by the states and the FPMU. Contract Estimat Bank Procurement Selecti Evaluati Title, ed Cost Oversig Approach/Competi on on Description US$ and ht tion Method Method and Risk Category Rating Implementati 9,500,00 Prior International SPD Rated on support0 (RFP) Criteria consultancy Substanti (VfM) al Long-term 2.500,00 Prior International SPD Rated framework 0, (RFP) Criteria and policy Substanti (VfM) support al Development 1,600,00 Prior International SPD Rated of strategic 0, (RFP) Criteria catchment Substanti (VfM) plan al Monitoring 600,000, Post International SPD Rated Information Moderate (RFP) Criteria System (MIS) (VfM) and maintenance s Others ICT 400,000, Post National RFB Lowest Equipment Moderate Evaluated and Cost connectivity, cloud services, others general services Desktops & 300,000, Post National RFB Lowest Laptops Low Evaluated Cost Data 168,000, Post National CQS Negotiati collection Moderate on and analysis at State/federal Level Production of 90,000, Post National RFQ Lowest Manuals Low Evaluated (PIM) Design and 56,000, Post National CQS Negotiati hosting of Moderate on interactive website PROCUREMENT Nigeria : Agro-Climatic Resilience in Semi-Arid Landscapes (ACReSAL) PLAN General Information Country: Nigeria 2022-12-06 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175237 GPN Date: Project Name: Agro-Climatic Resilience in Semi-Arid Landscapes (ACReSAL) Loan / Credit No: IDA / 70150 Gombe State ACReSAL Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GMS-ACRESAL/RFQ/22/010 / Request for Quota Fencing of 1500 hactres of w Component A: Dryland Mana Request for Quota Single Stage - One E Under Imple 2023-05-1 IDA / 70150 Post Limited tions (Non Bank-S 195,000.00 0.00 2022-12-17 2023-02-11 oodlot plantations in the 11 L gement tions nvelope mentation 2 PD) GAs across the state GMS-ACRESAL/RFQ/22/08 / Request for Quota Component A: Dryland Mana Request for Quota Single Stage - One E Under Imple 2023-07-0 Maintenance of plant nurseri IDA / 70150 Post Limited tions (Non Bank-S 197,690.00 0.00 2023-01-21 2023-03-04 gement tions nvelope mentation 2 es of assorted species IN 11 PD) LGAS GMS-ACRESAL/RFQ/22/10 / Request for Quota Component A: Dryland Mana Request for Quota Single Stage - One E Under Imple 2023-08-2 Drilling and reticulation of sol IDA / 70150 Post Limited tions (Non Bank-S 193,000.00 0.00 2023-04-15 2023-05-27 gement tions nvelope mentation 5 ar-powererd borehole in 11 L PD) GAs(1500 hacters) Request for Bids - GMS-ACRESAL/RFB/22/02 / R Component A: Dryland Mana Single Stage - One E Small Works SPD Pending Imp 2024-08-1 ailway line-Unguwa Uku Gull IDA / 70150 Post Request for Bids Open - National 6,364,820.00 0.00 2023-03-20 2023-03-25 2023-05-06 2023-06-05 2023-07-10 gement nvelope (1 envelope proce lementation 3 y Erosion control ss) GMS-ACRESAL/RFB/22/01 / F Request for Bids - ederal College of Education(T Component A: Dryland Mana Open - Internationa Single Stage - One E Works (without pr 22,808,846.7 Under Revie 2025-07-1 ) Staff School - Railway Line IDA / 70150 Prior Request for Bids 0.00 2023-03-06 2023-03-11 2023-04-22 2023-05-22 2023-06-26 gement l nvelope equalification) SP 9 w 0 Gully Erosion Control(Prelimi D nary Earthworks and Soil Sta bilization, etc) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GMS-ACRESAL/RFQ/22/01 / P rocurement of Laptops, Acce Component C: Institutional S Single Stage - One E Under Imple ssories, communication gadg IDA / 70150 trengthening and Project Ma Post Request for Bids Open - National 250,000.00 0.00 2022-10-03 2023-05-25 2022-10-17 2023-05-26 2022-10-20 2022-11-03 2022-11-24 2023-05-23 nvelope mentation ets, and ICT equipments for S nagement PMU, MDAs and data manage ment centre GMS-ACRESAL/RFQ/22/02 / P Component C: Institutional S Request for Quota Single Stage - One E Under Imple rocurement of office furnitur IDA / 70150 trengthening and Project Ma Post Limited 100,000.00 0.00 2022-10-15 2022-12-28 2022-12-10 2022-12-31 tions nvelope mentation e and equipments nagement GMS-ACRESAL/RFQ/22/04 / P Component C: Institutional S Request for Quota Single Stage - One E Under Imple rocurement of Information, E IDA / 70150 trengthening and Project Ma Post Limited 50,000.00 0.00 2022-10-08 2022-12-28 2022-11-19 2022-12-01 tions nvelope mentation ducation and Communication nagement IEC GMS-ACRESAL/RFQ/22/07 / P rocurement to Support Minis Component C: Institutional S Request for Quota Single Stage - One E Under Imple try of Environment for wild lif IDA / 70150 trengthening and Project Ma Post Limited 100,000.00 0.00 2022-11-21 2022-12-26 2023-01-25 tions nvelope mentation e management in the state-( nagement Gadgets for wild protection a nd management) GMS-ACRESAL/RFQ/22/03 / P Component C: Institutional S Request for Quota Single Stage - One E Pending Impl rocurement of Grievance Rea IDA / 70150 trengthening and Project Ma Post Limited 100,000.00 0.00 2023-01-07 2023-02-25 2023-04-11 tions nvelope ementation diness Mechanisms (GRM) to nagement ols GMS-ACRESAL/RFQ/22/09 / P rocurement of seedlings to pl Component A: Dryland Mana Request for Quota Single Stage - One E Under Imple IDA / 70150 Post Limited 100,000.00 0.00 2023-04-09 2023-06-04 2023-10-02 ant 1500 hactres across the gement tions nvelope mentation 11 LGAs across the state' NG-GOMBE STATE ACRESAL- Component C: Institutional S Single Stage - One E Pending Impl 342771-GO-RFB / Procureme IDA / 70150 trengthening and Project Ma Post Request for Bids Open - National 180,000.00 0.00 2023-05-15 2023-05-20 2023-07-01 2023-07-31 2023-09-04 2024-03-02 nvelope ementation nt of Data Management Cen nagement tre NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GMS-ACRESAL/CQS/22/03 / Component C: Institutional S Consultant Qualifi Pending Impleme IDA / 70150 Post Open - National 250,000.00 0.00 2022-11-08 2022-11-29 2023-01-12 2023-02-11 2023-03-18 2023-09-14 Upgrade of GIS Mapping trengthening and Project Ma cation Selection ntation nagement GMS-ACRESAL/CQS/22/01 / Upgrade and Development of Component B: Community Cl Consultant Qualifi Pending Impleme IDA / 70150 Post Limited 250,000.00 0.00 2023-01-09 2023-01-23 2023-02-22 2023-03-29 2023-09-25 2 Micro watershed planning, imate Resilience cation Selection ntation Gombe ACReSAL GMS-ACRESAL/CQS/22/04 / E Component C: Institutional S Consultant Qualifi Under Implement ngagement for Focal NGO C IDA / 70150 trengthening and Project Ma Post Open - National 80,000.00 0.00 2023-01-23 2023-02-06 2023-02-13 2023-05-26 2023-03-29 2023-04-28 2023-06-02 2023-11-29 cation Selection ation ommunity sansitazation and nagement mobilisations Page 1 NG-GOMBE STATE ACRESAL- 357014-CS-CQS / Consultanc Component A: Dryland Mana Consultant Qualifi Pending Impleme IDA / 70150 Post Open - National 198,000.00 0.00 2023-08-08 2023-08-29 2023-10-12 2023-11-11 2023-12-16 2025-08-27 y for Supervision of Railway t gement cation Selection ntation o Unguwa uku Gully Erosion sites GMS-ACRESAL/CQS/22/02 / Consultancy for Supervision Component A: Dryland Mana Quality And Cost- Open - Internationa Under Implement IDA / 70150 Post 720,000.00 0.00 2023-06-04 2023-06-02 2023-06-18 2023-07-23 2023-08-13 2023-08-27 2023-09-24 2023-10-29 2026-01-11 of Construction works Federa gement Based Selection l ation l College of Education (TECH) Gully Erosion Control INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GMS-ACRESAL/IC/22/03 / Up Component C: Institutional S grade and development of R Individual Consult Under Implement IDA / 70150 trengthening and Project Ma Post Limited 20,000.00 0.00 2022-11-07 2023-02-15 2022-11-28 2023-03-10 2022-12-19 2023-01-09 2023-07-08 AP for 2 sites (FCE and Railw ant Selection ation nagement ay line to U/uku Gully erosion Control sites) GMS-ACRESAL/IC/22/04 / Co nsultancy for Livelihoods Nee Component C: Institutional S Individual Consult Pending Impleme ds Assesment for 2 sites (FC IDA / 70150 trengthening and Project Ma Post Limited 20,000.00 0.00 2022-11-14 2022-11-21 2022-12-12 2023-01-02 2023-05-02 ant Selection ntation E and Railway line to U/uku G nagement ully erosion Control sites) GMS-ACRESAL/IC/22/02 / Up Component C: Institutional S grade and development of E Individual Consult Under Implement IDA / 70150 trengthening and Project Ma Post Limited 20,000.00 0.00 2023-01-16 2023-02-06 2023-01-21 2023-02-16 2023-02-11 2023-03-18 2023-09-14 SMP for 2 sites-(FCE and Rail ant Selection ation nagement way line to U/uku Gully erosi on Control sites) GMS-ACRESAL/IC/22/01 / Co Component C: Institutional S Individual Consult Pending Impleme IDA / 70150 Post Limited 25,000.00 0.00 2023-05-15 2023-05-20 2023-06-10 2023-07-15 2023-10-13 nsultancy for M&E Baseline S trengthening and Project Ma ant Selection ntation tudies. nagement GMS-ACRESAL/IC/22/05 / Co nsultancy to Carryout studies Component C: Institutional S Individual Consult Pending Impleme to exploit and harnesses surf IDA / 70150 trengthening and Project Ma Post Limited 25,000.00 0.00 2023-05-22 2023-05-27 2023-06-17 2023-07-15 2023-10-13 ant Selection ntation ace and ground waters sourc nagement es i.e springs, wet lands. lak es and ponds Page 2 3 MONTHS PROCUREMENT PLAN-MRPLP Project information: Malawi COVID-19 Emergency Response and Health Systems Preparedness Project-P173806 Project Implementation Agency: Ministry of Health and Population Date of the Procurement Plan: April 2020 Period covered by this Procurement Plan: April 2020 to June 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement and Disposal of Public Assets Act, 2017 of the Republic of Malawi, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. In accordance with paragraph 5.4 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. 1 Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable for those contracts identified in the Procurement Plan tables; Works: Not Applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Applicable. Other Relevant Procurement Information: - (a). Thresholds for Request for Quotations Being emergency procurement, thresholds for Requests for Quotations (RFQ) has been increased to US$1 million for goods and services and US$5 million for works. Prequalification. Not expected for the works/goods packages in the procurement plan. Proposed Procedures for CDD Components: Not Applicable Reference to (if any) Project Operational/Procurement Manual: The Ministry of Health and Population team will prepare a Procurement manual. The Procurement Plan will also form part of the Project Implementation Manual. Any Other Special Procurement Arrangements: use of simple and fast procurement and selection methods fit for purpose in emergency situations including procurement from UN Agencies such as UNICEF, WHO and others, enabled and expedited by World Bank procedures and templates for procurement of medicines, medical supplies and equipment for emergency requirements Procurement Packages/Plan with Procurement Arrangements and Time Schedule: as per the table below: b) PROCUREMENT PLAN 1 2 3 4 5 6 7 8 9 10 2 Ref. Contract Title Compone Estimated Procur Procur Bank Expected Sourc Comme No. nt Cost (US$) ement ement Review date for e nts Catego Metho Requir IFBs/EOIs ry d and ement Marke t Appro ach 1. Procurement and 1, 3 2,687,043. GO UN, Post 15-Apr- MoHP distribution of 00 Direct Review 2020 ambulances and motor vehicles, tents for quarantine at ground crossings and IDTCs, medical equipment and supplies. 2. Printing of 50,000 No. 1 5,088.00 GO RFQ, Post 15-Apr- MoHP Health Declaration, Limited Review 2020 Surveillance and Case Management Form 3. Procurement of 1 220,000.0 GO DIR Post 15-Apr- MoHP cartridges for 0 Direct Review 2020 existing GeneXpert machines 4. Procurement of 2 15,000.00 GO RFQ, Post 20-Apr- MoHP computers, Laptops, Limited Review 2020 5. Procurement of 2 6,000.00 GO RFQ, Post 15-Apr- MoHP phones for EOC Limited Review 2020 6. Procurement of 2 50,000.00 NC RFQ, Post 15-Apr- MoHP grievance hotline Limited Review 2020 platform 7. Procurement of 2 1,000.00 GO RFQ, Post 15-Apr- MoHP refrigerator for EOC Limited Review 2020 8. Selection of a 1 5,000.00 CS INDV, Post 17-Apr- MoHP Consulting services Limited Review 2020 to assess minor works and determine scope of work for EOC 9. Selection of 1 562,363.0 CS INDV, Post 17-Apr- MoHP Consultants/Health 0 Direct Review 2020 workers to enhance Surge Capacity Key DIR – Direct Selection RFQ – Request for Quotations INDV – Selection of Individual Consultants Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: 3 Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 5 6 PROCUREMENT Malawi : Malawi COVID-19 Emergency Response and Health Systems Preparedness Project PLAN General Information Country: Malawi 2020-05-12 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173806 GPN Date: 2020-07-23 Project Name: Malawi COVID-19 Emergency Response and Health Systems Preparedness Project Loan / Credit No: IDA / D6200, IDA / D8870, IDA / 71770, TF / B8719 National TB Control Program Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MW-CHSU-244462-CW-RFQ / Request for Quota Renovations of Quarantine U Emergency COVID-19 Respo Request for Quota Single Stage - One E tions - Small Work 2022-04-0 IDA / D6200 Post Limited 21,139.00 0.00 Canceled 2021-08-08 2021-10-03 nits at Point of Entries- Chile nse tions nvelope s (Emergency) SP 1 ka International Airport D -Competitive Request for Quota MW-CHSU-244465-CW-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E tions - Small Work 2022-04-0 Minor renovations of the EO IDA / D6200 Post Limited 15,172.41 0.00 Canceled 2021-08-08 2021-10-03 nse tions nvelope s (Emergency) SP 1 C Office Building D -Competitive MW-CHSU-322292-CW-RFQ / Request for Quota Building of capacity of the E Emergency COVID-19 Respo Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-08-0 IDA / D8870 Post Limited 256,000.00 0.00 2022-12-08 2023-02-09 mergency Operation Centre t nse tions nvelope s (Emergency) SP lementation 8 hough Minor renovations of t D -Competitive he EOC Building Request for Quota MW-CHSU-325572-CW-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-04-0 IDA / 71770 Post Limited 250,000.00 0.00 2023-08-18 2023-10-06 Construction of EPI Fence nse tions nvelope s (Emergency) SP lementation 3 D -Competitive MW-CHSU-322598-CW-RFQ / Request for Quota Refurbishment of X Ray room Emergency COVID-19 Respo Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-03-3 s at Ntchisi Hospital, Chitipa IDA / 71770 Post Limited 60,000.00 0.00 2023-08-08 2023-10-02 nse tions nvelope s (Emergency) SP lementation 0 Hospital, MzuzuCentral Hosp D -Competitive ital Radiology departments Request for Quota MW-CHSU-322267-CW-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-03-0 Renavation of Quarantine Uni IDA / D8870 Post Limited 95,139.00 0.00 2023-07-16 2023-09-06 nse tions nvelope s (Emergency) SP lementation 4 t at Point of Entry D -Competitive Request for Quota MW-CHSU-322600-CW-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-05-2 Rehabilitation of 3 PHC Traini IDA / 71770 Post Limited 900,000.00 0.00 2023-10-29 2023-11-22 nse tions nvelope s (Emergency) SP lementation 0 ng Centres for HSAs D -Competitive Request for Quota MW-CHSU-322607-CW-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-06-2 IDA / 71770 Post Limited 150,000.00 0.00 2023-11-06 2023-12-28 Renovation of laboratories nse tions nvelope s (Emergency) SP lementation 5 D -Competitive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-CHSU-172790-GO-RFQ / Supporting National and Sub Request for Quota Single Stage - One E Procurement of phones for E IDA / D6200 -national, Prevention and Pr Post Limited 6,000.00 5,718.86 Completed 2020-05-26 2020-05-29 2020-06-19 2020-06-27 2020-07-10 2020-07-10 tions nvelope OC eparedness MW-CHSU-172782-GO-RFQ / Supporting National and Sub Request for Quota Single Stage - One E Procurement of computers, L IDA / D6200 -national, Prevention and Pr Post Limited 15,000.00 14,731.45 Completed 2020-05-28 2020-05-29 2020-06-23 2020-06-27 2020-07-14 2020-07-15 tions nvelope aptops eparedness MW-CHSU-177188-GO-UN / P Emergency COVID-19 Respo UN Agencies (Dire rocurement of Ambulances a IDA / D6200 Post Direct 900,000.00 919,471.24 Completed 2020-06-02 2020-05-29 2020-06-07 2020-05-29 2020-06-22 2020-06-06 2020-09-20 2021-01-06 nse ct) nd Rapid response vehicles MW-CHSU-172822-GO-UN / P Emergency COVID-19 Respo UN Agencies (Dire IDA / D6200 Post Direct 550,000.00 0.00 Canceled 2020-05-12 2020-05-19 2020-05-17 2020-06-21 2020-09-04 rocurement of Ambulances nse ct) MW-CHSU-172856-GO-DIR / Emergency COVID-19 Respo Procurement of cartridges for IDA / D6200 Post Direct Selection Direct 220,000.00 0.00 Canceled 2020-05-13 2020-05-19 2020-05-18 2020-06-15 2020-07-30 nse existing GeneXpert machines MW-CHSU-172814-GO-UN / P rocurement and distribution Emergency COVID-19 Respo UN Agencies (Dire of motor vehicles, tents for q IDA / D6200 Post Direct 2,137,043.00 0.00 Canceled 2020-05-15 2020-05-19 2020-05-20 2020-06-10 2020-09-08 nse ct) uarantine at ground crossing s and IDTCs, medical equipm ent and supplies. MW-CHSU-177194-GO-UN / P Emergency COVID-19 Respo UN Agencies (Dire rocurement and distribution IDA / D6200 Post Direct 1,700,000.00 3,568,488.24 Signed 2020-06-02 2020-06-02 2020-06-16 2020-04-07 2020-08-04 2020-08-19 2020-11-02 nse ct) of medical equipment and su pplies. MW-CHSU-172794-GO-RFQ / Supporting National and Sub Request for Quota Single Stage - One E Procurement of fridges, ultra IDA / D6200 -national, Prevention and Pr Post Limited 9,900.00 6,174.79 Completed 2021-05-01 2021-07-22 2021-05-21 2021-07-29 2021-06-11 2021-10-01 tions nvelope freezer and cooler boxes for eparedness PHIM and EOC MW-CHSU-244488-GO-RFQ / Procurement of ICT Equipme Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / D6200 Post Limited 180,623.00 160,656.20 Signed 2021-08-08 2021-07-23 2021-10-03 2021-08-13 2022-04-01 2021-11-30 nt for EOC Capacity building nse tions nvelope and Project Operations. MW-CHSU-257097-GO-DIR / Emergency COVID-19 Respo Procurement of COVID-19 Va IDA / D6200 Prior Direct Selection Direct 17,000,000.00 16,650,737.28 Signed 2021-10-11 2021-10-13 2021-10-16 2022-06-28 2021-10-31 2021-10-30 2023-10-01 nse ccines and related supplies MW-CHSU-281905-GO-RFQ / Procurement of materials an Emergency COVID-19 Respo Request for Quota Single Stage - One E d equipment for Infection Co IDA / D6200 Post Limited 285,000.00 0.00 Canceled 2022-03-20 2022-03-15 2022-04-15 2022-05-15 nse tions nvelope ntrol and Health Care Waste Management for Health Facili ties Page 1 MW-CHSU-283324-GO-RFQ / Procurement of computing d evices/tablets and laptops fo Emergency COVID-19 Respo Request for Quota Single Stage - One E r COVID 19 vaccine tracking IDA / D6200 Post Limited 260,000.00 251,426.65 Signed 2022-05-11 2022-05-30 2022-06-01 2022-06-22 2022-06-29 nse tions nvelope thorough the Electronic vacci ne registry, and Laboratory I nformation Management Syst ems Server MW-CHSU-281905-GO-RFQ. / Supply and delivery of Medic Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / D6200 Post Limited 414,000.00 334,685.49 Completed 2022-03-15 2022-03-15 2022-04-04 2022-04-11 2022-04-06 2022-04-12 al Waste Management items nse tions nvelope and equipment MW-CHSU-305304-GO-RFQ / Supply and delivery of ICT E Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / D6200 Post Limited 15,000.00 43,584.94 Terminated 2022-08-08 2022-08-08 2022-08-26 2022-09-17 2022-10-07 quipment( Laptops and Table nse tions nvelope ts) for Strengthening Online Presence MW-CHSU-293683-GO-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Supply and delivery of Centr IDA / D6200 Post Limited 202,400.00 186,056.87 Signed 2022-08-05 2022-08-08 2022-09-01 2022-08-24 2022-09-29 nse tions nvelope ifuges, Heat Blocks and Pipet tes MW-CHSU-306824-GO-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Supply and delivery of Covid IDA / D6200 Post Limited 203,000.00 122,730.74 Signed 2022-08-05 2022-08-02 2022-08-23 2022-09-08 2022-09-13 nse tions nvelope 19 Personal and Protective E quipment MW-CHSU-305304I-GO-RFQ / Supply and delivery of ICT E Emergency COVID-19 Respo Request for Quota Single Stage - One E Under Imple IDA / D6200 Post Limited 26,000.00 0.00 2022-08-08 2022-08-08 2022-09-07 2022-10-05 quipment ( Laptops and Tabl nse tions nvelope mentation ets) for strengthening Online Presence MW-CHSU-322318-GO-DIR / Procurement of Laboratory Emergency COVID-19 Respo Pending Impl IDA / D8870 Post Direct Selection Direct - National 1,110,000.00 0.00 2022-11-25 2022-11-30 2022-12-31 2023-12-31 Diagnostics equipment, reag nse ementation ents and Covid Test Kits MW-CHSU-322687-GO-DIR / Supply and delivery of essen tial medicines, medical suppli Emergency COVID-19 Respo Pending Impl IDA / 71770 Prior Direct Selection Direct - National 4,470,000.00 0.00 2023-06-11 2023-06-21 2023-07-16 2024-07-15 es and 10 Gene expert machi nse ementation nes, biohazard bags, family p lanning products and birth co ntrols MW-CHSU-322694-GO-DIR / Supply and delivery 0f Rapid Emergency COVID-19 Respo Under Imple IDA / 71770 Post Direct Selection Direct - National 1,700,000.00 0.00 2023-07-16 2023-05-12 2023-07-26 2023-05-31 2023-08-19 2024-02-15 response vehicles and mobile nse mentation vans for 6 districts MW-CHSU-322696-GO-RFB / Supply and delivery of CT Sc anner for KCH, Digital Xray Emergency COVID-19 Respo Open - Internationa Single Stage - One E Under Imple IDA / 71770 Prior Request for Bids 5,950,000.00 0.00 2023-05-07 2023-05-03 2023-05-21 2023-06-20 2023-06-18 2023-07-09 2023-08-02 2023-11-30 Machines, Ultra sound scanni nse l nvelope mentation ng machines and High Thro ughput Sequencer Magnetic Imaging Machines MW-CHSU-322798-GO-RFB / Emergency COVID-19 Respo Single Stage - One E Pending Impl Procurement of push bikes a IDA / 71770 Prior Request for Bids Open - National 2,407,000.00 0.00 2023-01-13 2023-02-03 2023-02-17 2023-03-03 2023-04-07 2023-10-04 nse nvelope ementation nd motor cycles MW-CHSU-322859-GO-DIR / Emergency COVID-19 Respo Pending Impl Procurement of 1 million dos IDA / 71770 Prior Direct Selection Direct - National 7,500,000.00 0.00 2023-03-26 2023-04-02 2023-05-14 2024-05-13 nse ementation es of Vaccine MW-CHSU-322878-GO-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Under Imple Procurement of ultra low tem IDA / 71770 Post Limited 234,900.00 0.00 2022-12-02 2023-03-07 2023-01-09 2023-03-06 nse tions nvelope mentation perature freezer MW-CHSU-322892-GO-RFQ / Procurement of a set of PA s Emergency COVID-19 Respo Request for Quota Single Stage - One E Under Imple IDA / 71770 Post Limited 44,600.00 0.00 2022-12-08 2023-01-19 2023-03-16 ystem, speakers TV screen, nse tions nvelope mentation megaphone and heavy duty printer MW-CHSU-325544-GO-DIR / Supply and delivery of essen Emergency COVID-19 Respo Under Imple TF / B8719 Prior Direct Selection Direct - National 5,000,000.00 0.00 2022-12-01 2022-11-21 2022-12-06 2022-11-22 2022-12-28 2023-12-28 tial medicines to meet the ur nse mentation gent need of Health Sector MW-CHSU-331110-GO-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Under Imple Supply and delivery of ICT E IDA / 71770 Post Limited 400,000.00 0.00 2023-01-11 2023-01-18 2023-03-01 2023-04-26 nse tions nvelope mentation quipment for PIU MW-CHSU-322587I-NC-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Under Imple Procurement of Printing Servi IDA / 71770 Post Limited 139,000.00 0.00 2022-11-18 2022-11-18 2022-12-09 2023-01-05 nse tions nvelope mentation ces for Policies,Guidelines an d SOPs MW-CHSU-354763-GO-RFQ / Supply and delivery of Labor atory supplies ( 2000 petri di Contingent Emergency Resp Request for Quota Single Stage - One E Under Imple shes, 10000 disposable Inocu IDA / 71770 Post Limited 750,000.00 0.00 2023-04-14 2023-05-23 2023-05-06 2023-11-02 onse tions nvelope mentation lating loop, 30 carry blair,30 alkaline peptone water and 2 0 000 cholera RDTs and proc urement of sequencing Rea gents MW-CHSU-354774-GO-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Under Imple Supply and delivery of Medic IDA / 71770 Post Limited 320,000.00 0.00 2023-04-15 2023-05-30 2023-11-26 nse tions nvelope mentation al Waste incinerators MW-CHSU-355126-GO-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Under Imple Supply and delivery of 240 Li IDA / 71770 Post Limited 90,000.00 0.00 2023-04-19 2023-04-17 2023-06-07 2023-09-05 nse tions nvelope mentation tres bins for waste storage a nd bin liners MW-CHSU-356667-GO-RFQ / Supply and delivery of Wate r Testing Kits, Residual Chlor Emergency COVID-19 Respo Request for Quota Single Stage - One E Under Imple IDA / 71770 Post Limited 376,000.00 0.00 2023-05-05 2023-06-09 2023-07-14 ine Testing Kits and Waste M nse tions nvelope mentation anagement Containers for Ch olera Control Activities in Dis trict Councils MW-CHSU-322884-GO-RFB / Emergency COVID-19 Respo Single Stage - One E Pending Impl Procurement of PPE and esse IDA / 71770 Post Request for Bids Open - National 1,300,000.00 0.00 2023-09-24 2023-10-08 2023-11-05 2023-11-19 2023-12-24 2023-12-29 nse nvelope ementation ntial medical equip Page 2 MW-CHSU-322886-GO-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Pending Impl IDA / 71770 Post Limited 110,000.00 0.00 2023-09-06 2023-10-12 2024-04-09 Procurement of IEC Materials nse tions nvelope ementation MW-CHSU-322791-GO-RFB / Supply and delivery of end u Emergency COVID-19 Respo Open - Internationa Single Stage - One E Pending Impl IDA / 71770 Post Request for Bids 1,110,000.00 0.00 2023-09-01 2023-09-15 2023-10-13 2023-10-27 2023-11-24 2024-03-23 ser devices ( Tablets) for vac nse l nvelope ementation cination tracking MW-CHSU-322784-GO-RFB / Emergency COVID-19 Respo Open - Internationa Single Stage - One E Pending Impl Supply and delivery of comp IDA / 71770 Post Request for Bids 1,300,000.00 0.00 2023-09-29 2023-10-09 2023-11-06 2023-12-06 2024-01-03 2024-07-01 nse l nvelope ementation lete setup equipment for 2 D ata Centres MW-CHSU-322810-GO-RFQ / Procurement of Oxygen and Emergency COVID-19 Respo Request for Quota Single Stage - One E Pending Impl IDA / 71770 Post Limited 325,000.00 0.00 2023-08-08 2023-09-22 2023-11-17 installation of Oxygen Manifo nse tions nvelope ementation ld Systems and Oxygen acce ssories MW-CHSU-293687-GO-RFB / Supply, delivery, installation Emergency COVID-19 Respo Single Stage - One E Pending Impl IDA / D6200 Post Request for Bids Limited 1,167,885.00 0.00 2024-01-01 2024-01-08 2024-01-29 2024-02-19 2024-03-11 2024-09-07 and commissioning of oxyge nse nvelope ementation n plant for Zomba Central Ho spital MW-CHSU-317442-GO-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Pending Impl Supply and delivery of Suppl IDA / D6200 Post Limited 152,941.00 0.00 2023-12-02 2024-02-03 2024-08-01 nse tions nvelope ementation y Chain Vehicles MW-CHSU-322808-GO-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Pending Impl Procurement of lab supplies IDA / 71770 Post Limited 40,000.00 0.00 2023-10-08 2023-11-22 2024-01-17 nse tions nvelope ementation and power back up for 15 P OE MW-CHSU-322691-GO-RFQ / Supply and delivery of ICT Eq Emergency COVID-19 Respo Request for Quota Single Stage - One E Pending Impl IDA / 71770 Post Limited 254,100.00 0.00 2022-12-09 2023-01-13 2023-07-12 uipment for EPI ( Desktops, nse tions nvelope ementation Tablets & Protective Covers a nd Printers) MW-CHSU-356666-GO-DIR / Emergency COVID-19 Respo Direct - Internation Under Revie Procurement of Medicines an IDA / 71770 Prior Direct Selection 9,000,000.00 0.00 2023-06-04 2023-05-30 2023-06-09 2023-06-02 2023-07-05 2024-07-04 nse al w d Medicinal Supplies for Chol era Response MW-CHSU-366659-GO-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Pending Impl Supply and delivery of 3 Mo IDA / 71770 Post Limited 300,000.00 0.00 2023-06-24 2023-08-19 2024-02-15 nse tions nvelope ementation bile Vans Units for communit y mobilization NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-CHSU-172855-NC-RFQ / Supporting National and Sub Request for Quota Single Stage - One E Procurement of grievance ho IDA / D6200 -national, Prevention and Pr Post Limited 50,000.00 0.00 Canceled 2020-05-16 2020-06-18 2021-06-18 tions nvelope tline platform eparedness MW-CHSU-245209-NC-DIR / Implementation Managemen Upgrading of Tompro Accou IDA / D6200 t and Monitoring and Evaluat Post Direct Selection Direct 35,000.00 32,833.00 Signed 2021-07-30 2021-07-29 2021-08-04 2020-12-09 2021-08-20 2020-12-16 2022-08-20 nting System ion MW-CHSU-293684-NC-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / D6200 Post Limited 95,260.00 60,168.28 Completed 2022-05-17 2022-05-30 2022-06-17 2022-06-25 2022-07-15 2022-09-03 Printing of Vaccine Publicity nse tions nvelope Materials MW-CHSU-322587-NC-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Procurement of printing serv IDA / D8870 Post Limited 139,000.00 0.00 Canceled 2022-11-23 2022-11-18 2022-12-30 2023-01-02 nse tions nvelope ices of policies, guidelines an d SOPs MW-CHSU-355904-NC-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Pending Impl IDA / 71770 Post Limited 25,000.00 0.00 2023-04-21 2023-05-19 2023-06-09 Printing of EBS reporting too nse tions nvelope ementation ls MW-CHSU-322789-NC-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Pending Impl Provision of services for main IDA / 71770 Post Limited 24,000.00 0.00 2023-07-09 2023-08-23 2024-08-22 nse tions nvelope ementation tenance of Genomic Sequenc ers MW-CHSU-322766-NC-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Pending Impl Service contract for MRI and IDA / 71770 Post Limited 50,000.00 0.00 2023-12-10 2024-01-17 2024-07-15 nse tions nvelope ementation CT Scanners maintenance se rvice MW-CHSU-322809-NC-RFQ / Emergency COVID-19 Respo Request for Quota Single Stage - One E Pending Impl Printing of CHBC policy and IDA / 71770 Post Limited 270,000.00 0.00 2023-10-29 2023-12-24 2024-01-21 nse tions nvelope ementation guidelines and COVID 19 PFM Guidelines CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-CHSU-322672-CS-QCBS / Consultancy services for su Emergency COVID-19 Respo Consultant Qualifi Pending Impleme IDA / 71770 Post Open - National 300,000.00 0.00 2023-08-31 2023-09-21 2023-10-12 2023-10-22 2023-11-12 2024-02-10 pervision of construction of nse cation Selection ntation Infectious Disease Wards at QECH MW-CHSU-322662-CS-QCBS / Consultant to supervise re Contingent Emergency Resp Consultant Qualifi Pending Impleme IDA / 71770 Post Open - National 300,000.00 0.00 2023-07-02 2023-07-23 2023-08-20 2023-08-21 2023-09-14 2023-09-23 novation of QECH and Zomba onse cation Selection ntation Central Hospital MW-CHSU-322686-CS-QCBS / Preparation of Detailed desi Emergency COVID-19 Respo Quality And Cost- Pending Impleme IDA / 71770 Post Open - National 500,000.00 0.00 2023-09-24 2023-10-15 2023-11-12 2023-11-26 2023-12-10 2023-12-25 2024-01-14 2024-04-13 gns and BOQ s for the constr nse Based Selection ntation uction of Public Health Institu te MW-CHSU-366951-CS-CQS / Consultancy services to desi Emergency COVID-19 Respo Consultant Qualifi Pending Impleme IDA / 71770 Post Limited 200,000.00 0.00 2023-06-25 2023-07-09 2023-07-23 2023-08-20 2024-02-16 gn and supervise renovation nse cation Selection ntation of Kamuzu Central Hospital Page 3 MW-CHSU-366936-CS-QCBS / Consultancy to Design and Emergency COVID-19 Respo Consultant Qualifi Pending Impleme IDA / 71770 Post Limited 200,000.00 0.00 2023-06-25 2023-07-09 2023-07-23 2023-08-07 2024-02-03 supervise the Renovation of nse cation Selection ntation Mzuzu Central Hospital MW-CHSU-366958-CS-CQS / Consultancy services to Desi Emergency COVID-19 Respo Consultant Qualifi Pending Impleme IDA / 71770 Post Limited 200,000.00 0.00 2023-06-25 2023-07-09 2023-07-23 2023-08-07 2024-02-03 gn and supervise the Rehabil nse cation Selection ntation itaion of Zomba Central Hos pital MW-CHSU-367014-CS-CQS / Consultancy services to sup Emergency COVID-19 Respo Consultant Qualifi Pending Impleme IDA / 71770 Post Limited 200,000.00 0.00 2023-06-25 2023-07-09 2023-07-23 2023-08-20 2024-02-16 ervise the renovation of Que nse cation Selection ntation en Elezabeth Central Hospital INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-CHSU-172857-CS-INDV / Selection of a Consulting ser Emergency COVID-19 Respo Individual Consult IDA / D6200 Post Limited 5,000.00 0.00 Canceled 2020-06-05 2020-06-10 2020-07-01 2020-07-18 2020-08-17 vices to assess minor works nse ant Selection and determine scope of work for EOC MW-CHSU-186787-CS-INDV / Implementation Managemen Individual Consult IDA / D6200 Post Open 36,000.00 23,632.92 Signed 2020-08-04 2020-08-18 2020-08-19 2020-11-25 2020-08-22 2020-12-08 2020-09-01 2020-12-16 2021-09-01 Assistant Procurement Speci t and Monitoring and Evaluat ant Selection alist ion MW-CHSU-186798-CS-INDV / Implementation Managemen Individual Consult Medical Waste Management IDA / D6200 t and Monitoring and Evaluat Post Open 41,000.00 25,208.45 Signed 2020-08-04 2020-08-18 2020-08-19 2020-11-25 2020-08-22 2020-12-08 2020-09-01 2020-12-17 2021-09-01 ant Selection Specialist ion MW-CHSU-186802-CS-INDV / Implementation Managemen Individual Consult IDA / D6200 Post Open 36,000.00 26,783.98 Signed 2020-08-04 2020-08-18 2020-08-19 2020-11-25 2020-08-22 2020-12-08 2020-09-01 2020-12-15 2021-09-01 Project Accountant t and Monitoring and Evaluat ant Selection ion MW-CHSU-186806-CS-INDV / Implementation Managemen Individual Consult Assistant Monitoring and Eval IDA / D6200 t and Monitoring and Evaluat Post Open 36,000.00 23,632.92 Terminated 2020-08-04 2020-08-18 2020-08-19 2020-11-25 2020-08-22 2020-12-08 2020-09-01 2020-12-15 2021-09-01 ant Selection uation Specialist ion MW-CHSU-228548-CS-CDS / Implementation Managemen Provision of Accounting Softw IDA / D6200 t and Monitoring and Evaluat Post Direct Selection Direct 35,000.00 0.00 Canceled 2021-04-20 2021-07-23 2021-04-30 2021-07-04 2021-12-31 are upgrading services ion MW-CHSU-258710-CS-INDV / Implementation Managemen Individual Consult Consulting services for Assist IDA / D6200 t and Monitoring and Evaluat Post Limited 36,000.00 26,130.72 Signed 2021-10-28 2021-11-04 2021-11-18 2021-12-12 2021-11-25 2022-01-11 2021-12-30 2022-01-14 2022-12-30 ant Selection ant Monitoring and Evaluatio ion n Specialist MW-CHSU-325527-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement IDA / D8870 Post Direct - National 16,000.00 0.00 2022-11-18 2023-01-06 2022-11-28 2022-12-03 2022-12-13 2023-06-11 Individual Consultant- Data M nse ant Selection ation anager MW-CHSU-322636-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Individual consultnat- Project IDA / 71770 Post Open - National 190,000.00 0.00 2022-12-01 2022-12-12 2023-01-15 2023-01-22 2023-02-08 2024-02-08 nse ant Selection ation Coordinator MW-CHSU-322640-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Individual Consultant- Monito IDA / 71770 Prior Open - National 162,000.00 0.00 2022-11-25 2023-02-09 2023-01-29 2023-02-05 2023-03-08 2023-04-13 nse ant Selection ation ring and Evaluation Specialis t MW-CHSU-322646-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Individual Consultant- Financ IDA / 71770 Prior Open - National 162,000.00 0.00 2022-11-25 2023-04-05 2023-01-09 2023-01-16 2023-02-02 2024-02-02 nse ant Selection ation e Management Specialist MW-CHSU-322650-CS-INDV / Contingent Emergency Resp Individual Consult Under Implement Individual Consultant- Procur IDA / 71770 Prior Open - National 162,000.00 0.00 2022-11-25 2022-12-13 2023-01-09 2023-01-16 2023-02-02 2023-03-10 onse ant Selection ation ement Specialist MW-CHSU-322651-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Individual Consultant - Enviro IDA / 71770 Prior Open - National 162,000.00 0.00 2022-11-25 2022-12-14 2023-01-09 2023-01-16 2023-01-24 2024-01-24 nse ant Selection ation nmental and Social Specialist MW-CHSU-325524-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Individual Consultant- Data O IDA / D8870 Post Direct - National 12,000.00 0.00 2022-11-28 2022-11-21 2022-12-10 2022-12-15 2022-12-25 2023-06-23 nse ant Selection ation fficer Surveillance MW-CHSU-325526-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Consultancy Services- Data O IDA / D8870 Post Direct - National 12,000.00 0.00 2022-11-28 2022-11-21 2022-12-08 2022-12-13 2022-12-23 2023-06-21 nse ant Selection ation fficer- Case Management MW-CHSU-325528-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Consultancy services for Dat IDA / D8870 Post Direct - National 12,000.00 0.00 2022-11-28 2023-01-05 2022-12-08 2022-12-13 2022-12-23 2023-06-21 nse ant Selection ation a Officer- Laboratory MW-CHSU-327245-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Individual Consultancy- Recr IDA / D8870 Post Direct - National 12,000.00 0.00 2022-11-28 2022-11-21 2022-12-08 2022-12-13 2022-12-23 2023-06-21 nse ant Selection ation uitment of Data Officer- Case Management MW-CHSU-327247-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Individual Consultant- Data O IDA / D8870 Post Direct - National 12,000.00 0.00 2022-11-28 2023-01-05 2022-12-08 2022-12-13 2022-12-23 2023-06-21 nse ant Selection ation fficer Case Management MW-CHSU-327250-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Individual Consultancy Data IDA / D8870 Post Direct - National 12,000.00 0.00 2022-11-28 2023-01-05 2022-12-08 2022-12-13 2022-12-23 2023-06-21 nse ant Selection ation Officer Surveillance MW-CHSU-327251-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Individual Consultancy - Data IDA / D8870 Post Direct - National 12,000.00 0.00 2022-11-28 2022-11-21 2022-12-08 2022-12-13 2022-12-23 2023-06-21 nse ant Selection ation Officer- Surveillance MW-CHSU-327259-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Consultacny Services- Data O IDA / D8870 Post Direct - National 12,000.00 0.00 2022-11-28 2022-11-21 2022-12-08 2022-12-13 2022-12-23 2023-06-21 nse ant Selection ation fficer- Laboratory MW-CHSU-327261-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Consultancy Services Data Of IDA / D8870 Post Direct - National 12,000.00 0.00 2022-11-28 2022-11-21 2022-12-08 2022-12-13 2022-12-23 2023-06-21 nse ant Selection ation ficer- Laboratory Page 4 MW-CHSU-327266-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Consultancy services for Dat IDA / D8870 Post Direct - National 12,000.00 0.00 2022-11-28 2022-11-21 2022-12-08 2022-12-13 2022-12-23 2023-06-21 nse ant Selection ation a Officer- Surveillance MW-CHSU-329216-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Consultancy Services for Acc IDA / D8870 Post Open - National 36,000.00 0.00 2022-12-01 2022-12-21 2023-01-09 2023-01-16 2023-01-24 2023-01-24 nse ant Selection ation ounts Assistant MW-CHSU-344844-CS-INDV / Emergency COVID-19 Respo Individual Consult Under Implement Individual Consultant- Life an IDA / 71770 Post Open - National 105,000.00 0.00 2023-02-28 2023-03-15 2023-04-11 2023-05-02 2023-06-06 2023-12-03 nse ant Selection ation d Fire Safety Specialist MW-CHSU-322677-CS-INDV / Emergency COVID-19 Respo Individual Consult Pending Impleme Consultancy services for Tec IDA / 71770 Post Limited 20,000.00 0.00 2023-07-02 2023-07-09 2023-07-16 2023-08-06 2024-08-05 nse ant Selection ntation hnical assistance to update N DVP MW-CHSU-362881-CS-INDV / Individual Consultancy Servic Emergency COVID-19 Respo Individual Consult Under Implement IDA / 71770 Post Limited 20,000.00 0.00 2023-06-11 2023-06-07 2023-06-18 2023-06-25 2023-07-06 2023-08-15 es to develop COVID 19 Inte nse ant Selection ation rgrated Vaccine Deployment Plan Page 5 18-MONTH PROCUREMENT PLAN Project information: Phase I of Improved Child Survival Program for Human Capital MPA- P167156-- Immunization Plus and Malaria Progress by Accelerating Coverage and Transforming Services (IMPACT) Project Project Implementation Agencies: Federal Ministry of Health (NMEP and NPHCDA) Date of the Procurement Plan: January 1, 2020 Period covered by this Procurement Plan: January 2020 to June 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016), revised on November 1, 2017 and on August 1, 2018 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Nigeria Public Procurement Act 2007, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [15% is applicable for those contracts identified in the Procurement Plan tables]; Works: [ 7.5% is applicable for those contracts identified in the Procurement Plan tables] I. Threshold for Prior Review – Goods, Works, Non-Consulting Services and Consulting Services Prior-review Thresholds Thresholds for Procurement Methods High Substanti Moderate Low Risk Goods, IT & Non-Consulting Shortlist of National Procurement Type Risk al Risk Risk Works ($'000) ($'000) ($'000) ($'000) Services Consultants Request Request Engineering Open for for Open Open Open Consultin & Quotatio Quotatio 10,0 15,0 20,0 Internatio National internatio National g Constructio Works n or n or 5,000 00 00 00 nal or ICB or NCB National nal or ICB or NCB National Services n ($'000) ($'000) ($'000) ($'000) ($'000) Supervision Shopping Shopping ($'000) ($'000) ($'000) Goods, IT & Non- 2,0 4,0 6,0 Consulting Services 1,500 00 00 00 ≧ < ≦ ≧ < ≦ < ≦ Consultants 1,0 2,0 4,0 20,0 20,0 5,0 5,0 1 3 5 200 (Firms) 500 00 00 00 00 00 00 00 00 00 00 Post Review: All contracts not subject to prior review shall be subject to post review. Summary of the procurement packages for Goods, Works and Non-Consulting Services (Planned for the first 18 months after project effectiveness): Selec Evaluation Market tion Options Approa Review Meth (Most Expected ch Prequal- Domestic Expected by od Advantageo date of Sr. Contract Estimated (Open- ification Preferenc date of Bank (RFP, us Bid, bid/ No Description Cost (US$) Nation (Yes/ e Contract (Prior/ RFB, BAFO, proposal al/ No) (Yes/No) Signature Post) RFQ, Rated opening Limited DS Criteria etc.) etc.) etc.) Nigeria Malaria Elimination Programme (NMEP) GOODS Procurement of Long Lasting Open- Insecticide Internati Most Treated Nets 45,852,523 3rd Feb 13th July 1 Prior onal RFB Advantageou No Yes (Mass .29 2020 2020 s Bid Campaign & Routine Distribution) Procurement of Artemisinin based Open - Most National 3rd Feb 13th July 2 Combination Post 2,381,472 RFB Advantageou No No 2020 2020 Therapy (ACT)- s Bid (Public and Private) Procurement of Open- Most Rapid National 3rd Feb 13th July 3 Post 1,960,202 RFB Advantageou No No Diagnostics 2020 2020 s Bid Tests (RDTs) Most Artesunate Open- 3rd Feb 13th July 4 Post 420,881.89 RFB Advantageou No No Injection National 2020 2020 s Bid Sulphodoxine/P Most Open - 3rd Feb 13th July 5 yrimethamine_I Post 612,322 RFB Advantageou No No National 2020 2020 PTp s Bid Amodiaquine/Su Most lphodoxine/Pyri 2,990,781. Open - 3rd Feb 13th July 6 Post RFB Advantageou No No methamine 47 National 2020 2020 s Bid (SPAQ) Most Open - 3rd Feb 13th July 7 Sharp Boxes Post 152,122,43 RFB Advantageou No No National 2020 2020 s Bid Most Microscope Open - 3rd Feb 13th July 8 Post 491,031 RFB Advantageou No No commodities National 2020 2020 s Bid NON-CONSULTING SERVICES - NMEP State Malaria Elimination MOU/P Programme erform 10th 2,250,000. 9th July 1 (SMEP) Prior Limited ance Rated Criteria No NA February 00 2020 Performance Contra 2020 Contract and ct Operations National Malaria Elimination MOU/P Programme erform 10th 1,500,000. 9th July 2 (NMEP) Prior Limited ance Rated Criteria No NA February 00 2020 Performance Contra 2020 Contract and ct Operations National Primary Health Care Development Agency (NPHCDA) GOODS Procurement of Most vaccines and 61,380,767 5th Feb 13th July 1 Prior UN RFB Advantageou No No devices for .00 2020 2020 s Bid immunization Procurement and maintenance of Most UN 5th Feb 13th July 2 Generators and Post 900,000.00 RFB Advantageou No No System 2020 2020 Cold Chain s Bid Equipment (CCEs) Procurement and installation of Cold Chain Most 4,500,000. 5th Feb 13th July 3 Hubs (3 Prior UN RFB Advantageou No No 00 2020 2020 walking-in cold s Bid rooms) in Lagos Procurement of Emergency Transport 5th Feb 13th July 4 Service (ETS) Post 45,101.72 Limited RFQ Rated Criteria No No 2020 2020 vouchers, handbooks, and logbooks Procurement of Most Open- 5th Feb 13th July 5 equipment for Post 281,969.00 RFB Advantageou No No National 2020 2020 call centre s Bid Most Procurement of Open- 5th Feb 13th July 6 Post 969,529.00 RFB Advantageou No No 14 vehicles National 2020 2020 s Bid Procurement of 5th Feb 13th July 7 14 computer Post 14,000 Limited RFQ Rated Criteria No No 2020 2020 sets II. Summary of the procurement packages for Consulting Services -Planned for the first 18 months after project effectiveness): Selection Market Method Review Approach Expected Expected Estimate (QCBS, Shortlisti Sr. by Bank (Open - date of bid/ date of Contract Description d Cost FBS, ng No (Prior/ International proposal Contract (US$) LCBS, (Yes/ No) Post) / National/ opening Signature QBS, CQS, etc.) DS etc.) Nigeria Malaria Elimination Programme (NMEP) NGOs Service Contract (for 5 11,525,51 Open 10th Feb 31st Aug 1 Prior QCBS Yes states) 1.00 International 2020 2020 Technical Assistance to SMEP in 5 participating states, 630,000.0 10th Feb 31st July 2 Prior Limited INDV No multiple contracts by 0 2020 2020 different consultants Technical Assistance to NMEP (including procurement 150,000.0 10th Feb 31st July 3 Post Limited INDV No consultant), multiple 0 2020 2020 contracts. Independent Verification 300,000.0 Open- 10th Feb 31st July 4 Post CQS No Agents (IVA) for NGOs 0 National 2020 2020 Social and Behavioral Change 3,000,000. Open 10th Feb 31st Aug 5 Prior QCBS Yes Communication (SBCC) 00 International 2020 2020 Operations research on 2,131,148. Open 10th Feb 31st Aug 6 Prior QCBS Yes disease vector mapping 00 International 2020 2020 Operations research on entomological surveillance by 655,738.0 10th Feb 31st July 7 Prior Direct DS No Nigeria Institute of 0 2020 2020 Medical Research (NIMR) Operations research on therapeutic efficacy by 655,738.0 10th Feb 31st July 8 Prior Direct CDS No Nigeria Institute of 0 2020 2020 Medical Research (NIMR) Consultancy on warehouse 10th Feb 31st July 9 Post 32,131.00 Limited INDV No assessment 2020 2020 Programme Management Training (case management, 2,000,000. 10th Feb 31st July 10 Prior Limited INDV No M&E, IVM etc.) Multiple 00 2020 2020 Contracts National Primary Health Care Development Agency (NPHCDA) Technical assistance support 9,869,000. 10th Feb 31st July 1 to government for polio Prior UN CDS No 00 2020 2020 surveillance Technical assistance support to government for polio 15,301,00 10th Feb 31st July 2 Supplemental Immunization Prior UN CDS No 0.00 2020 2020 Activities (SIAs) surveillance through WHO Technical assistance support to government for polio 4,830,000. 10th Feb 31st July 3 logistics and social Prior UN CDS No 00 2020 2020 mobilization for polio through UNICEF Procurement of consultant for 10th Feb 31st July 4 Post 20,000.00 Limited INDV No landscape survey (SQUATS) 2020 2020 Technical assistance support 837,673.1 10th Feb 31st July 5 Prior Open-National INDV No to 12 SPHCDA PIU 3 2020 2020 Technical assistance support 10th Feb 31st July 6 Post 89,750.63 Limited INDV No to NPHCDA PIU 2020 2020 Procurement of Emergency Transport Services (ETS), MOU with National Union of 530,794.3 10th Feb 31st July 7 Prior Direct CDS No Road Transport Workers 9 2020 2020 (NURTW) and NACTOROMAS Training of ETS service providers, MOU with Federal 207,672.0 10th Feb 31st July 8 Post Direct CDS No Road Safety Commission 0 2020 2020 (FRSC) Conduct PAPA – Lot Quality Assurance Sampling, MOU 2,213,850. 10th Feb 31st July 9 Prior Limited CDS No with National Bureau of 00 2020 2020 Statistics (NBS) Consultancy for RCT research 1,902,356. 10th Feb 31st Aug 10 services with Nigerian Prior Open-National QCBS Yes 00 2020 2020 Universities Procurement of operations 1,689,751. Open- 10th Feb 31st Aug 11 Prior QCBS Yes research services 00 International 2020 2020 Support to Cold Chain Equipment (CCE) 23,000,00 10th Feb 31st July 12 Prior UN CDS No optimization platform 0.00 2020 2020 through UNICEF Technical assistance to 1,553,185. 10th Feb 31st July 13 LGHAs (89 total), multiple Post Open-National INDV No 50 2020 2020 contracts Technical assistance 310,076.0 10th Feb 31st July 14 Post Open-National QCBS Yes management firm 0 2020 2020 10th Feb 31st July 15 IVA for performance contract Post 300,000 Open-National CQS No 2020 2020 Procurement of services 3,203,345 Open- 10th Feb 31st Aug 16 for GIS imagery and Prior QCBS Yes .45 International 2020 2020 microplanning Procurement of Social Behaviour Change Open- 10th Feb 31st Aug 17 Prior 5,000,000 QCBS Yes Communication (SBCC) International 2020 2020 services Contracting of direct 2,000,000. Open- 10th Feb 31st Aug 18 Prior QCBS Yes facility financing firms 00 International 2020 2020 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a 1Guidelineson Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Nigeria : Nigeria Improved Child Survival Program for Human Capital MPA PLAN General Information Country: Nigeria 2022-02-09 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167156 GPN Date: Project Name: Nigeria Improved Child Survival Program for Human Capital MPA Loan / Credit No: IDA / 65390 Sokoto State IMPACT Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-SOKOTO IMPACT-277856 Component 2: Immunization Request for Quota Single Stage - One E Under Imple -GO-RFQ / Procurement of 2 IDA / 65390 Post Open - National 151,818.80 0.00 2022-02-13 2022-08-18 2022-04-10 2022-10-07 Plus tions nvelope mentation Nos. 4WD Hilux for Monitorin g and Supervision NG-SOKOTO IMPACT-277818 -GO-RFQ / Procurement and I Component 2: Immunization Request for Quota Single Stage - One E IDA / 65390 Post Limited 30,844.20 0.00 Canceled 2022-02-20 2022-02-15 2022-03-29 2022-05-28 nstallation of Office Furniture Plus tions nvelope and Equipment for PIU Office NG-SOKOTO IMPACT-277829 -GO-RFQ / Procurement of 1 2 Laptops , 2 Desktop Compu Component 2: Immunization Request for Quota Single Stage - One E Under Imple IDA / 65390 Post Limited 26,685.60 0.00 2022-02-20 2022-03-27 2022-03-29 2022-05-28 ters, 2 Printers,1 Big Printer, Plus tions nvelope mentation 2 Photocopiers, 1 scanner, 1 projectors, 1 Cameras and 1 public address system. NG-SOKOTO IMPACT-277842 Component 2: Immunization Request for Quota Single Stage - One E Under Imple -GO-RFQ / Procurement and I IDA / 65390 Post Limited 23,654.10 0.00 2022-02-11 2022-02-08 2022-03-27 2022-05-26 Plus tions nvelope mentation nstallation of 50KVA Generat or Set NG-SOKOTO IMPACT-277857 Component 2: Immunization Request for Quota Single Stage - One E Under Imple IDA / 65390 Post Limited 18,413.20 0.00 2022-02-19 2022-07-26 2022-04-04 2022-06-03 -GO-RFQ / Provision of Intern Plus tions nvelope mentation et Facilities NG-SOKOTO IMPACT-362946 -GO-RFQ / Provision of Sun S Component 2: Immunization Request for Quota Single Stage - One E Under Imple IDA / 65390 Post Open - National 8,785.20 0.00 2023-06-02 2023-07-28 2024-01-24 hade PIU Official Vehicles at t Plus tions nvelope mentation he Office Complex NG-SOKOTO IMPACT-363884 -GO-RFQ / Procurement of 2 Laptops for Finance Officer a Component 2: Immunization Request for Quota Single Stage - One E Pending Impl IDA / 65390 Post Open - National 5,760.90 0.00 2023-06-04 2023-07-30 2024-01-26 nd Admin Secretary ,3 Printe Plus tions nvelope ementation rs for PM, DPM and Admin Un it, 1 No Projector and 1No Pu blic Address System NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-SOKOTO IMPACT-327560 Component 2: Immunization Under Implement -CS-CDS / Flexible Accountin IDA / 65390 Post Direct Selection Direct - National 12,216.90 0.00 2022-11-28 2022-12-20 2022-12-08 2023-02-11 2023-08-10 Plus ation g Software Training NG-SOKOTO IMPACT-330816 -CS-INDV / DECENTRALIZED F Component 2: Immunization Individual Consult Pending Impleme IDA / 65390 Post Open - National 8,837.21 0.00 2023-01-10 2023-02-28 2023-03-21 2023-04-25 2023-10-22 ACILITY FINANCING (DFF) NA Plus ant Selection ntation TIONAL CONSULTANT ENGAG EMENT Page 1 PROCUREMENT PLAN (Textual Part) Project information: [Benin] [Benin Global Partnership for Education Project Phase 3] [P-167432] Project Implementation agency: Ministry of Preschool and Primary Education] Date of the Procurement Plan: January 6, 2020 Period covered by this Procurement Plan: January 6 to December 31, 2020. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is applicable for those contracts identified in the Procurement Plan tables]; Works: [is applicable for those contracts identified in the Procurement Plan tables] PROCUREMENT Benin : Benin Global Partnership for Education Project Phase 3 PLAN General Information Country: Benin 2020-03-05 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167432 GPN Date: 2020-03-02 Project Name: Benin Global Partnership for Education Project Phase 3 Loan / Credit No: / , TF / B0364 PROJECT TECHNICAL SUPPORT AND MONITORING UNIT Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-UATS-152375-GO-RFB / A cquisition d’un (01) véhicule 4X4 station wagon et d’un (0 1) véhicule PICK – UP 4X4 do Component 1 : Improving th Single Stage - One E Under Imple uble cabines au profit de l'Un / Post Request for Bids Open - National 258,621.00 0.00 2020-01-28 2020-10-16 2020-02-02 2020-03-15 2020-11-30 2020-04-14 2020-12-01 2020-05-19 2020-11-15 e Quality of Basic Education nvelope mentation ité d’Appui Technique et de S uivi du Programme PME 3 et de deux (02) mini bus de 30 places avec climatisation d'o rigine au profit des CPSA BJ-UATS-152379-GO-RFQ / A cquisition de pièces de recha nge au profit de l'Unité d’App Component 1 : Improving th Request for Quota Single Stage - One E Under Imple / Post Open - National 25,862.00 0.00 2020-02-08 2020-04-19 2020-04-04 2020-10-01 ui Technique et de Suivi du P e Quality of Basic Education tions nvelope mentation rogramme Partenariat Mondi al pour l’Education (UATS/PM E 3) BJ-UATS-152289-GO-RFB / A cquisition de matériels et con sommables informatiques et divers équipements, matériel Component 1 : Improving th Single Stage - One E s, fournitures et mobiliers de TF / B0364 Post Request for Bids Open - National 346,896.00 444,096.03 Completed 2020-03-30 2020-10-16 2020-04-04 2021-12-14 2020-05-16 2020-11-30 2020-06-15 2021-01-22 2020-07-20 2021-04-27 2021-01-16 2021-06-16 e Quality of Basic Education nvelope bureau au profit de l’UATS, d e l’INFRE, du STP/PSE, de la DPHTA et d’autres structures puis des tablettes électroniq ues au profit des BJ-UATS-152381-GO-RFB / A cquisition de matériels et éq uipements d'enseignement, d'appareils spécifiques et de Component 1 : Improving th Single Stage - One E Under Imple TF / B0364 Post Request for Bids Open - National 379,310.00 0.00 2020-04-20 2020-12-30 2020-04-25 2021-12-17 2020-06-06 2021-02-01 2020-07-06 2021-02-22 2020-08-10 2021-02-06 mobilité, de kits scolaires et e Quality of Basic Education nvelope mentation de vivres au profit des enfant s handicapés des écoles spéc ialisées et d'Équipements su pplémentaires au profit des E NI et ENS BJ-UATS-164562-GO-RFB / F ourniture pluriannuelle de qu Component 3: Strengthening atre mille (4000) repas dans l Single Stage - One E TF / B0364 the Delivery of Education Se Post Request for Bids Open - National 103,448.00 19,803.69 Completed 2020-05-11 2020-12-07 2020-05-16 2020-06-27 2021-02-01 2020-07-27 2021-02-12 2020-08-31 2021-04-08 2021-02-27 2021-11-18 e cadre des réunions et ateli nvelope rvices ers au niveau des départeme nts de l'Ouémé et du Littoral BJ-UATS-164565-GO-RFQ / A cquisition d'un logiciel Tablea u soft (licence 1 an pour 5 ut Component 3: Strengthening ilisateurs), d'équipements de Request for Quota Single Stage - One E TF / B0364 the Delivery of Education Se Post Limited 65,517.00 103,180.12 Signed 2020-04-18 2020-04-07 2020-06-13 2020-10-08 2020-12-10 filtrage de bande passante et tions nvelope rvices d'équipements de numérisati on de documents et stockage de données au profit de la DI P secondaire BJ-UATS-164564-GO-RFQ / A cquisition et mise en place d' équipements électriques et r Component 3: Strengthening éseau pour le renforcement Request for Quota Single Stage - One E Under Imple TF / B0364 the Delivery of Education Se Post Limited 87,810.00 0.00 2020-05-02 2020-06-27 2020-12-24 du DATA CENTER du MEMP et tions nvelope mentation rvices d'équipements réseau et TEL ECOM pour l'extension de l'in tranet du MEMP élargi aux str uctures externes BJ-UATS-164584-GO-DIR / Co nvention de financement de l 'UNICEF pour la fourniture et Component 2: Improving Eq Pending Impl TF / B0364 Post Direct Selection Direct 1,292,433.00 0.00 2020-03-30 2020-04-04 2020-05-09 2020-11-05 la distribution des kits scolair uity in Basic Education ementation es aux écoliers des écoles pri maires publiques (CI et CP) BJ-UATS-199919-GO-RFQ / A cquisition pluriannuelle de fo urnitures de bureau, de cons ommables informatiques et d Component 1 : Improving th Request for Quota Single Stage - One E Pending Impl TF / B0364 Post Limited 54,545.00 0.00 2020-10-24 2020-12-19 2021-06-17 e produits d’entretien au prof e Quality of Basic Education tions nvelope ementation it des structures financées pa r le PPME 3 dans le cadre de l 'exécution de leurs différente s activités BJ-UATS-224401-GO-RFB / A cquisition et mise en place d' équipements électriques et r éseau pour le renforcement Component 1 : Improving th Single Stage - One E Pending Impl TF / B0364 Post Request for Bids Open - National 137,000.00 0.00 2021-03-25 2021-03-30 2021-05-11 2021-06-10 2021-07-15 2022-01-11 du DATA CENTER du MEMP et e Quality of Basic Education nvelope ementation d'équipements réseau et TEL ECOM pour l'extension de l'in tranet du MEMP élargi aux str uctures externes BJ-UATS-262345-GO-RFB / A cquisition d'intrants (papiers, Component 1 : Improving th Single Stage - One E TF / B0364 Post Request for Bids Open - National 320,000.00 243,142.74 Signed 2021-11-15 2021-11-16 2021-11-20 2021-11-26 2022-01-01 2021-12-10 2022-01-31 2021-12-13 2022-03-07 2022-02-03 2022-09-03 encres, etc...) pour la multipli e Quality of Basic Education nvelope cation des documents pédag ogiques de CI. Page 1 BJ-UATS-281282-GO-RFQ / A Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl cquisition de deux (2) véhicul TF / B0364 the Delivery of Education Se Post Limited 64,000.00 0.00 2022-03-15 2022-05-10 2022-11-06 tions nvelope ementation es pick-up 4X4 double cabine rvices s BJ-UATS-305418-GO-RFQ / A Component 3: Strengthening Request for Quota Single Stage - One E TF / B0364 Post Open - National 17,000.00 0.00 Signed 2022-08-02 2022-09-27 2023-03-26 cquisition de 12 motos au pr the Delivery of Education Se tions nvelope ofit de ISEH rvices BJ-UATS-316236-GO-RFQ / A Component 3: Strengthening Request for Quota Single Stage - One E cquisition de 50 tablettes co TF / B0364 the Delivery of Education Se Post Open - National 16,364.00 0.00 Signed 2022-10-04 2022-11-29 2023-05-28 tions nvelope mplémentaires rvices BJ-UATS-305409-GO-RFQ / A cquisition de matériels infor Component 2: Improving Eq Request for Quota Single Stage - One E matiques au profit de l'UATS, TF / B0364 Post Open - National 95,000.00 0.00 Canceled 2022-10-04 2023-02-06 2022-11-29 2023-05-28 uity in Basic Education tions nvelope de la DPSHPA, de la DDASM et des CPS des Collines. BJ-UATS-310167-GO-RFQ / A cquisition de matériels et éq Component 2: Improving Eq Request for Quota Single Stage - One E uipements spécifiques puis d' TF / B0364 Post Open - National 36,473.00 0.00 Canceled 2022-10-08 2022-12-13 2022-12-03 2023-06-01 uity in Basic Education tions nvelope aide techniques de mobilité a u profit des enfants handicap és des Collines BJ-UATS-310156-GO-RFQ / A Component 2: Improving Eq Request for Quota Single Stage - One E cquisition de kits scolaires au TF / B0364 Post Open - National 9,100.00 0.00 Signed 2022-10-05 2022-11-30 2023-05-29 uity in Basic Education tions nvelope profit des enfants handicapé s des Collines BJ-UATS-310162-GO-RFQ / A cquisition de vivre et autres Component 2: Improving Eq Request for Quota Single Stage - One E produits de premières nécess TF / B0364 Post Open - National 14,345.00 0.00 Signed 2022-10-11 2022-12-06 2023-06-04 uity in Basic Education tions nvelope ité aux apprenants référencé s dans les écoles et centre d e référence BJ-UATS-338647-GO-RFQ / A CQUISITION DE KITS SCOLAIR Component 1 : Improving th Request for Quota Single Stage - One E TF / B0364 Post Open - National 10,000.00 0.00 Signed 2023-04-26 2023-03-14 2023-06-21 2023-12-18 ES AU PROFIT DES LAUREATS e Quality of Basic Education tions nvelope DU JEU " LES PTITS CHAMPIO NS DE LA LECTURE " BJ-UATS-340453-GO-RFQ / A cquisitions de matériels et éq Component 2: Improving Eq Request for Quota Single Stage - One E uipements spécifiques puis d' TF / B0364 Post Open - National 36,473.00 0.00 Canceled 2023-03-05 2023-03-08 2023-04-30 2023-10-27 uity in Basic Education tions nvelope aides techniques de mobilité au profit des enfants handica pés des Collines. BJ-UATS-338633-GO-RFQ / A Component 3: Strengthening cquisition de matériels et con Request for Quota Single Stage - One E TF / B0364 the Delivery of Education Se Post Open - National 9,990.00 0.00 Signed 2023-04-04 2023-02-28 2023-05-30 2023-11-26 sommables informatiques et tions nvelope rvices fournitures de bureau au prof it du STP-PDDSE BJ-UATS-362967-GO-RFQ / A cquisition d’équipement des Component 3: Strengthening Request for Quota Single Stage - One E Under Imple salles de la RSE/INFRE pour l TF / B0364 the Delivery of Education Se Post Open - National 83,300.00 0.00 2023-06-19 2023-06-15 2023-08-14 2024-02-10 tions nvelope mentation a production audio et visuelle rvices pour l'enseignement à distan ce BJ-UATS-344231-GO-RFB / A cquisition d'équipement des Component 3: Strengthening Single Stage - One E salles de la RSE/INFRE pour l TF / B0364 the Delivery of Education Se Post Request for Bids Open - National 140,000.00 0.00 Canceled 2023-04-04 2023-04-09 2023-05-21 2023-06-20 2023-07-25 2024-01-21 nvelope a production audio et visuelle rvices pour l'enseignement à distan ce NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-UATS-152389-NC-RFQ / R ecrutement pluriannuel d'un prestataire pour l'assurance Component 3: Strengthening Request for Quota Single Stage - One E Under Imple maladie du personnel et des / the Delivery of Education Se Post Open - National 34,483.00 0.00 2020-02-22 2020-04-18 2020-10-15 tions nvelope mentation véhicules de l'Unité d’Appui T rvices echnique et de Suivi du Progr amme Partenariat Mondial po ur l’Education (UATS/PME 3) BJ-UATS-152388-GO-RFB / I mpression du livret de lectur e initiale pour les élèves de l Component 1 : Improving th Open - Internationa Single Stage - One E TF / B0364 Prior Request for Bids 2,324,138.00 0.00 Canceled 2020-04-20 2020-04-25 2020-06-06 2020-07-06 2020-08-10 2021-02-06 a 1ère année et de la 2ème a e Quality of Basic Education l nvelope nnée et des guides de l'ensei gnant (2ème année de Math ématiques) BJ-UATS-164567-NC-RFQ / A cquisition et installation d’un logiciel de gestion financière Component 1 : Improving th Request for Quota Single Stage - One E et comptable au profit de l'U TF / B0364 Post Limited 20,690.00 12,915.45 Signed 2020-05-02 2020-04-09 2020-06-27 2020-09-12 2020-12-24 e Quality of Basic Education tions nvelope nité d’Appui Technique et de Suivi du Programme Partenar iat Mondial pour l’Education ( UATS/PME 3) BJ-UATS-152397-NC-RFB / R ecrutement d'un prestataire pour la distribution de nouve aux livrets de lecture initiale Component 1 : Improving th Single Stage - One E Pending Impl et autres matériels pour les é TF / B0364 Post Request for Bids Open - National 248,276.00 0.00 2020-06-15 2020-06-20 2020-08-01 2020-08-31 2020-10-05 2021-04-03 e Quality of Basic Education nvelope ementation lèves du CI et du CP ainsi qu e des programmes et guides pédagogiques élaborés du 1e r cycle secondaire dans toute s les communes du Bénin BJ-UATS-164583-NC-DIR / Co nvention de financement de l Component 2: Improving Eq Pending Impl 'appui à l'intégration scolaire TF / B0364 Post Direct Selection Direct 517,241.00 0.00 2020-03-30 2020-04-04 2020-05-09 2020-11-05 uity in Basic Education ementation des enfants handicapés dans le département Zou à travers le Volet ISEH BJ-UATS-152399-NC-RFQ / R Component 3: Strengthening Request for Quota Single Stage - One E ecrutement d'un prestataire TF / B0364 the Delivery of Education Se Post Open - National 8,621.00 6,802.14 Completed 2020-03-19 2021-12-17 2020-05-14 2020-10-08 2020-11-10 2020-10-23 tions nvelope pour assurer le déménageme rvices nt de l'UATS Page 2 BJ-UATS-199961-NC-RFQ / R ecrutement d’un prestataire pour les travaux d’impressio n pour l’atelier de formation Component 1 : Improving th Request for Quota Single Stage - One E Pending Impl TF / B0364 Post Limited 20,000.00 0.00 2020-10-24 2020-12-19 2021-06-17 des enseignants de la 1ère a e Quality of Basic Education tions nvelope ementation nnée (Cours d’Initiation) et d es directeurs d'écoles à l'utili sation de nouveaux program mes, guides et manuels révis és BJ-UATS-201666-NC-RFQ / R estauration des participants à l’atelier de formation des e nseignants de la 1ère année Component 1 : Improving th Request for Quota Single Stage - One E (Cours d’Initiation) et des dir TF / B0364 Post Limited 11,818.00 7,235.65 Signed 2020-11-04 2020-08-24 2020-12-30 2020-09-08 2021-06-28 e Quality of Basic Education tions nvelope ecteurs d'écoles à l'utilisation de nouveaux programmes, g uides et manuels révisés (lec ture-écriture et mathématiqu e) phase pilote BJ-UATS-201668-NC-RFQ / I mpression de nouveaux prog rammes pour écoliers et de modules de formation et guid Component 1 : Improving th Request for Quota Single Stage - One E TF / B0364 Post Limited 47,273.00 93,085.96 Signed 2020-11-14 2020-11-24 2021-01-09 2020-12-12 2021-07-08 es de professeur dans les ma e Quality of Basic Education tions nvelope tières de français, de mathé matiques, de PCT et d'anglai s pour la phase d'expériment ation au niveau des écoles d u secondaire BJ-UATS-215241-NC-RFB / Im pression des nouveaux livres de lecture initiale et cahiers Component 1 : Improving th Open - Internationa Single Stage - One E Under Imple d’activité pour les élèves de l TF / B0364 Post Request for Bids 2,324,138.00 0.00 2021-01-20 2021-04-13 2021-01-25 2021-04-14 2021-03-08 2021-06-14 2021-04-07 2021-05-12 2021-11-08 e Quality of Basic Education l nvelope mentation a 1ère année et de la 2ème a nnée et de divers documents pédagogiques pour enseigna nts et écoliers du primaire BJ-UATS-224056-NC-DIR / Co nvention de partenariat avec la FERCAB dans le cadre de l Component 1 : Improving th Pending Impl a campagne de sensibilisatio TF / B0364 Post Direct Selection Direct 27,273.00 0.00 2021-03-25 2021-03-30 2021-05-04 2021-10-31 e Quality of Basic Education ementation n pour la scolarisation des en fants dans les onze commun es des départements du Borg ou et de l'Alibori BJ-UATS-164558-NC-RFB / Im pression de divers document Component 1 : Improving th Single Stage - One E Under Imple TF / B0364 Post Request for Bids Open - National 931,897.00 0.00 2021-04-28 2021-03-31 2021-05-03 2021-06-14 2021-06-14 2021-07-14 2021-08-18 2022-02-14 s pédagogiques pour écoliers e Quality of Basic Education nvelope mentation et enseignants du secondaire BJ-UATS-224064-NC-RFQ / R ecrutement d'une imprimerie pour la multiplication des no Component 1 : Improving th Request for Quota Single Stage - One E uveaux documents du CP da TF / B0364 Post Limited 36,500.00 89,227.59 Completed 2021-04-17 2021-08-13 2021-06-12 2021-08-25 2021-12-09 2021-12-28 e Quality of Basic Education tions nvelope ns le cadre de la mise à l'ess ai au cours de la rentrée 202 1 - 2022 et d'autres docume nts du Projet BJ-UATS-199929-NC-RFQ / R ecrutement d’une agence de communication pour la conce ption et la production des out Component 1 : Improving th Request for Quota Single Stage - One E Pending Impl TF / B0364 Post Limited 30,909.00 0.00 2020-10-31 2020-12-26 2021-06-24 ils/supports de communicatio e Quality of Basic Education tions nvelope ementation n et de sensibilisation au prof it de la DEP ainsi que la couv erture médiatique des activit és du Projet BJ-UATS-278117-NC-RFQ / M ultiplication de module de for Component 1 : Improving th Request for Quota Single Stage - One E TF / B0364 Post Limited 37,000.00 9,496.77 Signed 2022-02-22 2022-03-07 2022-04-19 2022-04-09 2022-10-16 mation coaching + tableau d e Quality of Basic Education tions nvelope e bord du CEP 2021 BJ-UATS-278056-NC-DIR / Int ervention chirurgicale de l'hô Component 2: Improving Eq Under Imple pital BETHESDA au profit des TF / B0364 Post Direct Selection Direct 7,900.00 0.00 2022-02-17 2022-03-03 2022-02-22 2022-03-29 2022-09-25 uity in Basic Education mentation enfants handicapés du dépar tements des Collines. BJ-UATS-287673-NC-RFQ / R Component 3: Strengthening ecrutement d’une imprimerie Request for Quota Single Stage - One E Pending Impl TF / B0364 the Delivery of Education Se Post Limited 68,000.00 0.00 2022-05-04 2022-06-29 2022-12-26 pour la multiplication des pla tions nvelope ementation rvices nches thématiques BJ-UATS-316233-NC-DIR / Si gnature d'un contrat avec la Component 1 : Improving th TF / B0364 Post Direct Selection Direct - National 18,182.00 0.00 Signed 2022-09-21 2022-09-23 2022-09-26 2022-10-06 2022-10-31 2023-04-29 Fédération des Radios Comm e Quality of Basic Education unautaires et Assimilées du B énin BJ-UATS-338639-NC-RFQ / F OURNITURE DES OUTILS DE COMMUNICATION PROMOTIO Component 2: Improving Eq Request for Quota Single Stage - One E NNELS ET DE SENSIBILISATIO TF / B0364 Post Open - National 30,000.00 0.00 Signed 2023-05-20 2023-03-30 2023-07-15 2024-01-11 uity in Basic Education tions nvelope N POUR LA PROMOTION DE L A SCOLARISATION DES FILLE S ET SUR L’INSERTION SCOL AIRE DES ENFANTS HANDICA PES BJ-UATS-338662-NC-RFQ / R ecrutement d’un prestataire pour l’impression des docum Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl ents d’évaluation sur échanti TF / B0364 the Delivery of Education Se Post Open - National 20,000.00 0.00 2023-05-24 2023-07-19 2024-01-15 tions nvelope ementation llonnage des élèves du CP et rvices du CM1 au titre de l’année sc olaire 2022-2023 (prétest et post-test) BJ-UATS-338664-NC-RFQ / I mpression complémentaire d es programmes de guides pé dagogiques (Guides de l’ense Component 1 : Improving th Request for Quota Single Stage - One E Under Imple TF / B0364 Post Open - National 40,000.00 0.00 2023-03-01 2023-04-12 2023-04-26 2023-10-23 ignant, Guide d’organisation e Quality of Basic Education tions nvelope mentation pédagogique et matériel, Gui de d’évaluation) de français, mathématiques, sciences et anglais au 1er Cycle du seco ndaire BJ-UATS-338677-NC-RFQ / R ecrutement d'une agence po Component 3: Strengthening ur la réalisation des supports Request for Quota Single Stage - One E Pending Impl TF / B0364 the Delivery of Education Se Post Open - National 30,000.00 0.00 2023-04-10 2023-06-05 2023-12-02 magazines de capitalisations tions nvelope ementation rvices des acquis du projet et de do cumentaires aux normes de l a Banque mondiale Page 3 BJ-UATS-338669-NC-RFQ / R ecrutement d'une agence po ur la production des émission Component 2: Improving Eq Request for Quota Single Stage - One E s à caractère pédagogique p TF / B0364 Post Open - National 18,230.00 0.00 Canceled 2023-05-10 2023-07-05 2024-01-01 uity in Basic Education tions nvelope our accompagner les enseign ants du CI dans l'exécution d es nouveaux curricula révisé s de mathématiques et de fr ançais CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-UATS-152416-CS-CQS / R ecrutement d'un Consultant pour la réalisation d'une étud Component 1 : Improving th Consultant Qualifi Pending Impleme / Post Open - National 8,621.00 0.00 2020-02-26 2020-03-18 2020-05-01 2020-05-31 2020-07-05 2021-01-01 e sur les déterminants de la r e Quality of Basic Education cation Selection ntation épartition inéquitable des en seignants au niveau des com munes BJ-UATS-152418-CS-CQS / R Component 3: Strengthening Consultant Qualifi Under Implement ecrutement d'une ONG pour l / the Delivery of Education Se Post Open - National 25,862.00 0.00 2020-02-26 2021-02-11 2020-03-11 2021-12-17 2020-05-06 2020-06-10 2020-12-07 cation Selection ation e contrôle citoyen rvices BJ-UATS-152420-CS-CQS / R ecrutement d'un Consultant Component 3: Strengthening pour l'étude sur les causes d Consultant Qualifi Under Implement / the Delivery of Education Se Post Open - National 51,724.00 0.00 2020-02-28 2020-03-24 2020-03-13 2021-12-17 2020-05-08 2020-11-13 2020-06-12 2020-12-09 e la dégradation des principa cation Selection ation rvices ux indicateurs des sous-secte urs des enseignements prim aire et secondaire BJ-UATS-152421-CS-CQS / R ecrutement d'un Consultant pour la réalisation d'une étud e sur les défis sous-jacents, l Component 3: Strengthening Consultant Qualifi Pending Impleme es opportunités, les implicati / the Delivery of Education Se Post Open - National 34,483.00 0.00 2020-02-28 2020-03-13 2020-05-08 2020-06-12 2020-12-09 cation Selection ntation ons budgétaires ainsi qu'une rvices stratégie pour la mise en œu vre de l'éducation de base co nformément au plan sectoriel de l'éducation BJ-UATS-164561-CS-CQS / R ecrutement d'un Consultant ( Cabinet) chargé de l'évaluati Component 1 : Improving th Consultant Qualifi TF / B0364 Post Open - National 275,862.00 258,812.72 Completed 2020-03-30 2020-04-10 2020-04-20 2021-12-20 2020-06-03 2021-02-19 2020-07-03 2021-03-04 2020-08-07 2021-03-26 2021-02-03 2021-11-25 on sur échantillonnage des c e Quality of Basic Education cation Selection ompétences et pratiques péd agogiques des enseignants BJ-UATS-164577-CS-CQS / R ecrutement d'une ONG charg Component 2: Improving Eq Consultant Qualifi ée de la mobilisation commu TF / B0364 Post Open - National 31,034.00 0.00 Under Review 2020-04-20 2020-05-24 2020-05-11 2020-06-24 2020-07-24 2020-08-28 2021-02-24 uity in Basic Education cation Selection nautaire au niveau des com munes du Borgou ciblés par l e Projet BJ-UATS-164554-CS-CQS / R ecrutement d'un consultant ( Component 3: Strengthening Cabinet) pour mettre à la dis Consultant Qualifi TF / B0364 the Delivery of Education Se Post Open - National 193,966.00 17,254.20 Signed 2020-06-15 2020-08-14 2020-07-06 2021-12-20 2020-08-19 2021-03-04 2020-09-18 2021-05-28 2020-10-23 2021-11-10 2021-04-21 position du MEMP et du MEST cation Selection rvices FP 25 statisticiens en vue d'a ppuyer la production des ann uaires statistiques BJ-UATS-164559-CS-LCS / Re Component 3: Strengthening crutement d'un Consultant (C Least Cost Selecti TF / B0364 the Delivery of Education Se Post Open - National 82,759.00 20,616.43 Completed 2020-04-20 2019-05-10 2020-05-11 2021-12-17 2020-06-24 2020-08-26 2020-07-22 2020-11-06 2020-08-21 2020-11-06 2020-09-25 2020-11-19 2020-10-30 2021-01-23 2021-04-28 2021-09-29 abinet) pour réaliser l'audit fi on rvices nancier et l'audit des marché s du programme BJ-UATS-164578-CS-CQS / R ecrutement d'une ONG charg Component 2: Improving Eq Consultant Qualifi Under Implement ée de la mobilisation commu TF / B0364 Post Open - National 31,034.00 0.00 2020-04-20 2020-05-24 2020-05-11 2021-12-17 2020-06-24 2020-07-24 2020-08-28 2021-02-24 uity in Basic Education cation Selection ation nautaire au niveau des com munes de l'Alibori ciblés par l e Projet BJ-UATS-164582-CS-CQS / R ecrutement d'un Consultant ( Component 3: Strengthening Consultant Qualifi Cabinet) pour la vérification TF / B0364 the Delivery of Education Se Post Open - National 172,414.00 187,967.25 Signed 2020-04-20 2019-04-10 2020-05-11 2021-12-20 2020-06-24 2020-10-20 2020-07-24 2020-11-09 2020-08-28 2021-01-09 2021-02-24 cation Selection des indicateurs liés au décais rvices sement de la part variable de projet BJ-UATS-223170-CS-CQS / R ecrutement d’un consultant ( éditeur) pour les travaux d’é Component 1 : Improving th Consultant Qualifi dition des nouveaux livres de TF / B0364 Post Open - National 54,545.00 0.00 Under Review 2021-03-10 2021-03-15 2021-03-31 2021-05-14 2021-06-13 2021-07-18 2022-01-14 e Quality of Basic Education cation Selection lecture initiale et cahiers d’a ctivité pour les élèves de la 1 ère année et de la 2ème ann ée BJ-UATS-224053-CS-CQS / R ecrutement d’un Consultant ( cabinet médical) pour la Con Component 1 : Improving th Consultant Qualifi Under Implement TF / B0364 Post Open - National 81,818.00 0.00 2021-03-25 2021-03-25 2021-04-15 2021-05-29 2021-06-28 2021-08-02 2022-01-29 sultation, les soins médicaux, e Quality of Basic Education cation Selection ation les traitements chirurgicaux et l'appareillage aux enfants handicapés des Collines INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-UATS-152401-CS-INDV / R ecrutement d'un Spécialiste Component 2: Improving Eq Individual Consult Under Implement / Post Open 38,793.00 0.00 2020-02-25 2020-03-16 2020-04-14 2020-12-01 2020-05-05 2020-10-26 2020-06-09 2020-12-06 en Ingénierie pédagogique a uity in Basic Education ant Selection ation u profit de la DIIP BJ-UATS-152407-CS-INDV / R ecrutement d'un Consultant Component 1 : Improving th Individual Consult Under Implement / Post Open 38,793.00 0.00 2020-02-19 2020-03-16 2020-04-08 2020-04-29 2020-06-03 2020-11-30 Spécialiste en évaluation des e Quality of Basic Education ant Selection ation acquis au profit de l'INFRE BJ-UATS-152408-CS-INDV / R Component 1 : Improving th Individual Consult Under Implement ecrutement d'un Consultant / Post Open 17,241.00 0.00 2020-02-20 2020-03-16 2020-04-09 2020-12-01 2020-04-30 2021-01-01 2020-06-04 2020-12-01 e Quality of Basic Education ant Selection ation en illustration des documents pédagogiques Page 4 BJ-UATS-152410-CS-INDV / R Component 3: Strengthening Individual Consult Pending Impleme ecrutement d'un Spécialiste / the Delivery of Education Se Post Open 38,793.00 0.00 2020-02-21 2020-04-10 2020-05-01 2020-06-05 2020-12-02 ant Selection ntation en communication rvices BJ-UATS-152412-CS-INDV / R ecrutement d'un Consultant I Component 1 : Improving th Individual Consult Pending Impleme / Post Open 15,174.00 0.00 2020-02-21 2020-04-10 2020-05-01 2020-06-05 2020-12-02 nternational pour assurer les e Quality of Basic Education ant Selection ntation formations au niveau du prim aire BJ-UATS-152413-CS-INDV / R ecrutement d'un Consultant Component 1 : Improving th Individual Consult Pending Impleme / Post Open 10,603.00 0.00 2020-02-24 2020-04-13 2020-05-04 2020-06-08 2020-12-05 National pour assurer les for e Quality of Basic Education ant Selection ntation mations au niveau du primair e BJ-UATS-164560-CS-INDV / R ecrutement d'un Consultant Component 3: Strengthening Individual Consult Under Implement pour assurer la formation des TF / B0364 the Delivery of Education Se Post 6,897.00 0.00 2020-04-27 2021-04-24 2020-06-15 2020-07-06 2020-08-10 2021-02-06 ant Selection ation acteurs de la chaîne de pass rvices ation de marchés du Progra mme BJ-UATS-152409-CS-INDV / R ecrutement d'un Consultant Component 3: Strengthening Individual Consult pour la vérification des indica / the Delivery of Education Se Post Open 38,793.00 0.00 Canceled 2020-02-20 2020-04-09 2020-04-30 2020-06-04 2020-12-01 ant Selection teurs liés au décaissement d rvices e la part variable de projet BJ-UATS-201660-CS-INDV / R ecrutement d'un Consultant Spécialiste Chirurgien Pédiatr Component 1 : Improving th Individual Consult TF / B0364 Post Limited 4,545.00 0.00 Canceled 2020-10-31 2020-11-05 2020-11-26 2020-12-31 2021-06-29 e pour les consultations, soin e Quality of Basic Education ant Selection s et traitements chirurgicaux des enfants handicapés des c ollines BJ-UATS-199935-CS-INDV / R ecrutement d'un Enseignant i Component 1 : Improving th Individual Consult tinérant pour les communes TF / B0364 Post Limited 6,364.00 0.00 Under Review 2020-11-09 2021-03-25 2020-11-14 2020-12-05 2021-01-09 2021-07-08 e Quality of Basic Education ant Selection de Bantè, Savalou et Dassa ( Département des Collines) BJ-UATS-201661-CS-INDV / R ecrutement d'un Consultant Spécialiste Kinésithérapeute Component 1 : Improving th Individual Consult TF / B0364 Post Limited 4,545.00 0.00 Canceled 2020-10-31 2020-11-05 2020-11-26 2020-12-31 2021-06-29 Orthoprothésiste pour les co e Quality of Basic Education ant Selection nsultations, soins et traiteme nts chirurgicaux des enfants handicapés des collines BJ-UATS-201662-CS-INDV / R ecrutement d'un Consultant Spécialiste Ophtalmologue p Component 1 : Improving th Individual Consult TF / B0364 Post Limited 4,545.00 0.00 Canceled 2020-10-31 2020-11-05 2020-11-26 2020-12-31 2021-06-29 our les consultations, soins e e Quality of Basic Education ant Selection t traitements chirurgicaux de s enfants handicapés des coll ines BJ-UATS-201664-CS-INDV / R ecrutement d'un Consultant Spécialiste Otorhinolaryngolo Component 1 : Improving th Individual Consult TF / B0364 Post Limited 4,545.00 0.00 Canceled 2020-10-31 2020-11-05 2020-11-26 2020-12-31 2021-06-29 giste (ORL) pour les consultat e Quality of Basic Education ant Selection ions, soins et traitements chi rurgicaux des enfants handic apés des collines BJ-UATS-201665-CS-INDV / R ecrutement d'un Enseignant i Component 1 : Improving th Individual Consult Under Implement tinérant pour les communes TF / B0364 Post Limited 6,364.00 0.00 2020-11-09 2021-03-25 2020-11-14 2020-12-05 2021-01-09 2021-07-08 e Quality of Basic Education ant Selection ation de Ouèssè, Savè et Glazoué ( Département des Collines) BJ-UATS-223173-CS-INDV / R ecrutement d’un Consultant I nternational pour appuyer la Component 1 : Improving th Individual Consult Pending Impleme mise en œuvre des activités TF / B0364 Post Direct 109,091.00 0.00 2021-03-29 2021-04-08 2021-04-29 2021-06-03 2021-11-30 e Quality of Basic Education ant Selection ntation de révision des curricula de C I et CP et de formation des e nseignants sur les nouveaux documents de CI et CP BJ-UATS-224059-CS-INDV / R ecrutement d'un Consultant Spécialiste en évaluation des Component 1 : Improving th Individual Consult Pending Impleme TF / B0364 Post Limited 38,793.00 0.00 2021-03-25 2021-03-30 2021-04-20 2021-05-25 2021-11-21 apprentissages en appui à l’I e Quality of Basic Education ant Selection ntation nstitut National pour la Form ation et la Recherche en Edu cation (INFRE) BJ-UATS-224070-CS-INDV / R Component 1 : Improving th Individual Consult Pending Impleme ecrutement d'un Assistant Ad TF / B0364 Post Open 20,464.00 0.00 2021-03-10 2021-04-28 2021-05-19 2021-06-23 2021-12-20 e Quality of Basic Education ant Selection ntation ministratif au profit de l'UATS BJ-UATS-224072-NC-RFQ / R Component 1 : Improving th Individual Consult Pending Impleme ecrutement d’un consultant TF / B0364 Post Limited 5,455.00 0.00 2021-03-25 2021-03-30 2021-04-20 2021-05-25 2021-11-21 e Quality of Basic Education ant Selection ntation pour la réalisation d’un site w eb pour le Projet BJ-UATS-255850-CS-INDV / R Component 3: Strengthening Individual Consult enouvellement du contrat de TF / B0364 the Delivery of Education Se Post Direct 83,465.00 0.00 Under Review 2021-10-01 2021-10-14 2021-10-11 2021-11-01 2021-12-06 2022-06-04 ant Selection la Spécialiste en Gestion fina rvices ncière BJ-UATS-255865-CS-INDV / R Component 3: Strengthening Individual Consult enouvellement du contrat du TF / B0364 the Delivery of Education Se Post Direct 43,221.00 0.00 Under Review 2021-10-01 2021-10-14 2021-10-11 2021-11-01 2021-12-06 2022-06-04 ant Selection Comptable rvices BJ-UATS-255867-CS-INDV / R Component 3: Strengthening Individual Consult enouvellement du contrat du TF / B0364 the Delivery of Education Se Post Direct 78,809.00 0.00 Under Review 2021-10-01 2021-10-14 2021-10-11 2021-11-01 2021-12-06 2022-06-04 ant Selection Spécialiste en Suivi Evaluatio rvices n BJ-UATS-258364-CS-INDV / R Component 3: Strengthening ecrutement d'un Spécialiste Individual Consult Under Implement TF / B0364 the Delivery of Education Se Post Open 63,000.00 0.00 2021-11-15 2021-11-26 2022-01-03 2022-01-24 2022-02-28 2022-08-27 en Passation des Marchés au ant Selection ation rvices profit de l'UATS - PM3 BJ-UATS-281280-CS-INDV / R enouvellement du contrat du consultant spécialiste en ing Component 1 : Improving th Individual Consult Pending Impleme TF / B0364 Post Direct 100,000.00 0.00 2022-03-08 2022-03-18 2022-04-08 2022-05-13 2022-11-09 énierie pédagogique pour la e Quality of Basic Education ant Selection ntation poursuite des activités relativ es à la révision des curricula de CI et de CP Page 5 BJ-UATS-281281-CS-INDV / R enouvellement du contrat de la contrat relatif à l'accompa Component 1 : Improving th Individual Consult Pending Impleme TF / B0364 Post Direct 100,000.00 0.00 2022-03-08 2022-03-18 2022-04-08 2022-05-13 2022-11-09 gnement du MEMP dans la ra e Quality of Basic Education ant Selection ntation révision des curricula de fran çais et de mathématique au CI-CP BJ-UATS-357390-CS-INDV / R ECRUTEMENT D’UN CONSULT Component 3: Strengthening Individual Consult Under Implement ANT INDIVIDUEL POUR LA RE TF / B0364 the Delivery of Education Se Post Limited 10,000.00 0.00 2023-04-21 2023-05-16 2023-04-26 2023-06-14 2023-05-17 2023-06-21 2023-12-18 ant Selection ation ALISATION DE L’AUDIT ENVIR rvices ONNEMENTAL ET SOCIAL DU PROJET BJ-UATS-357388-CS-CDS / R ecrutement de l'IIPE pour un e assistance technique dans l Component 3: Strengthening e cadre de l’évaluation natio Direct - Internation TF / B0364 the Delivery of Education Se Post Direct Selection 40,000.00 0.00 Under Review 2023-05-29 2023-05-19 2023-06-08 2023-08-12 2024-02-08 nale des acquis scolaires des al rvices écoliers de CP et de CM1 en f rançais et en mathématiques dans les écoles primaires pu bliques et privées du BENIN. Page 6 PROCUREMENT PLAN (Textual Part) Project information: São Tomé and Príncipe - Institutional Capacity Building Project (P162129) Project Implementation agency: Projects Administrative and Fiduciary Agency (AFAP) Date of the Procurement Plan: August 2017 Period covered by this Procurement Plan: August 2017 – March 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Procurement Law (Law 8/2009 of August 26), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables; PROCUREMENT Sao Tome and Principe : Sao Tome and Principe: Institutional Capacity Building Project PLAN General Information Country: Sao Tome and Principe 2017-09-19 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162129 GPN Date: Project Name: Sao Tome and Principe: Institutional Capacity Building Project Loan / Credit No: IDA / D3080, / , IDA / V1240, IDA / D8180 Project Fiduciary and Administrative Agency Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 02/G/ICB/2018 / Supply of inf Strengthening Budget Credi Request for Quota Single Stage - One E IDA / V1240 Post Limited 50,000.00 269,373.65 Completed 2018-03-06 2018-11-13 2018-05-01 2019-02-08 2018-10-28 2019-07-29 ormatic equipment for VAT O bility, Tax Base and SOE Gov tions nvelope ffices ernance 04/G/ICB/2018 / Supply of m Strengthening Budget Credi Request for Quota Single Stage - One E aterials and equipment for th IDA / V1240 bility, Tax Base and SOE Gov Post Limited 250,000.00 197,704.66 Completed 2018-02-27 2019-04-08 2018-04-24 2019-06-21 2018-10-21 2019-12-02 tions nvelope e refurbishment of VAT room ernance s 16/G/ICB/2019 / Acquisition Property Registration and St Single Stage - One E of construction materials and IDA / D3080 Post Request for Bids Open - National 150,000.00 277,368.38 Completed 2019-03-29 2020-02-07 2019-04-03 2019-05-15 2020-04-27 2019-06-14 2020-04-30 2019-07-19 2020-05-26 2020-01-15 2020-09-23 atistical Development nvelope equipments for refurbisheme nt of INE building 17/C/ICB/2019 / Purchase of Property Registration and St Request for Quota Single Stage - One E surveillance cameras and A/C IDA / D3080 Post Limited 20,000.00 10,800.00 Signed 2019-03-05 2019-04-30 2019-03-12 2019-10-27 atistical Development tions nvelope for INE building 35/G/ICB/2019 / Acquisition Property Registration and St Request for Quota Single Stage - One E IDA / D3080 Post Open - National 50,000.00 55,634.72 Completed 2019-03-05 2019-04-30 2019-07-11 2019-10-27 2019-11-11 of software and IT equipment atistical Development tions nvelope s for INE 36/G/ICB/2019 / Acquisition Property Registration and St Request for Quota Single Stage - One E IDA / D3080 Post Open - National 100,000.00 0.00 Canceled 2019-04-03 2019-06-28 2019-05-29 2019-11-25 of IT equipments for DGRN atistical Development tions nvelope 39/G/ICB/2018 / Acquisition Property Registration and St Single Stage - One E of minibus, double cabine pic IDA / D3080 Post Request for Bids Open - National 70,000.00 106,331.33 Completed 2019-02-25 2018-10-17 2019-03-02 2019-08-23 2019-04-13 2018-11-27 2019-05-13 2018-12-14 2019-06-17 2019-02-05 2019-12-14 2019-05-29 atistical Development nvelope k up and motorcicles for INE and PIU 2/G/ICB/2018 / Acquisition of Strengthening Budget Credi Request for Quota Single Stage - One E Informatic equipments and s IDA / V1240 bility, Tax Base and SOE Gov Post Limited 280,352.66 271,796.25 Completed 2019-03-31 2018-09-27 2019-05-26 2019-02-08 2019-11-22 2019-07-29 tions nvelope oftwares for DiTEI ernance 37/G/ICB/2019 / Acquisition Property Registration and St IDA / D3080 Post Direct Selection Direct 5,000.00 3,990.00 Completed 2019-02-28 2019-03-12 2019-03-05 2019-03-12 2019-04-09 2019-03-22 2019-10-06 2019-03-24 of software STATA for INE atistical Development 15/C/2019 / Acquisition of po Financial Soundness and Acc Request for Quota Single Stage - One E wer generator for Debt Depa IDA / D3080 Post Limited 30,000.00 26,751.99 Completed 2019-03-05 2019-05-30 2019-04-30 2019-07-30 2019-10-27 2019-08-26 ess tions nvelope rtment and DGRN 12/G/ICB/2019 / Acquisition Financial Soundness and Acc Request for Quota Single Stage - One E of informatic equipment for IDA / D3080 Post Open - National 13,000.00 14,699.88 Signed 2019-05-29 2019-06-28 2019-07-24 2019-10-04 2020-01-20 ess tions nvelope Debt Deparment 54/G/RFQ/PRCI/2019 / Acqui Property Registration and St Request for Quota Single Stage - One E IDA / D3080 Post Limited 100,000.00 133,299.14 Completed 2019-09-28 2019-10-22 2019-11-23 2019-12-20 2020-05-21 2020-03-18 sition of IT equipments for D atistical Development tions nvelope GRN 03/G/ICB/2018 / Supply of Fu Strengthening Budget Credi Request for Quota Single Stage - One E IDA / V1240 Post Limited 40,000.00 39,217.00 Signed 2020-02-22 2021-03-10 2020-04-18 2021-07-15 2020-10-15 rniture for VAT Offices bility, Tax Base and SOE Gov tions nvelope ernance 71/G/PRCI/2020 / Acquisition Property Registration and St Request for Quota Single Stage - One E of Tablets and desk compute IDA / D3080 Post Limited 35,000.00 23,048.53 Completed 2020-10-10 2020-10-01 2020-12-05 2020-10-06 2021-06-03 2020-10-20 atistical Development tions nvelope rs for INE survey(Covid19 an d Census) 75/G/PRCI/2021 / Acquisition Property Registration and St Request for Quota Single Stage - One E of informatic equipment for C IDA / V1240 Post Limited 85,000.00 0.00 Canceled 2021-05-29 2021-07-24 2022-01-20 atistical Development tions nvelope OSSIL, DGRN and INE 74/G/PRCI/2021 / Acquisition Property Registration and St Request for Quota Single Stage - One E of complementary constructi IDA / V1240 Post Limited 70,000.00 68,093.08 Completed 2021-06-05 2021-05-20 2021-07-31 2021-08-03 2022-01-27 2022-01-21 atistical Development tions nvelope on material for INE 76/G/PRCI/2021 / Acquisition Property Registration and St Request for Quota Single Stage - One E of remaining informatic equi IDA / V1240 Post Limited 40,000.00 32,801.21 Completed 2021-06-05 2021-05-12 2021-07-31 2021-08-28 2022-01-27 2022-01-19 atistical Development tions nvelope pment for INE 77/G/PRCI/2021 / Acquisition Strengthening Budget Credi Request for Quota Single Stage - One E IDA / V1240 Post Limited 22,000.00 0.00 Canceled 2021-06-06 2021-08-01 2022-01-28 of informatic equipment for C bility, Tax Base and SOE Gov tions nvelope OSSIL ernance 78/G/PRCI/2021 / Acquisition Property Registration and St Request for Quota Single Stage - One E IDA / V1240 Post Limited 23,000.00 52,316.45 Signed 2021-06-13 2021-08-24 2021-08-08 2021-11-06 2022-02-04 of Informatic equipment for atistical Development tions nvelope DGRN 11/G/ICB/2019 / Acquisition Financial Soundness and Acc Request for Quota Single Stage - One E of a Back-up for data security IDA / D3080 Post Open - National 6,000.00 0.00 Canceled 2019-11-20 2020-01-15 2020-07-13 ess tions nvelope for Debt Department 73/G/PRCI/2021 / Acquisition Strengthening Budget Credi of construction materials and Single Stage - One E IDA / D3080 bility, Tax Base and SOE Gov Post Request for Bids Open - National 250,000.00 0.00 Canceled 2021-05-17 2021-04-20 2021-05-22 2021-07-03 2021-08-02 2021-09-06 2022-03-05 equipment for VAT declaratio nvelope ernance n center at Principe Island 90/G/PRCI/2021 / Acquisition Strengthening Budget Credi Single Stage - One E of 2 vehicles and 6 motorcycl IDA / V1240 bility, Tax Base and SOE Gov Post Request for Bids Open - National 100,000.00 67,397.34 Signed 2021-11-25 2021-12-01 2021-11-30 2022-01-11 2022-01-21 2022-02-10 2022-01-27 2022-03-17 2022-02-12 2022-09-13 nvelope es for VAT supervision ernance Page 1 93/G/PRCI/2021 / Acquisition Strengthening Budget Credi Request for Quota Single Stage - One E of informatic equipment for I IDA / V1240 bility, Tax Base and SOE Gov Post Limited 24,000.00 0.00 Canceled 2021-11-30 2021-12-30 2022-01-25 2022-07-24 tions nvelope NE, DPL and DT ernance 91/G/PRCI/2021 / Acquisition Strengthening Budget Credi Request for Quota Single Stage - One E of Informatic Equipment for V IDA / V1240 bility, Tax Base and SOE Gov Post Limited 78,000.00 0.00 Canceled 2021-12-20 2021-12-06 2022-02-14 2022-08-13 tions nvelope AT headquarter ernance 96/G/PRCI/2022 / Aquisition Strengthening Budget Credi Single Stage - One E of informatic Equipement for IDA / V1240 bility, Tax Base and SOE Gov Post Request for Bids Open - National 150,000.00 0.00 Signed 2022-03-31 2022-04-05 2022-04-05 2022-04-06 2022-05-17 2022-05-20 2022-06-16 2022-09-13 2022-07-21 2023-01-17 nvelope VAT headquarter ernance 97/G/PRCI/2022 / Aquisition Strengthening Budget Credi Single Stage - One E of informatic equipment for I IDA / V1240 bility, Tax Base and SOE Gov Post Request for Bids Open - National 32,000.00 0.00 Signed 2022-03-31 2022-04-14 2022-04-05 2022-04-15 2022-05-17 2022-05-31 2022-06-16 2022-08-12 2022-07-21 2023-01-17 nvelope NE,DPL and DT ernance 98/G/PRCI/2022 / Aquisition Strengthening Budget Credi Single Stage - One E of 2 pic up and 7 motorcycles IDA / V1240 bility, Tax Base and SOE Gov Post Request for Bids Open - National 136,000.00 0.00 Signed 2022-03-31 2022-04-05 2022-04-05 2022-04-06 2022-05-17 2022-05-19 2022-06-16 2022-07-19 2022-07-21 2023-01-17 nvelope for VAT supervision and DITEI ernance 102/G/PRCI/2022 / Aquisição Strengthening Budget Credi Request for Quota Single Stage - One E de equipamentos de design IDA / V1240 bility, Tax Base and SOE Gov Post Limited 60,000.00 0.00 Signed 2022-07-12 2022-11-17 2022-09-06 2023-03-05 tions nvelope gráfico e materiais de comun ernance icação do IVA 105/G/PRCI/2022 / Aquisição Property Registration and St Request for Quota Single Stage - One E IDA / V1240 Post Limited 40,000.00 0.00 Signed 2022-07-05 2022-08-17 2022-08-30 2023-02-26 de equipamentos TI e licença atistical Development tions nvelope s software 88/G/PRCI/2021 / Acquisition Strengthening Budget Credi Request for Quota Single Stage - One E Pending Impl of refrigeration system kit fo IDA / V1240 bility, Tax Base and SOE Gov Post Open - National 25,000.00 0.00 2022-07-25 2022-09-19 2023-03-18 tions nvelope ementation r DITEI Data Center ernance 101/G/PRCI/2022 / Aquisição Strengthening Budget Credi Request for Quota Single Stage - One E de equipamentos informático IDA / D3080 bility, Tax Base and SOE Gov Post Open - National 26,500.00 0.00 Signed 2022-07-12 2022-09-06 2023-03-05 tions nvelope s para o SIRP-DGRN ernance 104/G/PRCI/2022 / Aquisição Property Registration and St Request for Quota Single Stage - One E e instalação de uma Bomba IDA / V1240 Post Limited 29,000.00 0.00 Canceled 2022-07-05 2022-08-30 2023-02-26 atistical Development tions nvelope eletrónica para o gerador do INE 106/G/PRCI/2021 / Acquisitio Financial Soundness and Acc Request for Quota Single Stage - One E Under Imple n of hardware and third-party IDA / V1240 Post Limited 350,000.00 0.00 2023-01-01 2023-02-17 2023-02-26 2023-08-25 ess tions nvelope mentation software (main site and D/R) to host the CRC 84/G/PRCI/2021 / Acquisition Financial Soundness and Acc Open - Internationa Single Stage - One E of hardware and third-party s IDA / V1240 Post Request for Bids 350,000.00 0.00 Canceled 2021-11-29 2022-04-18 2021-12-04 2022-04-19 2022-01-15 2022-06-03 2022-02-14 2022-03-21 2022-09-17 ess l nvelope oftware (main site and D/R) t o host the CRC 117/G/PRCI/2023 / Aquisição e Instalação de Equipamento Financial Soundness and Acc Request for Quota Single Stage - One E Pending Impl IDA / D8180 Post Limited 20,000.00 0.00 2023-08-05 2023-09-30 2024-03-28 s Informáticos e Materiais pa ess tions nvelope ementation ra o Gabinete da Divida 118/G/PRCI/2023 / Aquisição Financial Soundness and Acc Request for Quota Single Stage - One E Pending Impl e Instalação de Matérias para IDA / D8180 Post Limited 20,000.00 0.00 2023-08-31 2023-10-26 2024-04-23 ess tions nvelope ementation a Contabilidade 119/G/PRCI/2023 / Aquisição e Instalação de Equipamento Financial Soundness and Acc Request for Quota Single Stage - One E Pending Impl IDA / D8180 Post Limited 20,000.00 0.00 2023-09-05 2023-10-31 2024-04-28 s e Materiais para o Espaço d ess tions nvelope ementation os Serviços do IVA na Ilha do Príncipe 120/G/PRCI/2023 / Aquisição Financial Soundness and Acc Request for Quota Single Stage - One E Pending Impl e Instalação de Equipamento IDA / D3080 Post Limited 37,500.00 0.00 2023-09-21 2023-09-26 2023-11-07 2023-12-07 2024-01-11 2024-07-09 ess tions nvelope ementation s Informáticos para a OTOCA 121/G/PRCI/2023 / Aquisição e Instalação de um Sistema F Financial Soundness and Acc Open - Internationa Single Stage - One E Pending Impl IDA / D8180 Post Request for Bids 400,000.00 0.00 2023-09-29 2023-10-04 2023-11-15 2023-12-15 2024-01-19 2024-07-17 otovoltaico no Edifício das Fi ess l nvelope ementation nanças em São Tomé e do P ríncipe NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 69/NC/PRCI/2020 / Acquisitio Financial Soundness and Acc Open - Internationa Single Stage - One E Under Imple IDA / V1240 Post Request for Bids 700,000.00 0.00 2021-05-24 2022-12-09 2021-05-29 2021-07-10 2021-08-09 2021-09-13 2022-03-12 n of a Software for Bank Sup ess l nvelope mentation ervision 79/S/PRCI/2021 / Integrated Financial Platform (Core Ban Financial Soundness and Acc Open - Internationa Single Stage - One E Under Imple IDA / V1240 Prior Request for Bids 2,700,000.00 0.00 2021-06-07 2021-10-15 2021-06-12 2021-11-25 2021-07-24 2022-02-15 2021-08-23 2023-02-09 2021-09-27 2022-03-26 king System & Accounting Sy ess l nvelope mentation stem) for the Central Bank o f Sao Tome and Principe CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 01/C/ICB/2017 / Asset qualit Financial Soundness and Acc Quality And Cost- Open - Internationa IDA / D3080 Prior 1,000,000.00 1,509,906.03 Signed 2017-09-18 2017-09-21 2017-10-09 2017-09-26 2017-11-22 2018-02-13 2017-12-20 2018-03-30 2018-01-19 2018-04-27 2018-02-23 2018-09-14 2018-03-30 2018-08-31 2019-03-30 y of the banking system ess Based Selection l 02/C/ICB/2017 / Financial us Consultant Qualifi Open - Internationa / Post 150,000.00 0.00 Canceled 2017-10-02 2017-10-23 2017-12-06 2018-01-05 2018-02-09 2018-08-08 age survey cation Selection l 13/C/ICB/2019 / Improvemen t of the Credit Registry Platfo Financial Soundness and Acc Quality And Cost- Open - Internationa IDA / D3080 Prior 250,000.00 795,000.00 Signed 2019-01-28 2018-12-06 2019-02-18 2019-03-07 2019-04-03 2019-06-26 2019-05-01 2019-11-01 2019-05-31 2020-01-13 2019-07-05 2021-03-01 2019-08-09 2021-04-02 2020-08-08 rm in the Central Bank of Sa ess Based Selection l o Tome and Principe 03/C/ICB/2017 / Implementa Consultant Qualifi Open - Internationa tion of gap assessment of pu / Post 100,000.00 0.00 Canceled 2017-10-02 2017-10-23 2017-12-06 2018-01-05 2018-02-09 2018-08-08 cation Selection l blic credit registry Page 2 29/C/ICB/2019 / Consultancy Financial Soundness and Acc Quality And Cost- Open - Internationa services to provide Technical IDA / D3080 Post 250,000.00 232,710.00 Signed 2019-08-21 2019-07-26 2019-09-11 2019-10-10 2019-10-25 2020-02-18 2019-11-22 2020-04-30 2019-12-22 2020-10-22 2020-01-26 2021-04-07 2020-03-01 2021-03-24 2021-03-01 ess Based Selection l Assistance and training to OT OCA 49/C/ICB/2019 / Financial Au Strengthening Budget Credi Quality And Cost- Open - Internationa IDA / D3080 Post 200,000.00 200,526.52 Signed 2019-05-27 2019-07-15 2019-06-17 2019-08-07 2019-07-31 2019-10-01 2019-08-28 2020-02-14 2019-09-27 2020-02-14 2019-11-01 2020-05-24 2019-12-06 2020-05-26 2020-12-05 diting for the 4 State Enterpri bility, Tax Base and SOE Gov Based Selection l ses ernance 58/C/PRCI/2019 / Communic Property Registration and St Consultant Qualifi IDA / V1240 Post Open - National 22,000.00 24,940.00 Signed 2019-10-08 2019-10-02 2019-10-29 2019-12-12 2019-12-03 2020-01-11 2020-03-05 2020-02-15 2020-03-12 2020-08-13 ation Service for Enterprise C atistical Development cation Selection ensus 61/C/ICB/2019 / DESENVOLV Strengthening Budget Credi IMENTO DO SISTEMA INFORM Quality And Cost- Open - Internationa IDA / V1240 bility, Tax Base and SOE Gov Prior 950,000.00 624,367.71 Signed 2019-11-22 2019-12-16 2019-12-13 2020-01-15 2020-01-26 2020-05-27 2020-02-23 2020-07-30 2020-03-24 2020-11-16 2020-04-28 2021-10-15 2020-06-02 2021-11-16 2021-06-02 ÁTICO PARA A GESTÃO DO IM Based Selection l ernance POSTO SOBRE VALOR ACRES CENTADO (IVA) 62/C/ICB/2019 / Project Audi Project Implementation Sup Least Cost Selecti Open - Internationa Under Implement IDA / V1240 Post 30,000.00 0.00 2019-11-25 2019-12-09 2019-12-16 2019-12-17 2020-01-29 2020-01-31 2020-02-26 2020-03-16 2020-03-27 2020-05-01 2020-06-05 2020-12-02 t for the years 2019/2021 port on l ation 50/C/ICB/2019 / Developmen Strengthening Budget Credi t of Public Debt Management Consultant Qualifi Open - Internationa Pending Impleme IDA / D3080 bility, Tax Base and SOE Gov Post 150,000.00 0.00 2019-08-26 2019-09-16 2019-10-30 2019-11-29 2020-01-03 2020-07-01 System and software solution cation Selection l ntation ernance for debt service forecast and reports 67/C/PRCI/2020 / Developme nt of a procurement website Strengthening Budget Credi Consultant Qualifi Open - Internationa for COSSIL (Gabinete de Seg IDA / D3080 bility, Tax Base and SOE Gov Prior 20,000.00 0.00 Canceled 2020-06-15 2020-07-06 2020-08-19 2020-09-18 2020-10-23 2021-04-21 cation Selection l uimento do Sistema de Licita ernance ção e Contratação Pública) 70/C/PRCI/2019 / Developme Property Registration and St Quality And Cost- Open - Internationa IDA / D3080 Prior 500,000.00 392,921.50 Signed 2020-09-15 2020-09-25 2020-10-06 2020-11-19 2020-11-06 2020-12-17 2021-03-09 2021-01-16 2021-06-22 2021-02-20 2021-10-11 2021-03-27 2021-10-17 2022-03-27 nt of SIRP software atistical Development Based Selection l 32/C/ICB/2019 / Developmen Property Registration and St Consultant Qualifi Open - Internationa IDA / D3080 Post 170,000.00 0.00 Canceled 2020-01-13 2019-11-29 2020-02-03 2020-01-15 2020-03-18 2020-04-17 2020-05-22 2020-11-18 t of SIRP software atistical Development cation Selection l 68/C/PRCI/2020 / Developme nt of a procurement website Strengthening Budget Credi Consultant Qualifi for COSSIL (Gabinete de Seg IDA / D3080 bility, Tax Base and SOE Gov Post Open - National 20,000.00 10,333.03 Signed 2020-09-21 2020-09-28 2020-10-12 2020-11-12 2020-11-25 2021-04-06 2020-12-25 2021-05-23 2021-01-29 2021-06-08 2021-07-28 cation Selection uimento do Sistema de Licita ernance ção e Contratação Pública) 19/C/ICB/2019 / Developmen Financial Soundness and Acc Quality And Cost- Open - Internationa Pending Impleme t of a moveable asset electro IDA / D3080 Post 700,000.00 0.00 2021-06-30 2021-07-21 2021-09-03 2021-10-01 2021-10-31 2021-12-05 2022-01-09 2023-01-09 ess Based Selection l ntation nic Collateral Registry 14/C/ICB/2019 / Developmen Financial Soundness and Acc Quality And Cost- Open - Internationa IDA / D3080 Post 350,000.00 0.00 Canceled 2020-03-02 2020-03-23 2020-05-06 2020-06-03 2020-07-03 2020-08-07 2020-09-11 2021-09-11 t of a Data Center for the Ce ess Based Selection l ntral Bank 18/C/ICB/2019 / Design of a Financial Soundness and Acc Quality And Cost- Open - Internationa D/R solution to guarantee Bu IDA / D3080 Post 350,000.00 0.00 Canceled 2020-03-16 2020-04-06 2020-05-20 2020-06-17 2020-07-17 2020-08-21 2020-09-25 2021-09-25 ess Based Selection l siness continuity (module 3) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 05/C/ICB/2018 / Consultant s Strengthening Budget Credi ervices for project design of IDA / V1240 bility, Tax Base and SOE Gov Post Direct Selection Direct 10,000.00 10,000.00 Completed 2018-02-21 2018-06-19 2018-03-03 2018-05-07 2018-02-26 2018-11-03 2020-02-21 VAT room and work supervisi ernance on 06/C/ICB/2018 / CPI Specialis Property Registration and St Individual Consult IDA / V1240 Post Limited 15,000.00 17,510.00 Completed 2018-04-12 2018-04-20 2018-04-17 2018-07-03 2018-05-08 2018-11-14 2018-06-12 2018-11-15 2018-12-09 2020-01-16 t for INE atistical Development ant Selection 07/C/ICB/2018 / Poverty anal Property Registration and St Individual Consult IDA / V1240 Post Limited 27,500.00 16,800.00 Signed 2018-04-05 2018-04-20 2018-04-10 2018-05-01 2018-08-15 2018-06-05 2018-08-27 2018-12-02 ysis Specialist for INE atistical Development ant Selection 08/C/ICB/2018 / Hiring of IT s Property Registration and St Individual Consult IDA / V1240 Post Limited 30,000.00 14,308.00 Completed 2018-02-22 2018-04-20 2018-02-27 2018-04-21 2018-03-20 2018-04-23 2018-04-24 2018-04-25 2018-10-21 2020-02-18 pecialist for INE atistical Development ant Selection 09/C/ICB/2018 / Technical As Strengthening Budget Credi sistance to support the hiring IDA / V1240 bility, Tax Base and SOE Gov Post Direct Selection Direct 30,000.00 31,736.00 Completed 2018-03-08 2018-03-08 2018-03-18 2018-03-21 2018-05-22 2018-04-04 2018-11-18 2018-07-17 of 25 new tax staff ernance 10/C/ICB/2018 / Preparation Project Implementation Sup of the Operating, administrat IDA / V1240 Post Direct Selection Direct 10,000.00 10,100.00 Completed 2018-03-01 2018-06-19 2018-03-11 2018-05-15 2018-06-27 2018-11-11 2020-02-19 port ive and financial Procedures Manual 31/C/ICB/2019 / Technical as sistance to desegn and quant Property Registration and St IDA / D3080 Post Direct Selection Direct 10,000.00 10,000.00 Completed 2019-02-22 2019-01-23 2019-03-04 2019-05-08 2019-01-31 2019-11-04 2020-02-19 ify the materials nedeed for t atistical Development he INE rehabilitation 34/C/ICB/2019 / Technical as Property Registration and St Individual Consult sistance to training 25 INE St IDA / D3080 Post Limited 20,000.00 19,700.00 Completed 2019-03-15 2019-01-23 2019-03-20 2019-02-07 2019-04-10 2019-02-20 2019-05-15 2019-02-20 2019-11-11 2019-03-28 atistical Development ant Selection affs in multiple topics 20/C/ICB/2019 / Introduction Financial Soundness and Acc Individual Consult Under Implement of a methodologiy for macroe IDA / D3080 Post Open 100,000.00 0.00 2019-04-26 2019-04-01 2019-06-14 2019-05-16 2019-07-05 2019-08-09 2019-08-09 2020-02-05 ess ant Selection ation conomic and revenue forecst ing 21/C/ICB/2019 / Updating of Strengthening Budget Credi Individual Consult a Public procurement law an IDA / D3080 bility, Tax Base and SOE Gov Prior Open 150,000.00 147,142.45 Signed 2019-03-29 2019-05-06 2019-05-17 2020-01-16 2019-06-07 2020-05-11 2019-07-12 2020-04-28 2020-01-08 ant Selection d related documents ernance 38/C/ICB/2019 / Post-gradua Strengthening Budget Credi tion on Public Procurement fo IDA / D3080 bility, Tax Base and SOE Gov Prior Direct Selection Direct 80,500.00 70,900.20 Signed 2019-02-25 2019-03-06 2019-03-07 2019-03-04 2019-05-11 2019-03-21 2019-11-07 r 7 COSSIL staff ernance 24/C/ICB/2019 / Training on l Strengthening Budget Credi ogical architecture of the dat IDA / D3080 bility, Tax Base and SOE Gov Post Direct Selection Direct 88,000.00 61,380.00 Completed 2019-05-27 2019-04-18 2019-06-06 2019-04-22 2019-08-10 2019-05-04 2020-02-06 2019-08-15 a center infrastructure for 7 ernance DITEI staff 28/C/ICB/2019 / T.A. to supp Strengthening Budget Credi Individual Consult IDA / D3080 Post Open 100,000.00 239,290.68 Signed 2019-05-27 2019-06-19 2019-07-15 2019-11-14 2019-08-05 2020-06-13 2019-09-09 2020-06-10 2020-03-07 ort issues regarding State En bility, Tax Base and SOE Gov ant Selection terprises ernance Page 3 40/C/ICB/2019 / T.A. on Prop Strengthening Budget Credi erty Registry, Commercial an IDA / D3080 bility, Tax Base and SOE Gov Post Direct Selection Direct 50,000.00 65,802.80 Signed 2019-10-28 2019-07-17 2019-11-07 2019-09-27 2020-01-11 2019-09-23 2020-07-09 d Notary new Codes ernance 41/C/ICB/2019 / T.A. for prep Financial Soundness and Acc Individual Consult Pending Impleme IDA / D3080 Post Limited 19,110.00 0.00 2019-07-10 2019-07-15 2019-08-05 2019-09-09 2020-03-07 aration of the Consumer Pric ess ant Selection ntation e Index 44/C/ICB/2019 / Elaboration Financial Soundness and Acc Individual Consult of an information System Str IDA / D3080 Post Open 25,000.00 0.00 Signed 2019-10-24 2022-02-28 2019-12-12 2022-07-19 2020-01-02 2022-08-08 2020-02-06 2020-08-04 ess ant Selection ategic Plan for INE 46/C/ICB/2019 / Senior Admi Project Implementation Sup Individual Consult IDA / D3080 Post Open 14,000.00 7,647.50 Signed 2019-04-26 2019-03-28 2019-06-14 2019-08-13 2019-07-05 2019-08-14 2019-08-09 2019-08-18 2020-02-05 nistrative for AFAP port ant Selection 47/C/ICB/2019 / Accountant f Project Implementation Sup Individual Consult IDA / D3080 Post Open 14,000.00 21,000.00 Signed 2019-09-26 2019-09-16 2019-11-14 2019-11-19 2019-12-05 2020-01-07 2020-01-09 2020-01-08 2020-07-07 or AFAP port ant Selection 48/C/ICB/2019 / Design, arch Project Implementation Sup Individual Consult itecture project and work sup IDA / D3080 Post Open 10,000.00 9,411.06 Completed 2019-04-30 2019-03-26 2019-06-18 2019-04-04 2019-07-09 2019-04-05 2019-08-13 2019-04-08 2020-02-09 2020-04-07 port ant Selection ervision of the 3rd floor for A FAP Offices 45/C/ICB/2019 / T.A. for the Financial Soundness and Acc Individual Consult IDA / D3080 Post Open 40,000.00 29,497.00 Signed 2019-10-10 2019-08-29 2019-11-28 2019-11-27 2019-12-19 2020-01-07 2020-01-23 2020-01-08 2020-07-21 organization of enterprises C ess ant Selection ensus 57/C/PRCI/2019 / Accounting Property Registration and St Individual Consult Under Implement training for Inquisitors on Ent IDA / V1240 Post Open 10,000.00 0.00 2019-10-08 2019-10-14 2019-11-26 2019-12-17 2020-01-21 2020-07-19 atistical Development ant Selection ation erprise Census 56/C/PRCI/2019 / Technical A Project Implementation Sup IDA / V1240 Post Direct Selection Direct 38,478.00 0.00 Canceled 2019-10-03 2019-10-13 2019-12-17 2020-06-14 dvisor for PRCI port 55/C/PRCI/2019 / Financial M IDA / V1240 Project Implementation Sup Post Direct Selection Direct 38,478.00 0.00 Canceled 2019-10-03 2019-10-13 2019-12-17 2020-06-14 anager port 59/C/PRCI/2019 / Technical A Project Implementation Sup IDA / V1240 Post Direct Selection Direct 38,478.00 38,478.00 Signed 2018-12-03 2018-12-30 2018-12-13 2019-01-01 2019-01-22 2019-01-07 2020-01-22 dvisor for PRCI port 60/C/PRCI/2019 / Financial M IDA / V1240 Project Implementation Sup Post Direct Selection Direct 38,478.00 38,478.00 Signed 2018-12-03 2019-12-02 2018-12-13 2019-01-02 2019-01-07 2019-01-04 2020-01-07 anager port 43/C/ICB/2019 / Preparation Strengthening Budget Credi Individual Consult of Roadmap for updating Nati IDA / D3080 bility, Tax Base and SOE Gov Post Open 25,000.00 14,200.00 Signed 2019-12-09 2021-06-14 2020-01-27 2022-04-22 2020-02-17 2022-05-30 2020-03-23 2022-05-24 2020-09-19 ant Selection onal Accounts ernance 33//C/ICB/2019 / Technical a Property Registration and St Individual Consult IDA / D3080 Post Limited 21,000.00 0.00 Canceled 2020-03-16 2020-03-21 2020-04-11 2020-05-16 2020-11-12 ssistance to training 10 INE s atistical Development ant Selection taff in STATA 11/C/AFAP/2020 / Senior Acc Project Implementation Sup ountant IDA / V1240 Post Direct Selection Direct 30,000.00 30,000.00 Signed 2020-02-13 2019-12-02 2020-02-23 2020-01-02 2020-04-28 2020-01-04 2020-10-25 port Nilza Maria de Jesus Costa Na zaré 63/C/PRCI/2020 / 5 ASSISTE NTES PARA APOIAREM A DG Property Registration and St RN NO PROCESSO DE DIGITA IDA / V1240 Post Direct Selection Direct 20,000.00 3,034.74 Signed 2020-02-23 2020-02-27 2020-03-04 2020-04-02 2020-05-08 2020-05-06 2020-11-04 atistical Development LIZAÇÃO E CATALOGAÇÃO D OS LIVROS DA SECÇÃO PRED IAL E AUTOMÓVEL 64/C/ICB/2020 / T.A. to Desi gn Public Debt Management Financial Soundness and Acc Individual Consult IDA / V1240 Post Open 60,000.00 96,000.00 Signed 2020-03-09 2020-04-01 2020-04-27 2020-11-16 2020-05-18 2021-04-09 2020-06-22 2021-04-21 2020-12-19 System and software solution ess ant Selection for debt service forecast and reports 65/C/ICB/2020 / Training on System, Comunication and In Financial Soundness and Acc Individual Consult IDA / V1240 Post Open 40,000.00 16,408.58 Signed 2020-03-02 2020-02-24 2020-04-20 2020-07-22 2020-05-11 2020-07-16 2020-06-15 2021-01-26 2020-12-12 fomatic Security (Fortigate a ess ant Selection nd Storage) for DITEI Staff 30/C/ICB/2019 / T.A. to assis t on preparation of ToR for SI Financial Soundness and Acc Individual Consult IDA / D3080 Post Limited 80,000.00 0.00 Canceled 2019-05-31 2019-06-05 2019-06-26 2019-07-31 2020-01-27 RP design and LEGI-NON inte ess ant Selection gration and solution 22/C/ICB/2019 / Developmen Strengthening Budget Credi Individual Consult IDA / D3080 Prior Open 20,000.00 0.00 Canceled 2019-04-05 2019-05-24 2019-06-14 2019-07-19 2020-01-15 t of a procurement website f bility, Tax Base and SOE Gov ant Selection or COSSIL ernance 72/C/PRCI/2021 / Training of Financial Soundness and Acc Individual Consult Pending Impleme INE staff and delegated body IDA / D3080 Post Limited 25,000.00 0.00 2021-10-11 2021-10-16 2021-11-06 2021-12-11 2022-06-09 ess ant Selection ntation on data anonymization 42/C/ICB/2019 / T.A. for train Financial Soundness and Acc Individual Consult ing of 10 INE staff and delega IDA / D3080 Post Open 25,000.00 0.00 Canceled 2019-08-22 2021-02-19 2019-10-10 2019-10-31 2019-12-05 2020-06-02 ess ant Selection ted body on data anonymizat ion 81/C/PRCI/2021 / AT du logic Project Implementation Sup IDA / D3080 Post Direct Selection Direct 10,000.00 10,069.92 Signed 2021-09-23 2021-09-14 2021-10-03 2021-10-15 2021-12-07 2021-11-02 2022-06-05 iel TOMPRO au niveau de l'AF port AP 82/C/PRCI/2021 / Assistência Property Registration and St à DGRN para digitalização e IDA / V1240 Post Direct Selection Direct 20,000.00 12,754.87 Signed 2021-09-30 2021-09-08 2021-10-10 2021-09-21 2021-12-14 2021-10-23 2022-06-12 atistical Development catalogação dos livros 25/C/ICB/2019 / T.A. to desig n the electronic interface bet Financial Soundness and Acc Individual Consult IDA / D3080 Post Open 40,000.00 0.00 Canceled 2019-11-25 2020-01-13 2020-02-03 2020-03-09 2020-09-05 ween Treasury and Central B ess ant Selection ank (Management Treasury Module) 51/C/ICB/2019 / T.A. to desig Strengthening Budget Credi Individual Consult IDA / D3080 Post Open 15,000.00 0.00 Canceled 2019-10-28 2019-12-16 2020-01-06 2020-02-10 2020-08-08 n a Manual for VAT bility, Tax Base and SOE Gov ant Selection ernance 27/C/ICB/2019 / T.A. to creat Strengthening Budget Credi Individual Consult IDA / D3080 Post Limited 35,000.00 0.00 Canceled 2019-10-23 2019-10-28 2019-11-18 2019-12-23 2020-06-20 e a Communication Strategy bility, Tax Base and SOE Gov ant Selection for VAT ernance 86/C/PRCI/2021 / T.A. to sup Strengthening Budget Credi Individual Consult IDA / V1240 Post Open 180,000.00 105,670.00 Signed 2021-12-07 2021-11-10 2022-01-25 2022-04-11 2022-02-15 2022-05-19 2022-03-22 2022-05-20 2022-09-18 port Comite Macrofiscal bility, Tax Base and SOE Gov ant Selection ernance 92/C/PRCI/2021 / T.A. for dis Property Registration and St Individual Consult semination of INE activities o IDA / V1240 Post Limited 18,000.00 12,604.58 Signed 2021-11-30 2021-11-18 2021-12-05 2021-12-03 2021-12-26 2022-03-09 2022-01-30 2022-03-16 2022-07-29 atistical Development ant Selection n the Radio and TV Page 4 87/C/PRCI/2021 / T.A for e-G Strengthening Budget Credi IDA / V1240 Post Direct Selection Direct 15,000.00 15,484.98 Signed 2021-11-15 2021-11-17 2021-11-25 2021-12-07 2022-01-29 2021-12-16 2022-07-28 overnment Procurement bility, Tax Base and SOE Gov ernance 83/C/PRCI/2021 / Procureme Project Implementation Sup Individual Consult IDA / D8180 Post Limited 24,040.00 0.00 Canceled 2021-10-19 2021-10-24 2021-11-14 2021-12-19 2022-06-17 nt Officer port ant Selection 95/G/PRCI/2021 / Contrataçã Project Implementation Sup Individual Consult IDA / D8180 Prior Open 30,000.00 30,000.00 Signed 2021-12-08 2021-12-08 2022-01-26 2022-04-11 2022-02-16 2022-04-25 2022-03-23 2022-05-08 2022-09-19 o de Oficial de Licitações port ant Selection 94/C/PRCI/2021 / Calculation Property Registration and St Individual Consult IDA / D8180 Post Direct 9,000.00 9,154.00 Signed 2021-12-10 2021-12-08 2021-12-20 2021-12-14 2022-01-10 2022-01-06 2022-02-14 2022-01-07 2022-08-13 of the Consumer Price Index atistical Development ant Selection (CPI) 99/C/PRCI/2022 / Contrataçã Property Registration and St Individual Consult o do Conselheiro Técnico Prin IDA / V1240 Post Open 100,000.00 0.00 Canceled 2022-03-31 2022-03-27 2022-05-19 2022-08-02 2022-06-09 2022-07-14 2023-01-10 atistical Development ant Selection cipal (CTP) do 5º RGPH 100/C/PRCI/2022 / Assistênci a técnica em comunicação, Project Implementation Sup Individual Consult IDA / D3080 Post Limited 7,000.00 0.00 Signed 2022-06-22 2022-06-30 2022-06-27 2022-08-31 2022-07-18 2022-09-26 2022-08-22 2023-02-18 conceptualização de desenho port ant Selection s gráficos e informação sobre MRR 103/C/PRCI/2022 / AT para el Strengthening Budget Credi Individual Consult IDA / V1240 Post Open 50,000.00 0.00 Signed 2022-07-11 2022-06-30 2022-08-29 2023-03-02 2022-09-19 2023-03-14 2022-10-24 2023-04-22 aboração do Manual do IVA bility, Tax Base and SOE Gov ant Selection ernance 108/C/PRCI/2022 / Contractt of an international institution Financial Soundness and Acc Individual Consult Open - Internationa Under Implement al development specialist to IDA / D3080 Post 70,000.00 0.00 2023-07-30 2023-04-10 2023-09-17 2023-10-08 2023-11-12 2024-05-10 ess ant Selection l ation support the management of a centralized Electronic Cent er for securities collateral 109/C/PRCI/2022 / Contract a cybersecurity expert to dev Financial Soundness and Acc Individual Consult Open - Internationa Under Implement IDA / D3080 Post 95,000.00 0.00 2023-02-28 2023-03-07 2023-04-18 2023-06-08 2023-05-09 2023-06-13 2023-12-10 elop cyberattack-related reg ess ant Selection l ation ulations and response agains t the BCSTP 107/C/PRCI/2022 / Contract a specialist for the elaboratio Financial Soundness and Acc Individual Consult Direct - Internation Under Implement IDA / D3080 Post 65,000.00 0.00 2022-12-20 2023-01-10 2022-12-30 2023-01-18 2023-01-20 2023-04-24 2023-02-24 2023-08-23 n of regulations for the Secur ess ant Selection al ation ed Transactions System in Sã o Tomé and Príncipe 110/C/PRCI/2023 / Especialis Project Implementation Sup Individual Consult Under Implement IDA / D3080 Post Direct - National 27,600.00 0.00 2023-02-19 2023-04-03 2023-03-01 2023-03-22 2023-04-26 2023-10-23 ta Social port ant Selection ation 112/C/PRCI/2022 / Contracti ng a Company to Implement Financial Soundness and Acc Direct - Internation Under Implement IDA / D3080 Post Direct Selection 150,000.00 0.00 2023-02-28 2023-03-09 2023-03-10 2023-05-14 2023-11-10 the Consultants' Recommend ess al ation ations on the Public Compani es 113/C/PRCI/2023 / Contrataç Financial Soundness and Acc Individual Consult Under Implement ão do Conselheiro Técnico Pri IDA / V1240 Post Limited 100,000.00 0.00 2023-03-19 2023-03-09 2023-03-24 2023-03-27 2023-04-14 2023-05-22 2023-05-19 2023-11-15 ess ant Selection ation ncipal (CTP) do 5º RGPH 114/C/PRCI/2023 / Recrutam ento de um Assistente de M Project Implementation Sup Individual Consult Under Implement IDA / D3080 Post Open - National 26,040.00 0.00 2023-03-17 2023-03-14 2023-05-05 2023-05-26 2023-06-30 2023-12-27 onitoria e Avaliação para o Pr port ant Selection ation ojecto Reforço das Capacida des Institucionais (PRCI) 115/C/PRCI/2023 / Developm Financial Soundness and Acc Individual Consult Open - Internationa ent of Informatic system for IDA / V1240 Post 200,000.00 0.00 Under Review 2023-05-31 2023-06-27 2023-07-19 2023-08-09 2023-09-13 2024-03-11 ess ant Selection l Debt management 116/C/PRCI/2023 / Assistênci Financial Soundness and Acc Individual Consult Direct - Internation Under Implement a Técnica para o Programa P IDA / V1240 Post 15,000.00 0.00 2023-06-20 2023-04-22 2023-06-30 2023-05-04 2023-07-21 2023-05-30 2023-08-25 2024-02-21 ess ant Selection al ation hoenix para o INE 111/C/PRCI/2023 / Assistent Project Implementation Sup Individual Consult IDA / D3080 Post Direct - National 19,404.00 0.00 Canceled 2023-02-19 2023-04-12 2023-03-01 2023-03-22 2023-04-26 2023-10-23 e de Contabilidade port ant Selection 122/C/PRCI/2023 / DESIGN O Strengthening Budget Credi Individual Consult Open - Internationa Pending Impleme F THE 2024-2029 COSSIL STR IDA / D3080 bility, Tax Base and SOE Gov Prior 50,000.00 0.00 2023-09-15 2023-11-03 2023-11-24 2023-12-29 2024-06-26 ant Selection l ntation ATEGY AND OPERATIOPNAL P ernance LAN 23/C/ICB/2019 / Design of th Strengthening Budget Credi Individual Consult e 2019-2023 COSSIL strategy IDA / D3080 bility, Tax Base and SOE Gov Prior Open 50,000.00 0.00 Canceled 2019-04-30 2022-09-12 2019-06-18 2019-07-09 2019-08-13 2020-02-09 ant Selection and operatiopnal Plan ernance 80/C/PRCI/2021 / Developme Financial Soundness and Acc Individual Consult nt of Informatic system for D IDA / V1240 Prior Open 200,000.00 0.00 Canceled 2021-05-31 2021-10-27 2021-07-19 2021-08-09 2021-09-13 2022-03-12 ess ant Selection ebt management Page 5 Armenia Social Investment and Local Development Project (P148836) Procurement Plan I. General 1. Date of General Procurement Notice: December 2, 2014 2. Period covered by this procurement plan: from January 2015 to December, 2019 The TOR of consulting assignments (individual and firm) and technical specifications of packages are subject of prior agreement with the TTL. All cancellation of selection process and/or re-invitation shall be subject to Bank’s prior review. All the contracts whose cost estimation was below the Bank’s prior review threshold are subject to prior review if the financial offer of the selected firm exceeds such threshold at the proposals evaluation stage. . Irrespective of the thresholds the selection of all consultants (firm and individuals) hired for legal work or for procurement activities as well as the individual hired for long-term technical assistance or advisory services for duration of the Project (or most of it) are subject to prior review. In case of a slice and package arrangement, the prior review threshold is determined based on the aggregate value of individual contracts to be awarded under such arrangement. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. NCB (Goods) packages > US$ 200,000 and All the contracts (< USD 100,000 and < USD first 2 contracts subject to 500,000) irrespective of retroactive estimation financing 2. NCB (Works) packages > US$ 500,000 and (< USD 200,000 and < USD first 2 contracts 4,000,000) irrespective of estimation 3. Shopping (Goods) packages All the contracts (≤USD 100,000 ) subject to First 2 contracts retroactive financing 4. Shopping (Minor Works) packages First 3 contracts (≤ USD 200,000 ) 5. Direct contracting (Goods and All the contracts Works) All the contracts subject to irrespective of retroactive estimation financing 2. Prequalification. No prequalification is envisaged. 3. Proposed Procedures for Community participation in Procurement (as per paragraph. 3.19 of the Guidelines: implementation procedures of procurement of Goods, Works and Non- Consulting services and selection of Consulting services to be followed by the communities are described in detail in the POM. 4. Reference to (if any) Project Operational/Procurement Manual: Operational Manual for Social Investment and Local Development Project to be approved by the Bank. 5. Any Other Special Procurement Arrangements: Some furniture for schools and kindergartens totaling USD 70000 (Shopping) equivalent may be procured in accordance with the provisions of paragraph 1.11 of the procurement Guidelines 6. Procurement Packages with Methods and Time Schedule On the later stage the details (description of packages, schedule, methods etc.) should be provided. 1 2 3 4 5 6 7 Estimate Revie d Domesti Envisage w Cost Numbe Ref c d start of by US$ r of . Description Prefere procurem Bank Million packag No. nce ent (Prior (tax es (yes/no) process / inclusive Post) amount) Summary of the NCB Prior / (Goods) 1.8 12 NO Jul.2015 Post packages Summary of the NCB Prior / (Works) 27.46 115 NO May.2015 Post packages Summary of the Shopping Prior / (Goods) 0.76 9 NO Feb.2015 Post packages Summary of the Shopping Prior / (Minor Works) 5.4 30 NO May.15 Post packages Total 35.42 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments >US$ 100,000 and first 2 contracts under each 1. Competitive Methods (Firms) method of selection All the irrespective of estimation contracts All the contracts 2. Single Source subject to irrespective of estimation retroactive > US$ 50,000 and first 2 3. Individual financing contracts All the contracts 4. Sole source selection irrespective of estimation 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $200,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Consultants’ Services, including Training, up to an aggregate amount not exceed $400,000 equivalent may be procured in accordance with the provisions of paragraph 1.14 of the Consultant Guidelines. 4. Consultancy Assignments with Selection Methods and Time Schedule On the later stage the details (description of packages, schedule, methods etc.) should be provided. 1 2 3 4 5 6 Envisage Re Estimat Selecti d start f. Description of ed Review on of No Assignment Cost by Bank Metho procure . US$ (Prior / Post) d ment million process May.2015 Technical Supervision of Construction (9 contracts) 0.65 CQ (3 Prior / Post contracts) Architectural Design and Jan.2015 Author Supervision (21 1.6 CQ (4 Prior / Post contracts) contracts) Jan.2015 Expertise of Architectural Design (5 contracts) 0.08 CQ (1 Prior / Post contract) Expertise of Buildings and Jan.2015 Constructions (6 0.1 CQ (1 Prior / Post contracts) contract) Local Government Jul.2015 Financial Training (3 0.27 CQ (1 Prior / Post contracts) contract) Apr.2016 Beneficiary and Impact Assessment (2 contracts) 0.09 CQ (1 Prior / Post contract) Quality of civil works assessment 0.02 CQ Sep.2016 Prior / Post Study Tours, Staff Trainings and Seminars 0.12 SOE Jul.2015 Activities to support the transition from ASIF to 0.3 TDF Total Consultant and Training Services 3.23 PROCUREMENT Armenia : Armenia Social Investment and Local Development Project PLAN General Information Country: Armenia 2017-12-07 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P148836 GPN Date: Project Name: Armenia Social Investment and Local Development Project Loan / Credit No: IBRD / 84830, IBRD / 90600 Armenian Territorial Development Fund Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned TTV-14 / Reconstruction of t ASIF Institutional Strengthen Request for Quota Single Stage - One E 2018-09-1 he Drinking Water Supply Sy IBRD / 84830 Post Limited 121,140.00 117,044.39 Completed 2018-01-30 2018-02-02 2018-03-06 2018-03-01 ing and Project Management tions nvelope 7 stem in Varagavan, marz of T avush TSQ-14 / Reconstruction of t ASIF Institutional Strengthen Single Stage - One E 2019-08-0 he Kindergarten in Village Te IBRD / 84830 Post Request for Bids Open - National 412,665.00 316,541.82 Completed 2018-01-29 2018-01-29 2018-01-30 2018-01-31 2018-02-27 2018-02-22 2018-04-13 2018-03-15 2018-05-26 2018-05-04 ing and Project Management nvelope 9 gh, marz of Syunik TAR-08 AND TAT-09 / Recon struction of the Kindergarden ASIF Institutional Strengthen Single Stage - One E 2019-10-0 in Metsamor, Marz of Armavir IBRD / 84830 Post Request for Bids Open - National 808,162.00 591,539.50 Completed 2018-03-06 2018-03-05 2018-03-11 2018-03-06 2018-04-08 2018-04-03 2018-05-23 2018-04-11 2018-07-04 2018-05-14 ing and Project Management nvelope 2 and Reconstruction of the Kin dergarden in Aygavan, Marz of Ararat (with 2 lots) TTV-17 / Reconstruction of t ASIF Institutional Strengthen Single Stage - One E 2019-07-0 he External Water Supply Sys IBRD / 84830 Post Request for Bids Open - National 319,194.00 264,640.70 Completed 2018-04-03 2018-05-07 2018-04-10 2018-05-11 2018-05-08 2018-06-08 2018-06-22 2018-06-25 2018-08-03 2018-07-06 ing and Project Management nvelope 9 tem in Tsaghkavan, marz of Tavush TAN-13 / Renovation of the K indergarten Area in Village A ASIF Institutional Strengthen Request for Quota Single Stage - One E 2018-08-0 IBRD / 84830 Post Limited 38,551.00 38,127.02 Completed 2018-04-10 2018-04-06 2018-06-01 2018-04-25 ghdzq and Construction of th ing and Project Management tions nvelope 5 e External Engineering Nets, marz of Aragatsotn TAT-11 / Reconstruction of o ASIF Institutional Strengthen Single Stage - One E 2020-04-1 ne building of Yeraskh school IBRD / 84830 Post Request for Bids Open - National 296,410.00 243,112.08 Completed 2019-02-13 2019-02-25 2019-02-15 2019-03-05 2019-03-15 2019-04-02 2019-04-14 2019-04-19 2019-05-26 2019-05-20 ing and Project Management nvelope 0 into kindergarten, marz of Ar arat TVZ-09 / Reconstruction of K Support to Socio-Economic Request for Quota Single Stage - One E 2019-12-1 hndzorut water source and dr IBRD / 84830 Development and Capacity Post Open - National 33,000.00 33,737.31 Completed 2019-08-31 2019-09-04 2019-10-05 2019-09-24 tions nvelope 4 inking water line Building at the Local Level TTV-18 / Reconstruction of t Support to Socio-Economic Single Stage - One E 2021-01-2 he Drinking Water Distributin IBRD / 84830 Development and Capacity Post Request for Bids Open - National 391,000.00 325,626.73 Completed 2019-11-14 2019-11-12 2019-11-19 2019-11-13 2019-12-17 2019-12-10 2020-01-16 2019-12-20 2020-02-27 2020-02-07 nvelope 2 g Network of Paravakar Building at the Local Level TSH-21 / Construction of "St. Support to Socio-Economic Single Stage - One E 2021-07-1 Mariam" Kindergarten in Gyu IBRD / 84830 Development and Capacity Post Request for Bids Open - National 412,000.00 353,035.83 Completed 2020-03-10 2020-03-10 2020-03-15 2020-03-10 2020-04-12 2020-04-07 2020-05-12 2020-04-20 2020-06-23 2020-06-04 nvelope 8 mri Building at the Local Level TSQ-16 / Construction of the Support to Socio-Economic Single Stage - One E 2021-11-0 drinking water pipeline in Kh IBRD / 84830 Development and Capacity Post Request for Bids Open - National 177,000.00 0.00 Canceled 2020-12-25 2020-12-23 2020-12-30 2020-12-23 2021-02-03 2021-01-27 2021-03-05 2021-04-07 nvelope 3 natsakh community Building at the Local Level TLR-13 / Reconstruction of t Support to Socio-Economic Single Stage - One E 2022-05-2 he second building of kinderg IBRD / 84830 Development and Capacity Post Request for Bids Open - National 364,000.00 265,250.60 Signed 2021-03-17 2021-03-15 2021-03-24 2021-03-16 2021-04-21 2021-04-12 2021-05-21 2021-04-26 2021-07-02 2021-05-21 nvelope 8 arten No. 11 in Vanadzor Building at the Local Level Support to Socio-Economic TSH-22 / "Zangak" kindegart Single Stage - One E 2022-08-0 IBRD / 84830 Development and Capacity Post Request for Bids Open - National 443,000.00 841,967.18 Signed 2021-04-27 2021-04-16 2021-05-04 2021-04-16 2021-06-01 2021-05-14 2021-07-01 2021-06-16 2021-08-12 2021-07-16 en construction of Gyumri nvelope 7 Building at the Local Level Support to Socio-Economic TSH-23 / Reconstruction of t Single Stage - One E 2022-04-0 IBRD / 84830 Development and Capacity Post Request for Bids Open - National 311,000.00 265,690.20 Signed 2021-04-27 2021-04-16 2021-05-02 2021-04-16 2021-05-30 2021-05-14 2021-06-29 2021-06-09 2021-08-10 2021-07-01 he kindegarten of Panik nvelope 7 Building at the Local Level Support to Socio-Economic TSH-19 / Construction of kin Single Stage - One E 2022-08-0 IBRD / 84830 Development and Capacity Post Request for Bids Open - National 407,000.00 374,000.87 Signed 2021-04-27 2021-04-19 2021-05-04 2021-04-19 2021-06-01 2021-05-17 2021-07-01 2021-06-16 2021-08-12 2021-07-16 degarten of Horom nvelope 7 Building at the Local Level TSQ-16-2 / Construction of t Support to Socio-Economic Single Stage - One E 2022-03-1 he drinking water pipeline in IBRD / 84830 Development and Capacity Post Request for Bids Open - National 160,000.00 159,702.94 Signed 2021-04-30 2021-04-20 2021-05-05 2021-04-20 2021-06-02 2021-05-18 2021-07-02 2021-06-02 2021-08-13 2021-06-25 nvelope 1 Khnatsakh Building at the Local Level W-27.29 / Lot 1 "W-27, Cons truction and repair of irrigati on system in Byureghavan e Request for Bids - nlarged community" Support to Intercommunity S Single Stage - One E Small Works SPD 2022-06-2 Lot 2 "W-29, Construction an IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 805,000.00 552,259.96 Completed 2021-06-10 2021-06-01 2021-06-15 2021-06-01 2021-07-13 2021-06-29 2021-08-12 2021-07-26 2021-09-23 2021-08-31 nvelope (1 envelope proce 0 d repair of a gravity irrigation ment Initiatives ss) system in Hoghmik, Goghovit , and Torosgyugh settlement s of Sarapat community" AFT-TV-01 / Construction of pumping station, drinking wa Request for Bids - Support to Socio-Economic ter supply pipeline and daily Single Stage - One E Small Works SPD 2022-08-3 IBRD / 90600 Development and Capacity Post Request for Bids Open - National 361,000.00 360,928.87 Signed 2021-06-21 2021-06-21 2021-06-26 2021-06-21 2021-07-24 2021-07-19 2021-08-23 2021-08-05 2021-10-04 2021-09-07 regulation reservoir (DRR), re nvelope (1 envelope proce 0 Building at the Local Level construction of the distributio ss) n network of Archis settleme nt W-29 / Construction and rep Support to Intercommunity S air of a gravity irrigation syst Single Stage - One E 2022-05-0 IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 285,000.00 0.00 Canceled 2021-04-27 2021-04-19 2021-05-04 2021-04-19 2021-06-01 2021-05-17 2021-07-01 2021-08-12 em in Hoghmik, Goghovit, an nvelope 9 ment Initiatives d Torosgyugh settlements of Sarapat community AFT-TV-02 / Construction of pumping station, drinking wa Request for Bids - Support to Socio-Economic ter supply pipeline and daily Single Stage - One E Small Works SPD 2022-06-2 IBRD / 90600 Development and Capacity Post Request for Bids Open - National 240,000.00 0.00 Canceled 2021-06-10 2021-06-01 2021-06-15 2021-06-01 2021-07-13 2021-06-29 2021-08-12 2021-09-23 regulation reservoir (DRR), re nvelope (1 envelope proce 0 Building at the Local Level construction of the distributio ss) n network of Lchkadzor settle ment Page 1 AFT-TV-02-2/TV-03 / Constru Request for Bids - Support to Socio-Economic ction and Expansion of drinki Single Stage - One E Small Works SPD 2022-08-0 IBRD / 90600 Development and Capacity Post Request for Bids Open - National 383,000.00 296,825.31 Signed 2021-07-27 2021-07-22 2021-08-01 2021-07-22 2021-08-29 2021-08-19 2021-09-28 2021-09-24 2021-11-09 2021-10-22 ng water supply systems of L nvelope (1 envelope proce 6 Building at the Local Level chkadzor and Movses settle ss) ments W-29-2 / Construction and re Request for Bids - Support to Intercommunity S pair of a gravity irrigation sys Single Stage - One E Small Works SPD 2022-06-1 IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 310,000.00 0.00 Canceled 2021-08-06 2021-08-03 2021-08-13 2021-08-03 2021-09-10 2021-08-31 2021-10-10 2021-09-17 2021-11-21 tem in Hoghmik, Goghovit, a nvelope (1 envelope proce 9 ment Initiatives nd Torosgyugh settlements o ss) f Sarapat community W-29-3 / Construction and re Request for Bids - Support to Intercommunity S pair of a gravity irrigation sys Single Stage - One E Small Works SPD 2022-09-0 IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 310,000.00 0.00 Canceled 2021-10-21 2021-10-07 2021-10-28 2021-10-07 2021-11-25 2021-11-11 2021-12-25 2021-11-22 2022-02-05 tem in Hoghmik, Goghovit, a nvelope (1 envelope proce 3 ment Initiatives nd Torosgyugh settlements o ss) f Sarapat community AFT-TV-03-2 / Expansion of Request for Bids - Movses settlement water sup Support to Socio-Economic Single Stage - One E Small Works SPD 2022-07-1 ply system: construction of p IBRD / 90600 Development and Capacity Post Request for Bids Open - National 138,000.00 0.00 Canceled 2021-10-29 2021-10-19 2021-11-03 2021-10-19 2021-12-01 2021-11-16 2021-12-31 2021-11-22 2022-02-12 nvelope (1 envelope proce 2 umping station and pumping Building at the Local Level ss) pipeline, repair of a daily reg ulation reservoir (DRR). W-36/W-37 / Construction of Request for Bids - Support to Intercommunity S parking lots in the enlarged c Single Stage - One E Small Works SPD 2022-12-0 IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 302,000.00 0.00 Canceled 2021-12-20 2021-12-15 2021-12-27 2021-12-16 2022-01-24 2022-01-26 2022-02-23 2022-04-06 ommunities of Akunk, Kotayk nvelope (1 envelope proce 2 ment Initiatives marz and Geghamasar, Gegh ss) arkunik marz of RA AFT-TV-03-3 / Expansion of Request for Bids - Movses settlement water sup Support to Socio-Economic Single Stage - One E Small Works SPD 2022-11-0 ply system: construction of p IBRD / 90600 Development and Capacity Post Request for Bids Open - National 178,000.00 0.00 Canceled 2022-03-09 2022-04-12 2022-03-14 2022-04-12 2022-04-11 2022-05-10 2022-05-11 2022-06-21 2022-06-22 nvelope (1 envelope proce 4 umping station and pumping Building at the Local Level ss) pipeline, repair of a daily reg ulation reservoir (DRR). W-29-4 / Construction and re Request for Bids - Support to Intercommunity S pair of a gravity irrigation sys Single Stage - One E Small Works SPD 2023-03-2 IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 301,000.00 0.00 Canceled 2022-03-09 2022-03-16 2022-04-13 2022-05-13 2022-06-24 tem in Hoghmik, Goghovit, a nvelope (1 envelope proce 1 ment Initiatives nd Torosgyugh settlements o ss) f Sarapat community W-36-2/W-37-2 / Constructio Request for Bids - n of parking lots in the enlarg Support to Intercommunity S Single Stage - One E Small Works SPD 2022-11-2 ed communities of Akunk, Ko IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 301,000.00 0.00 Canceled 2022-02-11 2022-02-07 2022-02-18 2022-03-06 2022-03-18 2022-03-07 2022-04-17 2022-05-29 nvelope (1 envelope proce 5 tayk marz and Geghamasar, ment Initiatives ss) Gegharkunik marz of RA Request for Bids - WAFT-KQ-01 / Construction Support to Intercommunity S Single Stage - One E Small Works SPD 2023-03-2 of parking lot in the enlarged IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 203,000.00 256,679.97 Signed 2022-05-30 2022-05-02 2022-06-06 2022-05-02 2022-07-04 2022-05-30 2022-08-03 2022-08-04 2022-09-28 2022-09-10 nvelope (1 envelope proce 7 community of Akunk, Kotayk ment Initiatives ss) marz of RA Request for Bids - AFT-GQ-01 / Renovation of t Support to Socio-Economic Single Stage - One E Small Works SPD 2023-01-2 he wrestling hall in the Hous IBRD / 90600 Development and Capacity Post Request for Bids Open - National 67,000.00 0.00 Canceled 2022-05-30 2022-04-27 2022-06-06 2022-04-27 2022-07-04 2022-05-25 2022-08-03 2022-09-28 nvelope (1 envelope proce 6 e of Culture of the Akunk co Building at the Local Level ss) mmunity WAFT-SH-02 / Construction a Request for Bids - nd repair of a gravity irrigatio Support to Intercommunity S Single Stage - One E Small Works SPD 2023-04-2 n system in Hoghmik, Gogho IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 313,000.00 0.00 Canceled 2022-05-30 2022-05-03 2022-06-06 2022-05-03 2022-07-04 2022-05-31 2022-08-03 2022-08-04 2022-09-28 nvelope (1 envelope proce 6 vit, and Torosgyugh settleme ment Initiatives ss) nts of Sarapat community WAFT-GQ-01 / Construction Request for Bids - Support to Intercommunity S of a parking lot in the enlarg Single Stage - One E Small Works SPD 2023-04-1 IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 150,000.00 147,067.76 Signed 2022-06-20 2022-06-27 2022-06-27 2022-06-27 2022-07-25 2022-07-25 2022-08-24 2022-08-29 2022-10-19 2022-10-03 ed community of Geghamasa nvelope (1 envelope proce 7 ment Initiatives r, Gegharkunik marz of RA. ss) AFT-LR-02 / Replacement of Request for Quota aluminum stained glass wind Support to Intercommunity S Request for Quota Single Stage - One E tions - Small Work 2022-12-1 ows and renovation of bathro IBRD / 84830 ocial and Economic Develop Post Open - National 83,000.00 83,033.81 Signed 2022-07-26 2022-07-25 2022-09-13 2022-09-13 tions nvelope s (Emergency) SP 2 oms of Stepanavan "Culture ment Initiatives D -Competitive and Entertainment Center" Request for Quota AFT-SH-03 / Overhaul of the Support to Intercommunity S Request for Quota Single Stage - One E tions - Small Work 2023-03-0 balcony and gymnasium of G IBRD / 84830 ocial and Economic Develop Post Open - National 122,000.00 0.00 Canceled 2022-08-24 2022-09-08 2022-10-19 tions nvelope s (Emergency) SP 3 yumri school No. 1 ment Initiatives D -Competitive Request for Bids - AFT-LR-01 / Reconstruction o Support to Intercommunity S Single Stage - One E Small Works SPD 2023-07-1 f the Lori Berd community ce IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 328,000.00 0.00 Canceled 2022-08-19 2022-09-15 2022-08-26 2022-09-15 2022-09-23 2022-10-13 2022-10-23 2022-12-18 nvelope (1 envelope proce 6 nter, with the construction of ment Initiatives ss) the second floor AFT-TV-03-4 / Expansion of Request for Bids - Movses settlement water sup Support to Socio-Economic Single Stage - One E Small Works SPD 2023-06-0 ply system: construction of p IBRD / 90600 Development and Capacity Post Request for Bids Open - National 208,000.00 0.00 Canceled 2022-09-23 2022-09-28 2022-10-26 2022-11-25 2023-01-06 nvelope (1 envelope proce 5 umping station and pumping Building at the Local Level ss) pipeline, repair of a daily reg ulation reservoir (DRR). WAFT-SH-01/WAFT-SH-02-2 / Lot 1 "Reconstruction of the I rrigation System in Amasia C Request for Bids - Support to Intercommunity S onsolidated Community ", Lo Single Stage - One E Small Works SPD 2023-11-1 IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 952,000.00 0.00 Signed 2022-10-04 2022-10-06 2022-10-09 2022-10-06 2022-11-06 2022-11-03 2022-12-06 2022-12-20 2023-01-17 t 2 "Construction and repair nvelope (1 envelope proce 3 ment Initiatives of a gravity irrigation system ss) in Hoghmik, Goghovit, and T orosgyugh settlements of Sar apat community" AFT-TV-03-4/AFT-TV-04 / Lot 1, Expansion of Movses settl ement water supply system: Request for Bids - construction of pumping stati Support to Socio-Economic Single Stage - One E Small Works SPD 2024-05-1 on and pumping pipeline, rep IBRD / 90600 Development and Capacity Post Request for Bids Open - National 946,000.00 0.00 Canceled 2022-10-04 2022-09-29 2022-10-09 2022-09-29 2022-11-06 2022-10-27 2022-12-06 2022-11-21 2023-01-17 nvelope (1 envelope proce 1 air of a daily regulation reser Building at the Local Level ss) voir (DRR), Lot 2, Construction of Drinkin g Water Line and Springs Int akes of Getahovit Settlement AFT-GQ-01-2/AFT-AN-02 / Lo t 1, "Renovation of the wrestl Request for Bids - Support to Socio-Economic ing hall in the House of Cultu Single Stage - One E Small Works SPD 2024-03-1 IBRD / 90600 Development and Capacity Post Request for Bids Open - National 937,000.00 0.00 Signed 2022-10-04 2022-10-17 2022-10-09 2022-10-17 2022-11-06 2022-11-14 2022-12-06 2022-12-08 2023-01-17 re of the Akunk community", nvelope (1 envelope proce 2 Building at the Local Level Lot 2, "Construction of the Al ss) agyaz Community Center"․ Request for Bids - AFT-LR-01-2 / Reconstructio Support to Intercommunity S Single Stage - One E Small Works SPD 2023-09-2 n of the Lori Berd community IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 331,000.00 0.00 Canceled 2022-11-01 2022-11-01 2022-11-08 2022-11-01 2022-12-06 2022-11-15 2023-01-05 2023-03-02 nvelope (1 envelope proce 8 center, with the construction ment Initiatives ss) of the second floor Page 2 AFT-VZ-02 / Construction of Request for Bids - Support to Intercommunity S a Sewerage System and Bio-t Single Stage - One E Small Works SPD 2024-01-2 IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 691,000.00 0.00 Signed 2023-01-17 2023-01-17 2023-01-24 2023-01-17 2023-02-21 2023-02-14 2023-03-21 2023-03-06 2023-05-02 reatment Facility in Nor Avan nvelope (1 envelope proce 7 ment Initiatives District of Yeghegnadzor City ss) Request for Bids - AFT-LR-01-3 / Reconstructio Support to Intercommunity S Single Stage - One E Small Works SPD Under Imple 2023-12-0 n of the Lori Berd community IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 337,000.00 0.00 2023-01-24 2023-01-26 2023-01-31 2023-01-26 2023-02-28 2023-02-23 2023-03-28 2023-04-21 2023-05-09 nvelope (1 envelope proce mentation 5 center, with the construction ment Initiatives ss) of the second floor Request for Bids - Support to Intercommunity S Single Stage - One E Small Works SPD 2023-11-1 TEST / TEST IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 1.00 0.00 Canceled 2023-01-18 2022-12-01 2023-01-23 2023-01-18 2023-03-06 2023-01-18 2023-04-05 2023-01-18 2023-05-17 nvelope (1 envelope proce 3 ment Initiatives ss) AFT-GQ-01-3 / Renovation of Request for Quota Support to Intercommunity S the Wrestling Hall Located in Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-11-2 IBRD / 90600 ocial and Economic Develop Post Open - National 85,000.00 0.00 2023-06-04 2023-06-01 2023-07-30 the House of Culture of Akun tions nvelope s (Emergency) SP mentation 7 ment Initiatives k Community of Gegharkunik D -Competitive Marz of RoA Request for Bids - AFT-TV-05 / Renovation of th Support to Intercommunity S Single Stage - One E Small Works SPD Under Imple 2024-06-0 e kindergarten in Khashtarak IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 547,000.00 0.00 2023-05-30 2023-06-01 2023-06-04 2023-06-01 2023-07-02 2023-06-29 2023-08-01 2023-09-12 nvelope (1 envelope proce mentation 8 settlement of Tavush marz of ment Initiatives ss) RoA Request for Quota AFT-SH-03-4 / Overhaul of th Support to Socio-Economic Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-01-2 e balcony and gymnasium of IBRD / 84830 Development and Capacity Post Open - National 135,000.00 0.00 2023-06-29 2023-05-30 2023-08-24 tions nvelope s (Emergency) SP mentation 1 Gyumri School No. 1, Shirak Building at the Local Level D -Competitive marz, RA AFT-TV-04-2 / Construction o Request for Bids - Support to Socio-Economic f external water line and spri Single Stage - One E Small Works SPD Under Imple 2024-12-2 IBRD / 90600 Development and Capacity Post Request for Bids Open - National 796,000.00 0.00 2023-06-07 2023-06-08 2023-06-12 2023-06-08 2023-07-10 2023-07-24 2023-09-04 ng connections of Getahovit nvelope (1 envelope proce mentation 7 Building at the Local Level community, Tavush marz, RA ss) Request for Bids - AFT-SH-01 / Construction of Support to Intercommunity S Single Stage - One E Small Works SPD Under Imple 2024-12-2 a kindergarten in the Nor Kny IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 1,202,000.00 0.00 2023-06-28 2023-06-22 2023-07-05 2023-06-22 2023-08-02 2023-08-16 2023-09-27 nvelope (1 envelope proce mentation 0 ak community of Shirank mar ment Initiatives ss) z, RA AFT-AR-01 / Procurement of Request for Bids - Support to Intercommunity S Construction of the Sports Gr Single Stage - One E Small Works SPD 2024-01-0 IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 123,000.00 0.00 Canceled 2023-05-25 2023-05-29 2023-05-30 2023-05-29 2023-06-27 2023-06-26 2023-07-27 2023-09-07 ound of the Myasnikyan Settl nvelope (1 envelope proce 5 ment Initiatives ement School of Armavir Mar ss) z of RoA AFT-AR-01-2 / Procurement Request for Quota Support to Intercommunity S of Construction of the Sports Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-01-0 IBRD / 90600 ocial and Economic Develop Post Open - National 123,000.00 0.00 2023-07-15 2023-09-09 Ground of the Myasnikyan Se tions nvelope s (Emergency) SP lementation 7 ment Initiatives ttlement School of Armavir M D -Competitive arz of RoA TSQ-01 / Reconstruction of H Support to Socio-Economic Request for Quota Open - Internationa ouse-museum after Sero Kha IBRD / 84830 Development and Capacity Prior 0.00 145,640.22 Signed 2015-10-06 tions l nzadyan in Goris, Marz of Sy Building at the Local Level uniq TTV-02 / Reconstruction of t Support to Socio-Economic Request for Quota Open - Internationa he third building of N2 kinder IBRD / 84830 Development and Capacity Prior 0.00 138,337.21 Signed 2015-09-19 tions l garten in Berd, Marz of Tavo Building at the Local Level ush TAT-01 / Reinforcement, ove Support to Socio-Economic Request for Quota Open - Internationa rhaul of ambulatory in the vill IBRD / 84830 Development and Capacity Prior 0.00 78,366.58 Signed 2015-09-29 tions l age of Norashen, Marz of Ara Building at the Local Level rat TSH-01 / Construction of a s Support to Socio-Economic Single Stage - One E chool for 100 pupils in the vill IBRD / 84830 Development and Capacity Prior Request for Bids Open - National 0.00 386,367.08 Signed 2015-11-10 2015-11-30 nvelope age of Vardaqar, Marz of Shir Building at the Local Level ak TVZ-01 / Reinforcement, rec Support to Socio-Economic onstruction of the kindergart Single Stage - One E IBRD / 84830 Development and Capacity Prior Request for Bids Open - National 0.00 294,656.01 Signed 2015-11-23 2015-12-24 en in the village of Zaritap, M nvelope Building at the Local Level arz of Vayots Dzor GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-11 / Supply of furniture f ASIF Institutional Strengthen Request for Quota Single Stage - One E IBRD / 84830 Post Limited 96,700.00 96,365.03 Completed 2018-03-11 2018-03-07 2018-05-06 2018-03-26 2018-07-15 2018-08-23 or kindergartens for marzes ing and Project Management tions nvelope of RA TG-12 / Supply of goods for kindergartens, schools and c ASIF Institutional Strengthen Single Stage - One E IBRD / 84830 Post Request for Bids Open - National 184,000.00 150,596.63 Completed 2018-08-06 2018-08-14 2018-08-11 2018-08-15 2018-09-08 2018-09-12 2018-10-08 2018-09-28 2018-11-19 2018-10-05 2019-02-02 2019-02-21 ommunity centers in the mar ing and Project Management nvelope zes of RA (consisted of 3 Lots ) TIIG-01 / Procurement of Ve Support to Intercommunity S Single Stage - One E hicles, Equipment and Trash IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 924,950.00 806,891.39 Completed 2018-10-24 2018-10-24 2018-10-29 2018-11-08 2018-11-26 2018-11-27 2018-12-26 2018-12-14 2019-02-06 2019-01-11 2019-05-07 2019-05-08 nvelope Bins for Communities ment Initiatives TG-13 / Procurement of furni ASIF Institutional Strengthen Request for Propo Single Stage - One E ture for the kindergartens of IBRD / 84830 Post Limited 45,115.00 30,222.32 Completed 2018-11-15 2018-11-12 2018-11-20 2018-11-14 2018-11-27 2018-11-21 2018-12-07 2018-11-22 2018-12-21 2018-11-30 2019-01-15 2018-12-25 ing and Project Management sals nvelope the regions of the RoA TIIG-02 / Procurement of Ve Support to Intercommunity S Single Stage - One E hicles and Equipment for Co IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 933,970.00 492,656.34 Completed 2019-03-28 2019-04-03 2019-04-02 2019-04-04 2019-04-30 2019-05-02 2019-05-30 2019-06-19 2019-07-11 2019-06-26 2019-10-09 2019-09-13 nvelope mmunities ment Initiatives TG-14 / Supply of furniture f ASIF Institutional Strengthen Request for Quota Single Stage - One E or schools and kindergartens IBRD / 84830 Post Open - National 89,000.00 56,070.85 Completed 2019-04-08 2019-04-18 2019-06-03 2019-05-22 2019-10-01 2019-10-29 ing and Project Management tions nvelope for marzes of RoA TIIG-03 / Procurement of Ve Support to Intercommunity S Single Stage - One E hicles and Equipment for Co IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 933,460.00 920,649.72 Completed 2019-05-24 2019-05-31 2019-05-29 2019-06-04 2019-06-26 2019-07-02 2019-07-26 2019-07-18 2019-09-06 2019-08-16 2019-12-05 2019-12-14 nvelope mmunities ment Initiatives Support to Intercommunity S TIIG-04 / Procurement of 4 M Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 377,000.00 272,097.79 Completed 2019-06-24 2019-06-25 2019-06-29 2019-07-31 2019-07-27 2019-07-31 2019-08-26 2019-08-06 2019-10-07 2019-08-27 2019-12-21 2019-12-18 ultifunctional Excavators nvelope ment Initiatives TIIG-05 / Procurement of Ve Support to Intercommunity S Single Stage - One E hicles and Equipment for Co IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 893,080.00 741,001.05 Completed 2019-08-05 2019-08-15 2019-08-10 2019-08-29 2019-09-07 2019-09-13 2019-09-08 2019-09-27 2019-10-20 2019-11-01 2020-01-18 2020-01-21 nvelope mmunities consisted of 9 Lot ment Initiatives s Page 3 TIIG-06 / Procurement of Ve Support to Intercommunity S Single Stage - One E hicles and Equipment for Co IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 685,995.00 416,500.74 Completed 2019-09-10 2019-09-11 2019-09-15 2019-09-13 2019-09-17 2019-10-17 2019-10-17 2019-11-01 2019-11-28 2019-11-26 2020-02-26 2019-12-13 nvelope mmunities ment Initiatives Support to Intercommunity S TIIG-07 / Procurement of 4 M Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 378,000.00 369,714.75 Completed 2019-11-06 2019-10-31 2019-11-11 2019-11-01 2019-12-09 2019-11-29 2020-01-08 2019-12-04 2020-02-19 2019-12-18 2020-05-04 2020-06-03 ultifunctional Excavators nvelope ment Initiatives TG-15 / Supply of furniture f ASIF Institutional Strengthen Request for Quota Single Stage - One E or kindergartens, schools an IBRD / 84830 Post Open - National 34,850.00 26,899.28 Signed 2019-12-07 2019-12-26 2020-01-19 2020-01-18 2020-03-04 2020-02-29 ing and Project Management tions nvelope d cultural centers for the ma rzes of RoA Support to Intercommunity S TIIG-06/8 / TIIG-06/8 Contrac IBRD / 84830 ocial and Economic Develop Post Direct Selection Direct 2,310.00 1,775.45 Completed 2020-01-08 2020-01-09 2020-01-08 2019-09-12 2020-01-08 2019-12-04 2020-01-08 2019-12-16 t "1 Hydraulic Twist Bucket" ment Initiatives TIIG-08 / Procurement of 500 ASIF Institutional Strengthen Request for Quota Single Stage - One E IBRD / 84830 Post Open - National 93,025.00 72,076.69 Completed 2020-03-02 2020-02-28 2020-04-13 2020-04-16 2020-06-12 2020-06-19 Metal Trash Bins ing and Project Management tions nvelope TIIG-09 / Procurement of co Support to Intercommunity S mmunal equipment for Areni, Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 916,000.00 862,774.43 Completed 2020-03-15 2020-03-17 2020-03-20 2020-03-18 2020-04-17 2020-04-15 2020-05-17 2020-05-06 2020-06-28 2020-06-11 2020-09-26 2020-09-11 Sisian, Akhtala, Gladzor, Egh nvelope ment Initiatives egis communities TIIG-10 / Procurement of Agr Support to Intercommunity S icultural Equipment for Shno Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 949,585.00 0.00 Canceled 2020-03-29 2020-04-01 2020-04-03 2020-04-01 2020-05-01 2020-05-31 2020-07-12 2020-10-10 gh, Akhtala, Eghegis, Sarcha nvelope ment Initiatives pet, Ani, Eghvard Communiti es TIIG-11 / Procurement of Agr Support to Intercommunity S icultural Heavy Equipment fo Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 812,000.00 678,871.19 Completed 2020-04-29 2020-05-08 2020-05-04 2020-05-08 2020-06-01 2020-06-05 2020-07-01 2020-06-22 2020-08-12 2020-08-13 2020-11-10 2020-11-14 r Shnogh, Akhtala, Yeghegis, nvelope ment Initiatives Sarchapet, Ani, Yeghvard Co mmunities TIIGS-01 / Procurement of a Support to Intercommunity S Request for Quota Single Stage - One E Motor Cultivator for Akhtala IBRD / 84830 ocial and Economic Develop Post Open - National 5,000.00 5,059.10 Completed 2020-05-04 2020-05-09 2020-06-29 2020-06-18 2020-08-28 2020-08-12 tions nvelope Community ment Initiatives TIIGS-02 / Procurement of A Support to Intercommunity S Request for Quota Single Stage - One E gricultural Sprayers for Shno IBRD / 84830 ocial and Economic Develop Post Open - National 21,000.00 7,059.79 Completed 2020-05-04 2020-05-09 2020-06-29 2020-06-18 2020-08-28 2020-07-24 tions nvelope gh, Akhtala and Sarchapet C ment Initiatives ommunities TIIGS-03 / Procurement of Se Support to Intercommunity S Request for Quota Single Stage - One E ed Drills for Shnogh, Akhtala IBRD / 84830 ocial and Economic Develop Post Open - National 53,000.00 37,834.27 Completed 2020-05-04 2020-05-09 2020-06-29 2020-06-18 2020-08-28 2020-08-05 tions nvelope and Sarchapet Communities ment Initiatives TIIGS-04 / Procurement of B Support to Intercommunity S Request for Quota Single Stage - One E aling Machines for Yeghegis IBRD / 84830 ocial and Economic Develop Post Open - National 32,000.00 23,671.07 Completed 2020-05-04 2020-05-09 2020-06-29 2020-06-18 2020-08-28 2020-07-18 tions nvelope and Yeghvard Communities ment Initiatives TIIGS-05 / Procurement of Gr Support to Intercommunity S Request for Quota Single Stage - One E ass-Mowing Machines for Akh IBRD / 84830 ocial and Economic Develop Post Open - National 6,500.00 3,426.08 Completed 2020-05-04 2020-05-09 2020-06-29 2020-06-18 2020-08-28 2020-08-15 tions nvelope tala, Yeghegis and Yeghvard ment Initiatives Communities TIIGS-06 / Procurement of Pl Support to Intercommunity S oughs, Harrows and Cultivato Request for Quota Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Open - National 73,000.00 53,397.79 Completed 2020-05-04 2020-05-09 2020-06-29 2020-06-18 2020-08-28 2020-08-15 rs for Shnogh, Yeghegis, Sarc tions nvelope ment Initiatives hapet and Yeghvard Commu nities TIIG-12 / Procurement of co Support to Intercommunity S mmunal equipment for Shog Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 983,000.00 831,467.34 Completed 2020-05-22 2020-05-27 2020-05-27 2020-06-28 2020-06-24 2020-06-29 2020-07-24 2020-08-04 2020-09-04 2020-09-09 2020-12-03 2021-02-11 hakat, Akhtala, Gladzor, Yegh nvelope ment Initiatives egis, Sarchapet, Ani, Yeghvar d Communities TIIG-13 / Procurement of Agr Support to Intercommunity S icultural Heavy Equipment fo Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 483,000.00 410,152.86 Completed 2020-06-22 2020-06-29 2020-06-27 2020-07-06 2020-07-25 2020-07-27 2020-08-24 2020-08-17 2020-10-05 2020-09-29 2021-01-03 2020-12-15 r Kapan, Metsavan, Akunq, G nvelope ment Initiatives eghamasar, Alaverdi Commu nities TIIG-14 / Procurement of Co Support to Intercommunity S Single Stage - One E mmunal Equipment for Kapa IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 957,000.00 780,364.18 Completed 2020-07-13 2020-07-10 2020-07-18 2020-07-13 2020-08-15 2020-08-13 2020-09-14 2020-09-14 2020-10-26 2020-10-21 2021-02-23 2021-03-18 nvelope n, Metsavan, Marmashen Co ment Initiatives mmunities TIIG-15 / Procurement of Co Support to Intercommunity S Single Stage - One E mmunal Equipment for Gegh IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 771,550.00 585,502.29 Completed 2020-08-19 2020-08-21 2020-08-24 2020-08-24 2020-09-21 2020-09-22 2020-10-21 2020-09-30 2020-12-02 2020-11-06 2021-04-01 2021-03-10 nvelope amasar, Akunq, Alaverdi Co ment Initiatives mmunities TG-16 / Procurement of Com ASIF Institutional Strengthen Request for Quota Single Stage - One E IBRD / 84830 Post Open - National 21,000.00 20,982.30 Signed 2020-09-30 2020-09-29 2020-11-25 2020-10-24 2021-02-03 puter equipment for ATDF ing and Project Management tions nvelope Support to Intercommunity S TIIGS-07 / Procurement of a Request for Quota Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Open - National 70,000.00 65,740.35 Completed 2020-10-03 2020-09-28 2020-11-28 2020-10-24 2021-02-26 2020-12-18 Bus for Ani community tions nvelope ment Initiatives TIIGS-08 / Procurement of a Support to Intercommunity S Request for Quota Single Stage - One E Mini-loader for Yeghvard com IBRD / 84830 ocial and Economic Develop Post Open - National 54,000.00 0.00 Canceled 2020-10-03 2020-09-28 2020-11-28 2021-02-26 tions nvelope munity ment Initiatives Support to Intercommunity S TIIGS-10 / Procurement of 1 Request for Quota Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Open - National 53,000.00 47,780.97 Completed 2020-10-26 2020-10-20 2020-12-21 2020-11-14 2021-04-20 2020-12-19 Mini-loader tions nvelope ment Initiatives TIIGS-09 / Procurement of 2 Support to Intercommunity S Request for Quota Single Stage - One E technical assistance cars wit IBRD / 84830 ocial and Economic Develop Post Open - National 51,000.00 50,998.75 Completed 2020-10-26 2020-10-20 2020-12-21 2020-11-14 2021-04-20 2021-02-10 tions nvelope h attachments ment Initiatives Support to Intercommunity S TIIGS-11 / Procurement of 25 Request for Quota Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Open - National 18,000.00 45,127.49 Completed 2020-10-26 2020-11-10 2020-12-21 2020-12-08 2021-02-19 2020-12-16 0 Garbage Container tions nvelope ment Initiatives TIIG-16 / Procurement of Co Support to Intercommunity S Single Stage - One E mmunal Equipment for Jrvez IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 288,000.00 274,664.33 Completed 2020-11-13 2020-11-12 2020-11-18 2020-12-02 2020-12-16 2020-12-21 2021-01-15 2020-12-29 2021-02-26 2021-02-12 2021-06-26 2021-05-21 nvelope h Community ment Initiatives TIIG-17 / Supply and installat Support to Intercommunity S ion of solar photovoltaic stati Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 191,600.00 160,964.78 Completed 2020-11-20 2021-04-12 2020-11-25 2021-04-12 2020-12-23 2021-05-10 2021-01-22 2021-05-27 2021-03-05 2021-06-30 2021-06-03 2022-01-28 ons on the territories of muni nvelope ment Initiatives cipal organizations in Charen tsavan Page 4 TG-17 / Procurement of a hy ASIF Institutional Strengthen Request for Quota Single Stage - One E IBRD / 84830 Post Open - National 2,500.00 2,047.05 Completed 2020-12-24 2021-01-18 2021-01-26 2021-02-06 2021-04-06 2021-03-02 brid portable computer for A ing and Project Management tions nvelope TDF TIIG-18 / Supply and installat Support to Intercommunity S Single Stage - One E ion of a solar photovoltaic sta IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 69,000.00 56,726.58 Completed 2021-07-22 2021-07-21 2021-07-27 2021-07-22 2021-08-24 2021-08-18 2021-09-23 2021-09-17 2021-11-04 2021-09-30 2022-02-02 2022-02-12 nvelope tion of Meghradzor communit ment Initiatives y. TIIG-19 / Procurement of Co Support to Intercommunity S mmunal and Agricultural Hea Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 940,000.00 825,122.95 Signed 2021-10-27 2021-10-25 2021-11-01 2021-10-26 2021-11-29 2021-11-23 2021-12-29 2021-12-13 2022-01-26 2022-01-19 2022-04-26 2022-04-17 vy Equipment for Ijevan, Meg nvelope ment Initiatives hradzor and Lermontovo Co mmunities TIIGS-12 / Procurement of 35 Support to Intercommunity S Request for Quota Single Stage - One E 0 Garbage Containers for Ijev IBRD / 84830 ocial and Economic Develop Post Open - National 58,500.00 0.00 Canceled 2021-11-01 2021-10-22 2021-12-27 2022-03-07 tions nvelope an Community ment Initiatives TG-18 / Supply of furniture f Support to Socio-Economic Request for Quota Single Stage - One E or St. Mariam kindergarten in IBRD / 84830 Development and Capacity Post Open - National 12,000.00 0.00 Canceled 2021-10-18 2021-10-01 2021-12-06 2022-01-15 tions nvelope Gyumri, Marz of Shirak Building at the Local Level TG-18-2 / Supply of furniture Support to Socio-Economic Request for Quota Single Stage - One E for St. Mariam kindergarten i IBRD / 84830 Development and Capacity Post Open - National 12,000.00 12,653.64 Completed 2021-11-05 2021-10-27 2021-12-24 2021-12-01 2022-02-22 2022-02-02 tions nvelope n Gyumri, Marz of Shirak Building at the Local Level TIIGS-13 / Procurement of 35 Support to Socio-Economic Request for Quota Single Stage - One E 0 Plastic Garbage Containers IBRD / 84830 Development and Capacity Post Open - National 64,500.00 54,051.12 Completed 2021-12-27 2021-12-21 2022-02-14 2022-02-09 2022-04-25 2022-05-24 tions nvelope for Ijevan Community Building at the Local Level TIIG-20 / Supply and installat Support to Intercommunity S ion of solar photovoltaic stati Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 212,000.00 180,863.60 Signed 2022-03-21 2022-03-17 2022-03-26 2022-03-17 2022-04-23 2022-04-14 2022-05-23 2022-04-29 2022-07-04 2022-05-26 2022-11-01 ons in Akunk, Lermontovo, B nvelope ment Initiatives yuregavan, Kapan communiti es. TG-19 / Supply of Computer ASIF Institutional Strengthen Request for Quota Single Stage - One E IBRD / 84830 Post Open - National 20,630.00 20,100.55 Signed 2022-03-26 2022-03-28 2022-05-21 2022-04-27 2022-07-30 equipment for ATDF ing and Project Management tions nvelope TIIG-21 / Supply and installat Support to Intercommunity S Single Stage - One E ion of solar photovoltaic stati IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 66,500.00 96,420.15 Signed 2022-05-10 2022-04-29 2022-05-15 2022-04-29 2022-06-12 2022-05-27 2022-07-12 2022-06-10 2022-08-23 2022-07-01 2022-12-21 nvelope ons in Tashir community ment Initiatives TIIG-22 / Supply and installat ion of solar photovoltaic stati Support to Intercommunity S Single Stage - One E ons in Sarchapet, Akhtala co IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 190,400.00 214,508.15 Signed 2022-06-03 2022-05-30 2022-06-08 2022-05-30 2022-07-06 2022-06-27 2022-08-05 2022-07-20 2022-09-16 2022-08-28 2023-01-14 nvelope mmunities of Lori marz and Y ment Initiatives eghegis of Vayots Dzor marz of RA TIIG-23 / Procurement of Equ Support to Intercommunity S Single Stage - One E ipment for Ground Road Main IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 385,100.00 390,748.04 Signed 2022-06-26 2022-06-28 2022-06-29 2022-06-28 2022-07-27 2022-07-26 2022-08-10 2022-08-08 2022-09-12 2022-09-01 2022-12-21 nvelope tenance ment Initiatives Support to Intercommunity S TIIG-24 / Procurement of Min Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 375,000.00 215,305.13 Signed 2022-06-26 2022-06-28 2022-06-29 2022-06-28 2022-07-27 2022-07-26 2022-08-10 2022-08-08 2022-09-12 2022-09-01 2022-12-21 i-Loaders nvelope ment Initiatives TIIG-25 / Procurement of Equ Support to Intercommunity S Single Stage - One E ipment for Public Service Pro IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 553,500.00 54,133.86 Signed 2022-06-26 2022-06-29 2022-06-29 2022-06-29 2022-07-27 2022-07-27 2022-08-10 2022-08-08 2022-09-12 2022-08-25 2022-12-21 nvelope vision ment Initiatives Support to Intercommunity S TIIG-26 / Procurement of Exc Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 695,200.00 486,279.54 Signed 2022-06-26 2022-06-29 2022-06-29 2022-06-29 2022-07-27 2022-07-27 2022-08-10 2022-08-08 2022-09-12 2022-09-13 2022-12-21 avator-Loaders nvelope ment Initiatives TIIG-27 / Supply and installat ion of solar photovoltaic stati Support to Intercommunity S ons in communities Stepanav Single Stage - One E IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 200,000.00 217,625.17 Signed 2022-07-06 2022-06-30 2022-07-11 2022-06-30 2022-08-08 2022-07-28 2022-09-07 2022-08-24 2022-10-19 2022-10-03 2023-02-16 an, Metsavan of Lori marz, Gl nvelope ment Initiatives adzor of Vayots Dzor marz, a nd Tsaghkahovit of Aragatsot ni marz of RA TIIG-28 / Supply and installat ion of solar photovoltaic stati Support to Intercommunity S Single Stage - One E ons in communities of Lori Be IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 119,000.00 12,102.90 Signed 2022-08-17 2022-08-29 2022-08-17 2022-08-29 2022-08-31 2022-09-12 2022-09-14 2022-09-19 2022-09-29 2022-10-08 2022-12-28 nvelope rd, Odzun of Lori marz, and S ment Initiatives hoghakat of Gegharkunik ma rz of RA TIIG-29 / Communal Equipm Support to Intercommunity S Single Stage - One E ent for Public Service Provisio IBRD / 84830 ocial and Economic Develop Post Request for Bids Open - National 516,500.00 0.00 Signed 2022-08-15 2022-08-31 2022-08-17 2022-08-31 2022-08-31 2022-09-14 2022-09-07 2022-09-28 2022-09-23 2022-12-22 nvelope n2 ment Initiatives TG-20 / Supply of furniture f Support to Socio-Economic Request for Quota Single Stage - One E or Vanadzor N 1 and Panik ki IBRD / 84830 Development and Capacity Post Open - National 53,600.00 0.00 Signed 2022-09-16 2022-09-07 2022-10-17 2022-12-16 tions nvelope ndergartens Building at the Local Level SILD-AFG-01 / Procurement Support to Socio-Economic of Communal Equipment for Single Stage - One E IBRD / 90600 Development and Capacity Post Request for Bids Open - National 910,000.00 0.00 Canceled 2022-10-27 2022-12-28 2022-11-01 2022-12-29 2022-11-29 2023-01-31 2022-12-20 2023-01-17 2023-04-17 Ashtarak, Garni, Martuni, Sev nvelope Building at the Local Level an Communities SILD-AFG-02 / Procurement Support to Intercommunity S of 8 Dump Trucks for Abovya Single Stage - One E IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 920,000.00 0.00 Canceled 2023-01-17 2023-01-16 2023-01-22 2023-01-16 2023-02-19 2023-02-13 2023-03-12 2023-04-23 2023-08-01 n, Garni, Martuni, Metsamor, nvelope ment Initiatives Spitak and Pambak communi ties SILD-AFG-03 / Procurement Support to Intercommunity S Single Stage - One E of Garbage Trucks for Ashtar IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 937,000.00 0.00 Canceled 2023-01-29 2023-01-24 2023-02-03 2023-01-24 2023-03-03 2023-02-24 2023-03-24 2023-05-05 2023-08-13 nvelope ak and Metsamor Communiti ment Initiatives es SILD-AFG-04 / Procurement Support to Intercommunity S of Multifunctional Utility Vehi Single Stage - One E IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 930,000.00 0.00 Canceled 2023-02-06 2023-01-30 2023-02-11 2023-01-30 2023-03-11 2023-02-27 2023-04-01 2023-05-13 2023-08-21 cles for Ashtarak, Abovyan, N nvelope ment Initiatives or Hachn, Spitak, Metsamor Communities SILD-AFG-05 / Procurement Support to Intercommunity S of Garbage Containters for S Single Stage - One E Under Imple IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 471,500.00 0.00 2023-05-24 2023-05-25 2023-05-29 2023-05-25 2023-06-26 2023-06-22 2023-07-26 2023-09-06 2024-01-04 pitak, Vayk, Pambak, Vedi, Ar nvelope mentation ment Initiatives mavir and Metsamor Commu nities of RoA SILD-AFG-06 / Procurement Support to Intercommunity S of Technical Assistance Cars Single Stage - One E Under Imple IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 205,500.00 0.00 2023-05-24 2023-05-25 2023-05-29 2023-05-25 2023-06-28 2023-06-23 2023-07-28 2023-09-08 2024-01-06 for Ashtarak, Artik and Garni nvelope mentation ment Initiatives Communities of RoA Page 5 SILD-AFG-07 / Procurement Support to Intercommunity S Single Stage - One E Under Imple of Minibuses for Ashotsq, Mar IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 338,500.00 0.00 2023-05-24 2023-05-25 2023-05-29 2023-05-25 2023-06-30 2023-06-26 2023-07-30 2023-09-10 2023-12-19 nvelope mentation tuni, Nor Hachn and Vedi Co ment Initiatives mmunities of RoA SILD-AFG-08 / Procurement Support to Intercommunity S Single Stage - One E Under Imple of Graders for Armavir, Gava IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 668,000.00 0.00 2023-05-24 2023-05-25 2023-05-29 2023-05-25 2023-07-03 2023-06-27 2023-08-02 2023-09-13 2024-01-11 nvelope mentation r, Metsamor and Sevan Com ment Initiatives munities of RoA SILD-AFG-09 / Procurement Support to Intercommunity S of Excavators and a Mini-load Single Stage - One E Under Imple IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 961,500.00 0.00 2023-06-06 2023-05-30 2023-06-11 2023-05-30 2023-07-09 2023-08-08 2023-09-19 2024-01-17 er for Abovyan, Metsamor, P nvelope mentation ment Initiatives ambak, Nor Hachn, and Seva n Communities SILD-AFG-10 / Procurement of Multifunctional Excavators Support to Socio-Economic for Ashtarak, Garni, Martuni, Single Stage - One E Under Imple IBRD / 90600 Development and Capacity Post Request for Bids Open - National 953,000.00 0.00 2023-06-05 2023-06-01 2023-06-08 2023-06-01 2023-06-29 2023-06-23 2023-07-13 2023-08-24 2023-12-22 Sevan Communities, and Pro nvelope mentation Building at the Local Level curement of a Multifunctional Mini-Loader for Ashtarak Co mmunity SILD-AFG-11 / Procurement Support to Intercommunity S Single Stage - One E Under Imple of Garbage Trucks for Ashtar IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 962,000.00 0.00 2023-06-09 2023-06-01 2023-06-14 2023-06-01 2023-07-05 2023-06-22 2023-07-19 2023-08-30 2023-12-28 nvelope mentation ak and Metsamor Communiti ment Initiatives es SILD-AFG-12 / Procurement Support to Intercommunity S of Dump Trucks for Abovyan, Single Stage - One E Under Imple IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 940,000.00 0.00 2023-06-09 2023-06-01 2023-06-14 2023-06-01 2023-07-06 2023-06-26 2023-07-20 2023-08-31 2023-12-29 Garni, Martuni, Metsamor, Sp nvelope mentation ment Initiatives itak and Pambak communitie s SILD-AFG-13 / Procurement Support to Intercommunity S of Multifunctional Utility Vehi Single Stage - One E Under Imple IBRD / 90600 ocial and Economic Develop Post Request for Bids Open - National 995,000.00 0.00 2023-06-09 2023-06-01 2023-06-14 2023-06-01 2023-07-06 2023-06-27 2023-07-20 2023-08-31 2023-12-29 cles for Ashtarak, Abovyan, N nvelope mentation ment Initiatives or Hachn, Spitak, Metsamor Communities SILD-AFG-21-SH / Procureme Support to Intercommunity S Request for Quota Single Stage - One E Pending Impl nt of Semi-Trucks for Vaghar IBRD / 90600 ocial and Economic Develop Post Open - National 49,000.00 0.00 2023-06-23 2023-08-11 2023-12-09 tions nvelope ementation shapat Community ment Initiatives SILD-AFG-SOL-01 / Supply a nd installation of solar photo Support to Intercommunity S Request for Quota Single Stage - One E Pending Impl voltaic plants in the communi IBRD / 90600 ocial and Economic Develop Post Open - National 166,000.00 0.00 2023-07-03 2023-08-28 2023-12-26 tions nvelope ementation ties of Masis and Ararat, Arar ment Initiatives at Marz, RA, and Tsaghkadzo r, Kotayk Marz, RA. Support to Socio-Economic TG-04-2 / Procurement of 2 c Single Stage - One E IBRD / 84830 Development and Capacity Prior Request for Bids Open - National 0.00 33,912.43 Signed 2016-05-19 2016-05-30 ompact SUV Cars nvelope Building at the Local Level Support to Socio-Economic TG-04-1 / Procurement of 5 Single Stage - One E IBRD / 84830 Development and Capacity Prior Request for Bids Open - National 0.00 62,761.66 Signed 2016-05-21 2016-05-30 Sedan Cars- Lot 1 nvelope Building at the Local Level Support to Socio-Economic TG-03 / Procurement of IT eq Request for Quota Open - Internationa IBRD / 84830 Development and Capacity Prior 0.00 9,473.65 Signed 2015-12-28 uipment tions l Building at the Local Level Support to Socio-Economic TG-04-3 / Procurement of 1 Single Stage - One E IBRD / 84830 Development and Capacity Prior Request for Bids Open - National 0.00 61,421.28 Canceled 2016-05-19 SUV Car nvelope Building at the Local Level Support to Socio-Economic TG-02 / Procurement of furni Request for Quota Open - Internationa IBRD / 84830 Development and Capacity Prior 0.00 7,841.45 Signed 2016-05-27 ture for ATDF tions l Building at the Local Level NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SSS-01 / Procurement of hot el services in Jermuk commu ASIF Institutional Strengthen IBRD / 84830 Post Direct Selection Direct 1,200.00 1,088.35 Completed 2021-09-30 2021-09-24 2021-09-30 2021-10-01 2021-10-04 2021-10-02 2021-10-07 2021-10-08 nity for the training participa ing and Project Management nts’ accommodation CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AUD-17 / AUDIT OF THE ARM ENIAN TERRITORIAL DEVELO PMENT FUND and OF THE SO ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 10,400.00 16,723.84 Completed 2018-01-31 2018-02-06 2018-02-07 2018-02-06 2018-03-07 2018-02-26 2018-03-28 2018-03-12 2018-04-18 2018-03-12 2018-05-15 2018-06-30 CIAL INVESTMENT AND LOCA ing and Project Management cation Selection L DEVELOPMENT (SILD) PROJ ECT FOR THE YEAR ENDED D ECEMBER 31, 2017 AUD-18 / AUDIT OF THE ARM ENIAN TERRITORIAL DEVELO PMENT FUND and OF THE SO ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 6,691.00 24,294.41 Completed 2018-11-29 2018-11-23 2018-12-04 2018-12-27 2018-12-30 2018-12-24 2019-01-20 2018-12-27 2019-02-08 2018-12-28 2019-02-26 2019-06-27 CIAL INVESTMENT AND LOCA ing and Project Management cation Selection L DEVELOPMENT (SILD) PROJ ECT FOR THE YEAR ENDED D ECEMBER 31, 2018 TPD-31 / Design and Author' s Supervision for Constructio ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 10,500.00 7,842.11 Completed 2019-08-05 2019-08-07 2019-08-19 2019-08-15 2019-10-02 2019-08-30 2019-10-09 2019-09-11 2019-11-13 2019-09-11 2020-02-26 2020-05-06 n of the kindergarten after "S ing and Project Management cation Selection aint Maryam" in Gyumri TBA-01 / BENEFICIARIES ASS ESSMENT OF SOCIAL INVEST ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 50,000.00 32,629.20 Completed 2019-10-30 2019-10-30 2019-11-20 2019-12-09 2020-01-01 2019-11-26 2020-01-15 2019-12-17 2020-02-12 2019-12-18 2020-06-03 2020-07-24 MENT AND LOCAL DEVELOPM ing and Project Management cation Selection ENT PROJECT IMPACT Page 6 TCWA-01 / Assessment of CI VIL WORKS QUALITY, COST A ND MAINTENANCE of infrastr ASIF Institutional Strengthen Consultant Qualifi uctures rehabilitated in fram IBRD / 84830 Post Open - National 30,000.00 0.00 Canceled 2019-10-30 2019-10-30 2019-11-20 2019-12-09 2020-01-01 2020-01-15 2020-02-12 2020-05-06 ing and Project Management cation Selection es of the Component 1 of Social Investment and Local Development Project TS-09 / Technical Supervisio ASIF Institutional Strengthen Consultant Qualifi n of Reconstruction of the Dri IBRD / 84830 Post Open - National 5,860.00 6,622.88 Completed 2019-12-25 2019-12-23 2020-01-15 2019-12-24 2020-02-28 2020-02-05 2020-03-29 2020-02-24 2020-05-03 2020-02-25 2021-03-29 2021-06-10 ing and Project Management cation Selection nking Water Distributing Net work of Paravakar. TPD-33 / Design and Author' s Supervision for Reconstruct ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 20,870.00 14,178.31 Signed 2020-02-27 2020-03-05 2020-03-18 2020-03-11 2020-05-01 2020-04-06 2020-05-08 2020-04-20 2020-06-12 2020-04-21 2020-09-25 2020-12-25 ion of the second building of ing and Project Management cation Selection the Kindergarten N 11 in Van adzor, marz of Lori . TPD-34 / Design and Author' s Supervision for Constructio ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 12,620.00 0.00 Canceled 2020-02-27 2020-03-18 2020-05-01 2020-05-08 2020-06-12 2020-09-10 n of the potable water pipelin ing and Project Management cation Selection e of Khnatsakh, marz of Syun ik TEX-12 / Survey the technica ASIF Institutional Strengthen Consultant Qualifi l condition of the Kindergarte IBRD / 84830 Post Open - National 625.00 620.48 Completed 2020-02-27 2020-03-05 2020-03-19 2020-03-11 2020-05-02 2020-04-10 2020-06-01 2020-05-06 2020-07-06 2020-05-07 2021-01-02 2020-05-23 ing and Project Management cation Selection n N 11 in Vanadzor, marz of Lori . AUD-19 / AUDIT OF THE ARM ENIAN TERRITORIAL DEVELO PMENT FUND and AUDIT OF T ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 30,918.00 23,973.29 Completed 2020-03-10 2020-03-04 2020-03-15 2020-03-18 2020-04-19 2020-04-10 2020-05-10 2020-05-05 2020-05-29 2020-05-07 2020-09-06 2020-07-29 HE SOCIAL INVESTMENT AND ing and Project Management cation Selection LOCAL DEVELOPMENT (SILD) PROJECT FOR THE YEAR END ED DECEMBER 31, 2019 TS-10 / Technical supervisio ASIF Institutional Strengthen Consultant Qualifi n for Construction of the kind IBRD / 84830 Post Open - National 6,280.00 7,277.72 Completed 2020-04-07 2020-04-01 2020-04-28 2020-04-23 2020-06-11 2020-05-15 2020-07-11 2020-05-21 2020-08-15 2020-05-27 2021-09-09 2021-05-13 ing and Project Management cation Selection ergarten after "Saint Mariam " in Gyumri. TCWA-02 / Assessment of Ci vil Works Quality, Cost and M aintenance of Infrastructures ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 30,000.00 34,292.85 Completed 2020-05-04 2020-07-10 2020-05-25 2020-08-04 2020-07-06 2020-08-31 2020-07-20 2020-11-13 2020-08-17 2020-11-14 2020-11-09 2021-08-21 Rehabilitated in Frames of Co ing and Project Management cation Selection mponent 1 of Social Investm ent and Local Development P roject TPD-35 / Modification and sit ing of Design, Author's Super ASIF Institutional Strengthen Consultant Qualifi vision for construction of the IBRD / 84830 Post Open - National 17,775.00 16,832.17 Signed 2020-06-24 2020-06-18 2020-07-24 2020-06-22 2020-09-06 2020-07-27 2020-09-13 2020-08-07 2020-10-18 2020-08-14 2021-10-18 2021-03-21 ing and Project Management cation Selection Horom community and Gyum ri community "Zangak" kinde rgartens, marz of Shirak. TPD-36 / Design and Author' s Supervision for the Reconst ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 19,735.00 18,647.11 Signed 2020-07-10 2020-07-06 2020-08-09 2020-07-21 2020-09-22 2020-08-14 2020-09-29 2020-09-01 2020-11-03 2020-09-04 2021-10-04 2021-04-01 ruction of Panik community k ing and Project Management cation Selection indergarten, marz of Shirak. TEX-13 / Survey the technica l condition for the Reconstruc ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 735.00 699.59 Completed 2020-06-24 2020-06-18 2020-07-24 2020-06-22 2020-09-06 2020-07-27 2020-10-06 2020-08-08 2020-11-10 2020-08-11 2020-11-25 2020-09-04 tion of Panik community kind ing and Project Management cation Selection ergarten, marz of Shirak. TPD-37 / Design and author’ s supervision of Construction and repair of irrigation syste m in Byureghavan enlarged c ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 40,850.00 40,204.35 Signed 2020-08-10 2020-08-04 2020-08-31 2020-09-02 2020-10-14 2020-09-29 2020-11-13 2020-10-12 2020-12-18 2020-10-18 2021-12-18 2021-05-01 ommunity and of Constructi ing and Project Management cation Selection on and repair of gravity irriga tion system in Hoghmik, Gog hovit and Torosgyugh settle ments included in Sarapat co mmunity. TEX-14 / Expertise of Archite ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 7,720.00 6,998.00 Completed 2020-10-26 2020-10-19 2020-11-16 2020-11-04 2020-12-30 2020-11-26 2021-01-29 2020-12-11 2021-03-05 2020-12-17 2022-03-05 2022-05-04 ctural Design (8 micro-projec ing and Project Management cation Selection ts). TS-11 / Technical supervisio Support to Socio-Economic Consultant Qualifi n of "Construction of the dri IBRD / 84830 Development and Capacity Post Open - National 3,100.00 4,081.83 Signed 2021-03-11 2021-03-11 2021-03-25 2021-04-02 2021-04-22 2021-05-10 2021-05-06 2021-07-01 2021-05-25 2021-07-02 2021-05-30 cation Selection nking water pipeline in Khnat Building at the Local Level sakh" TPD-39 / Design and author’ Support to Intercommunity S Consultant Qualifi s supervision of Construction IBRD / 84830 ocial and Economic Develop Post Open - National 8,000.00 8,331.49 Signed 2021-03-12 2021-03-11 2021-03-26 2021-03-12 2021-04-23 2021-04-09 2021-05-07 2021-07-06 2021-05-17 2021-07-07 2022-03-13 2021-11-10 cation Selection of a car park in Akunk comm ment Initiatives unity TS-12 / Technical supervisio Support to Socio-Economic n of "Reconstruction of the s Consultant Qualifi IBRD / 84830 Development and Capacity Post Open - National 5,700.00 6,918.81 Signed 2021-03-24 2021-03-18 2021-04-14 2021-04-09 2021-05-12 2021-04-30 2021-05-19 2021-05-21 2021-06-07 2021-05-25 2022-05-03 econd building of kindergarte cation Selection Building at the Local Level n No. 11 in Vanadzor" AUD-20 / "AUDIT OF THE AR MENIAN TERRITORIAL DEVEL OPMENT FUND and AUDIT OF ASIF Institutional Strengthen Consultant Qualifi IBRD / 84830 Post Open - National 42,000.00 58,612.64 Completed 2021-03-29 2021-03-22 2021-04-12 2021-04-01 2021-05-10 2021-04-30 2021-05-15 2021-05-14 2021-05-25 2021-05-15 2021-07-09 2021-08-05 THE SOCIAL INVESTMENT AN ing and Project Management cation Selection D LOCAL DEVELOPMENT (SIL D) PROJECT FOR THE YEAR E NDED DECEMBER 31, 2020" TS-13 / Technical Supervisio n of 3 projects: "Constructio Support to Socio-Economic n of kindergarten of Horom", Consultant Qualifi IBRD / 84830 Development and Capacity Post Open - National 18,000.00 18,459.55 Signed 2021-05-13 2021-05-07 2021-06-03 2021-05-24 2021-07-01 2021-06-15 2021-07-08 2021-07-01 2021-07-27 2021-07-05 2022-07-22 ""Zangak" kindergarten cons cation Selection Building at the Local Level truction of Gyumri", "Reconst ruction of the kindergarten of Panik" TS-14 / Technical supervisio n of "Construction and repair Support to Intercommunity S Consultant Qualifi of a gravity irrigation system IBRD / 84830 ocial and Economic Develop Post Open - National 4,400.00 0.00 Canceled 2021-05-13 2021-05-07 2021-06-03 2021-07-01 2021-07-08 2021-07-27 2022-02-22 cation Selection in Hoghmik, Goghovit, and T ment Initiatives orosgyugh settlements of Sar apat community" TS-15 / Technical supervisio n of "W-29, Construction and repair of a gravity irrigation s Support to Intercommunity S ystem in Hoghmik, Goghovit, Consultant Qualifi IBRD / 84830 ocial and Economic Develop Post Open - National 12,100.00 12,243.75 Signed 2021-07-05 2021-06-21 2021-07-26 2021-07-08 2021-08-23 2021-08-06 2021-08-30 2021-08-31 2021-09-18 2021-09-01 2022-07-15 and Torosgyugh settlements cation Selection ment Initiatives of Sarapat community, W-27 , Construction and repair of ir rigation system in Byureghav an enlarged community" Page 7 AFT-TS-01 / Technical super vision of three projects: Cons truction of the pumping stati Support to Socio-Economic on and drinking water supply Consultant Qualifi IBRD / 90600 Development and Capacity Post Open - National 13,100.00 13,370.34 Signed 2021-07-05 2021-06-21 2021-07-26 2021-07-16 2021-08-23 2021-08-20 2021-08-30 2021-09-02 2021-09-18 2021-09-03 2022-08-14 pipeline, major renovation of cation Selection Building at the Local Level the DRRs and reconstruction of the distribution network of Archis, Lchkadzor and Movse s of Tavush region TPD-40 / Design and author’ Support to Intercommunity S s supervision of Construction Consultant Qualifi IBRD / 84830 ocial and Economic Develop Post Open - National 7,600.00 7,250.51 Signed 2021-07-16 2021-06-21 2021-08-06 2021-07-14 2021-09-19 2021-07-29 2021-10-19 2021-08-13 2021-11-23 2021-08-22 2022-11-18 2021-11-15 of the parking area in Gegha cation Selection ment Initiatives masar community AFT-PD-01 / Designing and a uthor’s supervision of the Re Support to Socio-Economic Consultant Qualifi construction of the communit IBRD / 90600 Development and Capacity Post Open - National 7,680.00 0.00 Canceled 2021-08-13 2021-08-12 2021-08-20 2021-10-03 2021-11-02 2021-11-12 2022-09-23 cation Selection y center by constructing the Building at the Local Level second floor in Lori-Berd, ma rz of Lori. AFT-PD-04 / Design and auth or’s supervision of the Constr Support to Socio-Economic Consultant Qualifi uction of external water pipel IBRD / 90600 Development and Capacity Post Open - National 24,700.00 23,952.12 Signed 2021-09-07 2021-09-02 2021-09-21 2021-09-09 2021-11-04 2021-10-05 2021-12-04 2021-10-12 2022-01-08 2021-10-14 2023-07-02 cation Selection ine and capping in the comm Building at the Local Level unity of Getahovit of Tavush region. TPD-41 / Design and author’ s supervision of reconstructio Support to Intercommunity S Consultant Qualifi n of the irrigation system in c IBRD / 84830 ocial and Economic Develop Post Open - National 18,980.00 17,116.62 Signed 2021-09-09 2021-09-28 2021-09-30 2021-09-28 2021-11-13 2021-10-22 2021-12-13 2021-10-29 2022-01-17 2021-11-03 2022-12-23 cation Selection onsolidated community in A ment Initiatives masia, marz of Shirak. AFT-PD-05 / Design and auth Support to Socio-Economic or’s supervision of the Constr Consultant Qualifi IBRD / 90600 Development and Capacity Post Open - National 28,000.00 24,163.66 Signed 2021-10-22 2021-09-30 2021-11-12 2021-10-01 2021-12-10 2021-10-22 2021-12-24 2021-11-10 2022-01-03 2021-11-16 2023-08-16 uction of the Alagyaz Commu cation Selection Building at the Local Level nity Center of region Aragats otn AFT-PD-01/1 / Designing and author’s supervision of the R Support to Socio-Economic Consultant Qualifi econstruction of the commun IBRD / 90600 Development and Capacity Post Open - National 10,960.00 10,607.96 Signed 2021-11-15 2021-11-09 2021-12-06 2021-12-01 2022-01-03 2021-12-30 2022-01-17 2022-01-19 2022-01-27 2022-01-27 2022-12-23 cation Selection ity center by constructing the Building at the Local Level second floor in Lori-Berd, ma rz of Lori. AFT-EX-01 / Reviewing and E valuation of the technical st Support to Socio-Economic ate of the Building of reconst Consultant Qualifi IBRD / 90600 Development and Capacity Post Open - National 1,330.00 1,265.20 Signed 2021-12-10 2021-12-30 2021-12-31 2022-01-27 2022-02-06 2022-02-25 2022-02-27 2022-03-16 2022-03-13 2022-03-17 2022-04-02 ruction of the kindergarten in cation Selection Building at the Local Level Ushi and renovation of the ki ndergarten in Khashtarak, m arz of Aragatsotn. AFT-PD-06 / Design and auth or’s supervision of the Recon Support to Socio-Economic Consultant Qualifi struction of the kindergarten IBRD / 90600 Development and Capacity Post Open - National 42,060.00 40,717.20 Signed 2021-12-14 2021-12-21 2021-12-28 2021-12-28 2022-02-10 2022-02-02 2022-03-03 2022-03-01 2022-03-13 2022-03-02 2023-08-05 cation Selection in Ushi and Renovation of the Building at the Local Level kindergarten in Khashtarak, marz of Aragatsotn. AFT-PD-07 / Design and auth Support to Socio-Economic or’s supervision of the Constr Consultant Qualifi IBRD / 90600 Development and Capacity Post Open - National 36,700.00 38,654.85 Signed 2022-02-22 2022-02-24 2022-02-23 2022-02-28 2022-04-08 2022-03-28 2022-05-08 2022-04-21 2022-06-05 2022-04-22 2022-11-17 uction of the kindergarten in cation Selection Building at the Local Level Nor Kyanq, marz of Shirak. AFT-EX-02 / Expertise of Arc Support to Socio-Economic Consultant Qualifi hitectural Design (10 project IBRD / 90600 Development and Capacity Post Open - National 16,090.00 16,499.77 Signed 2022-02-23 2022-03-10 2022-03-16 2022-03-25 2022-04-22 2022-04-28 2022-05-13 2022-05-12 2022-05-27 2022-05-13 2023-05-27 cation Selection s). Building at the Local Level TS-16 / "Construction of park Support to Intercommunity S ing lots in the enlarged com Consultant Qualifi IBRD / 84830 ocial and Economic Develop Post Open - National 5,800.00 0.00 Canceled 2022-04-11 2022-05-02 2022-05-30 2022-06-06 2022-06-25 2022-11-22 munities of Akunk, Kotayk m cation Selection ment Initiatives arz and Geghamasar, Geghar kunik marz of RA" AFT-PD-08 / Design and auth Support to Socio-Economic or’s supervision of the Constr Consultant Qualifi IBRD / 90600 Development and Capacity Post Open - National 4,930.00 0.00 Canceled 2022-05-03 2022-04-27 2022-05-17 2022-05-27 2022-06-23 2022-07-23 2022-08-13 2022-10-27 uction of the sports area of t cation Selection Building at the Local Level he school in Myasnikyan Villa ge, marz of Armavir. AFT-TS-02 / Technical super vision of "Renovation of the wrestling hall located in the Support to Socio-Economic Consultant Qualifi Culture House of Akunq com IBRD / 90600 Development and Capacity Post 5,000.00 0.00 Canceled 2022-05-03 2022-05-17 2022-06-14 2022-07-05 2022-07-26 2023-01-22 cation Selection mnunity, Gegharkunik marz Building at the Local Level of RoA", and "Construction of parking lots in Akunk, Kotayk marz of RoA". AFT-TS-02-1 / Technical sup ervision of "Renovation of th e wrestling hall located in the Support to Socio-Economic Culture House of Akunq com Consultant Qualifi IBRD / 84830 Development and Capacity Post Open - National 8,220.00 8,343.28 Signed 2022-06-21 2022-06-28 2022-07-05 2022-07-26 2022-08-11 2022-09-01 2022-09-01 2022-09-14 2022-09-15 2022-09-23 2023-03-14 munity", "Construction of a p cation Selection Building at the Local Level arking lot in Geghamasar co mmunity, Gegharkunik marz of RoA", "Construction of par king lots in Akunk, Kotayk m arz of RoA". AFT-PD-09 / Design and auth or’s supervision of the Constr uction of the kindergarden in Support to Socio-Economic Consultant Qualifi Under Implement Aknashen Village Araqs Com IBRD / 90600 Development and Capacity Post Open - National 34,500.00 0.00 2022-08-01 2022-09-05 2022-08-15 2022-09-12 2022-09-21 2022-10-13 2022-10-21 2022-11-17 2022-11-04 2023-04-03 cation Selection ation munity, marz of Aragacotn a Building at the Local Level nd of the Construction of the sports area of the school in M yasnikyan Village, marz of Ar mavir. AFT-PD-10 / Design and Auto Support to Socio-Economic r's supervision of Constructio Consultant Qualifi IBRD / 90600 Development and Capacity Post Open - National 45,500.00 0.00 Signed 2022-10-26 2022-10-25 2022-11-09 2022-11-15 2022-12-16 2022-12-20 2023-01-06 2023-05-18 2023-01-20 2024-03-15 n of the new physical educati cation Selection Building at the Local Level on school in Paraqar commu nity, marz of Armavir. AFT-TS-03 / Technical super Support to Socio-Economic Consultant Qualifi Under Implement vision of the civil works (3 pr IBRD / 84830 Development and Capacity Post Open - National 18,900.00 0.00 2022-10-26 2022-10-25 2022-11-09 2022-12-02 2022-12-16 2022-12-23 2023-01-06 2023-01-20 2024-03-15 cation Selection ation ojects). Building at the Local Level AFT-TS-04 / Technical super vision of the Reconstruction Support to Socio-Economic Consultant Qualifi Under Implement of the irrigation system in th IBRD / 84830 Development and Capacity Post Open - National 9,200.00 0.00 2022-10-26 2022-10-25 2022-11-09 2023-01-20 2022-12-16 2023-03-20 2023-01-06 2023-04-27 2023-01-20 2023-11-16 cation Selection ation e enlarged rural community Building at the Local Level of Amasia, Shirak Marz, RA. Page 8 AFT-TS-05 / Technical super vision of the Construction of Support to Socio-Economic Consultant Qualifi Under Implement external water line and sprin IBRD / 84830 Development and Capacity Post Open - National 10,600.00 0.00 2022-10-26 2022-10-25 2022-11-09 2022-11-01 2022-12-16 2023-01-30 2023-01-06 2023-03-06 2023-01-20 2024-05-14 cation Selection ation g connections of Getahovit c Building at the Local Level ommunity" of Tavush Region, RA. AFT-TS-06 / Technical super vision of the Construction of Support to Socio-Economic Consultant Qualifi Under Implement a Sewerage System and Bio-t IBRD / 84830 Development and Capacity Post Open - National 10,250.00 0.00 2023-02-08 2023-04-27 2023-02-22 2023-05-10 2023-03-31 2023-05-31 2023-04-21 2023-06-22 2023-05-05 2024-01-30 cation Selection ation reatment Facility in Nor Avan Building at the Local Level District of Yeghegnadzor City . AUD-22 / AUDIT OF THE SILD PROJECT FOR THE YEAR ENDI NG DECEMBER 31, 2022 (ALS O COVERING THE GRACE PER ASIF Institutional Strengthen Consultant Qualifi Under Implement IBRD / 84830 Post Open - National 20,000.00 0.00 2023-03-16 2023-03-16 2023-03-23 2023-03-22 2023-04-13 2023-04-10 2023-04-18 2023-04-28 2023-04-28 2023-12-24 IOD) and AUDIT OF THE ADDI ing and Project Management cation Selection ation TIONAL FINANCING FOR THE SILD PROJECT FOR THE PERI OD FROM DECEMBER 8, 2020 TO DECEMBER 31, 2022. AFT-TS-07 / Technical super Support to Socio-Economic vision of the Construction of t Consultant Qualifi Under Implement IBRD / 84830 Development and Capacity Post Open - National 2,500.00 0.00 2023-06-07 2023-06-09 2023-06-14 2023-06-12 2023-07-12 2023-08-02 2023-08-16 2023-12-14 he Sports Ground of the Mya cation Selection ation Building at the Local Level snikyan Settlement School of Armavir Marz of RoA. AFT-TS-08 / Technical super Support to Socio-Economic vision of the renovation of th Consultant Qualifi Under Implement IBRD / 84830 Development and Capacity Post Open - National 8,200.00 0.00 2023-06-12 2023-06-12 2023-06-26 2023-06-20 2023-08-02 2023-08-23 2023-09-06 2024-06-02 e kindergarten in Khashtarak cation Selection ation Building at the Local Level settlement of Tavush marz of RoA. TPD -01 / Architectural Desig Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 51,254.80 Signed 2015-06-30 2015-06-30 cation Selection l tion, Renovation & Reconstru Building at the Local Level ction of Buildings TPD-05-1 / Author Supervisio Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 4,848.52 Signed 2015-07-30 2015-07-31 cation Selection l tion, Renovation& Reconstru Building at the Local Level ction of Buildings TEX-02 / Expertise of Archite Support to Socio-Economic Consultant Qualifi Open - Internationa ctural Design (12 micro-proje IBRD / 84830 Development and Capacity Prior 0.00 17,902.25 Signed 2015-07-08 2015-07-08 cation Selection l cts) Building at the Local Level TBD-04 / Architectural Desig Support to Socio-Economic n for Construction, Rehabilita Consultant Qualifi Open - Internationa IBRD / 84830 Development and Capacity Prior 0.00 31,145.69 Signed 2015-06-30 2015-06-30 tion, Renovation & Reconstru cation Selection l Building at the Local Level ction of Buildings (two micro- projects) TPD-02 / Architectural Desig Support to Socio-Economic n for Construction, Rehabilita Consultant Qualifi Open - Internationa IBRD / 84830 Development and Capacity Prior 0.00 18,929.73 Signed 2015-06-30 2015-06-30 tion, Renovation & Reconstru cation Selection l Building at the Local Level ction of Buildings (two micro- projects) TEX-01 / Expertise of buildin Support to Socio-Economic gs stability, ventilation, powe Consultant Qualifi Open - Internationa IBRD / 84830 Development and Capacity Prior 0.00 12,145.80 Signed 2015-06-30 2015-06-30 r and water supplies and drai cation Selection l Building at the Local Level nage systems (8 mictro-proje cts) TPD-03 / Architectural Desig Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 45,112.36 Signed 2015-06-30 2015-06-30 cation Selection l tion, Renovation & Reconstru Building at the Local Level ction of Buildings TPD-06-1 / Author Supervisio Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 3,877.33 Signed 2015-07-30 2015-07-31 cation Selection l tion, Renovation& Reconstru Building at the Local Level ction of Buildings TPD-02-1 / Author Supervisio Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 2,665.23 Signed 2015-07-30 2015-07-31 cation Selection l tion, Renovation& Reconstru Building at the Local Level ction of Buildings TPD-03-1 / Author Supervisio Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 4,623.95 Signed 2015-07-30 2015-07-31 cation Selection l tion, Renovation& Reconstru Building at the Local Level ction of Buildings TPD-04-1 / Author Supervisio Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 5,012.55 Canceled 2015-08-17 cation Selection l tion, Renovation& Reconstru Building at the Local Level ction of Buildings TPD 06 / Architectural Desig Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 27,397.79 Signed 2015-06-30 2015-06-30 cation Selection l tion, Renovation & Reconstru Building at the Local Level ction of Buildings TPD-05 / Architectural Desig Support to Socio-Economic n for Construction, Rehabilita Consultant Qualifi Open - Internationa IBRD / 84830 Development and Capacity Prior 0.00 36,498.39 Signed 2015-06-30 2015-06-30 tion, Renovation & Reconstru cation Selection l Building at the Local Level ction of Buildings (two micro- projects) TPD-01-1 / Author Supervisio Support to Socio-Economic Consultant Qualifi Open - Internationa n for Construction, Rehabilita IBRD / 84830 Development and Capacity Prior 0.00 6,892.20 Signed 2015-07-30 2015-07-31 cation Selection l tion, Renovation& Reconstru Building at the Local Level ction of Buildings INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TPD-32 / Authors supervision for Renovation of the Kinderg ASIF Institutional Strengthen arden Area in Village Aghdzq IBRD / 84830 Post Direct Selection Direct 240.00 0.00 Canceled 2018-04-26 2018-04-20 2018-05-06 2018-04-20 2018-06-03 2018-08-07 ing and Project Management and Construction of the Exter nal Engineering Nets, Marz of Aragatsotn TIIC-01 / Selection of Estimat Support to Intercommunity S Individual Consult or for providing consulting se IBRD / 84830 ocial and Economic Develop Post Open 10,740.00 0.00 Canceled 2018-10-30 2018-10-23 2018-12-02 2018-12-09 2018-12-30 2020-08-21 ant Selection rvices ment Initiatives TPD-38/1 / Author's supervisi Support to Socio-Economic on of Construction of drinkin IBRD / 84830 Development and Capacity Post Direct Selection Direct 1,000.00 1,054.75 Signed 2021-02-17 2021-02-15 2021-02-27 2021-03-24 2021-03-10 2021-05-08 2021-10-06 g water pipeline for Khnatsak Building at the Local Level h Page 9 AFT-PD-02 / Author’s supervi sion of the Construction of th e pumping station and drinki Support to Socio-Economic ng water supply pipeline, re IBRD / 90600 Development and Capacity Post Direct Selection Direct 2,340.00 0.00 Canceled 2021-08-26 2021-08-26 2021-09-05 2021-10-19 2022-07-16 novation of the DRRs and rec Building at the Local Level onstruction of the distributio n network of Lchkadzor and Movses of Tavush region. AFT-PD-03 / Author’s supervi sion of the Construction of th e pumping station and drinki Support to Socio-Economic ng water supply pipeline, maj IBRD / 90600 Development and Capacity Post Direct Selection Direct 2,290.00 0.00 Canceled 2021-08-26 2021-08-26 2021-09-05 2021-10-19 2022-09-14 or renovation of the DRRs an Building at the Local Level d reconstruction of the distri bution network of Archis settl ement of Tavush Marz. AFT-PD-02/1 / Author’s super vision of the Construction of t he pumping station and drink Support to Socio-Economic ing water supply pipeline, re IBRD / 90600 Development and Capacity Post Direct Selection Direct 3,090.00 0.00 Canceled 2021-09-09 2021-09-02 2021-09-19 2021-09-03 2021-11-02 2022-09-28 novation of the DRRs and rec Building at the Local Level onstruction of the distributio n network of Archis and Movs es settlements of Tavush regi on. AFT-PD-03/1 / Author’s super vision of the Construction of t he pumping station and drink Support to Socio-Economic ing water supply pipeline, re IBRD / 90600 Development and Capacity Post Direct Selection Direct 1,510.00 1,543.46 Signed 2021-09-09 2021-09-02 2021-09-19 2021-09-03 2021-11-02 2021-10-22 2022-07-30 novation of the DRRs and rec Building at the Local Level onstruction of the distributio n network of Lchkadzor settle ment of Tavush region. Support to Intercommunity S AFT-IC-01 / Individual Consul Individual Consult Under Implement IBRD / 90600 ocial and Economic Develop Post Open - National 18,900.00 0.00 2022-10-06 2022-10-07 2022-11-08 2022-10-21 2022-11-15 2022-10-24 2022-12-06 2023-12-06 tant /Power Engineer ant Selection ation ment Initiatives AFT-PD-11/1 / Authors super vision of the Construction of Support to Socio-Economic Under Implement a Sewerage System and Bio-t IBRD / 84830 Development and Capacity Post Direct Selection Direct - National 4,100.00 0.00 2023-05-09 2023-05-15 2023-05-19 2023-05-18 2023-06-28 2024-03-24 ation reatment Facility in Nor Avan Building at the Local Level District of Yeghegnadzor City . AFT-PD-12/1 / Authors super vision of the "Renovation of t Support to Socio-Economic Under Implement he wrestling hall located in th IBRD / 84830 Development and Capacity Post Direct Selection Direct - National 500.00 0.00 2023-05-22 2023-05-17 2023-06-01 2023-05-18 2023-07-11 2023-11-08 ation e Culture House of Akunq co Building at the Local Level mmunity", Gegharkunik marz of RoA. Page 10 PROCUREMENT Turkiye : Sustainable Cities Project 2 PLAN General Information Country: Turkiye 2018-03-29 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161915 GPN Date: 2018-03-14 Project Name: Sustainable Cities Project 2 Loan / Credit No: / , IBRD / 88430, IBRD / 89740 Ilbank PMU Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ASAT3 W7 / Construction of Component A: Municipal Inv Single Stage - One E 2022-11-1 / Post Request for Bids Open - National 0.00 Canceled 2021-01-06 2021-01-11 2021-02-22 2021-04-05 2021-05-10 Manavgat Deep Sea Outfall estments nvelope 1 ASAT3-W1 / Lot1-Constructio n of Collector and Wastewat er Network in Döşemealtı Di Component A: Municipal Inv Single Stage - One E 5,920,826.0 2021-04-0 IBRD / 88430 Prior Request for Bids Open - National Signed 2018-11-30 2019-01-07 2018-12-05 2019-01-16 2019-01-16 2019-03-27 2019-02-27 2019-09-16 2019-04-03 2019-10-25 strict, estments nvelope 6 2 Lot2-Construction of Collect or and Wastewater Network in Aksu and Kundu District ASAT3 W1 / Construction of Component A: Municipal Inv Single Stage - One E 2020-04-2 Collector and Wastewater N IBRD / 88430 Prior Request for Bids Open - National 0.00 Canceled 2018-04-06 2018-11-15 2018-04-11 2018-05-23 2018-07-25 2018-08-29 estments nvelope 0 etwork in Döşemealtı District ASAT3 W4 / Construction of Component A: Municipal Inv Single Stage - One E 2021-11-0 Wastewater Network in Man / Post Request for Bids Open - National 0.00 Canceled 2018-12-27 2019-01-02 2019-02-13 2019-04-03 2019-05-08 estments nvelope 8 avgat District MUS2 W2 / Construction of S Component A: Municipal Inv Single Stage - One E Under Imple 2022-02-2 IBRD / 88430 Post Request for Bids Open - National 0.00 2019-10-14 2022-02-10 2019-10-21 2019-12-02 2022-04-20 2020-01-20 2022-06-28 2020-02-24 ewerage Network in Ören - M estments nvelope mentation 3 ilas District ASAT3/W4 / Construction of Wastewater Network in Man Component A: Municipal Inv Single Stage - One E 5,353,634.1 2022-04-1 IBRD / 88430 Post Request for Bids Open - National Signed 2019-12-16 2020-10-25 2020-01-02 2020-02-13 2020-11-18 2020-03-14 2020-12-18 2020-04-18 2021-02-20 avgat District (Procurement estments nvelope 0 8 Plan Item No ASAT3 W4) ASAT3/W8 / Kovanlık Water Component A: Municipal Inv Single Stage - One E Under Imple 2022-01-3 IBRD / 88430 Post Request for Bids Open - National 0.00 2019-10-21 2021-11-11 2019-10-26 2019-12-07 2022-01-27 2020-01-06 2022-06-15 2020-02-10 Supply Project (ASAT3/W8) estments nvelope mentation 0 ASAT3-W9 / Construction of Component A: Municipal Inv Single Stage - One E 3,628,244.9 2022-09-0 IBRD / 88430 Post Request for Bids Open - National Signed 2020-12-28 2021-03-01 2021-01-26 2021-03-09 2021-04-27 2021-04-08 2021-06-29 2021-05-13 2021-10-29 Wastewater Network in Finik estments nvelope 1 5 e District ASAT3 W5 / Transmission of Water From Manavgat Water Component A: Municipal Inv Single Stage - One E 2022-11-0 Treatment Plant to Manavgat IBRD / 88430 Post Request for Bids Open - National 0.00 Canceled 2019-06-26 2019-07-01 2019-08-12 2019-09-23 2019-10-28 estments nvelope 1 Left Coasts via transmission lines, water supply for the re sidential areas ASAT3 W6 / Transmission of Water From Manavgat Water Component A: Municipal Inv Single Stage - One E 2023-10-2 Treatment Plant to Manavgat IBRD / 88430 Prior Request for Bids Open - National 0.00 Canceled 2020-05-06 2020-05-11 2020-06-22 2020-08-17 2020-09-21 estments nvelope 6 Right Coasts via transmissio n lines and water supply for t he residental areas MUS2 W4 / Construction of Component A: Municipal Inv Single Stage - One E Under Imple 2023-07-2 IBRD / 88430 Post Request for Bids Open - National 0.00 2021-03-03 2022-03-22 2021-03-10 2021-04-21 2022-05-24 2021-06-16 2021-07-21 WWTP in Ören - Milas District estments nvelope mentation 1 ASAT3-W3 / Construction of Component A: Municipal Inv Single Stage - One E 6,416,947.0 2021-05-1 IBRD / 88430 Post Request for Bids Open - National Signed 2019-01-11 2020-02-27 2019-01-16 2019-02-27 2020-06-09 2019-04-10 2020-07-21 2019-05-15 2020-08-29 Wastewater Network in Kepe estments nvelope 3 4 z District Request for B KOZAKLI-ENR-W1 / Construc ids - Small W tion Works for Rehabilitation Component A: Municipal Inv Single Stage - One E Under Imple 2022-12-0 IBRD / 89740 Post Request for Bids Open - National orks SPD (1 e 0.00 2022-01-06 2022-04-04 2022-01-11 2022-02-08 2022-05-16 2022-03-08 2022-04-05 /Extension of Kozaklı-Geother estments nvelope mentation 1 nvelope proc mal Energy Heating System ess) Network Request for B NİKSAR-W1 / Construction of ids - Small W Component A: Municipal Inv Single Stage - One E Under Imple 2025-06-3 Tokat-Niksar Centrum Drinki IBRD / 89740 Post Request for Bids Open - National orks SPD (1 e 0.00 2022-12-16 2023-01-09 2022-12-21 2023-02-01 2023-04-10 2023-03-03 2023-05-23 2023-04-07 estments nvelope mentation 0 ng Water Network Project nvelope proc ess) Request for B KOSKİ-W1 / Construction of ids - Small W Konya - Derebucak & Doğanh Component A: Municipal Inv Single Stage - One E Pending Imp 2024-08-1 IBRD / 89740 Post Request for Bids Open - National orks SPD (1 e 0.00 2023-02-26 2023-03-03 2023-04-14 2023-05-14 2023-06-18 isar & Taşkent Wastewater Tr estments nvelope lementation 1 nvelope proc eatment Plant (WWTP) ess) KOSKİ-W2 / Construction of Request for B Konya -Karapınar Water Supp ids - Small W Component A: Municipal Inv Single Stage - One E Pending Imp 2024-10-0 ly Transmission Lines (Lot 1), IBRD / 89740 Prior Request for Bids Open - National orks SPD (1 e 0.00 2023-04-26 2023-05-01 2023-06-12 2023-07-12 2023-08-16 estments nvelope lementation 9 Construction of Konya Suğla nvelope proc Water Supply Transmission Li ess) ne (Lot 2) Request for B NIGDE-W1 / Construction of ids - Small W Component A: Municipal Inv Single Stage - One E Pending Imp 2026-05-2 Niğde Stormwater and Sewer IBRD / 89740 Post Request for Bids Open - National orks SPD (1 e 0.00 2024-01-03 2024-01-10 2024-02-07 2024-03-13 2024-04-03 estments nvelope lementation 3 age Network nvelope proc ess) Request for B ASKI-W1 / ASKI-W1 Construc ids - Works ( tion of IVEDIK Drinking Water Component A: Municipal Inv Open - Internationa Single Stage - One E Pending Imp 2027-01-3 IBRD / 89740 Prior Request for Bids without preq 0.00 2023-10-02 2023-10-07 2023-11-18 2023-12-18 2024-01-22 Treatment Plant - 4th Unit (c estments l nvelope lementation 1 ualification) apacity increase) Project SPD Request for B BASKİ-W1 / Construction of ids - Small W Ayvalık Sarımsaklı Wastewat Component A: Municipal Inv Single Stage - One E Pending Imp 2026-02-2 IBRD / 89740 Post Request for Bids Open - National orks SPD (1 e 0.00 2023-11-15 2023-11-20 2024-01-01 2024-01-31 2024-03-06 er Pump Station Displacemen estments nvelope lementation 4 nvelope proc t and Renewal of the Collect ess) or Lines Project KONYAAF -TRANSPORT-W1 / Request for B Construction of -Tram Line C ids - Works ( onstruction for Barış Caddesi- Component A: Municipal Inv Open - Internationa Single Stage - One E Pending Imp 2026-03-0 IBRD / 89740 Prior Request for Bids without preq 0.00 2023-09-26 2023-10-01 2023-11-12 2023-12-12 2023-12-29 Street (LINE-III), Tram Line Ex estments l nvelope lementation 8 ualification) tension between City Court a SPD nd City Hospital (Adliye – Şeh ir Hastanesi) Page 1 Request for B KONYAAF -TRANSPORT-W2 / Component A: Municipal Inv Single Stage - One E ids - Small W Pending Imp 2026-01-3 Construction of Traffic Contro IBRD / 89740 Post Request for Bids Open - National 0.00 2023-09-26 2023-10-01 2023-10-31 2023-11-30 2023-12-17 estments nvelope orks SPD (1 e lementation 1 l Center nvelope proc ess) Request for B MERZIFON-W1 / Constructio Component A: Municipal Inv Single Stage - One E ids - Small W Pending Imp 2026-05-2 n of Merzifon (Amasya) Drink IBRD / 89740 Post Request for Bids Open - National 0.00 2024-01-02 2024-01-09 2024-02-06 2024-03-12 2024-04-02 estments nvelope orks SPD (1 e lementation 2 ing Water nvelope proc ess) Request for B MASKİ-W1 / Construction of ids - Small W Muradiye Drinking Water Net Component A: Municipal Inv Single Stage - One E Pending Imp 2026-01-2 IBRD / 89740 Post Request for Bids Open - National orks SPD (1 e 0.00 2023-10-15 2023-10-20 2023-12-01 2023-12-31 2024-02-04 work Project, Drinking Water estments nvelope lementation 4 nvelope proc Transmission Line Project ess) Request for B MASKİ-W2 / Construction of ids - Small W Component A: Municipal Inv Single Stage - One E Pending Imp 2026-02-2 Muradiye Sewerage and Stor IBRD / 89740 Prior Request for Bids Open - National orks SPD (1 e 0.00 2023-11-15 2023-11-20 2024-01-01 2024-01-31 2024-03-06 estments nvelope lementation 4 mwater Network Project nvelope proc ess) Request for B MASKİ-W3 / Construction of Component A: Municipal Inv Single Stage - One E ids - Small W Pending Imp 2026-04-2 IBRD / 89740 Post Request for Bids Open - National 0.00 2024-01-15 2024-01-20 2024-03-02 2024-04-01 2024-05-06 Muradiye WWTP Project estments nvelope orks SPD (1 e lementation 6 nvelope proc ess) Request for B MASKİ-W4 / Construction of ids - Small W Component A: Municipal Inv Single Stage - One E Pending Imp 2026-05-3 Gördes Central Drinking Wat IBRD / 89740 Post Request for Bids Open - National orks SPD (1 e 0.00 2024-02-19 2024-02-24 2024-04-06 2024-05-06 2024-06-10 estments nvelope lementation 1 er Reservoir and Transmissio nvelope proc n Line Project ess) MASKİ-W5 / Construction of Request for B Gelenbe Drinking Water Net ids - Small W Component A: Municipal Inv Single Stage - One E Pending Imp 2026-06-2 work Project, Drinking Water IBRD / 89740 Post Request for Bids Open - National orks SPD (1 e 0.00 2024-03-18 2024-03-23 2024-05-04 2024-06-03 2024-07-08 estments nvelope lementation 8 Transmission Line Project an nvelope proc d Gelenbe Sewerage Networ ess) k Project Request for B KEMERHİSAR-W1 / Construct ids - Small W Component A: Municipal Inv Single Stage - One E Pending Imp 2026-07-2 ion of Kemerhisar Drinking W IBRD / 89740 Post Request for Bids Open - National orks SPD (1 e 0.00 2024-03-04 2024-04-01 2024-05-06 2024-06-17 2024-08-05 estments nvelope lementation 6 ater Network Project nvelope proc ess) Request for B ASAT3-W10 / Construction of ids - Small W Component A: Municipal Inv Single Stage - One E Pending Imp 2026-03-0 Wastewater Network in Dose IBRD / 88430 Post Request for Bids Open - National orks SPD (1 e 0.00 2023-05-19 2023-05-26 2023-06-23 2023-08-02 2023-09-09 estments nvelope lementation 2 mealti Region nvelope proc ess) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ASAT3 G7 / Procurement of Component A: Municipal Inv Single Stage - One E / Post Request for Bids Open - National 0.00 Canceled 2022-06-16 2022-06-21 2022-08-02 2022-09-13 2022-10-18 2023-10-13 170.000 Nos of Water Meters estments nvelope ASAT3-G2 / Procurement of Component A: Municipal Inv Open - Internationa Single Stage - One E IBRD / 88430 Prior Request for Bids 0.00 Canceled 2018-12-21 2019-04-04 2018-12-26 2019-02-06 2019-03-20 2019-04-24 2020-04-23 200.000 Nos of Water Meters estments l nvelope ASAT3 G1 / Procurement of Component A: Municipal Inv Single Stage - One E IBRD / 88430 Post Request for Bids Open - National 297,919.30 Signed 2018-12-07 2019-01-04 2018-12-12 2019-01-23 2019-02-13 2019-03-06 2019-05-25 2019-04-10 2019-06-21 2019-07-09 4 Nos of Watering Truck estments nvelope ASAT3 G4 / Lot 1- Procurem ent of CCTV Channel Monitori Component A: Municipal Inv Single Stage - One E IBRD / 88430 Post Request for Bids Open - National 1,592,139.78 Signed 2019-09-30 2021-03-04 2019-10-05 2019-11-16 2021-06-01 2019-12-28 2021-07-27 2020-02-01 2021-09-17 2020-08-09 ng Vehicle, Lot 2- Procureme estments nvelope nt of 2 Nos of Water Leakage Detection Vehicle ASAT3 G6 / Procurement of Component A: Municipal Inv Open - Internationa Single Stage - One E IBRD / 88430 Prior Request for Bids 0.00 Canceled 2021-01-11 2021-01-16 2021-03-01 2021-04-12 2021-05-17 2022-05-17 400.000 Nos of Water Meters estments l nvelope ASAT3 G3 / Lot 1- Procurem ent of 2 Nos of Combined Ca Component A: Municipal Inv Single Stage - One E nal Cleaning Vehicle, Lot 2- P IBRD / 88430 Post Request for Bids Open - National 932,581.64 Signed 2018-05-16 2019-08-09 2018-05-21 2018-07-02 2019-10-01 2018-08-13 2019-11-06 2018-09-17 2019-12-26 2019-03-26 estments nvelope rocurement of 5 Nos of Kuka Type Canal Cleaning Vehicle ASAT3/G8 / Procurement of Office Equipments for the Ne Component A: Municipal Inv Request for Quota Single Stage - One E IBRD / 88430 Post Open - National 0.00 Canceled 2019-02-15 2019-04-12 2019-10-09 w Additional Service Building estments tions nvelope of ASAT (Procurement Plan It em No ASAT3 G8) ASAT3/G9 / Procurement of I T Equipments for the New Ad Component A: Municipal Inv Request for Quota Single Stage - One E IBRD / 88430 Post Open - National 0.00 Canceled 2019-10-05 2019-11-30 2020-01-14 ditional Service Building of A estments tions nvelope SAT (Procurement Plan Item No ASAT3 G9) ASAT3/G10 / Procurement Of fice Equipments and Rehabili Component A: Municipal Inv Request for Quota Single Stage - One E tation Works for the New Add IBRD / 88430 Post Open - National 0.00 Canceled 2019-10-05 2019-11-23 2020-01-07 estments tions nvelope itional Service Building of AS AT (Procurement Plan Item N o ASAT3 G10) ASAT3 G2(CORRECTION) / Pr Component A: Municipal Inv Single Stage - One E ocurement of 100.000 Nos of IBRD / 88430 Post Request for Bids Open - National 1,072,030.00 Signed 2019-10-03 2019-10-24 2019-10-08 2019-11-19 2019-12-10 2019-12-19 2020-02-19 2020-01-23 2020-04-04 2020-07-21 estments nvelope Water Meters ASAT3-G5(CORRECTION) / Pr Component A: Municipal Inv Single Stage - One E ocurement of 100.000 Nos of IBRD / 88430 Post Request for Bids Open - National 1,211,860.00 Signed 2021-03-07 2021-04-05 2021-03-12 2021-04-23 2021-05-25 2021-05-23 2021-08-02 2021-06-27 2021-10-02 2021-12-24 estments nvelope Water Meters ASAT3 G12 / Procurement of Component A: Municipal Inv Single Stage - One E IBRD / 88430 Post Request for Bids Open - National 323,176.21 Signed 2020-12-13 2021-04-05 2020-12-18 2021-01-29 2021-05-27 2021-02-28 2021-08-26 2021-04-04 2021-10-12 2021-10-01 2 nos of Wastewater Vacuum estments nvelope Trucks ASAT3 G11 / Procurement of Component A: Municipal Inv Single Stage - One E 300 nos Handheld Terminals IBRD / 88430 Post Request for Bids Open - National 131,543.67 Signed 2020-12-10 2022-01-24 2020-12-15 2021-01-26 2022-03-08 2021-02-25 2022-05-18 2021-04-01 2022-07-03 2021-09-28 estments nvelope and 250 nos Mobile Printers ASAT3-G5 / Procurement of Component A: Municipal Inv Open - Internationa Single Stage - One E IBRD / 88430 Post Request for Bids 0.00 Canceled 2019-07-10 2019-07-15 2019-08-26 2019-10-07 2019-11-11 2020-11-10 100.000 Nos of Water Meters estments l nvelope ASAT3/G2 / Procurement of Water Meters (Procurement P Component A: Municipal Inv Open - Internationa Single Stage - One E IBRD / 88430 Prior Request for Bids 0.00 Canceled 2019-09-27 2019-10-02 2019-11-13 2019-12-13 2020-01-17 2020-07-15 lan Item No ASAT3 G2) (Proc estments l nvelope urement of 100.000 Nos of W ater Meters) ASAT3-G13 / Procurement of Component A: Municipal Inv Single Stage - One E IBRD / 88430 Post Request for Bids Open - National 0.00 Canceled 2022-01-14 2022-01-21 2022-02-22 2022-04-05 2022-05-12 2022-10-10 High Flowrate Water Meters estments nvelope Page 2 ASAT3-G6(REV) / Procureme Component A: Municipal Inv Single Stage - One E IBRD / 88430 Post Request for Bids Open - National 1,624,860.00 Signed 2021-12-30 2022-04-05 2022-01-14 2022-02-28 2022-05-11 2022-03-04 2022-06-27 2022-04-08 2022-08-27 2023-02-02 nt of Water Meters estments nvelope ISCEHISAR-G1 / Purchase of Component A: Municipal Inv Single Stage - One E Pending Impl IBRD / 89740 Post Request for Bids Open - National 0.00 2022-11-30 2023-01-02 2023-02-01 2023-03-03 2023-04-07 2024-04-06 Fire Trucks Project estments nvelope ementation ASAT3-G14 / Procurement of Component A: Municipal Inv Single Stage - One E Under Imple IBRD / 88430 Post Request for Bids Open - National 0.00 2023-01-16 2023-03-20 2023-01-30 2023-03-06 2023-05-10 2023-04-03 2023-05-08 2024-03-03 Water Meters estments nvelope mentation ASAT3-G15 / Procurement of Component A: Municipal Inv Single Stage - One E Pending Impl IBRD / 88430 Post Request for Bids Open - National 0.00 2023-03-13 2023-03-27 2023-05-01 2023-05-29 2023-07-03 2024-04-28 Water Meters estments nvelope ementation BASKİ-G1 / Procurement of Component A: Municipal Inv Single Stage - One E Under Imple IBRD / 89740 Post Request for Bids Open - National 0.00 2023-03-30 2023-04-07 2023-04-27 2023-05-27 2023-05-18 2023-06-16 2023-07-03 2023-12-30 Water Meters Project estments nvelope mentation BASKİ-G2 / Procurement of Component A: Municipal Inv Single Stage - One E Pending Impl IBRD / 89740 Post Request for Bids Open - National 0.00 2024-02-01 2024-02-29 2024-03-30 2024-04-29 2024-05-16 2024-11-12 Water Meters Project estments nvelope ementation BASKİ-G3 / Procurement of Component A: Municipal Inv Single Stage - One E Pending Impl IBRD / 89740 Post Request for Bids Open - National 0.00 2025-02-01 2025-03-01 2025-03-31 2025-04-30 2025-05-17 2025-11-13 Water Meters Project estments nvelope ementation KONYAAF -TRANSPORT-G1 / Component A: Municipal Inv Single Stage - One E Pending Impl Design, Supply and Installati IBRD / 89740 Post Request for Bids Open - National 0.00 2023-09-26 2023-10-01 2023-10-31 2023-11-30 2023-12-17 2024-08-13 estments nvelope ementation on of Information Systems GUMUSHANE-G1 / Gümüşha Component A: Municipal Inv Single Stage - One E Pending Impl ne Municipality Purchase of F IBRD / 89740 Post Request for Bids Open - National 0.00 2023-04-24 2023-05-10 2023-06-09 2023-07-09 2023-07-26 2024-01-22 estments nvelope ementation ire Trucks Project. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MUS2 C1 / Consultancy Servi ces for Review of Final Desig Component A: Municipal Inv Quality And Cost- Open - Internationa IBRD / 88430 Post 0.00 Canceled 2018-12-21 2019-01-11 2019-03-08 2019-04-19 2019-06-14 2019-07-19 2019-08-23 2021-10-31 ns, Preparation of Bidding Do estments Based Selection l cuments and Construction Su pervision MUS2/C2 / Consultancy Servi ces for ESIA and ESMP for Ör Component A: Municipal Inv Consultant Qualifi Open - Internationa Pending Impleme en WWTP , Ören Sewerage N IBRD / 88430 Post 0.00 2019-10-14 2019-11-04 2019-12-23 2020-01-20 2020-02-24 2020-10-31 estments cation Selection l ntation etwork and miscellaneous se werage Networks of Bodrum NEVŞEHİR-KOZAKLI-C1 / Con sultancy Services for Constru Component A: Municipal Inv Consultant Qualifi Under Implement IBRD / 89740 Post Open - National 0.00 2021-12-10 2022-02-09 2021-12-31 2022-02-11 2022-07-05 2022-03-11 2022-04-05 2022-12-01 ction supervision of Kozaklı-G estments cation Selection ation eothermal Energy Heating Sy stem Network NİKSAR-C1 / Consultancy Ser vices for Design Review, Prep aration of Bidding Document Component A: Municipal Inv Quality And Cost- Open - Internationa Under Implement IBRD / 89740 Post 0.00 2022-03-17 2022-04-11 2022-04-07 2022-04-19 2022-05-21 2022-06-09 2022-06-18 2022-07-27 2022-07-18 2022-08-12 2022-08-22 2022-09-26 2025-07-12 s and Construction Supervisi estments Based Selection l ation on Services for Tokat-Niksar Centrum Drinking Water Net work Project KOSKİ-C1 / Consultancy Serv ices for Design Review, Prepa ration of Bidding Documents Component A: Municipal Inv Quality And Cost- Open - Internationa Under Implement IBRD / 89740 Post 0.00 2022-05-26 2022-08-25 2022-06-09 2022-09-01 2022-07-23 2022-10-26 2022-08-20 2022-12-02 2022-09-19 2022-12-28 2022-10-24 2023-01-06 2022-11-28 2024-10-28 and Construction Supervision estments Based Selection l ation Services Services for Environ mental Infrastructure Project s ASAT3 C1 / Consultancy Ser Component A: Municipal Inv Quality And Cost- Open - Internationa vices for Master Plan, Feasibil IBRD / 88430 Post 0.00 Canceled 2019-10-14 2019-11-04 2020-01-13 2020-02-17 2020-04-13 2020-05-18 2020-06-22 2022-06-12 estments Based Selection l ity and Project Preparation NIGDE-C1 / Consultancy Ser vices for Design Review, Prep Component A: Municipal Inv Quality And Cost- Open - Internationa Under Implement aration of Bidding Document IBRD / 89740 Post 0.00 2022-12-19 2023-04-11 2023-01-02 2023-04-13 2023-02-27 2023-04-03 2023-05-15 2023-07-10 2023-08-21 2026-05-07 estments Based Selection l ation s and Construction Supervisi on Services for Niğde Sub-Pr oject ASKI-C1 / ASKI-C1 - Consulta ncy Services for Design Revi ew, Preparation of Bidding D Component A: Municipal Inv Quality And Cost- Open - Internationa Under Implement ocuments and Construction S IBRD / 89740 Post 0.00 2023-02-01 2023-03-14 2023-02-15 2023-03-31 2023-04-28 2023-05-28 2023-07-02 2023-08-06 2027-01-31 estments Based Selection l ation upervision Services for İVEDİ K Drinking Water Treatment Plant - 4th Unit (capacity incr ease) Project BASKİ-C1 / Consultancy Serv ices for Design Review, Prepa ration of Bidding Documents Component A: Municipal Inv Quality And Cost- Open - Internationa Under Implement IBRD / 89740 Post 0.00 2023-03-31 2023-04-02 2023-04-14 2023-04-13 2023-05-28 2023-06-25 2023-07-25 2023-08-29 2023-10-03 2025-09-02 and Construction Supervision estments Based Selection l ation Services for Environmental In frastructure Projects of BASKİ KONYAAF-TRANSPORT-C1 / C onsultancy Services for Desig n Review, Preparation of Bidd Component A: Municipal Inv Quality And Cost- Open - Internationa Under Implement IBRD / 89740 Prior 0.00 2023-03-15 2023-04-11 2023-03-20 2023-05-24 2023-05-03 2023-05-31 2023-06-30 2023-08-04 2023-09-08 2027-02-28 ing Documents and Construc estments Based Selection l ation tion Supervision Services Ser vices for Transportation Infra structure Projects MASKİ-C1 / Consultancy Serv ices for Design Review, Prepa ration of Bidding Documents Component A: Municipal Inv Quality And Cost- Open - Internationa Under Implement IBRD / 89740 Prior 0.00 2023-03-31 2023-05-22 2023-04-14 2023-05-30 2023-05-28 2023-06-25 2023-07-25 2023-08-29 2023-10-03 2027-03-30 and Construction Supervision estments Based Selection l ation Services Services for Environ mental Infrastructure Project s of MASKİ Page 3 KEMERHİSAR-C1 / Consultan cy Services for Design Revie w, Preparation of Bidding Do Component A: Municipal Inv Consultant Qualifi Pending Impleme IBRD / 89740 Post Open - National 0.00 2023-05-21 2023-06-05 2023-07-19 2023-08-18 2023-09-22 2026-02-08 cuments and Construction Su estments cation Selection ntation pervision Services for Kemer hisar Drinking Water Network Project MERZIFON-C1 / Consultancy Services for Design Review, P Component A: Municipal Inv Quality And Cost- Open - Internationa Under Implement reparation of Bidding Docum IBRD / 89740 Post 0.00 2023-04-17 2023-05-24 2023-05-01 2023-05-29 2023-06-26 2023-07-31 2023-09-11 2023-11-06 2023-12-18 2026-05-01 estments Based Selection l ation ents and Construction Super vision Services for Merzifon S ub-Project INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ASAT3/C2 / Training of ASAT Employees on World Bank Pr Component A: Municipal Inv ocurement Procedures and C IBRD / 88430 Post Direct Selection Direct 0.00 Canceled 2019-10-14 2019-10-24 2019-12-28 2020-06-25 estments ontract Management (Procur ement Plan Item No ASAT3 C 2) Page 4 PROCUREMENT PLAN (Textual Part) Project information: Republic of Tajikistan Project name: Tajikistan Preparedness and Resilience to Disasters Project Project ID: P177779 Project Implementation agency: MoF, MoT, CoESCD Date of the Procurement Plan: May 14, 2023 Period covered by this Procurement Plan: Only two packages were provided by MoT, not the full plan Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the Tendering with Unlimited Participation procurement method may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Law of the Republic of Tajikistan “Оn Public Procurement of Goods, Works and Services”, # 1955 dated March 15, 2023 such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: a. The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. b. The request for bids/request for proposals document, including contract forms, acceptable to the Bank shall be used. c. The request for bids/request for proposals document and contract shall provide the right to the Bank to review procurement documentation and activities. d. Borrower shall put in place an effective complaints review mechanism and shall disclose the details in all the bidding documents. All complaints shall be recorded by the Borrower in the appropriate tracking and monitoring system, as agreed between the Bank and the Borrower. e. No preference shall be applied under competitive bidding following national market approach. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables “Not Applicable”. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable”. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] “Not Applicable”. Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] “Not Applicable”. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. “Not Applicable” Other Relevant Procurement Information. No CDC activities are envisaged under the project. The MoF will implement Contingent Emergency Response Component, with technical inputs and supervision from relevant agencies such as the CoESCD, IGEES and relevant departments within the MoF. PROCUREMENT Tajikistan : Tajikistan Preparedness and Resilience to Disasters Project PLAN General Information Country: Tajikistan Bank’s Approval Date of the Original Procurement Plan: 2023-05-23 Revised Plan Date(s): (comma delineated, leave blank if 2023-05-29 none) Project ID: P177779 GPN Date: Project Name: Tajikistan Preparedness and Resilience to Disasters Project Loan / Credit No: IDA / D9780 STATE INSTITUTION "Project Implementation Unit for Access to Green and Rural Development Finance" Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MOF/TPRDP/W-RFB-01 / Wor Request for Bids - ks to build or renovate faciliti Component 2: Strengthening Single Stage - One E Small Works SPD Pending Imp 2025-04-2 es to host CoESCD’s regional IDA / D9780 Disaster Risk Management C Post Request for Bids Open - National 3,000,000.00 0.00 2024-01-10 2024-01-15 2024-02-26 2024-03-27 2024-04-24 nvelope (1 envelope proce lementation 4 crisis management centers ( apacity ss) RCMCs) in Khujand, Khorog a nd Bokhtar GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOF/TPRDP/G-RFB-01 / Purc Component 2: Strengthening hasing of required informatio Open - Internationa Single Stage - One E Pending Impl IDA / D9780 Disaster Risk Management C Prior Request for Bids 3,100,000.00 0.00 2024-10-13 2024-10-18 2024-11-29 2024-12-29 2025-02-02 2025-08-01 n and communication techno l nvelope ementation apacity logy equipment to be installe d within 3 RCMCs MOF/TPRDP/G-RFB-03 / Purc Component 2: Strengthening Open - Internationa Single Stage - One E Pending Impl IDA / D9780 Prior Request for Bids 2,440,000.00 0.00 2023-08-27 2023-09-01 2023-10-13 2023-11-12 2023-12-17 2024-06-14 hasing of MCCV Disaster Risk Management C l nvelope ementation apacity MOF/TPRDP/G-RFQ-01 / Proc Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl urement of office equipment IDA / D9780 Post Open - National 20,000.00 0.00 2023-07-23 2023-09-17 2024-03-15 ement tions nvelope ementation for PIU MoF staff NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOF/TPRDP/CQS-03 / Prepar Component 2: Strengthening ation of capacity building pla Consultant Qualifi Pending Impleme IDA / D9780 Disaster Risk Management C Post Open - National 100,000.00 0.00 2023-08-20 2023-09-10 2023-10-24 2023-11-23 2023-12-28 2024-06-25 ns for relevant staff and oper cation Selection ntation apacity ators of the RCMCS and user s of MCCV MOF/TPRDP/CQS-04 / Furthe Component 2: Strengthening Consultant Qualifi Pending Impleme IDA / D9780 Post Open - National 50,000.00 0.00 2024-06-15 2024-07-06 2024-08-19 2024-09-18 2024-10-23 2025-04-21 r updating of the SNiP Disaster Risk Management C cation Selection ntation apacity MOF/TPRDP/CQS-05 / Buildin Component 2: Strengthening g the capacity of the SCS in t Consultant Qualifi Pending Impleme IDA / D9780 Disaster Risk Management C Post Open - National 50,000.00 0.00 2024-06-26 2024-07-17 2024-08-30 2024-09-29 2024-11-03 2025-05-02 he field of monitoring and en cation Selection ntation apacity forcement of rules and regul ations MOF/TPRDP/CQS-06 / Trainin Component 2: Strengthening g of the construction commu Consultant Qualifi Pending Impleme IDA / D9780 Disaster Risk Management C Post Open - National 50,000.00 0.00 2023-08-01 2023-08-22 2023-10-05 2023-11-04 2023-12-09 2024-06-06 nity in the application and int cation Selection ntation apacity egration of SNiP requirement s into design solutions MOF/TPRDP/CQS-07 / Consul Component 2: Strengthening ting services to assess the re Consultant Qualifi Pending Impleme IDA / D9780 Disaster Risk Management C Post Open - National 100,000.00 0.00 2023-12-25 2024-01-15 2024-02-28 2024-03-29 2024-05-03 2024-10-30 quirements, fiscal realities, n cation Selection ntation apacity eeded legislation and regulat ions MOF/TPRDP/CQS-08 / Design Component 2: Strengthening ing priority mechanisms to e Consultant Qualifi Pending Impleme IDA / D9780 Disaster Risk Management C Post Open - National 200,000.00 0.00 2024-03-26 2024-04-16 2024-05-30 2024-06-29 2024-08-03 2025-01-30 nable establishment and fun cation Selection ntation apacity ctioning of disaster risk finan cing instruments MOF/TPRDP/CQS-01 / Develo pment of feasibility study, de sign estimates, cost estimate Component 2: Strengthening Consultant Qualifi Pending Impleme s, bills of quantities for the R IDA / D9780 Disaster Risk Management C Post Open - National 300,000.00 0.00 2023-06-05 2023-06-26 2023-08-09 2023-09-08 2023-10-13 2024-04-10 cation Selection ntation CMC in Khujand, Khorog and apacity Bokhtar, technical specificati on of ICT equipment and aut hor supervision MOF/TPRDP/LCS-09 / Project Component 3: Project Manag Least Cost Selecti Pending Impleme IDA / D9780 Post Open - National 10,000.00 0.00 2023-10-01 2023-10-22 2023-12-05 2024-01-02 2024-02-01 2024-03-07 2024-04-11 2024-05-11 audit for the 2023 year ement on ntation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOF/TPRDP/CQS-02 / Servic Component 2: Strengthening Pending Impleme es to expand the national op IDA / D9780 Disaster Risk Management C Post Direct Selection Direct - National 60,000.00 0.00 2023-06-22 2023-07-02 2023-09-05 2024-03-03 ntation erational manual for the RCM apacity C Page 1 PROCUREMENT PLAN (Textual Part) Project information: São Tomé and Principe; STP Girls Empowerment and Quality Education for All Project; P169222 Project Implementation agency: Ministry of Education, with fiduciary functions to be carried by AFAP Date of the Procurement Plan: 15 June 2020 Period covered by this Procurement Plan: 15 June to 30 September 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used – Not applicable. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is Not applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables. Other Relevant Procurement Information All Direct Contract will be prior reviewed during the first year of project’s implementation. At the end of that period, an assessment will be made to revise the requirement, if needed. PROCUREMENT Sao Tome and Principe : Girls Empowerment and Quality Education for All Project PLAN General Information Country: Sao Tome and Principe 2020-06-16 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169222 GPN Date: Project Name: Girls Empowerment and Quality Education for All Project Loan / Credit No: IDA / V3070, IDA / D7340, TF / B3318 Project Fiduciary and Administrative Agency Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Project Coordination, Monito 04/W/GEE/2020 / Rehabilitati Request for Quota Single Stage - One E 2021-04-0 IDA / V3070 ring and Evaluation, and Cap Post Open - National 30,000.00 27,416.49 Completed 2020-08-16 2020-10-11 2020-10-08 on of PCU office in the MEES tions nvelope 9 acity Building 20/G/GEE/2020 / Rehabilitati Empowering Girls through th on and construction of bathr e Acquisition of Life Skills an Single Stage - One E 2021-10-0 IDA / V3070 Post Request for Bids Open - National 1,600,000.00 0.00 Canceled 2020-12-21 2020-12-26 2021-02-06 2021-03-08 2021-04-12 ooms and water suplply in sc d the Promotion of a Safe Sc nvelope 9 hools hool Environment National Procure 48/W/GEE/2022 / Hiring a co Empowering Girls through th ment Document - nstruction company to build e Acquisition of Life Skills an Request for Quota Single Stage - One E 2023-01-2 IDA / D7340 Post Open - National 1 Envelope proce 47,539.74 52,420.20 Signed 2022-05-29 2022-07-24 2022-09-10 a room (medium-sized physic d the Promotion of a Safe Sc tions nvelope 0 ss (Non Bank-SPD al space for backstage int th hool Environment ) e MEES) National Procure 68/W/GEE/2022 / MECC War Empowering Girls through th ment Document - ehouse refurbishment works, e Acquisition of Life Skills an Request for Quota Single Stage - One E 2023-11-0 IDA / D7340 Post Limited 1 Envelope proce 15,498.73 0.00 Signed 2023-03-13 2022-12-09 2023-05-08 to archive the AALEEB AND A d the Promotion of a Safe Sc tions nvelope 4 ss (Non Bank-SPD ALEES assessment instrumen hool Environment ) ts 75/W/GEE/2023 / Hiring of a Civil Construction Company t Empowering Girls through th Request for Bids - o carry out the Construction e Acquisition of Life Skills an Single Stage - One E Small Works SPD Under Imple 2024-01-2 IDA / D7340 Post Request for Bids Open - National 1,831,758.37 0.00 2023-04-04 2023-04-12 2023-04-09 2023-05-21 2023-06-20 2023-07-25 and Rehabilitation of Bathroo d the Promotion of a Safe Sc nvelope (1 envelope proce mentation 1 ms and Improvements to the hool Environment ss) Infrastructures of Schools in São Tomé and Príncipe (1.1.2 ) 81/W/GEE/2023 / Hiring of a Civil Construction Company t o carry out the Construction Empowering Girls through th Request for Bids - and Rehabilitation of Bathroo e Acquisition of Life Skills an Single Stage - One E Small Works SPD Pending Imp 2024-06-0 IDA / D7340 Post Request for Bids Open - National 1,790,849.80 0.00 2023-08-22 2023-08-27 2023-10-08 2023-11-07 2023-12-12 ms and Improvements to the d the Promotion of a Safe Sc nvelope (1 envelope proce lementation 9 Infrastructures of Schools (Es hool Environment ss) c. Basica Leal Bouças, Esc. B as.Venêncio Pires, Esc. Bas. Secun. Guadalup)in São Tom é and Príncipe GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 03/G/GEE/2020 / Acquisition Project Coordination, Monito Request for Quota Single Stage - One E of officve furniture for PIU (Mi IDA / V3070 ring and Evaluation, and Cap Post Limited 3,000.00 4,322.05 Completed 2020-05-05 2020-11-16 2020-06-30 2020-12-15 2020-12-27 2021-06-18 tions nvelope nistry of Education) acity Building Project Coordination, Monito 14/G/GEE/2020 / Purchase of Request for Quota Single Stage - One E IDA / V3070 ring and Evaluation, and Cap Post Limited 10,000.00 5,035.30 Completed 2020-05-13 2020-04-21 2020-07-08 2020-07-10 2021-01-04 2020-08-13 ITC Equipments for DPIE tions nvelope acity Building Project Coordination, Monito 01/G/GEE/2020 / Axquisition Request for Quota Single Stage - One E IDA / V3070 ring and Evaluation, and Cap Post Open - National 50,000.00 60,391.62 Completed 2020-08-01 2020-09-26 2020-11-25 2021-03-25 2021-02-11 of two (2) vehicles tions nvelope acity Building 02/G/GEE/2020 / Purchase of Project Coordination, Monito ITC equipment (5 Desktops, Request for Quota Single Stage - One E IDA / V3070 ring and Evaluation, and Cap Post Limited 15,500.00 17,018.05 Completed 2020-08-29 2020-10-12 2020-10-24 2020-11-12 2021-04-22 2021-06-16 1 multifunction printer, 4 po tions nvelope acity Building wer stations, 2 laptops) for P CU 18/C/GEE/2020 / Editing and Empowering Girls through th Printing of communication m e Acquisition of Life Skills an Request for Quota Single Stage - One E IDA / V3070 Post Limited 50,000.00 0.00 Canceled 2021-02-15 2021-04-12 2021-10-09 aterials (tamps, logos, etc.) f d the Promotion of a Safe Sc tions nvelope or PEREQT hool Environment Project Coordination, Monito 01/G/GEE/2021 / Aquisição d Request for Quota Single Stage - One E IDA / V3070 ring and Evaluation, and Cap Post Limited 28,000.00 29,713.52 Completed 2021-01-24 2021-01-20 2021-03-21 2021-01-23 2021-09-17 2021-06-18 e 19 Computadores Portáteis tions nvelope acity Building 37/G/GEE/2021 / Acquisition of 40 Tablets and Technology Equipment (2 video-conferen Request for Quota Single Stage - One E IDA / D7340 Tackling Learning Poverty Post Limited 30,000.00 22,203.12 Completed 2022-01-03 2021-06-30 2022-02-28 2021-08-27 2022-08-27 2021-10-26 cing systems and 4 Laptops) tions nvelope to support the implementatio n of Basic Education classroo m observation (TEACH) 46/G/GEE/2022 / Acquisition Project Coordination, Monito and installation of Generator Request for Quota Single Stage - One E IDA / D7340 ring and Evaluation, and Cap Post Limited 31,252.85 22,593.03 Completed 2022-04-02 2022-03-16 2022-05-28 2022-07-06 2022-11-24 2022-08-24 and Electric Pump (including tions nvelope acity Building Construction of Generator Ho use). 44/G/GEE/2022 / Acquisition Project Coordination, Monito Request for Quota Single Stage - One E of Equipment and Furniture f IDA / D7340 ring and Evaluation, and Cap Post Limited 12,770.22 0.00 Canceled 2022-03-05 2022-03-01 2022-04-30 2022-10-27 tions nvelope or MEES acity Building Project Coordination, Monito 59/G/GEE/2022 / Purchasing Request for Quota Single Stage - One E IDA / D7340 ring and Evaluation, and Cap Post Limited 9,000.00 6,169.41 Completed 2022-07-05 2022-07-22 2022-08-30 2022-09-24 2023-02-26 2023-01-02 a UPS for AFAP tions nvelope acity Building Empowering Girls through th 63/G/GEE/2022 / Acquisition e Acquisition of Life Skills an Single Stage - One E of 5 off-road vehicles to supe IDA / D7340 Post Request for Bids Open - National 211,168.60 0.00 Signed 2022-09-21 2022-09-21 2022-09-26 2022-11-07 2022-11-03 2022-12-07 2022-11-15 2023-01-11 2023-07-10 d the Promotion of a Safe Sc nvelope rvise the Project's activities. hool Environment Page 1 49/G/GEE/2022 / Acquisition Empowering Girls through th of 4 vehicles to supervise the e Acquisition of Life Skills an Single Stage - One E IDA / D7340 Post Request for Bids Open - National 175,000.00 0.00 Canceled 2022-05-20 2022-05-25 2022-07-06 2022-08-05 2022-09-09 2023-03-08 works of Bathrooms in School d the Promotion of a Safe Sc nvelope s hool Environment Project Coordination, Monito 65/G/GEE/2022 / Supply of F Request for Quota Single Stage - One E IDA / D7340 ring and Evaluation, and Cap Post Limited 7,431.94 0.00 Completed 2022-11-27 2022-11-07 2023-01-22 2023-07-21 2023-04-04 urniture for MEES tions nvelope acity Building 66/G/GEE/2022 / Acquisition Project Coordination, Monito of equipment (CHARGER FOR Request for Quota Single Stage - One E IDA / D7340 ring and Evaluation, and Cap Post Limited 2,799.49 0.00 Signed 2022-11-30 2022-11-04 2023-01-25 2023-07-24 DIGITALCAMERA, AIR CONDIT tions nvelope acity Building IONING and PROJECTOR) for MEES 19/G/GEE/2020 / Design, edi Open - Internationa Single Stage - One E ting and printing of Teaching IDA / V3070 Tackling Learning Poverty Post Request for Bids 500,000.00 0.00 Canceled 2020-09-01 2020-09-06 2020-10-18 2020-11-17 2020-12-22 2021-06-20 l nvelope learning materials (TLMS) for Basic education 09/G/GEE/2020 / Editing and Contingency Emergency Res Request for Quota Single Stage - One E IDA / V3070 Post Open - National 70,000.00 0.00 Canceled 2023-01-04 2023-03-01 2023-08-28 printing of materials on COVI ponse Component (CERC) tions nvelope D19 17/G/GEE/2020 / Purchase of ITC equipments for schools (c Open - Internationa Single Stage - One E TF / B3318 Tackling Learning Poverty Post Request for Bids 700,000.00 0.00 Canceled 2022-06-29 2022-07-04 2022-08-15 2022-09-14 2022-10-19 2023-04-17 omputers,printers, tablets, la l nvelope ptops, power stations) (2.2.1) Empowering Girls through th 79/G/GEE/2023 / Providing e Acquisition of Life Skills an Request for Quota Single Stage - One E Under Imple menstrual management prod IDA / D7340 Post Limited 30,000.00 0.00 2023-06-17 2023-08-12 2024-02-08 d the Promotion of a Safe Sc tions nvelope mentation ucts/reusable pads (1.1.2) hool Environment NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 06/S/GEE/2020 / Updadte of Project Coordination, Monito Tompro for Eduication Projec IDA / V3070 ring and Evaluation, and Cap Post Direct Selection Direct 15,000.00 16,500.00 Completed 2020-05-29 2021-05-28 2020-06-03 2021-05-31 2020-07-08 2021-06-09 2021-01-04 2021-07-02 t acity Building 37/NC/GEE/2020 / Editing an Empowering Girls through th d printing of communication e Acquisition of Life Skills an Request for Quota Single Stage - One E IDA / V3070 Post Limited 40,000.00 4,088.74 Completed 2021-06-22 2021-09-10 2021-08-17 2021-11-03 2022-02-13 2021-12-02 materials (tamps, logos, etc.) d the Promotion of a Safe Sc tions nvelope for PEREQT hool Environment 18/S/GEE/2020 / Editing and Empowering Girls through th Printing of communication m e Acquisition of Life Skills an Request for Quota Single Stage - One E IDA / V3070 Post Open - National 50,000.00 0.00 Canceled 2021-03-15 2021-05-10 2021-11-06 aterials (tamps, logos, etc.) f d the Promotion of a Safe Sc tions nvelope or PEREQT hool Environment 05/G/GEE/220 / Internet Serv IDA / V3070 Tackling Learning Poverty Post Direct Selection Direct 20,000.00 0.00 Canceled 2020-07-31 2020-08-05 2020-09-09 2021-03-08 ice for MEES Empowering Girls through th 60/S/GEE/2022 / Provision of e Acquisition of Life Skills an services to MEES/PEREQT in t IDA / D7340 Post Direct Selection Direct - National 72,750.00 72,750.00 Signed 2022-08-30 2022-07-27 2022-09-04 2022-07-28 2022-10-09 2022-08-30 2023-04-07 d the Promotion of a Safe Sc he area of ​communication hool Environment Project Coordination, Monito 64/NC/GEE/2022 / TomPro S Direct - Internation IDA / V3070 ring and Evaluation, and Cap Post Direct Selection 10,000.00 0.00 Completed 2022-10-06 2022-09-27 2022-10-11 2022-10-06 2022-11-15 2023-05-14 2023-01-02 ystem Technical Support al acity Building Project Coordination, Monito 62/S/GEE/2022 / Provision of Request for Quota Single Stage - One E IDA / D7340 ring and Evaluation, and Cap Post Limited 2,538.79 0.00 Signed 2022-11-27 2022-11-04 2023-01-22 2023-07-21 Security Service for MEES tions nvelope acity Building CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 10/C/GEE/2020 / Capacity bu Project Coordination, Monito Consultant Qualifi Open - Internationa ilding activity on large scale IDA / V3070 ring and Evaluation, and Cap Post 80,000.00 0.00 Canceled 2020-09-14 2020-10-05 2020-11-18 2020-12-18 2021-01-22 2021-07-21 cation Selection l student learning assessment acity Building 27/C/GEE/2020 / TA to imple Quality And Cost- Open - Internationa ment the Professional develo IDA / V3070 Tackling Learning Poverty Post 350,000.00 0.00 Canceled 2021-01-28 2021-02-18 2021-04-03 2021-05-01 2021-05-31 2021-07-05 2021-08-09 2022-08-09 Based Selection l pment program for pre-schoo l teachers 26/C/GEE/2020 / TA to condu ct large-scale students learni Quality And Cost- Open - Internationa IDA / V3070 Tackling Learning Poverty Post 300,000.00 0.00 Canceled 2021-04-22 2021-02-11 2021-05-13 2021-02-18 2021-06-26 2021-07-24 2021-08-23 2021-09-27 2021-11-01 2022-11-01 ng assessment in primary an Based Selection l d secondarybschools (ALLEB and ALLES) 42/C/GEE/2022 / Selection a nd contracting of a Consultan Empowering Girls through th cy Office/Company to develo e Acquisition of Life Skills an Consultant Qualifi IDA / V3070 Post Open - National 79,296.00 30,764.97 Completed 2022-01-26 2022-01-17 2022-02-16 2022-01-24 2022-04-01 2022-04-05 2022-05-01 2022-05-09 2022-06-05 2022-06-04 2022-12-02 2023-02-26 p architectural and structural d the Promotion of a Safe Sc cation Selection projects for the construction hool Environment and rehabilitation of bathroo ms in schools 45/C/GEE/2022 / Hiring a co Project Coordination, Monito Consultant Qualifi mpany to teach the English c IDA / D7340 ring and Evaluation, and Cap Post Open - National 24,000.00 24,773.57 Signed 2022-03-30 2022-03-14 2022-04-20 2022-06-03 2022-06-06 2022-07-03 2022-08-08 2022-08-07 2022-08-30 2023-02-03 cation Selection ourse for MEES´s Technicians acity Building . Empowering Girls through th 29/C/GEE/2020 / TA to imple e Acquisition of Life Skills an Quality And Cost- Open - Internationa ment the Girls' Empweremen IDA / V3070 Post 220,000.00 0.00 Canceled 2021-01-04 2021-01-25 2021-03-10 2021-04-07 2021-05-07 2021-06-11 2021-07-16 2022-07-16 d the Promotion of a Safe Sc Based Selection l t Program hool Environment 28/C/GEE/2020 / TA to imple ment the Professional Develo Quality And Cost- Open - Internationa Under Implement pment Program for Elementa IDA / D7340 Tackling Learning Poverty Prior 1,840,000.00 0.00 2022-06-30 2022-11-21 2022-07-21 2023-04-25 2022-09-03 2022-10-01 2022-10-31 2022-12-05 2023-01-09 2024-01-09 Based Selection l ation ry School Teachers (Elaborati on of Structured Materials) Page 2 53/C/GEE/2022 / T.A to prom Project Coordination, Monito ote Inclusive Education that r Consultant Qualifi Open - Internationa Pending Impleme IDA / D7340 ring and Evaluation, and Cap Post 145,000.00 0.00 2022-06-30 2022-07-21 2022-09-03 2022-10-03 2022-11-07 2023-05-06 esponds to the challenges of cation Selection l ntation acity Building the Framework Law 55/C/GEE/2022 / Project com Project Coordination, Monito Consultant Qualifi munication strategy (Educati IDA / D7340 ring and Evaluation, and Cap Post Open - National 52,500.00 0.00 Canceled 2022-06-24 2022-07-15 2022-08-28 2022-09-27 2022-11-01 2023-04-30 cation Selection on Strengthening, Inclusive E acity Building ducation) 61/C/GEE/2022 / PREPARATI Project Coordination, Monito Consultant Qualifi Open - Internationa ON OF ENVIRONMENTAL AND IDA / D7340 ring and Evaluation, and Cap Post 35,843.00 0.00 Signed 2022-08-30 2022-07-20 2022-09-20 2022-08-02 2022-11-03 2022-11-11 2022-12-03 2023-03-09 2023-01-07 2023-07-06 cation Selection l SOCIAL MANAGEMENT PLANS acity Building (ESMP) 69/C/GEE/2022 / Technical A ssistance to develop process Empowering Girls through th es and actions that promote e Acquisition of Life Skills an Consultant Qualifi Open - Internationa Under Implement a more sustainable, safe and IDA / D7340 Post 65,127.00 0.00 2023-01-10 2022-12-19 2023-01-31 2022-12-22 2023-03-16 2023-03-30 2023-04-15 2023-05-20 2023-11-16 d the Promotion of a Safe Sc cation Selection l ation inclusive school environment hool Environment , as well as strategies for adv ocacy and behavior change i n schools in STP (Wash) 70/C/GEE/2022 / T.A TO STR ENGTHEN THE IMPLEMENTAT Project Coordination, Monito Quality And Cost- Open - Internationa Pending Impleme ION OF THE DEVELOPMENT S TF / B3318 ring and Evaluation, and Cap Post 291,852.00 0.00 2023-07-25 2023-08-15 2023-09-28 2023-10-26 2023-11-25 2023-12-30 2024-02-03 2025-02-02 Based Selection l ntation TRATEGY FOR SPECIAL EDUC acity Building ATION IN SÃO TOMÉ AND PRÍ NCIPE. 71/C/GEE/2023 / Hiring an in stitution to revise the Teache rs' Management Policy in São Quality And Cost- Open - Internationa Under Implement IDA / D7340 Tackling Learning Poverty Post 460,000.00 0.00 2023-08-22 2023-03-17 2023-09-12 2023-03-20 2023-10-26 2023-11-23 2023-12-23 2024-01-27 2024-03-02 2025-03-02 Tomé and Príncipe and carry Based Selection l ation out training, certification in s chool leadership for manager s and supervisors. 72/C/GEE/2023 / Hiring a Offi Empowering Girls through th ce/Company to supervise the e Acquisition of Life Skills an Consultant Qualifi Under Implement TF / B3318 Post Open - National 213,578.27 0.00 2023-10-24 2023-04-12 2023-11-14 2023-12-28 2024-01-27 2024-03-02 2024-08-29 Works of Construction and R d the Promotion of a Safe Sc cation Selection ation ehabilitation of Bathrooms in hool Environment Schools (1.1.2) 23/C/GEE/2020 / Technical A Quality And Cost- Open - Internationa Pending Impleme ssistance for implementation TF / B3318 Tackling Learning Poverty Post 210,000.00 0.00 2023-06-21 2023-07-12 2023-08-25 2023-09-22 2023-10-22 2023-11-26 2023-12-31 2024-12-30 Based Selection l ntation of the accelerated Education Program (3.3.1) 74/C/GEE/2023 / Hiring a TA to develop an integrated tec hnological system that make Reaching the Most Vulnerabl Consultant Qualifi Pending Impleme IDA / D7340 Post Open - National 80,000.00 0.00 2023-11-29 2023-12-20 2024-02-02 2024-03-03 2024-04-07 2024-10-04 s it possible to cross-referenc e cation Selection ntation e the database of both sector s (MECC and Social Protectio n) (3.3.3) 54/C/GEE/2022 / Hiring a co Project Coordination, Monito Consultant Qualifi Open - Internationa Pending Impleme nsultancy to update the Scho IDA / D7340 ring and Evaluation, and Cap Post 50,000.00 0.00 2023-09-27 2023-10-18 2023-12-01 2023-12-31 2024-02-04 2024-08-02 cation Selection l ntation ol Charter (4.4.2) acity Building 78/C/GEE/2023 / STRENGTH EN THE CAPACITY OF PUBLIC Empowering Girls through th SCHOOLS AND GIRLS, ESPECI e Acquisition of Life Skills an Quality And Cost- Open - Internationa Under Implement IDA / D7340 Post 252,303.00 0.00 2023-05-23 2023-05-23 2023-06-13 2023-05-23 2023-07-27 2023-08-24 2023-09-23 2023-10-28 2023-12-02 2024-12-01 ALLY THE MOST VULNERABLE d the Promotion of a Safe Sc Based Selection l ation , TO MANAGE MENSTRUATIO hool Environment N WITH DIGNITY AND IN A SA FE ENVIRONMENT (1.1.2) 22/C/GEE/2020 / Adaptation Project Coordination, Monito Consultant Qualifi Open - Internationa and supervision of data colle IDA / D7340 ring and Evaluation, and Cap Post 140,000.00 0.00 Canceled 2022-11-29 2022-11-14 2022-12-20 2022-11-15 2023-02-02 2023-02-20 2023-03-04 2023-04-08 2023-10-05 cation Selection l ction to baseline using MELQ acity Building O INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 11/C/GEE/2020 / Technical a Project Coordination, Monito ssistance to elaborate the En Individual Consult IDA / V3070 ring and Evaluation, and Cap Post Open 40,000.00 0.00 Canceled 2020-07-19 2020-09-06 2020-09-27 2020-11-01 2021-04-30 vironmental and Social Fram ant Selection acity Building ework instruments 13/C/GEE/2020 / Technical a Project Coordination, Monito ssistance for training and for Individual Consult IDA / V3070 ring and Evaluation, and Cap Post Open 40,000.00 0.00 Canceled 2020-06-26 2020-08-14 2020-09-04 2020-10-09 2021-04-07 providing specialized support ant Selection acity Building to the statics staff 08/CGEE/2020 / Hiring Envir Project Coordination, Monito Individual Consult onmental and Social Develop IDA / V3070 ring and Evaluation, and Cap Post Open 32,000.00 39,150.00 Signed 2020-05-14 2020-12-04 2020-07-02 2021-03-05 2020-07-23 2021-03-24 2020-08-27 2021-04-02 2021-02-23 ant Selection ment specialist for PIU (MEES acity Building ) 07/C/GEE/2020 / Hiring Moni Project Coordination, Monito Individual Consult toring and Evaluation speciali IDA / V3070 ring and Evaluation, and Cap Post Open 32,000.00 0.00 Canceled 2020-07-13 2020-07-10 2020-08-31 2020-08-06 2020-09-21 2020-10-26 2021-04-24 ant Selection st acity Building Project Coordination, Monito 15/C/GEE/2020 / Hiring a Pro Individual Consult IDA / V3070 ring and Evaluation, and Cap Post Open 100,000.00 0.00 Canceled 2020-06-30 2020-07-06 2020-08-18 2020-09-10 2020-09-08 2020-10-13 2021-04-11 ject Management Expert ant Selection acity Building Empowering Girls through th 16/C/GEE/2020 / Hiring a Co e Acquisition of Life Skills an Individual Consult IDA / V3070 Post Open 35,000.00 0.00 Canceled 2020-07-03 2020-07-10 2020-08-21 2020-09-11 2020-10-16 2021-04-14 ordinator for PCU d the Promotion of a Safe Sc ant Selection hool Environment 24/C/GEE/2020 / TA to imple Reaching the Most Vulnerabl Individual Consult Pending Impleme ment an Early warning syste IDA / V3070 Post Open 199,000.00 0.00 2020-12-16 2021-02-03 2021-02-24 2021-03-31 2021-09-27 e ant Selection ntation m to signal students in learn dificulties 30/C/GEE/2020 / Technical a Project Coordination, Monito ssistance to elaborate the en IDA / V3070 ring and Evaluation, and Cap Post Direct Selection Direct 40,000.00 15,000.00 Completed 2020-08-14 2020-08-14 2020-08-24 2020-08-10 2020-10-28 2020-09-01 2021-04-26 2021-12-18 vironmental &Social framewo acity Building rk instruments Empowering Girls through th 31/C/GEE/2020 / Hiring Moni e Acquisition of Life Skills an Individual Consult toring and Evaluation speciali IDA / V3070 Post Open 32,000.00 68,232.60 Signed 2020-10-08 2020-09-30 2020-11-26 2020-11-04 2020-12-17 2020-11-17 2021-01-21 2020-12-02 2021-07-20 d the Promotion of a Safe Sc ant Selection st hool Environment Page 3 Empowering Girls through th 32/C/GEE/2020 / Hiring a Co e Acquisition of Life Skills an Individual Consult IDA / V3070 Post Open 35,000.00 16,200.00 Signed 2020-10-08 2020-09-29 2020-11-26 2020-11-27 2020-12-17 2020-11-30 2021-01-21 2020-12-02 2021-07-20 ordinator for PCU d the Promotion of a Safe Sc ant Selection hool Environment Empowering Girls through th 33/C/GEE/2020 / Hiring a Pro e Acquisition of Life Skills an Individual Consult IDA / V3070 Post Open 100,000.00 93,176.52 Completed 2020-10-13 2020-09-30 2020-12-01 2020-11-17 2020-12-22 2020-11-24 2021-01-26 2020-12-02 2021-07-25 2021-11-27 ject Management Expert d the Promotion of a Safe Sc ant Selection hool Environment Empowering Girls through th 36/C/GEE/2020 / Design of c e Acquisition of Life Skills an Individual Consult ommunication materials (ta IDA / V3070 Post Limited 10,000.00 13,750.00 Completed 2021-04-05 2021-03-18 2021-04-10 2021-03-22 2021-05-01 2021-05-17 2021-06-05 2021-05-22 2021-12-02 2021-11-09 d the Promotion of a Safe Sc ant Selection mps, logos, etc.) for PEREQT hool Environment 35/C/GEE/2020 / TA to condu ct Large-Scale Students Lear IDA / D7340 Tackling Learning Poverty Prior Direct Selection Direct 300,000.00 327,424.09 Signed 2021-03-31 2021-03-29 2021-04-10 2021-03-30 2021-06-14 2022-01-19 2021-12-11 ning Assessment in Primary a nd Secondarybschools (AALE B AND AALES) 34/C/GEE/2020 / Techical As sistance to conduct the Lear IDA / D7340 Tackling Learning Poverty Prior Direct Selection Direct 290,000.00 141,459.43 Signed 2021-03-31 2021-03-30 2021-04-10 2021-04-15 2021-06-14 2021-12-03 2021-12-11 ning Assessment PASEC Empowering Girls through th 08/C/GEE/2021 / Hiring a Co e Acquisition of Life Skills an Individual Consult IDA / V3070 Post Open 32,000.00 45,000.00 Signed 2021-06-10 2021-06-07 2021-07-29 2021-08-06 2021-08-19 2021-08-19 2021-09-23 2021-08-31 2022-03-22 ordinator for PCU d the Promotion of a Safe Sc ant Selection hool Environment Empowering Girls through th 09/C/GEE/2021 / Hiring Civil e Acquisition of Life Skills an Individual Consult IDA / D7340 Post Open 26,400.00 0.00 Canceled 2021-09-28 2021-06-09 2021-11-16 2021-12-07 2022-01-11 2022-07-10 Construction Engineer d the Promotion of a Safe Sc ant Selection hool Environment Empowering Girls through th 38/C/GEE/2021 / Hiring a Civ e Acquisition of Life Skills an Individual Consult IDA / D7340 Post Open 33,840.00 48,600.00 Signed 2021-07-28 2021-06-23 2021-09-15 2021-09-29 2021-10-06 2021-10-06 2021-11-10 2021-10-10 2022-05-09 il Construction Engineer d the Promotion of a Safe Sc ant Selection hool Environment 39/C/GEE/2021 / TECHNICAL ASSISTANCE FOR TRAINING A Individual Consult ND SUPPORT IN DATA ANALY IDA / D7340 Tackling Learning Poverty Post Open 42,500.00 0.00 Canceled 2021-09-22 2021-06-23 2021-11-10 2021-12-01 2022-01-05 2022-07-04 ant Selection SIS FOR THE STATISTICS AND EDUCATIONAL EVALUATION T EAM 40/C/GEE/2021 / Hiring an in Project Coordination, Monito Individual Consult dividual consultant to survey IDA / D7340 ring and Evaluation, and Cap Post Limited 2,500.00 2,500.00 Completed 2021-09-22 2021-09-08 2021-09-27 2021-09-10 2021-10-18 2021-10-18 2021-11-22 2021-10-20 2022-05-21 2021-12-07 ant Selection the conditions of the MEES el acity Building ectrical system 41/C/GEE/2021 / TA FOR TRA INING PRESCHOOL EDUCATIO N TEACHERS, CONCEPTION, IDA / V3070 Tackling Learning Poverty Post Direct Selection Direct 1,151,003.00 1,151,003.00 Signed 2021-12-20 2021-12-17 2021-12-30 2021-12-20 2022-03-05 2022-01-29 2022-09-01 CONSTRUCTION AND ACQUIS ITION OF SUPPORT MATERIAL S FOR THE TEACHING AND LE ARNING OF CHILDREN 43/C/GEE/2022 / TECHNICAL ASSISTANCE FOR TRAINING A ND SUPPORT IN DATA ANALY Individual Consult IDA / D7340 Tackling Learning Poverty Post Open 78,200.00 75,167.84 Signed 2022-01-26 2022-01-17 2022-03-16 2022-04-27 2022-04-06 2022-06-13 2022-05-11 2022-07-10 2022-11-07 SIS FOR THE EDUCATIONAL S ant Selection TATISTICS AND EVALUATION TEAM IN SAO TOME AND PRI NCIPE Empowering Girls through th 56/C/GEE/2022 / Financial M e Acquisition of Life Skills an Individual Consult IDA / D7340 Post Direct 45,627.24 45,627.24 Signed 2022-04-18 2022-05-19 2022-04-28 2022-06-13 2022-05-19 2022-06-14 2022-06-23 2022-06-25 2022-12-20 anager for AFAP d the Promotion of a Safe Sc ant Selection hool Environment Empowering Girls through th 58/C/GEE/2022 / Senior Acco e Acquisition of Life Skills an Individual Consult IDA / D7340 Post Direct 32,340.00 32,340.00 Signed 2022-04-18 2022-05-19 2022-04-28 2022-06-13 2022-05-19 2022-06-14 2022-06-23 2022-06-25 2022-12-20 untant for AFAP d the Promotion of a Safe Sc ant Selection hool Environment Empowering Girls through th 57/C/GEE/2022 / Specialist i e Acquisition of Life Skills an Individual Consult n Environmental and Social S IDA / D7340 Post Direct 44,465.76 0.00 Under Review 2022-04-18 2022-05-20 2022-04-28 2022-05-19 2022-06-23 2022-12-20 d the Promotion of a Safe Sc ant Selection afeguards for AFAP hool Environment Empowering Girls through th 47/C/GEE/2022 / TA to imple e Acquisition of Life Skills an ment the Girls' Empweremen IDA / D7340 Post Direct Selection Direct 761,584.00 726,207.00 Signed 2022-06-28 2022-05-10 2022-07-08 2022-05-19 2022-09-11 2022-06-03 2023-03-10 d the Promotion of a Safe Sc t Program hool Environment Project Coordination, Monito 67/C/GEE/2022 / Project Audi Direct - Internation Pending Impleme TF / B3318 ring and Evaluation, and Cap Post Direct Selection 19,000.00 0.00 2022-11-11 2022-11-21 2023-01-25 2023-07-24 t al ntation acity Building Project Coordination, Monito 76/C/GEE/2023 / Hiring a GB Individual Consult IDA / D7340 ring and Evaluation, and Cap Post Limited 32,000.00 0.00 Canceled 2023-04-05 2023-04-10 2023-05-01 2023-06-05 2023-12-02 V specialist (4.4.1) ant Selection acity Building Project Coordination, Monito 77/C/GEE/2023 / Hiring a GB IDA / D7340 ring and Evaluation, and Cap Post Direct Selection Direct - National 32,000.00 0.00 Signed 2023-05-10 2023-05-02 2023-05-20 2023-05-03 2023-07-24 2024-01-20 V specialist (4.4.1) acity Building 80/C/GEE/2023 / Data Cente Project Coordination, Monito r Design and Specifications f Individual Consult Under Implement TF / B3318 ring and Evaluation, and Cap Post Limited 5,000.00 0.00 2023-06-13 2023-06-01 2023-06-18 2023-07-09 2023-08-13 2024-02-09 or Ministry of Education of Sa ant Selection ation acity Building o Tome and Principe Page 4 PROCUREMENT PLAN (Textual Part) Project information: [Pakistan] Balochistan Human Capital Investment Project (BHCIP) P166308 Project Implementation agency: (i) Secondary Education Department (SED) and; (ii) Health Department Date of the Procurement Plan: May 2021 Period covered by this Procurement Plan: May 2021 November 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Khyber Pakhtunkhwa Public Procurement Rules ( as amended from time to time), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 2) For national open competitive procurement, only the model procurement documents acceptable to the World Bank, shall be used. 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 5) Access to procurement opportunities shall not be restricted to firms that have pre-registered and/or paid a registration fee. 6) No preference of any kind shall be given to national bidders in the bidding process. 7) When using any method other than single-stage single envelope on compliance-based evaluation criteria, Bank’s prior concurrence shall be mandatory When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact- finding activities undertaken by the Bank or persons appointed by the Bank to address specific the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Pakistan : Balochistan Human Capital Investment Project PLAN General Information Country: Pakistan 2021-05-21 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166308 GPN Date: Project Name: Balochistan Human Capital Investment Project Loan / Credit No: IDA / 67130 Health Department Government of Balochistan Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-HD-GOB-249263-CW-RFB Request for B / Renovation and repair of Gy ids - Small W 1. Improving utilization of qu Single Stage - One E 2022-08-0 nae Ward, OT, Labor Room, R IDA / 67130 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-11-11 2021-11-14 2021-12-04 2021-12-18 2022-01-07 ality health services nvelope 5 ecovery Room and Female O nvelope proc PD of THQ hospital, Mufti Me ess) hmood Quetta PK-HD-GOB-249270-CW-RFB / Renovation and repair of Gy nae Ward, OT, Labor Room, R Request for B ecovery Room and Female O ids - Small W 1. Improving utilization of qu Single Stage - One E 2022-10-0 PD of DHQ hospital. Construc IDA / 67130 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-11-11 2021-11-14 2021-12-04 2021-12-18 2022-01-07 ality health services nvelope 4 tion of accommodation for fe nvelope proc male health care provider in ess) DHQ hospital 10 rooms. Bloo d bank and upgradation of B HU to RHC for District Chaghi . PK-HD-GOB-249288-CW-RFB Request for B / Renovation and repair of Gy ids - Small W nae Ward, OT, Labor Room, R 1. Improving utilization of qu Single Stage - One E 2022-10-0 IDA / 67130 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-11-11 2021-11-14 2021-12-04 2021-12-18 2022-01-07 ecovery Room and Female O ality health services nvelope 4 nvelope proc PD,DHQ hospital and upgrad ess) ation of BHU to RHC District Chaman PK-HD-GOB-249292-CW-RFB Request for B / Renovation and repair of Gy ids - Small W 1. Improving utilization of qu Single Stage - One E 2022-10-0 nae Ward, OT, Labor Room, R IDA / 67130 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-11-11 2021-11-14 2021-12-04 2021-12-18 2022-01-07 ality health services nvelope 4 ecovery Room, and Female O nvelope proc PD DHQ Hospital District Pish ess) in Request for B PK-HD-GOB-249294-CW-RFB ids - Small W / Rehabilitation of others facil 1. Improving utilization of qu Single Stage - One E 2022-08-0 IDA / 67130 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-11-11 2021-11-14 2021-12-04 2021-12-18 2022-01-07 ities in the clusters District C ality health services nvelope 5 nvelope proc haghi & Killa Abdullah ess) Request for B PK-HD-GOB-332768-CW-RFB ids - Small W 1. Improving utilization of qu Single Stage - One E 2023-08-1 / Chaghi Works Construction IDA / 67130 Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-12-26 2022-12-30 2022-12-31 2022-12-31 2023-01-15 2023-01-17 2023-01-25 2023-02-16 2023-02-14 ality health services nvelope 3 Package-1 nvelope proc ess) Request for B PK-HD-GOB-332772-CW-RFB 1. Improving utilization of qu Single Stage - One E ids - Small W 2023-08-1 / Chaghi Construction Work P IDA / 67130 Post Request for Bids Open - National 0.00 Signed 2022-12-26 2022-12-30 2022-12-31 2022-12-31 2023-01-15 2023-01-17 2023-01-25 2023-02-16 2023-02-14 ality health services nvelope orks SPD (1 e 3 ackage -2 nvelope proc ess) Request for B PK-HD-GOB-340421-CW-RFB ids - Small W / District Quetta Package-1 C 1. Improving utilization of qu Single Stage - One E Under Imple 2024-06-3 IDA / 67130 Post Request for Bids Open - National orks SPD (1 e 0.00 2023-03-01 2023-06-26 2023-03-06 2023-06-26 2023-03-21 2023-04-05 2023-05-10 onstruction & Rehabilitation ality health services nvelope mentation 0 nvelope proc works of Health Facilities ess) Request for B PK-HD-GOB-340424-CW-RFB ids - Small W / District Quetta Package-2 C 1. Improving utilization of qu Single Stage - One E Under Imple 2024-06-1 IDA / 67130 Post Request for Bids Open - National orks SPD (1 e 0.00 2023-02-10 2023-02-09 2023-02-15 2023-02-10 2023-03-02 2023-02-27 2023-03-22 2023-04-19 2023-04-26 onstruction & Rehabilitation ality health services nvelope mentation 6 nvelope proc works of Health Facilities ess) Request for B PK-HD-GOB-340430-CW-RFB ids - Small W / District Pishin Package-1 Co 1. Improving utilization of qu Single Stage - One E Under Imple 2024-06-1 IDA / 67130 Post Request for Bids Open - National orks SPD (1 e 0.00 2023-02-10 2023-02-09 2023-02-15 2023-02-10 2023-03-02 2023-02-27 2023-03-22 2023-04-19 2023-04-26 nstruction & Rehabilitation w ality health services nvelope mentation 6 nvelope proc orks of Health Facilities ess) Request for B PK-HD-GOB-340433-CW-RFB ids - Small W / District Pishin Package-2 Co 1. Improving utilization of qu Single Stage - One E Under Imple 2024-06-1 IDA / 67130 Post Request for Bids Open - National orks SPD (1 e 0.00 2023-02-10 2023-02-09 2023-02-15 2023-02-10 2023-03-02 2023-03-06 2023-03-22 2023-04-19 2023-04-26 nstruction & Rehabilitation w ality health services nvelope mentation 6 nvelope proc orks of Health Facilities ess) Request for B PK-HD-GOB-340434-CW-RFB ids - Small W / District Killa Abdullah Packa 1. Improving utilization of qu Single Stage - One E Under Imple 2024-06-1 IDA / 67130 Post Request for Bids Open - National orks SPD (1 e 0.00 2023-02-10 2023-02-09 2023-02-15 2023-02-10 2023-03-02 2023-02-27 2023-03-22 2023-04-19 2023-04-26 ge-1 Construction & Rehabilit ality health services nvelope mentation 6 nvelope proc ation works of Health Facilitie ess) s Request for B PK-HD-GOB-340437-CW-RFB ids - Small W / District Killa Abdullah Packa 1. Improving utilization of qu Single Stage - One E Under Imple 2024-06-1 IDA / 67130 Post Request for Bids Open - National orks SPD (1 e 0.00 2023-02-10 2023-02-09 2023-02-15 2023-02-10 2023-03-02 2023-02-27 2023-03-22 2023-04-19 2023-04-26 ge-2 Construction & Rehabilit ality health services nvelope mentation 6 nvelope proc ation works of Health Facilitie ess) s Request for PK-HD-GOB-342485-CW-RFQ Quotations - / Repair & Maintenance for St 1. Improving utilization of qu Request for Quota Single Stage - One E Small Works Under Imple 2023-11-0 IDA / 67130 Post Open - National 0.00 2023-04-01 2023-05-30 2023-05-11 rengthening Teaching / Traini ality health services tions nvelope (Emergency) mentation 7 ng Institutes of Paramedics SPD -Compet itive Request for PK-HD-GOB-364389-CW-RFQ Quotations - 1. Improving utilization of qu Request for Quota Single Stage - One E Pending Imp 2023-11-1 / Repair & Renovation of MIS IDA / 67130 Post Open - National Small Works 0.00 2023-07-01 2023-08-12 ality health services tions nvelope lementation 0 Rooms of DGHS. (Emergency) SPD -Compet itive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-HD-GOB-249295-GO-RFB / Provision of GPS enabled s mart phones to healthcare pr 1. Improving utilization of qu Single Stage - One E Pending Impl IDA / 67130 Post Request for Bids Open - National 0.00 2021-11-01 2021-11-08 2021-12-08 2021-12-20 2022-01-05 2022-05-05 oviders (in charge of HF) for r ality health services nvelope ementation eporting of staff presence/pe rformance in real time in all HFs in project districts Page 1 PK-HD-GOB-249298-GO-RFB 1. Improving utilization of qu Single Stage - One E / Purchases PF Ambulances f IDA / 67130 Post Request for Bids Open - National 961,301.62 Signed 2022-02-02 2022-03-16 2022-02-07 2022-03-18 2022-03-09 2022-04-21 2022-03-29 2022-05-13 2022-04-14 2022-06-18 2022-10-11 ality health services nvelope or PHC facilities for all project district PK-HD-GOB-306784-GO-RFQ 1. Improving utilization of qu Request for Quota Single Stage - One E / Procurement of Laptops & P IDA / 67130 Post Limited 13,130.51 Signed 2022-08-03 2022-08-06 2022-08-31 2022-09-07 2022-09-16 ality health services tions nvelope rinter for PMU staff. PK-HD-GOB-307507-GO-RFQ 1. Improving utilization of qu Request for Quota Single Stage - One E IDA / 67130 Post Limited 47,268.59 Signed 2022-08-08 2022-08-11 2022-09-02 2022-09-01 2022-10-22 / Purchase of vehicle for BHCI ality health services tions nvelope P health PK-HD-GOB-314145-GO-RFQ 1. Improving utilization of qu Request for Quota Single Stage - One E / Furniture's for Health Facilit IDA / 67130 Post Limited 0.00 Signed 2022-09-13 2022-09-12 2022-11-08 2023-03-08 ality health services tions nvelope ies of BHCIP PK-HD-GOB-314642-GO-RFQ 1. Improving utilization of qu Request for Quota Single Stage - One E / Package (1) Medicines For IDA / 67130 Post Limited 0.00 Signed 2022-09-10 2022-09-08 2022-09-12 2022-09-19 ality health services tions nvelope Flood Emergency Medical Rel ief Camps PK-HD-GOB-314652-GO-RFQ 1. Improving utilization of qu Request for Quota Single Stage - One E / Package (3) HFs Flood Resp IDA / 67130 Post Limited 0.00 Signed 2022-09-29 2022-11-16 2022-10-09 2022-10-23 ality health services tions nvelope onse Medicines PK-HD-GOB-314656-GO-RFQ 1. Improving utilization of qu Request for Quota Single Stage - One E / Package (2) Flood Emergen IDA / 67130 Post Limited 0.00 Signed 2022-09-20 2022-11-16 2022-10-04 2022-11-08 ality health services tions nvelope cy Medical Relief Equipment' s PK-HD-GOB-320585-GO-RFB 1. Improving utilization of qu Single Stage - One E / Medicines for all Health Faci IDA / 67130 Post Request for Bids Open - National 0.00 Signed 2022-10-20 2022-10-24 2022-10-25 2022-11-03 2022-11-24 2022-11-28 2022-12-08 2022-12-09 2023-01-02 2023-04-02 ality health services nvelope lities and in Patient Medicine s for DHQs PK-HD-GOB-320731-GO-RFB 1. Improving utilization of qu Single Stage - One E / Medical Equipment's for BH IDA / 67130 Post Request for Bids Open - National 0.00 Signed 2022-10-20 2022-11-01 2022-10-25 2022-11-03 2022-11-24 2022-12-05 2022-12-08 2023-01-10 2023-01-02 2023-07-01 ality health services nvelope Us & DHQ PK-HD-GOB-320737-GO-RFQ 1. Improving utilization of qu Request for Quota Single Stage - One E IDA / 67130 Post Limited 0.00 Signed 2022-10-22 2022-12-05 2022-11-21 2023-01-20 / Environment related items f ality health services tions nvelope or HFs PK-HD-GOB-324310-GO-RFB 1. Improving utilization of qu Single Stage - One E / Solarization of DHQs/THQs IDA / 67130 Post Request for Bids Open - National 0.00 Signed 2022-11-07 2022-12-06 2022-11-22 2022-12-06 2022-11-27 2022-12-22 2022-12-02 2023-03-07 2022-12-12 2023-03-12 ality health services nvelope of BHCIP District. PK-HD-GOB-340390-GO-RFQ 1. Improving utilization of qu Request for Quota Single Stage - One E / IT Equipment's for Strength IDA / 67130 Post Open - National 0.00 Signed 2023-02-25 2023-03-11 2023-03-26 2023-06-24 ality health services tions nvelope ening Teaching / Training PK-HD-GOB-340414-GO-RFQ / Office Equipment Strengthe 1. Improving utilization of qu Request for Quota Single Stage - One E IDA / 67130 Post Open - National 0.00 Signed 2023-02-27 2023-03-11 2023-03-28 2023-06-26 ning Teaching / Training Insti ality health services tions nvelope tutes of Paramedics PK-HD-GOB-340412-GO-RFQ / Medical Equipment Strengt 1. Improving utilization of qu Request for Quota Single Stage - One E IDA / 67130 Post Open - National 0.00 Signed 2023-02-27 2023-04-05 2023-03-28 2023-06-26 hening Teaching / Training In ality health services tions nvelope stitutes of Paramedics PK-HD-GOB-340389-GO-RFQ 1. Improving utilization of qu Request for Quota Single Stage - One E / Furniture for Strengthening IDA / 67130 Post Open - National 0.00 Signed 2023-02-25 2023-03-11 2023-03-26 2023-06-24 ality health services tions nvelope Teaching / Training Institutes of Paramedics PK-HD-GOB-363173-GO-RFQ 1. Improving utilization of qu Request for Quota Single Stage - One E Under Imple IDA / 67130 Post Open - National 0.00 2023-06-03 2023-05-29 2023-06-30 2023-07-30 / CMWs Equipment & Medicin ality health services tions nvelope mentation es PK-HD-GOB-332780-GO-RFQ 1. Improving utilization of qu Request for Quota Single Stage - One E Under Imple / GPS Enable Tabs & Devices IDA / 67130 Post Limited 0.00 2023-01-02 2023-05-29 2023-02-04 2023-05-05 ality health services tions nvelope mentation and Software's PK-HD-GOB-364348-GO-RFQ 1. Improving utilization of qu Request for Quota Single Stage - One E Pending Impl / Printing DHIS Registers ,Tic IDA / 67130 Post Open - National 0.00 2023-06-07 2023-07-24 2023-10-22 ality health services tions nvelope ementation kets and Files for BHCIP Distr icts PK-HD-GOB-364367-GO-DIR 1. Improving utilization of qu Pending Impl / Ambulance for newly added IDA / 67130 Post Direct Selection Direct - National 0.00 2023-06-07 2023-06-12 2023-07-10 2023-11-07 ality health services ementation health facility. PK-HD-GOB-364392-GO-RFQ 1. Improving utilization of qu Request for Quota Single Stage - One E Pending Impl / IT Equipment for establishm IDA / 67130 Post Open - National 0.00 2023-07-01 2023-07-28 2023-10-26 ality health services tions nvelope ementation ent of DGHS MIS Control Roo m NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-HD-GOB-295770-NC-RFQ / Hiring of Firm for design/ma 1. Improving utilization of qu Request for Quota Single Stage - One E intain the website structure, IDA / 67130 Post Limited 3,979.65 Signed 2022-05-30 2022-05-27 2022-07-23 2022-08-06 2025-06-28 ality health services tions nvelope uploading/update contents a nd maintenance of the BHCIP health component website. PK-HD-GOB-329829-NC-RFB 1. Improving utilization of qu Single Stage - One E / Patient Transfer Services Fo IDA / 67130 Post Request for Bids Open - National 0.00 Canceled 2022-12-07 2022-12-16 2022-12-12 2022-12-17 2022-12-27 2023-01-03 2023-01-17 2025-06-27 ality health services nvelope r RMNCH In Four Districts of Balochistan PK-HD-GOB-340362-NC-DIR / Hiring services of Medical Em 1. Improving utilization of qu ergency Response Centers ( IDA / 67130 Post Direct Selection Direct - National 0.00 Signed 2023-02-10 2023-02-17 2023-02-15 2023-02-17 2023-02-28 2025-06-30 ality health services MERC) for patient referral am bulance service in four distric ts of BHCIP PK-HD-GOB-364357-NC-RFQ 1. Improving utilization of qu Request for Quota Single Stage - One E Pending Impl IDA / 67130 Post Open - National 0.00 2023-06-12 2023-08-03 2023-12-31 / Digital HRH Database activi ality health services tions nvelope ementation ty CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Page 2 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-HD-GOB-249316-CS-QCB S / Awareness raising, comm 1. Improving utilization of qu Quality And Cost- Under Implement IDA / 67130 Post Open - National 0.00 2022-03-01 2022-06-11 2022-03-10 2022-07-07 2022-04-25 2022-10-22 2022-05-15 2022-11-22 2022-05-17 2023-03-08 2022-06-17 2023-04-11 2022-07-03 2024-07-22 unity outreach, including citiz ality health services Based Selection ation en engagement and grievanc e redress system PK-HD-GOB-249646-CS-LCS / 1. Improving utilization of qu Least Cost Selecti Pending Impleme Internal Audit Firm for the pr IDA / 67130 Post Open - National 0.00 2022-03-08 2022-03-18 2022-04-25 2022-05-05 2022-05-16 2022-06-10 2022-07-01 2025-06-25 ality health services on ntation oject activities PK-HD-GOB-249648-CS-LCS / 1. Improving utilization of qu Least Cost Selecti Pending Impleme Development of digital HRH IDA / 67130 Post Open - National 0.00 2022-02-01 2022-02-10 2022-03-17 2022-04-04 2022-04-07 2022-05-02 2022-05-24 2024-05-23 ality health services on ntation database for health PK-HD-GOB-324308-CS-CQS / Development & Assessment 1. Improving utilization of qu Consultant Qualifi of innovative technology bas IDA / 67130 Post Limited 0.00 Signed 2022-11-02 2022-12-02 2022-11-17 2023-01-11 2022-11-24 2023-02-13 2022-12-09 2024-12-08 ality health services cation Selection ed assessment of provider kn owledge and competences. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-HD-GOB-233386-CS-INDV 1. Improving utilization of qu Individual Consult IDA / 67130 Post Open 40,622.70 Signed 2021-05-17 2021-05-28 2021-05-29 2021-07-16 2021-06-01 2021-07-19 2021-06-05 2021-07-20 2025-12-31 / Hiring of Procurement Speci ality health services ant Selection alist. PK-HD-GOB-233410-CS-INDV 1. Improving utilization of qu Individual Consult / Hiring of Financial Manage IDA / 67130 Post Open 40,625.03 Signed 2021-05-17 2021-05-26 2021-05-29 2021-07-16 2021-06-01 2021-07-19 2021-06-05 2021-07-27 2025-12-31 ality health services ant Selection ment Specialist PK-HD-GOB-249334-CS-INDV 1. Improving utilization of qu Individual Consult IDA / 67130 Post Open 1,885.78 Signed 2021-10-22 2022-01-02 2021-12-01 2022-02-17 2021-12-03 2022-02-18 2021-12-08 2022-03-03 2025-06-30 / Hiring of Health Specialist ality health services ant Selection PK-HD-GOB-249345-CS-INDV 1. Improving utilization of qu Individual Consult / Health and Nutrition Educat IDA / 67130 Post Open 1,881.22 Signed 2021-10-22 2022-01-02 2021-12-01 2022-02-16 2021-12-03 2022-02-18 2021-12-08 2022-02-19 2025-06-30 ality health services ant Selection ion (SBCC) Specialist PK-HD-GOB-249348-CS-INDV 1. Improving utilization of qu Individual Consult IDA / 67130 Post Open 1,478.10 Signed 2021-10-22 2022-01-02 2021-12-01 2022-02-15 2021-12-03 2022-02-15 2021-12-08 2022-02-17 2025-06-30 / M&E Specialist ality health services ant Selection PK-HD-GOB-269767-CS-INDV 1. Improving utilization of qu Individual Consult IDA / 67130 Post Open 1,914.14 Signed 2021-12-29 2021-12-22 2022-01-24 2022-02-15 2022-01-26 2022-04-03 2022-02-03 2022-02-17 2025-06-30 / Hiring of Development Cons ality health services ant Selection ultant PK-HD-GOB-307494-CS-CDS 1. Improving utilization of qu / EDS&QA firm for the BHCIP IDA / 67130 Post Direct Selection Direct - National 74,326.27 Signed 2022-08-03 2022-08-11 2022-08-04 2022-08-11 2022-08-15 2022-08-23 2024-09-30 ality health services Health component. PK-HD-GOB-324301-CS-INDV 1. Improving utilization of qu Individual Consult IDA / 67130 Post Limited 0.00 Canceled 2022-11-02 2022-11-14 2022-11-17 2022-11-14 2022-11-19 2022-11-24 2022-11-29 2025-06-30 / Hiring of Health Specialist ality health services ant Selection PK-HD-GOB-324335-CS-CDS 1. Improving utilization of qu Under Implement / Managed solution for compl IDA / 67130 Post Direct Selection Direct - National 0.00 2022-11-03 2023-03-11 2022-11-07 2023-03-21 2022-12-07 2025-06-30 ality health services ation aints recording from PTCL PK-HD-GOB-340345-CS-INDV 1. Improving utilization of qu Individual Consult / Hiring of Health & Educatio IDA / 67130 Post Limited 0.00 Signed 2023-02-08 2023-02-13 2023-02-23 2023-02-15 2023-02-25 2023-02-20 2023-03-04 2025-06-30 ality health services ant Selection n Specialist BHCIP Health Co mponent PK-HD-GOB-342496-CS-INDV 1. Improving utilization of qu Individual Consult / Hiring of Health Specialist f IDA / 67130 Post Limited 0.00 Signed 2023-02-16 2023-02-22 2023-02-21 2023-04-04 2023-02-28 2023-04-11 2023-03-12 2025-06-30 ality health services ant Selection or the BHCIP Health Compon ent Page 3 PROCUREMENT PLAN (Textual Part) Project information: Burundi COVID19 Project (P173845) Project Implementation agency: Ministry of Finance Date of the Procurement Plan: April 22, 2020 Period covered by this Procurement Plan: April 2020 – July 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the country procurement handbook, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. - The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. - Rights for the Bank to review procurement documentation and activities. - An effective complaints mechanism. - Maintenance of records of the Procurement Process When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable Works: Not Applicable Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. As specified under World Bank Operations to Address COVID-19 PROCUREMENT Burundi : Burundi COVID19 Preparedness and Response Project PLAN General Information Country: Burundi 2022-11-04 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173845 GPN Date: Project Name: Burundi COVID19 Preparedness and Response Project Loan / Credit No: IDA / D9640, IDA / D6160 Ministry of Health and Fight against Aids Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Quota BI-MOH-323410-CW-RFQ / A Emergency COVID-19 Respo Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-07-2 ménagement de deux abris d IDA / D9640 Post Limited 40,000.00 0.00 2022-11-27 2023-01-22 nse tions nvelope s (Emergency) SP lementation 1 es unités de production d'oxy D -Competitive gène Request for Bids - BI-MOH-323436-CW-RFB / C Emergency COVID-19 Respo Single Stage - One E Small Works SPD Under Imple 2024-03-0 onstruction de 5 incinérateur IDA / D9640 Post Request for Bids Open - National 186,677.00 0.00 2022-11-15 2023-06-02 2022-11-20 2023-06-02 2023-01-01 2023-01-31 2023-03-07 nse nvelope (1 envelope proce mentation 1 s type Montfort et ouvrages c ss) onnexes GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BI-BI-MOF-282012-GO-RFB / Emergency COVID-19 Respo Single Stage - One E Acquisition de lits pour les hô IDA / D9640 Post Request for Bids Open - National 533,000.00 0.00 Signed 2022-11-15 2022-11-10 2022-11-20 2022-11-10 2023-01-01 2023-01-30 2023-01-17 2023-01-30 2023-02-07 2023-06-07 nse nvelope pitaux (10 lits par hôpital) BI-BI-MOF-282016-GO-RFB / Acquisition des respirateurs, Emergency COVID-19 Respo Open - Internationa Single Stage - One E Under Imple IDA / D9640 Post Request for Bids 1,410,000.00 0.00 2022-11-22 2022-11-10 2022-11-27 2022-11-10 2023-01-08 2022-12-30 2023-01-24 2023-02-21 2023-07-21 bonbonnes et leurs accessoir nse l nvelope mentation es pour les hôpitaux commu naux BI-MOH-323432-GO-RFB / Ac quisition des réactifs d'amplif ication et d'extraction pour l Emergency COVID-19 Respo Single Stage - One E Pending Impl IDA / D9640 Post Request for Bids Open - National 690,740.00 0.00 2023-01-10 2023-01-15 2023-02-26 2023-03-28 2023-05-02 2023-10-29 e diagnostic de la COVID-19 nse nvelope ementation pour les laboratoires + kits d e contrôle et autres consom mables BI-MOH-323441-GO-RFB / Ac hat de matériel pour la gesti Emergency COVID-19 Respo Single Stage - One E Under Imple on des déchets en faveur des IDA / D9640 Post Request for Bids Open - National 252,878.00 0.00 2023-01-25 2023-04-26 2023-01-30 2023-04-26 2023-03-13 2023-04-12 2023-05-17 2023-08-15 nse nvelope mentation structures des soins (pour 4 8 sites de vaccination) BI-MOH-323442-GO-RFQ / Ac quisition des équipements de Emergency COVID-19 Respo Request for Quota Single Stage - One E protection individuelle (EPI) e IDA / D9640 Post Limited 25,475.00 0.00 Canceled 2023-01-15 2023-03-12 2023-05-11 nse tions nvelope t de produits de désinfection pour les structures de soins BI-MOH-323450-GO-RFB / Ac hat de matériel informatique Emergency COVID-19 Respo Single Stage - One E Pending Impl pour COUSP, les centres d' a IDA / D9640 Post Request for Bids Open - National 196,224.00 0.00 2022-12-14 2022-12-19 2023-01-30 2023-03-01 2023-04-05 2023-06-04 nse nvelope ementation lerte et de réponse précoce, pour collecte des données et pour l' équipe du projet BI-MOH-323456-GO-RFB / Ac Emergency COVID-19 Respo Single Stage - One E quisition les imprimés pour la IDA / D9640 Post Request for Bids Open - National 102,421.00 0.00 Canceled 2023-02-07 2023-02-12 2023-03-26 2023-04-25 2023-05-30 2023-11-26 nse nvelope collecte des données BI-MOH-323459-GO-RFB / Ac Emergency COVID-19 Respo Single Stage - One E Under Imple hat d'un véhicule pour la sup IDA / D9640 Post Request for Bids Open - National 572,230.00 0.00 2022-11-15 2023-03-02 2022-11-20 2023-03-07 2023-01-01 2023-01-31 2023-03-07 2023-06-05 nse nvelope mentation ervision du projet BI-MOH-323462-GO-RFQ / Ac Emergency COVID-19 Respo Request for Quota Single Stage - One E Pending Impl quisition du mobilier pour le IDA / D9640 Post Limited 8,341.00 0.00 2022-11-27 2023-01-22 2023-07-21 nse tions nvelope ementation personnel du projet BI-MOH-323945-GO-RFB / Ac quisition d' équipement infor Emergency COVID-19 Respo Single Stage - One E Pending Impl IDA / D9640 Post Request for Bids Open - National 148,537.00 0.00 2022-12-21 2022-12-26 2023-02-06 2023-03-08 2023-04-12 2023-07-11 matique pour centres d'alert nse nvelope ementation e et de réponse précoce des 14 DS pilotes BI-BI-MOF-282008-GO-RFB / Acquisition de 20 ambulance Supporting National and Sub Open - Internationa Single Stage - One E Under Imple s médicalisées pour les hôpit IDA / D9640 -national, Prevention and Pr Post Request for Bids 2,900,000.00 0.00 2022-11-18 2022-11-10 2022-11-23 2022-11-10 2023-01-04 2022-12-30 2023-01-13 2023-01-28 2023-02-10 2023-07-10 l nvelope mentation aux et 30 ambulances non m eparedness édicalisées pour les hôpitaux BI-BI-MOF-282092-GO-RFQ / Acquisition des équipements Emergency COVID-19 Respo Request for Quota Single Stage - One E Pending Impl requis pour les centres de pri IDA / D9640 Post Limited 45,720.00 0.00 2023-03-12 2023-04-28 2023-07-27 nse tions nvelope ementation se en charge (oxymètres de pouls, scopes, et autres) BI-BI-MOF-282025-GO-RFB / Achat des médicaments pour Emergency COVID-19 Respo Single Stage - One E IDA / D9640 Post Request for Bids Open - National 514,940.00 0.00 Signed 2022-11-18 2022-11-10 2022-11-23 2022-11-10 2023-01-04 2022-12-30 2023-01-20 2023-01-30 2023-02-17 2023-05-18 les centres/unités de prise en nse nvelope charge des cas de COVID-19 BI-BI-MOF-282007-GO-RFB / Emergency COVID-19 Respo Single Stage - One E Pending Impl Acquisition des autres intrant IDA / D9640 Post Request for Bids Open - National 211,814.00 0.00 2023-02-07 2023-02-12 2023-03-26 2023-04-11 2023-05-09 2023-08-07 nse nvelope ementation s vaccinaux BI-MOH-325356-GO-RFB / Ex tension du centre d'alerte et Emergency COVID-19 Respo Single Stage - One E Pending Impl de réponse précoce sur 14 D IDA / D9640 Post Request for Bids Open - National 148,537.00 0.00 2023-01-10 2023-01-15 2023-02-26 2023-03-28 2023-05-02 2023-07-31 nse nvelope ementation S pilotes par fourniture d' éq uipement informatique Page 1 BI-BI-MOF-282021-GO-RFB / Emergency COVID-19 Respo Single Stage - One E Under Imple Acquisition de concentrateur IDA / D9640 Post Request for Bids Open - National 240,000.00 0.00 2023-02-16 2023-03-02 2023-02-21 2023-03-06 2023-04-04 2023-04-20 2023-05-11 2023-08-09 nse nvelope mentation d' oxygène pour les FOSA BI-BI-MOF-282015-GO-RFB / Supporting National and Sub Open - Internationa Single Stage - One E Under Imple Acquisition d'unités de radiol IDA / D9640 -national, Prevention and Pr Post Request for Bids 1,500,000.00 0.00 2022-11-18 2022-11-10 2022-11-23 2022-12-20 2023-01-04 2023-02-03 2023-03-25 2023-09-21 l nvelope mentation ogie pour les hôpitaux (1 unit eparedness é par hôpital) BI-BI-MOF-282082-GO-RFQ / Acquisition du matériel de so norisation (haut-parleur, mix Emergency COVID-19 Respo Single Stage - One E Pending Impl IDA / D9640 Post Request for Bids Open - National 25,024.00 0.00 2023-02-14 2023-02-19 2023-04-02 2023-04-18 2023-05-09 2023-08-07 eur, microphone), d'un appar nse nvelope ementation eil photo-numérique, d'un en registreur et autres matériels associés BI-MOH-346412-GO-DIR / Ac quisition de 6 unités de prod Emergency COVID-19 Respo Direct - Internation Under Imple IDA / D9640 Prior Direct Selection 3,604,103.00 0.00 2023-04-03 2023-04-05 2023-04-18 2023-04-11 2023-05-26 2023-11-22 uction d'oxygène, 45 réfrigér nse al mentation ateurs solaires et consomma bles de laboratoires BI-MOH-323389-GO-DIR / Ac Emergency COVID-19 Respo Direct - Internation quisition de (2) deux unités p IDA / D9640 Post Direct Selection 900,655.00 0.00 Canceled 2022-12-09 2022-12-14 2023-01-18 2023-07-17 nse al our la production d' oxygène BI-BI-MOF-282031-GO-RFB / Acquisition des tests de dépi Emergency COVID-19 Respo Open - Internationa Single Stage - One E IDA / D9640 Prior Request for Bids 7,200,000.00 0.00 Canceled 2022-07-29 2022-08-03 2022-09-14 2022-09-30 2022-10-28 2023-02-13 stage rapide de la COVID-19 nse l nvelope pour les laboratoires BI-BI-MOF-282036-GO-DIR / Emergency COVID-19 Respo Direct - Internation Entente Directe avec UNICEF IDA / D9640 Post Direct Selection 2,376,000.00 0.00 Canceled 2022-12-13 2022-12-18 2023-01-15 2023-07-14 nse al pour l'acquisition des cartouc hes GeneXpert, BI-BI-MOF-282045-GO-DIR / Entente Directe avec l'UNICE F pour l'acquisition et l'install Emergency COVID-19 Respo Direct - Internation IDA / D9640 Post Direct Selection 196,750.00 0.00 Canceled 2022-12-21 2022-12-26 2023-01-24 2023-07-23 ation des équipements néces nse al saires (chambre froide, réfrig érateurs, congelateurs, glaci ères) ainsi que leur entretien BI-MOH-346748-GO-RFQ / Ac Implementation Managemen Request for Quota Single Stage - One E quisition des imprimés pour l IDA / D9640 t and Monitoring and Evaluat Post Limited 25,000.00 0.00 Signed 2023-03-20 2023-03-10 2023-04-24 2023-05-15 tions nvelope a collecte des données ion NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BI-MOH-315987-CS-LCS / Au Implementation Managemen dit comptable et financier du Least Cost Selecti Open - Internationa Pending Impleme IDA / D9640 t and Monitoring and Evaluat Post 20,000.00 0.00 2022-11-15 2022-12-06 2023-01-19 2023-02-16 2023-03-18 2023-04-22 2023-05-27 2024-10-18 projet pour la période de ju on l ntation ion illet 2022 à juin 2024 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BI-MOH-323787-CS-INDV / R Emergency COVID-19 Respo Individual Consult Under Implement ecrutement par entente direc IDA / D9640 Post Direct - National 24,000.00 0.00 2022-12-02 2022-11-15 2022-12-12 2022-11-18 2023-01-02 2023-02-06 2024-02-01 nse ant Selection ation te d' une assistante comptabl e du projet BI-MOH-323776-CS-INDV / R Emergency COVID-19 Respo Individual Consult Under Implement ecrutement par entente direc IDA / D9640 Post Direct - National 30,000.00 0.00 2022-12-02 2022-11-15 2022-12-12 2022-11-18 2023-01-02 2023-02-06 2024-02-01 nse ant Selection ation te du Directeur Technique du Projet BI-BI-MOF-307289-CS-CDS / Implementation Managemen Entente Directe avec le bure Direct - Internation Pending Impleme IDA / D6160 t and Monitoring and Evaluat Post Direct Selection 10,000.00 0.00 2022-11-18 2022-11-28 2022-12-25 2023-02-23 au IAC pour l'audit comptabl al ntation ion e et financier exercice du 01/ 07/2021 au 30/09/2022 BI-BI-MOF-301761-CS-INDV / Implementation Managemen Individual Consult Recrutement d'un Expert en IDA / D9640 t and Monitoring and Evaluat Post Open 24,000.00 0.00 Canceled 2022-07-15 2022-09-29 2022-09-02 2022-09-23 2022-10-28 2023-10-27 ant Selection sauvegardes sociales ion BI-BI-MOF-301757-CS-INDV / Implementation Managemen Individual Consult Recrutement d'un Expert en IDA / D9640 t and Monitoring and Evaluat Post Open 24,000.00 0.00 Canceled 2022-07-15 2022-10-17 2022-09-02 2022-09-23 2022-10-28 2023-10-27 ant Selection suivi-évaluation ion BI-MOH-354582-CS-INDV / C Implementation Managemen onsultant(e) pour une analys Individual Consult Under Implement IDA / D9640 t and Monitoring and Evaluat Post Open - National 15,000.00 0.00 2023-04-10 2023-04-10 2023-05-19 2023-06-02 2023-07-07 2023-08-06 e des répartitions des charge ant Selection ation ion s communes des différents p rojets BI-MOH-363224-CS-INDV / R Implementation Managemen ecrutement d'un (e) assistant Individual Consult Under Implement IDA / D9640 t and Monitoring and Evaluat Post Open - National 24,000.00 0.00 2023-05-30 2023-06-22 2023-07-02 2023-07-16 2023-08-13 2024-08-07 (e) préposé (e) à l'archivage ant Selection ation ion physique et électronique Page 2 PROCUREMENT PLAN (Textual Part) Project information: Republic of Congo Education Sector Support Project P152910 Project Implementation agency: [insert legal name] Date of the Procurement Plan: [insert date] Period covered by this Procurement Plan: [insert from – to period] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Congo, Republic of : Congo - Education Sector Support Project PLAN General Information Country: Congo, Republic of 2017-09-26 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P152910 GPN Date: Project Name: Congo - Education Sector Support Project Loan / Credit No: IDA / V0020, IDA / 58060 Education Sector Support Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRAASED-001-F-CF / matérie l informatique et mobilier- a Request for Quota Single Stage - One E IDA / V0020 Unallocated Post Limited 80,000.00 0.00 Canceled 2017-03-31 2017-05-26 2017-11-22 cquisition équipement inform tions nvelope atique et mobilier UCP PRAASED-014-F-CF / mobilie Request for Quota Single Stage - One E IDA / V0020 Unallocated Post Limited 80,000.00 0.00 Canceled 2017-04-04 2017-05-30 2017-11-26 r de bureau UCP tions nvelope PRAASED-012-F-CF / vehicul Request for Quota Single Stage - One E IDA / V0020 Unallocated Post Limited 120,000.00 246,318.60 Completed 2017-10-25 2018-02-09 2017-12-20 2018-01-09 2018-06-18 2018-03-30 e UCP tions nvelope PRAASED-002-F-ED / TOMPR IDA / V0020 Unallocated Prior Direct Selection Direct 40,000.00 0.00 Canceled 2017-03-28 2017-04-02 2017-05-07 2017-11-03 O- Acquisition logiciel TOMPR O PRAASED-012-F-ED / cablag IDA / V0020 Unallocated Post Direct Selection Direct 150,000.00 1,244.88 Signed 2017-10-30 2017-11-04 2017-12-09 2018-01-12 2018-06-07 es 4 sites MEPSA CG-PRAASED-065-F-CF-2018 / Fourniture matériel informa Providing quality education f Request for Quota Single Stage - One E tique (tablettes-ordinateurs) IDA / 58060 Post Limited 300,000.00 230,746.50 Completed 2018-04-24 2018-04-18 2018-06-19 2018-04-30 2018-12-16 2018-08-03 or all tions nvelope pour la collectes des donnée s statistiques des 3 ministère s de l'ensignement CG-PRAASED-075-F-CF-2018 / Fourniture, livraison et insta Improving system performa Request for Quota Single Stage - One E IDA / 58060 Post Limited 15,000.00 12,550.32 Completed 2018-07-11 2018-03-21 2018-09-05 2018-04-17 2019-03-04 2018-05-04 llation de l'équipement infor nce tions nvelope matique destiné à l'INS CG-PRAASED-078-F-CF-2018 / Fourniture de la conexion In Improving system performa Request for Quota Single Stage - One E IDA / 58060 Post Limited 12,000.00 10,469.68 Completed 2018-07-16 2018-04-30 2018-09-10 2018-06-04 2019-03-09 2022-06-22 ternet dans les bureaux du P nce tions nvelope RAASED (Abonnement et Equ ipement) CG-PRAASED-048-F-AON-17 Providing quality education f Request for Quota Single Stage - One E / Télephone mobile contrôle IDA / 58060 Post Open - National 10,000.00 0.00 Canceled 2018-11-27 2019-01-22 2019-07-21 or all tions nvelope action au sein des écoles CG-PRAASED-080-F-CF-2018 Improving system performa Request for Quota Single Stage - One E IDA / 58060 Post Limited 40,000.00 22,228.04 Completed 2018-08-04 2018-05-31 2018-09-29 2018-09-07 2019-03-28 2018-09-25 / Acquisition du Groupe élect nce tions nvelope rogène CG-PRAASED-085-AOI-2019 / Appel d'offre international po Improving scope, quality an Open - Internationa Single Stage - Two E ur la fourniture et installation IDA / 58060 d management of human re Post Request for Bids 800,000.00 0.00 Canceled 2019-03-04 2019-03-09 2019-04-20 2019-07-03 2019-08-07 2020-02-03 l nvelope d'un système pour l' enregist sources rement biométrique des ense ignants. CG-PRAASED-085 BIS-AOI-20 19-2 / Fourniture, installation Improving scope, quality an Open - Internationa Single Stage - One E et assistance à la mise en oe IDA / 58060 d management of human re Post Request for Bids 800,000.00 899,030.25 Completed 2019-05-11 2019-05-13 2019-05-16 2019-05-13 2019-06-27 2019-07-12 2019-07-27 2019-09-12 2019-08-31 2019-12-31 2020-02-27 2022-06-22 l nvelope uvre d'un système d'enregist sources rement biometrique des ense ignants du MEPSA. CG-PRAASED-104- F -ED- 20 19 / Internet : Renouvelleme Improving system performa nt du contrat de Fourniture d IDA / 58060 Post Direct Selection Direct 36,000.00 0.00 Canceled 2019-07-10 2019-06-26 2019-07-15 2019-07-16 2019-08-19 2020-02-15 nce e la connexion Internet dans les bureaux du PRAASED CG-PRAASED-099-F-ED-2019 Improving system performa IDA / 58060 Post Direct Selection Direct 2,000.00 3,600.00 Completed 2020-02-27 2019-11-08 2020-03-03 2020-01-13 2020-04-07 2020-01-30 2020-10-04 2020-02-08 / Acquisition du logiciel STAT nce A CG-PRAASED-0120-ASC-CF-2 020 / Production des fascicul Providing quality education f Request for Quota Single Stage - One E IDA / 58060 Post Limited 557,076.00 433,604.47 Completed 2020-06-16 2020-06-05 2020-08-11 2020-06-17 2021-02-07 2020-07-01 es restants destinés aux elev or all tions nvelope es du MEPSA en classes d'ex amen. CG-PRAASED-0121-CF- 2020 / Production des cahiers d’act ivités des classes intermédiai Providing quality education f Request for Quota Single Stage - One E IDA / 58060 Post Limited 853,788.00 1,218,698.85 Completed 2020-09-06 2020-09-18 2020-11-01 2020-10-08 2021-04-30 2020-12-31 res dans le pôle de Pointe-No or all tions nvelope ire (Pointe-Noire, Kouilou, Nia ri, Lekoumou, Bouenza), en d eux lots CG-PRAASED-0122-CF -2020 / Production des cahiers d’act ivités des classes intermédiai Providing quality education f Request for Quota Single Stage - One E IDA / 58060 Post Limited 970,973.00 1,280,761.25 Completed 2020-09-06 2020-09-18 2020-11-01 2020-10-08 2021-04-30 2021-04-27 res dans le pôle de Brazzavill or all tions nvelope e (Brazzaville, Pool, Plateaux Cuvette, Cuvette-Ouest, San gha et Likouala), lot unique. CG-PRAASED-081-F-CF-2018 / Acquisition fourniture de bu Improving system performa Request for Quota Single Stage - One E IDA / 58060 Post Limited 80,000.00 0.00 Canceled 2020-04-21 2020-06-16 2020-12-13 reau et consommables infor nce tions nvelope matiques- contrat cadre Page 1 CG-PRAASED-0149 -F-ED-20 21 / Logiciel AFIS- Acquisition Improving scope, quality an Under Imple d'une licence AFIS pour l'enr IDA / 58060 d management of human re Post Direct Selection Direct 185,981.00 0.00 2021-12-30 2021-12-17 2022-01-04 2022-02-08 2022-08-07 mentation ôlement biométrique de 30 0 sources 00 enseignants (phase génér alisation) CG-PRAASED-0157- / 12 véhi Improving system performa Request for Quota Single Stage - One E cules - Acquisition des 12 vé IDA / 58060 Post Limited 761,421.32 570,110.40 Signed 2022-03-21 2022-03-22 2022-05-16 2022-04-29 2022-11-12 nce tions nvelope hicules destinés aux DDEPSA CG-PRAASED-0158- F -CF-20 22 / PE+ CA du CP1-CP2 -La production et la livraison dan s les 12 Départements des pr Providing quality education f Request for Quota Single Stage - One E IDA / 58060 Post Limited 1,130,355.00 1,429,888.73 Signed 2022-03-23 2022-01-26 2022-05-18 2022-04-14 2022-11-14 ogrammes et guides pédago or all tions nvelope giques ainsi que les cahiers d'activités des nouveaux pro grammes révisés pour les cla sses de CP1, CP2. CG- PRAASED-0159-F- CF-20 22 / PE+ CA de la 6è et 5è -L a production et la livraison d ans les 12 Départements des Providing quality education f Request for Quota Single Stage - One E Under Imple IDA / 58060 Post Limited 752,248.91 0.00 2022-03-30 2022-08-01 2022-05-25 2022-11-21 programmes et guides pédag or all tions nvelope mentation ogiques (PE) ainsi que les ca hiers d'activités (CA) des nou veaux programmes révisés p our les classes de la 6ème et 5ème . CG-PRAASED-0176-F-CF-202 2 / DEP- IGEPSA-DDEPPSA - A Improving system performa Request for Quota Single Stage - One E cquisition du matériel inform IDA / 58060 Post Limited 60,000.00 0.00 Signed 2022-10-16 2022-10-25 2022-12-11 2023-06-09 nce tions nvelope atique destiné à la DEP, l'IGE PSA .et aux DDEPPSA du MEP PSA. CG-PRAASED-0177- F-ED-20 22 / CA 6è et 5è- Production des cahiers d’activités compl Providing quality education f émentaires des classes de 6è IDA / 58060 Post Direct Selection Direct - National 160,500.00 0.00 Signed 2022-10-29 2022-10-05 2022-11-03 2022-10-06 2022-12-08 2023-06-06 or all me et 5ème, issus des nouve aux programmes dans les d eux pôles (Brazzaville et Poin te-Noire). CG-PRAASED-0184-F-CF-202 Improving scope, quality an Request for Quota Single Stage - One E Under Imple 3 / DNEAS - Acquisition des é IDA / 58060 d management of human re Post Limited 16,933.00 0.00 2023-04-06 2023-06-01 2023-11-28 tions nvelope mentation quipements informatiques du sources DNEAS CG-PRAASED-0185-CS-CI-20 23 / Recrutement de 12 vérifi Providing quality education f Request for Quota Single Stage - One E IDA / 58060 Post Limited 70,632.00 0.00 Canceled 2023-04-08 2023-06-03 2023-11-30 cateurs indépendants des su or all tions nvelope pports pédagogiques distribu és CG-PRAASED-0189-F-CF-202 Improving scope, quality an 3 / Impression de 200 annuai Request for Quota Single Stage - One E Pending Impl IDA / 58060 d management of human re Post Limited 3,626.00 0.00 2023-04-19 2023-06-14 2023-12-11 res statistiques du MEPPSA 2 tions nvelope ementation sources 018 -2019 & 2019-2020 (15 j ours) CG-PRAASED-0192-CF-ED-20 23 / Recrutement des imprim eurs pour la Reproduction de Providing quality education f IDA / 58060 Post Direct Selection Direct - National 322,310.00 0.00 Canceled 2023-04-03 2023-04-08 2023-05-13 2023-11-09 s nouveaux programmes édu or all catifs et guides pédagogique s des classes restantes du CE 1 au CM2, 4ème à 3ème CG-PRAASED-0193-F-CF-202 Providing quality education f Request for Quota Single Stage - One E Pending Impl 3 / Impression des instrumen IDA / 58060 Post Limited 65,192.00 0.00 2023-04-08 2023-06-03 2023-11-30 or all tions nvelope ementation ts d’enquête finale du DNEAS CG-PRAASED-0195-F-CF-202 Providing quality education f Request for Quota Single Stage - One E Under Imple 3 / Acquisition de fournitures IDA / 58060 Post Limited 8,724.00 0.00 2023-04-08 2023-06-03 2023-11-30 or all tions nvelope mentation pour le DNEAS CG-PRAASED-0194-CF-ED-20 23 / Recrutement des imprim Providing quality education f eurs pour la Reproduction de IDA / 58060 Post Direct Selection Direct - National 1,205,584.00 0.00 Canceled 2023-04-03 2023-04-08 2023-05-13 2023-11-09 or all s cahiers d'activités des class es restantes du CE1 au CM2, 4ème à 3ème CG-PRAASED-0191-F-CF-202 Providing quality education f Request for Quota Single Stage - One E Pending Impl 3 / Impression des instrumen IDA / 58060 Post Limited 65,192.00 0.00 2023-04-15 2023-06-10 2023-12-07 or all tions nvelope ementation ts d’enquête finale CG-PRAASED-0198-CF-ED-20 23 / Reproduction des nouve aux programmes éducatifs et Providing quality education f Pending Impl IDA / 58060 Post Direct Selection Direct - National 322,311.00 0.00 2023-05-02 2023-05-07 2023-06-11 2023-12-08 guides pédagogiques du pri or all ementation maire (du CP1 au CM2) et col lège (de la 6ème en 3ème) CG-PRAASED-0199-CF-ED-20 23 / Reproduction des Cahier Providing quality education f Pending Impl IDA / 58060 Post Direct Selection Direct - National 974,955.00 0.00 2023-05-02 2023-05-07 2023-06-11 2023-12-08 s d'activités des programme or all ementation s révisés restants (CE1 au C M2, 4e et 3e) CG-PRAASED-0200-CF-ED-20 23 / Reproduction des Cahier Providing quality education f Pending Impl IDA / 58060 Post Direct Selection Direct - National 406,231.00 0.00 2023-05-02 2023-05-07 2023-06-11 2023-12-08 s d’activités des programmes or all ementation révisés restants (CE1 au CM2 , 4e et 3e) CG-PRAASED-0201-CF-ED-20 23 / Reproduction des Cahier Providing quality education f Pending Impl IDA / 58060 Post Direct Selection Direct - National 243,739.00 0.00 2023-05-02 2023-05-07 2023-06-11 2023-12-08 s d'activités des programmes or all ementation révisés restants (CE1 au CM2 , 4e et 3e) CG-PRAASED-0178 -F-AON-2 022 / - Tablettes SIGE- Acquis Improving system performa Single Stage - One E IDA / 58060 Post Request for Bids Open - National 124,000.00 0.00 Canceled 2022-12-23 2023-01-26 2022-12-28 2023-02-08 2023-02-08 2023-03-10 2023-04-14 2023-10-11 ition de 400 tablettes pour la nce nvelope mise en place du SIGE du ME PPSA PRAASED-013-F-AON / appar Single Stage - One E IDA / V0020 Unallocated Post Request for Bids Open - National 120,000.00 0.00 Canceled 2017-04-05 2017-04-10 2017-05-22 2017-06-21 2017-07-26 2018-01-22 eils biométriques nvelope NON CONSULTING SERVICES Page 2 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PRAASED-074-CF-ED-201 Improving system performa 8 / Contrat de bail à usage d IDA / 58060 Post Direct Selection Direct 122,400.00 0.00 Canceled 2018-06-27 2018-07-02 2018-08-06 2019-02-02 nce es bureaux du PRAASED CG-PRAASED-073-AS-CF-201 8 / Prestation de services pou Improving system performa Request for Quota Single Stage - One E IDA / 58060 Post Limited 12,000.00 4,667.89 Completed 2018-07-11 2018-03-05 2018-09-05 2018-03-15 2019-03-04 2018-03-16 r l'assurance tous risques de nce tions nvelope s véhicules destinés au PRAA SED CG-PRAASED-076-AS-CF-201 Improving system performa Request for Quota Single Stage - One E 8 / Prestation de services pou IDA / 58060 Post Limited 20,000.00 16,899.39 Completed 2018-07-11 2018-04-03 2018-09-05 2018-05-10 2019-03-04 2019-05-09 nce tions nvelope r le gardiennage des bureaux du PRAASED CG-PRAASED-077-AS-CF-201 Improving system performa Request for Quota Single Stage - One E 8 / Prestation de services pou IDA / 58060 Post Limited 10,000.00 7,331.05 Completed 2018-07-11 2018-04-03 2018-09-05 2018-05-10 2019-03-04 2019-05-09 nce tions nvelope r l'entretien des bureau du P RAASED CG-PRAASED-079-AS-CF-201 8 / Prestation de services pou r la restauration des participa nts à la formation sur la colle Improving system performa Request for Quota Single Stage - One E IDA / 58060 Post Limited 150,000.00 172,585.42 Completed 2018-07-16 2018-06-12 2018-09-10 2018-06-30 2019-03-09 2018-06-28 cte des données statistiques nce tions nvelope des ministères en charge de l 'éducation à Brazzaville, Poin te-Noire et Owando (en lots distincts. CG-PRAASED-091-ED-2019 / Contrat de maintenance et e Improving system performa ntretien du groupe electroge IDA / 58060 Post Direct Selection Direct 15,000.00 1,637.82 Completed 2019-04-23 2019-04-28 2019-04-29 2019-06-02 2019-05-10 2019-11-29 2020-08-28 nce ne du PRAASED, avec Grasse t SPORAFRIC- Fournisseur du groupe CG-PRAASED-105- ASC-ED-2 019 / Gardiennage - Renouve Improving system performa llement du contrat de Prestat IDA / 58060 Post Direct Selection Direct 57,600.00 32,554.89 Completed 2019-07-10 2019-07-07 2019-07-15 2019-07-07 2019-08-19 2019-08-20 2020-02-15 2020-12-30 nce ion de services pour le gardie nnage des bureaux du PRAA SED CG-PRAASED-106- ASC-ED-2 019 / Entretien bureaux : Ren Improving system performa ouvellement du contrat de Pr IDA / 58060 Post Direct Selection Direct 25,200.00 14,090.92 Completed 2019-07-10 2019-07-07 2019-07-15 2019-07-07 2019-08-19 2019-08-20 2020-02-15 2020-12-30 nce estation de services pour l'en tretien des bureau du PRAAS ED CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRAASED-009-C-SFQC / cabi Quality And Cost- Open - Internationa IDA / V0020 Unallocated Post 300,000.00 0.00 Canceled 2017-03-31 2017-04-21 2017-06-04 2017-07-02 2017-08-01 2017-09-05 2017-10-10 2018-10-10 net evalu syst educatif congo Based Selection l lais PRAASED-006-C-QC / cabine Consultant Qualifi Open - Internationa IDA / V0020 Unallocated Prior 40,000.00 0.00 Canceled 2017-03-27 2017-04-17 2017-05-31 2017-06-30 2017-08-04 2018-01-31 t perso clé cation Selection l CG-PRAASED-049-C-SFQC-17 Providing quality education f Quality And Cost- Open - Internationa / Cabinet système biométriqu IDA / 58060 Post 120,000.00 0.00 Canceled 2017-10-20 2017-11-10 2017-12-24 2018-01-21 2018-02-20 2018-03-27 2018-05-01 2019-05-01 or all Based Selection l e recensement enseignant CG-PRAASED-056-C-CI-17 / A Improving system performa Quality And Cost- Open - Internationa IDA / 58060 Prior 40,000.00 48,895.38 Completed 2018-02-05 2018-02-14 2018-02-26 2018-02-16 2018-04-11 2018-04-27 2018-05-09 2018-06-08 2018-06-04 2018-07-13 2018-06-13 2018-08-17 2018-06-13 2019-08-17 2019-08-29 udit externe 2017-2018 nce Based Selection l CG-PRAASED-037-C-SFQC-17 Providing quality education f Quality And Cost- Open - Internationa IDA / 58060 Prior 50,000.00 0.00 Canceled 2018-03-14 2018-04-04 2018-05-18 2018-06-15 2018-07-15 2018-08-19 2018-09-23 2019-09-23 / Audit externe or all Based Selection l CG-PRAASED-032-C-SFQC-17 / Analyse reforme enseignem Improving scope, quality an ent superieur et l'ensembe d Quality And Cost- Open - Internationa IDA / 58060 d management of human re Prior 250,000.00 0.00 Canceled 2019-06-17 2019-07-08 2019-08-21 2019-09-18 2019-10-18 2019-11-22 2019-12-27 2020-12-26 u système portant sur l'adéq Based Selection l sources uation enseignement superie ur et marché du travail , gou vernance du secteur... CG-PRAASED-029-C-SFQC-17 / Eval dispositifs et/ ou meca Providing quality education f Quality And Cost- Open - Internationa IDA / 58060 Post 200,000.00 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-26 2020-04-25 nismes d'évaluation des acqu or all Based Selection l is des élèves/apprentissage CG-PRAASED-026-C-SFQC / Cabinet recensement bénévo Providing quality education f Quality And Cost- Open - Internationa les et autres personnel ensei IDA / 58060 Post 170,000.00 0.00 Canceled 2018-11-05 2018-11-26 2019-01-09 2019-02-06 2019-03-08 2019-04-12 2019-05-17 2020-05-16 or all Based Selection l gnant: directeurs scolaires, c onseillers pédagogiques, insp ecteurs.. PRAASED-011 BIS-C-SFQC-2 018 / Révision des curriculas Improving system performa Quality And Cost- - Recrutement d'un cabinet c IDA / 58060 Prior Open - National 500,000.00 0.00 Canceled 2018-08-10 2018-08-31 2018-10-14 2018-11-11 2018-12-11 2019-01-15 2019-02-19 2020-02-19 nce Based Selection hargé de la révision des curri culas du primaire et secondai re CG-PRAASED-021-C-SFQC-17 Providing quality education f Quality And Cost- Open - Internationa IDA / 58060 Post 234,000.00 0.00 Canceled 2019-02-28 2019-03-21 2019-05-04 2019-06-01 2019-07-01 2019-08-05 2019-09-09 2020-09-08 / Contrôle travaux depart 1 or all Based Selection l CG-PRAASED-027-C-SFQC / c abinet enquête SDI - Recrute Providing quality education f Consultant Qualifi Open - Internationa IDA / 58060 Post 500,000.00 0.00 Canceled 2018-07-30 2018-08-17 2018-08-20 2018-09-03 2018-10-03 2018-11-02 2018-12-07 2019-06-05 ment d'un cabinet chargé de or all cation Selection l réaliser l'enquête SDI CG-PRAASED-030-C-SFQC-17 Providing quality education f Quality And Cost- Open - Internationa / Analyse programme de for IDA / 58060 Prior 700,000.00 0.00 Canceled 2019-02-19 2019-03-12 2019-04-25 2019-05-23 2019-06-22 2019-07-27 2019-08-31 2020-08-30 or all Based Selection l mation et pratiques classe CG-PRAASED-060-C-SQC-18 Improving scope, quality an / Mise en place du système bi Consultant Qualifi Open - Internationa IDA / 58060 d management of human re Post 240,000.00 0.00 Canceled 2018-03-13 2018-04-03 2018-05-17 2018-03-15 2018-06-16 2018-07-21 2019-01-17 ométrique pour l'enregistrem cation Selection l sources ent des enseignants Page 3 CG-PRAASED-089-CS-SFQC-2 019 / Enquete SDI- Recrutem Providing quality education f Quality And Cost- Open - Internationa ent d'un cabinet en charge d IDA / 58060 Prior 750,000.00 919,214.00 Completed 2019-03-12 2019-04-12 2019-04-02 2019-04-18 2019-05-16 2019-07-17 2019-06-13 2019-08-22 2019-07-13 2019-10-09 2019-08-17 2019-12-23 2019-09-21 2019-12-25 2020-09-20 2022-07-15 or all Based Selection l e l'enquete sur les indicateur s de prestation de services e n Republique du Congo CG-PRAASED-108- CS-QC-20 19 / INRAP- Recrutement d’u n consultant International po Improving system performa Consultant Qualifi Open - Internationa IDA / 58060 Post 50,000.00 0.00 Canceled 2019-07-11 2019-08-01 2019-09-14 2019-10-14 2019-11-18 2020-05-16 ur une assistance a l’elaborat nce cation Selection l ion d’une feuille de route et d ’un plan strategique de l’INR AP CG-PRAASED- 107- CS- QC-2 019 / ENI/ENS - Recrutement d’un Consultant International Improving system performa Consultant Qualifi Open - Internationa IDA / 58060 Post 50,000.00 0.00 Canceled 2019-07-11 2019-08-01 2019-09-14 2019-10-14 2019-11-18 2020-05-16 pour une assistance a l’elabo nce cation Selection l ration d’une feuille de route et d’un plan strategique de ENI/ENS CG-PRAASED-0114-CS-SFQC- 2019 / Audit Externe 2019-20 20 : Recrutement d'un cabin Improving system performa Quality And Cost- Open - Internationa IDA / 58060 Post 60,000.00 26,404.83 Completed 2019-10-24 2019-11-20 2019-11-14 2019-11-27 2019-12-28 2020-02-25 2020-01-25 2020-03-25 2020-02-24 2020-06-08 2020-03-30 2020-06-22 2020-05-04 2020-07-02 2021-05-04 2021-07-31 et d'expertise comptable cha nce Based Selection l rgé de l'audit des comptes d u PRAASED (exercices 2019- 2020). CG-PRAASED-125-SFQC-202 1 / Auditeur Interne - Recrute Improving system performa Quality And Cost- Open - Internationa IDA / 58060 Post 50,000.00 67,984.66 Terminated 2021-06-15 2021-01-14 2021-07-06 2021-08-19 2021-05-06 2021-09-16 2021-06-04 2021-10-16 2021-06-28 2021-11-20 2021-07-01 2021-12-25 2021-09-25 2022-12-25 ment d'un cabinet ou firme p nce Based Selection l our assurer la fonction d’audi t interne du PRAASED CG-PRAASED-125-SC-SFQC-2 021-REGULARISATI / Audit Int Improving system performa Quality And Cost- Open - Internationa erne - Recrutement d'un cabi IDA / 58060 Post 50,000.00 70,222.92 Signed 2021-10-08 2021-01-19 2021-10-29 2021-12-12 2021-05-06 2022-01-09 2021-06-04 2022-02-08 2021-06-18 2022-03-15 2021-07-01 2022-04-19 2021-09-25 2023-04-19 nce Based Selection l net ou firme pour assurer la f onction d'audit interne du PR AASED CG-PRAASED-0137-CS-QC-2 021 / Leadership - Recrutem Improving scope, quality an ent d’un cabinet/ Bureau d’ét Consultant Qualifi Open - Internationa Under Implement IDA / 58060 d management of human re Post 150,000.00 0.00 2021-11-04 2022-02-08 2021-11-25 2022-03-08 2022-01-08 2022-02-07 2022-03-14 2022-09-10 ude chargé de la formation d cation Selection l ation sources es Directeurs d’établissemen ts scolaires en leadership et en Management. CG-PRAASED-0148-CS-SFQC- 2021 / Audit externe 2021-20 22- Recrutement d'un cabin Improving system performa Quality And Cost- Open - Internationa et/ Firme d'expertise compta IDA / 58060 Post 60,000.00 13,616.09 Signed 2021-12-29 2022-01-18 2022-01-19 2022-02-02 2022-03-04 2022-03-18 2022-04-01 2022-04-20 2022-05-01 2022-04-26 2022-06-05 2022-05-24 2022-07-10 2022-05-24 2023-07-10 nce Based Selection l ble, chargé de l'audit des co mptes du PRAASED, exercice 2021 et exercice 2022 (clôtur e au 30 juin) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRAASED-003-C-CI / CI DFC- Individual Consult IDA / V0020 Unallocated Post Open 50,000.00 0.00 Canceled 2017-03-30 2017-05-18 2017-06-08 2017-07-13 2018-01-09 Evaluation des capacités DFC ant Selection PRAASED-008-C-CI / CI capa Individual Consult IDA / V0020 Unallocated Post Open 70,000.00 0.00 Canceled 2017-03-29 2017-05-17 2017-06-07 2017-07-12 2018-01-08 cité DDPSA ant Selection PRAASED-004-C-CI / CI INRA Individual Consult IDA / V0020 Unallocated Post Open 60,000.00 0.00 Canceled 2017-03-31 2017-05-19 2017-06-09 2017-07-14 2018-01-10 P- evaluation capacités INRA ant Selection P PRAASED-011-C-CI / CI revisi Individual Consult IDA / V0020 Unallocated Post Open 120,000.00 0.00 Canceled 2018-03-07 2018-04-25 2018-05-16 2018-06-20 2018-12-17 on curricula primaire et seco ant Selection ndaire PRAASED-015-C-ED / Elabor IDA / 58060 Unallocated Prior Direct Selection Direct 10,000.00 0.00 Canceled 2017-04-06 2017-04-16 2017-06-20 2017-12-17 ation manuel de procédures PRAASED-005-C-CI / CI ENI e Individual Consult t ENS- evaluation des formati IDA / V0020 Unallocated Post Open 90,000.00 0.00 Canceled 2017-03-31 2017-05-19 2017-06-09 2017-07-14 2018-01-10 ant Selection ons ENI et ENS CG-PRAASED-020-C-CI-17 / A Improving system performa Individual Consult IDA / 58060 Post Open 90,000.00 0.00 Canceled 2018-01-12 2018-01-11 2018-03-02 2018-03-23 2018-04-27 2018-10-24 uditeur interne nce ant Selection CG-PRAASED-038-C-CI-17 / R Improving system performa Individual Consult IDA / 58060 Post Open 90,000.00 0.00 Canceled 2017-11-06 2017-12-01 2017-12-25 2018-01-15 2018-02-19 2018-08-18 ecrut Comptable nce ant Selection CG-PRAASED-028-C-CI-17 / A Providing quality education f Individual Consult IDA / 58060 Prior Open 200,000.00 0.00 Canceled 2018-03-18 2018-01-19 2018-05-06 2018-05-27 2018-07-01 2018-12-28 nalyse inst MEPSA et DDPSA or all ant Selection CG-PRAASED-36-C-ED-17 / Pl Improving scope, quality an ate forme contrôle et verifica IDA / 58060 d management of human re Prior Direct Selection Direct 100,000.00 0.00 Canceled 2018-06-13 2018-06-23 2018-08-27 2019-02-23 tion des actions au sein de l' sources école par BLUE SQUARE CG-PRAASED-051-C-CI-17 / R Improving system performa Individual Consult IDA / 58060 Prior Open 139,200.00 245,144.43 Completed 2017-12-18 2018-02-05 2018-02-26 2018-01-18 2018-04-02 2018-01-15 2018-09-29 2021-01-30 ecrutement coordonnateur P nce ant Selection RAASED CG-PRAASED-052-C-CI-17 / R Improving system performa Individual Consult IDA / 58060 Prior Open 51,600.00 48,273.86 Completed 2017-12-18 2018-02-05 2018-02-26 2018-01-18 2018-04-02 2018-01-15 2018-09-29 2019-01-14 ecrutement RAFC nce ant Selection CG-PRAASED-053-C-CI-17 / R Improving system performa Individual Consult IDA / 58060 Prior Open 51,600.00 48,273.86 Completed 2017-12-18 2018-02-05 2018-02-26 2018-01-18 2018-04-02 2018-01-15 2018-09-29 2019-01-14 ecrutement SPM nce ant Selection CG-PRAASED-055-C-CDS-17 Providing quality education f / Appui INS aux trois ministèr IDA / 58060 Prior Direct Selection Direct 48,000.00 98,518.39 Completed 2018-02-15 2018-02-25 2018-05-01 2018-02-08 2018-10-28 2020-02-28 or all es MEPSA MES METPFQE CG-PRAASED-057-C-CI-18 / R Improving system performa Individual Consult IDA / 58060 Prior Open 228,000.00 0.00 Canceled 2018-02-13 2018-02-14 2018-04-03 2018-12-27 2018-04-24 2018-05-29 2018-11-25 ecrutement Auditeur interne nce ant Selection Page 4 CG-PRAASED-058-C-CI-18 / R Improving system performa Individual Consult IDA / 58060 Prior Open 192,000.00 101,406.72 Completed 2018-02-13 2018-02-14 2018-04-03 2018-04-18 2018-04-24 2018-06-12 2018-05-29 2018-06-12 2018-11-25 2021-01-30 ecrutement Comptable nce ant Selection CG-PRAASED-059-C-ED-18 / Appui au MEPSA pour partici Providing quality education f IDA / 58060 Prior Direct Selection Direct 617,760.00 466,774.66 Completed 2018-02-12 2018-02-22 2018-07-20 2018-04-28 2018-12-11 2018-10-25 2020-12-30 pation à l'évaluation internati or all onale PASEC 2019 CG-PRAASED-060-C-ED-2018 Improving system performa / Analyse institutionnelle MEP IDA / 58060 Prior Direct Selection Direct 200,000.00 56,498.00 Completed 2018-03-02 2018-03-07 2018-03-12 2018-03-13 2018-05-16 2018-06-11 2018-11-12 2018-12-29 nce SA et DDPSA CG-PRAASED-063-C-CI-18 / R Improving system performa Individual Consult ecrutement du Responsable IDA / 58060 Post Open 258,000.00 0.00 Canceled 2018-03-13 2018-03-06 2018-05-01 2018-05-22 2018-06-26 2018-12-23 nce ant Selection de la composante 3 (RC 3) d u PRAASED CG-PRAASED-062-C-CI-18 / R Improving system performa Individual Consult ecrutement du Responsable IDA / 58060 Post Open 258,000.00 0.00 Canceled 2018-03-13 2018-03-06 2018-05-01 2018-05-22 2018-06-26 2018-12-23 nce ant Selection de la composante 2 (RC 2) d u PRAASED CG-PRAASED-061-C-CI-18 / R Improving system performa Individual Consult ecrutement du responsable d IDA / 58060 Post Open 258,000.00 0.00 Canceled 2018-03-13 2018-03-06 2018-05-01 2018-05-22 2018-06-26 2018-12-23 nce ant Selection e la composante 1 (RC 1) du PRAASED CG-PRAASED-064-C-CI-18 / R Improving system performa Individual Consult ecrutement du Responsable IDA / 58060 Post Open 258,000.00 0.00 Canceled 2018-03-13 2018-03-06 2018-05-01 2018-05-22 2018-06-26 2018-12-23 nce ant Selection du Suivi-Evaluation (RSE) du PRAASED CG-PRAASED-063-C-CI-2018 Improving system performa Individual Consult / Recrutement du Responsabl IDA / 58060 Prior Open 258,000.00 87,084.54 Completed 2018-03-30 2018-04-27 2018-05-18 2018-12-07 2018-06-08 2019-02-07 2018-07-13 2019-02-08 2019-01-09 2021-01-30 nce ant Selection e de la composante 3 (RC3) du PRAASED CG-PRAASED-061-C-CI-2018 Improving system performa Individual Consult / Recrutement du Responsabl IDA / 58060 Prior Open 258,000.00 87,027.53 Completed 2018-03-30 2018-05-21 2018-05-18 2018-12-07 2018-06-08 2019-02-12 2018-07-13 2019-02-13 2019-01-09 2021-01-30 nce ant Selection e de la composante 1 (RC1) du PRAASED CG-PRAASED-064-C-CI-2018 Improving system performa Individual Consult / Recrutement du Responsabl IDA / 58060 Prior Open 258,000.00 87,519.28 Completed 2018-03-30 2018-04-27 2018-05-18 2018-12-07 2018-06-08 2019-02-07 2018-07-13 2019-02-08 2019-01-09 2021-01-30 nce ant Selection e Suivi-Évaluation (RSE) du P RAASED CG-PRAASED-066-C-CI-2018 Improving system performa Individual Consult / Recrutement d'un Assistant IDA / 58060 Post Open 168,000.00 0.00 Canceled 2018-05-04 2018-06-30 2018-06-22 2018-07-13 2018-08-17 2019-02-13 nce ant Selection chargé de la communication du PRAASED CG-PRAASED-068-C-CI-2018 Improving system performa Individual Consult / Recrutement d'un Trésorier IDA / 58060 Post Open 144,000.00 0.00 Canceled 2018-05-25 2018-04-25 2018-07-13 2018-08-03 2018-09-07 2019-03-06 nce ant Selection du PRAASED CG-PRAASED-069-C-CI-2018 Improving system performa Individual Consult / Recrutement d'un Assistant IDA / 58060 Post Open 96,000.00 0.00 Canceled 2018-05-25 2018-04-25 2018-07-13 2018-08-03 2018-09-07 2019-03-06 nce ant Selection Administratif du PRAASED CG-PRAASED-070-C-CI-2018 Improving system performa Individual Consult / Recrutement d'une Sécretai IDA / 58060 Post Open 72,000.00 0.00 Canceled 2018-05-25 2018-04-25 2018-07-13 2018-08-03 2018-09-07 2019-03-06 nce ant Selection re de direction du PRAASED CG-PRAASED-071-C-CI-2018 Improving system performa Individual Consult / Recutement de trois Chauff IDA / 58060 Post Open 108,000.00 25,277.93 Completed 2018-05-25 2018-04-25 2018-07-13 2018-08-06 2018-08-03 2018-08-23 2018-09-07 2018-09-03 2019-03-06 2020-09-30 nce ant Selection eurs du PRAASED CG-PRAASED-066-CS-CI-201 Improving system performa Individual Consult 8 / Recrutement d'un Spéciali IDA / 58060 Prior Open 258,000.00 87,556.69 Completed 2018-07-11 2018-08-02 2018-08-29 2019-01-21 2018-09-19 2019-02-27 2018-10-24 2019-03-01 2019-04-22 2021-01-30 nce ant Selection ste en charge de la communi cation CG-PRAASED-018-C-CI-17 / I ngénieur en génie civil - Rec Improving system performa Individual Consult IDA / 58060 Post Open 120,000.00 0.00 Canceled 2019-01-08 2019-02-26 2019-03-19 2019-04-23 2019-10-20 rutement d'un Ingénieur en g nce ant Selection énie civile chargé des constr uctions scolaires CG-PRAASED-050-C-CI-17 / C onsultant banque items pour Providing quality education f Individual Consult IDA / 58060 Post Open 25,000.00 0.00 Canceled 2018-10-22 2018-12-10 2018-12-31 2019-02-04 2019-08-03 évaluation des acquis scolair or all ant Selection e au primaire et secondaire CG-PRAASED-072-CS-CI-201 8 / Recrutement d'un Spéciali Improving system performa Individual Consult IDA / 58060 Post Open 90,000.00 0.00 Canceled 2018-09-04 2018-10-23 2018-11-13 2018-12-18 2019-06-16 ste en Sauvegarde environne nce ant Selection mentale du PRAASED CG-PRAASED-017-BIS-C-CI-2 018 / Sauvegarde sociale - R Improving system performa Individual Consult IDA / 58060 Post Open 90,000.00 0.00 Canceled 2018-09-04 2018-10-23 2018-11-13 2018-12-18 2019-06-16 ecrutement d'un consultant c nce ant Selection hargé d la suvegarde sociale du PRAASED CG-PRAASED-019-C-CI-17 / T Improving system performa Individual Consult IDA / 58060 Post Open 60,000.00 0.00 Canceled 2019-01-08 2019-02-26 2019-03-19 2019-04-23 2019-10-20 echnicien sup en génie civil nce ant Selection CG-PRAASED-082-C-ED-2018 / Consultant FGB - Recrutem ent du consultant Internation Providing quality education f IDA / 58060 Post Direct Selection Direct 60,000.00 0.00 Canceled 2018-08-07 2018-08-17 2018-08-17 2018-10-21 2019-04-19 al, spécialiste en formation g or all estion à la Base, pour la mise en oeuvre du volet communa utaire CG-PRAASED-062-C-CI-2018 Improving system performa Individual Consult / Recrutement du Responsabl IDA / 58060 Prior Open 258,000.00 0.00 Canceled 2018-03-30 2018-06-04 2018-05-18 2018-06-08 2018-07-13 2019-01-09 nce ant Selection e de la composante 2 (RC2) du PRAASED CG-PRAASED-062 BIS-CS-IN Improving system performa Individual Consult DV / Recrutement d'un Respo IDA / 58060 Prior Open 258,000.00 87,871.19 Completed 2019-01-15 2018-12-08 2019-03-05 2019-02-18 2019-03-26 2019-04-25 2019-04-30 2019-04-26 2019-10-27 2021-01-30 nce ant Selection nsable de la Composante 2 ( RC2) CG-PRAASED-017-C-CI-17 / R Improving system performa Individual Consult ecrutement Spécialiste sauve IDA / 58060 Post Open 90,000.00 0.00 Canceled 2018-09-20 2018-11-08 2019-01-17 2018-11-29 2019-01-03 2019-07-02 nce ant Selection garde environnementale et s ociale CG-PRAASED-057-CS-CI-201 Improving system performa Individual Consult 8 / Recrutement d'une Assist IDA / 58060 Post Open 76,800.00 32,760.67 Completed 2019-03-06 2019-04-24 2019-06-12 2019-05-15 2019-06-13 2019-06-19 2019-06-14 2019-12-16 2021-01-30 nce ant Selection ance de direction du PRAASE D Page 5 CG-PRAASED-083-CS-CI-201 9 / Renouvelement du contra Improving system performa Individual Consult IDA / 58060 Prior Direct 206,400.00 88,034.50 Completed 2019-02-22 2019-02-28 2019-03-04 2019-01-14 2019-03-25 2019-03-12 2019-04-29 2019-03-13 2019-10-26 2021-01-30 t de service du Responsable nce ant Selection Administratif et Financier (RA F) du PRAASED CG-PRAASED-086-CS-CI-201 9 / Renouvelement du contra Improving system performa Individual Consult IDA / 58060 Prior Direct 206,400.00 87,053.33 Completed 2019-02-22 2019-02-28 2019-03-04 2019-01-14 2019-03-25 2019-03-12 2019-04-29 2019-03-13 2019-10-26 2021-01-30 t de service de la Spécialiste nce ant Selection en Passation des Marches (S PM) du PRAASED CG-PRAASED-087-CS-CI-201 9 / Recrutement d'un consult ant international pour l'analy Providing quality education f Individual Consult IDA / 58060 Post Open 60,000.00 90,929.39 Completed 2019-02-28 2019-04-30 2019-04-18 2019-07-23 2019-05-09 2019-09-23 2019-06-13 2019-09-24 2019-12-10 2021-04-30 se du dispositif des évaluatio or all ant Selection ns sommatives et examens n ationaux (CEPE, BEPC, BAC) CG-PRAASED-090-CS-CI-201 Improving system performa Individual Consult 9 / Recrutement du 3ème ch IDA / 58060 Post Open 28,800.00 6,081.98 Completed 2019-03-27 2019-04-11 2019-05-15 2019-07-22 2019-06-05 2019-07-23 2019-07-10 2019-07-25 2020-01-06 2020-07-30 nce ant Selection auffeur du PRAASED CG-PRAASED-093-CS-CI-201 Improving system performa Individual Consult 9 / Recrutement d'un Speciali IDA / 58060 Post Open 103,200.00 67,045.43 Completed 2019-04-29 2019-04-29 2019-06-17 2019-08-12 2019-07-08 2019-09-05 2019-08-12 2019-10-09 2020-02-08 2021-01-30 nce ant Selection ste en Sauvegardes Sociales du PRAASED PRAASED-094-CS-CI-2019 / Recrutement d'un consultant national pour l'analyse des e Providing quality education f Individual Consult IDA / 58060 Post Open 12,000.00 0.00 Canceled 2019-05-13 2019-07-01 2019-07-22 2019-08-26 2020-02-22 valuations formatives en situ or all ant Selection ation de classe pour les devo irs departemantaux, examen s blancs et tests. CG PRAASED-095-CS-CI-201 9 / Recrutement d'un consult ant national pour l'analyse d Providing quality education f Individual Consult IDA / 58060 Post Open 12,000.00 0.00 Canceled 2019-05-13 2019-07-01 2019-07-22 2019-08-26 2020-02-22 es évaluations formatives en or all ant Selection situation de classe pour les d evoirs, compositions mensuel les/trimestrielles CG-PRAASED-097-CS-CI-201 9 / Recrutement d'un consult ant pour la redynamisation d Improving system performa Individual Consult IDA / 58060 Post Open 8,000.00 30,960.18 Signed 2019-05-16 2019-08-29 2019-07-04 2019-11-20 2019-07-25 2020-02-18 2019-08-29 2020-05-23 2020-02-25 u site web du MEPSA et mise nce ant Selection en place des sites web de l'IN RAP, IGEPSA, DEC et DGRHA. PRAASED-098-CS-CI-2019 / Recrutement d'un consultant international charge d'appui aux équipe tecniques- à l'ela Improving system performa Individual Consult IDA / 58060 Post Open 40,000.00 0.00 Canceled 2019-05-17 2019-07-05 2019-07-26 2019-08-30 2020-02-26 boration des feuilles de route nce ant Selection et plans strategiques pour la mise en oeuvre des recomm andations des etudes realise es (ENI/ENS, INRAP, MEPSA-D DEPSA. PRAASED-0100-CS-ED-2019 / Contrat de service de consu ltant avec Viticia THAMES, co Providing quality education f nsultante internationale pour IDA / 58060 Post Direct Selection Direct 60,000.00 0.00 Canceled 2019-05-21 2019-07-30 2019-05-31 2019-08-30 2019-08-04 2020-01-31 or all l'élaboration/adaptation du p rotocole/outils CLASS pour l'a melioration de la pedagogie active et de l'apprentissage. CG-PRAASED- 101- CS-ED-20 19 / Evaluations curriculas- R ecrutement du consultant int Providing quality education f ernational pour l'appui techni IDA / 58060 Post Direct Selection Direct 140,000.00 119,210.13 Completed 2019-07-04 2019-07-09 2019-07-14 2019-07-23 2019-09-17 2019-09-25 2020-03-15 2021-12-30 or all que au processus de révision des curricula (évaluation et l a réécriture) des programme s du primaire et du secondair e CG- PRAASED- 102-CS- CI-20 19 / Evaluations Formatives - Recrutement d’un consultant national chargé de l’analyse Providing quality education f Individual Consult du dispositif actuel des evalu IDA / 58060 Post Open 24,000.00 33,076.77 Completed 2019-07-07 2019-07-09 2019-08-21 2019-09-11 2019-09-11 2019-11-21 2019-10-16 2019-12-11 2020-04-13 2021-02-26 or all ant Selection ations formatives (devoirs de classe et departementaux, c ompositions mensuelles, trim estrielles, et examens blancs /tests ) dans le systeme educ CG-PRAASED-103- CS-CI-201 Improving system performa Individual Consult 9 / Auditeur Interne : Recrute IDA / 58060 Prior Open 228,000.00 0.00 Canceled 2019-07-08 2019-08-26 2019-09-16 2019-10-21 2020-04-18 nce ant Selection ment d'un auditeur interne d u PRAASED CG-PRAASED-109-CS-CI-201 9 / SIGE : Schema directeurs Improving system performa Individual Consult Recrutement d'un consultant IDA / 58060 Post Open 80,000.00 112,081.22 Completed 2019-08-12 2019-10-23 2019-09-30 2020-02-04 2019-10-21 2020-03-27 2019-11-25 2020-06-27 2020-05-23 2021-03-31 nce ant Selection international en charge de l'e laboration du schéma directe ur du SIGE. CG-PRAASED-110-CS-CI-201 9 / Carte Scolaire- Recruteme Improving system performa Individual Consult nt d'un consultant internatio IDA / 58060 Post Open 80,000.00 0.00 Canceled 2019-08-13 2019-10-24 2019-10-01 2019-10-22 2019-11-26 2020-05-24 nce ant Selection nal pour l'appui à l'équipe ch argé de l'élaboration de la ca rte scolaire CG-PRAASED-111-CS-CI-201 9 / IGEPSA- Recrutement du consultant international pour Improving system performa Individual Consult le renforcement des capacité IDA / 58060 Post Open 60,000.00 0.00 Canceled 2019-08-15 2019-09-03 2019-10-03 2019-10-24 2019-11-28 2020-05-26 nce ant Selection s de l'IGEPSA: appui à la réda ction du manuel de procédur e d'inspection et d'encadrem ent pédagogique et formatio ns CG-PRAASED- 108 BIS-CS-CI- 2019 / INRAP- Recrutement d ’un consultant International p Improving system performa Individual Consult IDA / 58060 Post Open 20,000.00 30,150.18 Signed 2019-08-16 2019-10-31 2019-10-04 2020-03-27 2019-10-25 2020-08-10 2019-11-29 2020-08-11 2020-05-27 our une assistance a élaborat nce ant Selection ion d’une feuille de route et d ’un plan stratégique de l’INR AP Page 6 CG-PRAASED-107 BIS-CS-ED- 2019 / ENI/ENS - Recrutemen t d’un Consultant Internation Improving system performa Individual Consult IDA / 58060 Post Limited 40,000.00 0.00 Canceled 2019-08-15 2019-10-02 2019-08-20 2019-09-10 2019-10-15 2020-04-12 al pour une assistance a l’ela nce ant Selection boration d’une feuille de rout e et d’un plan strategique de ENI/ENS CG-PRAASED-112-CS-ED-201 9 / DFC - Contrat de service a vec M. BALONGA Moise ,Cons Improving system performa Individual Consult IDA / 58060 Post Direct 20,000.00 0.00 Canceled 2019-09-17 2019-10-01 2019-09-27 2019-10-18 2019-11-22 2020-05-20 ultant national en charge de l nce ant Selection 'assistance a élaboration d’u ne feuille de route et d’un pla n strategique de la DFC CG PRAASED-096-CS-CI-201 9 / Recrutement d'un consult ant international chargé d'ap Improving system performa Individual Consult pui au renforcement des cap IDA / 58060 Post Open 30,000.00 0.00 Canceled 2019-11-17 2020-01-05 2020-01-26 2020-03-01 2020-08-28 nce ant Selection acites des partie prenantes ( cabinet MEPSA, APE, ONGs...) sur la gestion de l'ecole, le m erite et la recevabilite. CG-PRAASED-0115-CS-IND-2 020 / - Contrat Coordo- Reno Improving system performa Individual Consult uvellement du contrat de ser IDA / 58060 Post Direct 174,000.00 0.00 Canceled 2020-01-15 2020-02-12 2020-01-25 2020-02-15 2020-02-15 2020-02-17 2020-03-21 2020-09-17 nce ant Selection vice du Coordonnateur de l'U nité de Coordination du Proje t PRAASED. CG-PRAASED-0113-CS-CI-20 19 / ENI-ENS/DFC : Recrutem ent d'un consultant internati onal chargé d'appuiaux équi Improving system performa Individual Consult IDA / 58060 Post Open 60,000.00 0.00 Canceled 2019-10-24 2019-11-14 2019-12-12 2020-01-02 2020-02-06 2020-08-04 pes techniques, à l'élaboratio nce ant Selection n des feuilles de route pour l a mise en oeuvre des recom mandations des études réalis ées ENI-ENS/DFC. CG-PRAASED-0117-CS-ED-20 20 / Feuille MEPSA-DDEPSA : Recrutement d’un consultant international chargé d’appui Improving system performa Individual Consult aux équipes techniques, à l’é IDA / 58060 Post Direct 40,000.00 0.00 Canceled 2020-03-11 2020-03-19 2020-03-21 2020-03-19 2020-04-11 2020-05-16 2020-11-12 nce ant Selection laboration des feuilles de rou tes et plans stratégiques pou r la mise en œuvre des reco mmandations des études réa lisées MEPSA –DDEPSA CG-PRAASED-0119-CS-CI-20 20 / Elaboration PPA: Recrute ment d'un consultant nationa Providing quality education f Individual Consult IDA / 58060 Post Open 40,000.00 16,613.49 Completed 2020-03-11 2020-03-13 2020-04-29 2020-06-12 2020-05-20 2020-08-10 2020-06-24 2020-08-15 2020-12-21 2021-07-31 l chargé de l’élaboration d’u or all ant Selection n plan d’action en faveur des populations autochtones du PRAAESD CG-PRAASED-0118-CS-ED-20 20 / FGB-COGES: Recruteme nt d'un consultant internatio Providing quality education f Individual Consult nal, spécialiste n formation, e IDA / 58060 Post Direct 50,000.00 113,489.30 Signed 2020-03-20 2020-03-18 2020-03-30 2020-03-19 2020-04-20 2020-09-29 2020-05-25 2020-10-01 2020-11-21 or all ant Selection n gestion à la base (FGB) pou r la mise en place des comité s de Gestion scolaire (COGES ) CG-PRAASED-0116-CS-ED-20 20 / ENI-ENS/DFC- Recruteme nt d’un consultant internatio Improving scope, quality an nal chargé d’appui aux équip Individual Consult IDA / 58060 d management of human re Post Direct 40,000.00 33,199.26 Signed 2020-03-20 2020-03-19 2020-03-30 2020-03-19 2020-04-20 2021-01-07 2020-05-25 2021-01-12 2020-11-21 es techniques, à l’élaboration ant Selection sources des feuilles de routes et plan s stratégiques pour la mise e n œuvre des recommandatio ns des études réalisées ENI-E NS/ DFC CG-PRAASED-103 BIS-CS-CI- Improving system performa Individual Consult 2019 / Auditeur Interne - Rec IDA / 58060 Post Open 122,222.00 0.00 Canceled 2019-08-16 2019-10-24 2019-10-04 2019-12-13 2019-10-25 2019-11-29 2020-05-27 nce ant Selection rutement d'un Auditeur Inter ne du PRAASED PRAASED-092-CS-CI-2019 / Recrutement du consultant i nternational pour l'appui tec Providing quality education f Individual Consult IDA / 58060 Post Open 140,000.00 0.00 Canceled 2019-04-25 2019-06-13 2019-06-13 2019-07-04 2019-08-08 2020-02-04 hnique au processus de révis or all ant Selection ion des curricula (évaluation et la réécriture) des program mes du primaire et du secon daire CG-PRAASED-123-CS-ED-202 1 / Carte scolaire Consul Int - Improving system performa Recrutement d'un consultant IDA / 58060 Post Direct Selection Direct 66,667.00 54,100.00 Completed 2021-06-15 2021-01-14 2021-06-25 2021-03-26 2021-08-29 2021-06-15 2022-02-25 2022-05-03 nce international en charge de l'é laboration de la carte scolair e du MEPSA CG-PRAASED-126-CS-ED-202 1 / Guides pedagogiques- Ac compagnement pour la suite du processus de revision des Providing quality education f curricula pour les classes de IDA / 58060 Post Direct Selection Direct 60,000.00 46,931.85 Signed 2021-06-21 2022-02-01 2021-07-01 2022-03-23 2021-09-04 2022-03-26 2022-03-03 or all ce1, ce2, cm1, cm2, 4eme et 3eme ainsi que la conception des guides et des cahiers d’a ctivites des programmes edu catifs revises pour le primair ee CG-PRAASED- -124-CS-INDV- 2021 / Carte scolaire Consul Nat - Recrutement d'un cons Improving system performa Individual Consult IDA / 58060 Post Open 2,000.00 12,188.88 Completed 2021-06-15 2021-01-14 2021-08-03 2021-04-12 2021-08-24 2021-04-30 2021-09-28 2021-06-15 2022-03-27 2022-05-03 ultant national pour appui au nce ant Selection consultant international en c harge de l'élaboration de la c arte scolaire du MEPSA. CG-PRAASED-0128-CS-INDV- 2021 / Formateurs nationaux . - Recrutement de 5 consult Improving scope, quality an ants nationaux chargés de l’é Individual Consult IDA / 58060 d management of human re Post Limited 20,000.00 0.00 Canceled 2021-08-27 2021-09-10 2021-09-01 2021-09-22 2021-10-27 2022-04-25 laboration du guide et outils ant Selection sources de formation des enseignant s et inspecteurs et de la form ation des formateurs au mani ement des nouveaux progra mmes Page 7 CG-PRAASED-0127-CS-INDV- 2021 / Graphiste - Recrutem ent d’un graphiste pour l’éla Improving system performa Individual Consult boration des guides illustres IDA / 58060 Post Limited 8,000.00 4,657.84 Signed 2021-08-23 2021-09-10 2021-08-28 2021-04-26 2021-09-18 2021-09-13 2021-10-23 2021-09-17 2022-04-21 nce ant Selection des 3 modules de formation en gestion a la base (FGB) du programme d’institutionnalis ation des COGES CG-PRAASED-0133-CS-INDV- 2021 / Formateur Sylvain MB UYAMBA - Recrutement d'un consultant international char Improving scope, quality an Individual Consult gé de l’élaboration du guide IDA / 58060 d management of human re Post Direct 15,000.00 14,193.58 Completed 2021-08-27 2021-09-09 2021-09-06 2021-09-08 2021-09-27 2021-09-13 2021-11-01 2021-09-26 2022-04-30 2022-05-03 ant Selection et outils de formation des en sources seignants et inspecteurs et d e la formation des formateur s au maniement des nouveau x programmes. CG-PRAASED-0131-CS-INDV- 2021 / Formateur KATSUNGA - Recrutement d'un consulta Improving scope, quality an nt international chargé de l’é Individual Consult IDA / 58060 d management of human re Post Direct 15,000.00 14,193.58 Completed 2021-08-27 2021-09-09 2021-09-06 2021-09-16 2021-09-27 2021-09-25 2021-11-01 2021-09-26 2022-04-30 2022-05-03 laboration du guide et outils ant Selection sources de formation des enseignant s et inspecteurs et de la form ation des formateurs au mani ement des nouveaux progra mmes. CG -PRAASED 0129-CS -INDI V-2021 / Formateur IBUTCH - Recrutement d'un consultant Improving scope, quality an international chargé de l’élab Individual Consult IDA / 58060 d management of human re Post Direct 15,000.00 14,193.58 Completed 2021-08-27 2021-09-10 2021-09-06 2021-09-09 2021-09-27 2021-09-13 2021-11-01 2021-09-26 2022-04-30 2022-05-03 oration du guide et outils de f ant Selection sources ormation des enseignants et inspecteurs et de la formatio n des formateurs au maniem ent des nouveaux programm es. CG-PRAASED-0130-CS-INDV- 2021 / Formateur NKONGOL O - Recrutement d'un consult Improving scope, quality an ant international chargé de l’ Individual Consult IDA / 58060 d management of human re Post Direct 15,000.00 14,193.58 Completed 2021-08-27 2021-09-09 2021-09-06 2021-09-08 2021-09-27 2021-09-13 2021-11-01 2021-09-26 2022-04-30 2022-05-03 élaboration du guide et outils ant Selection sources de formation des enseignant s et inspecteurs et de la form ation des formateurs au mani ement des nouveaux progra mmes. CG-PRAASED-0132-CS-INDV- 2021 / Formateur Roger MBO UYAMBA TSIUNZA - Recrutem ent d'un consultant internati Improving scope, quality an Individual Consult onal chargé de l’élaboration IDA / 58060 d management of human re Post Direct 15,000.00 14,193.58 Completed 2021-08-27 2021-09-09 2021-09-06 2021-09-16 2021-09-27 2021-09-13 2021-11-01 2021-09-26 2022-04-30 2022-05-03 ant Selection du guide et outils de formatio sources n des enseignants et inspect eurs et de la formation des fo rmateurs au maniement des nouveaux programmes. CG-PRAASED-0134-CS-INDV- 2021 / Animateurs AGC- FGB : Recrutement de 12 animate Improving system performa Individual Consult Under Implement IDA / 58060 Post Open 40,000.00 0.00 2021-09-14 2021-09-10 2021-11-02 2021-11-23 2021-12-28 2022-06-26 urs en gestion communautair nce ant Selection ation e pour accompagner les com munautés éducatives au nive au primaire. CG-PRAASED-0135-CS-INDV- 2021 / Formateurs FGB : Recr Improving system performa Individual Consult Under Implement IDA / 58060 Post Open 40,000.00 0.00 2021-09-14 2021-09-10 2021-11-02 2021-11-23 2021-12-28 2022-06-26 utement de 12 formateurs F nce ant Selection ation GB du niveau primaire CG-PRAASED-0136-CS-ED-20 21 / Editoriale CA- Recruteme nt d'un consultant pour l'app ui à la mise en conformité éd Providing quality education f itoriale des Cahiers d'activit IDA / 58060 Post Direct Selection Direct 100,000.00 23,924.06 Completed 2021-10-30 2021-11-05 2021-11-09 2021-11-04 2022-01-13 2021-11-11 2022-07-12 2022-02-27 or all és issus des nouveaux progr ammes éducatifs révisés, en deux phases (phase 1: CP1, CP2, 6è et 5è et phase 2 : C E1, CE2, CM1, CM2, 4è et 3è) CG-PRAASED-0138-CS-ED-20 21 / CA - YAZBECK- Recrutem ent d’une Assistance techniq Providing quality education f ue pour la mise en conformit IDA / 58060 Post Direct Selection Direct 6,560.00 5,670.00 Completed 2021-11-10 2021-11-11 2021-11-20 2021-11-09 2022-01-24 2021-11-11 2022-07-23 2022-07-09 or all é éditoriale des cahiers d’acti vités issus des nouveaux pro grammes éducatifs révisés d e CP1, CP2, 6ème et 5ème. CG-PRAASED-0139-CS-ED-20 21 / CA- TARCELIN- Recrutem ent d’une Assistance techniq Providing quality education f ue pour la mise en conformit IDA / 58060 Post Direct Selection Direct 3,570.00 3,395.40 Completed 2021-11-10 2021-11-11 2021-11-20 2021-11-10 2022-01-24 2021-11-11 2022-07-23 2021-12-16 or all é éditoriale des cahiers d’acti vités issus des nouveaux pro grammes éducatifs révisés d e CP1, CP2, 6ème et 5ème CG-PRAASED-0140-CS-ED-20 21 / CA- RENARD - Recrutem ent d’une Assistance techniq Providing quality education f ue pour la mise en conformit IDA / 58060 Post Direct Selection Direct 2,975.00 2,841.75 Completed 2021-11-10 2021-11-11 2021-11-20 2021-11-04 2022-01-24 2021-11-11 2022-07-23 2022-03-01 or all é éditoriale des cahiers d’acti vités issus des nouveaux pro grammes éducatifs révisés d e CP1, CP2, 6ème et 5ème. CG-PRAASED-0141-CS-ED-20 21 / CA- MIOLA- Recrutement d’une Assistance technique p Providing quality education f our la mise en conformité édi IDA / 58060 Post Direct Selection Direct 4,760.00 4,546.80 Completed 2021-11-10 2021-11-11 2021-11-20 2021-11-04 2022-01-24 2021-11-11 2022-07-23 2022-07-09 or all toriale des cahiers d’activités issus des nouveaux program mes éducatifs révisés de CP1 , CP2, 6ème et 5ème CG-PRAASED-0142-CS-ED-20 21 / CA- MILLET : Recruteme nt d’une Assistance techniqu e pour la mise en conformité Providing quality education f IDA / 58060 Post Direct Selection Direct 2,711.00 2,580.50 Completed 2021-11-10 2021-11-11 2021-11-20 2021-12-09 2022-01-24 2021-11-11 2022-07-23 2022-07-09 éditoriale des cahiers d’activi or all tés issus des nouveaux progr ammes éducatifs révisés de CP1, CP2, 6ème et 5ème (Ch ristian MILLET). Page 8 CG-PRAASED-0143- CS-ED-2 021 / CA-Gabrielle Debbas- R ecrutement d’une Assistance technique pour la mise en co Providing quality education f IDA / 58060 Post Direct Selection Direct 1,785.00 1,701.00 Completed 2021-11-10 2021-11-11 2021-11-20 2021-11-09 2022-01-24 2021-11-11 2022-07-23 2022-07-09 nformité éditoriale des cahier or all s d’activités issus des nouve aux programmes éducatifs ré visés de CP1, CP2, 6ème et 5 ème . CG-PRAASED -0144-CS-ED-2 021 / CA- GUGES : Recrutem ent d’une Assistance techniq Providing quality education f ue pour la mise en conformit IDA / 58060 Post Direct Selection Direct 7,615.00 7,250.88 Completed 2021-11-10 2021-11-11 2021-11-20 2021-11-08 2022-01-24 2021-11-11 2022-07-23 2022-07-09 or all é éditoriale des cahiers d’acti vités issus des nouveaux pro grammes éducatifs révisés d e CP1, CP2, 6ème et 5ème. CG-PRAASED-0145- CS-ED-2 021 / CA-DAUBIGNARD : Recr utement d’une Assistance te Providing quality education f chnique pour la mise en conf IDA / 58060 Post Direct Selection Direct 5,946.00 5,659.00 Completed 2021-11-10 2021-11-11 2021-11-20 2021-11-10 2022-01-24 2021-11-11 2022-07-23 2022-07-09 or all ormité éditoriale des cahiers d’activités issus des nouveau x programmes éducatifs révi sés de CP1, CP2, 6ème et 5è me. CG-PRAASED-0146-CS-ED-20 21 / CA-HORRENBERGER- Re crutement d’une Assistance t Providing quality education f echnique pour la mise en con IDA / 58060 Post Direct Selection Direct 3,211.00 3,046.95 Completed 2021-11-10 2021-11-11 2021-11-20 2021-11-10 2022-01-24 2021-11-11 2022-07-23 2022-07-09 or all formité éditoriale des cahiers d’activités issus des nouveau x programmes éducatifs révi sés de CP1, CP2, 6ème et 5è me. CG-PRAASED-0147-CS-ED-20 21 / CA- AYMARD : Recrutem ent d’une Assistance techniq Providing quality education f ue pour la mise en conformit IDA / 58060 Post Direct Selection Direct 7,615.00 6,820.20 Completed 2021-11-10 2021-11-10 2021-11-20 2021-11-04 2022-01-24 2021-11-11 2022-07-23 2022-07-09 or all é éditoriale des cahiers d’acti vités issus des nouveaux pro grammes éducatifs révisés d e CP1, CP2, 6ème et 5ème. CG-PRAASED-0150-CS-INDV- 2022 / IBUTCH Valère Renf. C apacités -Recrutement du co nsultant international du renf Improving scope, quality an Individual Consult orcement pour renforcement IDA / 58060 d management of human re Post Direct 11,581.00 9,212.87 Signed 2022-03-11 2022-03-17 2022-03-21 2022-03-25 2022-04-11 2022-03-25 2022-05-16 2022-04-14 2022-11-12 ant Selection du pool des formateurs et pe sources rsonnel d'encadrement en ch arge de la formation décentr alisée dans le maniement de s nouveau programmes (IBU TCH Valère). CG-PRAASED-0151CS-INDV- 2022 / Roger MBUYAMBA Ren f. Capacités- Recrutement du consultant international pour Improving scope, quality an Individual Consult le renforcement du pool des f IDA / 58060 d management of human re Post Direct 11,581.00 9,220.26 Signed 2022-03-11 2022-03-17 2022-03-21 2022-03-25 2022-04-11 2022-03-30 2022-05-16 2022-04-14 2022-11-12 ant Selection ormateurs et personnel d'enc sources adrement en charge de la for mation décentralisée dans le maniement des nouveau pro grammes éducatifs (MBUYAM BA Roger) ; CG-PRAASED-152-CS-INDV-2 022 / Sylvain MBUYAMBA Re nf. Capacités- Recrutement d u consultant international po Improving scope, quality an Individual Consult ur le renforcement du pool d IDA / 58060 d management of human re Post Direct 11,581.00 9,220.26 Signed 2022-03-11 2022-03-17 2022-03-21 2022-03-24 2022-04-11 2022-03-25 2022-05-16 2022-04-14 2022-11-12 ant Selection es formateurs et personnel d' sources encadrement en charge de la formation décentralisée dans le maniement des nouveau p rogrammes éducatifs (MBUY AMBA Sylvain) CG-PRAASED-0153-CS-INDV- 2022 / KATSUNGA Renf. Capa cités- Recrutement du consul tant international du renforce Improving scope, quality an Individual Consult ment du pool des formateurs IDA / 58060 d management of human re Post Direct 11,581.00 9,212.87 Signed 2022-03-11 2022-03-17 2022-03-21 2022-03-25 2022-04-11 2021-09-13 2022-05-16 2022-04-14 2022-11-12 ant Selection et personnel d'encadrement sources en charge de la formation dé centralisée dans le manieme nt des nouveau programmes éducatifs (KATSUNGA) CG-PRAASED-0154-CS-INDV- 2022 / NKONGOLO Renf. Cap acités - Recrutement du cons ultant international pour le re Improving scope, quality an Individual Consult nforcement du pool des form IDA / 58060 d management of human re Post Direct 11,581.00 9,212.87 Signed 2022-03-11 2022-03-17 2022-03-21 2022-03-25 2022-04-11 2022-03-24 2022-05-16 2022-04-14 2022-11-12 ant Selection ateurs et personnel d'encadr sources ement en charge de la forma tion décentralisée dans le ma niement des nouveau progra mmes éducatifs (NKONGOLO ) CG-PRAASED- 0155-CS-ED-2 022 / SIGE- ACSI - Mise en pl ace des modules 1, 2 et 4 (g estion des établissements, d Improving system performa Under Implement es ressources humaines et e IDA / 58060 Post Direct Selection Direct 350,000.00 0.00 2022-03-16 2022-03-17 2022-03-26 2022-05-30 2022-11-26 nce ation xamen et concours) du SIGE au sein du MEPPSA, avec l'a ppui de l'ACSI : Développeme nt, déploiement et et interfaç age à Stateduc de l’ISU. CG-PRAASED-0156-CS-ED -2 022 / SIGE ISU-Mise en place et opérationnalisation du mo dule 5 (Statistique et Aide à l Improving system performa Pending Impleme a décision) du SIGE-MEPPSA IDA / 58060 Post Direct Selection Direct 313,900.00 0.00 2022-03-21 2022-03-31 2022-06-04 2022-12-01 nce ntation avec l'assistance technique d e l'Institut de l'UNESCO (ISU) : mise en place, utilisation, in terfaçage avec les modules 1 ,2 et et 4 du SIGE, CG - PRAASED- 0160- CS-ED- 2022 / NDOUNGOU - Appui a u consultant international da Providing quality education f ns le cadre de la reecriture d IDA / 58060 Post Direct Selection Direct 12,510.00 11,147.99 Signed 2022-04-12 2022-03-23 2022-04-22 2022-03-07 2022-06-26 2022-04-09 2022-12-23 or all es programmes des classes CE1 àCM2 et 4ème a 3ème ( Consultant NDOUNGOU Jean Pierre) Page 9 CG-PRAASED- 0161-CS-ED-2 022 / NKOMBO - Appui au co nsultant international dans le Providing quality education f IDA / 58060 Post Direct Selection Direct 12,510.00 11,147.99 Signed 2022-04-12 2022-03-23 2022-04-22 2022-03-28 2022-06-26 2022-04-09 2022-12-23 cadre de la reecriture des pr or all ogrammes des classes CE1 a CM2 et 4ème a 3ème.(Cons ultant NKOMBO Edouard) CG-PRAASED-0162-CS-ED-20 22 / NDEBANI- Appui au cons ultant international dans le c Providing quality education f IDA / 58060 Post Direct Selection Direct 12,510.00 11,147.99 Signed 2022-04-12 2022-03-23 2022-04-22 2022-03-28 2022-06-26 2022-04-09 2022-12-23 adre de la reecriture des pro or all grammes des classes CE1 a CM2 et 4ème a 3ème.(Cons ultant NDEBANI François) CG-PRAASED-0163-CS-ED-20 22 / NZENZA- Appui au consu ltant international dans le ca Providing quality education f IDA / 58060 Post Direct Selection Direct 12,510.00 11,147.99 Signed 2022-04-12 2022-03-23 2022-04-22 2022-03-25 2022-06-26 2022-04-09 2022-12-23 dre de la reecriture des progr or all ammes des classes CE1 a CM 2 et 4ème a 3ème.(Consulta nt NZENZA Jacqueline) CG-PRAASED-0164-CS-ED-20 22 / DIANSATOU- Appui au c onsultant international dans l Providing quality education f IDA / 58060 Post Direct Selection Direct 12,510.00 11,139.08 Signed 2022-04-12 2022-03-23 2022-04-22 2022-03-28 2022-06-26 2022-04-09 2022-12-23 e cadre de la reecriture des p or all rogrammes des classes CE1 a CM2 et 4ème a 3ème.(DIA SANTOU Jonas) CG-PRAASED-0165-CS-ED-20 22 / MAZIKOU- Appui au cons ultant international dans le c Providing quality education f IDA / 58060 Post Direct Selection Direct 12,510.00 11,147.99 Signed 2022-04-12 2022-03-23 2022-04-22 2022-03-25 2022-06-26 2022-04-09 2022-12-23 adre de la reecriture des pro or all grammes des classes CE1 a CM2 et 4ème a 3ème.(MAZI KOU Aimé Hubert CG-PRAASED-0166-CS-ED-20 22 / Editoriale PE- Mise en co nformité éditoriale et de mis Providing quality education f IDA / 58060 Post Direct Selection Direct 32,000.00 7,575.12 Signed 2022-06-10 2022-06-23 2022-06-20 2022-06-23 2022-08-24 2022-06-11 2023-02-20 e en pages de 6 guides-progr or all ammes Congo, Français, Mat hs et sciences, CP1-CP2 et 6è me -5ème. CG-PRAASED-0167-CS-ED-20 22 / Editoriale PE Daubignard - Mise en conformité éditorial Providing quality education f IDA / 58060 Post Direct Selection Direct 5,800.00 5,392.01 Signed 2022-06-27 2022-06-27 2022-07-07 2022-06-22 2022-09-10 2022-06-11 2023-03-09 e et de mise en pages de 6 g or all uides-programmes Congo, Fr ançais, Maths et sciences, CP 1-CP2 et 6ème -5ème. CG-PRAASED-0168-CS-ED-20 22 / Editoriale PE Guges- Mis e en conformité éditoriale et Providing quality education f IDA / 58060 Post Direct Selection Direct 4,330.00 4,028.49 Signed 2022-06-27 2022-06-27 2022-07-07 2022-06-22 2022-09-10 2022-06-11 2023-03-09 de mise en pages de 6 guide or all s-programmes Congo, França is, Maths et sciences, CP1-CP 2 et 6ème -5ème. CG-PRAASED-0169-CS-ED-20 22 / Editoriale PE-2 - Assistan ce technique, pour la mise e n conformité éditoriale des n Providing quality education f Direct - Internation ouveaux programmes éducat IDA / 58060 Post Direct Selection 25,000.00 21,738.68 Signed 2022-08-19 2022-08-19 2022-08-29 2022-08-08 2022-11-02 2022-08-21 2023-05-01 or all al ifs et guides pédagogiques d e CP1-CP2 pour le français et les sciences du primaire et le s classes de 6è et 5è pour les SVT de collège (phase 2). CG-PRAASED-0170-CS-ED-20 22 / NDOUNGOU -Phase 2- A ppui au consultant internatio Providing quality education f nal dans le cadre de la reecri IDA / 58060 Post Direct Selection Direct - National 12,000.00 0.00 Signed 2022-10-04 2022-10-07 2022-10-14 2022-07-14 2022-12-18 2023-06-16 or all ture des programmes des cla sses CE1 a CM2 et 4ème a 3 ème.(NDOUNGOU Jean Pierre ), Phase 2. CG-PRAASED-0171-CS-ED-20 22 / NKOMBO- Phase 2 - App ui au consultant international Providing quality education f Under Implement IDA / 58060 Post Direct Selection Direct - National 12,000.00 0.00 2022-10-04 2022-10-07 2022-10-14 2022-07-14 2022-12-18 2023-06-16 dans le cadre de la reecriture or all ation des programmes des classes CE1 a CM2 et 4ème a 3ème. (NKOMBO Edouard), Phase 2 CG-PTAASED-0172-CS-ED-20 22 / NDEBANI-Phase 2- Appui au consultant international d Providing quality education f Under Implement ans le cadre de la reecriture IDA / 58060 Post Direct Selection Direct - National 12,000.00 0.00 2022-10-04 2022-10-07 2022-10-14 2022-08-29 2022-12-18 2023-06-16 or all ation des programmes des classes CE1 a CM2 et 4ème a 3ème (Consultant NDEBANI Françoi s), Phase 2. CG- PRAASED-0173-CS-ED-2 022 / NZENZA- Phase 2- App ui au consultant international Providing quality education f dans le cadre de la reecriture IDA / 58060 Post Direct Selection Direct - National 12,000.00 0.00 Signed 2022-10-04 2022-10-07 2022-10-14 2022-07-14 2022-12-18 2023-06-16 or all des programmes des classes CE1 a CM2 et 4ème a 3ème (NZENZA Jacqueline), Phase 2; CG-PRAASED-0175-SC-ED-20 22 / MAZIKOU- Phase 2- App ui au consultant international Providing quality education f Under Implement dans le cadre de la reecriture IDA / 58060 Post Direct Selection Direct - National 12,000.00 0.00 2022-10-04 2022-10-07 2022-10-14 2022-10-07 2022-12-18 2023-06-16 or all ation des programmes des classes CE1 a CM2 et 4ème a 3ème (MAZIKOU Aimé Hubert), pha se 2. CG-PRAASED-0174-CS-ED-20 22 / DIANSATOU -Phase 2- Ap pui au consultant internation Providing quality education f Under Implement al dans le cadre de la reecrit IDA / 58060 Post Direct Selection Direct - National 12,000.00 0.00 2022-10-04 2022-10-17 2022-10-14 2022-08-29 2022-12-18 2023-06-16 or all ation ure des programmes des clas ses CE1 a CM2 et 4ème a 3è me (DIASANTOU Jonas); Phas e 2; Page 10 CG-PRAASED-0178- CS-ED-2 022 / PNEAS- Convention ave c la CONFEMEN pour la mise Providing quality education f Direct - Internation Under Implement à disposition de 3 consultant IDA / 58060 Post Direct Selection 145,622.00 0.00 2022-11-15 2022-11-09 2022-11-25 2023-01-29 2023-07-28 or all al ation s chargés de l'enquête natio nale sur l'évaluation et le ren forcement des capacités des membres du PNEAS. CG-PRAASED -0179- CS-ED-2 022 / ISU- DEP- Convention a vec ISU (UNESCO), pour la fo Improving system performa Direct - Internation Under Implement rmation des agents de la DEP IDA / 58060 Post Direct Selection 70,632.00 0.00 2022-11-16 2022-11-09 2022-11-26 2023-01-30 2023-07-29 nce al ation dans le calcul des indicateurs requis pour l'analyse de la pe rformance du système éduca tif. CG-PRAASED-0180- CS-CI-20 22 / 12 Vérificateurs - Recrut ement de 12 consultants en Providing quality education f Individual Consult Pending Impleme charge de la vérification des IDA / 58060 Post Limited 70,632.00 0.00 2022-11-15 2022-11-20 2022-12-11 2023-01-15 2023-07-14 or all ant Selection ntation supports pédagogiques et m atériels didactiques distribué s par le PRAASED, dans les d épartements. CG-PRAASED-0181-CS-CI- 20 22 / LMD CI- Recrutement de Improving scope, quality an Individual Consult Open - Internationa Under Implement deux consultants internation IDA / 58060 d management of human re Post 108,200.00 0.00 2022-11-21 2022-11-16 2023-01-09 2023-01-30 2023-03-06 2023-09-02 ant Selection l ation aux en charge des contenus sources de formation en lien avec le s ysteme LMD . CG-PRAASED-0182- CS-CI-20 22 / LMD CN- Recrutement d Improving scope, quality an e deux consultants nationaux Individual Consult Under Implement IDA / 58060 d management of human re Post Open - National 52,500.00 0.00 2022-11-21 2022-11-16 2023-01-09 2023-01-30 2023-03-06 2023-09-02 en appui aux consultants inte ant Selection ation sources rnationaux en charge des co ntenus de formation en lien a vec le système LMD. CG-PRAASED- 0179-CS-ED-2 023 / PE CE1-CM, 4è-3è -Phas e1- Mise en conformité éditor Providing quality education f Direct - Internation iale des programmes éducati IDA / 58060 Post Direct Selection 48,462.00 0.00 Canceled 2023-01-12 2023-01-22 2023-03-28 2023-09-24 or all al fs et guides pédagogiques, Fr ançais, Maths et Sciences, de s classes de CE1-CE2, CM1-C M2, 4è-3è (phase1). CG-PRAASED-0180-CS-ED-20 23 / PE CE-CM,4è-3è- Mise en conformité éditoriale des pro Providing quality education f Direct - Internation grammes éducatifs et guides IDA / 58060 Post Direct Selection 90,000.00 0.00 Canceled 2023-01-31 2023-01-26 2023-02-10 2023-04-16 2023-10-13 or all al pédagogiques, Français, Mat hs et Sciences, des classes d e CE1-CE2, CM1-CM2, 4è-3è ( phase1). CG-PRAASED-0181-CS-ED-20 23 / PE+CA - CE-CM, 4è-3è -- Mise en conformité éditoriale des programmes éducatifs et Providing quality education f Direct - Internation Under Implement IDA / 58060 Post Direct Selection 172,500.00 0.00 2023-02-07 2023-02-07 2023-02-17 2023-01-16 2023-04-23 2023-10-20 guides pédagogiques en Fran or all al ation çais, Maths et Sciences, et de s cahiers d’activités des class es de CE1-CE2, CM1-CM2, 4è -3è (phase1+phase2), CG-PRAASED-0182-SC-ED-20 23 / Etats généraux- Recrute ment d’un consultant interna Improving scope, quality an Direct - Internation Under Implement tional dans le cadre de l’app IDA / 58060 d management of human re Post Direct Selection 17,500.00 0.00 2023-02-22 2023-02-23 2023-03-04 2023-05-08 2023-11-04 al ation ui du PRAASED aux etats gen sources eraux de l’education national e, de la formation et de la re cherche CG-PRAASED-0183-CS-ED-20 23 / Recrutement par entent Improving system performa Under Implement e avec l'ACSI pour le Dévelop IDA / 58060 Post Direct Selection Direct - National 240,276.00 0.00 2023-03-20 2023-03-22 2023-03-30 2023-06-03 2023-11-30 nce ation pement, la mise en place et l e déploiement du SIGE CG-PRAASED-0186-CS-ED-20 23 / Recrutement d’un consul tant international pour l’appu Improving system performa Direct - Internation Under Implement IDA / 58060 Post Direct Selection 5,708.00 0.00 2023-03-31 2023-05-05 2023-04-10 2023-06-14 2023-12-11 i thématique aux états génér nce al ation aux de l’éducation nationale, de la formation et de la rech erche CG-PRAASED-0187-CS-ED-20 23 / Recrutement d’un cabin Improving scope, quality an et d’expertise comptable pou Direct - Internation Under Implement IDA / 58060 d management of human re Post Direct Selection 16,336.00 0.00 2023-03-30 2023-04-06 2023-04-09 2023-06-13 2023-12-10 r l’audit des comptes du PRA al ation sources ASED pour les exercices 202 2 (exercice plein) et 2023 (cl os au 30 juin 2023) CG-PRAASED-0188-CS-ED-20 23 / Recrutement du consult Improving scope, quality an ant international pour le renf Direct - Internation Under Implement IDA / 58060 d management of human re Post Direct Selection 23,709.00 0.00 2023-04-03 2023-04-06 2023-04-13 2023-06-17 2023-12-14 orcement des capacités tech al ation sources nique des membres de l'équi pe du projet "assurance-quali té" CG-PRAASED-0190-CS-ED-20 Improving scope, quality an Direct - Internation Pending Impleme 23 / Convention avec l'ISU su IDA / 58060 d management of human re Post Direct Selection 72,500.00 0.00 2023-04-10 2023-04-20 2023-06-24 2023-12-21 al ntation r le calcul des indicateurs sources CG-PRAASED-0196-CS-ED-20 23 / Recrutement d’une agen ce n° 1 de paiement des part icipants à la formation décen Improving system performa Under Implement IDA / 58060 Post Direct Selection Direct - National 53,042.00 0.00 2023-04-17 2023-04-17 2023-04-27 2023-07-01 2023-12-28 tralisée des enseignants au nce ation maniement des nouveaux pr ogrammes éducatifs de CE1- CM2 et 4ème -3ème : Groupe ment MAOUENE CG-PRAASED-0197-CS-ED-20 23 / Recrutement de l’agenc e 1 de paiement des particip Improving system performa Under Implement ants à la formation décentrali IDA / 58060 Post Direct Selection Direct - National 83,702.00 0.00 2023-04-17 2023-04-17 2023-04-27 2023-07-01 2023-12-28 nce ation sée des enseignants au mani ement des nouveaux progra mmes éducatifs de CE1-CM2 et 4ème -3ème : EXPRESS U NION Page 11 CG-PRAASED-0202-CS-CI-20 23 / Recrutement d'un consul Individual Consult IDA / 58060 Unallocated Post Limited 192,730.00 0.00 Canceled 2023-05-08 2023-05-08 2023-05-13 2023-06-03 2023-07-08 2024-01-04 tant en charge de l'élaboratio ant Selection n du rapport d'achèvement d u PRAASED CG-PRAASED-0185BIS-CS-CI- 2023 / Recrutement de 12 vé Providing quality education f Individual Consult IDA / 58060 Post Limited 70,632.00 0.00 Canceled 2023-04-13 2023-04-18 2023-05-09 2023-06-13 2023-12-10 rificateurs indépendants des or all ant Selection supports pédagogiques distri bués CG-PRAASED-0203-CS-ED-20 23 / Recrutement de 12 vérifi cateurs indépendants de l’eff Providing quality education f Under Implement IDA / 58060 Post Direct Selection Direct - National 70,632.00 0.00 2023-05-24 2023-06-02 2023-06-03 2023-08-07 2024-02-03 ectivité de la distribution et u or all ation tilisation des programmes éd ucatifs et cahiers d’activités dans les 12 départements CG-PRAASED-0202BIS-CS-ED Improving scope, quality an -2023 / Recrutement d'un co Direct - Internation Under Implement IDA / 58060 d management of human re Post Direct Selection 43,772.00 0.00 2023-05-31 2023-05-31 2023-06-10 2023-08-14 2024-02-10 nsultant en charge de l'élabo al ation sources ration du rapport d'achèvem ent du PRAASED CG-PRAASED-0204-CS-ED-20 23 / Recrutement d’une micr ofinance devant assurer la pr Improving system performa Under Implement ise en charge des participant IDA / 58060 Post Direct Selection Direct - National 3,187.00 0.00 2023-06-01 2023-06-01 2023-06-11 2023-08-15 2024-02-11 nce ation s à la formation décentralisé e des directeurs d’établissem ents scolaires au leadership et au management PRAASED-007-C-CI / manuel Individual Consult IDA / V0020 Unallocated Prior Open 22,000.00 0.00 Canceled 2017-03-27 2017-05-15 2017-06-05 2017-07-10 2018-01-06 exécution ant Selection PRAASED-010-C-CI / CI prep Individual Consult IDA / V0020 Unallocated Prior Open 60,000.00 0.00 Canceled 2017-04-20 2017-06-08 2017-06-29 2017-08-03 2018-01-30 ation DAO matériel didactiqu ant Selection e Page 12 Procurement Plan I. General 1. Project Information Country : Kenya Recipient : Republic of Kenya Project Name : National Agriculture and Rural Inclusive Growth Loan Credit No. : IDA 59000 2. Date of General Procurement Notice : 9th February 2018 3. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services 1. Thresholds for the Method of Procurement: Method of Procurement Thresholds for Method (US$ equivalent) Open International (Goods) Equal to or more than 3 million Open National ( Goods) – Open < $3 million Tender as per PPDA 2015 RFQ (Goods) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Open International (Works) Equal to or more than 15 million Open National (Works) - Open Less than 15 million Tender as per PPDA 2015 RFQ (works) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Method of Procurement Thresholds for Method (US$ equivalent) Open International (Non-consulting Equal to or More than 3 million Services) Open National (Non-consulting Less than 3 million Services) - Open Tender as per PPDA 2015 Direct Contracting No threshold; meet requirements of Bank’s Procurement Regulations Prior Review: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection (Project Procurement Risk Rating is “High”): (a) Goods, information technology and Non-consulting Services: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1.5 million (b) Works (including turnkey, supply & installation of plant and equipment and PPP); First procurement under the project irrespective of value and all procurements estimated to cost more than USD 5 million and The prior review thresholds will be reviewed during the implementation of the project and modified, based on the risk assessment. 2. For contracts subject to prior review, the Borrower shall seek the Bank’s no objection before agreeing to: a. an extension of the stipulated time for execution of a contract that has an impact on the planned completion of the project; b. any material modification of the scope of the Works, Goods, Non- consulting services or Consulting Services, or other significant changes to the terms and conditions of the contract; c. any variation order or contract amendment (except in cases of extreme urgency), including due to extension of time, that singly or combined with all previous variation orders or amendments, increases the original contract amount by more than 15% (fifteen percent); or d. the proposed termination of the contract. The Borrower / IA shall provide a copy of all amendments to the contract to the Bank for its records. 3. Prequalification Not Applicable Domestic Preference. The provision of domestic preference shall be applied in the procurement of goods following international market approach in accordance with Annex VI of the Regulations. Domestic preference shall not apply in the procurement of works. 4. Reference to Standard Procurement Documents Bank’s Standard RFB Goods and RFP Consulting Services dated July 2016 will be used as a base and incorporating suitable modifications and the same would be agreed with the Bank subject international competition. 5. Any Other Special Procurement Arrangements A. Procurement approach under CDD Approach by Communities: Applicable if stipulated in the PAD. B. When approaching the national market, as agreed in the Procurement Plan, the Open Tender procedure of Public Procurement and Asset Disposal Act 2015 and Regulations 2017 may be used. The specific Requirements for national open competitive procurement include the following: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. Other national procurement arrangements (other than national open competitive procurement), that may be applied by the Borrower (such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti-Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. In all cases, the national procurement procedures to be used shall give due attention to quality aspects. 6. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Selection methods of procurement of Consultants' Services (Firms): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Quality and Cost Based As per requirements of para 7.3 of the Selection (QCBS) Regulations Quality Based Selection As per requirements of para 7.8 to 7.10 (QBS) of the Regulations Selection based on a Fixed As per requirements of para 7.4 and 7.5 of the Budget (FBS) Regulations Selection Based on Least As per requirements of para 7.6 and 7.7 of the Cost Basis (LCS) Regulations Selection based on As per requirements of para 7.11 and 7.12 of Consultant’s Qualification the Regulations (CQ) Direct Must meet the requirements of Para 7.13 to 7.15 of the Regulations, and with prior agreement in PP with the Bank. The short list may consist of all National consultants in case the estimated cost is less than USD 300,000 Procurement methods for Selection of Individual Consultants (IC): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Open Competitive As per requirements of para 7.36 and 7.37 of Selection the Regulations Limited Competitive As per requirements of para 7.38 of the Selection Regulations Direct Must meet the requirements of Para 7.39 of the Regulations, and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Regulations Prior Review Thresholds: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 0.5 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.2 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. PROCUREMENT Kenya : National Agricultural and Rural Inclusive Growth Project PLAN General Information Country: Kenya 2019-10-03 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153349 GPN Date: 2018-02-09 Project Name: National Agricultural and Rural Inclusive Growth Project Loan / Credit No: IDA / 59000, IDA / Q9870 Meru County Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-MERU COUNTY-160797-C W-RFB / Construction of Ntha Supporting County Communi Single Stage - One E 2021-06-3 IDA / 59000 Post Request for Bids Open - National 1,000,000.00 872,679.74 Signed 2020-03-13 2020-04-01 2020-03-18 2020-04-29 2020-05-12 2020-05-29 2020-09-15 2020-07-03 2020-07-31 rene Banana Market and imp ty-Led Development nvelope 0 rovement of market adjacent roads KE-MERU COUNTY-188858-C W-RFQ / Office refurbishment ; Project Coordination and Ma Request for Quota Single Stage - One E 2020-11-2 IDA / 59000 Post Limited 5,000.00 0.00 Canceled 2020-08-28 2020-10-23 1. Floor Tiling nagement tions nvelope 2 2. Repair of office doors / rei nforcement 3. Painting { walls, ceiling, d oors} KE-MERU COUNTY-234278-C W-RFQ / improvement of spo Request for Quota Strengthening Producer Org rt roads at Kirimba, Gikiri an Request for Quota Single Stage - One E tions - Small Work 2021-10-2 IDA / 59000 anizations and Value Chain Post Limited 140,000.00 0.00 Canceled 2021-05-28 2021-07-23 d Kiamiriru . tions nvelope s (Emergency) SP 1 Development Involving construction of a ro D -Competitive ad crossing ( Box Culvert ) an d road grading. KE-MERU COUNTY-243393-C Strengthening Producer Org Request for Quota Request for Quota Single Stage - One E Pending Imp 2021-11-2 W-RFQ / construction of Box IDA / 59000 anizations and Value Chain Post Limited tions (Non Bank-S 29,000.00 0.00 2021-08-04 2021-08-28 tions nvelope lementation 6 Culvert at Kirimba in Mitungu Development PD) u Ward Request for Quota KE-MERU COUNTY-243397-C Strengthening Producer Org Request for Quota Single Stage - One E tions - Small Work Pending Imp 2021-11-2 W-RFQ / Grading and Graveli IDA / 59000 anizations and Value Chain Post Limited 18,700.00 0.00 2021-08-04 2021-08-28 tions nvelope s (Emergency) SP lementation 6 ng of Gikiriri road spot in Nti Development D -Competitive ma West Request for Quota KE-MERU COUNTY-243399-C Strengthening Producer Org Request for Quota Single Stage - One E tions - Small Work Pending Imp 2021-11-2 W-RFQ / Construction of road IDA / 59000 anizations and Value Chain Post Limited 52,000.00 0.00 2021-08-02 2021-08-26 tions nvelope s (Emergency) SP lementation 4 crossing at Kiamiriru Development D -Competitive KE-MERU COUNTY-265714-C Request for Quota W-RFQ / Construction of Mac Strengthening Producer Org Request for Quota Single Stage - One E tions - Small Work 2022-09-0 adamia Aggregation and Pro IDA / 59000 anizations and Value Chain Post Limited 105,746.35 0.00 Canceled 2022-01-15 2022-03-12 tions nvelope s (Emergency) SP 8 cessing Store for Tigania Mac Development D -Competitive adamia Cooperative society. KE-MERU COUNTY-266919-C W-RFQ / Construction of Irish Request for Quota Potato Collection Centre for Strengthening Producer Org Request for Quota Single Stage - One E tions - Small Work 2022-09-1 marketing, Agroprocessing a IDA / 59000 anizations and Value Chain Post Limited 94,958.93 0.00 Canceled 2022-01-22 2022-03-19 tions nvelope s (Emergency) SP 5 nd Agro Inputs Store for Ntiri Development D -Competitive miti Tumaini Cooperative So ciety. A Narigp funded Prod ucer Organization. KE-MERU COUNTY-293844-C W-RFB / Construction of Irish Potato collection center for m Request for Bids - Strengthening Producer Org arketing, agro processing an Single Stage - One E Small Works SPD Under Imple 2023-03-1 IDA / 59000 anizations and Value Chain Post Request for Bids Open - National 94,958.93 0.00 2022-05-23 2022-06-30 2022-05-28 2023-05-04 2022-07-09 2023-05-04 2022-08-08 2022-08-08 2022-09-12 d agro inputs store for Ntiri nvelope (1 envelope proce mentation 1 Development miti Tumaini coprative societ ss) y. A Narigp funded Producer or ganization. KE-MERU COUNTY-293846-C W-RFB / Construction of Mac National Procure adamia Aggregation and pro Strengthening Producer Org ment Document - Single Stage - One E Under Imple 2023-03-1 cessing store for Tigania Mac IDA / 59000 anizations and Value Chain Post Request for Bids Open - National 1 Envelope proce 105,746.35 0.00 2022-05-23 2022-07-15 2022-05-28 2023-05-10 2022-07-09 2022-08-05 2022-08-08 2022-09-12 2022-09-12 nvelope mentation 1 adamia coperative society. Development ss (Non Bank-SPD This is a Narigp funded Prod ) ucer Organization KE-MERU COUNTY-296705-C W-RFQ / Office renovations; Painting Request for Quota Project Coordination and Ma Request for Quota Single Stage - One E Pending Imp 2022-08-0 Tilling IDA / 59000 Post Limited tions (Non Bank-S 4,350.00 0.00 2022-06-10 2022-07-02 nagement tions nvelope lementation 1 Door/Window reinforcements PD) Ceiling works Roof leakage repairs KE-MERU COUNTY-300285-C Request for Bids - W-RFB / Construction of Bana Strengthening Producer Org Single Stage - One E Small Works SPD Under Imple 2023-04-1 na aggregation store for Nyo IDA / 59000 anizations and Value Chain Post Request for Bids Open - National 127,087.00 0.00 2022-06-22 2022-07-28 2022-06-27 2023-05-04 2022-08-08 2022-08-19 2022-09-07 2022-09-12 2022-10-12 nvelope (1 envelope proce mentation 0 mba ya Athi co- op Society in Development ss) Imenti Sourth Sub County. Request for Bids - KE-MERU COUNTY-314480-C Strengthening Producer Org Single Stage - One E Small Works SPD Under Imple 2023-05-2 W-RFB / construction of potat IDA / 59000 anizations and Value Chain Post Request for Bids Open - National 413,045.77 0.00 2022-09-09 2022-10-12 2022-09-30 2023-05-10 2022-10-21 2022-11-04 2022-11-25 nvelope (1 envelope proce mentation 4 o ambient store in Ntugi, Kibi Development ss) richia ward KE-MERU COUNTY-314489-C Request for Bids - Strengthening Producer Org W-RFB / Construction of Mac Single Stage - One E Small Works SPD Under Imple 2023-05-3 IDA / 59000 anizations and Value Chain Post Request for Bids Open - National 106,198.50 0.00 2022-09-09 2022-10-12 2022-09-30 2023-05-10 2022-10-21 2022-10-25 2022-11-04 2022-07-11 2022-12-02 adamia aggregation Center i nvelope (1 envelope proce mentation 1 Development n Kitheo, Akithi Ward ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MERU COUNTY-138551-G Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Open - National 500,000.00 0.00 Canceled 2019-10-13 2019-10-04 2019-12-08 2020-06-05 O-RFQ / Procurement of moto nagement tions nvelope rcycle Page 1 KE-MERU COUNTY-168215-G Project Coordination and Ma Request for Quota Single Stage - One E O-RFQ / Procurement of IP ba IDA / 59000 Post Limited 63,000.00 63,216.32 Completed 2020-04-24 2021-05-20 2020-05-17 2021-06-15 2020-05-31 2021-07-01 nagement tions nvelope sed audio visual teleconferen ce system KE-MERU COUNTY-168216-G Project Coordination and Ma Request for Quota Single Stage - One E O-RFQ / Network Router & Ne IDA / 59000 Post Limited 10,000.00 0.00 Canceled 2020-04-24 2020-05-17 2020-05-31 nagement tions nvelope twork Firewall KE-MERU COUNTY-168219-G Project Coordination and Ma Request for Quota Single Stage - One E O-RFQ / Movable/adjustable l IDA / 59000 Post Limited 3,000.00 0.00 Canceled 2020-04-24 2020-05-17 2020-05-31 nagement tions nvelope ow back office chairs KE-MERU COUNTY-168218-G Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 8,000.00 7,249.55 Completed 2020-04-24 2021-06-16 2020-05-17 2021-06-24 2020-05-31 2021-07-01 O-RFQ / Laptop Computers nagement tions nvelope KE-MERU COUNTY-188872-G Supporting Community-Driv Request for Quota Single Stage - One E O-RFQ / purchase of Motor cy IDA / 59000 Post Limited 80,000.00 0.00 Canceled 2020-09-12 2020-11-07 2020-12-05 en Development tions nvelope cles for use by field technical support staff KE-MERU COUNTY-206164-G Supporting Community-Driv Request for Quota Single Stage - One E O-RFQ / procurement of 25 N IDA / 59000 Post Limited 5,000.00 4,547.77 Completed 2020-12-22 2021-06-09 2021-01-12 2021-06-24 2021-01-26 2021-07-01 en Development tions nvelope O. Steel filing cabinets KE-MERU COUNTY-138551-G Supporting Community-Driv Request for Quota Single Stage - One E O-RFQ-2 / procurement of fiel IDA / 59000 Post Limited 80,000.00 48,804.36 Completed 2021-03-20 2021-03-02 2021-05-08 2021-05-20 2021-05-11 2021-12-02 en Development tions nvelope d motor bikes KE-MERU COUNTY-225960-G O-RFQ / procurement of Desk Supporting Community-Driv Request for Quota Single Stage - One E top Computers ( 20 NO) IDA / 59000 Post Limited 12,000.00 11,049.72 Completed 2021-04-16 2021-05-21 2021-06-11 2021-06-17 2021-07-02 2021-07-01 en Development tions nvelope procurement of Small Printer s ( 20 No ) for CDDC secretariat KE-MERU COUNTY-225962-G O-RFQ / procurement of table Supporting Community-Driv Request for Quota Single Stage - One E IDA / 59000 Post Limited 2,200.00 0.00 Canceled 2021-04-16 2021-06-11 2021-06-13 s 20No. en Development tions nvelope procurement of chairs 20NO . For CDDC secretariat KE-MERU COUNTY-296649-G O-DIR / Specially designed An droid tablet and smart digital Project Coordination and Ma Under Imple IDA / 59000 Post Direct Selection Direct 13,799.00 0.00 2022-05-31 2022-06-27 2022-06-05 2022-06-28 2022-06-15 2022-06-22 projector with agripreneurs nagement mentation digital platform license pre in stalled in the tablets. 12 kits KE-MERU COUNTY-296676-G Project Coordination and Ma Under Imple IDA / 59000 Post Direct Selection Direct 847.00 0.00 2022-05-30 2022-06-27 2022-06-04 2022-06-27 2022-06-14 2022-06-21 O-DIR / Ruka Device 2 no. nagement mentation KE-MERU COUNTY-296681-G Project Coordination and Ma Under Imple O-DIR / Procurement of 6 No. IDA / 59000 Post Direct Selection Direct 44,348.00 0.00 2022-05-30 2022-06-27 2022-06-04 2022-06-27 2022-06-14 2022-06-21 nagement mentation soil scanner kits KE-MERU COUNTY-296684-G Project Coordination and Ma Request for Quota Single Stage - One E Pending Impl O-RFQ / procurement of asso IDA / 59000 Post Limited 17,000.00 0.00 2022-07-05 2022-07-19 nagement tions nvelope ementation rted furniture and office equi pments KE-MERU COUNTY-300292-G Supporting County Communi Request for Quota Single Stage - One E Under Imple O-RFQ / Procurement of Total IDA / 59000 Post Limited 34,783.00 0.00 2022-07-09 2022-06-14 2022-08-03 2022-09-02 ty-Led Development tions nvelope mentation Station for survey works KE-MERU COUNTY-333417-G O-RFQ / Supply, Delivery, Inst Strengthening Producer Org allation, Commissioning, trai Request for Quota Single Stage - One E IDA / Q9870 anizations and Value Chain Post Limited 92,638.00 0.00 Canceled 2023-01-25 2023-03-18 2023-05-17 ning and testing of avocado tions nvelope Development processing line for Abogeta West Avocado Co-operative S ociety, Meru County KE-MERU COUNTY-362933-G O-RFQ / Supply and Delivery Supporting Community-Driv Request for Quota Single Stage - One E IDA / Q9870 Post Limited 21,770.68 0.00 Canceled 2023-05-29 2023-07-13 2024-01-09 of 20 number desktop compu en Development tions nvelope ters and 20 number printers KE-MERU COUNTY-362937-G O-RFB / Supply, Delivery, Inst Strengthening Producer Org allation, Commissioning, trai Single Stage - One E Under Imple IDA / Q9870 anizations and Value Chain Post Request for Bids Open - National 174,165.46 0.00 2023-05-26 2023-06-27 2023-05-31 2023-06-28 2023-07-12 2023-08-11 2023-09-15 2024-03-13 ning and testing of avocado nvelope mentation Development processing line for Abogeta West Avocado Co-operative S ociety, Meru County KE-MERU COUNTY-364638-G O-RFQ / Supply and delivery Supporting Community-Driv Request for Quota Single Stage - One E Pending Impl IDA / Q9870 Post Limited 10,822.51 0.00 2023-06-09 2023-08-04 2023-12-31 of 10 number desktop compu en Development tions nvelope ementation ters and 10 number printers f or CDDC SACCOs NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MERU COUNTY-317994-N Project Coordination and Ma Under Imple C-DIR / Provision of technolo IDA / 59000 Post Direct Selection Direct - National 17,530.00 0.00 2022-09-30 2022-12-15 2022-10-05 2022-12-14 2022-11-02 2023-01-31 nagement mentation gical services to farmers. KE-MERU COUNTY-302744-N Project Coordination and Ma Pending Impl C-DIR / Provision of technolo IDA / 59000 Post Direct Selection Direct - National 22,689.00 0.00 2022-09-30 2022-10-05 2022-11-02 2023-01-31 nagement ementation gical services to farmers KE-MERU COUNTY-342212-G O-DIR / Provision of M-shamb Project Coordination and Ma Under Imple IDA / Q9870 Post Direct Selection Direct - National 19,033.90 0.00 2023-02-22 2023-03-31 2023-02-27 2023-03-31 2023-04-03 2023-06-30 a licences for market technol nagement mentation ogy and famer sensitization a nd training Page 2 KE-MERU COUNTY-342216-G O-DIR / Procurement of Geos patial mapping system comp rising of farmer database, an Project Coordination and Ma Under Imple alytics dashboard and mobile IDA / Q9870 Post Direct Selection Direct - National 15,864.48 0.00 2023-02-22 2023-03-31 2023-02-27 2023-03-31 2023-04-03 2023-06-30 nagement mentation mapping application. Trainin g manuals development and production, capacity building and farmer mapping targetin g 2000 farmers KE-MERU COUNTY-342214-N C-DIR / Procurement of 8 aut Project Coordination and Ma Pending Impl omated credit scoring syste IDA / Q9870 Post Direct Selection Direct - National 27,235.77 0.00 2023-05-08 2023-05-13 2023-06-17 2023-09-30 nagement ementation m license, set up, installation , configuration of the Automa ted Credit Scoring sytem CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MERU COUNTY-182420-C S-CQS / Training planing and Supporting Community-Driv Consultant Qualifi Under Implement IDA / 59000 Post Open - National 50,000.00 0.00 2020-07-08 2020-10-06 2020-07-29 2020-09-11 2020-10-11 2020-11-15 2021-12-31 development consultancy ser en Development cation Selection ation vice for Banana value chain KE-MERU COUNTY-182422-C S-CQS / Training planning an Supporting Community-Driv Consultant Qualifi Under Implement IDA / 59000 Post Open - National 50,000.00 0.00 2020-07-08 2020-10-06 2020-07-29 2020-09-11 2020-10-11 2020-11-15 2021-12-31 d development consultancy f en Development cation Selection ation or Avocado value chain KE-MERU COUNTY-182425-C S-CQS / Training planning an Supporting Community-Driv Consultant Qualifi Under Implement IDA / 59000 Post Open - National 50,000.00 0.00 2020-07-08 2020-10-06 2020-07-29 2020-09-11 2020-10-11 2020-11-15 2021-12-31 d development of consultanc en Development cation Selection ation y service for Irish potato KE-MERU COUNTY-182429-C S-CQS / Training planning an Supporting Community-Driv Consultant Qualifi IDA / 59000 Post Open - National 50,000.00 0.00 Canceled 2020-07-08 2020-10-06 2020-08-17 2020-09-21 2021-12-31 d development of consultanc en Development cation Selection y service for Macademia KE-MERU COUNTY-246772-C S-CQS / Training planning an Supporting Community-Driv Consultant Qualifi Under Implement IDA / 59000 Post Open - National 50,000.00 0.00 2021-08-04 2020-10-06 2021-08-25 2021-10-08 2021-11-07 2021-12-12 2023-12-30 d development of consultanc en Development cation Selection ation y service for Macadamia' INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 Summarized Procurement Plan I. GENERAL Project information: Borrower: Government of Eswatini Project Name: Eswatini Water and Sanitation Access Project Project ID No: P 166697 Grant No.: Project Implementing Agency: Eswatini Water Services Corporation Bank’s approval Date of the Procurement Plan: May 27, 2019 Date of General Procurement Notice: Period covered by this procurement plan: 18 months II. Goods and Works and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by IDA as stated in the Procurement Regulations for IPF Borrowers: Thresholds for Procurement Methods and Prior Review Goods, Works and Non- Consulting Services Procurement Approaches and Methods (US$ Prior millions) Review Category Open Open Request for (US$ millions) International National Quotation (RfQ) Works ≥ 15 ≥7 <7 ≤ 0.2 Goods, IT, and non- ≥4 ≥1 <1 ≤ 0.1 consulting services 2. Reference to (if any) Project Operational/Procurement Manual: The Procurement Plan also forms part of the Project Implementation Manual approved on May 2019. 1 3. Procurement Packages with Methods and Time Schedule Procurement of Goods & Non-consulting Services Summary 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Comments No. Cost Preference by Bank US$ million (yes/no) (Prior / Post) Summary of the ICB 17 2 NIL Post Framework (Works) agreements Summary of the NCB Nil Nil NIL Nil NIL (Works) Summary of the ICB 5 1 NIL Prior Nil (Goods) Summary of the NCB NIL NIL NIL NIL NIL (Goods) Summary of the RfQ 0.2M 1 NIL NIL (Goods & Non- Consulting Services) Summary of the DC NIL NIL NIL NIL (Non-consulting services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in the Procurement Regulations for IPF Borrowers: Thresholds for Consultants Selection Methods and Prior Review Thresholds for Consultants Selection Methods and Prior Review for Consulting Services Category Prior Short List of National Consultants (US$ million) 2 Review Consulting Engineering and (US$ Services Construction Supervision millions) Consultants (Firms) ≥2 ≤ 0.1 ≤ 0.3 Individual Consultants ≥ 0.4 NA. NA. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of the Procurement Regulations for IPF Borrowers. 3. Terms of Reference (TOR) for all consultancy contracts as well as all direction selections, irrespective of the contract value, will be subject to prior review. 4. Any Other Special Selection Arrangements: N/A 5. Consultancy Assignments with Selection Methods and Time Procurement of Consulting Services Summary 1 2 3 4 5 6 Ref. No. Description of Estimated Package Review Comments Assignment Cost s by Bank (Prior / US$ million Post) Summary of 10.5 8 Post 1 Package Prior review contracts through QCBS Summary of 1.0 5 Post NIL contracts through CQS 3 Summary of NIL NIL NIL NIL contracts through IC 4 PROCUREMENT Eswatini : Kingdom of Eswatini: Water Supply and Sanitation Access Project PLAN General Information Country: Eswatini 2020-02-13 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166697 GPN Date: Project Name: Kingdom of Eswatini: Water Supply and Sanitation Access Project Loan / Credit No: IBRD / 90120 Eswatini water Services Corporation Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SZ-EWSC-231635-CW-RFB / Request for Bids - Construction of 3 No. Reserv Component 1: Resilient Wat Single Stage - One E Works (without pr 6,773,589.1 2023-05-1 IBRD / 90120 Prior Request for Bids Open - National 6,500,000.00 Signed 2021-06-20 2021-07-27 2021-07-14 2021-08-06 2021-08-27 2021-09-03 2021-09-10 2021-09-30 2021-11-12 2022-03-30 oirs and Pumpstation Along t er Access and Management nvelope equalification) SP 6 4 he Nhlangano Siphambanwe D ni Main (Package 2) SZ-EWSC-230735-CW-RFB / Request for Bids - Construction of the Eswatini Component 1: Resilient Wat Open - Internationa Single Stage - One E Works (without pr 23,393,199.8 2023-05-2 IBRD / 90120 Prior Request for Bids 0.00 Canceled 2021-07-02 2021-08-01 2021-07-30 2021-08-17 2021-09-10 2021-10-22 2021-10-01 2022-05-18 2021-11-26 Water Supply Project (Packag er Access and Management l nvelope equalification) SP 0 8 e 2) - Main Pipeline D SZ-EWSC-354043-CW-RFB / Request for Bids - Package 2 - Construction of Component 1: Resilient Wat Open - Internationa Single Stage - One E Works (without pr Under Imple 2024-09-2 IBRD / 90120 Prior Request for Bids 8,300,000.00 0.00 2023-04-11 2023-05-01 2023-04-23 2023-05-03 2023-06-11 2023-07-23 2023-09-21 Main Pipeline from Nhlangan er Access and Management l nvelope equalification) SP mentation 0 o to Siphambanweni D GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SZ-EWSC-165262-GO-RFQ / Vehicles for supervision of B Component 2: Improved San Request for Quota Single Stage - One E IBRD / 90120 Post Limited 200,000.00 133,316.10 Signed 2020-06-06 2020-07-31 2020-08-01 2020-11-18 2021-01-28 C and construction of sanitati itation Access tions nvelope on facilities (3 in total) SZ-EWSC-182776-GO-RFQ / Laptops for the Project Coord Component 3: Project Manag Request for Quota Single Stage - One E IBRD / 90120 Post Limited 5,400.00 3,990.71 Signed 2020-07-15 2020-07-31 2020-08-19 2021-02-25 2021-03-01 inator, Social Specialist and E ement tions nvelope nvironmental Specialist SZ-EWSC-222802-GO-RFQ / PPE for PIU and other project Component 3: Project Manag Request for Quota Single Stage - One E IBRD / 90120 Post Limited 5,333.00 6,938.72 Signed 2021-04-12 2021-07-21 2021-07-05 2021-11-27 2021-10-03 personnel including; Commu ement tions nvelope nity Liaison Officers, Sanitati on Technicians SZ-EWSC-259768-CW-RFB / Provision of IT equipment to enable operations of the CDI- Component 1: Resilient Wat Open - Internationa Single Stage - One E Under Imple IBRD / 90120 Post Request for Bids 700,000.00 0.00 2021-11-19 2022-06-23 2021-11-30 2022-06-28 2022-01-21 2022-08-05 2022-02-20 2022-10-17 2022-04-15 2022-10-12 E (Server, software, client co er Access and Management l nvelope mentation mputers, video conferencing equipment networking and fi rewall) SZ-EWSC-327154-GO-RFQ / Component 3: Project Manag Request for Quota Single Stage - One E IBRD / 90120 Post Open - National 20,000.00 0.00 Canceled 2022-12-12 2023-03-25 2023-05-24 Additional laptops for PIU ement tions nvelope SZ-EWSC-327270-GO-RFB / Provision of IT Equipment to enable operations of the CDI- Component 1: Resilient Wat Open - Internationa Single Stage - One E Under Imple IBRD / 90120 Post Request for Bids 600,000.00 0.00 2022-12-09 2023-02-01 2022-12-19 2023-02-01 2023-02-07 2023-03-17 2023-03-14 2023-05-04 2023-10-31 E (server, software, client co er Access and Management l nvelope mentation mputers, video conferencing equipment networking and fi rewall SZ-EWSC-339532-GO-DIR / L ot 4 - Supply and Configurati Component 1: Resilient Wat Direct - Internation Under Imple IBRD / 90120 Post Direct Selection 70,600.00 0.00 2023-02-14 2023-02-09 2023-04-15 2023-02-10 2023-05-27 2023-11-23 on of Office 365 license (50) er Access and Management al mentation with SharePoint configuration SZ-EWSC-346300-GO-RFQ / Component 3: Project Manag Request for Quota Single Stage - One E Under Imple Additional laptops for PIU an IBRD / 90120 Post Limited 20,000.00 0.00 2023-03-15 2023-03-23 2023-05-24 2023-06-23 ement tions nvelope mentation d Task Team SZ-EWSC-349691-GO-RFQ / Component 3: Project Manag Request for Quota Single Stage - One E Under Imple IBRD / 90120 Post Limited 5,000.00 0.00 2023-03-29 2023-03-22 2023-06-16 2023-07-16 Additional PPE for CLOs and ement tions nvelope mentation PIU NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SZ-EWSC-159501-CS-QCBS / Consultancy Services for Det ailed Engineering Designs an d Construction Supervision of Component 1: Resilient Wat Quality And Cost- Open - Internationa a water supply system from IBRD / 90120 Post 1,500,000.00 1,891,331.12 Signed 2020-03-12 2020-02-19 2020-04-01 2020-02-28 2020-05-12 2020-05-15 2020-06-24 2020-07-13 2020-08-18 2020-08-21 2020-10-06 2020-08-27 2020-10-21 2020-10-28 2022-10-21 er Access and Management Based Selection l Nhlangano to Siphambanwen i consisting of the constructio n of water supply reservoirs, a pumping & gravity main, w ater network and kiosks. SZ-EWSC-162076-CS-QCBS / Component 2: Improved San Quality And Cost- Open - Internationa IBRD / 90120 Post 1,000,000.00 0.00 Canceled 2020-06-01 2020-05-28 2020-06-22 2020-07-14 2020-07-27 2020-09-28 2020-09-07 2020-11-20 2020-10-07 2021-02-08 2020-11-11 2020-12-10 2022-12-10 Behavior Change Campaign itation Access Based Selection l Page 1 SZ-EWSC-165260-CS-QCBS / Component 1: Resilient Wat Quality And Cost- Open - Internationa National Water Supply & Sani IBRD / 90120 Prior 5,000,000.00 0.00 Signed 2020-06-07 2020-08-14 2020-06-28 2020-09-02 2020-08-11 2021-09-08 2020-09-08 2021-11-26 2020-10-08 2022-05-19 2020-11-12 2022-10-10 2020-12-17 2023-04-18 2022-06-18 er Access and Management Based Selection l tation Masterplan SZ-EWSC-185139-CS-QCBS / NDMA - Comprehensive prep aration and update of multi-s ectoral drought preparednes Component 1: Resilient Wat Quality And Cost- Open - Internationa s and contingency plans for E IBRD / 90120 Post 700,000.00 0.00 Canceled 2020-08-04 2020-08-09 2020-08-25 2020-09-02 2020-09-23 2021-02-05 2020-10-21 2021-03-26 2020-11-05 2021-04-27 2020-12-03 2021-01-07 2022-07-09 er Access and Management Based Selection l swatini - To develop operatio nal drought management pla ns for all of the 14 city counci ls and town boards througho ut the Kingdom of Eswatini. SZ-EWSC-221188-CS-QCBS / NDMA - Development of Com Component 1: Resilient Wat Quality And Cost- Open - Internationa Under Implement IBRD / 90120 Prior 1,000,000.00 0.00 2021-03-09 2021-08-18 2021-04-08 2021-08-25 2021-05-22 2022-01-21 2021-06-21 2022-03-11 2021-07-21 2022-09-26 2021-09-01 2023-05-26 2021-10-13 2023-03-17 prehensive Disaster and Vuln er Access and Management Based Selection l ation erability Risk Profiles for the Kingdom of Eswatini SZ-EWSC-257596-CS-QCBS / BCC - WASH (WATER, SANITA TION, AND HYGIENE) SOCIAL AND BEHAVIOURAL RESEARC Component 2: Improved San Quality And Cost- Open - Internationa H AND DEVELOP COMPLEME IBRD / 90120 Prior 1,500,000.00 0.00 Signed 2021-10-29 2021-10-27 2021-11-19 2021-11-16 2021-12-24 2022-05-12 2022-02-11 2022-06-17 2022-03-04 2022-09-21 2022-04-15 2022-11-28 2022-05-27 2023-05-27 itation Access Based Selection l NTARY WASH SOCIAL AND BE HAVIOURAL CHANGE CAMPAI GN/INTERVENTIONS IN TARG ETED AREAS OF THE SHISEL WENI REGION SZ-EWSC-259721-CS-QCBS / NDMA - Comprehensive prep aration and update of multi-s ectoral drought preparednes Component 1: Resilient Wat Quality And Cost- Open - Internationa Under Implement s and contingency plans for E IBRD / 90120 Prior 700,000.00 0.00 2021-11-19 2021-11-30 2021-12-10 2021-12-06 2022-01-14 2022-04-15 2022-03-04 2022-06-10 2022-03-25 2022-09-21 2022-04-29 2023-02-06 2022-06-17 2023-06-17 er Access and Management Based Selection l ation swatini - To develop operatio nal drought management pla ns for all of the 14 city counci ls and town boards througho ut the Kingdom of Eswatini. SZ-EWSC-342978-CS-QCBS / Component 1: Resilient Wat Quality And Cost- Open - Internationa Under Implement River Health Monitoring Plan IBRD / 90120 Post 42,000.00 0.00 2023-03-15 2023-03-15 2023-04-14 2023-03-21 2023-06-04 2023-07-02 2023-08-01 2023-10-01 2023-11-22 2024-06-19 er Access and Management Based Selection l ation for the Upper Mkhondvo Rive r SZ-EWSC-361497-CS-QCBS / Component 1: Resilient Wat Quality And Cost- Open - Internationa Under Implement Review of Water Act of 2003 IBRD / 90120 Prior 500,000.00 0.00 2023-06-09 2023-06-18 2023-07-09 2023-08-29 2023-09-26 2023-10-26 2023-11-30 2024-01-04 2025-01-03 er Access and Management Based Selection l ation - Consultancy Services INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SZ-EWSC-165230-CS-INDV / Component 2: Improved San Individual Consult Situational assessment of WA IBRD / 90120 Post Open 50,000.00 0.00 Canceled 2020-06-01 2020-06-30 2020-07-29 2020-08-19 2020-09-23 2021-01-21 itation Access ant Selection SH in Peri-Urban areas SZ-EWSC-165258-CS-INDV / Component 2: Improved San Individual Consult Institutional - Situational Ass IBRD / 90120 Post Open 50,000.00 0.00 Canceled 2020-06-01 2020-06-30 2020-07-29 2020-08-19 2020-09-23 2021-01-21 itation Access ant Selection essment of Institutional WAS H SZ-EWSC-186743-CS-INDV / Component 1: Resilient Wat Individual Consult EWSC - Resettlement Action IBRD / 90120 Post Open 43,750.00 18,439.79 Signed 2020-08-14 2020-09-14 2020-09-16 2020-11-03 2020-09-30 2021-01-18 2020-10-28 2021-04-13 2020-12-27 er Access and Management ant Selection Plan Preparation SZ-EWSC-201299-CS-INDV / Component 2: Improved San Individual Consult Peri Urban - WASH Situationa IBRD / 90120 Post Open 50,000.00 28,360.00 Signed 2020-11-06 2020-10-28 2021-01-10 2021-02-01 2021-01-31 2021-08-05 2021-03-16 2021-12-09 2021-07-14 itation Access ant Selection l Assessment SZ-EWSC-201306-CS-INDV / Component 2: Improved San Individual Consult Institutions - Situational Asse IBRD / 90120 Post Open 50,000.00 37,643.49 Signed 2020-11-06 2020-10-28 2021-01-10 2021-02-01 2021-01-31 2021-04-21 2021-03-16 2021-06-21 2021-07-14 itation Access ant Selection ssment of WASH SZ-EWSC-258242-CS-CDS / Component 1: Resilient Wat CDI-E Validation process with IBRD / 90120 Post Direct Selection Direct 100,000.00 0.00 Signed 2021-10-29 2021-11-30 2021-12-24 2022-01-18 2022-02-22 2022-08-21 er Access and Management local university SZ-EWSC-282865-CS-INDV / Component 1: Resilient Wat Individual Consult IBRD / 90120 Post Open 53,000.00 0.00 Canceled 2022-03-31 2022-03-21 2022-06-04 2022-06-25 2022-07-30 2023-03-31 IT Advisor Consultancy Servic er Access and Management ant Selection es SZ-EWSC-312641-CS-INDV / CONSULTANCY TO DRAFT A Component 1: Resilient Wat Individual Consult Open - Internationa IBRD / 90120 Prior 200,000.00 0.00 Canceled 2022-09-30 2022-10-09 2023-01-08 2023-02-12 2023-03-26 2023-05-10 NATIONAL DISASTER RISK FI er Access and Management ant Selection l NANCE STRATEGY FOR THE K INGDOM OF ESWATINI SZ-EWSC-352328-CS-INDV / Component 1: Resilient Wat Individual Consult Open - Internationa Under Implement IBRD / 90120 Post 15,000.00 0.00 2023-04-21 2023-04-14 2023-06-25 2023-07-16 2023-08-20 2023-11-26 RAP for Pipeline Laterals er Access and Management ant Selection l ation Page 2 PROCUREMENT PLAN (Textual Part) Project information: Republic of Marshall Islands Sustainable Energy Development Project P160910 Project Implementation agency: Marshalls Energy Company (MEC); Division of International Development Assistance-Ministry of Finance (DIDA- MOF) Date of the Procurement Plan: January 31, 2018 Period covered by this Procurement Plan: Feb 1, 2018 to July 31, 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Code of 1988, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1. The procurement is open to all eligible firms from any country; 2. The request for bids/request for proposals document shall require the Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting signed contracts, confirming application of, and compliance with, the Bank's Anti- Corruption Guidelines, including without limitation the Bank's right to sanction and the Bank's inspection and audit rights; 3. Publication of contract award information; 4. Rights for the Bank to review procurement documentation and activities; and 5. An effective complaints mechanism. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Work) Goods: is not applicable; Works: is not applicable. PROCUREMENT Marshall Islands : Sustainable Energy Development Project PLAN General Information Country: Marshall Islands 2018-08-10 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160910 GPN Date: 2017-10-30 Project Name: Sustainable Energy Development Project Loan / Credit No: IDA / D2610, IDA / V0640 Marshalls Energy Company Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MH-MEC-77891-CW-DIR / S & I of Ebeye Diesel Generator Renewable Energy Investme 2,596,484.0 Under Revie 2019-04-2 IDA / D2610 Prior Direct Selection Direct 1,100,000.00 2018-09-13 2018-09-25 2018-09-18 2018-09-26 2018-10-23 2019-06-04 s based on single sourcing d nts 0 w 1 ue to current emergency situ ation MH-MEC-74211-CW-RFB / S Renewable Energy Investme Open - Internationa Single Stage - One E 22,600,000.0 2019-10-2 & I of Integrated Solar PV-Sto IDA / D2610 Prior Request for Bids 0.00 Canceled 2019-01-01 2019-01-06 2019-02-17 2019-03-19 2019-04-23 nts l nvelope 0 0 rage-Control System-O & M S upport-Feeder MH-MEC-74213-CW-RFB / Su Renewable Energy Investme Open - Internationa Single Stage - One E 2019-10-2 pply and Installation of Diesel IDA / D2610 Prior Request for Bids 3,000,000.00 0.00 Canceled 2019-01-01 2019-01-06 2019-02-17 2019-03-19 2019-04-23 nts l nvelope 0 Gen Sets at Majuro MH-MEC-96579-CW-RFB / Su pply and Installation of Solar Renewable Energy Investme Open - Internationa Single Stage - One E 26,000,000.0 21,014,369. 2020-03-2 IDA / D2610 Prior Request for Bids Signed 2019-06-03 2019-09-02 2019-06-08 2019-10-17 2019-07-20 2019-11-27 2019-08-19 2020-08-04 2019-09-23 2020-11-19 PV System, Power Station Re nts l nvelope 0 84 1 furbishment and BESS MH-MEC-74212-CW-RFB / Im Promotion of Energy Efficien Open - Internationa Single Stage - One E 2020-12-1 plementation of Supply Side IDA / D2610 cy and Loss Reduction Progr Prior Request for Bids 1,200,000.00 0.00 Canceled 2020-03-01 2020-03-06 2020-04-17 2020-05-17 2020-06-21 l nvelope 8 Management am MH-MEC-123335-CW-RFB / S Promotion of Energy Efficien Open - Internationa Single Stage - One E 2021-01-1 upply and installation of air h IDA / D2610 cy and Loss Reduction Progr Post Request for Bids 200,000.00 0.00 Canceled 2020-04-01 2020-04-06 2020-05-18 2020-06-17 2020-07-22 l nvelope 8 andling units at Ebeye Hospit am al MH-MEC-73125-CW-RFB / S Renewable Energy Investme Open - Internationa Single Stage - One E 2019-06-0 IDA / D2610 Prior Request for Bids 1,100,000.00 0.00 Canceled 2018-08-15 2018-08-20 2018-10-01 2018-10-31 2018-12-05 & I of Ebeye Diesel Generator nts l nvelope 3 s GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MH-MEC-74214-GO-RFB / De Promotion of Energy Efficien Open - Internationa Single Stage - One E mand Side Management Ener IDA / D2610 cy and Loss Reduction Progr Prior Request for Bids 750,000.00 0.00 Canceled 2018-10-01 2019-04-17 2018-10-06 2019-05-20 2018-11-17 2018-12-17 2019-01-21 2019-07-20 l nvelope gy Efficiency Equipment am MH-MEC-85519-GO-RFQ / Off Technical Assistance, Capaci Request for Quota Single Stage - One E IDA / D2610 Post Limited 10,000.00 0.00 Canceled 2018-12-08 2019-02-02 2019-08-01 ice Equipment ty Building, and Project Man tions nvelope agement MH-MEC-85520-GO-RFQ / Off Technical Assistance, Capaci Request for Quota Single Stage - One E IDA / V0640 Post Open - National 15,000.00 7,787.16 Signed 2019-04-06 2020-04-15 2019-06-01 2020-04-21 2019-11-28 ice Equipment ty Building, and Project Man tions nvelope agement MH-MEC-119113-GO-RFQ / S Promotion of Energy Efficien Request for Quota Open - Internationa Single Stage - One E IDA / D2610 Post 60,000.00 77,387.09 Completed 2019-07-06 2019-08-28 2019-08-31 2020-04-20 2020-02-27 2020-12-10 upply of LED lights at Airport, cy and Loss Reduction Progr tions l nvelope Majuro am MH-MEC-126725-GO-RFQ / S upply and installation includi Promotion of Energy Efficien ng foundation, of total of four Request for Quota Open - Internationa Single Stage - One E IDA / D2610 cy and Loss Reduction Progr Prior 400,000.00 546,491.96 Signed 2019-09-21 2019-08-29 2019-11-16 2020-02-24 2020-05-14 nos. (Two nos. each for wast tions l nvelope am e water lift station 2 and lift s tation 3) of self-priming centr ifugal pump systems. MH-MEC-123334-GO-RFQ / P Promotion of Energy Efficien Request for Quota Open - Internationa Single Stage - One E rocurment of Electrical vehicl IDA / D2610 cy and Loss Reduction Progr Post 300,000.00 178,200.00 Signed 2020-04-06 2020-03-07 2020-06-01 2020-11-03 2020-11-28 tions l nvelope es for pilot project in majuro am MH-MEC-160488-GO-RFQ / P Promotion of Energy Efficien Request for Quota Open - Internationa Single Stage - One E rocurment of charging statio IDA / D2610 cy and Loss Reduction Progr Post 100,000.00 0.00 Canceled 2020-04-06 2020-03-07 2020-06-01 2020-11-28 tions l nvelope n for EV pilot project at majur am o MH-MEC-201642-GO-RFQ / P Promotion of Energy Efficien rocurement of Charging Stati Request for Quota Open - Internationa Single Stage - One E Under Imple IDA / D2610 cy and Loss Reduction Progr Post 100,000.00 0.00 2020-11-01 2020-11-11 2020-12-27 2021-06-25 on for EV Pilot Project at Maju tions l nvelope mentation am ro (Re-Issuance Oct 2020) MH-MEC-203886-GO-RFQ / S Renewable Energy Investme Request for Quota Open - Internationa Single Stage - One E IDA / D2610 Post 350,000.00 0.00 Signed 2021-01-06 2021-01-20 2021-03-03 2021-08-30 treetwalk Solar PV Pilot Proje nts tions l nvelope ct at Ebeye MH-MEC-203903-GO-RFQ / S Promotion of Energy Efficien Request for Quota Open - Internationa Single Stage - One E upply of portable meter testi IDA / D2610 cy and Loss Reduction Progr Post 40,000.00 0.00 Signed 2022-07-10 2022-08-29 2022-09-04 2023-03-03 tions l nvelope ng sets for KAJUR am MH-MEC-203902-GO-RFQ / S Promotion of Energy Efficien Request for Quota Open - Internationa Single Stage - One E IDA / D2610 Post 14,000.00 0.00 Signed 2022-07-13 2022-08-29 2022-09-07 2023-03-06 upply of Transformers cy and Loss Reduction Progr tions l nvelope am NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Page 1 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MH-MEC-73124-CS-QBS / Su Promotion of Energy Efficien Consultant Qualifi Open - Internationa pply Side Loss Reduction Stu IDA / D2610 cy and Loss Reduction Progr Post 100,000.00 276,339.00 Completed 2018-08-13 2018-08-15 2018-09-03 2018-08-16 2018-10-17 2019-06-05 2018-11-16 2019-06-10 2018-12-21 2019-06-19 2019-06-19 2020-12-30 cation Selection l dy in Ebeye am MH-MEC-74856-CS-CQS / de Technical Assistance, Capaci Consultant Qualifi sign of Future Generation Mix IDA / D2610 ty Building, and Project Man Prior Limited 500,000.00 0.00 Canceled 2019-01-07 2019-01-21 2019-02-20 2019-03-27 2019-09-23 cation Selection projects in Ebeye and the Ou agement ter Islands MH-MEC-85522-CS-QBS / De Renewable Energy Investme Quality Based Sel Open - Internationa IDA / D2610 Post 400,000.00 0.00 Canceled 2018-11-05 2018-11-26 2019-01-09 2019-02-06 2019-03-08 2019-04-07 2019-05-12 2020-05-11 sign of Solar Plants erection nts ection l MH-MEC-74853-CS-QCBS / S Renewable Energy Investme Quality And Cost- Open - Internationa IDA / D2610 Prior 600,000.00 907,249.00 Signed 2019-07-01 2019-09-02 2019-07-22 2019-09-10 2019-09-04 2020-11-09 2019-10-02 2020-04-10 2019-11-01 2020-11-16 2019-12-06 2020-12-02 2020-01-10 2020-12-25 2021-01-09 upervision of Solar plants ere nts Based Selection l ction MH-MEC-74855-CS-CQS / saf Technical Assistance, Capaci Consultant Qualifi e Guard Study for Future RE IDA / D2610 ty Building, and Project Man Post Limited 100,000.00 0.00 Canceled 2020-05-01 2020-05-15 2020-06-14 2020-07-19 2021-01-15 cation Selection projects in Ebeye and the out agement er Islands MH-MEC-74857-CS-CQS / Ins Promotion of Energy Efficien titutional Strengthening, reg Consultant Qualifi IDA / D2610 cy and Loss Reduction Progr Post Limited 250,000.00 0.00 Canceled 2020-01-01 2020-01-15 2020-02-14 2020-03-20 2020-09-16 ulatory Mechanism and Polic cation Selection am y Framework for Energy Effici ency MH-MEC-112295-CS-QBS / D Renewable Energy Investme Quality Based Sel Open - Internationa IDA / D2610 Post 400,000.00 480,100.00 Completed 2017-11-11 2017-12-02 2018-01-15 2018-02-12 2018-03-14 2018-04-13 2018-04-20 2018-05-01 2018-06-04 2019-04-30 2021-03-31 esign of Solar Plants nts ection l MH-MEC-203905-CS-CQS / B Technical Assistance, Capaci Consultant Qualifi Open - Internationa Pending Impleme usiness processes, training a IDA / D2610 ty Building, and Project Man Post 156,000.00 0.00 2024-01-01 2024-01-22 2024-03-06 2024-04-05 2024-05-10 2024-11-06 cation Selection l ntation nd capacity building services agement for KAJUR MH-MEC-357505-CS-CQS / O wner’s Engineer for Supervisi on for Review of Conceptual and Detailed Design & drawi Renewable Energy Investme Consultant Qualifi Open - Internationa Under Implement IDA / D2610 Prior 500,000.00 0.00 2023-05-03 2023-05-19 2023-05-24 2023-07-07 2023-08-06 2023-09-10 2024-03-08 ngs and Supervision (OES) of nts cation Selection l ation Demolition and Construction of Power Station 1 (PS1) buil ding at Marshalls Energy Co mpany (MEC) Power plant in Majuro MH-MEC-350170-CS-QBS / C onstruction Environmental an Renewable Energy Investme Quality Based Sel Open - Internationa IDA / D2610 Post 50,000.00 0.00 Canceled 2023-03-24 2023-05-21 2023-04-14 2023-05-28 2023-06-25 2023-07-25 2023-08-24 2023-09-28 2024-09-27 d Social Management Plan (E nts ection l SMP)-Majuro power Station 1 Refurbishment Work MH-MEC-365080-CS-CQS / F Technical Assistance, Capaci Consultant Qualifi Open - Internationa Pending Impleme easibility Study of Renewable IDA / D2610 ty Building, and Project Man Post 350,000.00 0.00 2024-01-01 2024-01-22 2024-03-06 2024-04-05 2024-05-10 2024-11-06 cation Selection l ntation Energy Integration to meet f agement uture demand. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MH-MEC-85524-CS-INDV / Se Technical Assistance, Capaci Individual Consult tup of O & M mechanism and IDA / D2610 ty Building, and Project Man Post Open 30,000.00 0.00 Canceled 2019-01-01 2019-02-19 2019-03-12 2019-04-16 2019-10-13 ant Selection implementation arrangement agement s MH-MEC-85525-CS-INDV / D Promotion of Energy Efficien Individual Consult emand side Management En IDA / D2610 cy and Loss Reduction Progr Post Open 50,000.00 0.00 Canceled 2018-11-05 2018-12-24 2019-01-14 2019-02-18 2019-08-17 ant Selection ergy Efficiency Study am MH-MEC-85530-CS-INDV / Pr Technical Assistance, Capaci Individual Consult IDA / D2610 Post Open 750,000.00 0.00 Canceled 2018-11-05 2018-12-24 2019-01-14 2019-02-18 2019-08-17 oject Manager ty Building, and Project Man ant Selection agement MH-MEC-110528-CS-INDV / P Technical Assistance, Capaci Individual Consult IDA / D2610 Prior Open 750,000.00 0.00 Canceled 2017-12-12 2018-01-30 2018-02-20 2018-03-12 2019-06-14 roject Manager ty Building, and Project Man ant Selection agement MH-MEC-85529-CS-INDV / Te Renewable Energy Investme Individual Consult chnical study for Majuro Dies IDA / D2610 Post Open 30,000.00 0.00 Canceled 2021-03-01 2021-04-19 2021-05-10 2021-06-14 2021-12-11 nts ant Selection el Generators MH-MEC-117774-CS-CDS / Pr Technical Assistance, Capaci IDA / D2610 Prior Direct Selection Direct 750,000.00 477,322.00 Signed 2019-06-03 2019-06-03 2019-06-13 2019-05-23 2019-08-17 2019-06-18 2020-02-13 oject Manager (renewal of co ty Building, and Project Man ntract) agement MH-MEC-123332-CS-INDV / A ssessment of Affordable Com Technical Assistance, Capaci Individual Consult pensation to Public Facilities IDA / D2610 ty Building, and Project Man Post Open 50,000.00 46,961.00 Completed 2019-08-01 2019-08-08 2019-09-19 2019-12-17 2019-10-10 2019-12-17 2019-11-14 2020-02-22 2020-05-12 2021-08-06 ant Selection for Grid Connected Solar PV agement plants under SEDeP at Majur o MH-MEC-123336-CS-INDV / P Technical Assistance, Capaci Individual Consult IDA / D2610 Post Open 150,000.00 105,000.00 Terminated 2019-08-01 2019-08-25 2019-09-19 2019-10-08 2019-10-10 2019-10-16 2019-11-14 2020-02-11 2020-05-12 roject Implementation Officer ty Building, and Project Man ant Selection agement MH-MEC-123331-CS-INDV / P Technical Assistance, Capaci Individual Consult IDA / D2610 Post Open 200,000.00 431,264.00 Completed 2019-08-01 2019-08-08 2019-09-19 2019-12-11 2019-10-10 2019-11-14 2020-02-29 2020-05-12 2022-06-08 ower Specialist ty Building, and Project Man ant Selection agement MH-MEC-203906-CS-CDS / F Renewable Energy Investme easibility Study for hybrid mi IDA / D2610 Post Direct Selection Direct 100,000.00 84,579.00 Completed 2020-12-15 2021-01-20 2020-12-25 2021-01-20 2021-02-28 2021-08-27 2021-08-27 2022-04-08 nts ni-grids project at Arno MH-MEC-221283-CS-INDV / P Technical Assistance, Capaci Individual Consult IDA / D2610 Post Open 105,000.00 0.00 Signed 2021-03-01 2021-03-11 2021-04-19 2021-10-06 2021-05-10 2023-01-20 2021-06-14 2021-12-11 roject Implementation Officer ty Building, and Project Man ant Selection agement MH-MEC-85527-CS-INDV / En Technical Assistance, Capaci Individual Consult IDA / D2610 Prior Open 300,000.00 0.00 Canceled 2019-10-01 2021-04-06 2019-11-19 2021-10-06 2019-12-10 2020-01-14 2020-07-12 ergy Advisor ty Building, and Project Man ant Selection agement MH-MEC-167280-CS-INDV / 2 Technical Assistance, Capaci Individual Consult IDA / D2610 Prior Open 400,000.00 0.00 Canceled 2020-12-14 2020-04-05 2021-02-01 2021-02-22 2021-03-29 2021-09-25 020 Fulltime Project Manager ty Building, and Project Man ant Selection agement MH-MEC-203907-CS-INDV / S Technical Assistance, Capaci Individual Consult enior Project Implementation IDA / D2610 ty Building, and Project Man Post Open 200,000.00 0.00 Canceled 2021-01-01 2020-12-21 2021-02-19 2021-03-12 2021-04-16 2021-10-13 ant Selection Officer/Assistant PM agement Page 2 MH-MEC-203908-CS-INDV / Technical Assistance, Capaci Individual Consult Open - Internationa Pending Impleme IDA / D2610 Post 150,000.00 0.00 2024-01-01 2024-02-19 2024-03-11 2024-04-15 2024-10-12 RE Integration Specialist ty Building, and Project Man ant Selection l ntation agement MH-MEC-345845-CS-CDS / F Technical Assistance, Capaci Direct - Internation Pending Impleme easibility Study for Hybrid Mi IDA / D2610 ty Building, and Project Man Post Direct Selection 100,000.00 0.00 2024-01-01 2024-01-11 2024-03-16 2024-09-12 al ntation ni-grids Project at Killi Island agement MH-MEC-363299-CS-INDV / E nvironmental and Social Man agement Plan (ESMP) Majuro Renewable Energy Investme Individual Consult Open - Internationa Under Implement IDA / D2610 Post 50,000.00 0.00 2023-06-05 2023-06-15 2023-07-24 2023-08-14 2023-09-18 2024-03-16 Power Station 1 (PS1) Demoli nts ant Selection l ation tion and Construction Works at Marshalls Energy Compan y (MEC) Power Plant in Majur o. Page 3 PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, Desert Locust Response Project, P173702 Project Implementation agency: Ministry of Agriculture, Ethiopia Date of the Procurement Plan: April 6, 2012 Period covered by this Procurement Plan: April 2020 to March 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Directives of the Federal and Regional Governments of Ethiopia, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. For national open competitive procurement the following requirement apply: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts; e. contracts with an appropriate allocation of responsibilities, risks, and liabilities; f. publication of contract award information; g. rights for the Bank to review procurement documentation and activities; h. an effective complaints mechanism; and i. maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Secondhand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable For national open competitive procurement the following requirement apply: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts; e. contracts with an appropriate allocation of responsibilities, risks, and liabilities; f. publication of contract award information; g. rights for the Bank to review procurement documentation and activities; h. an effective complaints mechanism; and i. maintenance of records of the Procurement Process. cable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. Since the project is an emergency response project the provisions of Procurement in Situations of Urgent Need of Assistance shall apply. PROCUREMENT Eastern and Southern Africa : Emergency Locust Response Program PLAN General Information Country: Eastern and Southern Africa 2022-10-12 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173702 GPN Date: 2020-12-03 Project Name: Emergency Locust Response Program Loan / Credit No: IDA / 66480 Wajir County Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-WAJIR COUNTY-320754-C Request for Quota Livelihoods Protection and R Request for Quota Single Stage - One E Pending Imp 2023-06-1 W-RFQ / DESILTING OF MATH IDA / 66480 Post Limited tions (Non Bank-S 82,710.00 0.00 2022-10-20 2022-12-15 ehabilitation tions nvelope lementation 3 O WATER PAN PD) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-WAJIR COUNTY-337474-G O-RFQ / Livestock Vaccinatio Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl n and supportive treatment.( IDA / 66480 Post Limited 80,512.08 0.00 2023-03-04 2023-04-29 2023-10-26 ehabilitation tions nvelope ementation vaccine SGP 365,000 doses,C PP 220,000 doses and albend azole 10% 1130kgs) KE-WAJIR COUNTY-325823-G O-RFQ / Provision of livestock Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl supplementary feeds(range c IDA / 66480 Post Limited 76,800.88 0.00 2023-05-29 2023-07-09 2024-01-05 ehabilitation tions nvelope ementation ubes).Wajir West,Tarbaj and Eldas. 2620 bags (50kgs) of range c ubes. KE-WAJIR COUNTY-325148-G O-RFQ / Provision of livestock supplementary feeds(range c Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66480 Post Limited 77,205.96 0.00 2023-05-29 2023-07-12 2024-01-08 ubes). ehabilitation tions nvelope ementation Wajir North, Wajir South and Wajir East. 2640 Bags (50kgs) of range c ubes. KE-WAJIR COUNTY-363296-G O-DIR / Livestock disease ma nagement. Livelihoods Protection and R Pending Impl IDA / 66480 Post Direct Selection Direct - National 30,872.97 0.00 2023-05-24 2023-05-29 2023-07-03 2023-12-30 purchase of 76,000 doses of ehabilitation ementation Blanthrax vaccines and vacci nation againist anthrax in ca mels NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 PROCUREMENT PLAN (Textual Part) Project information: INDIA, Punjab Municipal Services Improvement Project (P170811) Project Implementation agency: Punjab Municipal Infrastructure Development Corporation Date of the Procurement Plan (Textual Part): February 03, 2022 Period covered by this Procurement Plan (textual part): From February 03, 2022 till publication of next version of the Procurement Plan. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. Procurement for the project will be carried out in accordance with the World Bank’s Procurement Regulations for IPF Borrowers, November 2020 applicable to Investment Project Financing (IPF). The project will be subject to the World Bank’s Anticorruption Guidelines, dated October 15, 2006, as revised in January 2011 and July 2016. The table below describes various procurement methods to be used for activities financed by the loan. The thresholds (Error! Reference source not found.) indicated will govern the procurement approach and methods; Table 1: Procurement Approaches and Methods Procurement Approaches Thresholds (US$ equivalent) and Methods For any value activity Open international Open national (works – Up to 40 million including turnkey, supply and installation of plant and equipment and PPP) Open national (goods, IT Up to 10 million system, and non- consulting services) National request for Up to 100,000 quotation (works, goods, IT system and non-consulting services) Direct selection No threshold; For works, goods, non-consulting services and IT system procurement: According to paragraphs 6.8–6.10 of the Regulations; For consultants: According to paragraphs 7.13–7.15 of the Regulations National Market Approach Up to 2,000,000 for Selection of Consultants Prior Review Thresholds Works including Supply & All contracts more than or equal to US$ 10 million Installation of Plant and equivalent. Equipment Goods, IT system and Non- All contracts more than or equal to US$2 million consulting services equivalent Consultants All contracts (i) more than or equal to US$1 million equivalent for firms; and (ii) more than or equal to US$300,000 equivalent for individuals. Prior Review contracts Irrespective of the contract value, the following irrespective of value procurement activities are subject to the Bank’s procurement prior review: (a)procurement processes involving contract negotiations, as described in Section VI, paragraphs 6.34-36, of the Procurement Regulation for Borrowers (b) competitive dialogue; (c) sustainable procurement; (d) selection of probity assurance providers, as described in Section III, paragraph 3.3 of the Procurement Regulations for Borrowers; and (e) best and final offer. To help borrower undertake emergency procurement through faster means, market approaches and review requirements as defined below would be applicable only under component-3 and only for the period of emergency. Table2: Procurement Approaches & Methods for Component -03 applicable only for the emergency period Category of Market approach threshold Prior review procurement threshold (US $m) Works Above US$40 M for ICP Up to None for emergency US$40 M for NCP Up to US$1 M for period. Standard RFQ review procedure will Goods & Non- Above US$25 M for ICP Up to -do- after this period. apply Consultancy US$25 M for NCP Up to US$1 m for services RFQ Consultancy US$ 2.0 M for NPP (with option for -do- Services direct RFP) Above US$0.8 M-Other methods Note: Direct contracting/single source prior review will follow the requirements of the category of procurement (goods, works and services). Higher thresholds (US$ 25M for Goods NCP and US$ 1 M for RFQ) are applicable only for emergency response period, normal threshold (US$ 10M for Goods NCP and US$ 100,000 for RFQ will be used thereafter. Domestic preference- The provision of domestic preference for goods will be applied in the evaluation of bids in accordance with Annex VI of the Regulations. National Procurement Arrangements: National competition for the procurement of works, goods, IT system procurement and non-consulting services according to the established thresholds will be conducted in accordance with paragraphs 5.3–5.5 of Section V of the Regulations and the following provisions: 1. Only the model bidding documents for National Competitive Procurement (NCP) agreed with the GOI Task Force (and as amended for time to time), shall be used for bidding. 2. Invitations to bid shall be advertised on a widely used website or electronic portal with free open access at least 30 days prior to the deadline for the submission of bids, unless otherwise agreed in the approved procurement plan. 3. No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state- owned enterprises, small-scale enterprises or enterprises from any given State. 4. Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder. 5. Government e-Marketplace (GeM) set-up by Ministry of Commerce, Government of India will be acceptable for procurement under Request for Quotations (RFQ) method. 6. At the Borrower’s request, the Bank may agree to the Borrower’s use, in whole or in part, of its electronic procurement system, provided that the Bank is satisfied with the adequacy of such system. 7. Procurement will be open to eligible firms from any country. This eligibility shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 8. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals include a signed acceptance in the bid, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 9. The Borrower shall use an effective complaints mechanism for handling procurement related complaints in a timely manner. 10. Procurement Documents will include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts. Procurement of Works, Goods (Supply and Installation; and IT Equipment), Non-Consultancy Services and Consultancy Services – As per procurement plan approved in STEP. PROCUREMENT India : Punjab Municipal Services Improvement Project PLAN General Information Country: India 2020-05-07 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P170811 GPN Date: 2020-03-18 Project Name: Punjab Municipal Services Improvement Project Loan / Credit No: / , IBRD / 92260 Punjab Municipal Infrastructure Development Company Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-PMIDC-170785-CW-RFP / DBOT Contract for Water Tre Component 2: Improving Wa Request for Propo Open - Internationa Single Stage - Two E 209,520,000. 2033-07-1 / Prior 0.00 Canceled 2020-07-04 2020-07-14 2020-10-14 2020-12-27 2021-01-31 atment Plant, Transmission n ter Supply Infrastructure sals l nvelope 00 7 etwork and OHSR, Ludhiana IN-PMIDC-170755-CW-RFP / DBOT Contract for Water Tre Component 2: Improving Wa Request for Propo Open - Internationa Single Stage - Two E 152,150,000. 105,455,44 2033-05-1 / Prior Signed 2020-05-04 2020-07-07 2020-05-14 2020-07-13 2020-08-14 2020-10-14 2020-10-27 2021-03-04 2020-12-01 2021-04-30 atment Plant, Transmission n ter Supply Infrastructure sals l nvelope 00 3.06 7 etwork and OHSR, Amritsar Request for Propo IN-PMIDC-281361-CW-RFP / sal Works and Op Design, Build and Operation ( eration Service - DBO) for Water Treatment Pl Design, Build and ant (WTP) - 580 MLD and ass Component 2: Improving Wa Request for Propo Open - Internationa Single Stage - Two E Operation for Wat 202,330,000. Under Revie 2035-09-0 IBRD / 92260 Prior 0.00 2022-02-28 2022-06-06 2022-03-21 2022-10-05 2022-05-20 2023-03-06 2022-08-03 2022-09-07 ociated Transmission Networ ter Supply Infrastructure sals l nvelope er and Wastewate 00 w 6 k and Over Head Service Res r Treatment Plant ervoirs (OHSRs) in City of Lud s SPD (single-stag hiana, Punjab, India e) - Works SPD (si ngle-Stage- Applyi ng contractor disq IN-PMIDC-349628-CW-RFB / Request for Bids - ualificiation) Construction of Head Regulat Component 2: Improving Wa Single Stage - Two E Small Works SPD 2023-12-1 IBRD / 92260 Post Request for Bids Open - National 440,000.00 0.00 Canceled 2023-03-15 2023-03-30 2023-04-20 2023-05-31 2023-06-14 or and Cross Regulator for W ter Supply Infrastructure nvelope (2 envelope proce 1 ater Intake at 440MLD WTP, ss) Amritsar GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-PMIDC-363314-NC-DIR / S Component 3: COVID-19 Cris Pending Impl etting up of GIS based COVID IBRD / 92260 Post Direct Selection Direct - National 14,065.00 0.00 2023-06-05 2023-06-10 2023-07-15 2024-01-11 is Response ementation Dashboard CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-PMIDC-175698-CS-QCBS / Component 4: Project Manag Quality And Cost- Open - Internationa Supervision Consultancy for / Prior 1,790,000.00 0.00 Canceled 2020-06-15 2020-07-06 2020-08-19 2020-09-16 2020-10-16 2020-11-20 2020-12-25 2023-12-25 ement Based Selection l DBOT Contract, Amritsar IN-PMIDC-175785-CS-QCBS / Component 4: Project Manag Quality And Cost- Open - Internationa Supervision Consultancy fro / Prior 2,580,000.00 0.00 Canceled 2020-08-15 2020-09-05 2020-10-19 2020-11-16 2020-12-16 2021-01-20 2021-02-24 2024-02-24 ement Based Selection l DBOT Contract, Ludhiana IN-PMIDC-175791-CS-QCBS / Component 1: Strengthening Strengthening Municipal Rev Quality And Cost- / Urban Service Delivery Syst Post Open - National 150,000.00 0.00 Canceled 2020-12-01 2020-12-22 2021-02-04 2021-03-04 2021-04-03 2021-05-08 2021-06-12 2022-06-12 enue & Financial Cadre in Am Based Selection ems ritsar and Ludhiana Municipal Corporations IN-PMIDC-249518-CS-QCBS / Direct RFP for selection of In dependent Verification Agenc y (IVA) for the Projects of "DB Component 4: Project Manag Quality And Cost- O of 440 MLD WTP & associat IBRD / 92260 Post Open - National 747,709.36 926,135.47 Signed 2021-08-24 2021-07-27 2021-08-24 2021-09-07 2021-09-03 2021-09-28 2021-11-30 2021-10-13 2021-11-30 2021-10-27 2021-12-23 2021-11-24 2022-01-11 2025-03-23 ement Based Selection ed Transmission Network & O HSR in City of Amritsar and 5 80 MLD WTP and associated Transmission Network & OH SR in City of Ludhiana" IN-PMIDC-292634-CS-QCBS / Direct RFP for Hiring of Envir onment & Social Consultancy Firm for preparation of Enviro Component 4: Project Manag Quality And Cost- Under Implement nment and Social Impact Ass IBRD / 92260 Post Open - National 127,911.56 0.00 2022-04-28 2022-04-18 2022-04-28 2022-04-29 2022-05-18 2022-05-20 2022-07-11 2022-06-05 2022-07-25 2022-06-19 2022-08-26 2022-07-08 2023-04-07 ement Based Selection ation essment (ESIA), Environment and Social Management Plan (ESMP) and Resettlement Act ion Plan (RAP) for Amritsar a nd Ludhiana IN-PMIDC-175787-CS-QCBS / Establishing Asset Managem Component 1: Strengthening Quality And Cost- Under Implement ent and Capital Investment Pl IBRD / 92260 Urban Service Delivery Syst Post Open - National 545,000.00 0.00 2020-07-15 2023-03-21 2020-08-05 2023-05-24 2020-09-18 2020-10-16 2020-11-15 2020-12-20 2021-01-24 2022-01-24 Based Selection ation anning Framework and Syste ems ms in Amritsar and Ludhiana Municipal Corporations IN-PMIDC-355622-CS-QCBS / Direct RFP for Enhancement Component 1: Strengthening Quality And Cost- and strengthening of IT servi IBRD / 92260 Urban Service Delivery Syst Post Open - National 490,465.00 0.00 Under Review 2023-05-15 2023-05-12 2023-06-05 2023-07-19 2023-08-16 2023-09-15 2023-10-20 2023-11-24 2024-11-23 Based Selection ces under M-SEVA projects a ems nd strengthening of GRM in P MIDC Page 1 IN-PMIDC-356877-CS-QCBS / Direct RFP for Contract Mana Component 4: Project Manag Quality And Cost- Under Implement gement for DBO contracts in IBRD / 92260 Post Open - National 558,425.00 0.00 2023-04-30 2023-05-12 2023-05-21 2023-05-24 2023-07-04 2023-08-01 2023-08-31 2023-10-05 2023-11-09 2024-11-08 ement Based Selection ation Amritsar and Ludhiana for W TPs and associated transmiss ion networks and OHSR IN-PMIDC-356878-CS-QCBS / Direct RFP for Firm for Intern Component 4: Project Manag Quality And Cost- Pending Impleme IBRD / 92260 Post Open - National 36,785.00 0.00 2023-04-30 2023-05-21 2023-07-04 2023-08-01 2023-08-31 2023-10-05 2023-11-09 2024-11-08 al Auditing at PMU & Water U ement Based Selection ntation tilities at Ludhiana and Amrit sar INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-PMIDC-176285-CS-CDS / P reparation of Environmental & Social Assessment (ESA) fo r Amritsar City and Environm Component 4: Project Manag ental & Social Management F / Post Direct Selection Direct 91,536.44 89,516.69 Signed 2020-06-15 2020-01-25 2020-06-25 2020-01-31 2020-08-29 2020-02-01 2020-12-31 ement ramework (ESMF) for Ludhian a City, Environmental & Soci al Commitment Plans (ESCP) and Resettlement Action Plan / Policy Framework (RAP / RP F) IN-PMIDC-356880-CS-INDV / Component 1: Strengthening Individual Consult Pending Impleme IBRD / 92260 Post Open - National 73,575.00 0.00 2023-05-10 2023-06-28 2023-07-19 2023-08-23 2024-02-19 IT Manager in IT cell in PMIDC Urban Service Delivery Syst ant Selection ntation ems IN-PMIDC-356881-CS-INDV / Component 4: Project Manag Individual Consult Pending Impleme Water Expert (Water Supply IBRD / 92260 Post Open - National 81,745.00 0.00 2023-05-15 2023-07-03 2023-07-24 2023-08-28 2024-02-24 ement ant Selection ntation Projects) for a 3 year period i n PMIDC IN-PMIDC-356887-CS-INDV / Component 4: Project Manag Individual Consult Pending Impleme IBRD / 92260 Post Open - National 58,860.00 0.00 2023-04-25 2023-06-13 2023-07-04 2023-08-08 2024-02-04 Communication Specialist in ement ant Selection ntation PMIDC IN-PMIDC-356890-CS-INDV / Component 4: Project Manag Individual Consult Pending Impleme Chartered Accountant for Fin IBRD / 92260 Post Open - National 39,327.00 0.00 2023-05-10 2023-06-28 2023-07-19 2023-08-23 2024-02-19 ement ant Selection ntation ancial Management at PMIDC IN-PMIDC-356892-CS-INDV / Component 4: Project Manag Individual Consult Pending Impleme Accountant for Financial Man IBRD / 92260 Post Open - National 24,523.00 0.00 2023-05-20 2023-07-08 2023-07-29 2023-09-02 2024-02-29 ement ant Selection ntation agement at PMIDC IN-PMIDC-356893-CS-INDV / Component 4: Project Manag Individual Consult Pending Impleme Accountant for Financial Man IBRD / 92260 Post Open - National 24,523.00 0.00 2023-05-20 2023-07-08 2023-07-29 2023-09-02 2024-02-29 ement ant Selection ntation agement at PMIDC IN-PMIDC-356894-CS-INDV / Component 4: Project Manag Individual Consult Pending Impleme MIS Specialist (DBO Amritsar IBRD / 92260 Post Open - National 73,569.00 0.00 2023-05-10 2023-06-28 2023-07-19 2023-08-23 2024-02-19 ement ant Selection ntation Project) at PMIDC IN-PMIDC-356895-CS-INDV / Component 4: Project Manag Individual Consult Pending Impleme MIS Specialist (DBO Ludhiana IBRD / 92260 Post Open - National 73,569.00 0.00 2023-05-10 2023-06-28 2023-07-19 2023-08-23 2024-02-19 ement ant Selection ntation Project) at PMIDC Page 2 PROCUREMENT PLAN Version 1.8 – Date: February 16, 2022 INSTITUTIONAL STRENGTHENING FOR IMPROVED VILLAGE SERVICE DELIVERY PROJECT A. Project information: Country: Indonesia Borrower: Republic of Indonesia Project ID: P165543 Financing Agreement IBRD Loan 8941-ID Number: Project Implementation Agency(ies): CPMU: Ministry of Home Affairs (MOHA), Directorate General of Village Government Affairs CPIU: Ministry of Home Affairs (MOHA), Directorate General of Village Government Affairs Ministry of Villages, Directorate General of Village Development and Community Empowerment (PPMD) Ministry of National Development Planning/BAPPENAS, Deputy for Regional Development Directorate for the Development of Disadvantaged Regions, Transmigration and Rural Areas Coordinating Ministry of Human Development and Cultural Affairs (PMK), Deputy for Community Empowerment, Village and Regions B. Key Dates: 1. Procurement Plan: a. Version 1.0 (for Feb 28, 2019 negotiation) Bank’s Approval to this Mar 12, 2019 version: Period covered by this Apr 1, 2019 – December 31, version: 2020 b. Version 1.7 (previous June 17, 2021 version) Bank’s Approval to this June 21, 2021 version: Period covered by this Apr 1, 2019 – December 31, version: 2023 c. Version 1.8 (this version) Feb 16, 2022 Bank’s Approval to this Feb 21, 2022 version: Period covered by this Apr 1, 2019 – December 31, version: 2023 d. [next version, if any] [to be updated] 2. General Procurement Mar 26, 2020 Notice: C. Preamble All Procurement under the Project shall be carried out in accordance with the World Bank’s Procurement Regulations for IPF Borrowers of July 2016, revised November 2017 and August 2018, and the provisions of the Procurement Plan and Project Operations Manual and shall take precedence over any national procurement regulations. In accordance with paragraph 5.9 of the Procurement Regulations, the Bank’s online procurement planning and tracking tools i.e. Systematic Tracking and Exchanges in Procurement (STEP) will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. D. Key Provisions The following conditions apply to all procurement activities in this Procurement Plan. The Bank’s procurement prior review thresholds: The identified procurement risk under this Project is ‘Substantial’. Accordingly, all contracts listed in the Procurement Plan that are at or above the thresholds set out below are subject to the Bank’s prior review. All other contracts are subject to the Bank’s ex-post review. Table 1. Applied Prior Review Threshold Type of procurement Procurement Prior Review Thresholds (US$ millions) Works (including turnkey, supply & installation of 10 plant and equipment, and PPP) Goods, Information Technology and Non- 2 consulting Services Consultants: Firms 1 Consultants: Individuals 0.3 The Bank’s approved selection methods thresholds: The following selection method thresholds shall apply for procurement of goods & information technology, non-consulting services and consulting services of each identified activity. Table 2. Applied Approved Selection Method Threshold Type of procurement and Approved Selection Method Thresholds Approved Selection (US$ millions) Method National International Works (including turnkey, supply & installation of plant and equipment, and PPP) (i) Request for Request for at or above $0.2 and at or above $25 Bids (RFB) less than $25 (ii) Request for Quotations less than $0.2 N/A (RFQ) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 6.8, 6.9 paragraph 6.8, 6.9 and 6.10 of the and 6.10 of the Procurement Procurement Regulations Regulations Type of procurement and Approved Selection Method Thresholds Approved Selection (US$ millions) Method National International Goods, Information Technology and Non-consulting services a. For Goods and Information Technology: (i) Request for Request for at or above $0.1 and at or above $2 Bids (RFB) less than $2 (ii) Request for Quotations less than $0.1 N/A (RFQ) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 6.8, 6.9 paragraph 6.8, 6.9 and 6.10 of the and 6.10 of the Procurement Procurement Regulations Regulations b. For Non-consulting Services: (i) Request for Request for at or above $0.1 and at or above $10 Bids (RFB) less than $10 (ii) Request for Quotations less than $0.1 N/A (RFQ) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 6.8, 6.9 paragraph 6.8, 6.9 and 6.10 of the and 6.10 of the Procurement Procurement Regulations Regulations Consultants: firms a. For Selection of Consulting Firms (i) Quality Cost Based Shortlist of firms for at or above $0.4 Selection (QCBS), Fixed contracts below $0.4 Budget Based Selection may comprise (FBS), Least Cost Based entirely national Selection (LCS) and firms Quality Based Selection (QBS) (ii) Consultant’s less than $0.3 N/A Qualifications Based Selection (CQS) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per Type of procurement and Approved Selection Method Thresholds Approved Selection (US$ millions) Method National International paragraph 7.13, 7.14 paragraph 7.13, 7.14 and 7.15 of the and 7.15 of the Procurement Procurement Regulations Regulations b. For Selection of Individual Consultants (i) Open Competitive All, no monetary All, no monetary Selection of Individual threshold threshold Consultants and Limited Competitive Selection of Individual Consultants (ii) Direct Selection of On exceptional basis On exceptional basis Individual Consultants if justified as per if justified as per paragraph 7.39 of paragraph 7.39 of the Procurement the Procurement Regulations Regulations Standard Procurement Documents (SPD): The Bank’s SPD shall be used when approaching the international market (specifically for international competitive procurement and those contracts shall be as specified in the Procurement Plan tables in STEP. Use of National Procurement Procedures: In accordance with paragraphs 5.3 of the Procurement Regulations, when approaching the national market all contracts to be procured through open national competitive procurement will follow the GoI’s procurement regulation. The procedures applicable to the procurement of goods and non-consulting services awarded on the basis of open national competitive procurement shall be those of the Tender method as set forth in the Peraturan Presiden No. 16/2018 and its subsequent amendment Peraturan Presiden No. 12/2021) provided that such arrangements continue to meet requirements set forth under paragraph 5.4 of these Regulations and the following conditions: 1. The procurement is open to eligible firms from any country. There shall not any restriction to the bidders’ participation including mandatory requirement to form in joint venture; 2. Any gaps between National Procurement Procedures and the Procurement Regulations will be addressed and incorporated in the harmonized bidding documents acceptable by the Bank. Use of National e-Procurement System (SPSE): Unless informed otherwise by the Bank in writing, SPSE e-procurement system may be used only for procurement of works, goods and non-consulting services under Request for Bids (RFB) method through national open competitive procurement method, applying the harmonized model bidding documents for national open competitive procurement agreed by the Bank. For selection of consulting services through QCBS method, only the modified SPSE (termed by LKPP as SPSE-“ICB”) may be used applying the Bank’s Standard Request for Proposal (RFP) document. The Bank has further accepted GOI’s proposal for use of SPSE-ICB for selection of consulting services through CQS method applying a modified Bank’s Standard RFP. Two consulting services activities (contracts) under other Bank-financed project are being performed as pilot use of SPSE-ICB for CQS method to ensure that the system is working as intended. Since at the present time LKPP has not yet developed the modified SPSE for procurement of goods, works and non-consulting services under international open Competitive method, nor for selection of consulting services under QBS, LCS, FBS, and individual consultant selection methods, therefore procurement of all contract packages under these methods shall be carried out through non- electronic process with manual issuance of specific procurement notice (request for expression of interest or invitation for bids/proposals and receipt of bids/proposals), until such time that the modified SPSE has been completed by LKPP and assessed by the Bank to be acceptable. If the Bank determines the modified SPSE to be acceptable for use under the above- mentioned remaining procurement methods, the Bank will confirm through the Bank’s written no objection to LKPP and will also notify in writing to CMPU/CPIUs. Use of National e-Catalogue System. Based on the Bank’s assessment of the national e-catalogue system, the Bank allows the Project Implementing Units (PIUs) under World Bank financed projects to use the national e- catalogue for procurement of small value of goods in lieu of the Request for Quotations (RFQ) method specified in these Regulations within the parameters as below: a) For Goods (other than medicines) with estimated cost not more than USD 15,000 equivalent per contract. PIUs may use the national e-catalogue for procuring such items of goods within the above-specified threshold, if such goods are required under the project and specified in the Procurement Plan approved by the Bank. b) Goods (other than medicines) with estimated cost greater than USD 15,000 but less than USD 100,000 equivalent per contract. PIUs may use the national e-catalogue for procuring such items of goods if such goods are required under the project subject to fulfilling the following additional procedural requirement as below: PIU shall carry out a secondary procurement process through mini competition, by comparing the prices of similar goods offered by at least three different suppliers which available in the national e-catalogue and then selecting the Supplier with the lowest evaluated price on the basis of “as delivered" price at final destination (i.e., including inland transportation, insurance, applicable taxes and any other incidental charges for the delivery of the required quantity of goods at final destination). E. Other Relevant Procurement Information • Project Operations Manual (POM) shall set out the operating procedures for procurement and contract implementation matters under the Project written in Bahasa, which shall be consistent with the procedures and rules specified under the Bank’s Procurement Regulations. In case of any difference of interpretation between the POM and the Bank’s Procurement Regulations, the later shall prevail; • CPMU and CPIUs may use its own forms of contract for goods/non- consulting services procured under Request for Quotations (RFQ) method when approaching to national market, acceptable to the Bank; • Advance procurement may be applied under the project and shall be valid by signing of the Loan Agreement. CPMU and CPIUs may commence the procurement process prior to issuance of the DIPA for any anticipated activity to be procured under the Project, while signing of the contract shall be subject to issuance of the DIPA of the respective activity. All contracts shall not be designed as single-year contract, and therefore procurement process shall continue throughout multiple calendar years without limitation of contract period up to end of the GoI’s fiscal year; • Regardless of the Bank’s review requirement (prior or post), the Bank may review technical aspects of procurement documents and other non- procurement matters (terms of reference, statement of works, technical specifications, environmental documents, cost estimate, etc.) related to the procurement activity in question, if needed; • The Bank will continue to provide guidance and support to the CPMUs, and CPIUs for procurement processing through the STEP. • Project Implementation Support Personnel as defined in the PPSD shall not be included in this Procurement Plan. Their selection and hiring procedures shall continue to apply the GoI’s selection and hiring procedures as further defined in the POM. The Procurement Plan is a living document and can be revised if there are any changes during the implementation of the project. PROCUREMENT Indonesia : Institutional Strengthening for Improved Village Service Delivery PLAN General Information Country: Indonesia 2020-05-17 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P165543 GPN Date: 2020-03-26 Project Name: Institutional Strengthening for Improved Village Service Delivery Loan / Credit No: IBRD / 89410 DG Bina Pemdes, Ministry of Home Affairs Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-BINA PEMDES-263424-GO Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 14,000.00 0.00 2022-04-21 2022-04-29 2022-05-06 -RFQ / Printing of Unit SOP D nment Institutions tions nvelope ementation ocuments NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-BINA PEMDES-210159-NC -RFB / Administration Service Strengthening Village Gover Single Stage - One E Under Imple IBRD / 89410 Prior Request for Bids Open - National 36,000,000.00 0.00 2021-01-11 2021-12-22 2021-01-16 2021-02-06 2022-06-02 2021-03-08 2022-11-11 2021-03-12 2024-12-11 Firm (ASF) for Managing Cont nment Institutions nvelope mentation ract of Technical Assistance Supports (Region 1 - 7) ID-BINA PEMDES-245384-NC Strengthening Village Gover Single Stage - One E -RFB / Trainning of Trainner ( IBRD / 89410 Post Request for Bids Open - National 386,000.00 0.00 Canceled 2021-08-02 2021-08-05 2021-08-12 2021-08-17 2021-08-21 2021-09-20 nment Institutions nvelope TOT) Badan Permusyawarata n Desa ID-BINA PEMDES-245385-NC -RFB / Workshop Sosialisasi P Strengthening Village Gover Single Stage - One E IBRD / 89410 Post Request for Bids Open - National 147,000.00 0.00 Canceled 2021-08-03 2021-08-06 2021-08-13 2021-08-18 2021-08-22 2021-09-21 rogram Penguatan Pemerinta nment Institutions nvelope han dan Pembangunan Desa (P3PD) ID-BINA PEMDES-251710-NC -RFB / Event Organizer on Ap Strengthening Village Gover Single Stage - One E Pending Impl IBRD / 89410 Post Request for Bids Open - National 132,000.00 0.00 2021-09-12 2021-09-22 2021-09-29 2021-10-04 2021-10-10 2021-12-09 plication Based Technical Tra nment Institutions nvelope ementation ining on Rural Financial Mana gement ID-BINA PEMDES-309667-NC -RFQ / Facilitation and Syner Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl gy for Strengthening Village I IBRD / 89410 Post Limited 89,000.00 0.00 2022-08-23 2022-09-02 2022-09-09 nment Institutions tions nvelope ementation nstitutions In Women Empow erment and Improving The Q uality of Village Shopping ID-BINA PEMDES-319345-NC -RFQ / Training of Trainers for Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 95,000.00 0.00 2022-10-16 2022-10-26 2022-11-02 Village Governance Facilitato nment Institutions tions nvelope ementation r (PTPD) Region 1 ID-BINA PEMDES-319347-NC -RFQ / Training of Trainers for Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 94,800.00 0.00 2022-10-20 2022-10-30 2022-11-06 Village Governance Facilitato nment Institutions tions nvelope ementation r (PTPD) Region 2 ID-BINA PEMDES-319348-NC -RFQ / Training of Trainers for Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 94,000.00 0.00 2022-10-16 2022-10-26 2022-11-02 Village Governance Facilitato nment Institutions tions nvelope ementation r (PTPD) Region 3 ID-BINA PEMDES-319349-NC -RFQ / Training of Trainers for Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 96,500.00 0.00 2022-10-16 2022-10-26 2022-11-02 Village Governance Facilitato nment Institutions tions nvelope ementation r (PTPD) Region 5 ID-BINA PEMDES-319350-NC -RFQ / Training of Trainers for Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 95,000.00 0.00 2022-10-16 2022-10-26 2022-11-02 Village Governance Facilitato nment Institutions tions nvelope ementation r (PTPD) Region 4 ID-BINA PEMDES-319351-NC -RFQ / Training of Trainers for Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 96,700.00 0.00 2022-10-16 2022-10-26 2022-11-02 Village Governance Facilitato nment Institutions tions nvelope ementation r (PTPD) Region 6 ID-BINA PEMDES-319352-NC -RFQ / Training of Trainers for Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 96,200.00 0.00 2022-10-16 2022-10-26 2022-11-02 Village Governance Facilitato nment Institutions tions nvelope ementation r (PTPD) Region 7 ID-BINA PEMDES-319353-NC Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl -RFQ / National Consolidation IBRD / 89410 Post Limited 91,300.00 0.00 2022-10-16 2022-10-26 2022-11-02 nment Institutions tions nvelope ementation for the Acceleration of P3PD I mplementation ID-BINA PEMDES-291425-NC -RFB / Trainer of Trainer (TOT Strengthening Village Gover Single Stage - One E Pending Impl ) Village Financial Supervisio IBRD / 89410 Post Request for Bids Open - National 145,000.00 0.00 2022-10-10 2022-10-13 2022-10-27 2022-11-01 2022-11-05 2023-02-03 nment Institutions nvelope ementation n for Regional Internal Audito rs (APIP) In the Java and Bali Region ID-BINA PEMDES-323512-NC Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl -RFQ / Coordination Meeting f IBRD / 89410 Post Limited 59,000.00 0.00 2022-11-05 2022-11-15 2022-11-22 nment Institutions tions nvelope ementation or Acceleration of P3PD Impl ementation Page 1 ID-BINA PEMDES-342341-NC -RFQ / Village Financial Super Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl vision Training for Regional I IBRD / 89410 Post Limited 93,900.00 0.00 2023-03-14 2023-03-24 2023-03-31 nment Institutions tions nvelope ementation nternal Auditors (APIP) Regio n I (Lampung, Bengkulu) ID-BINA PEMDES-342342-NC -RFQ / Village Financial Super Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 84,750.00 0.00 2023-03-14 2023-03-24 2023-04-23 vision Training for Regional I nment Institutions tions nvelope ementation nternal Auditors (APIP) Regio n II (Jambi, Babel) ID-BINA PEMDES-342343-NC -RFQ / Village Financial Super Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl vision Training for Regional I IBRD / 89410 Post Limited 94,500.00 0.00 2023-03-14 2023-03-24 2023-04-23 nment Institutions tions nvelope ementation nternal Auditors (APIP) Regio n III (Kalsel, Kaltim & Kaltara) ID-BINA PEMDES-342346-NC -RFQ / Village Financial Super Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 94,450.00 0.00 2023-03-14 2023-03-24 2023-04-23 vision Training for Regional I nment Institutions tions nvelope ementation nternal Auditors (APIP) Regio n IV (Sulteng & Sultra) ID-BINA PEMDES-342347-NC -RFB / Village Financial Super Strengthening Village Gover Single Stage - One E Pending Impl IBRD / 89410 Post Request for Bids Open - National 750,000.00 0.00 2023-03-10 2023-03-15 2023-04-05 2023-04-20 2023-04-24 2023-12-05 vision Training for Regional I nment Institutions nvelope ementation nternal Auditors (APIP) Regio n V - IX ID-BINA PEMDES-347251-NC -RFB / Strenghening the Cap Strengthening Village Gover Single Stage - One E IBRD / 89410 Prior Request for Bids Open - National 48,500,000.00 0.00 Canceled 2023-03-15 2023-03-20 2023-04-10 2023-04-20 2023-04-24 2023-12-06 acity of Village Government nment Institutions nvelope Apparatus and Village Institu tional Management ID-BINA PEMDES-355979-NC -RFB / Strenghening the Cap acity of Village Government Strengthening Village Gover Single Stage - One E Under Imple Apparatus and Village Institu IBRD / 89410 Prior Request for Bids Open - National 7,160,000.00 0.00 2023-04-12 2023-04-14 2023-04-17 2023-05-08 2023-05-23 2023-05-18 2023-06-27 2023-05-22 2023-12-31 nment Institutions nvelope mentation tional Management in the pr ovince of Bangka Belitung Isl ands, Banten, East Kalimanta n, Maluku, West Papua and B ali (6 Lots) ID-BINA PEMDES-355985-NC -RFB / Strenghening the Cap acity of Village Government Apparatus and Village Institu Strengthening Village Gover Single Stage - One E Under Imple IBRD / 89410 Prior Request for Bids Open - National 7,000,000.00 0.00 2023-04-12 2023-04-14 2023-04-17 2023-05-08 2023-05-23 2023-05-18 2023-06-18 2023-05-22 2023-12-31 tional Management in the pr nment Institutions nvelope mentation ovince of North Sumatera, Ri au Islands, West Java, South Kalimantan, Southeast Sulaw esi, Papua and West Nusa Te nggara (7 Lots) ID-BINA PEMDES-355988-NC -RFB / Strenghening the Cap acity of Village Government Apparatus and Village Institu Strengthening Village Gover Single Stage - One E Under Imple IBRD / 89410 Prior Request for Bids Open - National 9,000,000.00 0.00 2023-04-12 2023-04-14 2023-04-17 2023-05-08 2023-05-23 2023-05-18 2023-06-23 2023-05-22 2023-12-31 tional Management in the pr nment Institutions nvelope mentation ovince of Aceh, West Sumatr a, Central Java, West Kaliman tan, West Sulawesi and North Maluku (6 Lots) ID-BINA PEMDES-355989-NC -RFB / Strenghening the Cap acity of Village Government Apparatus and Village Institu Strengthening Village Gover Single Stage - One E Under Imple IBRD / 89410 Prior Request for Bids Open - National 14,900,000.00 0.00 2023-04-12 2023-04-15 2023-04-17 2023-05-08 2023-05-23 2023-05-18 2023-06-27 2023-05-22 2023-12-31 tional Management in the pr nment Institutions nvelope mentation ovince of Riau, Jambi, Lampu ng, East Java, Central Kalima ntan, Gorontalo, South Sulaw esi and East Nusa Tenggara ( 8 Lots) ID-BINA PEMDES-355983-NC -RFB / Strenghening the Cap acity of Village Government Apparatus and Village Institu Strengthening Village Gover Single Stage - One E Under Imple IBRD / 89410 Prior Request for Bids Open - National 6,950,000.00 0.00 2023-04-12 2023-04-14 2023-04-17 2023-05-08 2023-05-23 2023-05-18 2023-06-23 2023-05-22 2023-12-31 tional Management in the pr nment Institutions nvelope mentation ovince of South Sumatra, Be ngkulu, DI Yogyakarta, North Kalimantan, North Sulawesi a nd Central Sulawesi (6 Lots) ID-BINA PEMDES-361276-NC -RFQ / Support the Implemen Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 95,000.00 0.00 2023-05-14 2023-05-19 2023-05-26 tation of the Ten PKK Progra nment Institutions tions nvelope ementation ms at the celebration of PKK Day ID-BINA PEMDES-363100-NC -RFB / National Coordination Strengthening Village Gover Single Stage - One E Pending Impl IBRD / 89410 Post Request for Bids Open - National 280,000.00 0.00 2023-05-28 2023-05-31 2023-06-21 2023-06-24 2023-06-26 2023-07-26 Meeting on Preparation for th nment Institutions nvelope ementation e Implementation of the P3P D Program ID-BINA PEMDES-363103-NC -RFB / Production and Publica Strengthening Village Gover Single Stage - One E tion of Learning Videos on M IBRD / 89410 Post Request for Bids Open - National 916,000.00 0.00 Canceled 2023-06-01 2023-06-02 2023-06-23 2023-06-26 2023-06-28 2024-12-30 nment Institutions nvelope anagement of Village Revenu e and Expenditures Budget ( APBDES) ID-BINA PEMDES-363111-NC Strengthening Village Gover Single Stage - One E Pending Impl -RFB / National Workshop an IBRD / 89410 Post Request for Bids Open - National 220,000.00 0.00 2023-05-29 2023-06-01 2023-06-22 2023-06-25 2023-06-27 2023-07-27 nment Institutions nvelope ementation d Awards for Achievement Vil lages ID-BINA PEMDES-363114-NC -RFQ / Reengineering, Mainte Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 38,000.00 0.00 2023-06-01 2023-06-19 2023-07-19 nance and Web Content Prod nment Institutions tions nvelope ementation uction to support the P3PD pr ogram ID-BINA PEMDES-363115-NC -RFQ / Management, Producti Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl on and Distribution of Digital IBRD / 89410 Post Limited 70,000.00 0.00 2023-06-01 2023-06-19 2023-12-29 nment Institutions tions nvelope ementation Content on Social Media to S upport the P3PD Program ID-BINA PEMDES-363116-NC -RFQ / Internal and External Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl Communication and Publicati IBRD / 89410 Post Limited 49,000.00 0.00 2023-06-01 2023-06-19 2023-12-29 nment Institutions tions nvelope ementation on through Journals and Mag azines to Support the P3PD P rogram Page 2 ID-BINA PEMDES-363117-NC -RFQ / Socialization Through Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl Documentary Videos and Pub IBRD / 89410 Post Limited 91,000.00 0.00 2023-06-01 2023-06-19 2023-12-29 nment Institutions tions nvelope ementation lic Service Advertisements to Support the P3PD Program ID-BINA PEMDES-363118-NC -RFQ / Video Publications, Tal Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 26,000.00 0.00 2023-06-01 2023-06-19 2023-12-29 k Shows and Podcasts to Sup nment Institutions tions nvelope ementation port the P3PD Program ID-BINA PEMDES-363102-NC -RFB / Training Of Trainers (T Strengthening Village Gover Single Stage - One E Pending Impl IBRD / 89410 Post Request for Bids Open - National 320,000.00 0.00 2023-05-28 2023-05-31 2023-06-21 2023-06-24 2023-06-26 2023-07-26 oT) for the Implementation of nment Institutions nvelope ementation Village Financial Managemen t Applications ID-BINA PEMDES-365851-NC -RFQ / Workshop on Village O fficials and Managers of Villa Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 87,000.00 0.00 2023-06-13 2023-07-01 2023-07-31 ge Traditional Institutions an nment Institutions tions nvelope ementation d Village Community Instituti ons on Noble Values and Loc al Wisdom ID-BINA PEMDES-365853-NC Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl -RFQ / Technical Guidance on IBRD / 89410 Post Limited 56,000.00 0.00 2023-06-13 2023-07-01 2023-07-31 nment Institutions tions nvelope ementation The Online Village Managem ent Application ID-BINA PEMDES-365854-NC -RFQ / Coordination Meeting Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 90,000.00 0.00 2023-06-13 2023-07-01 2023-07-31 on Preparation for the imple nment Institutions tions nvelope ementation mentation of the P3PD in 202 3 ID-BINA PEMDES-365873-NC -RFQ / Training Of Trainers (T Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 95,000.00 0.00 2023-06-13 2023-07-01 2023-08-30 OT) for Badan Permusyawara nment Institutions tions nvelope ementation tan Desa (BPD) in The Weste rn Region ID-BINA PEMDES-365865-NC -RFQ / Training Of Trainers (T Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 98,000.00 0.00 2023-06-13 2023-07-01 2023-08-30 OT) for Badan Permusyawara nment Institutions tions nvelope ementation tan Desa (BPD) in The Easter n Region ID-BINA PEMDES-366995-NC -RFQ / Workshop on Strength Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 94,000.00 0.00 2023-06-20 2023-07-08 2023-09-06 ening Local Government for t nment Institutions tions nvelope ementation he Implementation of P3PD R egion 1 ID-BINA PEMDES-366997-NC -RFQ / Workshop on Strength Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 93,500.00 0.00 2023-06-20 2023-07-08 2023-09-06 ening Local Government for t nment Institutions tions nvelope ementation he Implementation of P3PD R egion 2 ID-BINA PEMDES-367000-NC -RFB / Success Story of Imple menting Village Government Strengthening Village Gover Single Stage - One E Pending Impl in IBRD / 89410 Post Request for Bids Open - National 916,000.00 0.00 2023-06-19 2023-06-24 2023-07-15 2023-07-25 2023-07-29 2023-12-29 nment Institutions nvelope ementation Institutional Strengthening a nd improving the quality of s hopping at the village level in the P3PD Program ID-BINA PEMDES-363105-NC -RFB / Success Story of villag e government to strengthen i Strengthening Village Gover Request for Quota Single Stage - One E IBRD / 89410 Post Limited 87,000.00 0.00 Canceled 2023-05-31 2023-06-18 2023-07-18 nstitutional Capacity for Impr nment Institutions tions nvelope oved Quality of Spending in P articipating Villages in the P3 PD Program ID-BINA PEMDES-366993-NC Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl -RFQ / National Coordination IBRD / 89410 Post Limited 93,000.00 0.00 2023-06-18 2023-07-06 2023-09-04 nment Institutions tions nvelope ementation Meeting (Kick Off) of P3PD Im plementation ID-BINA PEMDES-369139-NC Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl -RFQ / Publication of the P3P IBRD / 89410 Post Limited 22,000.00 0.00 2023-07-06 2023-07-20 2023-12-30 nment Institutions tions nvelope ementation D Program through News Adv etorials ID-BINA PEMDES-369166-NC Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl -RFQ / Programmatic Adverti IBRD / 89410 Post Limited 92,000.00 0.00 2023-07-06 2023-07-20 2023-12-30 nment Institutions tions nvelope ementation sing to Support the P3PD Pro gram ID-BINA PEMDES-369177-NC Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl -RFQ / Drafting of Modules fo IBRD / 89410 Post Limited 98,000.00 0.00 2023-07-05 2023-07-19 2023-08-18 nment Institutions tions nvelope ementation r Training of LKD LAD and Po syandu ID-BINA PEMDES-369178-NC Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl -RFQ / Training of Master of T IBRD / 89410 Post Limited 37,000.00 0.00 2023-07-05 2023-07-19 2023-08-18 nment Institutions tions nvelope ementation rainer for LKD LAD, PKK and Posyandu ID-BINA PEMDES-369179-NC Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 98,000.00 0.00 2023-07-05 2023-07-19 2023-08-18 -RFQ / Training of Trainer for nment Institutions tions nvelope ementation LKD LAD ID-BINA PEMDES-369181-NC Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 89,000.00 0.00 2023-07-05 2023-07-19 2023-08-18 -RFQ / Training of Trainer for nment Institutions tions nvelope ementation Posyandu ID-BINA PEMDES-369182-NC Strengthening Village Gover Request for Quota Single Stage - One E Pending Impl IBRD / 89410 Post Limited 98,000.00 0.00 2023-07-05 2023-07-19 2023-08-18 -RFQ / Training of Trainer for nment Institutions tions nvelope ementation PKK CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-BINA PEMDES-170080-CS- Strengthening Village Gover Quality And Cost- Open - Internationa Under Implement QCBS / National Management IBRD / 89410 Prior 6,000,000.00 0.00 2020-05-15 2021-01-11 2020-05-29 2021-08-17 2020-07-15 2021-12-22 2020-08-12 2022-01-24 2020-09-11 2022-06-23 2020-10-16 2022-09-14 2020-11-20 2023-11-20 nment Institutions Based Selection l ation Consultant and Advisory Serv ices for P3PD ID-BINA PEMDES-173460-CS- QCBS / Digital system for Lea Strengthening Village Gover Quality And Cost- Open - Internationa rning Management - System IBRD / 89410 Prior 5,000,000.00 0.00 Canceled 2020-08-02 2020-08-23 2020-10-06 2020-11-03 2020-12-03 2021-01-07 2021-02-11 2022-02-11 nment Institutions Based Selection l Development for Village Apparatus CB Page 3 ID-BINA PEMDES-273280-CS- Strengthening Village Gover Quality And Cost- Open - Internationa Under Implement QCBS / Learning Managemen IBRD / 89410 Prior 1,190,000.00 0.00 2022-04-12 2022-09-07 2022-04-27 2022-09-13 2022-05-19 2023-02-19 2022-06-16 2023-04-11 2022-07-01 2022-07-15 2022-08-19 2024-12-31 nment Institutions Based Selection l ation t System Platform ID-BINA PEMDES-273283-CS- Strengthening Village Gover Quality And Cost- Open - Internationa QCBS / Content Development IBRD / 89410 Prior 1,925,000.00 0.00 Under Review 2022-04-12 2022-09-07 2022-04-27 2022-10-06 2022-05-19 2022-06-16 2022-07-01 2022-07-15 2022-08-19 2025-02-25 nment Institutions Based Selection l for Learning Management Sy stem ID-BINA PEMDES-306004-CS- Strengthening Village Gover Quality And Cost- Open - Internationa Pending Impleme IBRD / 89410 Post 550,000.00 0.00 2022-07-27 2022-08-11 2022-09-02 2022-09-30 2022-10-15 2022-10-29 2022-12-03 2025-04-16 QCBS / Reengineering Prodes nment Institutions Based Selection l ntation kel ID-BINA PEMDES-347252-CS- Strengthening Village Gover Quality And Cost- Open - Internationa Pending Impleme IBRD / 89410 Post 692,000.00 0.00 2023-03-10 2023-03-25 2023-04-16 2023-05-14 2023-05-29 2023-06-12 2023-07-17 2025-11-28 QCBS / Reengineering Prodes nment Institutions Based Selection l ntation kel INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-BINA PEMDES-202830-CS- INDV / Individual Consultants Strengthening Village Gover Individual Consult Under Implement IBRD / 89410 Post Open 190,000.00 0.00 2020-11-09 2020-11-09 2020-11-15 2020-11-16 2020-11-18 2021-12-31 for Secretariat - Planning and nment Institutions ant Selection ation Finance Division, 2020-2024 ID-BINA PEMDES-202882-CS- Strengthening Village Gover Individual Consult INDV / Individual Consultans f IBRD / 89410 Post Open 70,000.00 0.00 Canceled 2020-11-09 2020-11-15 2020-11-16 2020-11-18 2022-01-03 nment Institutions ant Selection or Secretariat - Program Divi sion ID-BINA PEMDES-224429-CS- Strengthening Village Gover Individual Consult INDV / Individual Consultant f IBRD / 89410 Post Open 120,000.00 0.00 Canceled 2021-03-15 2021-03-21 2021-03-22 2021-03-24 2022-05-09 nment Institutions ant Selection or Secertariat P3PD-Program Division ID-BINA PEMDES-226937-CS- INDV / Individual Consultants Strengthening Village Gover Individual Consult Under Implement to support the Secretariat in IBRD / 89410 Post Open 42,000.00 0.00 2021-03-29 2021-03-31 2021-04-18 2021-04-19 2021-04-21 2022-01-14 nment Institutions ant Selection ation Village Government Institutio nal Arrangements, FY 2021 ID-BINA PEMDES-226940-CS- INDV / Individual Consultants Strengthening Village Gover Individual Consult Under Implement to support the Secretariat in IBRD / 89410 Post Open 32,000.00 0.00 2021-03-29 2021-03-29 2021-04-18 2021-04-19 2021-04-21 2022-01-14 nment Institutions ant Selection ation developing village apparatus training material and training methodology, FY 2021 ID-BINA PEMDES-226942-CS- INDV / Individual Consultants Strengthening Village Gover Individual Consult Under Implement to support the Secretariat in IBRD / 89410 Post Open 42,000.00 0.00 2021-03-31 2021-03-31 2021-04-20 2021-04-21 2021-04-23 2022-01-16 nment Institutions ant Selection ation Development of Digital Learn ing and Information Systems FY 2021 ID-BINA PEMDES-312587-CS- Strengthening Village Gover Individual Consult Pending Impleme INDV / Project Coordinator for IBRD / 89410 Post Limited 5,400.00 0.00 2022-09-07 2022-09-12 2022-09-14 2022-09-18 2022-11-18 nment Institutions ant Selection ntation Finalization of the Grand Desi gn Prodeskel ID-BINA PEMDES-312591-CS- INDV / Business Analyst Expe Strengthening Village Gover Individual Consult Pending Impleme IBRD / 89410 Post Limited 3,500.00 0.00 2022-09-07 2022-09-12 2022-09-14 2022-09-18 2022-11-18 rt for Finalization of the Gran nment Institutions ant Selection ntation d Design Prodeskel ID-BINA PEMDES-312593-CS- INDV / System/Data Architect Strengthening Village Gover Individual Consult Pending Impleme IBRD / 89410 Post Limited 3,500.00 0.00 2022-09-12 2022-09-14 2022-09-21 2022-09-25 2022-12-31 for Finalization of the Grand nment Institutions ant Selection ntation Design Prodeskel ID-BINA PEMDES-312598-CS- Strengthening Village Gover Individual Consult Pending Impleme INDV / Data Engineer for Fin IBRD / 89410 Post Limited 2,400.00 0.00 2022-09-12 2022-09-14 2022-09-21 2022-09-25 2022-12-31 nment Institutions ant Selection ntation alization of the Grand Design Prodeskel ID-BINA PEMDES-312596-CS- INDV / Human Centered Desi Strengthening Village Gover Individual Consult Pending Impleme IBRD / 89410 Post Limited 4,650.00 0.00 2022-09-12 2022-09-14 2022-09-21 2022-09-25 2022-12-31 gn (HCD) Researcher for Fina nment Institutions ant Selection ntation lization of the Grand Design Prodeskel ID-BINA PEMDES-312594-CS- INDV / User Interface (UI) dan Strengthening Village Gover Individual Consult Pending Impleme IBRD / 89410 Post Limited 3,100.00 0.00 2022-09-12 2022-09-14 2022-09-21 2022-09-25 2022-12-31 User Experience (UX) Design nment Institutions ant Selection ntation er for Finalization of the Gran d Design Prodeskel ID-BINA PEMDES-312597-CS- Strengthening Village Gover Individual Consult Pending Impleme INDV / Web Programmer for F IBRD / 89410 Post Limited 2,650.00 0.00 2022-09-12 2022-09-14 2022-09-21 2022-09-25 2022-12-31 nment Institutions ant Selection ntation inalization of the Grand Desi gn Prodeskel ID-BINA PEMDES-315138-CS- Strengthening Village Gover Individual Consult Pending Impleme IBRD / 89410 Post Limited 2,000.00 0.00 2022-09-12 2022-09-14 2022-09-21 2022-09-25 2022-12-31 INDV / Village Institutional Sp nment Institutions ant Selection ntation ecialist ID-BINA PEMDES-353371-CS- Strengthening Village Gover Individual Consult Pending Impleme INDV / Senior Expert for Prog IBRD / 89410 Post Limited 18,000.00 0.00 2023-04-03 2023-04-10 2023-04-17 2023-04-19 2023-12-31 nment Institutions ant Selection ntation ram Control ID-BINA PEMDES-353390-CS- Strengthening Village Gover Individual Consult Pending Impleme INDV / Senior Expert for Proje IBRD / 89410 Post Limited 18,000.00 0.00 2023-04-03 2023-04-10 2023-04-17 2023-04-19 2023-12-31 nment Institutions ant Selection ntation ct Management ID-BINA PEMDES-353392-CS- Strengthening Village Gover Individual Consult Pending Impleme IBRD / 89410 Post Limited 13,500.00 0.00 2023-04-03 2023-04-10 2023-04-17 2023-04-19 2023-12-31 INDV / Budget Planning Expe nment Institutions ant Selection ntation rt ID-BINA PEMDES-353397-CS- Strengthening Village Gover Individual Consult Pending Impleme INDV / Village Development P IBRD / 89410 Post Limited 13,500.00 0.00 2023-04-03 2023-04-10 2023-04-17 2023-04-19 2023-12-31 nment Institutions ant Selection ntation lanning Expert ID-BINA PEMDES-353403-CS- Strengthening Village Gover Individual Consult Pending Impleme INDV / Human Resources Ma IBRD / 89410 Post Limited 13,500.00 0.00 2023-04-03 2023-04-10 2023-04-17 2023-04-19 2023-12-31 nment Institutions ant Selection ntation nagement Expert ID-BINA PEMDES-353411-CS- Strengthening Village Gover Individual Consult Pending Impleme INDV / Alignment of Program IBRD / 89410 Post Limited 13,500.00 0.00 2023-04-03 2023-04-10 2023-04-17 2023-04-19 2023-12-31 nment Institutions ant Selection ntation Implementation and Develop ment Expert Page 4 ID-BINA PEMDES-353413-CS- Strengthening Village Gover Individual Consult Pending Impleme INDV / Village Economic Dev IBRD / 89410 Post Limited 13,500.00 0.00 2023-04-03 2023-04-10 2023-04-17 2023-04-19 2023-12-31 nment Institutions ant Selection ntation elopment Expert ID-BINA PEMDES-353420-CS- Strengthening Village Gover Individual Consult Pending Impleme INDV / Data Management, Ev IBRD / 89410 Post Limited 13,500.00 0.00 2023-04-03 2023-04-10 2023-04-17 2023-04-19 2023-12-31 nment Institutions ant Selection ntation aluation and Reporting Exper t ID-BINA PEMDES-353421-CS- Strengthening Village Gover Individual Consult Pending Impleme INDV / Media, Publication and IBRD / 89410 Post Limited 13,500.00 0.00 2023-04-03 2023-04-10 2023-04-17 2023-04-19 2023-12-31 nment Institutions ant Selection ntation Information Expert ID-BINA PEMDES-363107-CS- Strengthening Village Gover Individual Consult Pending Impleme IBRD / 89410 Post Limited 3,000.00 0.00 2023-05-29 2023-06-03 2023-06-05 2023-06-07 2023-09-05 INDV / Rural Sociology Expert nment Institutions ant Selection ntation s ID-BINA PEMDES-363108-CS- Strengthening Village Gover Individual Consult Pending Impleme INDV / Development Economi IBRD / 89410 Post Limited 2,500.00 0.00 2023-05-29 2023-06-03 2023-06-05 2023-06-07 2023-09-05 nment Institutions ant Selection ntation c Experts ID-BINA PEMDES-363109-CS- Strengthening Village Gover Individual Consult Pending Impleme IBRD / 89410 Post Limited 2,500.00 0.00 2023-05-29 2023-06-03 2023-06-05 2023-06-07 2023-09-05 INDV / Data Engineer nment Institutions ant Selection ntation ID-BINA PEMDES-363110-CS- Strengthening Village Gover Individual Consult Pending Impleme IBRD / 89410 Post Limited 2,500.00 0.00 2023-05-29 2023-06-03 2023-06-05 2023-06-07 2023-09-05 INDV / Statistical Experts nment Institutions ant Selection ntation ID-BINA PEMDES-363112-CS- Strengthening Village Gover Individual Consult Pending Impleme INDV / Full Stack Programme IBRD / 89410 Post Limited 3,000.00 0.00 2023-05-29 2023-06-03 2023-06-05 2023-06-07 2023-09-05 nment Institutions ant Selection ntation r (Front & Back End Applicati on) ID-BINA PEMDES-363113-CS- Strengthening Village Gover Individual Consult Pending Impleme IBRD / 89410 Post Limited 3,000.00 0.00 2023-05-29 2023-06-03 2023-06-05 2023-06-07 2023-09-05 INDV / Information Systems A nment Institutions ant Selection ntation nalyst Page 5 PROCUREMENT PLAN (Textual Part) Project information: Country: Democratic Republic of Congo; Project name: DRC Enhancing Collection of Revenue and Expenditure Management Project (ENCORE), Project number: P171762 Project Implementation agency: Comité d’Orientation de la Réforme des Finances Publiques (COREF) Date of the Procurement Plan: 02/12/2021 Period covered by this Procurement Plan: from 12/02/2021 to 05/01/2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation: “Not applicable”], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Secondhand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables. Works: is not applicable for those contracts identified in the Procurement Plan tables Revue Date prévue Méthode par la pour Réf. Prévu/Ré Commentai Description* Coût en $US de Banque l'ouverture No al. res sélection (priori/po de l'offre st) technique Sélection des consultants Recrutement du personnel clé et du 248 Prévu CI Post NA 1 personnel d’appoint de l’Equipe du Projet 600,00 (Période PPA) Réalisé Sélection d'un consultant cabinet Prévu 150 QC Post NA international en vue de mener les études de 000,00 2 faisabilité pour la mise en œuvre de E- Réalisé Procurement en RDC Recrutement d'un Consultant international 90 Prévu CI Post 25-3-2022 3 chargé de l’appui à la mise en œuvre du 000,00 SIGRH-Paie Réalisé Sélection d'un consultant individuel chargé Prévu 70 CI Post NA d'appuyer l'élaboration des textes fixant les 000,00 4 modalités de répartition des recettes à Réalisé caractère national Sélection d'un consultant individuel pour Prévu 50 CI Post NA réaliser une étude de faisabilité pour la mise 000,00 5 en place des administrations provinciales du trésor, de la comptabilité et du budget dans Réalisé 3 provinces identifiées Sélection d'un consultant individuel pour 50 élaborer un cahier de charges de mise en Prévu CI Post NA 000,00 6 place d'un système intégré des recettes et des dépenses en Provinces Réalisé Revue Date prévue Méthode par la pour Réf. Prévu/Ré Commentai Description* Coût en $US de Banque l'ouverture No al. res sélection (priori/po de l'offre st) technique Sélection d'un Consultant individuel pour la Prévu 50 CI Post NA rédaction du manuel des procédures de 000,00 7 gestion financière et de la passation des Réalisé marchés du Projet ENCORE Sélection d'un Cabinet pour l'acquisition et le 50 Prévu QC Post NA 8 paramétrage du logiciel de stockage et 000,00 analyse des données du Suivi-Evaluation Réalisé Sélection d'un Consultant cabinet pour Prévu 50 QC Post NA l'acquisition et le paramétrage du logiciel de 000,00 9 gestion de projet (technique et mise en Réalisé œuvre des activités) Recrutement d'un Consultant individuel Prévu 45 CI Post NA chargé de la conception et la mise en œuvre 000,00 10 d’une plateforme web pour la mise à jour du fichier de référence des agents de Réalisé l’Administration publique (FRAP 2) Sélection d'un Cabinet Webmaster pour la 45 Prévu QC Post NA 11 mise en place du Site WEB de 3 provinces 000,00 sélectionnées Réalisé Sélection d'un consultant international expert 40 Prévu CI Post en sondage pour 4 mois chargé 000,00 12 d’accompagner l’équipe technique nationale dans l'organisation de l'enquête et Réalisé l'actualisation de la base d'échantillonnage Revue Date prévue Méthode par la pour Réf. Prévu/Ré Commentai Description* Coût en $US de Banque l'ouverture No al. res sélection (priori/po de l'offre st) technique Sélection d'un consultant pour l'évaluation de 30 Prévu CI Post NA la répartition effective (etude Benefit Sharing 000,00 13 Assessment ou BSA) des recettes minières Réalisé au niveau local (0.3% aux ETDs) Sélection d'un Consultant individuel pour la Prévu 30 CI Post 18-3-2022 14 rédaction du manuel de vérification des PBCs 000,00 et PBPs du Projet ENCORE Réalisé Sélection d'un consultant cabinet chargé de 25 Prévu SMC Post NA 15 l'Audit financier externe du PPA clos au 000,00 30/04/2022 Réalisé Sélection d'un Consultant Individuel chargé 25 Prévu CI Post NA 16 d'élaborer le plan d'engagement 000,00 environnemental et social Réalisé Sélection d'un Consultant Individuel chargé 25 Prévu CI Post 5-3-2022 17 d'élaborer le plan de mobilisation des parties 000,00 prenantes Réalisé 24 Sélection d'un Consultant Individuel Prévu CI Post 5-3-2022 18 000,00 Ingénieur Génie Civil Réalisé Sélection d'un consultant international expert Prévu 20 CI Post 5-3-2022 en CAPI pour 2 mois qui seront chargés 000,00 19 d’accompagner l’équipe technique nationale Réalisé dans l'organisation de l'enquête et Revue Date prévue Méthode par la pour Réf. Prévu/Ré Commentai Description* Coût en $US de Banque l'ouverture No al. res sélection (priori/po de l'offre st) technique l'actualisation de la base d'échantillonnage Sélection d'un Consultant pour appuyer la Prévu 16 ED Post NA 20 2ème phase de la mise en place de SIGMAP 000,00 (20 nouvelles cellules) (Pierre Tshiyombo) Réalisé 15 Sélection d'un Cabinet Webmaster pour la Prévu QC Post NA 21 000,00 mise en place du Site WEB du Projet ENCORE Réalisé Recrutement d'un Consultant Expert en 14 Prévu CI Post NA informatique et systèmes d’information 000,00 22 chargé d’appuyer la mise en œuvre du Système Intégré de Gestion des Ressources Réalisé Humaines et de la Paie (SIGRH-Paie) Recrutement d'un Consultant National 14 Prévu CI Post NA individuel en Administration Publique chargé 000,00 23 d’appuyer la mise en œuvre du Système Intégré de Gestion des Ressources Humaines Réalisé et de la Paie (SIGRH-Paie) 1 175 600,00 SFQC : sélection fondée sur la qualité et le coût QC : sélection fondée sur les qualifications des consultants SMC : sélection au moindre coût CI : sélection de Consultant individuel ED: sélection par entente directe PROCUREMENT Congo, Democratic Republic of : Enhancing Collection of Revenue and Expenditure Management Project PLAN General Information Country: Congo, Democratic Republic of 2021-12-02 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171762 GPN Date: 2022-06-14 Project Name: Enhancing Collection of Revenue and Expenditure Management Project Loan / Credit No: IDA / 70200, / , IDA / V4000 Comité d'Orientation de la Reforme des Finances Publiques Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ZR-COREF-345140-CW-RFQ / Component 1. Strengthening Request for Quota Travaux de réhabilitation du Public Resources Manageme Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-02-1 IDA / 70200 Post Open - National 200,000.00 0.00 2023-06-20 2023-08-15 bâtiment devant abriter la ch nt at Central Government Le tions nvelope s (Emergency) SP lementation 1 ambre des comptes déconce vel D -Competitive ntrées de Kananga ZR-COREF-345177-CW-RFQ / Request for Quota Component 3. Project and C Réhabilitation du bâtiment m Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-12-1 IDA / 70200 hange Management, and Em Post Open - National 100,000.00 0.00 2023-04-27 2023-06-22 is à disposition pour la coordi tions nvelope s (Emergency) SP lementation 9 ergency Response nation provinciale du Kasaï D -Competitive Request for Quota ZR-COREF-345180-CW-RFQ / Component 3. Project and C Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-12-2 Réhabilitation des bâtiments IDA / 70200 hange Management, and Em Post Open - National 145,000.00 0.00 2023-05-03 2023-06-28 tions nvelope s (Emergency) SP lementation 5 de la coordination nationale ergency Response D -Competitive ZR-COREF-345109-CW-RFQ / Appui à l'aménagement des l Component 1. Strengthening ocaux devant abriter les post Request for Quota Public Resources Manageme Request for Quota Single Stage - One E Pending Imp 2023-12-2 es du réseau comptable à Ki IDA / 70200 Post Limited tions (Non Bank-S 150,000.00 0.00 2023-04-30 2023-06-25 nt at Central Government Le tions nvelope lementation 2 nshasa pour les postes comp PD) vel tables des 4 ministères déco ncentrés (EPST, Santé, ITPR e t Développement Rural) + l'A CCT ZR-COREF-356044-CW-RFQ / Component 1. Strengthening Request for Quota Travaux d’aménagement du l Public Resources Manageme Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-01-2 IDA / 70200 Post Limited 50,000.00 0.00 2023-05-30 2023-07-25 ocal technique du datacenter nt at Central Government Le tions nvelope s (Emergency) SP lementation 1 de l'Hôtel du Gouvernement vel D -Competitive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-COREF-264864-GO-RFQ / Component 1. Strengthening Acquisition et déploiement d Public Resources Manageme Request for Quota Single Stage - One E Pending Impl es matériels auprès des utilis / Post Limited 40,000.00 0.00 2022-01-15 2022-02-25 2022-04-26 nt at Central Government Le tions nvelope ementation ateurs de SIGMAP dans 20 no vel uveaux cellules identifiées ZR-COREF-265014-GO-DIR / Component 3. Project and C Acquisition d'un logiciel de g IDA / 70200 hange Management, and Em Post Direct Selection Direct 50,000.00 46,473.00 Completed 2021-12-20 2021-12-20 2021-12-25 2021-12-20 2022-01-27 2022-02-12 2022-03-28 2022-12-09 estion financière du projet E ergency Response NCORE (auprès de TOMATE) ZR-COREF-265086-GO-DIR / Marché de fourniture de Rec Component 1. Strengthening harge des Clés APN pour la r Public Resources Manageme IDA / 70200 Post Direct Selection Direct 20,000.00 20,000.00 Completed 2021-12-24 2022-01-25 2021-12-29 2022-01-21 2022-01-14 2022-01-26 2022-04-30 2022-05-04 emontée des informations de nt at Central Government Le s 75 Administrations + l’équi vel pe technique de la FP (25)/ S OCIETE RAAH SARL ZR-COREF-296208-GO-RFQ / Component 1. Strengthening Marché de fourniture de mob Public Resources Manageme Request for Quota Single Stage - One E Pending Impl IDA / V4000 Post Limited 70,000.00 0.00 2022-06-22 2022-07-22 2022-08-21 ilier de bureaux pour équiper nt at Central Government Le tions nvelope ementation les nouveaux locaux de la D vel GRH-DBDR ZR-COREF-296509-GO-DIR / Reconduction du contrat des fournitures de recharge des c Component 1. Strengthening lés APN pour la remontée des Public Resources Manageme IDA / 70200 Post Direct Selection Direct 15,000.00 15,000.00 Completed 2022-05-23 2022-05-23 2022-05-25 2022-05-23 2022-05-29 2022-05-31 2022-07-31 2022-07-07 informations de 75 administr nt at Central Government Le ations + l'équipe technique d vel e la FP (25) pour la période d e Mai à Juillet 2022 - Société RAAH SARL ZR-COREF-296039-GO-RFQ / Component 3. Project and C Acquisition des laptops et ac Request for Quota Single Stage - One E IDA / V4000 hange Management, and Em Post Limited 49,000.00 46,270.00 Completed 2022-06-09 2022-06-06 2022-07-05 2022-07-15 2022-08-05 2022-12-04 cessoires pour le personnel d tions nvelope ergency Response u PPA du Projet ENCORE ZR-COREF-345208-GO-RFB / Acquisition des équipements Component 1. Strengthening informatiques pour les 4 cent Public Resources Manageme Single Stage - One E Pending Impl IDA / 70200 Post Request for Bids Open - National 600,000.00 0.00 2023-05-15 2023-05-20 2023-07-01 2023-07-31 2023-09-04 2024-03-02 res d'ordonnancement et pou nt at Central Government Le nvelope ementation r le renforcement du systèm vel e d'information de la chaîne de la dépense ZR-COREF-345267-GO-RFQ / Impression du manuel des pr Component 1. Strengthening océdures administratives et f Public Resources Manageme Request for Quota Single Stage - One E Pending Impl IDA / 70200 Post Limited 100,000.00 0.00 2023-04-25 2023-06-20 2023-12-17 inancières des DAF (2000 ex nt at Central Government Le tions nvelope ementation emplaires de 220 pages dont vel certaines pages en couleur) ZR-COREF-345306-GO-RFQ / Component 1. Strengthening Appui à la reproduction des Public Resources Manageme Request for Quota Single Stage - One E Pending Impl IDA / 70200 Post Limited 100,000.00 0.00 2023-04-15 2023-06-10 2023-12-07 manuels et textes règlement nt at Central Government Le tions nvelope ementation aires élaborés et validés vel ZR-COREF-345326-GO-RFQ / Component 1. Strengthening Request for Quota Single Stage - One E Pending Impl Acquisition des équipements IDA / 70200 Public Resources Manageme Post Limited 100,000.00 0.00 2023-07-06 2023-08-31 2024-02-27 tions nvelope ementation informatiques des postes clé nt at Central Government Le s de la DGTCP vel Page 1 ZR-COREF-345327-GO-RFQ / Component 1. Strengthening Request for Quota Single Stage - One E Pending Impl Acquisition des mobiliers de IDA / 70200 Public Resources Manageme Post Limited 90,000.00 0.00 2023-07-27 2023-09-21 2024-03-19 tions nvelope ementation bureau des postes clés de la nt at Central Government Le DGTCP vel ZR-COREF-345456-GO-RFQ / Component 1. Strengthening Acquisition des petites fourni Public Resources Manageme Request for Quota Single Stage - One E Pending Impl IDA / 70200 Post Limited 50,000.00 0.00 2023-08-12 2023-10-07 2024-04-04 tures de bureaux et consom nt at Central Government Le tions nvelope ementation mables en faveur des postes vel clés de la DGTCP ZR-COREF-345460-GO-RFB / Component 1. Strengthening Single Stage - One E Pending Impl Acquisition d'une solution inf IDA / 70200 Public Resources Manageme Post Request for Bids Open - National 1,200,000.00 0.00 2023-07-15 2023-07-20 2023-08-31 2023-09-30 2023-11-04 2024-05-02 nvelope ementation ormatique du CUT nt at Central Government Le vel ZR-COREF-345473-GO-RFQ / Component 1. Strengthening Request for Quota Single Stage - One E Pending Impl Acquisition des mobiliers pou IDA / 70200 Public Resources Manageme Post Limited 200,000.00 0.00 2023-04-10 2023-06-05 2023-12-02 tions nvelope ementation r les 6 directions de la DGRH nt at Central Government Le réhabilitées vel ZR-COREF-345479-GO-RFQ / Component 1. Strengthening Acquisition de 40 machines s Public Resources Manageme Request for Quota Single Stage - One E Under Imple canners pour la numérisation IDA / 70200 Post Limited 48,000.00 0.00 2023-04-20 2023-06-15 2023-12-12 nt at Central Government Le tions nvelope mentation des actes administratifs de fo vel nctionnaires en provinces et au niveau central ZR-COREF-345482-GO-RFQ / Component 1. Strengthening Request for Quota Single Stage - One E Under Imple Acquisition des 80 lecteurs d' IDA / 70200 Public Resources Manageme Post Limited 12,000.00 0.00 2023-04-06 2023-06-01 2023-11-28 tions nvelope mentation empreintes pour identificatio nt at Central Government Le n biométrique vel ZR-COREF-345512-GO-RFQ / Component 1. Strengthening Acquisition de 100 machines Public Resources Manageme Request for Quota Single Stage - One E Pending Impl IDA / 70200 Post Limited 200,000.00 0.00 2023-05-04 2023-06-29 2023-12-26 d'impression des cartes des nt at Central Government Le tions nvelope ementation agents de carrières de servic vel es publics de l'Etat ZR-COREF-345539-GO-RFQ / Acquisition des matériels info Component 1. Strengthening rmatiques pour le déploieme Public Resources Manageme Request for Quota Single Stage - One E Pending Impl nt du SIGMAP dans 20 CGPM IDA / 70200 Post Limited 150,000.00 0.00 2023-06-20 2023-08-15 2024-02-11 nt at Central Government Le tions nvelope ementation Ps additionnelles au niveau c vel entral, la DGCMP ainsi que la salle machine SIGMAP au Min du Budget. ZR-COREF-345540-GO-RFQ / Component 1. Strengthening Acquisition des mobiliers de Public Resources Manageme Request for Quota Single Stage - One E Pending Impl IDA / 70200 Post Limited 30,000.00 0.00 2023-06-25 2023-08-20 2024-02-16 bureau pour la salle de mach nt at Central Government Le tions nvelope ementation ine SIGMAP au Budget. vel ZR-COREF-345544-GO-RFQ / Abonnement internet de la C Component 1. Strengthening our des comptes pour la publ Public Resources Manageme Request for Quota Single Stage - One E Pending Impl IDA / 70200 Post Limited 35,000.00 0.00 2023-04-11 2023-06-06 2023-12-03 ication notamment des rappo nt at Central Government Le tions nvelope ementation rts de reddition des comptes vel du pouvoir central et des pro vinces couvertes par le proje t ZR-COREF-345548-GO-RFQ / Component 1. Strengthening Appui à la reproduction des t Public Resources Manageme Request for Quota Single Stage - One E Pending Impl extes fixant les modalités de IDA / 70200 Post Limited 30,000.00 0.00 2023-05-11 2023-07-06 2024-01-02 nt at Central Government Le tions nvelope ementation répartition des impôts et tax vel es d’intérêt commun ZR-COREF-345551-GO-RFQ / Acquisition des matériels info Component 2. Supporting rmatiques en faveur des adm Resource Management at th Request for Quota Single Stage - One E Pending Impl IDA / 70200 Post Limited 250,000.00 0.00 2023-06-28 2023-08-23 2024-02-19 inistrations fiscales Provincial e Provincial Government Lev tions nvelope ementation es du Kasaï Oriental, du Kasa el ï, du Kasaï Central et de Lom ami ZR-COREF-345556-GO-RFQ / Acquisition des mobiliers des Component 2. Supporting bureaux en faveur des admin Resource Management at th Request for Quota Single Stage - One E Pending Impl IDA / 70200 Post Limited 250,000.00 0.00 2023-06-25 2023-08-20 2024-02-16 istrations fiscales Provinciale e Provincial Government Lev tions nvelope ementation s du Kasaï Oriental, du Kasaï el , du Kasaï Central et de Loma mi ZR-COREF-345557-GO-RFQ / Acquisition des fournitures d Component 2. Supporting es bureaux et consommables Resource Management at th Request for Quota Single Stage - One E Pending Impl IDA / 70200 Post Limited 110,000.00 0.00 2023-07-20 2023-09-14 2024-03-12 informatiques pour les régies e Provincial Government Lev tions nvelope ementation provinciales du Kasaï Orient el al, du Kasaï, du Kasaï Central et de Lomami ZR-COREF-345582-GO-RFQ / Acquisition des desktops et a Component 3. Project and C Request for Quota Single Stage - One E Pending Impl ccessoires pour le personnel IDA / 70200 hange Management, and Em Post Limited 60,000.00 0.00 2023-04-20 2023-06-15 2023-12-12 tions nvelope ementation du Projet ENCORE (Coordina ergency Response tion nationale et coordination s provinciales) ZR-COREF-345591-GO-RFQ / Acquisition des imprimantes Component 3. Project and C Request for Quota Single Stage - One E Pending Impl et appareils de reprographie IDA / 70200 hange Management, and Em Post Limited 60,000.00 0.00 2023-04-22 2023-06-17 2023-12-14 tions nvelope ementation pour le Projet ENCORE (Coor ergency Response dination nationale et coordin ations provinciales) ZR-COREF-345620-GO-RFQ / Component 3. Project and C Request for Quota Single Stage - One E Pending Impl Production d'un nouveau pa IDA / 70200 hange Management, and Em Post Limited 2,000.00 0.00 2023-04-04 2023-05-30 2023-11-26 tions nvelope ementation nneau ENCORE ergency Response ZR-COREF-345703-GO-DIR / Component 1. Strengthening Pending Impl Rechargement des Clés APN IDA / 70200 Public Resources Manageme Post Direct Selection Direct - National 60,000.00 0.00 2023-03-20 2023-03-25 2023-04-29 2024-04-28 ementation pour 75 postes nt at Central Government Le vel ZR-COREF-345707-GO-RFQ / Component 3. Project and C Reproduction des documents Request for Quota Single Stage - One E Pending Impl IDA / 70200 hange Management, and Em Post Limited 50,000.00 0.00 2023-05-18 2023-07-13 2024-01-09 stratégiques sur les réformes tions nvelope ementation ergency Response des finances publiques ZR-COREF-345708-GO-RFQ / Component 3. Project and C Reproduction de la revue tri Request for Quota Single Stage - One E Pending Impl IDA / 70200 hange Management, and Em Post Limited 40,000.00 0.00 2023-04-20 2023-06-15 2023-12-12 mestrielle sur la réforme des tions nvelope ementation ergency Response finances publiques ZR-COREF-345711-GO-RFQ / Component 3. Project and C Request for Quota Single Stage - One E Pending Impl Reproduction des agendas 2 IDA / 70200 hange Management, and Em Post Limited 40,000.00 0.00 2023-04-01 2023-05-27 2023-11-23 tions nvelope ementation 023 pour le Projet ENCORE ergency Response Page 2 ZR-COREF-345478-GO-RFQ / Component 1. Strengthening Request for Quota Single Stage - One E Pending Impl Mise aux normes de sécurisa IDA / 70200 Public Resources Manageme Post Limited 60,000.00 0.00 2023-08-12 2023-10-07 2024-04-04 tions nvelope ementation tion du Data Center de secou nt at Central Government Le rs vel ZR-COREF-345288-GO-RFB / Component 1. Strengthening Acquisition des fournitures d Public Resources Manageme Single Stage - One E Pending Impl IDA / 70200 Post Request for Bids Open - National 600,000.00 0.00 2023-08-07 2023-08-12 2023-09-23 2023-10-23 2023-11-27 2024-05-25 e bureau et consommables p nt at Central Government Le nvelope ementation our les 12 nouvelles DAF à in vel staller ZR-COREF-345249-GO-RFQ / Component 1. Strengthening Achat des mobiliers de burea Public Resources Manageme Request for Quota Single Stage - One E Pending Impl u pour les 4 centres d'ordonn IDA / 70200 Post Limited 320,000.00 0.00 2023-04-19 2023-06-14 2023-12-11 nt at Central Government Le tions nvelope ementation ancement des ministères de l vel ’EPST, Santé, Développemen t rural et des ITPR. ZR-COREF-345272-GO-RFB / Acquisition des matériels et mobiliers de bureau pour les Component 1. Strengthening 12 nouvelles DAF (Affaires ét Public Resources Manageme Single Stage - One E Pending Impl IDA / 70200 Post Request for Bids Open - National 1,000,000.00 0.00 2023-04-10 2023-04-15 2023-05-20 2023-06-10 2023-07-15 2024-01-11 rangères, Coopération intern nt at Central Government Le nvelope ementation ational, Coopération régional vel e, Economie, Energie, Hydroc arbures, Jeunesse, Mines, PM E et artisanat, PTNTIC, Sports et loisirs, Justice) ZR-COREF-345320-GO-RFQ / Acquisition des équipements Component 1. Strengthening informatiques et petites four Public Resources Manageme Request for Quota Single Stage - One E Pending Impl nitures pour l'opérationnalisa IDA / 70200 Post Limited 200,000.00 0.00 2023-07-20 2023-09-14 2024-03-12 nt at Central Government Le tions nvelope ementation tion de l'ACCT, de postes co vel mptables des 4 ministères dé concentrés (EPST, Santé, ITP R et Développement Rural) ZR-COREF-345705-GO-DIR / Appui à la migration du SIGM Component 1. Strengthening AP vers un hébergeur sécuris Public Resources Manageme Direct - Internation IDA / 70200 Post Direct Selection 15,000.00 0.00 Canceled 2023-07-25 2023-07-30 2023-09-03 2024-03-01 é, (frais d'hébergement) et A nt at Central Government Le al bonnement annuel de l'héber vel gement du SIGMAP avec l'ent reprise GODADDY ZR-COREF-362720-GO-RFB / Fourniture, installation et la mise en marche du datacent Component 2. Supporting er de secours au bâtiment ad Resource Management at th Single Stage - One E Pending Impl IDA / 70200 Post Request for Bids Open - National 216,000.00 0.00 2023-07-03 2023-07-08 2023-08-19 2023-09-18 2023-10-23 2024-04-20 ministratif de la fonction publ e Provincial Government Lev nvelope ementation ique du système intégré de g el estion des ressources humai nes et de la paie de l'adminis tration publique ZR-COREF-363973-GO-DIR / Appui à la migration du SIGM Component 1. Strengthening AP vers un hébergeur sécuris Public Resources Manageme Pending Impl IDA / 70200 Post Direct Selection Direct - National 15,000.00 0.00 2023-05-30 2023-06-04 2023-07-09 2024-01-05 é (frais d'hebergement) et ab nt at Central Government Le ementation onnement annuel de l'heberg vel ement du SIGMAP avec l'entr eprise ITIK ZR-COREF-362725-GO-RFQ / Acquisition de 2 véhicules 4X Component 2. Supporting 4 pour faciliter le déploiemen Resource Management at th Request for Quota Single Stage - One E Pending Impl t des équipes de recensemen IDA / 70200 Post Limited 160,000.00 0.00 2023-07-06 2023-08-31 2024-02-27 e Provincial Government Lev tions nvelope ementation t et de collecte des données el à Kinshasa et dans les 4 prov inces du Kasaï, Kasaï Central, Kasaï Oriental et Lomami ZR-COREF-345281-GO-RFB / Acquisition des matériels info rmatiques pour les 12 nouvel Component 1. Strengthening les DAF, (Affaires étrangères, Public Resources Manageme Open - Internationa Single Stage - One E Under Revie IDA / 70200 Prior Request for Bids 2,200,000.00 0.00 2023-04-10 2023-04-15 2023-05-27 2023-06-26 2023-07-31 2024-01-27 Coopération international, Co nt at Central Government Le l nvelope w opération régionale, Economi vel e, Energie, Hydrocarbures, Je unesse, Mines, PME et artisa nat, PTNTIC, Sports et loisirs, Justice) ZR-COREF-362723-GO-RFQ / Component 3. Project and C Acquisition de 6 véhicules 4X Request for Quota Single Stage - One E Pending Impl IDA / 70200 hange Management, and Em Post Limited 480,000.00 0.00 2023-07-06 2023-08-31 2024-02-27 4 dont 2 pour la coordination tions nvelope ementation ergency Response nationale et 4 pour les coordi nations provinciales NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-COREF-264873-NC-DIR / Component 3. Project and C Recrutement d'un prestataire IDA / 70200 hange Management, and Em Post Direct Selection Direct 9,600.00 9,600.00 Completed 2021-12-10 2021-12-20 2021-12-15 2021-12-20 2021-12-31 2021-12-29 2022-04-30 2022-05-10 de service d'entretien des bu ergency Response reaux ZR-COREF-264876-NC-DIR / Component 3. Project and C Recrutement d'un prestataire IDA / 70200 hange Management, and Em Post Direct Selection Direct 12,000.00 12,000.00 Completed 2021-12-15 2021-12-20 2021-12-20 2021-12-20 2021-12-31 2021-12-29 2022-04-30 2022-04-26 pour le service de gardienna ergency Response ge des bureaux de la Coordin ation nationale ZR-COREF-264970-NC-RFQ / Component 3. Project and C Request for Quota Single Stage - One E Service d'assurance médical / hange Management, and Em Post Limited 50,000.00 0.00 Canceled 2021-12-08 2022-01-06 2022-04-27 tions nvelope e pour le personnel du Projet ergency Response (Période du PPA) ZR-COREF-296507-NC-DIR / Renouvellement contrat pres Component 3. Project and C tataire de service d'entretien IDA / 70200 hange Management, and Em Post Direct Selection Direct 7,200.00 7,200.00 Completed 2022-05-23 2022-05-23 2022-05-25 2022-05-23 2022-05-29 2022-05-31 2022-07-31 2022-08-18 et nettoyage des bureaux (d ergency Response e Mai à Juillet 2022) - BAM'S CLEAN ZR-COREF-296508-NC-DIR / Renouvellement contrat du p restataire pour le service de Component 3. Project and C gardiennage et sécurité des IDA / 70200 hange Management, and Em Post Direct Selection Direct 9,000.00 9,000.00 Completed 2022-05-23 2022-05-23 2022-05-25 2022-05-23 2022-05-29 2022-05-31 2022-07-31 2022-07-26 bureaux de la Coordination N ergency Response ationale du Projet ENCORE (d e Mai à Juin 2022) - ATALANT E GROUP ZR-COREF-316188-NC-DIR / Component 3. Project and C Renouvellement contrat du p IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 40,000.00 0.00 Signed 2022-09-20 2022-11-30 2022-09-22 2022-12-14 2022-09-26 2023-09-26 restataire de service de netto ergency Response yage des bureaux Page 3 ZR-COREF-316202-NC-DIR / Renouvellement contrat du p Component 3. Project and C restataire de service de gardi IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 40,000.00 0.00 Signed 2022-09-20 2022-11-30 2022-09-22 2022-12-14 2022-09-26 2023-07-31 ennage et sécurité des burea ergency Response ux de la Coordination Nation ale du Projet ZR-COREF-345709-NC-RFQ / Sélection d'une maison de pr Component 3. Project and C oduction (agence de presse) Request for Quota Single Stage - One E Pending Impl IDA / 70200 hange Management, and Em Post Limited 20,000.00 0.00 2023-04-22 2023-06-17 2023-12-14 pour la prise des images, la c tions nvelope ementation ergency Response onception d'un documentaire sur le lancement du projet da ns les 5 sites et sa diffusion ZR-COREF-345004-NC-DIR / Renouvellement contrat du p Component 3. Project and C restataire de service de gardi Pending Impl IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 40,000.00 0.00 2023-07-15 2023-07-25 2023-07-31 2024-07-30 ennage et sécurité des burea ementation ergency Response ux de la Coordination Nation ale du Projet avec ATALANT Group ZR-COREF-345000-NC-DIR / Contrat de prestation de serv Component 3. Project and C Pending Impl ice de nettoyage des bureau IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 40,000.00 0.00 2023-07-15 2023-07-25 2023-07-29 2024-07-28 ementation x de la Coordination du Proje ergency Response t ENCORE, Etablissement BA M’S CLEAN ZR-COREF-356049-NC-RFQ / Fourniture, installation et par Component 1. Strengthening amétrage du réseau dans les Public Resources Manageme Request for Quota Single Stage - One E Pending Impl IDA / 70200 Post Limited 100,000.00 0.00 2023-05-04 2023-06-29 2023-12-26 4 centres d'ordonnancement nt at Central Government Le tions nvelope ementation des Mininistères: Santé, EPS vel T, ITPR, et Développement ru ral CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-COREF-264820-CS-CQS / Component 1. Strengthening Sélection d'un Cabinet Inter Public Resources Manageme Consultant Qualifi Open - Internationa national pour le développem IDA / 70200 Post 150,000.00 145,400.00 Signed 2021-12-10 2021-12-16 2022-01-09 2022-01-06 2022-01-24 2022-03-24 2022-02-03 2022-04-05 2022-02-13 2022-05-24 2022-04-29 nt at Central Government Le cation Selection l ent de la stratégie de mise e vel n œuvre d'une solution e-GP ZR-COREF-264866-CS-CQS / Sélection d'un Cabinet pour l Component 3. Project and C Consultant Qualifi a rédaction du manuel des pr IDA / 70200 hange Management, and Em Post Open - National 50,000.00 47,410.00 Completed 2021-12-22 2021-12-16 2022-01-05 2021-12-23 2022-01-25 2022-03-01 2022-02-01 2022-03-14 2022-02-18 2022-03-16 2022-04-29 2022-07-12 cation Selection océdures de gestion financièr ergency Response e et de la passation des marc hés du Projet ENCORE ZR-COREF-264867-CS-CQS / Component 3. Project and C Sélection d'un Cabinet Webm Consultant Qualifi IDA / 70200 hange Management, and Em Post Open - National 15,000.00 0.00 Signed 2021-12-20 2022-01-25 2022-01-03 2022-01-23 2022-03-16 2022-02-02 2022-05-30 2022-02-19 2022-04-30 aster pour la mise en place d cation Selection ergency Response u Site WEB du Projet ENCORE ZR-COREF-265013-CS-CQS / Component 2. Supporting Sélection d'un Cabinet Webm Resource Management at th Consultant Qualifi IDA / 70200 Post Open - National 45,000.00 44,554.80 Signed 2021-12-20 2022-01-25 2022-01-03 2022-01-23 2022-03-16 2022-01-28 2022-05-30 2022-02-17 2022-06-03 2022-04-30 aster pour la mise en place d e Provincial Government Lev cation Selection u Site WEB de 4 provinces sé el lectionnées ZR-COREF-296044-CS-QCBS Component 1. Strengthening / Sélection d'un Consultant fir Public Resources Manageme Quality And Cost- Open - Internationa Under Implement me pour accompagner la mis IDA / 70200 Prior 2,000,000.00 0.00 2022-06-15 2022-06-13 2022-07-30 2022-06-23 2022-09-03 2022-10-03 2022-10-24 2022-11-17 2022-12-22 2024-12-21 nt at Central Government Le Based Selection l ation e en service effective des str vel uctures de la DGTCP ZR-COREF-264863-CS-LCS / Sélection d'un Cabinet indép Component 3. Project and C Least Cost Selecti Open - Internationa endant pour l'Audit financier / hange Management, and Em Post 25,000.00 0.00 Canceled 2021-12-10 2021-12-31 2022-01-21 2022-02-18 2022-02-25 2022-03-17 2022-03-31 2022-06-29 on l externe sur la gestion fiducia ergency Response ire du PPA clos au 30/04/202 2 ZR-COREF-344156-CS-QCBS / Recrutement d'un Consulta nt International firme pour le Component 1. Strengthening renforcement de capacités d Public Resources Manageme Quality And Cost- Open - Internationa Pending Impleme IDA / 70200 Post 150,000.00 0.00 2023-04-20 2023-05-11 2023-06-24 2023-07-22 2023-08-21 2023-09-25 2023-10-30 2024-10-29 es membres de la Commissio nt at Central Government Le Based Selection l ntation n interministérielle de la vali vel dation des études de faisabili té d'un projet minier avec la participation des OSC ZR-COREF-344187-CS-QCBS / Recrutement d'un Cabinet i Component 1. Strengthening nternational pour évaluer les Public Resources Manageme Quality And Cost- Open - Internationa Under Implement besoins en renforcement de IDA / 70200 Post 180,000.00 0.00 2023-03-18 2023-06-21 2023-04-08 2023-05-13 2023-06-10 2023-07-01 2023-08-05 2023-09-09 2024-09-08 nt at Central Government Le Based Selection l ation capacités des services interv vel enant dans la gestion des rev enus miniers et autres partie s prenantes ZR-COREF-344190-CS-QCBS / Recrutement d'un Cabinet i Component 1. Strengthening nternational pour évaluer les Public Resources Manageme Quality And Cost- Open - Internationa Pending Impleme besoins techniques en renfor IDA / 70200 Post 180,000.00 0.00 2023-03-15 2023-04-05 2023-05-10 2023-06-07 2023-07-07 2023-08-11 2023-09-15 2024-09-14 nt at Central Government Le Based Selection l ntation cement de capacités de la C vel ommission interministérielle d'harmonisation et de consoli dation des statistiques minièr es ZR-COREF-344276-CS-QCBS / Recrutement d’une Cabinet International devant appuyer Component 1. Strengthening le gouvernement à : (i) défini Public Resources Manageme Quality And Cost- Open - Internationa Pending Impleme r le nouveau cadre organisati IDA / 70200 Post 180,000.00 0.00 2023-04-10 2023-05-01 2023-06-05 2023-07-03 2023-07-24 2023-08-28 2023-10-02 2024-10-01 nt at Central Government Le Based Selection l ntation onnel et juridique, (ii) élabor vel er le manuel de procédures d es dépenses non salariales ; ( iii) proposer l'adaption de la chaîne de dépense/sys ZR-COREF-344288-CS-QCBS / Recrutement d'un cabinet p Component 1. Strengthening our assurer la formation des Public Resources Manageme Quality And Cost- Open - Internationa Pending Impleme IDA / 70200 Post 400,000.00 0.00 2023-04-03 2023-04-24 2023-05-29 2023-06-26 2023-07-17 2023-08-21 2023-09-25 2024-09-24 DAF suivant plan de formatio nt at Central Government Le Based Selection l ntation n sur une période de 6 mois ( vel suivant les modules et group es) Page 4 ZR-COREF-344335-CS-QCBS / Recrutement d'une Firme c Component 1. Strengthening hargée d'appuyer le Ministèr Public Resources Manageme Quality And Cost- Open - Internationa Under Implement e de la Fonction Publique en IDA / 70200 Post 600,000.00 0.00 2023-03-27 2023-04-21 2023-04-17 2023-05-31 2023-06-28 2023-07-28 2023-09-01 2023-10-06 2024-10-05 nt at Central Government Le Based Selection l ation matière de la méthologie et vel planification de la constitutio n du Fichier de Référence de l'Administration Publique ZR-COREF-344343-CS-QCBS Component 1. Strengthening / Recrutement d'une Firme p Public Resources Manageme Quality And Cost- Open - Internationa Under Implement IDA / 70200 Prior 1,300,000.00 0.00 2023-03-15 2023-04-05 2023-05-19 2023-06-16 2023-07-16 2023-08-20 2023-09-24 2024-09-23 our la constitution du Fichier nt at Central Government Le Based Selection l ation de Référence de l'Administra vel tion Publique ZR-COREF-344418-CS-QCBS / Recrutement d’une firme po ur l'assistance en maître d'ou Component 1. Strengthening vrage du SIGeFiP avec le noy Public Resources Manageme Quality And Cost- Open - Internationa Pending Impleme au composé des modules co IDA / 70200 Post 150,000.00 0.00 2023-05-08 2023-05-29 2023-07-12 2023-08-09 2023-09-08 2023-10-13 2023-11-17 2024-11-16 nt at Central Government Le Based Selection l ntation mptable et budgétaire (étude vel s préalables et analyse des b esoins complémentaires en r enforcement de capacités et en équipements pour la mise en pla ZR-COREF-344472-CS-LCS / Component 1. Strengthening Recrutement d'un cabinet int Public Resources Manageme Least Cost Selecti Open - Internationa Pending Impleme IDA / 70200 Post 160,000.00 0.00 2023-04-05 2023-04-26 2023-06-09 2023-07-07 2023-08-06 2023-09-10 2023-10-15 2024-01-13 ernational chargé de l'audit i nt at Central Government Le on l ntation ndépendant en PPP (exercice vel 2019-2022) ZR-COREF-344478-CS-QCBS / Recrutement d’un consulta Component 1. Strengthening nt sénior international pour l’ Public Resources Manageme Quality And Cost- Open - Internationa Under Implement élaboration de la stratégie de IDA / 70200 Post 100,000.00 0.00 2023-03-22 2023-05-20 2023-04-12 2023-05-26 2023-06-23 2023-07-23 2023-08-27 2023-10-01 2023-11-30 nt at Central Government Le Based Selection l ation renforcement des capacités, vel de formation et de profession nalisation des acteurs nation aux de la commande publiq ue. ZR-COREF-344507-CS-QCBS Component 1. Strengthening / Recrutement d'une firme po Public Resources Manageme Quality And Cost- Under Implement IDA / 70200 Post Open - National 300,000.00 0.00 2023-03-20 2023-04-10 2023-04-10 2023-05-24 2023-06-21 2023-07-21 2023-08-25 2023-09-29 2023-12-28 ur réaliser l'audit organisatio nt at Central Government Le Based Selection ation nnel du Conseil Supérieur du vel Portefeuille (CSP) ZR-COREF-344755-CS-QCBS / Recrutement d'un consultan Component 1. Strengthening t cabinet pour l'élaboration d' Public Resources Manageme Quality And Cost- Open - Internationa Pending Impleme un plan de renforcement des IDA / 70200 Post 250,000.00 0.00 2023-04-13 2023-05-04 2023-06-17 2023-07-15 2023-08-14 2023-09-18 2023-10-23 2024-10-22 nt at Central Government Le Based Selection l ntation capacités du CSP, COPIREP, d vel u Secrétariat Général et des managers des entreprises pu bliques ciblées par le projet ZR-COREF-344884-CS-QCBS / Recrutement d'un Cabinet p our assistance-métier et tech Component 2. Supporting nique pour la mise en place d Resource Management at th Quality And Cost- Open - Internationa Pending Impleme 'un système d'informations d IDA / 70200 Post 500,000.00 0.00 2023-04-05 2023-04-26 2023-06-09 2023-07-07 2023-08-06 2023-09-10 2023-10-15 2024-10-14 e Provincial Government Lev Based Selection l ntation e collecte des prélèvements f el iscaux et non fiscaux dans le s 4 provinces (du Kasaï Orien tal, du Kasaï, du Kasaï Centra l et de Lomami) ZR-COREF-345075-CS-CQS / Component 3. Project and C Recrutement d’une ONG spé Consultant Qualifi Under Implement IDA / 70200 hange Management, and Em Post Open - National 300,000.00 0.00 2023-04-07 2023-04-11 2023-04-28 2023-06-11 2023-07-11 2023-08-15 2024-02-11 cialisée en VBG pendant la m cation Selection ation ergency Response ise en œuvre du projet ZR-COREF-344126-CS-QCBS / Recrutement d'un Consulta Component 1. Strengthening nt International firme pour la Public Resources Manageme Quality And Cost- Open - Internationa Pending Impleme réalisation de l'étude sur le p IDA / 70200 Post 100,000.00 0.00 2023-04-15 2023-04-29 2023-06-03 2023-07-01 2023-07-03 2023-08-07 2023-09-11 2024-09-10 nt at Central Government Le Based Selection l ntation otentiel fiscal du secteur mini vel er de la République Démocra tique du Congo y compris l'a nalyse et l'audit du régime fi scal ZR-COREF-356052-CS-CQS / Recrutement d’un Cabinet int ernational chargé d' (i) évalu Component 3. Project and C Consultant Qualifi Open - Internationa Under Implement ation environnementale et so IDA / 70200 hange Management, and Em Post 400,000.00 0.00 2023-04-25 2023-05-12 2023-05-16 2023-06-29 2023-07-29 2023-09-02 2024-02-29 cation Selection l ation ciale stratégique et (ii) évalu ergency Response ation du partage des bénéfic es de l’exploitation minière a vec les communautés locales ZR-COREF-355997-CS-CQS / Recrutement du Cabinet Inte rnational chargé d'effectuer l' Component 1. Strengthening étude de cadrage sur l'artisa Public Resources Manageme Consultant Qualifi Open - Internationa Pending Impleme IDA / 70200 Post 200,000.00 0.00 2023-04-25 2023-05-16 2023-06-29 2023-07-29 2023-09-02 2024-02-29 nat minier, Filière Diamant a nt at Central Government Le cation Selection l ntation u Kasaï Oriental et Kasaï aup vel rès des régies provinciales (E TDs et Direction des recettes provinciales) ZR-COREF-356053-CS-CQS / Recrutement d'un Cabinet In Component 1. Strengthening dépendant chargé d'élaborer Public Resources Manageme Consultant Qualifi Open - Internationa Pending Impleme le Rapport sur l'artisanat min IDA / 70200 Post 130,000.00 0.00 2023-04-25 2023-05-16 2023-06-29 2023-07-29 2023-09-02 2024-02-29 nt at Central Government Le cation Selection l ntation ier, Filière Diamant au Kasaï vel Oriental et Kasaï auprès des régies provinciales (ETD et Di rection des recettes provinci ales). ZR-COREF-355930-CS-CQS / Recrutement d'un cabinet ch Component 3. Project and C Consultant Qualifi Open - Internationa Under Implement argé de l'audit financier et co IDA / 70200 hange Management, and Em Post 50,000.00 0.00 2023-04-18 2023-04-24 2023-05-09 2023-06-22 2023-07-22 2023-08-26 2024-02-22 cation Selection l ation mptable du Projet ENCORE p ergency Response our l'exercice clos 2022 com prenant aussi le PPA ZR-COREF-355935-CS-QCBS / Recrutement d'un cabinet c Component 3. Project and C Quality And Cost- Open - Internationa hargé de l'audit financier et c IDA / 70200 hange Management, and Em Post 150,000.00 0.00 Under Review 2023-05-05 2023-04-24 2023-05-26 2023-06-11 2023-07-09 2023-08-08 2023-09-12 2023-10-17 2024-10-16 Based Selection l omptable du Projet ENCORE ergency Response pour les Exercices 2023, 202 4 et 2025 ZR-COREF-345046-CS-QCBS Component 3. Project and C Quality And Cost- Open - Internationa / Recrutement d'un auditeur IDA / 70200 hange Management, and Em Post 120,000.00 0.00 Canceled 2023-03-10 2023-03-16 2023-03-31 2023-04-16 2023-05-14 2023-06-13 2023-07-18 2023-08-22 2024-08-21 Based Selection l externe (cabinet) ergency Response INDIVIDUAL CONSULTANTS Page 5 Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-COREF-264859-CS-INDV / Sélection d'un Consultant ind Component 3. Project and C Individual Consult ividuel pour la rédaction du IDA / 70200 hange Management, and Em Post Open 30,000.00 43,000.00 Completed 2021-12-15 2021-12-15 2022-01-13 2022-03-01 2022-01-20 2022-03-29 2022-02-01 2022-04-10 2022-04-28 2023-02-25 ant Selection manuel de vérification des P ergency Response BCs et PBPs du Projet ENCOR E ZR-COREF-265030-CS-INDV / Sélection d'un consultant indi Component 2. Supporting viduel pour réaliser une étud Resource Management at th Individual Consult e de faisabilité pour la mise e IDA / 70200 Post Open 50,000.00 0.00 Canceled 2021-12-20 2022-02-24 2022-01-22 2022-02-01 2022-02-14 2022-04-30 e Provincial Government Lev ant Selection n place des administrations p el rovinciales du trésor, de la co mptabilité et du budget dans 4 provinces identifiées ZR-COREF-265038-CS-INDV / Sélection d'un Consultant ind Component 3. Project and C ividuel chargé de finaliser le Individual Consult IDA / 70200 hange Management, and Em Post Open 25,000.00 22,035.00 Completed 2021-11-25 2021-12-15 2021-12-28 2022-02-18 2022-01-07 2022-03-11 2022-01-19 2022-03-15 2022-04-30 2022-07-12 Plan de mobilisation des parti ant Selection ergency Response es prenantes (PMPP) et les Pr océdures de gestion de main -d’œuvre (PGMO) ZR-COREF-265039-CS-INDV / Component 3. Project and C Sélection d'un Consultant ind Individual Consult IDA / 70200 hange Management, and Em Post Open 25,000.00 24,893.00 Completed 2021-12-20 2021-12-15 2022-01-15 2022-03-01 2022-01-29 2022-03-11 2022-02-09 2022-03-15 2022-04-30 2022-07-14 ividuel chargé de finaliser le ant Selection ergency Response Plan d'Action VBG - EAS/HS ZR-COREF-265078-CS-CDS / Sélection d'un Consultant Na Component 1. Strengthening tional individuel en Administr Public Resources Manageme ation Publique chargé d’appu / Post Direct Selection Direct 14,000.00 0.00 Canceled 2021-12-07 2021-12-15 2021-12-30 2022-04-30 nt at Central Government Le yer la mise en œuvre du Syst vel ème Intégré de Gestion des Ressources Humaines et de l a Paie (SIGRH-Paie)/ Jean LE MA ZR-COREF-265088-CS-INDV / Sélection d'un consultant int Component 1. Strengthening ernational pour 4 mois (CTP) Public Resources Manageme Individual Consult chargé d’accompagner l’équi IDA / 70200 Post Limited 40,000.00 0.00 Signed 2021-12-20 2022-03-08 2021-12-25 2022-03-29 2022-01-15 2022-12-30 2022-02-01 2022-04-02 nt at Central Government Le ant Selection pe technique nationale dans l vel 'organisation de l'enquête et l'actualisation de la base d'éc hantillonnage (ECVM) ZR-COREF-265089-CS-INDV / Sélection d'un consultant int Component 1. Strengthening ernational expert en sondage Public Resources Manageme Individual Consult pour 4 mois chargé d’accom IDA / 70200 Post Limited 40,000.00 0.00 Canceled 2021-12-10 2022-03-08 2021-12-15 2021-12-29 2022-01-10 2022-04-30 nt at Central Government Le ant Selection pagner l’équipe technique na vel tionale dans l'organisation de l'enquête et l'actualisation de la base d'échantillonnage ZR-COREF-265092-CS-INDV / Sélection d'un consultant int Component 1. Strengthening ernational expert en CAPI po Public Resources Manageme Individual Consult ur 2 mois chargé d’accompa IDA / 70200 Post Limited 20,000.00 0.00 Signed 2021-12-15 2022-03-08 2021-12-20 2022-03-29 2022-01-03 2023-03-03 2022-01-15 2022-04-30 nt at Central Government Le ant Selection gner l’équipe technique natio vel nale dans l'organisation de l' enquête et l'actualisation de la base d'échantillonnage (EC VM) ZR-COREF-265093-CS-CDS / Component 3. Project and C Recrutement d'un Coordonna IDA / 70200 hange Management, and Em Post Direct Selection Direct 28,000.00 29,600.00 Completed 2021-12-10 2021-12-23 2021-12-18 2021-12-24 2021-12-30 2021-12-25 2022-04-30 2022-04-26 teur National du Projet (Gode ergency Response froid MISENGA) ZR-COREF-265097-CS-CDS / Recrutement d'un Spécialiste Component 3. Project and C en charge de la réforme du s IDA / 70200 hange Management, and Em Post Direct Selection Direct 18,000.00 19,200.00 Completed 2021-12-10 2022-01-11 2021-12-18 2022-01-12 2021-12-30 2022-01-13 2022-04-30 2022-04-26 ystème des marchés publics ergency Response (Jean Baptiste VEKO) ZR-COREF-265098-CS-CDS / Recrutement d'un Spécialiste Component 3. Project and C en charge de la réforme du s IDA / 70200 hange Management, and Em Post Direct Selection Direct 18,000.00 19,200.00 Completed 2021-12-10 2022-01-10 2021-12-18 2022-01-10 2021-12-30 2022-01-11 2022-04-30 2022-04-26 ystème comptable et gestion ergency Response de la trésorerie (Robert BAM BA) ZR-COREF-265100-CS-CDS / Recrutement d'un Spécialiste Component 3. Project and C en charge de la réforme de l' / hange Management, and Em Post Direct Selection Direct 18,000.00 0.00 Canceled 2021-12-10 2021-12-18 2021-12-30 2022-04-30 administration fiscale et gesti ergency Response on des revenus miniers (Jean Pierre SAMOLIA) ZR-COREF-265101-CS-CDS / Component 3. Project and C Recrutement d'un Spécialiste IDA / 70200 hange Management, and Em Post Direct Selection Direct 18,000.00 19,200.00 Completed 2021-12-10 2022-01-10 2021-12-18 2022-01-10 2021-12-30 2022-01-11 2022-04-30 2022-04-26 en charge du contrôle intern ergency Response e et externe (ETIENNE MAFW ENI) ZR-COREF-265103-CS-CDS / Component 3. Project and C Recrutement d'un Spécialiste IDA / 70200 hange Management, and Em Post Direct Selection Direct 18,000.00 19,200.00 Completed 2021-12-10 2022-01-11 2021-12-18 2022-01-12 2021-12-30 2022-01-13 2022-04-30 2022-04-26 en charge de la décentralisat ergency Response ion financière (Moise ASSANI) ZR-COREF-265104-CS-CDS / Component 3. Project and C Recrutement d'un Responsab IDA / 70200 hange Management, and Em Post Direct Selection Direct 17,200.00 18,400.00 Completed 2021-12-10 2021-12-25 2021-12-18 2021-12-28 2021-12-30 2021-12-29 2022-04-30 2022-04-26 le Administratif et Financier ( ergency Response EMILE ASELE) ZR-COREF-265105-CS-CDS / Component 3. Project and C Recrutement d'un Spécialiste IDA / 70200 hange Management, and Em Post Direct Selection Direct 17,200.00 18,400.00 Completed 2021-12-10 2021-12-23 2021-12-18 2021-12-24 2021-12-30 2021-12-25 2022-04-30 2022-04-26 Sénior en Passation des Marc ergency Response hés (Luc M. SUKADI) ZR-COREF-265106-CS-CDS / Component 3. Project and C Recrutement d'un Spécialiste IDA / 70200 hange Management, and Em Post Direct Selection Direct 17,200.00 18,400.00 Completed 2021-12-10 2021-12-23 2021-12-18 2021-12-24 2021-12-30 2021-12-25 2022-04-30 2022-04-26 sénior en Suivi & Evaluation ergency Response (Jules KWILU) ZR-COREF-265107-CS-CDS / Component 3. Project and C Recrutement d'un (e) Assista IDA / 70200 hange Management, and Em Post Direct Selection Direct 11,400.00 12,400.00 Completed 2021-12-10 2021-12-23 2021-12-18 2021-12-24 2021-12-30 2021-12-25 2022-04-30 2022-04-26 nt (e) principal (e) de coordin ergency Response ation (Véronique MANYA) Page 6 ZR-COREF-265110-CS-CDS / Component 3. Project and C Recrutement d'un (e) Assista IDA / 70200 hange Management, and Em Post Direct Selection Direct 6,000.00 7,000.00 Completed 2021-12-10 2021-12-23 2021-12-18 2021-12-24 2021-12-30 2021-12-25 2022-04-30 2022-04-26 nt (e) en Passation des marc ergency Response hés (Gisele MUAHUKA) ZR-COREF-265111-CS-INDV / Component 3. Project and C Individual Consult Recrutement d'un (e) Récepti IDA / 70200 hange Management, and Em Post Limited 4,000.00 1,000.00 Completed 2021-12-07 2021-12-15 2021-12-21 2021-12-28 2021-12-24 2021-12-29 2021-12-30 2022-01-01 2022-04-30 2022-04-26 ant Selection onniste ergency Response ZR-COREF-265113-CS-CDS / Component 3. Project and C Recrutement d'un Chauffeur IDA / 70200 hange Management, and Em Post Direct Selection Direct 3,200.00 4,000.00 Completed 2021-12-10 2021-12-23 2021-12-18 2021-12-24 2021-12-30 2021-12-25 2022-04-30 2022-04-26 (Jean BELO MUYUMBA) ergency Response ZR-COREF-265253-CS-CDS / Component 3. Project and C Recrutement d'un Coordonat IDA / 70200 hange Management, and Em Post Direct Selection Direct 28,000.00 28,000.00 Completed 2021-12-10 2022-01-19 2021-12-18 2022-01-21 2021-12-30 2022-01-22 2022-04-30 2022-05-04 eur de la Cellule de Suivi des ergency Response Projets et Programmes CSPP (Honoré TSHIYOYO) ZR-COREF-265255-CS-CDS / Recrutement d'un Coordonna Component 3. Project and C teur Adjoint de la Cellule de IDA / 70200 hange Management, and Em Post Direct Selection Direct 20,000.00 20,000.00 Completed 2021-12-10 2022-01-19 2021-12-18 2022-01-21 2021-12-30 2022-01-22 2022-04-30 2022-05-04 Suivi des Projets et Program ergency Response mes CSPP ( Clément MBIKAYI ) ZR-COREF-265269-CS-CDS / Recrutement d'un Chargé de Component 3. Project and C s Projets à la Section Appui O IDA / 70200 hange Management, and Em Post Direct Selection Direct 12,000.00 12,000.00 Completed 2021-12-10 2022-01-19 2021-12-18 2022-01-21 2021-12-30 2022-01-22 2022-04-30 2022-05-04 pératoire '1) de la Cellule de ergency Response Suivi des Projets et Program mes CSPP ( Audry KAZEMBOL A) ZR-COREF-265272-CS-CDS / Recrutement d'un Chargé de Component 3. Project and C s Projets à la Section Moyens IDA / 70200 hange Management, and Em Post Direct Selection Direct 12,000.00 12,000.00 Completed 2021-12-10 2022-01-19 2021-12-18 2022-01-21 2021-12-30 2022-01-22 2022-04-30 2022-05-04 Généraux de la Cellule de Sui ergency Response vi des Projets et Programmes CSPP (GRATIAS KAYIBABU KA BUYA) ZR-COREF-265273-CS-CDS / Recrutement d'un Chargé de Component 3. Project and C s Projets à la Section Fiduciai IDA / 70200 hange Management, and Em Post Direct Selection Direct 12,000.00 12,000.00 Completed 2021-12-10 2022-01-19 2021-12-18 2022-02-19 2021-12-30 2022-01-22 2022-04-30 2022-05-04 re de la Cellule de Suivi des P ergency Response rojets et Programmes CSPP ( Diamant EBENE) ZR-COREF-265276-CS-CDS / Recrutement d'un Chargé de Component 3. Project and C s Projets à la Section Fiduciai IDA / 70200 hange Management, and Em Post Direct Selection Direct 12,000.00 12,000.00 Completed 2021-12-10 2022-01-19 2021-12-18 2022-01-21 2021-12-30 2022-01-22 2022-04-30 2022-05-04 re de la Cellule des Projets et ergency Response Programmes CSPP (Lourlaine MUANZA) ZR-COREF-265277-CS-CDS / Recrutement d'un Chargé de Component 3. Project and C s Projets à la Section Appui O IDA / 70200 hange Management, and Em Post Direct Selection Direct 12,000.00 12,000.00 Completed 2021-12-10 2022-01-19 2021-12-18 2022-01-21 2021-12-30 2022-01-22 2022-04-30 2022-05-04 pératoire de la Cellule de Sui ergency Response vi des Projets et Programmes CSPP ( Samuel KAULU) ZR-COREF-265278-CS-CDS / Recrutement d'un Chargé de Component 3. Project and C s Projets à la Section Fiduciai IDA / 70200 hange Management, and Em Post Direct Selection Direct 12,000.00 12,000.00 Completed 2021-12-10 2022-01-19 2021-12-18 2022-01-21 2021-12-30 2022-01-22 2022-04-30 2022-05-04 re de la Cellule de Suivi des P ergency Response rojets et Programmes CSPP ( Eddy MBUNGU) ZR-COREF-265419-CS-CDS / Component 1. Strengthening Sélection d'un Consultant Ind Public Resources Manageme ividuel pour appuyer la 2ème IDA / 70200 Post Direct Selection Direct 16,000.00 37,050.00 Signed 2021-12-15 2022-04-29 2021-12-25 2022-05-20 2022-01-05 2022-05-31 2022-04-30 nt at Central Government Le phase de la mise en place de vel SIGMAP (20 nouvelles cellule s)/ Pierre TSHIYOMBO ZR-COREF-265010-CS-INDV / Component 1. Strengthening Sélection d'un consultant indi Public Resources Manageme Individual Consult viduel pour la mise en place / Post Limited 50,000.00 0.00 Canceled 2021-12-24 2021-12-27 2022-01-10 2022-01-30 2022-04-30 nt at Central Government Le ant Selection d'un système de gestion bud vel gétaire en Provinces ZR-COREF-265027-CS-CDS / Sélection d'un consultant indi Component 2. Supporting viduel chargé d'appuyer l'éla Resource Management at th IDA / 70200 Post Direct Selection Direct 70,000.00 46,395.00 Completed 2022-01-03 2022-02-25 2022-01-11 2022-03-18 2022-01-29 2022-04-17 2022-04-29 2022-12-27 boration des textes fixant les e Provincial Government Lev modalités de répartition des el recettes à caractère national (Michael WINTER) ZR-COREF-267867-CS-CDS / Consultant pour l'appui à la p Component 1. Strengthening réparation de l'Enquête sur l Public Resources Manageme IDA / 70200 Post Direct Selection Direct 450,000.00 0.00 Signed 2021-12-27 2022-12-22 2022-01-06 2022-12-24 2022-01-19 2022-04-30 es Conditions de Vie des Mén nt at Central Government Le ages (ECVM): Enquête sur les vel Unités non conventionnelles (NSU) avec PNUD Component 3. Project and C ZR-COREF-270844-CS-INDV / Individual Consult IDA / V4000 hange Management, and Em Post Limited 6,000.00 7,000.00 Completed 2021-12-27 2021-12-31 2022-01-01 2022-01-05 2022-01-02 2022-01-07 2022-01-08 2022-01-11 2022-04-30 2022-04-26 Recrutement d'un Trésorier ant Selection ergency Response ZR-COREF-265109-CS-CDS / Component 3. Project and C Recrutement d'un (e) Trésori / hange Management, and Em Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-12-10 2021-12-18 2021-12-30 2022-04-30 er (e) ( Sylvie NGEVESISE) ergency Response ZR-COREF-265108-CS-CDS / Component 3. Project and C Recrutement d'un Comptable IDA / V4000 hange Management, and Em Post Direct Selection Direct 10,000.00 11,000.00 Completed 2021-12-30 2021-12-31 2022-01-03 2022-01-04 2022-01-08 2022-01-05 2022-04-30 2022-04-26 (Sylvie NGEVESISE) ergency Response ZR-COREF-280723-CS-CDS / Component 3. Project and C Recrutement d'un Spécialiste IDA / V4000 hange Management, and Em Post Direct Selection Direct 18,000.00 9,600.00 Completed 2022-02-23 2022-02-28 2022-02-27 2022-03-01 2022-03-02 2022-03-02 2022-04-30 2022-04-26 en charge du suivi des donn ergency Response ées statistiques sur la pauvre té (SASSE KEMBE) ZR-COREF-296056-CS-CDS / Component 1. Strengthening Sélection d'un consultant int Public Resources Manageme IDA / V4000 Post Direct Selection Direct 50,000.00 0.00 Signed 2022-06-10 2022-06-08 2022-06-20 2022-06-18 2022-06-28 2022-09-26 ernational pour la finalisation nt at Central Government Le du cahier des charges et du vel DAO du SiGeFiP Page 7 ZR-COREF-264872-CS-INDV / Sélection d'un consultant po Component 1. Strengthening ur l'évaluation de la répartiti Public Resources Manageme Individual Consult / Post Limited 30,000.00 0.00 Canceled 2022-01-10 2022-01-24 2022-01-31 2022-02-17 2022-04-18 on effective (Etude Benefit S nt at Central Government Le ant Selection haring Assessment ou BSA) d vel es recettes minières au nivea u local (0.3% aux ETDs) ZR-COREF-265068-CS-CDS / Sélection d'un Consultant Ex pert en informatique et systè Component 1. Strengthening mes d’information chargé d’a Public Resources Manageme / Post Direct Selection Direct 14,000.00 0.00 Canceled 2021-12-07 2021-12-15 2021-12-30 2022-04-30 ppuyer la mise en œuvre du nt at Central Government Le Système Intégré de Gestion vel des Ressources Humaines et de la Paie (SIGRH-Paie)! PIER RE TSHIYOMBO ZR-COREF-265080-CS-CDS / Component 1. Strengthening Sélection d'un Consultant int Public Resources Manageme ernational chargé de l' appui IDA / V4000 Post Direct Selection Direct 100,000.00 63,625.00 Completed 2022-05-30 2022-05-31 2022-06-07 2022-06-13 2022-06-22 2022-07-08 2022-10-21 2022-12-27 nt at Central Government Le a la mise en œuvre du SIGRH vel -Paie/ GERARD VERGER ZR-COREF-265082-CS-CDS / Sélection d'un Consultant ind Component 1. Strengthening ividuel chargé de la concepti Public Resources Manageme on et la mise en œuvre d’une / Post Direct Selection Direct 45,000.00 0.00 Canceled 2021-12-20 2021-12-28 2022-01-12 2022-04-30 nt at Central Government Le plateforme web pour la mise vel à jour du fichier de référence des agents de l’Administratio n publique (FRAP 2)/BOB BOS EKO ZR-COREF-265412-CS-INDV / Sélection d'un Consultant Ind Component 3. Project and C ividuel pour le développeme Individual Consult / hange Management, and Em Post Limited 50,000.00 0.00 Canceled 2022-01-07 2022-02-16 2022-01-21 2022-01-31 2022-02-17 2022-04-18 nt , le paramétrage et la mis ant Selection ergency Response e en service du logiciel de st ockage et analyse des donné es du Suivi-Evaluation ZR-COREF-265411-CS-INDV / Sélection d'un Consultant Ind Component 3. Project and C ividuel pour le développeme Individual Consult IDA / 70200 hange Management, and Em Post Limited 30,000.00 0.00 Canceled 2021-12-20 2022-02-23 2022-01-03 2022-01-13 2022-01-30 2022-04-30 nt, le paramétrage et la mise ant Selection ergency Response en service du logiciel de gest ion de projet (technique et m ise en œuvre des activités) ZR-COREF-265095-CS-CDS / Component 3. Project and C Recrutement d'un Spécialiste IDA / 70200 hange Management, and Em Post Direct Selection Direct 18,000.00 0.00 Canceled 2021-12-10 2022-01-10 2021-12-18 2021-12-30 2022-04-30 en charge du suivi des donn ergency Response ées statistiques sur la pauvre té (SASSE KEMBE) ZR-COREF-296648-CS-INDV / Component 3. Project and C Recrutement du Coordonnat Individual Consult IDA / 70200 hange Management, and Em Post Limited 42,000.00 0.00 Signed 2022-06-10 2022-06-02 2022-06-24 2022-06-24 2022-07-08 2022-08-19 2022-07-21 2023-07-21 eur Provincial de la province ant Selection ergency Response du Kasaï Central ZR-COREF-296654-CS-INDV / Component 3. Project and C Recrutement d'un Coordonna Individual Consult IDA / 70200 hange Management, and Em Post Limited 42,000.00 38,400.00 Signed 2022-06-10 2022-06-02 2022-06-24 2022-06-24 2022-07-08 2022-07-04 2022-07-21 2022-08-20 2023-07-21 teur Provincial pour la provin ant Selection ergency Response ce du Kasaï Oriental ZR-COREF-296655-CS-INDV / Component 3. Project and C Individual Consult Recrutement d'un Coordonna IDA / 70200 hange Management, and Em Post Limited 42,000.00 0.00 Signed 2022-06-10 2022-06-02 2022-06-24 2022-06-24 2022-07-08 2022-08-19 2022-07-21 2023-07-21 ant Selection teur provincial pour la provin ergency Response ce de Lomami ZR-COREF-296656-CS-INDV / Component 3. Project and C Individual Consult Recrutement d'un Coordonna IDA / 70200 hange Management, and Em Post Limited 42,000.00 38,400.00 Signed 2022-06-10 2022-06-02 2022-06-24 2022-06-24 2022-07-08 2022-07-15 2022-07-21 2022-08-20 2023-07-21 ant Selection teur provincial pour la provin ergency Response ce du Kasaï ZR-COREF-296657-CS-INDV / Component 3. Project and C Recrutement d'un Assistant P Individual Consult IDA / 70200 hange Management, and Em Post Limited 24,000.00 0.00 Signed 2022-06-15 2022-06-02 2022-06-29 2022-06-24 2022-07-13 2022-08-20 2022-07-26 2023-07-26 rovincial chargé de l'Administ ant Selection ergency Response ration et Finances de la Provi nce du Kasaï Central ZR-COREF-296661-CS-INDV / Recrutement de l'Assistant Pr Component 3. Project and C Individual Consult ovincial Chargé de l'Administ IDA / 70200 hange Management, and Em Post Limited 24,000.00 0.00 Signed 2022-06-15 2022-06-02 2022-06-29 2022-06-24 2022-07-13 2022-08-20 2022-07-26 2023-07-26 ant Selection ration et Finances de la provi ergency Response nce du Kasaï Oriental ZR-COREF-296662-CS-INDV / Component 3. Project and C Recrutement de l'Assistant Pr Individual Consult IDA / 70200 hange Management, and Em Post Limited 24,000.00 0.00 Signed 2022-06-15 2022-06-02 2022-06-29 2022-06-24 2022-07-13 2022-08-20 2022-07-26 2023-07-26 ovincial chargé de l'Administr ant Selection ergency Response ation et Finances de la provin ce de Lomami ZR-COREF-296665-CS-INDV / Component 3. Project and C Recrutement de l'Assistant Pr Individual Consult IDA / 70200 hange Management, and Em Post Limited 24,000.00 0.00 Signed 2022-06-15 2022-06-08 2022-06-29 2022-06-24 2022-07-13 2022-08-20 2022-07-26 2023-07-26 ovincial chargé de l'Administr ant Selection ergency Response ation et Finances de la provin ce du Kasaï ZR-COREF-298958-CS-INDV / Component 3. Project and C Sélection d'un Consultant Sp Individual Consult IDA / 70200 hange Management, and Em Post Limited 51,600.00 55,200.00 Signed 2022-06-15 2022-06-08 2022-06-20 2022-06-23 2022-07-04 2022-07-27 2022-07-25 2022-07-28 2023-07-20 écialiste en Passation des ma ant Selection ergency Response rchés du Projet ENCORE ZR-COREF-305471-CS-INDV / Component 3. Project and C Recrutement d'Un Deuxième Individual Consult IDA / 70200 hange Management, and Em Post Limited 54,180.00 0.00 Signed 2022-08-15 2022-08-17 2022-08-20 2022-09-15 2022-08-27 2023-04-04 2022-09-13 2023-09-13 Spécialiste en SUivi Evaluatio ant Selection ergency Response n du Projet ENCORE ZR-COREF-305481-CS-INDV / Component 3. Project and C Individual Consult Recrutement d'un (e) Chargé IDA / 70200 hange Management, and Em Post Limited 31,500.00 0.00 Signed 2022-08-15 2022-08-17 2022-08-20 2022-09-13 2022-09-03 2022-09-29 2022-09-24 2023-09-24 ant Selection (e) de Communication du Pro ergency Response jet ENCORE ZR-COREF-305484-CS-INDV / Component 3. Project and C Individual Consult Recrutement d'un (e) Trésori IDA / 70200 hange Management, and Em Post Limited 18,900.00 0.00 Signed 2022-08-10 2022-08-17 2022-08-17 2022-09-13 2022-08-31 2022-09-23 2022-09-26 2022-11-01 ant Selection er (e) du Projet ENCORE ergency Response ZR-COREF-305485-CS-INDV / Component 3. Project and C Individual Consult Recrutement d'un (e) Caissie IDA / 70200 hange Management, and Em Post Limited 15,000.00 0.00 Signed 2022-08-10 2022-08-17 2022-08-17 2022-09-23 2022-08-31 2022-09-29 2022-09-26 2023-09-26 ant Selection r (e) du Projet ENCORE ergency Response ZR-COREF-305486-CS-INDV / Component 3. Project and C Individual Consult Recrutement d'un Comptable IDA / 70200 hange Management, and Em Post Limited 31,500.00 0.00 Signed 2022-08-15 2022-08-17 2022-08-20 2022-09-14 2022-09-10 2022-09-29 2022-10-15 2023-10-15 ant Selection Pour le Projet ENCORE ergency Response Page 8 ZR-COREF-305499-CS-INDV / Component 3. Project and C Recrutement d'un Chauffeur Individual Consult IDA / 70200 hange Management, and Em Post Limited 12,600.00 0.00 Signed 2022-08-15 2022-08-17 2022-08-20 2022-09-13 2022-08-27 2022-09-23 2022-09-15 2023-09-15 coursier de la Coordination d ant Selection ergency Response u Projet ENCORE ZR-COREF-305502-CS-INDV / Component 3. Project and C Recrutement d'un Deuxième Individual Consult IDA / 70200 hange Management, and Em Post Limited 10,800.00 0.00 Signed 2022-08-15 2022-08-17 2022-08-20 2022-09-13 2022-08-27 2022-09-23 2022-09-15 2023-09-15 Chauffeur Coursier de la Coor ant Selection ergency Response dination du Projet ENCORE ZR-COREF-305512-CS-INDV / Component 3. Project and C Recrutement d'un (e) Récepti Individual Consult IDA / 70200 hange Management, and Em Post Limited 12,600.00 0.00 Signed 2022-08-15 2022-08-17 2022-08-29 2022-09-13 2022-09-01 2022-09-23 2022-09-07 2023-09-07 onniste de la Coordination Na ant Selection ergency Response tionale du Projet ENCORE ZR-COREF-305514-CS-INDV / Component 3. Project and C Recrutement d'un (e) deuxiè Individual Consult IDA / 70200 hange Management, and Em Post Limited 12,600.00 0.00 Signed 2022-08-15 2022-08-17 2022-08-29 2022-09-13 2022-09-01 2022-09-23 2022-09-07 2023-09-07 me Réceptionniste de la Coor ant Selection ergency Response dination Nationale du projet ENCORE ZR-COREF-305517-CS-INDV / Component 3. Project and C Recrutement d'un (e) Spécial Individual Consult Under Implement IDA / 70200 hange Management, and Em Post Limited 56,700.00 0.00 2022-08-15 2023-04-12 2022-08-20 2022-09-03 2022-09-24 2023-09-24 iste chargé des systèmes d'i ant Selection ation ergency Response nformation du Projet ENCORE ZR-COREF-305522-CS-INDV / Recrutement d'un (e) Spécial Component 3. Project and C Individual Consult iste en charge de la réforme IDA / 70200 hange Management, and Em Post Limited 56,700.00 0.00 Signed 2022-08-15 2022-08-17 2022-08-20 2022-09-23 2022-09-03 2022-09-29 2022-09-24 2023-09-24 ant Selection de l'Administration fiscale et ergency Response gestion des revenus miniers ZR-COREF-305531-CS-INDV / Recrutement d'un (e) Spécial Component 3. Project and C Individual Consult iste en charge de la surveilla IDA / 70200 hange Management, and Em Post Limited 56,700.00 0.00 Signed 2022-08-15 2022-08-17 2022-08-20 2022-08-22 2022-09-10 2022-09-29 2022-10-01 2023-10-01 ant Selection nce des risques budgétaires l ergency Response iés à la gestion des Entrepris es publiques ZR-COREF-305540-CS-INDV / Component 3. Project and C Recrutement d'un Spécialiste Individual Consult IDA / 70200 hange Management, and Em Post Limited 54,180.00 0.00 Signed 2022-08-15 2022-08-17 2022-08-20 2022-09-15 2022-09-03 2022-11-22 2022-09-24 2022-10-30 en Charge des questions des ant Selection ergency Response Violences basées sur le genr e ZR-COREF-305547-CS-INDV / Component 3. Project and C Recrutement d'un (e) Spécial Individual Consult IDA / 70200 hange Management, and Em Post Limited 54,180.00 0.00 Signed 2022-08-15 2022-08-17 2022-08-20 2022-09-15 2022-09-03 2022-11-22 2022-09-24 2023-09-24 iste en sauvegarde environn ant Selection ergency Response ementale et sociale du projet ENCORE ZR-COREF-305557-CS-INDV / Component 3. Project and C Individual Consult Pending Impleme Recrutement d'un Assistant I IDA / 70200 hange Management, and Em Post Limited 18,900.00 0.00 2022-08-15 2022-08-20 2022-09-03 2022-09-24 2023-09-24 ant Selection ntation T ergency Response ZR-COREF-305561-CS-INDV / Component 3. Project and C Recrutement d'un (e) Assista Individual Consult IDA / 70200 hange Management, and Em Post Limited 25,200.00 0.00 Signed 2022-08-15 2022-08-17 2022-08-20 2022-08-22 2022-09-03 2022-08-29 2022-09-24 2023-09-24 nt (e) en décentralisation fin ant Selection ergency Response ancière et Budget Participatif ZR-COREF-305564-CS-INDV / Recrutement d'un Spécialiste Component 3. Project and C Individual Consult en charge de la gestion du c IDA / 70200 hange Management, and Em Post Limited 56,700.00 0.00 Signed 2022-08-15 2022-08-17 2022-08-20 2022-08-26 2022-09-03 2022-08-30 2022-09-24 2023-09-24 ant Selection hangement et du Budget Par ergency Response ticipatif du projet ENCORE ZR-COREF-305496-CS-CDS / Component 3. Project and C Renouvellement contrat du C IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 9,600.00 12,000.00 Signed 2022-07-25 2022-08-19 2022-07-28 2022-08-19 2022-08-02 2022-08-20 2024-08-01 hauffeur de la Coordination N ergency Response ationale du Projet ENCORE - BELO MUYUMBA ZR-COREF-305107-CS-CDS / Component 3. Project and C Renouvellement du contrat d IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 54,000.00 57,600.00 Signed 2022-07-25 2022-08-19 2022-07-28 2022-08-19 2022-08-02 2022-08-20 2024-08-01 u Spécialiste en charge du co ergency Response ntrôle interne et externe - Eti enne Mafweni ZR-COREF-305468-CS-CDS / Component 3. Project and C Renouvellement du Contrat d IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 51,600.00 55,200.00 Signed 2022-07-25 2022-08-19 2022-07-28 2022-08-19 2022-08-02 2022-08-20 2024-08-01 u Responsable Administratif ergency Response et Financier (RAF) du Projet E NCORE - Emile ASELE ZR-COREF-305470-CS-CDS / Component 3. Project and C Renouvellement Contrat du S IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 51,600.00 55,200.00 Signed 2022-07-25 2022-08-19 2022-07-28 2022-08-19 2022-08-02 2022-08-20 2024-08-01 pécialiste en Suivi Evaluation ergency Response du Projet ENCORE - Jules KWI LU ZR-COREF-305487-CS-INDV / Component 3. Project and C Individual Consult Under Implement Recrutement d'un Deuxième IDA / 70200 hange Management, and Em Post Limited 30,000.00 0.00 2022-08-15 2022-08-19 2022-08-20 2022-11-03 2022-09-10 2022-11-18 2022-10-15 2023-10-15 ant Selection ation Comptable du Projet ENCORE ergency Response ZR-COREF-305098-CS-CDS / Renouvellement du Contrat d Component 3. Project and C u Spécialiste en charge de la IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 54,000.00 57,600.00 Signed 2022-07-25 2022-08-19 2022-07-28 2022-08-19 2022-08-02 2022-08-20 2024-08-01 Réforme du système de la co ergency Response mptabilité et gestion de la tr ésorerie - Robert Bamba ZR-COREF-305478-CS-CDS / Component 3. Project and C Renouvellement contrat de l' IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 34,200.00 37,800.00 Signed 2022-07-25 2022-08-19 2022-07-28 2022-08-19 2022-08-02 2022-08-20 2024-08-01 Assistante Principale du Proje ergency Response t ENCORE (APP) - Véronique MANYA ZR-COREF-305112-CS-CDS / Renouvellement du contrat d Component 3. Project and C u Spécialiste en charge du su IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 54,000.00 57,600.00 Signed 2022-07-25 2022-08-19 2022-07-28 2022-08-19 2022-08-02 2022-08-20 2024-08-01 ivi des données statistiques s ergency Response ur la Pauvreté du Projet ENC ORE - Sasse Kembe ZR-COREF-305110-CS-CDS / Renouvellement du Contrat d Component 3. Project and C u Spécialiste en charge de la IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 54,000.00 57,600.00 Signed 2022-07-25 2022-08-19 2022-07-28 2022-08-19 2022-08-02 2022-08-20 2024-08-01 réforme du système des mar ergency Response chés publics et gestion de la dépense - Jean Baptiste VEK O ZR-COREF-305483-CS-CDS / Component 3. Project and C Recrutement Chargée de Pas IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 36,000.00 39,600.00 Signed 2022-07-25 2022-08-19 2022-07-28 2022-08-19 2022-08-02 2022-08-20 2024-08-01 sation des Marchés du Projet ergency Response ENCORE (Gisèle MUAHUKA) Page 9 ZR-COREF-305090-CS-CDS / Component 3. Project and C Renouvellement Contrat du C IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 84,000.00 88,800.00 Signed 2022-07-25 2022-08-19 2022-07-28 2022-08-19 2022-08-02 2022-08-20 2024-08-01 oordonnateur National du Pro ergency Response jet ENCORE - Godefroid MISE NGA MILABYO ZR-COREF-305094-CS-CDS / Component 3. Project and C Renouvellement du Contrat S IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 54,000.00 57,600.00 Signed 2022-07-25 2022-08-19 2022-07-28 2022-08-19 2022-08-02 2022-08-20 2024-08-01 pécialiste en charge de la Dé ergency Response centralisation financière - Moi se ASSANI ZR-COREF-310943-CS-INDV / Selection d'un consultant int Component 1. Strengthening ernational expert en sondage Public Resources Manageme Individual Consult pour 4 mois chargé d'accom IDA / 70200 Post Limited 40,000.00 0.00 Signed 2022-08-31 2022-08-19 2022-09-03 2022-08-24 2022-09-08 2022-11-28 2022-09-15 2023-01-13 nt at Central Government Le ant Selection pagner l'équipe technique na vel tional dans l'organisation de l 'enquête et l'actualisation de la base d'échantilllonnage ZR-COREF-344138-CS-INDV / Recrutement d'un Consultant National pour assurer la form Component 1. Strengthening ation des agents des services Public Resources Manageme Individual Consult Under Implement d'assiette et de recouvremen IDA / 70200 Post Open - National 70,000.00 0.00 2023-03-18 2023-04-10 2023-04-27 2023-05-18 2023-06-22 2023-12-19 nt at Central Government Le ant Selection ation t (DGRAD et administrations vel de mines) sur la maitrise de l 'assiette de la redevance min ière dans les 5 sites miniers de la RDC : Kinshasa, H ZR-COREF-344146-CS-INDV / Recrutement d'un Consultant International pour assurer la Component 1. Strengthening formation à Kinshasa sur la c Public Resources Manageme Individual Consult Open - Internationa Under Implement haîne de valeur de l'industrie IDA / 70200 Post 100,000.00 0.00 2023-03-15 2023-04-10 2023-04-24 2023-05-15 2023-06-19 2023-12-16 nt at Central Government Le ant Selection l ation extractive minière, sur les sp vel écificités comptable et la Fis calité du secteur des mines ( DGI) des vérificateurs proven ant des 5 sites mi ZR-COREF-344206-CS-INDV / Recrutement d'un Consultant Component 1. Strengthening National pour évaluer le nive Public Resources Manageme Individual Consult Under Implement IDA / 70200 Post Open - National 40,000.00 0.00 2023-02-25 2023-04-10 2023-03-18 2023-04-08 2023-05-13 2023-11-09 au d'exécution des réformes nt at Central Government Le ant Selection ation engagées par les entreprises vel Publiques du secteur extracti f. ZR-COREF-344209-CS-INDV / Component 1. Strengthening Recrutement des deux (02) c Public Resources Manageme Individual Consult onsultants individuels pour l IDA / 70200 Post Open - National 60,000.00 0.00 Under Review 2023-03-03 2023-06-01 2023-03-24 2023-04-07 2023-05-12 2023-11-08 nt at Central Government Le ant Selection a mise à jour des guides d’él vel aboration du PEB et du PTR e n lien avec le PPM ZR-COREF-344299-CS-INDV / Component 1. Strengthening Recrutement d'un consultant Public Resources Manageme Individual Consult Pending Impleme IDA / 70200 Post Open - National 30,000.00 0.00 2023-07-03 2023-08-12 2023-08-26 2023-09-30 2024-03-28 individuel pour la production nt at Central Government Le ant Selection ntation du guide de contrôle budgéta vel ire ZR-COREF-344310-CS-INDV / Component 1. Strengthening Recrutement d'un consultant Public Resources Manageme Individual Consult Pending Impleme individuel pour la production IDA / 70200 Post Open - National 30,000.00 0.00 2023-10-02 2023-11-20 2023-12-11 2024-01-15 2024-07-13 nt at Central Government Le ant Selection ntation du projet de plan de renforce vel ment des capacités des contr ôleurs budgétaires ZR-COREF-344314-CS-INDV / Recrutement d'un consultant Component 1. Strengthening international devant mener u Public Resources Manageme Individual Consult Open - Internationa Pending Impleme ne étude de faisabilité sur la IDA / 70200 Post 70,000.00 0.00 2023-03-20 2023-05-08 2023-05-29 2023-07-03 2023-12-30 nt at Central Government Le ant Selection l ntation mise en place du Compte Uni vel que du Trésor et son architec ture favorable au cadre instit utionnel de la RDC ZR-COREF-344327-CS-INDV / Recrutement d'un consultant Component 1. Strengthening international et d'un consulta Public Resources Manageme Individual Consult Pending Impleme nt national pour mener une é IDA / 70200 Post Limited 100,000.00 0.00 2023-03-27 2023-04-01 2023-04-22 2023-05-27 2023-11-23 nt at Central Government Le ant Selection ntation tude relative à la mise en pla vel ce d'une solution informatiqu e nécessaire au fonctionnem ent du CUT ZR-COREF-344350-CS-INDV / Component 1. Strengthening Recrutement d'un consultant Public Resources Manageme Individual Consult Open - Internationa Under Implement International chargé d'optimi IDA / 70200 Post 100,000.00 0.00 2023-03-22 2023-04-24 2023-05-10 2023-05-31 2023-07-05 2024-01-01 nt at Central Government Le ant Selection l ation ser les macro-processus de g vel estion des ressources humai nes et de la paie ZR-COREF-344399-CS-INDV / Recrutement d'un consultant Component 1. Strengthening International pour les Etudes Public Resources Manageme Individual Consult Open - Internationa Pending Impleme IDA / 70200 Post 60,000.00 0.00 2023-03-10 2023-04-28 2023-05-19 2023-06-23 2023-12-20 de faisabilités relatives au ré nt at Central Government Le ant Selection l ntation seau étendu en fibre optique vel et boucle radio local de l’Ad ministration Publique ZR-COREF-344421-CS-INDV / Component 1. Strengthening Recrutement d'un consultant Public Resources Manageme Individual Consult Pending Impleme individuel pour accompagner IDA / 70200 Post Limited 40,000.00 0.00 2023-03-29 2023-04-03 2023-04-24 2023-05-29 2023-07-13 nt at Central Government Le ant Selection ntation le processus de sélection de l vel 'Assistance en maitrise d'ouv rage du SiGeFiP ZR-COREF-344445-CS-INDV / Recrutement d'un consultant Component 1. Strengthening international chargé de l'assi Public Resources Manageme Individual Consult Open - Internationa Under Implement stance technique à l'ARMP po IDA / 70200 Post 70,000.00 0.00 2023-04-03 2023-06-21 2023-05-22 2023-06-12 2023-07-17 2023-09-15 nt at Central Government Le ant Selection l ation ur la révision du cadre juridiq vel ue des marchés publics en te nant compte de la dématéria lisation du processus ZR-COREF-344466-CS-INDV / Recrutement d'un consultant Component 1. Strengthening international chargé de la for Public Resources Manageme Individual Consult Open - Internationa Pending Impleme IDA / 70200 Post 80,000.00 0.00 2023-03-30 2023-04-20 2023-05-11 2023-06-15 2023-08-14 mation des auditeurs de l'AR nt at Central Government Le ant Selection l ntation MP en MP et PPP ainsi que la vel redaction du manuel de proc edures des audits. ZR-COREF-344495-CS-INDV / Component 1. Strengthening Individual Consult Pending Impleme Recrutement d'un webmaste IDA / 70200 Public Resources Manageme Post Limited 50,000.00 0.00 2023-04-01 2023-04-06 2023-04-27 2023-06-01 2023-07-31 ant Selection ntation r pour l'audit du site web du nt at Central Government Le CSP vel Page 10 ZR-COREF-344499-CS-INDV / Component 1. Strengthening Recrutement d'un web maste Public Resources Manageme Individual Consult Pending Impleme r pour développement du sit IDA / 70200 Post Open - National 50,000.00 0.00 2023-03-17 2023-05-05 2023-05-26 2023-06-30 2023-12-27 nt at Central Government Le ant Selection ntation e web du Ministère du Portef vel euille conformément au plan national de numérisation ZR-COREF-344503-CS-INDV / Recrutement d'un Web Mast Component 1. Strengthening er pour le développement d’ Public Resources Manageme Individual Consult Under Implement un portail au niveau des entr IDA / 70200 Post Open - National 50,000.00 0.00 2023-03-14 2023-04-11 2023-04-23 2023-05-14 2023-06-18 2023-12-15 nt at Central Government Le ant Selection ation eprises sur les informations à vel collecter et à échanger avec possibilité d’interaction en lig ne avec le CSP. ZR-COREF-344504-CS-INDV / Recrutement d'un consultant pour la production du projet Component 1. Strengthening de guide pour l'examen du ra Public Resources Manageme Individual Consult Under Implement pport consolidé de la situatio IDA / 70200 Post Open - National 50,000.00 0.00 2023-04-05 2023-05-20 2023-05-15 2023-06-05 2023-07-10 2023-09-08 nt at Central Government Le ant Selection ation n financière des entreprises vel publiques à l'usage des mem bres des services techniques des commission ECOFIN de l' Assemblée National et du Sé n ZR-COREF-344514-CS-INDV / Recrutement d'un consultant Component 1. Strengthening pour l’élaboration d’un manu Public Resources Manageme Individual Consult Under Implement IDA / 70200 Post Open - National 50,000.00 0.00 2023-04-10 2023-05-20 2023-05-29 2023-06-19 2023-07-24 2023-10-22 el des procédures en matière nt at Central Government Le ant Selection ation de contrôle et audit des entr vel eprises publiques et établiss ements publics ZR-COREF-344517-CS-INDV / Component 1. Strengthening Recrutement d'un consultant Public Resources Manageme Individual Consult Under Implement IDA / 70200 Post Open - National 50,000.00 0.00 2023-04-17 2023-05-20 2023-06-05 2023-06-26 2023-07-31 2024-01-27 pour la production du projet nt at Central Government Le ant Selection ation de la stratégie du Portefeuille vel ZR-COREF-344723-CS-INDV / Component 1. Strengthening Recrutement d'un consultant Public Resources Manageme Individual Consult Pending Impleme IDA / 70200 Post Open - National 50,000.00 0.00 2023-07-03 2023-08-21 2023-09-11 2023-10-16 2023-12-15 pour la production des contra nt at Central Government Le ant Selection ntation ts de performance type par s vel ecteur d'activités ZR-COREF-344749-CS-INDV / Component 1. Strengthening Recrutement d'un consultant Public Resources Manageme Individual Consult Pending Impleme national pour la production d IDA / 70200 Post Open - National 50,000.00 0.00 2023-04-01 2023-05-20 2023-06-10 2023-07-15 2023-09-13 nt at Central Government Le ant Selection ntation es contrats de concession ty vel pe des biens du domaine pub lic de l'Etat ZR-COREF-344774-CS-INDV / Recrutement des consultants nationaux pour mener l'analy Component 2. Supporting se des états de suivi budgéta Resource Management at th Individual Consult Pending Impleme ires (ESB) trimestriels et sem IDA / 70200 Post Open - National 80,000.00 0.00 2023-05-08 2023-06-26 2023-07-17 2023-08-21 2024-02-17 e Provincial Government Lev ant Selection ntation estriels des secteurs pro pau el vres (Education, Santé, Mine s, Agriculture et développem ent rural, Energie, Sécurité, I nfrastructures) et le ge ZR-COREF-344786-CS-INDV / Recrutement de consultants Component 1. Strengthening nationaux pour la formation Public Resources Manageme Individual Consult Under Implement IDA / 70200 Post Open - National 70,000.00 0.00 2023-03-30 2023-04-10 2023-05-18 2023-06-08 2023-07-13 2024-01-09 des services concernés à la p nt at Central Government Le ant Selection ation roduction et à la publication vel des documents budgétaires-c lés nationaux ZR-COREF-344812-CS-INDV / Recrutement du consultant i ndividuel chargé réaliser les Component 1. Strengthening études, la production du DAO Public Resources Manageme Individual Consult Pending Impleme IDA / 70200 Post Open - National 100,000.00 0.00 2023-03-27 2023-05-15 2023-06-05 2023-07-10 2024-01-06 ainsi que le contrôle et survei nt at Central Government Le ant Selection ntation llance des travaux de réhabili vel tation du bâtiment devant ab riter la chambre des comptes déconcentrées de Kananga ZR-COREF-344837-CS-INDV / Recrutement d'un consultant Component 2. Supporting international pour la réalisati Resource Management at th Individual Consult Open - Internationa Under Implement IDA / 70200 Post 120,000.00 0.00 2023-03-20 2023-04-10 2023-05-08 2023-05-29 2023-07-03 2023-12-30 on de l'évaluation de la perf e Provincial Government Lev ant Selection l ation ormance des administrations el fiscales provinciales suivant l 'approche TADAT. ZR-COREF-344901-CS-INDV / Recrutement d'un consultant Component 2. Supporting ingénieur architecte pour fair Resource Management at th Individual Consult Pending Impleme e l'état des lieux et le suivi d IDA / 70200 Post Open - National 150,000.00 0.00 2023-04-08 2023-05-27 2023-06-17 2023-07-22 2024-01-18 e Provincial Government Lev ant Selection ntation es bâtiments à réhabiliter da el ns les 4 provinces (du Kasaï Oriental, du Kasaï, du Kasaï C entral et de Lomami) ZR-COREF-344912-CS-CDS / Déploiement multi-sites du lo Component 3. Project and C Direct - Internation Pending Impleme giciel de gestion financière d IDA / 70200 hange Management, and Em Post Direct Selection 40,000.00 0.00 2023-04-15 2023-04-25 2023-06-29 2023-12-26 al ntation u projet ENCORE (auprès de ergency Response TOMATE) et mise à niveau ZR-COREF-345018-CS-INDV / Component 3. Project and C Individual Consult Under Implement Recrutement d'un auditeur in IDA / 70200 hange Management, and Em Post Open - National 60,000.00 0.00 2023-03-10 2023-03-16 2023-04-19 2023-05-10 2023-06-14 2024-06-13 ant Selection ation terne ergency Response ZR-COREF-345068-CS-INDV / Recrutement d'un consultant pour traduire un document s Component 3. Project and C Individual Consult Pending Impleme ynthèse sur le projet en lang IDA / 70200 hange Management, and Em Post Open - National 20,000.00 0.00 2023-04-14 2023-06-02 2023-06-23 2023-07-28 2024-01-24 ant Selection ntation ues locales (résumé du proje ergency Response t : son envergure, ses risques et effets environnementales et sociale) ZR-COREF-345081-CS-INDV / Recrutement d'un consultant Component 3. Project and C individuel pour l'élaboration Individual Consult Under Implement IDA / 70200 hange Management, and Em Post Open - National 30,000.00 0.00 2023-03-21 2023-04-24 2023-05-09 2023-05-30 2023-07-04 2023-12-31 de la stratégie de gestion du ant Selection ation ergency Response changement et la revue quali té de la stratégie de commun ication ZR-COREF-345087-CS-INDV / Component 3. Project and C Recrutement des consultants Individual Consult Pending Impleme IDA / 70200 hange Management, and Em Post Open - National 50,000.00 0.00 2023-04-07 2023-05-26 2023-06-16 2023-07-21 2024-01-17 ponctuels pour les évaluation ant Selection ntation ergency Response s des offres et propositions Page 11 ZR-COREF-345088-CS-INDV / Component 3. Project and C Individual Consult Under Implement Recrutement de deux compt IDA / 70200 hange Management, and Em Post Open - National 79,200.00 0.00 2023-03-28 2023-03-17 2023-05-16 2023-06-06 2023-07-11 2024-07-10 ant Selection ation ables pour le projet ENCORE ergency Response ZR-COREF-345092-CS-INDV / Component 1. Strengthening Recrutement d'un consultant Public Resources Manageme Individual Consult Pending Impleme IDA / 70200 Post Open - National 100,000.00 0.00 2023-04-18 2023-06-06 2023-06-27 2023-08-01 2024-01-28 pour une assistance techniqu nt at Central Government Le ant Selection ntation e dans la fiscalité minière vel ZR-COREF-344362-CS-INDV / Component 1. Strengthening Recrutement d'un consultant Public Resources Manageme Individual Consult Pending Impleme national pour l'élaboration du IDA / 70200 Post Open - National 100,000.00 0.00 2023-03-17 2023-05-05 2023-05-26 2023-06-30 2023-12-27 nt at Central Government Le ant Selection ntation manuel de procédures de ge vel stion des ressources humain es et la Paie ZR-COREF-344818-CS-CDS / Recrutement d'un Cabinet int Component 1. Strengthening ernational Expertise France, Public Resources Manageme Direct - Internation Under Implement IDA / 70200 Post Direct Selection 400,000.00 0.00 2023-03-24 2023-04-10 2023-04-03 2023-06-07 2023-12-04 chargé d’appuyer la Cour des nt at Central Government Le al ation comptes dans la mise en œu vel vre de son plan stratégique ZR-COREF-344827-CS-CDS / Component 1. Strengthening Appui à l'Organisation de l’en IDA / 70200 Public Resources Manageme Prior Direct Selection Direct - National 9,607,330.00 0.00 Signed 2023-03-15 2023-04-28 2023-03-25 2023-05-18 2023-05-29 2023-11-25 quête ECVM proprement dite nt at Central Government Le avec le PNUD vel ZR-COREF-344384-CS-INDV / Recrutement consultant indiv iduel pour élaborer le cahier Component 1. Strengthening des charges et le DAO pour l' Public Resources Manageme Individual Consult Pending Impleme installation, la sécurisation et IDA / 70200 Post Limited 30,000.00 0.00 2023-03-13 2023-03-18 2023-04-08 2023-05-13 2023-11-09 nt at Central Government Le ant Selection ntation la mise en marche du datace vel nter de secours de la Directio n de la Gestion des bases de s données des RH à la fonctio n publique (DBDR). ZR-COREF-344845-CS-INDV / Component 2. Supporting Recrutement d'un cabinet po Resource Management at th Individual Consult Open - Internationa Pending Impleme ur mener une étude sur le po IDA / 70200 Prior 600,000.00 0.00 2023-03-31 2023-05-19 2023-06-09 2023-07-14 2024-01-10 e Provincial Government Lev ant Selection l ntation tentiel fiscal en faveur de qu el atre provinces ENCORE ZR-COREF-344484-CS-INDV / Component 1. Strengthening Recrutement du consultant i Public Resources Manageme Pending Impleme ndividuel Expert Pierre Tshiy IDA / 70200 Post Direct Selection Direct - National 50,000.00 0.00 2023-03-24 2023-04-03 2023-06-07 2023-12-04 nt at Central Government Le ntation ombo pour l'assistance techn vel ique dans la phase de produc tion du SIGMAP ZR-COREF-355174-CS-INDV / Component 3. Project and C Recrutement d'un(e) assistan Individual Consult Under Implement IDA / 70200 hange Management, and Em Post Limited 30,000.00 0.00 2023-05-01 2023-04-24 2023-05-06 2023-05-20 2023-06-10 2024-06-09 t(e) en décentralisation finan ant Selection ation ergency Response cière et budget participatif ZR-COREF-355179-CS-INDV / Component 3. Project and C Recrutement d'un spécialiste Individual Consult Pending Impleme IDA / 70200 hange Management, and Em Post Limited 56,700.00 0.00 2023-05-01 2023-05-06 2023-05-27 2023-07-01 2023-12-28 en charge de la reforme de l ant Selection ntation ergency Response a fonction publique pour le Pr ojet ENCORE ZR-COREF-355180-CS-INDV / Component 1. Strengthening Recrutement d'un consultan Public Resources Manageme Individual Consult Under Implement IDA / 70200 Post Limited 56,700.00 0.00 2023-04-15 2023-05-23 2023-04-20 2023-05-11 2023-06-15 2023-12-12 t national Expert en Mine pou nt at Central Government Le ant Selection ation r le projet ENCORE vel ZR-COREF-355425-CS-INDV / Component 3. Project and C Recrutement d'un 2ème spéc Individual Consult Under Implement IDA / 70200 hange Management, and Em Post Limited 55,200.00 0.00 2023-04-15 2023-04-11 2023-04-20 2023-05-11 2023-06-15 2023-12-12 ialiste en Passation des Marc ant Selection ation ergency Response hés du Projet ENCORE ZR-COREF-345715-CS-INDV / Component 1. Strengthening Individual Consult Pending Impleme Assistance technique à l'ARM IDA / 70200 Public Resources Manageme Post Open - National 200,000.00 0.00 2023-05-10 2023-06-28 2023-07-19 2023-08-23 2024-02-19 ant Selection ntation P pour la mise en œuvre des nt at Central Government Le réformes vel ZR-COREF-345701-CS-INDV / Component 3. Project and C Individual Consult Recrutement d'un chargé de IDA / 70200 hange Management, and Em Post Open - National 40,000.00 0.00 Canceled 2023-04-29 2023-03-17 2023-05-20 2023-06-10 2023-07-15 2024-07-14 ant Selection Passation des Marchés ergency Response ZR-COREF-356313-CS-INDV / Component 3. Project and C Individual Consult Pending Impleme Recrutement d'un expert fisc IDA / 70200 hange Management, and Em Post Open - National 56,700.00 0.00 2023-04-12 2023-05-31 2023-06-21 2023-07-26 2024-01-22 ant Selection ntation aliste pour le projet ENCORE ergency Response ZR-COREF-360909-CS-CDS / Component 3. Project and C Recrutement d'un consultant Direct - Internation Under Implement IDA / 70200 hange Management, and Em Post Direct Selection 350,000.00 0.00 2023-05-11 2023-05-12 2023-05-21 2023-07-25 2024-01-21 firme chargé de l'audit des d al ation ergency Response épenses éligibles au program me (PDE) ZR-COREF-363418-CS-CDS / Component 3. Project and C Recrutement d'un consultant Direct - Internation Pending Impleme IDA / 70200 hange Management, and Em Post Direct Selection 350,000.00 0.00 2023-05-27 2023-06-06 2023-08-10 2024-02-06 firme chargé de l'audit des d al ntation ergency Response épenses éligibles au program me (PDE) ZR-COREF-363431-CS-INDV / Recrutement d'un consultant Component 1. Strengthening Senior International pour l'él Public Resources Manageme Individual Consult Open - Internationa Under Implement aboration de la stratégie de r IDA / 70200 Post 100,000.00 0.00 2023-05-29 2023-06-07 2023-07-17 2023-08-07 2023-09-11 2024-03-09 nt at Central Government Le ant Selection l ation enforcement des capacités, d vel e formation et de professionn alisation des acteurs nationa ux de la commande Publique. Page 12 PLAN DE PASSATION DE MARCHÉS Information sur le Projet : Emprunteur/Bénéficiaire République Togolaise Ministère Responsable Nom du Projet Identification P172769 Agence d’exécution du Projet : [A insérer] Date du plan de passation des marchés : [A indiquer] Période couverte par ce plan de passation des marchés : [A indiquer] Date d’approbation par la Banque du plan de passation de marchés : [A indiquer] Date de publication de l’Avis Général de Passation des Marchés : [A indiquer] Evaluation de risque par P-RAMS (Procurement Risk Assessment and Management System) : Elevé Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Novembre 2020) (“Règlement de Passation des Marchés”), le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marchés se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus dans STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans la loi No. 2009-013 du 30 juin 2009 relative aux Marchés Publics et Délégation de Service Public, le Décret Nº 2009-277/PR du 11 novembre 2009 portant Code des Marchés Publics et Délégation de Service Public, et les textes d’application y afférents, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : - Le dossier d’appel d’offres/à propositions oblige le Soumissionnaire/les proposants présentant une Offre/Proposition à déposer un agrément signé, qui sera joint à tout contrat éventuel, pour confirmer qu’il applique et respecte les Directives de la Banque pour la lutte contre la corruption, y compris sans limitation, le droit de la Banque de sanctionner et les droits de la Banque pour l’inspection e l’audit ; - Le droit de la Banque d’examiner le dossier et les activités de passation des marchés. Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas pour les contrats indiqués dans les tableaux du Plan de passation des marchés Travaux ne s’applique pas pour les contrats indiqués dans les tableaux du Plan de passation des marchés L’Assistance directe à la mise en œuvre (sigle HEIS en anglais) tel que précisée aux paragraphes 3.10 et 3.11 du Règlement de Passation des marchés ne s’applique pas. Autres informations pertinentes sur la passation des marchés : Néant I. TRAVAUX, FOURNITURES ET SERVICES AUTRES QUE LES SERVICES DE CONSULTANTS 1. Dispositions relatives aux seuils de revue préalable : Seuils requis pour les décisions de marchés soumis à la revue préalable de la Banque, tel que prévu dans les paragraphes 3.5 à 3.8 de la Section III, et de l’Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI), en date de Juillet 2016, révisé en Novembre 2017. Catégories de marchés Montants Observations estimatifs des contrats en millions de dollars américains Travaux (incluant clé à main, Fourniture et Installation, et les >= 5 Partenariat Public - Privé -PPP) Biens, Système d’Information et de Services autres que les >= 1,5 Services intellectuels Contrats à Travaux passer par (incluant clé à >= 5 entente main, directe Fourniture et Les justifications de Installation, et l’entente directe les Partenariat devront être jointes et Public - Privé - approuvées avec PPM PPP) Biens, Système d’Information et de Services >= 1,5 autres que les Services intellectuels 2. Seuils pour les méthodes de passation des marchés : Les seuils de passation des marchés se présentent comme suit au vu des conditions du marché : FOURNITURES ET SERVICES AUTRE QUE LES SERVICES DE CONSULTANTS TRAVAUX (US$ équivalent) (US$ équivalent) AOI AON DC AOI AON DC < < 100.000 ≥5.000.000 <5.000.000 200.00 ≥500.000 <500.000 0 3. Dispositions spéciales sur les marchés : Concernant les acquisitions de véhicules et de carburant, en fonction des circonstances et des besoins spécifiques du pays, le seuil pour la consultation de fournisseurs pourrait être porté à la contre-valeur d’USD 500,000 (en prenant soin de consulter tous les principaux concessionnaires de marque ou distributeurs de produits pétroliers). Liste de Marchés de Travaux, Fournitures, et Services autres que Consultant Date Type Méthode/ Montan de Comme d'Exa Modalité Appro t lance ntaire Réf. DESCRIP men de che de Estimat ment /Fin de No. TION par la passatio march if en de la prestat Banqu n des és US$ procé ions e marchés dure II. SÉLECTION DES CONSULTANTS 1. Dispositions relatives aux seuils de revue préalable des marchés : Décisions de sélection sujette à la revue préalable de la Banque comme indiqué dans Seuils requis pour les décisions de marchés soumis à la revue préalable de la Banque, tel que prévu dans les paragraphes 3.5 à 3.8 de la Section III, et de l’Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI), en date de Novembre 2020. Méthode de Seuils de revue a priori Observations sélection/Catégories de Montants estimatifs des marchés contrats en millions de dollars américains Méthode compétitive/Firmes de >= 0.5 consultants Entente directe/firmes de Les justifications pour consultants >= 0.5 l’entente directe devront être jointes et approuvées Entente avec le PPM directe/Consultants >= 0.2 individuel Méthode Compétitive >= 0.2 (Comparaison de CVs)/ Consultants individuels 2. Liste restreinte composée entièrement de firmes nationales: La liste restreinte de consultants pour les prestations d’études d’ingénierie, de contrôle et de surveillance estimées à moins de 300,000 US$ par contrat, et pour tout autre type de prestations, estimées à moins de 100 000 US$ par contrat, peut comporter entièrement de consultants nationaux en conformité avec les dispositions des Règlements de Passation des marchés., et l’Emprunteur ne procède pas à une publication dans UNDB 3. Autre arrangement spécial de Sélection de consultants : Le seuil pour l’utilisation de la méthode de sélection de consultant fondée sur les qualifications des consultants est déterminé au cas par cas en tenant compte de la nature et de la complexité de la mission ; cependant, ce seuil ne devrait pas dépasser la contre-valeur de USD 300,000 sauf dans des cas exceptionnels telles des situations d’urgence en conformité au Règlement de Passation des marchés II- Liste de Marchés de Services de Consultants Date Méthod Comm Montan Type de Ré e de entair t d'Exam Approch lancem f. DESCRIPTION passati e/Fin Estimat en par e de ent de No DES MISSIONS on des des if en la Marché la . marché presta US$ Banque procéd s tions ure Lexique des Sigles et Abréviations ARMP Autorité de Régulation des Marchés Publics AOI Appel d’Offres International AON Appel d’Offres National A Revue a posteriori posteriori A Priori Revue a priori CI Consultant Individuel DC Demande de Cotations DNCMP Direction Nationale de Contrôle des Marchés Publics ED Sélection Directe ou Entente Directe PPM Plan de Passation des Marchés SFQ Sélection Fondée sur la Qualité SFQC Sélection Fondée sur la Qualité et le Coût SMC Sélection au Moindre Coût SQC Sélection fondée sur les Qualifications des Consultants PROCUREMENT Western and Central Africa : West Africa Food System Resilience Program (FSRP) PLAN General Information Country: Western and Central Africa 2022-10-10 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172769 GPN Date: Project Name: West Africa Food System Resilience Program (FSRP) Loan / Credit No: IDA / D9210, IDA / 69950, IDA / 69960, TF / B7227 Unit Coordination of West Africa System Resilience Program - BF Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned BF-UCP/PRSA-BF-339062-CW Request for Bids - Sustainability and adaptive c -RFB / Travaux de constructio Single Stage - One E Small Works SPD Pending Imp 2024-01-2 IDA / 69950 apacity of the food system’s Post Request for Bids Open - National 1,065,371.00 0.00 2023-08-15 2023-08-20 2023-10-01 2023-10-31 2023-11-28 n des infrastructures profit d nvelope (1 envelope proce lementation 7 productive base es structures de l'INERA ss) BF-UCP/PRSA-BF-339102-CW Request for Bids - -RFB / Travaux de réhabilitati Sustainability and adaptive c Single Stage - One E Small Works SPD Pending Imp 2023-09-0 ons des infrastructures au pr IDA / 69950 apacity of the food system’s Post Request for Bids Open - National 395,318.00 0.00 2023-03-15 2023-03-20 2023-05-01 2023-05-31 2023-07-05 nvelope (1 envelope proce lementation 3 ofit de l'INERA de l'IRSAT, du productive base ss) CNS-FL et de la SONAGESS BF-UCP/PRSA-BF-339107-CW Request for Bids - Sustainability and adaptive c -RFB / Réalisation de jardins Single Stage - One E Small Works SPD Pending Imp 2023-10-2 IDA / 69950 apacity of the food system’s Post Request for Bids Open - National 1,378,091.00 0.00 2023-05-16 2023-05-21 2023-07-02 2023-08-01 2023-08-29 maraichers équipés de forag nvelope (1 envelope proce lementation 8 productive base es solaires au profit des fem ss) mes National Procure BF-UCP/PRSA-BF-339111-CW Sustainability and adaptive c ment Document - Single Stage - One E Pending Imp 2023-11-2 -RFB / Réalisation de modèle IDA / 69950 apacity of the food system’s Post Request for Bids Open - National 1 Envelope proce 662,545.00 0.00 2023-06-15 2023-06-20 2023-08-01 2023-08-31 2023-09-28 nvelope lementation 7 s d'exploitation ( 15 modèles productive base ss (Non Bank-SPD ) ) BF-UCP/PRSA-BF-339113-CW Request for Bids - Sustainability and adaptive c -RFB / Réhabilitation des loca Single Stage - One E Small Works SPD Pending Imp 2024-01-0 IDA / 69950 apacity of the food system’s Post Request for Bids Open - National 247,350.00 0.00 2023-06-15 2023-06-20 2023-07-20 2023-08-03 2023-09-07 ux Abritant les UGR de l'Est; nvelope (1 envelope proce lementation 5 productive base Centre Est; Centre Sud et Ce ss) ntre ouest BF-UCP/PRSA-BF-339064-CW Sustainability and adaptive c Request for Quota -RFQ / Travaux de constructi Request for Quota Single Stage - One E Pending Imp 2023-10-0 IDA / 69950 apacity of the food system’s Post Limited tions (Non Bank-S 27,000.00 0.00 2023-07-16 2023-09-03 on de 02 banques de gènes s tions nvelope lementation 3 productive base PD) olaires à Farako-Bâ et à Kam boinsé BF-UCP/PRSA-BF-339100-CW Sustainability and adaptive c Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-11-0 -RFQ / Travaux de réalisation IDA / 69950 apacity of the food system’s Post Limited tions (Non Bank-S 53,000.00 0.00 2023-08-20 2023-10-08 tions nvelope lementation 7 d'une chambre froide solaire productive base PD) à Farako-bâ BF-UCP/PRSA-BF-339117-CW Sustainability and adaptive c Request for Quota -RFQ / Réalisation des travau Request for Quota Single Stage - One E Pending Imp 2023-08-0 IDA / 69950 apacity of the food system’s Post Limited tions (Non Bank-S 97,174.00 0.00 2023-05-21 2023-07-09 x de récupération mécanisée tions nvelope lementation 8 productive base PD) des terres dégradées BF-UCP/PRSA-BF-360925-CW Sustainability and adaptive c Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-10-2 -RFQ / Réalisation de trois (0 IDA / 69950 apacity of the food system’s Post Limited tions (Non Bank-S 81,000.00 0.00 2023-05-27 2023-07-22 tions nvelope lementation 0 3) forages équipés de châtea productive base PD) u d'eau BF-UCP/PRSA-BF-339106-CW Request for Quota -RFB / Aménagement de parc Sustainability and adaptive c Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-12-3 elles expérimentales avec di IDA / 69950 apacity of the food system’s Post Limited 119,000.00 0.00 2023-09-20 2023-11-15 tions nvelope s (Emergency) SP lementation 0 spositif de micro irrigation et productive base D -Competitive d'aménagement d'une pépini ère fruitière BF-UCP/PRSA-BF-360932-CW Request for Quota -DIR / Réalisation des travaux Sustainability and adaptive c tions - Small Work Under Imple 2023-10-2 mécaniques de récupération IDA / 69950 apacity of the food system’s Post Direct Selection Direct - National s (Emergency) SP 270,000.00 0.00 2023-06-05 2023-06-16 2023-06-10 2023-07-22 mentation 0 de terre dégradées, d'ensem productive base D -Non Competiti encement et plantation ve GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-UCP/PRSA-BF-320059-GO Single Stage - One E Pending Impl -RFB / Acquisition de matériel IDA / D9210 Project Management Post Request for Bids Open - National 127,000.00 0.00 2022-11-06 2022-11-11 2022-12-11 2022-12-16 2023-01-06 2023-02-05 nvelope ementation s informatiques et de tablett es BF-UCP/PRSA-BF-320069-GO Single Stage - One E Pending Impl -RFB / Acquisition de 02 grou IDA / D9210 Project Management Post Request for Bids Open - National 88,200.00 0.00 2022-11-10 2022-11-15 2022-12-15 2022-12-20 2023-01-10 2023-03-11 nvelope ementation pes électrogènes BF-UCP/PRSA-BF-320071-GO Digital advisory services for -RFB / Acquisition de pluviom Single Stage - One E Pending Impl IDA / D9210 agriculture and food crisis pr Post Request for Bids Open - National 120,000.00 0.00 2022-11-30 2022-12-05 2023-01-04 2023-01-09 2023-01-30 2023-03-31 ètres automatiques, d’anten nvelope ementation evention and management nes et d’un calculateur BF-UCP/PRSA-BF-320073-GO -DIR / Acquisition de 02 Véhic Direct - Internation Pending Impl IDA / D9210 Project Management Post Direct Selection 1,147,000.00 0.00 2022-11-10 2022-11-15 2022-12-20 2023-04-19 ules -Station wagon 4X4, de al ementation 22 Pick up double cabine et d e 20 motos BF-UCP/PRSA-BF-320116-GO Request for Quota Single Stage - One E Pending Impl IDA / D9210 Project Management Post Limited 35,280.00 0.00 2022-11-03 2022-11-25 2022-12-09 -RFQ / Assurance maladie du tions nvelope ementation personnel BF-UCP/PRSA-BF-320561-GO Request for Quota Single Stage - One E Pending Impl -RFQ / Acquisition du logiciel IDA / D9210 Project Management Post Limited 70,000.00 0.00 2022-11-03 2022-12-02 2023-01-16 tions nvelope ementation de gestion financière et com ptable BF-UCP/PRSA-BF-320563-GO Request for Quota Single Stage - One E Pending Impl -RFQ / Acquisition d’un logici IDA / D9210 Project Management Post Limited 52,000.00 0.00 2022-11-03 2022-12-02 2023-01-16 tions nvelope ementation el de suivi évaluation Page 1 BF-UCP/PRSA-BF-339122-GO -RFB / Acquisition de mobilier Single Stage - One E Pending Impl IDA / 69950 Project Management Post Request for Bids Open - National 282,685.00 0.00 2023-03-15 2023-03-20 2023-05-01 2023-05-31 2023-07-05 2023-09-03 s au profit du CNS-FL ,INERA nvelope ementation (Farako- ba),ANAM et de la D GESS BF-UCP/PRSA-BF-339262-GO -RFQ / Acquisition des équipe Request for Quota Single Stage - One E Pending Impl ments agro-méthéorogique ( IDA / 69950 Project Management Post Limited 319,000.00 0.00 2023-03-25 2023-05-20 2023-06-19 tions nvelope ementation capteurs en fin de durée de v ie, batteries et paramètres d u sol, insolation) BF-UCP/PRSA-BF-339291-GO -DIR / Convention avec l'UN OPS pour l'acquisition de mat ériels roulant (deux camions Direct - Internation Under Revie de 40 tonnes; 2 Véhicules -St IDA / 69950 Project Management Prior Direct Selection 4,697,740.00 0.00 2023-03-30 2023-04-11 2023-04-04 2023-05-09 2023-12-05 al w ation wagon 4X4; de 32 Véhi cules Pick-up 4X4; 2 Minibus; 4 Berlines; 20 Motos; matéri els informatiques;smartphon e pour soutenir la collecte BF-UCP/PRSA-BF-339349-GO -RFQ / Diffusion des supports Request for Quota Single Stage - One E Pending Impl IDA / 69950 Project Management Post Limited 17,700.00 0.00 2023-07-05 2023-08-30 2023-09-29 audio visuels sur la gestion d tions nvelope ementation urable des terres BF-UCP/PRSA-BF-341703-GO Request for Quota Single Stage - One E Pending Impl -RFQ / Produits d'entretien et IDA / 69960 Project Management Post Limited 9,000.00 0.00 2023-04-05 2023-05-31 2023-11-27 tions nvelope ementation de nettoyage des locaux BF-UCP/PRSA-BF-339266-GO -RFQ / Acquisition et installati Digital advisory services for Single Stage - One E Pending Impl on 02 centrales d’énergie sol IDA / 69950 agriculture and food crisis pr Post Request for Bids Open - National 135,000.00 0.00 2023-04-20 2023-04-25 2023-06-06 2023-07-06 2023-08-10 2023-12-08 nvelope ementation aire photovoltaïque sur les si evention and management tes de recherche du CNS-FL ( Farako-Ba) BF-UCP/PRSA-BF-320057-GO Request for Quota Single Stage - One E Pending Impl -RFQ / Acquisition de fournitu IDA / D9210 Project Management Post Limited 26,500.00 0.00 2022-11-23 2022-12-15 2023-01-14 tions nvelope ementation res de bureau BF-UCP/PRSA-BF-341698-GO -RFQ / Acquisition d'équipem Request for Quota Single Stage - One E Pending Impl IDA / 69960 Project Management Post Limited 40,000.00 0.00 2023-04-04 2023-05-30 2023-11-26 ents minimum en informatiq tions nvelope ementation ue pour le personnel de l'UG P BF-UCP/PRSA-BF-339123-GO Request for Quota Single Stage - One E Pending Impl -RFQ / Acquisition des kits de IDA / 69950 Project Management Post Limited 12,370.00 0.00 2023-03-18 2023-05-13 2023-06-12 tions nvelope ementation détection rapide d'aflatoxine BF-UCP/PRSA-BF-339068-GO -RFQ / Acquisition d'équipem Sustainability and adaptive c Single Stage - One E Pending Impl ent au profit de la SONAGESS IDA / 69950 apacity of the food system’s Post Request for Bids Open - National 159,894.00 0.00 2023-04-13 2023-04-18 2023-05-30 2023-06-29 2023-08-03 2023-10-02 nvelope ementation (échelles mobiles sacs PICS s productive base ilos cuves métalliques et des diables) BF-UCP/PRSA-BF-344463-GO Sustainability and adaptive c Open - Internationa Single Stage - One E Pending Impl -RFB / Acquisition de tracteur IDA / 69950 apacity of the food system’s Post Request for Bids 1,700,000.00 0.00 2023-04-14 2023-04-19 2023-05-31 2023-06-30 2023-08-04 2024-01-01 l nvelope ementation s pour les producteurs productive base BF-UCP/PRSA-BF-344471-GO Sustainability and adaptive c Open - Internationa Single Stage - One E Pending Impl -RFB / Acquisition de motocul IDA / 69950 apacity of the food system’s Post Request for Bids 1,500,000.00 0.00 2023-04-14 2023-04-19 2023-05-31 2023-06-30 2023-08-04 2024-01-01 l nvelope ementation teurs pour les producteurs ( s productive base ubvention) BF-UCP/PRSA-BF-344473-GO Sustainability and adaptive c -RFB / Acquisition de matériel Open - Internationa Single Stage - One E Pending Impl IDA / 69950 apacity of the food system’s Post Request for Bids 445,000.00 0.00 2023-04-14 2023-04-19 2023-05-31 2023-06-30 2023-08-04 2024-01-01 post récolte pour les product l nvelope ementation productive base eurs (subvention) BF-UCP/PRSA-BF-344479-GO Sustainability and adaptive c Request for Quota Single Stage - One E Pending Impl -RFQ / Acquisition des égrene IDA / 69950 apacity of the food system’s Post Limited 46,000.00 0.00 2023-04-25 2023-06-20 2023-11-17 tions nvelope ementation uses et de kits des maintena productive base nciers BF-UCP/PRSA-BF-344482-GO Request for Quota Single Stage - One E Pending Impl -RFQ / Acquisition d'équipem IDA / 69960 Project Management Post Limited 12,000.00 0.00 2023-07-05 2023-08-30 2023-10-29 tions nvelope ementation ents de protection et de sécu rité BF-UCP/PRSA-BF-344486-GO Request for Quota Single Stage - One E Pending Impl -RFQ / Services de gardienna IDA / 69960 Project Management Post Limited 12,000.00 0.00 2023-04-22 2023-06-17 2023-08-16 tions nvelope ementation ge des locaux de PRSA-BF BF-UCP/PRSA-BF-320054-GO Request for Quota Single Stage - One E Pending Impl -RFQ / Réalisation des outils TF / B7227 Project Management Post Limited 17,640.00 0.00 2023-05-28 2023-06-19 2023-07-19 tions nvelope ementation de communication BF-UCP/PRSA-BF-320070-GO Request for Quota Single Stage - One E Pending Impl -RFQ / Acquisition de mobilier TF / B7227 Project Management Post Limited 85,100.00 0.00 2023-05-28 2023-06-19 2023-07-19 tions nvelope ementation s de bureau BF-UCP/PRSA-BF-361041-GO -RFB / Acquisition de kits CES Sustainability and adaptive c Single Stage - One E Pending Impl /DRS pour les producteurs po IDA / 69950 apacity of the food system’s Post Request for Bids Open - National 820,000.00 0.00 2023-05-31 2023-06-05 2023-07-05 2023-08-04 2023-09-01 2023-11-30 nvelope ementation ur les travaux de récupératio productive base ns de terres dégradées BF-UCP/PRSA-BF-361044-GO -RFB / Acquisition d'équipem Sustainability and adaptive c Single Stage - One E Pending Impl ents: tricycle, motopompe, ci IDA / 69950 apacity of the food system’s Post Request for Bids Open - National 215,130.00 0.00 2023-06-12 2023-06-17 2023-07-17 2023-08-16 2023-09-13 2023-12-12 nvelope ementation terne pour les producteurs e productive base t pour les brigades mobiles BF-UCP/PRSA-BF-339128-GO -RFB / Acquisition de kits CES Sustainability and adaptive c Open - Internationa Single Stage - One E Pending Impl /DRS et des équipements (tri IDA / 69950 apacity of the food system’s Post Request for Bids 1,003,720.00 0.00 2023-06-15 2023-06-20 2023-08-01 2023-08-31 2023-10-05 2023-12-04 l nvelope ementation cycle, motopompe, citerne) productive base pour les producteurs et pour les brigades mobiles Page 2 BF-UCP/PRSA-BF-361082-GO -DIR / Acquisition des équipe ments de labo complémentai res pour les laboratoires ann exes (INERA IRSAT) Direct - Internation Pending Impl Acquisition matériels informa IDA / 69950 Project Management Prior Direct Selection 2,300,000.00 0.00 2023-06-30 2023-07-05 2023-08-23 2023-10-22 al ementation tiques; Acquisition de smartphone p our soutenir la collecte; Acquisition des équipements pour le centre de formation d u CNS-FL (p BF-UCP/PRSA-BF-365459-GO Sustainability and adaptive c -RFQ / Travaux de réalisation Request for Quota Single Stage - One E Pending Impl IDA / 69950 apacity of the food system’s Post Limited 117,000.00 0.00 2023-06-20 2023-08-01 2023-09-15 des labours sur 1000 ha de b tions nvelope ementation productive base as fonds pour améliorer la pr oduction agricole NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-UCP/PRSA-BF-315982-CS- Consultant Qualifi Under Implement CQS / Réalisation de la situati IDA / D9210 Project Management Post Open - National 60,000.00 0.00 2022-10-20 2022-11-03 2022-10-30 2022-11-22 2022-11-29 2022-12-09 2023-02-07 cation Selection ation on de référence du Program me BF-UCP/PRSA-BF-319898-CS- CQS / Etudes techniques de c onstruction/Réhabilitation de Sustainability and adaptive c bureaux à l'INERA, la constru Consultant Qualifi Under Implement IDA / D9210 apacity of the food system’s Post Open - National 45,425.00 0.00 2022-11-15 2023-01-10 2022-11-25 2022-12-18 2022-12-25 2023-01-04 2023-03-05 ction d'un centre d'hébergem cation Selection ation productive base ent, réhabilitations et d'exten sion de la maison des hôtes de l'INERA réhabilitations de l aboratoires et ateliers BF-UCP/PRSA-BF-319903-CS- Sustainability and adaptive c CQS / Etudes techniques des Consultant Qualifi Under Implement IDA / 69950 apacity of the food system’s Post Limited 88,200.00 0.00 2022-11-10 2022-11-14 2022-11-24 2022-12-24 2023-01-03 2023-05-03 travaux de réhabilitation de cation Selection ation productive base 1260 ha de périmètres irrigu és de Bama BF-UCP/PRSA-BF-319924-CS- CQS / Réalisation des EIES et Sustainability and adaptive c Consultant Qualifi Under Implement l'élaboration d'un PAR pour l IDA / 69950 apacity of the food system’s Post Limited 132,000.00 0.00 2022-11-15 2022-11-15 2022-11-29 2022-12-29 2023-01-08 2023-04-08 cation Selection ation es travaux de réhabilitation d productive base e 1260 ha de périmètres irrig ués de Bama BF-UCP/PRSA-BF-320009-CS- Sustainability and adaptive c CQS / Etudes techniques de c Consultant Qualifi IDA / 69950 apacity of the food system’s Post Open - National 19,400.00 0.00 Under Review 2022-11-15 2023-06-12 2022-11-25 2022-12-12 2022-12-26 2023-01-05 2023-03-06 onstruction de centrales solai cation Selection productive base res photovoltaïques BF-UCP/PRSA-BF-320010-CS- CQS / Élaboration d'une strat égie de communication et d'i Consultant Qualifi Under Implement IDA / D9210 Project Management Post Open - National 35,280.00 0.00 2022-11-25 2023-03-11 2022-12-05 2022-12-28 2023-01-04 2023-01-14 2023-03-15 nformation du PRSA et du CN cation Selection ation S-FL y compris des plans d'in formation et de communicati on BF-UCP/PRSA-BF-323257-CS- LCS / audit externe annuel d Least Cost Selecti Under Implement IDA / D9210 Project Management Post Open - National 79,380.00 0.00 2022-10-31 2022-10-25 2022-11-14 2022-12-01 2022-12-31 2023-01-05 2023-02-02 2023-02-16 2026-02-15 es compte du projet (exercic on ation es 2022, 2023 et 2024) BF-UCP/PRSA-BF-339356-CS- CQS / Assistance pour la mis Consultant Qualifi Under Implement IDA / 69950 Project Management Post Limited 21,300.00 0.00 2023-04-28 2023-06-12 2023-05-12 2023-06-11 2023-07-16 2023-10-14 e en place d'un système d'ar cation Selection ation chivage électronique de la d ocumentation BF-UCP/PRSA-BF-339358-CS- Sustainability and adaptive c CQS / Étude de renforcement Consultant Qualifi Pending Impleme IDA / 69950 apacity of the food system’s Post Limited 35,300.00 0.00 2023-03-20 2023-04-03 2023-05-03 2023-06-07 2023-08-06 des infrastructures nationale cation Selection ntation productive base s (états de lieux et études pr éalables) BF-UCP/PRSA-BF-339366-CS- CQS / Réalisation d'une étud Sustainability and adaptive c Consultant Qualifi Pending Impleme e sur le circuit de distribution IDA / 69950 apacity of the food system’s Post Limited 72,000.00 0.00 2023-04-20 2023-05-04 2023-06-03 2023-07-08 2023-10-06 cation Selection ntation (approvisionnement) et de co productive base mmercialisation des produits agricoles BF-UCP/PRSA-BF-339367-CS- CQS / Réalisation d'une étud Sustainability and adaptive c e de faisabilité pour la mise e Consultant Qualifi IDA / 69950 apacity of the food system’s Post Open - National 180,000.00 0.00 Under Review 2023-04-28 2023-06-12 2023-05-19 2023-07-02 2023-08-01 2023-09-05 2023-12-04 n place d’unités de transform cation Selection productive base ation industrielles agroalime ntaires adaptées (poudre d'oi gnon tomate, farine de mais) BF-UCP/PRSA-BF-339393-CS- Sustainability and adaptive c Consultant Qualifi CQS / Réalisation d'une étud IDA / 69950 apacity of the food system’s Post Limited 54,000.00 0.00 Under Review 2023-04-24 2023-06-12 2023-05-08 2023-06-07 2023-07-12 2023-09-10 cation Selection e de faisabilité de la construc productive base tion des silos BF-UCP/PRSA-BF-338981-CS- CQS / Élaboration d’un plan d Sustainability and adaptive c e maintenance et d’une strat Consultant Qualifi Pending Impleme IDA / 69950 apacity of the food system’s Post Limited 90,000.00 0.00 2023-03-15 2023-03-29 2023-04-28 2023-06-02 2023-11-29 égie d’optimisation du résea cation Selection ntation productive base u d'observation agrométéorol ogie face aux défis actuels BF-UCP/PRSA-BF-338988-CS- CQS / Conception d'une strat Sustainability and adaptive c égie nationale de partenariat Consultant Qualifi Pending Impleme IDA / 69950 apacity of the food system’s Post Limited 44,200.00 0.00 2023-03-15 2023-03-29 2023-04-28 2023-05-26 2023-07-25 public privé, universités en m cation Selection ntation productive base atière d’informations et de d onnées agro-météorologique au profit de l'ANAM Page 3 BF-UCP/PRSA-BF-339058-CS- Sustainability and adaptive c Consultant Qualifi Pending Impleme CQS / Production d'outils de c IDA / 69950 apacity of the food system’s Post Limited 88,339.00 0.00 2023-04-11 2023-04-25 2023-05-25 2023-06-22 2023-08-21 cation Selection ntation ommunication et de visibilité productive base du projet BF-UCP/PRSA-BF-338978-CS- CQS / Réalisation d'une étud Sustainability and adaptive c Consultant Qualifi Pending Impleme e diagnostique en vue de dét IDA / 69950 apacity of the food system’s Post Limited 88,339.00 0.00 2023-03-15 2023-03-29 2023-04-12 2023-05-03 2023-07-02 cation Selection ntation erminer la vulnérabilité alime productive base ntaire dans la zone du progra mme BF-UCP/PRSA-BF-339397-CS- Contingent Emergency Resp Consultant Qualifi Pending Impleme CQS / Réalisation des études IDA / 69950 Post Limited 170,000.00 0.00 2023-03-22 2023-04-05 2023-05-05 2023-06-09 2023-12-06 onse (CERC) cation Selection ntation APD de l'aménagement des b as-fonds BF-UCP/PRSA-BF-339402-CS- CQS / Étude sur les capacité Sustainability and adaptive c s des systèmes de conseil et Consultant Qualifi Under Implement IDA / 69950 apacity of the food system’s Post Limited 36,000.00 0.00 2023-04-20 2023-04-27 2023-05-04 2023-06-03 2023-07-08 2023-09-06 du système d’innovation dan cation Selection ation productive base s le cadre de la modernisatio n des services nationaux de vulgarisation BF-UCP/PRSA-BF-339403-CS- Sustainability and adaptive c CQS / Étude pour la réalisatio Consultant Qualifi Pending Impleme IDA / 69950 apacity of the food system’s Post Limited 22,500.00 0.00 2023-03-22 2023-04-05 2023-05-05 2023-06-09 2023-08-08 n des modèles d'exploitation cation Selection ntation productive base agricoles innovants d'irrigatio n BF-UCP/PRSA-BF-339401-CS- QCBS / Élaboration des plans Contingent Emergency Resp Quality And Cost- Open - Internationa Under Implement intégrés de développement IDA / 69950 Post 516,200.00 0.00 2023-05-31 2023-03-11 2023-06-21 2023-08-04 2023-09-18 2023-10-18 2023-11-22 2023-12-27 2024-05-25 onse (CERC) Based Selection l ation des paysages y compris la fo rmation des bénéficiaires BF-UCP/PRSA-BF-338949-CS- Sustainability and adaptive c QCBS / Réalisation des étude Consultant Qualifi Pending Impleme IDA / 69950 apacity of the food system’s Post Limited 150,000.00 0.00 2023-05-10 2023-05-24 2023-06-23 2023-07-28 2023-11-25 s environnementales, sociale cation Selection ntation productive base s et pédologique des bas fon ds BF-UCP/PRSA-BF-360934-CS- INDV / Étude d’ingénieure et Consultant Qualifi Pending Impleme IDA / 69950 Project Management Post Limited 100,000.00 0.00 2023-06-15 2023-06-29 2023-07-29 2023-09-02 2024-01-30 de suivi pour l'achèvement d cation Selection ntation es bâtiments de la DGESS INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-UCP/PRSA-BF-319882-CS- Sustainability and adaptive c INDV / Etudes techniques de Individual Consult IDA / 69950 apacity of the food system’s Post Limited 4,940.00 0.00 Under Review 2022-10-20 2023-06-12 2022-10-25 2022-11-08 2022-11-18 2022-12-18 construction d'une unité de s ant Selection productive base échage et d’extraction de jus à l'IRSAT BF-UCP/PRSA-BF-319902-CS- Sustainability and adaptive c INDV / Etudes techniques en Individual Consult Pending Impleme IDA / 69950 apacity of the food system’s Post Limited 3,970.00 0.00 2022-10-25 2022-10-30 2022-11-13 2022-11-23 2023-01-22 vue de la construction d'une ant Selection ntation productive base unité de traitement de seme nces maraîchères BF-UCP/PRSA-BF-339361-CS- INDV / Réalisation des études Individual Consult Pending Impleme IDA / 69950 Project Management Post Limited 8,900.00 0.00 2023-03-22 2023-03-27 2023-04-17 2023-05-22 2023-09-19 thématiques pour renforcer l ant Selection ntation e plaidoyer entre les acteurs BF-UCP/PRSA-BF-339362-CS- Individual Consult INDV / Élaboration de la strat IDA / 69950 Project Management Post Limited 50,000.00 0.00 Canceled 2023-03-30 2023-04-04 2023-04-25 2023-05-30 2023-09-27 ant Selection égie genre du Programme Page 4 PROCUREMENT PLAN (Textual Part) Project information: Cabo Verde: Resilient Tourism and Blue Economy Development in Cabo Verde Project (P176981) Project Implementation agency: UGPE (Unidade de Gestão de Projetos Especiais) Date of the Procurement Plan: June 23, 2022 Period covered by this Procurement Plan: 2022 - 2024 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable. Works: is not applicable. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. “Not Applicable” Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Cabo Verde : Resilient Tourism and Blue Economy Development in Cabo Verde Project PLAN General Information Country: Cabo Verde 2022-06-25 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P176981 GPN Date: 2022-06-23 Project Name: Resilient Tourism and Blue Economy Development in Cabo Verde Project Loan / Credit No: IDA / 71260 Unidade de Gestao de Projectos Especiais Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - 07/RTBED/UGPE/2022 / Reha Component 1: Development Single Stage - One E Works (without pr 2023-05-1 bilitation of Ponte de Canal, i IDA / 71260 of integrated and resilient to Post Request for Bids Open - National 300,000.00 0.00 Canceled 2022-07-31 2022-12-23 2022-08-05 2022-09-16 2022-10-16 2022-11-20 nvelope equalification) SP 9 n Santo Antão urism and blue economy infr D astructure 20/RTBED/UGPE/2022 / Reha Component 1: Development Request for Bids - bilitation of a section 8 km of of integrated and resilient to Open - Internationa Single Stage - One E Works (without pr Under Imple 2023-10-1 IDA / 71260 Prior Request for Bids 8,000,000.00 0.00 2022-12-26 2023-01-17 2022-12-31 2023-01-17 2023-02-11 2023-03-31 2023-03-13 2023-05-30 2023-04-17 main road connecting Esparg urism and blue economy infr l nvelope equalification) SP mentation 4 os and Santa Maria – Sal astructure D Request for Bids - 07/RTBED/UGPE/2023 - 2 / R Component 1: Development Single Stage - One E Works (without pr Under Imple 2023-12-0 ehabilitation of Ponte de Can IDA / 71260 of integrated and resilient to Post Request for Bids Open - National 300,000.00 0.00 2023-02-20 2023-02-28 2023-02-25 2023-04-08 2023-04-11 2023-05-08 2023-06-12 nvelope equalification) SP mentation 9 al, in Santo Antão urism and blue economy infr D astructure 25-RTBED-UGPE-2023 / Expa Component 1: Development Request for Bids - nsion and completion of the of integrated and resilient to Single Stage - One E Works (without pr Pending Imp 2024-05-1 IDA / 71260 Post Request for Bids Open - National 200,000.00 0.00 2023-07-31 2023-08-05 2023-09-16 2023-10-16 2023-11-20 cultural and arts center of Ri urism and blue economy infr nvelope equalification) SP lementation 8 beira Grande - 7 Sois 7 Luas astructure D GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Enhancement 11/RTBED/UGPE/2022 / Ocea of inclusive and sustainable Request for Quota Single Stage - One E Under Imple n Race: Set up of a Village Pa IDA / 71260 Post Open - National 270,000.00 0.00 2022-10-15 2022-12-10 2023-06-08 management of tourism in a tions nvelope mentation rk blue economy Component 2: Enhancement 12/RTBED/UGPE/2022 / Ocea of inclusive and sustainable Request for Quota Single Stage - One E Under Imple n Race: Recreation and Enter IDA / 71260 Post Open - National 200,000.00 0.00 2022-10-15 2022-12-10 2023-06-08 management of tourism in a tions nvelope mentation tainment blue economy 15/RTBED/UGPE/2022 / RAC Component 2: Enhancement E VILLAGE HOSPITALITY PLAT of inclusive and sustainable Direct - Internation Under Imple IDA / 71260 Post Direct Selection 60,000.00 0.00 2022-10-16 2022-10-10 2022-10-21 2022-10-19 2022-11-25 2023-05-24 FORM - Tall Ship Oosterschel management of tourism in a al mentation de. blue economy Component 2: Enhancement 14/RTBED/UGPE/2022 / Mark of inclusive and sustainable Request for Quota Single Stage - One E Under Imple IDA / 71260 Post Open - National 30,000.00 0.00 2022-12-05 2023-01-30 2023-07-29 eting & Communications management of tourism in a tions nvelope mentation blue economy CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 02/RTBED/UGPE/2022 / Deta Component 1: Development iled urban plan (study) for th of integrated and resilient to Least Cost Selecti Open - Internationa Under Implement e historic center of `Cidade V IDA / 71260 Post 250,000.00 0.00 2022-06-19 2022-06-30 2022-07-10 2022-07-11 2022-08-23 2022-11-16 2022-09-20 2022-12-28 2022-10-20 2023-03-10 2022-11-24 2022-12-29 2023-06-27 urism and blue economy infr on l ation elha`, according to UNESCO astructure guidelines (IPC, INGT, CMRGS ) 06/RTBED/UGPE/2022 / Map Component 1: Development ping (cartographic, digital, ph of integrated and resilient to Consultant Qualifi Under Implement otographic) and physical sign IDA / 71260 Post Open - National 150,000.00 0.00 2022-07-08 2022-07-14 2022-07-29 2022-09-11 2022-10-11 2022-11-15 2023-05-14 urism and blue economy infr cation Selection ation aling of 44 hiking trails (+-39 astructure 4 km in the 3 municipalities) 05/RTBED/UGPE/2022 / Prep Component 1: Development aratory Studies for the const of integrated and resilient to Quality And Cost- Open - Internationa Under Implement ruction or upgrade of maritim IDA / 71260 Post 460,000.00 0.00 2022-07-08 2022-09-05 2022-07-29 2022-09-22 2022-09-11 2022-10-09 2022-11-08 2022-12-13 2023-01-17 2024-01-17 urism and blue economy infr Based Selection l ation e passenger terminals locate astructure d on 4 islands (Praia, Sal, São Nicolau e Fogo) Component 2: Enhancement 09/RTBED/UGPE/2022 / TA fo of inclusive and sustainable Consultant Qualifi Open - Internationa Under Implement r Rebranding of Cabo Verde IDA / 71260 Post 120,000.00 0.00 2022-08-30 2022-08-27 2022-09-20 2022-08-30 2022-11-03 2022-12-13 2022-12-03 2023-01-07 2023-07-06 management of tourism in a cation Selection l ation as a Tourism Destination blue economy Component 2: Enhancement 10/RTBED/UGPE/2022 / Draft of inclusive and sustainable Quality And Cost- Open - Internationa Under Implement ing of Coastal Zone Plans for IDA / 71260 Post 200,000.00 0.00 2022-08-31 2022-09-02 2022-09-21 2022-09-13 2022-11-04 2022-12-02 2023-01-01 2023-02-05 2023-03-12 2024-03-11 management of tourism in a Based Selection l ation Sal Island blue economy 13/RTBED/UGPE/2022 / Cont Component 1: Development racting Supervision/Inspectio of integrated and resilient to Quality And Cost- Under Implement IDA / 71260 Post Open - National 302,000.00 0.00 2022-10-10 2022-10-07 2022-10-31 2022-12-14 2022-12-15 2023-01-11 2023-02-10 2023-02-10 2023-04-05 2023-03-17 2023-06-08 2023-04-21 2024-04-20 n Service for the Road Espar urism and blue economy infr Based Selection ation gos Santa Maria – Ilha de Sal astructure Page 1 Component 2: Enhancement 18/RTBED / TA to ITCV on De of inclusive and sustainable Consultant Qualifi Open - Internationa Under Implement stination Online Communicati IDA / 71260 Post 200,000.00 0.00 2022-12-10 2023-01-02 2022-12-31 2023-02-10 2023-02-13 2023-03-15 2023-04-19 2023-10-16 management of tourism in a cation Selection l ation on/Marketing blue economy 23-RTBED-UGPE-2023 / Tech Component 1: Development nical study for the upgrade of of integrated and resilient to Quality And Cost- Under Implement IDA / 71260 Post Open - National 300,000.00 0.00 2023-02-12 2023-03-22 2023-03-05 2023-03-24 2023-04-18 2023-05-16 2023-06-15 2023-07-20 2023-08-24 2024-08-23 the existing quay in Tarrafal urism and blue economy infr Based Selection ation de Santiago and its surroundi astructure ng areas 24-RTBED-UGPE-2023 / Stud Component 1: Development Consultant Qualifi y for the rehabilitation of the IDA / 71260 of integrated and resilient to Post Open - National 200,000.00 0.00 Canceled 2023-02-20 2023-05-11 2023-03-13 2023-04-26 2023-05-26 2023-06-30 2023-12-27 cation Selection fish market in Mindelo urism and blue economy infr astructure 08/RTBED/UGPE/2022 / Seaf Component 1: Development ront Protection, road access, of integrated and resilient to Least Cost Selecti Pending Impleme IDA / 71260 Post Open - National 250,000.00 0.00 2023-10-30 2023-11-20 2024-01-03 2024-01-31 2024-03-01 2024-04-05 2024-05-10 2024-11-06 boat landing, and fisheries su urism and blue economy infr on ntation pport in Tarrafal de Monte Tri astructure go 29/RTBED/UGPE/2023 / TA to support co-management initi Component 2: Enhancement atives in artisanal fishing co of inclusive and sustainable Quality And Cost- Open - Internationa Under Implement mmunities, to continue empo IDA / 71260 Post 300,000.00 0.00 2023-05-19 2023-05-23 2023-06-09 2023-05-30 2023-07-23 2023-08-20 2023-09-19 2023-10-24 2023-11-28 2024-11-27 management of tourism in a Based Selection l ation wering communities in the su blue economy stainable and inclusive mana gement of their marine and c oastal resources. 24-RTBED-UGPE-2023 - 2 / S Component 1: Development Consultant Qualifi Open - Internationa Under Implement tudy for the rehabilitation of IDA / 71260 of integrated and resilient to Post 200,000.00 0.00 2023-05-31 2023-05-30 2023-06-21 2023-05-30 2023-08-04 2023-09-03 2023-10-08 2024-04-05 cation Selection l ation the fish market in Mindelo urism and blue economy infr astructure INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 04/RTBED/UGPE/2022 / Mark eting Specialist for ITCV - Indi Component 3: Project Imple Individual Consult Under Implement IDA / 71260 Post Open 100,000.00 0.00 2022-06-23 2022-06-28 2022-08-11 2022-09-01 2022-10-06 2023-04-04 vidual consultant to support t mentation Support ant Selection ation he Ministry of Tourism and Tr ansportation (MTT) 01/RTBED/UGPE/2022 / Proje ct Manager for Resilient Touri Component 3: Project Imple Individual Consult IDA / 71260 Post Direct 188,000.00 19,661.68 Signed 2022-06-30 2022-06-30 2022-07-10 2022-07-04 2022-07-31 2022-07-04 2022-09-04 2022-07-05 2023-03-03 sm and Blue Economy Devel mentation Support ant Selection opment in Cabo Verde 03/RTBED/UGPE/2022 / Plan ning and Tourism Specialist - Component 3: Project Imple Individual Consult Under Implement IDA / 71260 Post Open 150,000.00 0.00 2022-07-08 2022-06-30 2022-08-26 2022-09-26 2022-09-16 2022-10-21 2023-04-19 Individual consultant to supp mentation Support ant Selection ation ort the Ministry of Tourism an d Transportation (MTT) Component 2: Enhancement 16/RTBED/UGPE/2022 / TA of of inclusive and sustainable Individual Consult Under Implement a senior consultant for the Mi IDA / 71260 Post Open - National 102,000.00 0.00 2022-11-30 2023-05-24 2023-01-18 2023-02-08 2023-03-15 2023-09-11 management of tourism in a ant Selection ation nistry of Sea blue economy Component 2: Enhancement 17/RTBED/UGPE/2022 / TA of of inclusive and sustainable Individual Consult Under Implement a junior consultant for the Mi IDA / 71260 Post Open - National 60,000.00 0.00 2022-11-30 2023-01-06 2023-01-18 2023-02-08 2023-03-15 2023-09-11 management of tourism in a ant Selection ation nistry of Sea blue economy 19/RTBED/UGPE/2022 / Busi Component 2: Enhancement ness development support a of inclusive and sustainable Individual Consult IDA / 71260 Post Open - National 105,000.00 0.00 Canceled 2022-12-09 2023-01-02 2023-01-27 2023-02-17 2023-03-24 2023-09-20 nd access to finance to SMEs management of tourism in a ant Selection – Suppliers Development Pro blue economy gram 19/RTBED/UGPE/2022-2 / Bu Component 2: Enhancement siness development support of inclusive and sustainable Individual Consult Open - Internationa Under Implement IDA / 71260 Post 105,000.00 0.00 2023-01-23 2023-01-19 2023-03-13 2023-04-03 2023-05-08 2023-11-04 and access to finance to SME management of tourism in a ant Selection l ation s – Suppliers Development Pr blue economy ogram 21/RTBED/UGPE/2023 / Stre Component 2: Enhancement ngthen Tourism National Stat of inclusive and sustainable Individual Consult Under Implement IDA / 71260 Post Limited 40,000.00 0.00 2023-02-10 2023-03-02 2023-02-15 2023-03-22 2023-03-08 2023-04-12 2023-10-09 istic System: TA to INE - Inter management of tourism in a ant Selection ation national Tourist Survey blue economy Component 2: Enhancement 26-RTBED-UGPE-2023 / Impl of inclusive and sustainable Individual Consult Under Implement ement gender mainstreamin IDA / 71260 Post Open - National 200,000.00 0.00 2023-02-20 2023-03-28 2023-04-10 2023-05-01 2023-06-05 2023-12-02 management of tourism in a ant Selection ation g activities into tourism blue economy 28/RTBED/UGPE/2023 / Cont Component 2: Enhancement ratação de um consultor naci of inclusive and sustainable Individual Consult onal para elaborar proposta IDA / 71260 Post Open - National 15,000.00 0.00 Canceled 2023-03-27 2023-03-24 2023-05-15 2023-06-05 2023-07-10 2024-01-06 management of tourism in a ant Selection de regulamento da atividade blue economy de prestador de serviço de al ojamento complementar 27/RTBED/UGPE/2023 / Inter national individual consultan Component 2: Enhancement cy to support the ministry of of inclusive and sustainable Individual Consult Open - Internationa IDA / 71260 Post 25,000.00 0.00 Canceled 2023-03-27 2023-03-27 2023-05-15 2023-06-05 2023-07-10 2024-01-06 tourism to prepare proposal management of tourism in a ant Selection l of regulation for complement blue economy ary accommodation service p roviders 22/RTBED/UGPE/2023 / TEC Component 1: Development HNICAL ASSISTANCE REGAR of integrated and resilient to Individual Consult Open - Internationa Pending Impleme DING HIKING TRAIL MANAGE IDA / 71260 Post 50,000.00 0.00 2023-06-30 2023-08-18 2023-09-08 2023-10-13 2024-04-10 urism and blue economy infr ant Selection l ntation MENT AND FEE STRUCTURE F astructure OR SANTO ANTÃO ISLAND 28/RTBED/UGPE/2023-2 / Co Component 2: Enhancement ntratação de um consultor na of inclusive and sustainable Individual Consult Under Implement cional para elaborar proposta IDA / 71260 Post Limited 15,000.00 0.00 2023-06-15 2023-05-30 2023-06-20 2023-06-06 2023-07-11 2023-08-15 2024-02-11 management of tourism in a ant Selection ation de regulamento da atividade blue economy de prestador de serviço de al ojamento complementar 27/RTBED/UGPE/2023-2 / Int ernational individual consulta Component 2: Enhancement ncy to support the ministry o of inclusive and sustainable Individual Consult Under Implement IDA / 71260 Post Limited 25,000.00 0.00 2023-06-15 2023-05-30 2023-06-20 2023-06-06 2023-07-11 2023-08-15 2024-02-11 f tourism to prepare proposal management of tourism in a ant Selection ation of regulation for complement blue economy ary accommodation service p roviders Page 2 Page 3 PROCUREMENT PLAN General 1. Project Information a. Country: Federal Republic of Somalia b. Project Name: Horn of Africa - Ground Water for Resilience - Somalia Component c. Project Number: P174867 d. Total Finance: USD 30 million 2. Project Implementation Agency: Ministry of Energy and Water Resources (MoEWR) 3. Date of Project Plan: January 2022 4. Period Covered by this Procurement: April2021 – Nov 2023 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” November 2020 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Document: The Bank’s standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified into Procurement Plan tables in STEP III. National Procurement Arrangements: Not applicable IV. Prequalification: Not applicable V. Leased Assets: Not Applicable VI. Procurement of Second-hand Goods: Not Applicable VII. Domestic Preference: Not Applicable 1 VIII. Hands on Expanded Implementation Support (HEIS): Not applicable IX. Other Relevant Procurement Information: Not Applicable X. Thresholds for Procurement Approaches and Method (US$ millions) Based on the risks identified above, the following procurement arrangements are proposed: a) Approach to Market: Based on previous experience and available local market, the following threshold will be used of open national/international and RFQ bidding (all figures in million USD) Table 1.2: Thresholds for procurement approaches and methods Procurement Methods (US$ millions)–Goods, Works, and Non- Consulting Services Open Open Request for Direct Category Internatio National Quotation Selection nal (RfQ) Works ≥ 5.0 <5.0 ≤ 0.2 All Values Goods, IT, and non- ≥ 0.5 <0.5 ≤ 0.1 All Values consultin g services Thresholds for Procurement Approaches and Methods (US$, millions) – Consulting Services Category Short List of National Consultants Consulting Engineering and Services Construction Supervision Consultants (Firms) ≤ 0.1 ≤ 0.2 Individual Consultants N/A N/A Direct Selection Consultants (Firms) All Values All Values Individual Consultants All Values All Values 2 XI. Table Packages for Goods, Works and Non-Consulting Services (At Negotiations – to be entered in STEP) Procurement Selection Estimat Bank Approach Ref. Contract Title, Description and Method Evaluation ed Cost Oversig (Open- No Category (RFP, RFB, Method (US$) ht National/ RFQ etc.) Limited etc.) Most Water Quality Testing kits for 5 states - G1 37,500.0 Prior Limited RFQ advantageous FGS 0 Bid Most Vehicles (1 per MS, 2 for FGS/MoEWR) - G2 315,000. Prior Open-National RFB advantageous FGS & 5 states 00 Bid Most GW office furniture and equipment - FGS & 144,000. Prior Open-National RFB advantageous G3 5 states 00 Bid Most Hydromet center data, information and 30,000.0 G4 Prior Limited RFQ advantageous national monitoring equipment - FGS 0 Bid 526,50 0.00 Works Most Design new/rehabilitate FGS MoEWR office 100,000. W1 Prior Limited RFQ advantageous - FGS 00 Bid Most 250,000. W2 Build new offices - 5 states Prior Open-National RFB advantageous 00 Bid Establish GW-data and information office Most 10,000.0 W3 section within National Hydromet Center - Prior Limited RFQ advantageous 0 FGS Bid 1 Procurement Selection Estimat Bank Approach Ref. Contract Title, Description and Method Evaluation ed Cost Oversig (Open- No Category (RFP, RFB, Method (US$) ht National/ RFQ etc.) Limited etc.) Engage construction engineering firm in Most 600,000. Open- W4 water point development / investments - 5 Prior RFB advantageous 00 International state Bid Most Open- W5 Develop the manually drilling technique 320,000 Prior RFB advantageous International Bid Sub- 1,280,000 Total Market Method Review by Approach Estimated (QCBS, Ref No. Contract Description Bank (Open- Cost (US$) LCBCS, QBS, (Prior/Post) National/ DS Limited etc.) Consulting Services Consultancy Services for back-stopping Open- C1 528,000.00 Prior QCBS engineers - FGS International Consultancy - Comprehensive hydrogeological Open C2 600,000.00 Prior QCBS survey - FGS International Consultancy - Study and development of Merti C3 200,000.00 Prior Open – National CQS auifer water - FGS 2 Market Method Review by Approach Estimated (QCBS, Ref No. Contract Description Bank (Open- Cost (US$) LCBCS, QBS, (Prior/Post) National/ DS Limited etc.) Consultancy - Study on resilient water supply Open- C4 for densely populated rural/peri-urban areas - 480,000.00 Prior QCBS International FGS & 5 States Consultancy Services - Rapid assessment of existing GW-governance condition (incl standards, guidelines) and (i) arrange interim C5 200,000.00 Prior Open - National CQS project system and (ii) present to government national comprehensive system - FGS (50% of project total) Consultancy Services - Develop national GW- C6 75,000.00 Prior Limited CQS strategy - FGS C7 Arrange water quality testing in Nairobi - FGS 10,000.00 Prior TBD TBD Consultancy Services - Develop business models for private sector engagement in GW C8 210,000.00 Prior Open-National CQS development, distribution and management - FGS Consultancy Services - Develop transboundary C9 water management models and engage in 150,000.00 Prior Open-National CQS cooperation - FGS Develop national GW data and information C10 25,000.00 Prior Open-National CQS management system - FGS Consultancy Services - Transfer of knowledge and method development (incl manual well- C11 250,000.00 Prior Open-National QCBS drilling, sustainable gw-management; reduce cost of investments) - FGS Consultancy Services - Develop academic BSc C12 education in GW development, management 150,000.00 Prior Open-National QCBS and monitoring - FGS 3 Market Method Review by Approach Estimated (QCBS, Ref No. Contract Description Bank (Open- Cost (US$) LCBCS, QBS, (Prior/Post) National/ DS Limited etc.) Consultancy Services - Arrange and deliver 1 year long "learning by doing & organized C13 40,000.00 Prior Limited INDV training" package in groundwater development and management. Consultancy Services - Assess capacity development status/needs, develop linked C14 strategy, prepare project training and 70,000.00 Prior Limited INDV curriculum in selected GW capacity development topics - FGS Consultancy Services - Develop, establish and C15 support project monitoring, evaluation and 60,000.00 Prior Limited INDV internal learning system - FGS Consultancy Services - Arrange and deliver GW C16 75,000.00 Prior Limited INDV capacity development (a package) - FGS Consultancy Services - Arrange and deliver GW Open- C17 400,000.00 Prior QCBS capacity development (a package) - 5 states International C18 Project Coordinator NPCU (18 month) - FGS 126,000.00 Prior Open-National INDV C19 Groundwater Engineer NPCU (18 month) - FGS 99,000.00 Prior Open-National INDV Social & Environmental Safeguard Specialist C20 63,000.00 Prior Open-National INDV NPCU (18 month) - FGS C21 Finance Specialist NPCU (18 month) - FGS 63,000.00 Prior Open-National INDV Procurement Specialist for NPCU (18 months) – C22 63,000.00 Prior Open-National INDV FGS C23 Security Specialist for NPCU (18 months) - FGS 63,000.00 Prior Open-National INDV Gender and Social Safeguard Specialist for C24 63,000.00 Prior Open-National INDV NPCU (18 months) - FGS Community Development Specialist for NPCU C25 63,000.00 Prior Open-National INDV (18 months) - FGS C26 Office Manager for NPCU - FGS 18,000.00 Prior Open-National INDV 4 Market Method Review by Approach Estimated (QCBS, Ref No. Contract Description Bank (Open- Cost (US$) LCBCS, QBS, (Prior/Post) National/ DS Limited etc.) Consultancy Services - Arrange a project C27 18,000.00 Prior Open-National INDV website and develop information strategy - FGS Security and Safeguard arrangements - FGS C28 450,000.00 Prior Open-National QCBS and 5 states C29 Water Engineer PIUs (18 month) – for 5 States 270,000.00 Prior Open-National QCBS Consultancy Services - Annual audit Services - C31 50,000.00 Prior Open-National LCS FGS Sub-total 4,932,000 Grand Total 6,738,500 5 PROCUREMENT Eastern and Southern Africa : Horn of Africa - Groundwater for Resilience Project PLAN General Information Country: Eastern and Southern Africa 2022-09-12 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174867 GPN Date: 2022-11-22 Project Name: Horn of Africa - Groundwater for Resilience Project Loan / Credit No: IDA / 70820 Water Sector Trust Fund Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-WSTF-307268-GO-RFB / S Component one: Delivery of upply and Delivery of various Single Stage - One E IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 381,000.00 0.00 Canceled 2022-08-22 2022-08-27 2022-10-08 2022-11-07 2022-12-12 2023-06-10 Groundwater management e nvelope es to priority areas quipment for Counties KE-WSTF-307271-GO-RFQ / P Component one: Delivery of Request for Quota Single Stage - One E rovision for Microsoft Office 3 IDA / 70820 inclusive groundwater servic Post Limited 30,000.00 0.00 Canceled 2022-10-12 2022-12-07 2023-02-27 tions nvelope 60 license es to priority areas KE-WSTF-307267-GO-RFB / S upply and Delivery of assorte Component one: Delivery of Single Stage - One E d office furniture and Confere IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 300,000.00 0.00 Canceled 2022-10-07 2022-10-12 2022-11-23 2022-12-23 2023-01-27 2023-03-27 nvelope nce Facilities for WSTF and th es to priority areas e 5 County Governments KE-WSTF-307242-GO-RFB / S Component one: Delivery of upply and Delivery of 7 No. P Single Stage - One E IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 620,000.00 0.00 Canceled 2022-10-07 2022-10-12 2022-11-23 2022-12-23 2023-01-27 2023-03-01 roject Vehicles for WSTF PIU nvelope es to priority areas and 5 Counties implementing the project KE-WSTF-307265-GO-RFB / S upply and Delivery of assorte Component one: Delivery of Single Stage - One E d ICT Equipment and Accesso IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 150,000.00 0.00 Canceled 2022-10-07 2022-10-12 2022-11-23 2022-12-23 2023-01-27 2023-04-03 nvelope ries (Laptops, Printers) for W es to priority areas STF and the 5 Counties KE-WSTF-307270-GO-RFQ / P Component one: Delivery of Request for Quota Single Stage - One E rovision for Auto Desk licens IDA / 70820 inclusive groundwater servic Post Limited 20,000.00 0.00 Canceled 2022-10-12 2022-12-07 2023-02-27 tions nvelope e (Civil 3D) - Multiple users es to priority areas KE-WSTF-307273-GO-RFQ / Component one: Delivery of Request for Quota Single Stage - One E Communication Equipment a IDA / 70820 inclusive groundwater servic Post Limited 40,000.00 0.00 Canceled 2022-10-12 2022-12-07 2023-02-07 tions nvelope nd Publicity for WSTF and 5 C es to priority areas ounties KE-WSTF-332744-GO-RFB / S Component one: Delivery of upply and Delivery of 7 No. P Single Stage - One E Pending Impl IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 620,000.00 0.00 2023-01-04 2023-01-09 2023-01-30 2023-02-20 2023-03-27 2023-06-25 roject Vehicles for WSTF PIU nvelope ementation es to priority areas and 5 Sub-PIUs Counties KE-WSTF-332761-GO-RFB / S Component one: Delivery of Single Stage - One E Pending Impl upply and Installation of Auto IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 20,000.00 0.00 2023-01-04 2023-01-09 2023-01-30 2023-02-20 2023-03-27 2023-06-25 nvelope ementation Desk License (Civil 3D) for M es to priority areas ultiple Users KE-WSTF-332828-GO-RFB / P Component one: Delivery of Single Stage - One E Pending Impl rovision for Microsoft Office 3 IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 30,000.00 0.00 2023-01-04 2023-01-09 2023-01-30 2023-02-20 2023-03-27 2023-05-26 nvelope ementation 60 License es to priority areas KE-WSTF-332758-GO-RFB / S Component one: Delivery of upply and Delivery of Various Single Stage - One E Pending Impl IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 381,000.00 0.00 2023-05-02 2023-05-07 2023-05-28 2023-06-18 2023-07-23 2023-10-21 Groundwater Management E nvelope ementation es to priority areas quipment for Counties KE-WSTF-332751-GO-RFB / S upply and Delivery of Assorte Component one: Delivery of Single Stage - One E Pending Impl d Office Furniture and Confer IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 300,000.00 0.00 2023-05-02 2023-05-07 2023-05-28 2023-06-18 2023-07-23 2023-10-21 nvelope ementation ence Facilities for WSTF and t es to priority areas he 5 County Governments KE-WSTF-332748-GO-RFB / S upply and Delivery of Assorte Component one: Delivery of Single Stage - One E Pending Impl d ICT Equipment and Accesso IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 170,000.00 0.00 2023-05-12 2023-05-17 2023-06-07 2023-06-28 2023-08-02 2023-10-31 nvelope ementation ries (Laptops and Printers) fo es to priority areas r WSTF and the 5 Counties KE-WSTF-332832-GO-RFB / S Component one: Delivery of upply and Delivery of Comm Request for Quota Single Stage - One E Pending Impl IDA / 70820 inclusive groundwater servic Post Limited 20,000.00 0.00 2023-06-04 2023-07-30 2023-09-28 unication and Publicity Equip tions nvelope ementation es to priority areas ment for WaterFund and 5 Su b-PIU Counties NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 KE-WSTF-307237-CS-QCBS / Component one: Delivery of Consultancy to undertake Ind Quality And Cost- Open - Internationa IDA / 70820 inclusive groundwater servic Post 800,000.00 0.00 Canceled 2023-06-22 2023-07-13 2023-08-26 2023-09-23 2023-10-23 2023-11-27 2024-01-01 2024-12-31 ependent Verification of Resu Based Selection l es to priority areas lts under the Performance-Ba sed Grant KE-WSTF-307238-CS-QCBS / Consultancy to provide TA to County Governments of Turk Component one: Delivery of Quality And Cost- Open - Internationa ana, Wajir, Garissa, Mandera, IDA / 70820 inclusive groundwater servic Post 200,000.00 0.00 Canceled 2022-08-22 2022-09-12 2022-10-26 2022-11-23 2022-12-23 2023-01-27 2023-03-03 2024-03-02 Based Selection l and Marsabit to develop Insti es to priority areas tutional Systems for sustaina ble O&M of rural Water suppl y Infrastructure KE-WSTF-307240-CS-QCBS / Consultancy for the Develop ment and Implementation Su Component one: Delivery of pport of a Web-based Inform Quality And Cost- Open - Internationa IDA / 70820 inclusive groundwater servic Post 500,000.00 0.00 Canceled 2022-08-22 2022-09-12 2022-10-26 2022-11-23 2022-12-23 2023-01-27 2023-03-03 2024-03-02 ation Management System (I Based Selection l es to priority areas MS) and Decision Support Sy stem (DSS) for the O&M of ru ral water supply systems at t he county level KE-WSTF-307241-CS-QCBS / Consultancy for TA to County Component one: Delivery of Governments for the Prepara Quality And Cost- IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2022-12-16 2023-01-06 2023-02-19 2023-03-19 2023-04-18 2023-05-23 2023-06-27 2024-06-26 tion of the County Water Sec Based Selection es to priority areas tor Drought Contingency Plan s for Turkana, Marsabit, Wajir , and Mandera counties KE-WSTF-328819-CS-QCBS / Lot 1: Implementation Suppo rt Consultancy to undertake Component one: Delivery of Feasibility studies, Detailed d Quality And Cost- Open - Internationa Under Implement IDA / 70820 inclusive groundwater servic Prior 1,200,000.00 0.00 2022-12-20 2023-04-05 2022-12-24 2023-05-18 2023-01-21 2023-02-11 2023-03-13 2023-04-10 2023-05-15 2023-07-14 esigns , preparation of ESF in Based Selection l ation es to priority areas struments and Construction Supervision of various new, R ehabilitations and Upgrading of existing groundwater infra structure KE-WSTF-328828-CS-QCBS / Component one: Delivery of Consultancy to Undertake In Quality And Cost- Open - Internationa Under Implement IDA / 70820 inclusive groundwater servic Prior 800,000.00 0.00 2023-01-04 2023-04-05 2023-01-11 2023-05-18 2023-02-22 2023-03-08 2023-03-29 2023-05-03 2023-06-07 2024-06-06 dependent Verification of Res Based Selection l ation es to priority areas ults under the Performance-B ased Grant KE-WSTF-330591-CS-QCBS / Consultancy to provide Tech nical Assistance to County G Component one: Delivery of Quality And Cost- Open - Internationa Under Implement overnments to develop Instit IDA / 70820 inclusive groundwater servic Post 200,000.00 0.00 2022-12-18 2023-04-03 2023-01-08 2023-05-11 2023-02-21 2023-03-21 2023-04-20 2023-05-25 2023-06-29 2024-06-28 Based Selection l ation utional Systems for Sustaina es to priority areas ble Operation & Maintenance of Rural Water Supply Infrast ructure KE-WSTF-330626-CS-QCBS / Consultancy for Technical As Component one: Delivery of Quality And Cost- Open - Internationa Under Implement sistance to County Governme IDA / 70820 inclusive groundwater servic Post 100,000.00 0.00 2023-01-04 2023-01-25 2023-03-10 2023-04-07 2023-05-07 2023-06-11 2023-07-16 2024-01-12 Based Selection l ation nts for the Preparation of the es to priority areas County Water Sector Drought Contingency Plans KE-WSTF-332741-CS-QCBS / Lot 2 - Implementation Supp ort Consultancy to Undertake Component one: Delivery of Feasibility Studies, Detailed Quality And Cost- Open - Internationa Under Implement IDA / 70820 inclusive groundwater servic Prior 1,800,000.00 0.00 2022-12-27 2023-04-05 2023-01-17 2023-05-18 2023-02-21 2023-03-14 2023-04-04 2023-05-09 2023-06-13 2023-12-12 Designs, Preparation of ESF I Based Selection l ation es to priority areas nstruments and Construction Supervision of various new, R ehabilitations and Upgrading of existing Groundwater Infra structure. KE-WSTF-332742-CS-QCBS / Consultancy for the Develop Component one: Delivery of ment and Implementation Su Quality And Cost- Open - Internationa Under Implement IDA / 70820 inclusive groundwater servic Prior 500,000.00 0.00 2023-01-04 2023-04-24 2023-01-25 2023-05-18 2023-03-01 2023-03-22 2023-04-12 2023-05-17 2023-06-21 2023-12-20 pport of a Web-based Inform Based Selection l ation es to priority areas ation Management System a nd Decision Support System KE-WSTF-307233-CS-QCBS / Implementation Support Con sultancy to undertake Feasibi lity studies, Detailed designs Component one: Delivery of Quality And Cost- Open - Internationa , preparation of ESF instrume IDA / 70820 inclusive groundwater servic Post 3,000,000.00 0.00 Canceled 2022-08-22 2022-09-22 2022-11-22 2022-12-20 2023-01-19 2023-02-23 2023-03-30 2024-03-29 Based Selection l nts and Construction Supervi es to priority areas sion of various new, Rehabilit ations and Upgrading of exist ing groundwater infrastructur e in the implementing INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-WSTF-307277-CS-INDV / Component one: Delivery of Individual Consult M&E Consultant to Support IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2022-08-22 2022-10-10 2022-10-31 2022-12-05 2023-06-03 ant Selection WSTF PIU es to priority areas KE-WSTF-307280-CS-INDV / Component one: Delivery of Individual Consult Procurement Specialist Supp IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2022-08-22 2022-10-10 2022-10-31 2022-12-05 2023-06-03 ant Selection ort to the Counties through es to priority areas WSTF KE-WSTF-307282-CS-INDV / Component one: Delivery of Individual Consult Environmental Safeguards C IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2022-08-22 2022-10-10 2022-10-31 2022-12-05 2023-06-03 ant Selection onsultant to Support WSTF a es to priority areas nd WRA PIUs KE-WSTF-307284-CS-INDV / Component one: Delivery of Individual Consult Consultant Project Accountan IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2022-08-22 2022-10-10 2022-10-31 2022-12-05 2023-06-03 ant Selection t for WSTF to support PBG Di es to priority areas sbursements KE-WSTF-307842-CS-INDV / Component one: Delivery of This is an Individual Consulta Individual Consult IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2027-11-19 ncy support to the PIU, mainl ant Selection es to priority areas y for administration of PBG. KE-WSTF-346281-CS-INDV / Component one: Delivery of Individual Consult Pending Impleme Monitoring and Evaluation (M IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 2023-05-12 2023-06-30 2023-07-21 2023-08-25 2025-02-15 ant Selection ntation &E) Consultant to support W es to priority areas STF PIU Page 2 KE-WSTF-346285-CS-INDV / Component one: Delivery of Individual Consult Pending Impleme Procurement specialist suppo IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 2023-05-12 2023-06-30 2023-07-21 2023-08-25 2025-02-15 ant Selection ntation rt to the 5 Counties through es to priority areas WSTF KE-WSTF-346290-CS-INDV / Component one: Delivery of Individual Consult Gender Based Violence Cons IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2023-05-12 2023-05-22 2023-06-30 2023-07-21 2023-08-25 2025-02-15 ant Selection ultant to support PIUs and SP es to priority areas IUs through WSTF KE-WSTF-363462-CS-INDV / Component one: Delivery of Individual Consult Under Implement Gender Based Violence Cons IDA / 70820 inclusive groundwater servic Post Limited 100,000.00 0.00 2023-05-31 2023-05-28 2023-06-05 2023-06-26 2023-07-31 2025-07-30 ant Selection ation ultant to support PIUs and SP es to priority areas IUs through WSTF Page 3 PROCUREMENT PLAN General 1. Project Information a. Country: Federal Republic of Somalia b. Project Name: Horn of Africa - Ground Water for Resilience - Somalia Component c. Project Number: P174867 d. Total Finance: USD 30 million 2. Project Implementation Agency: Ministry of Energy and Water Resources (MoEWR) 3. Date of Project Plan: January 2022 4. Period Covered by this Procurement: April2021 – Nov 2023 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” November 2020 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Document: The Bank’s standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified into Procurement Plan tables in STEP III. National Procurement Arrangements: Not applicable IV. Prequalification: Not applicable V. Leased Assets: Not Applicable VI. Procurement of Second-hand Goods: Not Applicable VII. Domestic Preference: Not Applicable 1 VIII. Hands on Expanded Implementation Support (HEIS): Not applicable IX. Other Relevant Procurement Information: Not Applicable X. Thresholds for Procurement Approaches and Method (US$ millions) Based on the risks identified above, the following procurement arrangements are proposed: a) Approach to Market: Based on previous experience and available local market, the following threshold will be used of open national/international and RFQ bidding (all figures in million USD) Table 1.2: Thresholds for procurement approaches and methods Procurement Methods (US$ millions)–Goods, Works, and Non- Consulting Services Open Open Request for Direct Category Internatio National Quotation Selection nal (RfQ) Works ≥ 5.0 <5.0 ≤ 0.2 All Values Goods, IT, and non- ≥ 0.5 <0.5 ≤ 0.1 All Values consultin g services Thresholds for Procurement Approaches and Methods (US$, millions) – Consulting Services Category Short List of National Consultants Consulting Engineering and Services Construction Supervision Consultants (Firms) ≤ 0.1 ≤ 0.2 Individual Consultants N/A N/A Direct Selection Consultants (Firms) All Values All Values Individual Consultants All Values All Values 2 XI. Table Packages for Goods, Works and Non-Consulting Services (At Negotiations – to be entered in STEP) Procurement Selection Estimat Bank Approach Ref. Contract Title, Description and Method Evaluation ed Cost Oversig (Open- No Category (RFP, RFB, Method (US$) ht National/ RFQ etc.) Limited etc.) Most Water Quality Testing kits for 5 states - G1 37,500.0 Prior Limited RFQ advantageous FGS 0 Bid Most Vehicles (1 per MS, 2 for FGS/MoEWR) - G2 315,000. Prior Open-National RFB advantageous FGS & 5 states 00 Bid Most GW office furniture and equipment - FGS & 144,000. Prior Open-National RFB advantageous G3 5 states 00 Bid Most Hydromet center data, information and 30,000.0 G4 Prior Limited RFQ advantageous national monitoring equipment - FGS 0 Bid 526,50 0.00 Works Most Design new/rehabilitate FGS MoEWR office 100,000. W1 Prior Limited RFQ advantageous - FGS 00 Bid Most 250,000. W2 Build new offices - 5 states Prior Open-National RFB advantageous 00 Bid Establish GW-data and information office Most 10,000.0 W3 section within National Hydromet Center - Prior Limited RFQ advantageous 0 FGS Bid 1 Procurement Selection Estimat Bank Approach Ref. Contract Title, Description and Method Evaluation ed Cost Oversig (Open- No Category (RFP, RFB, Method (US$) ht National/ RFQ etc.) Limited etc.) Engage construction engineering firm in Most 600,000. Open- W4 water point development / investments - 5 Prior RFB advantageous 00 International state Bid Most Open- W5 Develop the manually drilling technique 320,000 Prior RFB advantageous International Bid Sub- 1,280,000 Total Market Method Review by Approach Estimated (QCBS, Ref No. Contract Description Bank (Open- Cost (US$) LCBCS, QBS, (Prior/Post) National/ DS Limited etc.) Consulting Services Consultancy Services for back-stopping Open- C1 528,000.00 Prior QCBS engineers - FGS International Consultancy - Comprehensive hydrogeological Open C2 600,000.00 Prior QCBS survey - FGS International Consultancy - Study and development of Merti C3 200,000.00 Prior Open – National CQS auifer water - FGS 2 Market Method Review by Approach Estimated (QCBS, Ref No. Contract Description Bank (Open- Cost (US$) LCBCS, QBS, (Prior/Post) National/ DS Limited etc.) Consultancy - Study on resilient water supply Open- C4 for densely populated rural/peri-urban areas - 480,000.00 Prior QCBS International FGS & 5 States Consultancy Services - Rapid assessment of existing GW-governance condition (incl standards, guidelines) and (i) arrange interim C5 200,000.00 Prior Open - National CQS project system and (ii) present to government national comprehensive system - FGS (50% of project total) Consultancy Services - Develop national GW- C6 75,000.00 Prior Limited CQS strategy - FGS C7 Arrange water quality testing in Nairobi - FGS 10,000.00 Prior TBD TBD Consultancy Services - Develop business models for private sector engagement in GW C8 210,000.00 Prior Open-National CQS development, distribution and management - FGS Consultancy Services - Develop transboundary C9 water management models and engage in 150,000.00 Prior Open-National CQS cooperation - FGS Develop national GW data and information C10 25,000.00 Prior Open-National CQS management system - FGS Consultancy Services - Transfer of knowledge and method development (incl manual well- C11 250,000.00 Prior Open-National QCBS drilling, sustainable gw-management; reduce cost of investments) - FGS Consultancy Services - Develop academic BSc C12 education in GW development, management 150,000.00 Prior Open-National QCBS and monitoring - FGS 3 Market Method Review by Approach Estimated (QCBS, Ref No. Contract Description Bank (Open- Cost (US$) LCBCS, QBS, (Prior/Post) National/ DS Limited etc.) Consultancy Services - Arrange and deliver 1 year long "learning by doing & organized C13 40,000.00 Prior Limited INDV training" package in groundwater development and management. Consultancy Services - Assess capacity development status/needs, develop linked C14 strategy, prepare project training and 70,000.00 Prior Limited INDV curriculum in selected GW capacity development topics - FGS Consultancy Services - Develop, establish and C15 support project monitoring, evaluation and 60,000.00 Prior Limited INDV internal learning system - FGS Consultancy Services - Arrange and deliver GW C16 75,000.00 Prior Limited INDV capacity development (a package) - FGS Consultancy Services - Arrange and deliver GW Open- C17 400,000.00 Prior QCBS capacity development (a package) - 5 states International C18 Project Coordinator NPCU (18 month) - FGS 126,000.00 Prior Open-National INDV C19 Groundwater Engineer NPCU (18 month) - FGS 99,000.00 Prior Open-National INDV Social & Environmental Safeguard Specialist C20 63,000.00 Prior Open-National INDV NPCU (18 month) - FGS C21 Finance Specialist NPCU (18 month) - FGS 63,000.00 Prior Open-National INDV Procurement Specialist for NPCU (18 months) – C22 63,000.00 Prior Open-National INDV FGS C23 Security Specialist for NPCU (18 months) - FGS 63,000.00 Prior Open-National INDV Gender and Social Safeguard Specialist for C24 63,000.00 Prior Open-National INDV NPCU (18 months) - FGS Community Development Specialist for NPCU C25 63,000.00 Prior Open-National INDV (18 months) - FGS C26 Office Manager for NPCU - FGS 18,000.00 Prior Open-National INDV 4 Market Method Review by Approach Estimated (QCBS, Ref No. Contract Description Bank (Open- Cost (US$) LCBCS, QBS, (Prior/Post) National/ DS Limited etc.) Consultancy Services - Arrange a project C27 18,000.00 Prior Open-National INDV website and develop information strategy - FGS Security and Safeguard arrangements - FGS C28 450,000.00 Prior Open-National QCBS and 5 states C29 Water Engineer PIUs (18 month) – for 5 States 270,000.00 Prior Open-National QCBS Consultancy Services - Annual audit Services - C31 50,000.00 Prior Open-National LCS FGS Sub-total 4,932,000 Grand Total 6,738,500 5 PROCUREMENT Eastern and Southern Africa : Horn of Africa - Groundwater for Resilience Project PLAN General Information Country: Eastern and Southern Africa 2022-09-12 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174867 GPN Date: 2022-11-22 Project Name: Horn of Africa - Groundwater for Resilience Project Loan / Credit No: IDA / 70820 Water Sector Trust Fund Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-WSTF-307268-GO-RFB / S Component one: Delivery of upply and Delivery of various Single Stage - One E IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 381,000.00 0.00 Canceled 2022-08-22 2022-08-27 2022-10-08 2022-11-07 2022-12-12 2023-06-10 Groundwater management e nvelope es to priority areas quipment for Counties KE-WSTF-307271-GO-RFQ / P Component one: Delivery of Request for Quota Single Stage - One E rovision for Microsoft Office 3 IDA / 70820 inclusive groundwater servic Post Limited 30,000.00 0.00 Canceled 2022-10-12 2022-12-07 2023-02-27 tions nvelope 60 license es to priority areas KE-WSTF-307267-GO-RFB / S upply and Delivery of assorte Component one: Delivery of Single Stage - One E d office furniture and Confere IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 300,000.00 0.00 Canceled 2022-10-07 2022-10-12 2022-11-23 2022-12-23 2023-01-27 2023-03-27 nvelope nce Facilities for WSTF and th es to priority areas e 5 County Governments KE-WSTF-307242-GO-RFB / S Component one: Delivery of upply and Delivery of 7 No. P Single Stage - One E IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 620,000.00 0.00 Canceled 2022-10-07 2022-10-12 2022-11-23 2022-12-23 2023-01-27 2023-03-01 roject Vehicles for WSTF PIU nvelope es to priority areas and 5 Counties implementing the project KE-WSTF-307265-GO-RFB / S upply and Delivery of assorte Component one: Delivery of Single Stage - One E d ICT Equipment and Accesso IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 150,000.00 0.00 Canceled 2022-10-07 2022-10-12 2022-11-23 2022-12-23 2023-01-27 2023-04-03 nvelope ries (Laptops, Printers) for W es to priority areas STF and the 5 Counties KE-WSTF-307270-GO-RFQ / P Component one: Delivery of Request for Quota Single Stage - One E rovision for Auto Desk licens IDA / 70820 inclusive groundwater servic Post Limited 20,000.00 0.00 Canceled 2022-10-12 2022-12-07 2023-02-27 tions nvelope e (Civil 3D) - Multiple users es to priority areas KE-WSTF-307273-GO-RFQ / Component one: Delivery of Request for Quota Single Stage - One E Communication Equipment a IDA / 70820 inclusive groundwater servic Post Limited 40,000.00 0.00 Canceled 2022-10-12 2022-12-07 2023-02-07 tions nvelope nd Publicity for WSTF and 5 C es to priority areas ounties KE-WSTF-332744-GO-RFB / S Component one: Delivery of upply and Delivery of 7 No. P Single Stage - One E Pending Impl IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 620,000.00 0.00 2023-01-04 2023-01-09 2023-01-30 2023-02-20 2023-03-27 2023-06-25 roject Vehicles for WSTF PIU nvelope ementation es to priority areas and 5 Sub-PIUs Counties KE-WSTF-332761-GO-RFB / S Component one: Delivery of Single Stage - One E Pending Impl upply and Installation of Auto IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 20,000.00 0.00 2023-01-04 2023-01-09 2023-01-30 2023-02-20 2023-03-27 2023-06-25 nvelope ementation Desk License (Civil 3D) for M es to priority areas ultiple Users KE-WSTF-332828-GO-RFB / P Component one: Delivery of Single Stage - One E Pending Impl rovision for Microsoft Office 3 IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 30,000.00 0.00 2023-01-04 2023-01-09 2023-01-30 2023-02-20 2023-03-27 2023-05-26 nvelope ementation 60 License es to priority areas KE-WSTF-332758-GO-RFB / S Component one: Delivery of upply and Delivery of Various Single Stage - One E Pending Impl IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 381,000.00 0.00 2023-05-02 2023-05-07 2023-05-28 2023-06-18 2023-07-23 2023-10-21 Groundwater Management E nvelope ementation es to priority areas quipment for Counties KE-WSTF-332751-GO-RFB / S upply and Delivery of Assorte Component one: Delivery of Single Stage - One E Pending Impl d Office Furniture and Confer IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 300,000.00 0.00 2023-05-02 2023-05-07 2023-05-28 2023-06-18 2023-07-23 2023-10-21 nvelope ementation ence Facilities for WSTF and t es to priority areas he 5 County Governments KE-WSTF-332748-GO-RFB / S upply and Delivery of Assorte Component one: Delivery of Single Stage - One E Pending Impl d ICT Equipment and Accesso IDA / 70820 inclusive groundwater servic Post Request for Bids Open - National 170,000.00 0.00 2023-05-12 2023-05-17 2023-06-07 2023-06-28 2023-08-02 2023-10-31 nvelope ementation ries (Laptops and Printers) fo es to priority areas r WSTF and the 5 Counties KE-WSTF-332832-GO-RFB / S Component one: Delivery of upply and Delivery of Comm Request for Quota Single Stage - One E Pending Impl IDA / 70820 inclusive groundwater servic Post Limited 20,000.00 0.00 2023-06-04 2023-07-30 2023-09-28 unication and Publicity Equip tions nvelope ementation es to priority areas ment for WaterFund and 5 Su b-PIU Counties NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 KE-WSTF-307237-CS-QCBS / Component one: Delivery of Consultancy to undertake Ind Quality And Cost- Open - Internationa IDA / 70820 inclusive groundwater servic Post 800,000.00 0.00 Canceled 2023-06-22 2023-07-13 2023-08-26 2023-09-23 2023-10-23 2023-11-27 2024-01-01 2024-12-31 ependent Verification of Resu Based Selection l es to priority areas lts under the Performance-Ba sed Grant KE-WSTF-307238-CS-QCBS / Consultancy to provide TA to County Governments of Turk Component one: Delivery of Quality And Cost- Open - Internationa ana, Wajir, Garissa, Mandera, IDA / 70820 inclusive groundwater servic Post 200,000.00 0.00 Canceled 2022-08-22 2022-09-12 2022-10-26 2022-11-23 2022-12-23 2023-01-27 2023-03-03 2024-03-02 Based Selection l and Marsabit to develop Insti es to priority areas tutional Systems for sustaina ble O&M of rural Water suppl y Infrastructure KE-WSTF-307240-CS-QCBS / Consultancy for the Develop ment and Implementation Su Component one: Delivery of pport of a Web-based Inform Quality And Cost- Open - Internationa IDA / 70820 inclusive groundwater servic Post 500,000.00 0.00 Canceled 2022-08-22 2022-09-12 2022-10-26 2022-11-23 2022-12-23 2023-01-27 2023-03-03 2024-03-02 ation Management System (I Based Selection l es to priority areas MS) and Decision Support Sy stem (DSS) for the O&M of ru ral water supply systems at t he county level KE-WSTF-307241-CS-QCBS / Consultancy for TA to County Component one: Delivery of Governments for the Prepara Quality And Cost- IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2022-12-16 2023-01-06 2023-02-19 2023-03-19 2023-04-18 2023-05-23 2023-06-27 2024-06-26 tion of the County Water Sec Based Selection es to priority areas tor Drought Contingency Plan s for Turkana, Marsabit, Wajir , and Mandera counties KE-WSTF-328819-CS-QCBS / Lot 1: Implementation Suppo rt Consultancy to undertake Component one: Delivery of Feasibility studies, Detailed d Quality And Cost- Open - Internationa Under Implement IDA / 70820 inclusive groundwater servic Prior 1,200,000.00 0.00 2022-12-20 2023-04-05 2022-12-24 2023-05-18 2023-01-21 2023-02-11 2023-03-13 2023-04-10 2023-05-15 2023-07-14 esigns , preparation of ESF in Based Selection l ation es to priority areas struments and Construction Supervision of various new, R ehabilitations and Upgrading of existing groundwater infra structure KE-WSTF-328828-CS-QCBS / Component one: Delivery of Consultancy to Undertake In Quality And Cost- Open - Internationa Under Implement IDA / 70820 inclusive groundwater servic Prior 800,000.00 0.00 2023-01-04 2023-04-05 2023-01-11 2023-05-18 2023-02-22 2023-03-08 2023-03-29 2023-05-03 2023-06-07 2024-06-06 dependent Verification of Res Based Selection l ation es to priority areas ults under the Performance-B ased Grant KE-WSTF-330591-CS-QCBS / Consultancy to provide Tech nical Assistance to County G Component one: Delivery of Quality And Cost- Open - Internationa Under Implement overnments to develop Instit IDA / 70820 inclusive groundwater servic Post 200,000.00 0.00 2022-12-18 2023-04-03 2023-01-08 2023-05-11 2023-02-21 2023-03-21 2023-04-20 2023-05-25 2023-06-29 2024-06-28 Based Selection l ation utional Systems for Sustaina es to priority areas ble Operation & Maintenance of Rural Water Supply Infrast ructure KE-WSTF-330626-CS-QCBS / Consultancy for Technical As Component one: Delivery of Quality And Cost- Open - Internationa Under Implement sistance to County Governme IDA / 70820 inclusive groundwater servic Post 100,000.00 0.00 2023-01-04 2023-01-25 2023-03-10 2023-04-07 2023-05-07 2023-06-11 2023-07-16 2024-01-12 Based Selection l ation nts for the Preparation of the es to priority areas County Water Sector Drought Contingency Plans KE-WSTF-332741-CS-QCBS / Lot 2 - Implementation Supp ort Consultancy to Undertake Component one: Delivery of Feasibility Studies, Detailed Quality And Cost- Open - Internationa Under Implement IDA / 70820 inclusive groundwater servic Prior 1,800,000.00 0.00 2022-12-27 2023-04-05 2023-01-17 2023-05-18 2023-02-21 2023-03-14 2023-04-04 2023-05-09 2023-06-13 2023-12-12 Designs, Preparation of ESF I Based Selection l ation es to priority areas nstruments and Construction Supervision of various new, R ehabilitations and Upgrading of existing Groundwater Infra structure. KE-WSTF-332742-CS-QCBS / Consultancy for the Develop Component one: Delivery of ment and Implementation Su Quality And Cost- Open - Internationa Under Implement IDA / 70820 inclusive groundwater servic Prior 500,000.00 0.00 2023-01-04 2023-04-24 2023-01-25 2023-05-18 2023-03-01 2023-03-22 2023-04-12 2023-05-17 2023-06-21 2023-12-20 pport of a Web-based Inform Based Selection l ation es to priority areas ation Management System a nd Decision Support System KE-WSTF-307233-CS-QCBS / Implementation Support Con sultancy to undertake Feasibi lity studies, Detailed designs Component one: Delivery of Quality And Cost- Open - Internationa , preparation of ESF instrume IDA / 70820 inclusive groundwater servic Post 3,000,000.00 0.00 Canceled 2022-08-22 2022-09-22 2022-11-22 2022-12-20 2023-01-19 2023-02-23 2023-03-30 2024-03-29 Based Selection l nts and Construction Supervi es to priority areas sion of various new, Rehabilit ations and Upgrading of exist ing groundwater infrastructur e in the implementing INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-WSTF-307277-CS-INDV / Component one: Delivery of Individual Consult M&E Consultant to Support IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2022-08-22 2022-10-10 2022-10-31 2022-12-05 2023-06-03 ant Selection WSTF PIU es to priority areas KE-WSTF-307280-CS-INDV / Component one: Delivery of Individual Consult Procurement Specialist Supp IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2022-08-22 2022-10-10 2022-10-31 2022-12-05 2023-06-03 ant Selection ort to the Counties through es to priority areas WSTF KE-WSTF-307282-CS-INDV / Component one: Delivery of Individual Consult Environmental Safeguards C IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2022-08-22 2022-10-10 2022-10-31 2022-12-05 2023-06-03 ant Selection onsultant to Support WSTF a es to priority areas nd WRA PIUs KE-WSTF-307284-CS-INDV / Component one: Delivery of Individual Consult Consultant Project Accountan IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2022-08-22 2022-10-10 2022-10-31 2022-12-05 2023-06-03 ant Selection t for WSTF to support PBG Di es to priority areas sbursements KE-WSTF-307842-CS-INDV / Component one: Delivery of This is an Individual Consulta Individual Consult IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2027-11-19 ncy support to the PIU, mainl ant Selection es to priority areas y for administration of PBG. KE-WSTF-346281-CS-INDV / Component one: Delivery of Individual Consult Pending Impleme Monitoring and Evaluation (M IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 2023-05-12 2023-06-30 2023-07-21 2023-08-25 2025-02-15 ant Selection ntation &E) Consultant to support W es to priority areas STF PIU Page 2 KE-WSTF-346285-CS-INDV / Component one: Delivery of Individual Consult Pending Impleme Procurement specialist suppo IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 2023-05-12 2023-06-30 2023-07-21 2023-08-25 2025-02-15 ant Selection ntation rt to the 5 Counties through es to priority areas WSTF KE-WSTF-346290-CS-INDV / Component one: Delivery of Individual Consult Gender Based Violence Cons IDA / 70820 inclusive groundwater servic Post Open - National 100,000.00 0.00 Canceled 2023-05-12 2023-05-22 2023-06-30 2023-07-21 2023-08-25 2025-02-15 ant Selection ultant to support PIUs and SP es to priority areas IUs through WSTF KE-WSTF-363462-CS-INDV / Component one: Delivery of Individual Consult Under Implement Gender Based Violence Cons IDA / 70820 inclusive groundwater servic Post Limited 100,000.00 0.00 2023-05-31 2023-05-28 2023-06-05 2023-06-26 2023-07-31 2025-07-30 ant Selection ation ultant to support PIUs and SP es to priority areas IUs through WSTF Page 3 PLAN DE PASSATION DE MARCHÉS (Texte) Information sur le Projet : [Nom du pays] [Nom du Projet] [No d’identification du projet] Agence d’exécution du Projet : [Insérer le nom officiel de l’Agence] Date du plan de passation des marchés : [Insérer la date] Période couverte par ce plan de passation des marchés : [Insérer date de début, date de fin] Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016) (“Règlement de Passation des Marchés”) le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marché se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus de STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées [Insérer la référence exacte de la législation nationale], ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : Indiquer la liste des conditions requises pour assurer la cohérence avec le paragraphe 5.4 du Règlement de passation des marchés. Si aucune condition s’applique, supprimer la mention « et aux conditions suivantes ». Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. Sinon indiquer « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. Sinon indiquer « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : [ne s’applique pas/s’applique pour les contrats indiqués dans les tableaux du Plan de passation des marchés] Travaux [ne s’applique pas/s’applique pour les contrats indiqués dans les tableaux du Plan de passation des marchés] L’Assistance directe à la mise en œuvre (sigle HEIS en anglais) tel que précisée aux paragraphes 3.10 et 3.11 du Règlement de Passation des marchés s’applique. [Inclure cette mention seulement si la Banque a formellement acceptée de fournir cette assistance directe à l’Emprunteur. Sinon, supprimer cette phrase.] Autres informations pertinentes sur la passation des marchés Indiquer toute autre information pertinente relative aux procédures de passation, telle que par exemple l’utilisation de procédures de participation communautaire au développement (CDD), de l’utilisation de procédures pour un besoin urgent d’assistance ou de faible capacité, etc. PROCUREMENT Western and Central Africa : Regional Electricity Access and BEST Project PLAN General Information Country: Western and Central Africa 2021-07-28 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167569 GPN Date: 2021-05-17 Project Name: Regional Electricity Access and BEST Project Loan / Credit No: IDA / 69030 CI-ENERGIES Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-CI-ENERGIES-236839-GO- Supervision of the constructi Pending Impl IDA / 69030 Post Direct Selection Direct 5,535.00 0.00 2021-08-26 2021-08-31 2021-09-28 2021-10-28 DIR / Acquisition de carburan on and technical advisory ementation t CI-CI-ENERGIES-236844-GO- Supervision of the constructi Request for Quota Single Stage - One E Pending Impl RFQ / Acquisition de véhicule IDA / 69030 Post Limited 92,251.00 0.00 2021-09-02 2021-10-01 2021-10-31 on and technical advisory tions nvelope ementation s pour le projet CI-CI-ENERGIES-236853-GO- Supervision of the constructi Request for Quota Single Stage - One E Pending Impl RFQ / Acquisition de matériel IDA / 69030 Post Limited 55,351.00 0.00 2021-08-24 2021-09-27 2021-10-27 on and technical advisory tions nvelope ementation s informatiques et de bureau NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-CI-ENERGIES-236855-NC- Supervision of the constructi Request for Quota Single Stage - One E Pending Impl RFQ / Polices d'assurance po IDA / 69030 Post Limited 8,856.00 0.00 2021-10-28 2021-11-25 2023-05-01 on and technical advisory tions nvelope ementation ur les véhicules CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-CI-ENERGIES-236834-CS-L Supervision of the constructi Least Cost Selecti Under Implement CS / Consultant -Firme pour l' IDA / 69030 Post Open - National 29,520.00 0.00 2021-08-23 2023-02-20 2021-09-06 2021-09-20 2021-10-18 2021-11-01 2021-12-06 2021-12-27 2022-01-26 on and technical advisory on ation audit financier et comptable du projet INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-CI-ENERGIES-236821-CS-I Supervision of the constructi Individual Consult Pending Impleme NDV / Consultant individuel e IDA / 69030 Post Open 50,000.00 0.00 2021-07-20 2021-08-17 2021-08-31 2021-09-09 2026-12-31 on and technical advisory ant Selection ntation n Environnement CI-CI-ENERGIES-236824-CS-I Supervision of the constructi Individual Consult Pending Impleme NDV / Consultant individuel e IDA / 69030 Post Open 50,000.00 0.00 2021-07-20 2021-08-17 2021-08-31 2021-09-09 2026-12-31 on and technical advisory ant Selection ntation n Violence basée sur le Genr e CI-CI-ENERGIES-236828-CS-I Supervision of the constructi Individual Consult Pending Impleme NDV / Consultant Individuel- IDA / 69030 Post Open 50,000.00 0.00 2021-07-26 2021-08-23 2021-09-06 2021-09-15 2027-02-25 on and technical advisory ant Selection ntation Affaires sociales CI-CI-ENERGIES-316564-CS-I Supervision of the constructi Individual Consult Under Implement NDV / Recrutement d'un nou IDA / 69030 Post Open - National 4,000.00 0.00 2022-09-19 2022-10-05 2022-10-13 2022-12-20 2022-10-18 2022-10-27 2023-10-22 on and technical advisory ant Selection ation veau spécialiste en passation de marchés CI-CI-ENERGIES-363510-CS-I NDV / Recrutement d' un exp Project coordination and tec Individual Consult Open - Internationa Under Implement IDA / 69030 Post 39,442.00 0.00 2023-06-05 2023-06-02 2023-07-24 2023-08-14 2023-09-18 2024-03-16 ert technologie de stockage hnical assistance ant Selection l ation d' énergie par batterie Page 1 PROCUREMENT PLAN (Textual Part) Project information: Nigeria - M & E Support for NFWP (P177941) Project Implementation agency: Diadem Consult Date of the Procurement Plan: December 12, 2022 Period covered by this Procurement Plan: January 2023 – June 2024 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Nigeria Public Procurement Act 2007, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. – Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables – Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: - Not Applicable Works: - Not Applicable PROCUREMENT Nigeria : M&E Support for NFWP PLAN General Information Country: Nigeria 2023-01-03 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P177941 GPN Date: Project Name: M&E Support for NFWP Loan / Credit No: / , TF / B9785 M and E Support for NFWP Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-M AND E SUPPORT-3275 18-GO-RFQ / Purchase of trai Component 1: M&E System Request for Quota Single Stage - One E / Post Limited 8,690.00 0.00 Canceled 2022-12-17 2023-02-11 2023-08-10 ning materials (Branded Jotte Development and Support tions nvelope rs, pen and flip charts etc.) NG-M AND E SUPPORT-3312 Component 3: Capacity Buil 58-GO-RFQ / Purchase and br Request for Quota Single Stage - One E / ding, Knowledge Manageme Post Limited 55,961.07 0.00 Canceled 2023-10-20 2023-12-15 2024-12-31 anding of conference materia tions nvelope nt, Sharing and Learning ls for annual NFWP knowledg e sharing event NG-M AND E SUPPORT-3660 35-GO-RFQ / Large screen s Component 1: M&E System Request for Quota Single Stage - One E Pending Impl mart TV for internal data de TF / B9785 Post Limited 3,200.00 0.00 2023-08-30 2023-10-25 2024-04-22 Development and Support tions nvelope ementation mand and information use (D DIU) - M&E real-time monitori ng set-up. NG-M AND E SUPPORT-3311 Component 1: M&E System Pending Impl 72-GO-DIR / Procurement of TF / B9785 Post Direct Selection Direct - National 13,500.00 0.00 2023-12-29 2024-01-03 2024-02-07 2024-08-05 Development and Support ementation STATA statistical software NG-M AND E SUPPORT-3311 Component 1: M&E System Pending Impl 87-GO-DIR / Procurement of TF / B9785 Post Direct Selection Direct - National 1,500.00 0.00 2023-12-29 2024-01-03 2024-02-07 2024-08-05 Development and Support ementation NVIVO qualitative software. NG-M AND E SUPPORT-3661 Component 1: M&E System Pending Impl 02-GO-DIR / Procurement of TF / B9785 Post Direct Selection Direct - National 3,700.00 0.00 2023-12-29 2024-01-03 2024-02-07 2024-08-05 Development and Support ementation Power BI Quantitative Softwa re NG-M AND E SUPPORT-3661 Component 1: M&E System Pending Impl 05-GO-DIR / Procurement of TF / B9785 Post Direct Selection Direct - National 910.00 0.00 2023-12-29 2024-01-03 2024-02-07 2024-08-05 Development and Support ementation CANVA software NG-M AND E SUPPORT-3311 16-GO-RFQ / Purchase of prin ter, laptops, accessories (opti Component 1: M&E System Request for Quota Single Stage - One E Pending Impl cal mouse, headset, external TF / B9785 Post Limited 52,910.00 0.00 2023-08-27 2023-10-22 2024-04-19 Development and Support tions nvelope ementation hard drive and internet route rs), antivirus for multiple use rs and office 365 software for project staff and laptop bags for staff NG-M AND E SUPPORT-3667 Component 2: Iterative Bene Request for Quota Single Stage - One E Pending Impl 84-GO-RFQ / Tablets for IBM TF / B9785 ficiary Monitoring and Respo Post Limited 8,000.00 0.00 2023-08-25 2023-10-20 2024-04-17 tions nvelope ementation setup nsive Feedback Mechanism NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-M AND E SUPPORT-3312 Component 3: Capacity Buil 25-GO-RFQ / Engagement of Request for Quota Single Stage - One E Pending Impl TF / B9785 ding, Knowledge Manageme Post Limited 40,500.00 0.00 2023-12-23 2024-02-17 2025-06-24 firm for printing of factsheet tions nvelope ementation nt, Sharing and Learning and knowledge products NG-M AND E SUPPORT-3311 Component 2: Iterative Bene Request for Quota Single Stage - One E 45-NC-RFQ / Engagement of I / ficiary Monitoring and Respo Post Limited 12,165.45 0.00 Canceled 2023-02-11 2023-04-08 2024-12-31 tions nvelope T maintenance firm nsive Feedback Mechanism NG-M AND E SUPPORT-3311 Component 2: Iterative Bene Request for Quota Single Stage - One E 27-NC-RFQ / Set up of Client / ficiary Monitoring and Respo Post Limited 59,620.00 0.00 Canceled 2023-01-21 2023-03-18 2023-09-14 tions nvelope Response Mechanism (CRM) nsive Feedback Mechanism NG-M AND E SUPPORT-3311 Component 2: Iterative Bene 97-NC-RFB / Call cost for Iter Request for Quota Single Stage - One E Pending Impl TF / B9785 ficiary Monitoring and Respo Post Limited 120,000.00 0.00 2023-12-05 2024-01-30 2024-07-28 ative Beneficiary Monitoring ( tions nvelope ementation nsive Feedback Mechanism IBM) - Engagement of firm CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-M AND E SUPPORT-3660 37-CS-CQS / Engagement of Component 1: M&E System Consultant Qualifi Pending Impleme TF / B9785 Post Limited 17,000.00 0.00 2023-12-31 2024-01-14 2024-02-13 2024-03-19 2024-09-15 a firm for external audit in ye Development and Support cation Selection ntation ar 2023 and 2024 INDIVIDUAL CONSULTANTS Page 1 Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-M AND E SUPPORT-3312 Component 3: Capacity Buil Individual Consult 42-CS-INDV / Engagement of / ding, Knowledge Manageme Post Limited 75,912.41 0.00 Canceled 2022-12-18 2022-12-23 2023-01-13 2023-02-17 2023-08-16 ant Selection RM&E Advisor - FCT nt, Sharing and Learning NG-M AND E SUPPORT-3312 Component 3: Capacity Buil Individual Consult 48-CS-INDV / Engagement of / ding, Knowledge Manageme Post Limited 75,912.41 0.00 Canceled 2022-12-18 2023-01-09 2022-12-23 2023-01-13 2023-02-17 2024-12-31 ant Selection RM&E Advisor-Taraba nt, Sharing and Learning NG-M AND E SUPPORT-3312 Component 3: Capacity Buil Individual Consult 50-CS-INDV / Engagement of / ding, Knowledge Manageme Post Limited 75,912.41 0.00 Canceled 2022-12-18 2023-01-09 2022-12-23 2023-01-13 2023-02-17 2024-12-31 ant Selection RM&E Advisor-Akwa Ibom nt, Sharing and Learning NG-M AND E SUPPORT-3312 Component 3: Capacity Buil Individual Consult 53-CS-INDV / Engagement of / ding, Knowledge Manageme Post Limited 75,912.41 0.00 Canceled 2022-12-18 2023-01-09 2022-12-23 2023-01-13 2023-02-17 2024-12-31 ant Selection RM&E Advisor-Abia nt, Sharing and Learning NG-M AND E SUPPORT-3312 Component 3: Capacity Buil Individual Consult 55-CS-INDV / Engagement of / ding, Knowledge Manageme Post Limited 75,912.41 0.00 Canceled 2022-12-18 2023-01-09 2022-12-23 2023-01-13 2023-02-17 2024-12-31 ant Selection RM&E Advisor-Ogun nt, Sharing and Learning NG-M AND E SUPPORT-3312 Component 3: Capacity Buil Individual Consult 56-CS-INDV / Engagement of / ding, Knowledge Manageme Post Limited 75,912.41 0.00 Canceled 2022-12-18 2023-01-09 2022-12-23 2023-01-13 2023-02-17 2024-12-31 ant Selection RM&E Advisor-Niger nt, Sharing and Learning NG-M AND E SUPPORT-3312 Component 3: Capacity Buil Individual Consult 57-CS-INDV / Engagement of / ding, Knowledge Manageme Post Limited 75,912.41 0.00 Canceled 2022-12-18 2023-01-09 2022-12-23 2023-01-13 2023-02-17 2023-08-16 ant Selection RM&E Advisor-Kebbi nt, Sharing and Learning NG-M AND E SUPPORT-3634 71-CS-INDV / Engagement of Assessor for the Inception Re Component 1: M&E System Individual Consult Under Implement TF / B9785 Post Limited 950.00 0.00 2023-06-12 2023-06-02 2023-06-17 2023-06-05 2023-07-08 2023-06-14 2023-08-12 2024-02-08 connaissance (RECKI) and Mo Development and Support ant Selection ation nitoring and Evaluation and S ystem Strengthening Assess ment (MESSA): Niger State - A NG-M AND E SUPPORT-3634 80-CS-INDV / Engagement of Assessor for the Inception Re Component 1: M&E System Individual Consult Under Implement TF / B9785 Post Limited 950.00 0.00 2023-06-12 2023-06-02 2023-06-17 2023-06-05 2023-07-08 2023-06-14 2023-08-12 2024-02-08 connaissance (RECKI) and Mo Development and Support ant Selection ation nitoring and Evaluation and S ystem Strengthening Assess ment (MESSA): Niger State - B NG-M AND E SUPPORT-3634 82-CS-INDV / Engagement of Assessor for the Inception Re Component 1: M&E System Individual Consult Under Implement TF / B9785 Post Limited 950.00 0.00 2023-06-12 2023-06-02 2023-06-17 2023-06-05 2023-07-08 2023-06-14 2023-08-12 2024-02-08 connaissance (RECKI) and Mo Development and Support ant Selection ation nitoring and Evaluation and S ystem Strengthening Assess ment (MESSA): Ogun State - A NG-M AND E SUPPORT-3634 84-CS-INDV / Engagement of Assessor for the Inception Re Component 1: M&E System Individual Consult Under Implement TF / B9785 Post Limited 950.00 0.00 2023-06-12 2023-06-02 2023-06-17 2023-06-05 2023-07-08 2023-06-14 2023-08-12 2024-02-08 connaissance (RECKI) and Mo Development and Support ant Selection ation nitoring and Evaluation and S ystem Strengthening Assess ment (MESSA): Ogun State - B NG-M AND E SUPPORT-3634 85-CS-INDV / Engagement of Assessor for the Inception Re Component 1: M&E System Individual Consult Under Implement TF / B9785 Post Limited 950.00 0.00 2023-06-12 2023-06-02 2023-06-17 2023-06-05 2023-07-08 2023-06-14 2023-08-12 2024-02-08 connaissance (RECKI) and Mo Development and Support ant Selection ation nitoring and Evaluation and S ystem Strengthening Assess ment (MESSA): Abia State - A NG-M AND E SUPPORT-3634 87-CS-INDV / Engagement of Assessor for the Inception Re Component 1: M&E System Individual Consult Under Implement TF / B9785 Post Limited 950.00 0.00 2023-06-12 2023-06-02 2023-06-17 2023-06-05 2023-07-08 2023-08-12 2024-02-08 connaissance (RECKI) and Mo Development and Support ant Selection ation nitoring and Evaluation and S ystem Strengthening Assess ment (MESSA): Abia State - B NG-M AND E SUPPORT-3635 16-CS-INDV / Engagement of Assessor for the Inception Re Component 1: M&E System Individual Consult Under Implement TF / B9785 Post Limited 950.00 0.00 2023-06-12 2023-06-02 2023-06-17 2023-06-05 2023-07-08 2023-06-14 2023-08-12 2024-02-08 connaissance (RECKI) and Mo Development and Support ant Selection ation nitoring and Evaluation and S ystem Strengthening Assess ment (MESSA): Kebbi State - A NG-M AND E SUPPORT-3635 17-CS-INDV / Engagement of Assessor for the Inception Re Component 1: M&E System Individual Consult Under Implement TF / B9785 Post Limited 950.00 0.00 2023-06-12 2023-06-02 2023-06-17 2023-06-05 2023-07-08 2023-06-14 2023-08-12 2024-02-08 connaissance (RECKI) and Mo Development and Support ant Selection ation nitoring and Evaluation and S ystem Strengthening Assess ment (MESSA): Kebbi State - B NG-M AND E SUPPORT-3635 18-CS-INDV / Engagement of Assessor for the Inception Re Component 1: M&E System Individual Consult Under Implement connaissance (RECKI) and Mo TF / B9785 Post Limited 950.00 0.00 2023-06-12 2023-06-02 2023-06-17 2023-06-05 2023-07-08 2023-06-14 2023-08-12 2024-02-08 Development and Support ant Selection ation nitoring and Evaluation and S ystem Strengthening Assess ment (MESSA): Taraba State -A NG-M AND E SUPPORT-3635 19-CS-INDV / Engagement of Assessor for the Inception Re Component 1: M&E System Individual Consult Under Implement connaissance (RECKI) and Mo TF / B9785 Post Limited 950.00 0.00 2023-06-12 2023-06-02 2023-06-17 2023-06-05 2023-07-08 2023-06-14 2023-08-12 2024-02-08 Development and Support ant Selection ation nitoring and Evaluation and S ystem Strengthening Assess ment (MESSA): Taraba State -B NG-M AND E SUPPORT-3635 20-CS-INDV / Engagement of Assessor for the Inception Re Component 1: M&E System Individual Consult Under Implement connaissance (RECKI) and Mo TF / B9785 Post Limited 950.00 0.00 2023-06-12 2023-06-02 2023-06-17 2023-06-05 2023-07-08 2023-06-14 2023-08-12 2024-02-08 Development and Support ant Selection ation nitoring and Evaluation and S ystem Strengthening Assess ment (MESSA): Akwa Ibom St ate - A Page 2 NG-M AND E SUPPORT-3635 22-CS-INDV / Engagement of Assessor for the Inception Re Component 1: M&E System Individual Consult Under Implement connaissance (RECKI) and Mo TF / B9785 Post Limited 950.00 0.00 2023-06-12 2023-06-02 2023-06-17 2023-06-05 2023-07-08 2023-06-14 2023-08-12 2024-02-08 Development and Support ant Selection ation nitoring and Evaluation and S ystem Strengthening Assess ment (MESSA): Akwa Ibom St ate - B NG-M AND E SUPPORT-3312 16-CS-INDV / Engagement of Component 3: Capacity Buil Individual Consult Pending Impleme consultant to develop factshe TF / B9785 ding, Knowledge Manageme Post Limited 40,500.00 0.00 2023-12-10 2023-12-15 2024-01-05 2024-02-09 2024-08-07 ant Selection ntation ets for data review meeting, nt, Sharing and Learning data analysis and developme nt of knowledge products NG-M AND E SUPPORT-3663 10-CS-INDV / Engagement of Component 1: M&E System Individual Consult Under Implement TF / B9785 Post Limited 2,300.00 0.00 2023-08-31 2023-06-16 2023-09-05 2023-06-20 2023-09-26 2023-10-31 2024-04-28 research, monitoring and eva Development and Support ant Selection ation luation consultant - Qualitativ e Data Analyst NG-M AND E SUPPORT-3633 Component 1: M&E System Individual Consult 93-CS-INDV / Engagement of TF / B9785 Post Limited 16,600.00 0.00 Canceled 2023-06-26 2023-06-07 2023-07-01 2023-07-22 2023-08-26 2024-02-22 Development and Support ant Selection IT Programmer/Database Ma nager NG-M AND E SUPPORT-3663 58-CS-INDV / Engagement of Component 1: M&E System Individual Consult Under Implement TF / B9785 Post Limited 81,600.00 0.00 2023-08-31 2023-06-16 2023-09-05 2023-06-19 2023-09-26 2023-10-31 2024-04-28 IT Programmer/Database Ma Development and Support ant Selection ation nager for Pilot DVE and set u p of IBM system. Page 3 PROCUREMENT PLAN (Textual Part) Project information: GUYANA – GUYANA COVID – 19 EMERGENCY RESPONSE PROJECT – ID No. P175268 Project Implementation agency: Ministry of Health Date of the Procurement Plan: April 9, 2021 Period covered by this Procurement Plan: April – December 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used, in which case the Bank will have to be satisfied that the procurement procedures and bidding documents are acceptable to the Bank When the Borrower uses its own national open competitive procurement arrangements as set forth in Guyana Procurement Act 2003, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations, in which case the Bank will have to be satisfied that the procurement procedures and bidding documents are acceptable to the Bank. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations, in which case the Bank will have to be satisfied that the procurement procedures and bidding documents are acceptable to the Bank. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works): Not Applicable Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information: Not Applicable. PROCUREMENT Guyana : Guyana COVID-19 Emergency Response Project PLAN General Information Country: Guyana 2021-04-15 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175268 GPN Date: 2021-05-19 Project Name: Guyana COVID-19 Emergency Response Project Loan / Credit No: IDA / 68020, TF / B6163, IDA / 69750 Guyana COVID-19 FTO Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GY-G-COVID FTO-228610-GO Component 1. Emergency R Request for Quota Single Stage - One E Pending Impl -RFQ / Supply and Delivery of IDA / 68020 Post Open - National 202,712.00 0.00 2021-05-07 2021-07-02 2021-12-29 esponse to COVID-19 tions nvelope ementation Laboratory Equipment GY-G-COVID FTO-228612-GO Component 1. Emergency R Request for Quota Single Stage - One E Pending Impl -RFQ / Supply and Delivery of IDA / 68020 Post Open - National 373,000.00 0.00 2021-05-07 2021-07-02 2021-12-29 esponse to COVID-19 tions nvelope ementation Laboratory Supplies GY-G-COVID FTO-228615-GO Component 1. Emergency R Request for Quota Single Stage - One E Pending Impl -RFQ / Supply and Delivery of IDA / 68020 Post Open - National 15,400.00 0.00 2021-05-22 2021-07-17 2022-01-13 esponse to COVID-19 tions nvelope ementation Refrigerators(B) GY-G-COVID FTO-228616-GO Component 1. Emergency R Request for Quota Single Stage - One E Pending Impl -RFQ / Supply and Delivery of IDA / 68020 Post Open - National 35,200.00 0.00 2021-05-22 2021-07-17 2022-01-13 esponse to COVID-19 tions nvelope ementation Freezers (C ) GY-G-COVID FTO-228620-GO -RFQ / Supply and Delivery of Component 1. Emergency R Request for Quota Single Stage - One E IDA / 68020 Post Open - National 40,000.00 46,271.47 Signed 2021-05-31 2021-07-26 2021-10-30 2022-01-22 One Motor Vehicle (4x4 Doub esponse to COVID-19 tions nvelope le Cab Pick Up Type Vehicle) GY-G-COVID FTO-228623-GO Component 1. Emergency R Request for Quota Single Stage - One E -RFQ / Supply and Delivery of IDA / 68020 Post Open - National 125,000.00 189,236.86 Signed 2021-06-12 2021-08-12 2021-08-07 2022-01-26 2022-02-03 esponse to COVID-19 tions nvelope All Terrain Vehicles (ATV's) GY-G-COVID FTO-228624-GO Component 1. Emergency R Request for Quota Single Stage - One E Under Imple -RFQ / Supply and Delivery of IDA / 68020 Post Open - National 75,000.00 0.00 2021-05-30 2021-11-16 2021-07-25 2022-01-21 esponse to COVID-19 tions nvelope mentation One Cold Storage Truck GY-G-COVID FTO-228627-GO -RFQ / Supply and Delivery of Component 1. Emergency R Request for Quota Single Stage - One E IDA / 68020 Post Open - National 100,000.00 110,813.99 Completed 2021-05-15 2021-06-24 2021-07-10 2021-10-10 2022-01-06 2022-02-12 Computers, Tablets, Servers esponse to COVID-19 tions nvelope and Accessories GY-G-COVID FTO-228614-GO Component 1. Emergency R Request for Quota Single Stage - One E Pending Impl -RFQ / Supply and Delivery of IDA / 68020 Post Open - National 121,990.00 0.00 2021-05-15 2021-07-10 2022-01-06 esponse to COVID-19 tions nvelope ementation Hospital Supplies GY-G-COVID FTO-228622-GO -RFQ / Supply and Delivery of Component 1. Emergency R Request for Quota Single Stage - One E Under Imple IDA / 68020 Post Open - National 125,000.00 0.00 2021-06-19 2022-04-08 2021-08-14 2022-02-10 Two (2) Aluminum Boats Wi esponse to COVID-19 tions nvelope mentation th 40 HP Engines GY-G-COVID FTO-228613-GO Component 1. Emergency R UN Agencies (Dire -UN / Supply and Delivery of IDA / 68020 Post Direct 1,699,888.00 0.00 Canceled 2021-05-24 2021-05-29 2021-07-03 2021-12-30 esponse to COVID-19 ct) Hospital Equipment GY-G-COVID FTO-278175-GO Component 1. Emergency R Pending Impl -DIR / Supply and Delivery of IDA / 68020 Post Direct Selection Direct 210,000.00 0.00 2021-10-15 2021-10-20 2021-11-24 2022-05-23 esponse to COVID-19 ementation Hospital Beds GY-G-COVID FTO-278186-GO Component 1. Emergency R Pending Impl -DIR / Supply and Delivery of IDA / 68020 Post Direct Selection Direct 140,000.00 0.00 2021-10-15 2021-10-20 2021-11-24 2022-05-23 esponse to COVID-19 ementation Laryngoscope GY-G-COVID FTO-278187-GO -DIR / Supply and Delivery of Component 1. Emergency R Pending Impl Infusion Pumps, Syringe Pum IDA / 68020 Post Direct Selection Direct 405,000.00 0.00 2021-10-15 2021-10-20 2021-11-24 2022-05-23 esponse to COVID-19 ementation ps, Vital Signs Monitor, Defibr illator and Physiologic monito r GY-G-COVID FTO-278161-GO Component 1. Emergency R Pending Impl -DIR / Supply and Delivery of IDA / 68020 Post Direct Selection Direct 900,000.00 0.00 2021-10-15 2021-10-20 2021-11-24 2022-05-23 esponse to COVID-19 ementation Ventilators and Ultrasound M achines GY-G-COVID FTO-278132-GO Component 1. Emergency R -DIR / Supply and Delivery of IDA / 68020 Post Direct Selection Direct 40,000.00 37,110.00 Signed 2021-10-15 2021-11-09 2021-10-20 2021-11-22 2021-11-24 2022-01-08 2022-05-23 esponse to COVID-19 Ventilators GY-G-COVID FTO-278171-GO Component 1. Emergency R Pending Impl -DIR / Supply and Delivery of IDA / 68020 Post Direct Selection Direct 40,000.00 0.00 2021-10-15 2021-10-20 2021-11-24 2022-05-23 esponse to COVID-19 ementation Suction Units GY-G-COVID FTO-281188-GO Component 1. Emergency R Pending Impl -DIR / Supply and Delivery of IDA / 68020 Post Direct Selection Direct 7,000.00 0.00 2021-10-15 2021-10-20 2021-11-24 2022-05-23 esponse to COVID-19 ementation Laryngoscopes and Otoscope s GY-G-COVID FTO-278196-GO Component 1. Emergency R Pending Impl -DIR / Supply and Delivery of IDA / 68020 Post Direct Selection Direct 40,000.00 0.00 2021-10-15 2021-10-20 2021-11-24 2022-05-23 esponse to COVID-19 ementation Oxygen Concentrator and Ve ntilator GY-G-COVID FTO-278202-GO Component 1. Emergency R Pending Impl -DIR / Supply and Delivery of IDA / 68020 Post Direct Selection Direct 340,000.00 0.00 2021-10-15 2021-10-20 2021-11-24 2022-05-23 esponse to COVID-19 ementation X-ray machine Page 1 GY-G-COVID FTO-278205-GO Component 1. Emergency R Pending Impl -DIR / Supply and Delivery of IDA / 68020 Post Direct Selection Direct 30,000.00 0.00 2021-10-15 2021-10-20 2021-11-24 2022-05-23 esponse to COVID-19 ementation Humidifiers and Accessories GY-G-COVID FTO-278942-GO Component 1. Emergency R -DIR / Supply and Delivery of IDA / 68020 Post Direct Selection Direct 150,000.00 131,868.11 Signed 2022-02-10 2022-02-15 2022-02-15 2022-02-01 2022-03-22 2022-04-12 2022-09-18 esponse to COVID-19 2 No. Road Ambulances GY-G-COVID FTO-281199-GO Component 1. Emergency R Single Stage - One E Pending Impl -RFB / Supply and Delivery of IDA / 68020 Post Request for Bids Open - National 75,000.00 0.00 2022-03-29 2022-04-03 2022-05-15 2022-06-14 2022-07-19 2023-01-15 esponse to COVID-19 nvelope ementation One Infectious Waste Dispos al Vehicle GY-G-COVID FTO-281196-GO Component 1. Emergency R Request for Quota Single Stage - One E Under Imple -RFQ / Supply and Delivery of IDA / 68020 Post Open - National 100,000.00 0.00 2022-03-27 2022-04-08 2022-05-22 2022-11-18 esponse to COVID-19 tions nvelope mentation One 4x4 Motor Vehicle GY-G-COVID FTO-296098-GO Component 1. Emergency R -DIR / Supply and Delivery of IDA / 69750 Post Direct Selection Direct 1,500,000.00 0.00 Signed 2021-05-15 2021-06-11 2021-05-20 2021-06-03 2021-06-24 2021-12-21 esponse to COVID-19 COVID-19 Vaccines GY-G-COVID FTO-228629-GO Component 1. Emergency R Request for Quota Single Stage - One E -RFQ / Supply and Delivery of IDA / 68020 Post Open - National 150,000.00 0.00 Canceled 2021-08-20 2021-10-15 2022-04-13 esponse to COVID-19 tions nvelope Cloth Masks GY-G-COVID FTO-228617-GO Component 1. Emergency R Request for Quota Single Stage - One E -RFQ / Supply and Delivery of IDA / 68020 Post Open - National 24,970.00 0.00 Canceled 2021-05-11 2021-07-06 2022-01-02 esponse to COVID-19 tions nvelope Quarantine equipment GY-G-COVID FTO-228626-GO -RFQ / Supply and Delivery of Component 1. Emergency R Request for Quota Single Stage - One E IDA / 68020 Post Open - National 28,000.00 0.00 Canceled 2021-05-31 2021-07-26 2022-01-22 Eight Isolation Pods for trans esponse to COVID-19 tions nvelope porting COVID-19 patients GY-G-COVID FTO-228625-GO Component 1. Emergency R Request for Quota Single Stage - One E -RFQ / Supply and Delivery of IDA / 68020 Post Open - National 4,800.00 0.00 Canceled 2021-05-21 2021-07-16 2022-01-12 esponse to COVID-19 tions nvelope Twelve Bicycles GY-G-COVID FTO-228618-GO Component 1. Emergency R Request for Quota Single Stage - One E -RFQ / Supply and Delivery of IDA / 68020 Post Open - National 8,000.00 0.00 Canceled 2022-04-16 2022-06-11 2022-12-08 esponse to COVID-19 tions nvelope Waste Receptacle for Schools GY-G-COVID FTO-228628-GO Component 1. Emergency R Request for Quota Single Stage - One E -RFQ / Supply and Delivery of IDA / 68020 Post Open - National 286,000.00 0.00 Canceled 2021-05-29 2021-07-24 2022-01-20 esponse to COVID-19 tions nvelope IT Software GY-G-COVID FTO-325831-GO Component 1. Emergency R Direct - Internation Pending Impl -DIR / Supply and Delivery of IDA / 68020 Post Direct Selection 4,000,000.00 0.00 2021-06-15 2021-06-20 2021-07-25 2022-01-21 esponse to COVID-19 al ementation Additional Hospital Equipmen t GY-G-COVID FTO-228619-GO -UN / Supply and Delivery of Component 1. Emergency R Request for Quota Open - Internationa Single Stage - One E Pending Impl IDA / 68020 Post 225,000.00 0.00 2022-03-05 2022-04-30 2022-10-27 (3) Ambulances, 1 Road and esponse to COVID-19 tions l nvelope ementation 2 off road ambulances GY-G-COVID FTO-325830-GO Component 1. Emergency R Direct - Internation Pending Impl -DIR / Supply and Delivery of IDA / 68020 Post Direct Selection 400,000.00 0.00 2021-03-15 2021-03-20 2021-04-24 2021-10-21 esponse to COVID-19 al ementation Cold Chain Equipment GY-G-COVID FTO-362338-GO Component 1. Emergency R Single Stage - One E Pending Impl -RFB / Procurement of Dental IDA / 69750 Post Request for Bids Open - National 315,000.00 0.00 2023-05-21 2023-05-26 2023-07-07 2023-08-06 2023-09-10 2023-12-09 esponse to COVID-19 nvelope ementation Equipment GY-G-COVID FTO-362350-GO Component 1. Emergency R Open - Internationa Single Stage - One E Pending Impl -RFB / Procurement of Spiro IDA / 69750 Post Request for Bids 220,000.00 0.00 2023-05-21 2023-05-26 2023-07-07 2023-08-06 2023-09-10 2023-12-09 esponse to COVID-19 l nvelope ementation metry Equipment and Access ories GY-G-COVID FTO-362356-GO Component 1. Emergency R Open - Internationa Single Stage - One E Pending Impl -RFB / Procurement of Equip IDA / 69750 Post Request for Bids 400,000.00 0.00 2023-05-21 2023-05-26 2023-07-07 2023-08-06 2023-09-10 2023-12-09 esponse to COVID-19 l nvelope ementation ment for Simulation Lab and Centre GY-G-COVID FTO-362355-GO Component 1. Emergency R Request for Quota Single Stage - One E Pending Impl -RFB / Procurement of Eye Ca IDA / 69750 Post Open - National 100,000.00 0.00 2023-06-05 2023-07-31 2023-10-29 esponse to COVID-19 tions nvelope ementation re Equipment GY-G-COVID FTO-361592-GO Component 1. Emergency R Direct - Internation Under Revie -DIR / Procurement of Pathol IDA / 69750 Prior Direct Selection 2,140,000.00 0.00 2023-05-15 2023-06-07 2023-05-20 2023-06-21 2023-06-24 2023-12-21 esponse to COVID-19 al w ogy Equipment NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3. Supporting N GY-G-COVID FTO-286132-NC ational and Sub-national, Pre Direct - Internation Pending Impl TF / B6163 Post Direct Selection 150,000.00 0.00 2022-08-09 2022-08-14 2022-09-18 2023-03-17 -RFQ / One Health Training vention and Preparedness a al ementation nd Health System Resilience CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3. Supporting N GY-G-COVID FTO-285818-CS ational and Sub-national, Pre Consultant Qualifi Under Implement -CDS / National Focal Point C TF / B6163 Post Open - National 60,000.00 0.00 2022-03-22 2022-03-25 2022-04-12 2022-05-26 2022-06-25 2022-07-30 2023-01-26 vention and Preparedness a cation Selection ation onsulancy nd Health System Resilience INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 GY-G-COVID FTO-228632-CS Component 2. Implementati Pending Impleme IDA / 68020 Post Direct Selection Direct 4,221.00 0.00 2021-05-10 2021-05-20 2021-07-24 2022-01-20 -CDS / Health Systems Speci on Management and M&E ntation alist GY-G-COVID FTO-228633-CS Component 2. Implementati Pending Impleme IDA / 68020 Post Direct Selection Direct 4,221.00 0.00 2021-04-09 2021-04-19 2021-06-23 2021-12-20 -CDS / Procurement Specialis on Management and M&E ntation t GY-G-COVID FTO-228634-CS Component 2. Implementati Individual Consult Pending Impleme IDA / 68020 Post Open 26,355.00 0.00 2021-05-02 2021-06-20 2021-07-11 2021-08-15 2022-02-11 -INDV / Procurement Assistan on Management and M&E ant Selection ntation t GY-G-COVID FTO-228635-CS Component 2. Implementati Individual Consult IDA / 68020 Post Open 28,237.00 26,264.84 Completed 2021-05-02 2021-06-15 2021-06-20 2021-07-12 2021-07-11 2021-07-21 2021-08-15 2021-08-10 2022-02-11 2022-02-15 -INDV / Finance Officer on Management and M&E ant Selection GY-G-COVID FTO-228636-CS Component 2. Implementati Individual Consult Pending Impleme IDA / 68020 Post Direct 2,014.00 0.00 2021-04-09 2021-04-19 2021-05-10 2021-06-14 2021-12-11 -INDV / M&E Specialist on Management and M&E ant Selection ntation GY-G-COVID FTO-228637-CS Component 2. Implementati Individual Consult Under Implement IDA / 68020 Post Open 18,825.00 0.00 2021-04-09 2021-05-03 2021-05-28 2021-12-15 2021-06-18 2021-07-23 2022-01-19 -INDV / E&S Specialist on Management and M&E ant Selection ation GY-G-COVID FTO-228638-CS -INDV / Social Consultant to C Component 2. Implementati Individual Consult Pending Impleme IDA / 68020 Post Open 12,000.00 0.00 2021-06-07 2021-07-26 2021-08-16 2021-09-20 2022-03-19 onduct Seminars on Domesti on Management and M&E ant Selection ntation cs Violence , Childs Abuse et c. Component 3. Supporting N GY-G-COVID FTO-286130-CS ational and Sub-national, Pre Pending Impleme -CDS / Joint External Evaluati TF / B6163 Post Direct Selection Direct 150,000.00 0.00 2022-03-31 2022-04-10 2022-06-14 2022-12-11 vention and Preparedness a ntation on nd Health System Resilience Component 3. Supporting N GY-G-COVID FTO-286131-CS ational and Sub-national, Pre Pending Impleme -CDS / Performance Veterinar TF / B6163 Post Direct Selection Direct 150,000.00 0.00 2022-04-26 2022-05-06 2022-07-10 2023-01-06 vention and Preparedness a ntation y Service nd Health System Resilience GY-G-COVID FTO-358791-CS Component 2. Implementati Pending Impleme -CDS / Hire of Part-time Proc IDA / 68020 Post Direct Selection Direct - National 1,500.00 0.00 2023-04-26 2023-04-28 2023-05-01 2023-06-30 on Management and M&E ntation urement Specialist Page 3 Stratégie de Passation des Marchés pour le Développement (PPSD) du Projet de Préparation à REDD+ 1. RESUME DU PROJET Pays Burkina Faso Nom du Projet Don de préparation à la REDD+ Financement $ 6.87 millions total $ Numéro Projet P156827 2. 0 PRESENTATION GENERALE DU PROJET 2.1 RESUME DES OBJECTIFS La Réduction des Emissions résultant de la Déforestation et de la Dégradation des forêts (REDD+) est un Processus qui vise simultanément à atténuer les changements climatiques grâce à la conservation des forêts et à promouvoir le développement durable. Le principe de la REDD+ consiste à fournir des ressources financières aux pays forestiers qui réduisent les émissions de gaz à effet de serre (GES) dues à la déforestation et à la dégradation des forêts et/ou renforcent les stocks de carbone forestier. Le Plan de préparation à la REDD+ (R-PP) du Burkina a été approuvé en 2013 par le Comité des participants du Fonds de préparation du FCPF. Cette approbation a permis au Burkina Faso d'accéder à des ressources pour sa mise en œuvre (3.8 millions de dollars). En 2018, le don accordé au Burkina Faso a été revu de 3.8 millions dollars à 6, 87 millions de dollars. Cette extension a permis de lancer de nouvelles activités. La subvention du Fonds de Partenariat pour le Carbone Forestier (FCPF) au gouvernement du Burkina Faso est acheminée par le biais de la Banque Mondiale (BM) et est utilisée pour soutenir les activités de préparation à la REDD+ liées notamment à l'obtention de résultats clés: l'élaboration d'une stratégie nationale REDD+ et l'évaluation environnementale et sociale associée à la stratégie, un niveau national d'émissions de référence forestières, un système de suivi des forêts solide et transparent, un mécanisme de gestion des plaintes et des recours ainsi qu'un système d'information sur la manière dont les garanties sont prises en compte et respectées. Le processus REDD+ est ancré, au plan institutionnel, à la Direction Générale de l’Economie Verte et du Changement Climatique (DGEVCC) et l’élaboration de la Stratégie Nationale REDD+ se fait sous la coordination du Programme d’Investissement Forestier (PIF) à travers le Secrétariat 1 Technique National REDD+ (STN-REDD+). Le STN-REDD+ a pour objectif de construire les capacités nationales pour la mise en œuvre de la REDD+ (la préparation) d’une part, et d’autre part de développer le cadre global pour les investissements qui vont réduire les émissions issues de la déforestation et la dégradation des forêts. 2.2 Composantes du Projet Le projet fait partie d’un programme composé de quatorze (14) axes de travail. Le financement FCPF en soutient sept (7) selon la nomenclature suivante : 2.2.1: La réglementation et les stratégies sectorielles en matière de la REDD+ sont améliorées ; Cette composante comprend majoritairement des activités de formation, des ateliers et des missions, mais aussi le recrutement de consultants pour effectuer des diagnostics sectoriels. 2.2.2 Un montage organisationnel et un plan de consultation sont développés ; Cette composante comprend une grosse prestation de firme pour la réalisation des vagues de concertation dans 32 communes, des ateliers de consultation ainsi que de multiples activités de formation (ateliers). 2.2.3 La stratégie REDD+ est élaborée ; Cette composante comprend trois activités majeures : (i) l’élaboration des options stratégiques suite à une analyse des causes de la déforestation. Cette activité repose sur de nombreux contrats locaux. (ii) l’évaluation des impacts environnementaux et sociaux de niveau stratégique (EESS), confié à un cabinet de niveau international et (iii) des analyses du potentiel carbone, environnementale et socio-économique du secteur agricole et de certaines filières (beurre de karité, biodigesteurs) qui demandent des expertises pointues et rares. 2.2.4 : Des systèmes de suivi des forêts et de suivi des cobénéfices sont mis en place Cette activité est conduite par une firme recrutée par un projet de la BAD pour le volet suivi des forêts et par la Banque Mondiale pour les aspects liés aux cobénéfices. Des campagnes de collecte de données, de travaux pour l’analyse des données et de diagnostic d’outils existant par des 2 organisations spécialisées et des consultants du Burkina Faso seront nécessaires. 2.2.5 : Des mécanismes de partage des connaissances sont fonctionnels Cette composante vise à renforcer les capacités de tous les acteurs et à faire connaître l’expérience du Burkina Faso pour mobiliser de nouveaux fonds. 2.2.6 : Les mécanismes de suivi-évaluation et de gestion sont fonctionnels Il s’agit de la gestion opérationnelle du projet. 3.0 Evaluation de la capacité du client et de l’Unité de Projet Forces : La Coordination Nationale du PIF opère depuis 6 ans et gère 2 projets (Banque mondiale et BAD). Elle a maintenant une bonne expérience des pratiques des bailleurs de fonds et a pu bénéficier de nombreuses formations. Faiblesses : Les prestataires accusent beaucoup de retard dans l’exécution. Par ailleurs, des marchés ont été identifiés comme non conformes aux procédures de la Banque mondiale. Le projet a fait un commentaire sur ce rapport qui est transmis au ministère des finances. Opportunités : L’expérience acquise lors des projets PIF est un bon socle permettant d’augmenter le volume de marchés. Le projet de la BAD prend fin le 30/06/2020 et le volume de marchés à passer est très faible ce qui diminue la charge de travail du spécialiste en passation des marchés. Les structures d’appui du Ministère pour la passation des marchés comme la Direction des marchés publics (DMP) et la Direction du contrôle des marchés publics et des engagements financiers (DCMEF) entretiennent maintenant une bonne communication avec l’unité de coordination du programme pour la gestion des dossiers de passation des marchés. 4.0 Analyse du marché Un seul contrat (EESS) représente environ 20% du montant du don. Ce marché a été passé en demande de proposition (SBQC) de niveau international. Le contrat sera pris en charge sur deux fonds, le TF 015339 PGDFEB jusqu’au 31 Décembre 2020 et le TF 17919 FCPF après le 31 Décembre 2020. Le contrat de l’EESS est d’importance critique pour le 3 projet, et son exécution durera 10 mois. La procédure de sélection est déjà terminée et le contrat est en attente de signature au niveau du Ministère de l’environnement. Tous les autres marchés seront en appel d’offre ouvert de niveau national et international, sauf lorsqu’il s’agit de marchés pour une expertise très spécifique et unique. Notamment : 1. Mise en place d’un système MNV : La phase initiale de développement d’un système MNV a été réalisée par la firme AGRICONSULTING EUROPE SA (AESA) dont le contrat était supporté par le projet PGFC/REDD+ de la Banque Africaine de Développement. Afin d’assurer la cohérence et l’efficacité, AESA sera de nouveau sollicitée pour la réalisation des activités résiduelles de mise en place du système MNV financées par le TF 17919 FCPF. 2. Appui au processus de consultation : Le processus de consultation des parties prenantes de la REDD+ est une continuité. Il s’améliore aussi avec l’accumulation de l’expérience des phases précédentes. Le consultant ayant appuyé ce processus dès sa phase initiale sera à nouveau sollicité pour la suite des consultations des parties prenantes. 3. Droit carbone : La finance carbone est un domaine encore en pleine croissance dont les principes ne sont pas toujours clairs pour ceux qui s’y aventurent. La clarification du statut du carbone dans la REDD+ nécessite ainsi une expertise spécifique et unique. La première phase de ce travail a été effectuée de manière satisfaisante avec l’appui d’un expert international. Il sera de nouveau sollicité pour la suite de ce processus. 5.0 ANALYSE DES RISQUES DE PASSATION DES MARCHES Description des Allocation des Description des risques mesures de mitigation risques Ouvrir les marchés pour Absence de compétence des candidats Faible internationaux Faiblesse des rémunérations Proposer des avantages pour attirer les plus non monétaires Modéré performants Confier le suivi des Absence de suivi des contrats (et les copies des Faible contrats contrats) aux équipes techniques Accompagner les Faible capacité technique et prestataires en leur Modéré financière des prestataires facilitant les paiements 4 Fournir les caractéristiques Retard dans la sélection des techniques et les TDRs Modéré prestataires validés dans meilleurs délais 6.0 OBJECTIF DE LA PASSATION DES MARCHES - Acquérir les biens et services dans la transparence et dans l’équité ; - Contribuer à l’atteinte des objectifs de développement assignés par le Projet ; - Avoir des prestations de qualité au meilleur coût ; - avoir les biens et services demandés dans les délais les plus brefs; - Assurer le bon emploi des ressources publiques; - Achèvement des prestations dans les délais requis. 7.0 APPROCHE RECOMMANDEE POUR LA PASSATION DES MARCHES Contrats critiques : Les contrats suivants sont d’importance critique pour le projet et doivent faire l’objet d’un suivi particulier : 1. ATI REDD+ (contrat en cours, à renouveler) 2. EESS (à réaliser en moins de 1 mois) 3. Expert technique en appui à l’EESS (contrat en cours, à renouveler) 4. IGB (contrat passé mais à suivre attentivement) Atténuation des risques identifiés : Par défaut, tous les contrats devront faire l’objet d’une mise en concurrence ouverte de niveau national. Les réceptions de matériels devront se faire avec les experts techniques. Activités de communication et impressions : Une grande quantité de documents de communication est attendue pour promouvoir le projet. Plutôt que de multiplier les contrats d’impression, il est préférable d’opter pour un contrat cadre avec une société spécialisée avec qui des prix inférieurs au marché seront négociés. 8.0 ARRANGEMENTS PREFERES POUR LES ACTIVITES DE FAIBLE VALEUR, FAIBLE RISQUE 5 Activités Catégories Coûts Arrangements de Estimés Passation de US$ Marchés Prestations de consultants Consultant Inférieurs à Consultation ouverte inférieures à 15 millions de individuel 30,000 USD FCFA Consultant Inférieurs à Recrutement similaire aux Personnel contractuel du individuel 30,000 USD consultants (ouvert), mais projet contrats de contractuels ANNEXE : PLAN DE PASSATION DES MARCHES 6 FOURNITURES ET SERVICES Date Cout Méthode Préfére Cout prévue Date de Pourcent estimés de nce Revue Source de estimés pour signature Code de age de Observati Réf. No. Description $ EU Passatio Nationa (Prior/Po financem FCFA (en l’ouvertur du l’activité financem ons (en n des le st) ent millier) e des contrat ent millier ) marchés (Oui/No offres n) Editer et imprimer un ContratCommented [BD1]: A completer guide d'élaboration et de C3.2A113 TF- cadre de 1 7 000 14 CF NON Post FCPF mise en œuvre de projets 004 17919 l’imprime et programmes REDD+ ur FCPF Contrat NON C3.2A113 Imprimer le bulletin 15 000 30/07/202 30/08/202 cadre de 30 CF Post 004 d'information REDD+ / 0 0 TF- l’imprime 2 Infos (4 numéros) 17919 ur Editer et diffuser la stratégie et le plan NON d'action genre à C3.3A123 5 000 15/05/202 15/06/202 TF- l'ensemble des acteurs 10 CF Post 0 0 FCPF 015 Contrat 17919 de mise en œuvre des cadre de activités du PIF (300 l’imprime 3 copies) ur TOTAL 27 000 54 7 SERVICES DE CONSULTANTS Examen Date préalable Date Cout Cout prévue Pourcent Méthode ou revue prévue Source de Réf. estimés en estimés pour Code de age de Description de à pour financem Observations No. FCFA (en $EU (en l'ouvertur l’activité financem sélection postériori l’attributi ent millier) millier) e des ent par la on offres Banque Consultant international pour Contrat de Commented [BD2]: A consulter C1.3A0310 1 appuyer le Point Focal et la CI 96 000 192 Postériori FCPF 13 TF-17919 l'expert REDD+ DGEVCC (à renouveler) Recrutement en Agent Secrétaire de direction du 20/05/202 20/05/202 C1.3A031 cours au niveau 2 secrétariat technique contract 4 500 9 Postériori 0 0 FCPF 015 TF-17919 de la DRH du uel ministère Recruter une firme pour rédiger un document de projet 11/03/201 11/05/201 C1.4A0420 3 sur la gestion durable des QC 76 000 132 Postériori 9 9 FCPF 07 TF-17919 En cours terres agricoles (SALM) d’exécution Assurer le renouvellement de Entente 30/03/201 C3.2A113 4 l'abonnement du site web et 2 000 4 Postériori FCPF TF-17919 Contrat à directe 9 022 sa mise à jour renouveler EESS + CGES + CF + SIS + mécanisme de gestion de 28/03/201 28/04/201 C1.4A0430 5 plaintes et des recours + les SBQC 300 000 600 Priori 9 9 FCPF 04 TF-17919 principes pour le mécanisme en cours de partage des bénéfices d’approbation consultant chargé d'appuyer la firme pour l'élaboration de l'EESS + CGES + CF + SIS + 15/02/201 15/05/201 C1.4A0430 6 mécanisme de gestion des CI 70 000 140 Priori 9 9 FCPF 05 TF-17919 plaintes et des recours + les contrat en principes pour le mécanisme cours de de partage des bénéfices réalisation 7 Payer le salaire d'un chauffeur Agent 3 600 En cours de pour le véhicule du Secrétariat contract 7,2 priori passation Technique National REDD+ uel 25/03/202 25/06/202 FCPF C3.4A134 TF-17919 0 0 8 086 Payer les honoraire d'un expert juriste international C1.2A022 05/04/202 20/05/202 FCPF 8 pour appuyer 1011le plaidoyer CI 20 000 40 Postériori 0 0 002 TF-17919 au niveau nation12al et international Payer les honoraires d'un expert en politiques de C1.2A022 05/04/202 20/05/202 FCPF 9 développement pour CI 20 000 40 Postériori 0 0 005 TF-17919 introduire la REDD+ dans les En cours de politiques sectorielles passation Payer les honoraires d'un C1.2A022 consultant pour développer un 10 000 15/07/202 FCPF 10 canevas des projets REDD+ et CI 20 Postériori 1/06/2020 0 006 TF-17919 un registre des projets REDD+ Payer les honoraires d'un C1.3A031 7 000 15/02/202 15/04/202 FCPF 11 consultant pour affiner les CI 14 Postériori 0 0 019 TF-17919 En cours de options stratégiques REDD+ passation Payer les honoraires de l'assistant national au C1.3A032 15/02/202 15/04/202 021 12 processus de consultations et CI 18 375 36 ,75 Priori 0 0 FCPF TF-17919 de construction de la stratégie nationale REDD+. Payer les honoraires du pool de consultants pour la C1.4A042 15 000 15/03/202 15/04/202 FCPF 008 13 proposition de Projets en CI 30 Postériori 0 0 TF-17919 relation avec les options stratégiques de la REDD+. Payer les honoraires de deux C1.4A042 consultants internationaux en 44 000 15/04/202 15/05/202 FCPF 010 14 appui à la rédaction de la CI 88 Postériori 0 0 TF-17919 stratégie nationale REDD+. 15 Payer les honoraires d'un CI 11 000 22 Postériori 15/04/202 15/05/202 FCPF C1.4A042 TF-17919 Processus de assistant en appui au 0 0 011 passation STN/REDD+ pour les terminé renforcements de capacités Contrat à signer des parties prenantes et la après l’octroi du 9 conduite de plaidoyer pour Don additionnel l'intégration de la REDD+ dans le cadre juridique et les référentiels politiques. Commented [BD3]: Toutes ces operations C1.5A052 doivent sortir du PPM dès lors quíl s’agit de 15/04/202 15/05/202 paiement supposant l’existence d’un contrat 16 Appuyer la firme AESA pour la CI 20 000 40 015 TF-17919 finalisation du système MNV Postériori 0 0 FCPF signé et dûment entré en vigueur FCPF C3.3A123 15/05/202 15/06/202 17 Élaborer la stratégie et le plan CI 15 000 30 posteriori 0 0 013 TF-17919 d’action genre BF-PIF-93955-CS-INDV / 15/05/202 20/06/202 18 Rédiger un document de CI 20 000 40 posteriori 0 0 TF-17919 projet carbone sur le "karité" FCPF . TOTAL 752 475 1505 10 PROCUREMENT Burkina Faso : Communal Climate Action and Landscape Management Project PLAN General Information Country: Burkina Faso 2021-07-08 Bank’s Approval Date of the Original Procurement Plan: 2023-05-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P170482 GPN Date: Project Name: Communal Climate Action and Landscape Management Project Loan / Credit No: / , IDA / V3730, IDA / D9660, IDA / 70350 Coordination Unit of decentralized management Project Forestry and Woodlands Areas Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - BF-PIF-355124-CW-RFB / Réa Component 4: Project coordi Single Stage - One E Small Works SPD Pending Imp 2025-08-0 liser les travaux de constructi IDA / 70350 nation, monitoring and evalu Post Request for Bids Open - National 4,000,000.00 0.00 2023-11-20 2023-12-20 2023-12-27 2024-01-10 2024-02-14 nvelope (1 envelope proce lementation 7 on de l'immeuble ation ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PIF-239312-GO-RFQ / Acq Request for Quota Single Stage - One E Pending Impl uisition de consommable info / Post Limited 30,000.00 0.00 2021-06-30 2021-08-11 2021-09-10 tions nvelope ementation rmatique au profit du PIF BF-PIF-239313-GO-RFQ / Acq uisition de matériel informati Request for Quota Single Stage - One E / Post Limited 50,000.00 0.00 Canceled 2021-06-30 2021-08-25 2021-10-24 que ( 2 copieurs, des ordinat tions nvelope eurs et imprimantes pour les nouveaux , scanner Component 2: Institutional s BF-PIF-275362-GO-RFQ / Mat trengthening for integrated l Request for Quota Single Stage - One E ériel spécifiques pour l'opéra IDA / V3730 andscape management, env Post Limited 81,818.00 0.00 Canceled 2022-03-29 2022-05-17 2022-08-15 tions nvelope tionnalisation du SNSF ironmental and social risk m anagement, an d mobilizatio n of climate finance BF-PIF-239310-GO-RFQ / Fou Component 4: Project coordi Request for Quota Single Stage - One E Pending Impl IDA / V3730 Post Limited 19,091.00 0.00 2022-03-01 2022-04-12 2022-05-12 rnitures de Bureau nation, monitoring and evalu tions nvelope ementation ation BF-PIF-239307-GO-RFQ / Mo Component 4: Project coordi Request for Quota Single Stage - One E Pending Impl IDA / V3730 Post Limited 37,258.00 0.00 2022-03-15 2022-05-04 2022-07-03 bilier de bureau au profit du nation, monitoring and evalu tions nvelope ementation STN/REDD+ ation BF-PIF-314776-GO-DIR / Acq Component 4: Project coordi uisition d'un logiciel de planif Under Imple IDA / V3730 nation, monitoring and evalu Post Direct Selection Direct - National 118,182.00 0.00 2022-09-25 2022-11-23 2022-10-09 2022-10-20 2022-11-14 2023-01-13 ication et de suivi-évaluation mentation ation au profit du PGPC/REDD+ BF-PIF-340293-GO-DIR / Acq Component 4: Project coordi uisition de matériels informat Direct - Internation Under Imple IDA / D9660 nation, monitoring and evalu Post Direct Selection 167,000.00 0.00 2023-02-20 2023-02-14 2023-02-25 2023-01-25 2023-03-25 2023-04-24 ique et Peri informatique au al mentation ation profit du PGPC/REDD+ BF-PIF-314842-GO-RFQ / Act Component 4: Project coordi Request for Quota Single Stage - One E Pending Impl ualiser l'adressage du projet IDA / D9660 nation, monitoring and evalu Post Limited 8,333.00 0.00 2023-07-10 2023-09-04 2023-11-03 tions nvelope ementation au niveau central ation BF-PIF-352582-GO-RFQ / Equ Component 1: Decentralized Request for Quota Single Stage - One E Pending Impl iper les communes en matéri IDA / D9660 management of forests and Post Limited 100,000.00 0.00 2023-07-25 2023-09-12 2023-11-11 tions nvelope ementation el de bureau natural resources BF-PIF-352583-GO-RFQ / Acq Component 1: Decentralized Request for Quota Single Stage - One E Pending Impl uérir des moyens matériels a IDA / D9660 management of forests and Post Limited 74,165.00 0.00 2023-07-15 2023-08-31 2024-02-27 tions nvelope ementation u profit des comités de gesti natural resources on des plaintes BF-PIF-352604-GO-RFQ / Acq Component 1: Decentralized Request for Quota Single Stage - One E Pending Impl uérir du matériel informatiqu IDA / D9660 management of forests and Post Limited 71,667.00 0.00 2023-05-04 2023-06-22 2023-12-19 tions nvelope ementation e au profit de la DGI et du SN natural resources -SIF BF-PIF-352960-GO-RFB / Acq Component 4: Project coordi uérir des motos au profit des Single Stage - One E IDA / D9660 nation, monitoring and evalu Post Request for Bids Open - National 168,667.00 0.00 Canceled 2023-05-15 2023-06-14 2023-06-28 2023-07-12 2023-08-09 2023-11-07 antennes régionales et deux nvelope ation agents de liaison de l'UGP et de STN/REDD+ BF-PIF-353011-GO-RFQ / Ass urer l'acquisition du kit de for mation des stagiaires Étudia Component 4: Project coordi Request for Quota Single Stage - One E Pending Impl nt et stagiaires fonctionnaire IDA / D9660 nation, monitoring and evalu Post Limited 22,083.00 0.00 2023-05-09 2023-06-27 2023-08-26 tions nvelope ementation s de l'Initiative Masse Critiqu ation e de Professionnels des Proje ts et Programmes de dévelop pement BF-PIF-355133-GO-RFQ / Acq Component 4: Project coordi uérir des motos au profit des Request for Quota Single Stage - One E Under Imple IDA / D9660 nation, monitoring and evalu Post Limited 83,333.00 0.00 2023-05-04 2023-06-29 2023-07-08 antennes régionales et deux tions nvelope mentation ation agents de liaison de l'UGP et de STN/REDD+ BF-PIF-352591-GO-RFQ / Acq Component 1: Decentralized Request for Quota Single Stage - One E Pending Impl uérir des smartphones pour l IDA / D9660 management of forests and Post Limited 30,164.00 0.00 2023-06-08 2023-08-03 2023-08-09 tions nvelope ementation a collecte des données GEMS natural resources BF-PIF-344407-GO-RFQ / Acq Component 1: Decentralized Single Stage - One E Pending Impl uérir des GPS au profit de la IDA / D9660 management of forests and Post Request for Bids Open - National 226,667.00 0.00 2023-05-25 2023-06-24 2023-07-08 2023-07-22 2023-08-19 2023-11-17 nvelope ementation DGI et SN-SIF . natural resources BF-PIF-353006-GO-RFQ / Acq uérir du matériel de terrain e t des équipements pour opér Component 1: Decentralized Request for Quota Single Stage - One E Pending Impl ationnaliser la base de donné IDA / D9660 management of forests and Post Limited 66,667.00 0.00 2023-05-29 2023-07-31 2024-01-27 tions nvelope ementation es sur les avis de faisabilité e natural resources t de conformité environneme ntale et sur les PGES (mesur es incluses) valides Page 1 BF-PIF-361648-GO-RFQ / Acq Component 4: Project coordi Request for Quota Single Stage - One E Pending Impl uérir des mobiliers de bureau IDA / D9660 nation, monitoring and evalu Post Limited 59,000.00 0.00 2023-06-14 2023-07-21 2024-01-17 tions nvelope ementation au profit des agents du proje ation t BF-PIF-361649-GO-RFQ / Acq Component 3: Entrepreneur Request for Quota Single Stage - One E Pending Impl uérir un matériel mobilier de IDA / D9660 ship and sustainable develo Post Limited 5,000.00 0.00 2023-06-14 2023-07-23 2023-09-06 tions nvelope ementation bureaux au profit de l'UICN pment of value chains BF-PIF-363456-GO-RFQ / Acq Component 1: Decentralized uérir des véhicules 4x4 doubl Request for Quota Single Stage - One E Pending Impl IDA / D9660 management of forests and Post Limited 223,333.00 0.00 2023-06-13 2023-08-08 2023-10-07 e cabine , station wagon au p tions nvelope ementation natural resources rofit de l'ANEVE et UICN BF-PIF-352629-GO-RFB / Acq Component 1: Decentralized uérir des véhicules 4x4 doubl Single Stage - One E IDA / D9660 management of forests and Post Request for Bids Open - National 223,333.00 0.00 Canceled 2023-05-15 2023-06-14 2023-06-28 2023-07-05 2023-08-02 2023-10-31 e cabine , station wagon au p nvelope natural resources rofit de l'ANEVE et UICN NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PIF-352996-NC-DIR / Assu Component 4: Project coordi Pending Impl rer la mise à jour de la base IDA / D9660 nation, monitoring and evalu Post Direct Selection Direct - National 13,333.00 0.00 2023-05-15 2023-05-25 2023-07-13 2024-03-09 ementation de Tom2Pro et assistance tec ation hnique CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PIF-239317-CS-CQS / Rec rutement d’opérateurs pour l ’élaboration des Projets de D éveloppement Communaux p Consultant Qualifi Under Implement / Post Open - National 160,000.00 0.00 2021-08-20 2021-07-31 2021-09-10 2021-10-24 2021-10-28 2021-11-23 2021-12-28 2022-06-26 our la REDD+ (PDIC/ REDD+) cation Selection ation et la validation par la popula tion au profit des communes de Boromo, Fara, Ouri, Siby e t Zamo BF-PIF-239323-CS-CQS / REC RUTEMENT D’UN CONSULTA Consultant Qualifi Under Implement / Post Open - National 60,000.00 0.00 2021-06-25 2021-06-07 2021-07-16 2021-08-29 2021-07-26 2021-09-28 2021-11-02 2022-05-01 NT POUR L’ÉLABORATION DE cation Selection ation LA STRATÉGIE GENRE POUR LA REDD+ BF-PIF-239315-CS-CQS / Rec rutement d’opérateurs pour l ’élaboration des Projets de D Consultant Qualifi Under Implement éveloppement Communaux p IDA / V3730 Post Open - National 128,000.00 0.00 2021-09-15 2021-10-12 2021-10-06 2021-11-04 2021-11-11 2021-12-16 2022-06-14 cation Selection ation our la REDD+ (PDIC/REDD+) et la validation par la populat ion au profit des communes de Koumbia, Houndé, yaho,p â. BF-PIF-239316-CS-CQS / Rec rutement d’opérateurs pour l ’élaboration des Projets de D Consultant Qualifi Under Implement éveloppement Communaux p IDA / V3730 Post Open - National 96,000.00 0.00 2021-06-25 2021-10-12 2021-07-16 2021-08-29 2021-09-28 2021-11-02 2022-05-01 cation Selection ation our la REDD+ (PDIC/ REDD+) et la validation par la popula tion au profit des communes de Bondoukuy, Ouarkoye, Sa fané . BF-PIF-239319-CS-CQS / Rec rutement d’opérateurs pour l ’élaboration des Projets de D éveloppement Communaux p Consultant Qualifi Under Implement IDA / V3730 Post Open - National 192,000.00 0.00 2021-08-20 2021-10-12 2021-09-10 2021-10-24 2021-11-23 2021-12-28 2022-06-26 our la REDD+ (PDIC/ REDD+) cation Selection ation et la validation par la popula tion au profit des communes de Boura, Léo, Nianbouri, Sill y ,to et Biéha BF-PIF-239320-CS-CQS / Rec rutement d’opérateurs pour l ’élaboration des Projets de D éveloppement Communaux p Consultant Qualifi Under Implement our la REDD+ (PDIC /REDD+) IDA / V3730 Post Open - National 224,000.00 0.00 2021-08-20 2021-10-12 2021-09-10 2021-10-24 2021-11-23 2021-12-28 2022-06-26 cation Selection ation et la validation par la popula tion au profit des communes de Bakata, Bougnounou, Cas sou, Dalo, Gao et sapouy et Gombousgou BF-PIF-239321-CS-CQS / Rec rutement d’opérateurs pour l ’élaboration des Projets de D éveloppement Communaux p Consultant Qualifi IDA / V3730 Post Open - National 96,000.00 0.00 Canceled 2021-09-24 2021-10-12 2021-10-15 2021-11-28 2021-12-28 2022-02-01 2022-07-31 our la REDD+ (PDIC/ REDD+) cation Selection et la validation par la populat ion au profit des communes de kpuéré, Bouroum -Bourou m, Nioronioro BF-PIF-246444-CS-CQS / Rec rutement d’opérateurs pour l ’élaboration des Projets de D Consultant Qualifi éveloppement Communaux p IDA / V3730 Post Open - National 64,000.00 0.00 Canceled 2021-07-30 2021-10-12 2021-08-13 2021-09-01 2021-09-15 2021-10-20 2022-04-18 cation Selection our la REDD+ (PDIC/ REDD+) et la validation par la populat ion au profit des communes de Kantchari et Partiaga BF-PIF-262982-CS-CQS / Rec rutement d’opérateurs pour l ’élaboration des Projets de D Component 1: Decentralized Consultant Qualifi Pending Impleme éveloppement Communaux p IDA / V3730 management of forests and Post Open - National 87,500.00 0.00 2021-11-12 2021-11-26 2021-12-15 2021-12-22 2022-01-12 2022-06-11 cation Selection ntation our la REDD+ (PDIC/REDD+) natural resources et la validation par la populat ion au profit des communes deIpelcé, Doulougou, Gombo usgou Page 2 BF-PIF-262983-CS-CQS / Rec rutement d’opérateurs pour l ’élaboration des Projets de D Component 1: Decentralized éveloppement Communaux p Consultant Qualifi Pending Impleme IDA / V3730 management of forests and Post Open - National 87,500.00 0.00 2021-11-16 2021-11-30 2021-12-19 2022-01-02 2022-01-23 2022-07-22 our la REDD+ (PDIC/ REDD+) cation Selection ntation natural resources et la validation par la populat ion au profit des communes de Batié, Bouroum -Bouroum , Nioronioro BF-PIF-264893-CS-LCS / Recr utement d’un cabinet d’expe rtise comptable pour l’audit fi nancier et comptable du fond Component 4: Project coordi Least Cost Selecti Under Implement s de préparation du PGPC/RE IDA / V3730 nation, monitoring and evalu Post Open - National 40,000.00 0.00 2021-11-30 2021-12-04 2021-12-07 2022-01-04 2022-01-28 2022-01-05 2022-01-19 2022-02-03 2022-03-10 2025-02-22 on ation DD+ et l’audit du projet de g ation estion durable des paysages communaux pour la REDD+ ( PGPC/REDD+) exercice 2022, 2023 et 2024. BF-PIF-269411-CS-CQS / Rec rutement d’une agence de co mmunication pour la réalisati Component 4: Project coordi Consultant Qualifi Under Implement on d’un paquet d’outils de co IDA / V3730 nation, monitoring and evalu Post Limited 18,200.00 0.00 2021-12-17 2021-12-15 2021-12-31 2021-12-23 2022-01-14 2022-02-18 2022-04-19 cation Selection ation mmunication pour la visibilité ation du Projet de Gestion durable des Paysages Communaux p our la REDD+ (PGPC/REDD+) BF-PIF-273216-CS-CQS / Etu de diagnostique des maillons critiques des filières de PFNL Component 3: Entrepreneur Consultant Qualifi Under Implement et des organisations de prod IDA / V3730 ship and sustainable develo Post Open - National 72,730.00 0.00 2022-01-21 2022-01-27 2022-02-04 2022-02-25 2022-04-14 2022-03-11 2022-04-14 2022-04-15 2022-10-12 cation Selection ation ucteurs dans la zone d’interv pment of value chains ention du projet de gestion d urable des paysages commu naux pour la REDD+ (PGPC/R EDD+) BF-PIF-239340-CS-CQS / Opé Consultant Qualifi / Post Open - National 160,000.00 0.00 Canceled 2021-08-27 2021-09-17 2021-10-31 2021-11-30 2022-01-04 2022-07-03 rationnalisation du SNSF cation Selection BF-PIF-239332-CS-CQS / Niv Component 4: Project coordi Consultant Qualifi eau de référence des indicat IDA / V3730 nation, monitoring and evalu Post Open - National 81,818.00 0.00 Canceled 2022-02-25 2022-03-18 2022-04-15 2022-04-29 2022-06-03 2022-11-30 cation Selection eurs du projet (firme) ation BF-PIF-239345-CS-INDV / Re Component 3: Entrepreneur crutement d'un consultant (b Consultant Qualifi IDA / V3730 ship and sustainable develo Post Limited 36,364.00 0.00 Canceled 2022-03-03 2022-02-15 2022-03-17 2022-04-16 2022-05-21 2022-07-20 ureau d'études) pour l'étude cation Selection pment of value chains sur les moyens de soutenir la foresterie privée BF-PIF-280591-CS-CQS / Rec Component 3: Entrepreneur rutement d’un (01) consultan Consultant Qualifi Under Implement IDA / V3730 ship and sustainable develo Post Open - National 36,364.00 0.00 2022-02-23 2022-03-03 2022-03-09 2022-04-06 2022-04-25 2022-05-06 2022-08-23 2022-06-10 2022-12-07 t pour une étude sur les moy cation Selection ation pment of value chains ens de soutenir la foresterie privée BF-PIF-325084-CS-CQS / Etu de diagnostique pour la prom Component 1: Decentralized Consultant Qualifi Under Implement otion des pratiques ASP clim IDA / V3730 management of forests and Post Open - National 45,450.00 0.00 2022-11-10 2022-11-14 2022-11-20 2022-11-28 2022-12-05 2022-12-19 2023-04-18 cation Selection ation ato-intelligentes dans la zone natural resources d’intervention du PGPC/REDD + BF-PIF-314898-CS-INDV / Ac cord cadre en vue du recrute Component 1: Decentralized ment des consultants (firmes Consultant Qualifi IDA / V3730 management of forests and Post Open - National 54,545.00 0.00 Canceled 2022-10-04 2023-02-08 2022-10-25 2022-12-08 2023-01-07 2023-02-11 2025-01-31 ) pour la réalisation des étud cation Selection natural resources es /Plans d’Action de Cadre F onctionnels (PACF) dans le ca dre des PDIC REDD+, BF-PIF-338446-CS-CQS / Rec rutement d’un consultant (fir me) pour la réalisation d’étu des architecturales et techni Component 4: Project coordi Consultant Qualifi Under Implement ques détaillées, l’élaboration IDA / V3730 nation, monitoring and evalu Post Open - National 405,000.00 0.00 2023-02-02 2023-02-06 2023-02-12 2023-02-22 2023-02-25 2023-03-05 2024-08-26 cation Selection ation du DAO, le contrôle et la surv ation eillance architectural et tech nique en vue de la constructi on du siège (Bâtiment R+3 e xtensible en R+6) BF-PIF-280581-CS-CQS / Rec rutement d'un consultant po Component 4: Project coordi Consultant Qualifi ur les études architecturales IDA / V3730 nation, monitoring and evalu Post Limited 243,000.00 0.00 Canceled 2022-03-01 2022-03-15 2022-03-29 2022-04-19 2022-10-16 cation Selection en vue de la construction du ation bâtiment du STN/REDD+ BF-PIF-239336-CS-CQS / État Consultant Qualifi des lieux des méthodologies / Post Open - National 40,000.00 0.00 Canceled 2021-08-27 2021-09-10 2021-10-08 2021-10-15 2021-11-19 2022-05-18 cation Selection carbone applicable au PGPC/ REDD+. BF-PIF-239337-CS-CQS / Esti Consultant Qualifi mation du potentiel de séque / Post Open - National 60,000.00 0.00 Canceled 2021-08-27 2021-09-17 2021-10-31 2021-11-14 2021-12-05 2022-06-03 cation Selection stration des activités de l’ER- Program. BF-PIF-239338-CS-CQS / App ui au développement d’un ca Consultant Qualifi / Post Open - National 50,000.00 0.00 Canceled 2021-08-20 2021-09-10 2021-10-24 2021-11-23 2021-12-28 2022-06-26 dre d’agri- business durable cation Selection dans la zone de l’ER-Program . BF-PIF-239339-CS-CQS / Réd Consultant Qualifi action d’un document de pro / Post Open - National 30,000.00 0.00 Canceled 2021-08-27 2021-09-17 2021-10-08 2021-10-15 2021-11-19 2022-05-18 cation Selection gramme pour l’ER- Program me BF-PIF-239341-CS-CQS / Mon Consultant Qualifi / Post Open - National 190,000.00 0.00 Canceled 2021-08-27 2021-09-17 2021-10-31 2021-11-30 2022-01-04 2022-07-03 tage de dossier carbone cation Selection BF-PIF-352110-CS-CQS / Réa Component 2: Institutional s liser une étude de clarificatio trengthening for integrated l n des PSE dans le cadre de la andscape management, env Consultant Qualifi Pending Impleme IDA / D9660 Post Open - National 133,333.00 0.00 2023-05-15 2023-06-05 2023-07-19 2023-08-18 2023-09-22 2024-03-20 REDD+ et proposition d'une ironmental and social risk m cation Selection ntation démarche de leur intégration anagement, an d mobilizatio dans les référentiels de déve n of climate finance loppement BF-PIF-352565-CS-CQS / Rec Component 2: Institutional s ruter un consultant/bureau d’ trengthening for integrated l Consultant Qualifi Under Implement études pour l’établissement IDA / D9660 andscape management, env Post Open - National 58,333.00 0.00 2023-05-15 2023-06-05 2023-05-29 2023-06-26 2023-07-26 2023-08-30 2024-02-26 cation Selection ation de la situation de référence d ironmental and social risk m u stock de carbone forestier anagement, an d mobilizatio de la zone de l’ER-program n of climate finance Page 3 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PIF-239322-CS-INDV / Re crutement d’un Consultant p our la préparation du Cadre d e Gestion Environnement et Component 1: Decentralized Individual Consult Social (CGES) incluant un MG IDA / V3730 management of forests and Post Limited 70,000.00 66,460.15 Completed 2021-06-14 2021-06-10 2021-06-19 2021-06-14 2021-07-10 2021-07-27 2021-08-14 2021-08-21 2021-11-12 2022-01-07 ant Selection P du PGPC/REDD+, la prépar natural resources ation d’un Cadre Fonctionnel (CF) et la préparation des Pro cédures de Gestion de la Mai n d’Œuvre du PGPC/REDD+ a up BF-PIF-239334-CS-CDS / Rec Component 1: Decentralized rutement d’un consultant po IDA / V3730 management of forests and Post Direct Selection Direct 72,000.00 61,242.48 Completed 2021-08-20 2021-06-25 2021-08-30 2021-06-15 2021-11-03 2021-08-28 2022-05-02 2021-11-16 ur l’Évaluation sécuritaire natural resources BF-PIF-239314-CS-CDS / Rec rutement d’une firme pour l’ organisation de Consultation Component 1: Decentralized s inclusives avec jeux de rôle IDA / V3730 management of forests and Post Direct Selection Direct 500,000.00 744,814.91 Completed 2021-07-28 2021-08-06 2021-08-21 2021-06-25 2021-09-26 2021-10-30 2022-03-25 2021-11-16 (Terristories) pour une gestio natural resources n participative des terroirs da ns 30 communes (niveau co mmunal et niveau village). BF-PIF-264858-CS-CDS / MIG Component 4: Project coordi Under Implement RATION LOGICIELS TOM²PRO IDA / V3730 nation, monitoring and evalu Post Direct Selection Direct 30,000.00 0.00 2021-11-25 2021-12-04 2021-12-05 2021-12-08 2022-01-03 2022-12-29 ation - TOMPAIE PARAMETRAGE ET ation FORMATION BF-PIF-266587-CS-INDV / Re crutement d’un (01) consulta Component 1: Decentralized nt spécialiste en violences ba Individual Consult Under Implement IDA / V3730 management of forests and Post Open 30,000.00 0.00 2021-12-02 2022-06-01 2021-12-28 2022-06-29 2022-01-11 2023-03-29 2022-02-01 2023-01-27 sées sur le genre au profit du ant Selection ation natural resources Projet de Gestion Durable de s Paysages Communaux pour la REDD+ (PGPC/REDD+). BF-PIF-275384-CS-INDV / Re Component 2: Institutional s crutement d' un consultant trengthening for integrated l Individual Consult pour la réalisation du diagno IDA / V3730 andscape management, env Post Limited 27,272.00 0.00 Canceled 2022-02-15 2022-02-20 2022-03-13 2022-04-17 2022-10-14 ant Selection stic organisationnel et foncti ironmental and social risk m onnel de l'ANEVE anagement, an d mobilizatio n of climate finance BF-PIF-275397-CS-INDV / Re crutement d'un consultant po Component 1: Decentralized Individual Consult ur la révision du manuel d'él IDA / V3730 management of forests and Post Limited 10,909.00 0.00 Canceled 2022-02-15 2022-02-20 2022-03-02 2022-03-17 2022-09-13 ant Selection aboration, de mise en œuvre natural resources et d'évaluation des PDIC/RED D+ BF-PIF-267720-CS-INDV / Re crutement d’un (01) consulta Component 1: Decentralized nt spécialiste en violences ba Individual Consult IDA / V3730 management of forests and Post Open 30,000.00 0.00 Canceled 2021-12-09 2022-01-04 2022-01-18 2022-02-08 2023-02-03 sées sur le genre au profit du ant Selection natural resources Projet de Gestion Durable de s Paysages Communaux pour la REDD+ (PGPC/REDD+). BF-PIF-314876-CS-INDV / Re crutement d'un consultant po Component 1: Decentralized Under Implement ur réaliser une évaluation sé IDA / V3730 management of forests and Post Direct Selection Direct - National 72,727.00 0.00 2022-09-20 2022-09-22 2022-09-30 2022-12-04 2023-02-02 ation curitaire dans la zone d'inter natural resources vention du PGPC/REDD+ BF-PIF-314888-CS-CDS / Etu de du diagnostic socio-foncie r et de la planification partici Component 1: Decentralized Under Implement pative (DPP) de l’usage des t IDA / V3730 management of forests and Post Direct Selection Direct - National 909,100.00 0.00 2022-10-16 2022-11-14 2022-11-04 2022-12-09 2023-06-07 ation erres autour des espaces de natural resources conservation dans 40 commu nes supplémentaires d’interv ention du PGPC/REDD+ BF-PIF-314899-CS-INDV / Ac cord cadre en vue du recrute Component 1: Decentralized ment de consultants individu Individual Consult IDA / V3730 management of forests and Post Open - National 54,545.00 0.00 Canceled 2022-10-04 2023-02-08 2022-11-22 2022-12-13 2023-01-17 2025-01-06 els pour l'élaboration des No ant Selection natural resources tices d’Impact Environnemen tal et Social (NIES) dans le ca dre des PDIC REDD+ BF-PIF-314892-CS-INDV / Re crutement d’un consultant in Component 1: Decentralized Individual Consult dividuel pour l’élaboration du IDA / V3730 management of forests and Post Limited 18,182.00 0.00 Canceled 2022-09-22 2022-09-22 2022-09-27 2022-10-18 2022-11-22 2023-01-21 ant Selection manuel du Mécanisme de Ge natural resources stion des Plaintes (MGP) du P GPC/REDD+ BF-PIF-239343-CS-INDV / L’é Individual Consult valuation du volume de com / Post Limited 50,000.00 0.00 Canceled 2021-08-30 2021-09-04 2021-09-25 2021-10-30 2022-04-28 ant Selection post à produire d’ici 2026 BF-PIF-239363-CS-INDV / Ap Individual Consult puyer la filière karité pour la / Post Direct 10,000.00 0.00 Canceled 2021-09-17 2021-09-27 2021-10-18 2021-11-22 2022-05-21 ant Selection certification des parcs à karit é BF-PIF-239342-CS-CQS / L’id entification des principales z ones de production de karité Individual Consult et des coopératives partenair / Post Limited 100,000.00 0.00 Canceled 2021-08-27 2021-09-01 2021-09-22 2021-10-27 2022-04-25 ant Selection es dans les communes d’inte rvention (+ identification des besoins de transformation et système de traçabilité) Component 2: Institutional s trengthening for integrated l BF-PIF-352567-CS-INDV / For Individual Consult Pending Impleme IDA / D9660 andscape management, env Post Limited 8,330.00 0.00 2023-07-17 2023-07-31 2023-08-14 2023-09-11 2023-11-10 mation sur la finance climat ant Selection ntation ironmental and social risk m anagement, an d mobilizatio n of climate finance BF-PIF-352569-CS-CDS / Rec Component 2: Institutional s ruter un consultant pour la fo trengthening for integrated l Pending Impleme rmation du personnel de gest IDA / D9660 andscape management, env Post Direct Selection Direct - National 36,650.00 0.00 2023-08-15 2023-09-12 2023-10-11 2024-04-08 ntation ion du laboratoire géomatiqu ironmental and social risk m e sur l'utilisation des drones anagement, an d mobilizatio n of climate finance Page 4 Component 2: Institutional s BF-PIF-352572-CS-INDV / Ela trengthening for integrated l borer une stratégie d'implica Individual Consult Pending Impleme IDA / D9660 andscape management, env Post Limited 16,665.00 0.00 2023-08-25 2023-09-08 2023-09-22 2023-10-20 2024-04-17 tion du secteur privé à la RE ant Selection ntation ironmental and social risk m DD+ anagement, an d mobilizatio n of climate finance Component 2: Institutional s BF-PIF-352573-CS-INDV / Re trengthening for integrated l nforcer les capacités des cad Individual Consult Pending Impleme IDA / D9660 andscape management, env Post Limited 6,665.00 0.00 2023-06-16 2023-06-30 2023-07-14 2023-08-18 2024-02-14 res du STN/REDD+ en anglai ant Selection ntation ironmental and social risk m s anagement, an d mobilizatio n of climate finance BF-PIF-340291-CS-INDV / Re Component 4: Project coordi crutement de l’Assistant Tec Individual Consult Direct - Internation IDA / D9660 nation, monitoring and evalu Post 167,000.00 0.00 Canceled 2023-02-03 2023-02-06 2023-02-13 2023-03-06 2023-03-20 2025-03-09 hnique International REDD+ ant Selection al ation au profit du STN/REDD+ Component 2: Institutional s BF-PIF-353382-CS-CDS / Rec trengthening for integrated l rutement de l’Assistant Tech Individual Consult Direct - Internation Under Implement IDA / D9660 andscape management, env Prior 391,760.00 0.00 2023-04-12 2023-04-11 2023-05-06 2023-02-09 2023-05-20 2023-06-26 2023-06-17 2025-06-06 nique International REDD+ a ant Selection al ation ironmental and social risk m u profit du STN/REDD+ anagement, an d mobilizatio n of climate finance BF-PIF-355572-CS-INDV / RE CRUTEMENT D’UN(E) ASSIST Component 2: Institutional s ANT(E) TECHNIQUE POUR L’E trengthening for integrated l NCADREMENT TECHNIQUE D andscape management, env Individual Consult Direct - Internation Under Implement IDA / D9660 Post 33,333.00 0.00 2023-05-15 2023-04-25 2023-06-12 2023-06-26 2023-07-24 2024-07-18 E L’EVALUATION ENVIRONNE ironmental and social risk m ant Selection al ation MENTALE ET SOCIALE STRAT anagement, an d mobilizatio EGIQUE DE LA STRATEGIE NA n of climate finance TIONALE REDD+ DU BURKIN A FASO ET DES ETUDES CON NEXES BF-PIF-352078-CS-INDV / Ré aliser les études environnem Component 1: Decentralized Individual Consult Pending Impleme entales et sociales du site d IDA / D9660 management of forests and Post Open - National 25,000.00 0.00 2023-10-12 2023-11-07 2023-11-21 2023-12-12 2024-02-10 ant Selection ntation e construction du siège du ST natural resources N/REDD+ et des UGP/REDD+ BF-PIF-363584-CS-INDV / Re Component 2: Institutional s crutement d'un assistant nati trengthening for integrated l onal en appui au Secrétariat andscape management, env Individual Consult Pending Impleme IDA / D9660 Post Limited 26,500.00 0.00 2023-05-30 2023-06-13 2023-06-27 2023-08-01 2024-03-28 Permanent pour la REDD+ p ironmental and social risk m ant Selection ntation our le renforcement de ses c anagement, an d mobilizatio apacités institutionnelles et o n of climate finance pérationnelles Page 5 PROCUREMENT PLAN (Textual Part) Project information: PAKISTAN COMMUNITY SUPPORT PROJECT (CASA-1000) (P151075) – KP CSP Project Implementation agency: Sustainable Development Unit (SDU), Planning & Development Department, Civil Secretariat, Peshawar, Khyber Pakhtunkhwa Pakistan Date of the Procurement Plan: 29 July 2020 Period covered by this Procurement Plan: December 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 updated November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the most updated KP PPRA Rules, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. 1. The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 2. For national open competitive procurement, only the model procurement documents acceptable to the World Bank, shall be used. 3. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 5. Access to procurement opportunities shall not be restricted to firms that have pre-registered and/or paid a registration fee. 6. No preference of any kind shall be given to national bidders in the bidding process. 7. When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works): Not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information: None. PROCUREMENT Pakistan : Pakistan Community Support Project (CASA-1000) PLAN General Information Country: Pakistan 2020-08-03 Bank’s Approval Date of the Original Procurement Plan: 2023-05-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151075 GPN Date: 2020-07-30 Project Name: Pakistan Community Support Project (CASA-1000) Loan / Credit No: / , TF / B2589, TF / B2594, TF / B2595 Directorate of Projects for Merged Areas, Planning and Development Department, GoKPK Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PK-DOPMA-241355-CW-RFB / Hiring of Contractor for Reha Request for Bids - bilitation & Renovation Work Community Investments in S Single Stage - One E Small Works SPD 2022-05-1 TF / B2594 Post Request for Bids Open - National 434,000.00 107,184.45 Signed 2021-06-30 2021-07-08 2021-07-05 2021-07-19 2021-08-16 2021-08-02 2021-09-15 2021-08-02 2021-10-20 2021-09-16 in Basic Health Facilities &Go mall Infrastructure Schemes nvelope (1 envelope proce 8 vt Girls Primary Schools in Di ss) stricts Khyber, Peshawar& No wshera. PK-DOPMA-257089-CW-RFQ Request for Quota / Renovation work in the Sust Community Mobilization and Request for Quota Single Stage - One E 2022-03-1 TF / B2595 Post Limited tions (Non Bank-S 10,000.00 10,166.14 Signed 2021-10-17 2021-10-13 2021-12-12 2021-11-12 ainable Development Unit off Capacity Building tions nvelope 2 PD) ice building and PCSP Laison office. PK-DOPMA-297270-CW-RFB / Request for Bids - Construction of Flood Protecti Community Investments in S Single Stage - One E Small Works SPD 2023-05-0 TF / B2594 Post Request for Bids Open - National 223,060.83 0.00 Canceled 2022-06-03 2022-06-06 2022-06-08 2022-06-09 2022-06-23 2022-07-08 2022-08-08 on Works/Retaining Walls in mall Infrastructure Schemes nvelope (1 envelope proce 5 Tehsil Landikotal District Khy ss) ber PK-DOPMA-297274-CW-RFB / Request for Bids - Construction of Flood Protecti Community Investments in S Single Stage - One E Small Works SPD 2023-05-0 TF / B2594 Post Request for Bids Open - National 147,865.22 0.00 Canceled 2022-06-03 2022-06-06 2022-06-08 2022-06-09 2022-06-23 2022-07-08 2022-08-08 on Works/Retaining Walls in mall Infrastructure Schemes nvelope (1 envelope proce 5 Ali Masjid Tehsil Jamrud Distri ss) ct Khyber PK-DOPMA-297276-CW-RFB / Request for Bids - Construction of Flood Protecti Community Investments in S Single Stage - One E Small Works SPD 2023-05-0 TF / B2594 Post Request for Bids Open - National 149,380.72 0.00 Canceled 2022-06-03 2022-06-06 2022-06-08 2022-06-09 2022-06-23 2022-07-08 2022-08-08 on Works/Retaining Walls in mall Infrastructure Schemes nvelope (1 envelope proce 5 Lala Cheena Tehsil Jamrud Di ss) strict Khyber PK-DOPMA-297277-CW-RFB / Request for Bids - Construction of Flood Protecti Community Investments in S Single Stage - One E Small Works SPD 2023-05-0 TF / B2594 Post Request for Bids Open - National 136,930.50 0.00 Canceled 2022-06-03 2022-06-06 2022-06-08 2022-06-09 2022-06-23 2022-07-08 2022-08-08 on Works/Retaining Walls in mall Infrastructure Schemes nvelope (1 envelope proce 5 Tehsil Pabbi District Khyber ss) PK-DOPMA-330857-CW-RFB / Request for Bids - Construction of Flood Protecti Community Investments in S Single Stage - One E Small Works SPD 2023-06-3 TF / B2594 Post Request for Bids Open - National 171,600.00 0.00 Signed 2023-01-25 2023-01-27 2023-01-26 2023-01-26 2023-02-10 2023-02-10 2023-03-02 2023-02-21 2023-04-02 on Works/Retaining Wall in L mall Infrastructure Schemes nvelope (1 envelope proce 0 andikotal District Khbyer ss) PK-DOPMA-330858-CW-RFB / Request for Bids - Construction of Flood Protecti Community Investments in S Single Stage - One E Small Works SPD 2023-06-3 TF / B2594 Post Request for Bids Open - National 113,750.00 0.00 Signed 2023-01-25 2023-01-27 2023-01-26 2023-01-27 2023-02-10 2023-02-10 2023-03-02 2023-02-21 2023-04-06 on Works/Retaining walls in A mall Infrastructure Schemes nvelope (1 envelope proce 0 li Masjid District Khyber ss) PK-DOPMA-330859-CW-RFB / Request for Bids - Construction of Flood Protecti Community Investments in S Single Stage - One E Small Works SPD 2023-06-3 TF / B2594 Post Request for Bids Open - National 114,910.00 0.00 Signed 2023-01-25 2023-01-27 2023-01-26 2023-01-27 2023-02-10 2023-02-10 2023-03-02 2023-02-21 2023-03-26 on Works/Retaining Walls in mall Infrastructure Schemes nvelope (1 envelope proce 0 Lala Cheena District Khyber ss) PK-DOPMA-330860-CW-RFB / Request for Bids - Construction of Flood Protecti Community Investments in S Single Stage - One E Small Works SPD 2023-06-3 TF / B2594 Post Request for Bids Open - National 105,335.00 0.00 Signed 2023-01-25 2023-01-27 2023-01-26 2023-01-27 2023-02-10 2023-02-10 2023-03-02 2023-02-21 2023-03-26 on Works/Retaining Walls in J mall Infrastructure Schemes nvelope (1 envelope proce 0 alozai District Nowshera ss) PK-DOPMA-345455-CW-RFB / Engaging of Contractor for R Request for Bids - econstruction, Repair & Reno Community Investments in S Single Stage - One E Small Works SPD Under Imple 2023-06-3 vation Work TF / B2594 Post Request for Bids Open - National 350,039.00 0.00 2023-03-02 2023-03-02 2023-03-07 2023-03-05 2023-03-25 2023-03-21 2023-04-12 2023-04-10 2023-04-27 mall Infrastructure Schemes nvelope (1 envelope proce mentation 0 in Basic Health Facilities &Go ss) vt Girls Primary Schools in Districts Khyber, Peshawar& Nowshera. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-DOPMA-186307-GO-RFQ / Project Management, Imple Request for Quota Single Stage - One E 3 high power generators for TF / B2589 mentation, and Monitoring a Post Open - National 62,305.00 9,400.75 Signed 2020-09-20 2020-11-15 2021-03-10 2021-05-14 tions nvelope PMU & PIU nd Evaluation PK-DOPMA-186310-GO-RFB / Project Management, Imple MIS Section allied Equipment Single Stage - One E / mentation, and Monitoring a Post Request for Bids Open - National 174,455.00 0.00 Canceled 2020-09-15 2020-09-20 2020-11-01 2020-12-01 2021-01-05 2021-07-04 , networking, laptops, deskto nvelope nd Evaluation ps, multimedia, Cameras etc. (Including PIUs) PK-DOPMA-186311-GO-RFQ / Project Management, Imple Request for Quota Single Stage - One E Office Furniture and Fixtures TF / B2589 mentation, and Monitoring a Post Open - National 93,457.00 37,868.83 Signed 2020-09-20 2020-11-15 2021-01-07 2021-05-14 tions nvelope (Including PIU) nd Evaluation PK-DOPMA-186308-GO-DIR / Project Management, Imple Procurement of Vehicles (06 TF / B2589 mentation, and Monitoring a Post Direct Selection Direct 168,224.00 82,076.10 Signed 2020-09-15 2021-02-01 2020-09-20 2021-02-08 2020-10-25 2021-02-09 2021-04-23 ) nd Evaluation PK-DOPMA-207612-GO-RFQ / Project Management, Imple Request for Quota Single Stage - One E Laptops(62 numbers) Deskto TF / B2589 mentation, and Monitoring a Post Limited 98,900.00 37,870.20 Signed 2020-12-12 2020-12-22 2021-01-12 2021-01-14 2021-03-13 tions nvelope p Computers(16 numbers) fo nd Evaluation r PCSP Staff. PK-DOPMA-208065-GO-RFQ / Project Management, Imple Office equipment (Printers, S Request for Quota Single Stage - One E TF / B2589 mentation, and Monitoring a Post Limited 45,000.00 15,798.09 Signed 2020-12-14 2020-12-22 2021-01-14 2021-01-15 2021-03-15 canners, Photocopiers, Video tions nvelope nd Evaluation Conference, Multi Media and Cameras) for PCSP. Page 1 Project Management, Imple PK-DOPMA-251216-GO-RFQ / Request for Quota Single Stage - One E TF / B2595 mentation, and Monitoring a Post Limited 10,000.00 8,626.56 Signed 2021-09-07 2021-09-06 2021-11-02 2021-11-02 2022-05-01 Procurement of MIS Software tions nvelope nd Evaluation PK-DOPMA-257094-GO-RFQ / Support ot Resource Center P Community Mobilization and Request for Quota Single Stage - One E lanning & Development Depa TF / B2595 Post Open - National 37,500.00 28,938.53 Signed 2021-10-22 2022-02-09 2021-12-17 2021-11-24 2022-02-15 Capacity Building tions nvelope rtment Govt of Khyber Pakht unkhwa in terms of provision of IT equipment PK-DOPMA-261023-GO-RFQ / Project Management, Imple Request for Quota Single Stage - One E Complaint Boxes as part of G TF / B2589 mentation, and Monitoring a Post Limited 14,500.00 6,597.26 Signed 2021-11-10 2021-11-11 2022-01-05 2021-12-21 2022-03-06 tions nvelope RM. nd Evaluation PK-DOPMA-363613-GO-RFQ / Procurement and installation Community Mobilization and Request for Quota Single Stage - One E Under Imple TF / B2595 Post Limited 8,550.00 0.00 2023-05-28 2023-05-26 2023-06-09 2023-06-29 of CCT Ips based Camera alo Capacity Building tions nvelope mentation ng with Security equipment f or P&DD Govt of KP NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-DOPMA-213336-NC-RFQ / Rental vehicles for field visits Community Mobilization and Request for Quota Single Stage - One E TF / B2594 Post Limited 35,000.00 20,752.37 Signed 2021-01-23 2021-02-02 2021-03-20 2021-03-23 2022-03-20 (02 number for each district i Capacity Building tions nvelope .e. Khyber, Peshawar(FR Pes hawar) & Nowshehra PK-DOPMA-268111-NC-RFB / Project Management, Imple Hiring of firm for the supply a Single Stage - One E TF / B2595 mentation, and Monitoring a Post Request for Bids Open - National 38,000.00 16,489.41 Signed 2021-12-20 2021-12-21 2021-12-25 2021-12-27 2022-01-14 2022-01-11 2022-02-03 2022-02-07 2022-02-17 2022-04-02 2022-06-30 nd installation of IVR System nvelope nd Evaluation in perspective of GRM. PK-DOPMA-312369-NC-RFB / Community Outreach and C Hiring of a Communication Fi Single Stage - One E TF / B2589 ommunications for CASA-10 Post Request for Bids Open - National 120,625.00 0.00 Signed 2022-09-01 2022-09-09 2022-09-06 2022-10-10 2022-10-01 2022-10-24 2022-10-21 2022-10-28 2022-11-09 2023-06-30 rm for the PCSP Communicati nvelope 00 on Strategy Implementation PK-DOPMA-345448-NC-RFB / Project Management, Imple Hiring the services of third p Single Stage - One E Under Imple TF / B2595 mentation, and Monitoring a Post Request for Bids Open - National 64,103.00 0.00 2023-03-01 2023-03-02 2023-03-06 2023-03-05 2023-03-26 2023-03-24 2023-04-15 2023-05-03 2023-05-01 2023-06-30 arty audit/monitoring firm for nvelope mentation nd Evaluation community schemes paymen ts PK-DOPMA-346328-NC-RFB / Community Mobilization and Single Stage - One E Under Imple Hiring the services of the Trai TF / B2595 Post Request for Bids Open - National 64,103.00 0.00 2023-03-03 2023-03-06 2023-03-08 2023-03-06 2023-03-25 2023-04-14 2023-04-28 2023-06-30 Capacity Building nvelope mentation ning Service Provider firm(s) PK-DOPMA-347948-NC-DIR / Community Outreach and C Engaging of State owned Rad TF / B2589 ommunications for CASA-10 Post Direct Selection Direct - National 7,055.00 0.00 Signed 2023-03-09 2023-03-13 2023-03-14 2023-03-27 2023-03-26 2023-06-30 io Station for Radio Messages 00 Campaign CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-DOPMA-150876-CS-LCS / Community Mobilization and Least Cost Selecti / Post Open - National 250,000.00 0.00 Canceled 2020-08-12 2020-09-04 2020-09-02 2020-10-16 2020-11-13 2020-12-13 2021-01-17 2021-02-21 2022-06-30 SMP Consultancy Services Capacity Building on PK-DOPMA-196549-CS-CQS / Community Mobilization and Consultant Qualifi Hiring of Social Mobilization P / Post Limited 250,000.00 0.00 Canceled 2020-10-01 2020-10-08 2020-10-15 2020-11-14 2020-12-19 2021-12-19 Capacity Building cation Selection artner (SMP) PK-DOPMA-211793-CS-CQS / Community Outreach and C Hiring Services of firm for co Consultant Qualifi TF / B2589 ommunications for CASA-10 Post Limited 70,000.00 0.00 Canceled 2020-12-30 2021-01-12 2021-01-13 2021-02-12 2021-03-19 2022-05-31 nducting Baseline, midline, e cation Selection 00 ndline surveys and special st udies. PK-DOPMA-224853-CS-QCBS Community Outreach and C / Hiring services of firm to co Quality And Cost- TF / B2589 ommunications for CASA-10 Post Open - National 70,000.00 55,036.92 Signed 2021-03-16 2021-03-16 2021-03-18 2021-03-24 2021-03-17 2021-04-05 2021-03-17 2021-04-12 2021-03-29 2021-04-15 2021-03-31 2021-04-23 2021-06-02 2022-04-23 nduct Baseline, Midline, Endli Based Selection 00 ne Surveys & Special Studies PK-DOPMA-227866-CS-QCBS Community Mobilization and Quality And Cost- / Hiring of NGO as Social Mob TF / B2589 Post Open - National 125,000.00 106,515.19 Signed 2021-04-04 2021-04-06 2021-04-05 2021-04-08 2021-04-22 2021-02-16 2021-04-22 2021-03-28 2021-04-26 2021-03-28 2021-04-30 2021-03-31 2021-05-17 2021-07-28 2022-06-30 Capacity Building Based Selection ilization Partner- District Khy ber PK-DOPMA-227868-CS-QCBS / Hiring of NGO as Social Mob Community Mobilization and Quality And Cost- TF / B2589 Post Open - National 125,000.00 110,627.34 Signed 2021-04-04 2021-04-06 2021-04-05 2021-04-08 2021-04-16 2021-03-17 2021-04-22 2021-03-28 2021-04-25 2021-03-28 2021-04-27 2021-03-31 2021-05-17 2021-07-28 2022-06-30 ilization Partner- District Pesh Capacity Building Based Selection awar and Nowshera PK-DOPMA-224848-CS-QCBS Community Mobilization and Quality And Cost- / Hiring of NGO as Social Mob TF / B2589 Post Open - National 250,000.00 0.00 Canceled 2021-03-16 2021-03-16 2021-03-19 2021-03-23 2021-04-02 2021-04-07 2021-04-12 2021-04-20 2022-04-20 Capacity Building Based Selection ilization Partner PK-DOPMA-262021-CS-CQS / Community Outreach and C Hiring of a Consulting Firm fo Consultant Qualifi TF / B2589 ommunications for CASA-10 Post Open - National 64,625.00 0.00 Canceled 2021-11-10 2021-11-11 2021-11-15 2021-11-17 2021-12-21 2022-01-05 2022-01-11 2022-06-30 r the cation Selection 00 PCSP Communications Strate gy Implementation PK-DOPMA-311764-CS-LCS / Community Outreach and C Least Cost Selecti Hiring of Firm for conducting TF / B2589 ommunications for CASA-10 Post Open - National 68,750.00 0.00 Signed 2022-08-25 2022-09-09 2022-08-30 2022-10-05 2022-10-03 2022-11-21 2022-10-23 2022-12-21 2022-11-12 2022-12-21 2022-12-09 2022-12-21 2022-12-29 2023-06-30 on Studies & Evaluation on Proje 00 ct Impacts INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-DOPMA-150548-CS-INDV Community Investments in S Individual Consult / Prior Open 56,075.00 0.00 Canceled 2020-09-15 2020-10-19 2020-11-09 2020-12-14 2021-12-28 / Hiring of Infrastructure Spec mall Infrastructure Schemes ant Selection ialist Page 2 PK-DOPMA-150862-CS-INDV Community Investments in S Individual Consult / Hiring of Monitoring & Evalu TF / B2589 Post Open 56,075.00 24,937.51 Signed 2020-09-15 2020-09-04 2020-11-03 2020-10-25 2020-11-24 2020-11-27 2020-12-29 2020-12-06 2021-12-28 mall Infrastructure Schemes ant Selection ation Specialist PK-DOPMA-150864-CS-INDV Community Mobilization and Individual Consult / Post Open 56,075.00 0.00 Canceled 2020-09-15 2020-09-04 2020-11-03 2020-11-24 2020-12-29 2021-12-29 / Hiring of Gender Specialist Capacity Building ant Selection PK-DOPMA-150863-CS-INDV Community Investments in S Individual Consult / Hiring of NRM/Environment / Post Open 56,075.00 0.00 Canceled 2020-09-15 2020-11-03 2020-11-24 2020-12-29 2021-12-29 mall Infrastructure Schemes ant Selection al Specialist PK-DOPMA-150867-CS-INDV Community Mobilization and Individual Consult / Hiring of Social Sector Deve / Post Open 56,075.00 0.00 Canceled 2020-09-16 2020-11-04 2020-11-25 2020-12-30 2021-12-30 Capacity Building ant Selection lopment Specialist PK-DOPMA-186207-CS-INDV Project Management, Imple Individual Consult / Hiring of Financial Manage / mentation, and Monitoring a Post Open 56,075.00 0.00 Canceled 2020-09-16 2020-08-07 2020-11-04 2020-11-25 2020-12-30 2021-12-30 ant Selection ment Specialist nd Evaluation PK-DOPMA-186204-CS-INDV Project Management, Imple Individual Consult / Hiring of Deputy Project Dir / mentation, and Monitoring a Post Open 102,804.00 0.00 Canceled 2020-08-16 2020-08-07 2020-10-04 2020-10-25 2020-11-29 2021-11-29 ant Selection ector nd Evaluation Project Management, Imple PK-DOPMA-186201-CS-INDV Individual Consult Under Implement / mentation, and Monitoring a Post Open 121,495.00 0.00 2020-08-16 2020-08-07 2020-10-04 2020-10-25 2020-11-29 2021-11-29 / Hiring of Project Director ant Selection ation nd Evaluation PK-DOPMA-186209-CS-INDV Project Management, Imple Individual Consult / Hiirng of Procurement Speci / mentation, and Monitoring a Post Open 56,075.00 0.00 Canceled 2020-08-16 2020-08-07 2020-10-04 2020-10-25 2020-11-29 2021-11-29 ant Selection alist nd Evaluation PK-DOPMA-191839-CS-INDV Project Management, Imple Individual Consult / Hiirng of Procurement Speci TF / B2589 mentation, and Monitoring a Post Limited 56,075.00 34,473.79 Signed 2020-09-07 2020-09-09 2020-09-12 2020-10-09 2020-10-03 2020-10-09 2020-11-07 2020-11-03 2021-11-07 ant Selection alist nd Evaluation PK-DOPMA-191841-CS-INDV Project Management, Imple Individual Consult / Hiirng of NRM/Environment TF / B2589 mentation, and Monitoring a Post Limited 56,075.00 8,030.01 Signed 2020-09-07 2020-09-09 2020-09-12 2020-12-29 2020-10-03 2020-11-07 2021-01-23 2021-11-07 ant Selection Specialist nd Evaluation PK-DOPMA-191842-CS-INDV Project Management, Imple Individual Consult / Hiirng of Social Sector Deve TF / B2589 mentation, and Monitoring a Post Limited 56,075.00 20,367.76 Signed 2020-09-07 2020-09-09 2020-09-12 2020-10-19 2020-10-03 2020-11-06 2020-11-07 2020-11-21 2021-11-07 ant Selection lopment Specialist nd Evaluation PK-DOPMA-193505-CS-INDV Project Management, Imple Individual Consult / Hiring of Infrastructure Spec TF / B2589 mentation, and Monitoring a Post Limited 56,075.00 31,222.91 Signed 2020-09-15 2020-09-21 2020-09-20 2020-10-15 2020-10-11 2020-11-16 2020-11-15 2020-11-21 2021-11-15 ant Selection ialist nd Evaluation PK-DOPMA-193511-CS-INDV Project Management, Imple Individual Consult / Hiirng of Financial Manage TF / B2589 mentation, and Monitoring a Post Limited 56,075.00 12,715.37 Signed 2020-09-15 2020-09-21 2020-09-20 2020-10-30 2020-10-11 2020-11-20 2020-11-15 2020-12-05 2021-11-15 ant Selection ment Specialist nd Evaluation PK-DOPMA-193514-CS-INDV Project Management, Imple Individual Consult / Hiring of Deputy Project Dir / mentation, and Monitoring a Post Limited 102,804.00 0.00 Canceled 2020-09-15 2020-09-21 2020-09-20 2020-10-11 2020-11-15 2021-11-15 ant Selection ector nd Evaluation PK-DOPMA-194830-CS-INDV Project Management, Imple Individual Consult / Hiring of Community Driven / mentation, and Monitoring a Post Limited 56,075.00 0.00 Canceled 2020-10-01 2020-09-21 2020-10-06 2020-10-27 2020-12-01 2021-12-01 ant Selection Development Specialist nd Evaluation PK-DOPMA-196190-CS-INDV Project Management, Imple Individual Consult / Hiring of Deputy Project Dir TF / B2589 mentation, and Monitoring a Post Direct 102,804.00 76,244.52 Signed 2020-09-24 2020-09-24 2020-10-04 2020-09-24 2020-10-25 2020-09-24 2020-11-29 2020-09-19 2021-11-29 ant Selection ector nd Evaluation Project Management, Imple PK-DOPMA-199545-CS-INDV Individual Consult TF / B2589 mentation, and Monitoring a Post Limited 56,075.00 31,549.89 Signed 2020-10-19 2020-10-15 2020-10-24 2020-10-15 2020-11-14 2020-11-16 2020-12-19 2020-11-21 2021-12-19 / Hiring of Gender Specialist ant Selection nd Evaluation PK-DOPMA-221357-CS-CDS / Community Mobilization and Pending Impleme Community Driven Developm TF / B2589 Post Direct Selection Direct 11,250.00 0.00 2021-02-25 2021-03-07 2021-05-11 2021-11-07 Capacity Building ntation ent Specialist PK-DOPMA-221358-CS-CDS / Community Outreach and C TF / B2589 Post Direct Selection Direct 11,250.00 9,716.60 Signed 2021-02-25 2021-03-05 2021-03-07 2021-03-09 2021-05-11 2021-03-10 2021-11-07 Communication Specialist ommunications for CASA-10 00 PK-DOPMA-292189-CS-INDV Community Mobilization and Individual Consult Under Implement / Hiring of PC1 Development TF / B2595 Post Limited 40,000.00 0.00 2022-04-26 2022-04-26 2022-05-01 2022-05-22 2022-06-26 2022-12-23 Capacity Building ant Selection ation (Planning) for KP RIISP PK-DOPMA-292193-CS-INDV Community Mobilization and Individual Consult / Hiring of Environment Speci TF / B2595 Post Limited 26,000.00 5,534.59 Signed 2022-04-26 2022-04-26 2022-05-02 2022-05-26 2022-05-23 2022-06-28 2022-06-27 2022-07-05 2022-12-24 Capacity Building ant Selection alist for KP RIISP PK-DOPMA-292196-CS-INDV Community Mobilization and Individual Consult TF / B2595 Post Limited 28,000.00 8,830.18 Signed 2022-04-26 2022-04-26 2022-05-02 2022-05-26 2022-05-23 2022-06-28 2022-06-27 2022-08-06 2022-12-24 / Hiring of Social Specialist fo Capacity Building ant Selection r KP RIISP PK-DOPMA-292199-CS-INDV Community Mobilization and Individual Consult / Hiring of Procurement Speci TF / B2595 Post Limited 25,000.00 4,109.01 Signed 2022-04-26 2022-04-26 2022-05-01 2022-05-26 2022-05-22 2022-06-28 2022-06-26 2022-07-05 2022-12-23 Capacity Building ant Selection alist for KP RIISP PK-DOPMA-312414-CS-INDV / Hiring of Strategic Commu Community Mobilization and Individual Consult nication Specialist as individu TF / B2595 Post Limited 8,825.00 0.00 Signed 2022-08-30 2022-08-30 2022-09-04 2022-09-04 2022-09-25 2022-09-13 2022-10-30 2023-03-29 Capacity Building ant Selection al consultant for P&DD Govt of Khyber Pakhtunkhwa PK-DOPMA-312415-CS-INDV / Hiring of Digital Media Expe Community Mobilization and Individual Consult rt / Content Development an TF / B2595 Post Limited 6,765.00 0.00 Signed 2022-08-30 2022-08-30 2022-09-04 2022-09-05 2022-09-25 2022-10-17 2022-10-30 2023-03-29 Capacity Building ant Selection d Data Visualization as Indivi dual consultant for P&DD Go vt of Khyber Pakhtunkhwa PK-DOPMA-312416-CS-INDV / Hiring of Graphic Designer a Community Mobilization and Individual Consult TF / B2595 Post Limited 6,765.00 0.00 Signed 2022-08-30 2022-08-30 2022-09-04 2022-09-05 2022-09-25 2022-10-17 2022-10-30 2023-03-29 nd Video Editor as Individual Capacity Building ant Selection consultant for P&DD Govt of Khyber Pakhtunkhwa PK-DOPMA-312418-CS-INDV / Hiring of Photographer & Vi Community Mobilization and Individual Consult TF / B2595 Post Limited 4,412.00 0.00 Signed 2022-08-30 2022-08-30 2022-09-04 2022-09-05 2022-09-25 2022-09-13 2022-10-30 2023-03-29 deographer for P&DD Govt of Capacity Building ant Selection Khyber Pakhtunkhwa Page 3 PK-DOPMA-325963-CS-CDS / Hiring of Social Mobilization P artner to provide support in i mplementation of women an Community Mobilization and Under Implement TF / B2595 Post Direct Selection Direct - National 129,777.00 0.00 2022-11-12 2022-11-14 2022-11-14 2022-11-22 2023-06-30 d youth activities, post-compl Capacity Building ation etion engagement with Com munity Development Council s (CDCs) to ensure sustainabi lity of CDC sub-projects. PK-DOPMA-353100-CS-INDV Project Management, Imple Individual Consult Under Implement / Hiring of Environmental Nat TF / B2595 mentation, and Monitoring a Post Limited 4,600.00 0.00 2023-03-31 2023-03-31 2023-04-03 2023-04-03 2023-04-12 2023-04-23 2023-06-30 ant Selection ation ural Resource Management S nd Evaluation pecialist(NRM) Project Management, Imple PK-DOPMA-353104-CS-INDV Individual Consult Under Implement TF / B2595 mentation, and Monitoring a Post Limited 4,000.00 0.00 2023-03-31 2023-03-31 2023-04-03 2023-04-03 2023-04-12 2023-04-23 2023-06-30 / Hiring of M&E Specialist ant Selection ation nd Evaluation Project Management, Imple PK-DOPMA-353116-CS-INDV Individual Consult Under Implement TF / B2595 mentation, and Monitoring a Post Limited 4,600.00 0.00 2023-03-31 2023-03-31 2023-04-03 2023-04-03 2023-04-12 2023-04-24 2023-06-30 / Hiring of Gender Specialist ant Selection ation nd Evaluation PK-DOPMA-355867-CS-INDV Community Mobilization and Individual Consult / Hiring of Planning Specialist TF / B2595 Post Limited 2,565.00 0.00 Under Review 2023-04-13 2023-06-05 2023-04-16 2023-04-26 2023-05-07 2023-06-30 Capacity Building ant Selection for P&DD Govt of KP Page 4 PROCUREMENT PLAN for SURP II General 1. Project Information Country: Federal Republic of Somalia Project Name: Somali Urban Resilience Project (SURP) Phase II Project Number: P170922 Total Finance: USD 112,000,000 2. Project Implementation Agencies: Ministry of Public Works, Benadir Regional Administration (BRA), Garowe Municipality, Kismayo Municipality, Baidoa Municipality 3. Date of Project Plan: October 2019 4. Period Covered by this Procurement: May 2020 to December 2021 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Document: The Bank’s standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified into Procurement Plan tables in STEP III. National Procurement Arrangements: Not applicable IV. Prequalification: Not applicable V. Leased Assets: Not Applicable VI. Procurement of Second hand Goods: Not Applicable 1 VII. Domestic Preference: Not Applicable VIII. Hands on Expanded Implementation Support (HEIS): Not Applicable IX. Other Relevant Procurement Information: Not Applicable X. Thresholds for Procurement Approaches and Method (US$ millions) Thresholds for Procurement Approaches and Methods (US$ millions)– Goods, Works, and Non-Consulting Services Category Prior Open Open Request for Review Internation National Quotation (US$ al (RfQ) millions) Works All ≥ 5.0 < 5.0 ≤ 0.2 Goods, IT, and all ≥ 0.5 < 0.5 ≤ 0.1 non-consulting services Thresholds for Procurement Approaches and Methods (US$, millions) – Consulting Services Category Prior Short List of National Consultants Review Consulting Services Engineering and (US$, Construction millions) Supervision Consultants all ≤ 0.1 ≤ 0.2 (Firms) Individual all n.a. n.a. Consultants 2 1) Baidoa Municipality Sr. Contract Estima Rev Marke Sele Evalua Procure Prequalifi Domes Expec Expected No Description ted iew t ctio tion ment cation tic ted date of Cost by Appro n Optio Process (Yes/ No) Prefer date Contract (US$) Ban ach Met ns (Single ence of bid/ Signatur k (Open- hod (BAFO stage- (Yes/N propo e (Pri Nation (RFP , single o) sal or/ al/ , Rated envelop openi Pos Limite RFB, Criteri e etc.) ng t) d etc.) RFQ a etc.) etc.) GOODS Procurement Lowest Single of Three 4WD Shoppi Evaluat stage 05/05/ 06/07/202 G1 80,000. Prior RFQ N/A N/A motor Vehicle ng ed One- 2020 0 00 pick ups Cost Envelop Survey and Lowest Single Laboratory 20,000. Shoppi Evaluat stage 07/07/ 09/09/202 G2 Prior RFQ N/A N/A equipment 00 ng ed One- 2020 0 Cost Envelop Hired vehicles for a period Lowest Single of time before 30,000. Shoppi Evaluat stage 04/07/ 31/12/202 G3 Prior RFQ N/A N/A the new 00 ng ed One- 2020 0 vehicles are Cost Envelop delivered Total Goods WORKS Construction of section Lowest Single Open 3,000,00 Evaluat stage 20/04/ 01/05/202 of Ali Prior Nation RFB N/A N/A W1 0 ed One- 2020 0 Amhar al Cost Envelop Road in 3 Baidoa Construction of Section Lowest Single Open of 30 KA 4,000,00 Evaluat stage 20/04/ 01/05/202 W2 Prior Nation RFB N/A N/A Road in 0 ed One- 2020 0 al Baidoa Cost Envelop Construction Lowest Single of Section Open 4,000,00 Evaluat stage 20/04/ 01/05/202 W3 of Hospital Prior Nation RFB N/A N/A 0 ed One- 2020 0 Road in al Cost Envelop Baidoa Lowest Construction 60.000.0 Shoppi Evaluat 01/03/20 01/04/202 01/06/ 01/08/202 W4 of RFQ N/A 0 Prior ng ed 20 0 2020 0 Laboratory Cost Total 12,070, Works 000 Non -Consulting Services – Not applicable Consulting Services Sr No. Contract Estimated Review Market Selection Shortlisti Expected Expected Descripti Cost by Bank Approach Method ng Date of Date of on (Prior/P (Open- (QCBS, (Yes/No) Bid Contract ost) National/ LCBCS, QBS, Proposal Signatur Limited etc.) DS Opening e Engineerin g 02/10/202 supervisio 1,500,000.00 Prior Open National QCBS N/A 01/11/2019 C1 1 n of Urban Roads M&E 02/02/202 C2 Survey 750,000.00 Prior Open National QCBS N/A 01/03/2020 1 (Base line, 4 Mid and Impact Control) Project 01/10/202 Direct C3 Coordinato 66,000.00 Prior CDS N/A 01/07/2020 1 Selection r Procureme 01/10/202 Direct C4 nt 46,000.00 Prior CDS N/A 01/07/2020 1 Selection Specialist Financial 01/10/202 Managem Direct 01/07/202 1 C5 46,000.00 Prior CDS N/A ent Selection 0 Specialist 01/10/202 Project Direct C6 Prior CDS N/A 01/07/2020 1 Engineer Selection 48,000.00 Social/Envi 01/10/202 Direct C7 ronmental 61,200.00 Prior CDS N/A 01/07/2020 1 Selection Specialist M&E 01/10/202 C8 42,000.00 Prior Open National INDV N/A 01/03/2020 Specialist 1 Communit 01/10/202 y Direct 1 C9 30,000.00 Prior CDS N/A 01/03/2020 Mobilizatio Selection n Officer Female 01/10/202 Communit 1 C10 y 30,000.00 Prior Open National INDV N/A 01/03/2020 Mobilizatio n Officer Total 2,619,200.0 Consultin 0 g Services Grand 14,926,200. Total 00 5 6 PROCUREMENT Somalia : Somalia Urban Resilience Project II PLAN General Information Country: Somalia 2020-11-13 Bank’s Approval Date of the Original Procurement Plan: 2023-05-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P170922 GPN Date: Project Name: Somalia Urban Resilience Project II Loan / Credit No: IDA / D5310, TF / B1519 Beledweyne Municipality Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-BW-265896-GO-RFQ / Pr ocurement of Office Equipme Project Management and Ca Request for Quota Single Stage - One E IDA / D5310 Prior Limited 13,300.00 12,810.00 Signed 2021-12-09 2021-12-09 2022-02-03 2022-02-03 2022-08-02 nt (Laptops, Projector and Pri pacity Building tions nvelope nter) for Beledweyn PIU SO-BW-359893-GO-RFQ / Pr Project Management and Ca Request for Quota Single Stage - One E Under Imple ocurement of new vehicle for TF / B1519 Prior Limited 50,000.00 0.00 2023-06-03 2023-07-29 2024-01-25 pacity Building tions nvelope mentation Beledweyn PIU SO-BW-359699-GO-RFQ / Pr ocurement of Office Furniture Project Management and Ca Request for Quota Single Stage - One E Under Imple (Office Desks, Office Chairs, TF / B1519 Prior Limited 11,900.00 0.00 2023-06-03 2023-07-29 2024-01-25 pacity Building tions nvelope mentation Meeting Table, Meeting Chair s, Filling Cabinet, Plastic Chai rs and Fridge) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-BW-360146-NC-RFQ / Off Project Management and Ca Request for Quota Single Stage - One E Under Imple TF / B1519 Prior Limited 10,500.00 0.00 2023-06-03 2023-07-29 2024-01-25 ice rent for Beledweyn PIU fo pacity Building tions nvelope mentation r 7 Months CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-BW-324122-CS-CQS / Pre paration of Detailed Engineer Urban Infrastructure and Ser Consultant Qualifi Under Implement ing Designs and Bidding Doc IDA / D5310 Prior Limited 50,000.00 0.00 2022-11-02 2023-01-09 2022-11-16 2023-03-28 2022-12-16 2023-01-20 2023-07-19 vices cation Selection ation uments for Beledweyn PIU Of fice Block and Laboratory INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-BW-204509-CS-INDV / PI Project Management and Ca Individual Consult IDA / D5310 Prior Open 54,000.00 0.00 Canceled 2020-11-16 2020-11-17 2021-01-04 2021-01-25 2021-03-01 2021-08-28 U Coordinator for Hirshabelle pacity Building ant Selection FMS SO-BW-204539-CS-INDV / En Project Management and Ca Individual Consult vironmental and Social Safeg IDA / D5310 Prior Open 51,000.00 0.00 Canceled 2020-11-16 2020-11-17 2021-01-04 2021-01-25 2021-03-01 2021-08-28 pacity Building ant Selection uards Specialist for Hirshabel le FMS SO-BW-204540-CS-INDV / Pr Project Management and Ca Individual Consult ocurement Specialist for Hirs IDA / D5310 Prior Open 42,000.00 0.00 Canceled 2020-11-17 2020-11-17 2021-01-05 2021-01-26 2021-03-02 2021-08-29 pacity Building ant Selection habelle FMS SO-BW-204542-CS-INDV / Fi Project Management and Ca Individual Consult nancial Management Speciali IDA / D5310 Prior Open 42,000.00 0.00 Canceled 2020-11-16 2020-11-17 2021-01-04 2021-01-25 2021-03-01 2021-08-28 pacity Building ant Selection st for Hirshabelle FMS SO-BW-204544-CS-INDV / Pr Project Management and Ca Individual Consult IDA / D5310 Prior Open 42,000.00 0.00 Canceled 2020-11-17 2020-11-17 2021-01-05 2021-01-26 2021-03-02 2021-08-29 oject Engineer for Hirshabelle pacity Building ant Selection FMS SO-BW-204609-CS-INDV / M Urban Infrastructure and Ser Individual Consult onitoring and Evaluation (M IDA / D5310 Prior Open 42,000.00 0.00 Canceled 2020-11-18 2020-11-17 2021-01-06 2021-01-27 2021-03-03 2021-08-30 vices ant Selection & E) Specialist for Hirshabelle FMS SO-BW-205268-CS-INDV / Pr Project Management and Ca Individual Consult IDA / D5310 Prior Open 54,000.00 140,400.00 Under Review 2020-11-21 2020-11-19 2021-01-09 2021-05-05 2021-01-30 2021-05-11 2021-03-06 2021-06-01 2021-09-02 oject Coordinator for Beledw pacity Building ant Selection eyne PIU SO-BW-205271-CS-INDV / En vironmental and Social Safeg Project Management and Ca Individual Consult IDA / D5310 Prior Open 50,400.00 92,160.00 Under Review 2020-11-21 2020-11-19 2021-01-09 2021-05-05 2021-01-30 2021-05-10 2021-03-06 2021-06-07 2021-09-02 uards (E&SS) Specialist for B pacity Building ant Selection eledweyne PIU. SO-BW-205273-CS-INDV / Fi Project Management and Ca Individual Consult nancial Management Speciali IDA / D5310 Prior Open 42,000.00 96,000.00 Signed 2020-11-21 2020-11-19 2021-01-09 2021-05-05 2021-01-30 2021-09-08 2021-03-06 2021-09-22 2021-09-02 pacity Building ant Selection st for Beledweyne PIU SO-BW-205275-CS-INDV / Pr Project Management and Ca Individual Consult ocurement Specialist for Bele IDA / D5310 Prior Open 42,000.00 92,160.00 Under Review 2020-11-21 2020-11-19 2021-01-09 2021-05-05 2021-01-30 2021-05-10 2021-03-06 2021-06-06 2021-09-02 pacity Building ant Selection dweyne PIU Page 1 SO-BW-205278-CS-INDV / M Project Management and Ca Individual Consult onitoring and Evaluation (M& IDA / D5310 Prior Open 42,000.00 92,160.00 Under Review 2020-11-21 2020-11-19 2021-01-09 2021-05-05 2021-01-30 2021-05-10 2021-03-06 2021-06-09 2021-09-02 pacity Building ant Selection E) Specialist for Beledweyne PIU SO-BW-205270-CS-INDV / Pr Project Management and Ca Individual Consult IDA / D5310 Post Open 42,000.00 0.00 Canceled 2020-11-21 2020-11-19 2021-01-09 2021-01-30 2021-03-06 2021-09-02 oject Engineer for Beledweyn pacity Building ant Selection e PIU SO-BW-276043-CS-INDV / Pr Project Management and Ca Individual Consult Under Implement IDA / D5310 Prior Open 46,080.00 0.00 2022-02-06 2022-12-20 2022-03-27 2022-04-17 2022-05-22 2022-11-18 oject Engineer for Beledweyn pacity Building ant Selection ation e PIU Page 2 Procurement Plan I. General 1. Project Information Country : Kenya Recipient : Republic of Kenya Project Name : National Agriculture and Rural Inclusive Growth Loan Credit No. : IDA 59000 2. Date of General Procurement Notice : 9th February 2018 3. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services 1. Thresholds for the Method of Procurement: Method of Procurement Thresholds for Method (US$ equivalent) Open International (Goods) Equal to or more than 3 million Open National ( Goods) – Open < $3 million Tender as per PPDA 2015 RFQ (Goods) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Open International (Works) Equal to or more than 15 million Open National (Works) - Open Less than 15 million Tender as per PPDA 2015 RFQ (works) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Method of Procurement Thresholds for Method (US$ equivalent) Open International (Non-consulting Equal to or More than 3 million Services) Open National (Non-consulting Less than 3 million Services) - Open Tender as per PPDA 2015 Direct Contracting No threshold; meet requirements of Bank’s Procurement Regulations Prior Review: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection (Project Procurement Risk Rating is “High”): (a) Goods, information technology and Non-consulting Services: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1.5 million (b) Works (including turnkey, supply & installation of plant and equipment and PPP); First procurement under the project irrespective of value and all procurements estimated to cost more than USD 5 million and The prior review thresholds will be reviewed during the implementation of the project and modified, based on the risk assessment. 2. For contracts subject to prior review, the Borrower shall seek the Bank’s no objection before agreeing to: a. an extension of the stipulated time for execution of a contract that has an impact on the planned completion of the project; b. any material modification of the scope of the Works, Goods, Non- consulting services or Consulting Services, or other significant changes to the terms and conditions of the contract; c. any variation order or contract amendment (except in cases of extreme urgency), including due to extension of time, that singly or combined with all previous variation orders or amendments, increases the original contract amount by more than 15% (fifteen percent); or d. the proposed termination of the contract. The Borrower / IA shall provide a copy of all amendments to the contract to the Bank for its records. 3. Prequalification Not Applicable Domestic Preference. The provision of domestic preference shall be applied in the procurement of goods following international market approach in accordance with Annex VI of the Regulations. Domestic preference shall not apply in the procurement of works. 4. Reference to Standard Procurement Documents Bank’s Standard RFB Goods and RFP Consulting Services dated July 2016 will be used as a base and incorporating suitable modifications and the same would be agreed with the Bank subject international competition. 5. Any Other Special Procurement Arrangements A. Procurement approach under CDD Approach by Communities: Applicable if stipulated in the PAD. B. When approaching the national market, as agreed in the Procurement Plan, the Open Tender procedure of Public Procurement and Asset Disposal Act 2015 and Regulations 2017 may be used. The specific Requirements for national open competitive procurement include the following: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. Other national procurement arrangements (other than national open competitive procurement), that may be applied by the Borrower (such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti-Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. In all cases, the national procurement procedures to be used shall give due attention to quality aspects. 6. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Selection methods of procurement of Consultants' Services (Firms): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Quality and Cost Based As per requirements of para 7.3 of the Selection (QCBS) Regulations Quality Based Selection As per requirements of para 7.8 to 7.10 (QBS) of the Regulations Selection based on a Fixed As per requirements of para 7.4 and 7.5 of the Budget (FBS) Regulations Selection Based on Least As per requirements of para 7.6 and 7.7 of the Cost Basis (LCS) Regulations Selection based on As per requirements of para 7.11 and 7.12 of Consultant’s Qualification the Regulations (CQ) Direct Must meet the requirements of Para 7.13 to 7.15 of the Regulations, and with prior agreement in PP with the Bank. The short list may consist of all National consultants in case the estimated cost is less than USD 300,000 Procurement methods for Selection of Individual Consultants (IC): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Open Competitive As per requirements of para 7.36 and 7.37 of Selection the Regulations Limited Competitive As per requirements of para 7.38 of the Selection Regulations Direct Must meet the requirements of Para 7.39 of the Regulations, and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Regulations Prior Review Thresholds: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 0.5 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.2 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. PROCUREMENT Kenya : National Agricultural and Rural Inclusive Growth Project PLAN General Information Country: Kenya 2019-06-11 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153349 GPN Date: 2018-02-09 Project Name: National Agricultural and Rural Inclusive Growth Project Loan / Credit No: IDA / 59000 kirinyaga County Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-KIRINYAGA COUNTY-1439 Project Coordination and Ma Request for Quota Single Stage - One E Pending Imp 2020-07-2 78-CW-RFQ / renovation and IDA / 59000 Post Limited 3,972.00 0.00 2019-12-04 2020-01-29 nagement tions nvelope lementation 7 refurbishment of county proj ect office KE-KIRINYAGA COUNTY-2701 Request for Quota Supporting Community-Driv Request for Quota Single Stage - One E Pending Imp 2022-09-0 80-CW-RFQ / construction of IDA / 59000 Post Limited tions (Non Bank-S 19,400.00 0.00 2022-01-22 2022-03-05 en Development tions nvelope lementation 1 fish aggregation and processi PD) ng facility KE-KIRINYAGA COUNTY-2701 Request for Quota Supporting Community-Driv Request for Quota Single Stage - One E 2022-09-0 97-CW-RFQ / sewerage syste IDA / 59000 Post Limited tions (Non Bank-S 1,000.00 0.00 Canceled 2022-01-29 2022-03-12 en Development tions nvelope 8 m for waste management wo PD) rks GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-KIRINYAGA COUNTY-1146 Project Coordination and Ma Request for Quota Single Stage - One E 33-GO-RFQ / Purchase of offi IDA / 59000 Post Limited 23,500.00 17,758.80 Completed 2019-06-08 2019-06-24 2019-08-03 2019-07-10 2020-01-30 2019-08-20 nagement tions nvelope ce furniture and fittings KE-KIRINYAGA COUNTY-1402 Project Coordination and Ma Request for Quota Single Stage - One E 50-GO-RFQ / purchase of offi IDA / 59000 Post Limited 34,020.00 0.00 Signed 2019-12-04 2020-08-18 2020-01-29 2020-07-27 nagement tions nvelope ce furniture and fittings KE-KIRINYAGA COUNTY-1401 Project Coordination and Ma Request for Quota Single Stage - One E 75-GO-RFQ / purchase of 5 n IDA / 59000 Post Limited 8,000.00 7,459.91 Completed 2019-12-27 2020-03-30 2020-02-21 2020-04-18 2020-03-22 2020-07-01 nagement tions nvelope o. Laptop computers KE-KIRINYAGA COUNTY-1678 Project Coordination and Ma Request for Quota Single Stage - One E 91-GO-RFQ / video conferenc IDA / 59000 Post Limited 73,000.00 67,213.14 Completed 2020-05-02 2020-11-16 2020-05-30 2021-01-06 2020-06-29 2021-01-22 nagement tions nvelope ing equipment KE-KIRINYAGA COUNTY-1679 Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 80,000.00 64,088.73 Completed 2020-05-02 2020-08-13 2020-05-30 2020-10-27 2020-06-29 2021-04-13 03-GO-RFQ / purchase of mot nagement tions nvelope or cycles KE-KIRINYAGA COUNTY-1782 73-GO-RFQ / procurement of Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 29,525.00 27,349.47 Completed 2020-07-13 2020-08-13 2020-08-10 2020-10-23 2020-08-24 2020-12-16 Disruptive Agricultural Techn nagement tions nvelope ology (DAT) Equipment KE-KIRINYAGA COUNTY-1971 Project Coordination and Ma Request for Quota Single Stage - One E 86-GO-RFQ / purchase of 20 ( IDA / 59000 Post Limited 3,000.00 2,746.00 Completed 2020-08-17 2020-08-17 2020-09-21 2020-09-17 2020-10-05 2020-10-06 nagement tions nvelope no) tender boxes KE-KIRINYAGA COUNTY-1971 Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 53,500.00 48,957.33 Completed 2020-10-26 2020-11-02 2020-12-07 2020-12-18 2021-01-06 2020-12-22 92-GO-RFQ / purchase of Equ ty-Led Development tions nvelope ipments KE-KIRINYAGA COUNTY-2082 Supporting County Communi Request for Quota Single Stage - One E 60-GO-RFQ / PURCHASE OF S IDA / 59000 Post Limited 6,500.00 23,186.46 Completed 2021-01-27 2021-03-18 2021-02-24 2021-05-16 2021-03-26 2021-06-09 ty-Led Development tions nvelope OIL TESTING EQUIPMENT KE-KIRINYAGA COUNTY-2148 Project Coordination and Ma Request for Quota Single Stage - One E 25-GO-RFQ / purchase of 20 IDA / 59000 Post Limited 12,000.00 10,818.39 Completed 2021-01-27 2021-03-18 2021-02-24 2021-05-13 2021-03-26 2021-06-09 nagement tions nvelope desktop computers and 20 pr inters KE-KIRINYAGA COUNTY-2201 Project Coordination and Ma Request for Quota Single Stage - One E Pending Impl IDA / 59000 Post Limited 1,600.00 0.00 2021-04-30 2021-05-28 2021-06-27 56-GO-RFQ / purchase of 1(n nagement tions nvelope ementation o) laptops KE-KIRINYAGA COUNTY-2702 Supporting Community-Driv Request for Quota Single Stage - One E Pending Impl 17-GO-RFQ / IoT water tempe IDA / 59000 Post Limited 900.00 0.00 2022-01-22 2022-03-05 2022-05-04 en Development tions nvelope ementation rature sensors KE-KIRINYAGA COUNTY-2690 67-GO-DIR / supply and deliv Supporting Community-Driv ery of tablets pre installed wi IDA / 59000 Post Direct Selection Direct 13,224.00 0.00 Signed 2022-03-01 2022-03-28 2022-03-06 2022-04-01 2022-04-10 2022-10-07 en Development th agripreneur digital license s and smart digital projectors for DAT activities KE-KIRINYAGA COUNTY-3432 34-GO-RFB / Supply, Installati on, testing and commissionin Strengthening Producer Org Single Stage - One E Pending Impl g of six (6) mechanical Eco-L IDA / 59000 anizations and Value Chain Post Request for Bids Open - National 374,707.00 0.00 2023-03-07 2023-03-12 2023-04-09 2023-04-16 2023-05-14 2023-09-11 nvelope ementation ogical Coffee Pulper of nomin Development al/intake capacity 6 to 7.5 m 3 complete with rotary scree n, three phase electric motor s. KE-KIRINYAGA COUNTY-3450 Supporting Community-Driv Request for Quota Single Stage - One E Pending Impl 25-GO-RFQ / purchase of (20) IDA / 59000 Post Limited 2,532.00 0.00 2023-03-04 2023-04-22 2023-07-21 en Development tions nvelope ementation no. soil augers KE-KIRINYAGA COUNTY-3636 33-GO-RFQ / purchase of (20 Supporting Community-Driv Request for Quota Single Stage - One E Pending Impl IDA / 59000 Post Limited 21,700.00 0.00 2023-06-03 2023-07-29 2023-10-27 ) desk top computers and (20 en Development tions nvelope ementation ) multi function printers KE-KIRINYAGA COUNTY-2701 69-GO-RFQ / supply and inst Supporting Community-Driv Request for Quota Single Stage - One E IDA / 59000 Post Limited 12,500.00 0.00 Canceled 2022-01-22 2022-02-26 2022-04-27 allation of (2) 40 ft steel stru en Development tions nvelope cture container for fish feed s torage and delivery. Page 1 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-KIRINYAGA COUNTY-2690 Supporting Community-Driv Pending Impl 72-GO-DIR / provision of licen IDA / 59000 Post Direct Selection Direct 8,000.00 0.00 2022-01-17 2022-01-22 2022-02-26 2022-08-25 en Development ementation se for market technology plat form utilization KE-KIRINYAGA COUNTY-3472 55-NC-DIR / Set up, Installati Supporting Community-Driv Pending Impl on, Configuration and Commi IDA / 59000 Post Direct Selection Direct - National 22,265.00 0.00 2023-03-06 2023-03-11 2023-04-15 2023-07-14 en Development ementation ssioning of ACS (Automated Credit Scoring System) KE-KIRINYAGA COUNTY-3531 Supporting Community-Driv Request for Quota Single Stage - One E Pending Impl 88-NC-RFQ / Soil testing and IDA / 59000 Post Limited 9,875.00 0.00 2023-05-07 2023-07-02 2023-09-30 en Development tions nvelope ementation related services KE-KIRINYAGA COUNTY-3472 59-NC-DIR / Geospatial Mappi Supporting Community-Driv Pending Impl IDA / 59000 Post Direct Selection Direct - National 10,765.00 0.00 2023-05-02 2023-05-07 2023-06-11 2023-09-09 ng System (Farmer Database en Development ementation Analytics Dashboard and Mo bile Mapping App) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-KIRINYAGA COUNTY-1730 Supporting Community-Driv Consultant Qualifi Under Implement 17-CS-CQS / recruitment of s IDA / 59000 Post Open - National 50,000.00 0.00 2020-05-13 2020-10-20 2020-05-27 2020-06-17 2020-11-05 2020-07-01 2021-06-16 2020-08-05 2021-10-29 en Development cation Selection ation ervice provider for chicken v alue chain. KE-KIRINYAGA COUNTY-1730 Supporting Community-Driv Consultant Qualifi Under Implement 22-CS-CQS / recruitment of s IDA / 59000 Post Open - National 50,000.00 0.00 2020-05-13 2020-10-20 2020-05-27 2020-06-17 2020-11-05 2020-07-01 2020-06-16 2020-08-05 2021-10-29 en Development cation Selection ation ervice provider for tomatoes value chain KE-KIRINYAGA COUNTY-1730 Supporting Community-Driv Consultant Qualifi Under Implement 24-CS-CQS / recruitment of s IDA / 59000 Post Open - National 50,000.00 0.00 2020-05-13 2020-10-20 2020-05-27 2020-06-17 2020-08-07 2020-07-01 2020-08-05 2021-10-29 en Development cation Selection ation ervice provider for avocado v alue chain KE-KIRINYAGA COUNTY-1730 Supporting Community-Driv Consultant Qualifi Under Implement 26-CS-CQS / recruitment of s IDA / 59000 Post Open - National 50,000.00 0.00 2020-05-13 2020-10-20 2020-05-27 2020-06-17 2020-11-05 2020-07-01 2021-06-16 2020-08-05 2021-10-29 en Development cation Selection ation ervice provider for dairy valu e chain KE-KIRINYAGA COUNTY-1486 07-CS-QCBS / recruitment of service provision (SP's)cosort Supporting Community-Driv Quality And Cost- IDA / 59000 Post Open - National 300,967.00 0.00 Canceled 2019-04-30 2019-05-21 2019-07-04 2019-08-01 2019-08-31 2019-10-05 2019-11-09 2020-11-08 ia to provide technical and a en Development Based Selection dvisory services to farmer an d community organisations i n prioritized value chains. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 Contents Project Overview....................................................................................................1 Overview of Country, Borrower and Marketplace ..................................................3 Procurement Risk Analysis.....................................................................................6 Procurement Objectives.........................................................................................7 Recommended Procurement Approach for the Project ..........................................8 ANNEX 1 ..............................................................................................................11 1 Punjab Resource Improvement and Digital Effectiveness Project Procurement Strategy for Development (PPSD) Project Overview 1.1 The Government of Punjab intends to implement several programs aimed at improving business processes for tax administration and financial management, streamlining public investment management, and modernizing service delivery. The TA component will support finance ICT investments and technical assistance (TA) to accelerate the implementation of these objective, principally to advance the larger objectives of the Government reform program. . a. Window-1 will be financed through the Bank’s Program for Results (PforR) instrument and will comprise three result areas; a) Budget Formulation and Fiscal Risk Management; b) Enhanced use of digital technology in public sector and c; increased in Own Source Revenue. b. Window-2 will use the IPF instrument for Technical Assistance (TA) and Institutional Strengthening (IS The activities that the TA component will finance are necessary to embed the new business processes and specialized technical support to implement capacity-enhancing innovations including fiscal planning, monitoring and management of fiscal risks, business process improvement, advanced revenue forecasting and tax audit techniques, database integration and change management. 1.2 The details of window-1 P4R have been addressed in the FSA, and this PPSD addresses the window 2 (IPF component), which will be in the form of a TA to provincial government agencies viz. Finance Department and Planning and Development Department. Country: PAKISTAN Full Project Name: Punjab Public Resource Management Program Total Finance ($): 330 million Project Number: P171417 Summary of Project to strengthen budget formulation and Development Objectives fiscal risk mitigation; increase the use of digital technologies for delivery of selected public services; and improve collection of OSR 2 1.3 Key Procurements under the project: the Bank’s contribution in the project is US $ 330 m out of which about 30 million will be allocated for Technical Assistance/Capacity Building and Program Management. TA will be executed by FD and P&DD, where program specific units Public Financial Management Reform Unit (PFMRU), and Program Support Unit (PSU) shall be established Procurement activities will include consultancy firms of small to medium size and individual consultants, besides some office equipment for establishment of the project units. Major activities include: i. Firms Consultancy contracts Consulting Firms will be hired by PFMU and PSU for Technical Assistance (TA) Component. The major consulting firms identified are given below: S. Consultant Firms Cost USD No PFMU 1 Capacity Building, Change management and 300,000 gender mainstreaming in PFM systems 2 Pension Sustainability Analysis 60,000 3 Functional Reviews & Business process re- 1,000,000 engineering of FD and 03-Tax Authorities PRA , BOR & ET&NC 4 Analytical & Research support of PRA , BOR & 1,500,000 ET&NC 5 Third Party Validation of DLI achievements 500,000 6 Internal Audit 300,000 PSU 7 Development of a comprehensive inter-operability 500,000 framework and associated rules and regulations 8 Development of sector masterplans, linked with 500,000 Provincial Growth Strategy, RISE strategy and Spatial Strategy 9 Business review for project preparation, Monitoring 2,000,000 and Evaluation, ADP guidelines, Digitization and change management of Public Investment Policy under P&D Board 10 Development of rules and regulations to facilitate e- 500,000 government including digital signature, digital identity protection 11 Development of standard operating / procedures on 250,000 e-waste management and Social assessment 12 E-Procurement Implementation Support Firm 500,000 3 13 Training Strategy Implementation and updating 250,000 PPRA Regulatory Framework 14 PPRA MIS analysis and support 150,000 ii. Individual Consultants: the entire staffing of PFMU and PSU is to be hired from the market. There are 13 individuals identified for PFMU including the head, technical experts for BPR, tax, PFM, MIS, IT and procurement. It has been reviewed by the task team that the individual staffing is for identification of the various actions agreed under the program and to support its implementation; and there is no duplication for supporting the unit to be prepared under the DLI 1. The identified charge rates are aligned with the government’s MP scales; whereas for the Head PFMU position MP3 plus scale has been estimated. PSU staffing includes the head, technical experts for public sector, legal, gender and social aspects, and procurement. the hiring shall be on market rates. The consultants will be hired for the duration of the project. iii. Goods General office set up equipment and vehicles are identified which include computers, printers, scanners, plotter and office furniture etc. to be procured for the implementation units. All identified activities fall under shopping procedures. 1.4 Key Conclusions This PPSD covers the US$ 30 m of the TA component which will be implemented by the two units, with US $ 15 m allocation for each. The procurement outlays are such that largest of the consultancies is expected to cost US$ 2 m. Large number of individual hiring for the two units is planned and suitable candidates will need to be identified through dissemination as well as head hunting. Overview of Country, Borrower and Marketplace 2.1 Operational Context Governan The proposed Program will support selected ce actions under RISE Punjab and the PFMRS amounting to US$524 million. Specifically, the Program will support actions under the PFM and Governance Reform pillars (pillars D and E respectively) of the RISE Punjab, and discrete activities in various pillars of the PFMRS. The expected results correspond with the 4 Government’s expenditure framework across three Result Areas as follows: • Result Area 1: Strengthened budget formulation and fiscal risk management. • Result Area 2: Increased use of digital technology for delivery of selected public services. • Result Area 3: Improved collection of OSR. Technical Assistance An Investment Project Financing (IPF) portion worth US$30 million will support the PforR. The IPF will finance activities to support the achievement and sustainability of Program results. The TA will support implementing entities to develop their capacity for achieving the program milestones Generally planning and budgeting are the two areas where delays due to administrative procedures hinder timely implementation. In this Program the main counter parts and coordinating units are P&D and Finance, and it is expected that the administrative approvals and budged releases would not be delayed. There will be a need to constantly engage with the implementing entities for internalizing the systems; for example the e-procurement implementation is to be done by major expenditure entities. Economic The Program’s net economic impact is expected to be positive and to accrue beyond the duration of the Program. While an accurate estimation of the returns to investment of PFM reforms in the Program are difficult to make, inferences for economic evaluation can be made based on research carried out elsewhere. For example, an analysis carried out by IMF finds that digitalizing government payments in developing countries could save roughly 0.8–1.1 percent of GDP annually.1 In addition, efficiency gains as a result of risk mitigation measures in pension liability and commodity financing during the five years is estimated at US$ 500 million. The cumulative benefits for the increased OSR tax receipts over the next five years are estimated at US$1.5 billion. Sustainabi The Program has widespread buy-in at the strategic level lity through ownership of the PFM Reform Strategy, which is supportive of the Post Covid19 Strategy of GoPj (RISE Punjab). The GoPj has established a PFM Reforms Oversight Committee, headed by the Minister of Finance, which acts as a Steering Committee to provide high-level leadership for PFM reforms. GoPj has an extensive 1Sanjeev Gupta, Michael Keen, Alpa Shah and Genevieve Verder (2017). The Value of Digitalizing Government Payments in Developing Economics. Washington, DC: International Monetary Fund. 5 experience of managing PforR Program as evidenced by satisfactory completion of PPMRP. Support will be provided through the TA component for Business Process Re-engineering in implementing entities, functional reviews of the Finance Department, P&D Department, and the three tax authorities; development of e-service capabilities, development of a comprehensive inter-operability framework and associated rules and regulations to enable integration of databases), Punjab’s PFM regulatory framework and guidelines for their implementation; establishment of a Tax Policy Unit (TPU) in the Finance Department; design of performance framework, establishment of a Disaster Risk Fund for Local Governments; and revision of the rules and regulations and revisions for the Provincial Finance Commission. revision of ADP guidelines and rules. The above activities converge towards developing systems for which there is a complete ownership in the government and these areas are identified in the policy documents. Technolog One of the result areas is interoperability of the various y technological interventions. Besides, automation of services. e governance and e-waste management will all utilize the latest available technology. 2.2 Key Conclusions The overall operational context is well grounded in the provincial governments policies and strategies, and therefore, implementation deadlocks are not expected. The TA provides the required support to facilitate execution of the agreed actions for achieving results. Buy in from major procuring departments will be required for roll out of e- procurement. 2.3 Client Capability Assessment Execution of the TA component is the responsibility of PFMU and PSU. Constitution of PFMU has been approved by Finance Department, and he organogram is as follows: 6 For PSU constitution has been discussed with P&D, and official decision is awaited. The procurement plan includes the individual consultants as identified for the two units. The first project activity will be staffing of these two units, which is expected by October/November 2020. Discussion was made to hire one contract management and procurement staff for contracting and implementation of activities under the TA, however it was preferred to hired separate procurement staff for each unit. The procurement staff(s) will be working in close coordination with the technical staff within the units. The capacity of the units will be re-assessed as soon as core staff is hired and the units are functional. It will be preferred that the procurement staff has some experience of the Bank/multi lateral procurements, and training will be provided to all core staff as soon as they are hired. The delegations to the units are such that the respective Head(s) will be authorized to make procurement decisions and sign contracts. the evaluation committees will be formed within the respective units. PPSD will be updated with committee constitution as soon as hiring is done. SWOT ANALYSIS Strengths Weaknesses • Concept note for PFMU is • The two units are neither approved by the Chief staffed nor operational Minister. • Continued availability of the • FD has access to budget hired staff will need to be resources and therefore the ensured. issue of delays in budget • Hiring of all individual releases shall not be consultants needs to be applicable to the PFMU. completed within six months • PSU shall be based in PnDD of the project effectiveness. which has extensive experience in executing 7 PforR and TA based programs. Opportunities Threats • PFM RU shall work under the • Program effectiveness watch of Finance Minister. depends on support from the • Due to present challenges, top management. there is a greater awareness • During the initial period, about fiscal challenges and robust hand holding will be need for business continuity required. • Adequate staffing is essential for effective implementation 2.4 Key Conclusions Efficient implementation of TA is essential for successful Program results. The two units would be responsible for TA execution, both are yet to be set up hence the assessment would be updated after their establishment. 2.5 Market Analysis The procurement outlays include consultancy firms in the areas of analytical support, taxation, business process re-engineering, information technology and systems development, functional reviews, financial management & audit, procurement regulations, e-procurement roll out support, and third party validation. The estimated costs of the identified activities do not exceed US $ 2 m for an individual assignment. There is a robust pool of potential firms available in national market as well as international market who would be interested to participate in the various selections. The two units will disseminate the project opportunities to these potential firms to solicit optimum response. Some known market players are listed as Annex 1. 2.6 Key Conclusions The contracts currently identified under the project are of small/medium value and low/medium risk. The market is adequate to meet the requirements, and the potential firms have track record of having conducted the identified activities in their respective area of expertise. Procurement Risk Analysis 8 3.1 For achieving the targets and goals, risk analysis is to be critically made and should cover well versed mitigation measures. The risks and mitigation measures are tabulated below: Description of Risk Timeline Risk Area Mitigation Owner Efficiency of Hiring at PFMU and PSU FD, PnDD Core staff processing and will be done quickly and hired/deployed decision making contracts will be offered Within three for multiple years to months of attract good approval. professionals Decision making for FD, PnDD Agreed with procurement and the Bank. PSU contract award devolved is yet to be to PFM RU and PSU notified Delays in ToRs for individual FD, PnDD Ongoing procurement consultants and firms shall be prepared and approved before the project effectiveness. Participation of FD, PnDD Awareness dissemination Within three bidders: Some to the potential firms months of potential bidders regarding the Bank’s Operation may shy away procurement procedures approval from and contract participation management. given the perception of delays in payments and completion. Procurement and Dedicated staff hired at FD, PnDD Within three contract PFMU and PSU months of management Operation competency approval Training to relevant of World As soon as PFM RU and PSU Bank staff is hired 3.2 Based on the above assessment, size of procurement packages, identified risks and mitigation measures, the risk of the TA component is Moderate. The implementation units are planned to be staffed by Nov/Dec 2020, after which the selection of consulting firms will commence. The risk reassessment will however be done as soon as the implementation units are staffed. 9 Procurement Objectives 4.1 Project Procurement Development Objectives (PPDO): The project procurement development objectives are the following: i. To ensure effective contract management that contributes towards achieving the PDO 4.2 Project Procurement Result Indicator: Achievement of the PPDO will be measured by the following indicators i. Good competition and contract prices within 10% of the estimated costs. ii. 100% of the contract delays captured, and extensions provided before contract closing date. iii. Closing of all contracts in line with project documents Recommended Procurement Approach for the Project 5.1 The identified procurement activities and the expected ones to be identified include consultancies for which all the available options (QCBS, FBS, LCS, QBS, CQS, and Direct selection) are applicable. However, the current plan shows QCBS and CQS as options. Identified goods are small packages are office equipment to be procured through Shopping. Selection of individual consultants will be done through dissemination as well as head hunting. 5.2 National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Sindh Public Procurement Rules, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: a. The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. b. For national open competitive procurement, only the model procurement documents acceptable to the World Bank, shall be used. c. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s 10 inspection and audit rights. d. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts e. Access to procurement opportunities shall not be restricted to firms that have pre-registered and/or paid a registration fee. f. No preference of any kind shall be given to national bidders in the bidding process. When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. 5.3 Procurement thresholds: The procurement plan shall set forth those contracts which shall be subject to the World Bank’s mandatory Prior Review as well as ex-post review. The procurement thresholds will be applicable as part of the procurement framework, to the extent of Moderate Risk Projects. Type of High Risk Substantial Moderate Low Risk Procurement Risk Risk Works, S&I 5 10 15 20 Goods, 1.5 2 4 6 Information Tech& Non- consulting Consultants: 0.5 1 2 4 Firms Consultants: 0.2 0.3 0.4 0.5 Individuals 5.4 Procurement Plan The procurement plan of the identified activities is tabulated below: S. Consultant Firms Estimate Bank Procureme Risk Date of No d Cost Oversigh nt commenc (USD) t Approach ing selection PFMU 1 Capacity Building, 300,000 Post Consultancy Substanti Dec 2020 Change CQS al management and gender mainstreaming in PFM systems 2 Pension 60,000 Post Consultancy Moderate Jan 2021 Sustainability CQS Analysis 11 3 Functional Reviews 1,000,000 Post Consultancy Substanti Dec 2020 & Business process QCBS al re-engineering of FD and 03-Tax Authorities PRA , BOR & ET&NC 4 Analytical & 1,500,000 Post Consultancy Substanti April 2021 Research support of QCBS al PRA , BOR & ET&NC 5 Third Party 500,000 Post Consultancy Moderate Dec 2020 Validation of DLI QCBS achievements 6 Internal Audit 300,000 Post Consultancy Low Dec 2020 CQS PSU 7 Development of a 500,000 Post Consultancy Moderate Dec 2020 comprehensive QCBS inter-operability framework and associated rules and regulations 8 Development of 500,000 Post Consultancy Substanti Dec 2020 sector masterplans, QCBS al linked with Provincial Growth Strategy, RISE strategy and Spatial Strategy 9 Business review for 2,000,000 Prior Consultancy Substanti April 2021 project preparation, QCBS al Monitoring and Evaluation, ADP guidelines, Digitization and change management of Public Investment Policy under P&D Board 10 Development of 500,000 Post Consultancy Moderate Jan 2021 rules and QCBS regulations to facilitate e- government including digital signature, digital identity protection 11 Development of 250,000 Post Consultancy Moderate Jan 2021 standard operating / QCBS procedures on e- waste management and Social assessment 12 12 E-Procurement 500,000 Post Consultancy Substanti April 2021 Implementation QCBS al Support Firm 13 Training Strategy 250,000 Post Consultancy Moderate Dec 2020 Implementation and CQS updating PPRA Regulatory Framework 14 PPRA MIS analysis 150,000 Post Consultancy Moderate Dec 2020 and support CQS 13 ANNEX 1 IT Systems Firms Sr. Name of firm Address No. 01 NETSOL Technologies Net Sol Avenue, Main Ghazi Road ،Lahore Inc. 54792. Ph. 042-111448800 02. Teradata Pakistan Telecom Foundation Complex, Ground Floor, 7-Mauve Area, G-9/4, Islamabad Ph. 051-2011111 03. Ovex Technologies 1st Floor, KSL Complex, Software Technology Park, Plot No. 156, I-9/3 Industrial Area Islamabad Ph. 0514430721 04. TRG Tech Pakistan Plot No. 7, Aitchison Street, 1-Km Thokar Niaz Baig, Raiwind Road, Lahore-54000 Ph. 042-111874874 05. Systems (Pvt.) Ltd. E-5, Central Commercial Area, Shaheed-e- Millat Road, Karachi Ph. 021-34549385-87 06. Microsoft Pakistan 42-A, Abu Bakar Block, New Garden Town, Lahore Ph: 042-35867781-82 BPR and Financial Management & Audit Firms Sr. Name of firm Address No. 01 AF Ferguson & Co 23-C, Aziz Avenue, Canal Bank, Gulberg-V, P.O.Box 39, Lahore-54660, Pakistan Ph: 042-35715868-71/35775747-50 02. UHY Hassan Naeem & 193-A Shah Jamal, Lahore-54000 Pakistan. Co Ph: 042-35403550/042-354035510 03. Ernst and Young (EY) 96-B-1, 4th Floor, Pace Mall Building Ford Rhodes M.M.Alam Road, Gulberg-II P.O Box 104, Lahore-54660 Ph: 042-35778402-11 04. KPMG Taseer Hadi 2nd Floor, Servis House, 2-Main Gulberg and Co. Chartered Jail Road Lahore. Accountants Ph: 042-35790901-6 05. National Engineering NESPAK House, 1-C, Block-N, Model Town services Pakistan Extention Lahore-54700, Pakistan (Pvt) Ltd Ph: 042-9909000 Urban Planning & Engineering Firms 14 Sr. Name of firm Address No. 01 NESPAK 1-C Block N ،Model Town Extension ، Lahore 54000. Ph. 042-99090000 02. M/s. JERS Engineering 124-Model Town, Lahore. Consultant Ph. 042-35847124 03. M/s. Asian Consulting 251-A, HBFC, Faisal Town, Lahore, Engineers Ph. 042-35167445 04. M/s. National 28-M, Mader-e-Millat Road, Development Quaid-e-Azam Industrial Estate, Consultant (Pvt.) Lahore-54760 Limited Ph. 042-35215942-46 05. M/s. Osmani & Osmani House. 245/2K, Block-6, PECHS Company Pvt. Ltd. Karachi. Ph. 021-34546541-42 06. M/s ACE Consultants 1-C/2, M.M. Alam Road, Gulberg-III, Lahore-54660 Ph: 042-35759417-9 07 G3 Engineering 57-M, Gulberg III, Lahore,Pakistan Consultants (Pvt) Ltd Ph: 042-35441641-3 08 MM Pakistan (Pvt) Ltd 2nd Floor, CTI Building 27 Empress Road, lahore Ph: 042-36300460/ 042-36300440 15 PROCUREMENT Pakistan : Punjab Resource Improvement and Digital Effectiveness PLAN General Information Country: Pakistan 2021-11-01 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171417 GPN Date: Project Name: Punjab Resource Improvement and Digital Effectiveness Loan / Credit No: IBRD / 91700 Program Support Unit Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PSU-257312-GO-RFQ / Pr oc of i) Computer Server (01 No), ii) Laptop (11 Nos) iii) D esktop Computer (04 Nos iv) Request for Quota Single Stage - One E Scanner (02 Nos) v)Heavy Du IBRD / 91700 Post Open - National 92,078.00 48,598.28 Signed 2021-10-20 2022-02-18 2021-12-15 2022-04-29 2022-06-13 tions nvelope ty Laser Printer B&W Duplex/ Network (01 No) vi.Heavy Du ty Colour Laser Printer (01 N o) vii) Desktop Printer (10 N os), viii)UPS (3 Nos) PK-PSU-257315-GO-RFQ / Pr oviding and Installation of Au Request for Quota Single Stage - One E IBRD / 91700 Post Open - National 48,303.00 13,651.05 Signed 2021-10-20 2022-02-18 2021-12-15 2022-04-29 2022-06-13 dio/Video Conferencing syste tions nvelope m with Multimedia Equipmen t with LED 70" PK-PSU-257316-GO-RFQ / Pr oviding & Installation of: Request for Quota Single Stage - One E Under Imple IBRD / 91700 Post Open - National 9,057.00 0.00 2021-10-20 2022-02-18 2021-12-15 2022-06-13 i)Photocopier=02 Nos tions nvelope mentation ii) Fax Machine=01 No PK-PSU-257317-GO-RFQ / Pr oviding & Installation of: Request for Quota Single Stage - One E IBRD / 91700 Post Open - National 6,038.00 4,442.65 Signed 2021-10-20 2022-02-18 2021-12-15 2022-04-29 2022-06-13 i) Telephone Exchange=1 No tions nvelope ii) Digital Set=15 Nos PK-PSU-257318-GO-RFQ / Pr oviding & Installation of: i) Water Dispenser = 10 Nos Request for Quota Single Stage - One E IBRD / 91700 Post Open - National 3,985.00 2,142.16 Signed 2021-10-20 2022-02-18 2021-12-15 2022-04-29 2022-06-13 ii) Microwave Oven = 2 Nos tions nvelope iii) Fridge = 2 Nos PK-PSU-257319-GO-RFQ / Pr Request for Quota Single Stage - One E Pending Impl oviding & Installation of Gene IBRD / 91700 Post Open - National 24,152.00 0.00 2021-10-20 2021-12-15 2022-06-13 tions nvelope ementation rator 50 KVA (1 No) PK-PSU-257321-GO-RFQ / Pr oviding & Installation of: Request for Quota Single Stage - One E Pending Impl IBRD / 91700 Post Open - National 22,944.00 0.00 2021-10-20 2021-12-15 2022-06-13 Air Conditioners tions nvelope ementation (1+1.5+4 Tons)= 20 Nos PK-PSU-257322-GO-RFQ / Pr Request for Quota Single Stage - One E Under Imple ocurement of Motorcycles (1 IBRD / 91700 Post Open - National 1,509.00 0.00 2021-10-20 2022-11-18 2021-12-15 2022-06-13 tions nvelope mentation 00-CC)=2 Nos PK-PSU-257323-GO-RFQ / Pr Request for Quota Single Stage - One E Under Imple ocurement of Vehicles (1300 IBRD / 91700 Post Open - National 38,643.00 0.00 2021-10-20 2022-11-18 2021-12-15 2022-06-13 tions nvelope mentation CC)=2 Nos PK-PSU-257325-GO-RFB / Pr ocurement of Equipment for development of Punjab Busin ess Portal for automation of Single Stage - One E Pending Impl IBRD / 91700 Post Request for Bids Open - National 600,000.00 0.00 2021-10-15 2021-10-20 2021-12-01 2021-12-31 2022-02-04 2022-08-03 Business Registrations, Licen nvelope ementation ses, Certificates and Other P ermits (RLCOs) under Pakista n Regulatory Modernization I nitiative (PRMI). PK-PSU-257324-GO-RFQ / Pr Request for Quota Single Stage - One E Pending Impl oviding & Installation of: IBRD / 91700 Post Open - National 90,000.00 0.00 2021-12-10 2022-02-04 2022-08-03 tions nvelope ementation Office Furniture and Fixtures PK-PSU-257311-GO-RFB / Eq Open - Internationa Single Stage - One E Pending Impl uipment / Hardware for Digiti IBRD / 91700 Post Request for Bids 1,980,000.00 0.00 2022-10-10 2022-10-15 2022-11-26 2022-12-26 2023-01-30 2023-07-29 l nvelope ementation zation of P&D Board. PK-PSU-363634-GO-RFB / Vi Single Stage - One E Under Imple IBRD / 91700 Post Request for Bids Open - National 518,175.00 0.00 2023-05-30 2023-06-01 2023-06-04 2023-06-08 2023-07-16 2023-08-15 2023-09-19 2023-10-19 deo Wall Solution for auditori nvelope mentation um PK-PSU-363640-GO-RFQ / Pr Request for Quota Single Stage - One E Under Imple IBRD / 91700 Post Open - National 44,406.00 0.00 2023-06-04 2023-07-30 2024-01-26 ocurement of IP Phone (50 N tions nvelope mentation os) PK-PSU-363644-GO-RFQ / Pr Request for Quota Single Stage - One E Under Imple ocurement of Motorized Multi IBRD / 91700 Post Open - National 4,440.00 0.00 2023-06-04 2023-07-30 2023-08-29 tions nvelope mentation media Screen (01 No) PK-PSU-363648-GO-RFQ / Vi Request for Quota Single Stage - One E Under Imple IBRD / 91700 Post Open - National 14,800.00 0.00 2023-06-04 2023-07-30 2023-08-02 deo wall Shifting / Installation tions nvelope mentation PK-PSU-363650-GO-RFQ / Lic Request for Quota Single Stage - One E Under Imple IBRD / 91700 Post Open - National 14,800.00 0.00 2023-06-04 2023-07-30 2023-08-29 ensed Software tions nvelope mentation PK-PSU-363651-GO-RFQ / IP Request for Quota Single Stage - One E Under Imple IBRD / 91700 Post Open - National 7,424.00 0.00 2023-06-04 2023-07-30 2023-08-29 Security Cameras Solution tions nvelope mentation Page 1 PK-PSU-363654-GO-RFQ / Da Request for Quota Single Stage - One E Under Imple IBRD / 91700 Post Open - National 73,500.00 0.00 2023-06-04 2023-07-30 2023-08-29 ta Center Equipment tions nvelope mentation PK-PSU-363655-GO-RFQ / All Request for Quota Single Stage - One E Under Imple IBRD / 91700 Post Open - National 15,500.00 0.00 2023-06-04 2023-07-30 2023-08-29 in One Collaboration Device tions nvelope mentation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PSU-257328-NC-RFQ / Hir Request for Quota Single Stage - One E Pending Impl ing of Security Firm (Framew IBRD / 91700 Post Open - National 25,500.00 0.00 2021-10-20 2021-12-15 2027-12-15 tions nvelope ementation ork Contract) PK-PSU-257329-NC-RFQ / Hir Request for Quota Single Stage - One E Under Imple ing of Vehicle Rental Service IBRD / 91700 Post Open - National 25,500.00 0.00 2021-10-25 2022-06-23 2021-12-20 2027-12-20 tions nvelope mentation s (Framework Contract) PK-PSU-265005-NC-RFB / Hir Single Stage - One E Under Imple ing of Event Management Fir IBRD / 91700 Post Request for Bids Open - National 300,000.00 0.00 2021-12-15 2022-07-16 2021-12-20 2022-08-16 2022-01-31 2022-08-23 2022-03-02 2022-08-31 2022-04-06 2026-12-15 nvelope mentation m (framework contract) PK-PSU-311977-NC-RFB / Hir Single Stage - One E Under Imple ing of Communication Firm ( IBRD / 91700 Post Request for Bids Open - National 500,000.00 0.00 2022-09-07 2022-09-29 2022-09-12 2022-09-29 2022-10-24 2022-10-31 2022-11-23 2022-11-11 2022-12-28 2025-08-25 nvelope mentation under framework contract) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PSU-257284-CS-QCBS / H iring of consultancy firm for i Quality And Cost- Pending Impleme mplementation of a compreh IBRD / 91700 Post Open - National 500,000.00 0.00 2021-10-12 2021-11-02 2021-12-16 2022-01-13 2022-02-12 2022-03-19 2022-04-23 2023-04-23 Based Selection ntation ensive inter-operability fram ework and associated rules a nd regulations PK-PSU-257286-CS-QCBS / H Quality And Cost- Under Implement IBRD / 91700 Post Open - National 400,000.00 0.00 2021-10-12 2022-02-24 2021-11-02 2022-03-28 2021-12-16 2022-11-03 2022-01-13 2022-12-05 2022-02-12 2022-12-28 2022-03-19 2023-01-26 2022-04-23 2027-04-04 iring of firm for Internal Audit Based Selection ation PK-PSU-257293-CS-CQS / Hir ing of consultancy firm for de Consultant Qualifi Under Implement velopment of standard opera IBRD / 91700 Post Open - National 50,000.00 0.00 2021-10-12 2022-02-09 2021-11-02 2022-03-28 2021-12-16 2022-08-27 2022-01-15 2022-10-03 2022-02-19 2022-08-18 cation Selection ation ting procedures (SOPs) on e- waste management and Soci al assessment PK-PSU-257691-CS-QCBS / H iring of Consultancy firm for Quality And Cost- IBRD / 91700 Prior Open - National 1,800,000.00 0.00 Canceled 2021-12-05 2022-01-24 2021-12-26 2022-03-25 2022-02-08 2022-03-08 2022-04-07 2022-05-12 2022-06-16 2024-06-16 Public Investment Manageme Based Selection nt Support for Planning & De velopment Board PK-PSU-257296-CS-CQS / Tra Consultant Qualifi Pending Impleme ining & Capacity Building for IBRD / 91700 Post Open - National 150,000.00 0.00 2021-10-12 2021-11-02 2021-12-16 2022-01-15 2022-02-19 2022-08-18 cation Selection ntation public investment managem ent . PK-PSU-257306-CS-CDS / De velopment of Punjab Busines s Portal for automation of Bu Quality And Cost- Pending Impleme siness Registrations, License IBRD / 91700 Post Open - National 400,000.00 0.00 2021-12-15 2022-01-05 2022-02-18 2022-03-18 2022-04-17 2022-05-22 2022-06-26 2023-06-26 Based Selection ntation s, Certificates and Other Per mits (RLCOs) under Pakistan Regulatory Modernization Init iative (PRMI) PK-PSU-265002-CS-CQS / Hir ing of Consultancy firm for St Consultant Qualifi Pending Impleme IBRD / 91700 Post Open - National 150,000.00 0.00 2021-12-05 2021-12-26 2022-02-08 2022-03-10 2022-04-14 2022-10-11 ocking of Digitalization of Pu cation Selection ntation blic Services in Punjab PK-PSU-311986-CS-CQS / Hir ing of consulting firm for con ducting Third Party Evaluatio Consultant Qualifi Under Implement IBRD / 91700 Post Open - National 40,000.00 0.00 2022-09-14 2022-09-23 2022-10-05 2022-10-12 2022-11-18 2022-12-18 2023-01-22 2023-07-21 n (TPE) of Process Orchestrat cation Selection ation ion Programming for Intra-Op erability of CGA System with other systems PK-PSU-317772-CS-QCBS / H Quality And Cost- Under Implement iring of consulting firm for Pr IBRD / 91700 Post Open - National 300,000.00 0.00 2022-09-30 2022-09-28 2022-10-21 2022-11-04 2022-12-04 2023-01-01 2023-01-31 2023-03-07 2023-04-11 2026-04-10 Based Selection ation ogram Impact Assessment PK-PSU-324800-CS-QCBS / H iring of consulting firm for Pu Quality And Cost- Open - Internationa Under Implement blic Investment Management IBRD / 91700 Post 1,800,000.00 0.00 2022-11-09 2022-11-11 2022-11-30 2023-01-06 2023-01-13 2023-02-24 2023-02-10 2023-05-02 2023-03-12 2023-04-16 2023-05-21 2024-11-19 Based Selection l ation Support for Planning & Devel opment Board, Punjab PK-PSU-341982-CS-QCBS / H iring of consultancy firm for I Quality And Cost- Under Implement mplementation Support to Pu IBRD / 91700 Post Open - National 272,460.00 0.00 2023-03-03 2023-02-23 2023-03-24 2023-03-13 2023-05-07 2023-06-04 2023-07-04 2023-08-08 2023-09-12 2024-09-11 Based Selection ation njab PPRA for E-Procurement System under PRIDE progra m PK-PSU-357879-CS-CQS / Hir ing of consultancy firm for pr oviding Technical Support to Consultant Qualifi Under Implement IBRD / 91700 Post Open - National 300,000.00 0.00 2023-04-27 2023-05-03 2023-05-18 2023-05-25 2023-06-30 2023-07-14 2023-08-11 2025-06-30 Planning & Development Boa cation Selection ation rd, Government of Punjab, un der Framework Agreement INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 PK-PSU-255809-CS-INDV / U Individual Consult IBRD / 91700 Post Open 243,290.00 0.00 Canceled 2021-09-30 2021-11-02 2021-11-26 2021-12-17 2022-01-21 2026-12-25 nit Head ant Selection PK-PSU-255817-CS-INDV / Pr Individual Consult IBRD / 91700 Post Open 154,821.00 127,967.10 Signed 2021-09-30 2021-11-02 2021-11-26 2022-04-12 2021-12-17 2022-04-26 2022-01-21 2022-04-29 2026-12-25 ocurement Specialist ant Selection PK-PSU-255819-CS-INDV / Fi Individual Consult IBRD / 91700 Post Open 154,821.00 0.00 Canceled 2021-09-30 2021-11-02 2021-11-26 2021-12-17 2022-01-21 2026-12-25 nancial Management Speciali ant Selection st PK-PSU-255823-CS-INDV / Pu Individual Consult IBRD / 91700 Post Open 154,821.00 127,887.35 Signed 2021-09-30 2021-11-02 2021-11-26 2022-03-16 2021-12-17 2022-04-20 2022-01-21 2022-04-26 2026-12-25 blic Sector Specialist ant Selection PK-PSU-255826-CS-INDV / In Individual Consult formation & Communication IBRD / 91700 Post Open 154,821.00 0.00 Canceled 2021-09-30 2021-11-02 2021-11-26 2022-04-19 2021-12-17 2022-05-06 2022-01-21 2026-12-25 ant Selection Technology (ICT) Specialist PK-PSU-255828-CS-INDV / M Individual Consult IBRD / 91700 Post Open 154,821.00 127,887.35 Signed 2021-09-30 2021-11-02 2021-11-26 2022-03-30 2021-12-17 2022-04-20 2022-01-21 2022-04-26 2026-12-25 &E Specialist ant Selection PK-PSU-255840-CS-INDV / Le Individual Consult IBRD / 91700 Post Open 154,821.00 127,887.35 Signed 2021-09-30 2021-11-02 2021-11-26 2022-04-07 2021-12-17 2022-04-26 2022-01-21 2022-05-15 2026-12-25 gal Expert ant Selection PK-PSU-255860-CS-INDV / C Individual Consult IBRD / 91700 Post Open 154,821.00 0.00 Canceled 2021-09-30 2021-11-02 2021-11-26 2021-12-17 2022-01-21 2026-12-25 ommunication Specialist ant Selection PK-PSU-257584-CS-INDV / E Individual Consult nvironment, Social Safeguard IBRD / 91700 Post Open 154,821.00 127,887.35 Completed 2021-10-12 2021-11-02 2021-11-30 2022-04-07 2021-12-21 2022-04-26 2022-01-25 2022-05-19 2027-01-25 2022-06-02 ant Selection and Gender Specialist PK-PSU-280536-CS-CDS / Hir ing of consultancy firm for i Pending Impleme IBRD / 91700 Post Direct Selection Direct 100,000.00 0.00 2022-04-05 2022-04-15 2022-06-19 2022-12-16 mpact assessment of govern ntation ance reforms / interventions PK-PSU-286804-CS-INDV / U Individual Consult Under Implement IBRD / 91700 Post Open 243,290.00 0.00 2022-04-01 2022-06-07 2022-05-20 2022-06-10 2022-07-15 2026-06-30 nit Head ant Selection ation PK-PSU-286807-CS-INDV / Fi Individual Consult Under Implement IBRD / 91700 Post Open 154,821.00 0.00 2022-04-01 2022-06-07 2022-05-20 2022-06-10 2022-07-15 2026-06-30 nancial Management Speciali ant Selection ation st PK-PSU-299335-CS-INDV / Hi Individual Consult Under Implement IBRD / 91700 Post Open 154,821.00 0.00 2022-06-24 2022-07-15 2022-08-12 2022-09-02 2022-10-07 2027-10-06 ring of Communication Speci ant Selection ation alist PK-PSU-302829-CS-INDV / Hi Individual Consult ring of Environmental, Social IBRD / 91700 Post Open 154,821.00 0.00 Canceled 2022-07-27 2022-07-29 2022-09-14 2022-10-05 2022-11-09 2027-11-08 ant Selection Safeguard and Gender Speci alist PK-PSU-308776-CS-INDV / Hi Individual Consult Under Implement IBRD / 91700 Post Limited 12,076.00 0.00 2022-08-24 2022-08-23 2022-09-03 2022-09-13 2022-09-25 2022-12-24 ring of Labor Expert ant Selection ation PK-PSU-308780-CS-INDV / Hi Individual Consult Under Implement IBRD / 91700 Post Limited 30,190.00 0.00 2022-08-24 2022-08-23 2022-09-03 2022-09-13 2022-09-25 2023-03-24 ring of Social Specialist ant Selection ation PK-PSU-341976-CS-INDV / Pr ocurement Expert - Re-writin Individual Consult Under Implement IBRD / 91700 Post Limited 9,082.00 0.00 2023-02-24 2023-02-27 2023-03-06 2023-03-16 2023-03-28 2023-04-12 g of PPRA Legal Framework u ant Selection ation nder PRIDE program PK-PSU-341979-CS-INDV / Le Individual Consult Under Implement gal Expert - Re-writing of PPR IBRD / 91700 Post Limited 24,219.00 0.00 2023-02-24 2023-02-27 2023-03-06 2023-03-16 2023-03-28 2023-07-26 ant Selection ation A Legal Framework under PRI DE program PK-PSU-352318-CS-INDV / Hi Individual Consult Under Implement IBRD / 91700 Post Limited 29,062.00 0.00 2023-03-31 2023-04-11 2023-04-05 2023-04-15 2023-04-29 2023-10-26 ring of Communication Speci ant Selection ation alist PK-PSU-357383-CS-INDV / Hi Individual Consult Under Implement ring of Environmental, Social IBRD / 91700 Post Open - National 154,821.00 0.00 2023-04-26 2023-04-20 2023-06-14 2023-07-05 2023-08-09 2025-06-30 ant Selection ation Safeguard and Gender Speci alist PK-PSU-357384-CS-INDV / Hi Individual Consult Under Implement IBRD / 91700 Post Open - National 154,821.00 0.00 2023-04-26 2023-04-20 2023-06-22 2023-07-13 2023-08-17 2025-06-30 ring of ICT Specialist ant Selection ation Page 3 PROCUREMENT PLAN (Textual Part) Project information: Democratic Republic Democratic of Congo – Multisectoral Child Nutrition and Health Project - P168756 Project Implementation agency: UGP PDSS Date of the Procurement Plan: April 2019 Period covered by this Procurement Plan: April 2019 – October 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 and revised November 2017) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Borrower’s Public Procurement Law No 10/010 of April 27, 2010 (PPL) and the Manual of Procedures of the PPL as per Borrower’s Decree No 10/22 of June 2, 2010, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (a) Standard Bidding Documents: All standard bidding documents to be used for the Project under NCB shall be found acceptable to the World Bank before their use during the implementation of Project; (b) Eligibility: Eligibility of bidders and acceptability of their goods and services shall not be based on their nationality and/or their origin; and association with a national firm shall not be a condition for participation in a bidding process. Therefore, except for the ineligibility situations referred to in paragraphs 1.10(a) (i) and 1.10(a) (ii) of the Procurement Guidelines, the eligibility of bidders must be based solely on their qualification, experience and capacity to carry out the contract related to the specific bidding process; (c) Advertising and Bid Preparation Time: Bidding opportunities shall be advertised at least in a national newspaper of wide circulation and on the website of the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) and bidders should be given at least 30 days from the date of invitation to bid or the date of availability of the bidding documents, whichever is later; (d) Criteria for Qualification of Bidders: Qualification criteria shall only concern the bidder’s capability and resources to perform the contract taking into account objective and measurable factors. Such criteria for qualification of bidders shall be clearly specified in the bidding documents; (e) Bid Evaluation and Contract Award: A contract shall be awarded to the substantially responsive and lowest evaluated bidder provided that such bidder meets the qualification criteria specified in the bidding documents. No scoring system shall be allowed for the evaluation of bids, and no “blanket” limitation to the number of lots which can be awarded to a bidder shall apply. The criteria for bid evaluation and the contract award conditions shall be clearly specified in the bidding documents; (f) Preferences: No preference shall be given to domestic/regional bidders; to domestically/regionally manufactured goods; and to bidders forming a joint venture with a national firm or proposing national sub-contractors or carrying out economic activities in the territory of the Recipient; (g) Publication of Contract Award: Information on all contract awards shall be published in at least a national newspaper of wide circulation or in the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) web-site; (h) Fraud and Corruption: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy to sanction firms or individuals found to have engaged in fraud and corruption as set forth in the Procurement Guidelines; (i) Inspection and Audit Rights: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy with respect to inspection and audit of accounts, records and other documents relating to the bid submission and contract performance; (j) Requirement for administrative documents and/or tax clearance certificate: The bidding documents shall not require foreign bidders to produce any administrative or tax related certificates prior to confirmation of awarding a contract; and (k) Modifications of a Signed Contract: Any change in the contract amount which, singly or combined with all previous changes, increases the original contract amount by fifteen (15) percent or more must be done through an amendment to the signed contract instead of signing a new contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Congo, Democratic Republic of : DRC Multisectoral Nutrition and Health Project PLAN General Information Country: Congo, Democratic Republic of 2019-05-03 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P168756 GPN Date: 2019-09-27 Project Name: DRC Multisectoral Nutrition and Health Project Loan / Credit No: IDA / 64410, / , IDA / D4790, IDA / V2420, IDA / V1400 RDC-MINISTERE DE LA SANTE PUBLIQUE Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ZR-DRC-MSP-104597-CW-RF Convergence Demonstration Request for Quota Single Stage - One E 2020-05-1 Q / Construction et ou réhabil / Post Limited 280,000.00 0.00 Canceled 2019-09-21 2019-11-16 Project tions nvelope 4 itation des sanitaires ZR-DRC-MSP-105617-CW-RF Q / Construction et réhabilita Capacity Strengthening and Request for Quota Single Stage - One E 2020-03-1 / Post Limited 280,000.00 0.00 Canceled 2019-07-20 2019-09-14 tion de structures sanitaires Project Management tions nvelope 2 dans les provinces d'interven tion ZR-DRC-MSP-196590-CW-RF Single Stage - One E Pending Imp 2021-10-0 B / Travaux de réhabilitation IDA / 64410 CERC Post Request for Bids Open - National 700,000.00 0.00 2020-12-21 2020-12-26 2021-02-06 2021-03-08 2021-04-12 nvelope lementation 9 et d'extension du bâtiment d u PRONANUT ZR-DRC-MSP-185062-CW-RF B / Extension/réhabilitation d es locaux PDSS pour acquérir Single Stage - One E 2021-11-0 IDA / 64410 CERC Post Request for Bids Open - National 550,000.00 0.00 Canceled 2021-01-15 2021-01-20 2021-03-03 2021-04-02 2021-05-07 l'équipe PMNS et Réhabilitati nvelope 3 on des locaux et du laboratoi re d'analyse du PRONANUT ZR-DRC-MSP-220154-CW-RF B / Travaux de construction d Single Stage - One E Pending Imp 2022-01-0 IDA / 64410 CERC Post Request for Bids Open - National 900,000.00 0.00 2021-03-17 2021-03-22 2021-05-03 2021-06-02 2021-07-07 es bâtiments devant abriter l nvelope lementation 3 es bureaux du PDSS ZR-DRC-MSP-282061-CW-RF Request for Bids - B / Travaux de Réhabilitation Capacity Strengthening and Single Stage - One E Works French Civi Pending Imp 2023-05-1 IDA / 64410 Post Request for Bids Open - National 700,000.00 0.00 2022-07-29 2022-08-03 2022-09-14 2022-10-14 2022-11-18 du bâtiment devant abriter le Project Management nvelope l Law (French) SP lementation 7 s bureaux du PRONANUT (Ext D ension) ZR-DRC-MSP-105624-CW-RF Q / Réhabilitation et rafraichi Capacity Strengthening and Request for Quota Single Stage - One E 2020-01-0 / Post Limited 150,000.00 0.00 Canceled 2019-05-11 2019-07-06 ssement des locaux du PDSS Project Management tions nvelope 2 pour abriter le personnel du PMNS GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-DRC-MSP-105627-GO-RF Capacity Strengthening and Request for Quota Single Stage - One E Q / Acquisition de cinq (5) vé / Post Limited 250,000.00 225,244.45 Signed 2019-05-18 2020-02-13 2019-07-13 2020-05-05 2020-01-09 Project Management tions nvelope hicules 4x4 pour la coordinati on du projet ZR-DRC-MSP-114486-GO-RF Q / Contractualisation avec le Convergence Demonstration Request for Quota Single Stage - One E / Prior Open - National 20,000,000.00 0.00 Canceled 2019-09-21 2019-11-16 2020-05-14 s agences spécialisées dans l Project tions nvelope e transfert monétaire des all ocations familiales ZR-DRC-MSP-212918-GO-RF Q / Acquisition du matériel in formatique, audiovisuel et d Capacity Strengthening and Request for Quota Single Stage - One E Pending Impl IDA / 64410 Post Limited 420,000.00 0.00 2021-03-21 2021-05-16 2021-11-12 e connexion internet pour ap Project Management tions nvelope ementation puyer Minagri/Minpeche , PN SR, EPSP, MINAS & PRONANU T ZR-DRC-MSP-212919-GO-RF Q / Acquisition de tablettes e Capacity Strengthening and Request for Quota Single Stage - One E Pending Impl IDA / 64410 Post Limited 70,000.00 0.00 2021-03-22 2021-05-17 2021-11-13 t chargeurs solaires pour les Project Management tions nvelope ementation vérificateurs du FBP ZR-DRC-MSP-105647-GO-RF Q / Acquisition des matériels Capacity Strengthening and Request for Quota Single Stage - One E Pending Impl IDA / 64410 Post Limited 200,000.00 0.00 2019-05-27 2019-07-22 2020-01-18 de connexion internet en fav Project Management tions nvelope ementation eur du Projet (V-SAT et conne xes) ZR-DRC-MSP-185114-GO-RF Capacity Strengthening and Request for Quota Single Stage - One E Q / Acquisition des équipeme IDA / 64410 Post Limited 100,000.00 0.00 Canceled 2020-08-08 2020-10-03 2021-04-01 Project Management tions nvelope nts essentiels pour le PRONA NUT ZR-DRC-MSP-224670-GO-RF Convergence Demonstration Request for Quota Single Stage - One E Q / Acquisition des mobiliers IDA / 64410 Post Limited 15,000.00 4,175.00 Signed 2021-03-22 2021-03-18 2021-05-17 2021-03-23 2021-11-13 Project tions nvelope de bureau pour le compte du PMNS ZR-DRC-MSP-282048-GO-DI Improving the Delivery of Co R / Acquisition et distribution mmunity Interventions and Pending Impl des produits nutritionnels et l IDA / 64410 Prior Direct Selection Direct 12,998,321.15 0.00 2022-03-18 2022-03-23 2022-04-27 2022-10-24 Social and Behavioral Chang ementation e renforcement des capacité e s de gestion de stock (UNICE F) ZR-DRC-MSP-282018-GO-RF Improving the Delivery of Co Q / Reproduction et vulgarisa mmunity Interventions and Request for Quota Single Stage - One E Pending Impl IDA / 64410 Post Limited 50,000.00 0.00 2022-05-05 2022-06-30 2022-12-27 tion du Plan National Stratégi Social and Behavioral Chang tions nvelope ementation que Multisectoriel de Nutritio e n 2022-2026 ZR-DRC-MSP-282035-GO-RF B / Acquisition et dotation de s motos DT aux DPS (12), IP Improving Service Supply an Single Stage - One E S (8), BCZS ( 80) (Kasaï, Kasa IDA / 64410 Post Request for Bids Open - National 670,000.00 660,981.00 Signed 2022-05-25 2022-05-04 2022-05-30 2022-05-05 2022-07-11 2022-06-06 2022-08-10 2022-06-13 2022-09-14 2022-08-25 2023-03-13 d Strategic Purchasing nvelope ï Central, Kwilu et Sud-KIVU) ainsi qu'aux services techniq ues provinciaux du secteur a gricoles (dans 9 territoires) Page 1 ZR-DRC-MSP-282032-GO-RF B / Acquisition des Médicame Improving Service Supply an Open - Internationa Single Stage - One E nts Essentiels Génériques (M IDA / 64410 Prior Request for Bids 2,340,000.00 0.00 Canceled 2022-03-31 2022-04-05 2022-05-17 2022-06-16 2022-07-21 2023-01-17 d Strategic Purchasing l nvelope EG) des dotations initiales au x CS et HGR (Kasaï, Kasaï Ce ntral, Kwilu et Sud-Kivu) ZR-DRC-MSP-282039-GO-RF B / Acquisition et dotation de Improving Service Supply an Open - Internationa Single Stage - One E Under Imple s CS et HGR en petits Matérie IDA / 64410 Prior Request for Bids 19,190,781.00 0.00 2022-03-30 2022-05-03 2022-04-04 2022-06-29 2022-05-16 2022-07-15 2022-06-15 2023-04-27 2022-07-20 2023-01-16 d Strategic Purchasing l nvelope mentation ls des soins ( DPS Kasaï, Kasa ï Central, Kwilu et Sud-Kivu) ZR-DRC-MSP-282027-GO-RF B / Acquisition et dotation de Improving Service Supply an Single Stage - One E Under Imple IDA / 64410 Post Request for Bids Open - National 400,000.00 0.00 2022-05-20 2022-06-03 2022-05-25 2022-06-06 2022-07-06 2022-07-04 2022-08-05 2022-09-09 2023-03-08 8 véhicules 4x4 aux DPS Ka d Strategic Purchasing nvelope mentation saï, Kasaï central, Kwilu et Su d-Kivu ZR-DRC-MSP-282034-GO-RF Convergence Demonstration Single Stage - One E Pending Impl IDA / 64410 Post Request for Bids Open - National 100,575.00 0.00 2022-05-20 2022-05-25 2022-07-06 2022-08-05 2022-09-09 2023-03-08 B / Acquisition et distribution Project nvelope ementation des FAF ZR-DRC-MSP-282037-GO-RF B / Acquisition et dotation de s mobiliers des bureaux dans Convergence Demonstration Single Stage - One E Under Imple IDA / 64410 Post Request for Bids Open - National 100,000.00 0.00 2022-03-30 2022-09-13 2022-04-04 2022-09-14 2022-05-16 2022-06-15 2022-07-20 2023-01-16 le cadre de l'Appui institution Project nvelope mentation nel aux services du secteur a gricoles (SNV, SENASEM, DEP ) Agriculture et Pêche Elevag e ZR-DRC-MSP-282053-GO-RF B / Acquisition et dotation de s matériels informatique et a udiovisuels aux structures pa Capacity Strengthening and Single Stage - One E IDA / 64410 Post Request for Bids Open - National 137,760.00 0.00 Signed 2022-06-20 2022-09-13 2022-06-25 2022-10-11 2022-08-06 2022-10-18 2022-09-05 2022-11-25 2022-10-10 2023-04-08 rties prenantes du niveau nat Project Management nvelope ional (PNSR, PRONANUT, PNS A, EPST, MINAS) ainsi qu'aux Coordinations provinciales (P NSR, PRONANUT, PNSA) ZR-DRC-MSP-282062-GO-RF Q / Acquisition de quatre (4) Capacity Strengthening and Request for Quota Single Stage - One E Under Imple IDA / 64410 Post Limited 200,000.00 0.00 2022-03-20 2022-06-09 2022-05-15 2022-11-11 véhicules 4X4 pour les 4 bur Project Management tions nvelope mentation eaux provinciaux du PMNS ZR-DRC-MSP-282069-GO-RF Capacity Strengthening and Request for Quota Single Stage - One E Q / Conception et Production IDA / 64410 Post Limited 115,000.00 0.00 Signed 2022-05-05 2022-07-06 2022-06-30 2022-12-27 Project Management tions nvelope des supports de communicati on du projet ZR-DRC-MSP-282070-GO-RF Capacity Strengthening and Request for Quota Single Stage - One E Pending Impl Q / Acquisition des équipeme IDA / 64410 Post Limited 35,000.00 0.00 2022-05-02 2022-06-27 2022-12-24 Project Management tions nvelope ementation nts de communication pour l e Projet ZR-DRC-MSP-282024-GO-RF Improving the Delivery of Co Q / Reproduction des outils d mmunity Interventions and Request for Quota Single Stage - One E Under Imple IDA / 64410 Post Limited 450,000.00 0.00 2022-12-10 2023-03-01 2023-02-04 2023-08-03 e collecte des données pour Social and Behavioral Chang tions nvelope mentation 1.026 FOSA dans les 4 provin e ces ZR-DRC-MSP-272829-GO-RF B / Acquisition et distribution du petit matériel médical pou Improving Service Supply an Open - Internationa Single Stage - One E r une dotation initiale aux For IDA / 64410 Prior Request for Bids 13,100,000.00 0.00 Canceled 2022-04-20 2022-04-25 2022-06-06 2022-07-06 2022-08-10 2023-02-06 d Strategic Purchasing l nvelope mations Sanitaires (FoSa) ap puyées par le PMNS dans les provinces de Kasai, Kasai Ce ntral, Kwilu et Sud Kivu (en 4 lots) ZR-DRC-MSP-282060-GO-RF B / Acquisition des équipeme Capacity Strengthening and Single Stage - One E nts (mobilier et matériels info IDA / 64410 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2022-03-31 2022-04-05 2022-05-17 2022-06-16 2022-07-21 2023-01-17 Project Management nvelope rmatiques) pour les 4 bureau x provinciaux ( kasai,Kasai-c entral,Kwilu et Sud Kivu) ZR-DRC-MSP-105628-GO-RF Capacity Strengthening and Single Stage - One E Q / Acquisition en deux lots d / Post Request for Bids Open - National 750,000.00 0.00 Canceled 2019-07-15 2019-07-20 2019-08-31 2019-09-30 2019-11-04 2020-05-02 Project Management nvelope es mobiliers et équipements i nformatiques ZR-DRC-MSP-282019-GO-RF Improving the Delivery of Co Q / Acquisition et dotation de mmunity Interventions and Request for Quota Single Stage - One E IDA / 64410 Post Limited 40,000.00 0.00 Canceled 2022-03-30 2022-05-25 2022-11-21 s motos DT 125 aux Coordina Social and Behavioral Chang tions nvelope tions PRONANUT (2 motos pa e r coordination) ZR-DRC-MSP-282052-GO-RF Q / Acquisition et dotation de Improving Service Supply an Request for Quota Single Stage - One E IDA / 64410 Post Limited 75,000.00 0.00 Canceled 2022-04-05 2022-05-31 2022-11-27 s motos DT 125 aux Coordina d Strategic Purchasing tions nvelope tions PNSR et PNSA ZR-DRC-MSP-282038-GO-RF Q / Acquisition des équipeme nts informatiques pour les S Convergence Demonstration Request for Quota Single Stage - One E ervices techniques au nivea IDA / 64410 Post Limited 50,370.00 0.00 Canceled 2022-04-04 2022-05-30 2022-11-26 Project tions nvelope u provincial des IPAPEL et IT ATEL de l'Agriculture et Pêch e (24 PC, 6 LCD, 24 Modems , 3 Scaners, 3 imprimantes et c) ZR-DRC-MSP-282044-GO-RF Q / Acquisition et dotation de s équipements et mobiliers d Convergence Demonstration Request for Quota Single Stage - One E IDA / 64410 Post Limited 99,000.00 0.00 Canceled 2022-04-02 2022-05-28 2022-11-24 es bureaux dans le cadre de l Project tions nvelope 'Appui institutionnel aux serv ices provinciaux du secteur a gricoles (AGRI & P-E) ZR-DRC-MSP-212915-GO-RF Q / Acquisition de matériels e Capacity Strengthening and Request for Quota Single Stage - One E IDA / 64410 Post Limited 100,000.00 0.00 Canceled 2021-03-28 2021-05-23 2021-11-19 t équipements informatiques Project Management tions nvelope pour les bureaux ZR-DRC-MSP-357677-GO-RF B / Acquisition des matériels i nformatiques et mobiliers de Convergence Demonstration Single Stage - One E Pending Impl IDA / 64410 Post Request for Bids Open - National 300,000.00 0.00 2023-05-31 2023-06-05 2023-07-17 2023-08-16 2023-09-20 2024-03-18 bureau (en 2 lots) en faveur Project nvelope ementation des directions (DEP-MINAS, P NSR, PNSA, PRONANUT, Educ ation) impliquées dans le Proj et ZR-DRC-MSP-363658-GO-RF Capacity Strengthening and Request for Quota Single Stage - One E Pending Impl Q / Reproduction des outils d IDA / 64410 Post Limited 190,000.00 0.00 2023-07-05 2023-08-30 2024-02-26 Project Management tions nvelope ementation e communication du Projet Page 2 ZR-DRC-MSP-282030-GO-RF Q / Acquisition et dotation de Improving Service Supply an Request for Quota Single Stage - One E IDA / 64410 Post Limited 110,000.00 0.00 Canceled 2022-05-30 2022-07-25 2023-01-21 s PC aux DPS (12), IPS(8 ) et d Strategic Purchasing tions nvelope BCZS ( 80) (Kasaï, Kasaï Cent ral, Kwilu et Sud-Kivu) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-DRC-MSP-268434-NC-DIR / Assistance technique dans l Convergence Demonstration a fourniture de kits agricoles IDA / 64410 Prior Direct Selection Direct 13,000,000.00 12,111,858.00 Signed 2021-12-28 2022-01-07 2022-01-02 2022-01-17 2022-02-06 2022-02-08 2022-08-05 Project et de petites exploitations, E ntente directe avec FAO ZR-DRC-MSP-288158-NC-DIR / Contractualisation avec le U NFPA chargé de la mise en œ uvre des activités de prévent Improving Service Supply an ion et réponse aux Violences IDA / 64410 Prior Direct Selection Direct 20,000,000.00 20,000,000.00 Signed 2022-04-21 2022-04-18 2022-04-26 2022-05-10 2022-05-31 2022-06-24 2022-11-27 d Strategic Purchasing Basées sur le Genre (VBG), y compris l’exploitation et les a bus sexuels (EAS) et le harcè lement sexuel (HS), dans le c adre du PMNS ZR-DRC-MSP-282064-NC-DIR / Contractualisation avec PA M pour l’amélioration de la s écurité alimentaire des popul IDA / 64410 CERC Prior Direct Selection Direct 10,416,000.00 14,364,977.00 Signed 2022-04-20 2022-05-23 2022-04-25 2022-05-31 2022-05-30 2022-06-28 2022-11-26 ations vulnérables à travers une réponse intégrée en filet s sociaux (transferts monétai res) dans 5 zones de santé a u Kasaï et au Kasaï Central ZR-DRC-MSP-282067-NC-DIR / Contractualisation avec UNI CEF pour l’amélioration de la sécurité alimentaire des pop IDA / 64410 CERC Prior Direct Selection Direct 11,104,000.00 11,103,989.00 Signed 2022-07-30 2022-05-23 2022-08-04 2022-05-31 2022-09-08 2022-06-17 2023-03-07 ulations vulnérables à traver s des interventions nutritionn elles et en eau, hygiène et as sainissement (EHA) dans 5 z ones de santé au Kasaï et au Kasaï Central ZR-DRC-MSP-282063-NC-DIR / Contractualisation avec FAO pour l’amélioration de la séc urité alimentaire des populati IDA / 64410 CERC Prior Direct Selection Direct 10,200,000.00 10,200,000.00 Signed 2022-07-20 2022-05-16 2022-07-25 2022-06-06 2022-08-29 2022-06-24 2023-02-25 ons vulnérables au travers u ne agriculture sensible à la n utrition dans 5 zones de sant és dans les provinces du Kas aï et Kasaï-Central ZR-DRC-MSP-293975-NC-DIR / Contractualisation avec le F AO pour l’amélioration de la sécurité alimentaire des pop IDA / 64410 CERC Prior Direct Selection Direct 6,000,000.00 0.00 Canceled 2022-07-25 2022-10-27 2022-07-30 2022-09-03 2023-03-02 ulations vulnérables au trave rs une agriculture sensible à l a nutrition dans 2 zones de s anté dans la province du Kas aï Oriental ZR-DRC-MSP-293979-NC-DIR / Contractualisation avec le P AM pour l’amélioration de la sécurité alimentaire des pop IDA / 64410 CERC Prior Direct Selection Direct 3,135,023.00 0.00 Canceled 2022-07-27 2022-10-27 2022-08-01 2022-09-05 2023-03-04 ulations vulnérables à traver s une réponse intégrée en fil ets sociaux (transfert monéta ire inditionnel) dans 2 zones de santé dans la province du Kasaï Oriental ZR-DRC-MSP-293973-NC-DIR / Contractualisation avec UNI CEF pour l’amélioration de la sécurité alimentaire des pop ulations vulnérables à traver IDA / 64410 CERC Prior Direct Selection Direct 5,200,000.00 0.00 Canceled 2022-07-20 2022-10-28 2022-07-25 2022-08-29 2023-02-25 s des interventions nutritionn elles et en eau, hygiène et as sainissement (EHA) dans 2 z ones de santé dans la provin ce du Kasaï Oriental ZR-DRC-MSP-319185-CS-CD Improving the Delivery of Co S / Contractualisation avec U mmunity Interventions and Direct - Internation IDA / 64410 Prior Direct Selection 5,000,000.00 0.00 Signed 2023-01-20 2023-01-30 2023-01-25 2023-02-03 2023-03-01 2023-04-08 2023-08-28 NICEF pour réaliser l'enquête Social and Behavioral Chang al démographique et de santé ( e EDS-RDC III 2022) ZR-DRC-MSP-357552-NC-DIR / Contractualisation avec FAO pour la production et distribu Convergence Demonstration Direct - Internation Pending Impl tion des semences et culture IDA / 64410 Prior Direct Selection 9,000,000.00 0.00 2023-06-30 2023-07-05 2023-08-09 2024-02-05 Project al ementation s bio certifiées dans le cadre de la mise en œuvre des acti vités de GAFSP dans les zone s d'interventions ZR-DRC-MSP-325968-NC-RF Q / Entreposage des petits m Improving the Delivery of Co atériels des soins et des outil mmunity Interventions and Single Stage - One E Pending Impl s de collecte des données da IDA / 64410 Post Request for Bids Open - National 800,000.00 0.00 2023-06-30 2023-07-05 2023-08-16 2023-09-15 2023-10-20 2024-04-17 Social and Behavioral Chang nvelope ementation ns les quatre (4) provinces c e oncernées par le PMNS (Kasa ï, Kasaï Central, Kwilu et Sud- Kivu) ZR-DRC-MSP-325973-NC-RF Q / Distribution des petits ma tériels des soins et des outils Improving the Delivery of Co de collecte des données aux mmunity Interventions and Single Stage - One E Pending Impl IDA / 64410 Post Request for Bids Open - National 1,400,000.00 0.00 2023-08-31 2023-09-05 2023-10-17 2023-11-16 2023-12-21 2024-06-18 niveaux des Formations Sanit Social and Behavioral Chang nvelope ementation aires dans les quatre (4) prov e inces concernées par le PMN S (Kasaï, Kasaï Central, Kwilu et Sud-Kivu) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Page 3 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-DRC-MSP-104572-CS-CQ S / Recrutement d'une firme Convergence Demonstration Consultant Qualifi Pending Impleme pour le ciblage des ménages / Post Open - National 350,000.00 0.00 2019-09-09 2019-09-30 2019-11-13 2019-12-13 2020-01-17 2020-07-15 Project cation Selection ntation vulnérables bénéficiaires des allocations financières ZR-DRC-MSP-104542-CS-QC BS / Recrutement d'ONG Cad Capacity Strengthening and Quality Based Sel Open - Internationa res Internationales pour la mi IDA / D4790 Prior 150,000,000.00 0.00 Canceled 2019-07-08 2019-07-29 2019-09-11 2019-10-09 2019-11-08 2019-12-08 2020-01-12 2021-01-11 Project Management ection l se en œuvre de l'approche N utrition à Assise Communaut aire ZR-DRC-MSP-197623-CS-QC BS / Recrutement d’une ONG chargée de la mise en œuvre des activités de prévention e Capacity Strengthening and Quality And Cost- t réponse aux Violences Basé IDA / D4790 Post Open - National 200,000.00 0.00 Canceled 2021-01-22 2020-10-01 2021-02-12 2021-03-28 2021-04-25 2021-05-25 2021-06-29 2021-08-03 2022-08-03 Project Management Based Selection es sur le Genre (VBG), y com pris l’exploitation et les abus sexuels (EAS) et le harcèlem ent sexuel (HS), dans le cadr e du PMNS ZR-DRC-MSP-185113-CS-CQ S / Recrutement d'une firme Consultant Qualifi IDA / 64410 CERC Post Open - National 45,000.00 0.00 Canceled 2020-10-02 2020-10-23 2020-12-06 2021-01-05 2021-02-09 2021-08-08 pour le renforcement des cap cation Selection acités de PRONANUT ZR-DRC-MSP-212852-CS-QC BS / Recrutement des ONG p Quality And Cost- IDA / 64410 CERC Prior Open - National 150,000,000.00 0.00 Canceled 2021-02-17 2021-03-10 2021-04-23 2021-05-21 2021-06-20 2021-07-25 2021-08-29 2022-08-29 our la mise en œuvre de l’ap Based Selection proche Nutrition à Assise Co mmunautaire ZR-DRC-MSP-209258-CS-CQ S / Recrutement et financem Consultant Qualifi ent des ONG pour la mise en IDA / 64410 CERC Post Open - National 50,000.00 0.00 Canceled 2020-12-23 2021-01-13 2021-02-26 2021-03-28 2021-05-02 2021-10-29 cation Selection œuvre de l'approche nutritio n à assise communautaire(N AC) ZR-DRC-MSP-185059-CS-QC Capacity Strengthening and Quality And Cost- BS / Recrutement d'un cabin IDA / 64410 Post Open - National 60,000.00 0.00 Canceled 2020-10-26 2020-11-16 2020-12-30 2021-01-27 2021-02-26 2021-04-02 2021-05-07 2022-05-07 Project Management Based Selection et pour l'audit externe du pro jet PMNS ZR-DRC-MSP-204745-CS-QC BS / Recrutement d'une ONG chargée de la mise en œuvr e des activités de prévention Capacity Strengthening and Quality And Cost- et réponse aux Violences Bas IDA / D4790 Prior Open - National 4,000,000.00 0.00 Canceled 2020-12-21 2021-01-11 2021-02-24 2021-03-24 2021-04-23 2021-05-28 2021-07-02 2022-07-02 Project Management Based Selection ées sur le Genre (VBG), y co mpris l'exploitation et les ab us sexuels (EAS) et le harcèle ment sexuel (HS), dans le ca dre de la mise en œuvre ZR-DRC-MSP-196582-CS-CQ S / Recrutement d'un consult ant chargé des études, contr Capacity Strengthening and Consultant Qualifi IDA / 64410 Post Open - National 100,000.00 0.00 Canceled 2020-10-12 2020-10-01 2020-11-02 2020-12-16 2021-01-15 2021-02-19 2021-08-18 ôles et surveillances des trav Project Management cation Selection aux de réhabilitation et exte nsion du bâtiment du PRONA NUT ZR-DRC-MSP-212823-CS-CQ S / Contractualisation avec u Consultant Qualifi IDA / 64410 CERC Post Open - National 45,000.00 0.00 Canceled 2021-04-06 2021-04-27 2021-06-10 2021-07-10 2021-08-14 2022-02-10 ne firme pour le renforcemen cation Selection t des capacités du PRONANU T ZR-DRC-MSP-212830-CS-CQ S / Recrutement des Consult Consultant Qualifi Pending Impleme ants pour l'évaluation des be IDA / 64410 CERC Post Open - National 350,000.00 0.00 2021-04-15 2021-05-06 2021-06-19 2021-07-19 2021-08-23 2022-02-19 cation Selection ntation soins d'investissement des F OSA dans les 4 provinces cibl ées ZR-DRC-MSP-235317-CS-QC BS / Contractualisation avec l Capacity Strengthening and Quality And Cost- es ONG (Acteurs non Etatiqu IDA / D4790 Prior Open - National 13,000,000.00 11,969,674.90 Signed 2021-05-31 2021-05-27 2021-06-21 2021-05-28 2021-08-04 2021-08-16 2021-09-01 2021-10-08 2021-10-01 2022-01-10 2021-11-05 2022-05-04 2021-12-10 2022-05-06 2022-12-10 Project Management Based Selection es) pour appuyer la planificat ion familiale dans la province du Kasaï ZR-DRC-MSP-235318-CS-QC BS / Contractualisation avec l Capacity Strengthening and Quality And Cost- es ONG (Acteurs non Etatiqu IDA / D4790 Prior Open - National 13,000,000.00 11,247,745.61 Signed 2021-06-15 2021-05-27 2021-07-06 2021-05-28 2021-08-19 2021-08-11 2021-09-16 2021-10-08 2021-10-16 2022-02-02 2021-11-20 2022-06-08 2021-12-25 2022-06-11 2022-12-25 Project Management Based Selection es) pour appuyer la planificat ion familiale dans la province du Kasaï Central ZR-DRC-MSP-235319-CS-QC BS / Contractualisation avec l Capacity Strengthening and Quality And Cost- Under Implement es ONG (Acteurs non Etatiqu IDA / D4790 Prior Open - National 13,000,000.00 0.00 2021-06-15 2021-05-27 2021-07-06 2021-05-28 2021-08-19 2021-08-11 2021-09-16 2021-10-19 2021-10-16 2022-02-16 2021-11-20 2022-11-17 2021-12-25 2022-12-25 Project Management Based Selection ation es) pour appuyer la planificat ion familiale dans la province du Sud-Kivu ZR-DRC-MSP-235320-CS-QC BS / Contractualisation avec l Capacity Strengthening and Quality And Cost- es ONG (Acteurs non Etatiqu IDA / D4790 Prior Open - National 13,000,000.00 11,791,594.00 Signed 2021-06-15 2021-05-27 2021-07-06 2021-05-28 2021-08-19 2021-09-06 2021-09-16 2021-10-22 2021-10-16 2022-02-18 2021-11-20 2022-05-05 2021-12-25 2022-05-07 2022-12-25 Project Management Based Selection es) pour appuyer la planificat ion familiale dans la province du Kwilu ZR-DRC-MSP-235326-CS-QC BS / Recrutement d'un consul Capacity Strengthening and Quality And Cost- Under Implement IDA / 64410 Prior Open - National 2,000,000.00 0.00 2021-06-23 2021-11-17 2021-07-14 2022-01-10 2021-08-27 2022-08-02 2021-09-24 2022-09-16 2021-10-24 2022-11-04 2021-11-28 2023-06-02 2022-01-02 2023-01-02 tant firme pour le diagnostic Project Management Based Selection ation organisationnel du PRONANU T ZR-DRC-MSP-235329-CS-QC BS / Recrutement d’une ONG Quality And Cost- Under Implement chargée de la mise en œuvre IDA / 64410 CERC Prior Open - National 37,500,000.00 0.00 2021-06-24 2021-06-08 2021-07-15 2021-07-22 2021-08-28 2022-02-11 2021-09-25 2022-04-20 2021-10-25 2022-07-13 2021-11-29 2023-06-07 2022-01-03 2023-01-03 Based Selection ation de l'approche Nutrition à Assi se Communautaire dans la pr ovince du Kasaï ZR-DRC-MSP-235330-CS-QC BS / Recrutement d’une ONG chargée de la mise en œuvre Quality And Cost- Under Implement IDA / 64410 CERC Prior Open - National 37,500,000.00 0.00 2021-06-24 2021-06-08 2021-07-15 2021-07-23 2021-08-28 2022-03-15 2021-09-25 2022-04-29 2021-10-25 2022-07-13 2021-11-29 2023-06-07 2022-01-03 2023-01-03 de l'approche Nutrition à Assi Based Selection ation se Communautaire dans la pr ovince du Kasaï Central Page 4 ZR-DRC-MSP-235333-CS-QC BS / Recrutement d’une ONG Quality And Cost- Under Implement chargée de la mise en œuvre IDA / 64410 CERC Prior Open - National 37,500,000.00 0.00 2021-06-24 2021-06-08 2021-07-15 2021-07-22 2021-08-28 2022-03-15 2021-09-25 2022-04-29 2021-10-25 2022-07-13 2021-11-29 2022-01-03 2023-01-03 Based Selection ation de l'approche Nutrition à Assi se Communautaire dans la pr ovince du Sud-Kivu ZR-DRC-MSP-235334-CS-QC BS / Recrutement d’une ONG Quality And Cost- Under Implement chargée de la mise en œuvre IDA / 64410 CERC Prior Open - National 37,500,000.00 0.00 2021-06-24 2021-06-08 2021-07-15 2021-07-22 2021-08-28 2022-03-15 2021-09-25 2022-04-29 2021-10-25 2022-07-13 2021-11-29 2022-01-03 2023-01-03 Based Selection ation de l'approche Nutrition à Assi se Communautaire dans la pr ovince du Kwilu ZR-DRC-MSP-261471-CS-CQ S / Recrutement d’ONG/cons ortium d’ONG chargées de la mise en œuvre des activités Consultant Qualifi de prévention et réponse aux IDA / 64410 CERC Post Open - National 250,000.00 0.00 Canceled 2021-11-30 2021-11-11 2021-12-21 2022-02-03 2022-03-05 2022-04-09 2022-10-06 cation Selection Violences Basées sur le Genr e (VBG), y compris l’exploitat ion et les abus sexuels (EAS) et le harcèlement sexuel (HS ) dans la Province du Kasaï ZR-DRC-MSP-261472-CS-CQ S / Recrutement d’ONG/cons ortium d’ONG chargées de la mise en œuvre des activités Consultant Qualifi de prévention et réponse aux IDA / 64410 CERC Post Open - National 250,000.00 0.00 Canceled 2021-11-30 2021-11-11 2021-12-21 2022-02-03 2022-03-05 2022-04-09 2022-10-06 cation Selection Violences Basées sur le Genr e (VBG), y compris l’exploitat ion et les abus sexuels (EAS) et le harcèlement sexuel (HS ) dans la Province du Kwilu ZR-DRC-MSP-261473-CS-CQ S / Recrutement d’ONG/cons ortium d’ONG chargées de la mise en œuvre des activités Consultant Qualifi de prévention et réponse aux IDA / 64410 CERC Post Open - National 250,000.00 0.00 Canceled 2021-11-30 2021-12-21 2022-02-03 2022-03-05 2022-04-09 2022-10-06 cation Selection Violences Basées sur le Genr e (VBG), y compris l’exploitat ion et les abus sexuels (EAS) et le harcèlement sexuel (HS ) dans la Province du Sud Kiv u ZR-DRC-MSP-261475-CS-CQ S / Recrutement d’ONG/cons ortium d’ONG chargées de la mise en œuvre des activités Consultant Qualifi de prévention et réponse aux IDA / 64410 CERC Post Open - National 250,000.00 0.00 Canceled 2021-11-30 2021-11-11 2021-12-21 2022-02-03 2022-03-05 2022-04-09 2022-10-06 cation Selection Violences Basées sur le Genr e (VBG), y compris l’exploitat ion et les abus sexuels (EAS) et le harcèlement sexuel (HS ) dans la Province du Kasaï c ent ZR-DRC-MSP-272824-CS-QC BS / Recrutement d’une age nce/ firme de vérification ext Improving Service Supply an Quality And Cost- Open - Internationa Under Implement erne chargée de la vérificatio IDA / 64410 Prior 2,300,000.00 0.00 2022-04-22 2022-11-21 2022-05-13 2022-12-14 2022-06-26 2022-07-24 2022-08-23 2022-09-27 2022-11-01 2023-11-01 d Strategic Purchasing Based Selection l ation n des services des ONG NAC et ONG PF et la contre vérific ation des prestations de l'ach at stratégique ZR-DRC-MSP-282059-CS-QC BS / Sélection d'un Consultan Capacity Strengthening and Quality And Cost- Pending Impleme t firme pour la Réalisation de IDA / 64410 Post Open - National 425,000.00 0.00 2022-03-15 2022-04-05 2022-05-19 2022-06-16 2022-07-16 2022-08-20 2022-09-24 2023-09-24 Project Management Based Selection ntation s études environnementales et sociales (EIES, PPA, PGES, etc,) ZR-DRC-MSP-325931-CS-CQ Improving the Delivery of Co S / Recrutement d’un Consult mmunity Interventions and Quality And Cost- Open - Internationa Under Implement IDA / 64410 Post 500,000.00 0.00 2022-12-30 2023-02-02 2023-01-20 2023-02-15 2023-03-05 2023-04-02 2023-05-02 2023-06-06 2023-07-11 2024-07-10 ant Cabinet pour réaliser les Social and Behavioral Chang Based Selection l ation enquêtes SMART dans le cad e re du PMNS ZR-DRC-MSP-212871-CS-CQ S / Recrutement d'une ONG c hargée de la mise en ŒUVR E des activités de preventio Capacity Strengthening and Consultant Qualifi IDA / D4790 Post Open - National 536,000.00 0.00 Canceled 2021-03-25 2021-03-15 2021-04-15 2021-04-30 2021-05-29 2021-06-28 2021-08-02 2022-01-29 n et reponse aux violences b Project Management cation Selection asées sur le genre(VBG), y co mpris l'exploitation et les ab us sexuels (EAS) et le harcele ment sexuel dans le cadre du PMNS ZR-DRC-MSP-282047-CS-CQ S / Recrutement d'un consult Capacity Strengthening and Consultant Qualifi ant Cabinet (Bureau d'études IDA / 64410 Post Open - National 100,000.00 0.00 Canceled 2022-04-30 2022-05-21 2022-07-04 2022-08-03 2022-09-07 2023-03-06 Project Management cation Selection ) chargé de la surveillance de s travaux du PRONANUT ZR-DRC-MSP-212875-CS-QB S / Recrutement d’agences s Quality Based Sel IDA / 64410 CERC Prior Open - National 20,000,000.00 0.00 Canceled 2021-03-29 2021-04-19 2021-06-02 2021-06-30 2021-07-30 2021-08-29 2021-10-03 2022-10-03 pécialisées dans les transfert ection s de monétaires (Cash Transf ert) ZR-DRC-MSP-212860-CS-QC BS / Contractualisation avec l Capacity Strengthening and Quality And Cost- IDA / D4790 Prior Open - National 52,000,000.00 0.00 Canceled 2021-02-17 2021-02-24 2021-03-10 2021-02-25 2021-04-23 2021-05-21 2021-06-20 2021-07-25 2021-08-29 2022-08-29 es ONG (Acteurs non Etatiqu Project Management Based Selection es) pour appuyer la planificat ion familiale ZR-DRC-MSP-104546-CS-QC BS / Contractualisation avec l Capacity Strengthening and Quality Based Sel Open - Internationa IDA / D4790 Prior 52,000,000.00 0.00 Canceled 2019-07-08 2019-07-29 2019-09-11 2019-10-09 2019-11-08 2019-12-08 2020-01-12 2021-01-11 es ONG pour appuyer la plani Project Management ection l fication familiale ZR-DRC-MSP-104595-CS-CQ S / Contractualisation avec o pérateur de téléphonie mobil Convergence Demonstration Consultant Qualifi / Post Limited 50,000.00 0.00 Canceled 2019-08-05 2019-08-19 2019-09-18 2019-10-23 2020-04-20 e chargé de la vulgarisation Project cation Selection des messages d'alerte en lan gues nationales au profit des ménages ciblés ZR-DRC-MSP-104562-CS-QC BS / Contractualisation avec une firme pour développer et Capacity Strengthening and Quality And Cost- Open - Internationa / Prior 7,000,000.00 0.00 Canceled 2019-08-12 2020-05-14 2019-09-02 2019-10-16 2019-11-13 2019-12-13 2020-01-17 2020-02-21 2021-02-20 mettre en œuvre la stratégie Project Management Based Selection l de changement des comport ements et le changement so cial Page 5 ZR-DRC-MSP-185072-CS-CQ S / Recrutement d'un consult Capacity Strengthening and Consultant Qualifi IDA / 64410 Post Open - National 200,000.00 0.00 Canceled 2021-05-12 2021-06-02 2021-07-16 2021-08-15 2021-09-19 2022-03-18 ant firme pour le diagnostic o Project Management cation Selection rganisationnel du PRONANUT INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-DRC-MSP-104560-CS-CD S / Contractualisation avec H Convergence Demonstration IDA / 64410 Prior Direct Selection Direct 12,000,000.00 11,010,837.00 Signed 2019-07-15 2020-05-05 2019-07-25 2021-05-14 2019-09-28 2021-06-16 2020-03-26 arvest Plus pour la productio Project n de semences bio fortifiées ZR-DRC-MSP-104569-CS-CD Capacity Strengthening and Under Implement S / Contractualisation avec l' / Prior Direct Selection Direct 4,000,000.00 0.00 2019-08-28 2020-11-24 2019-09-07 2019-11-11 2020-05-09 Project Management ation UNICEF pour l'appui techniqu e et logistique ZR-DRC-MSP-104592-CS-CD S / Contractualisation avec S Convergence Demonstration / Post Direct Selection Direct 100,000.00 0.00 Canceled 2019-08-20 2019-08-30 2019-11-03 2020-05-01 ENASEM pour la production d Project e semences bio fortifiées ZR-DRC-MSP-105637-CS-IND Capacity Strengthening and Individual Consult V / Recrutement d'un Spécial IDA / 64410 Prior Open 216,000.00 168,400.00 Signed 2019-05-13 2019-05-14 2019-07-01 2019-05-22 2019-07-22 2019-08-16 2019-08-26 2019-09-25 2020-02-22 Project Management ant Selection iste en Passation des Marché s ZR-DRC-MSP-105641-CS-IND Capacity Strengthening and Individual Consult Under Implement V / Responsable d'un respons / Prior Open 216,000.00 0.00 2019-05-13 2019-05-14 2019-07-01 2019-07-22 2019-08-26 2020-02-22 Project Management ant Selection ation able suivi et évaluation ZR-DRC-MSP-105643-CS-IND Capacity Strengthening and Individual Consult IDA / 64410 Prior Open 288,000.00 156,000.00 Signed 2019-05-13 2019-09-16 2019-07-01 2020-04-16 2019-07-22 2020-10-27 2019-08-26 2020-08-27 2020-02-22 V / Recrutement d'un Chef de Project Management ant Selection Projet ZR-DRC-MSP-105646-CS-IND Capacity Strengthening and Individual Consult Under Implement / Prior Open 240,000.00 0.00 2019-05-13 2019-05-14 2019-07-01 2019-05-21 2019-07-22 2019-12-03 2019-08-26 2020-02-22 V / Recrutement de deux co Project Management ant Selection ation mptables ZR-DRC-MSP-104548-CS-CD S / Contractualisation avec la Convergence Demonstration / Prior Direct Selection Direct 14,000,000.00 0.00 Canceled 2019-07-22 2020-04-30 2019-08-01 2020-08-04 2019-10-05 2020-04-02 FAO pour la mise à dispositi Project on de kits agricoles et petits élevages ZR-DRC-MSP-159573-CS-IND V / Recrutement d'un Spécial iste en Santé Publique, charg Capacity Strengthening and Individual Consult IDA / 64410 Prior Open 240,000.00 57,600.00 Signed 2020-02-17 2020-03-06 2020-04-06 2020-08-04 2020-04-27 2020-09-16 2020-06-01 2020-09-30 2020-11-28 é du Suivi et Evaluation, pour Project Management ant Selection le compte du Programme Mul tisectoriel de Nutrition et de Santé ZR-DRC-MSP-159577-CS-IND V / Recrutement d'un Spécial Capacity Strengthening and Individual Consult iste en Sauvegarde Sociale, p IDA / 64410 Prior Open 250,000.00 57,600.00 Signed 2020-02-17 2020-03-06 2020-04-06 2020-08-05 2020-04-27 2020-09-16 2020-06-01 2020-10-01 2020-11-28 Project Management ant Selection our le compte du Projet Multi sectoriel de Nutrition et de S anté ZR-DRC-MSP-159578-CS-IND V / Recrutement d'un Spécial Capacity Strengthening and Individual Consult iste en Sauvegarde Environn IDA / 64410 Prior Open 250,000.00 45,000.00 Signed 2020-02-17 2020-03-16 2020-04-06 2020-08-05 2020-04-27 2020-09-16 2020-06-01 2020-09-30 2020-11-28 Project Management ant Selection ementale, pour le compte du Programme Multisectoriel de Nutrition et de Santé ZR-DRC-MSP-179043-CS-IND V / RECRUTEMENT D´UN SPE Capacity Strengthening and Individual Consult IDA / 64410 Prior Open 228,000.00 57,000.00 Signed 2020-06-15 2020-07-17 2020-08-03 2020-12-23 2020-08-24 2021-01-19 2020-09-28 2021-01-26 2021-03-27 CIALISTE VIOLENCE BASE SU Project Management ant Selection R LE GENRE AU SEIN DE DU PROJET PMNS ZR-DRC-MSP-182812-CS-CD S / Contractualisation en ent ente directe avec YOUSSOUF Capacity Strengthening and IDA / V2420 Post Direct Selection Direct 6,000.00 5,860.00 Signed 2020-07-08 2020-07-13 2020-07-18 2020-08-06 2020-09-21 2020-08-08 2021-03-20 CISSE, consultant chargé de l Project Management 'élaboration du manuel de mi se en oeuvre opérationnel de s activités du PMNS ZR-DRC-MSP-104563-CS-CD Improving the Delivery of Co S / Contractualisation avec B mmunity Interventions and LUESQUARE pour développer / Prior Direct Selection Direct 900,000.00 0.00 Canceled 2019-08-22 2019-09-01 2019-11-05 2020-05-03 Social and Behavioral Chang et tester un système de la vé e rification base sur les risques ZR-DRC-MSP-185078-CS-IND V / Recrutement d'un audite Capacity Strengthening and Individual Consult Pending Impleme ur interne pour le respect de IDA / 64410 Post Open 240,000.00 0.00 2020-08-27 2020-10-15 2020-11-05 2020-12-10 2021-06-08 Project Management ant Selection ntation s procédures des gestions ad ministratives et financières d u PMNS ZR-DRC-MSP-196577-CS-IND V / Recrutement d'un assista Capacity Strengthening and Individual Consult IDA / V1400 Prior Open 216,000.00 57,000.00 Signed 2020-09-30 2020-11-16 2020-11-18 2021-06-22 2020-12-09 2021-07-12 2021-01-13 2021-06-30 2021-07-12 nt technique volet agricole e Project Management ant Selection n appui au PMNS ZR-DRC-MSP-185076-CS-IND Individual Consult Under Implement V / Recrutement des trois (3) IDA / 64410 CERC Post Open 151,200.00 0.00 2020-12-14 2020-12-01 2021-02-01 2021-02-22 2021-03-29 2021-09-25 ant Selection ation chauffeurs pour le compte du PMNS ZR-DRC-MSP-197616-CS-IND V / Recrutement d'un Consult Capacity Strengthening and Individual Consult ant Individuel chargé de la C IDA / V2420 Post Open 80,000.00 0.00 Canceled 2021-01-20 2020-10-02 2021-03-10 2021-03-31 2021-05-05 2021-11-01 Project Management ant Selection artographie Générique Violen ce Basée sur le Genre pour P MNS ZR-DRC-MSP-105638-CS-IND Capacity Strengthening and Individual Consult V / Recrutement d'un Respon / Prior Open 216,000.00 0.00 Canceled 2019-05-13 2019-05-14 2019-07-01 2019-07-22 2019-08-26 2020-02-22 Project Management ant Selection sable Administratif et Financi er ZR-DRC-MSP-105631-CS-IND Capacity Strengthening and Individual Consult V / Recrutement d'un Assista / Prior Open 216,000.00 0.00 Canceled 2019-06-17 2019-12-19 2019-08-05 2019-08-26 2019-09-30 2020-03-28 Project Management ant Selection nt Technique en appui au Vol et agriculture Page 6 ZR-DRC-MSP-212818-CS-IND Capacity Strengthening and Individual Consult V / Recrutement d' un Assista IDA / 64410 Post Open 54,000.00 0.00 Canceled 2021-02-15 2021-04-05 2021-04-26 2021-05-31 2021-11-27 Project Management ant Selection nt Technique en appui au vol et Education ZR-DRC-MSP-105635-CS-IND Capacity Strengthening and Individual Consult V / Recrutement d'un Assista / Prior Open 216,000.00 0.00 Canceled 2019-05-13 2019-07-01 2019-07-22 2019-08-26 2020-02-22 Project Management ant Selection nt Technique en appui au Vol et Education ZR-DRC-MSP-212819-CS-IND V / Recrutement d' un Assista Capacity Strengthening and Individual Consult Pending Impleme IDA / 64410 Post Open 54,000.00 0.00 2021-02-23 2021-04-13 2021-05-04 2021-06-08 2021-12-05 nt Technique en appui au vol Project Management ant Selection ntation et Protection Sociale ZR-DRC-MSP-105634-CS-IND V / Recrutement d'un Assista Capacity Strengthening and Individual Consult / Prior Open 216,000.00 0.00 Canceled 2019-06-17 2019-08-05 2019-08-26 2019-09-30 2020-03-28 nt Technique en appui au Vol Project Management ant Selection et protection sociale ZR-DRC-MSP-212824-CS-IND V / Recrutement d'un Consult Capacity Strengthening and Individual Consult Pending Impleme ant pour l’identification et l'e IDA / 64410 Post 15,000.00 0.00 2021-03-24 2021-03-29 2021-04-19 2021-05-24 2021-11-20 Project Management ant Selection ntation stimation des besoins d’amél ioration du laboratoire d'anal yse du Pronanut ZR-DRC-MSP-212829-CS-IND V / Recrutement d’un Consult ant (ou groupe de consultant s) pour la détermination d’un Capacity Strengthening and Individual Consult Pending Impleme IDA / 64410 Post Open 50,000.00 0.00 2021-02-25 2021-04-15 2021-05-06 2021-06-10 2021-12-07 taux de paiement conforme Project Management ant Selection ntation à la situation socio-économiq ue dans les zones ciblées po ur les participants aux activit és de « cash Transfer » ZR-DRC-MSP-212839-CS-IND Capacity Strengthening and Individual Consult V / Recrutement d’un contrôl IDA / 64410 Post Open 160,000.00 0.00 Canceled 2021-03-17 2021-05-05 2021-05-26 2021-06-30 2021-12-27 Project Management ant Selection eur de gestion ZR-DRC-MSP-212845-CS-CD Convergence Demonstration S / Contractualisation avec le IDA / 64410 Prior Direct Selection Direct 24,000,000.00 0.00 Canceled 2021-03-24 2021-04-03 2021-06-07 2021-12-04 Project s EUPs pour l’achat stratégiq ue ZR-DRC-MSP-182814-CS-CD S / Contractualisation en ent Capacity Strengthening and ente directe avec l'agence de IDA / D4790 Prior Direct Selection Direct 2,000,000.00 0.00 Canceled 2020-07-13 2020-08-25 2020-07-23 2020-09-26 2021-03-25 Project Management contre vérification externe (C REDES) pour l'achat stratégiq ue ZR-DRC-MSP-212849-CS-CD S / Contractualisation avec C CP/JHU pour développer et m IDA / 64410 CERC Prior Direct Selection Direct 10,000,000.00 0.00 Canceled 2021-02-24 2021-02-23 2021-03-06 2021-05-10 2021-11-06 ettre en œuvre la stratégie d e changement de comporte ment et de changement soci al ZR-DRC-MSP-197607-CS-IND V / Consultant International c Capacity Strengthening and Individual Consult Pending Impleme IDA / V2420 Post Open 50,000.00 0.00 2021-02-02 2021-03-23 2021-04-13 2021-05-18 2021-11-14 hargé de l'élaboration du pla Project Management ant Selection ntation n stratégique du PNSA ZR-DRC-MSP-212880-CS-IND V / Recrutement d'un Consult Capacity Strengthening and Individual Consult Pending Impleme IDA / 64410 Post Open 50,000.00 0.00 2021-03-16 2021-05-04 2021-05-25 2021-06-29 2021-12-26 ant international pour l'élabo Project Management ant Selection ntation ration du plan stratégique d u PNSR ZR-DRC-MSP-212883-CS-IND V / Recrutement d' un Consul tant individuel pour évaluer l es besoins en appui et propo Capacity Strengthening and Individual Consult ser un plan de renforcement IDA / 64410 Post Open 50,000.00 0.00 Canceled 2021-03-30 2021-05-18 2021-06-08 2021-07-13 2022-01-09 Project Management ant Selection des capacités des Directions et Services techniques des M inistères de l’Agriculture et d e Pêche et Elevage qui interv iennent dans la mise en œuv ZR-DRC-MSP-212887-CS-IND Improving the Delivery of Co Individual Consult V / Recrutement d'un AT en a IDA / 64410 mmunity Interventions and Post Open 54,000.00 0.00 Canceled 2021-03-30 2021-05-18 2021-06-08 2021-07-13 2022-01-09 ant Selection ppui au PRONANUT Social and Behavioral Chang e ZR-DRC-MSP-185071-CS-IND Improving the Delivery of Co Individual Consult V / Recrutement d'un assista IDA / 64410 mmunity Interventions and Prior Open 216,000.00 0.00 Canceled 2021-01-05 2020-11-12 2021-02-23 2021-03-16 2021-04-20 2021-10-17 ant Selection nt technique en appui au PR Social and Behavioral Chang ONANUT e ZR-DRC-MSP-212894-CS-IND V / Recrutement d'un AT char Individual Consult Under Implement IDA / 64410 CERC Post Open 54,000.00 0.00 2021-03-23 2021-02-27 2021-05-11 2021-06-01 2021-07-06 2022-01-02 gé du suivi des activités du P ant Selection ation MNS dans le Sud Kivu ZR-DRC-MSP-185103-CS-IND Improving the Delivery of Co V / Recrutement d'un assista mmunity Interventions and Individual Consult IDA / 64410 Prior Open 216,000.00 0.00 Canceled 2020-11-16 2021-01-04 2021-01-25 2021-03-01 2021-08-28 nt technique en appui au PM Social and Behavioral Chang ant Selection NS dans le KASAI e ZR-DRC-MSP-185099-CS-IND Improving the Delivery of Co V / Recrutement d'un assista mmunity Interventions and Individual Consult IDA / 64410 Prior Open 216,000.00 0.00 Canceled 2020-11-16 2021-01-04 2021-01-25 2021-03-01 2021-08-28 nt technique en appui au PM Social and Behavioral Chang ant Selection NS dans le Kasai-Central e ZR-DRC-MSP-185101-CS-IND Improving the Delivery of Co V / Recrutement d'un assista mmunity Interventions and Individual Consult IDA / 64410 Prior Open 216,000.00 0.00 Canceled 2020-11-16 2021-01-04 2021-01-25 2021-03-01 2021-08-28 nt technique en appui au PM Social and Behavioral Chang ant Selection NS dans le KWILU e ZR-DRC-MSP-209302-CS-CD S / Contractualisation par ent ente directe avec Médecin d' Afrique (MEDA), pour l' Etude Under Implement IDA / 64410 CERC Post Direct Selection Direct 210,000.00 0.00 2021-02-17 2021-03-03 2021-02-27 2021-05-03 2021-10-30 de base sur les indicateurs n ation utritionnels dans les provinc es d'intervention du PMNS da ns le cadre de l'étude d'impa ct du PDSS Page 7 ZR-DRC-MSP-185096-CS-IND Improving the Delivery of Co V / Recrutement d'un assista mmunity Interventions and Individual Consult IDA / 64410 Prior Open 216,000.00 0.00 Canceled 2020-11-16 2021-01-04 2021-01-25 2021-03-01 2021-08-28 nt technique en appui au PM Social and Behavioral Chang ant Selection NS dans le Sud-Kivu e ZR-DRC-MSP-197611-CS-IND Improving the Delivery of Co Individual Consult V / Recrutement d'un Spécial IDA / 64410 mmunity Interventions and Prior Open 240,000.00 0.00 Canceled 2020-11-18 2021-01-06 2021-01-27 2021-03-03 2021-08-30 ant Selection iste en Nutrition pour le PMN Social and Behavioral Chang S e ZR-DRC-MSP-185075-CS-IND Individual Consult V / Recrutement d'une assist IDA / 64410 CERC Post Open 128,000.00 0.00 Canceled 2020-12-23 2021-02-10 2021-03-03 2021-04-07 2021-10-04 ant Selection ante de programme ZR-DRC-MSP-204735-CS-CD S / Contractualisation par ent ente directe avec Center for Communication Programms ( CCP)/ John HOPKINS Universit IDA / 64410 CERC Prior Direct Selection Direct 2,500,000.00 0.00 Canceled 2020-11-16 2020-11-26 2021-01-30 2021-07-29 y pour une Recherche Forma tive et le développement de l a stratégie de communicatio n pour le changement social et comportements ZR-DRC-MSP-217495-CS-IND V / Recrutement d'un Consult ant Individuel chargé de la R éalisation des Etudes Techni Capacity Strengthening and Individual Consult IDA / 64410 Post Open 100,000.00 0.00 Canceled 2021-03-25 2021-02-26 2021-05-13 2021-06-03 2021-07-08 2022-01-04 ques et surveillance des trav Project Management ant Selection aux de Réhabilitation, extens ion des Bureaux et Laboratoi res du PRONANUT à Kinshasa /Gombe ZR-DRC-MSP-212834-CS-IND V / Recrutement d’un Assista Capacity Strengthening and Individual Consult Pending Impleme IDA / 64410 Prior Open 360,000.00 0.00 2021-03-30 2021-05-18 2021-06-08 2021-07-13 2022-01-09 nt Technique en gestion fina Project Management ant Selection ntation ncière et comptable ZR-DRC-MSP-212898-CS-IND Improving the Delivery of Co V / Recrutement d'un AT char mmunity Interventions and Individual Consult IDA / 64410 Post Open 162,000.00 56,400.00 Signed 2021-03-30 2021-02-27 2021-05-18 2021-07-07 2021-06-08 2021-08-18 2021-07-13 2021-09-21 2022-01-09 gé du suivi des activités du Social and Behavioral Chang ant Selection PMNS dans le Kwilu e ZR-DRC-MSP-212910-CS-IND Improving the Delivery of Co V / Recrutement d'un Consult mmunity Interventions and Individual Consult Pending Impleme IDA / 64410 Post Open 54,000.00 0.00 2021-03-25 2021-05-13 2021-06-03 2021-07-08 2022-01-04 ant spécialiste en Nutrition p Social and Behavioral Chang ant Selection ntation our le PRONANUT e ZR-DRC-MSP-212882-CS-IND V / Recrutement d'un Consult Capacity Strengthening and Individual Consult IDA / 64410 Post Open 20,000.00 0.00 Canceled 2021-03-25 2021-05-13 2021-06-03 2021-07-08 2022-01-04 ant national pour l'élaboratio Project Management ant Selection n du plan strategique du PNS R ZR-DRC-MSP-212914-CS-IND Capacity Strengthening and Individual Consult V / Recrutement d'un Consult IDA / V1400 Post Open 272,000.00 0.00 Canceled 2021-03-31 2021-05-19 2021-06-09 2021-07-14 2022-01-10 Project Management ant Selection ant spécialiste en Nutrition p our le PMNS ZR-DRC-MSP-185053-CS-IND V / Recrutement d'un consult Capacity Strengthening and Individual Consult Pending Impleme IDA / V2420 Post Open 20,000.00 0.00 2021-04-15 2021-06-03 2021-06-24 2021-07-29 2022-01-25 ant national pour l'élaboratio Project Management ant Selection ntation n d'un plan stratégique du P NSA ZR-DRC-MSP-212896-CS-IND V / Recrutement d'un AT char Individual Consult IDA / 64410 CERC Post Open 162,000.00 56,400.00 Signed 2021-03-23 2021-03-11 2021-05-11 2021-07-07 2021-06-01 2021-08-18 2021-07-06 2021-09-21 2022-01-02 gé du suivi des activités du ant Selection PMNS dans le Kasai ZR-DRC-MSP-212895-CS-IND V / Recrutement d'un AT char Individual Consult IDA / 64410 CERC Post Open 162,000.00 56,400.00 Signed 2021-03-25 2021-03-11 2021-05-13 2021-08-17 2021-06-03 2021-08-18 2021-07-08 2021-09-21 2022-01-04 gé du suivi des activités du P ant Selection MNS dans le Kasai Central ZR-DRC-MSP-220149-CS-CD S / Contractualisation avec l' Capacity Strengthening and IDA / 64410 Prior Direct Selection Direct 25,000,000.00 24,941,597.69 Signed 2021-03-17 2021-05-28 2021-03-27 2021-06-14 2021-05-31 2022-03-03 2021-11-27 UNICEF pour l'acquisition des Project Management intrants nutritionnels pour le compte du PMNS ZR-DRC-MSP-222858-CS-IND V / Recrutement d'un AT char Individual Consult Pending Impleme IDA / 64410 CERC Post Open 162,000.00 0.00 2021-03-30 2021-05-18 2021-06-08 2021-07-13 2022-01-09 gé du suivi des activités du P ant Selection ntation MNS dans le Sud Kivu ZR-DRC-MSP-225929-CS-IND V / Recrutement d'un Consult ant Individuel chargé de la R éalisation des Etudes Techni Capacity Strengthening and Individual Consult IDA / 64410 Post Limited 100,000.00 30,000.00 Signed 2021-03-31 2021-03-31 2021-04-05 2021-04-14 2021-04-26 2021-06-24 2021-05-31 2021-07-02 2021-11-27 ques (actualisation) et survei Project Management ant Selection llance des travaux de Réhabil itation, extension des Bureau x et Laboratoires du PRONAN UT à Kinshasa / Gombe ZR-DRC-MSP-228773-CS-CD S / Contractualisation par ent ente directe avec CCP/JHU po ur la recherche formative po ur la mise en œuvre de la str IDA / 64410 CERC Prior Direct Selection Direct 500,000.00 518,461.94 Signed 2021-04-29 2021-04-27 2021-05-09 2021-06-25 2021-07-13 2021-10-01 2022-01-09 atégie de communication po ur le changement social et d e comportement en faveur d’ une nutrition adéquate et de la promotion de la planificati on ZR-DRC-MSP-228776-CS-CD S / Contractualisation par ent ente direct avec CCP/JHU pou r l'élaboration de la stratégie IDA / 64410 CERC Prior Direct Selection Direct 9,000,000.00 0.00 Canceled 2021-04-30 2021-05-10 2021-07-14 2022-01-10 de communication pour le ch angement social et de compo rtement en faveur d’une nutr ition adéquate et de la prom otion de la planification famili ale ZR-DRC-MSP-234322-CS-IND Improving the Delivery of Co Individual Consult Under Implement V / Recrutement d'un assista IDA / 64410 mmunity Interventions and Prior Open 270,000.00 0.00 2021-05-31 2021-06-15 2021-07-19 2022-01-28 2021-08-09 2021-09-13 2022-03-12 ant Selection ation nt technique en appui au PR Social and Behavioral Chang ONANUT e Page 8 ZR-DRC-MSP-234328-CS-IND V / Contractualisation par ent ente directe avec Monsieur E Individual Consult IDA / 64410 CERC Prior Direct 228,000.00 0.00 Canceled 2021-06-23 2021-07-26 2021-07-03 2021-07-24 2021-08-28 2022-02-24 variste KAYEMBE consultant ant Selection spécialiste en violence basée sur le Genre en appui au PM NS ZR-DRC-MSP-234340-CS-IND V / Recrutement d'un consult ant senior chargé de l'évalua Individual Consult IDA / 64410 CERC Post Open 7,000.00 0.00 Canceled 2021-06-23 2021-08-11 2021-09-01 2021-10-06 2022-04-04 tion des demandes des propo ant Selection sitions techniques et financiè res des ONG NAC dans le cad re du PMNS ZR-DRC-MSP-234345-CS-IND V / Contractualisation par ent Individual Consult Under Implement ente directe avec Monsieur A IDA / 64410 CERC Prior Direct 318,000.00 0.00 2021-06-29 2021-11-16 2021-07-09 2021-07-30 2021-09-03 2022-03-02 ant Selection ation braham MAFUMO TOBOLOLO , spécialiste en gestion finan cière en appui au PMNS ZR-DRC-MSP-235335-CS-IND Improving the Delivery of Co V / Sélection et Recrutement mmunity Interventions and Individual Consult Under Implement IDA / 64410 Prior Open 216,000.00 0.00 2021-07-15 2021-09-02 2021-09-23 2021-10-28 2022-04-26 d'un assistant technique nutr Social and Behavioral Chang ant Selection ation ition pour le PMNS e ZR-DRC-MSP-255693-CS-CD S / Contractualisation par ent ente directe avec l'AAP/EUP S Convergence Demonstration IDA / 64410 Prior Direct Selection Direct 2,285,465.00 1,919,947.00 Signed 2021-10-12 2021-11-10 2021-10-22 2021-12-09 2021-12-26 2022-02-06 2022-06-24 UD-KIVU pour la mise en œu Project vre de l'achat stratégique d ans la province du Sud-Kivu ZR-DRC-MSP-255696-CS-CD S / Contractualisation en ent Convergence Demonstration ente directe avec AAP/EUP-B IDA / 64410 Prior Direct Selection Direct 2,500,000.00 2,549,470.69 Signed 2021-10-13 2022-02-23 2021-10-23 2022-03-03 2021-12-27 2022-03-02 2022-06-25 Project andundu pour la mise en œu vre de l'achat stratégique da ns la province du Bandundu ZR-DRC-MSP-255699-CS-CD S / Contractualisation en ent ente directe avec AAP/EUP-K Convergence Demonstration IDA / 64410 Prior Direct Selection Direct 1,383,296.00 3,549,513.93 Signed 2021-10-13 2021-11-29 2021-10-23 2022-01-28 2021-12-27 2022-04-03 2022-06-25 asai-Central pour la mise en Project œuvre de l'achat stratégique dans la province du Kasai-Ce ntral ZR-DRC-MSP-255701-CS-CD S / Contractualisation en ent Convergence Demonstration ente directe avec AAP/EUP-K IDA / 64410 Prior Direct Selection Direct 1,120,608.00 2,966,302.58 Signed 2021-10-13 2021-11-29 2021-10-23 2022-01-28 2021-12-27 2022-04-03 2022-06-25 Project asai pour la mise en œuvre d e l'achat stratégique dans la province du Kasai. ZR-DRC-MSP-261476-CS-IND V / Recrutement d'un consult Capacity Strengthening and Individual Consult ant Chargé de l'élaboration d IDA / 64410 Post Open 70,000.00 0.00 Canceled 2021-11-30 2022-03-23 2022-01-18 2022-02-08 2022-03-15 2022-09-11 Project Management ant Selection u plan stratégique national m ultisectoriel de nutrition 2022 -2026 ZR-DRC-MSP-266790-CS-IND Individual Consult Pending Impleme V / Recrutement d’une Assist IDA / 64410 CERC Post Limited 30,000.00 0.00 2022-01-26 2022-01-31 2022-02-21 2022-03-28 2022-09-24 ant Selection ntation ante au Programme en appui à l’UG-PDSS ZR-DRC-MSP-266793-CS-IND V / Recrutement en urgence d’Un Expert National Junior e Individual Consult Under Implement IDA / 64410 CERC Post Limited 54,000.00 0.00 2022-01-28 2022-02-15 2022-02-02 2022-02-23 2022-03-30 2022-09-26 n Passation des marchés cha ant Selection ation rgés d’appuyer le service de Passation des marchés de l’U nité de Gestion du PDSS ZR-DRC-MSP-212846-CS-CD S / Contractualisation avec u Capacity Strengthening and IDA / D4790 Prior Direct Selection Direct 2,000,000.00 0.00 Canceled 2021-04-05 2021-09-13 2021-04-15 2021-06-19 2021-12-16 ne agence de contre-vérificat Project Management ion (GINGER CREDES) de l’ac hat stratégique ZR-DRC-MSP-272846-CS-CD S / Contractualisation avec l e UNFPA chargé de la mise e n œuvre des activités de pré Improving Service Supply an Under Implement vention et réponse aux Viole IDA / 64410 Prior Direct Selection Direct 6,500,000.00 0.00 2022-03-24 2022-02-08 2022-04-03 2022-06-07 2022-12-04 d Strategic Purchasing ation nces Basées sur le Genre (VB G), y compris l’exploitation et les abus sexuels (EAS) et le harcèlement sexuel (HS), da ns le cadre de PMNS ZR-DRC-MSP-272805-CS-CD S / Contractualisation par ent ente directe avec CREDES GI Improving Service Supply an IDA / 64410 Prior Direct Selection Direct 2,000,000.00 0.00 Signed 2022-03-24 2022-02-27 2022-04-03 2022-03-17 2022-06-07 2022-12-04 NGER en vue de la contre vé d Strategic Purchasing rification des prestations de l' achat stratégique et des serv ices des ONG NAC et ONG PF . ZR-DRC-MSP-282022-CS-IND Improving the Delivery of Co V / Recrutement d'un consult mmunity Interventions and Individual Consult Pending Impleme ant international en appui a IDA / 64410 Post Open 70,000.00 0.00 2022-03-31 2022-05-19 2022-06-09 2022-07-14 2023-01-10 Social and Behavioral Chang ant Selection ntation u processus de l'élaboration e du PNSMN 2022 2026 ZR-DRC-MSP-282020-CS-IND Improving the Delivery of Co V / Recruter un consultant na mmunity Interventions and Individual Consult IDA / 64410 Post Limited 20,000.00 0.00 Signed 2022-03-31 2022-10-19 2022-04-05 2023-01-11 2022-04-26 2022-12-21 2022-05-31 2022-11-27 tional en appui au processu Social and Behavioral Chang ant Selection s de l'élaboration du PNSMN e 2022 2026 ZR-DRC-MSP-282051-CS-IND V / Recrutement de 4 Consult ants individuels pour les étud Improving Service Supply an Individual Consult Pending Impleme IDA / 64410 Prior Open 350,000.00 0.00 2022-04-30 2022-06-18 2022-07-09 2022-08-13 2023-02-09 es préalables en vue des réh d Strategic Purchasing ant Selection ntation abilitations et constructions des FOSA de démonstration dans les 4 provinces ciblées ZR-DRC-MSP-282042-CS-IND Capacity Strengthening and Individual Consult Pending Impleme V / Recrutement d'un assista IDA / 64410 Post Open 54,000.00 0.00 2022-03-25 2022-05-13 2022-06-03 2022-07-08 2023-01-04 Project Management ant Selection ntation nt technique Nutrition Page 9 ZR-DRC-MSP-286042-CS-IND V / Recrutement de 6 Experts Capacity Strengthening and Individual Consult Under Implement spécialisés dans différents do IDA / 64410 Post Limited 90,000.00 0.00 2022-03-31 2022-03-22 2022-04-05 2022-04-26 2022-05-31 2022-11-27 Project Management ant Selection ation maines techniques en rappor t avec les activités mises en œuvre par le PMNS ZR-DRC-MSP-286670-CS-CD S / Contractualisation avec l' Ecole de santé Publique de l' Improving the Delivery of Co UNIKIN pour appuyer le PRO mmunity Interventions and NANUT dans l'organisation d IDA / 64410 Post Direct Selection Direct 400,000.00 0.00 Canceled 2022-04-29 2022-05-09 2022-07-13 2023-01-09 Social and Behavioral Chang e qualité des formations de r e enforcement des capacités d es acteurs Provinciaux dans les DPS Sud Kivu, Kwilu, Kasa ï et Kasaï Central ZR-DRC-MSP-301732-CS-IND V / Recrutement d'un Consult ant Individuel chargé d'élabo Convergence Demonstration Individual Consult Under Implement IDA / 64410 Post Open 100,000.00 0.00 2022-07-20 2022-08-15 2022-09-07 2022-09-28 2022-11-02 2023-05-01 rer le Cadre de Protection de Project ant Selection ation s peuples autochtones (CPPA ) dans les provinces concern ées par le PMNS ZR-DRC-MSP-309950-CS-IND V / Recrutement d'un Spécial Convergence Demonstration Individual Consult Under Implement iste provincial en sauvegarde IDA / 64410 Post Open - National 56,400.00 0.00 2022-09-15 2022-08-16 2022-11-03 2022-11-24 2022-12-29 2023-06-27 Project ant Selection ation environnementale et sociale pour la province du Sud-Kivu ZR-DRC-MSP-309955-CS-IND V / Recrutement d'un Spécial Convergence Demonstration Individual Consult Under Implement iste provincial en sauvegarde IDA / 64410 Post Open - National 56,400.00 0.00 2022-09-15 2022-08-16 2022-11-03 2022-11-24 2022-12-29 2023-06-27 Project ant Selection ation environnementale et sociale pour la province du Kwilu ZR-DRC-MSP-309958-CS-IND V / Recrutement d'un Spécial Convergence Demonstration Individual Consult Under Implement iste provincial en sauvegarde IDA / 64410 Post Open - National 56,400.00 0.00 2022-09-15 2022-08-16 2022-11-03 2022-11-24 2022-12-29 2023-06-27 Project ant Selection ation environnemental et social po ur la province du Kasaï Centr al ZR-DRC-MSP-309957-CS-IND V / Recrutement d'un Spécial Convergence Demonstration Individual Consult Under Implement iste provincial en sauvegarde IDA / 64410 Post Open - National 56,400.00 0.00 2022-09-15 2022-08-16 2022-11-03 2022-11-24 2022-12-29 2023-06-27 Project ant Selection ation environnemental et social po ur la province du Kasaï ZR-DRC-MSP-309959-CS-IND V / Recrutement d'un Consult Convergence Demonstration Individual Consult Under Implement IDA / 64410 Post Open - National 70,000.00 0.00 2022-09-30 2022-08-16 2022-11-18 2022-12-09 2023-01-13 2023-07-12 ant Individuel chargé de l'éla Project ant Selection ation boration d'un Plan de santé e t bien être animal ZR-DRC-MSP-311245-CS-IND V / Recrutement d’un consult Improving the Delivery of Co ant international en appui au mmunity Interventions and Individual Consult IDA / 64410 Post Limited 70,000.00 0.00 Signed 2022-09-15 2022-10-06 2022-09-20 2022-10-14 2022-10-11 2023-02-09 2022-11-15 2023-05-14 processus de l’élaboration du Social and Behavioral Chang ant Selection Plan Stratégique National Mu e ltisectoriel de Nutrition 2022 – 2026 ZR-DRC-MSP-325942-CS-IND V / Recrutement d’un Assista Capacity Strengthening and Individual Consult Under Implement IDA / 64410 Post Open - National 57,000.00 0.00 2022-12-20 2022-11-28 2023-02-07 2023-02-28 2023-04-04 2023-10-01 nt technique en Santé publiq Project Management ant Selection ation ue pour la province du Kasaï ZR-DRC-MSP-325956-CS-IND V / Recrutement d’un Assista Capacity Strengthening and Individual Consult Under Implement IDA / 64410 Post Open - National 57,000.00 0.00 2022-12-20 2022-11-28 2023-02-07 2023-02-28 2023-04-04 2023-10-01 nt technique en Santé publiq Project Management ant Selection ation ue pour la province du Kasaï- Central ZR-DRC-MSP-325958-CS-IND V / Recrutement d’un Assista Capacity Strengthening and Individual Consult Under Implement IDA / 64410 Post Open - National 57,000.00 0.00 2022-12-20 2022-11-28 2023-02-07 2023-02-28 2023-04-04 2023-10-01 nt technique en Santé publiq Project Management ant Selection ation ue pour la province du Kwilu ZR-DRC-MSP-325959-CS-IND V / Recrutement d’un Assista Capacity Strengthening and Individual Consult Under Implement IDA / 64410 Post Open - National 57,000.00 0.00 2022-12-20 2022-11-28 2023-02-07 2023-02-28 2023-04-04 2023-10-01 nt technique en Santé publiq Project Management ant Selection ation ue pour la province du Sud-Ki vu ZR-DRC-MSP-282026-CS-CD Improving the Delivery of Co S / Contrat avec CCP/JHU pou mmunity Interventions and IDA / 64410 Post Direct Selection Direct 466,615.75 0.00 Canceled 2022-04-26 2022-05-06 2022-07-10 2023-01-06 r la recherche formative sur Social and Behavioral Chang la nutrition et la planification e ZR-DRC-MSP-282023-CS-CD Improving the Delivery of Co S / Contrat avec CCP/JHU pou mmunity Interventions and r le développement de la str IDA / 64410 Prior Direct Selection Direct 948,153.81 0.00 Canceled 2022-10-25 2022-11-04 2023-01-08 2023-07-07 Social and Behavioral Chang atégie de communication po e ur le changement social et d e comportement ZR-DRC-MSP-319202-CS-CD S / Recrutement de Monsieur Willy N'SHOLE en qualité de Capacity Strengthening and Consultant individuel chargé IDA / 64410 Post Direct Selection Direct - National 45,000.00 0.00 Signed 2022-11-25 2022-12-02 2022-12-05 2022-12-14 2023-02-08 2023-08-07 Project Management de contrôle et surveillance d es travaux de réhabilitation d es locaux devant abriter les bureaux du PRONANUT ZR-DRC-MSP-329777-CS-IND V / Recrutement d'un Consult ant Individuel Expert Pharma Capacity Strengthening and Individual Consult Pending Impleme cien en charge de suivi des a IDA / 64410 Post Open - National 56,000.00 0.00 2022-12-31 2023-02-18 2023-03-11 2023-04-15 2023-10-12 Project Management ant Selection ntation cquisitions en médicaments et autres intrants effectués p ar l'UG-PDSS aux niveaux de s provinces ZR-DRC-MSP-212889-CS-IND Individual Consult V / Recrutement d'une assist IDA / 64410 CERC Post Open 30,000.00 0.00 Canceled 2021-03-23 2021-12-03 2021-05-11 2021-06-01 2021-07-06 2022-01-02 ant Selection ante de programme ZR-DRC-MSP-104593-CS-IND V / Recrutement d'un consult ant individuel pour les étude Capacity Strengthening and Individual Consult / Post Limited 50,000.00 0.00 Canceled 2019-07-31 2019-08-05 2019-08-26 2019-09-30 2020-03-28 s de faisabilité et de concepti Project Management ant Selection on des infrastructures d'eau hygiène et assainissement Page 10 ZR-DRC-MSP-105650-CS-IND Improving the Delivery of Co V / Recrutement d'un consult mmunity Interventions and Individual Consult / Post Limited 350,000.00 0.00 Canceled 2019-05-23 2019-05-28 2019-06-18 2019-07-23 2020-01-19 ant pour faire l'état des lieux Social and Behavioral Chang ant Selection des FOSA dans les cinq provi e nces ciblées ZR-DRC-MSP-212885-CS-IND V / Recrutement d' un Consul tant individuel pour évaluer l es besoins en appui en terme Capacity Strengthening and Individual Consult s de renforcement des capaci IDA / 64410 Post Open 15,000.00 0.00 Canceled 2021-03-26 2021-05-14 2021-06-04 2021-07-09 2022-01-05 Project Management ant Selection tés techniques, opérationnell es et managériales au CAPSA Benalongo pour contribuer e fficacement dans la producti on et la diffusion des semenc es ZR-DRC-MSP-334421-CS-IND Improving the Delivery of Co V / Recrutement de Monsieur mmunity Interventions and Individual Consult BANYWESIZE CHIGANGU Cla IDA / 64410 Post Direct - National 56,400.00 0.00 Signed 2023-01-20 2023-01-18 2023-01-30 2023-01-24 2023-02-20 2023-02-02 2023-03-27 2023-09-23 Social and Behavioral Chang ant Selection ude en qualité d'Assistant Te e chnique en Nutrition pour le PMNS ZR-DRC-MSP-334424-CS-IND V / Recrutement de Monsieur Capacity Strengthening and Individual Consult Yancy KABONGO en qualité d IDA / 64410 Post Direct - National 36,000.00 0.00 Signed 2023-01-20 2023-01-15 2023-01-30 2023-01-26 2023-02-20 2023-01-31 2023-03-27 2023-09-23 Project Management ant Selection e Consultant Individuel Comp table pour le PMNS ZR-DRC-MSP-334426-CS-IND V / Recrutement de Monsieur Capacity Strengthening and Individual Consult MUNGU Philémon en qualité IDA / 64410 Post Direct - National 36,000.00 0.00 Canceled 2023-01-20 2023-01-15 2023-01-30 2023-01-26 2023-02-20 2023-03-27 2023-09-23 Project Management ant Selection de Consultant Individuel Com ptable pour le PMNS ZR-DRC-MSP-343081-CS-IND V / Recrutement de Madame Capacity Strengthening and Individual Consult IDA / 64410 Post Direct - National 36,000.00 0.00 Signed 2023-02-20 2023-02-27 2023-03-02 2023-03-01 2023-03-23 2023-03-02 2023-04-27 2023-10-24 Sylvie NGEVESISE en qualité Project Management ant Selection de Consultant Comptable po ur le PMNS ZR-DRC-MSP-343083-CS-IND V / Renouvellement du contr Capacity Strengthening and Individual Consult Pending Impleme at de Monsieur Olivier MBO IL IDA / 64410 Post Direct - National 67,200.00 0.00 2023-02-20 2023-03-02 2023-03-23 2023-04-27 2023-10-24 Project Management ant Selection ntation ENGA en qualité de Spécialist e en Passation des Marchés p our le PMNS ZR-DRC-MSP-344301-CS-IND V / Recrutement d'un deuxiè Capacity Strengthening and Individual Consult Under Implement IDA / 64410 Post Limited 67,200.00 0.00 2023-03-15 2023-02-27 2023-03-20 2023-04-10 2023-05-15 2023-11-11 me Spécialiste en Passation Project Management ant Selection ation des Marchés pour le PMNS ZR-DRC-MSP-246445-CS-CD S / Contractualisation par ent ente directe (ED) avec INACO , Institut National des Archive Capacity Strengthening and s du Congo, pour l’archivage IDA / 64410 Post Direct Selection Direct 200,000.00 0.00 Canceled 2021-08-26 2021-08-20 2021-09-05 2021-11-09 2022-05-08 Project Management électronique et physique des données et documents de l’U nité de Gestion du Programm e de Développement du Syst ème de Santé, « UG – PDSS ZR-DRC-MSP-325928-CS-CD S / Contractualisation avec JH U pour l’élaboration de la str Improving the Delivery of Co atégie de communication po mmunity Interventions and Direct - Internation Under Implement ur le changement social et d IDA / 64410 Prior Direct Selection 9,000,000.00 0.00 2023-03-31 2023-04-13 2023-04-10 2023-06-14 2023-12-11 Social and Behavioral Chang al ation e comportement (CCSC) en f e aveur d’une nutrition adéqua te et de la promotion de la pl anification familiale chez les adolescentes et les femmes ZR-DRC-MSP-357684-CS-IND V / Recrutement d'un Consult ant Individuel Ingénieur char Capacity Strengthening and Individual Consult Pending Impleme IDA / 64410 Post Open - National 45,000.00 0.00 2023-06-30 2023-08-18 2023-09-08 2023-10-13 2024-04-10 gé de suivi des activités de r Project Management ant Selection ntation éhabilitation des structures s anitaires dans la province du Kasaï ZR-DRC-MSP-357692-CS-IND V / Recrutement d’un Consult ant Individuel Ingénieur char Capacity Strengthening and Individual Consult Pending Impleme IDA / 64410 Post Open - National 45,000.00 0.00 2023-05-31 2023-07-19 2023-08-09 2023-09-13 2024-03-11 gé de suivi des activités de r Project Management ant Selection ntation éhabilitation des structures s anitaires dans la province du Kasaï Central ZR-DRC-MSP-357697-CS-IND V / Recrutement d’un Consult ant Individuel Ingénieur char Capacity Strengthening and Individual Consult Pending Impleme IDA / 64410 Post Open - National 45,000.00 0.00 2023-05-31 2023-07-19 2023-08-09 2023-09-13 2024-03-11 gé de suivi des activités de r Project Management ant Selection ntation éhabilitation des structures s anitaires dans la province du Kwilu ZR-DRC-MSP-357700-CS-IND V / Recrutement d’un Consult ant Individuel Ingénieur char Capacity Strengthening and Individual Consult Pending Impleme IDA / 64410 Post Open - National 45,000.00 0.00 2023-05-31 2023-07-19 2023-08-09 2023-09-13 2024-03-11 gé de suivi des activités de r Project Management ant Selection ntation éhabilitation des structures s anitaires dans la province du Sud-Kivu Page 11 PROCUREMENT PLAN (Textual Part) Project information: Nigeria Fiscal Governance and Institutions Project (FGIP) P163540 Project Implementation agency: Bureau of Public Procurement Date of the Procurement Plan: September 20, 2019 Period covered by this Procurement Plan: 2019 - 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Public Procurement Act, 2007, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable for those contracts identified in the Procurement Plan tables] Other Relevant Procurement Information. Not Applicable PROCUREMENT Nigeria : Fiscal Governance and Institutions Project PLAN General Information Country: Nigeria 2020-01-09 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163540 GPN Date: Project Name: Fiscal Governance and Institutions Project Loan / Credit No: IDA / 62880 Federal Ministry of of Finance FGIP Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-FMF FGIP-156300-GO-RF Request for Quota Single Stage - One E IDA / 62880 Implementation Support Post Limited 19,934.42 11,956.55 Signed 2020-05-03 2020-05-08 2020-06-28 2020-07-03 2020-12-25 Q / Furnishing of FGIP PCU/PI tions nvelope U Office NG-FMF FGIP-164221-GO-RF Request for Quota Single Stage - One E IDA / 62880 Implementation Support Post Limited 3,934.43 0.00 Canceled 2020-05-26 2020-07-21 2021-01-17 Q / Office Consumables tions nvelope NG-FMF FGIP-164428-GO-RF Request for Quota Q / Office Equipment (Photoc IDA / 62880 Implementation Support Post 23,868.85 0.00 Canceled 2020-05-22 2020-05-22 2020-05-22 tions opier Medium, Laptops, Desk top Computers) NG-FMF FGIP-176154-GO-RF Request for Quota Single Stage - One E IDA / 62880 Implementation Support Post Limited 23,868.85 22,881.50 Signed 2020-06-03 2022-07-22 2020-07-29 2022-09-07 2021-01-25 Q / Office Equipment tions nvelope NG-FMF FGIP-189191-GO-DI IDA / 62880 Implementation Support Post Direct Selection Direct 30,000.00 0.00 Canceled 2021-06-29 2021-07-04 2021-08-08 2022-02-04 R / Accounting Software NG-FMF FGIP-300128-GO-RF Strengthening Controls, Tran Request for Quota Single Stage - One E Q / Procurement of Office Fur IDA / 62880 sparency and Accountability Post Limited 23,758.02 22,037.52 Signed 2022-06-28 2022-07-01 2022-08-23 2022-09-07 2023-02-19 tions nvelope niture to support implementa in the Use of Public Funds tion of FCSSIP NG-FMF FGIP-300135-GO-RF Strengthening Controls, Tran Request for Quota Single Stage - One E Q / Provision of Office Equip IDA / 62880 sparency and Accountability Post Limited 43,006.55 40,284.78 Signed 2022-06-28 2022-07-01 2022-08-23 2022-09-07 2023-02-19 tions nvelope ment (alternative power sup in the Use of Public Funds ply) for OHCSF Strengthening Controls, Tran NG-FMF FGIP-302552-GO-RF Single Stage - One E IDA / 62880 sparency and Accountability Post Request for Bids Open - National 450,243.43 0.00 Signed 2022-07-07 2022-08-18 2022-07-12 2022-08-18 2022-08-23 2022-09-29 2022-09-22 2022-10-27 2022-10-27 2023-04-25 B / Computer and Peripherals nvelope in the Use of Public Funds NG-FMF FGIP-306111-GO-RF Strengthening Controls, Tran Request for Quota Single Stage - One E Q / Production of 2,000 copie IDA / 62880 sparency and Accountability Post Limited 21,000.00 0.00 Signed 2022-08-10 2022-08-19 2022-10-05 2023-04-03 tions nvelope s of FCSSIP Booklets in the Use of Public Funds NG-FMF FGIP-309300-GO-RF Request for Quota Single Stage - One E IDA / 62880 Implementation Support Post Limited 10,000.00 0.00 Canceled 2022-08-23 2022-10-18 2023-04-16 Q / Office Consumable tions nvelope NG-FMF FGIP-368554-GO-RF Request for Quota Single Stage - One E Pending Impl Q / Purchase of Office Consu IDA / 62880 Implementation Support Post Limited 37,500.00 0.00 2023-07-05 2023-08-30 2024-02-26 tions nvelope ementation mables for PCU NG-FMF FGIP-368632-GO-RF Request for Quota Single Stage - One E Pending Impl Q / Purchase of Office Equip IDA / 62880 Implementation Support Post Limited 62,800.00 0.00 2023-07-05 2023-08-30 2024-02-26 tions nvelope ementation ment for PCU and OAGF NG-FMF FGIP-368638-GO-RF Request for Quota Single Stage - One E Pending Impl IDA / 62880 Implementation Support Post Limited 54,500.00 0.00 2023-07-05 2023-08-30 2024-02-26 Q / Office furniture for PCU a tions nvelope ementation nd TSD NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-FMF FGIP-164448-NC-RF Request for Quota Single Stage - One E Q / Printing of Letter Head, Fi IDA / 62880 Implementation Support Post Limited 1,639.34 0.00 Canceled 2020-05-25 2021-03-01 2020-07-20 2021-01-16 tions nvelope le Jackets e.t.c. NG-FMF FGIP-170518-NC-RF Request for Propo Single Stage - Two E P / FGIP Web-site Developme IDA / 62880 Implementation Support Post Limited 8,196.72 0.00 Canceled 2020-09-23 2020-09-28 2020-11-09 2021-02-26 2021-08-25 sals nvelope nt/Maintenance NG-FMF FGIP-244178-NC-RF Request for Quota Single Stage - One E IDA / 62880 Implementation Support Post Limited 25,000.00 24,545.68 Signed 2021-09-04 2021-09-09 2021-10-30 2022-02-11 2022-04-28 Q / Accounting Software tions nvelope CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-FMF FGIP-170050-CS-CQ Consultant Qualifi IDA / 62880 Implementation Support Post Open - National 70,000.00 0.00 Canceled 2020-05-29 2020-06-19 2020-08-02 2020-09-01 2020-10-06 2021-04-04 S / Independent Verification cation Selection Agent (IVA) NG-FMF FGIP-239227-CS-CQ Consultant Qualifi IDA / 62880 Implementation Support Post Limited 30,000.00 0.00 Canceled 2021-06-16 2021-06-29 2021-06-30 2021-07-30 2021-09-03 2022-03-02 S / External Auditor cation Selection NG-FMF FGIP-251503-CS-LC Least Cost Selecti IDA / 62880 Implementation Support Post Open - National 180,000.00 0.00 Canceled 2021-09-21 2021-10-07 2021-10-12 2021-11-25 2021-12-23 2022-01-22 2022-02-26 2022-04-02 2022-09-29 S / Domestic Tax Study on Page 1 NG-FMF FGIP-251506-CS-LC Least Cost Selecti IDA / 62880 Implementation Support Post Open - National 200,000.00 0.00 Canceled 2021-09-21 2021-10-07 2021-10-12 2021-11-25 2021-12-23 2022-01-22 2022-02-26 2022-04-02 2022-09-29 S / International Tax Study on NG-FMF FGIP-251508-CS-LC Least Cost Selecti S / Assessment and Guideline IDA / 62880 Implementation Support Post Open - National 150,000.00 0.00 Canceled 2021-10-05 2021-10-26 2021-12-09 2022-01-06 2022-02-05 2022-03-12 2022-04-16 2022-10-13 on s on Public-Private-Partnershi p NG-FMF FGIP-189194-CS-CQ Consultant Qualifi IDA / 62880 Implementation Support Post Limited 70,000.00 0.00 Canceled 2020-08-21 2021-01-27 2020-09-04 2021-04-21 2020-10-04 2020-11-08 2021-05-07 S / Independent Verification cation Selection Agent (IVA) NG-FMF FGIP-280304-CS-CQ Consultant Qualifi IDA / 62880 Implementation Support Post Open - National 70,000.00 0.00 Signed 2022-03-03 2022-03-03 2022-03-24 2022-04-04 2022-05-07 2022-08-18 2022-06-06 2022-11-10 2022-07-11 2023-01-07 S / Independent Verification cation Selection Agent NG-FMF FGIP-251480-CS-LC Least Cost Selecti S / Training on Understandin IDA / 62880 Implementation Support Post Open - National 60,000.00 0.00 Canceled 2021-09-14 2021-09-28 2021-10-05 2021-11-18 2021-12-16 2022-01-15 2022-02-19 2022-03-26 2022-09-22 on g and Computing Tax Expend iture Analysis NG-FMF FGIP-246348-CS-LC Least Cost Selecti S / Training on Understandin IDA / 62880 Implementation Support Post Open - National 60,000.00 0.00 Canceled 2021-08-16 2021-09-06 2021-10-20 2021-11-17 2021-12-17 2022-01-21 2022-02-25 2022-08-24 on g Tax Expenditure Analysis a nd Reporting NG-FMF FGIP-286069-CS-CQ Strengthening Revenue Man Consultant Qualifi Open - Internationa S / Trade Taxation and Custo IDA / 62880 Post 280,000.00 0.00 Signed 2022-03-29 2022-04-07 2022-04-19 2022-05-19 2022-06-02 2022-09-08 2022-07-02 2022-12-28 2022-08-06 2023-02-02 agement cation Selection l ms Policy Study NG-FMF FGIP-286340-CS-CQ Strengthening Revenue Man Consultant Qualifi Under Implement IDA / 62880 Post Open - National 180,000.00 0.00 2022-03-29 2022-04-07 2022-04-19 2022-05-19 2022-06-02 2022-07-02 2022-08-06 2023-02-02 S / Domestic Tax Study agement cation Selection ation NG-FMF FGIP-293728-CS-CQ Strengthening Revenue Man Consultant Qualifi Open - Internationa Under Implement S / Assessment, Guidelines a IDA / 62880 Post 315,000.00 0.00 2022-06-27 2022-05-20 2022-07-18 2022-07-14 2022-08-31 2022-09-30 2022-09-30 2022-12-22 2022-11-04 2023-05-03 agement cation Selection l ation nd Training on Public Private Partnership NG-FMF FGIP-293733-CS-CQ S / Capacity Building for Tax Strengthening Revenue Man Consultant Qualifi Open - Internationa IDA / 62880 Post 86,000.00 0.00 Signed 2022-06-13 2022-05-20 2022-07-04 2022-07-14 2022-08-17 2022-09-30 2022-09-16 2022-10-31 2022-10-21 2023-04-19 Policy Analysis including Inte agement cation Selection l rnational Tax Cooperation on Transfer Pricing NG-FMF FGIP-293741-CS-CQ Strengthening Revenue Man Consultant Qualifi Open - Internationa IDA / 62880 Post 160,000.00 0.00 Signed 2022-05-11 2022-05-20 2022-06-01 2022-07-14 2022-07-15 2022-10-28 2022-08-14 2022-10-31 2022-09-18 2023-03-17 S / Domestic Tax Training Pa agement cation Selection l ckage NG-FMF FGIP-300141-CS-CQ Consultant Qualifi Open - Internationa S / Audit of Public Private Par IDA / 62880 Implementation Support Post 450,000.00 0.00 Signed 2022-06-28 2022-06-29 2022-07-19 2022-08-09 2022-09-01 2022-09-26 2022-10-01 2022-11-28 2022-11-05 2023-05-04 cation Selection l tnership Concession Contract s NG-FMF FGIP-300154-CS-CQ S / Development of Organizat Consultant Qualifi Open - Internationa Under Implement IDA / 62880 Implementation Support Post 450,000.00 0.00 2022-06-28 2022-09-29 2022-07-19 2022-08-09 2022-09-01 2022-08-31 2022-10-01 2022-11-28 2022-11-05 2023-05-04 ional and Strategic Plan for M cation Selection l ation inistry of Finance Incorporate d NG-FMF FGIP-300320-CS-CQ S / Development of a Frame Consultant Qualifi Open - Internationa IDA / 62880 Implementation Support Post 450,000.00 0.00 Signed 2022-06-30 2022-06-30 2022-07-21 2022-08-09 2022-09-03 2022-09-26 2022-10-03 2022-11-28 2022-11-07 2023-05-06 work for a Modernized Integr cation Selection l ated Public Financial Manage ment Information System NG-FMF FGIP-300340-CS-CQ Consultant Qualifi Open - Internationa Under Implement S / Strategic Plan for the Mini IDA / 62880 Implementation Support Post 350,000.00 0.00 2022-06-30 2022-06-30 2022-07-21 2022-08-09 2022-09-03 2022-09-26 2022-10-03 2022-11-28 2022-11-07 2023-05-06 cation Selection l ation stry of Finance Training Instit ute INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-FMF FGIP-153273-CS-CD S / Preparation of Project Pro IDA / 62880 Implementation Support Prior Direct Selection Direct 39,000.00 45,899.10 Signed 2020-01-09 2020-01-10 2020-01-19 2020-01-14 2020-03-24 2020-01-16 2020-09-20 curement Strategy for Devel opment NG-FMF FGIP-173205-CS-CQ Individual Consult S / Senior Technical Coordina IDA / 62880 Implementation Support Post Limited 50,000.00 38,733.71 Signed 2020-05-29 2020-06-05 2020-06-03 2020-07-20 2020-06-24 2020-10-28 2020-07-29 2021-01-21 2021-01-25 ant Selection ting Consultant NG-FMF FGIP-169189-CS-IND Individual Consult IDA / 62880 Implementation Support Post Open 37,377.05 0.00 Canceled 2020-05-29 2020-07-17 2020-08-07 2020-09-11 2021-03-10 V / Communication Specialist ant Selection NG-FMF FGIP-189199-CS-IND Individual Consult IDA / 62880 Implementation Support Post Limited 50,000.00 0.00 Canceled 2020-08-26 2021-01-26 2020-08-31 2020-09-21 2020-10-26 2021-04-24 V / M & E Specialist ant Selection NG-FMF FGIP-189202-CS-IND Individual Consult IDA / 62880 Implementation Support Post Limited 50,000.00 0.00 Canceled 2020-09-07 2021-01-26 2020-09-12 2020-10-03 2020-11-07 2021-05-06 V / Project Associate ant Selection NG-FMF FGIP-170027-CS-IND Individual Consult IDA / 62880 Implementation Support Post Open 50,000.00 0.00 Canceled 2020-05-29 2020-07-17 2020-08-07 2020-09-11 2021-03-10 V / M & E Specialist ant Selection NG-FMF FGIP-170681-CS-IND Individual Consult IDA / 62880 Implementation Support Post Open 50,000.00 0.00 Canceled 2020-05-29 2020-07-17 2020-08-07 2020-09-11 2021-03-10 V / Project Associate ant Selection NG-FMF FGIP-238345-CS-CD Individual Consult IDA / 62880 Implementation Support Post Direct 95,000.00 88,821.25 Signed 2021-07-30 2021-08-31 2021-08-09 2021-08-11 2021-08-30 2021-08-16 2021-10-04 2021-09-23 2022-04-02 S / Special Assistant to the H ant Selection MFBNP NG-FMF FGIP-238351-CS-CD S / Consultant to Integrated P IDA / 62880 Implementation Support Post Direct Selection Direct 66,600.00 62,043.80 Signed 2021-08-02 2021-08-16 2021-08-12 2021-09-27 2021-10-16 2021-11-14 2022-04-14 ayroll and Personnel Informat ion System HR-OHCSF NG-FMF FGIP-250082-CS-IND Individual Consult V / Preparatory Training of St IDA / 62880 Implementation Support Post Limited 11,800.00 11,678.83 Signed 2021-08-27 2021-08-30 2021-09-01 2021-09-03 2021-09-22 2021-09-29 2021-10-27 2021-10-29 2022-04-25 ant Selection aff on the Excel Software NG-FMF FGIP-270602-CS-CD IDA / 62880 Implementation Support Post Direct Selection Direct 30,000.00 20,030.80 Signed 2021-12-30 2022-01-05 2022-01-09 2022-02-09 2022-03-15 2022-04-17 2022-09-11 S / External Auditor NG-FMF FGIP-306136-CS-IND Strengthening Controls, Tran Individual Consult V / FCSSIP 25 Programme Ma IDA / 62880 sparency and Accountability Post Limited 58,536.59 0.00 Signed 2022-08-01 2022-08-05 2022-08-03 2022-08-19 2022-08-24 2022-09-30 2022-09-28 2023-03-27 ant Selection nagement Consultant in the Use of Public Funds Page 2 NG-FMF FGIP-309272-CS-IND Individual Consult IDA / 62880 Implementation Support Post 8,500.00 0.00 Canceled 2022-08-17 2022-10-05 2022-10-26 2022-11-30 2023-05-29 V / Project Assistant ant Selection NG-FMF FGIP-312592-CS-IND Individual Consult IDA / 62880 Implementation Support Post Limited 12,400.00 0.00 Signed 2022-08-31 2022-09-06 2022-09-05 2022-09-07 2022-09-26 2022-09-21 2022-10-31 2023-04-29 V / Project Assistant ant Selection NG-FMF FGIP-318807-CS-IND Strengthening Controls, Tran V / Consultant to support inst Individual Consult IDA / 62880 sparency and Accountability Post Limited 48,000.00 0.00 Canceled 2022-10-06 2022-10-12 2022-10-11 2022-11-01 2022-12-06 2023-06-04 itutionalization of Performanc ant Selection in the Use of Public Funds e Management System in the Public Service NG-FMF FGIP-318816-CS-IND V / Consultant to support Perf Strengthening Controls, Tran Individual Consult ormance Management Syste IDA / 62880 sparency and Accountability Post Limited 36,000.00 0.00 Canceled 2022-10-06 2022-10-12 2022-10-11 2022-11-01 2022-12-06 2023-06-04 ant Selection m hand holding exercises for in the Use of Public Funds MDAs in the Social Services s ector NG-FMF FGIP-318823-CS-IND V / Consultant to support Perf Strengthening Controls, Tran Individual Consult ormance Management Syste IDA / 62880 sparency and Accountability Post Limited 36,000.00 0.00 Canceled 2022-10-06 2022-10-12 2022-10-11 2022-11-01 2022-12-06 2023-06-04 ant Selection m hand holding exercise for in the Use of Public Funds MDAs in the Economy Sector NG-FMF FGIP-319217-CS-IND V / Consultant to support Perf Strengthening Controls, Tran Individual Consult ormance Management Syste IDA / 62880 sparency and Accountability Post Limited 36,000.00 0.00 Canceled 2022-10-06 2022-10-12 2022-10-11 2022-11-01 2022-12-06 2023-06-04 ant Selection m hand holding exercises for in the Use of Public Funds MDAs in the Infrastructure se ctor NG-FMF FGIP-319224-CS-IND V / Consultant to support Perf Strengthening Controls, Tran Individual Consult ormance Management Syste IDA / 62880 sparency and Accountability Post Limited 36,000.00 0.00 Canceled 2022-10-06 2022-10-12 2022-10-11 2022-11-01 2022-12-06 2023-06-04 ant Selection m hand holding exercises for in the Use of Public Funds MDAs in the Administrative a nd Governance sector NG-FMF FGIP-349970-CS-IND Strengthening Revenue Man Individual Consult Under Implement V / Appointment of Consultan IDA / 62880 Post Limited 10,975.61 0.00 2023-03-24 2023-03-17 2023-03-29 2023-04-19 2023-05-24 2023-08-24 agement ant Selection ation t for Production of Training M aterials NG-FMF FGIP-350591-CS-IND Strengthening Controls, Tran Individual Consult Open - Internationa Under Implement V / Appointment of Consultan IDA / 62880 sparency and Accountability Post 41,000.00 0.00 2023-03-31 2023-03-28 2023-05-19 2023-06-09 2023-07-14 2023-09-14 ant Selection l ation t on GIFMIS Security Enhance in the Use of Public Funds ment NG-FMF FGIP-361310-CS-IND V / Consultant to support Perf Strengthening Controls, Tran Individual Consult Under Implement ormance Management Syste IDA / 62880 sparency and Accountability Post Limited 36,000.00 0.00 2023-05-11 2023-06-15 2023-05-16 2023-06-06 2023-07-11 2024-01-07 ant Selection ation m hand holding exercises for in the Use of Public Funds MDAs in the Infrastructure se ctor. NG-FMF FGIP-363683-CS-IND V / Consultant to support Perf Strengthening Controls, Tran Individual Consult Under Implement ormance Management Syste IDA / 62880 sparency and Accountability Post Limited 36,000.00 0.00 2023-05-30 2023-06-15 2023-06-04 2023-06-25 2023-07-30 2024-01-26 ant Selection ation m hand holding exercises for in the Use of Public Funds MDAs in the Administrative a nd Governance sector NG-FMF FGIP-363686-CS-IND Strengthening Controls, Tran V / Consultant to support inst Individual Consult Under Implement IDA / 62880 sparency and Accountability Post Limited 48,000.00 0.00 2023-05-30 2023-06-15 2023-06-04 2023-06-25 2023-07-30 2024-01-26 itutionalization of Performanc ant Selection ation in the Use of Public Funds e Management System in the Public Service NG-FMF FGIP-363687-CS-IND V / Consultant to support Perf Strengthening Controls, Tran Individual Consult Under Implement ormance Management Syste IDA / 62880 sparency and Accountability Post Limited 36,000.00 0.00 2023-05-30 2023-06-15 2023-06-04 2023-06-25 2023-07-30 2024-01-26 ant Selection ation m hand holding exercise for in the Use of Public Funds MDAs in the Economy Sector NG-FMF FGIP-363690-CS-IND V / Consultant to support Perf Strengthening Controls, Tran Individual Consult Under Implement ormance Management Syste IDA / 62880 sparency and Accountability Post Limited 36,000.00 0.00 2023-05-30 2023-06-15 2023-06-04 2023-06-25 2023-07-30 2024-01-26 ant Selection ation m hand holding exercises for in the Use of Public Funds MDAs in the Social Services s ector NG-FMF FGIP-367239-CS-CD Under Implement IDA / 62880 Implementation Support Post Direct Selection Direct - National 43,917.62 0.00 2023-06-20 2023-06-19 2023-06-30 2023-08-15 2023-12-20 S / Engagement of External A ation uditor Page 3 PLAN DE PASSATION DE MARCHÉS Projet : Projet pour promouvoir l’offre de logements abordables dans l’espace UEMOA - assistance technique pour soutenir les politique d’offre de logements - Composante 3 Agence d’exécution du Projet : Commission de l’UEMOA Date du plan de passation des marchés : 15 Mars 2018 Période couverte par ce plan de passation des marchés : 2018-2019 Preambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016) (“Règlement de Passation des Marchés”) l’Emprunteur utilise les outils électroniques de planification et de suivi de la passation des marchés (STEP) pour préparer, valider et actualiser ses plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Cette partie textuelle ainsi que les tableaux du plan de passation des marchés dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types d’appel d’offres publiés par la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale ainsi que pour tous les autres contrats spécifiés dans les tableaux du plan de passation des marchés inclus dans STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, au cas où la procédure de passation des marchés est retenue (telle que spécifiée dans les tableaux du plan de passation des marchés inclus dans STEP), les procédures de passation de marchés du pays considéré peuvent être appliquées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans le code des marchés publics (règlement d’exécution N° 008/2014/ COM/UEMOA relatif aux règles de passation, d’exécution et de réception des marchés des organes de l’UEMOA), ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés. Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués dans le Plan de passation des marchés. « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas Travaux : ne s’applique pas Autres informations pertinentes sur la passation des marchés « Sans objet ». PROCUREMENT Western and Central Africa : WAEMU Affordable Housing Finance PLAN General Information Country: Western and Central Africa 2018-05-27 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161658 GPN Date: 2018-03-13 Project Name: WAEMU Affordable Housing Finance Loan / Credit No: IDA / D2360 Caisse Regionale de Refinancement Hypothecaire Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-CRRH-214356-GO-RFQ / Technical Assistance for Non ACQUISITION DE MATERIEL E Request for Quota Single Stage - One E IDA / D2360 -Bank Financial Institutions a Post Limited 80,000.00 0.00 Canceled 2021-02-08 2021-04-12 2021-06-11 T AMENAGEMENT D’UNE SAL tions nvelope nd CRRH LE INFORMATIQUE POUR LA CRRH-UEMOA TG-CRRH-214356-GO-RFQ-2 / Acquisition de matériels inf Technical Assistance for Non Request for Quota Single Stage - One E ormatiques, d'un robot de sa IDA / D2360 -Bank Financial Institutions a Post Limited 77,000.00 109,627.91 Signed 2022-03-25 2022-04-14 2022-05-20 2022-06-14 2022-07-19 tions nvelope uvegarde plus les accessoire nd CRRH s (y compris les services aprè s-vente) TG-CRRH-283645-GO-RFQ / Technical Assistance for Non Fourniture et installation de Request for Quota Single Stage - One E IDA / D2360 -Bank Financial Institutions a Post Limited 20,000.00 0.00 Canceled 2022-03-25 2022-05-20 2022-07-19 Caméra de vidéosurveillance tions nvelope nd CRRH et contrôle d’accès par badg e et empreinte digitale TG-CRRH-283643-GO-RFQ / Aménagement de la salle inf Technical Assistance for Non ormatique de la CRRH-UEMO Request for Quota Single Stage - One E Under Imple IDA / D2360 -Bank Financial Institutions a Post Limited 50,000.00 0.00 2022-03-25 2022-03-16 2022-05-20 2022-07-19 A : achat et installation de cli tions nvelope mentation nd CRRH matiseurs, porte coupe-feu, f aux plancher, extincteur, gr oupe électrogène et onduleu r TG-CRRH-362764-GO-RFQ / FOURNITURE ET INSTALLATIO Technical Assistance for Non Request for Quota Single Stage - One E Under Imple N D’UN SYSTEME DE CONTR IDA / D2360 -Bank Financial Institutions a Post Open - National 27,000.00 0.00 2023-05-30 2023-07-25 2023-08-24 tions nvelope mentation ÔLE D’ACCES ET DE VIDEOSU nd CRRH RVEILLANCE A LA CRRH-UEM OA NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-CRRH-63754-NC-DIR / Un e Agence conseil en commun Participating Banks Mortgag Request for Quota Single Stage - One E IDA / D2360 Post Limited 58,613.00 39,209.04 Completed 2018-08-25 2018-06-04 2018-10-20 2018-07-03 2019-04-18 2018-09-26 ication pour la préparation d e Refinancing tions nvelope u lancement du projet Banqu e mondiale/UEMOA TG-CRRH-58272-NC-DIR / 1 s oftware pour adapter le syste me comptable IBIS aux nouv Participating Banks Mortgag IDA / D2360 Post Direct Selection Direct 81,500.00 77,688.07 Completed 2018-06-24 2018-06-24 2018-06-29 2018-07-10 2018-08-03 2018-10-30 2019-01-30 2018-11-09 elles réformes BCEAO (Bâle 2 e Refinancing /3 et PCB révisé) et à la gesti on du projet Banque mondial e/UEMOA TG-CRRH-116117-NC-DIR / R Affordable Housing Policies T éalisation d'une Vidéo utilisat IDA / D2360 Post Direct Selection Direct 11,000.00 8,862.78 Completed 2019-05-23 2019-05-24 2019-05-28 2019-05-27 2019-07-02 2019-06-03 2019-12-29 2019-12-09 echnical Assistance eurs pour la CRRH-UEMOA TG-CRRH-127286-NC-DIR / O RGANISATION DE LA CONFER Affordable Housing Policies T ENCE CRRH-UEMOA/BANQUE IDA / D2360 Post Direct Selection Direct 6,000.00 5,888.23 Completed 2019-08-23 2019-08-27 2019-08-23 2019-08-30 2019-09-20 2019-09-02 2020-03-18 2019-10-11 echnical Assistance MONDIALE SUR LES POLITIQU ES DE L’HABITAT ET LA CROI SSANCE ECONOMIQUE TG-CRRH-241473-NC-DIR / O RGANISATION DE LA CAMPAG NE DE PROMOTION DU REFIN ANCEMENT DES SFD, AVEC L Affordable Housing Policies T IDA / D2360 Post Direct Selection Direct 40,000.00 37,518.62 Completed 2021-07-12 2021-06-23 2021-07-12 2021-06-25 2021-07-20 2021-07-03 2022-01-16 2022-01-13 A PREMIERE SIGNATURE D’U echnical Assistance N CONTRAT DE REFINANCEM ENT AVEC UN SFD AU SENEG AL ET LA RENCONTRE AVEC L ES SFD DU SENEGAL TG-CRRH-333807-NC-RFQ / I Technical Assistance for Non MPLEMENTATION ET SECURIS Request for Quota Single Stage - One E IDA / D2360 -Bank Financial Institutions a Post Limited 40,000.00 0.00 Signed 2023-01-07 2023-01-09 2023-01-27 2023-02-26 ATION D’UNE NOUVELLE ARC tions nvelope nd CRRH HITECTURE RESEAU POUR LA CRRH-UEMOA TG-CRRH-364709-NC-RFQ / Technical Assistance for Non PRESTATION DE MAINTENAN Request for Quota Single Stage - One E Pending Impl IDA / D2360 -Bank Financial Institutions a Post Open - National 37,000.00 0.00 2023-06-17 2023-07-29 2023-12-08 CE DU PARC INFORMATIQUE tions nvelope ementation nd CRRH ET SUIVI DU SYSTEME RESEA U DE LA CRRH-UEMOA CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 TG-CRRH-58265-CS-QCBS / 1 firme de consultant pour fa ire l'état des lieux du finance ment du logement par les SF Participating Banks Mortgag Quality And Cost- Open - Internationa D, identifier des SFD éligibles IDA / D2360 Post 400,000.00 89,738.00 Completed 2018-06-28 2018-08-12 2018-07-19 2018-08-24 2018-09-01 2018-11-20 2018-09-29 2019-01-08 2018-10-29 2019-03-13 2018-12-03 2019-06-14 2019-01-07 2019-07-18 2020-01-07 2020-04-14 e Refinancing Based Selection l , et structurer la fenêtre d'ac cès au refinancement des SF D - critères, conditions d'éligi bilité, coût ... + rédiger tous les documents TG-CRRH-58292-CS-CQS / 1 bureau d'études pour conduir Participating Banks Mortgag Quality And Cost- Open - Internationa e des ateliers sur le risque en IDA / D2360 Post 200,000.00 157,289.16 Completed 2018-06-26 2018-08-03 2018-07-17 2018-09-04 2018-08-30 2018-11-20 2018-09-27 2019-01-03 2018-10-27 2019-02-06 2018-12-01 2019-03-06 2019-01-05 2019-04-15 2020-01-05 2021-05-04 e Refinancing Based Selection l vironnemental et social et for mer les institutions financier es sur ce risque TG-CRRH-58348-CS-CQS / 1 firme de consultants pour 1.E valuer la faisabilité d'un prod Technical Assistance for Non uit de garantie régional et fai Quality And Cost- Open - Internationa IDA / D2360 -Bank Financial Institutions a Post 400,000.00 416,976.50 Completed 2018-06-25 2019-03-05 2018-07-16 2019-03-11 2018-08-29 2019-05-23 2018-09-26 2019-06-24 2018-10-26 2019-08-08 2018-11-30 2019-12-23 2019-01-04 2020-03-27 2020-01-04 2021-09-10 re des propositions d'options Based Selection l nd CRRH 2.rédiger la structure, gouver nance et pricing de ce produi t et le plan d'affaires après u n atelier afin de choisir la me illeure opt TG-CRRH-73025-CS-QCBS / Technical Assistance for Non Assistant à Maîtrise d'ouvrag Quality And Cost- Open - Internationa IDA / D2360 -Bank Financial Institutions a Post 58,500.00 175,049.81 Signed 2018-08-07 2018-08-03 2018-08-28 2018-09-03 2018-10-11 2018-11-20 2018-11-08 2019-01-03 2018-12-08 2019-01-14 2019-01-12 2019-01-31 2019-02-16 2019-04-08 2020-02-16 e (AMOA) pour la nouvelle ap Based Selection l nd CRRH plication de gestion des refin ancements TG-CRRH-102015-CS-QCBS / Technical Assistance for Non Quality And Cost- Open - Internationa Etude d'impact sur les financ IDA / D2360 -Bank Financial Institutions a Post 200,000.00 246,415.83 Completed 2019-04-01 2019-04-02 2019-04-22 2019-04-04 2019-06-05 2019-07-15 2019-07-03 2019-08-26 2019-08-02 2019-09-06 2019-09-06 2020-02-21 2019-10-11 2020-03-19 2020-10-10 2021-02-25 Based Selection l ements sur ressources de ma nd CRRH rché TG-CRRH-102022-CS-QCBS / Technical Assistance for Non Quality And Cost- Open - Internationa IDA / D2360 Post 150,000.00 233,740.50 Signed 2019-03-15 2019-05-23 2019-04-05 2019-07-08 2019-05-19 2019-09-09 2019-06-16 2019-10-09 2019-07-16 2020-01-23 2019-08-20 2020-03-11 2019-09-24 2020-05-13 2020-09-23 Etude sur le crédit-bail immo -Bank Financial Institutions a Based Selection l bilier nd CRRH TG-CRRH-101905-CS-CQS / 1 firme de consultant pour acc Technical Assistance for Non ompagner les SFD presenties Consultant Qualifi Open - Internationa IDA / D2360 -Bank Financial Institutions a Post 225,000.00 0.00 Canceled 2019-04-30 2019-05-21 2019-07-04 2019-08-03 2019-09-07 2020-03-05 pour accéder à la fenetre de cation Selection l nd CRRH refinancement et respecter l es conditions d'éligiblité, not amment prudentielle TG-CRRH-101908-CS-QCBS / 1 firme de consultant pour ac compagner les SFD a dévelo Technical Assistance for Non Quality And Cost- Open - Internationa pper des méthodes de crédit IDA / D2360 -Bank Financial Institutions a Post 228,000.00 0.00 Canceled 2019-04-30 2019-05-21 2019-07-04 2019-08-01 2019-08-31 2019-10-05 2019-11-09 2020-11-08 Based Selection l pour le secteur informel (not nd CRRH amment numériques) , et ren forcer leur capacité de gestio n du risque TG-CRRH-101909-CS-QCBS / Une firme de consultant pour accompagner la mise en plac Design of Regional Guarante Quality And Cost- Open - Internationa e du produit de garantie : arr IDA / D2360 Post 400,000.00 0.00 Canceled 2019-04-15 2019-05-06 2019-06-19 2019-07-17 2019-08-16 2019-09-20 2019-10-25 2020-10-24 e Product for Housing Loans Based Selection l angements contractuels, règl es et procédures, sensibilisat ion et renforcement des capa cités des bénéficiaires TG-CRRH-72930-CS-QCBS / Technical Assistance for Non Quality And Cost- Open - Internationa Un software pour la gestion d IDA / D2360 -Bank Financial Institutions a Post 200,000.00 0.00 Canceled 2018-08-22 2018-08-02 2018-09-12 2018-09-03 2018-10-26 2018-11-20 2018-11-23 2019-01-03 2018-12-23 2019-06-04 2019-01-27 2019-03-03 2020-03-02 Based Selection l es refinancements des banqu nd CRRH es et des SFD TG-CRRH-102031-CS-CQS / Technical Assistance for Non Accompagnement CRRH-UEM Consultant Qualifi Open - Internationa IDA / D2360 -Bank Financial Institutions a Post 60,000.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-05 2019-08-09 2020-02-05 OA vers une notation financi cation Selection l nd CRRH ère internationale TG-CRRH-102020-CS-QCBS / Technical Assistance for Non Quality And Cost- Open - Internationa Etude d'impact sur les financ IDA / D2360 -Bank Financial Institutions a Post 200,000.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-10-10 Based Selection l ements sur ressources conce nd CRRH ssionnelles TG-CRRH-72930-CS-QCBS-2 Technical Assistance for Non / MISE EN PLACE D'UNE APPLI Quality And Cost- Open - Internationa IDA / D2360 -Bank Financial Institutions a Post 450,000.00 484,946.91 Signed 2019-12-18 2019-12-17 2020-01-08 2019-12-23 2020-02-21 2020-03-06 2020-03-20 2020-04-10 2020-04-19 2020-05-12 2020-05-24 2020-05-25 2020-06-28 2020-09-01 2020-12-25 CATION DE GESTION DES RE Based Selection l nd CRRH FINANCEMENTS DES BANQUE S ET SFD TG-CRRH-181721-CS-CQS / RECRUTEMENT D’UN CABINE Technical Assistance for Non T CONSEIL POUR LE DIAGNO Consultant Qualifi IDA / D2360 -Bank Financial Institutions a Post Limited 200,000.00 125,920.35 Signed 2020-07-21 2020-07-22 2020-07-28 2020-08-21 2020-08-04 2020-12-04 2020-08-18 2020-12-15 2021-08-18 STIC DES BESOINS D’ASSIST cation Selection nd CRRH ANCE TECHNIQUE AUX SFD R EFINANCES PAR LA CRRH-UE MOA TG-CRRH-254898-CS-CQS / UN SWAP ADVISOR POUR LA MISE EN PLACE D’UN SWAP D Affordable Housing Policies T Consultant Qualifi OLLAR/EURO DANS LE CADR IDA / D2360 Post Limited 120,000.00 39,469.50 Completed 2021-09-27 2021-09-23 2021-10-11 2021-10-13 2021-10-25 2021-10-15 2021-11-15 2021-10-19 2022-03-15 2022-04-26 echnical Assistance cation Selection E DE L’OPERATION D’EMISSI ON OBLIGATAIRE DE LA CRR H-UEMOA SUR LE MARCHE FI NANCIER AMERICAIN TG-CRRH-263296-CS-CQS / F ORMATION DU PERSONNEL D Affordable Housing Policies T Consultant Qualifi E LA CRHH-UEMOA SUR LA G IDA / D2360 Post Limited 30,000.00 0.00 Canceled 2021-11-18 2021-12-10 2021-12-02 2022-01-01 2022-02-05 2022-08-04 echnical Assistance cation Selection ESTION DU SWAP DE COUVE RTURE DE RISQUE DE CHANG E TG-CRRH-101905-CS-CQS-2 / UN CABINET CONSEIL POUR LE DIAGNOSTIC DES BESOIN Technical Assistance for Non Consultant Qualifi Open - Internationa S EN ASSISTANCE TECHNIQU IDA / D2360 -Bank Financial Institutions a Post 290,000.00 0.00 Signed 2021-11-22 2021-11-25 2022-01-10 2021-11-26 2022-03-11 2022-05-23 2022-04-01 2022-09-12 2022-05-13 2023-05-08 cation Selection l E DES SFD ET DES BANQUES nd CRRH ACTIONNAIRES REFINANCEES DE LA CRRH-UEMOA ET POUR LEUR ACCOMPAGNEMENT TG-CRRH-271802-CS-CQS / RECRUTEMENT D’UN CONSU Affordable Housing Policies T Consultant Qualifi LTANT POUR L’EVALUATION IDA / D2360 Post Limited 100,000.00 87,531.40 Signed 2022-01-11 2022-01-18 2022-01-21 2022-04-14 2022-02-05 2022-05-20 2022-02-15 2022-07-08 2022-05-16 echnical Assistance cation Selection DES NORMES PRUDENTIELLE S APPLICABLES A LA CRRH-U EMOA Page 2 TG-CRRH-352156-CS-CQS / UN CONSULTANT (AMOA) PO UR ASSISTER LA CRRH-UEMO A DANS LA REDACTION DES Technical Assistance for Non TERMES DE REFERENCE POU Consultant Qualifi IDA / D2360 -Bank Financial Institutions a Post Limited 90,000.00 0.00 Canceled 2023-04-24 2023-05-08 2023-05-22 2023-05-27 2023-06-26 R LES PRESTATIONS DE SERV cation Selection nd CRRH ICES INFORMATIQUES ET L’EL ABORATION DES SPECIFICATI ONS TECHNIQUES POUR LES ACQUISITIONS DE MATERIELS ET LOGICIELS INFORMATIQUE S TG-CRRH-363684-CS-CQS / UN CONSULTANT (AMOA) PO UR ASSISTER LA CRRH-UEMO A DANS LA REDACTION DES Technical Assistance for Non TERMES DE REFERENCE POU Consultant Qualifi Open - Internationa Under Implement IDA / D2360 -Bank Financial Institutions a Post 90,000.00 0.00 2023-06-07 2023-06-07 2023-06-22 2023-06-08 2023-07-13 2023-07-20 2023-07-30 2023-09-13 R LES PRESTATIONS DE SERV cation Selection l ation nd CRRH ICES INFORMATIQUES ET L’EL ABORATION DES SPECIFICATI ONS TECHNIQUES POUR LES ACQUISITIONS DE MATERIELS ET LOGICIELS INFORMATIQUE S TG-CRRH-364705-CS-CQS / Technical Assistance for Non UN CONSULTANT POUR LA C Consultant Qualifi Under Implement IDA / D2360 -Bank Financial Institutions a Post Open - National 40,000.00 0.00 2023-06-12 2023-06-01 2023-06-27 2023-07-18 2023-07-25 2023-08-04 2023-10-03 ONCEPTION ET LA MISE EN LI cation Selection ation nd CRRH GNE DU SITE WEB DE LA CRR H-UEMOA INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-CRRH-58281-CS-CQS / 1 consultant pour mettre en pl Participating Banks Mortgag Individual Consult ace la fenêtre SFD, former le IDA / D2360 Prior Open 250,000.00 76,164.00 Signed 2018-06-21 2018-08-13 2018-08-09 2018-11-30 2018-08-30 2019-02-18 2018-10-04 2019-03-08 2019-04-02 e Refinancing ant Selection personnel gérant la ligne et s uperviser son évolution TG-CRRH-58357-CS-INDV / U Technical Assistance for Non Individual Consult n consultant pour la passatio IDA / D2360 -Bank Financial Institutions a Post Open 25,000.00 58,893.42 Signed 2018-06-27 2018-06-29 2018-08-15 2018-09-04 2018-09-05 2018-10-30 2018-10-10 2018-11-19 2019-04-08 ant Selection n des marches et la gestion d nd CRRH u projet (1 an). TG-CRRH-101911-CS-INDV / Un consultant pour le renforc Design of Regional Guarante Individual Consult ement des capacités de la C IDA / D2360 Prior Open 300,000.00 0.00 Canceled 2019-04-15 2019-06-03 2019-06-24 2019-07-29 2020-01-25 e Product for Housing Loans ant Selection RRH-UEMOA pour la gestion du produit relatif au fonds de garantie et de la ligne SFD TG-CRRH-129521-CS-INDV / Recrutement d'un Juriste spé Participating Banks Mortgag Individual Consult IDA / D2360 Post Limited 25,000.00 54,012.50 Completed 2019-09-04 2019-09-04 2019-09-09 2020-01-20 2019-09-19 2020-03-04 2019-09-27 2020-03-06 2019-11-26 2020-12-10 cialiste des systèmes financi e Refinancing ant Selection ers décentralisés (SFD) TG-CRRH-139861-CS-CDS / Accompagnement de la CRR H-UEMOA vers une notation f Technical Assistance for Non inancière internationale : IDA / D2360 -Bank Financial Institutions a Post Direct Selection Direct 120,000.00 0.00 Canceled 2019-10-28 2019-10-24 2019-11-06 2019-11-13 2019-12-18 2020-04-16 - Lot 1 : sélection de l'agenc nd CRRH e Fitch - Lot 2 : sélection de l'agenc e Moody's TG-CRRH-162377-CS-INDV / RECRUTEMENT D’UN CONSU Technical Assistance for Non Individual Consult LTANT ANALYSTE FINANCIER IDA / D2360 -Bank Financial Institutions a Post Limited 54,000.00 76,740.93 Completed 2020-03-02 2020-03-03 2020-03-07 2020-03-06 2020-03-17 2020-03-16 2020-04-01 2020-03-18 2020-06-30 2020-12-10 ant Selection SENIOR SPECIALISTE DES SY nd CRRH STEMES FINANCIERS DECENT RALISES (SFD) TG-CRRH-171696-CS-INDV / CONSULTANT POUR L’ASSIST ANCE DES BANQUES REFINA Technical Assistance for Non Individual Consult NCEES DANS LA MISE EN PLA IDA / D2360 -Bank Financial Institutions a Post Limited 30,000.00 168,874.33 Signed 2020-05-07 2020-05-07 2020-05-12 2020-06-24 2020-05-27 2020-08-24 2020-06-08 2020-09-13 2020-09-06 ant Selection CE D’UN SYSTEME DE GESTI nd CRRH ON DU RISQUE ENVIRONNEM ENTAL ET SOCIAL SPECIFIQU E AUX PRETS A L’HABITAT TG-CRRH-220474-CS-INDV / RECRUTEMENT D'UN SECON D CONSULTANT POUR L'ASSI Technical Assistance for Non STANCE DES BANQUES ET SF IDA / D2360 -Bank Financial Institutions a Post Direct Selection Direct 65,000.00 105,872.94 Signed 2021-03-01 2021-03-05 2021-03-11 2021-04-07 2021-05-15 2021-07-11 2022-05-15 D REFINACES DANS LA MISE nd CRRH EN PLACE D'UN SYSTEME DE GESTION DU RISQUE ENVIRO NNEMENATL ET SOCIAL SPEC IFIQUE AUX PRETS A L'HABIT AT TG-CRRH-254889-NC-DIR / D éveloppement d’un module i nterface entre la nouvelle ap Affordable Housing Policies T IDA / D2360 Post Direct Selection Direct 45,000.00 37,843.87 Completed 2021-09-27 2021-09-09 2021-10-02 2021-09-14 2021-10-17 2021-10-06 2021-12-16 2022-03-24 plication de gestion des refin echnical Assistance ancements et l’application co mptable IBIS de la CRRH-UE MOA TG-CRRH-272750-CS-CDS / S ELECTION D'UN CONSULTAN T POUR LA REALISATION DE L Affordable Housing Policies T IDA / D2360 Post Direct Selection Direct 260,000.00 236,585.84 Signed 2022-01-14 2022-01-18 2022-01-17 2022-01-19 2022-01-25 2022-02-09 2022-01-28 ’ETUDE D’IMPACT DES REFIN echnical Assistance ANCEMENTS DE LA CRRH-UE MOA SUR LES RESSOURCES CONCESSIONNELLES TG-CRRH-316608-CS-CDS / Technical Assistance for Non REVUE DES ETATS FINANCIE IDA / D2360 -Bank Financial Institutions a Post Direct Selection Direct - National 50,000.00 0.00 Signed 2022-09-16 2022-08-31 2022-09-26 2022-08-31 2022-10-29 2022-11-28 RS 2019, 2020 et 2021 DE LA nd CRRH CRRH-UEMOA ETABLIS SELO N LES NORMES IFRS TG-CRRH-319061-CS-CDS / S ELECTION D’UN CABINET PO Technical Assistance for Non UR LA FORMATION DES BAN Direct - Internation Under Implement IDA / D2360 -Bank Financial Institutions a Post Direct Selection 25,000.00 0.00 2022-09-30 2022-10-11 2022-10-10 2022-10-12 2022-11-12 2022-12-12 QUES ET SFD DE LA CRRH-UE al ation nd CRRH MOA SUR LA NOUVELLE APPL ICATION DE GESTION DES RE FINANCEMENTS CARTHAGO Page 3 TG-CRRH-359247-CS-CDS / E TUDE DE FAISABILITE POUR L A MISE EN PLACE D’UNE SOL Affordable Housing Policies T Direct - Internation Under Implement UTION DE GARANTIE FNANCI IDA / D2360 Post Direct Selection 200,000.00 0.00 2023-05-15 2023-05-18 2023-05-30 2023-11-01 echnical Assistance al ation ERE DE PRETS AU LOGEMENT EN APPUI AUX INSTITUTIONS FINANCIERES DANS LA ZONE UEMOA TG-CRRH-362753-CS-CDS / UNE FIRME POUR LE DEVELO Technical Assistance for Non PPEMENT ET L’INSTALLATION Direct - Internation IDA / D2360 -Bank Financial Institutions a Post Direct Selection 395,000.00 0.00 Under Review 2023-05-29 2023-06-01 2023-06-13 2023-09-11 D’UNE APPLICATION CARTHA al nd CRRH GO MOYENS GENERAUX ET C OMPTABILITE GENERALE A LA CRRH-UEMOA Page 4 PROCUREMENT PLAN (Textual Part) Project information: Land Registration and Property Valuation Project (P161238) Project Implementation agency: Public Services Agency, Moldova Date of the Procurement Plan: February 4, 2019 Applicable Regulations: World Bank Procurement Regulations for IPF Borrowers, dated July 2016, revised November 2017 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Law No 131 dated July 3, 2015 as further amended, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables – Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables - Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works) - Not Applicable PROCUREMENT Moldova : Land Registration and Property Valuation Project PLAN General Information Country: Moldova 2019-02-04 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161238 GPN Date: 2019-06-28 Project Name: Land Registration and Property Valuation Project Loan / Credit No: IDA / 63060 Public Services Agency Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MD-PSA-122742-GO-RFQ / S Land Administration System Request for Quota Single Stage - One E oftware licenses for valuation IDA / 63060 Post Open - National 4,500.66 Completed 2019-09-07 2019-08-30 2019-11-02 2020-01-24 2021-11-02 2020-02-13 Strengthening tions nvelope (SPSS license) MD-PSA-215894-GO-RFQ / Pr Request for Quota Single Stage - One E Pending Impl ocurement of special paper f IDA / 63060 First Property Registration Post Open - National 0.00 2021-02-05 2021-03-26 2021-09-22 tions nvelope ementation or printing property title certi ficates MD-PSA-210221-GO-RFQ / IT Land Administration System Request for Quota Single Stage - One E Pending Impl equipment for PIU and data c IDA / 63060 Post Open - National 0.00 2020-12-26 2021-04-02 2021-09-29 Strengthening tions nvelope ementation ollection consultants MD-PSA-226578-GO-RFB / IC Land Administration System Single Stage - One E Pending Impl IDA / 63060 Post Request for Bids Open - National 0.00 2021-04-09 2021-04-14 2021-05-26 2021-06-25 2021-07-30 2022-01-26 T Equipment for Piloting Mold Strengthening nvelope ementation lis MD-PSA-242290-GO-RFB / In ternational Consultant Comp Land Administration System Open - Internationa Single Stage - One E Under Imple IDA / 63060 Post Request for Bids 0.00 2021-07-08 2021-08-03 2021-07-13 2021-08-13 2021-08-24 2021-09-23 2021-10-28 2022-04-26 any for developing of Nationa Strengthening l nvelope mentation l Spatial Data Infrastructure Geoportal MD-PSA-249287-GO-RFQ / 2 Land Administration System Request for Quota Single Stage - One E IDA / 63060 Post Open - National 1,401.10 Signed 2021-08-31 2021-10-26 2021-11-06 2022-04-24 Printers for Barcode Labels Strengthening tions nvelope MD-PSA-264812-GO-RFQ / L Request for Quota Single Stage - One E Pending Impl AYOUT AND PRINTING OF TH IDA / 63060 First Property Registration Post Open - National 0.00 2021-12-03 2022-01-28 2022-07-27 tions nvelope ementation E PROMOTIONAL MATERIALS MD-PSA-278879-GO-RFQ / T Land Administration System Request for Quota Single Stage - One E Under Imple he improvement of the Natio IDA / 63060 Post Open - National 0.00 2022-02-18 2022-04-15 2022-10-12 Strengthening tions nvelope mentation nal Positioning System MOLD POS MD-PSA-287190-GO-RFQ / E Request for Quota Single Stage - One E IDA / 63060 First Property Registration Post Open - National 0.00 Signed 2022-04-05 2022-05-31 2022-11-27 quipment for Surveyors tions nvelope MD-PSA-290316-GO-RFQ / IT Land Administration System Request for Quota Single Stage - One E equipment and other periphe IDA / 63060 Post Open - National 0.00 Signed 2022-04-22 2022-06-17 2022-12-14 Strengthening tions nvelope rals for PIU and data collectio n consultants. MD-PSA-290324-GO-RFB / IC Land Administration System Single Stage - One E T Equipment ( 150 PC's for M IDA / 63060 Post Request for Bids Open - National 0.00 Signed 2022-04-22 2022-04-22 2022-04-27 2022-06-08 2022-06-15 2022-07-08 2022-10-24 2022-08-12 2023-02-08 Strengthening nvelope oldlis System) MD-PSA-299898-GO-RFQ / Of Capacity Building and Projec Request for Quota Single Stage - One E IDA / 63060 Post Open - National 0.00 Canceled 2022-06-22 2022-08-17 2023-02-13 fice furniture for PIU office. t Management tions nvelope MD-PSA-320524-GO-RFQ / B Land Administration System Request for Quota Single Stage - One E IDA / 63060 Post Open - National 0.00 Signed 2022-10-14 2022-12-09 2023-01-31 arcode labels (400.000 piece Strengthening tions nvelope s) MD-PSA-324845-GO-RFQ / L Request for Quota Single Stage - One E AYOUT AND PRINTING OF AW IDA / 63060 First Property Registration Post Open - National 0.00 Signed 2022-11-04 2022-12-30 2023-03-30 tions nvelope ARNESS&VISIBILITY MATERIA LS MD-PSA-346761-GO-RFB / In ternational Company for Sup ply and Installation of the Sta Land Administration System Open - Internationa Single Stage - One E Under Imple IDA / 63060 Post Request for Bids 0.00 2023-03-03 2023-03-03 2023-03-10 2023-03-03 2023-04-21 2023-05-23 2023-05-21 2023-06-30 2024-06-30 te Register of Objects of Tech Strengthening l nvelope mentation nical-Constructions Infrastruc ture (ROITE) Information Syst em NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MD-PSA-120160-NC-RFB / Co Land Administration System Single Stage - One E IDA / 63060 Post Request for Bids Open - National 535,636.47 Signed 2019-06-27 2019-09-09 2019-07-12 2019-09-06 2019-08-11 2019-11-11 2019-09-10 2020-01-03 2019-10-15 2020-02-20 2021-04-07 mpletion of the Digital archiv Strengthening nvelope e MD-PSA-122733-NC-RFQ / S Request for Quota Single Stage - One E IDA / 63060 First Property Registration Post Open - National 21,765.48 Signed 2019-09-07 2019-09-19 2019-11-02 2019-11-25 2021-10-22 urveying works Calarasovca, tions nvelope Ocnita r-n MD-PSA-124230-NC-RFQ / S Request for Quota Single Stage - One E IDA / 63060 First Property Registration Post Open - National 13,177.75 Signed 2019-09-14 2019-09-19 2019-11-09 2019-11-25 2021-10-29 urveying works Dingeni, Ocni tions nvelope ta r-n MD-PSA-124231-NC-RFQ / S Request for Quota Single Stage - One E IDA / 63060 First Property Registration Post Open - National 16,536.38 Signed 2019-09-14 2019-09-19 2019-11-09 2019-11-25 2021-10-29 urveying works Lencauti, Ocn tions nvelope ita r-n MD-PSA-124233-NC-RFQ / S Request for Quota Single Stage - One E IDA / 63060 First Property Registration Post Open - National 10,419.40 Signed 2019-09-14 2019-09-19 2019-11-09 2019-11-25 2021-10-29 urveying works Unguri, Ocnit tions nvelope a r-n Page 1 MD-PSA-124234-NC-RFQ / S Request for Quota Single Stage - One E IDA / 63060 First Property Registration Post Open - National 16,357.20 Signed 2019-09-14 2019-09-19 2019-11-09 2019-11-25 2021-10-29 urveying works Valcinet, Ocn tions nvelope ita r-n MD-PSA-124235-NC-RFQ / S Request for Quota Single Stage - One E urveying works for 16 localiti IDA / 63060 First Property Registration Post Open - National 120,277.49 Signed 2019-09-14 2019-09-19 2019-11-09 2019-11-25 2021-10-29 tions nvelope es, Ocnita r-n MD-PSA-124248-NC-DIR / Da IDA / 63060 First Property Registration Post Direct Selection Direct 7,299.21 Completed 2019-10-15 2019-09-02 2019-10-20 2019-07-15 2019-11-24 2019-11-20 2020-05-22 2019-12-13 ta acquisition from IPOT MD-PSA-122748-NC-DIR / Da IDA / 63060 First Property Registration Post Direct Selection Direct 7,326.49 Signed 2019-10-15 2019-08-07 2019-10-20 2019-03-15 2019-11-24 2019-11-20 2021-02-12 ta acquisition from INGEOCA D MD-PSA-149015-NC-RFB / Su Single Stage - One E IDA / 63060 First Property Registration Post Request for Bids Open - National 237,212.65 Signed 2019-12-13 2019-12-24 2019-12-20 2020-01-02 2020-02-05 2020-02-19 2020-03-06 2020-02-19 2020-04-10 2020-06-11 2021-06-30 rveying Works, Edinet rayon nvelope MD-PSA-160154-NC-DIR / Da IDA / 63060 First Property Registration Post Direct Selection Direct 0.00 Completed 2020-02-24 2020-03-06 2020-02-29 2020-03-25 2020-04-04 2020-10-01 2020-08-22 ta acquisition from IPOT MD-PSA-165029-NC-RFB / Su Single Stage - One E rveying Works in Balti and So IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 Canceled 2020-03-19 2020-03-23 2020-03-24 2020-05-10 2020-06-09 2020-07-14 2021-10-03 nvelope roca Rayon MD-PSA-165030-NC-RFB / Su Single Stage - One E IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 Canceled 2020-03-19 2020-03-23 2020-03-24 2020-05-10 2020-06-09 2020-07-14 2021-10-03 rveying Works in Briceni rayo nvelope n MD-PSA-189891-NC-RFB / Su Single Stage - One E IDA / 63060 First Property Registration Post Request for Bids Open - National 356,008.33 Signed 2020-08-21 2020-09-08 2020-08-26 2020-10-07 2020-10-09 2020-11-06 2020-10-09 2020-12-11 2021-01-19 2021-06-09 rveying Works in Briceni rayo nvelope n MD-PSA-193676-NC-RFB / Su Single Stage - One E Under Imple rveying Works in Soroca Ray IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 2020-09-14 2020-09-18 2020-09-19 2020-10-31 2020-10-23 2020-11-30 2020-12-02 2021-01-04 2021-07-03 nvelope mentation on and Balti Municipality MD-PSA-204704-NC-RFB / Su Single Stage - One E Under Imple IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 2020-11-18 2020-11-18 2020-11-23 2021-01-04 2021-01-15 2021-02-03 2021-01-27 2021-03-10 2021-09-06 rveying Works in Drochia ray nvelope mentation on MD-PSA-207610-NC-RFB / Su Single Stage - One E IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 Canceled 2020-12-07 2020-12-03 2020-12-12 2020-12-29 2021-01-23 2021-02-03 2021-02-22 2021-03-29 2021-09-25 rveying Works in Riscani rayo nvelope n MD-PSA-210280-NC-RFB / Co Land Administration System Single Stage - One E IDA / 63060 Post Request for Bids Open - National 612,108.27 Signed 2020-12-23 2020-12-25 2020-12-28 2021-02-17 2021-02-17 2021-03-19 2021-03-04 2021-04-23 2021-05-16 2021-10-20 mpletion of the Digital archiv Strengthening nvelope e MD-PSA-214547-NC-RFB / Su Single Stage - One E Under Imple IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 2021-01-18 2021-01-22 2021-01-23 2021-03-06 2021-02-24 2021-04-05 2021-03-25 2021-05-10 2021-11-06 rveying Works in Falesti rayo nvelope mentation n MD-PSA-208040-NC-RFB / Su Single Stage - One E IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 Canceled 2020-12-09 2021-03-29 2020-12-14 2021-02-03 2021-02-03 2021-03-05 2021-04-09 2021-10-06 rveying Works in Nisporeni ra nvelope yon MD-PSA-218340-NC-RFB / Su Single Stage - One E Under Imple IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 2021-02-10 2021-02-12 2021-02-12 2021-03-17 2021-03-17 2021-04-16 2021-04-07 2021-05-21 2021-11-17 rveying Works in Singerei ray nvelope mentation on MD-PSA-177424-NC-RFB / Su Single Stage - One E IDA / 63060 First Property Registration Post Request for Bids Open - National 731,637.62 Signed 2020-06-15 2020-09-25 2020-06-22 2020-08-08 2020-11-04 2020-09-07 2021-01-11 2021-02-26 2021-03-03 2022-05-18 rveying works, Floresti rayon nvelope MD-PSA-177425-NC-RFB / Su Single Stage - One E Under Imple IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 2020-06-15 2020-10-06 2020-06-22 2020-08-08 2020-11-11 2020-09-07 2020-12-23 2021-02-26 2022-05-18 rveying works, Donduseni ra nvelope mentation yon MD-PSA-224451-NC-DIR / Mo Pending Impl ldPos Connection Services for IDA / 63060 First Property Registration Post Direct Selection Direct 0.00 2021-03-19 2021-03-24 2021-04-28 2023-12-31 ementation Surveying works, Ingeocad di rect contract. MD-PSA-226463-NC-RFB / Su Single Stage - One E Under Imple IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 2021-03-31 2021-04-02 2021-04-05 2021-05-17 2021-05-05 2021-06-16 2021-06-09 2021-07-21 2022-01-17 rveying works, Soldanesti ray nvelope mentation on MD-PSA-218341-NC-RFB / Su Single Stage - One E Under Imple IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 2021-02-24 2021-03-19 2021-03-05 2021-04-16 2021-04-21 2021-05-16 2021-06-09 2021-06-20 2021-12-17 rveying Works in Straseni ray nvelope mentation on MD-PSA-230424-NC-RFB / Su Single Stage - One E Under Imple IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 2021-04-23 2021-04-23 2021-04-28 2021-06-09 2021-05-26 2021-07-09 2021-07-01 2021-08-13 2022-02-09 rveying works, Glodeni rayon nvelope mentation MD-PSA-234157-NC-RFB / Su Single Stage - One E IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 Canceled 2021-05-14 2021-05-14 2021-06-25 2021-07-25 2021-08-29 2022-02-25 rveying Works in Chisinau m nvelope unicipality MD-PSA-236024-NC-RFB / Su Single Stage - One E Under Imple IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 2021-05-28 2021-05-28 2021-06-02 2021-07-14 2021-06-30 2021-08-13 2021-07-20 2021-09-17 2022-03-16 rveying Works in Calarasi ray nvelope mentation on MD-PSA-239012-NC-RFB / Su Single Stage - One E IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 Canceled 2021-06-14 2021-06-11 2021-06-19 2021-07-31 2021-08-30 2021-10-04 2022-04-02 rveying Works in Telenesti ra nvelope yon MD-PSA-241398-NC-RFB / Su Single Stage - One E Under Imple IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 2021-06-30 2021-06-29 2021-07-05 2021-08-16 2021-09-15 2021-10-20 2022-04-18 rveying Works in Orhei rayon nvelope mentation MD-PSA-244263-NC-RFB / Su Single Stage - One E IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 Canceled 2021-07-20 2021-07-20 2021-07-25 2021-09-05 2021-10-05 2021-11-09 2022-05-08 rveying Works in Rezina rayo nvelope n MD-PSA-244774-NC-RFB / Su Single Stage - One E IDA / 63060 First Property Registration Post Request for Bids Open - National 194,179.42 Signed 2021-07-26 2021-07-23 2021-07-31 2021-09-11 2021-09-01 2021-10-11 2021-10-06 2021-11-15 2021-11-30 2022-05-14 rveying Works in mun. Chisi nvelope nau MD-PSA-246058-NC-RFB / Int Open - Internationa Single Stage - One E ernational Surveying Works i IDA / 63060 First Property Registration Prior Request for Bids 0.00 Canceled 2021-08-06 2021-08-23 2021-08-11 2021-08-25 2021-09-22 2021-10-22 2021-11-26 2022-05-25 l nvelope n the North Region of Moldov a MD-PSA-252455-NC-RFB / Su Single Stage - One E Under Imple IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 2021-09-10 2021-09-10 2021-09-15 2021-10-27 2021-10-13 2021-11-26 2021-11-11 2021-12-31 2022-06-29 rveying Works in Ialoveni ray nvelope mentation on MD-PSA-253301-NC-RFB / Su Single Stage - One E IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 Canceled 2021-09-17 2021-09-20 2021-09-22 2021-11-03 2021-10-21 2021-12-03 2021-11-09 2022-01-07 2022-07-06 rveying Works in Anenii Noi r nvelope ayon MD-PSA-258701-NC-RFB / Su Single Stage - One E Under Imple IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 2021-10-22 2021-12-02 2021-10-27 2021-12-08 2021-12-15 2022-01-07 2022-01-13 2022-02-11 2022-08-10 rveying Works in Criuleni ray nvelope mentation on MD-PSA-262267-NC-RFB / Su Single Stage - One E IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 Canceled 2021-11-19 2021-12-02 2021-11-24 2022-01-05 2022-02-04 2022-03-11 2022-09-07 rveying Works in Dubasari ra nvelope yon Page 2 MD-PSA-265720-NC-RFB / Su Single Stage - One E rveying Works in Cimislia & B IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 Signed 2021-12-03 2021-12-03 2021-12-08 2022-01-19 2022-01-19 2022-02-18 2022-03-30 2022-03-25 2022-09-21 nvelope asarabeasca rayons MD-PSA-266990-NC-RFB / Co Land Administration System Single Stage - One E Under Imple IDA / 63060 Post Request for Bids Open - National 0.00 2021-12-15 2021-12-10 2021-12-20 2022-02-02 2022-03-04 2022-04-08 2024-04-07 mpletion of the Digital archiv Strengthening nvelope mentation e -3 MD-PSA-265055-NC-RFB / Int Open - Internationa Single Stage - One E ernational Surveying Works i IDA / 63060 First Property Registration Prior Request for Bids 0.00 Canceled 2021-12-10 2021-12-20 2021-12-11 2021-12-23 2022-01-26 2022-02-25 2022-04-01 2024-03-31 l nvelope n the North-Center of Moldov a MD-PSA-279947-NC-RFB / Su Single Stage - One E IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 Signed 2022-02-25 2022-02-25 2022-03-02 2022-04-13 2022-03-30 2022-05-13 2022-06-08 2022-06-17 2022-12-14 rveying Works in Leova rayo nvelope n MD-PSA-280377-NC-RFB / Su Single Stage - One E IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 Signed 2022-02-25 2022-03-04 2022-03-02 2022-04-13 2022-04-06 2022-05-13 2022-06-08 2022-06-17 2023-06-16 rveying Works in Hincesti ray nvelope on MD-PSA-283129-NC-RFB / Su Single Stage - One E IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 Signed 2022-03-18 2022-03-22 2022-03-23 2022-05-04 2022-04-27 2022-06-03 2022-06-08 2022-07-08 2023-07-08 rveying Works in Cantemir ra nvelope yon MD-PSA-283127-NC-RFB / Su Single Stage - One E IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 Canceled 2022-03-11 2022-03-16 2022-04-27 2022-05-27 2022-07-01 2023-07-01 rveying Works in Taraclia ray nvelope on MD-PSA-285343-NC-RFQ / S Request for Quota Single Stage - One E Under Imple IDA / 63060 First Property Registration Post Open - National 0.00 2022-03-27 2022-05-22 2023-12-31 urveying works-2 in Riscani r tions nvelope mentation ayon MD-PSA-287188-NC-RFB / Su Single Stage - One E IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 Signed 2022-03-31 2022-04-01 2022-04-05 2022-05-17 2022-05-04 2022-06-16 2022-06-08 2022-07-21 2023-07-21 rveying works in Cahul rayon nvelope MD-PSA-290404-NC-RFB / Su Single Stage - One E IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 Signed 2022-04-22 2022-04-22 2022-04-27 2022-06-08 2022-05-25 2022-07-08 2022-06-14 2022-08-12 2023-08-11 rveying works in Causeni ray nvelope on MD-PSA-290411-NC-RFB / Su Single Stage - One E IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 Signed 2022-04-22 2022-04-22 2022-04-27 2022-06-08 2022-05-26 2022-07-08 2022-06-15 2022-08-12 2023-08-11 rveying works in Stefan Voda nvelope rayon MD-PSA-290419-NC-RFQ / S Request for Quota Single Stage - One E IDA / 63060 First Property Registration Post Open - National 0.00 Signed 2022-04-27 2022-06-22 2023-06-21 urveying works in Valea Perje tions nvelope i village MD-PSA-291138-NC-DIR / Dir ect selection of INGEOCAD St Land Administration System ate enterprize to perform the IDA / 63060 Post Direct Selection Direct 0.00 Signed 2022-04-19 2022-04-12 2022-04-24 2022-10-07 2022-05-29 2022-11-25 Strengthening Consultancy “On the CORINE Land Cover (CLC) of the Repu blic of Moldova” MD-PSA-298930-NC-RFQ / S Request for Quota Single Stage - One E Pending Impl IDA / 63060 First Property Registration Post Open - National 0.00 2022-06-15 2022-08-10 2023-08-10 urveying works in Zubresti vil tions nvelope ementation lage MD-PSA-299916-NC-RFB / Su Single Stage - One E IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 Signed 2022-06-17 2022-06-17 2022-06-22 2022-08-03 2022-07-20 2022-09-02 2022-08-11 2022-10-07 2023-10-07 rveying works in Ungheni ray nvelope on MD-PSA-299920-NC-RFQ / S Request for Quota Single Stage - One E urveying works in Vatici, Nec IDA / 63060 First Property Registration Post Open - National 0.00 Signed 2022-06-22 2022-08-17 2023-08-17 tions nvelope ulaieuca, Pohrebeni, Bulaiesti villages MD-PSA-299922-NC-RFQ / S Request for Quota Single Stage - One E urveying works in Mirzesti, Vi IDA / 63060 First Property Registration Post Open - National 0.00 Signed 2022-06-22 2022-08-17 2023-08-17 tions nvelope scauti, Trebujeni villages MD-PSA-300729-NC-RFQ / S Request for Quota Single Stage - One E urveying works in 13 Territori IDA / 63060 First Property Registration Post Open - National 0.00 Canceled 2022-06-29 2022-08-24 2023-08-24 tions nvelope al Administrative Units from Drochia rayon MD-PSA-300733-NC-RFQ / S Request for Quota Single Stage - One E urveying works in 4 Territoria IDA / 63060 First Property Registration Post Open - National 0.00 Canceled 2022-06-29 2022-08-24 2023-08-24 tions nvelope l Administrative Units from D rochia rayon MD-PSA-302058-NC-RFB / Su Single Stage - One E rveying works in Falesti Glod IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 Signed 2022-07-01 2022-07-01 2022-07-06 2022-08-17 2022-08-03 2022-09-16 2022-11-07 2022-10-21 2023-10-21 nvelope eni Riscani rayons MD-PSA-313706-NC-RFQ / S Request for Quota Single Stage - One E IDA / 63060 First Property Registration Post Open - National 0.00 Signed 2022-09-09 2022-11-04 2023-12-31 urveying works in UTA Gagau tions nvelope zia MD-PSA-313707-NC-RFQ / S Request for Quota Single Stage - One E IDA / 63060 First Property Registration Post Open - National 0.00 Signed 2022-09-16 2022-11-11 2023-12-31 urveying works in Telenesti r tions nvelope ayon MD-PSA-313708-NC-RFQ / S Request for Quota Single Stage - One E IDA / 63060 First Property Registration Post Open - National 0.00 Signed 2022-09-23 2022-11-18 2023-12-31 urveying works in Rezina ray tions nvelope on MD-PSA-322022-NC-RFQ / S Request for Quota Single Stage - One E urveying works in Boltun, Cri IDA / 63060 First Property Registration Post Open - National 0.00 Signed 2022-10-21 2022-12-16 2023-12-31 tions nvelope stesti, Bursuc villages, Nispor eni rayon MD-PSA-322023-NC-RFQ / S urveying works in Balauresti, Request for Quota Single Stage - One E IDA / 63060 First Property Registration Post Open - National 0.00 Signed 2022-10-21 2022-12-16 2023-12-31 Iurceni, Valea-Trestieni villag tions nvelope es, Nisporeni rayon MD-PSA-328232-NC-RFQ / S Request for Quota Single Stage - One E urveying works in Slobozia D IDA / 63060 First Property Registration Post Open - National 0.00 Signed 2022-11-25 2023-01-20 2023-12-31 tions nvelope usca,Cruglic villages, Criuleni rayon MD-PSA-328234-NC-RFQ / S Request for Quota Single Stage - One E urveying works in Mascauti, IDA / 63060 First Property Registration Post Open - National 0.00 Signed 2022-11-25 2023-01-20 2023-12-31 tions nvelope Miclesti villages, Criuleni ray on MD-PSA-330544-NC-RFQ / S Request for Quota Single Stage - One E urveying works in Condrita, IDA / 63060 First Property Registration Post Open - National 0.00 Canceled 2022-12-16 2023-02-11 2024-02-11 tions nvelope Ghidighici, Vatra and Truseni MD-PSA-330547-NC-RFQ / S Request for Quota Single Stage - One E urveying works in Colonita, T IDA / 63060 First Property Registration Post Open - National 0.00 Canceled 2022-12-16 2023-02-10 2024-02-10 tions nvelope ohatin, Bubueci MD-PSA-330548-NC-RFQ / S Request for Quota Single Stage - One E urveying works in Durlesti, C IDA / 63060 First Property Registration Post Open - National 0.00 Canceled 2022-12-16 2023-02-10 2024-02-10 tions nvelope odru, Singera Page 3 MD-PSA-330553-NC-RFQ / S Request for Quota Single Stage - One E urveying works in Radeni and IDA / 63060 First Property Registration Post Open - National 0.00 Canceled 2022-12-16 2023-02-10 2024-02-10 tions nvelope Buda villages MD-PSA-330554-NC-RFQ / S Request for Quota Single Stage - One E urveying works in Paulesti an IDA / 63060 First Property Registration Post Open - National 0.00 Canceled 2022-12-16 2023-02-10 2024-02-10 tions nvelope d Pitusca villages MD-PSA-330653-NC-DIR / Cr edit rating calculation service IDA / 63060 Property Valuation Post Direct Selection Direct - National 0.00 Signed 2022-12-09 2022-12-09 2022-12-14 2022-12-16 2023-01-18 2024-01-18 s for land registered in the R eal Estate Register MD-PSA-335698-NC-RFQ / S Request for Quota Single Stage - One E urveying works in Holercani, IDA / 63060 First Property Registration Post Open - National 0.00 Signed 2023-01-13 2023-02-24 2024-02-29 tions nvelope Marcauti, Ustia villages MD-PSA-335701-NC-RFQ / S Request for Quota Single Stage - One E urveying works in Botnaresti, IDA / 63060 First Property Registration Post Open - National 0.00 Canceled 2023-01-13 2023-02-24 2024-02-29 tions nvelope Hirbovat villages MD-PSA-335703-NC-RFQ / S Request for Quota Single Stage - One E urveying works in Calfa, Maxi IDA / 63060 First Property Registration Post Open - National 0.00 Signed 2023-01-13 2023-02-24 2024-02-29 tions nvelope movca, Speia villages MD-PSA-338832-NC-DIR / Me trological verification for 2 G IDA / 63060 First Property Registration Post Direct Selection Direct - National 0.00 Signed 2023-01-27 2023-01-27 2023-01-30 2023-01-30 2023-03-07 2023-12-31 NSS devices MD-PSA-302061-NC-RFQ / S Request for Quota Single Stage - One E IDA / 63060 First Property Registration Post Open - National 0.00 Canceled 2022-07-06 2022-08-31 2023-08-31 urveying works in Straseni ra tions nvelope yon MD-PSA-296725-NC-RFB / Su Single Stage - One E IDA / 63060 First Property Registration Post Request for Bids Open - National 0.00 Canceled 2022-05-27 2022-06-01 2022-07-13 2022-08-12 2022-09-16 2023-09-16 rveying works in UTAG nvelope MD-PSA-342894-NC-RFQ / S Request for Quota Single Stage - One E urveying works in Dereneu, IDA / 63060 First Property Registration Post Open - National 0.00 Signed 2023-02-17 2023-04-14 2024-04-13 tions nvelope Hoginesti villages MD-PSA-342902-NC-RFQ / S Request for Quota Single Stage - One E urveying works in Coscodeni, IDA / 63060 First Property Registration Post Open - National 0.00 Signed 2023-02-17 2023-04-14 2024-04-13 tions nvelope Bursuceni villages from Singe rei rayon MD-PSA-342904-NC-RFQ / S Request for Quota Single Stage - One E urveying works in Ciuciuleni, IDA / 63060 First Property Registration Post Open - National 0.00 Canceled 2023-02-17 2023-04-14 2024-04-13 tions nvelope Prepelita villages from Singer ei rayon MD-PSA-342906-NC-RFQ / S Request for Quota Single Stage - One E urveying works in Cotiujenii IDA / 63060 First Property Registration Post Open - National 0.00 Signed 2023-02-17 2023-04-14 2024-04-13 tions nvelope Mici village from Singerei ray on MD-PSA-344328-NC-RFQ / S Request for Quota Single Stage - One E urveying works in Horodca, R IDA / 63060 First Property Registration Post Open - National 0.00 Canceled 2023-02-24 2023-03-31 2024-03-30 tions nvelope usestii Noi villages MD-PSA-344331-NC-RFQ / S Request for Quota Single Stage - One E urveying works in Cigirleni, C IDA / 63060 First Property Registration Post Open - National 0.00 Signed 2023-02-24 2023-03-31 2024-03-30 tions nvelope arbuna villages MD-PSA-345490-NC-RFQ / S Request for Quota Single Stage - One E urveying works in Hircesti, N IDA / 63060 First Property Registration Post Open - National 0.00 Signed 2023-03-03 2023-04-01 2024-03-31 tions nvelope apadeni, Cornova villages MD-PSA-345502-NC-RFQ / S Request for Quota Single Stage - One E urveying works in Magurele, IDA / 63060 First Property Registration Post Open - National 0.00 Canceled 2023-03-03 2023-04-01 2024-03-31 tions nvelope Negurenii Vechi, Bumbata vill ages MD-PSA-345505-NC-RFQ / S Request for Quota Single Stage - One E urveying works in Costuleni, IDA / 63060 First Property Registration Post Open - National 0.00 Canceled 2023-03-03 2023-04-01 2024-03-31 tions nvelope Macaresti villages MD-PSA-347392-NC-RFQ / S Request for Quota Single Stage - One E IDA / 63060 First Property Registration Post Open - National 0.00 Signed 2023-03-10 2023-04-01 2024-03-31 urveying works in Gangura vi tions nvelope llage MD-PSA-350526-NC-RFQ / S Request for Quota Single Stage - One E urveying works in Antoneuca IDA / 63060 First Property Registration Post Open - National 0.00 Canceled 2023-03-24 2023-04-30 2024-03-31 tions nvelope , Pervomaisc, Fintinta village s MD-PSA-355725-NC-RFQ / S Request for Quota Single Stage - One E urveying works in Draganesti IDA / 63060 First Property Registration Post Open - National 0.00 Signed 2023-04-14 2023-05-18 2024-04-18 tions nvelope and Izvoare villages MD-PSA-355728-NC-RFQ / S Request for Quota Single Stage - One E urveying works in Taura Vec IDA / 63060 First Property Registration Post Open - National 0.00 Canceled 2023-04-14 2023-05-18 2024-04-18 tions nvelope he and Heciul Nou villages MD-PSA-355730-NC-RFQ / S Request for Quota Single Stage - One E Under Imple urveying works in Botnaresti IDA / 63060 First Property Registration Post Open - National 0.00 2023-04-14 2023-05-19 2024-04-19 tions nvelope mentation village, Anenii Noi rayon MD-PSA-355733-NC-RFQ / S Request for Quota Single Stage - One E Under Imple urveying works in Serpeni vill IDA / 63060 First Property Registration Post Open - National 0.00 2023-04-14 2023-05-18 2024-04-18 tions nvelope mentation age from Anenii Noi rayon MD-PSA-355734-NC-RFQ / S Request for Quota Single Stage - One E Under Imple urveying works in Antoneuca IDA / 63060 First Property Registration Post Open - National 0.00 2023-04-14 2023-05-10 2024-04-10 tions nvelope mentation , Pervomaisc, Fintinta village s MD-PSA-359838-NC-RFQ / S Request for Quota Single Stage - One E Under Imple urveying works in Negurenii IDA / 63060 First Property Registration Post Open - National 0.00 2023-05-05 2023-05-31 2024-05-01 tions nvelope mentation Vechi and Sinesti villages fro m Ungheni rayon MD-PSA-361050-NC-RFQ / S Request for Quota Single Stage - One E urveying works in Tibirica, Ba IDA / 63060 First Property Registration Post Open - National 0.00 Canceled 2023-05-12 2023-06-15 2024-05-15 tions nvelope hmut, Sipoteni villages CONSULTING FIRMS Page 4 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MD-PSA-122740-CS-CQS / Pu Consultant Qualifi IDA / 63060 First Property Registration Post Open - National 0.00 Canceled 2019-12-02 2020-10-19 2019-12-23 2020-02-05 2020-03-06 2020-04-10 2021-04-05 blic Awareness cation Selection MD-PSA-122736-CS-LCS / Cu Capacity Building and Projec Consultant Qualifi IDA / 63060 Post Open - National 36,643.00 Signed 2019-12-02 2020-10-19 2019-12-23 2020-02-05 2021-01-29 2020-03-06 2021-03-16 2020-04-10 2021-05-13 2020-10-07 stomer Satisfaction Survey t Management cation Selection MD-PSA-210225-CS-LCS / Pr Capacity Building and Projec Least Cost Selecti Pending Impleme IDA / 63060 Post Open - National 0.00 2020-12-21 2020-12-21 2020-12-21 2021-01-18 2021-02-17 2021-03-24 2021-04-28 2021-10-25 oject Audit Services for 2019 t Management on ntation - 2020 MD-PSA-174745-NC-RFB / Int ernational Consultant Compa Land Administration System Consultant Qualifi Open - Internationa IDA / 63060 Post 0.00 Canceled 2021-06-15 2021-07-06 2021-08-19 2021-09-18 2021-10-23 2022-04-21 ny for developing of National Strengthening cation Selection l Spatial Data Infrastructure G eoportal MD-PSA-243092-CS-CQS / Co nsultant to develop national Land Administration System Consultant Qualifi Open - Internationa NSDI data standards for IDA / 63060 Post 90,523.43 Signed 2021-07-16 2021-07-20 2021-08-18 2021-08-05 2021-10-01 2021-11-23 2021-10-31 2022-03-16 2021-12-05 2022-03-22 2022-06-03 Strengthening cation Selection l priority data themes and dat a model MD-PSA-246911-CS-CQS / Pu Consultant Qualifi IDA / 63060 First Property Registration Post Open - National 0.00 Canceled 2021-08-13 2021-09-20 2021-09-03 2021-10-17 2021-11-16 2021-12-21 2022-06-19 blic Awareness 2 cation Selection MD-PSA-253643-CS-CQS / PE Land Administration System Consultant Qualifi IDA / 63060 Post Open - National 133,750.00 Signed 2021-09-24 2021-09-22 2021-10-15 2021-09-24 2021-11-28 2021-11-23 2021-12-28 2022-02-25 2022-02-01 2022-03-02 2022-07-31 RFORMANCE AUDIT OF MOLD Strengthening cation Selection LIS MD-PSA-259029-CS-CQS / Co Consultant Qualifi Under Implement IDA / 63060 Property Valuation Post Open - National 0.00 2021-10-29 2021-11-03 2021-11-19 2022-01-02 2022-02-01 2022-03-08 2022-09-04 st Table cation Selection ation MD-PSA-264949-CS-LCS / Pr Capacity Building and Projec Least Cost Selecti IDA / 63060 Post Open - National 10,676.00 Signed 2021-12-02 2021-12-02 2021-12-02 2021-12-02 2021-12-02 2021-12-22 2021-12-29 2022-01-21 2022-01-26 2022-02-25 2022-02-14 2022-04-01 2022-03-03 2022-06-30 oject Audit Services for 2021 t Management on MD-PSA-282238-CS-CQS / Co nsultant Services to support Land Administration System Consultant Qualifi Open - Internationa Under Implement IDA / 63060 Post 0.00 2022-03-04 2022-03-09 2022-03-25 2022-03-10 2022-05-08 2022-05-27 2022-06-07 2022-08-03 2022-07-12 2024-05-02 NSDI Action Plan and Busines Strengthening cation Selection l ation s Model Implementation MD-PSA-297741-CS-CQS / Co Land Administration System Consultant Qualifi nsultant Services to strength IDA / 63060 Post Open - National 0.00 Canceled 2022-06-03 2022-06-24 2022-08-07 2022-09-06 2022-10-11 2024-09-30 Strengthening cation Selection en the NSDI Capacity at the ALRC MD-PSA-307724-CS-CQS / Co Consultant Qualifi IDA / 63060 Property Valuation Post Open - National 0.00 Signed 2022-08-05 2022-08-16 2022-08-26 2022-10-09 2022-10-28 2022-11-08 2022-12-05 2022-12-13 2023-05-13 st Table for 1 Volume cation Selection MD-PSA-332044-CS-CQS / Pu Consultant Qualifi Under Implement IDA / 63060 First Property Registration Post Open - National 0.00 2022-12-23 2022-12-22 2023-01-18 2023-02-14 2023-02-24 2023-03-16 2023-04-20 2024-03-31 blic Outreach Campaign cation Selection ation MD-PSA-339215-CS-CQS / So Capacity Building and Projec Consultant Qualifi Under Implement cial assessment for land regi IDA / 63060 Post Open - National 0.00 2023-01-30 2023-01-30 2023-02-22 2023-04-07 2023-05-07 2023-06-11 2023-12-08 t Management cation Selection ation stration and property valuati on project MD-PSA-122759-CS-CQS / So Capacity Building and Projec Consultant Qualifi IDA / 63060 Post Open - National 0.00 Canceled 2021-06-30 2023-02-01 2021-07-21 2021-09-03 2021-10-03 2021-11-07 2022-05-06 cial Survey t Management cation Selection MD-PSA-168530-CS-CQS / In ternational Consultant Comp Land Administration System Consultant Qualifi Open - Internationa IDA / 63060 Post 0.00 Canceled 2020-04-20 2020-10-27 2020-05-11 2020-06-24 2020-07-24 2020-08-28 2021-02-24 any for developing of standar Strengthening cation Selection l ds for National Spatial Data I nfrastructure MD-PSA-344374-CS-CQS / Co nsulting services for the impl Capacity Building and Projec Consultant Qualifi Under Implement IDA / 63060 Post Open - National 0.00 2023-02-24 2023-02-23 2023-02-24 2023-03-22 2023-03-31 2023-05-05 2024-01-30 ementation of the Action Pla t Management cation Selection ation n for the improvement of cad astral services INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MD-PSA-98080-CS-INDV / Pr Capacity Building and Projec Individual Consult oject Implementation Unit Fin IDA / 63060 Post Open 30,712.32 Signed 2019-02-03 2019-01-31 2019-02-22 2019-03-25 2019-02-24 2019-12-03 2019-03-01 2019-05-28 2024-06-28 t Management ant Selection ancial Management Specialis t MD-PSA-98086-CS-INDV / Pr Capacity Building and Projec Individual Consult oject Implementation Unit Pr IDA / 63060 Post Open 28,796.93 Terminated 2019-02-03 2019-01-31 2019-02-22 2019-03-19 2019-02-24 2019-05-07 2019-03-01 2019-05-17 2023-12-29 t Management ant Selection ocurement Specialist MD-PSA-120121-CS-CDS / Te Capacity Building and Projec chnical training course on th IDA / 63060 Post Direct Selection Direct 2,500.00 Completed 2019-06-27 2019-07-10 2019-07-07 2019-07-11 2019-08-01 2019-11-13 2019-08-31 2019-12-30 t Management e general modules of the Arc Gis MD-PSA-120113-CS-INDV / In Individual Consult IDA / 63060 First Property Registration Post Open 47,144.08 Signed 2019-07-02 2019-07-12 2019-08-18 2019-09-13 2019-09-08 2019-10-25 2019-10-13 2019-11-15 2023-12-31 itial Data Collection Expert ant Selection MD-PSA-122761-CS-INDV / S Capacity Building and Projec Individual Consult IDA / 63060 Post Open 0.00 Canceled 2019-10-15 2019-11-11 2019-12-03 2019-12-24 2020-01-28 2021-01-22 ocial Development Specialist t Management ant Selection MD-PSA-124223-CS-INDV / E Capacity Building and Projec Individual Consult IDA / 63060 Post Open 0.00 Canceled 2019-10-15 2019-11-11 2019-12-03 2019-12-24 2020-01-28 2021-01-22 nvironmental Specialist t Management ant Selection MD-PSA-122757-CS-INDV / C Individual Consult oordinator for Collection of m IDA / 63060 Property Valuation Post Open 0.00 Canceled 2019-09-02 2019-10-21 2019-11-11 2019-12-16 2020-12-10 ant Selection arket data, Modeling & GIS c onsultant (local) MD-PSA-122756-CS-INDV / C oordinator for Collection of m Individual Consult IDA / 63060 Property Valuation Post Open 0.00 Canceled 2019-09-02 2019-10-25 2019-10-21 2019-11-11 2019-12-16 2020-12-10 arket data, Modeling consult ant Selection ant (Local Consultant ) MD-PSA-122749-CS-INDV / Q Land Administration System Individual Consult uality Control digital archive IDA / 63060 Post Open 19,409.91 Signed 2019-12-02 2020-02-11 2020-01-20 2020-03-26 2020-02-10 2020-06-01 2020-03-16 2020-06-02 2021-03-11 Strengthening ant Selection consultant (local, 12 persons) Page 5 MD-PSA-122754-CS-INDV / C Individual Consult ollection of market data Cons IDA / 63060 Property Valuation Post Open 6,241.76 Signed 2019-12-02 2019-10-25 2020-01-20 2020-02-11 2020-02-10 2020-07-01 2020-03-16 2020-07-02 2021-03-11 ant Selection ultant (local, 45 persons) MD-PSA-122760-CS-INDV / M Capacity Building and Projec Individual Consult IDA / 63060 Post Open 0.00 Canceled 2019-10-15 2019-11-01 2019-12-03 2019-12-24 2020-01-28 2021-01-22 onitoring&Evaluation Speciali t Management ant Selection st MD-PSA-122758-CS-INDV / R eview of legislation, exempti Individual Consult IDA / 63060 Property Valuation Post Open 0.00 Canceled 2020-06-01 2020-07-20 2020-08-10 2020-09-14 2021-09-09 ons, and socioeconomic anal ant Selection ysis, (international consultan t) MD-PSA-135921-CS-INDV / In Individual Consult ternational Individual Valuati IDA / 63060 Property Valuation Post Open 0.00 Signed 2019-10-31 2019-11-14 2019-12-19 2020-03-04 2020-01-09 2020-03-12 2020-02-13 2020-12-31 ant Selection on Consultant MD-PSA-136123-CS-INDV / Q Individual Consult A - Ground Checks 5 Individu IDA / 63060 First Property Registration Post Open 0.00 Canceled 2019-12-02 2019-11-28 2020-01-20 2020-02-10 2020-03-16 2020-09-12 ant Selection al Consultants MD-PSA-97718-CS-INDV / Pr Capacity Building and Projec Individual Consult IDA / 63060 Post Open 0.00 Canceled 2019-02-03 2019-02-22 2019-02-24 2019-03-01 2024-06-28 oject Implementation Unit Dir t Management ant Selection ector MD-PSA-97718-CS-INDV-2 / Capacity Building and Projec Individual Consult IDA / 63060 Post Open 0.00 Canceled 2019-10-30 2019-11-08 2019-11-18 2019-11-20 2019-11-25 2025-03-24 Project Implementation Unit t Management ant Selection Director MD-PSA-135917-CS-INDV / T Capacity Building and Projec Individual Consult rainer (Statistician), Individua IDA / 63060 Post Open 1,115.27 Signed 2019-11-05 2019-11-12 2019-12-24 2020-03-19 2020-01-14 2020-03-19 2020-02-18 2020-05-19 2020-03-19 t Management ant Selection l Consultant MD-PSA-142661-CS-INDV / In Individual Consult itial Data Collection Expert (3 IDA / 63060 First Property Registration Post Open 0.00 Canceled 2019-11-01 2019-11-11 2019-12-20 2020-01-10 2020-02-14 2021-02-08 ant Selection local Consultants) MD-PSA-136123-CS-INDV-2 / Individual Consult QA-Ground Check Consultant IDA / 63060 First Property Registration Post Open 0.00 Canceled 2020-02-03 2020-06-14 2020-03-13 2020-04-03 2020-05-08 2020-11-04 ant Selection s (5 Consultants) MD-PSA-142661-CS-INDV-2 / Individual Consult Initial Data Collection Consult IDA / 63060 First Property Registration Post Open 12,318.04 Signed 2020-02-02 2020-02-06 2020-03-13 2020-03-26 2020-04-03 2020-07-01 2020-05-08 2020-07-02 2021-05-03 ant Selection ants (5 Consultants) MD-PSA-124223-CS-INDV-2 / Capacity Building and Projec Individual Consult IDA / 63060 Post Open 0.00 Canceled 2020-02-27 2020-03-05 2020-04-10 2020-05-01 2020-06-05 2021-05-31 Environmental Specialist t Management ant Selection MD-PSA-122756-CS-INDV-2 / Individual Consult Under Implement Individual Consultant for the IDA / 63060 Property Valuation Post Open 0.00 2020-03-09 2020-03-13 2020-04-27 2020-04-27 2020-05-18 2020-06-16 2020-06-22 2021-06-17 ant Selection ation Development of Valuation Mo dels MD-PSA-166617-CS-INDV / In Individual Consult itial Data Collection Consulta IDA / 63060 First Property Registration Post Open 1,032.30 Signed 2020-03-30 2020-03-31 2020-05-09 2020-05-06 2020-05-30 2020-07-01 2020-07-04 2020-07-02 2021-06-29 ant Selection nts (4 Consultants) MD-PSA-168528-CS-INDV / In ternational Individual Consult ant for Implementation of the Land Administration System Individual Consult IDA / 63060 Post Open 0.00 Canceled 2020-04-15 2021-04-02 2020-06-03 2020-06-24 2020-07-29 2021-01-25 Integrated Geospatial Inform Strengthening ant Selection ation Framework (IGIF) Strate gic Pathway 9, Communicati on and Engagement, in Mold ova MD-PSA-168548-CS-INDV / In ternational Consultant for de Land Administration System Individual Consult IDA / 63060 Post Open 0.00 Canceled 2020-04-19 2020-10-27 2020-06-07 2020-06-28 2020-08-02 2021-01-29 veloping Capacities Building i Strengthening ant Selection n the Spatial Data Infrastruct ure of Moldova MD-PSA-168549-CS-INDV / In ternational Individual Consult Land Administration System Individual Consult ant for developing a Business IDA / 63060 Post Open 0.00 Canceled 2020-04-19 2020-11-03 2020-06-07 2020-06-28 2020-08-02 2020-12-30 Strengthening ant Selection Model for the Spatial Data Inf rastructure in Moldova MD-PSA-189887-CS-INDV / Q Land Administration System Individual Consult uality Control digital archive IDA / 63060 Post Open 26,281.14 Signed 2020-08-21 2020-08-28 2020-10-09 2020-10-02 2020-10-30 2020-10-22 2020-12-04 2020-10-23 2021-11-29 Strengthening ant Selection consultant (local, 6 persons) MD-PSA-189890-CS-INDV / In itial Data Collection and Qual Individual Consult IDA / 63060 First Property Registration Post Open 28,919.76 Signed 2020-08-21 2020-08-28 2020-10-09 2020-10-01 2020-10-30 2020-10-20 2020-12-04 2020-10-21 2021-06-02 ity Assurance Consultant (lo ant Selection cal, 3 consultants) MD-PSA-197666-CS-INDV / C ollection of market data and Individual Consult IDA / 63060 Property Valuation Post Open 9,537.69 Signed 2020-10-05 2020-11-03 2020-11-23 2020-12-09 2020-12-14 2020-12-31 2021-01-18 2020-12-31 2021-07-17 real property evaluation Con ant Selection sultant (6 local consultants) MD-PSA-202116-CS-INDV / Q Land Administration System Individual Consult uality Control digital archive IDA / 63060 Post Open 24,745.54 Signed 2020-11-02 2020-11-04 2020-12-21 2020-12-09 2021-01-11 2020-12-15 2021-02-15 2021-01-02 2021-08-14 Strengthening ant Selection consultant (local, 4 persons) MD-PSA-205277-CS-INDV / In Individual Consult dividual Consultant for the D IDA / 63060 Property Valuation Post Open 0.00 Canceled 2020-11-18 2020-12-01 2021-01-08 2021-01-29 2021-03-05 2021-09-01 ant Selection evelopment of Valuation Mod els MD-PSA-210230-CS-INDV / Q Land Administration System Individual Consult uality Control digital archive IDA / 63060 Post Open 60,671.87 Signed 2020-12-25 2021-01-11 2021-02-19 2021-02-03 2021-03-12 2021-02-03 2021-04-16 2021-03-03 2021-10-13 Strengthening ant Selection consultant (local, 5 persons) MD-PSA-210232-CS-INDV / In dividual Consultant for the D Individual Consult IDA / 63060 Property Valuation Post Open 25,236.27 Signed 2020-12-25 2021-01-19 2021-02-23 2021-02-23 2021-03-16 2021-03-30 2021-04-20 2021-03-31 2021-10-17 evelopment of Valuation Mod ant Selection els (Commercial and Industri al) MD-PSA-136124-CS-INDV / Q A - Receiving Data @ Cadastr Individual Consult IDA / 63060 First Property Registration Post Open 0.00 Canceled 2021-03-15 2021-05-03 2021-05-24 2021-06-28 2022-06-23 u (Verification Acceptance) 7 ant Selection Individual Consultants Page 6 MD-PSA-122735-CS-INDV / P reparation of the TOR for dev Land Administration System Individual Consult elopment of module for Syste IDA / 63060 Post Open 0.00 Canceled 2021-07-15 2021-09-02 2021-09-23 2021-10-28 2022-04-26 Strengthening ant Selection matic Registration, QA impro vement and Valuation & MOL DLIS Modifications MD-PSA-222257-CS-INDV / I Capacity Building and Projec Individual Consult IDA / 63060 Post Open 4,057.13 Signed 2021-03-09 2021-03-26 2021-04-27 2021-05-20 2021-05-18 2021-05-01 2021-06-22 2021-06-08 2021-12-19 CT Procurement Specialist t Management ant Selection MD-PSA-213829-CS-INDV / In Individual Consult itial Data Collection Consulta IDA / 63060 First Property Registration Post Open 11,364.90 Signed 2021-04-30 2021-04-07 2021-06-18 2021-06-30 2021-07-09 2021-07-01 2021-08-13 2021-07-27 2022-02-09 ant Selection nts (2 Consultants) MD-PSA-226575-CS-INDV / In dividual Consultant for the D Individual Consult IDA / 63060 Property Valuation Post Open 0.00 Canceled 2021-04-02 2021-03-31 2021-05-28 2021-06-18 2021-07-23 2022-01-19 evelopment of the Real Estat ant Selection e Evaluation Methodological Framework MD-PSA-226665-CS-INDV / In dividual Consultant to Develo Land Administration System Individual Consult IDA / 63060 Post Open 0.00 Canceled 2021-04-02 2021-03-31 2021-05-21 2021-06-11 2021-07-16 2022-01-12 p the Technical Specification Strengthening ant Selection s for the AIS Public Utilities R egister MD-PSA-228085-CS-INDV / In Individual Consult dividual Consultant for Initial IDA / 63060 First Property Registration Post Open 0.00 Canceled 2021-04-30 2021-06-18 2021-07-09 2021-08-13 2022-02-09 ant Selection Data Collection of State Own ed Real Estate MD-PSA-237390-CS-INDV / In Individual Consult ternational Individual Consult IDA / 63060 Property Valuation Post Open 145,025.29 Signed 2021-06-04 2021-06-04 2021-07-23 2021-10-04 2021-08-13 2021-10-24 2021-09-17 2022-01-02 2022-03-16 ant Selection ant Real Property Valuation MD-PSA-237377-CS-INDV / I NDIVIDUAL CONSULTANT FO Individual Consult IDA / 63060 Property Valuation Post Open 0.00 Canceled 2021-06-04 2021-06-04 2021-07-30 2021-08-20 2021-09-24 2022-03-23 R THE DEVELOPMENT OF VAL ant Selection UATION MODELS (REAL EST ATE) MD-PSA-239035-CS-INDV / Q uality Control digital archive Land Administration System Individual Consult Under Implement IDA / 63060 Post Open 0.00 2021-06-11 2021-06-10 2021-08-06 2021-08-27 2021-10-01 2022-03-30 consultant (local, 6 persons f Strengthening ant Selection ation or Digitization nr.2) MD-PSA-240743-CS-INDV / In dividual Local Consultant to Land Administration System Individual Consult IDA / 63060 Post Open 0.00 Canceled 2021-06-25 2021-06-25 2021-08-13 2021-09-03 2021-10-08 2022-04-06 Develop the Technical Specifi Strengthening ant Selection cations for the AIS Public Utili ties Register MD-PSA-240745-CS-INDV / In dividual International Consult Land Administration System Individual Consult IDA / 63060 Post Open 51,700.00 Signed 2021-06-25 2021-06-25 2021-08-13 2021-10-28 2021-09-03 2021-11-30 2021-10-08 2021-12-02 2022-04-06 ant to Develop the Technical Strengthening ant Selection Specifications for the AIS Pub lic Utilities Register MD-PSA-241055-CS-INDV / C ollection of market data and Individual Consult IDA / 63060 Property Valuation Post Open 0.00 Canceled 2021-06-25 2021-08-20 2021-09-10 2021-10-15 2022-04-13 real property evaluation Con ant Selection sultant (4 local consultants) MD-PSA-246019-CS-INDV / In Individual Consult itial Data Collection Consulta IDA / 63060 First Property Registration Post Open 0.00 Canceled 2021-07-30 2021-09-24 2021-10-15 2021-11-19 2022-05-18 ant Selection nts ( Taraclia, Cahul, UTAG) MD-PSA-246021-CS-INDV / Q Individual Consult uality Assurance Consultant ( IDA / 63060 First Property Registration Post Open 25,831.98 Terminated 2021-07-30 2021-12-16 2021-09-24 2021-09-09 2021-10-15 2021-09-20 2021-11-19 2021-10-02 2022-05-18 ant Selection 8 Consultants) MD-PSA-253302-CS-INDV / L Individual Consult IDA / 63060 Property Valuation Post Open 2,997.57 Signed 2021-09-17 2021-09-22 2021-11-05 2021-11-03 2021-11-26 2021-12-01 2021-12-31 2021-12-11 2022-06-29 ocal Valuation Specialist ant Selection MD-PSA-265062-CS-INDV / L Individual Consult IDA / 63060 Property Valuation Post Open 0.00 Canceled 2021-12-03 2022-01-21 2022-02-11 2022-03-18 2022-09-14 ead Valuer (Agricultural Land ant Selection ) MD-PSA-265077-CS-INDV / L Individual Consult ocal Valuation Specialist (Agr IDA / 63060 Property Valuation Post Open 0.00 Canceled 2021-12-03 2022-01-21 2022-02-11 2022-03-18 2022-09-14 ant Selection icultural Land) MD-PSA-265081-CS-INDV / S Individual Consult IDA / 63060 Property Valuation Post Open 0.00 Canceled 2021-12-03 2022-01-21 2022-02-11 2022-03-18 2022-09-14 tatistician (Agricultural Land) ant Selection MD-PSA-268887-CS-INDV / C ollection of market data and Individual Consult IDA / 63060 Property Valuation Post Open 0.00 Canceled 2021-12-17 2021-12-23 2022-02-16 2022-03-09 2022-04-13 2023-04-13 real property evaluation Con ant Selection sultant (4 local consultants). MD-PSA-270721-CS-INDV / In dividual Consultant to develo Land Administration System Individual Consult IDA / 63060 Post Open 63,555.54 Signed 2021-12-24 2021-12-27 2022-02-11 2022-03-09 2022-03-04 2022-03-30 2022-04-08 2022-04-05 2022-10-05 p in the framework of the GIS Strengthening ant Selection -Local platform THE GIS. MD-PSA-272558-CS-INDV / C onsultants for development o Individual Consult f methodology and models fo IDA / 63060 Property Valuation Post Open 0.00 Canceled 2022-01-14 2022-01-12 2022-03-04 2022-04-04 2022-03-25 2022-04-29 2022-10-26 ant Selection r assessing agricultural land f or tax purposes (team leader ) MD-PSA-272559-CS-INDV / C onsultants for development o Individual Consult IDA / 63060 Property Valuation Post Open 25,502.20 Signed 2022-01-14 2022-01-12 2022-03-04 2022-04-05 2022-03-25 2022-04-18 2022-04-29 2022-04-29 2022-10-26 f methodology and models fo ant Selection r assessing agricultural land f or tax purposes MD-PSA-272560-CS-INDV / C onsultants for development o Individual Consult IDA / 63060 Property Valuation Post Open 20,605.79 Signed 2022-01-14 2022-01-12 2022-03-04 2022-04-05 2022-03-25 2022-04-18 2022-04-29 2022-04-28 2022-10-26 f models for the evaluation of ant Selection agricultural land (Statistician ) MD-PSA-275542-CS-INDV / I Capacity Building and Projec Individual Consult Under Implement IDA / 63060 Post Open 0.00 2022-02-04 2022-02-02 2022-03-25 2022-04-15 2022-05-20 2022-11-16 CT Procurement Specialist t Management ant Selection ation MD-PSA-278597-CS-INDV / In Land Administration System Individual Consult ternational Consultant in Spa IDA / 63060 Post Open 0.00 Signed 2022-02-18 2022-02-15 2022-04-08 2022-06-16 2022-04-29 2022-07-21 2022-06-03 2023-02-28 Strengthening ant Selection tial Data Licensing Page 7 MD-PSA-278603-CS-INDV / S Land Administration System Individual Consult enior Consultant for NSDI Co IDA / 63060 Post Open 0.00 Canceled 2022-02-18 2022-02-15 2022-04-08 2022-04-29 2022-06-03 2024-05-23 Strengthening ant Selection ordination Team MD-PSA-278875-CS-INDV / C Land Administration System Individual Consult IDA / 63060 Post Open 0.00 Canceled 2022-02-18 2022-02-17 2022-04-08 2022-04-29 2022-06-03 2024-05-23 onsultant for NSDI Coordinati Strengthening ant Selection on Team MD-PSA-280834-CS-CDS / IC Capacity Building and Projec IDA / 63060 Post Direct Selection Direct 22,000.00 Signed 2022-02-28 2022-02-24 2022-03-10 2022-04-22 2022-05-14 2022-04-23 2023-05-09 T Procurement Specialist t Management MD-PSA-286364-CS-INDV / T Capacity Building and Projec Individual Consult echnical Consultant for Spati IDA / 63060 Post Open 0.00 Canceled 2022-03-25 2022-03-25 2022-05-13 2022-06-03 2022-07-08 2023-07-03 t Management ant Selection al Data Harmonization ( two Consultant's) MD-PSA-290497-CS-INDV / In dividual consultant for the co Individual Consult Under Implement IDA / 63060 First Property Registration Post Open 0.00 2022-04-15 2022-04-11 2022-06-03 2022-06-13 2022-06-24 2022-07-06 2022-07-29 2023-07-28 ordination of activities in the ant Selection ation process of delimitation of pu blic property MD-PSA-291927-CS-INDV / In dividual International Consult Land Administration System Individual Consult IDA / 63060 Post Open 0.00 Signed 2022-04-29 2022-05-03 2022-06-17 2022-07-07 2022-07-08 2022-07-27 2022-08-12 2023-02-08 ant to Develop the Technical Strengthening ant Selection Specifications for the AIS Pub lic Utilities Register MD-PSA-291928-CS-INDV / C onsultants for development o Individual Consult f methodology and models fo IDA / 63060 Property Valuation Post Open 0.00 Canceled 2022-04-29 2022-05-06 2022-06-17 2022-07-08 2022-08-12 2023-08-12 ant Selection r assessing agricultural land f or tax purposes (team leader ) - RELUNCHED MD-PSA-293360-CS-INDV / C ollection of market data and Individual Consult IDA / 63060 Property Valuation Post Open 0.00 Signed 2022-05-06 2022-05-05 2022-06-24 2022-06-15 2022-07-15 2022-06-16 2022-08-19 2023-02-15 real property evaluation Con ant Selection sultant (2 local consultants). MD-PSA-293361-CS-INDV / C ollection of market data and Individual Consult IDA / 63060 Property Valuation Post Open 0.00 Signed 2022-05-06 2022-05-05 2022-06-24 2022-06-15 2022-07-15 2022-06-16 2022-08-19 2023-02-15 real property evaluation Con ant Selection sultant (1 local consultant). MD-PSA-295644-CS-INDV / Q uality Control digital archive Land Administration System Individual Consult IDA / 63060 Post Open 0.00 Signed 2022-05-20 2022-08-25 2022-07-08 2022-08-09 2022-07-29 2022-08-18 2022-09-02 2023-09-02 consultant (local, 4 persons f Strengthening ant Selection or Digitization nr.3) MD-PSA-300553-CS-INDV / In dividual consultant for the ex Individual Consult IDA / 63060 First Property Registration Post Open 0.00 Canceled 2022-06-24 2022-06-23 2022-08-12 2022-09-02 2022-10-07 2023-10-07 ecution of massive cadastral ant Selection works (8 consultants) MD-PSA-302063-CS-INDV / Q Individual Consult uality Assurance Consultant ( IDA / 63060 First Property Registration Post Open 0.00 Signed 2022-06-30 2022-06-29 2022-08-18 2022-08-10 2022-09-08 2022-08-18 2022-10-13 2023-10-13 ant Selection 5 Consultants) MD-PSA-302258-CS-INDV / L ocal Consultant for Spatial D Land Administration System Individual Consult IDA / 63060 Post Open 0.00 Signed 2022-06-30 2023-01-16 2022-08-18 2023-01-04 2022-09-08 2023-01-24 2022-10-13 2023-10-13 ata Harmonization for the Ro Strengthening ant Selection ads (ToR's revised and appro ved through email) MD-PSA-302886-CS-INDV / In dividual Consultants for Valu Individual Consult Under Implement IDA / 63060 Property Valuation Post Open 0.00 2022-07-08 2022-07-06 2022-08-26 2022-09-16 2022-10-21 2023-06-30 ation Infrastructure Develop ant Selection ation ment (2 consultants) MD-PSA-312129-CS-INDV / Q uality Control digital archive Land Administration System Individual Consult Under Implement IDA / 63060 Post Open - National 0.00 2022-08-26 2022-08-26 2022-10-17 2022-11-07 2022-12-12 2023-06-10 consultant (local, 2 persons f Strengthening ant Selection ation or Digitization nr.3) MD-PSA-319411-CS-INDV / Q Individual Consult Under Implement uality Assurance Consultant ( IDA / 63060 First Property Registration Post Open - National 0.00 2022-10-06 2022-09-16 2022-11-24 2023-01-04 2022-12-15 2023-01-17 2023-01-19 2023-07-18 ant Selection ation 5 Consultants) MD-PSA-319415-CS-INDV / In dividual consultant for the ex Individual Consult IDA / 63060 First Property Registration Post Open - National 0.00 Canceled 2022-10-06 2022-11-24 2022-12-15 2023-01-19 2023-07-18 ecution of massive cadastral ant Selection works (8 consultants) MD-PSA-320634-CS-INDV / C onsultant who will provide tr Individual Consult aining services in the field of IDA / 63060 First Property Registration Post Open - National 0.00 Signed 2022-10-14 2022-10-13 2022-11-04 2022-11-21 2022-11-08 2022-12-01 2022-11-30 2023-11-30 ant Selection application of the Geographic al Information System QGIS ( advanced module) MD-PSA-320636-CS-INDV / C onsultant who will provide tr Individual Consult aining services in the field of IDA / 63060 First Property Registration Post Open - National 0.00 Signed 2022-10-14 2022-10-13 2022-11-04 2022-11-21 2022-11-08 2022-12-01 2022-12-04 2023-12-04 ant Selection application of Geographical I nformation System QGIS (be ginner module) MD-PSA-326784-CS-INDV / Q Individual Consult uality Assurance Consultant ( IDA / 63060 First Property Registration Post Open - National 0.00 Signed 2022-11-17 2022-11-17 2022-12-23 2022-12-23 2023-01-13 2023-01-13 2023-02-17 2023-12-31 ant Selection 5 Consultants) MD-PSA-328254-CS-INDV / C ollection of market data and Individual Consult IDA / 63060 Property Valuation Post Open - National 0.00 Signed 2022-11-24 2022-11-24 2022-12-29 2023-01-27 2023-01-19 2023-02-08 2023-02-23 2023-12-31 real property evaluation Con ant Selection sultant (7 local consultants). MD-PSA-330637-CS-INDV / L Individual Consult ocal specialist in market data IDA / 63060 Property Valuation Post Open - National 0.00 Signed 2022-12-09 2022-12-22 2023-01-11 2023-03-06 2023-02-01 2023-03-17 2023-03-08 2024-03-07 ant Selection analysis (2 Consultants) MD-PSA-330645-CS-INDV / L Individual Consult ocal specialist in geospatial i IDA / 63060 Property Valuation Post Open - National 0.00 Signed 2022-12-08 2022-12-23 2023-01-26 2023-02-02 2023-02-16 2023-02-10 2023-03-23 2024-03-22 ant Selection nformation systems MD-PSA-338333-CS-CDS / Pr Capacity Building and Projec IDA / 63060 Post Direct Selection Direct - National 0.00 Signed 2023-01-27 2023-01-26 2023-01-29 2023-01-11 2023-03-02 2023-11-20 oject Audit Services for 2022 t Management Page 8 MD-PSA-341923-CS-INDV / In dividual Consultant to Develo Individual Consult IDA / 63060 Property Valuation Post Open - National 0.00 Canceled 2023-02-13 2023-02-13 2023-04-11 2023-05-02 2023-06-06 2024-06-05 p the Technical Specification ant Selection s for Automated Information System MD-PSA-344381-CS-CDS / Tr aining of the department spe Direct - Internation Under Implement IDA / 63060 Property Valuation Post Direct Selection 0.00 2023-02-24 2023-02-24 2023-03-06 2023-02-02 2023-05-10 2023-09-07 cialists on the: "Mathematica al ation l modeling and economic ana lysis" MD-PSA-349124-CS-CDS / Lo Land Administration System cal Consultant for Spatial Dat IDA / 63060 Post Direct Selection Direct - National 0.00 Signed 2023-03-16 2023-03-16 2023-03-23 2023-03-13 2023-04-30 2024-04-29 Strengthening a Harmonization for the Soils MD-PSA-350306-CS-INDV / C ollection of market data and Individual Consult Under Implement IDA / 63060 Property Valuation Post Open - National 0.00 2023-03-17 2023-03-17 2023-04-20 2023-04-30 2023-05-20 2024-05-19 real property evaluation Con ant Selection ation sultant (5 local consultants). MD-PSA-357629-CS-INDV / C onsultant for development a Individual Consult Under Implement nd testing of the methodolog IDA / 63060 Property Valuation Post Open - National 0.00 2023-04-21 2023-05-03 2023-05-30 2023-06-14 2023-07-15 2024-06-30 ant Selection ation y of real estate valuation mo dels for taxation purposes MD-PSA-358878-CS-INDV / In dividual Consultant for the co Individual Consult Under Implement IDA / 63060 First Property Registration Post Open - National 0.00 2023-05-01 2023-05-03 2023-06-09 2023-06-19 2023-07-20 2024-06-24 ordination of activities in the ant Selection ation process of delimitation of pu blic property MD-PSA-361053-CS-INDV / C Land Administration System Individual Consult Under Implement onsultant for Spatial Data Ha IDA / 63060 Post Open - National 0.00 2023-05-15 2023-05-16 2023-06-05 2023-06-10 2023-06-15 2024-06-14 Strengthening ant Selection ation rmonization for the Hydrogra phy MD-PSA-363711-CS-CDS / IN DIVIDUAL CONSULTANT (hea d of the team) for the develo Under Implement IDA / 63060 Property Valuation Post Direct Selection Direct - National 0.00 2023-05-26 2023-05-29 2023-06-05 2023-05-31 2023-07-09 2024-05-04 pment of a valuation method ation ology of complex commercial and industrial real estate MD-PSA-363713-CS-CDS / 3 I ndividual Consultants (team Under Implement members) for the developme IDA / 63060 Property Valuation Post Direct Selection Direct - National 0.00 2023-05-26 2023-05-29 2023-06-05 2023-06-13 2023-07-09 2024-05-04 ation nt of a valuation methodolog y of complex commercial and industrial real estate MD-PSA-363714-CS-CDS / In dividual Consultant (team lea der) for the development of t Under Implement IDA / 63060 Property Valuation Post Direct Selection Direct - National 0.00 2023-05-29 2023-05-30 2023-06-08 2023-05-31 2023-07-12 2024-05-07 he methodology and models ation for the assessment of agricul tural land for taxation purpos es MD-PSA-365864-CS-INDV / Q Individual Consult Pending Impleme IDA / 63060 First Property Registration Post Open - National 0.00 2023-06-08 2023-07-12 2023-07-22 2023-08-15 2024-06-30 uality Assurance Consultant ant Selection ntation MD-PSA-367318-CS-INDV / C Individual Consult Pending Impleme oordinator for Valuation (Co IDA / 63060 Property Valuation Post Open - National 0.00 2023-06-16 2023-07-07 2023-07-12 2023-07-31 2024-05-31 ant Selection ntation mponent B in LRPVP) Page 9 Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: December, 2016 2. Date of General Procurement Notice: 3. Period covered by this procurement plan: Jan 2017 to June 2018 II. Goods, Works, Consultant and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Prior Review Comments Threshold (PRT) US$ (Millions) 1. Works (Including turnkey, supply & 5 High risk installation of plant and equipment and PPP) 2. (Goods; Information Technology & 1.5 High risk Non-Consulting Services) 3. Consultant Services (Firms) 0.5 High risk 4. Consultant Services (Individual 0.2 High risk Consultants) 2. Prequalification. NA 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: Available in Project files 5. Any Other Special Procurement Arrangements: NA 6. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 7. All TORs for the procurement of consultants services irrespective of the estimated cost of the assignment shall be reviewed and cleared by the TTL 8. Operating expenditures are neither subject to the Procurement and Consultant Guidelines nor prior or post reviews. Operating expenditures are normally verified by TTLs and FM specialists and obtained using the Borrower’s national procurement and administrative procedures. January 11, 2018 9. Renewal or extension of individual consultant’s contracts hired for technical assistance and which are intended for a long-term period but signed for an initial period shorter than the duration of the project, and that have been prior reviewed, do not require procurement clearance if there is no substantial change in the terms and conditions of the contract. January 11, 2018 PROCUREMENT Kenya : Kenya Climate Smart Agriculture Project PLAN General Information Country: Kenya 2019-10-01 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P154784 GPN Date: 2018-02-08 Project Name: Kenya Climate Smart Agriculture Project Loan / Credit No: IDA / 59450 Siaya County Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component 4: Project Coordi KE-SIAYA COUNTY-148235-C nation and Management (US Request for Quota Single Stage - One E 2019-07-3 IDA / 59450 Post Limited 24,272.00 24,380.57 Completed 2019-05-02 2019-05-02 2019-06-04 2019-06-20 W-RFQ / Renovation of Office $29.3 million equivalent, of tions nvelope 1 which IDA US$20.0 million e quivalent) Component 1: Upscaling Cli KE-SIAYA COUNTY-153256-C mate-Smart Agricultural Pra Request for Quota Single Stage - One E 2019-11-0 W-RFQ / Rehabilitation of Mir IDA / 59450 Post Limited 86,981.00 80,691.66 Completed 2019-03-13 2019-03-13 2019-05-08 2019-04-02 ctices (US$163.8 million equ tions nvelope 4 uka Water Pan ivalent, of which IDA US$150 .0 million eq uivalent) Component 1: Upscaling Cli SYA/KCSAP/CPCU/RFQ/001/2 mate-Smart Agricultural Pra Request for Quota Single Stage - One E 2020-10-0 019 - 2020 / Proposed Rehabi IDA / 59450 Post Limited 151,128.00 146,751.70 Completed 2020-04-24 2020-04-24 2020-06-08 2020-09-24 ctices (US$163.8 million equ tions nvelope 6 litation of Kamola Water Pan ivalent, of which IDA US$150 .0 million eq uivalent) Component 1: Upscaling Cli SYA/KCSAP/CPCU/RFQ/002/2 mate-Smart Agricultural Pra Request for Quota Single Stage - One E 2020-10-0 019 - 2020 / Proposed Rehabi IDA / 59450 Post Limited 124,236.00 114,503.31 Completed 2020-04-24 2020-04-24 2020-06-08 2020-09-30 ctices (US$163.8 million equ tions nvelope 6 litation of Ogenga Water Pan ivalent, of which IDA US$150 .0 million eq uivalent) SYA/KCSAP/CPCU/RFQ/004/2 Component 1: Upscaling Cli 019-2020 / Proposed Improv mate-Smart Agricultural Pra Request for Quota Single Stage - One E 2020-09-0 IDA / 59450 Post Limited 156,390.00 0.00 Canceled 2020-04-24 2020-04-24 2020-06-08 ement Works at Kamariga O ctices (US$163.8 million equ tions nvelope 6 mena Drying Plant ivalent, of which IDA US$150 .0 million eq uivalent) KE-SIAYA COUNTY-201837-C Component 1: Upscaling Cli W-RFQ / Proposed Constructi mate-Smart Agricultural Pra Single Stage - One E 2021-04-2 IDA / 59450 Post Request for Bids Limited 210,000.00 179,351.43 Completed 2020-11-20 2020-11-18 2020-11-27 2020-11-19 2020-12-11 2020-12-02 2020-12-16 2020-12-11 2020-12-21 2020-12-18 on of Kamariga Omena Dryin ctices (US$163.8 million equ nvelope 0 g Project ivalent, of which IDA US$150 .0 million eq uivalent) Component 1: Upscaling Cli KE-SIAYA COUNTY-153253-C mate-Smart Agricultural Pra Request for Quota Single Stage - One E 2019-11-0 W-RFQ / Rehabilitation of Ad IDA / 59450 Post Limited 81,162.00 76,588.66 Completed 2019-03-13 2019-03-13 2019-05-08 2019-04-02 ctices (US$163.8 million equ tions nvelope 4 hiri Water Pan ivalent, of which IDA US$150 .0 million eq uivalent) KE-SIAYA COUNTY-282054-C W-RFQ / Construction of Nurs Component 1: Upscaling Cli ery sheds for propagation of mate-Smart Agricultural Pra Request for Quota tree seedlings for environme Request for Quota Single Stage - One E 2022-07-1 IDA / 59450 ctices (US$163.8 million equ Post Limited tions (Non Bank-S 24,545.90 0.00 Completed 2022-03-23 2022-05-20 2022-04-20 ntal conservation , installatio tions nvelope 9 ivalent, of which IDA US$150 PD) n of Chlorine Doser water dis .0 million eq uivalent) pensers for provision of clean water for domestic use , wat er tanks for irrigation KE-SIAYA COUNTY-283178-C Component 1: Upscaling Cli W-RFB / REHABILITATION OF Request for Bids - mate-Smart Agricultural Pra ONG'IYO (KOGOLA) WATER P Single Stage - One E Small Works SPD 2022-11-0 IDA / 59450 ctices (US$163.8 million equ Post Request for Bids Open - National 584,723.40 375,783.20 Signed 2022-03-31 2022-05-17 2022-04-22 2022-05-20 2022-05-22 2022-06-17 2022-06-21 2022-06-27 2022-07-12 2022-07-02 AN OF CAPACITY 35,000 CU nvelope (1 envelope proce 9 ivalent, of which IDA US$150 BIC METERS, IN AKOKO VILLA ss) .0 million eq uivalent) GE, WEST MIGWENA SUB-LO CATION, SOUTH SAKWA WAR D, KE-SIAYA COUNTY-283444-C W-RFB / REHABILITATION AN Component 1: Upscaling Cli Request for Bids - D EXPANSION OF ACHAR WA mate-Smart Agricultural Pra Single Stage - One E Small Works SPD Under Imple 2022-11-1 TER PAN, 42,000 CUBIC MET IDA / 59450 ctices (US$163.8 million equ Post Request for Bids Open - National 300,518.00 0.00 2022-03-31 2022-05-17 2022-04-22 2022-05-20 2022-05-22 2022-06-17 2022-06-21 2022-06-21 2022-07-19 nvelope (1 envelope proce mentation 6 ERS IN OKELA VILLAGE, WES ivalent, of which IDA US$150 ss) T KATWENG'A SUB-LOCATIO .0 million eq uivalent) N , NORTH UYOMA WARD, R ARIEDA SUB - COUNTY, SIAYA COUNTY KE-SIAYA COUNTY-283447-C W-RFB / REHABILITATION AN Component 1: Upscaling Cli D EXPAMSION OF TINGA AGE Request for Bids - mate-Smart Agricultural Pra GE WATER PAN WITH A CAP Single Stage - One E Small Works SPD 2022-11-0 IDA / 59450 ctices (US$163.8 million equ Post Request for Bids Open - National 264,266.00 0.00 Signed 2022-03-31 2022-05-17 2022-04-22 2022-05-20 2022-05-22 2022-06-17 2022-06-21 2022-06-21 2022-07-12 ACITY OF 43, 500 CUBIC MET nvelope (1 envelope proce 9 ivalent, of which IDA US$150 ERS, IN MITURI VILLAGE, EAS ss) .0 million eq uivalent) T KATWENG'A SUB-LOCATIO N, NORTH UYOMA WARD, RA RIEDA SUB - COUNTY, SIAYA COUNTY KE-SIAYA COUNTY-283450-C Component 1: Upscaling Cli W-RFB / REHABILITATION OF Request for Bids - mate-Smart Agricultural Pra NYANDONG' WATER PAN , WI Single Stage - One E Small Works SPD 2022-11-0 IDA / 59450 ctices (US$163.8 million equ Post Request for Bids Open - National 207,244.67 0.00 Completed 2022-03-31 2022-05-17 2022-04-22 2022-05-20 2022-05-22 2022-06-17 2022-06-21 2022-06-21 2022-07-12 TH A CAPCAITY OF 43,000 CU nvelope (1 envelope proce 9 ivalent, of which IDA US$150 BIC METERS, IN NORTH SAK ss) .0 million eq uivalent) WA WARD, BONDO SUB-COU NTY, SIAYA COUNTY KE-SIAYA COUNTY-283453-C W-RFB / REHABILITATION OF Component 1: Upscaling Cli Request for Bids - PANYAKO WATER PAN , WITH mate-Smart Agricultural Pra Single Stage - One E Small Works SPD 2023-01-0 A CAPACITY OF 42,00 CUBIC IDA / 59450 ctices (US$163.8 million equ Post Request for Bids Open - National 292,344.00 0.00 Completed 2022-03-31 2022-05-17 2022-04-22 2022-05-20 2022-05-22 2022-06-17 2022-06-21 2022-06-21 2022-07-12 nvelope (1 envelope proce 8 METERS, IN WEST UYOMA W ivalent, of which IDA US$150 ss) ARD , RARIEDA SUB - COUNT .0 million eq uivalent) Y, WITH A CAPACITY OF 14,0 00 BENEFICIARIES KE-SIAYA COUNTY-292891-C W-RFQ / Construction of Nurs Component 1: Upscaling Cli ery sheds for propagation of mate-Smart Agricultural Pra Request for Quota tree seedlings for environme Request for Quota Single Stage - One E 2022-09-2 IDA / 59450 ctices (US$163.8 million equ Post Limited tions (Non Bank-S 27,959.80 0.00 Completed 2022-05-11 2022-05-20 2022-07-01 ntal conservation , installatio tions nvelope 9 ivalent, of which IDA US$150 PD) n of Chlorine Doser water dis .0 million eq uivalent) pensers for provision of clean water for domestic use , wat er tanks for irrigation , Miruk a Eearth Dam KE-SIAYA COUNTY-302507-C Component 1: Upscaling Cli W-RFQ / CONSTRUCTION OF mate-Smart Agricultural Pra Request for Quota Request for Quota Single Stage - One E Under Imple 2022-11-1 NURSERY SHEDS & INSTALLA IDA / 59450 ctices (US$163.8 million equ Post Limited tions (Non Bank-S 55,477.63 0.00 2022-07-12 2023-02-13 2022-08-16 tions nvelope mentation 4 TION OF WATER TANKS AND ivalent, of which IDA US$150 PD) CATCHMENT PROTECTION FO .0 million eq uivalent) R NYADONG' WATER PAN. Page 1 KE-SIAYA COUNTY-302503-C Component 1: Upscaling Cli W-RFQ / CONSTRUCTION OF mate-Smart Agricultural Pra Request for Quota Request for Quota Single Stage - One E 2022-11-1 NURSERY SHEDS & INSTALLA IDA / 59450 ctices (US$163.8 million equ Post Limited tions (Non Bank-S 47,152.93 0.00 Canceled 2022-07-12 2022-08-16 tions nvelope 4 TION OF WATER TANKS AND ivalent, of which IDA US$150 PD) CATCHMENT FOR PANYAKO .0 million eq uivalent) WATER PAN. KE-SIAYA COUNTY-302496-C Component 1: Upscaling Cli W-RFQ / PROPOSED CONSTR mate-Smart Agricultural Pra Request for Quota UCTION OF NURSERY SHEDS Request for Quota Single Stage - One E 2022-11-1 IDA / 59450 ctices (US$163.8 million equ Post Limited tions (Non Bank-S 41,341.01 0.00 Canceled 2022-07-12 2022-08-16 & INSTALLATION OF WATER T tions nvelope 4 ivalent, of which IDA US$150 PD) ANKS AND CATCHMENT PROT .0 million eq uivalent) ECTION FOR AGEGE WATER P AN. KE-SIAYA COUNTY-302525-C Component 1: Upscaling Cli W-RFQ / CONSTRUCTION OF mate-Smart Agricultural Pra Request for Quota Request for Quota Single Stage - One E 2022-11-1 NURSERY SHEDS & INSTALLA IDA / 59450 ctices (US$163.8 million equ Post Limited tions (Non Bank-S 107,547.32 0.00 Canceled 2022-07-12 2022-08-16 tions nvelope 4 TION OF WATER TANKS AND ivalent, of which IDA US$150 PD) CATCHMENT PROTECTIION F .0 million eq uivalent) OR KOGOLA WATER PAN KE-SIAYA COUNTY-302490-C Component 1: Upscaling Cli W-RFQ / PROPOSED CONSTR mate-Smart Agricultural Pra Request for Quota Request for Quota Single Stage - One E 2022-11-1 UCTION OF NURSERY SHEDS IDA / 59450 ctices (US$163.8 million equ Post Limited tions (Non Bank-S 34,474.66 0.00 Canceled 2022-07-12 2022-08-16 tions nvelope 4 & INSTALLATION OF WATER T ivalent, of which IDA US$150 PD) ANKS AND CATCHMENT FOR .0 million eq uivalent) ACHAR WATER PAN. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Upscaling Cli KE-SIAYA COUNTY-136482-G mate-Smart Agricultural Pra Single Stage - One E O-RFB / procurement of Com IDA / 59450 Post Request for Bids Open - National 500,000.00 0.00 Canceled 2019-10-21 2019-10-01 2019-10-26 2019-11-25 2019-10-01 2019-12-09 2020-01-06 2020-02-05 ctices (US$163.8 million equ nvelope puters ivalent, of which IDA US$150 .0 million eq uivalent) Component 1: Upscaling Cli KE-SIAYA COUNTY-136636-G mate-Smart Agricultural Pra Single Stage - One E O-RFB / Purchase of Compute IDA / 59450 Post Request for Bids Open - National 500,000.00 0.00 Canceled 2019-10-21 2019-10-26 2019-11-25 2019-12-09 2020-01-06 2020-02-05 ctices (US$163.8 million equ nvelope rs ivalent, of which IDA US$150 .0 million eq uivalent) Component 4: Project Coordi KE-SIAYA COUNTY-142478-G nation and Management (US Request for Quota Single Stage - One E O-RFQ / Purchase of Office Fu IDA / 59450 Post Limited 24,272.00 23,466.97 Completed 2019-06-10 2019-06-10 2019-06-24 2019-06-22 2019-07-24 2019-07-25 $29.3 million equivalent, of tions nvelope rniture which IDA US$20.0 million e quivalent) SYA/KCSAP/CPCU/RFQ/003/2 Component 1: Upscaling Cli 019 - 2020 / Procurement for mate-Smart Agricultural Pra Single Stage - One E IDA / 59450 Post Request for Bids Limited 155,042.00 142,935.57 Completed 2020-04-13 2020-04-13 2020-04-24 2020-04-24 2020-05-24 2020-06-09 2020-06-03 2020-07-10 2020-06-08 2020-10-01 2020-10-06 Fish Drying Machine and Rela ctices (US$163.8 million equ nvelope ted Equipment for Kamariga ivalent, of which IDA US$150 Omena Drying Plant .0 million eq uivalent) KE-SIAYA COUNTY-233546-G Component 1: Upscaling Cli O-RFQ / Procurement for Mot mate-Smart Agricultural Pra Request for Quota Single Stage - One E IDA / 59450 Post Limited 40,500.00 34,973.65 Completed 2021-05-20 2021-05-21 2021-06-11 2021-10-07 2021-12-08 2022-04-01 or Cycles to be used in the fi ctices (US$163.8 million equ tions nvelope eld for farmer follow ups ivalent, of which IDA US$150 .0 million eq uivalent) KE-SIAYA COUNTY-247771-G Component 1: Upscaling Cli O-RFQ / Procurement for Pro mate-Smart Agricultural Pra Request for Quota Single Stage - One E Under Imple IDA / 59450 Post Limited 22,581.00 0.00 2021-08-24 2021-09-03 2021-09-07 2021-11-06 pagation Materials for Adhiri ctices (US$163.8 million equ tions nvelope mentation Water Pan ivalent, of which IDA US$150 .0 million eq uivalent) KE-SIAYA COUNTY-247776-G Component 1: Upscaling Cli O-RFQ / Procurement for Pro mate-Smart Agricultural Pra Request for Quota Single Stage - One E Under Imple IDA / 59450 Post Limited 22,581.00 0.00 2021-08-24 2021-09-03 2021-09-07 2021-11-06 pagation Materials for Miruka ctices (US$163.8 million equ tions nvelope mentation Water Pan ivalent, of which IDA US$150 .0 million eq uivalent) KE-SIAYA COUNTY-282083-G O-RFQ / Supply of Low press ure petrol engine Portable wa Component 1: Upscaling Cli ter Pumps for Adhiri and Mir mate-Smart Agricultural Pra uka water pan Request for Quota Single Stage - One E Under Imple IDA / 59450 ctices (US$163.8 million equ Post Limited 1,317.45 0.00 2022-03-23 2022-05-20 2022-04-20 2022-06-19 2NO. 6 to 8HP, 2" Dia, Inlet a tions nvelope mentation ivalent, of which IDA US$150 nd Outlet with matching pipe .0 million eq uivalent) couplings 4 - 6m Non- Collapsible sucti on pipes 23m Max. delivery , 200m de livery pipe, 2" Dia , KE-SIAYA COUNTY-292893-G Component 1: Upscaling Cli O-RFQ / Electronic digital wei mate-Smart Agricultural Pra ghing scale machine 300kg T Request for Quota Single Stage - One E Under Imple IDA / 59450 ctices (US$163.8 million equ Post Limited 18,529.60 0.00 2022-05-11 2022-05-20 2022-07-01 2022-08-30 cs 6No. tions nvelope mentation ivalent, of which IDA US$150 Moisture Metre Tk 100s Mod .0 million eq uivalent) el Aflatoxin Rapid Kit Manual Knapsack sprayer 16l KE-SIAYA COUNTY-292916-G ts Component 1: Upscaling Cli O-RFQ / training brochures 1 mate-Smart Agricultural Pra Request for Quota Single Stage - One E 000 copies IDA / 59450 ctices (US$163.8 million equ Post Limited 1,536.44 0.00 Completed 2022-05-11 2022-05-20 2022-07-01 2022-08-30 2022-09-11 tions nvelope marketing brochures 1000 co ivalent, of which IDA US$150 pies .0 million eq uivalent) Rectangular banners 6 No. Tear Drops 3 No. KE-SIAYA COUNTY-312714-G O-RFQ / Supply and pitching(i Component 1: Upscaling Cli nstallation) of signposts for mate-Smart Agricultural Pra Request for Quota Single Stage - One E Under Imple micro/sub project phase 2,3 IDA / 59450 ctices (US$163.8 million equ Post Limited 49,608.72 0.00 2022-09-10 2023-03-13 2022-10-15 2022-11-14 tions nvelope mentation and Supply of project brande ivalent, of which IDA US$150 d T-Shirts & Shirts (project br .0 million eq uivalent) anded materials/merchandis e) for publicity and visibility purposes. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-SIAYA COUNTY-322051-N Component 1: Upscaling Cli C-DIR / PROCUREMENT OF M mate-Smart Agricultural Pra Under Imple IDA / 59450 Post Direct Selection Direct - National 6,722.68 0.00 2022-10-18 2022-10-28 2022-10-23 2022-10-28 2022-11-13 2023-02-11 SHAMBA SERVICES UNDER D ctices (US$163.8 million equ mentation AT PROGRAMME ivalent, of which IDA US$150 .0 million eq uivalent) CONSULTING FIRMS Page 2 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Upscaling Cli KE-SIAYA COUNTY-137105-C mate-Smart Agricultural Pra Quality And Cost- S-QCBS / Provision of farmer' IDA / 59450 Prior Open - National 25,800.00 0.00 Canceled 2019-10-01 2019-10-22 2019-10-29 2019-10-30 2019-11-24 2019-12-03 2019-12-05 2020-12-04 ctices (US$163.8 million equ Based Selection s training services ivalent, of which IDA US$150 .0 million eq uivalent) Component 1: Upscaling Cli KE-SIAYA COUNTY-143388-C mate-Smart Agricultural Pra Quality And Cost- S-QCBS / Contracted Service IDA / 59450 Post Open - National 250,485.00 233,373.19 Signed 2019-04-19 2019-04-25 2019-05-09 2020-02-19 2019-05-31 2019-05-16 2019-06-25 2019-06-25 2019-07-30 2019-07-30 2019-08-27 2019-08-27 2019-12-02 2019-12-03 2020-12-01 ctices (US$163.8 million equ Based Selection Providers ivalent, of which IDA US$150 .0 million eq uivalent) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 PROCUREMENT PLAN (Textual Part) Project information: Papua New Guinea, Project Preparation Grant (PPG) Improving Access to and Value from Health Services (IMPACT Health), P-167184 Project Implementation agency: National Department of Health Date of the Procurement Plan: February 18, 2020 Period covered by this Procurement Plan: February 2020 to December 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the National Procurement Act 2018, No. 12 of 2018, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. National preferences Eligibility: Eligibility to participate in a procurement process for and to be awarded a Bank financed contract shall be as defined under paragraphs 3.21-3.23 of the Procurement Regulations; accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in the said paragraphs. Foreign bidders shall be eligible to participate in bidding under the same conditions as national bidders. No domestic preference shall be granted in bid evaluation on the basis of bidder’s nationality, origin of goods or services, and/or preferential programs. Registration of bidders as Registration of bidders: condition for bidding Registration shall not be used to assess bidders’ qualifications. A foreign bidder shall not be required to register as a condition for submitting its bid, and a foreign bidder recommended for contract award shall be given a reasonable opportunity to register, with the reasonable cooperation of the Recipient, prior to contract signing. Procurement documents Procurement Documents: Templates of procurement documents, including contract forms, acceptable to the Association shall be used for all procurement financed by the Project. Document Fees Bidding Document Fees: A fee for bidding documents if applied must be reasonable and is to be used to offset the actual costs associated with reproduction of large bidding documents and associated plans and drawings. It is not to be used to generate revenue, or to limit or restrict participation in procurement processes. Bidding document fees are not to be charged for the procurement of consulting services (firms and individual), non-consulting services, or goods. Fraud and Corruption Fraud and Corruption: The procurement documents shall require that bidders submitting bids present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. Negotiations and Cancellation of all bids: cancellation of All bids (or the sole bid if only one bid is procurement process received) shall not be rejected, the procurement process shall not be cancelled, and new bids shall not be solicited without the Bank’s prior written concurrence. Complaints Handling Complaints Review Mechanism: The Recipient shall establish and implement an effective, fair and timely complaints review mechanism allowing bidders to complain and to have their complaints handled in a timely manner. Until an adequate complaints review mechanism (as assessed by the Bank) is established the Bank’s review mechanism as set out in the Procurement Regulations will apply. Contract Award Notice Publication of Contract Award Notice: For purposes of Article 36(5) of the Act, within one month from award, a notice of all procurement contract awards shall include, at a minimum as relevant and applicable for each procurement method (a) the name of each bidder that submitted a bid; (b) bid prices as read out at bid opening; (c) evaluated prices of each bid that was evaluated; (d) the names of bidders whose bids were either rejected as nonresponsive or not meeting qualification criteria, or not evaluated, with the reasons thereof; and (e) the name of the winning bidder, the final total contract price, as well as the duration and a summary of the scope of the contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. The above captioned conditions also apply when approaching the international market. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable Works: is not applicable PROCUREMENT Papua New Guinea : Improving Access to and Value from Health Services in PNG: Financing the Frontlines PLAN General Information Country: Papua New Guinea 2020-02-17 Bank’s Approval Date of the Original Procurement Plan: 2023-05-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167184 GPN Date: 2022-04-27 Project Name: Improving Access to and Value from Health Services in PNG: Financing the Frontlines Loan / Credit No: TF / B0956, IDA / 64970 National Department of Health Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-NDOH-116194-GO-RFQ / Component 3: Project mana Request for Quota Single Stage - One E Purchase of computers, print TF / B0956 Post Open - National 7,934.40 Completed 2020-05-22 2020-07-17 2021-07-10 2020-09-30 2021-11-02 gement tions nvelope ers, cell phones and internet connectivity PG-NDOH-116192-GO-RFQ / Component 3: Project mana Request for Quota Single Stage - One E TF / B0956 Post Open - National 64,809.00 Terminated 2020-05-22 2020-07-17 2020-07-18 2020-09-30 Purchase of two project vehic gement tions nvelope les PG-NDOH-231210-GO-RFQ / Purchase of 1x SUV for Progr Component 3: Project mana Request for Quota Single Stage - One E am Coordinator and 1x 4WD IDA / 64970 Post Open - National 70,498.57 Signed 2021-04-28 2021-06-23 2021-05-12 2021-12-20 gement tions nvelope Double Cab to support admin istration for Impact Health Pr oject PG-NDOH-261038-GO-RFQ / Component 3: Project mana Request for Quota Single Stage - One E Vehicle Tracking System for t IDA / 64970 Post Limited 1,943.13 Signed 2021-11-13 2021-09-13 2021-12-03 2022-08-02 2022-12-03 gement tions nvelope wo Project Vehicles PG-NDOH-338779-GO-RFQ / Component 1: Increase servi Request for Quota Single Stage - One E Pending Impl Video Conferencing System IDA / 64970 ce delivery readiness and co Post Limited 0.00 2023-02-08 2023-04-05 2023-10-02 tions nvelope ementation with conferencing table mmunity-based service deliv ery PG-NDOH-338788-GO-RFQ / Component 3: Project mana Request for Quota Single Stage - One E IDA / 64970 Post Limited 0.00 Signed 2023-02-08 2023-02-09 2023-04-05 2023-10-02 Laptops gement tions nvelope NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-NDOH-161338-NC-RFB / Component 1: Increase servi Health Facility Survey includi ce delivery readiness and co Open - Internationa Single Stage - One E TF / B0956 Post Request for Bids 0.00 Canceled 2020-06-01 2020-06-06 2020-07-18 2020-08-17 2020-09-21 2021-03-20 ng design, testing and condu mmunity-based service deliv l nvelope cting baseline survey ery CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-NDOH-175562-CS-QCBS / Component 2: Improve frontl Quality And Cost- Open - Internationa TF / B0956 Prior 0.00 Canceled 2020-05-25 2020-06-05 2020-06-15 2020-06-08 2020-07-29 2020-08-26 2020-09-25 2020-10-30 2020-12-04 2025-12-31 Independent Verification Age ine service delivery perform Based Selection l nt ance PG-NDOH-306791-CS-QCBS / Component 2: Improve frontl Independent Verification Age Quality And Cost- Open - Internationa Under Implement IDA / 64970 ine service delivery perform Prior 0.00 2022-08-05 2022-08-03 2022-08-26 2022-08-15 2022-11-09 2022-12-09 2023-01-08 2023-03-09 2023-04-13 2025-12-31 nt (IVA) to verify reported res Based Selection l ation ance ults against which DLIs will b e paid INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-NDOH-116183-CS-INDV / Component 3: Project mana Individual Consult TF / B0956 Post Open 274,478.11 Completed 2020-04-01 2020-03-29 2020-05-20 2020-07-07 2020-06-10 2020-07-13 2020-07-15 2020-07-24 2020-12-31 2022-10-08 Program Coordinator gement ant Selection Component 1: Increase servi PG-NDOH-116186-CS-INDV / Individual Consult TF / B0956 ce delivery readiness and co Post Open 0.00 Signed 2020-04-19 2021-04-06 2020-06-07 2022-11-22 2020-06-28 2022-12-20 2020-08-02 2020-12-31 Communications Officer ant Selection mmunity-based service deliv ery PG-NDOH-116180-CS-INDV / Component 1: Increase servi Individual Consult Monitoring and evaluation (M TF / B0956 ce delivery readiness and co Post Open 267,044.00 Signed 2020-04-19 2020-06-19 2020-06-07 2020-10-29 2020-06-28 2021-02-15 2020-08-02 2021-03-29 2020-12-31 ant Selection &E) specialist to support M&E mmunity-based service deliv activities ery PG-NDOH-116185-CS-INDV / Component 3: Project mana Individual Consult TF / B0956 Post Open 0.00 Canceled 2020-05-08 2020-06-26 2020-07-17 2020-08-21 2020-12-31 Administrative Assistant gement ant Selection PG-NDOH-116188-CS-INDV / Component 3: Project mana Individual Consult TF / B0956 Post Open 222,797.00 Signed 2020-05-08 2020-06-18 2020-06-26 2020-09-10 2020-07-17 2019-09-17 2020-08-21 2020-09-24 2020-12-31 Financial Management Speci gement ant Selection alist PG-NDOH-160928-CS-CDS / Component 3: Project mana TF / B0956 Post Direct Selection Direct 236,770.00 Signed 2020-03-02 2020-03-30 2020-03-12 2020-04-25 2020-04-17 2020-05-03 2020-12-27 Procurement Specialist gement PG-NDOH-192641-CS-INDV / Component 3: Project mana Individual Consult Procurement and Administrat TF / B0956 Post Open 68,788.16 Signed 2020-09-11 2020-09-09 2020-10-15 2022-06-02 2020-10-20 2022-06-02 2020-10-30 2022-06-28 2020-12-31 gement ant Selection ion Officer Page 1 PG-NDOH-226542-CS-INDV / Component 2: Improve frontl Individual Consult Individual Consultant for Disb TF / B0956 ine service delivery perform Post Open 0.00 Canceled 2021-04-05 2021-03-29 2021-05-20 2021-06-10 2021-07-15 2021-09-13 ant Selection ursement Linked Indicators ( ance DLI) Verification PG-NDOH-180872-CS-INDV / Development of a Project Op Component 3: Project mana Individual Consult TF / B0956 Post Open 0.00 Canceled 2020-06-19 2020-06-19 2020-08-07 2020-08-28 2020-10-02 2021-03-31 erations Manual and Emerge gement ant Selection ncy Operations Manual PG-NDOH-255240-CS-INDV / Component 3: Project mana Individual Consult IDA / 64970 Post Open 0.00 Terminated 2021-11-01 2021-10-06 2021-12-20 2023-01-24 2022-01-10 2023-01-25 2022-01-20 2026-06-30 Assistant Accounts Officer gement ant Selection PG-NDOH-279932-CS-INDV / Environmental, Social, Health Component 3: Project mana Individual Consult Under Implement IDA / 64970 Post Limited 0.00 2022-02-28 2022-03-21 2022-03-05 2023-06-03 2022-03-26 2022-04-30 2026-06-30 , Safety and Community Eng gement ant Selection ation agement Specialist PG-NDOH-292143-CS-INDV / Component 3: Project mana Individual Consult Under Implement IDA / 64970 Post Open 0.00 2022-05-09 2022-04-27 2022-07-19 2022-08-09 2022-09-13 2026-06-13 Deputy Program Coordinator gement ant Selection ation PG-NDOH-292144-CS-INDV / Component 3: Project mana Individual Consult IDA / 64970 Post Limited 0.00 Terminated 2022-05-20 2022-06-05 2022-05-30 2022-12-15 2022-06-20 2023-01-24 2022-07-25 2026-04-24 Accounts Officer gement ant Selection PG-NDOH-325519-CS-INDV / Component 3: Project mana Individual Consult IDA / 64970 Post Direct - National 0.00 Signed 2022-11-11 2022-11-10 2022-11-20 2022-11-11 2022-11-25 2022-11-15 2022-12-05 2023-03-31 Program Coordinator gement ant Selection PG-NDOH-328544-CS-INDV / Component 3: Project mana Individual Consult Under Implement IDA / 64970 Prior Open - National 0.00 2022-12-02 2022-12-06 2023-01-20 2023-02-10 2023-03-17 2026-06-30 Program Coordinator gement ant Selection ation PG-NDOH-350911-CS-CDS / I Component 2: Improve frontl ndependent Verification Age Under Implement IDA / 64970 ine service delivery perform Post Direct Selection Direct - National 0.00 2023-03-27 2023-03-21 2023-04-06 2023-05-01 2023-12-31 nt (IVA) to verify Years 1 and ation ance 2 Disbursement Linked Indic ators (DLI) PG-NDOH-363736-CS-INDV / Component 3: Project mana Individual Consult Under Implement IDA / 64970 Post Limited 0.00 2023-06-02 2023-06-07 2023-06-07 2023-06-28 2023-08-02 2026-06-30 Accounts Officer gement ant Selection ation PG-NDOH-363737-CS-INDV / Component 3: Project mana Individual Consult Under Implement IDA / 64970 Post Limited 0.00 2023-06-02 2023-06-07 2023-06-07 2023-06-28 2023-08-02 2026-06-30 Assistant Accounts Officer gement ant Selection ation Page 2 SUMMARY O F PROCUREMENT PLAN Project Preparation Advancement (PPA) Project information: Harmonizing and Improving Statistics in West Africa Project -P169265 Project Implementation agency: Liberia Institute of Statistics and Geo- Information Services (LISGIS) Date of the Procurement Plan: February 3, 2020 Period covered by this Procurement Plan: 3rd February to 31st July 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 1, 2016), revised in November 2017, and August 2018 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement and Concessions Act, 2010 of the Republic of Liberia, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable for those contracts identified in the Procurement Plan tables; Works: Not Applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not Applicable. Other Relevant Procurement Information: - (a). Prior Procurement Arrangements: The Procurement Arrangements as indicated in the below table and within the thresholds indicated in the below tables will be used. The thresholds for the Bank’s prior review requirements are also provided in the table below: Table: Thresholds*, Procurement Arrangements, and Prior Review (The table below depicts the Thresholds and Procurement Methods to be used under the Regional Project for Statistics Thresholds*, Procurement Methods, and Prior Review Contract (C) Value Expenditure Procurement Contracts Subject to No Threshold* [eq. Category Method Prior Review /[eq. US$] USD] All contracts at or above USD Open Competition 5,000,000 are subject to International Market 1 Works C ≥ 5,000,000 Approach and Direct international advertising and the use of the Bank’s SPDs (or other Contracting documents agreed with the Contract (C) Value Expenditure Procurement Contracts Subject to No Threshold* [eq. Category Method Prior Review /[eq. US$] USD] Bank). Open Competition National Market 200,000 < C < 5,000,000 None Approach C ≤ 200,000 RfQ None All contracts at or above USD Open Competition 500,000 are subject to International Market international advertising and the C ≥ 500,000 Approach and Direct use of the Bank’s SPDs (or other Goods, IT and Contracting documents agreed with the 2 non-consulting Bank). services Open Competition 100,000 < C < 500,000 National Market None Approach C ≤ 100,000 RfQ None All contracts at or above USD 100,000 are subject to for international advertising and the C < 100,000 Consulting Services use of the Bank’s SPDs (or other National documents agreed with the shortlist for Bank). 3 selection of All contracts at or above USD consultant firms for 200,000 are subject to Engineering and international advertising and the C ≤ 200,000 Construction use of the Bank’s SPDs (or other Supervision documents agreed with the Bank). Selection of All values ≥ 100,000 4 Individual All Approaches consultants Training, This line activity is not subject to Workshops, Based on approved Procurement Review However, 5 Study Tours All Values Annual Work Plan & each of the activities will be Budgets (AWPB) by TTL cleared with the TTL prior to its implementation. (Special procurement arrangements like direct contracting, use of SOEs, UN Agencies, third party monitors, local NGOs, Force Account, servants needs, results based arrangements. It is not expected that there will be need for prequalification in the procurement arrangements under this Regional Project *These thresholds are for the purposes of the initial procurement plan for the PPA and for first 18 months. The thresholds will be revised periodically based on re- assessment of risks. All contracts not subject to prior review will be post-reviewed. Prequalification. Not expected for the packages of works/goods packages in the procurement plan. Proposed Procedures for CDD Components: Not Applicable Reference to (if any) Project Operational/Procurement Manual: The LISGIS Project Management Team will prepare Procurement manuals. The Procurement Plan will also form part of the Project Implementation Manual. Any Other Special Procurement Arrangements: None Procurement Packages/PLAN with Procurement Arrangements and Time Schedule: as per the Table below: b) PROCUREMENT PLAN Works There are no works under the Project Preparation Advance Goods and Non-Consulting Services 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procurement Prequ Nation Revie Expecte Expecte Comment No. (Description) Cost Method alifica al w d bid d s US$ tion Prefer by opening Contrac (yes/n ence Bank date t o) (yes/n (Prior Signatu o) / Post) re Date 1 Procurement of 4 12,100 laptops, 3 No. all- in-1 printers, Limited, RFQ No No Post 28 Feb 4 Mar office desks, a 20 20 projector, metal filing cabinet, and stationery and supplies for project management Consultancy Services 1 2 3 4 5 6 7 8 9 Ref. Description of Estimate Selection Review Expecte Expected Expected Comments No. Assignment d Method/ by Bank d date Contract Completi Cost in Arrangem (Prior / of Signatur on US$ ent Post) proposal e Date submissi Date on 1. Recruitment of a Consultant to draft and validate 10,000 INDV Post 16 Mar 10 Apr 23 Apr ToR to be curricula of the 20 20 20 submitted to IDA Statistics degree & for Review and No CEST Program at Objection. the UL 2. Recruitment of a ToR, performance Financial evaluation, draft Management contract and Officer for Project DS Prior 10 Feb 21 Feb 31 Aug minutes of Management 20 20 20 contract negotiation to be submitted to IDA for Review and No 15,600 Objection. 3. ToR, performance evaluation, draft Recruitment of a contract and Procurement DS Prior 10 Feb 21 Feb 31 Aug minutes of Specialist for 20 20 20 contract Project 18,000 negotiation to be Management submitted to IDA for Review and No Objection. Training and Workshop (Training & Workshop activities are subject to TTL clearance). Estimat Estimated Expected Ref. Training, workshop and ed Cost Duration Training/workshop No. study tours in (Days) Date (US$) Conduct of validation 54,000 workshop and TOT for the GP Feb. 20 to March 1. on the design of 13 2020 questionnaires and enumeration training manual Workshop for cartographic 150,000 Feb. 24 to March 2. field staff training 16 2020 Workshop for enumeration 113,900 3. mapping training April 15, 2020 Study Tours to regional 32,000 countries for first-hand experience on regional March to April 4. harmonization of data 2020 collection, management and communication Workshops on current 50,000 administrative data across 5. April to July 2020 MACs and LISGIS regional offices Workshop to strengthen and 35,000 6. develop institutional capacity April to July 2020 of NSO Workshops for steering 40,000 7. committee on Administrative April to July 2020 Data Workshop for Project 10,000 Steering/Technical 8. Committees for annual work February 2020 plan preparation, review and validation GENERAL NOTES 1. Training and capacity building: Training workshops (including training material and support), conference attendance and study tours, will be carried out based on approved annual training and allied activities plan by the TTL. The beneficiaries, after the training, will be requested to submit a brief report indicating what skills have been acquired and how these skills will contribute to enhance their performance and contribute to the attainment of the Project’s development objective. 2. Operational Costs: These are expenditures incurred by the Recipient to finance: (i) communication technology (including, without limitation, internet and telephone; (ii) per diem and travel expenses of the operational staff performing their responsibilities under the Project; (iii) fuel and vehicle maintenance; (iv) maintenance of equipment; (v) photocopies and publications; (viii) bank commissions; and (ix) utilities and office supplies as defined in the FA. Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Western and Central Africa : Harmonizing and Improving Statistics in West Africa PLAN General Information Country: Western and Central Africa 2020-09-01 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169265 GPN Date: 2021-05-19 Project Name: Harmonizing and Improving Statistics in West Africa Loan / Credit No: IDA / 65740 Unidade de Gestao de Projectos Especiais Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Regional component: Harmo 06/UGPE/HISWA/2021 / Purc nization, Data Collection, Qu hase of ICT Equipment’s for t Open - Internationa Single Stage - One E Under Imple IDA / 65740 ality Improvement, Dissemin Post Request for Bids 300,000.00 0.00 2021-08-01 2022-06-30 2021-08-06 2022-06-30 2021-09-17 2022-08-11 2021-10-17 2022-10-21 2021-11-21 2022-05-20 he National Statistical Syste l nvelope mentation ation and Use of Core Social m (NSS) and Economic Statistics Regional component: Harmo 08/UGPE/HISWA/2021 / Purc nization, Data Collection, Qu Single Stage - One E hase of equipment (Electroni IDA / 65740 ality Improvement, Dissemin Post Request for Bids Open - National 140,000.00 112,076.65 Signed 2021-09-13 2022-04-05 2021-09-18 2021-10-30 2022-05-23 2021-11-29 2022-06-27 2022-01-03 2022-08-05 2022-07-02 nvelope c System Infrastructure) ation and Use of Core Social and Economic Statistics Regional component: Harmo 09/UGPE/HISWA/2021 / Purc nization, Data Collection, Qu Request for Quota Single Stage - One E hase of ICT Equipment’s for I IDA / 65740 ality Improvement, Dissemin Post Limited 90,000.00 46,866.50 Signed 2021-09-08 2021-09-13 2021-11-03 2021-12-14 2022-05-02 tions nvelope Mar ation and Use of Core Social and Economic Statistics Regional component: Harmo 20/UGPE/HISWA/2022 / Purc nization, Data Collection, Qu hase of weight balance for IV Request for Quota Single Stage - One E IDA / 65740 ality Improvement, Dissemin Post Open - National 9,500.00 0.00 Signed 2022-08-02 2022-09-27 2023-03-26 Household Expenditure and I tions nvelope ation and Use of Core Social ncome Survey and Economic Statistics Regional component: Harmo 037/UGPE/HISWA/2022 / Acq nization, Data Collection, Qu Request for Quota Single Stage - One E uisition of covid-19 kit for fiel IDA / 65740 ality Improvement, Dissemin Post Open - National 27,000.00 0.00 Signed 2022-08-22 2022-10-17 2023-04-15 tions nvelope d agents ation and Use of Core Social and Economic Statistics Regional component: Harmo 038/UGPE/HISWA/2022 / Pur nization, Data Collection, Qu chase of ICT Equipment’s for Request for Quota Single Stage - One E IDA / 65740 ality Improvement, Dissemin Post Open - National 70,000.00 0.00 Signed 2022-08-29 2022-10-24 2023-04-22 Completion of the Mindelo La tions nvelope ation and Use of Core Social nd Registry Operation and Economic Statistics Regional component: Harmo 040/UGPE/HISWA/2022 / Acq nization, Data Collection, Qu uisition of Furniture Equipme Request for Quota Single Stage - One E IDA / 65740 ality Improvement, Dissemin Post Open - National 90,000.00 0.00 Signed 2022-09-05 2022-10-31 2023-04-29 nt for Completion of the Mind tions nvelope ation and Use of Core Social elo Land Registry Operation. and Economic Statistics Regional component: Harmo 05/UGPE/HISWA/2021 / Purc nization, Data Collection, Qu Open - Internationa Single Stage - One E Pending Impl hase of Equipment for Health IDA / 65740 ality Improvement, Dissemin Post Request for Bids 200,000.00 0.00 2023-10-25 2023-10-30 2023-12-11 2024-01-10 2024-02-14 2024-08-12 l nvelope ementation Infrastructure ation and Use of Core Social and Economic Statistics NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Regional component: Harmo 16/UGPE/HISWA/2021 / Grap nization, Data Collection, Qu hic Materials, Audiovisuals an Request for Quota Single Stage - One E IDA / 65740 ality Improvement, Dissemin Post Limited 30,000.00 10,791.14 Signed 2022-01-16 2022-01-07 2022-03-13 2022-02-01 2022-09-09 d Clothing for the General Sp tions nvelope ation and Use of Core Social orts Census and Economic Statistics Regional component: Harmo 018/UGPE/HISWA/2022 / Pro nization, Data Collection, Qu duction of Audiovisuals Mater Request for Quota Single Stage - One E IDA / 65740 ality Improvement, Dissemin Post Limited 10,000.00 0.00 Signed 2022-08-31 2022-08-22 2022-10-26 2023-04-24 ials for IV Household Expendi tions nvelope ation and Use of Core Social ture and Income Survey and Economic Statistics 19/UGPE/HISWA/2022 / Prod Regional component: Harmo uction of graphic materials, c nization, Data Collection, Qu Request for Quota Single Stage - One E lothing and gifts for IV House IDA / 65740 ality Improvement, Dissemin Post Limited 100,000.00 0.00 Signed 2022-09-04 2022-09-06 2022-10-30 2023-04-28 tions nvelope hold Expenditure and Income ation and Use of Core Social Survey and Economic Statistics Regional component: Harmo 22/UGPE/HISWA/2022 / Printi nization, Data Collection, Qu ng service for IV Household E Request for Quota Single Stage - One E Under Imple IDA / 65740 ality Improvement, Dissemin Post Limited 28,000.00 0.00 2022-09-04 2022-11-11 2022-10-30 2023-04-28 xpenditure and Income Surve tions nvelope mentation ation and Use of Core Social y and Economic Statistics 23/UGPE/HISWA/2022 / Grap hic Materials, Audiovisuals, S Regional component: Harmo pot and Clothing for i) livesto nization, Data Collection, Qu Request for Quota Single Stage - One E ck survey, ii) National Survey IDA / 65740 ality Improvement, Dissemin Post Limited 40,000.00 0.00 Signed 2022-08-03 2022-09-23 2022-09-28 2023-03-27 tions nvelope on Food and Nutritional Vuln ation and Use of Core Social erability, iii) Annual survey o and Economic Statistics n non-irrigated crops and iv) Irrigated Crops Survey Page 1 Regional component: Harmo 036/UGPE/HISWA/2022 / Diff nization, Data Collection, Qu usion of spot for IV Househol Request for Quota Single Stage - One E Pending Impl IDA / 65740 ality Improvement, Dissemin Post Limited 25,000.00 0.00 2022-08-22 2022-10-17 2023-04-15 d Expenditure and Income Su tions nvelope ementation ation and Use of Core Social rvey and Economic Statistics 41/UGPE/HISWA/2022 / Car Regional component: Harmo Rental Service for the IV IDRF nization, Data Collection, Qu Request for Quota Single Stage - One E - Municipalities of Ribeira Gra IDA / 65740 ality Improvement, Dissemin Post Open - National 100,000.00 0.00 Signed 2022-11-27 2023-01-22 2023-07-21 tions nvelope nde, Paúl and Porto Novo - S ation and Use of Core Social anto Antão Island and Economic Statistics 42/UGPE/HISWA/2022 / Car Regional component: Harmo Rental Service for the IV IDRF nization, Data Collection, Qu Request for Quota Single Stage - One E - Municipalities of Ribeira Bra IDA / 65740 ality Improvement, Dissemin Post Open - National 70,000.00 0.00 Signed 2022-11-28 2023-01-23 2023-07-22 tions nvelope va and Tarrafal – São Nicolau ation and Use of Core Social Island and Economic Statistics 43/UGPE/HISWA/2022 / Car Regional component: Harmo Rental Service for the IV IDRF nization, Data Collection, Qu Request for Quota Single Stage - One E - Municipalities of Mosteiros, IDA / 65740 ality Improvement, Dissemin Post Open - National 100,000.00 0.00 Canceled 2022-11-29 2023-01-24 2023-07-23 tions nvelope São Filipe and Santa Catarina ation and Use of Core Social – Fogo Island and Economic Statistics 44/UGPE/HISWA/2022 / Car Regional component: Harmo Rental Service for the IV IDRF nization, Data Collection, Qu Request for Quota Single Stage - One E - Municipalities of São Salvad IDA / 65740 ality Improvement, Dissemin Post Open - National 100,000.00 0.00 Signed 2022-11-29 2023-01-24 2023-07-23 tions nvelope or do Mundo, São Domingos ation and Use of Core Social and São Lourenço dos Órgão and Economic Statistics s – Santiago Island 45/UGPE/HISWA/2022 / Car Regional component: Harmo Rental Service for the IV IDRF nization, Data Collection, Qu Request for Quota Single Stage - One E - Municipalities of Tarrafal an IDA / 65740 ality Improvement, Dissemin Post Open - National 70,000.00 0.00 Signed 2022-11-29 2023-01-24 2023-07-23 tions nvelope d São Miguel – Santiago Islan ation and Use of Core Social d and Economic Statistics 46/UGPE/HISWA/2022 / Car Regional component: Harmo Rental Service for the IV IDRF nization, Data Collection, Qu Request for Quota Single Stage - One E - Municipalities of Santa Cruz IDA / 65740 ality Improvement, Dissemin Post Open - National 70,000.00 0.00 Signed 2022-11-29 2023-01-24 2023-07-23 tions nvelope and Santa Catarina – Santia ation and Use of Core Social go Island and Economic Statistics Regional component: Harmo 47/UGPE/HISWA/2022 / Car nization, Data Collection, Qu Rental Service for the IV IDRF Request for Quota Single Stage - One E IDA / 65740 ality Improvement, Dissemin Post Open - National 33,500.00 0.00 Signed 2022-11-29 2023-01-24 2023-07-23 - Municipalities of Ribeira Gra tions nvelope ation and Use of Core Social nde – Santiago Island and Economic Statistics Regional component: Harmo 48/UGPE/HISWA/2022 / Car nization, Data Collection, Qu Request for Quota Single Stage - One E Rental Service for the IV IDRF IDA / 65740 ality Improvement, Dissemin Post Open - National 70,000.00 0.00 Signed 2022-11-29 2023-01-24 2023-07-23 tions nvelope – Sal and Boavista Islands ation and Use of Core Social and Economic Statistics Regional component: Harmo 50/UGPE/HISWA/2022 / Rent nization, Data Collection, Qu Request for Quota Single Stage - One E al Service for the IV IDRF – S IDA / 65740 ality Improvement, Dissemin Post Open - National 70,000.00 0.00 Signed 2022-11-29 2023-01-24 2023-07-23 tions nvelope ão Vicente Island ation and Use of Core Social and Economic Statistics Regional component: Harmo 51/UGPE/HISWA/2022 / Rent nization, Data Collection, Qu Request for Quota Single Stage - One E al Service for the IV IDRF – M IDA / 65740 ality Improvement, Dissemin Post Open - National 33,500.00 0.00 Signed 2022-11-29 2023-01-24 2023-07-23 tions nvelope aio Island ation and Use of Core Social and Economic Statistics Regional component: Harmo 49/UGPE/HISWA/2022 / Car nization, Data Collection, Qu Request for Quota Single Stage - One E Rental Service for the IV IDRF IDA / 65740 ality Improvement, Dissemin Post Open - National 33,500.00 0.00 Canceled 2022-11-29 2023-01-24 2023-07-23 tions nvelope –Brava Island ation and Use of Core Social and Economic Statistics 43/UGPE/HISWA/2022-2 / Pre Regional component: Harmo stação de Serviço de Aluguer nization, Data Collection, Qu de Viaturas Para o IV Inquérit Request for Quota Single Stage - One E Under Imple IDA / 65740 ality Improvement, Dissemin Post Open - National 100,000.00 0.00 2023-02-15 2023-04-12 2023-10-09 o às Despesas e Receitas Fa tions nvelope mentation ation and Use of Core Social miliares (IDRF): Municípios d and Economic Statistics e Mosteiros, de São Filipe e d e Santa Catarina – Ilha do Fo go Regional component: Harmo 49/UGPE/HISWA/2022-2 / Ca nization, Data Collection, Qu Request for Quota Single Stage - One E r Rental Service for the IV ID IDA / 65740 ality Improvement, Dissemin Post Limited 33,500.00 0.00 Signed 2023-03-21 2023-03-23 2023-05-16 2023-11-12 tions nvelope RF –Brava Island ation and Use of Core Social and Economic Statistics Regional component: Harmo 029/UGPE/HISWA/2022 / Gra nization, Data Collection, Qu phic Materials, Audiovisuals, Request for Quota Single Stage - One E Pending Impl IDA / 65740 ality Improvement, Dissemin Post Limited 10,000.00 0.00 2023-08-21 2023-10-16 2024-04-13 spot and Clothing for dissemi tions nvelope ementation ation and Use of Core Social nation census data and Economic Statistics Regional component: Harmo 12/UGPE/HISWA/2021 / Com nization, Data Collection, Qu Request for Quota Single Stage - One E Pending Impl munication/divulgation electr IDA / 65740 ality Improvement, Dissemin Post Limited 25,000.00 0.00 2024-04-02 2024-05-28 2024-11-24 tions nvelope ementation onic billing System ation and Use of Core Social and Economic Statistics 13/UGPE/HISWA/2021 / PRO Regional component: Harmo DUCTION OF AUDIOVISUAL A nization, Data Collection, Qu Request for Quota Single Stage - One E ND COMMUNICATION MATERI IDA / 65740 ality Improvement, Dissemin Post Limited 30,000.00 0.00 Canceled 2021-11-13 2022-01-08 2022-07-07 tions nvelope ALS FOR THE V GENERAL FIS ation and Use of Core Social HERIES CENSUS and Economic Statistics Regional component: Harmo 061/UGPE/HISWA/2023 / Pro nization, Data Collection, Qu duction of Audiovisuals Mater Request for Quota Single Stage - One E Under Imple IDA / 65740 ality Improvement, Dissemin Post Open - National 7,000.00 0.00 2023-06-17 2023-08-12 2024-02-08 ials for IV IDRF Methodologic tions nvelope mentation ation and Use of Core Social al Experimental Survey and Economic Statistics 062/UGPE/HISWA/2023 / Pro Regional component: Harmo duction of graphic materials, nization, Data Collection, Qu Request for Quota Single Stage - One E Under Imple clothing and gifts for IV IDRF IDA / 65740 ality Improvement, Dissemin Post Open - National 7,000.00 0.00 2023-06-20 2023-08-15 2024-02-11 tions nvelope mentation Methodological Experimental ation and Use of Core Social Survey and Economic Statistics Page 2 Regional component: Harmo 063/UGPE/HISWA/2023 / Car nization, Data Collection, Qu Rental Services for the IV IDR Request for Quota Single Stage - One E Pending Impl IDA / 65740 ality Improvement, Dissemin Post Open - National 40,000.00 0.00 2023-06-20 2023-08-15 2024-02-11 F Methodological Experiment tions nvelope ementation ation and Use of Core Social al Survey and Economic Statistics Regional component: Harmo 064/UGPE/HISWA/2023 / Car nization, Data Collection, Qu Request for Quota Single Stage - One E Under Imple Rental Services for the Baseli IDA / 65740 ality Improvement, Dissemin Post Open - National 70,000.00 0.00 2023-06-19 2023-08-14 2024-02-10 tions nvelope mentation ne LFS + Informal Sector ation and Use of Core Social and Economic Statistics 065/UGPE/HISWA/2023 / Pro Regional component: Harmo duction of Audiovisuals Mater nization, Data Collection, Qu Request for Quota Single Stage - One E Under Imple ials for the Baseline LFS + Inf IDA / 65740 ality Improvement, Dissemin Post Open - National 10,000.00 0.00 2023-06-21 2023-08-16 2024-02-12 tions nvelope mentation ormal Sector and Enterprise ation and Use of Core Social census. and Economic Statistics 066/UGPE/HISWA/2023 / Pro Regional component: Harmo duction of graphic materials nization, Data Collection, Qu Request for Quota Single Stage - One E Under Imple and clothing for the Baseline IDA / 65740 ality Improvement, Dissemin Post Open - National 15,000.00 0.00 2023-06-25 2023-08-20 2024-02-16 tions nvelope mentation LFS + Informal Sector and En ation and Use of Core Social terprise census. and Economic Statistics CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Regional component: Harmo 04/UGPE/HISWA/2021 / Stre nization, Data Collection, Qu ngthening of Health Informati Quality And Cost- Open - Internationa IDA / 65740 ality Improvement, Dissemin Post 300,000.00 0.00 Canceled 2021-07-15 2021-09-29 2021-08-05 2021-10-20 2021-09-18 2022-03-01 2021-10-16 2022-04-12 2021-11-15 2021-12-20 2022-01-24 2023-01-24 on Systems and Electronic Pr Based Selection l ation and Use of Core Social escription and Economic Statistics 15/UGPE/HISWA/2021 / Acco unting and Financing audit D evelopment of Financial and Accounting Audits for the DIG Project Management and Mo Least Cost Selecti Open - Internationa Under Implement ITAL CABO VERDE PROJECT (I IDA / 65740 Post 45,000.00 0.00 2021-03-24 2021-04-01 2021-04-14 2021-05-28 2021-06-25 2021-07-25 2021-08-29 2021-10-03 2022-04-01 nitoring and Evaluation on l ation DA CREDITS Ref. V3050 and 6792-CV) and HARMONINZIN G AND IMPROVING STATISTIC S IN WEST AFRICA PROJECT (I DA CREDIT Ref. 6574-CV) 039/UGPE/HISWA/2022 / San Country-Specific Component Quality And Cost- Open - Internationa Under Implement tiago Island Land Registry Op IDA / 65740 : Improving and modernizing Prior 3,000,000.00 0.00 2022-08-31 2022-09-06 2022-09-21 2022-09-23 2022-11-04 2023-01-23 2022-12-02 2023-03-28 2023-01-01 2023-06-12 2023-02-05 2023-03-12 2024-03-11 Based Selection l ation eration physical and statistical infra structure Country-Specific Component 057/UGPE/HISWA/2023 / Trai Consultant Qualifi Under Implement IDA / 65740 : Improving and modernizing Post Open - National 15,000.00 0.00 2023-01-27 2023-02-08 2023-02-17 2023-04-02 2023-04-29 2023-05-02 2023-06-06 2023-12-03 ning in English for NSS cation Selection ation physical and statistical infra structure Regional component: Harmo 02/UGPE/HISWA/2021 / Impl nization, Data Collection, Qu Consultant Qualifi Pending Impleme ementation of the MASTERD IDA / 65740 ality Improvement, Dissemin Post Open - National 60,000.00 0.00 2023-07-18 2023-08-08 2023-09-21 2023-10-21 2023-11-25 2024-05-23 cation Selection ntation ATA-INE platform ation and Use of Core Social and Economic Statistics Regional component: Harmo nization, Data Collection, Qu 032UGPE/HISWA/2022 / Trai Consultant Qualifi IDA / 65740 ality Improvement, Dissemin Post Open - National 15,000.00 0.00 Canceled 2022-08-30 2022-09-20 2022-11-03 2022-12-03 2023-01-07 2023-07-06 ning in English for NSS cation Selection ation and Use of Core Social and Economic Statistics Regional component: Harmo nization, Data Collection, Qu 033/UGPE/HISWA/202 / Train Consultant Qualifi IDA / 65740 ality Improvement, Dissemin Post Open - National 10,000.00 0.00 Canceled 2022-08-10 2022-08-31 2022-10-14 2022-11-13 2022-12-18 2023-06-16 ing in French for NSS cation Selection ation and Use of Core Social and Economic Statistics Country-Specific Component 059/UGPE/HISWA/2023 / Trai Consultant Qualifi Pending Impleme IDA / 65740 : Improving and modernizing Post Open - National 10,000.00 0.00 2023-10-26 2023-11-16 2023-12-30 2024-01-29 2024-03-04 2024-08-31 ning in French for NSS cation Selection ntation physical and statistical infra structure 07/UGPE/HISWA/2021 / Draft Country-Specific Component Consultant Qualifi Pending Impleme ing and implementation of th IDA / 65740 : Improving and modernizing Post Open - National 50,000.00 0.00 2024-05-14 2024-06-04 2024-07-18 2024-08-17 2024-09-21 2025-03-20 cation Selection ntation e ICT Plan 2021-2025 physical and statistical infra structure 03/UGPE/HISWA/2021 / Deve Regional component: Harmo lopment of the single technol nization, Data Collection, Qu Quality And Cost- Open - Internationa Pending Impleme ogical platform of consolidat IDA / 65740 ality Improvement, Dissemin Post 250,000.00 0.00 2023-11-14 2023-12-05 2024-01-18 2024-02-15 2024-03-16 2024-04-20 2024-05-25 2025-05-25 Based Selection l ntation ed indicators of the National ation and Use of Core Social Statistical System(NSS) and Economic Statistics Regional component: Harmo 04/UGPE/HISWA/2021-2 / Str nization, Data Collection, Qu engthening of Health Informa Quality And Cost- Open - Internationa Under Implement IDA / 65740 ality Improvement, Dissemin Post 300,000.00 0.00 2023-06-06 2023-05-26 2023-06-27 2023-05-29 2023-08-10 2023-09-07 2023-10-07 2023-11-11 2023-12-16 2024-12-15 tion Systems and Electronic P Based Selection l ation ation and Use of Core Social rescription and Economic Statistics INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 01 UGPE HISWA 2020 / Recr Project Management and Mo Individual Consult IDA / 65740 Post Open 156,655.00 0.00 Canceled 2020-09-02 2020-09-01 2020-10-21 2020-11-20 2020-11-11 2020-12-16 2021-06-14 uitment of Project Manager nitoring and Evaluation ant Selection 01 UGPE HISWA 2021 / Recr Project Management and Mo Individual Consult IDA / 65740 Post Open 156,655.00 64,911.83 Signed 2021-01-08 2021-01-26 2021-02-26 2021-04-07 2021-03-19 2021-04-13 2021-04-23 2021-04-16 2021-10-20 uitment of Project Manager nitoring and Evaluation ant Selection Regional component: Harmo 14/UGPE/HISWA/2021 / Impr nization, Data Collection, Qu ovement of the "Happiness I IDA / 65740 ality Improvement, Dissemin Post Direct Selection Direct 90,000.00 0.00 Signed 2022-02-04 2022-02-04 2022-02-14 2022-02-18 2022-04-20 2022-10-17 nvoice" Raffle Platform ation and Use of Core Social and Economic Statistics Page 3 Regional component: Harmo 21/UGPE/HISWA/2022 / Recr nization, Data Collection, Qu uitment of two graduate tech Individual Consult IDA / 65740 ality Improvement, Dissemin Post Open - National 51,000.00 0.00 Signed 2022-07-26 2022-08-02 2022-09-13 2022-11-22 2022-10-04 2022-11-24 2022-11-08 2023-05-07 nicians for IV Household Exp ant Selection ation and Use of Core Social enditure and Income Survey and Economic Statistics Regional component: Harmo 028/UGPE/UGPE/2022 / Recr nization, Data Collection, Qu uitment of a Developer/Progr Individual Consult IDA / 65740 ality Improvement, Dissemin Post Open - National 50,000.00 0.00 Signed 2022-07-31 2022-08-01 2022-09-18 2022-11-24 2022-10-09 2022-11-24 2022-11-13 2023-05-12 ammer to Update the Survey ant Selection ation and Use of Core Social Management System and Economic Statistics Regional component: Harmo nization, Data Collection, Qu 034/UGPE/HISWA/2022 / Trai Individual Consult Pending Impleme IDA / 65740 ality Improvement, Dissemin Post Open - National 7,000.00 0.00 2022-08-30 2022-10-18 2022-11-08 2022-12-13 2023-06-11 ning in Sampling for NSS ant Selection ntation ation and Use of Core Social and Economic Statistics Regional component: Harmo 035/UGPE/HISWA/2022 / Trai nization, Data Collection, Qu Individual Consult Pending Impleme ning in advanced excel traini IDA / 65740 ality Improvement, Dissemin Post Open - National 7,000.00 0.00 2022-07-29 2022-09-16 2022-10-07 2022-11-11 2023-05-10 ant Selection ntation ng for NSS ation and Use of Core Social and Economic Statistics Regional component: Harmo 052/UGPE/HISWA/2023 / Rec nization, Data Collection, Qu Individual Consult Under Implement ruitment of two (2) IT Techni IDA / 65740 ality Improvement, Dissemin Post Open - National 27,000.00 0.00 2023-01-16 2023-01-30 2023-03-06 2023-03-27 2023-05-01 2023-10-28 ant Selection ation cians for INE ation and Use of Core Social and Economic Statistics Regional component: Harmo 054/UGPE/HISWA/2023 / Rec nization, Data Collection, Qu Individual Consult ruitment of three (3) Statistic IDA / 65740 ality Improvement, Dissemin Post Open - National 40,000.00 0.00 Signed 2023-01-17 2023-01-30 2023-03-07 2023-04-26 2023-03-28 2023-05-05 2023-05-02 2023-10-29 ant Selection al Technicians ation and Use of Core Social and Economic Statistics Regional component: Harmo 055/UGPE/HISWA/2023 / Rec nization, Data Collection, Qu Individual Consult Under Implement ruitment of an Economics an IDA / 65740 ality Improvement, Dissemin Post Open - National 13,000.00 0.00 2023-01-17 2023-01-30 2023-03-07 2023-03-28 2023-05-02 2023-10-29 ant Selection ation d Management Technician ation and Use of Core Social and Economic Statistics Regional component: Harmo 017/UGPE/HISWA/2022 / Tec nization, Data Collection, Qu hnical support to Strengtheni Individual Consult Pending Impleme IDA / 65740 ality Improvement, Dissemin Post Open - National 30,000.00 0.00 2023-08-31 2023-10-19 2023-11-09 2023-12-14 2024-06-11 ng Quality Management Syst ant Selection ntation ation and Use of Core Social em and Economic Statistics 060/UGPE/HISWA/2022 / Trai Country-Specific Component Individual Consult ning in advanced excel for N IDA / 65740 : Improving and modernizing Post Open - National 7,000.00 0.00 Canceled 2023-01-23 2023-03-13 2023-04-03 2023-05-08 2023-11-04 ant Selection SS physical and statistical infra structure Regional component: Harmo nization, Data Collection, Qu 056/UGPE/HISWA/2023 / Co Individual Consult Pending Impleme IDA / 65740 ality Improvement, Dissemin Post Open - National 20,000.00 0.00 2023-09-20 2023-11-08 2023-11-29 2024-01-03 2024-07-01 mputer Security Training ant Selection ntation ation and Use of Core Social and Economic Statistics 058/UGPE/HISWA/2023 / Trai Country-Specific Component Individual Consult Pending Impleme ning in Statistical Software (S IDA / 65740 : Improving and modernizing Post Open - National 10,000.00 0.00 2023-08-29 2023-10-17 2023-11-07 2023-12-12 2024-06-09 ant Selection ntation PSS) for NSS physical and statistical infra structure Regional component: Harmo 053/UGPE/HISWA/2023 / Rec nization, Data Collection, Qu Individual Consult ruitment of a Demographer f IDA / 65740 ality Improvement, Dissemin Post Open - National 13,000.00 0.00 Canceled 2023-01-17 2023-02-03 2023-03-07 2023-03-28 2023-05-02 2023-10-29 ant Selection or INE ation and Use of Core Social and Economic Statistics Regional component: Harmo 030/UGPE/HISWA/2022 / Trai nization, Data Collection, Qu Individual Consult Open - Internationa Pending Impleme ning in Statistical Software - IDA / 65740 ality Improvement, Dissemin Post 14,000.00 0.00 2023-11-12 2023-12-31 2024-01-21 2024-02-25 2024-08-23 ant Selection l ntation STATA for NSS ation and Use of Core Social and Economic Statistics Regional component: Harmo 11/UGPE/HISWA/2021 / Tech nization, Data Collection, Qu nical support to Strengthenin Individual Consult Pending Impleme IDA / 65740 ality Improvement, Dissemin Post Open - National 30,000.00 0.00 2024-04-17 2024-06-05 2024-06-26 2024-07-31 2025-01-27 g Quality Management Syste ant Selection ntation ation and Use of Core Social m and Economic Statistics 10/UGPE/HISWA/2021 / Prom Regional component: Harmo otion for Efficient use of Adm nization, Data Collection, Qu Individual Consult Pending Impleme inistrative Records and Capa IDA / 65740 ality Improvement, Dissemin Post Open - National 100,000.00 0.00 2024-03-18 2024-05-06 2024-05-27 2024-07-01 2024-12-28 ant Selection ntation city Building Sessions on Ad ation and Use of Core Social ministrative Records and Economic Statistics Regional component: Harmo 31/UGPE/HISWA/2022 / Train nization, Data Collection, Qu Individual Consult ing in Statistical Software (SP IDA / 65740 ality Improvement, Dissemin Post Open - National 10,000.00 0.00 Canceled 2022-08-30 2022-10-18 2022-11-08 2022-12-13 2023-06-11 ant Selection SS) for NSS ation and Use of Core Social and Economic Statistics Page 4 PROCUREMENT PLAN (Textual Part) Project information: [country] [Project name] [P-number] Project Implementation agency: [insert legal name] Date of the Procurement Plan: [insert date] Period covered by this Procurement Plan: [insert from – to period] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Mozambique : Northern Mozambique Rural Resilience Project PLAN General Information Country: Mozambique 2021-07-30 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174635 GPN Date: Project Name: Northern Mozambique Rural Resilience Project Loan / Credit No: IDA / 69320 ProAzul Blue Economy Promotion Fund Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-PROAZUL-245979-GO-RF Improving Management of N Single Stage - One E IDA / 69320 Post Request for Bids Open - National 800,000.00 0.00 Canceled 2021-08-15 2021-09-17 2021-08-20 2021-10-01 2021-10-31 2022-01-13 2022-07-12 B / Purchase of 2 Patrol Boats atural Resources nvelope MZ-PROAZUL-265177-GO-DI Improving Management of N R / Supply and delivery of 2 P IDA / 69320 Post Direct Selection Direct 375,000.00 374.18 Signed 2021-11-30 2021-11-16 2021-12-05 2021-09-17 2022-02-17 2022-01-13 2022-06-17 atural Resources atrol Boats for Fishery Inspec tion MZ-PROAZUL-277324-GO-RF Improving Management of N Request for Quota Single Stage - One E Q / Supply and delivery of tw IDA / 69320 Post Limited 40,000.00 61,026.95 Signed 2022-02-19 2022-02-17 2022-04-12 2022-03-05 2022-05-27 atural Resources tions nvelope o boat engines MZ-PROAZUL-245980-GO-RF Multi-stakeholder Coordinati Single Stage - One E Under Imple B / Purchase of miscellaneou IDA / 69320 Post Request for Bids Open - National 280,000.00 0.00 2022-10-31 2022-10-26 2022-11-05 2022-10-27 2022-12-17 2022-12-09 2023-01-16 2023-02-06 2023-03-31 2023-06-29 on and Project Management nvelope mentation s IT Equipment and Software MZ-PROAZUL-245990-GO-RF Multi-stakeholder Coordinati Single Stage - One E B / Office Furniture for Maput IDA / 69320 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2023-04-28 2023-05-03 2023-06-14 2023-07-14 2023-09-26 2023-12-25 on and Project Management nvelope o and Provinces MZ-PROAZUL-363918-GO-RF Improving Management of N Single Stage - One E Under Imple B / Purchase of Five (4X4) Do IDA / 69320 Post Request for Bids Open - National 238,095.00 0.00 2023-06-18 2023-06-08 2023-06-23 2023-06-08 2023-08-04 2023-09-03 2023-11-16 2024-02-14 atural Resources nvelope mentation uble Cabin Vehicles MZ-PROAZUL-364855-GO-RF Multi-stakeholder Coordinati Request for Quota Single Stage - One E Under Imple Q / Supply and delivery of off IDA / 69320 Post Limited 25,000.00 0.00 2023-06-17 2023-08-21 2023-09-20 on and Project Management tions nvelope mentation ice furniture for provincial as sistants MZ-PROAZUL-350011-GO-RF Improving Management of N Request for Quota Single Stage - One E Pending Impl IDA / 69320 Post Limited 95,000.00 0.00 2023-06-30 2023-08-25 2024-02-21 Q / Two double cabin 4X4 ve atural Resources tions nvelope ementation hicles NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-PROAZUL-245970-NC-RF P / Production and planting of Improving Management of N Request for Propo IDA / 69320 Prior Open - National Multi Stage 2,000,000.00 0.00 Canceled 2021-08-13 2021-08-18 2021-10-27 2022-02-08 2022-04-23 2027-04-22 mangrove seedlings includin atural Resources sals g training of covered commu nities MZ-PROAZUL-340316-NC-RF Improving Management of N Open - Internationa Single Stage - One E Under Imple B / Production and planting o IDA / 69320 Post Request for Bids 600,000.00 0.00 2023-03-31 2023-04-14 2023-04-05 2023-04-14 2023-05-17 2023-06-16 2023-08-29 2026-12-11 atural Resources l nvelope mentation f mangrove seedlings CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-PROAZUL-256931-CS-QC Improving Management of N Quality And Cost- BS / Implementation of Co-M IDA / 69320 Post Open - National 800,000.00 0.00 Canceled 2021-10-15 2021-11-15 2021-11-05 2021-11-23 2021-12-19 2022-01-16 2022-02-15 2022-03-22 2022-06-04 2026-06-03 atural Resources Based Selection anagement Initiatives at Lak e Niassa MZ-PROAZUL-277833-CS-QB Improving Management of N Quality Based Sel Under Implement S / Implementation of Co-Ma IDA / 69320 Post Open - National 800,000.00 0.00 2022-02-21 2022-02-10 2022-03-14 2022-02-14 2022-04-27 2022-04-21 2022-05-25 2022-05-24 2022-06-24 2022-09-23 2022-07-24 2022-08-28 2026-12-05 atural Resources ection ation nagement Initiatives at Lake Niassa MZ-PROAZUL-320294-CS-QC Improving Access to Liveliho BS / Promotion, training and Quality And Cost- IDA / 69320 ods and Community Infrastr Prior Open - National 600,000.00 0.00 Canceled 2022-10-31 2023-02-07 2022-11-21 2023-01-04 2023-02-01 2023-03-03 2023-04-07 2023-06-20 2026-06-19 evolution of community base Based Selection ucture d savings and revolving credi t (PCRs) groups MZ-PROAZUL-329811-CS-QC BS / Technical, Economical, S ocial and Environmental Feas Improving Access to Liveliho Quality And Cost- Under Implement ibility Study and Elaboration IDA / 69320 ods and Community Infrastr Post Open - National 350,000.00 0.00 2022-12-16 2023-03-25 2023-01-06 2023-02-19 2023-03-19 2023-04-18 2023-05-23 2023-08-05 2024-05-31 Based Selection ation of the Executive Project for t ucture he Construction of a Landing in Metangula , District of Lag o in Niassa. MZ-PROAZUL-277830-CS-QC BS / Technical, Economical, S ocial and Environmental Feas Improving Access to Liveliho Quality And Cost- ibility Study and Elaboration IDA / 69320 ods and Community Infrastr Post Open - National 300,000.00 0.00 Canceled 2022-02-21 2022-02-12 2022-03-14 2022-02-16 2022-04-27 2022-04-20 2022-05-25 2022-05-31 2022-06-24 2022-07-29 2022-10-11 2023-04-09 Based Selection of the Executive Project for t ucture he Construction of a Landin g in Metangula , District of La go in Niassa. Page 1 MZ-PROAZUL-349919-CS-QC BS / Assistance and develop Improving Access to Liveliho ment of community-based re Quality And Cost- Open - Internationa IDA / 69320 ods and Community Infrastr Prior 600,000.00 0.00 Under Review 2023-03-31 2023-03-24 2023-04-15 2023-04-05 2023-05-20 2023-06-10 2023-06-25 2023-07-30 2023-10-12 2026-10-11 volving savings and credit (P Based Selection l ucture CR) groups in . Nampula (Mogincual, Nacala Porto and Nacala-a-Velha dist ricts). INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-PROAZUL-245972-CS-IN Improving Access to Liveliho Individual Consult IDA / 69320 Post Open 50,000.00 0.00 Signed 2021-08-09 2021-08-16 2021-09-27 2022-08-17 2021-10-18 2022-03-08 2021-12-31 2024-12-30 DV / Business Plans Specialis ods and Community Infrastr ant Selection t1 ucture MZ-PROAZUL-245973-CS-IN Improving Access to Liveliho Individual Consult IDA / 69320 Post Open 50,000.00 0.00 Canceled 2021-08-10 2021-08-16 2021-09-28 2021-10-19 2022-01-01 2024-12-31 DV / Business Plans Specialis ods and Community Infrastr ant Selection t2 ucture MZ-PROAZUL-245977-CS-CD Multi-stakeholder Coordinati S / Monitoring and Evaluation IDA / 69320 Post Direct Selection Direct 113,500.00 90,000.00 Signed 2021-08-08 2021-08-14 2021-08-18 2021-08-23 2021-10-07 2021-09-17 2024-10-06 on and Project Management Assistant MZ-PROAZUL-245978-CS-IN Multi-stakeholder Coordinati Individual Consult IDA / 69320 Post Open 93,600.00 0.00 Signed 2021-08-11 2021-08-25 2021-09-29 2022-07-19 2021-10-20 2022-07-20 2022-01-02 2022-07-16 DV / Project Accountant on and Project Management ant Selection MZ-PROAZUL-245996-CS-IN Multi-stakeholder Coordinati Individual Consult IDA / 69320 Post Open 87,000.00 216,000.00 Signed 2021-08-16 2022-03-16 2021-10-04 2022-06-14 2021-10-25 2022-06-19 2022-01-07 2022-06-29 2022-04-22 DV / Communication Speciali on and Project Management ant Selection st MZ-PROAZUL-246002-CS-IN Multi-stakeholder Coordinati Individual Consult DV / Provincial Matching Gra IDA / 69320 Post Open 75,600.00 0.00 Signed 2021-08-17 2021-08-14 2021-10-05 2022-06-13 2021-10-26 2022-06-20 2022-01-08 2025-01-07 on and Project Management ant Selection nts Assistant for Nampula MZ-PROAZUL-246003-CS-IN Multi-stakeholder Coordinati Individual Consult DV / Provincial Matching Gra IDA / 69320 Post Open 75,600.00 0.00 Signed 2021-08-13 2021-08-14 2021-10-01 2022-06-12 2021-10-22 2022-07-19 2022-01-04 2025-01-03 on and Project Management ant Selection nts Assistant for Niassa MZ-PROAZUL-246004-CS-IN Multi-stakeholder Coordinati Individual Consult DV / Provincial Matching Gra IDA / 69320 Post Open 75,600.00 0.00 Signed 2021-08-12 2021-08-14 2021-09-30 2022-06-14 2021-10-21 2022-07-17 2022-01-03 2025-01-02 on and Project Management ant Selection nts Assistant for Cabo Delgad o MZ-PROAZUL-246006-CS-IN Multi-stakeholder Coordinati Individual Consult IDA / 69320 Post Open 75,600.00 0.00 Signed 2021-08-18 2021-08-26 2021-10-06 2022-07-12 2021-10-27 2022-07-12 2022-01-09 2025-01-08 DV / Safeguards Assistant for on and Project Management ant Selection Nampula MZ-PROAZUL-246007-CS-IN Multi-stakeholder Coordinati Individual Consult IDA / 69320 Post Open 75,600.00 0.00 Signed 2021-08-10 2021-08-26 2021-09-28 2022-07-12 2021-10-19 2022-07-01 2022-01-01 2024-12-31 DV / Safeguards Assistant for on and Project Management ant Selection Niassa MZ-PROAZUL-246009-CS-IN Multi-stakeholder Coordinati Individual Consult DV / Safeguards Assistant for IDA / 69320 Post Open 75,600.00 0.00 Signed 2021-08-10 2021-08-26 2021-09-28 2022-07-11 2021-10-19 2022-07-20 2022-01-01 2024-12-31 on and Project Management ant Selection Cabo Delgado MZ-PROAZUL-246010-CS-IN Multi-stakeholder Coordinati Individual Consult DV / Gender Issues Assistant IDA / 69320 Post Open 75,600.00 0.00 Signed 2021-08-18 2021-08-14 2021-10-06 2022-07-12 2021-10-27 2022-07-20 2022-01-09 2025-01-08 on and Project Management ant Selection for Nampula MZ-PROAZUL-245976-CS-IN Multi-stakeholder Coordinati Individual Consult IDA / 69320 Prior Open 113,508.00 100,800.00 Signed 2021-08-11 2021-08-19 2021-09-29 2022-03-22 2021-10-20 2022-03-23 2022-01-02 2022-07-20 2024-11-08 DV / Procurement Assistant on and Project Management ant Selection MZ-PROAZUL-247051-CS-CD Improving Access to Liveliho S / Coordinator of Matching G IDA / 69320 ods and Community Infrastr Prior Direct Selection Direct 315,000.00 293,633.24 Signed 2021-08-13 2022-01-24 2021-08-23 2022-02-02 2021-12-05 2022-03-04 2024-12-04 rants, Private Sector and Inn ucture ovation. MZ-PROAZUL-247055-CS-CD Multi-stakeholder Coordinati S / Human Resources and Ins IDA / 69320 Post Direct Selection Direct 189,216.00 189,000.00 Signed 2021-08-13 2021-08-14 2021-08-23 2021-08-23 2021-12-05 2021-09-17 2024-12-04 on and Project Management titutional Development Speci alist MZ-PROAZUL-248646-CS-IN Multi-stakeholder Coordinati Individual Consult DV / Technical Assistance in IDA / 69320 Post Open 234,000.00 270,000.00 Signed 2021-08-18 2021-08-25 2021-10-06 2022-03-16 2021-10-27 2022-03-07 2022-01-09 2022-03-09 2025-01-08 on and Project Management ant Selection Financial Management MZ-PROAZUL-264513-CS-CD Multi-stakeholder Coordinati IDA / 69320 Post Direct Selection Direct 87,500.00 15,600.00 Signed 2021-11-28 2021-12-02 2021-12-08 2022-03-27 2022-02-11 2021-12-18 2025-02-10 S / Data Base Assistant on and Project Management MZ-PROAZUL-278013-CS-CD Multi-stakeholder Coordinati IDA / 69320 Post Direct Selection Direct 51,000.00 90,187.18 Signed 2022-02-20 2022-02-14 2022-03-02 2022-03-27 2022-06-14 2022-03-28 2025-06-13 S / Sworn Translator Services on and Project Management MZ-PROAZUL-303419-CS-IN Multi-stakeholder Coordinati Individual Consult IDA / 69320 Post Open 31,200.00 0.00 Signed 2022-07-22 2022-07-16 2022-09-09 2022-10-28 2022-09-30 2022-11-28 2022-12-13 2024-12-12 DV / Junior planning assistant on and Project Management ant Selection MZ-PROAZUL-303422-CS-IN Multi-stakeholder Coordinati Individual Consult DV / Junior knowledge manag IDA / 69320 Post Open 31,200.00 0.00 Signed 2022-07-24 2022-07-16 2022-09-11 2022-11-16 2022-10-02 2023-01-09 2022-12-15 2024-12-14 on and Project Management ant Selection ement assistant MZ-PROAZUL-248626-CS-IN Improving Access to Liveliho Individual Consult IDA / 69320 Post Open 35,000.00 0.00 Canceled 2021-08-19 2022-03-16 2021-10-07 2021-10-28 2022-01-10 2025-01-09 DV / Business Plan Specialist ods and Community Infrastr ant Selection 3 ucture MZ-PROAZUL-245998-CS-IN Improving Management of N Individual Consult DV / Mangrove Assistant bas IDA / 69320 Post Open 68,400.00 0.00 Canceled 2022-07-27 2022-09-14 2022-10-05 2022-12-18 2025-12-17 atural Resources ant Selection ed in Pemba MZ-PROAZUL-245974-CS-IN Improving Management of N Individual Consult DV / Elaboration of Environm IDA / 69320 Post Open - National 100,000.00 0.00 Canceled 2022-12-22 2023-02-09 2023-03-02 2023-03-22 2025-03-21 atural Resources ant Selection ental and Social Managemen t Plans MZ-PROAZUL-317065-CS-IN Improving Management of N Individual Consult IDA / 69320 Post Open - National 198,000.00 0.00 Canceled 2022-10-26 2022-10-17 2022-12-14 2023-01-04 2023-03-19 2026-03-18 DV / Mangrove specialist atural Resources ant Selection MZ-PROAZUL-245975-CS-IN Improving Management of N Individual Consult IDA / 69320 Post Open 198,000.00 0.00 Canceled 2021-08-20 2022-02-10 2021-10-08 2022-06-10 2021-10-29 2022-01-11 2025-01-10 DV / Mangrove Specialist atural Resources ant Selection MZ-PROAZUL-334488-CS-CD Multi-stakeholder Coordinati IDA / 69320 Post Direct Selection Direct - National 31,200.00 0.00 Signed 2023-01-13 2023-01-17 2023-01-23 2022-10-25 2023-02-17 2025-02-16 S / Database Assistant on and Project Management Page 2 PROCUREMENT PLAN (Textual Part) Project information: Republic of North Macedonia Project Implementation Agency: Ministry of Agriculture, Forestry and Water Economy (MAFWE) Date of the Procurement Plan: May 2022 Period covered by this Procurement Plan: Duration of project Preamble: The Bank’s Procurement Framework (PF) effective as of July 1, 2016 will be governing procurement under the project. Procurement of contracts for goods, works non-consulting and consulting services financed from the project, will be carried out in accordance with the World Bank Procurement Regulations for Investment Project Financing (IPF) Borrowers – Procurement in IPF of Goods, Works, Non‐Consulting and Consulting Services, (Regulations) issued in July 2016, revised November 2017 and August 2018. The Bank’s Standard Procurement Documents (SPD) will be used as required by the Regulations. They are all accessible at www.worldbank.org/procurement In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. The General Procurement Notice (GPN) and all procurement notices for contracts following international market approach will be published in United Nations Development Business (UNDB) and on the World Bank’s external website through STEP. Procurement notices for contracts following national market approach will be published on the electronic system for public procurement, hosted by the Public Procurement Bureau at https://e-nabavki.gov.mk/PublicAccess/Home.aspx#/home, on the website of the MAFWE and/or in national newspapers with wide daily circulation. For international procedures the procurement notices will be published automatically through STEP on the Bank’s external website and UNDB, as well as locally on the Ministry’s website, daily newspaper as relevant PROCUREMENT North Macedonia : Agriculture Modernization Project PLAN General Information Country: North Macedonia 2022-05-10 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P168014 GPN Date: 2022-04-15 Project Name: Agriculture Modernization Project Loan / Credit No: IBRD / 90370 Ministry of Agriculture, Forestry and Water Economy Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AMP-RFQ-G-C3-8 / Purchase Request for Quota Single Stage - One E Under Imple of Laptops, Printers and othe IBRD / 90370 Project Management Post Open - National 11,556.00 0.00 2022-09-23 2022-10-13 2022-11-22 tions nvelope mentation r IT Equipment for the PMT AMP-RFQ-G-C3-9 / Purchase Request for Quota Single Stage - One E Under Imple of Financial/Accounting Softw IBRD / 90370 Project Management Post Open - National 15,073.00 0.00 2022-08-22 2022-09-27 2022-12-27 tions nvelope mentation are, Support and Maintenanc e AMP/G/RFQ-C3.1-10 / Purcha Request for Quota Single Stage - One E Under Imple IBRD / 90370 Project Management Post Open - National 32,263.00 0.00 2023-01-23 2023-03-06 2023-07-04 se of Vehicle tions nvelope mentation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AMP-TS-RFB-C2.1-12 / Procur ement of Non-Consulting Ser Institutional Capacity for EU Single Stage - One E Under Imple vices for Improving Data Qua IBRD / 90370 Post Request for Bids Open - National 150,000.00 0.00 2023-06-12 2023-06-29 2023-06-17 2023-07-08 2023-07-23 2023-08-13 2024-04-09 Accession nvelope mentation lity on State Owned Agricultu ral Land - Sub-division of par cels in co-ownership CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AMP/CS/CQS/SC2.1-2.5 / Des ign and Creation of a Tempor Institutional Capacity for EU Consultant Qualifi Under Implement IBRD / 90370 Post Open - National 150,737.00 0.00 2022-09-27 2022-09-23 2022-10-12 2022-11-09 2022-11-14 2022-11-14 2022-11-25 2023-08-25 ary Inventory for State-Owne Accession cation Selection ation d Agricultural Land AMP/CS/QCBS/SC1.2-1 / Con sulting services for Feasibility Study, Urbanism, Schematic Agriculture Sector Competiti Quality And Cost- Open - Internationa IBRD / 90370 Prior 502,459.00 0.00 Canceled 2022-09-30 2022-10-14 2022-10-24 2022-11-21 2022-12-05 2022-12-09 2022-12-19 2025-05-30 and Development Design of veness Based Selection l 2 Collection and Conditioning Centers in Strumica and Res en AMP/CS/QBS/SC1.2-1 / Cons ulting Services for Site Select ion, Urban Planning, Feasibili Agriculture Sector Competiti Quality Based Sel Open - Internationa IBRD / 90370 Prior 502,459.00 0.00 Under Review 2022-10-12 2022-10-13 2022-11-02 2022-11-04 2022-11-12 2023-03-15 2022-12-10 2022-12-17 2022-12-24 2023-01-16 2025-05-30 ty, Schematic and Detailed D veness ection l esign of 2 (Two) Collection a nd Conditioning Centers in St rumica and Resen AMP/CS/QBS-SC1.2-2 / Cons ulting Services for Site Select ion, Urban Planning, Feasibili Agriculture Sector Competiti Quality Based Sel Open - Internationa Under Implement IBRD / 90370 Prior 810,000.00 0.00 2022-10-27 2022-10-27 2022-11-17 2022-10-27 2022-11-29 2023-03-17 2022-12-27 2023-05-10 2023-01-05 2023-01-10 2023-01-23 2025-05-30 ty, Schematic and Detailed D veness ection l ation esign of an Agri-Food Platfor m in Skopje area (Gazi Baba Municipality) AMP/CS/QBS-SC2.3-1 / Cons ulting Services for establishm Institutional Capacity for EU Quality Based Sel Open - Internationa Under Implement IBRD / 90370 Post 400,000.00 0.00 2022-11-15 2022-12-13 2022-12-06 2023-01-20 2023-01-04 2023-03-22 2023-02-01 2023-02-16 2023-02-17 2023-02-28 2025-04-30 ent of a sustainable system f Accession ection l ation or Animal By-Products Manag ement AMP/CS/CQS-SC2.2-1 / CS for Preparation of the Main Proje ct Design, Environmental and Institutional Capacity for EU Consultant Qualifi Under Implement Social Management Docume IBRD / 90370 Post Open - National 163,568.00 0.00 2023-04-18 2023-05-26 2023-05-09 2023-06-22 2023-07-22 2023-08-26 2024-02-22 Accession cation Selection ation nts and Supervision of civil w orks for Refurbishment of the interior and exterior of the b uilding for the AFSARD AMP-CS-CQS-SC1.1 / Consult ing Services on Targeted Trai ning for the potential benefici Agriculture Sector Competiti Consultant Qualifi Under Implement IBRD / 90370 Post Open - National 328,392.00 0.00 2023-05-26 2023-06-28 2023-06-09 2023-07-23 2023-08-23 2023-09-05 2025-01-02 aries of the Collecting and Co veness cation Selection ation nditioning Centers in Resen a nd Strumica and the Agri-foo d Platform in Skopje AMP-CS-LCS-C3.15-1 / Consu lting Services for Providing A Least Cost Selecti Under Implement IBRD / 90370 Project Management Post Open - National 79,267.00 0.00 2023-05-31 2023-05-31 2023-06-14 2023-07-28 2023-08-25 2023-08-31 2023-09-04 2023-09-14 2025-12-31 udit of the Agriculture Moder on ation nization Project for the fiscal years 2022 -2025 INDIVIDUAL CONSULTANTS Page 1 Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AMP/IC/C3-5 / Environment a Individual Consult Under Implement IBRD / 90370 Project Management Post Open 72,000.00 0.00 2022-05-09 2022-05-11 2022-06-27 2022-07-18 2022-08-22 2025-06-30 nd Social Safeguard Specialis ant Selection ation t AMP/IC/C3-6 / Architect/Civil Individual Consult Under Implement IBRD / 90370 Project Management Post Open 42,000.00 0.00 2022-05-09 2022-05-11 2022-06-27 2022-07-18 2022-08-22 2025-06-30 Engineer Specialist ant Selection ation AMP/IC/SC2.1-1.4 / Strength ening the Monitoring Capacit Institutional Capacity for EU Individual Consult Under Implement y of the Ministry of Agricultur IBRD / 90370 Post Open 80,000.00 0.00 2022-05-13 2022-06-09 2022-07-01 2022-09-20 2022-07-04 2022-07-08 2023-07-07 Accession ant Selection ation e, Forestry and Water Econo my (MAFWE) of Republic of N orth Macedonia AMP/IC/C3-4 / Office Assistan Individual Consult Under Implement IBRD / 90370 Project Management Post Limited 31,500.00 0.00 2022-07-06 2022-07-08 2022-07-11 2022-07-12 2022-07-13 2022-08-04 2025-06-30 t/Translator ant Selection ation AMP/IC/3.1-1 / Project Coordi Individual Consult IBRD / 90370 Project Management Post Open - National 42,900.00 0.00 Canceled 2022-11-16 2022-11-11 2023-01-04 2023-01-05 2023-01-12 2025-06-30 nator ant Selection AMP/IC/SC2.1-1.1 / Consultin Institutional Capacity for EU Individual Consult Open - Internationa Under Implement g Services for Definition of Pl IBRD / 90370 Post 50,000.00 0.00 2023-01-25 2023-02-09 2023-03-15 2023-03-20 2023-03-27 2024-01-26 Accession ant Selection l ation atform Variables AMP/IC/C3-1-1 / Project Coor Individual Consult Under Implement IBRD / 90370 Project Management Prior Direct - National 46,000.00 0.00 2023-03-06 2023-03-15 2023-03-06 2023-03-16 2023-03-07 2023-03-16 2023-03-10 2025-06-30 dinator ant Selection ation AMP/IC/C3-2-1 / Procuremen Individual Consult Under Implement IBRD / 90370 Project Management Post Open - National 40,000.00 0.00 2023-03-06 2023-03-15 2023-04-08 2023-04-10 2023-04-26 2025-06-30 t Specialist ant Selection ation AMP-CS-IC-SC3.12-1 / IT Spe Individual Consult Under Implement IBRD / 90370 Project Management Post Open - National 24,000.00 0.00 2023-07-03 2023-06-28 2023-08-07 2023-08-10 2023-08-14 2024-08-30 cialist (part-time) ant Selection ation Page 2 PROCUREMENT PLAN (Textual Part) Project information: Country: Democratic Republic of Congo; Project name: DRC Enhancing Collection of Revenue and Expenditure Management Project (ENCORE), Project number: P171762 Project Implementation agency: Comité d’Orientation de la Réforme des Finances Publiques (COREF) Date of the Procurement Plan: 02/12/2021 Period covered by this Procurement Plan: from 12/02/2021 to 05/01/2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation: “Not applicable”], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Secondhand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables. Works: is not applicable for those contracts identified in the Procurement Plan tables Revue Date prévue Méthode par la pour Réf. Prévu/Ré Commentai Description* Coût en $US de Banque l'ouverture No al. res sélection (priori/po de l'offre st) technique Sélection des consultants Recrutement du personnel clé et du 248 Prévu CI Post NA 1 personnel d’appoint de l’Equipe du Projet 600,00 (Période PPA) Réalisé Sélection d'un consultant cabinet Prévu 150 QC Post NA international en vue de mener les études de 000,00 2 faisabilité pour la mise en œuvre de E- Réalisé Procurement en RDC Recrutement d'un Consultant international 90 Prévu CI Post 25-3-2022 3 chargé de l’appui à la mise en œuvre du 000,00 SIGRH-Paie Réalisé Sélection d'un consultant individuel chargé Prévu 70 CI Post NA d'appuyer l'élaboration des textes fixant les 000,00 4 modalités de répartition des recettes à Réalisé caractère national Sélection d'un consultant individuel pour Prévu 50 CI Post NA réaliser une étude de faisabilité pour la mise 000,00 5 en place des administrations provinciales du trésor, de la comptabilité et du budget dans Réalisé 3 provinces identifiées Sélection d'un consultant individuel pour 50 élaborer un cahier de charges de mise en Prévu CI Post NA 000,00 6 place d'un système intégré des recettes et des dépenses en Provinces Réalisé Revue Date prévue Méthode par la pour Réf. Prévu/Ré Commentai Description* Coût en $US de Banque l'ouverture No al. res sélection (priori/po de l'offre st) technique Sélection d'un Consultant individuel pour la Prévu 50 CI Post NA rédaction du manuel des procédures de 000,00 7 gestion financière et de la passation des Réalisé marchés du Projet ENCORE Sélection d'un Cabinet pour l'acquisition et le 50 Prévu QC Post NA 8 paramétrage du logiciel de stockage et 000,00 analyse des données du Suivi-Evaluation Réalisé Sélection d'un Consultant cabinet pour Prévu 50 QC Post NA l'acquisition et le paramétrage du logiciel de 000,00 9 gestion de projet (technique et mise en Réalisé œuvre des activités) Recrutement d'un Consultant individuel Prévu 45 CI Post NA chargé de la conception et la mise en œuvre 000,00 10 d’une plateforme web pour la mise à jour du fichier de référence des agents de Réalisé l’Administration publique (FRAP 2) Sélection d'un Cabinet Webmaster pour la 45 Prévu QC Post NA 11 mise en place du Site WEB de 3 provinces 000,00 sélectionnées Réalisé Sélection d'un consultant international expert 40 Prévu CI Post en sondage pour 4 mois chargé 000,00 12 d’accompagner l’équipe technique nationale dans l'organisation de l'enquête et Réalisé l'actualisation de la base d'échantillonnage Revue Date prévue Méthode par la pour Réf. Prévu/Ré Commentai Description* Coût en $US de Banque l'ouverture No al. res sélection (priori/po de l'offre st) technique Sélection d'un consultant pour l'évaluation de 30 Prévu CI Post NA la répartition effective (etude Benefit Sharing 000,00 13 Assessment ou BSA) des recettes minières Réalisé au niveau local (0.3% aux ETDs) Sélection d'un Consultant individuel pour la Prévu 30 CI Post 18-3-2022 14 rédaction du manuel de vérification des PBCs 000,00 et PBPs du Projet ENCORE Réalisé Sélection d'un consultant cabinet chargé de 25 Prévu SMC Post NA 15 l'Audit financier externe du PPA clos au 000,00 30/04/2022 Réalisé Sélection d'un Consultant Individuel chargé 25 Prévu CI Post NA 16 d'élaborer le plan d'engagement 000,00 environnemental et social Réalisé Sélection d'un Consultant Individuel chargé 25 Prévu CI Post 5-3-2022 17 d'élaborer le plan de mobilisation des parties 000,00 prenantes Réalisé 24 Sélection d'un Consultant Individuel Prévu CI Post 5-3-2022 18 000,00 Ingénieur Génie Civil Réalisé Sélection d'un consultant international expert Prévu 20 CI Post 5-3-2022 en CAPI pour 2 mois qui seront chargés 000,00 19 d’accompagner l’équipe technique nationale Réalisé dans l'organisation de l'enquête et Revue Date prévue Méthode par la pour Réf. Prévu/Ré Commentai Description* Coût en $US de Banque l'ouverture No al. res sélection (priori/po de l'offre st) technique l'actualisation de la base d'échantillonnage Sélection d'un Consultant pour appuyer la Prévu 16 ED Post NA 20 2ème phase de la mise en place de SIGMAP 000,00 (20 nouvelles cellules) (Pierre Tshiyombo) Réalisé 15 Sélection d'un Cabinet Webmaster pour la Prévu QC Post NA 21 000,00 mise en place du Site WEB du Projet ENCORE Réalisé Recrutement d'un Consultant Expert en 14 Prévu CI Post NA informatique et systèmes d’information 000,00 22 chargé d’appuyer la mise en œuvre du Système Intégré de Gestion des Ressources Réalisé Humaines et de la Paie (SIGRH-Paie) Recrutement d'un Consultant National 14 Prévu CI Post NA individuel en Administration Publique chargé 000,00 23 d’appuyer la mise en œuvre du Système Intégré de Gestion des Ressources Humaines Réalisé et de la Paie (SIGRH-Paie) 1 175 600,00 SFQC : sélection fondée sur la qualité et le coût QC : sélection fondée sur les qualifications des consultants SMC : sélection au moindre coût CI : sélection de Consultant individuel ED: sélection par entente directe PROCUREMENT Congo, Democratic Republic of : Enhancing Collection of Revenue and Expenditure Management Project PLAN General Information Country: Congo, Democratic Republic of 2021-12-02 Bank’s Approval Date of the Original Procurement Plan: 2023-05-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171762 GPN Date: 2022-06-14 Project Name: Enhancing Collection of Revenue and Expenditure Management Project Loan / Credit No: IDA / 70200, / , IDA / V4000 Comité d'Orientation de la Reforme des Finances Publiques Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ZR-COREF-345140-CW-RFQ / Component 1. Strengthening Request for Quota Travaux de réhabilitation du Public Resources Manageme Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-02-1 IDA / 70200 Post Open - National 200,000.00 0.00 2023-06-20 2023-08-15 bâtiment devant abriter la ch nt at Central Government Le tions nvelope s (Emergency) SP lementation 1 ambre des comptes déconce vel D -Competitive ntrées de Kananga ZR-COREF-345177-CW-RFQ / Request for Quota Component 3. Project and C Réhabilitation du bâtiment m Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-12-1 IDA / 70200 hange Management, and Em Post Open - National 100,000.00 0.00 2023-04-27 2023-06-22 is à disposition pour la coordi tions nvelope s (Emergency) SP lementation 9 ergency Response nation provinciale du Kasaï D -Competitive Request for Quota ZR-COREF-345180-CW-RFQ / Component 3. Project and C Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-12-2 Réhabilitation des bâtiments IDA / 70200 hange Management, and Em Post Open - National 145,000.00 0.00 2023-05-03 2023-06-28 tions nvelope s (Emergency) SP lementation 5 de la coordination nationale ergency Response D -Competitive ZR-COREF-345109-CW-RFQ / Appui à l'aménagement des l Component 1. Strengthening ocaux devant abriter les post Request for Quota Public Resources Manageme Request for Quota Single Stage - One E Pending Imp 2023-12-2 es du réseau comptable à Ki IDA / 70200 Post Limited tions (Non Bank-S 150,000.00 0.00 2023-04-30 2023-06-25 nt at Central Government Le tions nvelope lementation 2 nshasa pour les postes comp PD) vel tables des 4 ministères déco ncentrés (EPST, Santé, ITPR e t Développement Rural) + l'A CCT ZR-COREF-356044-CW-RFQ / Component 1. Strengthening Request for Quota Travaux d’aménagement du l Public Resources Manageme Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-01-2 IDA / 70200 Post Limited 50,000.00 0.00 2023-05-30 2023-07-25 ocal technique du datacenter nt at Central Government Le tions nvelope s (Emergency) SP lementation 1 de l'Hôtel du Gouvernement vel D -Competitive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-COREF-264864-GO-RFQ / Component 1. Strengthening Acquisition et déploiement d Public Resources Manageme Request for Quota Single Stage - One E Pending Impl es matériels auprès des utilis / Post Limited 40,000.00 0.00 2022-01-15 2022-02-25 2022-04-26 nt at Central Government Le tions nvelope ementation ateurs de SIGMAP dans 20 no vel uveaux cellules identifiées ZR-COREF-265014-GO-DIR / Component 3. Project and C Acquisition d'un logiciel de g IDA / 70200 hange Management, and Em Post Direct Selection Direct 50,000.00 46,473.00 Completed 2021-12-20 2021-12-20 2021-12-25 2021-12-20 2022-01-27 2022-02-12 2022-03-28 2022-12-09 estion financière du projet E ergency Response NCORE (auprès de TOMATE) ZR-COREF-265086-GO-DIR / Marché de fourniture de Rec Component 1. Strengthening harge des Clés APN pour la r Public Resources Manageme IDA / 70200 Post Direct Selection Direct 20,000.00 20,000.00 Completed 2021-12-24 2022-01-25 2021-12-29 2022-01-21 2022-01-14 2022-01-26 2022-04-30 2022-05-04 emontée des informations de nt at Central Government Le s 75 Administrations + l’équi vel pe technique de la FP (25)/ S OCIETE RAAH SARL ZR-COREF-296208-GO-RFQ / Component 1. Strengthening Marché de fourniture de mob Public Resources Manageme Request for Quota Single Stage - One E Pending Impl IDA / V4000 Post Limited 70,000.00 0.00 2022-06-22 2022-07-22 2022-08-21 ilier de bureaux pour équiper nt at Central Government Le tions nvelope ementation les nouveaux locaux de la D vel GRH-DBDR ZR-COREF-296509-GO-DIR / Reconduction du contrat des fournitures de recharge des c Component 1. Strengthening lés APN pour la remontée des Public Resources Manageme IDA / 70200 Post Direct Selection Direct 15,000.00 15,000.00 Completed 2022-05-23 2022-05-23 2022-05-25 2022-05-23 2022-05-29 2022-05-31 2022-07-31 2022-07-07 informations de 75 administr nt at Central Government Le ations + l'équipe technique d vel e la FP (25) pour la période d e Mai à Juillet 2022 - Société RAAH SARL ZR-COREF-296039-GO-RFQ / Component 3. Project and C Acquisition des laptops et ac Request for Quota Single Stage - One E IDA / V4000 hange Management, and Em Post Limited 49,000.00 46,270.00 Completed 2022-06-09 2022-06-06 2022-07-05 2022-07-15 2022-08-05 2022-12-04 cessoires pour le personnel d tions nvelope ergency Response u PPA du Projet ENCORE ZR-COREF-345208-GO-RFB / Acquisition des équipements Component 1. Strengthening informatiques pour les 4 cent Public Resources Manageme Single Stage - One E Pending Impl IDA / 70200 Post Request for Bids Open - National 600,000.00 0.00 2023-05-15 2023-05-20 2023-07-01 2023-07-31 2023-09-04 2024-03-02 res d'ordonnancement et pou nt at Central Government Le nvelope ementation r le renforcement du systèm vel e d'information de la chaîne de la dépense ZR-COREF-345267-GO-RFQ / Impression du manuel des pr Component 1. Strengthening océdures administratives et f Public Resources Manageme Request for Quota Single Stage - One E Pending Impl IDA / 70200 Post Limited 100,000.00 0.00 2023-04-25 2023-06-20 2023-12-17 inancières des DAF (2000 ex nt at Central Government Le tions nvelope ementation emplaires de 220 pages dont vel certaines pages en couleur) ZR-COREF-345306-GO-RFQ / Component 1. Strengthening Appui à la reproduction des Public Resources Manageme Request for Quota Single Stage - One E Pending Impl IDA / 70200 Post Limited 100,000.00 0.00 2023-04-15 2023-06-10 2023-12-07 manuels et textes règlement nt at Central Government Le tions nvelope ementation aires élaborés et validés vel ZR-COREF-345326-GO-RFQ / Component 1. Strengthening Request for Quota Single Stage - One E Pending Impl Acquisition des équipements IDA / 70200 Public Resources Manageme Post Limited 100,000.00 0.00 2023-07-06 2023-08-31 2024-02-27 tions nvelope ementation informatiques des postes clé nt at Central Government Le s de la DGTCP vel Page 1 ZR-COREF-345327-GO-RFQ / Component 1. Strengthening Request for Quota Single Stage - One E Pending Impl Acquisition des mobiliers de IDA / 70200 Public Resources Manageme Post Limited 90,000.00 0.00 2023-07-27 2023-09-21 2024-03-19 tions nvelope ementation bureau des postes clés de la nt at Central Government Le DGTCP vel ZR-COREF-345456-GO-RFQ / Component 1. Strengthening Acquisition des petites fourni Public Resources Manageme Request for Quota Single Stage - One E Pending Impl IDA / 70200 Post Limited 50,000.00 0.00 2023-08-12 2023-10-07 2024-04-04 tures de bureaux et consom nt at Central Government Le tions nvelope ementation mables en faveur des postes vel clés de la DGTCP ZR-COREF-345460-GO-RFB / Component 1. Strengthening Single Stage - One E Pending Impl Acquisition d'une solution inf IDA / 70200 Public Resources Manageme Post Request for Bids Open - National 1,200,000.00 0.00 2023-07-15 2023-07-20 2023-08-31 2023-09-30 2023-11-04 2024-05-02 nvelope ementation ormatique du CUT nt at Central Government Le vel ZR-COREF-345473-GO-RFQ / Component 1. Strengthening Request for Quota Single Stage - One E Pending Impl Acquisition des mobiliers pou IDA / 70200 Public Resources Manageme Post Limited 200,000.00 0.00 2023-04-10 2023-06-05 2023-12-02 tions nvelope ementation r les 6 directions de la DGRH nt at Central Government Le réhabilitées vel ZR-COREF-345479-GO-RFQ / Component 1. Strengthening Acquisition de 40 machines s Public Resources Manageme Request for Quota Single Stage - One E Under Imple canners pour la numérisation IDA / 70200 Post Limited 48,000.00 0.00 2023-04-20 2023-06-15 2023-12-12 nt at Central Government Le tions nvelope mentation des actes administratifs de fo vel nctionnaires en provinces et au niveau central ZR-COREF-345482-GO-RFQ / Component 1. Strengthening Request for Quota Single Stage - One E Under Imple Acquisition des 80 lecteurs d' IDA / 70200 Public Resources Manageme Post Limited 12,000.00 0.00 2023-04-06 2023-06-01 2023-11-28 tions nvelope mentation empreintes pour identificatio nt at Central Government Le n biométrique vel ZR-COREF-345512-GO-RFQ / Component 1. Strengthening Acquisition de 100 machines Public Resources Manageme Request for Quota Single Stage - One E Pending Impl IDA / 70200 Post Limited 200,000.00 0.00 2023-05-04 2023-06-29 2023-12-26 d'impression des cartes des nt at Central Government Le tions nvelope ementation agents de carrières de servic vel es publics de l'Etat ZR-COREF-345539-GO-RFQ / Acquisition des matériels info Component 1. Strengthening rmatiques pour le déploieme Public Resources Manageme Request for Quota Single Stage - One E Pending Impl nt du SIGMAP dans 20 CGPM IDA / 70200 Post Limited 150,000.00 0.00 2023-06-20 2023-08-15 2024-02-11 nt at Central Government Le tions nvelope ementation Ps additionnelles au niveau c vel entral, la DGCMP ainsi que la salle machine SIGMAP au Min du Budget. ZR-COREF-345540-GO-RFQ / Component 1. Strengthening Acquisition des mobiliers de Public Resources Manageme Request for Quota Single Stage - One E Pending Impl IDA / 70200 Post Limited 30,000.00 0.00 2023-06-25 2023-08-20 2024-02-16 bureau pour la salle de mach nt at Central Government Le tions nvelope ementation ine SIGMAP au Budget. vel ZR-COREF-345544-GO-RFQ / Abonnement internet de la C Component 1. Strengthening our des comptes pour la publ Public Resources Manageme Request for Quota Single Stage - One E Pending Impl IDA / 70200 Post Limited 35,000.00 0.00 2023-04-11 2023-06-06 2023-12-03 ication notamment des rappo nt at Central Government Le tions nvelope ementation rts de reddition des comptes vel du pouvoir central et des pro vinces couvertes par le proje t ZR-COREF-345548-GO-RFQ / Component 1. Strengthening Appui à la reproduction des t Public Resources Manageme Request for Quota Single Stage - One E Pending Impl extes fixant les modalités de IDA / 70200 Post Limited 30,000.00 0.00 2023-05-11 2023-07-06 2024-01-02 nt at Central Government Le tions nvelope ementation répartition des impôts et tax vel es d’intérêt commun ZR-COREF-345551-GO-RFQ / Acquisition des matériels info Component 2. Supporting rmatiques en faveur des adm Resource Management at th Request for Quota Single Stage - One E Pending Impl IDA / 70200 Post Limited 250,000.00 0.00 2023-06-28 2023-08-23 2024-02-19 inistrations fiscales Provincial e Provincial Government Lev tions nvelope ementation es du Kasaï Oriental, du Kasa el ï, du Kasaï Central et de Lom ami ZR-COREF-345556-GO-RFQ / Acquisition des mobiliers des Component 2. Supporting bureaux en faveur des admin Resource Management at th Request for Quota Single Stage - One E Pending Impl IDA / 70200 Post Limited 250,000.00 0.00 2023-06-25 2023-08-20 2024-02-16 istrations fiscales Provinciale e Provincial Government Lev tions nvelope ementation s du Kasaï Oriental, du Kasaï el , du Kasaï Central et de Loma mi ZR-COREF-345557-GO-RFQ / Acquisition des fournitures d Component 2. Supporting es bureaux et consommables Resource Management at th Request for Quota Single Stage - One E Pending Impl IDA / 70200 Post Limited 110,000.00 0.00 2023-07-20 2023-09-14 2024-03-12 informatiques pour les régies e Provincial Government Lev tions nvelope ementation provinciales du Kasaï Orient el al, du Kasaï, du Kasaï Central et de Lomami ZR-COREF-345582-GO-RFQ / Acquisition des desktops et a Component 3. Project and C Request for Quota Single Stage - One E Pending Impl ccessoires pour le personnel IDA / 70200 hange Management, and Em Post Limited 60,000.00 0.00 2023-04-20 2023-06-15 2023-12-12 tions nvelope ementation du Projet ENCORE (Coordina ergency Response tion nationale et coordination s provinciales) ZR-COREF-345591-GO-RFQ / Acquisition des imprimantes Component 3. Project and C Request for Quota Single Stage - One E Pending Impl et appareils de reprographie IDA / 70200 hange Management, and Em Post Limited 60,000.00 0.00 2023-04-22 2023-06-17 2023-12-14 tions nvelope ementation pour le Projet ENCORE (Coor ergency Response dination nationale et coordin ations provinciales) ZR-COREF-345620-GO-RFQ / Component 3. Project and C Request for Quota Single Stage - One E Pending Impl Production d'un nouveau pa IDA / 70200 hange Management, and Em Post Limited 2,000.00 0.00 2023-04-04 2023-05-30 2023-11-26 tions nvelope ementation nneau ENCORE ergency Response ZR-COREF-345703-GO-DIR / Component 1. Strengthening Pending Impl Rechargement des Clés APN IDA / 70200 Public Resources Manageme Post Direct Selection Direct - National 60,000.00 0.00 2023-03-20 2023-03-25 2023-04-29 2024-04-28 ementation pour 75 postes nt at Central Government Le vel ZR-COREF-345707-GO-RFQ / Component 3. Project and C Reproduction des documents Request for Quota Single Stage - One E Pending Impl IDA / 70200 hange Management, and Em Post Limited 50,000.00 0.00 2023-05-18 2023-07-13 2024-01-09 stratégiques sur les réformes tions nvelope ementation ergency Response des finances publiques ZR-COREF-345708-GO-RFQ / Component 3. Project and C Reproduction de la revue tri Request for Quota Single Stage - One E Pending Impl IDA / 70200 hange Management, and Em Post Limited 40,000.00 0.00 2023-04-20 2023-06-15 2023-12-12 mestrielle sur la réforme des tions nvelope ementation ergency Response finances publiques ZR-COREF-345711-GO-RFQ / Component 3. Project and C Request for Quota Single Stage - One E Pending Impl Reproduction des agendas 2 IDA / 70200 hange Management, and Em Post Limited 40,000.00 0.00 2023-04-01 2023-05-27 2023-11-23 tions nvelope ementation 023 pour le Projet ENCORE ergency Response Page 2 ZR-COREF-345478-GO-RFQ / Component 1. Strengthening Request for Quota Single Stage - One E Pending Impl Mise aux normes de sécurisa IDA / 70200 Public Resources Manageme Post Limited 60,000.00 0.00 2023-08-12 2023-10-07 2024-04-04 tions nvelope ementation tion du Data Center de secou nt at Central Government Le rs vel ZR-COREF-345288-GO-RFB / Component 1. Strengthening Acquisition des fournitures d Public Resources Manageme Single Stage - One E Pending Impl IDA / 70200 Post Request for Bids Open - National 600,000.00 0.00 2023-08-07 2023-08-12 2023-09-23 2023-10-23 2023-11-27 2024-05-25 e bureau et consommables p nt at Central Government Le nvelope ementation our les 12 nouvelles DAF à in vel staller ZR-COREF-345249-GO-RFQ / Component 1. Strengthening Achat des mobiliers de burea Public Resources Manageme Request for Quota Single Stage - One E Pending Impl u pour les 4 centres d'ordonn IDA / 70200 Post Limited 320,000.00 0.00 2023-04-19 2023-06-14 2023-12-11 nt at Central Government Le tions nvelope ementation ancement des ministères de l vel ’EPST, Santé, Développemen t rural et des ITPR. ZR-COREF-345272-GO-RFB / Acquisition des matériels et mobiliers de bureau pour les Component 1. Strengthening 12 nouvelles DAF (Affaires ét Public Resources Manageme Single Stage - One E Pending Impl IDA / 70200 Post Request for Bids Open - National 1,000,000.00 0.00 2023-04-10 2023-04-15 2023-05-20 2023-06-10 2023-07-15 2024-01-11 rangères, Coopération intern nt at Central Government Le nvelope ementation ational, Coopération régional vel e, Economie, Energie, Hydroc arbures, Jeunesse, Mines, PM E et artisanat, PTNTIC, Sports et loisirs, Justice) ZR-COREF-345320-GO-RFQ / Acquisition des équipements Component 1. Strengthening informatiques et petites four Public Resources Manageme Request for Quota Single Stage - One E Pending Impl nitures pour l'opérationnalisa IDA / 70200 Post Limited 200,000.00 0.00 2023-07-20 2023-09-14 2024-03-12 nt at Central Government Le tions nvelope ementation tion de l'ACCT, de postes co vel mptables des 4 ministères dé concentrés (EPST, Santé, ITP R et Développement Rural) ZR-COREF-345705-GO-DIR / Appui à la migration du SIGM Component 1. Strengthening AP vers un hébergeur sécuris Public Resources Manageme Direct - Internation IDA / 70200 Post Direct Selection 15,000.00 0.00 Canceled 2023-07-25 2023-07-30 2023-09-03 2024-03-01 é, (frais d'hébergement) et A nt at Central Government Le al bonnement annuel de l'héber vel gement du SIGMAP avec l'ent reprise GODADDY ZR-COREF-362720-GO-RFB / Fourniture, installation et la mise en marche du datacent Component 2. Supporting er de secours au bâtiment ad Resource Management at th Single Stage - One E Pending Impl IDA / 70200 Post Request for Bids Open - National 216,000.00 0.00 2023-07-03 2023-07-08 2023-08-19 2023-09-18 2023-10-23 2024-04-20 ministratif de la fonction publ e Provincial Government Lev nvelope ementation ique du système intégré de g el estion des ressources humai nes et de la paie de l'adminis tration publique ZR-COREF-363973-GO-DIR / Appui à la migration du SIGM Component 1. Strengthening AP vers un hébergeur sécuris Public Resources Manageme Pending Impl IDA / 70200 Post Direct Selection Direct - National 15,000.00 0.00 2023-05-30 2023-06-04 2023-07-09 2024-01-05 é (frais d'hebergement) et ab nt at Central Government Le ementation onnement annuel de l'heberg vel ement du SIGMAP avec l'entr eprise ITIK ZR-COREF-362725-GO-RFQ / Acquisition de 2 véhicules 4X Component 2. Supporting 4 pour faciliter le déploiemen Resource Management at th Request for Quota Single Stage - One E Pending Impl t des équipes de recensemen IDA / 70200 Post Limited 160,000.00 0.00 2023-07-06 2023-08-31 2024-02-27 e Provincial Government Lev tions nvelope ementation t et de collecte des données el à Kinshasa et dans les 4 prov inces du Kasaï, Kasaï Central, Kasaï Oriental et Lomami ZR-COREF-345281-GO-RFB / Acquisition des matériels info rmatiques pour les 12 nouvel Component 1. Strengthening les DAF, (Affaires étrangères, Public Resources Manageme Open - Internationa Single Stage - One E Under Revie IDA / 70200 Prior Request for Bids 2,200,000.00 0.00 2023-04-10 2023-04-15 2023-05-27 2023-06-26 2023-07-31 2024-01-27 Coopération international, Co nt at Central Government Le l nvelope w opération régionale, Economi vel e, Energie, Hydrocarbures, Je unesse, Mines, PME et artisa nat, PTNTIC, Sports et loisirs, Justice) ZR-COREF-362723-GO-RFQ / Component 3. Project and C Acquisition de 6 véhicules 4X Request for Quota Single Stage - One E Pending Impl IDA / 70200 hange Management, and Em Post Limited 480,000.00 0.00 2023-07-06 2023-08-31 2024-02-27 4 dont 2 pour la coordination tions nvelope ementation ergency Response nationale et 4 pour les coordi nations provinciales NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-COREF-264873-NC-DIR / Component 3. Project and C Recrutement d'un prestataire IDA / 70200 hange Management, and Em Post Direct Selection Direct 9,600.00 9,600.00 Completed 2021-12-10 2021-12-20 2021-12-15 2021-12-20 2021-12-31 2021-12-29 2022-04-30 2022-05-10 de service d'entretien des bu ergency Response reaux ZR-COREF-264876-NC-DIR / Component 3. Project and C Recrutement d'un prestataire IDA / 70200 hange Management, and Em Post Direct Selection Direct 12,000.00 12,000.00 Completed 2021-12-15 2021-12-20 2021-12-20 2021-12-20 2021-12-31 2021-12-29 2022-04-30 2022-04-26 pour le service de gardienna ergency Response ge des bureaux de la Coordin ation nationale ZR-COREF-264970-NC-RFQ / Component 3. Project and C Request for Quota Single Stage - One E Service d'assurance médical / hange Management, and Em Post Limited 50,000.00 0.00 Canceled 2021-12-08 2022-01-06 2022-04-27 tions nvelope e pour le personnel du Projet ergency Response (Période du PPA) ZR-COREF-296507-NC-DIR / Renouvellement contrat pres Component 3. Project and C tataire de service d'entretien IDA / 70200 hange Management, and Em Post Direct Selection Direct 7,200.00 7,200.00 Completed 2022-05-23 2022-05-23 2022-05-25 2022-05-23 2022-05-29 2022-05-31 2022-07-31 2022-08-18 et nettoyage des bureaux (d ergency Response e Mai à Juillet 2022) - BAM'S CLEAN ZR-COREF-296508-NC-DIR / Renouvellement contrat du p restataire pour le service de Component 3. Project and C gardiennage et sécurité des IDA / 70200 hange Management, and Em Post Direct Selection Direct 9,000.00 9,000.00 Completed 2022-05-23 2022-05-23 2022-05-25 2022-05-23 2022-05-29 2022-05-31 2022-07-31 2022-07-26 bureaux de la Coordination N ergency Response ationale du Projet ENCORE (d e Mai à Juin 2022) - ATALANT E GROUP ZR-COREF-316188-NC-DIR / Component 3. Project and C Renouvellement contrat du p IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 40,000.00 0.00 Signed 2022-09-20 2022-11-30 2022-09-22 2022-12-14 2022-09-26 2023-09-26 restataire de service de netto ergency Response yage des bureaux Page 3 ZR-COREF-316202-NC-DIR / Renouvellement contrat du p Component 3. Project and C restataire de service de gardi IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 40,000.00 0.00 Signed 2022-09-20 2022-11-30 2022-09-22 2022-12-14 2022-09-26 2023-07-31 ennage et sécurité des burea ergency Response ux de la Coordination Nation ale du Projet ZR-COREF-345709-NC-RFQ / Sélection d'une maison de pr Component 3. Project and C oduction (agence de presse) Request for Quota Single Stage - One E Pending Impl IDA / 70200 hange Management, and Em Post Limited 20,000.00 0.00 2023-04-22 2023-06-17 2023-12-14 pour la prise des images, la c tions nvelope ementation ergency Response onception d'un documentaire sur le lancement du projet da ns les 5 sites et sa diffusion ZR-COREF-345004-NC-DIR / Renouvellement contrat du p Component 3. Project and C restataire de service de gardi Pending Impl IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 40,000.00 0.00 2023-07-15 2023-07-25 2023-07-31 2024-07-30 ennage et sécurité des burea ementation ergency Response ux de la Coordination Nation ale du Projet avec ATALANT Group ZR-COREF-345000-NC-DIR / Contrat de prestation de serv Component 3. Project and C Pending Impl ice de nettoyage des bureau IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 40,000.00 0.00 2023-07-15 2023-07-25 2023-07-29 2024-07-28 ementation x de la Coordination du Proje ergency Response t ENCORE, Etablissement BA M’S CLEAN ZR-COREF-356049-NC-RFQ / Fourniture, installation et par Component 1. Strengthening amétrage du réseau dans les Public Resources Manageme Request for Quota Single Stage - One E Pending Impl IDA / 70200 Post Limited 100,000.00 0.00 2023-05-04 2023-06-29 2023-12-26 4 centres d'ordonnancement nt at Central Government Le tions nvelope ementation des Mininistères: Santé, EPS vel T, ITPR, et Développement ru ral CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-COREF-264820-CS-CQS / Component 1. Strengthening Sélection d'un Cabinet Inter Public Resources Manageme Consultant Qualifi Open - Internationa national pour le développem IDA / 70200 Post 150,000.00 145,400.00 Signed 2021-12-10 2021-12-16 2022-01-09 2022-01-06 2022-01-24 2022-03-24 2022-02-03 2022-04-05 2022-02-13 2022-05-24 2022-04-29 nt at Central Government Le cation Selection l ent de la stratégie de mise e vel n œuvre d'une solution e-GP ZR-COREF-264866-CS-CQS / Sélection d'un Cabinet pour l Component 3. Project and C Consultant Qualifi a rédaction du manuel des pr IDA / 70200 hange Management, and Em Post Open - National 50,000.00 47,410.00 Completed 2021-12-22 2021-12-16 2022-01-05 2021-12-23 2022-01-25 2022-03-01 2022-02-01 2022-03-14 2022-02-18 2022-03-16 2022-04-29 2022-07-12 cation Selection océdures de gestion financièr ergency Response e et de la passation des marc hés du Projet ENCORE ZR-COREF-264867-CS-CQS / Component 3. Project and C Sélection d'un Cabinet Webm Consultant Qualifi IDA / 70200 hange Management, and Em Post Open - National 15,000.00 0.00 Signed 2021-12-20 2022-01-25 2022-01-03 2022-01-23 2022-03-16 2022-02-02 2022-05-30 2022-02-19 2022-04-30 aster pour la mise en place d cation Selection ergency Response u Site WEB du Projet ENCORE ZR-COREF-265013-CS-CQS / Component 2. Supporting Sélection d'un Cabinet Webm Resource Management at th Consultant Qualifi IDA / 70200 Post Open - National 45,000.00 44,554.80 Signed 2021-12-20 2022-01-25 2022-01-03 2022-01-23 2022-03-16 2022-01-28 2022-05-30 2022-02-17 2022-06-03 2022-04-30 aster pour la mise en place d e Provincial Government Lev cation Selection u Site WEB de 4 provinces sé el lectionnées ZR-COREF-296044-CS-QCBS Component 1. Strengthening / Sélection d'un Consultant fir Public Resources Manageme Quality And Cost- Open - Internationa Under Implement me pour accompagner la mis IDA / 70200 Prior 2,000,000.00 0.00 2022-06-15 2022-06-13 2022-07-30 2022-06-23 2022-09-03 2022-10-03 2022-10-24 2022-11-17 2022-12-22 2024-12-21 nt at Central Government Le Based Selection l ation e en service effective des str vel uctures de la DGTCP ZR-COREF-264863-CS-LCS / Sélection d'un Cabinet indép Component 3. Project and C Least Cost Selecti Open - Internationa endant pour l'Audit financier / hange Management, and Em Post 25,000.00 0.00 Canceled 2021-12-10 2021-12-31 2022-01-21 2022-02-18 2022-02-25 2022-03-17 2022-03-31 2022-06-29 on l externe sur la gestion fiducia ergency Response ire du PPA clos au 30/04/202 2 ZR-COREF-344156-CS-QCBS / Recrutement d'un Consulta nt International firme pour le Component 1. Strengthening renforcement de capacités d Public Resources Manageme Quality And Cost- Open - Internationa Pending Impleme IDA / 70200 Post 150,000.00 0.00 2023-04-20 2023-05-11 2023-06-24 2023-07-22 2023-08-21 2023-09-25 2023-10-30 2024-10-29 es membres de la Commissio nt at Central Government Le Based Selection l ntation n interministérielle de la vali vel dation des études de faisabili té d'un projet minier avec la participation des OSC ZR-COREF-344187-CS-QCBS / Recrutement d'un Cabinet i Component 1. Strengthening nternational pour évaluer les Public Resources Manageme Quality And Cost- Open - Internationa Under Implement besoins en renforcement de IDA / 70200 Post 180,000.00 0.00 2023-03-18 2023-06-21 2023-04-08 2023-05-13 2023-06-10 2023-07-01 2023-08-05 2023-09-09 2024-09-08 nt at Central Government Le Based Selection l ation capacités des services interv vel enant dans la gestion des rev enus miniers et autres partie s prenantes ZR-COREF-344190-CS-QCBS / Recrutement d'un Cabinet i Component 1. Strengthening nternational pour évaluer les Public Resources Manageme Quality And Cost- Open - Internationa Pending Impleme besoins techniques en renfor IDA / 70200 Post 180,000.00 0.00 2023-03-15 2023-04-05 2023-05-10 2023-06-07 2023-07-07 2023-08-11 2023-09-15 2024-09-14 nt at Central Government Le Based Selection l ntation cement de capacités de la C vel ommission interministérielle d'harmonisation et de consoli dation des statistiques minièr es ZR-COREF-344276-CS-QCBS / Recrutement d’une Cabinet International devant appuyer Component 1. Strengthening le gouvernement à : (i) défini Public Resources Manageme Quality And Cost- Open - Internationa Pending Impleme r le nouveau cadre organisati IDA / 70200 Post 180,000.00 0.00 2023-04-10 2023-05-01 2023-06-05 2023-07-03 2023-07-24 2023-08-28 2023-10-02 2024-10-01 nt at Central Government Le Based Selection l ntation onnel et juridique, (ii) élabor vel er le manuel de procédures d es dépenses non salariales ; ( iii) proposer l'adaption de la chaîne de dépense/sys ZR-COREF-344288-CS-QCBS / Recrutement d'un cabinet p Component 1. Strengthening our assurer la formation des Public Resources Manageme Quality And Cost- Open - Internationa Pending Impleme IDA / 70200 Post 400,000.00 0.00 2023-04-03 2023-04-24 2023-05-29 2023-06-26 2023-07-17 2023-08-21 2023-09-25 2024-09-24 DAF suivant plan de formatio nt at Central Government Le Based Selection l ntation n sur une période de 6 mois ( vel suivant les modules et group es) Page 4 ZR-COREF-344335-CS-QCBS / Recrutement d'une Firme c Component 1. Strengthening hargée d'appuyer le Ministèr Public Resources Manageme Quality And Cost- Open - Internationa Under Implement e de la Fonction Publique en IDA / 70200 Post 600,000.00 0.00 2023-03-27 2023-04-21 2023-04-17 2023-05-31 2023-06-28 2023-07-28 2023-09-01 2023-10-06 2024-10-05 nt at Central Government Le Based Selection l ation matière de la méthologie et vel planification de la constitutio n du Fichier de Référence de l'Administration Publique ZR-COREF-344343-CS-QCBS Component 1. Strengthening / Recrutement d'une Firme p Public Resources Manageme Quality And Cost- Open - Internationa Under Implement IDA / 70200 Prior 1,300,000.00 0.00 2023-03-15 2023-04-05 2023-05-19 2023-06-16 2023-07-16 2023-08-20 2023-09-24 2024-09-23 our la constitution du Fichier nt at Central Government Le Based Selection l ation de Référence de l'Administra vel tion Publique ZR-COREF-344418-CS-QCBS / Recrutement d’une firme po ur l'assistance en maître d'ou Component 1. Strengthening vrage du SIGeFiP avec le noy Public Resources Manageme Quality And Cost- Open - Internationa Pending Impleme au composé des modules co IDA / 70200 Post 150,000.00 0.00 2023-05-08 2023-05-29 2023-07-12 2023-08-09 2023-09-08 2023-10-13 2023-11-17 2024-11-16 nt at Central Government Le Based Selection l ntation mptable et budgétaire (étude vel s préalables et analyse des b esoins complémentaires en r enforcement de capacités et en équipements pour la mise en pla ZR-COREF-344472-CS-LCS / Component 1. Strengthening Recrutement d'un cabinet int Public Resources Manageme Least Cost Selecti Open - Internationa Pending Impleme IDA / 70200 Post 160,000.00 0.00 2023-04-05 2023-04-26 2023-06-09 2023-07-07 2023-08-06 2023-09-10 2023-10-15 2024-01-13 ernational chargé de l'audit i nt at Central Government Le on l ntation ndépendant en PPP (exercice vel 2019-2022) ZR-COREF-344478-CS-QCBS / Recrutement d’un consulta Component 1. Strengthening nt sénior international pour l’ Public Resources Manageme Quality And Cost- Open - Internationa Under Implement élaboration de la stratégie de IDA / 70200 Post 100,000.00 0.00 2023-03-22 2023-05-20 2023-04-12 2023-05-26 2023-06-23 2023-07-23 2023-08-27 2023-10-01 2023-11-30 nt at Central Government Le Based Selection l ation renforcement des capacités, vel de formation et de profession nalisation des acteurs nation aux de la commande publiq ue. ZR-COREF-344507-CS-QCBS Component 1. Strengthening / Recrutement d'une firme po Public Resources Manageme Quality And Cost- Under Implement IDA / 70200 Post Open - National 300,000.00 0.00 2023-03-20 2023-04-10 2023-04-10 2023-05-24 2023-06-21 2023-07-21 2023-08-25 2023-09-29 2023-12-28 ur réaliser l'audit organisatio nt at Central Government Le Based Selection ation nnel du Conseil Supérieur du vel Portefeuille (CSP) ZR-COREF-344755-CS-QCBS / Recrutement d'un consultan Component 1. Strengthening t cabinet pour l'élaboration d' Public Resources Manageme Quality And Cost- Open - Internationa Pending Impleme un plan de renforcement des IDA / 70200 Post 250,000.00 0.00 2023-04-13 2023-05-04 2023-06-17 2023-07-15 2023-08-14 2023-09-18 2023-10-23 2024-10-22 nt at Central Government Le Based Selection l ntation capacités du CSP, COPIREP, d vel u Secrétariat Général et des managers des entreprises pu bliques ciblées par le projet ZR-COREF-344884-CS-QCBS / Recrutement d'un Cabinet p our assistance-métier et tech Component 2. Supporting nique pour la mise en place d Resource Management at th Quality And Cost- Open - Internationa Pending Impleme 'un système d'informations d IDA / 70200 Post 500,000.00 0.00 2023-04-05 2023-04-26 2023-06-09 2023-07-07 2023-08-06 2023-09-10 2023-10-15 2024-10-14 e Provincial Government Lev Based Selection l ntation e collecte des prélèvements f el iscaux et non fiscaux dans le s 4 provinces (du Kasaï Orien tal, du Kasaï, du Kasaï Centra l et de Lomami) ZR-COREF-345075-CS-CQS / Component 3. Project and C Recrutement d’une ONG spé Consultant Qualifi Under Implement IDA / 70200 hange Management, and Em Post Open - National 300,000.00 0.00 2023-04-07 2023-04-11 2023-04-28 2023-06-11 2023-07-11 2023-08-15 2024-02-11 cialisée en VBG pendant la m cation Selection ation ergency Response ise en œuvre du projet ZR-COREF-344126-CS-QCBS / Recrutement d'un Consulta Component 1. Strengthening nt International firme pour la Public Resources Manageme Quality And Cost- Open - Internationa Pending Impleme réalisation de l'étude sur le p IDA / 70200 Post 100,000.00 0.00 2023-04-15 2023-04-29 2023-06-03 2023-07-01 2023-07-03 2023-08-07 2023-09-11 2024-09-10 nt at Central Government Le Based Selection l ntation otentiel fiscal du secteur mini vel er de la République Démocra tique du Congo y compris l'a nalyse et l'audit du régime fi scal ZR-COREF-356052-CS-CQS / Recrutement d’un Cabinet int ernational chargé d' (i) évalu Component 3. Project and C Consultant Qualifi Open - Internationa Under Implement ation environnementale et so IDA / 70200 hange Management, and Em Post 400,000.00 0.00 2023-04-25 2023-05-12 2023-05-16 2023-06-29 2023-07-29 2023-09-02 2024-02-29 cation Selection l ation ciale stratégique et (ii) évalu ergency Response ation du partage des bénéfic es de l’exploitation minière a vec les communautés locales ZR-COREF-355997-CS-CQS / Recrutement du Cabinet Inte rnational chargé d'effectuer l' Component 1. Strengthening étude de cadrage sur l'artisa Public Resources Manageme Consultant Qualifi Open - Internationa Pending Impleme IDA / 70200 Post 200,000.00 0.00 2023-04-25 2023-05-16 2023-06-29 2023-07-29 2023-09-02 2024-02-29 nat minier, Filière Diamant a nt at Central Government Le cation Selection l ntation u Kasaï Oriental et Kasaï aup vel rès des régies provinciales (E TDs et Direction des recettes provinciales) ZR-COREF-356053-CS-CQS / Recrutement d'un Cabinet In Component 1. Strengthening dépendant chargé d'élaborer Public Resources Manageme Consultant Qualifi Open - Internationa Pending Impleme le Rapport sur l'artisanat min IDA / 70200 Post 130,000.00 0.00 2023-04-25 2023-05-16 2023-06-29 2023-07-29 2023-09-02 2024-02-29 nt at Central Government Le cation Selection l ntation ier, Filière Diamant au Kasaï vel Oriental et Kasaï auprès des régies provinciales (ETD et Di rection des recettes provinci ales). ZR-COREF-355930-CS-CQS / Recrutement d'un cabinet ch Component 3. Project and C Consultant Qualifi Open - Internationa Under Implement argé de l'audit financier et co IDA / 70200 hange Management, and Em Post 50,000.00 0.00 2023-04-18 2023-04-24 2023-05-09 2023-06-22 2023-07-22 2023-08-26 2024-02-22 cation Selection l ation mptable du Projet ENCORE p ergency Response our l'exercice clos 2022 com prenant aussi le PPA ZR-COREF-355935-CS-QCBS / Recrutement d'un cabinet c Component 3. Project and C Quality And Cost- Open - Internationa hargé de l'audit financier et c IDA / 70200 hange Management, and Em Post 150,000.00 0.00 Under Review 2023-05-05 2023-04-24 2023-05-26 2023-06-11 2023-07-09 2023-08-08 2023-09-12 2023-10-17 2024-10-16 Based Selection l omptable du Projet ENCORE ergency Response pour les Exercices 2023, 202 4 et 2025 ZR-COREF-345046-CS-QCBS Component 3. Project and C Quality And Cost- Open - Internationa / Recrutement d'un auditeur IDA / 70200 hange Management, and Em Post 120,000.00 0.00 Canceled 2023-03-10 2023-03-16 2023-03-31 2023-04-16 2023-05-14 2023-06-13 2023-07-18 2023-08-22 2024-08-21 Based Selection l externe (cabinet) ergency Response INDIVIDUAL CONSULTANTS Page 5 Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-COREF-264859-CS-INDV / Sélection d'un Consultant ind Component 3. Project and C Individual Consult ividuel pour la rédaction du IDA / 70200 hange Management, and Em Post Open 30,000.00 43,000.00 Completed 2021-12-15 2021-12-15 2022-01-13 2022-03-01 2022-01-20 2022-03-29 2022-02-01 2022-04-10 2022-04-28 2023-02-25 ant Selection manuel de vérification des P ergency Response BCs et PBPs du Projet ENCOR E ZR-COREF-265030-CS-INDV / Sélection d'un consultant indi Component 2. Supporting viduel pour réaliser une étud Resource Management at th Individual Consult e de faisabilité pour la mise e IDA / 70200 Post Open 50,000.00 0.00 Canceled 2021-12-20 2022-02-24 2022-01-22 2022-02-01 2022-02-14 2022-04-30 e Provincial Government Lev ant Selection n place des administrations p el rovinciales du trésor, de la co mptabilité et du budget dans 4 provinces identifiées ZR-COREF-265038-CS-INDV / Sélection d'un Consultant ind Component 3. Project and C ividuel chargé de finaliser le Individual Consult IDA / 70200 hange Management, and Em Post Open 25,000.00 22,035.00 Completed 2021-11-25 2021-12-15 2021-12-28 2022-02-18 2022-01-07 2022-03-11 2022-01-19 2022-03-15 2022-04-30 2022-07-12 Plan de mobilisation des parti ant Selection ergency Response es prenantes (PMPP) et les Pr océdures de gestion de main -d’œuvre (PGMO) ZR-COREF-265039-CS-INDV / Component 3. Project and C Sélection d'un Consultant ind Individual Consult IDA / 70200 hange Management, and Em Post Open 25,000.00 24,893.00 Completed 2021-12-20 2021-12-15 2022-01-15 2022-03-01 2022-01-29 2022-03-11 2022-02-09 2022-03-15 2022-04-30 2022-07-14 ividuel chargé de finaliser le ant Selection ergency Response Plan d'Action VBG - EAS/HS ZR-COREF-265078-CS-CDS / Sélection d'un Consultant Na Component 1. Strengthening tional individuel en Administr Public Resources Manageme ation Publique chargé d’appu / Post Direct Selection Direct 14,000.00 0.00 Canceled 2021-12-07 2021-12-15 2021-12-30 2022-04-30 nt at Central Government Le yer la mise en œuvre du Syst vel ème Intégré de Gestion des Ressources Humaines et de l a Paie (SIGRH-Paie)/ Jean LE MA ZR-COREF-265088-CS-INDV / Sélection d'un consultant int Component 1. Strengthening ernational pour 4 mois (CTP) Public Resources Manageme Individual Consult chargé d’accompagner l’équi IDA / 70200 Post Limited 40,000.00 0.00 Signed 2021-12-20 2022-03-08 2021-12-25 2022-03-29 2022-01-15 2022-12-30 2022-02-01 2022-04-02 nt at Central Government Le ant Selection pe technique nationale dans l vel 'organisation de l'enquête et l'actualisation de la base d'éc hantillonnage (ECVM) ZR-COREF-265089-CS-INDV / Sélection d'un consultant int Component 1. Strengthening ernational expert en sondage Public Resources Manageme Individual Consult pour 4 mois chargé d’accom IDA / 70200 Post Limited 40,000.00 0.00 Canceled 2021-12-10 2022-03-08 2021-12-15 2021-12-29 2022-01-10 2022-04-30 nt at Central Government Le ant Selection pagner l’équipe technique na vel tionale dans l'organisation de l'enquête et l'actualisation de la base d'échantillonnage ZR-COREF-265092-CS-INDV / Sélection d'un consultant int Component 1. Strengthening ernational expert en CAPI po Public Resources Manageme Individual Consult ur 2 mois chargé d’accompa IDA / 70200 Post Limited 20,000.00 0.00 Signed 2021-12-15 2022-03-08 2021-12-20 2022-03-29 2022-01-03 2023-03-03 2022-01-15 2022-04-30 nt at Central Government Le ant Selection gner l’équipe technique natio vel nale dans l'organisation de l' enquête et l'actualisation de la base d'échantillonnage (EC VM) ZR-COREF-265093-CS-CDS / Component 3. Project and C Recrutement d'un Coordonna IDA / 70200 hange Management, and Em Post Direct Selection Direct 28,000.00 29,600.00 Completed 2021-12-10 2021-12-23 2021-12-18 2021-12-24 2021-12-30 2021-12-25 2022-04-30 2022-04-26 teur National du Projet (Gode ergency Response froid MISENGA) ZR-COREF-265097-CS-CDS / Recrutement d'un Spécialiste Component 3. Project and C en charge de la réforme du s IDA / 70200 hange Management, and Em Post Direct Selection Direct 18,000.00 19,200.00 Completed 2021-12-10 2022-01-11 2021-12-18 2022-01-12 2021-12-30 2022-01-13 2022-04-30 2022-04-26 ystème des marchés publics ergency Response (Jean Baptiste VEKO) ZR-COREF-265098-CS-CDS / Recrutement d'un Spécialiste Component 3. Project and C en charge de la réforme du s IDA / 70200 hange Management, and Em Post Direct Selection Direct 18,000.00 19,200.00 Completed 2021-12-10 2022-01-10 2021-12-18 2022-01-10 2021-12-30 2022-01-11 2022-04-30 2022-04-26 ystème comptable et gestion ergency Response de la trésorerie (Robert BAM BA) ZR-COREF-265100-CS-CDS / Recrutement d'un Spécialiste Component 3. Project and C en charge de la réforme de l' / hange Management, and Em Post Direct Selection Direct 18,000.00 0.00 Canceled 2021-12-10 2021-12-18 2021-12-30 2022-04-30 administration fiscale et gesti ergency Response on des revenus miniers (Jean Pierre SAMOLIA) ZR-COREF-265101-CS-CDS / Component 3. Project and C Recrutement d'un Spécialiste IDA / 70200 hange Management, and Em Post Direct Selection Direct 18,000.00 19,200.00 Completed 2021-12-10 2022-01-10 2021-12-18 2022-01-10 2021-12-30 2022-01-11 2022-04-30 2022-04-26 en charge du contrôle intern ergency Response e et externe (ETIENNE MAFW ENI) ZR-COREF-265103-CS-CDS / Component 3. Project and C Recrutement d'un Spécialiste IDA / 70200 hange Management, and Em Post Direct Selection Direct 18,000.00 19,200.00 Completed 2021-12-10 2022-01-11 2021-12-18 2022-01-12 2021-12-30 2022-01-13 2022-04-30 2022-04-26 en charge de la décentralisat ergency Response ion financière (Moise ASSANI) ZR-COREF-265104-CS-CDS / Component 3. Project and C Recrutement d'un Responsab IDA / 70200 hange Management, and Em Post Direct Selection Direct 17,200.00 18,400.00 Completed 2021-12-10 2021-12-25 2021-12-18 2021-12-28 2021-12-30 2021-12-29 2022-04-30 2022-04-26 le Administratif et Financier ( ergency Response EMILE ASELE) ZR-COREF-265105-CS-CDS / Component 3. Project and C Recrutement d'un Spécialiste IDA / 70200 hange Management, and Em Post Direct Selection Direct 17,200.00 18,400.00 Completed 2021-12-10 2021-12-23 2021-12-18 2021-12-24 2021-12-30 2021-12-25 2022-04-30 2022-04-26 Sénior en Passation des Marc ergency Response hés (Luc M. SUKADI) ZR-COREF-265106-CS-CDS / Component 3. Project and C Recrutement d'un Spécialiste IDA / 70200 hange Management, and Em Post Direct Selection Direct 17,200.00 18,400.00 Completed 2021-12-10 2021-12-23 2021-12-18 2021-12-24 2021-12-30 2021-12-25 2022-04-30 2022-04-26 sénior en Suivi & Evaluation ergency Response (Jules KWILU) ZR-COREF-265107-CS-CDS / Component 3. Project and C Recrutement d'un (e) Assista IDA / 70200 hange Management, and Em Post Direct Selection Direct 11,400.00 12,400.00 Completed 2021-12-10 2021-12-23 2021-12-18 2021-12-24 2021-12-30 2021-12-25 2022-04-30 2022-04-26 nt (e) principal (e) de coordin ergency Response ation (Véronique MANYA) Page 6 ZR-COREF-265110-CS-CDS / Component 3. Project and C Recrutement d'un (e) Assista IDA / 70200 hange Management, and Em Post Direct Selection Direct 6,000.00 7,000.00 Completed 2021-12-10 2021-12-23 2021-12-18 2021-12-24 2021-12-30 2021-12-25 2022-04-30 2022-04-26 nt (e) en Passation des marc ergency Response hés (Gisele MUAHUKA) ZR-COREF-265111-CS-INDV / Component 3. Project and C Individual Consult Recrutement d'un (e) Récepti IDA / 70200 hange Management, and Em Post Limited 4,000.00 1,000.00 Completed 2021-12-07 2021-12-15 2021-12-21 2021-12-28 2021-12-24 2021-12-29 2021-12-30 2022-01-01 2022-04-30 2022-04-26 ant Selection onniste ergency Response ZR-COREF-265113-CS-CDS / Component 3. Project and C Recrutement d'un Chauffeur IDA / 70200 hange Management, and Em Post Direct Selection Direct 3,200.00 4,000.00 Completed 2021-12-10 2021-12-23 2021-12-18 2021-12-24 2021-12-30 2021-12-25 2022-04-30 2022-04-26 (Jean BELO MUYUMBA) ergency Response ZR-COREF-265253-CS-CDS / Component 3. Project and C Recrutement d'un Coordonat IDA / 70200 hange Management, and Em Post Direct Selection Direct 28,000.00 28,000.00 Completed 2021-12-10 2022-01-19 2021-12-18 2022-01-21 2021-12-30 2022-01-22 2022-04-30 2022-05-04 eur de la Cellule de Suivi des ergency Response Projets et Programmes CSPP (Honoré TSHIYOYO) ZR-COREF-265255-CS-CDS / Recrutement d'un Coordonna Component 3. Project and C teur Adjoint de la Cellule de IDA / 70200 hange Management, and Em Post Direct Selection Direct 20,000.00 20,000.00 Completed 2021-12-10 2022-01-19 2021-12-18 2022-01-21 2021-12-30 2022-01-22 2022-04-30 2022-05-04 Suivi des Projets et Program ergency Response mes CSPP ( Clément MBIKAYI ) ZR-COREF-265269-CS-CDS / Recrutement d'un Chargé de Component 3. Project and C s Projets à la Section Appui O IDA / 70200 hange Management, and Em Post Direct Selection Direct 12,000.00 12,000.00 Completed 2021-12-10 2022-01-19 2021-12-18 2022-01-21 2021-12-30 2022-01-22 2022-04-30 2022-05-04 pératoire '1) de la Cellule de ergency Response Suivi des Projets et Program mes CSPP ( Audry KAZEMBOL A) ZR-COREF-265272-CS-CDS / Recrutement d'un Chargé de Component 3. Project and C s Projets à la Section Moyens IDA / 70200 hange Management, and Em Post Direct Selection Direct 12,000.00 12,000.00 Completed 2021-12-10 2022-01-19 2021-12-18 2022-01-21 2021-12-30 2022-01-22 2022-04-30 2022-05-04 Généraux de la Cellule de Sui ergency Response vi des Projets et Programmes CSPP (GRATIAS KAYIBABU KA BUYA) ZR-COREF-265273-CS-CDS / Recrutement d'un Chargé de Component 3. Project and C s Projets à la Section Fiduciai IDA / 70200 hange Management, and Em Post Direct Selection Direct 12,000.00 12,000.00 Completed 2021-12-10 2022-01-19 2021-12-18 2022-02-19 2021-12-30 2022-01-22 2022-04-30 2022-05-04 re de la Cellule de Suivi des P ergency Response rojets et Programmes CSPP ( Diamant EBENE) ZR-COREF-265276-CS-CDS / Recrutement d'un Chargé de Component 3. Project and C s Projets à la Section Fiduciai IDA / 70200 hange Management, and Em Post Direct Selection Direct 12,000.00 12,000.00 Completed 2021-12-10 2022-01-19 2021-12-18 2022-01-21 2021-12-30 2022-01-22 2022-04-30 2022-05-04 re de la Cellule des Projets et ergency Response Programmes CSPP (Lourlaine MUANZA) ZR-COREF-265277-CS-CDS / Recrutement d'un Chargé de Component 3. Project and C s Projets à la Section Appui O IDA / 70200 hange Management, and Em Post Direct Selection Direct 12,000.00 12,000.00 Completed 2021-12-10 2022-01-19 2021-12-18 2022-01-21 2021-12-30 2022-01-22 2022-04-30 2022-05-04 pératoire de la Cellule de Sui ergency Response vi des Projets et Programmes CSPP ( Samuel KAULU) ZR-COREF-265278-CS-CDS / Recrutement d'un Chargé de Component 3. Project and C s Projets à la Section Fiduciai IDA / 70200 hange Management, and Em Post Direct Selection Direct 12,000.00 12,000.00 Completed 2021-12-10 2022-01-19 2021-12-18 2022-01-21 2021-12-30 2022-01-22 2022-04-30 2022-05-04 re de la Cellule de Suivi des P ergency Response rojets et Programmes CSPP ( Eddy MBUNGU) ZR-COREF-265419-CS-CDS / Component 1. Strengthening Sélection d'un Consultant Ind Public Resources Manageme ividuel pour appuyer la 2ème IDA / 70200 Post Direct Selection Direct 16,000.00 37,050.00 Signed 2021-12-15 2022-04-29 2021-12-25 2022-05-20 2022-01-05 2022-05-31 2022-04-30 nt at Central Government Le phase de la mise en place de vel SIGMAP (20 nouvelles cellule s)/ Pierre TSHIYOMBO ZR-COREF-265010-CS-INDV / Component 1. Strengthening Sélection d'un consultant indi Public Resources Manageme Individual Consult viduel pour la mise en place / Post Limited 50,000.00 0.00 Canceled 2021-12-24 2021-12-27 2022-01-10 2022-01-30 2022-04-30 nt at Central Government Le ant Selection d'un système de gestion bud vel gétaire en Provinces ZR-COREF-265027-CS-CDS / Sélection d'un consultant indi Component 2. Supporting viduel chargé d'appuyer l'éla Resource Management at th IDA / 70200 Post Direct Selection Direct 70,000.00 46,395.00 Completed 2022-01-03 2022-02-25 2022-01-11 2022-03-18 2022-01-29 2022-04-17 2022-04-29 2022-12-27 boration des textes fixant les e Provincial Government Lev modalités de répartition des el recettes à caractère national (Michael WINTER) ZR-COREF-267867-CS-CDS / Consultant pour l'appui à la p Component 1. Strengthening réparation de l'Enquête sur l Public Resources Manageme IDA / 70200 Post Direct Selection Direct 450,000.00 0.00 Signed 2021-12-27 2022-12-22 2022-01-06 2022-12-24 2022-01-19 2022-04-30 es Conditions de Vie des Mén nt at Central Government Le ages (ECVM): Enquête sur les vel Unités non conventionnelles (NSU) avec PNUD Component 3. Project and C ZR-COREF-270844-CS-INDV / Individual Consult IDA / V4000 hange Management, and Em Post Limited 6,000.00 7,000.00 Completed 2021-12-27 2021-12-31 2022-01-01 2022-01-05 2022-01-02 2022-01-07 2022-01-08 2022-01-11 2022-04-30 2022-04-26 Recrutement d'un Trésorier ant Selection ergency Response ZR-COREF-265109-CS-CDS / Component 3. Project and C Recrutement d'un (e) Trésori / hange Management, and Em Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-12-10 2021-12-18 2021-12-30 2022-04-30 er (e) ( Sylvie NGEVESISE) ergency Response ZR-COREF-265108-CS-CDS / Component 3. Project and C Recrutement d'un Comptable IDA / V4000 hange Management, and Em Post Direct Selection Direct 10,000.00 11,000.00 Completed 2021-12-30 2021-12-31 2022-01-03 2022-01-04 2022-01-08 2022-01-05 2022-04-30 2022-04-26 (Sylvie NGEVESISE) ergency Response ZR-COREF-280723-CS-CDS / Component 3. Project and C Recrutement d'un Spécialiste IDA / V4000 hange Management, and Em Post Direct Selection Direct 18,000.00 9,600.00 Completed 2022-02-23 2022-02-28 2022-02-27 2022-03-01 2022-03-02 2022-03-02 2022-04-30 2022-04-26 en charge du suivi des donn ergency Response ées statistiques sur la pauvre té (SASSE KEMBE) ZR-COREF-296056-CS-CDS / Component 1. Strengthening Sélection d'un consultant int Public Resources Manageme IDA / V4000 Post Direct Selection Direct 50,000.00 0.00 Signed 2022-06-10 2022-06-08 2022-06-20 2022-06-18 2022-06-28 2022-09-26 ernational pour la finalisation nt at Central Government Le du cahier des charges et du vel DAO du SiGeFiP Page 7 ZR-COREF-264872-CS-INDV / Sélection d'un consultant po Component 1. Strengthening ur l'évaluation de la répartiti Public Resources Manageme Individual Consult / Post Limited 30,000.00 0.00 Canceled 2022-01-10 2022-01-24 2022-01-31 2022-02-17 2022-04-18 on effective (Etude Benefit S nt at Central Government Le ant Selection haring Assessment ou BSA) d vel es recettes minières au nivea u local (0.3% aux ETDs) ZR-COREF-265068-CS-CDS / Sélection d'un Consultant Ex pert en informatique et systè Component 1. Strengthening mes d’information chargé d’a Public Resources Manageme / Post Direct Selection Direct 14,000.00 0.00 Canceled 2021-12-07 2021-12-15 2021-12-30 2022-04-30 ppuyer la mise en œuvre du nt at Central Government Le Système Intégré de Gestion vel des Ressources Humaines et de la Paie (SIGRH-Paie)! PIER RE TSHIYOMBO ZR-COREF-265080-CS-CDS / Component 1. Strengthening Sélection d'un Consultant int Public Resources Manageme ernational chargé de l' appui IDA / V4000 Post Direct Selection Direct 100,000.00 63,625.00 Completed 2022-05-30 2022-05-31 2022-06-07 2022-06-13 2022-06-22 2022-07-08 2022-10-21 2022-12-27 nt at Central Government Le a la mise en œuvre du SIGRH vel -Paie/ GERARD VERGER ZR-COREF-265082-CS-CDS / Sélection d'un Consultant ind Component 1. Strengthening ividuel chargé de la concepti Public Resources Manageme on et la mise en œuvre d’une / Post Direct Selection Direct 45,000.00 0.00 Canceled 2021-12-20 2021-12-28 2022-01-12 2022-04-30 nt at Central Government Le plateforme web pour la mise vel à jour du fichier de référence des agents de l’Administratio n publique (FRAP 2)/BOB BOS EKO ZR-COREF-265412-CS-INDV / Sélection d'un Consultant Ind Component 3. Project and C ividuel pour le développeme Individual Consult / hange Management, and Em Post Limited 50,000.00 0.00 Canceled 2022-01-07 2022-02-16 2022-01-21 2022-01-31 2022-02-17 2022-04-18 nt , le paramétrage et la mis ant Selection ergency Response e en service du logiciel de st ockage et analyse des donné es du Suivi-Evaluation ZR-COREF-265411-CS-INDV / Sélection d'un Consultant Ind Component 3. Project and C ividuel pour le développeme Individual Consult IDA / 70200 hange Management, and Em Post Limited 30,000.00 0.00 Canceled 2021-12-20 2022-02-23 2022-01-03 2022-01-13 2022-01-30 2022-04-30 nt, le paramétrage et la mise ant Selection ergency Response en service du logiciel de gest ion de projet (technique et m ise en œuvre des activités) ZR-COREF-265095-CS-CDS / Component 3. Project and C Recrutement d'un Spécialiste IDA / 70200 hange Management, and Em Post Direct Selection Direct 18,000.00 0.00 Canceled 2021-12-10 2022-01-10 2021-12-18 2021-12-30 2022-04-30 en charge du suivi des donn ergency Response ées statistiques sur la pauvre té (SASSE KEMBE) ZR-COREF-296648-CS-INDV / Component 3. Project and C Recrutement du Coordonnat Individual Consult IDA / 70200 hange Management, and Em Post Limited 42,000.00 0.00 Signed 2022-06-10 2022-06-02 2022-06-24 2022-06-24 2022-07-08 2022-08-19 2022-07-21 2023-07-21 eur Provincial de la province ant Selection ergency Response du Kasaï Central ZR-COREF-296654-CS-INDV / Component 3. Project and C Recrutement d'un Coordonna Individual Consult IDA / 70200 hange Management, and Em Post Limited 42,000.00 38,400.00 Signed 2022-06-10 2022-06-02 2022-06-24 2022-06-24 2022-07-08 2022-07-04 2022-07-21 2022-08-20 2023-07-21 teur Provincial pour la provin ant Selection ergency Response ce du Kasaï Oriental ZR-COREF-296655-CS-INDV / Component 3. Project and C Individual Consult Recrutement d'un Coordonna IDA / 70200 hange Management, and Em Post Limited 42,000.00 0.00 Signed 2022-06-10 2022-06-02 2022-06-24 2022-06-24 2022-07-08 2022-08-19 2022-07-21 2023-07-21 ant Selection teur provincial pour la provin ergency Response ce de Lomami ZR-COREF-296656-CS-INDV / Component 3. Project and C Individual Consult Recrutement d'un Coordonna IDA / 70200 hange Management, and Em Post Limited 42,000.00 38,400.00 Signed 2022-06-10 2022-06-02 2022-06-24 2022-06-24 2022-07-08 2022-07-15 2022-07-21 2022-08-20 2023-07-21 ant Selection teur provincial pour la provin ergency Response ce du Kasaï ZR-COREF-296657-CS-INDV / Component 3. Project and C Recrutement d'un Assistant P Individual Consult IDA / 70200 hange Management, and Em Post Limited 24,000.00 0.00 Signed 2022-06-15 2022-06-02 2022-06-29 2022-06-24 2022-07-13 2022-08-20 2022-07-26 2023-07-26 rovincial chargé de l'Administ ant Selection ergency Response ration et Finances de la Provi nce du Kasaï Central ZR-COREF-296661-CS-INDV / Recrutement de l'Assistant Pr Component 3. Project and C Individual Consult ovincial Chargé de l'Administ IDA / 70200 hange Management, and Em Post Limited 24,000.00 0.00 Signed 2022-06-15 2022-06-02 2022-06-29 2022-06-24 2022-07-13 2022-08-20 2022-07-26 2023-07-26 ant Selection ration et Finances de la provi ergency Response nce du Kasaï Oriental ZR-COREF-296662-CS-INDV / Component 3. Project and C Recrutement de l'Assistant Pr Individual Consult IDA / 70200 hange Management, and Em Post Limited 24,000.00 0.00 Signed 2022-06-15 2022-06-02 2022-06-29 2022-06-24 2022-07-13 2022-08-20 2022-07-26 2023-07-26 ovincial chargé de l'Administr ant Selection ergency Response ation et Finances de la provin ce de Lomami ZR-COREF-296665-CS-INDV / Component 3. Project and C Recrutement de l'Assistant Pr Individual Consult IDA / 70200 hange Management, and Em Post Limited 24,000.00 0.00 Signed 2022-06-15 2022-06-08 2022-06-29 2022-06-24 2022-07-13 2022-08-20 2022-07-26 2023-07-26 ovincial chargé de l'Administr ant Selection ergency Response ation et Finances de la provin ce du Kasaï ZR-COREF-298958-CS-INDV / Component 3. Project and C Sélection d'un Consultant Sp Individual Consult IDA / 70200 hange Management, and Em Post Limited 51,600.00 55,200.00 Signed 2022-06-15 2022-06-08 2022-06-20 2022-06-23 2022-07-04 2022-07-27 2022-07-25 2022-07-28 2023-07-20 écialiste en Passation des ma ant Selection ergency Response rchés du Projet ENCORE ZR-COREF-305471-CS-INDV / Component 3. Project and C Recrutement d'Un Deuxième Individual Consult IDA / 70200 hange Management, and Em Post Limited 54,180.00 0.00 Signed 2022-08-15 2022-08-17 2022-08-20 2022-09-15 2022-08-27 2023-04-04 2022-09-13 2023-09-13 Spécialiste en SUivi Evaluatio ant Selection ergency Response n du Projet ENCORE ZR-COREF-305481-CS-INDV / Component 3. Project and C Individual Consult Recrutement d'un (e) Chargé IDA / 70200 hange Management, and Em Post Limited 31,500.00 0.00 Signed 2022-08-15 2022-08-17 2022-08-20 2022-09-13 2022-09-03 2022-09-29 2022-09-24 2023-09-24 ant Selection (e) de Communication du Pro ergency Response jet ENCORE ZR-COREF-305484-CS-INDV / Component 3. Project and C Individual Consult Recrutement d'un (e) Trésori IDA / 70200 hange Management, and Em Post Limited 18,900.00 0.00 Signed 2022-08-10 2022-08-17 2022-08-17 2022-09-13 2022-08-31 2022-09-23 2022-09-26 2022-11-01 ant Selection er (e) du Projet ENCORE ergency Response ZR-COREF-305485-CS-INDV / Component 3. Project and C Individual Consult Recrutement d'un (e) Caissie IDA / 70200 hange Management, and Em Post Limited 15,000.00 0.00 Signed 2022-08-10 2022-08-17 2022-08-17 2022-09-23 2022-08-31 2022-09-29 2022-09-26 2023-09-26 ant Selection r (e) du Projet ENCORE ergency Response ZR-COREF-305486-CS-INDV / Component 3. Project and C Individual Consult Recrutement d'un Comptable IDA / 70200 hange Management, and Em Post Limited 31,500.00 0.00 Signed 2022-08-15 2022-08-17 2022-08-20 2022-09-14 2022-09-10 2022-09-29 2022-10-15 2023-10-15 ant Selection Pour le Projet ENCORE ergency Response Page 8 ZR-COREF-305499-CS-INDV / Component 3. Project and C Recrutement d'un Chauffeur Individual Consult IDA / 70200 hange Management, and Em Post Limited 12,600.00 0.00 Signed 2022-08-15 2022-08-17 2022-08-20 2022-09-13 2022-08-27 2022-09-23 2022-09-15 2023-09-15 coursier de la Coordination d ant Selection ergency Response u Projet ENCORE ZR-COREF-305502-CS-INDV / Component 3. Project and C Recrutement d'un Deuxième Individual Consult IDA / 70200 hange Management, and Em Post Limited 10,800.00 0.00 Signed 2022-08-15 2022-08-17 2022-08-20 2022-09-13 2022-08-27 2022-09-23 2022-09-15 2023-09-15 Chauffeur Coursier de la Coor ant Selection ergency Response dination du Projet ENCORE ZR-COREF-305512-CS-INDV / Component 3. Project and C Recrutement d'un (e) Récepti Individual Consult IDA / 70200 hange Management, and Em Post Limited 12,600.00 0.00 Signed 2022-08-15 2022-08-17 2022-08-29 2022-09-13 2022-09-01 2022-09-23 2022-09-07 2023-09-07 onniste de la Coordination Na ant Selection ergency Response tionale du Projet ENCORE ZR-COREF-305514-CS-INDV / Component 3. Project and C Recrutement d'un (e) deuxiè Individual Consult IDA / 70200 hange Management, and Em Post Limited 12,600.00 0.00 Signed 2022-08-15 2022-08-17 2022-08-29 2022-09-13 2022-09-01 2022-09-23 2022-09-07 2023-09-07 me Réceptionniste de la Coor ant Selection ergency Response dination Nationale du projet ENCORE ZR-COREF-305517-CS-INDV / Component 3. Project and C Recrutement d'un (e) Spécial Individual Consult Under Implement IDA / 70200 hange Management, and Em Post Limited 56,700.00 0.00 2022-08-15 2023-04-12 2022-08-20 2022-09-03 2022-09-24 2023-09-24 iste chargé des systèmes d'i ant Selection ation ergency Response nformation du Projet ENCORE ZR-COREF-305522-CS-INDV / Recrutement d'un (e) Spécial Component 3. Project and C Individual Consult iste en charge de la réforme IDA / 70200 hange Management, and Em Post Limited 56,700.00 0.00 Signed 2022-08-15 2022-08-17 2022-08-20 2022-09-23 2022-09-03 2022-09-29 2022-09-24 2023-09-24 ant Selection de l'Administration fiscale et ergency Response gestion des revenus miniers ZR-COREF-305531-CS-INDV / Recrutement d'un (e) Spécial Component 3. Project and C Individual Consult iste en charge de la surveilla IDA / 70200 hange Management, and Em Post Limited 56,700.00 0.00 Signed 2022-08-15 2022-08-17 2022-08-20 2022-08-22 2022-09-10 2022-09-29 2022-10-01 2023-10-01 ant Selection nce des risques budgétaires l ergency Response iés à la gestion des Entrepris es publiques ZR-COREF-305540-CS-INDV / Component 3. Project and C Recrutement d'un Spécialiste Individual Consult IDA / 70200 hange Management, and Em Post Limited 54,180.00 0.00 Signed 2022-08-15 2022-08-17 2022-08-20 2022-09-15 2022-09-03 2022-11-22 2022-09-24 2022-10-30 en Charge des questions des ant Selection ergency Response Violences basées sur le genr e ZR-COREF-305547-CS-INDV / Component 3. Project and C Recrutement d'un (e) Spécial Individual Consult IDA / 70200 hange Management, and Em Post Limited 54,180.00 0.00 Signed 2022-08-15 2022-08-17 2022-08-20 2022-09-15 2022-09-03 2022-11-22 2022-09-24 2023-09-24 iste en sauvegarde environn ant Selection ergency Response ementale et sociale du projet ENCORE ZR-COREF-305557-CS-INDV / Component 3. Project and C Individual Consult Pending Impleme Recrutement d'un Assistant I IDA / 70200 hange Management, and Em Post Limited 18,900.00 0.00 2022-08-15 2022-08-20 2022-09-03 2022-09-24 2023-09-24 ant Selection ntation T ergency Response ZR-COREF-305561-CS-INDV / Component 3. Project and C Recrutement d'un (e) Assista Individual Consult IDA / 70200 hange Management, and Em Post Limited 25,200.00 0.00 Signed 2022-08-15 2022-08-17 2022-08-20 2022-08-22 2022-09-03 2022-08-29 2022-09-24 2023-09-24 nt (e) en décentralisation fin ant Selection ergency Response ancière et Budget Participatif ZR-COREF-305564-CS-INDV / Recrutement d'un Spécialiste Component 3. Project and C Individual Consult en charge de la gestion du c IDA / 70200 hange Management, and Em Post Limited 56,700.00 0.00 Signed 2022-08-15 2022-08-17 2022-08-20 2022-08-26 2022-09-03 2022-08-30 2022-09-24 2023-09-24 ant Selection hangement et du Budget Par ergency Response ticipatif du projet ENCORE ZR-COREF-305496-CS-CDS / Component 3. Project and C Renouvellement contrat du C IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 9,600.00 12,000.00 Signed 2022-07-25 2022-08-19 2022-07-28 2022-08-19 2022-08-02 2022-08-20 2024-08-01 hauffeur de la Coordination N ergency Response ationale du Projet ENCORE - BELO MUYUMBA ZR-COREF-305107-CS-CDS / Component 3. Project and C Renouvellement du contrat d IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 54,000.00 57,600.00 Signed 2022-07-25 2022-08-19 2022-07-28 2022-08-19 2022-08-02 2022-08-20 2024-08-01 u Spécialiste en charge du co ergency Response ntrôle interne et externe - Eti enne Mafweni ZR-COREF-305468-CS-CDS / Component 3. Project and C Renouvellement du Contrat d IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 51,600.00 55,200.00 Signed 2022-07-25 2022-08-19 2022-07-28 2022-08-19 2022-08-02 2022-08-20 2024-08-01 u Responsable Administratif ergency Response et Financier (RAF) du Projet E NCORE - Emile ASELE ZR-COREF-305470-CS-CDS / Component 3. Project and C Renouvellement Contrat du S IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 51,600.00 55,200.00 Signed 2022-07-25 2022-08-19 2022-07-28 2022-08-19 2022-08-02 2022-08-20 2024-08-01 pécialiste en Suivi Evaluation ergency Response du Projet ENCORE - Jules KWI LU ZR-COREF-305487-CS-INDV / Component 3. Project and C Individual Consult Under Implement Recrutement d'un Deuxième IDA / 70200 hange Management, and Em Post Limited 30,000.00 0.00 2022-08-15 2022-08-19 2022-08-20 2022-11-03 2022-09-10 2022-11-18 2022-10-15 2023-10-15 ant Selection ation Comptable du Projet ENCORE ergency Response ZR-COREF-305098-CS-CDS / Renouvellement du Contrat d Component 3. Project and C u Spécialiste en charge de la IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 54,000.00 57,600.00 Signed 2022-07-25 2022-08-19 2022-07-28 2022-08-19 2022-08-02 2022-08-20 2024-08-01 Réforme du système de la co ergency Response mptabilité et gestion de la tr ésorerie - Robert Bamba ZR-COREF-305478-CS-CDS / Component 3. Project and C Renouvellement contrat de l' IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 34,200.00 37,800.00 Signed 2022-07-25 2022-08-19 2022-07-28 2022-08-19 2022-08-02 2022-08-20 2024-08-01 Assistante Principale du Proje ergency Response t ENCORE (APP) - Véronique MANYA ZR-COREF-305112-CS-CDS / Renouvellement du contrat d Component 3. Project and C u Spécialiste en charge du su IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 54,000.00 57,600.00 Signed 2022-07-25 2022-08-19 2022-07-28 2022-08-19 2022-08-02 2022-08-20 2024-08-01 ivi des données statistiques s ergency Response ur la Pauvreté du Projet ENC ORE - Sasse Kembe ZR-COREF-305110-CS-CDS / Renouvellement du Contrat d Component 3. Project and C u Spécialiste en charge de la IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 54,000.00 57,600.00 Signed 2022-07-25 2022-08-19 2022-07-28 2022-08-19 2022-08-02 2022-08-20 2024-08-01 réforme du système des mar ergency Response chés publics et gestion de la dépense - Jean Baptiste VEK O ZR-COREF-305483-CS-CDS / Component 3. Project and C Recrutement Chargée de Pas IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 36,000.00 39,600.00 Signed 2022-07-25 2022-08-19 2022-07-28 2022-08-19 2022-08-02 2022-08-20 2024-08-01 sation des Marchés du Projet ergency Response ENCORE (Gisèle MUAHUKA) Page 9 ZR-COREF-305090-CS-CDS / Component 3. Project and C Renouvellement Contrat du C IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 84,000.00 88,800.00 Signed 2022-07-25 2022-08-19 2022-07-28 2022-08-19 2022-08-02 2022-08-20 2024-08-01 oordonnateur National du Pro ergency Response jet ENCORE - Godefroid MISE NGA MILABYO ZR-COREF-305094-CS-CDS / Component 3. Project and C Renouvellement du Contrat S IDA / 70200 hange Management, and Em Post Direct Selection Direct - National 54,000.00 57,600.00 Signed 2022-07-25 2022-08-19 2022-07-28 2022-08-19 2022-08-02 2022-08-20 2024-08-01 pécialiste en charge de la Dé ergency Response centralisation financière - Moi se ASSANI ZR-COREF-310943-CS-INDV / Selection d'un consultant int Component 1. Strengthening ernational expert en sondage Public Resources Manageme Individual Consult pour 4 mois chargé d'accom IDA / 70200 Post Limited 40,000.00 0.00 Signed 2022-08-31 2022-08-19 2022-09-03 2022-08-24 2022-09-08 2022-11-28 2022-09-15 2023-01-13 nt at Central Government Le ant Selection pagner l'équipe technique na vel tional dans l'organisation de l 'enquête et l'actualisation de la base d'échantilllonnage ZR-COREF-344138-CS-INDV / Recrutement d'un Consultant National pour assurer la form Component 1. Strengthening ation des agents des services Public Resources Manageme Individual Consult Under Implement d'assiette et de recouvremen IDA / 70200 Post Open - National 70,000.00 0.00 2023-03-18 2023-04-10 2023-04-27 2023-05-18 2023-06-22 2023-12-19 nt at Central Government Le ant Selection ation t (DGRAD et administrations vel de mines) sur la maitrise de l 'assiette de la redevance min ière dans les 5 sites miniers de la RDC : Kinshasa, H ZR-COREF-344146-CS-INDV / Recrutement d'un Consultant International pour assurer la Component 1. Strengthening formation à Kinshasa sur la c Public Resources Manageme Individual Consult Open - Internationa Under Implement haîne de valeur de l'industrie IDA / 70200 Post 100,000.00 0.00 2023-03-15 2023-04-10 2023-04-24 2023-05-15 2023-06-19 2023-12-16 nt at Central Government Le ant Selection l ation extractive minière, sur les sp vel écificités comptable et la Fis calité du secteur des mines ( DGI) des vérificateurs proven ant des 5 sites mi ZR-COREF-344206-CS-INDV / Recrutement d'un Consultant Component 1. Strengthening National pour évaluer le nive Public Resources Manageme Individual Consult Under Implement IDA / 70200 Post Open - National 40,000.00 0.00 2023-02-25 2023-04-10 2023-03-18 2023-04-08 2023-05-13 2023-11-09 au d'exécution des réformes nt at Central Government Le ant Selection ation engagées par les entreprises vel Publiques du secteur extracti f. ZR-COREF-344209-CS-INDV / Component 1. Strengthening Recrutement des deux (02) c Public Resources Manageme Individual Consult onsultants individuels pour l IDA / 70200 Post Open - National 60,000.00 0.00 Under Review 2023-03-03 2023-06-01 2023-03-24 2023-04-07 2023-05-12 2023-11-08 nt at Central Government Le ant Selection a mise à jour des guides d’él vel aboration du PEB et du PTR e n lien avec le PPM ZR-COREF-344299-CS-INDV / Component 1. Strengthening Recrutement d'un consultant Public Resources Manageme Individual Consult Pending Impleme IDA / 70200 Post Open - National 30,000.00 0.00 2023-07-03 2023-08-12 2023-08-26 2023-09-30 2024-03-28 individuel pour la production nt at Central Government Le ant Selection ntation du guide de contrôle budgéta vel ire ZR-COREF-344310-CS-INDV / Component 1. Strengthening Recrutement d'un consultant Public Resources Manageme Individual Consult Pending Impleme individuel pour la production IDA / 70200 Post Open - National 30,000.00 0.00 2023-10-02 2023-11-20 2023-12-11 2024-01-15 2024-07-13 nt at Central Government Le ant Selection ntation du projet de plan de renforce vel ment des capacités des contr ôleurs budgétaires ZR-COREF-344314-CS-INDV / Recrutement d'un consultant Component 1. Strengthening international devant mener u Public Resources Manageme Individual Consult Open - Internationa Pending Impleme ne étude de faisabilité sur la IDA / 70200 Post 70,000.00 0.00 2023-03-20 2023-05-08 2023-05-29 2023-07-03 2023-12-30 nt at Central Government Le ant Selection l ntation mise en place du Compte Uni vel que du Trésor et son architec ture favorable au cadre instit utionnel de la RDC ZR-COREF-344327-CS-INDV / Recrutement d'un consultant Component 1. Strengthening international et d'un consulta Public Resources Manageme Individual Consult Pending Impleme nt national pour mener une é IDA / 70200 Post Limited 100,000.00 0.00 2023-03-27 2023-04-01 2023-04-22 2023-05-27 2023-11-23 nt at Central Government Le ant Selection ntation tude relative à la mise en pla vel ce d'une solution informatiqu e nécessaire au fonctionnem ent du CUT ZR-COREF-344350-CS-INDV / Component 1. Strengthening Recrutement d'un consultant Public Resources Manageme Individual Consult Open - Internationa Under Implement International chargé d'optimi IDA / 70200 Post 100,000.00 0.00 2023-03-22 2023-04-24 2023-05-10 2023-05-31 2023-07-05 2024-01-01 nt at Central Government Le ant Selection l ation ser les macro-processus de g vel estion des ressources humai nes et de la paie ZR-COREF-344399-CS-INDV / Recrutement d'un consultant Component 1. Strengthening International pour les Etudes Public Resources Manageme Individual Consult Open - Internationa Pending Impleme IDA / 70200 Post 60,000.00 0.00 2023-03-10 2023-04-28 2023-05-19 2023-06-23 2023-12-20 de faisabilités relatives au ré nt at Central Government Le ant Selection l ntation seau étendu en fibre optique vel et boucle radio local de l’Ad ministration Publique ZR-COREF-344421-CS-INDV / Component 1. Strengthening Recrutement d'un consultant Public Resources Manageme Individual Consult Pending Impleme individuel pour accompagner IDA / 70200 Post Limited 40,000.00 0.00 2023-03-29 2023-04-03 2023-04-24 2023-05-29 2023-07-13 nt at Central Government Le ant Selection ntation le processus de sélection de l vel 'Assistance en maitrise d'ouv rage du SiGeFiP ZR-COREF-344445-CS-INDV / Recrutement d'un consultant Component 1. Strengthening international chargé de l'assi Public Resources Manageme Individual Consult Open - Internationa Under Implement stance technique à l'ARMP po IDA / 70200 Post 70,000.00 0.00 2023-04-03 2023-06-21 2023-05-22 2023-06-12 2023-07-17 2023-09-15 nt at Central Government Le ant Selection l ation ur la révision du cadre juridiq vel ue des marchés publics en te nant compte de la dématéria lisation du processus ZR-COREF-344466-CS-INDV / Recrutement d'un consultant Component 1. Strengthening international chargé de la for Public Resources Manageme Individual Consult Open - Internationa Pending Impleme IDA / 70200 Post 80,000.00 0.00 2023-03-30 2023-04-20 2023-05-11 2023-06-15 2023-08-14 mation des auditeurs de l'AR nt at Central Government Le ant Selection l ntation MP en MP et PPP ainsi que la vel redaction du manuel de proc edures des audits. ZR-COREF-344495-CS-INDV / Component 1. Strengthening Individual Consult Pending Impleme Recrutement d'un webmaste IDA / 70200 Public Resources Manageme Post Limited 50,000.00 0.00 2023-04-01 2023-04-06 2023-04-27 2023-06-01 2023-07-31 ant Selection ntation r pour l'audit du site web du nt at Central Government Le CSP vel Page 10 ZR-COREF-344499-CS-INDV / Component 1. Strengthening Recrutement d'un web maste Public Resources Manageme Individual Consult Pending Impleme r pour développement du sit IDA / 70200 Post Open - National 50,000.00 0.00 2023-03-17 2023-05-05 2023-05-26 2023-06-30 2023-12-27 nt at Central Government Le ant Selection ntation e web du Ministère du Portef vel euille conformément au plan national de numérisation ZR-COREF-344503-CS-INDV / Recrutement d'un Web Mast Component 1. Strengthening er pour le développement d’ Public Resources Manageme Individual Consult Under Implement un portail au niveau des entr IDA / 70200 Post Open - National 50,000.00 0.00 2023-03-14 2023-04-11 2023-04-23 2023-05-14 2023-06-18 2023-12-15 nt at Central Government Le ant Selection ation eprises sur les informations à vel collecter et à échanger avec possibilité d’interaction en lig ne avec le CSP. ZR-COREF-344504-CS-INDV / Recrutement d'un consultant pour la production du projet Component 1. Strengthening de guide pour l'examen du ra Public Resources Manageme Individual Consult Under Implement pport consolidé de la situatio IDA / 70200 Post Open - National 50,000.00 0.00 2023-04-05 2023-05-20 2023-05-15 2023-06-05 2023-07-10 2023-09-08 nt at Central Government Le ant Selection ation n financière des entreprises vel publiques à l'usage des mem bres des services techniques des commission ECOFIN de l' Assemblée National et du Sé n ZR-COREF-344514-CS-INDV / Recrutement d'un consultant Component 1. Strengthening pour l’élaboration d’un manu Public Resources Manageme Individual Consult Under Implement IDA / 70200 Post Open - National 50,000.00 0.00 2023-04-10 2023-05-20 2023-05-29 2023-06-19 2023-07-24 2023-10-22 el des procédures en matière nt at Central Government Le ant Selection ation de contrôle et audit des entr vel eprises publiques et établiss ements publics ZR-COREF-344517-CS-INDV / Component 1. Strengthening Recrutement d'un consultant Public Resources Manageme Individual Consult Under Implement IDA / 70200 Post Open - National 50,000.00 0.00 2023-04-17 2023-05-20 2023-06-05 2023-06-26 2023-07-31 2024-01-27 pour la production du projet nt at Central Government Le ant Selection ation de la stratégie du Portefeuille vel ZR-COREF-344723-CS-INDV / Component 1. Strengthening Recrutement d'un consultant Public Resources Manageme Individual Consult Pending Impleme IDA / 70200 Post Open - National 50,000.00 0.00 2023-07-03 2023-08-21 2023-09-11 2023-10-16 2023-12-15 pour la production des contra nt at Central Government Le ant Selection ntation ts de performance type par s vel ecteur d'activités ZR-COREF-344749-CS-INDV / Component 1. Strengthening Recrutement d'un consultant Public Resources Manageme Individual Consult Pending Impleme national pour la production d IDA / 70200 Post Open - National 50,000.00 0.00 2023-04-01 2023-05-20 2023-06-10 2023-07-15 2023-09-13 nt at Central Government Le ant Selection ntation es contrats de concession ty vel pe des biens du domaine pub lic de l'Etat ZR-COREF-344774-CS-INDV / Recrutement des consultants nationaux pour mener l'analy Component 2. Supporting se des états de suivi budgéta Resource Management at th Individual Consult Pending Impleme ires (ESB) trimestriels et sem IDA / 70200 Post Open - National 80,000.00 0.00 2023-05-08 2023-06-26 2023-07-17 2023-08-21 2024-02-17 e Provincial Government Lev ant Selection ntation estriels des secteurs pro pau el vres (Education, Santé, Mine s, Agriculture et développem ent rural, Energie, Sécurité, I nfrastructures) et le ge ZR-COREF-344786-CS-INDV / Recrutement de consultants Component 1. Strengthening nationaux pour la formation Public Resources Manageme Individual Consult Under Implement IDA / 70200 Post Open - National 70,000.00 0.00 2023-03-30 2023-04-10 2023-05-18 2023-06-08 2023-07-13 2024-01-09 des services concernés à la p nt at Central Government Le ant Selection ation roduction et à la publication vel des documents budgétaires-c lés nationaux ZR-COREF-344812-CS-INDV / Recrutement du consultant i ndividuel chargé réaliser les Component 1. Strengthening études, la production du DAO Public Resources Manageme Individual Consult Pending Impleme IDA / 70200 Post Open - National 100,000.00 0.00 2023-03-27 2023-05-15 2023-06-05 2023-07-10 2024-01-06 ainsi que le contrôle et survei nt at Central Government Le ant Selection ntation llance des travaux de réhabili vel tation du bâtiment devant ab riter la chambre des comptes déconcentrées de Kananga ZR-COREF-344837-CS-INDV / Recrutement d'un consultant Component 2. Supporting international pour la réalisati Resource Management at th Individual Consult Open - Internationa Under Implement IDA / 70200 Post 120,000.00 0.00 2023-03-20 2023-04-10 2023-05-08 2023-05-29 2023-07-03 2023-12-30 on de l'évaluation de la perf e Provincial Government Lev ant Selection l ation ormance des administrations el fiscales provinciales suivant l 'approche TADAT. ZR-COREF-344901-CS-INDV / Recrutement d'un consultant Component 2. Supporting ingénieur architecte pour fair Resource Management at th Individual Consult Pending Impleme e l'état des lieux et le suivi d IDA / 70200 Post Open - National 150,000.00 0.00 2023-04-08 2023-05-27 2023-06-17 2023-07-22 2024-01-18 e Provincial Government Lev ant Selection ntation es bâtiments à réhabiliter da el ns les 4 provinces (du Kasaï Oriental, du Kasaï, du Kasaï C entral et de Lomami) ZR-COREF-344912-CS-CDS / Déploiement multi-sites du lo Component 3. Project and C Direct - Internation Pending Impleme giciel de gestion financière d IDA / 70200 hange Management, and Em Post Direct Selection 40,000.00 0.00 2023-04-15 2023-04-25 2023-06-29 2023-12-26 al ntation u projet ENCORE (auprès de ergency Response TOMATE) et mise à niveau ZR-COREF-345018-CS-INDV / Component 3. Project and C Individual Consult Under Implement Recrutement d'un auditeur in IDA / 70200 hange Management, and Em Post Open - National 60,000.00 0.00 2023-03-10 2023-03-16 2023-04-19 2023-05-10 2023-06-14 2024-06-13 ant Selection ation terne ergency Response ZR-COREF-345068-CS-INDV / Recrutement d'un consultant pour traduire un document s Component 3. Project and C Individual Consult Pending Impleme ynthèse sur le projet en lang IDA / 70200 hange Management, and Em Post Open - National 20,000.00 0.00 2023-04-14 2023-06-02 2023-06-23 2023-07-28 2024-01-24 ant Selection ntation ues locales (résumé du proje ergency Response t : son envergure, ses risques et effets environnementales et sociale) ZR-COREF-345081-CS-INDV / Recrutement d'un consultant Component 3. Project and C individuel pour l'élaboration Individual Consult Under Implement IDA / 70200 hange Management, and Em Post Open - National 30,000.00 0.00 2023-03-21 2023-04-24 2023-05-09 2023-05-30 2023-07-04 2023-12-31 de la stratégie de gestion du ant Selection ation ergency Response changement et la revue quali té de la stratégie de commun ication ZR-COREF-345087-CS-INDV / Component 3. Project and C Recrutement des consultants Individual Consult Pending Impleme IDA / 70200 hange Management, and Em Post Open - National 50,000.00 0.00 2023-04-07 2023-05-26 2023-06-16 2023-07-21 2024-01-17 ponctuels pour les évaluation ant Selection ntation ergency Response s des offres et propositions Page 11 ZR-COREF-345088-CS-INDV / Component 3. Project and C Individual Consult Under Implement Recrutement de deux compt IDA / 70200 hange Management, and Em Post Open - National 79,200.00 0.00 2023-03-28 2023-03-17 2023-05-16 2023-06-06 2023-07-11 2024-07-10 ant Selection ation ables pour le projet ENCORE ergency Response ZR-COREF-345092-CS-INDV / Component 1. Strengthening Recrutement d'un consultant Public Resources Manageme Individual Consult Pending Impleme IDA / 70200 Post Open - National 100,000.00 0.00 2023-04-18 2023-06-06 2023-06-27 2023-08-01 2024-01-28 pour une assistance techniqu nt at Central Government Le ant Selection ntation e dans la fiscalité minière vel ZR-COREF-344362-CS-INDV / Component 1. Strengthening Recrutement d'un consultant Public Resources Manageme Individual Consult Pending Impleme national pour l'élaboration du IDA / 70200 Post Open - National 100,000.00 0.00 2023-03-17 2023-05-05 2023-05-26 2023-06-30 2023-12-27 nt at Central Government Le ant Selection ntation manuel de procédures de ge vel stion des ressources humain es et la Paie ZR-COREF-344818-CS-CDS / Recrutement d'un Cabinet int Component 1. Strengthening ernational Expertise France, Public Resources Manageme Direct - Internation Under Implement IDA / 70200 Post Direct Selection 400,000.00 0.00 2023-03-24 2023-04-10 2023-04-03 2023-06-07 2023-12-04 chargé d’appuyer la Cour des nt at Central Government Le al ation comptes dans la mise en œu vel vre de son plan stratégique ZR-COREF-344827-CS-CDS / Component 1. Strengthening Appui à l'Organisation de l’en IDA / 70200 Public Resources Manageme Prior Direct Selection Direct - National 9,607,330.00 0.00 Signed 2023-03-15 2023-04-28 2023-03-25 2023-05-18 2023-05-29 2023-11-25 quête ECVM proprement dite nt at Central Government Le avec le PNUD vel ZR-COREF-344384-CS-INDV / Recrutement consultant indiv iduel pour élaborer le cahier Component 1. Strengthening des charges et le DAO pour l' Public Resources Manageme Individual Consult Pending Impleme installation, la sécurisation et IDA / 70200 Post Limited 30,000.00 0.00 2023-03-13 2023-03-18 2023-04-08 2023-05-13 2023-11-09 nt at Central Government Le ant Selection ntation la mise en marche du datace vel nter de secours de la Directio n de la Gestion des bases de s données des RH à la fonctio n publique (DBDR). ZR-COREF-344845-CS-INDV / Component 2. Supporting Recrutement d'un cabinet po Resource Management at th Individual Consult Open - Internationa Pending Impleme ur mener une étude sur le po IDA / 70200 Prior 600,000.00 0.00 2023-03-31 2023-05-19 2023-06-09 2023-07-14 2024-01-10 e Provincial Government Lev ant Selection l ntation tentiel fiscal en faveur de qu el atre provinces ENCORE ZR-COREF-344484-CS-INDV / Component 1. Strengthening Recrutement du consultant i Public Resources Manageme Pending Impleme ndividuel Expert Pierre Tshiy IDA / 70200 Post Direct Selection Direct - National 50,000.00 0.00 2023-03-24 2023-04-03 2023-06-07 2023-12-04 nt at Central Government Le ntation ombo pour l'assistance techn vel ique dans la phase de produc tion du SIGMAP ZR-COREF-355174-CS-INDV / Component 3. Project and C Recrutement d'un(e) assistan Individual Consult Under Implement IDA / 70200 hange Management, and Em Post Limited 30,000.00 0.00 2023-05-01 2023-04-24 2023-05-06 2023-05-20 2023-06-10 2024-06-09 t(e) en décentralisation finan ant Selection ation ergency Response cière et budget participatif ZR-COREF-355179-CS-INDV / Component 3. Project and C Recrutement d'un spécialiste Individual Consult Pending Impleme IDA / 70200 hange Management, and Em Post Limited 56,700.00 0.00 2023-05-01 2023-05-06 2023-05-27 2023-07-01 2023-12-28 en charge de la reforme de l ant Selection ntation ergency Response a fonction publique pour le Pr ojet ENCORE ZR-COREF-355180-CS-INDV / Component 1. Strengthening Recrutement d'un consultan Public Resources Manageme Individual Consult Under Implement IDA / 70200 Post Limited 56,700.00 0.00 2023-04-15 2023-05-23 2023-04-20 2023-05-11 2023-06-15 2023-12-12 t national Expert en Mine pou nt at Central Government Le ant Selection ation r le projet ENCORE vel ZR-COREF-355425-CS-INDV / Component 3. Project and C Recrutement d'un 2ème spéc Individual Consult Under Implement IDA / 70200 hange Management, and Em Post Limited 55,200.00 0.00 2023-04-15 2023-04-11 2023-04-20 2023-05-11 2023-06-15 2023-12-12 ialiste en Passation des Marc ant Selection ation ergency Response hés du Projet ENCORE ZR-COREF-345715-CS-INDV / Component 1. Strengthening Individual Consult Pending Impleme Assistance technique à l'ARM IDA / 70200 Public Resources Manageme Post Open - National 200,000.00 0.00 2023-05-10 2023-06-28 2023-07-19 2023-08-23 2024-02-19 ant Selection ntation P pour la mise en œuvre des nt at Central Government Le réformes vel ZR-COREF-345701-CS-INDV / Component 3. Project and C Individual Consult Recrutement d'un chargé de IDA / 70200 hange Management, and Em Post Open - National 40,000.00 0.00 Canceled 2023-04-29 2023-03-17 2023-05-20 2023-06-10 2023-07-15 2024-07-14 ant Selection Passation des Marchés ergency Response ZR-COREF-356313-CS-INDV / Component 3. Project and C Individual Consult Pending Impleme Recrutement d'un expert fisc IDA / 70200 hange Management, and Em Post Open - National 56,700.00 0.00 2023-04-12 2023-05-31 2023-06-21 2023-07-26 2024-01-22 ant Selection ntation aliste pour le projet ENCORE ergency Response ZR-COREF-360909-CS-CDS / Component 3. Project and C Recrutement d'un consultant Direct - Internation Under Implement IDA / 70200 hange Management, and Em Post Direct Selection 350,000.00 0.00 2023-05-11 2023-05-12 2023-05-21 2023-07-25 2024-01-21 firme chargé de l'audit des d al ation ergency Response épenses éligibles au program me (PDE) ZR-COREF-363418-CS-CDS / Component 3. Project and C Recrutement d'un consultant Direct - Internation Pending Impleme IDA / 70200 hange Management, and Em Post Direct Selection 350,000.00 0.00 2023-05-27 2023-06-06 2023-08-10 2024-02-06 firme chargé de l'audit des d al ntation ergency Response épenses éligibles au program me (PDE) ZR-COREF-363431-CS-INDV / Recrutement d'un consultant Component 1. Strengthening Senior International pour l'él Public Resources Manageme Individual Consult Open - Internationa Under Implement aboration de la stratégie de r IDA / 70200 Post 100,000.00 0.00 2023-05-29 2023-06-07 2023-07-17 2023-08-07 2023-09-11 2024-03-09 nt at Central Government Le ant Selection l ation enforcement des capacités, d vel e formation et de professionn alisation des acteurs nationa ux de la commande Publique. Page 12 PROCUREMENT PLAN (Textual Part) Project information: [West Bank and Gaza] [Technology for Youth and Jobs] [P-172571] Project Implementation agency: [Development Alternative Inc -DAI] Date of the Procurement Plan: [22-October-2020] Period covered by this Procurement Plan: [22-October- 2020 – to 30- October-2025] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The procurement under the project will be carried out following well- established private sector procurement arrangements or commercial practices, acceptable to the World Bank as specified in Paras 6.46 and 7.26 of the Bank’s Procurement regulations Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods). Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is not Applicable. PROCUREMENT West Bank and Gaza : Technology for Youth and Jobs PLAN General Information Country: West Bank and Gaza 2020-10-22 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172571 GPN Date: Project Name: Technology for Youth and Jobs Loan / Credit No: TF / B2944 Development Alternative Inc., Europe Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-DAI-201021-GO-CP / Proc Project management and Im Commercial Practi Single Stage - One E urement of ICT Equipment fo TF / B2944 Post Limited 12,876.04 Completed 2020-10-22 2020-10-13 2020-10-25 2020-10-13 2020-10-29 2020-10-25 2020-11-01 2020-11-05 2020-11-05 2020-10-27 2020-12-06 2021-01-19 plementation Support ces nvelope r "Technology for Youth and J obs" project. GZ-DAI-201026-GO-CP / Proc urement of Furniture and win Project management and Im Commercial Practi TF / B2944 Post Direct 1,613.01 Completed 2020-10-22 2020-10-22 2020-10-25 2020-11-01 2020-11-01 2020-10-29 2020-11-30 2020-11-20 dow blinds for "Technology f plementation Support ces or youth and jobs" Project. GZ-DAI-201029-CW-CP / Gla ss separation and 3 glass do Project management and Im Commercial Practi TF / B2944 Post Direct 3,400.00 Completed 2020-10-28 2020-11-01 2020-11-02 2020-10-28 2020-11-09 2020-10-30 2020-12-10 2020-11-20 ors for "Technology for youth plementation Support ces and jobs" project. GZ-DAI-254165-GO-RFQ / Pr ocurement of Equipment & F Improving IT service capabili Request for Quota Single Stage - One E TF / B2944 Post Limited 22,534.50 Completed 2021-09-27 2021-09-22 2021-11-03 2021-10-15 2022-01-30 2021-12-28 urniture for Gaza Recovery G ties tions nvelope rantee (Pal Life company)- G aza GZ-DAI-265539-GO-RFQ / Pr ocurement of Equipment for Improving IT service capabili Request for Quota Single Stage - One E TF / B2944 Post Limited 301,885.00 Completed 2021-12-05 2021-11-29 2022-01-26 2021-12-22 2022-05-31 2022-06-29 Gaza recovery program Gran ties tions nvelope tee (Digital communication c ompany)- Gaza GZ-DAI-269093-GO-RFQ / Pr ocurement of Equipment & F Improving IT service capabili Request for Quota Single Stage - One E TF / B2944 Post Limited 35,207.20 Completed 2021-12-22 2021-12-20 2022-01-20 2022-01-12 2022-05-31 2022-02-04 urniture under Gaza recovery ties tions nvelope program (for ADMARK co. in Gaza) GZ-DAI-271189-GO-RFQ / Pr ocurement of equipment for Improving IT service capabili Request for Quota Single Stage - One E Gaza recovery program for t TF / B2944 Post Limited 129,440.00 Completed 2021-12-29 2022-01-04 2022-01-23 2022-01-24 2022-06-30 2022-03-15 ties tions nvelope he benefit of Mashareq for eq uipment & production- Gaza GZ-DAI-272864-GO-RFQ / Pr ocurement of Office Furniture Improving IT service capabili Request for Quota Single Stage - One E & Equipment under Gaza rec TF / B2944 Post Limited 37,456.40 Completed 2022-01-20 2022-01-18 2022-02-10 2022-02-03 2022-07-31 2022-04-11 ties tions nvelope overy program for the benefi t of (Laptop center & Clever toys) GZ-DAI-317942-GO-RFQ / Pr Project management and Im Request for Quota Single Stage - One E ocurement of Laptops and Int TF / B2944 Post Limited 0.00 Completed 2022-09-29 2022-09-28 2022-10-11 2022-10-17 2022-11-05 plementation Support tions nvelope eractive LCD for the benefit o f MTIT. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-DAI-364033-GO-RFQ / Jo Improving IT service capabili Request for Quota Single Stage - One E b Fair Event (will be conduct TF / B2944 Post Limited 0.00 Signed 2023-05-31 2023-05-29 2023-06-11 2023-07-31 ties tions nvelope ed in 4 Universities in WestB ank) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-DAI-212188-NC-CP / Tec Project management and Im Commercial Practi TF / B2944 Post Limited 4,060.00 Completed 2021-01-06 2021-01-13 2021-01-14 2021-02-15 2021-02-01 2021-02-11 2021-02-07 2021-02-11 2021-02-10 2021-02-17 2021-02-11 2021-02-18 2021-04-25 2021-07-01 hstart Website Development. plementation Support ces GZ-DAI-221149-CS-CCP / Int ernship program setup Train ing for HR departments in IT Firms (Cosulting Firm) Improving IT service capabili Commercial Practi The firm will be giving HR trai TF / B2944 Post Limited 0.00 Canceled 2021-04-06 2021-04-11 2021-05-02 2021-05-09 2021-05-13 2021-05-16 2022-05-16 ties ces ning for IT firms so that they are able to design and mana ge efficient and productive tr aining programs for trainees. GZ-DAI-252214-CS-CQS / Te Project management and Im Consultant Qualifi TF / B2944 Post Limited 12,500.00 Signed 2021-10-17 2021-11-21 2021-10-31 2021-11-24 2021-11-30 2021-12-20 2022-01-04 2021-12-21 2023-06-29 ch Start Audit/ 2 years contra plementation Support cation Selection ct GZ-DAI-221163-CS-CCP / Dia gnostic study Consulting Fir m The firm will conduct a gap a Improving IT service capabili Consultant Qualifi TF / B2944 Post Limited 0.00 Canceled 2022-09-04 2022-09-18 2022-10-18 2022-11-22 2023-05-21 nalysis and diagnosis of IT fir ties cation Selection ms weaknesses and potential areas of improvement based on best practices of manage ment and operations under c omponent 1 Page 1 GZ-DAI-221175-CS-CCP / IT Gender assessment Consulti ng firm. Improving IT service capabili Consultant Qualifi Pending Impleme A company will be contracted TF / B2944 Post Limited 0.00 2022-08-04 2022-08-18 2022-09-17 2022-10-22 2023-04-20 ties cation Selection ntation to run a gender assessment study to identify obstacles an d challenges faced by emplo yees and IT firms under com ponent 1. GZ-DAI-221213-CS-CCP / Ass essment, design and implem entation of Outsourcing matc Improving market access, an hmaking with International b Consultant Qualifi Pending Impleme TF / B2944 d increasing demand and in Post Limited 0.00 2022-10-02 2022-10-16 2022-11-15 2022-12-20 2023-06-18 uyers, foreign investment out cation Selection ntation vestments reach and Promotion campai gn by doing Research and as sessment activities & other I mplementation activities. GZ-DAI-360548-CS-CQS / Pro Improving IT service capabili Consultant Qualifi Open - Internationa Under Implement viding Advisory Services on TF / B2944 Post 0.00 2023-05-14 2023-05-09 2023-05-21 2023-05-28 2023-06-15 2023-06-20 2023-07-10 2024-07-09 ties cation Selection l ation Managerial Capabilities for IT Services Firms GZ-DAI-364303-CS-CQS / En Project management and Im Consultant Qualifi Pending Impleme TF / B2944 Post Limited 0.00 2023-06-05 2023-06-08 2023-06-11 2023-06-18 2023-08-31 glish Trainings for the Ministr plementation Support cation Selection ntation y staff. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-DAI-201140-CS-INDV / Gr Project management and Im Individual Consult ants and Procurement Specia TF / B2944 Post Limited 46,800.00 Terminated 2020-10-22 2020-10-25 2020-10-25 2020-10-22 2020-11-01 2020-10-28 2020-11-08 2020-10-29 2021-11-07 plementation Support ant Selection list Procurement Plan-TechSt art Project. GZ-DAI-201601-CS-INDV / M Project management and Im Individual Consult onitoring and Evaluation Spe TF / B2944 Post Direct 31,200.00 Terminated 2020-12-10 2020-12-09 2020-12-20 2020-10-29 2020-12-27 2020-10-14 2021-01-10 2020-10-16 2022-01-10 plementation Support ant Selection cialist (part time) GZ-DAI-207291-CS-INDV / Se Improving the IT services ec Individual Consult TF / B2944 Post Direct 8,100.00 Completed 2020-12-05 2020-12-07 2020-12-15 2020-12-15 2020-12-16 2020-12-07 2020-12-23 2020-12-10 2021-02-21 2021-02-16 nior Consultant osystem ant Selection GZ-DAI-207300-CS-INDV / Te Improving IT service capabili Individual Consult TF / B2944 Post Limited 57,600.00 Terminated 2020-12-10 2020-12-08 2020-12-15 2020-12-21 2021-01-05 2020-12-23 2021-02-09 2020-12-24 2022-02-09 chnical Lead - Component On ties ant Selection e GZ-DAI-207318-CS-INDV / Pr Improving market access, an Individual Consult TF / B2944 Post Direct 104,000.00 Signed 2020-12-08 2020-12-09 2020-12-18 2020-11-01 2021-01-08 2020-11-14 2021-02-12 2020-10-15 2022-02-12 oject Director d increasing demand and in ant Selection vestments GZ-DAI-207319-CS-INDV / Fi Project management and Im Individual Consult TF / B2944 Post Direct 48,100.00 Signed 2020-12-10 2020-12-09 2020-12-20 2021-01-25 2021-01-16 2020-10-28 2021-02-04 2020-10-15 2022-02-04 nancial Management Speciali plementation Support ant Selection st GZ-DAI-207391-CS-INDV / Te Improving the IT services ec Individual Consult TF / B2944 Post Limited 42,000.00 Signed 2020-12-10 2020-12-08 2020-12-15 2021-02-22 2021-01-05 2021-03-02 2021-02-09 2021-03-03 2022-02-09 chnical Lead- Component 2 osystem ant Selection GZ-DAI-207392-CS-INDV / C Improving IT service capabili Individual Consult TF / B2944 Post Direct 16,250.00 Completed 2020-12-10 2020-12-10 2020-12-20 2020-12-10 2020-12-27 2020-11-02 2021-01-10 2020-11-03 2022-01-10 2021-12-16 ommunication Officer ties ant Selection GZ-DAI-207313-CS-INDV / Te Improving the IT services ec Individual Consult TF / B2944 Post Direct 0.00 Canceled 2020-12-10 2020-12-20 2020-12-22 2021-01-14 2022-01-14 chnical Lead _Component 2 osystem ant Selection GZ-DAI-211380-CS-CCP / Re Improving IT service capabili Individual Consult TF / B2944 Post Limited 57,600.00 Signed 2020-12-24 2020-12-24 2020-12-28 2020-12-17 2021-01-10 2020-12-23 2021-01-14 2020-12-24 2022-01-13 cruitment of component 1 le ties ant Selection ad. GZ-DAI-208394-CS-INDV / En Project management and Im Individual Consult vironmental and Social Cons TF / B2944 Post Direct 31,200.00 Signed 2020-12-10 2020-12-31 2020-12-14 2020-12-01 2020-12-17 2021-01-07 2020-12-21 2020-12-08 2025-06-28 plementation Support ant Selection ultant- Split between Techsta rt and IPSD GZ-DAI-212164-CS-INDV / Hi Project management and Im Individual Consult re a Procurement Specialist f TF / B2944 Post Limited 36,000.00 Signed 2021-01-03 2021-01-06 2021-01-06 2020-12-28 2021-01-12 2021-01-06 2021-01-17 2021-01-07 2021-12-16 plementation Support ant Selection or Techstart Project. GZ-DAI-215912-CS-INDV / Hi re Operations Coordinator-Ga Project management and Im Individual Consult TF / B2944 Post Limited 12,000.00 Signed 2021-02-01 2021-01-20 2021-02-02 2021-01-20 2021-02-03 2021-01-17 2021-02-03 2021-01-18 2022-02-02 za Full time, Split between IP plementation Support ant Selection SD and Techstart Projects. GZ-DAI-239077-CS-INDV / Te Improving IT service capabili Individual Consult TF / B2944 Post Open 18,000.00 Signed 2021-06-13 2021-08-05 2021-07-05 2021-08-08 2021-07-15 2021-08-08 2021-07-25 2021-08-12 2022-07-24 chnical Advisor- Gaza ties ant Selection GZ-DAI-245555-CS-INDV / Te Improving IT service capabili Individual Consult TF / B2944 Post Limited 17,010.00 Signed 2021-08-01 2021-08-05 2021-08-06 2021-11-22 2021-08-10 2021-11-22 2021-09-01 2021-11-26 2022-08-31 chnical Coordinator for TechS ties ant Selection tart GZ-DAI-246770-CS-INDV / Hi Project management and Im Individual Consult re a short term technical gra TF / B2944 Post Limited 0.00 Canceled 2021-08-11 2021-11-14 2021-08-19 2021-09-06 2021-09-19 2022-03-20 plementation Support ant Selection nt support officer (Assistant) GZ-DAI-264345-CS-INDV / Sh ort Term Technical and Grant Improving IT service capabili Individual Consult TF / B2944 Post Limited 4,800.00 Signed 2021-11-21 2021-11-24 2021-11-23 2021-11-25 2021-11-24 2021-11-25 2021-12-01 2021-11-26 2022-03-31 s Support officer (4 Months w ties ant Selection ith possibility of renewable). GZ-DAI-268404-CS-INDV / C ommunication Specialist for Improving IT service capabili Individual Consult TF / B2944 Post Open 27,600.00 Signed 2021-12-19 2021-12-16 2022-01-21 2022-02-06 2022-01-30 2022-03-29 2022-02-02 2022-03-31 2023-02-01 TechStart Project (50% of the ties ant Selection salary will be from TechStart Project) GZ-DAI-275306-CS-CDS / Pro vision of Service For Establis Improving IT service capabili TF / B2944 Post Direct Selection Direct 70,000.00 Completed 2022-01-27 2022-02-01 2022-02-13 2022-02-03 2022-02-24 2022-03-08 2022-05-31 2022-07-28 hing IT Companies database ties for firms operating in West B ank and Gaza. GZ-DAI-299931-CS-INDV / D AI is seeking to hire a technic Improving IT service capabili Individual Consult al consultant to support Tech TF / B2944 Post Limited 0.00 Canceled 2022-06-23 2022-06-22 2022-07-03 2022-07-13 2022-07-25 2023-07-24 ties ant Selection Start activities at the nationa l center for technological inn ovation & creativity at MTIT GZ-DAI-307239-CS-INDV / So Improving IT service capabili Individual Consult cial Media Campaign for Tech TF / B2944 Post Limited 0.00 Canceled 2022-08-02 2022-08-07 2022-08-04 2022-08-11 2022-09-18 2022-09-30 ties ant Selection Start project Page 2 GZ-DAI-310913-CS-INDV / R Improving IT service capabili Individual Consult TF / B2944 Post Open - National 0.00 Completed 2022-08-22 2022-08-24 2022-09-05 2022-10-11 2022-09-08 2022-10-11 2022-10-13 2023-10-12 2022-11-01 esident Technical Consultant ties ant Selection GZ-DAI-324778-CS-CDS / Vid Improving IT service capabili eo production to highlight Te TF / B2944 Post Direct Selection Direct - National 0.00 Completed 2022-11-02 2022-11-08 2022-11-06 2022-11-08 2022-11-13 2022-11-22 2022-12-04 ties chStart Project beneficiaries. GZ-DAI-331221-CS-INDV / Se nior Consultant – Committee Improving IT service capabili Individual Consult TF / B2944 Post Limited 0.00 Signed 2022-12-12 2022-12-13 2022-12-17 2022-12-15 2022-12-18 2023-02-05 2022-12-22 2023-06-19 Member (HCIS & Pioneer Pro ties ant Selection grams) Individual consultant number 1 GZ-DAI-331414-CS-INDV / Se nior Consultant – Committee Improving IT service capabili Individual Consult TF / B2944 Post Limited 0.00 Signed 2022-12-13 2023-01-19 2022-12-15 2023-01-24 2022-12-18 2023-02-14 2022-12-22 2023-06-20 Member (HCIS & Pioneer Pro ties ant Selection grams) Individual consultant number 2 GZ-DAI-331415-CS-CDS / Re gistration of new firms at the Improving IT service capabili TF / B2944 Post Direct Selection Direct - National 0.00 Signed 2022-12-18 2023-01-19 2022-12-21 2023-01-22 2022-12-27 2023-12-26 Ministry of National Economy ties (Local Companies) GZ-DAI-331433-CS-CDS / Re Improving IT service capabili gistration of Branches of fore TF / B2944 Post Direct Selection Direct - National 0.00 Signed 2022-12-15 2023-01-19 2022-12-19 2023-01-22 2022-12-27 2023-12-26 ties ign firms at the Ministry of N ational Economy GZ-DAI-360822-CS-INDV / Hi re M&E Specialist for IPSD an Project management and Im Individual Consult Under Implement TF / B2944 Post Open - National 0.00 2023-05-15 2023-05-09 2023-06-06 2023-06-08 2023-06-18 2024-06-17 d Techstart. This position will plementation Support ant Selection ation be allocated for both IPSD an d Techstart. Page 3 National Urban Cadaster Projec (P162278) Procurement Plan Country: Peru Region: LATIN AMERICA AND CARIBBEAN Approval Date: 10-Jan-2020 July 9, 2010 PROCUREMENT Peru : National Urban Cadaster and Municipal Support Project PLAN General Information Country: Peru 2021-02-23 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162278 GPN Date: 2021-06-30 Project Name: National Urban Cadaster and Municipal Support Project Loan / Credit No: IBRD / 90350 Organismo de Formalización de la Propiedad Informal Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PE-COFOPRI-363961-GO-RFB Component 2: Strengthening / Equipamiento Informático p Single Stage - One E Pending Impl IBRD / 90350 of the Institutional Framewor Post Request for Bids Open - National 178,750.00 0.00 2023-06-30 2023-07-03 2023-08-14 2023-08-31 2023-09-24 2023-12-08 ara Desarrollo y Soporte para nvelope ementation k el Componente 02 PE-COFOPRI-364078-GO-RFQ Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl / Adquisición de 04 computa IBRD / 90350 of the Institutional Framewor Post Limited 7,000.00 0.00 2023-06-10 2023-07-08 2023-09-06 tions nvelope ementation doras para el Equipo de Mesa k Agil Component 1: Strengthening PE-COFOPRI-365507-GO-RFB Municipal Systems, Services Single Stage - One E Pending Impl / Adquisicion de Estación tota IBRD / 90350 and Capacities to Generate Post Request for Bids Open - National 188,237.50 0.00 2023-06-22 2023-06-27 2023-08-08 2023-09-07 2023-10-12 2023-12-11 nvelope ementation l de precisión and Maintain Urban Cadaste rs in Project Municipalities NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthening UE003-NC5 / Campañas de c Municipal Systems, Services omunicación previo al levant Request for Quota Single Stage - One E IBRD / 90350 and Capacities to Generate Post Open - National 39,862.09 0.00 Canceled 2021-10-06 2021-12-01 2022-03-01 amiento catastral para Chicla tions nvelope and Maintain Urban Cadaste yo La Victoria y SMP rs in Project Municipalities PE-COFOPRI-218141-NC-RFB Component 1: Strengthening / Levantamiento catastral urb Municipal Systems, Services Open - Internationa Single Stage - One E ano en San Martin de Porres, IBRD / 90350 and Capacities to Generate Prior Request for Bids 6,765,671.94 0.00 Canceled 2022-02-04 2022-02-13 2022-03-27 2022-04-20 2022-05-25 2022-11-21 l nvelope información geográfica y ad and Maintain Urban Cadaste ministrativa. rs in Project Municipalities PE-COFOPRI-217991-NC-RFB Component 1: Strengthening / Generación de modelos digi Municipal Systems, Services Open - Internationa Single Stage - One E tales de elevaciones - Ortoim IBRD / 90350 and Capacities to Generate Prior Request for Bids 2,227,186.73 749,646.82 Signed 2021-08-10 2021-10-26 2021-08-20 2021-10-28 2021-10-01 2021-12-23 2021-10-16 2022-02-08 2021-11-20 2022-05-14 2022-11-20 l nvelope agenes y Bases de datos cart and Maintain Urban Cadaste ografica simplificada rs in Project Municipalities PE-COFOPRI-218140-NC-RFB Component 1: Strengthening / Levantamiento catastral urb Municipal Systems, Services Open - Internationa Single Stage - One E ano en Chiclayo y La Victoria, IBRD / 90350 and Capacities to Generate Prior Request for Bids 3,569,582.37 0.00 Canceled 2022-02-04 2022-02-13 2022-03-27 2022-04-20 2022-05-25 2022-11-21 l nvelope información geográfica y ad and Maintain Urban Cadaste ministrativa. rs in Project Municipalities Component 1: Strengthening PE-COFOPRI-335375-NC-RFB Municipal Systems, Services / Servicio de Levantamiento Open - Internationa Single Stage - One E Under Revie IBRD / 90350 and Capacities to Generate Prior Request for Bids 15,021,953.00 0.00 2023-02-20 2023-02-25 2023-04-17 2023-05-17 2023-07-13 2025-07-02 catastral Lote 1 (Lambayequ l nvelope w and Maintain Urban Cadaste e y Piura) rs in Project Municipalities Component 1: Strengthening PE-COFOPRI-335380-NC-RFB Municipal Systems, Services / Servicio de Levantamiento Open - Internationa Single Stage - One E Pending Impl IBRD / 90350 and Capacities to Generate Prior Request for Bids 5,724,710.00 0.00 2023-02-20 2023-02-25 2023-04-17 2023-05-17 2023-07-13 2024-10-05 catastral Lote 4 (Lima cercad l nvelope ementation and Maintain Urban Cadaste o) rs in Project Municipalities PE-COFOPRI-363493-NC-RFQ Component 1: Strengthening / Servicio de producción de pi Municipal Systems, Services Request for Quota Single Stage - One E Under Imple ezas publicitarias para la ca IBRD / 90350 and Capacities to Generate Post Limited 48,223.00 0.00 2023-06-06 2023-06-15 2023-07-06 2023-09-14 tions nvelope mentation mpaña de comunicaciones pr and Maintain Urban Cadaste evio al levantamiento catastr rs in Project Municipalities al Component 1: Strengthening PE-COFOPRI-363958-NC-RFB Municipal Systems, Services / Servicio de Levantamiento Open - Internationa Single Stage - One E Pending Impl IBRD / 90350 and Capacities to Generate Prior Request for Bids 13,617,223.00 0.00 2023-06-05 2023-06-10 2023-07-31 2023-08-30 2023-10-26 2024-12-19 catastral Lote 2 (Los Olivos, l nvelope ementation and Maintain Urban Cadaste San Luis, Breña y Surquillo) rs in Project Municipalities CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthening PE-COFOPRI-218143-CS-CQS Municipal Systems, Services / Supervision del levantamie Consultant Qualifi IBRD / 90350 and Capacities to Generate Post Open - National 105,519.75 0.00 Canceled 2021-11-01 2021-11-22 2022-01-05 2022-02-04 2022-03-11 2022-09-07 nto catastral urbano en Chicl cation Selection and Maintain Urban Cadaste ayo y La Victoria rs in Project Municipalities Page 1 Component 1: Strengthening PE-COFOPRI-218144-CS-CQS Municipal Systems, Services / Supervision del levantamie Consultant Qualifi IBRD / 90350 and Capacities to Generate Post Open - National 199,998.75 0.00 Canceled 2021-11-01 2021-11-22 2022-01-05 2022-02-04 2022-03-11 2022-09-07 nto catastral urbano en San cation Selection and Maintain Urban Cadaste Martin de Porres rs in Project Municipalities PE-COFOPRI-218147-CS-QCB Component 1: Strengthening S / Consultoría especializada Municipal Systems, Services Quality And Cost- para diseño, desarrollo y pro IBRD / 90350 and Capacities to Generate Post Open - National 150,000.00 0.00 Canceled 2021-10-01 2021-10-15 2021-11-12 2021-12-10 2021-12-27 2022-01-24 2022-02-28 2022-06-28 Based Selection ducción de Plataforma de Ca and Maintain Urban Cadaste pacitación Virtual rs in Project Municipalities PE-COFOPRI-239697-CS-QCB Component 1: Strengthening S / Consultoria para la verific Municipal Systems, Services Quality And Cost- ación y validación de la calid IBRD / 90350 and Capacities to Generate Post Open - National 414,648.70 421,295.40 Signed 2021-08-10 2021-10-06 2021-08-24 2021-10-16 2021-09-07 2021-12-02 2021-10-05 2022-01-05 2021-10-12 2022-01-14 2021-11-02 2022-03-22 2021-11-30 2022-05-14 2022-11-30 Based Selection ad de los prouctos de ortoim and Maintain Urban Cadaste agenes y bases cartograficas rs in Project Municipalities PE-COFOPRI-239713-CS-QCB Component 2: Strengthening S / Consultoría de Diseño de Quality And Cost- Open - Internationa IBRD / 90350 of the Institutional Framewor Prior 1,000,000.00 0.00 Canceled 2022-01-31 2022-02-14 2022-03-14 2022-04-13 2022-05-04 2022-06-08 2022-07-13 2024-08-01 mecanismos que promuevan Based Selection l k el uso fiscal del catastro PE-COFOPRI-335387-CS-QCB Component 1: Strengthening S / Servicio de verificación y Municipal Systems, Services validación de la calidad de lo Quality And Cost- Open - Internationa IBRD / 90350 and Capacities to Generate Prior 2,358,229.00 0.00 Under Review 2023-01-21 2023-04-21 2023-02-05 2023-04-26 2023-02-28 2023-04-05 2023-05-05 2023-05-15 2023-07-10 2025-07-01 s productos del levantamient Based Selection l and Maintain Urban Cadaste o catastral en municipalidade rs in Project Municipalities s seleccionadas Lote 1 (Lamb ayeque y Piura) PE-COFOPRI-335391-CS-CQS Component 1: Strengthening / Servicio de verificación y va Municipal Systems, Services lidación de la calidad de los p Consultant Qualifi Open - Internationa Pending Impleme IBRD / 90350 and Capacities to Generate Post 182,000.00 0.00 2023-01-21 2023-01-31 2023-03-20 2023-06-03 2023-07-10 2025-06-29 roductos del levantamiento c cation Selection l ntation and Maintain Urban Cadaste atastral en municipalidades s rs in Project Municipalities eleccionadas Lote 4 (Lima Ce rcado) PE-COFOPRI-335398-CS-QCB Component 1: Strengthening S / Servicio de diseño e imple Municipal Systems, Services mentación de módulos de ca Quality And Cost- Open - Internationa IBRD / 90350 and Capacities to Generate Post 621,845.00 0.00 Canceled 2023-01-21 2023-02-05 2023-03-07 2023-05-05 2023-06-04 2023-06-19 2023-08-16 2025-02-06 pacitación en gestión catastr Based Selection l and Maintain Urban Cadaste al urbana con fines fiscales, rs in Project Municipalities planificación urbana y gestió n de riesgo de desastre PE-COFOPRI-335399-CS-CQS Component 1: Strengthening / Servicio de fortalizacimient Municipal Systems, Services Consultant Qualifi Open - Internationa o de capacidades municipale IBRD / 90350 and Capacities to Generate Post 203,078.00 0.00 Canceled 2023-01-21 2023-01-31 2023-02-25 2023-06-23 2023-08-06 2025-01-27 cation Selection l s en la gestión de riesgo de d and Maintain Urban Cadaste esastres rs in Project Municipalities PE-COFOPRI-335403-CS-QCB Component 2: Strengthening S / Servicio de desarrollo e i Quality And Cost- Open - Internationa Pending Impleme IBRD / 90350 of the Institutional Framewor Prior 4,887,310.00 0.00 2023-01-27 2023-02-11 2023-03-13 2023-05-18 2023-06-17 2023-07-02 2023-09-05 2026-08-20 mplementación del Sistema Based Selection l ntation k de Información Catastral PE-COFOPRI-359386-CS-QCB S / Servicio de consultoria pa Component 1: Strengthening ra la veriticación y validación Municipal Systems, Services Quality And Cost- Open - Internationa de la calidad de los producto IBRD / 90350 and Capacities to Generate Prior 2,137,904.00 0.00 Under Review 2023-05-05 2023-05-20 2023-06-12 2023-07-18 2023-08-17 2023-08-27 2023-10-22 2025-10-13 Based Selection l s del Levantamiento Catastra and Maintain Urban Cadaste l Lote 2 (distritos de la provin rs in Project Municipalities cia de Lima, departamento d e Lima) Component 1: Strengthening PE-COFOPRI-363521-CS-CQS Municipal Systems, Services / Servicio de consultoría Dise Consultant Qualifi Under Implement IBRD / 90350 and Capacities to Generate Post Open - National 110,000.00 0.00 2023-06-12 2023-06-06 2023-06-22 2023-07-27 2023-08-01 2023-08-25 2023-12-23 ño de Procedimientos de Man cation Selection ation and Maintain Urban Cadaste tenimiento Catastral rs in Project Municipalities PE-COFOPRI-365666-CS-CQS Component 1: Strengthening / Servicio de consultoria Dise Municipal Systems, Services ño e implementación de Line Consultant Qualifi Open - Internationa Under Implement IBRD / 90350 and Capacities to Generate Post 200,032.00 0.00 2023-06-12 2023-06-16 2023-06-22 2023-07-17 2023-11-12 2023-12-26 2024-09-21 amientos para el uso de la In cation Selection l ation and Maintain Urban Cadaste formación Catastral en la Ge rs in Project Municipalities stión de Riesgos de Desastre s PE-COFOPRI-365728-CS-CQS Component 2: Strengthening Consultant Qualifi / Servicio de Plataforma en la IBRD / 90350 of the Institutional Framewor Post Open - National 120,000.00 0.00 Under Review 2023-06-12 2023-06-14 2023-07-03 2023-08-16 2023-09-15 2023-10-20 2024-10-19 cation Selection Nube (PaaS) para Sistema Ca k tastral INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthening PE-COFOPRI-218148-CS-IND Municipal Systems, Services V / Consultoría para elaboraci Individual Consult IBRD / 90350 and Capacities to Generate Post Limited 20,000.00 0.00 Canceled 2021-10-06 2021-10-11 2021-10-20 2021-11-03 2022-02-01 ón del Modulo para levantam ant Selection and Maintain Urban Cadaste iento catastral urbano rs in Project Municipalities Component 1: Strengthening PE-COFOPRI-218151-CS-IND Municipal Systems, Services V / Consultoría para elaboraci Individual Consult IBRD / 90350 and Capacities to Generate Post Limited 20,000.00 0.00 Canceled 2021-10-06 2021-10-13 2021-10-20 2021-11-01 2022-01-30 ón del Modulo para actualiza ant Selection and Maintain Urban Cadaste ción de catastro rs in Project Municipalities Component 1: Strengthening UE003-CS7 / Consultoría par Municipal Systems, Services a elaboración del Modulo par Individual Consult IBRD / 90350 and Capacities to Generate Post Limited 20,000.00 0.00 Canceled 2021-10-06 2021-10-13 2021-10-20 2021-11-01 2022-01-30 a uso del catastro urbano co ant Selection and Maintain Urban Cadaste n fines fiscales rs in Project Municipalities PE-COFOPRI-218149-CS-IND Component 1: Strengthening V / Consultoría para elaboraci Municipal Systems, Services Individual Consult ón del Modulo para uso del c IBRD / 90350 and Capacities to Generate Post Limited 20,000.00 0.00 Canceled 2021-10-06 2021-10-13 2021-10-20 2021-11-01 2022-01-30 ant Selection atastro urbano con fines de g and Maintain Urban Cadaste estión de riesgos de desastre rs in Project Municipalities s PE-COFOPRI-218150-CS-IND Component 1: Strengthening V / Consultoría para elaboraci Municipal Systems, Services Individual Consult ón del Modulo para uso del c IBRD / 90350 and Capacities to Generate Post Limited 20,000.00 0.00 Canceled 2021-10-06 2021-10-13 2021-10-20 2021-11-01 2022-01-30 ant Selection atastro urbano con fines de p and Maintain Urban Cadaste lanificación urbana rs in Project Municipalities Page 2 Component 1: Strengthening PE-COFOPRI-218002-CS-IND Municipal Systems, Services V / Consultoria individual de Individual Consult IBRD / 90350 and Capacities to Generate Post Open 15,000.00 10,200.00 Signed 2021-09-01 2022-04-22 2021-10-06 2022-05-31 2021-10-18 2022-06-06 2021-11-01 2022-06-16 2022-04-30 Asistencia Tecnica Directa a l ant Selection and Maintain Urban Cadaste a Municipalidad Chiclayo rs in Project Municipalities Component 1: Strengthening PE-COFOPRI-218005-CS-IND Municipal Systems, Services V / Consultoria individual de Individual Consult Under Implement IBRD / 90350 and Capacities to Generate Post Open 15,000.00 0.00 2021-09-01 2023-04-04 2021-10-06 2023-05-30 2021-10-18 2023-05-30 2021-11-01 2022-04-30 Asistencia Tecnica Directa a l ant Selection ation and Maintain Urban Cadaste a Municipalidad La Victoria rs in Project Municipalities PE-COFOPRI-218006-CS-IND Component 1: Strengthening V / Consultoria individual de Municipal Systems, Services Individual Consult Asistencia Tecnica Directa a l IBRD / 90350 and Capacities to Generate Post Open 15,000.00 10,200.00 Signed 2021-09-01 2022-04-22 2021-10-06 2022-05-31 2021-10-18 2022-06-06 2021-11-01 2022-06-16 2022-04-30 ant Selection a Municipalidad San Martin d and Maintain Urban Cadaste e Porres rs in Project Municipalities Component 1: Strengthening PE-COFOPRI-218007-CS-IND Municipal Systems, Services V / Consultoria individual de Individual Consult Pending Impleme IBRD / 90350 and Capacities to Generate Post Open 15,000.00 0.00 2021-09-01 2021-10-06 2021-10-18 2021-11-01 2022-04-30 Asistencia Tecnica Directa a l ant Selection ntation and Maintain Urban Cadaste a Municipalidad de Comas rs in Project Municipalities Component 1: Strengthening PE-COFOPRI-218009-CS-IND Municipal Systems, Services V / Consultoria individual de Individual Consult IBRD / 90350 and Capacities to Generate Post Open 15,000.00 10,200.00 Signed 2021-09-01 2022-03-25 2021-10-06 2022-04-21 2021-10-18 2022-05-02 2021-11-01 2022-05-10 2022-04-30 Asistencia Tecnica Directa a l ant Selection and Maintain Urban Cadaste a Municipalidad de Los Olivos rs in Project Municipalities PE-COFOPRI-218011-CS-IND Component 1: Strengthening V / Consultoria individual de Municipal Systems, Services Individual Consult Asistencia Tecnica Directa a l IBRD / 90350 and Capacities to Generate Post Open 15,000.00 10,200.00 Signed 2021-09-01 2022-04-22 2021-10-06 2022-05-31 2021-10-18 2022-06-06 2021-11-01 2022-06-16 2022-04-30 ant Selection a Municipalidad de San Juan and Maintain Urban Cadaste de Miraflores rs in Project Municipalities PE-COFOPRI-218013-CS-IND Component 1: Strengthening V / Consultoria individual de Municipal Systems, Services Individual Consult Asistencia Tecnica Directa a l IBRD / 90350 and Capacities to Generate Post Open 15,000.00 10,200.00 Signed 2021-09-01 2022-03-25 2021-10-06 2022-04-21 2021-10-18 2022-05-02 2021-11-01 2022-05-13 2022-04-30 ant Selection a Municipalidad de Lima Metr and Maintain Urban Cadaste opolitana rs in Project Municipalities Component 1: Strengthening PE-COFOPRI-218014-CS-IND Municipal Systems, Services V / Consultoria individual de Individual Consult IBRD / 90350 and Capacities to Generate Post Open 15,000.00 10,200.00 Signed 2021-09-01 2022-03-25 2021-10-06 2022-04-21 2021-10-18 2022-05-02 2021-11-01 2022-05-12 2022-04-30 Asistencia Tecnica Directa a l ant Selection and Maintain Urban Cadaste a Municipalidad de Chorrillos rs in Project Municipalities PE-COFOPRI-218017-CS-IND Component 1: Strengthening V / Consultoria individual de Municipal Systems, Services Individual Consult Pending Impleme Asistencia Tecnica Directa a l IBRD / 90350 and Capacities to Generate Post Open 15,000.00 0.00 2021-09-01 2021-10-06 2021-10-18 2021-11-01 2022-04-30 ant Selection ntation a Municipalidad de Villa El Sa and Maintain Urban Cadaste lvador rs in Project Municipalities PE-COFOPRI-218021-CS-IND Component 1: Strengthening V / Consultoria individual de Municipal Systems, Services Individual Consult Asistencia Tecnica Directa a l IBRD / 90350 and Capacities to Generate Post Open 15,000.00 10,200.00 Signed 2021-09-01 2022-04-22 2021-10-06 2022-05-31 2021-10-18 2022-06-06 2021-11-01 2022-06-24 2022-04-30 ant Selection a Municipalidad de Independ and Maintain Urban Cadaste encia rs in Project Municipalities Component 1: Strengthening PE-COFOPRI-218022-CS-IND Municipal Systems, Services V / Consultoria individual de Individual Consult IBRD / 90350 and Capacities to Generate Post Open 15,000.00 10,200.00 Signed 2021-09-01 2022-04-22 2021-10-06 2022-05-31 2021-10-18 2022-06-06 2021-11-01 2022-06-25 2022-04-30 Asistencia Tecnica Directa a l ant Selection and Maintain Urban Cadaste a Municipalidad de San Luis rs in Project Municipalities PE-COFOPRI-218023-CS-IND Component 1: Strengthening V / Consultoria individual de Municipal Systems, Services Individual Consult Pending Impleme Asistencia Tecnica Directa a l IBRD / 90350 and Capacities to Generate Post Open 15,000.00 0.00 2021-09-01 2021-10-06 2021-10-18 2021-11-01 2022-04-30 ant Selection ntation a Municipalidad de El Agustin and Maintain Urban Cadaste o rs in Project Municipalities Component 1: Strengthening PE-COFOPRI-218026-CS-IND Municipal Systems, Services V / Consultoria individual de Individual Consult IBRD / 90350 and Capacities to Generate Post Open 15,000.00 10,200.00 Signed 2021-09-01 2022-04-22 2021-10-06 2022-05-31 2021-10-18 2022-06-06 2021-11-01 2022-06-16 2022-04-30 Asistencia Tecnica Directa a l ant Selection and Maintain Urban Cadaste a Municipalidad de Piura rs in Project Municipalities Component 1: Strengthening PE-COFOPRI-218028-CS-IND Municipal Systems, Services V / Consultoria individual de Individual Consult Under Implement IBRD / 90350 and Capacities to Generate Post Open 15,000.00 0.00 2021-09-01 2023-04-12 2021-10-06 2023-05-30 2021-10-18 2023-06-09 2021-11-01 2022-04-30 Asistencia Tecnica Directa a l ant Selection ation and Maintain Urban Cadaste a Municipalidad de Castilla rs in Project Municipalities Component 1: Strengthening PE-COFOPRI-218029-CS-IND Municipal Systems, Services V / Consultoria individual de Individual Consult Under Implement IBRD / 90350 and Capacities to Generate Post Open 15,000.00 0.00 2021-09-01 2023-04-04 2021-10-06 2023-05-30 2021-10-18 2021-11-01 2022-04-30 Asistencia Tecnica Directa a l ant Selection ation and Maintain Urban Cadaste a Municipalidad de Catacaos rs in Project Municipalities PE-COFOPRI-218030-CS-IND Component 1: Strengthening V / Consultoria individual de Municipal Systems, Services Individual Consult Under Implement Asistencia Tecnica Directa a l IBRD / 90350 and Capacities to Generate Post Open 15,000.00 0.00 2021-09-01 2023-04-12 2021-10-06 2023-05-30 2021-10-18 2023-05-30 2021-11-01 2022-04-30 ant Selection ation a Municipalidad de José Leon and Maintain Urban Cadaste ardo Ortiz rs in Project Municipalities PE-COFOPRI-218034-CS-IND Component 1: Strengthening V / Consultoria individual de Municipal Systems, Services Individual Consult Pending Impleme Asistencia Tecnica Directa a l IBRD / 90350 and Capacities to Generate Post Open 15,000.00 0.00 2021-09-01 2021-10-06 2021-10-18 2021-11-01 2022-04-30 ant Selection ntation a Municipalidad de 26 de Oct and Maintain Urban Cadaste ubre rs in Project Municipalities PE-COFOPRI-218107-CS-IND Component 2: Strengthening V / Nueva normativa para el l Individual Consult IBRD / 90350 of the Institutional Framewor Post Limited 20,000.00 0.00 Canceled 2021-10-01 2021-10-06 2021-10-20 2021-11-01 2022-01-30 evantamiento catastral de la ant Selection k informacion predial y de las e dificaciones. PE-COFOPRI-218113-CS-IND Component 2: Strengthening Individual Consult V / Nueva normativa para la IBRD / 90350 of the Institutional Framewor Post Limited 20,000.00 0.00 Canceled 2021-10-01 2021-10-06 2021-10-13 2021-11-01 2022-01-30 ant Selection valoracion predial masiva k PE-COFOPRI-218132-CS-IND V / Desarrollo de estandares Component 2: Strengthening Individual Consult semanticos modelos de catas IBRD / 90350 of the Institutional Framewor Post Limited 40,000.00 0.00 Canceled 2021-10-01 2021-10-06 2021-10-13 2021-11-01 2022-01-30 ant Selection tro fisico y de valuacion masi k va adaptados a legislacion y situacion peruana Page 3 PE-COFOPRI-218134-CS-IND V / Desarrollo de proceso gen Component 2: Strengthening Individual Consult ericos de actualizacion para s IBRD / 90350 of the Institutional Framewor Post Limited 30,000.00 0.00 Canceled 2021-10-04 2021-10-09 2021-10-15 2021-11-01 2022-02-03 ant Selection u adaptacion a cada municip k alidad priorizada del Proyect o PE-COFOPRI-218135-CS-IND Component 2: Strengthening V / Descripción del backlog d Individual Consult IBRD / 90350 of the Institutional Framewor Post Limited 30,000.00 0.00 Canceled 2021-10-04 2021-10-11 2021-10-18 2021-11-01 2022-02-01 el sistema informático de inf ant Selection k ormación catastral PE-COFOPRI-218136-CS-IND V / Contratacion de experto 1 Component 2: Strengthening Individual Consult para el Fortalecimiento de ca IBRD / 90350 of the Institutional Framewor Post Limited 100,000.00 0.00 Canceled 2021-10-04 2021-10-11 2021-10-18 2021-11-01 2022-01-30 ant Selection pacidades tecnicas de entida k des involucradas en materia de catastro PE-COFOPRI-218137-CS-IND V / Contratación de experto 2 Component 2: Strengthening Individual Consult para el Fortalecimiento de ca IBRD / 90350 of the Institutional Framewor Post Limited 100,000.00 0.00 Canceled 2021-10-04 2021-10-11 2021-10-18 2021-11-01 2022-01-30 ant Selection pacidades técnicas de entida k des involucradas en materia de catastro PE-COFOPRI-218138-CS-IND V / Contratacion de experto 1 Component 2: Strengthening Individual Consult para el apoyo en el desarroll IBRD / 90350 of the Institutional Framewor Post Limited 50,000.00 0.00 Canceled 2021-10-05 2021-10-11 2021-10-19 2021-11-02 2022-01-31 ant Selection o de instrumentos de gestion k ROF CAP estandares protoco los PE-COFOPRI-218139-CS-IND V / Contratación de experto 2 Component 2: Strengthening Individual Consult para el apoyo en el desarroll IBRD / 90350 of the Institutional Framewor Post Limited 50,000.00 0.00 Canceled 2021-10-05 2021-10-11 2021-10-19 2021-11-02 2022-01-31 ant Selection o de instrumentos de gestión k ROF CAP estándares protocol os PE-COFOPRI-272648-CS-IND V / Servicio de consultoria in Component 1: Strengthening dividual de coordinación de a Municipal Systems, Services Individual Consult sistencia técnica en la gestió IBRD / 90350 and Capacities to Generate Post Open 15,000.00 15,000.00 Signed 2022-01-21 2022-01-22 2022-02-14 2022-02-18 2022-02-21 2022-02-18 2022-02-28 2022-03-22 2022-08-27 ant Selection n de la cartografía catastral a and Maintain Urban Cadaste las municipalidades priorizad rs in Project Municipalities as del Proyecto de Catastro U rbano PE-COFOPRI-272649-CS-IND V / Servicio de consultoria in Component 1: Strengthening dividual de coordinación de a Municipal Systems, Services Individual Consult sistencia técnica en la gestió IBRD / 90350 and Capacities to Generate Post Open 15,000.00 15,000.00 Signed 2022-01-21 2022-01-22 2022-02-14 2022-02-18 2022-02-21 2022-03-01 2022-02-28 2022-04-02 2022-08-27 ant Selection n de operaciones catastrales and Maintain Urban Cadaste a las municipalidades prioriz rs in Project Municipalities adas del Proyecto de Catastr o Urbano PE-COFOPRI-272650-CS-IND V / Servicio de consultoria in Component 1: Strengthening dividual de coordinación de a Municipal Systems, Services Individual Consult sistencia técnica en la gestió IBRD / 90350 and Capacities to Generate Post Open 15,000.00 15,000.00 Signed 2022-01-21 2022-01-22 2022-02-14 2022-02-18 2022-02-21 2022-03-01 2022-02-28 2022-03-19 2022-08-27 ant Selection n de sistemas y tecnologías d and Maintain Urban Cadaste e la información a las munici rs in Project Municipalities palidades priorizadas del Pro yecto de Catastro Urbano PE-COFOPRI-272651-CS-IND Component 1: Strengthening V / Servicio de consultoria in Municipal Systems, Services dividual de coordinación de a Individual Consult IBRD / 90350 and Capacities to Generate Post Open 15,000.00 15,000.00 Terminated 2022-01-21 2022-01-22 2022-02-14 2022-02-23 2022-02-21 2022-03-02 2022-02-28 2022-03-23 2022-08-27 sistencia técnica en la gestió ant Selection and Maintain Urban Cadaste n normativa a las municipalid rs in Project Municipalities ades priorizadas del Proyecto de Catastro Urbano PE-COFOPRI-272652-CS-IND V / Servicio de consultoria in Component 1: Strengthening dividual de coordinación de a Municipal Systems, Services sistencia técnica en la gestió Individual Consult IBRD / 90350 and Capacities to Generate Post Open 15,000.00 15,000.00 Signed 2022-01-21 2022-01-22 2022-02-14 2022-02-18 2022-02-21 2022-03-02 2022-02-28 2022-03-23 2022-08-27 n de planeamiento urbano y ant Selection and Maintain Urban Cadaste gestión de riesgos de desastr rs in Project Municipalities es a las municipalidades prio rizadas del Proyecto de Catas tro Urbano PE-COFOPRI-272653-CS-IND Component 1: Strengthening V / Servicio de consultoria in Municipal Systems, Services dividual de coordinación de a Individual Consult IBRD / 90350 and Capacities to Generate Post Open 15,000.00 15,000.00 Signed 2022-01-21 2022-01-18 2022-02-14 2022-02-18 2022-02-21 2022-03-02 2022-02-28 2022-03-22 2022-08-27 sistencia técnica en la gestió ant Selection and Maintain Urban Cadaste n fiscal a las municipalidades rs in Project Municipalities priorizadas del Proyecto de C atastro Urbano PE-COFOPRI-317832-CS-IND Component 1: Strengthening V / SERVICIO DE CONSULTOR Municipal Systems, Services Individual Consult Open - Internationa Under Implement ÍA INDIVIDUAL DE ASISTENCI IBRD / 90350 and Capacities to Generate Post 10,200.00 0.00 2022-10-03 2022-11-03 2022-11-21 2022-12-12 2023-01-16 2023-07-15 ant Selection l ation A TÉCNICA A LA MUNICIPALID and Maintain Urban Cadaste AD DE VEINTISÉIS DE OCTUB rs in Project Municipalities RE PE-COFOPRI-317834-CS-IND Component 1: Strengthening V / SERVICIO DE CONSULTOR Municipal Systems, Services Individual Consult Open - Internationa Under Implement ÍA INDIVIDUAL DE ASISTENCI IBRD / 90350 and Capacities to Generate Post 10,200.00 0.00 2022-10-03 2022-11-03 2022-11-21 2022-12-12 2023-01-16 2023-07-15 ant Selection l ation A TÉCNICA A LA MUNICIPALID and Maintain Urban Cadaste AD DE LAMBAYEQUE rs in Project Municipalities PE-COFOPRI-218033-CS-IND Component 1: Strengthening V / Consultoria individual de Municipal Systems, Services Individual Consult Pending Impleme Asistencia Tecnica Directa a l IBRD / 90350 and Capacities to Generate Post Open - National 15,000.00 0.00 2022-11-03 2022-12-08 2022-12-20 2023-01-03 2023-07-02 ant Selection ntation a Municipalidad de Lambaye and Maintain Urban Cadaste que rs in Project Municipalities PE-COFOPRI-325051-CS-IND Component 1: Strengthening V / SERVICIO DE CONSULTOR Municipal Systems, Services Individual Consult Under Implement ÍA INDIVIDUAL DE ASISTENCI IBRD / 90350 and Capacities to Generate Post Open - National 10,200.00 0.00 2022-11-10 2022-12-02 2022-12-29 2023-01-19 2023-02-23 2023-08-22 ant Selection ation A TÉCNICA A LA MUNICIPALID and Maintain Urban Cadaste AD PROVINCIAL DE CHICLAY rs in Project Municipalities O PE-COFOPRI-317835-CS-IND V / SERVICIO DE CONSULTOR ÍA INDIVIDUAL DE COORDINA Component 1: Strengthening CIÓN DE ASISTENCIA Municipal Systems, Services TÉCNICA EN LA GESTIÓN DE Individual Consult Under Implement IBRD / 90350 and Capacities to Generate Post Open - National 15,000.00 0.00 2022-11-25 2022-12-02 2023-01-13 2023-02-03 2023-03-10 2023-09-06 SISTEMAS Y TECNOLOGÍAS D ant Selection ation and Maintain Urban Cadaste E LA INFORMACIÓN rs in Project Municipalities A LAS MUNICIPALIDADES PRI ORIZADAS DEL PROYECTO D E CATASTRO URBANO. Page 4 PE-COFOPRI-335406-CS-IND V / Servicio de consultoría in Component 2: Strengthening Individual Consult Under Implement dividual Especialista para la IBRD / 90350 of the Institutional Framewor Post Limited 3,701.00 0.00 2023-01-16 2023-06-27 2023-01-18 2023-01-26 2023-01-31 2023-03-20 ant Selection ation elaboración de estándares ca k rtográficos aplicados al catas tro urbano PE-COFOPRI-335407-CS-IND V / Servicio de consultoría in Component 2: Strengthening Individual Consult Under Implement dividual Especialista para la IBRD / 90350 of the Institutional Framewor Post Limited 11,299.00 0.00 2023-01-16 2023-06-14 2023-01-18 2023-01-26 2023-01-31 2023-05-31 ant Selection ation elaboración y actualización d k e metodologías de levantami ento catastral PE-COFOPRI-355819-CS-IND Component 1: Strengthening V / Servicio de consultoria In Municipal Systems, Services Individual Consult Pending Impleme dividual Asistencia Técnica a IBRD / 90350 and Capacities to Generate Post Open - National 15,000.00 0.00 2023-04-14 2023-05-08 2023-05-20 2023-06-03 2023-11-30 ant Selection ntation la Municipalidad de Lima Met and Maintain Urban Cadaste ropolitana rs in Project Municipalities PE-COFOPRI-355821-CS-IND Component 1: Strengthening V / Servicio de consultoria in Municipal Systems, Services dividual de Coordinacion de Individual Consult Under Implement IBRD / 90350 and Capacities to Generate Post Open - National 16,210.00 0.00 2023-04-14 2023-05-25 2023-05-08 2023-06-14 2023-05-15 2023-06-21 2023-05-22 2023-11-18 Asistencia Tecnica en la Gest ant Selection ation and Maintain Urban Cadaste ion Normativa a las Municipal rs in Project Municipalities idades priorizadas del Proyec to de Catastro Urbano Component 1: Strengthening PE-COFOPRI-356067-CS-IND Municipal Systems, Services V / Servicio de consultoria in Individual Consult Under Implement IBRD / 90350 and Capacities to Generate Post Open - National 9,000.00 0.00 2023-04-17 2023-05-10 2023-04-29 2023-05-01 2023-05-07 2023-11-03 dividual Analista de Comunic ant Selection ation and Maintain Urban Cadaste aciones rs in Project Municipalities PE-COFOPRI-352574-CS-IND Component 1: Strengthening V / Servicio de consultoría in Municipal Systems, Services Individual Consult Under Implement dividual Responsable TIC de l IBRD / 90350 and Capacities to Generate Post Open - National 18,135.00 0.00 2023-03-31 2023-05-24 2023-04-19 2023-04-21 2023-04-27 2023-10-24 ant Selection ation a Plataforma de Capacitación and Maintain Urban Cadaste Virtual rs in Project Municipalities PE-COFOPRI-352631-CS-IND Component 1: Strengthening V / Servicio de consultoría in Municipal Systems, Services Individual Consult Under Implement dividual Tutor docente especi IBRD / 90350 and Capacities to Generate Post Open - National 12,090.00 0.00 2023-03-31 2023-05-25 2023-04-19 2023-04-21 2023-04-27 2023-10-24 ant Selection ation alista en capacitación en la t and Maintain Urban Cadaste emática de uso del catastro c rs in Project Municipalities on fines fiscales PE-COFOPRI-356059-CS-IND V / Servicio de consultoria in Component 2: Strengthening dividual Analista de Procesos Individual Consult Under Implement IBRD / 90350 of the Institutional Framewor Post Open - National 9,000.00 0.00 2023-04-17 2023-05-26 2023-04-29 2023-05-01 2023-05-07 2023-11-03 Catastro / Rentas 2 del Siste ant Selection ation k ma de Armonizacion de la Inf ormacion Catastral con el Re gistro de Contribuyentes PE-COFOPRI-356065-CS-IND V / Servicio de consultoria in Component 2: Strengthening dividual Analista de Procesos Individual Consult Under Implement IBRD / 90350 of the Institutional Framewor Post Open - National 9,000.00 0.00 2023-04-17 2023-05-26 2023-04-29 2023-05-01 2023-05-07 2023-11-03 Catastro / Rentas 5 del Siste ant Selection ation k ma de Armonizacion de la Inf ormacion Catastral con el Re gistro de Contribuyentes PE-COFOPRI-356063-CS-IND V / Servicio de consultoria in Component 2: Strengthening dividual Analista de Procesos Individual Consult Under Implement IBRD / 90350 of the Institutional Framewor Post Open - National 9,000.00 0.00 2023-04-17 2023-05-26 2023-04-29 2023-05-01 2023-05-07 2023-11-03 Catastro / Rentas 4 del Siste ant Selection ation k ma de Armonizacion de la Inf ormacion Catastral con el Re gistro de Contribuyentes PE-COFOPRI-352644-CS-IND Component 2: Strengthening Individual Consult Under Implement V / Servicio de Consultoría In IBRD / 90350 of the Institutional Framewor Post Open - National 20,000.00 0.00 2023-03-31 2023-05-11 2023-04-19 2023-04-21 2023-04-27 2023-10-24 ant Selection ation dividual QA Analyst k PE-COFOPRI-352630-CS-IND Component 1: Strengthening V / Servicio de consultoría in Municipal Systems, Services Individual Consult Under Implement dividual Tutor docente especi IBRD / 90350 and Capacities to Generate Post Open - National 12,090.00 0.00 2023-03-31 2023-05-25 2023-04-19 2023-04-21 2023-04-27 2023-10-24 ant Selection ation alista en capacitación, en la t and Maintain Urban Cadaste emática de actualización y m rs in Project Municipalities antenimiento catastral PE-COFOPRI-352634-CS-IND Component 2: Strengthening V / Especialista en Arquitectu Individual Consult Under Implement IBRD / 90350 of the Institutional Framewor Post Open - National 28,000.00 0.00 2023-03-31 2023-05-11 2023-04-19 2023-04-21 2023-04-27 2023-10-24 ra de Sistemas Catastrales/Pr ant Selection ation k ediales SCRUM Master PE-COFOPRI-352650-CS-IND V / Servicio de consultoria in Component 2: Strengthening dividual Analista Programado Individual Consult Under Implement IBRD / 90350 of the Institutional Framewor Post Open - National 9,000.00 0.00 2023-03-31 2023-05-26 2023-04-19 2023-04-21 2023-04-27 2023-10-24 r 1 del Sistema de Armonizac ant Selection ation k ion de la Informacion Catastr al con el Registro de Contribu yentes PE-COFOPRI-352639-CS-IND Component 2: Strengthening Individual Consult Under Implement V / Servicio de Consultoría In IBRD / 90350 of the Institutional Framewor Post Open - National 16,000.00 0.00 2023-03-31 2023-05-11 2023-04-19 2023-04-21 2023-04-27 2023-10-24 ant Selection ation dividual Agile Mobile 2 App k Developer PE-COFOPRI-352642-CS-IND Component 2: Strengthening V / Servicio de Consultoría In Individual Consult Under Implement IBRD / 90350 of the Institutional Framewor Post Open - National 20,000.00 0.00 2023-03-31 2023-05-11 2023-04-19 2023-04-21 2023-04-27 2023-10-24 dividualAgile Backend Develo ant Selection ation k per 2 (Sistemas y Bases de D atos) PE-COFOPRI-356060-CS-IND V / Servicio de consultoria in Component 2: Strengthening dividual Analista de Procesos Individual Consult Under Implement IBRD / 90350 of the Institutional Framewor Post Open - National 9,000.00 0.00 2023-04-17 2023-05-26 2023-04-29 2023-05-01 2023-05-07 2023-11-03 Catastro / Rentas 3 del Siste ant Selection ation k ma de Armonizacion de la Inf ormacion Catastral con el Re gistro de Contribuyentes PE-COFOPRI-352638-CS-IND Component 2: Strengthening Individual Consult Under Implement V / Servicio de Consultoría In IBRD / 90350 of the Institutional Framewor Post Open - National 20,000.00 0.00 2023-03-31 2023-05-11 2023-04-19 2023-04-21 2023-04-27 2023-10-24 ant Selection ation dividual Agile Mobile 1 App D k eveloper Senior PE-COFOPRI-356058-CS-IND V / Servicio de consultoria in Component 2: Strengthening dividual Analista Programado Individual Consult Under Implement IBRD / 90350 of the Institutional Framewor Post Open - National 9,000.00 0.00 2023-04-17 2023-05-26 2023-05-02 2023-05-04 2023-05-10 2023-11-06 r 2 del Sistema de Armonizac ant Selection ation k ion de la Informacion Catastr al con el Registro de Contribu yentes Page 5 PE-COFOPRI-352577-CS-IND Component 1: Strengthening V / Servicio de consultoría in Municipal Systems, Services Individual Consult Under Implement dividual Tutor docente especi IBRD / 90350 and Capacities to Generate Post Open - National 12,090.00 0.00 2023-03-31 2023-05-25 2023-04-19 2023-04-21 2023-04-27 2023-10-24 ant Selection ation alista en capacitación en la t and Maintain Urban Cadaste emática de levantamiento ca rs in Project Municipalities tastral urbano PE-COFOPRI-356066-CS-IND V / Servicio de consultoria in Component 2: Strengthening dividual Analista de Procesos Individual Consult Under Implement IBRD / 90350 of the Institutional Framewor Post Open - National 9,000.00 0.00 2023-04-17 2023-05-26 2023-04-29 2023-05-01 2023-05-07 2023-11-03 Catastro / Rentas 6 del Siste ant Selection ation k ma de Armonizacion de la Inf ormacion Catastral con el Re gistro de Contribuyentes PE-COFOPRI-352641-CS-IND Component 2: Strengthening V / Servicio de Consultoría In Individual Consult Under Implement IBRD / 90350 of the Institutional Framewor Post Open - National 20,000.00 0.00 2023-03-31 2023-05-11 2023-04-19 2023-04-21 2023-04-27 2023-10-24 dividual Agile Backend Devel ant Selection ation k oper 1 (Sistemas y Bases de Datos) PE-COFOPRI-352636-CS-IND Component 2: Strengthening V / Especialista Funcional en Individual Consult Under Implement IBRD / 90350 of the Institutional Framewor Post Open - National 26,000.00 0.00 2023-03-31 2023-05-11 2023-04-19 2023-04-21 2023-04-27 2023-10-24 Sistemas Catastrales/Predial ant Selection ation k es Cartográficos/GIS PE-COFOPRI-352640-CS-IND Component 2: Strengthening Individual Consult Under Implement V / Servicio de Consultoría In IBRD / 90350 of the Institutional Framewor Post Open - National 22,000.00 0.00 2023-03-31 2023-05-11 2023-04-19 2023-04-21 2023-04-27 2023-10-24 ant Selection ation dividual Agile FrontEnd Web k Developer PE-COFOPRI-352645-CS-IND Component 2: Strengthening Individual Consult Under Implement V / Servicio de Consultoría In IBRD / 90350 of the Institutional Framewor Post Open - National 20,000.00 0.00 2023-03-31 2023-05-11 2023-04-19 2023-04-21 2023-04-27 2023-10-24 ant Selection ation dividualDesarrollador Cartogr k áfico/GIS PE-COFOPRI-352646-CS-IND Component 2: Strengthening Individual Consult Under Implement V / Especialista en Nube y Se IBRD / 90350 of the Institutional Framewor Post Open - National 12,000.00 0.00 2023-03-31 2023-05-11 2023-04-19 2023-04-21 2023-04-27 2023-10-24 ant Selection ation guridad de la Información k Component 1: Strengthening PE-COFOPRI-352576-CS-IND Municipal Systems, Services V / Servicio de consultoría in Individual Consult Under Implement IBRD / 90350 and Capacities to Generate Post Open - National 21,158.00 0.00 2023-03-31 2023-05-24 2023-04-19 2023-04-21 2023-04-27 2023-10-24 dividual Responsable Técnico ant Selection ation and Maintain Urban Cadaste - Pedagógico rs in Project Municipalities PE-COFOPRI-352637-CS-IND Component 2: Strengthening Individual Consult Under Implement V / Servicio de Consultoría In IBRD / 90350 of the Institutional Framewor Post Open - National 26,000.00 0.00 2023-03-31 2023-05-11 2023-04-19 2023-04-21 2023-04-27 2023-10-24 ant Selection ation dividual Scrum Master k PE-COFOPRI-352648-CS-IND V / Servicio de consultoria in Component 2: Strengthening dividual Analista de Procesos Individual Consult Under Implement IBRD / 90350 of the Institutional Framewor Post Open - National 9,000.00 0.00 2023-04-17 2023-05-26 2023-04-29 2023-05-01 2023-05-07 2023-11-03 Catastro / Rentas 1 del Siste ant Selection ation k ma de Armonizacion de la Inf ormacion Catastral con el Re gistro de Contribuyentes PE-COFOPRI-352649-CS-IND V / Servicio de consultoria in Component 2: Strengthening Individual Consult Under Implement dividual Analista Senior del Si IBRD / 90350 of the Institutional Framewor Post Open - National 10,500.00 0.00 2023-03-31 2023-05-26 2023-04-19 2023-04-21 2023-04-27 2023-10-24 ant Selection ation stema de Armonización de la k Información Catastral con el Registro de Contribuyentes PE-COFOPRI-352632-CS-IND Component 1: Strengthening V / Servicio de consultoría in Municipal Systems, Services dividual Tutor docente especi Individual Consult Under Implement IBRD / 90350 and Capacities to Generate Post Open - National 12,090.00 0.00 2023-03-31 2023-05-25 2023-04-19 2023-04-21 2023-04-27 2023-10-24 alista en capacitación en la t ant Selection ation and Maintain Urban Cadaste emática de uso del catastro rs in Project Municipalities urbano con fines de gestión de riesgos de desastres PE-COFOPRI-352633-CS-IND Component 1: Strengthening V / Servicio de consultoría in Municipal Systems, Services dividual Tutor docente especi Individual Consult Under Implement IBRD / 90350 and Capacities to Generate Post Open - National 12,090.00 0.00 2023-03-31 2023-05-25 2023-04-19 2023-04-21 2023-04-27 2023-10-24 alista en capacitación en la t ant Selection ation and Maintain Urban Cadaste emática de uso del catastro rs in Project Municipalities urbano con fines de planifica ción urbana PE-COFOPRI-352635-CS-IND Component 2: Strengthening Individual Consult Under Implement V / Especialista Funcional en IBRD / 90350 of the Institutional Framewor Post Open - National 26,000.00 0.00 2023-03-31 2023-05-11 2023-04-19 2023-04-21 2023-04-27 2023-10-24 ant Selection ation Sistemas Catastrales/Predial k es Alfanuméricos PE-COFOPRI-352643-CS-IND Component 2: Strengthening Individual Consult Under Implement V / Servicio de Consultoría In IBRD / 90350 of the Institutional Framewor Post Open - National 16,000.00 0.00 2023-03-31 2023-05-11 2023-04-19 2023-04-21 2023-04-27 2023-10-24 ant Selection ation dividual Diseñador UX / UI k PE-COFOPRI-218032-CS-IND Component 1: Strengthening V / Servicio de consultoria in Municipal Systems, Services Individual Consult Under Implement dividual de Asistencia Tecnic IBRD / 90350 and Capacities to Generate Post Open - National 10,200.00 0.00 2023-05-29 2023-05-25 2023-07-03 2023-07-15 2023-07-29 2024-01-25 ant Selection ation a Directa a la Municipalidad and Maintain Urban Cadaste distrital de Pimentel rs in Project Municipalities PE-COFOPRI-218019-CS-IND Component 1: Strengthening V / Servicio de consultoria in Municipal Systems, Services Individual Consult Under Implement dividual de Asistencia Tecnic IBRD / 90350 and Capacities to Generate Post Open - National 10,200.00 0.00 2023-05-29 2023-05-25 2023-07-03 2023-07-15 2023-07-29 2024-01-25 ant Selection ation a Directa a la Municipalidad and Maintain Urban Cadaste distrital de San Miguel rs in Project Municipalities PE-COFOPRI-218025-CS-IND Component 1: Strengthening V / Servicio de consultoria in Municipal Systems, Services Individual Consult Under Implement dividual de Asistencia Tecnic IBRD / 90350 and Capacities to Generate Post Open - National 10,200.00 0.00 2023-05-29 2023-05-25 2023-07-03 2023-07-15 2023-07-29 2024-01-25 ant Selection ation a Directa a la Municipalidad and Maintain Urban Cadaste distrital de Surquillo rs in Project Municipalities PE-COFOPRI-218020-CS-IND Component 1: Strengthening V / Servicio de consultoria in Municipal Systems, Services Individual Consult Under Implement dividual de Asistencia Tecnic IBRD / 90350 and Capacities to Generate Post Open - National 10,200.00 0.00 2023-05-29 2023-05-25 2023-07-03 2023-07-15 2023-07-29 2024-01-25 ant Selection ation a Directa a la Municipalidad and Maintain Urban Cadaste distrital de Breña rs in Project Municipalities Page 6 PROCUREMENT PLAN (Textual Part) Project information: Maldives, MV: Learning Advancemnet and Measurement Project-P172631 Project Implementation agency: Ministry of Education (MoE) and the Ministry of Higher Education (MoHE) Date of the Procurement Plan: June 15, 2020 Period covered by this Procurement Plan: June 15, 2020– June 15, 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (The World Bank Procurement Regulations for IPF Borrowers- Procurement in Investment Project Financing- Goods, Works, Non-Consulting and Consulting Services, July 2016 Revised November 2017 and August 2018’- “Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Chapter on Public Procurement for Maldives’ Public Finance Regulations 2017, Chapter 10 – State Procurement System, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. 1) Only bidding documents acceptable to the Bank shall be used for all national open competitive procurement. 2) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 5) In case of Open Tendering, the receipt of less than three bids shall not be considered grounds for cancellation and re-invitation of bids. 6) Bid shall not be rejected merely on the basis of a comparison with an official estimate. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Not Applicable Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Not Applicable Table 5.1. Procurement Methods to Be Used in the Project Applicable for ‘Moderate’ risk Expenditur Contract Value Procurement Contracts/ e Category (threshold) Method Processes Subject to Prior Review Goods ≥US$100,000 Open International All contracts over US$750,000 $ 2,500 Open Tender as per Rwanda PPL RFQ – Limited Less than $ 2,500or as stipulated in Rwanda Procurement Regulations Direct Contracting No threshold; meet requirements of Bank’s Procurement Regulations Non- Open International Equal to or More than 1 million Consulting Open National (Non- Less than 1 million Services consulting Services) - Open Tender as per Rwanda PPL RFQ – Limited Less than $ 2,500or as stipulated in Rwanda Procurement Regulations Direct Contracting No threshold; meet requirements of Bank’s Procurement Regulations Works, Supply RFB - Open Equal to or more than 10 million & Installation International RFB - Open National – < $10 million and >$ 2,500 Open Tender as per Ministerial Order 2014 RFQ – Limited Less than $ 2,500or as stipulated in Rwanda Procurement Regulations Direct Contracting No threshold; meet requirements of Bank’s Procurement Regulations 2) Selection methods of procurement of Consultants' Services (Firms): The Approved Selection Methods as reflected in the Section VII of the procurement regulations. Selection Thresholds for Methods Procurement Method and arrangement * Quality and Cost As per requirements of para 7.3 of the Bank’s Based Selection Procurement Regulations (QCBS) Quality Based As per requirements of para 7.8 to 7.10 of the Selection (QBS) Regulations Selection based on a As per requirements of para 7.4 and 7.5 of the Fixed Budget (FBS) Regulations Selection Based on As per requirements of para 7.6 and 7.7 of the Least Cost Basis Regulations (LCS) Selection based on As per requirements of para 7.11 and 7.12 of the Consultant’s Regulations Qualification (CQ) Contracts estimated to cost equivalent of US$ 300,000 or less per contract Direct Selection Must meet the requirements of Para 7.13 to 7.15 of the Regulations, and with prior clearance by the Bank thru procurement plan. UN Agencies In accordance with paragraph 7.27 & 7.28 of the Procurement Regulations and with prior agreement in Procurement plan with the Bank NGOs In accordance with paragraph 7.29 of the Procurement Regulations. *procurement arrangements like direct contracting, use of SOEs, third party monitors, servants need, results based arrangements is not expected. There will no need for prequalification in the procurement arrangements under this project. The short list may consist of all National consultants in case the estimated cost is less than USD 200,000 per contract for consulting services, USD 300,000 for Engineering and Construction Supervision. 3) Procurement methods for Selection of Individual Consultants (IC): The Approved Selection Methods as reflected in the Section VII of the Procurement Regulations. Method of Procurement Thresholds for Methods Open Competitive Selection As per requirements of para 7.36 and 7.37 of the Regulations Limited Competitive As per requirements of para 7.38 of the Selection Regulations Direct Must meet the requirements of Para 7.39 of the Regulations, and with prior agreement in PP with the Bank 4) Prior Procurement Arrangements: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection. Type of procurement Bank’s Prior review threshold * Works All procurements estimated to cost more than USD 10million Goods All procurement estimated to cost more than USD 2 Million Consultant Firm All procurements estimated to cost more than USD 2 million Consultant Individual All procurement estimated to cost more than USD 300,000 *Substantial Risk: These thresholds are for the purposes of the initial procurement plan for the first 12 months. The thresholds may be increased or decreased based on re-assessment of risks. All contracts not subject to prior review will be post-reviewed. 5) For contracts subject to prior review, the Borrower shall seek the Bank’s no objection before agreeing to: (a) an extension of the stipulated time for execution of a contract that has an impact on the planned completion of the project; (b)any material modification of the scope of the Works, Goods, Non-consulting services or Consulting Services, or other significant changes to the terms and conditions of the contract; (c) any variation order or contract amendment (except in cases of extreme urgency), including due to extension of time, that singly or combined with all previous variation orders or amendments, increases the original contract amount by more than 15% (fifteen percent); or (d)the proposed termination of the contract. The Borrower / IA shall provide a copy of all amendments to the contract to the Bank for its records. 1. Pre-qualification: No 2. Any Other Special Procurement Arrangements: Not Applicable 3. Domestic Preference. The provision of domestic preference shall not be applied in the evaluation of bids in accordance with Annex VI of the Regulations. 4. Reference to Standard Procurement Documents Bank’s Standard RFB Works &Goods and RFP Consulting Services dated January 2017 will be used as a base and incorporating suitable modifications and the same would be agreed with the Bank subject to international competition. 5. Other Relevant Procurement Information: All contracts not covered under prior review by the Bank will be subject to post review during implementation support missions and/or special post review missions, including missions by consultants hired by the Bank. At any time, the Independent Procurement Reviews can be carried out by the Bank / by the consultants hired by the Bank. Even for Post Review cases, the inputs of Bank on Technical Specifications / TORs may be obtained by project. 6. Use of E-Procurement: The World Bank has assessed the adequacy of Government of Rwanda’s eProcurement system (http://www.umucyo.gov.rw/) and given go ahead for use of e-Procurement system for selection methods with Post Review contracts as approved in the Procurement Plan. PROCUREMENT Rwanda : Rwanda - Energy Access and Quality Improvement Project PLAN General Information Country: Rwanda 2021-04-29 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172594 GPN Date: 2022-06-02 Project Name: Rwanda - Energy Access and Quality Improvement Project Loan / Credit No: IDA / 67760 Rwanda Energy Group - Energy Development Corporation Limited Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure RW-REG/EDCL-229976-CW-R ment Document - Enhancing the Efficiency of Open - Internationa Single Stage - One E 11,000,000.0 Under Imple 2023-07-2 FB / Rehabilitation of the Nta IDA / 67760 Post Request for Bids 1 Envelope proce 0.00 2021-08-04 2021-07-08 2021-08-25 2021-10-24 2021-12-23 2022-01-29 Electricity Service l nvelope 0 mentation 3 ruka Hydro Power Plant ss (Non Bank-SPD ) RW-REG/EDCL-230153-CW-R National Procure FB / Electrification of Bwira, ment Document - Gatumba, Hindiro, Kabaya, K Increasing Access to Grid Ele Open - Internationa Single Stage - One E 20,159,763.0 25,106,409. 2023-04-1 IDA / 67760 Prior Request for Bids 1 Envelope proce Signed 2021-04-25 2021-08-31 2021-05-16 2021-09-08 2021-07-15 2021-11-18 2021-08-26 2022-05-16 2021-10-20 2022-08-26 ageyo, Kavumu, Matyazo, Mu ctricity l nvelope 0 37 3 ss (Non Bank-SPD handa, Muhororo, Ndaro, Nya ) nge, Sovu sectors of NGORO RERO District RW-REG/EDCL-230155-CW-R National Procure FB / Electrification of Mukami ment Document - ra, Jenda, Bigogwe, Kabatwa, Increasing Access to Grid Ele Open - Internationa Single Stage - One E 15,051,143.0 20,038,447. 2023-04-1 IDA / 67760 Prior Request for Bids 1 Envelope proce Signed 2021-04-25 2021-08-31 2021-05-16 2021-09-08 2021-07-15 2021-11-18 2021-08-26 2022-05-16 2021-10-20 2022-08-26 Kintobo, Rugera, Rurembo, S ctricity l nvelope 0 95 3 ss (Non Bank-SPD hyira, Jomba, Muringa, Ramb ) ura, Karago sectors of NYABI HU District RW-REG/EDCL-230878-CW-R FB / Electrification of Bukure; National Procure Bwisige; Byumba; Cyumba; G ment Document - iti; Kageyo; Manyagiro; Miyov Increasing Access to Grid Ele Open - Internationa Single Stage - One E 11,916,143.0 9,009,140.8 2022-12-0 IDA / 67760 Post Request for Bids 1 Envelope proce Signed 2020-12-15 2021-07-14 2021-01-05 2022-03-07 2021-03-06 2021-04-20 2021-04-17 2021-11-05 2021-06-11 2022-03-25 e; Mukarange; Muko; Mutete; ctricity l nvelope 0 0 3 ss (Non Bank-SPD Nyamiyaga; Nyankenke; Rub ) aya; Rukomo; Rushaki; Rutar e; Ruvune; Rwamiko; and Sh angasha sectors of GICUMBI District RW-REG/EDCL-230880-CW-R FB / Electrification of Bungwe National Procure ; Butaro; Cyanika; Cyeru; Ga ment Document - Increasing Access to Grid Ele Open - Internationa Single Stage - One E 12,262,143.0 9,477,645.3 2022-12-0 hunga; Gatebe; Gitovu; Kago IDA / 67760 Post Request for Bids 1 Envelope proce Signed 2020-12-15 2021-07-14 2021-01-05 2022-03-07 2021-03-06 2021-04-20 2021-04-17 2021-07-30 2021-06-11 2022-03-17 ctricity l nvelope 0 5 3 go; Kinoni; Kinyababa; Kivuy ss (Non Bank-SPD e; Nemba; Rugarama; Rugen ) gabari; Ruhunde; Rusarabuy e; Rwerere sectors of BURER A District National Procure RW-REG/EDCL-230879-CW-R ment Document - FB / Installation of automatic Enhancing the Efficiency of Open - Internationa Single Stage - One E 7,017,716.0 2022-12-0 IDA / 67760 Post Request for Bids 1 Envelope proce 7,640,000.00 Signed 2020-12-15 2020-12-31 2021-01-05 2022-03-07 2021-03-06 2021-05-06 2021-04-17 2021-06-20 2021-06-11 2021-12-10 voltage regulators on 220kV Electricity Service l nvelope 0 3 ss (Non Bank-SPD Subastations (Shango and R ) wabusoro) 010/W/2021-2022 /ICB/RUEA P/EAQIP / Design, supply, and installation of low voltage an Request for Bids - d medium voltage lines and s Increasing Access to Grid Ele Open - Internationa Single Stage - One E Works (without pr 29,474,900.0 Under Imple 2023-10-1 ervice connections in Ruhara IDA / 67760 Prior Request for Bids 0.00 2021-06-20 2022-01-17 2021-06-25 2022-03-01 2021-08-06 2022-04-14 2021-09-05 2022-09-26 2021-10-10 ctricity l nvelope equalification) SP 0 mentation 0 mbuga, Bushekeri, Bushenge D , Cyato, Gihombo, Kagano, K anjongo, Karambi, Karengera , Kirimbi, Macuba, Nyabiteker i, Mahembe, Rangiro, Shangi in Nyamashek 011/W/2021-2022/ICB/RUEA P/EAQIP / Design, supply, and installation of low voltage an d medium voltage lines and s Request for Bids - ervice connections in Bugara Increasing Access to Grid Ele Open - Internationa Single Stage - One E Works (without pr 21,277,000.0 2023-10-1 IDA / 67760 Prior Request for Bids 0.00 Canceled 2021-06-20 2021-09-08 2021-06-25 2021-10-15 2021-08-06 2022-01-14 2021-09-05 2021-10-10 ma, Butare, Bweyeye, Gikun ctricity l nvelope equalification) SP 0 0 damvura, Gashonga, Giheke, D Gihundwe, Gitambi, Kamemb e, Muganza, Mururu, Nkanka, Nkombo, Nkungu, Nyakabuy e, Nyakarenzo, Nzah RW-REG/EDCL-351067-CW-R FB / Design, Supply, and Inst allation of low voltage and m Request for Bids - edium voltage lines and servi Increasing Access to Grid Ele Open - Internationa Single Stage - One E Works (without pr Under Imple 2025-01-1 IDA / 67760 Post Request for Bids 9,692,547.00 0.00 2023-03-31 2023-04-18 2023-04-05 2023-04-18 2023-05-25 2023-06-24 2023-07-29 ce connections in Gashonga, ctricity l nvelope equalification) SP mentation 9 Nyakarenzo, Mururu, Nkungu D , Kamembe, Gihundwe, Gihe ke, Nkanka & Nkombo Sector s (Rusizi District) RW-REG/EDCL-351071-CW-R FB / Design, Supply, and Inst allation of low voltage and m Request for Bids - edium voltage lines and servi Increasing Access to Grid Ele Open - Internationa Single Stage - One E Works (without pr Under Imple 2024-12-0 IDA / 67760 Post Request for Bids 7,569,104.00 0.00 2023-03-31 2023-04-18 2023-04-05 2023-04-18 2023-04-10 2023-05-10 2023-06-14 ce connections in Bugarama, ctricity l nvelope equalification) SP mentation 5 Nzahaha, Rwimbogo, Muganz D a, Gikundamvura, Gitambi, N yakabuye, Bweyeye & Butare Sectors (Rusizi District) RW-REG/EDCL-355568-CW-R FB / DESIGN, SUPPLY, AND IN Request for Bids - STALLATION OF LOW VOLTA Increasing Access to Grid Ele Open - Internationa Single Stage - One E Works (without pr Under Imple 2025-02-1 IDA / 67760 Post Request for Bids 9,997,055.00 0.00 2023-04-14 2023-04-28 2023-04-19 2023-04-28 2023-06-18 2023-07-18 2023-08-22 GE AND MEDIUM VOLTAGE LI ctricity l nvelope equalification) SP mentation 2 NES AND SERVICE CONNECTI D ONS IN KARONGI DISTRICT RW-REG/EDCL-355569-CW-R Request for Bids - FB / DESIGN, SUPPLY, AND IN Increasing Access to Grid Ele Open - Internationa Single Stage - One E Works (without pr Under Imple 2025-02-1 STALLATION OF LOW VOLTA IDA / 67760 Post Request for Bids 9,960,749.00 0.00 2023-04-16 2023-04-28 2023-04-21 2023-04-28 2023-06-20 2023-07-20 2023-08-24 ctricity l nvelope equalification) SP mentation 4 GE AND MEDIUM VOLTAGE LI D NES AND SERVICE CONNECTI ONS IN RUTSIRO DISTRICT RW-REG/EDCL-355570-CW-R FB / DESIGN, SUPPLY, AND IN Request for Bids - STALLATION OF LOW VOLTA Increasing Access to Grid Ele Open - Internationa Single Stage - One E Works (without pr Under Imple 2025-02-1 IDA / 67760 Post Request for Bids 9,991,931.00 0.00 2023-04-16 2023-04-28 2023-04-21 2023-04-28 2023-06-20 2023-07-20 2023-08-24 GE AND MEDIUM VOLTAGE LI ctricity l nvelope equalification) SP mentation 4 NES AND SERVICE CONNECTI D ONS IN RULINDO DISTRICT Page 1 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-REG/EDCL-230148-GO-R Enhancing the Efficiency of Open - Internationa Single Stage - One E FB / Supply and Installation o IDA / 67760 Prior Request for Bids 6,000,000.00 0.00 Canceled 2022-08-04 2022-09-21 2022-08-25 2022-10-10 2022-10-24 2022-12-05 2023-01-29 2024-01-24 Electricity Service l nvelope f GiS system RW-REG/EDCL-230157-GO-R FB / Installation of power syst Enhancing the Efficiency of Open - Internationa Single Stage - One E Under Imple IDA / 67760 Post Request for Bids 3,500,000.00 0.00 2021-12-15 2022-10-17 2022-01-05 2022-10-17 2022-03-06 2023-01-27 2022-04-17 2022-06-14 2023-05-20 em stabilizers and governing Electricity Service l nvelope mentation systems on main generators RW-REG/EDCL-235852-GO-R Technical Assistance, Institu Open - Internationa Single Stage - One E FB / Supply of 2 Trucks and 5 IDA / 67760 tional Capacity Building and Post Request for Bids 952,212.00 1,071,369.98 Signed 2021-06-01 2021-06-16 2021-06-16 2021-11-26 2021-07-28 2021-09-09 2021-08-27 2021-09-28 2021-10-01 2022-03-05 2021-12-30 2022-07-01 l nvelope pick ups for Project operatio Implementation Support ns Technical Assistance, Institu RW-REG/EDCL-236070-GO-R Single Stage - One E IDA / 67760 tional Capacity Building and Post Request for Bids Open - National 45,000.00 82,552.11 Completed 2021-06-15 2021-11-26 2021-06-20 2021-11-26 2021-08-01 2021-08-26 2021-08-31 2021-09-06 2021-10-05 2021-12-04 2021-12-19 2022-02-05 FB / Acquisition of Furniture nvelope Implementation Support Technical Assistance, Institu RW-REG/EDCL-251716-GO-R Single Stage - One E IDA / 67760 tional Capacity Building and Post Request for Bids Open - National 166,740.00 276,479.75 Completed 2021-09-02 2021-11-26 2021-09-07 2021-11-26 2021-10-07 2021-08-26 2021-10-17 2021-09-06 2021-11-15 2021-12-03 2022-01-14 2022-03-01 FB / Supply of IT equipment nvelope Implementation Support RW-REG/EDCL-230639-GO-R FB / Electrification of Base; B ushoki; Buyoga; Cyinzuzi; Cy ungo; Kinihira; Kisaro; Masor Increasing Access to Grid Ele Open - Internationa Single Stage - One E IDA / 67760 Prior Request for Bids 10,476,480.00 0.00 Canceled 2021-05-15 2021-05-30 2021-05-30 2021-05-30 2021-05-30 2022-11-21 o; Mbogo; Murambi; Ngoma; ctricity l nvelope Ntarabana; Rukozo; Rusiga; Shyorongi; Tumba sectors of RULINDO District (Supply of e lectrical materials only) RW-REG/EDCL-230638-GO-R FB / Electrification of Bugeshi , Busasamana, Cyanzarwe, G Increasing Access to Grid Ele Open - Internationa Single Stage - One E isenyi, Kanama, Kanzenze, M IDA / 67760 Prior Request for Bids 8,794,000.00 0.00 Canceled 2021-05-15 2021-05-15 2021-05-15 2021-05-15 2021-05-30 2022-11-21 ctricity l nvelope udende, Nyakiriba, Nyamyu mba, Nyundo, Rubavu, Ruger ero sectors of RUBAVU Distri ct (supply of electrical materi als only) RW-REG/EDCL-230640-GO-R FB / Electrification of Busogo; Cyuve; Gacaca; Gashaki; Gat Increasing Access to Grid Ele Open - Internationa Single Stage - One E araga; Kimonyi; Kinigi; Muho IDA / 67760 Prior Request for Bids 9,216,120.00 0.00 Canceled 2021-05-15 2021-05-30 2021-05-30 2021-05-30 2021-05-30 2022-11-21 ctricity l nvelope za; Musanze; Muko, Nkotsi; N yange; Remera; Rwaza; Shin giro sectors of MUSANZE Dist rict (supply of electrical mate rials only) RW-REG/EDCL-253748-GO-R FB / Supply of MV-Pole acces Increasing Access to Grid Ele Open - Internationa Single Stage - One E IDA / 67760 Post Request for Bids 3,785,747.00 0.00 Canceled 2021-09-16 2021-09-21 2021-11-02 2021-11-12 2021-11-27 2022-11-27 sories for electrification of Ru ctricity l nvelope bavu, Musanze and Rulindo Districts RW-REG/EDCL-253814-GO-R FB / Supply of Concrete Poles Increasing Access to Grid Ele Open - Internationa Single Stage - One E (Concrete poles 12m 650daN IDA / 67760 Post Request for Bids 317,939.71 0.00 Canceled 2021-09-16 2021-09-21 2021-11-02 2021-11-12 2021-11-27 2022-11-27 ctricity l nvelope ) for electrification of Rubavu , Musanze and Rulindo distric ts RW-REG/EDCL-253745-GO-R FB / Supply of MV Steel Poles Increasing Access to Grid Ele Open - Internationa Single Stage - One E (MV Steel poles 12m and MV IDA / 67760 Post Request for Bids 1,892,873.40 0.00 Canceled 2021-09-16 2021-09-21 2021-11-02 2021-11-12 2021-11-27 2022-11-27 ctricity l nvelope Steel poles 14m) for electrific ation of Rubavu, Musanze an d Rulindo Districts RW-REG/EDCL-253767-GO-R FB / Supply of LV Accessories Increasing Access to Grid Ele Open - Internationa Single Stage - One E IDA / 67760 Post Request for Bids 2,985,689.54 0.00 Canceled 2021-09-16 2021-09-21 2021-11-02 2021-11-12 2021-11-27 2022-11-27 for electrification of Rubavu, ctricity l nvelope Musanze and Rulindo district s RW-REG/EDCL-253776-GO-R FB / Supply of Line protection Increasing Access to Grid Ele Open - Internationa Single Stage - One E IDA / 67760 Post Request for Bids 75,027.15 0.00 Canceled 2021-09-16 2021-09-21 2021-11-02 2021-11-12 2021-11-27 2022-11-27 materials for electrification of ctricity l nvelope Rubavu, Musanze and Rulind o districts RW-REG/EDCL-253758-GO-R FB / Supply of LV Cables for e Increasing Access to Grid Ele Open - Internationa Single Stage - One E IDA / 67760 Prior Request for Bids 7,439,118.90 0.00 Canceled 2021-09-16 2021-09-21 2021-11-02 2021-11-12 2021-11-27 2022-11-27 lectrification of Rubavu, Mus ctricity l nvelope anze and Rulindo Districts RW-REG/EDCL-253761-GO-R FB / Supply of Prepayment M Increasing Access to Grid Ele Open - Internationa Single Stage - One E eters (Single Phase Meters, T IDA / 67760 Post Request for Bids 1,298,346.30 0.00 Canceled 2021-09-16 2021-09-21 2021-11-02 2021-11-12 2021-11-27 2022-11-27 ctricity l nvelope hree Phase Meters) for electri fication of Rubavu, Musanze and Rulindo districts RW-REG/EDCL-253765-GO-R FB / Supply of Service Cables Increasing Access to Grid Ele Open - Internationa Single Stage - One E IDA / 67760 Prior Request for Bids 6,825,093.90 0.00 Canceled 2021-09-16 2021-09-21 2021-11-02 2021-11-12 2021-11-27 2022-11-27 for electrification of Rubavu, ctricity l nvelope Musanze and Rulindo District s RW-REG/EDCL-253809-GO-R FB / Supply of ACSR Conduct Increasing Access to Grid Ele Open - Internationa Single Stage - One E IDA / 67760 Post Request for Bids 3,819,494.80 0.00 Canceled 2021-09-16 2021-09-21 2021-11-02 2021-11-12 2021-11-27 2022-11-27 ors & MV Cables for electrific ctricity l nvelope ation of Rubavu, Musanze an d Rulindo districts RW-REG/EDCL-253822-GO-R FB / Supply of Wooden Poles Increasing Access to Grid Ele Open - Internationa Single Stage - One E IDA / 67760 Post Request for Bids 3,998,000.00 0.00 Canceled 2021-09-16 2021-09-21 2021-11-02 2021-11-12 2021-11-27 2022-11-27 for electrification of Rubavu, ctricity l nvelope Musanze and Rulindo district RW-REG/EDCL-253770-GO-R FB / Supply of Power Transfor Increasing Access to Grid Ele Open - Internationa Single Stage - One E mers (2kVA, 50kVA, 100kVA, IDA / 67760 Post Request for Bids 1,857,798.95 0.00 Canceled 2021-09-16 2021-09-21 2021-11-02 2021-11-12 2021-11-27 2022-11-27 ctricity l nvelope 160kVA, 250kVA, 400kVA) fo r electrification of Rubavu, M usanze and Rulindo Districts Page 2 RW-REG/EDCL-253773-GO-R FB / Supply of LV Distribution Increasing Access to Grid Ele Open - Internationa Single Stage - One E IDA / 67760 Post Request for Bids 857,366.40 0.00 Canceled 2021-09-16 2021-09-21 2021-11-02 2021-11-12 2021-11-27 2022-11-27 Boxes (LVDB) for electrificati ctricity l nvelope on of Rubavu, Musanze and Rulindo Districts MOF-REF-1 / Supply of MV Po Increasing Access to Grid Ele Open - Internationa Single Stage - One E Under Imple IDA / 67760 Post Request for Bids 3,785,747.00 0.00 2021-01-15 2021-12-24 2021-01-15 2021-12-24 2021-03-05 2022-03-02 2021-05-21 2022-07-13 2021-06-17 2022-06-17 le accessories ctricity l nvelope mentation MOF-REF-2 / Supply of LV Ca Increasing Access to Grid Ele Open - Internationa Single Stage - One E IDA / 67760 Prior Request for Bids 7,439,118.90 0.00 Canceled 2021-01-15 2021-01-15 2021-03-05 2021-05-20 2021-10-04 2022-10-04 bles ctricity l nvelope MOF-REF-5 / Supply of Servic Increasing Access to Grid Ele Open - Internationa Single Stage - One E IDA / 67760 Prior Request for Bids 6,825,093.90 0.00 Canceled 2021-01-15 2021-01-15 2021-03-05 2021-07-26 2021-10-04 2022-10-04 e Cables ctricity l nvelope MOF-REF-6 / Supply of LV Ac Increasing Access to Grid Ele Open - Internationa Single Stage - One E Under Imple IDA / 67760 Post Request for Bids 2,985,689.54 0.00 2019-02-15 2022-11-02 2019-02-15 2023-02-21 2019-04-26 2023-02-20 2020-01-24 2020-05-18 2022-05-18 cessories ctricity l nvelope mentation MOF-REF-7 / Supply of Power Increasing Access to Grid Ele Open - Internationa Single Stage - One E Under Imple IDA / 67760 Post Request for Bids 1,857,798.95 0.00 2020-04-17 2021-12-13 2020-04-17 2021-12-24 2020-06-12 2022-03-02 2020-12-17 2021-04-06 2022-04-06 Transformers ctricity l nvelope mentation MOF-REF-8 / Supply of Concr Increasing Access to Grid Ele Open - Internationa Single Stage - One E IDA / 67760 Post Request for Bids 317,939.71 467.47 Signed 2019-02-15 2021-12-13 2019-02-15 2022-09-22 2019-04-26 2019-04-26 2020-07-19 2020-01-24 2021-06-24 2021-06-25 2022-06-24 ete Poles ctricity l nvelope MOF-REF-9 / Supply of ACSR Increasing Access to Grid Ele Open - Internationa Single Stage - One E Under Imple IDA / 67760 Post Request for Bids 3,819,494.80 0.00 2021-01-15 2021-12-13 2021-01-15 2021-12-24 2021-03-05 2022-03-02 2021-05-21 2022-07-13 2021-08-21 2022-08-21 Conductors & MV Cables ctricity l nvelope mentation MOF-REF-10 / Supply of MV Increasing Access to Grid Ele Open - Internationa Single Stage - One E Under Imple IDA / 67760 Post Request for Bids 75,027.15 0.00 2019-02-15 2021-12-13 2019-02-15 2021-12-24 2019-04-26 2022-03-02 2020-01-24 2022-07-13 2020-05-05 2022-05-05 Accessories (Line protection ctricity l nvelope mentation materials) MOF-REF-11 / Supply of LV D Increasing Access to Grid Ele Open - Internationa Single Stage - One E Under Imple IDA / 67760 Post Request for Bids 857,366.40 0.00 2019-02-15 2021-12-13 2019-02-15 2021-12-24 2019-04-26 2022-03-02 2020-01-24 2020-08-18 2022-08-18 istribution Boxes (LVDB) ctricity l nvelope mentation MOF-REF-12 / Supply of Woo Increasing Access to Grid Ele Open - Internationa Single Stage - One E IDA / 67760 Post Request for Bids 3,998,000.00 1,343.00 Signed 2019-01-25 2021-12-13 2019-01-25 2022-09-22 2019-03-14 2019-03-14 2019-05-02 2019-05-02 2019-08-27 2019-08-28 2022-08-26 den Poles ctricity l nvelope RW-REG/EDCL-230144-GO-R FB / Supply and installation o Enhancing the Efficiency of Open - Internationa Single Stage - One E IDA / 67760 Prior Request for Bids 4,500,000.00 0.00 Canceled 2021-04-30 2021-05-30 2021-07-29 2021-09-27 2021-10-25 2022-10-20 f smart metering for all distri Electricity Service l nvelope bution transformers and med ium/large customer RW-REG/EDCL-265250-GO-D Increasing Access to Grid Ele Open - Internationa Single Stage - One E IR / Supply of prepaid meters IDA / 67760 Prior Request for Bids 4,500,000.00 0.00 Signed 2022-02-14 2022-05-10 2022-03-20 2022-05-23 2022-05-04 2022-07-12 2022-06-03 2023-01-23 2022-07-05 2022-10-03 ctricity l nvelope and ready boards RW-REG/EDCL-283635-GO-D Increasing Access to Grid Ele IR / Supply of service cables f IDA / 67760 Post Direct Selection Direct 3,800,000.00 27,664.00 Signed 2022-03-15 2022-04-06 2022-03-20 2022-04-06 2022-04-24 2022-04-07 2022-10-21 ctricity or connecting Musanze and R ubavu districts RW-REG/EDCL-283637-GO-R Increasing Access to Grid Ele Open - Internationa Single Stage - One E FB / SUPPLY OF DIGITAL DIST IDA / 67760 Post Request for Bids 990,000.00 0.00 Signed 2022-03-25 2022-05-05 2022-03-30 2022-05-05 2022-05-11 2022-06-20 2022-06-10 2022-10-12 2022-07-15 2023-01-11 ctricity l nvelope URBANCE FAULT RECORDER S RW-REG/EDCL-283639-GO-R Increasing Access to Grid Ele Open - Internationa Single Stage - One E Pending Impl FB / SUPPLY OF METER TESTI IDA / 67760 Post Request for Bids 280,000.00 0.00 2022-03-25 2022-03-30 2022-05-11 2022-06-10 2022-07-15 2023-01-11 ctricity l nvelope ementation NG AND CALIBRATION RW-REG/EDCL-300336-GO-D Increasing Access to Grid Ele IR / Supply of smart meters u IDA / 67760 Post Direct Selection Direct 3,200,000.00 542,735.00 Signed 2022-06-19 2022-09-01 2022-06-24 2021-05-24 2022-07-05 2021-11-27 2022-11-04 ctricity nder existing framework cont ract RW-REG/EDCL-300341-GO-R Increasing Access to Grid Ele Open - Internationa Single Stage - One E Under Imple FB / Supply of accessories an IDA / 67760 Post Request for Bids 3,129,000.00 0.00 2022-07-22 2023-02-09 2022-07-27 2023-02-21 2022-09-07 2022-10-07 2022-11-11 2023-05-10 ctricity l nvelope mentation d tools for smart meters inst allation RW-REG/EDCL-317424-GO-R Increasing Access to Grid Ele Single Stage - One E Under Imple IDA / 67760 Post Request for Bids Open - National 260,000.00 0.00 2022-09-28 2022-10-17 2022-10-03 2022-10-17 2022-11-14 2023-02-13 2022-12-14 2023-01-18 2023-07-17 FB / Supply of Protective Equi ctricity nvelope mentation pment RW-REG/EDCL-236090-GO-R FB / Electrification of Bwishyu ra, Gishyita, Gitesi, Mubuga, Increasing Access to Grid Ele Open - Internationa Single Stage - One E Murambi, Murundi, Mutuntu, IDA / 67760 Post Request for Bids 2,372,000.00 0.00 Canceled 2021-06-15 2021-06-20 2021-08-01 2021-08-31 2021-10-05 2022-10-05 ctricity l nvelope Rubengera, Rugabano, Rwan kuba, Twumba sectors of KA RONGI District (Design and In stallation works only) RW-REG/EDCL-236100-GO-R FB / Electrification of Boneza, Gihango, Kigeyo, Kivumu, Ma Increasing Access to Grid Ele Open - Internationa Single Stage - One E nihira,Mukura, Murunda,Mus IDA / 67760 Post Request for Bids 3,731,000.00 0.00 Canceled 2021-06-15 2021-06-20 2021-08-01 2021-08-31 2021-10-05 2022-10-05 ctricity l nvelope asa,Mushonyi,Mushubati,Nya birasi,Ruhango,Rusebeya sec tors of RUTSIRO District (Desi gn and Installation works onl y) RW-REG/EDCL-332095-GO-R FB / Supply of MV Poles Acce Increasing Access to Grid Ele Open - Internationa Single Stage - One E IDA / 67760 Prior Request for Bids 4,648,627.70 0.00 Canceled 2022-12-23 2022-12-28 2023-02-11 2023-03-13 2023-04-17 2023-10-14 ssories for Rulindo, Rutsiro a ctricity l nvelope nd Karongi Districts RW-REG/EDCL-331512-GO-R FB / Supply of Prepaid meter Increasing Access to Grid Ele Open - Internationa Single Stage - One E IDA / 67760 Prior Request for Bids 4,000,714.65 0.00 Canceled 2023-01-08 2023-01-13 2023-02-27 2023-03-29 2023-05-12 2023-10-09 s and ready boards for Rulind ctricity l nvelope o, Karongi and Rutsiro distric ts RW-REG/EDCL-332099-GO-R FB / Supply of Transformers, Increasing Access to Grid Ele Open - Internationa Single Stage - One E IDA / 67760 Prior Request for Bids 4,058,475.06 0.00 Canceled 2022-12-23 2022-12-28 2023-02-11 2023-03-13 2023-04-17 2023-10-14 Distribution Boxes, and Line ctricity l nvelope protection for Rulindo, Rutsir o and Karongi districts RW-REG/EDCL-332100-GO-R Increasing Access to Grid Ele Open - Internationa Single Stage - One E FB / Supply of Service Cables IDA / 67760 Prior Request for Bids 7,269,141.15 0.00 Canceled 2022-12-23 2022-12-28 2023-02-11 2023-03-13 2023-04-17 2023-10-14 ctricity l nvelope for Rulindo, Rutsiro and Karo ngi districts RW-REG/EDCL-332101-GO-R Increasing Access to Grid Ele Open - Internationa Single Stage - One E FB / Supply of LV Accessories IDA / 67760 Prior Request for Bids 6,912,379.48 0.00 Canceled 2022-12-23 2022-12-28 2023-02-11 2023-03-13 2023-04-17 2023-10-14 ctricity l nvelope for Rulindo, Rutsiro and Karo ngi districts RW-REG/EDCL-332104-GO-R Increasing Access to Grid Ele Open - Internationa Single Stage - One E FB / Supply of LV Cables for R IDA / 67760 Prior Request for Bids 12,464,672.52 0.00 Canceled 2022-12-23 2022-12-28 2023-02-11 2023-03-13 2023-04-17 2023-10-14 ctricity l nvelope utsiro, Rulindo and Karongi di stricts Page 3 RW-REG/EDCL-332106-GO-R FB / Supply of ACSR Conduct Increasing Access to Grid Ele Open - Internationa Single Stage - One E IDA / 67760 Prior Request for Bids 4,916,051.42 0.00 Canceled 2022-12-23 2022-12-28 2023-02-11 2023-03-13 2023-04-17 2023-10-14 ors and MV Cables for Rutsiro ctricity l nvelope , Rulindo and Karongi district s RW-REG/EDCL-341323-GO-R FB / Supply and installation o Increasing Access to Grid Ele Under Imple f IBMS Support & Maintenanc IDA / 67760 Post Direct Selection Direct - National 313,697.86 0.00 2023-02-10 2023-04-04 2023-02-15 2023-05-03 2023-02-22 2024-02-22 ctricity mentation e and New License for effecti ve and efficient management of EAQIP Project RW-REG/EDCL-339043-GO-R Increasing Access to Grid Ele Open - Internationa Single Stage - One E FB / Supply and Installation o IDA / 67760 Prior Request for Bids 6,000,000.00 0.00 Canceled 2023-01-30 2023-02-04 2023-03-18 2023-04-17 2023-05-22 2023-11-18 ctricity l nvelope f GiS system RW-REG/EDCL-355571-NC-DI Increasing Access to Grid Ele Under Imple IDA / 67760 Post Direct Selection Direct - National 2,000,000.00 0.00 2023-04-14 2023-04-19 2023-04-19 2023-05-24 2023-11-20 R / Upgrade of GIS system ctricity mentation RW-REG/EDCL-363657-GO-D Increasing Access to Grid Ele Direct - Internation Under Imple IR / IBMIS support and maint IDA / 67760 Post Direct Selection 806,000.00 0.00 2023-05-25 2023-02-02 2023-05-30 2023-06-27 2025-06-26 ctricity al mentation enance services NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-REG/EDCL-238704-NC-DI Increasing Access to Off-Grid R / Provision of domestic coo IDA / 67760 Electricity and Clean Cookin Post Direct Selection Direct 60,000.00 114.19 Signed 2021-06-18 2021-06-29 2021-06-23 2021-07-16 2021-07-06 2021-07-13 2023-07-06 king appliance testing servic g Solutions es RW-REG/EDCL-242557-NC-DI Increasing Access to Off-Grid R / Hiring the National Data C IDA / 67760 Electricity and Clean Cookin Post Direct Selection Direct 3,800.00 3,493.93 Signed 2021-07-09 2021-07-15 2021-07-14 2021-07-15 2021-07-28 2021-08-05 2024-07-27 enter for Hosting Off-grid Ma g Solutions nagement Information Syste m (OMIS) RW-REG/EDCL-238709-NC-R Increasing Access to Off-Grid FB / Supply of clean cooking Single Stage - One E IDA / 67760 Electricity and Clean Cookin Post Request for Bids Open - National 220,000.00 0.00 Canceled 2021-06-17 2021-06-22 2021-08-03 2021-08-24 2021-09-22 2022-03-21 RBF information managemen nvelope g Solutions t tool (software development , training of users, etc) RW-REG/EDCL-235753-NC-R Technical Assistance, Institu Single Stage - One E FB / Acquisition of financial m IDA / 67760 tional Capacity Building and Post Request for Bids Limited 44,674.96 0.00 Canceled 2021-06-15 2021-06-20 2021-08-01 2021-08-31 2021-10-05 2021-12-04 nvelope anagement software Implementation Support RW-REG/EDCL-351089-NC-DI Increasing Access to Grid Ele R / Renewal of different soft IDA / 67760 Post Direct Selection Direct - National 30,142.43 0.00 Signed 2023-03-20 2023-03-26 2023-03-25 2023-03-31 2023-04-29 2023-06-04 ctricity wares licenses CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-REG/EDCL-232319-CS-Q CBS / Consultancy Services o Technical Assistance, Institu f Supervision of Rural Electrifi Quality And Cost- Open - Internationa IDA / 67760 tional Capacity Building and Prior 3,600,000.00 0.00 Signed 2020-12-15 2021-07-12 2020-12-29 2021-03-27 2021-12-15 2021-04-24 2022-01-28 2021-06-23 2022-08-24 2021-07-28 2022-09-19 2021-08-25 2026-06-20 cation Construction Works u Based Selection l Implementation Support nder Rwanda Energy Access and Quality Improvement Pro ject RW-REG/EDCL-235737-CS-Q CBS / Hiring a consultant firm Technical Assistance, Institu Quality And Cost- Open - Internationa (s) as Independent Verificatio IDA / 67760 tional Capacity Building and Prior 700,000.00 0.00 Canceled 2021-05-26 2021-06-10 2021-06-16 2021-07-12 2021-07-30 2021-10-29 2021-08-27 2022-03-07 2021-09-26 2022-08-24 2021-10-31 2021-12-05 2023-12-05 Based Selection l n Agency (IVAs) for verificati Implementation Support on of solar home systems an d clean cooking claims RW-REG/EDCL-235748-CS-Q CBS / Hiring a Supervision fir m for design, supply and inst Enhancing the Efficiency of Quality And Cost- Open - Internationa IDA / 67760 Post 460,000.00 0.00 Canceled 2021-06-01 2021-06-22 2021-08-05 2021-09-02 2021-10-02 2021-11-06 2021-12-11 2024-03-30 allation of low voltage and m Electricity Service Based Selection l edium voltage lines and servi ce connections in Ngoreroro and Nyabihu Districts RW-REG/EDCL-238721-CS-Q Increasing Access to Off-Grid Quality And Cost- CBS / Recruitment of a mark IDA / 67760 Electricity and Clean Cookin Post Open - National 240,000.00 200,737.88 Signed 2021-06-21 2021-08-09 2021-07-12 2021-08-25 2021-08-25 2021-10-20 2021-09-22 2021-11-19 2021-10-22 2021-12-03 2021-11-26 2021-12-22 2021-12-31 2022-02-10 2023-12-31 Based Selection et facilitator firm for clean co g Solutions oking technologies RW-REG/EDCL-238713-CS-Q CBS / Recruitment of a comm Increasing Access to Off-Grid Quality And Cost- unication firm to support the IDA / 67760 Electricity and Clean Cookin Post Open - National 484,600.00 424,353.26 Signed 2021-06-18 2021-06-24 2021-07-09 2021-08-10 2021-08-22 2021-10-08 2021-09-19 2021-11-19 2021-10-19 2021-12-08 2021-11-23 2022-03-22 2021-12-28 2022-05-26 2023-12-28 Based Selection campaign for clean cooking a g Solutions wareness and behavior chan ge RW-REG/EDCL-236115-CS-Q CBS / SUPERVISION FIRM FOR Enhancing the Efficiency of Quality And Cost- Open - Internationa IDA / 67760 Post 460,000.00 0.00 Canceled 2021-08-16 2021-06-06 2021-09-06 2021-10-20 2021-11-17 2021-12-17 2022-01-21 2022-02-25 2024-02-25 NTARUKA HPP, SVCs AND VO Electricity Service Based Selection l LTAGE STABILIZER RW-REG/EDCL-265242-CS-Q Increasing Access to Grid Ele Quality Based Sel Open - Internationa Under Implement CBS / Supervision of Static V IDA / 67760 Post 230,000.00 0.00 2022-01-21 2022-02-02 2022-02-01 2022-03-25 2022-03-17 2022-04-14 2022-05-14 2022-06-13 2022-07-18 2023-07-18 ctricity ection l ation AR Compensator (SVCs) RW-REG/EDCL-300253-CS-Q CBS / Consultant service to c Increasing Access to Grid Ele Quality And Cost- Open - Internationa Under Implement arry out a feasibility study of IDA / 67760 Post 300,000.00 0.00 2022-07-08 2022-08-18 2022-07-29 2022-10-17 2022-09-11 2022-10-09 2022-11-08 2022-12-13 2023-01-17 2024-01-17 ctricity Based Selection l ation pump storage at Ntaruka hH PP and comparison with othe r alternative options RW-REG/EDCL-230888-CS-Q CBS / Consultancy Services: Technical Assistance, Institu Quality And Cost- Open - Internationa Organization and Supervision IDA / 67760 tional Capacity Building and Prior 2,000,000.00 0.00 Canceled 2020-12-15 2020-12-29 2021-03-27 2021-04-24 2021-06-23 2021-07-28 2021-09-01 2025-08-11 Based Selection l of Capacity Building Program Implementation Support s to Strengthen the Energy S ector in Rwanda Page 4 RW-REG/EDCL-339044-CS-Q Enhancing the Efficiency of Quality Based Sel Under Implement BS / Hiring A Firm To Conduct IDA / 67760 Post Open - National 50,000.00 0.00 2023-01-31 2023-01-30 2023-02-21 2023-06-23 2023-04-06 2023-05-04 2023-06-03 2023-07-03 2023-08-07 2024-08-06 Electricity Service ection ation Impact Assessment For RESS P RW-REG/EDCL-344186-CS-Q BS / Recruitment of a consult Increasing Access to Grid Ele Quality Based Sel Under Implement IDA / 67760 Post Open - National 57,036.00 0.00 2023-02-20 2023-03-06 2023-02-23 2023-06-23 2023-03-29 2023-04-26 2023-05-26 2023-06-25 2023-07-30 2024-07-29 ant to design loan product fo ctricity ection ation r Clean Cooking financing. RW-REG/EDCL-351084-CW-R FB / Consultancy services for Increasing Access to Grid Ele Quality And Cost- Open - Internationa Under Implement IDA / 67760 Prior 4,000,000.00 0.00 2023-03-20 2023-05-18 2023-04-10 2023-06-22 2023-05-24 2023-06-21 2023-07-21 2023-08-25 2023-09-29 2024-09-28 GIS Network data collection c ctricity Based Selection l ation ustomers mapping & Indexin g RW-REG/EDCL-265238-CS-Q Increasing Access to Grid Ele Quality And Cost- Under Implement CBS / Consultancy Services f IDA / 67760 Post Open - National 100,000.00 0.00 2023-04-16 2023-04-19 2023-05-07 2023-06-20 2023-07-18 2023-08-17 2023-09-21 2023-10-26 2024-04-23 ctricity Based Selection ation or a Baseline survey and Imp act assessment RW-REG/EDCL-366656-CS-Q Increasing Access to Off-Grid BS / Hiring Emission Reductio Quality Based Sel Open - Internationa Pending Impleme IDA / 67760 Electricity and Clean Cookin Post 50,000.00 0.00 2023-06-12 2023-07-03 2023-08-16 2023-09-13 2023-10-13 2023-11-12 2023-12-17 2023-12-26 n (ER) third-party independe ection l ntation g Solutions nt verifier for EAQIP INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-REG/EDCL-243427-CS-IN Technical Assistance, Institu DV / Hiring a Administrative Individual Consult IDA / 67760 tional Capacity Building and Post Open 62,369.35 760.47 Signed 2021-07-18 2021-08-23 2021-09-05 2021-08-27 2021-09-26 2022-03-21 2021-10-31 2022-03-22 2026-10-30 Assistant for Rwanda Energy ant Selection Implementation Support Access and Quality Improve ment Project RW-REG/EDCL-243428-CS-IN Technical Assistance, Institu DV / Hiring an Internal Audito Individual Consult IDA / 67760 tional Capacity Building and Post Open 89,338.64 1,250.96 Signed 2021-07-18 2021-08-23 2021-09-05 2022-04-14 2021-09-26 2022-08-19 2021-10-31 2022-08-20 2026-10-30 r for Rwanda Energy Access ant Selection Implementation Support and Quality Improvement Pro ject RW-REG/EDCL-243432-CS-IN Technical Assistance, Institu DV / Hiring a Generation Proj Individual Consult IDA / 67760 tional Capacity Building and Post Open 89,338.64 0.00 Canceled 2021-07-18 2021-08-05 2021-09-05 2021-09-26 2021-10-31 2026-10-30 ect Manager for Rwanda Ene ant Selection Implementation Support rgy Access and Quality Impro vement Project RW-REG/EDCL-243438-CS-IN DV / Hiring a Senior Contract Technical Assistance, Institu Individual Consult Management Specialist for R IDA / 67760 tional Capacity Building and Post Open 119,359.56 2,359.68 Signed 2021-07-18 2021-11-02 2021-09-05 2021-12-01 2021-09-26 2022-07-27 2021-10-31 2022-07-28 2026-10-30 ant Selection wanda Energy Access and Qu Implementation Support ality Improvement Project RW-REG/EDCL-243442-CS-IN DV / Hiring a Senior Environ Technical Assistance, Institu Individual Consult mental & social safeguard S IDA / 67760 tional Capacity Building and Post Open 119,359.56 1,899.25 Signed 2021-07-18 2021-08-26 2021-09-05 2021-08-27 2021-09-26 2022-01-04 2021-10-31 2022-01-05 2026-10-30 ant Selection pecialist for Rwanda Energy Implementation Support Access and Quality Improve ment Project RW-REG/EDCL-243446-CS-IN Technical Assistance, Institu DV / Hiring a Senior Procure Individual Consult IDA / 67760 tional Capacity Building and Post Open 119,359.56 2,137.48 Signed 2021-07-18 2021-08-25 2021-09-05 2021-12-02 2021-09-26 2021-12-17 2021-10-31 2021-12-18 2026-10-30 ment Specialist for Rwanda ant Selection Implementation Support Energy Access and Quality I mprovement Project RW-REG/EDCL-243447-CS-IN DV / Hiring a Senior Corporat Technical Assistance, Institu Individual Consult Under Implement e Services specialist for Rwa IDA / 67760 tional Capacity Building and Post Open 119,359.56 0.00 2021-07-18 2021-08-05 2021-09-05 2022-10-04 2021-09-26 2022-10-12 2021-10-31 2026-10-30 ant Selection ation nda Energy Access and Quali Implementation Support ty Improvement Project RW-REG/EDCL-243449-CS-IN Technical Assistance, Institu DV / Hiring a Mechanical Engi Individual Consult IDA / 67760 tional Capacity Building and Post Open 62,369.35 0.00 Canceled 2021-07-18 2021-08-25 2021-09-05 2021-09-26 2021-10-31 2026-10-30 neer for Rwanda Energy Acc ant Selection Implementation Support ess and Quality Improvement Project RW-REG/EDCL-243453-CS-IN Technical Assistance, Institu DV / Hiring a Off grid Speciali Individual Consult IDA / 67760 tional Capacity Building and Post Open 62,369.35 760.47 Signed 2021-07-18 2021-08-26 2021-09-05 2021-08-27 2021-09-26 2022-04-05 2021-10-31 2022-04-06 2022-04-29 st for Rwanda Energy Access ant Selection Implementation Support and Quality Improvement Pro ject RW-REG/EDCL-243455-CS-IN Technical Assistance, Institu DV / Hiring a GIS Specialist f Individual Consult IDA / 67760 tional Capacity Building and Post Open 62,369.35 760.47 Signed 2021-07-18 2021-08-26 2021-09-05 2021-08-27 2021-09-26 2022-03-21 2021-10-31 2022-03-22 2026-10-30 or Rwanda Energy Access an ant Selection Implementation Support d Quality Improvement Proje ct no 1 RW-REG/EDCL-243460-CS-IN Technical Assistance, Institu DV / Hiring a Energy Planning Individual Consult IDA / 67760 tional Capacity Building and Post Open 62,369.35 760.59 Signed 2021-07-18 2021-08-24 2021-09-05 2021-08-27 2021-09-26 2022-03-21 2021-10-31 2022-03-22 2026-10-30 Specialist No 1 for Rwanda E ant Selection Implementation Support nergy Access and Quality Im provement Project RW-REG/EDCL-243463-CS-IN Technical Assistance, Institu DV / Hiring a Planning civil en Individual Consult IDA / 67760 tional Capacity Building and Post Open 62,369.35 760.33 Signed 2021-07-18 2021-08-26 2021-09-05 2021-08-27 2021-09-26 2022-03-21 2021-10-31 2022-03-22 2026-10-30 gineer for Rwanda Energy Ac ant Selection Implementation Support cess and Quality Improveme nt Project RW-REG/EDCL-243464-CS-IN DV / Hiring a Contract Manag Technical Assistance, Institu Individual Consult ement Specialist No 1 for Rw IDA / 67760 tional Capacity Building and Post Open 62,369.35 760.47 Signed 2021-07-18 2021-08-25 2021-09-05 2021-09-16 2021-09-26 2022-03-15 2021-10-31 2022-03-16 2026-10-30 ant Selection anda Energy Access and Qua Implementation Support lity Improvement Project RW-REG/EDCL-243465-CS-IN DV / Hiring a Contract Manag Technical Assistance, Institu Individual Consult Under Implement ement Specialist No 2 for Rw IDA / 67760 tional Capacity Building and Post Open 62,369.35 0.00 2021-07-18 2021-08-25 2021-09-05 2021-09-26 2021-10-31 2026-10-30 ant Selection ation anda Energy Access and Qua Implementation Support lity Improvement Project RW-REG/EDCL-243466-CS-IN Technical Assistance, Institu DV / Hiring a Legal & Transiti Individual Consult IDA / 67760 tional Capacity Building and Post Open 62,369.35 760.47 Signed 2021-07-18 2021-08-24 2021-09-05 2022-04-14 2021-09-26 2022-09-05 2021-10-31 2022-09-06 2026-10-30 on Specialist for Rwanda En ant Selection Implementation Support ergy Access and Quality Impr ovement Project Page 5 RW-REG/EDCL-243468-CS-IN Technical Assistance, Institu DV / Hiring an Environmentali Individual Consult Under Implement IDA / 67760 tional Capacity Building and Post Open 62,369.35 0.00 2021-07-18 2021-08-26 2021-09-05 2022-07-08 2021-09-26 2022-12-01 2021-10-31 2026-10-30 st for Rwanda Energy Access ant Selection ation Implementation Support and Quality Improvement Pro ject RW-REG/EDCL-243471-CS-IN Technical Assistance, Institu DV / Hiring a social safeguard Individual Consult IDA / 67760 tional Capacity Building and Post Open 62,369.35 760.33 Signed 2021-07-18 2021-08-05 2021-09-05 2021-08-27 2021-09-26 2022-03-28 2021-10-31 2022-03-29 2026-10-30 Specialist for Rwanda Energ ant Selection Implementation Support y Access and Quality Improv ement Project RW-REG/EDCL-243490-CS-IN Technical Assistance, Institu DV / Hiring a Procurement Sp Individual Consult IDA / 67760 tional Capacity Building and Post Open 62,369.35 760.72 Signed 2021-07-18 2021-08-25 2021-09-05 2021-10-12 2021-09-26 2022-03-28 2021-10-31 2022-03-26 2026-10-30 ecialist for Rwanda Energy A ant Selection Implementation Support ccess and Quality Improvem ent Project RW-REG/EDCL-243491-CS-IN Technical Assistance, Institu DV / Hiring a HR Specialist fo Individual Consult Under Implement IDA / 67760 tional Capacity Building and Post Open 62,369.35 0.00 2021-07-18 2021-08-24 2021-09-05 2022-11-01 2021-09-26 2022-11-01 2021-10-31 2022-04-29 r Rwanda Energy Access and ant Selection ation Implementation Support Quality Improvement Project RW-REG/EDCL-243492-CS-IN Technical Assistance, Institu DV / Hiring a IT Specialist for Individual Consult IDA / 67760 tional Capacity Building and Post Open 62,369.35 855.09 Signed 2021-07-18 2021-08-24 2021-09-05 2021-08-27 2021-09-26 2022-03-21 2021-10-31 2022-03-22 2026-10-30 Rwanda Energy Access and ant Selection Implementation Support Quality Improvement Project RW-REG/EDCL-243495-CS-IN Technical Assistance, Institu DV / Hiring a Chief Accountan Individual Consult IDA / 67760 tional Capacity Building and Post Open 62,369.35 760.59 Signed 2021-07-18 2021-08-23 2021-09-05 2021-08-27 2021-09-26 2022-02-28 2021-10-31 2022-03-22 2026-10-30 t No 1 for Rwanda Energy Ac ant Selection Implementation Support cess and Quality Improveme nt Project RW-REG/EDCL-246762-CS-IN Technical Assistance, Institu DV / Hiring a Project Enginee Individual Consult IDA / 67760 tional Capacity Building and Post Open 62,369.35 760.33 Signed 2021-08-04 2021-09-16 2021-09-22 2021-09-16 2021-10-13 2022-03-21 2021-11-17 2022-03-22 2026-11-16 r No 3 for Rwanda Energy Ac ant Selection Implementation Support cess and Quality Improveme nt Project RW-REG/EDCL-246760-CS-IN Technical Assistance, Institu DV / Hiring a Project Enginee Individual Consult IDA / 67760 tional Capacity Building and Post Open 62,369.35 760.33 Signed 2021-08-04 2021-09-16 2021-09-22 2021-09-16 2021-10-13 2022-03-14 2021-11-17 2022-03-15 2026-11-16 r No 1 for Rwanda Energy Ac ant Selection Implementation Support cess and Quality Improveme nt Project RW-REG/EDCL-246764-CS-C DS / Consulting company, G. F.AB.I.S for the adaption and Increasing Access to Off-Grid maintenance of the eligibility IDA / 67760 Electricity and Clean Cookin Post Direct Selection Direct 220,000.00 95,390.00 Signed 2021-08-04 2021-11-04 2021-08-09 2021-04-11 2021-09-02 2021-11-27 2021-12-31 tool for REF Window 5 and de g Solutions velopment of eligibility tool a nd clean cooking manageme nt information system (CCMI S) for the clean cooking wind ow RW-REG/EDCL-246761-CS-IN Technical Assistance, Institu DV / Hiring a Project Enginee Individual Consult IDA / 67760 tional Capacity Building and Post Open 62,369.35 760.33 Signed 2021-08-04 2021-09-16 2021-09-22 2021-09-16 2021-10-13 2022-03-14 2021-11-17 2022-03-15 2026-11-16 r No 2 for Rwanda Energy Ac ant Selection Implementation Support cess and Quality Improveme nt Project RW-REG/EDCL-318558-CS-IN Increasing Access to Grid Ele Individual Consult Open - Internationa DV / Hiring Project Implemen IDA / 67760 Post 36,000.00 0.00 Signed 2022-09-30 2022-10-04 2022-11-18 2023-03-10 2022-12-09 2023-03-31 2023-01-13 2023-07-12 ctricity ant Selection l tation Specialist RW-REG/EDCL-330500-CS-C Increasing Access to Grid Ele Under Implement DS / Hiring a contract Manag IDA / 67760 Post Direct Selection Direct - National 36,000.00 0.00 2022-12-11 2022-12-13 2022-12-14 2022-12-30 2023-04-29 ctricity ation er of RESSP as an individual consultant RW-REG/EDCL-330502-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring Logistics and Flee IDA / 67760 Post Open - National 62,369.35 0.00 2022-12-11 2022-12-13 2023-01-10 2023-01-15 2023-02-08 2028-02-07 ctricity ant Selection ation t Management Specialist RW-REG/EDCL-330504-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring a Store Managem IDA / 67760 Post Open - National 62,369.35 0.00 2022-12-11 2022-12-20 2023-01-09 2023-01-24 2023-02-16 2028-02-15 ctricity ant Selection ation ent Specialist, No 1 RW-REG/EDCL-330505-CS-IN Increasing Access to Grid Ele Individual Consult Under Implement DV / Hiring a Store Managem IDA / 67760 Post Open - National 62,369.35 0.00 2022-12-11 2022-12-20 2023-01-06 2023-01-21 2023-02-16 2028-02-15 ctricity ant Selection ation ent Specialist, No 2 RW-REG/EDCL-342082-CS-C DS / Hiring Chief Executive O Increasing Access to Grid Ele IDA / 67760 Post Direct Selection Direct - National 276,095.55 0.00 Signed 2023-02-10 2023-01-16 2023-02-20 2023-01-01 2023-03-01 2023-09-27 fficer of Rwanda Energy Grou ctricity p under EAQIP Program RW-REG/EDCL-342085-CS-C Increasing Access to Grid Ele DS / Hiring a Monitoring & Ev IDA / 67760 Post Direct Selection Direct - National 70,310.16 0.00 Signed 2023-02-14 2023-02-01 2023-02-24 2022-11-01 2023-03-08 2025-02-25 ctricity aluation Specialist under EAQ IP Program RW-REG/EDCL-342099-CS-C Increasing Access to Grid Ele DS / Hiring a Technical Advis IDA / 67760 Post Direct Selection Direct - National 51,159.60 0.00 Signed 2023-02-14 2023-02-01 2023-02-24 2023-02-21 2023-03-08 2024-03-02 ctricity or on Regional Projects under EAQIP Program RW-REG/EDCL-342098-CS-C Increasing Access to Grid Ele DS / Hiring a Legal & Transac IDA / 67760 Post Direct Selection Direct - National 70,310.16 0.00 Signed 2023-02-14 2023-02-01 2023-02-24 2022-11-01 2023-03-08 2025-02-25 ctricity tion Specialist under EAQIP P rogram RW-REG/EDCL-342087-CS-C Increasing Access to Grid Ele DS / Hiring a Donor & Extern IDA / 67760 Post Direct Selection Direct - National 70,310.16 0.00 Signed 2023-02-14 2023-02-01 2023-02-24 2022-11-01 2023-03-08 2025-02-25 ctricity al link coordinator under EAQ IP Program RW-REG/EDCL-342097-CS-C Increasing Access to Grid Ele DS / Hiring a ESWAP Coordin IDA / 67760 Post Direct Selection Direct - National 81,376.32 0.00 Signed 2023-02-14 2023-02-01 2023-02-24 2022-11-01 2023-03-08 2025-02-25 ctricity ator under EAQIP Program RW-REG/EDCL-342101-CS-C Increasing Access to Grid Ele DS / Hiring a Energy Policy A IDA / 67760 Post Direct Selection Direct - National 70,310.16 0.00 Signed 2023-02-14 2023-02-01 2023-02-24 2023-02-21 2023-03-08 2025-02-25 ctricity nalyst under EAQIP Program RW-REG/EDCL-369362-CS-C Increasing Access to Off-Grid Pending Impleme DS / Individual Temporary st IDA / 67760 Electricity and Clean Cookin Post Direct Selection Direct - National 5,436.21 0.00 2023-06-30 2023-07-10 2023-09-13 2024-10-07 ntation aff for component 3a and 3b g Solutions RW-REG/EDCL-369363-CS-C Increasing Access to Off-Grid Pending Impleme DS / Individual Temporary st IDA / 67760 Electricity and Clean Cookin Post Direct Selection Direct - National 5,436.21 0.00 2023-06-30 2023-07-10 2023-09-13 2024-10-07 ntation aff for component 3a and 3b g Solutions No 2 Page 6 RW-REG/EDCL-369364-CS-C Increasing Access to Off-Grid Pending Impleme DS / Individual Temporary st IDA / 67760 Electricity and Clean Cookin Post Direct Selection Direct - National 5,436.21 0.00 2023-06-30 2023-07-10 2023-09-13 2024-10-07 ntation aff for component 3a and 3b g Solutions No 3 RW-REG/EDCL-369365-CS-C Increasing Access to Off-Grid Pending Impleme DS / Individual Temporary st IDA / 67760 Electricity and Clean Cookin Post Direct Selection Direct - National 5,436.21 0.00 2023-06-30 2023-07-10 2023-09-13 2024-10-07 ntation aff for component 3a and 3b g Solutions No4 Page 7 REPUBLIQUE D’HAITI Direction Nationale de l’Eau Potable et de l’Assainissement (DINEPA) PROJET/PROGRAMME: Projet/Programme Décentralisé Eau et Assainissement Rural Durable et Résilient PLAN DE DEVELOPPEMENT STRATEGIQUE DE PASSATION DES MARCHES (PPSD) 1. Présentation sommaire du Projet/Programme (Aperçu du projet) Pays : REPUBLIQUE D’HAITI Projet/Programme Décentralisé Nom complet du Eau Potable et Assainissement Projet/Programme: Rural Durable et Résilient Montant total du SDR 46.2 MILLIONS financement (Dollars US) : (US $ 80 MILLIONS EQUIVALENTS) Numéro identifiant du P178188 Projet/Programme: Accroître l'accès à des services Résumé des Objectifs de ruraux d'eau potable et développement du d'assainissement de base inclusifs, Projet/Programme résilients et durables. La Banque a l’intention d’allouer une enveloppe de 80 millions de dollars américains à l'Etat Haïtien via la DINEPA pour réaliser les activités identifiées dans le cadre du Projet/Programme Décentralisé Eau et Assainissement Rural Durable et Résilient. Ce Projet/Programme a pour objectif d’accroître l'accès à des services ruraux d'eau potable et d'assainissement de base inclusifs, résilients et durables. Dans ce contexte, les expériences acquises par la DINEPA dans la gestion des projets IDA constituent une base importante de référence pour la formulation des analyses et options contenues dans le présent document. Le Projet/Programme se décline en trois composantes : (i) Composante 1 : Réponse « Eau, assainissement et hygiène » au choléra et préparation aux situations d'urgence (8 millions de dollars) (ii) Composante 2 : Développement des services « Eau, assainissement et hygiène » (60 millions de dollars US) 1 (iii) Composante 3 : Renforcement sectoriel axé sur les résultats (12 millions de dollars) (iv) Composante 4 : Réponse d'urgence contingente (0 million de dollars) Composante 1 : Réponse « Eau, assainissement et hygiène » au choléra et préparation aux situations d'urgence (8 millions de dollars) . Cette composante soutiendra (a) des mesures de réponse immédiate au choléra, (b) le renforcement de l'assainissement et de l'hygiène dans 10 communes prioritaires du pays touchées par le choléra, (c) le renforcement des capacités du secteur WASH pour la réponse d'urgence. Les interventions à mener dans le cadre de cette composante s'appuieront sur la réponse initiale au choléra donnée dans le cadre du Projet/Programme de renforcement des soins de santé primaires et de la surveillance en Haïti (PROSYS) (P175949) financé par la Banque mondiale. Cette composante financera : (a) une campagne de communication ciblée sur l'eau potable et la promotion de l'assainissement et des comportements hygiéniques ; (b) l'achat de biens et de fournitures d'urgence, y compris la livraison de comprimés de chloration, de carburant et d’unités autonomes de traitement d’eau , la construction de réservoirs d'eau et l’installation d’hypochlorateurs ; (c) la mise en œuvre de la stratégie nationale de chloration, y compris l’achat des intrants pour les tests de qualité de l'eau ,les formations ,le suivi du sisklor et la chloration au niveau local ; (d) une campagne dans les 10 communes prioritaires touchées par le choléra pour promouvoir le lavage des mains et mettre fin à la défécation à l'air libre grâce à une approche communautaire d'assainissement total sensible au genre (appelée Approche Communautaire pour l'Assainissement Total en Haïti), le marketing de l'assainissement, la promotion de l'hygiène, et la communication pour le changement de comportement qui ont donné de bons résultats (80 % des ménages sensibilisés en Haïti ont été évalués sur la disponibilité des latrines familiales selon l'UNICEF) ; et e) un Projet/Programme pilote dans un centre urbain pour préparer et mettre en œuvre un plan complet de gestion des boues de vidange (FSM) comprenant des dispositions institutionnelles, réglementaires, commerciales et financières appropriées pour la collecte, le transport et le traitement afin d'assurer une chaîne de services FSM sûre et durable;(e)la mise en place d'un plan de contingence visant à prévenir, à prévoir et à réagir en cas de crise et de désastre. En outre, cette composante financera des activités visant à renforcer la capacité du service des urgences de la DINEPA à répondre aux urgences, y compris le choléra, ainsi qu'aux événements et catastrophes extrêmes climatiques et non climatiques, en élaborant (a) un plan d'intervention 2 d'urgence du secteur WASH, (b) des outils d'évaluation de la vulnérabilité des systèmes d'approvisionnement en eau et d'assainissement, et (c) des outils de communication sur les conseils en matière d'eau. Composante 2 : Développement des services WASH (60 millions de dollars US) Sous-composante 2.1 : Infrastructure d'approvisionnement en eau prioritaire (50 millions de dollars) Cette sous-composante soutiendra le développement de services d’eau potable dans une trentaine de communes à travers la construction/réhabilitation/extension de SAEP pré-identifiés pour lesquels les activités de mobilisation communautaire ont déjà eu lieu de manière satisfaisante et des études techniques ainsi que environnementales et sociales (E&S) sont disponibles, permettant une mise en œuvre rapide de ces sous- projets. Fait partie également de cette liste de SAEP celui de Lascahobas dont les travaux sont à terminer. Cette sous-composante financera le diagnostic des SAEP, la préparation des dossiers techniques et études d’impact environnementale et sociale; le montage des Dossier d’Appels d’Offres (DAO); la supervision des travaux; l’accompagnement en sauvegarde environnementale et sociale; la formation des communautés et gestionnaires de services (OP, CAEPA, URD, TEPAC, etc) pour assurer la participation active des parties prenantes et des bénéficiaires afin de faciliter la mise en œuvre du sous-projet et de soutenir la durabilité; l’ accompagnement en passation des marchés, la fourniture de biens et matériaux destinés aux travaux de construction et son transport et entreposage (magasins régionaux), le transfert de compétences en direction des institutions du secteur et la construction, la réhabilitation et l'extension des SAEP. Sous-composante 2.2 : Développement Local des Services EAH à grande échelle (10 millions de dollars) Cette sous-composante soutiendra le développement de services EAH dans une quinzaine de communes dans la région couverte par l’OREPA Sud à travers l'octroi de subventions aux porteurs de sous-projets visant (a) à rétablir et/ou améliorer le niveau de service des systèmes d'approvisionnement en eau existants, (b) améliorer les services publics d'assainissement, (c) protéger les ressources en eau, et (d) améliorer la sécurité hydrique et alimentaire des communautés. Composante 3 : Renforcement sectoriel axé sur les résultats (12 millions de dollars) Cette composante vise à soutenir la gestion de projet et à renforcer les institutions du secteur pour consolider l'approche programmatique sectorielle axée sur les résultats 3 afin d'améliorer la planification, la budgétisation, l'établissement de rapports, le suivi et l'évaluation, la responsabilité, la réglementation et la durabilité afin d'accélérer l’accès universel aux services EPAH. Sous-composante 3.1 : Gestion du projet (5 millions d'USD) Cette sous-composante financera les dépenses associées de l’Unité de Gestion du Projet (UGP) pour la gestion, la supervision des activités du projet et les audits. Cette sous-composante financera également les coûts de l'agent de vérification indépendant (AVI) qui évaluera la conformité avec les Conditions Basées sur les Performances (CBP) respectives sous la sous-composante 3.3 (y compris la vérification de l'éligibilité des dépenses et le calcul des décaissements). Cette sous-composante financera aussi les dépenses liées à la réinstallation involontaire jusqu'à 100 000 dollars US. Sous-composante 3.2 : Développement des capacités institutionnelles (4 millions de dollars) Cette sous-composante financera l'assistance technique et le renforcement des capacités pour (a) l'opérationnalisation du programme budgétaire axé sur les résultats de la DINEPA, (b) la mise à niveau du SIEPA, (c) la préparation et la mise en œuvre d'une Stratégie d'inclusion et plan d'action, (d) l'élaboration de procédures standard pour la régulation du secteur, (e) des études visant à améliorer la connaissance sur les ressources en eau (f) un programme de formation nationale des opérateurs de l'eau (CAEPA et OP) pour assurer une prestation de services résiliente et durable et (g) des activités d'échange de connaissances. Sous-composante 3.3 : Appui à la structure de la DINEPA pour la durabilité (3 millions de dollars) Cette sous-composante soutiendra l'amélioration de la performance institutionnelle de la DINEPA en fournissant des paiements incitatifs pour les principaux éléments constitutifs des services durables. Composante 4 : Réponse d'urgence contingente (0 million de dollars) En raison de la grande vulnérabilité d'Haïti aux catastrophes naturelles et aux chocs, y compris ceux exacerbés par le changement climatique, un CERC est inclus dans le projet. Cette composante provisoire est conçue comme un mécanisme de réponse rapide en cas d'urgence éligible. Cette composante serait activée à la demande du GoH, conformément aux dispositions du POM. Il reflétera également les enseignements tirés de l'expérience opérationnelle acquise en Haïti dans la réponse aux événements et chocs catastrophiques naturels, y compris les urgences sanitaires. Cette composante ne bénéficierait d'aucune allocation de financement initiale, mais en cas d'urgence éligible, les fonds non engagés pourraient être réaffectés à partir d'autres composantes conformément à un plan d'action d'urgence préparé par le gouvernement haïtien et au manuel d'intervention d'urgence contingente. Le montant des fonds non engagés à allouer à cette composante sera décidé au moment de l'urgence en accord avec la Banque Mondiale. 4 2. Présentation sommaire du pays, de l’emprunteur ( du bénéficiaire) et du marché 2.1 Contexte opérationnel • Aspects sur la gouvernance Le Projet/Programme sera mis en œuvre par la DINEPA — responsable de l’exécution de la politique de l’état dans le secteur de l’eau potable et de l’assainissement par le développement du secteur au Niveau National, sa régulation et contrôle des acteurs y intervenant en Haïti. La DINEPA sera l'agence d'exécution responsable de la mise en œuvre globale du Projet/Programme comme elle l'a fait pour tous les projets passés de la Banque mondiale dans le secteur. Pour cette nouvelle opération, une équipe de Projet/Programme spécifique sera mise en place au sein de la DINEPA, chargée de l'exécution du projet. L‘équipe de Projet/Programme sera dotée d'un personnel suffisant au niveau régional et d'un financement adéquat tout au long de la mise en œuvre du projet. La DINEPA, de concert avec la coordination du Projet/Programme sera responsable de la planification, de l'examen technique, de l'approvisionnement, de l'administration des contrats, de la FM, de la gestion des risques E&S, du contrôle et de l'assurance qualité et du S&E. Les directions de la DINEPA sont impliquées dans la mise en œuvre du Projet/Programme ,celles-ci coordonneront le suivi des activités du Projet/Programme qui les concernent par l’intermédiaire de points focaux faisant partie de la l’équipe de projet. . .Chacune de ces directions pourra soit désigner un point focal pour le Projet/Programme , au sein de son équipe soit être directement impliquée, pour suivre les activités du Projet/Programme liées à son domaine de compétence et pour le suivi de la coordination technique avec l’Equipe de Projet/Programme . Au sein de la DINEPA, l’équipe de projet composée de profils divers et variés avec des représentants au niveau régional assurera la collaboration entre les directions centrale et régionale pour les interventions du Projet/Programme. Cette équipe jouera un rôle clé dans la mise en œuvre du Projet/Programme. Cette équipe déterminera conjointement avec la Direction Générale de la DINEPA la stratégie et le plan d’action annuel pour les interventions du Projet/Programme. Les termes de référence de chaque membre de l’équipe décriront en détail leurs responsabilités. 5 • Aspects technologiques Le Projet/Programme utilisera : (i) L'application de solution de passation de marchés en ligne (Solucao Online de Licitacao SOL) sera implémentée ,si possible , pour aider les communes et les communautés à effectuer la passation de marchés des sous-projets afin de garantir la transparence et la sécurité et de simplifier la création et l'exécution des processus d' Appels d’offres par les communautés bénéficiaires. SOL applique un logiciel open source et une chaîne de blocs pour garantir l'intégrité, la transparence et l'audit et (ii) L'Initiative géo-habilitante pour le suivi et la supervision (GEMS) pour la collecte et l'analyse de données en temps réel. La méthode GEMS a été développée par le groupe FCV du GBM et permet aux équipes de Projet/Programme d'utiliser des outils de technologie de l'information et de la communication (TIC) open source pour la collecte de données numériques structurées sur le terrain qui alimentent automatiquement un système centralisé de suivi et d'évaluation (S&E). et le système d'information de gestion (SIG). Ces aspects seront adressés au début de la mise en œuvre du Projet/Programme, et la DINEPA recevra le support et l’assistance appropriés pour l’utilisation de ces technologies durant le déroulement du Projet/Programme. • Aspects de développement durable et aspects sociaux Le principe central de la conception de ce Projet/Programme est de travailler à l'amélioration de la fiabilité, de la résilience et de la durabilité de la prestation de services à grande échelle. Bien que les systèmes physiques soient une exigence évidente, ce n'est qu'une partie d'un ensemble d'actions beaucoup plus complexe pour fournir un service véritablement durable. La conception est éclairée par l'approche de prestation de services (SDA) qui est enracinée dans la nécessité de déplacer l'attention des moyens de prestation de services (l'infrastructure) vers le service réel auquel les consommateurs ont accès. En conséquence, le Projet/Programme adoptera une nouvelle approche pour aider les communes et les communautés à entreprendre des réformes et à mettre en œuvre des investissements à petite échelle sur leurs systèmes d'approvisionnement en eau et d'assainissement existants tout en appuyant les fonctions de régulation et de facilitation par la DINEPA pour assurer une gestion résiliente et durable de ces systèmes. L’approche du Projet/Programme adresse aussi les inégalités systémiques auxquelles sont confrontées les femmes et les personnes handicapées par le biais d'interventions qui : 6 a) comblent l'écart entre les sexes en matière de représentation, en prévoyant un quota d'au moins 30% de femmes membres et présidentes des organisations communautaires d'eau et d'assainissement et des répondants à l'enquête de satisfaction des bénéficiaires ; b) répondent à leurs besoins en matière de conception d'infrastructures (sécurité, accessibilité et qualité) et c) sensibilisent contre la VBG ( Violence Basée sur le Genre) ,tour en partageant des stratégies de prévention et de signalement et des actions de recours en tirant partie des espaces communautaires et des activités de mobilisation. Le Projet/Programme introduira la conception d'infrastructures WASH tenant compte du handicap en Haïti, sur la base du Guide pratique mondial de l'eau sur la conception d'infrastructures pour des personnes handicapées. L’approche du Projet/Programme vise à remédier aux principales vulnérabilités dues au changement climatique telles que les sécheresses, les inondations et les cyclones exacerbés par le climat en améliorant la résilience du secteur EPA( Eau Potable et Assainissement ). Pour remédier aux vulnérabilités climatiques, les activités du Projet/Programme comprennent la conservation des sources d'eau, la conception d'infrastructures résilientes, des services exploités efficacement, la maintenance préventive, la gestion des actifs et une stratégie efficace de gestion de la demande basée sur des politiques d'économie d'eau et de tarification de l'eau pour maintenir une eau résiliente au changement climatique. Les améliorations attendues dans les opérations techniques et commerciales des systèmes d’Alimentation en Eau Potable et en Assainissement contribueront à réduire la consommation d'eau et d'énergie non génératrice de revenus. Dans l'ensemble, le Projet/Programme contribuera à réduire à la fois les risques et les impacts des interruptions de service liées aux sécheresses, aux inondations et aux cyclones exacerbés par le climat. Les activités contribueront également à réduire les risques croissants pour la santé publique liés à l'absence de systèmes d’Alimentation en Eau Potable et en Assainissement, qui sont encore exacerbés par les catastrophes induites par le changement climatique. La priorisation des communes participantes inclura des critères de vulnérabilité aux risques climatiques pour supporter l'adaptation dans les localités les plus vulnérables aux impacts du changement climatique. Enfin, le Projet/Programme appuiera l'élaboration de plans d'urgence du secteur WASH dans toutes les communes participantes. Pour faciliter l’atteinte des résultats ciblés par ces aspects du Projet/Programme, la DINEPA par le biais de l’Equipe de Projet ,sera renforcée par des Consultants ayant des expériences avérées dans les domaines susmentionnés .. • Aspects économiques Les aspects de gestion financière du Projet/Programme seront pris en charge par l’Equipe de Projet en collaboration avec la DINEPA. Il a été constaté, lors de l’exécution du Projet/Programme précédent, que les firmes locales, d’une manière générale, rencontrent des difficultés dans le cadre de l’exécution des contrats dont elles sont attributaires. Ces difficultés sont notamment liées : (i) au problème de trésorerie ; (ii) aux difficultés à soumettre des garanties d’avance et de bonne exécution ; 7 (iii) à l’instabilité de la monnaie locale. Les contrats sont signés en gourdes,alors que la plupart des biens sont importés ; (iv) à l’inflation etc… Les éléments mentionnés ci-dessus ont une très grande influence sur l’exécution des activités. Certaines firmes locales ne disposent pas d’une bonne trésorerie pour exécuter des contrats sans avance de démarrage ou avec une avance contre caution bancaire, surtout lorsqu’il s’agit de contrats de plusieurs milliers de dollars. Les prix varient rapidement sur le marché , donc il est assez difficile qu’un fournisseur garde un prix pour 90 jours (période normale de validité des offres). Des dépréciations effrénées de la gourde par rapport au dollar ont été constatées et dans un espace de temps très court , plusieurs réclamations de révision de prix ont été acheminées au Projet/Programme précédent dans les mois passés. Ces réclamations ont été gérées tant bien que mal, mais ces difficultés risquent de resurgir lors de l’exécution de ce nouveau Projet/Programme. Sinon, il serait raisonnable de libeller le contrat dans la monnaie du don pour remédier aux problèmes de fluctuation de prix et de spéculation. Toujours dans l’aspect économique, en fonction de la période de validité exigée dans les documents de consultation, beaucoup de fournisseurs manifestent un désintérêt total pour les marchés. Et fort malheureusement, ce sont de grandes entreprises avec une assez bonne santé financière. Lors de l’exécution du Projet/Programme précédent, pour les marchés de biens, un manque d’intérêt des firmes a été constaté. Certaines fois, il a été extrêmement difficile de collecter des pro forma , ce qui a retardé l’exécution de certaines activités. Au moment de l’ouverture des plis, fort souvent une seule offre est reçue. Cette situation fausse la concurrence; et même lorsque les fournisseurs acceptent de soumissionner, le grand problème de respect du délai de livraison reste et demeure entier. • Aspects socio-politiques L'instabilité politique chronique d'Haïti et la situation sécuritaire instable peuvent créer des goulots d'étranglement et des retards dans la mise en œuvre du projet. Bien qu'il soit difficile d'atténuer ce risque, le Projet/Programme adopte en conséquence une stratégie de « atténuation des risques dès la conception » basée sur une évaluation continue des risques de sécurité pour mieux adapter la portée des activités du Projet/Programme et la supervision de la Banque Mondiale. Les risques de sécurité sont pris en compte dans tous les éléments de la conception, de la supervision et de la mise en œuvre du projet. Comme facteur de risque politique, nous pouvons citer le changement de Gouvernement, l’instabilité politique, les longues procédures d’importation et dans certaines circonstances, de mauvaises pratiques de passation des marchés. Quoique ces facteurs puissent être gérés par l’équipe en place, cette dernière ne peut les ignorer. 8 Le personnel impliqué dans l’exécution du projet, ne devra afficher aucune position politique quelle qu’elle soit, il y va d’une approche purement technique et managériale pour mener à bien les différentes activités. C’est dans cette perspective que pour cette nouvelle opération, une équipe en charge de l’exécution des activités spécifiques au Projet/Programme sera mise en place au sein de la DINEPA avec un personnel entièrement dédié. Le personnel sera affecté au Projet/Programme en fonction de sa qualification et de son expérience. Le problème de l'insécurité et la situation politique couplés à la montée du choléra rendront difficile l'attraction d'entrepreneurs et de consultants qualifiés. De plus, le personnel de ce nouveau Projet/Programme devra avoir de l’expérience dans la gestion des contrats, car il devrait saisir des informations importantes sur les contrats, gérer correctement les risques liés aux contrats, surveiller l'avancement des contrats et des travaux , gérer les variations et les modifications des contrats, bref en faire le suivi dans leurs aspects légaux et administratifs . Les cadres de la DINEPA et des OREPA assisteront de manière soutenue le personnel dédié pour l’atteinte des indicateurs du Projet/Programme. La situation sécuritaire également risque de provoquer de très longs retards dans l’exécution des activités. Certaines fois, l’accès à plusieurs départements où le Projet/Programme précédent réalisait des activités , était complètement paralysé et ce pour plusieurs jours. Face à pareille situation, l’équipe de Projet du nouveau Projet/Programme devra prendre des mesures appropriées lorsqu’elle anticipe le risque d’avoir un ou plusieurs « pays lock » au cours d’une année. Parmi ces mesures d’adaptation, la proactivité est déterminante. Il faut profiter au maximum de chaque période de calme pour réaliser un maximum d’activités. Une bonne planification des processus de passation de marchés qui ont des délais incompressibles est à envisager. Dans ce contexte il est recommandé de lancer en priorité les marchés les plus critiques ou plus lourds avec des délais de passation très longs ; ii) Grouper certains contrats. Il convient en outre i) d’alléger les procédures administratives ; ii) de prévoir des procédures d’urgence internes et également ; iii) d’adapter les contrats pour prendre en compte les cas de force majeure et iv) recourir aux agences des NU. v) Augmenter la pression sur la firme de supervision qui devra tenir rigueur dans l'évaluation et l'exécution des projets. Toujours, en ce qui a trait aux aspects politiques, se pose le problème d’importation en Haïti (douane) surtout pour les acquisitions de matériels. Un nombre assez important de biens seront achetés et seront forcément importés. Avec les grèves et autres blocages , de grands retards de livraison peuvent être constatés et des pénalités 9 injustement prélevées. En ce sens, une franche communication doit exister entre le Client et les Fournisseurs pour éviter des pénalités qui en réalité ne sont nullement imputables aux Fournisseurs. Le Client également doit avoir un maximum d’information sur les vraies causes et prolonger le délai de livraison lorsque c’est justifié. Cependant, le recours aux agences des nations unies pourrait atténuer ce risque. Du point de vue sociologique, nous ne pouvons pas passer outre la crise sanitaire du CHOLERA où Haïti est actuellement en situation d’alerte. Cette situation inédite risque d’impacter lourdement les activités de terrain et d’obliger la DINEPA à adapter les réponses au besoin . Certaines réponses qui peuvent sembler évidentes sont parfois difficiles à implémenter dans un contexte assez difficile. La meilleure décision serait de faire un usage optimal des nouvelles technologies et d’opter dans la mesure du possible pour la tenue ou la réalisation à distance de certaines activités. Conclusions clés : D’une manière générale, on peut conclure que plusieurs facteurs peuvent impacter la mise en œuvre du Projet/Programme et de grands défis sont à relever ,par conséquent des dispositions devront être prises pour les prévenir et les mitiger. Les dispositions, listées plus haut, seront mises en œuvre dès l’effectivité du Projet/Programme. 2.2Organisation et fonctionnement de l’ Equipe du Projet/Programme Le Projet/Programme sera mis en œuvre par la DINEPA, au sein de laquelle des consultants additionnels seront recrutés pour mener à bien les activités spécifiques y relatives . Afin de renforcer l’Equipe de Projet/Programme dans la prise en charge de ces nouvelles activités, les consultants suivants seront recrutés par la DINEPA : • Le Coordonnateur de projet ; ; • Les Coordonnateurs Régionaux chargés de la coordination régionale des activités du projet EPARRD ; • Le Spécialiste de la gestion financière /Comptable ; • Le Spécialiste de la Sauvegarde environnementale et sociale ; • Le Spécialiste technique ; • Le Spécialiste en Suivi et Evaluation ; • Les Spécialistes en passation de marchés. • Le personnel d’appui au niveau régional NB : Des Termes de Référence (TDR) définiront les rôles et les responsabilités respectifs des personnes physiques composant cette équipe. La DINEPA pourra en fonction du déroulement des activités et pour renforcer l’équipe , recruter des Consultants pour des prestations spécifiques et en fonction des capacités de gestion du projet. 10 2.2.1 Les organes de passation des marchés La DINEPA à travers l’équipe de Coordination assure la gestion efficiente et efficace de la Passation et de l’Exécution des Marchés avec des prestataires publics et privés. Des Assistances Techniques par Résultats pourraient être prévues avec des organisations à but non lucratif ou des Agences des Nations-Unies1 pour l’acquisition de biens et de Services Spécifiques, 2.2.2 Composition de l’équipe et dispositions relatives à la Passation des Marchés et au Plan de Passation des Marchés : LA DINEPA dispose d'une Direction de Passation et d’Exécution de Marchés publics (DPEM) dont un cadre de la dite Direction est directement rattaché à la Coordination du Projet. L'équipe de Passation de Marchés actuelle de la DINEPA qui travaille sur le projet de la Banque est composée : de deux (2) Spécialistes dont un (1) coordonne les activités de la cellule, et d’un Technicien en Passation des Marchés dont le MOP viendra confirmer la composition définitive. L’équipe existante a une bonne expérience en passation des marchés financés par les Bailleurs de Fonds notamment, la Banque Mondiale. Certains membres de cette équipe ont conduit dans le passé des marchés (toutes catégories confondues) pour les différents Projets EPARD antérieurs. Les marchés du Projet/Programme sont diversifiés et sont en grande partie des consultations individuelles, des prestations intellectuelles, des travaux, des acquisitions de biens, des assistances techniques à la construction et des contractualisations avec des organisations à but non lucratif et si possible avec des agences des Nations Unies2. Le Bailleur de Fonds qui depuis plusieurs années a une expérience avec les institutions des Nations Unies pourra formuler des recommandations à la DINEPA .. 1Lesagences des Nations Unies dont la capacité de mise en oeuvre ou de collaboration avec le Secteur EPA est avérée. 2Lesagencies des Nations Unies dont la capacité de mise en oeuvre ou de collaboration avec le Secteur EPA est avérée. 11 En résumé, la passation de ces marchés représente un grand défi pour l’équipe en place, à cause de ces montants et des difficultés liées à la gestion de contrat particulièrement l’obtention des garanties par les firmes. Cependant, des dispositions devront être prises par la DINEPA pour respecter les délais et ainsi signer les contrats à temps. Sachant que cette même équipe sera parallèlement sur d’autres projets, il serait conseillé de renforcer l’équipe du Département de Suivi et Exécution des Contrats (DSEC) et de faire une meilleure distribution des tâches. Eventuellement, un SPM supplémentaire et deux gestionnaires de contrat seront recrutés avec l’accord du Bailleur. 2.2.3 Capacité et aptitude pour la gestion des contrats En se basant sur les leçons apprises du précédent Projet/Programme, des lacunes pour une bonne gestion des contrats devront être comblées. Donc, il serait recommandé non seulement une plateforme électronique gérée par la DINEPA et l’Equipe de Projet, mais : a) De recruter deux spécialistes en gestion des contrats. b) De travailler sur une planification anticipée des marchés avec les spécialistes techniques et assistants techniques du Projet. Le délai de traitement d’un marché ne devrait pas être compressé en raison d’un manque de planification. Les avenants sont rédigés pour un but précis mais ne devraient pas être un moyen de corriger une mauvaise gestion contractuelle. c) que les besoins soient mieux définis pour les marchés. d) que les paiements soient déclenchés dans les jours qui suivent la réception de la facture, grâce à une collaboration renforcée avec la gestion financière du Projet. e) Qu’un bon suivi soit assuré pour tous les contrats par une équipe multidisciplinaire de la DINEPA et qu’un reporting régulier soit exigé notamment des OREPA,communes , des prestataires de service , et des Organisations à but non lucratif engagés dans le projet. Une bonne gestion contractuelle repose obligatoirement sur un personnel adéquat et une bonne planification, sur des besoins bien définis et clairs et un suivi contractuel régulier. Les cadres de la DINEPA et des OREPA mettront leurs compétences à la disposition de l’Equipe de Projet pour une mise en œuvre satisfaisante des activités du Projet/Programme. 12 2.2.4 Systèmes de gestion des plaintes et de résolutions de conflits Les plaintes reçues par la DINEPA en ce qui concerne la PM sont gérées suivant les politiques et procédures de la Banque ,car c’est la DINEPA qui porte le Projet/Programme Conclusions clés : La DINEPA a une bonne expérience en passation des marchés et a globalement les capacités requises pour assurer la gestion des marchés liés à ce Projet, avec le soutien de l’équipe de la Banque pour les marchés en revue A priori. Les conditions pour l’attribution de marchés en revue a posteriori doivent être discutées au préalable avec le Bailleur de Fonds et dépendront des niveaux de risques des marchés. 2.4 Analyse du marché Les marchés qui seront passés pour ce Projet/Programme sont en nombre limité et de tous types ( biens, services et travaux) . Il s’agit de consultations individuelles, de l’achat de matériels et accessoires, de prestations de services et des contrats d’assistance technique par résultats avec des Organisations à but non lucratif , si possible des agences des Nations-Unies qui auront obligatoirement passé des Contrats de Sous-traitance avec des Firmes locales pour le transfert de connaissance. Pour les marchés de consultants, il s’agit principalement de réalisation et d’actualisation d’études, de supervision et de maitrise d’œuvre ,… Dans le cadre de la mise en œuvre de cette stratégie de passation de marchés de ce nouveau Projet/Programme, il sera primordial de s’appuyer sur : a) L’expérience des organisations à but non lucratif et des agences des Nations Unies déjà mobilisées sur le terrain et qui ont déjà travaillé avec la DINEPA dans des domaines bien précis et assez complexe.). b) Les consultants nationaux, les firmes locales et des spécialistes à expériences internationales compétents du Secteurs pour la réalisation de plusieurs études et consultations notamment les campagnes de sensibilisation, le renforcement des capacités et l’accompagnement des communes ... c) Les fournisseurs locaux pour les acquisitions de biens (achat de véhicules) d) Les cabinets conseils et des organisations spécialisés en formation pour ce qui concerne la formation des collectivités. Ces firmes devront avoir une grande 13 capacité de déploiement logistique. Ce type de marché est assez particulier et demande une bonne connaissance des régions et une excellente équipe logistique. Il est fortement recommandé que ces firmes aient une assez bonne santé financière pour éviter des coupures lors de ces formations pour manque de fonds. En termes de pourcentage, nous retrouvons la répartition suivante pour les différents types de marchés (a inclure et à travailler ensemble ) : a) Biens pour 23 %3 b) Travaux 34 % c) Services non consultatifs pour 21 % d) Services de Consultant/ Bureaux Conseils pour 11% e) Prestations intellectuelles/Consultants individuels pour environ 5 % Tableau 1 : Description des contrats et du niveau de risque associé Budget Coûts % Montan % cumulé Risqu estimat du t par # Description es (1 if (US$, budget cumulé rapport au a 5) millions total du (Million budget du ) projet USD) projet Acquisition de biens et 1 accessoires pour la 2 64 8% 8% 6.00 construction des réseaux (UNOPS) Travaux de construction de 25 2 3.2 15 19% 26% réseaux en trois 21.00 lots Travaux de construction et de 3 3.2 9 11% 38% réhabilitation des 30.00 réseaux de Anse 3 Le pourcentage de biens a acheté dans le cadre du projet est de 23 % puisque le montant total des matériels et accessoires pour les travaux est estimé à environ 17 M USD. Cependant, ce ne sera pas un seul contrat. Pour les 18 premier mois un contrat de 6 millions sera signé et les autres contrats viendront après au fur et à mesure que les études sont disponibles. Ce contrat pourrait être signé avec le même fournisseur dépendamment de sa performance. 4 Voir footnote #6 14 Rouge Mole Saint Nicolas et Jean Rabel Assistance technique basée 4 2.8 10 13% 50% sur les résultats 40.00 pour la gestion des fonds à transférer pour les porteurs de projets communautaires Assistance technique pour la réalisation des études, la 5 2.5 5.8 7% 57% préparation des 45.80 DAO et la supervision des travaux (UNOPS) Assistance technique base sur les résultats pour appuyer la DINEPA dans la fourniture 6 d’une réponse 2 5 6% 64% 50.80 d’urgence au cholera et promouvoir l’hygiène sanitaire de base (UNICEF) Assistance Technique pour le 7 renforcement des 2.5 2.45 3% 67% 53.25 capacités de la DINEPA Acquisition de 8 matériels 2 0.2 0% 67% 53.45 informatiques Acquisition de 9 mobiliers de 2 0.15 0% 67% 53.60 bureau Sensibilisation, mobilisation sociale et renforcement des 10 capacités 2.4 2 3% 66% 52.80 techniques et commerciales des opérateurs et des acteurs locaux de 15 la DINEPA sur trois ans (UNOPS) Travaux de construction et équipement de 11 2 1.5 2% 68% trois entrepôts 54.30 avec supervision par les OREPAs Finalisation des travaux 12 1.5 1.4 2% 70% électromécanique 55.70 s Acquisition de 20 13 véhicules en 1 1 1% 71% 56.70 plusieurs lots Finalisation des travaux 14 1.5 0.6 1% 72% hydraulique de 57.30 Lascahobas Supervision des 15 travaux de 0.9 0.2 0% 72% 57.50 Lascahobas Etude pour l’amélioration des 16 connaissances sur 1.2 0.2 0% 72% 57.70 l’hydrogéologie d’Haïti Assistance technique pour le 17 1 0.1 0% 72% développement de 57.80 la régulation 2.5 Dynamiques du marché Acquisition de biens : Environ 23% du montant du projet sera alloué à l’acquisition de biens. En effet, il est prévu d’avoir un contrat important pour l’acquisition des biens et accessoires 16 (Tuyauterie, compteurs d’eau etc…) qui seront utilisés dans le cadre des travaux à exécuter par le projet. Cette stratégie qui consiste à acheter tous les matériaux nécessaires pour les travaux dans le cadre d’un marché groupé est justifié par les raisons suivantes : 1. L’expérience dans d’autres projets du secteur montre que les firmes construction rencontrent de grandes difficultés à commander les matériaux, surtout, ceux qui ne sont pas disponibles sur le marché local à cause des problèmes de capacité financière qui leur empêche de passer les grosses commandes nécessaires à la réalisation des travaux ; 2. Le dédouanement des matériaux importés par les firmes sont très compliqués et prends parfois beaucoup de temps pour être effectif. 3. L’achat groupé des matériaux permettra de faire des économies d’échelle et par conséquent présente un avantage financier important pour le projet ; Les points 1 et 2 mentionnés ci-dessus représentent un goulot important dans l’exécution des travaux et à contribuer à retarder l’exécution de plusieurs contrats dans le cadre du projet précèdent. Le projet compte utilisé les services de l’UNOPS pour passer cette commande. Vu les conditions politiques et sécuritaire du pays, il serait très difficile de pouvoir attirer un ou des fournisseurs internationaux capable de fournir ce volume de biens et d’assurer la transportation dans les régions ou les travaux seront exécuté. L’UNOPS présente un avantage comparatif important pour l’acquisition de ces biens vu leur connaissance du marché international, leur capacité à assurer le dédouanement des biens dans un délai raisonnable et leur capacité logistique qui leur permettra de transporter ces biens sur les sites du projet même en tenant compte des problèmes de sécurité sur les principales routes du pays. Cependant, vu que les études pour les 25 systèmes d’eau ne seront pas toutes disponibles en même temps, il est prévu de commencer avec un contrat d’environ 6 millions de dollars pour alimenter les travaux pour les premières études disponibles. Lorsque les autres études sont prêtes, et dépendamment des résultats du premier contrat, un d’autres contrats peuvent être signés avec UNOPS pour l’acquisition des autres matériels et accessoires. En plus de l’acquisition de ces biens pour la réalisation des travaux, le projet prévoit de faire l’acquisition d’une quantité maximum de 20 véhicules. Ces véhicules seront achetés selon les besoins qui seront déterminés et confirmés durant toute l’exécution du projet. Travaux 17 Le montant des travaux représente 34 % du montant total du projet. Il s’agit de la réalisation des travaux de construction d’environ 28 réseaux d’eau potable. Tel que déjà mentionné dans la section relative aux biens, ces contrats seront exclusivement pour la réalisation des travaux car les matériaux et accessoires nécessaires seront fournis par la DINEPA car ils seront déjà acquis dans le cadre du marché pour l’acquisition de biens et accessoires. Il y aura un appel d’offre international ouvert pour le recrutement de firmes de construction pour la réalisation des travaux pour les trois réseaux les plus importants à savoir Anse Rouge, Mole Saint Nicolas et Jean Rabel dont le budget estimatif est 9 millions de dollars. Pour les 25 autres réseaux, ils seront constitués en trois lots, soit un lot par région et ils feront l’objet d’un appel d’offre national restreint. En effet, sur la base des leçons apprises du projet EPARD, pour éviter le risque de sélectionner des firmes de construction qui n’ont pas la capacité nécessaire pour exécuter les travaux, le projet a décidé de travailler avec une liste restreinte de firmes qui ont prouvé leur capacité dans le projet antérieur. Pour finir, il y a les travaux qui ont commencé dans le cadre du projet antérieur et qui doit être finalisé dans le cadre de ce projet. Les contrats pour la finalisation de ces travaux seront exécutés par entente directe avec la possibilité d’un financement rétroactif vu qu’il est urgent de finaliser ces travaux et que l’accord de financement pour ce projet n’est pas encore signé. Services de consultants (bureaux et firmes de consultation) Le projet prévoit un contrat de 5.8 millions de dollars pour une assistance technique basée sur les résultats pour la réalisation des études nécessaires, la préparation des DAO et la supervision des travaux pour les 28 réseaux d’eau potable. Ce contrat sera attribué par entente directe avec UNOPS selon les modalités des régulations de la Banque. UNOPS est choisi pour la réalisation de cette activité sur la base de sa capacité à se mobiliser très rapidement sur le terrain et d’une expérience fructueuse qu’il y a eu avec la DINEPA pur des activités similaires. Il y a également un marché d’assistance technique pour le renforcement et l’accompagnement de la DINEAP pour un montant équivalent a 2.45 millions de dollars, soit 3 % du montant total du financement.. Le processus d’identification des besoins liés a ce renforcement est toujours en cours. Les trois autres marchés de consultation dont le budget estimatif est estimé à 500 milles dollars, soit 1 % du montant du projet, seront lancés en appel d’offre ouvert selon la méthode SFQC. Services autres que ceux de Consultants 18 Il y aura sur le projet trois marchés de services non Consultatifs sous forme d’assistance technique par résultats orientée sur le transfert des compétences. Le marché le plus important de cette section est l’Assistance technique basée sur les résultats pour la gestion des fonds à transférer pour les porteurs de projets communautaires. Le montant estimatif de ces contrats est de 10 millions de dollars. Il s’agit de recruter une ou plusieurs ONG dont la mission consistera à gérer les fonds qui seront transférés à des acteurs locaux pour la réalisation des travaux dans leurs communautés sous une modalité MDOD. Cette approche s'inspire des enseignements tirés des précédents projets CDD en Haïti, du Projet de reconstruction de logements du quartier de Port-au- Prince/PREKAD (P125805) et du Projet de développement communautaire urbain en Haïti/PRODEPUR (P106699), ainsi que d'autres projets financés par la Banque Mondiale. Les ONG seront sélectionnées à la suite d’un appel à proposition international. Les critères d’évaluation devront être définis selon des exigences qui permettraient de sélectionner des ONG qui ont une expérience sectorielle éprouvée, une bonne capacité à opérer à grande échelle et en partenariat avec les communes et les communautés ; qui ont une compréhension approfondie des dynamiques sociales et institutionnelles qui influenceront la mise en œuvre et qui connait bien le milieu haïtien. Le projet financera également une assistance technique base sur les résultats pour appuyer la DINEPA dans la fourniture d’une réponse d’urgence au cholera et promouvoir l’hygiène sanitaire de base. Il s’agit d’un contrat de 5 millions de dollars qui sera signé avec l’UNICEF qui a déjà une expérience avérée dans la réalisation de ces types d’activité. Le dernier contrat de services non consultatifs est une assistance technique pour la sensibilisation, mobilisation sociale et renforcement des capacités techniques et commerciales des opérateurs et des acteurs locaux de la DINEPA sur trois ans pour un montant équivalent à 2 millions de dollars. Ce contrat pourrait être signé avec l’UNOPS si les résultats du contrat pour la réalisation des études avec UNOPS est jugé satisfaisant. Sinon, il y aura la possibilité de lancer un appel à proposition pour recruter une firme capable de réaliser cette prestation. a 19 Services consultants (consultants individuels) Un éventail de consultants individuels sera recruté pour appuyer la mise en œuvre du Projet /Programme et pour constituer l’équipe de Projet/Programme. La plupart de ces recrutements seront conduits de manière restreinte par comparaison d’au moins trois(3) CV. Cependant si la DINEPA n’arrive pas à trouver des consultants dans sa base de données qui répondent au profil recherché, une publication dans le Nouvelliste ou sur son site pourra être envisagée. Au-delà des consultants individuels, certaines de ces consultations pourront être regroupées et ainsi faire appel à un bureau d’étude spécialisé. Conclusions clés : Les informations disponibles ont permis de vérifier la capacité du marché national et international de répondre aux besoins du Projet/Programme. Les fournisseurs, les prestataires , les bureaux d’étude, les consultants individuels nationaux , les organisations à but non lucratif disposent d’une bonne connaissance du marché haïtien ,et ont un personnel expérimenté pour exécuter les marchés cités initialement. Néanmoins, pour les marchés d’Assistance Technique par Résultats en fonction de ses expériences en cours , la DINEPA devra s’assurer : a) que les TDR répondent aux besoins exprimés par le Projet/Programme et permettront l’atteinte des objectifs du Projet/Programme ; a) que les délais de construction prévus dans les DAO soient raisonnables et correspondent au contexte de la zone d’intervention ; b) , que les spécifications techniques et les cahiers de charge soient bien détaillés .clairs et validées avant même d’autoriser de lancer les marchés, c) c) la santé financière de toutes firmes en sous-traitance, notamment en ce qui concerne les demandes d’avance et les garanties de bonne exécution, d) que les éventuels prestataires de services soient dotés d'un personnel qualifié pouvant délivrer les extrants souhaités . e) que les firmes de supervision soient de rigueur dans le processus d'évaluation et de contrôle, Les garanties bancaires ont par le passé engendré des délais additionnels dans la conduite des marchés. Il est recommandé d’organiser un atelier de travail avec les institutions financières de façon à leur donner des informations génériques sur le Projet/Programme , et cela faciliterait éventuellement l’émission des garanties. Synthèse des points clés sous forme de matrice (A REVISER ENSEMBLE): 20 A la suite de ces éléments, nous préciserons l’analyse des risques inhérents au Projet/Programme et l’impact sur les stratégies d’achats. 3. Analyse des risques liés à la passation de marchés ( A REVISER ENSEMBLE DINEPA-BM) Risque = impacts négatifs sur le Projet/Programme et sur l’activité elle-même. Dans le tableau ci-dessous, les risques sont évalués afin de les mitiger au maximum. Détenteur Description du risque Mesures d’atténuation du risque Personnel impliqué dans le Embaucher un spécialiste de Client / projet peut être surchargé ou passation des marchés sur la base Banque ne pas avoir une connaissance des termes de référence acceptables Mondiale suffisante des régulations de la pour la Banque Banque mondiale Organiser des ateliers pour former tout le personnel impliqué dans l’approvisionnement dans le cadre du projet sur le nouveau cadre d’approvisionnement Formations pratiques continues du personnel clé identifié sur le règlement sur les marchés publics En raison du climat Mettre en œuvre des actions de Client d’insécurité, les entreprises sensibilisation auprès des firmes qui qualifiées pour la fourniture de ont eu de bonnes performances dans biens, de travaux et de services le projet précèdent pour assurer qu’il de conseil peuvent être y ait une base d’approvisionnement réticentes à soumissionner. pour le projet. Se prémunir contre les risques Définir des mécanismes de paiement Client de pertes de change liés à la clairs et simples dans les clauses dépréciation de la gourde et à contractuelles. l’inflation du pays Signer des contrats en devises Inclure des clauses d’ajustement de prix dans les contrats Interférences dans le Les procédures et la réglementation Client processus de la Banque mondiale doivent d’approvisionnement s’appliquer. Expliquer le processus aux autorités et aux homologues Retard de paiement des Mettre en place un mécanisme de Client factures fournisseurs suivi du paiement des intérêts moratoires. 21 Le retard dans le délai de Appliquer les pénalités de retard du Client livraison code des marchés publics. Les gestionnaires de contrats doivent assurer un suivi étroit des contrats Manque de capacité technique Renforcer la gestion des contrats et Client et financière des le contrôle des coûts, en surveillant soumissionnaires les paiements par rapport à la qualité et pas seulement par rapport à l’avancement des livrables attendus des entrepreneurs / consultants, conformément au contrat. Perte de vue totale de Suivi des contrats grâce, notamment Client l’exécution d’un contrat (i) à l’élaboration de calendriers précis avec des alertes pour les porteurs de dossier et la PM, (ii) à l’élaboration d’échéanciers des livrables, (iii) à la tenue de réunions périodiques portant sur l’exécution des contrats, permettant de faire le suivi avec la firme si sera (iii) utilisation du systeme de suivi des contrats développés par la BM. Absence d’un système Mettre en place un système Client d’archivage pouvant entraîner d’archivage approprié au niveau de la perte de documents l’unité pour assurer la conformité avec le manuel de d’archivage de documents de passation de marché de la Banque mondiale Utilisation systématique de STEP pour toutes les transactions de passation de marché et la gestion des contrats Ce tableau d’analyse des risques ne prend pas en compte tous les marchés du PPM, mais ceux dont les risques sont plus élevés et plus susceptibles d’avoir un niveau de criticité important sur le Projet. 22 4. Les stratégies préférentielles qui vont être exposées découlent d’une analyse croisée des montants des marchés au regard du montant global pour le Projet/Programme avec le niveau de criticité de risques évalué. Cette analyse permet de positionner les différents marchés au sein d’une matrice : CRITICITE DU RISQUE ELEVEE Les 7 premier marchés sont des marchés stratégiques. Ils sont une priorité pour le projet. Le premier marché pour l’acquisition des biens ainsi que le marché numéro 5 pour la préparation des études et les dossiers d’appel d’offre sont considérés comme les marchés les plus important du projet car la réalisation de tous les travaux de la composante 2 dépende des études et de la disponibilité des biens et accessoires. Par conséquent, une attention spéciale doit être porté à ces deux marchés car bien que de manière générale la probabilité associée à ces risques est faible mais l’impact est considérable. Les marchés de travaux (#2 et #3) ont un niveau de risque très élevé vu qu’il s’agit de marché pour un montant total d’environ 24 million de dollars et donc il faut s’assurer de pouvoir contracter des firmes avec de bonne qualification technique et financière. Etant donné le contexte socio-politique et sécuritaire précaire du pays, il s’agit d’un défi assez important. Le marché #4 pour le recrutement des ONG pour la gestion des fonds (MDOD) est aussi un marché d’un montant important (10 M USD). Il s’agit de pouvoir recruter une ou des ONG internationale ayant une bonne connaissance du secteur de l’eau et du pays et disposant de la capacite nécessaire pour effectuer la mission, ce qui réduit considérablement la liste des fournisseurs potentiels. La DINEPA dispose d’une base de données avec des ONG qualifiées dans le secteur et elle doit pouvoir examiner et sensibiliser ces ONG pour qu’elles participent dans le processus. L’assistance technique à fournir par l’UNICEF (marché #6) ne présente pas un niveau de risque élevé mais il s’agit d’une activité critique pour la composante 1 par conséquent tout retard dans l’exécution de ce contrat aura des conséquences importantes sur les résultats de cette composante. Les autres marchés sont de montant et de risque relativement faibles. Ils peuvent être gérés simplement selon les procédures convenues. 5. Stratégies recommandées Budget estimat Approch Méthode Categor # Description if (US$, e de de Remarque ie millions marché selection ) 23 Acquisition de Entente directe avec biens et UNOPS selon les accessoires Paragraphes 6.47 Selection 1 pour la Biens 6 Directe and 6.48 of the directe construction World Bank des réseaux Procurement (UNOPS) Regulations Travaux de construction et de Appel réhabilitation d’offre Internatio 2 des réseaux Travaux 9 ouverte nal de Anse Rouge en trois et de Mole lots Saint Nicolas et Jean Rabel Liste restreinte avec Travaux de Appel les firmes dont les construction d’offre performances ont 3 Travaux 15 National de 25 réseaux national été satisfaisantes en trois lots restreint dans le projet antérieur Assistance technique Entente directe avec pour la UNOPS selon les réalisation des Paragraphes 6.47 études, la Consult Entente Selection 4 5.8 and 6.48 of the préparation ant Directe directe World Bank des DAO et la Procurement supervision Regulations des travaux (UNOPS) Travaux de construction et équipement Appel de trois 5 Travaux 1.5 National d’offre entrepôts avec ouvert supervision par les OREPAs Continuite des travaux du projet Finalisation anterieur / des travaux Entente Selection Paragraphe 6.8 et 6 hydraulique Travaux 0.6 Directe directe 6.9 des régulations de de passation de Lascahobas marché de la Banque Continuite des Finalisation Entente Selection 7 Travaux 1.4 travaux du projet des travaux Directe directe anterieur / 24 électromécani Paragraphe 6.8 et ques 6.9 des régulations de passation de marché de la Banque Continuite des travaux du projet anterieur / Supervision Consult Entente Selection Paragraphe 7.13 et 8 des travaux de 0.2 ant Directe directe 7.14 des régulations Lascahobas de passation de marché de la Banque Sensibilisation , mobilisation sociale et renforcement Entente directe avec des capacités UNOPS selon les techniques et Non Paragraphes 6.47 commerciales consulti Entente Selection 9 2 and 6.48 of the des ng Directe directe World Bank opérateurs et services Procurement des acteurs Regulations locaux de la DINEPA sur trois ans (UNOPS) Etude pour l’amélioration des 1 Consult connaissances 0.2 National SFQC 0 ant sur l’hydrogéologi e d’Haïti Assistance technique basée sur les résultats pour Service la gestion des autres Open 1 fonds à que 10 Internatio SFQC 1 transférer consult nal pour les ant porteurs de projets communautair es Assistance Service Entente directe avec technique autres UNICEF selon les 1 Entente Direct base sur les que 5 Paragraphes 6.47 2 Directe Selection résultats pour consult and 6.48 of the appuyer la ant World Bank 25 DINEPA dans Procurement la fourniture Regulations d’une réponse d’urgence au cholera et promouvoir l’hygiène sanitaire de base (UNICEF) Assistance Technique 1 pour le Consult Internatio 2.45 SFQC Composante 3.2 3 renforcement ant nal des capacités de la DINEPA Consultati Acquisition de 1 on de Composante 3.2 matériels Biens 0.2 National 4 fournisse Plusieurs achats informatiques urs Consultati Acquisition de 1 on de Composante 3.2 mobiliers de Biens 0.15 National 5 fournisse Plusieurs achats bureau urs Composante 3.2 Acquisition de Consultati Plusieurs achats en 1 20 véhicules on de Good 1 National fonction des besoins 6 en plusieurs fournisse du projet durant la lots urs periode d'execution Assistance technique Consultan 1 pour le Consult Internatio 0.1 t 7 développeme ant nal individuel nt de la régulation Selection Auditeur 1 Consult au financier 0.1 National 8 ant moindre externe cout Consultan 1 Coordonnateu Consult 0.27 National t 9 r de projet ant individuel Consultan 2 Coordonnateu Consult 0.54 National t 0 r régional ant individuel Spécialiste en développeme Consultan 2 Consult nt 0.22 National t 1 ant communautair individuel e 26 Ingénieurs Consultan 2 Consult hydrauliques 0.38 National t 2 ant (2) individuel Consultan 2 Ingénieur Consult 0.19 National t 3 sanitaire ant individuel Spécialiste en Consultan 2 opération de Consult 0.22 National t 4 réseau d’eau ant individuel potable Spécialiste en Consultan 2 gestion des Consult 0.22 National t 5 risques ant individuel sociaux Spécialiste en gestion des Consultan 2 Consult risques 0.22 National t 6 ant environnemen individuel taux Consultan 2 Spécialiste en Consult 0.16 National t 7 genre ant individuel Consultan 2 Spécialiste Consult 0.2 National t 8 financier ant individuel Spécialiste en Consultan 2 Consult passation des 0.2 National t 9 ant marchés individuel Spécialiste en Consultan 3 Consult gestion de 0.32 National t 0 ant contrats (2) individuel Consultan 3 Spécialiste en Consult 0.18 National t 1 sécurité ant individuel Spécialiste en Consultan 3 Consult communicatio 0.18 National t 2 ant n individuel Spécialiste en collection et Consultan 3 Consult gestion de 0.22 National t 3 ant données individuel géospatiales Spécialiste en Consultan 3 Consult suivi et 0.22 National t 4 ant évaluation individuel 6. Résumé de la Stratégie de Développement en Passation des Marchés du Projet/Programme(SDPM) pour le Document d’Evaluation du Projet ( A REVISER ENSEMBLE DINEPA-BM) 27 Au vu de ce qui précède, on peut conclure que l’environnement national est globalement favorable pour l’acquisition des biens et services identifiés pour la mise en œuvre du projet. L’acquisition des biens et services, les marchés de prestations intellectuelles et de travaux seront exécutés, selon la nécessité, conformément à la réglementation de la Banque mondiale. Il est à noter que les prestations intellectuelles de services seront assez importantes par la réalisation des études qui permettront de réaliser les travaux des 21 réseaux. La disponibilité de ces études dans un délai raisonnable pour permettre le lancement des travaux est très important pour l’avancement du projet. Quant aux travaux, il a été anticipé qu’il serait difficile, compte tenu du contexte du pays, d’attirer des firmes internationales pour la réalisation des travaux. De plus, dans le projet antérieur, la DINEPA a eu des mauvaises expériences avec certaines firmes nationales. Par conséquent, il est prévu de considérer une stratégie qui permettrait de travailler avec les firmes qui ont eu une performance satisfaisante dans le projet antérieur. Le projet envisage de prendre des dispositions appropriées pour minimiser les risques liés aux processus de passation des marchés. 28 PROCUREMENT Haiti : Decentralized Sustainable and Resilient Rural Water and Sanitation Project PLAN General Information Country: Haiti 2023-05-29 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178188 GPN Date: Project Name: Decentralized Sustainable and Resilient Rural Water and Sanitation Project Loan / Credit No: IDA / E1700 AF-WSS Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned T-GG-NO.01-02/2023 / FINAL National Procure ISATION DES TRAVAUX DE RE ment Document - HABILITATION ET D’EXTENSI Component 2: WASH Service Under Imple 2024-02-0 IDA / E1700 Prior Direct Selection Direct - National 1 Envelope proce 3,590,000.00 0.00 2023-05-24 2023-02-10 2023-05-26 2023-02-15 2023-06-06 ON DU SYSTEME D’ALIMENTA Development mentation 1 ss (Non Bank-SPD TION EN EAU POTABLE (SAEP ) ) DE LASCAHOBAS DANS LE DÉPARTEMENT DU CENTRE GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HT-AF-WSS-363732-GO-DIR / Acquisition de biens et acces Component 2: WASH Service Direct - Internation Pending Impl IDA / E1700 Prior Direct Selection 6,000,000.00 0.00 2023-07-14 2023-07-19 2023-08-23 2024-02-19 soires pour la construction d Development al ementation es réseaux (UNOPS) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HT-AF-WSS-368989-CS-QCB S / Assistance Technique ba sée sur les résultats pour la Component 2: WASH Service Quality And Cost- Open - Internationa Pending Impleme gestion du fonds local desti IDA / E1700 Prior 3,000,000.00 0.00 2023-07-05 2023-07-26 2023-09-08 2023-10-06 2023-11-05 2023-12-10 2024-01-14 2026-12-29 Development Based Selection l ntation né aux interventions EAH d es 15 communes de l'OREPA SUD et de la mobilisation co mmunautaire INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HT-AF-WSS-240523-CS-CDS / REALISATION D'ACTIVITES D 'INGENIERIE SOCIALE ET DE S UPERVISION DES TRAVAUX D Component 2: WASH Service Under Implement IDA / E1700 Post Direct Selection Direct - National 500,000.00 0.00 2023-05-28 2023-05-30 2023-06-01 2023-06-28 2024-02-23 E REHABILITATION ET D’EXTE Development ation NSION DU SYSTEME D’ALIME NTATION EN EAU POTABLE (S AEP) DE LASCAHOBAS DANS LE DEPARTEMENT DU CENTR E HT-AF-WSS-368672-CS-CDS / Recrutement d'un Coordonn ateur pour le Projet Eau Pot Component 3: Sector wide r Under Implement IDA / E1700 Post Direct Selection Direct - National 14,800.00 0.00 2023-06-22 2023-06-28 2023-06-28 2023-07-06 2023-11-03 able et Assainissement en esults-based strengthening ation milieu rural résilient ,durabl e et décentralisé (P178188 ) HT-AF-WSS-368686-CS-CDS / Recrutement d'un spécialist e en passation de marchés p Component 3: Sector wide r Under Implement IDA / E1700 Post Direct Selection Direct - National 10,800.00 0.00 2023-06-22 2023-06-28 2023-06-28 2023-07-06 2023-11-03 our le Projet Eau Potable et A esults-based strengthening ation ssainissement en milieu rural ,résilient ,durable et décentr alisé ( EPARRDD- P178188) HT-AF-WSS-368697-CS-CDS / Recrutement d'un spécialist e en gestion de contrats pour Component 3: Sector wide r Under Implement IDA / E1700 Post Direct Selection Direct - National 8,800.00 0.00 2023-06-22 2023-06-28 2023-06-28 2023-07-06 2023-11-03 le Projet Eau Potable et Assa esults-based strengthening ation inissement en milieu rural r ésilient ,durable et décentrali sé (EPARRDD-P178188) HT-AF-WSS-368712-CS-CDS / Recrutement d'un spécialist e en gestion financière/Admi Component 3: Sector wide r Under Implement nistrateur/Comptable pour le IDA / E1700 Post Direct Selection Direct - National 10,800.00 0.00 2023-06-22 2023-06-28 2023-06-28 2023-07-06 2023-11-03 esults-based strengthening ation projet Eau Potable et Assaini ssement rural ,résilient ,dura ble et décentralisé ( EPARRD- P178188) HT-AF-WSS-368713-CS-CDS / Recrutement d'un Spéciali ste en Opération de Réseaux Component 3: Sector wide r Pending Impleme d'Eau Potable pour le projet IDA / E1700 Post Direct Selection Direct - National 12,000.00 0.00 2023-06-22 2023-06-28 2023-07-06 2023-11-03 esults-based strengthening ntation Eau Potable et assainisseme nt en milieu rural ,résilient ,d urable et décentralisé ( EPA RRDD-P178188) Page 1 HT-AF-WSS-368719-CS-CDS / Recrutement d'un Spéciali ste en Suivi et Evaluation po Component 3: Sector wide r Under Implement IDA / E1700 Post Direct Selection Direct - National 12,000.00 0.00 2023-06-22 2023-06-28 2023-06-28 2023-07-06 2023-07-18 ur le projet Eau Potable et as esults-based strengthening ation sainissement en milieu rural ,résilient ,durable et décentr alisé ( EPARRDD-P178188) HT-AF-WSS-368724-CS-CDS / Recrutement d'un Spécialist e en Gestion des Risques Soc Component 3: Sector wide r Under Implement iaux pour le Projet Eau Potabl IDA / E1700 Post Direct Selection Direct - National 12,000.00 0.00 2023-06-22 2023-06-28 2023-06-28 2023-07-06 2023-11-03 esults-based strengthening ation e et Assainissement en milie u rural ,résilient ,durable et d écentralisé. ( EPARRDD-P178 188) HT-AF-WSS-368969-CS-INDV / Recrutement d'un Spécialis te en Gestion des Risques E Component 3: Sector wide r Individual Consult Under Implement nvironnementaux pour le Pro IDA / E1700 Post Open - National 36,000.00 0.00 2023-07-03 2023-06-29 2023-07-31 2023-08-14 2023-09-03 2024-08-28 esults-based strengthening ant Selection ation jet Eau Potable et Assainisse ment en milieu rural, résilien t ,durable et décentralisé ( E PARRDD-P178188) HT-AF-WSS-368972-CS-INDV / Recrutement d'un spécialist e en Développement Comm Component 3: Sector wide r Individual Consult Pending Impleme unautaire pour le Projet Eau IDA / E1700 Post Open - National 36,000.00 0.00 2023-07-03 2023-07-31 2023-08-14 2023-09-09 2024-03-07 esults-based strengthening ant Selection ntation Potable et assainissement en milieu rural ,résilient ,durable et décentralisé ( EPARRDD-P 178188) HT-AF-WSS-368979-CS-INDV / Recrutement d'un spécialist e Genre et Inclusion pour le Component 3: Sector wide r Individual Consult Pending Impleme IDA / E1700 Post Open - National 26,400.00 0.00 2023-07-03 2023-07-31 2023-08-14 2023-09-03 2024-08-28 projet Eau potable et assaini esults-based strengthening ant Selection ntation ssement en milieu rural ,rési lient ,durable et décentralisé ( EPARRDD-P178188) HT-AF-WSS-368986-CS-CDS / Recrutement d'un cabinet d e Consultants pour la finalisa Component 3: Sector wide r Pending Impleme IDA / E1700 Post Direct Selection Direct - National 27,000.00 0.00 2023-07-03 2023-07-09 2023-07-18 2023-08-07 tion de l'audit financier du p esults-based strengthening ntation rojet EPARD pour la période du 1er octobre 2020 au 31 ju illet 2023 HT-AF-WSS-368990-CS-INDV / Recrutement de trois ( 3) Coordonnateur régional pour Component 3: Sector wide r Individual Consult Under Implement IDA / E1700 Post Limited 86,400.00 0.00 2023-07-03 2023-06-29 2023-07-08 2023-07-29 2023-08-27 2024-08-21 le Projet Eau Potable et Assai esults-based strengthening ant Selection ation nissement en milieu rural,rés ilient ,durable et décentralisé ( EPARRDD- P 178188) Page 2 PROCUREMENT PLAN (Textual Part) Project information: [West Bank and Gaza] [Technology for Youth and Jobs] [P-172571] Project Implementation agency: [Development Alternative Inc -DAI] Date of the Procurement Plan: [22-October-2020] Period covered by this Procurement Plan: [22-October- 2020 – to 30- October-2025] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The procurement under the project will be carried out following well- established private sector procurement arrangements or commercial practices, acceptable to the World Bank as specified in Paras 6.46 and 7.26 of the Bank’s Procurement regulations Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods). Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is not Applicable. PROCUREMENT West Bank and Gaza : Technology for Youth and Jobs PLAN General Information Country: West Bank and Gaza 2020-10-22 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172571 GPN Date: Project Name: Technology for Youth and Jobs Loan / Credit No: TF / B2944 Development Alternative Inc., Europe Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-DAI-201021-GO-CP / Proc Project management and Im Commercial Practi Single Stage - One E urement of ICT Equipment fo TF / B2944 Post Limited 12,876.04 Completed 2020-10-22 2020-10-13 2020-10-25 2020-10-13 2020-10-29 2020-10-25 2020-11-01 2020-11-05 2020-11-05 2020-10-27 2020-12-06 2021-01-19 plementation Support ces nvelope r "Technology for Youth and J obs" project. GZ-DAI-201026-GO-CP / Proc urement of Furniture and win Project management and Im Commercial Practi TF / B2944 Post Direct 1,613.01 Completed 2020-10-22 2020-10-22 2020-10-25 2020-11-01 2020-11-01 2020-10-29 2020-11-30 2020-11-20 dow blinds for "Technology f plementation Support ces or youth and jobs" Project. GZ-DAI-201029-CW-CP / Gla ss separation and 3 glass do Project management and Im Commercial Practi TF / B2944 Post Direct 3,400.00 Completed 2020-10-28 2020-11-01 2020-11-02 2020-10-28 2020-11-09 2020-10-30 2020-12-10 2020-11-20 ors for "Technology for youth plementation Support ces and jobs" project. GZ-DAI-254165-GO-RFQ / Pr ocurement of Equipment & F Improving IT service capabili Request for Quota Single Stage - One E TF / B2944 Post Limited 22,534.50 Completed 2021-09-27 2021-09-22 2021-11-03 2021-10-15 2022-01-30 2021-12-28 urniture for Gaza Recovery G ties tions nvelope rantee (Pal Life company)- G aza GZ-DAI-265539-GO-RFQ / Pr ocurement of Equipment for Improving IT service capabili Request for Quota Single Stage - One E TF / B2944 Post Limited 301,885.00 Completed 2021-12-05 2021-11-29 2022-01-26 2021-12-22 2022-05-31 2022-06-29 Gaza recovery program Gran ties tions nvelope tee (Digital communication c ompany)- Gaza GZ-DAI-269093-GO-RFQ / Pr ocurement of Equipment & F Improving IT service capabili Request for Quota Single Stage - One E TF / B2944 Post Limited 35,207.20 Completed 2021-12-22 2021-12-20 2022-01-20 2022-01-12 2022-05-31 2022-02-04 urniture under Gaza recovery ties tions nvelope program (for ADMARK co. in Gaza) GZ-DAI-271189-GO-RFQ / Pr ocurement of equipment for Improving IT service capabili Request for Quota Single Stage - One E Gaza recovery program for t TF / B2944 Post Limited 129,440.00 Completed 2021-12-29 2022-01-04 2022-01-23 2022-01-24 2022-06-30 2022-03-15 ties tions nvelope he benefit of Mashareq for eq uipment & production- Gaza GZ-DAI-272864-GO-RFQ / Pr ocurement of Office Furniture Improving IT service capabili Request for Quota Single Stage - One E & Equipment under Gaza rec TF / B2944 Post Limited 37,456.40 Completed 2022-01-20 2022-01-18 2022-02-10 2022-02-03 2022-07-31 2022-04-11 ties tions nvelope overy program for the benefi t of (Laptop center & Clever toys) GZ-DAI-317942-GO-RFQ / Pr Project management and Im Request for Quota Single Stage - One E ocurement of Laptops and Int TF / B2944 Post Limited 0.00 Completed 2022-09-29 2022-09-28 2022-10-11 2022-10-17 2022-11-05 plementation Support tions nvelope eractive LCD for the benefit o f MTIT. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-DAI-364033-GO-RFQ / Jo Improving IT service capabili Request for Quota Single Stage - One E b Fair Event (will be conduct TF / B2944 Post Limited 0.00 Signed 2023-05-31 2023-05-29 2023-06-11 2023-07-31 ties tions nvelope ed in 4 Universities in WestB ank) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-DAI-212188-NC-CP / Tec Project management and Im Commercial Practi TF / B2944 Post Limited 4,060.00 Completed 2021-01-06 2021-01-13 2021-01-14 2021-02-15 2021-02-01 2021-02-11 2021-02-07 2021-02-11 2021-02-10 2021-02-17 2021-02-11 2021-02-18 2021-04-25 2021-07-01 hstart Website Development. plementation Support ces GZ-DAI-221149-CS-CCP / Int ernship program setup Train ing for HR departments in IT Firms (Cosulting Firm) Improving IT service capabili Commercial Practi The firm will be giving HR trai TF / B2944 Post Limited 0.00 Canceled 2021-04-06 2021-04-11 2021-05-02 2021-05-09 2021-05-13 2021-05-16 2022-05-16 ties ces ning for IT firms so that they are able to design and mana ge efficient and productive tr aining programs for trainees. GZ-DAI-252214-CS-CQS / Te Project management and Im Consultant Qualifi TF / B2944 Post Limited 12,500.00 Signed 2021-10-17 2021-11-21 2021-10-31 2021-11-24 2021-11-30 2021-12-20 2022-01-04 2021-12-21 2023-06-29 ch Start Audit/ 2 years contra plementation Support cation Selection ct GZ-DAI-221163-CS-CCP / Dia gnostic study Consulting Fir m The firm will conduct a gap a Improving IT service capabili Consultant Qualifi TF / B2944 Post Limited 0.00 Canceled 2022-09-04 2022-09-18 2022-10-18 2022-11-22 2023-05-21 nalysis and diagnosis of IT fir ties cation Selection ms weaknesses and potential areas of improvement based on best practices of manage ment and operations under c omponent 1 Page 1 GZ-DAI-221175-CS-CCP / IT Gender assessment Consulti ng firm. Improving IT service capabili Consultant Qualifi Pending Impleme A company will be contracted TF / B2944 Post Limited 0.00 2022-08-04 2022-08-18 2022-09-17 2022-10-22 2023-04-20 ties cation Selection ntation to run a gender assessment study to identify obstacles an d challenges faced by emplo yees and IT firms under com ponent 1. GZ-DAI-221213-CS-CCP / Ass essment, design and implem entation of Outsourcing matc Improving market access, an hmaking with International b Consultant Qualifi Pending Impleme TF / B2944 d increasing demand and in Post Limited 0.00 2022-10-02 2022-10-16 2022-11-15 2022-12-20 2023-06-18 uyers, foreign investment out cation Selection ntation vestments reach and Promotion campai gn by doing Research and as sessment activities & other I mplementation activities. GZ-DAI-360548-CS-CQS / Pro Improving IT service capabili Consultant Qualifi Open - Internationa Under Implement viding Advisory Services on TF / B2944 Post 0.00 2023-05-14 2023-05-09 2023-05-21 2023-05-28 2023-06-15 2023-06-20 2023-07-10 2024-07-09 ties cation Selection l ation Managerial Capabilities for IT Services Firms GZ-DAI-364303-CS-CQS / En Project management and Im Consultant Qualifi Pending Impleme TF / B2944 Post Limited 0.00 2023-06-05 2023-06-08 2023-06-11 2023-06-18 2023-08-31 glish Trainings for the Ministr plementation Support cation Selection ntation y staff. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-DAI-201140-CS-INDV / Gr Project management and Im Individual Consult ants and Procurement Specia TF / B2944 Post Limited 46,800.00 Terminated 2020-10-22 2020-10-25 2020-10-25 2020-10-22 2020-11-01 2020-10-28 2020-11-08 2020-10-29 2021-11-07 plementation Support ant Selection list Procurement Plan-TechSt art Project. GZ-DAI-201601-CS-INDV / M Project management and Im Individual Consult onitoring and Evaluation Spe TF / B2944 Post Direct 31,200.00 Terminated 2020-12-10 2020-12-09 2020-12-20 2020-10-29 2020-12-27 2020-10-14 2021-01-10 2020-10-16 2022-01-10 plementation Support ant Selection cialist (part time) GZ-DAI-207291-CS-INDV / Se Improving the IT services ec Individual Consult TF / B2944 Post Direct 8,100.00 Completed 2020-12-05 2020-12-07 2020-12-15 2020-12-15 2020-12-16 2020-12-07 2020-12-23 2020-12-10 2021-02-21 2021-02-16 nior Consultant osystem ant Selection GZ-DAI-207300-CS-INDV / Te Improving IT service capabili Individual Consult TF / B2944 Post Limited 57,600.00 Terminated 2020-12-10 2020-12-08 2020-12-15 2020-12-21 2021-01-05 2020-12-23 2021-02-09 2020-12-24 2022-02-09 chnical Lead - Component On ties ant Selection e GZ-DAI-207318-CS-INDV / Pr Improving market access, an Individual Consult TF / B2944 Post Direct 104,000.00 Signed 2020-12-08 2020-12-09 2020-12-18 2020-11-01 2021-01-08 2020-11-14 2021-02-12 2020-10-15 2022-02-12 oject Director d increasing demand and in ant Selection vestments GZ-DAI-207319-CS-INDV / Fi Project management and Im Individual Consult TF / B2944 Post Direct 48,100.00 Signed 2020-12-10 2020-12-09 2020-12-20 2021-01-25 2021-01-16 2020-10-28 2021-02-04 2020-10-15 2022-02-04 nancial Management Speciali plementation Support ant Selection st GZ-DAI-207391-CS-INDV / Te Improving the IT services ec Individual Consult TF / B2944 Post Limited 42,000.00 Signed 2020-12-10 2020-12-08 2020-12-15 2021-02-22 2021-01-05 2021-03-02 2021-02-09 2021-03-03 2022-02-09 chnical Lead- Component 2 osystem ant Selection GZ-DAI-207392-CS-INDV / C Improving IT service capabili Individual Consult TF / B2944 Post Direct 16,250.00 Completed 2020-12-10 2020-12-10 2020-12-20 2020-12-10 2020-12-27 2020-11-02 2021-01-10 2020-11-03 2022-01-10 2021-12-16 ommunication Officer ties ant Selection GZ-DAI-207313-CS-INDV / Te Improving the IT services ec Individual Consult TF / B2944 Post Direct 0.00 Canceled 2020-12-10 2020-12-20 2020-12-22 2021-01-14 2022-01-14 chnical Lead _Component 2 osystem ant Selection GZ-DAI-211380-CS-CCP / Re Improving IT service capabili Individual Consult TF / B2944 Post Limited 57,600.00 Signed 2020-12-24 2020-12-24 2020-12-28 2020-12-17 2021-01-10 2020-12-23 2021-01-14 2020-12-24 2022-01-13 cruitment of component 1 le ties ant Selection ad. GZ-DAI-208394-CS-INDV / En Project management and Im Individual Consult vironmental and Social Cons TF / B2944 Post Direct 31,200.00 Signed 2020-12-10 2020-12-31 2020-12-14 2020-12-01 2020-12-17 2021-01-07 2020-12-21 2020-12-08 2025-06-28 plementation Support ant Selection ultant- Split between Techsta rt and IPSD GZ-DAI-212164-CS-INDV / Hi Project management and Im Individual Consult re a Procurement Specialist f TF / B2944 Post Limited 36,000.00 Signed 2021-01-03 2021-01-06 2021-01-06 2020-12-28 2021-01-12 2021-01-06 2021-01-17 2021-01-07 2021-12-16 plementation Support ant Selection or Techstart Project. GZ-DAI-215912-CS-INDV / Hi re Operations Coordinator-Ga Project management and Im Individual Consult TF / B2944 Post Limited 12,000.00 Signed 2021-02-01 2021-01-20 2021-02-02 2021-01-20 2021-02-03 2021-01-17 2021-02-03 2021-01-18 2022-02-02 za Full time, Split between IP plementation Support ant Selection SD and Techstart Projects. GZ-DAI-239077-CS-INDV / Te Improving IT service capabili Individual Consult TF / B2944 Post Open 18,000.00 Signed 2021-06-13 2021-08-05 2021-07-05 2021-08-08 2021-07-15 2021-08-08 2021-07-25 2021-08-12 2022-07-24 chnical Advisor- Gaza ties ant Selection GZ-DAI-245555-CS-INDV / Te Improving IT service capabili Individual Consult TF / B2944 Post Limited 17,010.00 Signed 2021-08-01 2021-08-05 2021-08-06 2021-11-22 2021-08-10 2021-11-22 2021-09-01 2021-11-26 2022-08-31 chnical Coordinator for TechS ties ant Selection tart GZ-DAI-246770-CS-INDV / Hi Project management and Im Individual Consult re a short term technical gra TF / B2944 Post Limited 0.00 Canceled 2021-08-11 2021-11-14 2021-08-19 2021-09-06 2021-09-19 2022-03-20 plementation Support ant Selection nt support officer (Assistant) GZ-DAI-264345-CS-INDV / Sh ort Term Technical and Grant Improving IT service capabili Individual Consult TF / B2944 Post Limited 4,800.00 Signed 2021-11-21 2021-11-24 2021-11-23 2021-11-25 2021-11-24 2021-11-25 2021-12-01 2021-11-26 2022-03-31 s Support officer (4 Months w ties ant Selection ith possibility of renewable). GZ-DAI-268404-CS-INDV / C ommunication Specialist for Improving IT service capabili Individual Consult TF / B2944 Post Open 27,600.00 Signed 2021-12-19 2021-12-16 2022-01-21 2022-02-06 2022-01-30 2022-03-29 2022-02-02 2022-03-31 2023-02-01 TechStart Project (50% of the ties ant Selection salary will be from TechStart Project) GZ-DAI-275306-CS-CDS / Pro vision of Service For Establis Improving IT service capabili TF / B2944 Post Direct Selection Direct 70,000.00 Completed 2022-01-27 2022-02-01 2022-02-13 2022-02-03 2022-02-24 2022-03-08 2022-05-31 2022-07-28 hing IT Companies database ties for firms operating in West B ank and Gaza. GZ-DAI-299931-CS-INDV / D AI is seeking to hire a technic Improving IT service capabili Individual Consult al consultant to support Tech TF / B2944 Post Limited 0.00 Canceled 2022-06-23 2022-06-22 2022-07-03 2022-07-13 2022-07-25 2023-07-24 ties ant Selection Start activities at the nationa l center for technological inn ovation & creativity at MTIT GZ-DAI-307239-CS-INDV / So Improving IT service capabili Individual Consult cial Media Campaign for Tech TF / B2944 Post Limited 0.00 Canceled 2022-08-02 2022-08-07 2022-08-04 2022-08-11 2022-09-18 2022-09-30 ties ant Selection Start project Page 2 GZ-DAI-310913-CS-INDV / R Improving IT service capabili Individual Consult TF / B2944 Post Open - National 0.00 Completed 2022-08-22 2022-08-24 2022-09-05 2022-10-11 2022-09-08 2022-10-11 2022-10-13 2023-10-12 2022-11-01 esident Technical Consultant ties ant Selection GZ-DAI-324778-CS-CDS / Vid Improving IT service capabili eo production to highlight Te TF / B2944 Post Direct Selection Direct - National 0.00 Completed 2022-11-02 2022-11-08 2022-11-06 2022-11-08 2022-11-13 2022-11-22 2022-12-04 ties chStart Project beneficiaries. GZ-DAI-331221-CS-INDV / Se nior Consultant – Committee Improving IT service capabili Individual Consult TF / B2944 Post Limited 0.00 Signed 2022-12-12 2022-12-13 2022-12-17 2022-12-15 2022-12-18 2023-02-05 2022-12-22 2023-06-19 Member (HCIS & Pioneer Pro ties ant Selection grams) Individual consultant number 1 GZ-DAI-331414-CS-INDV / Se nior Consultant – Committee Improving IT service capabili Individual Consult TF / B2944 Post Limited 0.00 Signed 2022-12-13 2023-01-19 2022-12-15 2023-01-24 2022-12-18 2023-02-14 2022-12-22 2023-06-20 Member (HCIS & Pioneer Pro ties ant Selection grams) Individual consultant number 2 GZ-DAI-331415-CS-CDS / Re gistration of new firms at the Improving IT service capabili TF / B2944 Post Direct Selection Direct - National 0.00 Signed 2022-12-18 2023-01-19 2022-12-21 2023-01-22 2022-12-27 2023-12-26 Ministry of National Economy ties (Local Companies) GZ-DAI-331433-CS-CDS / Re Improving IT service capabili gistration of Branches of fore TF / B2944 Post Direct Selection Direct - National 0.00 Signed 2022-12-15 2023-01-19 2022-12-19 2023-01-22 2022-12-27 2023-12-26 ties ign firms at the Ministry of N ational Economy GZ-DAI-360822-CS-INDV / Hi re M&E Specialist for IPSD an Project management and Im Individual Consult Under Implement TF / B2944 Post Open - National 0.00 2023-05-15 2023-05-09 2023-06-06 2023-06-08 2023-06-18 2024-06-17 d Techstart. This position will plementation Support ant Selection ation be allocated for both IPSD an d Techstart. Page 3 PROCUREMENT PLAN (Textual Part) Project information: P164435 - SOLAR ENERGY IN LOCAL COMMUNITIES - SOLEIL NYAKIRIZA Project Implementation agency: REGIDESO - Ministry in charge of Energy Date of the Procurement Plan: October 12, 2020 Period covered by this Procurement Plan: October 2020 – February 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, , Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the country procurement handbook, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. - The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. - Rights for the Bank to review procurement documentation and activities. - An effective complaints mechanism. - Maintenance of records of the Procurement Process When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable Works: is not applicable PROCUREMENT Burundi : Solar Energy in Local Communities PLAN General Information Country: Burundi 2020-11-13 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164435 GPN Date: Project Name: Solar Energy in Local Communities Loan / Credit No: IDA / D5670 Solar Energy in Local Communities Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BI-REGIDESO-199331-GO-RF Technical Assistance, Capaci B / Acquisition de 4 Véhicules Single Stage - One E IDA / D5670 ty Building and Project Imple Post Request for Bids Open - National 130,000.00 184,502.27 Completed 2020-12-17 2021-06-23 2020-12-22 2021-06-23 2021-02-02 2021-07-06 2021-03-04 2021-10-01 2021-04-08 2022-02-03 2021-07-07 2022-02-05 du Projet (Véhicule de terrain nvelope mentation Support double cabine 4x4) BI-REGIDESO-199327-GO-RF Q / Acquisition des équipeme Technical Assistance, Capaci nts informatiques et matériel Request for Quota Single Stage - One E IDA / D5670 ty Building and Project Imple Post Open - National 40,000.00 0.00 Canceled 2021-01-04 2021-02-22 2021-08-21 s de bureau (6 Ordinateurs p tions nvelope mentation Support ortables, 9 ordinateurs de bu reau, 2 imprimantes multifon ctions) BI-SOLEIL PIU-261783-GO-RF Technical Assistance, Capaci Request for Quota Single Stage - One E Q / Fourniture du mobilier de IDA / D5670 ty Building and Project Imple Post Limited 50,000.00 40,726.91 Completed 2021-11-16 2021-10-07 2022-01-11 2021-12-30 2022-07-10 2022-01-14 tions nvelope bureau et autres Equipemen mentation Support ts BI-SOLEIL PIU-261688-GO-RF Technical Assistance, Capaci Request for Quota Single Stage - One E Q / Fourniture et pose des rid IDA / D5670 ty Building and Project Imple Post Limited 8,000.00 5,266.00 Completed 2021-11-09 2021-10-07 2022-01-04 2021-12-30 2022-07-03 2022-01-14 tions nvelope eaux mentation Support BI-SOLEIL PIU-261686-GO-RF Technical Assistance, Capaci Request for Quota Single Stage - One E Q / Fourniture du matériel de IDA / D5670 ty Building and Project Imple Post Limited 22,000.00 18,299.19 Completed 2021-11-10 2021-10-07 2022-01-05 2021-12-30 2022-07-04 2022-01-14 tions nvelope bureau mentation Support BI-SOLEIL PIU-261743-GO-RF Technical Assistance, Capaci Request for Quota Single Stage - One E Q / Installation du matériel et IDA / D5670 ty Building and Project Imple Post Limited 9,000.00 3,611.30 Signed 2021-11-16 2021-11-17 2022-01-11 2021-12-29 2022-07-10 tions nvelope Fourniture de l'internet mentation Support BI-SOLEIL PIU-267193-GO-RF Q / FOURNITURE DES EQUIPE Technical Assistance, Capaci Request for Quota Single Stage - One E MENTS INFORMATIQUES (6or IDA / D5670 ty Building and Project Imple Post Limited 40,000.00 47,225.13 Completed 2021-12-12 2021-09-28 2022-02-06 2021-12-30 2022-08-05 2022-01-28 tions nvelope dinateurs portable, 9 ordinat mentation Support eurs de bureau, 2 imprimant es multifonctions) BI-SOLEIL PIU-276897-GO-RF Technical Assistance, Capaci Request for Quota Single Stage - One E Q / Fourniture des Equipeme IDA / D5670 ty Building and Project Imple Post Limited 35,000.00 0.00 Signed 2022-03-02 2022-10-20 2022-04-27 2022-10-24 tions nvelope nts pour vidéoconférence mentation Support BI-SOLEIL PIU-303856-GO-RF B / Fourniture, Installation et Maintenance de Systèmes Ph otovoltaïques pour les Établis Energy Services for Schools Open - Internationa Single Stage - One E IDA / D5670 Prior Request for Bids 4,500,000.00 0.00 Signed 2022-07-18 2022-08-22 2022-07-23 2022-08-25 2022-09-03 2022-11-08 2022-10-03 2023-05-05 2022-11-07 2023-05-06 sements de Santé et le Loge and Health Service Centers l nvelope ment du Personnel des Form ations Sanitaires dans les pro vinces de Bujumbura,Karuzi, Makamba, Muyinga, Rumong e et Rutana BI-SOLEIL PIU-312336-GO-RF Q / Acquisition du mobilier su Technical Assistance, Capaci Request for Quota Single Stage - One E Under Imple pplémentaires(12 Etagères, IDA / D5670 ty Building and Project Imple Post Limited 7,000.00 0.00 2022-09-18 2023-03-21 2022-11-13 2023-05-12 tions nvelope mentation 2 armoires, 6 Chaises tourna mentation Support ntes, 22 chaises simple, . BI-SOLEIL PIU-318306-GO-RF Technical Assistance, Capaci B / Acquisition de deux camio Single Stage - One E IDA / D5670 ty Building and Project Imple Post Request for Bids Open - National 170,000.00 0.00 Canceled 2022-09-30 2022-11-17 2022-10-05 2022-11-17 2022-11-16 2022-12-19 2022-12-16 2023-01-20 2023-07-19 nnettes double cabine 4x4 e nvelope mentation Support t un véhicule station wagon 4 x4 BI-SOLEIL PIU-318311-GO-RF Technical Assistance, Capaci Q / Acquisition des équipeme Single Stage - One E Under Imple IDA / D5670 ty Building and Project Imple Post Request for Bids Open - National 20,000.00 0.00 2022-10-14 2023-05-14 2022-10-19 2023-05-15 2022-11-30 2022-12-30 2023-02-03 2023-08-02 nts bureautiques(1GPS, 1 An nvelope mentation mentation Support glomètre, 1 appareil photo) BI-SOLEIL PIU-318309-GO-RF B / Acquisition du matériel inf Technical Assistance, Capaci ormatiques de Quatorze(14) Single Stage - One E IDA / D5670 ty Building and Project Imple Post Request for Bids Open - National 60,000.00 0.00 Signed 2022-10-14 2022-12-14 2022-10-19 2022-12-15 2022-11-30 2023-01-20 2022-12-30 2023-02-24 2023-02-03 2023-08-02 Lap TOP, un (1) Serveur et Q nvelope mentation Support uatre (4)imprimantes réseau x multifonctions et des anti-v irus BI-SOLEIL PIU-333671-GO-RF Energy Services for Schools Open - Internationa Single Stage - One E B / Fourniture des Equipeme IDA / D5670 Prior Request for Bids 2,000,000.00 0.00 Canceled 2023-02-28 2023-03-05 2023-04-16 2023-05-16 2023-06-20 2023-12-17 and Health Service Centers l nvelope nts pour les ateliers de maint enance BI-SOLEIL PIU-342762-GO-RF B / Fourniture, Installation et Maintenance de Systèmes Ph otovoltaïques de 234 Établis Energy Services for Schools Open - Internationa Single Stage - One E Under Imple sements de Santé et le Loge IDA / D5670 Prior Request for Bids 7,800,000.00 0.00 2023-02-24 2023-03-19 2023-03-01 2023-06-01 2023-04-12 2023-06-23 2023-05-12 2023-06-16 2023-12-13 and Health Service Centers l nvelope mentation ment du Personnel Sanitaires dans les provinces Bubanza, Bururi , Cankuzo,Cibitoke, Git ega, Kayanza , Mwaro, Ngozi et Ruyigi Phase B en trois lot Page 1 BI-SOLEIL PIU-342763-GO-RF B / Fourniture de 4 bureaux Technical Assistance, Capaci Request for Quota Single Stage - One E Under Imple en L avec tiroirs, 1 armoire s IDA / D5670 ty Building and Project Imple Post Limited 10,000.00 0.00 2023-02-25 2023-04-22 2023-10-19 tions nvelope mentation emi-vitre, 6 Etagères métalli mentation Support ques, 5 chaises pour visiteur, BI-SOLEIL PIU-345063-GO-RF Technical Assistance, Capaci B / Acquisition de deux camio Single Stage - One E Under Imple IDA / D5670 ty Building and Project Imple Post Request for Bids Open - National 170,000.00 0.00 2023-02-28 2023-03-01 2023-03-05 2023-03-01 2023-04-16 2023-04-03 2023-05-16 2023-06-20 2023-12-17 nnettes double cabine 4x4et nvelope mentation mentation Support un véhicule station wagon 4x 4 BI-SOLEIL PIU-358702-GO-RF B / Fourniture des Equipeme nts informatiques(66 tablette Energy Services for Schools Single Stage - One E Under Imple IDA / D5670 Post Request for Bids Open - National 88,000.00 0.00 2023-05-03 2023-06-29 2023-05-08 2023-06-29 2023-06-19 2023-07-19 2023-08-23 2024-02-19 s,33 desk top, 33 imprimante and Health Service Centers nvelope mentation s,10 ordinateur portable, 33 power Bank) pour les Distric ts sanitaires, la DISE et la DG E BI-SOLEIL PIU-358867-GO-RF B / Fourniture de Trente trois Energy Services for Schools Open - Internationa Single Stage - One E Under Imple ( 33 )motos et coffres de ran IDA / D5670 Post Request for Bids 250,000.00 0.00 2023-05-08 2023-06-29 2023-05-13 2023-06-29 2023-06-24 2023-07-24 2023-08-28 2024-02-24 and Health Service Centers l nvelope mentation gement d'outils pour les cent res de maintenance des Distr icts BI-SOLEIL PIU-359099-GO-RF Energy Services for Rural Co Open - Internationa Single Stage - One E Pending Impl B / Fourniture et installation IDA / D5670 Prior Request for Bids 33,000,000.00 0.00 2023-06-01 2023-06-06 2023-07-18 2023-08-17 2023-09-21 2024-03-19 mmunities l nvelope ementation des Mini réseaux sur 26 sites BI-SOLEIL PIU-359103-GO-RF Technical Assistance, Capaci Request for Quota Single Stage - One E Under Imple Q / Fourniture du matériel de IDA / D5670 ty Building and Project Imple Post Limited 40,000.00 0.00 2023-05-08 2023-05-24 2023-07-03 2023-12-30 tions nvelope mentation bureau et d'entretien mentation Support BI-SOLEIL PIU-359841-GO-RF Q / Fourniture du mobilier de Energy Services for Schools Request for Quota Single Stage - One E Pending Impl IDA / D5670 Post Limited 30,000.00 0.00 2023-05-23 2023-07-18 2024-01-14 33 districts sanitaires(66 tabl and Health Service Centers tions nvelope ementation e de bureau et 66 chaises) BI-SOLEIL PIU-359848-GO-RF B / Fourniture des Equipeme Energy Services for Schools Open - Internationa Single Stage - One E Under Imple IDA / D5670 Post Request for Bids 1,100,000.00 0.00 2023-05-15 2023-06-28 2023-05-20 2023-06-29 2023-07-01 2023-07-31 2023-09-04 2024-03-02 nts pour atelier de maintena and Health Service Centers l nvelope mentation nce des districts sanitaires, D ISE, DGE BI-SOLEIL PIU-364305-GO-RF B / Fourniture, Installation et Maintenance de Systèmes Ph Energy Services for Schools Open - Internationa Single Stage - One E Under Imple otovoltaïques pour 400 Établ IDA / D5670 Prior Request for Bids 5,480,000.00 0.00 2023-06-05 2023-06-15 2023-06-10 2023-06-20 2023-07-22 2023-08-21 2023-09-25 2024-03-23 and Health Service Centers l nvelope mentation issements scolaire dans les p rovinces de Bubanza , Bujum bura , Cibitoke , Gitega Kirun do,Muyinga, Ngozi NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BI-REGIDESO-205282-NC-RF Technical Assistance, Capaci Request for Quota Single Stage - One E Q / Location bureau qui hebe IDA / D5670 ty Building and Project Imple Post Open - National 100,000.00 43,612.25 Signed 2020-12-12 2021-02-06 2021-06-01 2022-02-06 tions nvelope rgera l'UCP mentation Support BI-REGIDESO-242359-NC-DI R / Engagement des Nations Unies pour le contrat avec PA Energy Services for Schools IDA / D5670 Prior Direct Selection Direct 3,700,000.00 3,500,000.00 Signed 2021-08-09 2021-08-26 2021-08-14 2021-09-01 2021-09-02 2021-09-29 2022-08-28 M dans le cadre de Construct and Health Service Centers ion des foyers améliorés aup rès des écoles choisies dans l e Projet Soleil Nyakiriza BI-SOLEIL PIU-262121-NC-RF Technical Assistance, Capaci Request for Quota Single Stage - One E Q / recrutement d'une sociét IDA / D5670 ty Building and Project Imple Post Limited 9,000.00 1,170.04 Signed 2021-11-24 2022-02-07 2022-01-19 2022-03-11 2022-07-18 tions nvelope é de gardiennage mentation Support BI-SOLEIL PIU-264110-CS-CD S / Recrutement par entente Technical Assistance, Capaci directe de TOMATE pour la fo IDA / D5670 ty Building and Project Imple Post Direct Selection Direct 50,000.00 24,656.49 Signed 2021-12-10 2021-12-07 2021-12-15 2021-12-29 2022-01-19 2022-02-18 2022-07-18 urniture, l'installation, le para mentation Support métrage du logiciel TOM² PR O ainsi que la formation BI-SOLEIL PIU-291079-NC-RF Technical Assistance, Capaci Request for Quota Single Stage - One E Q / Location du bureau qui h IDA / D5670 ty Building and Project Imple Post Limited 100,000.00 0.00 Canceled 2022-05-05 2022-05-10 2022-06-30 2022-12-27 tions nvelope erbagera le UCP mentation Support BI-SOLEIL PIU-294813-NC-DI Technical Assistance, Capaci R / Recrutement de CRMP pa IDA / D5670 ty Building and Project Imple Post Direct Selection Direct 12,000.00 0.00 Canceled 2022-05-18 2022-05-19 2022-05-23 2022-06-27 2022-12-24 r entente pour la mise en œu mentation Support vre des tests de foyer amélio ré. BI-SOLEIL PIU-347445-GO-RF Technical Assistance, Capaci B / Acquisition, Installation d' Open - Internationa Single Stage - One E Pending Impl IDA / D5670 ty Building and Project Imple Post Request for Bids 50,000.00 0.00 2023-03-17 2023-03-22 2023-05-03 2023-06-02 2023-07-07 2024-01-03 un logiciel et formation sur l l nvelope ementation mentation Support a planification de l'électrifica tion par réseaux CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BI-REGIDESO-205280-CS-QC Technical Assistance, Capaci BS / Recrutement du Cabinet Quality And Cost- Open - Internationa IDA / D5670 ty Building and Project Imple Post 200,000.00 0.00 Signed 2020-12-07 2022-07-29 2020-12-21 2021-12-17 2021-02-03 2022-03-16 2021-03-05 2022-09-19 2021-04-04 2022-11-11 2021-05-02 2022-11-30 2021-05-16 2022-05-16 conseil en transaction au sei Based Selection l mentation Support n de l'UCP et l'ABER BI-REGIDESO-225556-CS-QC BS / Recrutement d'un Admin Energy Services for Rural Co Quality And Cost- Open - Internationa IDA / D5670 Prior 3,000,000.00 4,220,881.65 Signed 2021-04-16 2021-05-10 2021-05-07 2021-08-18 2021-06-20 2021-12-10 2021-07-18 2022-02-23 2021-08-17 2022-04-05 2021-09-21 2022-09-12 2021-10-26 2022-09-25 2022-10-26 istrateur-Gestionnaire Intern mmunities Based Selection l ational de Fonds de Subventi ons Page 2 BI-REGIDESO-235218-CS-LC S / Audit comptable et financi Technical Assistance, Capaci Least Cost Selecti Open - Internationa er du Projet pour la période a IDA / D5670 ty Building and Project Imple Post 60,000.00 11,840.34 Signed 2021-06-14 2021-06-15 2021-06-28 2021-12-07 2021-07-17 2022-03-29 2021-08-16 2022-05-12 2021-08-17 2022-06-09 2021-09-21 2022-08-04 2021-10-12 2022-09-24 2022-04-10 on l llant du 1er Juillet 2020 au 30 mentation Support Juin 2021 ,et 1er Juillet 2021 au 30 Juin 2022 BI-SOLEIL PIU-263797-CS-QC Technical Assistance, Capaci BS / Recrutement d'un Coord Quality And Cost- Open - Internationa Under Implement IDA / D5670 ty Building and Project Imple Prior 2,500,000.00 0.00 2021-11-22 2021-12-01 2021-12-13 2022-05-31 2022-01-26 2022-08-05 2022-02-23 2022-10-24 2022-03-25 2023-04-20 2022-04-29 2022-06-03 2023-06-03 inateur-Gestionnaire Internat Based Selection l ation mentation Support ional de la facilité BI-SOLEIL PIU-263906-CS-QC BS / Recrutement d'un Consu Technical Assistance, Capaci Quality And Cost- Open - Internationa ltant pour l'élaboration d'une IDA / D5670 ty Building and Project Imple Post 250,000.00 207,666.81 Signed 2021-11-25 2021-11-24 2021-12-16 2021-12-17 2022-01-29 2022-02-25 2022-02-26 2022-04-14 2022-03-28 2022-06-09 2022-05-02 2022-07-11 2022-06-06 2022-08-31 2023-06-06 Based Selection l stratégie nationale d'accès u mentation Support niversel à l'électricité BI-SOLEIL PIU-263919-CS-QC Technical Assistance, Capaci BS / Etude pour l'électrificati Quality And Cost- Open - Internationa IDA / D5670 ty Building and Project Imple Prior 500,000.00 0.00 Canceled 2021-12-23 2022-01-13 2022-02-26 2022-03-26 2022-04-25 2022-05-30 2022-07-04 2023-07-04 on des centres secondaires e Based Selection l mentation Support t collinaires du Burundi BI-SOLEIL PIU-271188-CS-QC Technical Assistance, Capaci BS / Etude pour l'électrificati Quality And Cost- Open - Internationa IDA / D5670 ty Building and Project Imple Post 450,000.00 358,975.00 Signed 2021-12-31 2021-12-28 2022-01-21 2021-12-29 2022-03-06 2022-02-25 2022-04-03 2022-04-05 2022-05-03 2022-06-09 2022-06-07 2022-06-24 2022-07-12 2022-09-06 2023-07-12 on des centres secondaires e Based Selection l mentation Support t collinéaires du Burundi BI-SOLEIL PIU-276908-CS-QC BS / Supervision et vérificatio Energy Services for Schools Quality And Cost- Open - Internationa IDA / D5670 Post 500,000.00 0.00 Canceled 2022-02-11 2022-06-30 2022-03-04 2022-04-17 2022-05-15 2022-06-14 2022-07-19 2022-08-23 2023-08-23 n des activités d'Equipement and Health Service Centers Based Selection l des CDS et centre de mainte nance BI-SOLEIL PIU-312101-CS-CQ Technical Assistance, Capaci S / Conception et Développe Least Cost Selecti Under Implement IDA / D5670 ty Building and Project Imple Post Open - National 8,000.00 0.00 2022-09-05 2022-10-10 2022-09-26 2022-12-13 2022-11-09 2023-03-09 2022-12-07 2023-04-24 2023-01-06 2023-02-10 2023-03-17 2023-09-13 ment du site WEB ,hébergem on ation mentation Support ent, non du domaine et sécur ité SI BI-SOLEIL PIU-321370-CS-CQ Technical Assistance, Capaci Consultant Qualifi S / Recrutement d'un Cabinet IDA / D5670 ty Building and Project Imple Post Open - National 60,000.00 0.00 Signed 2022-10-21 2022-10-19 2022-11-11 2022-11-17 2022-12-25 2023-03-08 2023-01-24 2023-04-11 2023-02-28 2023-08-27 cation Selection local d'audit interne mentation Support BI-SOLEIL PIU-329222-CS-QC BS / Prestations des service fi duciaires par une firme avec des références en IVA afin d' Technical Assistance, Capaci Quality And Cost- Open - Internationa Under Implement assurer le respect par les soc IDA / D5670 ty Building and Project Imple Prior 1,000,000.00 0.00 2022-12-12 2023-06-16 2023-01-02 2023-06-26 2023-02-15 2023-03-15 2023-04-14 2023-05-19 2023-06-23 2024-06-22 Based Selection l ation iétés de leurs obligations vis mentation Support à vis des écoles, centres de s anté et clients de mini-résea ux, distributeurs de produits solaires et de foyer BI-SOLEIL PIU-333427-CS-QC BS / RECRUTEMENT D’UN CO Technical Assistance, Capaci Quality And Cost- Open - Internationa Under Implement NSULTANT( FIRME) CHARGE IDA / D5670 ty Building and Project Imple Prior 1,500,000.00 0.00 2022-12-31 2023-02-14 2023-01-21 2023-03-21 2023-03-06 2023-04-03 2023-05-03 2023-06-07 2023-07-12 2024-07-11 Based Selection l ation DE LA REALISATION DES ETU mentation Support DES RELATIVES A L’ELECTRIF ICATION DE 722 COLLINES BI-SOLEIL PIU-333432-CS-QC BS / Recrutement d'un Cabin Energy Services for Househo Quality And Cost- Open - Internationa Under Implement et pour la supervision et vérif IDA / D5670 Post 500,000.00 0.00 2022-12-31 2023-02-21 2023-01-21 2023-03-14 2023-03-06 2023-04-03 2023-05-03 2023-06-07 2023-07-12 2024-07-11 lds Based Selection l ation ication des activités d'équipe ment des CDS et centres de maintenance BI-SOLEIL PIU-333553-CS-QC Technical Assistance, Capaci BS / Formation des technicie Quality And Cost- Open - Internationa IDA / D5670 ty Building and Project Imple Post 250,000.00 0.00 Canceled 2022-12-31 2023-01-21 2023-03-06 2023-04-03 2023-05-03 2023-06-07 2023-07-12 2024-07-11 ns locaux sur l'installation et Based Selection l mentation Support la maintenance des système s solaires adaptés BI-SOLEIL PIU-341932-CS-QC Technical Assistance, Capaci Quality And Cost- Open - Internationa Under Implement BS / Recrutement d'une ONG IDA / D5670 ty Building and Project Imple Post 460,000.00 0.00 2023-02-28 2023-03-30 2023-03-21 2023-04-12 2023-05-04 2023-06-01 2023-07-01 2023-08-05 2023-09-09 2024-09-08 Based Selection l ation spécialisée/VBG/EAS-HS mentation Support BI-SOLEIL PIU-347358-CS-CQ Technical Assistance, Capaci Consultant Qualifi Under Implement S / Illustration du MGP et pro IDA / D5670 ty Building and Project Imple Post Open - National 50,000.00 0.00 2023-03-14 2023-03-10 2023-04-04 2023-06-07 2023-05-18 2023-06-17 2023-07-22 2024-01-18 cation Selection ation duction des boîtes à images mentation Support en Kirundi BI-SOLEIL PIU-347360-CS-QC BS / Recrutement du Cabinet Technical Assistance, Capaci Quality And Cost- Open - Internationa Under Implement pour réaliser l'étude d'impact IDA / D5670 ty Building and Project Imple Post 250,000.00 0.00 2023-03-17 2023-04-19 2023-04-07 2023-04-27 2023-05-21 2023-06-18 2023-07-18 2023-08-22 2023-09-26 2024-09-25 Based Selection l ation environnemental et social po mentation Support ur l'implantation de 19 sites des Mini réseaux BI-SOLEIL PIU-347483-CS-QC Technical Assistance, Capaci BS / Recrutement d'un Cabin Quality And Cost- Open - Internationa IDA / D5670 ty Building and Project Imple Post 600,000.00 0.00 Canceled 2023-03-17 2023-04-07 2023-05-21 2023-06-18 2023-07-18 2023-08-22 2023-09-26 2024-09-25 et pour les missions de sauve Based Selection l mentation Support garde pour les activités du pr ojet BI-SOLEIL PIU-359101-CS-QC BS / RECRUTEMENT D’UNE E NTITE RESPONSABLE DU RE NFORCEMENT DES CAPACITE Technical Assistance, Capaci S TECHNIQUES ET ASSURER Quality And Cost- Open - Internationa Under Implement IDA / D5670 ty Building and Project Imple Prior 1,200,000.00 0.00 2023-05-05 2023-06-01 2023-05-26 2023-06-20 2023-07-09 2023-08-06 2023-09-05 2023-10-10 2023-11-14 2024-11-13 LA MAINTENANCE PREVENTIV Based Selection l ation mentation Support E ET CURATIVE AUPRES DES FORMATIONS SANITAIRES (H OPITAUX ET CENTRES DE SA NTE) DES DISTRICTS SANITA IRES ET DANS LES ECOLES BI-SOLEIL PIU-359955-CS-QC BS / Recrutement d’un cabin et de communication pour ré Energy Services for Schools Quality And Cost- Under Implement aliser la sensibilisation des ut IDA / D5670 Post Open - National 250,000.00 0.00 2023-05-15 2023-06-26 2023-06-05 2023-06-26 2023-07-19 2023-08-16 2023-09-15 2023-10-20 2023-11-24 2024-11-23 and Health Service Centers Based Selection ation ilisateurs des foyers amélioré s dans les écoles et pour de l ’usage et de l’entretien des s ystèmes solaires dans les CD S. BI-SOLEIL PIU-360099-CS-LC Technical Assistance, Capaci S / Recrutement d'un Cabinet Least Cost Selecti Open - Internationa Under Implement IDA / D5670 ty Building and Project Imple Post 10,000.00 0.00 2023-05-10 2023-05-17 2023-05-31 2023-06-02 2023-07-14 2023-08-11 2023-09-10 2023-10-15 2023-11-19 2024-05-17 pour l'audit des comptes exe on l ation mentation Support rcice du 1er juillet 2022 au 3 0 juin 2023 INDIVIDUAL CONSULTANTS Page 3 Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BI-REGIDESO-199310-CS-IN Technical Assistance, Capaci DV / Elaboration du Manuel O Individual Consult IDA / D5670 ty Building and Project Imple Post Direct 12,000.00 10,450.00 Signed 2020-10-19 2020-07-17 2020-10-29 2020-07-20 2020-11-19 2020-07-20 2020-12-24 2021-01-21 2021-03-24 pérationnel de la composant ant Selection mentation Support e contingente d'intervention d'urgence BI-REGIDESO-199308-CS-IN Technical Assistance, Capaci Individual Consult DV / Recrutement d'un Chef IDA / D5670 ty Building and Project Imple Post Open 60,000.00 0.00 Canceled 2020-12-11 2021-02-08 2021-01-29 2021-02-19 2021-03-05 2022-03-05 ant Selection de Projet au sein de l'ABER mentation Support BI-REGIDESO-198987-CS-IN Technical Assistance, Capaci Individual Consult DV / Recrutement d'un Coord IDA / D5670 ty Building and Project Imple Post 60,000.00 73,109.19 Signed 2020-12-04 2020-12-17 2021-01-07 2021-08-16 2021-01-21 2021-08-16 2021-01-29 2021-09-16 2022-01-29 ant Selection ination National de l'UCP mentation Support BI-REGIDESO-198995-CS-IN Technical Assistance, Capaci DV / Recrutement d'un Spéci Individual Consult IDA / D5670 ty Building and Project Imple Post Open 50,000.00 24,648.82 Signed 2020-12-04 2021-01-08 2021-01-07 2021-08-23 2021-01-21 2021-09-06 2021-02-04 2021-10-15 2023-02-04 aliste en passation des marc ant Selection mentation Support hés au sein de l'UCP BI-REGIDESO-205230-CS-IN Technical Assistance, Capaci DV / Recrutement du Spéciali Individual Consult IDA / D5670 ty Building and Project Imple Post Open 50,000.00 23,420.75 Signed 2020-12-15 2021-11-19 2021-02-02 2022-02-10 2021-02-16 2022-03-10 2021-03-02 2022-04-12 2022-03-02 ste en énergie au sein de l'U ant Selection mentation Support CP du projet NYAKIRIZA BI-REGIDESO-205233-CS-IN Technical Assistance, Capaci DV / Recrutement du Spéciali Individual Consult IDA / D5670 ty Building and Project Imple Post Open 50,000.00 0.00 Canceled 2020-12-15 2021-12-02 2021-02-02 2021-02-16 2021-03-02 2021-04-07 ste en genre au sein de l'UCP ant Selection mentation Support du projet NYAKIRIZA BI-REGIDESO-205239-CS-IN Technical Assistance, Capaci Individual Consult DV / Recrutement du Spéciali IDA / D5670 ty Building and Project Imple Post Open 50,000.00 23,411.10 Signed 2020-12-15 2021-02-01 2021-02-02 2022-02-18 2021-02-09 2022-03-08 2021-03-02 2022-04-12 2022-03-02 ant Selection ste en éducation au sein de l' mentation Support UCP BI-REGIDESO-205258-CS-IN Technical Assistance, Capaci Individual Consult DV / Recrutement d'un Spéci IDA / D5670 ty Building and Project Imple Post Open 50,000.00 24,039.74 Signed 2020-12-15 2021-02-01 2021-02-02 2021-12-03 2021-02-09 2021-12-08 2021-02-17 2022-01-19 2022-02-17 ant Selection aliste en santé au sien de l'U mentation Support CP BI-REGIDESO-205266-CS-IN Technical Assistance, Capaci DV / Recrutement du Spéciali Individual Consult IDA / D5670 ty Building and Project Imple Post Open 50,000.00 24,617.42 Signed 2020-12-15 2021-02-01 2021-02-02 2021-08-16 2021-02-09 2021-09-06 2021-03-02 2021-12-17 2022-03-02 ste en Passation des Marchés ant Selection mentation Support Junior au sein de l'ABER BI-REGIDESO-205272-CS-IN Technical Assistance, Capaci DV / Recrutement d'un Spéci Individual Consult IDA / D5670 ty Building and Project Imple Post Open 50,000.00 23,356.35 Signed 2021-01-12 2021-11-19 2021-03-02 2022-03-16 2021-03-09 2022-04-01 2021-03-30 2022-05-24 2022-03-30 aliste en sauvegardes Enviro ant Selection mentation Support nnemental au sein de l'UCP BI-REGIDESO-205274-CS-IN Technical Assistance, Capaci DV / Recrutement d'un Spéci Individual Consult IDA / D5670 ty Building and Project Imple Post Open 50,000.00 23,422.19 Signed 2021-01-13 2021-12-02 2021-03-03 2022-02-11 2021-03-10 2022-03-09 2021-03-31 2022-04-01 2022-03-31 aliste en sauvegardes enviro ant Selection mentation Support nnemental au sein de l'ABER BI-REGIDESO-210691-CS-IN Technical Assistance, Capaci Individual Consult DV / Recrutement d'un Spéci IDA / D5670 ty Building and Project Imple Post Open 50,000.00 0.00 Canceled 2021-01-19 2021-11-22 2021-03-09 2021-03-30 2021-05-04 2021-10-31 ant Selection aliste social au sein de l'UCP mentation Support BI-REGIDESO-210696-CS-IN Technical Assistance, Capaci Individual Consult DV / Recrutement du Spéciali IDA / D5670 ty Building and Project Imple Post Open 50,000.00 0.00 Canceled 2021-01-18 2021-12-02 2021-03-08 2021-03-29 2021-05-03 2021-10-30 ant Selection ste Social au sein de l'ABER mentation Support BI-REGIDESO-242343-CS-IN DV / Recrutement d'un Consu Technical Assistance, Capaci ltant international pour appu Individual Consult IDA / D5670 ty Building and Project Imple Post Limited 40,000.00 41,240.31 Signed 2021-07-21 2021-08-19 2021-07-26 2021-09-22 2021-08-16 2021-12-08 2021-08-30 2021-12-11 2022-02-26 yer le Projet dans la préparat ant Selection mentation Support ion des DAOs pour l'électrific ation des établissements de santé BI-SOLEIL PIU-261683-CS-IN Technical Assistance, Capaci Individual Consult DV / Recrutement du Chef Co IDA / D5670 ty Building and Project Imple Post Open 50,000.00 21,448.57 Signed 2021-11-10 2021-11-12 2021-12-29 2022-02-02 2022-01-19 2022-03-03 2022-02-23 2022-04-05 2022-08-22 ant Selection mptable de l'UCP du Projet mentation Support Soleil NYAKIRIZA BI-SOLEIL PIU-262118-CS-IN Technical Assistance, Capaci Individual Consult DV / Recrutement de l'Assist IDA / D5670 ty Building and Project Imple Post Open 15,500.00 0.00 Canceled 2021-11-17 2021-12-02 2022-01-05 2022-01-26 2022-03-02 2022-08-29 ant Selection ant du Coordonnateur mentation Support BI-SOLEIL PIU-262120-CS-IN Technical Assistance, Capaci Individual Consult DV / Recrutement d'un Respo IDA / D5670 ty Building and Project Imple Post Open 15,500.00 23,408.73 Signed 2021-11-22 2021-12-02 2022-01-10 2022-02-22 2022-01-31 2022-03-14 2022-03-07 2022-04-28 2022-09-03 ant Selection nsable de la communication mentation Support BI-SOLEIL PIU-263801-CS-IN Technical Assistance, Capaci Individual Consult DV / Recrutement d'un Comp IDA / D5670 ty Building and Project Imple Post Open 50,000.00 15,065.58 Signed 2021-11-29 2021-12-02 2022-01-17 2022-02-22 2022-02-07 2022-03-03 2022-03-14 2022-04-05 2022-09-10 ant Selection table mentation Support BI-SOLEIL PIU-263910-CS-IN Technical Assistance, Capaci Individual Consult DV / Recrutement d'un Spéci IDA / D5670 ty Building and Project Imple Post Open 50,000.00 23,907.82 Signed 2021-12-08 2021-12-02 2022-01-26 2022-02-15 2022-02-16 2022-03-04 2022-03-23 2022-04-12 2022-09-19 ant Selection aliste en Suivi-Evaluation mentation Support BI-SOLEIL PIU-264049-CS-IN Technical Assistance, Capaci Individual Consult DV / Recrutement d'un Respo IDA / D5670 ty Building and Project Imple Post Limited 50,000.00 26,840.37 Signed 2021-11-22 2021-11-19 2021-11-27 2021-11-09 2021-12-18 2021-11-23 2022-01-22 2021-12-17 2022-07-21 ant Selection nsable Administratif et Finan mentation Support cier de l'UCP BI-SOLEIL PIU-264063-CS-IN Technical Assistance, Capaci Individual Consult DV / Recrutement d'un Respo IDA / D5670 ty Building and Project Imple Post Limited 50,000.00 26,840.37 Signed 2021-11-22 2021-11-19 2021-11-27 2021-11-09 2021-12-18 2021-11-23 2022-01-22 2021-12-17 2022-07-21 ant Selection nsable Administratif et Finan mentation Support cier de l'ABER BI-REGIDESO-199321-CS-IN Technical Assistance, Capaci DV / Recrutement d'un Respo Individual Consult IDA / D5670 ty Building and Project Imple Post Open 50,000.00 0.00 Canceled 2020-12-11 2021-02-08 2021-01-29 2021-02-19 2021-03-26 2022-03-26 nsable Administratif et Finan ant Selection mentation Support cier au sein de l'ABR BI-REGIDESO-198991-CS-IN Technical Assistance, Capaci Individual Consult DV / Recrutement d'un Respo IDA / D5670 ty Building and Project Imple Post 50,000.00 0.00 Canceled 2020-12-04 2021-02-08 2021-01-07 2021-01-08 2021-01-29 2021-02-01 ant Selection nsable Administratif et Finan mentation Support cier de l'UCP BI-SOLEIL PIU-275939-CS-IN Technical Assistance, Capaci DV / Recrutement d'un Spéci Individual Consult IDA / D5670 ty Building and Project Imple Post Open 50,000.00 23,295.80 Signed 2022-02-11 2022-02-17 2022-04-01 2022-06-09 2022-04-22 2022-06-30 2022-05-27 2022-08-17 2022-11-23 aliste en Développement So ant Selection mentation Support cial au sein de l'UCP Page 4 BI-SOLEIL PIU-276894-CS-IN Technical Assistance, Capaci DV / Recrutement d'un Spéci Individual Consult IDA / D5670 ty Building and Project Imple Post Open 50,000.00 23,295.80 Signed 2022-02-11 2022-03-01 2022-04-01 2022-06-09 2022-04-22 2022-06-30 2022-05-27 2022-08-17 2022-11-23 aliste en développement soci ant Selection mentation Support al au sein de l'ABER BI-SOLEIL PIU-276895-CS-IN Technical Assistance, Capaci DV / Recrutement d'un Spéci Individual Consult IDA / D5670 ty Building and Project Imple Post Open 50,000.00 0.00 Signed 2022-02-11 2022-07-22 2022-04-01 2022-10-26 2022-04-22 2022-11-02 2022-05-27 2022-11-23 aliste en Genre au sein de l'U ant Selection mentation Support nité de Coordination BI-SOLEIL PIU-277360-CS-IN Technical Assistance, Capaci Individual Consult DV / Recrutement d'un Chef IDA / D5670 ty Building and Project Imple Post Open 60,000.00 0.00 Signed 2022-02-14 2022-08-04 2022-04-04 2022-11-10 2022-04-25 2022-12-02 2022-05-30 2022-11-26 ant Selection de Projet de l'ABER mentation Support BI-SOLEIL PIU-282281-CS-IN Technical Assistance, Capaci Individual Consult DV / Recrutement de l'Assist IDA / D5670 ty Building and Project Imple Post Open 15,500.00 14,977.17 Signed 2022-03-07 2022-03-14 2022-04-25 2022-06-10 2022-05-16 2022-07-18 2022-06-20 2022-09-02 2022-12-17 ant Selection ant du Coordonnateur mentation Support BI-SOLEIL PIU-294801-CS-CD S / Recrutement du Cabinet Technical Assistance, Capaci CHEMAS par Entente directe IDA / D5670 ty Building and Project Imple Post Direct Selection Direct 250,000.00 0.00 Signed 2022-05-16 2022-05-16 2022-05-26 2022-07-06 2022-07-30 2023-01-26 pour réaliser l'étude d'impact mentation Support environnemental et social po ur l'implantation des Mini rés eaux BI-SOLEIL PIU-302494-CS-IN Technical Assistance, Capaci Individual Consult DV / Recrutement d'un (e) E IDA / D5670 ty Building and Project Imple Post Open 50,000.00 0.00 Signed 2022-07-11 2022-07-11 2022-08-29 2022-12-07 2022-09-19 2022-12-22 2022-10-24 2023-04-22 ant Selection xpert(e) National(e) du Secte mentation Support ur Privé BI-SOLEIL PIU-312089-CS-CD Technical Assistance, Capaci S / Recrutement de CRMP par IDA / D5670 ty Building and Project Imple Post Direct Selection Direct - National 12,000.00 0.00 Signed 2022-08-29 2022-08-31 2022-09-08 2022-09-13 2022-11-12 2023-05-11 entente directe pour la mise mentation Support oeuvre des tests de foyer a mélioré BI-SOLEIL PIU-311993-CS-CD S / Recrutement par entente directe du Cabinet Tecno Tra Technical Assistance, Capaci ma Ambiental (TTA) pour la r Direct - Internation IDA / D5670 ty Building and Project Imple Post Direct Selection 50,000.00 0.00 Signed 2022-08-29 2022-09-05 2022-09-08 2022-09-15 2022-11-12 2023-05-11 éalisation des études techniq al mentation Support ues et élaboration des dossie rs d'Appel d'offres pour les tr avaux d'implantation des Min i réseaux phase 1 BI-SOLEIL PIU-318303-CS-CD S / Recrutement du Cabinet Alliance Soleil pour l'appui à l’Unité de Coordination du Pr Technical Assistance, Capaci Direct - Internation ojet dans le processus de pas IDA / D5670 ty Building and Project Imple Post Direct Selection 200,000.00 0.00 Signed 2022-09-29 2022-10-22 2022-10-09 2022-10-25 2022-12-13 2023-06-11 al sation des marchés et de mis mentation Support e en œuvre des premières Ph ases du projet d’électrificatio n des centres de santé pour l a sous-Composante 1.2 BI-SOLEIL PIU-341917-CS-IN Technical Assistance, Capaci Individual Consult Under Implement DV / Recrutement d'un Ingéni IDA / D5670 ty Building and Project Imple Post Open - National 50,000.00 0.00 2023-02-16 2023-02-16 2023-04-06 2023-04-27 2023-06-01 2023-11-28 ant Selection ation eur n° 2 d'appui de l'UCP mentation Support BI-SOLEIL PIU-341925-CS-IN Technical Assistance, Capaci Individual Consult Under Implement DV / Recrutement d'un Ingéni IDA / D5670 ty Building and Project Imple Post Open - National 50,000.00 0.00 2023-02-15 2023-02-16 2023-04-05 2023-04-26 2023-05-31 2023-11-27 ant Selection ation eur d'appui de l'ABER mentation Support Page 5 Plan de Passation des marchés du Projet d’Appui aux Communautés dépendantes de la Forêt (DGM-DRC) P149049 (TF0A0924). I. Général 1. Date d’élaboration : 8 février 2016 2. Date d’approbation par la Banque du Plan de Passation des Marches : 8 février 2016 - Version négociée 3. Date de l’Avis Général de Passation des marchés: 4. Période couverte par ce Plan : Janvier à Décembre 2016 5. Risque passation des marchés : Substantiel II. Biens et Travaux et services autres que ceux de consultants. 1. Seuil de revue préalable: au-dessus duquel le processus de passation des marchés fait l’objet d’une revue préalable de la Banque mondiale tel que décrit dans l’annexe 1 des Directives pour l’acquisition de biens et de services autres que ceux de consultants. Nature des Méthode de passation Valeur seuil Contrats soumis à dépenses de marchés du marché examen préalable de $EU l’IDA 1. Travaux Entente directe Tout montant Tout contrat supérieur ou égal à US$ 100 000 Demande de cotation – < 200.000 Aucun comparaison d’au moins 3 offres 2. AON ˂1 000.000 Tout contrat supérieur ou Fournitures égal à US$500 000 et services Consultation de < 100.000 Aucun assimilés Fournisseurs Entente directe Tout montant Tout contrat supérieur ou égal à US$ 100 000 N.B. : Toutes les justifications du recours à l’entente directe incluant le montant estimé du contrat sont à soumettre à la revue préalable de la Banque. 2. Liste globale des contrats d’équipement devant être financés sur le don de préparation et le projet. Date Réf. Cout Méthode Préfére prévue Commentai Description Revue No. estimés$ de nce pour res 1 Passatio nationa (Prior / l’ouvertur n des le Post) e des marchés (oui/no offres n) Acquisition de cinq 1 motos de brousse 12.000 CF Non Post 15/06/16 et 32 vélos Service informatique de configuration de 2 15/05/16 logiciels 5,000 CF Non Post spécialisés de comptabilité Assurance du 3 matériel roulant 15/06/16 2,000 ED Non Post (pour 3 ans) Contrat ouvert – tarif Impression et préférentiels duplication des négociés documents du 4 20,000 1/12/16 pour les projet, du Code AC Non Post prestations Forestier et des attendues décrets durant l’année CF= Consultations de Fournisseurs AC = Accord Cadre III. Sélection de Consultants 1. Seuil de revue préalable: au-dessus duquel le processus de sélection fait l’objet d’une revue préalable de la Banque mondiale tel que décrit dans l’annexe 1 des Directives pour la sélection et l’emploi de consultants. Nature de Méthode de Valeur seuil du Contrats soumis à examen dépenses passation de contrat préalable marchés $EU Consultan ≥ 200.000 Tout contrat supérieur ou ts égal à US$ 500 000 Firmes < 200.000 Aucun QC Tout montant Tout contrat supérieur ou égal à US$ 100 000 Entente directe 2 Consultan Tout montant Tout contrat supérieur ou ts Consultant égal à Individuel individuel 200 000 US$ s Entente directe Tout montant Tout contrat supérieur ou égal à US$ 100 000 Tous les TDRs, quelle que soit la valeur du contrat, sont soumis à examen préalable. Toutes les justifications du recours à l’entente directe incluant le montant estimé du contrat sont soumis à l’examen préalable de la Banque. QC = Qualifications du Consultant 2. Listes restreintes comprenant uniquement des candidats nationaux: Les listes restreintes pour les contrats de consultants estimées à un coût inférieur à $100,000 pour les services ordinaires et $200,000 pour les contrats de supervision peuvent être entièrement composées de consultants nationaux, suivant les dispositions du Paragraphe 2.7 des Directives pour l’emploi des Consultants. 1 2 3 4 5 6 7 8 Examen Date Ref. Description Montant Préalable prévue Date Commentaires No. Méthod estimé ou à pour prévue e de ($.US) postériori l’ouvertu pour sélectio par la re des attributio n Banque offres n Opérateur spécialisé Pour les 3 pour le suivi des premières plaintes, 1 ED 200,000 Priori 15/07/16 15/08/16 années – consultation Composante 3b - permanente des REPALEF communautés Réalisation pour 2 chaque APAC de la 1 seule sélection cartographie avec 5 lots de QC 225,000 Post 15/08/16 15/09/16 participative, du 45,000 USD – plan de gestion et du Composante 2b PARAR Opérateur spécialisé Pour 3 ans – 3 QC 45,000 Post 1/03/16 1/04/16 sur la question des Composante 1a – 3 droits fonciers des PA Etudes pour dégager des options susceptibles de 4 renseigner la CI 5,000 Post 15/08/16 15/09/16 Composante 1a réforme foncière sur l'accès des PA à la terre Opérateur spécialisé pour créer des Pour 3 ans - 5 lobbies pour QC 45,000 Post 1/03/16 1/04/16 Composante 1a l'adoption de la loi sur les PA Opérateur spécialisé pour l'appui à la gestion Pour 3 ans - 6 QC 45,000 Post 1/03/16 1/04/16 communautaire de Composante 1a l'affectation des terres (APAC) Opérateurs pour Les lots seront l'alphabétisation des définis après le PACL impliqués dans diagnostic la gestion du projet institutionnel et les former à la initial pour 7 QC 40,000 Post 15/08/16 15/09/16 gestion et à la petite identifier les comptabilité (tenue opérateurs du livre de caisse, locaux et les gestion des entrées besoins - et des sorties, etc) Composante 1b Consultant appui Conservation Communautaire 8 CI 5,000 Post 15/2/16 10/03/16 pour le bilan des expériences existantes Contrat 3 ans 9 Expert Sauvegardes CI 70,000 Post 15/07/16 15/08/16 renouvelable - Composante 3a Appui pour la finalisation - Rédaction du Manuel 10 CI 5,000 Post 1/03/16 1/04/16 pour la mise en de mise en œuvre vigueur - Composante 3a Pour 3 ans - 11 Auditeur externe SMC 45,000 Post 15/07/16 15/08/16 Composante 3a En vue de la Expert technique revue à mi- 12 CI 30,000 Post 15/11/16 15/12/16 indépendant parcours - Composante 3b 4 5 PROCUREMENT Congo, Democratic Republic of : Forest Dependent Communities Support Project PLAN General Information Country: Congo, Democratic Republic of 2018-09-19 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P149049 GPN Date: Project Name: Forest Dependent Communities Support Project Loan / Credit No: TF / A0924, TF / A5550 CARITAS CONGO Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-CARITAS-125539-GO-RF Component 3 - Increase the Q / 40 téléphones (+4) Andro capacity to implement the IP Request for Quota Single Stage - One E TF / A0924 Post Limited 15,600.00 6,783.00 Signed 2019-08-05 2019-10-29 2019-09-30 2020-03-14 2020-03-28 id pour le suivi des indicateur LC development activities a tions nvelope s avec KOBO. nd consolidate feedback NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-CARITAS-83598-NC-RFQ / Contrat - Cadre avec Imprim Component 1 - Reinforce the eurs (plusieurs lots) pour mo participation of the IPLC in fo Request for Quota Single Stage - One E Pending Impl TF / A0924 Post Limited 60,000.00 0.00 2018-11-05 2018-12-31 2019-06-29 dules d'alphabétisation , cod rest and land management tions nvelope ementation e forestier, textes sur le fonci processes related to REDD+ er (40000 documents de taill es diverses) ZR-CARITAS-122739-CS-CDS Component 1 - Reinforce the / Transport et distribution de participation of the IPLC in fo Request for Quota Single Stage - One E Pending Impl s modules dans les territoires TF / A0924 Post Limited 8,000.00 0.00 2019-07-31 2019-09-25 2020-03-23 rest and land management tions nvelope ementation avec AEN ( consultations de processes related to REDD+ trois transporteurs pour dem ande des prixà ZR-CARITAS-83603-NC-RFQ / Component 1 - Reinforce the Transport des documents po participation of the IPLC in fo Request for Quota Single Stage - One E TF / A0924 Post Limited 3,000.00 0.00 Canceled 2018-11-05 2018-12-31 2019-06-29 ur Kisangani, Mbujimayi, Go rest and land management tions nvelope ma, Kanange, Inongo et Mba processes related to REDD+ ndaka ZR-CARITAS-175242-NC-RFQ / Sélection d'un prestataire p Component 2 - Support com Request for Quota Single Stage - One E our la reproduction des docu TF / A0924 munity-based sustainable fo Post Limited 12,750.00 0.00 Canceled 2020-07-25 2020-09-19 2021-03-18 tions nvelope ments sur le foncier, foresteri rest and land management e communautaire et amenag ement du territoire CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3 - Increase the ZR-CARITAS-66039-CS-CDS / capacity to implement the IP Consultant Qualifi Recrutement point focal INO TF / A0924 Post Open - National 18,000.00 0.00 Signed 2018-09-13 2018-09-13 2018-09-18 2023-06-01 2018-10-07 2023-06-05 2018-10-17 2023-06-09 2018-10-27 2019-04-25 LC development activities a cation Selection NGO nd consolidate feedback ZR-CARITAS-241037-CS-QCB Component 3 - Increase the S / Recrutement d'un Cabinet capacity to implement the IP Consultant Qualifi TF / A0924 Post Open - National 6,000.00 8,260.00 Signed 2021-07-14 2021-07-15 2021-07-17 2021-09-10 2021-07-24 2021-07-27 2021-07-29 2021-07-30 2021-08-08 2021-08-11 2021-09-07 d'Audit pour Auditer les Etats LC development activities a cation Selection financiers du Projet DGM exe nd consolidate feedback rcice 2020 ZR-CARITAS-49120-CS-CDS / Component 3 - Increase the CAUDITEC - Recrutement d'u capacity to implement the IP Quality And Cost- n Auditeur externe pour la c TF / A0924 Post Open - National 40,000.00 0.00 Canceled 2018-10-31 2018-10-31 2018-11-21 2019-01-04 2019-02-01 2019-03-03 2019-04-07 2019-05-12 2020-05-11 LC development activities a Based Selection ertification des comptes de l nd consolidate feedback a DGM pour les comptables 2 016, 2017 et 2018 ZR-CARITAS-280030-CS-QCB Component 3 - Increase the S / Recrutement d'un auditeu capacity to implement the IP Quality And Cost- r externe pour la reddition de TF / A0924 Post Open - National 40,000.00 0.00 Signed 2022-03-07 2023-06-12 2022-03-28 2023-06-22 2022-05-11 2023-06-20 2022-06-08 2023-06-20 2022-07-08 2023-06-20 2022-08-12 2023-06-20 2022-09-16 2023-09-16 LC development activities a Based Selection s comptes du projet DGM exe nd consolidate feedback rcices 2016, 2017 et 2018 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3 - Increase the ZR-CARITAS-66157-CS-CDS / capacity to implement the IP Individual Consult TF / A0924 Post Open 22,500.00 0.00 Canceled 2018-10-31 2019-10-01 2018-12-19 2019-01-09 2019-02-13 2019-08-12 PF Sauvegardes KISANGANI LC development activities a ant Selection nd consolidate feedback Component 3 - Increase the ZR-CARITAS-66158-CS-CDS / capacity to implement the IP Individual Consult TF / A0924 Post Open 9,000.00 0.00 Signed 2018-10-31 2019-10-01 2018-12-19 2023-06-05 2019-01-09 2023-06-07 2019-02-13 2019-08-12 PF Sauvegardes GOMA LC development activities a ant Selection nd consolidate feedback Component 3 - Increase the ZR-CARITAS-66159CS-CDS / capacity to implement the IP Individual Consult Under Implement TF / A0924 Post Open 13,500.00 0.00 2018-10-31 2018-10-31 2018-12-19 2019-01-09 2019-02-13 2019-08-12 PF Sauvegardes KANANGA LC development activities a ant Selection ation nd consolidate feedback Page 1 Component 3 - Increase the ZR-CARITAS-66159-CS-CDS / capacity to implement the IP Individual Consult TF / A0924 Post Open 22,500.00 0.00 Signed 2018-10-31 2019-10-01 2018-12-19 2023-06-04 2019-01-09 2023-06-06 2019-02-13 2019-08-12 PF Sauvegardes MBUJIMAYI LC development activities a ant Selection nd consolidate feedback Component 3 - Increase the ZR-CARITAS-83607-CS-INDV capacity to implement the IP Individual Consult Under Implement TF / A0924 Post Open 72,000.00 0.00 2018-10-25 2018-10-25 2018-12-13 2019-01-03 2019-02-07 2019-08-06 / Expert Sauvegardes LC development activities a ant Selection ation nd consolidate feedback Component 3 - Increase the ZR-CARITAS-66156-CS-CDS / capacity to implement the IP Individual Consult TF / A0924 Post Open 18,000.00 0.00 Canceled 2018-10-31 2018-12-19 2019-01-09 2019-02-13 2019-08-12 PF sauvegardes INONGO LC development activities a ant Selection nd consolidate feedback ZR-CARITAS-122805-CS-CDS Component 1 - Reinforce the / Salaire expert sauvegarde e participation of the IPLC in fo Individual Consult nv. et sociale et mission suivi TF / A0924 Post Limited 126,000.00 0.00 Canceled 2019-08-08 2019-08-13 2019-09-03 2019-10-08 2020-04-05 rest and land management ant Selection sauvegarde (respect des cad processes related to REDD+ res de gestion environnemen tale et sociale ZR-CARITAS-62547-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as BUKAVU sur l'Alphabétisat TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-06-22 2020-07-24 2020-07-02 2020-08-03 2020-09-05 2020-08-14 2021-03-04 rest and land management ion Dio BUKAVU, Territoire de processes related to REDD+ KALEHE . Component 1 - Reinforce the ZR-CARITAS-49616-CS-CDS / participation of the IPLC in fo Alphabétisation Dio KANANG TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2019-07-16 2020-07-24 2019-07-26 2020-08-03 2019-09-29 2020-08-25 2020-03-27 rest and land management A, Territoire de DIMBELENGE processes related to REDD+ ZR-CARITAS-62538-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as diocese de MWEKA pour l' TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-06-22 2020-07-24 2020-07-02 2020-08-03 2020-09-05 2020-08-21 2021-03-04 rest and land management éducation de base et l'alphab processes related to REDD+ étisation territoire MWEKA ZR-CARITAS-62540-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as diocese d'INONGO, territoi TF / A0924 Post Direct Selection Direct 18,000.00 18,000.00 Signed 2020-06-25 2020-07-24 2020-07-05 2020-08-06 2020-09-08 2020-08-11 2021-03-07 rest and land management re de KIRI, OSWE et INONGO processes related to REDD+ pour l'éducation de base et l' alphabétisation . ZR-CARITAS-62543-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as diocese d'ISANGI, territoir TF / A0924 Post Direct Selection Direct 12,000.00 12,000.00 Signed 2020-07-20 2020-07-24 2020-07-30 2020-07-27 2020-10-03 2020-08-11 2021-04-01 rest and land management e de YAHUMA et OPALA pour processes related to REDD+ l'éducation de base et l'alpha bétisation ZR-CARITAS-62546-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-07-31 2020-07-24 2020-08-10 2020-08-06 2020-10-14 2020-08-12 2021-04-12 as diocese de MBANDAKA BI rest and land management KORO, territoire de BIKORO processes related to REDD+ Component 1 - Reinforce the ZR-CARITAS-83577-CS-CDS / participation of the IPLC in fo Alphabétisation Dio WAMBA - TF / A0924 Post Direct Selection Direct 12,000.00 12,000.00 Signed 2020-06-26 2020-07-24 2020-07-06 2020-08-03 2020-09-09 2020-08-11 2021-03-08 rest and land management MAMBASA ET BAFWASENDE processes related to REDD+ ZR-CARITAS-175241-CS-CDS Component 3 - Increase the / Renouvelement de contrat capacity to implement the IP avec REPALEF avec les opéra TF / A0924 Post Direct Selection Direct 120,950.00 0.00 Signed 2020-07-27 2016-07-01 2020-08-06 2016-07-11 2020-10-10 2021-04-08 LC development activities a teurs pour le suivi de satifact nd consolidate feedback ion et gestion des plainte 20 20 2022 ZR-CARITAS-62460-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as diocese de KABINDA pour TF / A0924 Post Direct Selection Direct 18,000.00 18,000.00 Signed 2020-06-17 2021-03-17 2020-06-27 2020-07-27 2020-09-15 2020-08-21 2021-03-14 rest and land management l'alphabétisation , Territoire K processes related to REDD+ ABINDA, LUBAO et LUSAMBO ZR-CARITAS-185697-CS-CDS / Contractualisation avec l'O NG FONDATION NSELALA pou Component 2 - Support com r valorisation des initiatives l TF / A0924 munity-based sustainable fo Post Direct Selection Direct 61,000.00 61,000.00 Signed 2020-08-10 2021-03-18 2020-08-20 2020-08-24 2020-09-15 2020-11-11 2021-03-14 ocales des plantations d'arbr rest and land management es dans le secteur entre LUK ENI - LOKORO , Territoire de 0shwe ZR-CARITAS-185700-CS-CDS / Contractualisation avec l'O Component 2 - Support com NG EQUIPE MIKA pour la valo TF / A0924 munity-based sustainable fo Post Direct Selection Direct 61,000.00 66,077.00 Signed 2020-08-10 2021-03-18 2020-08-20 2020-08-24 2020-09-15 2020-11-03 2021-03-14 risation des initiatives locales rest and land management des plantations d'arbres dans le secteur de Penzwa, Territo ire de Kiri ZR-CARITAS-175248-CS-CDS / Renouvelement de contrat Component 1 - Reinforce the avec LINAPYCO pour la Colle participation of the IPLC in fo Under Implement TF / A0924 Post Direct Selection Direct 120,000.00 0.00 2020-07-13 2020-07-13 2020-07-23 2020-07-23 2020-09-26 2021-03-25 cte des données sur les terre rest and land management ation s des PA pour la reconnaissa processes related to REDD+ nce légale et la sécurisation des terres ZR-CARITAS-62535-CS-CDS / Contractualisation avec Carit Component 1 - Reinforce the as diocese de MUJIMAYI , terri participation of the IPLC in fo toire de LUPATAPATA Les Les TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-06-29 2021-03-17 2020-07-09 2020-07-27 2020-09-15 2020-08-21 2021-03-14 rest and land management justificatifs techniques ( note processes related to REDD+ s méthodologiques et cv des alphabétiseurs vous parviend rons par mail. ZR-CARITAS-185701-CS-CDS / Contractualisation avec le C entre National d'appui au Dé veloppement et à la participa Component 2 - Support com tion populaire (CENEDEP) po TF / A0924 munity-based sustainable fo Post Direct Selection Direct 66,000.00 0.00 Canceled 2020-08-10 2020-08-20 2020-09-15 2021-03-14 ur l'amélioration des capacit rest and land management és de 280 ménages PA et CO LO à planter et entretenir les arbres de la forêt MOBOKON DA secteur INONGO ZR-CARITAS-62464-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as diocese de KOLE pour l'éd TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-09-21 2021-03-16 2020-10-01 2020-07-27 2021-11-22 2020-08-21 2022-02-20 rest and land management ucation de base et l'alphabéti processes related to REDD+ sation des PA et COLO Territo ire de DEKESE Page 2 ZR-CARITAS-189907-CS-CDS Component 1 - Reinforce the / Contractualisation avec l'O participation of the IPLC in fo NG CENADEP pour l'élevage TF / A0924 Post Direct Selection Direct 65,000.00 65,416.00 Signed 2020-09-21 2021-03-18 2020-10-01 2020-08-26 2020-12-05 2020-11-06 2021-06-03 rest and land management des porcs à MOMBOKONDA, processes related to REDD+ dans le Territoire d’INONGO ZR-CARITAS-185690-CS-CDS / Contractualisation avec l'O NG Programme d'intégration Component 1 - Reinforce the et du développement des pe participation of the IPLC in fo uples pygmées (PIDP) pour l' TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Signed 2020-09-15 2020-09-08 2020-09-25 2021-09-18 2020-10-21 2021-04-19 rest and land management éducation de base et l'alphab processes related to REDD+ étisation aux peuples autoch tones (PA ) et aux communa utés locales (COLO) pour le T erritoire de Walikale. ZR-CARITAS-62537-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-09-15 2021-03-17 2020-09-25 2020-07-27 2020-12-09 2020-08-21 2021-06-07 as de KISANGANI pour l'éduc rest and land management ation de base et l'alphabétisa processes related to REDD+ tion ZR-CARITAS-62539-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as diocese de TSHUMBE pour TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-09-15 2020-07-10 2020-09-25 2020-07-27 2020-10-28 2020-08-21 2021-04-26 rest and land management l'éducation de base et l'alpha processes related to REDD+ bétisation Territoire de LUBE FU ZR-CARITAS-154570-CS-CDS Component 2 - Support com / Contractualisation avec AN TF / A0924 munity-based sustainable fo Post Direct Selection Direct 80,000.00 0.00 Canceled 2020-07-21 2020-07-31 2020-10-04 2021-04-02 APAC pour l'organisation de r rest and land management éunions avec les peules auto chtones ZR-CARITAS-175245-CS-CDS / Avenant avec ANAPAC pour Component 2 - Support com suivi des dossiers de deman TF / A0924 munity-based sustainable fo Post Direct Selection Direct 12,000.00 0.00 Canceled 2020-07-27 2020-08-06 2020-10-10 2021-04-08 de auprès du Ministère de l'e rest and land management nvironnement et du Gouvern ement ZR-CARITAS-175244-CS-CDS / Renouvellement contrat AN APAC pour organiser des ass Component 2 - Support com emblées communautaires et TF / A0924 munity-based sustainable fo Post Direct Selection Direct 285,000.00 0.00 Canceled 2020-07-21 2020-07-21 2020-07-31 2020-07-31 2020-10-04 2021-04-02 réunions consultatives, d'ide rest and land management ntification, prospection des si tes à : Walikale, Bikoro et fin alisation dossier Mweka, Kiri et Mambasa ZR-CARITAS-196411-CS-CDS Component 1 - Reinforce the / Contractualisation avec DG participation of the IPLC in fo PA pour Suivi des loi au Parle TF / A0924 Post Direct Selection Direct 25,500.00 0.00 Signed 2020-09-28 2020-09-28 2020-10-08 2020-09-08 2020-12-12 2021-06-10 rest and land management ment et lutte contre la discri processes related to REDD+ mination pour les PA ZR-CARITAS-62578-CS-CDS / DIPED: Opérateur pour acco mpagner les communautés d Component 2 - Support com e Walikale dans l'identificatio TF / A0924 munity-based sustainable fo Post Direct Selection Direct 5,800.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 n des idées des microprojets rest and land management et des Opérateurs locaux d'a ppui aux communautés -Com posante 2.a.1 - Consultant ZR-CARITAS-62576-CS-CDS / UEFA: Opérateur pour accom pagner les communautés de Component 2 - Support com Kalehe dans l'identification d TF / A0924 munity-based sustainable fo Post Direct Selection Direct 5,800.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 es idées des microprojets et rest and land management des Opérateurs locaux d'app ui aux communautés -Compo sante 2.a.1 - Consultant ZR-CARITAS-49316-CS-CDS / CAIF- Opérateur pour accom Component 2 - Support com pagner les communautés (m TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,900.00 0.00 Canceled 2018-03-01 2018-03-11 2018-05-15 2018-11-11 icroprojets et des Opérateurs rest and land management locaux d'appui aux communa utés Lubao et Lubefu ZR-CARITAS-62579-CS-CDS / FECOFA: Opérateur pour acc ompagner les communautés Component 2 - Support com de Kabinda et Lusambo dans TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,900.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 l'identification des idées des rest and land management microprojets et des Opérateu rs locaux d'appui aux commu nautés -Composante 2.a.1 - Consultant ZR-CARITAS-62575-CS-CDS / GTF: Opérateur pour accomp agner les communautés de Y Component 2 - Support com ahuma et Opala dans l'identif TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 ication des idées des micropr rest and land management ojets et des Opérateurs locau x d'appui aux communautés -Composante 2.a.1 - Consult ant ZR-CARITAS-62572-CS-CDS / EPAP/RDC: Opérateur pour a ccompagner les communaut Component 2 - Support com és de Lupatapata et Dimbele TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,350.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 nge dans l'identification des i rest and land management dées des microprojets et des Opérateurs locaux d'appui au x communautés -Composant e 2.a.1 - Consultant ZR-CARITAS-62582-CS-CDS / APSVR:Opérateur pour acco mpagner les communautés d Component 2 - Support com e Mweka et Dekese dans l'id TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,700.00 0.00 Canceled 2018-05-14 2019-10-30 2018-05-24 2018-07-28 2019-01-24 entification des idées des mi rest and land management croprojets et des Opérateurs locaux d'appui aux communa utés -Composante 2.a.1 - Co nsultant ZR-CARITAS-62581-CS-CDS / OCEAN: Opérateur pour acco mpagner les communautés d Component 2 - Support com e Banalia, Bafwasende et Ma TF / A0924 munity-based sustainable fo Post Direct Selection Direct 12,950.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 mbasa dans l'identification d rest and land management es idées des microprojets et des Opérateurs locaux d'app ui aux communautés -Compo sante 2.a.1 - Consultant Page 3 ZR-CARITAS-49123-CS-CDS / Consultant Kasongo Kabusa Component 2 - Support com Raphael, chargé d'identificati TF / A0924 munity-based sustainable fo Post Direct Selection Direct 8,000.00 0.00 Canceled 2018-02-05 2018-02-15 2018-04-21 2018-10-18 on des expériences de mise rest and land management en œuvre des microprojets c ommunautaires ZR-CARITAS-125538-CS-CDS Component 1 - Reinforce the / Contrat REPEQ identificatio participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 10,000.00 0.00 Canceled 2019-08-31 2019-09-10 2019-11-14 2020-05-12 n des besoins en renforceme rest and land management nt des capacités processes related to REDD+ ZR-CARITAS-62580-CS-CDS / DIPY: Opérateur pour accom pagner les communautés d'I Component 2 - Support com nongo et Oshwe dans l'identi TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 fication des idées des microp rest and land management rojets et des Opérateurs loca ux d'appui aux communautés -Composante 2.a.1 - Consult ant ZR-CARITAS-49610-CS-CDS / -CIDB: Opérateur d'identificat Component 2 - Support com ion des micros projets et ON TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,600.00 0.00 Canceled 2018-03-01 2018-03-11 2018-05-15 2018-11-11 G locales ( Bikoro et Kiri) AN rest and land management O obtenu 25/09/2017 Component 1 - Reinforce the ZR-CARITAS-122741-CS-CDS participation of the IPLC in fo Individual Consult / Evaluation à mis parcours s TF / A0924 Post Limited 17,500.00 0.00 Canceled 2019-08-10 2019-08-15 2019-09-05 2019-10-10 2020-04-07 rest and land management ant Selection uivi processes related to REDD+ ZR-CARITAS-253078-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocésaine de M participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Under Review 2021-12-08 2020-09-08 2021-12-18 2022-02-21 2022-06-21 BANDAKA pour l'éducation d rest and land management e base et l'alphabétisation, T processes related to REDD+ erritoire de BIKORO composa nte 1b ZR-CARITAS-253085-CS-CDS / Renouvellement avec ANAP AC pour appui à l'élaboration des cartes des droits et d'aff Component 2 - Support com ectation des terres, plans de TF / A0924 munity-based sustainable fo Post Direct Selection Direct 113,500.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2021-12-18 2022-02-21 2022-06-21 sondage, Dépôt des dossiers rest and land management de demande de CFCL, Enquê te de vacance des terres, Ob tention de CFCL à Mweka, Bi ko, Walikale. composante 2b ZR-CARITAS-253091-CS-CDS Component 3 - Increase the / Renouvellement de Contrat capacity to implement the IP avec REPALEF pour le suivi d TF / A0924 Post Direct Selection Direct 40,500.00 0.00 Signed 2021-12-08 2021-12-08 2021-12-18 2021-12-18 2022-02-21 2022-06-21 LC development activities a e satisfaction et gestion des nd consolidate feedback plaintes. composante 3b ZR-CARITAS-253093-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec (CENADEP) pour l'améli participation of the IPLC in fo oration des capacités de 280 TF / A0924 Post Direct Selection Direct 38,045.00 0.00 Signed 2021-12-08 2022-02-28 2021-12-18 2022-03-10 2022-02-21 2022-06-21 rest and land management ménages PA et COLO à plant processes related to REDD+ er et entretenir les arbres de la forêt MOBOKONDA secteur INONGO. composante 2a ZR-CARITAS-253094-CS-CDS / Renouvellement contrat av ec l'ONG ADGRN pour le pro Component 2 - Support com jet de plantation d’arbres su TF / A0924 munity-based sustainable fo Post Direct Selection Direct 71,250.00 73,773.50 Signed 2021-12-08 2021-12-06 2021-12-18 2022-01-31 2022-02-21 2022-01-25 2022-03-05 r 45 ha et de promotion de l’ rest and land management élevage et de l'apiculture da ns les villages de Milela, Toko meka et Tshintu mwanza, Te rritoire de Lupatapata. comp osante 2a ZR-CARITAS-253072-CS-CDS / Renouvellement contrat Ca ritas diocésaine Kabinda po Component 1 - Reinforce the ur le projet d'appui à la prote participation of the IPLC in fo ction du forestière par l'agro TF / A0924 Post Direct Selection Direct 73,960.00 0.00 Signed 2021-12-08 2022-01-14 2021-12-18 2022-01-31 2022-03-08 2022-07-06 rest and land management foresterie et en faveur des p processes related to REDD+ euples autochtones pour les villages de Tulimbi, Ebaala et Kashoko, Territoire de Kabind a composante 2a ZR-CARITAS-253097-CS-CDS / Renouvellement de contrat Component 2 - Support com avec l'ONG SPFA pour le proj TF / A0924 munity-based sustainable fo Post Direct Selection Direct 22,680.00 0.00 Signed 2021-09-30 2021-09-30 2021-10-10 2021-10-10 2021-12-14 2022-04-13 et d'appui à l'agroforesterie e rest and land management t à la pisciculture dans les vill ages Moboyo, Mboli et Iyand a, dans le Territoire de Bikor o ZR-CARITAS-253098-CS-CDS / Renouvellement contrat UE Component 2 - Support com FA projet d'amélioration des TF / A0924 munity-based sustainable fo Post Direct Selection Direct 48,760.00 0.00 Signed 2021-12-08 2021-07-01 2021-12-18 2023-01-01 2022-02-21 2022-06-21 écosystèmes forestiers avec l rest and land management a plantation d'arbres de 17 g roupements du Territoire de Kalehe, composante 2b ZR-CARITAS-253067-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocésaine Kisa participation of the IPLC in fo ngani pour donner l'Educatio TF / A0924 Post Direct Selection Direct 3,000.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2022-03-03 2022-07-01 rest and land management n de base et alphabétisation processes related to REDD+ aux PA et Communautés loca les Territoire BANALIA comp osante 1b ZR-CARITAS-253086-CS-CDS / Renouvellement de contrat avec l'ONG FONDATION NSEL Component 2 - Support com ALA pour valorisation des init TF / A0924 munity-based sustainable fo Post Direct Selection Direct 30,761.00 0.00 Signed 2021-12-08 2021-12-08 2021-12-18 2022-02-07 2022-01-13 2022-05-13 iatives locales des plantation rest and land management s d'arbres dans le secteur en tre LUKENI - LOKORO, Territoi re de 0shwe. composante 2a ZR-CARITAS-253090-CS-CDS / Renouvellement de Contrat Component 1 - Reinforce the avec LINAPYCO pour la Colle participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 61,790.00 0.00 Signed 2021-12-08 2021-12-08 2021-12-18 2021-12-18 2022-02-21 2022-06-21 cte des données sur les terre rest and land management s des PA pour la reconnaissa processes related to REDD+ nce légale et la sécurisation des terres. composante 1a Page 4 ZR-CARITAS-253096-CS-CDS / Renouvellement Contrat av ec l'ONG Programme d'intég Component 1 - Reinforce the ration et du développement participation of the IPLC in fo des peuples pygmées (PIDP) TF / A0924 Post Direct Selection Direct 42,300.00 0.00 Signed 2021-12-08 2016-07-01 2021-12-18 2022-12-09 2022-02-21 2022-06-21 rest and land management pour le projet d'amélioration processes related to REDD+ des capacités de production agropastorale des ménages autochtones pygmées dans l e Territoire de Walikale. com pos 2a ZR-CARITAS-253099-CS-CDS / Renouvellement contrat DG Component 1 - Reinforce the PA pour soutien à la finalisati participation of the IPLC in fo on de 4 concessions : Bondo, TF / A0924 Post Direct Selection Direct 106,636.00 0.00 Signed 2021-09-30 2017-07-17 2021-10-10 2017-07-27 2021-12-14 2022-04-13 rest and land management Kombe, Mitshia, Tongonwena processes related to REDD+ forestières des communauté s locales de TSHIEFU / Territo ire de Dimbelenge. composa nte 2b ZR-CARITAS-253095-CS-CDS / Contractualisation avec CA RITAS Kabinda pour le pro d Component 2 - Support com 'appui à la protection du cou TF / A0924 munity-based sustainable fo Post Direct Selection Direct 71,359.00 0.00 Signed 2022-01-27 2022-01-27 2022-02-06 2022-02-18 2022-04-12 2022-08-10 ver forestier par l'agroforeste rest and land management rie, la porciculture et la picic ulture en faveur des peuples autochtones des villages d'E baala et Kangulube, Territoir e de Lubao. c 2a ZR-CARITAS-253087-CS-CDS / Renouvellement de contrat avec l'ONG EQUIPE MIKA pou Component 2 - Support com r la valorisation des initiative TF / A0924 munity-based sustainable fo Post Direct Selection Direct 12,500.00 0.00 Signed 2021-12-08 2021-12-08 2021-12-18 2021-12-18 2022-01-13 2022-05-13 s locales des plantations d'ar rest and land management bres dans le secteur de Penz wa, Territoire de Kiri. compos ante 2a ZR-CARITAS-280706-CS-CDS / CAIF- Opérateur pour acco Component 2 - Support com mpagner les communautés ( TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-24 2022-12-21 microprojets et des Opérateu rest and land management rs locaux d'appui aux commu nautés Lubao et Lubefu ZR-CARITAS-280677-CS-CDS / EPAP/RDC: Opérateur pour accompagner les communau Component 2 - Support com tés de Lupatapata et Dimbel TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-24 2022-12-21 enge dans l'identification des rest and land management idées des microprojets et des Opérateurs locaux d'appui au x communautés -Composant e 2.a.1 - Consultant ZR-CARITAS-280720-CS-CDS / Recrutement d'un opérateu r spécialisé, chargé d'organis er des assemblées communa Component 2 - Support com utaires et d'accompagner les TF / A0924 munity-based sustainable fo Post Direct Selection Direct 80,000.00 0.00 Canceled 2022-04-10 2022-04-20 2022-06-24 2022-12-21 PA et communautés locales d rest and land management ans le processus de la reconn aissance formelle de leur con cession forestière et de leurs aires de conservation ZR-CARITAS-280674-CS-CDS / APSVR: Opérateur pour acc ompagner les communautés Component 2 - Support com de Mweka et Dekese dans l'i TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-24 2022-12-21 dentification des idées des m rest and land management icroprojets et des Opérateurs locaux d'appui aux communa utés -Composante 2.a.1 - Co nsultant ZR-CARITAS-280683-CS-CDS / OCEAN: Opérateur pour acc ompagner les communautés Component 2 - Support com de Banalia, Bafwasende et M TF / A0924 munity-based sustainable fo Post Direct Selection Direct 12,950.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-24 2022-12-21 ambasa dans l'identification rest and land management des idées des microprojets et des Opérateurs locaux d'app ui aux communautés -Compo sante 2.a.1 - Consultant ZR-CARITAS-280711-CS-CDS / DIPY: Opérateur pour acco mpagner les communautés d Component 2 - Support com 'Inongo et Oshwe dans l'ident TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-24 2022-12-21 ification des idées des micro rest and land management projets et des Opérateurs loc aux d'appui aux communaut és -Composante 2.a.1 – Cons ultant ZR-CARITAS-281043-CS-CDS / Avenant avec ANAPAC pour Component 2 - Support com suivi des dossiers de demand TF / A0924 munity-based sustainable fo Post Direct Selection Direct 27,000.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-12-07 2022-06-24 2022-12-21 e auprès du Ministère de l'en rest and land management vironnement et du Gouverne ment ZR-CARITAS-280020-CS-CDS Component 2 - Support com / Identification des idées des TF / A0924 munity-based sustainable fo Post Direct Selection Direct 5,800.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-24 2022-12-21 micro-projets dans le territoir rest and land management e de Walikale ZR-CARITAS-280023-CS-CDS / UEFA: Opérateur pour acco mpagner les communautés d Component 2 - Support com e Kalehe dans l'identification TF / A0924 munity-based sustainable fo Post Direct Selection Direct 5,800.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-10 2022-12-07 des idées des microprojets et rest and land management des Opérateurs locaux d'app ui aux communautés -Compo sante 2.a.1 - Consultant ZR-CARITAS-280659-CS-CDS / FECOFA: Opérateur pour ac compagner les communauté Component 2 - Support com s de Kabinda et Lusambo à l'i TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Signed 2022-04-10 2022-04-20 2022-04-20 2022-10-12 2022-06-24 2022-12-21 dentification des idées des m rest and land management icroprojets et des Opérateurs locaux d'appui aux communa utés -Composante 2.a.1 - Co nsultant ZR-CARITAS-280688-CS-CDS / Contrat REPEQ renforcemen Component 1 - Reinforce the t des capacités dans le cadre participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 5,000.00 0.00 Signed 2022-04-10 2023-04-10 2022-04-20 2023-06-18 2022-06-24 2022-12-21 du plan d’action pour le déve rest and land management loppement et la promotion d processes related to REDD+ es droits des peuples autocht ones en RDC Page 5 Component 1 - Reinforce the ZR-CARITAS-280724-CS-CDS participation of the IPLC in fo / Evaluation externe à mi-par TF / A0924 Post Direct Selection Direct 20,000.00 0.00 Signed 2022-04-10 2023-06-12 2022-04-20 2023-06-18 2022-06-24 2022-12-21 rest and land management cours du projet PACDF processes related to REDD+ ZR-CARITAS-286914-CS-CDS / GTF: Opérateur pour accom pagner les communautés de Component 2 - Support com Yahuma et Opala dans l'ident Under Implement TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 2022-04-10 2023-06-12 2022-04-20 2023-06-18 2022-06-24 2022-12-21 ification des idées des micro ation rest and land management projets et des Opérateurs loc aux d'appui aux communaut és -Composante 2.a.1 – Cons ultant Component 1 - Reinforce the ZR-CARITAS-279788-CS-CQS participation of the IPLC in fo / Contractualisation avec le c TF / A0924 Post Direct Selection Direct 30,000.00 0.00 Canceled 2022-04-10 2022-04-20 2022-06-24 2022-12-21 rest and land management onsultant DGPA processes related to REDD+ ZR-CARITAS-281039-CS-CDS / ANAPAC: accompagner les PA et les COLO dans le proce ssus de la reconnaissance for Component 2 - Support com melle de leurs concessions fo TF / A0924 munity-based sustainable fo Post Direct Selection Direct 250,000.00 0.00 Signed 2022-05-20 2022-05-20 2022-05-30 2022-05-30 2022-08-03 2023-01-30 restières et des aires de cons rest and land management ervation et patrimoine autoc htone et communautaires da ns les sites de Walikale, Bikor o, Kiri, Mambasa et Mweka ZR-CARITAS-280041-CS-CDS / FECOFA: Opérateur pour ac compagner les communauté Component 2 - Support com s de Kabinda et Lusambo dan TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Canceled 2022-04-10 2022-04-10 2022-04-20 2022-06-24 2022-12-21 s l'identification des idées de rest and land management s microprojets et des Opérat eurs locaux d'appui aux com munautés -Composante 2.a.1 - Consultant ZR-CARITAS-281031-CS-CDS / Renouvèlement de contrat Component 1 - Reinforce the avec LINAPYCO pour la Collec participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 120,000.00 0.00 Canceled 2022-04-10 2022-04-20 2022-06-24 2022-12-21 te des données sur les terres rest and land management des PA pour la reconnaissanc processes related to REDD+ e légale et la sécurisation de s terres ZR-CARITAS-253083-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocésaine de M participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-12-08 2020-09-08 2021-12-18 2022-02-21 2022-06-21 WEKA pour l'éducation de ba rest and land management se et l'alphabétisation, Territ processes related to REDD+ oire MWEKA composante 1b ZR-CARITAS-300093-CS-CQS / POINT FOCAL: Suivi rapproc Component 2 - Support com Individual Consult Under Implement hé environnemental et social TF / A0924 munity-based sustainable fo Post Direct 3,000.00 0.00 2022-06-30 2022-10-11 2022-07-10 2022-07-31 2022-09-04 2023-03-03 ant Selection ation des activités des microprojet rest and land management s dans le territoire de Walikal e ZR-CARITAS-300099-CS-CQS / POINT FOCAL: Suivi rapproc Component 2 - Support com Individual Consult hé environnemental et social TF / A0924 munity-based sustainable fo Post Direct 3,000.00 0.00 Canceled 2022-06-30 2022-10-11 2022-07-10 2022-07-31 2022-09-04 2023-03-03 ant Selection des activités des microprojet rest and land management s dans le territoire de Kahele ZR-CARITAS-300107-CS-CQS / POINT FOCAL: Suivi rapproc hé environnemental et social Component 2 - Support com Individual Consult Under Implement des activités à Mbuji-Mayi da TF / A0924 munity-based sustainable fo Post Direct 9,000.00 0.00 2022-06-30 2022-10-11 2022-07-10 2022-07-31 2022-09-04 2023-03-03 ant Selection ation ns les territoires de Lupatapa rest and land management ta (Tshintumuanza, Tokomek a et Milela), Kabinda (Ebala - Tulimbi) et Lubao (Kangulube ) ZR-CARITAS-319901-CS-CDS Component 3 - Increase the / ADDEC: Recrutement d'une capacity to implement the IP ONG d'appui à la mise en œu TF / A5550 Post Direct Selection Direct - National 99,373.50 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-21 2022-12-25 2023-06-23 LC development activities a vre de microprojet à Kabala, nd consolidate feedback dans le territoire de Dimbele nge ZR-CARITAS-319916-CS-CDS / UNION POUR LE DEVELOPPE MENT DES MINORITES EKON Component 2 - Support com DA: Recrutement d'une ONG TF / A5550 munity-based sustainable fo Post Direct Selection Direct - National 108,749.00 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-22 2022-12-25 2023-06-23 d'appui à la mise en œuvre d rest and land management e microprojet à MPANGOLA, dans le territoire de LUSAMB O ZR-CARITAS-319961-CS-CDS / FODI: Recrutement d'une O Component 2 - Support com NG d'appui à la mise en œuv TF / A5550 munity-based sustainable fo Post Direct Selection Direct - National 104,749.00 0.00 Signed 2022-10-11 2022-10-11 2022-10-20 2022-10-21 2022-12-24 2023-06-22 re de microprojet dans le vill rest and land management age d'Itunga, territoire de Lu befu ZR-CARITAS-319986-CS-CDS / PCF: Recrutement d'une ON Component 1 - Reinforce the G d'appui à la mise en œuvre participation of the IPLC in fo TF / A5550 Post Direct Selection Direct - National 96,509.50 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-21 2022-12-25 2023-06-23 de microprojet à MANGBAUT rest and land management U, KILONDE, et BANANA GITE processes related to REDD+ dans le territoire de MAMBAS A ZR-CARITAS-319996-CS-CDS / CARITAS KABINDA: Recrute Component 2 - Support com ment d'une structure d'appui TF / A5550 munity-based sustainable fo Post Direct Selection Direct - National 72,509.00 0.00 Canceled 2022-10-11 2022-10-11 2022-10-21 2022-12-25 2023-06-23 à la mise en œuvre de micro rest and land management projet à TSHINTU MWANZA, MILELA et TOKOMEKA dans le territoire de LUPATAPATA ZR-CARITAS-320000-CS-CDS / ACODELPY: Recrutement d' Component 2 - Support com une ONG d'appui à la mise e TF / A5550 munity-based sustainable fo Post Direct Selection Direct - National 99,948.50 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-11 2022-12-25 2023-06-23 n œuvre de microprojet à BI rest and land management MELI, dans le territoire de BA FWASENDE Page 6 ZR-CARITAS-300080-CS-CDS / LIMA: Promotion des initiati ves de restauration de la forê t, développement des alterna Component 2 - Support com tives économiques compensa TF / A0924 munity-based sustainable fo Post Direct Selection Direct - National 111,383.50 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-21 2022-12-25 2023-06-23 toires aux efforts de la forêt rest and land management et contribution à la cohésion sociale entre les PA et les CO LO à Bomili dans le territoire de Bafwasende. Com 2a ZR-CARITAS-300070-CS-CDS / CARITAS ISANGI: Contributi on à la réduction de la pressi on sur la forêt par l'améliorat Component 2 - Support com ion de la production, commer TF / A0924 munity-based sustainable fo Post Direct Selection Direct - National 116,220.00 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-12-12 2022-12-25 2023-06-23 cialisation du riz, du manioc, rest and land management du miel et l'artisanat en fave ur des PA et des COLO à Yalo nde et Yasamola dans le terri toire de Yahuma. C 2a ZR-CARITAS-300059-CS-CDS / CARITAS ISANGI: Contributi on à la restauration de la for Component 2 - Support com êt, la croissance économique TF / A0924 munity-based sustainable fo Post Direct Selection Direct - National 83,056.00 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-21 2022-12-25 2023-06-23 de 150 ménages cibles et en rest and land management même temps à l'encouragem ent de la cohésion sociale de s PA et CL à Lieke Lesole dan s le territoire d'Opala. Compo sante 2a ZR-CARITAS-300115-CS-CDS / LIMA: Promotion des initiati ves de restauration de la forê t, développement des alterna Component 2 - Support com tives économiques compensa TF / A0924 munity-based sustainable fo Post Direct Selection Direct - National 111,383.50 0.00 Canceled 2022-10-11 2022-10-21 2022-12-25 2023-06-23 toires aux efforts de la forêt rest and land management et contribution à la cohésion sociale entre les PA et les CO LO à Bangbo dans le territoir e de Banalia. Comp 2a ZR-CARITAS-280716-CS-CDS / Consultant Kasongo Kabusa Component 2 - Support com Individual Consult Raphael, Chargé d’identificat TF / A0924 munity-based sustainable fo Post Direct - National 8,000.00 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-22 2022-11-11 2022-11-11 2022-12-16 2023-06-14 ant Selection ion des expériences de mise rest and land management en œuvre des microprojets c ommunautaires ZR-CARITAS-320534-CS-CDS / CARITAS KOLE: Recrutemen Component 2 - Support com t d'une ONG d'appui à la mis TF / A5550 munity-based sustainable fo Post Direct Selection Direct - National 99,603.00 0.00 Signed 2022-10-12 2022-11-21 2022-10-22 2022-12-01 2022-12-26 2023-06-24 e en œuvre de microprojet à rest and land management ITUNGA dans le territoire de DEKESE. Comp 2a ZR-CARITAS-320537-CS-CDS / CEDAP: Recrutement d'une ONG locale pour la mise en œuvre du projet de restaurat Component 2 - Support com Under Implement ion de la foret d'Itungampen TF / A5550 munity-based sustainable fo Post Direct Selection Direct - National 105,094.00 0.00 2022-10-12 2022-11-21 2022-10-22 2022-12-01 2022-12-26 2023-06-24 ation de à travers la plantation d'a rest and land management rbres et le développement de s alternatives économiques pour lutter contre la dégrada tion de la foret. Comp 2a ZR-CARITAS-320542-CS-IND V / POINT FOCAL: Recruteme Component 2 - Support com nt d'un consultant pour le sui Individual Consult TF / A5550 munity-based sustainable fo Post Direct - National 5,200.00 0.00 Signed 2022-10-12 2022-11-21 2022-10-22 2022-12-01 2022-11-12 2022-12-22 2022-12-17 2023-06-15 vi environnemental et social ant Selection rest and land management dans les territoires de BAFW ASENDE, YAHUMA, OPALA et BANALIA ZR-CARITAS-320547-CS-IND V / POINT FOCAL: Recruteme Component 2 - Support com Individual Consult nt d'un consultant pour le sui TF / A5550 munity-based sustainable fo Post Direct - National 1,000.00 0.00 Signed 2022-10-11 2022-11-21 2022-10-21 2022-11-26 2022-11-11 2022-12-17 2022-12-16 2023-06-14 ant Selection vi environnemental et social rest and land management dans le territoire de MAMBAS A ZR-CARITAS-320549-CS-IND V / POINT FOCAL: Recruteme Component 2 - Support com Individual Consult nt d'un consultant pour le sui TF / A5550 munity-based sustainable fo Post Direct - National 4,200.00 0.00 Signed 2022-10-12 2022-11-21 2022-10-22 2022-12-01 2022-11-12 2022-12-22 2022-12-17 2023-06-15 ant Selection vi environnemental et social rest and land management dans les territoires de MWEK A, DEKESE et DIMBELENGE ZR-CARITAS-320552-CS-IND V / POINT FOCAL: Recruteme Component 2 - Support com Individual Consult nt d'un consultant pour le sui TF / A5550 munity-based sustainable fo Post Direct - National 3,400.00 0.00 Signed 2022-10-12 2022-11-21 2022-10-22 2022-12-01 2022-11-12 2022-12-22 2022-12-17 2023-06-15 ant Selection vi environnemental et social rest and land management dans les territoires de LUSAM BO ET LUBEFU ZR-CARITAS-253070-CS-CDS / Renouvellement contrat Car Component 1 - Reinforce the itas Mbujimayi pour donner l' participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 5,400.00 0.00 Canceled 2021-12-08 2021-07-08 2021-12-18 2022-02-24 2022-06-24 éducation de base et alphab rest and land management étisation aux PA et communa processes related to REDD+ utés locales territoire de LUP ATAPATA composante 1b ZR-CARITAS-253063-CS-CDS / Renouvellement contrat av Component 1 - Reinforce the ec Caritas diocèse Kananga p participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2022-02-21 2022-06-21 our l'Education de base des P rest and land management A et communautés locales Te processes related to REDD+ rritoire de Dimbelenge comp 1b ZR-CARITAS-253084-CS-CDS Component 1 - Reinforce the / Renouvellement contrat av participation of the IPLC in fo ec Caritas diocésaine de WA TF / A0924 Post Direct Selection Direct 12,000.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2022-02-21 2022-06-21 rest and land management MBA Alphabétisation Dio WA processes related to REDD+ MBA - MAMBASA ET BAFWAS ENDE composante 1b ZR-CARITAS-253082-CS-CDS Component 1 - Reinforce the / Renouvellement de contrat participation of the IPLC in fo avec Caritas BUKAVU sur l'Al TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-12-08 2020-09-08 2021-12-18 2020-09-22 2022-02-21 2022-06-21 rest and land management phabétisation Dio BUKAVU, T processes related to REDD+ erritoire de KALEHE composa nte 1b ZR-CARITAS-253089-CS-CDS Component 1 - Reinforce the / Renouvellement de Contrat participation of the IPLC in fo avec DGPA pour Suivi des loi TF / A0924 Post Direct Selection Direct 30,000.00 0.00 Canceled 2021-12-08 2020-09-08 2021-12-18 2022-02-21 2022-06-21 rest and land management au Parlement et lutte contre l processes related to REDD+ a discrimination pour les PA. composante 1a Page 7 ZR-CARITAS-280035-CS-CDS / CAIF- Opérateur pour acco Component 2 - Support com mpagner les communautés à TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,900.00 0.00 Canceled 2022-04-10 2022-04-20 2022-06-24 2022-12-21 l’identification des micro-proj rest and land management ets pour les territoires de Lub ao et Lubefu ZR-CARITAS-253092-CS-CDS / Renouvellement de Contrat avec l'ONG Programme d'inté Component 1 - Reinforce the gration et du développement participation of the IPLC in fo des peuples pygmées (PIDP) TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-12-08 2020-09-08 2021-12-18 2022-01-13 2022-05-13 rest and land management pour l'éducation de base et l' processes related to REDD+ alphabétisation aux peuples autochtones (PA ) et aux com munautés locales (COLO) po ur le Territoire de Walikale. c 1b ZR-CARITAS-253073-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocésaine de d participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2022-05-31 2022-09-28 e KOLE pour l'éducation de b rest and land management ase et l'alphabétisation des P processes related to REDD+ A et COLO Territoire de DEKE SE composante 1b ZR-CARITAS-253088-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocèse d'ISANG participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 12,000.00 0.00 Canceled 2021-12-08 2021-12-27 2021-12-18 2022-01-15 2022-02-21 2022-06-21 I, territoire de YAHUMA et OP rest and land management ALA pour l'éducation de bas processes related to REDD+ e et l'alphabétisation. compo sante 1b ZR-CARITAS-280699-CS-CDS / Identification des idées des Component 2 - Support com microprojets et des organisat TF / A0924 munity-based sustainable fo Post Direct Selection Direct 5,900.00 0.00 Canceled 2022-04-10 2022-04-20 2022-06-24 2022-12-21 ions et site d'implémentation rest and land management du microprojet à Walikale ZR-CARITAS-253081-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocésaine de K participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 18,000.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2022-03-08 2022-07-06 ABINDA pour l'alphabétisatio rest and land management n , Territoire KABINDA, LUBA processes related to REDD+ O et LUSAMBO composante 1 b ZR-CARITAS-294564-CS-CQS Component 3 - Increase the / Recrutement d'un auditeur capacity to implement the IP Individual Consult externe pour la révision du m TF / A0924 Post Direct 3,000.00 0.00 Canceled 2022-06-24 2022-10-11 2022-07-04 2022-07-25 2022-08-29 2023-02-25 LC development activities a ant Selection anuel des procédures admini nd consolidate feedback stratives et financières du pr ojet PACDF ZR-CARITAS-242600-CS-IND Component 3 - Increase the V / Recrutement d'un consult capacity to implement the IP Individual Consult ant individuel pour la révisio TF / A0924 Post Limited 4,000.00 0.00 Canceled 2021-07-30 2021-08-04 2021-08-25 2021-09-29 2021-11-13 LC development activities a ant Selection n du manuel des procédures nd consolidate feedback administratives et financière s du projet PCDF ZR-CARITAS-362380-CS-CDS Component 3 - Increase the / Recrutement d'un Consulta capacity to implement the IP Individual Consult Direct - Internation nt International pour l'évalua TF / A0924 Post 10,000.00 0.00 Canceled 2023-05-30 2023-05-30 2023-06-09 2023-06-04 2023-06-30 2023-08-04 2024-01-31 LC development activities a ant Selection al tion final et la rédaction du r nd consolidate feedback apport d'achèvement du pro jet ZR-CARITAS-362377-CS-CDS Component 3 - Increase the / Recrutement d'un Consulta capacity to implement the IP Individual Consult Under Implement nt National pour l'appui à l'év TF / A0924 Post Direct - National 10,000.00 0.00 2023-05-30 2023-05-30 2023-06-09 2023-06-04 2023-06-30 2023-06-25 2023-08-04 2024-01-31 LC development activities a ant Selection ation aluation finale et à la rédacti nd consolidate feedback on du rapport d'achèvement du projet ZR-CARITAS-253079-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocésaine d'IN participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 18,000.00 0.00 Canceled 2021-12-08 2020-09-08 2021-12-18 2022-02-21 2022-06-21 ONGO, territoire de KIRI, OS rest and land management WE et INONGO pour l'éducat processes related to REDD+ ion de base et l'alphabétisati on. composante 1b ZR-CARITAS-253068-CS-CDS / Renouvellement contrat av Component 1 - Reinforce the ec Caritas diocésaine TSHUM participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2022-01-20 2022-05-20 BE pour Education de Base et rest and land management Alphabétisation aux PA et co processes related to REDD+ mmunautés locales territoire de LUBEFU composante 1b ZR-CARITAS-365668-CS-CDS / CIDB: Identification des idée Component 2 - Support com s des microprojets communa TF / A0924 munity-based sustainable fo Post Direct Selection Direct - National 9,800.00 0.00 Signed 2023-06-06 2023-06-12 2023-06-16 2023-06-18 2023-08-20 2024-02-16 utaires et des opérateurs loc rest and land management aux d'appui aux communaut és à Bikoro-Kiri ZR-CARITAS-365674-NC-DIR / OSAPY: Appuyer l'élaboratio n des cartes des terroirs com Component 1 - Reinforce the munautaires et des plans d'a participation of the IPLC in fo Under Implement TF / A0924 Post Direct Selection Direct - National 150,000.00 0.00 2023-06-12 2023-06-25 2023-06-22 2023-08-26 2024-02-22 ménagement et de gestion si rest and land management ation mplifiée des concessions fore processes related to REDD+ stières des COLO et des aires de patrimoine ou aires de co nservation des PA et des COL O Page 8 PROCUREMENT PLAN (Textual Part) Project information: Digital Sao Tome and Principe (P177158) Project Implementation Agency: AFAP Date of the Procurement Plan: March 3, 2022 Period covered by this Procurement Plan: March 3, 2022 – March 2, 2023. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used: When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations - Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables. PROCUREMENT Sao Tome and Principe : Digital Sao Tome and Principe PLAN General Information Country: Sao Tome and Principe 2022-03-09 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P177158 GPN Date: 2022-04-26 Project Name: Digital Sao Tome and Principe Loan / Credit No: IDA / V4030, IDA / E0730 Project Fiduciary and Administrative Agency Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned 01/W/DSTP/2023 / Obras de Request for Quota Request for Quota Single Stage - One E Pending Imp 2024-03-1 remodelação dos pisos 2 do IDA / V4030 Digital access Post Open - National tions (Non Bank-S 60,000.00 0.00 2023-07-23 2023-09-17 tions nvelope lementation 5 edifício da AGER PD) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 21/G/DSTP/2022 / Purchase Project management and co Request for Quota Single Stage - One E IDA / V4030 Post Open - National 65,000.00 0.00 Signed 2022-11-05 2022-12-31 2023-06-29 of IT equipment and furniture ordination tions nvelope for the PIU 01/G/DSTP/2023 / Aquisição de quatro veículos 4x4 para Housing and population cens Single Stage - One E Under Imple IDA / E0730 Post Request for Bids Open - National 200,000.00 0.00 2023-06-11 2023-06-23 2023-06-16 2023-06-23 2023-07-28 2023-08-27 2023-10-01 2024-03-29 o INE; um veiculo 4x4 para UI us nvelope mentation P e uma viatura ligeira para UIP na RAP. 22/G/DSTP/2022 / Aquisição de Mobiliario de Escritório e Single Stage - One E Pending Impl IDA / E0730 Digital access Post Request for Bids Open - National 370,000.00 0.00 2023-06-27 2023-07-02 2023-08-13 2023-09-12 2023-10-17 2024-04-14 Equipamentos informáticos p nvelope ementation ara AGER, DGRN, ANPDP, INE e UIP 02/G/DSTP/2023 / Aquisição Housing and population cens Single Stage - One E Pending Impl IDA / E0730 Post Request for Bids Open - National 454,500.00 0.00 2023-06-05 2023-06-10 2023-07-22 2023-08-21 2023-09-25 2023-11-27 de equipamentos informático us nvelope ementation para o INE NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 18/C/DSTP/2022 / Strengthe ning the regulatory capacity Quality And Cost- Open - Internationa IDA / V4030 Digital access Post 300,000.00 0.00 Signed 2022-06-23 2022-06-27 2022-07-14 2022-07-23 2022-08-27 2022-11-21 2022-09-24 2023-01-16 2022-10-24 2023-03-24 2022-11-28 2023-04-05 2023-01-02 2024-01-02 of theGeneral Regulation of S Based Selection l ão Tomé and Príncipe (AGER) 26/C/DSTP/2023 / Transactio nal Advisory Services for a Te Quality And Cost- Open - Internationa Under Implement IDA / V4030 Digital access Post 800,000.00 0.00 2023-01-31 2023-04-11 2023-02-21 2023-02-01 2023-04-06 2023-04-12 2023-05-04 2023-06-09 2023-06-03 2023-07-08 2023-08-12 2024-08-11 lecommunications Infrastruct Based Selection l ation ure Investment Transaction 01/C/DSTP/2023 / Technical Assistance for the elaboratio Consultant Qualifi Open - Internationa Pending Impleme IDA / E0730 Digital access Post 100,000.00 0.00 2023-07-02 2023-07-23 2023-09-05 2023-10-05 2023-11-09 2024-05-07 n of the National Strategy for cation Selection l ntation Civil Registry and ID 04/C/DSTP/2023 / Technical Assistance for establishment of the Sao Tome and Principe Quality And Cost- Open - Internationa Under Implement National Computer Security I IDA / E0730 Digital access Post 500,000.00 0.00 2023-06-26 2023-06-09 2023-07-17 2023-06-21 2023-08-30 2023-09-27 2023-10-27 2023-12-01 2024-01-05 2025-01-04 Based Selection l ation ncident Response Team (CSIRT) 06/C/DSTP/2023 / Technical assistance for the design and installation of the ANPDP (Na Consultant Qualifi Open - Internationa Pending Impleme IDA / E0730 Digital access Post 150,000.00 0.00 2023-06-12 2023-07-03 2023-08-16 2023-09-15 2023-10-20 2024-04-17 tional Agency for Personal Da cation Selection l ntation ta Protection) internal manag ement and process manage ment system 14/C/DSTP/2022 / Technical Assistance to AGER (4g licce Quality And Cost- Open - Internationa IDA / V4030 Digital access Post 350,000.00 0.00 Canceled 2022-06-13 2022-07-04 2022-08-17 2022-09-14 2022-10-14 2022-11-18 2022-12-23 2023-12-23 nsing appaisal, infrastructure Based Selection l sharing, spectrum, allocation , QoS) 07/C/DSTP/2023 / Technical assistance for advocacy, awa Housing and population cens Consultant Qualifi Open - Internationa Pending Impleme IDA / E0730 Post 189,809.00 0.00 2023-06-20 2023-07-11 2023-08-24 2023-09-23 2023-10-28 2024-04-25 reness, communication and o us cation Selection l ntation utreach for the Census 12/C/DSTP/2022 / Technical Data foundations for digital Quality And Cost- Open - Internationa IDA / V4030 Post 300,000.00 0.00 Canceled 2022-05-27 2022-06-17 2022-07-31 2022-08-28 2022-09-27 2022-11-01 2022-12-06 2023-12-06 assistance for cybersecurity public service delivery Based Selection l 15/C/DSTP/2022 / Technical Quality And Cost- Open - Internationa Pending Impleme assistance for Environmental IDA / E0730 Digital access Post 250,000.00 0.00 2023-07-09 2023-07-30 2023-09-12 2023-10-10 2023-11-09 2023-12-14 2024-01-18 2025-01-17 Based Selection l ntation and Social Impact Assessmen t (ESIA) 03/C/DSTP/2023 / Technical Quality And Cost- Open - Internationa Pending Impleme Assistance for the Implement IDA / E0730 Digital access Post 200,000.00 0.00 2023-07-17 2023-08-07 2023-09-20 2023-10-18 2023-11-17 2023-12-22 2024-01-26 2025-01-25 Based Selection l ntation ation of the Interoperability P latform Page 1 08/C/DSTP/2023 / Technical Data foundations for digital Quality And Cost- Open - Internationa Pending Impleme Assistance for the formulatio IDA / E0730 Post 150,000.00 0.00 2023-08-21 2023-09-11 2023-10-25 2023-11-22 2023-12-22 2024-01-26 2024-03-01 2025-03-01 public service delivery Based Selection l ntation n of digital economy laws INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 01/C/DSTP/2022 / Hiring the Project management and co Individual Consult IDA / V4030 Post Open 80,000.00 0.00 Canceled 2022-03-08 2022-07-23 2022-04-26 2022-05-17 2022-06-21 2022-12-18 Project Coordinator ordination ant Selection 02/C/DSTP/2022 / Hiring Tec Project management and co Individual Consult IDA / V4030 Post Open 50,000.00 0.00 Canceled 2022-03-11 2022-04-29 2022-05-20 2022-06-24 2022-12-21 hnical advisor ordination ant Selection 03/C/DSTP/2022 / Hiring Env Project management and co Individual Consult IDA / V4030 Post Open 50,000.00 0.00 Signed 2022-03-15 2022-11-23 2022-05-03 2022-12-30 2022-05-24 2023-01-09 2022-06-28 2022-12-25 ironmental safeguard ordination ant Selection 04/C/DSTP/2022 / Hiring Soci Project management and co Individual Consult IDA / V4030 Post Open 50,000.00 0.00 Signed 2022-03-22 2022-11-23 2022-05-10 2023-01-17 2022-05-31 2023-01-16 2022-07-05 2023-01-01 al safeguard specialist ordination ant Selection 05/C/DSTP/2022 / Hiring Pro Project management and co Individual Consult IDA / V4030 Post Open 50,000.00 0.00 Canceled 2022-03-08 2022-07-28 2022-04-26 2022-05-17 2022-06-21 2022-12-18 curement specialist ordination ant Selection 06/C/DSTP/2022 / Hiring con Project management and co Individual Consult sultant to develop the Operat IDA / V4030 Post Open 30,000.00 0.00 Canceled 2022-04-22 2022-05-24 2022-06-10 2022-07-01 2022-08-05 2023-02-01 ordination ant Selection ions manuals 10/C/DSTP/2022 / Aechnical Data foundations for digital Individual Consult IDA / V4030 Post Direct 44,000.00 0.00 Signed 2022-02-28 2022-03-08 2022-03-10 2022-02-16 2022-03-31 2022-07-19 2022-05-05 2022-11-01 assistance to prepare RFP public service delivery ant Selection 11/C/DSTP/2022 / Aechnical assistance to prepare Enviro Data foundations for digital Individual Consult IDA / V4030 Post Direct 44,000.00 0.00 Signed 2022-02-28 2022-03-07 2022-03-10 2022-03-09 2022-03-31 2022-03-14 2022-05-05 2022-11-01 nmental and Social Manage public service delivery ant Selection ment Framework (ESMF) 17/C/DSTP/2022 / Hiring of A Project management and co Individual Consult IDA / V4030 Post Open 30,000.00 0.00 Signed 2022-06-10 2022-06-28 2022-07-29 2022-11-21 2022-08-19 2022-11-21 2022-09-23 2023-03-22 ccountant ordination ant Selection 19/C/DSTP/2022 / Hiring of P Project management and co Individual Consult IDA / V4030 Prior Open - National 50,000.00 0.00 Signed 2022-08-08 2022-08-24 2022-09-26 2023-01-13 2022-10-17 2023-01-31 2022-11-21 2023-05-20 rocurement Specialist ordination ant Selection 20/C/DSTP/2022 / Hiring of a Project management and co Individual Consult Under Implement Consultant to develop the Op IDA / V4030 Post Limited 30,000.00 0.00 2022-09-22 2022-12-02 2022-09-27 2022-12-12 2022-10-18 2022-12-19 2022-11-22 2023-05-21 ordination ant Selection ation eration manuals 23/C/DSTP/2022 / Contrataç Project management and co Individual Consult Open - Internationa IDA / V4030 Post 80,000.00 0.00 Signed 2022-10-26 2022-11-02 2022-12-14 2022-12-30 2023-01-04 2023-01-31 2023-02-08 2023-08-07 ão do Coordenador do Projet ordination ant Selection l o 24/C/DSTP/2022 / Assessme Direct - Internation IDA / V4030 Digital access Post Direct Selection 150,000.00 0.00 Signed 2023-02-01 2022-10-26 2023-02-11 2022-10-26 2023-04-17 2023-10-14 nt of connectivity in schools al 25/C/DSTP/2023 / Contrataç Project management and co Individual Consult IDA / V4030 Post Open - National 24,000.00 0.00 Signed 2023-01-20 2023-01-17 2023-03-10 2023-02-28 2023-03-31 2023-02-27 2023-05-05 2023-11-01 ão de Oficial de Ligação para ordination ant Selection o Príncipe 40/C/DSTP/2022 / Hiring Mon Project management and co Individual Consult IDA / V4030 Post Open - National 50,000.00 0.00 Canceled 2022-08-15 2022-10-03 2022-10-24 2022-11-28 2023-05-27 itoring and Evaluation special ordination ant Selection ist (M&E) 07/C/DSTP/2022 / Technical assistance to review and revi Project management and co Individual Consult IDA / V4030 Post Open 75,000.00 0.00 Canceled 2022-04-20 2022-06-08 2022-06-29 2022-08-03 2023-01-30 se Licence agreement followi ordination ant Selection ng purchase of Oi's shares in CST 16/C/DSTP/2022 / Marine sur IDA / V4030 Digital access Post Direct Selection Direct 830,000.00 0.00 Canceled 2022-04-12 2022-04-22 2022-06-26 2022-12-23 vey 02/C/DSTP/2023 / Technical Project management and co Pending Impleme assistance for the study of th IDA / E0730 Post Direct Selection Direct - National 15,000.00 0.00 2023-07-25 2023-08-04 2023-10-08 2024-04-05 ordination ntation e turtle habitat in Praia Melã o 05/C/DSTP/2023 / Technical Individual Consult Open - Internationa Pending Impleme Assistance to conduct qualita IDA / E0730 Digital access Post 50,000.00 0.00 2023-07-31 2023-09-18 2023-10-09 2023-11-13 2024-05-11 ant Selection l ntation tive research on the populati on's perspective Page 2 PLAN DE PASSATION DES MARCHES PART BAILLEUR_PROJET D’INTEGRATION PORT VILLE DU GRAND ABIDJAN (PACOGA) Le présent plan de passation de marchés initial couvre les dix-huit (18) premiers mois du PACOGA. I. GÉNÉRALITÉS 1.1. Information générale sur le projet Pays : République de Côte d’Ivoire Emprunteur : Gouvernement de Côte d’Ivoire Nom du Projet : Projets d’Appui à La Compétitivité du Grand Abidjan (PACOGA). Numéros du Crédit : n° CREDIT NUMBER 6272-CI Montant du Crédit: 315 millions de $ US Unité de Gestion du Projet : CC-PRICI 1.2 Date d’approbation du plan de passation de marchés Plan original : 1.3 Date de publication de l’avis général de passation de marchés : ____2018 1.4 Période couverte par le Plan de passation des marchés : de Juin 2018 à Novembre 2019 II. Fourniture, Travaux et Services Assimilés 2.1. Seuils d’examen préalable Les marchés qui seront soumis à l'examen préalable de la banque conformément aux dispositions de l'Annexe 1 Les marchés qui seront soumis à l'examen préalable de la banque conformément aux dispositions de l'Annexe 1 des Règlements de Passation de marchés pour les Emprunteurs sollicitant le Financement de projets de juillet 2016: Nouveaux seuils de revue de la Banque élaborés en décembre 2012 et proposés au Gouvernement le 05 décembre 2012, révisés en juillet 2016 et liés au niveau de risque du projet. Nature des Méthode de passation de Valeur Contrats soumis à dépenses marchés seuil du examen préalable de marché l’IDA $EU 1. Travaux AOI ≥ (y compris clés en 10,000,000 main, Fourniture et AON < Tous les contrats de montage 10,000,000 15.000.000 $EU et plus d’installations et Demande de cotation – < 200,000 PPP) au moins 3 offres Entente Directe (*) Pas de seuil Contrats ≥ 15. 000.000 2. Fournitures, AOI ≥ Systèmes 1,000,000 d’Informations et AON < Services autres 1,000,000 que les services Consultation de Fournisseurs à Tous les contrats de de Consultants l’échelle Nationale - Au moins 3 < 100,000 4.000.000 $EU et plus offres Consultation de Fournisseurs à l’échelle Nationale - Au moins 3 < 500 000 offres pour les véhicules et le carburant 1 Entente directe (*) Pas de seuil Contrats ≥ 4.000.000 (*) Le justificatif de toute entente directe dont le coût estimatif n’atteint pas le seuil de revue préalable de la Banque doit être transmis avec le PPM 2 2.2. Marchés, planning et Méthode de passation Type de marchés : Travaux - Fournitures et Prestations de services non intellectuelles Préféren Coût Méthode ce Ouvertur Liste des ensembles de estimé Exam par passation P-Q fournisse e plis Commentaire marchés millier Banque Marchés urs prévue ($EU) locaux A priori / N° Description Oui/No Date Bailleur Oui/Non A n prévue posteriori Composante n°1 : Gouvernance, 1 8 200,00 Planification et Services urbains Sous-Composante : 1-1 8 200,00 Planification urbaine Travaux d'adressage des A 06/03/201 La méthode AOI pour 1 rues dans le district 8 200,00 AOI Non N/A posteriori 9 l’approche marché d'Abidjan Municipal Governance and Institutional Capacity Strengthening Sous-Composante : Gouvernance municipale 1-2 et renforcement des 0 capacités institutionnelles Sous-Composante : 1-3 0 Services urbains Composante 2 : Amélioration des 165 2 infrastructures de 300,00 transport urbain Travaux de réhabilitation A 26/12/201 DAO en cours de 2 de la voirie du port 5 300,00 AON NON N/A posteriori 8 finalisation d’Abidjan En attente de l’ANO de la Banque Travaux d'aménagement AOI 28/11/201 3 50 000,00 OUI N/A A priori Mondiale sur le du carrefour Akwaba avec (P-Q) 8 dossier de Pré qualification. En attente de l’ANO Travaux de construction de la Banque de l'autoroute de 110 AOI 28/11/201 4 OUI N/A A priori Mondiale sur le contournement d'Abidjan 000,00 avec (P-Q) 8 dossier de Pré Y4 qualification. Composante 3: 3 Service logistique et 00,00 compétitivité 3 Sous Composante: 3-1 plateforme logistique et 00,00 services Composante 4: 4 Gestion du projet et 0 Suivi Evaluation 173 TOTAL 500,00 Taux de change utilisé: 1 $ EU= 550F CFA 4 III. Sélection de Consultants 3.1. Seuil d’examen préalable Les contrats qui seront soumis à l'examen préalable de la Banque conformément aux dispositions de l'Annexe 1 Les marchés qui seront soumis à l'examen préalable de la banque conformément aux dispositions de l'Annexe 1 des Règlements de Passation de marchés pour les Emprunteurs sollicitant le Financement de projets de juillet 2016: Nouveaux seuils de revue de la Banque élaborés en décembre 2012 et proposés au Gouvernement le 05 décembre 2012, révisés en juillet 2016 et liés au niveau de risque du projet Nature de Méthode de passation Valeur Contrats soumis à dépenses de marchés seuil du examen préalable contrat $EU Consultan SFQC1, SFQ2, SMC3, ≥ 300.000 ts SCBD4, Tout contrat de 2.000.000 Firmes SFQC, SFQ, SMC, SCBD, $EU ou plus < 300.000 QC5 Pas de Contrat ≥ 2.000.000 Entente directe (*) seuil Et Audit financier Consultan Consultant individuel (AMI) ≥ 100.000 ts Tout contrat de 400.000 $ Individuel Consultant individuel (3 EU ou plus < 100.000 s CV) Contrat ≥ 400.000 Pas de Entente directe (*) Et Coordonnateur, SPM et seuil RAF Tous les TDRs, quelle que soit la valeur du contrat, sont soumis à examen préalable. (*) Le justificatif de toute sélection par entente directe dont le coût estimatif n’atteint pas le seuil de revue préalable de la Banque doit être transmis avec le PPM. 3.2. Liste restreinte composée entièrement de Consultants Nationaux : Liste restreinte de consultants pour prestations de services, d’un coût estimatif inférieur à 300 000$ US ou équivalent par contrat, peut être entièrement composée de Consultants nationaux conformément aux dispositions du paragraphe 2.7 des Directives de Sélection et Emploi de Consultants 1 SFQC : Sélection Fondée sur la Qualité et le Coût 2 SFQ : Sélection fondée sur la qualité 3 SMC : Sélection au moindre coût 4 SCBD : Sélection dans le cadre d’un budget déterminé 5 QC : Sélection basée sur les Qualifications des Consultants CI : Consultant Individuel : AMI : Avis à Manifestation d’Intérêt 5 6 Type de marchés : services de Consultants Coût Exam. Ouverture estimé Métho par plis Liste des ensembles de marchés millier de Banque prévue $EU passati Commentaire on A Marché priori/A s Date N° Description BAILLEUR posterio prévue ri COMPOSANTE 1 : Gouvernance, 12 planification et services urbains 917,89 sous composante: 1.1 4 500,00 Planification urbaine Recrutement de Consultant/ TDRs élaborés à 15/01/201 1 Firme pour la préparation de 4 500,00 SFQ A priori transmettre à la 9 Plans d'Urbanisme de Détail Banque pour ANO sous composante: Gouvernance municipale et 1.2 3 168,85 renforcement des capacités institutionnelles Recrutement d'un consultant pour la réalisation d'études à la A 30/03/201 TDR en cours 2 création d'une structure 1 000,00 SFQ posterio 9 d’élaboration métropolitaine de coordination ri de la mise en œuvre du SDUGA Convention PACOGO / INPHB, Convention en A pour la mise en œuvre d’un 15/11/201 cours de 3 SED posterio Master of Sciences en 705,416 8 finalisation/ A ri Economie de transport posteriori Convention PACOGA/INPC 15/11/201 A Avis technique (France) pour la mise en œuvre 8 4 1 463,43 SED posterio de l’IDA est d’un Master of Sciences en ri requis Economie de transport sous composante: Services 1.3 5 249,04 urbains Le Ministère de la Recrutement d'une Agence de Construction et le A communication pour 31/07/201 district doivent 5 1 000,00 SFQ posterio l'adressage des rues dans le 9 élaborer et ri district d'Abidjan soumettre les TDRs. Recrutement d'un Consultant/Firme pour la A réalisation des études des 25/11/201 TDR à préparer 6 400,00 SFQ posterio mobilités « doux » (vélo, moto, 8 par le BNETD ri engins non motorisés) à Abidjan Recrutement d'un Consultant A pour la réalisation des études 28/12/201 TDR en cours de 7 500,00 SFQ posterio de l'aménagement de zone 8 préparation ri verte d'Abidjan Recrutement d'un consultant pour la réalisation des études A 20/01/201 TDR en cours de 8 de l'aménagement du bassin 500,00 SFQC posterio 9 préparation des Rosiers dans la commune ri de Cocody-Riviera Contrat avec le Groupement IGDP/AFRICURBA pour Contrat à A l’élaboration du répertoire des 15/11/201 soumettre à 9 259,035 SED posterio toponymes et odonymes des 8 l’avis technique ri voies et lieux du District de l’IDA d’Abidjan ACTIVITES BRT Recrutement d’un Consultant/Firme pour la Contrat en cours réalisation de l’étude de A d’exécution. 15/07/201 10 trafic d’un Transport en 180 SFQC posterio Attributaire : 8 Commun sur Site Propre ri SETEC (TCSP) pour la desserte Est- International Ouest d’Abidjan. 7 Contrat avec le BNETD pour une Assistance à Maitrise d’Ouvrage (AMO) pour la mise A 30/08/201 Contrat en cours 11 en place d’un transport en 200 SED postéri 8 de signature commun sur site propre (TCSP) ori pour la desserte Est-Ouest d’Abidjan. Recrutement d’un Consultant/Firme pour la AMI et DP à réalisation des études avant- A 25/11/201 soumettre à 12 projet sommaire et détaillé 550 SBQ postério 9 l’avis du TTL (APS) et (APD) pour la ri avant publication réalisation d’une ligne de BRT sur l’axe Est-Ouest d’Abidjan. Recrutement d’un Consultant/Firme pour la réalisation d’une étude de TDRs à élaborer restructuration des lignes de A et soumettre à la transport de la SOTRA et du 30/12/201 13 300 SFQ postério Banque avant la transport artisanal à Abidjan et 8 ri prochaine pour la réalisation d’une étude mission PACOGA d'intégration modale et tarifaire dans le transport urbain à Abidjan Recrutement d’un TDRs à éditer et Consultant/Firme pour la transmettre par réalisation de l'EIES pour la A le Ministère des 05/01/201 14 mise en place d’un transport 300 SFQC postério Transports et le 9 en commun sur site propre ri BNETD au plus (TCSP) pour la desserte Est- tard le 22 Ouest d’Abidjan. Octobre 2018. Recrutement d’un TDRs à éditer et Consultant/Firme pour la transmettre par réalisation du CGES pour la A le Ministère des SCI 15/11/201 15 mise en place d’un transport 100 postério Transports et le (AMI) 8 en commun sur site propre ri BNETD au plus (TCSP) pour la desserte Est- tard le 22 Ouest d’Abidjan. Octobre 2018. Recrutement d’un TDRs à éditer et Consultant/Firme pour transmettre par l’élaboration du CPR pour la A le Ministère des SCI 15/11/201 16 mise en place d’un transport 100 postério Transports et le (AMI) 8 en commun sur site propre ri BNETD au plus (TCSP) pour la desserte Est- tard le 22 Ouest d’Abidjan. Octobre 2018. Recrutement d’un TDRs à éditer et Consultant/Firme pour transmettre par l’élaboration du PAR pour la A le Ministère des 15/12/201 17 mise en place d’un transport 300 SFQC postério Transports et le 8 en commun sur site propre ri BNETD au plus (TCSP) pour la desserte Est- tard le 22 Ouest d’Abidjan. Octobre 2018. Recrutement d’un TDRs à Consultant/Firme pour la transmettre le 22 réalisation d’une étude sur la Octobre lutte contre le harcèlement et 2018.Montant A la prise en compte du genre 05/01/201 faible par 18 150 SFQ postério dans les transports publics à 9 rapport à la ri Abidjan méthode (SFQ). Etude importante Recrutement d’un TDRs à Consultant/Firme pour la soumettre le 22 réalisation d’une étude pour la Octobre 2018. A mise en place de mesures 05/01/201 Montant faible 19 150 SFQ postério incitatives à l'endroit des 9 par rapport à la ri transporteurs artisanaux à méthode (SFQ). Abidjan Etude importante ACTIVITE AOT 8 Recrutement d’un TDRs déjà soumis Consultant/Firme pour la A à l’ANO de la 20 réalisation d’une étude sur le 150 SBQ postério Banque financement du transport ri urbain à Abidjan. Contrat avec UITP pour l’Assistance technique pour TDRs à l’opérationnalisation de transmettre par A l’Autorité Organisatrice des 15/11/201 le Ministère des 21 110,0 SED postéri Transports Urbains d’Abidjan 8 Transport au plus ori (mise en place de tard le 19 l’organigramme, le manuel de Octobre 2018. procédures…) COMPOSANTE 2 : Amélioration 12 des infrastructures de transport 150,00 urbain Recrutement d'un Consultant L’AGEROUTE doit /Firme pour le suivi et contrôle élaborer et 15/12/20 22 des travaux de construction de 7 000,00 SFQC A priori transmettre les 18 la Section 2 de l'autoroute de TDRs le 15 contournement d'Abidjan Y4 Octobre 2018. L’AGEROUTE Recrutement d’un Consultant / A doit élaborer et Firme pour le suivi et contrôle 15/12/201 23 500 SFQC posterio transmettre les des travaux réhabilitation de la 8 ri TDRs le 15 voirie du port Octobre 2018. L’AGEROUTE doit Recrutement d'un consultant élaborer et pour le suivi et contrôle des 15/01/201 24 4 300,00 SFQC A priori transmettre les travaux de réaménagement du 9 TDRs le 15 carrefour Akwaba Octobre 2018. Audit de la sécurité routière sur les APD de l’aménagement du A 15/01/201 TRD validé par 25 carrefour Akwaba, de la section 350,00 SFQ posterio 9 l’IDA 2 de la Y4 et de la réhabilitation ri de la voirie du Port d’Abidjan COMPOSANTE 3 : Services 1 079,09 logistiques et compétitivité sous composante: 3.1 plateforme logistique et 1 079,09 services Sélection de consultants pour Contrat en cours les études de construction A d’exécution. d'une plateforme logistique, y 15/18/201 26 1079,09 SFQC posterio Attributaire : compris le port sec, la zone 8 ri Groupement logistique et un parking de SYSTRA/STUDI camions poids lourds Sous composante : 3.2 Régulation du trafic des - poids lourds dans le port Sous composante : développement du secteur 3.3 - privé et renforcement de la logistique Composante 4: Gestion de l'exécution du projet et Suivi 8 482,00 évaluation En place à CC- A Recrutement du 15/12/201 PRICI Avis 27 SED postério Coordonnateur Adjoint 8 technique de ri l’IDA est requis CI A TRD en cours Recrutement de l’Expert Genre 15/12/201 28 (AMI) postério d’élaboration et inclusion sociale 8 ri SED En place à CC- A Recrutement de l’Expert en 15/12/201 PRICI Avis 29 postério Environnement 8 technique de ri l’IDA est requis Audit comptable et financier du 30/10/20 TRD en cours 30 120,00 SFQC A priori projet 19 d’élaboration 9 Recrutement d’une firme pour A la campagne de sensibilisation 30/06/20 TRD en cours 31 100,00 SFQC posterio sur le genre et l’inclusion 19 d’élaboration ri sociale dans le grand Abidjan Convention PACOGO / AGEROUTE, pour la mise en Convention à A 32 œuvre de la composante 2 2 000,00 SED 15/11/201 soumettre à priori « Amélioration des 8 l’ANO de l’IDA infrastructures de transport » Convention PACOGA / District Autonome d’Abidjan (DAA) pour la mise en œuvre de la A Avis technique sous composante 1.3. 15/11/201 33 300,00 SED posterio de l’IDA est C « Gestion 8 ri requis environnementale : aménagement de la sécurité de la ceinture verte » Convention PACOGA/DAGERU, pour l’appui à la mise en œuvre A Avis technique 34 de la sous composante 1.3 C 300,00 SED posterio de l’IDA est « Adressage des voies de la ri 15/11/201 requis ville d’Abidjan » 8 Convention PACOGA / DGTTC, pour l’appui à la mise en œuvre des sous composantes 1.2 « Gouvernance municipale et A 15/11/201 Avis technique 35 renforcement des capacités 400,00 SED posterio 8 de l’IDA est institutionnelles » 1.3 ri requis « Services Urbains » et la composante 3 « Services logistiques et compétitivité » Convention PACOGA / DGUF, A Avis technique pour la mise en œuvre de la 36 300,00 SED posterio de l’IDA est sous-composante ri 15/11/201 requis « Planification Urbaine » 8 Convention PACOGA/PAA, pour l’appui à la mise en œuvre de A Avis technique la sous-composante « Création 37 200,00 SED posterio de l’IDA est plate-forme informatique de 15/11/201 ri requis gestion du flux de camion au 8 Port » Convention PACOGA de gestion A 15/11/201 ANO de l’IDA 38 4 762,00 SED judiciaire priori 8 est requis 34 TOTAL 628,98 10 IV : RENFORCEMENT DE CAPACITE Dans cette section, lister les activités de renforcement de capacités approuvées et leur planning Réf Montant Durée Date . Description du estimatif estimée de Commentaires No contrat ($EU) (jours) début 1 Voyages d’étude sur 2 TDRs finalisés réseaux de BRT en par le BNETD et Colombie Mars à transmis à la 50 10 jours 2019 Cellule de Coordination du PRICI 2 Rencontre à Dakar TDRs à élaborer Janvier avec CETUD, DAR 18.18 2 jours et à transmettre 2019 par le BNETD TOTAL NB: 1$ USD =550 FCFA 5. RECAPITULATIF Commentai Nombre Montant estimatif N° res Composante/ Catégories ordre Contrat Milliers de $ milliers CFA s EU COMPOSANTE 1 : 11 1 Gouvernance, planification 22 21 117,89 614 839,5 et services urbains 4 510 Travaux et fournitures par AOI 1 8 200 000,00 Travaux et fournitures par AON 0 7 104 Consultants 21 12 917,89 839,50 COMPOSANTE 2: Amélioration des 97 597 2 7 177 450,00 infrastructures de transport 500,00 urbain Travaux et fournitures par AOI 2 160 000,00 88 000 000 Travaux et fournitures par AON 1 5 300,00 2 915 000 Consultants 4 12 150,00 6 682 500 COMPOSANTE 3: Services 3 1 1 079,09 593 499,5 logistiques et compétitivité Travaux et fournitures par AOI 0 0,00 - Travaux et fournitures par AON 0 0,00 - Consultants 1 1 079,09 593 499,5 Composante 4: Gestion de 4 l'exécution du projet et Suivi 9 8 482,00 4 665 100 évaluation Travaux et fournitures par AOI 0 Travaux et fournitures par AON 0 Consultants 9 8 482,00 4 665 100 114 470 TOTAL 39 208 128,98 938,50 11 12 PROCUREMENT Cote d'Ivoire : GREATER ABIDJAN PORT - CITY INTEGRATION PROJECT PLAN General Information Country: Cote d'Ivoire 2018-11-27 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P159697 GPN Date: 2018-12-14 Project Name: GREATER ABIDJAN PORT - CITY INTEGRATION PROJECT Loan / Credit No: IDA / 62720, IDA / V0760 PROJECT TO SUPPORT THE COMPETITIVENESS OF THE GREATER ABIDJAN AGGLOMERATION Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CI-PACOGA-86862-CW-RFB / Urban Transport Infrastructu Single Stage - One E 4,219,826.8 2019-10-0 Travaux de réhabilitation de l IDA / 62720 Post Request for Bids Open - National 5,300,000.00 Terminated 2018-12-18 2019-09-12 2018-12-23 2019-02-03 2019-10-04 2019-03-05 2019-10-04 2019-04-09 2020-01-10 re nvelope 1 6 a voirie du Port d'Abidjan CI-PACOGA-86864-CW-RFB / Urban Transport Infrastructu Open - Internationa Single Stage - Two E 50,000,000.0 2021-01-1 Travaux d'aménagement de l IDA / 62720 Prior Request for Bids 0.00 Canceled 2018-11-13 2019-01-29 2019-01-29 2018-11-18 2019-04-09 2019-06-22 2019-07-27 re l nvelope 0 7 'échangeur du carrefour d'Ak waba CI-PACOGA-86869-CW-RFB / Urban Transport Infrastructu Open - Internationa Single Stage - Two E 110,000,000. 2021-01-1 Travaux de construction de l' IDA / 62720 Prior Request for Bids 0.00 Canceled 2018-11-14 2019-01-30 2019-01-30 2018-11-19 2019-04-10 2019-06-23 2019-07-28 re l nvelope 00 8 autoroute de contournement Y4 d'Abidjan CI-PACOGA-122998-CW-RFB Urban Transport Infrastructu Open - Internationa Single Stage - One E 50,000,000.0 48,364,547. 2020-09-1 / Travaux d'aménagement du IDA / 62720 Prior Request for Bids Signed 2019-11-28 2020-10-15 2019-12-03 2021-01-29 2020-01-14 2021-01-12 2020-02-13 2021-05-14 2020-03-19 2021-06-16 re l nvelope 0 78 5 carrefour Akwaba - Tranche prioritaire CI-PACOGA-123003-CW-RFB / Travaux d'aménagement de Urban Transport Infrastructu Open - Internationa Single Stage - One E 110,000,000. 59,993,733. 2020-08-1 l'autoroute de contournemen IDA / 62720 Prior Request for Bids Signed 2019-10-29 2020-03-30 2019-11-03 2020-06-02 2019-12-15 2020-06-18 2020-01-14 2020-11-18 2020-02-18 2021-02-16 re l nvelope 00 80 6 t Y4 d'Abidjan-Section 2 : Ech angeur d'Anyama - Autoroute du Nord. CI-PACOGA-92018-CW-RFB / Construction de l'autoroute d Urban Transport Infrastructu Open - Internationa Single Stage - One E 160,000,000. 2019-10-2 e contournement Y4 et Trava IDA / 62720 Prior Request for Bids 0.00 Canceled 2019-01-08 2019-01-13 2019-02-24 2019-03-26 2019-04-30 re l nvelope 00 7 ux d'aménagement de l'écha ngeur du carrefour Akwaba d 'Abidjan CI-PACOGA-86855-CW-RFB / Urban Planning, Services an Open - Internationa Single Stage - One E 2020-01-0 Travaux d'adressage des rue IDA / 62720 Post Request for Bids 8,200,000.00 0.00 Canceled 2019-03-20 2019-03-25 2019-05-06 2019-06-05 2019-07-10 d Governance l nvelope 6 s dans le district d'Abidjan CI-PACOGA-86544-CW-RFB / Urban Planning, Services an Open - Internationa Single Stage - One E 2019-12-2 Travaux d'adressage des rue IDA / 62720 Post Request for Bids 8,200,000.00 0.00 Canceled 2019-03-06 2019-03-11 2019-04-22 2019-05-22 2019-06-26 d Governance l nvelope 3 s dans le district d'Abidjan CI-PACOGA-122965-CW-RFQ / Aménagement de 4 salles ( Administration, cours et salle Urban Planning, Services an Request for Quota Single Stage - One E 2020-08-2 IDA / 62720 Post Limited 47,510.00 50,608.92 Completed 2020-01-01 2019-08-14 2020-02-26 2019-11-08 s spécialisées) de l'INP HB da d Governance tions nvelope 4 ns le cadre de la mise en œu vre du Mastère Professionnel en TAU CI-PACOGA-219336-CW-RFB / Travaux d'aménagement de Urban Transport Infrastructu Open - Internationa Single Stage - One E 53,302,000.0 36,202,519. 2022-02-1 l'autoroute périphérique d'Ab IDA / 62720 Prior Request for Bids Signed 2021-04-29 2021-04-27 2021-05-04 2021-05-03 2021-06-15 2021-06-22 2021-07-15 2021-12-07 2021-08-19 2022-03-25 re l nvelope 0 97 5 idjan - Section 3 : Autoroute du Nord-Autoroute de Dabou CI-PACOGA-247044-CW-RFB Request for Bids - / Travaux d'aménagement de Urban Planning, Services an Single Stage - Two E Works French Civi 2022-09-1 s gares lagunaires d'Abobodo IDA / 62720 Prior Request for Bids Open - National 8,200,000.00 0.00 Canceled 2021-10-18 2021-10-23 2021-12-04 2022-03-23 d Governance nvelope l Law (French) SP 9 umé, du Plateaux et des voie D s d'accès aux gares lagunair es. CI-PACOGA-268448-CW-RFQ National Procure / Travaux confortatifs dans le ment Document - cadre de la résiliation du mar Urban Transport Infrastructu Request for Quota Single Stage - One E 2022-08-2 IDA / 62720 Post Limited 1 Envelope proce 177,248.18 0.00 Canceled 2022-01-04 2022-03-01 ché de réhabilitation des infr re tions nvelope 8 ss (Non Bank-SPD astructures routières du Port ) Autonome d'Abidjan (Voies p rioritaires). CI-PACOGA-238485-CW-RFB / Travaux d'aménagement et Request for Bids - de réhabilitation des infrastr Urban Transport Infrastructu Single Stage - One E Works French Civi 18,075,222.0 2022-04-3 uctures de Transport routier IDA / 62720 Post Request for Bids Open - National 0.00 Canceled 2021-07-12 2021-07-17 2021-08-28 2021-09-27 2021-11-01 re nvelope l Law (French) SP 0 0 du Port Autonome d'Abidjan ( D Anciennes voies prioritaires e t voies complémentaires) en 2 lots CI-PACOGA-273835-CW-RFB / Travaux d'aménagement et Request for Bids - de réhabilitation des infrastr Urban Transport Infrastructu Open - Internationa Single Stage - One E Works French Civi 18,075,222.0 Under Imple 2023-01-0 uctures de transport routier IDA / 62720 Prior Request for Bids 0.00 2022-03-22 2022-03-29 2022-03-27 2022-04-19 2022-05-08 2022-06-02 2022-06-07 2022-08-09 2022-07-12 re l nvelope l Law (French) SP 0 mentation 8 du Port Autonome d'Abidjan ( D Anciennes voies prioritaires e t voies complémentaires) en 2 lots. CI-PACOGA-307250-CW-RFB Request for Bids - / Travaux d'aménagement et Urban Planning, Services an Open - Internationa Single Stage - One E Works (without pr 14,545,454.5 Under Imple 2023-07-1 de construction des gares lag IDA / 62720 Prior Request for Bids 0.00 2022-09-22 2022-08-09 2022-09-27 2022-08-16 2022-11-08 2022-10-13 2022-12-08 2022-11-09 2023-01-12 d Governance l nvelope equalification) SP 5 mentation 1 unaires d'Abobodoumé et du D Plateaux et de leurs voies d'a ccès. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 CI-PACOGA-122967-GO-RFQ / Fourniture de matériel infor matique et bureautique dans le cadre de la mise en œuvre Urban Planning, Services an Request for Quota Single Stage - One E IDA / 62720 Post Limited 27,904.00 67,551.89 Completed 2019-10-23 2019-09-23 2019-12-18 2019-11-28 2020-06-15 2020-01-30 du Mastère Professionnel en d Governance tions nvelope TAU en 3 lots (Lot 1 : Matérie l informatique; Lot 2 : Mobilie r de bureau; Lot 3 : Fournitur e de bureau). CI-PACOGA-149780-GO-DIR / Marché par SED avec HDM G Urban Planning, Services an IDA / 62720 Post Direct Selection Direct 6,450.00 8,917.68 Completed 2020-01-30 2020-04-23 2020-02-04 2020-04-23 2020-03-10 2020-10-10 2020-09-06 2020-12-03 LOBAL, pour la fourniture et l d Governance 'installation du logiciel HDM- 4 VERSION 2 CI-PACOGA-149781-GO-DIR / Marché par SED avec le four Urban Planning, Services an nisseur PTV-GROUP, pour la f IDA / 62720 Post Direct Selection Direct 6,000.00 5,943.50 Completed 2020-01-29 2020-04-23 2020-02-03 2020-04-23 2020-03-09 2020-04-02 2020-09-05 2020-12-03 d Governance ourniture et l'installation du l ogiciel PTV Vissim version 11 CI-PACOGA-149783-GO-DIR / Marché par SED avec le four Urban Planning, Services an nisseur CITILABS, pour la four IDA / 62720 Post Direct Selection Direct 17,000.00 16,166.32 Completed 2020-01-14 2020-04-23 2020-01-19 2020-04-23 2020-02-23 2020-09-29 2020-08-21 2020-10-01 d Governance niture et l'installation du logi ciel cube voyager version 6.4 .5 CI-PACOGA-162084-GO-RFQ / La fourniture, l'installation, l Program Management and M Request for Quota Single Stage - One E a mise en service et la maint IDA / 62720 Post Limited 15,000.00 59,524.74 Completed 2020-06-15 2020-06-05 2020-08-10 2020-08-25 2021-02-06 2020-12-11 onitoring tions nvelope enance d'un système de visio conférence dans la salle de r éunion de la CC-PRICI CI-PACOGA-219328-GO-RFQ / La fourniture, l'installation e t la mise en service d'un syst Urban Planning, Services an Request for Quota Single Stage - One E IDA / 62720 Post Limited 27,272.73 25,475.07 Signed 2021-03-13 2021-03-08 2021-05-08 2021-05-22 2021-11-04 ème de visioconférence d'un d Governance tions nvelope e salle à l'INP HB dans le cad re de la mise en œuvre du M astère en TAU. CI-PACOGA-238467-GO-RFQ / Fourniture de mobilier de b Urban Planning, Services an Request for Quota Single Stage - One E ureau pour la centrale d'adre IDA / 62720 Post Limited 19,645.46 18,453.60 Completed 2021-06-23 2021-07-02 2021-08-18 2021-08-27 2022-02-14 2021-12-23 d Governance tions nvelope ssage dans le cadre du projet d'adressage des rues et port es du district d'Abidjan CI-PACOGA-238476-GO-RFQ / Fourniture de matériel infor matique pour l’Équipe Perma Urban Planning, Services an Request for Quota Single Stage - One E nente Locale (EPL) de la cent IDA / 62720 Post Limited 53,618.18 73,402.19 Signed 2021-06-30 2021-07-02 2021-08-25 2021-10-07 2022-02-21 d Governance tions nvelope rale d'adressage dans le cadr e du projet d'adressage des r ues et portes du district d'Abi djan. CI-PACOGA-261098-GO-RFQ / Fourniture de mobilier de b Urban Planning, Services an Request for Quota Single Stage - One E IDA / 62720 Post Limited 27,272.72 12,888.84 Signed 2021-11-29 2021-11-17 2022-01-24 2022-01-06 2022-07-23 ureau pour la salle géomatiq d Governance tions nvelope ue de la centrale d'adressage . CI-PACOGA-261116-GO-RFQ / Fourniture de mobilier de b ureau supplémentaire (table Urban Planning, Services an Request for Quota Single Stage - One E d'ordinateur, chaises, table d IDA / 62720 Post Limited 21,449.81 20,350.04 Signed 2021-11-21 2020-07-01 2022-01-16 2021-03-13 2022-07-15 d Governance tions nvelope e classe, fauteuils de directio n) dans le cadre de l'aménag ement de 4 salles de classes à l'INP-Sud - Bâtiment A. CI-PACOGA-122963-GO-RFB / Fourniture et pose de pann Urban Planning, Services an Open - Internationa Single Stage - One E IDA / 62720 Prior Request for Bids 3,500,000.00 0.00 Canceled 2019-12-06 2019-12-11 2020-01-22 2020-02-21 2020-03-27 2020-09-23 eaux (Panneautage) pour l'a d Governance l nvelope dressage des rues et lieux da ns le district d'Abidjan CI-PACOGA-295285-GO-RFB / Fourniture et pose des plaq Urban Planning, Services an Open - Internationa Single Stage - One E IDA / 62720 Prior Request for Bids 3,500,000.00 0.00 Canceled 2022-07-29 2022-09-15 2022-08-03 2022-10-31 2022-09-14 2022-11-17 2022-10-14 2023-05-09 2022-11-18 2023-05-17 ues dans le cadre du projet d d Governance l nvelope 'adressage des voies du distr ict d'Abidjan. CI-PACOGA-305566-GO-RFQ / Fourniture de mobiliers de b Urban Planning, Services an Request for Quota Single Stage - One E Pending Impl ureaux supplémentaires pour IDA / 62720 Post Limited 21,547.28 0.00 2022-08-30 2022-10-25 2023-04-23 d Governance tions nvelope ementation le compte de l'équipe perma nente de la centrale d'adress age. CI-PACOGA-305633-GO-RFQ / Fourniture de matériels info rmatiques et bureautiques co Urban Planning, Services an Request for Quota Single Stage - One E Pending Impl IDA / 62720 Post Limited 64,000.00 0.00 2022-09-26 2022-11-21 2023-05-20 mplémentaires à la Centrale d Governance tions nvelope ementation d’adressage (Serveur, Impri mante A0+, Scanner A0+, O nduleur …) CI-PACOGA-360854-GO-RFQ / L'ACQUISITION DU SERVEU Urban Planning, Services an Request for Quota Single Stage - One E Pending Impl IDA / 62720 Post Limited 236,500.00 0.00 2023-05-20 2023-06-26 2023-09-24 R INFORMATIQUE DU PROJET d Governance tions nvelope ementation D'ADRESSAGE DU DISTRICT D'ABIDJAN (PADA) CI-PACOGA-295285-GO-RFB- 2 / FOURNITURE ET POSE DE S PLAQUES ET PANNEAUX DE Urban Planning, Services an Open - Internationa Single Stage - One E Under Imple IDA / 62720 Prior Request for Bids 6,400,000.00 0.00 2023-06-05 2023-06-29 2023-06-10 2023-07-25 2023-08-24 2023-09-28 2025-09-17 RUE DANS LE CADRE DU PRO d Governance l nvelope mentation JET D’ADRESSAGE DES VOIES DU DISTRICT D’ABIDJAN CI-PACOGA-367044-GO-RFQ / ACTIVITES DE VISIBILITE DA Urban Planning, Services an Request for Quota Pending Impl NS LE CADRE DE LA MISE EN IDA / 62720 Post 110,730.00 0.00 2023-06-21 2023-07-18 2023-09-16 d Governance tions ementation OEUVRE DU PROJET D'ADRES SAGE DU DISTRICT D'ABIDJA N NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 CI-PACOGA-123058-NC-DIR / Convention avec le GROUPE OLYMPE, pour diverses public Program Management and M IDA / 62720 Post Direct Selection Direct 36,363.00 34,087.90 Completed 2019-07-30 2019-10-07 2019-08-04 2019-10-07 2019-09-08 2019-10-11 2020-03-06 2021-01-22 ations relatives au processus onitoring de passation des marchés (A MI, AAO, publication de résult ats …) CI-PACOGA-123071-NC-RFQ / Atelier de validation du PPS Urban Planning, Services an Request for Quota Single Stage - One E D (Document de Stratégie d IDA / 62720 Post Limited 5,126.00 0.00 Canceled 2019-10-09 2019-12-04 2020-06-01 d Governance tions nvelope e la passation des marchés ) du Projet de Mobilité Urbaine d'Abidjan. CI-PACOGA-123066-NC-RFQ / Atelier de lancement du Ma Urban Planning, Services an Request for Quota Single Stage - One E IDA / 62720 Post Limited 15,960.00 1,347.11 Completed 2019-10-04 2019-09-23 2019-11-29 2019-12-13 2020-05-27 2019-12-13 stère Professionnel en Transp d Governance tions nvelope ort et en Aménagement Urba in. CI-PACOGA-72734-NC-DIR / Convention avec le Groupe F RATERNITE MATIN pour la pu Program Management and M IDA / 62720 Post Direct Selection Direct 55,000.00 54,364.80 Completed 2019-12-18 2020-01-28 2019-12-23 2020-01-30 2020-01-27 2020-02-11 2020-07-25 2020-12-31 blication des AMI, des TDR, d onitoring es Avis d'Appel d'Offres et de s résultats de la passation de s marchés. CI-PACOGA-219355-NC-DIR / Convention de service avec l a SNPE CI (la société FRATER NITE MATIN) pour la fournitur Program Management and M IDA / 62720 Post Direct Selection Direct 55,000.00 54,481.16 Signed 2021-03-16 2021-03-12 2021-03-21 2021-03-15 2021-04-25 2021-03-16 2021-10-22 e de service médias (publicat onitoring ion des AMI, des avis d'Appel s d'offres et publication de ré sultats) dans le cadre des act ivités du PACOGA. CI-PACOGA-268440-NC-RFQ / Recrutement d'un prestatai Urban Planning, Services an Request for Quota Single Stage - One E re pour l'organisation de l'até IDA / 62720 Post Limited 50,090.00 47,627.35 Signed 2022-01-04 2021-12-07 2022-03-01 2022-01-12 2022-08-28 d Governance tions nvelope lier de lancement des activit és d'adressage dans le distric t d'Abidjan. CI-PACOGA-273574-NC-RFQ / Organisation de l'atelier de l Urban Transport Infrastructu Request for Quota Single Stage - One E Pending Impl IDA / 62720 Post Limited 36,363.64 0.00 2022-03-20 2022-05-15 2022-11-11 ancement des travaux d'amé re tions nvelope ementation nagement du carrefour Akwa ba (Phase prioritaire) CI-PACOGA-273547-NC-RFQ / Recrutement d'un prestatai re pour l'organisation de l'at Urban Planning, Services an Request for Quota Single Stage - One E elier diagnostic et de restituti IDA / 62720 Post Limited 27,272.73 0.00 Canceled 2022-06-04 2022-07-30 2023-01-26 d Governance tions nvelope on de l'étude de faisabilité d e la mise en place d'une stru cture de gouvernance métro politaine du grand Abidjan. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-PACOGA-72707-CS-QCBS / Recrutement d'un consultan t pour la réalisation des étud Urban Planning, Services an Quality And Cost- IDA / 62720 Post Open - National 500,000.00 186,520.55 Signed 2016-03-15 2019-07-22 2016-04-05 2016-05-19 2020-04-23 2016-06-16 2020-04-23 2016-07-16 2020-02-07 2016-08-20 2020-02-20 2016-09-24 2020-03-28 2017-09-24 es de l'aménagement du bas d Governance Based Selection sin des rosiers dans la comm une de Cocody Riviera Palme raie CI-PACOGA-72716-CS-QCBS / Recrutement d'un consultan t pour la réalisation des étud es de faisabilité techniques p Urban Planning, Services an Quality And Cost- Open - Internationa IDA / V0760 Prior 500,000.00 0.00 Canceled 2018-12-28 2019-05-24 2019-01-11 2019-06-07 2019-02-09 2019-03-09 2019-03-24 2019-04-22 2019-05-21 2019-08-19 our la réalisation du projet de d Governance Based Selection l préservation et de valorisatio n de la ceinture verte du Sch éma Directeur d'Urbanisme d u Grand Abidjan (SDUGA) CI-PACOGA-86849-CS-QBS / Recrutement d'un consultant /Firme pour la réalisation d'u Urban Planning, Services an Quality Based Sel IDA / 62720 Post Open - National 150,000.00 0.00 Canceled 2019-05-14 2019-06-04 2019-07-18 2019-08-15 2019-09-14 2019-10-14 2019-11-18 2020-11-17 ne étude pour la mise en pla d Governance ection ce de mesures incitatives à l' endroit des transporteurs arti sanaux à Abidjan. CI-PACOGA-72273-CS-QCBS / Recrutement d'un Consulta nt/Firme pour la réalisation d Urban Planning, Services an Quality And Cost- Open - Internationa IDA / 62720 Post 180,000.00 118,796.29 Completed 2018-07-31 2018-05-07 2018-08-21 2018-10-04 2018-06-28 2018-11-01 2018-07-17 2018-12-01 2018-05-18 2019-01-05 2018-05-18 2019-02-09 2018-09-12 2020-02-09 2018-11-17 e l'étude de trafic d'un trans d Governance Based Selection l port en commun sur site pro pre (TCSP) pour la desserte E st-Ouest d'Abidjan. CI-PACOGA-72696-CS-CQS / Recrutement d'un Consultant /Firme pour la réalisation de l Urban Planning, Services an Quality And Cost- IDA / 62720 Post Open - National 300,000.00 0.00 Canceled 2018-11-28 2018-12-19 2019-02-01 2019-03-01 2019-03-31 2019-05-05 2019-06-09 2020-06-08 'EIES pour la mise en place d' d Governance Based Selection un transport en commun sur site propre (TCSP) pour la de sserte Est-Ouest d'Abidjan CI-PACOGA-86519-CS-CQS / Recrutement d'un Consultant Urban Planning, Services an Consultant Qualifi pour la réalisation des étude IDA / 62720 Post Open - National 500,000.00 0.00 Canceled 2019-03-21 2019-04-11 2019-05-25 2019-06-24 2019-07-29 2020-01-25 d Governance cation Selection s de l'aménagement de zone verte de la ville d'Abidjan CI-PACOGA-86520-CS-QBS / Recrutement de Consultant/ Urban Planning, Services an Quality Based Sel Open - Internationa IDA / 62720 Prior 4,500,000.00 0.00 Canceled 2019-01-28 2019-05-24 2019-02-18 2019-06-07 2019-04-03 2021-01-05 2019-05-01 2019-05-31 2019-06-30 2019-08-04 2020-08-03 Firme pour la préparation de d Governance ection l Plans d'Urbanisme de Détail CI-PACOGA-86525-CS-QBS / Recrutement d'un Consultant Urban Planning, Services an Quality Based Sel /Firme pour la réalisation des IDA / 62720 Post Open - National 400,000.00 0.00 Canceled 2019-01-10 2019-01-31 2019-03-16 2019-04-13 2019-05-13 2019-06-12 2019-07-17 2020-07-16 d Governance ection études des mobilités « doux » (vélo, moto, engins non mo torisés) à Abidjan Page 3 CI-PACOGA-86528-CS-QBS / Recrutement d'un Consultant Urban Planning, Services an Quality Based Sel /Firme pour la réalisation d'u IDA / 62720 Post Open - National 150,000.00 334,016.98 Completed 2019-01-15 2020-04-17 2019-02-05 2020-04-17 2019-03-21 2020-04-17 2019-04-18 2020-04-17 2019-05-18 2020-04-17 2019-06-17 2020-04-17 2019-07-22 2020-07-21 2020-07-21 2021-09-24 d Governance ection ne étude sur le financement du transport urbain à Abidjan . CI-PACOGA-86530-CS-QCBS / Recrutement d'un Consulta nt /Firme pour le suivi et cont Urban Transport Infrastructu Quality And Cost- Open - Internationa IDA / 62720 Prior 7,000,000.00 2,412,631.91 Signed 2018-12-10 2020-04-27 2018-12-31 2020-06-02 2019-02-13 2020-12-28 2019-03-13 2021-03-04 2019-04-12 2021-06-08 2019-05-17 2021-07-15 2019-06-21 2021-11-03 2020-06-20 rôle des travaux de construct re Based Selection l ion de la Section 2 de l'autor oute de contournement d'Abi djan Y4 CI-PACOGA-86531-CS-QCBS / Recrutement d'un Consulta Urban Transport Infrastructu Quality And Cost- IDA / 62720 Post Open - National 500,000.00 321,143.90 Completed 2018-12-10 2019-08-26 2018-12-31 2019-02-13 2019-10-11 2019-03-13 2019-12-10 2019-04-12 2019-12-14 2019-05-17 2020-01-17 2019-06-21 2020-01-18 2020-06-20 2021-12-07 nt / Firme pour le suivi et con re Based Selection trôle des travaux réhabilitati on de la voirie du port CI-PACOGA-86532-CS-QCBS / Recrutement d'un consultan Urban Transport Infrastructu Quality And Cost- Open - Internationa t pour le suivi et contrôle des IDA / 62720 Prior 4,300,000.00 2,334,127.20 Signed 2018-12-17 2020-10-30 2019-01-07 2020-11-11 2019-02-20 2021-05-03 2019-03-20 2021-07-16 2019-04-19 2021-10-21 2019-05-24 2021-11-18 2019-06-28 2021-12-29 2020-06-27 re Based Selection l travaux de réaménagement du carrefour Akwaba CI-PACOGA-86533-CS-QBS / Audit de la sécurité routière s ur les APD de l'aménagemen Urban Transport Infrastructu Quality Based Sel IDA / 62720 Post Open - National 350,000.00 346,815.76 Completed 2018-11-13 2018-11-27 2018-12-04 2018-11-28 2019-01-17 2020-04-20 2019-02-14 2020-04-20 2019-03-16 2019-02-25 2019-04-15 2019-03-06 2019-05-20 2019-04-06 2020-05-19 2020-03-06 t du carrefour Akwaba, de la re ection section 2 de la Y4 et de la ré habilitation de la voirie du Po rt d'Abidjan CI-PACOGA-86534-CS-QCBS Program Management and M Quality And Cost- / Audit comptable et financie IDA / 62720 Prior Open - National 120,000.00 17,229.02 Signed 2019-10-30 2019-09-19 2019-11-20 2019-09-23 2020-01-03 2020-01-15 2020-01-31 2020-03-19 2020-03-01 2020-04-16 2020-04-05 2020-06-08 2020-05-10 2020-07-01 2021-05-10 onitoring Based Selection r du PACOGA CI-PACOGA-86535-CS-QCBS / Recrutement d'une firme po Program Management and M Quality And Cost- ur la campagne de sensibilis IDA / 62720 Post Open - National 250,000.00 0.00 Canceled 2019-06-30 2019-07-21 2019-09-03 2019-10-01 2019-10-31 2019-12-05 2020-01-09 2021-01-08 onitoring Based Selection ation sur le genre et l'inclusio n sociale dans le grand Abidj an CI-PACOGA-123013-CS-QCB S / Recrutement d'un Consult ant/firme pour les EIES pour l Urban Planning, Services an Quality And Cost- IDA / 62720 Post Open - National 90,909.00 0.00 Canceled 2019-09-09 2019-09-30 2019-11-13 2019-12-11 2020-01-10 2020-02-14 2020-03-20 2021-03-20 es travaux de drainage et tra d Governance Based Selection vaux routiers associés dans l e cadre de la préparation du Projet de Résilience Urbaine. CI-PACOGA-123015-CS-QCB S / Recrutement d'un Consult ant/firme pour l'élaboration d Urban Planning, Services an Quality And Cost- u PAR, pour les travaux de dr IDA / 62720 Post Open - National 90,900.00 0.00 Canceled 2019-09-30 2019-10-21 2019-12-04 2020-01-01 2020-01-31 2020-03-06 2020-04-10 2021-04-10 d Governance Based Selection ainage et travaux routiers as sociés dans le cadre de la pr éparation du Projet de Résilie nce Urbaine. CI-PACOGA-123016-CS-QBS / Recrutement d'un Consulta nt/firme pour l'élaboration de s études plans intercommun Urban Planning, Services an Quality Based Sel Open - Internationa IDA / 62720 Prior 272,727.00 0.00 Canceled 2019-10-02 2019-10-23 2019-12-06 2020-01-03 2020-02-02 2020-03-03 2020-04-07 2021-04-07 aux et identification des beso d Governance ection l ins en infrastructures et en é quipements pour villes secon daires dans le cadre de la pr éparation du Projet de Résilie nce Urbaine. CI-PACOGA-123022-CS-QBS / Recrutement d'un Consulta nt/Firme pour les études de f aisabilités et de conception d Urban Planning, Services an Quality Based Sel Open - Internationa étaillée y compris la préparat IDA / 62720 Prior 181,818.00 0.00 Canceled 2019-10-02 2019-10-23 2019-12-06 2020-01-03 2020-02-02 2020-03-03 2020-04-07 2021-04-07 d Governance ection l ion des Dossiers d'Appels d'O ffres (DAO) pour la plateform e numérique dans le cadre d e la préparation du Projet de Résilience Urbaine. CI-PACOGA-123027-CS-QBS / Recrutement d'un consultan t/Firme pour les études de fai sabilités et de conception dét Urban Planning, Services an Quality Based Sel Open - Internationa IDA / 62720 Prior 181,818.00 0.00 Canceled 2019-10-10 2019-10-31 2019-12-14 2020-01-11 2020-02-10 2020-03-11 2020-04-15 2021-04-15 aillée y compris la préparatio d Governance ection l n des DAO pour le système d 'alerte précoce aux inondatio ns dans le cadre de la prépar ation du Projet de Résilience Urbaine. CI-PACOGA-123031-CS-QBS / Recrutement d'un Consulta nt/Firme pour l'étude d'évalu Urban Planning, Services an Quality Based Sel ation de capacité et état de li IDA / 62720 Post Open - National 90,909.00 0.00 Canceled 2019-10-08 2019-10-29 2019-12-12 2020-01-09 2020-02-08 2020-03-09 2020-04-13 2021-04-13 d Governance ection eu sur les technologies digita les dans le cadre de la prépa ration du Projet de Résilience Urbaine. CI-PACOGA-123050-CS-QBS / Recrutement d'une assistan ce technique à la Centrale d' Urban Planning, Services an Quality Based Sel Open - Internationa IDA / 62720 Prior 7,100,000.00 0.00 Canceled 2019-08-12 2019-07-18 2019-09-02 2019-08-05 2019-10-16 2019-11-13 2019-12-13 2020-01-12 2020-02-16 2021-02-15 adressage dans le cadre de l d Governance ection l a mise en œuvre du projet d' adressage du District Autono me d'Abidjan CI-PACOGA-72706-CS-QCBS / Recrutement d'un Consulta nt/Firme pour la réalisation d' Urban Planning, Services an Quality And Cost- IDA / 62720 Post Open - National 150,000.00 0.00 Canceled 2019-01-22 2019-02-12 2019-03-28 2019-04-25 2019-05-25 2019-06-29 2019-08-03 2020-08-02 une étude sur la lutte contre d Governance Based Selection le harcèlement et la prise en compte du genre dans les tra nsports publics à Abidjan CI-PACOGA-72697-CS-QCBS / Recrutement d'un Consulta nt/Firme pour la réalisation d' Urban Planning, Services an Quality And Cost- IDA / 62720 Post Open - National 150,000.00 0.00 Canceled 2019-01-05 2019-01-26 2019-03-11 2019-04-08 2019-05-08 2019-06-12 2019-07-17 2020-07-16 une étude pour la mise en pl d Governance Based Selection ace de mesures incitatives a l'endroit des transporteurs ar tisanaux a Abidjan Page 4 CI-PACOGA-86852-CS-QCBS / Recrutement d'un consultan t pour les études de construc Urban Planning, Services an Quality And Cost- IDA / 62720 Post Open - National 1,013,820.00 0.00 Canceled 2019-08-15 2019-11-13 2019-09-05 2019-10-19 2019-11-16 2019-12-16 2020-01-20 2020-02-24 2021-02-23 tion d'une plateforme logistiq d Governance Based Selection ue, y compris le port sec, la z one logistique et un parking de camions lourds. CI-PACOGA-123069-CS-QBS / Recrutement d'un cabinet d Logistics Services and Comp Quality Based Sel e consultants pour le renforc IDA / 62720 Post Open - National 250,000.00 0.00 Signed 2019-07-24 2021-03-01 2019-08-14 2021-03-15 2019-09-27 2021-11-09 2019-10-25 2022-03-04 2019-11-24 2022-04-20 2019-12-24 2022-05-27 2020-01-28 2021-01-27 etitiveness ection ement du cadre institutionnel et règlementaire de la logisti que en Côte d'Ivoire CI-PACOGA-123072-CS-QCB S / Recrutement d'un cabinet de consultants pour l'étude d Logistics Services and Comp Quality And Cost- IDA / 62720 Post Open - National 150,000.00 52,821.30 Signed 2019-08-21 2020-06-17 2019-09-11 2020-08-04 2019-10-25 2021-01-15 2019-11-22 2021-01-27 2019-12-22 2021-02-26 2020-01-26 2021-03-26 2020-03-01 2021-06-19 2021-03-01 es besoins en renforcement etitiveness Based Selection des capacités des acteurs de logistiques en Côte d'Ivoire. CI-PACOGA-86521-CS-QBS / Recrutement d'un Consultant /Firme pour la réalisation d'ét Urban Planning, Services an Quality Based Sel Open - Internationa IDA / 62720 Post 500,000.00 0.00 Canceled 2019-10-21 2020-08-18 2019-11-11 2020-08-25 2019-12-25 2021-02-15 2020-01-22 2020-02-21 2020-03-22 2020-04-26 2021-04-26 udes à la création d'une stru d Governance ection l cture métropolitaine de coor dination de la mise en œuvre du SDUGA CI-PACOGA-135566-CS-QBS / Recrutement d'une firme po ur les services d'assistance t Urban Planning, Services an Quality Based Sel IDA / 62720 Post Open - National 110,000.00 324,171.72 Signed 2019-10-07 2019-11-11 2019-10-28 2020-01-14 2019-12-11 2020-05-22 2020-01-08 2020-07-14 2020-02-07 2020-07-30 2020-03-08 2020-10-23 2020-04-12 2020-10-27 2021-04-12 echnique pour l'opérationnali d Governance ection sation de la future autorité or ganisatrice de la mobilité urb aine du grand Abidjan. CI-PACOGA-149740-CS-CQS / Recrutement d’une firme po ur l’Etude d’Impact Environn ementale et Sociale (EIES) d Urban Planning, Services an Consultant Qualifi IDA / 62720 Post Limited 37,000.00 0.00 Canceled 2019-12-16 2019-12-30 2020-01-29 2020-03-04 2020-08-31 u projet d’aménagement des d Governance cation Selection ouvrages de drainage des ea ux pluviales de la GESCO et P ort-Bouet II dans la commune de Yopougon. CI-PACOGA-149741-CS-CQS / Recrutement d’une firme po ur l’Etude d’Impact Environn Urban Planning, Services an Consultant Qualifi IDA / 62720 Post Limited 37,000.00 0.00 Canceled 2019-12-16 2020-01-20 2019-12-30 2019-10-03 2020-01-29 2020-03-04 2020-08-31 ementale et Sociale (EIES) d d Governance cation Selection u projet de construction des ouvrages de drainage des ea ux pluviales à Anonkoua, Abo bo. CI-PACOGA-149742-CS-CQS / Recrutement d’une firme po ur l’Etude d’Impact Environn Urban Planning, Services an Consultant Qualifi IDA / 62720 Post Limited 71,000.00 0.00 Canceled 2019-12-17 2020-01-20 2019-12-31 2019-10-03 2020-01-30 2020-03-05 2020-09-01 ementale et Sociale (EIES) du d Governance cation Selection projet de construction des ou vrages de drainage des eaux pluviales de Grand-Bassam. CI-PACOGA-72693-CS-QCBS / Recrutement d'un Consulta nt/Firme pour la réalisation d' Urban Planning, Services an Quality Based Sel IDA / 62720 Post Open - National 300,000.00 0.00 Canceled 2018-12-27 2019-01-17 2019-03-02 2019-03-30 2019-04-29 2019-05-29 2019-07-03 2020-07-02 une étude de restructuration d Governance ection des lignes de transport de la SOTRA et du transport artisa nal a Abidjan CI-PACOGA-72713-CS-QCBS / Recrutement d'un consultan t/Firme pour l'élaboration du Urban Planning, Services an Quality And Cost- IDA / 62720 Post Open - National 300,000.00 0.00 Canceled 2018-12-18 2019-01-08 2019-02-21 2019-03-21 2019-04-20 2019-05-25 2019-06-29 2020-06-28 PAR pour la mise en place d' d Governance Based Selection un transport en site propre (T CSP) pour la desserte EST-Ou est d'Abidjan CI-PACOGA-72691-CS-QCBS / Recrutement d'un consultan t/firme pour le réalisation de Urban Planning, Services an Quality And Cost- Open - Internationa IDA / 62720 Post 300,000.00 0.00 Canceled 2018-12-10 2018-12-31 2019-02-13 2019-03-13 2019-04-12 2019-05-17 2019-06-21 2020-06-20 l'EIES et le CGES pour le mise d Governance Based Selection l en place d'un transport en co mmun sur le site propre de la desserte Est-Ouest Abidjan CI-PACOGA-149784-CS-QCB S / Recrutement d'un Consult ant/Firme pour l'élaboration Logistics Services and Comp Quality And Cost- du cahier de charges relatif à IDA / 62720 Post Open - National 60,000.00 102,127.50 Signed 2020-01-09 2020-08-11 2020-01-30 2020-08-12 2020-03-14 2020-12-02 2020-04-11 2021-01-28 2020-05-11 2021-05-14 2020-06-15 2021-06-02 2020-07-20 2021-08-15 2021-07-20 etitiveness Based Selection la création d'une plateforme i nformatique de gestion des fl ux de camions dans la zone portuaire. CI-PACOGA-149743-CS-CQS / Recrutement d’une firme po ur l’Etude d’Impact Environn Urban Planning, Services an Consultant Qualifi ementale et Sociale (EIES) d IDA / 62720 Post Limited 46,000.00 0.00 Canceled 2019-12-30 2020-01-20 2020-01-13 2019-11-26 2020-02-12 2020-03-18 2020-09-14 d Governance cation Selection u projet de construction des ouvrages de drainage des ea ux pluviales de Bouaké dans le cadre du PARU. CI-PACOGA-149761-CS-QBS / Etude du financement dura ble, de la viabilité économiqu Urban Planning, Services an Quality Based Sel Open - Internationa IDA / 62720 Post 350,000.00 0.00 Canceled 2020-01-13 2020-01-20 2020-02-03 2020-01-22 2020-03-18 2020-04-15 2020-05-15 2020-06-14 2020-07-19 2021-07-19 e et des réformes fiscales de d Governance ection l la gestion des déchets solide s en Côte d’Ivoire dans le cad re du PARU. CI-PACOGA-150807-CS-QBS / Recrutement d'une firme po ur les prestations d'assistanc Urban Planning, Services an Quality Based Sel Open - Internationa IDA / 62720 Prior 150,000.00 0.00 Canceled 2020-01-08 2021-03-24 2020-01-29 2021-03-26 2020-03-13 2020-04-10 2020-05-10 2020-06-09 2020-07-14 2021-07-14 e à la réalisation des travaux d Governance ection l de balisage des circuits de tr ansports lagulaires d'Abidjan CI-PACOGA-152960-CS-QBS / Recrutement d'une assistan ce technique/Firme à la centr Urban Planning, Services an Quality Based Sel Open - Internationa IDA / 62720 Prior 7,100,000.00 12,445,269.02 Signed 2020-01-15 2020-01-14 2020-02-05 2020-01-16 2020-03-20 2020-06-09 2020-04-17 2020-09-02 2020-05-17 2020-11-11 2020-06-16 2021-04-27 2020-07-21 2021-06-16 2021-07-21 ale d'adressage dans le cadr d Governance ection l e de la mise en oeuvre du pr ojet d'adressage du District A utonome d'Abidjan Page 5 CI-PACOGA-219324-CS-QCB S / Recrutement d'un consult Urban Planning, Services an Quality And Cost- Open - Internationa Under Implement ant/firme pour la réalisation IDA / 62720 Post 400,000.00 0.00 2021-02-18 2021-06-10 2021-03-11 2021-07-08 2021-04-24 2021-11-08 2021-05-22 2022-03-04 2021-06-21 2022-03-04 2021-07-26 2022-09-14 2021-08-30 2022-08-30 d Governance Based Selection l ation des études des mobilités "do ux" (Vélo, moto, engins non motorisés) à Abidjan CI-PACOGA-219325-CS-QBS / Recrutement d'un consultan t/firme pour la réalisation d'é Urban Planning, Services an Quality Based Sel Open - Internationa IDA / 62720 Post 500,000.00 374,922.93 Completed 2021-02-22 2021-02-17 2021-03-15 2021-04-08 2021-04-28 2021-01-29 2021-05-26 2021-03-17 2021-06-25 2021-04-09 2021-07-25 2021-04-30 2021-08-29 2021-06-02 2022-08-29 2022-01-29 tudes à la création d'une stru d Governance ection l cture métropolitaine de coor dination et de mise en œuvre du SDUGA. CI-PACOGA-219343-CS-QCB S / Recrutement d'un consult ant/firme pour le suivi et con Urban Transport Infrastructu Quality And Cost- Open - Internationa IDA / 62720 Prior 4,600,000.00 1,551,040.25 Signed 2021-05-10 2021-04-12 2021-05-31 2021-04-16 2021-07-14 2021-09-24 2021-08-11 2021-12-08 2021-09-10 2022-04-04 2021-10-15 2022-05-23 2021-11-19 2022-08-31 2022-11-19 trôle des travaux d'aménage re Based Selection l ment de l'autoroute périphéri que Y4 section 3: Autoroute du nord-Autoroute de Dabou CI-PACOGA-219346-CS-CQS / Recrutement d'un consulta nt/firme pour l'implantation d Urban Transport Infrastructu Consultant Qualifi IDA / 62720 Post Limited 27,272.72 0.00 Canceled 2021-02-26 2021-03-08 2021-03-12 2021-04-11 2021-05-16 2021-11-12 e 15 km de l'autoroute périp re cation Selection hérique Y4 section 3 : Autoro ute du Nord-Autoroute de Da bou CI-PACOGA-219350-CS-CQS / Recrutement d'un consultan t/firme pour l'étude de faisab ilité technique, socio-économ Logistics Services and Comp Consultant Qualifi Open - Internationa IDA / 62720 Post 300,000.00 299,689.00 Signed 2021-02-23 2021-02-15 2021-03-16 2021-02-17 2021-04-29 2021-04-15 2021-05-29 2021-05-11 2021-07-03 2021-06-01 2021-12-30 ique, institutionnelle et finan etitiveness cation Selection l cière d'un transport lagunair e de fret, entre le site du Port autonome d'Abidjan et la co mmune de Songon. CI-PACOGA-223005-CS-QCB S / Recrutement d'une firme pour la réalisation des étude Urban Planning, Services an Quality And Cost- Open - Internationa s de faisabilité du projet de p IDA / 62720 Post 820,000.00 534,808.95 Signed 2021-03-22 2019-05-28 2021-04-12 2021-03-30 2021-05-26 2021-03-19 2021-06-23 2021-07-30 2021-07-23 2021-08-27 2021-08-27 2021-09-16 2021-10-01 2021-11-12 2022-10-01 d Governance Based Selection l réservation et de valorisation de la zone verte du Schéma Directeur d'urbanisme du Gr and Abidjan (SDUGA). CI-PACOGA-238481-CS-CQS / Recrutement d'un consultan t/Firme dans le cadre de l'étu Urban Planning, Services an Consultant Qualifi de d'Impact Environnemental IDA / 62720 Post Limited 90,909.09 70,675.79 Signed 2021-06-30 2021-06-08 2021-07-14 2021-06-21 2021-08-13 2021-07-23 2021-09-17 2021-09-01 2022-03-16 d Governance cation Selection et Social (EIES) de l'aménage ment de la voies d'accès à la gare lagunaire du Plateau et d'Abobodoumé CI-PACOGA-238483-CS-QCB S / Recrutement d'une firme pour le suivi et contrôle des t Urban Planning, Services an Quality And Cost- Under Implement IDA / 62720 Post Open - National 363,636.36 0.00 2021-07-12 2022-09-30 2021-08-02 2022-10-03 2021-09-15 2021-10-13 2021-11-12 2021-12-17 2022-01-21 2023-01-21 ravaux d'aménagement des d Governance Based Selection ation gares lagunaires d'Abobodou mé, du Plateau et des voies d 'accès aux gares lagunaires CI-PACOGA-238486-CS-QCB S / Suivi et contrôle des trava ux d'aménagement et de ré Urban Transport Infrastructu Quality And Cost- habilitation des infrastructur IDA / 62720 Post Open - National 545,454.56 571,851.37 Signed 2021-07-30 2021-10-13 2021-08-20 2021-10-21 2021-10-03 2022-03-29 2021-10-31 2022-05-12 2021-11-30 2022-05-12 2022-01-04 2022-07-26 2022-02-08 2022-09-07 2023-02-08 re Based Selection es de transport routier du Por t Autonome d'Abidjan (Ancie nnes voies prioritaires et voie s complémentaires). CI-PACOGA-238488-CS-QCB S / Recrutement d'une firme Logistics Services and Comp Quality And Cost- Open - Internationa IDA / 62720 Post 909,090.90 0.00 Canceled 2021-07-30 2021-06-08 2021-08-20 2021-10-03 2021-10-31 2021-11-30 2022-01-04 2022-02-08 2023-02-08 pour l'élaboration du schéma etitiveness Based Selection l logistique national. CI-PACOGA-238942-CS-QCB S / Recrutement d'un Consult Logistics Services and Comp Quality And Cost- Open - Internationa IDA / 62720 Post 496,450.98 452,631.11 Signed 2021-06-21 2021-06-17 2021-07-12 2021-07-19 2021-08-25 2021-11-02 2021-09-22 2022-03-04 2021-10-22 2022-04-06 2021-11-26 2022-05-11 2021-12-31 2022-07-23 2022-12-31 ant/Firme pour l'élaboration etitiveness Based Selection l du Plan national de la logistiq ue en Côte d'Ivoire. CI-PACOGA-245871-CS-QCB S / Recrutement d'un consult ant Firme pour l'élaboration Urban Planning, Services an Quality And Cost- Open - Internationa Under Implement du Plan d'Urbanisme de détai IDA / 62720 Post 1,109,200.00 0.00 2021-08-04 2021-08-04 2021-08-25 2021-09-17 2021-10-08 2022-03-02 2021-11-05 2022-04-20 2021-12-05 2022-04-29 2022-01-09 2022-09-15 2022-02-13 2023-02-13 d Governance Based Selection l ation l (PUd) des unités urbaines n °3 (Commune d'Abobo et d'A nyama) et n°4 (commune de Cocody et Bingerville) du SD UGA. CI-PACOGA-245875-CS-QCB S / Recrutement d'un consult ant (firme) pour l'élaboration Urban Planning, Services an Quality And Cost- Open - Internationa Under Implement du Plan d'Urbanisme de détai IDA / 62720 Post 1,146,000.00 0.00 2021-08-05 2021-08-04 2021-08-26 2021-09-17 2021-10-09 2022-03-02 2021-11-06 2022-04-21 2021-12-06 2022-11-28 2022-01-10 2022-10-28 2022-02-14 2023-02-14 d Governance Based Selection l ation l (PUd) des unités urbaines n °5 (communes de Yopougon et Songon) et n°7 (Port Auto nome d'Abidjan) du SDUGA CI-PACOGA-245897-CS-CQS / Recrutement d'un consultan t (firme) pour l'actualisation des études APD de l'aménag Urban Planning, Services an Consultant Qualifi IDA / 62720 Post Open - National 184,428.10 175,475.22 Completed 2021-08-12 2021-09-13 2021-09-02 2021-10-16 2020-01-10 2021-11-15 2020-01-20 2021-12-20 2020-02-28 2022-06-18 2021-10-28 ement d'ouvrages de drainag d Governance cation Selection e des eaux pluviales à Gesco , route de Dabou, commune de Yopougon, dans le cadre de la PPF du PARU. CI-PACOGA-245907-CS-CQS / Recrutement d'u consultant (firme) pour l'Élaboration du Constat d’Impact Environne Urban Planning, Services an Consultant Qualifi IDA / 62720 Post Limited 36,854.55 34,985.01 Completed 2021-08-13 2021-09-13 2021-08-27 2019-10-03 2021-09-26 2019-11-26 2021-10-31 2020-01-07 2022-04-29 2020-03-24 mental et Social (CIES) du pr d Governance cation Selection ojet d’aménagement de la cu vette d’Anonkoua dans la co mmune d’Abobo, dans cadre du Fonds de Préparation du P ARU. CI-PACOGA-245911-CS-CQS / Recrutement d'un consultan t (firme) pour l'Élaboration d e l'EIES du projet d'aménage Urban Planning, Services an Consultant Qualifi IDA / 62720 Post Limited 70,727.28 67,139.46 Completed 2021-08-16 2021-09-13 2021-08-30 2019-11-13 2021-09-29 2019-12-03 2021-11-03 2020-01-21 2022-05-02 2020-03-04 ment des ouvrages des eaux d Governance cation Selection pluviales de ville de Grand-B assam dans le cadre du Proje t de l'Assainissement et de la Résilience Urbaine (PARU) Page 6 CI-PACOGA-245914-CS-CQS / Recrutement d'un consultan t (firme) pour l'Élaboration d e l'EIES du projet d'aménage Urban Planning, Services an Consultant Qualifi IDA / 62720 Post Limited 46,717.28 45,324.84 Completed 2021-08-17 2021-09-13 2021-08-31 2019-10-03 2021-09-30 2019-12-02 2021-11-04 2020-01-07 2022-05-03 2020-02-21 ment des ouvrages des eaux d Governance cation Selection pluviales de la ville de Bouak é dans le cadre de la PPF du Projet de l'Assainissement et de la Résilience Urbaine (PAR U). CI-PACOGA-245932-CS-QBS / Recrutement d'une firme po Program Management and M Quality Based Sel Open - Internationa ur l'Assistance à la Maitrise d IDA / 62720 Post 980,100.00 751,917.75 Signed 2021-09-02 2021-08-07 2021-09-23 2021-09-07 2021-11-06 2021-12-07 2021-12-04 2022-02-03 2022-01-03 2022-03-03 2022-02-02 2022-04-15 2022-03-09 2022-05-26 2023-03-09 onitoring ection l 'Ouvrage (AMO) pour la mise en œuvre des activités du P ACOGA CI-PACOGA-264222-CS-QBS / Recrutement d'un consultan t/firme pour les études APD e Logistics Services and Comp Quality Based Sel Open - Internationa IDA / 62720 Post 150,000.00 213,023.98 Signed 2021-11-23 2021-11-19 2021-12-14 2021-11-23 2022-01-27 2021-12-02 2022-02-24 2022-03-04 2022-03-26 2022-03-31 2022-04-25 2022-07-22 2022-05-30 2022-09-08 2023-05-30 t l'élaboration du DAO pour l etitiveness ection l es travaux de balisage dans l es circuits de transport lagun aire du district d'Abidjan. CI-PACOGA-222175-CS-QCB S / Recrutement d'une firme pour l'élaboration du Plan d'U Urban Planning, Services an Quality And Cost- Open - Internationa rbanisme de Détail (PUd) de l IDA / 62720 Prior 1,500,000.00 0.00 Canceled 2021-03-22 2021-04-12 2021-05-26 2021-06-23 2021-07-23 2021-08-27 2021-10-01 2022-10-01 d Governance Based Selection l 'unité urbaine n°3 (Commun e d'Abobo et d'Ayama) du Sc héma Directeur d'Urbanisme du Grand Abidjan (SDUGA). CI-PACOGA-222180-CS-QCB S / Recrutement d'une firme pour l'élaboration du Plan d'U Urban Planning, Services an Quality And Cost- Open - Internationa rbanisme de Détails (PUd) de IDA / 62720 Prior 1,000,000.00 0.00 Canceled 2021-03-23 2021-04-13 2021-05-27 2021-06-24 2021-07-24 2021-08-28 2021-10-02 2022-10-02 d Governance Based Selection l l'Unité urbaine n°4 (Commun e de Cocody et Bingerville) d u Schéma Directeur d'Urbani sme du Grand Abidjan (SDUG A). CI-PACOGA-222186-CS-QCB S / Recrutement d'une firme pour l'élaboration du Plan d'U Urban Planning, Services an Quality And Cost- Open - Internationa rbanisme de Détail (PUd) n°7 IDA / 62720 Prior 1,000,000.00 0.00 Canceled 2021-03-23 2021-04-13 2021-05-27 2021-06-24 2021-07-24 2021-08-28 2021-10-02 2022-10-02 d Governance Based Selection l (Port Autonome d'Abidjan) du Schéma Directeur d'Urbanis me du Grand Abidjan (SDUG A). CI-PACOGA-222185-CS-QCB S / Recrutement d'une firme pour l'élaboration des Plans d Urban Planning, Services an Quality And Cost- Open - Internationa 'Urbanisme de détail (PUd) n IDA / 62720 Prior 1,500,000.00 0.00 Canceled 2021-03-23 2021-04-13 2021-05-27 2021-06-24 2021-07-24 2021-08-28 2021-10-02 2022-10-02 d Governance Based Selection l ° 5 (Commune de Yopougon et de Songon) du Schéma Dir ecteur d'Urbanisme du Grand Abidjan (SDUGA). CI-PACOGA-123073-CS-QCB S / Recrutement d'une firme Logistics Services and Comp Quality And Cost- pour les études APS/APD pou IDA / 62720 Post Open - National 350,000.00 0.00 Canceled 2019-11-19 2019-11-13 2019-12-10 2020-01-23 2020-02-20 2020-03-21 2020-04-25 2020-05-30 2021-05-30 etitiveness Based Selection r l'aménagement d'un parkin g Poids Lourds au PK 26 à Abi djan en Côte d'Ivoire CI-PACOGA-123074-CS-QCB S / Recrutement d'un cabinet Logistics Services and Comp Quality And Cost- de consultants pour l'étude d IDA / 62720 Post Open - National 200,000.00 0.00 Canceled 2019-11-01 2019-11-22 2020-01-05 2020-02-02 2020-03-03 2020-04-07 2020-05-12 2021-05-12 etitiveness Based Selection e planification et de construc tion de parking Poids Lourds à Abidjan CI-PACOGA-286824-CS-QBS / Recrutement d'un Consulta nt/Firme pour la réalisation d Urban Transport Infrastructu Quality Based Sel Open - Internationa Under Implement es études techniques d'amén IDA / 62720 Post 759,700.00 0.00 2022-06-06 2022-04-07 2022-06-27 2022-04-23 2022-08-10 2022-09-07 2022-10-07 2022-11-06 2022-12-11 2023-12-11 re ection l ation agement et de bitumage de l a route interurbaine Dianra-B ouandougou (113 km) dans l a région du BERE. CI-PACOGA-286673-CS-QCB S / Recrutement d'un consult ant/firme pour le suivi et con Logistics Services and Comp Quality And Cost- Open - Internationa Pending Impleme IDA / 62720 Prior 1,636,363.64 0.00 2022-09-23 2022-10-14 2022-11-27 2022-12-25 2023-01-24 2023-02-28 2023-04-04 2024-04-03 trôle des travaux de construc etitiveness Based Selection l ntation tion et d'installation des équ ipements techniques de la ca sse automobile. CI-PACOGA-295287-CS-CQS / Recrutement d'un Consulta nt/Firme pour la réalisation d Urban Transport Infrastructu Consultant Qualifi Under Implement e l'Etude d'Impact Environne IDA / 62720 Post Limited 180,647.27 0.00 2022-06-30 2022-05-17 2022-07-14 2022-06-02 2022-08-13 2022-07-26 2022-09-17 2023-03-16 re cation Selection ation mental et Social (EIES) du bit umage de la route interurbai ne Dianra-Bouandougou (113 km) dans la région du Béré. CI-PACOGA-295288-CS-CQS / Recrutement d'un Consulta nt/Firme pour la réalisation d Urban Transport Infrastructu Consultant Qualifi Pending Impleme u Plan d'Action et de Réinstal IDA / 62720 Post Limited 142,923.75 0.00 2022-07-28 2022-08-11 2022-09-10 2022-10-15 2023-04-13 re cation Selection ntation lation des travaux de bituma ge de la route interurbaine Di anra-Bouandougou (113 Km) dans la région du Béré. CI-PACOGA-301226-CS-CQS / Recrutement d'un consultan t/Firme pour la réalisation et l'élaboration des pièces tech Urban Transport Infrastructu Consultant Qualifi Open - Internationa Under Implement niques du DAO pour la réhabi IDA / 62720 Post 179,500.00 0.00 2022-06-28 2022-06-24 2022-07-19 2022-06-27 2022-09-01 2022-10-01 2022-11-05 2023-05-04 re cation Selection l ation litation des routes rurales da ns les régions du Poro, du Tc hologo, de la Bagoué, du Bou kani, du Kabadougou et du F olon ( PCR-NCI). CI-PACOGA-305572-CS-CQS / Recrutement d’un Consulta nt/Firme pour la réalisation d es études techniques et élab Urban Transport Infrastructu Consultant Qualifi Under Implement oration de pièces techniques IDA / 62720 Post Open - National 143,000.00 0.00 2022-08-10 2022-08-01 2022-08-31 2022-08-03 2022-10-14 2022-11-13 2022-12-18 2023-06-16 re cation Selection ation du Dossier d’Appel d’Offres ( DAO) pour l’entretien de rout es rurales dans les régions d u BAFING, du BERE, du WOR ODOUGOU (Mission 1) du PC R-CI Page 7 CI-PACOGA-305578-CS-CQS / Recrutement d’un Consulta nt/Firme pour la réalisation d es études techniques et élab Urban Transport Infrastructu Consultant Qualifi Under Implement oration de pièces techniques IDA / 62720 Post Open - National 143,000.00 0.00 2022-08-31 2022-08-01 2022-09-21 2022-08-03 2022-11-04 2022-12-04 2023-01-08 2023-07-07 re cation Selection ation du Dossier d’Appel d’Offres ( DAO) pour la l’entretien de ro utes rurales dans les régions du FOLON et du KABADOUGO U (Mission 2) du PCR-CI. CI-PACOGA-305582-CS-CQS / Recrutement d’un Consulta nt/Firme pour la réalisation d es études techniques et élab Urban Transport Infrastructu Consultant Qualifi Under Implement oration de pièces techniques IDA / 62720 Post Open - National 143,000.00 0.00 2022-08-31 2022-08-01 2022-09-21 2022-08-03 2022-11-04 2022-12-04 2023-01-08 2023-07-07 re cation Selection ation du Dossier d’Appel d’Offres ( DAO) pour la l’entretien de ro utes rurales dans les régions du PORO, du TCHOLOGO et d u BAGOUE (Mission 3) du PC RCI CI-PACOGA-305583-CS-CQS / Recrutement d’un Consulta nt/Firme pour la réalisation d es études techniques et élab Urban Transport Infrastructu Consultant Qualifi Under Implement oration de pièces techniques IDA / 62720 Post Open - National 143,000.00 0.00 2022-09-06 2022-08-01 2022-09-27 2022-08-03 2022-11-10 2022-12-10 2023-01-14 2023-07-13 re cation Selection ation du Dossier d’Appel d’Offres ( DAO) pour la l’entretien de ro utes rurales dans les régions du BOUKANI et du GONTOUG O (Mission 4) du PCRCI. CI-PACOGA-305586-CS-CQS / Recrutement d’un Consulta nt/Firme pour la réalisation d es études techniques et élab Urban Transport Infrastructu Consultant Qualifi Under Implement IDA / 62720 Post Open - National 112,500.00 0.00 2022-09-06 2022-08-01 2022-09-27 2022-08-03 2022-11-10 2022-12-10 2023-01-14 2023-07-13 oration de pièces techniques re cation Selection ation du Dossier d’Appel d’Offres ( DAO) pour la l’entretien de ro utes rurales dans les régions du HAMBOL (Mission 5) du P CRCI. CI-PACOGA-305589-CS-CQS / Recrutement d’un Consulta nt/Firme pour la réalisation d es études techniques et élab Urban Transport Infrastructu Consultant Qualifi Under Implement oration de pièces techniques IDA / 62720 Post Open - National 126,100.00 0.00 2022-08-31 2022-08-02 2022-09-21 2022-08-03 2022-11-04 2022-12-04 2023-01-08 2023-07-07 re cation Selection ation du Dossier d’Appel d’Offres ( DAO) pour la l’entretien de ro utes rurales par la méthode GENIS dans les régions du PO RO, du BOUKANI et du KABA DOU CI-PACOGA-307148-CS-QCB S / Recrutement d’un Consult Program Management and M Least Cost Selecti Under Implement ant/Firme pour la réalisation IDA / 62720 Post Open - National 36,363.63 0.00 2022-08-22 2022-08-02 2022-09-12 2022-08-03 2022-10-26 2022-11-23 2022-12-23 2023-01-27 2023-03-03 2023-08-30 onitoring on ation de l’audit financier des comp tes du PACOGA pour les exer cices 2022, 2023 et 2024. CI-PACOGA-308631-CS-CQS / Recrutement d'une firme po ur la réalisation de l'audit de la sécurité routière sur 400 k Urban Transport Infrastructu Consultant Qualifi Open - Internationa Under Implement IDA / 62720 Post 145,454.55 0.00 2022-09-30 2022-08-16 2022-10-21 2022-08-26 2022-12-04 2023-01-03 2023-02-07 2023-08-06 m de routes rurales à réhabili re cation Selection l ation ter/entretenir dans les région s de la Bagoué, du Bounkani, du Kabadougou, du Poro, du Tchologo et du Folon. pour le PCR-CI. CI-PACOGA-238484-CS-QCB S / Recrutement d'une firme pour l'étude de faisabilité tec Urban Planning, Services an Quality And Cost- IDA / 62720 Post Open - National 181,818.18 0.00 Canceled 2021-07-12 2021-08-02 2021-09-15 2021-10-13 2021-11-12 2021-12-17 2022-01-21 2023-01-21 hnique, économique, financiè d Governance Based Selection re et sociale d'un projet pilot e d'un parking payant dans l a commune du Plateau CI-PACOGA-317034-CS-CQS / Recrutement d'un consultan t/firme pour la réalisation des Urban Transport Infrastructu Consultant Qualifi Open - Internationa Under Implement études de délimitation et de IDA / 62720 Post 203,636.36 0.00 2022-10-19 2022-10-05 2022-11-09 2022-10-07 2022-12-23 2023-01-22 2023-02-26 2023-08-25 re cation Selection l ation balisage des pistes à bétail p our une gestion durable des r essources naturelles dans le cadre des activités du PCR - CI. CI-PACOGA-317028-CS-CQS / Recrutement d'un consultan t/firme pour la préparation à l a mise en place de bosquets Urban Transport Infrastructu Consultant Qualifi Under Implement IDA / 62720 Post Open - National 90,909.09 0.00 2022-10-12 2022-10-03 2022-11-02 2022-10-07 2022-12-16 2023-01-15 2023-02-19 2023-08-18 villageois dans les 6 régions f re cation Selection ation rontalière du Nord de la Côte d'Ivoire (Bagoué, Bounkani, F olon, Kabadougou, Poro et Tc hologo), dans le cadre du PC R-CI. CI-PACOGA-360853-CS-CQS / RECRUTEMENT D’UN CONS ULTANT (FIRME) POUR L’APP UI A L’ELABORATION DU PLA Urban Transport Infrastructu Consultant Qualifi Under Implement N DE RESTAURATION DES M IDA / 62720 Post Open - National 50,000.00 0.00 2023-05-15 2023-05-10 2023-05-30 2023-05-10 2023-06-29 2023-07-04 2023-07-20 2023-09-03 re cation Selection ation OYENS DE SUBSISTANCE DE PERSONNES AFFECTEES PAR LA CONSTRUCTION DES SECT IONS 2 ET 3 DE L’AUTOROUT E DE CONTOURNEMENT Y4 D ’ABIDJAN INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-PACOGA-72710-CS-INDV / Recrutement d'un consultant individuel pour l'élaboration Urban Planning, Services an Individual Consult IDA / 62720 Post Limited 100,000.00 28,947.04 Completed 2019-01-02 2018-12-11 2019-01-07 2019-01-09 2019-02-13 2019-02-11 2019-03-20 2019-02-23 2019-06-18 2019-04-12 du CPR pour la mise en place d Governance ant Selection d'un transport en commun su r site propre (TCSP) pour la d esserte Est-Ouest d'Abidjan CI-PACOGA-72274-CS-CDS / Contrat avec le BNETD pour assistance à maîtrise d'Ouvra Urban Planning, Services an IDA / 62720 Post Direct Selection Direct 200,000.00 227,402.18 Signed 2018-11-12 2018-10-22 2018-11-22 2018-10-01 2019-01-26 2018-12-14 2019-07-25 ge (AMO) pour la mise en pla d Governance ce d'un transport en commun sur site propre (TCSP) pour la desserte est-Ouest d'Abidjan Page 8 CI-PACOGA-72694-CS-CQS / Recrutement d'un consultant Individuel pour l'élaboration Urban Planning, Services an Individual Consult IDA / 62720 Post Open 100,000.00 35,297.30 Completed 2018-12-12 2018-12-11 2019-01-30 2019-01-07 2019-02-20 2019-02-28 2019-03-27 2019-03-05 2019-09-23 2019-03-05 du CGES pour le mise en plac d Governance ant Selection e d'un transport en commun sur site propre (TCSP) pour le desserte Est-Ouest Abidjan CI-PACOGA-86522-CS-CDS / Contrat PACOGA / INPHB, pou Urban Planning, Services an r la mise en œuvre d'un mast IDA / 62720 Post Direct Selection Direct 705,416.00 728,083.31 Signed 2018-12-05 2019-01-07 2018-12-15 2020-03-18 2019-02-18 2020-04-02 2019-08-17 d Governance er professionnel en Transport et Aménagement Urbain CI-PACOGA-86526-CS-CDS / Contrat avec le Groupement IGDP/AFRICURBA/LAASE pour Urban Planning, Services an IDA / 62720 Post Direct Selection Direct 259,035.00 0.00 Canceled 2019-02-05 2019-02-15 2019-04-21 2019-10-18 l'élaboration du répertoire de d Governance s toponymes et odonymes de s voies et lieux du District d' Abidjan CI-PACOGA-86536-CS-CDS / Convention PACOGO / AGER Program Management and M OUTE, pour la mise en œuvre IDA / 62720 Prior Direct Selection Direct 2,000,000.00 1,275,980.92 Signed 2018-11-29 2020-11-24 2018-12-09 2018-11-30 2019-02-12 2018-12-06 2019-08-11 onitoring de la composante 2 « Amélio ration des infrastructures de transport » CI-PACOGA-86542-CS-CDS / Convention PACOGA de gesti Program Management and M on judiciaire (Coordination te IDA / 62720 Prior Direct Selection Direct 4,762,000.00 4,818,786.23 Signed 2018-12-03 2021-03-26 2018-12-13 2018-11-30 2019-02-16 2018-12-06 2019-08-15 onitoring chnique, Suivi et évaluation, Passation des marchés et ge stion financière) CI-PACOGA-92020-CS-CDS / Contrat avec le groupement ALLNEXT TERRABO Ingénieu Urban Planning, Services an IDA / 62720 Post Direct Selection Direct 145,515.12 143,751.84 Completed 2018-12-19 2018-08-14 2018-12-29 2019-01-28 2019-03-04 2019-02-07 2019-08-31 2021-04-03 r Conseil, pour compléments d Governance de faisabilité pour la mise en œuvre de l'adressage d'Abidj an CI-PACOGA-86523-CS-CDS / Contrat PACOGA/INPC (Franc Urban Planning, Services an e) pour la mise en œuvre d'u IDA / 62720 Prior Direct Selection Direct 2,209,023.45 2,198,097.16 Signed 2018-12-05 2018-12-28 2018-12-15 2019-10-01 2019-02-18 2019-03-27 2019-08-17 d Governance n Master Professionnel en Tr ansport et en aménagement urbain CI-PACOGA-109627-CS-CDS / Contrat avec le cabinet LIN ER ENVIRONNEMENT pour l'E Urban Transport Infrastructu IDA / 62720 Post Direct Selection Direct 179,490.91 178,753.29 Completed 2019-04-09 2019-04-09 2019-04-19 2019-05-22 2019-06-23 2019-05-28 2019-12-20 2019-06-28 valuation à mi parcours de la re mise en oeuvre du Plan d'Act ion et de Réinstallation (PAR) du 4ème pont CI-PACOGA-109628-CS-CDS / Contrat avec le cabinet EGI Urban Transport Infrastructu S pour la réalisation de l'Etud IDA / 62720 Post Direct Selection Direct 109,090.91 108,729.69 Completed 2019-04-10 2019-09-02 2019-04-20 2019-10-02 2019-06-24 2019-05-30 2019-12-21 2019-06-29 re e d'Avant Projet Sommaire (A PS) du design du 4ème pont. CI-PACOGA-109629-CS-INDV / Recrutement d'un Consulta Urban Transport Infrastructu Individual Consult nt Individuel pour assiter la t IDA / 62720 Post Limited 18,182.00 19,129.00 Completed 2019-04-10 2019-04-09 2019-04-15 2019-04-09 2019-05-06 2019-06-11 2019-06-10 2019-06-13 2019-12-07 2019-06-13 re ant Selection ask force pour l'elaboration d u PPSD du Projet de Mobilité Urbaine d'Abidjan (PMUA) CI-PACOGA-123006-CS-INDV / Recrutement d'un consultan t Individuel pour la mise à jo ur des études APD pour les tr Urban Planning, Services an Individual Consult IDA / 62720 Post Open 181,818.00 0.00 Canceled 2019-09-18 2019-11-06 2019-11-27 2020-01-01 2020-06-29 avaux de drainage des eaux d Governance ant Selection pluviales et préparation des Dossiers d'Appels d'Offres d ans le cadre de la préparatio n du Projet de Résilience Urb aine. CI-PACOGA-123032-CS-INDV / Recrutement d'un Consulta nt Individuel pour l'élaboratio Urban Planning, Services an Individual Consult IDA / 62720 Post Limited 68,181.00 0.00 Canceled 2019-08-20 2019-08-25 2019-09-15 2019-10-20 2020-04-17 n du Cadre de Gestion Enviro d Governance ant Selection nnementale et Sociale (CGES ) du Projet de Résilience Urb aine. CI-PACOGA-123035-CS-INDV / Recrutement d'un Consulta Urban Planning, Services an Individual Consult IDA / 62720 Post Limited 68,181.00 0.00 Canceled 2019-08-22 2019-07-29 2019-08-27 2019-08-22 2019-09-17 2019-10-22 2020-04-19 nt Individuel pour l'élaboratio d Governance ant Selection n du CPR du Projet de Résilie nce Urbaine CI-PACOGA-123038-CS-INDV / Recrutement d'un Consulta Urban Planning, Services an Individual Consult nt Individuel pour l'élaboratio IDA / 62720 Post Limited 18,181.00 0.00 Canceled 2019-08-28 2019-09-02 2019-09-23 2019-10-28 2020-04-25 d Governance ant Selection n du Plan Engagement Social et environnemental CI-PACOGA-123039-CS-INDV / Recrutement d'un Consulta nt Individuel pour l'élaboratio Urban Planning, Services an Individual Consult IDA / 62720 Post Limited 18,181.00 0.00 Canceled 2019-08-30 2019-09-04 2019-09-25 2019-10-30 2020-04-27 n du Plan Engagement Social d Governance ant Selection et Environnemental dans le c adre de la préparation du Pro jet de Résilience Urbaine. CI-PACOGA-123042-CS-INDV / Recrutement d'un Consulta Urban Planning, Services an Individual Consult nt Individuel pour l'élaboratio IDA / 62720 Post Limited 18,181.00 0.00 Canceled 2019-08-30 2019-09-04 2019-09-25 2019-10-30 2020-04-27 d Governance ant Selection n des Mécanisme de Gestion des Plaintes (GRM) du Projet de Résilience Urbaine CI-PACOGA-86539-CS-CDS / Convention PACOGA / DGTTC , pour l'appui à la mise en œ uvre des sous composantes Program Management and M 1.2 « Gouvernance municipal IDA / 62720 Post Direct Selection Direct 1.00 0.00 Canceled 2019-08-20 2019-08-30 2019-11-03 2020-05-01 onitoring e et renforcement des capaci tés institutionnelles » 1.3 « S ervices Urbains » et la comp osante 3 « Services logistiqu es et compétitivité » Page 9 CI-PACOGA-86537-CS-CDS / Convention PACOGA / District Autonome d'Abidjan (DAA) p Program Management and M our la mise en œuvre de la s IDA / 62720 Post Direct Selection Direct 1.00 0.00 Canceled 2018-11-28 2018-12-08 2019-02-11 2019-08-10 onitoring ous composante 1.3. C « Ges tion environnementale : amé nagement de la sécurité de l a ceinture verte » CI-PACOGA-86541-CS-CDS / Convention PACOGA/Port Aut onome d'Abidjan (PAA), pour Program Management and M l'appui à la mise en œuvre d IDA / 62720 Post Direct Selection Direct 1.00 0.00 Canceled 2019-01-10 2019-01-20 2019-03-26 2019-09-22 onitoring e la sous-composante « Créa tion plate-forme informatique de gestion du flux de camion au Port » CI-PACOGA-86538-CS-CDS / Convention PACOGA/DAGERU Program Management and M , pour l'appui à la mise en œ IDA / 62720 Post Direct Selection Direct 1.00 0.00 Canceled 2019-08-15 2019-08-25 2019-10-29 2020-04-26 onitoring uvre de la sous composante 1.3 C « Adressage des voies de la ville d'Abidjan » CI-PACOGA-86540-CS-CDS / Convention PACOGA / Directi on Général de l'Urbanisme et Program Management and M IDA / 62720 Post Direct Selection Direct 1.00 0.00 Canceled 2019-08-19 2019-08-29 2019-11-02 2020-04-30 du Foncier (DGUF), pour la m onitoring ise en œuvre de la sous-com posante « Planification Urbai ne » CI-PACOGA-86529-CS-CDS / Contrat avec Union Internatio nale des Transports Publics ( UITP) pour l'Assistance techni Urban Planning, Services an IDA / 62720 Post Direct Selection Direct 110,000.00 0.00 Canceled 2019-02-05 2019-02-15 2019-04-21 2019-10-18 que pour l'opérationnalisatio d Governance n de l'Autorité Organisatrice des Transports Urbains d'Abi djan (mise en place de l'orga nigramme, le manuel de proc édures...) CI-PACOGA-135572-CS-INDV / Recrutement d'un Consulta nt Individuel pour les prestati Logistics Services and Comp Individual Consult IDA / 62720 Post Open 109,090.00 0.00 Canceled 2019-10-07 2019-11-25 2019-12-16 2020-01-20 2020-07-18 ons d'assistance à la réalisati etitiveness ant Selection on des travaux de balisage d es circuits des transports lag unaires d'Abidjan. CI-PACOGA-149744-CS-INDV / Recrutement d’un Consulta nt Individuel pour l’élaboratio n du Plan d’Action et de Réin Urban Planning, Services an Individual Consult stallation des personnes affe IDA / 62720 Post Limited 55,000.00 0.00 Canceled 2019-12-16 2020-01-20 2019-12-21 2020-01-11 2020-02-15 2020-08-13 d Governance ant Selection ctée par le projet d’aménage ment des ouvrages de draina ge des eaux pluviales de GES CO et Port-Bouët II dans la co mmune de Yopougon. CI-PACOGA-149745-CS-INDV / Recrutement d’un Consulta nt Individuel pour l’élaboratio Urban Planning, Services an Individual Consult n du Plan d’Action et de Réin IDA / 62720 Post Limited 53,000.00 0.00 Canceled 2019-12-19 2020-01-20 2019-12-24 2019-11-06 2020-01-14 2020-02-18 2020-08-16 d Governance ant Selection stallation des personnes affe ctée par de construction des ouvrages de drainage des ea ux pluviales de Grand-Bassa m. CI-PACOGA-149746-CS-INDV / Recrutement d’un Consulta nt Individuel pour l’élaboratio n du Plan d’Action et de Réin Urban Planning, Services an Individual Consult IDA / 62720 Post Limited 49,000.00 0.00 Canceled 2019-12-20 2020-01-20 2019-12-25 2019-11-06 2020-01-15 2020-02-19 2020-08-17 stallation des personnes affe d Governance ant Selection ctée par le projet de construc tion des ouvrages de drainag e des eaux pluviales à Anonk oua. Kouté dans la commune d'Abobo. CI-PACOGA-149748-CS-INDV / Recrutement d’un Consulta nt Individuel pour l’élaboratio Urban Planning, Services an Individual Consult n du Plan d’Action et de Réin IDA / 62720 Post Limited 48,000.00 0.00 Canceled 2019-12-23 2020-01-20 2019-12-28 2019-12-06 2020-01-18 2020-02-22 2020-08-20 d Governance ant Selection stallation des personnes affe ctée par projet de constructi on des ouvrages de drainage des eaux pluviales de Bouak é. CI-PACOGA-149767-CS-INDV / Recrutement d’un Consulta Urban Planning, Services an Individual Consult nt Individuel pour l’élaboratio IDA / 62720 Post Limited 53,000.00 0.00 Canceled 2019-12-18 2020-01-20 2019-12-23 2019-09-18 2020-01-13 2020-02-17 2020-08-15 d Governance ant Selection n du CGES du Projet d’Assain issement et de Résilience Ur baine. CI-PACOGA-149768-CS-INDV / Recrutement d’un consulta Urban Planning, Services an Individual Consult nt individuel pour l’élaboratio IDA / 62720 Post Open 40,000.00 0.00 Canceled 2019-12-18 2020-01-20 2020-02-05 2020-02-26 2020-04-01 2020-09-28 d Governance ant Selection n du CPR du Projet d'Assainis sement et de Résilience Urb aine CI-PACOGA-149770-CS-INDV / Recrutement d’un Consulta Urban Planning, Services an Individual Consult IDA / 62720 Post Limited 19,000.00 0.00 Canceled 2019-12-16 2020-01-20 2019-12-21 2020-01-11 2020-02-15 2020-08-13 nt individuel pour l’appui à la d Governance ant Selection Task-Force pour l’élaboration du PPSD du PARU CI-PACOGA-123055-CS-INDV / Recrutement d'un Consulta nt Individuel pour l'élaboratio Logistics Services and Comp Individual Consult n du cahier de charges relatif IDA / 62720 Post Open 50,000.00 0.00 Canceled 2019-08-15 2019-10-03 2019-10-24 2019-11-28 2020-05-26 etitiveness ant Selection à la création d'une plateform e informatique de gestion de s flux de camions dans la zon e portuaire. CI-PACOGA-149733-CS-INDV / Recrutement d’un Consulta nt Individuel pour l’actualisat Urban Planning, Services an Individual Consult ion des études APD pour les t IDA / 62720 Post Open 47,000.00 0.00 Canceled 2019-12-30 2020-01-20 2020-02-17 2020-03-09 2020-04-13 2020-10-10 d Governance ant Selection ravaux de drainage des eaux pluviales et préparation du D AO de la ville de Grand-Bassa m dans le cadre du PARU. Page 10 CI-PACOGA-149731-CS-INDV / Recrutement d'un Consulta nt Individuel pour l'actualisati on des études APD pour les t Urban Planning, Services an Individual Consult IDA / 62720 Post Open 47,000.00 0.00 Canceled 2019-12-30 2020-01-20 2020-02-17 2020-03-09 2020-04-13 2020-10-10 ravaux de drainage des eaux d Governance ant Selection pluviales et préparation des Dossiers d'Appels d'Offres de la ville de Bouaké dans le ca dre du PARU. CI-PACOGA-150812-CS-INDV / Recrutement d’un Consulta nt Individuel pour l’actualisat Urban Planning, Services an Individual Consult ion des études APD pour les t IDA / 62720 Post Open 47,000.00 0.00 Canceled 2020-01-13 2020-01-20 2020-03-02 2019-11-14 2020-03-23 2020-04-27 2020-10-24 d Governance ant Selection ravaux de drainage des eaux pluviales et préparation du D AO à Anonkoi Kouté/commun e d’Abobo. CI-PACOGA-154639-CS-CDS / Convention avec l'INPHB de Yamoussoukro pour le paiem Urban Planning, Services an ent de la scolarité de six (6) IDA / 62720 Post Direct Selection Direct 39,357.42 39,192.06 Completed 2020-01-27 2020-02-26 2020-02-06 2020-03-27 2020-04-11 2020-07-10 2020-10-08 2020-10-02 d Governance boursiers du Mastère Professi onnelle en Economie des Tra nsport et aménagement urba in, pour l'année 2020. CI-PACOGA-174457-CS-INDV / Recrutement d'un consultan t Individuel pour l'actualisatio Urban Transport Infrastructu Individual Consult n du Plan d'Action de Réinsta IDA / 62720 Post Open 25,000.00 53,496.00 Completed 2020-06-10 2020-06-04 2020-07-29 2020-08-12 2020-08-19 2020-08-12 2020-09-23 2020-09-22 2021-03-22 2020-11-14 re ant Selection llation (PAR) des personnes a ffectées par la construction d e la section 2 de l'autoroute périphérique Y4 d'Abidjan. CI-PACOGA-184011-CS-INDV / Recrutement d'un consultan t individuel pour l'actualisatio Urban Transport Infrastructu Individual Consult n du Plan d'Action et de Réin IDA / 62720 Post Open 30,000.00 0.00 Canceled 2020-07-21 2020-09-08 2020-09-29 2020-11-03 2021-05-02 re ant Selection stallation (PAR) du projet d'a ménagement d'un échangeur au carrefour AKWABA dans la commune de Port-Bouët. CI-PACOGA-184012-CS-CDS / Contrat de service par SED avec le groupement de cabin ets STUDI International/TPF P Urban Transport Infrastructu LANEGE CENOR, pour l'actual IDA / 62720 Post Direct Selection Direct 229,596.82 228,461.35 Completed 2020-07-20 2020-07-20 2020-07-30 2020-10-28 2020-10-03 2020-11-25 2021-04-01 2020-12-23 re isation des études APS/APD d u nouveau design de l'aména gement d'un échangeur au c arrefour Akwaba dans la com mune de Port-Bouët. CI-PACOGA-219326-CS-CDS / Convention de service avec l'INP HB de Yamoussoukro po ur le paiement de la scolarité Urban Planning, Services an IDA / 62720 Post Direct Selection Direct 157,429.68 146,348.20 Signed 2021-02-26 2021-05-26 2021-03-08 2022-01-17 2021-05-12 2022-09-02 2021-11-08 de vingt-quatre boursiers po d Governance ur les années académiques d e 2021 à 2024 dans le cadre de la mise en œuvre du Mast ère en TAU. CI-PACOGA-219330-CS-CDS / Contrat de service avec le g roupement LAASSE/CAPEC p Urban Planning, Services an IDA / 62720 Post Direct Selection Direct 169,240.23 160,470.79 Completed 2021-02-17 2021-02-17 2021-02-27 2021-03-08 2021-05-03 2021-06-19 2021-10-30 2021-11-25 our l'élaboration du répertoir d Governance e des toponymes et odonym es des voies et lieux publics du District Autonome d'Abidj an. CI-PACOGA-219349-CS-INDV / Recrutement d'un Consulta nt Individuel pour la réalisati Urban Transport Infrastructu Individual Consult IDA / 62720 Post Limited 54,545.00 107,574.11 Completed 2021-03-31 2021-04-09 2021-04-05 2021-04-13 2021-04-26 2021-06-01 2021-05-31 2021-07-07 2021-11-27 2021-08-10 on du PAR de la section 3 de re ant Selection l'autoroute périphérique Y4 : Autoroute du Nord-Autoroute de Dabou. CI-PACOGA-238482-CS-INDV / Recrutement d'un consultan t/Firme dans le cadre de l'éla boration du Constat d'Impact Urban Planning, Services an Individual Consult IDA / 62720 Post Limited 36,363.63 18,494.71 Signed 2021-07-08 2021-06-08 2021-07-13 2021-08-03 2021-08-03 2021-09-02 2021-09-07 2021-10-26 2022-03-06 Environnemental et Social (CI d Governance ant Selection ES) de l'aménagement de la voies d'accès des gares lagu naires de Koumassi et Abobo doumé. CI-PACOGA-238487-CS-INDV / Recrutement d'un Consulta nt Individuel pour la réalisati Urban Transport Infrastructu Individual Consult IDA / 62720 Post Limited 109,090.90 79,883.55 Signed 2021-06-21 2021-06-08 2021-06-26 2021-06-15 2021-07-17 2021-07-15 2021-08-21 2021-10-01 2022-02-17 on des EIES des travaux d'a re ant Selection ménagement de l'autoroute périphérique d'Abidjan Y4 Se ction 3. CI-PACOGA-245883-CS-INDV / Recrutement d'un Consulta nt Individuel pour l'actualisati Urban Planning, Services an Individual Consult on des études APD du DAO d' IDA / 62720 Post Open 67,272.73 63,609.29 Completed 2021-08-09 2021-09-13 2021-09-27 2020-02-25 2021-10-18 2020-02-27 2021-11-22 2020-05-14 2022-05-21 2021-01-14 d Governance ant Selection ouvrages de drainage grand Bassam dans le cadre du Fon ds de Préparation du PARU (P PF). CI-PACOGA-245919-CS-INDV / Recrutement d'un consultan t individuel pour l'Elaboration du PAR du projet d'aménage Urban Planning, Services an Individual Consult ment des ouvrages de draina IDA / 62720 Post Limited 53,636.37 50,785.14 Completed 2021-08-18 2021-09-13 2021-08-23 2019-11-06 2021-09-13 2019-12-05 2021-10-18 2020-01-07 2022-04-16 2020-06-17 d Governance ant Selection ge des eaux pluviales de la vi lle de Grand-Bassam dans le cadre de la PPF du Projet de l 'Assainissement et de la Rési lience Urbaine (PARU) CI-PACOGA-245924-CS-INDV / Recrutement d'un consultan t individuel pour l'Élaboration du PAR du projet d'aménage Urban Planning, Services an Individual Consult ment des ouvrages de draina IDA / 62720 Post Limited 45,818.19 43,382.56 Completed 2021-08-19 2021-09-13 2021-08-24 2019-11-06 2021-09-14 2021-12-06 2021-10-19 2020-01-11 2022-04-17 2020-10-17 d Governance ant Selection ge des eaux pluviales de la vi lle de Bouaké dans le cadre d e la PPF du Projet de l'Assaini ssement et de la Résilience U rbaine (PARU) Page 11 CI-PACOGA-245925-CS-INDV / Recrutement d'un consultan t individuel pour l'Élaboration Urban Planning, Services an Individual Consult IDA / 62720 Post Limited 52,163.64 50,608.87 Completed 2021-08-19 2021-09-13 2021-08-24 2019-09-19 2021-09-14 2019-10-24 2021-10-19 2019-12-28 2022-04-17 2020-01-28 du CGES dans le cadre du Pr d Governance ant Selection ojet de l'Assainissement et d e la Résilience Urbaine (PAR U) CI-PACOGA-245926-CS-INDV / Recrutement d'un consultan t individuel pour l'Elaboration Urban Planning, Services an Individual Consult IDA / 62720 Post Open 39,836.37 38,649.02 Completed 2021-08-19 2021-09-13 2021-10-07 2019-10-18 2021-10-28 2019-10-04 2021-12-02 2019-11-01 2022-05-31 2019-12-01 du CPR dans le cadre du Proj d Governance ant Selection et de l'Assainissement et de l a Résilience Urbaine (PARU CI-PACOGA-245928-CS-INDV / Recrutement d'un consultan Urban Planning, Services an Individual Consult t individuel pour l'Élaboration IDA / 62720 Post Limited 28,909.09 27,372.33 Completed 2021-08-20 2021-09-13 2021-08-25 2019-12-16 2021-09-15 2020-02-18 2021-10-20 2020-03-07 2022-04-18 2020-05-13 d Governance ant Selection du document stratégique de passation de marchés (PPSD) du PARU CI-PACOGA-261122-CS-INDV / Recrutement d'un consultan Urban Planning, Services an Individual Consult t individuel pour l'appui à la IDA / 62720 Post Limited 163,636.36 289,024.20 Signed 2021-11-29 2021-12-29 2021-12-04 2021-12-22 2021-12-25 2022-01-27 2022-01-29 2022-05-11 2022-07-28 d Governance ant Selection CC-PRICI dans le cadre des a ctivités lagunaires et maritim es du PACOGA. CI-PACOGA-273568-CS-INDV / Recrutement d'un consultan t individuel pour l'audit techn Urban Transport Infrastructu Individual Consult Under Implement IDA / 62720 Post Limited 36,363.64 0.00 2022-01-25 2022-01-19 2022-01-30 2022-01-21 2022-02-20 2022-07-22 2022-03-27 2022-09-23 ique du projet d'aménageme re ant Selection ation nt et de réhabilitation des inf rastructures de transport rou tier du PAA (Voies prioritaires ). CI-PACOGA-273579-CS-INDV / Recrutement d'un consultan t individuel pour l'élaboration Urban Transport Infrastructu Individual Consult IDA / 62720 Post Limited 100,000.00 88,355.98 Signed 2022-03-30 2022-02-25 2022-04-04 2022-03-10 2022-04-25 2022-04-01 2022-05-30 2022-07-07 2022-11-26 du CGES du Projet de Connec re ant Selection tivité inclusive et d'Infrastruc ture Rurale dans le Nord de l a Côte d'Ivoire (PROCIR) CI-PACOGA-273581-CS-INDV / Recrutement d'un Consulta nt Individuel pour l'élaboratio Urban Transport Infrastructu Individual Consult n du Cadre de Politique de R IDA / 62720 Post Limited 60,000.00 53,929.19 Signed 2022-03-30 2022-02-21 2022-04-04 2022-03-08 2022-04-25 2022-04-13 2022-05-30 2022-07-07 2022-11-26 re ant Selection éinstallation (CPR) du Projet de Connectivité Inclusive et d 'Infrastructure Rurale dans le Nord de la Côte d'Ivoire (PRO CIR). CI-PACOGA-279489-CS-INDV / Recrutement d’un Expert e n génie rural dans le cadre d Urban Transport Infrastructu Individual Consult Under Implement es activités du Projet de conn IDA / 62720 Post Open 54,545.45 0.00 2022-03-30 2022-03-10 2022-05-18 2022-06-08 2022-07-13 2023-01-09 re ant Selection ation ectivité rurale pour le meilleu r accès aux services et oppor tunités économiques dans le nord de la Côte d'Ivoire (PCR- NCI). CI-PACOGA-279512-CS-INDV / Recrutement d’un CI pour l’ élaboration de 3 instruments de sauvegardes environnem Urban Transport Infrastructu Individual Consult entales et sociales (1. Plan d IDA / 62720 Post Limited 36,363.64 44,114.49 Signed 2022-02-25 2022-02-17 2022-03-02 2022-03-08 2022-03-23 2022-04-13 2022-04-27 2022-07-08 2022-10-24 re ant Selection e Gestion de la main-d’œuvr e ; 2. Plan de Mobilisation de s Parties Prenantes ; et 3. Pla n d’Engagement Environnem ental et Social) du PCR-NCI. CI-PACOGA-279517-CS-INDV / Recrutement d’un Consulta nt individuel pour l’analyse d es risques et les mesures d’a Urban Transport Infrastructu Individual Consult IDA / 62720 Post Limited 45,454.54 52,654.98 Signed 2022-02-28 2022-02-17 2022-03-05 2022-03-25 2022-03-26 2022-04-20 2022-04-30 2022-07-01 2022-10-27 tténuation Projet de connecti re ant Selection vité rurale pour le meilleur ac cès aux services et opportuni tés économiques dans le nor d de la Côte d'Ivoire (PCR-NC I). CI-PACOGA-238479-CS-INDV / Recrutement d'un Consulta nt Individuel pour la réalisati Urban Planning, Services an Individual Consult IDA / 62720 Post Limited 36,363.63 0.00 Canceled 2021-06-30 2021-07-05 2021-07-26 2021-08-30 2022-02-26 on de l'EIES pour l'aménage d Governance ant Selection ment du bassin des rossiers dans la commune de Cocody CI-PACOGA-305590-CS-INDV / Recrutement d’un Consulta nt Individuel pour l’élaboratio Urban Transport Infrastructu Individual Consult Under Implement n du manuel de procédures a IDA / 62720 Post Limited 18,181.82 0.00 2022-08-24 2022-09-19 2022-08-29 2022-10-04 2022-09-19 2022-10-27 2022-10-24 2023-04-22 re ant Selection ation dministratives, comptables e financières du Projet de conn ectivité rurale en Côte d'Ivoir e (PCR-CI). CI-PACOGA-279490-CS-INDV / Recrutement d’un Expert e n Genre et inclusion sociale d ans le cadre des activités du Urban Transport Infrastructu Individual Consult IDA / 62720 Post Open 54,545.45 0.00 Canceled 2022-03-30 2022-05-18 2022-06-08 2022-07-13 2023-01-09 Projet de connectivité rurale re ant Selection pour le meilleur accès aux se rvices et opportunités écono miques dans le nord de la Cô te d'Ivoire (PCR-NCI). CI-PACOGA-325624-CS-CDS / Contrat de service avec le L aboratoire du Bâtiment et de s Travaux Publics (LBTP) pou Urban Transport Infrastructu Pending Impleme r l'auscultation et dimension IDA / 62720 Post Direct Selection Direct - National 71,157.64 0.00 2022-12-13 2022-12-23 2023-02-26 2023-08-25 re ntation nement des structures de ch aussées pour les travaux d'a ménagement et de réhabilita tion des infrastructures de tr ansport routier du PAA. Page 12 Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: February 1,2017]: Revision 1 of Updated Procurement Plan, June 21,2017] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 4. Reference to (if any) Project Operational/Procurement Manual: Project Operations Manual for World Bank Loan Project P158099 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] July 9, 2010 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contrac (Works) t for Prior Review Summary 1.86 4 No Post 1st of the NCB contrac (Goods) t for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 110,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. July 9, 2010 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Pakistan : PK: Punjab Tourism for Economic Growth Project PLAN General Information Country: Pakistan 2017-12-21 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P158099 GPN Date: 2020-08-11 Project Name: PK: Punjab Tourism for Economic Growth Project Loan / Credit No: IDA / 59820 Punjab Tourism for Economic Growth Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PK-PTEG-40086-CW-RFB / Fa 3. Public Investment Facilit Open - Internationa Single Stage - One E 11,386,666.0 2021-09-3 IDA / 59820 Prior Request for Bids 0.00 Canceled 2018-08-31 2018-09-05 2018-10-17 2018-11-01 2018-11-22 cilities & Amenities up-gradat y l nvelope 0 0 ion at sites PK-PTEG-40077-CW-RFB / Da 3. Public Investment Facilit Single Stage - One E 2019-04-1 rbar sahib road Kartarpur - R IDA / 59820 Prior Request for Bids Open - National 588,219.00 0.00 Canceled 2018-08-06 2018-08-11 2018-09-22 2018-10-07 2018-10-21 y nvelope 9 ehabilitation of secondary & t ertiary roads PK-PTEG-40079-CW-RFB / Ta 3. Public Investment Facilit Single Stage - One E 2019-04-2 xila- Toap Mankila- Mohra - R IDA / 59820 Post Request for Bids Open - National 1,437,133.00 0.00 Canceled 2018-08-13 2018-08-18 2018-09-29 2018-10-14 2018-10-28 y nvelope 6 ehabilitation of roads PK-PTEG-40080-CW-RFB / Na 3. Public Investment Facilit Open - Internationa Single Stage - One E 2019-03-2 nkana Sahib-Farooqabad roa IDA / 59820 Post Request for Bids 5,262,066.00 0.00 Canceled 2018-07-16 2018-07-21 2018-09-01 2018-09-16 2018-09-30 y l nvelope 9 d - Rehabilitation of road PK-PTEG-40081-CW-RFB / E 3. Public Investment Facilit Single Stage - One E 2018-12-1 minabad - Rori roads - Rehab IDA / 59820 Post Request for Bids Open - National 399,228.00 0.00 Canceled 2018-04-04 2018-04-09 2018-05-21 2018-06-05 2018-06-19 y nvelope 6 ilitation of roads PK-PTEG-40084-CW-RFB / Uc 3. Public Investment Facilit Single Stage - One E 2019-04-1 IDA / 59820 Post Request for Bids Open - National 1,199,457.00 0.00 Canceled 2018-08-06 2018-08-11 2018-09-20 2018-10-04 2018-10-18 h Sharif road - Rehabilitation y nvelope 6 of roads PK-PTEG-40085-CW-RFB / Gh 3. Public Investment Facilit Single Stage - One E 2019-03-2 ulam Farid Mithan Kot Rajanp IDA / 59820 Post Request for Bids Open - National 1,024,428.00 0.00 Canceled 2018-07-09 2018-07-14 2018-08-25 2018-09-09 2018-09-23 y nvelope 2 ur - Rehabilitation of roads PK-PTEG-194132-CW-RFB / R 3. Public Investment Facilit Single Stage - One E 4,346,514.4 2021-11-2 oads Rehabilitation in Punjab IDA / 59820 Post Request for Bids Open - National 6,000,000.00 Signed 2020-09-16 2020-09-17 2020-09-18 2020-09-17 2020-10-20 2020-10-20 2020-10-30 2020-11-10 2020-11-20 2020-12-10 y nvelope 3 0 (4 Packages, 6 Roads) PK-PTEG-238517-CW-RFB / R 3. Public Investment Facilit Single Stage - One E Other (with field f Under Imple 2022-08-1 ehabilitation of Roads - Uch S IDA / 59820 Post Request for Bids Open - National 3,300,000.00 0.00 2021-06-08 2021-06-30 2021-06-10 2021-07-14 2021-07-10 2021-08-03 2021-07-25 2021-08-22 y nvelope or explanation) mentation 7 harif & Channan Pir PK-PTEG-269512-CW-RFQ / T Request for Quota 3. Public Investment Facilit Request for Quota Single Stage - One E 2022-08-0 axila Museum - Design & Con IDA / 59820 Post Open - National tions (Non Bank-S 95,000.00 20,833.57 Signed 2021-12-31 2022-03-25 2022-02-04 2022-04-27 y tions nvelope 3 struction of Entrance Gate PD) Request for Bids - PK-PTEG-279723-CW-RFB / C 3. Public Investment Facilit Single Stage - One E Small Works SPD 2023-04-2 onstruction/Rehabilitation of IDA / 59820 Post Request for Bids Open - National 1,950,000.00 0.00 Canceled 2022-02-22 2022-03-25 2022-02-27 2022-03-29 2022-03-29 2022-04-13 2022-04-27 y nvelope (2 envelope proce 2 Toilet facilities at Heritage & ss) Tourist Sites Request for Bids - PK-PTEG-314721-CW-RFB / C 3. Public Investment Facilit Single Stage - One E Small Works SPD 2023-11-1 onstruction/Rehabilitation of IDA / 59820 Post Request for Bids Open - National 1,950,000.00 0.00 Canceled 2022-09-19 2022-09-24 2022-10-24 2022-11-08 2022-11-22 y nvelope (1 envelope proce 7 Toilet Blocks at Tourist sites - ss) Punjab PK-PTEG-330987-CW-RFB / R ehabilitation / Improvement 3. Public Investment Facilit Single Stage - One E Other (with field f Under Imple 2024-02-1 of Metaled Road from Lahore IDA / 59820 Post Request for Bids Open - National 1,000,000.00 0.00 2022-12-12 2023-02-20 2022-12-12 2023-02-24 2023-01-16 2023-03-27 2023-01-26 2023-04-12 2023-02-19 y nvelope or explanation) mentation 9 -Sheikhupura-Sargodha Road to Gurdwara Sucha Soda Dist rict Sheikhupura. PK-PTEG-331277-CW-RFB / R ehabilitation / Improvement 3. Public Investment Facilit Single Stage - One E Other (with field f 2024-02-1 of Metalled Road from Lahore IDA / 59820 Post Request for Bids Open - National 950,000.00 0.00 Canceled 2022-12-12 2023-02-20 2022-12-12 2023-02-24 2023-01-16 2023-01-26 2023-02-19 y nvelope or explanation) 9 -Sheikhupura-Sargodha Road to Mariumabad (Right Side of canal) District Sheikhupura PK-PTEG-331281-CW-RFB / R ehabilitation / Improvement 3. Public Investment Facilit Single Stage - One E Other (with field f 2024-08-1 IDA / 59820 Post Request for Bids Open - National 8,250,000.00 0.00 Signed 2022-12-12 2023-02-20 2022-12-12 2023-02-24 2023-01-16 2023-03-27 2023-01-26 2023-04-10 2023-02-19 of Road from Kallar Kahar to y nvelope or explanation) 7 Manara District Boundary Ch akwal District Chakwal PK-PTEG-331284-CW-RFB / C 3. Public Investment Facilit Single Stage - One E Other (with field f Pending Imp 2024-08-1 onstruction of Rohtas Fort By IDA / 59820 Post Request for Bids Open - National 8,700,000.00 0.00 2022-12-12 2022-12-12 2023-01-16 2023-01-26 2023-02-19 y nvelope or explanation) lementation 7 pass Road District Jhelum. Request for Bids - PK-PTEG-333401-CW-RFB / C 3. Public Investment Facilit Single Stage - One E Small Works SPD Under Imple 2024-03-1 onstruction/Rehabilitation of IDA / 59820 Post Request for Bids Open - National 1,950,000.00 0.00 2022-12-23 2023-03-20 2022-12-28 2023-04-02 2023-02-01 2023-02-11 2023-03-19 y nvelope (1 envelope proce mentation 8 Toilet Blocks at Tourist sites - ss) Punjab Request for Bids - PK-PTEG-360704-CW-RFB / C 2. Private Investment and Single Stage - One E Small Works SPD Under Imple 2024-07-1 onservation & Rehabilitation IDA / 59820 Post Request for Bids Open - National 610,000.00 0.00 2023-05-09 2023-05-17 2023-05-09 2023-05-17 2023-06-03 2023-06-10 2023-06-22 Entrepreneurship Promotion nvelope (1 envelope proce mentation 5 of Buildings/Façade Work on ss) West Side Request for Bids - PK-PTEG-360710-CW-RFB / C 2. Private Investment and Single Stage - One E Small Works SPD Under Imple 2024-07-1 onservation & Rehabilitation IDA / 59820 Post Request for Bids Open - National 780,000.00 0.00 2023-05-09 2023-05-17 2023-05-09 2023-05-17 2023-06-03 2023-06-10 2023-06-22 Entrepreneurship Promotion nvelope (1 envelope proce mentation 5 of Buildings/Façade Work on ss) East Side-1 Request for Bids - PK-PTEG-360711-CW-RFB / C 2. Private Investment and Single Stage - One E Small Works SPD Under Imple 2024-07-1 onservation & Rehabilitation IDA / 59820 Post Request for Bids Open - National 780,000.00 0.00 2023-05-09 2023-05-17 2023-05-09 2023-05-17 2023-06-03 2023-06-10 2023-06-22 Entrepreneurship Promotion nvelope (1 envelope proce mentation 5 of Buildings/Façade Work On ss) East Side-2 PK-PTEG-360715-CW-RFB / C Request for Bids - onservation of Bhatti Gate: 2. Private Investment and Single Stage - One E Small Works SPD Under Imple 2024-07-1 Façade Rehabilitation of Main IDA / 59820 Post Request for Bids Open - National 545,000.00 0.00 2023-05-09 2023-05-17 2023-05-09 2023-05-17 2023-06-03 2023-06-10 2023-06-22 Entrepreneurship Promotion nvelope (1 envelope proce mentation 5 Trail, Relocation of Water Filt ss) ration Plant and Establishme nt of Parking Area Page 1 PK-PTEG-363215-CW-RFB / R ehabilitation / Improvement of Metaled Road from Lahore 2. Private Investment and Single Stage - One E Other (with field f Pending Imp 2024-07-1 IDA / 59820 Post Request for Bids Open - National 950,000.00 0.00 2023-05-23 2023-05-25 2023-06-15 2023-06-25 2023-07-15 -Sheikhupura-Sargodha Road Entrepreneurship Promotion nvelope or explanation) lementation 4 to Mariumabad Length 4.10K M (Right Side of canal) Distri ct Sheikhupura GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PTEG-32430-GO-RFQ / Ve 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 40,000.00 0.00 Canceled 2018-02-05 2018-04-02 2018-09-29 hicles Procurement onitoring and Evaluation tions nvelope PK-PTEG-32431-GO-RFQ / Of 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 58,650.00 23,294.21 Signed 2018-02-04 2018-04-01 2018-05-18 2018-09-28 fice Furniture onitoring and Evaluation tions nvelope PK-PTEG-40059-GO-RFQ / Po 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 9,600.00 6,930.48 Signed 2018-03-03 2018-04-28 2018-06-01 2018-10-25 wer Generator onitoring and Evaluation tions nvelope PK-PTEG-40060-GO-RFQ / Of fice Equipment 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 17,000.00 5,280.80 Signed 2018-01-13 2018-06-30 2018-03-10 2018-06-01 2018-09-06 (Telephone Exchange, CCTV, onitoring and Evaluation tions nvelope Air conditioners, refrigerators etc.) PK-PTEG-40065-GO-RFQ / M 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 600.00 0.00 Canceled 2018-01-24 2018-03-21 2018-09-17 otor Bike onitoring and Evaluation tions nvelope PK-PTEG-40054-GO-RFQ / IT Equipment 4. Project Management, M Request for Quota Single Stage - One E (Laptops, Desktops, Server, P IDA / 59820 Post Open - National 39,000.00 22,115.80 Signed 2017-12-30 2018-02-14 2018-02-24 2018-06-01 2018-08-23 onitoring and Evaluation tions nvelope rinters, Scanner, Multimedia Projector etc.) PK-PTEG-40058-GO-RFQ / Ne 4. Project Management, M Request for Quota Single Stage - One E tworking for IT connectivity & IDA / 59820 Post Open - National 7,000.00 2,693.07 Signed 2018-02-25 2018-04-22 2018-06-01 2018-10-19 onitoring and Evaluation tions nvelope Telephone Exchange PK-PTEG-40067-GO-RFB / Hu 1. Policy, Institutions and Open - Internationa Single Stage - One E IDA / 59820 Post Request for Bids 200,000.00 0.00 Canceled 2018-04-16 2018-04-21 2018-06-02 2018-06-18 2018-07-02 2018-12-29 man Resource Information Sy Governance for Tourism Dev l nvelope stem elopment PK-PTEG-93484-GO-RFB / To 1. Policy, Institutions and Open - Internationa Single Stage - One E IDA / 59820 Prior Request for Bids 3,500,000.00 0.00 Canceled 2019-02-04 2019-02-09 2019-03-23 2019-04-22 2019-05-27 2019-11-23 urism Mobile Application Governance for Tourism Dev l nvelope elopment PK-PTEG-151606-GO-RFQ / P urchase of new IT Equipment and software for project staf 4. Project Management, M Request for Quota Single Stage - One E Pending Impl f. IDA / 59820 Post Open - National 15,000.00 0.00 2019-12-24 2019-12-28 2020-01-31 onitoring and Evaluation tions nvelope ementation 7 Laptops Core i-5 8GB ram 1 3.3" Screen size 256/512 GB HDD Windows 10 + MS Office 1 Tablet PK-PTEG-161181-GO-RFQ / I 4. Project Management, M Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 17,300.00 0.00 2020-03-14 2020-05-09 2020-11-05 T Equipment onitoring and Evaluation tions nvelope ementation PK-PTEG-161189-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 11,800.00 0.00 2020-03-14 2020-05-09 2020-11-05 ffice Equipment onitoring and Evaluation tions nvelope ementation PK-PTEG-161192-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 16,000.00 10,960.00 Signed 2020-03-14 2020-03-17 2020-05-09 2020-03-21 2020-11-05 ffice Furniture onitoring and Evaluation tions nvelope PK-PTEG-186934-GO-RFB / Si 3. Public Investment Facilit Single Stage - One E Under Imple IDA / 59820 Post Request for Bids Open - National 1,000,000.00 0.00 2020-08-13 2020-08-31 2020-08-18 2020-09-03 2020-09-29 2020-10-05 2020-10-14 2020-11-04 2023-10-20 gnboards - Supply and Install y nvelope mentation ation (FA) PK-PTEG-200114-GO-RFQ / P 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Limited 2,500.00 2,580.69 Signed 2020-10-20 2020-10-26 2020-11-05 2020-10-31 2020-11-12 rofessional Camera y tions nvelope PK-PTEG-200602-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 36,000.00 19,551.99 Signed 2020-10-27 2020-10-28 2020-11-26 2020-11-12 2021-02-24 ffice Furniture - Tourism Dep onitoring and Evaluation tions nvelope artment PK-PTEG-200605-GO-RFQ / I 4. Project Management, M Request for Quota Single Stage - One E Under Imple IDA / 59820 Post Open - National 25,200.00 0.00 2020-10-30 2020-10-28 2020-12-11 2021-02-09 T Equipment - Tourism Depar onitoring and Evaluation tions nvelope mentation tment PK-PTEG-200606-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 15,000.00 12,992.20 Signed 2020-10-31 2020-11-19 2020-12-15 2020-12-11 2021-02-13 ffice Equipment - Tourism De onitoring and Evaluation tions nvelope partment PK-PTEG-230268-GO-RFQ / G 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 150,000.00 163,734.37 Signed 2021-04-30 2021-05-07 2021-06-04 2021-06-10 2021-12-01 olf Carts for Heritage Sites y tions nvelope PK-PTEG-230269-GO-RFQ / H 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 70,000.00 34,537.37 Signed 2021-05-01 2021-05-07 2021-06-05 2021-06-23 2021-12-02 eritage Rikshaws y tions nvelope PK-PTEG-230271-GO-RFQ / C 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 100,000.00 80,079.55 Signed 2021-05-01 2021-05-07 2021-06-05 2021-06-08 2021-12-02 oaster - Shuttle Bus y tions nvelope PK-PTEG-228308-GO-RFQ / S 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 95,000.00 38,012.80 Signed 2021-05-01 2021-09-03 2021-06-05 2021-10-29 2021-12-02 MD for Taxila Museum y tions nvelope PK-PTEG-231715-GO-RFB / S 3. Public Investment Facilit Single Stage - One E IDA / 59820 Post Request for Bids Open - National 700,000.00 207,024.82 Terminated 2021-05-05 2021-08-04 2021-05-10 2021-08-05 2021-06-09 2021-09-02 2021-06-23 2021-09-23 2021-07-14 2022-01-02 2022-01-10 olid Waste Management Equi y nvelope pment PK-PTEG-256404-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 35,000.00 34,327.89 Signed 2021-10-15 2021-10-07 2021-11-16 2021-10-27 2022-05-15 ffice Furniture - Tourism Dep onitoring and Evaluation tions nvelope artment PK-PTEG-256408-GO-RFQ / O ffice Equipment - Tourism De 4. Project Management, M Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 24,000.00 0.00 2021-10-15 2021-11-19 2022-05-18 partment onitoring and Evaluation tions nvelope ementation DSLR, AC, Generator 15 KV, Refrigirator, Fax Machine PK-PTEG-256411-GO-RFQ / I T Equipment - Tourism Depar 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 25,000.00 8,175.37 Signed 2021-10-15 2021-10-11 2021-11-19 2021-10-29 2022-05-18 tment onitoring and Evaluation tions nvelope LEDs, Printers, Smart Phones , Video Conferencing System Page 2 PK-PTEG-271627-GO-RFB / S olid Waste Management Equi 3. Public Investment Facilit Single Stage - One E pment IDA / 59820 Post Request for Bids Open - National 200,000.00 148,710.58 Signed 2022-01-05 2022-01-10 2022-01-07 2022-01-13 2022-02-06 2022-02-11 2022-02-13 2022-02-22 2022-02-27 2022-03-25 2022-08-26 y nvelope 10 Mini Tippers 05 Mechanical Sweepers (Tra ctor driven) PK-PTEG-222318-GO-RFB / G 3. Public Investment Facilit Single Stage - One E IDA / 59820 Post Request for Bids Open - National 165,000.00 0.00 Canceled 2021-03-10 2021-03-15 2021-04-14 2021-04-24 2021-05-15 2021-11-11 olf Carts & Heritage Rikshaw y nvelope s PK-PTEG-227444-GO-RFB / S 3. Public Investment Facilit Single Stage - One E olar Power Energy System for IDA / 59820 Post Request for Bids Open - National 410,000.00 0.00 Canceled 2021-04-02 2021-04-06 2021-04-04 2021-04-08 2021-05-06 2021-05-21 2021-06-16 2022-06-11 y nvelope Heritage Sites PK-PTEG-275532-GO-RFB / D 3. Public Investment Facilit Open - Internationa Single Stage - One E IDA / 59820 Prior Request for Bids 3,000,000.00 0.00 Canceled 2022-02-11 2022-05-06 2022-02-16 2022-05-07 2022-04-02 2022-06-20 2022-04-16 2022-08-25 2022-05-21 2022-11-17 ouble Decker Buses - 9 buses y l nvelope PK-PTEG-283628-GO-RFB / P 3. Public Investment Facilit Single Stage - One E re-fabricated Containers for IDA / 59820 Post Request for Bids Open - National 240,000.00 0.00 Canceled 2022-03-18 2022-03-23 2022-04-22 2022-04-29 2022-05-20 2022-11-16 y nvelope Rescue Services - Murree Im plementation Plan PK-PTEG-283630-GO-RFB / R 3. Public Investment Facilit Single Stage - One E ecovery Vehicles for Rescue IDA / 59820 Post Request for Bids Open - National 400,000.00 0.00 Canceled 2022-03-18 2022-03-23 2022-04-22 2022-04-29 2022-05-20 2022-11-16 y nvelope Services - Murree Implement ation Plan PK-PTEG-283631-GO-RFB / A 3. Public Investment Facilit Single Stage - One E mbulances with fabrication R IDA / 59820 Post Request for Bids Open - National 600,000.00 0.00 Canceled 2022-03-18 2022-03-23 2022-04-22 2022-05-06 2022-05-27 2022-11-23 y nvelope escue Services - Murree Impl ementation Plan PK-PTEG-283632-GO-RFB / R 3. Public Investment Facilit Single Stage - One E escue Equipment for Rescue IDA / 59820 Post Request for Bids Open - National 300,000.00 0.00 Canceled 2022-03-18 2022-03-23 2022-04-22 2022-05-06 2022-05-27 2022-11-23 y nvelope Services - Murree Implement ation Plan PK-PTEG-283634-GO-RFQ / R 3. Public Investment Facilit Request for Quota Single Stage - One E ehabilitation of Takht-e-Babri IDA / 59820 Post Open - National 100,000.00 32,388.30 Signed 2022-03-16 2022-03-16 2022-04-16 2022-03-30 2022-06-15 y tions nvelope , Kalar Kahar PK-PTEG-286749-GO-RFQ / A 3. Public Investment Facilit Request for Quota Single Stage - One E rcheological Laboratory Equi IDA / 59820 Post Open - National 68,000.00 47,017.08 Signed 2022-03-30 2022-05-16 2022-05-05 2022-06-21 2022-11-01 y tions nvelope pment - Directorate of Arche ology PK-PTEG-293035-GO-RFB / V 4. Project Management, M Single Stage - One E Pending Impl ehicles for PTEGP (PMU-Touri IDA / 59820 Post Request for Bids Open - National 750,000.00 0.00 2022-05-09 2022-05-14 2022-06-11 2022-06-18 2022-07-02 2023-06-27 onitoring and Evaluation nvelope ementation sm Department and C&W) & IDAP PK-PTEG-295160-GO-RFB / P 3. Public Investment Facilit Single Stage - One E rocurement of Architectural a IDA / 59820 Post Request for Bids Open - National 725,000.00 0.00 Canceled 2022-06-26 2022-07-01 2022-07-31 2022-08-14 2022-09-11 2023-03-10 y nvelope nd Civil Engineering related S oftware PK-PTEG-295161-GO-RFB / P rocurement of Computer Equ 3. Public Investment Facilit Single Stage - One E Pending Impl IDA / 59820 Post Request for Bids Open - National 795,000.00 0.00 2022-06-27 2022-07-02 2022-08-01 2022-08-15 2022-09-19 2023-03-18 ip. Drones, Terrestrial Laser y nvelope ementation Scanner & Total Station for I DAP PK-PTEG-302801-GO-RFQ / S upply of Uniforms and relate 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 70,000.00 0.00 Signed 2022-07-18 2022-07-18 2022-08-20 2023-02-16 d accessories for Tourism Sq y tions nvelope uad - Tourism Department PK-PTEG-302808-GO-RFB / S upply & Installation of Revers 3. Public Investment Facilit Single Stage - One E IDA / 59820 Post Request for Bids Open - National 500,000.00 0.00 Canceled 2022-07-25 2022-08-31 2022-07-30 2022-09-02 2022-08-29 2022-09-12 2022-10-10 2023-04-08 ible Tuck shops & Washroom y nvelope s - Tourist sites Punjab PK-PTEG-302810-GO-RFQ / S 3. Public Investment Facilit Request for Quota Single Stage - One E Pending Impl upply of Garbage Collection IDA / 59820 Post Open - National 72,000.00 0.00 2022-07-23 2022-09-17 2023-03-16 y tions nvelope ementation Carts - Tourist Sites Punjab PK-PTEG-303027-GO-RFQ / S 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple upply & Installation of SMD S IDA / 59820 Post Open - National 50,000.00 0.00 2022-07-20 2022-07-15 2022-08-17 2022-10-16 y tions nvelope mentation creens - Murree District PK-PTEG-317860-GO-RFQ / P unjab Tourism Squad - Procur 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 96,000.00 0.00 Signed 2022-10-05 2022-11-01 2023-01-30 ement of equipment for cap y tions nvelope acity building of PTS PK-PTEG-319157-GO-RFB / S upply & Installation of Solar P ower System (Jahangir Tomb, Lahore, Shal 3. Public Investment Facilit Single Stage - One E amar Gardens, Lahore, Hiran IDA / 59820 Post Request for Bids Open - National 430,000.00 0.00 Canceled 2022-10-03 2022-11-10 2022-10-08 2022-11-11 2022-11-19 2022-12-19 2023-01-23 2023-07-22 y nvelope Minar, Sheikhupura, Rohtas F ort, Jhelum, Taxila Museum, Taxila Rawalpindi, Wah Gard ens Wah Rawalpindi & Harap pa Museum & Site, Sahiwal ) PK-PTEG-324234-GO-RFB / S upply & Installation of Revers 3. Public Investment Facilit Single Stage - One E IDA / 59820 Post Request for Bids Open - National 550,000.00 0.00 Signed 2022-11-01 2022-11-10 2022-11-02 2022-11-11 2022-12-02 2022-12-13 2022-12-05 2022-12-20 2022-12-11 2023-03-11 ible Tuck shops & Washroom y nvelope s - Tourist sites Punjab PK-PTEG-335666-GO-RFB / S 3. Public Investment Facilit Single Stage - One E Under Imple upply & Installation of Solar P IDA / 59820 Post Request for Bids Open - National 500,000.00 0.00 2023-01-16 2023-01-17 2023-01-21 2023-03-04 2023-02-27 2023-04-03 2023-05-08 2023-08-06 y nvelope mentation ower System PK-PTEG-351380-GO-RFB / P 3. Public Investment Facilit Open - Internationa Single Stage - One E Under Imple rocurement of 06-Double De IDA / 59820 Post Request for Bids 2,000,000.00 0.00 2023-03-27 2023-05-01 2023-04-01 2023-05-20 2023-05-13 2023-05-28 2023-06-03 2023-11-30 y l nvelope mentation cker Bus (Diesel Hybrid) PK-PTEG-351387-GO-RFQ / P 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple IDA / 59820 Post Open - National 575,000.00 0.00 2023-03-31 2023-04-28 2023-07-27 rocurement of 05-Coasters ( y tions nvelope mentation Diesel) PK-PTEG-351403-GO-RFQ / P 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple IDA / 59820 Post Open - National 400,000.00 0.00 2023-03-31 2023-04-30 2023-07-29 rocurement of 07-VANS y tions nvelope mentation PK-PTEG-351418-GO-RFQ / F 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple urniture and Inverter Floor St IDA / 59820 Post Open - National 53,000.00 0.00 2023-03-31 2023-04-16 2023-06-15 y tions nvelope mentation anding Cabinet A.C for Lahor e Museum Page 3 PK-PTEG-351405-GO-RFQ / P rocurement of I.T. Equipment for Lahore Museum Lot-1: Desktop Computer, est 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple imated budget=USD$=15,00 IDA / 59820 Post Open - National 50,000.00 0.00 2023-03-31 2023-04-27 2023-07-26 y tions nvelope mentation 0/- Lot-2: Laptop, estimated bud get=USD$=12,00/- Lot-3: Server 96TB storage, e stimated budget=USD$=33, 800/- PK-PTEG-353673-GO-RFQ / P 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple rocurement of Office Equipm IDA / 59820 Post Open - National 15,000.00 0.00 2023-03-29 2023-05-02 2023-07-31 y tions nvelope mentation ent for Lahore Museum PK-PTEG-355575-GO-RFQ / P ROCUREMENT OF EQUIPMEN T FOR AUDIO-VIDEOGRAPHY 3. Public Investment Facilit Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 90,000.00 0.00 2023-04-15 2023-05-10 2023-08-08 STUDIO, PORTABLE PUBLIC A y tions nvelope ementation DDRESS SYSTEM AND WEBIN AR ROOM FOR LAHORE MUSE UM PK-PTEG-363800-GO-RFQ / E QUIPMENT (LED) LIGHTS FOR 2. Private Investment and Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 16,000.00 0.00 2023-05-29 2023-06-29 2023-09-27 ILLUMINATION OF FRONT ELE Entrepreneurship Promotion tions nvelope ementation VATION FOR LAHORE MUSEU M BUILDING PK-PTEG-363804-GO-RFQ / P ROCUREMENT OF GOLF CART 2. Private Investment and Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 95,000.00 0.00 2023-05-29 2023-06-21 2023-09-19 FOR TDCP AT CHANGA MANG Entrepreneurship Promotion tions nvelope ementation A RESORT, LAHORE PK-PTEG-365225-GO-RFB / P 1. Policy, Institutions and rocurement of 11-Seater Golf Single Stage - One E Pending Impl IDA / 59820 Governance for Tourism Dev Post Request for Bids Open - National 300,000.00 0.00 2023-06-05 2023-06-07 2023-07-03 2023-07-08 2023-07-19 2024-01-15 Carts for Walled City Lahore nvelope ementation elopment Authority (WCLA) PK-PTEG-365229-GO-RFQ / P 1. Policy, Institutions and Request for Quota Single Stage - One E Pending Impl rocurement of Coaster for W IDA / 59820 Governance for Tourism Dev Post Open - National 120,000.00 0.00 2023-06-10 2023-07-03 2023-12-30 tions nvelope ementation alled City Lahore Authority ( elopment WCLA) PK-PTEG-365231-GO-RFQ / P 1. Policy, Institutions and Request for Quota Single Stage - One E Pending Impl rocurement of High Roof-VAN IDA / 59820 Governance for Tourism Dev Post Open - National 120,000.00 0.00 2023-06-07 2023-07-01 2023-12-28 tions nvelope ementation S for Walled City Lahore Auth elopment ority (WCLA) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PTEG-48673-NC-RFQ / Ev 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 30,000.00 27,702.75 Signed 2018-02-14 2018-02-15 2018-02-26 2018-02-13 2018-03-08 ent Management Firm - Proje onitoring and Evaluation tions nvelope ct Launch PK-PTEG-91147-NC-RFQ / Su 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 35,000.00 10,591.35 Signed 2019-01-12 2019-02-13 2019-03-09 2019-04-22 2019-09-05 rvey Firm for Data collection onitoring and Evaluation tions nvelope PK-PTEG-103229-NC-RFQ / T 4. Project Management, M Request for Quota Single Stage - One E ourism Sector regulation and IDA / 59820 Post Open - National 20,000.00 0.00 Canceled 2019-03-04 2019-04-29 2019-06-30 onitoring and Evaluation tions nvelope Inspection Mapping Exercise -4 Months PK-PTEG-103234-NC-RFQ / D ocumentary Preparation of K 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 100,000.00 0.00 Canceled 2019-03-10 2019-05-05 2019-06-30 artarpur site (Non Consultanc onitoring and Evaluation tions nvelope y Services) 2-Months PK-PTEG-103260-NC-RFQ / T 4. Project Management, M Request for Quota Single Stage - One E raining need assessment of S IDA / 59820 Post Open - National 100,000.00 0.00 Canceled 2019-03-04 2019-04-29 2019-06-30 onitoring and Evaluation tions nvelope kill training 4-Months PK-PTEG-141301-NC-DIR / Pr 4. Project Management, M Pending Impl ocurement of Planning & Mon IDA / 59820 Post Direct Selection Direct 1,260.00 0.00 2019-10-21 2019-10-26 2019-11-08 2019-11-18 onitoring and Evaluation ementation itoring Software (SMARTSHEE T) PK-PTEG-140344-NC-DIR / H all and Auditorium facility ch 1. Policy, Institutions and arges for conduct of Lahore I IDA / 59820 Governance for Tourism Dev Post Direct Selection Direct 50,000.00 0.00 Canceled 2019-10-23 2019-10-28 2019-12-07 2019-12-28 nternational Tourism Expo (LI elopment TE) at Expo center Lahore PK-PTEG-134818-NC-RFQ / H 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 20,000.00 0.00 Canceled 2019-09-19 2019-09-24 2019-09-27 iring of Firm for Event Manag onitoring and Evaluation tions nvelope ement PK-PTEG-159994-NC-RFQ / E 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 12,000.00 4,442.20 Signed 2020-02-24 2020-02-25 2020-03-18 2020-03-18 2022-03-08 nvironment Laboratory y tions nvelope PK-PTEG-300757-NC-RFQ / T 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple opographic Survey of Archeol IDA / 59820 Post Open - National 100,000.00 0.00 2022-07-01 2022-07-18 2022-08-05 2023-02-01 y tions nvelope mentation ogical Sites PK-PTEG-306845-NC-RFB / Hi 1. Policy, Institutions and ring of Training Service Provi Single Stage - One E IDA / 59820 Governance for Tourism Dev Post Request for Bids Open - National 2,000,000.00 0.00 Canceled 2022-08-04 2022-10-03 2022-08-09 2022-09-08 2022-09-28 2022-10-26 2023-04-24 ders (TSPs) for Skills Develop nvelope elopment ment - Tourism Sector Punja b CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PTEG-32421-CS-QCBS / H 3. Public Investment Facilit UN Agencies (Dire iring of Heritage Firm IDA / 59820 Prior Direct 500,000.00 2,834,843.00 Signed 2018-01-27 2018-02-19 2021-01-29 y ct) UNESCO PK-PTEG-32423-CS-QCBS / H 1. Policy, Institutions and Quality And Cost- Open - Internationa Under Implement iring of firm for Legal & Regul IDA / 59820 Governance for Tourism Dev Prior 750,000.00 0.00 2017-12-25 2018-07-24 2018-01-15 2018-02-28 2018-03-28 2018-04-27 2018-06-01 2018-07-06 2019-07-06 Based Selection l ation atory Review elopment Page 4 PK-PTEG-32425-CS-CQS / Int 4. Project Management, M Least Cost Selecti ernal Audit Firm IDA / 59820 Post Open - National 150,000.00 0.00 Canceled 2017-12-18 2018-01-08 2018-02-21 2018-03-21 2018-04-20 2018-05-25 2018-06-29 2022-12-30 onitoring and Evaluation on Estimated cost for 5 years PK-PTEG-32422-CS-QCBS / Fi 2. Private Investment and Quality And Cost- Open - Internationa IDA / 59820 Post 1,500,000.00 0.00 Canceled 2018-01-31 2018-12-28 2018-02-16 2018-03-09 2018-04-23 2018-05-08 2018-05-22 2018-06-05 2020-10-13 rm Hiring for Skills Developm Entrepreneurship Promotion Based Selection l ent PK-PTEG-32418-CS-QCBS / S 3. Public Investment Facilit Quality And Cost- Open - Internationa upervision & Quality Assuran IDA / 59820 Prior 952,380.00 94,799.46 Signed 2018-01-15 2019-02-11 2018-01-30 2019-02-11 2018-02-27 2020-05-08 2018-04-01 2020-04-15 2018-04-17 2020-05-09 2018-05-08 2020-07-17 2018-05-22 2020-07-09 2020-09-29 y Based Selection l ce Firm Civil Works consultant firm - PISC PK-PTEG-32427-CS-CQS / Up 1. Policy, Institutions and Quality And Cost- Open - Internationa gradation of Existing Institute IDA / 59820 Governance for Tourism Dev Prior 750,000.00 0.00 Canceled 2018-02-01 2018-02-16 2018-03-12 2018-04-24 2018-05-09 2018-05-23 2018-06-06 2019-06-06 Based Selection l s - Hiring of firm elopment PK-PTEG-51948-CS-CQS / Int 4. Project Management, M Consultant Qualifi IDA / 59820 Post Open - National 150,000.00 0.00 Canceled 2018-03-06 2018-05-01 2018-03-26 2018-05-10 2018-05-17 2018-06-14 2023-04-30 ernal Audit Firm - 5 Years Co onitoring and Evaluation cation Selection ntract PK-PTEG-64589-CS-CQS / Up 1. Policy, Institutions and Consultant Qualifi gradation of Existing Institute IDA / 59820 Governance for Tourism Dev Post Open - National 400,000.00 0.00 Canceled 2018-06-11 2018-06-19 2018-07-02 2018-08-15 2018-09-14 2018-10-19 2019-06-28 cation Selection s - Restructuring of TDCP elopment PK-PTEG-93553-CS-QCBS / R 1. Policy, Institutions and Quality And Cost- IDA / 59820 Post Open - National 500,000.00 0.00 Canceled 2019-01-14 2019-01-08 2019-02-04 2019-02-13 2019-03-20 2019-04-17 2019-05-17 2019-06-21 2019-07-26 2020-07-25 e-structuring of TDCP Governance for Tourism Dev Based Selection elopment PK-PTEG-110939-CS-CQS / D 4. Project Management, M Consultant Qualifi Under Implement ocumentary Preparation of K IDA / 59820 Post Open - National 100,000.00 0.00 2019-04-22 2019-05-10 2019-05-13 2019-07-08 2019-06-26 2019-08-21 2019-07-26 2019-08-30 2020-04-30 onitoring and Evaluation cation Selection ation artarpur site PK-PTEG-110942-CS-CQS / T 4. Project Management, M Consultant Qualifi Under Implement IDA / 59820 Post Open - National 100,000.00 0.00 2019-04-22 2019-05-10 2019-05-13 2019-07-08 2019-06-26 2019-07-26 2019-08-30 2020-04-30 raining need assessment of S onitoring and Evaluation cation Selection ation kill training PK-PTEG-128723-CS-LCS / Hi 4. Project Management, M Least Cost Selecti IDA / 59820 Post Open - National 250,000.00 0.00 Canceled 2019-08-25 2020-03-09 2019-09-15 2019-10-29 2019-11-26 2019-12-26 2020-01-30 2020-03-05 2023-03-05 ring of Media Firm onitoring and Evaluation on PK-PTEG-103226-CS-LCS / Hi 4. Project Management, M Least Cost Selecti IDA / 59820 Post Open - National 150,000.00 0.00 Canceled 2019-02-27 2019-03-08 2019-03-20 2019-03-11 2019-05-03 2019-07-19 2019-05-31 2019-08-23 2019-06-30 2019-08-04 2019-09-08 2022-06-30 ring of Internal Audit Firm 5- onitoring and Evaluation on Years PK-PTEG-32414-CS-CQS / Me 2. Private Investment and Consultant Qualifi IDA / 59820 Prior Open - National 2,500,000.00 0.00 Canceled 2017-11-20 2018-09-20 2017-12-11 2018-01-24 2018-02-23 2018-03-30 2020-11-23 dia Firm hiring Entrepreneurship Promotion cation Selection PK-PTEG-163250-CS-QCBS / I 1. Policy, Institutions and Quality And Cost- IDA / 59820 Post Open - National 300,000.00 188,305.86 Signed 2020-03-13 2020-03-09 2020-04-02 2020-03-13 2020-04-19 2020-07-29 2020-05-19 2020-08-31 2020-05-29 2020-09-17 2020-06-15 2020-10-20 2020-07-06 2020-12-17 2021-07-01 SMP Qila Kohna Qasim Bagh Governance for Tourism Dev Based Selection elopment PK-PTEG-164014-CS-QCBS / 1. Policy, Institutions and Quality And Cost- IDA / 59820 Post Open - National 250,000.00 544,997.13 Signed 2020-03-12 2020-03-11 2020-04-02 2020-03-13 2020-05-16 2020-07-13 2020-06-13 2020-08-25 2020-07-13 2020-09-16 2020-08-17 2020-10-05 2020-09-21 2021-02-04 2023-09-06 Media Firm Hiring Governance for Tourism Dev Based Selection elopment PK-PTEG-183974-CS-QCBS / Destination Investment & Ma 1. Policy, Institutions and Quality And Cost- Open - Internationa nagement Plans (DIMPs) Con IDA / 59820 Governance for Tourism Dev Prior 3,000,000.00 614,175.00 Signed 2020-07-16 2020-07-24 2020-07-26 2020-08-28 2020-08-30 2020-11-26 2020-09-27 2021-01-11 2020-10-12 2021-03-03 2020-11-02 2021-03-16 2020-12-07 2021-05-15 2022-12-07 Based Selection l sultancy Services - elopment IDC (Framework contract) PK-PTEG-206682-CS-CQS / E 3. Public Investment Facilit Consultant Qualifi Under Implement nvironment Impact Assessme IDA / 59820 Post Open - National 100,000.00 0.00 2020-12-01 2020-12-15 2020-12-16 2020-12-30 2021-01-06 2021-02-11 2021-01-13 2021-01-25 2022-01-25 y cation Selection ation nt Services PK-PTEG-223666-CS-QCBS / 3. Public Investment Facilit Quality And Cost- Open - Internationa Pending Impleme Taxila Museum Upgradation - IDA / 59820 Post 450,000.00 0.00 2021-03-19 2021-04-03 2021-04-20 2021-05-18 2021-06-01 2021-06-22 2021-07-13 2022-07-13 y Based Selection l ntation Consulting Firm PK-PTEG-228305-CS-CQS / A 3. Public Investment Facilit Consultant Qualifi Pending Impleme rchitectural Firm for Design o IDA / 59820 Post Open - National 100,000.00 0.00 2021-04-11 2021-04-26 2021-05-17 2021-05-24 2021-06-07 2021-12-04 y cation Selection ntation f New Museum at Harappa PK-PTEG-246068-CS-QCBS / 3. Public Investment Facilit Quality And Cost- Under Implement Design Review and Supervisi IDA / 59820 Post Open - National 550,000.00 0.00 2021-08-02 2021-08-02 2021-08-17 2021-09-07 2021-10-05 2021-10-19 2021-11-02 2021-11-23 2022-11-23 y Based Selection ation on Firm (Roads & Buildings) PK-PTEG-267389-CS-CQS / S 3. Public Investment Facilit Consultant Qualifi Under Implement olar Energy - Design & Super IDA / 59820 Post Open - National 45,000.00 0.00 2021-12-13 2021-12-14 2021-12-28 2022-01-20 2022-01-26 2022-04-05 2022-02-09 2022-02-23 2023-02-18 y cation Selection ation vision Firm PK-PTEG-295159-CS-CQS / T 3. Public Investment Facilit Consultant Qualifi Under Implement opographic & Utilities Survey IDA / 59820 Post Open - National 100,000.00 0.00 2022-05-20 2022-05-30 2022-06-04 2022-07-03 2022-07-17 2022-08-14 2023-02-10 y cation Selection ation - IDAP Hiran Minar PK-PTEG-295158-CS-QCBS / Services for Preparation of As 3. Public Investment Facilit Consultant Qualifi Pending Impleme -Built Drawings & Scan-Base IDA / 59820 Post Open - National 175,000.00 0.00 2022-06-26 2022-07-17 2022-08-14 2022-08-28 2022-09-11 2023-03-10 y cation Selection ntation d 3D Models - IDAP Hiran Minar, Rohtas Fort & Ta xila PK-PTEG-320789-CS-CQS / D ESIGN AND RESIDENT SUPER 3. Public Investment Facilit Consultant Qualifi Under Implement VISION OF URBAN REHABILIT IDA / 59820 Post Open - National 150,000.00 0.00 2022-10-12 2022-11-10 2022-10-22 2022-12-28 2022-11-16 2022-12-01 2023-01-05 2024-10-31 y cation Selection ation ATION OF FAÇADE AND ESTA BLISHMENT OF PARKING ARE A - BHATTI GATE PK-PTEG-320794-CS-CQS / D ESIGN AND RESIDENT SUPER 3. Public Investment Facilit Consultant Qualifi Under Implement VISION OF URBAN REHABILIT IDA / 59820 Post Open - National 250,000.00 0.00 2022-10-12 2022-11-10 2022-10-27 2022-12-28 2022-11-20 2022-12-05 2023-01-09 2024-10-31 y cation Selection ation ATION OF INFRASTRUCTURE I MPROVEMENT - BHATTI GATE PK-PTEG-320797-CS-CQS / D ESIGN AND RESIDENT SUPER 3. Public Investment Facilit Consultant Qualifi IDA / 59820 Post Open - National 200,000.00 0.00 Under Review 2022-10-12 2022-11-10 2022-10-27 2022-11-20 2022-12-05 2022-12-25 2024-10-31 VISION FIRM FOR QILA KOHN y cation Selection A QASIM BAGH PROJECT PK-PTEG-330668-CS-QCBS / 3. Public Investment Facilit Quality And Cost- Under Implement Hiring of Firm for Digital Cura IDA / 59820 Post Open - National 600,000.00 0.00 2022-12-13 2022-12-06 2023-01-17 2023-01-02 2023-01-28 2023-03-04 2023-03-14 2023-03-27 2023-04-20 2024-04-19 y Based Selection ation tion of Lahore and Taxila Mus eum INDIVIDUAL CONSULTANTS Page 5 Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PTEG-32377-CS-INDV / So 4. Project Management, M Individual Consult cial Gender Specialist IDA / 59820 Post Open 189,450.00 26,773.76 Signed 2017-10-17 2017-08-01 2017-12-05 2018-01-02 2017-12-26 2018-01-01 2018-01-30 2018-02-01 2018-12-20 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32381-CS-INDV / E 4. Project Management, M Individual Consult nvironmental Specialist IDA / 59820 Post Open 189,450.00 24,361.53 Signed 2017-10-17 2017-07-17 2017-12-05 2017-12-26 2017-12-11 2018-01-30 2018-01-11 2019-01-10 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32410-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Bahawalpur IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-32411-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Rajanpur IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-40044-CS-INDV / R 4. Project Management, M Individual Consult IDA / 59820 Post Open 85,714.00 5,361.93 Signed 2017-12-18 2017-10-02 2018-02-05 2017-10-27 2018-02-26 2017-11-27 2018-04-02 2017-10-27 2018-09-28 esearch Associate onitoring and Evaluation ant Selection PK-PTEG-40046-CS-INDV / R 4. Project Management, M Individual Consult esearch Associate IDA / 59820 Post Open 85,714.00 5,361.93 Signed 2017-12-18 2017-12-04 2018-02-05 2018-01-03 2018-02-26 2018-01-02 2018-04-02 2018-01-08 2019-04-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-32376-CS-INDV / Fi 4. Project Management, M Individual Consult nancial Management Speciali IDA / 59820 Post Open 189,450.00 21,440.76 Signed 2017-10-17 2017-12-05 2017-09-11 2017-12-26 2017-09-13 2018-01-30 2017-09-26 2018-10-10 onitoring and Evaluation ant Selection st Estimated amount for 5 year s PK-PTEG-32398-CS-INDV / M 4. Project Management, M Individual Consult & E Specialist IDA / 59820 Post Open 225,000.00 29,233.84 Signed 2017-10-17 2017-07-01 2017-12-05 2017-09-11 2017-12-26 2017-09-25 2018-01-30 2017-09-26 2018-10-01 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-32389-CS-INDV / Pr 4. Project Management, M Individual Consult oject Director IDA / 59820 Prior Open 600,000.00 0.00 Canceled 2017-10-17 2018-08-16 2017-12-05 2017-12-26 2018-02-19 2019-02-19 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32391-CS-INDV / D 4. Project Management, M Individual Consult eputy Project Director IDA / 59820 Prior Open 370,000.00 0.00 Canceled 2017-10-17 2017-12-05 2017-12-26 2018-01-30 2018-10-25 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-40047-CS-INDV / R 4. Project Management, M Individual Consult esearch Associate - Account/ IDA / 59820 Post Open 85,714.00 14,616.92 Signed 2017-12-18 2017-09-11 2018-01-21 2017-12-08 2018-01-28 2017-12-11 2018-02-19 2017-12-12 2019-01-02 onitoring and Evaluation ant Selection Admin Estimated cost for 5 years PK-PTEG-68956-CS-INDV / Pu 4. Project Management, M Individual Consult IDA / 59820 Post Open 47,000.00 0.00 Canceled 2018-07-16 2018-09-03 2018-09-24 2018-10-29 2019-04-27 blic Sector Development Spe onitoring and Evaluation ant Selection cialist PK-PTEG-73991-CS-INDV / Pr 4. Project Management, M Individual Consult IDA / 59820 Post Open 47,000.00 17,457.63 Signed 2018-08-16 2019-01-14 2018-10-04 2019-09-20 2018-10-25 2019-09-24 2018-11-29 2019-09-24 2019-05-28 ivate Sector Development Sp onitoring and Evaluation ant Selection ecialist PK-PTEG-93482-CS-INDV / To 4. Project Management, M Individual Consult urism Expert IDA / 59820 Post Open 40,000.00 25,119.61 Signed 2019-01-11 2019-09-30 2019-03-01 2020-02-27 2019-03-22 2019-04-26 2020-04-09 2019-10-23 onitoring and Evaluation ant Selection (One year estimated cost) PK-PTEG-103221-CS-INDV / 4. Project Management, M Individual Consult Monitoring & Evaluation Spec IDA / 59820 Post Open 150,000.00 21,524.65 Signed 2019-02-27 2019-05-04 2019-04-17 2019-11-20 2019-05-08 2019-06-12 2019-11-26 2022-06-30 onitoring and Evaluation ant Selection ialist 3-Years and 4 Months PK-PTEG-103232-CS-INDV / P 4. Project Management, M Individual Consult rocurement & Contract Admi IDA / 59820 Post Open 16,000.00 0.00 Canceled 2019-02-27 2019-04-17 2019-05-08 2019-06-12 2020-04-30 onitoring and Evaluation ant Selection nistration Support 1-Year PK-PTEG-32401-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Rawalpindi IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32405-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Gujranwala IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32407-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Sheikhupura IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-136467-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 170,000.00 0.00 Canceled 2019-10-02 2019-10-03 2019-10-28 2019-11-04 2019-11-18 2022-11-16 Hiring of Sr. Procurement Sp onitoring and Evaluation ant Selection ecialist PK-PTEG-136466-CS-INDV / 4. Project Management, M Individual Consult Pending Impleme IDA / 59820 Post Open 4,260.00 0.00 2019-10-03 2019-10-12 2019-10-14 2019-10-19 2020-02-16 Hiring of Graphic Designer onitoring and Evaluation ant Selection ntation PK-PTEG-138460-CS-INDV / 4. Project Management, M Individual Consult Hiring of Monitoring & Evalua IDA / 59820 Post Open 76,600.00 0.00 Canceled 2019-10-03 2019-10-29 2019-11-05 2019-11-13 2022-10-31 onitoring and Evaluation ant Selection tion (M&E) Specialist PK-PTEG-139666-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 170,000.00 0.00 Canceled 2019-10-14 2019-11-16 2019-11-26 2019-12-10 2023-10-31 Hiring of Sr. Communication onitoring and Evaluation ant Selection Specialist PK-PTEG-139667-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 87,500.00 8,612.44 Signed 2019-10-14 2019-12-02 2019-11-09 2020-01-22 2019-11-16 2020-01-23 2019-11-30 2020-01-24 2023-10-30 Hiring of Research Associate onitoring and Evaluation ant Selection PK-PTEG-103217-CS-INDV / 4. Project Management, M Individual Consult Senior Communication Speci IDA / 59820 Prior Open 168,000.00 0.00 Canceled 2019-02-27 2019-03-07 2019-04-17 2019-05-08 2019-06-12 2022-06-30 onitoring and Evaluation ant Selection alist 3-Years and 4 Months PK-PTEG-145106-CS-INDV / P 4. Project Management, M Individual Consult IDA / 59820 Post Limited 150,000.00 26,016.25 Signed 2019-11-11 2019-11-08 2019-11-12 2019-11-08 2019-11-13 2019-11-19 2019-11-14 2019-11-20 2022-09-14 roject Manager onitoring and Evaluation ant Selection PK-PTEG-145603-CS-INDV / P 4. Project Management, M Individual Consult rocurement and Contract Ad IDA / 59820 Post Limited 12,000.00 8,863.64 Signed 2019-11-14 2019-10-15 2019-11-15 2021-02-24 2019-11-15 2021-03-22 2019-11-15 2021-03-23 2020-11-14 onitoring and Evaluation ant Selection ministration Support Assistan t PK-PTEG-145698-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Limited 12,000.00 0.00 Canceled 2019-11-14 2019-11-15 2019-11-15 2019-11-15 2020-02-16 Short Term Media Advisor for onitoring and Evaluation ant Selection YASAT Page 6 PK-PTEG-32372-CS-INDV / Se 4. Project Management, M Individual Consult nior Procurement Specialist IDA / 59820 Prior Open 255,000.00 0.00 Canceled 2017-10-17 2017-12-05 2017-12-26 2018-01-30 2018-10-08 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-103202-CS-INDV / 4. Project Management, M Individual Consult Senior Procurement Specialis IDA / 59820 Prior Open 170,000.00 0.00 Canceled 2019-02-27 2019-02-28 2019-04-17 2019-05-08 2019-06-12 2022-06-30 onitoring and Evaluation ant Selection t-3 Years & 4-Months PK-PTEG-145723-CS-INDV / 1. Policy, Institutions and Individual Consult Pending Impleme Short Term Media Consultant IDA / 59820 Governance for Tourism Dev Post Limited 12,000.00 0.00 2019-11-14 2019-11-15 2019-11-15 2019-11-15 2019-11-24 ant Selection ntation for YASA&T. Demand Driven elopment PK-PTEG-151717-CS-INDV / Estimated cost for Project Off icer -1 for 3 years 4. Project Management, M Individual Consult IDA / 59820 Post Limited 45,000.00 10,762.33 Signed 2019-12-24 2019-12-02 2019-12-29 2020-01-02 2019-12-30 2020-01-03 2020-01-07 2021-01-02 We will use limited competiti onitoring and Evaluation ant Selection on as we will select a candid ate from existing pool of can didates. PK-PTEG-151720-CS-INDV / P roject Officer -2 . Estimated cost for 3 years USD 45,000. 4. Project Management, M Individual Consult IDA / 59820 Post Limited 45,000.00 12,197.30 Signed 2019-12-24 2019-12-02 2019-12-29 2020-01-06 2020-01-03 2020-01-10 2020-01-07 2021-01-09 We will use limited competiti onitoring and Evaluation ant Selection on since we have existing po ol of consultants to select fro m. PK-PTEG-32404-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Chakwal IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-32385-CS-INDV / Se 4. Project Management, M Individual Consult nior Communication Specialis IDA / 59820 Prior Open 252,000.00 0.00 Canceled 2017-10-17 2018-08-31 2017-12-05 2017-12-26 2018-01-30 2019-01-30 onitoring and Evaluation ant Selection t Estimated amount for 5 year s PK-PTEG-153682-CS-INDV / 4. Project Management, M Individual Consult Hiring of Procurement Specia IDA / 59820 Post Limited 170,000.00 22,959.63 Signed 2020-01-14 2020-01-01 2020-01-17 2020-01-10 2020-01-18 2020-02-10 2020-01-20 2020-02-11 2023-01-19 onitoring and Evaluation ant Selection list PTEGP- cost for 3 years PK-PTEG-115815-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 168,000.00 0.00 Canceled 2019-05-21 2019-07-09 2019-07-30 2019-09-03 2022-06-30 Senior Communication Speci onitoring and Evaluation ant Selection alist PK-PTEG-32387-CS-INDV / In 4. Project Management, M Individual Consult frastructure Development Sp IDA / 59820 Post Open 189,450.00 0.00 Canceled 2017-10-17 2019-01-21 2017-12-05 2017-12-26 2018-01-30 2019-03-29 onitoring and Evaluation ant Selection ecialist Estimated amount for 5 year s PK-PTEG-162559-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Limited 100,000.00 18,126.90 Signed 2020-03-09 2020-03-09 2020-03-14 2020-03-06 2020-04-04 2020-03-16 2020-05-09 2020-03-21 2022-04-29 Civil Engineer onitoring and Evaluation ant Selection PK-PTEG-163247-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Limited 15,000.00 11,229.64 Signed 2020-03-10 2020-03-24 2020-03-15 2020-10-03 2020-04-05 2020-12-11 2020-05-10 2020-12-18 2021-05-10 Assistant Civil Engineer onitoring and Evaluation ant Selection PK-PTEG-190459-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 75,000.00 14,972.86 Signed 2020-09-02 2020-09-01 2020-10-21 2020-11-12 2020-11-11 2020-12-03 2020-12-16 2020-12-08 2021-06-14 Social Safeguard & Gender S onitoring and Evaluation ant Selection pecialist PK-PTEG-196847-CS-INDV / 3. Public Investment Facilit Individual Consult IDA / 59820 Post Limited 20,000.00 12,496.10 Signed 2020-10-05 2020-10-09 2020-10-10 2020-10-16 2020-10-24 2020-11-15 2020-11-17 2020-11-17 2022-11-17 Content Writer - Informative y ant Selection Signboards PK-PTEG-197173-CS-INDV / 3. Public Investment Facilit Individual Consult Under Implement IDA / 59820 Post Limited 20,000.00 0.00 2020-10-09 2022-07-19 2020-10-14 2020-11-04 2020-12-09 2021-12-04 Conservation Architect - PCR y ant Selection ation MP PK-PTEG-228307-CS-INDV / P 4. Project Management, M Individual Consult IDA / 59820 Post Open 20,000.00 12,954.55 Signed 2021-04-26 2021-04-26 2021-05-29 2021-06-04 2021-06-05 2021-06-04 2021-06-19 2021-07-08 2022-06-14 roject Officer - 1 onitoring and Evaluation ant Selection PK-PTEG-228310-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 30,000.00 0.00 2021-04-26 2021-09-23 2021-05-29 2021-06-12 2021-06-26 2022-06-21 Architect onitoring and Evaluation ant Selection ation PK-PTEG-232086-CS-INDV / L 4. Project Management, M Individual Consult Under Implement egal Consultant for Tourism IDA / 59820 Post Open 9,500.00 0.00 2021-05-03 2021-04-30 2021-06-05 2021-06-12 2021-06-26 2021-09-24 onitoring and Evaluation ant Selection ation Department PK-PTEG-243329-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 45,000.00 0.00 2021-07-16 2021-07-07 2021-08-18 2021-09-01 2021-09-18 2023-04-30 Environment Specialist onitoring and Evaluation ant Selection ation PK-PTEG-256619-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Limited 23,500.00 0.00 2021-11-21 2022-03-25 2021-11-26 2021-12-03 2021-12-17 2022-06-15 Consultant for Integrated Tou onitoring and Evaluation ant Selection ation rism Plan PK-PTEG-264216-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 20,000.00 0.00 2021-11-28 2021-12-14 2021-12-24 2021-12-31 2022-01-14 2023-01-09 Research Associate - I onitoring and Evaluation ant Selection ation PK-PTEG-264217-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 20,000.00 0.00 2021-11-28 2021-12-14 2021-12-24 2021-12-31 2022-01-14 2023-01-09 Research Associate - II onitoring and Evaluation ant Selection ation PK-PTEG-267380-CS-INDV / P 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 100,000.00 0.00 2021-12-17 2021-12-16 2022-01-26 2022-02-09 2022-02-23 2023-04-30 roject Director onitoring and Evaluation ant Selection ation PK-PTEG-274905-CS-INDV / 4. Project Management, M Individual Consult Under Implement Coordination Officer for Touri IDA / 59820 Post Open 21,000.00 0.00 2022-01-31 2022-01-28 2022-02-26 2022-03-05 2022-03-19 2023-03-14 onitoring and Evaluation ant Selection ation sm Department PK-PTEG-274909-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 14,000.00 0.00 2022-01-31 2022-01-28 2022-02-26 2022-03-05 2022-03-19 2023-03-14 Data Analyst for Tourism Dep onitoring and Evaluation ant Selection ation artment PK-PTEG-274911-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 14,000.00 0.00 2022-01-31 2022-01-28 2022-02-26 2022-03-05 2022-03-19 2023-03-14 Analyst for Tourism Departm onitoring and Evaluation ant Selection ation ent PK-PTEG-279726-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Limited 28,000.00 0.00 Signed 2022-02-22 2022-02-18 2022-02-27 2022-07-21 2022-03-13 2022-08-04 2022-03-27 2023-03-22 Environment Specialist onitoring and Evaluation ant Selection PK-PTEG-279729-CS-INDV / L 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Limited 20,000.00 0.00 2022-02-21 2022-02-18 2022-02-24 2022-03-03 2022-03-17 2023-03-12 iaison Officer onitoring and Evaluation ant Selection ation PK-PTEG-279736-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 21,000.00 0.00 2022-02-21 2022-02-18 2022-03-19 2022-04-02 2022-04-16 2023-04-11 Coordination Officer onitoring and Evaluation ant Selection ation PK-PTEG-286751-CS-INDV / 1. Policy, Institutions and Individual Consult Under Implement Economist - Assessment of e IDA / 59820 Governance for Tourism Dev Post Open 16,000.00 0.00 2022-04-25 2022-04-21 2022-05-21 2022-05-28 2022-06-11 2022-09-09 ant Selection ation conomic impact of the PTEGP elopment Page 7 PK-PTEG-293040-CS-INDV / 3. Public Investment Facilit Individual Consult Pending Impleme IDA / 59820 Post Open 26,000.00 0.00 2022-05-09 2022-06-04 2022-06-11 2022-06-25 2023-06-20 Conservation Specialist y ant Selection ntation PK-PTEG-302813-CS-INDV / P 4. Project Management, M Individual Consult Under Implement rocurement and Contract Ad IDA / 59820 Post Open 12,000.00 0.00 2022-07-18 2023-03-20 2022-08-20 2022-08-27 2022-09-10 2023-04-29 onitoring and Evaluation ant Selection ation ministration Officer PK-PTEG-305507-CS-INDV / P 4. Project Management, M Individual Consult IDA / 59820 Prior Open - National 20,000.00 0.00 Signed 2022-07-25 2022-07-26 2022-08-27 2022-10-21 2022-09-10 2023-05-25 2022-10-01 2023-06-01 2023-04-29 rocurement Specialist onitoring and Evaluation ant Selection PK-PTEG-321724-CS-INDV / 4. Project Management, M Individual Consult Under Implement Hiring of Financial Managem IDA / 59820 Post Open - National 15,000.00 0.00 2022-10-17 2022-10-31 2022-11-07 2023-01-05 2022-11-09 2022-11-12 2023-05-11 onitoring and Evaluation ant Selection ation ent Specialist PK-PTEG-332494-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open - National 12,000.00 0.00 2022-12-19 2022-12-12 2023-01-10 2023-01-15 2023-01-26 2023-04-30 Hiring of Electrical Engineer onitoring and Evaluation ant Selection ation PK-PTEG-347113-CS-INDV / 4. Project Management, M Individual Consult Under Implement Hiring of Digital Media & Com IDA / 59820 Post Open - National 25,000.00 0.00 2023-03-07 2023-03-20 2023-04-11 2023-04-16 2023-04-22 2024-04-21 onitoring and Evaluation ant Selection ation munication Expert PK-PTEG-347155-CS-INDV / 1. Policy, Institutions and Individual Consult Hiring of Museum Educator a IDA / 59820 Governance for Tourism Dev Post Open - National 5,000.00 0.00 Canceled 2023-03-10 2023-03-20 2023-04-08 2023-04-13 2023-04-23 2023-10-20 ant Selection t Lahore Museum elopment PK-PTEG-347167-CS-INDV / 4. Project Management, M Individual Consult Under Implement Hiring of Social Safeguard & IDA / 59820 Post Open - National 31,000.00 0.00 2023-03-10 2023-03-06 2023-04-13 2023-04-18 2023-04-28 2024-04-27 onitoring and Evaluation ant Selection ation Gender Specialist Page 8 TEXTUAL PART OF THE PROCUREMENT PLAN Support for Transition to Labor Market Project Project information: (P171471) Ministry of Labor and Social Security (MoLSS) Project Implementation The Turkish Employment Agency (ISKUR) Agencies: Turkish Red Crescent (TRC) Date of the Procurement 10 January 2022 Plan: Period covered by this 01 March 2022 - 31 December 2022 Procurement Plan: I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” November 2020 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. Any procurement activity under the Project shall not be initiated before it is approved by the Bank through STEP. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Goods, Works and Non-Consulting Services Procurement Method Procurement Method Threshold RFB/Open Default Method (No procurement method threshold) International Goods, Works and Non-consulting Services RFB/Open National Contracts less than US$2,000,000 Goods, Works and Non-Consulting Services RFQ Contracts less than US$400,000 Direct Selection No threshold III. Selection of Consultants Selection Method Selection Method Threshold Quality and Cost Based No selection method threshold Selection (QCBS) Least Cost Selection No selection method threshold (LCS) Quality Based Selection No selection method threshold (QBS) Selection Based on Consultants Contracts valued less than $600,000 Qualification (CQS) Individual Consultants No selection method threshold (IC) Direct Selection No selection method threshold The terms of references of any audit, procurement or legal consultants financed by the project shall be sent to the Bank for its comments. IV. Special Arrangements 1. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. For the procurements not subject to international competitive selection the procurement documents agreed by the Bank shall be used. 2. Review Procedure: All the procurements under the project are subject to the Bank’s ex-post review unless otherwise specified in the procurement schedule given below in Section V. 3. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. Mandatory Provisions for Procurement under Bank-Financed Contracts Subject to National Procurement Procedures: The procedures to be followed for National Open Competitive Bidding will be those set forth in the Public Procurement Law of the Borrower (Law No. 4734), as amended from time to time, with the latest amendment dated December 30, 2020, notwithstanding anything to the contrary in the Borrower’s Law on Public Procurement Contracts (Law No. 4735), as amended from time to time, with the latest amendment dated December 02, 2020, and subject to the following provisions: A. Eligibility i. Bidder eligibility will be determined as per the specifications under Section III of the Procurement Regulations; accordingly, no bidder or potential bidder will be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. ii. Bidding will not be restricted to domestic bidders. There will be no restrictions in respect to eligibility to participate in bidding for contracts on the basis of the nationality of the bidder and/or the origin of goods other than those set forth in paragraph 3.23 of the Procurement Regulations. There will be no restriction of any kind on foreign bidders who wish to submit a bid. iii. Bidding will not be restricted to pre-registered firms, and foreign bidders will not be required to be registered with the local authorities as a prerequisite for submitting bids. iv. Participation will be allowed from joint ventures on the condition that such joint venture partners will be jointly and severally liable under the contract. The Project Implementing Agencies shall use the bidding documents agreed by the Bank. B. Fraud and Corruption The request for bids/request for proposals document will require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation, the Bank’s right to sanction and the Bank’s inspection and audit rights. C. Debarment The Bank may recognize, if requested by the Borrower, exclusion from participation as a result of debarment under the national system, provided that the debarment is for offenses involving fraud and corruption, and further provided that the Bank confirms that the particular debarment procedure afforded due process, and the debarment decision is final. 4. Procurement of Second-Hand Goods: Not Applicable. 5. Domestic preference (as specified under paragraph 5.51 of the Procurement Regulations): Not applicable. 6. Operational costs will not be considered under WB procurement implementation. V. Procurement Packages with Methods and Time Schedule The estimated costs in the attached tables (sheets) (excluding deductible VAT). PROCUREMENT Turkiye : Support for Transition to Labor Market Project PLAN General Information Country: Turkiye 2023-02-27 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171471 GPN Date: 2022-06-30 Project Name: Support for Transition to Labor Market Project Loan / Credit No: TF / B7815 ISKUR Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FRIT2-GO-2.2-08-A / Procure Component 2. Support for D Request for Quota Single Stage - One E ment of Disaster Tents for Ea TF / B7815 elivery of Employment Servi Post Limited 32,000.00 0.00 Completed 2023-02-24 2023-02-28 2023-03-02 2023-03-09 2023-03-17 tions nvelope rthquake Region (60 pcs) ces FRIT2-GO-2.2-08-B / Procure Component 2. Support for D Request for Quota Single Stage - One E ment of 2 rooms container of TF / B7815 elivery of Employment Servi Post Limited 19,100.00 0.00 Completed 2023-02-24 2023-02-24 2023-03-22 2023-09-18 2023-03-19 tions nvelope fice units for earthquake regi ces on (3 pcs) FRIT2.GO-2.2-01-A / Procure Component 2. Support for D Request for Quota Single Stage - One E TF / B7815 Post Open - National 110,000.00 0.00 Completed 2023-05-02 2023-05-19 2023-06-18 2023-05-24 ment of Microsoft Licence elivery of Employment Servi tions nvelope ces FRIT2.GO-2.2-04-A / Procure Component 2. Support for D Request for Quota Single Stage - One E Pending Impl ment of IT Equipment (Lapto TF / B7815 elivery of Employment Servi Post Open - National 65,000.00 0.00 2023-06-01 2023-06-19 2023-09-17 tions nvelope ementation p, All in one desktop comput ces er, Monitor etc.) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FRIT2.NCS-2.2.03-A / Procur Component 2. Support for D Request for Quota Single Stage - One E ement of Technical Support f TF / B7815 elivery of Employment Servi Post Limited 8,900.00 0.00 Signed 2023-04-19 2023-05-16 2023-05-05 2024-12-31 tions nvelope or use of Logo Tiger Software ces CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FRIT2.CS-2.2-01-A / Procure Component 2. Support for D ment and Contract Managem TF / B7815 elivery of Employment Servi Post Direct Selection Direct - National 60,865.00 0.00 Canceled 2023-01-01 2022-12-23 2023-01-01 2022-12-25 2023-01-01 2024-12-31 ent Consultant ces FRIT2.CS-2.2-01-B / Procure Component 2. Support for D ment and Contract Managem TF / B7815 elivery of Employment Servi Post Direct Selection Direct - National 60,865.00 0.00 Canceled 2023-01-01 2022-12-23 2023-01-01 2022-12-28 2023-01-01 2024-12-31 ent Consultant ces FRIT2.CS-2.2-01-C / Project I Component 2. Support for D TF / B7815 Post Direct Selection Direct - National 39,989.00 0.00 Canceled 2023-01-01 2022-12-23 2023-01-01 2022-12-28 2023-01-01 2024-12-31 mplementation Consultant elivery of Employment Servi ces FRIT2.CS-2.2-01-D / Softwar Component 2. Support for D TF / B7815 Post Direct Selection Direct - National 64,068.00 0.00 Canceled 2023-01-01 2022-12-23 2023-01-01 2022-12-28 2023-01-01 2024-12-31 e Anaysis Consultant elivery of Employment Servi ces FRIT2.CS-2.2-01-E / Software Component 2. Support for D TF / B7815 Post Direct Selection Direct - National 76,882.00 0.00 Canceled 2023-01-01 2022-12-23 2023-01-01 2022-12-28 2023-01-01 2024-12-31 Development Consultant elivery of Employment Servi ces FRIT2.CS-2.2-01-F / Grafic D Component 2. Support for D TF / B7815 Post Direct Selection Direct - National 30,666.00 0.00 Canceled 2023-01-01 2022-12-23 2023-01-01 2023-01-01 2024-12-31 esigner Consultant elivery of Employment Servi ces FRIT2.CS-2.2-01-G / Softwar Component 2. Support for D TF / B7815 Post Direct Selection Direct - National 33,316.00 0.00 Canceled 2023-01-01 2022-12-23 2023-01-01 2022-12-28 2023-01-01 2024-12-31 e Development Consultant elivery of Employment Servi ces FRIT2.CS-2.2-01-H / Softwar Component 2. Support for D TF / B7815 Post Direct Selection Direct - National 64,068.00 0.00 Canceled 2023-01-01 2022-12-23 2023-01-01 2022-12-28 2023-01-01 2024-12-31 e Development Consultant elivery of Employment Servi ces FRIT2.CS-2.2-01-I / Software Component 2. Support for D TF / B7815 Post Direct Selection Direct - National 64,068.00 0.00 Canceled 2023-01-01 2022-12-23 2023-01-01 2023-01-01 2024-12-31 Development Consultant elivery of Employment Servi ces FRIT2.CS-2.2-01-J / Software Component 2. Support for D TF / B7815 Post Direct Selection Direct - National 28,190.00 0.00 Canceled 2023-01-01 2022-12-23 2023-01-01 2023-01-01 2024-12-31 Development Consultant elivery of Employment Servi ces FRIT2.CS-2.2-01-K / Software Component 2. Support for D TF / B7815 Post Direct Selection Direct - National 76,882.00 0.00 Canceled 2023-01-01 2022-12-23 2023-01-01 2023-01-01 2024-12-31 Development Consultant elivery of Employment Servi ces FRIT2.CS-2.2-01-L / Financial Component 2. Support for D TF / B7815 Post Direct Selection Direct - National 54,530.00 0.00 Canceled 2023-01-01 2022-12-23 2023-01-01 2022-12-28 2023-01-01 2024-12-31 Management Consultant elivery of Employment Servi ces Page 1 FRIT2.CS-2.2-01-M / Financia Component 2. Support for D TF / B7815 Post Direct Selection Direct - National 54,530.00 0.00 Canceled 2023-01-01 2022-12-23 2023-01-01 2023-01-01 2024-12-31 l Management Consultant elivery of Employment Servi ces FRIT2.CS-2.2-03-A / Local Fin Component 2. Support for D ancial Management Consulta TF / B7815 elivery of Employment Servi Post Direct Selection Direct - National 32,718.00 0.00 Canceled 2023-01-01 2022-12-23 2023-01-01 2022-12-28 2023-01-01 2024-12-31 nt (Şanlıurfa) ces FRIT2.CS-2.2-03-B / Local Fin Component 2. Support for D TF / B7815 Post Direct Selection Direct - National 32,718.00 0.00 Canceled 2023-01-01 2022-12-23 2023-01-01 2023-01-01 2024-12-31 ancial Management Consulta elivery of Employment Servi nt (Adana) ces FRIT2.CS-2.2-03-C / Local Plr Component 2. Support for D ocurement and Contract Man TF / B7815 elivery of Employment Servi Post Direct Selection Direct - National 32,718.00 0.00 Canceled 2023-01-01 2022-12-23 2023-01-01 2022-12-28 2023-01-01 2024-12-31 agement Consultant (İstanbu ces l) FRIT2.CS-2.2-05-A / Project S Component 2. Support for D TF / B7815 Post Direct Selection Direct - National 22,658.00 0.00 Canceled 2023-01-01 2022-12-23 2023-01-01 2023-01-01 2024-12-31 upport Personnel (Ankara) elivery of Employment Servi ces FRIT2.CS-2.2-05-B / Project S Component 2. Support for D TF / B7815 Post Direct Selection Direct - National 22,658.00 0.00 Canceled 2023-01-01 2022-12-23 2023-01-01 2023-01-01 2024-12-31 upport Personnel (Ankara) elivery of Employment Servi ces FRIT2.CS-2.2-05-C / Project S Component 2. Support for D TF / B7815 Post Direct Selection Direct - National 22,658.00 0.00 Canceled 2023-01-01 2022-12-23 2023-01-01 2022-12-28 2023-01-01 2024-12-31 upport Personnel (Adana) elivery of Employment Servi ces FRIT2.CS-2.2-05-D / Project Component 2. Support for D TF / B7815 Post Direct Selection Direct - National 22,658.00 0.00 Canceled 2023-01-01 2022-12-23 2023-01-01 2023-01-01 2024-12-31 Support Personnel (Adana) elivery of Employment Servi ces FRIT2.CS-2.2-05-E / IT Projec Component 2. Support for D TF / B7815 Post Direct Selection Direct - National 22,658.00 0.00 Canceled 2023-01-01 2022-12-23 2023-01-01 2023-01-01 2024-12-31 t Support Personnel (Ankara) elivery of Employment Servi ces FRIT2.CS-2.2-05-F / IT Projec Component 2. Support for D TF / B7815 Post Direct Selection Direct - National 22,658.00 0.00 Canceled 2023-01-01 2022-12-23 2023-01-01 2023-01-01 2024-12-31 t Support Personnel (Ankara) elivery of Employment Servi ces FRIT2.CS-2.2-02-B / Project C Component 2. Support for D Individual Consult TF / B7815 Post Open - National 76,000.00 0.00 Signed 2023-02-17 2022-12-23 2023-03-17 2023-04-18 2023-03-27 2023-04-14 2023-03-29 2024-12-31 oordination Consultant elivery of Employment Servi ant Selection ces FRIT2.CS-2.2-02-C / Project C Component 2. Support for D Individual Consult TF / B7815 Post Open - National 53,000.00 0.00 Signed 2023-01-18 2022-12-23 2023-02-25 2023-04-18 2023-03-07 2023-04-18 2023-04-01 2023-12-31 oordination Consultant elivery of Employment Servi ant Selection ces FRIT2.CS-2.2-02-D / Monitori Component 2. Support for D Individual Consult Under Implement TF / B7815 Post Open - National 53,000.00 0.00 2023-01-18 2022-12-23 2023-03-08 2023-03-29 2023-05-03 2024-12-31 ng and Evaluation Consultant elivery of Employment Servi ant Selection ation ces FRIT2.CS-2.2-02-A / Software Component 2. Support for D Individual Consult TF / B7815 Post Open - National 76,882.00 0.00 Signed 2022-08-16 2022-08-01 2022-10-12 2022-12-12 2022-11-02 2022-12-13 2022-12-14 2024-12-31 Development Consultant elivery of Employment Servi ant Selection ces FRIT2.CS-2.2-02-E / Senior S Component 2. Support for D Individual Consult TF / B7815 Post Open - National 60,000.00 0.00 Canceled 2023-01-17 2023-01-19 2023-03-07 2023-03-28 2023-05-02 2024-12-31 oftware Development Consul elivery of Employment Servi ant Selection tant ces FRIT2.CS-2.2-02-I / WEB Co Component 2. Support for D Individual Consult Under Implement TF / B7815 Post Open - National 45,000.00 0.00 2023-01-17 2023-01-19 2023-03-07 2023-05-12 2023-03-28 2023-05-18 2023-05-02 2024-12-31 nsultant elivery of Employment Servi ant Selection ation ces FRIT2.CS-2.2-02-H / Senior M Component 2. Support for D Individual Consult TF / B7815 Post Open - National 36,000.00 0.00 Canceled 2023-01-17 2023-01-19 2023-03-07 2023-03-28 2023-05-02 2024-05-01 S SQL Consultant (Ankara) elivery of Employment Servi ant Selection ces FRIT2.CS-2.2-01-A_ / Procure Component 2. Support for D Individual Consult ment and Contract Managem TF / B7815 elivery of Employment Servi Post Direct - National 60,865.00 0.00 Signed 2022-12-01 2022-12-22 2022-12-07 2022-12-28 2022-12-08 2022-12-28 2022-12-30 2024-12-31 ant Selection ent Consultant ces FRIT2.CS-2.2-01-B_ / Procure Component 2. Support for D Individual Consult ment and Contract Managem TF / B7815 elivery of Employment Servi Post Direct - National 60,865.00 0.00 Signed 2022-12-01 2022-12-22 2022-12-07 2022-12-28 2022-12-08 2023-01-28 2022-12-30 2024-12-31 ant Selection ent Consultant ces FRIT2.CS-2.2-01-C_ / Project Component 2. Support for D Individual Consult TF / B7815 Post Direct - National 39,989.00 0.00 Signed 2022-12-01 2022-12-22 2022-12-07 2022-12-28 2022-12-08 2022-12-28 2022-12-30 2024-12-31 Implementation Consultant elivery of Employment Servi ant Selection ces FRIT2.CS-2.2-01-D_ / Softwar Component 2. Support for D Individual Consult TF / B7815 Post Direct - National 64,068.00 0.00 Signed 2022-12-01 2022-12-22 2022-12-07 2022-12-28 2022-12-08 2022-12-28 2022-12-30 2024-12-31 e Anaysis Consultant elivery of Employment Servi ant Selection ces FRIT2.CS-2.2-01-E_ / Softwar Component 2. Support for D Individual Consult TF / B7815 Post Direct - National 76,882.00 0.00 Signed 2022-12-01 2022-12-22 2022-12-07 2022-12-28 2022-12-08 2022-12-28 2022-12-30 2024-12-31 e Development Consultant elivery of Employment Servi ant Selection ces FRIT2.CS-2.2-01-F_ / Grafic D Component 2. Support for D Individual Consult TF / B7815 Post Direct - National 30,666.00 0.00 Signed 2022-12-01 2022-12-22 2022-12-07 2022-12-28 2022-12-08 2022-12-28 2022-12-30 2024-12-31 esigner Consultant elivery of Employment Servi ant Selection ces FRIT2.CS-2.2-01-G_ / Softwar Component 2. Support for D Individual Consult TF / B7815 Post Direct - National 33,316.00 0.00 Signed 2022-12-01 2022-12-22 2022-12-07 2022-12-28 2022-12-08 2022-12-28 2022-12-30 2024-12-31 e Development Consultant elivery of Employment Servi ant Selection ces FRIT2.CS-2.2-01-H_ / Softwar Component 2. Support for D Individual Consult TF / B7815 Post Direct - National 64,068.00 0.00 Signed 2022-12-01 2022-12-22 2022-12-07 2022-12-28 2022-12-08 2022-12-28 2022-12-30 2024-12-31 e Development Consultant elivery of Employment Servi ant Selection ces FRIT2.CS-2.2-01-I_ / Softwar Component 2. Support for D Individual Consult TF / B7815 Post Direct - National 64,068.00 0.00 Signed 2022-12-01 2022-12-22 2022-12-07 2022-12-28 2022-12-08 2022-12-28 2022-12-30 2024-12-31 e Development Consultant elivery of Employment Servi ant Selection ces FRIT2.CS-2.2-01-J_ / Softwar Component 2. Support for D Individual Consult TF / B7815 Post Direct - National 28,190.00 0.00 Signed 2022-12-01 2022-12-22 2022-12-07 2022-12-28 2022-12-08 2022-12-28 2022-12-30 2024-12-31 e Development Consultant elivery of Employment Servi ant Selection ces FRIT2.CS-2.2-01-K_ / Softwar Component 2. Support for D Individual Consult TF / B7815 Post Direct - National 76,882.00 0.00 Signed 2022-12-01 2022-12-22 2022-12-07 2022-12-28 2022-12-08 2022-12-28 2022-12-30 2024-12-31 e Development Consultant elivery of Employment Servi ant Selection ces FRIT2.CS-2.2-01-L_ / Financi Component 2. Support for D Individual Consult TF / B7815 Post Direct - National 54,530.00 0.00 Signed 2022-12-01 2022-12-22 2022-12-07 2022-12-28 2022-12-08 2022-12-28 2022-12-30 2024-12-31 al Management Consultant elivery of Employment Servi ant Selection ces FRIT2.CS-2.2-01-M_ / Financi Component 2. Support for D Individual Consult TF / B7815 Post Direct - National 54,530.00 0.00 Signed 2022-12-01 2022-12-22 2022-12-07 2022-12-24 2022-12-08 2022-12-28 2022-12-30 2024-12-31 al Management Consultant elivery of Employment Servi ant Selection ces FRIT2.CS-2.2-03-A_ / Local Fi Component 2. Support for D Individual Consult nancial Management Consult TF / B7815 elivery of Employment Servi Post Direct - National 32,718.00 0.00 Signed 2022-12-01 2022-12-22 2022-12-07 2022-12-28 2022-12-08 2022-12-28 2022-12-30 2024-12-31 ant Selection ant (Şanlıurfa) ces FRIT2.CS-2.2-03-B_ / Local Fi Component 2. Support for D Individual Consult nancial Management Consult TF / B7815 elivery of Employment Servi Post Direct - National 32,718.00 0.00 Signed 2022-12-01 2022-12-22 2022-12-07 2022-12-28 2022-12-08 2022-12-28 2022-12-30 2024-12-31 ant Selection ant (Adana) ces Page 2 FRIT2.CS-2.2-03-C_ / Local Pl Component 2. Support for D Individual Consult rocurement and Contract Ma TF / B7815 elivery of Employment Servi Post Direct - National 32,718.00 0.00 Signed 2022-12-01 2022-12-22 2022-12-07 2022-12-28 2022-12-08 2023-01-30 2022-12-30 2024-12-31 ant Selection nagement Consultant (İstanb ces ul) FRIT2.CS-2.2-05-A_ / Project Component 2. Support for D Individual Consult TF / B7815 Post Direct - National 22,658.00 0.00 Signed 2022-12-01 2022-12-22 2022-12-07 2022-12-28 2022-12-08 2022-12-28 2022-12-30 2024-12-31 Support Personnel (Ankara) elivery of Employment Servi ant Selection ces FRIT2.CS-2.2-05-B_ / Project Component 2. Support for D Individual Consult TF / B7815 Post Direct - National 22,658.00 0.00 Signed 2022-12-01 2022-12-22 2022-12-07 2022-12-28 2022-12-08 2022-12-28 2022-12-30 2024-12-31 Support Personnel (Ankara) elivery of Employment Servi ant Selection ces FRIT2.CS-2.2-05-C_ / Project Component 2. Support for D Individual Consult TF / B7815 Post Direct - National 22,658.00 0.00 Signed 2022-12-01 2022-12-22 2022-12-07 2022-12-28 2022-12-08 2022-12-28 2022-12-30 2024-12-31 Support Personnel (Adana) elivery of Employment Servi ant Selection ces FRIT2.CS-2.2-05-D_ / Project Component 2. Support for D Individual Consult TF / B7815 Post Direct - National 22,658.00 0.00 Signed 2022-12-01 2022-12-22 2022-12-07 2022-12-28 2022-12-08 2022-12-28 2022-12-30 2024-12-31 Support Personnel (Adana) elivery of Employment Servi ant Selection ces FRIT2.CS-2.2-05-E_ / IT Proje Component 2. Support for D Individual Consult TF / B7815 Post Direct - National 22,658.00 0.00 Signed 2022-12-01 2022-12-22 2022-12-07 2022-12-28 2022-12-08 2022-12-28 2022-12-30 2024-12-31 ct Support Personnel (Ankara elivery of Employment Servi ant Selection ) ces FRIT2.CS-2.2-05-F_ / IT Proje Component 2. Support for D Individual Consult TF / B7815 Post Direct - National 22,658.00 0.00 Signed 2022-12-01 2022-12-22 2022-12-07 2022-12-28 2022-12-08 2022-12-28 2022-12-30 2024-12-31 ct Support Personnel (Ankara elivery of Employment Servi ant Selection ) ces FRIT2.CS-2.2-02-J / Individual Component 2. Support for D Individual Consult Under Implement Procurement and Contract M TF / B7815 elivery of Employment Servi Post Open - National 52,000.00 0.00 2023-06-16 2023-05-31 2023-07-27 2023-07-31 2023-08-01 2024-12-31 ant Selection ation anagement Consultant ces FRIT2.CS-2.2-06-A / Project S Component 2. Support for D Individual Consult Under Implement TF / B7815 Post Open - National 19,000.00 0.00 2023-06-16 2023-05-31 2023-07-27 2023-07-31 2023-08-01 2024-12-31 upport Staff (Procurement) ( elivery of Employment Servi ant Selection ation Ankara) ces FRIT2.CS-2.2-06-B / Project S Component 2. Support for D Individual Consult Under Implement TF / B7815 Post Open - National 19,000.00 0.00 2023-06-16 2023-05-31 2023-07-27 2023-07-31 2023-08-01 2024-12-31 upport Staff (Procurement) ( elivery of Employment Servi ant Selection ation Ankara) ces FRIT2.CS-2.2-04-A / Individu Component 2. Support for D Individual Consult Under Implement al Financial Management Con TF / B7815 elivery of Employment Servi Post Open - National 21,600.00 0.00 2023-06-21 2023-06-20 2023-07-24 2023-07-25 2023-08-01 2024-12-31 ant Selection ation sultant (İstanbul) ces FRIT2.CS-2.2-04-B / Individu Component 2. Support for D Individual Consult Under Implement al Financial Management Con TF / B7815 elivery of Employment Servi Post Open - National 21,600.00 0.00 2023-06-21 2023-06-20 2023-07-24 2023-07-25 2023-08-01 2024-12-31 ant Selection ation sultant (İstanbul) ces FRIT2.CS-2.2-04-D / Individu Component 2. Support for D Individual Consult Under Implement al Financial Management Con TF / B7815 elivery of Employment Servi Post Open - National 21,600.00 0.00 2023-06-21 2023-06-20 2023-07-24 2023-07-25 2023-08-01 2024-12-31 ant Selection ation sultant (Sanlıurfa) ces FRIT2.CS-2.2-04-C / Individu Component 2. Support for D Individual Consult Under Implement al Financial Management Con TF / B7815 elivery of Employment Servi Post Open - National 21,600.00 0.00 2023-06-21 2023-06-20 2023-07-24 2023-07-25 2023-08-01 2024-12-31 ant Selection ation sultant (Gaziantep) ces FRIT2.CS-2.2-04-H / Individu Component 2. Support for D Individual Consult Under Implement al Financial Management Con TF / B7815 elivery of Employment Servi Post Open - National 21,600.00 0.00 2023-06-21 2023-06-20 2023-07-24 2023-07-25 2023-08-01 2024-12-31 ant Selection ation sultant (Konya) ces FRIT2.CS-2.2-04-E / Individu Component 2. Support for D Individual Consult Under Implement al Financial Management Con TF / B7815 elivery of Employment Servi Post Open - National 21,600.00 0.00 2023-06-21 2023-06-20 2023-07-24 2023-07-25 2023-08-01 2024-12-31 ant Selection ation sultant (Kocaeli) ces FRIT2.CS-2.2-04-F / Individua Component 2. Support for D Individual Consult Under Implement l Financial Management Cons TF / B7815 elivery of Employment Servi Post Open - National 21,600.00 0.00 2023-06-21 2023-06-20 2023-07-24 2023-07-25 2023-08-01 2024-12-31 ant Selection ation ultant (İzmir) ces FRIT2.CS-2.2-04-G / Individu Component 2. Support for D Individual Consult Under Implement al Financial Management Con TF / B7815 elivery of Employment Servi Post Open - National 21,600.00 0.00 2023-06-21 2023-06-20 2023-07-24 2023-07-25 2023-08-01 2024-12-31 ant Selection ation sultant (Bursa) ces Page 3 PREPARATION ACTIVITIES FOR BIOCARBON FUND INITIATIVES FOR SUSTAINABLE FOREST LANDSCAPES (BIOCF ISFL) PROJECT No. TF OA7246 And TF OA7244 Procurement Plan Version No.: 2 Date: May, 16 2019 I. General Information 1. Project information: a. Country: Indonesia b. Recipient: Republic of Indonesia c. Project Name: Bio Carbon Fund ISFL , Jambi Province d. Project Executing Agency (PEA): Directorate for Mitigation of Climate Change under the Directorate General of Climate Change 2. Bank’s No Objection Date of the Procurement Plan: a. Original : July 25, 2018 b. Version 2 : May, 16, 2019 c. Version … : … 3. Date of General Procurement Notice: … 4. Period covered by this procurement plan: Feb 1, 2019 – Dec 31, 2019 II. Types of Contract, Bank’s Review Requirements and Applied Methods A. Works, Goods and Non-Consulting Services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Ref. Procureme Bank’s Review Procurement Method No. nt Method Requirement 1. Shopping for Goods (RFQ) <$100k Threshold Post Review 2. Individual Consultant N/A < $0,3 million , Post (Competitive Selection ) Review , except for Procurement Specialist and Financial Management Specialist (Prior Review) 1. Pre-qualification: Not applicable. 2. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: 3. Reference to (if any) Project Operational/Procurement Manual: Perpres 16/2018 from GOI and Procurement Guidelines World Bank 4. Any Other Special Procurement Arrangements: -N/A- 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Descripti Estimat Packag Domesti Revie Commen No. on ed es c w ts Cost Prefere by (US$ nce Bank million) (yes/no) (Prior / Post) 1. Summary 0.098 2 Yes Post of the NCB (Goods) B. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to prior review by Bank as stated in Appendix 1 to the Guidelines for Selection and Employment of Consultants: Ref. Selection Selection Method Bank’s Prior Review No. Method Threshold Requirement Ref. Selection Selection Method Bank’s Prior Review No. Method Threshold Requirement 1. Individual Competitive Selection by None, except for Consultant comparing at least three Procurement Specialist CVs and Financial Management Specialist. 2. Short list comprising entirely of national consultants: Short list of consultants for services (individual Consultant), estimated to cost less than $ 28,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: N/A 4. Summary of Consultancy Assignments with Selection Methods and Time Schedule during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 4 5 6 7 Ref Description Estimat Packag Revie Commen . of ed es/Posit w ts No. Assignments Cost ions by (US$ Bank million) (Prior / Post) 1. Summary of 0,20 13 Post Individual number of consultant individual to consultant conduct contracts that research, will be let Deputy under Coordinat competitive or and selection Supportin g Staff 2. Summary of 0,028 2 Prior Procurem number of ent individual Specialist consultant and contracts that Financial will be let Managem under ent competitive Specialist selection PROCUREMENT Indonesia : ID: Jambi Sustainable Landscape Management Project (J-SLMP) PLAN General Information Country: Indonesia 2022-06-14 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166672 GPN Date: 2021-06-24 Project Name: ID: Jambi Sustainable Landscape Management Project (J-SLMP) Loan / Credit No: TF / B3897 Dinas Kehutanan Provinsi Jambi Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ID-DISHUT PROV. JAMBI-316 Request for Quota Implementing Sustainable L Request for Quota Single Stage - One E Under Imple 2022-12-1 169-CW-RFQ / Procurement o TF / B3897 Post Limited tions (Non Bank-S 13,142.00 0.00 2022-10-12 2022-11-14 2022-10-20 and Management tions nvelope mentation 9 f Hotspot tower construction PD) in Jambi Province ID-DISHUT PROV. JAMBI-350 Request for Quota Implementing Sustainable L Request for Quota Single Stage - One E Pending Imp 2023-05-2 202-CW-RFQ / Procurement o TF / B3897 Post Limited tions (Non Bank-S 3,935.00 0.00 2023-03-17 2023-03-23 and Management tions nvelope lementation 2 f wacth tower in KPH Bungo PD) ID-DISHUT PROV. JAMBI-356 Request for Quota Implementing Sustainable L Request for Quota Single Stage - One E Pending Imp 2023-05-1 165-CW-RFQ / Procurement o TF / B3897 Post Limited tions (Non Bank-S 1,089.00 0.00 2023-04-13 2023-04-19 and Management tions nvelope lementation 9 f work hut in KPH Merangin PD) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-DISHUT PROV. JAMBI-295 Implementing Sustainable L Single Stage - One E Pending Impl 958-GO-RFB / Procurement of TF / B3897 Post Request for Bids Open - National 35,714.28 0.00 2022-05-23 2022-05-28 2022-06-06 2022-06-13 2022-06-27 2022-07-27 and Management nvelope ementation Portable Reservoir ID-DISHUT PROV. JAMBI-296 Implementing Sustainable L Single Stage - One E Pending Impl 380-GO-RFB / Procurement of TF / B3897 Post Request for Bids Open - National 29,503.65 0.00 2022-05-24 2022-05-31 2022-06-07 2022-06-14 2022-06-28 2022-07-19 and Management nvelope ementation Fire Extinguisher Packages ID-DISHUT PROV. JAMBI-296 Implementing Sustainable L Single Stage - One E Pending Impl 425-GO-RFB / Procurement s TF / B3897 Post Request for Bids Open - National 22,432.14 0.00 2022-08-01 2022-08-06 2022-08-11 2022-08-18 2022-09-01 2022-09-15 and Management nvelope ementation eedling of avocado, durian a nd mango ID-DISHUT PROV. JAMBI-296 Implementing Sustainable L Single Stage - One E Under Imple 446-GO-RFB / Procurement s TF / B3897 Post Request for Bids Open - National 55,746.42 0.00 2022-05-30 2022-08-05 2022-06-06 2022-06-13 2022-06-20 2022-07-27 2022-08-10 and Management nvelope mentation eedling of Jelutung ID-DISHUT PROV. JAMBI-296 Implementing Sustainable L Single Stage - One E Pending Impl 453-GO-RFB / Procurement s TF / B3897 Post Request for Bids Open - National 21,285.00 0.00 2022-05-30 2022-06-06 2022-06-13 2022-06-20 2022-07-04 2022-07-18 and Management nvelope ementation eedling of Jackfruit ID-DISHUT PROV. JAMBI-296 Implementing Sustainable L Single Stage - One E Pending Impl 466-GO-RFB / Procurement of TF / B3897 Post Request for Bids Open - National 26,352.85 0.00 2022-05-30 2022-06-06 2022-06-13 2022-06-20 2022-07-04 2022-07-18 and Management nvelope ementation betel palm seedling ID-DISHUT PROV. JAMBI-296 609-GO-RFB / Procurement s Implementing Sustainable L Single Stage - One E Pending Impl TF / B3897 Post Request for Bids Open - National 57,621.87 0.00 2022-06-02 2022-06-07 2022-06-14 2022-06-21 2022-07-05 2022-07-26 eedling of Cinamon, Jackfruit, and Management nvelope ementation petai and Surian (Toona Sure ni) ID-DISHUT PROV. JAMBI-296 Implementing Sustainable L Single Stage - One E Pending Impl 613-GO-RFB / Procurement s TF / B3897 Post Request for Bids Open - National 23,767.50 0.00 2022-06-02 2022-06-07 2022-06-14 2022-06-21 2022-07-05 2022-07-26 and Management nvelope ementation eedling of sugar palm tree an d coffee DISHUT/5.1/2/V/2022 / Procu Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl rement of seeds in Jambi Pro TF / B3897 Post Limited 3,027.00 0.00 2022-05-22 2022-07-17 2023-01-13 and Management tions nvelope ementation vince by the forestry service ID-DISHUT PROV. JAMBI-311 Implementing Sustainable L Request for Quota Single Stage - One E Under Imple TF / B3897 Post Limited 2,678.00 0.00 2022-09-03 2022-07-22 2022-09-09 2022-09-23 423-GO-RFQ / Procurement o and Management tions nvelope mentation f dolomite ID-DISHUT PROV. JAMBI-311 Implementing Sustainable L Request for Quota Single Stage - One E Under Imple 429-GO-RFQ / Procurement o TF / B3897 Post Limited 5,961.00 0.00 2022-09-03 2022-07-22 2022-09-09 2022-10-09 and Management tions nvelope mentation f organic fertiliser ID-DISHUT PROV. JAMBI-311 Implementing Sustainable L Request for Quota Single Stage - One E TF / B3897 Post Limited 10,135.00 0.00 Signed 2022-09-03 2022-07-22 2022-09-09 2022-10-09 432-GO-RFQ / Procurement o and Management tions nvelope f stake ID-DISHUT PROV. JAMBI-311 441-GO-RFQ / procurement o Implementing Sustainable L Request for Quota Single Stage - One E TF / B3897 Post Limited 4,158.00 0.00 Signed 2022-09-03 2022-08-09 2022-09-09 2022-10-09 f information boards at KPH T and Management tions nvelope anjung Jabung Barat Agency ID-DISHUT PROV. JAMBI-311 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 449-GO-RFQ / Procurement o TF / B3897 Post Limited 5,000.00 0.00 2022-09-03 2022-09-09 2022-10-09 and Management tions nvelope ementation f motorcycle ID-DISHUT PROV. JAMBI-311 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 456-GO-RFQ / Procurement o TF / B3897 Post Limited 12,857.00 0.00 2022-09-03 2022-09-09 2022-10-09 and Management tions nvelope ementation f fire exstinguisher ID-DISHUT PROV. JAMBI-311 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl TF / B3897 Post Limited 3,571.00 0.00 2022-10-05 2022-10-11 2022-11-10 458-GO-RFQ / Procurement o and Management tions nvelope ementation f drone ID-DISHUT PROV. JAMBI-311 Implementing Sustainable L Request for Quota Single Stage - One E Under Imple 769-GO-RFQ / Procurement o TF / B3897 Post Limited 5,000.00 0.00 2022-10-05 2022-08-22 2022-10-11 2022-11-10 and Management tions nvelope mentation f motorcycle ID-DISHUT PROV. JAMBI-311 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 770-GO-RFQ / Procurement o TF / B3897 Post Limited 4,000.00 0.00 2022-10-05 2022-10-11 2022-11-10 and Management tions nvelope ementation f palm sugar process machin e Page 1 ID-DISHUT PROV. JAMBI-311 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 775-GO-RFQ / Procurement o TF / B3897 Post Limited 2,217.00 0.00 2022-10-05 2022-10-11 2022-11-10 and Management tions nvelope ementation f coffee roaster machine ID-DISHUT PROV. JAMBI-311 810-GO-RFB / Procurement of Implementing Sustainable L Single Stage - One E Pending Impl TF / B3897 Post Request for Bids Open - National 31,301.00 0.00 2022-10-03 2022-10-08 2022-10-13 2022-10-18 2022-10-28 2022-12-12 timber tree, jelutung, rubber, and Management nvelope ementation coffee, avocado seedlings ID-DISHUT PROV. JAMBI-311 818-GO-RFB / Procurement of Implementing Sustainable L Request for Quota Single Stage - One E TF / B3897 Post Limited 16,200.00 0.00 Canceled 2022-09-21 2022-09-29 2022-10-02 betel nut seedlings in Jambi P and Management tions nvelope rovince by the forestry servic e ID-DISHUT PROV. JAMBI-311 831-GO-RFQ / Procurement o Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl TF / B3897 Post Limited 4,934.00 0.00 2022-10-05 2022-10-11 2022-11-10 f Herbicides for pest control and Management tions nvelope ementation by the forestry service ID-DISHUT PROV. JAMBI-311 Implementing Sustainable L Request for Quota Single Stage - One E Under Imple 842-GO-RFQ / procurement o TF / B3897 Post Limited 8,180.00 0.00 2022-10-05 2022-10-11 2022-11-10 and Management tions nvelope mentation f plant stake in Jambi by fore stry service ID-DISHUT PROV. JAMBI-296 Implementing Sustainable L Single Stage - One E TF / B3897 Post Request for Bids Open - National 24,285.71 0.00 Canceled 2022-05-30 2022-06-05 2022-06-12 2022-06-19 2022-07-17 2022-07-31 401-GO-RFB / Procurement of and Management nvelope Drone ID-DISHUT PROV. JAMBI-312 Implementing Sustainable L Pending Impl 738-GO-EA / Procurement of TF / B3897 Post Direct Selection Direct - National 24,286.00 0.00 2022-09-19 2022-09-21 2022-09-27 2022-10-27 and Management ementation drones in Jambi Province ID-DISHUT PROV. JAMBI-296 Implementing Sustainable L Single Stage - One E TF / B3897 Post Request for Bids Open - National 28,571.49 0.00 Canceled 2022-05-30 2022-06-04 2022-06-11 2022-06-18 2022-07-02 2022-07-22 389-GO-RFB / Procurement of and Management nvelope Motorcycle ID-DISHUT PROV. JAMBI-313 Implementing Sustainable L Pending Impl 592-GO-EA / Procurement of TF / B3897 Post Direct Selection Direct - National 28,571.00 0.00 2022-09-19 2022-09-21 2022-09-27 2022-10-27 and Management ementation motorcycles in Jambi Provinc e ID-DISHUT PROV. JAMBI-314 Implementing Sustainable L Pending Impl 979-GO-DIR / Procurement of TF / B3897 Post Direct Selection Direct - National 17,782.00 0.00 2022-09-19 2022-09-21 2022-09-27 2022-10-27 and Management ementation fire extinguisher ID-DISHUT PROV. JAMBI-296 Implementing Sustainable L Single Stage - One E 443-GO-RFB / Procurement of TF / B3897 Post Request for Bids Open - National 17,752.28 0.00 Canceled 2022-05-30 2022-06-06 2022-06-13 2022-06-20 2022-07-04 2022-07-18 and Management nvelope Fire Extinguisher ID-DISHUT PROV. JAMBI-320 Implementing Sustainable L Pending Impl 701-GO-DIR / Procurement of TF / B3897 Post Direct Selection Direct - National 8,571.00 0.00 2022-10-23 2022-10-25 2022-10-31 2022-11-30 and Management ementation motorcycles in Tanjung Jabun g Barat ID-DISHUT PROV. JAMBI-321 728-GO-RFQ / Procurement o Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl TF / B3897 Post Limited 16,200.00 0.00 2022-10-25 2022-11-02 2022-12-02 f betel nut seedling in Jambi and Management tions nvelope ementation Province by the forestry servi ce ID-DISHUT PROV. JAMBI-345 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 854-GO-RFQ / Procurement o TF / B3897 Post Limited 3,600.00 0.00 2023-03-08 2023-03-17 2023-03-31 and Management tions nvelope ementation f stake in Jambi Province ID-DISHUT PROV. JAMBI-345 874-GO-RFQ / Procurement s Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl TF / B3897 Post Limited 45,831.00 0.00 2023-03-06 2023-04-03 2023-09-30 eedling of Jelutung, Meranti, and Management tions nvelope ementation Betel nut, Tembesi, Cinamon and coffee ID-DISHUT PROV. JAMBI-345 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 882-GO-RFQ / Procurement o TF / B3897 Post Limited 10,000.00 0.00 2023-03-03 2023-03-13 2023-04-12 and Management tions nvelope ementation f Prohibition board in Jambi P rovince ID-DISHUT PROV. JAMBI-345 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 955-GO-RFQ / Procurement o TF / B3897 Post Limited 3,667.00 0.00 2023-03-03 2023-03-13 2023-03-27 and Management tions nvelope ementation f GPS, Laptop in KPH Merangi n ID-DISHUT PROV. JAMBI-345 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 969-GO-RFQ / Procurement o TF / B3897 Post Limited 4,667.00 0.00 2023-03-03 2023-03-13 2023-03-27 and Management tions nvelope ementation f motorcylces ID-DISHUT PROV. JAMBI-345 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 985-GO-RFQ / Procurement o TF / B3897 Post Limited 4,000.00 0.00 2023-03-03 2023-03-13 2023-03-27 and Management tions nvelope ementation f fire pump in KPH Merangin ID-DISHUT PROV. JAMBI-346 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 008-GO-RFQ / Procurement o TF / B3897 Post Limited 2,695.00 0.00 2023-03-03 2023-03-13 2023-04-12 and Management tions nvelope ementation f socialization Tshirt ID-DISHUT PROV. JAMBI-346 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 244-GO-RFQ / Procurement s TF / B3897 Post Limited 16,677.00 0.00 2023-03-03 2023-03-13 2023-03-27 and Management tions nvelope ementation eedling of aren and coffee ID-DISHUT PROV. JAMBI-346 248-GO-RFQ / Procurement o Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl TF / B3897 Post Limited 84,498.00 0.00 2023-03-03 2023-03-13 2023-04-12 f stake, Seedling of Avocado, and Management tions nvelope ementation Cinamon, Durian, Surian, Pet ai, Bambang Lanang ID-DISHUT PROV. JAMBI-346 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 253-GO-RFQ / Procurement o TF / B3897 Post Limited 4,667.00 0.00 2023-03-03 2023-03-13 2023-04-12 and Management tions nvelope ementation f motorcycle in KPH Sarolang un ID-DISHUT PROV. JAMBI-346 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 254-GO-RFQ / Procurement o TF / B3897 Post Limited 2,328.00 0.00 2023-03-03 2023-03-13 2023-03-27 and Management tions nvelope ementation f Fertilizer in KPH Merangin ID-DISHUT PROV. JAMBI-346 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl TF / B3897 Post Limited 3,982.00 0.00 2023-03-03 2023-03-13 2023-03-27 255-GO-RFQ / Procurement o and Management tions nvelope ementation f fertilizer ID-DISHUT PROV. JAMBI-346 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 262-GO-RFQ / Procurement o TF / B3897 Post Limited 4,968.00 0.00 2023-03-03 2023-03-13 2023-03-27 and Management tions nvelope ementation f fertilizer in KPH Merangin Page 2 ID-DISHUT PROV. JAMBI-346 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 271-GO-RFQ / Procurement s TF / B3897 Post Limited 11,147.00 0.00 2023-03-03 2023-03-13 2023-04-12 and Management tions nvelope ementation eedling of petai ID-DISHUT PROV. JAMBI-346 275-GO-RFQ / Procurement s Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl TF / B3897 Post Limited 1,010.00 0.00 2023-03-03 2023-03-13 2023-03-27 eedling of aren, duku, jengko and Management tions nvelope ementation l, petai, areca nut and fertiliz er in Jambi Province ID-DISHUT PROV. JAMBI-346 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 277-GO-RFQ / Procurement o TF / B3897 Post Limited 6,253.00 0.00 2023-03-03 2023-03-13 2023-03-27 and Management tions nvelope ementation f fire extinguisher in KPH Tan jung Jabung Barat ID-DISHUT PROV. JAMBI-346 278-GO-RFQ / Procurement o Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl TF / B3897 Post Limited 8,467.00 0.00 2023-03-03 2023-03-13 2023-03-27 f Drone, laptop, printer, cam and Management tions nvelope ementation era and GPS in KPH Tanjung J abung Barat ID-DISHUT PROV. JAMBI-346 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 291-GO-RFQ / Procurement o TF / B3897 Post Limited 5,333.00 0.00 2023-03-03 2023-03-13 2023-03-27 and Management tions nvelope ementation f motorcycles in KPH Tanjung Jabung Barat ID-DISHUT PROV. JAMBI-346 294-GO-RFQ / Procurement o Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl TF / B3897 Post Limited 2,899.00 0.00 2023-03-03 2023-03-13 2023-03-27 f three wheel motorcycle in K and Management tions nvelope ementation PH Tanjung Jabung Barat ID-DISHUT PROV. JAMBI-346 298-GO-RFQ / Procurement o f stake, seedling of jelutung, j Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl TF / B3897 Post Limited 29,895.00 0.00 2023-03-03 2023-03-13 2023-03-27 ack fruit, petai, areca nut, he and Management tions nvelope ementation rbicide, dolomite, organic fer tilizer in KPH Tanjung Jabung Barat ID-DISHUT PROV. JAMBI-346 447-GO-RFQ / Procurement s Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl eedling of jelutung, jack fruit, TF / B3897 Post Limited 26,944.00 0.00 2023-03-03 2023-03-13 2023-04-12 and Management tions nvelope ementation areca nut, herbicide and orga nic fertilizer in KPH Tanjung J abung Barat ID-DISHUT PROV. JAMBI-346 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 449-GO-RFQ / Procurement o TF / B3897 Post Limited 5,000.00 0.00 2023-03-03 2023-03-13 2023-04-12 and Management tions nvelope ementation f bee colony in KPH Tanjung J abung Barat ID-DISHUT PROV. JAMBI-349 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 331-GO-RFQ / Procurement s TF / B3897 Post Limited 960.00 0.00 2023-03-16 2023-03-24 2023-04-23 and Management tions nvelope ementation eedling of jack fruit, coffee, b etel nut. ID-DISHUT PROV. JAMBI-349 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 831-GO-RFQ / Procurement s TF / B3897 Post Limited 8,177.00 0.00 2023-03-17 2023-03-24 2023-04-23 and Management tions nvelope ementation eedling of Pulai and manggo ID-DISHUT PROV. JAMBI-349 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 832-GO-RFQ / Procurement s TF / B3897 Post Limited 4,713.00 0.00 2023-03-17 2023-03-24 2023-04-23 and Management tions nvelope ementation eedling of Durian, manggo ID-DISHUT PROV. JAMBI-349 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 840-GO-RFQ / Procurement o TF / B3897 Post Limited 4,528.00 0.00 2023-03-17 2023-03-24 2023-04-08 and Management tions nvelope ementation f fertilizer in Jambi Province ID-DISHUT PROV. JAMBI-349 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl TF / B3897 Post Limited 8,426.00 0.00 2023-03-17 2023-03-24 2023-04-23 846-GO-RFQ / Procurement o and Management tions nvelope ementation f seedling ID-DISHUT PROV. JAMBI-349 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 856-GO-RFQ / Procurement o TF / B3897 Post Limited 3,464.00 0.00 2023-03-17 2023-03-24 2023-04-23 and Management tions nvelope ementation f fertilizer in Jambi Province ID-DISHUT PROV. JAMBI-349 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 890-GO-RFQ / Procurement s TF / B3897 Post Limited 7,583.00 0.00 2023-03-17 2023-03-24 2023-04-23 and Management tions nvelope ementation eedling of jelutung, Blangera n ID-DISHUT PROV. JAMBI-350 192-GO-RFQ / Procurement s Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl TF / B3897 Post Limited 11,914.00 0.00 2023-03-17 2023-03-24 2023-04-23 eedling of Rambutan, Durian, and Management tions nvelope ementation Jack fruit, Aren, Coffee in KPH Bungo ID-DISHUT PROV. JAMBI-350 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 193-GO-RFQ / Procurement o TF / B3897 Post Limited 5,418.00 0.00 2023-03-17 2023-03-24 2023-04-23 and Management tions nvelope ementation f sling pump, safety glasses i n KPH Bungo ID-DISHUT PROV. JAMBI-350 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 194-GO-RFQ / Procurement o TF / B3897 Post Limited 8,176.00 0.00 2023-03-17 2023-03-23 2023-04-22 and Management tions nvelope ementation f coffee machinery ID-DISHUT PROV. JAMBI-350 196-GO-RFQ / Procurement s Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl TF / B3897 Post Limited 6,387.00 0.00 2023-03-17 2023-03-23 2023-04-22 eedling of avocado, betel nut and Management tions nvelope ementation , manggo, durian and fertilize r in KPH Bungo ID-DISHUT PROV. JAMBI-350 197-GO-RFQ / Procurement s Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl TF / B3897 Post Limited 2,526.00 0.00 2023-03-17 2023-03-23 2023-04-22 eedling of coffee, betel nut, c and Management tions nvelope ementation inamon in KPH Bungo ID-DISHUT PROV. JAMBI-350 198-GO-RFQ / Procurement s Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl TF / B3897 Post Limited 3,200.00 0.00 2023-03-17 2023-03-23 2023-04-22 eedling of betel nut, durian, j and Management tions nvelope ementation ack fruit and jengkol in KPH B ungo ID-DISHUT PROV. JAMBI-350 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 213-GO-RFQ / Procurement o TF / B3897 Post Limited 7,473.00 0.00 2023-03-17 2023-03-23 2023-04-22 and Management tions nvelope ementation f Coffee machinery in Jambi P rovince ID-DISHUT PROV. JAMBI-350 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 216-GO-RFQ / Procurement o TF / B3897 Post Limited 1,278.00 0.00 2023-03-17 2023-03-23 2023-04-22 and Management tions nvelope ementation f shoes in Jambi Province ID-DISHUT PROV. JAMBI-350 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 284-GO-RFQ / Procurement o TF / B3897 Post Limited 1,282.00 0.00 2023-03-17 2023-03-23 2023-04-06 and Management tions nvelope ementation f seedling equipment Page 3 ID-DISHUT PROV. JAMBI-353 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl TF / B3897 Post Limited 1,881.00 0.00 2023-03-31 2023-04-06 2023-05-06 647-GO-RFQ / Procurement o and Management tions nvelope ementation f shirt ID-DISHUT PROV. JAMBI-353 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 658-GO-RFQ / Procurement o TF / B3897 Post Limited 704.00 0.00 2023-03-31 2023-04-06 2023-04-09 and Management tions nvelope ementation f shirt and hat ID-DISHUT PROV. JAMBI-353 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 659-GO-RFQ / Procurement o TF / B3897 Post Limited 2,333.00 0.00 2023-03-31 2023-04-06 2023-05-06 and Management tions nvelope ementation f interior etalase in Jambi Pro vince ID-DISHUT PROV. JAMBI-354 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 421-GO-RFQ / Procurement o TF / B3897 Post Limited 388.00 0.00 2023-04-04 2023-04-11 2023-04-18 and Management tions nvelope ementation f stake for peat rehabilitation in Jambi Province ID-DISHUT PROV. JAMBI-354 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 426-GO-RFQ / Procurement o TF / B3897 Post Limited 1,294.00 0.00 2023-04-04 2023-04-11 2023-05-11 and Management tions nvelope ementation f prohibition board in KPH Ta njung Jabung Barat ID-DISHUT PROV. JAMBI-354 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 616-GO-RFQ / Procurement o TF / B3897 Post Limited 444.00 0.00 2023-04-05 2023-04-12 2023-04-26 and Management tions nvelope ementation f Training Shirt in KPH Meran gin ID-DISHUT PROV. JAMBI-354 620-GO-RFQ / Procurement o Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl TF / B3897 Post Limited 1,128.00 0.00 2023-04-05 2023-04-12 2023-05-12 f fungicide, herbicide, insecti and Management tions nvelope ementation cide, fertilizer and seedling in KPH Merangin ID-DISHUT PROV. JAMBI-354 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 930-GO-RFQ / Procurement o TF / B3897 Post Limited 695.00 0.00 2023-04-06 2023-04-13 2023-04-27 and Management tions nvelope ementation f field uniform in KPH Tanjun g Jabung Barat ID-DISHUT PROV. JAMBI-354 934-GO-RFQ / Procurement o Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl TF / B3897 Post Limited 1,397.00 0.00 2023-04-06 2023-04-13 2023-05-13 f shirt, hat for capacity buildi and Management tions nvelope ementation ng in KPH Sarolangun ID-DISHUT PROV. JAMBI-355 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 235-GO-RFQ / Procurement o TF / B3897 Post Limited 5,280.00 0.00 2023-04-10 2023-04-14 2023-05-14 and Management tions nvelope ementation f avocado seedling in KPH Sa rolangun ID-DISHUT PROV. JAMBI-355 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 237-GO-RFQ / Procurement o TF / B3897 Post Limited 7,480.00 0.00 2023-04-11 2023-04-17 2023-05-17 and Management tions nvelope ementation f Durian seedling in KPH Saro langun ID-DISHUT PROV. JAMBI-355 663-GO-RFQ / Procurement o Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl TF / B3897 Post Limited 1,017.00 0.00 2023-04-12 2023-05-14 2023-11-10 f construction material (wood and Management tions nvelope ementation , nail) in KPH Sarolangun ID-DISHUT PROV. JAMBI-355 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 825-GO-RFQ / Procurement o TF / B3897 Post Limited 512.00 0.00 2023-04-12 2023-04-18 2023-05-22 and Management tions nvelope ementation f Caps in Jambi Province ID-DISHUT PROV. JAMBI-355 826-GO-RFQ / Procurement o Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl TF / B3897 Post Limited 1,035.00 0.00 2023-04-12 2023-05-01 2023-05-17 f fertilizer for peat rehabilitati and Management tions nvelope ementation on in Jambi Province ID-DISHUT PROV. JAMBI-355 829-GO-RFQ / Procurement o Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl TF / B3897 Post Limited 2,068.00 0.00 2023-04-12 2023-05-08 2023-11-04 f seedling for peat maintenan and Management tions nvelope ementation ce in Jambi Province ID-DISHUT PROV. JAMBI-355 850-GO-RFQ / Procurement o Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl TF / B3897 Post Limited 1,207.00 0.00 2023-04-12 2023-04-18 2023-05-18 f Fertilizer for peat rehabilitat and Management tions nvelope ementation ion in Jambi Province ID-DISHUT PROV. JAMBI-355 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 860-GO-RFQ / Procurement o TF / B3897 Post Limited 3,235.00 0.00 2023-04-18 2023-05-07 2023-06-06 and Management tions nvelope ementation f fertilizer in KPH Sarolangun ID-DISHUT PROV. JAMBI-355 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 874-GO-RFQ / Procurement o TF / B3897 Post Limited 1,160.00 0.00 2023-04-12 2023-04-20 2023-05-04 and Management tions nvelope ementation f board plate, handsprayer in KPH Sarolangun ID-DISHUT PROV. JAMBI-355 Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl 878-GO-RFQ / Procurement o TF / B3897 Post Limited 865.00 0.00 2023-04-12 2023-04-18 2023-05-03 and Management tions nvelope ementation f stake in KPH Sarolangun ID-DISHUT PROV. JAMBI-355 880-GO-RFQ / Procurement s Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl TF / B3897 Post Limited 2,455.00 0.00 2023-04-12 2023-04-18 2023-05-18 eedling of durian, avocado, and Management tions nvelope ementation mango in KPH Sarolangun ID-DISHUT PROV. JAMBI-355 881-GO-RFQ / procurement o Implementing Sustainable L Request for Quota Single Stage - One E Pending Impl TF / B3897 Post Limited 2,974.00 0.00 2023-04-12 2023-04-18 2023-05-18 f herbicide, fertilizer, dolomit and Management tions nvelope ementation e in KPH Sarolangun NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DISHUT-TEBO/II/2022 / Vehic Implementing Sustainable L Request for Quota Single Stage - One E Under Imple TF / B3897 Post Limited 9,657.00 0.00 2022-01-13 2022-02-08 2022-03-10 2022-09-06 le Rent and Management tions nvelope mentation DISHUT-TANJABBAR/II/2022 / Implementing Sustainable L Request for Quota Single Stage - One E TF / B3897 Post Limited 9,698.85 8,979.40 Signed 2022-01-14 2022-02-09 2022-03-11 2022-03-07 2022-09-07 Vehicle Rent and Management tions nvelope DISHUT-SAROLANGUN/III/20 Implementing Sustainable L Request for Quota Single Stage - One E Under Imple TF / B3897 Post Limited 9,657.14 0.00 2022-01-07 2022-03-04 2022-03-04 2022-08-31 22 / Vehicle Rent and Management tions nvelope mentation CONSULTING FIRMS Page 4 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-DISHUT PROV. JAMBI-312 Implementing Sustainable L Individual Consult 722-CS-INDV / Legal spesialis TF / B3897 Post Direct - National 3,879.00 0.00 Canceled 2022-09-26 2022-09-28 2022-09-29 2022-10-01 2022-11-30 and Management ant Selection t consultant ID-DISHUT PROV. JAMBI-316 Implementing Sustainable L Individual Consult 152-CS-INDV / Procurement o TF / B3897 Post Limited 571.00 0.00 Under Review 2022-10-03 2022-09-15 2022-10-04 2022-10-05 2022-10-07 2022-10-14 and Management ant Selection f planning consultant ID-DISHUT PROV. JAMBI-316 Implementing Sustainable L Individual Consult Under Implement 153-CS-INDV / Procurement o TF / B3897 Post Limited 571.00 0.00 2022-10-24 2022-10-10 2022-10-25 2022-11-14 2022-10-26 2022-11-18 2022-10-28 2022-11-04 and Management ant Selection ation f supervisor consultant ID-DISHUT PROV. JAMBI-321 705-CS-CDS / Consultant (Fir Implementing Sustainable L Under Implement TF / B3897 Post Direct Selection Direct - National 3,879.00 0.00 2022-10-18 2022-09-28 2022-10-22 2022-10-27 2022-12-26 m) to draft a regulation for th and Management ation e Governor of the moratoriu m on peat ID-DISHUT PROV. JAMBI-346 252-CS-CDS / Consultant (fir Implementing Sustainable L Pending Impleme TF / B3897 Post Direct Selection Direct - National 1,653.00 0.00 2023-03-01 2023-03-06 2023-03-13 2023-05-12 m) to Governor Manuscrip an and Management ntation d SOP of the moratorium on peat ID-DISHUT PROV. JAMBI-354 628-CS-INDV / Procurement o Implementing Sustainable L Individual Consult Pending Impleme TF / B3897 Post Limited 171.00 0.00 2023-04-04 2023-04-05 2023-04-06 2023-04-11 2023-04-18 f consultant tower constructi and Management ant Selection ntation on planning in KPH Bungo ID-DISHUT PROV. JAMBI-354 931-CS-INDV / Procurement o Implementing Sustainable L Individual Consult Pending Impleme TF / B3897 Post Limited 171.00 0.00 2023-04-26 2023-04-27 2023-04-28 2023-05-02 2023-05-16 f supervisor consultant for to and Management ant Selection ntation wer construction in KPH Bung o Page 5 Plan de Passation des Marchés Projet de Promotion de la Compétitivité de la Chaîne des Valeurs de l’Anacarde (PPCA) FINANCEMENT SUR LE PPF I. Généralités 1. Information sur le projet: Pays : Côte d’Ivoire Emprunteur : Conseil Coton-Anacarde (CCA) Nom du Projet : Projet de Promotion de la Compétitivité de la Chaîne des Valeurs de l’Anacarde (PPCA Numéro du Crédit : Unité de Gestion du Projet : Le risque lié au projet : modéré (d’après les seuils proposés. Ce risque sera confirmé après évaluation des capacités en PM de l’unité de gestion du projet) II. Fournitures, Travaux et Services Assimilés 2.1. Seuils d’examen préalable Les marchés qui seront soumis à l'examen préalable de la Banque Nouveaux seuils de revue de la Banque élaborés en décembre 2012 et proposés au Gouvernement le 05 décembre 2012, révisés en juillet 2016 et liés au niveau de risque du projet. Nature des Méthode de Valeur seuil Contrats soumis à dépenses passation de du marché examen préalable marchés $EU de l’IDA 1. Travaux AOI ≥ 10,000,000 (y compris clés AON < 10,000,000 Tous les contrats de en main, Demande de cotation – < 200,000 15.000.000 $EU et Fourniture et au moins 3 offres plus montage Entente Directe (*) d’installations et Pas de seuil PPP) 2. Fournitures, AOI ≥ 1,000,000 Systèmes AON < 1,000,000 d’Informations Consultation de Tous les contrats de et Services Fournisseurs - Au moins < 100,000 4.000.000 $EU et plus autres que les 3 offres services de Consultation de < 500 000 Consultants Fournisseurs - Au moins 1 3 offres pour les véhicules et le carburant Entente directe (*) Pas de seuil (*) Le justificatif de toute entente directe doit être transmis avec le PPM 3. Procédures applicables aux Composantes relatives au Développement Conduit par les Communautés : N/A 4. Référence (si nécessaire) au Manuel opérationnel/de passation de marchés : 5. Autres arrangements spécifiques pour la passation de marchés : [y inclus passation anticipée de marchés et financement rétroactif, si applicables] Citer le paragraphe inscrit dans l’Accord de Financement le cas échéant) 6. Marchés et Planning et Méthode de Passation : 2 1 2 3 4 5 6 7 8 9 Méth Examen Monta ode préalable Date nt de Pré- Préféren de la prévue Estima Ref. Contract passa qualificati ce Banque pour tif Commentaires No. (Description) tion on nationale (a l’ouvert (en de (oui/non) (oui/non) priori/a ure des milliers march posterior offres $EU) és i) Acquisition de matériels informatiques (ordinateur portable, desktop, disque dur externe, imprimante, serveurs et onduleur) et A 31 Août F/01 matériels bureautiques 99 Non Non posteriori 2018 (photocopieuses, CFN scanneurs, téléphones fixes et mobiles, fax)- DOCKIN STATION pour l’UGP Acquisition de 20 motos pour renforcer le A 29 Août F/02 34 CFN Non Non dispositif de collecte posteriori 2018 des données Acquisition de véhicules pour l’UGP (3), la A 28 Août F/03 CFN Non Non DOPA(1) l’ARRE (1) et le 351 posteriori 2018 CCA(1 ) S/TOTAL FOURNITURE 484 Montant total prévisionnel : 484 $US 3 3. Marchés de Services Assimilés 1 2 3 4 5 6 7 8 9 Examen Montan Pré- Préféren préalable Date t Méthode Ref quali ce de la prévue Estimat de . Contract ficati national Banque pour Commentaires if passation No. (Description) on e (a l’ouvertur (en de (oui/ (oui/non priori/a e des milliers marchés non) ) posteriori offres $EU) ) Veuillez fournir le Contrat de Entente justificatif de location des directe A l’entente directe S/1 locaux de 53 Non Non Mai 2018 Avec SCI Posteriori comme demandé l'UGP pour 7 JAFI dé par la Banque mois Assurance des 5 CFN A 16 Août S/2 véhicules et 34 Non Non posteriori 2018 des 20 motos Fourniture de carburant CFN A 16 Août S/3 pour les 13 Non Non posteriori 2018 activités (5) véhicules TOTAL 100 MARCHES DE 4 SERVICES ASSIMILES Montant total prévisionnel : 100 $US 5 III. Sélection de Consultants 3.1. Seuil d’examen préalable Les marchés qui seront soumis à l'examen préalable de la banque conformément aux Nouveaux seuils de revue de la Banque élaborés en décembre 2012 et proposés au Gouvernement le 05 décembre 2012, révisés en juillet 2016 et liés au niveau de risque du projet. : Nature de Méthode de passation Valeur Contrats soumis à dépenses de marchés seuil du examen préalable contrat $EU Consultan SFQC1, SFQ2, SMC3, ≥ 300.000 ts SCBD4, Tout contrat de 2.000.000 Firmes SFQC, SFQ, SMC, SCBD, < 300.000 $EU ou plus QC5 Pas de Entente directe (*) seuil Consultan Consultant individuel (AMI) ≥ 100.000 ts Consultant individuel (3 Tout contrat de 400.000 $ Individuel < 100.000 CV) EU ou plus s Pas de Entente directe (*) seuil Tous les TDRs, quelle que soit la valeur du contrat, sont soumis à examen préalable. (*) Le justificatif de toute sélection par entente directe doit être transmis avec le PPM 2. Liste restreinte composée entièrement de Consultants Nationaux : La liste restreinte de Consultants pour les services, d'un coût estimatif inférieur à 300 0000 $ US ou équivalent par contrat, peut être entièrement composée de Consultants nationaux conformément aux dispositions du paragraphe 7.25 du Règlement de Passation de Marchés dans le Cadre du Financement de Projets d’Investissement (FPI) pour Fournitures, Travaux, Services Autres que des Services de Consultants et Services de Consultants – Juillet 2016. 1 SFQC : Sélection Fondée sur la Qualité et le Coût 2 SFQ : Sélection fondée sur la qualité 3 SMC : Sélection au moindre coût 4 SCBD : Sélection dans le cadre d’un budget déterminé 5 QC : Sélection basée sur les Qualifications des Consultants CI : Consultant Individuel : AMI : Avis à Manifestation d’Intérêt 6 3. Autres arrangements spécifiques pour la sélection : [y compris passation anticipée de marchés et financement rétroactif, si applicables] 7 4. Contrats de Consultants avec Méthode de Sélection et Planning 1 2 3 4 5 6 7 Examen Ref Montant Méthod Date prévue préalable de . Description du contrat estimatif e de pour la la Banque Commentaires No. (en sélectio soumission des (a priori / a milliers n propositions posteriori) $EU) Sélection du C/1 cabinet en cours Recrutement d’un consultant pour la L ANO de la réalisation des études Banque sur les environnementale et sociale 250 QC A posteriori 17 Avril 2018 TDR a été stratégique (EESS) de la zone agro obtenu/ Ce industrielle de KORHOGO marché figurait dans la version initiale du PPM Sélection du C/2 cabinet en cours Recrutement d’un consultant pour la L ANO de la réalisation de l’étude Banque sur les environnementale et sociale 250 QC A postériori 05 Juin 2018 TDR a été stratégique (EESS) de la zone agro obtenu/ Ce industrielle BOUAKE marché figurait dans la version initiale du PPM Sélection du Recrutement d’un consultant pour la C/3 cabinet en cours réalisation de études environnementale et sociale 250 QC A postériori 07 Mai 2018 L ANO de la stratégique (EESS) de la zone agro Banque sur les industrielle de BONDOUKOU TDR a été 8 1 2 3 4 5 6 7 Examen Ref Montant Méthod Date prévue préalable de . Description du contrat estimatif e de pour la la Banque Commentaires No. (en sélectio soumission des (a priori / a milliers n propositions posteriori) $EU) obtenu/ Ce marché figurait dans la version initiale du PPM Sélection du C/4 cabinet en cours Recrutement de consultants pour la L ANO de la réalisation de l’ études Banque sur les environnementale et sociale 250 QC A postériori 07 Avril 2018 TDR a été stratégique (EESS) de la zone agro obtenu/ Ce industrielle de SEGUELA marché figurait dans la version initiale du PPM C/ Recrutement d’un consultant 5 individuel pour le constat d’impact environnemental et social ( CIES) de AMI en cours 100 CI A Postériori 1er Juin 2018 travaux de 184 km de routes rurales dans les régions du GBEKE, HAMBOL et GONTOUGOU C/6 Recrutement d’un consultant AMI en cours individuel pour l’étude d’impact 50 CI A Postériori 1er Juin 2018 environnemental et social (EIES) de 18 km dans les régions du HAMBOL Selon le nouveau Recrutement d’un consultant pour cadre de passation l’actualisation de la structure des prix C/7 50 QC A Posteriori 11 Juin 2018 des marchés de la de la commercialisation de la noix Banque Mondiale, brute de cajou en Côte d’Ivoire en sa section VII, le 9 1 2 3 4 5 6 7 Examen Ref Montant Méthod Date prévue préalable de . Description du contrat estimatif e de pour la la Banque Commentaires No. (en sélectio soumission des (a priori / a milliers n propositions posteriori) $EU) point 7.11, la publication d’ un avis à manifestations d’intérêt n’est pas obligatoire C/8 ED avec 31 Juillet 2018 Justificatif en Recrutement d’un coordonnateur M 21 A priori annexe adjoint chargé de l’industrie KARIM Contrat pour 3 BERTHE mois TOTAL/CONSULTANT 1221 Montant prévisionnel des consultants : 1221 $US TOTAL PREVISIONNEL GENERAL : 1 805 000 $US 10 PROCUREMENT Cote d'Ivoire : Cashew Value Chain Competitiveness Project PLAN General Information Country: Cote d'Ivoire 2022-09-05 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P158810 GPN Date: Project Name: Cashew Value Chain Competitiveness Project Loan / Credit No: IBRD / 88450 Cashew Cotton Council Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CI-CCA-314836-CW-RFB / Tr avaux d'aménagement, d’éle Request for Bids - 3. Support to private invest ctrification du site et de cons Single Stage - One E Works (without pr Pending Imp 2023-07-2 IBRD / 88450 ment in post-harvest and pr Post Request for Bids Open - National 4,958,780.00 0.00 2022-10-03 2022-10-08 2022-11-19 2022-12-19 2023-01-23 truction des bâtiments du Ce nvelope equalification) SP lementation 2 ocessing infrastructure ntre de Valorisation des Coqu D es (CVC) à la zone industriell e de Yamoussoukro CI-CCA-314885-CW-RFB / Tr Request for Bids - avaux d'aménagement, d’éle 3. Support to private invest Single Stage - One E Works (without pr Pending Imp 2023-07-2 ctrification du site et de cons IBRD / 88450 ment in post-harvest and pr Post Request for Bids Open - National 5,540,140.00 0.00 2022-10-03 2022-10-08 2022-11-19 2022-12-19 2023-01-23 nvelope equalification) SP lementation 2 truction des bâtiments du HU ocessing infrastructure D B à la zone industrielle de Ya moussoukro National Procure CI-PPCA-315069-CW-RFQ / T 2. Productivity enhancement ment Document - RAVAUX DE FORAGE ET D'EQ Request for Quota Single Stage - One E Pending Imp 2023-05-2 IBRD / 88450 and improved access to mar Post Limited 1 Envelope proce 199,000.00 0.00 2022-10-05 2022-11-30 UIPEMENTS POUR L'ADDUCTI tions nvelope lementation 9 kets ss (Non Bank-SPD ON D'EAU DES TROIS CDC PR ) IORISES CI-CCA-314867-GO-RFB / Fo urniture et installation d'une Request for Bids - 3. Support to private invest unité de traitement de coque Single Stage - One E Works (without pr Pending Imp 2023-08-2 IBRD / 88450 ment in post-harvest and pr Post Request for Bids Open - National 3,700,000.00 0.00 2022-11-02 2022-11-07 2022-12-19 2023-01-18 2023-02-22 s avec un système de sécurit nvelope equalification) SP lementation 1 ocessing infrastructure é incendie intégré du Centre D de Valorisation des Coques ( CVC) Request for Bids - CI-CCA-314906-GO-RFB / Fo 3. Support to private invest Single Stage - One E Works (without pr Under Imple 2023-09-0 urniture et pose de charpent IBRD / 88450 ment in post-harvest and pr Post Request for Bids Open - National 2,719,000.00 0.00 2022-11-14 2023-03-23 2022-11-19 2023-03-28 2022-12-31 2023-01-30 2023-03-06 nvelope equalification) SP mentation 2 es métalliques du HUB Logist ocessing infrastructure D ique CI-CCA-320424-CW-RFB / Fo Request for Bids - 3. Support to private invest urniture et pose de charpent Single Stage - One E Works (without pr Under Imple 2023-08-2 IBRD / 88450 ment in post-harvest and pr Post Request for Bids Open - National 1,500,000.00 0.00 2022-11-04 2023-03-22 2022-11-09 2023-03-28 2022-12-21 2023-01-20 2023-02-24 es métalliques du Centre de nvelope equalification) SP mentation 3 ocessing infrastructure Valorisation des Coques (CVC D ) CI-CCA-341097-CW-RFB / Tr Request for Bids - avaux de réhabilitation par R 2. Productivity enhancement Single Stage - One E Works (without pr Pending Imp 2023-12-0 C et RLTPC d’environ 217,55 IBRD / 88450 and improved access to mar Post Request for Bids Open - National 7,449,000.00 0.00 2023-02-20 2023-02-25 2023-04-08 2023-05-08 2023-06-12 nvelope equalification) SP lementation 9 km de routes rurales dans le kets D s Régions du BERE, du HAMB OL et du BAFING CI-CCA-341104-CW-RFB / Tr Request for Bids - avaux d'entretien par RLEP d 2. Productivity enhancement Single Stage - One E Works (without pr Pending Imp 2024-02-1 ’environ 298 km de routes ru IBRD / 88450 and improved access to mar Post Request for Bids Open - National 278,000.00 0.00 2023-05-02 2023-05-07 2023-06-18 2023-07-18 2023-08-22 nvelope equalification) SP lementation 8 rales dans les Régions du GB kets D EKE, du HAMBOL et du GONT OUGO (3ème passe) Request for Quota CI-CCA-357795-CW-RFQ / Co 3. Support to private invest Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-03-0 nstruction d'une plate forme IBRD / 88450 ment in post-harvest and pr Post Limited 55,000.00 0.00 2023-07-11 2023-09-05 tions nvelope s (Emergency) SP lementation 3 de carbonisation.au CITA ocessing infrastructure D -Competitive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-CCA-314840-GO-RFB / Fo 3. Support to private invest Single Stage - One E Pending Impl urniture et installation de de IBRD / 88450 ment in post-harvest and pr Post Request for Bids Open - National 250,000.00 0.00 2022-10-04 2022-10-09 2022-11-20 2022-12-20 2023-01-24 2023-07-23 nvelope ementation ux groupes électrogène ocessing infrastructure CI-CCA-314854-GO-RFB / Fo urniture et installation du rés 3. Support to private invest Single Stage - One E Pending Impl eau électrique pour le raccor IBRD / 88450 ment in post-harvest and pr Post Request for Bids Open - National 839,248.00 0.00 2022-10-03 2022-10-08 2022-11-19 2022-12-19 2023-01-23 2023-07-22 nvelope ementation dement des équipements du ocessing infrastructure process du Centre de Caloris ation des Coques (CVC) CI-CCA-314859-GO-RFB / Fo 3. Support to private invest Single Stage - One E Pending Impl urniture et installation de de IBRD / 88450 ment in post-harvest and pr Post Request for Bids Open - National 200,000.00 0.00 2022-10-10 2022-10-15 2022-11-26 2022-12-26 2023-01-30 2023-07-29 nvelope ementation ux postes de pesage ocessing infrastructure CI-CCA-314863-GO-RFQ / Ins tallation d'un système de vid 3. Support to private invest Request for Quota Single Stage - One E Pending Impl éosurveillance des équipeme IBRD / 88450 ment in post-harvest and pr Post Limited 80,000.00 0.00 2022-11-19 2023-01-14 2023-07-13 tions nvelope ementation nts du process du Centre de ocessing infrastructure valorisation des Coques (CVC ) CI-CCA-314864-GO-RFQ / Fo 3. Support to private invest urniture d'engins et de matér Request for Quota Single Stage - One E Pending Impl IBRD / 88450 ment in post-harvest and pr Post Limited 450,000.00 0.00 2022-12-10 2023-02-04 2023-08-03 iels roulants pour le Centre d tions nvelope ementation ocessing infrastructure e Valorisation des Coques CI-CCA-314865-CS-CQS / Fo 3. Support to private invest urniture et pose de charpent Open - Internationa Single Stage - One E IBRD / 88450 ment in post-harvest and pr Post Request for Bids 1,500,000.00 0.00 Canceled 2022-10-06 2022-10-11 2022-11-22 2022-12-22 2023-01-26 2023-07-25 es métalliques du Centre de l nvelope ocessing infrastructure Valorisation des Coques (CVC ) CI-CCA-314887-GO-RFQ / Ins 3. Support to private invest Request for Quota Single Stage - One E Pending Impl tallation d'un système de vid IBRD / 88450 ment in post-harvest and pr Post Limited 92,000.00 0.00 2022-11-06 2023-01-01 2023-06-30 tions nvelope ementation éosurveillance du HUB ocessing infrastructure CI-CCA-314903-GO-RFB / Fo 3. Support to private invest Single Stage - One E Pending Impl urniture et installation d'un s IBRD / 88450 ment in post-harvest and pr Post Request for Bids Open - National 165,000.00 0.00 2022-11-03 2022-11-08 2022-12-20 2023-01-19 2023-02-23 2023-08-22 nvelope ementation ystème de sécurité incendie ocessing infrastructure pour le HUB Page 1 CI-PPCA-315077-GO-RFQ / A 4. Program coordination, mo cquisition de consommables Request for Quota Single Stage - One E Pending Impl IBRD / 88450 nitoring and knowledge man Post Limited 56,000.00 0.00 2022-10-16 2022-12-11 2023-06-09 et fournitures informatiques tions nvelope ementation agement pour le compte du PPCA CI-CCA-344525-GO-RFB / Fo urniture et installation d'une 3. Support to private invest unité de traitement de coque Open - Internationa Single Stage - One E Under Imple IBRD / 88450 ment in post-harvest and pr Prior Request for Bids 3,700,000.00 0.00 2023-03-08 2023-03-20 2023-03-13 2023-05-02 2023-04-24 2023-05-03 2023-05-24 2023-06-25 2023-06-28 2023-12-25 s avec un système de sécurit l nvelope mentation ocessing infrastructure é incendie intégré du Centre de Valorisation des Coques ( CVC) CI-CCA-344547-GO-RFQ / Ac 4. Program coordination, mo Request for Quota Single Stage - One E Pending Impl quisition logiciels statistiques IBRD / 88450 nitoring and knowledge man Post Limited 19,400.00 0.00 2023-04-17 2023-06-12 2023-12-09 tions nvelope ementation ( SPSS , STATA) agement CI-CCA-344553-GO-RFQ / Ac quisition et aménagement d' 1. Institutional strengthenin un conteneur pour le site de Request for Quota Single Stage - One E Pending Impl IBRD / 88450 g and value chain governanc Post Limited 98,360.00 0.00 2023-04-17 2023-06-12 2023-12-09 secours du Centre de donnée tions nvelope ementation e s à Abidjan (conteneur, froid, BTP, électricité, courant faibl e, courant fort) CI-CCA-344555-GO-RFQ / Ac quisition et aménagement d' 1. Institutional strengthenin Request for Quota Single Stage - One E Pending Impl un conteneur pour le site pri IBRD / 88450 g and value chain governanc Post Limited 98,360.00 0.00 2023-03-15 2023-05-10 2023-11-06 tions nvelope ementation ncipal à Yamoussoukro (cont e eneur, froid, BTP, électricité, courant faible, courant fort) CI-CCA-344798-GO-RFB / Int 1. Institutional strengthenin erconnexion des sites du Con Single Stage - One E Pending Impl IBRD / 88450 g and value chain governanc Post Request for Bids Open - National 166,000.00 0.00 2023-04-27 2023-05-02 2023-06-13 2023-07-13 2023-08-17 2024-02-13 seil du Coton et de l’Anacard nvelope ementation e e et fourniture d'internet CI-CCA-344802-GO-RFQ / Ac quisition de terminaux pour l 1. Institutional strengthenin Request for Quota Single Stage - One E Pending Impl es Agents de terrain du Cons IBRD / 88450 g and value chain governanc Post Limited 70,100.00 0.00 2023-03-19 2023-05-14 2023-11-10 tions nvelope ementation eil du Coton et de l'Anacarde e dédiées à la collecte de donn ées CI-CCA-344804-GO-RFQ / Ac 1. Institutional strengthenin Request for Quota Single Stage - One E Pending Impl quérir le mobilier de bureau IBRD / 88450 g and value chain governanc Post Limited 70,100.00 0.00 2023-06-04 2023-07-30 2024-01-26 tions nvelope ementation pour les 2 DR CCA de Bouaké e et Korhogo CI-CCA-344817-GO-RFQ / ac 1. Institutional strengthenin quisition d'équipements infor Request for Quota Single Stage - One E Pending Impl IBRD / 88450 g and value chain governanc Post Limited 35,000.00 0.00 2023-04-05 2023-05-31 2023-11-27 matique et bureautique pour tions nvelope ementation e la fédération des OPCA et le personnel de PPCA CI-CCA-344824-GO-RFQ / Ac quérir les équipements audio 1. Institutional strengthenin Request for Quota Single Stage - One E Pending Impl visuels pour la salle de confé IBRD / 88450 g and value chain governanc Post Limited 97,400.00 0.00 2023-05-28 2023-07-23 2024-01-19 tions nvelope ementation rence (cabine de traduction, e écouteurs, caméra, audiovisu el…) pour le CITA CI-CCA-344826-GO-RFB / Ac quisition d’équipement pour l 1. Institutional strengthenin Single Stage - One E Pending Impl a mise à niveau technologiqu IBRD / 88450 g and value chain governanc Post Request for Bids Open - National 175,400.00 0.00 2023-08-21 2023-08-26 2023-10-07 2023-11-06 2023-12-11 2024-06-08 nvelope ementation e du CITA ( nouveaux équipe e ments: Dicing machine, gradi ng machine, marqueur... ) CI-CCA-344828-GO-RFQ / Fo 1. Institutional strengthenin Request for Quota Single Stage - One E Pending Impl urniture et installation d'une IBRD / 88450 g and value chain governanc Post Limited 39,000.00 0.00 2023-10-15 2023-12-10 2024-06-07 tions nvelope ementation unité de traitement des efflu e ents CI-CCA-344839-GO-RFB / Ac 2. Productivity enhancement Single Stage - One E Pending Impl quérir les équipements techn IBRD / 88450 and improved access to mar Post Request for Bids Open - National 139,600.00 0.00 2023-07-20 2023-07-25 2023-09-05 2023-10-05 2023-11-09 2024-05-07 nvelope ementation iques des CDC kets CI-CCA-344852-GO-RFQ / Ac 4. Program coordination, mo Request for Quota Single Stage - One E Pending Impl IBRD / 88450 Post Limited 48,700.00 0.00 2023-03-25 2023-05-20 2023-11-16 hats de carburant nitoring and knowledge man tions nvelope ementation agement CI-CCA-344867-GO-RFQ / Fo 4. Program coordination, mo Request for Quota Single Stage - One E Pending Impl IBRD / 88450 Post Limited 29,200.00 0.00 2023-04-18 2023-06-13 2023-12-10 urniture de consommable inf nitoring and knowledge man tions nvelope ementation ormatiques agement CI-CCA-344859-GO-RFQ / Ac 4. Program coordination, mo Request for Quota Single Stage - One E Pending Impl hat de Fournitures de bureau IBRD / 88450 nitoring and knowledge man Post Limited 58,400.00 0.00 2023-05-21 2023-07-16 2024-01-12 tions nvelope ementation pour le compte de l’UCP (Ann agement ée 2023) CI-CCA-344833-GO-RFQ / Ac quérir huit (08) véhicules (cin 2. Productivity enhancement Request for Quota Single Stage - One E Pending Impl q véhicules pick up, deux vé IBRD / 88450 and improved access to mar Post Limited 460,000.00 0.00 2023-05-15 2023-07-10 2024-01-06 tions nvelope ementation hicules 4X4 et un véhicule be kets rline) pour les CDC et PPCA CI-PPCA-225054-GO-RFQ / A cquérir des matériels techniq 4. Program coordination, mo ues pour la gestion des mesu Request for Quota Single Stage - One E IBRD / 88450 nitoring and knowledge man Post Limited 8,000.00 0.00 Canceled 2021-07-10 2021-09-04 2022-03-03 res de sauvegarde environne tions nvelope agement mentale (appareils GPS, app areils photo et sonomètres) CI-PPCA-225581-GO-RFQ / A 1. Institutional strengthenin Request for Quota Single Stage - One E IBRD / 88450 Post Limited 3,000.00 0.00 Canceled 2021-06-05 2021-07-31 2022-01-27 cquérir un sonomètre g and value chain governanc tions nvelope e CI-CCA-356602-GO-RFQ / Fo 2. Productivity enhancement Request for Quota Single Stage - One E Pending Impl urniture de plants forestier d IBRD / 88450 and improved access to mar Post Limited 82,000.00 0.00 2023-06-04 2023-07-30 2024-01-26 tions nvelope ementation ans le cadre du reboisement kets compensatoire CI-CCA-356727-GO-RFQ / Ac quisition de divers support d 4. Program coordination, mo Request for Quota Single Stage - One E Pending Impl communication pour les activ IBRD / 88450 nitoring and knowledge man Post Limited 24,500.00 0.00 2023-06-18 2023-08-13 2024-02-09 tions nvelope ementation ités 2023 du PPCA (gadgets, agement tee shirt, polo, casquette, etc ..) CI-FIRCA-202091-GO-RFQ / S 4. Program coordination, mo élection d'une entreprise pou Request for Quota Single Stage - One E IBRD / 88450 nitoring and knowledge man Post Limited 65,000.00 0.00 Canceled 2021-01-04 2021-03-01 2021-08-28 r la production de supports d tions nvelope agement e sensibilisation (MGP, PGP, S CP) NON CONSULTING SERVICES Page 2 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-CCA-344876-NC-RFQ / Re cruter un prestataire agréé p 2. Productivity enhancement our la récupération et l'élimin Request for Quota Single Stage - One E Pending Impl IBRD / 88450 and improved access to mar Post Limited 93,110.00 0.00 2023-09-19 2023-11-14 2024-05-12 ation des pesticides périmés tions nvelope ementation kets et les emballages vides de p esticides détenus par les pép iniéristes CI-CCA-344869-GO-RFQ / Pro duction, actualisation des su 4. Program coordination, mo Request for Quota Single Stage - One E Pending Impl pports de communication ins IBRD / 88450 nitoring and knowledge man Post Limited 48,700.00 0.00 2023-07-03 2023-08-28 2024-02-24 tions nvelope ementation titutionnelle sur les résultats agement du projet (plaquettes, kakem onos, Note book, etc.) CI-CCA-344893-NC-RFQ / Ent 4. Program coordination, mo ent directe avec AGOSOFT p Pending Impl IBRD / 88450 nitoring and knowledge man Post Direct Selection Direct - National 11,700.00 0.00 2023-06-30 2023-07-05 2023-08-09 2024-02-05 our l'assistance pour le logici ementation agement el comptable TOM1PRO CI-CCA-356742-NC-RFQ / Sél 4. Program coordination, mo ection d'un prestataire pour l' Request for Quota Single Stage - One E Pending Impl IBRD / 88450 nitoring and knowledge man Post Limited 80,300.00 0.00 2023-06-26 2023-08-21 2024-02-17 organisation des événements tions nvelope ementation agement du PPCA (inauguration, lance ment, etc...) CI-CCA-356748-NC-RFQ / Sél ection d'un prestataire pour l' 3. Support to private invest Single Stage - One E Pending Impl organisation des activités de IBRD / 88450 ment in post-harvest and pr Post Request for Bids Open - National 250,000.00 0.00 2023-05-30 2023-06-04 2023-07-16 2023-08-15 2023-09-19 2024-03-17 nvelope ementation promotion de la consommati ocessing infrastructure on locale des produits de l'an acarde CI-CCA-356758-NC-RFB / Sél ection d'un prestataire pour l 3. Support to private invest Single Stage - One E Pending Impl ’organisation de la participati IBRD / 88450 ment in post-harvest and pr Post Request for Bids Open - National 328,000.00 0.00 2023-06-20 2023-06-25 2023-08-06 2023-09-05 2023-10-10 2024-04-07 nvelope ementation on du PPCA aux salons nation ocessing infrastructure aux et internationaux (SARA, SIETTA, WCC, etc...) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-PPCA-287614-CS-CQS / R 3. Support to private invest Consultant Qualifi ecruter un Consultant en vue IBRD / 88450 ment in post-harvest and pr Post Open - National 90,000.00 0.00 Canceled 2022-06-30 2022-07-21 2022-09-03 2022-10-03 2022-11-07 2023-05-06 cation Selection d’assurer le contrôle des trav ocessing infrastructure aux du CVC CI-PPCA-224296-CS-CQS / R ecruter un consultant pour ré 3. Support to private invest Consultant Qualifi aliser une mission de contrôl IBRD / 88450 ment in post-harvest and pr Post Open - National 71,000.00 0.00 Canceled 2021-08-10 2021-08-31 2021-10-14 2021-11-13 2021-12-18 2022-06-16 cation Selection e pour contrôler les travaux ocessing infrastructure de construction d'infrastructu res relatives au HUB pilote CI-CCA-314869-CS-CQS / Re crutement d'un cabinet pour la mission de contrôle de con 3. Support to private invest formité et de normalisation d Consultant Qualifi Under Implement IBRD / 88450 ment in post-harvest and pr Post Open - National 200,000.00 0.00 2022-12-05 2022-12-19 2022-12-26 2023-02-08 2023-03-10 2023-04-14 2023-10-11 es risques des travaux de co cation Selection ation ocessing infrastructure nstruction d'un Centre de Val orisation des Coques (CVC) e t d'un HUB logistique à la Zo ne Industrielle de Yamoussou kro CI-CCA-341088-CS-CQS / Fai re le contrôle de l’exécution 2. Productivity enhancement des travaux d'entretien par R Consultant Qualifi Under Implement IBRD / 88450 and improved access to mar Post Open - National 94,000.00 0.00 2023-02-13 2023-03-08 2023-03-06 2023-04-19 2023-05-19 2023-06-23 2023-09-21 LEP de 465 km de routes rur cation Selection ation kets ales (Régions du GBEKE, HA MBOL et du Gontougo) 2ème passe CI-CCA-341098-CS-CQS / Co ntrôle technique, environne mental et social de l’exécutio 2. Productivity enhancement n des travaux de réhabilitatio Consultant Qualifi Under Implement IBRD / 88450 and improved access to mar Post Open - National 280,000.00 0.00 2023-02-16 2023-02-20 2023-03-09 2023-04-22 2023-05-22 2023-06-26 2023-12-23 n et construction de 217,55 k cation Selection ation kets m de routes rurales dans les Régions du BERE, du HAMBO L et du BAFING (Mission B1: Région du Béré et du Bafing) CI-CCA-341102-CS-CQS / Co ntrôle technique, environne mental et social de l’exécutio 2. Productivity enhancement n des travaux de réhabilitatio Consultant Qualifi Under Implement IBRD / 88450 and improved access to mar Post Open - National 280,000.00 0.00 2023-02-16 2023-02-20 2023-03-09 2023-04-22 2023-05-22 2023-06-26 2023-12-23 n et construction de 217,55 k cation Selection ation kets m de routes rurales dans les Régions du BERE, du HAMBO L et du BAFING (Mission B2: Région du Béré et du Hambol ) CI-CCA-341105-CS-CQS / Co ntrôle de l’exécution des trav 2. Productivity enhancement Consultant Qualifi Pending Impleme aux d'entretien par RLEP de IBRD / 88450 and improved access to mar Post Open - National 75,000.00 0.00 2023-04-17 2023-05-08 2023-06-21 2023-07-21 2023-08-25 2024-02-21 cation Selection ntation 298 km de routes rurales dan kets s les Régions du GBEKE, HAM BOL et du Gontougo CI-CCA-344406-CS-CQS / Re cruter un cabinet pour réalis 1. Institutional strengthenin Consultant Qualifi Pending Impleme er l'étude de satisfaction des IBRD / 88450 g and value chain governanc Post Open - National 44,016.00 0.00 2023-03-21 2023-04-11 2023-05-25 2023-06-24 2023-07-29 2024-01-25 cation Selection ntation acteurs sur les mesures prise e s par le Gouvernement CI-CCA-344412-CS-CQS / rec 1. Institutional strengthenin Consultant Qualifi Pending Impleme rutement d'une Firme pour d IBRD / 88450 g and value chain governanc Post Open - National 65,573.00 0.00 2023-03-20 2023-04-10 2023-05-24 2023-06-23 2023-07-28 2024-01-24 cation Selection ntation éfinir une stratégie SRE e CI-CCA-344422-CS-CQS / Re 1. Institutional strengthenin cruter un cabinet pour réalis Consultant Qualifi Pending Impleme IBRD / 88450 g and value chain governanc Post Open - National 49,180.00 0.00 2023-05-23 2023-06-13 2023-07-27 2023-08-26 2023-09-30 2024-03-28 er les études techniques des cation Selection ntation e nouvelles infrastructures du CITA Page 3 CI-CCA-344489-CS-CQS / Re crutement d'un consultant-fir 2. Productivity enhancement Consultant Qualifi Pending Impleme me pour Réaliser l'évaluation IBRD / 88450 and improved access to mar Post Open - National 100,600.00 0.00 2023-03-27 2023-04-17 2023-05-31 2023-06-30 2023-08-04 2024-01-31 cation Selection ntation externe des activités du Prog kets ramme National de Recherch e sur l'Anacarde (PNRA CI-CCA-344527-CS-CQS / Re 2. Productivity enhancement Consultant Qualifi Pending Impleme cruter un Cabinet pour l'éval IBRD / 88450 and improved access to mar Post Open - National 99,200.00 0.00 2023-04-21 2023-05-12 2023-06-25 2023-07-25 2023-08-29 2024-02-25 cation Selection ntation uation externe du Conseil Ag kets ricole CI-CCA-344420-CS-CQS / Re cruter un cabinet pour faire l a mise aux normes des infras tructures du CITA suite aux a 1. Institutional strengthenin Consultant Qualifi udits techniques et environn IBRD / 88450 g and value chain governanc Post Open - National 163,934.00 0.00 Canceled 2023-04-03 2023-04-24 2023-06-07 2023-07-07 2023-08-11 2024-02-07 cation Selection ementales (PGE Audit, Etude e s de danger et plan d'opérati on interne, mise en œuvre d es recommandations de l'étu de et acquisitions des équip CI-CCA-357797-CS-CQS / Sél ection d’un cabinet/consultan t pour l’étude des modalités 3. Support to private invest Consultant Qualifi Pending Impleme et dispositifs de mise en plac IBRD / 88450 ment in post-harvest and pr Post Limited 30,000.00 0.00 2023-08-03 2023-08-17 2023-09-16 2023-10-21 2024-04-18 cation Selection ntation e d'une unité d'assemblage a ocessing infrastructure u sein de Centre d'Innovation et des Technologies de l'Ana carde (CITA) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-PPCA-308960-CS-CDS / C ONVENTION avec ANADER po 2. Productivity enhancement Under Implement ur la mise en œuvre des Tes IBRD / 88450 and improved access to mar Post Direct Selection Direct - National 460,000.00 0.00 2022-08-31 2022-09-08 2022-09-10 2022-11-14 2023-05-13 ation ts de démonstration des perf kets ormances des fertilisants biol ogiques sur l'anacardier" CI-PPCA-315073-CS-CDS / Sé lection directe entre le Projet de Promotion de la Compétiti vité de la Chaîne de Valeur d 2. Productivity enhancement Pending Impleme e l’Anacarde (PPCA) et M. NA IBRD / 88450 and improved access to mar Post Direct Selection Direct - National 38,000.00 0.00 2022-09-30 2022-10-10 2022-12-14 2023-06-12 ntation YO Ankouvi Mawoudoudji pou kets r une assistance à la mise en place d’un dispositif permane nt de collecte et d’archivage des données. CI-CCA-338582-CS-INDV / Re crutement d'un consultant in dividuel pour la préparations de la composante relative à 3. Support to private invest Individual Consult Under Implement la transformation des noix de IBRD / 88450 ment in post-harvest and pr Post Open - National 74,500.00 0.00 2023-02-14 2023-02-20 2023-03-23 2023-04-22 2023-05-27 2023-08-25 ant Selection ation pomme de cajou de la deuxiè ocessing infrastructure me phase du Projet de Promo tion de la Compétitivité de la Chaine de valeur de l'Anacar de (PPCA) CI-CCA-344455-CS-INDV / Re cruter un consultant individu 1. Institutional strengthenin el pour réaliser une étude po Individual Consult Pending Impleme IBRD / 88450 g and value chain governanc Post Limited 8,196.00 0.00 2023-05-19 2023-05-24 2023-06-14 2023-07-19 2024-01-15 ur déterminer un traitement ant Selection ntation e adéquat des effluents du CIT A (eau de cuisson chargée en CNSL) avant rejet CI-CCA-344501-CS-CDS / Co 2. Productivity enhancement nvention avec l'ANADER pour IBRD / 88450 and improved access to mar Prior Direct Selection Direct - National 2,141,500.00 0.00 Under Review 2023-03-22 2023-04-06 2023-04-01 2023-06-05 2023-12-02 le soutien du Conseil agricole kets CI-CCA-344505-CS-CDS / Co nvention avec le CNRA pour l a vulgarisation de la culture i 2. Productivity enhancement Pending Impleme ntercalaire de soja dans les p IBRD / 88450 and improved access to mar Post Direct Selection Direct - National 372,400.00 0.00 2023-03-31 2023-04-10 2023-06-14 2023-12-11 ntation arcelles de producteurs (ach kets at de semences, prestations d'appui technique à l'activité, etc.) CI-CCA-344518-CS-INDV / Re 2. Productivity enhancement cruter un consultant individu Individual Consult Open - Internationa Pending Impleme IBRD / 88450 and improved access to mar Post 223,500.00 0.00 2023-05-17 2023-07-05 2023-07-26 2023-08-30 2024-02-26 el pour la formation des acte ant Selection l ntation kets urs sur les innovations CI-CCA-344530-CS-CDS / Co nvention avec la SODEXAM p 2. Productivity enhancement Under Implement ortant sur l'appui à l'exécutio IBRD / 88450 and improved access to mar Post Direct Selection Direct - National 149,000.00 0.00 2023-04-12 2023-04-22 2023-04-22 2023-06-26 2023-12-23 ation n des activités de résilience kets des producteurs au changem ent climatique CI-CCA-344539-CS-INDV / Re cruter un consultant pour l'ét 3. Support to private invest ude technique de la construc Individual Consult Open - Internationa Pending Impleme IBRD / 88450 ment in post-harvest and pr Post 195,000.00 0.00 2023-04-27 2023-06-15 2023-07-06 2023-08-10 2024-02-06 tion du Laboratoire Central d ant Selection l ntation ocessing infrastructure u Centre d’Innovations et des Technologies de l’Anacarde CI-CCA-344541-CS-INDV / Ré 4. Program coordination, mo Individual Consult Pending Impleme IBRD / 88450 Post Limited 97,400.00 0.00 2023-04-25 2023-04-30 2023-05-21 2023-06-25 2023-12-22 aliser les études socioécono nitoring and knowledge man ant Selection ntation miques agement CI-CCA-344542-CS-INDV / Re 4. Program coordination, mo crutement d'un Consultant M Individual Consult Under Implement IBRD / 88450 nitoring and knowledge man Post Limited 19,200.00 0.00 2023-04-06 2023-03-21 2023-04-11 2023-05-02 2023-06-06 2023-12-03 edia Planner pour la campag ant Selection ation agement ne de Communication sur les résultats CI-CCA-344544-CS-INDV / Re 4. Program coordination, mo crutement d'un Consultant Vi Individual Consult Pending Impleme IBRD / 88450 nitoring and knowledge man Post Limited 9,740.00 0.00 2023-05-15 2023-05-20 2023-06-10 2023-07-15 2024-01-11 déaste/infographe pour la ca ant Selection ntation agement mpagne de Communication s ur les résultats CI-CCA-344545-CS-INDV / Re 4. Program coordination, mo Individual Consult Pending Impleme crutement d’un facilitateur p IBRD / 88450 nitoring and knowledge man Post Limited 9,740.00 0.00 2023-06-06 2023-06-11 2023-07-02 2023-08-06 2024-02-02 ant Selection ntation our l’animation d’une retraite agement du personnel Page 4 CI-CCA-344940-CS-CDS / Ent ente Directe avec Monsieur N AYO ANKOUVI MAWOUDOUDJ 2. Productivity enhancement I pour l’optimisation et le tra Pending Impleme IBRD / 88450 and improved access to mar Post Direct Selection Direct - National 16,000.00 0.00 2023-03-15 2023-03-25 2023-05-29 2023-11-25 nsfert de compétence de la c ntation kets ollecte électronique de donn ées aux services dédiés du c onseil du coton et de l’anaca rde dans le cadre du PPCA CI-CCA-344498-CS-INDV / Re 2. Productivity enhancement Individual Consult Pending Impleme cruter de consultants pour le IBRD / 88450 and improved access to mar Post Open - National 37,244.00 0.00 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 ant Selection ntation suivi des activités technique kets des CDC CI-CCA-341095-CS-CDS / Mis 1. Institutional strengthenin sion d’élaboration d’un Progr Direct - Internation IBRD / 88450 g and value chain governanc Post Direct Selection 536,063.00 0.00 Under Review 2023-07-03 2023-06-16 2023-07-13 2023-09-16 2024-01-04 amme Carbone de la filière a al e nacarde en Côte d’Ivoire : Ph ase 2 Page 5 Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: October 2016]: Revision 1 of Updated Procurement Plan, January 2017] 2. Date of General Procurement Notice: 15 July 2017 3. Period covered by this procurement plan: The procurement period of project covered from year January 2017 to December 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 780,000 All 3. ICB (Works) Above US$ 10 million All 4. NCB (Works) Above US$ 476,000 First contract 5. Consultation of the suppliers Above US$ 20,000 First contract (Works) 6. (Non-Consultant Services) Above US$ 10,000 First contract 6. Individual consultants Above US$ 19,200 All [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project under preparation. 5. Any Other Special Procurement Arrangements: 5 ICB works packages will be financed under Project preparation advance. PADAP August 22, 2017 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Ref. Description Estimat Packages Dome Review Comme No. ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary of the ICB 0.00 0 No Prior (Works) Summary of the ICB 0.50 1 No Prior (Goods) Summary of the NCB 3.656 5 No Prior (Works) Summary of the NCB 0.78 1 No Prior (Goods) Summary of the ICB 0.00 0 No Prior (Non-Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) All 2. Single Source (Firms) All 3. Individual All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 PADAP August 22, 2017 Ref. Description of Assignment Estimated Package Review Comment No. Cost s by Bank s US$ (Prior / million Post) Summary of number of 0.00 0 Prior contracts that will be let under QCBS Summary of number of 0.00 0 Prior contracts that will be let under other methods PADAP August 22, 2017 PROCUREMENT Madagascar : Sustainable Landscape Management Project PLAN General Information Country: Madagascar 2017-11-23 Bank’s Approval Date of the Original Procurement Plan: Revised Plan Date(s): (comma delineated, leave blank 2023-05-26 if none) Project ID: P154698 GPN Date: Project Name: Sustainable Landscape Management Project Loan / Credit No: IDA / V0430, IDA / 59790, COFN / C1540 PADAP PROJECT UNIT MANAGEMENT Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual A Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio High SEA/SH Process Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Contract Compl Description Component Review Type Method Document Ty Amount ( mount (U t and Recommendati Signed Contract No. ch ocess n (Y/N) Risk Status n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes etion pe US$) S$) on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned T 05-18/CN / Travaux de ré novation des locaux de l'UG Component 3: Project Mana Single Stage - One 2018-11-1 2018-10-1 2018-11-1 2018-12-1 2018-11-1 2018-12-2 2018-12-2 2019-02-0 2019-02-1 2019-07- P (Unité de Gestion du Proje IDA / 59790 gement Coordination and M Post Request for Bids Open - National 50,000.00 69,010.77 Signed Envelope 3 3 8 8 4 8 0 1 2 01 t) du PADAP à la direction d &E u Génie rural - MINAE à Nani sana Antananarivo. T 01-19/SAV / Travaux de r éhabilitation de deux (02) b âtiments de la DRAEP : Component 3: Project Mana Single Stage - One 2019-03-1 2019-04-1 2019-03-2 2019-04-2 2019-05-1 2019-05-0 2019-06-1 2019-06-0 2019-06-2 2019-08- Lot 01 : sis à Sambava, Co COFN / C1540 gement Coordination and M Post Request for Bids Open - National 65,000.00 55,651.97 Completed Envelope 5 1 6 5 3 5 7 9 8 18 mmune Sambava, District S &E ambava Lot 02 : à Sahamazava Anda pa, Commune Andapa, Distri ct Andapa T 03-19/SOF / Travaux de ré habilitations des bureaux de Component 3: Project Mana Single Stage - One 2019-05-2 2019-08-1 2019-05-2 2019-06-2 2019-09-1 2019-07-0 2019-10-2 2019-08-1 2019-11-1 2020-01- la DRAEP Sofia : COFN / C1540 gement Coordination and M Post Request for Bids Open - National 100,000.00 80,022.23 Signed Envelope 4 4 9 8 6 8 5 2 5 09 Lot 01 : Antsohihy &E Lot 02 : Bealanana T 01-19/ANJ / Travaux de ré Component 2: Investments habilitation des ouvrages su Single Stage - One 2019-02-2 2019-02-1 2019-02-2 2019-03-2 2019-03-1 2019-04-0 2019-04-0 2019-05-0 2019-04-2 2019-08- COFN / C1540 and capacity building in the Post Request for Bids Open - National 427,520.00 239,627.26 Completed r canaux d'irrigation dans le Envelope 1 4 1 3 8 7 3 2 0 30 selected landscapes périmètre de Sahavaviana-I azafo. T 02-19/ANJ / Travaux de ré Component 2: Investments habilitation des barrages de Single Stage - One 2019-02-2 2019-02-1 2019-02-2 2019-03-2 2019-03-1 2019-04-0 2019-04-0 2019-05-0 2019-04-2 2019-08- COFN / C1540 and capacity building in the Post Request for Bids Open - National 427,520.00 328,571.95 Signed dérivation dans le périmètre Envelope 1 4 1 3 8 7 3 2 0 30 selected landscapes de Sahanofia-Iazafo. T 02-19/SOF / Travaux d'am énagement du périmètre de Bealanana I Component 2: Investments Single Stage - One 2019-03-1 2019-03-0 2019-03-2 2019-04-2 2019-04-0 2019-05-0 2019-04-2 2019-06-0 2019-05-2 2019-11- Lot 01 : La partie amont du COFN / C1540 and capacity building in the Post Request for Bids Open - National 756,250.00 500,253.01 Signed Envelope 1 5 1 0 4 5 4 5 5 02 PM 580 sur le canal principal selected landscapes de la rive droite. Lot 02 : La partie aval du PM 580 sur le canal principal de la rive droite. T 01-19/SOF / Construction des ouvrages hydraulique et piste d'entretien dans le PI Mangindrano: Lot 1:BARRAGE ANTAFIANA Component 2: Investments MALONA Single Stage - One 2,188,071.8 1,554,350. 2019-03-1 2019-03-0 2019-03-2 2019-04-2 2019-04-0 2019-05-0 2019-04-2 2019-06-0 2019-05-2 2019-11- COFN / C1540 and capacity building in the Post Request for Bids Open - National Signed Lot 2:CANAL CPRD DU PM 2 Envelope 7 58 1 5 1 0 4 5 4 5 5 02 selected landscapes 153 - BOUT DU RESEAU Lot 3:CANAL CPRG 1er TRON ÇON DE 2921 ML Lot 4:CANAL CPRG 2ème TR ONÇON DE 3261 ML Lot 5:PISTE-PONT T 03-20/SOF / Travaux d'am Component 2: Investments énagement du périmètre d' Single Stage - One 2020-04-3 2020-05-1 2020-05-1 2020-06-0 2020-07-0 2020-06-2 2020-08-1 2020-08-0 2020-09-1 2021-01- COFN / C1540 and capacity building in the Post Request for Bids Open - National 375,000.00 234,454.72 Signed Anjohibe-Ambatosia dans le Envelope 0 5 0 9 6 9 7 4 2 01 selected landscapes Paysage de Bealanana. T 02-20/ANJ / Travaux de ré Component 2: Investments habilitation des infrastructur Single Stage - One 2020-02-2 2020-02-0 2020-03-1 2020-04-1 2020-03-1 2020-05-0 2020-03-2 2020-06-0 2020-04-2 2021-02- COFN / C1540 and capacity building in the Post Request for Bids Open - National 340,000.00 193,722.01 Signed es hydroagricoles dans le pé Envelope 8 1 4 3 0 3 4 3 8 08 selected landscapes rimètre d'Iazafo- Mahatsara - Andapatsara T 05-19/ANJ / Travaux de ré Component 2: Investments habilitation des infrastructur Single Stage - One 2019-09-3 2019-10-1 2019-10-1 2019-11-1 2019-11-1 2019-12-0 2020-01-0 2020-06- COFN / C1540 and capacity building in the Post Request for Bids Open - National 340,000.00 0.00 Canceled es hydroagricoles dans le pé Envelope 0 0 5 4 9 4 4 02 selected landscapes rimètre d'Iazafo- Mahatsara - Andapatsara T 04-19/SOF / Travaux de ré habilitation route non revêtu e (RIP 117M) reliant Bealana na à Ambatoriha District Be Component 2: Investments Single Stage - One 4,600,000.0 4,790,803. 2020-05-2 2020-06-2 2020-06-0 2020-07-0 2020-08-0 2020-07-2 2020-09-0 2020-09-0 2020-09-2 2021-03- alanana, Région Sofia repart COFN / C1540 and capacity building in the Post Request for Bids Open - National Signed Envelope 0 16 9 0 8 8 4 8 4 1 8 30 is en trois (03): selected landscapes Lot1:du PK 0+000-PK 18+00 0. Lot2:du PK 18+000-PK 22+0 00. Lot3:du PK 22+000-PK 30+8 T 05-19/SAV 25 / Travaux d'am (barrière Ambatoriha). élioration du réseau hydroa Component 2: Investments Single Stage - One 2020-03-2 2020-05-2 2020-04-0 2020-05-0 2020-07-0 2020-05-2 2020-08-0 2020-06-2 2020-08-2 2020-12- gricole du périmètre Ambala IDA / 59790 and capacity building in the Post Request for Bids Open - National 324,800.00 359,580.46 Signed Envelope 0 3 2 2 7 2 6 6 1 23 fary de 252 ha, Commune R selected landscapes urale Ambodidivaina, Distric t Andapa, Région SAVA T 03-19/SAV / Travaux de re construction du réseau hydr Component 2: Investments oagricole de la grappe des p Single Stage - One 2020-03-1 2020-05-2 2020-03-2 2020-04-2 2020-07-0 2020-05-1 2020-08-0 2020-06-2 2020-08-2 2020-12- IDA / 59790 and capacity building in the Post Request for Bids Open - National 313,500.00 248,719.71 Signed érimètres Andalamena et A Envelope 6 3 8 7 7 7 7 1 4 18 selected landscapes mboadiala de 191 ha , Com mune Rurale Andasibe Koba hina, District Andapa, Régio n SAVA. T 06-19/SAV / Travaux de ré novation du réseau hydroag Component 2: Investments Single Stage - One 2020-03-2 2020-05-2 2020-04-0 2020-05-0 2020-07-0 2020-05-2 2020-08-0 2020-06-2 2020-08-2 2020-12- ricole du périmètre Tanand IDA / 59790 and capacity building in the Post Request for Bids Open - National 598,500.00 494,317.43 Signed Envelope 0 3 2 2 7 2 6 6 1 23 ava sur 400 ha, Commune selected landscapes Rurale Tanandava, District A ndapa, Région SAVA. T 04-19/SAV / Travaux de re mise en état du réseau hydr oagricole de la grappe de Pé Component 2: Investments Single Stage - One 2020-03-1 2020-05-2 2020-03-2 2020-04-2 2020-07-0 2020-05-1 2020-08-0 2020-06-2 2020-12- rimètre Antanimbaribe, Amb COFN / C1540 and capacity building in the Post Request for Bids Open - National 412,500.00 0.00 Canceled Envelope 6 3 8 7 7 7 7 1 18 atoharanana et Andasimena selected landscapes lamba de 244 ha, CR Ambal amanasy II, District Andapa, Région SAVA. T 02-19/SAV / Travaux de re nforcement du réseau hydro Component 2: Investments agricole du Périmètre Ambo Single Stage - One 2020-03-2 2020-05-2 2020-04-0 2020-05-0 2020-07-0 2020-05-2 2020-08-1 2020-06-2 2020-08-2 2020-12- IDA / 59790 and capacity building in the Post Request for Bids Open - National 465,000.00 351,675.26 Signed divitagnona de 370ha, Com Envelope 0 3 1 1 7 1 0 5 1 22 selected landscapes mune Rurale Ambalamanas y II, District Andapa, Région SAVA. T 01-20/BOE / Travaux de r Component 2: Investments éhabilitation des réseaux de Single Stage - One 2020-09-0 2020-08-2 2020-09-1 2020-10-1 2020-09-2 2020-11-0 2021-08-1 2020-12-0 2021-04- COFN / C1540 and capacity building in the Post Request for Bids Open - National 800,000.00 0.00 Signed drainage des secteurs 04, 0 Envelope 8 8 8 8 9 3 6 2 01 selected landscapes 5 et 06 répartis en trois (3) lots. T 01-19/BOE / Travaux de c Component 2: Investments Single Stage - One -724,049.4 2020-07-1 2020-07-0 2020-07-3 2020-08-2 2020-08-1 2020-09-1 2020-09-1 2020-10-2 2020-09-1 2022-03- urage du drain de ceinture e COFN / C1540 and capacity building in the Post Request for Bids Open - National 431,250.00 Signed Envelope 4 6 8 0 9 0 8 5 3 9 07 t du drain naturel Manompo selected landscapes T 02-19/BOE / Travaux de r egabaritage des cours d’eau exutoire du drainage des PI Marovoay, répartis en 2 lots Component 2: Investments : Single Stage - One 2020-07-2 2020-07-1 2020-08-0 2020-09-1 2020-08-1 2020-10-1 2020-09-2 2020-11-2 2020-10-0 2022-04- COFN / C1540 and capacity building in the Post Request for Bids Open - National 458,000.00 299,370.00 Signed Lot 01: dans le secteur 5 du Envelope 8 7 7 6 8 1 9 1 6 20 selected landscapes PM 2903 (Ambohijaoka) au P M 4114 (Andranodaka). Lot 02: dans le secteur 4 du PM 4114 (Andranodaka) au PM 5865 (Ambolomoty). T 02-20/SAV / Travaux de re mise en état du réseau hydr oagricole de la grappe de Pé Component 2: Investments Single Stage - One 2020-10-1 2020-09-2 2020-10-1 2020-11-1 2020-10-2 2020-12-0 2020-12-0 2021-01-1 2020-12-1 2021-05- rimètre Antanimbaribe, Amb COFN / C1540 and capacity building in the Post Request for Bids Open - National 412,500.00 166,314.53 Completed Envelope 3 4 8 7 6 7 3 1 9 11 atoharanana et Andasimena selected landscapes lamba de 244 ha, CR Ambal amanasy II, District Andapa, Région SAVA (RELANCE). T 4-19/ANJ / Travaux de réh abilitation des canaux d'irrig ation et ouvrages de franchi Component 2: Investments ssement dans le district de Single Stage - One 2,720,000.0 1,255,680. 2019-12-2 2019-12-2 2019-12-3 2020-01-3 2020-01-2 2020-02-1 2020-02-2 2020-03-2 2020-03-2 2020-08- COFN / C1540 and capacity building in the Post Request for Bids Open - National Signed Soanierana Ivongo : Lot 01 : Envelope 0 22 1 1 1 0 1 9 6 1 6 18 selected landscapes périmètre de Marovinanto L ot 02 : périmètre de Sahafar y Lot 03 : périmètre de Vohij iny Lot 04 : périmètre d'Amp asimbola T 04-19/ANJ / Travaux de ré habilitation des canaux d'irri gation et des ouvrages de fr Component 2: Investments anchissement dans le distric Single Stage - One 2,720,000.0 2019-07-1 2019-12-2 2019-07-2 2019-08-2 2020-01-2 2019-09-0 2019-10-0 2020-03- COFN / C1540 and capacity building in the Post Request for Bids Open - National 0.00 Canceled t de Soanierana Ivongo : Envelope 0 1 1 1 0 1 9 4 02 selected landscapes Lot 01 : périmètre de Marovi nanto Lot 02 : périmètre de Sahafa ry Lot 03 : périmètre de Vohijin yT 03-19/ANJ / Travaux de re mise Lot 04en état des ouvrages : périmètre d'Ampasi e xistant mbola et curage des drains dans le PI d'Iazaf: Lot 1:zone Mahanoro-Mahat Component 2: Investments Single Stage - One 2,550,000.0 2019-04-2 2019-05-0 2019-05-1 2019-06-1 2019-06-1 2019-06-3 2019-07-3 2019-12- sara COFN / C1540 and capacity building in the Post Request for Bids Open - National 0.00 Canceled Envelope 0 6 6 1 0 1 0 1 28 Lot 2:zone Ambalabe II-Antsi selected landscapes ratenina Lot 3:zone B1-B6 Lot 4:zone Maromitety Lot 5:zone Sahafana-Ambat omirahalahy Lot 6:Mahatsara-Andapat T 05-20/SAV / Travaux de re piquage mécanisé dans les communes rurales d'Andasi Component 2: Investments 2020-10-2 2020-09-2 2020-11-0 2020-10-0 2020-12-2 2020-12-1 2021-01- be Kobahina, Ankiakabe Nor COFN / C1540 and capacity building in the Post Direct Selection Direct 450,000.00 446,347.92 Signed 3 8 7 9 2 1 21 d, Bealampona et Ambodidi selected landscapes vaina, district d'Andapa dan s le cadre de la relance de la production post-Covid. T 09-20/SOF / Reprise des tr avaux de réhabilitation du r éseau hydroagricole du péri Component 2: Investments mètre Andranomafana Mang 2020-10-2 2020-10-2 2020-11-0 2020-10-2 2020-12-0 2020-12-0 2021-04- COFN / C1540 and capacity building in the Post Direct Selection Direct 295,000.00 269,166.98 Signed indrano du paysage de Beal 7 6 6 6 6 1 05 selected landscapes anana, CR Mangindrano ; ré gion SOFIA lot 01 : travaux s ur le barrage d'Antafianamal ona CPRD, partiteur, bâche et chute Page 1 T 08-20/SOF / Reprise des tr avaux de réhabilitation des i nfrastructures hydroagricole Component 2: Investments s du périmètre Bealanana 1 2020-10-2 2020-10-0 2020-11-0 2020-10-0 2020-12-0 2020-10-0 2021-04- COFN / C1540 and capacity building in the Post Direct Selection Direct 180,000.00 172,694.40 Signed du paysage de Bealanana, C 7 2 6 2 6 8 05 selected landscapes R Bealanana district Bealana na région SOFIA- lot 01 bis : la partie amont du pm 580 s ur le canal principal de la riv e droite T 01-21/ANJ / Travaux de pr otection des berges des rivi ères dans les Paysages d'Iaz afo et de Soanierana Ivongo : Component 2: Investments Single Stage - One 2021-09-1 2021-09-2 2021-10-2 2021-11-0 2021-11-2 2022-03- -Lot 01: Berges de la rivière COFN / C1540 and capacity building in the Post Request for Bids Open - National 824,600.00 0.00 Canceled Envelope 0 0 0 4 4 24 Iazafo selected landscapes -Lot 02: Berges de la rivière Sahavaviana -Lot 03: Berges de rivière Sa hafototra Lot 04: Berges de la rivière Sahave T 04-20/BOE / Travaux de tr ouaison et plantation de ban Component 2: Investments des anti-érosives : Single Stage - One 2020-10-3 2020-11-0 2020-12-0 2020-12-2 2021-01-2 2021-05- COFN / C1540 and capacity building in the Post Request for Bids Open - National 200,000.00 0.00 Canceled Lot 1: CR Ambolomoty Envelope 0 9 9 9 7 27 selected landscapes Lot 2: CR Tsararano lot 3: CR Anosinalainolona T 07-20/SOF / Travaux de pr otection biologique des Bass ins Versants: Lot 1:Ambatosia Lot 2:Antsamaka, Beandrare Component 2: Investments Single Stage - One 2,766,000.0 2021-01-2 2021-02-0 2021-03-0 2021-03-2 2021-05-0 2022-08- zona COFN / C1540 and capacity building in the Post Request for Bids Open - National 0.00 Canceled Envelope 0 8 7 9 9 3 26 Lot 3:Ambodiampana, Beala selected landscapes nana Lot 4:Ambatoriha, Ambarara tabe, Mangindrano Lot 5: , Marotolana, Analila, Anjozoromadosy, Ankazotok ana,Ambovonomby T 05-20/BOE / Travaux de Component 2: Investments mise en place de dispositifs Single Stage - One 2021-02-0 2021-02-1 2021-03-1 2021-04-0 2021-05-0 2021-11- COFN / C1540 and capacity building in the Post Request for Bids Open - National 468,000.00 0.00 Canceled antiérosifs sur courbes de ni Envelope 2 2 4 3 8 04 selected landscapes veau dans le paysage de Ma rovoay. T 06-20/BOE / Travaux de p rotection des bassins versan ts par la plantation d'acacia et eucalyptus répatis en 4 lo Component 2: Investments ts de 300 ha Single Stage - One 2021-02-0 2021-02-1 2021-03-2 2021-04-2 2021-05-2 2022-09- COFN / C1540 and capacity building in the Post Request for Bids Open - National 480,000.00 0.00 Canceled Lot 1: Commune d' Anosinal Envelope 9 9 1 0 5 17 selected landscapes ainolona Lot 2: Commune de Tsarara no Ouest Lot 3: Commune de Tsarara no Est lot 4: Commune d'Ambolom T 01-21/SAV / Reprise des tr oty National Procure avaux de renforcement du r Component 2: Investments ment Document éseau hydroagricole du péri 2021-05-1 2021-06-3 2021-05-2 2022-04-2 2021-07-0 2022-07-1 2021-10- COFN / C1540 and capacity building in the Post Direct Selection Direct - 1 Envelope pro 215,824.00 308,588.34 Signed mètre Ambodivitagnona, Co 7 0 7 2 4 9 02 selected landscapes cess (Non Bank- mmune Rurale Ambalamana SPD) sy II, District Andapa, Régio n SAVA. T 05-20/SOF / Travaux de L Component 2: Investments Single Stage - One 2,367,000.0 2021-06-1 2021-06-2 2021-07-2 2021-08-1 2021-09-2 2022-09- utte Antiérosive et de restau COFN / C1540 and capacity building in the Post Request for Bids Open - National 0.00 Canceled Envelope 0 8 8 8 7 1 21 ration des sols dans le pays selected landscapes age de Bealanana. T 06-20/SOF / Travaux d'am Component 2: Investments énagement de champs d'agr Single Stage - One 2021-02-0 2021-02-0 2021-03-0 2021-03-2 2021-05-0 2022-05- COFN / C1540 and capacity building in the Post Request for Bids Open - National 522,710.00 0.00 Canceled oforesterie et plantation d'ar Envelope 1 6 8 8 2 02 selected landscapes bres fruitiers dans le paysag e de Bealanana. T 02-20/SOF / Travaux d'am Component 2: Investments Single Stage - One 2021-06-2 2021-07-0 2021-07-3 2021-08-2 2021-09-2 2022-02- énagement du périmètre de COFN / C1540 and capacity building in the Post Request for Bids Open - National 160,000.00 0.00 Canceled Envelope 1 1 1 0 4 21 Doany dans le paysage de B selected landscapes ealanana. T 07-19/SAV / Traitement et stabilisation des quatres (04 Component 2: Investments ) lavaka dans les anciennes Single Stage - One 2021-05-3 2021-06-1 2021-07-1 2021-08-0 2021-09-0 2022-03- IDA / 59790 and capacity building in the Post Request for Bids Open - National 61,820.00 0.00 Canceled zones d'exploitation minière Envelope 1 5 5 4 8 07 selected landscapes s à Andasinimaro, Commune Rurale Bealampona, District Andapa, Région SAVA T 3-19/ANJ. / Travaux de re mise en état ouvrages et cu rage des drains dans le PI d'I Request for Bids Component 2: Investments azaf: Lot 1:zone Mahanoro- Single Stage - One - Small Works SP 2,550,000.0 1,642,079. 2019-05-0 2019-05-1 2019-05-1 2019-06-2 2019-06-1 2019-07-2 2019-08-1 2019-08-2 2019-09-0 2020-02- COFN / C1540 and capacity building in the Post Request for Bids Open - National Completed Mahatsara Lot 2:zone Ambal Envelope D (1 envelope pr 0 05 6 1 1 2 1 2 4 6 6 22 selected landscapes abe II-Antsiratenina Lot 3:zo ocess) ne B1-B6 Lot 4:zone Maromi tety Lot 5:zone Sahafana-A mbatomirahalahy Lot 6:Mah atsara-Andapatsara T 03-20/SAV / Travaux d'am Component 2: Investments Single Stage - One 2021-06-2 2021-07-0 2021-08-0 2021-08-2 2021-09-2 2022-07- énagement des zones à fort COFN / C1540 and capacity building in the Post Request for Bids Open - National 140,000.00 0.00 Canceled Envelope 8 3 2 2 6 23 e érosion au niveau du pays selected landscapes age d'Andapa. T 04-20/SAV / Travaux pour la protection et restauration Component 2: Investments Single Stage - One 1,257,400.0 2021-06-3 2021-07-1 2021-08-0 2021-08-2 2021-10-0 2022-07- des flancs de colline (bassin COFN / C1540 and capacity building in the Post Request for Bids Open - National 0.00 Canceled Envelope 0 0 0 9 9 3 30 s versants) du Paysage d'An selected landscapes dapa, District d'Andapa, Rég ion SAVA. T 01-21/BOE / Travaux de c onstruction dans les CR d'A National Procure mbolomoty, de Tsararano et Component 2: Investments ment Document Single Stage - One 2021-10-1 2021-10-2 2021-11-2 2021-12-0 2022-01-1 2022-05- d'Anosinalainolona COFN / C1540 and capacity building in the Post Request for Bids Open - National - 1 Envelope pro 80,000.00 0.00 Canceled Envelope 3 3 2 7 1 11 lot 1: 06 ateliers d'élevage p selected landscapes cess (Non Bank- ilote SPD) Lot 2: 06 unités de compost age Lot 3: 3 couloirs de vaccina T 01-20/SOF tion / Travaux d'am des bovidés Request for Bids Component 2: Investments énagement du périmètre irri Single Stage - One - Works French C 1,940,330.0 2022-05-2 2022-05-2 2022-05-3 2022-06-0 2022-06-2 2022-07-0 2022-07-1 2022-08-1 2022-08-1 2023-07- COFN / C1540 and capacity building in the Post Request for Bids Open - National 0.00 Signed gué de Beandrarezona dans Envelope ivil Law (French) 0 0 8 0 1 9 1 9 1 9 30 selected landscapes le Paysage de Bealanana ré SPD partis en trois (03) lots. National Procure T 02-20/BOE / Travaux de st Component 2: Investments ment Document abilisation des zones d'érosi Single Stage - One 2021-10-2 2021-11-0 2021-12-0 2021-12-2 2022-01-1 2022-05- COFN / C1540 and capacity building in the Post Request for Bids Open - National - 1 Envelope pro 50,000.00 0.00 Canceled on CPRD et CSPC Ambolomo Envelope 7 6 6 6 9 19 selected landscapes cess (Non Bank- ty composé d'un seul lot. SPD) T 01-21/SOF / La constructi on de 12 unités de compost age dans le paysage de Beal anana repartis en trois lots : Component 2: Investments Request for Quot Lot 01 : 4 unités dans le sou Request for Quot Single Stage - One 2022-01-3 2022-04-2 2022-07- COFN / C1540 and capacity building in the Post Open - National ations (Non Bank 45,000.00 0.00 Canceled s-paysage d’Ambatotsia, ations Envelope 1 3 22 selected landscapes -SPD) Lot 02 : 4 unités dans le sou s-paysage de Bealanana, Lot 03 : 4 unités dans le sou s-paysage d’Ambatoriha. GOODS Activity Reference No. / Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amoun Process St Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Description Component Review Type Method t and Recommendati Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) t (US$) atus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual F 18-17/CN / Acquisition des Component 3: Project Mana UN Agencies (Dir 2017-11-2 2017-11-2 2017-12-2 2018-03-2 2018-01-3 2018-06-2 IDA / V0430 Post Direct 500,000.00 341,428.00 Signed 10 Voitures et des 20 Motos gement Coordination and M ect) 7 3 7 2 0 0 &E F 01-17/CN / Fournitures de s matériels informatiques: - Lot 01:08 ordinateurs de b ureau (desktop) avec 01 ond Component 3: Project Mana uleur de chaque et 10 ordin Request for Prop Single Stage - One 2017-11-3 2017-09-0 2017-12-0 2017-09-1 2017-12-2 2017-10-1 2017-12-2 2017-10-1 2017-12-2 2018-01-1 IDA / V0430 gement Coordination and M Post Limited 70,000.00 0.00 Canceled ateurs portable (Laptop). osals Envelope 0 5 5 9 1 9 3 0 7 6 &E - Lot 02: fournitures des acc essoires informatiques 09 i mprimantes, 09 scanners, - lot 03: 06 phootcopieu MG-UGP PADAP-38789-GO- Component 3: Project Mana RFP / L'acquisition des fourni Request for Prop Single Stage - One 2017-11-3 2017-12-0 2017-12-2 2017-12-2 2018-01-0 2018-01-2 IDA / V0430 gement Coordination and M Post Limited 20,000.00 0.00 Canceled tures de bureau, consomma osals Envelope 0 5 1 6 3 3 &E bles informatiques et produi ts d'entretien du PADAP. F 04-18/CN / Fournitures de s matériels informatiques po Component 3: Project Mana Request for Quot Single Stage - One 2018-03-2 2018-02-0 2018-05-2 2018-03-1 2018-06-1 2018-03-3 ur Quatre cellules régionales IDA / V0430 gement Coordination and M Post Limited 12,000.00 10,848.04 Completed ations Envelope 6 5 0 6 9 0 d'exécution : 08 ordinateurs &E de bureau (desktop) avec 0 1 onduleur de chaque. F 5-18/CN / Acquisition des matériels informatiques pou Component 3: Project Mana Request for Quot Single Stage - One 2018-03-2 2018-01-2 2018-05-2 2018-03-0 2018-06-1 2018-03-2 r Quatre cellules régionales IDA / V0430 gement Coordination and M Post Limited 80,000.00 74,307.22 Completed ations Envelope 4 4 0 8 9 8 d'exécution : 40 ordinateurs &E portables (laptop) avec une disque dure externe de chaq ue. MG-UGP PADAP-55622-GO- Component 3: Project Mana DIR / Migration en version w 2018-03-2 2018-03-2 2018-04-0 2018-03-0 2018-05-0 2018-03-2 2018-06-2 IDA / V0430 gement Coordination and M Post Direct Selection Direct 30,000.00 28,504.82 Signed eb et Formation de logiciel T 3 7 2 6 6 3 5 &E OM²PRO licence PN-BVPI pou r PADAP. F 15-18/CN / L'acquisition d Component 3: Project Mana Request for Quot Single Stage - One 2018-07-2 2018-07-2 2018-09-0 2018-08-1 2018-10-0 2018-08-2 es Consommables informati IDA / 59790 gement Coordination and M Post Limited 9,400.00 3,282.13 Completed ations Envelope 5 0 5 4 5 1 ques pour l'Unité de Gestion &E de Projet PADAP F 06-18/CN / Acquisition de : Component 3: Project Mana lot 01 03 photocopieuses po Request for Quot Single Stage - One 2018-07-2 2018-08-0 2018-09-0 2018-09-0 2018-10-0 2018-09-1 IDA / 59790 gement Coordination and M Post Limited 48,000.00 29,323.39 Completed ur l'unité de gestion projet P ations Envelope 5 8 5 7 5 4 &E ADAP. lot 02 08 photocopieuses m onochromes pour les quatre cellules d'exécution régional MG-UGP es PADAP-38789-GO- du PADAP. Component 3: Project Mana RFQ / L'acquisition des fourn Request for Quot Single Stage - One 2017-12-0 2017-07-0 2018-02-0 2017-07-1 2018-03-0 2017-08-2 IDA / V0430 gement Coordination and M Post Limited 20,000.00 7,545.86 Completed itures de bureau, consomma ations Envelope 5 5 4 4 6 5 &E bles informatiques et produi ts d'entretien du PADAP. F 01B-17/CN / Fournitures d es matériels informatiques:- Lot 01:08 ordinateurs de bur Component 3: Project Mana eau (desktop) avec 01 ondul Request for Quot Single Stage - One 2017-09-1 2017-09-0 2017-11-2 2017-10-2 2017-12-1 2017-11-0 IDA / V0430 gement Coordination and M Post Limited 70,000.00 46,297.28 Completed eur de chaque et 10 ordinat ations Envelope 9 6 7 7 7 6 &E eurs portable (Laptop).- Lot 02: fournitures des accessoi res informatiques 09 imprim antes, 09 scanners,- lot 03: 06 phootcopie F 12-18/CN / Acquisition de : - Lot 01 : Fournitures de b Component 3: Project Mana Request for Quot Single Stage - One 2018-11-1 2019-01-1 2018-12-2 2019-02-1 2018-12-2 ureau pour l'Unité de Gestio IDA / 59790 gement Coordination and M Post Open - National 12,500.00 9,848.58 Completed ations Envelope 8 3 6 2 8 n de Projet PADAP. &E - Lot 02 : Produits d'entreti en pour l'Unité de Gestion d e Projet PADAP. Page 2 MG-UGP PADAP-87379-GO- DIR / Acquisition du logiciel Component 1: Information a 2018-11-1 2018-12-2 2018-11-2 2018-12-3 2019-01-1 2019-01-2 2019-01-2 ArcGIS auprès de la société IDA / 59790 Post Direct Selection Direct 35,000.00 22,299.71 Completed nd planning 6 4 6 0 1 9 5 MAKY Engineering et formati on sur son utilisation (Stock age et gestion des données) . F 01-18/BOE / Dotation de t Component 2: Investments Request for Quot Single Stage - One 2018-11-3 2019-01-3 2019-03-2 2019-03-0 arares pour le Centre Multipl IDA / 59790 and capacity building in the Post Open - National 12,000.00 6,360.81 Terminated ations Envelope 0 1 2 2 icateur de Semence de Tsar selected landscapes arano (Marovoay) F 01-18/SAV / Dotations de 02 moto pompes suivi d'une Component 2: Investments Request for Quot Single Stage - One 2018-11-3 2019-01-3 2019-02-2 2019-03-0 2019-03-2 formation sur l'utilisation et l IDA / 59790 and capacity building in the Post Open - National 8,000.00 4,034.55 Completed ations Envelope 0 1 8 2 7 'entretien aux deux Fédérati selected landscapes ons : MEVA Ambodidivaina e t SOA Ankiakabe Nord F 9-18/CN / Acquisition des mobiliers de bureau pour les quatre Cellule d'Exécution R Component 3: Project Mana Request for Quot Single Stage - One 2018-11-2 2019-01-1 2019-04-1 2019-02-1 2019-05-1 égionale du PADAP repartis IDA / 59790 gement Coordination and M Post Open - National 40,000.00 64,583.70 Completed ations Envelope 8 4 6 3 4 en 04 lots : Lot 01 région SO &E FIA, lot 02 région Boeny, lot 03 région SAVA et lot 04 rég ion Analanjirofo. F 02-19/BOE / Acquisition d Component 2: Investments Request for Quot Single Stage - One 2019-05-2 2019-04-0 2019-07-0 2019-04-2 2019-07-2 2019-07-1 es semences pour la diffusio COFN / C1540 and capacity building in the Post Limited 4,400.00 4,361.57 Completed ations Envelope 7 4 8 3 8 6 n des paquets technique rizi selected landscapes cole. MG-UGP PADAP-113663-GO Component 3: Project Mana Request for Quot Single Stage - One 2019-06-0 2019-08-1 2019-08-3 2019-11-0 2019-11-0 -RFQ / Acquisition de 09 can COFN / C1540 gement Coordination and M Post Open - National 31,000.00 21,856.23 Completed ations Envelope 4 0 0 8 5 opy pour les matériels roula &E nt du projet F 1-18/ANJ / Acquisition : lot Component 3: Project Mana 01 des fournitures de burea Request for Quot Single Stage - One 2018-12-0 2019-01-3 2019-03-0 IDA / 59790 gement Coordination and M Post Open - National 4,500.00 0.00 Canceled u et lot 02 des consommabl ations Envelope 5 0 1 &E es informatiques pour le CE R Analanjirofo. F 05-19/SAV / Acquisition d'i Component 2: Investments Request for Quot Single Stage - One 2019-06-1 2019-08-1 2019-07-0 2019-08-2 2019-07-1 ntrants au profit des paysan COFN / C1540 and capacity building in the Post Open - National 7,000.00 5,300.62 Completed ations Envelope 0 6 5 6 2 s formateurs (PF). selected landscapes F 06-19/SAV / Acquisition d Component 2: Investments e matériels pour le sarclage Request for Quot Single Stage - One 2019-06-1 2019-08-1 2019-07-0 2019-11-2 2019-10-1 COFN / C1540 and capacity building in the Post Open - National 10,620.00 7,662.18 Completed et la récolte au profit des pa ations Envelope 0 6 5 9 7 selected landscapes ysans formateurs (PF). MG-UGP PADAP-87384-GO- RFQ / Acquisition des matéri els informatiques (02 Deskto Component 1: Information a Request for Quot Single Stage - One 2018-11-2 2019-01-2 2019-02-1 IDA / 59790 Post Open - National 35,000.00 0.00 Canceled p) et accessoires (02 imprim nd planning ations Envelope 1 0 9 antes) pour le logiciel ArcGI S ( Stockage et gestion des données) plus 10 GPS. MG-UGP PADAP-113652-GO -RFQ / Acquisition des matér iels et accessoires informati ques : Lot 1:11 Desktop Component 1: Information a Request for Quot Single Stage - One 2019-06-3 2019-08-2 2019-12-2 2019-09-2 2020-02-0 Lot 2:11 onduleurs online COFN / C1540 Post Open - National 33,000.00 134,817.17 Completed nd planning ations Envelope 0 9 8 8 7 Lot 3:09 Laptop avec 01 dis que dur externe de chaque Lot 4: imprimante : 01 A1, 0 6 A3 et 01 jet d'encre A4 Lot 5: 09 vidéoprojecteurs a vec écran MG-UGP PADAP-116266-GO -RFQ / Acquisition des : Component 3: Project Mana Lot 01 : 10 GPS (Global Posit Request for Quot Single Stage - One 2019-07-0 2019-09-0 2019-10-1 2019-10-0 2019-11-2 COFN / C1540 gement Coordination and M Post Open - National 12,000.00 46,888.43 Completed ioning System). ations Envelope 3 1 9 1 3 &E Lot 02 : 10 appareils photos numériques. MG-UGP PADAP-120173-GO Component 3: Project Mana Request for Quot Single Stage - One 2019-07-1 2019-09-2 2019-12-2 2019-11-2 2020-02-0 -RFQ / Materiel et mobiler de COFN / C1540 gement Coordination and M Post Open - National 75,000.00 36,864.87 Completed ations Envelope 1 3 8 2 4 bureau de l'UGP. &E MG-UGP PADAP-120176-GO Component 3: Project Mana Request for Quot Single Stage - One 2019-08-0 2019-10-1 2019-12-2 2019-11-1 -RFQ / Équipement de prote COFN / C1540 gement Coordination and M Post Open - National 3,000.00 5,206.72 Signed ations Envelope 4 7 8 6 ction individuel (EPI) du Proj &E et. F 01-19/BOE / Acquisition d Component 2: Investments e matériels pour les AUEs/Fé Request for Quot Single Stage - One 2019-06-0 2019-08-2 2019-10-1 COFN / C1540 and capacity building in the Post Open - National 82,000.00 0.00 Canceled dérations (Mini pelle, mini c ations Envelope 6 0 9 selected landscapes ompacteur motorisé et moto pompe) F 01-19/SOF / Achats des in Component 2: Investments Request for Quot Single Stage - One 2019-06-2 2019-09-0 2019-12-2 2019-10-0 2019-12-2 trants agricole pour paysans COFN / C1540 and capacity building in the Post Open - National 11,800.00 1,487.51 Completed ations Envelope 2 1 1 1 8 leaders/adoptants selected landscapes F 02-20 /SAV / Acquisition d' intrants (semences et engrai Component 2: Investments s) au profit des 111 anciens Request for Quot Single Stage - One 2020-05-1 2020-07-0 2020-07-0 2020-07-2 2020-07-1 COFN / C1540 and capacity building in the Post Open - National 8,110.00 6,732.54 Completed paysans formateurs et de 50 ations Envelope 1 9 1 3 1 selected landscapes nouveaux paysans formateu rs dans le paysage d'Andapa , Région SAVA F 01-19/SAV / Acquisition d Component 3: Project Mana Request for Quot Single Stage - One 2019-08-1 2019-10-2 2019-11-2 e deux groupes électrogène COFN / C1540 gement Coordination and M Post Open - National 5,000.00 0.00 Canceled ations Envelope 9 9 8 s de la CER SAVA. &E F 02-19/SOF / Dotation en Component 2: Investments Request for Quot Single Stage - One 2019-04-0 2019-06-1 2019-07-1 matériels et équipements de COFN / C1540 and capacity building in the Post Open - National 15,310.00 0.00 Canceled ations Envelope 3 3 3 surveillance des COBA selected landscapes F 02-19/ANJ / Acquisition de Component 2: Investments matériesl agricoles pour le r Request for Quot Single Stage - One 2019-10-0 2019-12-1 2020-01-0 COFN / C1540 and capacity building in the Post Open - National 15,710.00 0.00 Canceled eboisement dans les paysag ations Envelope 5 5 4 selected landscapes es de Soanierana Ivongo et I azafo. F 06-19/ANJ / Acquisition de Component 2: Investments s jeunes plants pour les acti Request for Quot Single Stage - One 2019-09-1 2019-11-2 2020-01-0 COFN / C1540 and capacity building in the Post Open - National 23,270.00 0.00 Canceled vités de reboisement dans l ations Envelope 4 4 8 selected landscapes es paysages d'Iazafo et de S oanierana Ivongo. F 02-18/BOE / Acquisition d Component 3: Project Mana e divers articles pour le fonc Request for Quot Single Stage - One 2018-11-3 2019-01-3 2019-03-0 IDA / 59790 gement Coordination and M Post Limited 1,700.00 0.00 Canceled tionnement du bureau du Pr ations Envelope 0 0 1 &E ojet (Marovoay et Mahajang a) F 03-20/BOE / Acquisition d Component 2: Investments Request for Quot Single Stage - One 2020-06-0 2020-08-3 2021-07-0 2020-11-2 2021-07-0 e tarare pour le centre multi COFN / C1540 and capacity building in the Post Open - National 21,875.00 20,276.70 Completed ations Envelope 4 0 9 8 9 plicateur de semence à Tsar selected landscapes arano (RELANCE) F 04-20/SAV / Acquisition d Component 2: Investments es balances automatiques fo Request for Quot Single Stage - One 2020-04-2 2020-06-2 2020-07-0 2020-07-2 2020-08-2 COFN / C1540 and capacity building in the Post Open - National 1,250.00 794.36 Completed rce de 20kg pour les semen ations Envelope 0 3 1 3 0 selected landscapes ciers dans le paysage d'And apa, Région SAVA. F 03-20/SAV / Acquisition d Component 2: Investments e 31 panneaux d'indication Request for Quot Single Stage - One 2020-03-1 2020-05-2 2020-06-2 COFN / C1540 and capacity building in the Post Open - National 1,300.00 0.00 Canceled pour les sites de reboisemnt ations Envelope 2 5 4 selected landscapes dans le paysage d'Andapa, Région SAVA. F 05-20/CN / Acquisition d' Component 3: Project Mana UN Agencies (Dir 2020-02-2 2020-03-0 2020-04-2 2020-10-2 IDA / V0430 Post Direct 83,500.00 0.00 Canceled un véhicule 4x4 pick-up du P gement Coordination and M ect) 8 9 3 0 ADAP &E F 01-20/CN / Acquisition de 4 véhicules (Motos) pour les Component 2: Investments Request for Quot Single Stage - One 2020-03-0 2020-05-1 2020-07-1 agents communaux chargés COFN / C1540 and capacity building in the Post Open - National 16,000.00 0.00 Canceled ations Envelope 4 7 6 de l'appui aux Communauté selected landscapes s Locales à l'approche LIFE MG-UGP PADAP-76372-GO- RFQ / Acquisition d’images s atellitaires à haute résolutio Component 1: Information a Request for Quot Open - Internation Single Stage - One 2020-04-0 2020-06-1 2020-08-1 COFN / C1540 Post 50,000.00 0.00 Canceled n avec modèle numérique d nd planning ations al Envelope 8 8 7 e terrain pour le paysage de Bealanana, d’une superficie de 2776 km2 environ. F 04-20/ANJ / Achat d'intran ts agricoles: Lot 01: Engrais minéraux Lot 02: Engrais organiques Lot 03: Semences: riz améli Component 2: Investments Request for Quot Single Stage - One 2021-06-2 2021-09-0 2020-12-2 2021-10-0 orés, de base, maïs et haric COFN / C1540 and capacity building in the Post Open - National 89,280.00 26,212.33 Signed ations Envelope 5 7 2 7 ot selected landscapes Lot 04: Semences: tephrosia et stylosanthes Lot 05: Eclats de souches de Bachiaria et Pennisetum Lot 06: Semence riz F 06-20/BOE / Acquisition d e manguiers Component 2: Investments Request for Quot Single Stage - One 2020-10-0 2020-12-1 2020-12-1 2021-02-1 Lot 01 : Site d'Ambolomoty COFN / C1540 and capacity building in the Post Open - National 97,500.00 9,896.21 Signed ations Envelope 5 6 2 4 Lot 02 : Site de Tsararano selected landscapes Lot 03: Site d'Anosinalainolo na F 07-20/BOE / Acquisition d' Component 2: Investments Request for Quot Single Stage - One 2020-09-2 2020-12-0 2020-11-1 2021-03-3 acacia pour la protection du COFN / C1540 and capacity building in the Post Open - National 98,000.00 96,805.52 Signed ations Envelope 6 1 2 1 sol selected landscapes F 08-20/BOE / Acquisition d' Component 2: Investments Request for Quot Single Stage - One 2020-09-2 2020-12-0 2020-11-1 2021-03-3 eucalyptus pour le reboisem COFN / C1540 and capacity building in the Post Open - National 98,500.00 101,868.48 Signed ations Envelope 6 1 2 1 ent à vocation bois d'œuvre selected landscapes F 09-20/BOE / Acquisition d Component 2: Investments Request for Quot Single Stage - One 2020-10-0 2020-12-1 2020-11-1 2021-04-0 e plantule pour le regarniss COFN / C1540 and capacity building in the Post Open - National 12,500.00 14,002.23 Signed ations Envelope 5 0 2 9 age des terrains de reboise selected landscapes ment 2019 - 2020 F 06-19/BOE / Acquisition d' Component 2: Investments engrais Request for Quot Single Stage - One 2020-09-2 2020-11-2 2020-12-1 2021-11-2 COFN / C1540 and capacity building in the Post Open - National 97,000.00 29,536.56 Signed Lot 1: Engrais organique ations Envelope 2 8 2 8 selected landscapes Lot 2: NPK et Urée F 10-20/BOE / Acquisition d e bouture et de haie vive Component 2: Investments Request for Quot Single Stage - One 2020-10-0 2020-12-1 2020-12-1 2021-03-1 Lot 1: Stylosanthès COFN / C1540 and capacity building in the Post Open - National 98,000.00 30,351.26 Signed ations Envelope 5 0 2 0 lot 2: Brachiaria selected landscapes Lot 3: Vétiver F 11-20/BOE / Acquisition d Component 2: Investments e matériel végétal et de cult Request for Quot Single Stage - One 2020-09-2 2020-12-0 2020-12-1 2021-01-0 COFN / C1540 and capacity building in the Post Open - National 96,000.00 2,228.17 Signed ure vivrière ations Envelope 7 2 2 1 selected landscapes Lot 1: arachide, riz pluvial, Maïs Lot 2: Bouture de manioc F 12-20/BOE / Acquisition d es citronniers Component 2: Investments Request for Quot Single Stage - One 2020-10-0 2020-12-1 2020-12-1 2021-02-0 Lot 01 : Site d'Ambolomoty COFN / C1540 and capacity building in the Post Open - National 95,000.00 19,160.49 Signed ations Envelope 5 0 2 8 Lot 02 : Site de Tsararano selected landscapes Lot 03: Site d'Anosinalainolo na Page 3 F 13-20/BOE / Achat d'oran Component 2: Investments giers : Request for Quot Single Stage - One 2020-10-0 2020-12-1 2020-12-1 2021-02-0 COFN / C1540 and capacity building in the Post Open - National 98,400.00 15,892.82 Signed Lot 01 : Site d'Ambolomoty ations Envelope 5 0 2 8 selected landscapes Lot 02 : Site de Tsararano Lot 03: Site d'Anosinalainolo na F 03-19/ANJ / Achat d'intran ts agricoles pour:les payasn s formateurs, semenciers, a Component 2: Investments doptants et banques de sem Request for Quot Single Stage - One 2020-09-0 2020-11-1 2020-12-2 COFN / C1540 and capacity building in the Post Open - National 89,500.00 0.00 Canceled ences: Lot 01: Engrais minér ations Envelope 1 1 6 selected landscapes al et organique Lot 02: Sem ences rizicoles Lot 03: Matér iels végétaux pour l'agroéco logie et production fourragèr e F 03-20/ANJ / Acquisition de Component 2: Investments jeunes plants de culture de r Request for Quot 2020-08-2 2020-11-1 2020-08-2 2021-01-0 COFN / C1540 and capacity building in the Post 22,150.00 10,262.33 Signed ente pour l'agroforesterie à I ations 8 0 6 9 selected landscapes azafo et Soanierana Ivongo F 04-19/SOF / Achat des éq Component 2: Investments Request for Quot Single Stage - One 2019-06-2 2019-09-0 2019-10-0 uipement agricole pour pays COFN / C1540 and capacity building in the Post Open - National 36,600.00 0.00 Canceled ations Envelope 3 2 2 ans leaders/adoptants. selected landscapes Component 2: Investments F 07-19/BOE / Acquisition d Request for Quot Single Stage - One 2019-09-2 2019-11-3 2019-12-3 COFN / C1540 and capacity building in the Post Open - National 33,000.00 0.00 Canceled es jeunes plants. ations Envelope 4 0 0 selected landscapes F 09-20/CN / Acquisition de Component 3: Project Mana Request for Quot Single Stage - One 2020-12-1 2020-12-1 2021-01-2 2021-03-1 2021-02-2 2021-03-2 fournitures de bureau pour l' COFN / C1540 gement Coordination and M Post Open - National 4,000.00 3,828.99 Completed ations Envelope 0 7 4 3 3 3 Unité de Gestion de Projet P &E ADAP F 01-20/BOE / Acquisition d Component 2: Investments Request for Quot Single Stage - One 2021-02-2 2021-05-2 2021-11-2 e semence pour la diffusion COFN / C1540 and capacity building in the Post Open - National 2,200.00 0.00 Canceled ations Envelope 0 5 1 des paquets techniques agri selected landscapes coles F 3-20/BOE / Acquisition de Component 2: Investments Request for Quot Single Stage - One 2020-06-0 2020-09-0 2020-07-0 2020-11-3 tarare pour le centre multipl COFN / C1540 and capacity building in the Post Open - National 21,900.00 19,670.17 Signed ations Envelope 6 1 9 0 icateur de semence à Tsarar selected landscapes ano. F 04-20/CN / Acquisition de Component 3: Project Mana Request for Quot Single Stage - One 2020-11-1 2020-12-1 2021-01-1 2021-03-1 2021-02-1 COFN / C1540 Post Open - National 2,250.00 7,641.34 Signed 7 coffres forts du PADAP. gement Coordination and M ations Envelope 5 7 4 8 3 &E F 07-20/CN / Acquisition de Component 3: Project Mana Request for Quot Single Stage - One 2020-11-0 2020-12-1 2021-01-1 2021-03-1 2021-03-1 2021-04-0 matériels informatiques du P COFN / C1540 gement Coordination and M Post Open - National 3,000.00 2,796.37 Completed ations Envelope 7 7 6 8 7 1 ADAP: 9 stabilisateurs &E F 08-20/CN / Acquisition des Component 3: Project Mana Request for Quot Single Stage - One 2020-11-0 2020-12-1 2021-01-0 2021-03-1 2021-02-0 2021-03-1 09 vidéoprojecteurs avec éc COFN / C1540 gement Coordination and M Post Open - National 25,000.00 17,232.84 Completed ations Envelope 7 7 6 0 5 1 ran du PADAP. &E F 04-19/SAV / Acquisition d Component 3: Project Mana Request for Quot Single Stage - One 2020-11-2 2021-01-1 2020-12-2 2021-02-0 2021-02-1 es consommables informati COFN / C1540 gement Coordination and M Post Open - National 21,880.00 21,420.49 Completed ations Envelope 8 0 2 9 1 ques pour la CER SAVA &E F 02-19/SAV / Acquisition d Component 3: Project Mana Request for Quot Single Stage - One 2020-11-3 2021-01-1 2020-12-2 2021-02-1 2021-02-1 es fournitures de bureau po COFN / C1540 gement Coordination and M Post Open - National 21,880.00 13,631.51 Completed ations Envelope 0 2 2 1 1 ur la CER SAVA. &E F 05-20/SAV / Acquisition d'i ntrants agricoles repartis en quatre lots: Lot1 : Semences de base Component 2: Investments Request for Quot Single Stage - One 2020-12-0 2021-02-0 2021-01-0 2021-03-1 2021-02-1 Lot2 : semences certifiées d COFN / C1540 and capacity building in the Post Open - National 34,000.00 19,235.18 Completed ations Envelope 5 8 6 0 1 e riz irrigué selected landscapes Lot 3 : Engrais organique Lot 4 : Urée Lot 5 : Graines pour 56 sites de pépinières permanente. F 01-20/SAV / Acquisition d es panneaux d'indication de s sites dans le paysage d'An Component 2: Investments Request for Quot Single Stage - One 2020-11-2 2021-02-1 2020-12-2 2021-03-1 2021-06-2 dapa, Région SAVA : COFN / C1540 and capacity building in the Post Open - National 8,600.00 7,829.69 Completed ations Envelope 8 1 2 3 4 Lot 01: sites de reboisement selected landscapes Lot 02 : sites de parcelle de démonstration F 14-20/CN / Achat de Prod Component 3: Project Mana Request for Quot Single Stage - One 2020-12-1 2020-12-1 2021-01-2 2021-02-2 uits d'entretien pour l'Unité COFN / C1540 gement Coordination and M Post Open - National 3,000.00 0.00 Canceled ations Envelope 0 7 4 3 de Gestion de Projet PADAP &E F 15-20/CN / Achat de cons Component 3: Project Mana Request for Quot Single Stage - One 2020-12-1 2020-12-1 2021-01-2 2021-03-1 2021-02-2 2021-03-2 ommable informatiques pou COFN / C1540 gement Coordination and M Post Open - National 20,500.00 18,530.15 Completed ations Envelope 0 7 4 3 3 3 r l'Unité de Gestion de Projet &E PADAP F 06-20/CN / Acquisition des Component 3: Project Mana Request for Quot Single Stage - One 2020-11-1 2021-01-1 2021-02-1 matériels de lavage à haute COFN / C1540 gement Coordination and M Post Open - National 1,500.00 0.00 Canceled ations Envelope 5 4 3 pression du PADAP. &E F 07-20/SAV / Acquisition p our les vétérinaires mandat aires en vue d’améliorer la s anté des animaux d’élevage Component 2: Investments Request for Quot Single Stage - One 2020-12-1 2021-02-2 2021-03-2 au niveau du paysage d’And COFN / C1540 and capacity building in the Post Open - National 5,000.00 0.00 Canceled ations Envelope 2 5 7 apa : selected landscapes Lot 1 : 02 (deux) réfrigérate urs solaires Lot 2 : 02 (deux) kits de vac cination F 02-20/SOF / Acquisitions d e semences certifiées de riz Component 2: Investments Request for Quot Single Stage - One 2021-01-1 2021-03-0 2020-12-1 2021-04-2 irrigué pour le Paysage de B COFN / C1540 and capacity building in the Post Open - National 75,000.00 40,209.69 Signed ations Envelope 1 8 1 2 ealanana : selected landscapes LOT 01: riz certifiées X-265 Lot 02 : riz certifiées MK-34 F 04-20/SOF / Acquisition d Component 2: Investments e fumier de parc pour la mis Request for Quot Single Stage - One 2021-01-1 2021-03-0 2020-12-0 2021-05-0 COFN / C1540 and capacity building in the Post Open - National 100,000.00 67,305.70 Signed e en œuvre de la riziculture ations Envelope 1 5 9 4 selected landscapes et de l'agroforesterie dans le paysage de Bealanana. F 05-20/SOF / Acquisition d' agrumes : Lot 1: 20 000 greffes de ma ndarinier ou de greffes d'ora Component 2: Investments Request for Quot Single Stage - One 2021-01-1 2021-03-0 2020-12-0 2021-08-0 nger COFN / C1540 and capacity building in the Post Open - National 80,000.00 45,208.10 Signed ations Envelope 1 8 9 5 Lot 2: 10 000 de citronnier selected landscapes Lot 3: 10 000 greffes de Pa mplemoussiers Lot 4: 30 000 porte-greffes d e la famille de mandarinier F 07-20/SOF / Acquisition d es jeunes plants de caféier e Component 2: Investments Request for Quot Single Stage - One 2021-01-1 2021-03-0 2020-12-1 2021-08-0 n 2 lots pour le paysage de COFN / C1540 and capacity building in the Post Open - National 91,450.00 31,516.80 Signed ations Envelope 1 8 0 5 Bealanana: selected landscapes Lot 01: 5 000 de caféier Ro busta Lot 02: 75 000 de caféier Ar F 08-20/SOF / Acquisition d' abica Component 2: Investments Request for Quot Single Stage - One 2021-01-1 2021-03-0 2020-12-1 2021-04-1 Engrais organique de type G COFN / C1540 and capacity building in the Post Open - National 54,400.00 38,341.43 Signed ations Envelope 1 5 0 9 uano pour le Paysage de Be selected landscapes alanana F 09-20/SOF / Acquisition d Component 2: Investments es jeunes plants pour stabili Request for Quot Single Stage - One 2021-01-2 2021-03-1 2020-12-0 2021-06-1 COFN / C1540 and capacity building in the Post Open - National 99,500.00 57,812.66 Signed sation de terrains dégradés ations Envelope 1 7 5 5 selected landscapes (Ambararatabe Nord - Amba toriha Est) F 10-20/SOF / Fourniture de Component 2: Investments s jeunes plants pour protecti Request for Quot Single Stage - One 2021-01-2 2021-03-2 2020-12-0 2021-06-2 COFN / C1540 and capacity building in the Post Open - National 99,000.00 57,812.66 Signed on des pistes ruraux (Antsa ations Envelope 1 8 5 6 selected landscapes maka -Beandrarezona) F 11-20/SOF / Achat des jeu Component 2: Investments Request for Quot Single Stage - One 2021-01-1 2021-03-2 2021-06-2 nes plants pour production d COFN / C1540 and capacity building in the Post Open - National 99,500.00 0.00 Canceled ations Envelope 6 3 1 e bois énergie (Ambatosia) selected landscapes F 12-20/SOF / Achat des jeu Component 2: Investments Request for Quot Single Stage - One 2021-01-1 2021-03-1 2020-12-1 2021-06-1 nes plants pour production d COFN / C1540 and capacity building in the Post Open - National 99,400.00 67,907.88 Signed ations Envelope 1 8 0 6 e bois d'œuvre (Ambatosia) selected landscapes F 13-20/SOF / Fourniture de Component 2: Investments s jeunes plants pour protecti Request for Quot Single Stage - One 2021-01-1 2021-03-1 2020-12-1 2021-06-1 COFN / C1540 and capacity building in the Post Open - National 99,000.00 57,239.35 Terminated on des périmètres irrigués à ations Envelope 1 8 1 6 selected landscapes réhabiliter par le Projet F 14-20/SOF / Acquisition d Component 2: Investments e jeunes plants pour protecti Request for Quot Single Stage - One 2021-01-1 2021-03-1 2020-12-1 2021-06-1 COFN / C1540 and capacity building in the Post Open - National 80,000.00 43,641.23 Terminated on des Lacs et Etangs (Beal ations Envelope 1 8 6 6 selected landscapes anana - Beandrarezona) F 15-20/SOF / Fourniture de Component 2: Investments s plants pour restauration d Request for Quot Single Stage - One 2021-01-1 2021-03-1 2020-12-1 2021-09-1 COFN / C1540 and capacity building in the Post Open - National 99,000.00 92,215.65 Signed es forêts dégradées (Analila ations Envelope 1 8 0 4 selected landscapes - Anjozoromadosy- Marotola na - Ankazotokana) F 16-20/SOF / Acquisition d Component 2: Investments es jeunes plants pour restau Request for Quot Single Stage - One 2021-01-1 2021-03-1 2020-12-0 2021-06-1 COFN / C1540 and capacity building in the Post Open - National 99,000.00 57,926.23 Signed ration/conservation des sols ations Envelope 1 8 5 6 selected landscapes (Bealanana - Ambodiampan a) F 17-20/SOF / Fourniture de Component 2: Investments s jeunes plants pour la prote Request for Quot Single Stage - One 2021-01-1 2021-03-2 2020-12-1 2021-06-2 COFN / C1540 and capacity building in the Post Open - National 99,800.00 87,330.08 Signed ction autour des zones géré ations Envelope 6 6 1 4 selected landscapes es par les COBA (Mangindra no - Ambovonomby) F 18-20/SOF / Acquisition d' arbres autochtones à fruits c Component 2: Investments Request for Quot Single Stage - One 2021-01-1 2021-03-0 2020-12-1 2021-08-0 omestibles : COFN / C1540 and capacity building in the Post Open - National 69,000.00 125,053.64 Signed ations Envelope 1 8 1 5 Lot 1: 30 000 Jacquier produ selected landscapes it Lot 2: 30 000 jeunes plants d'Eugenia F 19-20/SOF / Acquisition d es jeunes plaqueminiers, de bibaciers et de litchi: Lot 1: 30 000 variété amélio Component 2: Investments Request for Quot Single Stage - One 2021-01-1 2021-03-0 2020-12-1 2021-08-0 rée de plaqueminier (Kaki) COFN / C1540 and capacity building in the Post Open - National 86,000.00 66,761.00 Signed ations Envelope 1 8 0 5 Lot 2: 25 000 variété amélio selected landscapes rée de bibacier Lot 3: 20 000 jeunes plants de litchi F 20-20/SOF / Acquisition d e manguiers 2 lots pour le p aysage de Bealanana: Component 2: Investments Request for Quot Single Stage - One 2021-01-1 2021-03-0 2020-12-1 2021-08-0 Lot 01: 20 000 Manguier por COFN / C1540 and capacity building in the Post Open - National 69,000.00 22,894.92 Signed ations Envelope 1 8 0 5 te-greffe selected landscapes Lot 02: 40 000 variétés amél iorées de manguiers F 21-20/SOF / Acquisition d e papayer en 2 lots : Component 2: Investments Lot 1: 40 000 de papayer (S Request for Quot Single Stage - One 2021-01-1 2021-03-0 2020-12-0 2021-08-0 COFN / C1540 and capacity building in the Post Open - National 92,000.00 39,921.28 Signed olo Sunset, Solo Waimanalo, ations Envelope 1 8 9 5 selected landscapes Sunrise...) Lot2: 40 000 d'avocatier de race MEXICAIN. Page 4 F 22-20/SOF / Acquisition d Component 2: Investments Request for Quot Single Stage - One 2021-01-1 2021-03-1 2020-12-1 2021-04-2 e dolomie agricole de redres COFN / C1540 and capacity building in the Post Open - National 64,000.00 43,150.08 Signed ations Envelope 6 3 0 7 sement du sol pour le Paysa selected landscapes ge de Bealanana F 23-20/SOF / Acquisition d'i Component 2: Investments Request for Quot Single Stage - One 2021-01-1 2021-03-1 2020-12-1 2021-04-2 ntrants agricoles de synthès COFN / C1540 and capacity building in the Post Open - National 89,000.00 56,716.05 Signed ations Envelope 6 3 1 7 e (NPK et Urée) pour le Pays selected landscapes age de Bealanana F 25-20/SOF / Acquisition d Component 2: Investments e Semences de Brachiaria o Request for Quot Single Stage - One 2021-01-1 2021-03-2 2020-12-1 2021-04-2 COFN / C1540 and capacity building in the Post Open - National 95,000.00 106,338.91 Terminated u de Stylosanthès dans le pa ations Envelope 6 1 5 0 selected landscapes ysage de Bealanana. F 08-20/SAV / Acquisition d Component 3: Project Mana es produits d'entretien pour Request for Quot Single Stage - One 2021-02-0 2021-04-0 2021-05-0 COFN / C1540 gement Coordination and M Post Open - National 3,130.00 0.00 Canceled la Cellule d'Exécution Régio ations Envelope 3 9 9 &E nale SAVA (RELANCE). F 03-19/SAV / Acquisition d Component 3: Project Mana Request for Quot Single Stage - One 2020-11-3 2021-01-1 2021-02-1 COFN / C1540 Post Open - National 3,130.00 0.00 Canceled es produits d'entretien pour gement Coordination and M ations Envelope 0 2 1 la CER SAVA &E F 02-20/ BOE / Acquisition Component 3: Project Mana Request for Quot Single Stage - One 2021-01-0 2021-04-0 2021-05-0 de consommables informati COFN / C1540 gement Coordination and M Post Open - National 2,000.00 0.00 Canceled ations Envelope 2 8 8 ques pour 2 années &E F 04-21/BOE / Acquisition d’ intrants pour les riziculteu Component 2: Investments rs dans les CR d'Ambolomot Request for Quot Single Stage - One 2021-03-0 2021-05-2 2021-04-0 2021-06-2 COFN / C1540 and capacity building in the Post Open - National 98,500.00 98,512.49 Signed y, de Tsararano et d'Anosina ations Envelope 5 3 9 2 selected landscapes lainolona Lot 1 engrais de type organi que Lot 2 NPK et d' Urée F 02-21/BOE / Acquisition d e semence certifiée de riz irr Component 2: Investments Request for Quot Single Stage - One 2021-03-0 2021-05-1 2021-03-2 2021-06-1 igué X 360 et X 398 pour les COFN / C1540 and capacity building in the Post Open - National 98,500.00 7,704.83 Signed ations Envelope 2 5 4 4 riziculteurs dans les CR d'A selected landscapes mbolomoty, de Tsararano et d'Anosinalainolona F 03-19/BOE / Acquisition d Component 3: Project Mana Request for Quot Single Stage - One 2021-03-2 2021-06-0 2021-04-2 2021-07-0 COFN / C1540 Post Open - National 3,400.00 3,612.33 Signed es fournitures de bureau gement Coordination and M ations Envelope 2 2 0 2 &E F 06-20/SAV / Acquisition d' Component 2: Investments Request for Quot Single Stage - One 2021-03-0 2021-04-2 2021-04-0 2021-05-2 2021-04-2 équipements pour les 4 COB COFN / C1540 and capacity building in the Post Open - National 6,810.00 2,660.40 Completed ations Envelope 3 6 1 6 7 AS dans le paysage d'Andap selected landscapes a, Région SAVA; F 09-20/SAV / Acquisition d es matériels pour la mise en Component 2: Investments oeuvre des activités liées à l Request for Quot Single Stage - One 2021-02-0 2021-04-1 2021-04-0 2021-05-1 2021-06-2 COFN / C1540 and capacity building in the Post Open - National 22,000.00 19,805.99 Completed a production des jeunes pla ations Envelope 3 9 1 9 4 selected landscapes nts de 56 sites pépinières po lyvalents dans les 14 Comm unes du Paysage d'Andapa F 02-21/ANJ / Achat d'engrai s minéraux pour les Paysans Component 2: Investments Request for Quot Single Stage - One 2021-03-2 2021-05-1 2021-05-2 Formateurs (PF) et les Paysa COFN / C1540 and capacity building in the Post Open - National 9,500.00 0.00 Canceled ations Envelope 6 6 2 ns Semenciers (PS) dans les selected landscapes paysages d'Iazafo et de Soa nierana Ivongo F 27-20/SOF / Achat des pet its matériels d'entretien (bro Component 2: Investments Request for Quot Single Stage - One 2021-10-0 2021-12-1 2022-02-0 uettes, gants, gilets, etc.) po COFN / C1540 and capacity building in the Post Open - National 16,000.00 0.00 Canceled ations Envelope 5 8 1 ur la pérennité de la route RI selected landscapes P 117 M Bealanana - Ambat oriha Est F 2-21/ANJ / Achat d'engrais minéraux pour les Paysans F Component 2: Investments Request for Quot Single Stage - One 2021-05-2 2021-02-1 2021-07-1 2021-03-1 2021-08-0 ormateurs (PF) et les Paysan COFN / C1540 and capacity building in the Post Limited 9,500.00 10,185.75 Signed ations Envelope 7 0 6 3 5 s Semenciers (PS) dans les p selected landscapes aysages d'Iazafo et de Soani erana Ivongo. F 13-20/CN / Acquisition de Component 2: Investments Request for Quot Single Stage - One 2021-07-1 2021-09-1 2021-08-1 2021-10-1 2021-08-2 12 GPS pour les Services tec COFN / C1540 and capacity building in the Post Open - National 7,000.00 10,351.39 Completed ations Envelope 0 8 3 8 4 hniques déconcentrées. selected landscapes F 11-20/CN / Acquisition de 43 motos pour les régions d' intervention du Projet (dont Component 2: Investments Single Stage - One 2021-06-3 2021-06-1 2021-07-1 2021-06-1 2021-08-0 2021-06-2 2021-08-2 2021-08-1 2021-10-0 2022-04-0 : 7 motos pour les fédératio COFN / C1540 and capacity building in the Post Request for Bids Limited 253,520.00 0.00 Canceled Envelope 0 1 0 1 9 9 9 7 3 1 ns des AUEs, 24 motos pour selected landscapes les Services techniques déc oncentrées et 12 motos pou r les nouveaux agent du Proj et. F 01-21/SAV / Acquisition d Component 2: Investments es intrants pour la mécanisa 2021-04-2 2021-04-2 2021-05-0 2021-04-2 2021-06-1 2021-04-0 2022-04-1 COFN / C1540 and capacity building in the Post Direct Selection Direct 59,760.00 61,074.43 Signed tion des travaux de repiqua 9 6 4 6 8 8 4 selected landscapes ge dans le paysage d'Andap a. F 02-21/SAV / Acquisition d Component 2: Investments e Graines pour les 56 sites p Request for Quot Single Stage - One 2021-05-0 2021-05-3 2021-06-0 2021-06-1 COFN / C1540 and capacity building in the Post Open - National 20,400.00 3,833.58 Signed épinières polyvalents dans l ations Envelope 2 0 2 4 selected landscapes es 14 Communes du Paysag e d'Andapa (RELANCE) F 01-19/ANJ / Fourniture de Component 2: Investments Request for Quot Single Stage - One 2021-05-1 2021-07-2 2021-10-1 bureau pour la CER Analanjir COFN / C1540 and capacity building in the Post Open - National 40,000.00 0.00 Canceled ations Envelope 5 3 1 ofo. selected landscapes F 04-19/ANJ / Acquisition de Component 3: Project Mana Request for Quot Single Stage - One 2021-05-2 2021-07-3 2021-08-2 s consommables informatiq COFN / C1540 gement Coordination and M Post Open - National 27,000.00 0.00 Canceled ations Envelope 5 0 9 ues pour la CER Analanjirofo &E . F 05-19/ANJ / Acquisition de Component 3: Project Mana Request for Quot Single Stage - One 2021-04-3 2021-07-0 2021-08-0 s produits d'entretien pour l COFN / C1540 gement Coordination and M Post Open - National 43,530.00 0.00 Canceled ations Envelope 0 8 7 a CER Analanjirofo &E F 03-21/SAV / Acquisition d'i ntrants agricoles au profit d es Paysans Formateurs du p aysage d'Andapa, répartis e Component 2: Investments Request for Quot Single Stage - One 2021-07-1 2021-09-2 2021-07-1 2021-10-1 2021-09-1 n trois lots : COFN / C1540 and capacity building in the Post Open - National 8,000.00 244,181.21 Completed ations Envelope 9 7 8 2 2 - Lot 1 : Semences certifiées selected landscapes de riz irrigué - Lot 2 : Engrais organique d e type Guano - Lot 3 : Urée" F 12-20/CN / Acquisition de : Lot 1: 31 ordinateurs portabl e. Component 2: Investments Request for Quot Single Stage - One 2021-07-0 2021-09-1 2021-08-1 2021-10-1 2021-08-2 Lot 2: 11 ordinateurs de bur COFN / C1540 and capacity building in the Post Open - National 99,500.00 96,956.92 Signed ations Envelope 4 2 3 2 4 eau avec 1 onduleur de cha selected landscapes que (05 pour les fédérations des AUEs et 06 pour le Proje t). Lot 3: 08 imprimantes laser (04 pour les fédérations des F 02-20/ANJ AUEs le Projet) de / Acquisition et 04 pour matériels agricoles: - Lot 01: 277 sarcleuses - Lot 02: 900 Sarcleuses, 18 Component 2: Investments 0 charrues et 450 fourches Request for Quot Single Stage - One 2021-09-0 2021-11-1 2020-12-0 2021-12-3 COFN / C1540 and capacity building in the Post Open - National 66,000.00 3,737.93 Signed - Lot 03: 63 vanneuses et 63 ations Envelope 5 5 4 0 selected landscapes batteuses - Lot 04: 90 Pulvérisateurs, 1 35 arrosoirs et 9 rouleau de 100 m de gaine en polyprop ylène F 05-21/BOE / Acquisition d e semence de riz irrigué X Component 2: Investments Request for Quot Single Stage - One 2021-02-2 2021-02-1 2021-04-2 2021-05-2 360 et X 398 pour les rizicult COFN / C1540 and capacity building in the Post Limited 98,500.00 0.00 Canceled ations Envelope 8 2 8 8 eurs dans les CR d'Ambolom selected landscapes oty, de Tsararano et d'Anosi nalainolona F 04-19/BOE / Achat pneus Component 3: Project Mana Request for Quot Single Stage - One 2021-04-1 2021-07-1 2021-08-1 COFN / C1540 Post Open - National 4,000.00 0.00 Canceled pou 2 années pour la CER B gement Coordination and M ations Envelope 9 3 2 oeny &E F 10-20/SAV / Acquisition d es 56 lots des EPI (Bottes, C ombinaisons, Gants, Imperm Component 2: Investments Request for Quot Single Stage - One 2021-07-1 2021-09-2 2021-09-0 2021-10-2 2021-09-2 éables, Gilets, casquettes) p COFN / C1540 and capacity building in the Post Open - National 7,000.00 5,623.74 Completed ations Envelope 8 1 1 1 9 our les Pépiniéristes travaill selected landscapes ant dans les sites pépinières polyvalents dans les 14 Com munes du Paysage d'Andap a F 05-21/SAV / Acquisition d'i ntrants (semences pour les Component 2: Investments cultures intercalaires et eng Request for Quot Single Stage - One 2021-09-0 2021-10-2 2021-11-2 COFN / C1540 and capacity building in the Post Open - National 14,000.00 0.00 Canceled rais organique) au profit des ations Envelope 6 3 2 selected landscapes 50 paysans adoptant l'agrof oresterie dans le paysage d' Andapa, F 24-20/SOF / Acquisition d Component 2: Investments e matériels végétaux pour p Request for Quot Single Stage - One 2021-01-1 2021-03-2 2021-05-0 COFN / C1540 and capacity building in the Post Open - National 98,000.00 0.00 Canceled lante de couverture dans le ations Envelope 6 3 7 selected landscapes Paysage de Bealanana F 03-20/SOF / Acquisition ar bres fruitiers: Lot1: 5 000 pommier porte- greffe Lot2: 20 000 variété amélior Component 2: Investments Request for Quot Single Stage - One 2021-01-1 2021-03-0 2021-07-3 ée de pommier COFN / C1540 and capacity building in the Post Open - National 86,000.00 0.00 Canceled ations Envelope 1 3 1 Lot3: 5 000 pêcher porte-gr selected landscapes effe Lot4: 20 000 variété amélior ée de pêcher Lot5: 5 000 poirier porte-gre ffe Lot6: 20 000 variété amélior de poirier / Acquisition d' F 01-21/ANJ ée Alambics et accessoires d'al Component 2: Investments ambics pour les paysans pra Request for Quot Single Stage - One 2021-08-2 2021-11-0 2022-05-0 COFN / C1540 and capacity building in the Post Open - National 46,060.00 0.00 Canceled tiquants la distillation d'esse ations Envelope 2 5 4 selected landscapes nce de girofle dans les pays ages d'Iazafo et de Soaniera na Ivongo. F 05-19/BOE / Acquisition d es matériels agricole (Sarcle Component 2: Investments Request for Quot Single Stage - One 2020-09-2 2020-11-2 2020-12-2 use, charrue à soc, herse à COFN / C1540 and capacity building in the Post Open - National 43,800.00 0.00 Canceled ations Envelope 3 9 9 dents, pulvérisateur, batteu selected landscapes se à pédale, bâche) pour un e année. F 02-21/CN / Acquisition de 19 motos routier du Projet ( Component 2: Investments Request for Quot Single Stage - One 2021-09-2 2021-12-2 2021-12-1 2022-03-1 dont : 7 motos pour les fédé COFN / C1540 and capacity building in the Post Open - National 58,000.00 0.00 Canceled ations Envelope 7 4 0 0 rations des AUEs et 12 moto selected landscapes s pour les nouveaux agent d u Projet). F 03-21/CN / Acquisition de Component 2: Investments 24 motos cross pour les Ser Single Stage - One 2021-09-3 2021-12-2 2021-10-1 2021-12-2 2021-11-0 2022-01-2 2021-11-2 2022-02-1 2022-01-0 2022-04-0 COFN / C1540 and capacity building in the Post Request for Bids Open - National 200,000.00 0.00 Canceled vices techniques déconcentr Envelope 0 3 0 4 9 5 9 8 3 3 selected landscapes ées dans la zone d'interventi on du Projet. F 01-21/CN / Achat de Prod Component 3: Project Mana Request for Quot Single Stage - One Under Imple 2021-10-1 2021-10-1 2021-11-2 2021-12-2 uits d'entretien pour l'Unité COFN / C1540 gement Coordination and M Post Open - National 3,500.00 0.00 ations Envelope mentation 0 9 4 4 de Gestion de Projet PADAP &E Page 5 F 03-21/ANJ / Acquisition de Component 3: Project Mana 2021-09-1 2021-09-2 2021-11-0 2022-05-0 véhicule 4x4 pick-up pour F COFN / C1540 gement Coordination and M Post Direct Selection Direct 50,000.00 0.00 Canceled 5 5 9 8 DAR Analanjirofo &E F 03-21/BOE / Acquisition d' Component 2: Investments alevins pour les pisciculteur Request for Quot Single Stage - One 2021-03-1 2021-05-1 2021-06-2 COFN / C1540 and capacity building in the Post Open - National 97,000.00 0.00 Canceled s dans les CR de Marosakoa ations Envelope 2 1 5 selected landscapes , d'Ambolomoty et de Tsarar ano F 04-21BOE / Acquisition de divers matériels pour les pis Component 2: Investments Request for Quot Single Stage - One 2021-03-0 2021-05-1 2021-07-0 ciculteurs dans les CR de M COFN / C1540 and capacity building in the Post Open - National 98,000.00 0.00 Canceled ations Envelope 7 7 1 arosakoa, d'Ambolomoty et selected landscapes de Tsararano ( filets, bacs,glacières, fumo irs) F 02-20/CN / Conception et Component 2: Investments fourniture de supports de co Request for Quot Single Stage - One 2021-10-0 2021-12-1 2022-01-1 COFN / C1540 and capacity building in the Post Open - National 9,500.00 0.00 Canceled mmunication pour le PADAP ations Envelope 5 8 7 selected landscapes (Flyers, banderôles, T-shirt, Polo, …) F 07-21/SAV / Acquisition d es matériels et outillages au profit du Lycée Technique et Component 2: Investments Request for Quot Single Stage - One 2021-08-2 2021-10-1 2021-11-1 Professionnel d'Andapa pour COFN / C1540 and capacity building in the Post Open - National 11,500.00 0.00 Canceled ations Envelope 1 1 0 : selected landscapes Lot 1: L' Atelier d'entretien e t de réparation des matériel s agricoles Lot 2: Les travaux pratiques F 04-21/CN / Acquisition de Component 3: Project Mana Single Stage - One 2021-12-1 2021-12-2 2021-12-2 2021-12-2 2022-01-2 2022-01-2 2022-02-1 2022-02-1 2022-03-1 2022-03-1 2022-08-0 COFN / C1540 Post Request for Bids Open - National 496,000.00 513,604.00 Completed 8 voitures type 4x4 . gement Coordination and M Envelope 3 3 3 4 2 5 1 8 2 2 9 &E F 10-20/CN / Acquisition de réfrigérateurs solaires (RS) e t kits de vaccination (KV) po Component 2: Investments ur les Paysages d’Andapa, d Request for Quot Single Stage - One 2022-02-1 2022-04-1 2022-06-0 COFN / C1540 and capacity building in the Post Open - National 50,000.00 0.00 Canceled e Bealalana et de Marovoay ations Envelope 0 0 9 selected landscapes : Lot 1 : 7 réfrigérateurs solair es (RS) Lot 2 : 7 kits de vaccination (KV). F 05-22/CN / Achat d'équipe Component 3: Project Mana Request for Quot Single Stage - One Pending Imp 2022-10-0 2022-12-0 2023-01-0 COFN / C1540 Post Open - National 9,000.00 0.00 ment de protection individu gement Coordination and M ations Envelope lementation 3 5 4 elle &E F 06-22/CN / Acquisition des Component 1: Information a Request for Quot Single Stage - One Pending Imp 2022-09-0 2022-11-3 2023-02-0 COFN / C1540 Post Open - National 45,000.00 0.00 drones pour le Projet nd planning ations Envelope lementation 8 0 3 F 08-22/CN / Acquisition des Component 2: Investments kits solaire pour les 40 Com Request for Quot Single Stage - One Pending Imp 2022-09-0 2022-11-3 2023-02-0 COFN / C1540 and capacity building in the Post Open - National 52,000.00 0.00 munes Rurales dans les pay ations Envelope lementation 8 0 3 selected landscapes sages d'intervention du Proj et. F 03-22/CN / Achats des ma tériels informatiques du Proj Component 2: Investments et : Single Stage - One 2022-10-2 2022-12-2 2022-11-0 2022-12-2 2022-12-0 2023-01-2 2022-12-2 2023-03-2 2023-01-2 2023-03-2 COFN / C1540 and capacity building in the Post Request for Bids Open - National 200,000.00 0.00 Signed Lot 01 : 40 ordinateurs de b Envelope 8 3 2 3 2 4 2 1 6 7 selected landscapes ureau (DESKTOP) Lot 02 : 40 onduleurs Lot 03 : 20 ordinateurs porta bles F 01-22CN / Acquisition de Component 2: Investments motos du Projet : Single Stage - One Under Imple 2022-10-1 2022-11-0 2022-10-1 2022-11-1 2022-11-1 2022-12-0 2022-12-1 2023-03-0 2022-12-2 2023-02-2 COFN / C1540 and capacity building in the Post Request for Bids Open - National 240,000.00 0.00 Lot 01 : 33 motos cross Envelope mentation 4 5 9 4 8 6 0 3 7 5 selected landscapes Lot 02 : 04 motos routiers F 04-22/CN / Développemen Component 3: Project Mana Request for Quot Single Stage - One 2022-09-0 2022-12-0 2023-04-0 t d'un logiciel de suivi-évalu COFN / C1540 gement Coordination and M Post Open - National 31,000.00 0.00 Canceled ations Envelope 8 8 7 ation du Projet. &E NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amoun Process St Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Description Component Review Type Method t and Recommendati Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) t (US$) atus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-UGP PADAP-70332-NC- RFQ / Service de transit pour Component 3: Project Mana dédouanement de matériels Request for Quot Single Stage - One 2018-07-2 2018-09-0 2018-07-3 2018-10-0 IDA / 59790 gement Coordination and M Post Open - National 57,000.00 34,129.26 Signed roulants (10 voitures et 20 ations Envelope 4 4 0 4 &E motos), et service de mise e n circulation des véhicules e t moto du PADAP. C 03-20/CN / Service de tra Component 3: Project Mana Request for Quot Single Stage - One 2020-03-0 2020-04-1 2020-05-1 nsit et douane pour le dédo COFN / C1540 gement Coordination and M Post Open - National 5,500.00 0.00 Canceled ations Envelope 8 7 7 uanement des matériels roul &E ants du PADAP PSNC 01-21/SOFIA / Mise en œuvre des activités de reboi sement à vocation bois d'œ uvre et d'agroforesterie : Component 2: Investments Request for Quot Single Stage - One 2021-04-0 2021-02-1 2021-05-1 2021-03-1 2022-02-0 Lot 1 : dans le Fokontany d' COFN / C1540 and capacity building in the Post Limited 99,800.00 90,458.98 Signed ations Envelope 5 9 0 6 4 Ampandrana de la CR Amba selected landscapes tosia Lot 2 : dans les Fokontany : Ambalabe, Ambohimitsinjo e t Beanatsindra de la CR Amb atosia PSNC 01-21/BOE / Réalisati on des activités de reboisem ent dans le Paysage de Mar Component 2: Investments 2021-02-2 2021-02-2 2021-03-0 2021-03-0 2021-04-2 2021-03-1 2022-07-1 ovoay COFN / C1540 and capacity building in the Post Direct Selection Direct 800,000.00 438,445.98 Signed 6 6 8 2 2 2 6 Lot 01: Essence à vocation é selected landscapes nergetique Lot 02: Essence à vocation b ois d'oeuvre PSNC 03-21/SOFIA / Conduit e de reboisement à vocation bois énergie et 115 Ha de pl Component 2: Investments Request for Quot Single Stage - One 2021-04-0 2021-02-1 2021-05-1 2021-03-1 2022-02-0 antation d'arbres fruitiers Lo COFN / C1540 and capacity building in the Post Limited 99,500.00 158,708.79 Signed ations Envelope 5 9 0 6 4 t 1: dans 04 Fokontany de la selected landscapes CR Ambodiampana Lot 2 : dans 06 Fokontany d e la CR Antsamaka PSNC 04-21/SOFIA / Mise en œuvre de reboisement et d' embocagement pour protect Component 2: Investments Request for Quot Single Stage - One 2021-04-0 2021-02-1 2021-05-1 2021-03-1 2022-02-0 ion et restauration des sols. COFN / C1540 and capacity building in the Post Limited 99,700.00 158,708.79 Signed ations Envelope 5 9 0 6 4 Lot 1 : dans 04 Fokontany d selected landscapes e la CR Ambodiampana Lot 2 : dans 06 Fokontany d e la CR Bealanana PSNC 07-21/SOFIA / Protecti on PI via reboisement et pla ntation d'arbres fruitiers dan s la Commune Rurale de Be Component 2: Investments Request for Quot Single Stage - One 2021-04-0 2021-02-1 2021-05-1 2021-03-1 2022-02-0 andrarezona COFN / C1540 and capacity building in the Post Limited 99,600.00 143,231.68 Signed ations Envelope 5 9 0 6 4 Lot 1 : dans le Fokontany de selected landscapes Beandrarezona, Lot 2 : dans les 03 Fokontan y : Andraratrarina, Ambodis atrana, Amberivery PSNC 03-21/BOE / Agence d e paiement des travaux de r Component 2: Investments Request for Quot Single Stage - One 2021-03-2 2021-05-1 2021-08-1 eboisement , de l'agroforest COFN / C1540 and capacity building in the Post Limited 40,000.00 0.00 Canceled ations Envelope 0 8 6 erie et l'amélioration des pât selected landscapes urages dans la Région Boen y PSNC 08-21/SOFIA / Agence Component 2: Investments de paiement des travaux de Request for Quot Single Stage - One 2021-04-1 2021-06-0 2021-09-0 COFN / C1540 and capacity building in the Post Limited 50,000.00 0.00 Canceled reboisement ,de l'agroforest ations Envelope 0 8 6 selected landscapes erie pour la Région Sofia PSNC 06-21/ANJ / Agence d e paiement: -Lot 1 : Reboisement à Anal abe -Lot 2: Reboisement Iazafo n Component 2: Investments ord et sud Request for Quot Single Stage - One 2021-08-0 2021-07-1 2021-10-0 2021-09-0 2022-04-2 COFN / C1540 and capacity building in the Post Open - National 52,796.00 46,078.02 Signed -Lot 3: Reboisement à Soani ations Envelope 9 4 8 1 6 selected landscapes erana ouest -Lot 4: Reboisement pour les COBA -Lot 5: Installation d’un peup lement forestier et agrofores terie -Paysage Soanierana Iv ongo PSNC 05-21/SOFIA / Rebois ement pour protection auto ur des zones gérées par les Component 2: Investments Request for Quot Single Stage - One 2021-04-0 2021-05-1 2022-02-0 COBA COFN / C1540 and capacity building in the Post Limited 99,150.00 0.00 Canceled ations Envelope 5 0 4 Lot 1 : dans 08 Fokontany d selected landscapes e la CR Mangindrano Lot 2 : dans 05 Fokontany d e la CR Ambovonomby PSNC 06-21/SOFIA / Réalisa tion de reboisement pour st abilisation des terrains dégr Component 2: Investments Request for Quot Single Stage - One 2021-04-0 2021-05-1 2022-02-0 adés COFN / C1540 and capacity building in the Post Limited 99,750.00 0.00 Canceled ations Envelope 5 0 4 Lot 1 : dans 07 Fokontany d selected landscapes e la CR Ambatoriha Est Lot 2 : dans 03 Fokontany d e la CR Ambararatabe Nord PSNC 02-21/SOFIA / Plantati on d'arbres à vocations mult iples pour la protection des versants dénudés: Component 2: Investments Request for Quot Single Stage - One 2021-04-0 2021-05-1 2022-02-0 Lot 1 : dans 05 Fokontany d COFN / C1540 and capacity building in the Post Limited 99,150.00 0.00 Canceled ations Envelope 5 0 4 e la CR Analila selected landscapes Lot 2 : dans 05 Fokontany d e la CR Anjozoromadosy ; 1 Fokontany de la CR Ankazot okana ; dans 05 Fokontany de la CR Marotolana PSNC 05-21/ANJ / Recrutem ent d'agence d'encadrement d'un peuplement forestier et Component 2: Investments Request for Quot Single Stage - One 2021-09-0 2021-11-0 2022-12-1 agroforestier dans les Com COFN / C1540 and capacity building in the Post Open - National 57,000.00 0.00 Canceled ations Envelope 3 2 7 munes de Manompana, Anta selected landscapes nifotsy, Soanierana Ivongo, Fotsialanana et Ambinanisak ana- Paysage de Soanierana Ivongo PSNC 02-21/ANJ / Encadrem ent des travaux de reboisem ent sur une surface de 257h Component 2: Investments a dans le PAYSAGE D'IAZAF Request for Quot Single Stage - One 2021-02-2 2021-04-2 2022-09-1 COFN / C1540 and capacity building in the Post Open - National 34,154.00 0.00 Canceled O ZONE NORD ET SUD, Com ations Envelope 0 6 8 selected landscapes munes Maromitety, Ampasi mazava, Antanamarina, Vav atenina, Mahanoro et Ambat oharanana- Région Analanjir ofo PSNC 03-21/ANJ / Gestion d es personnels HIMO et suivi- encadrement des travaux d Component 2: Investments e reboisement sur une surfa Request for Quot Single Stage - One 2021-03-0 2021-05-0 2022-06-2 COFN / C1540 and capacity building in the Post Open - National 64,106.00 0.00 Canceled ce de 482ha au niveau de 0 ations Envelope 8 7 1 selected landscapes 7 Fokontany dans le PAYSAG E DE SOANIERANA IVONGO, ZONE OUEST, Communes A mbahoabe et Antenina- Régi on Analanjirofo Page 6 PSNC 01-21/ANJ / Encadrem ent technique et socio-organ isationnel des travaux de re Component 2: Investments Request for Quot Single Stage - One 2021-03-0 2021-05-0 2022-06-2 boisement sur une surface d COFN / C1540 and capacity building in the Post Open - National 54,422.00 0.00 Canceled ations Envelope 8 7 1 e 409ha au niveau de 03 Fo selected landscapes kontany dans le PAYSAGE D' IAZAFO, ZONE ANALABE, Co mmune Maromitety- Région Analanjirofo PSNC 04-21/ANJ / Recrutem ent d’une Agence d’Exécutio Component 2: Investments n pour l’accomplissement d Request for Quot Single Stage - One 2021-03-0 2021-05-0 2022-06-2 COFN / C1540 and capacity building in the Post Open - National 50,623.00 0.00 Canceled u reboisement à grande éch ations Envelope 8 7 1 selected landscapes elle au niveau des zones de transfert de gestion des CO BA de la Commune Ambaho abe PSNC 04-21/SAV / Agence de paiement: Component 2: Investments Lot 1: Reboisement dans la Request for Quot Single Stage - One 2021-12-0 2022-02-0 2022-10-0 COFN / C1540 and capacity building in the Post Open - National 20,000.00 0.00 Canceled zone sud du Paysage d'Anda ations Envelope 5 4 2 selected landscapes pa Lot 2: Reboisement dans la zone nord du Paysage d'And apa PSNC 01-22/CN / Édition de s plans d’aménagement et d Component 1: Information a Request for Quot Single Stage - One 2022-02-1 2022-03-2 2022-05-0 2022-05-0 2022-05-3 COFN / C1540 Post Open - National 98,000.00 26,652.22 Signed e gestion durable des paysa nd planning ations Envelope 0 8 1 4 1 ges (PAGDP) pour les cinq P aysages du PADAP. PSNC 02-22/CN / Service po ur encadrement des activité s : de stabilisation de flancs Component 2: Investments de collines (terracing), la res 2023-01-0 2022-12-2 2023-01-1 2023-01-2 2023-03-0 2023-03-1 COFN / C1540 and capacity building in the Post Direct Selection Direct - National 1,323,000.00 0.00 Signed tauration des forêts et les tr 6 7 1 5 3 7 selected landscapes avaux d’assainissement ma nuel des canaux secondaire s en HIMO dans les paysage s d’intervention du PADAP. CONSULTING FIRMS Activity Reference No. / Short List and Draft Combined Evaluatio Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Expression of Interes Request for Proposal Opening of Technical Evaluation of Techni Description Component Review Type Method Terms of Reference Request for Proposal n Report and Draft N Signed Contract Contract Completion No. ch ount (US$) nt (US$) s t Notice s as Issued Proposals / Minutes cal Proposal s egotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C 6-18/CN / Etude d'aména gement (APS-APD-EIES-PAR- Component 2: Investments Quality And Cost- 2018-04-1 2018-02-0 2018-02-2 2018-05-1 2018-03-3 2018-06-1 2018-04-1 2018-07-0 2018-05-0 2018-07-2 2018-05-2 2018-08-2 2018-10-2 DAO-MGE) et surveillance d IDA / 59790 and capacity building in the Post Open - National 62,500.00 51,882.50 Signed 2018-01-22 Based Selection 9 6 8 1 0 2 4 2 4 4 8 9 5 es travaux dans le périmètr selected landscapes e d'Andranomafana Mangind rano, région Sofia. C 4-18/CN / Etude de rehabi litation des infrasrtuctures Component 2: Investments hydroagricoles (APS-APD-EIE Quality And Cost- 2018-03-2 2018-02-0 2018-02-2 2018-05-1 2018-03-3 2018-06-1 2018-04-1 2018-07-0 2018-05-0 2018-07-2 2018-05-2 2018-09-0 2018-11-2 IDA / 59790 and capacity building in the Post Open - National 500,000.00 287,114.06 Signed 2018-01-22 S-PAR-DAO-MGE) et surveilla Based Selection 7 6 8 0 0 2 4 2 4 7 8 3 4 selected landscapes nce des travaux dans le péri mètre de Iazafo, Région Ana lanjirofo C 5-18/CN / Etude de recon struction du barrage et réfec Component 2: Investments tion des réseaux hydroagric Quality And Cost- 2018-04-1 2018-02-0 2018-02-2 2018-05-1 2018-03-3 2018-06-1 2018-04-1 2018-07-1 2018-05-0 2018-07-2 2018-05-2 2018-08-3 2018-10-2 IDA / 59790 and capacity building in the Post Open - National 87,500.00 23,197.46 Signed 2018-01-22 oles (APD-EIES-PAR-DAO-MG Based Selection 9 6 8 0 0 2 4 3 4 4 8 1 5 selected landscapes E) et surveillance des travau x dans le périmètre d'Anjohi be Ambatosia, Région Sofia. C 7-18/CN / Etude de réhabi litation de périmètre irrigué Component 2: Investments Quality And Cost- 2018-04-1 2018-02-0 2018-02-2 2018-05-1 2018-03-3 2018-06-1 2018-04-1 2018-07-1 2018-05-0 2018-07-2 2018-05-2 2018-09-1 2018-11-2 (APD-EIES-PAR-DAO-MGE) et IDA / 59790 and capacity building in the Post Open - National 125,000.00 29,974.84 Signed 2018-01-22 Based Selection 9 6 8 0 0 2 4 3 4 4 8 0 4 surveillance des travaux dan selected landscapes s le périmètre de Bealanana I, région Sofia. C 8-18/CN / Etude d'aména gement (APS-APD-EIES-PAR- Component 2: Investments Quality And Cost- 2018-02-0 2018-02-2 2018-03-3 2018-04-1 2018-05-0 2018-05-2 2018-11-2 DAO-MGE) pour la stabilisati IDA / 59790 and capacity building in the Post Open - National 54,000.00 0.00 Canceled 2018-01-22 Based Selection 6 8 0 4 4 8 4 on des terrasse à Bealanana selected landscapes et surveillance des travaux. C 03-18/CN / Un cabinet d'a Component 3: Project Mana Least Cost Select 2018-01-2 2018-01-3 2018-02-1 2018-04-1 2018-03-1 2018-05-1 2018-03-2 2018-05-1 2018-04-0 2018-05-2 2018-04-2 2018-05-2 2018-07-2 IDA / 59790 Post Open - National 30,000.00 8,305.01 Signed 2018-01-15 udit financier du PADAP. gement Coordination and M ion 3 1 7 7 9 7 9 8 9 5 9 8 8 &E C 04-17/CN / Études prépar atoires du Projet Agriculture Durable par une Approche P Component 1: Information a Quality And Cost- 2017-06-2 2018-02-1 2018-03-3 2017-09-2 2018-04-2 2017-10-3 2018-05-0 2017-11-0 2018-05-2 2018-02-0 2018-06-1 2018-02-0 2018-09-1 aysage (PADAP) Périmètre d IDA / V0430 Post Open - National 200,000.00 224,827.15 Signed 2018-01-24 nd planning Based Selection 8 4 0 8 7 0 7 8 1 2 4 5 2 'Iazafo dans le district de Va vatenina et dans le district d e Soanierana Ivongo, région ANALANJIROFO. C 02-17/CN / Études prépar atoires du Projet Agriculture Component 1: Information a Quality And Cost- 2017-06-2 2018-02-1 2018-03-3 2017-09-2 2018-04-2 2017-10-3 2018-05-0 2017-11-0 2018-05-2 2017-12-0 2018-06-1 2018-02-0 2018-09-1 Durable par une Approche P IDA / V0430 Post Open - National 150,000.00 156,130.05 Signed 2018-01-24 nd planning Based Selection 8 4 0 8 7 0 7 8 1 7 4 9 2 aysage (PADAP) dans le dist rict de Marovoay, région BO ENY C 01-17/CN / Études prépar atoires du Projet Agriculture Component 1: Information a Quality And Cost- 2017-06-2 2018-02-1 2018-03-3 2017-09-2 2018-04-2 2017-10-3 2018-05-0 2017-11-0 2018-05-2 2018-02-0 2018-06-1 2018-03-0 2018-09-1 IDA / V0430 Post Open - National 150,000.00 234,393.50 Signed 2018-01-24 Durable par une Approche P nd planning Based Selection 8 4 0 8 7 0 7 8 1 6 4 5 2 aysage (PADAP) dans le dist rict d'Andapa, région SAVA C 01-18/CN / Développeme Component 1: Information a Quality Based Sel Open - Internation 2018-05-0 2018-05-1 2018-05-1 2018-07-1 2018-08-1 2018-08-2 2018-09-0 2018-09-3 2018-12-2 nt d'un guide pour l'élaborat IDA / 59790 Post 100,000.00 0.00 Canceled 2018-04-30 nd planning ection al 3 0 5 3 2 2 6 0 9 ion des PAGDP (Firme intern ational) C 18-18/CN / Service de con Component 2: Investments sultant pour l'encadrement, Quality And Cost- 2018-09-1 2018-05-3 2018-06-1 2019-12-0 2018-07-1 2020-01-0 2018-07-2 2020-01-2 2018-09-0 2020-02-0 2018-09-2 2020-04-0 2019-04-2 IDA / 59790 and capacity building in the Post Open - National 50,000.00 22,725.03 Terminated 2018-05-09 formation et suivi des agent Based Selection 8 0 9 2 9 3 9 0 2 4 6 2 4 selected landscapes s communaux pour l'approc he LIFE C 24-18/CN / Etude de trait ement des points critiques d Component 2: Investments Quality And Cost- 2018-11-0 2018-06-0 2018-06-2 2018-12-2 2018-07-2 2019-01-2 2018-08-1 2019-02-1 2018-09-2 2019-02-2 2018-10-2 2019-03-0 2019-08-2 e la RN31 route non revêtue IDA / 59790 and capacity building in the Post Open - National 400,000.00 124,815.95 Signed 2018-05-14 Based Selection 6 4 8 7 8 8 7 5 1 5 6 6 2 reliant Bealanana-Ambatorih selected landscapes a d'une longueur de 32 km - Contrôle et surveillance C 12-18/CN / Etude et contr Component 3: Project Mana ôle-surveillance sur Les trav Quality And Cost- 2018-09-2 2018-06-0 2018-06-2 2018-10-3 2018-07-2 2018-12-0 2018-08-0 2019-02-1 2018-09-1 2019-02-1 2018-10-1 2019-02-2 2019-02-1 IDA / 59790 gement Coordination and M Post Open - National 21,000.00 24,935.50 Signed 2018-05-14 aux d'extension et de Réhab Based Selection 4 4 8 0 8 3 7 2 1 5 6 6 3 &E ilitation locaux Sofia C 15-18/CN / Etude et contr Component 3: Project Mana ôle-surveillance sur Les trav Quality And Cost- 2018-05-1 2018-06-0 2018-06-2 2018-06-1 2018-07-2 2018-07-1 2018-08-0 2018-08-3 2018-09-1 2018-10-0 2018-10-1 2018-11-1 2019-02-1 IDA / 59790 gement Coordination and M Post Open - National 10,500.00 3,669.43 Signed 2018-05-14 aux d'extension et de Réhab Based Selection 4 4 8 5 8 6 7 1 1 4 6 4 3 &E ilitation locaux Sava C 37-18/CN / Inventaire : s urfaces pâturables, espèces fourragères naturelles, point s d'abreuvement, infrastruct Component 1: Information a Quality And Cost- Under Implemen 2018-09-0 2018-08-0 2018-08-1 2018-11-2 2018-09-1 2018-09-2 2018-10-3 2018-12-0 2019-04-0 ures d'élevage existantes d IDA / 59790 Post Open - National 125,000.00 0.00 2018-07-12 nd planning Based Selection tation 5 2 6 6 5 5 0 4 3 ans la zone. Lot 01 : de Bealanana. Lot 02 : d'Andapa. Lot 03 : de Marovoay Lot 04 : d'Iazafo C 01BIS-18/CN / Développe Component 1: Information a Consultant Qualif Open - Internation 2018-05-2 2018-07-0 2018-08-0 2018-08-3 2018-11-2 ment d'un guide pour l'élabo IDA / 59790 Post 100,000.00 0.00 Canceled 2018-05-03 nd planning ication Selection al 4 7 6 0 8 ration des PAGDP (Firme int ernational) C 41-18/CN / Inventaire des périmètres hydroagricoles r Component 1: Information a Quality And Cost- 2018-09-0 2018-10-1 2018-11-1 2018-11-2 2018-12-1 2019-01-0 2018-12-2 2019-02-0 2019-01-2 2019-03-1 2019-02-2 2020-04-1 2019-06-2 2020-10-1 IDA / 59790 Post Open - National 230,000.00 155,001.04 Signed 2018-08-30 epartis en quatre (04) lots p nd planning Based Selection 4 4 7 1 7 4 7 1 0 4 4 6 4 6 our les régions : Sava, Boen y, Sofia et Analanjirofo. C 01-18/BOE / Recrutement d'une ONG chargée du renfo rcement de capacités et de l Component 2: Investments Quality And Cost- 2018-11-1 2018-12-1 2019-01-2 2018-12-0 2019-02-2 2019-03-0 2019-04-0 2019-05-1 2019-08-1 'appui des paysans pilotes s IDA / 59790 and capacity building in the Post Open - National 23,500.00 0.00 Canceled 2018-11-20 Based Selection 4 1 4 3 3 5 9 4 2 ur les paquets techniques d selected landscapes e la production fourragère, a groécologie, agroforesterie et arboriculture C 02-18/BOE / Recrutement d'une ONG ou Association c Component 2: Investments Quality And Cost- 2018-12-0 2018-12-1 2019-01-2 2019-02-0 2019-02-2 2019-03-0 2019-03-0 2019-03-2 2019-04-0 2019-04-1 2019-05-1 2019-05-0 2019-08-1 2019-10-1 hargée du diagnostic et redy IDA / 59790 and capacity building in the Post Open - National 5,200.00 5,702.82 Completed 2018-11-20 Based Selection 5 1 4 6 3 7 5 0 9 2 4 7 2 5 namisation des 03 Coopérati selected landscapes ves de producteurs de seme nces à Tsararano C 05-18/BOE / Etude spécifi Component 2: Investments que de protection des lavak Quality And Cost- 2019-07-0 2018-12-0 2018-12-2 2020-01-2 2019-01-2 2020-02-1 2019-02-1 2020-05-0 2019-03-0 2020-05-1 2019-03-2 2020-07-2 2019-04-2 IDA / 59790 and capacity building in the Post Open - National 47,000.00 77,973.66 Signed 2018-11-20 a au niveau des SBV Ambari Based Selection 8 5 7 8 6 2 0 4 2 9 6 8 5 selected landscapes ndahy, Androtra, Belafrika C 1-18/SAV / Amélioration d Component 2: Investments e la disponibilité de semenc Quality And Cost- 2019-01-0 2018-12-2 2019-02-0 2019-03-2 2019-03-0 2019-04-2 2019-03-1 2019-05-3 2019-04-1 2019-06-1 2019-05-2 2019-06-2 2019-07-0 2019-10-2 IDA / 59790 and capacity building in the Post Open - National 7,910.00 15,635.97 Completed 2018-11-30 es améliorées et certifiées d Based Selection 7 1 3 6 5 5 5 0 9 4 4 1 8 9 selected landscapes ans le paysage d'Andapa C 5-18/ANJ / Etude de rehab ilitation des infrasrtuctures hydroagricoles (APS-APD-EIE Component 2: Investments Quality And Cost- 2019-01-1 2018-12-1 2019-01-0 2019-01-2 2019-02-0 2019-02-2 2019-02-2 2019-03-0 2019-03-1 2019-03-1 2019-04-0 2019-03-2 2020-08-1 S-PAR-DAO-MGE) et surveilla IDA / 59790 and capacity building in the Post Open - National 79,200.00 46,026.84 Signed 2018-11-30 Based Selection 0 5 6 4 5 5 0 1 2 3 5 7 7 nce des travaux des périmèt selected landscapes res Marovinanto et Sahafary dans le paysage Soanierana Ivongo. C 02-18/SAV / Amélioration Component 2: Investments de la disponibilité de semen Quality And Cost- 2018-12-1 2019-01-2 2019-02-2 2019-03-1 2019-04-1 2019-05-1 2019-07-0 IDA / 59790 and capacity building in the Post Open - National 7,910.00 0.00 Canceled 2018-11-20 ces améliorées et certifiées Based Selection 1 4 3 0 4 9 3 selected landscapes dans le paysage d'Andapa C 01-19/SAV / Études de ré habilitation du barrage soupl e avec avant canal rive droit Component 2: Investments e et réfection des réseaux h Quality And Cost- 2018-12-1 2019-02-1 2019-03-0 2019-01-3 2019-04-0 2019-03-0 2019-04-1 2019-03-0 2019-04-2 2019-04-1 2019-05-1 2019-05-1 2020-12-1 IDA / 59790 and capacity building in the Post Open - National 45,500.00 67,478.28 Signed 2019-01-30 ydroagricoles, digue de prot Based Selection 1 4 2 1 1 4 5 9 7 7 7 7 2 selected landscapes ection et pistes (APS-APD-E IES-PAR-DAO-MGE) et contrô le - surveillance du périmètr e Ambalafary sur 203 ha et Analambe Est C 02-19/SAV / Études de ré habilitation du barrage en d ur avec avant canal rive droi Component 2: Investments te et renovation des réseaux Quality And Cost- 2019-01-1 2019-02-1 2019-03-0 2019-01-3 2019-04-0 2019-03-0 2019-04-1 2019-03-0 2019-04-2 2019-05-0 2019-05-1 2019-05-1 2020-12-1 IDA / 59790 and capacity building in the Post Open - National 72,220.00 37,620.86 Signed 2019-01-30 hydroagricoles et pistes (AP Based Selection 8 4 2 1 1 4 5 9 7 2 7 8 2 selected landscapes S-APD-EIES-PAR-DAO-MGE) et contrôle - surveillance du périmètre Ambodivitagnona sur 310ha, CR Ambalamana sy II, district d'Andap C 04-19/SAV / Études de ré habilitation d'un barrage av ec avant canal rive gauche et de réfection des réseaux Component 2: Investments Quality And Cost- 2019-01-2 2019-02-1 2019-03-0 2019-01-3 2019-04-0 2019-03-0 2019-04-1 2019-03-0 2019-04-2 2019-05-0 2019-05-1 2019-05-1 2020-12-1 hydroagricoles et les ouvrag IDA / 59790 and capacity building in the Post Open - National 63,500.00 64,941.59 Signed 2019-01-30 Based Selection 5 4 2 1 1 4 5 9 7 3 7 8 2 es connexes du grappe (APS selected landscapes -APD-EIES-PAR-DAO-MGE) et contrôle - surveillance du Pé rimètre Antanimbaribe et pé rimètre d'Ambatoharanan Page 7 C 05-19/SAV / Études de ré habilitation du barrage en d ur avec avant canal rive droi Component 2: Investments te et réfection des réseaux h Quality And Cost- 2019-01-2 2019-02-1 2019-03-0 2019-01-3 2019-04-0 2019-03-0 2019-04-1 2019-03-0 2019-04-2 2019-05-0 2019-05-1 2019-05-1 2020-12-1 IDA / 59790 and capacity building in the Post Open - National 94,470.00 45,623.17 Signed 2019-01-30 ydroagricoles (APS-APD-EIE Based Selection 5 4 2 1 1 4 5 9 7 3 7 8 2 selected landscapes S-PAR-DAO-MGE) et contrôle - surveillance du périmètre Tanandava sur 399ha CR Ta nandava, district d'Andapa C 08-19/SAV / Etude techni que et maitrise d'œuvre de t raitements et stabilisation d Component 2: Investments Quality And Cost- 2019-11-0 2019-03-1 2019-04-0 2019-12-1 2019-05-0 2020-01-1 2019-05-2 2020-03-0 2019-06-1 2020-05-0 2019-07-0 2020-06-2 2020-02-0 2021-06-2 es « lavaka » dans les ancie IDA / 59790 and capacity building in the Post Open - National 16,510.00 23,156.10 Completed 2019-02-11 Based Selection 4 3 6 2 6 3 6 5 9 7 9 0 4 4 nnes zones d'exploitation mi selected landscapes nières à Ankarierabe, Comm une Rurale Bealampona, Dis trict d'Andapa C 06-19/SAV / Création et m Component 2: Investments ise en place des huit (08) no Quality And Cost- 2019-09-1 2019-03-1 2019-04-0 2019-05-2 2019-05-0 2019-06-2 2019-05-2 2019-07-1 2019-06-2 2019-09-1 2019-07-1 2019-10-0 2020-07-0 2021-06-2 IDA / 59790 and capacity building in the Post Open - National 40,500.00 13,786.27 Completed 2019-02-12 uveaux AUE sur les périmètr Based Selection 3 4 7 9 7 8 7 7 0 6 0 3 4 4 selected landscapes es nouvellement à réhabilite r C 03-19/ANJ / Etude de reha bilitation des infrasrtuctures hydroagricoles (APS-APD-EIE Component 2: Investments Quality And Cost- 2019-02-0 2019-03-2 2019-04-1 2019-02-1 2019-05-1 2019-03-1 2019-05-2 2019-03-2 2019-06-1 2019-03-2 2019-07-1 2019-04-2 2021-02-2 2022-04-2 S-PAR-DAO-MGE) et Contrôl IDA / 59790 and capacity building in the Post Open - National 207,200.00 54,623.16 Signed 2019-02-20 Based Selection 8 2 3 4 3 8 8 2 7 8 1 4 0 3 e-surveillance des travaux d selected landscapes ans les périmètres de Vohiji ny et Ampasimbola-District de Soanierana Ivongo C 04-19/ANJ / Recrutement de firme pour la capitalisatio n des acquis sur les paquets Component 2: Investments Quality And Cost- 2019-02-0 2019-03-2 2019-04-1 2019-06-0 2019-05-1 2019-07-0 2019-05-2 2019-08-1 2019-06-1 2019-08-2 2019-07-1 2019-09-2 2022-10-2 techniques agroécologique, IDA / 59790 and capacity building in the Post Open - National 55,500.00 65,328.45 Signed 2019-02-20 Based Selection 8 2 3 6 3 8 8 3 7 3 1 2 3 agroforesterie, arbiriculture selected landscapes et culture fourragère dans le s paysages d'Iazafo et Soani erana Ivongo C 01-19/BOE / Recrutement Component 2: Investments d'une ONG chargée des étu Quality And Cost- 2019-02-1 2019-03-2 2019-04-1 2019-04-2 2019-05-1 2019-05-2 2019-06-0 2019-06-1 2019-07-0 2019-06-1 2019-07-2 2019-10-1 COFN / C1540 and capacity building in the Post Open - National 16,090.00 0.00 Signed 2019-02-24 des de diagnostic des AUE Based Selection 8 6 9 6 9 8 3 2 2 8 7 0 selected landscapes dans les secteurs 04, 05 et 06 C 02-19/BOE / Recrutement d'une ONG chargée de l'étu Component 2: Investments de de stabilisation des zone Quality And Cost- 2019-02-1 2019-03-2 2019-04-1 2019-04-1 2019-05-1 2019-05-1 2019-06-0 2019-05-2 2019-06-2 2019-06-0 2019-07-1 2019-06-2 2019-10-2 COFN / C1540 and capacity building in the Post Open - National 10,000.00 7,934.21 Signed 2019-02-24 s d'érosion et protection des Based Selection 8 6 7 5 7 4 1 9 1 6 5 1 3 selected landscapes réseaux hydroagricoles le lo ng du CPRD et CSPC Ambolo moty (ONG) C 03-19/BOE / Etudes, contr Component 2: Investments ôle et surveillance des trava Quality And Cost- 2018-12-1 2019-03-2 2019-04-1 2019-02-1 2019-05-1 2019-03-1 2019-06-0 2019-04-1 2019-06-2 2019-04-2 2019-07-1 2019-05-0 2021-01-2 COFN / C1540 and capacity building in the Post Open - National 26,000.00 20,616.05 Signed 2019-02-24 ux de curage du drain de cei Based Selection 8 6 7 9 7 9 1 2 1 4 5 9 5 selected landscapes nture et reprofilage du drain naturel Manompo C 04-19/BOE / Etudes des tr Component 2: Investments Quality And Cost- 2019-03-0 2019-03-2 2019-04-1 2019-02-2 2019-05-1 2019-04-0 2019-06-0 2019-04-0 2019-06-2 2019-04-3 2019-07-1 2019-06-0 2021-01-2 avaux de reprofilage des rés COFN / C1540 and capacity building in the Post Open - National 52,500.00 69,283.53 Signed 2019-02-24 Based Selection 3 6 7 8 7 1 1 9 1 0 5 6 5 eaux de drainage des secte selected landscapes urs 04, 05 et 06 C 16-18/CN / Analyse des pr oblématiques d'entretien de Component 1: Information a Consultant Qualif 2018-10-0 2018-08-0 2018-09-1 2018-11-3 2018-10-2 2018-11-1 2019-02-2 IDA / 59790 Post Open - National 30,000.00 0.00 Canceled 2018-06-28 s ouvrages hydroagricoles, p nd planning ication Selection 8 7 0 0 0 3 1 roposition d'instruments et s tratégies C 01-19/CN / Élaboration du Plans d'Aménagement et de Gestion Durable des Paysag es (PAGDP) du PADAP pour l e: Component 1: Information a Quality And Cost- Open - Internation 2019-05-0 2019-05-1 2019-06-0 2019-05-2 2019-07-1 2019-07-0 2019-08-0 2019-07-1 2019-08-3 2019-08-1 2019-10-0 2019-09-2 2020-02-2 COFN / C1540 Post 967,463.00 1,014,833.73 Signed 2019-03-29 Lot 01 : Paysage d'Andapa nd planning Based Selection al 1 3 2 5 7 8 1 9 1 6 1 6 8 Lot 02 : Paysage de Bealala na Lot 03 : Paysage de Marovo ay Lot 04 : Paysage d'Iazafo Lot 05 : Paysage de Soanier Ivongo / Développeme C 29-18/CN ana nt d'une méthodologie d'inv Component 1: Information a Quality And Cost- 2018-09-2 2018-10-1 2018-11-1 2018-12-1 2018-12-2 2019-01-2 2019-02-2 2019-06-2 IDA / 59790 Post Open - National 25,000.00 0.00 Canceled 2018-08-30 entaire des ressources en e nd planning Based Selection 6 4 7 7 7 0 4 4 au et estimation des besoins C 04 BIS-18/BOE / Etudes et contrôle-surveillance des tra Component 2: Investments vaux de regabaritage des co Quality And Cost- 2019-03-0 2018-12-2 2019-02-0 2018-12-0 2019-03-0 2019-01-0 2019-04-0 2019-02-2 2019-05-0 2019-02-2 2019-06-1 2019-03-2 2020-06-1 COFN / C1540 and capacity building in the Post Open - National 145,000.00 90,071.60 Signed 2018-11-21 urs d'eau exutoire du draina Based Selection 3 1 3 7 5 7 4 0 9 5 3 2 2 selected landscapes ge de périmètre irrigué des secteurs 4, 5 et 6 de la plain e de Marovoay. C 04-18/BOE / Etudes de Ré Component 2: Investments habilitation des cours d'eau Quality And Cost- 2018-11-2 2018-12-1 2019-01-0 2019-02-0 2019-02-1 2019-03-2 2019-04-2 2019-12-1 IDA / 59790 and capacity building in the Post Open - National 62,500.00 0.00 Canceled 2018-11-20 exutoire du drainage (Rivièr Based Selection 1 1 4 3 3 0 4 0 selected landscapes e Marovoay Aval, Rivière Kar ambo Aval) MG-UGP PADAP-117841-CS- Component 3: Project Mana QCBS / Agence de communi Quality And Cost- 2019-04-1 2019-07-0 2019-08-2 2019-05-2 2019-09-2 2019-10-0 2019-10-1 2019-11-0 2019-11-0 2019-12-0 2019-11-2 2020-01-0 2020-01-2 COFN / C1540 gement Coordination and M Post Open - National 28,500.00 20,587.41 Signed 2019-06-17 cation pour la création, anim Based Selection 0 8 1 3 0 2 0 6 3 3 7 1 6 &E ation et l'hébergement du si te web du PADAP. MG-UGP PADAP-118799-CS- Component 3: Project Mana LCS / Recrutement d'un cabi Least Cost Select 2019-06-2 2019-06-2 2019-06-2 2019-08-2 2019-07-2 2019-09-3 2019-08-0 2019-10-0 2019-08-2 2019-10-2 2019-10-0 2019-12-2 2020-01-0 COFN / C1540 gement Coordination and M Post Open - National 75,000.00 17,544.75 Signed 2019-06-20 net pour l'audit externe des ion 7 0 2 9 2 0 6 4 1 1 4 8 2 &E trois (03) exercices du PADA P : 2019, 2020 et 2021. C 01 BIS-18/BOE / Recrute ment d'une ONG chargée du renforcement de capacités e Component 2: Investments Quality And Cost- 2018-10-0 2018-12-0 2019-01-1 2018-12-0 2019-02-1 2019-01-0 2019-03-1 2019-01-2 2019-04-2 2019-01-3 2019-05-2 2019-02-1 2020-05-2 t de l'appui des paysans pilo COFN / C1540 and capacity building in the Post Open - National 70,500.00 49,883.77 Signed 2018-11-14 Based Selection 8 5 8 3 5 3 7 4 1 1 6 1 5 tes sur les paquets techniqu selected landscapes es de la production fourragè re, agroécologie, agroforest erie et arboriculture C 03-19/SAV / Etudes APS-A PD-EIES-PAR-MGE-DAO-assis tance passation de marché et contrôle-surveillance des Component 2: Investments Quality And Cost- 2019-01-2 2019-02-1 2019-03-0 2019-01-3 2019-04-0 2019-03-0 2019-04-1 2019-03-0 2019-04-2 2019-04-1 2019-05-1 2019-05-1 2020-12-1 travaux reconstruction des d IDA / 59790 and capacity building in the Post Open - National 47,000.00 46,114.62 Signed 2019-01-30 Based Selection 5 4 2 1 1 4 5 9 7 9 7 8 2 eux barrages avec avant-ca selected landscapes naux rive gauche & droite et des réseaux hydroagricoles d'Antsahameloka pour les PI Ambodiala et Andalamena. C 16 BIS-18/CN / Analyse de s problématiques d’entretie Component 2: Investments Quality And Cost- 2018-11-0 2018-12-2 2019-01-2 2019-02-1 2019-03-2 2019-04-3 2019-08-0 n des ouvrages hydroagricol COFN / C1540 and capacity building in the Post Open - National 30,000.00 0.00 Canceled 2018-10-08 Based Selection 7 1 0 9 6 0 8 es à Madagascar, propositio selected landscapes n d’instrument et stratégies C 07-19/SAV / Mise en place des douze (12) pépinières c Component 2: Investments Quality And Cost- 2019-04-1 2019-03-2 2019-04-1 2019-05-1 2019-06-0 2019-06-2 2019-07-1 2020-03-1 ommunautaires au niveau d IDA / 59790 and capacity building in the Post Open - National 37,490.00 0.00 Canceled 2019-02-20 Based Selection 2 2 5 5 4 8 8 4 es villages et des COBAS aut selected landscapes our des aires protegées de l a cuvette d'Andapa C 07-20/SOF / Contrôle et S Component 2: Investments urveillance des Travaux de r Quality And Cost- 2020-04-0 2020-03-0 2020-04-0 2020-04-3 2020-05-0 2020-06-0 2020-06-0 2020-07-2 2020-06-2 2020-08-0 2020-07-2 2020-09-1 2020-08-0 COFN / C1540 and capacity building in the Post Open - National 24,000.00 13,580.72 Signed 2020-02-28 éhabilitation du Périmètre d' Based Selection 2 9 2 0 2 2 1 1 6 1 1 1 5 selected landscapes Anjohibe Ambatosia dans le Paysage de Bealanana C 02-20/SAV / Etude de fais abilité, mise en place et opé Component 2: Investments Quality And Cost- 2020-05-2 2020-03-1 2020-04-2 2020-09-1 2020-05-2 2020-10-1 2020-06-1 2020-11-2 2020-07-1 2020-12-1 2020-08-2 2020-12-2 2020-10-2 2021-08-1 rationnalisation des comités COFN / C1540 and capacity building in the Post Open - National 10,500.00 10,290.96 Completed 2020-02-28 Based Selection 9 3 6 5 6 9 5 3 9 1 3 4 2 9 de gestion des matériels agr selected landscapes icoles dans le paysage d'An dapa, Région SAVA. C 04-19/SOF / Études, contr Component 2: Investments ôle et surveillance de travau Quality And Cost- 2019-10-0 2020-03-0 2020-04-0 2019-10-0 2020-05-0 2019-11-0 2020-05-2 2020-01-2 2020-06-2 2020-02-2 2020-07-2 2020-03-1 2020-12-2 COFN / C1540 and capacity building in the Post Open - National 41,000.00 18,719.00 Signed 2020-02-20 x d'aménagement du périm Based Selection 4 1 5 4 5 6 5 3 4 8 4 9 1 selected landscapes ètre de Doany,Paysage de B ealanana T 1-18/SOF / Travaux de sta bilisation biologique des lav Component 1: Information a Quality And Cost- 2018-12-1 2019-01-0 2019-02-0 2019-02-2 2019-03-1 2019-04-0 2019-05-0 IDA / 59790 Post Open - National 9,800.00 0.00 Canceled 2018-11-30 aka avec mise en place de f nd planning Based Selection 5 6 5 0 2 5 5 ascines dans le sous paysag e d'Ambatoriha MG-UGP PADAP-118793-CS- QCBS / Inventaire forestier e t écologique : - Lot 01: dans le paysage d' Andapa Component 1: Information a Quality And Cost- 2019-07-1 2019-08-1 2019-09-1 2019-09-2 2019-10-1 2019-11-2 2020-03-1 - Lot 02 : dans le paysage d COFN / C1540 Post Open - National 365,000.00 0.00 Canceled 2019-06-12 nd planning Based Selection 2 1 0 5 5 0 9 e Bealalana - Lot 03 : dans le paysage d e Marovoay - Lot 04 : dans le paysage S onierana Ivongo et Iazafo MG-UGP PADAP-117852-CS- QCBS / Un cabinet spécialisé Component 3: Project Mana Quality And Cost- 2019-06-2 2019-07-1 2019-08-1 2019-09-0 2019-09-3 2019-10-2 2019-12-2 en communication en vue d COFN / C1540 gement Coordination and M Post Open - National 22,900.00 0.00 Canceled 2019-06-03 Based Selection 4 8 7 6 0 4 3 e la réalisation du film docu &E mentaire sur le PADAP et le PAGDP. C 09-18/ANJ / Recrutement d'agence d'encadrement po ur la communauté locale fai Component 2: Investments Quality And Cost- 2019-11-1 2019-12-0 2020-01-0 2020-01-2 2020-04-0 2020-05-0 2022-05-0 sant la création pépinière et COFN / C1540 and capacity building in the Post Open - National 85,000.00 0.00 Canceled 2019-10-16 Based Selection 5 7 6 1 1 8 8 la Plantation d'espèces pére selected landscapes nnes par les agro forêts et le s espèces forestières à Iazaf o et Soanierana Ivongo. C 06-19/ANJ / Mise en place/ Component 2: Investments Actualisation de base des do Quality And Cost- 2019-05-3 2019-06-2 2019-07-2 2019-08-0 2019-08-2 2019-09-1 2019-12-2 IDA / 59790 and capacity building in the Post Open - National 37,500.00 0.00 Canceled 2019-04-30 nnées sur les référentiels te Based Selection 0 1 1 5 5 8 7 selected landscapes chnico financiers des filières porteuses régionales C 02-19/ANJ / Formation de Component 2: Investments tous les membres des AUEs Quality And Cost- 2019-09-0 2019-06-3 2019-07-2 2019-08-2 2019-09-0 2019-10-0 2019-10-3 2020-01-2 IDA / 59790 and capacity building in the Post Open - National 56,100.00 0.00 Canceled 2019-05-31 sur la gestion des réseaux tr Based Selection 2 0 4 3 7 6 1 9 selected landscapes ansférables (Entretien/Maint enance) C 03-20/BOE / Diagnostic d es banques de semences co Component 2: Investments mmunautaires à Madagasca Quality And Cost- 2020-02-1 2020-06-1 2020-08-0 2020-05-1 2020-08-3 2020-06-1 2020-09-2 2020-06-3 2020-10-2 2020-08-1 2020-11-2 2020-09-1 2021-08-2 COFN / C1540 and capacity building in the Post Open - National 20,000.00 11,848.65 Signed 2020-05-26 r et redynamisation de la ba Based Selection 0 0 1 5 1 5 0 0 0 8 3 8 3 selected landscapes nque de semence communa utaire à Tsararano, district d e Marovoay, Région Boeny C 03-19/SOF / Etudes et con Component 2: Investments trôle et surveillance de trav Quality And Cost- 2021-03-2 2021-04-1 2021-05-1 2021-06-0 2021-06-2 2021-07-1 2022-11-1 COFN / C1540 and capacity building in the Post Open - National 27,810.00 0.00 Canceled 2021-02-25 aux de construction du centr Based Selection 7 8 8 2 2 6 8 selected landscapes e de multiplication de seme nces à Betainkankana C 08-20/SOF / étude de fais abilité de la réouverture du Component 2: Investments Quality And Cost- 2020-03-2 2020-05-0 2020-06-0 2020-06-2 2020-07-1 2020-08-0 2020-11-0 centre de sélection variétale COFN / C1540 and capacity building in the Post Open - National 52,000.00 0.00 Canceled 2020-02-28 Based Selection 9 8 7 2 2 6 4 et de multiplication de seme selected landscapes nces Betaikankana dans le P aysage de Bealanana Page 8 C 30-20/SOF / Recrutement d'un Bureau d'études pour l Component 2: Investments Quality And Cost- 2020-11-2 2020-10-2 2020-12-0 2020-11-3 2021-01-0 2021-01-2 2021-01-3 2021-02-2 2021-03-0 2021-03-2 2021-04-1 2021-04-1 2022-04-1 a réalisation d'études, contr COFN / C1540 and capacity building in the Post Open - National 66,500.00 121,048.69 Signed 2020-09-30 Based Selection 5 1 4 0 1 0 1 6 7 2 1 3 1 ôle et surveillance des trava selected landscapes ux des travaux d'aménage ment PI Beandrarezona (567 ha) C 05/19/SOF / Etudes et con Component 2: Investments Quality And Cost- 2019-07-0 2019-06-2 2019-07-2 2019-10-2 2019-08-2 2020-01-2 2019-09-0 2020-02-2 2019-09-2 2019-10-1 2019-12-1 trôle et surveillance de trav COFN / C1540 and capacity building in the Post Open - National 58,590.00 0.00 Canceled 2019-05-30 Based Selection 8 9 1 1 0 2 4 1 4 8 7 aux de stabilisation de lavak selected landscapes a à Bealanana C 01-20/SAV / Elaboration c ontrat plan pluriannuel et Ac Component 2: Investments Quality And Cost- 2020-08-3 2020-09-1 2020-10-1 2020-10-2 2020-11-2 2020-12-3 2022-06-2 compagnement (Encadreme COFN / C1540 and capacity building in the Post Open - National 29,690.00 0.00 Canceled 2020-08-31 Based Selection 1 0 1 1 5 0 3 nt et Suivi) des AUEs sur la selected landscapes mise en œuvre des Contrat Plan C 02-20/ANJ / Etudes et Con trôle-Surveillance des travau x de réhabilitation des périm Component 2: Investments ètres dans le district de Soa Quality And Cost- Under Implemen 2020-11-2 2020-10-3 2020-12-0 2020-12-0 2021-01-0 2021-01-1 2021-01-2 2021-02-1 2021-02-2 2021-04-0 2022-04-0 COFN / C1540 and capacity building in the Post Open - National 91,000.00 0.00 2020-09-30 nierana Ivongo Based Selection tation 5 0 3 7 2 2 2 5 6 2 2 selected landscapes - Lot 01: PI d'Antanetilava et Vohilava - Lot 02: PI de Diavolamaso, Ambodiboanara et Sahondra na C 06-20/SOF / Etude, Contrô le et surveillance des travau Component 2: Investments Quality And Cost- 2020-09-3 2020-11-0 2020-12-0 2020-12-2 2021-01-1 2021-02-2 2021-06-2 x de réhabilitation (APD-EIES COFN / C1540 and capacity building in the Post Open - National 187,500.00 0.00 Canceled 2020-08-31 Based Selection 0 4 4 4 8 3 3 -PAR-DAO-MGE) du Périmètr selected landscapes e de Beandrarezona dans le paysage de Bealanana C 04-20/BOE / Recrutement Component 2: Investments d'une firme pour l'appui, enc Quality And Cost- 2020-10-0 2020-11-0 2020-12-0 2020-12-2 2021-01-3 2021-02-2 2022-02-2 COFN / C1540 and capacity building in the Post Open - National 125,000.00 0.00 Canceled 2020-09-18 adrement et réalisation des Based Selection 3 8 9 9 1 5 5 selected landscapes actions de reboisement C 04-20/SAV / Etude, contrô le et surveillance des travau x de réhabilitation : Lot 1 : Périmètre irrigué Ank Component 2: Investments aibe Quality And Cost- 2020-11-2 2020-12-2 2021-02-0 2020-12-2 2021-03-0 2021-01-2 2021-03-2 2021-02-2 2021-04-2 2021-04-0 2021-06-0 2021-05-0 2022-06-0 COFN / C1540 and capacity building in the Post Open - National 481,350.00 297,378.67 Signed 2020-11-30 Lot 2 : Périmètre Andasibe Based Selection 5 1 3 1 5 0 5 6 9 1 3 1 3 selected landscapes Mahaverika , Ambodipont, A ntsahanibalana Lot 3 : Périmètre Ambodirafi a I, Ambodirafia II, Antsahab e, Ambavala, Andasibe koba hina C 1-20/CN / Service de cons Component 3: Project Mana ultant pour l'évaluation à mi Consultant Qualif 2020-10-1 2020-12-1 2021-01-2 2020-10-2 2021-02-2 2020-11-3 2021-04-0 2021-02-0 2021-09-2 COFN / C1540 gement Coordination and M Post Open - National 18,750.00 54,171.09 Signed 2020-11-23 -parcours du Projet Agricultu ication Selection 6 4 7 6 6 0 2 3 9 &E re Durable par une Approch e Paysage C 14-20/SOF / Études, contr ôle et surveillance des trava ux de réhabilitation: Lot 01: Périmètre Irrigué Sa hatsara Ambalamanga Component 2: Investments Quality And Cost- 2020-12-1 2021-01-1 2021-02-1 2020-12-2 2021-03-1 2021-01-2 2021-03-1 2021-02-1 2021-04-0 2021-03-2 2021-04-2 2021-04-2 2022-04-2 Lot 02: Périmètre Irrigué Sa COFN / C1540 and capacity building in the Post Open - National 375,000.00 54,443.56 Signed 2020-12-28 Based Selection 8 7 3 1 5 0 5 2 1 2 1 0 1 hatsara Ouest selected landscapes Lot 03 : Périmètre Irrigué A mbovonomby Lot 04: Périmètre Irrigué Ma nakana-Antelopolo. C 09-20/SAV / Etudes, contr ôle- surveillance des travaux de réhabilitation des pistes: Lot 1: axe Matsobe Andrano Component 2: Investments Quality And Cost- 2020-12-2 2021-01-1 2021-02-0 2020-12-3 2021-03-1 2021-02-0 2021-03-3 2021-02-2 2021-05-0 2021-04-0 2021-06-0 2021-05-1 2021-09-2 2022-05-0 mena Ambalamanasy II de 2 COFN / C1540 and capacity building in the Post Open - National 161,130.00 210,652.81 Signed 2020-12-21 Based Selection 3 1 9 1 1 2 1 6 5 2 9 3 7 8 5 km et réhabilitation de 8 selected landscapes Ponts Lot 2: axe Belaoko, Anjavibe , Ambodirafia, Antanimbarib e Ambalamanasy, Ambavala , Ambodivohitra C 09-20/BOE / ETUDES APS- APD-EIES-PAR- MGE- DAO-A SSISTANCE A LA PASSATION Component 2: Investments DE MARCHE ET CONTROLE-S Quality And Cost- 2021-02-0 2020-12-2 2021-02-1 2020-12-2 2021-03-1 2021-01-2 2021-04-1 2021-01-1 2021-05-1 2021-02-2 2021-06-1 2021-03-2 2022-03-0 COFN / C1540 and capacity building in the Post Open - National 150,000.00 186,693.24 Signed 2020-12-08 URVEILLANCE DES TRAVAUX Based Selection 4 9 1 3 1 2 0 2 5 4 9 4 1 selected landscapes DE REVETEMENT EN BETON ARME DES CANAUX PRINCIP AUX (CPRD ET CPRG) DES P ERIMETRES IRRIGUES SECTE URS 04, 05 ET 06 C 01-20/CN / Service de con Component 3: Project Mana sultant pour l'évaluation à m Quality And Cost- 2020-10-1 2020-03-2 2020-04-2 2020-05-2 2020-06-0 2020-06-2 2020-07-1 2020-10-1 COFN / C1540 gement Coordination and M Post Open - National 18,750.00 0.00 Canceled 2020-02-28 i-parcours du Projet Agricult Based Selection 6 9 0 0 4 4 8 6 &E ure Durable par une Approc he Paysage C 15-20/SOF / Recrutement d'un bureau d'études pour l a réalisation d'études, contr Component 2: Investments ôle et surveillance des trava Quality And Cost- 2020-11-2 2021-01-2 2021-02-2 2020-12-2 2021-03-2 2021-01-2 2021-04-2 2021-02-1 2021-05-1 2021-04-1 2021-05-3 2021-05-0 2022-05-3 COFN / C1540 and capacity building in the Post Open - National 270,000.00 87,027.34 Signed 2021-01-06 ux d’extension du réseau d’i Based Selection 7 6 2 1 4 0 3 9 0 4 0 4 0 selected landscapes rrigation du périmètre d'Am balavelona Antsamaka Com mune Rurale Antsamaka, du paysage de Belanana C 18-20/SOF / Recrutement d'un Bureau d'études pour l a réalisation d'études, contr ôle et surveillance des trava Component 2: Investments Quality And Cost- 2020-12-1 2021-01-2 2021-02-2 2020-12-2 2021-03-2 2021-01-2 2021-04-2 2021-02-1 2021-05-1 2021-03-2 2021-05-3 2021-04-2 2022-05-3 ux d'aménagement : COFN / C1540 and capacity building in the Post Open - National 622,000.00 112,115.98 Signed 2021-01-06 Based Selection 8 6 2 1 4 0 3 2 0 2 0 0 0 LOT 01: Périmètre irrigué A selected landscapes mbararatabe Nord Ambahiv ahy Mahatsinjo - LOT 02 Péri mètre Irrigué Nord Ouest A mbahivahy Ambararatabe N ord C 01-21/CN / Prestation de la communication (relecture Component 3: Project Mana , de synthèse, de reprograp Consultant Qualif 2021-01-2 2021-02-1 2021-03-2 2021-04-0 2021-04-1 2021-05-2 2021-05-1 2021-06-0 2021-07-0 COFN / C1540 gement Coordination and M Post Open - National 90,000.00 115,715.44 Signed 2021-01-29 hie et de plaidoyer instituion ication Selection 2 9 5 1 4 1 3 1 2 &E nel) autour des Plans d'Amé nagement et de Gestion Dur able des Paysages (PAGDP). C 01-19/SOF / ONG ou Asso Component 2: Investments Quality And Cost- 2020-05-3 2020-06-2 2020-07-2 2020-08-1 2020-09-2 2020-10-2 2021-01-2 ciation pour le renouvelleme COFN / C1540 and capacity building in the Post Open - National 32,120.00 0.00 Canceled 2020-04-30 Based Selection 0 9 9 8 1 0 8 nt des contrats de transfert selected landscapes gestion. C 11-20/BOE / Recrutement d'une firme pour l'étude de f Component 2: Investments aisabilité de la mise en plac Quality And Cost- 2021-01-0 2021-03-1 2021-04-2 2021-02-1 2021-05-2 2021-03-1 2021-06-2 2021-06-0 2021-07-2 2021-07-0 2021-08-2 2021-07-2 2021-12-2 COFN / C1540 and capacity building in the Post Open - National 9,400.00 9,165.71 Signed 2021-02-17 e et formalisation de comité Based Selection 8 0 3 8 1 9 0 8 5 8 9 1 7 selected landscapes de gestion de matériels agri coles dans le paysage de Ma rovoay C 05-19/BOE / Recrutement d'une firme chargée de la re Component 2: Investments Quality And Cost- 2021-03-2 2021-03-2 2021-04-2 2020-12-1 2021-05-2 2021-01-1 2021-06-1 2021-04-1 2021-07-1 2021-04-2 2021-08-1 2021-05-1 2022-06-1 dynamisation et à l'élaborati COFN / C1540 and capacity building in the Post Open - National 95,000.00 135,810.28 Signed 2021-03-05 Based Selection 6 1 5 1 5 2 4 4 4 8 2 1 1 on des contrats-plans pluri-a selected landscapes nnuels des AUE dans les sec teurs 4-5-6 de Marovoay C 06-20/BOE / Etudes, contr ôle et surveillance des trava ux de réhabilitation des pist es reliant le Chef-lieu de la c Component 2: Investments ommune Ambolomoty à la R Quality And Cost- 2021-03-2 2021-03-3 2021-05-1 2020-12-2 2021-06-1 2021-01-2 2021-07-1 2021-03-1 2021-08-1 2021-03-2 2021-09-1 2021-04-2 2022-04-0 COFN / C1540 and capacity building in the Post Open - National 106,000.00 165,601.53 Signed 2021-03-10 N4 Based Selection 5 1 4 8 1 6 1 2 5 6 9 0 2 selected landscapes Lot 1 Piste Ambolomoty – M arosakoa répartis en 2 lots Lot 2 Piste Ampizaramaso – Maintimaso – Tsiandrarafa – Chantier Sinoa" C 05-20/ANJ / Recrutement d'un Bureau d'Etude pour ét Component 2: Investments udes, contrôle et surveillanc Quality And Cost- 2022-07-2 2021-07-1 2021-08-2 2021-09-2 2021-10-1 2021-11-1 2021-12-0 2022-12-0 COFN / C1540 and capacity building in the Post Open - National 15,200.00 0.00 Canceled 2021-06-25 e des travaux de constructio Based Selection 8 6 9 8 8 1 6 6 selected landscapes n de bâtiment à usage de ba nque de semence à Iazafo e t Soanierana Ivongo. C 01-21/SAV / Recrutement d'une firme spécialisée pour la création, formalisation, co Component 2: Investments nduite des formations, suivi Consultant Qualif 2021-06-3 2021-05-2 2021-06-2 2021-08-1 2021-07-1 2021-10-2 2021-07-1 2021-11-2 2022-07-1 COFN / C1540 and capacity building in the Post Open - National 55,260.00 98,488.84 Signed 2021-05-21 et encadrement , accompag ication Selection 0 1 7 9 1 0 6 4 6 selected landscapes nement à l'élaboration des c ontrats plans pluriannuels d es AUEs et le recensement p arcellaire des périmètres irri gués à Andapa. C 02-19/SOF / Élaboration d Component 2: Investments Quality And Cost- 2020-10-3 2020-11-2 2020-12-2 2021-01-0 2021-02-0 2021-03-0 2021-06-1 'un cadre incitatif (Contrat Pl COFN / C1540 and capacity building in the Post Open - National 56,250.00 0.00 Canceled 2020-09-30 Based Selection 0 3 3 7 5 2 0 an Pluriannuel) par AUE selected landscapes C 17-20/SOF / Recrutement d'un Bureau d'études pour l a réalisation d'études, contr Component 2: Investments ôle et surveillance de la mis Quality And Cost- 2021-01-2 2021-02-2 2021-03-2 2021-04-2 2021-05-1 2021-06-0 2022-06-0 IDA / 59790 and capacity building in the Post Open - National 195,000.00 0.00 Canceled 2021-01-06 e en œuvre : LOT 01: Travau Based Selection 6 2 2 1 6 5 5 selected landscapes x Piste Ambatosia-Anjohibe LOT 02: travaux de réhabilit ation d'un ouvrage de franc hissement "pont Andranotak atra" C 03-20/SOF / Recrutement d'une ONG ou association e n vue de l’Élaboration des sc hémas d'aménagement com Component 2: Investments Quality And Cost- 2021-03-2 2021-05-0 2021-06-0 2021-07-0 2021-08-0 2021-09-1 2022-05-1 munaux (SAC) dans la distri COFN / C1540 and capacity building in the Post Open - National 252,000.00 0.00 Canceled 2021-03-01 Based Selection 2 5 2 2 6 0 8 ct de Bealalana repartis en selected landscapes 03 lots: Lot 01: 06 communes Lot 02 : 05 communes Lot 03: 03 communes C 19-20/SOF / Recrutement ONG en vue de l'élaboration des contrats plans pluriannu els des AUE pour les périmèt Component 2: Investments Quality And Cost- 2021-06-1 2021-08-1 2021-09-1 2021-06-1 2021-10-1 2021-07-1 2021-11-0 2021-10-0 2021-12-0 2021-10-1 2022-01-0 2021-10-3 2022-11-0 res de : Mangindrano, Beala COFN / C1540 and capacity building in the Post Open - National 240,000.00 41,315.90 Signed 2021-07-30 Based Selection 7 5 9 9 9 9 8 6 8 1 6 1 2 nana I, Beandrarezona, Anjo selected landscapes hibe, Ambalavelona, Anjana borona, Sahatsara Anjanabo rona, Ambahivahy, Nord-Ou est Ambahivahy, Ambovono mby C 21-20/SOF / Recrutement d'un Bureau d'études pour l a réalisation d'études, contr Component 2: Investments Quality And Cost- 2020-12-1 2021-01-1 2021-02-1 2021-03-1 2021-04-1 2021-05-0 2021-05-2 2022-05-2 ôle et surveillance de la mis IDA / 59790 and capacity building in the Post Open - National 220,000.00 0.00 Canceled 2021-01-06 Based Selection 8 6 2 2 1 8 5 5 e en œuvre des travaux pou selected landscapes r amélioration de la voie d'a ccès ralliant Ambatoriha Est- Ambararatabe Nord C 05-20/SAV / Recrutement d'une firme pour la diffusion Component 2: Investments d'itinéraire technique agricol Quality And Cost- 2021-05-1 2021-06-2 2021-07-2 2021-08-1 2021-08-2 2021-09-1 2022-07-3 COFN / C1540 and capacity building in the Post Open - National 542,000.00 0.00 Canceled 2021-04-30 e et la promotion de l'éleva Based Selection 8 2 2 1 8 7 0 selected landscapes ge intensif du paysage d'An dapa, district d'Andapa, Rég ion SAVA Page 9 C 07-20/ANJ / Etudes et Con trôle-Surveillance des travau x de réhabilitation des périm Component 2: Investments Quality And Cost- Under Implemen 2020-12-1 2021-09-1 2021-10-2 2020-12-3 2021-11-2 2021-02-0 2021-12-1 2021-03-2 2022-01-1 2021-04-1 2022-02-2 2023-02-2 ètres dans le District de Soa COFN / C1540 and capacity building in the Post Open - National 153,000.00 0.00 2021-08-20 Based Selection tation 0 0 4 1 3 3 3 2 7 2 1 1 nierana Ivongo:Lot 01:PI Tsa selected landscapes ratanàna,Namantoana et Sa hasoa;Lot 02:PI Ambatonand roka,Vaniaraka et Antanetila va C 19-20/ANJ / Etudes,Contrô le et surveillance des travau x de réhabilitation des piste Component 2: Investments s à Iazafo et Soanierana Ivo Quality And Cost- 2021-05-1 2021-09-2 2021-10-1 2021-01-1 2021-11-1 2021-02-1 2021-11-2 2021-03-2 2021-12-1 2021-04-0 2022-01-1 2021-05-1 2023-01-1 COFN / C1540 and capacity building in the Post Open - National 283,500.00 126,545.83 Signed 2021-08-25 ngo:Lot 01:Antanifotsy à Ma Based Selection 2 4 9 9 8 8 8 2 8 6 2 5 2 selected landscapes rovinanto;Lot 02:Maromitety à Mahanoro,Maromitety à V avazahana,Marofototra à Ma hanoro et Ambodinonoka à Mahatera. C 04-20/ANJ / Recrutement de firme pour l'instauration Component 2: Investments et la formalisation de neuf ( Quality And Cost- 2020-11-0 2021-09-2 2021-11-0 2020-12-0 2021-12-0 2021-01-1 2021-12-2 2021-02-2 2022-01-2 2021-03-1 2022-03-0 2021-04-0 2022-05-3 COFN / C1540 and capacity building in the Post Open - National 12,000.00 10,179.28 Signed 2021-08-30 09) comités de gestion des Based Selection 4 9 2 4 2 4 2 4 6 8 2 5 1 selected landscapes matériels agricole dans le p aysage d'Iazafo et Soaniera na Ivongo C 16-20/ANJ / Etudes et Con trôle-Surveillance des travau x de réhabilitation des barra Component 2: Investments Quality And Cost- 2020-12-1 2021-09-2 2021-11-0 2020-12-2 2021-12-0 2021-01-2 2021-12-3 2021-02-2 2022-02-0 2021-03-2 2022-03-1 2021-04-2 2023-03-1 ges et des ouvrages connex COFN / C1540 and capacity building in the Post Open - National 64,000.00 64,322.18 Signed 2021-08-30 Based Selection 0 0 3 8 1 7 1 4 4 4 1 4 1 es dans la zone Ambatohar selected landscapes anana du paysage d'Iazafo; CR Ambatoharanana-District de Fénérive Est C 03-20/ANJ / Etudes et Con trôle-Surveillance des travau x de réhabilitation des résea Component 2: Investments ux d'irrigation et de drainag Quality And Cost- 2021-05-1 2021-09-0 2021-10-2 2020-12-3 2021-11-1 2021-02-0 2021-12-1 2021-03-0 2022-01-2 2021-04-1 2022-02-2 2021-04-2 2023-02-2 COFN / C1540 and capacity building in the Post Open - National 94,000.00 111,294.13 Signed 2021-08-17 e des périmètres Ampoezan Based Selection 9 7 1 1 8 3 8 2 2 2 6 8 6 selected landscapes a, Anamborano, Fandrianom by et Antsirabeniseva; CR S oanierana Ivongo et Fotsiala nana-District de Soanierana Ivongo C 18-20/ANJ / Etudes (APS, APD, DAO, EIE), Contrôle et surveillance des travaux de protection des berges des ri Component 2: Investments Quality And Cost- 2021-06-0 2021-07-2 2021-08-1 2021-09-1 2021-10-2 2021-11-2 2022-11-2 vières dans le paysage de S COFN / C1540 and capacity building in the Post 65,040.00 0.00 Canceled 2021-05-17 Based Selection 7 1 8 7 2 6 6 oanierana Ivongo : selected landscapes - Sahave dans la Commune Soanierana Ivongo - Sahafotra dans la Commu ne Antanifotsy C 06-19/BOE / Recrutement d'une ONG ou Association p Component 2: Investments our l'opérationnalisation du Quality And Cost- Under Implemen 2021-08-0 2020-06-0 2020-07-0 2022-04-2 2020-08-0 2022-05-2 2020-08-2 2020-09-2 2020-10-1 2021-05-2 COFN / C1540 and capacity building in the Post Open - National 55,000.00 0.00 2020-05-12 DINA Régionale et la mise e Based Selection tation 2 1 6 2 5 4 5 4 9 7 selected landscapes n œuvre des plans d'action contre les feux de brousses, dans le paysage de Marovoa y C 018-20/ANJ / Etudes (APS, APD, DAO, EIE), Contrôle et surveillance des travaux de Component 2: Investments protection des berges des ri Quality And Cost- 2021-05-3 2021-09-0 2021-10-1 2020-12-2 2021-11-1 2021-01-2 2021-12-0 2021-03-1 2021-12-1 2021-04-1 2022-01-2 2021-04-2 2022-07-2 COFN / C1540 and capacity building in the Post Open - National 66,000.00 33,945.00 Signed 2021-08-24 vières dans le paysage de S Based Selection 1 8 2 9 1 8 1 9 6 2 0 8 9 selected landscapes oanierana Ivongo : - Sahave dans la Commune Soanieran a Ivongo - Sahafotra dans la Commune Antanifotsy C 05-21/CN / Étude Genre d ans le développement de la Component 1: Information a Consultant Qualif 2021-07-2 2021-08-2 2021-10-1 2021-10-0 2022-02-1 2021-11-0 2022-06-1 2021-12-0 2022-07-1 2021-12-1 filière rizicole à Madagascar COFN / C1540 Post Open - National 50,000.00 47,143.38 Signed 2021-07-30 nd planning ication Selection 6 0 5 3 8 2 0 7 3 6 (Régions : Melaky, Sofia, Ala otra Mangoro, Analamanga, Atsinanana). C 01-20/BOE / Recrutement Component 2: Investments d'ONG/Association pour l'ins Quality And Cost- 2021-04-0 2021-05-0 2021-06-0 2021-06-2 2021-07-2 2021-08-3 2021-11-2 COFN / C1540 and capacity building in the Post Open - National 2,000.00 0.00 Canceled 2021-03-12 tauration et la formalisation Based Selection 1 8 7 7 9 0 9 selected landscapes de comités de gestion de m atériels agricoles C 16-20/SOF / Recrutement d'un Bureau d'études pour l a réalisation d'études, contr ôle et surveillance des trava Component 2: Investments Quality And Cost- 2020-12-1 2021-01-2 2021-02-2 2021-03-2 2021-04-2 2021-05-1 2021-06-0 2022-06-0 ux: IDA / 59790 and capacity building in the Post Open - National 234,000.00 0.00 Canceled 2021-01-06 Based Selection 8 6 2 2 1 8 7 7 LOT 1: piste depuis croisem selected landscapes ent de la route "Bealanana-a ntsamaka"-Beandrarezona ; LOT2: piste "Bealanana-ant samaka"de 15 km de longue ur C 20-20/SOF / Recrutement d'un Bureau d'études pour l a réalisation d'étude, contrôl Component 2: Investments Quality And Cost- 2021-03-0 2021-04-0 2021-05-0 2021-06-0 2021-06-1 2021-07-0 2022-07-0 e et surveillance de la mise COFN / C1540 and capacity building in the Post Open - National 27,000.00 0.00 Canceled 2021-02-15 Based Selection 7 3 3 2 9 9 9 en œuvre des travaux pour l selected landscapes e regabaritage des drains de la plaine d'Ankitrobaka, Ant animanga et Antsirakasada. C 09-20/SOF / Recrutement d'une ONG ou Association p our l'Instauration et Formalis ation des Comités de Gestio Component 2: Investments Quality And Cost- 2021-03-3 2021-05-1 2021-06-0 2021-06-2 2021-07-1 2021-08-1 2021-12-1 n des matériels agricoles : COFN / C1540 and capacity building in the Post Open - National 9,500.00 0.00 Canceled 2021-03-01 Based Selection 1 0 9 4 9 3 1 Lot 01 : dans le périmètre d selected landscapes e Mangindrano Lot 02 : dans le périmètre d e Bealanana C 07-21/SAV / Recrutement d'un Bureau d'études pour l' Component 2: Investments EIES, contrôle et surveillanc Consultant Qualif 2021-09-0 2021-10-0 2021-10-1 2021-10-3 2022-04-2 COFN / C1540 and capacity building in the Post Open - National 32,000.00 0.00 Canceled 2021-08-05 e des travaux de constructio ication Selection 4 4 9 1 9 selected landscapes n de tueries dans les Comm unes Rurales d'Ambalamana sy II et d'Ambodiangezoka C 01-20/ANJ / Elaboration ( Component 2: Investments PCD/SAC) au niveau des co Quality And Cost- 2021-07-1 2021-08-1 2021-09-1 2021-10-0 2021-11-0 2021-12-0 2022-03-0 COFN / C1540 and capacity building in the Post Open - National 33,140.00 0.00 Canceled 2021-06-10 mmunes dans les paysages Based Selection 0 9 8 8 7 6 6 selected landscapes d'intervention du PADAP CE R Analanjirofo C 01-19/ANJ / Élaboration d' Component 2: Investments un cadre incitatif (contrat pl Quality And Cost- 2020-09-0 2020-09-1 2020-10-1 2020-11-1 2020-11-2 2020-12-2 2021-01-1 2021-04-1 IDA / 59790 and capacity building in the Post Open - National 82,820.00 0.00 Canceled 2020-08-19 an pluriannuel) par AUE Iaza Based Selection 2 8 2 1 6 5 9 9 selected landscapes fo et Soanierana Ivongo. C 05-20/SOF / Etudes, mise en place et accompagneme Component 2: Investments nt d’une Structure de gestio Quality And Cost- 2021-02-1 2021-03-1 2021-04-3 2021-05-3 2021-06-2 2021-07-1 2021-08-1 2021-12-1 COFN / C1540 and capacity building in the Post Open - National 245,000.00 0.00 Canceled 2021-03-01 n adaptée pour l’axe routier Based Selection 1 6 0 0 9 9 3 1 selected landscapes Bealanana – Ambatoriha (RI P 117) dans le district de Be alanana, région Sofia C 04-20/CN / Service de Co nsultant pour la caractérisati Component 2: Investments Quality And Cost- Pending Implem 2022-03-2 2022-04-2 2022-05-2 2022-06-1 2022-07-2 2022-08-2 2022-11-2 on des ressources en eau et COFN / C1540 and capacity building in the Post Open - National 351,300.00 0.00 2022-02-22 Based Selection entation 4 7 7 6 1 5 3 estimation des besoins dans selected landscapes les 5 paysages d'interventio n du PADAP (5 lots) C 24-20/CN / Recrutement Component 2: Investments d'un Bureau d'étude pour la Consultant Qualif 2021-11-0 2021-12-1 2021-12-2 2022-01-1 2022-04-1 COFN / C1540 and capacity building in the Post Open - National 32,000.00 0.00 Canceled 2021-10-15 réalisation de la Mémoire te ication Selection 5 5 5 4 4 selected landscapes chnique de construction de t uerie. C 17-20/ANJ / Etudes , Contr ôle et surveillance des trava ux de protection des berges Component 2: Investments par méthode biologique et Quality And Cost- 2021-07-0 2021-08-1 2021-09-1 2021-10-1 2021-11-1 2021-12-2 2022-12-2 COFN / C1540 and capacity building in the Post Open - National 38,500.00 0.00 Canceled 2021-06-10 mécanique des rivières dans Based Selection 1 4 1 1 5 0 0 selected landscapes le paysage d'Iazafo : - Sahavaviana dans la Co mmune Maromitety - Iazafo C 07-22/CN / Recrutement Component 3: Project Mana d'un cabinet pour l'audit ext Least Cost Select Under Implemen 2022-12-0 2022-10-1 2022-11-1 2023-01-0 2022-12-1 2023-02-0 2023-01-0 2023-03-2 2023-02-0 2023-03-0 2023-08-0 COFN / C1540 gement Coordination and M Post Open - National 70,000.00 0.00 2022-10-18 erne des deux (02) dernière ion tation 1 9 2 9 0 9 9 1 9 1 8 &E exercices du PADAP : 2022, 2023 et clôture du Projet. C 02-20/CN / Service de con sultant pour le développeme Component 3: Project Mana Quality And Cost- 2020-08-2 2020-08-2 2020-10-0 2020-11-0 2020-11-2 2020-12-1 2021-01-0 2022-01-0 nt d'un logiciel pour le suivi- COFN / C1540 gement Coordination and M Post Open - National 25,000.00 0.00 Canceled 2020-07-30 Based Selection 8 0 3 2 2 6 9 4 évaluation du Projet Agricult &E ure Durable par une Approc he Paysage C 08-22/CN / Élaboration et mise en œuvre du Fond Régi Component 1: Information a Consultant Qualif Under Implemen 2023-03-2 2023-01-1 2023-02-2 2023-06-0 2023-03-2 2023-04-2 2023-07-2 onal d'entretien du réseaux COFN / C1540 Post Open - National 101,000.00 0.00 2022-12-29 nd planning ication Selection tation 4 9 2 9 4 8 7 hydoagricole (FRERHA) dans les zones d'intervention du P ADAP. C 24-20/SOF / Recrutement ONG pour la Mise en place, Formation, Encadrement, et Mise en place d'une cadre in citative pour l'Association de Component 2: Investments Quality And Cost- 2021-02-2 2021-03-1 2021-04-2 2021-06-1 2021-05-2 2021-06-1 2021-07-1 2021-08-0 2022-06-0 s usagers des pistes: COFN / C1540 and capacity building in the Post Open - National 76,000.00 0.00 Canceled 2021-03-01 Based Selection 6 7 1 9 1 0 0 8 4 Lot 1: Bealanana-Antsamaka selected landscapes Lot 2: croisement Antsamak a-Beandrarezona Lot 3: RIP 117m Bealanana - Ambatoriha C 04-21/SOF / Recrutement d’un bureau d’études pour l’ établissement d’un mémoire Component 2: Investments technique, contrôle et survei Consultant Qualif 2021-08-0 2021-08-1 2021-09-2 2021-10-2 2021-11-2 2022-05-2 COFN / C1540 and capacity building in the Post Open - National 30,000.00 0.00 Canceled 2021-07-29 llance des travaux d’extensi ication Selection 4 9 2 2 6 5 selected landscapes on du réseau d’irrigation du périmètre irrigue Bealanana I pour desservir le secteur A naborano du paysage de Be alanana C 21-20/BOE / Firme pour le s études, contrôle et surveill Component 2: Investments Quality And Cost- 2022-02-1 2022-03-3 2022-04-2 2022-05-2 2022-07-0 2022-08-0 2023-08-0 ance des travaux de stabilis COFN / C1540 and capacity building in the Post Open - National 100,000.00 0.00 Canceled 2022-01-25 Based Selection 5 1 8 8 2 6 6 ation des bassins versants d selected landscapes es canneaux de périmètre d e Marovoay secteur 4, 5 et 6 . INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Draft Negotiated Co Description Component Review Type Method Terms of Reference d/Selected Consulta Signed Contract Contract Completion No. ch ount (US$) nt (US$) s ntract nt Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-UGP PADAP-38775-CS-I Component 3: Project Mana NDV / Responsable de Passa Individual Consul 2017-08-1 2017-12-3 2018-02-0 2018-01-0 2018-03-0 2018-02-0 2018-03-2 2019-02-0 IDA / 59790 gement Coordination and M Post Open 48,000.00 11,178.36 Signed 2017-11-30 tion des marchés pour l'unit tant Selection 7 0 6 9 8 2 6 2 &E é de Coordination Régionale d'Andapa. Page 10 MG-UGP PADAP-38776-CS-I Component 3: Project Mana NDV / Responsable de Passa Individual Consul 2017-08-1 2018-01-1 2018-01-2 2018-01-2 2018-02-2 2018-01-3 2019-02-2 IDA / 59790 gement Coordination and M Post Open 48,000.00 13,209.42 Signed 2017-11-30 tion des Marchés (RPM) pour tant Selection 7 9 9 3 2 1 2 &E l'Unité de Coordination Régi onale de Sofia. C 61-17/CN / Responsable A Component 3: Project Mana dministratif et Finacier (RAF) Individual Consul 2017-09-0 2017-12-3 2017-11-0 2018-01-0 2018-02-0 2018-02-0 2018-02-2 2019-02-0 IDA / 59790 gement Coordination and M Post Open 48,000.00 14,267.74 Signed 2017-11-30 pour l'Unité de Coordination tant Selection 5 0 2 9 9 2 7 2 &E Régionale d'Analanjirofo. C 62-17/CN / Responsable d Component 3: Project Mana e Passation des Marchés (RP Individual Consul 2017-08-1 2018-01-1 2018-04-2 2018-01-2 2018-04-2 2018-02-1 2018-05-0 2019-02-1 IDA / 59790 gement Coordination and M Post Open 48,000.00 12,272.69 Signed 2017-11-27 M) pour l'Unité de Coordinati tant Selection 7 6 4 6 7 9 2 9 &E on Régionale d'Analanjirofo. MG-UGP PADAP-38779-CS-I Component 3: Project Mana NDV / Responsable Administ Individual Consul 2017-09-0 2017-12-3 2017-11-0 2018-01-0 2018-02-1 2018-02-0 2018-02-2 2019-02-0 IDA / 59790 gement Coordination and M Post Open 48,000.00 14,308.06 Signed 2017-11-30 ratif et Finacier (RAF) pour l' tant Selection 5 0 2 9 6 2 7 2 &E Unité de Coordination Régio nale de Sava. MG-UGP PADAP-38780-CS-I Component 3: Project Mana NDV / Responsable Administ Individual Consul 2017-09-0 2017-12-3 2017-11-0 2018-01-0 2018-02-0 2018-02-0 2018-02-2 2019-02-0 IDA / 59790 gement Coordination and M Post Open 48,000.00 11,889.78 Signed 2017-11-30 ratif et Finacier (RAF) pour l' tant Selection 5 0 2 9 9 2 7 2 &E Unité de Coordination Régio nale de Sofia. C 63-14/CN / Comptable po Component 3: Project Mana Individual Consul 2017-09-0 2017-12-3 2018-02-0 2018-01-0 2018-02-0 2018-02-0 2018-02-2 2019-02-0 ur l'Unité de Coordination R IDA / 59790 gement Coordination and M Post Open 12,000.00 8,181.79 Signed 2017-11-30 tant Selection 5 0 8 9 9 2 7 2 égionale d'Analanjirofo. &E C 57-17/CN / Responsable e Component 3: Project Mana Individual Consul 2017-12-2 2017-12-3 2018-01-1 2018-01-0 2018-02-0 2018-01-1 2019-02-0 IDA / 59790 Post Open 48,000.00 12,980.94 Signed 2017-12-01 au/irrigation national du Proj gement Coordination and M tant Selection 2 1 0 3 3 8 3 et. &E C 49-17/CN / Comptable nat Component 3: Project Mana Individual Consul 2017-09-1 2017-12-3 2017-11-0 2018-01-0 2018-02-0 2018-02-0 2018-02-2 2019-02-0 IDA / 59790 Post Open 24,000.00 11,923.38 Signed 2017-11-30 ional du PADAP. gement Coordination and M tant Selection 4 0 2 9 1 2 6 2 &E MG-UGP PADAP-38784-CS-I Component 3: Project Mana Individual Consul 2017-09-0 2017-12-3 2017-11-0 2018-01-0 2018-02-2 2018-02-0 2018-03-0 2019-02-0 NDV / Comptable pour l'Unit IDA / 59790 gement Coordination and M Post Open 12,000.00 8,176.03 Signed 2017-11-30 tant Selection 5 0 2 9 8 2 1 2 é de Coordination Régionale &E de Sofia. MG-UGP PADAP-38778-CS-I Component 3: Project Mana NDV / Responsable Administ Individual Consul 2017-09-0 2017-12-3 2017-11-0 2018-01-0 2018-02-0 2018-02-0 2018-02-2 2019-02-0 IDA / 59790 gement Coordination and M Post Open 48,000.00 13,588.32 Signed 2017-11-30 ratif et Finacier (RAF) pour l' tant Selection 5 0 2 9 9 2 7 2 &E Unité de Coordination Régio nale de Boeny. MG-UGP PADAP-38781-CS-I Component 3: Project Mana Individual Consul 2017-09-0 2017-12-3 2018-02-0 2018-01-0 2018-02-0 2018-02-0 2018-02-2 2019-02-0 NDV / Comptable pour l'Unit IDA / 59790 gement Coordination and M Post Open 12,000.00 8,181.79 Signed 2017-11-30 tant Selection 5 0 8 9 9 2 7 2 é de Coordination Régionale &E de Boeny. MG-UGP PADAP-38783-CS-I Component 3: Project Mana Individual Consul 2017-09-0 2017-12-3 2018-03-0 2018-01-0 2018-03-0 2018-02-0 2018-03-0 2019-02-0 NDV / Comptable pour l'Unit IDA / 59790 gement Coordination and M Post Open 12,000.00 8,176.03 Signed 2017-11-30 tant Selection 5 0 1 9 5 2 7 2 é de Coordination Régionale &E de Sava. MG-UGP PADAP-38445-CS-I Component 3: Project Mana NDV / Responsable de Passa Individual Consul 2017-08-1 2017-12-2 2018-01-0 2018-01-2 2018-01-3 2018-02-1 2019-01-3 IDA / 59790 gement Coordination and M Post Open 48,000.00 13,166.16 Signed 2017-11-27 tion des Marchés (RPM) pour tant Selection 7 7 6 3 0 5 0 &E l'Unité de Coordination Régi onale de Boeny. C 65-17/CN / 04 Responsabl es en Agriculture pour les 0 4 Unités de Gestion régional Component 3: Project Mana Individual Consul 2018-01-2 2018-02-1 2018-04-1 2018-03-1 2018-04-2 2018-04-1 2018-05-0 2019-04-1 2018-05-0 e du PADAP : Iazafo-Soanier IDA / 59790 gement Coordination and M Post Open 192,000.00 23,032.99 Signed 2018-01-08 tant Selection 5 7 7 0 4 4 2 4 2 ana Ivongo (Région Analanji &E rofo), Marovoay (Région Boe ny), Bealalana (Région SOFI A) et Andapa (Région SAVA) C 69-17/CN / 04 Responsabl es Socio-orga et développe ment local pour les 04 Unité Component 3: Project Mana s de Gestion régionale du PA Individual Consul 2017-12-2 2018-02-1 2018-04-1 2018-03-0 2018-04-2 2018-04-1 2018-04-2 2019-04-1 IDA / 59790 gement Coordination and M Post Open 192,000.00 40,130.70 Signed 2018-01-08 DAP : Iazafo-Soanierana Ivo tant Selection 8 6 7 9 5 3 6 3 &E ngo (Région Analanjirofo), M arovoay (Région Boeny), Be alalana (Région SOFIA) et An dapa (Région SAVA). C 67-17/CN / 04 Responsabl es en environnement et For esterie pour les 04 Unités de Component 3: Project Mana Gestion régionale du PADAP Individual Consul 2018-02-0 2018-02-1 2018-04-1 2018-03-1 2018-05-0 2018-04-1 2018-05-1 2019-04-1 IDA / 59790 gement Coordination and M Post Open 192,000.00 43,958.48 Signed 2018-01-08 : Iazafo-Soanierana Ivongo ( tant Selection 7 7 9 0 2 4 4 4 &E Région Analanjirofo), Marov oay (Région Boeny), Bealala na (Région SOFIA) et Andap a (Région SAVA). C 55-17/CN / Responsable S Component 3: Project Mana Individual Consul 2018-02-2 2018-02-1 2018-03-3 2018-03-1 2018-04-2 2018-04-1 2018-05-0 2019-04-1 auvegarde Environnemental IDA / 59790 gement Coordination and M Post Open 48,000.00 15,286.86 Signed 2018-01-08 tant Selection 3 7 0 0 7 4 2 4 e et Sociale au niveau natio &E nal (UGP) MG-UGP PADAP-44922-CS-I NDV / 04 Responsables Eau et Irrigation pour les 04 Unit Component 3: Project Mana és de Gestion régionale du P Individual Consul 2018-02-0 2018-03-1 2018-04-1 2018-04-0 2018-04-2 2018-05-0 2018-05-0 2019-05-0 IDA / 59790 gement Coordination and M Post Open 192,000.00 43,958.48 Signed 2018-01-22 ADAP : Iazafo-Soanierana Iv tant Selection 8 2 7 2 7 7 2 7 &E ongo (Région Analanjirofo), Marovoay (Région Boeny), B ealalana (Région SOFIA) et A ndapa (Région SAVA). C 60-17/CN / 04 Assistants t echniques des Opérations p our chaque Unité de Gestion Component 3: Project Mana Individual Consul 2017-10-2 2017-12-3 2018-01-2 2018-01-1 2018-02-2 2018-02-0 2018-05-0 2019-02-0 Régionale du PADAP : Iazafo IDA / 59790 gement Coordination and M Post Open 384,000.00 58,083.89 Signed 2017-12-01 tant Selection 3 1 2 0 3 3 2 3 -Soanierana Ivongo (Région &E Analanjirofo), Marovoay (Ré gion Boeny), Bealalana (Rég ion SOFIA) et Andapa (Régio n SAVA). MG-UGP PADAP-44950-CS-I Component 3: Project Mana Individual Consul 2018-03-2 2018-02-2 2018-05-1 2018-03-1 2018-06-2 2018-03-2 2018-06-2 2019-03-2 IDA / 59790 Post Open 48,000.00 17,197.72 Signed 2018-01-22 NDV / Auditeur interne gement Coordination and M tant Selection 1 6 8 3 7 8 9 8 &E MG-UGP PADAP-59456-CS-C DS / Recrutement d'un cons Component 2: Investments ultant international en vue d 2018-04-3 2018-05-0 2018-04-3 2018-06-2 2018-05-1 2018-07-2 2018-08-1 IDA / V0430 and capacity building in the Post Direct Selection Direct 30,250.00 40,425.00 Completed 2018-04-16 e la finalisation du plan d'act 0 6 0 9 6 9 7 selected landscapes ions sur la gestion des bois précieux (Diospyros spp, Dal bergia spp) MG-UGP PADAP-59459-CS-I NDV / Recrutement d'un con Component 2: Investments sultant national francophone Individual Consul 2018-05-1 2018-05-1 2018-04-1 2018-05-2 2018-05-2 2018-06-1 2018-05-2 2018-07-1 2018-08-1 IDA / V0430 and capacity building in the Post Limited 10,000.00 2,437.96 Completed 2018-04-16 pour l'assistance au consult tant Selection 4 6 9 6 1 5 1 5 7 selected landscapes ant international en vue de l a finalisation du plan d'actio ns sur la gestion des bois pr écieux. C 11-18/CN / Etude sur la R Component 3: Project Mana Individual Consul 2018-06-0 2018-06-0 2018-06-2 2018-06-1 2018-08-0 2018-06-2 2018-09-0 IDA / 59790 Post Open 2,500.00 2,172.74 Signed 2018-05-09 énovation locaux de l'UGP à gement Coordination and M tant Selection 6 7 8 4 2 9 1 Nanisana. &E MG-UGP PADAP-64943-CS-I NDV / Prestations d'un cons ultant individuel pour le post Component 3: Project Mana Individual Consul 2018-07-0 2018-07-1 2018-10-0 2018-07-2 2018-10-1 2018-08-1 2018-10-1 2019-08-1 e de IDA / 59790 gement Coordination and M Post Open 48,000.00 12,229.49 Signed 2018-06-01 tant Selection 9 6 8 3 1 2 2 2 Responsable en Suivi-évalua &E tion pour l'Unité de Coordina tion Régionale de PADAP-Ré gion ANALANJIROFO MG-UGP PADAP-65206-CS-C DS / Prestations pour 03 ans Component 3: Project Mana 2018-04-1 2018-06-1 2018-07-1 2018-04-2 2021-07-1 d'un consultant individuel p IDA / 59790 gement Coordination and M Post Direct Selection Direct 65,000.00 76,705.15 Signed 2018-06-04 9 4 8 3 7 our le poste de RESPONSAB &E LE ADMINISTRATIF ET FINAN CIER du projet PADAP. MG-UGP PADAP-66144-CS-I NDV / Prestations d'un cons Component 3: Project Mana Individual Consul 2018-02-2 2018-07-2 2018-03-2 2018-08-1 2018-03-2 2018-09-0 2018-03-2 2019-09-0 ultant individuel pour le post IDA / 59790 gement Coordination and M Post Open 10,000.00 7,459.85 Signed 2018-06-11 tant Selection 0 0 1 0 2 3 6 3 e d'Assistant Informatique p &E our l'Unité de Gestion du PA DAP MG-UGP PADAP-75687-CS-C DS / Prestations pour 03 ans Component 3: Project Mana 2017-01-1 2018-09-0 2018-10-1 2018-08-0 2021-10-0 d'un consultant individuel p IDA / 59790 gement Coordination and M Post Direct Selection Direct 65,000.00 50,287.43 Signed 2018-08-27 6 6 0 1 9 our le poste de RESPONSAB &E LE PASSATION DES MARCHE S du projet PADAP C 42-18/CN / La mise en pla ce d'un système d'informati Component 1: Information a Individual Consul 2018-08-3 2018-11-0 2019-01-1 2018-11-1 2019-02-0 2018-12-2 2019-02-0 2019-04-2 IDA / 59790 Post Open 10,000.00 7,436.62 Signed 2018-08-30 on géographique des périmè nd planning tant Selection 0 8 5 8 5 3 8 2 tres hydroagricoles (SIGPHY) C 17-18/CN / Adaptation de la méthodologie et le protoc Component 1: Information a Individual Consul 2018-09-2 2018-12-0 2018-12-1 2019-01-0 2019-01-1 2019-01-1 2019-04-0 IDA / 59790 Post Open 25,000.00 15,699.95 Signed 2018-11-09 ole du MEEF des inventaires nd planning tant Selection 4 8 8 3 8 1 3 forestiers et écologiques. MG-UGP PADAP-86980-CS-C DS / Prestations d'un an d'u Component 3: Project Mana 2018-10-0 2018-11-2 2018-12-2 2018-10-1 2019-12-2 n consultant individuel pour IDA / 59790 gement Coordination and M Post Direct Selection Direct 20,250.00 18,284.62 Signed 2018-11-13 2 3 7 8 7 le poste d'Assistant Techniq &E ue des Opérations du projet PADAP C 54-17/CN / Responsable e Component 3: Project Mana Individual Consul 2018-02-1 2018-03-0 2018-04-1 2019-04-1 IDA / 59790 Post Open 48,000.00 0.00 Canceled 2018-01-08 n Agriculture au niveau nati gement Coordination and M tant Selection 6 9 3 3 onal (UGP) &E C 10-19/ANJ / Recrutement Component 2: Investments Individual Consul 2019-05-1 2019-05-2 2019-06-1 2019-09-2 d'agent de suivi et d'accom COFN / C1540 and capacity building in the Post Open 6,560.00 0.00 Canceled 2019-03-12 tant Selection 8 8 7 5 pagnement des COBA. selected landscapes MG-UGP PADAP-86978-CS-C DS / Protocole d'accord PAP RIZ pour les Chaînes de vale Component 2: Investments 2018-10-1 2018-11-3 2019-01-1 2019-02-1 ur riz irrigué (Introduction d IDA / 59790 and capacity building in the Post Direct Selection Direct 31,400.00 0.00 Canceled 2018-11-13 6 0 3 2 es nouvelles technologie à tr selected landscapes avers de formation, Facilitati on d'accés à des intrants et des materiels Agricoles) MG-UGP PADAP-87818-CS-C DS / Protocole d'accord avec Component 2: Investments la DREEF analanjirofo pour l 2018-12-0 2019-01-1 2019-05-1 IDA / 59790 and capacity building in the Post Direct Selection Direct 35,000.00 0.00 Canceled 2018-11-22 a redynamisation et renforc 9 2 2 selected landscapes ement de capacité des COB A existants dans le paysage de Soanierana Ivongo MG-UGP PADAP-87819-CS-C DS / Protocole d'accord avec Component 2: Investments la DREEF Sofia pour la redyn 2018-12-0 2019-01-1 2019-05-1 IDA / 59790 and capacity building in the Post Direct Selection Direct 25,000.00 0.00 Canceled 2018-11-22 amisation et renforcement d 9 2 2 selected landscapes e capacité des COBA existan ts dans le paysage de Soani erana Ivongo C 02-18/CN / Protocole avec Component 2: Investments DPV sur l'atelier de formatio 2018-05-2 2018-07-0 2019-04-0 IDA / 59790 and capacity building in the Post Direct Selection Direct 40,000.00 0.00 Canceled 2018-05-09 n et production des fiches te 6 9 5 selected landscapes chniques de gestion des pes tes et pesticides Page 11 MG-UGP PADAP-127049-CS- CDS / Contrôle et surveillanc e des travaux sur PI d’Iazafo : Component 2: Investments LOT 3: réseaux d’irrigation e 2019-08-0 2019-08-2 2019-08-2 2019-09-2 2019-09-2 2020-02-1 COFN / C1540 and capacity building in the Post Direct Selection Direct 72,900.00 68,676.43 Signed 2019-08-16 t drainage zone d’Antsiraten 9 3 8 1 5 8 selected landscapes ina-Nosibe LOT 4: réseaux d’irrigation e t drainage zone d’Ambatomi paka-Maromitety LOT 6: réseaux d’irrigation z one de Mahatsara MG-UGP PADAP-127177-CS- CDS / Contrôle&surveillance des travaux sur PI Andrano mafana Mangindrano-paysa ge Bealanana : Component 2: Investments 2019-08-0 2019-08-2 2019-08-2 2019-09-2 2019-08-2 2020-02-1 -lot n°2: canal CPRD du pm COFN / C1540 and capacity building in the Post Direct Selection Direct 47,900.00 42,922.67 Signed 2019-08-16 9 3 3 1 7 8 2153 jusqu’au bout du résea selected landscapes u -lot n°3: canal CPRG 1er tro nçon de 2921 m -lot n°4: canal CPRG 2ème tr onçon de 3261 m -lot n°5: piste et pont C 22-18/CN / Protocole avec réseau des observatoires rur Component 1: Information a 2018-05-1 2018-07-2 2019-02-1 eaux sur l'observatoire des IDA / 59790 Post Direct Selection Direct 20,000.00 0.00 Canceled 2018-04-30 nd planning 7 1 6 données socio-économiques pour le paysage de Bealana na. C 07-19/ANJ / Appui aux dial Component 2: Investments ogues public-privé régionau Individual Consul 2019-05-1 2019-05-2 2019-06-1 2019-09-1 IDA / 59790 and capacity building in the Post Open 4,000.00 0.00 Canceled 2019-03-12 x pour la promotion de 3P d tant Selection 1 1 0 8 selected landscapes ans l'agriculture et l'élevage C 02-20/BOE / Recrutement de 3 Consultants Individuels pour la validation expérimen tale des paquets techniques Component 2: Investments Individual Consul 2020-05-0 2020-07-1 2020-08-0 2020-07-2 2020-08-0 2020-08-2 2020-10-1 2022-08-2 agroécologie, agroforesterie COFN / C1540 and capacity building in the Post Open 5,800.00 4,204.56 Signed 2020-05-22 tant Selection 8 6 1 7 3 6 7 6 , arboriculture et cultures fo selected landscapes urragères Lot 1: Commune d'Ambolom oty Lot 2: Commune Tsararano Lot 3: Commune Anosinalain C 03-18/BOE / Recrutement olona d'un consultant individuel ch Component 2: Investments Individual Consul 2020-03-0 2020-03-1 2020-03-1 2020-12-2 argé du diagnostic du foncti IDA / 59790 and capacity building in the Post Open 5,000.00 0.00 Canceled 2020-01-21 tant Selection 8 0 5 2 onnement et opérationnalis selected landscapes ation de la Banque de seme nces au CMS Tsararano. C 06-20/CN / Responsables Component 3: Project Mana en environnement et Forest Individual Consul 2020-01-2 2020-07-0 2020-05-1 2020-07-2 2020-05-1 2020-08-3 2020-07-0 2022-07-3 COFN / C1540 gement Coordination and M Post Open 35,000.00 9,410.11 Signed 2020-05-18 erie pour Unité de Gestion r tant Selection 0 6 3 7 5 1 2 0 &E égionale du PADAP Andapa ( Région SAVA). C 07-20/CN / Responsable A Component 3: Project Mana dministratif et Finacier (RAF) 2020-02-0 2020-05-2 2020-02-2 2020-08-0 2020-03-0 2022-08-0 IDA / 59790 gement Coordination and M Post Direct Selection Direct 170,000.00 121,661.24 Signed 2020-05-18 pour les 04 CERs (Sava, Boe 3 8 6 1 2 1 &E ny, Analanjirofo et Sofia) C 08-20/CN / Responsable P Component 3: Project Mana assation des marchés pour l 2020-02-0 2020-05-2 2020-02-2 2020-08-0 2020-05-1 2022-08-0 COFN / C1540 gement Coordination and M Post Direct Selection Direct 170,000.00 98,127.18 Signed 2020-05-18 es 04 CERs (Sava, Sofia, Boe 3 8 0 1 5 1 &E ny et Analanjirofo). C 09-20/CN / Comptable po Component 3: Project Mana 2020-02-1 2020-05-2 2020-02-2 2020-08-0 2020-03-0 2022-08-0 ur les 04 CERs (Sava, Sofia, COFN / C1540 gement Coordination and M Post Direct Selection Direct 85,000.00 73,670.47 Signed 2020-05-18 7 8 5 1 7 1 Boeny et Analanjirofo). &E C 10-20/CN / Responsable E Component 3: Project Mana 2020-04-1 2020-05-2 2020-04-2 2020-08-0 2020-05-0 2022-08-0 au et Irrigation pour les 04 C COFN / C1540 gement Coordination and M Post Direct Selection Direct 120,000.00 88,330.28 Signed 2020-05-18 0 8 0 1 2 1 ERs (Sava, Sofia, Boeny et A &E nalanjirofo). C 11-20/CN / Responsables Socio-orga et développemen t local pour les 04 CERs du P Component 3: Project Mana 2020-04-1 2020-05-2 2020-04-2 2020-08-0 2020-05-0 2022-08-0 ADAP : Iazafo-Soanierana Iv COFN / C1540 gement Coordination and M Post Direct Selection Direct 115,000.00 83,913.76 Signed 2020-05-18 0 8 7 1 2 1 ongo (Région Analanjirofo), &E Marovoay (Région Boeny), B ealalana (Région SOFIA) et A ndapa (Région SAVA). C 12-20/CN / 04 Assistants t echniques des Opérations p our chaque CER du PADAP : Component 3: Project Mana 2020-01-2 2020-05-2 2021-02-1 2020-08-0 2021-02-2 2022-08-0 Iazafo-Soanierana Ivongo (R COFN / C1540 gement Coordination and M Post Direct Selection Direct 200,000.00 120,566.77 Signed 2020-05-18 4 8 9 1 7 1 égion Analanjirofo), Marovoa &E y (Région Boeny), Bealalana (Région SOFIA) et Andapa (R égion SAVA). C 13-20/CN / 03 Responsabl es en environnement et For Component 3: Project Mana esterie pour les 03 CER du P 2020-04-1 2020-05-2 2020-04-2 2020-08-0 2020-05-1 2022-08-0 COFN / C1540 gement Coordination and M Post Direct Selection Direct 90,000.00 65,920.56 Signed 2020-05-18 ADAP : Iazafo-Soanierana Iv 6 8 7 1 3 1 &E ongo (Région Analanjirofo), Marovoay (Région Boeny) et Bealalana (Région SOFIA). C 14-20/CN / 03 Responsabl es en Agriculture pour les 0 Component 3: Project Mana 3 CER du PADAP : Iazafo-Soa 2020-03-2 2020-05-2 2020-04-2 2020-08-0 2020-04-2 2022-08-0 COFN / C1540 gement Coordination and M Post Direct Selection Direct 90,000.00 66,498.81 Signed 2020-05-18 nierana Ivongo (Région Anal 6 8 7 1 8 1 &E anjirofo), Marovoay (Région Boeny) et Andapa (Région S AVA) C 15-20/CN / Responsable e Component 3: Project Mana 2020-05-1 2020-05-2 2020-05-2 2020-08-0 2020-10-1 2022-08-0 n Suivi-évaluation pour la Ré COFN / C1540 gement Coordination and M Post Direct Selection Direct 40,000.00 19,598.78 Signed 2020-05-18 9 8 9 1 0 1 gion ANALANJIROFO du PAD &E AP. C 18-20/CN / Comptable nat Component 3: Project Mana 2020-02-1 2020-05-2 2020-02-2 2020-08-0 2020-02-2 2022-08-0 COFN / C1540 Post Direct Selection Direct 40,000.00 28,308.96 Signed 2020-05-18 ional du PADAP. gement Coordination and M 7 8 6 1 7 1 &E C 16-20/CN / Responsable S Component 3: Project Mana 2020-05-1 2020-05-2 2020-04-2 2020-08-0 2020-04-2 2022-08-0 auvegarde Environnemental COFN / C1540 gement Coordination and M Post Direct Selection Direct 40,000.00 32,056.56 Signed 2020-05-18 8 8 8 1 9 1 e et Sociale au niveau natio &E nal (UGP). C 17-20/CN / Assistant Tech Component 3: Project Mana 2020-05-1 2020-05-2 2020-10-0 2020-08-0 2020-10-2 2022-08-0 nique des Opérations du pro COFN / C1540 gement Coordination and M Post Direct Selection Direct 48,000.00 29,064.61 Signed 2020-05-18 8 8 9 1 0 1 jet PADAP au niveau de l'UG &E P. C 21-20/CN / Assistant Infor Component 3: Project Mana 2020-03-2 2020-05-2 2020-03-2 2020-08-0 2020-04-0 2022-08-0 matique pour l'Unité de Gest COFN / C1540 gement Coordination and M Post Direct Selection Direct 21,000.00 16,253.16 Signed 2020-05-18 3 8 3 1 2 1 ion du PADAP. &E C 20-20/CN / Auditeur inter Component 3: Project Mana 2020-05-1 2020-05-2 2020-06-2 2020-08-0 2020-07-0 2022-08-0 COFN / C1540 Post Direct Selection Direct 48,000.00 33,884.58 Signed 2020-05-18 ne du Projet. gement Coordination and M 8 8 2 1 2 1 &E C 19-20/CN / Responsable e Component 3: Project Mana 2020-01-1 2020-05-2 2020-01-1 2020-08-0 2020-01-1 2022-08-0 COFN / C1540 Post Direct Selection Direct 37,000.00 29,710.39 Signed 2020-05-18 au et irrigation national du P gement Coordination and M 3 8 3 1 8 1 rojet. &E C 11-20/SOF / Recrutement d’un Consultant Spécialiste en Travaux Publics chargé d Component 2: Investments Individual Consul 2020-12-3 2020-07-2 2021-05-1 2020-08-0 2021-05-1 2020-08-1 2021-06-1 2021-06-1 e l’appui à la Cellule d’exécu IDA / 59790 and capacity building in the Post Open 9,500.00 9,911.20 Signed 2020-06-17 tant Selection 0 9 1 5 4 9 6 5 tion Régionale Sofia sur l’ex selected landscapes écution des travaux de réha bilitation de la RIP 117 relian t Bealanana à Ambatoriha C 26-18/ CN / Diagnostic ag Component 2: Investments roécologique et Formation 2018-10-2 2018-05-2 2018-11-2 2018-07-2 2018-12-1 IDA / 59790 and capacity building in the Post Direct Selection Direct 45,000.00 0.00 Canceled 2018-05-09 des Organisations paysanne 6 6 2 0 7 selected landscapes s et des paysans sur les prat iques agroécologiques C 03-20/SAV / Recrutement de 02 techniciens agricoles pour encadrer les 300 pays ans adoptants en riziculture Component 2: Investments Individual Consul 2020-08-2 2020-09-2 2020-11-2 2020-10-1 2020-12-0 2020-11-1 2020-12-1 2021-05-1 2021-07-2 ameliorée dans le paysage d COFN / C1540 and capacity building in the Post Open 5,630.00 7,865.70 Completed 2020-08-05 tant Selection 0 3 4 4 3 8 7 7 4 'Andapa: selected landscapes Lot 1: Un technicien s'occup ant des périmètres de l'axe nord Lot 2: Un technicien s'occup ant des périmètres de l'axe C 06-20/ANJ / Consultant in ouest Component 2: Investments Individual Consul 2020-06-1 2020-06-2 2020-07-2 2020-10-2 dividuel pour formation des COFN / C1540 and capacity building in the Post Open 5,140.00 0.00 Canceled 2020-04-17 tant Selection 3 1 2 0 dirigeants du Tranoben'ny T selected landscapes antsaha C 09-19/ANJ / Recrutement d'un consultant individuel p our/ Component 2: Investments Lot 1: la formation en GIRE Individual Consul 2020-06-0 2020-06-1 2020-07-2 2020-12-1 COFN / C1540 and capacity building in the Post Open 4,500.00 0.00 Canceled 2020-04-13 des personnels de DREEH/D tant Selection 9 9 0 7 selected landscapes RAEP/DREDD Lot 2: Diffuser et expliquer l es rôles, responsabilités de l ’Autorité Nationale de l’Eau et de l’Assainissement C 23-20/CN / Responsables Component 3: Project Mana en Agriculture pour la cellule 2020-06-3 2020-07-1 2020-06-2 2020-08-0 2020-07-0 2022-08-0 COFN / C1540 gement Coordination and M Post Direct Selection Direct 23,000.00 20,447.60 Signed 2020-06-30 d'exécution régionale du PA 0 0 9 9 2 9 &E DAP Région SOFIA (Basé à B ealalana). C 27-20/CN / Recrutement d’un Responsable Agricultur Component 3: Project Mana Individual Consul 2020-09-2 2020-10-2 2020-10-2 2020-11-0 2020-10-2 2020-11-1 2020-11-1 2022-08-1 e au niveau de l’Unité de Ge IDA / 59790 gement Coordination and M Post Open 20,000.00 11,440.66 Signed 2020-09-28 tant Selection 8 8 9 4 9 8 2 0 stion du Projet Agriculture D &E urable par une Approche Pa ysage C 26-20/CN / Assistant tech Component 2: Investments 2020-09-1 2020-09-1 2020-09-1 2020-10-1 2020-09-1 2021-01-1 nique pour la gestion des co COFN / C1540 and capacity building in the Post Direct Selection Direct 90,000.00 11,872.80 Signed 2020-09-03 6 3 7 3 8 1 ntrats. selected landscapes C 12-20/SOF / Recrutement Component 2: Investments d'un Consultant Individuel s Individual Consul 2020-12-3 2020-11-2 2021-05-1 2020-12-0 2021-05-1 2021-01-0 2021-06-1 2022-03-0 COFN / C1540 and capacity building in the Post Open 13,500.00 9,911.20 Signed 2020-10-15 pécialiste en irrigation pour tant Selection 0 8 1 8 4 6 0 2 selected landscapes appuyer la Cellule d’exécuti on Régionale Sofia C 29-20/CN / Recrutement Component 3: Project Mana Individual Consul 2020-11-2 2021-01-1 2021-05-1 2021-01-2 2021-05-1 2021-02-2 2021-05-2 2022-08-0 COFN / C1540 Post Open 8,500.00 5,769.58 Signed 2020-11-30 d'un Assistant Administratif gement Coordination and M tant Selection 6 9 1 9 2 6 2 4 et Financier. &E C 30-20/CN / Recrutement Component 3: Project Mana de 04 Secrétaires en passati Individual Consul 2020-11-2 2021-01-1 2021-01-2 2021-01-2 2021-01-2 2021-02-2 2021-05-2 2022-08-0 COFN / C1540 gement Coordination and M Post Open 34,000.00 9,736.23 Signed 2020-11-30 on des marchés en tant que tant Selection 5 9 5 9 7 6 1 4 &E personnel d'appui pour les C ER du PADAP. C 31-20/CN / Spécialiste en Component 3: Project Mana Individual Consul 2020-12-0 2021-01-1 2021-01-2 2021-01-2 2021-03-2 2021-02-2 2021-04-1 2022-08-0 Passation des marchés au ni COFN / C1540 gement Coordination and M Post Open 16,000.00 10,812.70 Signed 2020-11-30 tant Selection 1 9 2 9 5 6 6 4 veau de l'UGP. &E C 28-20/CN / 02 Responsabl Component 3: Project Mana es en Suivi-évaluation dont Individual Consul 2020-12-1 2021-02-0 2021-02-1 2021-02-1 2021-04-0 2021-03-0 2021-05-2 2022-07-3 COFN / C1540 gement Coordination and M Post Open 36,000.00 13,996.22 Signed 2020-12-18 01 pour la Région SOFIA et 0 tant Selection 0 6 8 6 7 5 1 0 &E 1 pour la région de SAVA du PADAP. Page 12 C 28-20/BOE / Recrutement de 3 Consultants individuels pour l'encadrement techniq Component 2: Investments Individual Consul 2021-03-0 2021-04-0 2021-04-1 2021-04-2 2021-04-1 2021-05-3 2021-04-2 2021-12-2 ue et suivi de l'adoption du COFN / C1540 and capacity building in the Post Open 12,600.00 7,616.83 Signed 2021-02-25 tant Selection 1 5 6 6 6 1 9 7 paquet technique par les rizi selected landscapes culteurs. Lot 1 d'Ambolomot y, lot 2 Tsararano Lot 3 Anos inalinolona C 14-20/ANJ / Recrutement de 8 Techniciens en environ nement: Lot 1:1/3 CR Vavatenina zo ne Sud Component 2: Investments Lot 2:1/1 CR Vavatenina zon Individual Consul 2020-12-1 2020-12-2 2021-02-0 2023-02-0 COFN / C1540 and capacity building in the Post Open 71,300.00 0.00 Canceled 2020-10-30 e Nord-2CR Fen Est tant Selection 3 8 1 1 selected landscapes Lot 3:2/3CR Soanierana Ivon go zone Sud Lot 4:1/CR Antanifotsy-Mano mpana Lot 5: 1/CR Ambahoabe-Am bodiampana Lot 6:1/CR Antenina C 35-20/SOF / Recrutement de trois (03) consultants indi viduels au titre de technicie Component 2: Investments ns accompagnateurs pour l' Individual Consul 2020-10-1 2021-02-1 2021-01-2 2021-02-2 2021-02-0 2021-03-0 2021-02-0 2021-10-0 COFN / C1540 and capacity building in the Post Open 33,500.00 5,787.94 Signed 2021-01-06 encadrement et l'appui cons tant Selection 5 0 6 0 8 9 9 5 selected landscapes eils de proximité aux paysan s formateurs et paysans ado ptant la riziculture amélioré e dans le paysage de Bealan ana C 05-20/CN / Responsables Component 3: Project Mana en Agriculture pour la cellule Individual Consul 2020-04-2 2020-06-1 2020-07-0 2020-08-1 2022-08-1 IDA / 59790 gement Coordination and M Post Open 48,000.00 0.00 Canceled 2020-04-30 d'exécution régionale du PA tant Selection 3 8 9 3 3 &E DAP Région SOFIA (Basé à Bealalana). C 05-21/ANJ / Recrutement d’un(e)consultant(e) spéciali Component 2: Investments Individual Consul 2021-02-1 2021-04-0 2021-05-1 2021-04-0 2021-05-1 2021-04-2 2021-06-0 2022-04-2 ste en travaux publics charg COFN / C1540 and capacity building in the Post Open 11,884.00 387.26 Terminated 2021-02-25 tant Selection 6 6 1 7 4 7 9 7 e de l’appui a la cellule d’ex selected landscapes écution régionale Analanjirof o C 20-20/ANJ / Assistance te Component 2: Investments chnique de FDA pour la mise 2021-02-1 2021-03-1 2021-03-2 2021-04-2 2021-06-0 2022-07-2 COFN / C1540 and capacity building in the Post Direct Selection Direct 531,956.00 67,639.56 Completed 2021-02-26 en oeuvre d'AGR priorisées 2 8 3 7 9 1 selected landscapes dans les paysages d'Iazafo e t de Soanierana Ivongo C 7-20/BOE / Recrutement de 3 consultants individuels pour l'encadrement techniq Component 2: Investments ue des agriculteurs sur tane Individual Consul Under Implemen 2021-07-2 2021-04-2 2021-05-1 2021-06-1 2021-12-1 COFN / C1540 and capacity building in the Post Open 10,000.00 0.00 2021-03-10 ty dans le paysage de Marov tant Selection tation 8 4 5 9 6 selected landscapes oay Lot 1: Ambolomoty Lot 2: Tsararano Lot 3: Anosinalainolona C 07-20/BOE / Recrutement de 3 consultants individuels Component 2: Investments pour l'encadrement techniq Individual Consul 2020-12-2 2021-01-1 2021-02-2 2021-09-2 COFN / C1540 and capacity building in the Post Open 10,000.00 0.00 Canceled 2020-10-30 ue des agriculteurs sur tane tant Selection 9 9 3 1 selected landscapes ty dans le paysage de Marov oay Lot 1: Ambolomoty Lot 2: Tsararano Lot 3: Anosinal ainolona. C 08-20/ANJ / Recrutement d'un consultant individuel p Component 2: Investments Individual Consul 2021-03-2 2021-04-0 2021-04-2 2021-05-0 our la formation du personn COFN / C1540 and capacity building in the Post Open 2,250.00 0.00 Canceled 2021-02-10 tant Selection 5 4 4 9 el des Ministères au niveau selected landscapes Régional à la construction et mise en œuvre du SIS (Form ation) C 13-20/ANJ / Recrutement des techniciens accompagn ateurs dans les paysages d'I Component 2: Investments azafo et de Soanierana Ivon Individual Consul Under Implemen 2021-03-0 2021-04-2 2021-04-0 2021-05-0 2021-04-1 2021-05-3 2021-11-2 COFN / C1540 and capacity building in the Post Open 115,900.00 0.00 2021-03-03 go: tant Selection tation 2 1 6 1 2 0 6 selected landscapes Lot 01: 05 techniciens en ag riculture Lot 02: 08 techniciens en en vironnement C 10-20/SOF / Recrutement de Consultants individuels p Component 2: Investments Individual Consul 2020-12-2 2021-01-1 2021-02-2 2021-05-2 our l'encadrement et l'appui COFN / C1540 and capacity building in the Post Open 6,000.00 0.00 Canceled 2020-09-30 tant Selection 9 9 3 4 conseils de proximité aux Pa selected landscapes ysans Formateurs et aux Pa ysans adoptants C 05-19/ANJ / Consultant in Component 2: Investments dividuel pour appuyer la red Individual Consul 2021-03-1 2021-03-2 2021-04-1 2021-08-1 COFN / C1540 and capacity building in the Post Open 5,630.00 0.00 Canceled 2021-01-13 ynamisation duTranoben'ny tant Selection 4 5 5 3 selected landscapes Tantsaha à Fenérive Est. C 22-20 / CN / Responsable Environnement et Foresterie Component 3: Project Mana Individual Consul 2020-05-0 2020-07-2 2020-05-1 2020-08-1 2020-09-2 2022-08-1 au niveau de la Cellule d’Ex IDA / 59790 gement Coordination and M Post Open 48,000.00 0.00 Canceled 2020-06-10 tant Selection 5 9 3 9 3 4 écution Régionale du projet &E : Poste basé à Andapa (Régi on SAVA) C 23-20/BOE / Recrutement d'un consultant individuel p our les Etudes - contrôle et Component 2: Investments Individual Consul 2021-03-2 2021-04-2 2021-04-1 2021-05-2 2021-04-2 2021-06-2 2021-06-1 2021-12-2 surveillance des travaux de COFN / C1540 and capacity building in the Post Open 9,500.00 9,690.00 Signed 2021-03-16 tant Selection 5 9 6 0 2 4 8 1 réhabilitation des trois maga selected landscapes sins de stockage à la disposi tion des trois coopératives s emencières de Tsararano C 03-21/CN / Analyse du ma Component 1: Information a 2021-05-0 2021-06-1 2021-05-0 2021-09-0 2021-09-1 2022-03-0 rché et de la politique rizicol COFN / C1540 Post Direct Selection Direct 125,000.00 104,172.41 Signed 2021-05-21 nd planning 3 0 4 4 8 3 e à Madagascar. C 04-21/CN / Responsable A Component 3: Project Mana griculture pour la Cellule d’E Individual Consul 2021-05-0 2021-06-0 2021-06-1 2021-06-1 2021-06-2 2021-07-0 2021-07-2 2022-07-0 COFN / C1540 gement Coordination and M Post Open 16,000.00 9,693.95 Signed 2021-05-03 xécution Régionale du PADA tant Selection 3 2 7 2 1 6 0 6 &E P BOENY (Basé à Marovoay). C 02-21/CN / Responsable E Component 3: Project Mana nvironnement et Foresterie Individual Consul 2021-03-1 2021-04-1 2021-05-1 2021-04-2 2021-05-2 2021-05-2 2021-06-1 2022-08-1 COFN / C1540 gement Coordination and M Post Open 16,000.00 10,362.62 Signed 2021-03-19 pour la Cellule d’Exécution R tant Selection 9 8 9 8 1 2 6 5 &E égionale du PADAP SOFIA (B asé à Bealanana). C 02-21/SAV / Mémoire tech nique et contrôle-surveillanc e’ des travaux restant pour l Component 2: Investments a réhabilitation du barrage e 2021-05-3 2021-06-1 2021-07-1 2021-08-0 2021-07-3 2022-01-3 COFN / C1540 and capacity building in the Post Direct Selection Direct 18,600.00 18,045.72 Signed 2021-05-21 n dur avec avant-canal rive 1 0 3 4 1 1 selected landscapes droite et la rénovation des r éseaux hydroagricoles du pé rimètre Ambodivitagnona su r 370 ha, CR Ambalamanasy II, District Andapa. C 03-21/SAV / Recrutement Component 2: Investments de 03 techniciens agricoles Individual Consul 2021-05-1 2021-06-2 2021-07-1 2021-07-0 2021-07-1 2021-07-1 2021-07-2 2022-07-1 COFN / C1540 and capacity building in the Post Open 18,500.00 7,890.30 Signed 2021-05-10 pour encadrer les Paysans F tant Selection 2 9 3 6 9 9 2 9 selected landscapes ormateurs dans le paysage d'Andapa, Région SAVA. C 02-20/SOF / Recrutement de deux (02) agents commu Component 2: Investments Individual Consul 2021-03-2 2021-04-1 2021-05-1 2023-02-2 naux sur l'approche LIFE : 0 COFN / C1540 and capacity building in the Post Open 8,750.00 0.00 Canceled 2021-01-29 tant Selection 0 0 5 4 1 Commune Rurale AMBODI selected landscapes AMPANA- 01 Commune Rura le AMBATOSIA C 12-20/ANJ / Contrôle et su rveillance des travaux de ré Component 2: Investments habilitation des réseaux hyd 2021-03-3 2021-09-0 2020-10-1 2021-10-1 2020-12-1 2022-02-0 COFN / C1540 and capacity building in the Post Direct Selection Direct 24,500.00 20,661.41 Signed 2021-08-19 roagricoles de la zone Mahat 0 8 2 2 2 9 selected landscapes sara Sud- Andapatsra, dans l a plaine d'Iazafo (Lot 06); Di strict de Vavatenina. C 04-21/ANJ / Recrutement d'un Consultants individuel s Component 2: Investments pécialiste en Socio organisat Individual Consul 2021-06-2 2021-07-0 2021-07-2 2022-01-1 COFN / C1540 and capacity building in the Post Open 23,030.00 0.00 Canceled 2021-04-30 ion pour appui au développe tant Selection 3 3 3 9 selected landscapes ment de chaîne de valeur gi rofle dans le paysage de So anierana Ivongo C 03-21/ANJ / Recrutement de Consultant individuel spé Component 2: Investments cialiste en Distillation pour a Individual Consul 2021-05-1 2021-06-0 2021-07-0 2022-05-0 COFN / C1540 and capacity building in the Post Open 46,060.00 0.00 Canceled 2021-03-18 ppui au développement de c tant Selection 1 1 6 2 selected landscapes haîne de valeur girofle dans les paysages d’Iazafo et de Soanierana Ivongo C 02-21/ANJ / Recrutement de Consultant individuel spé Component 2: Investments cialiste en Chaudronnerie po Individual Consul 2021-05-1 2021-06-0 2021-07-0 2022-05-0 COFN / C1540 and capacity building in the Post Open 46,060.00 0.00 Canceled 2021-03-18 ur appui au développement tant Selection 1 1 6 2 selected landscapes de chaîne de valeur girofle d ans les paysages d’Iazafo et de Soanierana Ivongo C 13-20/BOE / Recrutement de 03 consultants individuel s pour l'encadrement techni Component 2: Investments Individual Consul 2021-03-2 2021-04-1 2021-05-2 2021-07-2 que et suivi de l'adoption du COFN / C1540 and capacity building in the Post Open 12,600.00 0.00 Canceled 2021-02-02 tant Selection 8 8 3 2 paquet technique par les rizi selected landscapes culteurs dans les CR d'Ambo lomoty, de Tsararano et d'A nosinalainolona C 05-20/BOE / Recrutement de deux (02) agents commu naux pour l'approche LIFE d Component 2: Investments ans le district de Marovoay, Individual Consul 2021-07-2 2021-08-1 2021-09-0 2023-09-1 COFN / C1540 and capacity building in the Post Open 8,100.00 0.00 Canceled 2021-06-09 Région Boeny. tant Selection 8 2 8 8 selected landscapes Lot 1: Commune rurale de T sararano Lot 2: Commune rurale d' An osinalainolona C 07-21/CN / Recrutement Component 3: Project Mana Individual Consul 2021-08-0 2021-09-2 2022-01-0 2021-10-1 2022-07-0 2021-11-1 2022-11-1 d’un consultant pour la com COFN / C1540 gement Coordination and M Post Open 12,000.00 0.00 Signed 2021-08-02 tant Selection 4 0 5 1 5 5 5 munication du PADAP. &E C 09-21/CN / Spécialiste en Component 3: Project Mana Individual Consul 2021-10-0 2021-12-0 2021-12-0 2021-12-2 2022-01-1 2022-02-0 2022-01-2 2022-08-0 Passation des marchés pour COFN / C1540 gement Coordination and M Post Open 20,000.00 5,956.39 Signed 2021-10-20 tant Selection 1 8 1 9 8 2 7 1 la Cellule d'Exécution Régio &E nale Sofia. C 08-21/CN / Responsable A Component 3: Project Mana griculture pour la Cellule d’E Individual Consul 2021-10-2 2021-12-1 2021-12-0 2022-01-0 2022-01-1 2022-02-0 2022-01-2 2022-09-0 COFN / C1540 gement Coordination and M Post Open 16,000.00 4,662.83 Signed 2021-10-20 xécution Régionale du PADA tant Selection 7 3 1 3 0 7 6 2 &E P SOFIA (Basé à Bealanana) C 10-20/ANJ / Recrutement consultant individuel pour la Component 2: Investments Individual Consul 2021-09-0 2021-09-1 2021-10-0 2021-10-2 formation en GIRE des perso COFN / C1540 and capacity building in the Post Open 2,925.00 0.00 Canceled 2021-07-20 tant Selection 6 6 6 1 nnels des 03 Directions Régi selected landscapes onales de tutelles et ceux d e la CER C 10-21/CN / Consultant sp Component 3: Project Mana 2021-10-1 2021-11-0 2021-11-0 2021-12-2 2021-11-1 2022-09-0 écialiste en travaux publics COFN / C1540 gement Coordination and M Post Direct Selection Direct 16,000.00 6,614.38 Signed 2021-10-20 5 9 3 3 6 2 à la cellule d’exécution régio &E nale Analanjirofo C 11-21/CN / Responsable E Component 3: Project Mana 2021-10-1 2021-11-1 2021-11-0 2021-12-2 2021-11-1 2022-09-0 nvironnement et Foresterie COFN / C1540 gement Coordination and M Post Direct Selection Direct 16,000.00 8,267.97 Signed 2021-10-20 5 4 3 8 6 2 au niveau de l'UGP. &E Page 13 C 13-20/SOF / Recrutement d'un Consultant Individuel s Component 2: Investments Individual Consul 2020-12-3 2021-01-3 2021-02-1 2021-03-0 2022-06-0 pécialiste en infrastructure r COFN / C1540 and capacity building in the Post Open 13,500.00 0.00 Canceled 2020-12-18 tant Selection 0 1 0 2 5 outière pour appuyer la Cell selected landscapes ule d’exécution Régionale S ofia C 12-20/BOE / Recrutement d'un consultant individuel p our l'étude - contrôle et surv Component 2: Investments Individual Consul 2021-07-2 2021-12-0 2021-12-2 2022-01-2 2022-06-2 eillance des travaux de cons COFN / C1540 and capacity building in the Post Open 2,400.00 0.00 Canceled 2021-10-13 tant Selection 8 1 2 6 5 truction de 3 couloirs de va selected landscapes ccination des bovidés dans l es CR d'Ambolomoty, de Tsa rarano et d'Anosinalainolona C 13-21/CN / Quatre (04) as sistants régionaux en sauve Component 3: Project Mana Individual Consul 2021-10-0 2021-12-1 2022-01-0 2022-01-0 2022-01-0 2022-02-1 2022-01-2 2022-08-1 garde environnementale et COFN / C1540 gement Coordination and M Post Open 40,000.00 8,755.14 Signed 2021-10-29 tant Selection 1 8 5 8 6 2 7 1 sociale (ARSES) au niveau d &E es paysages d’intervention du PADAP C 26-20/BOE / Recrutement de consultant individuel pou Component 2: Investments Individual Consul 2021-10-2 2021-11-0 2021-11-2 2022-06-2 r l'encadrement technique d COFN / C1540 and capacity building in the Post Open 3,600.00 0.00 Canceled 2021-09-20 tant Selection 4 3 3 1 es 40 pisciculteurs dans les selected landscapes CR de Marosakoa, d'Ambolo moty et de Tsararano C 22-20/BOE / Recrutement d'un Consultant individuel p our le contrôle et surveillanc Component 2: Investments Individual Consul 2021-12-0 2021-12-2 2022-01-2 2022-07-2 e des Travaux de stabilisatio COFN / C1540 and capacity building in the Post Open 5,000.00 0.00 Canceled 2021-10-13 tant Selection 1 2 6 5 n des zones d'érosion et pro selected landscapes tection des réseaux hydroag ricole le long du CPRD et CS PC Ambolomoty C 10-20/BOE / Recrutement d'un consultant individuel p our identification, formation Component 2: Investments Individual Consul 2021-11-2 2021-12-1 2022-01-1 2022-09-1 des Paysans formateurs et COFN / C1540 and capacity building in the Post Open 5,400.00 0.00 Canceled 2021-10-01 tant Selection 4 5 9 6 encadrement de 06 ateliers selected landscapes d'élevage bovin pilotes dans les CR d'Ambolomoty, de Ts ararano et d'Anosinalainolon a C 19-20/BOE / Recrutement de deux (2) techniciens fore Component 2: Investments stiers Individual Consul 2020-11-1 2020-12-0 2021-01-0 2021-07-0 COFN / C1540 and capacity building in the Post Open 21,000.00 0.00 Canceled 2020-09-25 Lot 1: Zone Marosakoa-Amb tant Selection 3 4 8 7 selected landscapes olomoty Lot 2: Zone Tsararano-Anosi nalainolona C 14-21/CN / Recrutement d'un consultant individuel p Component 1: Information a Individual Consul 2021-12-2 2022-01-1 2022-03-3 2022-01-2 2022-04-0 2022-02-1 2022-04-1 our l'actualisation de la strat COFN / C1540 Post Open 10,000.00 0.00 Signed 2021-11-30 nd planning tant Selection 1 4 1 4 1 3 4 égie national de développe ment rizicole à Madagascar. C 06-21/CN / Recrutement Component 3: Project Mana Individual Consul 2021-12-0 2021-12-1 2022-01-0 2022-11-2 d’un Assistant en Informatiq COFN / C1540 gement Coordination and M Post Open 8,500.00 0.00 Canceled 2021-11-04 tant Selection 4 4 7 7 ue du PADAP, poste basé à : &E Antananarivo C 01-22/CN / 02 Assistants Component 3: Project Mana en Génie Civil pour les Cellul Individual Consul 2022-03-1 2022-04-0 2022-09-2 2022-04-1 2022-05-1 2022-10-0 COFN / C1540 gement Coordination and M Post Open 20,000.00 0.00 Canceled 2022-01-31 es d’Exécution Régionales d tant Selection 4 6 0 6 0 7 &E u Projet PADAP Sofia et Ana nalanjirofo. C 03-22/CN / Spécialiste en Component 3: Project Mana Passation des Marchés char Individual Consul 2022-05-1 2022-06-2 2022-07-0 2022-07-2 2023-07-2 COFN / C1540 gement Coordination and M Post Open 16,000.00 0.00 Canceled 2022-05-10 gé de l’appui technique de l’ tant Selection 2 9 9 9 9 &E Unité de Gestion de Projet s ur les activités FSRP. C 04-22/CN / Spécialiste en Component 3: Project Mana Passation des Marchés char Individual Consul Under Implemen 2022-10-1 2022-08-2 2022-09-0 2022-09-2 2023-07-2 COFN / C1540 gement Coordination and M Post Open 16,000.00 0.00 2022-07-15 gé de l’appui technique de l’ tant Selection tation 0 9 9 7 4 &E Unité de Gestion de Projet. C 05-22/CN / Responsable e Component 3: Project Mana Individual Consul 2022-09-2 2022-09-2 2022-12-0 2022-10-0 2022-12-0 2022-10-2 2023-07-3 COFN / C1540 Post Open - National 11,000.00 0.00 Signed 2022-08-08 au et irrigation national du P gement Coordination and M tant Selection 9 2 7 2 9 2 1 rojet. &E C 06-22/CN / Spécialiste en Component 3: Project Mana Individual Consul Under Implemen 2022-10-1 2022-09-2 2022-10-0 2022-10-2 2023-07-3 Passation des marchés pour COFN / C1540 gement Coordination and M Post Open - National 22,000.00 0.00 2022-08-08 tant Selection tation 0 2 2 2 1 les 02 CERs (Sofia et Analanj &E irofo). C 02-22/CN / Recrutement Component 2: Investments Individual Consul 2022-11-1 2022-12-1 2023-03-1 2022-12-2 2023-03-3 2023-01-1 2023-04-1 d'un consultant individuel p COFN / C1540 and capacity building in the Post Open - National 5,000.00 0.00 Signed 2022-10-27 tant Selection 0 7 5 8 1 7 7 our la formation en SIG du P selected landscapes rojet. C 01-23/CN / Études des inf Component 2: Investments Direct - Internatio Pending Implem 2023-05-0 2023-06-0 2023-07-2 rastructures du système d’ir COFN / C1540 and capacity building in the Post Direct Selection 210,000.00 0.00 2023-04-29 nal entation 9 5 5 rigation solaire pour PADAP. selected landscapes C 02-23/CN / Recrutement Component 3: Project Mana Under Implemen 2023-05-3 2023-05-2 2023-05-1 2023-06-2 2023-07-2 d'un cabinet pour l'audit ext COFN / C1540 gement Coordination and M Post Direct Selection Direct - National 30,000.00 0.00 2023-05-22 tation 1 7 9 0 0 erne de l’exercice 2022 du P &E ADAP. Page 14 PROCUREMENT PLAN (Textural Part) Project information Country: Federal Democratic Republic of Ethiopia Project Name: Development Response to Displacement Impacts Project in the Horn of Africa Phase II (DRDIP II) Project ID: P178047 Project Implementation Agency: Ministry of Agriculture (MoA) Date of the Procurement Plan: September 2022 Period covered by this Procurement Plan: September 2022 to December 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” dated November 2020 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Directives of the Federal and Regional Governments of Ethiopia such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations. Goods: Applicable Works: Applicable Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Not Applicable. Proposed Procedures for CDD Components: Applicable Other Relevant Procurement Information: The procurement procedures for Situations in Urgent Need of Assistance or Capacity Constraints described under paragraph 12 of Section III of the World Bank Policy on IPF, which will be applicable to fast track emergency procurements shall not apply. PROCUREMENT Eastern and Southern Africa : Development Response to Displacement Impacts Project in the Horn of Africa Phase II PLAN General Information Country: Eastern and Southern Africa 2023-04-25 Bank’s Approval Date of the Original Procurement Plan: 2023-05-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178047 GPN Date: 2022-10-05 Project Name: Development Response to Displacement Impacts Project in the Horn of Africa Phase II Loan / Credit No: IDA / E0590 Somali Regional State Bureau of Agriculture Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure ET-SRS-BOA-363217-CW-RF ment Document - B / (CONSTRUCTION OF SMAL Sustainable Environmental Single Stage - One E Pending Imp 2025-03-0 IDA / E0590 Post Request for Bids Open - National 1 Envelope proce 1,521,983.83 0.00 2023-05-26 2023-05-31 2023-07-12 2023-08-11 2023-09-15 L SCALE IRRIGATION IN BOQ Management nvelope lementation 8 ss (Non Bank-SPD OLMAYO (SEDE) ) at Reginal ) Bureau Of Agriculture ET-SRS-BOA-363219-CW-RF National Procure B / (CONSTRUCTION OF SMA ment Document - Sustainable Environmental Single Stage - One E Pending Imp 2025-03-0 LL SCALE IRRIGATION IN DOL IDA / E0590 Post Request for Bids Open - National 1 Envelope proce 1,537,019.01 0.00 2023-05-26 2023-05-31 2023-07-12 2023-08-11 2023-09-15 Management nvelope lementation 8 LO -ADO (GERBA ADO)) At Re ss (Non Bank-SPD gional Bureau Of Agriculture ) ET-SRS-BOA-364130-CW-RF Request for Quota Q / ((Construction of market Social and Economic Service Request for Quota Single Stage - One E Pending Imp 2024-02-0 IDA / E0590 Post Limited tions (Non Bank-S 199,997.00 0.00 2023-06-10 2023-08-05 center)Strategic Investment s and Infrastructure tions nvelope lementation 1 PD) Fund (SIF)) by Boqolmayo wo reda office of Finance ET-SRS-BOA-364132-CW-RF Q / ((Construction of Grain St Request for Quota Social and Economic Service Request for Quota Single Stage - One E Pending Imp 2024-02-0 ore and DA house ) Strategic IDA / E0590 Post Limited tions (Non Bank-S 199,997.00 0.00 2023-06-10 2023-08-05 s and Infrastructure tions nvelope lementation 1 Investment Fund (SIF)) by a PD) wbere Woreda Office of Finan ce ET-SRS-BOA-364136-CW-RF Request for Quota Q / ((Health center expansion Social and Economic Service Request for Quota Single Stage - One E Pending Imp 2024-02-0 IDA / E0590 Post Limited tions (Non Bank-S 199,997.00 0.00 2023-06-10 2023-08-05 ) Strategic Investment Fund ( s and Infrastructure tions nvelope lementation 1 PD) SIF)) by K/bayah Woreda Offi ce of Finance GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-SRS-BOA-355602-GO-RF Q / purchase of farmers seed Request for Quota Single Stage - One E Pending Impl IDA / E0590 Livelihoods Program Post Limited 69,811.32 0.00 2023-05-05 2023-06-30 2023-12-27 (awbare ,k/bayah, dolla-ado tions nvelope ementation & Bokolmayo) at regional lev el ET-SRS-BOA-355597-GO-RF Q / Purchase of Solar Light ( awbare(for the new Kebeles only) ,k/bayah(for the new Ke Request for Quota Single Stage - One E Pending Impl IDA / E0590 Livelihoods Program Post Limited 74,490.57 0.00 2023-04-30 2023-06-25 2023-12-22 beles only),K/bayah City Adm tions nvelope ementation inistration, Dollo-ado(for the new Kebeles only) , Bokolma yo (for the new Kebeles only) , Dollo Bay) at regional level ET-SRS-BOA-355598-GO-RF Q / purchase of farm tools aw bare(for the new Kebeles onl y) ,k/bayah(for the new Kebel Sustainable Environmental Request for Quota Single Stage - One E Pending Impl IDA / E0590 Post Limited 33,962.26 0.00 2023-05-01 2023-06-26 2023-12-23 es only),K/bayah City Admini Management tions nvelope ementation stration, Dollo-ado(for the ne w Kebeles only) , Bokolmayo (for the new Kebeles only), D ollo Bay) at regional level ET-SRS-BOA-355600-GO-RF Q / purchase of ICT Equipme nt awbare(for the new Kebel es only) ,k/bayah(for the new Social and Economic Service Request for Quota Single Stage - One E Pending Impl Kebeles only),K/bayah City A IDA / E0590 Post Limited 93,396.23 0.00 2023-05-02 2023-06-27 2023-12-24 s and Infrastructure tions nvelope ementation dministration New Staff, Doll o-ado(for the new Kebeles on ly) , Bokolmayo (for the new Kebeles only), Dollo Bay New Staff) at regional level ET-SRS-BOA-355601-GO-RF Q / Purchase of office Furnitu re awbare(for the new Kebel es only) ,k/bayah(for the new Social and Economic Service Request for Quota Single Stage - One E Pending Impl Kebeles only),K/bayah City A IDA / E0590 Post Limited 59,150.94 0.00 2023-05-02 2023-06-27 2023-12-24 s and Infrastructure tions nvelope ementation dministration New staff, Doll o-ado(for the new Kebeles on ly) , Bokolmayo (for the new Kebeles only), Dollo Bay new Staff ) at regional level ET-SRS-BOA-355596-GO-RF Q / purchase of cooking stov es awbare(for the new Kebel es only) ,k/bayah(for the new Sustainable Environmental Request for Quota Single Stage - One E Pending Impl IDA / E0590 Post Limited 33,254.72 0.00 2023-04-29 2023-06-24 2023-12-21 Kebeles only),K/bayah City A Management tions nvelope ementation dministration, Dollo-ado(for t he new Kebeles only) , Bokol mayo (for the new Kebeles o nly), Dollo Bay) at regional le vel NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Page 1 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 Procurement Plan I. General 1. Project Information Country : Kenya Recipient : Republic of Kenya Project Name : National Agriculture and Rural Inclusive Growth Loan Credit No. : IDA 59000 2. Date of General Procurement Notice : 9th February 2018 3. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services 1. Thresholds for the Method of Procurement: Method of Procurement Thresholds for Method (US$ equivalent) Open International (Goods) Equal to or more than 3 million Open National ( Goods) – Open < $3 million Tender as per PPDA 2015 RFQ (Goods) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Open International (Works) Equal to or more than 15 million Open National (Works) - Open Less than 15 million Tender as per PPDA 2015 RFQ (works) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Method of Procurement Thresholds for Method (US$ equivalent) Open International (Non-consulting Equal to or More than 3 million Services) Open National (Non-consulting Less than 3 million Services) - Open Tender as per PPDA 2015 Direct Contracting No threshold; meet requirements of Bank’s Procurement Regulations Prior Review: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection (Project Procurement Risk Rating is “High”): (a) Goods, information technology and Non-consulting Services: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1.5 million (b) Works (including turnkey, supply & installation of plant and equipment and PPP); First procurement under the project irrespective of value and all procurements estimated to cost more than USD 5 million and The prior review thresholds will be reviewed during the implementation of the project and modified, based on the risk assessment. 2. For contracts subject to prior review, the Borrower shall seek the Bank’s no objection before agreeing to: a. an extension of the stipulated time for execution of a contract that has an impact on the planned completion of the project; b. any material modification of the scope of the Works, Goods, Non- consulting services or Consulting Services, or other significant changes to the terms and conditions of the contract; c. any variation order or contract amendment (except in cases of extreme urgency), including due to extension of time, that singly or combined with all previous variation orders or amendments, increases the original contract amount by more than 15% (fifteen percent); or d. the proposed termination of the contract. The Borrower / IA shall provide a copy of all amendments to the contract to the Bank for its records. 3. Prequalification Not Applicable Domestic Preference. The provision of domestic preference shall be applied in the procurement of goods following international market approach in accordance with Annex VI of the Regulations. Domestic preference shall not apply in the procurement of works. 4. Reference to Standard Procurement Documents Bank’s Standard RFB Goods and RFP Consulting Services dated July 2016 will be used as a base and incorporating suitable modifications and the same would be agreed with the Bank subject international competition. 5. Any Other Special Procurement Arrangements A. Procurement approach under CDD Approach by Communities: Applicable if stipulated in the PAD. B. When approaching the national market, as agreed in the Procurement Plan, the Open Tender procedure of Public Procurement and Asset Disposal Act 2015 and Regulations 2017 may be used. The specific Requirements for national open competitive procurement include the following: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. Other national procurement arrangements (other than national open competitive procurement), that may be applied by the Borrower (such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti-Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. In all cases, the national procurement procedures to be used shall give due attention to quality aspects. 6. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Selection methods of procurement of Consultants' Services (Firms): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Quality and Cost Based As per requirements of para 7.3 of the Selection (QCBS) Regulations Quality Based Selection As per requirements of para 7.8 to 7.10 (QBS) of the Regulations Selection based on a Fixed As per requirements of para 7.4 and 7.5 of the Budget (FBS) Regulations Selection Based on Least As per requirements of para 7.6 and 7.7 of the Cost Basis (LCS) Regulations Selection based on As per requirements of para 7.11 and 7.12 of Consultant’s Qualification the Regulations (CQ) Direct Must meet the requirements of Para 7.13 to 7.15 of the Regulations, and with prior agreement in PP with the Bank. The short list may consist of all National consultants in case the estimated cost is less than USD 300,000 Procurement methods for Selection of Individual Consultants (IC): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Open Competitive As per requirements of para 7.36 and 7.37 of Selection the Regulations Limited Competitive As per requirements of para 7.38 of the Selection Regulations Direct Must meet the requirements of Para 7.39 of the Regulations, and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Regulations Prior Review Thresholds: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 0.5 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.2 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. PROCUREMENT Kenya : National Agricultural and Rural Inclusive Growth Project PLAN General Information Country: Kenya 2019-10-03 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153349 GPN Date: 2018-02-09 Project Name: National Agricultural and Rural Inclusive Growth Project Loan / Credit No: IDA / Q9870, IDA / 59000 Narok County Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-NAROK COUNTY-138555- Supporting County Communi Request for Quota Single Stage - One E 2020-06-0 IDA / 59000 Post Limited 10,000.00 0.00 Canceled 2019-10-16 2019-10-04 2019-12-11 CW-RFQ / Construction of a w ty-Led Development tions nvelope 8 ater pan KE-NAROK COUNTY-138557- Project Coordination and Ma Single Stage - One E 2020-08-0 IDA / 59000 Post Request for Bids Open - National 1,200.00 0.00 Canceled 2019-10-16 2019-10-04 2019-10-21 2019-12-02 2020-01-01 2020-02-05 CW-RFB / Office refurbishme nagement nvelope 3 nt KE-NAROK COUNTY-162298- Supporting Community-Driv Single Stage - One E 2020-12-0 CW-RFQ / Construction of Sal IDA / 59000 Post Request for Bids Open - National 250,000.00 206,767.93 Signed 2020-03-20 2020-02-12 2020-03-25 2020-05-19 2020-04-06 2020-04-06 2020-05-06 2020-04-13 2020-06-10 2020-07-31 en Development nvelope 7 eita-Olduale Dairy Water proj ect. KE-NAROK COUNTY-165468- Supporting Community-Driv Single Stage - One E 2020-12-0 CW-RFB / Construction of Rai IDA / 59000 Post Request for Bids Open - National 960,000.00 682,757.33 Signed 2020-04-13 2020-05-28 2020-04-18 2020-05-29 2020-05-30 2020-07-06 2020-06-29 2020-07-18 2020-08-03 2020-09-02 en Development nvelope 1 tiany water pan KE-NAROK COUNTY-144888- CW-RFQ / Construction of two Supporting Community-Driv Single Stage - One E 2020-10-1 water pans (Kilutoori - 76,00 IDA / 59000 Post Request for Bids Open - National 530,000.00 226,160.63 Completed 2020-03-26 2020-02-06 2020-03-31 2020-05-19 2020-04-12 2020-04-06 2020-05-12 2020-04-13 2020-06-16 2020-08-09 en Development nvelope 4 0 and Ochoro Le Ntim - 54,00 0 Cubic Metres) at Kilgoris Ce ntral Ward. KE-NAROK COUNTY-173093- Project Coordination and Ma Request for Quota Single Stage - One E 2020-08-1 IDA / 59000 Post Limited 11,000.00 12,597.13 Completed 2020-05-16 2020-04-17 2020-07-11 2020-12-29 CW-RFQ / Office Refurbishme nagement tions nvelope 0 nt KE-NAROK COUNTY-174340- Supporting Community-Driv Single Stage - One E 2021-03-1 IDA / 59000 Post Request for Bids Open - National 300,000.00 240,810.26 Signed 2020-05-27 2020-06-04 2020-06-01 2020-05-29 2020-07-13 2020-07-06 2020-08-12 2021-07-18 2020-09-16 2020-09-11 CW-RFB / Shulakino Irrigation en Development nvelope 5 Scheme KE-NAROK COUNTY-186064- CW-RFB / Kipkandulit water d Supporting Community-Driv Single Stage - One E 2021-02-0 IDA / 59000 Post Request for Bids Open - National 230,000.00 213,080.73 Signed 2020-08-17 2020-09-03 2020-08-22 2020-10-03 2020-10-02 2020-11-02 2020-10-25 2020-12-07 2021-02-06 am located in Kapsasasian w en Development nvelope 5 ard, Transmara East Sub Cou nty. KE-NAROK COUNTY-304116- CW-RFB / Construction of Ose Request for Bids - ro Oirrusha Water Pan in Olo Supporting Community-Driv Single Stage - One E Small Works SPD 2023-01-0 IDA / 59000 Post Request for Bids Open - National 280,000.00 0.00 Signed 2022-07-15 2022-07-11 2022-07-16 2022-08-13 2022-08-17 2022-08-20 2022-08-22 2022-09-08 ololo Sub-Location, Kimintet en Development nvelope (1 envelope proce 6 Location, Kimintet Ward, Tra ss) nsmara West Sub-County, Na rok County KE-NAROK COUNTY-304128- CW-RFB / Construction of Ne Request for Bids - nkamuriaki Water Pan Projec Supporting Community-Driv Single Stage - One E Small Works SPD Under Imple 2023-01-0 IDA / 59000 Post Request for Bids Open - National 270,000.00 0.00 2022-07-15 2022-07-21 2022-07-16 2022-08-13 2022-08-17 2022-08-20 2022-08-22 2022-09-08 t in Sitoka Sub-Location, Esoi en Development nvelope (1 envelope proce mentation 6 t Naibor Location, Kimintet W ss) ard, Transmara West Sub-Co unty, Narok County GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-NAROK COUNTY-138532- Supporting Community-Driv Single Stage - One E IDA / Q9870 Post Request for Bids Open - National 5,000.00 0.00 Canceled 2019-10-29 2019-10-04 2019-11-05 2019-10-04 2019-12-25 2019-10-04 2020-01-06 2019-10-04 2020-02-10 2020-08-08 GO-RFB / Procurement of mo en Development nvelope tor cycles. KE-NAROK COUNTY-138539- Supporting Community-Driv Single Stage - One E IDA / Q9870 Post Request for Bids Open - National 5,000.00 0.00 Canceled 2019-10-03 2019-11-02 2019-12-14 2020-01-13 2020-02-17 2020-08-15 GO-RFB / Motorcycles en Development nvelope KE-NAROK COUNTY-174345- Supporting Community-Driv Request for Quota Single Stage - One E IDA / 59000 Post Limited 80,000.00 44,644.54 Completed 2020-06-01 2020-06-11 2020-07-27 2020-07-07 2020-10-25 2020-08-20 GO-RFQ / 20 Motor cycles en Development tions nvelope KE-NAROK COUNTY-174349- Project Coordination and Ma Request for Quota Single Stage - One E Under Imple IDA / 59000 Post Limited 80,600.00 0.00 2020-06-01 2020-10-02 2020-07-27 2020-10-25 GO-RFQ / ICT Equipments nagement tions nvelope mentation KE-NAROK COUNTY-174359- Supporting County Communi Request for Quota Single Stage - One E Under Imple GO-RFQ / Basic survey and s IDA / 59000 Post Limited 50,000.00 0.00 2020-05-29 2020-06-04 2020-07-24 2020-10-22 ty-Led Development tions nvelope mentation oil testing equipment. KE-NAROK COUNTY-176226- GO-RFQ / installation of dam Supporting Community-Driv Request for Quota Single Stage - One E liners and quarter acre drip i IDA / 59000 Post Limited 50,000.00 42,259.36 Signed 2020-06-10 2020-08-06 2020-08-05 2020-10-14 2020-08-11 en Development tions nvelope rrigation kit to support VMG l ivelihoods along dairy, tomat o and poultry value chains KE-NAROK COUNTY-176234- Supporting Community-Driv Request for Quota Single Stage - One E Under Imple GO-RFQ / purchase of high va IDA / 59000 Post Limited 30,000.00 0.00 2020-06-10 2020-04-24 2020-08-05 2020-10-04 en Development tions nvelope mentation lue fruit tree seedlings KE-NAROK COUNTY-176238- GO-RFQ / purchase of suppor Supporting Community-Driv Request for Quota Single Stage - One E Under Imple IDA / 59000 Post Limited 20,000.00 0.00 2020-06-10 2020-08-03 2020-08-05 2020-10-04 t equipment (small projectors en Development tions nvelope mentation and tablets) to DAT youths KE-NAROK COUNTY-273022- GO-DIR / Purchase of speciall y designed Android tables, S Supporting County Communi Pending Impl IDA / 59000 Post Direct Selection Direct 12,319.20 0.00 2022-02-15 2022-02-20 2022-03-13 2022-09-09 mart Digital Projector with An ty-Led Development ementation droid OS and Agripreneurs Di gital platform License for DA T Kuza biasha cohort Page 1 KE-NAROK COUNTY-362884- GO-RFQ / Supply and deliver Supporting Community-Driv Request for Quota Single Stage - One E Pending Impl IDA / 59000 Post Open - National 23,100.00 0.00 2023-05-29 2023-07-31 2024-01-27 y of Desk top computers and en Development tions nvelope ementation Printer for Sacco's automatio n NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-NAROK COUNTY-272924- NC-DIR / Purchase of softwar Supporting County Communi Pending Impl IDA / 59000 Post Direct Selection Direct 12,000.00 0.00 2022-02-15 2022-02-22 2022-03-15 2022-09-11 e and access license for M-sh ty-Led Development ementation amba mobile DAT Cohort KE-NAROK COUNTY-272989- GO-DIR / Purchase of digital Supporting County Communi Under Imple IDA / 59000 Post Direct Selection Direct 1,750.00 0.00 2022-02-15 2020-05-24 2022-02-20 2020-05-24 2022-03-13 2022-09-09 mobile equipment devices fo ty-Led Development mentation r Hello tractor DAT cohort CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-NAROK COUNTY-168579- Supporting Community-Driv Consultant Qualifi Under Implement CS-CQS / Support to Service IDA / 59000 Post Open - National 50,000.00 0.00 2020-04-27 2021-05-03 2020-05-18 2020-07-01 2020-07-31 2020-09-04 2021-12-31 en Development cation Selection ation Provider in potato value chai n development. KE-NAROK COUNTY-168580- Supporting Community-Driv Consultant Qualifi Under Implement CS-CQS / Service Provider to IDA / 59000 Post Open - National 50,000.00 0.00 2020-04-27 2021-05-03 2020-05-18 2020-07-01 2020-07-31 2020-09-04 2021-12-31 en Development cation Selection ation support tomato value chain. KE-NAROK COUNTY-168578- Supporting Community-Driv Consultant Qualifi Under Implement CS-CQS / Service Provider su IDA / 59000 Post Open - National 50,000.00 0.00 2020-04-27 2021-05-03 2020-05-18 2020-07-01 2020-07-31 2020-09-04 2021-12-31 en Development cation Selection ation pport to Dairy Value Chain. KE-NAROK COUNTY-168585- Supporting Community-Driv Consultant Qualifi Under Implement CS-CQS / support to poultry v IDA / 59000 Post Open - National 50,000.00 0.00 2020-04-27 2021-05-03 2020-05-18 2020-07-01 2020-07-31 2020-09-04 2021-12-31 en Development cation Selection ation alue chain development KE-NAROK COUNTY-275919- CS-CQS / Procurement of NA Supporting Community-Driv Quality Based Sel Pending Impleme RIGP Financial Inclusion Matc IDA / 59000 Post Open - National 30,000.00 0.00 2022-02-14 2022-03-07 2022-04-20 2022-05-18 2022-06-17 2022-07-17 2022-08-21 2023-02-17 en Development ection ntation hing Grand (FIMG) Consultan cies for SACCOs promotion INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 Procurement Plan I. General 1. Project Information Country : Kenya Recipient : Republic of Kenya Project Name : National Agriculture and Rural Inclusive Growth Loan Credit No. : IDA 59000 2. Date of General Procurement Notice : 9th February 2018 3. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services 1. Thresholds for the Method of Procurement: Method of Procurement Thresholds for Method (US$ equivalent) Open International (Goods) Equal to or more than 3 million Open National ( Goods) – Open < $3 million Tender as per PPDA 2015 RFQ (Goods) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Open International (Works) Equal to or more than 15 million Open National (Works) - Open Less than 15 million Tender as per PPDA 2015 RFQ (works) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Method of Procurement Thresholds for Method (US$ equivalent) Open International (Non-consulting Equal to or More than 3 million Services) Open National (Non-consulting Less than 3 million Services) - Open Tender as per PPDA 2015 Direct Contracting No threshold; meet requirements of Bank’s Procurement Regulations Prior Review: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection (Project Procurement Risk Rating is “High”): (a) Goods, information technology and Non-consulting Services: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1.5 million (b) Works (including turnkey, supply & installation of plant and equipment and PPP); First procurement under the project irrespective of value and all procurements estimated to cost more than USD 5 million and The prior review thresholds will be reviewed during the implementation of the project and modified, based on the risk assessment. 2. For contracts subject to prior review, the Borrower shall seek the Bank’s no objection before agreeing to: a. an extension of the stipulated time for execution of a contract that has an impact on the planned completion of the project; b. any material modification of the scope of the Works, Goods, Non- consulting services or Consulting Services, or other significant changes to the terms and conditions of the contract; c. any variation order or contract amendment (except in cases of extreme urgency), including due to extension of time, that singly or combined with all previous variation orders or amendments, increases the original contract amount by more than 15% (fifteen percent); or d. the proposed termination of the contract. The Borrower / IA shall provide a copy of all amendments to the contract to the Bank for its records. 3. Prequalification Not Applicable Domestic Preference. The provision of domestic preference shall be applied in the procurement of goods following international market approach in accordance with Annex VI of the Regulations. Domestic preference shall not apply in the procurement of works. 4. Reference to Standard Procurement Documents Bank’s Standard RFB Goods and RFP Consulting Services dated July 2016 will be used as a base and incorporating suitable modifications and the same would be agreed with the Bank subject international competition. 5. Any Other Special Procurement Arrangements A. Procurement approach under CDD Approach by Communities: Applicable if stipulated in the PAD. B. When approaching the national market, as agreed in the Procurement Plan, the Open Tender procedure of Public Procurement and Asset Disposal Act 2015 and Regulations 2017 may be used. The specific Requirements for national open competitive procurement include the following: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. Other national procurement arrangements (other than national open competitive procurement), that may be applied by the Borrower (such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti-Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. In all cases, the national procurement procedures to be used shall give due attention to quality aspects. 6. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Selection methods of procurement of Consultants' Services (Firms): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Quality and Cost Based As per requirements of para 7.3 of the Selection (QCBS) Regulations Quality Based Selection As per requirements of para 7.8 to 7.10 (QBS) of the Regulations Selection based on a Fixed As per requirements of para 7.4 and 7.5 of the Budget (FBS) Regulations Selection Based on Least As per requirements of para 7.6 and 7.7 of the Cost Basis (LCS) Regulations Selection based on As per requirements of para 7.11 and 7.12 of Consultant’s Qualification the Regulations (CQ) Direct Must meet the requirements of Para 7.13 to 7.15 of the Regulations, and with prior agreement in PP with the Bank. The short list may consist of all National consultants in case the estimated cost is less than USD 300,000 Procurement methods for Selection of Individual Consultants (IC): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Open Competitive As per requirements of para 7.36 and 7.37 of Selection the Regulations Limited Competitive As per requirements of para 7.38 of the Selection Regulations Direct Must meet the requirements of Para 7.39 of the Regulations, and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Regulations Prior Review Thresholds: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 0.5 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.2 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. PROCUREMENT Kenya : National Agricultural and Rural Inclusive Growth Project PLAN General Information Country: Kenya 2019-10-03 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153349 GPN Date: 2018-02-09 Project Name: National Agricultural and Rural Inclusive Growth Project Loan / Credit No: IDA / 59000 Kwale County Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-KWALE COUNTY-145850- Project Coordination and Ma Request for Quota Single Stage - One E 2020-02-2 IDA / 59000 Post Limited 25,000.00 22,834.06 Completed 2019-11-21 2019-11-25 2019-12-22 2020-01-09 CW-RFQ / Refurbishment of o nagement tions nvelope 0 ffice KE-KWALE COUNTY-168345- Supporting County Communi Single Stage - One E Under Imple 2020-10-1 CW-RFB / REHABILITATION O IDA / 59000 Post Request for Bids Open - National 554,035.00 0.00 2020-04-13 2021-04-02 2020-04-17 2020-05-08 2021-05-18 2020-05-25 2021-05-25 2020-06-17 ty-Led Development nvelope mentation 5 F NYALANI IRRIGATION SCHE ME KE-KWALE COUNTY-316805- Request for Quota Supporting County Communi Request for Quota Single Stage - One E Under Imple 2022-11-2 CW-RFQ / REHABILITATION O IDA / 59000 Post Limited tions (Non Bank-S 190,000.00 0.00 2022-09-22 2022-09-21 2022-10-22 ty-Led Development tions nvelope mentation 1 F NURU EARTH DAM PD) Request for Bids - KE-KWALE COUNTY-316808- Supporting County Communi Single Stage - One E Small Works SPD Under Imple 2022-12-1 CW-RFB / REHABILITATION O IDA / 59000 Post Request for Bids Open - National 327,814.68 0.00 2022-09-21 2022-09-22 2022-09-22 2022-12-06 2022-10-22 2022-10-22 2022-10-26 2022-10-24 2022-11-14 ty-Led Development nvelope (1 envelope proce mentation 4 F DZIHOENI WATER PAN ss) Request for Bids - KE-KWALE COUNTY-274919- Works (without pr Supporting County Communi Single Stage - One E 2022-07-1 CW-RFB / REHABILITATION O IDA / 59000 Post Request for Bids Open - National equalification) SP 223,000.00 0.00 Canceled 2022-01-30 2022-06-29 2022-02-04 2022-09-19 2022-03-06 2022-08-15 2022-03-16 2022-04-13 ty-Led Development nvelope 3 F NURU EARTH DAM D - Applying contr actor disqualificia tion Request for Bids - KE-KWALE COUNTY-274929- Works (without pr Supporting County Communi Single Stage - One E 2022-07-1 CW-RFB / REHABILITATION O IDA / 59000 Post Request for Bids Open - National equalification) SP 269,000.00 0.00 Canceled 2022-01-30 2022-06-29 2022-02-04 2022-09-19 2022-03-06 2022-08-15 2022-03-16 2022-04-13 ty-Led Development nvelope 3 F DZIHOENI WATER PAN D - Applying contr actor disqualificia tion GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-KWALE COUNTY-138678- Supporting County Communi Single Stage - One E GO-RFB / Purchase and suppl IDA / 59000 Post Request for Bids Open - National 2,500.00 0.00 Canceled 2019-10-04 2019-10-11 2019-11-10 2019-11-17 2019-12-22 2020-06-19 ty-Led Development nvelope y of survey and soil testing e quipment KE-KWALE COUNTY-138668- Project Coordination and Ma Single Stage - One E GO-RFB / SUPPLY AND DELIV IDA / 59000 Post Request for Bids Open - National 50,000.00 0.00 Canceled 2019-10-04 2019-10-04 2019-10-09 2019-10-04 2019-11-08 2019-10-04 2019-11-15 2019-12-20 2020-06-17 nagement nvelope ERY OF OFFICE FURNITURE KE-KWALE COUNTY-138547- Supporting County Communi Single Stage - One E GO-RFB / SUPPLY AND DELIV IDA / 59000 Post Request for Bids Open - National 500,000.00 0.00 Canceled 2019-10-03 2019-10-08 2019-11-19 2019-12-19 2020-01-23 2020-02-22 ty-Led Development nvelope ERY OF MOTORCYCLES KE-KWALE COUNTY-138544- Supporting County Communi Single Stage - One E GO-RFB / Supply and delivery IDA / 59000 Post Request for Bids Open - National 5,000.00 0.00 Canceled 2019-10-03 2019-10-08 2019-11-07 2019-12-07 2020-01-11 2020-03-11 ty-Led Development nvelope of motor cycles KE-KWALE COUNTY-145799- Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 6,000.00 5,474.92 Completed 2019-11-18 2019-11-25 2019-12-21 2020-02-25 2020-01-04 2020-03-10 GO-RFQ / Purchase of Office nagement tions nvelope Furniture KE-KWALE COUNTY-145848- GO-RFQ / procurement of bas Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 21,800.00 24,245.06 Completed 2019-11-21 2019-12-25 2019-12-09 2020-01-04 2019-12-23 2020-08-12 ic tools and equipments for s ty-Led Development tions nvelope urvey and soil testing KE-KWALE COUNTY-168348- Project Coordination and Ma Request for Quota Single Stage - One E GO-RFQ / PURCHASE OF 5 LA IDA / 59000 Post Limited 8,000.00 6,235.67 Completed 2020-04-18 2020-08-25 2020-06-03 2020-10-29 2020-07-04 2020-12-30 nagement tions nvelope PTOPS AND THEIR ACCESSOR IES KE-KWALE COUNTY-178485- Project Coordination and Ma Request for Quota Single Stage - One E GO-RFQ / PURCHASE OF 20 M IDA / 59000 Post Limited 80,000.00 72,994.08 Completed 2020-06-16 2020-09-02 2020-07-16 2020-10-29 2020-08-15 2021-05-21 nagement tions nvelope OTORCYCLES KE-KWALE COUNTY-178486- GO-RFQ / Purchase and Instal Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 63,000.00 54,958.49 Completed 2020-06-16 2020-09-02 2020-07-18 2020-10-30 2020-08-17 2021-02-11 lation of IP based audio-visua nagement tions nvelope l teleconference system KE-KWALE COUNTY-201615- Supporting Community-Driv Request for Quota Single Stage - One E Under Imple GO-RFQ / black & white copi IDA / 59000 Post Limited 4,950.00 0.00 2020-11-02 2020-09-04 2020-11-24 2020-12-01 en Development tions nvelope mentation er, printer comes scanner KE-KWALE COUNTY-201608- Supporting Community-Driv Request for Quota Single Stage - One E GO-RFQ / purchase of 20 CD IDA / 59000 Post Limited 7,400.00 14,876.80 Completed 2020-11-09 2021-02-02 2020-11-25 2021-03-20 2020-12-02 2021-05-05 en Development tions nvelope DCs' Furniture KE-KWALE COUNTY-258298- Supporting County Communi Request for Quota Single Stage - One E GO-RFQ / Purchase of Pico Pr IDA / 59000 Post Limited 7,000.00 0.00 Canceled 2021-12-15 2022-01-17 2022-01-27 ty-Led Development tions nvelope ojector and video camera for e-extention KE-KWALE COUNTY-258300- Supporting County Communi Request for Quota Single Stage - One E GO-RFQ / Purchase of 5 porta IDA / 59000 Post Limited 30,000.00 0.00 Canceled 2021-12-15 2022-01-17 2022-01-27 ty-Led Development tions nvelope ble soil tsting kit and softwar e KE-KWALE COUNTY-258302- Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 9,000.00 0.00 Canceled 2021-12-15 2022-01-17 2022-01-27 GO-RFQ / Purchase of 6 solar ty-Led Development tions nvelope pumps KE-KWALE COUNTY-258303- Supporting County Communi Request for Quota Single Stage - One E GO-RFQ / Purchase of digitaz IDA / 59000 Post Limited 9,500.00 0.00 Canceled 2021-12-15 2022-01-17 2022-01-27 ty-Led Development tions nvelope ation equipments and soft w ares Page 1 KE-KWALE COUNTY-260524- Strengthening Producer Org Request for Quota Single Stage - One E GO-RFQ / Specially designed IDA / 59000 anizations and Value Chain Post Limited 4,524.00 0.00 Canceled 2021-12-15 2022-01-17 2022-02-07 tions nvelope Android Tablet (10 units) Development KE-KWALE COUNTY-260526- Strengthening Producer Org Request for Quota Single Stage - One E GO-DIR / Smart Digital Projec IDA / 59000 anizations and Value Chain Post Limited 2,436.00 0.00 Canceled 2021-12-15 2022-01-17 2022-02-07 tions nvelope tor with Android OS (10 units Development ) KE-KWALE COUNTY-260529- Strengthening Producer Org Request for Quota Single Stage - One E GO-DIR / Agripreneurs Digital IDA / 59000 anizations and Value Chain Post Limited 6,264.00 0.00 Canceled 2021-12-15 2022-01-17 2022-02-07 tions nvelope platform License (10 units) Development KE-KWALE COUNTY-274874- GO-DIR / Procurement of a di gital Kit(specially designed a Supporting County Communi ndroid tablet,smart dig proje IDA / 59000 Post Direct Selection Direct 13,224.00 10,956.08 Completed 2022-01-28 2022-01-22 2022-01-31 2022-01-22 2022-02-18 2022-07-09 2023-02-18 2022-09-01 ty-Led Development ctor with OS, and Agripreneu rs digital platform license) an d advisory services on produ ction of tomato & green gra ms. KE-KWALE COUNTY-305717- Supporting Community-Driv Request for Quota Single Stage - One E GO-RFQ / Purchase of 20 CD IDA / 59000 Post Limited 12,000.00 9,859.15 Completed 2022-07-27 2022-07-28 2022-08-15 2022-09-05 2022-08-29 2022-10-04 en Development tions nvelope DC Computers KE-KWALE COUNTY-326637- GO-RFB / Supply, delivery an Strengthening Producer Org Single Stage - One E Under Imple d installation of 1200 CAB hiv IDA / 59000 anizations and Value Chain Post Request for Bids Open - National 199,720.00 0.00 2022-12-05 2022-12-20 2022-12-10 2023-04-27 2023-01-09 2023-01-23 2023-01-14 2023-02-04 2023-01-31 2023-02-15 nvelope mentation es, 60 water tanks of 500ltrs, Development 24000 bee forage seedlings and demonstration in 60 CIG s KE-KWALE COUNTY-326638- GO-RFQ / Establishment of to Strengthening Producer Org Request for Quota Single Stage - One E Under Imple mato nurseries & supply of t IDA / 59000 anizations and Value Chain Post Limited 32,000.00 0.00 2022-12-10 2023-02-22 2023-01-10 2023-02-04 tions nvelope mentation he seedlings to farmers for 4 Development 0 acres in Nyalani scheme KE-KWALE COUNTY-326639- GO-RFQ / Supply and installa tion of a water pump In Nyal ani Irrigation Scheme.DWK S Strengthening Producer Org Request for Quota Single Stage - One E Under Imple ubmersible drainage(waste w IDA / 59000 anizations and Value Chain Post Limited 18,000.00 0.00 2022-12-05 2022-12-15 2023-01-05 2023-01-12 tions nvelope mentation ater). Hea 24M, Discharge 88 Development m3/h, outlet 100mm 5.5kw st arter type DOL operating, cur rent 11.9A pump to be moun ted on floated for suspending it inside the KE-KWALE COUNTY-139538- Strengthening Producer Org Request for Quota Single Stage - One E GO-RFQ / SUPPLY AND DELIV IDA / 59000 anizations and Value Chain Post Limited 36,000.00 0.00 Canceled 2019-10-20 2019-11-18 2019-12-03 tions nvelope ERY OF CERTIFIED GREEN GR Development AM SEEDS KE-KWALE COUNTY-139545- Strengthening Producer Org GO-RFQ / SUPPLY AND DELIV Request for Quota Single Stage - One E IDA / 59000 anizations and Value Chain Post Limited 1,400.00 0.00 Canceled 2019-10-20 2019-11-18 2019-12-03 ERY OF 400,000ML OF FUNG tions nvelope Development ICIDES(KABENDAZIM) KE-KWALE COUNTY-344480- GO-RFQ / Purchase of 2 soil s Supporting County Communi Request for Quota Single Stage - One E Under Imple canners that uses near infra r IDA / 59000 Post Limited 18,000.00 0.00 2023-02-26 2023-04-05 2023-03-29 2023-04-05 ty-Led Development tions nvelope mentation ed technology and 2 hand he ld printers compatible to the scanners KE-KWALE COUNTY-350313- Supporting County Communi GO-DIR / Supply and delivery IDA / 59000 Post Direct Selection Direct - National 2,320.00 0.00 Completed 2023-03-20 2023-03-27 2023-03-25 2023-04-30 2023-04-13 2023-04-27 2023-05-03 ty-Led Development of 1160 hybrid mango seedli ngs KE-KWALE COUNTY-363606- Supporting Community-Driv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Purchase of 20 SAC IDA / 59000 Post Limited 23,076.92 0.00 2023-06-17 2023-07-16 2023-08-05 en Development tions nvelope ementation CO'S desktops and 20 printer s NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-KWALE COUNTY-274897- NC-DIR / M-shamba digital Pl Supporting County Communi atform License-Comprehensi IDA / 59000 Post Direct Selection Direct 12,320.00 10,215.58 Signed 2022-01-28 2022-01-22 2022-01-31 2022-01-22 2022-02-18 2022-07-09 2023-02-18 ty-Led Development ve license for digital extensio n, market linkage, monitorin g and evaluation KE-KWALE COUNTY-274903- NC-DIR / Purchase of softwar e license/services(content de velopment license, MoA INFO Supporting County Communi platform programing license, IDA / 59000 Post Direct Selection Direct 22,207.71 18,414.34 Signed 2022-01-28 2022-01-22 2022-01-31 2022-01-22 2022-02-18 2022-07-09 2023-02-18 ty-Led Development Advisory SMS bundle purchas es,Data collection, managem ent & supervision) for provisi on of advisory services to tar geted beneficiaries. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-KWALE COUNTY-178490- CS-CQS / RECRUITMENT OF S Supporting Community-Driv Consultant Qualifi IDA / 59000 Post Open - National 50,000.00 0.00 Signed 2020-07-15 2020-10-25 2020-07-29 2020-08-17 2020-12-17 2020-08-20 2021-04-26 2020-09-06 2021-12-31 ERVICE PROVIDER FOR APICU en Development cation Selection LTURE VALUE CHAIN KE-KWALE COUNTY-178487- Supporting Community-Driv Consultant Qualifi Under Implement CS-CQS / RECRUITMENT OF S IDA / 59000 Post Open - National 50,000.00 0.00 2020-07-15 2020-10-25 2020-07-29 2022-12-06 2020-08-17 2020-11-23 2020-08-20 2021-04-26 2020-09-06 2021-12-31 en Development cation Selection ation ERVICE PROVIDER FOR DAIRY VALUE CHAIN KE-KWALE COUNTY-178489- CS-CQS / RECRUITMENTOF S Supporting Community-Driv Consultant Qualifi Under Implement IDA / 59000 Post Open - National 50,000.00 0.00 2020-07-15 2020-10-25 2020-07-29 2020-08-17 2020-12-17 2020-08-20 2021-04-26 2020-09-06 2021-12-31 ERVICE PROVIDER FOR GREE en Development cation Selection ation N GRAMS VALUE CHAIN Page 2 KE-KWALE COUNTY-178488- CS-CQS / RECRUITMENT OF S Supporting Community-Driv Consultant Qualifi Under Implement IDA / 59000 Post Open - National 50,000.00 0.00 2020-07-15 2020-09-18 2020-07-29 2020-08-17 2020-10-15 2020-08-20 2021-04-26 2020-09-06 2021-12-31 ERVICE PROVIDER FOR TOMA en Development cation Selection ation TO VALUE CHAIN KE-KWALE COUNTY-145854- Supporting Community-Driv Quality And Cost- CS-QCBS / procurement of se IDA / 59000 Post Open - National 200,000.00 0.00 Canceled 2019-11-15 2019-11-29 2019-12-13 2019-12-20 2019-12-27 2020-01-10 2020-01-21 2021-01-20 en Development Based Selection rvice providers INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 Third Village Investment Project (P146970) PROCUREMENT Kyrgyz Republic : Third Village Investment Project PLAN General Information Country: Kyrgyz Republic 2019-12-17 Bank’s Approval Date of the Original Procurement Plan: Revised Plan Date(s): (comma delineated, leave blank2023-05-30 if none) Project ID: P146970 GPN Date: 2022-11-22 Project Name: Third Village Investment Project Loan / Credit No: IDA / D0410, IDA / 56010, IDA / 67820, IDA / D7270 Community Development and Investment Agency Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process S Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Comple Description Component Review Type Method Amount (U ount (US$ and Recommendatio Signed Contract o. h cess (Y/N) isk ocument Type tatus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes tion S$) ) n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IDA-VIP3-HO-CW-NCB-20-1 / Construction of an additiona Single Stage - One 2021-01-1 l building for "Zhetigen" Kin IDA / D0410 Village Investments Post Request for Bids Open - National 152,173.91 132,012.63 Signed 2020-03-25 2020-04-17 2020-03-30 2020-05-11 2020-05-11 2020-06-10 2020-06-11 2020-07-15 2020-07-01 Envelope 1 dergarten in Beryu-Bash vill age, Ak-Suu region, Issyk-Ku l oblast IDA-VIP3-HO-CW-NCB-20-2 / Construction of a kindergart Single Stage - One 2021-01-1 IDA / D0410 Village Investments Post Request for Bids Open - National 143,500.00 468,937.48 Signed 2020-03-25 2020-04-17 2020-03-30 2020-05-11 2020-05-11 2020-06-10 2020-06-11 2020-07-15 2020-07-30 en for 100 places Ak-Sai vill Envelope 1 age, Ton region, Issyk-Kul o blast IDA-VIP3-HO-CW-NCB-20-3 / Construction of a kindergart Single Stage - One 2020-12-0 IDA / D0410 Village Investments Post Request for Bids Open - National 254,130.43 222,477.40 Signed 2020-02-21 2020-03-06 2020-02-26 2020-03-06 2020-04-08 2020-05-06 2020-05-08 2020-07-15 2020-06-12 2020-08-12 en for 50 places Zherge-Tal Envelope 9 village, Ak-Tala region, Nary n oblast IDA-VIP3-HO-CW-SH-20-3 / Construction of FAP in Kyzyl- Request for Quot Single Stage - One 2020-10-1 IDA / D0410 Village Investments Post Limited 28,418.48 31,135.12 Signed 2020-02-26 2020-02-21 2020-04-22 2020-03-17 Zhyldyz village, Zhumgal re ations Envelope 9 gion, Naryn oblast IDA-VIP3-HO-CW-NCB-20-4 / Construction of a kindergart Single Stage - One 2020-12-1 IDA / D0410 Village Investments Post Request for Bids Open - National 182,608.70 217,340.32 Signed 2020-02-24 2020-03-06 2020-02-29 2020-03-06 2020-04-11 2020-05-06 2020-05-11 2020-06-09 2020-06-15 2020-08-14 en for 50 places Zher-Kechk Envelope 2 yu village, Naryn region, Nar yn oblast IDA-VIP3-HO-CW-SH-20-6 / Construction of FAP in Tamc Request for Quot Single Stage - One 2020-11-2 IDA / D0410 Village Investments Post Limited 30,434.78 38,072.83 Signed 2020-03-30 2020-05-07 2020-05-25 2020-07-21 hy-Bulak village, Kara-Buura ations Envelope 1 region, Talas oblast IDA-VIP3-HO-CW-NCB-20-5 / Construction of a kindergart Single Stage - One 2020-12-1 IDA / D0410 Village Investments Post Request for Bids Open - National 258,695.65 205,590.46 Signed 2020-02-24 2020-03-06 2020-02-29 2020-03-06 2020-04-11 2020-08-05 2020-05-11 2020-08-13 2020-06-15 2020-08-21 en Ken-Aral village, Bakai-At Envelope 2 a region, Talas oblast IDA-VIP3-HO-CW-NCB-20-6 / Construction of a kindergart Single Stage - One 2020-12-1 IDA / D0410 Village Investments Post Request for Bids Open - National 227,991.99 226,285.69 Signed 2020-02-24 2020-03-06 2020-02-29 2020-03-06 2020-04-11 2020-05-06 2020-05-11 2020-06-09 2020-06-15 2020-07-21 en A.Ogonbaev village, Tala Envelope 2 s region, Talas oblast IDA-VIP3-HO-CW-NCB-20-7 / The device of a sewer collec Single Stage - One 2021-02-2 tor and connection to a city IDA / D0410 Village Investments Post Request for Bids Open - National 259,730.35 204,040.06 Signed 2020-05-04 2020-08-21 2020-05-09 2020-06-20 2020-09-11 2020-07-20 2020-09-23 2020-08-24 2020-10-16 Envelope 0 network in Nijnealarcha villa ge, Alamudun region, Chui o blast IDA-VIP3-HO-CW-SH-20-7 / Request for Quot Single Stage - One 2020-11-2 Asphalting of the road in Da IDA / D0410 Village Investments Post Limited 91,304.35 0.00 Canceled 2020-03-30 2020-05-25 ations Envelope 1 yyrbek village, Issyk-Ata reg ion, Chui oblast IDA-VIP3-HO-CW-SH-20-5 / Request for Quot Single Stage - One 2020-11-2 Construction of Library in Ot IDA / D0410 Village Investments Post Limited 45,652.17 0.00 Canceled 2020-03-30 2020-05-25 ations Envelope 1 tuk village, Naryn region, Na ryn oblast IDA-VIP3-HO-CW-SH-20-4 / Request for Quot Single Stage - One 2020-11-2 Construction of FAP in Chon- IDA / D0410 Village Investments Post Limited 39,565.00 0.00 Canceled 2020-03-30 2020-05-25 ations Envelope 1 Tash village, Tyup region, Is syk-Kul oblast IDA-VIP3-HO-CW-NCB-20-8 / Single Stage - One 2020-08-1 Construction of FAP in Chon- IDA / 56010 Village Investments Post Request for Bids Open - National 76,475.00 79,907.89 Signed 2020-04-24 2020-05-13 2020-04-29 2020-05-12 2020-06-10 2020-06-03 2020-07-10 2020-06-24 2020-07-31 2020-08-04 Envelope 5 Tash village, Tyup region, Is syk-Kul oblast IDA-VIP3-HO-CW-NCB-20-9 / Single Stage - One 2021-02-1 Construction of Library in Ot IDA / 56010 Village Investments Post Request for Bids Open - National 68,750.00 76,089.19 Signed 2020-04-27 2020-05-13 2020-05-02 2020-05-13 2020-06-13 2020-06-03 2020-07-13 2020-06-24 2020-08-17 2020-08-15 Envelope 3 tuk village, Naryn region, Na ryn oblast IDA-VIP3-HO-CW-SH-20-1 / Overhaul of school them. My Request for Quot Single Stage - One 2020-08-3 IDA / 56010 Village Investments Post Open - National 35,431.00 29,222.97 Completed 2020-02-17 2020-04-02 2020-03-26 rzakmatova in Kozhomkul vil ations Envelope 0 lage, Zhaiyl region, Chui obl ast IDA-VIP3-HO-CW-SH-20-2 / Request for Quot Single Stage - One 2020-09-1 Overhaul of kindergarten in IDA / 56010 Village Investments Post Open - National 65,625.00 45,323.76 Completed 2020-02-17 2020-04-13 2020-03-28 ations Envelope 0 Kaldyk village, Zhaiyl region , Chui oblast IDA-VIP3-HO-CW-NCB-20-10 Single Stage - One 2021-04-1 / Construction of GSV in Ak- IDA / D0410 Village Investments Post Request for Bids Open - National 102,958.00 91,295.42 Signed 2020-08-26 2020-09-04 2020-08-28 2020-09-18 2020-09-25 2020-10-18 2020-10-15 2020-11-15 2020-10-27 Envelope 4 Dobo village Bakai-Ata Ragi on, Talas Oblast IDA-VIP3-HO-CW-NCB-20-11 / Construction of kindergarte Single Stage - One 2021-10-0 IDA / 56010 Village Investments Post Request for Bids Open - National 519,484.00 401,429.27 Signed 2020-11-15 2020-12-02 2020-11-20 2020-12-02 2020-12-11 2020-12-23 2021-01-07 2021-01-26 2021-02-07 2021-02-26 n for 100 places in the Taldy Envelope 5 -Suu village, Tup Ragion, Iss yk-Kul oblast IDA-VIP3-HO-CW-NCB-20-12 / Construction of kindergarte Single Stage - One 2021-09-2 IDA / 56010 Village Investments Post Request for Bids Open - National 225,269.99 216,423.55 Signed 2020-12-09 2020-12-16 2020-12-10 2020-12-16 2020-12-31 2021-01-06 2021-01-30 2021-02-01 2021-02-28 2021-02-23 n for 50 places in the Dobol Envelope 6 u village, Naryn Ragion, Nar yn oblast IDA-VIP3-HO-CW-NCB-20-13 / Construction of kindergarte Single Stage - One 2021-08-3 IDA / 56010 Village Investments Post Request for Bids Open - National 225,707.41 215,418.47 Signed 2020-12-09 2020-12-16 2020-12-10 2020-12-16 2020-12-31 2021-01-06 2021-01-30 2021-02-05 2021-02-02 2021-02-20 n for 50 places in the Maym Envelope 1 ak village, Kara-Bura Ragion , Talas oblas IDA-VIP3-HO-CW-NCB-20-14 Single Stage - One 2021-08-1 / Repair of school in the villa IDA / 56010 Village Investments Post Request for Bids Open - National 194,077.52 198,757.36 Signed 2020-12-16 2020-12-25 2020-12-18 2020-12-28 2021-01-08 2021-01-15 2021-02-07 2021-02-03 2021-03-14 2021-02-18 Envelope 1 ge Stavropolovka, Zhayil ray on, Chui oblast IDA-VIP3-HO-CW-NCB-20-15 / Repair of the drinking wate Single Stage - One 2021-09-2 IDA / 56010 Village Investments Post Request for Bids Open - National 67,751.00 62,516.80 Signed 2021-02-10 2021-02-12 2021-02-11 2021-02-11 2021-03-04 2021-03-05 2021-04-03 2021-04-02 2021-04-29 2021-04-27 r supply system in the villag Envelope 6 e. Kadyraly, Ak-Tala rayon, Naryn oblast Page 1 IDA-VIP3-HO-CW-NCB-20-16 / Installation of lighting on th Single Stage - One 2021-11-0 e streets in the villages Zher IDA / 56010 Village Investments Post Request for Bids Open - National 42,730.00 48,268.97 Completed 2021-03-19 2021-03-19 2021-03-19 2021-04-09 2021-05-09 2021-05-09 2021-05-06 2021-06-09 2021-05-22 Envelope 6 -Kazar, Nizhniy-Nooruz, Druz hba Villages, Issyk-Ata Raion , Chuy Oblast IDA-VIP3-HO-CW-NCB-20-17 / Major Repair drinking wate Single Stage - One 2021-11-2 IDA / 56010 Village Investments Post Request for Bids Open - National 417,114.69 356,317.58 Completed 2021-04-09 2021-04-09 2021-04-09 2021-04-09 2021-04-30 2021-04-30 2021-05-30 2021-05-25 2021-06-28 2021-06-22 r system in the village Jyrgal Envelope 5 an Ak-Suu raijon Issyk-Kul o blast IDA-VIP3-HO-CW-NCB-20-18 / Major repair of kindergarte Single Stage - One 2021-11-2 IDA / 56010 Village Investments Post Request for Bids Open - National 294,029.83 0.00 Canceled 2021-04-02 2021-04-09 2021-04-02 2021-04-09 2021-04-23 2021-05-04 2021-05-23 2021-05-24 2021-06-23 n "ALENKA" in the village Pr Envelope 0 edtechenka Moscow rajion C hui oblast IDA-VIP3-HO-CW-NCB-20-19 / Construction of FAPs`in the Single Stage - One 2021-12-0 village Min-Bulak Bakai-Ata r IDA / 56010 Village Investments Post Request for Bids Open - National 134,529.40 89,501.47 Signed 2021-04-15 2021-04-23 2021-04-15 2021-04-23 2021-05-06 2021-05-14 2021-06-05 2021-06-23 2021-07-06 2021-08-25 Envelope 3 aijion Talas oblast and in the village Min-Bulak Typ rajion I ssyk-Kul oblast IDA-VIP3-HO-CW-NCB-20-20 Request for Bids / Construction of FAPs`in the Single Stage - One - Small Works SP 2021-12-1 village Ak-Bulun Tup raijion I IDA / 56010 Village Investments Post Request for Bids Open - National 106,382.00 92,992.83 Signed 2021-04-30 2021-05-21 2021-04-30 2021-05-21 2021-06-11 2021-06-20 2021-07-16 2021-07-21 2021-07-19 Envelope D (1 envelope pr 8 ssyk-Kul oblast and in the vil ocess) lage Kaiyndy-Bulak Ak-Talaa rajion Naryn oblast IDA-VIP3-HO-CW-NCB-20-18 Request for Bids /RT / Major repair of kinderg Single Stage - One - Small Works SP 2022-02-1 IDA / 56010 Village Investments Post Request for Bids Open - National 294,029.93 310,497.68 Signed 2021-05-27 2021-05-28 2021-06-01 2021-06-22 2021-06-22 2021-07-22 2021-07-21 2021-08-18 2021-08-26 arten "ALENKA" in the villag Envelope D (1 envelope pr 4 e Predtechenka Moscow raji ocess) on Chui oblast IDA-VIP3-HO-CW-NCB-20-21 / Construction of FAPs`in the Request for Bids village Jar-Bashy Internation Single Stage - One - Small Works SP 2022-03-0 IDA / 56010 Village Investments Post Request for Bids Open - National 114,282.76 53,199.76 Signed 2021-07-16 2021-07-16 2021-07-16 2021-08-06 2021-08-06 2021-09-05 2021-08-12 2021-10-06 2021-09-10 al AA Isyk-Ata district Chui Envelope D (1 envelope pr 5 oblast and in the village Bes ocess) h-Koruk Aleksandrovski AA Moscow district Chui oblast National Procure IDA-VIP3-HO-CW-NCB-20-22 ment Document - / Overhaul of the FAP buildin Single Stage - One 2022-05-2 IDA / 56010 Village Investments Post Request for Bids Open - National 1 Envelope proce 55,895.17 57,767.93 Signed 2021-09-07 2021-09-10 2021-09-07 2021-09-28 2021-10-01 2021-11-27 2021-10-20 2021-12-28 2021-11-17 g in the village Ozgorush Oz Envelope 7 ss (Non Bank-SP gorush AO Bakai-Ata rayon D) of Talas oblast IDA-VIP3-HO-CW-NCB-20-23 National Procure / Overhaul of the FAP buildin ment Document - g and improvement of the s Single Stage - One 2022-05-2 IDA / 56010 Village Investments Post Request for Bids Open - National 1 Envelope proce 51,029.51 0.00 Canceled 2021-09-07 2021-09-10 2021-09-07 2021-09-28 2021-11-27 2021-12-28 anitary and hygienic conditi Envelope 7 ss (Non Bank-SP ons of the kindergarten in th D) e village. Konorchok of Kono rchok AO Ak-Tala rayon Nar yn oblast National Procure IDA-VIP3-HO-CW-NCB-20-24 ment Document - / Renovation of high school Single Stage - One 2022-05-3 IDA / 56010 Village Investments Post Request for Bids Open - National 1 Envelope proce 56,713.16 56,418.69 Signed 2021-09-08 2021-09-10 2021-09-10 2021-10-01 2021-10-01 2021-11-30 2021-10-19 2021-12-31 2021-11-17 sanitary facilities. in with. Ky Envelope 0 ss (Non Bank-SP z-Molo Moscow rayon Chui o D) blast IDA-VIP3-HO-CW-SH-20-25 / Installation of sanitary facilit Request for Quot Request for Quot Single Stage - One 2022-04-2 ies in schools of villages Ken IDA / D0410 Village Investments Post Open - National ations (Non Bank 48,625.00 0.00 Canceled 2021-10-08 2021-11-28 ations Envelope 7 -Suu, Sary-Tologoi, San-Tash -SPD) of the San-Tash AA Tup distr ict Issyk-Kul oblast IDA-VIP3-HO-CW-NCB-20-23 National Procure /RT / Installation of sanitary ment Document - Single Stage - One 2022-05-0 facilities in schools of village IDA / D0410 Village Investments Post Request for Bids Open - National 1 Envelope proce 51,029.51 0.00 Canceled 2021-10-11 2021-10-11 2021-11-01 2021-11-29 2021-12-05 Envelope 4 s Ken-Suu, Sary-Tologoi, San ss (Non Bank-SP -Tash of the San-Tash AA Tu D) p district Issyk-Kul oblast IDA-VIP3-HO-CW-SH-20-25/ Request for Quot RT2 / Installation of sanitary Request for Quot Single Stage - One ations - Small Wo 2022-05-1 facilities in schools of village IDA / 56010 Village Investments Post Open - National 48,625.00 38,108.87 Completed 2021-11-15 2021-12-20 2021-12-16 ations Envelope rks (Emergency) 9 s Ken-Suu, Sary-Tologoi, San SPD -Competitive -Tash of the San-Tash AA Tu p district Issyk-Kul oblast IDA-VIP3-HO-CW-NCB-20-23 /RT2 / Overhaul of the FAP b Request for Bids uilding and improvement of Single Stage - One - Small Works SP 2022-06-1 the sanitary and hygienic co IDA / 56010 Village Investments Post Request for Bids Open - National 51,029.51 60,733.39 Signed 2021-11-19 2021-11-19 2021-11-19 2021-12-10 2021-11-19 2021-12-24 2022-01-11 2022-01-16 2022-01-29 Envelope D (1 envelope pr 5 nditions of the kindergarten ocess) in the village. Konorchok of Konorchok AO Ak-Tala rayon Naryn oblast ARIS-IDA-AF-VIP-3-CW-23-1 / Improving sanitary and hyg Request for Quot Pending Im ienic conditions and replacin Request for Quot Single Stage - One 2023-12-3 IDA / 56010 Village Investments Post Open - National ations (Non Bank 58,550.00 0.00 plementatio 2023-05-30 2023-07-04 g electrical wires and repair ations Envelope 1 -SPD) n s at the "Teremok" preschoo l educational establishment i n the village of Prigorodnoye ARIS-IDA-AF-VIP-3-CW-23-2 Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 / Replacing the roof of the s IDA / 67820 Village Investments Post Open - National ations (Non Bank 33,700.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 chool in Ozernoye village -SPD) n ARIS-IDA-AF-VIP-3-CW-23-3 Request for Quot Pending Im / Rehabilitation of indoor san Request for Quot Single Stage - One 2023-12-3 IDA / 67820 Village Investments Post Open - National ations (Non Bank 25,000.00 0.00 plementatio 2023-05-30 2023-07-04 itary facilities in the seconda ations Envelope 1 -SPD) n ry school in the village of Sa ry-Bulak ARIS-IDA-AF-VIP-3-CW-23-4 Request for Quot Pending Im / Replacing the interior and Request for Quot Single Stage - One 2023-12-3 IDA / 67820 Village Investments Post Open - National ations (Non Bank 25,000.00 0.00 plementatio 2023-05-30 2023-07-04 exterior doors of the second ations Envelope 1 -SPD) n ary school in the village of A k-Tyuz ARIS-IDA-AF-VIP-3-CW-23-5 / Installation of an indoor sa Request for Quot Pending Im nitary facilities in the second Request for Quot Single Stage - One 2023-12-3 IDA / 67820 Village Investments Post Open - National ations (Non Bank 33,000.00 0.00 plementatio 2023-05-30 2023-07-04 ary village of Ilyich village a ations Envelope 1 -SPD) n nd repair of indoor facilities i n the secondary school of So vetskoye village ARIS-IDA-AF-VIP-3-CW-23-6 Request for Quot Pending Im / Rehabilitation of indoor san Request for Quot Single Stage - One 2023-12-3 IDA / 67820 Village Investments Post Open - National ations (Non Bank 33,000.00 0.00 plementatio 2023-05-30 2023-07-04 itary facilities in the seconda ations Envelope 1 -SPD) n ry school of Kichi-Kemin villa ge ARIS-IDA-AF-VIP-3-CW-23-7 Request for Quot Pending Im / Repair of the sewage syste Request for Quot Single Stage - One 2023-12-3 IDA / 67820 Village Investments Post Open - National ations (Non Bank 25,000.00 0.00 plementatio 2023-05-30 2023-07-04 m of the "Kutu-Yan" kinderg ations Envelope 1 -SPD) n arten in Tolok village ARIS-IDA-AF-VIP-3-CW-23-8 Request for Quot Pending Im / Rehabilitation of the water Request for Quot Single Stage - One 2023-12-3 IDA / 67820 Village Investments Post Open - National ations (Non Bank 25,000.00 0.00 plementatio 2023-05-30 2023-07-04 supply system of a secondar ations Envelope 1 -SPD) n y school in the village of Tse linnyi Page 2 ARIS-IDA-AF-VIP-3-CW-23-9 Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 / Replacing the roof of the s IDA / 67820 Village Investments Post Open - National ations (Non Bank 33,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 econdary school building in -SPD) n Spartak Village ARIS-IDA-AF-VIP-3-CW-23-1 0 / Repairing the sewage sys Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 tem of the canteen and repa IDA / 67820 Village Investments Post Open - National ations (Non Bank 41,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 iring the indoor sanitary facil -SPD) n ities of the secondary school of Erkin-Sai village ARIS-IDA-AF-VIP-3-CW-23-1 Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 1 / Replacing the roof of the IDA / 67820 Village Investments Post Open - National ations (Non Bank 33,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 secondary school in Kamysh -SPD) n anovka village ARIS-IDA-AF-VIP-3-CW-23-1 2 / Repair of ventilation syst National Procure em and sanitary facilities an ment Document - Pending Im d replacement of windows a Single Stage - One 2024-02-2 IDA / 67820 Village Investments Post Request for Bids Open - National 1 Envelope proce 115,294.00 0.00 plementatio 2023-05-25 2023-05-30 2023-07-11 2023-08-10 2023-08-24 nd doors of the secondary s Envelope 0 ss (Non Bank-SP n chool named after Ch.Aitma D) tov and secondary school # 1. Installation of an outdoor toilet at the secondary scho ol #2 ARIS-IDA-AF-VIP-3-CW-23-1 3 / Repair of sanitary facilitie Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 s, electrical wiring, plumbing IDA / 67820 Village Investments Post Open - National ations (Non Bank 54,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 and sewage systems in the -SPD) n kindergarten in Krasnaya Re chka village ARIS-IDA-AF-VIP-3-CW-23-1 4 / Improving the energy effi Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 ciency (insulation of exterior IDA / 67820 Village Investments Post Open - National ations (Non Bank 65,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 walls and roofing) of Balasta -SPD) n n Kindergarten in Boz-Uchuk village ARIS-IDA-AF-VIP-3-CW-23-1 5 / Improving sanitary and h Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 ygienic conditions (installing IDA / 67820 Village Investments Post Open - National ations (Non Bank 13,640.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 hand-washing sinks) in the s -SPD) n chool named after Asanaliev in Otuz-Uul village ARIS-IDA-AF-VIP-3-CW-23-1 6 / Improving the energy effi Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 ciency (insulation of exterior IDA / 67820 Village Investments Post Open - National ations (Non Bank 37,580.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 walls and roofing) of the "Alt -SPD) n yn Beshik" kindergarten in O ktyabr Village ARIS-IDA-AF-VIP-3-CW-23-1 7 / Improvement of energy e Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 fficiency (installation of wind IDA / 67820 Village Investments Post Open - National ations (Non Bank 60,580.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 ows) at the school named af -SPD) n ter Mamakeev in the village of Teplokluchenka ARIS-IDA-AF-VIP-3-CW-23-1 8 / Improving energy efficie ncy (installation of windows) Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 and sanitary and hygienic co IDA / 67820 Village Investments Post Open - National ations (Non Bank 54,300.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 nditions (installation of hand -SPD) n -washing sinks) in school na med after Kirov in the villag e of Teplocluchenka ARIS-IDA-AF-VIP-3-CW-23-1 9 / Improvement of energy e Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 fficiency (insulation of exteri IDA / 67820 Village Investments Post Open - National ations (Non Bank 85,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 or walls) of the school name -SPD) n d after D. Imanov in Zheti-O guz village ARIS-IDA-AF-VIP-3-CW-23-2 0 / Improvement of sanitary Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 and hygienic conditions (rep IDA / 67820 Village Investments Post Open - National ations (Non Bank 54,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 air of sanitary facilities) in sc -SPD) n hools in Toru-Aygyr village a nd Sary-Kamysh village ARIS-IDA-AF-VIP-3-CW-23-2 Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 1 / Repair of sanitary facilitie IDA / 67820 Village Investments Post Open - National ations (Non Bank 64,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 s at Ch.Asekov Secondary S -SPD) n chool ARIS-IDA-AF-VIP-3-CW-23-2 Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 2 / Renovation of the FAP in IDA / 67820 Village Investments Post Open - National ations (Non Bank 33,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 the village of Epkin -SPD) n ARIS-IDA-AF-VIP-3-CW-23-2 Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 3 / Construction of a Family IDA / 67820 Village Investments Post Open - National ations (Non Bank 75,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 Practice Center (GFD) in Zha -SPD) n ny-Aryk village ARIS-IDA-AF-VIP-3-CW-23-2 Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 4 / Repair of FAP with the pu IDA / 67820 Village Investments Post Open - National ations (Non Bank 65,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 rchase of equipment in Kara -SPD) n -Suu village Request for Quot ARIS-IDA-AF-VIP-3-CW-23-2 Request for Quot Single Stage - One Pending Im 2023-12-3 IDA / 67820 Village Investments Post Open - National ations (Non Bank 70,450.00 0.00 2023-05-30 2023-07-04 5 / Construction of a FAP in ations Envelope plementatio 1 -SPD) Tendik village n Request for Quot ARIS-IDA-AF-VIP-3-CW-23-2 Request for Quot Single Stage - One Pending Im 2024-01-2 IDA / 67820 Village Investments Post Open - National ations (Non Bank 26,350.00 0.00 2023-05-30 2023-07-25 6 / Insulation of the school ( ations Envelope plementatio 1 -SPD) sports hall) n ARIS-IDA-AF-VIP-3-CW-23-2 Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 7 / Insulation of the school i IDA / 67820 Village Investments Post Open - National ations (Non Bank 95,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 n Oro-Bashy village -SPD) n ARIS-IDA-AF-VIP-3-CW-23-2 8 / Improving energy efficie Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 ncy and sanitary conditions IDA / 67820 Village Investments Post Open - National ations (Non Bank 25,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 (replacing windows and door -SPD) n s in the kindergarten and re pairing sanitary facilities) ARIS-IDA-AF-VIP-3-CW-23-2 9 / Improvement of sanitary Request for Quot Pending Im Request for Quot Single Stage - One 2024-01-2 and hygienic conditions (Inst IDA / 67820 Village Investments Post Open - National ations (Non Bank 54,000.00 0.00 plementatio 2023-05-30 2023-07-25 ations Envelope 1 allation of sanitary facilities i -SPD) n n the secondary school nam ed after Zh. Mambetov) ARIS-IDA-AF-VIP-3-CW-23-3 0 / Improvement of sanitary Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 condition, replacement of th IDA / 67820 Village Investments Post Open - National ations (Non Bank 54,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 e roof in the secondary scho -SPD) n ol named after U. Akynbeko v ARIS-IDA-AF-VIP-3-CW-23-3 Request for Quot Pending Im 1 / Replacing the heating sy Request for Quot Single Stage - One 2023-12-3 IDA / 67820 Village Investments Post Open - National ations (Non Bank 54,000.00 0.00 plementatio 2023-05-30 2023-07-04 stem, flooring the secondary ations Envelope 1 -SPD) n school named after Toichub ek uulu Zhanadil ARIS-IDA-AF-VIP-3-CW-23-3 Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 2 / Construction of a FAP in t IDA / 67820 Village Investments Post Open - National ations (Non Bank 41,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 he village of Kamash -SPD) n Page 3 ARIS-IDA-AF-VIP-3-CW-23-3 Request for Quot Pending Im 3 / Replacement of roof, win Request for Quot Single Stage - One 2023-12-3 IDA / 67820 Village Investments Post Open - National ations (Non Bank 54,000.00 0.00 plementatio 2023-05-30 2023-07-04 dows and exterior doors of t ations Envelope 1 -SPD) n he secondary school named after T.Aitmanbetov ARIS-IDA-AF-VIP-3-CW-23-3 4 / Replacement of roof, ove Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 rhaul of sanitary units and s IDA / 67820 Village Investments Post Open - National ations (Non Bank 41,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 ewage system of the kinder -SPD) n garten named after B.Sagyn dykov ARIS-IDA-AF-VIP-3-CW-23-3 5 / Overhaul of sanitary facil Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 ities in the secondary school IDA / 67820 Village Investments Post Open - National ations (Non Bank 49,500.00 0.00 plementatio 2023-06-10 2023-08-05 ations Envelope 1 of the village of Kara-Bulak, -SPD) n Kara-Bulak AA, Kemin distric t, Chui region ARIS-IDA-AF-VIP-3-CW-23-3 6 / Improving the sanitary a nd hygienic condition of the Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 school canteen of the Tabal IDA / 67820 Village Investments Post Open - National ations (Non Bank 53,200.00 0.00 plementatio 2023-06-10 2023-08-05 ations Envelope 1 dinovskaya secondary schoo -SPD) n l in the village of Kara-Jygac h, Kara-Jygach AA, Alamudu n district, Chui region ARIS-IDA-AF-VIP-3-CW-23-3 7 / Replacement of electric h Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 eaters in Baitik uulu, Kanaev IDA / 67820 Village Investments Post Open - National ations (Non Bank 33,750.00 0.00 plementatio 2023-06-10 2023-08-05 ations Envelope 1 secondary school in the villa -SPD) n ge of Oktyabrsky AA, Alamu dun district, Chui region ARIS-IDA-AF-VIP-3-CW-23-3 Request for Quot Pending Im 8 / Construction of a FAP in t Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 76,200.00 0.00 plementatio 2023-06-12 2023-08-07 he village of Zelenoye, Zhan ations Envelope 3 -SPD) n y-Zhersky AA, Sokuluk distri ct, Chui region ARIS-IDA-AF-VIP-3-CW-23-3 Request for Quot Pending Im 9 / Construction of a FAP in t Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 34,100.00 0.00 plementatio 2023-06-12 2023-08-07 he village of Saz, Sazski AA, ations Envelope 3 -SPD) n Sokuluk district, Chui region ARIS-IDA-AF-VIP-3-CW-23-4 Request for Quot Pending Im 0 / Construction of a FAP in t Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 30,000.00 0.00 plementatio 2023-06-12 2023-08-07 he village of Saz, Sazski AA, ations Envelope 3 -SPD) n Sokuluk district, Chui region ARIS-IDA-AF-VIP-3-CW-23-4 1 / Improving energy efficie Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 ncy (insulation of external w IDA / 67820 Village Investments Post Open - National ations (Non Bank 38,850.00 0.00 plementatio 2023-06-12 2023-08-07 ations Envelope 3 alls) of the school of Yu. Tu -SPD) n manov, Ak-Bulun AA, Ak-Suu district, Issyk-Kul region ARIS-IDA-AF-VIP-3-CW-23-4 2 / Redevelopment of the pr Request for Quot Pending Im emises of the social instituti Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 40,500.00 0.00 plementatio 2023-06-12 2023-08-07 on "Nauka" for a dental offic ations Envelope 3 -SPD) n e with the purchase of equip ment from AA Orgochor Jeti- Oguz district of Issyk-Kul reg ion ARIS-IDA-AF-VIP-3-CW-23-4 3 / Improvement of the sanit ary and hygienic condition (r Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 epair of bathrooms) in the s IDA / 67820 Village Investments Post Open - National ations (Non Bank 49,100.00 0.00 plementatio 2023-06-12 2023-08-07 ations Envelope 3 chool named after K. Orozov -SPD) n in the village of Korumdu, K um-Bel AA, Issyk-Kul district, Issyk-Kul region ARIS-IDA-AF-VIP-3-CW-23-4 4 / Improving energy efficie Request for Quot Pending Im ncy (insulation of external w Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 45,900.00 0.00 plementatio 2023-06-12 2023-08-07 alls) of a school in the villag ations Envelope 3 -SPD) n e of Chon-Oruktu, Orukta AA , Issyk-Kul district, Issyk-Kul region ARIS-IDA-AF-VIP-3-CW-23-4 5 / Improving sanitary and h Request for Quot Pending Im ygienic conditions (renovati Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 20,650.00 0.00 plementatio 2023-06-12 2023-08-07 on of sanitary facilities) in O ations Envelope 3 -SPD) n rto-Oruktu school, Orukta A A, Issyk-Kul district, Issyk-Ku l region ARIS-IDA-AF-VIP-3-CW-23-4 6 / Improving energy efficie ncy (insulation of external w Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 alls and roofs) of the school IDA / 67820 Village Investments Post Open - National ations (Non Bank 22,800.00 0.00 plementatio 2023-06-12 2023-08-07 ations Envelope 3 cafeteria in the school of E. -SPD) n Kerimkaziev in the village of Temir, Temirovsky AA, Issyk -Kul district, Issyk-Kul region ARIS-IDA-AF-VIP-3-CW-23-4 7 / Improvement of energy e Request for Quot Pending Im fficiency (installation of wind Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 52,200.00 0.00 plementatio 2023-06-12 2023-08-07 ows) at the K. Kudaiberdiev ations Envelope 3 -SPD) n school in Kashat village, Te mirovsky AA, Issyk-Kul distri ct, Issyk-Kul region ARIS-IDA-AF-VIP-3-CW-23-4 8 / Improving energy efficie Request for Quot Pending Im ncy (insulation of external w Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 37,400.00 0.00 plementatio 2023-06-12 2023-08-07 alls and roofs) of a building i ations Envelope 3 -SPD) n n the village. Ak-Bulak Ak-B ulak AA Tyup district Issyk-K ul region ARIS-IDA-AF-VIP-3-CW-23-4 9 / Improvement of sanitary Request for Quot Pending Im facilities in the secondary sc Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 36,400.00 0.00 plementatio 2023-06-12 2023-08-07 hool. A. Koichumanova of Ak ations Envelope 3 -SPD) n -Moyun village, Ak-Moyun A A, At-Bashyn district, Naryn region ARIS-IDA-AF-VIP-3-CW-23-5 Request for Bids Pending Im 0 / Repair of a kindergarten i Single Stage - One - Small Works SP 2024-01-3 IDA / D7270 Village Investments Post Request for Bids Open - National 144,870.00 0.00 plementatio 2023-06-07 2023-06-08 2023-06-29 2023-07-29 2023-08-04 n the village of Chaek, Chae Envelope D (1 envelope pr 1 n k AA, Jumgal district, Naryn r ocess) egion ARIS-IDA-AF-VIP-3-CW-23-5 1 / Replacement of the heati Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 ng system and the roof of th IDA / 67820 Village Investments Post Open - National ations (Non Bank 32,650.00 0.00 plementatio 2023-06-12 2023-08-07 ations Envelope 3 e school of Son-Kul AA, Koch -SPD) n kor district, Naryn region ARIS-IDA-AF-VIP-3-CW-23-5 Request for Quot Pending Im 2 / Replacement of windows Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 31,500.00 0.00 plementatio 2023-06-12 2023-08-07 in the school of the village o ations Envelope 3 -SPD) n f Cholpon, Cholpon AA, Koch kor district, Naryn region Page 4 ARIS-IDA-AF-VIP-3-CW-23-5 3 / Repair of the heating sys Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 tem of the 2nd building of th IDA / 67820 Village Investments Post Open - National ations (Non Bank 26,200.00 0.00 plementatio 2023-06-12 2023-08-07 ations Envelope 3 e school in the village of Epk -SPD) n in, Cholpon AA, Kochkor dist rict, Naryn region ARIS-IDA-AF-VIP-3-CW-23-5 4 / Replacing windows and i Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 nstalling a bathroom in a se IDA / 67820 Village Investments Post Open - National ations (Non Bank 52,300.00 0.00 plementatio 2023-06-12 2023-08-07 ations Envelope 3 condary school with. March -SPD) n 8, Ak-Kuduk AA, Naryn distri ct, Naryn region ARIS-IDA-AF-VIP-3-CW-23-5 Request for Quot Pending Im 5 / Construction of a FAP in t Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 66,400.00 0.00 plementatio 2023-06-12 2023-08-07 he village of Echki-Bashi, On ations Envelope 3 -SPD) n -Archinskiy AA, Naryn distric t, Naryn region ARIS-IDA-AF-VIP-3-CW-23-5 6 / Repair of the kindergarte Request for Quot Pending Im n Chon-Alysh (replacement Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 91,500.00 0.00 plementatio 2023-06-12 2023-08-07 of internal lighting, replace ations Envelope 3 -SPD) n ment of floors, interior decor ation of classrooms) of Baka i-Ata AA, Bakai-Ata district, Talas region ARIS-IDA-AF-VIP-3-CW-23-5 7 / Repair of the building of t Request for Quot Pending Im he secondary school named Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 53,400.00 0.00 plementatio 2023-06-12 2023-08-07 after D. Duishebaev for prim ations Envelope 3 -SPD) n ary classes of Boo-Terek AA, Bakai-Ata district, Talas regi on ARIS-IDA-AF-VIP-3-CW-23-5 8 / Construction of an exten Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 sion to the kindergarten "Ar IDA / 67820 Village Investments Post Open - National ations (Non Bank 56,800.00 0.00 plementatio 2023-06-12 2023-08-07 ations Envelope 3 cha-Beshik" in the village of -SPD) n Archagul, Shekersky AA, Kar a-Buura district, Talas regio n ARIS-IDA-AF-VIP-3-CW-23-5 9 / Replacement of windows, Request for Quot Pending Im installation of internal lightin Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 41,500.00 0.00 plementatio 2023-06-12 2023-08-07 g and repair of the heating s ations Envelope 3 -SPD) n ystem in the kindergarten N ariste AA Kyrgyzstan, Manas district, Talas region ARIS-IDA-AF-VIP-3-CW-23-6 Request for Quot Pending Im 0 / Repair of the FAP in the v Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 15,100.00 0.00 plementatio 2023-06-12 2023-08-07 illage of Zhyyde, Uch-Korgo ations Envelope 3 -SPD) n n AA, Manas district, Talas r egion ARIS-IDA-AF-VIP-3-CW-23-6 1 / Construction of a buildin Request for Quot Pending Im Request for Quot Single Stage - One 2024-01-3 g for a FDC (Family Doctors IDA / 67820 Village Investments Post Open - National ations (Non Bank 67,000.00 0.00 plementatio 2023-07-01 2023-08-03 ations Envelope 0 Center) in the Kaynazarova -SPD) n village, Kainazarov AA, Socu luc district, Chui oblast ARIS-IDA-AF-VIP-3-CW-23-6 2 / Renovation of indoor sani Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 tary facilities of secondary s IDA / 67820 Village Investments Post Open - National ations (Non Bank 37,000.00 0.00 plementatio 2023-07-05 2023-08-07 ations Envelope 3 chool in Internatsionalnoye -SPD) n village, Internatsionalny AA, Issyk-Ata district, Chui oblas t ARIS-IDA-AF-VIP-3-CW-23-6 Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-2 3 / Construction of FAP in th IDA / 67820 Village Investments Post Open - National ations (Non Bank 65,000.00 0.00 plementatio 2023-07-05 2023-08-26 ations Envelope 2 e Telman village Issyk-Ata di -SPD) n strict Chui oblast ARIS-IDA-AF-VIP-3-CW-23-6 Request for Quot Pending Im 4 / Construction of FAP in th Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 64,700.00 0.00 plementatio 2023-07-05 2023-08-07 e Jany-Turmush village Iskri ations Envelope 3 -SPD) n nski AA Chui district Chui obl ast ARIS-IDA-AF-VIP-3-CW-23-6 Request for Quot Pending Im 5 / Renovation of a kinderga Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 34,000.00 0.00 plementatio 2023-07-05 2023-08-07 rten in the Kirov village of K ations Envelope 3 -SPD) n urpuldek AA Panfilocski distr ict Chui oblast ARIS-IDA-AF-VIP-3-CW-23-6 6 / Installation of sanitary fa Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 cilities of the secondary sch IDA / 67820 Village Investments Post Open - National ations (Non Bank 25,300.00 0.00 plementatio 2023-07-05 2023-08-07 ations Envelope 3 ool in the Kyzyl-Oy village S -SPD) n uusamyr AA, Zhaiyl district Chui oblast ARIS-IDA-AF-VIP-3-CW-23-6 7 / Repair of sanitary units o Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 f a secondary school in the IDA / 67820 Village Investments Post Open - National ations (Non Bank 6,800.00 0.00 plementatio 2023-07-05 2023-08-07 ations Envelope 3 Madaniyat village Onbir-Zhyl -SPD) n ga AA, Chui district Chyi obl ast ARIS-IDA-AF-VIP-3-CW-23-6 8 / Establishing a medical ro Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 om for medical staff at the s IDA / 67820 Village Investments Post Open - National ations (Non Bank 3,500.00 0.00 plementatio 2023-07-05 2023-08-07 ations Envelope 3 econdary school in the Kayir -SPD) n ma village, Chui district Chui oblast ARIS-IDA-AF-VIP-3-CW-23-6 Request for Quot Pending Im 9 / Repair of FAP in the Vino Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 33,000.00 0.00 plementatio 2023-07-05 2023-08-07 gradnoye village of Saylyk A ations Envelope 3 -SPD) n A Chui district Chui oblast ARIS-IDA-AF-VIP-3-CW-23-7 Request for Quot Pending Im 0 / Repair of sanitary units o Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 5,000.00 0.00 plementatio 2023-07-05 2023-08-07 f kindergarten in the Saylyk ations Envelope 3 -SPD) n village of Saylyk AA Chui dis trict Chui oblast ARIS-IDA-AF-VIP-3-CW-23-7 Request for Quot Pending Im 1 / Heating system of FAP in Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 6,800.00 0.00 plementatio 2023-07-05 2023-08-07 the Saylyk village of Saylyk ations Envelope 3 -SPD) n AA Chui district Chui oblast ARIS-IDA-AF-VIP-3-CW-23-7 Request for Quot Pending Im 2 / Construction of a FAP in I Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 35,000.00 0.00 plementatio 2023-07-05 2023-08-07 chke Zhergez village of Boz ations Envelope 3 -SPD) n unchuk AA, Ak-suu district, I ssyk-kul oblast ARIS-IDA-AF-VIP-3-CW-23-7 3 / Installation of a septic ta nk in the kindergarten and r Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 ehabilitation of the school w IDA / 67820 Village Investments Post Open - National ations (Non Bank 20,300.00 0.00 plementatio 2023-07-05 2023-08-07 ations Envelope 3 ater supply system in the Zh -SPD) n arkynbaevo village of Abdyr ahman AA, Issyk-Kul district Issyk-kul oblast Page 5 ARIS-IDA-AF-VIP-3-CW-23-7 4 / Improving sanitary and h ygiene conditions (partial re Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 placement of sanitary equip IDA / 67820 Village Investments Post Open - National ations (Non Bank 17,700.00 0.00 plementatio 2023-07-05 2023-08-07 ations Envelope 3 ment in the sanitary units a -SPD) n nd kitchen) of the kindergart en in the Ton village of Ton AA, Ton district, Issyk-kul ob last ARIS-IDA-AF-VIP-3-CW-23-7 Request for Quot Pending Im 5 / Warming the school in th Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 38,000.00 0.00 plementatio 2023-07-05 2023-08-07 e Shor-Bulak village, Ulakol ations Envelope 3 -SPD) n AA, Ton district, Issyk-kul ob last ARIS-IDA-AF-VIP-3-CW-23-7 6 / Improvement of energy e Request for Quot Pending Im fficiency (installation of exte Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 12,000.00 0.00 plementatio 2023-07-05 2023-08-11 rior doors and a vestibule) o ations Envelope 7 -SPD) n f the school in the Tuura-Su u-2 village, Ton district, Issy k-kul oblast ARIS-IDA-AF-VIP-3-CW-23-7 7 / Improving energy efficie Request for Quot Pending Im ncy (installation of electrical Request for Quot Single Stage - One 2024-02-2 IDA / 67820 Village Investments Post Open - National ations (Non Bank 32,300.00 0.00 plementatio 2023-07-05 2023-08-26 convectors) in the school in ations Envelope 2 -SPD) n the Ak-Olon village of Kok- Moinok AA, Ton district, Issy k-kul oblast ARIS-IDA-AF-VIP-3-CW-23-7 Request for Quot Pending Im 8 / Construction of FAP in th Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 54,000.00 0.00 plementatio 2023-07-05 2023-08-07 e Santash 3 ferma village of ations Envelope 3 -SPD) n San-Tash AA, Tyup district, I ssyk-kul oblast ARIS-IDA-AF-VIP-3-CW-23-7 Request for Quot Pending Im 9 / Renovation of FAP in the Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 20,000.00 0.00 plementatio 2023-07-05 2023-08-07 Ara-Kol village of Cholpon A ations Envelope 3 -SPD) n A, Kochkor district, Naryn ob last ARIS-IDA-AF-VIP-3-CW-23-8 Request for Quot Pending Im 0 / Construction of a FAP in t Request for Quot Single Stage - One 2024-02-2 IDA / 67820 Village Investments Post Open - National ations (Non Bank 73,000.00 0.00 plementatio 2023-07-05 2023-08-26 he Kyzyl-Charba village of A ations Envelope 2 -SPD) n k-Dobo AA, Bakai-Ata distric t, Talas oblast ARIS-IDA-AF-VIP-3-CW-23-8 1 / Installation of ventilation Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 system in theM.Chaldanbae IDA / 67820 Village Investments Post Open - National ations (Non Bank 20,300.00 0.00 plementatio 2023-07-05 2023-08-07 ations Envelope 3 v secondary school, Bakayir -SPD) n AA, Kara-Buura district, Tala s oblast ARIS-IDA-AF-VIP-3-CW-23-8 Request for Quot Pending Im 2 / Construction of a FAP in t Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 34,700.00 0.00 plementatio 2023-07-05 2023-08-07 he Sogot village, Pokrovka A ations Envelope 3 -SPD) n A, Manas district, Talas obla st ARIS-IDA-AF-VIP-3-CW-23-8 3 / Redesigning the school b Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 uilding for a kindergarten for IDA / 67820 Village Investments Post Open - National ations (Non Bank 53,400.00 0.00 plementatio 2023-07-05 2023-08-07 ations Envelope 3 50 children in the Aral villag -SPD) n e of Aral AA, Talas district,T alas oblast ARIS-IDA-AF-VIP-3-CW-23-8 Request for Quot Pending Im 4 / Construction of a FAP in t Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 52,000.00 0.00 plementatio 2023-07-05 2023-08-07 he Ak-Zhar village of Talas d ations Envelope 3 -SPD) n istrict, Talas oblast ARIS-IDA-AF-VIP-3-CW-23-8 5 / Construction of an additi Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 onal building for FAP in the IDA / 67820 Village Investments Post Open - National ations (Non Bank 47,200.00 0.00 plementatio 2023-07-05 2023-08-07 ations Envelope 3 Kara-Suu village of Kara-Suu -SPD) n AA, Talas district, Talas obla st ARIS-IDA-AF-VIP-3-CW-23-8 6 / Construction of an additi Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 onal building for 25 children IDA / 67820 Village Investments Post Open - National ations (Non Bank 53,400.00 0.00 plementatio 2023-07-05 2023-08-07 ations Envelope 3 for the kindergarten named -SPD) n after A. Eshalieva of Omurali ev AA, Talas district, Talas o blast IDA-VIP3-HO-CW-16-05 / Co Capacity Building of Local S nstruction of a kindergarten Single Stage - One IDA / 56010 elf-Governments and Comm Prior Request for Bids Open - National 0.00 347,529.04 Signed 2016-10-03 2016-09-30 2016-10-19 2016-10-20 for 100 places in Tosor v., T Envelope unities amga AO, Jeti-Oguz Raion, Is syk-Kul Region GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-VIP3-HO-GOODS-SH-20- Request for Quot Single Stage - One 3 / personal protective equip IDA / D0410 Village Investments Post Limited 99,800.00 88,621.41 Signed 2020-04-24 2020-05-06 2020-05-08 2020-05-19 2020-05-29 2020-05-21 ations Envelope ment for work in the centers of COVID-19 IDA-VIP3-HO-EQ-NCB-20-7 / Purchase of special equipme Single Stage - One IDA / 56010 Village Investments Post Request for Bids Open - National 91,304.00 117,736.29 Signed 2020-11-05 2020-11-06 2020-11-05 2020-11-06 2020-11-26 2020-11-27 2020-12-17 2020-12-09 2021-01-17 2020-12-29 2021-05-17 nt for the removal of SHW T Envelope uz AA, Chui oblast IDA-VIP3-HO-EQ-NCB-20-8 / Purchase of special equipme Single Stage - One IDA / 56010 Village Investments Post Request for Bids Open - National 87,296.00 72,307.85 Signed 2020-11-05 2020-11-06 2020-11-05 2020-11-06 2020-11-26 2020-11-27 2020-12-17 2020-12-10 2021-01-17 2020-12-29 2021-05-17 nt for loading and transporti Envelope ng goods Nurjanov AA, Talas oblast IDA-VIP3-HO-EQ-NCB-20-9 / Purchase of electrical equip Single Stage - One IDA / 56010 Village Investments Post Request for Bids Open - National 68,500.00 0.00 Canceled 2020-11-04 2020-11-27 2020-11-04 2020-11-25 2020-12-18 2020-12-16 2020-12-29 2021-01-16 2021-03-17 ment for the reconstruction Envelope of VL-6-0,4 kV Kabak AA, Na ryn oblast IDA-VIP3-HO-EQ-NCB-20-9/ RT1 / Purchase of electrical Single Stage - One IDA / 56010 Village Investments Post Request for Bids Open - National 68,500.00 0.00 Canceled 2021-01-18 2021-01-20 2021-02-10 2021-03-12 2021-04-14 2021-06-13 equipment for the reconstru Envelope ction of VL-6-0,4 kV Kabak A A, Naryn oblast IDA-VIP3-GOODS-SH-22-1 / Request for Quot Single Stage - One Purhase of Firnitures for sch IDA / 56010 Village Investments Post Open - National 80,000.00 78,720.96 Signed 2022-03-03 2022-04-03 2022-04-21 2022-06-02 ations Envelope ool and kindergartens of 12 AA IDA-VIP3-GOODS-SH-22-2 / Request for Quot Single Stage - One Purhase of Office equipment IDA / 56010 Village Investments Post Open - National 80,500.00 88,409.65 Signed 2022-02-26 2022-03-29 2022-04-20 2022-05-28 ations Envelope for school and kindergartens of 12 AA IDA-VIP3-GOODS-SH-22-3 / Request for Quot Single Stage - One Purhase of kitchen equipme IDA / 56010 Village Investments Post Open - National 46,000.00 31,930.69 Signed 2022-02-26 2022-03-29 2022-04-20 2022-05-28 ations Envelope nt for school and kindergart ens of 12 AA Page 6 IDA-VIP3-EQ-NCB-20-9/RT2 / Purchase of electrical equi Single Stage - One IDA / 56010 Village Investments Post Request for Bids Open - National 68,500.00 84,582.00 Signed 2022-03-10 2022-02-12 2022-03-10 2022-03-31 2022-03-15 2022-04-14 2022-03-17 2022-05-13 2022-05-01 2022-06-12 pment for the reconstruction Envelope of VL-6-0,4 kV Kabak AA, Na ryn oblast IDA-VIP3-HO-GOODS-SH-22- 2 / Purchase of office equip ments and furnitures for the Request for Quot Single Stage - One IDA / 56010 Project Management Post Open - National 63,000.00 115,952.24 Signed 2022-02-18 2022-03-25 2022-04-20 2022-05-24 Project Team in the central ations Envelope office also for the Regional o ffice team and for CTSOs of all oblasts. IDA-AFVIP3-HO-GOODS-SH- Capacity Building of Local S 23-1 / Purchase of services o Request for Quot Single Stage - One IDA / 56010 elf-Governments and Comm Post Open - National 21,000.00 0.00 Canceled 2023-01-23 2023-03-12 2023-05-11 f internet provider for install ations Envelope unities ation of wi-fi hotspots for VIP -3 AF target areas IDA-AFVIP3-HO-GOODS-DS- Capacity Building of Local S 23-2 / Purchase of services o Pending Impl IDA / 56010 elf-Governments and Comm Post Direct Selection Direct - National 21,000.00 0.00 2023-03-06 2023-03-09 2023-03-15 2023-05-14 f internet provider for install ementation unities ation of wi-fi hotspots for VIP -3 AF target areas ARIS-IDA-AF-VIP-3-GOODS-2 Request for Quot Single Stage - One Pending Impl 3-1 / Purchase of special ma IDA / 67820 Village Investments Post Open - National 41,000.00 0.00 2023-05-30 2023-07-04 2023-12-31 ations Envelope ementation chinery (waste collection tru ck) ARIS-IDA-AF-VIP-3-GOODS-2 3-2 / Purchase of equipment Request for Quot Single Stage - One Pending Impl IDA / 67820 Village Investments Post Open - National 33,000.00 0.00 2023-05-30 2023-07-25 2024-01-21 and furniture for the FAP in ations Envelope ementation Kazhy-Saz and Ton villages ARIS-IDA-AF-VIP-3-GOODS-2 3-3 / Purchase of equipment Request for Quot Single Stage - One Pending Impl IDA / 67820 Village Investments Post Open - National 33,000.00 0.00 2023-05-30 2023-07-04 2023-12-31 for the kitchen of Nur Zheles ations Envelope ementation i kindergarten Kuugandy a/a Talas district ARIS-IDA-AF-VIP-3-GOODS-2 3-4 / Purchase of equipment Request for Quot Single Stage - One Pending Impl IDA / 67820 Village Investments Post Open - National 4,900.00 0.00 2023-07-05 2023-08-26 2024-02-22 and furniture for the FAP in t ations Envelope ementation he Telek AA of Moscovski dis trict Chui oblast ARIS-IDA-AF-VIP-3-GOODS-2 3-5 / Purchase of equipment Request for Quot Single Stage - One Pending Impl and furniture for the FAP in t IDA / 67820 Village Investments Post Open - National 10,000.00 0.00 2023-07-05 2023-08-07 2024-02-03 ations Envelope ementation he Kara-Shaar and Ottuk vill ages of Ton AA, Ton district, Issyk-Kul oblast ARIS-IDA-AF-VIP-3-GOODS-2 3-6 / Purchase of special eq uipment for FDC (Family Do Request for Quot Single Stage - One Pending Impl IDA / 67820 Village Investments Post Open - National 22,700.00 0.00 2023-07-05 2023-08-07 2024-02-03 ctors Center) (dental office) ations Envelope ementation in the Kara-Talaa village, Ul akol AA, Ton district, Issyk-k ul oblast ARIS-IDA-AF-VIP-3-GOODS-2 3-7 / Purchase of equipment Request for Quot Single Stage - One Pending Impl and furniture for the FAP in t IDA / 67820 Village Investments Post Open - National 8,300.00 0.00 2023-07-05 2023-08-07 2024-02-03 ations Envelope ementation he Kok-Moinok-1 village of K ok-Moinok AA, Ton district, I ssyk-kul oblast NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Techni Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) t (US$) Notice equest for Proposals as Issued Proposals / Minutes cal Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-VIP3-S-CQ-20-4 / Devel opment of detailed design e stimates for the installation Consultant Qualifi IDA / D0410 Village Investments Post Open - National 15,000.00 31,208.89 Signed 2020-07-13 2020-07-14 2020-08-03 2020-09-07 2020-10-13 2020-09-14 2020-12-07 2020-09-28 2020-12-11 2020-12-27 of lighting on the streets of cation Selection Zher-Kazar, Nizhniy-Nooruz, Druzhba Villages, Issyk-Ata Raion, Chuy Oblast IDA-VIP3-S-CQ-20-5 / develo pment of detailed design est imates for the capital repair Consultant Qualifi of the drinking water sup-ply IDA / D0410 Village Investments Post Open - National 30,000.00 12,277.54 Signed 2020-07-13 2020-08-13 2020-08-03 2020-09-07 2020-09-11 2020-09-14 2020-10-28 2020-09-28 2020-10-29 2020-12-27 cation Selection system in Zhyrgalan Village, Ak-Suy Raion, Issyk-Kul Obla st and in Kadyraly Village, A k-Talaa Raion, Naryn Oblast IDA-VIP3-S-CQ-20-6 / develo pment of detailed design est imates for the capital repair Consultant Qualifi IDA / D0410 Village Investments Post Open - National 15,000.00 12,026.61 Signed 2020-07-13 2020-08-17 2020-08-03 2020-09-07 2020-10-15 2020-09-14 2020-11-16 2020-09-28 2020-12-08 2020-12-27 of the building of the Alen-k cation Selection a kindergarten in the village of Predtechenka, Moskovski y Raion, Chuy Oblast IDA-VIP3-V-CQ-2020-16 / Pr Capacity Building of Local S Consultant Qualifi IDA / D0410 Post Open - National 2,000.00 3,713.63 Signed 2020-08-18 2020-10-26 2020-09-08 2020-10-13 2020-10-23 2020-10-18 2020-11-17 2020-10-28 2020-12-08 2021-01-26 eparing Audio and Video Les elf-Governments and Comm cation Selection sons unities IDA-VIP-S-CQ-20-7 / develop ment of detailed design esti mates for the construction o Consultant Qualifi IDA / D0410 Village Investments Post Open - National 15,000.00 0.00 Canceled 2020-07-24 2020-08-07 2020-09-13 2020-09-16 2020-09-18 2020-12-17 f the building for the GFD (G cation Selection roup of Family Doctors) in A k-Dobo Village, Bakai-Ata Ra ion, Talas Oblast IDA-VIP3-V-CQ-2021-1 / Info Capacity Building of Local S Consultant Qualifi IDA / D0410 Post Open - National 6,000.00 13,895.36 Signed 2021-03-29 2021-04-30 2021-04-19 2021-05-17 2021-06-21 2021-05-20 2021-08-11 2021-05-26 2021-09-08 2021-08-24 rmation Compaign elf-Governments and Comm cation Selection unities IDA-VIP3-CQ-2021-2 / AF VI Capacity Building of Local S Consultant Qualifi P-3 Baseline survey and VIP IDA / D0410 elf-Governments and Comm Post Open - National 60,000.00 69,949.01 Signed 2021-05-28 2021-05-31 2021-06-11 2021-07-14 2021-07-09 2021-07-19 2021-10-14 2021-07-25 2021-12-14 2021-11-22 cation Selection -3 Impact Assessment unities ARIS-AUDIT-LCS-2021-1 / A Least Cost Selecti Open - Internation Under Implement IDA / 56010 Project Management Post 42,589.00 0.00 2021-08-10 2021-08-16 2021-08-24 2021-09-24 2021-09-21 2021-10-12 2021-10-19 2021-11-05 2021-11-26 2023-12-31 udit on al ation IDA-VIP3-CQ-2021-3 / Cond Capacity Building of Local S ucting Market and Value Ch Consultant Qualifi IDA / 56010 elf-Governments and Comm Post Open - National 60,000.00 76,672.08 Signed 2021-10-04 2021-10-05 2021-10-18 2021-11-17 2022-05-10 2021-11-22 2022-05-10 2021-12-02 2022-05-21 2022-04-01 ain Analysis research in the cation Selection unities target areas of the Project IDA-VIP-AF-CQS-2021-3 / De Capacity Building of Local S Consultant Qualifi velopment of training modul IDA / D0410 elf-Governments and Comm Post Open - National 70,000.00 0.00 Signed 2022-05-26 2022-06-14 2022-06-09 2022-06-22 2022-07-07 2022-10-12 2022-07-14 2022-11-15 2022-07-20 2022-10-18 cation Selection es and conducting training o unities f traineers Page 7 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Draft Negotiated Con Description Component Review Type Method Process Status Terms of Reference d/Selected Consultan Signed Contract Contract Completion o. h unt (US$) t (US$) tract t Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-VIP3-T-IC-2020-1 / Tech nical Supervision Engineer ( Individual Consult TSE) for subproject ‘Constru IDA / D0410 Village Investments Post Open 5,600.00 2,888.23 Signed 2020-02-26 2020-02-24 2020-04-15 2020-05-29 2020-05-06 2020-05-29 2020-06-10 2020-06-12 2020-12-07 ant Selection ction of FAP in Kyzyl-Zhyldyz village, Zhumgal region, Nar yn oblast’ IDA-VIP3-T-IC-2020-2 / Tech nical Supervision Engineer ( Individual Consult TSE) for subproject ‘Overha IDA / D0410 Village Investments Post Open 5,600.00 0.00 Canceled 2020-02-21 2020-02-18 2020-04-10 2020-05-01 2020-06-05 2020-12-02 ant Selection ul of school them. Myrzakma tova in Kozhomkul village, Z haiyl region, Chui oblast’ IDA-VIP3-T-IC-2020-3 / Tech nical Supervision Engineer ( Individual Consult TSE) for subproject ‘Overha IDA / D0410 Village Investments Post Open 5,600.00 2,888.31 Signed 2020-02-21 2020-02-18 2020-04-10 2020-05-22 2020-05-01 2020-06-04 2020-06-05 2020-06-06 2020-12-02 ant Selection ul of kindergarten in Kaldyk village, Zhaiyl region, Chui o blast’ IDA-VIP3-T-IC-2020-4 / Tech nical Supervision Engineer ( Individual Consult TSE) for subproject “Constru IDA / D0410 Village Investments Post Open 5,600.00 2,954.24 Signed 2020-03-18 2020-03-16 2020-05-06 2020-08-03 2020-05-27 2020-08-03 2020-07-01 2020-08-06 2020-12-28 ant Selection ction of a kindergarten Ken- Aral village, Bakai-Ata regio n, Talas oblast” IDA-VIP3-T-IC-2020-5 / Tech nical Supervision Engineer ( Individual Consult TSE) for subproject “Constru IDA / D0410 Village Investments Post Open 5,600.00 3,211.66 Signed 2020-03-18 2020-03-16 2020-05-06 2020-08-03 2020-05-27 2020-08-04 2020-07-01 2020-08-06 2020-12-28 ant Selection ction of a kindergarten A.Og onbaev village, Talas region, Talas oblast” IDA-VIP3-T-IC-2020-6 / Tech nical Supervision Engineer ( Individual Consult TSE) for subproject “Constru IDA / D0410 Village Investments Post Open 5,600.00 4,002.26 Signed 2020-03-18 2020-03-16 2020-05-06 2020-08-03 2020-05-27 2020-08-04 2020-07-01 2020-08-06 2020-12-28 ant Selection ction of a kindergarten for 5 0 places Zherge-Tal village, Ak-Tala region, Naryn oblast ” IDA-VIP3-T-IC-2020-7 / Tech nical Supervision Engineer ( Individual Consult TSE) for subproject “Constru IDA / D0410 Village Investments Post Open 5,600.00 4,126.04 Signed 2020-03-18 2020-03-16 2020-05-06 2020-08-03 2020-05-27 2020-08-04 2020-07-01 2020-08-06 2020-12-28 ant Selection ction of a kindergarten for 5 0 places Zher-Kechkyu villag e, Naryn region, Naryn oblas t” IDA-VIP3-T-IC-2020-8 / Tech nical Supervision Engineer ( Individual Consult TSE) for subproject “Constru IDA / D0410 Village Investments Post Open 7,100.00 4,628.29 Signed 2020-05-19 2020-05-18 2020-07-07 2020-08-03 2020-07-28 2020-08-04 2020-09-01 2020-08-06 2021-02-28 ant Selection ction of a kindergarten for 1 00 places Ak-Sai village, Ton region, Issyk-Kul oblast” IDA-VIP3-T-IC-2020-9 / Tech nical Supervision Engineer ( TSE) for subproject “Constru Individual Consult IDA / D0410 Village Investments Post Open 7,100.00 5,133.08 Signed 2020-05-19 2020-05-18 2020-07-07 2020-08-03 2020-07-28 2020-08-04 2020-09-01 2020-08-06 2021-02-28 ction of an additional buildin ant Selection g for "Zhetigen" Kindergarte n in Beryu-Bash village, Ak-S uu region, Issyk-Kul oblast” IDA-VIP3-T-IC-2020-10 / Tec hnical Supervision Engineer Individual Consult (TSE) for subproject “Constr IDA / D0410 Village Investments Post Open 5,600.00 3,201.81 Completed 2020-05-19 2020-05-18 2020-07-07 2020-08-03 2020-07-28 2020-08-04 2020-09-01 2020-08-09 2021-02-28 2021-01-11 ant Selection uction of FAP in Tamchy-Bul ak village, Kara-Buura regio n, Talas oblast” IDA-VIP3-T-IC-2020-11 / Tec hnical Supervision Engineer Individual Consult (TSE) for subproject “Constr IDA / D0410 Village Investments Post Open 5,600.00 3,460.08 Completed 2020-05-20 2020-05-18 2020-07-08 2020-08-03 2020-07-29 2020-08-04 2020-09-02 2020-08-06 2021-03-01 2021-01-01 ant Selection uction of FAP in Chon-Tash v illage, Tyup region, Issyk-Kul oblast” IDA-VIP3-T-IC-2020-12 / Tec hnical Supervision Engineer Individual Consult (TSE) for subproject “Constr IDA / D0410 Village Investments Post Open 5,600.00 4,126.04 Signed 2020-05-20 2020-05-18 2020-07-08 2020-08-03 2020-07-29 2020-08-04 2020-09-02 2020-08-06 2021-03-01 ant Selection uction of Library in Ottuk vill age, Naryn region, Naryn ob last” IDA-VIP3-T-IC-2020-13 / Tec hnical Supervision Engineer (TSE) for subproject “The de Individual Consult IDA / D0410 Village Investments Post Open 5,600.00 2,617.09 Signed 2020-06-16 2020-05-20 2020-08-04 2020-10-19 2020-08-25 2020-10-19 2020-09-29 2020-10-21 2021-03-28 vice of a sewer collector and ant Selection connection to a city network in Nijnealarcha village, Alam udun region, Chui oblast” VIP-S-CQ-20-2 / The geo-ref erencing to the area design documents (DDE), calculatio n of the estimated cost of w IDA / D0410 Village Investments Post Direct Selection Direct 5,000.00 0.00 Canceled 2020-05-22 2020-08-13 2020-05-29 2020-06-03 2020-08-02 orks and materials, and con ducting supervision of the fa cility of Construction of a ki ndergarten for 50 children in the village of Maimak, Kara- Buura Raion IDA-VIP3-IC-20-13 / Develop ment Cost Estimate for the Individual Consult IDA / D0410 Village Investments Post Open 2,000.00 869.57 Signed 2020-07-13 2020-08-18 2020-08-17 2020-10-14 2020-08-20 2020-10-14 2020-08-26 2020-10-21 2020-11-24 Capital Repair of the buildin ant Selection g of School Stravopolovka of Jaiyl Ragion, Chui Region IDA-VIP-S-DC-20-3 / The ge o-referencing to the area of deteiled design documents ( DDE), calculation of the esti IDA / D0410 Village Investments Post Direct Selection Direct 13,500.00 12,195.12 Completed 2020-07-20 2020-07-23 2020-07-27 2020-08-03 2020-08-01 2020-08-16 2020-09-30 2020-10-31 mated cost of works and ma terials, and conducting supe rvision of the facility of Con struction of a kindergarten f or 100 children in the village of Taldy-Suu,IK IDA-VIP-S-DC-20-8 / author' s supervision Construction o f an additional building for " IDA / D0410 Village Investments Post Direct Selection Direct 2,000.00 1,460.18 Signed 2020-07-24 2020-08-13 2020-08-03 2020-08-19 2020-08-07 2020-08-27 2021-03-05 Zhetigen" Kindergarten in B eryu-Bash village, Ak-Suu re gion, Issyk-Kul oblast IDA-VIP-S-DC-20-9 / Author' s supervision of Constructio IDA / D0410 Village Investments Post Direct Selection Direct 2,000.00 730.09 Signed 2020-07-24 2020-08-13 2020-08-03 2020-08-19 2020-08-06 2020-08-27 2021-01-03 n of FAP in Tamchy-Bulak vil lage, Kara-Buura region, Tal as oblast IDA-VIP-S-DC-20-10 / Author 's supervision of constructio IDA / D0410 Village Investments Post Direct Selection Direct 2,000.00 878.40 Signed 2020-07-24 2020-08-13 2020-08-03 2020-08-19 2020-08-06 2020-08-27 2021-01-03 n of a kindergarten A.Ogonb aev village, Talas region, Tal as oblast Page 8 IDA-VIP-S-DC-20-11 / Author 's supervision of constructio IDA / D0410 Village Investments Post Direct Selection Direct 2,000.00 1,169.07 Signed 2020-07-24 2020-08-13 2020-08-03 2020-08-19 2020-08-06 2020-08-27 2021-01-03 n of a kindergarten Ken-Aral village, Bakai-Ata region, Tal as oblast IDA-VIP-S-DC-20-12 / Author 's supervision of сonstructio IDA / D0410 Village Investments Post Direct Selection Direct 2,000.00 1,226.87 Signed 2020-07-24 2020-08-13 2020-07-30 2020-08-19 2020-08-07 2020-08-27 2021-01-04 n of a kindergarten Zher-Kec hkyu village, Naryn region, Naryn oblast IDA-VIP-S-DC-20-13 / Author 's supervision of Constructio IDA / D0410 Village Investments Post Direct Selection Direct 2,000.00 1,746.01 Signed 2020-07-24 2020-08-13 2020-07-30 2020-08-19 2020-08-07 2020-08-27 2021-01-04 n of a kindergarten Zherge- Tal village, Ak-Tala region, N aryn oblast IDA-VIP-S-DC-20-14 / Author 's supervision of Constructio IDA / D0410 Village Investments Post Direct Selection Direct 1,322.00 1,155.89 Signed 2020-07-24 2020-08-13 2020-07-30 2020-08-19 2020-08-07 2020-08-28 2021-03-05 n of a kindergarten Ak-Sai vi llage, Ton region, Issyk-Kul o blast IDA-VIP-S-DC-20-15 / Author 's supervision of Constructio IDA / D0410 Village Investments Post Direct Selection Direct 2,000.00 1,469.34 Signed 2020-07-24 2020-08-13 2020-07-30 2020-08-19 2020-08-07 2020-08-28 2021-01-04 n of FAP in Chon-Tash villag e, Tyup region, Issyk-Kul obl ast IDA-VIP-S-DC-20-16 / Author 's supervision of Constructio IDA / D0410 Village Investments Post Direct Selection Direct 2,000.00 1,130.53 Signed 2020-07-24 2020-08-13 2020-07-30 2020-08-19 2020-08-07 2020-08-28 2021-01-04 n of Library in Ottuk village, Naryn region, Naryn oblast IDA-VIP-S-DC-20-1 / The ge o-referencing to the area of deteiled design documents ( DDE), calculation of the esti IDA / D0410 Village Investments Post Direct Selection Direct 5,500.00 4,728.87 Completed 2020-08-03 2020-08-13 2020-08-09 2020-08-24 2020-08-12 2020-08-27 2020-11-10 2020-11-27 mated cost of works and ma terials, and conducting supe rvision of the facility of Cons truction of a kindergarten fo r 50 children in the village of Dobolu, Naryn Raio IDA-VIP-S-DC-20-2 / The ge o-referencing to the area de sign documents (DDE), calc ulation of the estimated cost IDA / D0410 Village Investments Post Direct Selection Direct 5,500.00 4,728.87 Completed 2020-08-17 2020-08-24 2020-08-27 2020-08-24 2020-09-05 2020-08-27 2020-12-04 2020-11-27 of works and materials, and conducting supervision of th e facility of Construction of a kindergarten for 50 children in the village of Maimak, Kar a-Buura Raion IDA-VIP3-T-IC-2020-14 / Tec hnical supervision consultan Capacity Building of Local S t for sub projects of the cons Individual Consult IDA / D0410 elf-Governments and Comm Post Open 6,000.00 2,744.40 Signed 2020-10-21 2020-10-22 2020-11-12 2020-11-20 2020-11-13 2020-12-07 2020-11-17 2021-01-05 2021-07-15 truction of building for a gro ant Selection unities up of family doctors (FGP) in the village Ak-Dobo Talas ob last(3 cycle) IDA-VIP-S-DC-20-17 / Author 's supervision of the constru ction drainage collector and IDA / D0410 Village Investments Post Direct Selection Direct 2,500.00 2,563.50 Signed 2020-10-25 2020-11-13 2020-10-27 2020-10-26 2020-10-30 2021-01-07 2021-03-29 conection Bishkek City net i n the Chui oblast, Alamudun rajion, Nijnee Ala-Archa IDA-VIP-S-DC-20-18 / The g eo-referencing to the area o f deteiled design documents (DDE), calculation of the esti IDA / D0410 Village Investments Post Direct Selection Direct 18,115.00 14,246.62 Signed 2020-11-04 2020-11-04 2020-11-09 2020-11-05 2020-11-13 2020-12-10 2021-02-26 mated cost of works and ma terials, and conducting supe rvision of the facility of Cons truction of feldsher-obstetric station (FAP) in the villages. IDA-VIP3-T-IC-2020-15 / Tec hnical supervision consultan Individual Consult t for sub projects of the cons IDA / D0410 Village Investments Post Open 5,294.00 0.00 Canceled 2020-11-19 2020-11-20 2020-12-19 2020-12-22 2020-12-27 2021-09-23 ant Selection truction of Kindergarten for 100 places in the village Tal du-Suu Issyk-Kul (3 cycle) IDA-VIP3-T-IC-2020-16 / Tec hnical supervision consultan t for sub project of the сonst Individual Consult IDA / D0410 Village Investments Post Open 5,294.00 4,265.14 Signed 2020-12-16 2021-02-04 2021-01-14 2021-02-25 2021-01-15 2021-02-26 2021-01-21 2021-03-02 2021-10-18 ruction of kindergarten for 5 ant Selection 0 places in the Dobolu villag e, Naryn Ragion, Naryn obla st (3 cycle) IDA-VIP3-T-IC-2020-17 / Tec hnical supervision consultan t for sub project of the const Individual Consult IDA / D0410 Village Investments Post Open 5,294.00 0.00 Canceled 2020-12-16 2021-02-04 2021-01-01 2021-01-02 2021-01-21 2021-10-18 ruction of kindergarten for 5 ant Selection 0 places in the Maymak villa ge, Kara-Bura Ragion, Talas oblas (3 cycle) IDA-VIP3-IC-2020-18 / Selec tion of a consultant for the d evelopment of design estim Individual Consult ates for: IDA / D0410 Village Investments Post Open 1,647.00 0.00 Canceled 2020-12-16 2020-12-14 2021-01-14 2021-01-15 2021-01-21 2021-02-20 ant Selection "Repair of FAP, purchase of i nventory and equipment" in the village. Zhar-Bashy, Inte rnational AO, Issyk-Ata rayo n, Chui oblast " IDA-VIP3-T-IC-2020-18 / Tec hnical supervision consultan Individual Consult t for sub project of the Repai IDA / D0410 Village Investments Post Open 2,994.00 3,271.67 Signed 2021-01-06 2021-01-24 2021-02-08 2021-03-15 2021-02-08 2021-03-15 2021-02-13 2021-03-24 2021-09-11 ant Selection ring of school in the village Stavropolovka, Zhayil rayon, Chui oblast (3 cycle) IDA-VIP3-IC-2020-17 / Infras Capacity Building of Local S Individual Consult IDA / D0410 Post Open 5,835.00 0.00 Canceled 2020-11-19 2020-11-25 2020-12-20 2020-12-23 2020-12-25 2021-08-22 tructure Engineer elf-Governments and Comm ant Selection unities IDA-VIP3-T-IC-2021-1 / Tech nical supervision consultant Individual Consult for sub project of the Repairi IDA / D0410 Village Investments Post Open 2,948.00 3,361.79 Signed 2021-03-02 2021-03-04 2021-03-31 2021-05-13 2021-04-01 2021-05-13 2021-04-03 2021-05-15 2021-09-30 ant Selection ng water sistem in the Kadyr aly village Ak-Tala raijion Na ryn oblast IDA-VIP-S-DC-21-1 / Author' s supervision of the construc tion kindergarten for 50 plac IDA / D0410 Village Investments Post Direct Selection Direct 2,500.00 1,031.56 Signed 2021-03-03 2021-03-03 2021-03-18 2021-03-17 2021-03-21 2021-03-18 2021-10-17 es in the Maymak village Ka ra-Bura Rajion Talas oblast IDA-VIP-S-DC-21-2 / Author' s supervision of the construc IDA / D0410 Village Investments Post Direct Selection Direct 2,500.00 990.29 Signed 2021-03-03 2021-03-10 2021-03-18 2021-03-09 2021-03-21 2021-03-18 2021-10-17 tion kindergarten for 50 plac es in the Dobolu village Nar yn Rajion Naryn oblast IDA-VIP-S-DC-21-3 / Author' s supervision of the construc tion kindergarten for 100 pla IDA / D0410 Village Investments Post Direct Selection Direct 2,500.00 1,325.99 Signed 2021-03-03 2021-03-05 2021-03-18 2021-03-12 2021-03-21 2021-03-16 2021-10-17 ces in the Taldy-Suu village Tup Rajion Issyk-Kul oblast Page 9 IDA-VIP-S-DC-21-4 / Author' s supervision of Capital Rep IDA / D0410 Village Investments Post Direct Selection Direct 2,500.00 0.00 Canceled 2021-03-12 2021-03-18 2021-03-17 2021-03-20 2021-08-17 air Water System in the villa ge Kadyraly Naryn oblast (3 Cicle) IDA-VIP3-IC-2021-1 / Buisin Capacity Building of Local S Individual Consult IDA / D0410 Post Open 3,300.00 0.00 Canceled 2021-03-12 2021-04-12 2021-04-15 2021-04-24 2021-08-22 ess Planning Trainer elf-Governments and Comm ant Selection unities IDA-VIP3-IC-TR-2021-2 / Bus Capacity Building of Local S Individual Consult iness Planning and Financial IDA / D0410 elf-Governments and Comm Post Open 700.00 1,178.75 Signed 2021-03-29 2021-04-02 2021-04-29 2021-06-21 2021-04-30 2021-08-02 2021-05-02 2021-08-14 2021-08-30 ant Selection Literacy Trainer in the Naryn unities oblast IDA-VIP3-IC-TR-2021-3 / Bus Capacity Building of Local S Individual Consult iness Planning and Financial IDA / D0410 elf-Governments and Comm Post Open 700.00 1,178.75 Signed 2021-03-29 2021-04-02 2021-04-27 2021-06-21 2021-04-28 2021-06-21 2021-04-30 2021-08-14 2021-08-28 ant Selection Literacy Trainer in the Talas unities oblast IDA-VIP3-IC-TR-2021-4 / Bus Capacity Building of Local S Individual Consult iness Planning and Financial IDA / D0410 elf-Governments and Comm Post Open 700.00 1,178.75 Signed 2021-03-29 2021-04-02 2021-04-27 2021-06-21 2021-04-28 2021-08-02 2021-04-30 2021-08-14 2021-08-28 ant Selection Literacy Trainer in the Issyk- unities Kul oblast IDA-VIP3-IC-TR-2021-5 / Bus Capacity Building of Local S Individual Consult iness Planning and Financial IDA / D0410 elf-Governments and Comm Post Open 700.00 1,178.75 Signed 2021-03-29 2021-04-02 2021-04-27 2021-06-21 2021-04-28 2021-08-02 2021-04-30 2021-08-14 2021-08-28 ant Selection Literacy Trainer in the Chui unities oblst (1) IDA-VIP3-IC-TR-2021-6 / Bus Capacity Building of Local S Individual Consult iness Planning and Financial IDA / D0410 elf-Governments and Comm Post Open 700.00 1,178.75 Signed 2021-03-29 2021-04-02 2021-04-27 2021-06-21 2021-04-28 2021-08-02 2021-04-30 2021-08-14 2021-08-28 ant Selection Literacy Trainer in the Chui unities oblst (2) IDA-VIP3-IC-2021-2 / Senior Capacity Building of Local S Individual Consult Economist (Local Markets an IDA / D0410 elf-Governments and Comm Post Open 4,400.00 8,414.76 Signed 2021-03-31 2021-03-30 2021-04-30 2021-04-28 2021-05-02 2021-04-30 2021-05-07 2021-05-02 2021-11-03 ant Selection d Buisiness Expert) unities IDA-VIP3-IC-2021-3 / Consul Capacity Building of Local S tant for the development of IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 4,000.00 5,212.56 Signed 2021-03-31 2021-04-15 2021-04-03 2021-04-16 2021-04-12 2021-04-20 2021-07-11 Project Operational Manual f unities or VIP-3 AF IDA-VIP3-IC-SSS-TR-2021-7 Capacity Building of Local S / Trainer for basic trainings IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-24 2021-04-30 2021-05-25 2021-07-29 of Operational Manual of Pr unities oject in the Naryn oblast (1) IDA-VIP3-IC-SSS-TR-2021-8 Capacity Building of Local S / Trainer for basic trainings IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-08-23 2021-04-30 2021-05-25 2021-07-29 of Operational Manual of Pr unities oject in the Chui oblast (1) IDA-VIP3-IC-SSS-TR-2021-9 Capacity Building of Local S / Trainer for basic trainings IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-23 2021-04-30 2021-05-25 2021-07-29 of Operational Manual of Pr unities oject in the Chui oblast (2) IDA-VIP3-IC-SSS-TR-2021-1 Capacity Building of Local S 0 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.31 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Chui oblast (3) IDA-VIP3-IC-SSS-TR-2021-1 Capacity Building of Local S 1 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.31 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Issyk-Kul oblast (1) IDA-VIP3-IC-SSS-TR-2021-1 Capacity Building of Local S 2 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.31 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Naryn oblast (2) IDA-VIP3-IC-SSS-TR-2021-1 Capacity Building of Local S 3 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.31 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Chui oblast (4) IDA-VIP3-IC-SSS-TR-2021-1 Capacity Building of Local S 4 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Issyk-Kul oblast (2) IDA-VIP3-IC-SSS-TR-2021-1 Capacity Building of Local S 5 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 722.33 Signed 2021-04-19 2021-04-29 2021-04-24 2021-06-08 2021-04-30 2021-07-20 2021-07-29 s of Operational Manual of P unities roject in the Chui oblast (5) IDA-VIP3-IC-SSS-TR-2021-1 Capacity Building of Local S 7 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-29 2021-05-25 2021-07-28 s of Operational Manual of P unities roject in the Chui oblast (7) IDA-VIP3-IC-SSS-TR-2021-1 Capacity Building of Local S 8 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Chui oblast (8) IDA-VIP3-IC-SSS-TR-2021-1 Capacity Building of Local S 9 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Talas oblast (1) IDA-VIP3-IC-SSS-TR-2021-2 Capacity Building of Local S 0 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-05-19 2021-05-25 2021-08-17 s of Operational Manual of P unities roject in the Chui oblast (9) IDA-VIP3-IC-SSS-TR-2021-2 Capacity Building of Local S 1 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Chui oblast (10) IDA-VIP3-IC-SSS-TR-2021-2 Capacity Building of Local S 2 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.38 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Issyk-Kul oblast (3) IDA-VIP3-IC-SSS-TR-2021-2 Capacity Building of Local S 3 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.38 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Talas oblast (2) IDA-VIP3-IC-SSS-TR-2021-2 Capacity Building of Local S 4 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.38 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Naryn oblast (3) Page 10 IDA-VIP3-IC-SSS-TR-2021-2 Capacity Building of Local S 5 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.38 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Chui oblast (11) IDA-VIP3-IC-SSS-TR-2021-2 Capacity Building of Local S 6 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.38 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Issyk-Kul oblast (4) IDA-VIP3-IC-SSS-TR-2021-2 Capacity Building of Local S 7 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.38 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Naryn oblast (4) IDA-VIP3-IC-SSS-TR-2021-2 Capacity Building of Local S 8 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,591.47 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Naryn oblast (4) IDA-VIP3-IC-SSS-TR-2021-2 Capacity Building of Local S 9 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Talas oblast (3) IDA-VIP3-IC-SSS-TR-2021-3 Capacity Building of Local S 0 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Naryn oblast (5) IDA-VIP3-IC-SSS-TR-2021-3 Capacity Building of Local S 1 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Chui oblast (13) IDA-VIP3-IC-SSS-TR-2021-3 Capacity Building of Local S 2 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Chui oblast (14) IDA-VIP3-IC-SSS-TR-2021-3 Capacity Building of Local S 3 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Talas oblast (4) IDA-VIP3-IC-SSS-TR-2021-3 Capacity Building of Local S 4 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Issyk-Kul oblast (6) IDA-VIP3-IC-SSS-TR-2021-3 Capacity Building of Local S 5 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,591.47 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Chui oblast (14) IDA-VIP3-IC-SSS-TR-2021-3 Capacity Building of Local S 6 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,945.13 Signed 2021-04-19 2021-04-30 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Chui oblast (15) IDA-VIP3-T-IC-2021-2 / Tech nical supervision consultant Individual Consult for sub project of the Major r IDA / D0410 Village Investments Post Open 3,800.00 3,932.67 Signed 2021-05-03 2021-05-06 2021-06-03 2021-09-02 2021-06-06 2021-09-02 2021-06-10 2021-10-02 2022-01-06 ant Selection epair kindergarten Alenka in the Predtechenka village Ch ui oblast (3 cycle) IDA-VIP3-T-IC-2021-3 / Tech nical supervision consultant Individual Consult for sub project of the Repairi IDA / D0410 Village Investments Post Open 4,800.00 0.00 Canceled 2021-05-03 2021-06-07 2021-06-08 2021-06-10 2022-03-07 ant Selection ng water sistem in the Jyrgal an village Tup raijion Issyk-K ul oblast (3 cycle) IDA-VIP3-T-IC-2021-4 / Tech nical supervision consultant Individual Consult for sub project of the сonstr IDA / D0410 Village Investments Post Open 3,200.00 0.00 Canceled 2021-05-04 2021-06-04 2021-06-07 2021-06-09 2021-12-06 ant Selection uction of FAP`in the village Min-Bulak Bakai-Ata raijion T alas oblast (3 cycle) IDA-VIP3-T-IC-2021-5 / Tech nical supervision consultant Individual Consult for sub project of the сonstr IDA / D0410 Village Investments Post Open 3,200.00 0.00 Canceled 2021-05-03 2021-06-05 2021-06-06 2021-06-08 2021-12-05 ant Selection uction of FAP`in the village Min-Bulak Typ rajion Issyk-K ul oblast (3 cycle) IDA-VIP3-T-IC-2021-6 / Tech nical supervision consultant for sub project Installation of Individual Consult IDA / 56010 Village Investments Post Open 2,948.00 1.00 Signed 2021-05-17 2021-05-05 2021-06-17 2021-06-30 2021-06-20 2021-06-30 2021-06-24 2021-07-02 2021-12-21 lighting on the streets in vill ant Selection ages Zher-Kazar, Nizhniy-No oruz, Druzhba Villages, Issyk -Ata Raion, Chuy Oblast IDA-VIP3-T-IC-2021-7 / Tech nical supervision consultant Individual Consult for sub project of the Constr IDA / 56010 Village Investments Post Open 2,948.00 2,368.93 Signed 2021-05-17 2021-05-06 2021-06-17 2021-07-23 2021-06-20 2021-07-23 2021-06-24 2021-07-27 2021-12-21 ant Selection uction of FAP in the village Min-Bulak Bakai-Ata raijion T alas oblast IDA-VIP3-IC-2020-19 / Nary Capacity Building of Local S n Regional Specialist for Soc Individual Consult IDA / D0410 elf-Governments and Comm Post Open 6,000.00 4,291.43 Signed 2021-06-01 2021-05-25 2021-06-30 2021-07-26 2021-07-01 2021-07-27 2021-07-03 2021-08-03 2021-12-31 ial Mobilization, Capacity Bui ant Selection unities lding and Gender Developm ent IDA-VIP-S-DC-21-5 / Author' s supervision of the Installati on of lighting on the streets IDA / D0410 Village Investments Post Direct Selection Direct 2,500.00 722.33 Signed 2021-06-01 2021-06-08 2021-06-16 2021-06-08 2021-06-19 2021-07-20 2021-12-16 in villages Zher-Kazar, Nizhn iy-Nooruz, Druzhba Villages, Issyk-Ata Raion, Chuy Oblast (3 Cicle) IDA-VIP-S-DC-21-6 / Author' s supervision of the Major R epair drinking water system IDA / D0410 Village Investments Post Direct Selection Direct 10,700.00 2,058.40 Signed 2021-06-03 2021-06-08 2021-06-18 2021-06-09 2021-06-21 2021-07-16 2022-03-18 in the village Jyrgalan Ak-Su u raijon Issyk-Kul oblast (3 Cicle) IDA-VIP3-IC-2021-4 / Сonsul tant for the development of detailed design estimates fo r installation of sanitary facil Individual Consult IDA / D0410 Village Investments Post Open 1,176.00 1,315.56 Signed 2021-06-15 2021-06-15 2021-07-13 2021-07-12 2021-07-13 2021-07-19 2021-07-18 2021-07-23 2021-08-17 ities in a secondary school i ant Selection n the villages of Santash 3-f erma, Sary-Tologoi, Ken-Suu , Baizak, Santash AO, Tyup r ayon, Issyk-Kul oblast Page 11 IDA-VIP3-IC-2021-6 / Сonsul tant for the development of detailed design estimates fo Individual Consult IDA / D0410 Village Investments Post Open 1,176.00 1.14 Signed 2021-06-16 2021-06-15 2021-07-14 2021-07-13 2021-07-14 2021-07-12 2021-07-19 2021-07-23 2021-08-18 r the renovation of a FAP an ant Selection d purchase of inventory in t he village of Ozgorush, Ozgu rush AO, Bakai-Ata rayon, T alas oblast IDA-VIP3-IC-2021-7 / Сonsul tant for the development of detailed design estimates fo Individual Consult r the repair of sanitary facilit IDA / D0410 Village Investments Post Open 1,176.00 825.21 Signed 2021-06-16 2021-06-15 2021-07-14 2021-07-12 2021-07-14 2021-07-22 2021-07-19 2021-07-24 2021-08-18 ant Selection ies in the secondary school i n the village of Kyz-Molo, Ts elinniy AO, Moskovskiy rayo n, Chuy oblast IDA-VIP3-IC-2021-5 / Consul tant for the development of DED for the renovation of a FAP, the purchase of furnitur Individual Consult IDA / D0410 Village Investments Post Open 1,176.00 750.97 Signed 2021-06-16 2021-06-14 2021-07-14 2021-07-12 2021-07-14 2021-07-20 2021-07-19 2021-07-23 2021-08-18 e, office equipment, and the ant Selection installation of a water suppl y system with sanitary facilit ies in a kindergarten in the v illage of Konorchok, Ak-Taal a rayon, Naryn obl IDA-VIP3-IC-2021-8 / Techni cal supervision consultant fo Individual Consult r sub project of the Construc IDA / D0410 Village Investments Post Open 2,948.00 4,543.90 Signed 2021-07-22 2021-08-05 2021-08-22 2021-09-06 2021-08-25 2021-09-07 2021-08-29 2021-09-09 2022-02-25 ant Selection tion of FAP in the village Ak- Bulun Tup Ragion Issyk-Kul oblast IDA-VIP3-IC-2021-9 / Techni cal supervision consultant fo Individual Consult r sub project of the Construc IDA / D0410 Village Investments Post Open 2,948.00 0.00 Canceled 2021-07-22 2021-08-22 2021-08-25 2021-08-29 2022-02-25 ant Selection tion of FAP in the village Min -Bulak Bakai-Ata raijion Tala s oblast IDA-VIP3-T-IC-2021-10 / Tec hnical supervision consultan Individual Consult t for sub project of the Const IDA / D0410 Village Investments Post Open 2,948.00 4,131.14 Signed 2021-08-09 2021-08-05 2021-09-08 2021-09-03 2021-09-11 2021-09-06 2021-09-16 2021-09-09 2022-03-15 ant Selection ruction of FAP in the village Kaiyndy Bulak Ak-Tala raijio n Naryn oblast IDA-VIP3-T-IC-2021-11 / Tec hnical supervision consultan Individual Consult t for sub project of the Const IDA / D0410 Village Investments Post Open 2,948.00 3,361.55 Signed 2021-08-09 2021-08-05 2021-09-08 2021-09-14 2021-09-11 2021-09-16 2021-09-16 2021-09-21 2022-03-15 ant Selection ruction of FAP in the village J ar-Bashy Issyk-Ata district C hui oblast IDA-VIP-S-DC-21-7 / Author Supervision of Construction of feldsher-obstetric station IDA / D0410 Village Investments Post Direct Selection Direct 5,325.00 2,416.83 Signed 2021-08-12 2021-09-24 2021-08-18 2021-09-27 2021-08-29 2021-12-02 2022-02-25 (FAP) in the villages Ak-Bulu n, Min-Bulak, Kaindy-Bulak, Min-Bulak, Besh-kooruk, Jar- Bashy IDA-VIP3-IC-2021-10 / Monit IDA / 56010 Project Management Post Direct Selection Direct 2,625.00 2,589.59 Signed 2021-09-22 2021-10-01 2021-09-28 2021-10-04 2021-10-01 2021-10-05 2021-12-31 oring and MIS specialist IDA-VIP3-T-IC-2020-5/RT1 / I Individual Consult IDA / D0410 Village Investments Post Open 5,835.00 6,429.17 Signed 2021-01-28 2021-02-01 2021-03-18 2021-03-17 2021-04-08 2021-04-13 2021-05-13 2021-04-14 2021-11-09 nfrastructure Engineer ant Selection IDA-VIP3-T-IC-2021-12 / Tec hnical supervision consultan Individual Consult t for sub project of the Major IDA / 56010 Village Investments Post Open 2,948.00 4,670.57 Signed 2021-11-16 2021-11-19 2021-12-13 2021-12-13 2021-12-17 2021-12-13 2021-12-24 2021-12-14 2022-06-22 ant Selection Repair of Building FAP in the Ozgorysh village Bakai-Ata d istrict Talas oblast IDA-VIP-S-DC-21-8 / Author Supervision of Construction of Major repair of kindergart IDA / 56010 Village Investments Post Direct Selection Direct 5,325.00 1,007.37 Signed 2021-12-07 2021-12-08 2021-12-21 2021-12-06 2021-12-26 2021-11-06 2022-06-24 en "ALENKA" in the village P redtechenka Moscow rajion Chui oblast IDA-VIP3-AF-IC-2022-1 / CD Capacity Building of Local S Individual Consult Under Implement SO for the Alamudun rayon IDA / D0410 elf-Governments and Comm Post Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 ant Selection ation of the Chui oblast unities IDA-VIP3-AF-IC-2022-2 / CD Capacity Building of Local S Individual Consult IDA / D0410 Post Open 8,325.00 5,288.46 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-02 2022-02-11 2022-02-02 2022-02-13 2022-02-04 2022-12-31 SO for the Zhayil rayon of th elf-Governments and Comm ant Selection e Chui oblast unities IDA-VIP3-AF-IC-2022-3 / CD Capacity Building of Local S Individual Consult IDA / D0410 Post Open 8,325.00 5,236.74 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-02 2022-02-11 2022-02-02 2022-02-13 2022-02-04 2022-12-31 SO for the Kemin rayon of th elf-Governments and Comm ant Selection e Chui oblast unities IDA-VIP3-AF-IC-2022-4 / CD Capacity Building of Local S Individual Consult SO for the Moskova rayon of IDA / D0410 elf-Governments and Comm Post Open 8,325.00 5,236.74 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-02 2022-02-11 2022-02-02 2022-02-13 2022-02-04 2022-12-31 ant Selection the Chui oblast unities IDA-VIP3-AF-IC-2022-5 / CD Capacity Building of Local S Individual Consult SO for the Panfilov rayon of IDA / D0410 elf-Governments and Comm Post Open 8,325.00 5,344.13 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-02 2022-02-11 2022-02-02 2022-02-13 2022-02-04 2022-12-31 ant Selection the Chui oblast unities IDA-VIP3-AF-IC-2022-6 / CD Capacity Building of Local S Individual Consult SO for the Sokuluk rayon of IDA / D0410 elf-Governments and Comm Post Open 8,325.00 5,344.13 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-02 2022-02-11 2022-02-02 2022-02-13 2022-02-15 2022-12-31 ant Selection the Chui oblast unities IDA-VIP3-AF-IC-2022-7 / CD Capacity Building of Local S Individual Consult IDA / D0410 Post Open 8,325.00 5,344.13 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-02 2022-02-11 2022-02-02 2022-02-13 2022-02-04 2022-12-31 SO for the Chui rayon of the elf-Governments and Comm ant Selection Chui oblast unities IDA-VIP3-AF-IC-2022-8 / CD Capacity Building of Local S Individual Consult SO for the Ysyk-Ata rayon of IDA / D0410 elf-Governments and Comm Post Open 8,325.00 5,344.13 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-02 2022-02-11 2022-02-02 2022-02-13 2022-02-04 2022-12-31 ant Selection the Chui oblast unities IDA-VIP3-AF-IC-2022-9 / CD Capacity Building of Local S Individual Consult Under Implement SO for the Ak-Tala rayon of t IDA / 56010 elf-Governments and Comm Post Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 ant Selection ation he Naryn oblast unities IDA-VIP3-AF-IC-2022-10 / C Capacity Building of Local S Individual Consult DSO for the At-Bashy rayon IDA / D0410 elf-Governments and Comm Post Open 8,325.00 6,470.59 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-01 2022-02-11 2022-02-01 2022-02-13 2022-02-04 2022-12-31 ant Selection of the Naryn oblast unities IDA-VIP3-AF-IC-2022-11 / C Capacity Building of Local S Individual Consult DSO for the Zhumgal rayon IDA / D0410 elf-Governments and Comm Post Open 8,325.00 6,470.59 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-01 2022-02-11 2022-02-03 2022-02-13 2022-02-04 2022-12-31 ant Selection of the Naryn oblast unities IDA-VIP3-AF-IC-2022-12 / C Capacity Building of Local S Individual Consult DSO for the Kochkor rayon o IDA / D0410 elf-Governments and Comm Post Open 8,325.00 6,470.59 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-01 2022-02-11 2022-02-01 2022-02-13 2022-02-04 2022-12-31 ant Selection f the Naryn oblast unities IDA-VIP3-AF-IC-2022-13 / C Capacity Building of Local S Individual Consult DSO for the Naryn rayon of t IDA / D0410 elf-Governments and Comm Post Open 8,325.00 5,628.23 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-01 2022-02-11 2022-02-01 2022-02-13 2022-02-04 2022-12-31 ant Selection he Naryn oblast unities IDA-VIP3-AF-IC-2022-14 / C Capacity Building of Local S Individual Consult Under Implement DSO for the Ak-Suu rayon of IDA / D0410 elf-Governments and Comm Post Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 ant Selection ation the Issyk-Kul oblast unities Page 12 IDA-VIP3-AF-IC-2022-15 / C Capacity Building of Local S Individual Consult Under Implement DSO for the Jeti-Oguz rayon IDA / D0410 elf-Governments and Comm Post Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 ant Selection ation of the Issyk-Kul oblast unities IDA-VIP3-AF-IC-2022-16 / C Capacity Building of Local S Individual Consult DSO for the Ton rayon of the IDA / D0410 elf-Governments and Comm Post Open 8,325.00 5,628.23 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-01 2022-02-11 2022-02-01 2022-02-13 2022-02-04 2022-12-31 ant Selection Issyk-Kul oblast unities IDA-VIP3-AF-IC-2022-17 / C Capacity Building of Local S Individual Consult Under Implement DSO for the Tup rayon of the IDA / D0410 elf-Governments and Comm Post Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 ant Selection ation Issyk-Kul oblast unities IDA-VIP3-AF-IC-2022-18 / C Capacity Building of Local S Individual Consult DSO for the Issyk-Kul rayon IDA / D0410 elf-Governments and Comm Post Open 8,325.00 5,628.23 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-01 2022-02-11 2022-02-01 2022-02-13 2022-02-04 2022-12-31 ant Selection of the Issyk-Kul oblast unities IDA-VIP3-AF-IC-2022-19 / C Capacity Building of Local S Individual Consult DSO for the Talas rayon of t IDA / D0410 elf-Governments and Comm Post Open 8,325.00 6,470.59 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-01 2022-02-11 2022-02-01 2022-02-13 2022-02-04 2022-12-31 ant Selection he Talas oblast unities IDA-VIP3-AF-IC-2022-20 / C Capacity Building of Local S Individual Consult Under Implement DSO for the Bakai-Ata rayon IDA / D0410 elf-Governments and Comm Post Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 ant Selection ation of the Talas oblast unities IDA-VIP3-AF-IC-2022-21 / C Capacity Building of Local S Individual Consult DSO for the Manas rayon of IDA / D0410 elf-Governments and Comm Post Open 8,325.00 5,628.23 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-01 2022-02-11 2022-02-01 2022-02-13 2022-02-04 2022-12-31 ant Selection the Talas oblast unities IDA-VIP3-AF-IC-2022-22 / C Capacity Building of Local S Individual Consult Under Implement DSO for the Kara-Buura rayo IDA / D0410 elf-Governments and Comm Post Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 ant Selection ation n of the Talas oblast unities IDA-VIP3-IC-2022-22 / Talas Capacity Building of Local S Regional Specialist for Social Individual Consult IDA / D0410 elf-Governments and Comm Post Open 4,376.00 4,000.00 Signed 2022-01-19 2022-01-14 2022-02-19 2022-02-02 2022-02-22 2022-02-02 2022-02-28 2022-02-04 2022-06-30 Mobilization, Capacity Buildi ant Selection unities ng and Gender Developmen t IDA-VIP3-AF-IC-2022-57 / Cli Capacity Building of Local S Individual Consult IDA / 56010 Post Open 2,950.00 0.00 Canceled 2022-02-18 2022-02-18 2022-03-04 2022-03-07 2022-03-13 2022-06-30 mate Change Specialist elf-Governments and Comm ant Selection unities IDA-VIP3-AF-IC-2022-57/RT / Capacity Building of Local S Individual Consult IDA / D0410 Post Open 2,950.00 0.00 Signed 2022-06-12 2022-06-10 2022-07-20 2022-08-04 2022-07-22 2022-09-01 2022-07-26 2022-12-31 Climate Change Specialist elf-Governments and Comm ant Selection unities IDA-VIP3-AF-IC-2022-58 / Ec Capacity Building of Local S Individual Consult IDA / D0410 Post Open 2,950.00 0.00 Signed 2022-06-12 2022-06-10 2022-07-20 2022-08-04 2022-07-22 2022-09-05 2022-07-26 2022-12-31 onomist (Expert of buisiness elf-Governments and Comm ant Selection skills) unities IDA-AFVIP3-CDSE-IC-2022-2 Capacity Building of Local S Individual Consult 3 / CDSO of the Ak-Suu distri IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-01 2022-11-24 2022-10-12 2022-12-31 ant Selection ct of the Issyk-Kul oblast unities IDA-AFVIP3-CDSE-IC-2022-2 Capacity Building of Local S Individual Consult 4 / CDSO of the Zheti-Oguz IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-01 2022-11-24 2022-10-12 2022-12-14 ant Selection district of the Issyk-Kul oblas unities t IDA-AFVIP3-CDSE-IC-2022-2 Capacity Building of Local S Individual Consult 5 / CDSO of the Issyk-Kul dis IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2023-01-24 2022-10-01 2023-01-24 2022-10-12 2022-12-27 ant Selection trict of the Issyk-kul oblast unities IDA-AFVIP3-CDSE-IC-2022-2 Capacity Building of Local S Individual Consult 6 / CDSO of the Ton district IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-19 2022-09-30 2022-11-11 2022-10-01 2022-11-24 2022-10-12 2022-12-31 ant Selection of the Issyk-Kul oblast unities IDA-AFVIP3-CDSE-IC-2022-2 Capacity Building of Local S Individual Consult 7 / CDSO of the Tup district IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-01 2022-11-24 2022-10-12 2022-12-31 ant Selection of the Issyk-kul oblast unities IDA-AFVIP3-CDSE-IC-2022-2 Capacity Building of Local S Individual Consult 8 / CDSO of the Ak-Tala distr IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-19 2022-09-30 2022-12-23 2022-10-01 2023-01-11 2022-11-01 2023-01-20 ant Selection ict of the Naryn oblast unities IDA-AFVIP3-CDSE-IC-2022-2 Capacity Building of Local S Individual Consult 9 / CDSO of the At-Bashy dis IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-12-23 2022-10-05 2023-01-11 2022-11-01 2023-01-20 ant Selection trict of the Naryn oblast unities IDA-AFVIP3-CDSE-IC-2022-3 Capacity Building of Local S Individual Consult 0 / CDSO of the Jumgal distri IDA / 56010 elf-Governments and Comm Post Open - National 100.00 0.00 Completed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-01 2022-11-24 2022-10-12 2022-12-31 2023-03-11 ant Selection ct of the Naryn oblast unities IDA-AFVIP3-CDSE-IC-2022-3 Capacity Building of Local S Individual Consult 1 / CDSO of the Kochkor dist IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-01 2022-11-24 2022-10-12 2022-12-31 ant Selection rict of the Naryn oblast unities IDA-AFVIP3-CDSE-IC-2022-3 Capacity Building of Local S Individual Consult 2 / CDSO of the Naryn distric IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-12-23 2022-10-01 2023-01-11 2022-10-12 2022-12-31 ant Selection t of the Naryn oblast unities IDA-AFVIP3-CDSE-IC-2022-3 Capacity Building of Local S Individual Consult 3 / CDSO of the Bakai-Ata di IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-05 2022-11-24 2022-11-01 2023-01-20 ant Selection strict of the Talas oblast unities IDA-AFVIP3-CDSE-IC-2022-3 Capacity Building of Local S Individual Consult 4 / CDSO of the Kara-Bura di IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-01 2022-11-28 2022-10-12 2022-12-31 ant Selection strict of the Talas oblast unities IDA-AFVIP3-CDSE-IC-2022-3 Capacity Building of Local S Individual Consult 5 / CDSO of the Manas distri IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-05 2022-11-24 2022-11-01 2023-01-20 ant Selection ct of the Talas oblast unities IDA-AFVIP3-CDSE-IC-2022-3 Capacity Building of Local S Individual Consult 6 / CDSO of the Talas district IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-01 2022-11-28 2022-11-01 2023-01-20 ant Selection of the Talas oblast unities IDA-AFVIP3-CDSE-IC-2022-3 Capacity Building of Local S Individual Consult 7 / CDSO of the Alamudun di IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-05 2022-11-24 2022-11-01 2023-01-20 ant Selection strict of the Chui oblast unities IDA-AFVIP3-CDSE-IC-2022-3 Capacity Building of Local S Individual Consult 8 / CDSO of the Jaiyl district IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-01 2022-11-24 2022-11-01 2023-01-20 ant Selection of the Chui oblast unities IDA-AFVIP3-CDSE-IC-2022-3 Capacity Building of Local S Individual Consult 9 / CDSO of the Kemin distri IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-05 2022-11-24 2022-11-01 2023-01-20 ant Selection ct of the Chui oblast unities IDA-AFVIP3-CDSE-IC-2022-4 Capacity Building of Local S Individual Consult 0 / CDSO of the Moscow dist IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-05 2022-11-24 2022-10-16 2023-01-04 ant Selection rict of the Chui oblast unities IDA-AFVIP3-CDSE-IC-2022-4 Capacity Building of Local S Individual Consult 1 / CDSO of the Panfilov dist IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-05 2022-11-24 2022-11-01 2023-01-20 ant Selection rict of the Chui oblast unities Page 13 IDA-AFVIP3-CDSE-IC-2022-4 Capacity Building of Local S Individual Consult 2 / CDSO of the Sokuluk dist IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-05 2022-11-24 2022-10-27 2023-01-15 ant Selection rict of the Chui oblast unities IDA-AFVIP3-CDSE-IC-2022-4 Capacity Building of Local S Individual Consult 3 / CDSO of the Chui district IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2023-01-18 2022-10-05 2023-02-01 2022-11-01 2023-01-20 ant Selection of the Chui oblast unities IDA-AFVIP3-CDSE-IC-2022-4 Capacity Building of Local S Individual Consult 4 / CDSO of the Yssyk-Ata di IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2023-01-18 2022-10-05 2023-02-01 2022-11-01 2023-01-20 ant Selection strict of the Chui oblast unities IDA-AFVIP3-CHV-IC-2022-45 Capacity Building of Local S Individual Consult / Issyk-Kul regional chain val IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-10-03 2022-10-05 2022-10-19 2022-11-01 2023-01-20 ant Selection ue Specialist unities IDA-AFVIP3-CHV-IC-2022-46 Capacity Building of Local S Individual Consult IDA / 56010 Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-10-03 2022-10-05 2022-10-03 2022-11-01 2023-01-20 / Naryn regional chain value elf-Governments and Comm ant Selection Specialist unities IDA-AFVIP3-CHV-IC-2022-47 Capacity Building of Local S Individual Consult IDA / 56010 Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-10-03 2022-10-05 2022-10-19 2022-11-01 2023-01-20 / Talas regional chain value elf-Governments and Comm ant Selection Specialist unities IDA-AFVIP3-CHV-IC-2022-48 Capacity Building of Local S Individual Consult IDA / 56010 Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-10-03 2022-10-21 2022-10-19 2022-11-05 2023-01-24 / Chui regional chain value S elf-Governments and Comm ant Selection pecialist unities IDA-AFVIP3-TR-IC-2022-48 / Capacity Building of Local S Individual Consult IDA / 56010 Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-10-03 2022-10-01 2022-10-19 2022-10-12 2022-12-31 Chain Value Coach for the C elf-Governments and Comm ant Selection hui oblast (1) unities IDA-AFVIP3-TR-IC-2022-49 / Capacity Building of Local S Individual Consult IDA / 56010 Post Open - National 10,000.00 0.00 Completed 2022-09-01 2022-09-05 2022-09-30 2022-10-03 2022-10-01 2022-10-19 2022-10-12 2022-12-31 2023-03-10 Chain Value Coach for the C elf-Governments and Comm ant Selection hui oblast (2) unities IDA-AFVIP3-TR-IC-2022-50 / Capacity Building of Local S Individual Consult IDA / 56010 Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-10-16 2022-10-03 2022-10-17 2022-10-19 2022-10-28 2023-01-16 Chain Value Coach for the C elf-Governments and Comm ant Selection hui oblast (3) unities IDA-AFVIP3-TR-IC-2022-51 / Capacity Building of Local S Individual Consult IDA / 56010 Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-10-03 2022-10-05 2022-11-01 2022-10-29 2023-01-17 Chain Value Coach for the C elf-Governments and Comm ant Selection hui oblast (4) unities IDA-AFVIP3-TR-IC-2022-52 / Capacity Building of Local S Individual Consult Chain Value Coach for the T IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-10-03 2022-10-05 2022-10-19 2022-11-05 2023-01-24 ant Selection alas oblast (1) unities IDA-AFVIP3-TR-IC-2022-53 / Capacity Building of Local S Individual Consult Chain Value Coach for the T IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-18 2022-10-01 2022-12-01 2022-10-12 2022-12-31 ant Selection alas oblast (2) unities IDA-AFVIP3-TR-IC-2022-54 / Capacity Building of Local S Individual Consult Chain Value Coach for the Is IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-10-03 2022-10-05 2022-10-19 2022-10-29 2023-01-17 ant Selection syk-Kul oblast (1) unities IDA-AFVIP3-TR-IC-2022-55 / Capacity Building of Local S Individual Consult Chain Value Coach for the Is IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-10-03 2022-10-01 2022-10-19 2022-11-01 2023-01-20 ant Selection syk-Kul oblast (2) unities IDA-AFVIP3-TR-IC-2022-56 / Capacity Building of Local S Individual Consult Chain Value Coach for the Is IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-10-03 2022-10-01 2022-10-03 2022-10-12 2022-12-31 ant Selection syk-Kul oblast (3) unities IDA-AFVIP3-TR-IC-2022-57 / Capacity Building of Local S Individual Consult Chain Value Coach for the N IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-10-20 2022-10-05 2022-11-01 2022-10-16 2023-01-04 ant Selection aryn oblast (1) unities IDA-AFVIP3-TR-IC-2022-58 / Capacity Building of Local S Individual Consult Chain Value Coach for the N IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-10-20 2022-10-01 2022-11-01 2022-11-01 2023-01-20 ant Selection aryn oblast (2) unities IDA-AFVIP3-TR-IC-2022-59 / Capacity Building of Local S Individual Consult Chain Value Coach for the N IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-10-20 2022-10-05 2022-11-01 2022-11-01 2023-01-20 ant Selection aryn oblast (3) unities IDA-AFVIP3-CHV-IC-2022-49 Capacity Building of Local S Individual Consult IDA / 56010 Post Open - National 10,000.00 0.00 Signed 2023-01-19 2023-01-23 2023-02-02 2023-02-14 2023-02-07 2023-03-01 2023-02-09 2023-12-31 / Chui regional chain value S elf-Governments and Comm ant Selection pecialist unities IDA-AFVIP3-CDSE-IC-2022-4 Capacity Building of Local S Individual Consult Under Implement 5 / CDSO of the Alamudun di IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 2023-02-10 2023-02-13 2023-03-20 2023-03-20 2023-03-25 2023-12-31 ant Selection ation strict of the Chui oblast unities IDA-AFVIP3-CDSE-IC-2022-4 Capacity Building of Local S Individual Consult Under Implement 6 / CDSO for the Ak-Tala ray IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 2023-02-10 2023-03-20 2023-03-20 2023-03-25 2023-12-31 ant Selection ation on of the Naryn oblast unities IDA-AFVIP3-CDSE-IC-2022-4 Capacity Building of Local S Individual Consult Pending Impleme 7 / CDSO for the Jugal distric IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 2023-03-01 2023-04-08 2023-04-09 2023-04-30 2023-12-31 ant Selection ntation t rayon of the Naryn oblast unities IDA-AFVIP3-TR-IC-2022-60 / Capacity Building of Local S Individual Consult Pending Impleme Chain Value Coach for the P IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 2023-03-01 2023-04-08 2023-04-09 2023-04-11 2023-12-31 ant Selection ntation anfilov and Jaiyl districtsChui unities oblast IDA-AFVIP3-TR-IC-2022-61 / Capacity Building of Local S Individual Consult Under Implement Chain Value Coach for the Y IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 2023-03-13 2023-03-13 2023-04-20 2023-04-21 2023-05-06 2023-12-31 ant Selection ation ssyk-Ata and Alamedein dist unities ricts Chui oblast IDA-AFVIP3-TR-IC-2022-62 / Capacity Building of Local S Individual Consult Under Implement Chain Value Coach for the Ju IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 2023-03-13 2023-03-13 2023-04-11 2023-04-12 2023-04-14 2023-12-27 ant Selection ation mgal districts Naryn oblast unities IDA-AFVIP3-CDSE-IC-2022-4 Capacity Building of Local S Individual Consult Pending Impleme 8 / CDSO for the Kochkor dis IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 2023-05-04 2023-06-11 2023-06-12 2023-06-14 2023-12-31 ant Selection ntation trict rayon of the Naryn obla unities st IDA-VIP3-AF-IC-2023-2 / Issy Individual Consult Under Implement IDA / 67820 Project Management Post Open - National 10,000.00 0.00 2023-06-20 2023-06-22 2023-08-08 2023-08-29 2023-10-03 2024-03-31 k-Kul regional engineer ant Selection ation IDA-VIP3-AF-IC-2023-1 / Chu Individual Consult Under Implement IDA / 67820 Project Management Post Open - National 10,000.00 0.00 2023-06-20 2023-06-22 2023-08-08 2023-08-29 2023-10-03 2024-03-31 i Regional Social Mobilizatio ant Selection ation n Specialist Page 14 PROCUREMENT PLAN (Textual Part) Project information: Sierra Leone - Quality Essential Health Services and Systems Support Project (P172102). Project Implementation agency: Ministry of Health and Sanitation (MoHS). Date of the Procurement Plan: May, 2022. Period covered by this Procurement Plan: 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in The Public Procurement Act 2016, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable Other Relevant Procurement Information. None PROCUREMENT Sierra Leone : Sierra Leone - Quality Essential Health Services and Systems Support Project PLAN General Information Country: Sierra Leone 2022-06-03 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172102 GPN Date: 2022-04-23 Project Name: Sierra Leone - Quality Essential Health Services and Systems Support Project Loan / Credit No: TF / B7266, IDA / D9380, TF / B7267 Partners In Health-Sierra Leone Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SL-PIH-SL-306881-CW-RFQ / Component 1: Improving Qu Request for Quota Engagement of Contractor fo ality, Efficiency, and Effectiv Request for Quota Single Stage - One E Pending Imp 2023-12-0 IDA / D9380 Post Limited tions (Non Bank-S 20,000.00 0.00 2023-04-03 2023-06-12 r Facility Renovations at Jojoi eness of Reproductive, Mate tions nvelope lementation 9 PD) ma rnal, Newborn, Child Health and Nutriti on Services SL-PIH-SL-306884-CW-RFQ / Component 1: Improving Qu Engagement of Contractor fo ality, Efficiency, and Effectiv Request for Quota r Facility Renovations of Kaila Request for Quota Single Stage - One E Pending Imp 2024-03-0 IDA / D9380 eness of Reproductive, Mate Post Limited tions (Non Bank-S 30,000.00 0.00 2023-07-03 2023-09-11 hun Government Hospital tions nvelope lementation 9 rnal, Newborn, Child Health PD) Kailahun Town, Eastern Provi and Nutriti on Services nce, Sierra Leone SL-PIH-SL-306883-CW-RFQ / Component 1: Improving Qu Request for Quota Engagement of Contractor fo ality, Efficiency, and Effectiv Request for Quota Single Stage - One E Pending Imp 2023-12-0 IDA / D9380 Post Limited tions (Non Bank-S 95,000.00 0.00 2023-04-03 2023-06-12 r Facility Renovations at Ban eness of Reproductive, Mate tions nvelope lementation 9 PD) dajuma rnal, Newborn, Child Health and Nutriti on Services SL-PIH-SL-306882-CW-RFQ / Component 1: Improving Qu Request for Quota Engagement of Contractor fo ality, Efficiency, and Effectiv Request for Quota Single Stage - One E Pending Imp 2023-11-1 IDA / D9380 Post Limited tions (Non Bank-S 45,000.00 0.00 2023-03-06 2023-05-15 r Facility Renovations at Beu eness of Reproductive, Mate tions nvelope lementation 1 PD) du rnal, Newborn, Child Health and Nutriti on Services SL-PIH-SL-330099-CW-RFQ / Component 1: Improving Qu Request for Quota Procurement of Contractor fo ality, Efficiency, and Effectiv Request for Quota Single Stage - One E Pending Imp 2023-09-2 IDA / D9380 Post Limited tions (Non Bank-S 20,000.00 0.00 2023-01-16 2023-03-27 r Topographical Survey at Joj eness of Reproductive, Mate tions nvelope lementation 3 PD) oima rnal, Newborn, Child Health and Nutriti on Services Component 1: Improving Qu SL-PIH-SL-330102-CW-RFQ / Request for Quota ality, Efficiency, and Effectiv Request for Quota Single Stage - One E Pending Imp 2023-11-1 Procurement of a Contractor IDA / D9380 Post Limited tions (Non Bank-S 10,000.00 0.00 2023-03-06 2023-05-15 eness of Reproductive, Mate tions nvelope lementation 1 for Landscaping at Jojoima PD) rnal, Newborn, Child Health and Nutriti on Services Component 1: Improving Qu SL-PIH-SL-330103-CW-RFQ / Request for Quota ality, Efficiency, and Effectiv Request for Quota Single Stage - One E Pending Imp 2023-11-1 Procurement of Contractor fo IDA / D9380 Post Limited tions (Non Bank-S 15,000.00 0.00 2023-03-06 2023-05-15 eness of Reproductive, Mate tions nvelope lementation 1 r Generator House at Jojoima PD) rnal, Newborn, Child Health and Nutriti on Services SL-PIH-SL-330286-CW-RFQ / Component 1: Improving Qu Request for Quota Procurement of a Contractor ality, Efficiency, and Effectiv Request for Quota Single Stage - One E Pending Imp 2023-11-1 IDA / D9380 Post Limited tions (Non Bank-S 75,000.00 0.00 2023-03-06 2023-05-15 for External Works for Jojoim eness of Reproductive, Mate tions nvelope lementation 1 PD) a rnal, Newborn, Child Health and Nutriti on Services GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SL-PIH-SL-297136-GO-RFQ / Component 1: Improving Qu Procurement of Backup Gene ality, Efficiency, and Effectiv Request for Quota Single Stage - One E TF / B7266 Post Limited 36,000.00 0.00 Canceled 2022-09-09 2022-10-03 2023-01-31 rators - National Procuremen eness of Reproductive, Mate tions nvelope t rnal, Newborn, Child Health and Nutriti on Services SL-PIH-SL-300196-GO-RFQ / Component 1: Improving Qu Procurement of equipment fo ality, Efficiency, and Effectiv Request for Quota Single Stage - One E r health facilities (Lab. equip IDA / D9380 eness of Reproductive, Mate Post Limited 97,348.56 0.00 Canceled 2022-08-22 2022-10-03 2023-04-01 tions nvelope ment - analyzers, microscope rnal, Newborn, Child Health s, centrifuges, lab hardware, and Nutriti on Services etc.) SL-PIH-SL-300198-GO-RFQ / Component 1: Improving Qu Procurement of equipment fo ality, Efficiency, and Effectiv Request for Quota Single Stage - One E TF / B7266 Post Limited 71,472.04 0.00 Canceled 2022-08-22 2022-10-03 2023-04-01 r health facilities (Medical fur eness of Reproductive, Mate tions nvelope niture - beds, tables, shelves, rnal, Newborn, Child Health cabinets, etc.) and Nutriti on Services SL-PIH-SL-297140-GO-RFQ / Component 1: Improving Qu Procurement of Furniture ality, Efficiency, and Effectiv Request for Quota Single Stage - One E (office furniture, chairs, desk IDA / D9380 eness of Reproductive, Mate Post Limited 100,000.00 0.00 Signed 2023-01-09 2023-03-17 2023-03-13 2023-09-09 tions nvelope s, benches, door lockers, shel rnal, Newborn, Child Health ves, waste bins, etc.) and Nutriti on Services Component 1: Improving Qu SL-PIH-SL-297154-GO-RFQ / ality, Efficiency, and Effectiv Request for Quota Single Stage - One E Pending Impl Procurement of 9 Motor Bike IDA / D9380 Post Limited 18,000.00 0.00 2023-01-09 2023-01-29 2023-07-28 eness of Reproductive, Mate tions nvelope ementation s rnal, Newborn, Child Health and Nutriti on Services Component 1: Improving Qu SL-PIH-SL-327556-GO-UN / P ality, Efficiency, and Effectiv Direct - Internation Under Imple rocurement of 5 Vehicles and IDA / D9380 Post Direct Selection 370,800.00 0.00 2022-12-12 2023-03-16 2022-12-12 2023-03-16 2023-02-28 2023-08-27 eness of Reproductive, Mate al mentation 59 Laptop Computers rnal, Newborn, Child Health and Nutriti on Services Component 1: Improving Qu SL-PIH-SL-311895-GO-RFQ / ality, Efficiency, and Effectiv Request for Quota Single Stage - One E Pending Impl Procurement of Computers ( IDA / D9380 Post Limited 70,800.00 0.00 2022-08-22 2022-10-10 2023-04-08 eness of Reproductive, Mate tions nvelope ementation 59 Laptops) rnal, Newborn, Child Health and Nutriti on Services SL-PIH-SL-327061-GO-DIR / P Component 1: Improving Qu rocurement of drugs, medical ality, Efficiency, and Effectiv Direct - Internation Pending Impl TF / B7266 Post Direct Selection 759,728.00 0.00 2022-12-12 2022-12-12 2023-01-29 2023-07-28 equipment and supplies, and eness of Reproductive, Mate al ementation laboratory equipment and su rnal, Newborn, Child Health pplies and Nutriti on Services Component 1: Improving Qu SL-PIH-SL-341101-GO-RFQ / ality, Efficiency, and Effectiv Request for Quota Single Stage - One E Procurement of backup gene TF / B7266 Post Limited 56,000.00 0.00 Signed 2023-02-09 2023-03-16 2023-03-11 2023-09-07 eness of Reproductive, Mate tions nvelope rators rnal, Newborn, Child Health and Nutriti on Services Page 1 SL-PIH-SL-346997-GO-RFQ / Component 1: Improving Qu Procure two generators for Jo ality, Efficiency, and Effectiv Request for Quota Single Stage - One E Pending Impl TF / B7267 Post Limited 100,000.00 0.00 2023-06-12 2023-07-21 2024-01-17 joima CHC, 250KVA and 150K eness of Reproductive, Mate tions nvelope ementation VA generators (new for 2023 rnal, Newborn, Child Health PP) and Nutriti on Services SL-PIH-SL-346999-GO-RFQ / Component 1: Improving Qu Procure two additional 20KVA ality, Efficiency, and Effectiv Request for Quota Single Stage - One E Pending Impl TF / B7267 Post Limited 20,000.00 0.00 2023-06-12 2023-07-21 2024-01-17 back-up generators for Bued eness of Reproductive, Mate tions nvelope ementation u and Bandajuma (new for 2 rnal, Newborn, Child Health 023 PP) and Nutriti on Services SL-PIH-SL-347004-GO-DIR / P Component 1: Improving Qu rocure  two 4x4 Station wago ality, Efficiency, and Effectiv Direct - Internation Pending Impl TF / B7267 Post Direct Selection 120,000.00 0.00 2023-06-15 2023-06-15 2023-06-29 2023-12-26 n vehicle for Kailahun DHMT eness of Reproductive, Mate al ementation and Freetown intra district tr rnal, Newborn, Child Health avel (new for 2023 PP) and Nutriti on Services NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 Procurement Plan I. General 1. Project Information Country : Kenya Recipient : Republic of Kenya Project Name : National Agriculture and Rural Inclusive Growth Loan Credit No. : IDA 59000 2. Date of General Procurement Notice : 9th February 2018 3. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services 1. Thresholds for the Method of Procurement: Method of Procurement Thresholds for Method (US$ equivalent) Open International (Goods) Equal to or more than 3 million Open National ( Goods) – Open < $3 million Tender as per PPDA 2015 RFQ (Goods) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Open International (Works) Equal to or more than 15 million Open National (Works) - Open Less than 15 million Tender as per PPDA 2015 RFQ (works) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Method of Procurement Thresholds for Method (US$ equivalent) Open International (Non-consulting Equal to or More than 3 million Services) Open National (Non-consulting Less than 3 million Services) - Open Tender as per PPDA 2015 Direct Contracting No threshold; meet requirements of Bank’s Procurement Regulations Prior Review: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection (Project Procurement Risk Rating is “High”): (a) Goods, information technology and Non-consulting Services: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1.5 million (b) Works (including turnkey, supply & installation of plant and equipment and PPP); First procurement under the project irrespective of value and all procurements estimated to cost more than USD 5 million and The prior review thresholds will be reviewed during the implementation of the project and modified, based on the risk assessment. 2. For contracts subject to prior review, the Borrower shall seek the Bank’s no objection before agreeing to: a. an extension of the stipulated time for execution of a contract that has an impact on the planned completion of the project; b. any material modification of the scope of the Works, Goods, Non- consulting services or Consulting Services, or other significant changes to the terms and conditions of the contract; c. any variation order or contract amendment (except in cases of extreme urgency), including due to extension of time, that singly or combined with all previous variation orders or amendments, increases the original contract amount by more than 15% (fifteen percent); or d. the proposed termination of the contract. The Borrower / IA shall provide a copy of all amendments to the contract to the Bank for its records. 3. Prequalification Not Applicable Domestic Preference. The provision of domestic preference shall be applied in the procurement of goods following international market approach in accordance with Annex VI of the Regulations. Domestic preference shall not apply in the procurement of works. 4. Reference to Standard Procurement Documents Bank’s Standard RFB Goods and RFP Consulting Services dated July 2016 will be used as a base and incorporating suitable modifications and the same would be agreed with the Bank subject international competition. 5. Any Other Special Procurement Arrangements A. Procurement approach under CDD Approach by Communities: Applicable if stipulated in the PAD. B. When approaching the national market, as agreed in the Procurement Plan, the Open Tender procedure of Public Procurement and Asset Disposal Act 2015 and Regulations 2017 may be used. The specific Requirements for national open competitive procurement include the following: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. Other national procurement arrangements (other than national open competitive procurement), that may be applied by the Borrower (such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti-Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. In all cases, the national procurement procedures to be used shall give due attention to quality aspects. 6. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Selection methods of procurement of Consultants' Services (Firms): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Quality and Cost Based As per requirements of para 7.3 of the Selection (QCBS) Regulations Quality Based Selection As per requirements of para 7.8 to 7.10 (QBS) of the Regulations Selection based on a Fixed As per requirements of para 7.4 and 7.5 of the Budget (FBS) Regulations Selection Based on Least As per requirements of para 7.6 and 7.7 of the Cost Basis (LCS) Regulations Selection based on As per requirements of para 7.11 and 7.12 of Consultant’s Qualification the Regulations (CQ) Direct Must meet the requirements of Para 7.13 to 7.15 of the Regulations, and with prior agreement in PP with the Bank. The short list may consist of all National consultants in case the estimated cost is less than USD 300,000 Procurement methods for Selection of Individual Consultants (IC): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Open Competitive As per requirements of para 7.36 and 7.37 of Selection the Regulations Limited Competitive As per requirements of para 7.38 of the Selection Regulations Direct Must meet the requirements of Para 7.39 of the Regulations, and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Regulations Prior Review Thresholds: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 0.5 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.2 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. PROCUREMENT Kenya : National Agricultural and Rural Inclusive Growth Project PLAN General Information Country: Kenya 2019-10-29 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153349 GPN Date: 2018-02-09 Project Name: National Agricultural and Rural Inclusive Growth Project Loan / Credit No: IDA / 59000 Muranga County Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-MURANGA COUNTY-1395 Project Coordination and Ma Request for Quota Single Stage - One E 2019-12-3 IDA / 59000 Post Limited 20,000.00 17,203.15 Signed 2019-10-17 2019-12-13 2019-10-31 2020-05-21 74-CW-RFQ / Office Renovati nagement tions nvelope 0 on KE-MURANGA COUNTY-1489 Supporting County Communi Single Stage - One E 2020-09-2 18-CW-RFB / Ititu-Ikundu Irrig IDA / 59000 Post Request for Bids Open - National 200,000.00 0.00 Canceled 2019-12-06 2019-12-11 2020-01-22 2020-02-21 2020-03-27 ty-Led Development nvelope 3 ation Project KE-MURANGA COUNTY-1489 24-CW-RFB / Implementation Supporting County Communi Single Stage - Two E Under Imple 2020-11-0 IDA / 59000 Post Request for Bids Open - National 600,000.00 0.00 2019-12-06 2019-12-11 2020-01-22 2020-04-05 2020-05-10 of multi community investme ty-Led Development nvelope mentation 6 nt- ITITU IKUNDU Irrigation Pr oject KE-MURANGA COUNTY-1894 Supporting County Communi Single Stage - One E Under Imple 2021-06-2 67-CW-RFB / Construction of I IDA / 59000 Post Request for Bids Open - National 922,636.45 0.00 2020-09-04 2020-09-08 2020-09-09 2020-10-21 2020-09-22 2020-11-20 2020-12-25 ty-Led Development nvelope mentation 3 TITU IKUNDU irrigation sche me National Procure KE-MURANGA COUNTY-2788 Strengthening Producer Org ment Document - 22-CW-RFB / Construction of Single Stage - One E Under Imple 2022-11-0 IDA / 59000 anizations and Value Chain Post Request for Bids Open - National 1 Envelope proce 96,788.00 0.00 2022-02-21 2022-03-22 2022-02-22 2022-03-24 2022-04-12 2022-03-29 2022-05-10 Hatchery plant for the Chicke nvelope mentation 6 Development ss (Non Bank-SPD n Producer organisation. ) National Procure KE-MURANGA COUNTY-2788 Strengthening Producer Org ment Document - 27-CW-RFB / Construction of Single Stage - One E Under Imple 2022-11-1 IDA / 59000 anizations and Value Chain Post Request for Bids Open - National 1 Envelope proce 149,582.00 0.00 2022-02-28 2022-03-08 2022-03-01 2022-03-31 2022-04-12 2022-04-05 2022-05-17 Banana Plant for Banana Pro nvelope mentation 3 Development ss (Non Bank-SPD ducer Organisation ) KE-MURANGA COUNTY-3198 Request for Bids - Strengthening Producer Org 43-CW-RFB / Supply, delivery Single Stage - One E Small Works SPD Under Imple 2023-06-1 IDA / 59000 anizations and Value Chain Post Request for Bids Open - National 280,000.00 0.00 2022-10-06 2022-11-21 2022-10-07 2022-11-18 2022-11-23 2022-12-21 and installation of aggregatio nvelope (1 envelope proce mentation 9 Development n center for Murang,a Avoca ss) do Cooperative Union GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MURANGA COUNTY-1445 Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 36,100.00 31,600.70 Signed 2019-11-12 2019-12-16 2019-11-25 2020-05-21 2019-12-25 08-GO-RFQ / purchase of offi nagement tions nvelope ce furniture KE-MURANGA COUNTY-1489 28-GO-RFQ / 1 Total station,t his is an equipment to carry Supporting County Communi Request for Quota Single Stage - One E Under Imple IDA / 59000 Post Limited 40,000.00 0.00 2019-12-11 2020-08-27 2020-02-05 2020-08-03 out survey for irrigation proje ty-Led Development tions nvelope mentation cts.It will be used for the Ititu Ikundu Irrigation Project and other upcoming irrigation pro jects. KE-MURANGA COUNTY-1701 19-GO-RFQ / 20 motorcycles Project Coordination and Ma Request for Quota Single Stage - One E Under Imple IDA / 59000 Post Limited 80,000.00 0.00 2020-05-05 2020-11-30 2020-05-15 2020-05-22 with piston displacement in t nagement tions nvelope mentation he range of 100 cc-130 cc KE-MURANGA COUNTY-1708 Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 8,000.00 7,740.22 Signed 2020-04-28 2020-08-27 2020-05-08 2020-10-02 2020-05-15 99-GO-RFQ / 5 laptops nagement tions nvelope KE-MURANGA COUNTY-1709 00-GO-RFQ / IP based audio v Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 73,000.00 63,494.22 Signed 2020-04-28 2020-06-08 2020-05-08 2020-09-03 2020-05-22 isual teleconferencing syste nagement tions nvelope m, Network router and Netw ork firewall KE-MURANGA COUNTY-1788 Supporting County Communi Request for Quota Single Stage - One E Pending Impl 93-GO-RFQ / supply of T-shirt IDA / 59000 Post Limited 1,200.00 0.00 2020-06-12 2020-06-22 2020-06-29 ty-Led Development tions nvelope ementation s,Caps and banners KE-MURANGA COUNTY-2069 Supporting Community-Driv Request for Quota Single Stage - One E 47-GO-RFQ / Purchase of offi IDA / 59000 Post Limited 1,836.55 1,771.86 Signed 2020-11-27 2021-01-04 2020-12-08 2021-02-05 2020-12-15 en Development tions nvelope ce table for the 20 CDDCs in NARIGP project KE-MURANGA COUNTY-2069 64-GO-RFQ / purchase of 20 Supporting Community-Driv Request for Quota Single Stage - One E IDA / 59000 Post Limited 3,673.09 4,471.37 Signed 2020-11-27 2020-12-14 2020-12-08 2020-12-31 2020-12-15 chairs for each CDDC in the 2 en Development tions nvelope 0 wards of NARIGP project KE-MURANGA COUNTY-2069 Supporting Community-Driv Request for Quota Single Stage - One E Under Imple 65-GO-RFQ / Purchase of 1 d IDA / 59000 Post Limited 7,346.19 0.00 2020-11-27 2020-12-08 2020-12-15 en Development tions nvelope mentation esktop for each CDDC in the 20 wards KE-MURANGA COUNTY-2069 66-GO-RFQ / Purchase of 1 s Supporting Community-Driv Request for Quota Single Stage - One E IDA / 59000 Post Limited 3,673.09 5,315.58 Signed 2020-11-27 2021-01-04 2020-12-08 2021-03-24 2020-12-15 mall printer for each of the 2 en Development tions nvelope 0 CDDCs in the 20 wards. KE-MURANGA COUNTY-2283 77-GO-RFQ / Avocado Seedli ngs (hass variety)- 9000 piec Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 15,800.00 46,436.86 Signed 2021-04-14 2021-04-20 2021-04-24 2021-05-05 2021-05-08 es, fodder trees 4500 pieces, ty-Led Development tions nvelope vetiver grass 100 bags, Indig enous trees 500 pieces for re parian protection. Page 1 KE-MURANGA COUNTY-2283 81-GO-RFQ / Avocado seedlin Supporting County Communi Request for Quota Single Stage - One E gs(hass variety) 6500 pieces, IDA / 59000 Post Limited 12,150.00 57,935.96 Signed 2021-04-14 2021-04-20 2021-04-24 2021-05-05 2021-05-08 ty-Led Development tions nvelope fodder trees 3500 pieces, vet iver grass 100 bags, indegino us trees 500 pieces KE-MURANGA COUNTY-2465 81-GO-RFQ / Supply and deli Supporting County Communi Request for Quota Single Stage - One E Under Imple IDA / 59000 Post Limited 30,545.00 0.00 2021-08-11 2021-08-26 2021-08-23 2021-09-13 very of 8400M (Meters squar ty-Led Development tions nvelope mentation ed) pondliners for Makindi Ki rimamwaro watershed. KE-MURANGA COUNTY-2465 87-GO-RFQ / For supply and Supporting County Communi Request for Quota Single Stage - One E Under Imple IDA / 59000 Post Limited 20,364.00 0.00 2021-08-11 2021-08-26 2021-08-23 2021-09-13 delivery of pondliners for Wa ty-Led Development tions nvelope mentation rugara watershed. KE-MURANGA COUNTY-2468 Supporting County Communi Request for Quota Single Stage - One E Under Imple 99-GO-RFQ / Supply and deli IDA / 59000 Post Limited 10,909.00 0.00 2021-08-24 2021-11-05 2021-09-05 2021-10-05 ty-Led Development tions nvelope mentation very of 2 soil scanners. KE-MURANGA COUNTY-2507 Project Coordination and Ma Request for Quota Single Stage - One E Under Imple IDA / 59000 Post Limited 1,818.00 0.00 2021-09-08 2021-11-05 2021-09-20 2021-10-04 39-GO-RFQ / 1 Laptop nagement tions nvelope mentation KE-MURANGA COUNTY-2798 Supporting County Communi Under Imple 88-GO-DIR / 10 specially desi IDA / 59000 Post Direct Selection Direct 2,137.00 0.00 2022-03-07 2021-10-11 2022-03-12 2022-04-17 2022-05-17 ty-Led Development mentation gned android tablets KE-MURANGA COUNTY-2798 Supporting County Communi Under Imple IDA / 59000 Post Direct Selection Direct 3,968.00 0.00 2022-03-09 2021-10-11 2022-03-14 2022-04-19 2022-05-19 89-GO-DIR / 10 smart digital ty-Led Development mentation projectors KE-MURANGA COUNTY-2798 Supporting County Communi Under Imple 90-GO-DIR / 10 Agriprenuers IDA / 59000 Post Direct Selection Direct 5,495.00 0.00 2022-03-11 2021-10-11 2022-03-16 2022-04-20 2022-05-20 ty-Led Development mentation digital licences KE-MURANGA COUNTY-3074 Strengthening Producer Org 28-GO-RFQ / Supply, delivery Request for Quota Single Stage - One E IDA / 59000 anizations and Value Chain Post Limited 55,000.00 0.00 Canceled 2022-08-20 2022-09-17 2022-11-16 and installation of an eco pul tions nvelope Development per at Ruchu coffee factory KE-MURANGA COUNTY-3074 Strengthening Producer Org 42-GO-RFQ / Supply and deli Request for Quota Single Stage - One E IDA / 59000 anizations and Value Chain Post Limited 40,000.00 0.00 Canceled 2022-08-17 2022-08-29 2022-09-28 very of ripening chamber for tions nvelope Development Gikama Agribusiness KE-MURANGA COUNTY-3074 Strengthening Producer Org 45-GO-RFQ / Supply, delivery Request for Quota Single Stage - One E IDA / 59000 anizations and Value Chain Post Limited 55,000.00 0.00 Canceled 2022-08-16 2022-09-29 2023-03-28 and installation of an eco pul tions nvelope Development per at Kanguno coffee factor y KE-MURANGA COUNTY-3149 Strengthening Producer Org 26-GO-RFQ / Supply, delivery Request for Quota Single Stage - One E IDA / 59000 anizations and Value Chain Post Limited 55,000.00 0.00 Canceled 2022-09-27 2022-10-15 2023-04-13 , and installation of an eco p tions nvelope Development ulper at Gatumbi, Kangiri coff ee factory KE-MURANGA COUNTY-3149 Strengthening Producer Org 29-GO-RFQ / Supply, delivery Request for Quota Single Stage - One E IDA / 59000 anizations and Value Chain Post Limited 55,000.00 0.00 Canceled 2022-09-27 2022-10-15 2023-04-13 ,and installation of an eco pul tions nvelope Development per at Kaganda coffee factor y KE-MURANGA COUNTY-3149 Strengthening Producer Org 30-GO-RFQ / Supply,delivery Request for Quota Single Stage - One E IDA / 59000 anizations and Value Chain Post Limited 55,000.00 0.00 Canceled 2022-10-04 2022-10-23 2023-04-21 and installation of an eco pul tions nvelope Development per at Karurumo coffee facto ry KE-MURANGA COUNTY-3187 Strengthening Producer Org 79-GO-RFQ / Supply, delivery Request for Quota Single Stage - One E IDA / 59000 anizations and Value Chain Post Limited 55,000.00 0.00 Canceled 2022-10-08 2022-10-24 2023-04-22 and installation of Eco pulper tions nvelope Development s for Kamacharia Coffee Fact ory KE-MURANGA COUNTY-3187 Strengthening Producer Org 82-GO-RFQ / Supply, delivery Request for Quota Single Stage - One E IDA / 59000 anizations and Value Chain Post Limited 55,000.00 0.00 Canceled 2022-10-04 2022-10-20 2023-04-18 and installation of ecopulpers tions nvelope Development at Thangaini coffee factory KE-MURANGA COUNTY-3239 Strengthening Producer Org 47-GO-RFB / Supply and deliv Single Stage - One E Pending Impl IDA / 59000 anizations and Value Chain Post Request for Bids Open - National 160,000.00 0.00 2022-10-28 2022-11-02 2022-12-14 2022-12-19 2023-01-07 2023-07-06 ery of a grading line for the A nvelope ementation Development vocado producer organizatio n. KE-MURANGA COUNTY-3295 19-GO-RFQ / Supply and deli very of5040m pondliners, 20 Supporting County Communi Request for Quota Single Stage - One E Pending Impl IDA / 59000 Post Limited 47,346.00 0.00 2022-12-23 2023-01-20 2023-02-03 solarpump kits,9500 high val ty-Led Development tions nvelope ementation ue fruit trees, 350 indigenous tree seedlings and 10 line lev els for Gaaci SLM KE-MURANGA COUNTY-3295 29-GO-RFQ / Supply and deli very of 5040m pondliners, 20 Supporting County Communi Request for Quota Single Stage - One E Pending Impl IDA / 59000 Post Limited 43,265.00 0.00 2022-12-23 2023-01-20 2023-02-03 solar pump kits, 7000 high v ty-Led Development tions nvelope ementation alue fruit trees,350 indigeno us trees seedlings and 10 lin e levels for Miu SLM KE-MURANGA COUNTY-3295 31-GO-RFQ / Supply and deli very of 5040m pondliners,20 Supporting County Communi Request for Quota Single Stage - One E Pending Impl IDA / 59000 Post Limited 51,534.00 0.00 2022-12-24 2023-01-21 2023-02-04 solarpump kits with tank, 91 ty-Led Development tions nvelope ementation 00 high value fruit trees,200 0 vetiver grass and 10 line le vels for BOBOTI SLM KE-MURANGA COUNTY-3295 39-GO-RFQ / Supply and deli very of 5040m pondliners, 20 Supporting County Communi Request for Quota Single Stage - One E Pending Impl solar pump kit with tank, 598 IDA / 59000 Post Limited 50,114.00 0.00 2022-12-24 2023-01-21 2023-02-04 ty-Led Development tions nvelope ementation 0 high value fruit trees, 1500 bamboo tree seedlings,2000 vetiver grass and 10 line leve ls for the Gachocho SLM KE-MURANGA COUNTY-3295 42-GO-RFQ / Supply and deli very of 5040m pondliners ,20 Supporting County Communi Request for Quota Single Stage - One E Pending Impl IDA / 59000 Post Limited 51,069.00 0.00 2022-12-24 2023-01-21 2023-02-04 solarpump kits with tank.894 ty-Led Development tions nvelope ementation 0 high value fruit trees and 2 000 vetiver grass for Kagwan ja Mukui SLM Page 2 KE-MURANGA COUNTY-3487 19-GO-RFQ / Supply and deli very of pondliners, solar pum Supporting County Communi Request for Quota Single Stage - One E Pending Impl IDA / 59000 Post Limited 44,050.00 0.00 2023-03-15 2023-04-02 2023-04-16 p kits with tank, fruit tree see ty-Led Development tions nvelope ementation dlings/fodder, vetivar grass a nd line levels for the Kaseve SLM KE-MURANGA COUNTY-3487 23-GO-RFQ / Supply and deli very of pond liners, solar pu Supporting County Communi Request for Quota Single Stage - One E Pending Impl IDA / 59000 Post Limited 47,638.00 0.00 2023-03-15 2023-04-14 2023-04-15 mp kits with tank,Fruit tree s ty-Led Development tions nvelope ementation eedlings/fodder, vetivar gras s and line levels for Thamara slm KE-MURANGA COUNTY-3487 25-GO-RFQ / Supply and deli Supporting County Communi Request for Quota Single Stage - One E Pending Impl very of pondliners, solar pum IDA / 59000 Post Limited 40,769.00 0.00 2023-03-15 2023-04-16 2023-10-13 ty-Led Development tions nvelope ementation p kits,fruit trees/fodder, indig enous tree seedlings and line levels for Mika SLM KE-MURANGA COUNTY-2465 Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 9,091.00 0.00 Canceled 2021-08-26 2021-09-09 2021-10-09 90-GO-RFQ / 20 Pondliners. ty-Led Development tions nvelope KE-MURANGA COUNTY-3637 Strengthening Producer Org 40-GO-RFQ / SUPPLY AND DE Request for Quota Single Stage - One E Pending Impl IDA / 59000 anizations and Value Chain Post Limited 15,913.00 0.00 2023-06-02 2023-06-26 2023-06-27 LIVERY OF 20 DESKTOP COM tions nvelope ementation Development PUTERS FOR THE AUTOMATE D SACCOs KE-MURANGA COUNTY-3637 Strengthening Producer Org 41-GO-RFQ / SUPPLY AND DE Request for Quota Single Stage - One E Pending Impl IDA / 59000 anizations and Value Chain Post Limited 5,786.00 0.00 2023-06-02 2023-06-26 2023-07-10 LIVERY OF 20 PRINTERS FOR tions nvelope ementation Development THE AUTOMATED SACCOs KE-MURANGA COUNTY-3637 42-GO-RFQ / Supply and Deli Project Coordination and Ma Request for Quota Single Stage - One E Pending Impl IDA / 59000 Post Limited 1,446.00 0.00 2023-06-02 2023-06-26 2023-07-10 very of a laptop for the DAT a nagement tions nvelope ementation nd Mshamba Market survey s tudy NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MURANGA COUNTY-1489 20-CS-CQS / Procurement of Supporting Community-Driv Consultant Qualifi IDA / 59000 Post Open - National 200,000.00 0.00 Canceled 2019-12-06 2019-12-27 2020-02-09 2020-03-10 2020-04-14 2020-10-11 service providers for the 4 va en Development cation Selection lue chains-Avocado, Banana, Chicken and Dairy. KE-MURANGA COUNTY-1788 Supporting Community-Driv Consultant Qualifi Under Implement 66-CS-CQS / Call for Expressi IDA / 59000 Post Open - National 50,000.00 0.00 2020-06-17 2020-07-01 2020-07-22 2020-08-05 2020-08-22 2021-11-15 en Development cation Selection ation on of Interest for Banana Val ue Chain KE-MURANGA COUNTY-1788 Supporting Community-Driv Consultant Qualifi Under Implement 83-CS-CQS / Call for expressi IDA / 59000 Post Open - National 50,000.00 0.00 2020-06-17 2020-07-01 2020-07-22 2020-08-05 2020-08-22 2021-11-15 en Development cation Selection ation on of interest for Avocado Va lue Chain KE-MURANGA COUNTY-1788 Supporting Community-Driv Consultant Qualifi Pending Impleme 87-CS-CQS / Call for expressi IDA / 59000 Post Open - National 50,000.00 0.00 2020-06-17 2020-07-01 2020-07-22 2020-08-05 2020-08-22 2021-11-15 en Development cation Selection ntation on of Interest for Chicken Val ue Chain KE-MURANGA COUNTY-1788 Supporting Community-Driv Consultant Qualifi Under Implement 91-CS-CQS / Call for expressi IDA / 59000 Post Open - National 50,000.00 0.00 2020-06-17 2020-07-01 2020-07-22 2020-08-05 2020-08-22 2021-11-15 en Development cation Selection ation on of Interest for Dairy value chain INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 PROCUREMENT PLAN (Textual Part) Project information: Republic of Congo Education Sector Support Project P152910 Project Implementation agency: [insert legal name] Date of the Procurement Plan: [insert date] Period covered by this Procurement Plan: [insert from – to period] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Congo, Republic of : Congo - Education Sector Support Project PLAN General Information Country: Congo, Republic of 2017-09-26 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P152910 GPN Date: Project Name: Congo - Education Sector Support Project Loan / Credit No: IDA / V0020, IDA / 58060 Education Sector Support Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRAASED-001-F-CF / matérie l informatique et mobilier- a Request for Quota Single Stage - One E IDA / V0020 Unallocated Post Limited 80,000.00 0.00 Canceled 2017-03-31 2017-05-26 2017-11-22 cquisition équipement inform tions nvelope atique et mobilier UCP PRAASED-014-F-CF / mobilie Request for Quota Single Stage - One E IDA / V0020 Unallocated Post Limited 80,000.00 0.00 Canceled 2017-04-04 2017-05-30 2017-11-26 r de bureau UCP tions nvelope PRAASED-012-F-CF / vehicul Request for Quota Single Stage - One E IDA / V0020 Unallocated Post Limited 120,000.00 246,318.60 Completed 2017-10-25 2018-02-09 2017-12-20 2018-01-09 2018-06-18 2018-03-30 e UCP tions nvelope PRAASED-002-F-ED / TOMPR IDA / V0020 Unallocated Prior Direct Selection Direct 40,000.00 0.00 Canceled 2017-03-28 2017-04-02 2017-05-07 2017-11-03 O- Acquisition logiciel TOMPR O PRAASED-012-F-ED / cablag IDA / V0020 Unallocated Post Direct Selection Direct 150,000.00 1,244.88 Signed 2017-10-30 2017-11-04 2017-12-09 2018-01-12 2018-06-07 es 4 sites MEPSA CG-PRAASED-065-F-CF-2018 / Fourniture matériel informa Providing quality education f Request for Quota Single Stage - One E tique (tablettes-ordinateurs) IDA / 58060 Post Limited 300,000.00 230,746.50 Completed 2018-04-24 2018-04-18 2018-06-19 2018-04-30 2018-12-16 2018-08-03 or all tions nvelope pour la collectes des donnée s statistiques des 3 ministère s de l'ensignement CG-PRAASED-075-F-CF-2018 / Fourniture, livraison et insta Improving system performa Request for Quota Single Stage - One E IDA / 58060 Post Limited 15,000.00 12,550.32 Completed 2018-07-11 2018-03-21 2018-09-05 2018-04-17 2019-03-04 2018-05-04 llation de l'équipement infor nce tions nvelope matique destiné à l'INS CG-PRAASED-078-F-CF-2018 / Fourniture de la conexion In Improving system performa Request for Quota Single Stage - One E IDA / 58060 Post Limited 12,000.00 10,469.68 Completed 2018-07-16 2018-04-30 2018-09-10 2018-06-04 2019-03-09 2022-06-22 ternet dans les bureaux du P nce tions nvelope RAASED (Abonnement et Equ ipement) CG-PRAASED-048-F-AON-17 Providing quality education f Request for Quota Single Stage - One E / Télephone mobile contrôle IDA / 58060 Post Open - National 10,000.00 0.00 Canceled 2018-11-27 2019-01-22 2019-07-21 or all tions nvelope action au sein des écoles CG-PRAASED-080-F-CF-2018 Improving system performa Request for Quota Single Stage - One E IDA / 58060 Post Limited 40,000.00 22,228.04 Completed 2018-08-04 2018-05-31 2018-09-29 2018-09-07 2019-03-28 2018-09-25 / Acquisition du Groupe élect nce tions nvelope rogène CG-PRAASED-085-AOI-2019 / Appel d'offre international po Improving scope, quality an Open - Internationa Single Stage - Two E ur la fourniture et installation IDA / 58060 d management of human re Post Request for Bids 800,000.00 0.00 Canceled 2019-03-04 2019-03-09 2019-04-20 2019-07-03 2019-08-07 2020-02-03 l nvelope d'un système pour l' enregist sources rement biométrique des ense ignants. CG-PRAASED-085 BIS-AOI-20 19-2 / Fourniture, installation Improving scope, quality an Open - Internationa Single Stage - One E et assistance à la mise en oe IDA / 58060 d management of human re Post Request for Bids 800,000.00 899,030.25 Completed 2019-05-11 2019-05-13 2019-05-16 2019-05-13 2019-06-27 2019-07-12 2019-07-27 2019-09-12 2019-08-31 2019-12-31 2020-02-27 2022-06-22 l nvelope uvre d'un système d'enregist sources rement biometrique des ense ignants du MEPSA. CG-PRAASED-104- F -ED- 20 19 / Internet : Renouvelleme Improving system performa nt du contrat de Fourniture d IDA / 58060 Post Direct Selection Direct 36,000.00 0.00 Canceled 2019-07-10 2019-06-26 2019-07-15 2019-07-16 2019-08-19 2020-02-15 nce e la connexion Internet dans les bureaux du PRAASED CG-PRAASED-099-F-ED-2019 Improving system performa IDA / 58060 Post Direct Selection Direct 2,000.00 3,600.00 Completed 2020-02-27 2019-11-08 2020-03-03 2020-01-13 2020-04-07 2020-01-30 2020-10-04 2020-02-08 / Acquisition du logiciel STAT nce A CG-PRAASED-0120-ASC-CF-2 020 / Production des fascicul Providing quality education f Request for Quota Single Stage - One E IDA / 58060 Post Limited 557,076.00 433,604.47 Completed 2020-06-16 2020-06-05 2020-08-11 2020-06-17 2021-02-07 2020-07-01 es restants destinés aux elev or all tions nvelope es du MEPSA en classes d'ex amen. CG-PRAASED-0121-CF- 2020 / Production des cahiers d’act ivités des classes intermédiai Providing quality education f Request for Quota Single Stage - One E IDA / 58060 Post Limited 853,788.00 1,218,698.85 Completed 2020-09-06 2020-09-18 2020-11-01 2020-10-08 2021-04-30 2020-12-31 res dans le pôle de Pointe-No or all tions nvelope ire (Pointe-Noire, Kouilou, Nia ri, Lekoumou, Bouenza), en d eux lots CG-PRAASED-0122-CF -2020 / Production des cahiers d’act ivités des classes intermédiai Providing quality education f Request for Quota Single Stage - One E IDA / 58060 Post Limited 970,973.00 1,280,761.25 Completed 2020-09-06 2020-09-18 2020-11-01 2020-10-08 2021-04-30 2021-04-27 res dans le pôle de Brazzavill or all tions nvelope e (Brazzaville, Pool, Plateaux Cuvette, Cuvette-Ouest, San gha et Likouala), lot unique. CG-PRAASED-081-F-CF-2018 / Acquisition fourniture de bu Improving system performa Request for Quota Single Stage - One E IDA / 58060 Post Limited 80,000.00 0.00 Canceled 2020-04-21 2020-06-16 2020-12-13 reau et consommables infor nce tions nvelope matiques- contrat cadre Page 1 CG-PRAASED-0149 -F-ED-20 21 / Logiciel AFIS- Acquisition Improving scope, quality an Under Imple d'une licence AFIS pour l'enr IDA / 58060 d management of human re Post Direct Selection Direct 185,981.00 0.00 2021-12-30 2021-12-17 2022-01-04 2022-02-08 2022-08-07 mentation ôlement biométrique de 30 0 sources 00 enseignants (phase génér alisation) CG-PRAASED-0157- / 12 véhi Improving system performa Request for Quota Single Stage - One E cules - Acquisition des 12 vé IDA / 58060 Post Limited 761,421.32 570,110.40 Signed 2022-03-21 2022-03-22 2022-05-16 2022-04-29 2022-11-12 nce tions nvelope hicules destinés aux DDEPSA CG-PRAASED-0158- F -CF-20 22 / PE+ CA du CP1-CP2 -La production et la livraison dan s les 12 Départements des pr Providing quality education f Request for Quota Single Stage - One E IDA / 58060 Post Limited 1,130,355.00 1,429,888.73 Signed 2022-03-23 2022-01-26 2022-05-18 2022-04-14 2022-11-14 ogrammes et guides pédago or all tions nvelope giques ainsi que les cahiers d'activités des nouveaux pro grammes révisés pour les cla sses de CP1, CP2. CG- PRAASED-0159-F- CF-20 22 / PE+ CA de la 6è et 5è -L a production et la livraison d ans les 12 Départements des Providing quality education f Request for Quota Single Stage - One E Under Imple IDA / 58060 Post Limited 752,248.91 0.00 2022-03-30 2022-08-01 2022-05-25 2022-11-21 programmes et guides pédag or all tions nvelope mentation ogiques (PE) ainsi que les ca hiers d'activités (CA) des nou veaux programmes révisés p our les classes de la 6ème et 5ème . CG-PRAASED-0176-F-CF-202 2 / DEP- IGEPSA-DDEPPSA - A Improving system performa Request for Quota Single Stage - One E cquisition du matériel inform IDA / 58060 Post Limited 60,000.00 0.00 Signed 2022-10-16 2022-10-25 2022-12-11 2023-06-09 nce tions nvelope atique destiné à la DEP, l'IGE PSA .et aux DDEPPSA du MEP PSA. CG-PRAASED-0177- F-ED-20 22 / CA 6è et 5è- Production des cahiers d’activités compl Providing quality education f émentaires des classes de 6è IDA / 58060 Post Direct Selection Direct - National 160,500.00 0.00 Signed 2022-10-29 2022-10-05 2022-11-03 2022-10-06 2022-12-08 2023-06-06 or all me et 5ème, issus des nouve aux programmes dans les d eux pôles (Brazzaville et Poin te-Noire). CG-PRAASED-0184-F-CF-202 Improving scope, quality an Request for Quota Single Stage - One E Under Imple 3 / DNEAS - Acquisition des é IDA / 58060 d management of human re Post Limited 16,933.00 0.00 2023-04-06 2023-06-01 2023-11-28 tions nvelope mentation quipements informatiques du sources DNEAS CG-PRAASED-0185-CS-CI-20 23 / Recrutement de 12 vérifi Providing quality education f Request for Quota Single Stage - One E IDA / 58060 Post Limited 70,632.00 0.00 Canceled 2023-04-08 2023-06-03 2023-11-30 cateurs indépendants des su or all tions nvelope pports pédagogiques distribu és CG-PRAASED-0189-F-CF-202 Improving scope, quality an 3 / Impression de 200 annuai Request for Quota Single Stage - One E Pending Impl IDA / 58060 d management of human re Post Limited 3,626.00 0.00 2023-04-19 2023-06-14 2023-12-11 res statistiques du MEPPSA 2 tions nvelope ementation sources 018 -2019 & 2019-2020 (15 j ours) CG-PRAASED-0192-CF-ED-20 23 / Recrutement des imprim eurs pour la Reproduction de Providing quality education f IDA / 58060 Post Direct Selection Direct - National 322,310.00 0.00 Canceled 2023-04-03 2023-04-08 2023-05-13 2023-11-09 s nouveaux programmes édu or all catifs et guides pédagogique s des classes restantes du CE 1 au CM2, 4ème à 3ème CG-PRAASED-0193-F-CF-202 Providing quality education f Request for Quota Single Stage - One E Pending Impl 3 / Impression des instrumen IDA / 58060 Post Limited 65,192.00 0.00 2023-04-08 2023-06-03 2023-11-30 or all tions nvelope ementation ts d’enquête finale du DNEAS CG-PRAASED-0195-F-CF-202 Providing quality education f Request for Quota Single Stage - One E Under Imple 3 / Acquisition de fournitures IDA / 58060 Post Limited 8,724.00 0.00 2023-04-08 2023-06-03 2023-11-30 or all tions nvelope mentation pour le DNEAS CG-PRAASED-0194-CF-ED-20 23 / Recrutement des imprim Providing quality education f eurs pour la Reproduction de IDA / 58060 Post Direct Selection Direct - National 1,205,584.00 0.00 Canceled 2023-04-03 2023-04-08 2023-05-13 2023-11-09 or all s cahiers d'activités des class es restantes du CE1 au CM2, 4ème à 3ème CG-PRAASED-0191-F-CF-202 Providing quality education f Request for Quota Single Stage - One E Pending Impl 3 / Impression des instrumen IDA / 58060 Post Limited 65,192.00 0.00 2023-04-15 2023-06-10 2023-12-07 or all tions nvelope ementation ts d’enquête finale CG-PRAASED-0198-CF-ED-20 23 / Reproduction des nouve aux programmes éducatifs et Providing quality education f Pending Impl IDA / 58060 Post Direct Selection Direct - National 322,311.00 0.00 2023-05-02 2023-05-07 2023-06-11 2023-12-08 guides pédagogiques du pri or all ementation maire (du CP1 au CM2) et col lège (de la 6ème en 3ème) CG-PRAASED-0199-CF-ED-20 23 / Reproduction des Cahier Providing quality education f Pending Impl IDA / 58060 Post Direct Selection Direct - National 974,955.00 0.00 2023-05-02 2023-05-07 2023-06-11 2023-12-08 s d'activités des programme or all ementation s révisés restants (CE1 au C M2, 4e et 3e) CG-PRAASED-0200-CF-ED-20 23 / Reproduction des Cahier Providing quality education f Pending Impl IDA / 58060 Post Direct Selection Direct - National 406,231.00 0.00 2023-05-02 2023-05-07 2023-06-11 2023-12-08 s d’activités des programmes or all ementation révisés restants (CE1 au CM2 , 4e et 3e) CG-PRAASED-0201-CF-ED-20 23 / Reproduction des Cahier Providing quality education f Pending Impl IDA / 58060 Post Direct Selection Direct - National 243,739.00 0.00 2023-05-02 2023-05-07 2023-06-11 2023-12-08 s d'activités des programmes or all ementation révisés restants (CE1 au CM2 , 4e et 3e) CG-PRAASED-0178 -F-AON-2 022 / - Tablettes SIGE- Acquis Improving system performa Single Stage - One E IDA / 58060 Post Request for Bids Open - National 124,000.00 0.00 Canceled 2022-12-23 2023-01-26 2022-12-28 2023-02-08 2023-02-08 2023-03-10 2023-04-14 2023-10-11 ition de 400 tablettes pour la nce nvelope mise en place du SIGE du ME PPSA PRAASED-013-F-AON / appar Single Stage - One E IDA / V0020 Unallocated Post Request for Bids Open - National 120,000.00 0.00 Canceled 2017-04-05 2017-04-10 2017-05-22 2017-06-21 2017-07-26 2018-01-22 eils biométriques nvelope NON CONSULTING SERVICES Page 2 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PRAASED-074-CF-ED-201 Improving system performa 8 / Contrat de bail à usage d IDA / 58060 Post Direct Selection Direct 122,400.00 0.00 Canceled 2018-06-27 2018-07-02 2018-08-06 2019-02-02 nce es bureaux du PRAASED CG-PRAASED-073-AS-CF-201 8 / Prestation de services pou Improving system performa Request for Quota Single Stage - One E IDA / 58060 Post Limited 12,000.00 4,667.89 Completed 2018-07-11 2018-03-05 2018-09-05 2018-03-15 2019-03-04 2018-03-16 r l'assurance tous risques de nce tions nvelope s véhicules destinés au PRAA SED CG-PRAASED-076-AS-CF-201 Improving system performa Request for Quota Single Stage - One E 8 / Prestation de services pou IDA / 58060 Post Limited 20,000.00 16,899.39 Completed 2018-07-11 2018-04-03 2018-09-05 2018-05-10 2019-03-04 2019-05-09 nce tions nvelope r le gardiennage des bureaux du PRAASED CG-PRAASED-077-AS-CF-201 Improving system performa Request for Quota Single Stage - One E 8 / Prestation de services pou IDA / 58060 Post Limited 10,000.00 7,331.05 Completed 2018-07-11 2018-04-03 2018-09-05 2018-05-10 2019-03-04 2019-05-09 nce tions nvelope r l'entretien des bureau du P RAASED CG-PRAASED-079-AS-CF-201 8 / Prestation de services pou r la restauration des participa nts à la formation sur la colle Improving system performa Request for Quota Single Stage - One E IDA / 58060 Post Limited 150,000.00 172,585.42 Completed 2018-07-16 2018-06-12 2018-09-10 2018-06-30 2019-03-09 2018-06-28 cte des données statistiques nce tions nvelope des ministères en charge de l 'éducation à Brazzaville, Poin te-Noire et Owando (en lots distincts. CG-PRAASED-091-ED-2019 / Contrat de maintenance et e Improving system performa ntretien du groupe electroge IDA / 58060 Post Direct Selection Direct 15,000.00 1,637.82 Completed 2019-04-23 2019-04-28 2019-04-29 2019-06-02 2019-05-10 2019-11-29 2020-08-28 nce ne du PRAASED, avec Grasse t SPORAFRIC- Fournisseur du groupe CG-PRAASED-105- ASC-ED-2 019 / Gardiennage - Renouve Improving system performa llement du contrat de Prestat IDA / 58060 Post Direct Selection Direct 57,600.00 32,554.89 Completed 2019-07-10 2019-07-07 2019-07-15 2019-07-07 2019-08-19 2019-08-20 2020-02-15 2020-12-30 nce ion de services pour le gardie nnage des bureaux du PRAA SED CG-PRAASED-106- ASC-ED-2 019 / Entretien bureaux : Ren Improving system performa ouvellement du contrat de Pr IDA / 58060 Post Direct Selection Direct 25,200.00 14,090.92 Completed 2019-07-10 2019-07-07 2019-07-15 2019-07-07 2019-08-19 2019-08-20 2020-02-15 2020-12-30 nce estation de services pour l'en tretien des bureau du PRAAS ED CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRAASED-009-C-SFQC / cabi Quality And Cost- Open - Internationa IDA / V0020 Unallocated Post 300,000.00 0.00 Canceled 2017-03-31 2017-04-21 2017-06-04 2017-07-02 2017-08-01 2017-09-05 2017-10-10 2018-10-10 net evalu syst educatif congo Based Selection l lais PRAASED-006-C-QC / cabine Consultant Qualifi Open - Internationa IDA / V0020 Unallocated Prior 40,000.00 0.00 Canceled 2017-03-27 2017-04-17 2017-05-31 2017-06-30 2017-08-04 2018-01-31 t perso clé cation Selection l CG-PRAASED-049-C-SFQC-17 Providing quality education f Quality And Cost- Open - Internationa / Cabinet système biométriqu IDA / 58060 Post 120,000.00 0.00 Canceled 2017-10-20 2017-11-10 2017-12-24 2018-01-21 2018-02-20 2018-03-27 2018-05-01 2019-05-01 or all Based Selection l e recensement enseignant CG-PRAASED-056-C-CI-17 / A Improving system performa Quality And Cost- Open - Internationa IDA / 58060 Prior 40,000.00 48,895.38 Completed 2018-02-05 2018-02-14 2018-02-26 2018-02-16 2018-04-11 2018-04-27 2018-05-09 2018-06-08 2018-06-04 2018-07-13 2018-06-13 2018-08-17 2018-06-13 2019-08-17 2019-08-29 udit externe 2017-2018 nce Based Selection l CG-PRAASED-037-C-SFQC-17 Providing quality education f Quality And Cost- Open - Internationa IDA / 58060 Prior 50,000.00 0.00 Canceled 2018-03-14 2018-04-04 2018-05-18 2018-06-15 2018-07-15 2018-08-19 2018-09-23 2019-09-23 / Audit externe or all Based Selection l CG-PRAASED-032-C-SFQC-17 / Analyse reforme enseignem Improving scope, quality an ent superieur et l'ensembe d Quality And Cost- Open - Internationa IDA / 58060 d management of human re Prior 250,000.00 0.00 Canceled 2019-06-17 2019-07-08 2019-08-21 2019-09-18 2019-10-18 2019-11-22 2019-12-27 2020-12-26 u système portant sur l'adéq Based Selection l sources uation enseignement superie ur et marché du travail , gou vernance du secteur... CG-PRAASED-029-C-SFQC-17 / Eval dispositifs et/ ou meca Providing quality education f Quality And Cost- Open - Internationa IDA / 58060 Post 200,000.00 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-26 2020-04-25 nismes d'évaluation des acqu or all Based Selection l is des élèves/apprentissage CG-PRAASED-026-C-SFQC / Cabinet recensement bénévo Providing quality education f Quality And Cost- Open - Internationa les et autres personnel ensei IDA / 58060 Post 170,000.00 0.00 Canceled 2018-11-05 2018-11-26 2019-01-09 2019-02-06 2019-03-08 2019-04-12 2019-05-17 2020-05-16 or all Based Selection l gnant: directeurs scolaires, c onseillers pédagogiques, insp ecteurs.. PRAASED-011 BIS-C-SFQC-2 018 / Révision des curriculas Improving system performa Quality And Cost- - Recrutement d'un cabinet c IDA / 58060 Prior Open - National 500,000.00 0.00 Canceled 2018-08-10 2018-08-31 2018-10-14 2018-11-11 2018-12-11 2019-01-15 2019-02-19 2020-02-19 nce Based Selection hargé de la révision des curri culas du primaire et secondai re CG-PRAASED-021-C-SFQC-17 Providing quality education f Quality And Cost- Open - Internationa IDA / 58060 Post 234,000.00 0.00 Canceled 2019-02-28 2019-03-21 2019-05-04 2019-06-01 2019-07-01 2019-08-05 2019-09-09 2020-09-08 / Contrôle travaux depart 1 or all Based Selection l CG-PRAASED-027-C-SFQC / c abinet enquête SDI - Recrute Providing quality education f Consultant Qualifi Open - Internationa IDA / 58060 Post 500,000.00 0.00 Canceled 2018-07-30 2018-08-17 2018-08-20 2018-09-03 2018-10-03 2018-11-02 2018-12-07 2019-06-05 ment d'un cabinet chargé de or all cation Selection l réaliser l'enquête SDI CG-PRAASED-030-C-SFQC-17 Providing quality education f Quality And Cost- Open - Internationa / Analyse programme de for IDA / 58060 Prior 700,000.00 0.00 Canceled 2019-02-19 2019-03-12 2019-04-25 2019-05-23 2019-06-22 2019-07-27 2019-08-31 2020-08-30 or all Based Selection l mation et pratiques classe CG-PRAASED-060-C-SQC-18 Improving scope, quality an / Mise en place du système bi Consultant Qualifi Open - Internationa IDA / 58060 d management of human re Post 240,000.00 0.00 Canceled 2018-03-13 2018-04-03 2018-05-17 2018-03-15 2018-06-16 2018-07-21 2019-01-17 ométrique pour l'enregistrem cation Selection l sources ent des enseignants Page 3 CG-PRAASED-089-CS-SFQC-2 019 / Enquete SDI- Recrutem Providing quality education f Quality And Cost- Open - Internationa ent d'un cabinet en charge d IDA / 58060 Prior 750,000.00 919,214.00 Completed 2019-03-12 2019-04-12 2019-04-02 2019-04-18 2019-05-16 2019-07-17 2019-06-13 2019-08-22 2019-07-13 2019-10-09 2019-08-17 2019-12-23 2019-09-21 2019-12-25 2020-09-20 2022-07-15 or all Based Selection l e l'enquete sur les indicateur s de prestation de services e n Republique du Congo CG-PRAASED-108- CS-QC-20 19 / INRAP- Recrutement d’u n consultant International po Improving system performa Consultant Qualifi Open - Internationa IDA / 58060 Post 50,000.00 0.00 Canceled 2019-07-11 2019-08-01 2019-09-14 2019-10-14 2019-11-18 2020-05-16 ur une assistance a l’elaborat nce cation Selection l ion d’une feuille de route et d ’un plan strategique de l’INR AP CG-PRAASED- 107- CS- QC-2 019 / ENI/ENS - Recrutement d’un Consultant International Improving system performa Consultant Qualifi Open - Internationa IDA / 58060 Post 50,000.00 0.00 Canceled 2019-07-11 2019-08-01 2019-09-14 2019-10-14 2019-11-18 2020-05-16 pour une assistance a l’elabo nce cation Selection l ration d’une feuille de route et d’un plan strategique de ENI/ENS CG-PRAASED-0114-CS-SFQC- 2019 / Audit Externe 2019-20 20 : Recrutement d'un cabin Improving system performa Quality And Cost- Open - Internationa IDA / 58060 Post 60,000.00 26,404.83 Completed 2019-10-24 2019-11-20 2019-11-14 2019-11-27 2019-12-28 2020-02-25 2020-01-25 2020-03-25 2020-02-24 2020-06-08 2020-03-30 2020-06-22 2020-05-04 2020-07-02 2021-05-04 2021-07-31 et d'expertise comptable cha nce Based Selection l rgé de l'audit des comptes d u PRAASED (exercices 2019- 2020). CG-PRAASED-125-SFQC-202 1 / Auditeur Interne - Recrute Improving system performa Quality And Cost- Open - Internationa IDA / 58060 Post 50,000.00 67,984.66 Terminated 2021-06-15 2021-01-14 2021-07-06 2021-08-19 2021-05-06 2021-09-16 2021-06-04 2021-10-16 2021-06-28 2021-11-20 2021-07-01 2021-12-25 2021-09-25 2022-12-25 ment d'un cabinet ou firme p nce Based Selection l our assurer la fonction d’audi t interne du PRAASED CG-PRAASED-125-SC-SFQC-2 021-REGULARISATI / Audit Int Improving system performa Quality And Cost- Open - Internationa erne - Recrutement d'un cabi IDA / 58060 Post 50,000.00 70,222.92 Signed 2021-10-08 2021-01-19 2021-10-29 2021-12-12 2021-05-06 2022-01-09 2021-06-04 2022-02-08 2021-06-18 2022-03-15 2021-07-01 2022-04-19 2021-09-25 2023-04-19 nce Based Selection l net ou firme pour assurer la f onction d'audit interne du PR AASED CG-PRAASED-0137-CS-QC-2 021 / Leadership - Recrutem Improving scope, quality an ent d’un cabinet/ Bureau d’ét Consultant Qualifi Open - Internationa Under Implement IDA / 58060 d management of human re Post 150,000.00 0.00 2021-11-04 2022-02-08 2021-11-25 2022-03-08 2022-01-08 2022-02-07 2022-03-14 2022-09-10 ude chargé de la formation d cation Selection l ation sources es Directeurs d’établissemen ts scolaires en leadership et en Management. CG-PRAASED-0148-CS-SFQC- 2021 / Audit externe 2021-20 22- Recrutement d'un cabin Improving system performa Quality And Cost- Open - Internationa et/ Firme d'expertise compta IDA / 58060 Post 60,000.00 13,616.09 Signed 2021-12-29 2022-01-18 2022-01-19 2022-02-02 2022-03-04 2022-03-18 2022-04-01 2022-04-20 2022-05-01 2022-04-26 2022-06-05 2022-05-24 2022-07-10 2022-05-24 2023-07-10 nce Based Selection l ble, chargé de l'audit des co mptes du PRAASED, exercice 2021 et exercice 2022 (clôtur e au 30 juin) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRAASED-003-C-CI / CI DFC- Individual Consult IDA / V0020 Unallocated Post Open 50,000.00 0.00 Canceled 2017-03-30 2017-05-18 2017-06-08 2017-07-13 2018-01-09 Evaluation des capacités DFC ant Selection PRAASED-008-C-CI / CI capa Individual Consult IDA / V0020 Unallocated Post Open 70,000.00 0.00 Canceled 2017-03-29 2017-05-17 2017-06-07 2017-07-12 2018-01-08 cité DDPSA ant Selection PRAASED-004-C-CI / CI INRA Individual Consult IDA / V0020 Unallocated Post Open 60,000.00 0.00 Canceled 2017-03-31 2017-05-19 2017-06-09 2017-07-14 2018-01-10 P- evaluation capacités INRA ant Selection P PRAASED-011-C-CI / CI revisi Individual Consult IDA / V0020 Unallocated Post Open 120,000.00 0.00 Canceled 2018-03-07 2018-04-25 2018-05-16 2018-06-20 2018-12-17 on curricula primaire et seco ant Selection ndaire PRAASED-015-C-ED / Elabor IDA / 58060 Unallocated Prior Direct Selection Direct 10,000.00 0.00 Canceled 2017-04-06 2017-04-16 2017-06-20 2017-12-17 ation manuel de procédures PRAASED-005-C-CI / CI ENI e Individual Consult t ENS- evaluation des formati IDA / V0020 Unallocated Post Open 90,000.00 0.00 Canceled 2017-03-31 2017-05-19 2017-06-09 2017-07-14 2018-01-10 ant Selection ons ENI et ENS CG-PRAASED-020-C-CI-17 / A Improving system performa Individual Consult IDA / 58060 Post Open 90,000.00 0.00 Canceled 2018-01-12 2018-01-11 2018-03-02 2018-03-23 2018-04-27 2018-10-24 uditeur interne nce ant Selection CG-PRAASED-038-C-CI-17 / R Improving system performa Individual Consult IDA / 58060 Post Open 90,000.00 0.00 Canceled 2017-11-06 2017-12-01 2017-12-25 2018-01-15 2018-02-19 2018-08-18 ecrut Comptable nce ant Selection CG-PRAASED-028-C-CI-17 / A Providing quality education f Individual Consult IDA / 58060 Prior Open 200,000.00 0.00 Canceled 2018-03-18 2018-01-19 2018-05-06 2018-05-27 2018-07-01 2018-12-28 nalyse inst MEPSA et DDPSA or all ant Selection CG-PRAASED-36-C-ED-17 / Pl Improving scope, quality an ate forme contrôle et verifica IDA / 58060 d management of human re Prior Direct Selection Direct 100,000.00 0.00 Canceled 2018-06-13 2018-06-23 2018-08-27 2019-02-23 tion des actions au sein de l' sources école par BLUE SQUARE CG-PRAASED-051-C-CI-17 / R Improving system performa Individual Consult IDA / 58060 Prior Open 139,200.00 245,144.43 Completed 2017-12-18 2018-02-05 2018-02-26 2018-01-18 2018-04-02 2018-01-15 2018-09-29 2021-01-30 ecrutement coordonnateur P nce ant Selection RAASED CG-PRAASED-052-C-CI-17 / R Improving system performa Individual Consult IDA / 58060 Prior Open 51,600.00 48,273.86 Completed 2017-12-18 2018-02-05 2018-02-26 2018-01-18 2018-04-02 2018-01-15 2018-09-29 2019-01-14 ecrutement RAFC nce ant Selection CG-PRAASED-053-C-CI-17 / R Improving system performa Individual Consult IDA / 58060 Prior Open 51,600.00 48,273.86 Completed 2017-12-18 2018-02-05 2018-02-26 2018-01-18 2018-04-02 2018-01-15 2018-09-29 2019-01-14 ecrutement SPM nce ant Selection CG-PRAASED-055-C-CDS-17 Providing quality education f / Appui INS aux trois ministèr IDA / 58060 Prior Direct Selection Direct 48,000.00 98,518.39 Completed 2018-02-15 2018-02-25 2018-05-01 2018-02-08 2018-10-28 2020-02-28 or all es MEPSA MES METPFQE CG-PRAASED-057-C-CI-18 / R Improving system performa Individual Consult IDA / 58060 Prior Open 228,000.00 0.00 Canceled 2018-02-13 2018-02-14 2018-04-03 2018-12-27 2018-04-24 2018-05-29 2018-11-25 ecrutement Auditeur interne nce ant Selection Page 4 CG-PRAASED-058-C-CI-18 / R Improving system performa Individual Consult IDA / 58060 Prior Open 192,000.00 101,406.72 Completed 2018-02-13 2018-02-14 2018-04-03 2018-04-18 2018-04-24 2018-06-12 2018-05-29 2018-06-12 2018-11-25 2021-01-30 ecrutement Comptable nce ant Selection CG-PRAASED-059-C-ED-18 / Appui au MEPSA pour partici Providing quality education f IDA / 58060 Prior Direct Selection Direct 617,760.00 466,774.66 Completed 2018-02-12 2018-02-22 2018-07-20 2018-04-28 2018-12-11 2018-10-25 2020-12-30 pation à l'évaluation internati or all onale PASEC 2019 CG-PRAASED-060-C-ED-2018 Improving system performa / Analyse institutionnelle MEP IDA / 58060 Prior Direct Selection Direct 200,000.00 56,498.00 Completed 2018-03-02 2018-03-07 2018-03-12 2018-03-13 2018-05-16 2018-06-11 2018-11-12 2018-12-29 nce SA et DDPSA CG-PRAASED-063-C-CI-18 / R Improving system performa Individual Consult ecrutement du Responsable IDA / 58060 Post Open 258,000.00 0.00 Canceled 2018-03-13 2018-03-06 2018-05-01 2018-05-22 2018-06-26 2018-12-23 nce ant Selection de la composante 3 (RC 3) d u PRAASED CG-PRAASED-062-C-CI-18 / R Improving system performa Individual Consult ecrutement du Responsable IDA / 58060 Post Open 258,000.00 0.00 Canceled 2018-03-13 2018-03-06 2018-05-01 2018-05-22 2018-06-26 2018-12-23 nce ant Selection de la composante 2 (RC 2) d u PRAASED CG-PRAASED-061-C-CI-18 / R Improving system performa Individual Consult ecrutement du responsable d IDA / 58060 Post Open 258,000.00 0.00 Canceled 2018-03-13 2018-03-06 2018-05-01 2018-05-22 2018-06-26 2018-12-23 nce ant Selection e la composante 1 (RC 1) du PRAASED CG-PRAASED-064-C-CI-18 / R Improving system performa Individual Consult ecrutement du Responsable IDA / 58060 Post Open 258,000.00 0.00 Canceled 2018-03-13 2018-03-06 2018-05-01 2018-05-22 2018-06-26 2018-12-23 nce ant Selection du Suivi-Evaluation (RSE) du PRAASED CG-PRAASED-063-C-CI-2018 Improving system performa Individual Consult / Recrutement du Responsabl IDA / 58060 Prior Open 258,000.00 87,084.54 Completed 2018-03-30 2018-04-27 2018-05-18 2018-12-07 2018-06-08 2019-02-07 2018-07-13 2019-02-08 2019-01-09 2021-01-30 nce ant Selection e de la composante 3 (RC3) du PRAASED CG-PRAASED-061-C-CI-2018 Improving system performa Individual Consult / Recrutement du Responsabl IDA / 58060 Prior Open 258,000.00 87,027.53 Completed 2018-03-30 2018-05-21 2018-05-18 2018-12-07 2018-06-08 2019-02-12 2018-07-13 2019-02-13 2019-01-09 2021-01-30 nce ant Selection e de la composante 1 (RC1) du PRAASED CG-PRAASED-064-C-CI-2018 Improving system performa Individual Consult / Recrutement du Responsabl IDA / 58060 Prior Open 258,000.00 87,519.28 Completed 2018-03-30 2018-04-27 2018-05-18 2018-12-07 2018-06-08 2019-02-07 2018-07-13 2019-02-08 2019-01-09 2021-01-30 nce ant Selection e Suivi-Évaluation (RSE) du P RAASED CG-PRAASED-066-C-CI-2018 Improving system performa Individual Consult / Recrutement d'un Assistant IDA / 58060 Post Open 168,000.00 0.00 Canceled 2018-05-04 2018-06-30 2018-06-22 2018-07-13 2018-08-17 2019-02-13 nce ant Selection chargé de la communication du PRAASED CG-PRAASED-068-C-CI-2018 Improving system performa Individual Consult / Recrutement d'un Trésorier IDA / 58060 Post Open 144,000.00 0.00 Canceled 2018-05-25 2018-04-25 2018-07-13 2018-08-03 2018-09-07 2019-03-06 nce ant Selection du PRAASED CG-PRAASED-069-C-CI-2018 Improving system performa Individual Consult / Recrutement d'un Assistant IDA / 58060 Post Open 96,000.00 0.00 Canceled 2018-05-25 2018-04-25 2018-07-13 2018-08-03 2018-09-07 2019-03-06 nce ant Selection Administratif du PRAASED CG-PRAASED-070-C-CI-2018 Improving system performa Individual Consult / Recrutement d'une Sécretai IDA / 58060 Post Open 72,000.00 0.00 Canceled 2018-05-25 2018-04-25 2018-07-13 2018-08-03 2018-09-07 2019-03-06 nce ant Selection re de direction du PRAASED CG-PRAASED-071-C-CI-2018 Improving system performa Individual Consult / Recutement de trois Chauff IDA / 58060 Post Open 108,000.00 25,277.93 Completed 2018-05-25 2018-04-25 2018-07-13 2018-08-06 2018-08-03 2018-08-23 2018-09-07 2018-09-03 2019-03-06 2020-09-30 nce ant Selection eurs du PRAASED CG-PRAASED-066-CS-CI-201 Improving system performa Individual Consult 8 / Recrutement d'un Spéciali IDA / 58060 Prior Open 258,000.00 87,556.69 Completed 2018-07-11 2018-08-02 2018-08-29 2019-01-21 2018-09-19 2019-02-27 2018-10-24 2019-03-01 2019-04-22 2021-01-30 nce ant Selection ste en charge de la communi cation CG-PRAASED-018-C-CI-17 / I ngénieur en génie civil - Rec Improving system performa Individual Consult IDA / 58060 Post Open 120,000.00 0.00 Canceled 2019-01-08 2019-02-26 2019-03-19 2019-04-23 2019-10-20 rutement d'un Ingénieur en g nce ant Selection énie civile chargé des constr uctions scolaires CG-PRAASED-050-C-CI-17 / C onsultant banque items pour Providing quality education f Individual Consult IDA / 58060 Post Open 25,000.00 0.00 Canceled 2018-10-22 2018-12-10 2018-12-31 2019-02-04 2019-08-03 évaluation des acquis scolair or all ant Selection e au primaire et secondaire CG-PRAASED-072-CS-CI-201 8 / Recrutement d'un Spéciali Improving system performa Individual Consult IDA / 58060 Post Open 90,000.00 0.00 Canceled 2018-09-04 2018-10-23 2018-11-13 2018-12-18 2019-06-16 ste en Sauvegarde environne nce ant Selection mentale du PRAASED CG-PRAASED-017-BIS-C-CI-2 018 / Sauvegarde sociale - R Improving system performa Individual Consult IDA / 58060 Post Open 90,000.00 0.00 Canceled 2018-09-04 2018-10-23 2018-11-13 2018-12-18 2019-06-16 ecrutement d'un consultant c nce ant Selection hargé d la suvegarde sociale du PRAASED CG-PRAASED-019-C-CI-17 / T Improving system performa Individual Consult IDA / 58060 Post Open 60,000.00 0.00 Canceled 2019-01-08 2019-02-26 2019-03-19 2019-04-23 2019-10-20 echnicien sup en génie civil nce ant Selection CG-PRAASED-082-C-ED-2018 / Consultant FGB - Recrutem ent du consultant Internation Providing quality education f IDA / 58060 Post Direct Selection Direct 60,000.00 0.00 Canceled 2018-08-07 2018-08-17 2018-08-17 2018-10-21 2019-04-19 al, spécialiste en formation g or all estion à la Base, pour la mise en oeuvre du volet communa utaire CG-PRAASED-062-C-CI-2018 Improving system performa Individual Consult / Recrutement du Responsabl IDA / 58060 Prior Open 258,000.00 0.00 Canceled 2018-03-30 2018-06-04 2018-05-18 2018-06-08 2018-07-13 2019-01-09 nce ant Selection e de la composante 2 (RC2) du PRAASED CG-PRAASED-062 BIS-CS-IN Improving system performa Individual Consult DV / Recrutement d'un Respo IDA / 58060 Prior Open 258,000.00 87,871.19 Completed 2019-01-15 2018-12-08 2019-03-05 2019-02-18 2019-03-26 2019-04-25 2019-04-30 2019-04-26 2019-10-27 2021-01-30 nce ant Selection nsable de la Composante 2 ( RC2) CG-PRAASED-017-C-CI-17 / R Improving system performa Individual Consult ecrutement Spécialiste sauve IDA / 58060 Post Open 90,000.00 0.00 Canceled 2018-09-20 2018-11-08 2019-01-17 2018-11-29 2019-01-03 2019-07-02 nce ant Selection garde environnementale et s ociale CG-PRAASED-057-CS-CI-201 Improving system performa Individual Consult 8 / Recrutement d'une Assist IDA / 58060 Post Open 76,800.00 32,760.67 Completed 2019-03-06 2019-04-24 2019-06-12 2019-05-15 2019-06-13 2019-06-19 2019-06-14 2019-12-16 2021-01-30 nce ant Selection ance de direction du PRAASE D Page 5 CG-PRAASED-083-CS-CI-201 9 / Renouvelement du contra Improving system performa Individual Consult IDA / 58060 Prior Direct 206,400.00 88,034.50 Completed 2019-02-22 2019-02-28 2019-03-04 2019-01-14 2019-03-25 2019-03-12 2019-04-29 2019-03-13 2019-10-26 2021-01-30 t de service du Responsable nce ant Selection Administratif et Financier (RA F) du PRAASED CG-PRAASED-086-CS-CI-201 9 / Renouvelement du contra Improving system performa Individual Consult IDA / 58060 Prior Direct 206,400.00 87,053.33 Completed 2019-02-22 2019-02-28 2019-03-04 2019-01-14 2019-03-25 2019-03-12 2019-04-29 2019-03-13 2019-10-26 2021-01-30 t de service de la Spécialiste nce ant Selection en Passation des Marches (S PM) du PRAASED CG-PRAASED-087-CS-CI-201 9 / Recrutement d'un consult ant international pour l'analy Providing quality education f Individual Consult IDA / 58060 Post Open 60,000.00 90,929.39 Completed 2019-02-28 2019-04-30 2019-04-18 2019-07-23 2019-05-09 2019-09-23 2019-06-13 2019-09-24 2019-12-10 2021-04-30 se du dispositif des évaluatio or all ant Selection ns sommatives et examens n ationaux (CEPE, BEPC, BAC) CG-PRAASED-090-CS-CI-201 Improving system performa Individual Consult 9 / Recrutement du 3ème ch IDA / 58060 Post Open 28,800.00 6,081.98 Completed 2019-03-27 2019-04-11 2019-05-15 2019-07-22 2019-06-05 2019-07-23 2019-07-10 2019-07-25 2020-01-06 2020-07-30 nce ant Selection auffeur du PRAASED CG-PRAASED-093-CS-CI-201 Improving system performa Individual Consult 9 / Recrutement d'un Speciali IDA / 58060 Post Open 103,200.00 67,045.43 Completed 2019-04-29 2019-04-29 2019-06-17 2019-08-12 2019-07-08 2019-09-05 2019-08-12 2019-10-09 2020-02-08 2021-01-30 nce ant Selection ste en Sauvegardes Sociales du PRAASED PRAASED-094-CS-CI-2019 / Recrutement d'un consultant national pour l'analyse des e Providing quality education f Individual Consult IDA / 58060 Post Open 12,000.00 0.00 Canceled 2019-05-13 2019-07-01 2019-07-22 2019-08-26 2020-02-22 valuations formatives en situ or all ant Selection ation de classe pour les devo irs departemantaux, examen s blancs et tests. CG PRAASED-095-CS-CI-201 9 / Recrutement d'un consult ant national pour l'analyse d Providing quality education f Individual Consult IDA / 58060 Post Open 12,000.00 0.00 Canceled 2019-05-13 2019-07-01 2019-07-22 2019-08-26 2020-02-22 es évaluations formatives en or all ant Selection situation de classe pour les d evoirs, compositions mensuel les/trimestrielles CG-PRAASED-097-CS-CI-201 9 / Recrutement d'un consult ant pour la redynamisation d Improving system performa Individual Consult IDA / 58060 Post Open 8,000.00 30,960.18 Signed 2019-05-16 2019-08-29 2019-07-04 2019-11-20 2019-07-25 2020-02-18 2019-08-29 2020-05-23 2020-02-25 u site web du MEPSA et mise nce ant Selection en place des sites web de l'IN RAP, IGEPSA, DEC et DGRHA. PRAASED-098-CS-CI-2019 / Recrutement d'un consultant international charge d'appui aux équipe tecniques- à l'ela Improving system performa Individual Consult IDA / 58060 Post Open 40,000.00 0.00 Canceled 2019-05-17 2019-07-05 2019-07-26 2019-08-30 2020-02-26 boration des feuilles de route nce ant Selection et plans strategiques pour la mise en oeuvre des recomm andations des etudes realise es (ENI/ENS, INRAP, MEPSA-D DEPSA. PRAASED-0100-CS-ED-2019 / Contrat de service de consu ltant avec Viticia THAMES, co Providing quality education f nsultante internationale pour IDA / 58060 Post Direct Selection Direct 60,000.00 0.00 Canceled 2019-05-21 2019-07-30 2019-05-31 2019-08-30 2019-08-04 2020-01-31 or all l'élaboration/adaptation du p rotocole/outils CLASS pour l'a melioration de la pedagogie active et de l'apprentissage. CG-PRAASED- 101- CS-ED-20 19 / Evaluations curriculas- R ecrutement du consultant int Providing quality education f ernational pour l'appui techni IDA / 58060 Post Direct Selection Direct 140,000.00 119,210.13 Completed 2019-07-04 2019-07-09 2019-07-14 2019-07-23 2019-09-17 2019-09-25 2020-03-15 2021-12-30 or all que au processus de révision des curricula (évaluation et l a réécriture) des programme s du primaire et du secondair e CG- PRAASED- 102-CS- CI-20 19 / Evaluations Formatives - Recrutement d’un consultant national chargé de l’analyse Providing quality education f Individual Consult du dispositif actuel des evalu IDA / 58060 Post Open 24,000.00 33,076.77 Completed 2019-07-07 2019-07-09 2019-08-21 2019-09-11 2019-09-11 2019-11-21 2019-10-16 2019-12-11 2020-04-13 2021-02-26 or all ant Selection ations formatives (devoirs de classe et departementaux, c ompositions mensuelles, trim estrielles, et examens blancs /tests ) dans le systeme educ CG-PRAASED-103- CS-CI-201 Improving system performa Individual Consult 9 / Auditeur Interne : Recrute IDA / 58060 Prior Open 228,000.00 0.00 Canceled 2019-07-08 2019-08-26 2019-09-16 2019-10-21 2020-04-18 nce ant Selection ment d'un auditeur interne d u PRAASED CG-PRAASED-109-CS-CI-201 9 / SIGE : Schema directeurs Improving system performa Individual Consult Recrutement d'un consultant IDA / 58060 Post Open 80,000.00 112,081.22 Completed 2019-08-12 2019-10-23 2019-09-30 2020-02-04 2019-10-21 2020-03-27 2019-11-25 2020-06-27 2020-05-23 2021-03-31 nce ant Selection international en charge de l'e laboration du schéma directe ur du SIGE. CG-PRAASED-110-CS-CI-201 9 / Carte Scolaire- Recruteme Improving system performa Individual Consult nt d'un consultant internatio IDA / 58060 Post Open 80,000.00 0.00 Canceled 2019-08-13 2019-10-24 2019-10-01 2019-10-22 2019-11-26 2020-05-24 nce ant Selection nal pour l'appui à l'équipe ch argé de l'élaboration de la ca rte scolaire CG-PRAASED-111-CS-CI-201 9 / IGEPSA- Recrutement du consultant international pour Improving system performa Individual Consult le renforcement des capacité IDA / 58060 Post Open 60,000.00 0.00 Canceled 2019-08-15 2019-09-03 2019-10-03 2019-10-24 2019-11-28 2020-05-26 nce ant Selection s de l'IGEPSA: appui à la réda ction du manuel de procédur e d'inspection et d'encadrem ent pédagogique et formatio ns CG-PRAASED- 108 BIS-CS-CI- 2019 / INRAP- Recrutement d ’un consultant International p Improving system performa Individual Consult IDA / 58060 Post Open 20,000.00 30,150.18 Signed 2019-08-16 2019-10-31 2019-10-04 2020-03-27 2019-10-25 2020-08-10 2019-11-29 2020-08-11 2020-05-27 our une assistance a élaborat nce ant Selection ion d’une feuille de route et d ’un plan stratégique de l’INR AP Page 6 CG-PRAASED-107 BIS-CS-ED- 2019 / ENI/ENS - Recrutemen t d’un Consultant Internation Improving system performa Individual Consult IDA / 58060 Post Limited 40,000.00 0.00 Canceled 2019-08-15 2019-10-02 2019-08-20 2019-09-10 2019-10-15 2020-04-12 al pour une assistance a l’ela nce ant Selection boration d’une feuille de rout e et d’un plan strategique de ENI/ENS CG-PRAASED-112-CS-ED-201 9 / DFC - Contrat de service a vec M. BALONGA Moise ,Cons Improving system performa Individual Consult IDA / 58060 Post Direct 20,000.00 0.00 Canceled 2019-09-17 2019-10-01 2019-09-27 2019-10-18 2019-11-22 2020-05-20 ultant national en charge de l nce ant Selection 'assistance a élaboration d’u ne feuille de route et d’un pla n strategique de la DFC CG PRAASED-096-CS-CI-201 9 / Recrutement d'un consult ant international chargé d'ap Improving system performa Individual Consult pui au renforcement des cap IDA / 58060 Post Open 30,000.00 0.00 Canceled 2019-11-17 2020-01-05 2020-01-26 2020-03-01 2020-08-28 nce ant Selection acites des partie prenantes ( cabinet MEPSA, APE, ONGs...) sur la gestion de l'ecole, le m erite et la recevabilite. CG-PRAASED-0115-CS-IND-2 020 / - Contrat Coordo- Reno Improving system performa Individual Consult uvellement du contrat de ser IDA / 58060 Post Direct 174,000.00 0.00 Canceled 2020-01-15 2020-02-12 2020-01-25 2020-02-15 2020-02-15 2020-02-17 2020-03-21 2020-09-17 nce ant Selection vice du Coordonnateur de l'U nité de Coordination du Proje t PRAASED. CG-PRAASED-0113-CS-CI-20 19 / ENI-ENS/DFC : Recrutem ent d'un consultant internati onal chargé d'appuiaux équi Improving system performa Individual Consult IDA / 58060 Post Open 60,000.00 0.00 Canceled 2019-10-24 2019-11-14 2019-12-12 2020-01-02 2020-02-06 2020-08-04 pes techniques, à l'élaboratio nce ant Selection n des feuilles de route pour l a mise en oeuvre des recom mandations des études réalis ées ENI-ENS/DFC. CG-PRAASED-0117-CS-ED-20 20 / Feuille MEPSA-DDEPSA : Recrutement d’un consultant international chargé d’appui Improving system performa Individual Consult aux équipes techniques, à l’é IDA / 58060 Post Direct 40,000.00 0.00 Canceled 2020-03-11 2020-03-19 2020-03-21 2020-03-19 2020-04-11 2020-05-16 2020-11-12 nce ant Selection laboration des feuilles de rou tes et plans stratégiques pou r la mise en œuvre des reco mmandations des études réa lisées MEPSA –DDEPSA CG-PRAASED-0119-CS-CI-20 20 / Elaboration PPA: Recrute ment d'un consultant nationa Providing quality education f Individual Consult IDA / 58060 Post Open 40,000.00 16,613.49 Completed 2020-03-11 2020-03-13 2020-04-29 2020-06-12 2020-05-20 2020-08-10 2020-06-24 2020-08-15 2020-12-21 2021-07-31 l chargé de l’élaboration d’u or all ant Selection n plan d’action en faveur des populations autochtones du PRAAESD CG-PRAASED-0118-CS-ED-20 20 / FGB-COGES: Recruteme nt d'un consultant internatio Providing quality education f Individual Consult nal, spécialiste n formation, e IDA / 58060 Post Direct 50,000.00 113,489.30 Signed 2020-03-20 2020-03-18 2020-03-30 2020-03-19 2020-04-20 2020-09-29 2020-05-25 2020-10-01 2020-11-21 or all ant Selection n gestion à la base (FGB) pou r la mise en place des comité s de Gestion scolaire (COGES ) CG-PRAASED-0116-CS-ED-20 20 / ENI-ENS/DFC- Recruteme nt d’un consultant internatio Improving scope, quality an nal chargé d’appui aux équip Individual Consult IDA / 58060 d management of human re Post Direct 40,000.00 33,199.26 Signed 2020-03-20 2020-03-19 2020-03-30 2020-03-19 2020-04-20 2021-01-07 2020-05-25 2021-01-12 2020-11-21 es techniques, à l’élaboration ant Selection sources des feuilles de routes et plan s stratégiques pour la mise e n œuvre des recommandatio ns des études réalisées ENI-E NS/ DFC CG-PRAASED-103 BIS-CS-CI- Improving system performa Individual Consult 2019 / Auditeur Interne - Rec IDA / 58060 Post Open 122,222.00 0.00 Canceled 2019-08-16 2019-10-24 2019-10-04 2019-12-13 2019-10-25 2019-11-29 2020-05-27 nce ant Selection rutement d'un Auditeur Inter ne du PRAASED PRAASED-092-CS-CI-2019 / Recrutement du consultant i nternational pour l'appui tec Providing quality education f Individual Consult IDA / 58060 Post Open 140,000.00 0.00 Canceled 2019-04-25 2019-06-13 2019-06-13 2019-07-04 2019-08-08 2020-02-04 hnique au processus de révis or all ant Selection ion des curricula (évaluation et la réécriture) des program mes du primaire et du secon daire CG-PRAASED-123-CS-ED-202 1 / Carte scolaire Consul Int - Improving system performa Recrutement d'un consultant IDA / 58060 Post Direct Selection Direct 66,667.00 54,100.00 Completed 2021-06-15 2021-01-14 2021-06-25 2021-03-26 2021-08-29 2021-06-15 2022-02-25 2022-05-03 nce international en charge de l'é laboration de la carte scolair e du MEPSA CG-PRAASED-126-CS-ED-202 1 / Guides pedagogiques- Ac compagnement pour la suite du processus de revision des Providing quality education f curricula pour les classes de IDA / 58060 Post Direct Selection Direct 60,000.00 46,931.85 Signed 2021-06-21 2022-02-01 2021-07-01 2022-03-23 2021-09-04 2022-03-26 2022-03-03 or all ce1, ce2, cm1, cm2, 4eme et 3eme ainsi que la conception des guides et des cahiers d’a ctivites des programmes edu catifs revises pour le primair ee CG-PRAASED- -124-CS-INDV- 2021 / Carte scolaire Consul Nat - Recrutement d'un cons Improving system performa Individual Consult IDA / 58060 Post Open 2,000.00 12,188.88 Completed 2021-06-15 2021-01-14 2021-08-03 2021-04-12 2021-08-24 2021-04-30 2021-09-28 2021-06-15 2022-03-27 2022-05-03 ultant national pour appui au nce ant Selection consultant international en c harge de l'élaboration de la c arte scolaire du MEPSA. CG-PRAASED-0128-CS-INDV- 2021 / Formateurs nationaux . - Recrutement de 5 consult Improving scope, quality an ants nationaux chargés de l’é Individual Consult IDA / 58060 d management of human re Post Limited 20,000.00 0.00 Canceled 2021-08-27 2021-09-10 2021-09-01 2021-09-22 2021-10-27 2022-04-25 laboration du guide et outils ant Selection sources de formation des enseignant s et inspecteurs et de la form ation des formateurs au mani ement des nouveaux progra mmes Page 7 CG-PRAASED-0127-CS-INDV- 2021 / Graphiste - Recrutem ent d’un graphiste pour l’éla Improving system performa Individual Consult boration des guides illustres IDA / 58060 Post Limited 8,000.00 4,657.84 Signed 2021-08-23 2021-09-10 2021-08-28 2021-04-26 2021-09-18 2021-09-13 2021-10-23 2021-09-17 2022-04-21 nce ant Selection des 3 modules de formation en gestion a la base (FGB) du programme d’institutionnalis ation des COGES CG-PRAASED-0133-CS-INDV- 2021 / Formateur Sylvain MB UYAMBA - Recrutement d'un consultant international char Improving scope, quality an Individual Consult gé de l’élaboration du guide IDA / 58060 d management of human re Post Direct 15,000.00 14,193.58 Completed 2021-08-27 2021-09-09 2021-09-06 2021-09-08 2021-09-27 2021-09-13 2021-11-01 2021-09-26 2022-04-30 2022-05-03 ant Selection et outils de formation des en sources seignants et inspecteurs et d e la formation des formateur s au maniement des nouveau x programmes. CG-PRAASED-0131-CS-INDV- 2021 / Formateur KATSUNGA - Recrutement d'un consulta Improving scope, quality an nt international chargé de l’é Individual Consult IDA / 58060 d management of human re Post Direct 15,000.00 14,193.58 Completed 2021-08-27 2021-09-09 2021-09-06 2021-09-16 2021-09-27 2021-09-25 2021-11-01 2021-09-26 2022-04-30 2022-05-03 laboration du guide et outils ant Selection sources de formation des enseignant s et inspecteurs et de la form ation des formateurs au mani ement des nouveaux progra mmes. CG -PRAASED 0129-CS -INDI V-2021 / Formateur IBUTCH - Recrutement d'un consultant Improving scope, quality an international chargé de l’élab Individual Consult IDA / 58060 d management of human re Post Direct 15,000.00 14,193.58 Completed 2021-08-27 2021-09-10 2021-09-06 2021-09-09 2021-09-27 2021-09-13 2021-11-01 2021-09-26 2022-04-30 2022-05-03 oration du guide et outils de f ant Selection sources ormation des enseignants et inspecteurs et de la formatio n des formateurs au maniem ent des nouveaux programm es. CG-PRAASED-0130-CS-INDV- 2021 / Formateur NKONGOL O - Recrutement d'un consult Improving scope, quality an ant international chargé de l’ Individual Consult IDA / 58060 d management of human re Post Direct 15,000.00 14,193.58 Completed 2021-08-27 2021-09-09 2021-09-06 2021-09-08 2021-09-27 2021-09-13 2021-11-01 2021-09-26 2022-04-30 2022-05-03 élaboration du guide et outils ant Selection sources de formation des enseignant s et inspecteurs et de la form ation des formateurs au mani ement des nouveaux progra mmes. CG-PRAASED-0132-CS-INDV- 2021 / Formateur Roger MBO UYAMBA TSIUNZA - Recrutem ent d'un consultant internati Improving scope, quality an Individual Consult onal chargé de l’élaboration IDA / 58060 d management of human re Post Direct 15,000.00 14,193.58 Completed 2021-08-27 2021-09-09 2021-09-06 2021-09-16 2021-09-27 2021-09-13 2021-11-01 2021-09-26 2022-04-30 2022-05-03 ant Selection du guide et outils de formatio sources n des enseignants et inspect eurs et de la formation des fo rmateurs au maniement des nouveaux programmes. CG-PRAASED-0134-CS-INDV- 2021 / Animateurs AGC- FGB : Recrutement de 12 animate Improving system performa Individual Consult Under Implement IDA / 58060 Post Open 40,000.00 0.00 2021-09-14 2021-09-10 2021-11-02 2021-11-23 2021-12-28 2022-06-26 urs en gestion communautair nce ant Selection ation e pour accompagner les com munautés éducatives au nive au primaire. CG-PRAASED-0135-CS-INDV- 2021 / Formateurs FGB : Recr Improving system performa Individual Consult Under Implement IDA / 58060 Post Open 40,000.00 0.00 2021-09-14 2021-09-10 2021-11-02 2021-11-23 2021-12-28 2022-06-26 utement de 12 formateurs F nce ant Selection ation GB du niveau primaire CG-PRAASED-0136-CS-ED-20 21 / Editoriale CA- Recruteme nt d'un consultant pour l'app ui à la mise en conformité éd Providing quality education f itoriale des Cahiers d'activit IDA / 58060 Post Direct Selection Direct 100,000.00 23,924.06 Completed 2021-10-30 2021-11-05 2021-11-09 2021-11-04 2022-01-13 2021-11-11 2022-07-12 2022-02-27 or all és issus des nouveaux progr ammes éducatifs révisés, en deux phases (phase 1: CP1, CP2, 6è et 5è et phase 2 : C E1, CE2, CM1, CM2, 4è et 3è) CG-PRAASED-0138-CS-ED-20 21 / CA - YAZBECK- Recrutem ent d’une Assistance techniq Providing quality education f ue pour la mise en conformit IDA / 58060 Post Direct Selection Direct 6,560.00 5,670.00 Completed 2021-11-10 2021-11-11 2021-11-20 2021-11-09 2022-01-24 2021-11-11 2022-07-23 2022-07-09 or all é éditoriale des cahiers d’acti vités issus des nouveaux pro grammes éducatifs révisés d e CP1, CP2, 6ème et 5ème. CG-PRAASED-0139-CS-ED-20 21 / CA- TARCELIN- Recrutem ent d’une Assistance techniq Providing quality education f ue pour la mise en conformit IDA / 58060 Post Direct Selection Direct 3,570.00 3,395.40 Completed 2021-11-10 2021-11-11 2021-11-20 2021-11-10 2022-01-24 2021-11-11 2022-07-23 2021-12-16 or all é éditoriale des cahiers d’acti vités issus des nouveaux pro grammes éducatifs révisés d e CP1, CP2, 6ème et 5ème CG-PRAASED-0140-CS-ED-20 21 / CA- RENARD - Recrutem ent d’une Assistance techniq Providing quality education f ue pour la mise en conformit IDA / 58060 Post Direct Selection Direct 2,975.00 2,841.75 Completed 2021-11-10 2021-11-11 2021-11-20 2021-11-04 2022-01-24 2021-11-11 2022-07-23 2022-03-01 or all é éditoriale des cahiers d’acti vités issus des nouveaux pro grammes éducatifs révisés d e CP1, CP2, 6ème et 5ème. CG-PRAASED-0141-CS-ED-20 21 / CA- MIOLA- Recrutement d’une Assistance technique p Providing quality education f our la mise en conformité édi IDA / 58060 Post Direct Selection Direct 4,760.00 4,546.80 Completed 2021-11-10 2021-11-11 2021-11-20 2021-11-04 2022-01-24 2021-11-11 2022-07-23 2022-07-09 or all toriale des cahiers d’activités issus des nouveaux program mes éducatifs révisés de CP1 , CP2, 6ème et 5ème CG-PRAASED-0142-CS-ED-20 21 / CA- MILLET : Recruteme nt d’une Assistance techniqu e pour la mise en conformité Providing quality education f IDA / 58060 Post Direct Selection Direct 2,711.00 2,580.50 Completed 2021-11-10 2021-11-11 2021-11-20 2021-12-09 2022-01-24 2021-11-11 2022-07-23 2022-07-09 éditoriale des cahiers d’activi or all tés issus des nouveaux progr ammes éducatifs révisés de CP1, CP2, 6ème et 5ème (Ch ristian MILLET). Page 8 CG-PRAASED-0143- CS-ED-2 021 / CA-Gabrielle Debbas- R ecrutement d’une Assistance technique pour la mise en co Providing quality education f IDA / 58060 Post Direct Selection Direct 1,785.00 1,701.00 Completed 2021-11-10 2021-11-11 2021-11-20 2021-11-09 2022-01-24 2021-11-11 2022-07-23 2022-07-09 nformité éditoriale des cahier or all s d’activités issus des nouve aux programmes éducatifs ré visés de CP1, CP2, 6ème et 5 ème . CG-PRAASED -0144-CS-ED-2 021 / CA- GUGES : Recrutem ent d’une Assistance techniq Providing quality education f ue pour la mise en conformit IDA / 58060 Post Direct Selection Direct 7,615.00 7,250.88 Completed 2021-11-10 2021-11-11 2021-11-20 2021-11-08 2022-01-24 2021-11-11 2022-07-23 2022-07-09 or all é éditoriale des cahiers d’acti vités issus des nouveaux pro grammes éducatifs révisés d e CP1, CP2, 6ème et 5ème. CG-PRAASED-0145- CS-ED-2 021 / CA-DAUBIGNARD : Recr utement d’une Assistance te Providing quality education f chnique pour la mise en conf IDA / 58060 Post Direct Selection Direct 5,946.00 5,659.00 Completed 2021-11-10 2021-11-11 2021-11-20 2021-11-10 2022-01-24 2021-11-11 2022-07-23 2022-07-09 or all ormité éditoriale des cahiers d’activités issus des nouveau x programmes éducatifs révi sés de CP1, CP2, 6ème et 5è me. CG-PRAASED-0146-CS-ED-20 21 / CA-HORRENBERGER- Re crutement d’une Assistance t Providing quality education f echnique pour la mise en con IDA / 58060 Post Direct Selection Direct 3,211.00 3,046.95 Completed 2021-11-10 2021-11-11 2021-11-20 2021-11-10 2022-01-24 2021-11-11 2022-07-23 2022-07-09 or all formité éditoriale des cahiers d’activités issus des nouveau x programmes éducatifs révi sés de CP1, CP2, 6ème et 5è me. CG-PRAASED-0147-CS-ED-20 21 / CA- AYMARD : Recrutem ent d’une Assistance techniq Providing quality education f ue pour la mise en conformit IDA / 58060 Post Direct Selection Direct 7,615.00 6,820.20 Completed 2021-11-10 2021-11-10 2021-11-20 2021-11-04 2022-01-24 2021-11-11 2022-07-23 2022-07-09 or all é éditoriale des cahiers d’acti vités issus des nouveaux pro grammes éducatifs révisés d e CP1, CP2, 6ème et 5ème. CG-PRAASED-0150-CS-INDV- 2022 / IBUTCH Valère Renf. C apacités -Recrutement du co nsultant international du renf Improving scope, quality an Individual Consult orcement pour renforcement IDA / 58060 d management of human re Post Direct 11,581.00 9,212.87 Signed 2022-03-11 2022-03-17 2022-03-21 2022-03-25 2022-04-11 2022-03-25 2022-05-16 2022-04-14 2022-11-12 ant Selection du pool des formateurs et pe sources rsonnel d'encadrement en ch arge de la formation décentr alisée dans le maniement de s nouveau programmes (IBU TCH Valère). CG-PRAASED-0151CS-INDV- 2022 / Roger MBUYAMBA Ren f. Capacités- Recrutement du consultant international pour Improving scope, quality an Individual Consult le renforcement du pool des f IDA / 58060 d management of human re Post Direct 11,581.00 9,220.26 Signed 2022-03-11 2022-03-17 2022-03-21 2022-03-25 2022-04-11 2022-03-30 2022-05-16 2022-04-14 2022-11-12 ant Selection ormateurs et personnel d'enc sources adrement en charge de la for mation décentralisée dans le maniement des nouveau pro grammes éducatifs (MBUYAM BA Roger) ; CG-PRAASED-152-CS-INDV-2 022 / Sylvain MBUYAMBA Re nf. Capacités- Recrutement d u consultant international po Improving scope, quality an Individual Consult ur le renforcement du pool d IDA / 58060 d management of human re Post Direct 11,581.00 9,220.26 Signed 2022-03-11 2022-03-17 2022-03-21 2022-03-24 2022-04-11 2022-03-25 2022-05-16 2022-04-14 2022-11-12 ant Selection es formateurs et personnel d' sources encadrement en charge de la formation décentralisée dans le maniement des nouveau p rogrammes éducatifs (MBUY AMBA Sylvain) CG-PRAASED-0153-CS-INDV- 2022 / KATSUNGA Renf. Capa cités- Recrutement du consul tant international du renforce Improving scope, quality an Individual Consult ment du pool des formateurs IDA / 58060 d management of human re Post Direct 11,581.00 9,212.87 Signed 2022-03-11 2022-03-17 2022-03-21 2022-03-25 2022-04-11 2021-09-13 2022-05-16 2022-04-14 2022-11-12 ant Selection et personnel d'encadrement sources en charge de la formation dé centralisée dans le manieme nt des nouveau programmes éducatifs (KATSUNGA) CG-PRAASED-0154-CS-INDV- 2022 / NKONGOLO Renf. Cap acités - Recrutement du cons ultant international pour le re Improving scope, quality an Individual Consult nforcement du pool des form IDA / 58060 d management of human re Post Direct 11,581.00 9,212.87 Signed 2022-03-11 2022-03-17 2022-03-21 2022-03-25 2022-04-11 2022-03-24 2022-05-16 2022-04-14 2022-11-12 ant Selection ateurs et personnel d'encadr sources ement en charge de la forma tion décentralisée dans le ma niement des nouveau progra mmes éducatifs (NKONGOLO ) CG-PRAASED- 0155-CS-ED-2 022 / SIGE- ACSI - Mise en pl ace des modules 1, 2 et 4 (g estion des établissements, d Improving system performa Under Implement es ressources humaines et e IDA / 58060 Post Direct Selection Direct 350,000.00 0.00 2022-03-16 2022-03-17 2022-03-26 2022-05-30 2022-11-26 nce ation xamen et concours) du SIGE au sein du MEPPSA, avec l'a ppui de l'ACSI : Développeme nt, déploiement et et interfaç age à Stateduc de l’ISU. CG-PRAASED-0156-CS-ED -2 022 / SIGE ISU-Mise en place et opérationnalisation du mo dule 5 (Statistique et Aide à l Improving system performa Pending Impleme a décision) du SIGE-MEPPSA IDA / 58060 Post Direct Selection Direct 313,900.00 0.00 2022-03-21 2022-03-31 2022-06-04 2022-12-01 nce ntation avec l'assistance technique d e l'Institut de l'UNESCO (ISU) : mise en place, utilisation, in terfaçage avec les modules 1 ,2 et et 4 du SIGE, CG - PRAASED- 0160- CS-ED- 2022 / NDOUNGOU - Appui a u consultant international da Providing quality education f ns le cadre de la reecriture d IDA / 58060 Post Direct Selection Direct 12,510.00 11,147.99 Signed 2022-04-12 2022-03-23 2022-04-22 2022-03-07 2022-06-26 2022-04-09 2022-12-23 or all es programmes des classes CE1 àCM2 et 4ème a 3ème ( Consultant NDOUNGOU Jean Pierre) Page 9 CG-PRAASED- 0161-CS-ED-2 022 / NKOMBO - Appui au co nsultant international dans le Providing quality education f IDA / 58060 Post Direct Selection Direct 12,510.00 11,147.99 Signed 2022-04-12 2022-03-23 2022-04-22 2022-03-28 2022-06-26 2022-04-09 2022-12-23 cadre de la reecriture des pr or all ogrammes des classes CE1 a CM2 et 4ème a 3ème.(Cons ultant NKOMBO Edouard) CG-PRAASED-0162-CS-ED-20 22 / NDEBANI- Appui au cons ultant international dans le c Providing quality education f IDA / 58060 Post Direct Selection Direct 12,510.00 11,147.99 Signed 2022-04-12 2022-03-23 2022-04-22 2022-03-28 2022-06-26 2022-04-09 2022-12-23 adre de la reecriture des pro or all grammes des classes CE1 a CM2 et 4ème a 3ème.(Cons ultant NDEBANI François) CG-PRAASED-0163-CS-ED-20 22 / NZENZA- Appui au consu ltant international dans le ca Providing quality education f IDA / 58060 Post Direct Selection Direct 12,510.00 11,147.99 Signed 2022-04-12 2022-03-23 2022-04-22 2022-03-25 2022-06-26 2022-04-09 2022-12-23 dre de la reecriture des progr or all ammes des classes CE1 a CM 2 et 4ème a 3ème.(Consulta nt NZENZA Jacqueline) CG-PRAASED-0164-CS-ED-20 22 / DIANSATOU- Appui au c onsultant international dans l Providing quality education f IDA / 58060 Post Direct Selection Direct 12,510.00 11,139.08 Signed 2022-04-12 2022-03-23 2022-04-22 2022-03-28 2022-06-26 2022-04-09 2022-12-23 e cadre de la reecriture des p or all rogrammes des classes CE1 a CM2 et 4ème a 3ème.(DIA SANTOU Jonas) CG-PRAASED-0165-CS-ED-20 22 / MAZIKOU- Appui au cons ultant international dans le c Providing quality education f IDA / 58060 Post Direct Selection Direct 12,510.00 11,147.99 Signed 2022-04-12 2022-03-23 2022-04-22 2022-03-25 2022-06-26 2022-04-09 2022-12-23 adre de la reecriture des pro or all grammes des classes CE1 a CM2 et 4ème a 3ème.(MAZI KOU Aimé Hubert CG-PRAASED-0166-CS-ED-20 22 / Editoriale PE- Mise en co nformité éditoriale et de mis Providing quality education f IDA / 58060 Post Direct Selection Direct 32,000.00 7,575.12 Signed 2022-06-10 2022-06-23 2022-06-20 2022-06-23 2022-08-24 2022-06-11 2023-02-20 e en pages de 6 guides-progr or all ammes Congo, Français, Mat hs et sciences, CP1-CP2 et 6è me -5ème. CG-PRAASED-0167-CS-ED-20 22 / Editoriale PE Daubignard - Mise en conformité éditorial Providing quality education f IDA / 58060 Post Direct Selection Direct 5,800.00 5,392.01 Signed 2022-06-27 2022-06-27 2022-07-07 2022-06-22 2022-09-10 2022-06-11 2023-03-09 e et de mise en pages de 6 g or all uides-programmes Congo, Fr ançais, Maths et sciences, CP 1-CP2 et 6ème -5ème. CG-PRAASED-0168-CS-ED-20 22 / Editoriale PE Guges- Mis e en conformité éditoriale et Providing quality education f IDA / 58060 Post Direct Selection Direct 4,330.00 4,028.49 Signed 2022-06-27 2022-06-27 2022-07-07 2022-06-22 2022-09-10 2022-06-11 2023-03-09 de mise en pages de 6 guide or all s-programmes Congo, França is, Maths et sciences, CP1-CP 2 et 6ème -5ème. CG-PRAASED-0169-CS-ED-20 22 / Editoriale PE-2 - Assistan ce technique, pour la mise e n conformité éditoriale des n Providing quality education f Direct - Internation ouveaux programmes éducat IDA / 58060 Post Direct Selection 25,000.00 21,738.68 Signed 2022-08-19 2022-08-19 2022-08-29 2022-08-08 2022-11-02 2022-08-21 2023-05-01 or all al ifs et guides pédagogiques d e CP1-CP2 pour le français et les sciences du primaire et le s classes de 6è et 5è pour les SVT de collège (phase 2). CG-PRAASED-0170-CS-ED-20 22 / NDOUNGOU -Phase 2- A ppui au consultant internatio Providing quality education f nal dans le cadre de la reecri IDA / 58060 Post Direct Selection Direct - National 12,000.00 0.00 Signed 2022-10-04 2022-10-07 2022-10-14 2022-07-14 2022-12-18 2023-06-16 or all ture des programmes des cla sses CE1 a CM2 et 4ème a 3 ème.(NDOUNGOU Jean Pierre ), Phase 2. CG-PRAASED-0171-CS-ED-20 22 / NKOMBO- Phase 2 - App ui au consultant international Providing quality education f Under Implement IDA / 58060 Post Direct Selection Direct - National 12,000.00 0.00 2022-10-04 2022-10-07 2022-10-14 2022-07-14 2022-12-18 2023-06-16 dans le cadre de la reecriture or all ation des programmes des classes CE1 a CM2 et 4ème a 3ème. (NKOMBO Edouard), Phase 2 CG-PTAASED-0172-CS-ED-20 22 / NDEBANI-Phase 2- Appui au consultant international d Providing quality education f Under Implement ans le cadre de la reecriture IDA / 58060 Post Direct Selection Direct - National 12,000.00 0.00 2022-10-04 2022-10-07 2022-10-14 2022-08-29 2022-12-18 2023-06-16 or all ation des programmes des classes CE1 a CM2 et 4ème a 3ème (Consultant NDEBANI Françoi s), Phase 2. CG- PRAASED-0173-CS-ED-2 022 / NZENZA- Phase 2- App ui au consultant international Providing quality education f dans le cadre de la reecriture IDA / 58060 Post Direct Selection Direct - National 12,000.00 0.00 Signed 2022-10-04 2022-10-07 2022-10-14 2022-07-14 2022-12-18 2023-06-16 or all des programmes des classes CE1 a CM2 et 4ème a 3ème (NZENZA Jacqueline), Phase 2; CG-PRAASED-0175-SC-ED-20 22 / MAZIKOU- Phase 2- App ui au consultant international Providing quality education f Under Implement dans le cadre de la reecriture IDA / 58060 Post Direct Selection Direct - National 12,000.00 0.00 2022-10-04 2022-10-07 2022-10-14 2022-10-07 2022-12-18 2023-06-16 or all ation des programmes des classes CE1 a CM2 et 4ème a 3ème (MAZIKOU Aimé Hubert), pha se 2. CG-PRAASED-0174-CS-ED-20 22 / DIANSATOU -Phase 2- Ap pui au consultant internation Providing quality education f Under Implement al dans le cadre de la reecrit IDA / 58060 Post Direct Selection Direct - National 12,000.00 0.00 2022-10-04 2022-10-17 2022-10-14 2022-08-29 2022-12-18 2023-06-16 or all ation ure des programmes des clas ses CE1 a CM2 et 4ème a 3è me (DIASANTOU Jonas); Phas e 2; Page 10 CG-PRAASED-0178- CS-ED-2 022 / PNEAS- Convention ave c la CONFEMEN pour la mise Providing quality education f Direct - Internation Under Implement à disposition de 3 consultant IDA / 58060 Post Direct Selection 145,622.00 0.00 2022-11-15 2022-11-09 2022-11-25 2023-01-29 2023-07-28 or all al ation s chargés de l'enquête natio nale sur l'évaluation et le ren forcement des capacités des membres du PNEAS. CG-PRAASED -0179- CS-ED-2 022 / ISU- DEP- Convention a vec ISU (UNESCO), pour la fo Improving system performa Direct - Internation Under Implement rmation des agents de la DEP IDA / 58060 Post Direct Selection 70,632.00 0.00 2022-11-16 2022-11-09 2022-11-26 2023-01-30 2023-07-29 nce al ation dans le calcul des indicateurs requis pour l'analyse de la pe rformance du système éduca tif. CG-PRAASED-0180- CS-CI-20 22 / 12 Vérificateurs - Recrut ement de 12 consultants en Providing quality education f Individual Consult Pending Impleme charge de la vérification des IDA / 58060 Post Limited 70,632.00 0.00 2022-11-15 2022-11-20 2022-12-11 2023-01-15 2023-07-14 or all ant Selection ntation supports pédagogiques et m atériels didactiques distribué s par le PRAASED, dans les d épartements. CG-PRAASED-0181-CS-CI- 20 22 / LMD CI- Recrutement de Improving scope, quality an Individual Consult Open - Internationa Under Implement deux consultants internation IDA / 58060 d management of human re Post 108,200.00 0.00 2022-11-21 2022-11-16 2023-01-09 2023-01-30 2023-03-06 2023-09-02 ant Selection l ation aux en charge des contenus sources de formation en lien avec le s ysteme LMD . CG-PRAASED-0182- CS-CI-20 22 / LMD CN- Recrutement d Improving scope, quality an e deux consultants nationaux Individual Consult Under Implement IDA / 58060 d management of human re Post Open - National 52,500.00 0.00 2022-11-21 2022-11-16 2023-01-09 2023-01-30 2023-03-06 2023-09-02 en appui aux consultants inte ant Selection ation sources rnationaux en charge des co ntenus de formation en lien a vec le système LMD. CG-PRAASED- 0179-CS-ED-2 023 / PE CE1-CM, 4è-3è -Phas e1- Mise en conformité éditor Providing quality education f Direct - Internation iale des programmes éducati IDA / 58060 Post Direct Selection 48,462.00 0.00 Canceled 2023-01-12 2023-01-22 2023-03-28 2023-09-24 or all al fs et guides pédagogiques, Fr ançais, Maths et Sciences, de s classes de CE1-CE2, CM1-C M2, 4è-3è (phase1). CG-PRAASED-0180-CS-ED-20 23 / PE CE-CM,4è-3è- Mise en conformité éditoriale des pro Providing quality education f Direct - Internation grammes éducatifs et guides IDA / 58060 Post Direct Selection 90,000.00 0.00 Canceled 2023-01-31 2023-01-26 2023-02-10 2023-04-16 2023-10-13 or all al pédagogiques, Français, Mat hs et Sciences, des classes d e CE1-CE2, CM1-CM2, 4è-3è ( phase1). CG-PRAASED-0181-CS-ED-20 23 / PE+CA - CE-CM, 4è-3è -- Mise en conformité éditoriale des programmes éducatifs et Providing quality education f Direct - Internation Under Implement IDA / 58060 Post Direct Selection 172,500.00 0.00 2023-02-07 2023-02-07 2023-02-17 2023-01-16 2023-04-23 2023-10-20 guides pédagogiques en Fran or all al ation çais, Maths et Sciences, et de s cahiers d’activités des class es de CE1-CE2, CM1-CM2, 4è -3è (phase1+phase2), CG-PRAASED-0182-SC-ED-20 23 / Etats généraux- Recrute ment d’un consultant interna Improving scope, quality an Direct - Internation Under Implement tional dans le cadre de l’app IDA / 58060 d management of human re Post Direct Selection 17,500.00 0.00 2023-02-22 2023-02-23 2023-03-04 2023-05-08 2023-11-04 al ation ui du PRAASED aux etats gen sources eraux de l’education national e, de la formation et de la re cherche CG-PRAASED-0183-CS-ED-20 23 / Recrutement par entent Improving system performa Under Implement e avec l'ACSI pour le Dévelop IDA / 58060 Post Direct Selection Direct - National 240,276.00 0.00 2023-03-20 2023-03-22 2023-03-30 2023-06-03 2023-11-30 nce ation pement, la mise en place et l e déploiement du SIGE CG-PRAASED-0186-CS-ED-20 23 / Recrutement d’un consul tant international pour l’appu Improving system performa Direct - Internation Under Implement IDA / 58060 Post Direct Selection 5,708.00 0.00 2023-03-31 2023-05-05 2023-04-10 2023-06-14 2023-12-11 i thématique aux états génér nce al ation aux de l’éducation nationale, de la formation et de la rech erche CG-PRAASED-0187-CS-ED-20 23 / Recrutement d’un cabin Improving scope, quality an et d’expertise comptable pou Direct - Internation Under Implement IDA / 58060 d management of human re Post Direct Selection 16,336.00 0.00 2023-03-30 2023-04-06 2023-04-09 2023-06-13 2023-12-10 r l’audit des comptes du PRA al ation sources ASED pour les exercices 202 2 (exercice plein) et 2023 (cl os au 30 juin 2023) CG-PRAASED-0188-CS-ED-20 23 / Recrutement du consult Improving scope, quality an ant international pour le renf Direct - Internation Under Implement IDA / 58060 d management of human re Post Direct Selection 23,709.00 0.00 2023-04-03 2023-04-06 2023-04-13 2023-06-17 2023-12-14 orcement des capacités tech al ation sources nique des membres de l'équi pe du projet "assurance-quali té" CG-PRAASED-0190-CS-ED-20 Improving scope, quality an Direct - Internation Pending Impleme 23 / Convention avec l'ISU su IDA / 58060 d management of human re Post Direct Selection 72,500.00 0.00 2023-04-10 2023-04-20 2023-06-24 2023-12-21 al ntation r le calcul des indicateurs sources CG-PRAASED-0196-CS-ED-20 23 / Recrutement d’une agen ce n° 1 de paiement des part icipants à la formation décen Improving system performa Under Implement IDA / 58060 Post Direct Selection Direct - National 53,042.00 0.00 2023-04-17 2023-04-17 2023-04-27 2023-07-01 2023-12-28 tralisée des enseignants au nce ation maniement des nouveaux pr ogrammes éducatifs de CE1- CM2 et 4ème -3ème : Groupe ment MAOUENE CG-PRAASED-0197-CS-ED-20 23 / Recrutement de l’agenc e 1 de paiement des particip Improving system performa Under Implement ants à la formation décentrali IDA / 58060 Post Direct Selection Direct - National 83,702.00 0.00 2023-04-17 2023-04-17 2023-04-27 2023-07-01 2023-12-28 nce ation sée des enseignants au mani ement des nouveaux progra mmes éducatifs de CE1-CM2 et 4ème -3ème : EXPRESS U NION Page 11 CG-PRAASED-0202-CS-CI-20 23 / Recrutement d'un consul Individual Consult IDA / 58060 Unallocated Post Limited 192,730.00 0.00 Canceled 2023-05-08 2023-05-08 2023-05-13 2023-06-03 2023-07-08 2024-01-04 tant en charge de l'élaboratio ant Selection n du rapport d'achèvement d u PRAASED CG-PRAASED-0185BIS-CS-CI- 2023 / Recrutement de 12 vé Providing quality education f Individual Consult IDA / 58060 Post Limited 70,632.00 0.00 Canceled 2023-04-13 2023-04-18 2023-05-09 2023-06-13 2023-12-10 rificateurs indépendants des or all ant Selection supports pédagogiques distri bués CG-PRAASED-0203-CS-ED-20 23 / Recrutement de 12 vérifi cateurs indépendants de l’eff Providing quality education f Under Implement IDA / 58060 Post Direct Selection Direct - National 70,632.00 0.00 2023-05-24 2023-06-02 2023-06-03 2023-08-07 2024-02-03 ectivité de la distribution et u or all ation tilisation des programmes éd ucatifs et cahiers d’activités dans les 12 départements CG-PRAASED-0202BIS-CS-ED Improving scope, quality an -2023 / Recrutement d'un co Direct - Internation Under Implement IDA / 58060 d management of human re Post Direct Selection 43,772.00 0.00 2023-05-31 2023-05-31 2023-06-10 2023-08-14 2024-02-10 nsultant en charge de l'élabo al ation sources ration du rapport d'achèvem ent du PRAASED CG-PRAASED-0204-CS-ED-20 23 / Recrutement d’une micr ofinance devant assurer la pr Improving system performa Under Implement ise en charge des participant IDA / 58060 Post Direct Selection Direct - National 3,187.00 0.00 2023-06-01 2023-06-01 2023-06-11 2023-08-15 2024-02-11 nce ation s à la formation décentralisé e des directeurs d’établissem ents scolaires au leadership et au management PRAASED-007-C-CI / manuel Individual Consult IDA / V0020 Unallocated Prior Open 22,000.00 0.00 Canceled 2017-03-27 2017-05-15 2017-06-05 2017-07-10 2018-01-06 exécution ant Selection PRAASED-010-C-CI / CI prep Individual Consult IDA / V0020 Unallocated Prior Open 60,000.00 0.00 Canceled 2017-04-20 2017-06-08 2017-06-29 2017-08-03 2018-01-30 ation DAO matériel didactiqu ant Selection e Page 12 Procurement Plan (For Contracts not yet initiated – to be entered in STEP) I. General 1. Project Information Country: Malawi Project Name: Southern Africa Tuberculosis & Health Systems Support Project Project ID: P155658 2. Project Implementation Agency: Ministry of Health – National TB Control Programme 3. Date of the Procurement Plan: June 2017 4. Period Covered by this procurement plan: 24 Months II. Thresholds for Prior Review, Procurement Approaches and Methods A. Goods, Works and Non-Consulting Services Procurement Approaches and Methods Prior Review (US$ millions) Category (US$ Open Open Request for millions) International National Quotation (RfQ) Works ≥5 ≥5 >0.1- <0.1 <5 Goods, IT, and > 0.1 - non-consulting ≥1 ≥1 <0.1 <5 services B. Consulting Services Category Prior Review Short List of National Consultants (US$ (US$ million) millions) Consulting Engineering and Services Construction Supervision Consultants ≥ 0.2 < 0.2 ≥ 0.3 (Firms) Individual ≥ 0.1 NA. NA. Consultants 1 [Overall Project Procurement Risk is SUBSTANTIAL] Notes: Terms of Reference: Terms of Reference for all contracts shall be cleared by the Bank, regardless of whether the assignment is for prior or post review. Advertisement: Consultancy Service for Contracts estimated to cost US$ 300,000 equivalent and above per contract shall be advertised in UNDB online in addition to advertising in National News Paper(s) of wide circulation and/or Regional News Paper(s). 2 III. Packages for Goods, Works and Non-Consulting Services Component 1: Prevention Detection and Treatment of TB Goods Activity Contract Description Estimate Review Market Selection Evaluatio Procureme Prequ Domes Expect Expecte No d Cost by Approach Method n Options nt Process: alifica tic ed d date (US$) Bank (Open- (RFP, (BAFO, (Single/Mul tion Prefere date of of (Prior/P National/ RFB, Rated tiple (Yes/ nce bid/ Contract ost) Internation RFQ, DS Criteria Stages; No) (Yes/N propos Signatur al/ Limited etc.) etc.) One/Two o) al e etc.) Envelopes openin etc) g 1.2.1.1.5 Procure standard equipment 94,444 Post Limited RFQ Single No No 31st 30th for pre-in and post-service August Septem medical examinations for 2017 ber occupational health and safety. 2017 1.2.1.1.4 Procure Inspection Equipment 97,083 Post Limited RFQ Single No No 31st 30th for Ministry of Labour and August Septem Department of Mines 2017 ber 2017 1.1.1.4.4 Procure Motorcycles to support 63,300 Post Limited RFQ Single No No 31st 30th sputum sample collection August Septem points/supervision 2017 ber 2017 1.1.2.6.3 Personal protective materials 12,660 Post Limited RFQ Single No No 31st 30th for TB Laboratory Personnel August Septem (TB infection control) 2017 ber 2017 Stationery 19,305.4 Post Limited RFQ Single No No 31st 30th 9 August Septem 2017 ber 2017 Sub-Total 286,792 .49 3 Works Activity Contract Description Estimate Review Market Selection Evaluatio Procureme Prequ Domes Expect Expecte No d Cost by Approach Method n Options nt Process: alifica tic ed d date (US$) Bank (Open- (RFP, (BAFO, (Single/Mul tion Prefere date of of (Prior/P National/ RFB, Rated tiple (Yes/ nce bid/ Contract ost) Internation RFQ, DS Criteria Stages; No) (Yes/N propos Signatur al Limited etc.) etc.) One/Two o) al e etc.) Envelopes openin etc) g 1.1.3.3.1 Renovations (MDR TB Centres) 33,333 Post Limited RFQ Single No No 31st 30th August Septem 2017 ber 2017 1.1.2.6.2 Identify and Refurbishment of 41,667 Post Limited RFQ Single No No 31st 30th TB Isolation Rooms at selected August Septem facilities 2017 ber 2017 2.2.2.7.3 Renovations and Furnish Labs 108,333 Post Open- RFB Single No No 31st 30th National August Septem 2017 ber 2017 Sub-Total 183,333 4 Component 2: Regional Capacity for Disease Surveillance, Diagnostics Management of TB and Occupational Health Packages for Consulting Services Activity Contract Description Estimate Review Market Selectio Shortlis Expected date of bid/ Expected No d Cost by Approach n ting proposal opening date of (US$) Bank (Open- Method (Yes/ Contract (Prior/P National/ (QCBS, No) Signature ost) Internatio FBBS, nal LCBS, Limited QBS, etc.) CQS, DS etc.) 2.3.1.1.1 Consultant to draft/review the 18,950 Prior Open - CQS Yes 31st August 2017 30th Mines Safety Act/Public Health National September Act/Occupational Safety Health 2017 and Welfare Act and Regulations. Sub-Total 18,950 Goods 5 Activity Contract Description Estimated Review Market Selection Evaluati Procureme Prequ Domes Expect Expecte No Cost (US$) by Approach Method on nt Process: alifica tic ed d date Bank (Open- (RFP, RFB, Options (Single/Mul tion Prefere date of of (Prior/P National/ RFQ, DS (BAFO, tiple (Yes/ nce bid/ Contract ost) Internation etc.) Rated Stages; No) (Yes/N propos Signatur al Limited Criteria One/Two o) al e etc.) etc.) Envelopes openin etc) g 2.2.2.5.1 Procure Microscopes and Lab 53,932 Post Open- RFB Single No No 12 31 July Supplies National June 2017 2017 2.2.2.5.1 Procurement of Lab 20,000 Post Limited RFQ Single No No 31st 30th Information System, August Septem Computers and Printers 2017 ber 2017 2.2.2.6.1 Procure Xray Machines 888,889 Post Open- RFB Single No No 12 31 July National June 2017 2017 2.1.1.1.1 Procure Laptops for Regional 5352 Post Limited RFQ Single No No 31st 30th Field Epidemiology Training August Septem Program , 2017 ber 2017 2.2.2.4.1 Procure GeneXpert and 200,000 Post Limited RFB Single No No 31st 30th expand Xpert facilities August Septem 2017 ber 2017 Sub-Total 1,168,173 .00 Component 3: Learning, Knowledge and Innovation Packages for Consulting Services Activity Contract Description Estimate Review Market Selectio Shortlis Expected date of bid/ Expected No d Cost by Approach n ting proposal opening date of (US$) Bank (Open- Method (Yes/ Contract (Prior/P National/ (QCBS, No) Signature 6 ost) Internatio FBBS, nal LCBS, Limited QBS, etc.) CQS, DS etc.) 3.1.1.3.3 Consultant to conduct Baseline 108,410 Prior Open- DS Yes 28th February 2017 1st April Assessment for TB in Mines National 2017 3.1.1.4.3 Consultant to conduct E-Health 464409 Prior Open- DS Yes 8th March 2017 10th April for Community Intervention National 2017 3.1.31 IT Specialist - Consultant 36000 Post Open- DS Yes 11th May 2017 1st July National 2017 Sub-Total 608,819 7 Goods Activity Contract Description Estimate Review Market Selection Evaluatio Procureme Prequ Domes Expect Expecte No d Cost by Approach Method n Options nt Process: alifica tic ed d date (US$) Bank (Open- (RFP, (BAFO, (Single/Mul tion Prefere date of of (Prior/P National/ RFB, Rated tiple (Yes/ nce bid/ Contract ost) Internation RFQ, DS Criteria Stages; No) (Yes/N propos Signatur al Limited etc.) etc.) One/Two o) al e etc.) Envelopes openin etc) g 3.1.1.4.3 Procure E-Health for 125,000 Post Open- RFB Single No No 12 31 July Community Intervention National June 2017 Server, Computers, Networking 2017 and Tablets 3..3.43 Procure Geographical 4000 Post Limited RFQ Single No No Information System (GIS) Tool 3.4.1.1.1 Maintenance of Motor Vehicles 33,333 Post Limited RFQ Single No No 31st 30th 3 August Septem 2017 ber 2017 3.4.1.2.3 Purchase of Stationery 32,777 Post Limited RFQ Single No No 31st 30th August Septem 2017 ber 2017 3.4.1.2.1 Procurement of IT Equipment 105,000 Post Open- RFB Single No No 31st 30th (Video Conference National August Septem Facilities,Laptops and 2017 ber Communication 2017 Sub-Total 300,110 8 PROCUREMENT Eastern and Southern Africa : AFR RI-Southern Africa Tuberculosis and Health Systems Support Project PLAN General Information Country: Eastern and Southern Africa 2017-05-29 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P155658 GPN Date: Project Name: AFR RI-Southern Africa Tuberculosis and Health Systems Support Project Loan / Credit No: IDA / 58630, IDA / D1180 Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MZ-MISAU-15005-CW-RFB / Regional Capacity for Diseas Construction of two (2) clinic e Surveillance, and Diagnost Single Stage - One E 1,651,226.7 2018-08-2 al centers of excellence for T IDA / 58630 ics and Management of TB a Post Request for Bids Open - National 3,500,000.00 Signed 2017-11-01 2019-06-26 2017-11-06 2019-06-27 2017-12-18 2019-07-24 2018-01-17 2019-08-09 2018-02-21 2019-10-19 nvelope 9 0 B/MDR/XDR TB diagnosis, tre nd Occupational Lung Disea atment and management in ses North and Central Regions MZ-MISAU-15026-CW-RFB / Regional Capacity for Diseas Rehabilitation and Expand/U e Surveillance, and Diagnost Single Stage - One E 2018-08-2 IDA / 58630 Post Request for Bids Open - National 250,000.00 55,125.32 Signed 2017-11-01 2017-09-03 2017-11-06 2022-07-15 2017-12-18 2018-10-15 2018-01-17 2018-10-31 2018-02-21 2019-01-06 pgrade National Reference L ics and Management of TB a nvelope 0 aboratories and standardize nd Occupational Lung Disea LIS, add LPA capacity ses MZ-MISAU-56433-CW-RFB / Innovative Prevention, Detec Single Stage - One E 2020-04-1 Reabilitação dos Laboratórios IDA / 58630 Post Request for Bids Open - National 550,000.00 0.00 Signed 2018-06-22 2018-08-08 2018-06-27 2023-04-05 2018-08-08 2018-10-15 2018-09-07 2018-10-09 2018-10-12 tion and Treatment of TB nvelope 4 da Beira e de Nampula MZ-MISAU-68866-CW-RFB / Purchase and establish 42 un Innovative Prevention, Detec Single Stage - One E 2018-11-0 its of Pre Fabricated laborato IDA / 58630 Prior Request for Bids Open - National 5,000,000.00 0.00 Canceled 2018-07-16 2018-07-21 2018-09-01 2018-10-01 2018-11-05 tion and Treatment of TB nvelope 9 ries across the six(6) provinc es of the SATBHSS Project. MZ-MISAU-108372-CW-RFQ / Innovative Prevention, Detec Request for Quota Single Stage - One E 2019-12-1 Finance the reabilitation of s IDA / 58630 Post Limited 100,000.00 92,444.26 Signed 2019-04-20 2019-08-16 2019-06-15 2019-03-01 tion and Treatment of TB tions nvelope 2 urgical thoraxic service MZ-MISAU-15031-CW-RFB / Innovative Prevention, Detec Single Stage - One E 2018-07-2 Rehabilitate and establish sm IDA / 58630 Post Request for Bids Open - National 1,000,000.00 0.00 Canceled 2017-10-01 2017-10-06 2017-11-17 2017-12-17 2018-01-21 tion and Treatment of TB nvelope 0 ear microscopy points or con ditions for Xpert MZ-MISAU-68874-CW-RFB / Purchase and Establish Pre F Innovative Prevention, Detec Single Stage - One E 2019-05-1 abricated 56 TB consultation IDA / 58630 Post Request for Bids Open - National 3,650,000.00 0.00 Canceled 2018-07-23 2018-07-28 2018-09-08 2018-10-08 2018-11-12 tion and Treatment of TB nvelope 1 rooms across the six (6) prov inces of the SATBHSS Project . MZ-MISAU-81689-CW-RFB / Purchase and establish 42 un Innovative Prevention, Detec Single Stage - One E 2019-08-0 its of Pre Fabricated laborato IDA / 58630 Post Request for Bids Open - National 5,000,000.00 0.00 Canceled 2018-10-21 2018-10-26 2018-12-07 2019-01-06 2019-02-10 tion and Treatment of TB nvelope 9 ries across the six(6) provinc es of the SATBHSS Project. Regional Capacity for Diseas MZ-MISAU-14889-CW-RFQ / I e Surveillance, and Diagnost Request for Quota Single Stage - One E 2018-04-3 nfrastructure improvements f IDA / 58630 Post Limited 50,000.00 0.00 Canceled 2017-09-06 2017-11-01 ics and Management of TB a tions nvelope 0 or coordinating facility nd Occupational Lung Disea ses MZ-MISAU-14903-CW-RFB / I Regional Capacity for Diseas nfrastructure improvements e Surveillance, and Diagnost Single Stage - One E 2018-06-2 IDA / 58630 Post Request for Bids Open - National 195,000.00 0.00 Canceled 2017-09-01 2017-09-06 2017-10-18 2017-11-17 2017-12-22 at Provincial level to develop ics and Management of TB a nvelope 0 provincial services for occup nd Occupational Lung Disea ational health ses MZ-MISAU-60007-CW-RFB / Regional Capacity for Diseas Conduct Infrastructure impro e Surveillance, and Diagnost Request for Quota Single Stage - One E 2018-12-3 IDA / 58630 Post Open - National 195,000.00 0.00 Canceled 2018-05-08 2018-07-03 vements for Occupational He ics and Management of TB a tions nvelope 0 alth Services nd Occupational Lung Disea ses MZ-MISAU-68871-CW-RFQ / Acquisition and establisheme Innovative Prevention, Detec Single Stage - One E 2019-06-1 nt of container with all equip IDA / 58630 Post Request for Bids Open - National 350,000.00 0.00 Canceled 2018-08-27 2018-09-01 2018-10-13 2018-11-12 2018-12-17 tion and Treatment of TB nvelope 5 ment and small scale Refurbi shment of Ressano Garcia He alth Facility MZ-MISAU-15012-CW-RFB / Regional Capacity for Diseas Rehabilitation of 2 Meeting R e Surveillance, and Diagnost Single Stage - One E 2018-08-2 IDA / 58630 Post Request for Bids Open - National 120,000.00 0.00 Canceled 2017-11-01 2017-11-06 2017-12-18 2018-01-17 2018-02-21 ooms at MISAU - Central Lev ics and Management of TB a nvelope 0 el nd Occupational Lung Disea ses MZ-MISAU-56479-CW-RFP / Innovative Prevention, Detec Request for Quota Single Stage - One E 2018-10-3 Conduct Infrastructure impro IDA / 58630 Post Open - National 195,000.00 0.00 Canceled 2018-05-01 2018-06-29 tion and Treatment of TB tions nvelope 1 vements for Occupational He alth Services MZ-MISAU-15003-CW-RFB / Regional Capacity for Diseas Rehabilitation of one (1) clini e Surveillance, and Diagnost Single Stage - One E 2018-08-2 cal center of excellence for T IDA / 58630 ics and Management of TB a Post Request for Bids Open - National 4,500,000.00 0.00 Canceled 2017-11-01 2017-11-06 2017-12-18 2018-01-17 2018-02-21 nvelope 0 B/MDR/XDR TB diagnosis, tre nd Occupational Lung Disea atment and management in ses Maputo Province GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Regional Capacity for Diseas MZ-MISAU-14877-GO-RFQ / e Surveillance, and Diagnost Request for Quota Single Stage - One E Acquisition of 70 refrigerator IDA / 58630 Post Limited 56,000.00 0.00 Signed 2017-06-06 2017-09-22 2017-08-01 2018-01-28 ics and Management of TB a tions nvelope s nd Occupational Lung Disea ses MZ-MISAU-14895-GO-RFB / P Regional Capacity for Diseas urchase and Maintain Equip e Surveillance, and Diagnost Single Stage - One E IDA / 58630 Post Request for Bids Open - National 200,000.00 480,187.02 Signed 2017-08-01 2019-09-06 2017-08-06 2017-09-17 2019-11-25 2017-10-17 2020-03-30 2017-11-21 2020-03-30 2018-05-20 ment for mine health inspecti ics and Management of TB a nvelope on nd Occupational Lung Disea ses Page 1 MZ-MISAU-14906-GO-RFB / A Regional Capacity for Diseas cquisition of 6 Digital X-ray fo e Surveillance, and Diagnost Single Stage - One E IDA / 58630 Prior Request for Bids Open - National 640,000.00 0.00 Canceled 2017-09-01 2017-09-06 2017-10-18 2017-11-17 2018-05-23 2017-12-22 2018-06-20 r each Provincial Occupation ics and Management of TB a nvelope al Health Center and 2 additi nd Occupational Lung Disea onal for TB screening ses MZ-MISAU-14911-GO-RFB / A cquisition of 10 Spirometry, A cquisition of 9 Audiometry, A cquisition of 9 EKG machine Innovative Prevention, Detec Single Stage - One E IDA / 58630 Post Request for Bids Open - National 226,000.00 0.00 Signed 2017-09-01 2018-03-06 2017-09-06 2017-10-18 2018-04-04 2017-11-17 2018-04-17 2017-12-22 2018-06-20 and acquisition of 50 LED Mic tion and Treatment of TB nvelope roscopes, 45 Tablets for inter vention at the District level, office equipment for Central and Provincial Level (Table C omputers, print MZ-MISAU-14920-GO-RFB / 4 Regional Capacity for Diseas 5 Tablets for intervention at t e Surveillance, and Diagnost he District level and office eq Single Stage - One E IDA / 58630 ics and Management of TB a Post Request for Bids Open - National 786,000.00 0.00 Signed 2017-08-01 2018-03-16 2017-08-06 2023-04-10 2017-09-17 2018-06-22 2017-10-17 2018-08-15 2017-11-21 2018-05-20 uipment for Central and Provi nvelope nd Occupational Lung Disea ncial Level (Table Computer ses s, printers and photocopy ma chines) MZ-MISAU-14998-GO-RFQ / Innovative Prevention, Detec Request for Quota Single Stage - One E Under Imple IDA / 58630 Post Open - National 15,000.00 0.00 2017-06-06 2022-11-10 2017-08-01 2018-01-28 Printing of TB Manual tion and Treatment of TB tions nvelope mentation MZ-MISAU-15007-GO-RFB / E Regional Capacity for Diseas quipment for 3 clinical center e Surveillance, and Diagnost Single Stage - One E IDA / 58630 Post Request for Bids Open - National 500,000.00 0.00 Signed 2017-11-01 2020-10-16 2017-11-06 2020-10-16 2017-12-18 2020-11-11 2018-01-17 2020-12-17 2018-02-21 2018-08-20 s of excellence for TB/MDR/X ics and Management of TB a nvelope DR TB diagnosis, treatment a nd Occupational Lung Disea nd management ses MZ-MISAU-14879-GO-RFB / 7 Regional Capacity for Diseas 2 - Motorcycles for CHWs in t e Surveillance, and Diagnost Single Stage - One E IDA / 58630 Post Request for Bids Open - National 432,000.00 0.00 Signed 2017-07-07 2017-08-21 2017-07-12 2022-11-10 2017-08-23 2017-09-27 2017-09-22 2017-11-22 2017-10-27 2018-04-25 he Districts and coolers to tra ics and Management of TB a nvelope nsport samples nd Occupational Lung Disea ses MZ-MISAU-39021-GO-UN / A quisição de 9 viaturas do Tip o mini bus para as Direcções Regional Learning and Innov Provinciais de Saúde que são UN Agencies (Dire IDA / 58630 ation, and Project Managem Post Direct 600,000.00 0.00 Signed 2017-12-04 2017-12-05 2017-12-12 2017-12-31 parte do projecto e para o Ní ct) ent vel central, e 6 viaturas pick up 4 x 4 para os Ministérios d a Saúde, Recursos Minerais e Energia e Ministério do Traba lho MZ-MISAU-56371-GO-RFB / I Innovative Prevention, Detec Single Stage - One E nfrastruture Improvement of IDA / 58630 Post Request for Bids Open - National 250,000.00 656,347.67 Signed 2018-04-13 2018-09-01 2018-04-18 2018-05-30 2018-09-15 2018-07-05 2018-11-13 2018-08-16 2018-12-01 2019-02-28 tion and Treatment of TB nvelope Ressano Garcia HF. MZ-MISAU-60118-GO-RFB / E cho System for each provinc Innovative Prevention, Detec Single Stage - One E IDA / 58630 Post Request for Bids Open - National 175,000.00 0.00 Signed 2018-05-04 2018-07-10 2018-05-09 2023-03-31 2018-06-20 2018-08-27 2018-07-20 2019-01-30 2018-08-24 2018-11-09 e including MISAU /- fixed vid tion and Treatment of TB nvelope eo conference system.(10 Un its) MZ-MISAU-64073-GO-RFB / A quisição de 6 Raios-X Digitais Innovative Prevention, Detec Open - Internationa Single Stage - One E para cada Centro Provincial d IDA / 58630 Prior Request for Bids 1,750,000.00 0.00 Canceled 2018-05-28 2018-06-02 2018-07-14 2018-06-25 2018-08-13 2018-09-17 2019-03-16 tion and Treatment of TB l nvelope e Saúde Ocupacional e 2 adic ionais para triagem de TB MZ-MISAU-108373-GO-RFB / Regional Capacity for Diseas Finance the Purchase of addi e Surveillance, and Diagnost Single Stage - One E IDA / 58630 Post Request for Bids Open - National 320,000.00 370,494.49 Signed 2019-04-29 2021-06-09 2019-05-04 2019-06-28 2019-06-15 2021-07-09 2019-07-15 2021-08-25 2019-08-19 2022-03-30 2020-02-15 tional equipment for mine he ics and Management of TB a nvelope alth inspection (MITESS) nd Occupational Lung Disea ses MZ-MISAU-108380-GO-RFB / Innovative Prevention, Detec Single Stage - One E IDA / 58630 Post Request for Bids Open - National 600,000.00 0.00 Canceled 2019-04-30 2019-05-05 2019-06-16 2019-07-16 2019-08-20 2020-02-16 Acquisition of 6 Xray machin tion and Treatment of TB nvelope es MZ-MISAU-108381-GO-RFB / Innovative Prevention, Detec Single Stage - One E IDA / 58630 Post Request for Bids Open - National 875,000.00 197,185.02 Signed 2019-04-22 2017-09-15 2019-04-27 2022-07-15 2019-06-08 2017-10-06 2019-07-08 2018-02-01 2019-08-12 2018-12-01 2020-02-08 Acquisition of 25 GeneXperts tion and Treatment of TB nvelope (25 units) MZ-MISAU-146852-GO-RFB / ACQUISITION OF MATERIAL F Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 58630 Post Limited 33,000.00 96,410.66 Signed 2020-02-21 2021-05-21 2020-04-17 2021-08-02 2020-10-14 OR INDUCING EXPECTORATI tion and Treatment of TB tions nvelope ON AND GASTRIC WASHING MZ-MISAU-68843-GO-RFB / A Regional Capacity for Diseas quisição de 6 Raios-X Digitais e Surveillance, and Diagnost Open - Internationa Single Stage - One E para cada Centro Provincial d IDA / 58630 ics and Management of TB a Prior Request for Bids 1,750,000.00 0.00 Canceled 2018-07-16 2018-08-15 2018-07-21 2018-08-30 2018-08-16 2018-11-12 2018-08-23 2018-09-28 2018-10-15 l nvelope e Saúde Ocupacional e 2 adic nd Occupational Lung Disea ionais para triagem de TB ses MZ-MISAU-146851-GO-UN / Acquisition of XPERT MTB / RI Innovative Prevention, Detec UN Agencies (Dire IDA / 58630 Prior Direct 3,200,000.00 3,182,207.09 Signed 2020-02-23 2020-05-05 2020-02-28 2020-05-18 2020-04-03 2020-06-05 2020-09-30 F Cartridges, for diagnosis of tion and Treatment of TB ct) Tuberculosis at UNOPS / GDF MZ-MISAU-170882-GO-UN / Regional Capacity for Diseas COVID-19 Emergency Procur e Surveillance, and Diagnost UN Agencies (Dire IDA / D1180 Post Direct 1,000,000.00 612,417.97 Signed 2020-04-30 2020-05-13 2020-05-05 2020-05-14 2020-06-09 2020-07-04 2020-12-06 ement for MoH-INS Mozambi ics and Management of TB a ct) que Lab Reagents & Equipme nd Occupational Lung Disea nt WB ses MZ-MISAU-185691-GO-RFQ / Acquisition of Swabes in the Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 58630 Post Limited 227,445.00 221,510.30 Signed 2020-07-31 2020-06-11 2020-09-25 2020-08-15 2020-09-30 scope of the emergency - CO tion and Treatment of TB tions nvelope VID19 - 50,000 units MZ-MISAU-229809-GO-DIR / Direct contracting with a Unit Innovative Prevention, Detec IDA / 58630 Post Direct Selection Direct 1,260,000.00 0.00 Signed 2021-04-20 2021-08-20 2021-04-25 2021-08-19 2021-05-30 2021-11-26 ed Nations agency to supply tion and Treatment of TB the expert gene equipment Regional Capacity for Diseas MZ-MISAU-15022-GO-RFB / 1 e Surveillance, and Diagnost Single Stage - One E - Digital CXR machine and CA IDA / 58630 Post Request for Bids Open - National 80,000.00 0.00 Canceled 2018-03-01 2018-03-06 2018-04-17 2018-05-17 2018-06-21 2018-12-18 ics and Management of TB a nvelope D4TB nd Occupational Lung Disea ses Regional Capacity for Diseas MZ-MISAU-15019-GO-RFB / 3 e Surveillance, and Diagnost Single Stage - One E IDA / 58630 Post Request for Bids Open - National 195,000.00 0.00 Canceled 2017-11-01 2017-11-06 2017-12-18 2018-01-17 2018-02-21 2018-08-20 - 4x4 Ambulance ics and Management of TB a nvelope nd Occupational Lung Disea ses MZ-MISAU-14926-GO-RFB / P Regional Capacity for Diseas rinting material and guideline e Surveillance, and Diagnost Request for Quota Single Stage - One E IDA / 58630 Post Limited 65,000.00 0.00 Canceled 2017-08-01 2022-03-18 2017-08-06 2017-09-17 2017-10-17 2017-11-21 2018-05-20 s for TB, MDR-TB, TB/HIV and ics and Management of TB a tions nvelope infection control practices to nd Occupational Lung Disea all health facilities ses Page 2 MZ-MISAU-108889-GO-UN / Goods and Medicines:Procure ment of medical supplies,Pro curement of IV fluids,Establis Innovative Prevention, Detec UN Agencies (Dire h a temporal ward at Beira H IDA / 58630 Post Direct 500,000.00 0.00 Canceled 2019-04-12 2019-05-04 2019-04-17 2019-05-04 2019-05-22 2019-11-18 tion and Treatment of TB ct) ospital and Prevention & Tre atment of Diarrhea. To healt h emergency response to mit igate the immediate impacts of Cyclone Idai MZ-MISAU-229883-GO-DIR / Acquisition of 6 digital X-rays Innovative Prevention, Detec for each Provincial Occupatio IDA / 58630 Post Direct Selection Direct 1,750,000.00 0.00 Canceled 2021-04-22 2021-04-27 2021-06-01 2021-11-28 tion and Treatment of TB nal Health Center and 2 addit ional ones for TB screening a nd dosimeters MZ-MISAU-108375-GO-RFQ / Innovative Prevention, Detec Request for Quota Single Stage - One E Finance the purchase of equi IDA / 58630 Post Limited 90,000.00 0.00 Canceled 2019-04-22 2019-06-17 2019-12-14 tion and Treatment of TB tions nvelope pment for Occupacional Heal th Centers (6) Regional Capacity for Diseas MZ-MISAU-60112-GO-RFQ / e Surveillance, and Diagnost Request for Quota Single Stage - One E IDA / 58630 Post Limited 75,000.00 0.00 Canceled 2018-05-05 2018-06-30 2018-08-31 Office Furniture ics and Management of TB a tions nvelope nd Occupational Lung Disea ses MZ-MISAU-108376-GO-RFQ / Financing the acquistion of p Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 58630 Post Limited 15,000.00 0.00 Canceled 2019-04-27 2019-06-22 2019-12-19 ortable laboratory for the dia tion and Treatment of TB tions nvelope gnosis od occupational disea ses MZ-MISAU-108398-GO-RFQ / Innovative Prevention, Detec Request for Quota Single Stage - One E Purchazing of Suplementary IDA / 58630 Post Limited 33,000.00 0.00 Canceled 2019-05-04 2019-06-29 2019-12-26 tion and Treatment of TB tions nvelope Laboratory Equipments MZ-MISAU-229814-GO-DIR / Acquisition of XPERT MTB / RI Innovative Prevention, Detec IDA / 58630 Prior Direct Selection Direct 3,750,000.00 0.00 Canceled 2021-04-20 2021-04-25 2021-05-30 2021-11-26 F Cartridges, for diagnosis of tion and Treatment of TB Tuberculosis at UNOPS / GDF MZ-MISAU-109884-GO-RFQ / 2.3.2.1 - Purchase of addition al Equipments for the Refere Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 58630 Post Limited 64,000.00 0.00 Canceled 2019-04-27 2019-06-22 2019-12-19 nce TB Laboratories and Purc tion and Treatment of TB tions nvelope hase portable laboratory kits for the diagnosis of occupatio nal diseases Regional Capacity for Diseas MZ-MISAU-14873-GO-RFQ / e Surveillance, and Diagnost Request for Quota Single Stage - One E Acquisition of 120 transport c IDA / 58630 Post Limited 3,600.00 0.00 Canceled 2017-06-06 2017-08-01 2018-01-28 ics and Management of TB a tions nvelope oolers nd Occupational Lung Disea ses Regional Capacity for Diseas MZ-MISAU-15000-GO-RFQ / e Surveillance, and Diagnost Request for Quota Single Stage - One E Office material and equipme IDA / 58630 Post Limited 20,000.00 0.00 Canceled 2017-06-06 2017-08-01 2018-01-28 ics and Management of TB a tions nvelope nt for TB Prevalence Survey nd Occupational Lung Disea ses MZ-MISAU-15041-GO-DIR / T Innovative Prevention, Detec IDA / 58630 Post Direct Selection Direct 10,500.00 0.00 Canceled 2017-09-01 2021-03-11 2017-09-06 2017-10-11 2018-04-09 V Spots with Miramar tion and Treatment of TB MZ-MISAU-160703-GO-UN / Acquisition of 6 digital X-rays Innovative Prevention, Detec UN Agencies (Dire for each Provincial Occupatio IDA / 58630 Prior Direct 1,750,000.00 0.00 Canceled 2020-02-20 2020-02-25 2020-03-31 2020-09-27 tion and Treatment of TB ct) nal Health Center and 2 addit ional ones for TB screening Regional Capacity for Diseas MZ-MISAU-15016-GO-RFB / E e Surveillance, and Diagnost Single Stage - One E quipment for the 2 Meeting R IDA / 58630 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2017-11-01 2017-11-06 2017-12-18 2018-01-17 2018-02-21 2018-08-20 ics and Management of TB a nvelope ooms at MISAU nd Occupational Lung Disea ses MZ-MISAU-14885-GO-RFB / 2 Regional Capacity for Diseas - Vehicle with Chest-XR, Xper e Surveillance, and Diagnost Single Stage - One E IDA / 58630 Post Request for Bids Open - National 500,000.00 0.00 Canceled 2017-09-01 2017-09-06 2017-10-18 2017-11-17 2017-12-22 2018-06-20 t, mobile lab and HIV testing ics and Management of TB a nvelope - quote from Delft and Preval nd Occupational Lung Disea ence Survey ses MZ-MISAU-15050-GO-DIR / T Innovative Prevention, Detec IDA / 58630 Post Direct Selection Direct 10,500.00 0.00 Canceled 2017-11-01 2017-11-06 2017-12-11 2018-06-09 V Dessimination with STV tion and Treatment of TB MZ-MISAU-15037-GO-DIR / T Innovative Prevention, Detec IDA / 58630 Post Direct Selection Direct 10,500.00 0.00 Canceled 2017-09-01 2017-09-06 2017-10-11 2018-04-09 V Spots with TVM tion and Treatment of TB MZ-MISAU-39417-GO-RFP / F Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 58630 Post Open - National 200,000.00 0.00 Canceled 2017-12-11 2018-02-05 2018-02-13 ield material for TB Prevalenc tion and Treatment of TB tions nvelope e Survey MZ-MISAU-60000-GO-RFQ / Regional Capacity for Diseas Purchase and maintain equip e Surveillance, and Diagnost Single Stage - One E IDA / 58630 Post Request for Bids Open - National 240,000.00 0.00 Canceled 2018-06-08 2018-06-13 2018-07-25 2018-08-24 2018-09-28 2019-03-27 ment for mine health inspecti ics and Management of TB a nvelope on (Incl. maintanance of prev nd Occupational Lung Disea ious aquired material) ses MZ-MISAU-75776-GO-DIR / c quisition and establishment o Innovative Prevention, Detec f container with all equipmen IDA / 58630 Post Direct Selection Direct 350,000.00 0.00 Canceled 2018-08-29 2018-09-03 2018-10-22 2019-04-20 tion and Treatment of TB t and small scale. Remodelin g of the Ressano Garcia Heal th Center MZ-MISAU-14997-GO-RFQ / Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 58630 Post Open - National 15,000.00 0.00 Canceled 2017-06-06 2017-08-01 2018-01-28 Printing of Manual for Asthm tion and Treatment of TB tions nvelope a MZ-MISAU-146853-GO-RFB / Innovative Prevention, Detec Request for Quota Single Stage - One E 2.3.1.2- Acquisition of sputu IDA / 58630 Post Limited 70,000.00 0.00 Canceled 2020-02-22 2020-04-18 2020-06-14 tion and Treatment of TB tions nvelope m induction kits MZ-MISAU-108377-GO-RFB / Regional Capacity for Diseas 1.2.1.1 - Finance the Purchas e Surveillance, and Diagnost Single Stage - One E IDA / 58630 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2019-04-29 2019-09-13 2019-05-04 2019-09-13 2019-06-15 2019-07-15 2019-08-19 2020-02-15 e of additional equipment for ics and Management of TB a nvelope mine health inspection (MIRE nd Occupational Lung Disea M) ses MZ-MISAU-109883-GO-RFQ / Purchase additional diagnosti Innovative Prevention, Detec Request for Quota Single Stage - One E c equipment: Acquisition of 1 IDA / 58630 Post Limited 90,000.00 0.00 Canceled 2019-04-27 2019-06-22 2019-12-19 tion and Treatment of TB tions nvelope 0 Audiometers,Acquisition  of 10 Spirometers and Acquisiti on of 10 EKGs Page 3 MZ-MISAU-108395-GO-RFB / Innovative Prevention, Detec Single Stage - One E Purchase of Clinic Medical Eq IDA / 58630 Post Request for Bids Open - National 600,000.00 0.00 Canceled 2019-06-10 2019-06-15 2019-07-27 2019-08-26 2019-09-30 2020-03-28 tion and Treatment of TB nvelope uipment to Centers of excele nce MZ-MISAU-15029-GO-RFB / 2 Regional Capacity for Diseas 0-Xpert Machines to Expand e Surveillance, and Diagnost National Diagnostic Capacity Single Stage - One E IDA / 58630 ics and Management of TB a Post Request for Bids Open - National 772,000.00 0.00 Canceled 2017-09-01 2017-09-06 2017-10-18 2017-11-17 2018-01-05 2017-12-22 2018-06-20 (smear, Xpert, culture), 30 o nvelope nd Occupational Lung Disea mnis Machine, Acquisition of ses Equipment (Dongels for Xper t computers) MZ-MISAU-60094-GO-RFB / 2 5 laptops with their respectiv Regional Capacity for Diseas e offices and antivirus,6 proj e Surveillance, and Diagnost Single Stage - One E ectors,55 desktop computers IDA / 58630 ics and Management of TB a Post Request for Bids Open - National 500,000.00 0.00 Canceled 2018-04-30 2018-05-05 2018-06-16 2018-07-02 2018-07-23 2018-09-03 nvelope and their respective UPS, Offi nd Occupational Lung Disea ce and antivirus packages,25 ses External Hard Drives and 10 I mpressoras MZ-MISAU-14882-GO-RFB / 6 Regional Capacity for Diseas - Vehicle for mobile teams in e Surveillance, and Diagnost each of 6 priority provinces a Single Stage - One E IDA / 58630 ics and Management of TB a Post Request for Bids Open - National 550,000.00 0.00 Canceled 2017-08-10 2017-08-15 2017-09-26 2017-10-26 2017-11-30 2018-05-29 nd 5 - 4x4 Vehicle for: 1 MITE nvelope nd Occupational Lung Disea SS, 1 MIREM,1 DNSP, 1 vehicl ses e for PIU And 1- Vehicle for D NAM National Team NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-MISAU-59663-NC-RFQ / R Innovative Prevention, Detec Request for Quota Single Stage - One E eproduction of 600 copies of IDA / 58630 Post Limited 3,500.00 3,522.78 Signed 2018-04-27 2018-03-07 2018-05-23 2018-11-01 2018-05-31 tion and Treatment of TB tions nvelope the manual of Cholera MZ-MISAU-229806-NC-DIR / i Innovative Prevention, Detec ntegration of Gaza OHC into IDA / 58630 Post Direct Selection Direct 740,000.00 736,119.00 Signed 2021-04-19 2021-06-13 2021-04-20 2021-06-13 2021-04-28 2021-06-22 2021-12-31 tion and Treatment of TB occupational health project MZ-MISAU-229825-NC-DIR / Innovative Prevention, Detec Direct hiring of ADPP to conti IDA / 58630 Post Direct Selection Direct 600,000.00 0.00 Signed 2021-06-01 2020-02-18 2021-06-06 2020-05-11 2021-07-11 2022-01-07 tion and Treatment of TB nue the active search in Gaz a in other Districts MZ-MISAU-234229-NC-DIR / Innovative Prevention, Detec IDA / 58630 Post Direct Selection Direct 301,125.00 301,125.00 Signed 2021-07-11 2021-07-04 2021-07-16 2021-07-09 2021-08-20 2021-08-25 2022-01-12 TB - Drug Resistance Survey tion and Treatment of TB MZ-MISAU-55306-NC-RFQ / P Innovative Prevention, Detec Request for Quota Single Stage - One E roduction of the advertising s IDA / 58630 Post Limited 8,500.00 0.00 Canceled 2018-03-28 2018-04-16 2018-04-23 tion and Treatment of TB tions nvelope pot for the Tuberculosis Prev alence Study MZ-MISAU-39651-NC-RFQ / C Regional Learning and Innov ontract a publicity or market Request for Quota Single Stage - One E IDA / 58630 ation, and Project Managem Post Open - National 15,000.00 0.00 Canceled 2017-12-11 2018-02-05 2018-08-04 or advogacy firm to lead ann tions nvelope ent ual marketing budget MZ-MISAU-189513-NC-DIR / I nterventions to search for los t cases of tuberculosis (TB) a Innovative Prevention, Detec IDA / 58630 Post Direct Selection Direct 268,000.00 0.00 Canceled 2020-09-01 2020-09-02 2020-09-06 2020-09-02 2020-10-11 2021-04-09 t the level of high-risk popula tion and Treatment of TB tion groups and the general population - Is this new contr act? MZ-MISAU-146855-NC-RFQ / Hiring a company to install a Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 58630 Post Limited 15,000.00 0.00 Canceled 2020-02-21 2020-04-17 2020-07-26 nd maintain the DISA system tion and Treatment of TB tions nvelope at the tuberculosis reference laboratory in Beira. MZ-MISAU-90096-NC-RFP / F or the implementation of the Innovative Prevention, Detec Request for Propo Single Stage - One E community screening of Tub IDA / 58630 Post Open - National 300,000.00 0.00 Canceled 2018-12-14 2019-06-21 2018-12-19 2019-07-11 2019-01-16 2019-02-04 2019-03-11 2019-09-07 tion and Treatment of TB sals nvelope erculosis in Tete. Because th ere is currently no TB commu nity activities MZ-MISAU-88922-NC-RFP / F or the implementation of the Innovative Prevention, Detec Request for Propo Single Stage - Two E community screening of Tub IDA / 58630 Post Open - National 300,000.00 0.00 Canceled 2018-12-13 2019-06-21 2018-12-18 2019-07-11 2019-01-14 2019-03-27 2019-05-01 2019-10-28 tion and Treatment of TB sals nvelope erculosis in Zambézia. Becau se there is currently no TB co mmunity activities MZ-MISAU-55296-NC-DIR / In sertion of advertising spots o Innovative Prevention, Detec Request for Quota Single Stage - One E IDA / 58630 Post Limited 60,000.00 0.00 Canceled 2018-04-03 2018-05-10 2018-11-15 f the study of the prevalence tion and Treatment of TB tions nvelope of Tuberculosis in televisions and radios MZ-MISAU-56402-NC-RFP / Pi Innovative Prevention, Detec Request for Quota Single Stage - One E lot and scale up-of innovative IDA / 58630 Post Open - National 100,000.00 0.00 Canceled 2018-04-30 2018-06-25 2018-10-31 tion and Treatment of TB tions nvelope sputum sample transport sys tems MZ-MISAU-56389-NC-RFP / M Innovative Prevention, Detec Single Stage - One E ass publicity campaign for TB IDA / 58630 Post Request for Bids Open - National 176,600.00 0.00 Canceled 2018-04-19 2018-04-24 2018-06-05 2018-07-05 2018-08-09 2019-02-05 tion and Treatment of TB nvelope screening MZ-MISAU-60203-NC-DIR / tr Regional Learning and Innov IDA / 58630 Post Direct Selection Direct 10,000.00 0.00 Canceled 2018-04-27 2018-05-02 2018-06-06 2019-03-31 anslation services of docume ation, and Project Managem nts ent MZ-MISAU-109881-NC-RFB / Innovative Prevention, Detec Single Stage - One E IDA / 58630 Post Request for Bids Open - National 250,000.00 0.00 Canceled 2019-04-29 2019-05-04 2019-06-15 2019-07-15 2019-08-19 2020-01-17 Mapping of fomer miner geos tion and Treatment of TB nvelope patially MZ-MISAU-359105-CS-CDS / Innovative Prevention, Detec Under Revie Health Promotion and Assista IDA / 58630 Prior Direct Selection Direct - National 2,020,000.00 0.00 2023-06-11 2023-06-27 2023-06-16 2023-06-23 2023-12-20 tion and Treatment of TB w nce for Migrants (MA) MZ-MISAU-366143-NC-RFQ / Regional Learning and Innov Request for Quota Single Stage - One E Pending Impl IDA / 58630 Post Limited 91,000.00 0.00 2023-06-26 2023-08-21 2024-02-17 Hiring services for an interne ation, and Project Managem tions nvelope ementation t system ent CONSULTING FIRMS Page 4 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-MISAU-15040-CS-QCBS / Regional Capacity for Diseas Consulting services for desig e Surveillance, and Diagnost Quality And Cost- Open - Internationa n and supervision of construc IDA / 58630 ics and Management of TB a Post 175,000.00 533,490.61 Signed 2017-08-21 2018-09-08 2017-09-11 2017-12-01 2017-10-25 2018-08-23 2017-11-22 2018-08-23 2017-12-22 2018-08-21 2018-01-26 2018-08-23 2018-03-02 2018-09-28 2019-03-02 Based Selection l tion of one (1) center of exce nd Occupational Lung Disea llence in the Central region ses MZ-MISAU-39689-CS-CQS / B Regional Capacity for Diseas aseline Assessment for the e Surveillance, and Diagnost Consultant Qualifi Southern Africa Tuberculosis IDA / 58630 ics and Management of TB a Post Open - National 250,000.00 0.00 Signed 2017-12-07 2017-05-15 2017-12-28 2023-03-27 2018-02-10 2017-12-06 2018-03-12 2018-02-12 2018-04-16 2018-10-13 cation Selection and Health Systems Support nd Occupational Lung Disea Project ses Mozambique MZ-MISAU-146854-CS-QBS / Regional Capacity for Diseas Hiring a company to map the e Surveillance, and Diagnost Quality Based Sel IDA / 58630 Post Open - National 70,000.00 0.00 Under Review 2020-02-16 2019-04-09 2020-03-08 2023-04-04 2020-04-21 2020-05-19 2020-06-18 2020-07-18 2020-08-22 2020-09-27 main risk factors of the main ics and Management of TB a ection companies in Mozambique nd Occupational Lung Disea ses MZ-MISAU-161079-NC-UN / Innovative Prevention, Detec UN Agencies (Dire Health Promotion and Assista IDA / 58630 Prior Direct 1,463,265.00 2,516,808.00 Signed 2020-04-17 2020-05-26 2021-02-28 tion and Treatment of TB ct) nce for Migrants (MA) MZ-MISAU-15013-CS-QCBS / Specific Operational research Regional Learning and Innov Quality And Cost- Open - Internationa consistent with NTP Strategic IDA / 58630 ation, and Project Managem Prior 2,000,000.00 0.00 Canceled 2018-03-30 2018-04-20 2018-06-03 2018-07-01 2018-07-31 2018-09-04 2018-10-09 2019-10-09 Based Selection l Plan, Occupational Health an ent d Environmental Health Strat egic Plans MZ-MISAU-229884-NC-RFP / Interventions to search for lo st cases of tuberculosis (TB) Innovative Prevention, Detec Quality Based Sel IDA / 58630 Post Open - National 600,000.00 0.00 Canceled 2021-04-25 2021-05-16 2021-06-29 2021-07-27 2021-08-26 2021-09-25 2021-10-30 2022-10-30 at the level of high-risk popul tion and Treatment of TB ection ation groups and the general population in Some Districts i n Zambézia MZ-MISAU-229885-CS-QBS / Interventions to search for lo st cases of tuberculosis (TB) Innovative Prevention, Detec Quality Based Sel IDA / 58630 Post Open - National 600,000.00 0.00 Canceled 2021-04-25 2021-05-16 2021-06-29 2021-07-27 2021-08-26 2021-09-25 2021-10-30 2022-10-30 at the level of high-risk popul tion and Treatment of TB ection ation groups and the general population in Some Districts i n TETE MZ-MISAU-108987-CS-CQS / Finance the hiring of an IT Co Innovative Prevention, Detec Consultant Qualifi IDA / 58630 Post Open - National 60,000.00 0.00 Canceled 2019-04-15 2019-05-06 2019-06-19 2019-07-19 2019-08-23 2020-02-19 nsolting Firm to develop and tion and Treatment of TB cation Selection build capacit on the use of el ectronic devices MZ-MISAU-14927-CS-QCBS / Community based organizati Innovative Prevention, Detec Quality And Cost- Open - Internationa on to hire incentive communi IDA / 58630 Post 800,000.00 0.00 Canceled 2017-09-30 2017-10-21 2017-12-04 2018-01-01 2018-01-31 2018-03-07 2018-04-11 2019-04-11 tion and Treatment of TB Based Selection l ty members to execute integ rated TB/HIV Screening MZ-MISAU-15023-CS-CQS / C Regional Capacity for Diseas ontract a Firm to conduct ser e Surveillance, and Diagnost vice readiness assessment of Consultant Qualifi Open - Internationa IDA / 58630 ics and Management of TB a Post 60,000.00 0.00 Canceled 2017-09-18 2017-10-09 2017-11-22 2017-12-22 2018-01-26 2018-07-25 key TB sites in southen priori cation Selection l nd Occupational Lung Disea ty intervention sites to identif ses y infrastructure and other ne eds MZ-MISAU-15014-CS-CQS / F Regional Capacity for Diseas irm to develop a Protocol-In- e Surveillance, and Diagnost Consultant Qualifi Open - Internationa IDA / 58630 Post 90,000.00 0.00 Canceled 2017-08-21 2017-08-21 2017-08-21 2017-08-21 2017-09-11 2018-03-10 depth epidemiological analys ics and Management of TB a cation Selection l is nd Occupational Lung Disea ses MZ-MISAU-14884-CS-CQS / F Regional Capacity for Diseas irm to develop-upgrade elect e Surveillance, and Diagnost Consultant Qualifi Open - Internationa ronic IT Systems for complian IDA / 58630 ics and Management of TB a Post 135,000.00 0.00 Canceled 2018-03-01 2018-03-22 2018-05-05 2018-06-04 2018-07-09 2019-01-05 cation Selection l ce monitoring and mine healt nd Occupational Lung Disea h surveillance (at regulatory ses level MZ-MISAU-14888-CS-CQS / C Regional Capacity for Diseas ontract with IT Consultant Co e Surveillance, and Diagnost Consultant Qualifi Open - Internationa IDA / 58630 Post 40,000.00 0.00 Canceled 2017-09-15 2017-10-06 2017-11-19 2017-12-19 2018-01-23 2018-07-22 mpany (maintenance of data ics and Management of TB a cation Selection l base,) nd Occupational Lung Disea ses MZ-MISAU-15047-CS-CQS / C Regional Capacity for Diseas onsultant to develop a web/cl e Surveillance, and Diagnost Consultant Qualifi Open - Internationa oud based database/EMR to t IDA / 58630 ics and Management of TB a Post 175,000.00 0.00 Canceled 2017-08-01 2017-08-22 2017-10-05 2017-11-04 2017-12-09 2018-06-07 cation Selection l rack all DRTB patients (and e nd Occupational Lung Disea ventually expand to all TB) ses MZ-MISAU-15030-CS-CQS / C Regional Capacity for Diseas ontract a team to read, recor e Surveillance, and Diagnost Consultant Qualifi Open - Internationa d and monitor all digital Xray IDA / 58630 ics and Management of TB a Post 126,000.00 0.00 Canceled 2018-03-30 2018-04-20 2018-06-03 2018-07-03 2018-08-07 2019-02-03 cation Selection l s for all miners and ex-miner nd Occupational Lung Disea s and stablish data base on ses occupational lung disease MZ-MISAU-39416-CS-CQS / N Regional Capacity for Diseas GO to execute a pilot to do in e Surveillance, and Diagnost Consultant Qualifi tensifield case finding, diagn IDA / 58630 ics and Management of TB a Post Open - National 200,000.00 0.00 Canceled 2017-12-08 2017-12-29 2018-02-11 2018-03-13 2018-04-17 2018-10-14 cation Selection ose migrant miners with TB, nd Occupational Lung Disea HIV and to continue treatme ses nt MZ-MISAU-108390-CS-CQS / Financing the operational res Innovative Prevention, Detec Consultant Qualifi earch consistent with NTP Str IDA / 58630 Post Open - National 150,000.00 0.00 Canceled 2019-05-02 2019-05-23 2019-07-06 2019-08-05 2019-09-09 2020-03-07 tion and Treatment of TB cation Selection ategic Plan, Occupational He alth and Environmental Healt h Strategic Plan MZ-MISAU-15010-CS-CQS / C Innovative Prevention, Detec Consultant Qualifi Open - Internationa ontract a mHealth company IDA / 58630 Post 150,000.00 0.00 Canceled 2018-03-30 2018-04-20 2018-06-03 2018-07-03 2018-08-07 2019-02-03 tion and Treatment of TB cation Selection l which will include training of HCWs MZ-MISAU-39898-CS-CQS / C BOS/NGOs to conduct the Pil Innovative Prevention, Detec Consultant Qualifi IDA / 58630 Post Open - National 200,000.00 0.00 Canceled 2017-12-11 2018-01-01 2018-02-14 2018-03-16 2018-04-20 2018-10-17 ot of DOT-PLUS in MAPUTO a tion and Treatment of TB cation Selection nd Gaza Provinces Page 5 MZ-MISAU-39899-CS-CQS / C BOS7NGOS to conduct the Pil Innovative Prevention, Detec Consultant Qualifi IDA / 58630 Post Open - National 200,000.00 0.00 Canceled 2017-12-11 2018-01-01 2018-02-14 2018-03-16 2018-04-20 2018-10-17 ot of DOT-PLUS in Maputo an tion and Treatment of TB cation Selection d Gaza Provinces MZ-MISAU-60201-CS-QBS / C onsultancy for analysis of Epi demiological Profile of Tuber Innovative Prevention, Detec Consultant Qualifi culosis in populations of min IDA / 58630 Post Open - National 90,000.00 0.00 Canceled 2018-04-30 2018-05-21 2018-07-04 2018-08-03 2018-09-07 2019-03-06 tion and Treatment of TB cation Selection ers in Mozambique, Populatio ns of Miners in the Provinces of Manica, Tete, Zambezia an d Cabo Delgado, 2015- 2016 MZ-MISAU-15017-CS-QCBS / Innovative Prevention, Detec Quality And Cost- Open - Internationa Study of catastrophic cost for IDA / 58630 Post 200,000.00 0.00 Canceled 2017-09-20 2017-10-11 2017-11-24 2017-12-22 2018-01-21 2018-02-25 2018-04-01 2019-04-01 tion and Treatment of TB Based Selection l TB patients MZ-MISAU-39901-CS-CQS / S Regional Capacity for Diseas erviços de Consultoria para e Surveillance, and Diagnost Consultant Qualifi a o desenho e supervisão da IDA / 58630 ics and Management of TB a Post Open - National 175,000.00 0.00 Canceled 2017-12-15 2018-01-05 2018-02-18 2018-03-20 2018-04-24 2018-10-21 cation Selection s obras de reabilitação dos L nd Occupational Lung Disea aboratórios da Beira e Namp ses ula MZ-MISAU-14785-CS-QCBS / Innovative Prevention, Detec Quality And Cost- Open - Internationa Pilot and scale up of innovati IDA / 58630 Post 100,000.00 0.00 Canceled 2017-09-30 2017-10-21 2017-12-04 2018-01-01 2018-01-31 2018-03-07 2018-04-11 2019-04-11 tion and Treatment of TB Based Selection l ve sputum sample transport system MZ-MISAU-108384-CS-CQS / Financing the conclussion of Innovative Prevention, Detec Consultant Qualifi the ongoing consultance revi IDA / 58630 Post Open - National 92,480.00 0.00 Canceled 2019-04-30 2019-05-21 2019-07-04 2019-08-03 2019-09-07 2020-03-05 tion and Treatment of TB cation Selection sing the existing Lesgilastion to aline with international be st pratices MZ-MISAU-15036-CS-QCBS / Regional Capacity for Diseas Consulting services for desig e Surveillance, and Diagnost Quality And Cost- Open - Internationa n and supervision of construc IDA / 58630 ics and Management of TB a Post 175,000.00 0.00 Canceled 2017-08-21 2017-09-11 2017-10-25 2018-03-30 2017-11-22 2017-12-22 2018-01-26 2018-03-02 2019-03-02 Based Selection l tion of one (1) center of exce nd Occupational Lung Disea llence in the North region ses MZ-MISAU-56417-CS-QBS / I nnovative Community Case F Innovative Prevention, Detec Quality Based Sel inding and Community Scree IDA / 58630 Post Open - National 158,250.00 0.00 Canceled 2018-04-09 2018-04-05 2018-04-30 2018-06-13 2018-07-11 2018-08-10 2018-05-25 2018-09-09 2018-05-25 2018-10-14 2019-10-14 tion and Treatment of TB ection ning Campaigns for miners a nd their household contacts i ncluding children MZ-MISAU-15042-CS-QCBS / Regional Capacity for Diseas Consulting services for desig e Surveillance, and Diagnost Quality And Cost- Open - Internationa n and supervision of rehabilit IDA / 58630 ics and Management of TB a Post 350,000.00 0.00 Canceled 2017-08-21 2017-09-11 2017-10-25 2017-11-22 2017-12-22 2018-01-26 2018-03-02 2019-03-02 Based Selection l ation of one (1) center of exc nd Occupational Lung Disea ellence in Maputo Province ses MZ-MISAU-15054-CS-CQS / C Regional Capacity for Diseas ontract NGO or a researcher e Surveillance, and Diagnost partner to undertake optimal Consultant Qualifi Open - Internationa IDA / 58630 ics and Management of TB a Post 200,000.00 0.00 Canceled 2017-09-15 2017-10-06 2017-11-19 2017-12-19 2018-01-23 2018-07-22 case finding campaigns, pati cation Selection l nd Occupational Lung Disea ent screening with focus on ses miners, prisoners and other v ulnerable populations INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-MISAU-60617-CS-INDV / Innovative Prevention, Detec Individual Consult Hire a Consultant to Develop IDA / 58630 Post Limited 40,000.00 0.00 Signed 2018-05-21 2019-11-26 2018-05-26 2020-07-15 2018-06-16 2020-07-13 2018-07-21 2019-01-17 tion and Treatment of TB ant Selection the NTP Strategic Plan 2019 - 2023 MZ-MISAU-108385-CS-INDV / Regional Learning and Innov Individual Consult Consultancy to undertake an IDA / 58630 ation, and Project Managem Post Limited 15,000.00 9,749.00 Completed 2019-04-22 2019-04-05 2019-04-27 2019-04-05 2019-05-18 2019-04-30 2019-06-22 2019-04-12 2019-12-19 2019-04-30 ant Selection assessment of the project pe ent rformance MZ-MISAU-109880-CS-INDV / Finance a consultance to dev Innovative Prevention, Detec Individual Consult IDA / 58630 Post Limited 30,000.00 0.00 Signed 2019-04-22 2019-04-12 2019-04-27 2019-05-10 2019-05-18 2019-12-10 2019-06-22 2019-12-19 elop the Occupational Health tion and Treatment of TB ant Selection Program Strategic Plan MZ-MISAU-146850-CS-INDV / Innovative Prevention, Detec Individual Consult Under Implement Hiring a Monitoring & Evaluat IDA / 58630 Post Limited 108,000.00 0.00 2020-03-02 2020-03-16 2020-03-07 2020-03-28 2020-04-18 2021-12-31 tion and Treatment of TB ant Selection ation ion Specialist for the Tubercu losis Program MZ-MISAU-176326-CS-CDS / Innovative Prevention, Detec Study of catostrophic costs f IDA / 58630 Post Direct Selection Direct 150,000.00 196,165.00 Signed 2020-06-07 2020-06-05 2020-06-17 2020-06-12 2020-08-21 2020-08-11 2021-02-17 tion and Treatment of TB or TB patients MZ-MISAU-60202-CS-INDV / Innovative Prevention, Detec Individual Consult Study of catostrophic costs f IDA / 58630 Post Limited 50,000.00 0.00 Canceled 2018-04-26 2019-05-12 2018-05-01 2018-05-22 2018-06-26 2018-12-23 tion and Treatment of TB ant Selection or TB patients MZ-MISAU-15060-CS-INDV / Regional Learning and Innov Consultant to adapt curricula Individual Consult IDA / 58630 ation, and Project Managem Post Open 25,000.00 0.00 Canceled 2018-03-15 2018-05-03 2018-05-24 2018-06-28 2018-12-25 for intermediate level health ant Selection ent officers (initial training for oc cupational health) Regional Capacity for Diseas MZ-MISAU-15062-CS-INDV / I e Surveillance, and Diagnost Individual Consult T Consultant for Genotyping I IDA / 58630 Post Open 5,000.00 0.00 Canceled 2018-03-19 2018-05-07 2018-05-28 2018-07-02 2018-12-29 ics and Management of TB a ant Selection T Systems nd Occupational Lung Disea ses MZ-MISAU-15053-CS-INDV / Regional Capacity for Diseas Hire International Consultant e Surveillance, and Diagnost Individual Consult IDA / 58630 Post Open 30,000.00 0.00 Canceled 2017-09-18 2017-11-06 2017-11-27 2018-01-01 2018-06-30 to review across sectors (hea ics and Management of TB a ant Selection th, minerals, labor) legislatio nd Occupational Lung Disea n ses MZ-MISAU-15049-CS-INDV / I Regional Capacity for Diseas ndividual Consultant to Devel e Surveillance, and Diagnost Individual Consult IDA / 58630 Post Open 30,000.00 0.00 Canceled 2017-09-18 2017-11-06 2017-11-27 2018-01-01 2018-06-30 op-update mine health inspe ics and Management of TB a ant Selection ction guidelines-protocol. nd Occupational Lung Disea ses Page 6 MZ-MISAU-15039-CS-INDV / Regional Learning and Innov Consultant to update curricul Individual Consult IDA / 58630 ation, and Project Managem Post Open 5,000.00 0.00 Canceled 2018-03-30 2018-05-18 2018-06-08 2018-07-13 2019-01-09 um and teach intermediate l ant Selection ent evel clinical officers to beco me TB managers MZ-MISAU-15025-CS-INDV / I Regional Capacity for Diseas ndividual consultant - Occup e Surveillance, and Diagnost ational Health Specialist to d Individual Consult IDA / 58630 ics and Management of TB a Post Open 15,000.00 0.00 Canceled 2017-08-25 2017-10-13 2017-11-03 2017-12-08 2018-06-06 evelop training package on d ant Selection nd Occupational Lung Disea ifferent tasks of inspecting sh ses aft vs surface mines, coal ver sus rubies versus gold MZ-MISAU-15020-CS-INDV / I ndividual Consultant for data Regional Learning and Innov Individual Consult quality assessment teams (o IDA / 58630 ation, and Project Managem Post Open 50,000.00 0.00 Canceled 2018-03-30 2018-05-18 2018-06-08 2018-07-13 2019-01-09 ant Selection ne clinical advisor who will su ent pervise provincial TB Manage rs MZ-MISAU-14917-CS-INDV / I Regional Learning and Innov Individual Consult ndividual Consultont for Web IDA / 58630 ation, and Project Managem Post Open 3,000.00 0.00 Canceled 2018-03-15 2018-05-03 2018-05-24 2018-06-28 2018-12-25 ant Selection site hosting, IT Support ent MZ-MISAU-14922-CS-CQS / I ndividual consultant to evalu Innovative Prevention, Detec Individual Consult ate options for Mozambique IDA / 58630 Post Open 30,000.00 0.00 Canceled 2018-03-30 2018-05-18 2018-06-08 2018-07-13 2019-01-09 tion and Treatment of TB ant Selection mHealth Platform, developm ent for TB symptoms screeni ng, care, M&E. MZ-MISAU-14919-CS-INDV / Consultant for Translation se Innovative Prevention, Detec Individual Consult IDA / 58630 Post Open 50,000.00 0.00 Canceled 2018-03-20 2018-05-08 2018-05-29 2018-07-03 2018-12-30 rvices, IRB application fees, tion and Treatment of TB ant Selection manuscrip publication fees MZ-MISAU-108392-CS-INDV / Innovative Prevention, Detec Individual Consult IDA / 58630 Post Limited 90,000.00 0.00 Canceled 2019-04-29 2019-05-04 2019-05-25 2019-06-29 2020-05-31 Hire a Data Manager Consult tion and Treatment of TB ant Selection ant MZ-MISAU-14925-CS-INDV / Regional Learning and Innov Consultant for translation ser Individual Consult IDA / 58630 ation, and Project Managem Post Open 25,000.00 0.00 Canceled 2017-09-20 2017-11-08 2017-11-29 2018-01-03 2018-07-02 vices, IRB application fees, m ant Selection ent anuscript publication fees MZ-MISAU-190721-CS-INDV / Development Gender, Huma Innovative Prevention, Detec Individual Consult IDA / 58630 Post Limited 45,000.00 0.00 Canceled 2020-09-13 2020-09-02 2020-09-18 2020-10-09 2020-11-13 2021-05-12 n Rights Mainstream Guidelin tion and Treatment of TB ant Selection es for Tuberculosis MZ-MISAU-190724-CS-INDV / Implement the Study of Kno Innovative Prevention, Detec Individual Consult wledge, Attitudes and Practic IDA / 58630 Post Open 100,000.00 0.00 Canceled 2020-09-13 2020-10-15 2020-11-01 2020-11-22 2020-12-27 2021-06-25 tion and Treatment of TB ant Selection es related to Tuberculosis in the high-risk Population in M ozambique MZ-MISAU-190717-CS-INDV / Innovative Prevention, Detec Individual Consult Revise TB recording and repo IDA / 58630 Post Limited 45,000.00 0.00 Canceled 2020-09-06 2020-09-02 2020-09-11 2020-10-02 2020-11-06 2021-05-05 tion and Treatment of TB ant Selection rting tools MZ-MISAU-147106-CS-INDV / Review of the routine monito Innovative Prevention, Detec Individual Consult IDA / 58630 Post Limited 70,000.00 0.00 Canceled 2020-02-16 2020-02-21 2020-03-13 2020-04-17 2020-10-14 ring system for the National tion and Treatment of TB ant Selection Tuberculosis Control Program in Mozambique MZ-MISAU-112197-CS-INDV / Recruit Project Manager to re Regional Learning and Innov Individual Consult inforce existing PIU capacity IDA / 58630 ation, and Project Managem Post Limited 144,000.00 0.00 Canceled 2019-04-29 2019-05-30 2019-05-04 2019-05-25 2019-06-29 2019-12-26 ant Selection and co-lead efforts to turn ar ent ound the Mozambique compo nent of the SATBHSS MZ-MISAU-112200-CS-INDV / Regional Learning and Innov MISAU would like to hire a TB Individual Consult IDA / 58630 ation, and Project Managem Post Limited 144,000.00 0.00 Canceled 2019-05-27 2019-06-01 2019-06-22 2019-07-27 2020-01-23 specialist in the TB Project to ant Selection ent strengthen implementation c apacity MZ-MISAU-108378-CS-INDV / Hiring a consultant to train a Regional Learning and Innov Individual Consult number of 20 health profissio IDA / 58630 ation, and Project Managem Post Open 30,000.00 0.00 Canceled 2019-04-29 2019-06-17 2019-07-08 2019-08-12 2020-02-08 ant Selection nals , in Maputo, on Occupati ent onal Health Program Manage ment Regional Capacity for Diseas MZ-MISAU-15069-CS-INDV / e Surveillance, and Diagnost Individual Consult IDA / 58630 Post Open 3,000.00 0.00 Canceled 2017-08-20 2017-10-08 2017-10-29 2017-12-03 2018-06-01 Contract translators ics and Management of TB a ant Selection nd Occupational Lung Disea ses MZ-MISAU-15006-CS-INDV / Regional Capacity for Diseas Long Term Consultant to dev e Surveillance, and Diagnost Individual Consult IDA / 58630 Post Open 30,000.00 0.00 Canceled 2017-09-20 2017-11-08 2017-11-29 2018-01-03 2018-07-02 elop-strengthen compensatio ics and Management of TB a ant Selection n systems and guidelines nd Occupational Lung Disea ses MZ-MISAU-14786-CS-QCBS / Regional Learning and Innov Individual Consultant to Deve Individual Consult IDA / 58630 ation, and Project Managem Post Open 15,000.00 0.00 Canceled 2017-08-17 2017-10-05 2017-10-26 2017-11-30 2018-05-29 lop-update occupational heal ant Selection ent th screening protocols MZ-MISAU-14876-CS-INDV / I Regional Learning and Innov Individual Consult ndividual Consultant to devel IDA / 58630 ation, and Project Managem Post Open 60,000.00 0.00 Canceled 2018-03-01 2018-04-19 2018-05-10 2018-06-14 2018-12-11 ant Selection op and reproduce IEC materi ent als MZ-MISAU-14897-CS-INDV / I Regional Learning and Innov Individual Consult IDA / 58630 Post Open 20,000.00 0.00 Canceled 2018-03-15 2018-05-03 2018-05-24 2018-06-28 2018-12-25 T Consultant ation, and Project Managem ant Selection ent MZ-MISAU-14900-CS-INDV / I ndividual consultant to desig Innovative Prevention, Detec Individual Consult n, develop, train staff and ma IDA / 58630 Post Open 30,000.00 0.00 Canceled 2017-09-30 2017-11-18 2017-12-09 2018-01-13 2018-07-12 tion and Treatment of TB ant Selection intain cloud based database of healthcare work screening MZ-MISAU-14910-CS-INDV / I ndividual consultant to colled Innovative Prevention, Detec Individual Consult and compile data from all NG IDA / 58630 Post Open 30,000.00 0.00 Canceled 2018-03-15 2018-05-03 2018-05-24 2018-06-28 2018-12-25 tion and Treatment of TB ant Selection O's partners, write a report, c onsider developing a manusc ript for pulication Page 7 MZ-MISAU-16905-CS-INDV / I Innovative Prevention, Detec Individual Consult ndividual Consultant (Clinic A IDA / 58630 Post Open 10,000.00 0.00 Canceled 2017-09-20 2017-11-08 2017-11-29 2018-01-03 2018-07-02 tion and Treatment of TB ant Selection dviser) - 03 MZ-MISAU-16903-CS-INDV / I Innovative Prevention, Detec Individual Consult ndividual Consultant (Clinic A IDA / 58630 Post Open 10,000.00 0.00 Canceled 2017-09-15 2017-11-03 2017-11-24 2017-12-29 2018-06-27 tion and Treatment of TB ant Selection dviser) - 02 Regional Capacity for Diseas MZ-MISAU-14923-CS-INDV / I e Surveillance, and Diagnost Individual Consult ndividual Consultant (Clinic A IDA / 58630 Post Open 10,000.00 0.00 Canceled 2017-09-20 2017-11-08 2017-11-29 2018-01-03 2018-07-02 ics and Management of TB a ant Selection dviser) - 01 nd Occupational Lung Disea ses MZ-MISAU-14907-CS-INDV / I ndividual consultant to write Innovative Prevention, Detec Individual Consult scripts for radio and televisio IDA / 58630 Post Open 5,000.00 0.00 Canceled 2017-09-30 2017-11-18 2017-12-09 2018-01-13 2018-07-12 tion and Treatment of TB ant Selection n spots on mass publicity ca mpaign for TB screening MZ-MISAU-14891-CS-INDV / I ndividual consultant to condu ct innovative community cas Innovative Prevention, Detec Individual Consult IDA / 58630 Post Open 25,000.00 0.00 Canceled 2017-09-30 2017-11-18 2017-12-09 2018-01-13 2018-07-12 e finding and community scr tion and Treatment of TB ant Selection eening campaigns for miners and their households contact s including children MZ-MISAU-14904-CS-INDV / Consultant to conduct Lands Innovative Prevention, Detec Individual Consult cape analysis of current capa IDA / 58630 Post Open 50,000.00 0.00 Canceled 2017-07-20 2017-09-07 2017-09-28 2017-11-02 2018-05-01 tion and Treatment of TB ant Selection city and development of 5 ye ar strategic plan for growth MZ-MISAU-39019-CS-CDS / C ontratação de um consultor I Regional Learning and Innov ndividual para a correcção d IDA / 58630 ation, and Project Managem Post Direct Selection Direct 6,000.00 0.00 Canceled 2017-12-04 2017-12-05 2017-12-11 2018-06-13 o Capítulo 8 do Manual de Im ent plementação do Projecto (PI M). MZ-MISAU-60607-CS-INDV / Innovative Prevention, Detec Individual Consult Hire a Consultant to Review t IDA / 58630 Post Limited 30,000.00 0.00 Canceled 2018-05-07 2018-05-12 2018-06-02 2018-07-07 2019-01-03 tion and Treatment of TB ant Selection he NTP Management Module s MZ-MISAU-59993-CS-INDV / Continuous Quality Improve Innovative Prevention, Detec Individual Consult IDA / 58630 Post Open 163,000.00 0.00 Canceled 2018-04-27 2018-06-15 2018-07-06 2018-08-10 2019-02-06 ment initiatives and supervisi tion and Treatment of TB ant Selection on visits integrated with HIV program MZ-MISAU-64075-CS-INDV / Consultoria para Desenho de Innovative Prevention, Detec Individual Consult IDA / 58630 Post Open 20,000.00 0.00 Canceled 2018-05-28 2018-07-16 2018-08-06 2018-09-10 2019-03-09 Instrumentos para Recolha d tion and Treatment of TB ant Selection e dados em Saúde Ocupacio nal MZ-MISAU-109092-CS-INDV / Finance the Hiring of consult Innovative Prevention, Detec Individual Consult ant to develop guidelines for IDA / 58630 Post Open 70,000.00 0.00 Canceled 2019-04-17 2019-06-05 2019-06-26 2019-07-31 2019-11-29 tion and Treatment of TB ant Selection quality improvement on susc eptible and MDR - TB service s MZ-MISAU-68929-CS-CDS / T here is a need to implement the Patient Sactisfaction Surv Innovative Prevention, Detec IDA / 58630 Post Direct Selection Direct 45,000.00 0.00 Canceled 2018-07-16 2018-07-26 2018-09-29 2019-03-28 ey along the Baseline Study. tion and Treatment of TB Therefore, MoH-NTP has deci ded to cover all (27) the SAT BHSS Project districts. MZ-MISAU-70071-CS-INDV / Development of Guidelines f Innovative Prevention, Detec Individual Consult IDA / 58630 Post Open 75,000.00 0.00 Canceled 2018-07-23 2018-09-10 2018-10-01 2018-11-05 2019-05-04 or Quality Improvement of th tion and Treatment of TB ant Selection e National Tuberculosis Prog ram MZ-MISAU-109090-CS-INDV / Finance Hiring of consultant t Innovative Prevention, Detec Individual Consult o develop an interactive man IDA / 58630 Post Limited 30,000.00 0.00 Canceled 2019-04-16 2019-04-21 2019-05-12 2019-06-16 2019-12-13 tion and Treatment of TB ant Selection ual to inform, educate childre n, tween and teenagers abou t tuberculosis MZ-MISAU-60611-CS-INDV / Innovative Prevention, Detec Individual Consult Hire a Consultant to Develop IDA / 58630 Post Limited 30,000.00 0.00 Canceled 2018-05-04 2018-05-09 2018-05-30 2018-07-04 2018-12-31 tion and Treatment of TB ant Selection The National Latent Tubercul osis Guidelines MZ-MISAU-60616-CS-INDV / Hire a Consultant to Develop Innovative Prevention, Detec Individual Consult IDA / 58630 Post Limited 30,000.00 0.00 Canceled 2018-05-07 2018-05-12 2018-06-02 2018-07-07 2019-01-03 the Guidelines for Tuberculo tion and Treatment of TB ant Selection sis Community Activities MZ-MISAU-60610-CS-INDV / Innovative Prevention, Detec Individual Consult Hire a Consultant to Review t IDA / 58630 Post Limited 30,000.00 0.00 Canceled 2018-05-09 2018-05-14 2018-06-04 2018-07-09 2019-01-05 tion and Treatment of TB ant Selection he Childhood Tuberculosis H andbook MZ-MISAU-15008-CS-INDV / Consultant to update TB, MD Innovative Prevention, Detec Individual Consult R-TB clinical guidelines, infec IDA / 58630 Post Open 145,500.00 0.00 Canceled 2017-09-25 2017-11-13 2017-12-04 2018-01-08 2018-07-07 tion and Treatment of TB ant Selection tion control guidelines, print guides and distribute nationa lly MZ-MISAU-366141-CS-INDV / Regional Learning and Innov Individual Consult Pending Impleme IDA / 58630 Post Limited 34,000.00 0.00 2023-06-18 2023-06-22 2023-06-28 2023-07-10 2023-08-25 Hiring a consultant to prepar ation, and Project Managem ant Selection ntation e the ICR ent Page 8 PROCUREMENT PLAN Project information: Papua New Guinea, Energy Utility Performance and Reliability Improvement Project (EUPRIP), P167820 Project Implementation agency: PNG Power Limited (PPL) Date of the Procurement Plan: July 2019 Period covered by this Procurement Plan: July 2019 – December 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in National Procurement Act 2018 (came into operation April 1, 2019) and the Public Finance Management Act (1995 as amended), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable Other Relevant Procurement Information. Not Applicable PROCUREMENT Papua New Guinea : Energy Utility Performance and Reliability Improvement Project PLAN General Information Country: Papua New Guinea 2019-07-22 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167820 GPN Date: 2021-09-02 Project Name: Energy Utility Performance and Reliability Improvement Project Loan / Credit No: IBRD / 92120, / PNG Power Limited Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-PPL-157606-GO-RFB / DE SIGN, SUPPLY, AND INSTALLA Implementation of key comp TION OF ADVANCED METERI Open - Internationa Single Stage - One E Under Imple IBRD / 92120 onents of PPL's Performance Prior Request for Bids 3,000,000.00 0.00 2020-03-17 2020-06-30 2020-03-22 2020-11-09 2020-05-03 2021-06-09 2020-06-02 2022-11-23 2020-07-07 2021-01-03 NG INFRASTRUCTURE (AMI) S l nvelope mentation Improvement Plan YSTEMS TO SUPPORT REVEN UE RECOVERY AND PROTECT ION PROGRAMS NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-PPL-123839-CS-QCBS-01- Project management suppor Quality And Cost- Open - Internationa Pending Impleme 2019 / Owner’s Engineer for r / Prior 500,000.00 0.00 2019-07-30 2019-08-20 2019-10-03 2019-11-15 2019-12-15 2020-01-19 2020-02-23 2021-02-22 t Based Selection l ntation ehabilitation/upgrade of PPL I nfraestructure INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-PPL-123835-CS-INDV-02- Project management suppor Individual Consult 2019 / Financial Management IBRD / 92120 Prior Open 300,000.00 0.00 Canceled 2019-07-22 2019-08-16 2019-09-12 2019-10-03 2019-11-07 2020-11-11 t ant Selection Specialist PG-PPL-123836-CS-INDV-01- Project management suppor Individual Consult Pending Impleme / Prior Open 750,000.00 0.00 2019-07-30 2019-09-07 2019-09-28 2019-11-02 2020-11-11 2019 / Project Manager t ant Selection ntation PG-PPL-123837-CS-INDV-03- Project management suppor Individual Consult IBRD / 92120 Prior Open 300,000.00 0.00 Canceled 2019-07-26 2019-08-16 2019-09-13 2019-10-04 2019-11-08 2020-11-08 2019 / Procurement Specialis t ant Selection t PG-PPL-205423-CS-QCBS / R Implementation of key comp Individual Consult evenue protection program s IBRD / 92120 onents of PPL's Performance Post Open 200,000.00 172,529.83 Signed 2020-11-24 2020-11-25 2021-01-12 2021-05-26 2021-01-17 2021-05-27 2021-01-20 2021-05-29 2022-01-20 ant Selection pecialist Improvement Plan PG-PPL-326341-CS-INDV / En Project management suppor Individual Consult Open - Internationa Under Implement vironmental and Social Safeg IBRD / 92120 Post 250,000.00 0.00 2023-02-10 2023-04-20 2023-03-31 2023-04-14 2023-05-19 2023-11-15 t ant Selection l ation uard Specialist PG-PPL-PROCUREMENT SPEC Project management suppor Individual Consult Open - Internationa Under Implement IBRD / 92120 Post 300,000.00 0.00 2023-02-22 2023-03-14 2023-04-12 2023-05-03 2023-06-07 2024-06-07 -INDV - 2023 / Procurement S t ant Selection l ation pecialist PG-PPL-FMS-CS-INDV - 2023 Project management suppor Individual Consult Open - Internationa IBRD / 92120 Post 300,000.00 0.00 Canceled 2023-02-22 2023-02-27 2023-04-15 2023-05-06 2023-06-10 2024-06-14 / Financial Management Spec t ant Selection l ialist PG-PPL-364107-CS-INDV / Fi Project management suppor Individual Consult Under Implement IBRD / 92120 Post Open - National 210,000.00 0.00 2023-06-04 2023-05-31 2023-07-23 2023-08-13 2023-09-17 2024-09-16 nancial Management Speciali t ant Selection ation st Page 1 PROCUREMENT PLAN - Textual Part Project information: Sint Maarten Emergency Recovery Project (P167339) Project Implementation Agency: NRPB Date of the Procurement Plan: April 29, 2021 Period covered by this Procurement Plan: From April 2021 to March 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: Shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the National Procurement Legislation such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The Bank’s Anti- Corruption Guidelines and Sanctions Framework shall be incorporated into the national bidding documents by adding a page entitled “Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework”. 2. Contracts with an appropriate allocation of responsibilities, risks, and liabilities between the Borrower and the contractors/suppliers/consultants. 3. Rights for the Bank to review procurement documentation and activities. In accordance with the Procurement Regulations, each bidding document and contract shall include provisions stating the Bank's policy to sanction firms or individuals, found to have engaged in fraud and/or corruption as defined in the Procurement Regulations. In accordance with the Procurement Regulations, each bidding document and contract financed out of the proceeds of the Financing Agreement shall provide that bidders, suppliers, contractors and their subcontractors, agents, personnel, consultants, service providers, or suppliers shall permit the Bank to inspect all accounts, records and other documents relating to the bid submission and performance of the contract and to have said accounts and records audited by auditors appointed by the Bank. Acts intended to materially impede the exercise of the Bank's inspection and audit rights provided for in the Procurement Regulations constitute an obstructive practice as defined in the Regulations. 4. No bids shall be rejected solely because they fall below or exceed the estimated cost. All bids (including in the case when less than two bids are received) shall not be rejected, the procurement process shall not be cancelled, and new bids shall not be solicited without the Bank's prior written concurrence. The Bidding Documents template to be used under “national open competitive procurement arrangements” are subject to prior written concurrence by the Bank. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable. Procurement of Second-hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: not applicable Works: not applicable. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. Procurement in Situations of Urgent Need of Assistance or Capacity Constraints. PROCUREMENT PLAN Goods Notification Activity Draft Signed Review Procurement Evaluation of Intention Reference No. / In-Process Component Contract Contract Type Category Options of Award Description: Planned Planned Planned Restoring a community SX-NRPB- learning and 205571-GO-DIR / No cultural Post Goods Direct 2021/01/30 2021/02/13 2021/03/06 ICT Equipment environment, Project Management Consulting Services Draft Signed Negotiated Activity Contract Market Contract Reference No. In-Process Component Review Type Category Approach / Description: Planned Planned SX-NRPB- Restoring a 205590-CS- community CDS / ESS8 Consultant No learning and Post Direct 2021/03/26 2021/04/30 Cultural Services cultural Heritage environment Consultants SX-NRPB- 205594-CS- Rebuilding safe Consultant CDS / School No Prior Direct 2021/04/10 2021/05/15 schools Services and Library designs Individual Consultants Terms of Expression Signed Activity Reference of Interest Contract Reference In- Review Market Component Category No. / Process Type Approach Description: Planned Planned Planned SX-NRPB- 205589-CS- INDV / Consultant No Project Management Post Open 2021/03/04 2021/03/25 2021/06/24 MECYS Services Project Manager SX-NRPB- 205575-CS- Restoring a community INDV / learning and cultural Consultant Technical No Post Open 2021/01/04 2021/01/25 2021/04/26 environment,Project Services Assistant Management Project Engineer SX-NRPB- Restoring a community 205576-CS- learning and cultural Consultant INDV / No Post Open 2021/02/04 2021/02/25 2021/05/27 environment,Project Services Safeguards Management Specialist SX-NRPB- 205592-CS- Restoring a community INDV / Needs Consultant No learning and cultural Post Open 2021/02/04 2021/02/25 2021/05/27 Assessment Services environment for Inclusive Education SX-NRPB- 205415-CS- INDV / FRLP: Local Consultant to Restoring a community work on learning and cultural strategy and Consultant No environment,Strengthening Post Open 2021/01/04 2021/01/18 2021/04/19 Framework Services the Ministry’s Management for SXM Information System Cultural Heritage and other Learning Services SX-NRPB- 205561-CS- Consultant INDV / No Project Management Post Open 2021/01/04 2021/01/25 2021/04/26 Services Procurement Specialist SX-NRPB- 205593-CS- Strengthening the INDV / Consultant No Ministry’s Management Post Open 2021/03/01 2021/03/22 2021/06/21 Development Services Information System MIS framework PROCUREMENT St Maarten : Sint Maarten Emergency Recovery Project I PLAN General Information Country: St Maarten 2018-09-05 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167339 GPN Date: Project Name: Sint Maarten Emergency Recovery Project I Loan / Credit No: TF / A8079, TF / B5199 National Recovery Program Bureau Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SX-NRPB-156576-CW-RFB / P Housing Repair and Public B Open - Internationa Single Stage - One E 2020-12-1 ublic Building Repairs: Educa TF / A8079 uildings Repair and Reconstr Prior Request for Bids 5,000,000.00 0.00 Canceled 2020-03-02 2020-03-07 2020-04-18 2020-05-18 2020-06-22 l nvelope 9 tion Facilities uction SX-NRPB-165115-CW-RFB / Housing Repair and Public B Single Stage - One E 2,418,911.5 2021-01-1 TF / A8079 Post Request for Bids Limited 1,000,000.00 Completed 2020-03-25 2020-04-16 2020-03-30 2020-04-16 2020-05-11 2020-05-07 2020-06-10 2020-06-01 2020-07-15 2020-07-10 Rehabilitation of Shelters uildings Repair and Reconstr nvelope 4 1 uction SX-NRPB-181992-CW-RFB / P Housing Repair and Public B Single Stage - One E 1,946,600.0 2021-05-0 TF / A8079 Prior Request for Bids Limited 1,500,000.00 Signed 2020-07-14 2020-08-10 2020-07-19 2020-11-03 2020-08-30 2020-09-11 2020-09-29 2020-11-12 2020-11-03 2021-01-19 riority School Repairs uildings Repair and Reconstr nvelope 0 2 uction SX-NRPB-183349-CW-RFQ / Housing Repair and Public B Request for Quota Single Stage - One E 2021-03-0 SMHDF roof repairs, for retro TF / A8079 uildings Repair and Reconstr Post Limited 236,367.00 236,367.00 Signed 2020-07-13 2020-07-07 2020-09-07 2020-07-08 tions nvelope 6 active finance uction SX-NRPB-202289-CW-RFB / Housing Repair and Public B Open - Internationa Single Stage - One E 7,151,533.0 2021-08-2 Batch 2: Schools and F&A Bui TF / A8079 uildings Repair and Reconstr Post Request for Bids 4,750,000.00 Signed 2020-11-09 2021-04-27 2020-11-14 2021-05-10 2020-12-26 2021-07-06 2021-01-25 2021-10-01 2021-03-01 2021-12-21 l nvelope 0 8 lding Repairs uction SX-NRPB-202300-CW-RFB / Housing Repair and Public B Open - Internationa Single Stage - One E 5,471,564.0 2021-09-0 TF / A8079 Post Request for Bids 6,500,000.00 Signed 2020-11-16 2021-04-01 2020-11-21 2021-04-08 2021-01-02 2021-05-24 2021-02-01 2021-09-17 2021-03-08 2021-12-21 SMHDF Repairs Phase 2 uildings Repair and Reconstr l nvelope 0 4 uction SX-NRPB-202314-CW-RFB / Housing Repair and Public B Open - Internationa Single Stage - One E 2021-10-3 TF / A8079 Post Request for Bids 5,000,000.00 0.00 Canceled 2021-01-11 2021-08-31 2021-01-16 2021-08-31 2021-02-27 2021-11-09 2021-03-29 2022-01-14 2021-05-03 Batch 3: School Repairs uildings Repair and Reconstr l nvelope 0 uction Emergency measures for the SX-NRPB-202332-CW-RFB / Open - Internationa Single Stage - One E 3,779,342.0 2021-12-1 TF / A8079 recovery of disaster first res Post Request for Bids 5,000,000.00 Signed 2021-03-01 2021-08-23 2021-03-06 2021-08-23 2021-04-17 2021-10-05 2021-05-17 2021-11-05 2021-06-21 2022-01-11 GEBE Trenching Batch 1 l nvelope 0 8 ponders and preparedness f acilities SX-NRPB-208747-CW-DIR / Housing Repair and Public B 2021-07-1 Minor Repair Works to Home TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct 27,772.18 28,065.55 Completed 2020-12-09 2020-12-01 2020-12-14 2020-12-01 2021-01-18 2021-01-07 7 s: Aluminum System uction Request for Bids - SX-NRPB-202315-CW-RFB / Housing Repair and Public B Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2022-12-1 TF / A8079 Post Request for Bids 4,500,000.00 0.00 2022-03-01 2022-03-06 2022-04-17 2022-05-17 2022-06-21 Expansion of the EOC Buildin uildings Repair and Reconstr l nvelope (1 envelope proce lementation 8 g uction ss) National Procure SX-NRPB-275606-CW-RFB / Housing Repair and Public B Single Stage - One E ment Document - 2023-02-1 Single Family Home Repairs TF / A8079 uildings Repair and Reconstr Post Request for Bids Open - National 3,000,000.00 0.00 Signed 2022-05-01 2022-06-15 2022-05-06 2022-06-16 2022-06-17 2022-08-10 2022-07-17 2022-09-28 2022-08-21 nvelope 1 Envelope proce 7 PHASE 3 uction ss (Non Bank-SPD ) Request for Bids - Emergency measures for the SX-NRPB-202333-CW-RFB / Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2022-12-1 TF / A8079 recovery of disaster first res Post Request for Bids 5,000,000.00 0.00 2022-03-01 2022-03-06 2022-04-17 2022-05-17 2022-06-21 GEBE Trenching Batch 2 l nvelope (1 envelope proce lementation 8 ponders and preparedness f ss) acilities National Procure SX-NRPB-278379-CW-RFB / P Housing Repair and Public B ment Document - rocurement of Repair and Re Open - Internationa Single Stage - One E 2022-12-0 TF / A8079 uildings Repair and Reconstr Post Request for Bids 1 Envelope proce 5,000,000.00 0.00 Signed 2022-02-14 2022-03-10 2022-02-19 2022-03-10 2022-04-02 2022-05-27 2022-05-02 2022-08-05 2022-06-06 habilitation Works for 13 SXM l nvelope 3 uction ss (Non Bank-SPD schools - relaunch ) Request for Quota SX-NRPB-278660-CW-DIR / Housing Repair and Public B 2022-09-2 TF / A8079 Post Direct Selection Direct tions (Non Bank-S 4,000.00 4,100.45 Signed 2022-02-15 2022-01-27 2022-02-20 2022-02-24 2022-03-27 2022-03-15 MAC High I.T Classroom Relo uildings Repair and Reconstr 3 PD) cation uction Request for Quota AN-NRPB-93655-CW-RFQ / M Housing Repair and Public B Request for Quota Single Stage - One E Under Imple 2020-01-2 TF / A8079 Post Open - National tions (Non Bank-S 500,000.00 0.00 2019-06-06 2019-08-01 inor Repairs to 26 Homes uildings Repair and Reconstr tions nvelope mentation 8 PD) uction Request for Quota AN-NRPB-93655A-CW-RFQ / Housing Repair and Public B Request for Quota Single Stage - One E 2021-01-2 TF / A8079 Post Open - National tions (Non Bank-S 130,000.00 0.00 Signed 2020-06-06 2020-08-01 Minor Repairs to 3 Homes uildings Repair and Reconstr tions nvelope 8 PD) uction Request for Bids - SX-NRPB-357289-CW-RFB / Housing Repair and Public B Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2024-08-1 TF / B5199 Post Request for Bids 4,800,000.00 0.00 2023-04-30 2023-05-05 2023-06-16 2023-07-16 2023-08-20 Renovation of Gyms uildings Repair and Reconstr l nvelope (1 envelope proce lementation 9 uction ss) Request for Bids - SX-NRPB-357290-CW-RFB / Housing Repair and Public B Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2024-08-1 TF / B5199 Post Request for Bids 3,100,000.00 0.00 2023-04-30 2023-05-05 2023-06-16 2023-07-16 2023-08-20 Renovation of Sports facilitie uildings Repair and Reconstr l nvelope (1 envelope proce lementation 9 s uction ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Emergency measures for the SX-NRPB-136740-GO-DIR / Fi TF / A8079 recovery of disaster first res Prior Direct Selection Direct 2,250,000.00 1,938,933.00 Signed 2019-10-01 2020-06-04 2019-10-01 2020-06-18 2019-11-05 2020-02-27 2020-05-03 re Trucks ponders and preparedness f acilities Emergency measures for the SX-NRPB-143339-GO-DIR / S TF / A8079 recovery of disaster first res Prior Direct Selection Direct 15,000.00 15,120.00 Signed 2019-10-29 2020-05-27 2019-11-03 2020-06-15 2019-12-08 2020-01-09 2020-06-05 afety Shoes Fire Department ponders and preparedness f acilities Emergency measures for the SX-NRPB-157539-GO-DIR / D TF / A8079 recovery of disaster first res Post Direct Selection Direct 20,000.00 17,690.00 Signed 2020-02-09 2020-02-04 2020-02-14 2020-03-19 2020-03-20 2020-03-28 2020-09-16 iesel Water Pumps ponders and preparedness f acilities Emergency measures for the SX-NRPB-160723-GO-DIR / A TF / A8079 recovery of disaster first res Post Direct Selection Direct 60,000.00 52,355.72 Signed 2020-02-20 2019-12-11 2020-02-25 2020-03-10 2020-03-31 2020-04-15 2020-09-27 mbulance: Spare Parts ponders and preparedness f acilities SX-NRPB-160730-GO-DIR / F Emergency measures for the D&AD: Additional Radios and TF / A8079 recovery of disaster first res Post Direct Selection Direct 100,000.00 61,381.67 Signed 2020-02-20 2018-06-07 2020-02-25 2020-03-23 2020-03-31 2020-03-24 2020-09-27 Accessories ponders and preparedness f acilities Page 1 Emergency measures for the SX-NRPB-165436-GO-DIR / T TF / A8079 recovery of disaster first res Prior Direct Selection Direct 1,500,000.00 0.00 Canceled 2020-03-19 2020-06-04 2020-03-24 2020-06-18 2020-04-28 2020-10-25 ype II Ambulances ponders and preparedness f acilities Emergency measures for the SX-NRPB-167830-GO-DIR / P TF / A8079 recovery of disaster first res Post Direct Selection Direct 100,000.00 100,213.14 Signed 2020-04-06 2020-03-05 2020-04-06 2020-04-06 2020-05-11 2020-04-22 2020-11-07 roPac Isolation Capsules ponders and preparedness f acilities Emergency measures for the AN-NRPB-76471-GO-RFB / G Open - Internationa Single Stage - One E TF / A8079 recovery of disaster first res Prior Request for Bids 2,385,000.00 1,645,775.00 Signed 2020-05-18 2020-06-18 2020-05-23 2020-09-14 2020-07-04 2020-09-23 2020-08-03 2020-12-10 2020-09-07 2021-02-12 2021-03-06 eneral Vehicles l nvelope ponders and preparedness f acilities Emergency measures for the SX-NRPB-160728-GO-DIR / F TF / A8079 recovery of disaster first res Post Direct Selection Direct 100,000.00 174,753.00 Signed 2020-02-20 2021-05-10 2020-02-25 2021-02-05 2020-03-31 2021-05-26 2020-09-27 D: Spare Parts ponders and preparedness f acilities Emergency measures for the SX-NRPB-160720-GO-DIR / S TF / A8079 recovery of disaster first res Prior Direct Selection Direct 170,000.00 0.00 Canceled 2020-02-20 2020-02-25 2020-03-31 2020-09-27 ubmersible Water Pumps ponders and preparedness f acilities Emergency measures for the SX-NRPB-185662-GO-RFQ / Request for Quota Open - Internationa Single Stage - One E TF / A8079 recovery of disaster first res Post 320,000.00 0.00 Canceled 2020-08-12 2020-10-07 2021-04-05 Crane Trucks (2) tions l nvelope ponders and preparedness f acilities Emergency measures for the SX-NRPB-202313-GO-RFQ / Request for Quota Open - Internationa Single Stage - One E TF / A8079 recovery of disaster first res Post 630,000.00 0.00 Canceled 2020-11-20 2021-03-04 2021-01-15 2021-07-14 Command Vehicles tions l nvelope ponders and preparedness f acilities SX-NRPB-213914-GO-DIR / Si Emergency measures for the nt Maarten Fire Service Repai TF / A8079 recovery of disaster first res Post Direct Selection Direct 15,400.00 21,052.00 Signed 2021-01-15 2021-03-11 2021-01-20 2021-02-05 2021-02-24 2021-04-17 2021-08-23 r Parts 2 : Waziri Export ponders and preparedness f acilities SX-NRPB-213915-GO-DIR / Si Emergency measures for the nt Maarten Fire Service Repai TF / A8079 recovery of disaster first res Post Direct Selection Direct 8,800.00 6,603.47 Signed 2021-01-15 2021-03-11 2021-01-20 2021-02-05 2021-02-24 2021-05-07 2021-08-23 r Parts 3: Saint-Martin Cars ponders and preparedness f acilities Emergency measures for the SX-NRPB-216605-GO-RFQ / T Request for Quota Open - Internationa Single Stage - One E TF / A8079 recovery of disaster first res Post 90,000.00 0.00 Canceled 2021-02-03 2021-06-28 2021-03-31 2021-09-27 hirty Seater Bus (1) tions l nvelope ponders and preparedness f acilities SX-NRPB-218343-GO-DIR / Si Emergency measures for the nt Maarten Fire Service Repai TF / A8079 recovery of disaster first res Post Direct Selection Direct 27,500.00 28,132.52 Signed 2021-02-09 2021-03-11 2021-02-14 2021-02-08 2021-03-21 2021-04-14 2021-09-17 r Parts Package 4: Motorworl ponders and preparedness f d acilities SX-NRPB-218364-GO-DIR / Si Emergency measures for the nt Maarten Fire Service Repai TF / A8079 recovery of disaster first res Post Direct Selection Direct 3,000.00 2,181.54 Signed 2021-02-09 2021-03-11 2021-02-14 2021-02-08 2021-03-21 2021-04-16 2021-09-17 r Parts package 5: Napa Auto ponders and preparedness f Parts SXM acilities SX-NRPB-220199-GO-DIR / T Emergency measures for the ype II Ambulances: Wheeled TF / A8079 recovery of disaster first res Prior Direct Selection Direct 1,500,000.00 1,146,956.00 Signed 2021-02-18 2021-02-18 2021-02-23 2021-02-18 2021-03-30 2021-03-02 2021-09-26 Coach/ REV Group ponders and preparedness f acilities Emergency measures for the SX-NRPB-216373-GO-RFQ / S Request for Quota Open - Internationa Single Stage - One E TF / A8079 recovery of disaster first res Post 215,000.00 0.00 Canceled 2021-02-02 2021-04-12 2021-03-30 2021-09-26 upport Vehicles - Vans tions l nvelope ponders and preparedness f acilities SX-NRPB-221791-GO-DIR / C Emergency measures for the Pending Impl omputer Tablets and Protecti TF / A8079 recovery of disaster first res Post Direct Selection Direct 3,000.00 0.00 2021-02-27 2021-03-04 2021-04-08 2021-10-05 ementation ve Cases: Keijzer Computer S ponders and preparedness f ystems NV acilities Emergency measures for the SX-NRPB-239642-GO-RFQ / Request for Quota Single Stage - One E TF / A8079 recovery of disaster first res Post Limited 215,000.00 124,500.00 Signed 2021-06-22 2021-06-21 2021-08-17 2021-09-17 2022-02-13 Vans II tions nvelope ponders and preparedness f acilities Emergency measures for the SX-NRPB-241317-GO-RFQ / Request for Quota Open - Internationa Single Stage - One E TF / A8079 recovery of disaster first res Post 486,500.00 0.00 Canceled 2021-07-02 2021-07-21 2021-08-27 2022-02-23 Command Vehicles II (7) tions l nvelope ponders and preparedness f acilities Emergency measures for the SX-NRPB-241320-GO-RFQ / Request for Quota Open - Internationa Single Stage - One E TF / A8079 recovery of disaster first res Post 142,500.00 0.00 Canceled 2021-07-02 2021-07-15 2021-08-27 2022-02-23 Command Pick-up Trucks (3) tions l nvelope ponders and preparedness f acilities Emergency measures for the SX-NRPB-202345-GO-RFQ / Request for Quota Single Stage - One E TF / A8079 recovery of disaster first res Post Open - National 35,000.00 0.00 Signed 2020-12-06 2021-01-31 2021-07-30 MDS Goods tions nvelope ponders and preparedness f acilities SX-NRPB-202327-GO-RFQ / Emergency measures for the Request for Quota Open - Internationa Single Stage - One E Pending Impl MDS Automatic Weather Stat TF / A8079 recovery of disaster first res Post 350,000.00 0.00 2022-06-06 2022-08-01 2023-01-28 tions l nvelope ementation ions and Tidal Gauges ponders and preparedness f acilities Emergency measures for the SX-NRPB-275366-GO-DIR / Fi TF / A8079 recovery of disaster first res Post Direct Selection Direct 100,000.00 103,361.00 Signed 2022-02-01 2022-01-26 2022-02-06 2022-03-02 2022-03-13 2022-05-12 2022-09-09 re Suits - Viking ponders and preparedness f acilities SX-NRPB-284636-GO-RFB / F Emergency measures for the Open - Internationa Single Stage - One E Under Imple ire and Ambulance Vehicles ( TF / A8079 recovery of disaster first res Post Request for Bids 108,672.00 0.00 2022-03-21 2022-04-26 2022-03-26 2022-04-27 2022-05-07 2022-05-31 2022-06-06 2022-07-08 2022-07-11 2023-01-07 l nvelope mentation 12) ponders and preparedness f acilities Emergency measures for the SX-NRPB-284650-GO-RFB / V Open - Internationa Single Stage - One E Under Imple TF / A8079 recovery of disaster first res Post Request for Bids 200,000.00 0.00 2022-03-21 2022-07-14 2022-03-26 2022-07-19 2022-05-07 2022-10-04 2022-06-06 2022-11-16 2022-07-11 2023-01-07 ROMI Specialty Trucks l nvelope mentation ponders and preparedness f acilities SX-NRPB-288112-GO-DIR / M Emergency measures for the Pending Impl odular classrooms for tempor TF / A8079 recovery of disaster first res Post Direct Selection Direct 90,000.00 0.00 2022-04-05 2022-04-10 2022-05-15 2022-11-11 ementation ary relocation of classrooms ponders and preparedness f under repair acilities SX-NRPB-300150-GO-DIR / A Emergency measures for the mbulance Vehicle Warning Li TF / A8079 recovery of disaster first res Post Direct Selection Direct 4,000.00 0.00 Completed 2022-06-21 2022-07-01 2022-06-26 2022-07-01 2022-07-31 2023-01-27 2022-11-25 ghts & Siren ponders and preparedness f acilities NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SX-NRPB-160721-NC-DIR / E Housing Repair and Public B mergency Mold Assessment TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct 150,000.00 8,082.00 Signed 2020-02-20 2020-02-21 2020-02-25 2020-02-17 2020-03-31 2020-02-22 2020-09-27 and Remediation Action Plan uction Page 2 SX-NRPB-232003-NC-DIR / R Housing Repair and Public B etroactive Lease Agreement: TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct 4,200.00 5,400.00 Signed 2021-04-30 2021-04-09 2021-05-05 2020-12-04 2021-06-09 2021-05-20 2021-12-06 Simpson Bay Community Cen uction ter SX-NRPB-278661-NC-RFQ / Housing Repair and Public B Request for Quota Single Stage - One E Pending Impl TF / A8079 Post Limited 6,000.00 0.00 2022-02-20 2022-04-17 2022-10-14 Dumpster Rental for 16 Scho uildings Repair and Reconstr tions nvelope ementation ols uction SX-NRPB-278700-NC-RFQ / Housing Repair and Public B Request for Quota Single Stage - One E TF / A8079 Post Limited 100,000.00 0.00 Signed 2022-02-20 2022-05-18 2022-04-17 2022-10-14 Moving Company for 16 Scho uildings Repair and Reconstr tions nvelope ols uction SX-NRPB-278672-NC-DIR / S Housing Repair and Public B ecurity Company Services for TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct 30,000.00 0.00 Signed 2022-02-15 2022-02-11 2022-02-20 2022-02-23 2022-03-27 2022-09-23 MPC School uction SX-NRPB-278674-NC-RFQ / S Housing Repair and Public B Request for Quota Single Stage - One E torage Space/ Container Rent TF / A8079 uildings Repair and Reconstr Post Limited 130,000.00 57,995.00 Signed 2022-02-20 2022-06-13 2022-04-17 2022-08-10 2022-10-14 tions nvelope al for 16 Schools uction SX-NRPB-300184-NC-DIR / A Emergency measures for the mbulance Department Vehicl TF / A8079 recovery of disaster first res Post Direct Selection Direct 1,800.00 0.00 Completed 2022-06-21 2022-07-01 2022-06-26 2022-06-30 2022-07-31 2023-01-27 2022-12-02 e Branding and Striping ponders and preparedness f acilities SX-NRPB-311317-NC-DIR / M Housing Repair and Public B AC High Art Class Transporta TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct - National 32,000.00 0.00 Signed 2022-08-29 2022-08-19 2022-09-03 2022-08-18 2022-10-08 2023-04-06 tion Services uction Emergency measures for the SX-NRPB-312693-NC-DIR / R TF / A8079 recovery of disaster first res Post Direct Selection Direct - National 10,000.00 0.00 Signed 2022-08-31 2022-08-15 2022-09-05 2022-09-07 2022-10-10 2023-04-08 ental for MAC CSE Art Studio ponders and preparedness f acilities SX-NRPB-328192-NC-DIR / S Housing Repair and Public B Pending Impl chools Moving Services Here TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct - National 70,000.00 0.00 2021-02-25 2021-03-02 2021-04-06 2021-10-03 ementation and There Transport B.V uction SX-NRPB-328180-NC-DIR / A Housing Repair and Public B Pending Impl TF / A8079 Post Direct Selection Direct - National 5,000.00 0.00 2022-06-27 2022-07-02 2022-08-06 2023-02-02 rt Class Rental Silvia Carty uildings Repair and Reconstr ementation uction SX-NRPB-328195-NC-DIR / A Institutional Support for Rec Pending Impl dditional Structural Assessm TF / A8079 Post Direct Selection Direct - National 11,000.00 0.00 2021-02-21 2021-02-26 2021-04-02 2021-09-29 onstruction ementation ent and Design of 3 Schools I .C.E SX-NRPB-328194-NC-DIR / A Institutional Support for Rec Pending Impl dditional Structural Design a TF / A8079 Post Direct Selection Direct - National 2,432.00 0.00 2021-05-25 2021-05-30 2021-07-04 2021-12-31 onstruction ementation nd Assessment 3 Schools Pha se Two I.C.E SX-NRPB-328181-NC-DIR / S Housing Repair and Public B Pending Impl chools Security Services Haw TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct - National 15,038.00 0.00 2021-04-28 2021-05-03 2021-06-07 2021-12-04 ementation keye Security Force uction SX-NRPB-328179-NC-DIR / S Housing Repair and Public B Pending Impl chools Transportation Servic TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct - National 4,500.00 0.00 2022-04-01 2022-04-06 2022-05-11 2022-11-07 ementation es Group Transnational Trans uction port Services SX-NRPB-328183-NC-DIR / Fi Emergency measures for the Pending Impl re Dept. Suit Sizing Camille S TF / A8079 recovery of disaster first res Post Direct Selection Direct - National 1,400.00 0.00 2020-10-09 2020-10-14 2020-11-18 2021-05-17 ementation ewing & Boutique ponders and preparedness f acilities SX-NRPB-328182-NC-DIR / Fi Emergency measures for the Under Imple re Dept. Suit Sizing Camille S TF / A8079 recovery of disaster first res Post Direct Selection Direct - National 2,700.00 0.00 2021-09-15 2020-10-09 2021-09-20 2020-10-09 2021-10-25 2022-04-23 mentation ewing & Boutique ponders and preparedness f acilities SX-NRPB-328191-NC-DIR / H Institutional Support for Rec Pending Impl TF / A8079 Post Direct Selection Direct - National 3,901.00 0.00 2021-06-01 2021-06-06 2021-07-11 2022-01-07 ome Assessment I.C.E house onstruction ementation Nr.8 SX-NRPB-328189-NC-DIR / C Institutional Support for Rec Pending Impl ombining Technical Files for TF / A8079 Post Direct Selection Direct - National 1,578.00 0.00 2021-07-07 2021-07-12 2021-08-16 2022-02-12 onstruction ementation Schools RFB 3 I.C.E SX-NRPB-327303-NC-DIR / P Emergency measures for the erforated Vinyl Sides for Amb TF / B5199 recovery of disaster first res Post Direct Selection Direct - National 500.00 0.00 Completed 2022-11-23 2022-11-17 2022-11-28 2022-12-07 2023-01-02 2023-07-01 2023-01-23 ulances ponders and preparedness f acilities SX-NRPB-347195-NC-RFQ / S Housing Repair and Public B Request for Quota Single Stage - One E Under Imple TF / B5199 Post Open - National 96,140.00 0.00 2023-03-18 2023-05-13 2024-08-13 ecurity Services for 13 Schoo uildings Repair and Reconstr tions nvelope mentation ls uction SX-NRPB-347196-NC-DIR / Tr Housing Repair and Public B Pending Impl TF / B5199 Post Direct Selection Direct - National 66,667.00 0.00 2023-03-13 2023-03-18 2023-04-22 2024-03-31 ansportation Services for 13 uildings Repair and Reconstr ementation Schools uction SX-NRPB-347197-NC-DIR / L Housing Repair and Public B ease Agreement with NIPA fo Pending Impl TF / B5199 uildings Repair and Reconstr Post Direct Selection Direct - National 9,943.19 0.00 2023-03-13 2023-03-18 2023-04-22 2023-07-22 r Kitchen & Restaurant faciliti ementation uction es for Sundial School Student s SX-NRPB-347198-NC-DIR / L Housing Repair and Public B ease Agreement with NIA for Pending Impl TF / B5199 uildings Repair and Reconstr Post Direct Selection Direct - National 5,805.00 0.00 2023-03-13 2023-03-18 2023-04-22 2023-07-22 Dance Studio facilities for Su ementation uction ndial School Students CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SX-NRPB-132867-CS-LCS / A Institutional Support for Rec Least Cost Selecti TF / A8079 Prior Open - National 150,000.00 0.00 Canceled 2019-09-05 2019-09-26 2019-11-09 2019-12-07 2020-01-06 2020-02-10 2020-03-16 2020-09-12 udit Services NRPB onstruction on Institutional Support for Rec Least Cost Selecti ERP_C_015 / Audit services TF / A8079 Post Open - National 150,000.00 421,998.00 Signed 2019-09-05 2019-02-13 2019-09-26 2019-09-18 2019-11-09 2019-04-25 2019-12-07 2019-07-11 2020-01-06 2019-07-11 2020-02-10 2019-07-11 2020-03-16 2019-09-29 2020-09-12 onstruction on SX-NRPB-160722-CS-LCS / W Housing Repair and Public B Least Cost Selecti TF / A8079 Post Open - National 25,000.00 59,696.00 Signed 2019-11-06 2020-01-30 2019-11-27 2020-01-10 2020-01-30 2020-02-07 2020-03-25 2020-03-08 2020-03-25 2020-04-12 2020-03-25 2020-05-17 2020-04-24 2020-11-13 orks Verification Audit SMHD uildings Repair and Reconstr on F uction AN-IRC-NRPB-88561-CS-CQS Housing Repair and Public B Consultant Qualifi / SMHDF Technical Assessme TF / A8079 uildings Repair and Reconstr Post Open - National 250,000.00 207,300.00 Completed 2020-10-15 2019-01-03 2020-11-05 2020-11-17 2020-12-19 2019-01-24 2021-01-18 2019-09-27 2021-02-22 2019-10-01 2021-08-21 2020-04-09 cation Selection nt and Design for Phase 2 uction Page 3 AN-IRC-NRPB-109549-CS-QC Housing Repair and Public B Quality And Cost- BS / Technical Assessment Si TF / A8079 uildings Repair and Reconstr Post Open - National 500,000.00 522,461.00 Signed 2020-11-03 2019-07-10 2020-11-24 2021-08-04 2021-01-07 2019-04-22 2021-02-04 2019-04-22 2021-03-06 2019-04-22 2021-04-10 2019-07-11 2021-05-15 2019-07-16 2022-05-15 Based Selection ngle family Home Repairs 2 uction AN-NRPB-76431-CS-CQS / Su pervision Shelter Repairs Mai Institutional Support for Rec Consultant Qualifi n and Recovery Housing Rep TF / A8079 Post Open - National 100,000.00 402,811.88 Signed 2021-05-19 2019-02-11 2021-06-09 2022-03-08 2021-07-23 2019-03-22 2021-08-22 2019-08-12 2021-09-26 2019-08-16 2022-03-25 onstruction cation Selection air and Public Buildings Repai r and Reconstruction SX-NRPB-202330-CS-CQS / E Emergency measures for the Quality And Cost- Open - Internationa Pending Impleme mergency Cell Broadcast Sys TF / A8079 recovery of disaster first res Post 350,000.00 0.00 2022-06-01 2022-06-22 2022-08-05 2022-09-02 2022-10-02 2022-11-06 2022-12-11 2023-12-11 Based Selection l ntation tem ponders and preparedness f acilities SX-NRPB-298818-CS-LCS / N Institutional Support for Rec Least Cost Selecti Open - Internationa TF / A8079 Post 545,000.00 0.00 Signed 2022-06-14 2022-06-29 2022-07-05 2022-08-18 2022-07-05 2022-09-15 2022-08-15 2022-10-15 2022-09-29 2022-11-19 2022-09-29 2022-12-24 2023-06-22 RPB Financial Audit Services onstruction on l SX-NRPB-317497-CS-CQS / S Institutional Support for Rec Consultant Qualifi Open - Internationa TF / B5199 Post 20,000.00 0.00 Canceled 2022-09-23 2022-10-23 2022-11-07 2022-12-09 2023-01-08 2023-03-08 ecurity Assessment onstruction cation Selection l SX-NRPB-338215-CS-QCBS / Emergency measures for the Quality And Cost- Open - Internationa Under Implement Project Management Service TF / B5199 recovery of disaster first res Prior 3,000,000.00 0.00 2023-01-27 2023-04-12 2023-02-17 2023-05-17 2023-04-02 2023-04-30 2023-05-30 2023-07-04 2023-08-08 2024-12-02 Based Selection l ation s for ERP-1 ponders and preparedness f acilities SX-NRPB-352121-CS-CQS / P Housing Repair and Public B Consultant Qualifi Open - Internationa Pending Impleme TF / B5199 Post 150,000.00 0.00 2023-08-06 2023-08-27 2023-10-10 2023-11-09 2023-11-27 2024-11-26 reparation GEBE Investment uildings Repair and Reconstr cation Selection l ntation Plan uction INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SX-NRPB-124802-CS-INDV / Institutional Support for Rec Individual Consult PROJECT COORDINATOR– Sin TF / A8079 Post Open 180,000.00 267,983.36 Signed 2019-07-25 2019-07-25 2019-09-12 2019-10-18 2019-10-03 2019-11-25 2019-11-07 2020-05-30 2020-05-05 onstruction ant Selection t Maarten Digital Governmen t Project SX-NRPB-126135-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Prior Open 60,000.00 59,241.98 Signed 2019-08-03 2019-08-07 2019-09-21 2019-11-21 2019-10-12 2020-07-07 2019-11-16 2020-01-17 2020-05-14 Procurement Assistant Consu onstruction ant Selection ltant SX-NRPB-126138-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Prior Open 90,000.00 0.00 Canceled 2019-08-03 2019-08-07 2019-09-21 2019-10-12 2019-11-16 2020-05-14 Procurement Specialist Cons onstruction ant Selection ultant SX-NRPB-126137-CS-INDV / Institutional Support for Rec Individual Consult Portfolio and Accounting Offi TF / A8079 Post Open 180,000.00 0.00 Canceled 2019-08-03 2019-08-07 2019-09-21 2019-10-12 2019-11-16 2020-05-14 onstruction ant Selection cer for Small Enterprise Reco very Project SX-NRPB-126665-CS-CDS / I Institutional Support for Rec TF / A8079 Post Direct Selection Direct 14,000.00 12,150.00 Signed 2019-08-12 2019-09-01 2019-08-22 2019-08-08 2019-10-26 2019-09-01 2020-04-23 nterim Financial Managemen onstruction t Officer SX-NRPB-127209-CS-CDS / S Institutional Support for Rec TF / A8079 Post Direct Selection Direct 45,000.00 44,000.00 Signed 2019-08-14 2019-08-09 2019-08-24 2019-08-08 2019-10-28 2019-08-16 2020-04-25 takeholder Engagement Hom onstruction e Repairs SX-NRPB-128034-CS-INDV / J Institutional Support for Rec Individual Consult TF / A8079 Post Open 80,000.00 43,436.52 Terminated 2019-08-20 2019-08-23 2019-10-08 2019-10-18 2019-10-29 2019-11-12 2019-12-03 2019-11-16 2020-05-31 unior Communications Consu onstruction ant Selection ltant SX-NRPB-128036-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 40,000.00 27,000.00 Signed 2019-08-19 2019-08-22 2019-10-07 2019-11-19 2019-10-28 2019-11-26 2019-12-02 2019-11-27 2020-05-30 Financial Management Assist onstruction ant Selection ant SX-NRPB-129158-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 80,000.00 61,699.24 Signed 2019-08-26 2019-08-30 2019-10-14 2019-11-13 2019-11-04 2019-11-18 2019-12-09 2019-11-20 2020-06-06 Executive Assistant onstruction ant Selection SX-NRPB-129299-CS-INDV / J Institutional Support for Rec Individual Consult TF / A8079 Post Open 80,000.00 106,076.17 Signed 2019-08-30 2019-08-30 2019-10-18 2019-11-18 2019-11-08 2020-03-30 2019-12-13 2020-05-30 2020-06-10 r Environmental Safeguards onstruction ant Selection Specialist SX-NRPB-134548-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 25,000.00 0.00 Canceled 2019-09-16 2018-12-10 2019-11-04 2019-11-25 2019-12-30 2020-06-27 Communications Specialist onstruction ant Selection SX-NRPB-144180-CS-CDS / D Emergency measures for the esign Fire Department Renov TF / A8079 recovery of disaster first res Post Direct Selection Direct 100,000.00 0.00 Canceled 2019-11-04 2021-05-03 2019-11-04 2020-01-08 2020-07-06 ation and Expansion ponders and preparedness f acilities SX-NRPB-146192-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 150,000.00 0.00 Canceled 2019-12-12 2019-12-12 2020-02-14 2020-03-06 2020-04-10 2020-10-07 Contract Manager onstruction ant Selection SX-NRPB-153308-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 150,000.00 108,000.00 Signed 2020-01-31 2020-01-24 2020-03-20 2020-06-11 2020-04-10 2020-06-24 2020-05-15 2020-06-25 2020-11-11 Project Manager Education Pr onstruction ant Selection oject SX-NRPB-154610-CS-CDS / Institutional Support for Rec Mission Project Manager Digit TF / A8079 Post Direct Selection Direct 8,000.00 7,250.00 Signed 2020-01-20 2020-01-21 2020-01-20 2019-10-18 2020-01-27 2020-01-24 2020-02-17 onstruction al Government SX-NRPB-155761-CS-INDV / Institutional Support for Rec Individual Consult Project Manager Enterprise R TF / A8079 Post Open 150,000.00 0.00 Canceled 2020-01-24 2020-03-13 2020-04-03 2020-05-08 2020-11-04 onstruction ant Selection ecovery Project SX-NRPB-156570-CS-CDS / P Institutional Support for Rec TF / A8079 Post Direct Selection Direct 320,000.00 0.00 Canceled 2020-01-29 2020-01-29 2020-05-03 2020-10-30 rocurement Consultant Servi onstruction ces SX-NRPB-146438-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Prior Open 150,000.00 0.00 Canceled 2019-11-20 2020-01-08 2020-01-29 2020-03-04 2020-08-31 Procurement Specialist Cons onstruction ant Selection ultant 2 SX-NRPB-156572-CS-CDS / P roject Manager ERP-1 Institutional Support for Rec This is a continuation of the c TF / A8079 Post Direct Selection Direct 185,000.00 184,500.00 Signed 2020-01-29 2020-03-10 2020-02-08 2020-03-10 2020-04-13 2020-03-26 2020-10-10 onstruction urrent contract. This contract will go into effect on April 1 - March 31 2021. SX-NRPB-146440-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Limited 50,000.00 57,975.00 Signed 2019-11-22 2019-11-27 2019-11-27 2020-01-20 2020-02-07 2020-03-09 2020-03-13 2020-03-13 2020-09-09 Activity Manager School Rep onstruction ant Selection airs SX-NRPB-159532-CS-CDS / N Institutional Support for Rec TF / A8079 Prior Direct Selection Direct 200,000.00 49,262.46 Signed 2020-02-13 2021-02-02 2020-02-13 2020-02-13 2020-04-17 2020-02-13 2020-10-14 RPB Legal Services onstruction Page 4 SX-NRPB-161524-CS-CDS / A Institutional Support for Rec Pending Impleme TF / A8079 Post Direct Selection Direct 8,000.00 0.00 2020-02-26 2020-03-07 2020-05-11 2020-11-07 irport Benchmark Study onstruction ntation SX-NRPB-165435-CS-CDS / E Institutional Support for Rec TF / A8079 Post Direct Selection Direct 225,000.00 220,500.00 Signed 2020-03-19 2019-07-09 2020-03-29 2020-03-20 2020-06-02 2020-03-21 2020-11-29 ngineer onstruction SX-NRPB-166957-CS-CDS / P Institutional Support for Rec roject Coordinator Digital Go TF / A8079 Post Direct Selection Direct 16,000.00 40,000.00 Signed 2020-03-30 2019-12-01 2020-04-09 2020-04-02 2020-06-13 2020-04-10 2020-12-10 onstruction vernment INTERIM SX-NRPB-168099-CS-CDS / S Institutional Support for Rec TF / A8079 Post Direct Selection Direct 150,000.00 182,550.00 Signed 2020-04-08 2020-07-31 2020-04-18 2020-04-07 2020-06-22 2020-08-17 2020-12-19 ocial Safeguards Specialist onstruction SX-NRPB-168800-CS-CDS / D Institutional Support for Rec TF / A8079 Post Direct Selection Direct 120,000.00 177,000.00 Signed 2020-04-15 2020-04-14 2020-04-25 2020-05-04 2020-06-29 2020-05-05 2020-12-26 esign Rehabilitation of Shelte onstruction rs SX-NRPB-173096-CS-INDV / J Institutional Support for Rec Individual Consult TF / A8079 Post Open 60,000.00 89,982.21 Signed 2020-05-11 2019-10-01 2020-06-29 2020-05-15 2020-07-20 2020-06-19 2020-08-24 2020-06-23 2021-02-20 r Communication Officer 2 onstruction ant Selection SX-NRPB-167363-CS-CDS / Institutional Support for Rec TF / A8079 Prior Direct Selection Direct 30,000.00 63,000.00 Signed 2020-04-02 2021-01-12 2020-04-12 2020-05-08 2020-06-16 2020-05-08 2020-12-13 MP: Procurement Consultant onstruction SX-NRPB-167376-CS-CDS / S Institutional Support for Rec TF / A8079 Prior Direct Selection Direct 30,000.00 223,500.00 Signed 2020-04-02 2020-07-22 2020-04-12 2020-04-02 2020-06-16 2020-04-24 2020-12-13 I: Procurement Consultant onstruction SX-NRPB-186632-CS-CDS / T Housing Repair and Public B wenty Schools and F&A buildi TF / A8079 uildings Repair and Reconstr Prior Direct Selection Direct 820,600.00 790,190.00 Signed 2020-07-30 2020-08-19 2020-08-09 2020-05-19 2020-10-13 2020-09-01 2021-04-11 ng Design Consulting uction SX-NRPB-186392-CS-CDS / A Housing Repair and Public B sbestos Assessment Consulti TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct 25,000.00 56,950.00 Signed 2020-07-29 2020-07-29 2020-08-08 2020-08-23 2020-10-12 2020-09-19 2021-04-10 ng Services ROBERTO DAVID uction OVICH SX-NRPB-189349-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 85,000.00 0.00 Canceled 2020-08-18 2019-11-14 2020-10-06 2020-10-27 2020-12-01 2021-05-30 HR Consultant onstruction ant Selection SX-NRPB-189691-CS-CDS / L Emergency measures for the and Negotiation for Link 6 Ro TF / A8079 recovery of disaster first res Prior Direct Selection Direct 50,000.00 0.00 Canceled 2020-08-20 2020-08-28 2020-08-30 2020-09-23 2020-11-03 2021-05-02 ad-Hubert Lopez HISMAR NV ponders and preparedness f acilities SX-NRPB-191068-CS-CDS / S Institutional Support for Rec TF / A8079 Prior Direct Selection Direct 125,000.00 501,550.00 Signed 2020-08-28 2021-04-01 2020-09-07 2020-10-20 2020-11-11 2020-10-26 2021-05-10 GS Procurement Service onstruction SX-NRPB-196201-CS-CDS / F Institutional Support for Rec TF / A8079 Post Direct Selection Direct 30,000.00 0.00 Under Review 2020-09-25 2020-10-05 2020-12-09 2021-06-07 MO Consultant Home Based onstruction SX-NRPB-197284-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 180,000.00 181,250.00 Signed 2020-10-01 2020-12-12 2020-11-19 2020-05-18 2020-12-10 2020-06-01 2021-01-14 2021-01-12 2021-07-13 DL - Contract Manager onstruction ant Selection SX-NRPB-198813-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 150,000.00 0.00 Canceled 2020-10-15 2020-11-19 2020-12-03 2020-12-24 2021-01-28 2021-07-27 AR - Contract Manager onstruction ant Selection SX-NRPB-126986-CS-CDS / C Institutional Support for Rec Pending Impleme TF / A8079 Post Direct Selection Direct 85,690.00 0.00 2019-08-16 2019-08-26 2019-10-30 2020-04-27 orporate Governance Lawyer onstruction ntation 1 SX-NRPB-126988-CS-CDS / C Institutional Support for Rec Pending Impleme TF / A8079 Post Direct Selection Direct 61,250.00 0.00 2019-08-16 2019-08-26 2019-10-30 2020-04-27 orporate Governance Legal S onstruction ntation upport 1 SX-NRPB-126989-CS-CDS / C Institutional Support for Rec Pending Impleme TF / A8079 Post Direct Selection Direct 28,500.00 0.00 2019-08-16 2019-08-26 2019-10-30 2020-04-27 orporate Governance Legal S onstruction ntation upport 2 SX-NRPB-126987-CS-CDS / C Institutional Support for Rec Pending Impleme TF / A8079 Post Direct Selection Direct 79,000.00 0.00 2019-08-16 2019-08-26 2019-10-30 2020-04-27 orporate Governance Lawyer onstruction ntation 2 SX-NRPB-199448-CS-CDS / C Institutional Support for Rec TF / A8079 Post Direct Selection Direct 23,750.00 23,684.00 Signed 2020-10-13 2020-11-19 2020-10-23 2020-02-06 2020-12-27 2020-10-29 2021-06-25 ontract Manager (DL) Home onstruction Based SX-NRPB-170435-CS-CDS / I Institutional Support for Rec nterim Environmental Safegu TF / A8079 Post Direct Selection Direct 20,000.00 21,720.00 Signed 2020-04-24 2019-09-02 2020-05-04 2019-11-18 2020-07-08 2020-05-08 2021-01-04 onstruction ards Specialist SX-NRPB-201640-CS-CDS / J Institutional Support for Rec TF / A8079 Prior Direct Selection Direct 95,000.00 189,000.00 Signed 2020-10-26 2020-10-29 2020-11-05 2020-10-29 2021-01-09 2021-01-01 2021-07-08 B: Procurement Coordinator onstruction SX-NRPB-201789-CS-INDV / I Institutional Support for Rec Individual Consult Under Implement TF / A8079 Post Limited 25,000.00 0.00 2020-10-27 2020-10-27 2020-11-01 2020-11-22 2020-12-27 2021-06-25 nsurance Consultant onstruction ant Selection ation SX-NRPB-201788-CS-CDS / U Institutional Support for Rec TF / A8079 Post Direct Selection Direct 155,000.00 163,252.75 Signed 2020-10-27 2020-10-21 2020-11-06 2020-09-16 2021-01-10 2020-11-03 2021-07-09 B: Activity Manager Home Re onstruction pairs SX-NRPB-201795-CS-CDS / B Institutional Support for Rec TF / A8079 Post Direct Selection Direct 200,000.00 125,000.00 Signed 2020-10-27 2020-11-24 2020-11-06 2019-11-01 2021-01-10 2020-12-17 2021-07-09 B: ICT Helpdesk onstruction SX-NRPB-205755-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 50,000.00 50,000.00 Signed 2020-11-24 2020-11-20 2021-01-12 2021-03-04 2021-02-02 2021-03-04 2021-03-09 2021-05-20 2021-09-05 Copywriter onstruction ant Selection SX-NRPB-208921-CS-CDS / Institutional Support for Rec Mold Assessment Consultanc TF / A8079 Post Direct Selection Direct 50,000.00 141,910.00 Signed 2020-12-09 2020-12-07 2020-12-19 2020-12-03 2021-02-22 2021-01-15 2021-08-21 onstruction y: Farmer Environmental Gro up SX-NRPB-214549-CS-CDS / J Institutional Support for Rec TF / A8079 Prior Direct Selection Direct 50,000.00 48,000.00 Signed 2021-01-18 2021-01-28 2021-01-28 2021-01-07 2021-04-03 2021-02-10 2021-09-30 A: Procurement Consultant onstruction SX-NRPB-215465-CS-CDS / A Housing Repair and Public B TF / A8079 Post Direct Selection Direct 200,000.00 218,842.20 Signed 2021-01-21 2021-01-20 2021-01-31 2021-01-21 2021-04-06 2021-02-16 2021-10-03 C: Project Manager Infrastruc uildings Repair and Reconstr ture uction SX-NRPB-211337-CS-CDS / E Institutional Support for Rec TF / A8079 Post Direct Selection Direct 350,000.00 0.00 Canceled 2020-12-23 2021-01-02 2021-03-08 2021-09-04 ngineer onstruction SX-NRPB-231555-CS-INDV / J Emergency measures for the Individual Consult unior Environmental Speciali TF / A8079 recovery of disaster first res Post Open 60,000.00 70,200.00 Signed 2021-04-29 2021-05-18 2021-06-17 2021-09-06 2021-07-08 2021-09-30 2021-08-12 2021-10-01 2022-02-08 ant Selection st ponders and preparedness f acilities Page 5 SX-NRPB-232896-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 15,000.00 43,875.00 Signed 2021-05-03 2021-05-06 2021-06-21 2021-08-13 2021-07-12 2021-08-19 2021-08-16 2021-08-28 2022-02-12 HRM Consultant onstruction ant Selection SX-NRPB-236664-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 30,000.00 20,000.00 Signed 2021-05-28 2021-06-08 2021-07-16 2021-08-05 2021-08-06 2021-09-21 2021-09-10 2021-10-30 2022-03-09 Graphic Design Services onstruction ant Selection SX-NRPB-236668-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 30,000.00 35,000.00 Signed 2021-05-28 2021-06-08 2021-07-16 2021-08-05 2021-08-06 2021-09-21 2021-09-10 2021-11-04 2022-03-09 Video Production Services onstruction ant Selection SX-NRPB-236671-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 30,000.00 30,000.00 Signed 2021-05-28 2021-06-08 2021-07-16 2021-08-05 2021-08-06 2021-09-21 2021-09-10 2021-10-30 2022-03-09 Animation Services onstruction ant Selection SX-NRPB-239247-CS-CDS / S Institutional Support for Rec ocial Safeguards Consultant: TF / A8079 Post Direct Selection Direct 200,000.00 200,000.00 Signed 2021-06-14 2021-06-16 2021-06-24 2021-06-28 2021-08-28 2020-07-13 2022-02-24 onstruction Jo-Ann George SX-NRPB-240330-CS-CDS / Institutional Support for Rec TF / A8079 Post Direct Selection Direct 280,000.00 251,210.00 Signed 2021-06-18 2021-06-28 2021-06-20 2021-06-21 2021-06-23 2021-07-07 2023-05-31 MH: Project Manager EDMP onstruction SX-NRPB-241445-CS-CDS / D Emergency measures for the esign Fire Dept. Renovation a TF / A8079 recovery of disaster first res Post Direct Selection Direct 160,000.00 159,900.00 Signed 2021-06-28 2021-05-21 2021-07-08 2021-05-03 2021-09-11 2021-07-01 2022-03-10 nd Expansion: ICE ponders and preparedness f acilities SX-NRPB-242711-CS-CDS / P Institutional Support for Rec rocurement Coordinator: San TF / A8079 Post Direct Selection Direct 267,000.00 266,640.00 Signed 2021-07-11 2021-07-15 2021-07-21 2021-06-08 2021-09-24 2021-08-03 2022-03-23 onstruction tiago Ibarguen SX-NRPB-246966-CS-INDV / Institutional Support for Rec Individual Consult Under Implement TF / A8079 Prior Open 80,000.00 0.00 2021-09-17 2021-09-21 2021-11-05 2021-11-26 2021-12-31 2022-06-29 NRPB Procurement Assistant onstruction ant Selection ation SX-NRPB-252781-CS-CDS / P Institutional Support for Rec roject Funding Coordinator – TF / A8079 Post Direct Selection Direct 20,000.00 0.00 Canceled 2021-09-12 2021-09-08 2021-09-22 2021-11-26 2022-05-25 onstruction Housing Project SX-NRPB-253548-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 180,000.00 102,600.00 Signed 2021-09-17 2021-09-30 2021-11-05 2021-11-15 2021-11-26 2022-01-12 2021-12-31 2022-01-13 2022-06-29 DGTP Project Manager for DL onstruction ant Selection T SX-NRPB-254305-CS-INDV / Institutional Support for Rec Individual Consult Under Implement TF / A8079 Post Open 90,000.00 0.00 2021-09-24 2021-09-15 2021-11-12 2021-12-03 2022-01-07 2022-07-06 Program Management Assist onstruction ant Selection ation ant SX-NRPB-256482-CS-INDV / Institutional Support for Rec Individual Consult Under Implement TF / A8079 Post Open 90,000.00 0.00 2021-10-07 2021-10-05 2021-11-25 2021-12-16 2022-01-20 2022-07-19 Project Manager - Mental Hea onstruction ant Selection ation lth Project SX-NRPB-257387-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 60,000.00 58,800.00 Signed 2021-10-12 2021-10-08 2021-11-30 2022-01-27 2021-12-21 2022-04-06 2022-01-25 2022-04-07 2022-07-24 Executive Assistant II onstruction ant Selection SX-NRPB-257388-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 180,000.00 163,500.00 Signed 2021-10-12 2021-10-07 2021-11-30 2021-09-20 2021-12-21 2021-10-19 2022-01-25 2021-10-22 2022-07-24 Engineer II onstruction ant Selection SX-NRPB-257389-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 245,000.00 244,000.00 Signed 2021-10-12 2021-10-07 2021-11-30 2021-09-22 2021-12-21 2021-10-12 2022-01-25 2021-11-02 2022-07-24 Contract Manager II onstruction ant Selection SX-NRPB-257455-CS-CDS / E Institutional Support for Rec TF / A8079 Post Direct Selection Direct 20,000.00 31,972.50 Signed 2021-10-12 2021-10-07 2021-10-22 2021-09-20 2021-12-26 2021-10-22 2022-06-24 ngineer II onstruction SX-NRPB-258195-CS-CDS / P Institutional Support for Rec TF / A8079 Prior Direct Selection Direct 40,000.00 82,400.00 Signed 2021-10-15 2021-10-19 2021-10-25 2021-10-20 2021-12-29 2021-11-02 2022-06-27 rocurement Consultant: Paol onstruction o Maculotti SX-NRPB-258246-CS-CDS / P Institutional Support for Rec roject Finance Specialist-Hou TF / A8079 Post Direct Selection Direct 20,000.00 23,240.00 Signed 2021-10-14 2021-10-13 2021-10-24 2021-10-14 2021-12-28 2021-10-15 2022-06-26 onstruction sing Project SX-NRPB-258918-CS-CDS / P Institutional Support for Rec TF / A8079 Post Direct Selection Direct 15,000.00 12,750.00 Signed 2021-10-22 2021-10-27 2021-11-01 2021-10-27 2022-01-05 2021-10-30 2022-07-04 roject Officer - Mental Health onstruction Project SX-NRPB-262565-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Direct 130,000.00 140,000.00 Signed 2021-11-12 2021-11-08 2021-11-22 2021-10-20 2021-12-13 2021-12-04 2022-01-17 2021-12-13 2022-07-16 Procurement Consultant: Ms. onstruction ant Selection Jackson SX-NRPB-270528-CS-CDS / S Housing Repair and Public B TF / A8079 Post Direct Selection Direct 350,000.00 294,850.00 Signed 2021-12-24 2022-01-17 2022-01-03 2021-12-21 2022-03-09 2022-02-20 2022-09-05 chool Gyms Technical Assess uildings Repair and Reconstr ment uction SX-NRPB-272351-CS-CDS / P Institutional Support for Rec rocurement Consultant - Ho TF / A8079 Post Direct Selection Direct 72,090.00 72,090.00 Signed 2022-01-10 2022-01-14 2022-01-20 2022-01-18 2022-03-26 2022-01-22 2022-09-22 onstruction me Based : Paolo Maculotti SX-NRPB-272355-CS-CDS / P Institutional Support for Rec roject Manager EDMP: East W TF / A8079 Post Direct Selection Direct 165,000.00 174,000.00 Signed 2022-01-10 2022-01-07 2022-01-20 2022-01-05 2022-03-26 2022-02-25 2022-09-22 onstruction est Consultancy BV SX-NRPB-278264-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 250,000.00 295,050.00 Signed 2022-02-14 2022-03-01 2022-04-04 2022-04-18 2022-04-25 2022-05-16 2022-05-30 2022-05-17 2022-11-26 Senior Project Manager ERP1 onstruction ant Selection SX-NRPB-278699-CS-CDS / D Housing Repair and Public B esign of Fire Dept. Renovatio TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct 171,124.00 152,075.25 Signed 2022-02-15 2022-03-24 2022-02-25 2022-03-14 2022-05-01 2022-03-31 2022-10-28 n and Expansion completion uction of deliverables SX-NRPB-281075-CS-CDS / C Institutional Support for Rec TF / A8079 Post Direct Selection Direct 180,000.00 181,250.00 Signed 2022-02-28 2022-03-11 2022-03-10 2022-01-14 2022-05-14 2022-03-31 2022-11-10 ontract Manager - D. Louis onstruction SX-NRPB-282293-CS-INDV / Institutional Support for Rec Individual Consult Under Implement TF / A8079 Post Open 245,000.00 0.00 2022-03-11 2022-03-03 2022-04-29 2022-05-20 2022-06-24 2022-12-21 Social Safeguards Specialist onstruction ant Selection ation SX-NRPB-280013-CS-CDS / E Institutional Support for Rec TF / A8079 Post Direct Selection Direct 125,000.00 112,370.00 Signed 2022-03-08 2022-03-14 2022-03-18 2022-03-04 2022-05-22 2022-03-16 2022-11-18 nvironmental Safeguards Spe onstruction cialist SX-NRPB-286353-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Direct 52,500.00 150,480.00 Signed 2022-03-28 2022-03-21 2022-04-07 2022-03-23 2022-04-28 2022-03-23 2022-06-02 2022-04-06 2022-11-29 Senior Human Resources Con onstruction ant Selection sultant SX-NRPB-286729-CS-CDS / E Housing Repair and Public B Under Implement SS8 Cultural Heritage Mental TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct 20,000.00 0.00 2022-03-30 2022-04-14 2022-04-09 2022-04-21 2022-06-13 2022-12-10 ation Health Project uction SX-NRPB-287284-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Direct 105,000.00 103,106.00 Signed 2022-03-31 2022-05-24 2022-04-10 2022-05-31 2022-05-01 2022-05-31 2022-06-05 2022-06-02 2022-12-02 Activity Coordinator Home an onstruction ant Selection d Schools Page 6 SX-NRPB-288109-CS-INDV / Institutional Support for Rec Individual Consult Under Implement TF / A8079 Post Direct 161,712.00 0.00 2022-04-05 2022-05-15 2022-04-15 2022-08-17 2022-05-06 2022-08-17 2022-06-10 2022-12-07 Social Safeguards Consultant onstruction ant Selection ation SX-NRPB-291870-CS-CDS / R Housing Repair and Public B eview of MET building design TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct 7,400.00 6,688.00 Signed 2022-04-28 2022-05-04 2022-05-08 2022-04-13 2022-07-12 2022-05-10 2023-01-08 : Structural Integrity uction SX-NRPB-287287-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Direct 136,940.00 136,980.00 Signed 2022-05-04 2022-04-26 2022-05-14 2022-04-22 2022-06-04 2022-05-05 2022-07-09 2022-05-06 2023-01-05 Senior Advisor – Project Mana onstruction ant Selection gement SX-NRPB-294730-CS-INDV / Institutional Support for Rec Individual Consult Under Implement Medior Project Manager – Ho TF / A8079 Post Open 162,000.00 0.00 2022-05-17 2022-05-13 2022-07-05 2022-07-26 2022-08-30 2023-02-26 onstruction ant Selection ation using Project SX-NRPB-295647-CS-INDV / Institutional Support for Rec Individual Consult Communication Consultant - TF / A8079 Post Direct 63,250.00 63,000.00 Signed 2022-05-24 2022-05-16 2022-06-03 2022-06-30 2022-06-24 2022-06-30 2022-07-29 2022-07-01 2023-01-25 onstruction ant Selection Copywriter SX-NRPB-298841-CS-INDV / Institutional Support for Rec Individual Consult Communication and Commu TF / A8079 Post Direct 57,000.00 57,000.00 Signed 2022-06-10 2022-06-09 2022-06-20 2022-06-15 2022-07-11 2022-06-15 2022-08-15 2022-06-17 2023-02-11 onstruction ant Selection nity Outreach Consultant SX-NRPB-304252-CS-INDV / Institutional Support for Rec Individual Consult Direct - Internation PROJECT COORDINATOR - INF TF / A8079 Post 229,786.00 229,786.00 Signed 2022-07-21 2022-07-25 2022-07-31 2022-07-26 2022-08-21 2022-07-31 2022-09-25 2022-07-30 2024-03-25 onstruction ant Selection al RASTRUCTURE ERP-1 SX-NRPB-312698-CS-INDV / Institutional Support for Rec Individual Consult Open - Internationa Under Implement Communications and Commu TF / A8079 Post 91,200.00 0.00 2022-08-31 2022-08-25 2022-10-19 2022-11-09 2022-12-14 2023-12-14 onstruction ant Selection l ation nity Outreach Consultant SX-NRPB-314853-CS-INDV / Institutional Support for Rec Individual Consult Open - Internationa Under Implement Project Manager - St. Maarte TF / B5199 Post 270,000.00 0.00 2022-09-16 2022-09-20 2022-11-04 2022-11-25 2022-12-30 2024-06-30 onstruction ant Selection l ation n Wastewater Management P roject SX-NRPB-322083-CS-INDV / I Institutional Support for Rec Individual Consult Direct - Internation TF / B5199 Post 14,500.00 0.00 Signed 2022-10-21 2022-10-25 2022-10-31 2022-10-27 2022-11-21 2022-10-27 2022-12-26 2023-01-31 nterim Project coordinator W onstruction ant Selection al astewater SX-NRPB-325069-CS-INDV / Institutional Support for Rec Individual Consult Direct - Internation TF / B5199 Post 271,140.00 0.00 Signed 2022-11-15 2022-11-03 2022-11-25 2022-11-03 2022-12-16 2022-12-13 2023-01-20 2024-07-21 Head of Procurement - S.I onstruction ant Selection al SX-NRPB-326442-CS-INDV / J Institutional Support for Rec Individual Consult Pending Impleme TF / B5199 Post Open - National 90,000.00 0.00 2022-11-30 2023-01-18 2023-02-08 2023-03-15 2024-09-13 r. M&E Consultant onstruction ant Selection ntation SX-NRPB-326444-CS-INDV / Institutional Support for Rec Individual Consult Direct - Internation Under Implement TF / B5199 Post 160,000.00 0.00 2022-11-28 2022-01-11 2022-12-08 2023-01-12 2022-12-29 2023-01-12 2023-01-16 2024-07-17 Program Advisor onstruction ant Selection al ation SX-NRPB-326641-CS-INDV / Institutional Support for Rec Individual Consult Open - Internationa Under Implement TF / B5199 Post 260,000.00 0.00 2022-11-30 2023-01-11 2023-01-18 2023-02-08 2023-05-08 2024-11-06 Project Manager Housing onstruction ant Selection l ation SX-NRPB-333295-CS-INDV / Institutional Support for Rec Individual Consult Open - Internationa Under Implement TF / B5199 Post 45,000.00 0.00 2022-12-23 2023-01-12 2023-02-10 2023-03-03 2023-04-07 2024-04-06 Financial Management Assist onstruction ant Selection l ation ant SX-NRPB-260433-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 25,000.00 0.00 Canceled 2021-10-29 2021-12-17 2022-01-07 2022-02-11 2022-08-10 Sector Expert - Housing onstruction ant Selection SX-NRPB-342557-CS-INDV / Institutional Support for Rec Individual Consult Open - Internationa Under Implement TF / B5199 Post 110,000.00 0.00 2023-02-17 2023-02-27 2023-04-07 2023-04-28 2023-06-02 2024-06-01 Project Officer ERP-1 onstruction ant Selection l ation SX-NRPB-342572-CS-INDV / Institutional Support for Rec Individual Consult Open - Internationa TF / B5199 Post 100,000.00 0.00 Canceled 2023-02-17 2023-02-27 2023-04-07 2023-04-28 2023-06-02 2024-06-01 Senior Advisor -Housing Proje onstruction ant Selection l ct SX-NRPB-347124-CS-INDV / Institutional Support for Rec Individual Consult Direct - Internation Under Implement TF / B5199 Post 221,000.00 0.00 2023-03-05 2023-03-20 2023-03-15 2023-05-19 2023-04-05 2023-04-12 2023-05-10 2024-09-14 Coordinating Environmental onstruction ant Selection al ation Specialist SX-NRPB-347131-CS-INDV / Institutional Support for Rec Individual Consult Open - Internationa Under Implement TF / B5199 Post 245,000.00 0.00 2023-03-05 2023-03-20 2023-04-23 2023-05-14 2023-06-18 2024-10-31 Social Specialist onstruction ant Selection l ation SX-NRPB-353790-CS-INDV / Institutional Support for Rec Individual Consult Under Implement TF / B5199 Post Direct - National 65,000.00 0.00 2023-04-05 2023-04-26 2023-04-15 2023-05-16 2023-05-06 2023-05-16 2023-06-10 2024-06-09 Executive Assistant Consulta onstruction ant Selection ation nt SX-NRPB-326436-CS-INDV / Institutional Support for Rec Individual Consult Direct - Internation Under Implement TF / B5199 Post 165,000.00 0.00 2022-11-15 2023-05-23 2022-11-25 2022-12-16 2023-06-01 2024-12-31 Engineer ERP-1 - K.W onstruction ant Selection al ation SX-NRPB-363223-CS-INDV / Institutional Support for Rec Individual Consult TF / B5199 Post Direct - National 15,000.00 0.00 Under Review 2023-05-28 2023-05-23 2023-06-07 2023-06-28 2023-08-02 2023-10-02 Energy Specialist onstruction ant Selection SX-NRPB-364424-CS-INDV / Institutional Support for Rec Individual Consult Open - Internationa Under Implement TF / B5199 Post 100,000.00 0.00 2023-06-09 2023-05-31 2023-07-28 2023-08-18 2023-09-22 2024-09-21 Housing Sector Expert onstruction ant Selection l ation SX-NRPB-364743-CS-INDV / Institutional Support for Rec Individual Consult TF / B5199 Prior Direct - National 242,510.00 0.00 Signed 2023-06-01 2023-06-01 2023-06-11 2023-06-02 2023-07-02 2023-06-02 2023-08-06 2024-08-05 Procurement Consultant Ms. J onstruction ant Selection ackson II SX-NRPB-364744-CS-CDS / F Institutional Support for Rec Under Implement acilitator Performance Agree TF / B5199 Post Direct Selection Direct - National 60,000.00 0.00 2023-06-09 2023-06-22 2023-06-19 2023-06-19 2023-08-23 2024-05-22 onstruction ation ment Housing SX-NRPB-368036-CS-INDV / Institutional Support for Rec Individual Consult Direct - Internation Under Implement TF / B5199 Prior 153,900.00 0.00 2023-06-25 2023-06-22 2023-07-05 2023-06-13 2023-07-26 2023-06-26 2023-08-30 2024-08-29 Procurement Consultant Mr. onstruction ant Selection al ation Maculotti II Page 7 Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: March 21, 2017 2. Date of General Procurement Notice: June 3, 2016 3. Period covered by this procurement plan: March 2017 to Feb 2018 II. Goods, Works, Consultant and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Prior Review Comments Threshold (PRT) US$ (Millions) 1. Works (Including turnkey, supply & 5 High risk installation of plant and equipment and PPP) 2. (Goods; Information Technology & 1.5 High risk Non-Consulting Services) 3. Consultant Services (Firms) 0.5 High risk 4. Consultant Services (Individual 0.2 High risk Consultants) 2. Prequalification. NA 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: Available in Project files 5. Any Other Special Procurement Arrangements: NA 6. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 7. All TORs for the procurement of consultants services irrespective of the estimated cost of the assignment shall be reviewed and cleared by the TTL 8. Operating expenditures are neither subject to the Procurement and Consultant Guidelines nor prior or post reviews. Operating expenditures are normally verified by TTLs and FM specialists and obtained using the Borrower’s national procurement and administrative procedures. March 21, 2017 9. Renewal or extension of individual consultant’s contracts hired for technical assistance and which are intended for a long-term period but signed for an initial period shorter than the duration of the project, and that have been prior reviewed, do not require procurement clearance if there is no substantial change in the terms and conditions of the contract. March 21, 2017 PROCUREMENT Eastern and Southern Africa : AFR RI-The Eastern Electricity Highway Project under the First Phase of the Eastern Africa Power Integration Program PLAN General Information Country: Eastern and Southern Africa Bank’s Approval Date of the Original Procurement Plan: 2017-05-02 Revised Plan Date(s): (comma delineated, leave blank if 2023-05-27 none) Project ID: P126579 GPN Date: Project Name: AFR RI-The Eastern Electricity Highway Project under the First Phase of the Eastern Africa Power Integration Program Loan / Credit No: IDA / 51490, IDA / 51480 Kenya Electricity Transmission Company Limited Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-KETRACO-157906-CW-DI R / REQUEST FOR BIDS FOR I A. HVDC transmission interc Under Imple 2020-09-2 IDA / 51480 Post Direct Selection Direct 649,600.00 0.00 2020-02-14 2020-05-21 2020-02-19 2020-06-10 2020-03-25 NTEGRATION OF SCADA AT T onnector mentation 1 HE NATIONAL CONTROL CEN TRE KE-KETRACO-7578-CW-RFB / Engineering, Procurement, C A. HVDC transmission interc Open - Internationa Single Stage - One E 30,000,000.0 Under Imple 2022-02-1 IDA / 51480 Prior Request for Bids 0.00 2021-05-02 2021-05-07 2021-06-18 2021-07-18 2021-08-22 onstruction and Commissioni onnector l nvelope 0 mentation 8 ng of 400/220kV Substation i n Kimuka KE-KETRACO-357550-CW-RF Request for Bids - B / ENGINEERING, PROCURE A. HVDC transmission interc Open - Internationa Single Stage - One E Works (without pr 30,000,000.0 Pending Imp 2026-08-1 MENT, CONSTRUCTION AND IDA / 51480 Prior Request for Bids 0.00 2023-04-27 2023-05-02 2023-06-13 2023-07-13 2023-08-17 onnector l nvelope equalification) SP 0 lementation 6 COMMISSIONING OF 400/220 D KV SUBSTATION AT KIMUKA KE-KETRACO-353866-CW-RF B / ENGINEERING, PROCURE MENT AND CONSTRUCTION S ERVICES FOR THE DESIGN, P Request for Bids - ROCUREMENT, INSTALLATIO A. HVDC transmission interc Open - Internationa Single Stage - One E Works (without pr 67,000,000.0 Under Revie 2026-08-2 IDA / 51480 Prior Request for Bids 0.00 2023-05-02 2023-05-07 2023-06-18 2023-07-18 2023-08-22 N AND COMMISSIONING OF T onnector l nvelope equalification) SP 0 w 1 HE STATCOMS AND SHUNT D D EVICES ON THE KETRACO NE TWORK AT THE SUSWA 400/2 20 KV SUBSTATION (LOT 1) A ND RABAI 220/132 KV SUBST ATION (LOT 2) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-KETRACO-119183-GO-RF B / PROCUREMENT OF GOOD S FOR FOUR LOTS; LOT 1 SU BSTATION EQUIPMENT, LOT B. Project Management and Open - Internationa Single Stage - One E 2 TRUCK MOUNTED SUBSTAT IDA / 51480 Prior Request for Bids 61,000,000.00 0.00 Canceled 2019-06-14 2019-06-19 2019-07-31 2019-08-30 2019-10-04 2020-04-01 Capacity Building l nvelope IONS, LOT 3 TOOLS AND MAI NTENANCE EQUIPMENT, LOT 4 SUBSTATION AUTOMATION, CCTV SURVEILLANCE, CORPO RATE LAN WAN MONITORING EQUIPMENT NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-KETRACO-17359-NC-RFP / PROCUREMENT OF NON-CO A. HVDC transmission interc Request for Propo Open - Internationa Single Stage - One E NSULTING SERVICES FOR AE IDA / 51490 Prior 1,000,000.00 0.00 Canceled 2017-06-16 2017-06-21 2017-08-02 2017-09-01 2017-10-06 2018-04-04 onnector sals l nvelope RIAL MAPPING AND CADASTR AL SURVEY FOR TRANSMISSI ON LINE CORRIDORS. KE-KETRACO-30402-NC-RFB / PROCUREMENT OF NON-CO A. HVDC transmission interc Single Stage - One E IDA / 51480 Post Request for Bids Open - National 500,000.00 0.00 Canceled 2017-10-04 2017-10-09 2017-11-20 2017-12-20 2018-01-24 2018-07-23 NSULTING SERVICES FOR AE onnector nvelope RIAL MAPPING FOR TRANSMI SSION LINE CORRIDORS KE-KETRACO-34743-NC-RFB / NON-CONSULTANCY SERVIC B. Project Management and Single Stage - One E Under Imple ES AERIAL MAPPING SERVICE IDA / 51480 Post Request for Bids Open - National 730,000.00 790,841.59 2017-10-31 2017-11-10 2017-11-05 2017-12-17 2017-10-18 2018-01-16 2018-03-06 2018-02-20 2018-02-21 2018-08-19 Capacity Building nvelope mentation S FOR KENYA ELECTRICITY T RANSMISSION STRENGTHENI NG PROJECT KE-KETRACO-34755-NC-RFQ / NON-CONSULTANCY SERVIC ES CADASTRAL SERVICES FO B. Project Management and Request for Quota Single Stage - One E IDA / 51480 Post Limited 90,000.00 106,520.02 Signed 2017-11-05 2017-10-10 2017-12-31 2018-03-30 2018-06-29 R KENYA ELECTRICITY TRANS Capacity Building tions nvelope MISSION STRENGTHENING PR OJECT LOT 1 132kV NAROK B OMET TRANSMISSION LINE KE-KETRACO-35054-NC-RFQ / NON CONSULTANCY SERVIC ES FOR CADASTRAL SERVICE B. Project Management and Request for Quota Single Stage - One E S FOR KENYA ELECTRICITY T IDA / 51480 Post Limited 110,000.00 84,885.37 Signed 2017-11-07 2017-10-10 2018-01-02 2018-04-30 2018-07-01 Capacity Building tions nvelope RANSMISSION STRENGTHENI NG PROJECT LOT 2 132kV KA BARNET RUMURUTI TRANSMI SSION LINE KE-KETRACO-35056-NC-RFQ / NON CONSULTANCY SERVIC ES CADASTRAL SERVICES FO B. Project Management and Request for Quota Single Stage - One E IDA / 51480 Post Limited 60,000.00 105,720.48 Signed 2017-11-07 2017-10-10 2018-01-02 2018-04-30 2018-07-01 R KENYA ELECTRICITY TRANS Capacity Building tions nvelope MISSION STRENGTHENING PR OJECT LOT 4 220kV MALINDI KILIFI TRANSMISSION LINE KE-KETRACO-40014-NC-RFQ / NON CONSULTANCY SERVIC A. HVDC transmission interc Request for Quota Single Stage - One E ES CADASTRAL SERVICES LO IDA / 51480 Post Limited 112,000.00 102,063.57 Signed 2017-12-24 2017-10-10 2018-02-18 2018-04-30 2018-08-17 onnector tions nvelope T 5 132kV MACHAKOS MWAL A SARARA TRANSMISSION LI NE Page 1 KE-KETRACO-40028-NC-RFQ / NON-CONSULTANCY SERVIC A. HVDC transmission interc Request for Quota Single Stage - One E IDA / 51480 Post Limited 112,000.00 0.00 Canceled 2017-12-24 2018-02-18 2018-08-17 ES CADASTRAL SERVICES LO onnector tions nvelope T 6132kV SOTIK NYAMIRA TR ANSMISSION LINE KE-KETRACO-40031-NC-RFQ / NON-CONSULTANCY SERVIC A. HVDC transmission interc Request for Quota Single Stage - One E ES CADASTRAL SURVEY LOT IDA / 51480 Post Limited 112,000.00 57,535.71 Signed 2017-12-24 2017-10-10 2018-02-18 2018-03-30 2018-08-17 onnector tions nvelope 7 132 kV KILGORIS LOLGORIE N KIHANCHA TRANSMISSION LINE KE-KETRACO-40033-NC-RFQ / NON CONSULTANCY SERVIC ES AERIAL PHOTOGRAPHY AN A. HVDC transmission interc Request for Quota Single Stage - One E D MAPPING SERVICES FOR M IDA / 51480 Post Limited 375,900.00 0.00 Canceled 2017-12-24 2018-02-18 2018-08-17 onnector tions nvelope ACHAKOS MWALA SARARA S OTIK NYAMIRA KILGORIS LOL GORIEN KIHANCHA TRANSMI SSION LINE KE-KETRACO-64360-NC-RFQ / NON CONSULTANCY SERVIC ES FOR CADASTRAL SURVEY A. HVDC transmission interc Request for Quota Single Stage - One E FOR KENYA ELECTRICITY TRA IDA / 51480 Post Limited 115,000.00 93,402.06 Signed 2018-06-02 2017-10-10 2018-07-28 2018-03-30 2019-01-24 onnector tions nvelope NSMISSION STRENGTHENING PROJECT LOT 3 132kV RUMU RUTI MARALAL TRANSMISSIO N LINE KE-KETRACO-330762-NC-DIR A. HVDC transmission interc Under Imple / DIRECT SELECTION OF SER IDA / 51480 Post Direct Selection Direct - National 125,000.00 0.00 2022-12-14 2022-12-07 2022-12-19 2022-12-14 2023-01-23 2023-03-23 onnector mentation VICES FOR REPAIR OF GROU ND ELECTRODE CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-KETRACO-7576-CS-QCBS / Pre-construction consultant A. HVDC transmission interc Quality And Cost- Open - Internationa IDA / 51480 Prior 6,000,000.00 0.00 Canceled 2017-02-21 2017-03-14 2017-04-27 2017-05-25 2017-06-24 2017-07-29 2017-09-02 2018-09-02 for the Kenya Electricity Tran onnector Based Selection l smission Strengthening Proje ct KE-KETRACO-25263-CS-QCB S / Safeguards Consultancy S ervices for Resettlement Acti B. Project Management and Quality And Cost- Open - Internationa on Plan (RAP) and Environme IDA / 51480 Post 500,000.00 0.00 Canceled 2017-08-21 2017-09-11 2017-10-25 2017-11-22 2017-12-22 2018-01-26 2018-03-02 2019-03-02 Capacity Building Based Selection l ntal Social Impact Assessme nt (ESIA) for Kenya Electricity Transmission Company Limit ed Strengthening Project KE-KETRACO-40034-CS-QCB S / CONSULTANCY SERVICES SAFEGUARDS CONSULTANT F OR KILIFI MALINDI MACHAKO A. HVDC transmission interc Quality And Cost- Open - Internationa S MWALA SARARA MENENGAI IDA / 51480 Prior 800,000.00 0.00 Canceled 2017-12-19 2018-01-09 2018-02-22 2018-03-22 2018-04-21 2018-05-26 2018-06-30 2019-06-30 onnector Based Selection l NYANDARUA RUMURUTI RUM URUTI MARALLAL KABARNET RUMURUTI SOTIK NYAMIRA KI LGORIS LOLGORIEN KIHANCH A TRANSMISSION LINE KE-KETRACO-66261-CS-QCB S / CONSULTANCY SERVICES DETAILED DESIGN AND BIDDI NG DOCUMENT PREPARATIO N FOR LOTS LOT 1 RUMURUTI MARALAL M A. HVDC transmission interc Quality And Cost- Open - Internationa IDA / 51480 Prior 3,250,000.00 5,104,898.14 Signed 2018-06-12 2018-07-06 2018-07-03 2018-09-25 2018-08-16 2019-02-27 2018-09-13 2019-04-15 2018-10-13 2019-08-30 2018-11-17 2019-12-19 2018-12-22 2020-01-21 2019-12-22 ENENGAI RUMURUTI onnector Based Selection l LOT 2 KABRNT RUMRTI MACK OS SALALA MLINDI KILIFI LOT 3 NEW SS MARALAL OLK U KEHANCHA SALALA MALIN DI LOT 4 EXTSS NAROK BOMET MWINGI KITALE KE-KETRACO-66941-CS-QCB S / CONSULTANCY SERVICES FOR PREPARATION OF RAP V A. HVDC transmission interc Quality And Cost- Open - Internationa MGP AND ESIA FOR TRANSMI IDA / 51480 Post 700,000.00 255,065.88 Signed 2018-06-18 2018-08-23 2018-07-09 2018-06-28 2018-08-22 2018-08-09 2018-09-19 2018-10-17 2018-10-19 2018-11-02 2018-11-23 2019-02-11 2018-12-28 2019-04-15 2019-12-28 onnector Based Selection l SSION LINES PACKAGE 1 RUMURUTI MARA LAL KILGORIS KENHANCHA B OMET NAROK SS EXT KE-KETRACO-66985-CS-QCB S / CONSULTANCY SERVICES FOR PREPARATION OF RAP V A. HVDC transmission interc Quality And Cost- Open - Internationa MGP ESIA FOR TRANSMISSIO IDA / 51480 Post 700,000.00 244,342.73 Signed 2018-06-18 2018-08-23 2018-07-09 2018-06-28 2018-08-22 2018-08-09 2018-09-19 2018-10-17 2018-10-19 2018-11-02 2018-11-23 2019-02-11 2018-12-28 2019-04-15 2019-12-28 onnector Based Selection l N LINES PACKAGE 2 KABARNET RUMU RUTI MENENGAI RUMURUTI A ND SUBSTATION EXTENSION AT KITALE KE-KETRACO-66986-CS-QCB S / CONSULTANCY SERVICES FOR PREPARATION OF RAP V MGP AND ESIA FOR TRANSMI A. HVDC transmission interc Quality And Cost- Open - Internationa IDA / 51480 Post 700,000.00 247,414.46 Signed 2018-06-18 2018-08-23 2018-07-09 2018-06-28 2018-08-22 2018-08-09 2018-09-19 2018-10-17 2018-10-19 2018-11-02 2018-11-23 2019-02-11 2018-12-28 2019-04-15 2019-12-28 SSION LINES onnector Based Selection l PACKAGE 3 MACHAKOS MWA LA SALALA MALINDI KILIFI AN D SUBSTATION EXTENSIONS KYENI MWINGI MALINDI KE-KETRACO-7554-CS-QCBS / Engineering Services for Re view of Designs, inspection o f materials, Project Supervisi A. HVDC transmission interc Quality And Cost- Open - Internationa on and Commissioning of 3n IDA / 51480 Prior 4,000,000.00 0.00 Canceled 2017-02-17 2017-02-22 2017-03-15 2017-04-12 2017-05-12 2017-06-16 2017-07-21 2018-07-21 onnector Based Selection l o. 400/220kV Substation in Ki muka, Gilgil and Lessos. The assignment will include assis tance for the implementation of Environmental Social Man KE-KETRACO-40035-CS-QCB S / CONSULTANCY SERVICES DETAILED DESIGN AND BIDDI NG DOCUMENT PREPARATIO A. HVDC transmission interc Quality And Cost- Open - Internationa N FOR POWER TRANSMISSIO IDA / 51480 Prior 3,250,000.00 0.00 Canceled 2017-12-19 2018-01-08 2018-01-09 2018-02-22 2018-03-22 2018-04-21 2018-05-26 2018-06-30 2019-06-30 onnector Based Selection l N LINES WORKS FOR KILIFI M ALINDI MENENGAI NYANDAR UA RUMURUTI RUMURUTI MA RALLAL KABARNET RUMURUT I TRANSMISSION LINE Page 2 KE-KETRACO-100262-CS-QC B. Project Management and Quality Based Sel Open - Internationa BS / CONSULTANT SERVICES IDA / 51480 Post 600,000.00 0.00 Canceled 2019-04-05 2019-04-26 2019-06-09 2019-07-07 2019-08-06 2019-09-05 2019-10-10 2020-10-09 Capacity Building ection l LIVELINE AIR MOBILE TRAINI NG KE-KETRACO-359940-CS-QC B. Project Management and Quality And Cost- Open - Internationa Under Implement BS / SUPERVISION CONSULTA IDA / 51480 Prior 3,780,000.00 0.00 2023-05-14 2023-06-04 2023-07-18 2023-08-15 2023-09-14 2023-10-19 2023-11-23 2024-11-22 Capacity Building Based Selection l ation NT FOR COMPONENT A4 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-KETRACO-100254-CS-CD B. Project Management and Pending Impleme S / CONSULTANT SERVICES F IDA / 51480 Post Direct Selection Direct 200,000.00 0.00 2019-02-12 2019-02-22 2019-04-28 2019-10-25 Capacity Building ntation OR TRAINING BY HELICOPTER SUPPLIER KE-KETRACO-216516-CS-CD S / CONSULTANCY SERVICES B. Project Management and Under Implement IDA / 51480 Post Direct Selection Direct 150,000.00 0.00 2021-01-29 2021-03-08 2021-02-08 2021-03-28 2021-04-14 2021-10-11 FOR TRAINING SYSTEMS SIM Capacity Building ation ULATION STUDIES KE-KETRACO-234798-NC-DIR / TECHNICAL ASSISTANCE AS B. Project Management and SIGNMENT FOR PROJECT RIS IDA / 51480 Post Direct Selection Direct 493,156.00 0.00 Under Review 2021-05-31 2021-05-31 2021-06-10 2021-08-14 2022-02-10 Capacity Building K AND FINANCIAL MANAGEM ENT CAPACITY BUILDING KE-KETRACO-243048-CS-CD S / CONSULTANCY SERVICES FOR STATCOM FACILITY - PH ASE I: SYSTEM STUDY, STATC OM DESIGN, TENDER DOCUM A. HVDC transmission interc Under Implement IDA / 51480 Prior Direct Selection Direct 1,000,000.00 0.00 2021-07-12 2021-09-07 2021-07-22 2021-09-30 2021-09-25 2022-03-24 ENTATION & EVALUATION (L onnector ation UMP-SUM CONTRACT); PHAS E II: SUPERVISION AND MANA GEMENT OF THE DESIGN, SU PPLY, INSTALLATION, INTEGR ATION AND COMMISSIONING (TIME-BASED) KE-KETRACO-100267-CS-CD B. Project Management and S / CONSULTANT SERVICES S IDA / 51480 Post Direct Selection Direct 150,000.00 0.00 Canceled 2019-05-21 2020-01-21 2019-05-31 2019-08-04 2020-01-31 Capacity Building YSTEM STUDIES SIMULATION STUDIES KE-KETRACO-219703-CS-CD S / CONSULTANCY SERVICES FOR STATCOM FACILITY - PH ASE I: SYSTEM STUDY, STATC OM DESIGN, TENDER DOCUM B. Project Management and IDA / 51480 Prior Direct Selection Direct 1,000,000.00 0.00 Canceled 2021-03-05 2021-06-30 2021-03-12 2021-04-17 2022-09-09 ENTATION & EVALUATION (L Capacity Building UMP-SUM CONTRACT); PHAS E II: SUPERVISION AND MANA GEMENT OF THE DESIGN, SU PPLY, INSTALLATION, INTEGR ATION AND COMMISSIONING (TIME-BASED) Page 3 INVESTING IN NUTRITION AND EARLY YEARS (INEY) Grant No. TF-0A7565 Procurement Plan Version No.: 3 Date: January 14, 2019 I. General Information 1. Project information: a. Country: Indonesia b. Recipient: Republic of Indonesia c. Project Name: Investing In Nutrition And Early Years (INEY) d. Project Implementing Agency (PIA): a. Secretariat of Vice President of the Republic of Indonesia b. Ministry of Home Affairs c. National Planning and Development Agency (Bappenas) 2. Bank’s No Objection Date of the Procurement Plan: a. Original : April 15, 2018 b. Version 1 : May 17, 2018 c. Version 2 : November, 15, 2018 d. Version 3 : January 14, 2019 3. Date of General Procurement Notice: 5 February 2019 4. Period covered by this procurement plan: Effectiveness – Loan Closing (estimated Dec 2021) II. Types of Contract, Bank’s Review Requirements and Applied Methods A. Works, Goods and Non-Consulting Services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Ref. Procureme Bank’s Review Procurement Method No. nt Method Requirement 1. International Competitive ≥ $25 million Threshold Each contract shall Bidding (Works) be subject to Bank’s prior review. 2. National Competitive $200k - $25 Each contract ≥ Bidding (Works) million $15 million equivalent shall be subject to Bank’s prior review. All other contracts 3. Shopping for Works < $200k No priorto subject post review review. (only post review). 4. International Competitive ≥$2 million Each contract ≥ $4 Bidding (Goods) million equivalent shall be subject to Bank’s prior review. All other contracts subject to post 5. National Competitive $100k - $2 review. Each contract ≥ $4 Bidding (Goods) million million equivalent shall be subject to Bank’s prior review. All other contracts subject to post 6. Shopping for Goods <100k review. No prior review (only post review). 7. International Competitive ≥$10 million Each contract shall Bidding (Non-Consultant be subject to Bank’s Service) prior review. 8. National Competitive $100k - $10 Each contract ≥ $4 Bidding (Non-Consultant million million equivalent Service) shall be subject to Bank’s prior review. All other contracts subject to post 9. Shopping for Non- <$100,000 review. No prior review Consulting Service (only post review). 10. Direct Contracting N/A Justification shall be provided when submit procurement plan. 1. Pre-qualification: Not applicable. 2. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: -NA- 3. Reference to (if any) Project Operational/Procurement Manual: Project Operations Manual of INEY 4. Any Other Special Procurement Arrangements: -NA- 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Descripti Estimat Packag Domesti Revie Commen No. on ed es c w ts Cost Prefere by (US$ nce Bank million) (yes/no) (Prior / Post) 1 Summary 11.17 8 No Prior two of the and contract NCB (Non- Post for Prior Consultan Review t Services) B. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to prior review by Bank as stated in Appendix 1 to the Guidelines for Selection and Employment of Consultants: Ref. Selection Selection Method Bank’s Prior Review No. Method Threshold Requirement 1. Competitive ≥$300,000 Each contract ≥ Method (Firms) $2,000,000 equivalent QCBS, QBS, shall be subject to LCS, FBS Bank’s prior review. All other contracts subject to post review. 2. Competitive <$300,000 Each contract ≥ Methods (Firms) $2,000,000 equivalent QCS shall be subject to Bank’s prior review. All other contracts subject to post review. 3. Individual Competitive Selection by None, except for Consultant comparing at least three procurement specialist CVs and specific position as indicated in this 4. Single Source N/A procurement Justification plan. shall be (Firms and provided when submit Individual) procurement plan. 2. Short list comprising entirely of national consultants: Short list of consultants for services (firms), estimated to cost less than $ 400,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: N/A 4. Summary of Consultancy Assignments with Selection Methods and Time Schedule during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref Descripti Type of Estimat Packag Revie Commen . on of Assignme ed es/Posit w ts No. Assignme nts Cost ions by nts (US$ Bank million) (Prior / Post) 1. Firms to (Time- 2,910.0 1 Prior MOHA provide Based) 0 technical assistance at provinces to support districts’ convergen ce actions 2. Summary (Time- 83.35 6 Post Setwapres of number Based) & of Bappenas individual consultant contracts that will be let under competitiv e selection 3 Summary (Time- 295.03 4 Post Setwapres of number Based & of study /Lump- Bappenas activity Sum) contracts that will be let under CQS PROCUREMENT Indonesia : Investing in Nutrition and Early Years PLAN General Information Country: Indonesia 2023-05-30 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164686 GPN Date: 2021-06-24 Project Name: Investing in Nutrition and Early Years Loan / Credit No: TF / A7565 Direktorat Pengembangan Sosial Budaya dan Lingkungan Desa dan Perdesaaan, Kemendesa PDTT Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-DITJEN PDP-356164-NC-R FQ / EO for Strengthening the Request for Quota Single Stage - One E Pending Impl Role and Capacity of District TF / A7565 Post Limited 14,502.00 0.00 2023-05-02 2023-05-28 2023-07-27 tions nvelope ementation Stakeholders in Accelerating the Reduction of Stunting in Villages ID-DITJEN PDP-356167-NC-R FQ / EO for Technical Guidan Request for Quota Single Stage - One E Pending Impl TF / A7565 Post Limited 32,226.00 0.00 2023-05-02 2023-05-28 2023-08-26 ce for Actors in Villages to Ac tions nvelope ementation celerate Stunting Reduction i n Villages and e-HDW CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-DITJEN PDP-355668-CS-IN Individual Consult Pending Impleme TF / A7565 Post Limited 12,413.00 0.00 2023-03-10 2023-03-10 2023-03-28 2023-04-03 2023-12-31 DV / Data Management Expe ant Selection ntation rt ID-DITJEN PDP-355667-CS-IN Individual Consult Pending Impleme TF / A7565 Post Limited 14,069.00 0.00 2023-03-10 2023-03-16 2023-04-03 2023-04-11 2023-12-31 DV / Secretariat Team Leader ant Selection ntation ID-DITJEN PDP-355669-CS-IN Individual Consult Pending Impleme DV / Community Empowerme TF / A7565 Post Limited 12,413.00 0.00 2023-03-10 2023-03-10 2023-03-28 2023-04-03 2023-12-31 ant Selection ntation nt and Public Policy Expert ID-DITJEN PDP-356145-CS-IN Individual Consult Pending Impleme TF / A7565 Post Limited 8,275.00 0.00 2023-03-10 2023-03-10 2023-03-28 2023-04-03 2023-12-31 DV / Finance and Invoice Exp ant Selection ntation ert ID-DITJEN PDP-356155-CS-IN Individual Consult Pending Impleme TF / A7565 Post Limited 8,275.00 0.00 2023-03-10 2023-03-10 2023-03-28 2023-04-03 2023-12-31 DV / Budget and Procuremen ant Selection ntation t Expert ID-DITJEN PDP-356160-CS-IN Individual Consult Pending Impleme TF / A7565 Post Limited 16,552.00 0.00 2023-03-10 2023-03-10 2023-03-28 2023-04-03 2023-12-31 DV / IT and MIS Experts ant Selection ntation ID-DITJEN PDP-356158-CS-IN Individual Consult Pending Impleme TF / A7565 Post Limited 8,275.00 0.00 2023-03-10 2023-03-10 2023-03-28 2023-04-03 2023-12-31 DV / Training/Capacity Buildi ant Selection ntation ng Expert ID-DITJEN PDP-356162-CS-IN Individual Consult Pending Impleme TF / A7565 Post Limited 8,275.00 0.00 2023-03-10 2023-03-10 2023-03-28 2023-04-03 2023-04-30 DV / Management Knowledge ant Selection ntation Expert Page 1 PROCUREMENT PLAN Project information: Federal Republic of Ethiopia, The Republic of Madagascar, The Intergovernmental Authority of Development (IGAD), the Centre for Coordination of Agricultural Research and Development for Southern Africa (CCARDESA) Food System Resilience Program for Eastern and Southern Africa Phase 1 P178566 Project Implementation agency: Ministry of Agriculture (Ethiopia) Date of the Procurement Plan: October 13, 2022 Period covered by this Procurement Plan: October 2022 to June 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Proclamation No. 649/2009, The Ethiopian Federal Government Procurement and Property Administration Proclamation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. 1)Ensure bidding opportunities are open to all contractors/Suppliers and service providers When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods Not Applicable Works Not Applicable Other Relevant Procurement Information. The project envisages procurement activities that will be implemented through CDD arrangement following the CDD Procurement manual which will be prepared by the client agreed with the Bank . PROCUREMENT Eastern and Southern Africa : Food Systems Resilience Program for Eastern and Southern Africa PLAN General Information Country: Eastern and Southern Africa 2023-05-30 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178566 GPN Date: 2022-10-21 Project Name: Food Systems Resilience Program for Eastern and Southern Africa Loan / Credit No: IDA / 71560 Benishangul-Gumuz Region Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-BG FSRP-360383-GO-RFQ / Procurement of ICT Equipm Request for Quota Single Stage - One E Pending Impl ent (12 Lap top computer,2 p IDA / 71560 Project Management Post Limited 45,000.00 0.00 2023-05-23 2023-07-18 2023-08-17 tions nvelope ementation rinter, 4 LCD projector, 4 sca nner and 4 Photocopy machi ne) ET-BG FSRP-360387-GO-RFQ (Re-)building Resilient Agric Request for Quota Single Stage - One E Pending Impl IDA / 71560 Post Limited 24,000.00 0.00 2023-05-29 2023-07-24 2023-08-23 / Procurement of Motorcycle ulture Production Capacity tions nvelope ementation ET-BG FSRP-360389-GO-RFQ Request for Quota Single Stage - One E Pending Impl IDA / 71560 Project Management Post Limited 10,000.00 0.00 2023-05-29 2023-07-24 2023-08-23 / Procurement of Office Furni tions nvelope ementation ture ET-BG FSRP-360391-GO-RFQ (Re-)building Resilient Agric Request for Quota Single Stage - One E Pending Impl / Procurement of GPS and Di IDA / 71560 Post Limited 9,500.00 0.00 2023-06-05 2023-07-31 2023-08-28 ulture Production Capacity tions nvelope ementation gital Camera NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-BG FSRP-357445-CS-IND Individual Consult IDA / 71560 Project Management Prior Open - National 24,000.00 0.00 Under Review 2023-06-08 2023-07-27 2023-08-17 2023-09-21 2025-09-20 V / To hire/recruit Procureme ant Selection nt specialist Page 1 PLAN DE ADQUISICIONES Información del proyecto: IP, Afro and Montubio Devt Project Agencia implementadora del Proyecto: Multiple Fecha del Plan de adquisiciones: Abril 2022 Período cubierto por este Plan de Adquisiciones: 2022 al Cierre del proyecto Preámbulo De conformidad con el párrafo 5.9 de las "Regulaciones de Adquisición del Banco Mundial para prestatarios IPF" ("Regulaciones de Adquisiciones") el Sistema de seguimiento en Adquisiciones (STEP) será utilizado para preparar, aclarar y actualizar los Planes de Adquisiciones y realizar todas las transacciones de adquisiciones para el Proyecto. Esta parte del texto, junto con las tablas del Plan de Adquisiciones en STEP constituyen el Plan de Adquisiciones para el Proyecto. Las siguientes condiciones aplican a todas las actividades de adquisición en el Plan de Adquisiciones. Los otros elementos del Plan de Adquisiciones como se exigen en el apartado 4.4 de las Regulaciones de Adquisiciones se exponen en el STEP. Documentos Estándar de Adquisiciones del Banco: Se utilizarán para todos los contratos sujetos a competencia internacional y los contratos así especificados en las tablas Plan de Adquisiciones de STEP. Disposiciones Nacionales de Adquisición: De conformidad con el párrafo 5.3 de las Regulaciones de Adquisiciones, cuando el enfoque es el mercado nacional (como se especifica en las tablas del Plan de Adquisiciones de STEP), se utilizarán documentos acordados con el Banco Mundial los cuales forman parte del Manual de Operaciones del Proyecto y se aplicarán las Regulaciones de Adquisiciones del Banco Mundial y no la Ley de Contrataciones del Estado de Ecuador. PROCUREMENT Ecuador : Territorial Economic Empowerment for the Indigenous, Afro-Ecuadorians and Montubian Peoples and Nationalities (TEEIPAM) PLAN General Information Country: Ecuador Bank’s Approval Date of the Original Procurement Plan: 2022-10-03 Revised Plan Date(s): (comma delineated, leave blank if 2023-05-25 none) Project ID: P173283 GPN Date: 2022-05-11 Project Name: Territorial Economic Empowerment for the Indigenous, Afro-Ecuadorians and Montubian Peoples and Nationalities (TEEIPAM) Loan / Credit No: IBRD / 91630 National Institute of Popular and Solidarity Economy Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual B-IEPS-0001-2022 / Adquisici Component 4: Project Admin Single Stage - One E Under Imple on de bienes informaticos pa IBRD / 91630 istration, Communication, an Post Request for Bids Open - National 33,470.00 0.00 2023-05-05 2023-06-20 2023-05-08 2023-06-21 2023-05-15 2023-05-19 2023-05-24 2023-06-08 nvelope mentation ra la operacion de las UIP d Monitoring and Evaluation B-IEPS-0002-2022 / Adquisici Component 4: Project Admin Request for Quota Single Stage - One E Under Imple on de suministros de oficina IBRD / 91630 istration, Communication, an Post Open - National 5,232.72 0.00 2023-05-15 2023-06-13 2023-07-10 2024-01-06 tions nvelope mentation para la operacion de las UIP d Monitoring and Evaluation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NC-IEPS-0001-2022 / Contrat Component 4: Project Admin acion de servicio de manteni Request for Quota Single Stage - One E Pending Impl IBRD / 91630 istration, Communication, an Post Open - National 15,000.00 0.00 2023-05-27 2023-07-22 2023-11-19 miento y reparacion vehiculo tions nvelope ementation d Monitoring and Evaluation s para la operacion de las UIP NC-IEPS-0001-2023 / CONTR Component 4: Project Admin ATACIÓN DE SERVICIOS DE A Pending Impl IBRD / 91630 istration, Communication, an Post Direct Selection Direct - National 4,000.00 0.00 2023-06-05 2023-06-19 2023-07-04 2023-11-01 BASTECIMIENTO DE COMBUS ementation d Monitoring and Evaluation TIBLE DE LAS UIPS A NIVEL N ACIONAL CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-IEPS-0002-2022 / Consult Component 4: Project Admin Individual Consult Under Implement oria para el Especialista Fina IBRD / 91630 istration, Communication, an Post Open - National 115,155.00 0.00 2022-09-29 2022-10-05 2022-10-28 2023-03-09 2022-11-02 2023-03-09 2022-11-08 2026-12-31 ant Selection ation nciero de la UIP Central del IE d Monitoring and Evaluation PS CI-IEPS-0003-2022 / Consult Component 4: Project Admin Individual Consult oria para el Analista en Adqui IBRD / 91630 istration, Communication, an Prior Open - National 83,771.00 0.00 Canceled 2022-09-29 2022-10-07 2022-10-28 2022-11-02 2022-11-08 2026-12-31 ant Selection siciones de la UIP Central del d Monitoring and Evaluation IEPS CI-IEPS-0004-2022 / Consult Component 4: Project Admin oria para el Analista de Capa Individual Consult Under Implement IBRD / 91630 istration, Communication, an Post Open - National 83,771.00 0.00 2022-09-29 2022-10-05 2022-10-28 2023-03-10 2022-11-02 2023-03-10 2022-11-08 2026-12-31 citacion y Fortalecimiento de ant Selection ation d Monitoring and Evaluation la UIP Central del IEPS CI-IEPS-0005-2022 / Consult Component 4: Project Admin Individual Consult Under Implement oria para el Analista de Inclus IBRD / 91630 istration, Communication, an Post Open - National 83,771.00 0.00 2022-09-29 2022-10-05 2022-10-28 2023-03-10 2022-11-02 2023-03-10 2022-11-08 2026-12-31 ant Selection ation ion Financiera de la UIP Centr d Monitoring and Evaluation al del IEPS CI-IEPS-0006-2022 / Consult Component 4: Project Admin Individual Consult Under Implement oria para el Analista Contable IBRD / 91630 istration, Communication, an Post Open - National 83,771.00 0.00 2022-09-29 2022-10-05 2022-10-28 2023-03-10 2022-11-02 2023-03-10 2022-11-08 2026-12-31 ant Selection ation de la UIP Central del IEPS d Monitoring and Evaluation CI-IEPS-0008-2022 / Consult Component 4: Project Admin Individual Consult Under Implement oria para el Analista de Econ IBRD / 91630 istration, Communication, an Post Open - National 83,771.00 0.00 2022-09-29 2022-10-05 2022-10-28 2023-03-17 2022-11-02 2023-03-17 2022-11-08 2026-12-31 ant Selection ation omias Comunitarias de la UIP d Monitoring and Evaluation Central del IEPS CI-IEPS-0009-2022 / Consult Component 4: Project Admin Individual Consult Under Implement oria para el Analista de Empl IBRD / 91630 istration, Communication, an Post Open - National 83,771.00 0.00 2022-09-29 2022-10-05 2022-10-28 2023-03-10 2022-11-02 2023-03-10 2022-11-08 2026-12-31 ant Selection ation eo de la UIP Central del IEPS d Monitoring and Evaluation CI-IEPS-0010-2022 / Consult Component 4: Project Admin Individual Consult Under Implement oria para el Asistente Admini IBRD / 91630 istration, Communication, an Post Open - National 42,802.00 0.00 2022-09-29 2022-10-05 2022-10-28 2023-03-10 2022-11-02 2023-03-10 2022-11-08 2026-12-31 ant Selection ation strativo de la UIP Central del d Monitoring and Evaluation IEPS CI-IEPS-0011-2022 / Consult Component 4: Project Admin Individual Consult Under Implement oria para el Analista de Desar IBRD / 91630 istration, Communication, an Post Open - National 83,771.00 0.00 2022-09-29 2022-10-05 2022-10-28 2023-03-10 2022-11-02 2023-03-10 2022-11-08 2026-12-31 ant Selection ation rollo Productivo UIP territorial d Monitoring and Evaluation Ibarra CI-IEPS-0012-2022 / Consult Component 4: Project Admin Individual Consult Under Implement oria para el Analista de Empl IBRD / 91630 istration, Communication, an Post Open - National 83,771.00 0.00 2022-09-29 2022-10-05 2022-10-28 2023-03-10 2022-11-02 2023-03-10 2022-11-08 2026-12-31 ant Selection ation eo e Inclusion Financiera UIP d Monitoring and Evaluation territorial Ibarra Page 1 CI-IEPS-0013-2022 / Consult Component 4: Project Admin Individual Consult Under Implement oria para el Analista de Desar IBRD / 91630 istration, Communication, an Post Open - National 83,771.00 0.00 2022-09-29 2022-10-05 2022-10-28 2023-03-10 2022-11-02 2023-03-10 2022-11-08 2026-12-31 ant Selection ation rollo Productivo UIP territorial d Monitoring and Evaluation Guayaquil CI-IEPS-0014-2022 / Consult Component 4: Project Admin oria para el Analista de Empl Individual Consult Under Implement IBRD / 91630 istration, Communication, an Post Open - National 83,771.00 0.00 2022-09-29 2022-10-05 2022-10-28 2023-03-10 2022-11-02 2023-03-10 2022-11-08 2022-11-23 eo e Inclusion Financiera UIP ant Selection ation d Monitoring and Evaluation territorial Guayaquil CI-IEPS-0015-2022 / Consult Component 4: Project Admin Individual Consult Under Implement oria para el Analista de Desar IBRD / 91630 istration, Communication, an Post Open - National 83,771.00 0.00 2022-09-29 2022-10-05 2022-10-28 2023-03-10 2022-11-02 2023-03-10 2022-11-08 2026-12-31 ant Selection ation rollo Productivo UIP territorial d Monitoring and Evaluation Cuenca CI-IEPS-0016-2022 / Consult Component 4: Project Admin Individual Consult Under Implement oria para el Analista de Empl IBRD / 91630 istration, Communication, an Post Open - National 83,771.00 0.00 2022-09-29 2022-10-05 2022-10-28 2023-03-10 2022-11-02 2023-03-10 2022-11-08 2026-12-31 ant Selection ation eo e Inclusion Financiera UIP d Monitoring and Evaluation territorial Cuenca CI-IEPS-0017-2022 / Consult Component 4: Project Admin Individual Consult Under Implement oria para el Analista de Desar IBRD / 91630 istration, Communication, an Post Open - National 83,771.00 0.00 2022-09-29 2022-10-06 2022-10-28 2023-03-10 2022-11-02 2023-03-10 2022-11-08 2026-12-31 ant Selection ation rollo Productivo UIP territorial d Monitoring and Evaluation Portoviejo CI-IEPS-0018-2022 / Consult Component 4: Project Admin oria para el Analista de Empl Individual Consult Under Implement IBRD / 91630 istration, Communication, an Post Open - National 83,771.00 0.00 2022-09-29 2022-10-05 2022-10-28 2023-03-10 2022-11-02 2023-03-10 2022-11-08 2026-12-31 eo e Inclusión Financiera UIP ant Selection ation d Monitoring and Evaluation territorial Portoviejo CI-IEPS-0019-2022 / Consult Component 4: Project Admin Individual Consult Under Implement oria para el Analista de Desar IBRD / 91630 istration, Communication, an Post Open - National 83,771.00 0.00 2022-09-29 2022-10-05 2022-10-28 2023-03-10 2022-11-02 2023-03-10 2022-11-08 2026-12-31 ant Selection ation rollo Productivo UIP territorial d Monitoring and Evaluation Ambato CI-IEPS-0020-2022 / Consult Component 4: Project Admin oria para el Analista de Empl Individual Consult Under Implement IBRD / 91630 istration, Communication, an Post Open - National 83,771.00 0.00 2022-09-29 2022-10-05 2022-10-28 2023-03-10 2022-11-02 2023-03-10 2022-11-08 2026-12-31 eo e Inclusión Financiera UIP ant Selection ation d Monitoring and Evaluation territorial Ambato CI-IEPS-0007-2022 / Consult Component 4: Project Admin oria para el Especialista en M Individual Consult Under Implement IBRD / 91630 istration, Communication, an Post Open - National 115,155.00 0.00 2022-09-29 2022-10-12 2022-10-28 2023-03-10 2022-11-02 2023-03-10 2022-11-08 2026-12-31 onitoreo y Evaluacion de la U ant Selection ation d Monitoring and Evaluation IP Central del IEPS CI-IEPS-0001-2022 / Consult Component 4: Project Admin Individual Consult Under Implement oria para el Coordinador Téc IBRD / 91630 istration, Communication, an Post Open - National 115,155.00 0.00 2022-09-29 2022-10-12 2022-10-28 2023-03-10 2022-11-02 2023-03-10 2022-11-08 2026-12-31 ant Selection ation nico Operativo de la UIP Cent d Monitoring and Evaluation ral del IEPS CI-IEPS-0001-2023 / CONSUL Component 4: Project Admin TORIA PARA EL ANALISTA DE Individual Consult Under Implement IBRD / 91630 istration, Communication, an Prior Open - National 65,445.66 0.00 2023-06-02 2023-06-06 2023-07-01 2023-07-06 2023-07-16 2026-12-31 ADQUISICIONES DE LA UIP CE ant Selection ation d Monitoring and Evaluation NTRAL DEL IEPS. Page 2 PROCUREMENT PLAN (Textual Part) Climate Resilience and Water Security in Angola - RECLIMA (P177004) Project Implementation agency: Financial and Contract Management Unit (FCMU) Date of the Procurement Plan: July 2022 Period covered by this Procurement Plan: July – December 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. - Not Applicable. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). - Not Applicable Other Relevant Procurement Information: None. PROCUREMENT Angola : Climate Resilience and Water Security in Angola-RECLIMA PLAN General Information Country: Angola 2022-07-29 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P177004 GPN Date: Project Name: Climate Resilience and Water Security in Angola-RECLIMA Loan / Credit No: IBRD / 93700 National Directorate of Water Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 8CS2/UCP/R/23 / Regional W Strengthening Water Resour Quality And Cost- Open - Internationa Pending Impleme IBRD / 93700 Post 1,500,000.00 0.00 2023-05-22 2023-06-12 2023-07-26 2023-08-23 2023-09-22 2023-10-27 2023-12-01 2024-11-30 ater Availability and Harvesti ces Management for Climate Based Selection l ntation ng Study Resilience INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 1CS3/UCP/R/2022 / Senior T Individual Consult Open - Internationa IBRD / 93700 Project Management Prior 430,000.00 0.00 Canceled 2022-12-19 2022-08-03 2023-02-06 2023-02-27 2023-04-03 2025-04-22 echnical Subcoordinator ant Selection l 2CS3/UCP/R/2022 / Environ Individual Consult Open - Internationa Under Implement IBRD / 93700 Project Management Prior 430,000.00 0.00 2022-12-12 2022-08-02 2023-01-30 2023-02-28 2023-02-20 2023-05-05 2023-03-27 2025-04-15 mental Specialist ant Selection l ation 3CS3/UCP/R/2022 / Social S Individual Consult Open - Internationa IBRD / 93700 Project Management Prior 430,000.00 0.00 Canceled 2022-12-16 2022-08-12 2023-02-03 2023-02-24 2023-03-31 2025-04-19 pecialist ant Selection l 4CS3/UCP/R/2022 / Procure Individual Consult Open - Internationa IBRD / 93700 Project Management Prior 430,000.00 0.00 Canceled 2022-12-19 2022-08-02 2023-02-06 2023-02-27 2023-04-03 2025-04-22 ment Officer ant Selection l 3ACS3/UCP/R/2022 / Social S Individual Consult Under Implement IBRD / 93700 Project Management Prior Direct - National 430,000.00 0.00 2022-12-19 2022-09-20 2022-12-29 2022-10-05 2023-01-19 2022-10-24 2023-02-23 2025-02-22 pecialist ant Selection ation 1ACS3/UCP/R/2022 / Senior Individual Consult Open - Internationa IBRD / 93700 Project Management Post 430,000.00 0.00 Signed 2023-03-22 2022-11-28 2023-05-10 2023-05-12 2023-05-31 2023-05-19 2023-07-05 2025-07-24 Technical Subcoordinator ant Selection l 5CS3/UCP/R/22 / Hydrologist Individual Consult Open - Internationa Under Implement IBRD / 93700 Project Management Post 430,000.00 0.00 2023-03-10 2022-12-22 2023-04-28 2023-06-14 2023-05-19 2023-06-23 2025-06-22 /Hydrogeologist ant Selection l ation 6CS3/UCP/R/22 / Rural Wate Individual Consult Open - Internationa Under Implement IBRD / 93700 Project Management Post 430,000.00 0.00 2023-03-22 2022-12-22 2023-05-10 2023-05-31 2023-07-05 2023-09-16 r Supply Specialist ant Selection l ation 7CS3/UCP/R/22 / Water Utilit Individual Consult Open - Internationa Under Implement IBRD / 93700 Project Management Post 430,000.00 0.00 2023-03-28 2023-02-01 2023-05-16 2023-06-06 2023-07-11 2024-01-07 y Management Specialist ant Selection l ation 4ACS3/UCP/R/23 / Procurem Individual Consult Open - Internationa Under Implement IBRD / 93700 Project Management Post 430,000.00 0.00 2023-04-10 2023-03-14 2023-05-29 2023-06-19 2023-07-24 2025-08-12 ent Officer ant Selection l ation Page 1 STRENGTHENING DATA INFRASTRUCTURE TO CLOSE THE DIGITAL GAP IN ARGENTINA PROJECT (P178609) Requesting Unit: LCC7C Responsible Unit: IDD07/GGIVP Lending Instrument: Investment Project Financing Net commitment: 200 M PROCUREMENT Argentina : Strengthening data infrastructure to close the digital gap in Argentina Project PLAN General Information Country: Argentina 2023-02-13 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178609 GPN Date: Project Name: Strengthening data infrastructure to close the digital gap in Argentina Project Loan / Credit No: IBRD / 94550 Secretaría de Innovación Pública Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-SIP-362941-CS-QCBS / C onsultoría para el estudio de Inclusive broadband connect Quality And Cost- Under Implement la infraestructura de banda a IBRD / 94550 Post Open - National 80,000.00 0.00 2023-05-22 2023-05-29 2023-06-12 2023-07-26 2023-08-23 2023-09-22 2023-10-27 2023-12-01 2024-03-30 ivity Based Selection ation ncha, conectividad existente y demanda en localidades no conectadas. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-SIP-341488-CS-INDV / Co Project Management and Ev Individual Consult Under Implement nsultor Individual Especialist IBRD / 94550 Post Open - National 83,000.00 0.00 2023-02-15 2023-06-07 2023-03-15 2023-03-16 2023-04-01 2028-01-31 aluation ant Selection ation a en Adquisiciones AR-SIP-341489-CS-INDV / Co Project Management and Ev Individual Consult Under Implement nsultor Individual Especialist IBRD / 94550 Post Open - National 83,000.00 0.00 2023-02-15 2023-06-07 2023-03-15 2023-03-16 2023-04-01 2028-01-31 aluation ant Selection ation a Ambiental y Social AR-SIP-341732-CS-INDV / Co Project Management and Ev Individual Consult Under Implement IBRD / 94550 Post Open - National 83,000.00 0.00 2023-02-15 2023-06-07 2023-03-15 2023-03-16 2023-04-01 2028-01-31 nsultor Individual Especialist aluation ant Selection ation a Técnico AR-SIP-362936-CS-INDV / Es Individual Consult IBRD / 94550 Resilient data infrastructure Post Open - National 10,227.00 0.00 Under Review 2023-05-22 2023-05-29 2023-06-11 2023-06-13 2023-06-29 2023-10-27 pecialista individual Coordina ant Selection dor AR-SIP-342823-CS-INDV / Co nsultores Individuales para el Individual Consult Under Implement IBRD / 94550 Resilient data infrastructure Post Open - National 61,858.00 0.00 2023-05-22 2023-05-29 2023-06-11 2023-06-13 2023-06-29 2023-10-27 estudio de la demanda de Ce ant Selection ation ntros de Datos (5 puestos) Page 1 Projet de Gestion des Ressources Naturelles au Sénégal (P175915) Avance de Préparation Plan de Passation des Marchés Information sur le Projet : Projet de Gestion des Ressources Naturelles au Sénégal - P175915 Agence d’exécution du Projet : Direction de l'Environnement et des Établissements Classés du Ministère de l'Environnement et du Développement Durable Date du plan de passation des marchés : 9 septembre 2021 Période couverte par ce plan de passation des marchés : Septembre 2021 – Juin 2022 I. Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016, révisé en Novembre 2017, Aout 2018 et Novembre 2020) (“Règlement de Passation des Marchés”), le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du Projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du Projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marchés se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus dans 1 STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans le Décret No 2014-1212 du 22 septembre 2014 portant Code des Marches Publics au Sénégal, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés. Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés : « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas Travaux : ne s’applique pas Autres informations pertinentes sur la passation des marchés : « Néant » 2 PROCUREMENT Senegal : Senegal: Natural Resources Management Project PLAN General Information Country: Senegal 2023-03-24 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175915 GPN Date: 2023-04-29 Project Name: Senegal: Natural Resources Management Project Loan / Credit No: IDA / 71890, IDA / V3880 Ministry of Fisheries and Maritime Economy Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned T_SENRM/MPEM_027 / Trava Request for Bids - Component 2 - Resilience an ux de construction et de réha Single Stage - One E Works French Civi Pending Imp 2024-04-1 IDA / 71890 d productivity of the fisherie Post Request for Bids Open - National 5,518,146.00 0.00 2023-06-30 2023-07-05 2023-08-16 2023-09-15 2023-10-20 bilitation des infrastructures nvelope l Law (French) SP lementation 7 s and aquaculture sectors de débarquement et de trans D formation (en trois lots) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual F_SENRM/MPEM_027 / Acqui Component 2 - Resilience an Open - Internationa Single Stage - One E sition d'équipements techniq IDA / 71890 d productivity of the fisherie Post Request for Bids 1,070,000.00 0.00 Canceled 2023-06-08 2023-06-13 2023-07-25 2023-08-24 2023-09-28 2024-03-26 l nvelope ues s and aquaculture sectors F_SENRM/MPEM_033 / Acqui Component 4 – Project mana Request for Quota Single Stage - One E Pending Impl sition de matériels roulants p IDA / 71890 Post Open - National 165,000.00 0.00 2023-05-21 2023-07-16 2024-01-12 gement tions nvelope ementation our l'UGP MPEM du projet SE NRM F_SENRM/MPEM_034 / Acqui Component 4 – Project mana Request for Quota Single Stage - One E Pending Impl IDA / 71890 Post Limited 83,200.00 0.00 2023-05-27 2023-07-22 2024-01-18 sition matériels et mobilier d gement tions nvelope ementation e bureau F_SENRM/MPEM_036 / Acqui Component 2 - Resilience an Single Stage - One E Pending Impl sition de vedettes et de pirog IDA / 71890 d productivity of the fisherie Post Request for Bids Open - National 720,000.00 0.00 2023-07-11 2023-07-16 2023-08-27 2023-09-26 2023-10-31 2024-04-28 nvelope ementation ues (en deux lots) s and aquaculture sectors F_SENRM/MPEM_037 / Acqui Component 2 - Resilience an sition de matériels de surveill Request for Quota Single Stage - One E Pending Impl IDA / 71890 d productivity of the fisherie Post Limited 50,000.00 0.00 2023-06-04 2023-07-30 2024-01-26 ance (transmission et naviga tions nvelope ementation s and aquaculture sectors tion) pour la DPSP F_SENRM/MPEM_025 / Acqui Component 2 - Resilience an Single Stage - One E Pending Impl sition de matériels roulants ( IDA / 71890 d productivity of the fisherie Post Request for Bids Open - National 980,000.00 0.00 2023-07-05 2023-07-10 2023-08-21 2023-09-20 2023-10-25 2024-04-22 nvelope ementation véhicules et motos) s and aquaculture sectors F_SENRM/MPEM_026 / Acqui Component 2 - Resilience an sition d'équipements informa Single Stage - One E Pending Impl IDA / 71890 d productivity of the fisherie Post Request for Bids Open - National 160,000.00 0.00 2023-05-22 2023-05-27 2023-07-08 2023-08-07 2023-09-11 2024-03-09 tiques pour l'UGP et les servi nvelope ementation s and aquaculture sectors ces techniques centraux du P MEM (plusieurs lots) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual S_SENRM/MPEM_031 / Dével Component 2 - Resilience an oppement du logiciel pour la Request for Quota Single Stage - One E Pending Impl IDA / 71890 d productivity of the fisherie Post Open - National 40,000.00 0.00 2023-07-01 2023-08-26 2024-02-22 gestion et le suivi des inspect tions nvelope ementation s and aquaculture sectors ions, le contrôle et la certific ation SDP_SENRM/MPEM_038 / Sél ection directe du prestataire chargé de la migration du log Component 4 – Project mana Under Imple iciel TOM2PRO ainsi que du p IDA / 71890 Post Direct Selection Direct - National 11,500.00 0.00 2023-05-31 2023-05-26 2023-06-05 2023-07-10 2024-01-06 gement mentation aramétrage et de la formatio n du personnel, pour le proje t de Gestion des Ressources Naturelles au Sénégal (SENR M) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CF_SENRM/MPEM_013 / Séle ction d’un organisme indépe Component 2 - Resilience an Quality And Cost- Open - Internationa Under Implement ndant pour la réalisation des IDA / 71890 d productivity of the fisherie Post 330,000.00 0.00 2023-04-03 2023-04-05 2023-04-24 2023-05-12 2023-06-07 2023-07-05 2023-08-04 2023-09-08 2023-10-13 2024-10-12 Based Selection l ation évaluations à la certification s and aquaculture sectors MSC pour certaines pêcherie s artisanales CF_SENRM/MPEM_015 / Mobi lisation d’une expertise exter Component 2 - Resilience an ne pour l’élaboration et la mi Quality And Cost- Under Implement IDA / 71890 d productivity of the fisherie Post Open - National 420,000.00 0.00 2023-03-15 2023-04-05 2023-04-05 2023-05-19 2023-06-16 2023-07-16 2023-08-20 2023-09-24 2024-09-23 se en œuvre d’un programm Based Selection ation s and aquaculture sectors e de renforcement des capac ités des inspecteurs et respo nsables qualité CF_SENRM/MPEM_017 / Assis tance technique à la planifica tion de la gestion, à l’élabora Component 2 - Resilience an Quality And Cost- Open - Internationa tion et à la mise en œuvre du IDA / 71890 d productivity of the fisherie Prior 1,383,000.00 0.00 Canceled 2023-06-05 2023-06-26 2023-08-09 2023-09-06 2023-10-06 2023-11-10 2023-12-15 2024-12-14 Based Selection l programme de formation pou s and aquaculture sectors r les communautés ciblées et à l’assistance technique à la formation des GIE Page 1 CF_SENRM/MPEM_024 / Étud es pour la construction et le s Component 2 - Resilience an Quality And Cost- Under Implement uivi des pôles aquacoles (Fati IDA / 71890 d productivity of the fisherie Post Open - National 300,000.00 0.00 2023-04-12 2023-04-05 2023-05-03 2023-05-17 2023-06-16 2023-07-14 2023-08-13 2023-09-17 2023-10-22 2024-10-21 Based Selection ation ck, Thiès, Louga, Saint Louis, s and aquaculture sectors Kolda, Sédhiou, Kédougou) CF_SENRM/MPEM_009 / Révi Component 2 - Resilience an sion des EIES des infrastructu Consultant Qualifi Pending Impleme IDA / V3880 d productivity of the fisherie Post Open - National 100,000.00 0.00 2023-07-21 2023-08-11 2023-09-24 2023-10-24 2023-11-28 2024-05-26 res / élaboration de nouvelle cation Selection ntation s and aquaculture sectors s études pour les nouveaux s ites de la pêche CF_SENRM/MPEM_028 / Séle ction d'un cabinet pour le dé Component 2 - Resilience an Consultant Qualifi Pending Impleme veloppement et le déploieme IDA / 71890 d productivity of the fisherie Post Open - National 150,000.00 0.00 2023-06-12 2023-07-03 2023-08-16 2023-09-15 2023-10-20 2024-04-17 cation Selection ntation nt du système d'information s and aquaculture sectors national sur la pêche et l'aqu aculture (SINPA) CF_SENRM/PMEM_010 / Mobi lisation d’une agence d’intéri m pour le recrutement et la g Component 2 - Resilience an Quality And Cost- Pending Impleme estion des contrats des agen IDA / 71890 d productivity of the fisherie Post Open - National 660,000.00 0.00 2023-08-04 2023-08-25 2023-10-08 2023-11-05 2023-12-05 2024-01-09 2024-02-13 2025-02-12 Based Selection ntation ts communautaires en charg s and aquaculture sectors e du suivi et des relais comm unautaires en accompagnem ent des CLP/CLPA CF_SENRM/MPEM_021 / Assis tance technique pour le déve Component 2 - Resilience an loppement des pôles aquacol Quality And Cost- Open - Internationa Pending Impleme IDA / 71890 d productivity of the fisherie Post 640,000.00 0.00 2023-08-10 2023-08-31 2023-10-14 2023-11-11 2023-12-11 2024-01-15 2024-02-19 2025-02-18 es, le développement et la m Based Selection l ntation s and aquaculture sectors ise en œuvre d'un programm e de formation en aquacultur e des producteurs CF_SENRM/MPEM_004 / Assis tance technique pour la réali sation d’un diagnostic institu Component 2 - Resilience an Quality And Cost- Pending Impleme tionnel du MPEM et la mise e IDA / 71890 d productivity of the fisherie Post Open - National 510,000.00 0.00 2023-08-16 2023-09-06 2023-10-20 2023-11-17 2023-12-17 2024-01-21 2024-02-25 2025-02-24 Based Selection ntation n œuvre d’un programme de s and aquaculture sectors renforcement des capacités des agents en charge de la g estion des pêcheries aménag ées CF_SENRM/MPEM_020 / Mobi lisation d’une expertise tech nique pour réaliser une étude Component 2 - Resilience an Consultant Qualifi Open - Internationa Under Implement stratégique sur l’identificatio IDA / 71890 d productivity of the fisherie Post 250,000.00 0.00 2023-04-28 2023-04-19 2023-05-19 2023-05-12 2023-07-02 2023-08-01 2023-09-05 2024-03-03 cation Selection l ation n des zones propices à l’aqua s and aquaculture sectors culture, des aménagements structurants y relatifs et de l a planification/sécurisation d u foncier CF_SENRM/MPEM_005 / Assis tance technique pour le renfo Component 2 - Resilience an Quality And Cost- Open - Internationa Pending Impleme rcement des procédures et s IDA / 71890 d productivity of the fisherie Post 320,000.00 0.00 2023-08-02 2023-08-23 2023-10-06 2023-11-03 2023-12-03 2024-01-07 2024-02-11 2025-02-10 Based Selection l ntation ystème informatique sur la g s and aquaculture sectors estion de la flotte industrielle CF_SENRM/MPEM_014 / Séle ction d'un cabinet pour défini Component 2 - Resilience an r des opérations de suivi et d Consultant Qualifi Under Implement IDA / 71890 d productivity of the fisherie Post Open - National 230,000.00 0.00 2023-03-22 2023-04-28 2023-04-12 2023-05-26 2023-06-25 2023-07-30 2024-01-26 e contrôle pour améliorer la cation Selection ation s and aquaculture sectors qualité sanitaire des filières d e produits halieutiques ciblée s CF_SENRM/MPEM_008 / Assis tance technique pour aide à l ’identification des équipeme Component 2 - Resilience an nts de géolocalisation pour le Quality And Cost- Open - Internationa Pending Impleme IDA / 71890 d productivity of the fisherie Post 360,000.00 0.00 2023-11-27 2023-12-18 2024-01-31 2024-02-28 2024-03-29 2024-05-03 2024-06-07 2025-06-07 s pirogues (embarcations de Based Selection l ntation s and aquaculture sectors la pêche artisanale), leur inst allation et la formation du pe rsonnel pour le suivi et le trai tement des données CF_SENRM/MPEM_011 / Assis Component 2 - Resilience an Consultant Qualifi Pending Impleme tance technique pour l'élabor IDA / 71890 d productivity of the fisherie Post Open - National 157,000.00 0.00 2023-12-20 2024-01-10 2024-02-23 2024-03-24 2024-04-28 2024-10-25 cation Selection ntation ation de la documentation Fi s and aquaculture sectors TI INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI_SENREM/MPEM_029 / Elab Component 2 - Resilience an oration d'un programme nati Individual Consult Under Implement IDA / 71890 d productivity of the fisherie Post Limited 60,000.00 0.00 2023-05-04 2023-04-05 2023-05-09 2023-04-18 2023-05-30 2023-07-04 2023-12-31 onal de recherche développe ant Selection ation s and aquaculture sectors ment en aquaculture (PNRA) CI_SENRM/MPEM_030 / Acco Component 2 - Resilience an mpagnement à la mise en oe Individual Consult IDA / 71890 d productivity of the fisherie Post Limited 60,000.00 0.00 Canceled 2023-05-03 2023-05-08 2023-05-29 2023-07-03 2023-12-30 uvre des plans d'actions des ant Selection s and aquaculture sectors associations de la filière aqu acole SDF_SENRM/MPEM_032 / Sél ection directe d'un cabinet p Component 2 - Resilience an Direct - Internation Pending Impleme our le paramétrage, la forma IDA / 71890 d productivity of the fisherie Post Direct Selection 150,000.00 0.00 2023-06-15 2023-06-25 2023-08-29 2024-02-25 al ntation tion et la maintenance du Jou s and aquaculture sectors rnal de Bord Electronique (JB E) CI_SENRM/MPEM_022 / Sélec tion d'un consultant pour l'ap Component 2 - Resilience an pui à la consolidation et à la f Individual Consult Under Implement IDA / 71890 d productivity of the fisherie Post Limited 60,000.00 0.00 2023-04-20 2023-04-26 2023-04-25 2023-04-28 2023-05-16 2023-06-20 2023-12-17 ormalisation des associations ant Selection ation s and aquaculture sectors nationale et régionales des a cteurs de la filière aquacole d u Sénégal Component 2 - Resilience an CI_SENRM/MPEM_012 / Etud Individual Consult Pending Impleme IDA / 71890 d productivity of the fisherie Post Limited 50,000.00 0.00 2023-07-20 2023-07-25 2023-08-15 2023-09-19 2024-03-17 e de faisabilité des ZIRA ant Selection ntation s and aquaculture sectors CI_SENRM/MPEM_006 / Expe rtise juridique pour l’élaborat Component 2 - Resilience an ion des textes d’application p Individual Consult Pending Impleme IDA / 71890 d productivity of the fisherie Post Open - National 180,000.00 0.00 2023-07-17 2023-09-04 2023-09-25 2023-10-30 2024-04-27 our l’organisation et le foncti ant Selection ntation s and aquaculture sectors onnement des principaux mé tiers de la pêche artisanale Page 2 CI_SENRM/MPEM_016 / Mobil isation d’une expertise juridi Component 2 - Resilience an Individual Consult Pending Impleme que pour renforcer le cadre r IDA / 71890 d productivity of the fisherie Post Limited 90,000.00 0.00 2023-07-19 2023-07-24 2023-08-14 2023-09-18 2024-03-16 ant Selection ntation èglementaire relatif à la quali s and aquaculture sectors té sanitaire des produits hali eutiques CI_SENRM/MPEM_002 / Mobil isation d'une expertise juridi Component 2 - Resilience an Individual Consult Pending Impleme que pour l’élaboration des te IDA / 71890 d productivity of the fisherie Post Limited 50,000.00 0.00 2023-05-25 2023-05-30 2023-06-20 2023-07-25 2024-01-21 ant Selection ntation xtes d’application liés aux sy s and aquaculture sectors stèmes de concession et d’all ocation des droits de pêche CI_SENRM/MPEM_028 / Sélec Component 1 - Institutional tion d'un consultant individu Framework for Environment el pour la Réalisation d’une é Individual Consult Pending Impleme IDA / 71890 al and Social Risk Managem Post Limited 50,000.00 0.00 2023-07-05 2023-07-10 2023-07-31 2023-09-04 2024-03-02 tude spécifique sur l’approvis ant Selection ntation ent and Strategic Intersector ionnement durable des centr al Collaborati ons es de fumage de Diogué, Kaf ountine, Kayar et Niodor CI_SENRM/MPEM_023 / Etud Component 2 - Resilience an Individual Consult Pending Impleme es environnementale et socia IDA / 71890 d productivity of the fisherie Post Open - National 160,000.00 0.00 2023-07-03 2023-08-21 2023-09-11 2023-10-16 2024-04-13 ant Selection ntation le des Pôles aquacoles s and aquaculture sectors CI_SENRM/MPEM_001 / Étud e de faisabilité pour le dévelo Component 2 - Resilience an Individual Consult Pending Impleme ppement des systèmes de co IDA / 71890 d productivity of the fisherie Post Limited 75,000.00 0.00 2023-09-01 2023-09-06 2023-09-27 2023-11-01 2024-04-29 ant Selection ntation ncession et d’allocation des d s and aquaculture sectors roits de pêche et leur articula tion aux permis/licence CI_SENRM/MPEM_007 / Etud es stratégiques : Évaluation Component 2 - Resilience an et actualisation de la stratégi Individual Consult Pending Impleme IDA / 71890 d productivity of the fisherie Post Limited 50,000.00 0.00 2023-07-31 2023-08-05 2023-08-26 2023-09-30 2024-03-28 e d'opérationnalisation du PN ant Selection ntation s and aquaculture sectors A Pêche/Aquaculture horizon 2035, pour la période 2023-2 027 CI_SENRM/MPEM_019 / Mobil isation d’une expertise techn ique pour l'identification et l' analyse des opportunités d’in Component 2 - Resilience an Individual Consult Under Implement vestissement et de développ IDA / 71890 d productivity of the fisherie Post Open - National 100,000.00 0.00 2023-04-28 2023-04-28 2023-06-16 2023-07-07 2023-08-11 2024-02-07 ant Selection ation ement de la chaine de valeur s and aquaculture sectors aquacole au Sénégal et, subs équemment le développeme nt d'outils de communication applicables CI_SENRM/MPEM_018 / Mobil Component 2 - Resilience an isation d’une expertise juridi Individual Consult Pending Impleme IDA / 71890 d productivity of the fisherie Post Limited 50,000.00 0.00 2023-07-18 2023-07-23 2023-08-13 2023-09-17 2024-03-15 que pour le développement d ant Selection ntation s and aquaculture sectors es textes d'application du co de de l'aquaculture SDCI_SENRM/MPEM_035 / Co nsultant individuel pour l'app Component 4 – Project mana IDA / 71890 Post Direct Selection Direct - National 107,680.00 0.00 Under Review 2023-05-29 2023-05-26 2023-06-08 2023-08-12 2024-02-08 ui à la mise en œuvre des ac gement tivités de passation de march és CI_SENRM/MPEM_003 / Sélec Component 2 - Resilience an tion d'un consultant pour la Individual Consult Pending Impleme IDA / 71890 d productivity of the fisherie Post Limited 50,000.00 0.00 2023-07-25 2023-07-30 2023-08-20 2023-09-24 2024-03-22 mise en œuvre d'un program ant Selection ntation s and aquaculture sectors me de recherche sur les pêc heries aménagées Page 3 PROCUREMENT PLAN (Textual Part) Project information: Nigeria [SPESSE ][P169405] Project Implementation agency: National University Commission Date of the Procurement Plan: August 9, 2019 Period covered by this Procurement Plan: [August 9, 2019 – Jan 31, 2019] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Nigeria 2017 Procurement Act, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. None When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Goods: is not applicable Works: is not applicable Other Relevant Procurement Information. None PROCUREMENT Nigeria : Sustainable Procurement, Environmental and Social Standards Enhancement Project (SPESSE) PLAN General Information Country: Nigeria Bank’s Approval Date of the Original Procurement Plan: 2019-08-22 Revised Plan Date(s): (comma delineated, leave blank if 2023-05-29 none) Project ID: P169405 GPN Date: Project Name: Sustainable Procurement, Environmental and Social Standards Enhancement Project (SPESSE) Loan / Credit No: / , IDA / 65250, IDA / V2820 National Universities Commission Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-NUC-247295-CW-RFQ / R Component I: Technical assi Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-08-0 enovation of the Project Secr IDA / 65250 stance and Support to imple Post Limited tions (Non Bank-S 41,000.00 0.00 2021-12-11 2022-02-05 tions nvelope lementation 4 etariat menting agencies PD) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component II: Establishment NG-NUC-128742-GO-RFB / E Single Stage - One E / and operating the Centers of Post Request for Bids Open - National 1,100,000.00 0.00 Canceled 2019-09-12 2019-09-17 2019-10-29 2019-11-28 2020-01-02 2020-06-30 nterprise LMS nvelope Excellence (SPESSCE) NG-NUC-128743-GO-RFB / C Component II: Establishment Single Stage - One E entral Server and Storage for / and operating the Centers of Post Request for Bids Open - National 600,000.00 0.00 Canceled 2019-09-12 2019-09-17 2019-10-29 2019-11-28 2020-01-02 2020-06-30 nvelope LMS Excellence (SPESSCE) Component II: Establishment NG-NUC-121519-GO-RFQ / In Single Stage - One E / and operating the Centers of Post Request for Bids Open - National 680,000.00 0.00 Canceled 2019-09-15 2019-09-20 2019-11-01 2019-12-01 2020-01-05 2020-07-03 ternet Connectivity (1 GB) nvelope Excellence (SPESSCE) NG-NUC-128745-GO-RFB / L Component II: Establishment Single Stage - One E ecture Theater Communicati / and operating the Centers of Post Request for Bids Open - National 400,000.00 0.00 Canceled 2019-09-16 2019-09-21 2019-11-02 2019-12-02 2020-01-06 2020-07-04 nvelope on Infrastructure Excellence (SPESSCE) NG-NUC-127220-GO-RFP / Pr Component I: Technical assi Request for Quota Single Stage - One E Pending Impl ocuremet of IT Equipment for IDA / V2820 stance and Support to imple Post Limited 30,000.00 0.00 2020-05-11 2020-07-06 2021-01-02 tions nvelope ementation Project and Respective Desks menting agencies NG-NUC-181997-GO-RFQ / P Component I: Technical assi Request for Quota Single Stage - One E Pending Impl rocurement of Office tools Eq IDA / V2820 stance and Support to imple Post Limited 101,586.00 0.00 2020-09-29 2020-11-24 2021-05-23 tions nvelope ementation uipment menting agencies NG-NUC-181985-GO-DIR / Pr Component I: Technical assi ocurement of Learning Applic IDA / V2820 stance and Support to imple Post Direct Selection Direct 346,175.00 152,766.58 Signed 2020-08-07 2021-06-22 2020-08-12 2020-11-23 2020-09-16 2021-12-14 2021-03-15 ation Software menting agencies NG-NUC-181990-GO-DIR / Pr Component I: Technical assi ocurement of Learning Mana IDA / V2820 stance and Support to imple Post Direct Selection Direct 385,900.00 492,236.84 Signed 2020-08-10 2021-06-22 2020-08-15 2021-06-22 2020-09-19 2021-08-10 2021-03-18 gement System menting agencies NG-NUC-181918-GO-RFB / Pr Component I: Technical assi Single Stage - One E Under Imple ocurement of Electronic Doc IDA / V2820 stance and Support to imple Post Request for Bids Open - National 285,000.00 0.00 2020-09-16 2020-10-13 2020-09-21 2020-11-02 2020-12-18 2020-12-02 2021-01-06 2021-07-05 nvelope mentation ument Management System menting agencies Softwares NG-NUC-187505-GO-RFQ / P Component I: Technical assi Request for Quota Single Stage - One E Pending Impl rocurement of HRM Service S IDA / V2820 stance and Support to imple Post Limited 4,900.00 0.00 2020-09-02 2020-10-28 2021-04-26 tions nvelope ementation oftware menting agencies NG-NUC-187503-GO-RFQ / P Component I: Technical assi Request for Quota Single Stage - One E Pending Impl rocurement of E-Procuremen IDA / V2820 stance and Support to imple Post Limited 5,900.00 0.00 2020-09-02 2020-10-28 2021-04-26 tions nvelope ementation t Portal service Software menting agencies NG-NUC-198809-GO-RFQ / P Component II: Establishment Request for Quota Single Stage - One E rocurement of Anti-Plagiaris IDA / V2820 and operating the Centers of Post Limited 215,000.00 216,531.66 Completed 2020-10-27 2020-11-02 2020-12-22 2020-12-04 2021-06-20 2020-12-12 tions nvelope m Software for Centres of Ex Excellence (SPESSCE) cellence NG-NUC-203384-GO-RFB / Pr Component II: Establishment ocurement of learning Mana Single Stage - One E IDA / 65250 and operating the Centers of Post Request for Bids Open - National 651,000.00 0.00 Canceled 2020-11-19 2020-11-20 2020-11-24 2020-12-01 2021-01-05 2021-02-04 2021-03-11 2021-09-07 gement System Devices for nvelope Excellence (SPESSCE) SPESSE Centres of Excellenc e NG-NUC-203387-GO-RFB / Pr Component II: Establishment ocurement of Network Devic Single Stage - One E IDA / 65250 and operating the Centers of Post Request for Bids Open - National 230,000.00 0.00 Canceled 2020-11-19 2020-11-20 2020-11-24 2020-12-01 2021-01-05 2020-12-18 2021-02-04 2021-03-11 2021-09-07 es & Outdoor WiFi equipment nvelope Excellence (SPESSCE) for SPESSE Centres of Excelle nce NG-NUC-214086-GO-DIR / In Component II: Establishment ternet Subscription and asso IDA / V2820 and operating the Centers of Post Direct Selection Direct 1,380,236.31 1,288,219.30 Signed 2021-01-20 2021-01-15 2021-01-25 2021-02-17 2021-03-01 2021-03-05 2021-08-28 ciated facilities for SPESSE C Excellence (SPESSCE) entres of Excellence NG-NUC-236324-GO-RFB / Pr Component II: Establishment ocurement of learning Manag Single Stage - One E IDA / 65250 and operating the Centers of Post Request for Bids Open - National 651,000.00 580,222.53 Signed 2021-06-10 2021-06-10 2021-06-15 2021-06-22 2021-07-27 2021-07-07 2021-08-26 2021-10-04 2021-09-30 2021-12-10 2022-03-29 ement System Devices for SP nvelope Excellence (SPESSCE) ESSE Centres of Excellence NG-NUC-236331-GO-RFB / Pr Component II: Establishment ocurement of Network Devic Single Stage - One E IDA / 65250 and operating the Centers of Post Request for Bids Open - National 930,000.00 1,151,617.49 Signed 2021-06-10 2021-06-21 2021-06-15 2021-06-24 2021-07-27 2021-07-19 2021-08-26 2021-12-09 2021-09-30 2021-12-14 2022-03-29 es & Outdoor Wi-Fi equipmen nvelope Excellence (SPESSCE) t for SPESSE Centres of Excel lence NG-NUC-247287-GO-RFB / Pr Component I: Technical assi Single Stage - One E Pending Impl ocurement of IT Equipment f IDA / 65250 stance and Support to imple Post Request for Bids Open - National 150,000.00 0.00 2021-10-04 2021-10-09 2021-11-20 2021-12-20 2022-01-24 2022-07-23 nvelope ementation or SPESSE Project menting agencies NG-NUC-249367-GO-RFQ / P Component I: Technical assi Request for Quota Single Stage - One E Pending Impl rocurement of Project Vehicl IDA / 65250 stance and Support to imple Post Limited 159,500.00 0.00 2021-11-10 2022-01-05 2022-07-04 tions nvelope ementation es (Toyota Hilux and Toyota menting agencies Corolla) Page 1 NG-NUC-247297-GO-RFQ / P Component I: Technical assi rocurement of Power Inverter Request for Quota Single Stage - One E IDA / 65250 stance and Support to imple Post Limited 42,000.00 41,452.55 Signed 2021-10-16 2022-03-14 2021-12-11 2022-06-03 2022-06-09 Batteries and accessories for tions nvelope menting agencies the NgREN Network Centre NG-NUC-307982-GO-DIR / Su Component I: Technical assi Pending Impl pply and Installation of Anti-P IDA / 65250 stance and Support to imple Prior Direct Selection Direct - National 210,000.00 0.00 2022-08-25 2022-08-30 2022-10-04 2022-12-03 ementation lagiarism Software for Centre menting agencies s of Excellence NG-NUC-365759-GO-RFQ / M Component I: Technical assi Request for Quota Single Stage - One E Pending Impl aintenance of NgREN Networ IDA / 65250 stance and Support to imple Post Limited 26,198.00 0.00 2023-07-25 2023-09-19 2024-03-17 tions nvelope ementation k in NUC menting agencies NG-NUC-365760-GO-RFQ / L Component I: Technical assi Request for Quota Single Stage - One E Pending Impl ocal Area Network Upgrade f IDA / 65250 stance and Support to imple Post Limited 43,002.00 0.00 2023-07-15 2023-09-09 2024-03-07 tions nvelope ementation or NUC menting agencies NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-NUC-168386-NC-DIR / De Component I: Technical assi sign & Installation of Flexible IDA / V2820 stance and Support to imple Post Direct Selection Direct 117,000.00 129,810.86 Completed 2020-04-30 2020-05-25 2020-05-05 2020-05-25 2020-06-09 2020-07-09 2020-12-06 2020-09-09 Accounting Software for SPE menting agencies SSE NG-NUC-181980-NC-RFB / Pr Component I: Technical assi Single Stage - One E ocurement of Hyperconverge IDA / V2820 stance and Support to imple Post Request for Bids Limited 1,983,116.00 1,791,499.53 Signed 2020-07-24 2020-11-26 2020-07-29 2020-11-20 2020-09-09 2020-12-18 2020-10-09 2021-03-11 2020-11-13 2021-05-19 2021-05-12 nvelope d infrastructure for HPC menting agencies Component I: Technical assi NG-NUC-182003-NC-DIR / Ng IDA / V2820 stance and Support to imple Post Direct Selection Direct 111,609.00 0.00 Canceled 2020-08-04 2020-08-09 2020-09-13 2021-03-12 REN Subscription (lastmile) menting agencies Component I: Technical assi NG-NUC-247298-NC-DIR / Ng IDA / 65250 stance and Support to imple Post Direct Selection Direct 80,000.00 72,289.20 Signed 2021-12-06 2022-03-04 2021-12-11 2022-03-18 2022-01-17 2022-03-26 2022-07-16 REN subscription for the PIU menting agencies NG-NUC-247307-NC-DIR / Su Component I: Technical assi Pending Impl bscription to West and Centr IDA / 65250 stance and Support to imple Post Direct Selection Direct 50,000.00 0.00 2021-12-29 2022-01-03 2022-02-08 2022-08-07 ementation al Africa Research and Educa menting agencies tion Network NG-NUC-247309-NC-DIR / El Component I: Technical assi ectronic Platform for Perform IDA / 65250 stance and Support to imple Post Direct Selection Direct 57,000.00 0.00 Signed 2021-12-10 2022-08-02 2021-12-15 2022-08-12 2022-01-20 2022-07-19 ance Monitoring of CEs verifi menting agencies cation and reporting NG-NUC-308192-NC-DIR / Su Component I: Technical assi bscription to West and Centr Pending Impl IDA / 65250 stance and Support to imple Post Direct Selection Direct - National 50,000.00 0.00 2022-09-15 2022-09-20 2022-10-25 2023-04-23 al Africa Research and Educa ementation menting agencies tion Network (WACREN) for 2 023 NG-NUC-308197-NC-DIR / Ng Component I: Technical assi Pending Impl REN Subscription for the PIU IDA / 65250 stance and Support to imple Post Direct Selection Direct - National 100,000.00 0.00 2022-09-27 2022-10-02 2022-11-06 2023-05-05 ementation for year 2023 menting agencies Component I: Technical assi NG-NUC-365754-NC-DIR / Ng Pending Impl IDA / 65250 stance and Support to imple Post Direct Selection Direct - National 52,926.00 0.00 2023-06-30 2023-07-05 2023-08-09 2024-02-05 REN Subscription for the PIU ementation menting agencies CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NUC-SPESSE/C/CQS/04/19 / Component I: Technical assi Consultancy Services for the Consultant Qualifi IDA / V2820 stance and Support to imple Post Limited 78,000.00 60,891.94 Completed 2019-10-06 2020-03-23 2019-10-20 2020-05-25 2019-11-19 2020-07-07 2019-12-24 2020-07-09 2020-06-21 2020-11-11 Preparation of Project Imple cation Selection menting agencies mentation Manual (PIM) for S PESSE Project NUC-SPESSE/C/CQS/02/20 / Component I: Technical assi Consultancy Service for the P Consultant Qualifi IDA / V2820 stance and Support to imple Post Limited 30,000.00 0.00 Canceled 2020-03-17 2020-03-25 2020-03-31 2020-04-30 2020-06-04 2020-12-01 roduction of Documentary on cation Selection menting agencies (SPESSE) Project NG-NUC-127213-CS-CQS / C Component II: Establishment Consultant Qualifi onsultancy Services on Need / and operating the Centers of Post Limited 310,000.00 0.00 Canceled 2019-08-14 2019-04-15 2019-08-28 2019-09-27 2019-11-01 2020-04-29 cation Selection s Assessment Excellence (SPESSCE) NG-NUC-121510-CS-CQS / C Component II: Establishment Consultant Qualifi onsultancy Services on Dema / and operating the Centers of Post Limited 295,000.00 0.00 Canceled 2019-07-10 2019-04-10 2019-07-10 2019-08-01 2019-08-06 2020-02-02 cation Selection nd Assessment Excellence (SPESSCE) NG-NUC-236335-CS-QCBS / Component I: Technical assi Quality And Cost- Open - Internationa Engagement of Independent IDA / 65250 stance and Support to imple Post 500,000.00 512,265.93 Signed 2021-06-15 2021-06-09 2021-07-06 2022-01-13 2021-08-19 2021-10-19 2021-09-16 2021-11-23 2021-10-16 2021-12-08 2021-11-20 2021-12-14 2021-12-25 2022-01-12 2022-12-25 Based Selection l Verification Agent menting agencies NG-NUC-247299-CS-LCS / En Component I: Technical assi Least Cost Selecti Pending Impleme gagement of External Auditor IDA / 65250 stance and Support to imple Post Open - National 20,000.00 0.00 2021-09-30 2021-10-21 2021-12-04 2022-01-01 2022-01-31 2022-03-07 2022-04-11 2022-10-08 on ntation for the audit of 2021 Financia menting agencies l year NG-NUC-247301-CS-CQS / Pr Component I: Technical assi Consultant Qualifi Pending Impleme oduction of a documentary fo IDA / 65250 stance and Support to imple Post Limited 50,000.00 0.00 2021-12-10 2021-12-24 2022-01-23 2022-02-27 2022-08-26 cation Selection ntation r SPESSE Project menting agencies NG-NUC-247306-CS-CQS / E Component I: Technical assi Consultant Qualifi Pending Impleme ngagement of Consultant for IDA / 65250 stance and Support to imple Post Limited 150,000.00 0.00 2021-10-20 2021-11-03 2021-12-03 2022-01-07 2023-12-28 cation Selection ntation SPESSE Campaign for Chang menting agencies e INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 Component I: Technical assi NG-NUC-121512-CS-INDV / I Individual Consult / stance and Support to imple Post Open 30,296.00 0.00 Canceled 2019-10-14 2019-12-02 2019-12-23 2020-01-27 2020-07-25 CT Consultant on LMS ant Selection menting agencies NG-NUC-121514-CS-INDV/02 Component I: Technical assi /19 / Consultancy Services fo Individual Consult IDA / 65250 stance and Support to imple Post Open 38,950.00 46,962.83 Signed 2019-08-28 2019-09-01 2019-10-16 2020-02-07 2019-11-06 2020-03-12 2019-12-11 2020-06-29 2020-06-08 r the engagement of Lead Hi ant Selection menting agencies gher Education Specialist for SPESSE Project NG-NUC-121514-CS-INDV/05 Component I: Technical assi /19 / Consultancy Services fo Individual Consult / stance and Support to imple Post Open 38,950.00 99,990.00 Signed 2019-09-04 2019-09-01 2019-10-23 2020-02-07 2019-11-13 2020-03-19 2019-12-18 2020-03-24 2020-06-15 r the engagement of Lead IC ant Selection menting agencies T Specialist for SPESSE Proje ct NG-NUC-128749-CS-INDV / C Component II: Establishment onsultancy Services for the E Individual Consult / and operating the Centers of Post Open 38,950.00 0.00 Canceled 2019-09-04 2019-09-03 2019-10-23 2019-11-13 2019-12-18 2020-06-15 ngagement of Centres of Exc ant Selection Excellence (SPESSCE) ellence Monitoring Specialist for SPESSE Project NG-NUC-127246-CS-INDV / E Component I: Technical assi ngagement of a Senior Educa Individual Consult / stance and Support to imple Post Open 25,967.00 0.00 Canceled 2019-11-05 2019-11-28 2019-12-24 2020-01-14 2020-02-18 2020-08-16 tion Specialist ( Social Standa ant Selection menting agencies rd) for SPESSE Project NG-NUC-127238-CS-INDV / C Component I: Technical assi onsultancy Services for the E Individual Consult / stance and Support to imple Prior Direct 62,755.00 613,173.38 Signed 2019-08-14 2019-06-21 2019-08-24 2019-06-21 2019-09-14 2019-06-21 2019-10-19 2019-06-25 2020-04-16 ngagement of Project Coordi ant Selection menting agencies nator for SPESSE Project NG-NUC-127250-CS-INDV / E Component I: Technical assi Individual Consult ngagement of a Content Spe / stance and Support to imple Post Open 25,967.00 0.00 Signed 2019-11-11 2019-11-28 2019-12-30 2020-02-10 2020-01-20 2021-12-21 2020-02-24 2020-08-22 ant Selection cialist for SPESSE Project menting agencies NG-NUC-127248-CS-INDV / E Component I: Technical assi ngagement of an Education S Individual Consult / stance and Support to imple Post Open 25,967.00 0.00 Canceled 2019-11-05 2019-11-28 2019-12-24 2020-01-14 2020-02-18 2020-08-16 pecialist for Environmental S ant Selection menting agencies tandards for SPESSE NG-NUC-127252-CS-INDV / E Component I: Technical assi ngagement of a Computer an Individual Consult Under Implement / stance and Support to imple Post Open 25,967.00 0.00 2019-11-11 2019-11-28 2019-12-30 2020-01-20 2020-02-24 2020-08-22 d Communication Egineer for ant Selection ation menting agencies SPESSE Project NG-NUC-127247-CS-INDV / E Component I: Technical assi ngagement of a Senior Educa Individual Consult / stance and Support to imple Post Open 25,967.00 0.00 Canceled 2019-11-05 2019-11-28 2019-12-24 2020-01-14 2020-02-18 2020-08-16 tion Specialist (Procurement) ant Selection menting agencies for SPESSE Project NG-NUC-127239-CS-INDV / C Component I: Technical assi onsultancy Services for the E Individual Consult IDA / V2820 stance and Support to imple Post Direct 41,115.00 169,868.89 Signed 2019-08-14 2019-06-20 2019-08-24 2019-06-28 2019-09-14 2019-07-26 2019-10-19 2019-07-27 2020-04-16 ngagement of Senior Procure ant Selection menting agencies ment Specialist for SPESSE Pr oject NG-NUC-168389-CS-CDS / C Component I: Technical assi onsultancy Services for the E IDA / V2820 stance and Support to imple Prior Direct Selection Direct 74,000.00 0.00 Canceled 2020-04-28 2020-05-21 2020-05-08 2020-07-12 2021-01-08 ngagement of Project Imple menting agencies mentation Support Consultan tI NG-NUC-168390-CS-CDS / C Component I: Technical assi onsultancy Services for the E Under Implement IDA / V2820 stance and Support to imple Post Direct Selection Direct 45,000.00 0.00 2020-04-29 2020-05-18 2020-05-09 2020-07-13 2021-01-09 ngagement of Project Imple ation menting agencies mentation Support Consultan t II NG-NUC-121514-CS-INDV/03 Component II: Establishment /19 / Consultancy Services fo Individual Consult Pending Impleme IDA / V2820 and operating the Centers of Post Direct 100,000.00 0.00 2019-08-14 2019-08-24 2019-09-14 2019-10-19 2020-04-16 r the Selection of Centers of ant Selection ntation Excellence (SPESSCE) Excellence for SPESSE Projec t NG-NUC-181227-CS-CDS / C Component I: Technical assi onsultancy Services for the E IDA / V2820 stance and Support to imple Post Direct Selection Direct 74,000.00 59,221.70 Signed 2020-06-23 2020-06-25 2020-07-03 2020-05-25 2020-09-06 2020-06-03 2021-03-05 ngagement of Project Imple menting agencies mentation Support Consultan tI NG-NUC-127249-CS-INDV / E Component I: Technical assi ngagement of a Student Infor Individual Consult / stance and Support to imple Post Open 25,967.00 0.00 Canceled 2019-11-11 2019-11-28 2019-12-30 2020-01-20 2020-02-24 2020-08-22 mation System Specialist for ant Selection menting agencies SPESSE Project NG-NUC-121514-CS-INDV/04 Component I: Technical assi /19 / Consultancy Services fo Individual Consult / stance and Support to imple Prior Open 30,300.00 0.00 Canceled 2019-08-23 2019-09-20 2019-10-11 2019-11-01 2019-12-06 2020-06-03 r the engagement of Procure ant Selection menting agencies ment Officer for SPESSE Proj ect NG-NUC-127241-CS-INDV / E Component I: Technical assi Individual Consult ngagement of Project Accoun / stance and Support to imple Post Direct 30,295.00 0.00 Canceled 2019-08-23 2019-09-03 2019-09-02 2019-09-23 2019-10-28 2020-04-25 ant Selection tant menting agencies NG-NUC-121514-CS-INDV/01 Component I: Technical assi /19 / Consultancy Services fo Individual Consult / stance and Support to imple Post Open 34,630.00 0.00 Canceled 2019-08-28 2019-09-01 2019-10-16 2019-11-06 2019-12-11 2020-06-08 r the engagement of Commu ant Selection menting agencies nication Officer for SPESSE Pr oject NG-NUC-127242-CS-INDV / E Component I: Technical assi Individual Consult ngagement of Finance Office / stance and Support to imple Post Limited 17,312.00 0.00 Canceled 2019-08-25 2019-08-30 2019-09-20 2019-10-25 2020-04-22 ant Selection r menting agencies NG-NUC-187504-CS-CDS / C onsultancy Services for the r eview and Development of tr Component I: Technical assi aining Modules in Procureme IDA / V2820 stance and Support to imple Prior Direct Selection Direct 251,000.00 250,155.00 Signed 2020-08-20 2020-08-06 2020-08-30 2020-08-08 2020-11-03 2020-08-16 2021-05-02 nt at Entry and Practitioners’ menting agencies levels and Review of Curricul um Design related to the Aca demic Degrees’ levels in Nig eria Component II: Establishment NG-NUC-127218-CS-INDV / C Individual Consult IDA / V2820 and operating the Centers of Post Direct 100,000.00 0.00 Canceled 2019-08-19 2019-08-29 2019-09-19 2019-10-24 2020-04-21 urriculum Development ant Selection Excellence (SPESSCE) NG-NUC-247303-CS-INDV / E Component I: Technical assi ngagement of Gender Based Individual Consult Under Implement IDA / 65250 stance and Support to imple Post Limited 65,000.00 0.00 2021-09-17 2023-03-14 2021-09-22 2021-10-13 2021-11-17 2022-11-12 Violence (GBV) Specialist for ant Selection ation menting agencies SPESSE Project Page 3 NG-NUC-247304-CS-INDV / E Component I: Technical assi Individual Consult Pending Impleme ngagement of Assistant Gen IDA / 65250 stance and Support to imple Post Limited 30,000.00 0.00 2021-09-24 2021-09-29 2021-10-20 2021-11-24 2022-11-19 ant Selection ntation der Based Violence Specialist menting agencies NG-NUC-247305-CS-INDV / E Component I: Technical assi Individual Consult Pending Impleme ngagement of Procurement A IDA / 65250 stance and Support to imple Post Limited 20,000.00 0.00 2021-09-24 2021-09-29 2021-10-20 2021-11-24 2022-11-19 ant Selection ntation ssistant menting agencies NG-NUC-307984-CS-INDV / C Component I: Technical assi onsultancy Services for the E Individual Consult IDA / 65250 stance and Support to imple Post Direct - National 80,000.00 0.00 Signed 2022-09-09 2022-10-04 2022-09-19 2022-11-03 2022-10-10 2022-11-14 2022-11-14 2023-05-13 ngagement of Lead Higher E ant Selection menting agencies ducation Specialist for SPESS E Project NG-NUC-308175-CS-INDV / C Component I: Technical assi onsultancy Services for the E Individual Consult Under Implement IDA / 65250 stance and Support to imple Post Open - National 25,967.00 0.00 2022-10-12 2022-10-04 2022-11-30 2023-03-02 2022-12-21 2023-04-11 2023-01-25 2023-07-24 ngagement of a Computer an ant Selection ation menting agencies d Communication Engineer NG-NUC-308178-CS-INDV / C Component I: Technical assi onsultancy Services for the E Individual Consult Under Implement IDA / 65250 stance and Support to imple Post Open - National 25,967.00 0.00 2022-11-15 2022-10-04 2023-01-03 2023-01-24 2023-02-28 2023-08-27 ngagement of Student Infor ant Selection ation menting agencies mation System Specialist NG-NUC-308179-CS-INDV / C Component I: Technical assi onsultancy Services for the E Individual Consult Under Implement IDA / 65250 stance and Support to imple Post Open - National 38,950.00 0.00 2022-10-28 2022-10-04 2022-12-16 2023-03-02 2023-01-06 2023-04-14 2023-02-10 2023-08-09 ngagement of Centres of Exc ant Selection ation menting agencies ellence Monitoring Specialist NG-NUC-308183-CS-INDV / C Component I: Technical assi onsultancy Services for the E Individual Consult Under Implement IDA / 65250 stance and Support to imple Post Open - National 25,967.00 0.00 2022-10-27 2022-10-04 2022-12-15 2023-01-05 2023-02-09 2023-08-08 ngagement of an Education S ant Selection ation menting agencies pecialist for Environmental St andards NG-NUC-308187-CS-INDV / C Component I: Technical assi Individual Consult Under Implement onsultancy Services for the E IDA / 65250 stance and Support to imple Post Open - National 34,630.00 0.00 2022-09-06 2022-10-04 2022-10-25 2022-11-15 2022-12-20 2023-06-18 ant Selection ation ngagement of a Communicat menting agencies ion Officer NG-NUC-308200-CS-INDV / C Component I: Technical assi onsultancy Services for the E Individual Consult Under Implement IDA / 65250 stance and Support to imple Post Open - National 25,967.00 0.00 2022-10-28 2022-10-04 2022-12-16 2023-01-06 2023-02-10 2023-08-09 ngagement of a Senior Educa ant Selection ation menting agencies tion Specialist (Social Standa rds) NG-NUC-341688-CS-CDS / E Component I: Technical assi Under Implement ngagement of Environmental IDA / 65250 stance and Support to imple Post Direct Selection Direct - National 55,000.00 0.00 2023-03-01 2023-03-14 2023-03-11 2023-05-15 2024-05-14 ation Safeguard Specialist for SPES menting agencies SE Project NG-NUC-360863-CS-INDV / E Component I: Technical assi ngagement of a Consultant t Individual Consult IDA / 65250 stance and Support to imple Post Limited 100,000.00 0.00 Under Review 2023-05-15 2023-06-07 2023-05-20 2023-06-10 2023-07-15 2024-01-11 o conduct Tracer Studies for ant Selection menting agencies SPESSE Centres of Excellenc e NG-NUC-365756-CS-INDV / E Component I: Technical assi Individual Consult Pending Impleme ngagement of a Procurement IDA / 65250 stance and Support to imple Post Limited 29,770.00 0.00 2023-08-08 2023-08-13 2023-09-03 2023-10-08 2024-04-05 ant Selection ntation Audit Consultant (for CE's) menting agencies NG-NUC-365758-CS-INDV / E Component I: Technical assi Individual Consult Pending Impleme ngagement of Consultant on IDA / 65250 stance and Support to imple Post Limited 26,463.00 0.00 2023-07-15 2023-07-20 2023-08-10 2023-09-14 2024-03-12 ant Selection ntation Content Creation (text and vi menting agencies deo) Page 4 PROCUREMENT PLAN (Textual Part) Project information: Guyana-Additional Financing-Flood Risk Management Project- Additional Financing - CREDIT NUMBER - 6786- GY, Amendment: CREDIT AGREEMENT – 5474-GY Project Implementation agency: Agriculture Sector Development Unit, Ministry of Agriculture Date of the Procurement Plan: January 30, 2021 Period covered by this Procurement Plan: December 15, 2020 to December 30, 2024 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Guyana’s Procurement Act 2003 such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods manufactured in the Borrower’s country, compared with Goods manufactured abroad. The preference is fifteen percent (15%) added to the Carriage and Insurance Paid (CIP) price of the Goods manufactured abroad; and Works in member countries below a specified threshold of per capita gross national income (as defined annually by the Bank), when comparing Bids/Proposals from eligible domestic firms with those from foreign firms. The preference is seven and a half percent (7.5%) added to the price offered by the foreign firms. Other Relevant Procurement Information. Not Applicable. PROCUREMENT Guyana : GY Flood Risk Management PLAN General Information Country: Guyana 2021-02-25 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P147250 GPN Date: Project Name: GY Flood Risk Management Loan / Credit No: IDA / 67860, IDA / 54740 GY FLOOD RISK MNGMT Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GY-GY FRM-224545-CW-RFB / Rehabilitation of existing Irri Priority Works for Flood Risk Single Stage - One E 2022-07-1 IDA / 67860 Post Request for Bids Open - National 2,000,000.00 0.00 Signed 2021-09-27 2021-07-11 2021-10-02 2021-08-12 2021-11-13 2021-08-10 2021-12-13 2021-11-15 2022-01-17 gation Structures on the Nort Reduction nvelope 6 h Eastern Dam of the EDWC GY/AF/IDA/FRMP-CP1-W-DS-0 1 / Variation/Additional/Rema Priority Works for Flood Risk Single Stage - One E 2021-10-2 ining Works on the Constructi IDA / 67860 Post Request for Bids Open - National 600,000.00 0.00 Canceled 2021-01-01 2021-01-06 2021-02-17 2021-03-19 2021-04-23 Reduction nvelope 0 on of North Eastern Dams inc luding the maintenance of Eq uipment etc GY/AF/IDA/FRMP-CP1-W-ICB- 05 / Drainage Intervention at Priority Works for Flood Risk Open - Internationa Single Stage - One E 2022-09-0 Liliendaal & Ogle basins, Gre IDA / 67860 Prior Request for Bids 7,000,000.00 0.00 Canceled 2021-11-20 2021-11-25 2022-01-06 2022-02-05 2022-03-12 Reduction l nvelope 8 ater Georgetown and East Co ast of Demerara, Region No. 4 GY/AF/IDA/FRMP-CP1-W-NCB Request for Bids - -04 / Rehabilitation of existin Priority Works for Flood Risk Single Stage - One E Works (without pr 2023-04-0 g irrigation structures on the IDA / 67860 Post Request for Bids Open - National 1,500,000.00 0.00 Signed 2022-09-26 2022-09-26 2022-10-01 2022-09-27 2022-10-29 2022-10-20 2022-11-05 2022-10-24 2022-12-10 Reduction nvelope equalification) SP 9 North Eastern Dam of the ED D WC Lot 4 Nabaclis and Lot 5 Anns Grove GY/AF/IDA/FRMP-CP1-W-ICB- Request for Bids - 06 / Phase 1 - Drainage Inter Priority Works for Flood Risk Open - Internationa Single Stage - One E Works (without pr Under Imple 2023-11-2 IDA / 67860 Prior Request for Bids 4,000,000.00 0.00 2022-09-22 2022-10-05 2022-09-27 2022-10-05 2022-11-01 2022-11-17 2022-11-08 2022-12-02 2022-11-29 vention - Rehabilitation of Og Reduction l nvelope equalification) SP mentation 9 le and Liliendaal Drainage Ca D tchment Areas GY/AF/IDA/FRMP-CP1-W-ICB- Request for Bids - 02 / Reconstruction of North Priority Works for Flood Risk Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2022-09-0 IDA / 67860 Prior Request for Bids 7,000,000.00 0.00 2021-11-20 2021-11-25 2022-01-06 2022-02-05 2022-03-12 Eastern Dam (from Nabaclis t Reduction l nvelope (1 envelope proce lementation 8 o Buxton/Annadale area). ss) GY/AF/IDA/FRMP-CP1-W-ICB- Request for Bids - 07 / Phase 2 - New Works - D Priority Works for Flood Risk Open - Internationa Single Stage - One E Works (without pr 2024-08-1 rainage Intervention - New W IDA / 67860 Post Request for Bids 3,500,000.00 0.00 Canceled 2022-11-01 2022-11-06 2022-12-21 2023-01-04 2023-01-18 Reduction l nvelope equalification) SP 7 orks at Ogle and Liliendaal Dr D ainage Catchment Areas GY/AF/IDA/FRMP-CP2-W-NCB Request for Bids - -05 / Lots 6,7 & 8 - Rehabilita Priority Works for Flood Risk Single Stage - One E Works (without pr Pending Imp 2024-02-0 IDA / 67860 Post Request for Bids Open - National 2,195,000.00 0.00 2023-06-06 2023-06-11 2023-07-02 2023-07-16 2023-08-06 tion of Existing Structures on Reduction nvelope equalification) SP lementation 2 North Eastern Dam of EDWC D FRMP/NCB/01/2016 / Recons truction of the North Eastern Priority Works for Flood Risk Single Stage - One E 390,920,220. 1,887,409.7 IDA / 54740 Prior Request for Bids Open - National Signed 2016-12-12 2016-07-19 Dam of the East Demerara W Reduction nvelope 00 3 ater Conservancy (EDWC)-Re tender FRMP/ICB/01/2016 / Supply, Delivery and Testing of Earth Priority Works for Flood Risk Open - Internationa Single Stage - One E 1,988,816.6 IDA / 54740 Prior Request for Bids 2,060,000.00 Signed 2016-12-12 2016-07-27 Moving Equipment for East D Reduction l nvelope 7 emerara Water Conservancy (EDWC) (Lots 1 to 3) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GY/AF/IDA/FRMP-CP2-GO-NC Priority Works for Flood Risk Single Stage - One E Pending Impl B-01 / Purchase of Earth Movi IDA / 67860 Post Request for Bids Open - National 3,000,000.00 0.00 2021-03-28 2021-04-02 2021-05-14 2021-06-13 2021-07-18 2022-01-14 Reduction nvelope ementation ng Equipment GY/AF/IDA/FRMP-CP2-GO-NC Project Management and Im Single Stage - One E IDA / 67860 Post Request for Bids Open - National 120,000.00 0.00 Canceled 2021-04-09 2021-01-18 2021-04-14 2021-05-26 2021-06-25 2021-07-30 2022-01-26 B-02 / Purchase of Vehicles f plementation Support nvelope or ASDU GY/AF/IDA/FRMP-CP2-GO-NC B-07 / Purchase of Earth Harv Priority Works for Flood Risk Single Stage - One E Pending Impl IDA / 67860 Post Request for Bids Open - National 1,000,000.00 0.00 2022-08-08 2022-09-05 2022-10-03 2022-10-31 2022-12-05 2023-06-03 esting Equipment (Mud Bins Reduction nvelope ementation with Pontoons and Crawler ty pe Draglines) GY/AF/IDA/FRMP-CP2-GO-NC B-06 / Purchase of Earth Movi Priority Works for Flood Risk Single Stage - One E ng Equipment (Lot 1 only) (2 IDA / 67860 Prior Request for Bids Open - National 2,000,000.00 0.00 Canceled 2021-07-12 2021-07-14 2021-08-24 2021-09-23 2021-10-28 2022-04-26 Reduction nvelope Amphibious Excavators & 6 S uper Long Reach Excavators) GY/AF/IDA/FRMP-CP2-GO-NC B-08 / Supply, Delivery & Tes ting of Earth Moving Equipme Priority Works for Flood Risk Open - Internationa Single Stage - One E IDA / 67860 Prior Request for Bids 2,000,000.00 0.00 Signed 2021-11-09 2021-11-11 2021-11-30 2021-11-12 2021-12-01 2021-12-10 2021-12-08 2022-01-03 2021-12-29 2022-06-27 nt for the East Demerara Wat Reduction l nvelope er Conservancy (3 Amphibiou s excavator and additional ac cessories) GY/AF/IDA/FRMP-CP2-GO-DIR Project Management and Im Pending Impl -03 / Purchase of Motor Vehic IDA / 67860 Post Direct Selection Direct 63,450.00 0.00 2021-11-17 2021-11-22 2021-12-18 2022-02-16 plementation Support ementation le (4*4) for ASDU GY/AF/IDA/FRMP-CP2-GO-DIR -04 / Supply and Delivery of Project Management and Im Under Imple IDA / 67860 Post Direct Selection Direct 56,550.00 0.00 2021-11-17 2022-01-05 2021-11-22 2021-12-13 2022-02-11 One New Mini-Bus for use to plementation Support mentation transport staff from Project si te to Office. Page 1 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GY/AF/IDA/FRMP-CP2-NCS-RF Q-01 / Geology Study within t Institutional Strengthening f Request for Quota Single Stage - One E Pending Impl IDA / 67860 Post Limited 75,000.00 0.00 2023-01-11 2023-02-23 2024-04-23 he EDWC for Construction of or Flood Risk Reduction tions nvelope ementation 12 KM of Earthen Embankme nt CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GY/AF/IDA/FRMP-CP1-CS-QC BS-02 / Supervision of Works: Priority Works for Flood Risk Quality And Cost- Pending Impleme IDA / 67860 Post Open - National 100,000.00 0.00 2022-03-20 2022-04-10 2022-05-24 2022-06-21 2022-07-21 2022-08-25 2022-09-29 2023-09-29 Additional/Remaining Work o Reduction Based Selection ntation n the Construction of North E astern Dams GY/AF/IDA/FRMP-CP2-CS-IC-0 7 / Development and Implem Institutional Strengthening f Consultant Qualifi entation of an Emergency Pr IDA / 67860 Post Open - National 50,000.00 0.00 Canceled 2021-11-15 2022-02-04 2021-12-04 2022-01-17 2022-02-16 2022-03-23 2022-09-19 or Flood Risk Reduction cation Selection eparedness Plan (EPP) for the East Coast of Demerara GY/AF/IDA/FRMP-CP3-CS-IC-1 8 / Capacity building activitie s for MoA staff focusing on th Institutional Strengthening f Quality And Cost- Pending Impleme IDA / 67860 Post Open - National 120,000.00 0.00 2022-03-07 2022-03-28 2022-05-11 2022-06-08 2022-07-08 2022-08-12 2022-09-16 2023-09-16 ree major directions: a) hydr or Flood Risk Reduction Based Selection ntation aulic engineering and modelli ng; b) structural engineering; and c) geotechnical engineer ing GY/AF/IDA/FRMP-CP3-CS-LCS Project Management and Im Least Cost Selecti Pending Impleme -15 / Audit Services (Support IDA / 67860 Post Open - National 25,000.00 0.00 2022-06-06 2022-06-27 2022-08-10 2022-09-07 2022-10-07 2022-11-11 2022-12-16 2023-06-14 plementation Support on ntation to Audit Office of Guyana) GY/AF/IDA/FRMP-CP1-CS-QC BS-05 / Supervision of Works: Priority Works for Flood Risk Quality And Cost- Open - Internationa Under Implement IDA / 67860 Post 600,000.00 0.00 2022-07-04 2022-10-04 2022-07-25 2022-09-07 2022-12-16 2022-10-05 2023-01-05 2022-11-04 2023-01-19 2022-12-09 2023-02-14 2023-01-13 2024-01-13 Drainage Interventions at Lili Reduction Based Selection l ation endaal & Ogle basin, ECD GY/AF/IDA/FRMP-CP1-CS-QC BS-04 / Additional Study for Priority Works for Flood Risk Quality And Cost- Open - Internationa IDA / 67860 Post 350,000.00 343,415.38 Signed 2021-10-05 2021-11-01 2021-10-12 2021-11-02 2020-04-14 2021-11-09 2020-06-30 2021-11-16 2020-08-18 2021-12-07 2021-09-10 2021-12-28 2021-12-18 2022-04-28 Drainage Intervention at Lilie Reduction Based Selection l ndaal and Ogle basins GY/AF/IDA/FRMP-CP1-CS-CQ Priority Works for Flood Risk Consultant Qualifi S-01 / Optimization study an IDA / 67860 Post Open - National 40,000.00 0.00 Canceled 2021-10-06 2021-11-08 2021-10-27 2021-12-10 2022-01-09 2022-02-13 2022-08-12 Reduction cation Selection d updating of CSQAP for Nab acalis to Annadale GY/AF/IDA/FRMP-CP1-CS-QC BS-03 / Supervision of Works: Priority Works for Flood Risk Quality And Cost- Open - Internationa IDA / 67860 Post 900,000.00 0.00 Canceled 2021-10-24 2021-11-14 2021-12-28 2022-01-25 2022-02-24 2022-03-31 2022-05-05 2023-05-05 Reconstruction of North East Reduction Based Selection l ern Dam (from Nabaclis to B uxton/Annadale area). GY/AF/IDA/FRMP-CP2-CS-IC-1 7 / Development and Implem Institutional Strengthening f Consultant Qualifi Open - Internationa entation of an Emergency Pr IDA / 67860 Post 50,000.00 0.00 Canceled 2022-06-10 2022-07-06 2022-07-01 2022-07-06 2022-07-22 2022-08-05 2022-09-09 2022-12-08 or Flood Risk Reduction cation Selection l eparedness Plan (EPP) for the East Coast of Demerara GY/AF/IDA/FRMP-CP2-CS-IC-0 9 / Geology Survey and Detai Priority Works for Flood Risk Consultant Qualifi Open - Internationa IDA / 67860 Post 300,000.00 0.00 Canceled 2022-06-16 2023-01-04 2022-07-07 2022-08-20 2022-09-10 2022-10-22 2022-12-21 led Design of EDWC Embank Reduction cation Selection l ment, Region # 4 GY/AF/IDA/FRMP-CP2-QCBS- 10 / Consulting Services: Det ailed Design & Supervision of Institutional Strengthening f Quality And Cost- Open - Internationa East Demerara Water Conser IDA / 67860 Prior 1,175,000.00 0.00 Canceled 2023-01-13 2023-01-19 2023-01-13 2023-01-26 2023-01-20 2023-05-03 2023-02-17 2023-02-24 2023-03-17 2023-04-14 2024-06-12 or Flood Risk Reduction Based Selection l vancy Dam and Preparation of an Emergency Preparedne ss and Response Plan (EPRP) in Region # 4 GY/AF/IDA/FRMP-CP1-CS-QC BS-06 / Supervision of Works: Priority Works for Flood Risk Quality And Cost- Open - Internationa Under Implement Reconstruction of North East IDA / 67860 Post 700,000.00 0.00 2023-06-07 2023-06-12 2023-06-28 2023-08-11 2023-09-08 2023-10-08 2023-11-12 2023-12-17 2024-12-16 Reduction Based Selection l ation ern Dam (between Nabaclis t o Buxton/Annadale area). GY/AF/IDA/FRMP-CP2-CS-CQ S-02 / Optimization study, de Priority Works for Flood Risk Consultant Qualifi Open - Internationa Pending Impleme IDA / 67860 Post 300,000.00 0.00 2023-06-07 2023-06-28 2023-08-11 2023-09-10 2023-10-15 2024-04-12 sign and updated constructio Reduction cation Selection l ntation n methodology (CSQAP) for EDWC Dam GY/IDA/FRMP-CP2-CS-QCBS- 01 (Re-tender) / Supervision Priority Works for Flood Risk Quality And Cost- Open - Internationa of the Reconstruction of the IDA / 54740 Prior 0.00 502,204.94 Signed 2016-12-27 2017-02-14 Reduction Based Selection l North Eastern Dam of the Ea st Demerara Water Conserva ncy (EDWC) GY/IDA/FRMP-CP3-CS-IC-04 / Priority Works for Flood Risk Consultant Qualifi Open - Internationa Hiring of Project Engineer Ms. IDA / 54740 Prior 38,465.00 38,465.00 Signed 2016-12-13 2017-01-02 Reduction cation Selection l Melisa Melinder October GY/IDA/FRMP-CP1-CS-QCBS- 02 / Supervision of Pump Sta Priority Works for Flood Risk Quality And Cost- Open - Internationa IDA / 54740 Prior 0.00 278,207.71 Signed 2017-01-18 2017-02-28 tions at Lusignan, Buxton/Vig Reduction Based Selection l ilance and Hope/Enmore, Eas t Coast Demerara INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 GY/AF/IDA/FRMP-CP1-CS-IC-1 Institutional Strengthening f Individual Consult Pending Impleme IDA / 67860 Post Open 60,000.00 0.00 2021-11-20 2022-01-08 2022-01-29 2022-03-05 2022-09-01 9 / Dam Safety Specialist-Pha or Flood Risk Reduction ant Selection ntation se 2 GY/AF/IDA/FRMP-CP3-CS-DC- Priority Works for Flood Risk 21 / Biodiversity study for sel IDA / 67860 Post Direct Selection Direct 160,000.00 0.00 Signed 2021-04-04 2021-06-01 2021-04-14 2021-04-20 2021-06-18 2021-12-15 Reduction ected sections of the EDWC GY/AF/IDA/FRMP-CP3-CS-IC-1 Project Management and Im Individual Consult Under Implement IDA / 67860 Post Open 275,000.00 0.00 2021-04-04 2021-09-09 2021-05-23 2021-10-10 2021-06-13 2021-07-18 2022-01-14 2 / Project Engineer plementation Support ant Selection ation GY/AF/IDA/FRMP-CP2-CS-IC-0 8 / Updating and Training of t Priority Works for Flood Risk Individual Consult Pending Impleme IDA / 67860 Post Open 20,000.00 0.00 2022-06-06 2022-07-25 2022-08-15 2022-09-19 2023-03-18 he Operations and Maintenan Reduction ant Selection ntation ce System (OMS) Plan for the EDWC GY-GY FRM-256517-CS-INDV Project Management and Im Individual Consult IDA / 67860 Post Open 275,000.00 0.00 Under Review 2021-05-25 2022-01-14 2021-07-13 2021-08-03 2021-09-07 2022-09-07 / Senior Procurement Officer plementation Support ant Selection GY/AF/IDA/FRMP-CP1-CS-IC-2 Project Management and Im Individual Consult Under Implement 0 / Hiring of Environmental & IDA / 67860 Post Open 100,000.00 0.00 2021-05-25 2019-10-08 2021-07-13 2019-11-29 2021-08-03 2021-01-02 2021-09-07 2024-03-07 plementation Support ant Selection ation Social Specialist GY/AF/IDA/FRMP-CP3-CS-IC-1 Project Management and Im IDA / 67860 Post Direct Selection Direct 325,000.00 0.00 Under Review 2021-01-01 2022-01-14 2021-01-11 2021-02-01 2022-02-01 0 / Project Coordinator plementation Support GY/AF/IDA/FRMP-CP3-CS-IC-1 Project Management and Im Individual Consult Pending Impleme IDA / 67860 Post Open 200,000.00 0.00 2021-12-15 2022-02-02 2022-02-23 2022-03-30 2022-09-26 4 / Personnel/Administrative plementation Support ant Selection ntation Officer GY/AF/IDA/FRMP-CP3-CS-IC-1 Project Management and Im Individual Consult Pending Impleme IDA / 67860 Post Open 225,000.00 0.00 2021-10-14 2021-12-02 2021-12-23 2022-01-27 2023-01-27 3 / Project Accountant plementation Support ant Selection ntation GY/AF/IDA/FRMP-CP1-CS-DIR -02 / Geology Survey and Det Priority Works for Flood Risk Under Implement IDA / 67860 Post Direct Selection Direct 75,000.00 0.00 2021-11-17 2021-12-01 2021-11-27 2022-01-06 2021-12-28 2022-02-26 ailed Design of EDWC Emban Reduction ation kment, Region # 4 GY/AF/IDA/FRMP-CP3-CS-CD Project Management and Im IDA / 67860 Post Direct Selection Direct 62,800.00 58,875.00 Signed 2022-02-01 2022-02-01 2022-02-01 2022-01-01 2022-02-01 2022-02-02 2023-01-31 S-04 / Project Coordinator Yr plementation Support 2 GY/AF/IDA/FRMP-CP3-CS-CD Project Management and Im IDA / 67860 Post Direct Selection Direct 47,100.00 47,100.00 Signed 2022-02-15 2022-02-15 2022-02-15 2022-01-01 2022-02-15 2022-02-16 2023-02-14 S-05 / Senior Procurement Of plementation Support ficer Yr2 GY/AF/IDA/FRMP-CP3-CS-CD Project Management and Im IDA / 67860 Post Direct Selection Direct 62,800.00 0.00 Signed 2022-11-18 2023-01-02 2022-11-28 2023-01-31 2023-02-01 2024-01-31 S-18 / Project Coordinator Yr plementation Support 3 GY/AF/IDA/FRMP-CP3-CS-CD Project Management and Im IDA / 67860 Post Direct Selection Direct 47,100.00 0.00 Signed 2022-12-28 2023-02-09 2023-01-25 2023-02-01 2023-02-15 2024-02-14 S-19 / Senior Procurement Of plementation Support ficer Yr 3 GY/AF/IDA/FRMP-CP2-CS-IC-1 0 / Development and Implem Institutional Strengthening f Individual Consult IDA / 67860 Post Limited 80,000.00 0.00 Canceled 2023-06-07 2023-06-02 2023-06-12 2023-07-03 2023-07-24 2023-09-22 entation of an Emergency Pr or Flood Risk Reduction ant Selection eparedness Plan (EPP) for ED WC GY/AF/IDA/FRMP-CP1-CS-IC-1 1 / Development and Implem Institutional Strengthening f Individual Consult Open - Internationa Under Implement IDA / 67860 Post 80,000.00 0.00 2023-06-23 2023-06-25 2023-08-04 2023-08-11 2023-08-25 2023-10-24 entation of an Emergency Pr or Flood Risk Reduction ant Selection l ation eparedness Plan (EPP) for ED WC GY/IDA/FRMP-CP2-CS-SS-01 and 02 / Engineering Service s for Dam Design Optimizatio Priority Works for Flood Risk n, Construction Quality Assur IDA / 54740 Prior Direct Selection Direct 0.00 51,741.62 Signed 2015-07-17 Reduction ance System and Dam Safety Monitoring Program Develop ment including an Instrument ation Plan GY/IDA/DRMP-CP3-CS-IC-03 / Priority Works for Flood Risk Individual Consult Hiring of Project Coordinator IDA / 54740 Prior Open 0.00 47,100.00 Signed 2014-12-12 2014-12-02 Reduction ant Selection for the Flood Risk Manageme nt Project GY/IDA/FRMPCP3-CS-IC-03 / Priority Works for Flood Risk Individual Consult IDA / 54740 Prior Open 47,100.00 94,200.00 Signed 2015-11-24 2015-12-02 Contract Renewal for Project Reduction ant Selection Coordinator GY/IDA/FRMP-CP3-CS-IC-06 / Priority Works for Flood Risk Individual Consult IDA / 54740 Prior Open 0.00 51,810.00 Signed 2015-02-20 2015-05-02 HIRING OF PROCUREMENT O Reduction ant Selection FFICER Page 3 PLAN DE PASSATION DE MARCHÉS (Texte) Information sur le Projet : [Nom du pays] [Nom du Projet] [No d’identification du projet] Agence d’exécution du Projet : [Insérer le nom officiel de l’Agence] Date du plan de passation des marchés : [Insérer la date] Période couverte par ce plan de passation des marchés : [Insérer date de début, date de fin] Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016) (“Règlement de Passation des Marchés”) le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marché se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus de STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées [Insérer la référence exacte de la législation nationale], ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : Indiquer la liste des conditions requises pour assurer la cohérence avec le paragraphe 5.4 du Règlement de passation des marchés. Si aucune condition s’applique, supprimer la mention « et aux conditions suivantes ». Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. Sinon indiquer « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. Sinon indiquer « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : [ne s’applique pas/s’applique pour les contrats indiqués dans les tableaux du Plan de passation des marchés] Travaux [ne s’applique pas/s’applique pour les contrats indiqués dans les tableaux du Plan de passation des marchés] L’Assistance directe à la mise en œuvre (sigle HEIS en anglais) tel que précisée aux paragraphes 3.10 et 3.11 du Règlement de Passation des marchés s’applique. [Inclure cette mention seulement si la Banque a formellement acceptée de fournir cette assistance directe à l’Emprunteur. Sinon, supprimer cette phrase.] Autres informations pertinentes sur la passation des marchés Indiquer toute autre information pertinente relative aux procédures de passation, telle que par exemple l’utilisation de procédures de participation communautaire au développement (CDD), de l’utilisation de procédures pour un besoin urgent d’assistance ou de faible capacité, etc. PROCUREMENT Western and Central Africa : Regional Electricity Access and BEST Project PLAN General Information Country: Western and Central Africa 2021-07-07 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167569 GPN Date: 2021-05-17 Project Name: Regional Electricity Access and BEST Project Loan / Credit No: IDA / 68950, IDA / 68860 SENEGAL NATIONAL ELECTRICITY AGENCY Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 01-FOUR-ECOWAS-2022 / Ac quisition 02 VEHICULES pour l'UGPE avec le Projet BEST : Project coordination and tec Single Stage - One E ** 01 Véhicule de Type 4X4, IDA / 68950 Post Request for Bids Open - National 121,594.00 0.00 Canceled 2022-09-15 2022-09-20 2022-11-01 2022-12-01 2023-01-05 2023-02-04 hnical assistance nvelope Station Wagon - et ** 01 Véhicule de Type 4x4, Double Cabine 01 BIS-FOUR-ECOWAS-2022 / Acquisition 02 VEHICULES p our l'UGPE avec le Projet BES Project coordination and tec Request for Quota Single Stage - One E Under Imple IDA / 68950 Post Limited 121,594.00 0.00 2022-10-05 2022-11-08 2022-11-30 2022-12-30 T: hnical assistance tions nvelope mentation 01 Véhicule de Type 4X4, Sta tion Wagon et 01 Véhicule d e Type 4x4, Double Cabine. 02-FOUR-ECOWAS-2023 / Re Supervision of the constructi Request for Quota Single Stage - One E Under Imple lance Acquisition 01 VEHICUL IDA / 68950 Post Limited 85,000.00 0.00 2023-05-15 2023-06-27 2023-07-10 2023-07-14 on and technical advisory tions nvelope mentation E de Type 4X4, Station Wago n pour l'UGPE. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 06-CONS-ECOWAS-2021 / RE CRUTEMENT D’UN AUDITEUR Project coordination and tec Consultant Qualifi Pending Impleme IDA / 68950 Post Open - National 85,000.00 0.00 2021-08-11 2021-09-01 2021-10-15 2021-11-14 2021-12-19 2022-04-18 EXTERNE hnical assistance cation Selection ntation Pour ECOWAS pour les Exerci ces 2021-2022-2023 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 01-CONS-ECOWAS-2021 / Re crutement d’un Consultant p Project coordination and tec our la « MISE A JOUR DU MA IDA / 68950 Post Direct Selection Direct 20,000.00 28,902.55 Signed 2021-06-10 2021-08-05 2021-06-20 2021-10-19 2021-08-24 2021-12-18 2021-11-22 hnical assistance NUEL D’EXECUTION DU PASE avec PRISE EN COMPTE PROJ ETS ECOWAS & PADAES» 02-CONS-ECOWAS-2021 / RE CRUTEMENT D’UN CHARGE D Supervision of the constructi Individual Consult IDA / 68860 Post Limited 38,600.00 0.00 Canceled 2021-06-21 2021-08-05 2021-06-26 2021-07-17 2021-08-21 2022-08-21 U SUIVI SOCIAL - SPECIALIST on and technical advisory ant Selection E EN REINSTALLATION - 12 m ois Renouvelable 03 BIS-CONS-ECOWAS-2021 / RECRUTEMENT D’UN CHAR GE DU SUIVI SOCIAL - SPECIA Supervision of the constructi Individual Consult IDA / 68860 Post Open 38,600.00 0.00 Canceled 2021-11-16 2021-11-08 2022-01-04 2022-01-25 2022-03-01 2023-03-01 LISTE EN GENRE ET VIOLENC on and technical advisory ant Selection E BASEE SUR LE GENRE (VBG y compris ESAH) - 12 mois R enouvelable 04 BIS-CONS-ECOWAS-2021 / RECRUTEMENT D’UN CHAR Supervision of the constructi Individual Consult IDA / 68860 Post Open 38,600.00 0.00 Canceled 2021-11-16 2021-11-08 2022-01-04 2022-01-25 2022-03-01 2023-03-01 GE DU SUIVI DES QUESTIONS on and technical advisory ant Selection D’HYGIENE, SANTE ET SECU RITE AU TRAVAIL. 04-CONS-ECOWAS-2021 / RE CRUTEMENT D’UN CHARGE D Supervision of the constructi Individual Consult U SUIVI DES MESURES HYGIE IDA / 68860 Post Limited 38,600.00 0.00 Canceled 2021-06-21 2021-08-05 2021-06-26 2021-07-17 2021-08-21 2022-08-21 on and technical advisory ant Selection NE SECURITE ENVIRONNEME NT (HSE) - 12 mois Renouvel able 03-CONS-ECOWAS-2021 / RE CRUTEMENT D’UN CHARGE D U SUIVI SOCIAL - SPECIALIST Supervision of the constructi Individual Consult IDA / 68860 Post Limited 38,600.00 0.00 Canceled 2021-06-21 2021-08-05 2021-06-26 2021-07-17 2021-08-21 2022-08-21 E EN EXPLOITATION SEXUELL on and technical advisory ant Selection E - ABUS - HARCELEMENT (ES AH) - 12 mois Renouvelable Page 1 05 BIS-CONS-ECOWAS-2021 / RECRUTEMENT D’UN Compt Project coordination and tec Individual Consult Under Implement able pour l’Unité d’Exécution IDA / 68950 Post Open 38,600.00 0.00 2021-12-22 2022-01-13 2022-02-09 2022-03-02 2022-04-06 2023-04-06 hnical assistance ant Selection ation des Projets Energies - Senele c - 12 mois Renouvelable. 02 BIS-CONS-ECOWAS-2022 / RECRUTEMENT D’UN CONS Supervision of the constructi Individual Consult IDA / 68860 Post Limited 35,110.00 0.00 Signed 2022-02-24 2022-02-15 2022-03-01 2022-03-24 2022-03-22 2022-11-03 2022-04-26 2023-04-26 ULTANT CHARGE DU SUIVI S on and technical advisory ant Selection OCIAL - SPECIALISE EN REINS TALLATION. 03 BIS 2-CONS-ECOWAS-202 2 / RECRUTEMENT D’UN CON Supervision of the constructi Individual Consult SULTANT CHARGE DU SUIVI S IDA / 68860 Post Open 35,110.00 0.00 Signed 2022-02-24 2022-02-15 2022-04-14 2022-09-08 2022-05-05 2022-09-14 2022-06-09 2023-06-09 on and technical advisory ant Selection OCIAL - SPECIALISE EN VIOLE NCE BASEE SUR LE GENRE (V BG y compris ESAH). 04 BIS 2-CONS-ECOWAS-202 2 / RECRUTEMENT D’UN CON Supervision of the constructi Individual Consult IDA / 68860 Post Open 35,110.00 0.00 Signed 2022-02-24 2022-02-15 2022-04-14 2022-06-20 2022-05-05 2022-10-26 2022-06-09 2023-06-09 SULTANT CHARGE DU SUIVI on and technical advisory ant Selection DES QUESTIONS D’HYGIENE, SANTE ET SECURITE. Page 2 PROJET D’APPUI À L’AMÉLIORATION DES APPRENTISSAGES EN DÉBUT DE SCOLARITÉ (PAADESCO- SHISHIKARA) PLAN DE PASSATION SIMPLIFIE I. GÉNÉRALITÉS : 1.1. Information générale sur le projet Pays: République du Burundi Emprunteur : Gouvernement de Burundi ; Nom du Projet : Projet d’Appui à l’Amélioration des Apprentissages en Début de Scolarité (PAADESCO- SHISHIKARA) Numéros du Prêt : P 161600 Montant du Prêt : USD2.5 million equivalent Unité de Gestion du Projet : Ministère de l’Education et de l’Enseignement Supérieur et de la Recherche Scientifique 1.2 Date d’approbation du plan de passation de marchés Plan original : xx Révision 1 : xx 1.3 Date de publication de l’avis général de passation de marchés : xx dans UNDB et DgMarket 1.4 Période couverte par le Plan de passation des marchés : Février 2018 à Septembre 2018 II. Fourniture, Travaux et Services Assimilés 2.1. Seuils d’examen préalable Les marchés qui seront soumis à l'examen préalable de la banque conformément aux Nouveaux Seuils de Revue de la Banque Mondiale – Effectifs depuis Juillet 2016 : Niveau de risque du projet Risque élevé - Risque Risque Risque Bas Tout marché de Substantiel - Modéré - - Catégorie de … estimé égal ou Tout marché de … Tout marché Tout marchés supérieur à : estimé égal ou de … estimé marché de supérieur à : égal ou … estimé supérieur à : égal ou supérieur à : Travaux (incluant clé à main, Fourniture et $20, $5, 000,000 $10, 000,000 $15, 000,000 Installation, et les 000,000 Partenariat Public - Privé -PPP) Biens, Système d’Information et de $1, 500,000 $2, 000,000 $4, 000,000 $6, 000,000 Services autres que les Services intellectuels Services Consultant $500,000 $1, 000,000 $2, 000,000 $4, 000,000 (Firmes) Consultant $200,000 $300,000 $400,000 $500,000 Individuel Les marchés qui seront soumis à l'examen préalable de la banque conformément aux dispositions de l'Annexe 1 des Directives de passation de marchés : Nouveaux seuils de revue de la Banque élaborés, révisés en juillet 2016 et liés au niveau de risque du projet. Nature des dépenses Méthode de passation de Valeur seuil du Contrats soumis à examen marchés marché $EU préalable de l’IDA 1. Travaux AOI ≥ 7, 000,000 (y compris clés en main, AON < 7, 000,000 Tous les contrats de 10.000.000 Fourniture et montage $ et plus d’installations et PPP) Demande de cotation – < 200,000 au moins 3 offres Entente Directe (*) Pas de seuil Contrats ≥ 100,000 2. Fournitures, Systèmes AOI ≥ 3, 000,000 d’Informations et AON < 3, 000,000 Services autres que les Tous les contrats de 2.000.000 services de Consultants Consultation de Fournisseurs à $ et plus l’échelle Nationale - Au moins 3 < 100,000 offres Entente directe (*) Pas de seuil Contrats ≥ 100,000 (*) Le justificatif de toute entente directe dont le coût estimatif n’atteint pas le seuil de revue préalable de la Banque doit être transmis avec le PPM 2.2. Marchés/Contrats, planning et Méthode de passation Type de marchés : Travaux et Fournitures 1 2 3 4 5 6 7 8 Méthode Préférence Liste des ensembles Coût estimé passation P-Q Exam. par Ouverture plis fournisseurs de marchés Marchés Banque prévue locaux Commentaire BAILLEURS N° A Préali/A Comp. Description (milliers $) OUI/NON OUI/NON Date prévue posteriori FOURNITURES Edition, Impression et distribution de A 1 matériels (Manuels et Guides et autres 1, 800 AOI NON NON Posteriori Sept 2018 outils pédagogiques) 3 Achat groupe électrogène 30 CF NON NON A avril 2018 Posteriori Achat équipement informatique ED 4 220 NON NON A Priori ministère et UGP- UNOPS 5 Achat 3 véhicules- UNOPS 120 ED NON NON A Priori avril 2018 Fourniture- équipements de bureaux, CF A 6 50 NON NON avril 2018 consommables Posteriori TOTAL 2, 210 Taux de change utilisé : 1 $= 3 III. Sélection de Consultants 3.1. Seuil d’examen préalable Les contrats qui seront soumis à l'examen préalable de la Banque. Nature de Méthode de passation Valeur Contrats soumis à dépenses de marchés seuil du examen préalable contrat $ Consultan SFQC1, SFQ2, SMC3, ≥ 200.000 ts SCBD4, Tout contrat de 200.000 Firmes SFQC, SFQ, SMC, SCBD, $EU ou plus < 200.000 QC5 Pas de Contrat ≥ 200,000 Entente directe (*) seuil Et Audit financier Consultan Consultant individuel (AMI) ≥ 100.000 ts Tout contrat de 100.000 $ Individuel Consultant individuel (3 EU ou plus < 100.000 s CV) Contrat ≥ 100,000 Pas de Entente directe (*) Et personnel permanent seuil du projet Tous les TDRs, quelle que soit la valeur du contrat, sont soumis à examen préalable. (*) Le justificatif de toute sélection par entente directe dont le coût estimatif n’atteint pas le seuil de revue préalable de la Banque doit être transmis avec le PPM 3.2. Liste restreinte composée entièrement de Consultants Nationaux : Liste restreinte de consultants pour prestations de services, d’un coût estimatif inférieur à 300 000$ US ou équivalent par contrat, peut être entièrement composée de Consultants nationaux conformément aux dispositions du paragraphe 2.7 des Directives de Sélection et Emploi de Consultants 1 SFQC : Sélection Fondée sur la Qualité et le Coût 2 SFQ : Sélection fondée sur la qualité 3 SMC : Sélection au moindre coût 4 SCBD : Sélection dans le cadre d’un budget déterminé 5 QC : Sélection basée sur les Qualifications des Consultants CI : Consultant Individuel : AMI : Avis à Manifestation d’Intérêt Prestation de services de consultants 1 2 3 5 6 7 Liste des ensembles de contrats passés par Consultation Coût estimé Méthode Ouverture restreinte Description de la mission Examen BM Commentaire BAILLEUR sélection des offres T Com PREAL/A No. Description de la mission (milliers $) Date prévue p. POST CONSULTANTS Consultants pour la rédaction des manuels de 1 procédures administratives, financière et comptable, 50 QC Preal avril 2018 passation de marchés, suivi évaluation Consultant pour développer la stratégie de 2 7 CI Post mai 2018 communication et appuyer la CCI Recrutement Assistance Technique pour le 3 développement du matériel de lecture en Kirundi et 80 SSS Preal avril 2018 en français pour les enfants en début de scolarité 4 Etude sur les pratiques pédagogiques en classe 10 CI Post avril 2018 Consultant pour la traduction du curriculum révisé en 5 10 CI Post avril 2018 Kirundi Assistance Technique pour le développement et 6 implémentation des évaluations système (2e et 4e 300 QC Preal avril 2018 année) Recrutement d’un consultant pour le Développement 7 application pour collecte de données haute fréquence 50 QC Post avril 2018 M&E 8 Service d’une agence pour la gestion PPA 80 SFQC Preal avril 2018 9 Coordonnateur du Projet 32 CI Preal avril 2018 10 Responsable administratif et financier 24 CI Preal avril 2018 11 Responsable de Passation des Marchés 20 CI Preal avril 2018 12 Spécialiste des opérations et suivi & évaluation 20 CI Preal avril 2018 13 Spécialiste en Education 16 CI Preal avril 2018 14 Audits technique et financier 10 CI Preal juillet 2018 Assistance technique pour l’élaboration des études de 15 25 CI Post mai 2018 sauvegarde sociale et environnementale 5 Assistance technique pour l’intégration du programme 16 200 ED Preal juillet 2018 d’accélération des apprentissages de la lecture Assistance technique pour le renforcement des curriculums, développement des manuels scolaires, 17 500 ED Preal juillet 2018 guide des enseignants module de formation et supports pédagogiques TOTAL CONSULTANTS 1, 434 6 Formations, Ateliers et missions Examen Montant Préalable de la N° Description des activités Estimatif Durée estimée Date de début Commentaires Banque (milliers $EU) (Oui/Non) 1 Formation des enseignants et directeurs d’école 1,500 Oui Atelier de travail pour l’harmonisation des outils et 2 40 supports pédagogiques 3 Atelier de lancement du projet 10 TOTAL 1, 550 7 PROCUREMENT Burundi : Burundi Early Grade Learning Project PLAN General Information Country: Burundi 2018-06-07 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161600 GPN Date: Project Name: Burundi Early Grade Learning Project Loan / Credit No: IDA / V1680, IDA / D3200 Burundi Early Grade Learning Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Enhancing parental support UN Agencies (Dire D10117 / Achat 3 véhicules IDA / V1680 Post Direct 120,000.00 0.00 Canceled 2018-07-16 2018-07-16 2018-07-16 2018-07-16 and school attendance of st ct) udents D10124 / Acquisition des tab Enhancing parental support Request for Quota Single Stage - One E Under Imple IDA / D3200 Post Limited 50,000.00 0.00 2019-04-03 2019-03-15 2019-05-29 2019-11-25 lettes and school attendance of st tions nvelope mentation udents D10116 / Achat équipement Enhancing parental support Request for Quota Single Stage - One E IDA / V1680 Prior Limited 220,000.00 0.00 Canceled 2018-06-09 2018-08-04 2019-01-31 informatique pour le Ministèr and school attendance of st tions nvelope e et l'UGP udents D10118 / Fourniture équipe Enhancing parental support Request for Quota Single Stage - One E IDA / V1680 Post Limited 50,000.00 0.00 Canceled 2018-06-16 2018-08-11 2019-02-07 ments de bureaux, consomm and school attendance of st tions nvelope ables udents D10115 / Achat groupe élect Enhancing parental support Request for Quota Single Stage - One E IDA / V1680 Post Limited 30,000.00 0.00 Canceled 2018-06-09 2018-08-04 2019-01-31 rogène and school attendance of st tions nvelope udents B10116 / Acquisition d'un gr Align systems to improve st UN Agencies (Dire oupe électrogène pour le Min IDA / D3200 udent progression and learni Post Direct 50,000.00 0.00 Canceled 2019-07-28 2019-08-02 2019-09-06 2020-03-04 ct) istère ng in early grades B20101 / Mise en forme édit oriale, Impression des Manue Align systems to improve st ls Scolaires et livraison au niv Single Stage - One E IDA / D3200 udent progression and learni Post Request for Bids Open - National 600,000.00 0.00 Canceled 2019-08-05 2019-08-10 2019-09-21 2019-10-21 2019-11-25 2020-05-23 eau des DCE de la matière d nvelope ng in early grades u premier trimestre des man uels de la 1ère année de l’Ec ole Fondamentale D20112 / Acquisition des éq Align systems to improve st UN Agencies (Dire uipements informatiques pou IDA / D3200 udent progression and learni Post Direct 200,000.00 0.00 Canceled 2020-03-30 2020-04-05 2020-04-20 2020-10-17 ct) r l'UFP et le Ministère ng in early grades D20115 / Fourniture des équ Align systems to improve st Request for Quota Single Stage - One E ipement informatiques et ser IDA / D3200 udent progression and learni Post Limited 26,000.00 28,910.10 Completed 2019-11-19 2019-11-20 2020-01-14 2020-03-26 2020-07-12 2020-03-26 tions nvelope vices connexes pour l'UFP ng in early grades Align systems to improve st D20118 / Fourniture du mobi Request for Quota Single Stage - One E IDA / D3200 udent progression and learni Post Limited 25,000.00 22,547.20 Completed 2020-01-13 2020-01-14 2020-03-09 2020-04-01 2020-09-05 2020-07-24 lier de bureau pour l'UFP tions nvelope ng in early grades D20116 / Fourniture et instal Align systems to improve st Request for Quota Single Stage - One E lation d'une centrale télépho IDA / D3200 udent progression and learni Post Limited 22,000.00 0.00 Canceled 2020-01-08 2020-03-04 2020-08-31 tions nvelope niqueet équipements connex ng in early grades es pour l'UFP Align systems to improve st D20133 / Acquisition d'un Ce Request for Quota Single Stage - One E IDA / D3200 udent progression and learni Post Limited 21,000.00 2,795.98 Completed 2020-11-28 2020-11-18 2021-01-23 2021-01-09 2021-07-22 2021-01-13 ntral téléphonique pour l'UFP tions nvelope ng in early grades D20138 / Acquisition des rid Align systems to improve st Request for Quota Single Stage - One E eaux et services connexes p IDA / D3200 udent progression and learni Post Limited 7,500.00 0.00 Canceled 2020-11-28 2022-05-31 2021-01-23 2021-07-22 tions nvelope our les bureaux de l'UFP ng in early grades D20139 / Acquisition des cli Align systems to improve st Request for Quota Single Stage - One E matiseurs et services connex IDA / D3200 udent progression and learni Post Limited 31,000.00 14,958.36 Completed 2020-11-28 2020-12-22 2021-01-23 2021-02-20 2021-07-22 2021-06-25 tions nvelope es pour les bureaux de l'UFP ng in early grades D20143 / Acquisition de : i) Trois véhicules pour l'UFP, ii) Align systems to improve st UN Agencies (Dire groupe électrogène pour le M IDA / D3200 udent progression and learni Post Direct 900,000.00 851,782.00 Completed 2021-01-22 2021-01-19 2021-01-27 2021-02-05 2021-03-03 2021-02-27 2021-08-30 2021-08-21 ct) ENRS et iii) équipements info ng in early grades rmatiques pour le MENRS et l 'UFP auprès de l'UNOPS A30112 / Recrutement par e Enhancing parental support ntente directe de l'UNICEF po Under Imple IDA / D3200 and school attendance of st Post Direct Selection Direct 2,300,000.00 0.00 2018-10-02 2018-10-02 2018-10-07 2018-11-11 2019-05-10 ur la fourniture de matériels mentation udents scolaires et services connexe s A20114 / Recrutement par e Enhancing parental support ntente directe du PAM pour l' Under Imple IDA / D3200 and school attendance of st Prior Direct Selection Direct 7,000,000.00 0.00 2018-10-03 2022-09-19 2018-10-08 2018-11-12 2019-05-11 achat des produits alimentair mentation udents es en faveur des élèves et s ervices connexes D20138_BIS / Acquisition de Align systems to improve st s rideaux et services connex Request for Quota Single Stage - One E Pending Impl IDA / D3200 udent progression and learni Post Limited 7,500.00 0.00 2022-07-10 2022-09-04 2023-03-03 es pour les bureaux de l'UFP tions nvelope ementation ng in early grades PAADESCO-SHISHIKARA D20145 / Acquisition des ch Align systems to improve st aises de bureau pour le Minis Request for Quota Single Stage - One E Pending Impl IDA / D3200 udent progression and learni Post Limited 86,206.89 0.00 2023-04-03 2023-05-29 2023-11-25 tère de l’Education Nationale tions nvelope ementation ng in early grades et de la Recherche Scientifiq ue (MENRS). NON CONSULTING SERVICES Page 1 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual D10121 / Location d'un imm Enhancing parental support Request for Quota Single Stage - One E Pending Impl IDA / V1680 Post Limited 18,000.00 0.00 2018-07-28 2018-09-22 2019-03-21 euble pour héberger l'UFP and school attendance of st tions nvelope ementation udents D10119 / Acquisition de la lo Enhancing parental support gistique liée à l'atelier de tra Request for Quota Single Stage - One E IDA / V1680 and school attendance of st Post Limited 40,000.00 0.00 Canceled 2018-07-04 2018-08-29 2019-02-25 vail pour l'harmonisation des tions nvelope udents outils et supports pédagogiq ues D10120 / Acquisition de la lo Enhancing parental support Request for Quota Single Stage - One E gistique liée à l'atelier de lan IDA / V1680 and school attendance of st Post Limited 9,000.00 0.00 Canceled 2018-09-22 2018-11-17 2019-05-16 tions nvelope cement du projet udents B20100 / Acquisition d'un se rvice de mise en forme éditor Align systems to improve st iale, l'impression et la livrais Open - Internationa Single Stage - One E Under Imple IDA / D3200 udent progression and learni Prior Request for Bids 1,800,000.00 0.00 2019-05-31 2019-05-24 2019-06-05 2019-08-03 2019-07-17 2019-08-16 2019-08-16 2019-10-17 2019-09-20 2020-03-18 on au niveau communes des l nvelope mentation ng in early grades Manuels Scolaires de la 1ère année de l'Ecole Fondamenta le B10119 / Recrutement d'un f ournisseur de service de tran sfert monétaire relatif à la for Align systems to improve st Request for Quota Single Stage - One E Pending Impl mation des Enseignants, Dire IDA / D3200 udent progression and learni Post Limited 90,000.00 0.00 2019-07-06 2019-08-31 2020-02-27 tions nvelope ementation cteurs et Maîtres Responsabl ng in early grades es dans le cadre des prépara tifs de la rentrée scolaire 201 9-2020 B20102 / Recrutement d'une agence de transport au nivea u des communes des manuel Improve instructional practic Request for Quota Single Stage - One E Pending Impl IDA / D3200 Post Limited 25,000.00 0.00 2020-02-06 2020-04-02 2020-09-29 s des élves er guides des Maî e in the classroom tions nvelope ementation tres de la 1 ère année de l'e nseigenement fondamental d u Burundi B20103 / Mise en forme édit oriale et l'impression des cah Improve instructional practic Open - Internationa Single Stage - One E iers d'apprentissage et livret IDA / D3200 Post Request for Bids 1,300,000.00 0.00 Canceled 2020-04-10 2020-03-26 2020-04-15 2020-03-26 2020-05-27 2020-06-02 2020-06-26 2020-07-09 2020-07-31 2021-01-27 e in the classroom l nvelope s d'évaluation de la première année de l'école fondamenta le B20105 / Recrutement de la société Bollore Transport & L ogistics Burundi S.A pour le t ransport des manuels des él Improve instructional practic IDA / D3200 Post Direct Selection Direct 60,200.00 59,548.89 Completed 2020-04-02 2020-04-03 2020-04-07 2020-03-12 2020-05-12 2020-04-09 2020-11-08 2020-04-15 èves et Guides des Maîtres d e in the classroom e la 1 ère année de l'ECOFO du Burundi objet des lots 1 et 3 depuis Bujumbura jusqu'au niveau des DCE. B20106 / Acquisition d'un se rvice d'impression en noir et blanc et recto-verso des man Improve instructional practic Request for Quota Single Stage - One E IDA / D3200 Post Limited 96,000.00 31,784.82 Completed 2020-06-01 2020-06-23 2020-07-27 2020-08-19 2021-01-23 2020-08-23 uels destinés à la formation d e in the classroom tions nvelope es Enseignants de la deuxiè me année de l'Ecole Fondam entale, B20104 / Acquisition d'un se rvice de mise en forme éditor Improve instructional practic Open - Internationa Single Stage - One E iale et l'impression des manu IDA / D3200 Prior Request for Bids 2,000,000.00 1,237,552.30 Completed 2020-06-20 2020-06-30 2020-06-25 2020-08-04 2020-08-06 2020-09-04 2020-09-05 2020-12-01 2020-10-10 2020-12-29 2021-04-08 2021-11-06 e in the classroom l nvelope els scolaires de la deuxième année de l'Ecole Fondamenta le, B10120 / Recrutement de l'a gence CASSAVA FINTECH BU RUNDI en charge du transfert monétaire relatif à la formati Improve instructional practic IDA / D3200 Post Direct Selection Direct 35,000.00 29,094.19 Signed 2020-08-20 2020-08-19 2020-08-25 2020-08-20 2020-09-29 2020-08-27 2021-03-28 on des formateurs des Ensei e in the classroom gnants, Maitres Responsable s, des Enseignants et des Ins pecteurs Provinciaux pour la rentrée scolaire 2020-2021 B20103_BIS / Mise en forme éditoriale et l'impression des Improve instructional practic Open - Internationa Single Stage - One E Under Imple cahiers d'apprentissage et liv IDA / D3200 Post Request for Bids 1,300,000.00 0.00 2020-10-08 2020-11-09 2020-10-13 2020-11-06 2020-11-24 2020-12-23 2020-12-24 2021-04-09 2021-01-28 2021-07-27 e in the classroom l nvelope mentation rets d'évaluation de la premi ère année de l'école fondam entale C10108 / Multiplication de : i ) Module traduit en Kirundi et illustré pour la formation des Align school level activities t membres des CGE et des cop Request for Quota Single Stage - One E IDA / D3200 o improve student performa Post Limited 71,000.00 53,086.42 Signed 2020-12-14 2020-12-24 2021-02-08 2021-02-25 2021-08-07 ies en français ii) guide admi tions nvelope nce in early grades nistratif et pédagogique des Directeurs des écoles et iii) g uide méthodologique de form ation des CGE C20100 / Acquisition d'un se rvice d'impression, multiplica Align school level activities t Request for Quota Single Stage - One E tion et reliure de la Lettre cir IDA / D3200 o improve student performa Post Limited 22,500.00 5,794.58 Completed 2021-05-29 2021-07-21 2021-07-24 2021-10-07 2022-01-20 2021-10-23 tions nvelope culaire et ses annexes ainsi q nce in early grades ue le dépliant en Kirundi et e n Français B20107 / Recrutement de la société Bollore Transport & L ogistics Burundi S.A pour le t ransport des manuels des élè Improve instructional practic Pending Impl IDA / D3200 Post Direct Selection Direct 83,810.00 0.00 2021-08-27 2021-09-01 2021-10-06 2022-04-04 ves et Guides des Maîtres de e in the classroom ementation la 2 ème année de l'ECOFO , guide pratique, module inté gré et lettre circulaire et ses annexes en Kirundi dans 119 DCE. B20113 / Acquisition d'un se rvice de mise en forme édito Improve instructional practic Open - Internationa Single Stage - One E riale et l' impression des man IDA / D3200 Prior Request for Bids 2,000,000.00 1,684,227.50 Signed 2021-10-28 2021-11-28 2021-11-02 2022-01-28 2021-12-14 2022-02-15 2022-01-13 2022-05-30 2022-02-17 2022-07-23 2022-08-16 e in the classroom l nvelope uels scolaires de la 3 ème an née de l'école fondamentale. C20103 / Recrutement par e Align school level activities t ntente directe de la société P Under Imple IDA / D3200 o improve student performa Post Direct Selection Direct 5,720.00 0.00 2021-12-14 2021-12-15 2021-12-19 2021-12-21 2022-01-23 2022-07-22 RINTEC pour la multiplication mentation nce in early grades de la Lettre circulaire et ses annexes en Français. Page 2 B20115 / Recrutement par e ntente directe de la société B olloré Transport & Logistics B urundi SA pour le transport d Improve instructional practic Pending Impl IDA / D3200 Post Direct Selection Direct 116,400.00 0.00 2022-02-08 2022-02-13 2022-03-20 2022-09-16 es manuels d’élèves , cahiers e in the classroom ementation d’apprentissage de la lecture 1 et 2 ème année, livrets d’é valuation , lettre circulaires e t ses annexes en Français A20115 / Recrutement par E ntente Directe du Programm e Alimentaire Mondial (PAM) Enhancing parental support Pending Impl pour l'achat des produits et s IDA / D3200 and school attendance of st Post Direct Selection Direct 1,808,117.71 0.00 2022-03-04 2022-03-09 2022-04-13 2022-10-10 ementation ervices connexes dans le cad udents re de l'appui à l'extension de s cantines scolaires dans les Provinces de Muyinga et Kiru ndo. B30113 / Recrutement par e ntente directe de SASAI Finte ch Burundi pour le transfert Improve instructional practic Pending Impl monétaire relatif à la formati IDA / D3200 Post Direct Selection Direct 24,912.15 0.00 2022-07-18 2022-07-23 2022-08-27 2023-02-23 e in the classroom ementation on des Enseignants de 3 -èm e année, des Maitres Respon sables et des Directeurs des ECOFO n'ayant pas de cycle 4 B20140 / Recrutement par e ntente directe de la société MEX s.a pour la multiplicatio n des outils destinés à la for Improve instructional practic Pending Impl IDA / D3200 Post Direct Selection Direct - National 37,387.54 0.00 2022-07-25 2022-07-30 2022-09-03 2023-03-02 mation des Formateurs des E e in the classroom ementation nseignants de 3 ème année de l'ECOFO, des Maîtres Resp onsables et des Directeurs d es ECOFO n'ayant pas de cyc le 4. B20117 / Recrutement par e ntente directe de Bolloré Tra nsport & Logistics pour le tra nsport au niveau des chefs li Improve instructional practic Pending Impl IDA / D3200 Post Direct Selection Direct - National 226,169.19 0.00 2022-10-05 2022-10-10 2022-11-14 2023-05-13 eux des Communes de : i) M e in the classroom ementation anuels scolaires de la 3 ème année de l'ECOFO et ii) Cahie rs d'apprentissage de la lectu re de la 1 ère année de l'ECO FO. B20131 / Recrutement par e ntente directe de la maison d 'édition English Press Ltd pou Improve instructional practic Direct - Internation Under Imple r la mise en forme éditoriale IDA / D3200 Post Direct Selection 1,700,000.00 0.00 2023-02-16 2023-02-17 2023-02-21 2023-03-02 2023-03-28 2023-09-24 e in the classroom al mentation et l'impression des manuels s colaires de la 4 ème année d e l'école fondamentale du Bu rundi B20141 / Multiplication des manuels de formation des Fo Improve instructional practic Request for Quota Single Stage - One E Pending Impl IDA / D3200 Post Limited 74,620.00 0.00 2023-04-03 2023-05-29 2023-11-25 rmateurs des Enseignants de e in the classroom tions nvelope ementation la 4 ème année de l’Ecole fo ndamentale (ECOFO) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual D10102 / Recrutement d’un Enhancing parental support consultant pour le Développe Consultant Qualifi IDA / V1680 and school attendance of st Post Open - National 50,000.00 0.00 Canceled 2018-07-09 2018-07-30 2018-09-12 2018-10-12 2018-11-16 2019-05-15 ment application pour collect cation Selection udents e de données haute fréquenc e M&E B10101 / Assistance Techniq Align systems to improve st ue pour le développement et Consultant Qualifi Open - Internationa IDA / V1680 udent progression and learni Post 150,000.00 0.00 Canceled 2018-07-23 2018-08-13 2018-09-26 2018-10-26 2018-11-30 2019-05-29 implémentation des évaluati cation Selection l ng in early grades ons système (2e et 4e année ) B10117 / Recrutement d'un Align systems to improve st Least Cost Selecti Open - Internationa Under Implement cabinet pour l'audit financier IDA / D3200 udent progression and learni Post 25,000.00 0.00 2019-09-30 2019-09-11 2019-10-21 2019-12-04 2020-01-01 2020-01-31 2020-03-06 2020-04-10 2020-10-07 on l ation pour le PPA et la 1ère année ng in early grades fiscale (2020) D10101_BIS / Recrutement d 'un Cabinet pour l'assistance Align systems to improve st technique pour développer e Quality And Cost- Under Implement IDA / D3200 udent progression and learni Post International 200,000.00 0.00 2020-04-10 2020-03-26 2020-05-01 2020-04-03 2020-06-14 2020-07-12 2020-08-11 2020-09-15 2020-10-20 2021-10-20 t implémentetr la géolocalis Based Selection ation ng in early grades ation des écoles fondamental es et post fondamentales du Burundi D10125 / Recrutement d'un Cabinet chargé de l'évaluatio Align systems to improve st Quality And Cost- Open - Internationa n à mi parcours des résultats IDA / D3200 udent progression and learni Post 260,000.00 0.00 Canceled 2021-08-12 2021-09-17 2021-09-02 2021-10-13 2021-10-16 2021-11-13 2021-12-13 2022-01-17 2022-02-21 2023-02-21 Based Selection l d'apprentissage des élèves d ng in early grades es classes de 2 ème et de 4 ème année. D20121 / Recrutement d'un Align systems to improve st Cabinet d'audit financier du P Least Cost Selecti Open - Internationa Under Implement IDA / D3200 udent progression and learni Post 40,000.00 0.00 2021-08-21 2021-09-17 2021-09-11 2021-10-25 2021-11-22 2021-12-22 2022-01-26 2022-03-02 2022-08-29 rojet PAADESCO-SHISHIKARA on l ation ng in early grades pour les exercices 2020-202 1 et 2021-2022 D10101 / Recrutement d'un cabinet pour l'Assistance tec hnique pour: (i) développer e Enhancing parental support t implémenter la stratégie po Quality And Cost- Open - Internationa IDA / V1680 and school attendance of st Post 300,000.00 0.00 Canceled 2018-08-13 2019-02-18 2018-09-03 2019-05-24 2018-10-17 2018-11-14 2018-12-14 2019-01-18 2019-02-22 2020-02-22 ur codification et géolocalisat Based Selection l udents ion des écoles, (ii) développe r une application pour la coll ecte des données haute fréq uence  M&E D10132 / Recrutement d'un Cabinet chargé de réaliser u ne évaluation longitudinale c Align systems to improve st ombinant l'évaluation à mi-p Consultant Qualifi IDA / D3200 udent progression and learni Post Limited 260,000.00 0.00 Canceled 2022-08-23 2022-08-19 2022-09-06 2022-10-06 2022-11-10 2023-05-09 arcours et l'évaluation d'imp cation Selection ng in early grades act des résultats d'apprentiss age des élèves des classes d e 2 ème et de 4 ème année d e l'école fondamentale. Page 3 D10133 / Recrutement d'un cabinet en charge de l’évalu ation transversale des acquis Align systems to improve st de l’année scolaire 2022-202 Consultant Qualifi Under Implement IDA / D3200 udent progression and learni Post Limited 150,000.00 0.00 2023-04-17 2023-04-18 2023-05-01 2023-05-31 2023-07-05 2024-01-01 3 en 2e et 4e année et l’éval cation Selection ation ng in early grades uation longitudinale des résul tats d’apprentissage des élèv es de la 4e année pour l’ann ée scolaire 2023-2024 D20161 / Recrutement Cabi net audit financier 2022-202 3, audit technique de la distri Align systems to improve st bution des manuels d’élèves Least Cost Selecti Open - Internationa IDA / D3200 udent progression and learni Post 26,000.00 0.00 Under Review 2023-05-15 2023-06-20 2023-06-05 2023-07-19 2023-08-16 2023-09-15 2023-10-20 2023-11-24 2024-05-22 et guides pour enseignants d on l ng in early grades e 3ème des ECOFO publiques et privées & audit de transfer t des subventions aux écoles pour le volet j’entretiens mon école INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual A10100 / Consultant pour dé Align school level activities t Individual Consult Under Implement velopper la stratégie de com IDA / V1680 o improve student performa Post Limited 37,000.00 0.00 2018-06-15 2018-10-26 2018-06-20 2018-11-04 2018-07-11 2018-08-15 2019-02-11 ant Selection ation munication et appuyer la CCI nce in early grades B10102 / Assistance techniq Align systems to improve st ue pour l’intégration du progr IDA / V1680 udent progression and learni Prior Direct Selection Direct 200,000.00 0.00 Canceled 2018-07-16 2018-07-15 2018-07-26 2018-07-23 2018-09-29 2019-03-28 amme d’accélération des ap ng in early grades prentissages de la lecture B10103 / Assistance techniq ue pour le renforcement des Align systems to improve st curriculums, développement IDA / V1680 udent progression and learni Prior Direct Selection Direct 1,000,000.00 1,153,791.11 Signed 2018-07-23 2018-07-23 2018-08-02 2018-07-26 2018-10-06 2018-12-01 2019-04-04 des manuels scolaires, guide ng in early grades des enseignants module de f ormation et supports pédago giques  B10104 / Consultant local po Align systems to improve st Individual Consult Pending Impleme ur appuyer la rédaction en ki IDA / V1680 udent progression and learni Post Limited 2,000.00 0.00 2018-05-31 2018-06-05 2018-06-26 2018-07-31 2019-01-27 ant Selection ntation rundi des guides des directeu ng in early grades rs et CGEs  D10100 / Consultants pour l a rédaction des manuels de p Enhancing parental support Individual Consult Under Implement rocédures administratives, fi IDA / V1680 and school attendance of st Post Limited 15,800.00 0.00 2018-06-25 2018-06-09 2018-06-30 2018-07-21 2018-08-25 2019-02-21 ant Selection ation nancière et comptable, passa udents tion de marchés, suivi évalua tion D10108 / Recrutement d'un Enhancing parental support Individual Consult Pending Impleme IDA / V1680 Post Open 12,000.00 0.00 2018-07-02 2018-08-20 2018-09-10 2018-10-15 2019-04-13 comptable and school attendance of st ant Selection ntation udents D10109 / Recrutement d'un( Enhancing parental support Individual Consult Under Implement IDA / V1680 Post Limited 9,000.00 0.00 2018-07-02 2018-06-11 2018-07-07 2018-07-28 2018-09-01 2019-02-28 e) assistant(e) administratif ( and school attendance of st ant Selection ation ve) udents B10102 BIS / Assistance tec Align systems to improve st hnique pour l’intégration du IDA / V1680 udent progression and learni Post Direct Selection Direct 200,000.00 199,985.00 Signed 2018-07-16 2018-07-16 2018-07-23 2018-07-23 2019-03-22 2019-03-08 2019-09-18 programme d’accélération d ng in early grades es apprentissages de la lectu re B10105 / Recrutement d’une Align systems to improve st Institution pour faire l’illustra Pending Impleme IDA / D3200 udent progression and learni Post Direct Selection Direct - National 70,000.00 0.00 2019-01-20 2019-01-30 2019-04-05 2019-10-02 tion des manuels des élèves ntation ng in early grades et des guides pédagogiques B10106 / Recrutement d’un Align systems to improve st Individual Consult Pending Impleme expert pour l'élaboration des IDA / D3200 udent progression and learni Post Limited 10,000.00 0.00 2019-05-15 2019-05-20 2019-06-10 2019-07-15 2020-01-11 ant Selection ntation livrets de lecture supplément ng in early grades aires B10107 / Recrutement d'aut Align systems to improve st eurs experts dans la rédactio Individual Consult Pending Impleme IDA / D3200 udent progression and learni Post Open 25,000.00 0.00 2019-04-30 2019-06-18 2019-07-09 2019-08-13 2020-02-09 n des livrets de lecture et qui ant Selection ntation ng in early grades vont travailler en atelier B10108 / Recrutement des il Align systems to improve st lustrateurs pour l'illustration Individual Consult Under Implement IDA / D3200 udent progression and learni Post Open 25,000.00 0.00 2019-05-01 2019-03-27 2019-06-19 2019-07-10 2019-08-14 2020-02-10 des livrets de lecture et qui v ant Selection ation ng in early grades ont travailler en atelier avec l es auteurs B10109 / Recrutement d’un Align systems to improve st consultant pour appuyer dan Individual Consult Pending Impleme IDA / D3200 udent progression and learni Post Limited 10,000.00 0.00 2019-03-27 2019-04-01 2019-04-22 2019-05-27 2019-11-23 s la finalisation et la cohéren ant Selection ntation ng in early grades ce du guide administratif et d u guide pédagogique C10101 / Recrutement d’un Consultant senior qui sera ch argé d’inclure dans le manue Contingent Emergency Resp Individual Consult Pending Impleme l des éléments d’enrichissem IDA / D3200 Post Limited 15,000.00 0.00 2019-04-22 2019-04-27 2019-05-18 2019-06-22 2019-12-19 onse Component (CERC) ant Selection ntation ent du module pour la format ion des CGEs, de la boîte à o util ainsi que de sa traductio n en Kirundi. C10102 / Recrutement d’un Consultant junior qui sera ch argé de faire l’illustration du Contingent Emergency Resp Individual Consult Under Implement IDA / D3200 Post Limited 10,000.00 0.00 2019-04-30 2019-05-21 2019-05-05 2019-05-26 2019-06-30 2019-12-27 module pour la formation des onse Component (CERC) ant Selection ation CGEs qui sera traduit en Kiru ndi ainsi que de la boîte à ou til D10122 / Recrutement d'un Consultant spécialiste en scie Enhancing parental support Individual Consult nces de l'éduction pour l'enri IDA / D3200 and school attendance of st Post Direct 50,000.00 45,508.00 Signed 2019-03-27 2019-03-27 2019-04-06 2019-03-27 2019-04-27 2019-04-05 2019-06-01 2019-04-11 2019-11-28 ant Selection chissement des items d'éval udents uation (2e et 4e année) D10123 / Recrutement d'un Enhancing parental support Consultant statisticien pour l' Individual Consult Pending Impleme IDA / D3200 and school attendance of st Post Limited 25,000.00 0.00 2019-03-28 2019-04-02 2019-04-23 2019-05-28 2019-11-24 analyse et le traitement des ant Selection ntation udents données d'évaluation D10111 / Recutement d'un c Enhancing parental support Individual Consult IDA / V1680 Post Open 3,600.00 0.00 Canceled 2018-07-02 2018-08-20 2018-09-10 2018-10-15 2019-04-13 hauffeur and school attendance of st ant Selection udents Page 4 D10110 / Recutement d'un t Enhancing parental support Individual Consult IDA / V1680 Post Open 7,200.00 0.00 Canceled 2018-07-02 2018-08-20 2018-09-10 2018-10-15 2019-04-13 résorier and school attendance of st ant Selection udents B10100 / Etude sur les prati Align systems to improve st Individual Consult ques pédagogiques en classe IDA / V1680 udent progression and learni Post Limited 10,000.00 0.00 Canceled 2018-06-11 2018-06-16 2018-07-07 2018-08-11 2019-02-07 ant Selection ng in early grades D10107 / Recutement d'un s Enhancing parental support Individual Consult pécialiste des opérations et s IDA / V1680 and school attendance of st Prior Open 20,000.00 0.00 Canceled 2018-07-02 2018-07-15 2018-08-20 2018-09-10 2018-10-15 2019-04-13 ant Selection uivi&évaluation udents D10106 / Recrutement d'un Enhancing parental support Individual Consult IDA / V1680 Prior Open 20,000.00 0.00 Canceled 2018-07-02 2018-07-15 2018-08-20 2018-09-10 2018-10-15 2019-04-13 responsable en Passation des and school attendance of st ant Selection marchés udents D10105 / Recutement d'un r Enhancing parental support Individual Consult IDA / V1680 Prior Open 24,000.00 0.00 Canceled 2018-07-02 2018-07-15 2018-08-20 2018-09-10 2018-10-15 2019-04-13 esponsable administratif et fi and school attendance of st ant Selection nancier udents D10104 / Recrutement du C Enhancing parental support Individual Consult IDA / V1680 Prior Open 32,000.00 0.00 Canceled 2018-07-02 2018-07-15 2018-08-20 2018-09-10 2018-10-15 2019-04-13 oordonnateur du Projet and school attendance of st ant Selection udents D10113 / Recutement d'un s Enhancing parental support Individual Consult IDA / V1680 Post Open 16,000.00 0.00 Canceled 2019-05-15 2019-07-03 2019-07-24 2019-08-28 2020-02-24 pécialiste en Education and school attendance of st ant Selection udents B10110 / recrutement d'un c Align systems to improve st Individual Consult Under Implement onsultant spécialiste en déon IDA / D3200 udent progression and learni Post Direct 5,000.00 0.00 2019-05-31 2019-05-14 2019-06-10 2019-07-01 2019-08-05 2020-02-01 ant Selection ation tologie professionnelle et en ng in early grades administration Align systems to improve st B10111 / Recrutement d'un Individual Consult Under Implement IDA / D3200 udent progression and learni Post Open 32,000.00 0.00 2018-07-16 2018-07-16 2019-07-14 2019-08-04 2019-09-08 2020-03-06 coordonnateur du Projet ant Selection ation ng in early grades B10113 / Recrutement d'un Align systems to improve st Individual Consult Under Implement responsable en Passation des IDA / D3200 udent progression and learni Post Open 20,000.00 0.00 2018-07-16 2018-07-16 2019-07-14 2019-08-04 2019-09-08 2020-03-06 ant Selection ation marchés ng in early grades B10112 / Recrutement d'un Align systems to improve st Individual Consult Under Implement responsable en Administratif IDA / D3200 udent progression and learni Post Open 20,000.00 0.00 2018-07-16 2018-07-16 2019-07-14 2019-08-04 2019-09-08 2020-03-06 ant Selection ation et Financier ng in early grades B10115 / Recutement d'un s Align systems to improve st Individual Consult Under Implement pécialiste des opérations et s IDA / D3200 udent progression and learni Post Open 20,000.00 0.00 2018-07-16 2018-07-16 2019-07-14 2019-08-04 2019-09-08 2020-03-06 ant Selection ation uivi&évaluation ng in early grades A20101 / Recrutement d’un Consultant National Chargé d ’élaborer une étude d’Impact Align school level activities t Environnemental et Social et Individual Consult IDA / D3200 o improve student performa Post Open 10,000.00 15,509.70 Signed 2019-07-31 2019-07-10 2019-09-18 2020-04-23 2019-10-09 2020-05-15 2019-11-13 2020-05-17 2020-05-11 de Plan de Gestion de la Con ant Selection nce in early grades struction et de l’Utilisation de s Systèmes de Collecte des E aux Pluviales (SCEPs) dans le s écoles de Muyinga et de Kir undo B10114 / Recrutement d'un spécialiste en déontologie po Align systems to improve st Individual Consult Under Implement ur contribuer à la préparation IDA / D3200 udent progression and learni Post Direct 10,000.00 0.00 2019-07-15 2019-07-15 2019-07-25 2019-08-15 2019-09-19 2020-03-17 ant Selection ation du Guide Pédagogique pour l ng in early grades e Directeur de l’Ecole Fonda mentale B10118 / Recrutement d'un expert en éducation pour con Align systems to improve st Individual Consult Pending Impleme tribuer à la préparation du G IDA / D3200 udent progression and learni Post Direct 10,000.00 0.00 2019-07-05 2019-07-15 2019-08-05 2019-09-09 2020-03-07 ant Selection ntation uide Pédagogique pour le Dir ng in early grades ecteur de l’Ecole Fondament ale D20107 / Recrutement d'un Align systems to improve st Individual Consult Pending Impleme (e) Assistant (e) Administratif IDA / D3200 udent progression and learni Post Open 14,000.00 0.00 2019-11-01 2019-12-20 2020-01-10 2020-02-14 2020-08-12 ant Selection ntation (ve) ng in early grades Align systems to improve st D20113 / Recrutement d'un Individual Consult Pending Impleme IDA / D3200 udent progression and learni Post Open 22,000.00 0.00 2019-11-01 2019-12-20 2020-01-10 2020-02-14 2020-08-12 Spécialiste en Education ant Selection ntation ng in early grades Align systems to improve st D20106 / Recrutement d'un Individual Consult Pending Impleme IDA / D3200 udent progression and learni Post Open 14,000.00 0.00 2019-11-01 2019-12-20 2020-01-10 2020-02-14 2020-08-12 comptable 1 ant Selection ntation ng in early grades Align systems to improve st D20108 / Recrutement d'un Individual Consult Pending Impleme IDA / D3200 udent progression and learni Post Open 14,000.00 0.00 2019-11-01 2019-12-20 2020-01-10 2020-02-14 2020-08-12 comptable 2 ant Selection ntation ng in early grades Align systems to improve st D20114 / Recrutement d'un Individual Consult Pending Impleme IDA / D3200 udent progression and learni Post Open 22,000.00 0.00 2019-11-01 2019-12-20 2020-01-10 2020-02-14 2020-08-12 Auditeur Interne ant Selection ntation ng in early grades D20142 / Recrutement d'un Align systems to improve st Individual Consult Under Implement Spécialiste en Sauvegarde En IDA / D3200 udent progression and learni Post Open 24,200.00 0.00 2021-05-24 2021-05-24 2021-07-04 2021-07-25 2021-08-29 2022-02-25 ant Selection ation vironnementale et Sociale ng in early grades B10121 / Recrutement d'un Consultant Sénior pour assur er la qualité du travail des éc Improve instructional practic Individual Consult rivains et des illustrateurs de IDA / D3200 Post Open 6,950.00 0.00 Canceled 2021-05-21 2021-05-24 2021-07-09 2021-07-30 2021-09-03 2022-03-02 e in the classroom ant Selection s livrets supplémentaires de l ecture pour les enfants de la 1ère et 2 ème année de l'éco le fondamentale D20141 / Recrutement d'un Align systems to improve st Consultant individuel nationa Individual Consult Under Implement IDA / D3200 udent progression and learni Post Open 4,500.00 0.00 2021-08-12 2021-09-17 2021-09-30 2021-10-21 2021-11-25 2022-05-24 l (H/F) chargé (e) d'actualiser ant Selection ation ng in early grades le manuel d'exécution du pro jet PAADESCO B10122 / Recrutement d'un Improve instructional practic Individual Consult Consultant individuel n°1 me IDA / D3200 Post Open 2,700.00 0.00 Canceled 2021-08-23 2021-09-17 2021-10-11 2021-11-01 2021-12-06 2022-06-04 e in the classroom ant Selection mbre du PANEL des écrivains B10126 / Recrutement d'un Improve instructional practic Individual Consult Consultant individuel n°1 me IDA / D3200 Post Open 2,100.00 0.00 Canceled 2021-08-23 2021-09-17 2021-10-11 2021-11-01 2021-12-06 2022-06-04 e in the classroom ant Selection mbre du PANEL des illustrate urs Page 5 B10125 / Recrutement d'un Improve instructional practic Individual Consult Consultant individuel n°4 me IDA / D3200 Post Open 2,700.00 0.00 Canceled 2021-08-23 2021-09-17 2021-10-11 2021-11-01 2021-12-06 2022-06-04 e in the classroom ant Selection mbre du PANEL des écrivains B10127 / Recrutement d'un Improve instructional practic Individual Consult consultant individuel n°2 me IDA / D3200 Post Open 2,100.00 0.00 Canceled 2021-08-23 2021-09-17 2021-10-11 2021-11-01 2021-12-06 2022-06-04 e in the classroom ant Selection mbre du PANEL des illustrate urs B10123 / Recrutement d'un Improve instructional practic Individual Consult Consultant individuel n°2 me IDA / D3200 Post Open 2,700.00 0.00 Canceled 2021-08-23 2021-09-17 2021-10-11 2021-11-01 2021-12-06 2022-06-04 e in the classroom ant Selection mbre du PANEL des écrivain s B10124 / Recrutement d'un Improve instructional practic Individual Consult consultant individuel n°3 me IDA / D3200 Post Open 2,700.00 0.00 Canceled 2021-08-23 2021-09-17 2021-10-11 2021-11-01 2021-12-06 2022-06-04 e in the classroom ant Selection mbre du PANEL des écrivains B10129 / Recrutement d'un Improve instructional practic Individual Consult consultant individuel n°4 me IDA / D3200 Post Open 2,100.00 0.00 Canceled 2021-08-23 2021-09-17 2021-10-11 2021-11-01 2021-12-06 2022-06-04 e in the classroom ant Selection mbre du PANEL des illustrate urs B10128 / Recrutement d'un Improve instructional practic Individual Consult consultant individuel n°3 me IDA / D3200 Post Open 2,100.00 0.00 Canceled 2021-08-23 2021-09-17 2021-10-11 2021-11-01 2021-12-06 2022-06-04 e in the classroom ant Selection mbre du PANEL des illustrate urs D20151 / Recrutement par E ntente Directe de Monsieur M Align systems to improve st Individual Consult Under Implement bawa MWENYEBATU Jean Chr IDA / D3200 udent progression and learni Post Direct 24,030.00 0.00 2021-10-20 2022-08-04 2021-10-30 2021-11-20 2021-12-25 2022-06-23 ant Selection ation istophe, Spécialiste en Educa ng in early grades tion au Projet PAADESCO-SHI SHIKARA D20152 / Recrutement par E ntente Directe de Mademoise Align systems to improve st Individual Consult Under Implement lle IRAKOZE Digne, Assistant IDA / D3200 udent progression and learni Post Direct 15,456.00 0.00 2021-10-20 2022-08-04 2021-10-30 2021-11-20 2021-12-25 2022-06-23 ant Selection ation e Administrative au Projet PA ng in early grades ADESCO-SHISHIKARA D20153 / Recrutement par E Align systems to improve st ntente Directe de Monsieur N Individual Consult Under Implement IDA / D3200 udent progression and learni Post Direct 23,697.00 0.00 2021-10-20 2022-08-04 2021-10-30 2021-11-20 2021-12-25 2022-06-23 DIKUMANA Jean Bosco, Audit ant Selection ation ng in early grades eur Interne du Projet PAADES CO-SHISHIKARA. D20154 / Recrutement par E Align systems to improve st ntente Directe de Monsieur N Individual Consult Under Implement IDA / D3200 udent progression and learni Post Direct 15,456.00 0.00 2021-10-20 2022-08-05 2021-10-30 2021-11-20 2021-12-25 2022-06-23 SAVYIMANA Anselme, Compt ant Selection ation ng in early grades able 1 du Projet PAADESCO-S HIHSIKARA D20155 / Recrutement par E Align systems to improve st ntente Directe de Madame NI Individual Consult Under Implement IDA / D3200 udent progression and learni Post Direct 15,456.00 0.00 2021-10-20 2022-08-05 2021-10-30 2021-11-20 2021-12-25 2022-06-23 JIMBERE Denise, Comptable ant Selection ation ng in early grades 2 du Projet PAADESCO-SHISH IKARA D20204 / Recrutement par E Align systems to improve st ntente Directe de Madame S Under Implement IDA / D3200 udent progression and learni Post Direct Selection Direct 44,348.07 0.00 2022-06-30 2022-07-11 2022-07-10 2022-09-13 2023-03-12 AMANDARI Béatrice, Coordon ation ng in early grades natrice du Projet PAADESCO- SHISHIKARA. D20205 / Recrutement par E ntente Directe de Monsieur B Align systems to improve st Under Implement UTOYI Appolinaire, Responsa IDA / D3200 udent progression and learni Post Direct Selection Direct 32,070.98 0.00 2022-06-30 2022-07-11 2022-07-10 2022-09-13 2023-03-12 ation ble Administratif et Financier ng in early grades du Projet PAADESCO-SHISHIK ARA D20206 / Recrutement par E ntente Directe de Monsieur N Align systems to improve st Under Implement TAWUNKUNDA Gaston, Spéci IDA / D3200 udent progression and learni Post Direct Selection Direct 29,410.13 0.00 2022-06-30 2022-07-11 2022-07-10 2022-09-13 2023-03-12 ation aliste en Passation des March ng in early grades és du Projet PAADESCO-SHIS HIKARA D20207 / Recrutement par E ntente Directe de Madame NI Align systems to improve st Under Implement YONZIMA Mathilde, Responsa IDA / D3200 udent progression and learni Post Direct Selection Direct 29,410.13 0.00 2022-06-30 2022-07-11 2022-07-10 2022-09-13 2023-03-12 ation ble du Suivi-Evaluation du Pr ng in early grades ojet PAADESCO-SHISHIKARA D20179 / Recrutement d'un Align systems to improve st (e) Assistant (e) en Passatio Individual Consult Under Implement IDA / D3200 udent progression and learni Post Open - National 15,331.92 0.00 2022-07-25 2022-08-04 2022-09-12 2022-10-03 2022-11-07 2023-05-06 n des Marchés du Projet PAA ant Selection ation ng in early grades DESCO-SHISHIKARA D10131 / Recrutement par e ntente directe de SOFRECO p our l'assistance technique po Align systems to improve st ur développer et implémente Direct - Internation IDA / D3200 udent progression and learni Post Direct Selection 84,260.00 0.00 Completed 2022-08-22 2022-08-19 2022-09-01 2022-08-25 2022-11-05 2023-05-04 2023-01-08 r la géolocalisation des école al ng in early grades s d'enseignement des métier s, de la formation profession nelle et les structures d'ensei gnement supérieur et service s connexes D20182 / Recrutement d'un (e) consultant (e) individuel Align systems to improve st Individual Consult Under Implement (le) en Sauvegarde Environn IDA / D3200 udent progression and learni Post Limited 12,297.48 0.00 2023-02-27 2023-02-23 2023-03-04 2023-03-25 2023-04-29 2023-10-26 ant Selection ation ementale et Sociale du Projet ng in early grades PAADESCO-SHISHIKARA Page 6 PROCUREMENT PLAN (Textual Part) Project information: Sint Maarten Fostering Resilient Learning Project (P172753) Project Implementation agency: National Recovery Program Bureau Date of the Procurement Plan: 11/19/2020 Period covered by this Procurement Plan: December 2020- December 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets: “Not Applicable” Procurement of Second Hand Goods: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable Works: is not applicable PROCUREMENT St Maarten : FOSTERING RESILIENT LEARNING PROJECT PLAN General Information Country: St Maarten 2020-11-19 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172753 GPN Date: Project Name: FOSTERING RESILIENT LEARNING PROJECT Loan / Credit No: TF / B4914, / , TF / B8048 National Recovery Program Bureau Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual National Proc SX-NRPB-258535-CW-RFB / urement Doc Civil Works: Construction and Open - Internationa Single Stage - One E ument - 1 En 2022-10-0 TF / B4914 Rebuilding Inclusive Schools Prior Request for Bids 0.00 Canceled 2021-12-13 2021-12-18 2022-01-29 2022-02-28 2022-04-04 Furnishing of Charles Leopold l nvelope velope proce 1 Bell School and Philipsburg Ju ss (Non Bank bilee Library -SPD) National Proc SX-NRPB-258529-CW-RFB / urement Doc Open - Internationa Single Stage - One E 2023-01-0 Civil Works for Sister Marie L TF / B4914 Rebuilding Inclusive Schools Post Request for Bids ument - 1 En 0.00 Canceled 2022-03-15 2022-03-20 2022-05-01 2022-05-31 2022-07-05 l nvelope 1 aurence School velope proce ss (Non Bank -SPD) Request for B SX-NRPB-MG-279137-CW-RF ids - Small W B / Package for Reconstructio Open - Internationa Single Stage - One E Pending Imp 2025-06-3 TF / B4914 Rebuilding Inclusive Schools Post Request for Bids orks SPD (1 e 0.00 2024-01-09 2024-01-14 2024-02-25 2024-03-26 2024-04-30 n of Charles Leopold Bell Sch l nvelope lementation 0 nvelope proc ool and Philipsburg Jubilee Li ess) brary Request for SX-NRPB-MG-324419-CW-RF Request for Quota Single Stage - One E Quotations ( Pending Imp 2023-10-0 Q / Temporary Fencing for CL TF / B8048 Rebuilding Inclusive Schools Post Open - National 0.00 2023-06-11 2023-08-06 tions nvelope Non Bank-SP lementation 5 B school and PJL D) Request for B SX-NRPB-MG-279142-CW-RF ids - Small W Open - Internationa Single Stage - One E Pending Imp 2025-12-0 B / Package for reconstructio TF / B4914 Rebuilding Inclusive Schools Post Request for Bids orks SPD (1 e 0.00 2023-05-12 2023-05-17 2023-06-28 2023-07-28 2023-09-01 l nvelope lementation 4 n for Sister Marie Laurence S nvelope proc chool US ess) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SX-NRPB-205571-GO-DIR / I / Restoring Library Services Post Direct Selection Direct 0.00 Canceled 2021-01-25 2021-01-30 2021-03-06 2021-09-02 CT Equipment SX-NRPB-MG-279158-GO-RF Single Stage - One E Pending Impl TF / B4914 Rebuilding Inclusive Schools Post Request for Bids Open - National 0.00 2023-07-07 2023-07-12 2023-08-23 2023-09-22 2023-10-27 2024-03-30 B / Package for Furniture for nvelope ementation SML SX-NRPB-MG-279238-GO-RF Open - Internationa Single Stage - One E Pending Impl B / Package for Furniture for TF / B4914 Restoring Library Services Post Request for Bids 0.00 2023-08-30 2023-09-04 2023-10-16 2023-11-15 2023-12-20 2024-05-23 l nvelope ementation PJL/ICT and CLB School ICT/F urniture SX-NRPB-MG-324426-GO-RF Strengthening Management Request for Quota Single Stage - One E TF / B8048 Post Limited 0.00 Completed 2022-11-10 2022-11-17 2023-01-05 2023-04-05 2023-02-04 Q / Tablets for Learning Asse Information System of the M tions nvelope ssment ECYS SX-NRPB-279119-GO-RFQ / P Request for Quota Single Stage - One E TF / B4914 Project Management Post Open - National 0.00 Canceled 2022-02-26 2022-04-23 2022-10-20 roject Management goods tions nvelope NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SX-NRPB-MG-279144-NC-RF Strengthening Management Request for Propo Open - Internationa Single Stage - Two E TF / B4914 Post 0.00 Canceled 2022-07-30 2022-10-15 2022-10-15 2022-08-04 2022-12-24 2023-03-08 2023-04-12 2024-10-03 P / Package for MMIS Implem Information System of the M sals l nvelope entation ECYS SX-NRPB-MG-356528-NC-RF Strengthening Management B / Development and Implem Open - Internationa Single Stage - One E Pending Impl TF / B8048 Information System of the M Post Request for Bids 0.00 2023-04-17 2023-04-25 2023-06-06 2023-07-06 2023-08-10 2025-02-12 entation of a Ministry Manag l nvelope ementation ECYS ement Information System ( MMIS) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SX-NRPB-258510-CS-QCBS / Design Firm Works: Charles L Quality And Cost- Open - Internationa TF / B4914 Rebuilding Inclusive Schools Post 0.00 Canceled 2021-10-21 2021-11-11 2021-12-25 2022-01-22 2022-02-21 2022-03-28 2022-05-02 2023-05-02 eopold Bell School & Philipsb Based Selection l urg Jubilee Library SX-NRPB-MG-279174-CS-QC BS / Package for supervision Quality And Cost- Open - Internationa of works at SLM and CLB sch TF / B4914 Rebuilding Inclusive Schools Post 0.00 Canceled 2022-03-15 2022-04-05 2022-05-19 2022-06-16 2022-07-16 2022-08-20 2022-09-24 2023-09-24 Based Selection l ools and JB Library and Desig n of CLB school and JB Librar y. SX-NRPB-303758-CS-QCBS / Quality And Cost- Open - Internationa Under Implement Package for Supervision of w TF / B4914 Rebuilding Inclusive Schools Post 0.00 2022-11-11 2023-01-20 2022-11-25 2023-01-24 2023-01-08 2023-04-26 2023-02-22 2023-03-24 2023-04-28 2023-05-21 2025-05-31 Based Selection l ation orks at SML SX-NRPB-303762-CS-QCBS / Quality And Cost- Open - Internationa Under Implement Package for Design and Supe TF / B4914 Rebuilding Inclusive Schools Post 0.00 2022-11-18 2023-03-31 2022-12-09 2023-04-12 2023-01-22 2023-03-08 2023-04-07 2023-05-12 2023-06-16 2025-05-31 Based Selection l ation rvision of works of CLB schoo l and PJL INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 SX-NRPB-205589-CS-INDV / Individual Consult TF / B4914 Project Management Post Open 147,000.00 Signed 2021-03-04 2020-12-16 2021-04-29 2021-02-22 2021-05-20 2021-05-26 2021-06-24 2021-05-27 2022-03-15 MECYS Project Manager ant Selection SX-NRPB-205590-CS-CDS / E TF / B4914 Restoring Library Services Post Direct Selection Direct 5,000.10 Signed 2021-02-04 2021-11-01 2021-02-24 2021-11-09 2021-04-30 2022-03-01 2021-10-27 SS8 Cultural Heritage Consul tants SX-NRPB-205592-CS-INDV / Individual Consult Needs Assessment for Inclusi TF / B4914 Restoring Library Services Post Open 17,500.00 Signed 2021-02-04 2020-12-16 2021-04-01 2021-03-26 2021-04-22 2021-03-26 2021-05-27 2021-06-02 2022-02-15 ant Selection ve Education SX-NRPB-205415-CS-INDV / FRLP: Local Consultant to wo Individual Consult rk on strategy and Framewor TF / B4914 Restoring Library Services Post Open 27,000.00 Signed 2021-01-04 2020-12-16 2021-02-22 2021-03-26 2021-03-15 2021-03-26 2021-04-19 2021-05-11 2022-01-08 ant Selection k for SXM Cultural Heritage a nd other Learning Services SX-NRPB-205593-CS-INDV / Strengthening Management Individual Consult TF / B4914 Post Open 43,662.50 Completed 2021-03-01 2021-10-06 2021-04-26 2022-05-03 2021-05-17 2022-05-25 2021-06-21 2022-06-09 2022-03-12 2022-12-28 Development MIS framework Information System of the M ant Selection ECYS SX-NRPB-241375-CS-CDS / P TF / B4914 Project Management Post Direct Selection Direct 63,000.00 Signed 2021-06-25 2021-07-02 2021-07-05 2021-07-02 2021-09-08 2021-07-13 2022-03-07 roject Manager RL SX-NRPB-205594-CS-CDS / D esign Firm Works SML: OZ Ar TF / B4914 Rebuilding Inclusive Schools Post Direct Selection Direct 136,142.40 Completed 2021-03-01 2022-07-05 2021-03-11 2022-02-14 2021-05-15 2022-07-20 2021-11-11 2022-12-30 chitectural Company SX-NRPB-271842-CS-INDV / Individual Consult TF / B4914 Project Management Post Open 0.00 Canceled 2022-01-31 2022-03-21 2022-04-11 2022-05-16 2022-11-12 Project Assistant FRLP ant Selection SX-NRPB-256980-CS-INDV / Individual Consult TF / B4914 Project Management Post Open 0.00 Canceled 2021-10-08 2022-01-10 2021-11-26 2021-12-17 2022-01-21 2022-07-20 Project Engineer/ Contract M ant Selection anager SX-NRPB-205575-CS-INDV / Individual Consult / Restoring Library Services Post Open 0.00 Canceled 2021-01-04 2021-03-01 2021-03-22 2021-04-26 2022-01-15 Technical Assistant Project E ant Selection ngineer SX-NRPB-205576-CS-INDV / Individual Consult / Restoring Library Services Post Open 0.00 Canceled 2021-02-04 2021-04-01 2021-04-22 2021-05-27 2022-02-15 Safeguards Specialist ant Selection SX-NRPB-272516-CS-INDV / Individual Consult TF / B4914 Project Management Post Open 0.00 Canceled 2022-01-13 2022-03-03 2022-03-24 2022-04-28 2022-10-25 Engineer / Contract Manager ant Selection SX-NRPB-300355-CS-INDV / Individual Consult Under Implement TF / B4914 Project Management Post Direct 0.00 2022-06-23 2022-07-28 2022-07-03 2022-07-29 2022-07-24 2022-07-29 2022-08-28 2023-02-24 Project Manager - RL ant Selection ation SX-NRPB-300356-CS-INDV / Individual Consult TF / B4914 Project Management Post Direct 74,946.00 Signed 2022-06-23 2022-06-15 2022-07-03 2022-07-04 2022-07-24 2022-07-05 2022-08-28 2022-07-06 2023-02-24 Project Coordinator - MECYS - ant Selection APFM SX-NRPB-205561-CS-INDV / Individual Consult TF / B4914 Project Management Post Open 0.00 Canceled 2021-01-04 2021-03-01 2021-03-22 2021-04-26 2022-01-15 Procurement Specialist ant Selection SX-NRPB-279130-CS-INDV / Individual Consult TF / B4914 Project Management Post Open 0.00 Canceled 2022-03-15 2022-05-03 2022-05-24 2022-06-28 2022-12-25 Project Engineer/ Contract M ant Selection anager SX-NRPB-MG-324423-CS-IND Strengthening Management Individual Consult Under Implement V / Learning Assessment Enu TF / B8048 Information System of the M Post Direct - National 0.00 2022-11-09 2022-11-22 2022-11-19 2022-11-30 2022-12-10 2023-01-25 2022-12-24 2023-03-31 ant Selection ation merators batch 1 ECYS SX-NRPB-MG-324874-CS-IND Strengthening Management Individual Consult Under Implement V / Learning Assessment Enu TF / B8048 Information System of the M Post Direct - National 0.00 2022-11-21 2023-02-28 2022-12-01 2023-03-03 2022-12-22 2023-03-07 2023-03-31 2023-06-03 ant Selection ation merators batch 2 ECYS SX-NRPB-332223-CS-INDV / Individual Consult TF / B8048 Project Management Post Direct - National 0.00 Signed 2022-12-30 2023-01-26 2023-01-09 2023-01-31 2023-01-30 2023-01-31 2023-03-06 2024-03-05 MECYS Project Coordinator ant Selection SX-NRPB-332225-CS-INDV / Individual Consult Under Implement TF / B8048 Project Management Post Direct - National 0.00 2022-12-30 2023-01-17 2023-01-09 2023-01-19 2023-01-30 2023-01-19 2023-03-06 2023-09-02 Project Manager FRLP ant Selection ation SX-NRPB-MG-339644-CS-IND Strengthening Management Individual Consult TF / B8048 Post Limited 0.00 Canceled 2023-02-08 2023-02-09 2023-02-13 2023-02-10 2023-03-06 2023-04-10 2023-10-07 V / Learning Assessment Con Information System of the M ant Selection sultant ECYS SX-NRPB-MG-339663-CS-CD S / OZ Architectural support f Under Implement TF / B8048 Rebuilding Inclusive Schools Post Direct Selection Direct - National 0.00 2023-02-08 2023-05-28 2023-02-15 2023-06-14 2023-03-22 2025-06-20 or Supervision of Works for Si ation ster Marie Laurence School SX-NRPB-MG-345304-CS-IND Strengthening Management Individual Consult Direct - Internation TF / B8048 Post 0.00 Canceled 2023-02-23 2023-02-24 2023-02-24 2023-02-24 2023-02-28 2023-02-28 2023-03-04 2023-07-02 V / Learning Assessment Con Information System of the M ant Selection al sultant ECYS SX-NRPB-MG-349296-CS-IND Strengthening Management Individual Consult Open - Internationa Under Implement V / Learning Assessment Con TF / B8048 Information System of the M Post 0.00 2023-03-16 2023-03-21 2023-05-04 2023-05-05 2023-05-25 2023-05-05 2023-06-29 2023-10-29 ant Selection l ation sultant - relaunched ECYS SX-NRPB-353813-CS-INDV / Individual Consult Under Implement TF / B8048 Project Management Post Direct - National 0.00 2023-03-31 2023-04-03 2023-04-10 2023-04-06 2023-04-20 2023-04-06 2023-05-25 2023-11-23 FRLP Project Engineer ant Selection ation SX-NRPB-304290-CS-INDV / Individual Consult Open - Internationa TF / B4914 Project Management Post 0.00 Canceled 2022-07-21 2022-09-26 2022-09-08 2022-09-29 2022-11-03 2023-11-03 Project Engineer/ Contract M ant Selection l anager SX-NRPB-279132-CS-INDV / Individual Consult TF / B4914 Project Management Post Open 0.00 Canceled 2022-03-15 2022-07-13 2022-05-03 2022-05-24 2022-06-28 2022-12-25 Project Assistant ant Selection SX-NRPB-364221-CS-INDV / Strengthening Management Individual Consult Direct - Internation Under Implement TF / B8048 Post 0.00 2023-06-01 2023-06-26 2023-06-11 2023-07-02 2023-08-06 2024-08-05 MMIS Quality Assurance Information System of the M ant Selection al ation ECYS SX-NRPB-364225-CS-INDV / Individual Consult Open - Internationa Under Implement TF / B8048 Project Management Post 0.00 2023-06-01 2023-06-23 2023-07-20 2023-08-10 2023-09-14 2024-09-13 MECYS Project Coordinator ant Selection l ation SX-NRPB-364229-CS-INDV / Individual Consult Open - Internationa Pending Impleme TF / B8048 Project Management Post 0.00 2023-06-12 2023-07-31 2023-08-21 2023-09-25 2024-09-24 FRLP Site Engineer ant Selection l ntation SX-NRPB-364236-CS-INDV / Individual Consult Direct - Internation Under Implement TF / B8048 Project Management Post 0.00 2023-06-01 2023-06-26 2023-06-11 2023-06-27 2023-07-02 2023-08-06 2024-08-05 MMIS Implementation Suppor ant Selection al ation t Page 2 STRATEGIC IRRIGATION MODERNIZATION AND URGENT REHABILITATION PROJECT (SIMURP) Summary Procurement Plan Version No.: 1.1 Date: March 16, 2022 I. General Information 1. Project information: a. Country: Indonesia b. Borrower: Ministry of Finance, Republic of Indonesia c. Project Name: Strategic Irrigation Modernization and Urgent Rehabilitation Project (SIMURP) d. Loan No.: IBRD LOAN L0060A; and AIIB LOAN 8891-ID e. Applicable Procurement Procedures: World Bank Procurement and Consultant Guidelines of January 2011, Revised July 2014 f. The Executing Agency: Directorate Irrigation and Lowlands, Directorate General of Water Resources (DGWR), Ministry Public Works and Housing (MPWH) (i) Central Project Management Unit (CPMU): Directorate of Water Resources Development, DGWR, MPWH (ii) Central Project Implementing Unit (CPIU): Directorate Irrigation and Lowland, DGWR, MPWH (CPIU IRWA) (iii) National Project Implementing Unit (NPIU): • Directorate of Operations and Maintenance Directorate General of Natural Resources, MPWH (NPIU OP-PSDA), • Directorate General of Regional Development (SUPD I and SUPD II) Ministry of Home Affairs (NPIU Bangda) • Ministry of Agriculture's Extension and Agricultural Human Resources Development Agency Agriculture (NPIU Agriculture) (iv) Project Implementing Units (PIUs): DGWR’s River Basin Organizations (Balai Besar/Balai Wilayah Sunga, B/BWS) of Brantas, Citarum, Serayu Opak, Sumatera VIII, Sumatera II, Nusa Tenggara I 2. Bank’s No Objection Date of the Procurement Plan: a. Original : May 22, 2018 b. Last version : September 12, 2021 c. This version : March 16, 2022 3. Date of General Procurement Notice: May 7, 2020 4. Period covered by this procurement plan: May 22, 2018 – Project Closing Date (June 30, 2024) II. Types of Contract, Bank’s Review Requirements and Applied Methods A. Works, Goods and Non-Consulting Services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Procurement Guidelines: Ref. Procureme Bank’s Review Procurement Method No. nt Method Requirement 1. International Competitive ≥ $25 million Threshold Each contract shall Bidding (Works) be subject to Bank’s prior review. 2. National Competitive < $25 million Each contract ≥ Bidding (Works) $10 million equivalent shall be subject to Bank’s prior review. All other contracts 3. Shopping for Works < $200k subject No post prior to review review. (only post review). 4. International Competitive ≥$2 million Each contract ≥ $2 Bidding (Goods) million equivalent shall be subject to Bank’s prior review. All other contracts subject to post 5. National Competitive review. <$2 million Each contract ≥ $2 Bidding (Goods) million equivalent shall be subject to Bank’s prior review. All other contracts subject to post 6. Shopping for Goods <100k review. No prior review (only post review). 7. International Competitive ≥$10 million Each contract shall Bidding (Non-Consultant be subject to Bank’s Service) prior review. 8. National Competitive <$10 million Each contract ≥ $2 Bidding (Non-Consultant million equivalent Service) shall be subject to Bank’s prior review. All other contracts subject to post 9. Shopping for Non- <$100k review. No prior review Consulting Services (only post review). 10. Direct Contracting Subject to ≥ $2million and paragraph justification shall be 3.7 of the provided when Procurement submit procurement Guidelines plan. 1. Pre-qualification: Prequalification is not used instead post qualification shall be followed for all national competitive bidding under the project. 2. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: As specified in the Project Operations Manual (POM) 3. Reference to (if any) Project Operational/Procurement Manual: Project Operations Manual of SIMURP 4. Any Other Special Procurement Arrangements: -NA- 5. Summary of the Procurement Packages 1 2 3 4 5 Ref. Description Review Estimate Number No. by Bank d of Cost Package (US$ s mil.) ICB A. 1. Works Prior - - 2. Goods and Supply Prior 2.5 1 &Installation 3. Non-consulting Services Prior - - B. NCB 1. Works Prior 165 11 2. Works Post 82 17 3. Goods and Supply & Prior - - Installation 4. Goods and Supply & Post - - Installation 5. Non-consulting Services Prior - - 6. Non-consulting Services Post 0.2 3 C. Shopping 1. Works Post 2. Goods Post 0.18 7 3. Non-consulting Services Post 0.32 5 D. Direct Contracting 1. Works Post - - 2. Goods Post 0.56 1 3. Non-consulting Services Post 0.28 2 Total (All methods and Review 250,85 44 Requirements) B. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to prior review by Bank as stated in Appendix 1 to the Consultant Guidelines: Ref. Selection Selection Method Bank’s Prior Review No. Method Threshold Requirement 1. QCBS and all Applied to all Each contract equal to other methods, estimated value. No or above $1,000,000 including QBS, threshold. equivalent shall be FBS and LCS subject to Bank’s prior (Firms) review. All other contracts subject to post review. (Prior review from technical perspective of only the draft TOR 2. CQS (Firms) Only for estimated and No draft prior cost (only review contract value < $ estimate). post review). 300,000 as per paragraph 3.7 of the 3. Single Source Consultant No selection Guidelines. method Each contract equal to Selection of threshold. Subject to or above $1,000,000 Firms justification for Singe equivalent shall be Source Selection of subject to Bank’s prior firms as per para. 3.9 review. All other and 3.10 of the contracts subject to Consultant Guidelines. post review. (Prior review from technical perspective of only the draft TOR, Justification for use of Single Source Selection method and draft cost estimate, shall be sent for the Bank’s prior approval as part of the procurement plan). Ref. Selection Selection Method Bank’s Prior Review No. Method Threshold Requirement 4. Competitive No threshold. No prior review (only Selection of post review), unless Individual contract is equal to or Consultants above $300,000. (comparison of at least 3 CVs) (Prior review from technical perspective of only the draft TOR. In addition, the Bank’s prior review and no objection shall be also obtained for the exceptional deviations from the normal competitive selection procedure of individual consultants subject to the Bank’s expost- 5. Single Source No Threshold. No prior review in (only review listed Selection of post review), paragraph 5.4unless (a)-(c) of Individual Subject to justification the Consultant to or contract is equal Consultants for single source of above $300,000. Guidelines). individuals as per para. 5.4 of the (Prior review from Consultant Guidelines technical perspective of only the draft TOR, Justification for use of Single Source Selection method together with CV of the recommended candidate and draft cost estimate, shall be sent for the Bank’s 2. Short list comprising entirely of national consultants prior approval : Short as part of the procurement list of consultants for services (firms), estimated to cost less than US$ 400,000 equivalent per contract, may plan).comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: N/A 4. Summary of Consultancy Assignments 1 2 3 4 5 Ref. Description Review Estimate Number No. by Bank d of Cost Package (US$ s mil.) A. Consulting Firm 1. QCBS and all other Prior 64.7 9 methods 2. QCBS and all other Post 0.56 1 methods 3. CQS Post 0.26 2 4. Single-Source Post/Prior - - Sub-total (All methods and Review 65.52 12 Requirements) B. Individual Consultant 1. Competitive Selection Prior - - 2. Single-Source Prior - - 3. Competitive Selection Post 0.89 141) 4. Single-Source Post 0.38 3 Sub-total (All methods and Review 1.27 17 Requirements) 1) limited approach PROCUREMENT Indonesia : Strategic Irrigation Modernization and Urgent Rehabilitation Project PLAN General Information Country: Indonesia Bank’s Approval Date of the Original Procurement Plan: 2020-04-09 Revised Plan Date(s): (comma delineated, leave blank if2023-05-28 none) Project ID: P157585 GPN Date: 2020-05-07 Project Name: Strategic Irrigation Modernization and Urgent Rehabilitation Project Loan / Credit No: COFN / C1530, IBRD / 88910 Ministry of Home Affairs, Directorate of Synchronization of Regional Government Affairs II Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-SUPD II-169088-NC-RFB / Component A: Urgent Rehab Single Stage - One E Pending Impl Socialization of KPI guideline IBRD / 88910 ilitation of Irrigation and Drai Post Request for Bids Open - National 86,256.00 0.00 2020-04-27 2020-04-30 2020-05-21 2020-05-28 2020-06-02 2020-07-02 nvelope ementation s nage System ID-SUPD II-168873-NC-RFB / Component A: Urgent Rehab Socialization of PPSIP Guideli Single Stage - One E Pending Impl IBRD / 88910 ilitation of Irrigation and Drai Post Request for Bids Open - National 86,256.00 0.00 2020-04-27 2020-04-30 2020-05-21 2020-05-28 2020-06-02 2020-07-02 nes and the Implementation nvelope ementation nage System of Gender Mainstreaming in PPSIP ID-SUPD II-189419-NC-DIR / Component A: Urgent Rehab Public Service Advertisement Under Imple IBRD / 88910 ilitation of Irrigation and Drai Post Direct Selection Direct 14,376.00 0.00 2020-08-25 2020-08-14 2020-09-01 2020-09-11 2020-10-13 about Participative Irrigation mentation nage System System Development and Ma nagement Policy ID-SUPD II-189438-NC-DIR / Public Service Advertisement Component A: Urgent Rehab about Gender Mainstreaming Pending Impl IBRD / 88910 ilitation of Irrigation and Drai Post Direct Selection Direct 14,376.00 0.00 2020-08-25 2020-09-01 2020-09-11 2020-10-13 in the Implementation of Part ementation nage System icipative Irrigation System De velopment and Management ID-SUPD II-189442-NC-RFB / Component A: Urgent Rehab Single Stage - One E Under Imple SIMURP Activities Implement IBRD / 88910 ilitation of Irrigation and Drai Post Request for Bids Open - National 52,099.00 0.00 2020-08-26 2020-10-22 2020-08-29 2020-09-19 2020-09-26 2020-10-01 2020-10-31 nvelope mentation ation Coordination Meeting – nage System Component A ID-SUPD II-235505-NC-RFQ / Component A: Urgent Rehab Request for Quota Single Stage - One E SIMURP Activities Implement IBRD / 88910 ilitation of Irrigation and Drai Post Limited 71,880.00 65,230.07 Signed 2021-05-21 2021-05-17 2021-05-28 2021-06-07 2021-06-11 tions nvelope ation Coordination Meeting – nage System Component A ID-SUPD II-238641-NC-RFQ / Coordination Meeting for Rev Component A: Urgent Rehab Request for Quota Single Stage - One E italization and Preparation of IBRD / 88910 ilitation of Irrigation and Drai Post Limited 71,880.00 70,017.93 Signed 2021-06-08 2021-09-24 2021-06-16 2021-10-08 2021-07-06 tions nvelope Work Program of the Irrigatio nage System n Commission in the Compon ent A ID-SUPD II-254723-NC-RFQ / Coordination Meeting for Rev Component A: Urgent Rehab Request for Quota Single Stage - One E italization and Preparation of IBRD / 88910 ilitation of Irrigation and Drai Post Limited 53,191.00 52,068.83 Signed 2021-10-09 2021-10-05 2021-10-23 2021-10-19 2021-11-12 tions nvelope Work Program of the Irrigatio nage System n Commission in the Compon ent B ID-SUPD II-282811-NC-RFQ / Non Consulting Services (Eve Component A: Urgent Rehab Request for Quota Single Stage - One E nt Organizer) for Workshops IBRD / 88910 ilitation of Irrigation and Drai Post Limited 71,880.00 68,870.32 Signed 2022-03-11 2022-04-12 2022-03-25 2022-04-28 2022-04-14 tions nvelope Capacity Strengthening Wate nage System r User Association (P3A) Com ponent A ID-SUPD II-282812-NC-RFQ / Component A: Urgent Rehab Non Consulting Services (Eve Request for Quota Single Stage - One E IBRD / 88910 ilitation of Irrigation and Drai Post Limited 68,286.00 62,598.66 Signed 2022-05-10 2022-09-15 2022-05-26 2022-10-06 2022-06-15 nt Organizer) for Workshops tions nvelope nage System Gender Mainstreaming In PPS IP Component A ID-SUPD II-282813-NC-RFQ / Component B: Strategic Mod Non Consulting Services (Eve Request for Quota Single Stage - One E IBRD / 88910 ernization of Irrigation and D Post Limited 52,329.00 0.00 Signed 2022-05-10 2022-10-07 2022-05-27 2022-06-16 nt Organizer) for Workshops tions nvelope rainage System Gender Mainstreaming In PPS IP Component B ID-SUPD II-294503-NC-RFQ / Component A: Urgent Rehab Video profile production of PP Request for Quota Single Stage - One E IBRD / 88910 ilitation of Irrigation and Drai Post Limited 14,376.00 13,365.01 Signed 2022-05-18 2022-06-15 2022-06-02 2022-06-25 2022-07-01 SIP policies in P3A empower tions nvelope nage System ment activities SIMURP Progr am Component – A ID-SUPD II-361186-NC-RFQ / Video profile production of B Component A: Urgent Rehab Request for Quota Single Stage - One E Pending Impl uilding Exit Strategy Models f IBRD / 88910 ilitation of Irrigation and Drai Post Limited 14,736.00 0.00 2023-06-09 2023-06-30 2023-07-30 tions nvelope ementation or Strengthening Irrigation M nage System anagement Institutional Capa city in the Regions ID-SUPD II-361187-NC-RFQ / Video profile production of E Component A: Urgent Rehab mpowering Water-User Farm Request for Quota Single Stage - One E Pending Impl IBRD / 88910 ilitation of Irrigation and Drai Post Limited 14,736.00 0.00 2023-06-09 2023-06-30 2023-07-30 ers through the Development tions nvelope ementation nage System of Productive Economic Enter prises at the irrigation schem e level Page 1 ID-SUPD II-361189-NC-RFQ / Video profile production of Pa Component A: Urgent Rehab rticipation of Farmers Using Request for Quota Single Stage - One E Pending Impl IBRD / 88910 ilitation of Irrigation and Drai Post Limited 14,736.00 0.00 2023-06-09 2023-06-30 2023-07-30 Water Through P3A/GP3A/IP3 tions nvelope ementation nage System A in Supporting the Operatio n, Maintenance and Rehabilit ation of Irrigation Networks ID-SUPD II-361190-NC-RFQ / Non Consulting Services (Eve Component A: Urgent Rehab nt Organizer) for Workshop o Request for Quota Single Stage - One E IBRD / 88910 ilitation of Irrigation and Drai Post Limited 66,633.00 0.00 Signed 2023-06-09 2023-06-08 2023-06-30 2023-07-30 n Regional Program Synergy tions nvelope nage System in Supporting Capacity Stren gthening of P3A/GP3A/IP3A C omponent A ID-SUPD II-361192-NC-RFQ / Non Consulting Services (Eve Component A: Urgent Rehab Request for Quota Single Stage - One E Pending Impl nt Organizer) for Local Gover IBRD / 88910 ilitation of Irrigation and Drai Post Limited 61,098.00 0.00 2023-06-09 2023-06-30 2023-07-30 tions nvelope ementation nment Commitment Support nage System Meeting in PPSI Policy Imple mentation in the Regions ID-SUPD II-361194-NC-RFQ / Non Consulting Services (Eve Component B: Strategic Mod Request for Quota Single Stage - One E Pending Impl nt Organizer) for Regional Co IBRD / 88910 ernization of Irrigation and D Post Limited 47,374.00 0.00 2023-06-09 2023-06-30 2023-07-30 tions nvelope ementation mmittee Performance Evalua rainage System tion Coordination Meeting - C omponent B CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-SUPD II-123372-CS-CQS / The objective of this activity i s to develop regional water r esources/irrigation database Component C: Project Mana Consultant Qualifi Under Implement COFN / C1530 Post Open - National 42,984.47 0.00 2019-07-19 2020-04-29 2019-07-26 2019-08-09 2019-08-16 2019-08-26 2019-12-24 for managing regional gover gement cation Selection ation nment affairs II (SDA/irrigatio n in particular) as part of the implementation of duties and functions as well as facilitatio n ID-SUPD II-168863-CS-QCBS / Technical Assistance Institu Component C: Project Mana Quality And Cost- Open - Internationa IBRD / 88910 Prior 2,127,660.00 2,097,888.05 Signed 2020-04-27 2020-05-07 2020-05-12 2020-05-19 2020-06-09 2020-08-06 2020-06-16 2020-09-22 2020-06-30 2020-10-20 2020-07-28 2020-11-22 2020-09-01 2020-11-30 2024-05-31 tion Development Participato gement Based Selection l ry Irrigation Management (TA IDPIM) ID-SUPD II-168867-CS-QCBS / Technical Assistance Manag Component A: Urgent Rehab ement Support of P3A/GP3A / Quality And Cost- Open - Internationa IBRD / 88910 ilitation of Irrigation and Drai Prior 1,516,648.00 2,345,899.98 Signed 2020-04-27 2020-05-07 2020-05-12 2020-05-20 2020-06-09 2020-08-25 2020-06-16 2020-10-02 2020-06-30 2020-10-25 2020-07-28 2020-11-13 2020-09-01 2020-11-22 2024-05-31 IP3A for Formation and Empo Based Selection l nage System werment Programs by Comm unity Counselor (TPM/ KTPM) - Component A ID-SUPD II-168869-CS-QCBS / Technical Assistance Manag Component B: Strategic Mod ement Support of P3A/GP3A / Quality And Cost- Open - Internationa IBRD / 88910 ernization of Irrigation and D Prior 3,042,815.00 2,993,119.31 Signed 2020-04-27 2020-05-07 2020-05-12 2020-05-21 2020-06-09 2020-08-25 2020-06-16 2020-10-02 2020-06-30 2020-11-09 2020-07-28 2020-11-24 2020-09-01 2020-12-01 2024-05-31 IP3A for Formation and Empo Based Selection l rainage System werment Programs by Comm unity Counselor (TPM/ KTPM) - Component B (Jatiluhur) ID-SUPD II-168870-CS-CQS / Component A: Urgent Rehab Technical Assistance Syncron Consultant Qualifi IBRD / 88910 ilitation of Irrigation and Drai Post Open - National 215,614.00 277,758.89 Signed 2020-04-27 2020-05-22 2020-05-18 2020-06-12 2020-06-15 2020-09-21 2020-06-29 2020-09-27 2020-07-13 2020-09-20 2021-11-30 ization Regional Irrigation Ma cation Selection nage System nagement Database ID-SUPD II-316206-CS-CQS / Consultant Services Technica Component A: Urgent Rehab Consultant Qualifi Pending Impleme l Assistance Strengthening S IBRD / 88910 ilitation of Irrigation and Drai Post Open - National 77,451.00 0.00 2022-09-22 2022-10-06 2022-10-20 2022-10-21 2022-10-27 2023-03-28 cation Selection ntation DA Database Management /Ir nage System rigation in the SIMURP Progra m INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-SUPD II-456-CS-INDV / Fin Component C: Project Mana Individual Consult Under Implement IBRD / 88910 Post Direct 15,813.68 0.00 2020-01-07 2020-01-07 2020-01-21 2020-01-24 2020-01-31 2020-12-31 ancial management Individu gement ant Selection ation al Expert ID-SUPD II-123-CS-INDV / Ins Component C: Project Mana Individual Consult Under Implement IBRD / 88910 Post Direct 15,813.68 0.00 2020-01-07 2020-01-07 2020-01-21 2020-01-24 2020-01-31 2020-12-31 titutional Irrigation Individual gement ant Selection ation Expert Page 2 PROCUREMENT PLAN (Textual Part) Project information: Digital Cabo Verde Project - P171099 Implementation agency: UGPE (Unidade de Gestão de Projetos Especiais) Date of the Procurement Plan: February 28, 2020 Period covered by this Procurement Plan: February, 2020 - February 28, 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. “Not Applicable” Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Cabo Verde : Digital Cabo Verde Project PLAN General Information Country: Cabo Verde 2020-02-28 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171099 GPN Date: 2021-06-28 Project Name: Digital Cabo Verde Project Loan / Credit No: IDA / V3050, / , IDA / 67920 Unidade de Gestao de Projectos Especiais Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 09/GO/DCVP/UGPE/2020 / Pu Component 2: Digital Compe Request for Quota Single Stage - One E rchase of 700 Tablets for Ne IDA / V3050 Post Limited 137,000.00 141,700.03 Completed 2020-06-12 2020-06-24 2020-08-07 2020-08-01 2021-02-03 2020-10-28 titiveness tions nvelope w Education staff RFQ#15/GO/DCVP/UGPE/202 Component 3: Digital Public 0 / Purchase of 193 computer IDA / 67920 Post Direct Selection Direct 250,000.00 298,645.18 Signed 2021-01-21 2020-12-15 2021-01-21 2020-12-17 2021-03-03 2021-02-16 2021-08-30 Services and Marketplace s for diplomatic missions 26/DCVP/UGPE/2021 / Foreig Component 3: Digital Public Request for Quota Single Stage - One E Under Imple IDA / 67920 Post Limited 70,000.00 0.00 2021-11-10 2022-01-05 2022-05-05 n trade portal (goods aquisiti Services and Marketplace tions nvelope mentation on) 32/DCVP/UGPE/2021 / Goods Component 3: Digital Public Request for Quota Single Stage - One E aquisition - (tablet, sensor, s IDA / 67920 Post Limited 100,000.00 0.00 Canceled 2021-04-25 2021-06-20 2021-12-17 Services and Marketplace tions nvelope martphone,etc) 32/DCVP/UGPE/2021-2 / Goo Component 3: Digital Public Open - Internationa Single Stage - One E ds aquisition - (tablet, sensor IDA / 67920 Post Request for Bids 120,000.00 76,925.01 Signed 2021-11-17 2022-02-24 2021-11-22 2022-03-02 2022-01-03 2022-03-28 2022-02-02 2022-04-26 2022-03-09 2022-05-23 2022-09-05 Services and Marketplace l nvelope , smartphone,etc) 23/DCVP/UGPE/2021 / Purch ase of equipment and other s Component 2: Digital Compe Open - Internationa Single Stage - One E IDA / 67920 Prior Request for Bids 3,500,000.00 0.00 Canceled 2021-10-13 2021-10-18 2021-11-29 2021-12-29 2022-02-02 2022-08-01 upplies/materials for the impl titiveness l nvelope ementation of 44 new web L abs II 41/DCVP/UGPE/2022 / Purch ase of equipment and other s Component 2: Digital Compe Open - Internationa Single Stage - One E IDA / 67920 Post Request for Bids 1,400,000.00 0.00 Canceled 2022-08-03 2022-08-04 2022-08-08 2022-08-30 2022-09-19 2022-10-03 2022-10-19 2022-11-23 2023-05-22 upplies/materials for the for t titiveness l nvelope he assembly of ICT labs – We bLab II 45/DCVP/UGPE/2022 / Purch ase of Goods for the WebLab Component 2: Digital Compe Request for Quota Single Stage - One E Under Imple s II: Lot 1 - Purchase of fire IDA / 67920 Post Open - National 100,000.00 0.00 2022-12-05 2023-01-30 2023-07-29 titiveness tions nvelope mentation extinguishers: ii) Lot 2 - Purc hase of office cabinets; iii) Lo t 3 - Purchase of air condition ers 49/DCVP/UGPE/2023 / Purch ase of equipment and other s Component 2: Digital Compe Open - Internationa Single Stage - One E Under Imple IDA / 67920 Post Request for Bids 1,400,000.00 0.00 2023-03-02 2023-03-15 2023-03-07 2023-03-15 2023-04-18 2023-05-05 2023-05-18 2023-06-02 2023-06-22 2023-12-19 upplies/materials for the for t titiveness l nvelope mentation he assembly of ICT labs – We bLab II NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 08/NCS/DCVP/UGPE/2020 / P roduction of 640 Video Lesso ns: Component 5: Contingent E Lot 1: Production of 320 Vide IDA / V3050 mergency Response Compo Post Direct Selection Direct 210,000.00 223,045.14 Completed 2020-06-04 2020-06-04 2020-06-09 2020-07-13 2020-07-14 2020-07-18 2021-01-10 2020-11-25 o-Lessons for the Basic and S nent econdary schools Lot 2: Production of 320 Vid eo-Lessons for the Basic and Secondary schools 25/DCVP/UGPE/2021-2 / Fore ign Trade Manual (Semantics Component 3: Digital Public Request for Quota Single Stage - One E Under Imple IDA / 67920 Post Open - National 50,000.00 0.00 2021-11-10 2022-01-05 2022-06-04 , Grammar and Outreach Ca Services and Marketplace tions nvelope mentation mpaign of the Trade Manual) 48/DCVP/UGPE/2023 / Capac ity purchase for education (F Component 2: Digital Compe Single Stage - One E Under Imple ornecimento de Conectividad IDA / 67920 Post Request for Bids Open - National 1,700,000.00 0.00 2023-01-19 2023-02-07 2023-01-24 2023-03-07 2023-04-27 2023-04-06 2023-05-11 2023-11-07 titiveness nvelope mentation e em Banda Larga para as es colas básicas e secundárias d e Cabo Verde CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 01/CS/DCVP/UGPE/2020 / Te chnical Assistance to prepare a legal, policy and regulatory assessment to identify gaps Component 1: Enabling Lega Quality And Cost- Open - Internationa and gray zones, notably for f IDA / V3050 l and Regulatory Environme Post 250,000.00 226,000.00 Terminated 2020-06-10 2020-06-10 2020-06-30 2020-06-11 2020-07-19 2020-08-26 2020-08-18 2020-10-07 2020-09-17 2020-11-24 2020-10-22 2020-12-16 2020-11-26 2021-01-20 2021-11-26 Based Selection l orward-looking NextGen Tele nt communications (5G), data g overnance and emerging tec hnologies deployment (i.e., s andboxes and scaling) Page 1 02/CS/DCVP/UGPE/2020 / Te chnical Assistance to prepare Component 1: Enabling Lega Quality And Cost- Open - Internationa the feasibility study and biddi / l and Regulatory Environme Post 300,000.00 0.00 Canceled 2020-03-31 2020-04-21 2020-06-04 2020-07-02 2020-08-01 2020-09-05 2020-10-10 2021-10-10 Based Selection l ng documentation for the pur nt chase of international bandwi dth capacity 04/CS/DCVP/UGPE/2020 / Di gital Skills Technical Assistan ce for the preparation of the Component 2: Digital Compe Quality And Cost- Open - Internationa / Post 400,000.00 0.00 Canceled 2020-03-31 2020-04-21 2020-06-04 2020-07-02 2020-08-01 2020-09-05 2020-10-10 2021-10-10 national capacity developme titiveness Based Selection l nt strategy: Pilot Project “Sha ping the Future: Digital Skills for Digital Nation in Cabo Ver de 10/DCVP/UGPE/2020 / Techn ical Assistance for developin g a videoconferencing Syste Component 3: Digital Public Consultant Qualifi IDA / V3050 Post Limited 300,000.00 407,501.57 Signed 2020-07-27 2020-07-27 2020-08-03 2020-09-07 2020-08-13 2020-11-09 2020-08-23 2020-11-12 2021-02-19 m, a biometric data capture Services and Marketplace cation Selection System and an electronic sig nature APP all working fully i ntegrated with the Consular Portal 13/DCVP/UGPE/2020 / TA for the implementation and mai ntenance of the ComVida Pla Component 3: Digital Public Consultant Qualifi tform – (Official platform of t IDA / V3050 Post Limited 320,000.00 275,636.00 Signed 2020-07-27 2020-07-28 2020-08-10 2020-09-15 2020-09-09 2020-11-12 2020-10-14 2020-11-14 2021-04-12 Services and Marketplace cation Selection he government of Cabo Verd e) -To implement Health Pass port Solution based on intero perable platform Blockchain. 17/DCVP/UGPE/2021 / TA leg al for Cybersecurity Policy an d Strategy: data protection, c Component 1: Enabling Lega ybersecurity legal, cloud com Quality And Cost- Open - Internationa Under Implement IDA / 67920 l and Regulatory Environme Post 300,000.00 0.00 2021-02-10 2022-03-22 2021-03-03 2022-07-20 2021-04-16 2021-05-14 2021-06-13 2021-07-18 2021-08-22 2022-01-19 puting legal, infrastion regula Based Selection l ation nt tion, mobile payment system , digital signature and certific ation, time stamping, emerg ency communication 22/DCVP/UGPE/2021 / Techn ical Assistance to conduct a f Component 2: Digital Compe Consultant Qualifi Open - Internationa easibility study and prepare IDA / 67920 Post 150,000.00 150,000.00 Signed 2021-02-01 2021-03-30 2021-02-22 2021-04-05 2021-04-07 2021-06-25 2021-05-07 2021-08-04 2021-06-11 2021-08-21 2021-10-09 titiveness cation Selection l bidding documents to purcha se broadband capacity for pri mary 27/DCVP/UGPE/2021 / Foreig n trade portal ( phase 1 - Sys Component 3: Digital Public Consultant Qualifi IDA / 67920 Post Open - National 80,000.00 0.00 Canceled 2021-02-17 2021-06-30 2021-03-10 2021-04-23 2022-01-31 2021-05-23 2021-06-27 2021-12-24 tem development): publicatio Services and Marketplace cation Selection n and dissemination of infor mation 19/DCVP/2021 / Accounting and Financing audit Development of Financial an d Aaccounting Audits for the DIGITAL CABO VERDE PROJE Component 4: Project Imple Least Cost Selecti Open - Internationa IDA / 67920 Post 100,000.00 41,640.00 Signed 2021-03-24 2021-03-31 2021-04-14 2021-04-01 2021-05-28 2021-06-25 2021-06-25 2021-08-05 2021-07-25 2021-08-26 2021-08-29 2021-09-15 2021-10-03 2021-10-09 2024-10-02 CT (IDA CREDITS Ref. V3050 mentation Support on l and 6792-CV) and HARMONINZING AND IMP ROVING STATISTICS IN WEST AFRICA PROJECT (IDA CREDIT Ref. 6574-CV) 29/DCVP/UGPE/2021 / Natio Component 3: Digital Public Consultant Qualifi nal System of Management N IDA / 67920 Post Open - National 50,000.00 0.00 Canceled 2021-10-13 2021-11-04 2021-12-18 2022-01-17 2022-02-21 2022-05-22 Services and Marketplace cation Selection otifications ( phase 2- Syste m development) 20/DCVP/UGPE/2021 / Desig Component 3: Digital Public Consultant Qualifi n and development of a vacci IDA / 67920 Post Limited 100,000.00 0.00 Canceled 2021-04-22 2021-04-22 2021-05-06 2021-06-05 2021-07-10 2021-08-29 Services and Marketplace cation Selection nation management system 37/DCVP/UGPE/2021 / Techn ical Assistance to prepare an Component 1: Enabling Lega d support an Integrated key- Quality And Cost- Open - Internationa IDA / 67920 l and Regulatory Environme Post 220,000.00 0.00 Canceled 2021-08-12 2021-08-18 2021-09-02 2021-11-24 2021-10-16 2022-02-11 2021-11-13 2022-03-25 2021-12-13 2022-05-09 2022-01-17 2022-02-21 2022-08-20 competency-based Human C Based Selection l nt apital Management Model, fo r NOSi – Núcleo Operacional da Sociedade de Informação 38/DCVP/UGPE/2021 / Asses sment of the value of the ass Component 1: Enabling Lega ets and liabilities of the physi Quality And Cost- Open - Internationa Under Implement IDA / 67920 l and Regulatory Environme Post 250,000.00 0.00 2021-08-12 2021-08-18 2021-09-02 2021-12-21 2021-10-16 2022-03-16 2021-11-13 2022-04-27 2021-12-13 2022-06-09 2022-01-17 2022-09-21 2022-02-21 2022-06-21 cal component of the RTPE a Based Selection l ation nt s a WAN infrastructure, for N OSi – Núcleo Operacional da Sociedade de Informação 25/DCVP/UGPE/2021 / Foreig Component 3: Digital Public Consultant Qualifi IDA / 67920 Post Open - National 50,000.00 0.00 Canceled 2021-04-20 2021-06-30 2021-05-11 2021-06-24 2021-07-24 2021-08-28 2022-01-25 n trade Manual (outreach ca Services and Marketplace cation Selection mpaign 31/DCVP/UGPE/2021 / Unifie Component 3: Digital Public Consultant Qualifi d system for sharing informa IDA / 67920 Post Open - National 50,000.00 0.00 Canceled 2021-10-06 2021-10-27 2021-12-10 2022-01-09 2022-02-13 2022-05-14 Services and Marketplace cation Selection tion and booking joint interve ntions 16/DCVP/UGPE/2021 / TA to create a legal and regulatory framework allowing to test in Component 1: Enabling Lega Quality And Cost- Open - Internationa real environment of new tech IDA / 67920 l and Regulatory Environme Post 250,000.00 0.00 Canceled 2021-12-15 2022-01-05 2022-02-18 2022-03-18 2022-04-17 2022-05-22 2022-06-26 2022-11-23 Based Selection l nologies in areas whose legis nt lation or regulation can act a s a disincentive to the imple mentation of new technologi es 35/DCVP/UGPE/2021 / Progr Component 3: Digital Public Consultant Qualifi Open - Internationa am to reduce the digital gap i IDA / 67920 Post 150,000.00 0.00 Canceled 2021-11-14 2021-12-05 2022-01-18 2022-02-17 2022-03-24 2022-07-22 Services and Marketplace cation Selection l n emigrated communities 36/DCVP/UGPE/2021 / E-ID & Component 3: Digital Public Quality And Cost- Open - Internationa IDA / 67920 Post 822,000.00 0.00 Canceled 2021-11-21 2021-12-12 2022-01-25 2022-02-22 2022-03-24 2022-04-28 2022-06-02 2023-05-28 SNIAC consolidation Services and Marketplace Based Selection l 24/DCVP/UGPE/2021 / TA to i Component 2: Digital Compe Quality And Cost- Open - Internationa IDA / 67920 Post 350,000.00 0.00 Canceled 2021-02-10 2021-04-13 2021-03-03 2021-06-28 2021-04-16 2021-05-14 2021-06-13 2021-07-18 2021-08-22 2022-04-19 mplement Code for All progr titiveness Based Selection l am 28/DCVP/UGPE/2021 / Techn ical Assistance to develop Di Component 2: Digital Compe Quality And Cost- Open - Internationa IDA / 67920 Post 250,000.00 0.00 Canceled 2021-09-01 2021-09-20 2021-09-08 2021-09-21 2021-10-22 2021-11-19 2021-12-19 2022-01-23 2022-02-27 2022-08-26 gital Economy Strategy and I titiveness Based Selection l mplementation roadmap 39/DCVP/UGPE/2021 / Techn Component 3: Digital Public Quality And Cost- Open - Internationa Under Implement ical Assistance to upgrade th IDA / 67920 Post 350,000.00 0.00 2022-06-10 2022-05-31 2022-07-01 2022-06-22 2022-08-14 2022-09-11 2022-10-11 2022-11-15 2022-12-20 2023-12-20 Services and Marketplace Based Selection l ation e consular portal mobile app Page 2 42/DCVP/UGPE/2022 / Comm unication Strategy of the Con Component 3: Digital Public Consultant Qualifi Under Implement IDA / 67920 Post Open - National 100,000.00 0.00 2022-10-19 2022-10-16 2022-11-09 2022-12-23 2023-01-18 2023-01-22 2023-02-26 2023-11-23 sular Portal (Esteratégia de C Services and Marketplace cation Selection ation omunicação do portal Consul ar) 37/DCVP/UGPE/2022-2 / Tec hnical Assistance to prepare Component 1: Enabling Lega and support an integrated ke Quality And Cost- Open - Internationa Under Implement IDA / 67920 l and Regulatory Environme Post 450,000.00 0.00 2022-10-19 2022-10-19 2022-11-09 2022-10-26 2022-12-23 2023-01-20 2023-02-19 2023-03-26 2023-04-30 2023-10-27 y-competency-based Human Based Selection l ation nt Capital Management Model f or NOSi – Núcleo Operacional da Sociedade de Informação 44/DCVP/UGPE/2022 / Techn ical Assistance to strengthen regulatory tools for ex-ante r egulation on the wholesale a Component 1: Enabling Lega Quality And Cost- Open - Internationa Under Implement nd retail electronic communi IDA / 67920 l and Regulatory Environme Post 400,000.00 0.00 2022-11-24 2022-12-01 2022-12-15 2022-12-05 2023-01-28 2023-02-25 2023-03-27 2023-05-01 2023-06-05 2024-06-04 Based Selection l ation cations markets (focused on nt dominant position, asymmetr ic regulation for fixed and mo bile broadband, cost models for fixed and mobile 46/DCVP/UGPE/2022 / Consu ltancy Services to define a Ta Component 3: Digital Public Quality And Cost- Open - Internationa x and Customs information s IDA / 67920 Post 250,000.00 0.00 Canceled 2022-11-24 2022-12-01 2022-12-15 2023-01-28 2023-02-25 2023-03-27 2023-05-01 2023-06-05 2024-06-04 Services and Marketplace Based Selection l ystem architecture and conc eptual Interoperability model definition 47/DCVP/UGPE/2022 / Consu ltancy Services to develop an IT platform that allows imple Component 3: Digital Public Consultant Qualifi mentation of an Automatic E IDA / 67920 Post Open - National 150,000.00 0.00 Canceled 2022-12-09 2023-01-18 2022-12-30 2023-02-12 2023-03-14 2023-04-18 2023-10-15 Services and Marketplace cation Selection xchange of Information (AEOI ) in tax matters, to support t he operationalization of an in formation exchange office 46/DCVP/UGPE/2023 / Consu ltancy Services to define a Ta Component 3: Digital Public Consultant Qualifi x and Customs information s IDA / 67920 Post Open - National 150,000.00 0.00 Canceled 2023-02-10 2023-02-10 2023-03-03 2023-04-16 2023-05-16 2023-06-20 2023-12-17 Services and Marketplace cation Selection ystem architecture and conc eptual Interoperability model definition 47/DCVP/UGPE/2023 / Consu ltancy Services to develop an IT Solution that allows imple Component 3: Digital Public Quality And Cost- Open - Internationa Under Implement mentation of an Automatic E IDA / 67920 Post 250,000.00 0.00 2023-02-10 2023-02-10 2023-03-03 2023-02-13 2023-04-16 2023-05-14 2023-06-13 2023-07-18 2023-08-22 2024-02-18 Services and Marketplace Based Selection l ation xchange of Information (AEOI ) in tax matters, to support t he operationalization of an in formation exchange office 46/DCVP/UGPE/2023-2 / Con sultancy Services to define a Component 3: Digital Public Consultant Qualifi Open - Internationa Under Implement Tax and Customs information IDA / 67920 Post 150,000.00 0.00 2023-02-15 2023-02-28 2023-03-08 2023-03-15 2023-04-21 2023-05-21 2023-06-25 2023-12-22 Services and Marketplace cation Selection l ation system architecture and con ceptual Interoperability mode l definition 51/DCVP/UGPE/2023 / Capac ity building for Direção Nacio nal das Receitas do Estado ( Component 3: Digital Public Consultant Qualifi Under Implement IDA / 67920 Post Open - National 100,000.00 0.00 2023-03-15 2023-03-24 2023-04-05 2023-05-19 2023-06-18 2023-07-23 2024-01-19 DNRE) civil servant (Assistên Services and Marketplace cation Selection ation cia Técnica e Formação no â mbito da implementação SAF -T ) 52/DCVP/UGPE/2023 / Techn ical Assistance to develop th Component 3: Digital Public Consultant Qualifi Open - Internationa Under Implement IDA / 67920 Post 200,000.00 0.00 2023-03-15 2023-03-24 2023-04-05 2023-03-27 2023-05-19 2023-06-18 2023-07-23 2024-01-19 e Cape Verdean Music Societ Services and Marketplace cation Selection l ation y (SCM) APP and SCM author s and artists portal 54/DCVP/UGPE/2023 / Imple Component 3: Digital Public Quality And Cost- Open - Internationa Under Implement mentations of an Interoperab IDA / 67920 Post 300,000.00 0.00 2023-05-08 2023-05-11 2023-05-29 2023-06-29 2023-07-12 2023-08-09 2023-09-08 2023-10-13 2023-11-17 2025-05-10 Services and Marketplace Based Selection l ation le Cloud Governmental Platfo rm 50/DCVP/UGPE/2023 / Deplo y strategies for civic tax citiz enship (Elaboração de Plano Component 3: Digital Public Consultant Qualifi Estratégico de Comunicação IDA / 67920 Post Open - National 150,000.00 0.00 Canceled 2023-03-15 2023-03-24 2023-04-05 2023-05-19 2023-06-18 2023-07-23 2024-01-19 Services and Marketplace cation Selection da Direção Nacional das Rec eitas do Estado [DNRE] e Ass istência Técnica na sua Imple mentação) 57/DCVP/UGPE/2023 / Securi ty Operations Center (SOC) a nd Security Information and Component 3: Digital Public Quality And Cost- Open - Internationa IDA / 67920 Post 360,000.00 0.00 Under Review 2023-08-31 2023-06-27 2023-09-21 2023-11-04 2023-12-02 2024-01-01 2024-02-05 2024-03-11 2025-03-11 Event Management (SIEM) im Services and Marketplace Based Selection l plementation in the Private a nd Technological Network of the State of Cabo Verde (RTP E) 50/DCVP/UGPE/2023-2 / Dep loy strategies for civic tax citi zenship (Elaboração de Plano Component 3: Digital Public Consultant Qualifi Under Implement Estratégico de Comunicação IDA / 67920 Post Open - National 150,000.00 0.00 2023-08-31 2023-06-27 2023-09-21 2023-11-04 2023-12-04 2024-01-08 2024-07-06 Services and Marketplace cation Selection ation da Direção Nacional das Rec eitas do Estado [DNRE] e Ass istência Técnica na sua Imple mentação) 56/DVCP/UGPE/2023 / Techn ical Assistance to implement Component 3: Digital Public Quality And Cost- Open - Internationa Under Implement IDA / 67920 Post 200,000.00 0.00 2023-08-31 2023-06-27 2023-09-21 2023-06-29 2023-11-04 2023-12-02 2024-01-01 2024-02-05 2024-03-11 2025-03-11 a corporate governance plan Services and Marketplace Based Selection l ation for e-embassy digital transfor mation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 05/CS/DCVP/UGPE/2020 / Su pport to the National Director Component 1: Enabling Lega Individual Consult ate for Telecommunications IDA / V3050 l and Regulatory Environme Post Open 200,000.00 267,215.79 Terminated 2020-03-10 2020-03-04 2020-04-28 2020-06-29 2020-05-19 2020-07-10 2020-06-23 2020-07-17 2020-12-20 ant Selection and Digital Economy: Recruit nt ment of individual Adviser for Digital Economy. 07/CS/DCVP/UGPE/2020 / En Component 1: Enabling Lega Individual Consult IDA / V3050 Post Open 139,300.00 90,316.77 Signed 2020-03-15 2020-03-12 2020-05-03 2020-06-22 2020-05-24 2020-06-23 2020-06-28 2020-06-30 2020-12-25 vironmental Specilist for UGP l and Regulatory Environme ant Selection E nt Page 3 06/CS/DCVP/UGPE/2020 / Su Component 1: Enabling Lega Individual Consult pport to the PIU – UGPE: Recr IDA / V3050 l and Regulatory Environme Prior Open 300,000.00 0.00 Canceled 2020-03-08 2020-04-26 2020-05-17 2020-06-21 2020-12-18 ant Selection uitment of an Project Manage nt r. 06/CS/DCVP/UGPE/2020-2 / Component 4: Project Imple Individual Consult IDA / V3050 Post Open 57,530.00 94,155.45 Signed 2020-03-23 2020-03-19 2020-05-11 2020-06-29 2020-06-01 2020-07-17 2020-07-06 2020-07-21 2021-01-02 Recruitment of the Project M mentation Support ant Selection anager 11/CS/DCVP/UGPE/2020 / Pr Component 4: Project Imple IDA / V3050 Post Direct Selection Direct 27,530.00 90,903.89 Signed 2020-07-27 2020-07-27 2020-08-06 2020-07-27 2020-10-10 2020-07-29 2021-04-08 ocurement for the Officer for mentation Support the UGPE 03/CS/DCVP/UGPE/2020 / Te chnical Assistance for the pre Component 4: Project Imple Individual Consult paration, finalization and ado IDA / V3050 Post Open 35,000.00 0.00 Canceled 2020-10-30 2020-12-18 2021-01-08 2021-02-12 2021-08-11 mentation Support ant Selection ption of safeguards related (s ocial and environmental) doc umentation 18/DCVP/UGPE/2021 / Recrui tment on an individual consul Component 4: Project Imple tant for the elaboration of La IDA / 67920 Post Direct Selection Direct 7,000.00 5,600.27 Completed 2021-04-09 2021-04-13 2021-04-14 2021-03-25 2021-05-15 2021-04-17 2021-07-14 2021-10-27 mentation Support bour Management Plan, for t he Digital Cabo Verde Project (social and environmental) 40/DCVP/UGPE/2022 / Digital Transformation Senior Adviso Component 3: Digital Public Individual Consult Under Implement IDA / 67920 Prior Open 300,000.00 0.00 2022-06-28 2022-06-30 2022-08-16 2022-11-04 2022-09-06 2022-12-05 2022-10-11 2023-04-09 r for the Government of Cabo Services and Marketplace ant Selection ation Verde Cabo Verde Digital Pro ject 53/DCVP/UGPE/2023 / TECH NICAL ASSISTANCE FOR UPG Component 3: Digital Public Direct - Internation Under Implement RADE OF SYDONIA WORLD A IDA / 67920 Post Direct Selection 800,000.00 0.00 2023-05-08 2023-06-08 2023-05-18 2023-07-22 2025-07-11 Services and Marketplace al ation ND THE IMPLEMENTATION OF CUSTOMS REFORM (Upgrade Sydonia World) 55/DCVP/UGPE/2023 / Senior consultant – PMO support for Component 2: Digital Compe Individual Consult Open - Internationa Under Implement IDA / 67920 Post 100,000.00 0.00 2023-05-08 2023-05-11 2023-06-26 2023-07-17 2023-08-21 2025-08-20 youth capacity building & sta titiveness ant Selection l ation rtup ecosystem Page 4 BENIN PROJET e-AGRICULTURE PLAN DE PASSATION DE MARCHES 2017 I. Généralités 1. Information sur le Projet : Pays: BENIN Project: e-Agriculture PPF No : __________________ Agence chargée de la mise en œuvre du projet : Unité de Gestion du Projet (UGP) 2. Date d’approbation du plan de passation de marchés par la Banque : ……………………………….. Période couverte par ce plan de passation de marchés : Octobre à Décembre 2018 II. Travaux, Fournitures et services « non « consultants » 1. Seuil de revue a priori : Les dossiers suivants de passation des marchés sont sujets à la revue a priori de la Banque tels que précisés dans l’annexe 1 des directives de passation des marchés : Nature des Méthode de Seuil de Contrats dépenses passation de méthode de soumis à marchés passation de examen marchés (en préalable de USD) l’IDA 1. Travaux Appel d’offres ≥ 10,000,000 ≥ 10,000,000 ouvert à 1 l’échelle Internationale Appel d’offres 200,000 < C < Aucun national 10,000,000 Demande de ≤ 200,000 Aucun Cotation Entente Pas de seuil ≥ 10,000,000 directe 2. Fournitures Appel d’offres ≥ 1,000,000 ≥ 2,000,000 et services ouvert à « non l’échelle consultants Internationale » Appel d’offres 100,000 < C < Aucun national 1,000,000 Demande de ≤ 100,000 Aucun Cotation Entente Pas de seuil ≥ 2,000,000 directe 2. Reference à un manuel d’opération : Not applicable 3. Autre arrangement spécial en passation de marchés : Ceci inclut la passation de marchés sur les financements rétroactifs Passation de marchés avec méthodes et date prévisionnelle Préféren Méthode Revue Coût Préquali ce Date Ref de par Contrat estimati fi cation Domesti probable . passatio l’IDA (Description) ve (Oui/No que d’ouverture No. n de (Oui/ (US$) n) (Oui/Non des offres marchés Non) ) 1 Fourniture de Logiciels Non Non Non Octobre de Gestion financière et 25,000 DC 2017 formation sur le logiciel 2 Fourniture de matériels Non Non Non Octobre informatiques et 5,000 DC 2017 accessoires 2 3 Fourniture de mobiliers Non Non Non Octobre et matériels de bureau 100,000 DC 2017 4 Fourniture de véhicules 60,000 DC Non Non Non Octobre 4x4 2017 TOTAL 190 000 III. Sélection de Consultants 1. Seuil de revue a priori : Les dossiers suivants de passation des marchés sont sujets à la revue a priori de la Banque tels que précisés dans l’annexe I des directives de passation de marchés : Méthode de sélection Seuil de Contrats soumis à méthode de l’examen passation de préalable de l’IDA marchés (en USD) 1. Liste SFQC, SFQ, SMC, autres < 100,000 Aucun restreinte services de consultants nationale pour SFQC, SFQ, SMC, autres ≤ 200,000 Aucun la sélection de services d’ingénierie et de consultants supervision des (firmes/cabine constructions ts d’experts/) 2. Liste SFQC, SFQ, SMC, QC, autres ≥ 100,000 ≥ 1,000,000 restreinte services de consultants internationale SFQC, SFQ, SMC, QC, autres > 200,000 ≥ 1,000,000 pour la services d’ingénierie et de sélection de supervision des consultants constructions (firmes/cabine 3 ts d’experts/) 3. Sélection de CI Tous montants ≥ 300,000 consultants individuels 4. Entente --- Tous montants ≥ 1,000,000 pour les directe firmes et ≥ 300,000 pour les consultants individuels 5. Formation, Sur la base du Plan de Tous montants --- ateliers, Travail et de Budget Annuel voyages approuvé (PTBA) d’études 2. Liste restreinte constituée entièrement de consultants nationaux : La liste restreinte de services de consultants dont le coût estimatif est de moins de $100,000 ou équivalent par contrat peut comprendre que des consultants nationaux conformément aux dispositions du paragraphe 2.7 des directives sur les services de consultants. 3. Autre arrangement spécial : Non applicable 4. Services de consultants avec les méthodes de sélection et l’échéance (SFQC –Sélection Fondée sur la Qualité et le Coût ; SFQ –Sélection Fondée sur la Qualité ; SMC –Sélection au Moindre Coût ; CQ –Qualifications de Consultant ; CI- Consultant Individuel) 4 1 2 3 4 5 6 Date de Revue par Ref. No. Coût estimatif Méthode de soumission Description la Banque (US$) sélection de (Oui / Non) proposition 1. Services de Consultant pour le recrutement du personnel 20 000 QC Non Octobre 2017 de l'Unité de Coordination du Projet 2. Services de Consultant pour l’élaboration du Manuel de 40,000 QC Non Procédures adm, fin. et Octobre2017 comptable 3. Services de Consultant pour l’élaboration du document Non 40,000 CI Octobre 2017 d'exécution du Projet 4. Services de Consultant pour Novembre la formation sur le logiciel de 5 000 CI Non 2017 gestion financière 5. Services de Consultant pour la réalisation de l’étude sur Novembre 200 000 QC Non les services numériques 2017 agricoles 6. Services de Consultant pour la réalisation de l’étude de Décembre confirmation des zones 100 000 QC Non 2017 blanches à couvrir par le projet (Voice et Data) 7. Services de Consultant pour la réalisation de l’état des lieux des interventions sur Décembre les filières agricoles : 70 000 QC Non 2017 cartographie des interventions dans le secteur agricole 8. Services de Consultant pour la réalisation de l’étude sur l'Open Innovation et le Décembre 150 000 QC Non renforcement de 2017 l'écosystème numérique au Bénin 5 9. Service de Consultant pour la Décembre réalisation de l’étude 180 000 QC Non 2017 environnementale et sociale 10. Services de Consultant pour le renforcement des Décembre 100 000 QC Non capacités opérationnelles 2017 des acteurs du secteur IV- 11. Services de Consultant pour la réalisation de l’étude sur le Décembre modèle Economique de PPP 100 000 QC Non 2017 pour l'accroissement de l'accès en zone rurale 12. Service de consultant pour 6 000 ED Non Octobre 2017 appui fiduciaire TOTAL 1 011 000 Ateliers et Formations Revue par la Date de Observations Coût Banque soumission Description estimatif Réf N° (Oui / Non) des termes (US$) de références Atelier de validation du Novembre 1. 10 000 Oui manuel de procédure 2017 Atelier de validation du Novembre 2. 10 000 Oui manuel d'exécution 2017 Voyage d'Etude sur les meilleures pratiques internationales en e- Décembre 3. 120 000 Oui agriculture (Kenya et 2017 deux autres pays à identifier) Formation des membres Novembre 4. de l'Equipe Projet aux 50 000 Oui 2017 outils de gestion Atelier de validation de Décembre 5. l'étude sur les services 10 000 Oui 2017 numériques agricoles 6 Atelier de validation de l'étude de confirmation Décembre 6. des zones blanches à 10 000 Oui 2017 couvrir par le projet (Voice et Data) Atelier de validation de l'étude sur l'Etat des lieux des interventions sur les Décembre 7. filières agricoles : 10 000 Oui 2017 cartographie des interventions dans le secteur agricole Atelier de validation de l'étude sur l'Open Innovation et le Décembre 8. 10 000 Oui renforcement de 2017 l'écosystème numérique au Bénin Atelier de validation de Décembre 9. l'étude Environnementale 10 000 Oui 2017 et sociale Atelier de validation de l'étude sur le modèle Décembre 10. économique de PPP pour 10 000 Oui 2017 l'accroissement de l'accès en zone rurale TOTAL 250 000 7 PROCUREMENT Benin : Digital Rural Transformation Project PLAN General Information Country: Benin 2018-09-05 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162599 GPN Date: 2017-12-27 Project Name: Digital Rural Transformation Project Loan / Credit No: / , IDA / V1370, IDA / 64530 COORDINATION UNIT OF AGRICULTURAL DIVERSIFICATION'S SUPPORT PROGRAM Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned BJ-UCP / PADA-165769-CW-R FQ / Travaux d'aménagemen Request for Quota Single Stage - One E 2020-11-2 IDA / 64530 Project implementation Post Limited 42,000.00 78,277.91 Signed 2020-04-04 2020-05-28 2020-05-30 2020-07-01 t du bâtiment devant servir d tions nvelope 6 e siège du Projet PITN2R GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-UCP / PADA-43641-GO-RF Request for Quota Single Stage - One E Under Imple Q / Fourniture de Logiciels de / Post Limited 25,000.00 0.00 2018-02-20 2020-04-23 2018-03-27 2018-04-26 tions nvelope mentation Gestion financière et formati on sur le logiciel BJ-UCP / PADA-43643-GO-RF Request for Quota Single Stage - One E Under Imple Q / Fourniture de matériels in / Post Limited 5,000.00 0.00 2018-02-20 2020-04-24 2018-03-27 2018-04-26 tions nvelope mentation formatiques et accessoires BJ-UCP / PADA-43645-GO-RF Request for Quota Single Stage - One E Under Imple Q / Fourniture de mobiliers et / Post Limited 100,000.00 0.00 2018-02-20 2020-04-08 2018-03-27 2018-04-26 tions nvelope mentation matériels de bureau BJ-UCP / PADA-43648-GO-RF Request for Quota Single Stage - One E Pending Impl / Post Limited 60,000.00 0.00 2018-02-20 2018-03-27 2018-06-25 Q / Fourniture de véhicules 4 tions nvelope ementation x4 BJ-UCP / PADA-159148-GO-R Request for Quota Single Stage - One E FQ / Acquisition de fourniture IDA / 64530 Project implementation Post Limited 35,000.00 18,274.30 Signed 2020-02-26 2020-07-20 2020-04-22 2020-08-14 2020-10-19 tions nvelope s de bureau pour l'UCP du Pr ojet PITN2R BJ-UCP / PADA-159999-GO-R FQ / Fourniture et installation Request for Quota Single Stage - One E IDA / 64530 Project implementation Post Limited 85,000.00 98,190.26 Completed 2020-02-29 2021-01-04 2020-04-25 2021-03-14 2020-10-22 2021-09-12 des équipements réseaux po tions nvelope ur le siège du Projet PITN2R BJ-UCP / PADA-190199-GO-R FQ / Fourniture et installation Request for Quota Single Stage - One E IDA / 64530 Project implementation Post Open - National 25,000.00 22,955.28 Signed 2020-09-05 2020-10-31 2020-08-06 2021-04-29 de climatiseurs pour l'espace tions nvelope paysager de l'UCP du Projet P ITN2R BJ-UCP / PADA-190200-GO-R FQ / Fourniture et installation Request for Quota Single Stage - One E IDA / 64530 Project implementation Post Open - National 20,000.00 62,349.02 Completed 2020-09-12 2021-01-10 2020-11-07 2021-07-07 2021-05-06 2021-10-12 d'un groupe électrogène 10 tions nvelope KVA pour l'UCP du Projet PIT N2R BJ-UCP / PADA-190209-GO-R FQ / Acquisition de divers éq uipements au profit des Cent Digital solutions for rural dev Request for Quota Single Stage - One E Pending Impl res Technologiques de Zone IDA / 64530 Post Open - National 95,000.00 0.00 2020-12-07 2021-02-01 2021-07-31 elopment tions nvelope ementation dans le cadre du développem ent d'un écosystème numéri que pour l'agriculture et le to urisme BJ-UCP / PADA-195437-GO-U N / Acquisition de deux (02) v UN Agencies (Dire IDA / 64530 Project implementation Post Direct 125,000.00 103,022.12 Completed 2020-10-05 2020-11-18 2020-10-10 2020-11-10 2020-11-14 2021-03-12 2021-05-13 2021-04-08 éhicules 4x4 au profit de l'UC ct) P du Projet PITN2R BJ-UCP / PADA-213071-GO-R FB / Acquisition d'équipemen Extending connectivity in rur Single Stage - One E Under Imple IDA / 64530 Post Request for Bids Open - National 130,000.00 0.00 2021-05-18 2021-10-11 2021-05-23 2021-07-04 2021-08-03 2021-09-07 2022-03-06 ts pour la construction du de al areas nvelope mentation uxième point d'échange inter net à Parakou BJ-UCP / PADA-213080-CW-R FB / Fourniture et installation Extending connectivity in rur Open - Internationa Single Stage - One E Pending Impl IDA / 64530 Post Request for Bids 1,727,273.00 0.00 2021-04-30 2021-05-05 2021-06-16 2021-07-16 2021-08-20 2022-02-16 d'équipements pour la réalis al areas l nvelope ementation ation de l'infrastructure num érique dans le Pendjari BJ-UCP / PADA-213093-GO-R FQ / Acquisition de drone et Digital financial inclusion an Request for Quota Single Stage - One E autres matériels pour la mise IDA / 64530 Post Open - National 90,000.00 90,114.46 Completed 2021-04-04 2021-05-30 2022-01-23 2021-11-26 2022-10-28 d skills tions nvelope en place d'outils innovants p our le Conseil Agriocole BJ-UCP / PADA-213095-GO-R FQ / Acquisition et mise en pl Request for Quota Single Stage - One E Pending Impl IDA / 64530 Project implementation Post Open - National 36,000.00 0.00 2021-04-17 2021-06-12 2021-12-09 ace d'un système de vidéo c tions nvelope ementation onférence au niveau de l'UCP BJ-UCP / PADA-213096-GO-R Request for Quota Single Stage - One E FQ / Acquisition de matériels IDA / 64530 Project implementation Post Open - National 16,000.00 20,323.65 Signed 2021-04-20 2021-06-15 2021-10-09 2021-12-12 tions nvelope et mobiliers de bureau BJ-UCP / PADA-222404-GO-R FQ / Acquisition de matériels Request for Quota Single Stage - One E Under Imple IDA / 64530 Access to markets Post Open - National 37,000.00 0.00 2021-06-01 2021-07-27 2022-01-23 informatiques au profit des p tions nvelope mentation arties prenantes du PITN2R BJ-UCP / PADA-224286-GO-R Request for Quota Single Stage - One E FQ / Acquisition d'une moto a IDA / 64530 Project implementation Post Limited 2,000.00 1,714.42 Completed 2021-06-01 2021-08-12 2021-07-27 2021-08-31 2022-01-23 2021-09-16 tions nvelope u profit de l'agent de liaison du PITN2R Page 1 BJ-UCP / PADA-213083-CW-R FB / Fourniture d'équipement Extending connectivity in rur Open - Internationa Single Stage - One E Under Imple s, installation et intégration d IDA / 64530 Post Request for Bids 2,723,000.00 0.00 2021-06-16 2023-03-02 2021-06-21 2021-08-02 2021-09-01 2021-10-06 2022-04-04 al areas l nvelope mentation u réseau métropolitain en fib re optique de Parakou BJ-UCP / PADA-213098-GO-R FQ / Acquisition et mise en pl ace de terminaux de paieme Digital financial inclusion an Request for Quota Single Stage - One E Pending Impl nt digital pour renforcer l'éco IDA / 64530 Post Open - National 95,000.00 0.00 2021-04-24 2021-06-19 2021-12-16 d skills tions nvelope ementation système de paiement numéri que développé au profit des acteurs des chaines de valeu rs priroitaires BJ-UCP / PADA-234639-GO-R FB / Acquisition d'équipemen Digital financial inclusion an Single Stage - One E Under Imple t pour la mise en place de la IDA / 64530 Post Request for Bids Open - National 210,000.00 0.00 2021-06-30 2022-05-25 2021-07-05 2022-06-06 2021-08-16 2021-09-15 2021-10-20 2022-04-18 d skills nvelope mentation plateforme numérique de ge stion du matériel et équipem ents agricoles BJ-UCP / PADA-234647-GO-R FB / Acquisition d'équipemen Digital financial inclusion an Single Stage - One E Pending Impl IDA / 64530 Post Request for Bids Open - National 200,000.00 0.00 2021-08-16 2021-08-21 2021-10-02 2021-11-01 2021-12-06 2022-06-04 ts pour la mise en place de la d skills nvelope ementation plateforme numérique partag ée des SFD BJ-UCP / PADA-235378-GO-R FB / Fourniture d'équipement Digital financial inclusion an Single Stage - One E Under Imple IDA / 64530 Post Request for Bids Open - National 110,000.00 0.00 2021-08-09 2022-07-01 2021-08-14 2021-09-25 2021-11-17 2021-10-25 2021-11-29 2022-05-28 s pour la création des CSIRTs d skills nvelope mentation au profit des secteurs public et privés critiques BJ-UCP / PADA-213081-CW-R FB / Fourniture et installation Extending connectivity in rur Open - Internationa Single Stage - One E d'équipements pour la réalis IDA / 64530 Post Request for Bids 1,814,000.00 0.00 Signed 2021-08-30 2022-02-01 2021-09-04 2022-02-01 2021-10-16 2022-03-21 2021-11-15 2022-05-25 2021-12-20 2022-06-18 al areas l nvelope ation des infrastructures num ériques dans les administrati ons locales BJ-UCP / PADA-213072-CW-R FB / Fourniture et installation Extending connectivity in rur Single Stage - One E d'équipements pour la réalis IDA / 64530 Post Request for Bids Open - National 1,790,000.00 0.00 Signed 2021-09-15 2022-02-01 2021-09-20 2022-02-01 2021-11-01 2022-03-21 2021-12-01 2022-08-05 2022-01-05 2022-07-04 al areas nvelope ation de la connectivité dans les lycées agricoles, les ATDA et les CSA BJ-UCP / PADA-248619-GO-R FQ / Acquisition de fourniture Request for Quota Single Stage - One E IDA / 64530 Project implementation Post Limited 18,000.00 19,797.39 Signed 2021-09-04 2021-09-21 2021-10-30 2021-11-18 2022-04-28 s de bureau et de consomma tions nvelope bles informatiques au profit d e l'UCP du PITN2R BJ-UCP / PADA-277352-GO-R Request for Quota Single Stage - One E Pending Impl FQ / Acquisition de matériels IDA / 64530 Project implementation Post Limited 36,300.00 0.00 2022-04-23 2022-06-18 2022-12-15 tions nvelope ementation et mobiliers de bureau BJ-UCP / PADA-277432-GO-R Request for Quota Single Stage - One E Pending Impl FQ / Acquisition de matériels IDA / 64530 Project implementation Post Limited 6,500.00 0.00 2022-05-23 2022-07-18 2023-01-14 tions nvelope ementation informatiques et accessoires BJ-UCP / PADA-277433-GO-R Request for Quota Single Stage - One E FQ / Acquisition de fourniture IDA / 64530 Project implementation Post Limited 10,000.00 0.00 Completed 2022-06-18 2022-05-27 2022-08-13 2023-02-09 tions nvelope s de bureau au profit du PITN 2R BJ-UCP / PADA-213078-CW-R FB / Fournitures et installatio Extending connectivity in rur Open - Internationa Single Stage - One E n d'équipement pour la réalis IDA / 64530 Post Request for Bids 1,689,455.00 0.00 Canceled 2021-07-12 2021-07-17 2021-08-28 2021-09-27 2021-11-01 2022-04-30 al areas l nvelope ation de la connectivité des u niversités et autres établisse ments d'enseignement BJ-UCP / PADA-213077-GO-R FQ / Acquisition d'équipemen ts (smartphones et autres) p Extending connectivity in rur Request for Quota Single Stage - One E IDA / 64530 Post Limited 10,000.00 0.00 Canceled 2021-05-09 2021-07-04 2021-12-31 our faciliter la communicatio al areas tions nvelope n avec les communautés de base et les comités de gestio n des plaintes BJ-UCP / PADA-213069-CW-R FB / Fourniture et installation Extending connectivity in rur Open - Internationa Single Stage - One E d'équipements pour la réalis IDA / 64530 Prior Request for Bids 16,900,000.00 0.00 Canceled 2021-07-05 2021-07-10 2021-08-21 2021-09-20 2021-10-25 2022-04-23 al areas l nvelope ation des infrastructures num ériques dans les zones cibles du PITN2R BJ-UCP / PADA-342233-GO-R FB / Acquisition et installatio n d'émetteurs FM, combiners Extending connectivity in rur Open - Internationa Single Stage - One E , systèmes d'antennes, de gr IDA / 64530 Post Request for Bids 1,585,000.00 0.00 Canceled 2023-04-03 2023-04-08 2023-05-20 2023-06-19 2023-07-24 2024-01-20 al areas l nvelope oupes électrogènes et de cli matiseurs pour l'optimisation du fonctionnement du réseau FM de l'ORTB BJ-UCP / PADA-351872-GO-D Direct - Internation Pending Impl IR / Acquisition d'un véhicule IDA / 64530 Project implementation Post Direct Selection 50,000.00 0.00 2023-05-31 2023-06-05 2023-07-10 2024-01-06 al ementation 4*4 pick up auprès de l'UNOP S BJ-UCP / PADA-352481-GO-R FB / Acquisition de drone et a Digital financial inclusion an Single Stage - One E Pending Impl ccessoires et formation des a IDA / 64530 Post Request for Bids Open - National 160,000.00 0.00 2023-06-30 2023-07-05 2023-08-16 2023-09-15 2023-10-20 2024-04-17 d skills nvelope ementation cteurs de mise en œuvre du conseil agricole à leur utilisat ion BJ-UCP / PADA-347414-GO-R FB / Fourniture et installation Extending connectivity in rur Single Stage - One E Pending Impl d'équipements pour la réalis IDA / 64530 Post Request for Bids Limited 2,723,000.00 0.00 2023-06-20 2023-06-25 2023-08-06 2023-09-05 2023-10-10 2024-04-07 al areas nvelope ementation ation du réseau métropolitai n en fibre optique de Parako u BJ-UCP / PADA-351858-GO-R Request for Quota Single Stage - One E Pending Impl FQ / Acquisition de fourniture IDA / 64530 Project implementation Post Limited 8,360.00 0.00 2023-08-05 2023-09-30 2024-03-28 tions nvelope ementation s de bureau BJ-UCP / PADA-351865-GO-R FQ / Fourniture et installation Request for Quota Single Stage - One E Pending Impl des équipements réseaux po IDA / 64530 Project implementation Post Limited 43,910.00 0.00 2023-07-15 2023-09-09 2024-03-07 tions nvelope ementation ur le siège du Projet PITN2R ( y compris suivi et maintenan ce d'un an ) Page 2 BJ-UCP / PADA-351867-GO-R Request for Quota Single Stage - One E Pending Impl FQ / Acquisition de matériels IDA / 64530 Project implementation Post Limited 10,470.00 0.00 2023-06-11 2023-08-06 2024-02-02 tions nvelope ementation informatiques et accessoires NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-UCP / PADA-213099-NC-R FB / Développement d'un éco Digital solutions for rural dev Single Stage - One E Pending Impl système de paiement numéri IDA / 64530 Post Request for Bids Open - National 350,000.00 0.00 2021-04-19 2021-04-24 2021-06-05 2021-07-05 2021-08-09 2022-02-05 elopment nvelope ementation que au profit des acteurs des chaines de valeur prioritaires BJ-UCP / PADA-222347-GO-R Request for Quota Single Stage - One E FQ / Acquisition d'un logiciel IDA / 64530 Project implementation Post Limited 12,000.00 17,082.57 Signed 2021-04-27 2021-10-11 2021-06-22 2021-12-07 2021-12-19 tions nvelope de suivi évaluation au profit du PITN2R BJ-UCP / PADA-274845-GO-R FQ / Conception et impressio n de divers documents (regis tre de gestion des plaintes, fi Extending connectivity in rur Request for Quota Single Stage - One E IDA / 64530 Post Limited 18,000.00 16,294.73 Completed 2022-03-27 2022-03-09 2022-05-22 2022-04-05 2022-11-18 che de recueil de consentem al areas tions nvelope ent, etc) dans le cadre de la mise en œuvre du Mécanism e de Gestion des Plaintes dan s la zone d'intervention du pr ojet BJ-UCP / PADA-278640-GO-R FB / Sélection d'entreprises p Extending connectivity in rur Single Stage - One E Under Imple IDA / 64530 Prior Request for Bids Limited 16,900,000.00 0.00 2022-03-28 2022-03-29 2022-04-02 2022-04-06 2022-05-14 2022-06-16 2022-06-13 2023-02-22 2022-07-18 2023-01-14 our la fourniture de la connec al areas nvelope mentation tivité dans les zones rurales BJ-UCP / PADA-87333-NC-RF Q / Fourniture des prestation Digital financial inclusion an Request for Quota Single Stage - One E IDA / V1370 Post Limited 100,000.00 0.00 Canceled 2018-11-20 2019-01-15 2019-02-14 s d'évènementiel pour l'orga d skills tions nvelope nisation de la semaine du nu mérique BJ-UCP / PADA-345062-NC-DI R / ASSISTANCE COMPTABLE Pending Impl IDA / 64530 Project implementation Post Direct Selection Direct - National 8,000.00 0.00 2023-04-10 2023-04-15 2023-05-20 2023-11-16 ET INFORMATIQUE SUR LE LO ementation GICIEL SUCCESS BJ-UCP / PADA-357275-NC-R FB / Acquisition d'une platef Digital financial inclusion an Open - Internationa Single Stage - One E Pending Impl IDA / 64530 Post Request for Bids 180,000.00 0.00 2023-06-26 2023-07-01 2023-08-12 2023-09-11 2023-10-16 2024-04-13 orme numérique pilote de tra d skills l nvelope ementation cking du cheptel par le collier bovin électronique BJ-UCP / PADA-356585-CS-C QS / Service de cartographie Digital financial inclusion an Request for Quota Single Stage - One E Pending Impl IDA / 64530 Post Open - National 75,000.00 0.00 2023-09-05 2023-10-31 2024-04-28 des zones agricoles de la Zo d skills tions nvelope ementation ne d'Intervention du PITN2R BJ-UCP / PADA-344920-NC-R FQ / Archivage physique, nu mérisation, indexation et inje ction dans le Système d'Archi Extending connectivity in rur Request for Quota Single Stage - One E Pending Impl vage Electronique (SAE), du f IDA / 64530 Post Limited 50,000.00 0.00 2023-07-05 2023-08-30 2024-02-26 al areas tions nvelope ementation onds documentaire issu (i) d es dossiers des 800 bénéficia ires des subventions des TPE, (ii) des documents administr atifs et fiduciaires du PITN2R CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-UCP / PADA-43680-CS-CQ S / Services de Consultant po ur l'évaluation des besoins e Consultant Qualifi Under Implement / Post Open - National 100,000.00 0.00 2018-02-25 2019-04-24 2018-03-18 2018-04-01 2019-07-04 2018-04-08 2019-08-06 2018-04-29 2018-05-29 n infrastructure TIC, énergéti cation Selection ation que et en pistes rurales à co nstruire ou à réhabiliter dans le cadre du projet e-Agricultu re BJ-UCP / PADA-43683-CS-IND V / Services de Consultant po ur la réalisation de l'état des Consultant Qualifi Pending Impleme / Post Open - National 70,000.00 0.00 2018-02-22 2018-03-15 2018-04-28 2018-05-28 2018-07-02 2018-12-29 lieux des interventions sur le cation Selection ntation s filières agricoles : cartograp hie des interventions dans le secteur agricole BJ-UCP / PADA-43651-CS-CQ S / Sélection d'un cabinet po Digital solutions for rural dev Consultant Qualifi IDA / V1370 Post Open - National 20,000.00 26,883.62 Signed 2018-09-05 2019-05-27 2018-09-26 2018-11-09 2019-03-07 2018-12-09 2019-04-16 2019-01-13 2019-05-13 2019-07-12 ur le recrutement du personn elopment cation Selection el de l'Unité de Coordination du Projet BJ-UCP / PADA-43686-CS-CQ S / Services de Consultant po Extending connectivity in rur Consultant Qualifi Open - Internationa Under Implement ur la réalisation de l'étude su IDA / V1370 Post 150,000.00 0.00 2018-11-15 2019-04-24 2018-12-06 2019-01-19 2020-02-25 2019-02-18 2019-03-25 2019-09-21 al areas cation Selection l ation r l'Open Innovation et le renf orcement de l'écosystème nu mérique au Bénin BJ-UCP / PADA-130010-CS-C QS / sélection d'un cabinet p our l'élaboration du cadre juri Consultant Qualifi Under Implement dique et organisationnel de l' IDA / V1370 Project implementation Post Open - National 100,000.00 0.00 2019-09-06 2019-09-04 2019-09-27 2019-11-10 2020-02-25 2019-12-10 2020-03-26 2020-01-14 2020-07-12 cation Selection ation organe de contrôle des prest ataires de services de confia nce dans le domaine des co mmunications électroniques. BJ-UCP / PADA-140759-CS-C QS / Recrutement d'une Age Consultant Qualifi IDA / V1370 Project implementation Post Open - National 166,000.00 111,882.50 Signed 2019-10-25 2020-10-26 2019-11-15 2019-12-29 2021-10-04 2020-01-28 2021-10-04 2020-03-03 2021-12-03 2020-08-30 nce de Communication pour l cation Selection 'UCP du Projet PITN2R. BJ-UCP / PADA-151899-CS-L Least Cost Selecti CS / Sélection d'un cabinet d' IDA / 64530 Project implementation Post Open - National 42,000.00 9,046.50 Signed 2019-12-31 2020-02-05 2020-01-21 2020-03-05 2021-01-15 2020-04-02 2021-03-31 2020-05-02 2021-03-31 2020-06-06 2021-04-02 2020-07-11 2021-06-01 2021-01-07 on audit externe des comptes d u Projet PITN2R Page 3 BJ-UCP / PADA-190015-CS-C QS / Réalisation de l'étude de faisabilité technique et écono Extending connectivity in rur Consultant Qualifi mique de la construction d'u IDA / 64530 Post Open - National 40,000.00 40,537.40 Signed 2020-09-14 2020-10-30 2020-10-05 2021-01-10 2020-11-18 2021-03-26 2020-12-18 2021-04-30 2021-01-22 2021-09-02 2021-07-21 al areas cation Selection n réseau à fibre optique le lo ng des infrastructures routièr es de Bohicon-Dassa, Dassa- Parakou et Parakou-Malanvill e. BJ-UCP / PADA-190019-CS-C QS / Réalisation de l'étude su Digital solutions for rural dev Consultant Qualifi IDA / 64530 Post Open - National 60,000.00 104,755.20 Signed 2020-09-14 2021-02-01 2020-10-05 2020-11-18 2021-08-02 2020-12-18 2021-11-09 2021-01-22 2021-12-18 2021-07-21 r les règles standards de dép elopment cation Selection loiement des projets FTTX BJ-UCP / PADA-190028-CS-C QS / Réalisation d'une étude Digital solutions for rural dev Consultant Qualifi IDA / 64530 Post Open - National 70,000.00 165,060.06 Signed 2020-09-28 2021-03-10 2020-10-19 2020-12-02 2021-10-11 2021-01-01 2022-03-15 2021-02-05 2022-04-26 2021-08-04 technique sur la performance elopment cation Selection des réseaux fixes et mobiles au Bénin BJ-UCP / PADA-190040-CS-C QS / Réalisation d'une étude Digital financial inclusion an Consultant Qualifi de faisabilité sur la mise en p IDA / 64530 Post Open - National 84,000.00 131,870.12 Completed 2020-10-26 2021-03-15 2020-11-16 2021-06-10 2020-12-30 2021-09-10 2021-01-29 2021-10-11 2021-03-05 2021-12-22 2021-09-01 d skills cation Selection lace d'un centre de traiteme nt des données SFD au Bénin BJ-UCP / PADA-190190-CS-C QS / Réalisation de l'analyse Digital financial inclusion an Consultant Qualifi approfondie des chaines de v IDA / 64530 Post Open - National 50,000.00 123,223.36 Signed 2020-10-26 2020-10-26 2020-11-16 2021-06-10 2020-12-30 2021-10-11 2021-01-29 2022-01-14 2021-03-05 2022-01-06 2021-09-01 d skills cation Selection aleur prioritaires (riz, maïs, k arité, culture maraichères, a nacarde, ananas, etc.) BJ-UCP / PADA-190191-CS-C QS / Elaboration d'une applic Digital financial inclusion an Consultant Qualifi Under Implement ation intégrée de gestion des IDA / 64530 Post Open - National 168,000.00 0.00 2020-10-26 2020-10-30 2020-11-16 2020-12-30 2021-01-29 2021-03-05 2021-09-01 d skills cation Selection ation opérations financières des SF D, OTM et de supervision BJ-UCP / PADA-190192-CS-C QS / Réalisation et validation Consultant Qualifi IDA / 64530 Project implementation Post Open - National 50,000.00 129,428.84 Signed 2020-11-02 2020-10-30 2020-11-23 2021-01-06 2021-10-12 2021-02-05 2021-10-26 2021-03-12 2021-10-22 2021-09-08 de l'étude de référence sur le cation Selection s indicateurs clés du projet P ITN2R BJ-UCP / PADA-190194-CS-C QS / Mise en place d'un systè me de gestion électronique d Consultant Qualifi es documents (GED), de gest IDA / 64530 Project implementation Post Open - National 100,000.00 101,209.34 Signed 2020-11-02 2021-02-01 2020-11-23 2021-01-06 2021-09-07 2021-02-05 2022-02-17 2021-03-12 2021-12-07 2021-09-08 cation Selection ion électronique des courrier s (GEC), et d'un système d'ar chivage électronique (SAE) p our le compte du PITN2R BJ-UCP / PADA-212890-CS-C QS / Sélection d'un cabinet p Digital financial inclusion an Consultant Qualifi Pending Impleme our l'élaboration d'un modèle IDA / 64530 Post Open - National 60,000.00 0.00 2021-04-15 2021-05-06 2021-06-19 2021-07-19 2021-08-23 2022-02-19 d skills cation Selection ntation économique pour le sytème d'information des marchés a gricoles BJ-UCP / PADA-213067-CS-C QS / Réalisation d'une etude Extending connectivity in rur Consultant Qualifi IDA / 64530 Post Open - National 50,000.00 0.00 Completed 2021-04-13 2021-03-26 2021-05-04 2021-06-17 2022-02-28 2021-07-17 2022-06-13 2021-08-21 2022-02-17 2022-10-29 sur la contribution du secteur al areas cation Selection du numérique au PIB et à l'at teinte des ODD BJ-UCP / PADA-213073-CS-C QS / Contrôle des travaux de Extending connectivity in rur Consultant Qualifi Under Implement IDA / 64530 Post Open - National 90,000.00 0.00 2021-04-20 2021-08-06 2021-05-11 2021-09-17 2021-06-24 2021-12-10 2021-07-24 2021-08-28 2022-02-24 connectivité dans les lycées al areas cation Selection ation agricoles, les ATDA et les CS A BJ-UCP / PADA-213074-CS-C QS / Étude de faisabilité de d Extending connectivity in rur Consultant Qualifi Under Implement IDA / 64530 Post Open - National 95,000.00 0.00 2021-04-28 2021-03-31 2021-05-19 2021-07-02 2021-08-01 2021-09-05 2022-03-04 u Réseau Béninois d’Éducatio al areas cation Selection ation n et de Recherche (RBER) BJ-UCP / PADA-213075-CS-C QS / Étude d'Impact Environn Extending connectivity in rur Consultant Qualifi IDA / 64530 Post Limited 50,000.00 202,525.52 Signed 2021-04-05 2021-03-31 2021-04-19 2021-06-12 2021-05-19 2021-10-21 2021-06-23 2021-10-22 2021-12-20 emental et Social des sous pr al areas cation Selection ojets d’infrastructures numér iques du PITN2R BJ-UCP / PADA-213076-CS-C QS / Sélection d'ONG d'appui pour la sensibilisation des po Extending connectivity in rur Consultant Qualifi IDA / 64530 Post Open - National 12,500.00 17,499.37 Signed 2021-04-22 2021-05-13 2021-05-13 2021-06-21 2021-06-26 2021-04-06 2021-07-26 2021-09-30 2021-08-30 2021-10-01 2022-02-26 pulations dans le cadre de la al areas cation Selection mise en oeuvre du mécanism e de gestion des plaintes BJ-UCP / PADA-213089-CS-C QS / Sélection d'un consultan t pour l'élaboration d'un mod èle économique et la mise en Digital financial inclusion an Consultant Qualifi Open - Internationa Pending Impleme IDA / 64530 Post 150,000.00 0.00 2021-04-01 2021-04-22 2021-06-05 2021-07-05 2021-08-09 2022-02-05 place d'application numériqu d skills cation Selection l ntation e e conseil agricole pour l'acc ès à l'information des produc teurs sur les filières ciblées d u projet BJ-UCP / PADA-213090-CS-Q CBS / Recrutement d'un cons ultant pour l'élaboration d'un modèle économique et la mis Digital financial inclusion an Quality And Cost- Open - Internationa e en place d'une plate forme IDA / 64530 Post 350,000.00 386,986.14 Signed 2021-04-01 2021-05-07 2021-04-22 2021-06-21 2021-06-05 2022-01-14 2021-07-03 2022-01-14 2021-08-02 2022-01-14 2021-09-06 2022-01-14 2021-10-11 2022-02-18 2022-10-11 d skills Based Selection l de gestion et de suivi des ex ploitations agricoles intégran t les données géolocalisées p our apprécier l'évolution des agriculteurs enregistrés BJ-UCP / PADA-213091-CS-C QS / Renforcement de la plat e forme numérique de gestio Digital financial inclusion an Consultant Qualifi Open - Internationa IDA / 64530 Post 280,000.00 229,677.55 Signed 2021-04-05 2021-05-07 2021-04-26 2021-06-21 2021-06-09 2021-12-13 2021-07-09 2022-01-18 2021-08-13 2021-12-20 2022-02-09 n du matériel et équipement d skills cation Selection l agricole au profit des product eurs des filières ciblées du PI TN2R BJ-UCP / PADA-213092-CS-C QS / Élaboration de la stratég ie de conduite de changeme Digital financial inclusion an Consultant Qualifi Under Implement IDA / 64530 Post Open - National 30,000.00 0.00 2021-04-05 2022-02-11 2021-04-26 2021-06-09 2021-07-09 2021-08-13 2022-02-09 nt pour l'adoption des outils d skills cation Selection ation numériques pour la mise en oeuvre du Conseil Agricole Page 4 BJ-UCP / PADA-213094-CS-Q CBS / Création de modules d e niveau basique de sécurité numérique pour les lycées ag Digital financial inclusion an Quality And Cost- Open - Internationa Under Implement IDA / 64530 Post 400,000.00 0.00 2021-04-12 2021-09-14 2021-05-03 2021-06-16 2021-07-14 2021-08-13 2021-09-17 2021-10-22 2022-10-22 ricoles, les établissements d' d skills Based Selection l ation enseignement primaires et s econdaires et le renforcemen t des cursus académiques sp écialisés dans la sécurité nu mérique BJ-UCP / PADA-224079-CS-C QS / Recrutement d'un cabin et pour le développement d'u Digital financial inclusion an Consultant Qualifi IDA / 64530 Post Open - National 90,000.00 224,559.00 Signed 2021-06-23 2021-05-14 2021-07-14 2021-06-21 2021-08-27 2021-09-16 2021-09-26 2022-01-16 2021-10-31 2021-12-22 2022-04-29 n écosystème de paiement n d skills cation Selection umérique au profit des acteu rs des chaines de valeur prio ritaires BJ-UCP / PADA-224083-CS-C QS / Sélection d'un cabinet p Digital financial inclusion an Consultant Qualifi Under Implement our l'élaboration d'un modèle IDA / 64530 Post Open - National 50,000.00 0.00 2021-08-09 2021-12-22 2021-08-30 2021-10-13 2021-11-12 2021-12-17 2022-06-15 d skills cation Selection ation économique pour le Système d'Information des Marchés a gricole BJ-UCP / PADA-224453-CS-C QS / Mission de contrôle des Digital solutions for rural dev Consultant Qualifi Open - Internationa Pending Impleme IDA / 64530 Post 170,000.00 0.00 2021-05-31 2021-06-21 2021-08-04 2021-09-03 2021-10-08 2022-04-06 travaux de réalisation de l'inf elopment cation Selection l ntation rastructure numérique dans l e parc de la Pendjari BJ-UCP / PADA-224084-CS-C QS / Sélection d'un cabinet p our l'élaboration d'un modèle Digital financial inclusion an Consultant Qualifi Open - Internationa économique et la mise en pla IDA / 64530 Post 150,000.00 184,108.49 Signed 2021-06-14 2021-05-07 2021-07-05 2021-06-21 2021-08-18 2021-09-03 2021-09-17 2021-12-01 2021-10-22 2021-12-16 2022-04-20 d skills cation Selection l ce d’application numérique e -conseil agricole pour l'accès à l’information des producteu rs sur les filières ciblées du p rojet BJ-UCP / PADA-234633-CS-C QS / Sélection d'un consultan Digital financial inclusion an Consultant Qualifi Open - Internationa Under Implement IDA / 64530 Post 200,000.00 0.00 2021-06-30 2021-07-13 2021-07-21 2021-09-03 2021-10-03 2021-11-07 2022-05-06 t pour l'identification numéri d skills cation Selection l ation que des agriculteurs et leurs exploitations BJ-UCP / PADA-234648-CS-C QS / Sélection d'un consultan t pour le renforcement des c Digital financial inclusion an Consultant Qualifi Pending Impleme apacités des acteurs de mise IDA / 64530 Post Limited 60,000.00 0.00 2021-06-30 2021-07-14 2021-08-13 2021-09-17 2022-03-16 d skills cation Selection ntation en oeuvre du Conseil Agricol e sur l'utilisation des outils in novants dans la production a gricole BJ-UCP / PADA-235363-CS-C QS / Recrutement d'un consu ltant pour l'appui au dévelop Extending connectivity in rur Consultant Qualifi Open - Internationa Under Implement pement d'application, et de s IDA / 64530 Post 288,000.00 0.00 2021-08-16 2021-07-13 2021-09-06 2021-10-20 2021-11-19 2021-12-24 2022-06-22 al areas cation Selection l ation ervices numériques dans les domaines prioritaires identifi és et amener de solution issu es des hackatons à maturatio n. BJ-UCP / PADA-235366-CS-C QS / Recrutement d'un consu ltant pour l'identification des référentiels, systèmes d'infor Extending connectivity in rur Consultant Qualifi Under Implement IDA / 64530 Post Limited 80,000.00 0.00 2021-07-05 2022-03-07 2021-07-19 2021-08-18 2021-09-22 2022-03-21 mation et base de données d al areas cation Selection ation u secteur agricole à connecte r à XROAD et développement des e-services à intégrer à se rvice-public.bj BJ-UCP / PADA-235490-CS-Q CBS / Recrutement d'un cabi Extending connectivity in rur Quality And Cost- Open - Internationa Under Implement IDA / 64530 Post 370,000.00 0.00 2021-07-20 2021-07-13 2021-08-10 2021-09-23 2021-10-21 2021-11-20 2021-12-25 2022-01-29 2023-01-29 net pour l'implémentation de al areas Based Selection l ation la conduite de changement O pen Data au Bénin BJ-UCP / PADA-239352-CS-C QS / Sélection d'un consultan Digital financial inclusion an Consultant Qualifi Open - Internationa Pending Impleme t pour la formation sur l'éduc IDA / 64530 Post 170,000.00 0.00 2021-07-30 2021-08-20 2021-10-03 2021-11-02 2021-12-07 2022-06-05 d skills cation Selection l ntation ation financière des acteurs des chaînes de valeur agricol es prioritaires BJ-UCP / PADA-277339-CS-C QS / Sélection d'un cabinet p our la mise en place d'une pl Digital financial inclusion an Consultant Qualifi Open - Internationa Pending Impleme ateforme numérique de form IDA / 64530 Post 100,000.00 0.00 2022-05-09 2022-05-30 2022-07-13 2022-08-12 2022-09-16 2023-03-15 d skills cation Selection l ntation alisation, de suivi et de l'éval uation des OPA des filières a ppuyées par le projet assorti e de modèle d'affaire BJ-UCP / PADA-277342-CS-C QS / Recrutement d'un cabin et pour la mise en place d'un Digital financial inclusion an Consultant Qualifi Open - Internationa Pending Impleme IDA / 64530 Post 100,000.00 0.00 2022-05-25 2022-06-15 2022-07-29 2022-08-28 2022-10-02 2023-03-31 e plateforme numérique de s d skills cation Selection l ntation uivi de la transhumance asso rtie de modèle économique BJ-UCP / PADA-277346-CS-C QS / Recrutement d'un cabin et pour la surveillance enviro Digital financial inclusion an Consultant Qualifi IDA / 64530 Post Limited 80,000.00 0.00 Signed 2022-03-15 2023-03-02 2022-03-29 2022-04-19 2022-04-28 2023-04-05 2022-06-02 2022-11-29 nnementale et le suivi de la d skills cation Selection mise en œuvre des PGES dan s le cadre des travaux de con nectivité des 118 villages BJ-UCP / PADA-279827-CS-C QS / Sélection d'un cabinet p Extending connectivity in rur Consultant Qualifi Under Implement IDA / 64530 Post Limited 180,000.00 0.00 2022-03-21 2022-03-04 2022-04-04 2022-12-30 2022-05-04 2023-02-24 2022-06-08 2022-12-05 our le contrôle des travaux d al areas cation Selection ation e connectivité dans les admi nistrations locales BJ-UCP / PADA-274841-CS-C DS / Sélection d'une ONG po ur l’opérationnalisation du M écanisme de Gestion des Plai Extending connectivity in rur Consultant Qualifi IDA / 64530 Post Limited 90,000.00 0.00 Signed 2022-03-07 2022-02-23 2022-03-21 2022-03-23 2022-04-20 2022-06-21 2022-05-25 2022-11-21 ntes pour deux sous projets ( al areas cation Selection connectivité des zones rurale s et connectivité des ATDA/C SA, IOT LAB et administration s locales) Page 5 BJ-UCP / PADA-190029-CS-C QS / Réalisation de l'étude de faisabilité d'un réseau d'accè Extending connectivity in rur Consultant Qualifi s HD par satellite desservant IDA / 64530 Post Open - National 30,000.00 0.00 Canceled 2020-10-12 2021-03-10 2020-11-02 2020-12-16 2021-01-15 2021-02-19 2021-08-18 al areas cation Selection les zones " blanches" pour le s secteurs université, centres de santé, coopératives agrico les et écoles. BJ-UCP / PADA-213079-CS-Q CBS / Contrôle et suivi des tr Extending connectivity in rur Least Cost Selecti Open - Internationa IDA / 64530 Post 350,000.00 0.00 Canceled 2021-05-19 2021-06-09 2021-07-23 2021-08-20 2021-09-19 2021-10-24 2021-11-28 2022-05-27 avaux de connectivité des un al areas on l iversités et autres établissem ent d'enseignement BJ-UCP / PADA-43674-CS-CQ S / Services de Consultant po Extending connectivity in rur Consultant Qualifi Open - Internationa IDA / V1370 Post 200,000.00 0.00 Canceled 2018-11-15 2018-12-06 2019-01-19 2019-02-18 2019-03-25 2019-09-21 ur la réalisation de l'étude su al areas cation Selection l r les services numériques agr icoles BJ-UCP / PADA-277343-CS-C QS / Elaboration et vulgarisat ion de la stratégie et du plan Digital financial inclusion an Consultant Qualifi IDA / 64530 Post Limited 50,000.00 0.00 Canceled 2022-04-25 2022-05-09 2022-06-08 2022-07-13 2023-01-09 d'actions pour le développem d skills cation Selection ent et une meilleure utilisatio n des statistiques agricoles BJ-UCP / PADA-213088-CS-C QS / Recrutement d'un consu ltant pour le renforcement de Digital financial inclusion an Consultant Qualifi IDA / 64530 Post Open - National 80,000.00 0.00 Canceled 2021-03-23 2021-04-13 2021-05-27 2021-06-26 2021-07-31 2022-01-27 s capacités des acteurs des c d skills cation Selection haînes de valeur agricole (y c ompris éducation financière i nclusive) BJ-UCP / PADA-213082-CS-C QS / Mission de contrôle et d Extending connectivity in rur Consultant Qualifi e suivi des travaux de réalisa IDA / 64530 Post Open - National 110,000.00 0.00 Canceled 2021-03-22 2021-04-12 2021-05-26 2021-06-25 2021-07-30 2022-01-26 al areas cation Selection tion des infrastructures numé riques dans les administratio ns locales BJ-UCP / PADA-213070-CS-C QS / Mission de contrôle des Extending connectivity in rur Consultant Qualifi Open - Internationa travaux d'extension des infra IDA / 64530 Post 280,000.00 0.00 Canceled 2021-06-30 2021-07-21 2021-09-03 2021-10-03 2021-11-07 2022-05-06 al areas cation Selection l structures de la connectivité dans les zones cibles du PITN 2R BJ-UCP / PADA-213084-CS-C QS / Contrôle des travaux de Extending connectivity in rur Consultant Qualifi IDA / 64530 Post Open - National 125,000.00 0.00 Canceled 2021-03-29 2021-04-21 2021-04-19 2021-06-02 2021-07-02 2021-08-06 2022-02-02 construction du réseau métro al areas cation Selection politain de Parakou BJ-UCP / PADA-223268-CS-C Extending connectivity in rur Consultant Qualifi QS / Actualisation du manuel IDA / 64530 Post Open - National 60,000.00 0.00 Canceled 2021-07-05 2021-07-26 2021-09-08 2021-10-08 2021-11-12 2022-05-11 al areas cation Selection d'opérations pour les investis sements BJ-UCP / PADA-224089-CS-Q CBS / Recrutement d'un cabi net pour la création de modu les de niveau basique de séc Digital financial inclusion an Quality And Cost- Open - Internationa IDA / 64530 Post 400,000.00 0.00 Canceled 2021-08-18 2021-09-08 2021-10-22 2021-11-19 2021-12-19 2022-01-23 2022-02-27 2023-02-27 urité numérique pour les lycé d skills Based Selection l es agricoles, les enseigneme nts primaire et secondaire et les cursus académiques spéc ialisés dans la sécurité numé rique BJ-UCP / PADA-190022-CS-C Digital solutions for rural dev Consultant Qualifi QS / Elaboration d'une politiq IDA / 64530 Post Open - National 30,000.00 0.00 Canceled 2020-09-28 2020-10-19 2020-12-02 2021-01-01 2021-02-05 2021-08-04 elopment cation Selection ue de protection des infrastr uctures critiques BJ-UCP / PADA-43769-CS-CQ S / Services de Consultant po Consultant Qualifi ur la réalisation de l'étude su / Post Open - National 100,000.00 0.00 Canceled 2018-02-15 2021-07-14 2018-03-01 2021-09-17 2018-03-15 2018-03-22 2018-04-05 2018-05-05 cation Selection r le modèle Economique de P PP pour l'accroissement de l' accès en zone rurale BJ-UCP / PADA-316569-CS-C QS / Étude de faisabilité de la Extending connectivity in rur Consultant Qualifi Under Implement IDA / 64530 Post Open - National 70,000.00 0.00 2022-10-18 2022-11-24 2022-11-08 2022-12-22 2023-01-21 2023-02-25 2023-08-24 construction d'un point d'éch al areas cation Selection ation anges internet à Parakou BJ-UCP / PADA-316567-CS-C QS / Recrutement d'un consu ltant pour l'élaboration d'un Digital financial inclusion an Consultant Qualifi Pending Impleme IDA / 64530 Post Limited 50,000.00 0.00 2022-12-15 2022-12-29 2023-01-28 2023-03-04 2023-08-31 modèle économique dans le d skills cation Selection ntation cadre de la mise en place d'u n centre multimédia de cons eil agricole au Bénin BJ-UCP / PADA-340043-CS-C QS / Recrutement d'un cabin Extending connectivity in rur Consultant Qualifi Pending Impleme et pour la réalisation de la Ca IDA / 64530 Post Open - National 185,000.00 0.00 2023-03-27 2023-04-17 2023-05-31 2023-06-30 2023-08-04 2024-01-31 al areas cation Selection ntation rtographie de couverture de l a TNT et de la radiodiffusion FM au Bénin. BJ-UCP / PADA-342240-CS-C QS / RECRUTEMENT D'UN CA BINET DE CONTROLE DES TR Extending connectivity in rur Consultant Qualifi Open - Internationa AVAUX D’INSTALLATION D’E IDA / 64530 Post 250,000.00 0.00 Canceled 2023-03-27 2023-04-17 2023-05-31 2023-06-30 2023-08-04 2024-01-31 al areas cation Selection l METTEURS FM, COMBINERS, SYSTEMES D’ANTENNES, CLI MATISEURS ET GROUPE ELEC TROGENE BJ-UCP / PADA-340041-CS-C QS / RECRUTEMENT D’UN CA BINET D’ASSISTANCE A MAIT Digital financial inclusion an Consultant Qualifi Under Implement RISE D’OUVRAGE (AMOA) PO IDA / 64530 Post Limited 275,000.00 0.00 2023-02-27 2023-03-01 2023-03-13 2023-04-25 2023-04-12 2023-06-13 2023-05-17 2023-11-13 d skills cation Selection ation UR LA MISE EN PLACE D’UNE PLATEFORME DE FINANCE N UMERIQUE MUTUALISEE AU P ROFIT DES SFD DU BENIN BJ-UCP / PADA-345056-CS-L CS / RECRUTEMENT D’UN CA Least Cost Selecti BINET POUR L’AUDIT COMPT IDA / 64530 Project implementation Post Open - National 16,000.00 0.00 Under Review 2023-05-10 2023-05-25 2023-05-31 2023-07-14 2023-08-11 2023-09-10 2023-10-15 2023-11-19 2024-05-17 on ABLE ET FINANCIER DES COM PTES DU PITN2R AU TITRE DE S EXERCICES 2023 ET 2024 BJ-UCP / PADA-352111-CS-C Consultant Qualifi Pending Impleme QS / Recrutement d'un consu IDA / 64530 Project implementation Post Open - National 63,640.00 0.00 2023-07-18 2023-08-08 2023-09-21 2023-10-21 2023-11-25 2024-05-23 cation Selection ntation ltant pour l'évaluation finale du projet Page 6 BJ-UCP / PADA-356580-CS-C QS / Conception d’un centre Digital financial inclusion an Consultant Qualifi Pending Impleme d’appel assistance conseil au IDA / 64530 Post Open - National 70,000.00 0.00 2023-07-11 2023-08-01 2023-09-14 2023-10-14 2023-11-18 2024-05-16 d skills cation Selection ntation x producteurs et élaboration d’un modèle économique BJ-UCP / PADA-235359-CS-C QS / Recrutement d'un consu ltant pour l'élaboration d'un Digital financial inclusion an Consultant Qualifi IDA / 64530 Post Limited 50,000.00 0.00 Canceled 2021-07-29 2023-03-03 2021-08-12 2021-09-11 2021-10-16 2022-04-14 modèle économique dans le d skills cation Selection cadre de la mise en place d'u n centre d'appel d'assistance -conseil BJ-UCP / PADA-357250-CS-C QS / Recrutement d'un consu Extending connectivity in rur Consultant Qualifi Open - Internationa Pending Impleme ltant pour le contrôle des tra IDA / 64530 Post 210,000.00 0.00 2023-07-10 2023-07-31 2023-09-13 2023-10-13 2023-11-17 2024-05-15 al areas cation Selection l ntation vaux de connectivité dans le s lycées agricoles (IOT Lab) BJ-UCP / PADA-357263-CS-Q CBS / Recrutement de presta taires privés du conseil agric Digital financial inclusion an Quality And Cost- Pending Impleme IDA / 64530 Post Open - National 230,000.00 0.00 2023-06-12 2023-07-03 2023-08-16 2023-09-13 2023-10-13 2023-11-17 2023-12-22 2024-12-21 ole pour la vulgarisation des d skills Based Selection ntation différentes plateformes num ériques développées par le PI TN2R au profit du MAEP BJ-UCP / PADA-352468-CS-C DS / Recrutement d’un consu Consultant Qualifi Pending Impleme ltant pour la réalisation d’enq IDA / 64530 Project implementation Post Open - National 63,640.00 0.00 2023-07-25 2023-08-15 2023-09-28 2023-10-28 2023-12-02 2024-05-30 cation Selection ntation uêtes de suivi des indicateur s clés du cadre de résultats d u projet BJ-UCP / PADA-352105-CS-C QS / Recrutement d'un consu Consultant Qualifi Pending Impleme ltant individuel pour la réalis IDA / 64530 Project implementation Post Limited 45,450.00 0.00 2023-07-10 2023-07-24 2023-08-23 2023-09-27 2024-03-25 cation Selection ntation ation d'enquêtes de satisfacti on des bénéficiaires du proje t PITN2R BJ-UCP / PADA-352103-CS-C QS / Analyse évaluative des plateformes développées en Digital financial inclusion an Consultant Qualifi Pending Impleme vue de la mise en place d’un IDA / 64530 Post Limited 40,000.00 0.00 2023-07-17 2023-07-31 2023-08-30 2023-10-04 2024-04-01 d skills cation Selection ntation e plateforme intégrée multis ervices, d’accès web et mobil e au profit du secteur de l’ag riculture INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-UCP / PADA-43669-CS-IND V / Services de Consultant po Individual Consult Under Implement / Post Limited 40,000.00 0.00 2018-01-25 2018-02-02 2018-01-30 2018-07-10 2018-02-13 2018-08-17 2018-02-27 2018-03-29 ur l'élaboration du manuel d' ant Selection ation exécution du Projet BJ-UCP / PADA-43740-CS-IND V / Service de Consultant pou Individual Consult Under Implement r l'élaboration du cadre de ge / Post Limited 50,000.00 0.00 2018-01-25 2017-10-02 2018-01-30 2018-01-02 2018-02-20 2018-07-17 2018-03-06 2018-04-05 ant Selection ation stion environnementale et so ciale (CGES) la réalisation de l'étude BJ-UCP / PADA-43757-CS-IND V / Service de consultant pou Individual Consult Under Implement / Post Limited 35,000.00 0.00 2018-01-25 2017-10-03 2018-01-30 2018-01-02 2018-02-13 2018-07-17 2018-02-27 2018-03-29 r l'élaboration du cadre de po ant Selection ation litique de réinstallation (CPR) BJ-UCP / PADA-43771-CS-IND Individual Consult Under Implement V / Service de consultant pou / Post Limited 50,000.00 0.00 2018-01-25 2018-01-26 2018-01-30 2017-12-24 2018-02-14 2018-09-12 2018-02-28 2018-03-30 ant Selection ation r l'élaboration du manuel d'o pération BJ-UCP / PADA-43772-CS-IND V / Service de consultant pou Individual Consult Under Implement / Post Limited 50,000.00 0.00 2018-01-15 2022-02-22 2018-01-20 2018-02-03 2018-02-17 2018-03-19 r l'appui à la stratégie de pas ant Selection ation sation des marchés PPSD BJ-UCP / PADA-87330-CS-IND Extending connectivity in rur Individual Consult V / Etude de faisabilité de la IDA / V1370 Post Limited 85,000.00 45,158.99 Signed 2018-11-15 2018-10-10 2018-11-20 2019-01-18 2018-12-11 2019-04-02 2019-01-15 2019-04-03 2019-07-14 al areas ant Selection composante BJ-UCP / PADA-99764-CS-CD S / sélection par Entente Dire cte d'un consultant individuel Digital solutions for rural dev Under Implement IDA / V1370 Post Direct Selection Direct 4,200.00 0.00 2019-02-15 2019-05-07 2019-02-25 2019-04-18 2019-03-18 2019-03-28 pour l'élaboration du Cadre d elopment ation e Politique de Réinstallation CPR de la composante 3 du Projet e-Agriculture BJ-UCP / PADA-99767-CS-CD S / sélection par Entente Dire cte d'un consultant individuel Digital solutions for rural dev IDA / V1370 Post Direct Selection Direct 4,200.00 5,040.39 Completed 2019-02-15 2019-05-07 2019-02-25 2019-04-18 2019-03-18 2018-07-18 2019-03-28 2018-08-18 pour l'élaboration du Cadre d elopment e Gestion Environnementale et Sociale CGES de la compo sante 3 du Projet e-Agricultur e BJ-UCP / PADA-109694-CS-IN DV / Recrutement d'un consu Individual Consult ltant pour l'appui à la passati IDA / V1370 Project implementation Post Direct 17,500.00 0.00 Canceled 2019-04-15 2019-04-24 2019-04-25 2019-05-02 2019-05-16 2019-08-14 ant Selection on des marchés pour la prép aration du projet e-Agricultur e BJ-UCP / PADA-111854-CS-IN DV / Sélection d'un consultan Extending connectivity in rur Individual Consult t individuel pour la réalisatio IDA / V1370 Post Limited 8,500.00 11,082.44 Signed 2019-05-10 2019-04-30 2019-05-17 2019-04-08 2019-06-07 2019-05-03 2019-07-12 2019-05-03 2019-08-11 al areas ant Selection n de la cartographie des zon es blanches et grises du Proj et PITN2R BJ-UCP / PADA-113996-CS-C DS / Recrutement d'un consu Under Implement ltant pour l'appui à la passati IDA / V1370 Project implementation Post Direct Selection Direct 17,500.00 0.00 2019-05-12 2019-05-09 2019-05-22 2019-04-03 2019-07-26 2020-01-22 ation on de marchés pour la prépa ration du Projet PITN2R Page 7 BJ-UCP / PADA-118367-CS-IN DV / Sélection d'un consultan Individual Consult t individuel pour l'élaboration IDA / V1370 Project implementation Post Limited 17,000.00 15,672.35 Signed 2019-06-11 2018-07-02 2019-06-16 2018-07-10 2019-07-07 2018-08-17 2019-08-11 2018-08-18 2020-02-07 ant Selection du manuel de procédures ad ministrative, financière et co mptable du Projet PITN2R BJ-UCP / PADA-133530-CS-IN DV / Recrutement du Coordo Individual Consult Under Implement IDA / V1370 Project implementation Prior Open 60,000.00 0.00 2019-09-16 2019-09-16 2019-11-04 2019-11-25 2019-12-30 2020-06-27 nnateur de l'Unité de coordin ant Selection ation ation du Projet PITN2R BJ-UCP / PADA-133531-CS-IN DV / Recrutement d'un spéci Individual Consult Under Implement aliste en Etreprenariat et dév IDA / V1370 Project implementation Prior Open 45,000.00 0.00 2019-09-16 2019-11-04 2019-11-25 2019-12-30 2020-06-27 ant Selection ation eloppement de l'écosystème numérique pour l'UCP du proj et PITN2R BJ-UCP / PADA-133533-CS-IN DV / recrutement d'un spécia Individual Consult Under Implement IDA / V1370 Project implementation Prior Open 45,000.00 0.00 2019-09-16 2019-09-27 2019-11-04 2019-11-25 2019-12-30 2020-06-27 liste en gestion financière de ant Selection ation l'UCP du Projet PITN2R BJ-UCP / PADA-133534-CS-IN DV / Recrutement d'un spéci Individual Consult Under Implement IDA / V1370 Project implementation Prior Open 45,000.00 0.00 2019-09-16 2019-09-18 2019-11-04 2019-11-25 2019-12-30 2020-06-27 aliste en passation de march ant Selection ation é de l'UCP du projet PITN2R BJ-UCP / PADA-133535-CS-IN DV / Recrutement d'un Spéci Individual Consult Under Implement IDA / V1370 Project implementation Prior Open 45,000.00 0.00 2019-09-16 2019-10-01 2019-11-04 2019-11-25 2019-12-30 2020-06-27 aliste en Infrastucture et Usa ant Selection ation ge Numérique de l'UCP du Pr ojet PITN2R BJ-UCP / PADA-133536-CS-IN DV / Recrutement d'un spéci Individual Consult Under Implement IDA / V1370 Project implementation Prior Open 45,000.00 0.00 2019-09-16 2019-09-18 2019-11-04 2019-11-25 2019-12-30 2020-06-27 aliste en Sauvegarde environ ant Selection ation nementale et Genre de l'UCP du Projet PITN2R BJ-UCP / PADA-133538-CS-IN DV / Recrutement d'un Spéci Individual Consult Under Implement IDA / V1370 Project implementation Prior Open 45,000.00 0.00 2019-09-16 2019-09-16 2019-11-04 2019-11-25 2019-12-30 2020-06-27 aliste en Sui-évaluation pour ant Selection ation l'UCP Projet PITN2R BJ-UCP / PADA-133539-CS-IN Individual Consult Under Implement DV / Recrutement d'un comp IDA / V1370 Project implementation Prior Open 28,000.00 0.00 2019-09-16 2019-09-27 2019-11-04 2019-11-25 2019-12-30 2020-06-27 ant Selection ation table pour l'UCP du Projet PIT N2R BJ-UCP / PADA-133540-CS-IN Individual Consult Under Implement DV / Recrutement d'un Assist IDA / V1370 Project implementation Prior Open 28,000.00 0.00 2019-09-16 2019-09-16 2019-11-04 2019-11-25 2019-12-30 2020-06-27 ant Selection ation ant Administratif du l'UCP du Projet PITN2R BJ-UCP / PADA-133541-CS-IN DV / Recrutement d'un Cond Individual Consult Under Implement IDA / V1370 Project implementation Prior Open 20,000.00 0.00 2019-09-16 2019-09-16 2019-11-04 2019-11-25 2019-12-30 2020-06-27 ucteur de Véhicule Administr ant Selection ation atif pour l'UCP du Projet PITN 2R BJ-UCP / PADA-134685-CS-C DS / Sélection d'un consultan t Individuel, Expert en Systè me d'Information pour l'élabo Under Implement IDA / V1370 Project implementation Post Direct Selection Direct 11,000.00 0.00 2019-09-20 2019-09-23 2019-09-30 2019-09-13 2019-12-04 2020-06-01 ration d'un Arrêté pour l'orga ation ne de contrôle des prestatair es de services de confiance d ans le domaine du Numériqu e au Bénin BJ-UCP / PADA-134688-CS-IN DV / Recrutement d'un Spéci Individual Consult IDA / V1370 Project implementation Prior Open 40,000.00 0.00 Canceled 2019-09-27 2019-11-15 2019-12-06 2020-01-10 2020-07-08 aliste du Développement Soc ant Selection ial et Genre pour l'UCP du pr ojet PITN2R BJ-UCP / PADA-135415-CS-IN DV / Recrutement d'un Spéci Individual Consult Under Implement IDA / V1370 Project implementation Prior Open 40,000.00 0.00 2019-09-27 2019-09-24 2019-11-15 2019-12-06 2020-01-10 2020-07-08 aliste en Développement Soc ant Selection ation ial et Genre pour l'UCP du Pr ojet PITN2R. BJ-UCP / PADA-140764-CS-IN DV / Recrutement d'un Conse Individual Consult Under Implement IDA / V1370 Project implementation Post Open 250,000.00 0.00 2019-10-28 2022-01-20 2019-12-16 2020-01-06 2020-02-10 2020-08-08 iller Stratégique pour le Minis ant Selection ation tère du Numérique et de la D igitalisation. BJ-UCP / PADA-144074-CS-IN DV / Recrutement d'un spéci Individual Consult aliste en Inclusion financière, IDA / V1370 Project implementation Post Open 45,000.00 0.00 Canceled 2019-11-11 2020-02-04 2019-12-30 2021-04-06 2020-01-20 2021-04-14 2020-02-24 2020-08-22 ant Selection numérique et compétence po ur l'UCP du Projet PITN2R. BJ-UCP / PADA-159141-CS-IN Individual Consult Under Implement DV / Recrutement d'un Audit IDA / 64530 Project implementation Post Open 45,000.00 0.00 2020-02-14 2020-04-01 2020-04-03 2020-04-24 2020-05-29 2020-11-25 ant Selection ation eur Interne pour l'UCP du Pro jet PITN2R BJ-UCP / PADA-160000-CS-C DS / Recrutement d'un Consu Under Implement ltant Individuel, Coordonnate IDA / 64530 Project implementation Post Direct Selection Direct 25,000.00 0.00 2020-02-24 2020-02-26 2020-03-05 2020-05-09 2020-11-05 ation ur Intérimaire du Projet PITN 2R pour une durée de trois (0 3) mois BJ-UCP / PADA-172644-CS-IN DV / Recrutement d'un Spéci Individual Consult Under Implement IDA / 64530 Project implementation Post Open 45,000.00 0.00 2020-05-15 2020-05-19 2020-07-03 2021-03-30 2020-07-24 2020-08-28 2021-02-24 aliste en développement agri ant Selection ation cole et rural pour l'UCP du Pr ojet PITN2R BJ-UCP / PADA-190031-CS-IN DV / Réalisation d'une revue Extending connectivity in rur Individual Consult Pending Impleme de la réglementation relative IDA / 64530 Post Open 30,000.00 0.00 2020-10-12 2020-11-30 2020-12-21 2021-01-25 2021-07-24 al areas ant Selection ntation à la collecte, au traitement et au stockage des données du secteur de l'agriculture BJ-UCP / PADA-190810-CS-C DS / Recrutement d'un cabin Digital solutions for rural dev et pour l'élaboration des text IDA / 64530 Post Direct Selection Direct 240,000.00 105,907.74 Signed 2020-10-05 2020-12-15 2020-10-15 2021-09-01 2020-12-19 2021-09-02 2021-06-17 elopment es d'application du code du n umérique en République du Bénin. Page 8 BJ-UCP / PADA-222343-CS-IN DV / Recrutement d'un Assist Individual Consult Under Implement IDA / 64530 Project implementation Post Open 28,000.00 0.00 2021-04-15 2021-04-06 2021-06-03 2021-06-24 2021-07-29 2022-01-25 ant en Passation des Marché ant Selection ation s au profit du PITN2R BJ-UCP / PADA-222408-CS-IN DV / Recrutement d'un consu Individual Consult IDA / 64530 Access to markets Post Open 30,000.00 32,705.04 Signed 2021-06-22 2021-06-24 2021-08-10 2021-12-28 2021-08-31 2022-01-17 2021-10-05 2022-03-24 2022-04-03 ltant individuel pour l'élabora ant Selection tion du manuel de subventio n du PITN2R BJ-UCP / PADA-224095-CS-C DS / Réalisation d'une étude Digital financial inclusion an IDA / 64530 Post Direct Selection Direct 30,000.00 54,069.82 Completed 2021-04-13 2021-03-26 2021-04-23 2021-09-01 2021-06-27 2021-09-07 2021-12-24 2022-04-02 Open Data Readiness Assess d skills ment (ODRA) pour la Républi que du Bénin BJ-UCP / PADA-260017-CS-C DS / RECRUTEMENT D’UN CO NSULTANT POUR LA MISE EN PLACE D’UN MANUEL DES OP ERATIONS, DES MECANISMES Extending connectivity in rur IDA / 64530 Post Direct Selection Direct 100,000.00 615,127.79 Signed 2021-11-18 2021-10-31 2021-11-28 2021-11-12 2022-02-01 2021-11-13 2022-07-31 DE FINANCEMENT BASES SU al areas R LE MODELE DE PARTENAIA T PUBLIC PRIVE (PPP) ET LA R EDACTION DU DOSSIER D’AP PEL D’OFFRES POUR ASSURE R L’ACCES AUX RESEAUX DE COMMUNICATIONS BJ-UCP / PADA-274976-CS-IN DV / Recrutement d'un consu Extending connectivity in rur Individual Consult Under Implement IDA / 64530 Post Limited 18,000.00 0.00 2022-03-07 2023-02-22 2022-03-12 2023-03-07 2022-04-02 2022-05-07 2022-11-03 ltant pour l'actualisation de l al areas ant Selection ation a PPSD du PITN2R BJ-UCP / PADA-277345-CS-C Digital financial inclusion an Individual Consult QS / Recrutement d'un consu IDA / 64530 Post Limited 15,000.00 15,628.95 Completed 2022-03-28 2022-03-04 2022-04-02 2022-04-01 2022-04-23 2022-05-13 2022-05-28 2022-06-04 2022-11-24 2022-07-14 d skills ant Selection ltant pour l'actualisation du C EGS du PITN2R BJ-UCP / PADA-277414-CS-IN DV / Sélection d'un consultan Digital financial inclusion an Individual Consult Under Implement IDA / 64530 Post Limited 40,000.00 0.00 2022-03-21 2022-03-25 2022-03-26 2022-04-16 2022-05-21 2022-11-17 t pour la rédaction du cahier d skills ant Selection ation de charges de la digital mark etplace BJ-UCP / PADA-274839-CS-C DS / Élaboration de textes co mplémentaires d’application Extending connectivity in rur Pending Impleme de la loi n°2017-20 du 20 avr IDA / 64530 Post Direct Selection Direct 140,000.00 0.00 2022-04-04 2022-04-14 2022-06-18 2022-12-15 al areas ntation il 2018 portant code du numérique en République du Bénin BJ-UCP / PADA-274843-CS-C DS / Supervision (contrôle) d Extending connectivity in rur IDA / 64530 Post Direct Selection Direct 300,000.00 0.00 Signed 2022-02-15 2022-04-25 2022-02-25 2022-05-10 2022-05-01 2022-10-28 es travaux relatifs à la conne al areas ctivité des zones rurales du P ITN2R BJ-UCP / PADA-289808-CS-IN DV / Recrutement d'un consu Individual Consult IDA / 64530 Project implementation Post Limited 18,000.00 0.00 Signed 2022-05-19 2022-04-27 2022-05-24 2022-06-23 2022-06-14 2022-08-17 2022-07-19 2023-01-15 ltant pour l'évaluation à mi p ant Selection arcours du PITN2R BJ-UCP / PADA-289810-CS-C DS / Recrutement d'un consu ltant pour la rédaction du DA Extending connectivity in rur O et le suivi-contrôle de la ré IDA / 64530 Post Direct Selection Direct 350,000.00 0.00 Signed 2022-06-01 2022-04-25 2022-06-11 2022-05-17 2022-08-15 2023-02-11 al areas alisation des travaux de cons truction du réseau métropolit ain en fibre optique de Parak ou BJ-UCP / PADA-316560-CS-C DS / Sélection d'un consultan Digital financial inclusion an Pending Impleme IDA / 64530 Post Direct Selection Direct - National 50,000.00 0.00 2022-11-02 2022-11-12 2023-01-16 2023-07-15 t pour le renforcement des fo d skills ntation nctionnalités de la plateform e e-conseil agricole BJ-UCP / PADA-340049-CS-IN DV / Recrutement d'un consu Extending connectivity in rur Individual Consult Under Implement IDA / 64530 Post Limited 8,000.00 0.00 2023-02-23 2023-03-06 2023-02-28 2023-04-04 2023-03-21 2023-04-25 2023-10-22 ltant individuel pour l'élabora al areas ant Selection ation tion d'un plan global de form ation BJ-UCP / PADA-352473-CS-IN DV / RECRUTEMENT D’UN CO NSULTANT INDIVIDUEL POUR L’ACTUALISATION, LA FINALI Digital financial inclusion an Individual Consult Under Implement IDA / 64530 Post Limited 15,450.00 0.00 2023-06-26 2023-05-31 2023-07-01 2023-07-22 2023-08-26 2024-02-22 SATION DE LA STRATEGIE NA d skills ant Selection ation TIONALE D’AGRICULTURE NU MERIQUE (SNAN 2023-2026) ET L'ACCOMPAGNEMENT A L A VALIDATION Page 9 CENTRAL SULAWESI REHABILITATION AND RECONSTRUCTION PROJECT (CSRRP) LOAN No. IBRD Ln.8979; AIIB LN 004-IDN Summary of Procurement Plan Version No.: 1 Date: February 11, 2020 I. General Information 1. Project information: a. Country: Indonesia b. Recipient: Republic of Indonesia c. Project Name: Indonesia Disaster Resilience Initiatives Project ((IDRIP) d. Project Implementing Agency (PIA): (i) Badan Nasional Penanggulangan Bencana (National Disaster Management Authority) (BNPB) (ii) Badan Meteorologi, Klimatologi, dan Geofisika (Indonesian Agency for Meteorology, Climatology, and Geophysics) (BMKG) 2. Bank’s No Objection Date of the Procurement Plan: a. Original : 5 March 2021 b. Version 2 : c. Version 3 : 3. Date of General Procurement Notice: 23 February 2021 4. Period covered by this procurement plan: Effectiveness – Loan Closing (31 December 2024) II. Types of Contract, Bank’s Review Requirements and Applied Methods A. Works, Goods and Non-Consulting Services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Ref. Procureme Bank’s Review Procurement Method No. nt Method Requirement Threshold 1. International Competitive ≥ $50 million Each contract shall Bidding (Works) be subject to Bank’s prior review. 2. National Competitive $200k - $50 Each contract ≥ Bidding (Works) million $20 million equivalent shall be subject to Bank’s prior review. All other contracts 3. Request for Quotations for < $200k priorto subject No post review Works review. (only post review). 4 Direct Selection for works Subject to ≥ US$ 10 million conditions as per paragraph 6.8, 6.9 and 6.10 of the 5. International Competitive Procurement ≥$4 million Each contract ≥ $4 Bidding (Goods) Regulations million equivalent shall be subject to Bank’s prior review. All other contracts subject to post 6. National Competitive $100k - $4 review. Each contract ≥ $2 Bidding (Goods) million million equivalent shall be subject to Bank’s prior review. All other contracts subject to post 7. Request for Quotations for <100k review. No prior review Goods (only post review). 8. Direct Selection for goods Subject to ≥ US$ 2 million conditions as per paragraph 6.8, 6.9 and 6.10 of the 9. International Competitive Procurement ≥$20 million Each contract shall Bidding (Non-Consultant Regulations be subject to Bank’s Service) prior review. 10. National Competitive $100k - $20 Each contract ≥ Bidding (Non-Consultant million $10 million Service) equivalent shall be subject to Bank’s prior review. All other contracts 11. Request for Quotations for <$100,000 priorto subject No post review Non-Consulting Service review. (only post review). 12. Direct Contracting for non- Subject to ≥ US$ 5 million consulting services conditions as per paragraph 6.8, 6.9 and 6.10 of the Procurement Regulations 1. Pre-qualification: Not applicable. 2. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: As specified in the Project Operations Manual (POM) 3. Reference to (if any) Project Operational/Procurement Manual: Project Operations Manual of CSRRP 4. Any Other Special Procurement Arrangements: -NA- 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Descripti Estimat Packag Domesti Revie Comments No. on ed es c w Cost Prefere by (US$ nce Bank million) (yes/no) (Prior / Post) 1. Summary 9.167 1 Yes Prior of the Internatio nal Open Competiti ve Procurem ent (Goods) 2. Summary 3.731 3 No Post of the NCB (Goods) 2. Summary 0.371 2 No Post of the NCB (Non- consulting Services) 3. Summary 0.694 1 No Post of the NCB (Works) B. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to prior review by Bank as stated in Appendix 1 to the Guidelines for Selection and Employment of Consultants: Ref. Selection Selection Method Bank’s Prior Review No. Method Threshold Requirement 1. International ≥$ 1 million Each contract ≥ Open (Firms) $1,000,000 equivalent QCBS, QBS, shall be subject to LCS, FBS Bank’s prior review. All other contracts subject to post review. Ref. Selection Selection Method Bank’s Prior Review No. Method Threshold Requirement 2. National Open <$ 1 million Each contract ≥ (Firms) QCS $1,000,000 equivalent shall be subject to Bank’s prior review. All other contracts subject to post review. 3 Direct Selection Subject to conditions as ≥ US$ 0.5 million per paragraph 7.13, 7.14 and 7.15 of the Procurement Regulations 4. Individual Competitive Selection by ≥ US$ 600k or as stated Consultant comparing at least three in the procurement plan CVs 5. Single Source Subject to conditions as ≥ US$ 300k (Firms and per paragraph 7.39 of the Individual) Procurement Regulations 2. Short list comprising entirely of national consultants: Short list of consultants for services (firms), estimated to cost less than $ 600,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: N/A 4. Summary of Consultancy Assignments with Selection Methods and Time Schedule during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref Descripti Type of Estimat Packag Revie Commen . on of Assignme ed es/Posit w ts No. Assignme nts Cost ions by nts (US$ Bank million) (Prior / Post) 1 Summary (Time- 0.17 10 Post of number Based) of individual consultant contracts that will be selected through competitiv 1 2 3 4 5 6 7 Ref Descripti Type of Estimat Packag Revie Commen . on of Assignme ed es/Posit w ts No. Assignme nts Cost ions by nts (US$ Bank million) (Prior / Post) e selection PROCUREMENT Indonesia : Indonesia Disaster Resilience Initiatives Project (IDRIP) PLAN General Information Country: Indonesia 2021-07-11 Bank’s Approval Date of the Original Procurement Plan: 2023-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P170874 GPN Date: 2021-02-22 Project Name: Indonesia Disaster Resilience Initiatives Project (IDRIP) Loan / Credit No: IBRD / 89800 Project Management Unit BNPB Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - ID-PMU BNPB-361195-CW-RF Component 1 Disaster prepa Single Stage - One E Small Works SPD Under Imple 2023-12-1 B / Construction of Central P IBRD / 89800 redness and emergency ma Post Request for Bids Open - National 591,273.00 0.00 2023-08-01 2023-08-11 2023-09-01 2023-09-08 2023-09-18 nvelope (1 envelope proce mentation 8 USDALOPS Infrastructure nagement capacity ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-PMU BNPB-247234-GO-RF Component 1 Disaster prepa Single Stage - One E B / Revitalization of BNPB's I IBRD / 89800 redness and emergency ma Post Request for Bids Open - National 1,042,000.00 948,178.06 Signed 2021-08-15 2021-10-29 2021-08-20 2021-10-29 2021-09-03 2021-11-18 2021-09-10 2021-11-23 2021-09-24 2021-12-07 2022-03-23 nvelope CT Network and Infrastructur nagement capacity e for MHEWS ID-PMU BNPB-246448-GO-RF Component 1 Disaster prepa Single Stage - One E B / Procurement of Contact C IBRD / 89800 redness and emergency ma Post Request for Bids Open - National 1,140,000.00 0.00 Signed 2021-08-06 2022-10-13 2021-08-20 2021-09-03 2022-10-20 2021-09-17 2022-10-26 2021-10-01 2023-12-20 nvelope entre for Command Centre (P nagement capacity usdalops) ID-PMU BNPB-246443-GO-RF Component 1 Disaster prepa Single Stage - One E B / Procurement of ICT Equip IBRD / 89800 redness and emergency ma Post Request for Bids Open - National 223,000.00 211,502.59 Signed 2021-08-06 2021-10-29 2021-08-11 2021-10-29 2021-08-25 2021-11-18 2021-09-01 2021-11-23 2021-09-15 2021-12-07 2021-12-14 nvelope ment for Contact Centre (Pus nagement capacity dalops) ID-PMU BNPB-317930-GO-RF B / Provision of Evacuation Si Component 1 Disaster prepa Single Stage - One E gnage and Information Board IBRD / 89800 redness and emergency ma Post Request for Bids Open - National 432,483.00 0.00 Canceled 2022-09-26 2022-10-11 2022-10-01 2022-10-31 2022-11-30 2022-12-28 2023-08-28 nvelope s Region 1 (Aceh, Sumatera nagement capacity Utara, Sumatera Barat, Beng kulu dan Lampung) ID-PMU BNPB-317931-GO-RF B / Provision of Evacuation Si Component 1 Disaster prepa Single Stage - One E gnage and Information Board IBRD / 89800 redness and emergency ma Post Request for Bids Open - National 353,747.00 0.00 Canceled 2022-09-26 2022-10-11 2022-10-01 2022-10-31 2022-11-30 2022-12-28 2023-08-28 nvelope s Region 2 (Banten, Jawa Bar nagement capacity at, Jawa Timur, dan NTB) ID-PMU BNPB-317932-GO-RF B / Provision of Evacuation Si Component 1 Disaster prepa Single Stage - One E gnage and Information Board IBRD / 89800 redness and emergency ma Post Request for Bids Open - National 588,020.00 0.00 Canceled 2022-09-26 2022-10-11 2022-10-01 2022-10-31 2022-11-30 2022-12-28 2023-08-28 nvelope s Region 3 (Sulawesi Barat, S nagement capacity ulawesi Tengah, Sulawesi Ut ara dan Sulawesi Selatan) ID-PMU BNPB-317933-GO-RF B / Provision of Evacuation Si Component 1 Disaster prepa Single Stage - One E gnage and Information Board IBRD / 89800 redness and emergency ma Post Request for Bids Open - National 580,436.00 0.00 Canceled 2022-09-26 2022-10-11 2022-10-01 2022-10-31 2022-11-30 2022-12-28 2023-08-28 nvelope s Region 4 (Maluku, Maluku U nagement capacity tara, Papua dan Papua Barat) ID-PMU BNPB-323965-GO-RF Component 1 Disaster prepa B / Provision of Evacuation Si Single Stage - One E IBRD / 89800 redness and emergency ma Post Request for Bids Open - National 1,250,000.00 0.00 Signed 2022-11-04 2022-11-30 2022-11-09 2022-11-23 2022-12-08 2022-12-07 2022-12-15 2023-01-04 2023-12-13 gnage and Information Board nvelope nagement capacity s in 30 Districts/ Cities ID-PMU BNPB-324376-GO-RF Component 1 Disaster prepa Single Stage - One E B / Revitalization of Data Cen IBRD / 89800 redness and emergency ma Post Request for Bids Open - National 3,472,222.00 0.00 Signed 2022-11-04 2022-12-14 2022-11-09 2022-11-23 2022-12-14 2022-11-30 2022-12-23 2022-12-14 2023-02-14 nvelope ter (BNPB-Sentul) nagement capacity ID-PMU BNPB-324377-GO-RF Component 1 Disaster prepa Single Stage - One E B / Revitalization of Data Cen IBRD / 89800 redness and emergency ma Post Request for Bids Open - National 1,736,111.00 0.00 Canceled 2022-11-04 2022-11-09 2022-11-23 2022-11-30 2022-12-14 2023-02-14 nvelope ter (Graha BNPB-Pramuka) nagement capacity ID-PMU BNPB-324378-GO-RF Component 1 Disaster prepa Single Stage - One E B / Software Licenses for Dat IBRD / 89800 redness and emergency ma Post Request for Bids Open - National 1,736,111.00 0.00 Canceled 2022-11-04 2022-11-09 2022-11-23 2022-11-30 2022-12-14 2023-02-14 nvelope a Center nagement capacity ID-PMU BNPB-333834-GO-RF Component 1 Disaster prepa Single Stage - One E Under Imple B / Revitalization of Data Cen IBRD / 89800 redness and emergency ma Post Request for Bids Open - National 1,736,111.00 0.00 2022-12-27 2022-12-30 2023-01-01 2023-01-15 2023-01-22 2023-01-30 2023-04-02 nvelope mentation ter (Graha BNPB-Pramuka) nagement capacity ID-PMU BNPB-333835-GO-RF Component 1 Disaster prepa Single Stage - One E Under Imple B / Software Licenses for Dat IBRD / 89800 redness and emergency ma Post Request for Bids Open - National 1,736,111.00 0.00 2022-12-27 2022-12-30 2023-01-01 2023-01-15 2023-01-22 2023-01-30 2023-04-02 nvelope mentation a Center nagement capacity ID-PMU BNPB-361234-GO-RF Component 1 Disaster prepa B / Procurement of Informati Single Stage - One E Pending Impl IBRD / 89800 redness and emergency ma Post Request for Bids Open - National 407,775.00 0.00 2023-05-15 2023-05-25 2023-06-24 2023-07-24 2023-08-01 2023-10-31 on Communication Technolo nvelope ementation nagement capacity gy for The Central PUSDALOP S NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-PMU BNPB-246449-NC-RF Component 1 Disaster prepa Request for Quota Single Stage - One E Q / Training of Facilitator for IBRD / 89800 redness and emergency ma Post Open - National 69,500.00 0.00 Signed 2021-08-11 2021-09-11 2021-12-10 tions nvelope Disaster Preparedness nagement capacity ID-PMU BNPB-308651-NC-RF Component 1 Disaster prepa Single Stage - One E B / Service Provider for Conti IBRD / 89800 redness and emergency ma Post Request for Bids Open - National 844,640.00 0.00 Canceled 2022-08-10 2022-08-15 2022-08-24 2022-09-23 2022-10-23 2022-11-13 2023-09-13 nvelope ngency Plan Development nagement capacity Page 1 ID-PMU BNPB-311800-NC-RF Component 1 Disaster prepa B / Service Provider for Conti Single Stage - One E IBRD / 89800 redness and emergency ma Post Request for Bids Open - National 1,111,111.00 0.00 Canceled 2022-08-26 2022-09-26 2022-08-31 2022-10-12 2022-11-11 2022-12-16 2023-10-16 ngency Plan Development in nvelope nagement capacity 70 Districts/ Cities ID-PMU BNPB-318236-NC-RF B / Strengthening Communit Component 1 Disaster prepa Single Stage - One E y Preparedness in Region 1 ( IBRD / 89800 redness and emergency ma Post Request for Bids Open - National 6,107,650.00 0.00 Canceled 2022-10-17 2022-10-22 2022-11-05 2022-11-19 2022-11-24 2024-05-24 nvelope Aceh, Sumatera Utara, Suma nagement capacity tera Barat, Bengkulu dan La mpung) ID-PMU BNPB-318237-NC-RF B / Strengthening Communit Component 1 Disaster prepa Single Stage - One E y Preparedness in Region 2 ( IBRD / 89800 redness and emergency ma Post Request for Bids Open - National 7,617,080.00 0.00 Canceled 2022-10-17 2022-10-22 2022-11-05 2022-11-19 2022-11-24 2024-05-24 nvelope Banten, DI Yogyakarta, Jawa nagement capacity Barat, Jawa Timur, Bali, NTT dan NTB) ID-PMU BNPB-323961-NC-RF Component 1 Disaster prepa B / Strengthening Communit Single Stage - One E IBRD / 89800 redness and emergency ma Post Request for Bids Open - National 2,120,000.00 0.00 Signed 2022-10-31 2022-12-02 2022-11-04 2022-11-18 2022-12-12 2022-12-02 2022-12-16 2022-12-07 2024-06-06 y Resilience in Region 1 (Ban nvelope nagement capacity ten, West Sumatra, Lampung , Bengkulu) ID-PMU BNPB-323962-NC-RF B / Strengthening Communit Component 1 Disaster prepa Single Stage - One E y Resilience in Region 2 (DIY, IBRD / 89800 redness and emergency ma Post Request for Bids Open - National 3,230,500.00 0.00 Signed 2022-10-31 2022-12-02 2022-11-04 2022-11-18 2022-12-12 2022-12-02 2022-12-16 2022-12-07 2024-06-06 nvelope Central Java, West Java, East nagement capacity Java, Bali, NTT, NTB, Papua, West Papua) ID-PMU BNPB-323964-NC-RF B / Strengthening Communit Component 1 Disaster prepa Single Stage - One E y Resilience in Region 3 (Cen IBRD / 89800 redness and emergency ma Post Request for Bids Open - National 2,232,100.00 0.00 Signed 2022-10-31 2022-12-02 2022-11-04 2022-11-18 2022-12-12 2022-12-02 2022-12-16 2022-12-07 2024-06-06 nvelope tral Sulawesi, North Sulawesi, nagement capacity Maluku, North Maluku) ID-PMU BNPB-323966-NC-RF Component 1 Disaster prepa B / Service Provider for Conti Single Stage - One E IBRD / 89800 redness and emergency ma Post Request for Bids Open - National 1,041,750.00 0.00 Signed 2022-11-04 2022-12-02 2022-11-09 2022-11-23 2022-12-05 2022-12-07 2022-12-16 2023-01-04 2023-11-04 ngency Plan Development in nvelope nagement capacity 30 Districts/ Cities ID-PMU BNPB-353896-NC-RF Component 1 Disaster prepa Single Stage - One E Pending Impl B / Training for Pusdalops Ma IBRD / 89800 redness and emergency ma Post Request for Bids Open - National 590,277.00 0.00 2023-04-03 2023-04-10 2023-04-24 2023-05-08 2023-05-23 2023-11-22 nvelope ementation nagement & Operation nagement capacity ID-PMU BNPB-361188-NC-RF Component 1 Disaster prepa Single Stage - One E Under Imple B / Support for Secretariat P IBRD / 89800 redness and emergency ma Post Request for Bids Open - National 506,158.00 0.00 2023-05-11 2023-06-05 2023-05-21 2023-06-11 2023-06-18 2023-06-20 2024-12-19 nvelope mentation MU Component 1 nagement capacity CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-PMU BNPB-242834-CS-CQ Component 1 Disaster prepa Consultant Qualifi S / Study for DM Strategy De IBRD / 89800 redness and emergency ma Post Open - National 160,000.00 0.00 Canceled 2021-07-09 2021-07-23 2021-07-23 2021-11-19 2021-08-13 2021-12-16 2021-08-27 2022-01-14 2021-09-17 2021-12-16 cation Selection velopment in Disaster Prone nagement capacity Zones ID-PMU BNPB-243023-CS-CQ Component 1 Disaster prepa Consultant Qualifi S / Development of Disaster IBRD / 89800 redness and emergency ma Post Open - National 105,000.00 102,608.02 Signed 2021-07-12 2021-09-24 2021-08-02 2021-11-12 2021-09-15 2021-12-10 2021-10-15 2022-01-07 2021-11-19 2022-04-21 2022-05-18 cation Selection Knowledge Management Syst nagement capacity em ID-PMU BNPB-244841-CS-CQ Component 1 Disaster prepa Consultant Qualifi S / Feasibility Study for Multi IBRD / 89800 redness and emergency ma Post Open - National 125,000.00 107,584.93 Signed 2021-07-21 2021-09-24 2021-07-28 2021-09-30 2021-08-25 2021-11-03 2021-09-08 2021-12-09 2021-09-22 2021-12-11 2021-12-21 cation Selection Hazard Early Warning Syste nagement capacity m ID-PMU BNPB-259643-CS-QC Component 1 Disaster prepa BS / Identification of Priority Quality And Cost- Open - Internationa IBRD / 89800 redness and emergency ma Post 902,777.00 0.00 Signed 2021-11-01 2022-04-18 2021-11-22 2022-06-14 2022-01-05 2022-08-01 2022-02-02 2022-10-07 2022-03-04 2022-10-07 2022-04-08 2022-11-01 2022-05-13 2023-05-13 Location and Risk Analysis in Based Selection l nagement capacity Eastern Indonesia ID-PMU BNPB-259651-CS-QC Component 1 Disaster prepa BS / Identification of Priority Quality And Cost- Open - Internationa IBRD / 89800 redness and emergency ma Post 833,333.33 0.00 Signed 2021-11-01 2022-04-18 2021-11-22 2022-06-14 2022-01-05 2022-08-01 2022-02-02 2022-10-07 2022-03-04 2022-10-07 2022-04-08 2022-11-01 2022-05-13 2023-05-13 Location and Risk Analysis in Based Selection l nagement capacity Western Indonesia ID-PMU BNPB-295772-CS-CQ Component 1 Disaster prepa Consultant Qualifi S / Study for DM Strategy De IBRD / 89800 redness and emergency ma Post Open - National 160,000.00 0.00 Signed 2022-05-18 2022-05-30 2022-06-01 2022-08-25 2022-06-22 2022-09-23 2022-07-06 2022-10-19 2022-07-27 2022-10-25 cation Selection velopment in Disaster Prone nagement capacity Zones ID-PMU BNPB-311809-CS-QC Component 1 Disaster prepa Quality And Cost- BS / Development for Concep IBRD / 89800 redness and emergency ma Post Open - National 194,444.00 0.00 Canceled 2022-08-26 2022-09-05 2022-09-16 2022-10-30 2022-11-27 2022-12-27 2023-01-31 2023-03-07 2023-09-03 Based Selection t of Operations for MHEWS pl nagement capacity atform ID-PMU BNPB-311813-CS-CQ Component 1 Disaster prepa Consultant Qualifi S / Operational Manual, Tech IBRD / 89800 redness and emergency ma Post Open - National 193,000.00 0.00 Signed 2022-08-26 2022-09-05 2022-09-16 2022-10-30 2022-12-21 2022-11-29 2022-12-27 2023-01-03 2023-04-06 cation Selection nical Manual, Module for Des nagement capacity tana ID-PMU BNPB-314645-CS-CQ Component 1 Disaster prepa Consultant Qualifi S / Assessment for Revitaliza IBRD / 89800 redness and emergency ma Post Open - National 222,222.00 0.00 Canceled 2022-09-14 2022-09-21 2022-10-12 2022-10-19 2022-10-23 2023-01-22 cation Selection tion BNPB's ICT Network and nagement capacity Infrastructure ID-PMU BNPB-315351-CS-CQ Component 1 Disaster prepa Consultant Qualifi S / Development for Concept IBRD / 89800 redness and emergency ma Post Open - National 194,444.00 0.00 Signed 2022-09-13 2022-09-22 2022-10-04 2022-11-17 2022-10-27 2022-12-17 2022-11-10 2023-01-21 2023-07-23 cation Selection of Operations for MHEWS pla nagement capacity tform ID-PMU BNPB-318247-CS-CQ Component 1 Disaster prepa S / Development of Module a Consultant Qualifi Under Implement IBRD / 89800 redness and emergency ma Post Open - National 139,000.00 0.00 2022-11-07 2023-06-09 2022-11-21 2022-12-19 2022-12-26 2023-01-01 2023-06-30 nd Curriculum of Disaster Pre cation Selection ation nagement capacity paredness Training ID-PMU BNPB-318250-CS-CQ Component 1 Disaster prepa S / Study the Use of Innovati Consultant Qualifi Under Implement IBRD / 89800 redness and emergency ma Post Open - National 69,500.00 0.00 2022-10-10 2022-11-08 2022-10-17 2022-11-14 2022-11-21 2022-11-26 2023-01-26 ve Technologies for Awarene cation Selection ation nagement capacity ss Building and Outreach Pro grams ID-PMU BNPB-245016-CS-CQ Component 1 Disaster prepa S / Development of Module a Consultant Qualifi IBRD / 89800 redness and emergency ma Post Open - National 209,000.00 0.00 Canceled 2021-07-22 2021-07-23 2021-07-29 2021-09-02 2021-09-09 2021-10-05 2022-02-02 nd Curriculum of Disaster Pre cation Selection nagement capacity paredness Training Page 2 ID-PMU BNPB-339229-CS-CQ Component 1 Disaster prepa S / Expansion of the prototyp Consultant Qualifi IBRD / 89800 redness and emergency ma Post Open - National 347,222.22 0.00 Signed 2023-02-03 2023-02-09 2023-02-13 2023-03-30 2023-02-27 2023-04-18 2023-03-02 2023-05-16 2023-03-06 2023-11-01 e of Disaster Knowledge Man cation Selection nagement capacity agement System ID-PMU BNPB-357100-CS-CQ Component 1 Disaster prepa Consultant Qualifi Under Implement S / Study for Pusdalops Capa IBRD / 89800 redness and emergency ma Post Open - National 270,000.00 0.00 2023-05-15 2023-06-22 2023-05-22 2023-06-11 2023-06-21 2023-06-25 2023-08-24 cation Selection ation city Building nagement capacity ID-PMU BNPB-357097-CS-QC Component 1 Disaster prepa BS / Monitoring for Implemen Quality And Cost- Open - Internationa Pending Impleme IBRD / 89800 redness and emergency ma Post 689,305.00 0.00 2023-05-01 2023-05-11 2023-06-24 2023-07-08 2023-07-22 2023-08-19 2023-08-27 2024-11-25 tation of Strengthening Com Based Selection l ntation nagement capacity munity Resilience in Region 1 ID-PMU BNPB-357099-CS-QC Component 1 Disaster prepa BS / Monitoring for Implemen Quality And Cost- Open - Internationa Pending Impleme IBRD / 89800 redness and emergency ma Post 817,705.00 0.00 2023-05-01 2023-05-11 2023-06-24 2023-07-08 2023-07-22 2023-08-19 2023-08-27 2024-11-25 tation of Strengthening Com Based Selection l ntation nagement capacity munity Resilience in Region 2 ID-PMU BNPB-361191-CS-CQ Component 1 Disaster prepa Consultant Qualifi S / Construction Managemen IBRD / 89800 redness and emergency ma Post Open - National 511,034.00 0.00 Under Review 2023-05-15 2023-05-12 2023-05-25 2023-06-29 2023-07-06 2023-07-10 2024-11-08 cation Selection t for Pusdalops nagement capacity ID-PMU BNPB-361193-CS-CQ Component 1 Disaster prepa Consultant Qualifi Under Implement S / Project Planning Consulta IBRD / 89800 redness and emergency ma Post Open - National 400,965.00 0.00 2023-05-14 2023-05-12 2023-05-24 2023-06-21 2023-06-28 2023-06-30 2024-04-29 cation Selection ation nt for Pusdalops nagement capacity ID-PMU BNPB-323969-CS-QC Component 1 Disaster prepa BS / Monitoring for Implemen Quality And Cost- Open - Internationa Pending Impleme IBRD / 89800 redness and emergency ma Post 831,221.00 0.00 2023-05-15 2023-06-05 2023-08-04 2023-09-01 2023-10-01 2023-11-05 2023-12-10 2025-03-10 tation of Strengthening Com Based Selection l ntation nagement capacity munity Resilience in Region 3 ID-PMU BNPB-361236-CS-CQ Component 1 Disaster prepa Consultant Qualifi Pending Impleme S / Development of Pusdalop IBRD / 89800 redness and emergency ma Post Open - National 306,497.00 0.00 2023-05-15 2023-05-25 2023-06-18 2023-07-02 2023-07-10 2024-01-08 cation Selection ntation s Management System nagement capacity ID-PMU BNPB-361672-CS-CQ Component 1 Disaster prepa S / Design Planning Consultin Consultant Qualifi Pending Impleme IBRD / 89800 redness and emergency ma Post Open - National 107,171.00 0.00 2023-05-15 2023-06-05 2023-07-03 2023-07-17 2023-07-28 2023-11-25 g Services and TIA-942 Data cation Selection ntation nagement capacity Center Certification ID-PMU BNPB-361700-CS-CQ S / Identification of needs for Component 1 Disaster prepa Consultant Qualifi strengthening the disseminat IBRD / 89800 redness and emergency ma Post Open - National 168,719.00 0.00 Under Review 2023-05-22 2023-06-27 2023-06-12 2023-07-10 2023-07-24 2023-08-01 2023-12-31 cation Selection ion system of earthquake an nagement capacity d tsunami threat information and warnings ID-PMU BNPB-361714-CS-CQ Component 1 Disaster prepa S / Study for DM Strategy De Consultant Qualifi Pending Impleme IBRD / 89800 redness and emergency ma Post Open - National 522,947.00 0.00 2023-05-22 2023-06-12 2023-07-10 2023-07-24 2023-08-01 2024-03-31 velopment in Disaster Prone cation Selection ntation nagement capacity Zones (Phase 2) ID-PMU BNPB-367923-CS-CQ Component 1 Disaster prepa S / Development of Detailed Consultant Qualifi Under Implement IBRD / 89800 redness and emergency ma Post Open - National 107,585.00 0.00 2023-06-21 2023-06-21 2023-06-28 2023-07-12 2023-07-19 2023-07-23 2023-09-23 Engineering Design (DED) of cation Selection ation nagement capacity Multi Hazard Early Warning S ystem INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-PMU BNPB-245719-CS-CD Component 1 Disaster prepa Individual Consult S / Early Warning System Tec IBRD / 89800 redness and emergency ma Post Open 6,945.00 0.00 Canceled 2021-07-27 2021-11-05 2021-08-15 2021-08-18 2021-08-26 2021-12-24 ant Selection hnical Specialist nagement capacity ID-PMU BNPB-245724-CS-IN Component 1 Disaster prepa Individual Consult DV / Social Disaster Technica IBRD / 89800 redness and emergency ma Post Open 6,945.00 0.00 Signed 2021-07-27 2021-11-05 2021-08-15 2021-12-17 2021-08-18 2022-01-07 2021-08-26 2021-12-24 ant Selection l Specialist nagement capacity ID-PMU BNPB-246442-CS-IN DV / Individual Consultant for Component 3 Project imple Individual Consult IBRD / 89800 Post Open 5,990.00 0.00 Canceled 2021-07-30 2021-08-09 2021-08-12 2021-08-17 2021-08-25 2022-01-22 Disaster Risk Management IT mentation support ant Selection Specialist (DRM 3) ID-PMU BNPB-310792-CS-IN Component 1 Disaster prepa DV / Information Technology Individual Consult IBRD / 89800 redness and emergency ma Post Open - National 7,000.00 0.00 Signed 2022-08-19 2022-09-05 2022-10-07 2022-11-16 2022-10-28 2022-11-17 2022-12-02 2023-06-03 (IT) Individual Consultant for ant Selection nagement capacity Network and Infrastructure in the MHEWS DED ID-PMU BNPB-310799-CS-IN DV / Information Technology Component 1 Disaster prepa Individual Consult (IT) Individual Consultant for IBRD / 89800 redness and emergency ma Post Open - National 7,000.00 0.00 Signed 2022-08-19 2022-09-05 2022-10-07 2022-11-16 2022-10-28 2022-11-17 2022-12-02 2023-06-03 ant Selection System Analyst in the Imple nagement capacity mentation of MHEWS DED ID-PMU BNPB-333836-CS-IN DV / Monitoring and Evaluati Component 1 Disaster prepa Individual Consult Under Implement on Specialist for Identificatio IBRD / 89800 redness and emergency ma Post Open - National 5,600.00 0.00 2022-12-27 2022-12-29 2023-01-13 2023-01-14 2023-01-16 2023-07-18 ant Selection ation n of Priority Location and Ris nagement capacity k Analysis in Western Indone sia ID-PMU BNPB-333837-CS-IN DV / Monitoring and Evaluati Component 1 Disaster prepa Individual Consult Under Implement on Specialist for Identificatio IBRD / 89800 redness and emergency ma Post Open - National 5,600.00 0.00 2022-12-27 2022-12-29 2023-01-13 2023-01-14 2023-01-16 2023-07-18 ant Selection ation n of Priority Location and Ris nagement capacity k Analysis in Eastern Indones ia ID-PMU BNPB-339235-CS-IN DV / Public Policy and Govern Component 1 Disaster prepa Individual Consult Pending Impleme ance Analyst for Academic P IBRD / 89800 redness and emergency ma Post Open - National 3,128.12 0.00 2023-02-01 2023-03-01 2023-03-08 2023-03-14 2023-09-10 ant Selection ntation aper Development of instituti nagement capacity onal and regulatory framewo rk for MHEWS ID-PMU BNPB-356133-CS-IN Component 1 Disaster prepa Individual Consult Under Implement DV / Pusdalops Management IBRD / 89800 redness and emergency ma Post Open - National 18,857.00 0.00 2023-04-12 2023-04-18 2023-05-17 2023-05-24 2023-05-26 2024-01-24 ant Selection ation Specialist Individual Consulta nagement capacity nt Page 3 ID-PMU BNPB-356139-CS-IN Component 1 Disaster prepa Individual Consult Under Implement DV / Room Design and Civil IBRD / 89800 redness and emergency ma Post Open - National 18,857.00 0.00 2023-04-12 2023-04-18 2023-05-17 2023-05-24 2023-05-26 2024-01-24 ant Selection ation Works Specialist Individual C nagement capacity onsultant ID-PMU BNPB-356140-CS-IN Component 1 Disaster prepa DV / System Analyst and Info Individual Consult Under Implement IBRD / 89800 redness and emergency ma Post Open - National 18,857.00 0.00 2023-04-12 2023-04-18 2023-05-17 2023-05-24 2023-05-26 2024-01-24 rmation Technology Specialis ant Selection ation nagement capacity t Individual Consultant ID-PMU BNPB-339238-CS-IN Component 1 Disaster prepa DV / Team Leader for Acade Individual Consult Under Implement IBRD / 89800 redness and emergency ma Post Open - National 4,414.00 0.00 2023-02-01 2023-04-14 2023-03-01 2023-05-24 2023-03-08 2023-05-31 2023-03-14 2023-05-13 mic Paper Development of in ant Selection ation nagement capacity stitutional and Regulatory Fr amework for MHEWS ID-PMU BNPB-339232-CS-IN DV / Administrative Law Spec Component 1 Disaster prepa Individual Consult Under Implement ialist for Academic Paper Dev IBRD / 89800 redness and emergency ma Post Open - National 2,230.00 0.00 2023-02-01 2023-04-14 2023-03-01 2023-05-24 2023-03-08 2023-05-31 2023-03-14 2023-05-13 ant Selection ation elopment of institutional and nagement capacity regulatory framework for MH EWS ID-PMU BNPB-339233-CS-IN DV / Disaster Risk Manageme Component 1 Disaster prepa Individual Consult Under Implement nt Specialist for Academic Pa IBRD / 89800 redness and emergency ma Post Open - National 2,230.00 0.00 2023-02-01 2023-04-14 2023-03-01 2023-05-24 2023-03-08 2023-05-31 2023-03-14 2023-09-10 ant Selection ation per Development of institutio nagement capacity nal and regulatory framewor k for MHEWS ID-PMU BNPB-356132-CS-IN Component 1 Disaster prepa Individual Consult DV / Command Center Speci IBRD / 89800 redness and emergency ma Post Open - National 18,857.00 0.00 Canceled 2023-04-12 2023-04-18 2023-05-17 2023-05-24 2023-05-26 2024-01-24 ant Selection alist Individual Consultant nagement capacity ID-PMU BNPB-356135-CS-IN Component 1 Disaster prepa Individual Consult DV / Radio Communication S IBRD / 89800 redness and emergency ma Post Open - National 18,857.00 0.00 Canceled 2023-04-12 2023-04-18 2023-05-17 2023-05-24 2023-05-26 2024-01-24 ant Selection pecialist Individual Consultan nagement capacity t ID-PMU BNPB-356125-CS-IN Component 1 Disaster prepa Individual Consult DV / Information Technology IBRD / 89800 redness and emergency ma Post Open - National 18,857.00 0.00 Canceled 2023-04-12 2023-04-18 2023-05-17 2023-05-24 2023-05-26 2024-01-24 ant Selection and Network Specialist Indivi nagement capacity dual Consultant ID-PMU BNPB-356113-CS-IN Component 1 Disaster prepa Individual Consult DV / Team Leader for Pusdal IBRD / 89800 redness and emergency ma Post Open - National 26,939.00 0.00 Canceled 2023-04-12 2023-04-18 2023-05-17 2023-05-24 2023-05-26 2024-01-24 ant Selection ops Individual Consultant nagement capacity ID-PMU BNPB-361202-CS-IN Component 1 Disaster prepa Individual Consult Under Implement DV / Project Management Sp IBRD / 89800 redness and emergency ma Post Open - National 16,651.00 0.00 2023-05-15 2023-05-26 2023-06-19 2023-06-26 2023-06-30 2024-01-28 ant Selection ation ecialist Individual Consultant nagement capacity for Pusdalops ID-PMU BNPB-361204-CS-IN Component 1 Disaster prepa Individual Consult Under Implement DV / Contact Center Specialis IBRD / 89800 redness and emergency ma Post Open - National 4,757.00 0.00 2023-05-15 2023-05-26 2023-06-19 2023-06-26 2023-06-30 2023-08-31 ant Selection ation t Individual Consultant for Pu nagement capacity sdalops ID-PMU BNPB-361206-CS-IN Component 1 Disaster prepa DV / Information Technology Individual Consult Under Implement IBRD / 89800 redness and emergency ma Post Open - National 4,757.00 0.00 2023-05-15 2023-05-26 2023-06-19 2023-06-26 2023-06-30 2023-08-31 and Network Specialist Indivi ant Selection ation nagement capacity dual Consultant for Pusdalop s ID-PMU BNPB-361208-CS-IN Component 1 Disaster prepa Individual Consult Under Implement DV / Radio Communication S IBRD / 89800 redness and emergency ma Post Open - National 2,719.00 0.00 2023-05-15 2023-05-26 2023-06-19 2023-06-26 2023-06-30 2023-08-31 ant Selection ation pecialist Individual Consultan nagement capacity t ID-PMU BNPB-361439-CS-IN Component 1 Disaster prepa DV / Database Management Individual Consult Under Implement IBRD / 89800 redness and emergency ma Post Open - National 13,572.00 0.00 2023-05-15 2023-05-26 2023-06-12 2023-06-19 2023-06-23 2024-01-22 Specialist Individual Consulta ant Selection ation nagement capacity nt for Pusdatin PB ID-PMU BNPB-361442-CS-IN Component 1 Disaster prepa DV / Network and Infrastruct Individual Consult Under Implement IBRD / 89800 redness and emergency ma Post Open - National 13,572.00 0.00 2023-05-15 2023-05-26 2023-06-12 2023-06-19 2023-06-23 2024-01-22 ure Specialist Individual Cons ant Selection ation nagement capacity ultant for Pusdatin PB ID-PMU BNPB-361729-CS-IN Component 1 Disaster prepa Individual Consult Under Implement DV / IT Governance Specialist IBRD / 89800 redness and emergency ma Post Open - National 6,478.00 0.00 2023-05-22 2023-05-26 2023-06-19 2023-06-26 2023-06-30 2023-09-29 ant Selection ation Individual Consultant nagement capacity ID-PMU BNPB-361730-CS-IN Component 1 Disaster prepa Individual Consult Under Implement DV / Software Engineer Speci IBRD / 89800 redness and emergency ma Post Open - National 6,748.00 0.00 2023-05-22 2023-05-26 2023-06-19 2023-06-26 2023-06-30 2023-09-29 ant Selection ation alist Individual Consultant nagement capacity ID-PMU BNPB-361731-CS-IN Component 1 Disaster prepa Individual Consult Under Implement DV / Data Science Specialist I IBRD / 89800 redness and emergency ma Post Open - National 6,748.00 0.00 2023-05-22 2023-05-26 2023-06-19 2023-06-26 2023-06-30 2023-09-29 ant Selection ation ndividual Consultant nagement capacity ID-PMU BNPB-361732-CS-IN Component 1 Disaster prepa DV / Disaster Risk Manageme Individual Consult Under Implement IBRD / 89800 redness and emergency ma Post Open - National 6,748.00 0.00 2023-05-22 2023-05-26 2023-06-19 2023-06-26 2023-06-30 2023-09-29 nt Specialist Individual Consu ant Selection ation nagement capacity ltant for Directorate of Early Warning Page 4 PROCUREMENT PLAN (Textual Part) 1. Project Information Country: Rwanda 2. Project Name: Access to Finance for Recovery and Resilience Project (AIFRR) 3. Project ID: P175273 4. Project Implementation Agency: Business Development Fund 5. Date of the Procurement Plan: July 27, 2021 6. Period Covered by this procurement plan: August 2021 – Feb 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Rwanda Public Procurement Law (Law No. 12 of 2007), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Other Relevant Procurement Information. None PROCUREMENT Rwanda : Access to Finance for Recovery and Resilience Project PLAN General Information Country: Rwanda 2021-07-29 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175273 GPN Date: Project Name: Access to Finance for Recovery and Resilience Project Loan / Credit No: IDA / 69260, TF / B5809, IDA / D8520 Development Bank of Rwanda Ltd Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-BRD-304676-GO-RFB / S Component 3 – Institutional Single Stage - One E upply of promotional materia IDA / D8520 Strengthening and Impleme Post Request for Bids Open - National 366,907.29 Signed 2022-07-29 2021-08-10 2022-08-03 2022-08-24 2021-08-24 2022-09-14 2021-09-17 2022-10-05 2021-12-03 2024-10-04 nvelope ls for AFIRR Project ntation Support NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-BRD-245563-CS-QCBS / Component 3 – Institutional Quality And Cost- Framework agreements for t IDA / 69260 Strengthening and Impleme Post Open - National 0.00 Canceled 2022-05-16 2022-06-06 2022-07-11 2022-08-08 2022-08-29 2022-10-03 2022-10-31 2025-10-30 Based Selection hree years - Training and cap ntation Support acity building RW-BRD-245639-CS-LCS / A Component 3 – Institutional Least Cost Selecti udit and other review costs f IDA / 69260 Strengthening and Impleme Post Open - National 0.00 Signed 2022-07-11 2022-08-23 2022-08-01 2022-09-05 2021-08-18 2022-10-03 2021-08-31 2022-10-24 2021-09-27 2022-11-28 2021-10-15 2022-12-26 2026-12-25 on or 5 years ntation Support RW-BRD-245483-CS-QCBS / Component 3 – Institutional Framework agreements for t Quality And Cost- Open - Internationa IDA / 69260 Strengthening and Impleme Post 0.00 Canceled 2022-03-14 2022-04-04 2022-05-09 2022-06-06 2022-06-27 2022-08-01 2022-08-29 2025-08-28 hree years - Developing, impl Based Selection l ntation Support ementing, and supervising tu rnaround strategies RW-BRD-245512-CS-QCBS / Component 3 – Institutional Quality And Cost- Open - Internationa Framework agreements for t IDA / 69260 Strengthening and Impleme Post 0.00 Canceled 2022-03-14 2022-04-04 2022-04-20 2022-05-18 2022-06-08 2022-07-13 2022-08-17 2025-08-16 Based Selection l hree years - Value chains ass ntation Support essments RW-BRD-245475-CS-QCBS / Component 3 – Institutional Framework agreements for 3 Quality And Cost- Open - Internationa IDA / 69260 Strengthening and Impleme Post 0.00 Canceled 2022-01-10 2022-01-31 2022-02-16 2022-03-16 2022-04-06 2022-05-11 2022-06-08 2025-06-07 years Consultancies environ Based Selection l ntation Support mental safeguards strengthe ning RW-BRD-245632-CS-QCBS / Framework agreement for th Component 3 – Institutional Quality And Cost- Open - Internationa ree years- Awareness campai IDA / 69260 Strengthening and Impleme Post 152,219.28 Signed 2022-10-03 2022-03-09 2022-10-24 2022-11-28 2021-09-21 2022-12-26 2021-09-27 2023-01-16 2021-10-05 2023-02-20 2021-11-08 2023-03-27 2021-11-25 2026-03-26 Based Selection l gns, client’s outreach and ot ntation Support her marketing activities RW-BRD-245496-CS-QCBS / Component 3 – Institutional Quality And Cost- Open - Internationa Under Implement Skills, funding gap assessme IDA / 69260 Strengthening and Impleme Post 0.00 2022-03-07 2022-08-26 2022-03-28 2022-10-04 2022-05-02 2022-05-30 2022-06-20 2022-07-25 2022-08-22 2025-08-21 Based Selection l ation nts. Training and capacity bu ntation Support ilding RW-BRD-354896-CS-LCS / Tr Component 3 – Institutional Least Cost Selecti Open - Internationa ansaction Advisor - Sustainab IDA / 69260 Strengthening and Impleme Post 0.00 Canceled 2023-04-11 2023-04-26 2023-05-25 2023-06-22 2023-07-07 2023-08-04 2023-09-01 2023-11-30 on l ility Linked Bond ntation Support RW-BRD-356619-CS-CQS / Tr Component 3 – Institutional Consultant Qualifi Under Implement ansaction advisor /Lead Man IDA / 69260 Strengthening and Impleme Post Open - National 0.00 2023-04-17 2023-04-14 2023-05-02 2023-04-17 2023-05-23 2023-05-09 2023-05-30 2023-05-25 2023-06-13 2023-10-11 cation Selection ation ager-Sustainable linked Bond ntation Support RW-BRD-245480-CS-QCBS / Component 3 – Institutional Set up of digital tools and oth Quality And Cost- Open - Internationa Pending Impleme IDA / 69260 Strengthening and Impleme Post 0.00 2023-12-05 2023-12-20 2024-01-24 2024-02-21 2024-03-13 2024-04-17 2024-05-15 2027-05-15 er IT related cost for financial Based Selection l ntation ntation Support management of the Fund-IBA NK system RW-BRD-245564-CS-QCBS / Framework agreements for 3 years Project structuring and Component 3 – Institutional documentation/Initial designs Quality And Cost- Open - Internationa Pending Impleme IDA / 69260 Strengthening and Impleme Post 0.00 2024-02-20 2024-03-12 2024-04-16 2024-05-14 2024-06-04 2024-07-09 2024-07-24 2027-07-24 of business structure, feasibil Based Selection l ntation ntation Support ity studies, strategic plans, s ource of funding, strengthen identified weak areas, gover nance structure RW-BRD-245471-CS-QCBS / Framework agreements for t Component 3 – Institutional Quality And Cost- Pending Impleme hree years Market research a IDA / 69260 Strengthening and Impleme Post Open - National 0.00 2024-02-20 2024-03-12 2024-04-16 2024-05-14 2024-06-04 2024-07-09 2024-08-13 2027-08-13 Based Selection ntation nd other capacity building to ntation Support support the revenue growth of BRD RW-BRD-245566-CS-QCBS / Framework agreements for t hree years- Training worksho Component 3 – Institutional ps on appraisal process - fina Quality And Cost- Open - Internationa Pending Impleme IDA / 69260 Strengthening and Impleme Post 0.00 2023-06-30 2023-07-21 2023-08-25 2023-09-22 2023-10-13 2023-11-17 2023-12-15 2026-12-14 ncial modeling - Credit risk m Based Selection l ntation ntation Support anagement - projects monito ring and evaluation system f or the project, sector and sub sector-based data warehouse development. Page 1 RW-BRD-245507-CS-QCBS / Component 3 – Institutional Framework agreements for t Quality And Cost- Open - Internationa Pending Impleme IDA / 69260 Strengthening and Impleme Post 0.00 2024-04-15 2024-05-06 2024-06-10 2024-07-08 2024-07-29 2024-09-02 2024-09-30 2027-09-30 hree years - Holistic compan Based Selection l ntation ntation Support y financial & operational revi ew RW-BRD-245647-CS-QCBS / Component 3 – Institutional Quality And Cost- Pending Impleme Development of M & E Syste IDA / 69260 Strengthening and Impleme Post Open - National 0.00 2024-03-19 2024-04-09 2024-05-14 2024-06-11 2024-07-02 2024-08-06 2024-09-10 2025-03-09 Based Selection ntation m ntation Support RW-BRD-245474-CS-QCBS / Component 3 – Institutional Quality And Cost- Pending Impleme Review of funding readiness IDA / 69260 Strengthening and Impleme Post Open - National 0.00 2024-06-04 2024-06-25 2024-07-30 2024-08-27 2024-09-17 2024-10-22 2024-11-19 2027-11-19 Based Selection ntation and advise on source of finan ntation Support cing RW-BRD-245644-CS-QCBS / Component 3 – Institutional Quality And Cost- Pending Impleme Set up of digital tools for ma IDA / 69260 Strengthening and Impleme Post Open - National 0.00 2024-05-15 2024-06-05 2024-07-10 2024-08-07 2024-08-28 2024-10-02 2024-11-06 2025-11-06 Based Selection ntation naging the Fund ntation Support RW-BRD-245646-CS-QCBS / Component 3 – Institutional Sector and sub-sector-based Quality And Cost- Pending Impleme IDA / 69260 Strengthening and Impleme Post Open - National 0.00 2024-07-10 2024-07-31 2024-09-04 2024-10-02 2024-10-23 2024-11-27 2025-01-01 2028-01-01 data warehouse developmen Based Selection ntation ntation Support t (for clients and product dev elopment) RW-BRD-245469-CS-QCBS / Framework agreements for 3 Component 3 – Institutional Quality And Cost- Pending Impleme years Project structuring and IDA / 69260 Strengthening and Impleme Post Open - National 0.00 2024-03-29 2024-04-19 2024-05-24 2024-06-21 2024-07-21 2024-08-18 2024-09-15 2027-09-15 Based Selection ntation documentation/Initial designs ntation Support of business structure RW-BRD-245490-CS-QCBS / Component 3 – Institutional Framework agreements for 3 Quality And Cost- Pending Impleme IDA / 69260 Strengthening and Impleme Post Open - National 0.00 2024-02-27 2024-03-19 2024-04-23 2024-05-21 2024-06-11 2024-07-16 2024-08-13 2027-08-13 years - Hiring external expert Based Selection ntation ntation Support ise to strengthen identified w eak areas RW-BRD-245510-CS-QCBS / Component 3 – Institutional Framework agreements for t Quality And Cost- Pending Impleme IDA / 69260 Strengthening and Impleme Post Open - National 0.00 2024-04-25 2024-05-16 2024-06-20 2024-07-18 2024-08-08 2024-09-12 2024-10-10 2027-10-10 hree years - Strengthening G Based Selection ntation ntation Support overnance structures RW-BRD-245473-CS-QCBS / Component 3 – Institutional Quality And Cost- Open - Internationa Pending Impleme Framework agreements for t IDA / 69260 Strengthening and Impleme Post 0.00 2024-08-14 2024-09-04 2024-10-09 2024-11-06 2024-11-27 2025-01-01 2025-01-29 2028-01-29 Based Selection l ntation hree years - Feasibility studie ntation Support s, strategic plans RW-BRD-245516-CS-QCBS / Framework agreements for t Component 3 – Institutional Quality And Cost- Pending Impleme hree years- Review of expans IDA / 69260 Strengthening and Impleme Post Open - National 0.00 2024-08-05 2024-08-26 2024-09-30 2024-10-28 2024-11-18 2024-12-23 2025-01-20 2028-01-20 Based Selection ntation ion readiness and advise on t ntation Support he appropriateness of timing RW-BRD-245645-CS-QCBS / Technical Assistance (includi Component 3 – Institutional ng board evaluation, board K Quality And Cost- Pending Impleme IDA / 69260 Strengthening and Impleme Post Open - National 0.00 2023-10-25 2023-11-15 2023-12-20 2024-01-17 2024-02-07 2024-03-13 2024-04-17 2027-04-17 PIs, board development polic Based Selection ntation ntation Support y, legal opinions for resource s mobilization and Policy revi ew) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3 – Institutional RW-BRD-245650-CS-INDV / Individual Consult IDA / 69260 Strengthening and Impleme Post Open 73,085.59 Signed 2021-07-30 2021-07-29 2021-09-08 2021-10-21 2021-09-29 2022-06-24 2021-10-27 2021-12-02 2023-04-26 Hiring a Project Coordinator ant Selection ntation Support Component 3 – Institutional RW-BRD-245596-CS-INDV / Individual Consult IDA / 69260 Strengthening and Impleme Post Open 41,426.53 Signed 2021-10-04 2021-07-29 2021-11-13 2022-01-12 2021-11-27 2022-01-12 2021-12-25 2022-01-18 2023-06-24 Hiring M&E Officer ant Selection ntation Support Component 3 – Institutional RW-BRD-245603-CS-INDV / Individual Consult Under Implement IDA / 69260 Strengthening and Impleme Post Open 0.00 2021-10-04 2022-05-12 2021-11-13 2021-11-27 2021-12-25 2023-06-24 Hiring a Product developer ant Selection ation ntation Support Component 3 – Institutional RW-BRD-245608-CS-INDV / Individual Consult IDA / 69260 Strengthening and Impleme Post Open 0.00 Signed 2021-10-04 2022-07-23 2021-11-13 2022-08-04 2021-11-27 2022-08-04 2021-12-25 2023-06-24 Credit Risk Officer - 1 ant Selection ntation Support Component 3 – Institutional RW-BRD-245611-CS-INDV / Individual Consult IDA / 69260 Strengthening and Impleme Post Open 33,559.77 Signed 2021-10-04 2022-06-06 2021-11-13 2022-01-27 2021-11-27 2022-01-27 2021-12-25 2022-01-29 2023-06-24 Credit Risk Officers - 2 ant Selection ntation Support Component 3 – Institutional RW-BRD-245614-CS-INDV / I Individual Consult IDA / 69260 Strengthening and Impleme Post Open 34,966.28 Signed 2021-08-02 2021-07-29 2021-09-11 2021-10-21 2021-09-25 2021-10-26 2021-10-23 2021-10-27 2023-04-22 nvestment officer - 1 ant Selection ntation Support Component 3 – Institutional RW-BRD-245617-CS-INDV / I Individual Consult IDA / 69260 Strengthening and Impleme Post Open 34,966.28 Signed 2021-08-02 2021-07-29 2021-09-11 2020-12-31 2021-09-25 2021-02-08 2021-10-23 2021-05-02 2023-04-22 nvestment officer -2 ant Selection ntation Support Component 3 – Institutional RW-BRD-245618-CS-INDV / P Individual Consult IDA / 69260 Strengthening and Impleme Post Open 0.00 Signed 2021-10-11 2022-02-02 2021-11-20 2022-10-26 2021-12-04 2022-10-26 2022-01-01 2023-06-30 roject Monitoring officer ant Selection ntation Support Component 3 – Institutional RW-BRD-245622-CS-INDV / L Individual Consult Pending Impleme IDA / 69260 Strengthening and Impleme Post Open 0.00 2021-10-04 2021-11-13 2021-11-27 2021-12-25 2023-06-24 egal Officer ant Selection ntation ntation Support Component 3 – Institutional RW-BRD-245627-CS-QCBS / Individual Consult IDA / 69260 Strengthening and Impleme Post Open 0.00 Signed 2022-02-07 2022-03-09 2022-03-19 2022-10-03 2022-04-02 2022-10-03 2022-04-30 2023-10-27 Business analyst ant Selection ntation Support Component 3 – Institutional RW-BRD-245630-CS-INDV / S Individual Consult Under Implement IDA / 69260 Strengthening and Impleme Post Open 0.00 2021-10-25 2022-03-17 2021-12-13 2022-01-03 2022-02-07 2023-08-06 enior Financial advisor ant Selection ation ntation Support Component 3 – Institutional RW-BRD-245634-CS-INDV / Individual Consult Under Implement IDA / 69260 Strengthening and Impleme Post Open 0.00 2021-10-11 2022-05-13 2021-11-20 2022-10-03 2021-12-04 2022-10-03 2022-01-08 2023-07-07 Business support analysts ant Selection ation ntation Support Page 2 RW-BRD-245637-CS-INDV / S Component 3 – Institutional takeholder Engagement (SE)/ Individual Consult Under Implement IDA / 69260 Strengthening and Impleme Post Open 0.00 2021-10-11 2022-02-02 2021-11-29 2021-12-20 2022-01-24 2023-07-23 Grievance Redress Mechanis ant Selection ation ntation Support m (GRM) focal point RW-BRD-245625-CS-INDV / E Component 3 – Institutional Individual Consult mbedded advisor for advisor IDA / 69260 Strengthening and Impleme Post Open 0.00 Canceled 2021-10-25 2022-01-12 2021-12-13 2021-12-27 2022-01-24 2024-01-24 ant Selection y unit for 2 years ntation Support Component 3 – Institutional RW-BRD-281913-CS-INDV / P Individual Consult IDA / 69260 Strengthening and Impleme Post Open 0.00 Signed 2022-03-02 2022-03-02 2022-04-11 2022-08-14 2022-04-25 2022-08-22 2022-05-23 2022-08-04 roject Monitoring Officer - 2 ant Selection ntation Support Component 3 – Institutional RW-BRD-288711-CS-INDV / T Individual Consult TF / B5809 Strengthening and Impleme Post Open 0.00 Signed 2022-04-11 2022-04-11 2022-05-21 2022-09-06 2022-05-22 2022-09-08 2022-06-05 2023-06-05 rade Finance Officer ant Selection ntation Support Component 3 – Institutional RW-BRD-295054-CS-CDS / M IDA / 69260 Strengthening and Impleme Post Direct Selection Direct 0.00 Canceled 2022-05-18 2022-05-17 2022-05-28 2022-07-16 2023-07-16 arketing Officer ntation Support Component 3 – Institutional RW-BRD-307792-CS-INDV / Individual Consult IDA / 69260 Strengthening and Impleme Post Open - National 0.00 Signed 2022-08-04 2022-08-05 2022-09-13 2022-10-26 2022-09-27 2022-10-26 2022-10-25 2024-10-24 AFFIR Marketing Officer ant Selection ntation Support RW-BRD-311336-CS-INDV / Component 3 – Institutional Individual Consult Under Implement Hiring Embedded Advisor - A IDA / D8520 Strengthening and Impleme Post Limited 0.00 2022-08-23 2022-08-23 2022-08-28 2022-09-18 2022-10-23 2024-10-22 ant Selection ation dvisory Services ntation Support RW-BRD-360916-CS-INDV / E Component 3 – Institutional Individual Consult Under Implement nvironmental and Social Safe TF / B5809 Strengthening and Impleme Post Limited 0.00 2023-05-23 2023-05-25 2023-05-30 2023-06-13 2023-07-04 2026-07-03 ant Selection ation guards consultant -1 ntation Support RW-BRD-360922-CS-INDV / E Component 3 – Institutional Individual Consult Under Implement nvironmental and Social Safe TF / B5809 Strengthening and Impleme Post Limited 0.00 2023-05-23 2023-05-25 2023-05-28 2023-06-11 2023-07-02 2026-07-01 ant Selection ation guard Consultant-2 ntation Support Page 3 PROCUREMENT PLAN (Textual Part) Project information: Democratic Republic Democratic of Congo – Regional Disease Surveillance Systems Enhancement - P167817 Project Implementation agency: UGP PDSS Date of the Procurement Plan: June 2019 Period covered by this Procurement Plan: June 2019 – December 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 and revised November 2017) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Borrower’s Public Procurement Law No 10/010 of April 27, 2010 (PPL) and the Manual of Procedures of the PPL as per Borrower’s Decree No 10/22 of June 2, 2010, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (a) Standard Bidding Documents: All standard bidding documents to be used for the Project under NCB shall be found acceptable to the World Bank before their use during the implementation of Project; (b) Eligibility: Eligibility of bidders and acceptability of their goods and services shall not be based on their nationality and/or their origin; and association with a national firm shall not be a condition for participation in a bidding process. Therefore, except for the ineligibility situations referred to in paragraphs 1.10(a) (i) and 1.10(a) (ii) of the Procurement Guidelines, the eligibility of bidders must be based solely on their qualification, experience and capacity to carry out the contract related to the specific bidding process; (c) Advertising and Bid Preparation Time: Bidding opportunities shall be advertised at least in a national newspaper of wide circulation and on the website of the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) and bidders should be given at least 30 days from the date of invitation to bid or the date of availability of the bidding documents, whichever is later; (d) Criteria for Qualification of Bidders: Qualification criteria shall only concern the bidder’s capability and resources to perform the contract taking into account objective and measurable factors. Such criteria for qualification of bidders shall be clearly specified in the bidding documents; (e) Bid Evaluation and Contract Award: A contract shall be awarded to the substantially responsive and lowest evaluated bidder provided that such bidder meets the qualification criteria specified in the bidding documents. No scoring system shall be allowed for the evaluation of bids, and no “blanket” limitation to the number of lots which can be awarded to a bidder shall apply. The criteria for bid evaluation and the contract award conditions shall be clearly specified in the bidding documents; (f) Preferences: No preference shall be given to domestic/regional bidders; to domestically/regionally manufactured goods; and to bidders forming a joint venture with a national firm or proposing national sub-contractors or carrying out economic activities in the territory of the Recipient; (g) Publication of Contract Award: Information on all contract awards shall be published in at least a national newspaper of wide circulation or in the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) web-site; (h) Fraud and Corruption: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy to sanction firms or individuals found to have engaged in fraud and corruption as set forth in the Procurement Guidelines; (i) Inspection and Audit Rights: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy with respect to inspection and audit of accounts, records and other documents relating to the bid submission and contract performance; (j) Requirement for administrative documents and/or tax clearance certificate: The bidding documents shall not require foreign bidders to produce any administrative or tax related certificates prior to confirmation of awarding a contract; and (k) Modifications of a Signed Contract: Any change in the contract amount which, singly or combined with all previous changes, increases the original contract amount by fifteen (15) percent or more must be done through an amendment to the signed contract instead of signing a new contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Central Africa : Regional Disease Surveillance Systems Enhancement Project (REDISSE) Phase IV PLAN General Information Country: Central Africa 2019-06-10 Bank’s Approval Date of the Original Procurement Plan: Revised Plan Date(s): (comma delineated, leave blank 2023-05-25 if none) Project ID: P167817 GPN Date: 2020-05-18 Project Name: Regional Disease Surveillance Systems Enhancement Project (REDISSE) Phase IV Loan / Credit No: / , IDA / D5160, IDA / 64980, IDA / 64990, IBRD / 90040 RDC-MINISTERE DE LA SANTE PUBLIQUE Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual A Bid Evaluation Report Loan / Credit N Market Approac Procurement Pr Prequalification High SEA/SH Process S Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission Contract Comple Description Component Review Type Method Document Typ Amount (U mount (U and Recommendatio Signed Contract o. h ocess (Y/N) Risk tatus n Documents ation Report ent / Justification Notice / Invitation s Issued / Opening / Minutes tion e S$) S$) n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ZR-DRC-MSP-117854-CW-RF Component 1: Strengthenin Single Stage - One 8,500,000.0 2020-05-3 B / Construction de laboratoir / g Surveillance and Laborato Prior Request for Bids Open - National 0.00 Canceled 2019-08-12 2019-08-17 2019-09-28 2019-10-28 2019-12-02 Envelope 0 0 es de référence ry Capacity to Rapidly detec t Outbreaks ZR-DRC-MSP-117857-CW-RF Component 1: Strengthenin Single Stage - One 7,000,000.0 2020-06-0 B / Réhabilitation de laborato / g Surveillance and Laborato Prior Request for Bids Open - National 0.00 Canceled 2019-08-19 2019-08-24 2019-10-05 2019-11-04 2019-12-09 Envelope 0 6 ires dans la zone d'interventi ry Capacity to Rapidly detec on du projet t Outbreaks ZR-DRC-MSP-117888-CW-RF Q / Réhabilitation des locaux Component 3: Public Health Request for Quota Single Stage - One 2020-04-3 / Post Limited 500,000.00 0.00 Canceled 2019-09-07 2019-11-02 pour abriter les centres médi Workforce Development tions Envelope 0 caux (Postes d'inspection Fro ntalières (PIF) ZR-DRC-MSP-184473-CW-RF Component 1: Strengthenin Q / Réhabiliter 18 locaux pou g Surveillance and Laborato Request for Quota Single Stage - One 2021-04-3 IDA / 64980 Post Limited 30,000.00 0.00 Canceled 2020-09-06 2020-11-01 r les soins des animaux et la ry Capacity to Rapidly detec tions Envelope 0 quarantaine animale t Outbreaks ZR-DRC-MSP-184479-CW-RF Component 1: Strengthenin Request for Quota Single Stage - One 2021-09-2 Q / Réhabiliter le Bureau Nati IDA / D5160 g Surveillance and Laborato Post Limited 39,900.00 0.00 Canceled 2021-01-28 2021-03-25 tions Envelope 1 onal du PNCPS ry Capacity to Rapidly detec t Outbreaks ZR-DRC-MSP-117872-CW-RF Component 1: Strengthenin B / Construction et équipeme g Surveillance and Laborato Single Stage - One 2,000,000.0 2020-06-0 / Post Request for Bids Open - National 0.00 Canceled 2019-08-21 2019-08-26 2019-10-07 2019-11-06 2019-12-11 nt d'un laboratoire national d ry Capacity to Rapidly detec Envelope 0 8 e diagnostic vétérinaire de ni t Outbreaks veau 1 ZR-DRC-MSP-200124-CW-RF Component 1: Strengthenin Q / Réhabilitation deux (2) cli g Surveillance and Laborato Request for Quota Single Stage - One 2021-09-0 IDA / 64980 Post Limited 250,000.00 0.00 Canceled 2021-01-10 2021-03-07 niques des plantes à : Kinsha ry Capacity to Rapidly detec tions Envelope 3 sa et Lubumbashi. t Outbreaks ZR-DRC-MSP-200136-CW-RF Component 2: Strengthenin Q / Réhabilitation du Bureau g Emergency Planning and Request for Quota Single Stage - One 2021-09-2 National du Programme Nati IDA / D5160 Post Limited 50,000.00 0.00 Canceled 2021-01-27 2021-03-24 Management Capacity to Ra tions Envelope 0 onal de Communication et Pr pidly respond to Outbreaks omotion de la Santé (PNCPS) à Kinshasa ZR-DRC-MSP-200137-CW-RF Component 4: Institutional C Single Stage - One 1,000,000.0 2021-11-1 B / Réhabilitation des Bureau IDA / 64980 apacity Building, Project Ma Post Request for Bids Open - National 0.00 Canceled 2021-01-25 2021-01-30 2021-03-13 2021-04-12 2021-05-17 Envelope 0 3 x du Projet REDISSE nagement, Coordination and Advocacy ZR-DRC-MSP-200143-CW-RF Q / Construction des nouvea Component 4: Institutional C ux locaux (Bureaux et salles apacity Building, Project Ma Request for Quota Single Stage - One 2021-09-2 IDA / 64980 Post Limited 105,000.00 0.00 Canceled 2021-01-30 2021-03-27 des réunions) pour le Point F nagement, Coordination and tions Envelope 3 ocal Règlement Sanitaire Int Advocacy ernational (RSI) du PNHF à Ki nshasa. National Procure ZR-DRC-MSP-238522-CW-RF Component 1: Strengthenin ment Document - Pending Im Request for Quota Single Stage - One 2,500,000.0 2022-03-2 Q / Travaux de réhabilitation IDA / 64980 g Surveillance and Laborato Post Open - National 1 Envelope proce 0.00 plementatio 2021-07-28 2021-09-22 tions Envelope 0 1 du laboratoire provincial de ry Capacity to Rapidly detec ss (Non Bank-SPD n Bunia t Outbreaks ) ZR-DRC-MSP-272385-CW-RF Component 4: Institutional C Request for Bids - Pending Im B / Travaux de réhabilitation apacity Building, Project Ma Single Stage - One Small Works SPD 2023-04-1 IDA / 64980 Post Request for Bids Open - National 700,000.00 0.00 plementatio 2022-06-27 2022-07-02 2022-08-13 2022-09-12 2022-10-17 des bureaux du PFN, RSI, SE nagement, Coordination and Envelope (1 envelope proc 5 n NES, PNCPS à Kinshasa Advocacy ess) ZR-DRC-MSP-273778-CW-RF Component 1: Strengthenin Request for Bids - B / Travaux de Réhabilitation Pending Im g Surveillance and Laborato Single Stage - One Small Works SPD 2023-01-0 d’un (1) laboratoire national IDA / 64980 Post Request for Bids Open - National 900,000.00 0.00 plementatio 2022-03-23 2022-03-28 2022-05-09 2022-06-08 2022-07-13 ry Capacity to Rapidly detec Envelope (1 envelope proc 9 de diagnostic vétérinaire: un n t Outbreaks ess) (1) à Kinshasa ; un (1) à Lub umbashi et un (1) à Goma ZR-DRC-MSP-273794-CW-RF Component 2: Strengthenin Q / Travaux de désamiantag Pending Im g Emergency Planning and Request for Quota Single Stage - One Other (with field f 2022-06-1 e dans le cadre de la réhabili IDA / 64980 Post Limited 300,000.00 0.00 plementatio 2022-02-19 2022-04-16 Management Capacity to Ra tions Envelope or explanation) 5 tation du dépôt du Ministère n pidly respond to Outbreaks de la Santé à Kinshasa ZR-DRC-MSP-200130-CW-RF B / Construction/ Réhabilitati Component 1: Strengthenin on d’un (1) laboratoire natio g Surveillance and Laborato Single Stage - One 3,000,000.0 2022-04-3 nal de diagnostic vétérinaire IDA / D5160 Post Request for Bids Open - National 0.00 Canceled 2021-07-12 2021-07-17 2021-08-28 2021-09-27 2021-11-01 ry Capacity to Rapidly detec Envelope 0 0 de niveau 1 à Kinshasa ; de t t Outbreaks rois (3) laboratoires vétérinai res à Lubumbashi, Goma, et Bunia ZR-DRC-MSP-200133-CW-RF B / Réhabilitation des locaux pour abriter les centres médi Component 1: Strengthenin caux des Postes d’inspection g Surveillance and Laborato Single Stage - One 2022-05-0 Frontalières (PIF), des centre IDA / 64980 Post Request for Bids Open - National 900,000.00 0.00 Canceled 2021-07-19 2021-07-24 2021-09-04 2021-10-04 2021-11-08 ry Capacity to Rapidly detec Envelope 7 s des soins des animaux et d t Outbreaks e la quarantaine animale à : Kamako, Kipushi, la petite ba rrière (Goma), Ruzizi 1 et 2 ( Bukavu), Kavivira, Mahagi ZR-DRC-MSP-184475-CW-RF Component 1: Strengthenin B / Réhabilitation des laborat g Surveillance and Laborato Single Stage - One 9,000,000.0 2021-12-0 IDA / 64980 Post Request for Bids Open - National 0.00 Canceled 2021-02-19 2021-02-24 2021-04-07 2021-05-07 2021-06-11 oires provinciaux humains et ry Capacity to Rapidly detec Envelope 0 8 des cliniques de plantes t Outbreaks ZR-DRC-MSP-200120-CW-RF Q / Construction / Réhabilitat ion dans les sites sentinelles Component 1: Strengthenin des services de santé animal g Surveillance and Laborato Request for Quota Single Stage - One 2021-11-2 e afin d'assurer une meilleur IDA / 64980 Post Limited 420,000.00 0.00 Canceled 2021-04-07 2021-06-02 ry Capacity to Rapidly detec tions Envelope 9 e couverture sanitaire des m t Outbreaks aladies zoonotiques dans qu atorze (14) sites sentinelles : Bikoro, Gemena, Buta, Monk oto, Idiofa, Popokabaka, Mwe ZR-DRC-MSP-184472-CW-RF Component 1: Strengthenin Q / Réhabiliter 15 locaux dev g Surveillance and Laborato Request for Quota Single Stage - One 2021-04-2 IDA / 64980 Post Limited 110,000.00 0.00 Canceled 2020-09-01 2020-10-27 ant abriter les centres médic ry Capacity to Rapidly detec tions Envelope 5 aux aux 15 PoE désignés t Outbreaks ZR-DRC-MSP-184494-CW-RF Q / Construction dans les site s sentilles 50 bureaux des se Component 1: Strengthenin rvices de santé animale afin g Surveillance and Laborato Request for Quota Single Stage - One 2021-05-0 d'assurer une meilleure coou IDA / D5160 Post Limited 120,000.00 0.00 Canceled 2020-09-13 2020-11-08 ry Capacity to Rapidly detec tions Envelope 7 verture sanitaire des maladie t Outbreaks s zoonotiques Fourniture des mobiliers de b ureau en faveur des Coordin ations Locales du PNMLS Kik wit et Tshikapa) ZR-DRC-MSP-232788-CW-RF National Procure Component 1: Strengthenin Q / Sélection et Recrutement ment Document - g Surveillance and Laborato Request for Quota Single Stage - One 2022-01-2 d'un consultant Firme chargé IDA / 64980 Post Open - National 1 Envelope proce 300,000.00 0.00 Canceled 2021-05-31 2021-07-26 ry Capacity to Rapidly detec tions Envelope 2 de la réhabilitation du dépôt ss (Non Bank-SPD t Outbreaks du Ministère de la Santé à Ki ) nshasa ZR-DRC-MSP-209278-CW-RF Component 1: Strengthenin Q / Réhabilitation d'un bâtim g Surveillance and Laborato Request for Quota Single Stage - One 2021-08-3 ent devant abriter les équipe IDA / 64980 Post Limited 100,000.00 0.00 Canceled 2021-01-06 2021-03-03 ry Capacity to Rapidly detec tions Envelope 0 ments du laboratoire nationa t Outbreaks l de contrôle qualité des méd icaments LNCQ LAPHAKI. Page 1 ZR-DRC-MSP-184496-CW-RF Component 1: Strengthenin Request for Quota Single Stage - One 2021-10-0 Q / Construction d'un bâtime IDA / 64980 g Surveillance and Laborato Post Limited 200,000.00 0.00 Canceled 2021-02-15 2021-04-12 tions Envelope 9 nt abritant le siège de CDC ry Capacity to Rapidly detec t Outbreaks ZR-DRC-MSP-184495-CW-RF Q / Réhabiliter 80 bureaux d Component 1: Strengthenin es services de santé animale g Surveillance and Laborato Request for Quota Single Stage - One 2021-05-0 IDA / 64980 Post Limited 150,000.00 0.00 Canceled 2020-09-09 2020-11-04 dans les sites sentilles afin d' ry Capacity to Rapidly detec tions Envelope 3 assurer une meilleure coouv t Outbreaks erture sanitaire des maladies zoonotiques ZR-DRC-MSP-200137-CW-RF Component 1: Strengthenin B-2 / Réhabiliter 2 modules d g Surveillance and Laborato Single Stage - One Other (with field f 1,600,000.0 Under Impl 2023-07-2 u Laboratoire National de Co IDA / D5160 Post Request for Bids Open - National 0.00 2023-01-16 2023-01-23 2023-01-17 2023-06-08 2023-02-06 2023-02-21 2023-03-24 ry Capacity to Rapidly detec Envelope or explanation) 0 ementation 2 ntrôle Qualité (LNCQ/ LAPHA t Outbreaks KI) (Microbiologie et Dispositi fs médicaux à Kinshasa). ZR-DRC-MSP-335508-CW-RF Component 4: Institutional C B / Réhabilitation / Constructi apacity Building, Project Ma Single Stage - One Other (with field f 1,000,000.0 Under Impl 2024-03-2 IDA / D5160 Post Request for Bids Open - National 0.00 2023-01-16 2023-01-24 2023-01-17 2023-01-28 2023-03-03 2023-03-14 2023-03-18 2023-04-02 on des Bureaux Siège de l'U nagement, Coordination and Envelope or explanation) 0 ementation 7 G PDSS à Kinshasa. Advocacy ZR-DRC-MSP-339930-CW-DI R / Recrutement par ED de l a firme INOVIE AFRICA Médic Component 1: Strengthenin al Biology Laboratoires pour g Surveillance and Laborato Direct - Internation Other (with field f 2,400,000.0 Under Impl 2023-10-1 Réhabilitation, Aménagemen IDA / D5160 Post Direct Selection 0.00 2023-02-28 2023-02-07 2023-03-05 2023-02-20 2023-04-19 ry Capacity to Rapidly detec al or explanation) 0 ementation 6 t, Equipements Médicaux, dé t Outbreaks ploiement de Système techn ique du Personnel pour les 5 Laboratoires des HGR de la P rovince du Kwilu en RDC ZR-DRC-MSP-200125-CW-RF B / Construction / Réhabilitati on des laboratoires provincia Component 1: Strengthenin ux de santé humaine à : Kisa g Surveillance and Laborato Open - Internationa Single Stage - One 16,500,000. 2022-04-3 IDA / 64980 Prior Request for Bids 0.00 Canceled 2021-07-12 2021-07-17 2021-08-28 2021-09-27 2021-11-01 ngani, Kananga, Mbuji mayi, ry Capacity to Rapidly detec l Envelope 00 0 Bandundu ville et Mbandaka t Outbreaks ; et des laboratoires des hôpi taux provinciaux à : Kindu, B ukavu, Boende. ZR-DRC-MSP-358916-CW-RF B / Travaux Construction/Réa ménagement des Laboratoir Component 1: Strengthenin es de Santé Publique dans Ci g Surveillance and Laborato Open - Internationa Single Stage - One Other (with field f 25,000,000. Under Revi 2024-03-1 nq (05) Provinces: Kasai Cent IDA / D5160 Prior Request for Bids 0.00 2023-05-22 2023-05-27 2023-07-11 2023-08-10 2023-09-14 ry Capacity to Rapidly detec l Envelope or explanation) 00 ew 2 ral (ville de Kananga), Kasai t Outbreaks Oriental (ville de Mbujimayi), Tshopo (ville de Kisangani), Kwilu (ville de Bandundu), Eq uateur (ville de Mbandaka) ZR-DRC-MSP-358935-CW-RF B / Travaux Construction/Réa Component 1: Strengthenin Pending Im ménagement de deux (02) L g Surveillance and Laborato Open - Internationa Single Stage - One Other (with field f 6,000,000.0 2024-04-2 IDA / D5160 Post Request for Bids 0.00 plementatio 2023-07-03 2023-07-08 2023-08-22 2023-09-21 2023-10-26 aboratoires : 1 (un) Laboratoi ry Capacity to Rapidly detec l Envelope or explanation) 0 3 n re vétérinaire et 1 (un) Labor t Outbreaks atoire Environnemental dan s la ville province de Kinshas a. ZR-DRC-MSP-361359-CW-RF Component 2: Strengthenin B / Travaux de réhabilitation g Emergency Planning and Single Stage - One Other (with field f Under Impl 2024-01-0 IDA / D5160 Post Request for Bids Open - National 998,000.00 0.00 2023-05-22 2023-05-13 2023-05-27 2023-05-28 2023-06-11 2023-07-12 de l'entrepôt de l'Hôpital Gén Management Capacity to Ra Envelope or explanation) ementation 8 éral de Référence de Kinshas pidly respond to Outbreaks a ZR-DRC-MSP-361967-CW-RF Component 1: Strengthenin Request for Bids - B / Travaux de réhabilitation g Surveillance and Laborato Single Stage - One Works French Civi 2022-07-1 IDA / D5160 Post Request for Bids Open - National 998,000.00 0.00 Signed 2021-09-28 2021-09-28 2021-10-03 2021-11-14 2021-11-09 2021-12-14 2022-02-08 2022-01-18 de l'entrepôt de l'Hôpital Gén ry Capacity to Rapidly detec Envelope l Law (French) SP 7 éral de Référence de Kinshas t Outbreaks D a GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pr Prequalification Estimated Am Actual Amount Process St Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h ocess (Y/N) ount (US$) (US$) atus n Documents ation Report ent / Justification Notice / Invitation s Issued / Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-DRC-MSP-117864-GO-RF Component 1: Strengthenin Open - Internationa Single Stage - One B / Acquisition de réactifs et / g Surveillance and Laborato Prior Request for Bids 5,000,000.00 0.00 Canceled 2019-08-27 2019-09-01 2019-10-13 2019-11-12 2019-12-17 2020-06-14 l Envelope de consommables de laborat ry Capacity to Rapidly detec oire t Outbreaks ZR-DRC-MSP-117875-GO-RF Component 1: Strengthenin Open - Internationa Single Stage - One B / Acquisition de laboratoire / g Surveillance and Laborato Prior Request for Bids 1,500,000.00 0.00 Canceled 2019-08-12 2019-08-17 2019-09-28 2019-10-28 2019-12-02 2020-05-30 l Envelope s mobiles pour le compte du ry Capacity to Rapidly detec projet REDISSE t Outbreaks ZR-DRC-MSP-117878-GO-RF Component 4: Institutional C B / Acquisition de chaîne de f apacity Building, Project Ma Open - Internationa Single Stage - One roid (solaire) et matériels de / Prior Request for Bids 1,500,000.00 0.00 Canceled 2019-07-29 2019-08-03 2019-09-14 2019-10-14 2019-11-18 2020-05-16 nagement, Coordination and l Envelope prélèvement pour le renforce Advocacy ment des unités mobile de s anté animale ZR-DRC-MSP-184396-GO-RF Component 1: Strengthenin B / Fourniture d’équipement g Surveillance and Laborato Open - Internationa Single Stage - One IDA / D5160 Prior Request for Bids 6,000,000.00 0.00 Canceled 2021-12-17 2021-12-22 2022-02-02 2022-03-04 2022-04-08 2022-10-05 et matériels de laboratoire p ry Capacity to Rapidly detec l Envelope our la santé animale et hum t Outbreaks aine ZR-DRC-MSP-184407-GO-RF Component 1: Strengthenin Single Stage - One B / Acquisitions de laboratoir IDA / D5160 g Surveillance and Laborato Post Request for Bids Open - National 1,500,000.00 0.00 Canceled 2021-03-19 2021-03-24 2021-05-05 2021-06-04 2021-07-09 2022-01-05 Envelope es mobiles ry Capacity to Rapidly detec t Outbreaks ZR-DRC-MSP-184409-GO-RF Q / Acquisition d’équipement de transmission (postes radi Component 1: Strengthenin o émetteur /récepteur et ant g Surveillance and Laborato Request for Quota Single Stage - One IDA / D5160 Post Limited 500,000.00 0.00 Canceled 2021-10-03 2021-11-28 2022-05-27 ennes, Talkies Walkies), kits ry Capacity to Rapidly detec tions Envelope de production d’énergie solai t Outbreaks re, équipement intervention (dosimètre, débitmètre, expl osimètre) ZR-DRC-MSP-184412-GO-RF Component 1: Strengthenin Q / Acquisition des matériels g Surveillance and Laborato Request for Quota Single Stage - One IDA / D5160 Post Limited 500,000.00 0.00 Canceled 2021-10-03 2021-11-28 2022-05-27 de connexion internet en fav ry Capacity to Rapidly detec tions Envelope eur du Projet (V-SAT et conn t Outbreaks exes) ZR-DRC-MSP-184414-GO-RF Component 1: Strengthenin Q / Achat de moyens de com g Surveillance and Laborato Request for Quota Single Stage - One munication pour la surveillan IDA / D5160 Post Limited 350,000.00 0.00 Canceled 2021-10-03 2021-11-28 2022-05-27 ry Capacity to Rapidly detec tions Envelope ce au niveau central et provi t Outbreaks nciale (téléphone mobile et GPS) ZR-DRC-MSP-184417-GO-RF Component 1: Strengthenin Q / Acquisition d’équipement g Surveillance and Laborato Request for Quota Single Stage - One IDA / D5160 Post Limited 200,000.00 0.00 Canceled 2021-10-03 2021-11-28 2022-05-27 de communication (Visioconf ry Capacity to Rapidly detec tions Envelope érence) et interprétation t Outbreaks ZR-DRC-MSP-184421-GO-RF Component 1: Strengthenin Request for Quota Single Stage - One Q / Acquisition d'un serveur IDA / 64980 g Surveillance and Laborato Post Limited 15,000.00 0.00 Canceled 2020-08-04 2020-09-29 2021-03-28 tions Envelope pour le système de surveilla ry Capacity to Rapidly detec nce électronique t Outbreaks ZR-DRC-MSP-184436-GO-RF Component 1: Strengthenin Q / Acquisition en Kits inform g Surveillance and Laborato Request for Quota Single Stage - One IDA / D5160 Post Limited 225,000.00 0.00 Canceled 2020-09-02 2020-10-28 2021-04-26 atiques et bureautiques les l ry Capacity to Rapidly detec tions Envelope aboratoires intégrés au rése t Outbreaks au ZR-DRC-MSP-184440-GO-RF Component 1: Strengthenin B / Acquisition d'équipement g Surveillance and Laborato Open - Internationa Single Stage - One s des laboratoires intégrés d IDA / D5160 Prior Request for Bids 2,700,000.00 0.00 Canceled 2020-08-18 2020-08-23 2020-10-04 2020-11-03 2020-12-08 2021-06-06 ry Capacity to Rapidly detec l Envelope u réseau en kits et intrants s t Outbreaks pécifiques de prélèvement d es échantillons ZR-DRC-MSP-184443-GO-RF Component 1: Strengthenin Q / Acquisition d'équipement g Surveillance and Laborato Request for Quota Single Stage - One s des laboratoires intégrés d IDA / D5160 Post Limited 226,380.00 0.00 Canceled 2021-09-02 2021-10-28 2022-04-26 ry Capacity to Rapidly detec tions Envelope u réseau en matériels, kits et t Outbreaks intrants spécifiques de stock age des échantillons ZR-DRC-MSP-184453-GO-RF Q / Création d'un site Web p Component 1: Strengthenin our renforcer la communicati g Surveillance and Laborato Request for Quota Single Stage - One IDA / 64980 Post Limited 10,000.00 0.00 Canceled 2021-08-02 2021-09-27 2022-03-26 on institutionnelle (communi ry Capacity to Rapidly detec tions Envelope cation interne et communica t Outbreaks tion externe en créant un sit e Web) Page 2 ZR-DRC-MSP-184454-GO-RF Component 1: Strengthenin Q / Hébergement et gestion g Surveillance and Laborato Request for Quota Single Stage - One du Site WEB en Mettant à jo IDA / 64980 Post Limited 36,000.00 0.00 Canceled 2021-08-02 2021-09-27 2022-03-26 ry Capacity to Rapidly detec tions Envelope ur périoiquement les inform t Outbreaks ations du PANSS par domain e de RSI ZR-DRC-MSP-184461-GO-RF Component 1: Strengthenin Q / Reprographie du Plan Str g Surveillance and Laborato Request for Quota Single Stage - One IDA / 64980 Post Limited 20,000.00 0.00 Canceled 2020-09-02 2020-10-28 2021-04-26 atégique National Multisector ry Capacity to Rapidly detec tions Envelope iel de communication des ris t Outbreaks ques ZR-DRC-MSP-184465-GO-RF Component 1: Strengthenin B / Acquisition des véhicules g Surveillance and Laborato Single Stage - One IDA / D5160 Post Request for Bids Open - National 800,000.00 0.00 Canceled 2020-08-18 2020-10-13 2021-04-11 de 16 véhicules de type 4x4 ry Capacity to Rapidly detec Envelope pour le compte du projet au t Outbreaks niveau provincial ZR-DRC-MSP-184466-GO-RF Component 1: Strengthenin Request for Quota Single Stage - One Q / Fourniture de cinq (5) mo IDA / D5160 g Surveillance and Laborato Post Limited 32,500.00 0.00 Canceled 2020-08-24 2020-10-19 2021-04-17 tions Envelope tos de terrain pour le PF RSI ry Capacity to Rapidly detec t Outbreaks ZR-DRC-MSP-184467-GO-RF Component 1: Strengthenin Request for Quota Single Stage - One Pending Impl Q / Fourniture d'équipements IDA / 64980 g Surveillance and Laborato Post Limited 38,850.00 0.00 2020-08-15 2020-10-10 2021-04-08 tions Envelope ementation , mobiliers et matériels pour ry Capacity to Rapidly detec le PF RSI t Outbreaks ZR-DRC-MSP-118029-CS-IND Component 4: Institutional C V / Achat de moyens de com apacity Building, Project Ma Request for Quota Single Stage - One munication pour la surveillan / Post Limited 350,000.00 0.00 Canceled 2019-08-17 2019-10-12 2020-04-09 nagement, Coordination and tions Envelope ce au niveau central et provi Advocacy nciale (téléphone mobile et GPS) ZR-DRC-MSP-199481-GO-RF Component 1: Strengthenin Q / Fourniture de logiciel de s g Surveillance and Laborato Request for Quota Single Stage - One IDA / 64980 Post Limited 30,000.00 0.00 Canceled 2020-12-26 2021-02-20 2021-08-19 uivi des effets indésirables d ry Capacity to Rapidly detec tions Envelope es médicaments et intrants ( t Outbreaks pharmaco vigilance). ZR-DRC-MSP-199494-GO-RF B / Fourniture de téléphones cellulaires et crédits de com Component 1: Strengthenin munication pour les province g Surveillance and Laborato Single Stage - One Pending Impl s et les zones de santé cibles IDA / 64980 Prior Request for Bids Open - National 2,625,000.00 0.00 2021-01-05 2021-01-10 2021-02-21 2021-03-23 2021-04-27 2021-10-24 ry Capacity to Rapidly detec Envelope ementation , d’équipements de communi t Outbreaks cation (Visioconférence) et in terprétation pour les trois (3) secteurs au niveau central, d e moyens de communication ZR-DRC-MSP-209269-GO-RF Component 1: Strengthenin B / Fourniture de médicamen g Surveillance and Laborato Single Stage - One Pending Impl IDA / 64980 Post Request for Bids Open - National 1,800,000.00 0.00 2021-01-11 2021-01-16 2021-02-27 2021-03-29 2021-05-03 2021-10-30 ts génériques et vaccins dan ry Capacity to Rapidly detec Envelope ementation s la santé animale t Outbreaks ZR-DRC-MSP-209274-GO-RF Component 1: Strengthenin Single Stage - One B / Fourniture de réactifs et c IDA / 64980 g Surveillance and Laborato Prior Request for Bids Open - National 2,400,000.00 0.00 Canceled 2021-10-19 2021-10-24 2021-12-05 2022-01-04 2022-02-08 2022-08-07 Envelope onsommables de laboratoire. ry Capacity to Rapidly detec t Outbreaks ZR-DRC-MSP-199826-GO-RF Component 1: Strengthenin Q / Fourniture des tablettes p g Surveillance and Laborato Request for Quota Single Stage - One IDA / D5160 Post Limited 80,000.00 0.00 Canceled 2020-12-28 2021-02-22 2021-08-21 our les points d'entrée et les ry Capacity to Rapidly detec tions Envelope zones de santé cibles. t Outbreaks ZR-DRC-MSP-199846-GO-RF Component 1: Strengthenin B / Fourniture d’ambulances g Surveillance and Laborato Single Stage - One IDA / 64980 Post Request for Bids Open - National 1,080,000.00 0.00 Canceled 2020-12-23 2020-12-28 2021-02-08 2021-03-10 2021-04-14 2021-10-11 médicalisées au niveau des ry Capacity to Rapidly detec Envelope dix-huit (18) points d'entrée. t Outbreaks ZR-DRC-MSP-199851-GO-RF Component 1: Strengthenin Q / Fourniture d'un serveur c g Surveillance and Laborato Request for Quota Single Stage - One entral avec un système d'int IDA / D5160 Post Limited 200,000.00 0.00 Canceled 2020-12-28 2021-02-22 2021-08-21 ry Capacity to Rapidly detec tions Envelope er opérabilité et interconnect t Outbreaks ivité intra et intersectorielle ZR-DRC-MSP-117861-GO-RF Component 1: Strengthenin B / fourniture d'équipement g Surveillance and Laborato Open - Internationa Single Stage - One / Prior Request for Bids 6,000,000.00 0.00 Canceled 2019-08-20 2019-08-25 2019-10-06 2019-11-05 2019-12-10 2020-06-07 et matériels de laboratoire p ry Capacity to Rapidly detec l Envelope our la santé animale et hum t Outbreaks aine ZR-DRC-MSP-232300-GO-RF Component 1: Strengthenin Q / Fourniture de mobiliers, g Surveillance and Laborato Request for Quota Single Stage - One Pending Impl matériels informatiques et él IDA / 64980 Post Open - National 200,000.00 0.00 2021-06-06 2021-08-01 2022-01-28 ry Capacity to Rapidly detec tions Envelope ementation ectriques pour le dépôt du m t Outbreaks inistère de la santé réhabilité ZR-DRC-MSP-251700-GO-RF Component 4: Institutional C Request for Quota Single Stage - One Q / Acquisition des matériels IDA / D5160 apacity Building, Project Ma Post Limited 12,000.00 17,518.75 Signed 2021-10-04 2021-09-09 2021-11-29 2021-09-30 2022-05-28 tions Envelope informatique pour LAPHAKI nagement, Coordination and Advocacy ZR-DRC-MSP-256225-GO-RF Q / Acquisition en urgence d Component 1: Strengthenin es intrants et réactifs de labo g Surveillance and Laborato Request for Quota Single Stage - One ratoire en appui à la Directio IDA / 64980 Post Limited 69,933.00 0.00 Canceled 2021-10-25 2021-12-20 2022-06-18 ry Capacity to Rapidly detec tions Envelope n de Surveillance Epidémiolo t Outbreaks gique pour la riposte contre l 'épidémie de méningite à BA NALIA ZR-DRC-MSP-257127-GO-DI R / Contractualisation par ent Component 1: Strengthenin ente directe avec la firme PH g Surveillance and Laborato ATKIN, pour l'acquisition en u IDA / 64980 Post Direct Selection Direct 93,746.80 0.00 Canceled 2021-10-13 2021-10-07 2021-10-18 2021-10-07 2021-11-22 2022-05-21 ry Capacity to Rapidly detec rgence des médicaments et t Outbreaks consommables médicaux po ur la riposte contre l'épidémi e de méningite à BANALIA ZR-DRC-MSP-259420-GO-RF Q / Acquisition de 8 motos, d Component 2: Strengthenin ont 4 motos de type DT 125, g Emergency Planning and Request for Quota Single Stage - One et 4 motos de type AG 100, e IDA / 64980 Post Limited 45,000.00 42,900.00 Signed 2021-11-16 2021-10-26 2022-01-11 2021-11-20 2022-07-10 Management Capacity to Ra tions Envelope t 8 casques de protection; et pidly respond to Outbreaks de 2 moteurs Hors-bord, don t un de 25 CV et un autre de 40 CV, pour l'appui ZR-DRC-MSP-259009-GO-DI R / Contractualisation par ent ente directe avec RADIOCOM Component 1: Strengthenin pour l'acquisition de six (6) a g Surveillance and Laborato ppareils radiophoniques, (6) IDA / 64980 Post Direct Selection Direct 15,000.00 13,560.00 Signed 2021-11-10 2021-10-21 2021-11-15 2021-10-22 2021-12-20 2021-11-05 2022-06-18 ry Capacity to Rapidly detec batteries12 v/ 100 Ah, (6) Pa t Outbreaks nneau Solaire, et (6) Régulat eur pour l'appui à l'épidémie de méningite dans la ZS Ban alia, Province de la Tshopo Component 2: Strengthenin ZR-DRC-MSP-117868-GO-RF g Emergency Planning and Single Stage - One B / Acquisition d'ambulances IBRD / 90040 Prior Request for Bids Open - National 2,000,000.00 0.00 Canceled 2019-07-30 2019-08-04 2019-09-15 2019-10-15 2019-11-19 2020-05-17 Management Capacity to Ra Envelope médicalisées pidly respond to Outbreaks ZR-DRC-MSP-272396-GO-RF B / Fourniture et livraison de Component 1: Strengthenin s réactifs et intrants spécifiq g Surveillance and Laborato Single Stage - One Under Imple IDA / 64980 Post Request for Bids Open - National 450,000.00 0.00 2022-01-20 2022-06-02 2022-01-25 2022-03-08 2022-04-07 2022-05-12 2022-11-08 ues de détection des épidém ry Capacity to Rapidly detec Envelope mentation ies pour l'Institut National d t Outbreaks es Recherches Biologiques ( I NRB) ZR-DRC-MSP-272399-GO-RF Component 1: Strengthenin Request for Quota Single Stage - One Pending Impl Q / Acquisition des Fournitur IDA / 64980 g Surveillance and Laborato Post Limited 12,000.00 0.00 2022-02-05 2022-04-02 2022-05-02 tions Envelope ementation es de bureau et consommabl ry Capacity to Rapidly detec es informatiques t Outbreaks ZR-DRC-MSP-272400-GO-RF Q / Fourniture matériels de Component 2: Strengthenin manutention pour le dépôt d g Emergency Planning and Request for Quota Single Stage - One Pending Impl IDA / 64980 Post Limited 100,000.00 0.00 2022-04-06 2022-06-01 2022-07-01 u Ministère de la santé réhab Management Capacity to Ra tions Envelope ementation ilité / Hôpital général de réfé pidly respond to Outbreaks rence de Kinshasa ( HGR) :él évateur, diable, balance, etc ZR-DRC-MSP-272401-GO-RF Q / Fourniture et montage de Component 2: Strengthenin s mobiliers pour le dépôt du g Emergency Planning and Request for Quota Single Stage - One Pending Impl IDA / 64980 Post Limited 100,000.00 0.00 2022-04-06 2022-06-01 2022-07-01 Ministère de la Santé réhabili Management Capacity to Ra tions Envelope ementation té / Hôpital Général de Référ pidly respond to Outbreaks ence de Kinshasa (Maman Ye mo) Page 3 ZR-DRC-MSP-272405-GO-RF Q / Fourniture et montage de s mobiliers de bureau pour le Component 1: Strengthenin Service National d'épidémio- g Surveillance and Laborato Request for Quota Single Stage - One Pending Impl surveillance (SENES), le Point IDA / D5160 Post Limited 75,000.00 0.00 2022-02-06 2022-04-03 2022-05-03 ry Capacity to Rapidly detec tions Envelope ementation Focal National de Règlement t Outbreaks ation Sanitaire international et pour le Programme Natio nal de Communication pour l a Promotion de la Santé ZR-DRC-MSP-256226-GO-RF Component 1: Strengthenin Q / Acquisition en urgence d g Surveillance and Laborato Request for Quota Single Stage - One es médicaments et consomm IDA / 64980 Post Limited 93,746.80 0.00 Canceled 2021-10-25 2021-12-20 2022-06-18 ry Capacity to Rapidly detec tions Envelope ables médicaux pour la ripos t Outbreaks te contre l’épidémie de méni ngite à Banalia. ZR-DRC-MSP-273136-GO-RF Component 1: Strengthenin Q / Fourniture des matériels g Surveillance and Laborato Request for Quota Single Stage - One Pending Impl IDA / D5160 Post Limited 105,000.00 0.00 2022-04-30 2022-06-25 2022-07-25 pour le Système d'informatio ry Capacity to Rapidly detec tions Envelope ementation ns géographiques (SIG) , Em t Outbreaks a-I et Kobocollect ZR-DRC-MSP-273772-GO-RF Component 1: Strengthenin Q / Sélection d'un Transporte g Surveillance and Laborato Request for Quota Single Stage - One Pending Impl ur pour l'acheminement des IDA / D5160 Post Limited 100,000.00 0.00 2022-04-04 2022-05-30 2023-05-25 ry Capacity to Rapidly detec tions Envelope ementation bulletins épidémiologiques M t Outbreaks ensuels de surveillance des maladies. ZR-DRC-MSP-199902-GO-DI R / Fourniture d'une centaine (100) motos de terrain pour l Component 4: Institutional C e niveau central, provincial e apacity Building, Project Ma t opérationnel : Cinq (5) pour IDA / D5160 Post Direct Selection Direct 650,000.00 0.00 Canceled 2021-01-11 2021-01-16 2021-02-20 2021-08-19 nagement, Coordination and le Point Focal RSI, Sept (7) m Advocacy otos pour les provinces, seiz e (16) motos pour les laborat oires provinciaux, dix-huit (1 8) motos pour les poi ZR-DRC-MSP-273790-GO-RF Component 1: Strengthenin B / Fourniture de plus de ce g Surveillance and Laborato Single Stage - One Pending Impl nt quarante huit (148 ) moto IDA / 64980 Post Request for Bids Open - National 962,000.00 0.00 2022-04-04 2022-04-09 2022-05-21 2022-06-20 2022-07-25 2023-01-21 ry Capacity to Rapidly detec Envelope ementation s de terrain pour les laborato t Outbreaks ires provinciaux et pour les sites sentinelles ZR-DRC-MSP-117874-GO-RF Component 4: Institutional C Single Stage - One B / Acquisition de 32 véhicul / apacity Building, Project Ma Prior Request for Bids Open - National 1,600,000.00 0.00 Canceled 2019-07-24 2019-07-29 2019-09-09 2019-10-09 2019-11-13 2020-05-11 Envelope es de type 4x4 pour le compt nagement, Coordination and e du projet Advocacy ZR-DRC-MSP-257127-GO-DI R-2 / Contractualisation par e Component 1: Strengthenin ntente directe avec la firme g Surveillance and Laborato Under Imple IDA / 64980 Post Direct Selection Direct 424,000.00 0.00 2022-03-31 2022-02-18 2022-04-05 2022-02-22 2022-05-10 2022-07-09 PHATKIN, pour acquisition en ry Capacity to Rapidly detec mentation urgence des medicaments Es t Outbreaks sentiels aux zones de santé de la Province de l'Equateur ZR-DRC-MSP-291310-GO-RF Q / Acquisition des 3 motos DT + 6casques, 1 véhicule 4 Component 2: Strengthenin x4, tenues chirurgical et autr g Emergency Planning and Request for Quota Single Stage - One Pending Impl IDA / D5160 Post Limited 120,000.00 0.00 2022-04-23 2022-05-17 2022-05-31 es petits matériels medicaux Management Capacity to Ra tions Envelope ementation et non medicaux Assurer la pidly respond to Outbreaks mise la Campagne de vaccin ation contre la maladie à viru s Ébola dans la ville de Mban daka avec INRB ZR-DRC-MSP-291314-GO-RF Q / Acquisitions des Mobiliers de bureau, matériels inform Component 1: Strengthenin atiques, Consommables infor g Surveillance and Laborato Request for Quota Single Stage - One Pending Impl IDA / D5160 Post Limited 70,000.00 0.00 2022-04-24 2022-06-19 2022-07-19 matiques, et autres matériel ry Capacity to Rapidly detec tions Envelope ementation s pour les Directions du MSP t Outbreaks qui appuient REDISSE IV SENES, DGLM, DSE, INRB, PN HF, DSN et DLS ZR-DRC-MSP-294451-GO-RF Component 1: Strengthenin Q / Acquisition des Mobiliers g Surveillance and Laborato Request for Quota Single Stage - One Under Imple IDA / D5160 Post Limited 300,000.00 0.00 2022-05-21 2022-06-14 2022-06-28 (armoires, tables, chaises, et ry Capacity to Rapidly detec tions Envelope mentation c pour équiper le Laboratoire t Outbreaks de Bunia ZR-DRC-MSP-294457-GO-RF Component 1: Strengthenin Q / Acquisition des matériels g Surveillance and Laborato Request for Quota Single Stage - One Under Imple IDA / D5160 Post Limited 300,000.00 0.00 2022-05-21 2022-06-14 2022-06-28 et outils informatiques pour l ry Capacity to Rapidly detec tions Envelope mentation e fonctionnement de Laborat t Outbreaks oire de BUNIA ZR-DRC-MSP-294462-GO-RF Q / Fourniture des matériels Component 1: Strengthenin pour le QGIS EMA-I et KOBO g Surveillance and Laborato Request for Quota Single Stage - One Pending Impl COLECT pour la Surveillance IDA / D5160 Post Limited 120,000.00 0.00 2022-05-21 2022-06-14 2022-06-28 ry Capacity to Rapidly detec tions Envelope ementation et Renforcement des capacit t Outbreaks és de laboratoire pour détect er rapidement les épidémies (SENES) ZR-DRC-MSP-298180-GO-RF Component 1: Strengthenin B / Acquisitions des Équipem g Surveillance and Laborato Open - Internationa Single Stage - One Under Imple IDA / D5160 Prior Request for Bids 2,100,000.00 0.00 2022-06-13 2022-08-21 2022-06-18 2022-10-29 2022-07-02 2022-11-10 2022-07-09 2022-07-15 2022-09-13 ents et petits matériels pour ry Capacity to Rapidly detec l Envelope mentation le Laboratoire National de Bu t Outbreaks nia ZR-DRC-MSP-298181-GO-RF Component 1: Strengthenin B / . Acquisition des Réactifs g Surveillance and Laborato Open - Internationa Single Stage - One Under Imple IDA / D5160 Post Request for Bids 750,000.00 0.00 2022-06-13 2022-11-14 2022-06-18 2022-11-16 2022-07-02 2022-07-09 2022-07-15 2022-09-13 de laboratoire et divers Cons ry Capacity to Rapidly detec l Envelope mentation ommables de Laboratoire de t Outbreaks Bunia ZR-DRC-MSP-301448-GO-RF Component 2: Strengthenin B / Équiper deux (02) Modul g Emergency Planning and Open - Internationa Single Stage - One Pending Impl IDA / 64990 Prior Request for Bids 2,000,000.00 0.00 2022-07-18 2022-07-23 2022-09-06 2022-09-20 2022-10-21 2023-04-19 es (laboratoires de LAPHAKI Management Capacity to Ra l Envelope ementation à Réhabiliter pidly respond to Outbreaks ZR-DRC-MSP-311160-GO-RF Component 1: Strengthenin Q / Acquisition du Logiciel de g Surveillance and Laborato Request for Quota Single Stage - One Under Imple IDA / D5160 Post Limited 40,000.00 0.00 2022-09-26 2022-10-23 2022-10-26 Laboratoire d'Information Ma ry Capacity to Rapidly detec tions Envelope mentation nagement System (LIMS) t Outbreaks ZR-DRC-MSP-315473-GO-RF B / Acquisition des réactifs et Component 1: Strengthenin consommables médicaux po g Surveillance and Laborato Single Stage - One Pending Impl IDA / D5160 Post Request for Bids Open - National 900,000.00 0.00 2022-09-30 2022-10-30 2022-11-04 2022-11-18 2022-12-07 2023-04-06 ur les 02 laboratoires du Mini ry Capacity to Rapidly detec Envelope ementation stère de l’Environnement da t Outbreaks ns les provinces de Kinshasa et du Haut-Katanga ZR-DRC-MSP-315477-GO-RF B / Acquisition des réactifs et Component 1: Strengthenin consommables médicaux po g Surveillance and Laborato Open - Internationa Single Stage - One Pending Impl IDA / D5160 Prior Request for Bids 2,000,000.00 0.00 2022-09-30 2022-11-14 2022-11-19 2022-12-03 2022-12-22 2023-06-20 ur les 03 laboratoires vétérin ry Capacity to Rapidly detec l Envelope ementation aires des provinces du Nord- t Outbreaks Kivu, du Haut-Katanga et de Kinshasa ZR-DRC-MSP-315479-GO-RF B / Acquisition des équipeme Component 1: Strengthenin nts et matériels médicaux po g Surveillance and Laborato Open - Internationa Single Stage - One Pending Impl IDA / D5160 Prior Request for Bids 2,000,000.00 0.00 2022-09-30 2022-11-14 2022-11-19 2022-12-03 2022-12-22 2023-06-20 ur les 02 laboratoires du Mini ry Capacity to Rapidly detec l Envelope ementation stère de l’Environnement da t Outbreaks ns les provinces de Kinshasa et du Haut-Katanga ZR-DRC-MSP-273791-GO-RF Component 1: Strengthenin B / Fourniture de 10 véhicul g Surveillance and Laborato Single Stage - One es de type 4x4 dont 8 pour l IDA / 64980 Post Request for Bids Open - National 503,000.00 0.00 Canceled 2022-02-09 2022-02-14 2022-03-28 2022-04-27 2022-06-01 2022-09-29 ry Capacity to Rapidly detec Envelope es laboratoires provinciaux, t Outbreaks 1 pour l'UGP PDSS et 1 pour I NRB ZR-DRC-MSP-320771-GO-RF Component 1: Strengthenin B / Fourniture et Livraison de g Surveillance and Laborato Single Stage - One Pending Impl s véhicules de type 4x4 dont IDA / 64980 Post Request for Bids Open - National 503,000.00 0.00 2022-10-13 2022-10-15 2022-11-14 2022-11-20 2022-12-10 2023-06-08 ry Capacity to Rapidly detec Envelope ementation huit (8) pour les laboratoires t Outbreaks Provinciaux, 1 'un) pour l'UG P PDSS et 1 pour INRB ZR-DRC-MSP-295330-GO-RF Component 1: Strengthenin Q / Acquisition des Mobiliers, g Surveillance and Laborato Request for Quota Single Stage - One Under Imple matériels et outils informatiq IDA / D5160 Post Limited 220,000.00 0.00 2022-05-24 2022-06-25 2022-09-23 ry Capacity to Rapidly detec tions Envelope mentation ues et autres matériels pour t Outbreaks REDISSE IV / UG PDSS Page 4 ZR-DRC-MSP-318367-GO-RF Component 1: Strengthenin B / Fourniture et livraison de g Surveillance and Laborato Open - Internationa Single Stage - One s véhicules de type 4x4 pour IDA / D5160 Prior Request for Bids 2,200,000.00 0.00 Canceled 2022-10-05 2022-11-19 2022-11-20 2022-12-04 2023-01-15 2023-07-14 ry Capacity to Rapidly detec l Envelope les ambulances médicalisées t Outbreaks pour les 18 points d'entrées PoE ZR-DRC-MSP-324817-GO-RF Component 1: Strengthenin B / Acquisition des Véhicules g Surveillance and Laborato Open - Internationa Single Stage - One Under Imple de Type 4x4 pour les Ambula IDA / D5160 Prior Request for Bids 2,200,000.00 0.00 2022-11-16 2022-12-31 2023-01-01 2023-01-15 2023-02-26 2023-08-25 ry Capacity to Rapidly detec l Envelope mentation nces Médicalisées pour les 1 t Outbreaks 8 Points d'entées (PoE) ZR-DRC-MSP-117880-GO-RF Component 4: Institutional C Single Stage - One B / Acquisition de mobiliers e IBRD / 90040 apacity Building, Project Ma Post Request for Bids Open - National 1,200,000.00 0.00 Canceled 2019-07-25 2019-07-30 2019-09-10 2019-10-10 2019-11-14 2020-05-12 Envelope t équipement informatiques nagement, Coordination and Advocacy ZR-DRC-MSP-117871-GO-RF Component 1: Strengthenin B / fourniture de produits de g Surveillance and Laborato Single Stage - One / Prior Request for Bids Open - National 2,000,000.00 0.00 Canceled 2019-07-25 2019-07-30 2019-09-10 2019-10-10 2019-11-14 2020-05-12 base et consommables pour l ry Capacity to Rapidly detec Envelope e laboratoire de clinique vété t Outbreaks rinaire ZR-DRC-MSP-184434-GO-RF B / Acquisition d'équipement Component 1: Strengthenin s pour les laboratoires intégr g Surveillance and Laborato Single Stage - One IDA / D5160 Post Request for Bids Open - National 1,125,000.00 0.00 Canceled 2020-08-18 2020-08-23 2020-10-04 2020-11-03 2020-12-08 2021-06-06 és du réseau en matériels po ry Capacity to Rapidly detec Envelope ur la détection des maladies t Outbreaks prioritaires dans les secteurs humain et animal ZR-DRC-MSP-184403-GO-RF Component 1: Strengthenin Open - Internationa Single Stage - One B / Achat de réactifs et de co IDA / 64980 g Surveillance and Laborato Prior Request for Bids 5,000,000.00 0.00 Canceled 2021-12-17 2021-12-22 2022-02-02 2022-03-04 2022-04-08 2022-10-05 l Envelope nsommables de laboratoire ry Capacity to Rapidly detec t Outbreaks ZR-DRC-MSP-199501-GO-RF Component 1: Strengthenin Single Stage - One B / Fourniture d'intrants spéc IDA / 64980 g Surveillance and Laborato Post Request for Bids Open - National 1,800,000.00 0.00 Canceled 2021-01-19 2021-01-24 2021-03-07 2021-04-06 2021-05-11 2021-11-07 Envelope ifiques pour la détection des ry Capacity to Rapidly detec épidémies t Outbreaks ZR-DRC-MSP-272392-GO-RF Component 2: Strengthenin B / Fourniture d’ambulances g Emergency Planning and Open - Internationa Single Stage - One IDA / 64990 Prior Request for Bids 2,000,000.00 0.00 Canceled 2022-01-13 2022-02-03 2022-01-18 2022-03-01 2022-03-31 2022-05-05 2022-11-01 médicalisées de type 4x4 au Management Capacity to Ra l Envelope niveau des dix-huit (18) poin pidly respond to Outbreaks ts d'entrée. ZR-DRC-MSP-199841-GO-RF B / Fourniture en équipement s médicaux pour le diagnosti Component 1: Strengthenin c et la prise en charge (santé g Surveillance and Laborato Open - Internationa Single Stage - One publique et animale) pour les IDA / D5160 Prior Request for Bids 9,686,000.00 0.00 Canceled 2021-12-23 2021-12-28 2022-02-08 2022-03-10 2022-04-14 2022-10-11 ry Capacity to Rapidly detec l Envelope 18 PoE désignés, d’équipem t Outbreaks ents diversément spécifiques , de matériels divers pour les sites sentinelles (Minilab, Ce ntrifugeuse, Microscope,etc ZR-DRC-MSP-199497-GO-RF Component 1: Strengthenin B / Fourniture en matériels d' g Surveillance and Laborato Single Stage - One assainissement de base (pou IDA / D5160 Post Request for Bids Open - National 540,000.00 0.00 Canceled 2021-01-05 2021-01-10 2021-02-21 2021-03-23 2021-04-27 2021-10-24 ry Capacity to Rapidly detec Envelope belles, décharges, latrines, p t Outbreaks oints d'eau) pour les 18 PoE désignés. ZR-DRC-MSP-199901-GO-RF B / Fourniture d'un minibus e t de onze (11) véhicules de t Component 4: Institutional C ype 4x4 pour toutes les parti apacity Building, Project Ma Single Stage - One es prenantes au Projet au niv IDA / D5160 Post Request for Bids Open - National 610,000.00 0.00 Canceled 2021-01-15 2021-01-20 2021-03-03 2021-04-02 2021-05-07 2021-11-03 nagement, Coordination and Envelope eau central : PDSS (3), DGLM Advocacy (1), DLS (1), PNHF (1), PF RSI (1), MiniPE (1), MiniENV (1), L aboratoire vétérinaire central de Kinshasa (1), comi ZR-DRC-MSP-273785-GO-RF Component 1: Strengthenin B / Fourniture des équipeme g Surveillance and Laborato Single Stage - One IDA / 64980 Post Request for Bids Open - National 1,250,000.00 0.00 Canceled 2022-05-11 2022-05-16 2022-06-27 2022-07-27 2022-08-31 2023-02-27 nts pour les cinq (5) laborato ry Capacity to Rapidly detec Envelope ires pour les sites de LAPHA t Outbreaks KI réhabilité ZR-DRC-MSP-272394-GO-RF B / Fourniture et installations des équipements des laborat Component 2: Strengthenin oires pour le diagnostic biolo g Emergency Planning and Open - Internationa Single Stage - One IDA / 64990 Prior Request for Bids 5,000,000.00 0.00 Canceled 2022-07-15 2022-07-20 2022-08-31 2022-09-30 2022-11-04 2023-05-03 gique des maladies, y compri Management Capacity to Ra l Envelope s les maladies prioritaires po pidly respond to Outbreaks ur la prise en charge (santé publique et animale) pour les 9 laboratoires des Provinces ZR-DRC-MSP-273770-GO-RF Component 2: Strengthenin B / Fournitures des hors Bor g Emergency Planning and Single Stage - One d de 25 CV, Téléphones Mobi IDA / 64980 Post Request for Bids Open - National 372,500.00 0.00 Canceled 2022-04-11 2022-04-16 2022-05-28 2022-06-27 2022-08-01 2022-10-30 Management Capacity to Ra Envelope les Satellitaires pour les équi pidly respond to Outbreaks pes d'intervention rapides en moyens logistiques ZR-DRC-MSP-315466-GO-RF B / Acquisition des équipeme Component 1: Strengthenin nts et matériels médicaux po g Surveillance and Laborato Open - Internationa Single Stage - One IDA / D5160 Prior Request for Bids 4,500,000.00 0.00 Canceled 2022-10-03 2022-11-17 2022-12-01 2022-12-15 2023-01-05 2023-05-05 ur les 3 laboratoires vétérina ry Capacity to Rapidly detec l Envelope ires des provinces du Nord-Ki t Outbreaks vu, du Haut-Katanga et de Ki nshasa ZR-DRC-MSP-117877-GO-RF Component 4: Institutional C Single Stage - One B / Acquisition de matériels r / apacity Building, Project Ma Prior Request for Bids Open - National 1,500,000.00 0.00 Canceled 2019-07-30 2019-08-04 2019-09-15 2019-10-15 2019-11-19 2020-05-17 Envelope oulants divers ( vélos, canot nagement, Coordination and rapides, moto) Advocacy ZR-DRC-MSP-273135-GO-RF B / Acquisition d’équipement s de communication pour les Component 1: Strengthenin trois (3) secteurs pour la sur g Surveillance and Laborato Single Stage - One IDA / 64980 Post Request for Bids Open - National 500,000.00 0.00 Canceled 2022-04-18 2022-04-23 2022-06-04 2022-07-04 2022-08-08 2022-11-06 veillance ( postes radio émet ry Capacity to Rapidly detec Envelope teur/récepteur et antennes, t Outbreaks Talkies Walkies) kits de prod uction d'énergie solaire, équi pement intervention pour 18 PoE. ZR-DRC-MSP-272395-GO-RF B / Fourniture et installation Component 1: Strengthenin des équipements de laborato g Surveillance and Laborato Single Stage - One ire de Santé Publique de Bu IDA / 64980 Post Request for Bids Open - National 1,000,000.00 0.00 Canceled 2022-03-22 2022-03-27 2022-05-08 2022-06-07 2022-07-12 2023-01-08 ry Capacity to Rapidly detec Envelope nia pour le diagnostic biologi t Outbreaks que des maladies, y compris les maladies prioritaires pour la prise en charge. ZR-DRC-MSP-118023-GO-RF Component 4: Institutional C Q / Achat d'équipement (kits apacity Building, Project Ma Request for Quota Single Stage - One / Post Open - National 350,000.00 0.00 Canceled 2019-08-26 2019-10-21 2020-04-18 de protection individuelle) po nagement, Coordination and tions Envelope ur Biosécurité et bio sureté Advocacy ZR-DRC-MSP-184459-GO-RF Component 1: Strengthenin Q / Regrographie des directiv g Surveillance and Laborato Request for Quota Single Stage - One es et normes de fonctionnem IDA / 64980 Post Limited 57,600.00 0.00 Canceled 2021-07-15 2021-09-09 2022-03-08 ry Capacity to Rapidly detec tions Envelope ent du reseau de laboratoire t Outbreaks s et des textes légaux ZR-DRC-MSP-184418-GO-RF Q / Production et édition des Component 1: Strengthenin outils de gestion pour les cen g Surveillance and Laborato Request for Quota Single Stage - One IDA / D5160 Post Limited 100,000.00 0.00 Canceled 2021-10-03 2021-11-28 2022-05-27 tres de surveillance animale ry Capacity to Rapidly detec tions Envelope et environnementale en (regi t Outbreaks stres et notification, fiches d e notification) ZR-DRC-MSP-184419-GO-RF Component 1: Strengthenin Request for Quota Single Stage - One Q / Acquisition de logiciel de IDA / 64980 g Surveillance and Laborato Post Limited 30,000.00 0.00 Canceled 2021-09-16 2021-11-11 2022-05-10 tions Envelope suivi de gestion des médica ry Capacity to Rapidly detec ments et intrants t Outbreaks ZR-DRC-MSP-184463-GO-RF Component 1: Strengthenin Q / Production des bulletins é g Surveillance and Laborato Request for Quota Single Stage - One pidémiologiques mensuels d IDA / 64980 Post Limited 42,000.00 0.00 Canceled 2020-09-05 2020-10-31 2021-04-29 ry Capacity to Rapidly detec tions Envelope e surveillance des maladies ( t Outbreaks animales et humaines) ZR-DRC-MSP-184464-GO-RF Component 1: Strengthenin Q / Reproduction des support g Surveillance and Laborato Request for Quota Single Stage - One s existants de communicatio IDA / 64980 Post Limited 42,000.00 0.00 Canceled 2020-08-08 2020-10-03 2021-04-01 ry Capacity to Rapidly detec tions Envelope ns (la boite à images, les aut t Outbreaks ocollants, les affiches) sur le s relais additionnels Page 5 ZR-DRC-MSP-184462-GO-RF Component 1: Strengthenin Q / Reprographie des module g Surveillance and Laborato Request for Quota Single Stage - One IDA / 64980 Post Limited 10,000.00 0.00 Canceled 2020-11-03 2020-12-29 2021-06-27 s et guides de formation en c ry Capacity to Rapidly detec tions Envelope ommunication multisectoriel t Outbreaks s sur les risques ZR-DRC-MSP-199507-GO-RF Q / Fourniture de chaîne de f Component 1: Strengthenin roid (solaire) et matériel de p g Surveillance and Laborato Request for Quota Single Stage - One rélèvement pour le renforce IDA / D5160 Post Open - National 320,000.00 0.00 Canceled 2020-12-27 2021-02-14 2021-02-28 ry Capacity to Rapidly detec tions Envelope ment de quatorze (14) sites t Outbreaks sentinelles des services de s anté animale, et dix-huit (18) PoE de santé humaine. ZR-DRC-MSP-199855-GO-RF Component 2: Strengthenin Q / Fourniture de kits de pro g Emergency Planning and Request for Quota Single Stage - One duction d’énergie solaire, éq IDA / D5160 Post Limited 250,000.00 0.00 Canceled 2021-10-20 2021-12-15 2022-06-13 Management Capacity to Ra tions Envelope uipements intervention (dosi pidly respond to Outbreaks mètre, débitmètre, explosim ètre). ZR-DRC-MSP-117894-GO-RF Component 1: Strengthenin Q / Acquisition des matériels g Surveillance and Laborato Request for Quota Single Stage - One / Post Limited 500,000.00 0.00 Canceled 2019-08-11 2019-10-06 2020-04-03 de connexion internet en fav ry Capacity to Rapidly detec tions Envelope eur du Projet (V-SAT et conn t Outbreaks exes) ZR-DRC-MSP-184455-GO-RF Component 1: Strengthenin Request for Quota Single Stage - One Q / Connexion Internet aux la IDA / 64980 g Surveillance and Laborato Post Limited 100,800.00 0.00 Canceled 2020-08-15 2020-10-10 2021-04-08 tions Envelope boratoires intégrés du résea ry Capacity to Rapidly detec u multisectoriel t Outbreaks ZR-DRC-MSP-273082-GO-RF Component 2: Strengthenin Q / Fourniture de trois (3) hor g Emergency Planning and Request for Quota Single Stage - One s bords de 25CV et pirogues IDA / D5160 Post Limited 13,500.00 0.00 Canceled 2022-04-23 2022-06-18 2022-12-15 Management Capacity to Ra tions Envelope pour les sites sentinelles de s pidly respond to Outbreaks anté animale : Bikoro, Boend e, Mahagi ZR-DRC-MSP-318353-GO-RF Component 1: Strengthenin Q / Acquisition de deux (02) g Surveillance and Laborato Request for Quota Single Stage - One IDA / D5160 Post Limited 120,000.00 0.00 Canceled 2022-10-03 2022-11-03 2023-03-03 véhicule de type 4x4 pour la ry Capacity to Rapidly detec tions Envelope mobilité du personnel UG PD t Outbreaks SS ZR-DRC-MSP-184445-GO-RF Component 1: Strengthenin Q / Acquisition d'équipement g Surveillance and Laborato Request for Quota Single Stage - One s des laboratoires intégrés d IDA / D5160 Post Limited 270,000.00 0.00 Canceled 2021-09-02 2021-10-28 2022-04-26 ry Capacity to Rapidly detec tions Envelope u réseau en matériels/kits et t Outbreaks intrants spécifiques de trans port des échantillons ZR-DRC-MSP-184457-GO-RF Component 1: Strengthenin Request for Quota Single Stage - One Q / Acquisition de matériels r IDA / D5160 g Surveillance and Laborato Post Limited 582,400.00 0.00 Canceled 2021-07-15 2021-09-09 2022-03-08 tions Envelope oulants spécialisés pour le C ry Capacity to Rapidly detec DC t Outbreaks ZR-DRC-MSP-184413-GO-RF Component 1: Strengthenin Q / Achat d’équipement (kits g Surveillance and Laborato Request for Quota Single Stage - One IDA / D5160 Post Limited 350,000.00 0.00 Canceled 2021-10-03 2021-11-28 2022-05-27 de protection individuelle) po ry Capacity to Rapidly detec tions Envelope ur Biosécurité et bio sureté t Outbreaks ZR-DRC-MSP-199484-GO-RF Q / Reproduction des bulletin s épidémiologiques mensuel Component 1: Strengthenin s de surveillance des maladi g Surveillance and Laborato Request for Quota Single Stage - One es (animales et humaines), d IDA / D5160 Post Limited 84,000.00 0.00 Canceled 2021-01-16 2021-03-13 2021-09-09 ry Capacity to Rapidly detec tions Envelope es supports existants de com t Outbreaks munications (la boite à imag es, les autocollants, les affic hes) sur les relais additionnel s (secteur de l'enseignement , ZR-DRC-MSP-272398-GO-RF Component 1: Strengthenin Q / Fourniture et montage du g Surveillance and Laborato Request for Quota Single Stage - One matériel informatique pour le IDA / 64980 Post Limited 15,000.00 0.00 Canceled 2022-03-15 2022-05-10 2022-06-09 ry Capacity to Rapidly detec tions Envelope Point Focal National Règleme t Outbreaks ntaire International (PFNRSI) ZR-DRC-MSP-118032-GO-RF Component 4: Institutional C Q / Acquisition d'équipement apacity Building, Project Ma Request for Quota Single Stage - One / Post Open - National 200,000.00 0.00 Canceled 2019-09-15 2019-11-10 2020-05-08 de communication (Visioconf nagement, Coordination and tions Envelope érence) et interprétation Advocacy ZR-DRC-MSP-184451-GO-RF Component 1: Strengthenin Q / Acquisition de matériels e g Surveillance and Laborato Request for Quota Single Stage - One t équipements de travail pou IDA / 64980 Post Limited 115,000.00 0.00 Canceled 2020-10-04 2020-11-29 2021-05-28 ry Capacity to Rapidly detec tions Envelope r doter les bureaux de servic t Outbreaks es de santé animale ZR-DRC-MSP-184456-GO-RF Component 1: Strengthenin Q / Services de transport des g Surveillance and Laborato Request for Quota Single Stage - One IDA / 64980 Post Limited 504,000.00 0.00 Canceled 2021-07-19 2021-09-13 2022-03-12 échantillons des lieux de prél ry Capacity to Rapidly detec tions Envelope èvements aux lieux d'analys t Outbreaks es ZR-DRC-MSP-199900-GO-RF Q / Fourniture de mobiliers, Component 4: Institutional C matériels et biens pour le Bu apacity Building, Project Ma Request for Quota Single Stage - One reau de la coordination du Pr IDA / D5160 Post Limited 200,000.00 0.00 Canceled 2021-01-20 2021-03-17 2021-09-13 nagement, Coordination and tions Envelope ojet, les structures du minist Advocacy ère de la santé, du ministrèr e de pêche et élevage, et du ministère de l'environnemen t. ZR-DRC-MSP-199905-GO-RF Q / Fourniture des matériels Component 4: Institutional C de connexion internet en fav apacity Building, Project Ma Request for Quota Single Stage - One IDA / D5160 Post Limited 300,000.00 0.00 Canceled 2020-12-28 2021-02-22 2021-08-21 eur des structures bénéficiair nagement, Coordination and tions Envelope es du Projet (Acquisition de Advocacy matériel, maintenance, et pa iement de l'abonnement Inte rnet). ZR-DRC-MSP-199836-GO-RF Q / Production et édition des Component 1: Strengthenin outils de gestion pour les cen g Surveillance and Laborato Request for Quota Single Stage - One tres de surveillance animale IDA / D5160 Post Limited 100,000.00 0.00 Canceled 2021-02-02 2021-03-30 2021-09-26 ry Capacity to Rapidly detec tions Envelope et environnementale (registr t Outbreaks es de notification, fiches de n otification) dans les zones de s provinces cibles. ZR-DRC-MSP-199813-GO-RF Component 1: Strengthenin Q / Fourniture de kits et intra g Surveillance and Laborato Request for Quota Single Stage - One IDA / D5160 Post Limited 270,000.00 0.00 Canceled 2020-12-27 2021-02-21 2021-08-20 nts spécifiques de transport ry Capacity to Rapidly detec tions Envelope des échantillons. t Outbreaks ZR-DRC-MSP-117890-GO-RF Q / Acquisition d'équipement de transmission (postes radi o émetteur /récepteur et ant Component 3: Public Health Request for Quota Single Stage - One / Post Limited 500,000.00 0.00 Canceled 2019-09-14 2019-11-09 2020-05-07 ennes, Talkies Walkies), kits Workforce Development tions Envelope de production d'énergie solai re, équipement intervention (dosimètre, débitmètre, expl osimètre,) ZR-DRC-MSP-184427-GO-RF Component 1: Strengthenin Request for Quota Single Stage - One Q / Acquisition des tablettes IDA / D5160 g Surveillance and Laborato Post Limited 80,000.00 0.00 Canceled 2021-09-02 2021-10-28 2022-04-26 tions Envelope pour les points d'entrée ry Capacity to Rapidly detec t Outbreaks ZR-DRC-MSP-272397-GO-RF Component 1: Strengthenin Q / Fourniture et montage de g Surveillance and Laborato Request for Quota Single Stage - One s mobiliers de bureau pour le IDA / 64980 Post Limited 16,600.00 0.00 Canceled 2022-03-06 2022-05-01 2022-05-31 ry Capacity to Rapidly detec tions Envelope Point Focal National Règleme t Outbreaks ntaire Sanitaire International ( PFNRSI) ZR-DRC-MSP-184458-GO-RF Component 1: Strengthenin Q / Acquisition de matériel in g Surveillance and Laborato Request for Quota Single Stage - One IDA / D5160 Post Limited 92,710.00 0.00 Canceled 2021-07-15 2021-09-09 2022-03-08 formatique et de communica ry Capacity to Rapidly detec tions Envelope tion pour les ministères sect t Outbreaks oriels ZR-DRC-MSP-272402-GO-RF Component 1: Strengthenin Q / Fourniture de matériels in g Surveillance and Laborato Request for Quota Single Stage - One IDA / 64980 Post Limited 30,000.00 0.00 Canceled 2022-04-06 2022-06-01 2022-07-01 formatiques pour le dépôt du ry Capacity to Rapidly detec tions Envelope Ministère de la santé réhabili t Outbreaks té / Maman Yemo ZR-DRC-MSP-184428-GO-RF Component 1: Strengthenin Q / Acquisition en équipemen g Surveillance and Laborato Request for Quota Single Stage - One ts médicaux pour le diagnost IDA / 64980 Post Limited 486,000.00 0.00 Canceled 2021-09-02 2021-10-28 2022-04-26 ry Capacity to Rapidly detec tions Envelope ic et la prise en charge (Sant t Outbreaks é Publique et Animale) pour l es 18 PoE désignés Page 6 ZR-DRC-MSP-184433-GO-RF Component 1: Strengthenin Q / Acquisition d'équipement g Surveillance and Laborato Request for Quota Single Stage - One IDA / D5160 Post Limited 65,000.00 0.00 Canceled 2021-09-02 2021-10-28 2022-04-26 s en renforcement du laborat ry Capacity to Rapidly detec tions Envelope oire national de contrôle qual t Outbreaks ité LAPHAKI ZR-DRC-MSP-184447-GO-RF Component 1: Strengthenin Q / Acquisition en équipemen g Surveillance and Laborato Request for Quota Single Stage - One ts aux laboratoires intégrés a IDA / D5160 Post Limited 168,000.00 0.00 Canceled 2021-09-02 2021-10-28 2022-04-26 ry Capacity to Rapidly detec tions Envelope u reseau en kits de prélèvem t Outbreaks ent, stockage et transport d' échantillons ZR-DRC-MSP-200161-GO-RF Q / Fourniture de dix-neuf (1 9) hors bords de 25CV pour l Component 4: Institutional C es sites sentinelles de santé apacity Building, Project Ma Request for Quota Single Stage - One IDA / 64980 Post Limited 76,000.00 0.00 Canceled 2020-12-28 2021-02-22 2021-08-21 animale : Bikoro, Monkoto, M nagement, Coordination and tions Envelope angayi, Kalemie, Bunia, Tsha Advocacy ngalele et pour les équipes d 'intervention rapide dans les provinces de l'Equateur et de la Tshuapa. ZR-DRC-MSP-273134-GO-RF Component 1: Strengthenin Q / Fourniture des tablettes p g Surveillance and Laborato Request for Quota Single Stage - One IDA / D5160 Post Limited 80,000.00 0.00 Canceled 2022-04-09 2022-06-04 2022-07-04 our les points d'entrée et les ry Capacity to Rapidly detec tions Envelope zones de santé cibles. t Outbreaks ZR-DRC-MSP-184460-GO-RF Component 1: Strengthenin Q / Reprographie du docume g Surveillance and Laborato Request for Quota Single Stage - One IDA / 64980 Post Limited 20,000.00 0.00 Canceled 2020-10-05 2020-11-30 2021-05-29 nt projet de politique de com ry Capacity to Rapidly detec tions Envelope munication sur les risques t Outbreaks ZR-DRC-MSP-251729-GO-RF Component 1: Strengthenin Q / Acquisition des équipeme g Surveillance and Laborato Request for Quota Single Stage - One IDA / 64980 Post Limited 49,800.00 0.00 Canceled 2021-10-04 2021-11-03 2021-11-29 2022-05-28 nts du réseau intrant net au ry Capacity to Rapidly detec tions Envelope LNCQ et l'abonnement intern t Outbreaks et de LAPHAKI ZR-DRC-MSP-327552-GO-DI R / Contractualisation en Ent Component 4: Institutional C ente Directe avec la société apacity Building, Project Ma Under Imple ELITE NETWORKS pour l’Insta IDA / 64980 Post Direct Selection Direct - National 15,000.00 0.00 2022-11-21 2022-11-21 2022-11-26 2022-12-09 2023-06-07 nagement, Coordination and mentation llation du Réseau informatiq Advocacy ue local et extension Internet dans le nouveau local abrita nt le personnel UG PDSS ZR-DRC-MSP-315483-GO-DI Component 1: Strengthenin R / Contractualisation par ED g Surveillance and Laborato Direct - Internation IDA / 64980 Post Direct Selection 731,000.00 0.00 Canceled 2022-09-27 2022-09-08 2022-10-02 2022-09-22 2022-10-26 2022-12-25 avec la firme CEPHEID pour F ry Capacity to Rapidly detec al ourniture d'équipements et d t Outbreaks 'intrants GENEXEPRT ZR-DRC-MSP-330515-GO-RF Component 1: Strengthenin Q / Fourniture et livraison d'u g Surveillance and Laborato Request for Quota Single Stage - One Pending Impl IDA / D5160 Post Limited 60,000.00 0.00 2022-12-27 2023-01-20 2023-04-20 n incinérateur pour le Labora ry Capacity to Rapidly detec tions Envelope ementation toire Provincial de Bunia t Outbreaks ZR-DRC-MSP-327504-GO-DI Component 1: Strengthenin R / Contractualisation par Ent g Surveillance and Laborato ente Directe avec la Firme E IDA / 64980 Post Direct Selection Direct - National 762,350.00 0.00 Canceled 2022-12-27 2022-12-22 2023-01-01 2023-01-14 2023-03-15 ry Capacity to Rapidly detec SSOR EQUIPEMENTS pour Fo t Outbreaks urniture d'équipements et d'i ntrants GENEXPERT ZR-DRC-MSP-339859-GO-RF Component 1: Strengthenin Q / Acquisition des Equipeme g Surveillance and Laborato Request for Quota Single Stage - One Pending Impl IDA / D5160 Post Limited 300,000.00 0.00 2023-02-26 2023-04-23 2023-08-21 nts et Matériels du Laboratoi ry Capacity to Rapidly detec tions Envelope ementation re de Bactériologie de l'INRB t Outbreaks ZR-DRC-MSP-339869-GO-RF Component 4: Institutional C Q / Reproduire des bulletins apacity Building, Project Ma Request for Quota Single Stage - One Pending Impl IDA / D5160 Post Limited 60,000.00 0.00 2023-02-27 2023-04-24 2023-08-22 d'Information REDISSE IV : In nagement, Coordination and tions Envelope ementation tervention et Témoignages d Advocacy es Bénéficiaires ZR-DRC-MSP-339500-GO-DI Component 1: Strengthenin R / Contractualisation par ED g Surveillance and Laborato Under Imple avec ESSOR EQUIPEMENTS p IDA / 64980 Post Direct Selection Direct - National 770,200.00 0.00 2023-01-31 2023-01-05 2023-02-05 2023-01-06 2023-02-18 2023-04-19 ry Capacity to Rapidly detec mentation our l'Acquisition des Machine t Outbreaks s GeneExpertes du Labo de Bunia ZR-DRC-MSP-341403-GO-RF Component 1: Strengthenin Q / Acquisition des véhicules: g Surveillance and Laborato Request for Quota Single Stage - One Under Imple 1 Véhicule de Coordination U IDA / D5160 Post Limited 280,000.00 0.00 2023-02-18 2023-04-15 2023-07-14 ry Capacity to Rapidly detec tions Envelope mentation G PDSS, 1 véhicule fermé po t Outbreaks ur LAPHAKI, 2 véhicules STAF UG PDSS ZR-DRC-MSP-339816-GO-DI R / Contractualisation par Ent Component 1: Strengthenin ente Directe avec PRODIMPE g Surveillance and Laborato Under Imple IDA / 64980 Post Direct Selection Direct - National 260,000.00 0.00 2023-02-20 2023-02-07 2023-03-02 2023-02-15 2023-03-20 2023-05-19 X pour Acquisition de 50 Mot ry Capacity to Rapidly detec mentation os de terrain pour les EIR au t Outbreaks niveau Provincial et Labo Bu nia ZR-DRC-MSP-349954-GO-RF Component 4: Institutional C Q / Production et Multiplicati apacity Building, Project Ma Request for Quota Single Stage - One Pending Impl IDA / D5160 Post Limited 60,000.00 0.00 2023-03-25 2023-05-05 2023-07-04 on des supports de Communi nagement, Coordination and tions Envelope ementation cation des Projets de l'UG PD Advocacy SS ZR-DRC-MSP-351438-GO-RF Component 1: Strengthenin Q / Acquisition des Réactifs e g Surveillance and Laborato Request for Quota Single Stage - One Pending Impl IDA / D5160 Post Limited 150,000.00 0.00 2023-04-10 2023-05-08 2023-11-04 t Consommables du Laborato ry Capacity to Rapidly detec tions Envelope ementation ire Vétérinaire pour la Détect t Outbreaks ion des Epidémies ZR-DRC-MSP-315470-GO-RF B / Acquisition des réactifs et Component 1: Strengthenin consommables médicaux po g Surveillance and Laborato Open - Internationa Single Stage - One ur les 7 laboratoires de santé IDA / D5160 Prior Request for Bids 5,250,000.00 0.00 Canceled 2022-10-31 2022-12-15 2022-12-20 2023-01-03 2023-01-22 2023-07-21 ry Capacity to Rapidly detec l Envelope des provinces du Nord-Kivu, t Outbreaks Kwilu, Kasaï Central, Kasaï Or iental, Equateur, Tshuapa et Tshopo ZR-DRC-MSP-315461-GO-RF B / Acquisition des équipeme Component 1: Strengthenin nts et matériels médicaux po g Surveillance and Laborato Open - Internationa Single Stage - One ur les 07 laboratoires de sant IDA / D5160 Prior Request for Bids 15,000,000.00 0.00 Canceled 2022-10-04 2022-11-18 2022-12-02 2022-12-16 2023-01-06 2023-05-06 ry Capacity to Rapidly detec l Envelope é publique des provinces: N t Outbreaks ord-Kivu, Kwilu, Kasaï Central , Kasaï Oriental, Equateur, Ts huapa et Tshopo ZR-DRC-MSP-354051-GO-RF B / Assurer la reproduction d Component 1: Strengthenin es bulletins épidémiologique g Surveillance and Laborato Single Stage - One Pending Impl s Mensuels de surveillance d IDA / D5160 Post Request for Bids Open - National 620,175.00 0.00 2023-04-10 2023-04-15 2023-05-05 2023-05-12 2023-06-16 2024-06-10 ry Capacity to Rapidly detec Envelope ementation es maladies (animales, de l'e t Outbreaks nvironnement et humaines) pour les structures d'Appui a u REDISSE IV ZR-DRC-MSP-354053-GO-RF B / Assurer la reproduction d Component 1: Strengthenin u bulletin trimestriel de la lut g Surveillance and Laborato Single Stage - One Pending Impl IDA / D5160 Post Request for Bids Open - National 544,000.00 0.00 2023-04-10 2023-04-15 2023-05-05 2023-05-12 2023-06-16 2024-06-10 te contre la maladie et de la ry Capacity to Rapidly detec Envelope ementation sécurité sanitaire pour les str t Outbreaks uctures du MSP d'appui du R EDISSE IV ZR-DRC-MSP-358974-GO-RF B / Fournitures et livraison d es Equipements et Petits Mat Component 1: Strengthenin ériels pour les 5Labo (05) Pr g Surveillance and Laborato Open - Internationa Single Stage - One Pending Impl IDA / D5160 Prior Request for Bids 12,500,000.00 0.00 2023-05-25 2023-05-30 2023-07-14 2023-08-13 2023-09-17 2024-03-15 ovinces: Kasaï Central (ville ry Capacity to Rapidly detec l Envelope ementation de Kananga), Kasaï Oriental ( t Outbreaks ville de Mbujimayi), Tshopo ( ville de Kisangani), Kwilu (vill e de Bandundu), Equateur (vi lle de Mbandaka) ZR-DRC-MSP-358984-GO-RF B / Fourniture et Livraison de Component 1: Strengthenin s Equipements et Petits Maté g Surveillance and Laborato Open - Internationa Single Stage - One Pending Impl riels pour les deux (2) Labora IDA / D5160 Prior Request for Bids 5,000,000.00 0.00 2023-05-31 2023-06-05 2023-07-20 2023-08-19 2023-09-23 2024-03-21 ry Capacity to Rapidly detec l Envelope ementation toires: 1 laboratoire vétérinai t Outbreaks re et 1 laboratoire Environne mental dans la ville province de Kinshasa. Page 7 ZR-DRC-MSP-361352-GO-DI R / Contractualisation avec la firme PHATKIN par Entente D Component 2: Strengthenin irecte pour l’Acquisition en u g Emergency Planning and IDA / D5160 Post Direct Selection Direct - National 399,359.00 0.00 Signed 2023-05-22 2023-05-12 2023-05-27 2023-05-12 2023-06-24 2023-10-22 rgence des Médicaments et c Management Capacity to Ra onsommables médicaux pou pidly respond to Outbreaks r la prise en charge des sinist rés de la zone de santé de K alehe, Sud Kivu. ZR-DRC-MSP-367572-GO-RF Component 1: Strengthenin Request for Quota Single Stage - One Pending Impl Q / Acquisition des vaccins p IDA / D5160 g Surveillance and Laborato Post Open - National 350,000.00 0.00 2023-06-30 2023-08-05 2024-02-01 tions Envelope ementation our le Laboratoire vétérinaire ry Capacity to Rapidly detec de Kinshasa t Outbreaks ZR-DRC-MSP-367573-GO-DI R / Contractualisation par EN Component 2: Strengthenin avec PHATKIN pour l' Acquisi g Emergency Planning and Pending Impl tion complémentaire en Urg IDA / D5160 Post Direct Selection Direct - National 175,000.00 0.00 2023-07-04 2023-07-07 2023-08-04 2023-12-02 Management Capacity to Ra ementation ence des Médicaments et Int pidly respond to Outbreaks rants pour la prise en charge des sinistrés de Kalehe au Su d Kivu. ZR-DRC-MSP-367593-GO-RF Component 1: Strengthenin Q / Acquisition des réactifs et g Surveillance and Laborato Request for Quota Single Stage - One Pending Impl IDA / D5160 Post Limited 400,000.00 0.00 2023-07-04 2023-08-29 2024-02-25 consommables médicaux po ry Capacity to Rapidly detec tions Envelope ementation ur le laboratoire Provincial d t Outbreaks e SP Lubumbashi ZR-DRC-MSP-367595-GO-RF Component 1: Strengthenin Q / Acquisition des Mobiliers g Surveillance and Laborato Request for Quota Single Stage - One Pending Impl IDA / D5160 Post Limited 90,000.00 0.00 2023-07-22 2023-09-02 2023-12-01 meubles pour le laboratoire ry Capacity to Rapidly detec tions Envelope ementation Provincial de Bunia t Outbreaks NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pr Prequalification Estimated Am Actual Amount Process St Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h ocess (Y/N) ount (US$) (US$) atus n Documents ation Report ent / Justification Notice / Invitation s Issued / Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-DRC-MSP-200146-NC-DI R / "Accords cadre" (en contr Component 1: Strengthenin actualisation) d'avec les com g Surveillance and Laborato IDA / 64980 Post Direct Selection Direct 100,000.00 0.00 Canceled 2021-01-11 2021-01-16 2021-02-20 2021-08-19 pagnies aériennes, agences ry Capacity to Rapidly detec de voyage, pour le transport t Outbreaks des échantillons (santé anim ale et santé humaine). ZR-DRC-MSP-200158-NC-RF Component 1: Strengthenin Request for Quota Single Stage - One Pending Impl Q / Services spécialisés de tr IDA / 64980 g Surveillance and Laborato Post Limited 250,000.00 0.00 2021-01-16 2021-03-13 2021-09-09 tions Envelope ementation ansport des échantillons. ry Capacity to Rapidly detec t Outbreaks ZR-DRC-MSP-261328-NC-DI R / Contractualisation par ent ente avec l'UNICEF pour la r Component 2: Strengthenin éduction des infections assoc g Emergency Planning and IDA / 64980 Prior Direct Selection Direct 6,000,000.00 6,000,000.00 Signed 2021-11-30 2021-11-03 2021-12-05 2021-12-06 2022-01-09 2021-12-22 2022-07-08 iées aux soins de santé et re Management Capacity to Ra nforcement de la résilience c pidly respond to Outbreaks ommunautaire contre la Mal adie à Virus Ebola (MVE) et l a COVID-19. ZR-DRC-MSP-272388-NC-RF B / Sélection d'un prestataire Component 1: Strengthenin pour la reproduction des bul g Surveillance and Laborato Single Stage - One Pending Impl IDA / 64980 Post Request for Bids Open - National 500,000.00 0.00 2022-01-28 2022-02-02 2022-03-16 2022-04-15 2022-05-20 2023-05-20 letins épidémiologiques men ry Capacity to Rapidly detec Envelope ementation suels de surveillance des mal t Outbreaks adies et outils SIMAR (animal es et humaines) ZR-DRC-MSP-272389-NC-RF B / Sélection d'un prestataire Component 1: Strengthenin pour la reproduction des out g Surveillance and Laborato Single Stage - One Pending Impl IDA / 64980 Post Request for Bids Open - National 500,000.00 0.00 2022-01-28 2022-02-02 2022-03-16 2022-04-15 2022-05-20 2023-05-20 ils de SMIR (guides techniqu ry Capacity to Rapidly detec Envelope ementation es 3ème édition, Guide des p t Outbreaks articipants et de facilitateurs ) et bulletins épidémiologiqu es ZR-DRC-MSP-272404-NC-DI R / Contractualisation avec la Compagnie Transport Logisti Component 1: Strengthenin que Traiding TLC pour le tran g Surveillance and Laborato Under Imple IDA / 64980 Post Direct Selection Direct 400,000.00 0.00 2022-03-30 2022-03-07 2022-04-04 2022-03-08 2022-05-09 2023-05-09 sport des échantillons les Pro ry Capacity to Rapidly detec mentation vinces de: l'Equateur, Kasai t Outbreaks Central, la Tshopo, le Kwilu, Nord et en Ituri vers Kinsha sa pour les analyses ZR-DRC-MSP-295887-NC-RF Q / Location temporaire d'un Component 2: Strengthenin entrepôt pendant 6 mois pou g Emergency Planning and Request for Quota Single Stage - One r le stockage des biens et éq IDA / 64980 Post Limited 220,000.00 0.00 Canceled 2022-06-14 2022-06-30 2022-12-27 Management Capacity to Ra tions Envelope uipement du Ministère de la pidly respond to Outbreaks Santé actuellement logés da ns l’entrepôt de Mama Yemo en phase de réhabilitation ZR-DRC-MSP-300941-NC-DI R / Contractualisation par ED avec UNFPA pour appui des Component 1: Strengthenin projets PDSS, PMNS, REDISS g Surveillance and Laborato IDA / D5160 Prior Direct Selection Direct 20,000,000.00 20,000,000.00 Signed 2022-06-27 2022-07-13 2022-07-02 2022-07-14 2022-08-06 2022-06-24 2023-02-02 E IV et COVID 19 pour atténu ry Capacity to Rapidly detec ation et réponses aux risque t Outbreaks s de EAS/HS liés à la mise en Œuvre dans les zones d'inter vention de ces projets ZR-DRC-MSP-305229-NC-DI R / Contractualisation par Ent ente directe avec CAMESE e Component 1: Strengthenin n vue d'assurer les services g Surveillance and Laborato Under Imple de Réception, de stockage, d IDA / 64980 Post Direct Selection Direct - National 49,751.00 0.00 2022-07-21 2022-05-27 2022-07-26 2022-07-26 2022-08-30 2023-02-26 ry Capacity to Rapidly detec mentation e colisage par formation sani t Outbreaks taire bénéficiaire et distributi on secondaires des medicam ents vers 278 formations sa nitaires dans les 18 ZS ZR-DRC-MSP-311157-NC-DI R / Contractualisation par ED avec SADCAS ( Southern Afri Component 1: Strengthenin can Development Communit g Surveillance and Laborato Under Imple y Accréditation Services ) en IDA / D5160 Post Direct Selection Direct - National 100,000.00 0.00 2022-09-05 2022-08-26 2022-09-10 2022-10-15 2023-04-13 ry Capacity to Rapidly detec mentation Faveur du Laboratoire Nation t Outbreaks al de Contrôle Qualité - LAPH AKI à l'Accréditation ISO/IEC 17025:2017 de l'Unité d'Anal yse Physicochimique ZR-DRC-MSP-311158-NC-DI R / Contractualisation par ED HI-TECH détection System ( Component 1: Strengthenin HI-TECH) (HTDS) du Labo N g Surveillance and Laborato Under Imple ational de Contrôle Qualité - IDA / D5160 Post Direct Selection Direct - National 25,000.00 0.00 2022-09-05 2022-08-26 2022-09-10 2022-10-15 2023-04-13 ry Capacity to Rapidly detec mentation LAPHAKI pour qualification O t Outbreaks pérationnelle d'équipements en vue d'Accréditation ISO/IE C 17025 :2017 de l'unité d'a nalyse Physicochimique ZR-DRC-MSP-318362-NC-DI R / Contractualisation par Ent ente Directe avec la Firme B Component 1: Strengthenin OLLORE pour Location tempo g Surveillance and Laborato raire d'un entrepôt pendant IDA / D5160 Post Direct Selection Direct - National 220,000.00 0.00 Signed 2022-09-30 2022-09-27 2022-10-05 2022-09-30 2022-10-22 2023-04-20 ry Capacity to Rapidly detec 6 mois pour le stockage des t Outbreaks biens et équipement du MSP actuellement logés dans l’en trepôt de Mama Yemo en ph ase de Réhabilitation ZR-DRC-MSP-327484-NC-DI R / Contractualisation par Ent ente Directe avec la Firme BI Component 1: Strengthenin LEM IMPRESSIONS pour Repr g Surveillance and Laborato Under Imple oduire, l'imprimer les Outils IDA / 64980 Post Direct Selection Direct - National 790,778.00 0.00 2022-11-21 2022-11-18 2022-11-24 2022-11-24 2022-12-09 2023-04-08 ry Capacity to Rapidly detec mentation de Formation et relais comm t Outbreaks unautaire dans Six Provinces cibles: Kasaï Central, Kasaï O riental, Tshopo, Kwilu, Nord Kivu et Tshuapa. ZR-DRC-MSP-334013-NC-DI R / Contractualisation par Ent Component 1: Strengthenin ente Directe avec OIM pour l g Surveillance and Laborato Direct - Internation e renforcement des capacité IDA / D5160 Prior Direct Selection 21,658,235.00 0.00 Canceled 2022-12-29 2023-01-06 2023-01-03 2023-01-06 2023-01-25 2024-05-19 ry Capacity to Rapidly detec al s des 18 Points d'Entrée (PoE t Outbreaks ) désignés et sites sentinelle s pour appuyer REDISSE IV s ous Financement Banque Mo ndiale. Page 8 ZR-DRC-MSP-334218-NC-DI R / Contractualisation par Ent Component 1: Strengthenin ente Directe avec OIM pour l g Surveillance and Laborato Direct - Internation e renforcement des capacité IDA / D5160 Prior Direct Selection 21,658,235.00 0.00 Canceled 2022-12-30 2023-01-04 2023-01-23 2024-05-17 ry Capacity to Rapidly detec al s des 18 Points d'Entrée (PoE t Outbreaks ) désignés et sites sentinelle s pour appuyer REDISSE IV s ous Financement Banque Mo ndiale. ZR-DRC-MSP-334013-NC-DI Component 1: Strengthenin R-2 / Contractualisation par E g Surveillance and Laborato Direct - Internation ntente Directe avec l'OIM po IDA / D5160 Prior Direct Selection 21,658,235.00 0.00 Signed 2023-01-09 2023-01-10 2023-01-14 2023-01-10 2023-01-31 2024-05-25 ry Capacity to Rapidly detec al ur le Renforcement des Capa t Outbreaks cités des 18 Points d'Entrées (POEs) ZR-DRC-MSP-354033-NC-DI R / Contractualisation par ED avec le Groupe INNOVIE po Component 1: Strengthenin ur le Transport et Conservati g Surveillance and Laborato Under Imple IDA / D5160 Post Direct Selection Direct - National 200,000.00 0.00 2023-04-03 2023-04-14 2023-04-08 2023-05-05 2023-04-27 2023-10-24 on des échantillons Biologiqu ry Capacity to Rapidly detec mentation es pour les 5 Labo des HGR d t Outbreaks e la Province du Kwilu en RD C pour rapidement détecter l es épidémies ZR-DRC-MSP-358330-NC-RF Q / Sélection d'1 prestataire Logistique basé à Kin pour l'e Component 1: Strengthenin ntreposage temporaire des g Surveillance and Laborato Request for Quota Single Stage - One Pending Impl matériels médicaux destinés IDA / D5160 Post Open - National 650,000.00 0.00 2023-05-08 2023-06-12 2023-12-09 ry Capacity to Rapidly detec tions Envelope ementation au renforcement des capacit t Outbreaks és des FOSA des provinces: Kwilu, Kwango, Maindombe, Tshuapa et Kin dans la prépa ration et la riposte aux épidé mies ZR-DRC-MSP-358333-NC-RF Q / Sélection d'1 prestataire l ogistique basé à Gemena po Component 1: Strengthenin ur l'Entreposage Temporaire g Surveillance and Laborato Request for Quota Single Stage - One Pending Impl IDA / D5160 Post Open - National 150,000.00 0.00 2023-05-08 2023-06-30 2023-12-27 des matériels médicaux desti ry Capacity to Rapidly detec tions Envelope ementation nés au Renforcement des ca t Outbreaks pacités des FOSA de la Provi nce du Sud-Ubangui dans la préparation et la riposte aux Epidémies ZR-DRC-MSP-358341-NC-RF Q / Sélection d'un Prestataire Logistique basé à Lubumbas Component 1: Strengthenin hi pour l'entreposage Tempo g Surveillance and Laborato Request for Quota Single Stage - One Pending Impl IDA / D5160 Post Open - National 350,000.00 0.00 2023-05-08 2023-06-12 2023-12-09 raire des matériels médicaux ry Capacity to Rapidly detec tions Envelope ementation destinés au Renforcement C t Outbreaks apacité des FOSA des provin ces du Haut-Katanga, Haut-L omami et Lualaba ZR-DRC-MSP-358343-NC-RF Q / Sélection du prestataire l Component 1: Strengthenin ogistique basé à Goma pour l g Surveillance and Laborato Request for Quota Single Stage - One Pending Impl 'entreposage temporaire des IDA / D5160 Post Open - National 190,000.00 0.00 2023-05-08 2023-06-12 2023-12-09 ry Capacity to Rapidly detec tions Envelope ementation matériels médicaux destinés t Outbreaks au Renforcement des capacit és des FOSA des Provinces d u Nord-Kivu et du Maniema ZR-DRC-MSP-358992-NC-DI R / Contractualisation par ED avec CAI UNICEF pour: la col Component 2: Strengthenin lecte, comprendre les facteu g Emergency Planning and Under Imple IDA / D5160 Post Direct Selection Direct - National 178,000.00 0.00 2023-05-15 2023-04-28 2023-05-20 2023-05-10 2023-06-09 2023-12-06 rs (Obstacles et facilitateurs) Management Capacity to Ra mentation , l'analyse et l'utilisation de d pidly respond to Outbreaks onnées désagrégées par sex e et Sexo spécifiques dans la Surveillances des maladies e n RDC CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Expression of Interes Short List and Draft R Request for Proposal Opening of Technical Evaluation of Techni Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) t (US$) t Notice equest for Proposals s as Issued Proposals / Minutes cal Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-DRC-MSP-184499-CS-QC Component 1: Strengthenin BS / Contractualisation avec g Surveillance and Laborato Quality And Cost- une structure spécialisée po IDA / 64980 Prior Open - National 5,000,000.00 0.00 Canceled 2020-08-24 2020-09-14 2020-10-28 2020-11-25 2020-12-25 2021-01-29 2021-03-05 2022-03-05 ry Capacity to Rapidly detec Based Selection ur la gestion logistique et ch t Outbreaks aine d’approvisionnement ZR-DRC-MSP-184500-CS-QC Component 1: Strengthenin BS / Contractualisation avec g Surveillance and Laborato Quality And Cost- des Centres d’Excellence et IDA / 64980 Prior Open - National 1,200,000.00 0.00 Canceled 2021-06-27 2021-07-18 2021-08-31 2021-09-28 2021-10-28 2021-12-02 2022-01-06 2023-01-06 ry Capacity to Rapidly detec Based Selection de laboratoires pour la fourni t Outbreaks ture de service de diagnostic ZR-DRC-MSP-184517-CS-QC Component 1: Strengthenin Quality And Cost- BS / Recrutement d’une firm IDA / 64980 g Surveillance and Laborato Post Open - National 150,000.00 0.00 Canceled 2020-08-24 2020-09-14 2020-10-28 2020-11-25 2020-12-25 2021-01-29 2021-03-05 2022-03-05 Based Selection e pour l’audit financier exter ry Capacity to Rapidly detec ne du projet t Outbreaks ZR-DRC-MSP-184542-CS-QC Component 1: Strengthenin Quality And Cost- BS / Recrutement d'un consu IDA / 64980 g Surveillance and Laborato Post Open - National 350,000.00 0.00 Canceled 2020-08-28 2020-09-18 2020-11-01 2020-11-29 2020-12-29 2021-02-02 2021-03-09 2022-03-09 Based Selection ltant externe pour le suivi en ry Capacity to Rapidly detec vironnemental t Outbreaks ZR-DRC-MSP-118031-CS-CQ Component 1: Strengthenin Consultant Qualifi S / Recrutement de consulta / g Surveillance and Laborato Post Open - National 350,000.00 0.00 Canceled 2019-08-22 2019-09-12 2019-10-26 2019-11-25 2019-12-30 2020-06-27 cation Selection nt pour faire l'état des lieux ry Capacity to Rapidly detec des laboratoires t Outbreaks ZR-DRC-MSP-117886-CS-CQ Component 1: Strengthenin S / Contractualisation avec u g Surveillance and Laborato Consultant Qualifi ne structure spécialisée pour / Prior Open - National 900,000.00 0.00 Canceled 2019-08-28 2019-09-18 2019-11-01 2019-12-01 2020-01-05 2020-07-03 ry Capacity to Rapidly detec cation Selection l'amélioration des systèmes t Outbreaks de transport des échantillons ZR-DRC-MSP-118041-CS-QC Component 4: Institutional C Quality And Cost- BS / Recrutement d'une firm / apacity Building, Project Ma Post Open - National 150,000.00 0.00 Canceled 2019-09-09 2019-09-30 2019-11-13 2019-12-11 2020-01-10 2020-02-14 2020-03-20 2021-03-20 Based Selection e pour l'audit financier exter nagement, Coordination and ne du projet Advocacy ZR-DRC-MSP-118040-CS-CQ Component 1: Strengthenin S / Recrutement d'une firme g Surveillance and Laborato Consultant Qualifi / Post Open - National 150,000.00 0.00 Canceled 2019-08-27 2019-09-17 2019-10-31 2019-11-30 2020-01-04 2020-07-02 pour l'élaboration du Plan Str ry Capacity to Rapidly detec cation Selection atégique des laboratoires de t Outbreaks l'Espace CEEAC ZR-DRC-MSP-118039-CS-CQ Component 1: Strengthenin S / Recrutement d'un Cabine g Surveillance and Laborato Consultant Qualifi t pour élaborer le document / Post Open - National 150,000.00 0.00 Canceled 2019-08-14 2019-09-04 2019-10-18 2019-11-17 2019-12-22 2020-06-19 ry Capacity to Rapidly detec cation Selection de réglementation du transp t Outbreaks ort international des échantil lons biologiques ZR-DRC-MSP-118038-CS-CQ Component 1: Strengthenin S / Recrutement d'un Cabine g Surveillance and Laborato Consultant Qualifi t pour l'élaboration d'un plan / Post Open - National 150,000.00 0.00 Canceled 2019-08-05 2019-08-26 2019-10-09 2019-11-08 2019-12-13 2020-06-10 ry Capacity to Rapidly detec cation Selection stratégique de préparation e t Outbreaks t de réponse aux épidémies et urgences sanitaires ZR-DRC-MSP-118036-CS-CQ S / Recrutement d'une firme pour la mise en place d'un sy Component 3: Public Health Consultant Qualifi / Post Open - National 150,000.00 0.00 Canceled 2019-08-12 2019-09-02 2019-10-16 2019-11-15 2019-12-20 2020-06-17 stème d'information qui pren Workforce Development cation Selection d en compte les activités de l a santé humaine et animale ZR-DRC-MSP-118035-CS-CQ S / Recrutement d'une firme Component 3: Public Health Consultant Qualifi / Post Open - National 150,000.00 0.00 Canceled 2019-08-13 2019-09-03 2019-10-17 2019-11-16 2019-12-21 2020-06-18 pour l'élaboration de la strat Workforce Development cation Selection égie régionale sur les activit és transfrontalières ZR-DRC-MSP-209283-CS-CQ Component 1: Strengthenin S / Sélection et recrutement g Surveillance and Laborato Consultant Qualifi d'un consultant firme pour fa IDA / 64980 Post Open - National 350,000.00 0.00 Canceled 2021-01-26 2021-05-19 2021-02-16 2021-04-01 2021-05-01 2021-06-05 2021-12-02 ry Capacity to Rapidly detec cation Selection ire l’état des lieux (Ingénieur t Outbreaks Architecte et Bio médical) de s laboratoires. ZR-DRC-MSP-199255-CS-CQ S / Sélection et recrutement Component 1: Strengthenin d'un Consultant firme pour la g Surveillance and Laborato Consultant Qualifi Pending Impleme conception, la mise en place, IDA / 64980 Post Open - National 124,500.00 0.00 2020-12-30 2021-01-20 2021-03-05 2021-04-04 2021-05-09 2021-11-05 ry Capacity to Rapidly detec cation Selection ntation et la mise en oeuvre des syst t Outbreaks èmes électroniques de survei llance inter opérable dans le cadre de « Une Santé ». Page 9 ZR-DRC-MSP-199256-CS-CQ Component 1: Strengthenin S / Sélection et recrutement g Surveillance and Laborato Consultant Qualifi d’une firme pour l’élaboratio IDA / 64980 Post Open - National 150,000.00 0.00 Canceled 2021-01-05 2021-01-26 2021-03-11 2021-04-10 2021-05-15 2021-11-11 ry Capacity to Rapidly detec cation Selection n du Plan Stratégique des lab t Outbreaks oratoires de l’Espace CEEAC. ZR-DRC-MSP-199251-CS-CQ S / Sélection et recrutement Component 1: Strengthenin d'un consultant firme pour l' g Surveillance and Laborato Consultant Qualifi accompagnement de (s) labo IDA / 64980 Post Open - National 109,920.00 0.00 Canceled 2021-03-25 2021-04-15 2021-05-29 2021-06-28 2021-08-02 2022-01-29 ry Capacity to Rapidly detec cation Selection ratoire (s) de la RDC au proc t Outbreaks essus d'accréditation et de S ystème Management de Qua lité (SMQ). ZR-DRC-MSP-199263-CS-CQ S / Sélection et recrutement d'un consultant firme pour u Component 3: Public Health Consultant Qualifi IDA / 64980 Post Open - National 100,000.00 0.00 Canceled 2021-01-25 2021-02-15 2021-03-31 2021-04-30 2021-06-04 2021-12-01 n Audit organisationnel des s Workforce Development cation Selection tructures des trois (3) minist ères parties prenantes au Pr ojet. ZR-DRC-MSP-199278-CS-CQ S / Sélection d'un cabinet d'a Component 4: Institutional C vocats pour réaliser un état apacity Building, Project Ma Consultant Qualifi Pending Impleme des lieux des textes juridique IDA / 64980 Post Open - National 100,000.00 0.00 2021-01-11 2021-02-01 2021-03-17 2021-04-16 2021-05-21 2021-11-17 nagement, Coordination and cation Selection ntation s et reglémentaires et élabor Advocacy er les avants projet des texte s juridiques pour la mise en œuvre du RSI. ZR-DRC-MSP-199469-CS-CQ Component 4: Institutional C S / Sélection et recrutement apacity Building, Project Ma Consultant Qualifi IDA / 64980 Post Open - National 150,000.00 0.00 Canceled 2020-12-30 2021-01-20 2021-03-05 2021-04-04 2021-05-09 2021-11-05 d’une firme pour l’audit finan nagement, Coordination and cation Selection cier externe du projet. Advocacy ZR-DRC-MSP-199474-CS-CQ S / Sélection et recrutement Component 4: Institutional C d'un consultant firme extern apacity Building, Project Ma Consultant Qualifi IDA / 64980 Post Open - National 350,000.00 0.00 Canceled 2021-01-05 2021-01-26 2021-03-11 2021-04-10 2021-05-15 2021-11-11 e pour le suivi des études en nagement, Coordination and cation Selection vironnementales et la produc Advocacy tion des différents document s. ZR-DRC-MSP-199475-CS-CQ S / Sélection et recrutement Component 4: Institutional C d'une ONG pour la mise en apacity Building, Project Ma Consultant Qualifi IDA / 64980 Post Open - National 300,000.00 0.00 Canceled 2021-01-05 2021-01-26 2021-03-11 2021-04-10 2021-05-15 2021-11-11 œuvre des activités de préve nagement, Coordination and cation Selection ntion et sensibilisation des Vi Advocacy olences Basées sur le Genre ZR-DRC-MSP-199476-CS-CQ S / Sélection et recrutement Component 4: Institutional C d'une ONG chargée de l'éval apacity Building, Project Ma Consultant Qualifi IDA / 64980 Post Open - National 100,000.00 0.00 Canceled 2021-05-03 2021-05-24 2021-07-07 2021-08-06 2021-09-10 2022-03-09 uation de la mise en œuvre d nagement, Coordination and cation Selection es activités ayant trait aux Vi Advocacy olences Basées sur le Genre ZR-DRC-MSP-266799-CS-QC BS / Sélection et Recrutemen t d’un Consultant (Bureau d’ Component 4: Institutional C études Architecturales) char apacity Building, Project Ma Quality And Cost- Under Implement gé des Études techniques et IDA / 64980 Post Open - National 100,000.00 0.00 2022-02-24 2022-01-02 2022-03-17 2022-03-23 2022-04-30 2022-04-19 2022-05-28 2022-06-27 2022-08-01 2022-09-05 2023-09-05 nagement, Coordination and Based Selection ation d'évaluation environnementa Advocacy le et sociale préliminaire, du Contrôle et de la Surveillanc e des travaux de constructio n/ réhabilitation des bureaux ZR-DRC-MSP-287280-CS-QC BS / Recrutement "Bureau d’ études, Contrôle et Surveilla Component 1: Strengthenin nce" Chargé des Études Tech g Surveillance and Laborato Quality And Cost- Under Implement niques, Evaluation Environne IDA / 64980 Post Open - National 100,000.00 0.00 2022-04-04 2022-03-31 2022-04-18 2022-04-07 2022-06-01 2022-06-29 2022-07-29 2022-09-02 2022-10-07 2023-02-04 ry Capacity to Rapidly detec Based Selection ation mentale et Sociale, du Contr t Outbreaks ôle et de la Surveillance des Travaux de Réhab des Labo de Bactériologie en Charge d e la Surveillance Epidémiolog ique ZR-DRC-MSP-295894-CS-QC BS / Sélection et Recrutemen Component 1: Strengthenin t d'un Consultant firme pour l g Surveillance and Laborato Quality And Cost- a Conception, la mise en pla IDA / 64980 Post Open - National 150,000.00 0.00 Canceled 2022-05-31 2022-06-02 2022-06-14 2022-07-05 2022-07-12 2022-07-13 2022-08-17 2022-09-21 2023-09-21 ry Capacity to Rapidly detec Based Selection ce, et la mise en œuvre des t Outbreaks systèmes électroniques de s urveillance inter opérable da ns le cadre de « Une Santé ». ZR-DRC-MSP-295896-CS-CQ Component 4: Institutional C S / Recrutement d'un cabinet apacity Building, Project Ma Consultant Qualifi Under Implement IDA / 64980 Post Open - National 100,000.00 0.00 2022-05-31 2022-05-31 2022-06-14 2022-07-05 2022-07-20 2022-08-24 2023-02-20 d'avocat pour état des lieux nagement, Coordination and cation Selection ation des textes juridiques DGLM / Advocacy PNHF ZR-DRC-MSP-301427-CS-QC BS / Recruter d'un Bureau d' Component 2: Strengthenin Études pour les études Archi g Emergency Planning and Quality And Cost- Pending Impleme tecturales et environnement IDA / D5160 Post Open - National 100,000.00 0.00 2022-06-29 2022-07-13 2022-08-19 2022-08-26 2022-09-02 2022-09-10 2022-10-11 2022-12-10 Management Capacity to Ra Based Selection ntation ale en vue de la construction pidly respond to Outbreaks du bâtiment du Centre des O pérations des Urgences de S anté Publics ( COUSP) ZR-DRC-MSP-301442-CS-QC BS / Recrutement d'un Cabin Component 1: Strengthenin et / Bureau d'Études pour Ét g Surveillance and Laborato Quality And Cost- Under Implement ats des lieux pour la réhabilit IDA / D5160 Post Open - National 150,000.00 0.00 2022-06-29 2022-11-01 2022-07-13 2022-08-19 2022-08-26 2022-09-02 2022-09-10 2022-10-11 2022-12-10 ry Capacity to Rapidly detec Based Selection ation ation deux laboratoires de co t Outbreaks ntrôle phytosanitaire et surv eillance environnementale à Kinshasa et Lubumbashi. ZR-DRC-MSP-315480-CS-QC BS / Sélection et recrutemen Component 1: Strengthenin t d'un Consultant Firme pour g Surveillance and Laborato Quality And Cost- Under Implement la rationalisation et la mise e IDA / 64980 Post Open - National 100,000.00 0.00 2022-09-20 2022-11-07 2022-10-04 2022-10-23 2022-10-28 2022-11-02 2022-11-09 2022-11-21 2022-12-21 ry Capacity to Rapidly detec Based Selection ation n place d’un cadre réglemen t Outbreaks taire et institutionnel de l'Ins titut National de Santé Publiq ue (INSP) ZR-DRC-MSP-315481-CS-QC BS / Le Recrutement d’un co nsultant firme charge d’élab Component 1: Strengthenin oration de trois rapports d’Et g Surveillance and Laborato Quality And Cost- Under Implement udes d’impacts environneme IDA / 64980 Post Open - National 250,000.00 0.00 2022-09-20 2022-09-12 2022-10-04 2022-10-23 2022-10-28 2022-11-02 2022-11-09 2022-11-21 2023-01-20 ry Capacity to Rapidly detec Based Selection ation ntal et social (EIES) distincts t Outbreaks pour la construction des labo ratoires provinciaux de sante publique de Mbandaka, Kana nga et Mbuji-Mayi du redisse ZR-DRC-MSP-301452-CS-QC BS / Recruter un Cabinet firm e pour Surveillance des Trav Component 1: Strengthenin aux LAPHAKI, Spécifications t g Surveillance and Laborato Quality And Cost- echniques des matériels et é IDA / D5160 Post Open - National 300,000.00 0.00 Canceled 2022-07-04 2022-10-12 2022-07-18 2022-08-24 2022-08-31 2022-09-07 2022-09-15 2022-10-16 2022-12-15 ry Capacity to Rapidly detec Based Selection quipements, assistance tech t Outbreaks nique et renforcement des c apacités du personnel techni que de 2 laboratoires en cou rs de réhabilitation avec la U SP ZR-DRC-MSP-184529-CS-QC Component 1: Strengthenin BS / Accompagnement de la g Surveillance and Laborato Quality And Cost- bo de la RDC au processus d' IDA / D5160 Post Open - National 109,920.00 0.00 Canceled 2021-03-20 2021-04-10 2021-05-24 2021-06-21 2021-07-21 2021-08-25 2021-09-29 2022-09-29 ry Capacity to Rapidly detec Based Selection accreditation et de Système t Outbreaks Management de Qualité (SM Q) ZR-DRC-MSP-199261-CS-QC BS / Sélection et recrutemen Component 2: Strengthenin t des Centres d’Excellence et g Emergency Planning and Quality And Cost- de laboratoires pour renforce IDA / 64980 Prior Open - National 1,200,000.00 0.00 Canceled 2021-06-29 2021-07-20 2021-09-02 2021-09-30 2021-10-30 2021-12-04 2022-01-08 2023-01-08 Management Capacity to Ra Based Selection r les capacités des laboratoir pidly respond to Outbreaks es nationaux (en santé huma ine et en santé animale) à po ser des diagnostics. ZR-DRC-MSP-199276-CS-QC BS / Sélection et recrutemen Component 4: Institutional C t du (des) bureau (x) d'étude apacity Building, Project Ma Quality And Cost- s chargé (s) du contrôle et d IDA / 64980 Post Open - National 500,000.00 0.00 Canceled 2020-12-23 2021-02-18 2021-01-13 2022-02-16 2021-02-26 2021-03-26 2021-04-25 2021-05-30 2021-07-04 2022-07-04 nagement, Coordination and Based Selection e la surveillance des travaux Advocacy de construction/ réhabilitatio n envisagés dans le cadre de la mise en œuvre du Projet. Page 10 ZR-DRC-MSP-199257-CS-QC BS / Sélection et recrutemen Component 1: Strengthenin t d'une agence de communic g Surveillance and Laborato Quality And Cost- IDA / 64980 Post Open - National 950,000.00 0.00 Canceled 2021-06-29 2021-07-20 2021-09-02 2021-09-30 2021-10-30 2021-12-04 2022-01-08 2023-01-08 ation pour la gestion de l’info ry Capacity to Rapidly detec Based Selection rmation et le développement t Outbreaks technique (mise en place d’u n portail web). ZR-DRC-MSP-301445-CS-QC BS / Recruter un cabinet . fir Component 1: Strengthenin me pour l'accréditation / cert g Surveillance and Laborato Quality And Cost- IDA / D5160 Post Open - National 100,000.00 0.00 Canceled 2022-07-11 2022-07-25 2022-08-31 2022-09-07 2022-09-14 2022-09-22 2022-10-23 2022-12-22 ification du laboratoire physi ry Capacity to Rapidly detec Based Selection cochimique déjà Réhabilité I t Outbreaks SO / IEC 17025:2017. " ZR-DRC-MSP-199244-CS-QC BS / Sélection et recrutemen Component 1: Strengthenin t des structures spécialisées g Surveillance and Laborato Quality And Cost- IDA / 64980 Prior Open - National 5,000,000.00 0.00 Canceled 2021-01-26 2021-02-16 2021-04-01 2021-04-29 2021-05-29 2021-07-03 2021-08-07 2022-08-07 en stratégie de gestion logist ry Capacity to Rapidly detec Based Selection ique et chaine d’approvision t Outbreaks nement des médicaments, in trants et réactifs de laboratoi re. ZR-DRC-MSP-184502-CS-QC Component 1: Strengthenin BS / Contractualisation avec g Surveillance and Laborato Quality And Cost- une structure spécialisée po IDA / 64980 Post Open - National 900,000.00 0.00 Canceled 2021-06-27 2021-07-18 2021-08-31 2021-09-28 2021-10-28 2021-12-02 2022-01-06 2023-01-06 ry Capacity to Rapidly detec Based Selection ur l’amélioration des systèm t Outbreaks es de transport des échantill ons ZR-DRC-MSP-199258-CS-CQ S / Sélection et recrutement Component 2: Strengthenin d’un consultant firme pour la g Emergency Planning and Consultant Qualifi mise en place d’un système IDA / 64980 Post Open - National 150,000.00 0.00 Canceled 2021-01-05 2021-01-26 2021-03-11 2021-04-10 2021-05-15 2021-11-11 Management Capacity to Ra cation Selection d’information frontalier qui p pidly respond to Outbreaks rend en compte les activités de la santé humaine et anim ale. ZR-DRC-MSP-199478-CS-CQ Component 4: Institutional C S / Sélection et recrutement apacity Building, Project Ma Consultant Qualifi d’un consultant firme pour l’ IDA / 64980 Post Open - National 150,000.00 0.00 Canceled 2021-06-01 2021-06-22 2021-08-05 2021-09-04 2021-10-09 2022-04-07 nagement, Coordination and cation Selection élaboration de la stratégie ré Advocacy gionale sur les activités trans frontalières. ZR-DRC-MSP-335515-CS-CQ Component 4: Institutional C S / Recrutement d'un Cabine apacity Building, Project Ma Consultant Qualifi Under Implement IDA / D5160 Post Limited 25,000.00 0.00 2023-01-19 2023-02-06 2023-02-02 2023-03-04 2023-04-08 2024-04-02 t d'Audit pour Appuyer la Cell nagement, Coordination and cation Selection ation ule d'Audit de l'UG PDSS pou Advocacy r les 4 Programmes. ZR-DRC-MSP-339884-CS-CQ Component 1: Strengthenin S / Recrutement d'un consult g Surveillance and Laborato Consultant Qualifi Pending Impleme ant firme pour mise en place IDA / D5160 Post Limited 200,000.00 0.00 2023-02-24 2023-03-10 2023-04-09 2023-05-14 2024-05-08 ry Capacity to Rapidly detec cation Selection ntation du Système de Gestion digit t Outbreaks ale de l'Entrepôt du MSP, à l' hôpital Mama Yemo ZR-DRC-MSP-339948-CS-CQ S / Réaliser les évaluations e nvironnementales et sociales Component 1: Strengthenin préliminaires, études de sau g Surveillance and Laborato Consultant Qualifi Under Implement IDA / D5160 Post Limited 150,000.00 0.00 2023-02-15 2023-04-05 2023-02-22 2023-03-04 2023-03-19 2023-04-18 vegarde environnementales ry Capacity to Rapidly detec cation Selection ation et sociales des activités de ci t Outbreaks nq (5) laboratoires des HGR à Kwilu (Recrutement des co nsultants firme; individuels) ZR-DRC-MSP-346702-CS-CQ Component 1: Strengthenin S / Recrutement d'un Consult g Surveillance and Laborato Consultant Qualifi Pending Impleme ant pour Réaliser une Etude IDA / 64980 Post Limited 100,000.00 0.00 2023-03-06 2023-03-20 2023-04-03 2023-05-08 2023-06-13 ry Capacity to Rapidly detec cation Selection ntation sur la Viabilité et la pérennit t Outbreaks é des Laboratoires à Réhabili ter / Construire ZR-DRC-MSP-349986-CS-CQ S / Recrutement d'un cabinet Component 1: Strengthenin / Firme pour Etudes d'Impact g Surveillance and Laborato Consultant Qualifi Under Implement IDA / D5160 Post Limited 130,000.00 0.00 2023-03-20 2023-03-20 2023-04-03 2023-04-10 2023-05-08 2023-08-06 Environnemental et Social de ry Capacity to Rapidly detec cation Selection ation s Travaux de Construction de t Outbreaks s Laboratoires de Santé Publi que de Kwilu et Kisangani ZR-DRC-MSP-351456-CS-QC BS / Recrutement d'un Cabin Component 1: Strengthenin et Chargé pour la mise en pl g Surveillance and Laborato Quality And Cost- Pending Impleme ace d'un Système d'Opératio IDA / 64980 Post Open - National 425,000.00 0.00 2023-03-27 2023-04-10 2023-05-01 2023-05-08 2023-05-09 2023-06-13 2023-07-18 2024-02-13 ry Capacity to Rapidly detec Based Selection ntation nnalisation du Système Elect t Outbreaks ronique des Surveillances Int égrée et Interopérable dans « Une Santé ». INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Draft Negotiated Con Description Component Review Type Method Process Status Terms of Reference d/Selected Consultan Signed Contract Contract Completion o. h unt (US$) t (US$) tract t Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-DRC-MSP-117851-CS-CD Component 1: Strengthenin S / Contractualisation avec l' g Surveillance and Laborato / Prior Direct Selection Direct 20,000,000.00 0.00 Canceled 2019-07-22 2019-08-01 2019-10-05 2020-04-02 UNFPA pour la fourniture de ry Capacity to Rapidly detec médicaments et réactifs t Outbreaks ZR-DRC-MSP-117866-CS-CD Component 2: Strengthenin S / Contractualisation avec l' g Emergency Planning and / Prior Direct Selection Direct 5,000,000.00 0.00 Canceled 2019-07-24 2019-08-03 2019-10-07 2020-04-04 UNICEF pour la gestion logist Management Capacity to Ra ique et chaine d'approvision pidly respond to Outbreaks nement ZR-DRC-MSP-117882-CS-CD Component 2: Strengthenin S / Contractualisation avec l'I g Emergency Planning and / Prior Direct Selection Direct 1,200,000.00 0.00 Canceled 2019-08-19 2019-08-29 2019-11-02 2020-04-30 NRB pour la fourniture de ser Management Capacity to Ra vice de diagnostic pidly respond to Outbreaks ZR-DRC-MSP-117885-CS-CD Component 2: Strengthenin S / Contractualisation avec B g Emergency Planning and LUES QUARE pour la gestion / Prior Direct Selection Direct 950,000.00 0.00 Canceled 2019-08-27 2019-09-06 2019-11-10 2020-05-08 Management Capacity to Ra de l'information et le dévelop pidly respond to Outbreaks pement technique (mise en place d'un portail web) ZR-DRC-MSP-117895-CS-IND Component 4: Institutional C Individual Consult V / Recrutement d'un chef de IDA / D5160 apacity Building, Project Ma Prior Open 400,000.00 168,600.00 Signed 2019-08-13 2020-06-18 2019-10-01 2020-08-25 2019-10-22 2020-09-01 2019-11-26 2020-09-02 2020-05-24 ant Selection projet nagement, Coordination and Advocacy ZR-DRC-MSP-117896-CS-IND Component 4: Institutional C Individual Consult V / Recrutement de deux co / apacity Building, Project Ma Prior Open 400,000.00 0.00 Canceled 2019-08-13 2019-10-01 2019-10-22 2019-11-26 2020-05-24 ant Selection mptables pour la gestion du nagement, Coordination and projet Advocacy ZR-DRC-MSP-118016-CS-IND Component 4: Institutional C Individual Consult V / Recrutement d'un Assista / apacity Building, Project Ma Prior Open 250,000.00 0.00 Canceled 2019-07-30 2019-09-17 2019-10-08 2019-11-12 2020-05-10 ant Selection nt Technique en Santé Huma nagement, Coordination and ine Advocacy ZR-DRC-MSP-118017-CS-IND Component 4: Institutional C Individual Consult V / Recrutement d'un Assista / apacity Building, Project Ma Prior Open 250,000.00 0.00 Canceled 2019-07-30 2019-09-17 2019-10-08 2019-11-12 2020-05-10 ant Selection nt Technique en Santé anima nagement, Coordination and le Advocacy ZR-DRC-MSP-118019-CS-IND Component 4: Institutional C Individual Consult V / Recrutement d'un Assista / apacity Building, Project Ma Prior Open 250,000.00 0.00 Canceled 2019-07-30 2019-09-17 2019-10-08 2019-11-12 2020-05-10 ant Selection nt Technique en Santé végét nagement, Coordination and ale Advocacy ZR-DRC-MSP-118021-CS-IND Component 4: Institutional C V / Recrutement d'un Assista apacity Building, Project Ma Individual Consult Pending Impleme / Prior Open 250,000.00 0.00 2019-07-30 2019-09-17 2019-10-08 2019-11-12 2020-05-10 nt Technique en sauvegarde nagement, Coordination and ant Selection ntation environnementale et sociale Advocacy ZR-DRC-MSP-184520-CS-IND Component 1: Strengthenin V / Recrutement de consulta g Surveillance and Laborato Individual Consult IDA / D5160 Post Open 60,000.00 0.00 Canceled 2021-06-16 2021-08-04 2021-08-25 2021-09-29 2022-03-28 nt pour élaborer le Cadre de ry Capacity to Rapidly detec ant Selection planification des Peuples Aut t Outbreaks ochtone ZR-DRC-MSP-184521-CS-IND Component 1: Strengthenin V / Recrutement de consulta g Surveillance and Laborato Individual Consult IDA / D5160 Post Open 60,000.00 0.00 Canceled 2021-06-16 2021-08-04 2021-08-25 2021-09-29 2022-03-28 nts pour élaborer les plans d ry Capacity to Rapidly detec ant Selection e Gestion Environnementale t Outbreaks et Sociale ZR-DRC-MSP-184524-CS-IND Component 1: Strengthenin V / Recrutement de consulta g Surveillance and Laborato Individual Consult IDA / D5160 Post Open 60,000.00 0.00 Canceled 2021-06-16 2021-08-04 2021-08-25 2021-09-29 2022-03-28 nts pour élaborer les plans d’ ry Capacity to Rapidly detec ant Selection engagement des Parties Pre t Outbreaks nantes Page 11 ZR-DRC-MSP-184526-CS-IND V / Recruter un Consultant in Component 1: Strengthenin ternational pour la conceptio g Surveillance and Laborato Individual Consult IDA / D5160 Post Open 30,000.00 0.00 Canceled 2020-08-10 2020-09-28 2020-10-19 2020-11-23 2021-05-22 n et la mise en place des sys ry Capacity to Rapidly detec ant Selection tèmes électroniques de surv t Outbreaks eillance interopérable dans l e cadre de « Une Santé » ZR-DRC-MSP-184532-CS-IND Component 1: Strengthenin V / Recruter un consultant po g Surveillance and Laborato Individual Consult IDA / D5160 Post Open 13,140.00 0.00 Canceled 2020-08-02 2020-09-20 2020-10-11 2020-11-15 2021-05-14 ur réaliser l'évaluation conjoi ry Capacity to Rapidly detec ant Selection nte des risques liés aux PZD t Outbreaks (Grippe Aviaire) ZR-DRC-MSP-184535-CS-IND V / Recrutement d'un consult Component 1: Strengthenin ant national senior pour l'éla g Surveillance and Laborato Individual Consult IDA / D5160 Post Open 17,720.00 0.00 Canceled 2020-10-04 2020-11-22 2020-12-13 2021-01-17 2021-07-16 boration du plan national d'e ry Capacity to Rapidly detec ant Selection nvoi, de réception, de stocka t Outbreaks ge et de déploiement des m oyens médicaux ZR-DRC-MSP-184536-CS-IND V / Recrutement d'un consult Component 1: Strengthenin ant national senior pour l'éla g Surveillance and Laborato Individual Consult IDA / D5160 Post Open 17,720.00 0.00 Canceled 2020-09-04 2020-10-23 2020-11-13 2020-12-18 2021-06-16 boration du plan national rel ry Capacity to Rapidly detec ant Selection atif au déploiement du perso t Outbreaks nnel en situation d’urgence d e santé publique ZR-DRC-MSP-184537-CS-IND Component 1: Strengthenin V / Recrutement d'un consult g Surveillance and Laborato Individual Consult ant national pour élaborer le IDA / D5160 Post Open 10,000.00 0.00 Canceled 2020-08-02 2020-09-20 2020-10-11 2020-11-15 2021-05-14 ry Capacity to Rapidly detec ant Selection plan Stratégique National Mu t Outbreaks ltisectoriel de communicatio n des risques ZR-DRC-MSP-184540-CS-IND Component 1: Strengthenin V / Recruter un consultant na g Surveillance and Laborato Individual Consult IDA / D5160 Post Open 6,800.00 0.00 Canceled 2020-08-31 2020-10-19 2020-11-09 2020-12-14 2021-06-12 tional pour l'utilisation et l'im ry Capacity to Rapidly detec ant Selection plémentation de l'outil EMAI t Outbreaks ZR-DRC-MSP-199268-CS-IND Component 4: Institutional C Individual Consult V / Sélection et recrutement IDA / 64980 apacity Building, Project Ma Prior Open 337,500.00 0.00 Canceled 2020-12-23 2021-02-10 2021-03-03 2021-04-07 2021-10-04 ant Selection d’un Spécialiste en Santé ani nagement, Coordination and male Advocacy ZR-DRC-MSP-199270-CS-IND Component 4: Institutional C Individual Consult Under Implement V / Sélection et recrutement IDA / 64980 apacity Building, Project Ma Prior Open 337,500.00 0.00 2020-12-23 2021-06-15 2021-02-10 2021-03-03 2021-04-07 2021-10-04 ant Selection ation d’un Spécialiste en Epidémiol nagement, Coordination and ogie Advocacy ZR-DRC-MSP-199274-CS-IND V / Sélection et Recrutement d'un (1) Ingénieur conseil ch Component 4: Institutional C argé du contrôle et de la sur apacity Building, Project Ma Individual Consult IDA / 64980 Post Open 50,000.00 0.00 Canceled 2020-12-23 2021-02-10 2021-03-03 2021-04-07 2021-10-04 veillance des travaux de con nagement, Coordination and ant Selection struction/ réhabilitation dont Advocacy le démarrage est envisagé d ans le cadre de la mise en œ uvre du Projet pour l'an 2020 . ZR-DRC-MSP-209292-CS-IND V / Sélection et recrutement Component 4: Institutional C d'un consultant international apacity Building, Project Ma Individual Consult IDA / 64980 Post Open 30,000.00 0.00 Canceled 2020-12-23 2021-07-07 2021-02-10 2021-03-03 2021-04-07 2021-10-04 pour l'élaboration des protoc nagement, Coordination and ant Selection oles pour la gestion des urge Advocacy nces en lien avec MVE, COVI D, Rougéole et Choléra ZR-DRC-MSP-209294-CS-IND V / Sélection et recrutement Component 4: Institutional C d'un consultant national pour apacity Building, Project Ma Individual Consult IDA / 64980 Post Open 20,000.00 0.00 Canceled 2020-12-23 2021-02-10 2021-03-03 2021-04-07 2021-10-04 l'élaboration des protocoles nagement, Coordination and ant Selection pour la gestion des urgences Advocacy en lien avec MVE, COVID, Ro ugéole et Choléra ZR-DRC-MSP-218040-CS-CD S / Contractualisation par ent Component 2: Strengthenin ente directe avec l'OMS pour g Emergency Planning and IDA / 64980 Prior Direct Selection Direct 8,000,000.00 3,451,230.60 Signed 2021-03-17 2021-11-26 2021-03-27 2021-08-12 2021-05-31 2022-01-10 2021-11-27 l'appui au plan de 90 jours et Management Capacity to Ra renforcement des activités p pidly respond to Outbreaks ost Ebola à l'Equateur et Pro vinces voisines ZR-DRC-MSP-218043-CS-CD S / Contractualisation par ent Component 2: Strengthenin ente directe avec OIM pour l' g Emergency Planning and IDA / 64980 Prior Direct Selection Direct 2,000,000.00 0.00 Canceled 2021-03-24 2021-04-03 2021-06-07 2021-12-04 appui au plan de 90 jours et Management Capacity to Ra renforcement des activités p pidly respond to Outbreaks ost Ebola à l'Equateur et Pro vinces voisines ZR-DRC-MSP-227756-CS-IND V / Recrutement d'un consult Component 1: Strengthenin ant chargé d’appuyer le PDS g Surveillance and Laborato Individual Consult S dans l’élaboration du dossi IDA / 64980 Post Limited 7,000.00 0.00 Canceled 2021-04-29 2021-04-05 2021-05-04 2021-05-25 2021-06-29 2021-12-26 ry Capacity to Rapidly detec ant Selection er technique et du devis des t Outbreaks travaux de réaménagement de l’Entrepôt Central du Mini stère de la Santé ZR-DRC-MSP-232228-CS-CD S / Contractualisation par Ent ente Directe avec CRESTE Bu Component 1: Strengthenin reau d'Etudes chargé de la V g Surveillance and Laborato alidation du Rapport de missi IDA / 64990 Post Direct Selection Direct 200,000.00 258,420.00 Signed 2021-05-27 2021-05-04 2021-06-06 2021-05-10 2021-08-10 2021-05-15 2022-02-06 ry Capacity to Rapidly detec on de l'Ingénieur Jean-Paul M t Outbreaks AKOMA INRB, Elaboration du DAO et du Contrôle et Survei llance des travaux de réhabil itation du Laboratoire de Bun ia ZR-DRC-MSP-232790-CS-IND V / Contractualisation en ent Component 1: Strengthenin ente directe avec Monsieur g Surveillance and Laborato Individual Consult IDA / 64980 Post Direct 116,200.00 116,200.00 Signed 2021-05-27 2021-05-18 2021-06-06 2020-09-25 2021-06-27 2020-09-28 2021-08-01 2020-10-02 2022-01-28 AHLEGNAN KOMLAN Victor, c ry Capacity to Rapidly detec ant Selection onsultant spécialiste en gesti t Outbreaks on financière en appui au Pro jet REDISSE ZR-DRC-MSP-232061-CS-IND Component 1: Strengthenin V / Contractualisation par ent g Surveillance and Laborato Individual Consult IDA / 64980 Post Direct 53,400.00 53,400.00 Signed 2021-05-27 2021-05-18 2021-06-06 2020-09-21 2021-06-27 2020-09-22 2021-08-01 2020-09-25 2022-01-28 ente directe avec Monsieur D ry Capacity to Rapidly detec ant Selection imitri MATUTEZULWA LUBOK t Outbreaks OLO ZR-DRC-MSP-232064-CS-IND Component 1: Strengthenin V / Contractualisation par ent g Surveillance and Laborato Individual Consult ente directe avec Monsieur C IDA / 64980 Post Direct 36,822.50 36,822.50 Signed 2021-05-31 2021-05-18 2021-06-10 2021-10-19 2021-07-01 2021-02-03 2021-08-05 2021-02-04 2022-02-01 ry Capacity to Rapidly detec ant Selection amille BAMONEKENE WASUK t Outbreaks AMA, Comptable en appui au Projet REDISSE IV ZR-DRC-MSP-235192-CS-CD S / Contractualisation par ent ente directe (ED) avec la Fir Component 1: Strengthenin me United States Pharmacop g Surveillance and Laborato eia (USP) pour appuyer l'UG IDA / 64980 Post Direct Selection Direct 70,000.00 0.00 Canceled 2021-06-24 2021-06-05 2021-07-04 2021-10-20 2021-09-07 2022-03-06 ry Capacity to Rapidly detec PDSS dans l'établissement d t Outbreaks e l'état des lieux, l'élaboratio n du dossier technique et du devis des travaux de réamén agement des Laboratoires ZR-DRC-MSP-256330-CS-CD S / Contractualisation par ent ente directe (ED) avec la Fir Component 1: Strengthenin me United States Pharmacop g Surveillance and Laborato Under Implement eia (USP) pour appuyer l'UG IDA / 64980 Post Direct Selection Direct 434,222.00 0.00 2021-10-20 2021-10-04 2021-10-30 2022-01-03 2022-07-02 ry Capacity to Rapidly detec ation PDSS dans l'établissement d t Outbreaks e l'état des lieux, l'élaboratio n du dossier technique et du devis des travaux de réamén agement des Laboratoires ZR-DRC-MSP-218042-CS-CD S / Contractualisation par ent Component 2: Strengthenin ente avec UNICEF, appui au g Emergency Planning and IDA / 64980 Prior Direct Selection Direct 4,000,000.00 0.00 Canceled 2021-03-23 2021-04-02 2021-06-06 2021-12-03 plan de 90 jours et renforce Management Capacity to Ra ment des activités post Ebol pidly respond to Outbreaks a à l'Equateur et Provinces v oisines ZR-DRC-MSP-263380-CS-IND V / Recrutement d’un spécial Component 4: Institutional C iste en développement social apacity Building, Project Ma Individual Consult Under Implement IDA / 64980 Post Limited 57,600.00 0.00 2022-01-20 2021-11-30 2022-01-25 2022-02-15 2022-03-22 2022-09-18 appelé à prester pour le Proj nagement, Coordination and ant Selection ation et de Renforcement des syst Advocacy èmes de surveillance des ma ladies en Afrique Centrale Page 12 ZR-DRC-MSP-263706-CS-CD S / Contractualisation par Ent Component 4: Institutional C ente Directe avec Mr Theodo apacity Building, Project Ma Under Implement re KAZADI KASHISHI Consult IDA / 64980 Post Direct Selection Direct 60,000.00 0.00 2022-01-20 2021-12-04 2022-01-30 2022-04-05 2022-10-02 nagement, Coordination and ation ant chargé du Contrôle des t Advocacy ravaux de Désamiantage à E ntrepôt Central de Mama Ye mo. ZR-DRC-MSP-118014-CS-IND Component 4: Institutional C Individual Consult V / Recrutement d'un Spécial / apacity Building, Project Ma Prior Open 300,000.00 0.00 Canceled 2019-07-30 2021-03-01 2019-09-17 2019-10-08 2019-11-12 2020-05-10 ant Selection iste en Passation des Marché nagement, Coordination and s Advocacy ZR-DRC-MSP-228866-CS-CD Component 1: Strengthenin S / Contractualisation par ent g Surveillance and Laborato ente directe avec Monsieur C IDA / 64980 Post Direct Selection Direct 147,290.00 0.00 Canceled 2021-04-30 2021-05-10 2021-07-14 2022-01-10 ry Capacity to Rapidly detec amille BAMONEKENE WASUK t Outbreaks AMA, Comptable en appui au Projet REDISSE IV ZR-DRC-MSP-235192-CS-CD S-2 / Contractualisation par d irecte (ED) avec la Firme Uni Component 1: Strengthenin ted States Pharmacopeia (US g Surveillance and Laborato Pending Impleme P) pour l'entente de soutien IDA / 64980 Post Direct Selection Direct 434,222.00 0.00 2022-03-30 2022-04-09 2022-06-13 2022-12-10 ry Capacity to Rapidly detec ntation à l'UG PDSS dans l'établisse t Outbreaks ment de l'état des lieux, l'éla boration du dossier techniqu e et du devis des travaux de réaménagement des Laborat oires ZR-DRC-MSP-289453-CS-IND Component 1: Strengthenin V / Contractualisation par Ent g Surveillance and Laborato Individual Consult Under Implement ente Directe avec le Spéciali IDA / D5160 Post Direct 70,000.00 0.00 2022-04-08 2022-04-18 2022-04-21 2022-05-17 2023-05-12 ry Capacity to Rapidly detec ant Selection ation ste en Passation des Marché t Outbreaks s Mr. Adelard KUMBU KUMBU ZR-DRC-MSP-287587-CS-CD S / Contractualisation par ED avec UNFPA pour appui des Component 1: Strengthenin projets PDSS, PMNS, REDISS g Surveillance and Laborato Under Implement IDA / D5160 Prior Direct Selection Direct 20,000,000.00 0.00 2022-04-11 2022-04-19 2022-04-21 2022-05-30 2022-06-25 2023-12-17 E IV et COVID 19 pour attenu ry Capacity to Rapidly detec ation ation et réponses aux risque t Outbreaks s de EAS/HS liés à la mise en Oeuvre dans les zones d'inte rvention de ces projets ZR-DRC-MSP-273072-CS-CD S / Contractualisation par ent ente directe avec UNFPA pou Component 2: Strengthenin r appuiyer les projets PDSS P g Emergency Planning and IDA / 64980 Prior Direct Selection Direct 10,000,000.00 0.00 Canceled 2022-02-24 2022-03-06 2022-05-10 2022-11-06 MNS REDISSE IV et COVID 19 Management Capacity to Ra financement add.BM par pre pidly respond to Outbreaks vention , attenuation aux ris que l'EAS/HS lié à la mise en oeuvre des Opérations ZR-DRC-MSP-301462-CS-IND Component 1: Strengthenin V / Contractualisation par Ent g Surveillance and Laborato Individual Consult Pending Impleme ente Directe avec le Spéciali IDA / D5160 Post Direct 64,200.00 0.00 2022-07-01 2022-07-11 2022-07-14 2022-08-09 2023-08-04 ry Capacity to Rapidly detec ant Selection ntation ste en Suivi Evaluation Mr M t Outbreaks UISHA BAROKI Derrick ZR-DRC-MSP-305224-CS-CD S / Contractualisation par Ent ente directe avec le consulta Component 4: Institutional C nt individuel Mr Bruno BOLEK apacity Building, Project Ma IDA / 64980 Post Direct Selection Direct - National 95,000.00 0.00 Canceled 2022-07-21 2022-07-29 2022-07-31 2022-08-03 2022-10-04 2023-04-02 YMO pour la préparation du nagement, Coordination and plan d'action du peuple auto Advocacy chtone dans les zones de san té de WANGATA, BOLENGE e t MBANDAKA ZR-DRC-MSP-309077-CS-IND Component 1: Strengthenin V / Contractualisation par Ent g Surveillance and Laborato Individual Consult Under Implement ente Directe avec le Project IDA / D5160 Post Direct - National 90,000.00 0.00 2022-08-22 2022-08-17 2022-09-01 2022-09-22 2022-10-27 2023-10-22 ry Capacity to Rapidly detec ant Selection ation Manager de Projet REDISSE I t Outbreaks V Dr Baudouin MAKUMA BOO TO ZR-DRC-MSP-324810-CS-CD S / Contractualisation par Ent Component 1: Strengthenin ente Directe avec OIM pour l g Surveillance and Laborato Direct - Internation e renforcement des capacité IDA / D5160 Prior Direct Selection 21,677,602.00 0.00 Signed 2022-11-02 2022-11-08 2022-11-12 2022-06-16 2022-12-31 2024-06-23 ry Capacity to Rapidly detec al s des 18 Points d'Entrée (PoE t Outbreaks ) désignés et sites sentinelle s pour appuyer REDISSE IV s ous Financement Banque Mo ndiale. ZR-DRC-MSP-295886-CS-CD S / Contractualisation en Ent ente Directe (ED) avec l’Orga Component 1: Strengthenin nisation Internationale pour l g Surveillance and Laborato es Migrations (OIM) pour le r IDA / D5160 Prior Direct Selection Direct 16,000,000.00 0.00 Canceled 2022-05-30 2022-06-22 2022-06-09 2022-06-16 2022-07-28 2023-07-23 ry Capacity to Rapidly detec enforcement des capacités d t Outbreaks es 18 Points d’Entrée (PoE) d ésignés et sites sentinelles p our appuyer le projet REDISS E IV sous le financement BM ZR-DRC-MSP-263377-CS-IND V / Recrutement d’un spécial Component 4: Institutional C iste en sauvegarde environn apacity Building, Project Ma Individual Consult ementale appelé à prester p IDA / 64980 Post Limited 57,600.00 0.00 Canceled 2022-01-12 2021-11-24 2022-01-17 2022-02-07 2022-03-14 2022-09-10 nagement, Coordination and ant Selection our le Projet de Renforcemen Advocacy t des systèmes de surveillan ce des maladies en Afrique C entrale ZR-DRC-MSP-184519-CS-IND Component 1: Strengthenin V / Recrutement de consulta g Surveillance and Laborato Individual Consult IDA / D5160 Post Open 60,000.00 0.00 Canceled 2021-06-16 2021-08-04 2021-08-25 2021-09-29 2022-03-28 nt pour élaborer le Cadre de ry Capacity to Rapidly detec ant Selection Réinsertion des Populations t Outbreaks ZR-DRC-MSP-199247-CS-IND V / Sélection et recrutement Component 1: Strengthenin d'un (1) consultant internatio g Surveillance and Laborato Individual Consult IDA / 64980 Post Open 50,000.00 0.00 Canceled 2020-12-24 2021-02-11 2021-03-04 2021-04-08 2021-10-05 nal et deux (2) consultants n ry Capacity to Rapidly detec ant Selection ationaux pour réaliser l'évalu t Outbreaks ation conjointe des risques li és aux pandémies zoonotiqu es. ZR-DRC-MSP-199265-CS-IND Component 4: Institutional C Individual Consult V / Sélection et recrutement IDA / 64980 apacity Building, Project Ma Prior Open 375,000.00 0.00 Canceled 2020-12-23 2020-12-23 2021-02-10 2021-06-22 2021-03-03 2021-04-07 2021-10-04 ant Selection d’un Spécialiste en Suivi- Eva nagement, Coordination and luation Advocacy ZR-DRC-MSP-301456-CS-IND Component 1: Strengthenin V / Recrutement d'un Consult g Surveillance and Laborato Individual Consult ant Individuel pour l'Elaborati IDA / D5160 Post Open 70,000.00 0.00 Canceled 2022-07-11 2022-08-06 2022-08-27 2022-09-27 2022-11-26 ry Capacity to Rapidly detec ant Selection on du plan en faveur des pop t Outbreaks ulations des peuples autocht ones (PPA) ZR-DRC-MSP-184533-CS-IND Component 1: Strengthenin V / Recrutement de 2 consult g Surveillance and Laborato Individual Consult IDA / D5160 Post Open 20,000.00 0.00 Canceled 2020-08-16 2020-10-04 2020-10-25 2020-11-29 2021-05-28 ants nationaux pour la forma ry Capacity to Rapidly detec ant Selection tion en biosécurité t Outbreaks ZR-DRC-MSP-263383-CS-IND V / Contractualisation par Ent ente Directe avec Mme ANIN Component 4: Institutional C A MITULO consultant chargé apacity Building, Project Ma Individual Consult de la mise en œuvre du rapp IDA / 64980 Post Direct 7,000.00 0.00 Canceled 2022-01-27 2021-11-24 2022-02-06 2022-02-27 2022-04-03 2022-09-30 nagement, Coordination and ant Selection ort d’évaluation des pertes é Advocacy conomiques des travaux de r éhabilitation du laboratoire médical de référence provinc ial de Bunia (Province de l’Itu ri) ZR-DRC-MSP-117897-CS-IND Component 4: Institutional C Individual Consult V / Recrutement d'un respon / apacity Building, Project Ma Prior Open 300,000.00 0.00 Canceled 2019-08-13 2019-10-01 2019-10-22 2019-11-26 2020-05-24 ant Selection sable en suivi et évaluation d nagement, Coordination and u projet Advocacy ZR-DRC-MSP-184531-CS-IND V / Recruter un consultant na Component 1: Strengthenin tional pour développer un gu g Surveillance and Laborato Individual Consult ide standard pour réaliser un IDA / D5160 Post Open 7,870.00 0.00 Canceled 2020-08-20 2021-03-04 2020-10-08 2020-10-29 2020-12-03 2021-06-01 ry Capacity to Rapidly detec ant Selection état des lieux des textes juri t Outbreaks diques et reglémentaires pou r la mise en œuvre du RSI (2 005) Page 13 ZR-DRC-MSP-239895-CS-IND V / Contractualisation par ent ente directe avec Monsieur K Component 1: Strengthenin AYINDU KALUMBA Jean-Bienv g Surveillance and Laborato Individual Consult enu, consultant chargé de la IDA / 64980 Post Direct 14,000.00 0.00 Canceled 2021-07-22 2021-08-09 2021-08-01 2021-08-22 2021-09-26 2022-03-25 ry Capacity to Rapidly detec ant Selection réalisation d'un plan de gesti t Outbreaks on environnementale et soci ale (PGES) et d'un plan d'hyg iène, santé et sécurité (PHSS ) des travaux de réhabilitatio n ZR-DRC-MSP-327472-CS-IND Component 1: Strengthenin V / Contractualisation par Ent g Surveillance and Laborato Individual Consult Pending Impleme IDA / D5160 Post Direct - National 19,560.00 0.00 2022-11-21 2022-11-29 2022-12-06 2022-12-23 2023-12-18 ente Directe avec l'Assistant ry Capacity to Rapidly detec ant Selection ntation e Trésorière Madame LIZANS t Outbreaks IAFUMU FIFA ZR-DRC-MSP-327478-CS-IND Component 1: Strengthenin V / Contractualisation par Ent g Surveillance and Laborato Individual Consult Direct - Internation Pending Impleme IDA / 64980 Post 120,616.00 0.00 2022-11-21 2022-12-01 2022-12-08 2022-12-25 2023-12-20 ente Directe avec Monsieur ry Capacity to Rapidly detec ant Selection al ntation AHLEGNAN KOMLAN, Expert t Outbreaks en Finances ZR-DRC-MSP-320887-CS-CD S / Contractualisation par ED avec USP pour appuyer l'UG Component 1: Strengthenin PDSS dans la surveillance de g Surveillance and Laborato Direct - Internation Pending Impleme s Travaux de Réhabilitation d IDA / D5160 Post Direct Selection 300,000.00 0.00 2022-10-17 2022-10-27 2022-12-31 2023-06-29 ry Capacity to Rapidly detec al ntation es Labo d'analyses microbio t Outbreaks et dispositifs médicaux, de l' accompagnement technique ainsi que de la formation du personnel du LNCQ LAPHAKI ZR-DRC-MSP-335548-CS-IND V / Recrutement des Consult Component 1: Strengthenin ants pour Analyse et évaluati g Surveillance and Laborato Individual Consult Pending Impleme IDA / 64980 Post Limited 30,000.00 0.00 2023-01-31 2023-02-05 2023-02-26 2023-04-02 2023-09-29 on des documents de Passati ry Capacity to Rapidly detec ant Selection ntation on des Marchés pour Constru t Outbreaks ction des 7 Laboratoires du MSP ZR-DRC-MSP-341423-CS-IND V / Recrutement d'un Ingénie Component 1: Strengthenin ur en Génie Civil pour traite g Surveillance and Laborato Individual Consult Pending Impleme IDA / D5160 Post Limited 30,000.00 0.00 2023-02-13 2023-02-18 2023-03-11 2023-04-15 2023-10-12 ment du Dossier d'Appel d'Of ry Capacity to Rapidly detec ant Selection ntation fres et autres documents po t Outbreaks ur les Travaux de Constructi on de 7 laboratoires ZR-DRC-MSP-346694-CS-CD S / Contractualisation par Ent Component 4: Institutional C ente Directe avec Mr Claude apacity Building, Project Ma Direct - Internation IDA / 64980 Post Direct Selection 126,130.00 0.00 Signed 2023-03-06 2023-03-03 2023-03-16 2023-03-20 2023-04-27 2023-10-24 OGOU, Assistant Technique I nagement, Coordination and al nternational en Passation de Advocacy s Marchés pour Appuyer l'UG PDSS ZR-DRC-MSP-349989-CS-IND V / Recrutement d'un Consult Component 1: Strengthenin ant Individuel pour l'Elaborati g Surveillance and Laborato Individual Consult Under Implement on des Plans de Gestion Envi IDA / D5160 Post Limited 30,000.00 0.00 2023-03-23 2023-03-20 2023-03-28 2023-04-04 2023-05-09 2023-08-07 ry Capacity to Rapidly detec ant Selection ation ronnementale et Sociale des t Outbreaks Travaux de Réhabilitation de V2 Laboratoires Vétérinaire e t Environnemental de Kinsha sa. ZR-DRC-MSP-349991-CS-IND V / Recrutement d'un Consult ant Individuel pour l'Elaborati Component 1: Strengthenin on des Plans de Gestion Envi g Surveillance and Laborato Individual Consult Pending Impleme ronnementale et Sociale des IDA / D5160 Post Limited 60,000.00 0.00 2023-03-22 2023-03-29 2023-04-05 2023-04-22 2023-07-21 ry Capacity to Rapidly detec ant Selection ntation Travaux de Réhabilitation de t Outbreaks 5 Laboratoires de 4 Hôpitau x Généraux de Référence: Ba ndundu - Ville, Mosango, Kik wit Nord, Gungu et Idiofa ZR-DRC-MSP-350004-CS-IND Component 4: Institutional C V / Renouvellement du Contr apacity Building, Project Ma Individual Consult Pending Impleme at Pour Mr Adélard KUMBU K IDA / D5160 Post Direct - National 87,360.00 0.00 2023-04-05 2023-04-15 2023-04-18 2023-04-24 2024-04-18 nagement, Coordination and ant Selection ntation UMBU Spécialiste en Passati Advocacy on des Marchés de REDISSE I V au sein de l'UG - PDSS ZR-DRC-MSP-350188-CS-IND Component 4: Institutional C V / Renouvellement du Contr apacity Building, Project Ma Individual Consult Pending Impleme at pour Mr Derrick BAROKI S IDA / D5160 Post Direct - National 82,500.00 0.00 2023-03-31 2023-04-10 2023-04-17 2023-04-23 2024-04-17 nagement, Coordination and ant Selection ntation pécialiste en Suivi Evaluation Advocacy REDISSE IV - UG PDSS ZR-DRC-MSP-360618-CS-CD S / Contractualisation par ED avec BALEINE ENVIRONNEME Component 1: Strengthenin NT SARL pour la mission d'El g Surveillance and Laborato aboration de 02 rapports d'ét IDA / D5160 Post Direct Selection Direct - National 126,590.00 0.00 Signed 2023-05-22 2023-05-09 2023-06-03 2023-05-24 2023-06-22 2023-08-21 ry Capacity to Rapidly detec udes d'Impact Environnemen t Outbreaks tal et Social (EIES) pour la Co nstruction des Labo Provincia ux de SP Kwilu/ Bandundu et TSHOPO/ Kisangani Page 14 PROCUREMENT PLAN (Mandatory Requirements) Project information: Country: Bangladesh Project Name: Accelerating Transport and Trade Connectivity in Eastern South Asia – Bangladesh Phase 1 Project P-number: P176549 Project Implementation agency: (i) Roads and Highways Department (RHD) (ii) National Board of Revenue (NBR) Period covered by this Procurement Plan: Entire Project Period Preamble In accordance with paragraph 5.9 of the World Bank Procurement Regulations for IPF Borrowers, July 2016, revised November 2020 (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to record all procurement actions for the Project, including preparing, updating and clearing its Procurement Plan, and seeking and receiving the Bank’s review and No-objection to procurement actions as required. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents (SPDs) shall be used for goods, works and non- consulting services where international competition is required and for all consulting services, including their respective forms of contract. National Procurement Arrangements: In accordance with paragraph 5.3 of the World Bank Procurement Regulations, when approaching the national market, as agreed in the Procurement Plan, the country’s own procurement procedures may be used. These procurement procedures shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti- Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Act 2006 and the Public Procurement Rules 2008, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: i. Lottery in award of contracts shall not be allowed; ii. Bidders’ qualification[s]/experience requirement[s] shall be mandatory; iii. Bids shall not be rejected based on percentage above or below the estimated cost; iv. Model Bidding Documents agreed with the Bank shall be used for all national open competitive procurement; v. The eligibility of bidders shall be as defined under Section III of the World Bank Procurement Regulations for IPF Borrowers: accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. vi. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. As per paragraph 5.4 of the Procurement Regulations, the “Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework” as attached to this document shall form part of the Model Bidding Documents. Leased Assets: Not Applicable. Procurement of Second Hand Goods: Not Applicable. Domestic preference: as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works) as follows: Goods: Applicable; Works: Not applicable. Hands-on Expanded Implementation Support (HEIS): Not Applicable. Bank’s Procurement Prior Review Thresholds: contracts at or above the thresholds set out in table 1 below are subject to the Bank’s procurement prior review. Table 1: Procurement Prior Review Thresholds (US$ millions) Type of High risk Substantial Moderate Low risk procurement risk risk Works (including 5 10 15 20 turnkey, supply & installation of plant and equipment, and PPP) Goods, information 1.5 2 4 6 technology and non-consulting services Consulting 0.5 1 2 4 services: firms Consulting 0.2 0.3 0.4 0.5 services: Individual Notes: 1. These thresholds apply to all procurement activities regardless of their procurement/selection methods. There is no automatic requirement to undertake prior review for direct selection for value less than these thresholds. Consultant services covers a range of services that are of an advisory or professional nature. 2. In addition to the provisions of Table 1 above, and irrespective of the contract value, the following procurement activities are subject to the Bank’s procurement prior review: (a) procurement processes involving contract negotiations, as described in Section VI, paragraphs 6.34-36, of the Procurement Regulations; (b) competitive dialogue; (c) sustainable procurement; (d) selection of probity assurance providers, as described in Section III, paragraph 3.3 of the Procurement Regulations; and (e) best and final offer. 3. The determination of whether a contract meets the procurement prior review threshold is based on the estimated value of the contract or the package -when the selection document contains more than one lot/slice- , including all taxes and duties payable under the contract. Attachment 1 Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: PROCUREMENT Bangladesh : Accelerating Transport and Trade Connectivity in Eastern South Asia – Bangladesh Phase 1 Project PLAN General Information Country: Bangladesh Bank’s Approval Date of the Original Procurement Plan: 2023-05-16 Revised Plan Date(s): (comma delineated, leave blank if 2023-05-29 none) Project ID: P176549 GPN Date: 2023-03-14 Project Name: Accelerating Transport and Trade Connectivity in Eastern South Asia – Bangladesh Phase 1 Project Loan / Credit No: IDA / 71660 Roads and Highways Department Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BD-RHD-349374-CS-QCBS / Hiring of Consulting Services Green and Resilient Transpo Quality And Cost- Pending Impleme IDA / 71660 Post Open - National 151,386.00 0.00 2023-04-16 2023-05-07 2023-06-20 2023-07-18 2023-08-17 2023-09-21 2023-10-26 2024-10-25 for updating designs and saf rt and Trade Infrastructure Based Selection ntation eguard documents INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BD-RHD-349377-CS-INDV / H Green and Resilient Transpo Individual Consult Under Implement iring of Individual Consulting IDA / 71660 Post Open - National 232,713.00 0.00 2023-04-16 2023-05-17 2023-06-04 2023-06-25 2023-07-30 2024-01-26 rt and Trade Infrastructure ant Selection ation Services for Financial Manag ement expert BD-RHD-349370-CS-INDV / H iring of Individual Consultant Green and Resilient Transpo Individual Consult Under Implement Service as Procurement / Con IDA / 71660 Prior Open - National 131,000.00 0.00 2023-05-22 2023-06-04 2023-07-10 2023-07-31 2023-09-04 2024-03-02 rt and Trade Infrastructure ant Selection ation tract Specialist (National) for Sylhet-Charkhai-Sheola High way Improvement Project Page 1 Formulaire N°9 : PLAN DE PASSATION DE MARCHÉS (Texte) Information sur le Projet : Comores Projet de relèvement post- Kenneth et de résilience No d’identification du projet : P171361 Agence d’exécution du Projet : Ministère de l’Aménagement du Territoire, de l’Urbanisme en charge des Affaires Foncières et Transports Terrestres Date du plan de passation des marchés : 10 novembre 2019 Période couverte par ce plan de passation des marchés : 01 janvier 2020, 02 juin 2021 Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016) (“Règlement de Passation des Marchés”) le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marché se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus de STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées A discuter ultérieurement Ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : Indiquer la liste des conditions requises pour assurer la cohérence avec le paragraphe 5.4 du Règlement de passation des marchés. Si aucune condition s’applique, supprimer la mention « et aux conditions suivantes ». Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas pour les contrats indiqués dans les tableaux du Plan de passation des marchés] Travaux ne s’applique pas pour les contrats indiqués dans les tableaux du Plan de passation des marchés Autres informations pertinentes sur la passation des marchés Néant PROCUREMENT Comoros : Comoros Post-Kenneth Recovery and Resilience Project PLAN General Information Country: Comoros 2020-05-13 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171361 GPN Date: Project Name: Comoros Post-Kenneth Recovery and Resilience Project Loan / Credit No: IDA / D5490, IDA / 65290 Ministère de l'Amenagement du Territoire et de l'Urbanisme Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure 2021-017-AMEN-DATUH-UGP Component 1: Recovery and ment Document - Request for Quota Single Stage - One E 2021-08-2 -PRPKR / Réhabilitation des b IDA / D5490 Resilience in the Housing Se Post Limited 1 Envelope proce 3,497.00 6,222.44 Signed 2021-06-14 2021-06-17 2021-07-29 2021-07-29 tions nvelope 8 ureaux de la cellule cartogra ctor ss (Non Bank-SPD phie, DATUH. ) 2021-019-EXTENSION-UGP-P National Procure RPKR / TRAVAUX D’EXTENSIO Component 4: Project Manag ment Document - Single Stage - One E 2022-03-2 N DES BUREAUX ADMINISTRA IDA / D5490 ement, Risk Management, M Post Request for Bids Limited 1 Envelope proce 58,000.00 58,916.50 Signed 2021-07-12 2021-08-12 2021-07-17 2021-10-07 2021-08-21 2021-08-27 2021-09-06 2021-10-08 2021-09-28 2021-10-30 nvelope 7 TIFS DE L’UNITE DE GESTION onitoring and Evaluation ss (Non Bank-SPD DU PROJET DE RELEVEMENT ) POST - KENNETH 2022-035-INFRA.M-UGP-PRP RR / LOT1.M Réhabilitation d National Procure es deux (2) salles de classe y Component 1: Recovery and ment Document - Single Stage - One E 2022-09-2 compris latrines pour la locali IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 5,463,214.00 42,993.41 Signed 2022-02-11 2022-02-22 2022-03-28 2022-03-23 nvelope 4 té de Bandar Salama et un (1 ctor ss (Non Bank-SPD ) salle de classe y compris lat ) rines et un bassin pour les lo calités de Kangani -Moili. National Procure 2022-036-INFRA.M-UGP-PRP Component 1: Recovery and ment Document - Single Stage - One E 2022-09-2 KR / LOT2.M Construction d’u IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 129,328.88 121,149.95 Signed 2022-02-09 2022-02-14 2022-02-11 2022-02-22 2022-02-28 2022-03-02 2022-03-08 2022-03-12 2022-03-28 2022-03-25 nvelope 4 ne piste rurale à Hamavouna ctor ss (Non Bank-SPD - Moili. ) 2022-037-INFRA.M-UGP-PRP KR / LOT3.M Réhabilitation d National Procure e deux (2) salles de classe y Component 1: Recovery and ment Document - compris bureau, latrines pour Single Stage - One E 2022-09-1 IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 66,525.16 71,024.41 Signed 2022-02-09 2022-02-14 2022-02-11 2022-02-22 2022-02-28 2022-03-02 2022-03-08 2022-03-12 2022-03-22 2022-03-24 la localité Hamba et deux (2) nvelope 8 ctor ss (Non Bank-SPD salles de classe y compris bu ) reau, latrines et bassin de st ockage pour la localité de Nd rodroni-Moili. 2022-038-INFRA.M-UGP-PRP National Procure KR / LOT4.M Réhabilitation d Component 1: Recovery and ment Document - Single Stage - One E 2022-09-2 e deux (2) salles de classe y IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 41,069.61 46,736.48 Signed 2022-02-09 2022-02-14 2022-02-11 2022-03-11 2022-02-28 2022-03-02 2022-03-08 2022-03-12 2022-03-28 2022-03-25 nvelope 4 compris latrines et point d'ea ctor ss (Non Bank-SPD u pour la localité de Mbatse- ) Moili. National Procure 2022-039-INFRA.A-UGP-PRP Component 1: Recovery and ment Document - KR / LOT1.A construction d’u Single Stage - One E 2022-09-2 IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 165,920.72 152,257.91 Signed 2022-02-09 2022-02-17 2022-02-11 2022-03-11 2022-02-28 2022-03-02 2022-03-08 2022-03-14 2022-03-28 2022-03-23 ne piste ruelle de 400 mètre nvelope 4 ctor ss (Non Bank-SPD pour la localité de Dziani-Haj ) oho-ANJOUAN. 2022-040-INFRA.A-UGP-PRP National Procure KR / LOT2.A Réhabilitation de Component 1: Recovery and ment Document - Single Stage - One E 2022-09-2 quatre (4) salles de classe y IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 97,773.27 94,337.30 Signed 2022-02-09 2022-02-14 2022-02-11 2022-03-11 2022-02-28 2022-03-02 2022-03-08 2022-03-15 2022-03-28 2022-03-24 nvelope 4 compris latrines et citerne da ctor ss (Non Bank-SPD ns les localité de Koni-ngani ) et d'Ongoni - Anjouan. 2022-041-INFRA.A-UGP-PRP National Procure KR / LOT3.A Réhabilitation de Component 1: Recovery and ment Document - Single Stage - One E 2022-09-2 quatre (4) salles de classe y IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 99,370.41 0.00 Canceled 2022-02-09 2022-02-17 2022-02-11 2022-03-11 2022-02-28 2022-03-02 2022-03-08 2022-03-28 nvelope 4 compris latrines dans la local ctor ss (Non Bank-SPD ité de Salamani - Anjouan. ) 2022-042-INFRA.A-UGP-PRP National Procure KR / LOT4.A Réhabilitation de Component 1: Recovery and ment Document - Single Stage - One E 2022-09-2 quatre (4) salles de classe y IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 133,900.89 0.00 Canceled 2022-02-09 2022-02-18 2022-02-11 2022-03-11 2022-02-28 2022-03-02 2022-03-08 2022-03-28 nvelope 4 compris latrines et citerne da ctor ss (Non Bank-SPD ns la localité de Kono djodjo - ) Anjouan 2022-043-INFRA.A-UGP-PRP National Procure KR / LOT5.A Réhabilitation de Component 1: Recovery and ment Document - quatre (4) salles de classe y Single Stage - One E 2022-09-2 IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 162,275.41 0.00 Canceled 2022-02-09 2022-02-18 2022-02-11 2022-03-11 2022-02-28 2022-03-02 2022-03-08 2022-03-28 compris latrines et Citerne et nvelope 4 ctor ss (Non Bank-SPD un réservoir communautaire ) dans la localité de Jimlimé - A njouan. 2022-044-INFRA.A-UGP-PRP National Procure KR / LOT6.A Réhabilitation de Component 1: Recovery and ment Document - Single Stage - One E 2022-09-2 quatre (4) salles de classe de IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 80,095.00 67,693.75 Signed 2022-02-09 2022-02-18 2022-02-11 2022-03-11 2022-02-28 2022-03-02 2022-03-08 2022-03-16 2022-03-28 2022-03-24 nvelope 4 l'EPP et de la construction d’ ctor ss (Non Bank-SPD un réservoir dans la localité d ) e Lingoni - Anjouan. 2022-045-INFRA.A-UGP-PRP National Procure KR / LOT7.A Réhabilitation de Component 1: Recovery and ment Document - trois (03) salles de classe de l Single Stage - One E 2022-09-2 IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 96,084.94 80,413.82 Signed 2022-02-09 2022-02-14 2022-02-11 2022-02-22 2022-02-28 2022-03-02 2022-03-08 2022-03-15 2022-03-28 2022-03-24 'EPP de HANTSAHI et d’un (1) nvelope 4 ctor ss (Non Bank-SPD réservoir communautaire da ) ns la localité de HANTSAHI - Anjouan. 2022-046-INFRA.A-UGP-PRP National Procure KR / LOT8.A Réhabilitation de Component 1: Recovery and ment Document - Single Stage - One E 2022-09-2 trois (3) salles de classe de l' IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 62,991.24 49,656.32 Signed 2022-02-09 2022-02-14 2022-02-11 2022-02-22 2022-02-28 2022-03-02 2022-03-08 2022-03-16 2022-03-28 2022-03-24 nvelope 4 EPP et du réservoir communa ctor ss (Non Bank-SPD utaire de la localité de Miron ) gani - Anjouan. National Procure 2022-047-INFRA.A-UGP-PRP Component 1: Recovery and ment Document - KR / LOT9.A Réhabilitation de Single Stage - One E 2022-09-2 IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 125,841.28 128,192.60 Signed 2022-02-09 2022-02-14 2022-02-11 2022-03-11 2022-02-28 2022-03-02 2022-03-08 2022-03-16 2022-03-28 2022-03-23 quatre (4) salles de classe da nvelope 4 ctor ss (Non Bank-SPD ns l’EPP de la localité de Bou ) goueni - Anjouan. Page 1 2022-048-INFRA.N-UGP-PRP KR / LOT1.N Réhabilitation d National Procure u grand réservoir situé à côté Component 1: Recovery and ment Document - de la mosquée des femmes Single Stage - One E 2022-09-2 IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 73,676.28 75,066.64 Signed 2022-02-09 2022-02-14 2022-02-11 2022-02-21 2022-02-28 2022-03-02 2022-03-08 2022-03-22 2022-03-28 2022-03-24 du village de la localité de M nvelope 4 ctor ss (Non Bank-SPD andzissani, d'un (1) réservoir ) dans la localité de Mindradou et d'un (1) réservoir dans la l ocalité de Mlimani - Gde Com ores. 2022-049-INFRA.N-UGP-PRP KR / LOT2.N Réhabilitation de National Procure quatre (4) salles de classes d Component 1: Recovery and ment Document - Single Stage - One E 2022-09-2 ont deux (2) pour maternelle IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 105,068.33 91,669.39 Signed 2022-02-09 2022-02-14 2022-02-11 2022-02-21 2022-02-28 2022-03-02 2022-03-08 2022-03-14 2022-03-28 2022-03-24 nvelope 4 annexe du primaire et deux ( ctor ss (Non Bank-SPD 2) pour l’école communautair ) e de la localité de Tsinimoich ongo - Gde Comore. 2022-050-INFRA.N-UGP-PRP National Procure KR / LOT3.N - Réhabilitation d Component 1: Recovery and ment Document - Single Stage - One E 2022-09-2 'un (1) réservoir situé dans le IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 92,634.05 82,940.66 Signed 2022-02-09 2022-02-14 2022-02-11 2022-02-21 2022-02-28 2022-03-02 2022-03-08 2022-03-14 2022-03-28 2022-03-24 nvelope 4 quartier de Wewouniyadjou ctor ss (Non Bank-SPD NDZOUANI - Gde Comore. ) 2022-052-INFRA.N-UGP-PRP KR / LOT5.N 4 Réhabilitation National Procure de quatre (4) réservoirs d’ea Component 1: Recovery and ment Document - u, Un (1) auvent pour le lycé Single Stage - One E 1,616,225.6 2022-09-2 IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 171,791.11 Signed 2022-02-09 2022-02-14 2022-02-11 2022-02-21 2022-02-28 2022-03-02 2022-03-08 2022-03-22 2022-03-28 2022-03-24 e et collège (même endroit) nvelope 1 4 ctor ss (Non Bank-SPD et deux (2) salles de classes ) maternelle annexes de l’écol e primaire dans la localité de Somboussa -Gde Comore. 2022-053-INFRA.N-UGP-PRP KR / LOT6.N Réhabilitation de National Procure deux (2) salles de classes à l’ Component 1: Recovery and ment Document - Single Stage - One E 2022-09-2 Ecole Primaire Publique de O IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 86,239.80 71,871.31 Signed 2022-02-09 2022-02-21 2022-02-11 2022-02-21 2022-02-28 2022-03-02 2022-03-08 2022-03-16 2022-03-28 2022-03-24 nvelope 4 uemani et d’un (1) réservoir ctor ss (Non Bank-SPD communautaire et la reconst ) ruction d’un (1) autre dans la localité de Pidjanin - Gde Co more. National Procure 2022-054-INFRA.N-UGP-PRP Component 1: Recovery and ment Document - KR / LOT7.N Réhabilitation de Single Stage - One E 2022-09-2 IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 74,731.84 70,073.12 Signed 2022-02-09 2022-02-14 2022-02-11 2022-02-21 2022-02-28 2022-03-02 2022-03-08 2022-03-16 2022-03-28 2022-03-24 s salles de classe de la localit nvelope 4 ctor ss (Non Bank-SPD é d'Ouzio - Gde Comore. ) 2022-055-INFRA.N-UGP-PRP National Procure KR / LOT8.N Réhabilitation d' Component 1: Recovery and ment Document - un (1) réservoir de l’école da Single Stage - One E 2022-09-2 IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 55,463.40 47,906.09 Signed 2022-02-09 2022-02-21 2022-02-11 2022-02-22 2022-02-28 2022-03-02 2022-03-08 2022-03-14 2022-03-28 2022-03-24 ns la localité de Bouni et de d nvelope 4 ctor ss (Non Bank-SPD eux (2) réservoirs communau ) taires de la localité de Bouni - Gde Comore. 2022-056-INFRA.N-UGP-PRP National Procure KR / LOT9.N Réhabilitation d’ Component 1: Recovery and ment Document - Single Stage - One E 2022-09-2 une (1) salle de classe de l'E IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 54,373.88 49,798.57 Signed 2022-02-09 2022-02-21 2022-02-11 2022-02-23 2022-02-28 2022-03-02 2022-03-08 2022-03-14 2022-03-28 2022-03-24 nvelope 4 PP et d’un (1) réservoir com ctor ss (Non Bank-SPD munautaire de la localité de ) Koua Boude - Gde Comore. National Procure 2022-057-INFRA.N-UGP-PRP Component 1: Recovery and ment Document - KR / LOT10.N Réhabilitation d Single Stage - One E 2022-09-2 IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 32,018.32 76,332.38 Signed 2022-02-09 2022-02-21 2022-02-11 2022-02-23 2022-02-28 2022-03-02 2022-03-08 2022-03-14 2022-03-28 2022-03-24 e deux (2) réservoirs de la lo nvelope 4 ctor ss (Non Bank-SPD calité de Mdjoiezi Boude - Gd ) e.Comore. 2022-058-INFRA.N-UGP-PRP National Procure KR / LOT11.N Réhabilitation d Component 1: Recovery and ment Document - e trois (3) salles de classe de Single Stage - One E 2022-09-2 IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 98,279.82 77,169.57 Signed 2022-02-09 2022-02-21 2022-02-11 2022-02-23 2022-02-28 2022-03-02 2022-03-08 2022-03-14 2022-03-28 2022-03-24 l'EPP et de la reconstruction nvelope 4 ctor ss (Non Bank-SPD d’un (1) réservoir de la localit ) é de Helendje Boude - Gde.C omore. 2022-051-INFRA.N-UGP-PRP KR / LOT4.N Réhabilitation de National Procure deux (2) réservoirs un (1) à Component 1: Recovery and ment Document - Single Stage - One E 2022-10-1 coté de la Mosquée de vendr IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 25,533.76 20,760.72 Signed 2022-03-10 2022-02-14 2022-03-12 2022-02-14 2022-03-29 2022-03-02 2022-04-03 2022-03-31 2022-04-18 2022-03-24 nvelope 5 edi ctor ss (Non Bank-SPD et un (1) à coté d’école com ) munautaire de Dzahadjou La mzade - Gde Comore. 2022-060-INFRA.A-UGP-PRP National Procure KR / LOT3.A Réhabilitation de Component 1: Recovery and ment Document - Single Stage - One E 2022-10-3 quatre (4) salles de classe y IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 99,370.41 91,249.59 Signed 2022-03-21 2022-03-21 2022-03-25 2022-03-31 2022-04-11 2022-04-04 2022-04-18 2022-04-18 2022-05-03 2022-04-27 nvelope 1 compris latrines dans la local ctor ss (Non Bank-SPD ité de Salamani - Anjouan. ) 2022-061-INFRA.A-UGP-PRP National Procure KR / LOT4.A Réhabilitation de Component 1: Recovery and ment Document - Single Stage - One E 2022-10-3 quatre (4) salles de classe y IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 13,390.08 112,065.54 Signed 2022-03-21 2022-03-21 2022-03-25 2022-03-31 2022-04-11 2022-04-04 2022-04-18 2022-04-18 2022-05-03 2022-04-27 nvelope 1 compris latrines et citerne da ctor ss (Non Bank-SPD ns la localité de Kono djodjo - ) Anjouan. 2022-062-INFRA.A-UGP-PRP National Procure KR / LOT5.A Réhabilitation de Component 1: Recovery and ment Document - quatre (4) salles de classe y Single Stage - One E 2022-10-3 IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 162,275.40 145,980.49 Signed 2022-03-21 2022-03-21 2022-03-25 2022-03-31 2022-04-11 2022-04-04 2022-04-18 2022-04-19 2022-05-03 2022-04-27 compris latrines et Citerne et nvelope 1 ctor ss (Non Bank-SPD un réservoir communautaire ) dans la localité de Jimlimé - A njouan. 2022-070-TRAVAUX.DGCS-U GP-PRPKR / LOT1.N/DGSC: Co Request for Bids - nstruction d'un bâtiment de Component 1: Recovery and Single Stage - One E Small Works SPD 2023-11-0 15/10/6 dans la localité de Fo IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 163,600.00 0.00 Signed 2022-11-10 2023-02-17 2022-11-15 2023-02-23 2022-12-05 2023-03-09 2022-12-14 2023-03-13 2023-01-10 nvelope (1 envelope proce 9 umbouni dans le cadre des tr ctor ss) avaux pour la construction d es infrastructures de la DGSC par le PRPKR - NGAZIDJA 2022-071-TRAVAUX.DGCS-U GP-PRPKR / LOT1.N.bis/DGSC National Procure : Construction d'une citerne Component 1: Recovery and ment Document - Single Stage - One E 2023-11-0 de 500 m3 dans la localité de IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 183,000.00 0.00 Signed 2022-11-10 2023-02-17 2022-11-15 2023-02-23 2022-12-05 2023-03-09 2022-12-14 2023-04-08 2023-01-10 nvelope 9 Foumbouni dans le cadre des ctor ss (Non Bank-SPD travaux pour la construction ) des infrastructures de la DGS C par le PRPKR - NGAZIDJA Page 2 2022-072-TRAVAUX.DGSC-U GP-PRPKR / LOT2.N/DGCS: Co National Procure nstruction d'un bâtiment de Component 1: Recovery and ment Document - Single Stage - One E 2023-11-0 15/10/6 dans la localité de Mi IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 163,600.00 0.00 Signed 2022-11-10 2023-02-17 2022-11-15 2023-02-23 2022-12-05 2023-03-09 2022-12-14 2023-04-29 2023-01-10 nvelope 9 tsamiouli dans le cadre des tr ctor ss (Non Bank-SPD avaux pour la construction d ) es infrastructures de la DGSC par le PRPKR - NGAZIDJA 2022-073-TRAVAUX.DGCS-U GP-PRPKR / LOT2.N.bis/DGCS National Procure : Construction d'une citerne Component 1: Recovery and ment Document - Single Stage - One E 2023-11-0 de 500 m3 dans la localité de IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 1 Envelope proce 183,000.00 0.00 Signed 2022-11-10 2023-02-17 2022-11-15 2023-02-23 2022-12-05 2023-03-09 2022-12-14 2023-04-08 2023-01-10 nvelope 9 Mitsamiouli dans le cadre de ctor ss (Non Bank-SPD s travaux pour la constructio ) n des infrastructures de la D GSC par le PRPKR - NGAZIDJA 2022-075-TRAVAUX.DGCS-U GP-PRPKR / LOT3.N/DGCS: Co Request for Bids - nstruction d'une citerne de 1 Component 1: Recovery and Single Stage - One E Small Works SPD 2023-11-0 000 m3 dans la localité de M IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 304,000.00 0.00 Canceled 2022-11-10 2022-11-15 2022-12-05 2022-12-14 2023-01-10 nvelope (1 envelope proce 9 oroni dans le cadre des trava ctor ss) ux pour la construction des i nfrastructures de la DGSC pa r le PRPKR - NGAZIDJA 2022-076-TRAVAUX.DGCS-U GP-PRPKR / LOT4.A/DGCS: Co Request for Bids - nstruction d'un bâtiment de Component 1: Recovery and Single Stage - One E Small Works SPD Under Imple 2023-11-0 30/20/6 dans la localité de Pa IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 233,000.00 0.00 2022-11-10 2023-01-31 2022-11-15 2023-02-04 2022-12-05 2023-02-20 2022-12-14 2023-05-13 2023-01-10 nvelope (1 envelope proce mentation 9 tsy dans le cadre des travaux ctor ss) pour la construction des infra structures de la DGSC par le PRPKR - NDZUWANI 2022-077-TRAVAUX.DGSC-U GP-PRPKR / LOT4.A.bis/DGCS: Request for Bids - Construction d'une citerne de Component 1: Recovery and Single Stage - One E Small Works SPD 2023-11-0 750 m3 dans la localité de Pa IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 235,000.00 0.00 Signed 2022-11-10 2023-01-31 2022-11-15 2023-02-04 2022-12-05 2023-02-20 2022-12-14 2023-05-13 2023-01-10 nvelope (1 envelope proce 9 tsy dans le cadre des travaux ctor ss) pour la construction des infra structures de la DGSC par le PRPKR - NDZUWANI 2022-078-TRAVAUX.DGSC-U GP-PRPKR / LOT5.A/DGCS: Co Request for Bids - nstruction d'un bâtiment 15/ Component 1: Recovery and Single Stage - One E Small Works SPD 2023-11-0 10/6 dans la localité de Sima IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 173,900.00 0.00 Signed 2022-11-10 2023-01-31 2022-11-15 2023-02-04 2022-12-05 2023-02-20 2022-12-14 2023-05-13 2023-01-10 nvelope (1 envelope proce 9 dans le cadre des travaux po ctor ss) ur la construction des infrastr uctures de la DGSC par le PR PKR - NDZUWANI 2022-079-TRAVAUX.DGCS-U GP-PRPKR / LOT5.A.bis/DGCS: Request for Bids - Construction d'une citerne de Component 1: Recovery and Single Stage - One E Small Works SPD 2023-11-0 500m3 dans la localité de Si IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 276,400.00 0.00 Signed 2022-11-10 2023-01-31 2022-11-15 2023-02-02 2022-12-05 2023-02-20 2022-12-14 2023-05-23 2023-01-10 nvelope (1 envelope proce 9 ma dans le cadre des travau ctor ss) x pour la construction des inf rastructures de la DGSC par l e PRPKR - NDZUWANI 2022-080-TRAVAUX.DGCS-U GP-PRPKR / LOT6.M/DGCS: C Request for Bids - onstruction d'un bâtiment de Component 1: Recovery and Single Stage - One E Small Works SPD 2023-11-0 15/10/6 dans la localité de Fo IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 260,000.00 0.00 Signed 2022-11-10 2022-12-27 2022-11-15 2023-01-06 2022-12-05 2023-01-25 2022-12-14 2023-03-03 2023-01-09 nvelope (1 envelope proce 9 mboni dans le cadre des trav ctor ss) aux pour la construction des infrastructures de la DGSC p ar le PRPKR - MWALI 2022-081-TRAVAUX.DGSC-U GP-PRPKR / LOT6.M.bis/DGCS Request for Bids - : Construction d'une citerne Component 1: Recovery and Single Stage - One E Small Works SPD 2023-11-0 de 500 m3 dans la localité de IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 111,000.00 0.00 Signed 2022-10-31 2022-12-27 2022-11-05 2023-01-05 2022-12-05 2023-01-25 2022-12-14 2023-03-03 2023-01-10 nvelope (1 envelope proce 9 Fomboni dans le cadre des tr ctor ss) avaux pour la construction d es infrastructures de la DGSC par le PRPKR - MWALI 2022-082-TRAVAUX.DGCS-U GP-PRPKR / LOT7.M/DGCS: C Request for Bids - onstruction d'un bâtiment de Component 1: Recovery and Single Stage - One E Small Works SPD 2023-11-0 15/10/6 dans la localité de Ni IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 263,100.00 0.00 Signed 2022-11-10 2022-12-27 2022-11-15 2023-01-06 2022-12-05 2023-01-25 2022-12-14 2023-03-03 2023-01-10 nvelope (1 envelope proce 9 oumachouoi dans le cadre de ctor ss) s travaux pour la constructio n des infrastructures de la D GSC par le PRPKR - MWALI 2022-083-TRAVAUX.DGSC-U GP-PRPKR / LOT7.M.bis/DGCS Request for Bids - : Construction d'une citerne Component 1: Recovery and Single Stage - One E Small Works SPD 2023-11-0 de 500 m3 dans la localité de IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 111,000.00 0.00 Signed 2022-11-10 2022-12-27 2022-11-15 2023-01-05 2022-12-05 2023-01-25 2022-12-14 2023-03-04 2023-01-10 nvelope (1 envelope proce 9 Nioumachouoi dans le cadre ctor ss) des travaux pour la construct ion des infrastructures de la DGSC par le PRPKR - MWALI 2023-005-TRAVAUX.DGSC-U Request for Bids - Component 1: Recovery and GP-PRPKR / LOT 4 N/DGSC: C Single Stage - One E Small Works SPD 2023-12-3 IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 300,000.00 0.00 Canceled 2023-02-17 2023-02-22 2023-03-24 2023-04-13 2023-05-04 onstruction d'un bâtiment de nvelope (1 envelope proce 0 ctor 30/20/6m dans la Ville de Mo ss) roni-NGAZIDJA 2023-006-TRAVAUX.DGSC-U Request for Bids - Component 1: Recovery and GP-PRPKR / LOT4.N.bis/DGSC Single Stage - One E Small Works SPD 2023-12-3 IDA / D5490 Resilience in the Housing Se Post Request for Bids Limited 229,900.00 0.00 Canceled 2023-02-17 2023-02-22 2023-03-24 2023-04-13 2023-05-05 : Construction d'un bâtiment nvelope (1 envelope proce 0 ctor de 14/20/6m dans la ville de ss) Moroni-NGAZIDJA 2022-096-TRAVAUX.RN2.RN National Procure 3-UGP-PRPKR / TRAVAUX DE Component 2: Coastal Resili ment Document - Open - Internationa Single Stage - One E Pending Imp 2025-07-2 LA SECTION CIBLEE SUR LA R IDA / D5490 ence and Infrastructure Reh Prior Request for Bids 1 Envelope proce 7,300,000.00 0.00 2024-02-29 2024-03-05 2024-05-24 2024-06-23 2024-07-28 l nvelope lementation 8 OUTE MTSANGADJOU - FOUM abilitation ss (Non Bank-SPD BOUNI - UROVENI ( 13.5 Km) ) PRPKR 2023-001-TRAVAUX.COTIER- National Procure UGP-PRPKR / TRAVAUX D'AM Component 2: Coastal Resili ment Document - Open - Internationa Single Stage - One E 13,600,000.0 Pending Imp 2026-05-3 ENAGEMENT DES ZONES CO IDA / D5490 ence and Infrastructure Reh Prior Request for Bids 1 Envelope proce 0.00 2023-12-29 2024-01-06 2024-03-26 2024-04-25 2024-05-30 l nvelope 0 lementation 0 TIERES POUR 4 SITES (Foumb abilitation ss (Non Bank-SPD ouni-Nioumachouoi-Djoiezi-P ) agé) National Procure 2022-091-SECURISATION.OV Component 3: Integrated Dis ment Document - K-UGP-PRPKR / LOT7 - TRAVA Request for Quota Single Stage - One E Pending Imp 2023-11-2 IDA / D5490 aster Risk Management and Post Limited 1 Envelope proce 30,000.00 0.00 2023-08-05 2023-09-30 UX DE SECURISATION DES 8 tions nvelope lementation 9 CERC ss (Non Bank-SPD SITES DE L'OVK - Union des C ) omores Page 3 2023-010-TRAVAUX.DGCS-U GP-PRPKR / Tavaux de constr Request for Bids - Component 1: Recovery and uction des infrastructures de Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2024-04-1 IDA / D5490 Resilience in the Housing Se Post Request for Bids 900,700.00 0.00 2023-05-10 2023-05-15 2023-06-26 2023-07-16 2023-08-14 la DGSC, 1 Entrepôt de 30/20 l nvelope (1 envelope proce lementation 0 ctor /6m, 1 Entrepôt de 15/20/6m ss) et 1 Citerne de 300m3 dans l a Ville de Moroni - NGAZIDJA. 2023-017-LGT.RESILIENTS-U GP-PRPKR / Travaux de recon Request for Bids - struction logements (au moin Component 1: Recovery and Open - Internationa Single Stage - One E Small Works SPD 2024-06-1 s 51) – Phase 1 en Lot Unique IDA / D5490 Resilience in the Housing Se Post Request for Bids 1,785,000.00 0.00 Canceled 2023-10-31 2023-11-05 2023-12-17 2024-01-16 2024-02-20 l nvelope (1 envelope proce 9 dans le cadre de mis en œuv ctor ss) re du Projet de Relèvement P ost-Kenneth et de Résilience - Comores. 2023- 018 -LGT.RESILIENTS- UGP-PRPKR / Travaux de reco Request for Bids - Component 1: Recovery and nstruction de 263 logements Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2024-12-2 IDA / 65290 Resilience in the Housing Se Prior Request for Bids 9,205,000.00 0.00 2023-10-31 2023-11-05 2023-12-20 2024-01-19 2024-02-23 dans le cadre de mis en oeuv l nvelope (1 envelope proce lementation 5 ctor re du Projet de de Réleveme ss) nt Post-Kenneth - Union des Comores. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 2020-005*UGP-INFORMATIQ UE / Fourniture, livraison et i nstallation sur site des matér Component 4: Project Manag Single Stage - One E iels et équipements informati IDA / D5490 ement, Risk Management, M Post Request for Bids Limited 25,000.00 26,854.28 Signed 2020-10-19 2020-10-20 2020-10-24 2020-10-29 2020-11-09 2020-11-17 2020-11-30 2020-12-19 2020-12-17 2021-01-09 2021-01-18 nvelope ques pour l’Unité de Gestion onitoring and Evaluation de Gestion du Projet de Relè vement Post-Kenneth et de R ésilience (PRPKR) 2020-006/UGP-MOBILIERS B UREAU / Acquisition des Four nitures, livraison et installatio Component 4: Project Manag Single Stage - One E n sur site des mobiliers de bu IDA / D5490 ement, Risk Management, M Post Request for Bids Limited 24,600.00 20,103.27 Signed 2020-11-04 2020-11-03 2020-11-09 2020-11-05 2020-11-25 2020-12-09 2020-12-15 2020-12-18 2021-01-04 2021-01-09 2021-02-10 nvelope reau de l’Unité de Gestion de onitoring and Evaluation Gestion du Projet de Relève ment Post-Kenneth et de Rés ilience (PRPKR) 2020-012-UGP-VEHICULE-PI CK-UP-PRPKR / Acquisition de Component 4: Project Manag UN Agencies (Dire s véhicules Pick-Up pour l'Uni IDA / D5490 ement, Risk Management, M Post Direct 105,000.00 90,973.67 Signed 2021-01-11 2021-02-05 2021-01-16 2021-02-23 2021-02-15 2021-02-13 2021-05-20 ct) té de Gestion du Projet de Re onitoring and Evaluation lèvement Post-Kenneth. 2021-016-COT-EQUIP-UGP-P Component 1: Recovery and RPKR / Acquisition des mobili Request for Quota Single Stage - One E IDA / D5490 Resilience in the Housing Se Post Limited 5,265.00 6,874.42 Signed 2021-06-12 2021-06-17 2021-08-02 2021-07-29 2022-08-02 ers de bureau de la Cellule C tions nvelope ctor artographie de la DATUH. 2021-028-INFO.MAT2-UGP-P RPKR / Fourniture, livraison e Component 3: Integrated Dis t installation sur site des mat Request for Quota Single Stage - One E IDA / D5490 aster Risk Management and Post Limited 14,208.00 35,222.59 Signed 2021-11-14 2021-11-11 2021-12-22 2022-01-13 2022-01-22 ériels et équipements inform tions nvelope CERC atiques dans le cadre de mis en œuvre du PRPKR au profit du DGSC. 2021-027-INFI.MAT1-UGP-PR PKR / Fourniture, livraison et installation sur site des maté Component 1: Recovery and Request for Quota Single Stage - One E riels et équipements informa IDA / D5490 Resilience in the Housing Se Post Limited 44,912.00 88,679.55 Signed 2021-11-10 2021-11-11 2021-12-15 2022-01-13 2022-01-14 tions nvelope tiques dans le cadre de mis e ctor n œuvre du PRPKR au profit du MATUAFTT et ses Directio ns Techniques. 2021-029-INFO.MAT3-UGP-P RPKR / Fourniture , livraison Component 4: Project Manag et installation sur site des ma Request for Quota Single Stage - One E IDA / D5490 ement, Risk Management, M Post Limited 14,208.00 31,127.85 Signed 2021-11-08 2021-11-11 2021-12-10 2022-01-17 2022-01-10 tériels et équipements infor tions nvelope onitoring and Evaluation matiques supplémentaires p our l'Unité de gestion du Proj et PRPKR 2021-030-FOUR.ROULANT-U GP-PRPKR / ACQUISITION DE Component 2: Coastal Resili S VEHICULES PICK-UP POUR L Request for Quota Single Stage - One E IDA / D5490 ence and Infrastructure Reh Post Limited 101,652.00 61,044.01 Signed 2022-01-16 2022-01-25 2022-03-13 2022-03-12 2022-04-27 E CONTROLE ET LE SUIVI DES tions nvelope abilitation TRAVAUX DE LA ROUTE MTS ANGADJOU-FOUMBOUNI-OUR OVENI. 2021-032-MOTEUR-DGSC-U GP-PRPKR / Acquisition, livrai son et installation d’un mote Component 3: Integrated Dis Request for Quota Single Stage - One E ur complet de type 9 LT,320 IDA / D5490 aster Risk Management and Post Limited 17,000.00 0.00 Canceled 2022-01-25 2022-01-28 2022-03-24 2022-05-08 tions nvelope PS-ES y compris les kits et ac CERC cessoires au profit de la Dire ction Générale de la Sécurité Civile. 2022-063-MOTEURDGS-UGP- PRPKR / Acquisition, livraison et installation d’un moteur co Component 3: Integrated Dis Request for Quota Single Stage - One E mplet de type 9 LT, 320 PS-E IDA / D5490 aster Risk Management and Post Limited 23,102.69 35,020.77 Terminated 2022-04-20 2022-04-19 2022-06-01 2022-06-02 2022-07-04 tions nvelope S et comprenant les kits et a CERC ccessoires au profit de la Dir ection Générale de la Sécurit é Civile (DGSC). 2022-068-VOITURE.OVK-UGP -PRPKR / Acquisition d'un véh Component 3: Integrated Dis icule tout terrain pour les mis Request for Quota Single Stage - One E IDA / D5490 aster Risk Management and Post Limited 69,300.00 0.00 Signed 2022-09-09 2022-09-09 2022-09-16 2022-12-15 sions de maintenance sur le t tions nvelope CERC errain de l’Observatoire Volc anologique du Karthala (OVK ) - Comores 2022-086-EQUIP.OVK1-UGP- PRPKR / LOT1- ACQUISITION, Component 3: Integrated Dis LIVRAISON, INSTALLATION S Request for Quota Single Stage - One E IDA / D5490 aster Risk Management and Post Limited 108,800.00 0.00 Canceled 2022-11-07 2022-12-07 2022-12-14 2023-02-13 UR SITE DES CAPTEURS ET N tions nvelope CERC UMERISEURS SISMIQUES ET F ORMATION AU PROFIT DE L'O VK - Union des Comores Page 4 2022-087-EQUIP.OVK2-UGP- PRPKR / LOT2 - ACQUISITION, Component 3: Integrated Dis LIVRAISON SUR SITE D'EQUIP Request for Quota Single Stage - One E IDA / D5490 aster Risk Management and Post Limited 27,800.00 0.00 Canceled 2022-11-07 2022-12-07 2022-12-14 2023-02-13 EMENTS POUR STATION GPS, tions nvelope CERC INSTALLATION ET FORMATIO N AU PROFIT DE L'OVK - Unio n des Comores. 2022-088-EQUIP.OVK3-UGP- PRPKR / LOT3 - ACQUISITION Component 3: Integrated Dis DES MATERIELS DE TRANSMI Request for Quota Single Stage - One E IDA / D5490 aster Risk Management and Post Limited 12,400.00 0.00 Canceled 2022-11-07 2022-12-07 2022-12-14 2023-02-13 SION, LIVRAISON SUR SITE, I tions nvelope CERC NSTALLATION ET FORMATION AU PROFIT DE L'OVK - Union des Comores 2022-089-EQUIP.OVK4-UGP- PRPKR / LOT4 - ACQUISITION, Component 3: Integrated Dis Request for Quota Single Stage - One E LIVRAISON SUR SITE DES STA IDA / D5490 aster Risk Management and Post Limited 25,000.00 0.00 Canceled 2022-11-07 2022-12-07 2022-12-14 2023-02-13 tions nvelope TIONS GAZ, INSTALLATION E CERC T FORMATION AU PROFIT DE L'OVK - Union des Comores 2022-090-EQUIP.OVK5-UGP- PRPKR / LOT 5 - ACQUISITION , LIVRAISON SUR SITE DES E Component 3: Integrated Dis Request for Quota Single Stage - One E QUIPEMENTS INFORMATIQUE IDA / D5490 aster Risk Management and Post Limited 60,300.00 0.00 Signed 2022-11-12 2022-11-11 2023-01-07 2023-02-07 tions nvelope S ET DE SECURISATION, INST CERC ALLATION ET FORMATION AU PROFIT DE L'OVK - Union des Comores. 2022-092-EQUIP.OVK6-UGP- PRPKR / LOT6 - ACQUISITION, Component 3: Integrated Dis Request for Quota Single Stage - One E LIVRAISON SUR SITE ET INST IDA / D5490 aster Risk Management and Post Limited 10,400.00 0.00 Signed 2022-11-20 2022-11-11 2023-01-15 2023-03-16 tions nvelope ALLATION DES EQUIPEMENTS CERC SOLAIRES OVK - Union des C omores 2022-094-MS.PROJECT-UGP- PRPKR / Acquisition, installati Component 4: Project Manag Direct - Internation on et formation d'un Logiciel IDA / D5490 ement, Risk Management, M Post Direct Selection 10,000.00 0.00 Signed 2022-11-30 2022-12-14 2022-12-08 2022-12-15 2023-01-26 2023-04-26 al MS-PROJET pour le projet de r onitoring and Evaluation elèvement post-Kenneth et d e résilience. 2023-007-ACQUISITION.MAT Component 1: Recovery and -UGP-PRPKR / Acquisition d'é Request for Quota Single Stage - One E IDA / D5490 Resilience in the Housing Se Post Limited 22,400.00 0.00 Signed 2023-02-15 2023-02-15 2023-03-13 2023-04-02 quipents informatiques au pr tions nvelope ctor ofit de la DATUH et de l'UGP. 2023-009-EQUIP.OVK-UGP-P Component 3: Integrated Dis RPKR / EQUIPEMENTS SISMO Request for Quota Single Stage - One E Under Imple IDA / D5490 aster Risk Management and Post Limited 300,000.00 0.00 2023-06-04 2023-04-19 2023-09-28 2023-12-27 LOGIQUES, GPS, GAZ ET TRA tions nvelope mentation CERC NSMISSION DE L’OVK - Union des Comores NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 2020-003-UGP-CONSULTANT ENQUÊTE / RECRUTEMENT D’ Component 1: Recovery and UN CONSULTANT NATIONAL Quality And Cost- IDA / D5490 Resilience in the Housing Se Post Open - National 50,000.00 49,643.03 Signed 2020-09-30 2020-10-09 2020-10-15 2020-10-20 2020-10-29 2021-02-10 2020-11-26 2021-04-05 2020-12-11 2021-05-17 2021-01-08 2021-06-11 2021-01-29 2021-06-17 2021-06-28 POUR MENER UNE ENQUÊTE Based Selection ctor COMPLÉMENTAIRE DE CIBLA GE DES MÉNAGES AFFECTES PAR LE CYCLONE KENNETH 2020-004-UGP-AT PC / Etude Component 2: Coastal Resili Quality And Cost- Open - Internationa de diagnostic érosion côtière IDA / D5490 ence and Infrastructure Reh Post 560,000.00 655,851.09 Signed 2020-09-30 2020-09-23 2020-10-15 2020-09-28 2020-11-06 2021-03-01 2020-12-21 2021-04-21 2021-01-05 2021-07-10 2021-02-09 2021-07-20 2021-03-02 2021-11-23 2022-01-31 Based Selection l s et recherches solutions abilitation 2020-011-UGP-AUDIT EXTER NE-PRPKR / Recrutement d'A Component 4: Project Manag uditeur Externe pour les com Least Cost Selecti Open - Internationa IDA / D5490 ement, Risk Management, M Prior 60,000.00 0.00 Canceled 2020-12-30 2021-02-15 2021-01-05 2021-03-16 2021-03-22 2021-04-06 2021-05-11 2021-06-15 2022-12-31 ptes des exercices du 2020 à on l onitoring and Evaluation 2022 du Projet de Relèveme nt Post Kenneth et de résilien ce. 2020-011-UGP-AUDIT - EXTE RNE-PRPKR / Recrutement d' Component 4: Project Manag Auditeur Externe pour les co Least Cost Selecti Open - Internationa IDA / D5490 ement, Risk Management, M Post 60,000.00 36,153.57 Signed 2021-02-23 2021-02-21 2021-02-24 2021-03-11 2021-05-06 2021-05-28 2021-05-12 2021-07-16 2021-05-27 2021-08-24 2021-06-28 2021-10-07 2021-07-14 2021-12-01 2022-12-31 mptes des exercices 2020 à on l onitoring and Evaluation 2022 du Projet de Relèveme nt Post-Kenneth et de Résilie nce. 2021-012-PRES.SOCIAL-UGP- PRPKR / Recrutement d'un C Component 4: Project Manag Consultant Qualifi abinet de prestations sociale IDA / D5490 ement, Risk Management, M Post Open - National 250,000.00 281,157.95 Signed 2021-06-11 2021-06-02 2021-07-02 2021-06-09 2021-08-03 2021-10-21 2021-08-24 2022-01-12 2021-09-14 2022-01-13 2024-09-13 cation Selection s dans le domaine de facilitat onitoring and Evaluation ion sociale pour le compte PR PKR 2021-014-CAB-COTIER-UGP- PRPKR / Recrutement d'un ca Component 2: Coastal Resili Quality And Cost- Open - Internationa binet Expert en Génie Côtier IDA / D5490 ence and Infrastructure Reh Post 300,000.00 152,460.25 Signed 2021-06-10 2021-06-13 2021-06-24 2021-06-23 2021-08-21 2021-10-18 2021-08-26 2021-11-30 2021-09-16 2022-03-16 2021-10-08 2022-04-15 2021-11-11 2022-06-01 2023-11-11 Based Selection l pour une mission d'Assistanc abilitation e Technique dans le cadre du PRPKR aux Comores 2021-018-AMO-UGP-PRPKR / Recrutement d'un Consultant Component 1: Recovery and en Assistance technique au Quality And Cost- Open - Internationa IDA / D5490 Resilience in the Housing Se Prior 962,000.00 0.00 Signed 2021-07-15 2021-08-26 2021-08-02 2021-09-21 2021-09-08 2022-03-10 2021-10-23 2022-04-19 2021-11-03 2022-09-05 2021-12-01 2022-11-24 2021-12-23 2025-07-13 Maître d'Ouvrage pour appuy Based Selection l ctor er à la reconstruction des log ements y compris volet socia l et environnemental 2021-UGP-ETUDE ROUTE RN 2 RN3-PRPKR BIS / Etude con Component 2: Coastal Resili trôle et Surveillance travaux Quality And Cost- Open - Internationa IDA / D5490 ence and Infrastructure Reh Prior 800,000.00 742,768.64 Signed 2021-07-30 2021-08-04 2021-08-20 2021-10-03 2021-10-31 2021-09-04 2021-11-30 2021-09-24 2022-01-04 2022-02-15 2022-02-08 2022-02-17 2023-02-08 routiers Mtsangadjou - Foum Based Selection l abilitation bouni- Uroveni y compris étu des d'impact environnement ales et sociales Page 5 2021-UGP-ETUDE ROUTE RN 2 RN3-PRPKR / Etudes techni que, économique, environne Component 2: Coastal Resili mentale et sociale Consultant Qualifi Open - Internationa IDA / D5490 ence and Infrastructure Reh Post 800,000.00 0.00 Canceled 2021-02-22 2021-03-02 2021-03-15 2021-03-15 2021-06-07 2021-06-17 2021-07-12 2021-08-16 2024-02-20 Réactualisation des études d’ cation Selection l abilitation APD, Gestion, Contrôle et Sur veillance des travaux de réha bilitation de la de La Route N ationale RN2 et RN3 2022-059-CONCEPTION.LGT- UGP-PRPKR / Recrutement d’ un consultant (bureau d'étud Component 1: Recovery and e) pour l'élaboration d’étude Consultant Qualifi Open - Internationa IDA / D5490 Resilience in the Housing Se Post 140,000.00 0.00 Canceled 2022-02-25 2022-03-03 2022-04-08 2022-04-23 2022-05-28 2022-08-11 de conception de logement d cation Selection l ctor ans le cadre de la reconstruc tion des logements du projet de Relèvement Post-Kenneth et de Résilience (PRPKR) 2022-064-LOGEMENT-UGP-P RPKR / ÉLABORATION D’ETU DE DE CONCEPTION DE LOGE Component 1: Recovery and MENT DANS LE CADRE DE LA Quality And Cost- Open - Internationa IDA / D5490 Resilience in the Housing Se Post 300,000.00 0.00 Signed 2022-04-18 2022-04-28 2022-04-22 2022-05-30 2022-10-10 2022-06-30 2022-11-18 2022-07-08 2023-01-10 2022-08-01 2023-01-25 2022-08-24 2022-10-24 RECONSTRUCTION DES LOGE Based Selection l ctor MENT, COMPOSANTE 1 DU « PROJET DE RELÈVEMENT POS T-KENNETH ET DE RÉSILIENC E (PRPKR). 2022-065-EIE.PAR-UGP-PRPK R / ÉLABORATION DES ETUD Component 1: Recovery and ES D’IMPACTS ENVIRONNEME Quality And Cost- Open - Internationa IDA / D5490 Resilience in the Housing Se Post 100,000.00 0.00 Canceled 2022-04-20 2022-07-28 2022-04-25 2022-08-25 2022-05-30 2022-11-30 2022-06-30 2023-01-05 2022-07-07 2023-04-07 2022-07-29 2023-05-17 2022-08-19 2023-02-15 NTALE ET SOCIALE (EIES), Based Selection l ctor ET PLAN DE RELOCALISATION TEMPORAIRE (PRT) DE-LOGE MENTS 2022-066-CAB.COM-UGP-PR PKR / RECRUTEMENT D’UN P Component 4: Project Manag Least Cost Selecti RESTATAIRE DANS LE DOMAI IDA / D5490 ement, Risk Management, M Post Open - National 100,000.00 0.00 Signed 2022-06-10 2022-06-20 2022-06-14 2022-06-22 2022-07-22 2022-11-22 2022-08-22 2023-01-05 2022-08-29 2023-02-21 2022-09-27 2023-04-24 2022-10-18 2023-10-18 on NE DE LA COMMUNICATION P onitoring and Evaluation OUR LE COMPTE DU PRPKR 2022-093-EVA.ALEAS.DGSC- UGP-PRPKR / Evaluation des aléas, vulnérabilité et risques Component 3: Integrated Dis Quality And Cost- Open - Internationa Under Implement ainsi que la base de données IDA / D5490 aster Risk Management and Post 150,000.00 0.00 2022-11-30 2022-12-14 2022-12-21 2022-12-22 2023-02-03 2023-05-18 2023-03-03 2023-05-19 2023-04-02 2023-05-07 2023-06-11 2024-06-10 Based Selection l ation géoréférencées et la mise en CERC œuvre d'un programme de fo rmation au profit de la DGSC - PRPKR 2022-095-AUDIT.INTERNE-U GP-PRPKR / Recrutement d'u Component 4: Project Manag n Auditeur Interne pour l'Unit Least Cost Selecti Open - Internationa IDA / D5490 ement, Risk Management, M Post 50,000.00 0.00 Canceled 2022-12-31 2023-01-21 2023-03-27 2023-04-01 2023-04-21 2023-05-11 2023-06-12 2026-01-12 é de Gestion du Projet de Rel on l onitoring and Evaluation èvement Post-Kenneth et de Résilience Union des Comore s 2023-002-AUDIT.SEC.ROUTE Component 2: Coastal Resili -UGP-PRPKR / ETUDE SUR LA Quality And Cost- Open - Internationa Pending Impleme IDA / D5490 ence and Infrastructure Reh Post 200,000.00 0.00 2023-03-31 2023-04-21 2023-06-30 2023-07-28 2023-08-27 2023-10-01 2023-11-05 2024-11-04 SECURITE ROUTIERE Y COMP Based Selection l ntation abilitation RIS LA CAMPAGNE DE SENSIB ILISATION (RN2-RN3) 2022-101-PRES.FORMATION- UGP-PRPKR / Recrutement d’ Component 1: Recovery and un prestataire pour la comm Quality And Cost- Open - Internationa Under Implement IDA / D5490 Resilience in the Housing Se Post 100,000.00 0.00 2023-02-16 2023-02-16 2023-03-09 2023-04-22 2023-05-20 2023-06-19 2023-07-24 2023-08-28 2024-08-27 unication, la sensibilisation e Based Selection l ation ctor t la formation aux normes et des pratiques de constructio n résilientes aux Comores 2023-020-EIES-PAR COTIER- PRPKR / Recrutement d’un ca Component 2: Coastal Resili Consultant Qualifi Open - Internationa Pending Impleme binet en charge des études d IDA / 65290 ence and Infrastructure Reh Post 350,000.00 0.00 2023-06-30 2023-08-04 2023-09-17 2023-10-17 2023-11-21 2024-03-20 cation Selection l ntation ’impact environnementales e abilitation t sociales des travaux côtier. 2023-019-CONSULTANT.RN2 .RN3-UGP-PRPKR / Recrutem ent d'un cabinet chargé de la Component 2: Coastal Resili finalisation des études techni Consultant Qualifi Open - Internationa IDA / 65290 ence and Infrastructure Reh Prior 790,000.00 0.00 Under Review 2023-06-30 2023-08-14 2023-09-27 2023-10-27 2023-12-01 2025-11-30 ques (APD, DAO, Assistance cation Selection l abilitation à la passation des marchés e t contrôle et suivi des travau x de la route RN2-RN3 - Unio n des Comores. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KM-MATUAFTT-172195-CS-F Component 4: Project Manag Individual Consult BS / Recrutement d'un coord IDA / D5490 ement, Risk Management, M Prior Open 27,800.00 0.00 Canceled 2020-05-12 2020-05-21 2020-05-26 2020-05-30 2020-06-12 2021-06-12 ant Selection onateur du Projet onitoring and Evaluation KM-MATUAFTT-173275-CS-Q Component 4: Project Manag Individual Consult CBS / Récrutement d'un Resp IDA / D5490 ement, Risk Management, M Prior Open 18,600.00 0.00 Canceled 2020-05-12 2020-05-22 2020-05-26 2020-05-30 2020-06-12 2021-06-12 ant Selection onsable de Passation des Mar onitoring and Evaluation chés Publics KM-MATUAFTT-173396-CS-IN Component 4: Project Manag Individual Consult DV / Recrutement d'un exper IDA / D5490 ement, Risk Management, M Prior Open 18,600.00 0.00 Canceled 2020-05-12 2020-05-22 2020-05-26 2020-05-30 2020-06-12 2021-06-12 ant Selection t environnementaliste onitoring and Evaluation KM-MATUAFTT-173398-CS-IN Component 4: Project Manag Individual Consult DV / Recrutement d'un exper IDA / D5490 ement, Risk Management, M Prior Open 18,600.00 0.00 Canceled 2020-05-12 2020-05-22 2020-05-26 2020-05-30 2020-06-12 2021-06-12 ant Selection t en suivi évaluation onitoring and Evaluation KM-MATUAFTT-173400-CS-IN Component 4: Project Manag Individual Consult DV / Recrutement de Respon IDA / D5490 ement, Risk Management, M Prior Open 18,600.00 0.00 Canceled 2020-05-12 2020-05-22 2020-05-26 2020-05-30 2020-06-12 2021-06-12 ant Selection sable Administratif et Financi onitoring and Evaluation er KM-MATUAFTT-173401-CS-IN Component 4: Project Manag Individual Consult DV / Recrutement de compta IDA / D5490 ement, Risk Management, M Prior Open 18,600.00 0.00 Canceled 2020-05-12 2020-05-22 2020-05-26 2020-05-30 2020-06-12 2021-06-12 ant Selection ble onitoring and Evaluation KM-MATUAFTT-173405-CS-IN Component 4: Project Manag Individual Consult DV / Recrutement de speciali IDA / D5490 ement, Risk Management, M Prior Open 18,600.00 0.00 Canceled 2020-05-12 2020-05-22 2020-05-26 2020-05-30 2020-06-12 2021-06-12 ant Selection ste social onitoring and Evaluation Page 6 KM-MATUAFTT-173410-CS-IN Component 4: Project Manag Individual Consult DV / Recrutement de speciali IDA / D5490 ement, Risk Management, M Prior Open 18,600.00 0.00 Canceled 2020-05-12 2020-05-22 2020-05-26 2020-05-30 2020-06-12 2021-06-12 ant Selection ste en communication onitoring and Evaluation KM-MATUAFTT-173414-CS-IN Component 4: Project Manag Individual Consult DV / Recrutement de secretai IDA / D5490 ement, Risk Management, M Prior Open 9,300.00 0.00 Canceled 2020-05-12 2020-05-26 2020-05-30 2020-06-12 2021-06-12 ant Selection re de direction onitoring and Evaluation KM-MATUAFTT-173414-CS-IN Component 4: Project Manag Individual Consult DV// / Recrutement de Secret IDA / D5490 ement, Risk Management, M Post Open 9,300.00 0.00 Canceled 2020-05-30 2020-05-12 2020-06-13 2020-06-17 2020-06-30 2021-06-30 ant Selection aire de Direction onitoring and Evaluation KM-MATUAFTT-183226-CS-IN DV / Mission d'élaboration du Component 4: Project Manag PMPP, de CR et des parties s IDA / D5490 ement, Risk Management, M Post Direct Selection Direct 48,947.43 51,467.29 Signed 2020-09-25 2020-09-28 2020-10-05 2020-10-09 2020-12-09 2019-09-19 2021-06-07 ociales du PEES et du CGES e onitoring and Evaluation n vue de la préparation du Pr ojet PRPKR aux Comores 2020-001-UGP-ATCT / Assist Component 4: Project Manag ance technique temporaire e IDA / D5490 ement, Risk Management, M Post Direct Selection Direct 5,500.00 9,360.53 Signed 2020-09-18 2020-09-18 2020-09-28 2020-09-25 2020-10-15 2020-10-03 2021-04-13 n passation des Marchés pou onitoring and Evaluation r appuyer le RPM du PRPKR 2020-002-UGP-AT SOCIAL / Component 4: Project Manag Individual Consult Recrutement d'un Consultant IDA / D5490 ement, Risk Management, M Post Open 100,000.00 110,500.00 Signed 2020-09-24 2020-09-18 2020-10-27 2020-12-06 2020-11-17 2020-12-21 2020-12-08 2021-01-09 2021-12-08 ant Selection Expert en Développement So onitoring and Evaluation cial Senior 20-07 -MAPEATUTTAF-SG / R Component 4: Project Manag ecrutement d'un Coordonnat Individual Consult IDA / D5490 ement, Risk Management, M Post Open 27,800.00 84,635.59 Signed 2020-10-09 2020-10-14 2020-10-19 2020-10-27 2020-10-22 2020-10-28 2020-10-28 2020-08-14 2021-10-28 eur du projet de relevèment ant Selection onitoring and Evaluation post-kenneth et de résilience 20-012-MAPEATUTTAF-SG / Component 4: Project Manag Recrutement de Spécialiste C Individual Consult IDA / D5490 ement, Risk Management, M Post Open 18,600.00 20,041.81 Signed 2020-10-09 2020-10-14 2020-10-19 2020-10-27 2020-10-22 2020-10-28 2020-10-28 2020-08-20 2020-10-28 ommunication du projet de r ant Selection onitoring and Evaluation elevement post-kenneth et d e resilience 20-011-MAPEATUTTAF-SG / Component 4: Project Manag Recrutement d'un Expert Env Individual Consult IDA / D5490 ement, Risk Management, M Post Open 18,600.00 56,423.72 Signed 2020-10-09 2020-10-14 2020-10-19 2020-10-27 2020-10-22 2020-10-28 2020-10-28 2020-08-14 2021-10-28 ironnementaliste du projet d ant Selection onitoring and Evaluation e relevèment post-kenneth e t de résilience 20-008-MAPEATUTTAF-SG / Recrutement d'un Responsab Component 4: Project Manag Individual Consult le Administratif et Financier d IDA / D5490 ement, Risk Management, M Post Open 18,600.00 56,423.72 Signed 2020-10-09 2020-10-14 2020-10-19 2020-10-27 2020-10-22 2020-10-28 2020-10-28 2020-08-14 2021-10-28 ant Selection u projet de relevèment post- onitoring and Evaluation kenneth et de résilience 20-010-MAPEATUTTAF-SG / Component 4: Project Manag Recrutement d'un comptable Individual Consult IDA / D5490 ement, Risk Management, M Post Open 10,894.00 33,048.18 Signed 2020-10-09 2020-10-14 2020-10-19 2020-10-27 2020-10-22 2020-10-29 2020-10-28 2020-08-14 2021-10-28 du projet de relevèment post ant Selection onitoring and Evaluation -kenneth et de résilience 20-013-MAPEATUTTAF-SG / Component 4: Project Manag Recrutement de Spécialiste S Individual Consult IDA / D5490 ement, Risk Management, M Post Open 18,600.00 57,448.19 Signed 2020-10-09 2020-10-14 2020-10-19 2020-10-27 2020-10-22 2020-10-29 2020-10-28 2020-08-20 2021-10-28 ocial du projet de relevèment ant Selection onitoring and Evaluation post-kenneth et de resilience 20-014-MAPEATUTTAF-SG / Component 4: Project Manag Recrutement d'Expert en Sui Individual Consult IDA / D5490 ement, Risk Management, M Post Open 18,600.00 39,050.59 Signed 2020-10-09 2020-10-14 2020-10-19 2020-10-27 2020-10-22 2020-10-28 2020-10-28 2020-08-20 2021-10-28 vi évaluation du projet de rel ant Selection onitoring and Evaluation evèment post-kenneth et de resilience 20-009-MAPEATUTTAF-SG / Recrutement du Responsable Component 4: Project Manag Individual Consult de Passation de Marchés du IDA / D5490 ement, Risk Management, M Post Open 18,600.00 56,423.72 Signed 2020-10-09 2020-10-14 2020-10-19 2020-10-27 2020-10-22 2020-10-28 2020-10-28 2020-08-14 2021-10-28 ant Selection projet de relevèment post-ke onitoring and Evaluation nneth et de resilience 2020-007-UGP-PPSD / Recrut ement d’un Consultant Intern Component 4: Project Manag ational pour l’élaboration d’u IDA / D5490 ement, Risk Management, M Post Direct Selection Direct 14,200.00 18,514.23 Signed 2020-11-04 2020-11-18 2020-11-07 2020-11-26 2020-11-17 2020-12-05 2020-11-27 ne série de formation en lign onitoring and Evaluation e sur la PPSD et à la révision du PPSD en faveur du projet PRPKR KM-MATUAFTT-172195-CS-IN Component 4: Project Manag Individual Consult DIV / Recrutement d'un Coor IDA / D5490 ement, Risk Management, M Post Open 27,800.00 0.00 Canceled 2020-05-30 2020-05-12 2020-06-13 2020-06-17 2020-06-30 2021-06-30 ant Selection donateur du Projet onitoring and Evaluation KM-MATUAFTT-173396-CS-IN Component 4: Project Manag Individual Consult DV// / Recrutement d'un Exp IDA / D5490 ement, Risk Management, M Post Open 18,600.00 0.00 Canceled 2020-05-30 2020-05-12 2020-06-13 2020-06-17 2020-06-30 2021-06-30 ant Selection ert Environnementaliste onitoring and Evaluation KM-MATUAFTT-173405-CS-IN Component 4: Project Manag Individual Consult DV// / Recrutement de Specia IDA / D5490 ement, Risk Management, M Post Open 18,600.00 0.00 Canceled 2020-05-30 2020-05-12 2020-06-13 2020-06-17 2020-06-30 2021-06-30 ant Selection liste Social onitoring and Evaluation 2020-008-UGP-SD-PRPKR / R Component 4: Project Manag Individual Consult ecrutement d'un Secrétaire d IDA / D5490 ement, Risk Management, M Post Limited 9,705.00 19,468.09 Signed 2020-11-30 2020-12-09 2020-12-05 2020-12-22 2020-12-26 2020-12-29 2021-01-30 2021-01-02 2022-01-30 ant Selection e direction onitoring and Evaluation 2020-010-UGP-ATGC-PRPKR Component 2: Coastal Resili Individual Consult IDA / D5490 Post Open 13,575.00 0.00 Canceled 2020-12-07 2020-12-07 2021-02-05 2021-02-12 2021-03-09 2022-03-09 / Recrutement d'un Expert en ence and Infrastructure Reh ant Selection génie civil abilitation KM-MATUAFTT-173410-CS-IN Component 4: Project Manag Individual Consult DV// / Recrutement de Specia IDA / D5490 ement, Risk Management, M Post Open 18,600.00 0.00 Canceled 2020-05-30 2020-05-12 2020-06-13 2020-06-17 2020-06-30 2021-06-30 ant Selection liste Communication onitoring and Evaluation KM-MATUAFTT-173275-CS-IN Component 4: Project Manag Individual Consult DIV / Recrutement d'un Resp IDA / D5490 ement, Risk Management, M Post Open 18,600.00 0.00 Canceled 2020-05-30 2020-05-22 2020-06-13 2020-06-17 2020-06-30 2021-06-30 ant Selection onsable de Passation des Mar onitoring and Evaluation chés Publics KM-MATUAFTT-173398-CS-IN Component 4: Project Manag Individual Consult DV// / Recrutement d'un Exp IDA / D5490 ement, Risk Management, M Post Open 18,600.00 0.00 Canceled 2020-05-30 2020-05-12 2020-06-13 2020-06-17 2020-06-30 2021-06-30 ant Selection ert en Suivi Evaluation onitoring and Evaluation KM-MATUAFTT-173400-CS-IN Component 4: Project Manag Individual Consult DV// / Recrutement de Respo IDA / D5490 ement, Risk Management, M Post Open 18,600.00 0.00 Canceled 2020-05-30 2020-05-12 2020-06-13 2020-06-17 2020-06-30 2021-06-30 ant Selection nsable Administratif et Finan onitoring and Evaluation cier Page 7 KM-MATUAFTT-173401-CS-IN Component 4: Project Manag Individual Consult DV// / Recrutement de Compt IDA / D5490 ement, Risk Management, M Post Open 18,600.00 0.00 Canceled 2020-05-30 2020-05-12 2020-06-13 2020-06-17 2020-06-30 2021-06-30 ant Selection able onitoring and Evaluation 2020-009-UGP-AT CÔTIER-P Component 2: Coastal Resili RPKR / Recrutement d'un Ass Individual Consult IDA / D5490 ence and Infrastructure Reh Post Open 200,000.00 0.00 Canceled 2020-12-14 2020-12-14 2021-01-28 2021-02-18 2021-03-11 2022-03-11 istant Technique Internationa ant Selection abilitation l expert en génie côtier MATUAFTT-04-11-19 KMF / M arché de consultation individ Component 4: Project Manag uel pour la préparation du do Individual Consult IDA / D5490 ement, Risk Management, M Post Direct 22,360.00 23,852.29 Signed 2020-12-14 2020-12-11 2020-12-30 2020-12-14 2021-01-13 2020-12-14 2021-02-24 2020-12-15 2021-08-23 cument Cadre de Gestion En ant Selection onitoring and Evaluation vironnemental et Social (CG ES) du Projet de Relèvement Post-Kenneth et de Résilienc e 2021-001-UGP-LOGICIEL CO MPTABLE-PRPKR / Acquisition Component 4: Project Manag , Installation et Formation du IDA / D5490 ement, Risk Management, M Post Direct Selection Direct 27,260.00 28,080.16 Signed 2021-03-15 2021-04-03 2021-03-26 2021-04-19 2021-04-28 2021-05-26 2021-07-27 Logiciel Comptable au profit onitoring and Evaluation des utilisateurs du PRPKR. 2021-002-UGP-CS GÉOMATI CIEN-PRPKR / Recrutement d' Component 1: Recovery and un Géomaticien pour piloter l IDA / D5490 Resilience in the Housing Se Post Direct Selection Direct 13,800.00 14,470.44 Signed 2021-03-19 2021-06-01 2021-03-29 2021-06-14 2021-04-15 2021-06-17 2022-04-15 e projet dans la transversalit ctor é de la cellule cartographie d urant douze (12) mois au sei n de la DATUH. 2021-003-UGP-GÉOMATICIE N ADT-PRPKR / Recrutement Component 1: Recovery and d'un Géomaticien Adjoint pou IDA / D5490 Resilience in the Housing Se Post Direct Selection Direct 9,600.00 10,066.30 Signed 2021-03-19 2021-06-01 2021-03-29 2021-06-14 2021-04-16 2021-06-17 2022-04-16 r appuyer le pilotage du proj ctor et dans la transversalité au s ein de la DATUH avec l'appui du PRPKR. 2021-004-UGP-INF/CART-PRP KR / Recrutement d'un Infor maticien/cartographe pour as Component 1: Recovery and surer la gestion de parcs mat IDA / D5490 Resilience in the Housing Se Post Direct Selection Direct 9,600.00 10,066.30 Signed 2021-03-19 2021-06-01 2021-03-29 2021-06-14 2021-04-17 2021-06-17 2022-04-17 ériels informatiques du projet ctor sein de la Direction de l'Amé nagement du Territoire, de l' Urbanisme et de l'Habitat (D ATUH) avec l'appui du PRPKR . 2021-005-UGP-SIG1-PRPKR / Recrutement d'un Agent Con tractuel initié au Système d’I Component 1: Recovery and nformation Géographique po IDA / D5490 Resilience in the Housing Se Post Direct Selection Direct 3,800.00 3,984.56 Signed 2021-03-24 2021-06-01 2021-04-03 2021-06-14 2021-04-20 2021-06-17 2022-04-20 ur assurer la pérennisation d ctor u projet et le développement des activités de la Cellule du DATUH avec l'appui du PRPK R. 2021-006-UGP-SIG2-PRPKR / Recrutement d'un Agent Con tractuel initié au Système d’I Component 1: Recovery and nformation Géographique po IDA / D5490 Resilience in the Housing Se Post Direct Selection Direct 3,800.00 3,984.56 Signed 2021-03-24 2021-06-01 2021-04-03 2021-06-14 2021-04-20 2021-06-17 2022-04-20 ur assurer la pérennisation d ctor u projet et le développement des activités de la cellule du DATUH avec l'appui du PRPK R. 2021-007-UGP-SIG3-PRPKR / Recrutement d'un agent cont ractuel initié au Système d'In Component 1: Recovery and formation Géographique pou IDA / D5490 Resilience in the Housing Se Post Direct Selection Direct 3,800.00 3,984.56 Signed 2021-03-24 2021-06-01 2021-04-03 2021-06-14 2021-04-20 2021-06-17 2022-04-20 r assurer la pérennisation du ctor projet et le développement d es activités de la cellule du D ATUH avec l'appui du PRPKR. 2021-008-UGP-SIG4-PRPKR / Recrutement d'un agent cont ractuel initié au Système d'In Component 1: Recovery and formation Géographique pou IDA / D5490 Resilience in the Housing Se Post Direct Selection Direct 3,800.00 3,984.56 Signed 2021-03-24 2021-06-01 2021-04-03 2021-06-14 2021-04-20 2021-06-17 2022-04-20 r assurer la pérennisation et l ctor e développement des activit és de la cellule du DATUH av ec l'appui du PRPKR. 2021-009-UGP-SIG5-PRPKR / Recrutement d'un agent cont ractuel initié au Système d'In Component 1: Recovery and formation Géographique pou IDA / D5490 Resilience in the Housing Se Post Direct Selection Direct 3,800.00 3,984.56 Signed 2021-03-24 2021-06-01 2021-04-03 2021-06-14 2021-04-20 2021-06-17 2022-04-20 r assurer la pérennisation et l ctor e développement des activit és de la cellule du DATUH av ec l'appui du PRPKR. 2021-010-UGP-SIG6-PRPKR / Recrutement d'un Agent Con tractuel initié au Système d'I Component 1: Recovery and nformation Géographique po IDA / D5490 Resilience in the Housing Se Post Direct Selection Direct 3,800.00 3,984.56 Signed 2021-03-24 2021-06-01 2021-04-03 2021-06-14 2021-04-20 2021-06-17 2022-04-20 ur assurer la pérennisation et ctor le développement des activit és de la Cellule du DATUH av ec l'appui du PRPKR. 2021-011-UGP-ATGC-PRPKR Component 2: Coastal Resili Individual Consult / Recrutement d'un Expert en IDA / D5490 ence and Infrastructure Reh Post Open 13,575.00 103,985.58 Signed 2021-05-05 2021-05-24 2021-06-16 2021-07-24 2021-06-23 2021-09-03 2021-07-18 2021-09-04 2022-07-18 ant Selection Génie Civil abilitation 2021-013-VBG-UGP-PRPKR / Recrutement d'un (e) Expert Component 4: Project Manag e (e) Junior chargé (e) des qu Individual Consult IDA / D5490 ement, Risk Management, M Post Open 20,000.00 11,537.74 Signed 2021-06-07 2021-06-02 2021-07-26 2021-09-27 2021-08-16 2021-10-06 2021-09-04 2021-10-05 2022-09-04 estions de violence basée sur ant Selection onitoring and Evaluation le genre au sein du Projet de Relèvement Post-Kennet et d e Résilience. 2021-015-ASS-RPM-UGP-PRP KR / Recrutement d'un Assist Component 4: Project Manag Individual Consult ant en passation des marché IDA / D5490 ement, Risk Management, M Post Limited 9,705.00 20,289.21 Signed 2021-06-14 2021-06-07 2021-06-24 2021-06-21 2021-07-01 2021-07-13 2021-08-05 2021-07-09 2022-08-05 ant Selection s pour le Projet de Relèveme onitoring and Evaluation nt Post Kenneth et de Résilie nce 2021-020-CONSULTANT 1-U GP-PRPKR / Recrutement d'u Component 1: Recovery and n Consultant pour les Etudes Individual Consult IDA / D5490 Resilience in the Housing Se Post Limited 24,407.00 23,499.31 Signed 2021-07-09 2021-07-14 2021-07-09 2021-07-20 2021-07-12 2021-07-24 2021-07-15 2021-07-28 2021-08-29 techniques (APS, APD&DAO), ant Selection ctor Contrôles et suivi des travau x des infrastructures commu nautaire du lot 1 de Ngazidja. Page 8 2021-021-CONSULTANT 2-U GP-PRPKR / Recrutement d'u n consultant pour les Etudes Component 1: Recovery and Individual Consult techniques (APS, APD&DAO), IDA / D5490 Resilience in the Housing Se Post Limited 25,610.00 20,373.74 Signed 2021-07-09 2021-07-14 2021-07-09 2021-07-20 2021-07-12 2021-07-23 2021-07-15 2021-07-25 2021-08-29 ant Selection Contrôles et suivi des travau ctor x des infrastructures commu nautaire de la phase 1- Lot 2 de Ngazidja 2021-022-CONSULTANT 3-U GP-PRPKR / Recrutement d'u n consultant pour les Etudes Component 1: Recovery and Individual Consult techniques (APS, APD&DAO), IDA / D5490 Resilience in the Housing Se Post Limited 21,756.00 19,116.56 Signed 2021-07-09 2021-07-14 2021-07-09 2021-07-20 2021-07-12 2021-07-23 2021-07-15 2021-07-25 2021-08-29 ant Selection Contrôles et suivi des travau ctor x des infrastructures commu nautaire de la phase 1-Lot 1 de Ndzouani 2021-023-CONSULTANT 4-U GP-PRPKR / Recrutement d'u n consultant pour les Etudes Component 1: Recovery and Individual Consult techniques (APS, APD&DAO), IDA / D5490 Resilience in the Housing Se Post Limited 38,256.00 25,649.33 Signed 2021-07-09 2021-07-14 2021-07-09 2021-07-20 2021-07-12 2021-07-23 2021-07-15 2021-07-25 2021-08-29 ant Selection Contrôles et suivi des travau ctor x des infrastructures commu nautaire de la phase 1-Lot 2 de Ndzouani 2021-024-CONSULTANT 5-U GP-PRPKR / Recrutement d'u n consultant pour les Etudes Component 1: Recovery and Individual Consult techniques (APS, APD&DAO), IDA / D5490 Resilience in the Housing Se Post Limited 30,244.00 28,199.65 Signed 2021-07-09 2021-07-14 2021-07-09 2021-07-20 2021-07-12 2021-07-23 2021-07-15 2021-07-25 2021-08-29 ant Selection Contrôles et suivi des travau ctor x des infrastructures commu nautaire de la phase 1-Lot 1 de Mwali 2021-25-MANUEL.CONSTRU CTION-UGP-PRPKR / Recrute Component 1: Recovery and Individual Consult ment d’un (e) Consultant(e)p IDA / D5490 Resilience in the Housing Se Post Limited 10,000.00 11,985.23 Signed 2021-08-17 2021-09-20 2021-08-22 2021-09-22 2021-09-12 2021-09-22 2021-10-17 2021-09-17 2021-12-16 ant Selection our élaborer un Manuel de re ctor construction de logements 2021-26-UN HABITAT-UGP-P RPKR / Recrutement d'une as Component 1: Recovery and sistance technique de l'ONU IDA / D5490 Resilience in the Housing Se Post Direct Selection Direct 375,000.00 374,145.26 Signed 2021-09-24 2021-11-23 2021-10-04 2022-01-07 2021-11-14 2022-02-11 2023-11-14 Habitat au Ministère de l'amé ctor nagement du territoire MATUAFTT-23-09-19 KMF / M arché de consultation individ uel pour l'élaboration d'un Pl Component 4: Project Manag Individual Consult an d'Engagement Environne IDA / D5490 ement, Risk Management, M Post Limited 12,429.00 24,739.82 Signed 2019-09-19 2022-01-26 2019-09-25 2022-02-10 2019-10-16 2022-02-10 2019-11-20 2019-09-24 2020-05-18 ant Selection mental et Social et du Cadre onitoring and Evaluation de Gestion Environnementale et Sociale du Projet de Relèv ement Post-Kenneth et de Ré silience 2022-031-HANGARSDGSC-U GP-PRPKR / Etudes technique s (Avant-Projets Sommaires, Component 1: Recovery and Avant-Projets détaillés, Dossi IDA / D5490 Resilience in the Housing Se Post Direct Selection Direct 63,752.00 64,993.00 Signed 2022-02-15 2022-02-11 2022-02-27 2022-02-21 2022-04-17 2022-03-02 2022-11-18 er d’appel d’offres, Assistanc ctor e en passation des marchés ; ainsi que la supervision et co ntrôle des travaux des entre pôts et citernes NGAZIDJA de la DGSC. 2022-033-HANGARDSDGSC- UGP-PRPKR / Etudes techniqu es (Avant-Projets Sommaires, Component 1: Recovery and Avant-Projets détaillés, Dossi IDA / D5490 Resilience in the Housing Se Post Direct Selection Direct 41,855.00 41,855.00 Signed 2022-02-15 2022-02-11 2022-02-27 2022-02-21 2022-04-17 2022-02-19 2022-11-18 er d’appel d’offres, Assistanc ctor e en passation des marchés ; ainsi que la supervision et co ntrôle des travaux des entre pôts et citernes MWALI de la DGSC. 2022-034-HANGARDSDGSC- UGP-PRPKR / Etudes techniqu es (Avant-Projets Sommaires, Component 1: Recovery and Avant-Projets détaillés, Dossi IDA / D5490 Resilience in the Housing Se Post Direct Selection Direct 44,984.00 46,225.00 Signed 2022-02-15 2022-02-11 2022-02-27 2022-02-21 2022-04-17 2022-02-24 2022-11-18 er d’appel d’offres, Assistanc ctor e en passation des marchés ; ainsi que la supervision et co ntrôle des travaux des entre pôts et citernes NDZUANI de la DGSC. 2022-067-EXPERT.MI-PARCO URS-UGP-PRPKR / Consultant Component 4: Project Manag Individual Consult National pour l’Evaluation à IDA / D5490 ement, Risk Management, M Post Limited 7,800.00 0.00 Signed 2022-08-16 2022-09-05 2022-08-16 2022-10-12 2022-08-18 2022-10-14 2022-08-22 2022-10-06 ant Selection mi-parcours du Projet de Rel onitoring and Evaluation èvement Post Kenneth et de Résilience (PRPKR) 2022-069-PLAN.TYPE.LOGT- Component 1: Recovery and UGP-PRPKR / Elaboration d'u IDA / 65290 Resilience in the Housing Se Post Direct Selection Direct - National 2,200.00 0.00 Signed 2022-09-30 2022-09-26 2022-10-07 2022-09-27 2022-10-19 2022-11-23 n Plan Type pour réaliser les ctor 50 logements de 40 m2 de la phase pilote. 2022-084-PF.COMP1-UGP-PR PKR / Consultant national en Component 4: Project Manag Individual Consult charge de l'appui et du suivi IDA / D5490 ement, Risk Management, M Post Limited 29,300.00 0.00 Signed 2022-10-31 2022-12-05 2022-11-05 2022-12-21 2022-11-15 2023-04-24 2022-11-30 2024-03-04 ant Selection de la mise en œuvre de la Co onitoring and Evaluation mposante 1 auprès de l'UGP du PRPKR Comores 2022-085-EXPERT.SUIVI-UPG -PRPKR / Recrutement d'un E Component 4: Project Manag Individual Consult xpert national en Suivi-évalu IDA / D5490 ement, Risk Management, M Post Limited 59,800.00 0.00 Signed 2022-11-30 2022-11-02 2022-12-05 2022-12-08 2022-12-15 2022-12-08 2022-12-30 2025-11-28 ant Selection ation pour le Projet de Relève onitoring and Evaluation ment Post-Kenneth et de Rés ilience (PRPKR) 2023-003-FORMATION.DGCS -UGP-PRPKR / Formation des Component 3: Integrated Dis secteurs humanitaires du pla Individual Consult Pending Impleme IDA / D5490 aster Risk Management and Post Limited 18,000.00 0.00 2023-03-31 2023-04-05 2023-04-26 2023-05-31 2023-08-29 n de contingence National et ant Selection ntation CERC insulaire sur les standards mi nimums d'intervention huma nitaire 2023-004-FORMATION1.DGS C-UGP-PRPKR / Formation de l'équipe National sur les mét Component 3: Integrated Dis Individual Consult hodes d'estimation des perte IDA / D5490 aster Risk Management and Post Limited 36,000.00 0.00 Canceled 2023-05-31 2023-06-15 2023-07-06 2023-08-10 2024-02-06 ant Selection s et des dommages engendr CERC és par les catastrophes (PDN A) et l'élaboration des cadres de relèvement Page 9 2024-002-PROG.SENS.DGSC -UGP-PRPKR / Consultant pou r le développement d'un pro Component 3: Integrated Dis Individual Consult Pending Impleme gramme radio pour sensibilis IDA / D5490 aster Risk Management and Post Limited 29,200.00 0.00 2024-02-28 2024-03-19 2024-04-09 2024-05-14 2024-07-13 ant Selection ntation er la population sur leurs co CERC mpréhensions des messages d'alerte précoce et des actio ns à entreprendre. 2022-097-ETUDE.SITE.OVK- UGP-PRPKR / Etude techniqu Component 3: Integrated Dis e et financière relatif à la con IDA / D5490 aster Risk Management and Post Direct Selection Direct - National 20,600.00 0.00 Canceled 2022-12-30 2022-12-14 2023-01-09 2023-02-08 2023-06-08 struction des clôtures de 8 st CERC ations sismiques au profit de l'OVK. 2023-008-NOTAIRE-UGP-PRP Component 1: Recovery and KR / Recrutement d'un (e) No Individual Consult IDA / D5490 Resilience in the Housing Se Post Limited 3,500.00 0.00 Signed 2023-02-17 2023-02-22 2023-03-03 2023-01-16 2023-03-09 2023-04-21 2023-03-20 2023-04-09 taire pour le Projet de Relève ant Selection ctor ment Post-Kenneth et de Rés ilience (PRPKR) 2022-102-ETUDES.OVK-UGP- PRPKR / ETUDES Avant Projet Sommaire, Avant Projet Déta Component 3: Integrated Dis Individual Consult Under Implement llé et Demande d'Appel d'Offr IDA / D5490 aster Risk Management and Post Limited 5,550.00 0.00 2023-02-16 2023-02-27 2023-02-21 2023-03-14 2023-04-03 2023-05-08 ant Selection ation e pour les travaux des 8 sites CERC de l'Observatoire Volcanique du Karthala en Union des Co mores. 2022-098-STAGIAIRE1.UGP.P RPKR / Recrutement d'un (e ) Component 4: Project Manag Individual Consult stagiaire en passation des m IDA / D5490 ement, Risk Management, M Post Open - National 5,500.00 0.00 Signed 2023-02-16 2023-02-16 2023-04-06 2023-02-10 2023-04-16 2023-02-13 2023-05-05 2025-05-05 ant Selection archés pour le Projet de Relè onitoring and Evaluation vement Post-Kenneth en Uni on des Comores. 2022-099-STAGIAIRE2-UGP-P RPKR / Recrutement d'un (e) Component 4: Project Manag deuxième stagiaire en passat Individual Consult Under Implement IDA / D5490 ement, Risk Management, M Post Open - National 5,500.00 0.00 2023-02-16 2023-02-16 2023-04-06 2023-02-10 2023-04-16 2023-05-05 2025-05-05 ion des marchés pour le Proj ant Selection ation onitoring and Evaluation et de Relèvement Post-Kenn eth et de Résilience en Union des Comores. 2022-100-EE-UGP-PRPKR / R ecrutement d'un (e ) nouvea Component 4: Project Manag u (elle) Expert (e ) environne Individual Consult IDA / D5490 ement, Risk Management, M Post Limited 56,600.00 0.00 Signed 2023-02-16 2023-02-16 2023-02-21 2023-03-08 2023-03-14 2023-03-08 2023-04-03 2026-01-01 mental pour le Projet de Relè ant Selection onitoring and Evaluation vement Post-Kenneth et de R ésilience en Union des Comor es 2024-001-PLAN.SAUV.COM- UGP-PRPKR / Elaboration, vali Component 3: Integrated Dis Individual Consult Pending Impleme dation et diffusion des plans IDA / D5490 aster Risk Management and Post Limited 5,400.00 0.00 2024-02-29 2024-03-15 2024-04-05 2024-05-10 2024-07-09 ant Selection ntation de sauvegarde communale d CERC e Moroni, Mutsamudu et Fom boni Union des Comores 2023-012-EIES/PGES/PAR-UG P-PRPKR / Recrutement d'un Component 2: Coastal Resili prestataire pour l'étude envir Individual Consult Pending Impleme IDA / D5490 ence and Infrastructure Reh Post Limited 150,000.00 0.00 2023-05-31 2023-06-05 2023-06-26 2023-07-16 2023-09-14 onnementale et l'EIES/PGES/ ant Selection ntation abilitation PAR de la RN2-RN3 dans le c adre de mis en œuvre du PR PKR. 2023-013-PLAN.DGSC-UGP-P RPKR / Recrutement de 2 con sultants pour la mise à jour e Component 3: Integrated Dis Individual Consult Pending Impleme t validation du Plan Tsunami IDA / D5490 aster Risk Management and Post Limited 9,000.00 0.00 2023-06-30 2023-07-05 2023-07-26 2023-08-30 2023-10-29 ant Selection ntation et diffusion - Elaboration, vali CERC dation et diffusion des plans de sauvegarde communale d e Moroni, Mutsamudu et Fom boni. 2023-014-COR-UGP-PRPKR / Recrutement d'un (e ) nouve Component 4: Project Manag Individual Consult Under Implement au (elle) Coordonnateur (tric IDA / D5490 ement, Risk Management, M Post Open - National 77,600.00 0.00 2023-04-20 2023-04-07 2023-05-25 2023-06-15 2023-07-09 2026-02-23 ant Selection ation e) du Projet de Relèvement P onitoring and Evaluation ost-Kenneth et de Résilience. 2023-016-NOTAIRE.DATUH- UGP-PRPKR / Recrutement de Component 1: Recovery and 2 Notaires pour l'élaboration Individual Consult Under Implement IDA / D5490 Resilience in the Housing Se Post Limited 17,200.00 0.00 2023-05-30 2023-05-31 2023-06-04 2023-06-22 2023-06-25 2023-07-25 2023-09-23 de certificats d'immatriculati ant Selection ation ctor on et titre foncier notammen t dans la deuxième phase de 212 ménages. 2023-015-AUDIT.INT-UGP-PR PKR / Recrutement d'un (e) A Component 4: Project Manag Individual Consult Under Implement uditeur (trice) Interne pour le IDA / D5490 ement, Risk Management, M Post Open - National 50,000.00 0.00 2023-04-28 2023-06-16 2023-06-07 2023-06-28 2023-08-02 2025-11-29 ant Selection ation Projet de Relèvement Post-K onitoring and Evaluation enneth et de Résilience - Co mores 2023-011-CONSULTANT.RN2 .RN3-UGP-PRPKR / Recrutem ent d’un autre cabinet pour l’ Component 2: Coastal Resili achèvement des études APD, Direct - Internation Under Implement IDA / D5490 ence and Infrastructure Reh Post Direct Selection 242,000.00 0.00 2023-05-31 2023-06-10 2023-08-05 2023-11-03 DAO et la supervision des tra al ation abilitation vaux pour le projet de réhabil itation de la Route Nationale RN2 et RN3 Mtsangadjou-Di mani-Foumbouni 2023-021-EIES-LOGT.RESILIE Component 1: Recovery and NT-PRPKR / Recrutement de Individual Consult Under Implement IDA / D5490 Resilience in the Housing Se Post Limited 100,000.00 0.00 2023-05-26 2023-05-31 2023-05-31 2023-06-07 2023-07-12 2023-10-10 02 consultants individuels po ant Selection ation ctor ur la réalisation des EIES/PGE S des logements . 2023-012-EIES/PGES/PAR.RN 2/RN3-UGP-PRPKR / Recrute Component 2: Coastal Resili ment de 2 prestataires pour l Individual Consult IDA / D5490 ence and Infrastructure Reh Post Limited 100,000.00 0.00 Under Review 2023-05-31 2023-06-10 2023-07-01 2023-08-05 2023-11-03 'étude environnementale et l' ant Selection abilitation EIES/PGES/PAR de la RN2-RN 3 dans le cadre de mis en œ uvre du PRPKR Page 10 PROCUREMENT PLAN (Textual Part) Project information: Mauritania – INAYA – P156165 Project Implementation agency: Ministère de la Santé Date of the Procurement Plan: 1 June 2017 Period covered by this Procurement Plan: 1 June 2017-31 December 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the National Procurement Code Law 2010- 044 of 22 July 2010 and its subsequent implementation decrees., such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. The use of the World Bank standard bidding documents with the amendments indicated for use under the national procurement guidelines. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: is not applicable. Works: is not applicable. Other Relevant Procurement Information. None. PROCUREMENT Mauritania : Health System Support PLAN General Information Country: Mauritania 2017-06-06 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P156165 GPN Date: 2017-06-07 Project Name: Health System Support Loan / Credit No: IDA / D1890, / , IDA / D5760 INAYA Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned 01/T/INAYA/2018 / travaux d Capacity Building and Projec Single Stage - One E 2018-08-1 e réaménagement et d'adapt IDA / D1890 Post Request for Bids Open - National 22,535.00 22,819.71 Completed 2018-06-01 2018-07-03 2018-06-06 2018-06-16 2018-07-16 2018-06-23 2018-07-31 2018-07-11 2018-08-15 t Management nvelope 0 ation des bureaux de l'UT-FB R 01/T/INAYA/2017 / Extension Capacity Building and Projec Request for Quota Single Stage - One E 2017-12-2 et réaménagement d'une sall IDA / D1890 Post Open - National 27,000.00 0.00 Canceled 2017-10-23 2017-11-28 t Management tions nvelope 8 e d'archives 01/T/2018 / Extension et am Capacity Building and Projec Request for Quota Single Stage - One E 2019-03-2 énagement de la salle d'archi IDA / D1890 Post Open - National 27,000.00 13,685.83 Completed 2018-11-23 2018-12-05 2019-01-20 2019-03-11 t Management tions nvelope 1 ve pour la Daf. 19/T/2018 / Réalisation des t Capacity Building and Projec Request for Quota Single Stage - One E 2018-05-2 ravaux de réaménagement e IDA / D1890 Post Limited 3,239.00 0.00 Canceled 2018-03-10 2018-04-05 2018-04-29 t Management tions nvelope 9 t d'adaptation des bureaux d e l'UT-FBR 1/T/2019 / réhabilitation des Capacity Building and Projec Request for Quota Single Stage - One E 2019-07-0 IDA / D1890 Post Limited 21,700.00 21,413.68 Completed 2019-04-06 2019-06-12 2019-06-01 2019-07-22 locaux UT-FBR et ERV t Management tions nvelope 1 02/T/INAYA/2020 / Constructi on d'une salle de réunion en Capacity Building and Projec Request for Quota Single Stage - One E 2021-01-1 IDA / D1890 Post Limited 16,752.00 0.00 Canceled 2020-10-31 2020-12-20 préfabriqué pour l'UT-FBR av t Management tions nvelope 9 ec son équipement bureautiq ues et audiovisuels 01/T/INAYA/2020 / Réhabilita tion d'une partie de l'ex CH N Capacity Building and Projec Single Stage - One E 2021-09-1 éma , du poste de santé de ti IDA / D1890 Post Request for Bids Open - National 101,804.00 0.00 Canceled 2020-11-23 2020-11-28 2021-01-09 2021-02-08 2021-03-15 t Management nvelope 1 ntane ,ex Centre de sante de Bassiknou ainsi que du loca l de la DRAS du HEC 23/T/2018 / Construction d'i Capacity Building and Projec Single Stage - One E 2019-10-1 nfrastructures d'entreposage IDA / D1890 Post Request for Bids Open - National 44,394.00 0.00 Canceled 2019-03-10 2019-03-15 2019-04-14 2019-04-29 2019-06-19 t Management nvelope 7 pour les 2 hôpitaux régionau x et 4 CS National Procure 03/T/INAYA/2021 / Constructi ment Document - Capacity Building and Projec Request for Quota Single Stage - One E 2022-02-2 on d'infrastructures d'entrep IDA / D1890 Post Open - National 1 Envelope proce 114,504.00 108,516.70 Signed 2021-07-05 2021-08-30 2022-04-14 t Management tions nvelope 6 osage pour les 2 hôpitaux ré ss (Non Bank-SPD gionaux et 4 CS ) National Procure 04/T/INAYA/2021 / Réhabilita Capacity Building and Projec Request for Quota Single Stage - One E ment Document - 2022-02-2 tion CAMEC de Tintane et Ne IDA / D1890 Post Open - National 166,000.00 80,693.60 Signed 2021-06-29 2021-08-24 2021-09-10 t Management tions nvelope 2 Envelope proce 0 ma ss (Non Bank-SPD National ) Procure 05/T/INAYA/2021 / Extension ment Document - Capacity Building and Projec Request for Quota Single Stage - One E 2022-03-2 et réhabilitation DRASS du H IDA / D1890 Post Open - National 1 Envelope proce 164,000.00 175,672.66 Signed 2021-07-28 2021-09-22 2021-09-10 t Management tions nvelope 1 EC et le CS Bassiknou ss (Non Bank-SPD ) National Procure 01/T/INAYA/2021 / Constructi ment Document - Capacity Building and Projec Request for Quota Single Stage - One E 2022-08-1 on en préfabriqué et équipe IDA / D1890 Post Open - National 1 Envelope proce 75,000.00 183,014.65 Signed 2021-12-25 2022-02-19 2022-03-05 t Management tions nvelope 8 ment d'une salle de réunion ss (Non Bank-SPD pour l'UT-FBR . ) 01/T/IA+NAYA/2022 / Réhabi litation et extension des salle Capacity Building and Projec Request for Quota Single Stage - One E Other (with field f 2023-01-2 IDA / D1890 Post Limited 230,000.00 0.00 Signed 2022-06-06 2022-11-24 2022-08-01 s d'hébergement pour certai t Management tions nvelope or explanation) 8 nes maternités prioritaires de la zone pilote 02/T/INAYA/2022 / Constructi on d'une clôture en béton ar Capacity Building and Projec Request for Quota Single Stage - One E Other (with field f 2023-01-2 IDA / D1890 Post Limited 125,523.00 121,467.55 Signed 2022-06-06 2022-07-12 2022-08-01 2022-08-19 mé protègent le CS M'BERA d t Management tions nvelope or explanation) 8 ans le camp des réfugiés 03./T/INAYA/2022 / Construc tion de locaux de deux cham Capacity Building and Projec Request for Quota Single Stage - One E Other (with field f 2023-01-2 IDA / D1890 Post Limited 149,000.00 0.00 Signed 2022-06-06 2023-02-02 2022-08-01 bres froides à Aioun et à Seli t Management tions nvelope or explanation) 8 baby acquis sur les fonds du projet 10/T/INAYA/2022 / Réhabilita Capacity Building and Projec Single Stage - One E Other (with field f Under Imple 2023-10-1 tion de 4 CS (Tintane, Tembe IDA / D5760 Post Request for Bids Open - National 330,000.00 0.00 2022-12-28 2022-11-15 2023-01-02 2023-02-13 2023-01-05 2023-03-15 2023-04-25 2023-04-19 t Management nvelope or explanation) mentation 6 dra, Vassalla et Douérara) 04/T/INAYA/2022 / Réhabilita Capacity Building and Projec Single Stage - One E Other (with field f 2024-01-0 tion et extension des CS Amo IDA / D5760 Post Request for Bids Open - National 324,324.00 0.00 Canceled 2023-03-22 2023-03-27 2023-05-08 2023-06-07 2023-07-12 t Management nvelope or explanation) 8 urj;Wlata wompo et Adel Beg rou 11/T/INAYA/2023 / Petit Trav Increasing Demand for Healt Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-02-2 aux d'extension de Réhabilita IDA / D1890 Post Limited 108,000.00 0.00 2023-07-05 2023-08-30 h Services tions nvelope or explanation) lementation 6 tion de CS de WEMPOU GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 02/F/INAYA/2017 / Acquisitio Capacity Building and Projec Single Stage - One E n de 4 véhicules tout terrain IDA / D1890 Post Request for Bids Open - National 220,000.00 149,169.56 Completed 2017-10-19 2018-05-15 2017-11-02 2017-12-07 2018-06-20 2017-12-28 2018-07-11 2018-01-25 2018-08-15 2018-02-24 2018-11-06 t Management nvelope et deux véhicules légers 18/F/2018 / Acquisition des c Capacity Building and Projec Single Stage - One E IDA / D1890 Post Request for Bids Open - National 10,141.00 2,078.89 Signed 2018-03-19 2018-03-31 2018-03-24 2018-04-23 2018-04-11 2018-05-08 2018-04-26 2018-06-12 2018-06-13 2019-06-12 onsommables bureautiques t Management nvelope Page 1 20/F/2018 / Acquisition de m Capacity Building and Projec Single Stage - One E atériels et produits d'hygiène IDA / D1890 Post Request for Bids Open - National 6,479.00 527.72 Signed 2018-03-19 2018-03-30 2018-03-24 2018-04-23 2018-04-11 2018-05-08 2018-04-26 2018-06-12 2018-05-21 2018-07-12 t Management nvelope et d'entretien 21/F/2018 / Acquisition d'éq Capacity Building and Projec Single Stage - One E IDA / D1890 Post Request for Bids Open - National 26,634.00 26,329.83 Terminated 2018-03-12 2018-03-30 2018-03-17 2018-04-16 2018-04-11 2018-05-01 2018-05-21 2018-06-05 2018-06-12 2018-07-05 uipements informatiques t Management nvelope 26/F/2018 / Acquisition d'éq Capacity Building and Projec Single Stage - One E uipements et matériels de ge IDA / D1890 Post Request for Bids Open - National 8,752.00 16,857.53 Terminated 2018-05-02 2018-05-07 2018-08-17 2018-06-06 2018-08-27 2018-06-21 2018-09-28 2018-07-26 2018-10-25 2018-08-25 t Management nvelope stion des DBM 16/F/2018 / Acquisition d'éq Capacity Building and Projec Single Stage - One E IDA / D1890 Post Request for Bids Open - National 27,000.00 16,862.35 Terminated 2018-03-05 2018-03-31 2018-03-10 2018-04-09 2018-04-11 2018-04-24 2018-04-26 2018-05-29 2018-05-16 2018-06-13 uipements bureautiques pour t Management nvelope l'UT-FBR 03/F/INAYA/2017 / Acquisitio n d'un Système de gestion fi Capacity Building and Projec Request for Quota Single Stage - One E / Post Open - National 26,000.00 0.00 Canceled 2017-06-07 2017-08-02 2017-10-01 nancière (TOMPRO -version c t Management tions nvelope omplète ou équivalent). 28/F/2018 / Impression et vu Capacity Building and Projec Single Stage - One E lgarisation des protocoles thé IDA / D1890 Post Request for Bids Open - National 14,648.00 0.00 Canceled 2018-05-21 2018-05-26 2018-06-25 2018-07-10 2018-08-14 2018-09-13 t Management nvelope rapeutiques et documents no rmatifs 05/F/INAYA/2017 / Acquisitio Capacity Building and Projec Request for Quota Single Stage - One E n d'équipements informatiqu IDA / D1890 Post Open - National 25,000.00 0.00 Canceled 2017-11-20 2017-12-28 2018-01-11 t Management tions nvelope es et de matériel de la salle d 'archive 04/F/INAYA/2017 / Acquisitio Capacity Building and Projec Request for Quota Single Stage - One E n d'un système de gestion él IDA / D1890 Post Open - National 23,000.00 0.00 Canceled 2017-11-02 2017-12-15 2017-12-28 t Management tions nvelope ectronique des documents (G ED) 29/F/2018 / Acquisition d'éq uipements bureautiques et in Increasing Demand for Healt Single Stage - One E formatiques destinés aux co IDA / D1890 Post Request for Bids Open - National 210,480.00 121,886.10 Signed 2018-11-15 2018-10-15 2018-11-20 2018-10-24 2018-12-20 2018-11-22 2019-01-04 2018-12-10 2019-02-08 2019-02-25 2019-03-10 h Services nvelope mités de santé, ERV, DRAS et Moughataa,CIMAC et pour le portail FBR 18/F/INAYA/2017 / Acquisitio Capacity Building and Projec Request for Quota Single Stage - One E n de consommables de burea IDA / D1890 Post Limited 2,900.00 0.00 Canceled 2017-10-20 2017-11-23 2017-11-28 t Management tions nvelope u et de produits d'hygiène 16/F/INAYA/2017 / Acquisitio Capacity Building and Projec Request for Quota Single Stage - One E IDA / D1890 Post Limited 25,500.00 0.00 Canceled 2017-10-20 2017-11-24 2017-11-30 n de matériel de bureau t Management tions nvelope 22/F/2018 / Acquisition des s Capacity Building and Projec Single Stage - One E ervices d'assurance maladie IDA / D1890 Post Request for Bids Open - National 15,211.00 0.00 Canceled 2018-03-18 2018-03-23 2018-04-22 2018-05-07 2018-06-11 2019-06-11 t Management nvelope pour les contractuels 31/F/2018 / Consommables bureautiques et produits phr Capacity Building and Projec Single Stage - One E IDA / D1890 Post Request for Bids Open - National 11,549.00 2,962.74 Signed 2018-10-01 2018-10-08 2018-10-06 2018-10-11 2018-11-05 2018-10-22 2018-11-20 2018-10-26 2018-12-25 2018-11-27 2019-01-24 ygienne et d'entretien pour l' t Management nvelope équipe régional de vérificatio n 33/F/2018 / Acquisition d'un Capacity Building and Projec Single Stage - One E lot du matériel bureautique p IDA / D1890 Post Request for Bids Open - National 27,746.00 2,205.88 Completed 2018-08-29 2018-09-13 2018-09-28 2018-09-27 2018-10-13 2018-10-16 2018-11-17 2018-11-02 2018-12-02 2018-12-04 t Management nvelope our l'UT-FBR 39/F/2018 / Organisation des Capacity Building and Projec Single Stage - One E ateliers programmes dans l IDA / D1890 Post Request for Bids Open - National 17,900.00 17,683.56 Signed 2018-09-30 2018-10-08 2018-10-05 2018-10-15 2018-11-04 2018-10-22 2018-12-04 2018-10-26 2019-01-08 2018-10-29 2020-01-03 t Management nvelope e cadre de la mise en oeuvre du Projet 27/F/2018 / Organisation d'u n atelier de validation et vulg Capacity Building and Projec Request for Quota Single Stage - One E IDA / D1890 Post Limited 2,343.00 0.00 Canceled 2018-03-17 2018-05-06 2018-05-13 arisation des documents MPT t Management tions nvelope - FBR et décrets sur le SRC 24/F/2018 / Impression des Capacity Building and Projec Single Stage - One E IDA / D1890 Post Request for Bids Open - National 138,648.00 86,674.78 Signed 2018-10-15 2018-11-08 2018-10-20 2018-11-14 2018-11-19 2019-02-07 2018-12-04 2019-02-27 2019-01-08 2019-04-23 2019-02-07 documents clefs pour le proj t Management nvelope et 25/F/2018 / Acquisition des s Capacity Building and Projec Single Stage - One E upports de collecte et de rap IDA / D1890 Post Request for Bids Open - National 23,662.00 0.00 Canceled 2018-12-10 2018-12-15 2019-01-14 2019-01-29 2019-03-05 2019-04-04 t Management nvelope portage des données 23/F/2018 / Acquisition d'éq Capacity Building and Projec Request for Quota Single Stage - One E IDA / D1890 Post Open - National 26,634.00 35,545.90 Signed 2018-12-05 2018-12-05 2019-01-24 2019-02-18 2019-02-13 uipements informatiques t Management tions nvelope 04/F/2018 / Acquisition d'un Capacity Building and Projec Single Stage - One E système de gestion électroni IDA / D1890 Post Request for Bids Open - National 23,000.00 0.00 Canceled 2018-11-14 2018-11-19 2018-12-19 2019-01-03 2019-02-07 2019-03-09 t Management nvelope que des documents (GED). 01/F/2019 / Acquisition d'un lot de matériel informatique ( Increasing Demand for Healt Single Stage - One E Pending Impl hard et sowft) et équipemen IDA / D1890 Post Request for Bids Open - National 69,700.00 0.00 2019-03-15 2019-03-20 2019-04-19 2019-05-04 2019-06-08 2019-07-08 h Services nvelope ementation ts de maintenance informatiq ue destinés aux différents ni veaux du SS 03/F/2019 / Acquisition d'éq Capacity Building and Projec Request for Quota Single Stage - One E uipements informatiques et d IDA / D1890 Post Limited 25,000.00 13,404.48 Signed 2019-04-06 2019-09-11 2019-06-01 2019-11-13 2019-11-28 t Management tions nvelope e matériel de la salle d'archiv e 04/F/2019 / Acquisition d'éq Capacity Building and Projec Request for Quota Single Stage - One E uipements et matériels de ge IDA / D1890 Post Limited 36,500.00 38,367.66 Signed 2019-04-30 2019-07-09 2019-07-02 2019-08-05 2019-12-29 t Management tions nvelope stion des DBM 03.F.219 / Consommables b Capacity Building and Projec Single Stage - One E Under Imple ureautiques et informatique IDA / D1890 Post Request for Bids Open - National 100,418.00 0.00 2019-09-15 2019-11-12 2019-09-20 2019-11-01 2019-12-01 2020-01-05 2021-01-04 t Management nvelope mentation pour l'UT-FBR, la DAF et les ERV 08/F/2019 / Acquisition des Capacity Building and Projec Request for Quota Single Stage - One E IDA / D1890 Post Limited 523.00 0.00 Canceled 2019-04-05 2019-05-31 2019-11-27 produits d'hygiène t Management tions nvelope 05/F/2018 / Acquisition de m Capacity Building and Projec Single Stage - One E IDA / D1890 Post Request for Bids Open - National 25,000.00 0.00 Canceled 2018-12-03 2018-12-08 2019-01-07 2019-01-22 2019-02-20 2019-03-22 atériels pour la salle d'archiv t Management nvelope e 05/F/2019 / Acquisition de 5 versicules 4x4 destinés à la Capacity Building and Projec Single Stage - One E IDA / D1890 Post Request for Bids Open - National 188,285.00 157,594.20 Signed 2020-01-07 2021-09-07 2020-01-14 2020-02-13 2020-10-26 2020-03-05 2020-12-01 2020-04-02 2021-04-02 2020-05-02 région du Hodh charghy et a t Management nvelope ux missions de supervision i nter région Page 2 01/F/INAYA/2020 / Impressio Capacity Building and Projec Request for Quota Single Stage - One E IDA / D1890 Post Limited 39,460.00 29,119.74 Signed 2020-05-09 2020-06-22 2020-06-09 2020-07-21 2020-06-24 n du carnet mère & enfant t Management tions nvelope 02/F/INAYA/2020 / Acquisitio Capacity Building and Projec Request for Quota Single Stage - One E n des pièces de rechanges p IDA / D1890 Post Limited 4,000.00 11,802.89 Signed 2020-05-25 2021-01-05 2020-06-25 2021-01-19 2021-06-25 t Management tions nvelope our les véhicules du projet 16/F/INAYA/2020 / Acquisitio Capacity Building and Projec Request for Quota Single Stage - One E Pending Impl IDA / D1890 Post Limited 5,132.00 0.00 2020-12-15 2021-01-15 2021-02-04 n des matériels de protection t Management tions nvelope ementation tablettes 17/F/INAYA/2020 / Réparatio Capacity Building and Projec Request for Quota Single Stage - One E IDA / D1890 Post Limited 10,000.00 11,802.89 Signed 2020-12-15 2021-01-05 2021-01-15 2021-01-19 2022-01-15 n des véhicules du Projet t Management tions nvelope 07/S/INAYA/2020 / Acquisitio n des services hôteliers dans Capacity Building and Projec Request for Quota Single Stage - One E IDA / D1890 Post Limited 52,000.00 26,699.63 Signed 2021-01-09 2019-12-23 2021-03-06 2020-02-07 2022-03-01 le cadre de la mise en œuvre t Management tions nvelope des activités du Projet. 01/F/INAYA/2021 / Impressio Capacity Building and Projec Request for Quota Single Stage - One E n des registres FOSA, AC et c IDA / D1890 Post Open - National 11,600.00 1,150.46 Signed 2021-03-27 2021-05-22 2021-06-08 2021-11-18 t Management tions nvelope eux de la gestion des plainte s 03/F/INAYA/2021 / Achat des Capacity Building and Projec Request for Quota Single Stage - One E Under Imple tablettes et accessoires pour IDA / D1890 Prior Limited 52,000.00 0.00 2021-04-02 2021-05-28 2021-11-24 t Management tions nvelope mentation la vaccination anti-Covid19 09/F/INAYA/2020 / Acquisitio Capacity Building and Projec Single Stage - One E n de 10 Laboratoires pour 10 IDA / D1890 Post Request for Bids Open - National 196,382.00 0.00 Canceled 2020-11-02 2020-11-09 2020-12-09 2020-12-30 2021-01-27 2021-03-13 t Management nvelope CS prioritaires de la zone pilo te 15/F/INAYA/2020 / ACQUISITI ON D4UN CAMION ET VEHICU Capacity Building and Projec L FRIGORIFIQUE, D4UN LABO IDA / D1890 Post Direct Selection Direct 288,566.00 0.00 Canceled 2020-10-26 2020-10-31 2020-12-20 2021-06-18 t Management RATOIR COMPLET ET DE 2 V EHICULES DE TRANSPORTS D ES EQUIPES MEDICALES 08/F/INAYA/2020 / acquisitio Capacity Building and Projec Request for Quota Single Stage - One E IDA / D1890 Post Limited 30,025.00 0.00 Canceled 2020-10-20 2020-11-20 2020-12-10 n de 2 Chambres froides taill t Management tions nvelope e moyenne 05/F/INAYA/2020 / Acquisitio n de 3 véhicules pour Appuy Capacity Building and Projec Single Stage - One E IDA / D1890 Post Request for Bids Open - National 118,009.00 0.00 Canceled 2020-10-20 2020-10-27 2020-11-26 2020-12-17 2021-01-14 2021-02-28 er les 3 DRAS dans Les régi t Management nvelope ons pilotes ainsi que un d'un Camion frigorifique 07/F/INAYA/2020 / Acquisitio Capacity Building and Projec Single Stage - One E IDA / D1890 Post Request for Bids Open - National 267,170.00 0.00 Canceled 2020-10-20 2020-10-27 2020-11-26 2020-12-17 2021-01-14 2021-02-28 n de 16 Groupes électrogène t Management nvelope s 04/F/INAYA/2020 / Doter les formations sanitaires d'un kit Capacity Building and Projec Single Stage - One E IDA / D1890 Post Request for Bids Open - National 101,104.00 0.00 Canceled 2020-10-15 2020-10-20 2020-11-19 2020-12-04 2021-01-08 2021-02-07 d’équipements et matériels d t Management nvelope e gestion des DBM 11/F/INAYA/2020 / Acquisitio n des matériels bureautique Capacity Building and Projec Request for Quota Single Stage - One E IDA / D1890 Post Limited 34,800.00 0.00 Canceled 2020-11-07 2021-01-02 2021-02-01 s et informatiques destinés à t Management tions nvelope la nouvelle région 08/F/INAYA/2021 / Consomm Capacity Building and Projec Request for Quota Single Stage - One E IDA / D1890 Post Limited 47,200.00 44,590.86 Signed 2021-06-30 2021-10-25 2021-08-25 2021-11-27 2022-02-21 ables bureautiques (UT-FBR t Management tions nvelope DAF et ERV) 06/F/INAYA/2021 / Doter les formations sanitaires d'un kit Capacity Building and Projec Request for Quota Single Stage - One E IDA / D1890 Post Open - National 101,104.00 0.00 Canceled 2021-06-30 2021-08-25 2022-02-21 d’équipements et matériels d t Management tions nvelope e gestion des DBM 07/F/INAYA/2021 / Acquisitio Capacity Building and Projec Request for Quota Single Stage - One E n du Mobilier de bureau et du IDA / D1890 Post Open - National 52,777.00 51,190.54 Signed 2021-06-12 2021-08-07 2021-09-10 2022-02-03 t Management tions nvelope matériel informatique pour la nouvelle région 04/F/ INAYA/2021 / Acquisiti Capacity Building and Projec Request for Quota Single Stage - One E on des groupes pour les deux IDA / D1890 Post Open - National 198,000.00 16,035.20 Signed 2021-07-05 2021-08-30 2021-09-10 2022-02-26 t Management tions nvelope wilaya du hodh ch 10/F/INAYA/2021 / l’Acquisiti on des logistiques et équipe Capacity Building and Projec IDA / D1890 Post Direct Selection Direct 1,390,858.55 1,371,651.65 Signed 2021-06-21 2021-06-15 2021-06-26 2021-06-15 2021-07-31 2021-06-24 2022-01-27 ments pour la prise en charg t Management e médicale des population du HEC 11/F/INAYA/2021 / Acquisitio Capacity Building and Projec Request for Quota Single Stage - One E Under Imple n d'un véhicule destiné à la s IDA / D1890 Post Limited 44,600.00 0.00 2021-12-06 2022-12-23 2022-01-31 2022-07-30 t Management tions nvelope mentation upervision des activités TMC 01/F/INAYA/2022 / Acquisitio Improving Utilization of Qual Request for Quota Single Stage - One E Pending Impl n des affiches banderoles et IDA / D1890 ity RMNCH Health Services t Post Limited 10,500.00 0.00 2022-02-21 2022-04-18 2022-10-15 tions nvelope ementation kit pour la formation en GBD hrough PBF M 12/F/INAYA/2020 / Acquisitio Capacity Building and Projec Request for Quota Single Stage - One E n du Contrôle d'accès et com IDA / D1890 Post Limited 46,400.00 0.00 Canceled 2020-11-07 2020-12-19 2021-01-03 t Management tions nvelope plément de la sécurité d'ince ndie de la DGR 10/F/INAYA/2020 / Acquisitio Capacity Building and Projec Request for Quota Single Stage - One E IDA / D1890 Post Limited 6,460.00 0.00 Canceled 2020-10-31 2020-12-01 2020-12-21 n d'un lot des Matériels de m t Management tions nvelope anutention 14/F/INAYA/2020 / Impressio Capacity Building and Projec Single Stage - One E IDA / D1890 Post Request for Bids Open - National 95,618.00 0.00 Canceled 2020-12-15 2020-12-20 2021-01-19 2021-02-03 2021-03-10 2021-04-15 n normes SR et guide thérap t Management nvelope eutique 13/F/INAYA/2020 / Equipeme Capacity Building and Projec Request for Quota Single Stage - One E nts Audiovisuels de la Salle d IDA / D1890 Post Limited 36,082.00 0.00 Canceled 2020-11-07 2020-12-19 2021-01-03 t Management tions nvelope e réunion de la DGR 02/F/INAYA/2021 / Impressio n outils (registres, cartes fich Capacity Building and Projec Request for Quota Single Stage - One E IDA / D1890 Prior Limited 44,600.00 0.00 Canceled 2021-04-04 2021-05-30 2021-11-26 es et guides) pour la vaccina t Management tions nvelope tion anti- covid 19 02/F/INAYA/2022 / Réparatio Capacity Building and Projec IDA / D5760 Post Direct Selection Direct 16,500.00 13,098.67 Signed 2022-05-26 2022-05-20 2022-05-31 2022-03-01 2022-07-05 2022-06-30 2023-01-01 n d'un véhicule 4X4 Accident t Management é Page 3 04/F/INAYA/2022 / Consomm Capacity Building and Projec Request for Quota Single Stage - One E IDA / D1890 Post Limited 47,500.00 0.00 Signed 2022-08-15 2022-06-23 2022-10-10 2023-04-08 ables bureautiques (UT-FBR t Management tions nvelope DAF et ERV) 04/PI/INAYA/2022 / Recrute Capacity Building and Projec Single Stage - One E ment d’une agence spécialis IDA / D1890 Post Request for Bids Open - National 490,000.00 0.00 Signed 2022-08-08 2022-08-17 2022-08-13 2022-09-01 2022-09-24 2022-09-27 2022-10-24 2022-10-18 2022-11-28 2023-05-27 t Management nvelope ée pour l’amélioration de la p lateforme PBF 17/F/INAYA/2022 / Conventio n entre le Ministère de la San Capacity Building and Projec té et l’UNICEF relative à l’acq IDA / D5760 Post Direct Selection Direct 1,168,433.57 1,168,433.57 Signed 2022-08-18 2022-06-01 2022-08-23 2022-06-16 2022-09-27 2022-07-16 2023-03-26 t Management uisition des vaccins RR pour l a riposte à l’épidémie de la r ougeole 05/F/IANYA/2022 / Acquisitio n d'un lot de matériel inform Capacity Building and Projec Single Stage - One E IDA / D1890 Post Request for Bids Open - National 264,306.00 0.00 Signed 2022-11-28 2021-12-03 2022-12-03 2023-01-14 2023-01-05 2023-02-13 2023-03-06 2023-03-20 2023-09-16 atique et bureautiques pour t Management nvelope les coordinations du projet 18/F/INAYA/2022 / Dotation Capacity Building and Projec Single Stage - One E Pending Impl des CS d'un dispositif solaire IDA / D5760 Post Request for Bids Open - National 260,000.00 0.00 2023-01-08 2023-01-13 2023-02-24 2023-03-26 2023-04-30 2023-10-27 t Management nvelope ementation pour assurer la continuité de s services 20/F/INAYA/2022 / Acquisitio Capacity Building and Projec Request for Quota Single Stage - One E Pending Impl n des tablettes pour les opér IDA / D5760 Post Limited 14,500.00 0.00 2022-12-05 2023-01-30 2023-07-29 t Management tions nvelope ementation ations TMC/INAYA TEKAVOUL 22/F/INAYA/2022 / Acquisitio n , installation et mise en ser vice de 4 groupes électrogè Capacity Building and Projec Single Stage - One E Pending Impl IDA / D5760 Post Request for Bids Open - National 120,000.00 0.00 2023-03-22 2023-03-27 2023-05-08 2023-06-07 2023-07-12 2024-01-08 nes pour les deux chambres f t Management nvelope ementation roides acquises sur le fonds d u projet INAYA et les deux ER V (GUI et HEG) 06/F/INAYA/2022 / Impressio n des documents du projet ( Manuels, protocoles thérape Capacity Building and Projec Request for Quota Single Stage - One E utiques, rapports, bulletins, p IDA / D1890 Post Limited 136,960.00 0.00 Canceled 2022-09-06 2022-11-01 2023-04-30 t Management tions nvelope anneaux, banderoles, déplian ts, outils SNIS, carnet M&E, P NP et tout autre document lié à la mise en œuvre du projet ) 02/F/INAYA/2023 / Impressio n des documents du projet ( Manuels, protocoles thérape Capacity Building and Projec Request for Quota Single Stage - One E Pending Impl utiques, rapports, bulletins, p IDA / D1890 Post Limited 51,400.00 0.00 2023-06-06 2023-08-01 2024-01-28 t Management tions nvelope ementation anneaux, banderoles, déplian ts, outils SNIS, carnet M&E, P NP et tout autre document lié à la mise en œuvre du projet ) 01/F/INAYA/2023 / Acquisitio Capacity Building and Projec Request for Quota Single Stage - One E Pending Impl IDA / D1890 Post Limited 21,000.00 0.00 2023-07-05 2023-08-30 2024-02-26 n des pneus pour les véhicul t Management tions nvelope ementation es du Projet NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 01/S/2019 / Entretien des v Capacity Building and Projec Request for Quota Single Stage - One E IDA / D1890 Post Limited 6,700.00 10,206.14 Signed 2019-05-10 2019-07-09 2019-07-05 2019-08-06 2020-07-04 éhicules du Projet INAYA t Management tions nvelope 02/S/2019 / Maintenance de Capacity Building and Projec Request for Quota Single Stage - One E IDA / D1890 Post Limited 15,900.00 14,955.54 Signed 2019-05-10 2019-06-13 2019-07-05 2019-08-06 2020-07-04 s locaux de l'UT-FBR t Management tions nvelope 02/S/2020 / entretien des v Capacity Building and Projec Request for Quota Single Stage - One E Under Imple IDA / D1890 Post Limited 14,500.00 0.00 2020-10-20 2020-11-17 2021-11-17 éhicules du Projet INAYA l'UT- t Management tions nvelope mentation FBR 03/S/INAYA/2020 / maintena Capacity Building and Projec Request for Quota Single Stage - One E IDA / D1890 Post Limited 14,473.00 15,138.96 Signed 2020-10-17 2020-09-18 2020-11-06 2020-11-12 2021-11-06 nce pour les locaux de l'UT-F t Management tions nvelope BR 4/S/INAYA/2020 / Assistance Improving Utilization of Qual technique de TOMPRO et ap Pending Impl IDA / D1890 ity RMNCH Health Services t Post Direct Selection Direct 19,521.00 0.00 2020-12-14 2020-12-19 2021-01-23 2021-07-22 prentissage de l'équipe de la ementation hrough PBF gestion financière 06/S/INAYA/2020 / LOCATIO N DES VEHICULES DANS LE Capacity Building and Projec Request for Quota Single Stage - One E IDA / D1890 Post Limited 37,000.00 43,903.00 Signed 2020-12-19 2021-05-20 2021-01-16 2021-06-11 2022-01-16 CADRE DE LA MISE EN OAUV t Management tions nvelope RE DES ACTIVITES DU PROJE T 04/S/INAYA/2021 / Acquisitio Capacity Building and Projec Request for Quota Single Stage - One E n des services hôteliers pour IDA / D1890 Post Limited 44,900.00 0.00 Canceled 2021-04-04 2021-05-30 2021-11-26 t Management tions nvelope la Formation de formateurs l ocaux 05/S/INAYA/2021 / Acquisitio Capacity Building and Projec Request for Quota Single Stage - One E n des services hôteliers pour IDA / D1890 Post Open - National 165,728.00 147,989.66 Signed 2021-08-05 2021-09-30 2021-11-02 2022-03-29 t Management tions nvelope les ateliers et réunions du pr ojet 03/S/INAYA/2021 / Location Capacity Building and Projec Request for Quota Single Stage - One E des véhicules dans le cadre d IDA / D1890 Post Open - National 110,000.00 0.00 Canceled 2022-01-04 2022-03-01 2022-08-28 t Management tions nvelope e la mise en œuvre des activi tés du projet 02/S/INAYA/2022 / Location Capacity Building and Projec Request for Quota Single Stage - One E Under Imple des véhicules dans le cadre d IDA / D1890 Post Limited 39,300.00 0.00 2022-07-30 2022-06-15 2022-09-24 2023-03-23 t Management tions nvelope mentation e la mise en œuvre des activi tés du projet 04/S/INAYA/2022 / Acquisitio n, installation et mise en serv Capacity Building and Projec Request for Quota Single Stage - One E Pending Impl ice de câblage et réseau et t IDA / D5760 Post Limited 50,435.00 0.00 2022-09-05 2022-10-31 2023-04-29 t Management tions nvelope ementation élé informatique pour les DR S et ERV de la zone pilote IN AYA 5/S/INAYA/2022 / Acquisition des services hôteliers dans le Capacity Building and Projec Request for Quota Single Stage - One E Under Imple IDA / D5760 Post Limited 117,166.00 0.00 2022-09-02 2022-12-30 2022-10-28 2023-04-26 cadre de la mise en œuvre d t Management tions nvelope mentation es activités du Projet. Page 4 05/S/INAYA/2022 / Entretien, assurance réparation et main Capacity Building and Projec Request for Quota Single Stage - One E Pending Impl IDA / D5760 Post Limited 13,900.00 0.00 2022-12-05 2023-01-30 2023-07-29 tenance des véhicules y com t Management tions nvelope ementation pris l'achat des pièces de rec hange 21/F/INAYA/2022 / Réparatio n et construction du circuit él Capacity Building and Projec Request for Quota Single Stage - One E Pending Impl ectrique des Groupes Electro IDA / D5760 Post Limited 16,022.00 0.00 2023-03-08 2023-05-03 2023-10-30 t Management tions nvelope ementation gènes Acquis dans le cadre d u Projet INAYA dans certains CS bénéficiaires 06/S/INAYA/2022 / Assurer la maintenance des Groupes El Capacity Building and Projec Request for Quota Single Stage - One E Pending Impl IDA / D5760 Post Limited 16,076.00 0.00 2023-03-11 2023-05-06 2023-11-02 ectrogènes acquis dans le ca t Management tions nvelope ementation dre du Projet INAYA (contrat annuel) 07/S/INAYA/2022 / Elaboratio Capacity Building and Projec Request for Quota Single Stage - One E Pending Impl n d'un film (vidéo) document IDA / D5760 Post Limited 15,700.00 0.00 2023-04-08 2023-06-03 2023-11-30 t Management tions nvelope ementation aire sur le bilan PBF 03/S/INAYA/2022 / Elaboratio Capacity Building and Projec Request for Quota Single Stage - One E n d'un film (vidéo) document IDA / D1890 Post Limited 18,131.00 0.00 Canceled 2022-07-05 2022-08-30 2023-02-26 t Management tions nvelope aire sur le bilan PBF 08/S/INAYA/2021 / recrutem Capacity Building and Projec Request for Quota Single Stage - One E ent d'une agence d'assuranc IDA / D1890 Post Limited 30,000.00 0.00 Canceled 2021-12-25 2022-02-19 2022-08-18 t Management tions nvelope e pour le personnel du Projet 02/S/INAYA/2023 / Maintena Capacity Building and Projec Request for Quota Single Stage - One E Pending Impl IDA / D5760 Post Limited 14,600.00 0.00 2023-06-06 2023-08-01 2024-01-28 nce des locaux de l'UT FBR t Management tions nvelope ementation CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 14/PI/INAYA/2017 / Agence i Improving Utilization of Qual Quality And Cost- Open - Internationa nternationale chargée de for IDA / D1890 ity RMNCH Health Services t Prior 1,000,000.00 300,757.72 Signed 2017-07-17 2017-09-19 2017-08-07 2017-11-24 2017-09-20 2018-07-24 2017-10-18 2018-09-05 2017-11-17 2018-11-06 2017-12-22 2019-04-09 2018-01-26 2019-07-13 2018-07-25 Based Selection l mation sur le FBR et le coach hrough PBF ing 15/PI/INAYA/2017 / Auditeur Capacity Building and Projec Least Cost Selecti IDA / D1890 Prior Open - National 27,000.00 8,630.14 Signed 2017-10-16 2017-11-07 2017-10-25 2017-11-24 2017-11-30 2018-07-31 2018-01-02 2018-09-12 2018-01-16 2018-11-28 2018-02-07 2019-01-15 2018-02-27 2019-02-04 2021-02-26 externe pour une période de t Management on trois ans Improving Utilization of Qual 37/PI/2018 / Agence internat Quality And Cost- Open - Internationa IDA / D1890 ity RMNCH Health Services t Post 300,000.00 198,256.63 Signed 2018-02-22 2018-06-11 2018-04-15 2018-06-21 2018-05-14 2018-10-25 2018-06-25 2018-12-18 2018-07-16 2019-01-22 2018-08-13 2019-03-22 2018-09-17 2019-06-12 2019-09-17 ionale de contre- vérification Based Selection l hrough PBF 06/PI/INAYA/2017 / ONG nati Improving Utilization of Qual Quality And Cost- onales de vérification commu IDA / D1890 ity RMNCH Health Services t Post Open - National 160,000.00 0.00 Canceled 2017-11-22 2017-12-06 2018-01-11 2018-02-15 2018-02-28 2018-03-29 2018-04-26 2019-04-26 Based Selection nautaire hrough PBF 08/PI/INAYA/2017 / Recrute ment d'un cabinet internatio Capacity Building and Projec Quality And Cost- Open - Internationa IDA / D1890 Post 100,000.00 0.00 Canceled 2017-11-01 2017-11-02 2017-11-15 2017-11-24 2017-12-21 2018-03-05 2018-02-08 2018-04-16 2018-02-20 2018-07-23 2018-03-22 2018-04-19 2018-06-18 nal pour la fourniture, installa t Management Based Selection l tion et paramétrage du porta il et du système FBR 01/PI/INAYA/2021 / AUDIT EX Capacity Building and Projec Consultant Qualifi TERNE pour les exercice 202 IDA / D1890 Post Open - National 15,621.00 15,021.98 Signed 2021-02-16 2021-02-22 2021-03-09 2021-04-22 2021-05-05 2021-05-22 2021-05-05 2021-06-26 2022-01-13 2023-02-16 t Management cation Selection 0 , 2021, 2022, 2023 02/PI/INAYA/2021 / Recrute Capacity Building and Projec Consultant Qualifi Open - Internationa ment d'une Agence internati IDA / D1890 Post 250,000.00 276,000.00 Signed 2021-03-15 2021-03-30 2021-04-05 2021-11-30 2021-05-19 2022-01-07 2021-06-18 2022-04-21 2021-07-23 2022-06-01 2022-01-19 t Management cation Selection l onale de contre vérification. 01/PI/INAYA/2022 / Recrute Capacity Building and Projec Quality And Cost- Open - Internationa ment d’une agence spécialis IDA / D1890 Post 490,000.00 0.00 Canceled 2022-02-22 2022-01-25 2022-03-15 2022-04-28 2022-05-26 2022-06-25 2022-07-30 2022-09-03 2023-09-03 t Management Based Selection l ée pour l’amélioration de la plateforme PBF 02/PI/INAYA/2020 / Elaborati on et le renseignement d’un l ogiciel d’inventaire des infras Capacity Building and Projec Consultant Qualifi tructures, et des équipement IDA / D1890 Post Limited 39,000.00 0.00 Canceled 2021-01-28 2021-02-11 2021-03-03 2021-03-24 2021-05-23 t Management cation Selection s médicaux, ainsi que l’encad rement et la supervision des équipes chargées de l’opérat ion de l’inventaire. 34/PI/2018 / Etude et suivi d es travaux de construction d Capacity Building and Projec Consultant Qualifi IDA / D1890 Post Open - National 25,000.00 0.00 Canceled 2018-10-15 2018-10-22 2018-12-05 2018-12-12 2019-01-09 2019-07-08 'infrastructures d'entreposag t Management cation Selection e pour les 2 hôpitaux régiona ux et 4 CS 35/PI/2018 / ONG nationales Improving Utilization of Qual Consultant Qualifi de vérification communautair IDA / D1890 ity RMNCH Health Services t Post Open - National 160,000.00 0.00 Canceled 2018-03-01 2018-03-16 2018-04-14 2018-04-29 2018-06-03 2019-06-03 cation Selection e. hrough PBF 01/PI/2019 / Mise en place d' Capacity Building and Projec Consultant Qualifi Open - Internationa un système intégré GEC/GED IDA / D1890 Post 35,000.00 0.00 Canceled 2019-01-29 2019-01-27 2019-02-19 2019-03-07 2019-04-04 2019-05-30 2019-05-04 2019-06-08 2019-12-05 t Management cation Selection l (ECM)au profit du projet INAY A. 06/PI/INAYA/2020 / Mise en p lace d'une base de données pour la gestion des RH au niv Capacity Building and Projec Consultant Qualifi IDA / D1890 Post Limited 16,216.00 0.00 Canceled 2020-06-15 2021-03-30 2020-06-22 2020-07-22 2020-08-12 2020-11-10 eau de la DRH (acquisition d' t Management cation Selection un logiciel et assurer son par amétrage et son renseignem ent) 10/PI/INAYA/2021 / Recrute ment d'un bureau pour établi Capacity Building and Projec Consultant Qualifi Pending Impleme IDA / D5760 Post Limited 27,248.00 0.00 2022-09-15 2022-09-29 2022-10-29 2022-12-03 2023-06-01 r un cahier de charge pour u t Management cation Selection ntation n dispositif salaire dans les g rands centre de santé 11/PI/INAYA/2022 / Mise en p lace d'une base de données pour la gestion des RH au niv Capacity Building and Projec Consultant Qualifi Pending Impleme IDA / D5760 Post Limited 19,461.00 0.00 2022-09-30 2022-10-14 2022-11-13 2022-12-18 2023-06-16 eau de la DRH (acquisition d' t Management cation Selection ntation un logiciel et assurer son par amétrage et son renseignem ent) Page 5 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 11/PI/INAYA/2017 / Spécialist Capacity Building and Projec Individual Consult IDA / D1890 Prior Open 24,000.00 16,901.40 Terminated 2017-07-17 2017-07-14 2017-08-19 2017-10-09 2017-09-09 2017-10-19 2017-10-14 2017-11-08 2018-10-14 e en gestion financière t Management ant Selection 12/PI/INAYA/2017 / Spécialist Capacity Building and Projec Individual Consult IDA / D1890 Prior Open 24,000.00 23,641.97 Signed 2017-07-24 2017-07-25 2017-08-26 2017-11-29 2017-09-16 2018-01-16 2017-10-21 2018-02-01 2018-10-21 e en passation des marchés t Management ant Selection 13/PI/INAYA/2017 / Auditeur Capacity Building and Projec Individual Consult IDA / D1890 Post Open 24,000.00 23,013.70 Signed 2017-10-18 2017-11-27 2017-11-27 2018-08-03 2017-12-11 2018-08-07 2018-01-08 2019-01-10 2019-01-08 interne national t Management ant Selection 09/PI/INAYA/2017 / Consulta Improving Utilization of Qual Individual Consult nt individuel international en IDA / D1890 ity RMNCH Health Services t Post Open 90,000.00 148,890.00 Signed 2017-10-19 2017-11-07 2017-12-22 2018-02-21 2017-12-29 2018-03-15 2018-01-29 2018-04-17 2019-01-29 ant Selection FBP pour le niveau central hrough PBF 30/PI/2018 / Informaticien p Capacity Building and Projec Individual Consult IDA / D1890 Post Open 12,676.00 1,519.84 Signed 2018-02-26 2018-03-30 2018-04-19 2018-06-11 2018-04-26 2018-06-12 2018-05-22 2018-07-26 2019-05-22 our le Projet t Management ant Selection 31/PI/2018 / Statisticien/épid Capacity Building and Projec Individual Consult IDA / D1890 Post Open 15,211.00 15,198.41 Signed 2018-03-19 2018-03-20 2018-05-10 2018-06-11 2018-05-17 2018-06-12 2018-06-14 2018-07-19 2019-06-14 émiologiste pour le Projet t Management ant Selection 32/PI/2018 / Traduction des Capacity Building and Projec Individual Consult IDA / D1890 Post Limited 2,515.00 26,914.28 Signed 2018-04-02 2018-12-25 2018-04-07 2019-01-28 2018-04-17 2019-04-08 2018-05-09 2019-05-24 2018-05-24 textes du projet t Management ant Selection 33/PI/2018 / Consultant pour Capacity Building and Projec Individual Consult réviser, adapter et compléter IDA / D1890 Post Open 19,155.00 14,072.60 Completed 2018-04-23 2018-04-06 2018-06-04 2018-06-24 2018-06-19 2018-07-07 2018-07-24 2018-08-06 2018-09-22 2018-12-20 t Management ant Selection les supports de recueils des données 36/PI/2018 / Consultant indiv Improving Utilization of Qual iduel international spécialiste Individual Consult IDA / D1890 ity RMNCH Health Services t Post Open 120,000.00 60,000.00 Signed 2018-02-13 2018-05-05 2018-04-11 2018-06-13 2018-04-25 2018-07-16 2018-05-23 2018-08-15 2019-05-23 en FBP pour la mise en œuvr ant Selection hrough PBF e des activités sur le terrain. 38/PI/2018 / CONSULTANCE Capacity Building and Projec Individual Consult POUR LA DÉTERMINATION DE IDA / D1890 Post Limited 15,380.00 15,380.00 Completed 2018-03-27 2018-04-15 2018-04-03 2018-05-08 2018-04-10 2018-05-16 2018-05-03 2018-05-30 2018-06-02 2018-06-18 t Management ant Selection S COÛTS DE LA MISE EN ŒU VRE DU FBR 34/PI/INAYA/2018 / accompa Capacity Building and Projec Individual Consult gner et encadrer le processu IDA / D1890 Post Limited 30,000.00 23,000.00 Completed 2018-05-16 2018-07-09 2018-06-05 2018-08-13 2018-06-19 2018-08-30 2018-07-06 2018-11-05 2018-08-05 2018-12-05 t Management ant Selection s de formation en masse des acteurs en FBP 10/PI/INAYA/2017 / Consulta Improving Utilization of Qual nt individuel international en Individual Consult IDA / D1890 ity RMNCH Health Services t Post Open 90,000.00 0.00 Canceled 2017-10-19 2018-05-15 2017-12-22 2018-06-13 2017-12-29 2018-01-29 2019-01-29 FBP pour la mise en œuvre d ant Selection hrough PBF es activités sur le terrain 39/PI/2018 / Accompagneme Improving Utilization of Qual Individual Consult nt la mise en place du projet IDA / D1890 ity RMNCH Health Services t Post Open 30,000.00 14,269.00 Completed 2018-08-29 2018-10-23 2018-12-04 2018-10-30 2019-01-31 2018-11-30 2019-02-18 2018-12-15 2019-03-04 ant Selection pilote FBR hrough PBF 23/PI/2018 / Recrutement d' un consultant individuel per Improving Utilization of Qual Individual Consult manent spécialiste en sauve IDA / D1890 ity RMNCH Health Services t Post Open 1,972.00 22,617.13 Signed 2018-12-10 2019-02-21 2019-02-13 2019-05-10 2019-02-28 2019-05-20 2019-03-31 2019-06-17 2020-03-30 ant Selection garde environnementale et s hrough PBF ociale pour appui à la DHP 02/PI/2019 / Assurer la coord Improving Utilization of Qual Individual Consult ination INAYA-TEKAFOUL et a IDA / D1890 ity RMNCH Health Services t Post Open 23,400.00 0.00 Canceled 2019-03-17 2019-05-09 2019-05-21 2019-07-18 2019-06-05 2019-07-06 2020-07-05 ant Selection ppuey la mise en œuvre de l hrough PBF a composante 2 Improving Utilization of Qual 40/PI/2018 / Assistance tech Individual Consult IDA / D1890 ity RMNCH Health Services t Post Limited 17,225.00 0.00 Canceled 2018-10-15 2018-11-04 2018-11-27 2018-11-25 2018-12-16 2019-01-05 nique pour l'UT-FBR ant Selection hrough PBF 04/PI/2019 / assurer la coord Improving Utilization of Qual ination INAYA-TEKAFOUL et a Individual Consult IDA / D1890 ity RMNCH Health Services t Post Open 23,431.00 24,000.00 Signed 2019-09-03 2019-06-20 2019-10-22 2019-11-08 2019-11-12 2019-11-14 2019-12-17 2019-12-25 2020-12-16 ppuer la mise en œuvre de la ant Selection hrough PBF composante 2 du Projet 05/PI/2019 / Comptable du P Capacity Building and Projec Individual Consult IDA / D1890 Prior Open 16,900.00 21,696.80 Signed 2019-10-22 2020-02-17 2019-12-28 2020-06-02 2020-01-12 2021-03-08 2020-01-30 2020-07-17 2021-01-29 rojet t Management ant Selection 06/PI/2019 / spécialiste en p Capacity Building and Projec Individual Consult IDA / D1890 Post Open 24,000.00 23,121.33 Signed 2019-12-16 2020-04-01 2020-02-14 2020-09-22 2020-02-29 2020-12-14 2020-03-21 2021-04-05 2021-03-21 assation des marches pour le t Management ant Selection Projet 05/PI/INAYA2020 / Recrutem ent d’un consultant Internati Improving Utilization of Qual onal pour l’élaboration du Pla Individual Consult IDA / D1890 ity RMNCH Health Services t Post Limited 13,620.00 26,062.80 Signed 2020-05-03 2020-04-29 2020-05-08 2020-04-30 2020-05-15 2020-05-14 2020-06-02 2020-06-05 2020-07-02 n de Gestion de la Main d’œ ant Selection hrough PBF uvre et du Plan de Mobilisatio n des Parties Prenantes /proj et COVID19 08/PI/INAYA/2020 / consulta Improving Utilization of Qual Individual Consult nts spécialistes PBF pour ap IDA / D1890 ity RMNCH Health Services t Prior Direct 360,000.00 88,890.00 Signed 2020-10-19 2020-12-29 2020-10-29 2020-07-06 2020-11-03 2021-05-19 2020-11-13 2021-05-21 2021-05-12 ant Selection puyer le niveau régional hrough PBF 08/PI/2020 / Recrutement d' Capacity Building and Projec Individual Consult IDA / D1890 Post Open 16,737.00 16,519.78 Signed 2020-11-09 2021-02-02 2020-12-28 2021-05-04 2021-01-18 2021-05-05 2021-02-22 2021-05-27 2022-02-22 un aide comptable t Management ant Selection 03/PI/INAYA/2021 / Concepti Improving Utilization of Qual Individual Consult on et installation de la platef IDA / D1890 ity RMNCH Health Services t Post Limited 25,100.00 0.00 Canceled 2021-03-30 2021-03-27 2021-04-04 2021-04-25 2021-05-30 2021-11-26 ant Selection orme hrough PBF 04/PI/INAYA/2021 / Recrute ment d’un spécialiste de la s Capacity Building and Projec Individual Consult IDA / D1890 Post Open 24,000.00 23,127.69 Signed 2021-03-31 2021-03-29 2021-05-19 2021-06-25 2021-06-09 2021-07-19 2021-07-14 2021-07-20 2022-01-10 auvegarde sociale et commu t Management ant Selection nication pour INAYA 06/INAYA/PI/2021 / Recrute Improving Utilization of Qual Individual Consult ment du Consultant tekavoul IDA / D1890 ity RMNCH Health Services t Post Open 25,000.00 23,127.69 Signed 2021-05-03 2021-05-08 2021-06-21 2021-08-27 2021-07-12 2021-08-02 2021-08-16 2021-09-29 2022-02-12 ant Selection INAYA hrough PBF 08/PI/INAYA/2021 / Recrute Improving Utilization of Qual ment d'un consultant intern Individual Consult IDA / D1890 ity RMNCH Health Services t Post Limited 14,000.00 14,000.00 Signed 2021-05-25 2021-05-08 2021-05-30 2021-12-27 2021-06-20 2022-02-22 2021-07-25 2022-03-05 2022-01-21 ational pour évaluer et améli ant Selection hrough PBF orer le dispositif PBF en Maur itanie Page 6 09/PI/INAYA/2021 / Recrute Improving Utilization of Qual ment d'un spécialiste en sau Individual Consult IDA / D1890 ity RMNCH Health Services t Post Open 24,000.00 23,641.97 Signed 2021-12-20 2021-12-10 2022-02-07 2022-01-19 2022-02-28 2022-01-31 2022-04-04 2022-02-16 2022-10-01 vegarde environnementale e ant Selection hrough PBF t sociale pour appui à la DHP Improving Utilization of Qual 04/PI/2020 / chargé de com Individual Consult IDA / D1890 ity RMNCH Health Services t Post Open 20,084.00 0.00 Canceled 2020-03-30 2020-05-28 2020-06-12 2020-07-13 2021-07-13 munication du Projet ant Selection hrough PBF 01/PI/2020 / Assistance tech Improving Utilization of Qual Individual Consult nique courte durée pour app IDA / D1890 ity RMNCH Health Services t Post Limited 13,500.00 0.00 Canceled 2020-03-15 2020-03-20 2020-04-10 2020-05-15 2020-11-11 ant Selection ui institutionnel PBF hrough PBF Improving Utilization of Qual 02/PI/2020 / spécialistes PBF Individual Consult IDA / D1890 ity RMNCH Health Services t Post Open 60,000.00 0.00 Canceled 2020-03-15 2021-04-18 2020-05-11 2020-06-01 2020-07-06 2021-07-01 pour le niveau central ant Selection hrough PBF Improving Utilization of Qual 03/PI/2020 / spécialistes PBF Individual Consult IDA / D1890 ity RMNCH Health Services t Post Open 60,000.00 0.00 Canceled 2020-03-02 2021-04-18 2020-04-28 2020-05-19 2020-06-23 2021-06-18 pour la zone d'extension ant Selection hrough PBF 12/PI/INAYA/2022 / Recrute Capacity Building and Projec Individual Consult IDA / D5760 Post Limited 25,100.00 0.00 Signed 2022-08-26 2022-09-01 2022-08-31 2022-11-16 2022-09-21 2023-01-11 2022-10-26 2023-04-24 ment d'un spécialiste en Co t Management ant Selection mmunication 14/PI/INAYA/2022 / Recrute Capacity Building and Projec Individual Consult ment d'un spécialiste de sau IDA / D5760 Post Limited 26,500.00 0.00 Signed 2022-08-25 2022-08-31 2022-08-30 2022-11-15 2022-09-20 2023-01-11 2022-10-25 2023-04-23 t Management ant Selection vegardes sociales 17/PI/INAYA/2022 / Recrute Capacity Building and Projec Individual Consult ment d'un assistant pour le S IDA / D5760 Post Limited 11,700.00 11,145.78 Signed 2022-08-25 2022-07-07 2022-08-30 2022-07-15 2022-09-20 2022-07-27 2022-10-25 2022-08-16 2023-04-23 t Management ant Selection pécialiste en Passation des M archés 18/PI/INAYA/2022 / Conventi on entre le Ministère de la Sa nté et l’Agence Nationale de Capacity Building and Projec la Statistique et de l'Analyse IDA / D5760 Post Direct Selection Direct - National 179,521.00 168,316.14 Signed 2022-10-17 2022-08-20 2022-10-27 2022-08-24 2022-12-31 2022-09-20 2023-06-29 t Management Démographique et Economiq ue (ANSADE) relative à la réa lisation de l’enquête nutrition nelle « SMART » 2022 07/PI/INAYA/2022 / Recrute Capacity Building and Projec Individual Consult Open - Internationa Under Implement ment du spécialistes PBF pou IDA / D5760 Post 60,000.00 0.00 2022-12-31 2022-12-01 2023-02-18 2022-12-29 2023-03-11 2023-05-30 2023-04-15 2023-10-12 t Management ant Selection l ation r la zone d'extension 08/PI/INAYA/2022 / Recrute Capacity Building and Projec Individual Consult Under Implement IDA / D5760 Post Open - National 60,000.00 0.00 2022-12-31 2022-12-01 2023-02-18 2022-12-29 2023-03-11 2023-04-15 2023-10-12 ment du spécialistes PBF au t Management ant Selection ation niveau Central 9/PI/IANAYA/2022 / Codificati Capacity Building and Projec Individual Consult on des équipements matériel IDA / D5760 Post Limited 9,700.00 0.00 Under Review 2022-12-31 2022-11-08 2023-01-05 2023-01-26 2023-03-02 2023-08-29 t Management ant Selection s et logistiques du projet 19/PI/INAYA/2022 / Recrute ment d'un consultant interna Capacity Building and Projec Individual Consult tional pour appuyer l'élabora IDA / D5760 Post Limited 16,049.00 0.00 Canceled 2023-02-28 2023-03-05 2023-03-26 2023-04-30 2023-10-27 t Management ant Selection tion des documents de sauve gardes environnementales et sociales 20/PI/INAYA/2022 / Recrute Capacity Building and Projec Individual Consult Pending Impleme IDA / D5760 Post Limited 11,444.00 0.00 2023-03-01 2023-03-06 2023-03-27 2023-05-01 2023-10-28 ment d'un assistant Financier t Management ant Selection ntation du RAF 21/PI/INAYA/2022 / Recrute Capacity Building and Projec Individual Consult Pending Impleme ment d'un consultant interna IDA / D5760 Post Limited 13,351.00 0.00 2023-03-15 2023-03-20 2023-04-10 2023-05-15 2023-11-11 t Management ant Selection ntation tional pour évaluer et mettre à jour SN FBR 22/PI/INAYA/2022 / Recrute Capacity Building and Projec Individual Consult Under Implement IDA / D5760 Post Open - National 19,619.00 0.00 2023-04-03 2022-12-27 2023-05-22 2023-06-12 2023-07-17 2024-01-13 ment d'un comptable t Management ant Selection ation 23/PI/INAYA/2022 / Recrute ment d'un consultant pour la Capacity Building and Projec Individual Consult Under Implement IDA / D5760 Post Limited 11,100.00 0.00 2023-04-30 2023-01-26 2023-05-05 2023-05-26 2023-06-30 2023-12-27 mise à jour de la stratégie co t Management ant Selection ation mmunautaire de la santé co mmunautaire 16/PI/INAYA/2022 / Recrute Capacity Building and Projec Individual Consult IDA / D5760 Post Limited 19,619.00 0.00 Canceled 2022-07-31 2022-07-07 2022-08-05 2022-08-26 2022-09-30 2023-03-29 ment d'un comptable t Management ant Selection 07/PI/INAYA/2021 / Recrute Improving Utilization of Qual ment d'un consultant pour la Individual Consult IDA / D1890 ity RMNCH Health Services t Post Open 17,200.00 0.00 Canceled 2021-05-25 2022-04-13 2021-07-13 2021-08-03 2021-09-07 2022-03-06 mise ajour de la stratégie co ant Selection hrough PBF mmunautaire de la santé co mmunautaire 15/PI/INAYA/2022 / Traductio n des documents essentiels Capacity Building and Projec Individual Consult IDA / D5760 Post Limited 69,735.00 0.00 Canceled 2022-08-31 2022-09-05 2022-09-26 2022-10-31 2023-04-29 du projet ( Manuels des proc t Management ant Selection édures, outils, rapports, etc;) 01/PI/INAYA/2023 / Traductio n des documents essentiels d Capacity Building and Projec Individual Consult Pending Impleme IDA / D5760 Post Limited 51,400.00 0.00 2023-06-30 2023-07-05 2023-07-26 2023-08-30 2024-02-26 u projet ( Manuels des procé t Management ant Selection ntation dures, outils, rapports, etc;) 02/PI/INAYA/2023 / Recrute ment d'un consultant interna Capacity Building and Projec Individual Consult Pending Impleme IDA / D1890 Post Limited 16,500.00 0.00 2023-05-01 2023-05-06 2023-05-27 2023-07-01 2023-12-28 tional pour mettre à jour les t Management ant Selection ntation documents de sauvegardes I NAYA II 03/PI/INAYA/2023 / Recrute ment d'un consultant interna Capacity Building and Projec Individual Consult Pending Impleme tional pour appuyer l'élabora IDA / D1890 Post Limited 17,000.00 0.00 2023-06-30 2023-07-05 2023-07-26 2023-08-30 2023-10-09 t Management ant Selection ntation tion des documents de sauve gardes environnementales IN AYA II 04/PI/INAYA/2023 / Recrute ment d'un consultant interna Capacity Building and Projec Individual Consult Pending Impleme IDA / D1890 Post Limited 17,000.00 0.00 2023-06-30 2023-07-05 2023-07-26 2023-08-30 2023-10-09 tional pour appuyer l'élabora t Management ant Selection ntation tion des documents de sauve gardes sociales INAYA II Page 7 PROCUREMENT PLAN (Textual Part) Project information: Democratic Republic Democratic of Congo - SME Development and Growth Project P160806 Project Implementation agency: CFEF (PPA) Date of the Procurement Plan: November 27, 2017 Period covered by this Procurement Plan: December 2017 – May 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 and revised November 2017) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Borrower’s Public Procurement Law No 10/010 of April 27, 2010 (PPL) and the Manual of Procedures of the PPL as per Borrower’s Decree No 10/22 of June 2, 2010, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (a) Standard Bidding Documents: All standard bidding documents to be used for the Project under NCB shall be found acceptable to the World Bank before their use during the implementation of Project; (b) Eligibility: Eligibility of bidders and acceptability of their goods and services shall not be based on their nationality and/or their origin; and association with a national firm shall not be a condition for participation in a bidding process. Therefore, except for the ineligibility situations referred to in paragraphs 1.10(a) (i) and 1.10(a) (ii) of the Procurement Guidelines, the eligibility of bidders must be based solely on their qualification, experience and capacity to carry out the contract related to the specific bidding process; (c) Advertising and Bid Preparation Time: Bidding opportunities shall be advertised at least in a national newspaper of wide circulation and on the website of the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) and bidders should be given at least 30 days from the date of invitation to bid or the date of availability of the bidding documents, whichever is later; (d) Criteria for Qualification of Bidders: Qualification criteria shall only concern the bidder’s capability and resources to perform the contract taking into account objective and measurable factors. Such criteria for qualification of bidders shall be clearly specified in the bidding documents; (e) Bid Evaluation and Contract Award: A contract shall be awarded to the substantially responsive and lowest evaluated bidder provided that such bidder meets the qualification criteria specified in the bidding documents. No scoring system shall be allowed for the evaluation of bids, and no “blanket” limitation to the number of lots which can be awarded to a bidder shall apply. The criteria for bid evaluation and the contract award conditions shall be clearly specified in the bidding documents; (f) Preferences: No preference shall be given to domestic/regional bidders; to domestically/regionally manufactured goods; and to bidders forming a joint venture with a national firm or proposing national sub-contractors or carrying out economic activities in the territory of the Recipient; (g) Publication of Contract Award: Information on all contract awards shall be published in at least a national newspaper of wide circulation or in the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) web-site; (h) Fraud and Corruption: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy to sanction firms or individuals found to have engaged in fraud and corruption as set forth in the Procurement Guidelines; (i) Inspection and Audit Rights: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy with respect to inspection and audit of accounts, records and other documents relating to the bid submission and contract performance; (j) Requirement for administrative documents and/or tax clearance certificate: The bidding documents shall not require foreign bidders to produce any administrative or tax related certificates prior to confirmation of awarding a contract; and (k) Modifications of a Signed Contract: Any change in the contract amount which, singly or combined with all previous changes, increases the original contract amount by fifteen (15) percent or more must be done through an amendment to the signed contract instead of signing a new contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Congo, Democratic Republic of : DRC- SME Development and Growth Project PLAN General Information Country: Congo, Democratic Republic of Bank’s Approval Date of the Original Procurement Plan: 2019-03-26 Revised Plan Date(s): (comma delineated, leave blank if 2023-05-24 none) Project ID: P160806 GPN Date: 2019-08-22 Project Name: DRC- SME Development and Growth Project Loan / Credit No: IDA / 62870 Unité de Coordination d'Appui au Développement des Micros, Petites et Moyennes Entreprises Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process S Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Comple Description Component Review Type Method Amount (U ount (US$ and Recommendatio Signed Contract o. h cess (Y/N) isk ocument Type tatus n Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes tion S$) ) n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ZR-UCP-PADMPME-284274- National Procure CW-RFQ / Réhabilitations lég Component 3: Capacity buil ment Document - Request for Quot Single Stage - One Under Impl 2022-11-2 ères ou rafraîchissement et IDA / 62870 ding and Project Manageme Post Limited 1 Envelope proce 20,000.00 0.00 2022-03-29 2022-06-06 2022-05-24 ations Envelope ementation 0 petites extension pour l'app nt ss (Non Bank-SP ui à l'institution CASPOF dan D) s le cadre de SDE ZR-UCP-PADMPME-299192- National Procure CW-RFQ / Petits travaux et r Component 3: Capacity buil ment Document - Pending Im Request for Quot Single Stage - One 2023-03-0 éhabilitaion des batîments à IDA / 62870 ding and Project Manageme Post Limited 1 Envelope proce 66,000.00 0.00 plementatio 2022-07-08 2022-09-02 ations Envelope 1 Matadi de l'ANADEC, Commi nt ss (Non Bank-SP n ssariat aux PME, DP PME et D) DP Genre, Famille et Enfant National Procure ZR-UCP-PADMPME-323665- ment Document - Pending Im CW-RFQ / Travaux d'Aménag Component 2. SME Develop Request for Quot Single Stage - One 2023-07-1 IDA / 62870 Post Limited 1 Envelope proce 350,000.00 0.00 plementatio 2022-11-18 2023-01-13 ement des voies intérieures ment ations Envelope 2 ss (Non Bank-SP n pour Silikin Village/ COTEX D) ZR-UCP-PADMPME-323756- National Procure CW-RFQ / Réhabilitation des ment Document - Component 2. SME Develop Request for Quot Single Stage - One Under Impl 2023-07-1 Bureaux abritant la Direction IDA / 62870 Post Limited 1 Envelope proce 90,000.00 0.00 2022-11-18 2023-01-13 ment ations Envelope ementation 2 Provinciale d’ ANADEC à Kin ss (Non Bank-SP shasa, dans le cadre de l'Ap D) pui institutionnel de SDE. ZR-UCP-PADMPME-323668- CW-RFB / Travaux d'Aliment National Procure ation en électricité de Silikin ment Document - Pending Im Component 2. SME Develop Single Stage - One 2023-11-0 Village dans la Concession C IDA / 62870 Post Request for Bids Limited 1 Envelope proce 950,000.00 0.00 plementatio 2023-01-15 2023-01-20 2023-03-03 2023-04-02 2023-05-07 ment Envelope 3 otex SA à Kinshasa: Réseau ss (Non Bank-SP n de desserte en électricité du D) bâtiment-Réseau électrique pour desservir les différents bureaux National Procure ZR-UCP-PADMPME-299370- Component 3: Capacity buil ment Document - Request for Quot Single Stage - One 2023-03-0 CW-RFQ / Réhabilitation de l' IDA / 62870 ding and Project Manageme Post Limited 1 Envelope proce 30,000.00 0.00 Canceled 2022-07-15 2022-09-09 ations Envelope 8 ANADEC Lubumbashi nt ss (Non Bank-SP D) ZR-UCP-PADMPME-354279- CW-DIR / Contractualisation Request for Quot avec l'Entreprise HB ENGINE ations - Small Wo Pending Im ERING pour la réalisation de Component 2. SME Develop 2023-12-0 IDA / 62870 Post Direct Selection Direct - National rks (Emergency) 10,677.00 0.00 plementatio 2023-04-30 2023-05-05 2023-06-09 s travaux de réhabilitations l ment 6 SPD -Non Compet n égères ou rafraichissement itive pour l’appui au Secrétariat G énéral du genre famille et e nfant dans le cadre de SDE ZR-UCP-PADMPME-360363- CW-DIR / Contractualisation Request for Quot Pending Im par entente directe avec Pro Component 2. SME Develop 2023-12-2 IDA / 62870 Post Direct Selection Direct - National ations (Non Bank 791,128.08 0.00 plementatio 2023-05-14 2023-05-19 2023-06-23 ton en vue de l’exécution de ment 0 -SPD) n s travaux d’électricité sur le site de Silikin Village dans le cadre de l’accord avec COTE X National Procure ZR-UCP-PADMPME-299373- Component 3: Capacity buil ment Document - CW-RFQ / Réhabilitation des Request for Quot Single Stage - One 2023-03-0 IDA / 62870 ding and Project Manageme Post Limited 1 Envelope proce 30,000.00 0.00 Canceled 2022-07-15 2022-11-11 2022-09-09 bâtiments de l'ANADEC et la ations Envelope 8 nt ss (Non Bank-SP Division provinciale des PME D) à GOMA ZR-UCP-PADMPME-362015- CW-RFQ / Travaux de réhabil Component 1: Support entr Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 itation du batîment et de clo IDA / 62870 epreneurship opportunities Post Limited ations (Non Bank 30,000.00 0.00 plementatio 2023-06-17 2023-08-12 ations Envelope 8 isennement des bureaux e for youth and women -SPD) n vant abriter l'Antenne du GU CE/Matadi ZR-UCP-PADMPME-365529- CW-RFQ / Travaux d'Aménag Request for Quot Pending Im ement du hangar afin de cré Component 2. SME Develop Request for Quot Single Stage - One 2024-02-2 IDA / 62870 Post Limited ations (Non Bank 184,652.00 0.00 plementatio 2023-07-01 2023-08-26 er des espaces de bureaux p ment ations Envelope 2 -SPD) n our 30 PME au moins (cloiso n, etc) dans le cadre du Prot ocole d'accord avec Ingenio us City ZR-UCP-PADMPME-365539- CW-RFQ / Travaux Aménage Request for Quot Pending Im Component 2. SME Develop Request for Quot 2024-02-2 ment de 40 places de parkin IDA / 62870 Post ations (Non Bank 80,000.00 0.00 plementatio 2023-07-01 2023-08-26 ment ations 2 g dans le protocole d'accord -SPD) n du PADMPME avec Ingenious City GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus n Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-UCP-PADMPME-164487- GO-DIR / Firme Tomate pour Component 3: Capacity buil l'acquisition du logiciel Tom IDA / 62870 ding and Project Manageme Post Direct Selection Direct 75,000.00 36,239.70 Signed 2020-04-30 2020-03-31 2020-05-05 2020-02-12 2020-06-09 2020-07-14 2020-12-06 Monitoring , l'installation, le nt parametrage et fomation de s utilisateurs au PADMPME ZR-UCP-PADMPME-164510- Component 3: Capacity buil GO-RFQ / Acquisition de mat Request for Quot Single Stage - One IDA / 62870 ding and Project Manageme Post Limited 260,000.00 255,000.00 Completed 2020-05-03 2020-07-24 2020-06-28 2020-09-19 2020-12-25 2020-11-11 ériels roulant pour les besoi ations Envelope nt ns de l'UCP-PADMPME ZR-UCP-PADMPME-167524- Component 3: Capacity buil GO-RFQ / Acquisition de mat Request for Quot Single Stage - One IDA / 62870 ding and Project Manageme Post Limited 12,150.00 16,850.00 Completed 2020-05-05 2020-07-13 2020-06-30 2020-08-19 2020-12-27 2020-08-27 ériel informatique suppléme ations Envelope nt ntaire pour les besoins de l' UCP PADMPME ZR-UCP-PADMPME-167526- Component 3: Capacity buil GO-RFQ / Acquisition de four Request for Quot Single Stage - One IDA / 62870 ding and Project Manageme Post Limited 26,040.00 12,168.78 Completed 2020-05-04 2020-10-29 2020-06-29 2020-11-20 2020-12-26 2020-12-16 nitures de bureau et conso ations Envelope nt mmables informatiques ZR-UCP-PADMPME-167528- Component 3: Capacity buil GO-RFQ / Acquisition de mo Request for Quot Single Stage - One IDA / 62870 ding and Project Manageme Post Limited 6,000.00 7,174.60 Completed 2020-05-05 2020-07-15 2020-06-30 2020-09-18 2020-12-27 2020-09-24 biliers de bureau supplémen ations Envelope nt taire pour les besoins de l'U CP PADMPME ZR-UCP-PADMPME-205735- Component 3: Capacity buil GO-RFQ / Acquisition de mat Request for Quot Single Stage - One IDA / 62870 ding and Project Manageme Post Open - National 45,000.00 42,125.50 Completed 2020-12-21 2021-02-15 2021-03-13 2021-08-14 2021-03-27 ériel performant pour facilite ations Envelope nt r les séances de visioconfére nce à l'UCP. Page 1 ZR-UCP-PADMPME-218525- GO-RFB / Acquisition de télé Component 1: Support entr Single Stage - One phones mobiles ( portables) IDA / 62870 epreneurship opportunities Post Request for Bids Open - National 700,000.00 396,720.00 Signed 2021-03-02 2021-02-25 2021-03-07 2021-03-04 2021-04-18 2021-03-30 2021-05-18 2021-04-19 2021-06-22 2021-06-15 2021-12-19 Envelope pour les femmes bénéficiair for youth and women es du FIP à Goma et Lubum bashi ZR-UCP-PADMPME-226485- GO-RFQ / Acquisition de four Component 3: Capacity buil nitures de bureau pour l’unit Request for Quot Single Stage - One IDA / 62870 ding and Project Manageme Post Limited 7,200.00 4,563.21 Completed 2021-04-17 2021-04-06 2021-06-12 2021-06-10 2021-12-09 2021-07-13 é de coordination du projet ations Envelope nt de développement des micr os, petites et moyennes entr eprises ZR-UCP-PADMPME-226486- GO-RFQ / Acquisition de con Component 3: Capacity buil sommables informatiques p Request for Quot Single Stage - One IDA / 62870 ding and Project Manageme Post Limited 4,520.00 3,780.00 Completed 2021-04-17 2021-04-28 2021-06-12 2021-06-03 2021-12-09 2021-06-09 our l’unité de coordination d ations Envelope nt u projet de développement des micros, petites et moye nnes entreprises ZR-UCP-PADMPME-226600- GO-RFQ / Acquisition de 360 Component 1: Support entr Request for Quot Single Stage - One 0 cartes SIM ainsi que l'abon IDA / 62870 epreneurship opportunities Post Limited 220,000.00 216,000.00 Signed 2021-05-01 2021-04-29 2021-06-26 2021-07-22 2021-12-23 ations Envelope nement internet pour les tél for youth and women éphones des femmes entrep reneures ZR-UCP-PADMPME-226607- Component 3: Capacity buil GO-RFQ / Acquisition d’un gr Request for Quot Single Stage - One IDA / 62870 ding and Project Manageme Post Limited 18,000.00 14,585.81 Completed 2021-03-31 2021-03-24 2021-05-26 2021-05-21 2021-11-22 2021-05-27 oupe électrogène de l’Anten ations Envelope nt ne provinciale de Lubumbas hi ZR-UCP-PADMPME-243600- Component 3: Capacity buil Request for Quot Single Stage - One Under Imple GO-RFQ / Acquisition complé IDA / 62870 ding and Project Manageme Post Limited 15,000.00 0.00 2021-08-14 2021-09-03 2021-10-09 2022-04-07 ations Envelope mentation mentaires des mobiliers de nt bureau ZR-UCP-PADMPME-261700- GO-RFB / Acquisition de télé Component 1: Support entr Single Stage - One Under Imple phones mobiles (portables) IDA / 62870 epreneurship opportunities Post Request for Bids Open - National 500,000.00 0.00 2022-01-10 2022-01-27 2022-01-15 2022-10-05 2022-02-26 2022-02-28 2022-03-28 2022-03-11 2022-05-02 2022-10-29 Envelope mentation pour les femmes bénéficiair for youth and women es de la FIP à Kinshasa et à Matadi ZR-UCP-PADMPME-261702- Component 3: Capacity buil GO-RFQ / Acquisition et insta Request for Quot Single Stage - One Under Imple IDA / 62870 ding and Project Manageme Post Limited 25,000.00 0.00 2021-11-10 2021-10-29 2022-01-05 2022-07-04 llation de matériel informati ations Envelope mentation nt que pour le Ministère ZR-UCP-PADMPME-261714- Component 3: Capacity buil GO-RFQ / Acquisition des Fo Request for Quot Single Stage - One IDA / 62870 ding and Project Manageme Post Limited 7,200.00 8,623.67 Signed 2021-12-18 2022-03-02 2022-02-12 2022-05-04 2022-08-11 urnitures de bureau pour l’U ations Envelope nt nité de Coordination du Proj et ZR-UCP-PADMPME-283804- GO-DIR / Acquisition avec T Component 3: Capacity buil OMATE la licence TOM²PRO Under Imple IDA / 62870 ding and Project Manageme Post Direct Selection Direct 28,000.00 0.00 2022-05-16 2022-05-09 2022-05-21 2022-06-25 2022-12-22 WEB multi-projet +3 clés du mentation nt ngle supplémentaires + for mation des utilisateurs sur l es nouvelles fonctionnalités . ZR-UCP-PADMPME-283949- Component 1: Support entr GO-RFB / Recrutement d'une Single Stage - One Under Imple IDA / 62870 epreneurship opportunities Post Request for Bids Open - National 300,000.00 0.00 2022-03-28 2022-04-22 2022-04-02 2022-04-22 2022-05-14 2022-06-13 2022-07-18 2023-01-14 firme en charge de la logisti Envelope mentation for youth and women que de la formation IP pour Kinshasa et Matadi ZR-UCP-PADMPME-283960- Component 3: Capacity buil Request for Quot Single Stage - One GO-RFQ / Acquisition fournit IDA / 62870 ding and Project Manageme Post Limited 7,200.00 0.00 Canceled 2022-05-07 2022-07-02 2022-12-29 ations Envelope ure de bureau nt ZR-UCP-PADMPME-284027- Component 3: Capacity buil GO-RFQ / Acquisition des co Request for Quot Single Stage - One IDA / 62870 ding and Project Manageme Post Limited 47,200.00 22,078.00 Signed 2022-05-21 2022-03-02 2022-07-16 2022-05-04 2023-01-12 nsommables informatiques ations Envelope nt pour l'UCP-PADMPME ZR-UCP-PADMPME-284896- Component 3: Capacity buil Under Imple GO-DIR / Abonnement intern IDA / 62870 ding and Project Manageme Post Direct Selection Direct 94,000.00 0.00 2022-03-28 2022-02-08 2022-04-02 2022-05-07 2022-11-03 mentation et avec la Firme Liquid Tele nt com ZR-UCP-PADMPME-284196- GO-RFQ / Acquisition et insta llation des fournitures et mo Component 3: Capacity buil Request for Quot Single Stage - One Under Imple biliers des bureaux pour l'ap IDA / 62870 ding and Project Manageme Post Limited 20,900.00 0.00 2022-04-12 2022-11-01 2022-06-07 2022-12-04 ations Envelope mentation pui aux institutions privées e nt t publiques de la ville de Kin shasa dans le cadre de SDE( OPEC, COPEMECO, FENAPEC , PFE, et PJE) ZR-UCP-PADMPME-284211- GO-RFQ / Acquisition et insta llation de petits parcs d'ordi Component 3: Capacity buil nateurs pour l'appui des inst Request for Quot Single Stage - One IDA / 62870 ding and Project Manageme Post Open - National 69,000.00 68,145.36 Signed 2022-04-05 2022-05-31 2022-08-06 2022-11-27 itutions privées et publiques ations Envelope nt de la ville de Kinshasa dans l e cadre de SDE (OPEC,CASP OF, FEC, CNFE,COPEMECO,F ENAPEC,Mini.PME-SG, Min. G enre-SG, PFE et PJE) ZR-UCP-PADMPME-284255- GO-RFQ / Acquisition équipe Component 3: Capacity buil ments pour exposition et ac Request for Quot Single Stage - One Pending Impl IDA / 62870 ding and Project Manageme Post Limited 21,500.00 0.00 2022-05-05 2022-06-30 2022-12-27 halandage pour appui des in ations Envelope ementation nt stitutions privées de la ville de Kinshasa (CNFE et COPE MECO) ZR-UCP-PADMPME-261805- Component 3: Capacity buil GO-RFB / Appui institutionne Single Stage - One IDA / 62870 ding and Project Manageme Post Request for Bids Open - National 203,000.00 0.00 Canceled 2022-02-21 2022-02-26 2022-04-09 2022-05-09 2022-06-13 2022-12-10 l à la réhabilitation des bure Envelope nt aux des facilitateurs SDE ZR-UCP-PADMPME-261795- Component 3: Capacity buil Single Stage - One GO-RFB / Appui institutionne IDA / 62870 ding and Project Manageme Post Request for Bids Open - National 759,900.00 0.00 Canceled 2022-03-14 2022-03-19 2022-04-30 2022-05-30 2022-07-04 2022-12-31 Envelope l à l'équipement pour les fac nt ilitateurs SDE ZR-UCP-PADMPME-261777- Component 3: Capacity buil GO-RFQ / Acquisition des co Request for Quot Single Stage - One IDA / 62870 ding and Project Manageme Post Limited 20,000.00 0.00 Canceled 2021-12-18 2022-02-12 2022-08-11 nsommables informatiques ations Envelope nt pour les besoins de l'UCP-PA DMPME ZR-UCP-PADMPME-295834- Component 3: Capacity buil Request for Quot Single Stage - One GO-RFQ / Acquisition d'un lo IDA / 62870 ding and Project Manageme Post Limited 16,000.00 16,350.00 Signed 2022-06-06 2022-06-29 2022-08-01 2022-08-23 2023-01-28 ations Envelope giciel de signature électroni nt que des contrats ZR-UCP-PADMPME-295842- GO-RFQ / Acquisition et insta Component 3: Capacity buil Request for Quot Single Stage - One Under Imple llation de matériels de visio- IDA / 62870 ding and Project Manageme Post Limited 46,000.00 0.00 2022-05-28 2022-07-06 2022-07-23 2023-01-19 ations Envelope mentation conférence pour les instituti nt ons bénéficiaires de l'appui aux SDE ZR-UCP-PADMPME-299184- GO-RFQ / Acquisition des ma Component 3: Capacity buil Request for Quot Single Stage - One Under Imple tériels de visioconférence po IDA / 62870 ding and Project Manageme Post Limited 117,700.00 0.00 2022-07-08 2022-09-01 2022-09-02 2023-03-01 ations Envelope mentation ur l'appui institutionnels à M nt atadi, Lubumbashi et Goma Page 2 ZR-UCP-PADMPME-299193- GO-RFQ / Acquisition des Fo Component 3: Capacity buil Request for Quot Single Stage - One Under Imple urnitures et mobiliers des bu IDA / 62870 ding and Project Manageme Post Limited 50,000.00 0.00 2022-07-08 2022-11-01 2022-09-02 2023-03-01 ations Envelope mentation reaux pour les institutions à nt appuyer dans le cadre des S DE à Matadi ZR-UCP-PADMPME-299369- GO-RFQ / Acquisition des Fo Component 3: Capacity buil Request for Quot Single Stage - One Under Imple urnitures et mobiliers des bu IDA / 62870 ding and Project Manageme Post Limited 43,800.00 0.00 2022-07-15 2022-10-12 2022-09-09 2023-03-08 ations Envelope mentation reaux pour les institutions à nt appuyer dans le cadre des S DE à Lubumbashi ZR-UCP-PADMPME-299376- Component 3: Capacity buil GO-RFQ / Acquisition des Fo Request for Quot Single Stage - One Under Imple IDA / 62870 ding and Project Manageme Post Limited 43,800.00 0.00 2022-07-15 2022-10-12 2022-09-09 2023-03-08 urnitures et mobiliers des bu ations Envelope mentation nt reaux à Goma/ SDE ZR-UCP-PADMPME-317612- GO-RFQ / Acquisition de 420 Component 1: Support entr Request for Quot Single Stage - One Under Imple 0 cartes SIM ainsi que l'abon IDA / 62870 epreneurship opportunities Post Limited 252,000.00 0.00 2022-10-21 2022-09-21 2022-12-16 2023-06-14 ations Envelope mentation nement internet pour les tél for youth and women éphones des femmes entrep reneures ZR-UCP-PADMPME-320613- GO-RFQ / Acquisition et insta llation de matériels informati ques pour les institutions à a Component 2. SME Develop Request for Quot Single Stage - One Pending Impl ppuyer par le PADMPME dan IDA / 62870 Post Limited 110,000.00 0.00 2022-10-16 2022-12-11 2023-06-09 ment ations Envelope ementation s le cadre de SDE dans les vi lles de Matadi, Goma et Lub umbashi (SG PMEA, SG GFE, OPEC/ANADEC, CASPOF, FEC , CNFE et COPEMECO) ZR-UCP-PADMPME-344130- GO-RFQ / Fourniture et instal Component 3: Capacity buil lation d'un Groupe Electrogè Request for Quot Single Stage - One Pending Impl IDA / 62870 ding and Project Manageme Post Limited 20,000.00 0.00 2023-03-25 2023-05-20 2023-11-16 ne de 20 KVA pour l'antenne ations Envelope ementation nt de Matadi dans le cadre de l' exécution du Projet PADMPM E ZR-UCP-PADMPME-344132- Component 3: Capacity buil GO-RFQ / Acquisition et insta Request for Quot Single Stage - One Pending Impl IDA / 62870 ding and Project Manageme Post Limited 125,000.00 0.00 2023-03-25 2023-05-20 2023-11-16 llation des matériels informa ations Envelope ementation nt tiques supplémentaires pour l'UCP PADMPME ZR-UCP-PADMPME-344135- Component 3: Capacity buil GO-RFQ / Acquisition de mo Request for Quot Single Stage - One Pending Impl IDA / 62870 ding and Project Manageme Post Limited 16,000.00 0.00 2023-03-25 2023-05-20 2023-11-16 biliers de bureaux complém ations Envelope ementation nt entaires pour l'UCP PADMPM E ZR-UCP-PADMPME-344163- Component 3: Capacity buil GO-RFQ / Acquisition deux v Request for Quot Single Stage - One Pending Impl IDA / 62870 ding and Project Manageme Post Limited 140,500.00 0.00 2023-03-25 2023-05-20 2023-11-16 éhicules supplémentaires po ations Envelope ementation nt ur l’UCP/PADMPME ZR-UCP-PADMPME-299187- GO-RFB / Acquisition petits p Component 3: Capacity buil Single Stage - One arcs d’ordinateurs pour les i IDA / 62870 ding and Project Manageme Post Request for Bids Open - National 91,000.00 0.00 Canceled 2022-07-03 2022-07-08 2022-08-19 2022-09-18 2022-10-23 2023-04-21 Envelope nstitutions à appuyer dans l nt e cadre des SDE à Matadi, G oma et Lubumbashi ZR-UCP-PADMPME-284178- GO-RFB / Acquisition et insta llation des matériels de petit Component 3: Capacity buil es salles visio-conférence po Single Stage - One IDA / 62870 ding and Project Manageme Post Request for Bids Open - National 88,000.00 0.00 Canceled 2022-04-01 2022-04-06 2022-05-18 2022-06-17 2022-07-22 2023-01-18 ur appui aux institutions priv Envelope nt ées et publiques dans le cad re de SDE (COPEC, CASPOF, FEC,COPEMECO,FENAPEC, C NFE, Min.PME-SG, MinGenre. -SG) ZR-UCP-PADMPME-360662- GO-RFB / Acquisition et insta llation de 4 hangars sur un e Component 2. SME Develop Single Stage - One Pending Impl space de 3800 m2 pour 25 IDA / 62870 Post Request for Bids Limited 940,000.00 0.00 2023-05-15 2023-05-20 2023-07-01 2023-07-31 2023-09-04 2024-03-02 ment Envelope ementation à 30 PME supplémentaires d ans le cadre de l'Accord ave c Virunga pour la mise en oe uvre en des centres de PME ZR-UCP-PADMPME-360663- GO-RFQ / Alimentation en él ectricité de 40 PMEs dans le Component 2. SME Develop Request for Quot Single Stage - One Pending Impl IDA / 62870 Post Limited 90,720.00 0.00 2023-05-20 2023-07-15 2024-01-11 cadre de l'Accord de partena ment ations Envelope ementation riat avec VIRUNGA dans le c adre de la mise en oeuvre d es Centre des PME ZR-UCP-PADMPME-360690- GO-RFQ / Raccordement et i nstallation du site PEC/Goma Component 2. SME Develop Request for Quot Single Stage - One Pending Impl IDA / 62870 Post Limited 200,339.00 0.00 2023-05-20 2023-07-15 2024-01-11 en eau dans le cadre de l'Ac ment ations Envelope ementation cord de partenariat avec VIR UNGA dans le cadre de la mi se en oeuvre des Centre des PME ZR-UCP-PADMPME-362010- GO-RFQ / Acquisition des mo Component 1: Support entr Request for Quot Single Stage - One Pending Impl biliers de bureau pour l'Ante IDA / 62870 epreneurship opportunities Post Limited 10,000.00 0.00 2023-06-17 2023-08-12 2024-02-08 ations Envelope ementation nne de Matadi du Guichet U for youth and women nique de Création d'Entrepri se ZR-UCP-PADMPME-362011- GO-RFQ / Acquisition des ma Component 1: Support entr Request for Quot Single Stage - One Pending Impl tériels informatiques pour l'a IDA / 62870 epreneurship opportunities Post Limited 75,167.00 0.00 2023-06-17 2023-08-12 2024-02-08 ations Envelope ementation ntenne de Matadi du Guiche for youth and women t Unique de Création d'Entre prise ZR-UCP-PADMPME-362012- Component 1: Support entr GO-RFQ / Acquisition d'un Pi Request for Quot Single Stage - One Pending Impl IDA / 62870 epreneurship opportunities Post Limited 50,000.00 0.00 2023-06-17 2023-08-12 2024-02-08 ck-Up pour l'Antenne de Mat ations Envelope ementation for youth and women adi du Guichet Unique de Cr éation d'Entreprise ZR-UCP-PADMPME-362028- GO-RFQ / Acquisition des fou Component 1: Support entr rnitures de bureaux et cons Request for Quot Single Stage - One Pending Impl IDA / 62870 epreneurship opportunities Post Limited 17,200.00 0.00 2023-06-17 2023-08-12 2024-02-08 ommables informatiques po ations Envelope ementation for youth and women ur l'antenne de Matadi du G uichet Unique de Création d' entreprise ZR-UCP-PADMPME-362054- GO-RFQ / Acquisition et insta Component 1: Support entr llation des panneaux solaire Request for Quot Single Stage - One Pending Impl IDA / 62870 epreneurship opportunities Post Limited 24,807.72 0.00 2023-06-24 2023-08-19 2024-02-15 s pour les serveurs et matéri ations Envelope ementation for youth and women els informatiques du Guichet Unique de Création d'Entrep rise/ Antenne de Matadi ZR-UCP-PADMPME-365569- GO-RFQ / Acquisition et insta Component 2. SME Develop Request for Quot Pending Impl llation des panneaux solaire IDA / 62870 Post 95,025.00 0.00 2023-07-08 2023-09-02 2024-02-29 ment ations ementation s dans le cadre de l'accord d e partenariat avec Ingenious City ZR-UCP-PADMPME-365578- GO-RFQ / Acquisition et insta Component 2. SME Develop Request for Quot Single Stage - One Pending Impl llation de la fibre optique po IDA / 62870 Post Limited 72,000.00 0.00 2023-07-08 2023-09-02 2024-02-29 ment ations Envelope ementation ur 40 bureaux dans le cadre du protocole d'accord avec I ngenious City Page 3 ZR-UCP-PADMPME-365617- GO-RFQ / Travaux de forage Component 2. SME Develop Request for Quot Single Stage - One Pending Impl IDA / 62870 Post Limited 157,232.00 0.00 2023-07-08 2023-09-02 2024-02-29 dans le cadre de la mise en ment ations Envelope ementation œuvre du centre de PME de Virunga ZR-UCP-PADMPME-365624- GO-DIR / Travaux de raccord Component 2. SME Develop Pending Impl ement en eau potable par la IDA / 62870 Post Direct Selection Direct - National 43,107.00 0.00 2023-07-10 2023-07-15 2023-08-19 2024-02-15 ment ementation REGIDESO dans le cadre de l a mise en oeuvre des CPME Virunga NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus n Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-UCP-PADMPME-154549- NC-RFQ / Selection d'une ag ence d'organisation évenem Component 3: Capacity buil Request for Quot Single Stage - One entielle pour l'assistance à l' IDA / 62870 ding and Project Manageme Post Limited 150,000.00 77,453.20 Completed 2020-01-25 2020-01-24 2020-03-21 2020-02-07 2020-09-17 2020-03-19 ations Envelope organisation du Lancement nt solonnel et de l'atelier techn ique de présentation du proj et PADMPME ZR-UCP-PADMPME-167532- Component 3: Capacity buil Request for Quot Single Stage - One NC-RFQ / Service d'entretie IDA / 62870 ding and Project Manageme Post Limited 4,800.00 4,529.96 Completed 2020-05-05 2020-09-23 2020-06-30 2020-11-19 2020-12-27 2021-04-30 ations Envelope n de matériel de climatisatio nt n ZR-UCP-PADMPME-200922- Component 3: Capacity buil NC-DIR / Location de la band IDA / 62870 ding and Project Manageme Post Direct Selection Direct 133,632.00 133,408.00 Completed 2020-10-21 2020-12-02 2020-10-22 2020-03-02 2020-10-25 2020-07-18 2021-10-25 2021-08-10 e passante auprès de la firm nt e GBS pour la connection int ernet ZR-UCP-PADMPME-205582- NC-DIR / Contractualisation Component 1: Support entr avec la firme HOLOGRAM po IDA / 62870 epreneurship opportunities Post Direct Selection Direct 97,442.00 97,442.00 Signed 2020-11-23 2020-11-20 2020-11-28 2020-09-11 2021-01-02 2021-03-26 2021-07-01 ur l'informatisation du proce for youth and women ssus de gestion de l'administ ration des permis de constru ire ZR-UCP-PADMPME-226581- NC-RFB / Recrutement d'un Cabinet en charge de l’orga Component 1: Support entr Single Stage - One nisation matérielle (support) IDA / 62870 epreneurship opportunities Post Request for Bids Open - National 300,000.00 227,125.00 Signed 2021-04-19 2021-05-07 2021-04-24 2021-08-16 2021-06-05 2021-06-15 2021-07-05 2021-06-29 2021-08-09 2021-09-08 2022-02-05 Envelope de la formation IP au profit d for youth and women es femmes micro-entrepren eures dans les villes de Gom a et Lubumbashi ZR-UCP-PADMPME-226588- NC-RFB / Recrutement d'un Component 1: Support entr Single Stage - One cabinet en charge de l’organ IDA / 62870 epreneurship opportunities Post Request for Bids Open - National 500,000.00 446,200.20 Signed 2021-04-19 2021-05-07 2021-04-24 2021-06-05 2021-06-15 2021-07-05 2021-06-29 2021-08-09 2021-09-18 2022-02-05 Envelope isation matérielle (support) for youth and women de la formation STEP sous la supervision du cabinet MOV E ZR-UCP-PADMPME-284226- NC-RFQ / Installation Intrane Component 3: Capacity buil t dans les institutions privée Request for Quot Single Stage - One Under Imple IDA / 62870 ding and Project Manageme Post Limited 25,500.00 0.00 2022-03-21 2022-07-06 2022-05-16 2022-11-12 s et publiques de la ville de ations Envelope mentation nt Kinshasa (COPEC,CASPOF,FE C,COPEMECO,FENAPEC,Min. PME-SG,Min.GENRE-SG,PFE et PJE) ZR-UCP-PADMPME-303583- NC-RFQ / Fourniture d’une p Component 3: Capacity buil Request for Quot Single Stage - One Under Imple olice d’assurance de santé e IDA / 62870 ding and Project Manageme Post Limited 72,000.00 0.00 2022-07-16 2022-07-01 2022-09-10 2023-03-09 ations Envelope mentation n faveur des agents de l’UCP nt -PADMPME et des membres de leurs familles ZR-UCP-PADMPME-327537- Component 3: Capacity buil NC-RFQ / Acquisition d'une P Request for Quot Single Stage - One Pending Impl IDA / 62870 ding and Project Manageme Post Limited 95,000.00 0.00 2023-07-21 2023-09-15 2024-03-13 olice d’assurance pour les so ations Envelope ementation nt ins de santé agents PADMPM E ZR-UCP-PADMPME-356595- Component 3: Capacity buil NC-DIR / Protocole d'Accord Pending Impl IDA / 62870 ding and Project Manageme Post Direct Selection Direct - National 5,500.00 0.00 2023-04-23 2023-04-28 2023-06-02 2023-11-29 avec la RTNC pour la diffusio ementation nt n d'un programme sur les ré sultats du PADMPME ZR-UCP-PADMPME-284242- Component 3: Capacity buil NC-RFQ / Développement ba Request for Quot Single Stage - One IDA / 62870 ding and Project Manageme Post Limited 22,500.00 0.00 Canceled 2022-04-25 2022-06-20 2022-12-17 se des données/cartographi ations Envelope nt es actualisations et accessib les ZR-UCP-PADMPME-356600- Component 3: Capacity buil NC-DIR / Contractualisation Pending Impl IDA / 62870 ding and Project Manageme Post Direct Selection Direct - National 2,500.00 0.00 2023-04-30 2023-05-05 2023-06-09 2023-12-06 avec Canal Kin pour la diffus ementation nt ion d'un programme sur les résultats du PADMPME. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Techni Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) t (US$) Notice equest for Proposals as Issued Proposals / Minutes cal Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-UCP-PADMPME-106197- CS-QBS / Consultant firme (c Component 2. SME Develop Quality Based Sel Open - Internation abinet/ONG) pour la mise en IDA / 62870 Prior 4,800,000.00 0.00 Canceled 2019-04-15 2019-04-12 2019-05-15 2019-05-15 2019-06-28 2019-07-26 2019-08-25 2019-09-24 2019-10-29 2020-10-28 ment ection al ouvre des Centres de Petites et Moyennes Entreprises ZR-UCP-PADMPME-106289- CS-QBS / Recrutement d'un Component 1: Support entr Quality Based Sel Open - Internation Consultant firme (cabinet/O IDA / 62870 epreneurship opportunities Prior 15,000,000.00 0.00 Canceled 2019-05-20 2019-04-12 2019-06-17 2019-05-16 2019-07-31 2019-08-28 2019-09-27 2019-10-27 2019-12-01 2020-11-30 ection al NG) pour la mise en oeuvre for youth and women du soutien aux femmes entr epreneurs ZR-UCP-PADMPME-106312- CS-QBS / Recrutement d'un Component 1: Support entr Quality Based Sel Open - Internation Consultant firme (Cabinet/O IDA / 62870 epreneurship opportunities Prior 8,000,000.00 0.00 Canceled 2019-06-14 2019-07-14 2019-08-27 2019-09-24 2019-10-24 2019-11-23 2019-12-28 2020-12-27 ection al NG) chargée de la dissémin for youth and women ation des textes de lois sur l e genre ZR-UCP-PADMPME-106187- CS-QBS / Recrutement d'un Component 1: Support entr Quality Based Sel Open - Internation Consultant firme (Cabinet/O IDA / 62870 epreneurship opportunities Prior 54,000,000.00 0.00 Canceled 2019-03-31 2019-04-12 2019-04-30 2019-05-15 2019-06-13 2019-07-11 2019-08-10 2019-09-09 2019-10-14 2022-10-13 ection al NG) pour la mise en oeuvre for youth and women des Concours des Plans d'Aff aires ZR-UCP-PADMPME-106204- CS-QBS / Consultant firme(c abinet/ONG) chargée de l'ap Component 3: Capacity buil Quality Based Sel Open - Internation pui à la création des marché IDA / 62870 ding and Project Manageme Prior 4,000,000.00 0.00 Canceled 2019-05-02 2019-04-12 2019-06-01 2019-05-16 2019-07-15 2019-08-12 2019-09-11 2019-10-11 2019-11-15 2022-11-14 ection al s pour les services d'accomp nt agnement des entrepreuneu rs et de petites et moyennes entreprises ZR-UCP-PADMPME-133764- CS-QBS / Consultant firme c Component 3: Capacity buil Quality Based Sel Open - Internation hargé de l'Appui à la créatio IDA / 62870 ding and Project Manageme Prior 1,000,000.00 3,523,366.33 Signed 2019-09-20 2019-10-17 2019-10-11 2019-10-31 2019-11-24 2019-11-18 2019-12-22 2020-01-20 2020-01-21 2020-02-10 2020-02-20 2020-09-02 2020-03-26 2020-09-19 2021-03-26 ection al n des marchés pour les servi nt ces d'accompagnement des entrepreneurs et des PME Page 4 ZR-UCP-PADMPME-133767- CS-QBS / Consultant firme ( Component 2. SME Develop Quality Based Sel Open - Internation IDA / 62870 Prior 1,000,000.00 2,500,211.00 Signed 2019-09-19 2019-10-17 2019-10-10 2019-11-11 2019-11-23 2019-11-22 2019-12-21 2020-02-06 2020-01-20 2020-06-08 2020-02-19 2020-09-12 2020-03-25 2020-10-06 2021-03-25 Cabinet/ONG) chargé de me ment ection al ttre en oeuvre les Centres d es PME ZR-UCP-PADMPME-133748- Component 1: Support entr CS-QBS / Consultant firme ( Quality Based Sel Open - Internation IDA / 62870 epreneurship opportunities Prior 2,500,000.00 0.00 Canceled 2019-09-13 2019-10-17 2019-10-04 2019-11-11 2019-11-17 2019-12-02 2019-12-15 2020-02-05 2020-01-14 2020-02-25 2020-02-13 2020-09-14 2020-03-19 2021-03-19 Cabinet/ONG)chargé du sout ection al for youth and women ien aux femmes entreprene urs ZR-UCP-PADMPME-133613- CS-QBS / Recrutement d'une Component 1: Support entr Quality Based Sel Open - Internation firme (cabinet/ONG) chargée IDA / 62870 epreneurship opportunities Prior 7,900,000.00 9,578,996.96 Signed 2019-09-17 2019-10-18 2019-10-08 2019-11-01 2019-11-21 2019-11-05 2019-12-19 2020-01-15 2020-01-18 2020-01-23 2020-02-17 2020-06-11 2020-03-23 2020-06-28 2021-03-23 ection al de la mise en oeuvre des co for youth and women ncours des plans d'affaires ZR-UCP-PADMPME-140589- CS-CQS / Recrutement d'un Component 1: Support entr Consultant Qualifi Cabinet chargé de conduire l IDA / 62870 epreneurship opportunities Post Limited 252,000.00 280,013.00 Completed 2019-10-25 2019-11-12 2019-11-08 2020-01-30 2019-12-08 2020-03-13 2020-01-12 2020-03-31 2020-07-10 2020-12-31 cation Selection 'enquête de base de l'évalu for youth and women ation d'impact de la formatio n en Initiative Personnelle ZR-UCP-PADMPME-147412- CS-QCBS / Recrutement d'un Cabinet de consultants char Component 3: Capacity buil Quality And Cost- Open - Internation gé de l'audit externe financi IDA / 62870 ding and Project Manageme Post 100,000.00 31,353.80 Signed 2019-12-04 2019-12-06 2019-12-25 2020-08-03 2020-02-07 2020-03-18 2020-03-06 2020-04-24 2020-04-05 2020-05-07 2020-05-10 2020-05-15 2020-06-14 2020-06-04 2021-06-14 Based Selection al er et comptable du projet PA nt DMPME pour les exercices cl os au 31 décempbre 2018,2 019 et 2020. ZR-UCP-PADMPME-147453- Component 3: Capacity buil CS-CQS / Recrutement d'un Consultant Qualifi IDA / 62870 ding and Project Manageme Post Limited 400,000.00 247,769.00 Completed 2019-12-04 2020-01-02 2019-12-18 2020-05-11 2020-01-17 2020-07-17 2020-02-21 2020-08-15 2020-08-19 2021-03-16 Cabinet de Consultants char cation Selection nt gé de réaliser l'enquête de b ase du projet PADMPME ZR-UCP-PADMPME-147458- CS-CQS / Recrutement d'une Component 3: Capacity buil Consultant Qualifi Open - Internation agence conseil pour le renfo IDA / 62870 ding and Project Manageme Post 100,000.00 98,468.75 Signed 2019-12-04 2019-12-17 2019-12-25 2020-08-06 2020-02-07 2020-07-08 2020-03-08 2020-08-31 2020-04-12 2020-09-23 2020-10-09 cation Selection al rcement des actions de com nt munication du projet PADMP ME ZR-UCP-PADMPME-164517- CS-CQS / Recrutement d'un Component 3: Capacity buil consultant (ONG) chargé de Consultant Qualifi IDA / 62870 ding and Project Manageme Post Open - National 150,000.00 119,107.40 Signed 2020-04-20 2020-04-30 2020-05-11 2020-11-17 2020-06-24 2020-11-27 2020-07-24 2021-03-24 2020-08-28 2021-04-10 2021-02-24 l'accompagnement sur la pr cation Selection nt évention des violences basé es sur le genre (VBG) et le VI H dans les sites du projet ZR-UCP-PADMPME-200903- CS-QCBS / Recrutement d'un Component 1: Support entr Cabinet de Consultants char Quality And Cost- IDA / 62870 epreneurship opportunities Post Open - National 230,000.00 0.00 Canceled 2020-11-26 2020-12-03 2020-12-17 2021-01-30 2021-02-27 2021-03-29 2021-05-03 2021-06-07 2022-06-07 gé d'appuyer le gouverneme Based Selection for youth and women nt dans le renforcement du cadre institutionnel des peti tes et moyennes entreprises . ZR-UCP-PADMPME-205577- CS-QCBS / Recrutement d'un Component 1: Support entr Quality And Cost- Open - Internation Consultant (Cabinet) chargé IDA / 62870 epreneurship opportunities Prior 2,000,000.00 1,733,935.79 Signed 2020-12-17 2021-02-01 2021-01-07 2021-02-15 2021-02-20 2021-07-28 2021-03-20 2021-09-17 2021-04-19 2022-02-15 2021-05-24 2022-05-09 2021-06-28 2022-06-06 2022-06-28 Based Selection al de la formation et de l'acco for youth and women mpagnement des femmes e ntrepreneurs ZR-UCP-PADMPME-205770- CS-CQS / Recrutement d'un Consultant ( cabinet/ONG/ag Component 2. SME Develop Consultant Qualifi ence) chargé de réaliser l'au IDA / 62870 Post Open - National 250,000.00 247,810.02 Signed 2020-12-18 2021-01-27 2021-01-08 2021-03-10 2021-02-21 2021-04-15 2021-03-23 2021-06-16 2021-04-27 2021-06-23 2021-10-24 ment cation Selection dit environnemental et socia l des premières petites et m oyennes entreprises subvent ionnées par le projet ZR-UCP-PADMPME-215954- CS-CQS / Recrutement d'un Component 1: Support entr Quality And Cost- cabinet pour la révision de IDA / 62870 epreneurship opportunities Post Open - National 200,000.00 0.00 Canceled 2021-03-10 2021-07-08 2021-03-31 2021-05-14 2021-06-11 2021-07-11 2021-08-15 2021-09-19 2022-09-19 Based Selection la stratégie nationale des pe for youth and women tites et moyennes entreprise s ZR-UCP-PADMPME-226482- CS-QCBS / Recrutement d'un Cabinet de consultants char Component 3: Capacity buil Quality And Cost- Open - Internation Under Implement gé de l'audit externe financi IDA / 62870 ding and Project Manageme Post 80,000.00 0.00 2021-06-21 2021-04-05 2021-07-12 2021-04-19 2021-08-25 2021-09-17 2021-09-22 2021-11-01 2021-10-22 2021-11-26 2021-12-31 2022-12-31 Based Selection al ation er et comptable du projet PA nt DMPME pour les exercices cl os au 31 décempbre 2021,2 022 et 2023. ZR-UCP-PADMPME-200910- CS-QCBS / Recrutement d'un Cabinet chargé d'accompag Component 1: Support entr Quality And Cost- Open - Internation ner le gouvernement dans la IDA / 62870 epreneurship opportunities Prior 1,800,000.00 0.00 Canceled 2020-11-27 2020-12-18 2021-01-31 2021-02-28 2021-03-30 2021-05-04 2021-06-08 2022-06-08 Based Selection al promotion du dialogue publi for youth and women c-privé , de l'OHADA ainsi qu e les mécanismes alternatifs de règlement des différends ZR-UCP-PADMPME-200523- CS-QCBS / Recrutement d'u Component 1: Support entr n Consultant Cabinet Interna Quality And Cost- Open - Internation IDA / 62870 epreneurship opportunities Prior 1,000,000.00 0.00 Canceled 2020-11-25 2021-04-10 2020-12-16 2021-01-29 2021-02-26 2021-03-28 2021-05-02 2021-06-06 2022-06-06 tional chargé de la finalisatio Based Selection al for youth and women n du cadre juridique des Peti tes et Moyennes Entreprises (PME) ZR-UCP-PADMPME-226484- CS-QCBS / Recrutement d’u Component 1: Support entr n Consultant Cabinet chargé Quality And Cost- Open - Internation IDA / 62870 epreneurship opportunities Post 900,000.00 0.00 Canceled 2021-04-12 2021-05-03 2021-06-16 2021-07-14 2021-08-13 2021-09-17 2021-10-22 2022-10-22 de la promotion et la mise e Based Selection al for youth and women n place des plateformes du Dialogue Public-Privé dans le s zones du Projet ZR-UCP-PADMPME-205724- CS-CQS / Recrutement d'un cabinet /partenaire local pou Component 1: Support entr Quality And Cost- Open - Internation r assurer l'organisation maté IDA / 62870 epreneurship opportunities Post 500,000.00 0.00 Canceled 2021-02-28 2021-03-21 2021-05-04 2021-06-01 2021-07-01 2021-08-05 2021-09-09 2022-09-09 Based Selection al rielle (support logistique) de for youth and women s formations STEP au profit des jeunes entrepreneurs da ns les quatre villes du proje t ZR-UCP-PADMPME-205704- CS-CQS / Recrutement d'un cabinet /partenaire local pou Component 1: Support entr r assurer l'organisation mat Consultant Qualifi IDA / 62870 epreneurship opportunities Post Open - National 300,000.00 0.00 Canceled 2021-02-28 2021-03-21 2021-05-04 2021-06-03 2021-07-08 2022-01-04 érielle (support logistique) d cation Selection for youth and women es formations en IP au profit des femmes entrepreneurs é ligibles dans les villes de Go ma et Lubumbashi ZR-UCP-PADMPME-215940- CS-CQS / Recrutement d'un Component 1: Support entr Cabinet chargé de l'identific Consultant Qualifi IDA / 62870 epreneurship opportunities Post Open - National 105,000.00 0.00 Canceled 2021-03-01 2021-02-12 2021-03-22 2021-05-05 2021-06-04 2021-07-09 2022-01-05 ation des réformes prioritair cation Selection for youth and women es sur le cadre juridique des petites et moyennes entrepr ises ZR-UCP-PADMPME-215945- CS-QCBS / Recrutement d'un Component 1: Support entr Quality And Cost- Open - Internation Cabinet chargé de la mise e IDA / 62870 epreneurship opportunities Prior 1,000,000.00 0.00 Canceled 2021-03-15 2021-04-05 2021-05-19 2021-06-16 2021-07-16 2021-08-20 2021-09-24 2022-09-24 Based Selection al n œuvre des réformes priori for youth and women taires sur le cadre juridique des PME identifiées Page 5 ZR-UCP-PADMPME-215957- CS-CQS / Recrutement d'un consultant firme ( cabinet, O Component 2. SME Develop Consultant Qualifi Under Implement IDA / 62870 Post Open - National 200,000.00 0.00 2021-02-25 2021-09-16 2021-03-18 2021-11-01 2021-05-01 2021-05-31 2021-07-05 2022-01-01 NG) pour l'organisation et la ment cation Selection ation conduite de l'enquête de sa tisfaction des PME établies b énéficiaires de la première cohorte ZR-UCP-PADMPME-205728- CS-CQS / Recrutement d'un consultant ( cabinet, firme, Component 1: Support entr Consultant Qualifi Under Implement ONG) chargé de l'organisati IDA / 62870 epreneurship opportunities Post Open - National 250,000.00 0.00 2021-01-30 2021-09-16 2021-02-20 2021-11-01 2021-04-05 2022-02-21 2021-05-05 2021-06-09 2021-12-06 cation Selection ation on de l'enquête de suivi sur for youth and women la formation en Initiative per sonnelle dans les villes de G oma et Lubumbashi ZR-UCP-PADMPME-252805- CS-CQS / Recrutement d’un consultant cabinet chargé d Component 2. SME Develop Consultant Qualifi Under Implement IDA / 62870 Post Limited 60,000.00 0.00 2021-09-27 2022-01-06 2021-10-11 2021-11-10 2021-12-15 2022-06-13 e la conduite des études rel ment cation Selection ation atives à l’élaboration d’un c ahier des charges pour les é quipements des centres de PME ZR-UCP-PADMPME-256884- CS-CQS / Recrutement d’un cabinet de consultants pour assister le gouvernement da Component 2. SME Develop Consultant Qualifi IDA / 62870 Post Limited 120,000.00 115,590.00 Signed 2021-10-18 2021-11-09 2021-11-01 2022-04-18 2021-12-01 2022-06-08 2022-01-05 2022-06-30 2022-07-04 ns la conduite des études ar ment cation Selection chitecturales et environnem entales pour les travaux rela tifs au développement des centre des PME à Goma et M atadi en RDC ZR-UCP-PADMPME-262005- CS-CQS / Recrutement d'un Component 1: Support entr consultant (cabinet) de reno Consultant Qualifi Open - Internation IDA / 62870 epreneurship opportunities Post 230,000.00 0.00 Under Review 2021-11-29 2022-01-06 2021-12-20 2022-02-02 2022-03-04 2022-04-08 2022-10-05 mmée internationale pour a cation Selection al for youth and women ssister le gouvernement dan s la réforme du système fisc al et parafiscal de la RD Con go ZR-UCP-PADMPME-261819- Component 3: Capacity buil CS-CQS / Recrutement d'un Consultant Qualifi IDA / 62870 ding and Project Manageme Post Open - National 100,000.00 0.00 Canceled 2021-11-29 2022-01-07 2021-12-20 2022-02-02 2022-03-04 2022-04-08 2022-10-05 consultant cabinet pour app cation Selection nt uyer la transformation de l'O PEC en ANADEC ZR-UCP-PADMPME-283775- CS-CQS / Recrutement d'un consultant firme en charge d e mise en charge de mise e Component 1: Support entr Consultant Qualifi Under Implement n place , établissement et o IDA / 62870 epreneurship opportunities Post Open - National 400,000.00 0.00 2022-04-11 2022-04-28 2022-05-02 2022-07-12 2022-06-15 2022-07-15 2022-08-19 2023-02-15 cation Selection ation pérationnalisation d'un syst for youth and women ème d'octroi des subvention s en nature par bon/jeton él ectronique (e-voucher) au pr ofit des femmes micro-entre preneures ZR-UCP-PADMPME-283790- Component 1: Support entr Consultant Qualifi CS-CQS / Révision du code d IDA / 62870 epreneurship opportunities Post Open - National 100,000.00 0.00 Under Review 2022-04-25 2022-05-25 2022-05-16 2022-06-29 2022-07-29 2022-09-02 2023-03-01 cation Selection 'investissement for youth and women ZR-UCP-PADMPME-283795- Component 1: Support entr Consultant Qualifi CS-CQS / Appui à l'élaboratio IDA / 62870 epreneurship opportunities Post Open - National 60,000.00 0.00 Under Review 2022-04-25 2023-05-11 2022-05-16 2022-06-29 2022-07-29 2022-09-02 2023-03-01 cation Selection n des documents stratégiqu for youth and women es de l'ANADEC ZR-UCP-PADMPME-215950- CS-CQS / Recrutement d'un Component 2. SME Develop Consultant Qualifi Cabinet pour renforcer les c IDA / 62870 Post Open - National 250,000.00 0.00 Canceled 2021-02-27 2021-10-08 2021-03-20 2021-05-03 2021-06-02 2021-07-07 2022-01-03 ment cation Selection apacités des petites et moy ennes entreprises établies et les jeunes entrepreneurs ZR-UCP-PADMPME-261786- Component 1: Support entr CS-CQS / Recrutement d'un Consultant Qualifi IDA / 62870 epreneurship opportunities Post Limited 200,000.00 0.00 Canceled 2022-02-28 2022-03-14 2022-04-13 2022-05-18 2022-11-14 cabinet pour la revue du cod cation Selection for youth and women e des investissements ZR-UCP-PADMPME-294841- CS-CQS / Recrutement d’une Component 3: Capacity buil ONG locale chargée de la mi Consultant Qualifi Under Implement IDA / 62870 ding and Project Manageme Post Open - National 70,000.00 0.00 2022-06-01 2022-06-03 2022-06-22 2022-08-19 2022-08-05 2022-09-04 2022-10-09 2023-04-07 se en œuvre des activités de cation Selection ation nt prévention et de réponse au x violences basées sur le ge nre dans la ville de Lubumba shi. ZR-UCP-PADMPME-294844- CS-CQS / Recrutement d’une Component 3: Capacity buil ONG locale chargée de la mi Consultant Qualifi Under Implement IDA / 62870 ding and Project Manageme Post Open - National 70,000.00 0.00 2022-06-01 2022-06-03 2022-06-22 2022-07-18 2022-08-05 2022-09-04 2022-10-09 2023-04-07 se en œuvre des activités de cation Selection ation nt prévention et de réponse au x violences basées sur le ge nre dans la ville de Matadi ZR-UCP-PADMPME-295078- Component 1: Support entr CS-CQS / Recrutement d'une Consultant Qualifi Under Implement IDA / 62870 epreneurship opportunities Post Open - National 300,000.00 0.00 2022-06-15 2022-07-28 2022-07-06 2023-01-05 2022-08-19 2022-09-18 2022-10-23 2023-04-21 firme chargé du développem cation Selection ation for youth and women ent du partenariat public pri vé ZR-UCP-PADMPME-283802- Component 1: Support entr Consultant Qualifi CS-CQS / Revue de la loi de l IDA / 62870 epreneurship opportunities Post Open - National 50,000.00 0.00 Canceled 2022-05-02 2022-05-23 2022-07-06 2022-08-05 2022-09-09 2023-03-08 cation Selection a sous-traitance par un Con for youth and women sultant firme ZR-UCP-PADMPME-323112- Component 1: Support entr CS-CQS / Recrutement d’un Consultant Qualifi Under Implement IDA / 62870 epreneurship opportunities Post Limited 50,000.00 0.00 2022-12-01 2023-02-02 2022-12-15 2023-01-14 2023-02-18 2023-08-17 cabinet chargé l’audit enviro cation Selection ation for youth and women nnemental et social de fin pr ojet PADMPME ZR-UCP-PADMPME-327519- CS-CQS / Recrutement d’un Component 3: Capacity buil consultant international en c Consultant Qualifi IDA / 62870 ding and Project Manageme Post Open - National 75,000.00 0.00 Under Review 2023-01-15 2023-01-28 2023-02-05 2023-03-21 2023-04-20 2023-05-25 2023-11-21 harge de conduire le proces cation Selection nt sus de clôture du projet et l’ élaboration du rapport d’ach èvement ZR-UCP-PADMPME-283776- CS-CQS / Contractualisation Component 1: Support entr Consultant Qualifi avec le cabinet d'enquête d IDA / 62870 epreneurship opportunities Post Open - National 250,000.00 0.00 Canceled 2022-03-17 2022-04-07 2022-05-21 2022-06-20 2022-07-25 2023-01-21 cation Selection e suivi post subvention en n for youth and women ature des femmes à Goma e t Lubumbashi ZR-UCP-PADMPME-295841- CS-CQS / Recrutement d'un cabinet chargé de la formati on de staffs en micro-inform Component 3: Capacity buil Consultant Qualifi atique et en télétravail pour IDA / 62870 ding and Project Manageme Post Open - National 31,200.00 0.00 Canceled 2022-06-13 2022-07-04 2022-08-17 2022-09-16 2022-10-21 2023-04-19 cation Selection appui aux institutions privée nt s et publiques de la ville de Kinshasa/ SDE (COPEC,CASP OF,FEC;COPEMECO,FENAPEC ,Min.PME-SG,Min.GENRE-SG, PFE,etPJE) ZR-UCP-PADMPME-261806- CS-CQS / Recrutement d'un cabinet pour l'étude de faisa Component 1: Support entr bilité pour l'extension aux vil Consultant Qualifi IDA / 62870 epreneurship opportunities Post Limited 200,000.00 0.00 Canceled 2022-02-14 2022-05-25 2022-02-28 2022-03-30 2022-05-04 2022-10-31 les ciblées par le projet de la cation Selection for youth and women déclaration et de paiement unique des impôts, cotisatio ns sociales et contributions patronales sur les rémunéra tions Page 6 ZR-UCP-PADMPME-299332- CS-CQS / Recrutement d'un Cabinet chargé de renforcer les capacités techniques et Component 3: Capacity buil Consultant Qualifi managériales des institution IDA / 62870 ding and Project Manageme Post Open - National 130,500.00 0.00 Canceled 2022-07-03 2022-07-24 2022-09-06 2022-10-06 2022-11-10 2023-05-09 cation Selection s à appuyer dans le cadre d nt e SDE à Lubumbashi, Matadi et Goma ( OPEC, FENAPEC, F EC, COPEMECO, DP Genre, F amille et Enfant et DP PME. ZR-UCP-PADMPME-295839- CS-CQS / Recrutement d'un cabinet chargé du renforce ment des capacités techniqu Component 3: Capacity buil Consultant Qualifi es et managériales pour app IDA / 62870 ding and Project Manageme Post Open - National 70,500.00 0.00 Canceled 2022-06-20 2022-07-11 2022-08-24 2022-09-23 2022-10-28 2023-04-26 cation Selection ui aux institutions privées e nt t publiques de la ville de Kin shasa dans le cadre de SDE (COPEC,CASPOF,FEC,COPEM ECO,FENAPEC,Min.PME,Min. GENRE, ) ZR-UCP-PADMPME-365382- CS-CQS / Recrutement d'un consultant (cabinet) pour l'a Component 2. SME Develop Consultant Qualifi Pending Impleme ppui juridique, à la tenue de IDA / 62870 Post Open - National 238,000.00 0.00 2023-07-10 2023-07-31 2023-09-13 2023-10-13 2023-11-17 2024-05-15 ment cation Selection ntation la comptabilité et à la fiscalit é des PME dans le cadre de mise en oeuvre du Centre P ME Virunga ZR-UCP-PADMPME-362041- CS-CQS / Recrutement d'un consultant ( firme) chargé d Component 1: Support entr e réaliser l'enquête de suivi Consultant Qualifi IDA / 62870 epreneurship opportunities Post Open - National 250,000.00 0.00 Under Review 2023-06-05 2023-06-28 2023-06-26 2023-08-09 2023-09-08 2023-10-13 2024-04-10 post subvention auprès des f cation Selection for youth and women emmes bénéficiaires dans le s villes de Goma et Lubumb ashi dans le cadre de l'évalu ation d'impact de la FIP INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Draft Negotiated Con Description Component Review Type Method Process Status Terms of Reference d/Selected Consultan Signed Contract Contract Completion o. h unt (US$) t (US$) tract t Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-UCP-PADMPME-147461- Component 3: Capacity buil Individual Consult CS-INDV / Recrutement d'un IDA / 62870 ding and Project Manageme Post Open 48,000.00 48,000.00 Signed 2019-12-04 2019-12-17 2020-01-22 2020-05-21 2020-02-12 2020-06-10 2020-03-18 2020-11-03 2020-09-14 ant Selection Expert Juriste pour le projet nt PADMPME ZR-UCP-PADMPME-147464- Component 3: Capacity buil CS-INDV / Recrutement d'un Individual Consult IDA / 62870 ding and Project Manageme Post Limited 36,000.00 48,000.00 Completed 2019-12-06 2019-12-17 2019-12-11 2020-01-21 2020-01-01 2020-02-12 2020-02-05 2020-03-03 2020-08-03 2021-03-06 chargé de passation des ma ant Selection nt rchés pour le projet PADMPM E ZR-UCP-PADMPME-147466- Component 3: Capacity buil Individual Consult CS-INDV / Recrutement d'un IDA / 62870 ding and Project Manageme Post Limited 30,000.00 30,000.00 Signed 2019-12-09 2019-12-17 2019-12-14 2019-12-30 2020-01-04 2020-03-09 2020-02-08 2020-03-19 2020-08-06 ant Selection trésorier pour le projet PAD nt MPME ZR-UCP-PADMPME-147468- Component 3: Capacity buil Individual Consult CS-INDV / Recrutement d'un IDA / 62870 ding and Project Manageme Post Limited 21,600.00 24,000.00 Signed 2019-12-10 2019-12-17 2019-12-15 2020-09-14 2020-01-05 2020-10-28 2020-02-09 2020-11-06 2020-08-07 ant Selection Logisticien pour le projet PA nt DMPME ZR-UCP-PADMPME-147473- Component 3: Capacity buil Individual Consult CS-INDV / Recrutement d'un IDA / 62870 ding and Project Manageme Post Limited 10,800.00 9,600.00 Signed 2019-12-12 2019-12-17 2019-12-17 2020-01-22 2020-01-07 2020-01-31 2020-02-11 2020-02-04 2020-08-09 ant Selection chauffeur du Coordonnateur nt du projet PADMPME ZR-UCP-PADMPME-147930- CS-INDV / Recrutement d'un Component 3: Capacity buil Individual Consult Point Focal PADMPME auprè IDA / 62870 ding and Project Manageme Post Limited 24,000.00 24,000.00 Completed 2019-12-04 2019-12-05 2019-12-09 2019-12-11 2019-12-30 2020-02-25 2020-02-03 2020-02-27 2020-08-01 2021-02-26 ant Selection s du Ministères de la classe nt moyennes petites et moyen nes entreprises et artisanat. ZR-UCP-PADMPME-147432- CS-CDS / Recrutement des C onsultants GAUDREAULT Fra Component 3: Capacity buil ncis et HART POLIQUIN Noira IDA / 62870 ding and Project Manageme Prior Direct Selection Direct 451,935.00 351,732.00 Signed 2019-12-05 2019-12-09 2019-12-15 2019-12-10 2020-02-18 2020-03-03 2020-08-16 pour assistance technique e nt t renforcement des capacité s de l'UCP PADMPME en Lea dership axé sur les résultats et en approche à résultats r apides ZR-UCP-PADMPME-147429- Component 1: Support entr CS-CDS / Recrutement du Ca IDA / 62870 epreneurship opportunities Post Direct Selection Direct 167,240.00 164,734.00 Signed 2019-12-03 2019-12-06 2019-12-13 2020-03-10 2020-02-16 2020-04-24 2020-08-14 binet Vélior Développement for youth and women pour une assistance techniq ue à l'UCP PADMPME ZR-UCP-PADMPME-147474- Component 3: Capacity buil Individual Consult CS-INDV / Description d'un P IDA / 62870 ding and Project Manageme Post Limited 10,800.00 0.00 Canceled 2019-12-06 2019-12-17 2019-12-11 2020-01-01 2020-02-05 2020-08-03 ant Selection lanton pour le projet PADMP nt ME ZR-UCP-PADMPME-153440- CS-CDS / Recrutement d'un Component 3: Capacity buil éditeur chargé de la relectur IDA / 62870 ding and Project Manageme Post Direct Selection Direct 1,000.00 1,000.00 Completed 2020-01-10 2020-01-20 2020-01-20 2020-01-21 2020-03-25 2020-01-28 2020-09-21 2020-02-29 e du rapport sur l'écosystèm nt e des petites et moyennes e ntreprises en RDC ZR-UCP-PADMPME-159674- CS-CDS / Contractualisation Component 1: Support entr avec ONU femmes chargé IDA / 62870 epreneurship opportunities Prior Direct Selection Direct 1,000,000.00 6,513,602.00 Signed 2020-02-18 2020-03-31 2020-02-28 2020-04-06 2020-05-03 2021-03-15 2020-10-30 de la réforme et la dissémin for youth and women ation des textes de lois en fa veur des femmes ZR-UCP-PADMPME-144391- CS-INDV / Recrutement d'un Consultant individuel chargé Component 3: Capacity buil Individual Consult de la Cartographie de servic IDA / 62870 ding and Project Manageme Post Open 25,000.00 27,710.00 Completed 2019-11-22 2019-12-18 2020-01-10 2020-05-11 2020-01-31 2020-05-29 2020-03-06 2020-06-04 2020-09-02 2020-10-31 ant Selection es pour les survivantes des nt violences basées sur le genr e dans les villes de Matadi e t Lubumbashi ZR-UCP-PADMPME-147470- Component 3: Capacity buil Individual Consult CS-INDV / Recrutement d'un IDA / 62870 ding and Project Manageme Post Limited 15,600.00 0.00 Canceled 2019-12-11 2019-12-17 2019-12-16 2020-01-06 2020-02-10 2020-08-08 ant Selection Secrétaire financier pour le nt projet PADMPME ZR-UCP-PADMPME-164529- CS-INDV / Recrutement d'As Component 3: Capacity buil Individual Consult sistant administratif et finan IDA / 62870 ding and Project Manageme Post Limited 12,000.00 18,000.00 Signed 2020-04-30 2020-07-07 2020-05-05 2020-07-14 2020-05-26 2020-08-04 2020-06-30 2020-08-11 2020-12-27 ant Selection cier pour l'antenne provinci nt ale du PADMPME à Goma ZR-UCP-PADMPME-164531- CS-INDV / Recrutement d'un Component 3: Capacity buil Individual Consult Assistant administratif et fin IDA / 62870 ding and Project Manageme Post Limited 12,000.00 12,000.00 Signed 2020-03-31 2020-07-07 2020-04-05 2020-09-17 2020-04-26 2021-03-30 2020-05-31 2021-04-01 2020-11-27 ant Selection ancier pour l'antenne provin nt ciale du PADMPME Lubumba shi ZR-UCP-PADMPME-164533- CS-INDV / Recrutement d'un Component 3: Capacity buil Individual Consult Assistant administratif et fin IDA / 62870 ding and Project Manageme Post Limited 12,000.00 12,000.00 Signed 2020-03-31 2020-07-07 2020-04-05 2020-09-04 2020-04-26 2020-11-16 2020-05-31 2020-11-24 2020-11-27 ant Selection ancier pour l'antenne provin nt ciale du PADMPME Matadi Page 7 ZR-UCP-PADMPME-164535- Component 3: Capacity buil CS-INDV / Recrutement d'un Individual Consult IDA / 62870 ding and Project Manageme Post Limited 8,400.00 7,200.00 Signed 2020-03-31 2020-07-07 2020-04-05 2020-09-10 2020-04-26 2020-10-27 2020-05-31 2020-11-13 2020-11-27 Chauffeur pour l'antenne pro ant Selection nt vinciale du PADMPME Goma ZR-UCP-PADMPME-164536- Component 3: Capacity buil CS-INDV / Recrutement d'un Individual Consult IDA / 62870 ding and Project Manageme Post Limited 8,400.00 7,200.00 Signed 2020-03-31 2020-07-07 2020-04-05 2020-09-24 2020-04-26 2020-10-27 2020-05-31 2020-10-30 2020-11-27 chauffeur pour l'antenne pro ant Selection nt vinciale du PADMPME Lubum bashi ZR-UCP-PADMPME-164537- Component 3: Capacity buil CS-INDV / Recrutement d'un Individual Consult IDA / 62870 ding and Project Manageme Post Limited 8,400.00 10,036.00 Terminated 2020-03-31 2020-07-07 2020-04-05 2020-09-04 2020-04-26 2020-11-16 2020-05-31 2020-11-25 2020-11-27 Chauffeur pour l'antenne pro ant Selection nt vinciale du PADMPME Matadi ZR-UCP-PADMPME-147226- Component 1: Support entr CS-CDS / Recrutement du Ca IDA / 62870 epreneurship opportunities Post Direct Selection Direct 300,000.00 0.00 Canceled 2019-12-05 2020-01-10 2019-12-15 2020-02-18 2020-08-16 binet MOVES chargé de la fo for youth and women rmation STEP ZR-UCP-PADMPME-163881- CS-INDV / Renouvellement d Component 3: Capacity buil Individual Consult u contrat de Jean-Luc MUAL IDA / 62870 ding and Project Manageme Post Direct 48,000.00 24,000.00 Signed 2020-04-28 2020-12-04 2020-05-08 2021-02-11 2020-05-29 2020-04-16 2020-07-03 2020-04-21 2020-12-30 ant Selection U en qualité d'Expert en Co nt mmunication du PADMPME ZR-UCP-PADMPME-163477- CS-CDS / Contractualisation Component 1: Support entr avec le Cabinet MOVES char IDA / 62870 epreneurship opportunities Prior Direct Selection Direct 600,000.00 691,576.00 Signed 2020-04-29 2020-04-23 2020-05-09 2020-04-24 2020-07-13 2020-08-22 2021-01-09 gée de la mise en oeuvre d for youth and women e la formation en Initiative p ersonnelle et de la formatio n STEP ZR-UCP-PADMPME-158734- Component 3: Capacity buil CS-CDS / Renouvellement d IDA / 62870 ding and Project Manageme Post Direct Selection Direct 48,000.00 48,000.00 Signed 2020-04-28 2020-12-04 2020-05-08 2020-01-28 2020-07-12 2020-01-30 2021-01-08 u contrat de Raphael KAKUD nt JI MANDE en qualité d'Expert en suivi & évaluation ZR-UCP-PADMPME-158737- Component 3: Capacity buil CS-CDS / Renouvellement d IDA / 62870 ding and Project Manageme Post Direct Selection Direct 36,000.00 36,000.00 Signed 2020-04-28 2020-12-04 2020-05-08 2020-01-28 2020-07-12 2020-01-30 2021-01-08 u contrat de Benjamin TSHIE nt NDA wa MBANGU en qualité de Comptable ZR-UCP-PADMPME-158730- Component 3: Capacity buil CS-CDS / Renouvellement d IDA / 62870 ding and Project Manageme Post Direct Selection Direct 54,000.00 54,000.00 Signed 2020-04-28 2020-12-04 2020-05-08 2020-01-28 2020-07-12 2020-01-30 2021-01-08 u contrat de Kevinn NDONJI nt en qualité d'Auditeur interne ZR-UCP-PADMPME-158735- CS-CDS / Renouvellement d Component 3: Capacity buil u contrat de Roger BOKAND IDA / 62870 ding and Project Manageme Post Direct Selection Direct 48,000.00 48,000.00 Signed 2020-04-28 2020-12-04 2020-05-08 2020-01-28 2020-07-12 2020-01-30 2021-01-08 ENGA GBAMO en qualité d'E nt xpert en sauvegarde environ nementale et sociale ZR-UCP-PADMPME-158718- CS-CDS / Renouvellement d Component 3: Capacity buil u Contrat de Meilleur BASEM IDA / 62870 ding and Project Manageme Post Direct Selection Direct 54,000.00 54,000.00 Signed 2020-04-28 2020-11-04 2020-05-08 2020-01-28 2020-07-12 2020-01-30 2021-01-08 A KOMANDA en qualité de R nt esponsable Administratif et Finacier ZR-UCP-PADMPME-179017- CS-CDS / Contractualisation avec Kivu Entrepreneur co Component 1: Support entr mme consultant chargé de l' IDA / 62870 epreneurship opportunities Post Direct Selection Direct 70,000.00 76,700.00 Completed 2020-06-15 2020-06-26 2020-06-25 2020-07-13 2020-08-29 2020-08-11 2021-02-25 2020-12-01 identification des femmes e for youth and women ntrepreneurs devant particip er à la formation en initiativ e personnelle ZR-UCP-PADMPME-185723- CS-INDV / Recrutement d'un Component 3: Capacity buil Individual Consult Consultant individuel Chargé IDA / 62870 ding and Project Manageme Post Limited 10,000.00 8,885.00 Signed 2020-08-10 2020-08-06 2020-08-15 2020-07-27 2020-09-05 2020-08-20 2020-10-10 2020-08-27 2021-04-08 ant Selection de la traduction des docume nt nts du projet PADMPME ZR-UCP-PADMPME-185725- CS-INDV / Recrutement d'un Component 3: Capacity buil Individual Consult Assistant Comptable en char IDA / 62870 ding and Project Manageme Post Limited 30,000.00 36,000.00 Terminated 2020-08-12 2020-11-12 2020-08-17 2020-11-06 2020-09-07 2021-01-05 2020-10-12 2021-02-18 2021-04-10 ant Selection ge des Partenaires d'exécuti nt on des projets au sein de l'U CP ZR-UCP-PADMPME-185915- CS-INDV / Renouvellement d Component 3: Capacity buil Individual Consult u contrat de MUKADI TSHIEL IDA / 62870 ding and Project Manageme Post Direct 24,000.00 24,000.00 Signed 2020-08-10 2020-12-04 2020-08-20 2020-06-11 2020-09-10 2020-06-15 2020-10-15 2020-07-02 2021-04-13 ant Selection A Gloria en qualité d'Assista nt nte en Passation des marché s du PADMPME ZR-UCP-PADMPME-185914- CS-INDV / Renouvellement d Component 3: Capacity buil Individual Consult u contrat de MULEMBA MANI IDA / 62870 ding and Project Manageme Post Direct 10,800.00 10,800.00 Signed 2020-08-10 2020-12-04 2020-08-20 2020-06-04 2020-09-10 2020-06-26 2020-10-15 2020-07-02 2021-04-13 ant Selection ONGA Syntiche en qulaité d nt e réceptionniste du PADMPM E ZR-UCP-PADMPME-185913- CS-INDV / Renouvellement d Component 3: Capacity buil Individual Consult u contrat de NSIMBA MABUM IDA / 62870 ding and Project Manageme Post Direct 48,000.00 48,000.00 Signed 2020-08-10 2020-12-04 2020-08-20 2020-07-07 2020-09-10 2020-07-08 2020-10-15 2020-07-10 2021-04-13 ant Selection BA Chantal en qualité d'Exp nt erte en Genre et Inclusion S ociale ZR-UCP-PADMPME-188716- Component 3: Capacity buil CS-INDV / Renouvellement d Individual Consult IDA / 62870 ding and Project Manageme Post Direct 18,000.00 18,000.00 Signed 2020-10-19 2020-12-02 2020-10-29 2020-08-07 2020-11-19 2020-08-10 2020-12-24 2020-08-13 2021-06-22 u contrat de Carmy KODIA M ant Selection nt ASSAMBA en qualité l'IT Offi cer ZR-UCP-PADMPME-185912- CS-INDV / Renouvellement d Component 3: Capacity buil Individual Consult u contrat de Eddy ISEKAMA IDA / 62870 ding and Project Manageme Post Direct 54,000.00 54,000.00 Completed 2020-10-19 2020-12-02 2020-10-29 2020-01-28 2020-11-19 2020-01-28 2020-12-24 2020-01-28 2021-06-22 2021-01-29 ant Selection BOTULU en qualité de Spéci nt aliste en Passation des marc hés ZR-UCP-PADMPME-199246- CS-INDV / Renouvellement d Component 3: Capacity buil Individual Consult u contrat de Monsieur Gilber IDA / 62870 ding and Project Manageme Post Direct 9,600.00 9,600.00 Signed 2020-10-13 2020-12-04 2020-10-23 2020-08-13 2020-11-13 2020-08-17 2020-12-18 2020-09-10 2021-06-16 ant Selection t MUR’A-NSENG-NGAL en qu nt alité de Chauffeur Coursier au PADMPME ZR-UCP-PADMPME-167498- Component 3: Capacity buil CS-INDV-REV / Recrutement Individual Consult IDA / 62870 ding and Project Manageme Post Open 48,000.00 48,000.00 Signed 2020-04-30 2019-12-09 2020-06-18 2020-06-23 2020-07-09 2020-07-14 2020-08-13 2020-08-04 2021-02-09 d'un Point focal provincial du ant Selection nt projet pour la ville de Lubum bashi ZR-UCP-PADMPME-167498- Component 3: Capacity buil CS-INDV / Recrutement d'un Individual Consult IDA / 62870 ding and Project Manageme Prior Open 48,000.00 0.00 Canceled 2020-04-30 2020-06-18 2020-07-09 2020-08-13 2021-02-09 Point focal provincial du proj ant Selection nt et pour la ville de Lubumba shi ZR-UCP-PADMPME-200887- CS-INDV / Recrutement d'un Consultant individuel chargé Component 1: Support entr d'accompagner le gouverne Individual Consult IDA / 62870 epreneurship opportunities Post Open 35,000.00 23,594.00 Completed 2020-11-23 2020-11-13 2021-01-11 2021-02-24 2021-02-01 2021-03-04 2021-03-08 2021-03-18 2021-09-04 2021-07-21 ment de la RDC dans l'élabo ant Selection for youth and women ration d'avant projet de loi (t exte initial) sur le cadre insti tutionnel des micro, petites et moyennes entreprises Page 8 ZR-UCP-PADMPME-200604- Component 3: Capacity buil CS-INDV / Renouvellement d Individual Consult IDA / 62870 ding and Project Manageme Post Direct 48,000.00 48,000.00 Signed 2020-10-20 2020-12-04 2020-10-30 2020-09-23 2020-11-20 2020-09-23 2020-12-25 2020-10-02 2021-06-23 u contrat de Monsieur Pierre ant Selection nt MBAMBI Chef d'Antenne de l a ville de Matadi ZR-UCP-PADMPME-200608- CS-INDV / Renouvellement d Component 3: Capacity buil Individual Consult u contrat de Madame Esther IDA / 62870 ding and Project Manageme Post Direct 48,000.00 48,000.00 Signed 2020-11-20 2020-12-04 2020-11-30 2020-09-24 2020-12-21 2020-09-24 2021-01-25 2020-10-02 2021-07-24 ant Selection KALANGA, en qualité de Che nt f d'Antenne pour la ville de Goma ZR-UCP-PADMPME-204705- CS-INDV / Renouvellement d Component 3: Capacity buil u contrat de Mr MUBIALA BA Individual Consult IDA / 62870 ding and Project Manageme Post Direct 24,000.00 24,000.00 Signed 2020-11-13 2020-12-04 2020-11-23 2020-08-28 2020-12-14 2020-08-31 2021-01-18 2020-09-03 2021-07-17 LUB-IMBAND Odon-Charles ant Selection nt en qualité de Spécialiste en Petites et Moyennes Entrepri ses ZR-UCP-PADMPME-204749- Component 3: Capacity buil CS-INDV / Renouvellement d Individual Consult IDA / 62870 ding and Project Manageme Post Direct 48,000.00 48,000.00 Signed 2020-11-13 2020-12-04 2020-11-23 2020-10-28 2020-12-14 2020-10-28 2021-01-18 2020-10-30 2021-07-17 u contrat de Mr MUALU Jean- ant Selection nt Luc en qualité de Spécialiste en Communication ZR-UCP-PADMPME-205587- CS-CDS / Contractualisation Component 1: Support entr avec Monsieur Aimé ZONVE Under Implement IDA / 62870 epreneurship opportunities Post Direct Selection Direct 15,000.00 0.00 2020-11-30 2021-02-15 2020-12-10 2021-03-19 2021-02-13 2021-08-12 NI BE LEMBE Consultant ind ation for youth and women ividuel chargé de traduire en français le contrat à signer a vec l'agence ONU femmes ZR-UCP-PADMPME-205585- CS-CDS / Contractualisation avec la firme Kivu Entrepren Component 1: Support entr eur pour l'enregistrement de IDA / 62870 epreneurship opportunities Post Direct Selection Direct 70,000.00 78,523.90 Signed 2020-11-30 2021-02-04 2020-12-10 2021-04-06 2021-02-13 2021-05-21 2021-08-12 s femmes devant participer for youth and women à la formation en initiative p ersonnelle (FIP) dans les vill es de Kinshasa et Matadi ZR-UCP-PADMPME-208790- CS-INDV / Renouvellement d Component 3: Capacity buil Individual Consult u contrat de Elise MBUYU M IDA / 62870 ding and Project Manageme Post Direct 24,000.00 24,000.00 Signed 2020-12-09 2021-02-17 2020-12-19 2020-12-14 2021-01-09 2020-12-15 2021-02-13 2020-12-24 2021-08-12 ant Selection BAYO en qualité de secrétair nt e administratif du PADMPME ZR-UCP-PADMPME-208791- CS-INDV / Renouvellement d Component 3: Capacity buil Individual Consult u contrat de Mimie EYIMA M IDA / 62870 ding and Project Manageme Post Direct 42,000.00 42,000.00 Signed 2020-12-09 2021-02-15 2020-12-19 2020-12-14 2021-01-09 2020-12-15 2021-02-13 2020-12-21 2021-08-12 ant Selection ODJAKA en sa qualité de l'As nt sistante au Coordonnateur N ational du PADMPME ZR-UCP-PADMPME-216305- Component 3: Capacity buil Individual Consult CS-INDV / Recrutement d'un IDA / 62870 ding and Project Manageme Post Limited 8,400.00 7,200.00 Signed 2021-01-27 2021-02-15 2021-02-01 2021-03-22 2021-02-22 2021-04-16 2021-03-29 2021-04-20 2021-09-25 ant Selection chauffeur coursier pour l'ant nt enne de Matadi ZR-UCP-PADMPME-216364- Component 3: Capacity buil CS-INDV / Recrutement d'un Individual Consult IDA / 62870 ding and Project Manageme Post Limited 9,600.00 9,600.00 Signed 2021-01-27 2021-02-16 2021-02-01 2021-03-30 2021-02-22 2021-04-27 2021-03-29 2021-04-29 2021-09-25 Chauffeur de la Coordinnatio ant Selection nt n pour le projet PADMPME ZR-UCP-PADMPME-150611- CS-CDS / Contractualisation avec le Cabinet CARAPACES Component 1: Support entr pour la phase 2 de la missio IDA / 62870 epreneurship opportunities Prior Direct Selection Direct 500,000.00 0.00 Canceled 2020-02-05 2020-02-14 2020-02-15 2020-03-06 2020-04-20 2020-10-17 n portant sur l'accompagne for youth and women ment à la mise en oeuvre de s réformes du cadre juridiqu e des PME ZR-UCP-PADMPME-215822- Component 3: Capacity buil CS-INDV / Renouvellement d Individual Consult IDA / 62870 ding and Project Manageme Post Direct 37,800.00 37,800.00 Signed 2021-01-25 2021-03-19 2021-02-04 2021-01-22 2021-02-25 2021-01-28 2021-04-01 2021-01-29 2021-09-28 u contrat de Mr TSHIENDA B ant Selection nt enjamin en sa qualité de Co mptable du PADMPME ZR-UCP-PADMPME-215720- CS-INDV / Renouvellement d Component 3: Capacity buil Individual Consult u contrat de Mr KAKUDJI Rap IDA / 62870 ding and Project Manageme Post Direct 50,400.00 50,400.00 Signed 2021-01-25 2021-03-19 2021-02-04 2021-01-22 2021-02-25 2021-01-28 2021-04-01 2021-01-30 2021-09-28 ant Selection haël en sa qualité de Spécial nt iste en Suivi et Evaluation ZR-UCP-PADMPME-215809- CS-INDV / Renouvellement Component 3: Capacity buil Individual Consult du contrat de Mr BOKANDEN IDA / 62870 ding and Project Manageme Post Direct 50,400.00 48,000.00 Signed 2021-01-25 2021-03-19 2021-02-04 2021-01-22 2021-02-25 2020-01-28 2021-04-01 2021-01-29 2021-09-28 ant Selection GA Roger en sa qualité de S nt pécialiste en Sauvegarde En vironnementale et Sociale ZR-UCP-PADMPME-215812- Component 3: Capacity buil CS-INDV / Renouvellement d Individual Consult IDA / 62870 ding and Project Manageme Post Direct 56,760.00 56,760.00 Signed 2021-01-25 2021-03-19 2021-02-04 2021-01-22 2021-02-25 2021-01-28 2021-04-01 2021-01-29 2021-09-28 u contrat de Mr NDONJI Kevi ant Selection nt n en sa qualité d'Auditeur In terne du PADMPME ZR-UCP-PADMPME-215820- CS-INDV / Renouvellement d Component 3: Capacity buil Individual Consult u contrat de Mr BASEMA Mei IDA / 62870 ding and Project Manageme Post Direct 56,760.00 56,760.00 Signed 2021-01-25 2021-03-19 2021-02-04 2021-01-22 2021-02-25 2021-01-28 2021-04-01 2021-01-29 2021-09-28 ant Selection lleur du Responsable Admini nt stratif et financier du PADMP ME ZR-UCP-PADMPME-218524- Component 3: Capacity buil CS-INDV / Renouvellement d Individual Consult IDA / 62870 ding and Project Manageme Post Direct 9,600.00 9,600.00 Signed 2021-02-09 2021-03-19 2021-02-19 2021-01-29 2021-03-12 2021-02-01 2021-04-16 2021-02-04 2021-10-13 u contrat du Chauffeur du C ant Selection nt oordonnateur de l'UCP-PAD MPME ZR-UCP-PADMPME-164525- Component 3: Capacity buil CS-INDV / Recrutement d'un Individual Consult IDA / 62870 ding and Project Manageme Post Limited 12,000.00 0.00 Canceled 2020-04-30 2020-05-05 2020-05-26 2020-06-30 2020-12-27 Assistant administratif et fin ant Selection nt ancier pour l'UCP PADMPME ZR-UCP-PADMPME-216293- CS-INDV / Recrutement d'un Component 3: Capacity buil Individual Consult Consultant individuel Spécial IDA / 62870 ding and Project Manageme Post Direct 54,000.00 0.00 Canceled 2021-02-22 2021-03-04 2021-03-25 2021-04-29 2021-10-26 ant Selection iste en Passation des march nt és pour le compte du PADMP ME ZR-UCP-PADMPME-226471- CS-INDV / Renouvellement d Component 3: Capacity buil Individual Consult u contrat de Mr Odon-Charle IDA / 62870 ding and Project Manageme Post Direct 48,000.00 48,000.00 Signed 2021-03-25 2021-04-02 2021-04-04 2021-02-26 2021-04-25 2021-02-26 2021-05-30 2021-03-02 2021-11-26 ant Selection s MUBIALA en sa qualité de nt Spécialiste en Petites et Moy ennes Entreprises ZR-UCP-PADMPME-226478- Component 3: Capacity buil CS-INDV / Renouvellement d Individual Consult IDA / 62870 ding and Project Manageme Post Direct 30,000.00 30,000.00 Signed 2021-03-25 2021-04-02 2021-04-04 2021-03-11 2021-04-25 2021-03-16 2021-05-30 2021-03-16 2021-11-26 u contrat de Mr Venance N'S ant Selection nt AKA en sa qualité de Trésori er ZR-UCP-PADMPME-226489- Component 3: Capacity buil CS-INDV / Renouvellemet du Individual Consult IDA / 62870 ding and Project Manageme Post Direct 274,750.00 301,821.00 Signed 2021-03-25 2021-04-02 2021-04-04 2021-02-09 2021-04-25 2021-01-27 2021-05-30 2021-01-27 2021-11-26 contrat de Mr Alexis MANGA ant Selection nt LA en qualité de Coordonnat eur National du ZR-UCP-PADMPME-226467- Component 3: Capacity buil CS-CDS / Recrutement de Th Under Implement IDA / 62870 ding and Project Manageme Post Direct Selection Direct 54,000.00 0.00 2021-03-30 2021-03-15 2021-04-09 2021-06-13 2021-12-10 omas TSHIMANGA en qualité ation nt de Spécialiste en Passation des marchés Page 9 ZR-UCP-PADMPME-226579- CS-INDV / Recrutement d’un consultant individuel chargé Component 3: Capacity buil de l’identification des réform Individual Consult IDA / 62870 ding and Project Manageme Post Open 60,000.00 0.00 Canceled 2021-04-15 2021-06-03 2021-06-24 2021-07-29 2022-01-25 es à réaliser dans les zones ant Selection nt du projet en vue de la mise sur pied d’un cadre juridique attractif pour les micro, petit es et moyennes entreprises ZR-UCP-PADMPME-229974- CS-CDS / Contractualisation Component 1: Support entr avec Mr Patrick ABEDI MAPA IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-06-05 2021-08-09 2022-02-05 SSA comme formateur dans for youth and women le cadre de la formation à l’i nitiative personnelle à Goma ZR-UCP-PADMPME-229981- CS-CDS / Contractualisation Component 1: Support entr avec Mr Albert KALONJI MBW IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-06-05 2021-08-09 2022-02-05 ENGELA comme formateur d for youth and women ans le cadre de la formation à l’initiative personnelle à Lu bumbashi ZR-UCP-PADMPME-226604- CS-INDV / Recrutement d’un Consultant individuel chargé Component 2. SME Develop Individual Consult de la réalisation de Screenin IDA / 62870 Post Limited 60,000.00 0.00 Canceled 2021-04-12 2021-03-30 2021-04-17 2021-05-08 2021-06-12 2021-12-09 ment ant Selection g environnemental et social dans des Centres des PME à Goma, Lubumbashi, Matadi et Kinshasa. ZR-UCP-PADMPME-239515- CS-INDV / Renouvellement d Component 3: Capacity buil Individual Consult u contrat de Madame NSIMB IDA / 62870 ding and Project Manageme Post 50,400.00 0.00 Canceled 2021-07-05 2021-07-09 2021-07-18 2021-08-08 2021-09-12 2022-03-11 ant Selection A Chantal, en qualité de Spé nt cialiste en Genre et Inclusio n Sociale ZR-UCP-PADMPME-239519- CS-INDV / Renouvellement d Component 3: Capacity buil Individual Consult u Contrat de Madame Syntic IDA / 62870 ding and Project Manageme Post Direct 10,800.00 0.00 Canceled 2021-06-25 2021-07-01 2021-07-05 2021-07-26 2021-08-30 2022-02-26 ant Selection he MULEMBA, en qualité de nt Réceptionniste du PADMPME ZR-UCP-PADMPME-147454- CS-INDV / Recrutement d'un Component 3: Capacity buil Individual Consult Consultant individuel chargé IDA / 62870 ding and Project Manageme Post Open 50,000.00 0.00 Canceled 2019-12-05 2020-01-23 2020-02-13 2020-03-19 2020-09-15 ant Selection d'élaborer le manuel de gest nt ion des subventions et gesti on des sous projets ZR-UCP-PADMPME-226470- CS-INDV / Renouvellement d Component 3: Capacity buil u contrat de Mr Andy DIATA Individual Consult Under Implement IDA / 62870 ding and Project Manageme Post Direct 4,000.00 0.00 2021-03-25 2021-02-23 2021-04-04 2021-04-25 2021-05-30 2021-11-26 OSOKONDA en sa qualité poi ant Selection ation nt nt focal au ministère de CMP MEA pour le compte de PAD MPME ZR-UCP-PADMPME-243597- CS-INDV / Renouvellement d Component 3: Capacity buil Individual Consult u contrat de Madame Gloria IDA / 62870 ding and Project Manageme Post Direct 25,200.00 0.00 Canceled 2021-07-15 2021-07-01 2021-07-25 2021-08-15 2021-09-19 2022-03-18 ant Selection MUKADI, Assistante en Pass nt ation des marchés du PADM PME. ZR-UCP-PADMPME-244321- CS-CDS / Contractualisation Component 1: Support entr Under Implement avec 9 coachs en qualité de IDA / 62870 epreneurship opportunities Post Direct Selection Direct 24,300.00 0.00 2021-08-09 2021-08-04 2021-08-19 2021-10-23 2022-04-21 ation formateur dans le cadre de l for youth and women a formation à l’initiative pers onnelle à Lubumbashi ZR-UCP-PADMPME-244322- CS-CDS / Contractualisation Component 1: Support entr Under Implement avec 9 coachs en qualité de IDA / 62870 epreneurship opportunities Post Direct Selection Direct 24,300.00 0.00 2021-08-09 2021-08-04 2021-08-19 2021-10-23 2022-04-21 ation formateur dans le cadre de l for youth and women a formation à l’initiative pers onnelle à Lubumbashi ZR-UCP-PADMPME-244324- CS-CDS / Contractualisation Component 1: Support entr Under Implement avec 9 coachs en qualité de IDA / 62870 epreneurship opportunities Post Direct Selection Direct 24,300.00 0.00 2021-08-09 2021-08-04 2021-08-19 2021-10-23 2022-04-21 ation formateur dans le cadre de l for youth and women a formation à l’initiative pers onnelle à Goma ZR-UCP-PADMPME-244325- CS-CDS / Contractualisation Component 1: Support entr Under Implement avec 9 coachs en qualité de IDA / 62870 epreneurship opportunities Post Direct Selection Direct 24,300.00 0.00 2021-08-09 2021-08-04 2021-08-19 2021-10-23 2022-04-21 ation formateur dans le cadre de l for youth and women a formation à l’initiative pers onnelle à Goma ZR-UCP-PADMPME-244983- Component 3: Capacity buil CS-INDV / Recrutement d'un Individual Consult Under Implement IDA / 62870 ding and Project Manageme Post Limited 36,000.00 0.00 2021-08-09 2021-08-13 2021-08-14 2021-09-04 2021-10-09 2022-04-07 comptable en charge des ag ant Selection ation nt ences d'exécution du projet ZR-UCP-PADMPME-247451- CS-INDV / Renouvellement d Component 3: Capacity buil Individual Consult u Contrat de Madame Clotild IDA / 62870 ding and Project Manageme Post Direct 48,000.00 0.00 Canceled 2021-08-10 2021-08-20 2021-09-10 2021-10-15 2022-04-13 ant Selection e MWAPE MUSANTWA, en qu nt alité de Cheffe d'Antenne de la Ville de Lubumbashi ZR-UCP-PADMPME-251032- Component 3: Capacity buil CS-INDV / Renouvellement d Individual Consult IDA / 62870 ding and Project Manageme Post Direct 18,000.00 0.00 Canceled 2021-08-30 2021-08-12 2021-09-09 2021-09-30 2021-11-04 2022-05-03 u contrat de Monsieur Carm ant Selection nt y KODIA, en qualité de IT Off icer ZR-UCP-PADMPME-251088- CS-CDS / Contractualisation avec Monsieur Joseph Lemoi Component 1: Support entr Under Implement ne, Consultant individuel ch IDA / 62870 epreneurship opportunities Post Direct Selection Direct 60,000.00 0.00 2021-09-20 2021-10-18 2021-09-30 2021-12-04 2022-06-02 ation argé d'assister le gouverne for youth and women ment dans l'élaboration des réformes du climat des affair es et des investissements. ZR-UCP-PADMPME-256818- CS-INDV / Renouvellement d Component 3: Capacity buil Individual Consult u contrat de Monsieur Pierre IDA / 62870 ding and Project Manageme Post Direct 48,000.00 0.00 Canceled 2021-10-06 2021-11-24 2021-10-16 2021-11-06 2021-12-11 2022-06-09 ant Selection MBAMBI, en qualité de Chef nt d'Antenne de PADMPME/Mat adi ZR-UCP-PADMPME-256819- CS-INDV / Renouvellement d Component 3: Capacity buil Individual Consult u contrat de Madame Esther IDA / 62870 ding and Project Manageme Post Direct 48,000.00 0.00 Canceled 2021-10-06 2021-10-16 2021-11-06 2021-12-11 2022-06-09 ant Selection KALANGA KABASELE, en qua nt lité de Chef d'Antenne de Go ma ZR-UCP-PADMPME-256823- CS-INDV / Renouvellement d Component 3: Capacity buil Individual Consult u contrat de Monsieur Gilber IDA / 62870 ding and Project Manageme Post Direct 9,600.00 0.00 Canceled 2021-10-06 2021-10-16 2021-11-06 2021-12-11 2022-06-09 ant Selection t MUR'A'SENG, en qualité de nt Chauffeur Coursier du PADM PME ZR-UCP-PADMPME-256895- CS-CDS / Contractualisation Component 3: Capacity buil Under Implement avec Monsieur KAPENGA LU IDA / 62870 ding and Project Manageme Post Direct Selection Direct 4,800.00 0.00 2021-10-11 2021-11-24 2021-10-21 2021-12-25 2022-06-23 ation FULUABO José, en qualité d' nt Agent nettoyeur de l'UCP/PA DMPME Page 10 ZR-UCP-PADMPME-256902- CS-CDS / Contractualisation Component 3: Capacity buil Under Implement avec Monsieur MASAMBA M IDA / 62870 ding and Project Manageme Post Direct Selection Direct 2,400.00 0.00 2021-10-11 2021-11-24 2021-10-21 2021-12-25 2022-06-23 ation AKENGO Baudouin, en qualit nt é d'Agent nettoyeur de l'Ant enne PADMPME/ Matadi ZR-UCP-PADMPME-256906- CS-CDS / Contractualisation Component 3: Capacity buil Under Implement avec Madame PONGA TIYAB IDA / 62870 ding and Project Manageme Post Direct Selection Direct 2,400.00 0.00 2021-10-11 2021-11-24 2021-10-21 2021-12-25 2022-06-23 ation O Russell, en qualité d'Agent nt nettoyeur à l'Antenne PADM PME/Goma ZR-UCP-PADMPME-256908- CS-CDS / Contractualisation Component 3: Capacity buil Under Implement avec Monsieur BWANGU MA IDA / 62870 ding and Project Manageme Post Direct Selection Direct 2,400.00 0.00 2021-10-11 2021-11-24 2021-10-21 2021-12-25 2022-06-23 ation BAYA Gaston, en qualité d'A nt gent nettoyeur à l'Antenne P ADMPME LUBUMBASHI ZR-UCP-PADMPME-256910- CS-CDS / Contractualisation Component 3: Capacity buil Under Implement avec Madame BAYENO NDU IDA / 62870 ding and Project Manageme Post Direct Selection Direct 4,800.00 0.00 2021-10-11 2021-11-24 2021-10-21 2021-12-25 2022-06-23 ation NDU Géneviève, en qualité d nt 'Agent nettoyeur à l'UCP-PA DMPME ZR-UCP-PADMPME-247507- CS-CDS / Contractualisation Component 1: Support entr avec Monsieur Joseph LEMOI IDA / 62870 epreneurship opportunities Post Direct Selection Direct 60,000.00 0.00 Canceled 2021-08-23 2021-08-20 2021-09-02 2021-11-06 2022-05-05 NE, en qualité de Consultant for youth and women Individuel en charge du Clim at des Investissements. ZR-UCP-PADMPME-229712- CS-CDS / Contractualisation Component 1: Support entr avec Mme Agnès KABWIZ A IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 KABEY MUYAMBO comme fo for youth and women rmateur dans le cadre de la formation à l’initiative perso nnelle à Lubumbashi ZR-UCP-PADMPME-229725- CS-CDS / Contractualisation Component 1: Support entr avec Mr Guillaume SANGWA IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 YAMBAMBA comme formate for youth and women ur dans le cadre de la forma tion à l’initiative personnelle à Lubumbashi ZR-UCP-PADMPME-229716- CS-CDS / Contractualisation Component 1: Support entr avec Mr Cédrick MAYUKA KI IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 NENKINDA comme formateu for youth and women r dans le cadre de la formati on à l’initiative personnelle à Lubumbashi ZR-UCP-PADMPME-229724- CS-CDS / Contractualisation Component 1: Support entr avec Mr Paul MUMBA SHIWA IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 MYA KAISA comme formateu for youth and women r dans le cadre de la formati on à l’initiative personnelle à Lubumbashi ZR-UCP-PADMPME-229718- CS-CDS / Contractualisation Component 1: Support entr avec Mr Ingrid-Nathan KIME IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 NGA LUZAMBO comme form for youth and women ateur dans le cadre de la for mation à l’initiative personn elle à Lubumbashi ZR-UCP-PADMPME-229719- CS-CDS / Contractualisation Component 1: Support entr avec Mr Jean-Jacques KALON IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 JI comme formateur dans le for youth and women cadre de la formation à l’initi ative personnelle à Lubumb ashi ZR-UCP-PADMPME-229702- CS-CDS / Contractualisation Component 1: Support entr avec Mme Sophie SAFI MAM IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 BO comme formateur dans l for youth and women e cadre de la formation à l’in itiative personnelle à Goma ZR-UCP-PADMPME-229700- CS-CDS / Contractualisation Component 1: Support entr avec Mme Nelly MBANGU M IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 ADIEKA comme formateur d for youth and women ans le cadre de la formation à l’initiative personnelle à G oma ZR-UCP-PADMPME-229714- CS-CDS / Contractualisation Component 1: Support entr avec Mme Angèle NSILULU IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 NGUILU comme formateur d for youth and women ans le cadre de la formation à l’initiative personnelle à Lu bumbashi ZR-UCP-PADMPME-229704- CS-CDS / Contractualisation Component 1: Support entr avec Mr Ayanza PALUKU TUT IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 WAVUNOKA comme formate for youth and women ur dans le cadre de la forma tion à l’initiative personnelle à Goma ZR-UCP-PADMPME-229693- CS-CDS / Contractualisation Component 1: Support entr avec Mme Eudoxie NZIAVAK IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 E SAANANE comme formate for youth and women ur dans le cadre de la forma tion à l’initiative personnelle à Goma ZR-UCP-PADMPME-229696- CS-CDS / Contractualisation Component 1: Support entr avec Mme Lauren MUNTU K IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 UNTADI comme formateur d for youth and women ans le cadre de la formation à l’initiative personnelle à G oma ZR-UCP-PADMPME-229697- CS-CDS / Contractualisation Component 1: Support entr avec Mme Lucie-Ornella SOS IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 OLE KAHONGYA comme for for youth and women mateur dans le cadre de la f ormation à l’initiative person nelle à Goma ZR-UCP-PADMPME-229970- CS-CDS / Contractualisation Component 1: Support entr avec Mme Marceline KAVIRA IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 MAGHULU YEYE comme for for youth and women mateur dans le cadre de la f ormation à l’initiative person nelle à Goma ZR-UCP-PADMPME-229709- CS-CDS / Contractualisation Component 1: Support entr avec Mme Valérie NABULA IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 WASSO comme formateur d for youth and women ans le cadre de la formation à l’initiative personnelle à G oma Page 11 ZR-UCP-PADMPME-229708- CS-CDS / Contractualisation Component 1: Support entr avec Mme Maguy-Rachel YU IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 LA DJEMA comme formateur for youth and women dans le cadre de la formatio n à l’initiative personnelle à Goma ZR-UCP-PADMPME-229695- CS-CDS / Contractualisation Component 1: Support entr avec Mr Robert KITSA BASH IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 ALI comme formateur dans l for youth and women e cadre de la formation à l’in itiative personnelle à Goma ZR-UCP-PADMPME-229698- CS-CDS / Contractualisation Component 1: Support entr avec Mr Donat MAMBO MWE IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 NELWATA comme formateur for youth and women dans le cadre de la formatio n à l’initiative personnelle à Goma ZR-UCP-PADMPME-229711- CS-CDS / Contractualisation Component 1: Support entr avec Mme Thérèse AMANI KI IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 TENGE comme formateur da for youth and women ns le cadre de la formation à l’initiative personnelle à Lub umbashi ZR-UCP-PADMPME-229722- CS-CDS / Contractualisation Component 1: Support entr avec Mr Gaël MBALA KANGU IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 LUNGU comme formateur da for youth and women ns le cadre de la formation à l’initiative personnelle à Lub umbashi ZR-UCP-PADMPME-229710- CS-CDS / Contractualisation Component 1: Support entr avec Mr Consolation WETSHI IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 TAMBO comme formateur d for youth and women ans le cadre de la formation à l’initiative personnelle à Lu bumbashi ZR-UCP-PADMPME-229701- CS-CDS / Contractualisation Component 1: Support entr avec Mr Jonathan MUHINDO IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 ITENGERO comme formateu for youth and women r dans le cadre de la formati on à l’initiative personnelle à Goma ZR-UCP-PADMPME-229707- CS-CDS / Contractualisation Component 1: Support entr avec Mr Glody WENGA BANY IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 AWA comme formateur dans for youth and women le cadre de la formation à l’i nitiative personnelle à Goma ZR-UCP-PADMPME-229705- CS-CDS / Contractualisation Component 1: Support entr avec Mr François KAZADI TS IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 HINEMU comme formateur d for youth and women ans le cadre de la formation à l’initiative personnelle à G oma ZR-UCP-PADMPME-229688- CS-CDS / Contractualisation Component 1: Support entr avec Mme Claudine NSHOKA IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 NO BALEZI comme formateu for youth and women r dans le cadre de la formati on à l’initiative personnelle à Goma ZR-UCP-PADMPME-229699- CS-CDS / Contractualisation Component 1: Support entr avec Mme Linda MASIKA KY IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 AKIMWA comme formateur d for youth and women ans le cadre de la formation à l’initiative personnelle à G oma ZR-UCP-PADMPME-229721- CS-CDS / Contractualisation Component 1: Support entr avec Mr Lucien TSHINUISHI IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 KALONDA comme formateu for youth and women r dans le cadre de la formati on à l’initiative personnelle à Lubumbashi ZR-UCP-PADMPME-229715- CS-CDS / Contractualisation Component 1: Support entr avec Mr Jean-Guelord BINEM IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 O SHASIMIADI comme form for youth and women ateur dans le cadre de la for mation à l’initiative personn elle à Lubumbashi ZR-UCP-PADMPME-229717- CS-CDS / Contractualisation Component 1: Support entr avec Mr David CHALWE com IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 me formateur dans le cadre for youth and women de la formation à l’initiative personnelle à Lubumbashi ZR-UCP-PADMPME-229728- CS-CDS / Contractualisation Component 1: Support entr avec Mr KAKEL MBUMB com IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 me formateur dans le cadre for youth and women de la formation à l’initiative personnelle à Lubumbashi ZR-UCP-PADMPME-229713- CS-CDS / Contractualisation Component 1: Support entr avec Mme Aimée MANYONG IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 MUYUMB comme formateur for youth and women dans le cadre de la formatio n à l’initiative personnelle à Lubumbashi ZR-UCP-PADMPME-229723- CS-CDS / Contractualisation Component 1: Support entr avec Mme Véronique MWAM IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 BA KABASHA comme format for youth and women eur dans le cadre de la form ation à l’initiative personnell e à Lubumbashi ZR-UCP-PADMPME-229720- CS-CDS / Contractualisation Component 1: Support entr avec Mme KYONA MUKEINA IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 comme formateur dans le ca for youth and women dre de la formation à l’initiat ive personnelle à Lubumbas hi ZR-UCP-PADMPME-261684- CS-CDS / Contractualisation Component 3: Capacity buil Under Implement avec Monsieur SEKETULA KI IDA / 62870 ding and Project Manageme Post Direct Selection Direct 54,000.00 0.00 2021-11-05 2021-11-03 2021-11-15 2022-01-19 2022-07-18 ation THIMA, en qualité de Spécial nt iste en Passation des march és du PADMPME. ZR-UCP-PADMPME-261711- Component 3: Capacity buil CS-INDV / Recrutement d'un Individual Consult Under Implement IDA / 62870 ding and Project Manageme Post Limited 4,000.00 0.00 2021-11-15 2022-01-06 2021-11-20 2021-12-11 2022-01-15 2022-07-14 consultant développeur Web ant Selection ation nt pour la mise à niveau du site web d Projet Page 12 ZR-UCP-PADMPME-261814- Component 3: Capacity buil CS-INDV / Recrutement d'un Individual Consult IDA / 62870 ding and Project Manageme Post Open 50,000.00 0.00 Canceled 2021-11-22 2022-01-07 2022-01-10 2022-01-31 2022-03-07 2022-09-03 consultant individuel pour la ant Selection nt revue qualité des livrables S DE ZR-UCP-PADMPME-272887- CS-INDV / Recrutement d'un Component 3: Capacity buil Individual Consult Consultant individuel Assista IDA / 62870 ding and Project Manageme Post Open 24,000.00 0.00 Under Review 2022-02-03 2022-03-15 2022-03-24 2022-04-14 2022-05-19 2022-11-15 ant Selection nt en sauvegarde environne nt mentale et sociale à l'Anten ne PADMPME de Goma ZR-UCP-PADMPME-272904- CS-INDV / Recrutement d'un Component 3: Capacity buil Individual Consult consultant individuel Assista IDA / 62870 ding and Project Manageme Post Open 24,000.00 0.00 Under Review 2022-02-02 2022-03-15 2022-03-23 2022-04-13 2022-05-18 2022-11-14 ant Selection nt en sauvegarde environne nt mentale et sociale à l'Anten ne /PADMPME à Lubumbashi ZR-UCP-PADMPME-273625- CS-INDV / Recrutement d'un Component 3: Capacity buil Individual Consult Consultant individuel Assista IDA / 62870 ding and Project Manageme Post Open 24,000.00 0.00 Under Review 2022-02-04 2022-03-15 2022-03-25 2022-04-15 2022-05-20 2022-11-16 ant Selection nt en sauvegarde environne nt mentale et sociale à l'Anten ne PADMPME de Matadi ZR-UCP-PADMPME-273644- CS-INDV / Recrutement d'un Component 3: Capacity buil Individual Consult Consultant Individuel Assista IDA / 62870 ding and Project Manageme Post Open 24,000.00 0.00 Under Review 2022-02-05 2022-03-15 2022-03-26 2022-04-16 2022-05-21 2022-11-17 ant Selection nt en sauvegarde environne nt mentale et sociale à l'UCP P ADMPME de KInshasa ZR-UCP-PADMPME-273651- CS-INDV / Recrutement d'un Component 3: Capacity buil Individual Consult Under Implement Consultant Individuel Assista IDA / 62870 ding and Project Manageme Post Limited 12,000.00 0.00 2022-02-07 2022-03-14 2022-02-12 2022-03-05 2022-04-09 2022-10-06 ant Selection ation nt Administratif et Financier nt à l'UCP PADMPME Kinshasa ZR-UCP-PADMPME-273657- Component 3: Capacity buil Individual Consult Under Implement CS-INDV / Recrutement d'un IDA / 62870 ding and Project Manageme Post Limited 4,800.00 0.00 2022-02-08 2022-03-14 2022-02-13 2022-03-06 2022-04-10 2022-10-07 ant Selection ation planton à l'UCP Kinshasa nt ZR-UCP-PADMPME-280338- CS-CDS / Contractualisation Component 1: Support entr Under Implement avec les formateurs formés IDA / 62870 epreneurship opportunities Post Direct Selection Direct 150,000.00 0.00 2022-02-22 2022-04-21 2022-03-04 2022-05-08 2022-11-04 ation et certifiés par Move (Kinsha for youth and women sa et Matadi) Formation FIP. ZR-UCP-PADMPME-283783- CS-CDS / Formation des jeun Component 1: Support entr es entrepreneurs en STEP: c Under Implement IDA / 62870 epreneurship opportunities Post Direct Selection Direct 120,000.00 0.00 2022-04-18 2022-04-21 2022-04-28 2022-07-02 2022-12-29 ontractualisation avec les fo ation for youth and women rmateurs formés et certifiés par le Cabinet Move (Kinsha sa, Matadi , Lubumbashi, et Goma) ZR-UCP-PADMPME-284033- Component 3: Capacity buil Individual Consult Under Implement CS-INDV / Recrutement d'un IDA / 62870 ding and Project Manageme Post Limited 12,000.00 0.00 2022-05-10 2022-04-26 2022-05-15 2022-06-05 2022-07-10 2023-01-06 ant Selection ation photographe infographe nt ZR-UCP-PADMPME-284037- Component 3: Capacity buil Individual Consult Under Implement CS-INDV / Recrutement d'un IDA / 62870 ding and Project Manageme Post Limited 12,000.00 0.00 2022-04-14 2022-04-26 2022-04-19 2022-05-10 2022-06-14 2022-12-11 ant Selection ation producteur de vidéo nt ZR-UCP-PADMPME-261678- CS-INDV / Renouvellement d Component 3: Capacity buil Individual Consult Pending Impleme u contrat de MONSIEUR JAN IDA / 62870 ding and Project Manageme Post Direct 50,400.00 0.00 2022-02-10 2022-02-20 2022-03-13 2022-04-17 2022-10-14 ant Selection ntation VIER KIAMBU MBAYA, en qua nt lité d'EXPERT JURISTE du PA DMPME ZR-UCP-PADMPME-229730- CS-INDV / Recrutement d’un Component 1: Support entr consultant individuel chargé Individual Consult IDA / 62870 epreneurship opportunities Post Open 75,000.00 0.00 Canceled 2021-05-10 2021-06-28 2021-07-19 2021-08-23 2022-02-19 de la promotion et de la mis ant Selection for youth and women e en place de plateformes pr ovinciales du dialogue public prive dans les zones du proj et. ZR-UCP-PADMPME-239527- CS-CDS / Contractualisation avec le Cabinet Vélior Dével Component 2. SME Develop IDA / 62870 Post Direct Selection Direct 50,000.00 0.00 Canceled 2021-07-19 2021-08-06 2021-07-29 2021-08-12 2021-10-02 2022-03-31 oppement chargé d'élaborer ment le manuel de gestion des su bventions et gestion des sou s projets. ZR-UCP-PADMPME-252790- CS-INDV / Recrutement d'un Component 3: Capacity buil Individual Consult consultant individuel Interna IDA / 62870 ding and Project Manageme Post Open 30,000.00 0.00 Canceled 2021-10-11 2021-11-29 2021-12-20 2022-01-24 2022-07-23 ant Selection tional pour conduire la revue nt à mi-parcours du projet PAD MPME ZR-UCP-PADMPME-261781- Component 1: Support entr CS-INDV / Recrutement d'un Individual Consult IDA / 62870 epreneurship opportunities Post Open 50,000.00 0.00 Canceled 2022-03-07 2022-04-25 2022-05-16 2022-06-20 2022-12-17 consultant individuel pour la ant Selection for youth and women revue de la loi sur la sous-tr aitance ZR-UCP-PADMPME-273773- CS-INDV / Recrutement d'un Component 3: Capacity buil Individual Consult Consultant Expert en Sauve IDA / 62870 ding and Project Manageme Post Open 48,000.00 0.00 Canceled 2022-02-02 2022-03-15 2022-03-23 2022-04-13 2022-05-18 2022-11-14 ant Selection garde Environnementale et nt Sociale en appui à l'UCP/PA DMPME ZR-UCP-PADMPME-261679- CS-INDV / Renouvellement d Component 3: Capacity buil Individual Consult u contrat de MADAME VERO IDA / 62870 ding and Project Manageme Post Direct 25,200.00 0.00 Canceled 2022-02-15 2022-02-25 2022-03-18 2022-04-22 2022-10-19 ant Selection NIQUE NGALULA BAKAMONA nt , en sa qualité de Logisticien ne. ZR-UCP-PADMPME-261694- CS-INDV / Renouvellement d Component 3: Capacity buil Individual Consult u Contrat de MONSIEUR JEA IDA / 62870 ding and Project Manageme Post Direct 50,400.00 0.00 Canceled 2022-02-15 2022-02-25 2022-03-18 2022-04-22 2022-10-19 ant Selection N-LUC MUALU, en qualité de nt Spécialiste en COMMUNICAT ION ZR-UCP-PADMPME-294824- Component 3: Capacity buil CS-CDS / Recrutement de M IDA / 62870 ding and Project Manageme Post Direct Selection Direct 36,000.00 0.00 Canceled 2022-07-01 2022-07-06 2022-07-11 2022-09-14 2023-03-13 me Elise MBUYU comme Ass nt istante du Coordonnateur N ational ZR-UCP-PADMPME-294830- Component 3: Capacity buil CS-CDS / Recrutement de M Under Implement IDA / 62870 ding and Project Manageme Post Direct Selection Direct 48,000.00 0.00 2022-06-01 2022-07-06 2022-06-11 2022-08-15 2023-02-11 me Mimie EYIMA Comme Ch ation nt effe d'Antenne de la Ville de Kinshasa ZR-UCP-PADMPME-299364- Component 3: Capacity buil CS-INDV / Consultant individ Individual Consult Under Implement IDA / 62870 ding and Project Manageme Post Open 8,700.00 0.00 2022-07-10 2022-10-19 2022-08-28 2022-09-18 2022-10-23 2023-04-21 uel pour la Formation staff e ant Selection ation nt n micro-informatique et en t élétravail à Lubumbashi ZR-UCP-PADMPME-299365- CS-INDV / Recrutement d'un Component 3: Capacity buil Individual Consult Under Implement consultant individuel pour la IDA / 62870 ding and Project Manageme Post Open 9,300.00 0.00 2022-07-10 2022-10-19 2022-08-28 2022-09-18 2022-10-23 2023-04-21 ant Selection ation Formation staff en micro-inf nt ormatique et en télétravail à Matadi Page 13 ZR-UCP-PADMPME-299366- CS-INDV / Recrutement d'un Component 3: Capacity buil Individual Consult Under Implement consultant individuel pour la IDA / 62870 ding and Project Manageme Post Open 8,400.00 0.00 2022-07-10 2022-08-28 2022-09-18 2022-10-23 2023-04-21 ant Selection ation Formation staff en micro-inf nt ormatique et en télétravail à Goma ZR-UCP-PADMPME-317461- CS-CDS / Contractualisation Component 3: Capacity buil Under Implement avec Madame NGALULA BA IDA / 62870 ding and Project Manageme Post Direct Selection Direct - National 30,000.00 0.00 2022-10-09 2022-10-20 2022-10-19 2022-12-23 2023-06-21 ation KAMONA Véronique, en quali nt té d'Assistante du Coordonn ateur National ZR-UCP-PADMPME-317607- Component 3: Capacity buil CS-CDS / Contractualisation Under Implement IDA / 62870 ding and Project Manageme Post Direct Selection Direct - National 30,000.00 0.00 2022-10-09 2022-10-20 2022-10-19 2022-12-23 2023-06-21 avec Elise MBUYU MBAYO, e ation nt n qualité de Secrétaire Admi nistrative du PADMPME ZR-UCP-PADMPME-317615- Component 3: Capacity buil Individual Consult Under Implement CS-INDV / Recrutement d'un IDA / 62870 ding and Project Manageme Post Limited 24,000.00 0.00 2022-10-16 2022-10-20 2022-10-21 2022-11-11 2022-12-16 2023-06-14 ant Selection ation logisticien pour le PADMPME nt ZR-UCP-PADMPME-317640- CS-INDV / Recrutement d'un consultant individuel chargé Component 3: Capacity buil Individual Consult Under Implement de la révision du manuel de IDA / 62870 ding and Project Manageme Post Limited 20,000.00 0.00 2022-10-09 2022-10-19 2022-10-14 2022-11-09 2022-11-04 2022-11-28 2022-12-09 2023-06-07 ant Selection ation procédures administratives, nt financières, comptables et d e passation des marchés du PADMPME et son adaptation au Projet ZR-UCP-PADMPME-295838- CS-INDV / Recrutement de d Component 1: Support entr eux consultants individuels Individual Consult IDA / 62870 epreneurship opportunities Post Open 50,000.00 0.00 Canceled 2022-06-13 2022-08-01 2022-08-22 2022-09-26 2023-03-25 en charge de la collecte de d ant Selection for youth and women onnées qualitatives sur l'imp act des activités de PADMPM E sur les femmes entreprene ures. ZR-UCP-PADMPME-251036- CS-INDV / Renouvellement d Component 3: Capacity buil Individual Consult u contrat de Mr TABARO Jul IDA / 62870 ding and Project Manageme Post Direct 12,000.00 0.00 Canceled 2021-08-30 2021-08-03 2021-09-09 2021-09-30 2021-11-04 2022-05-03 ant Selection es, en qualité d'Assistant Ad nt ministratif et Financier de l'A ntenne PADMPME/GOMA ZR-UCP-PADMPME-352013- CS-INDV / Recrutement d’un Component 1: Support entr Individual Consult Under Implement Consultant en reforme agro IDA / 62870 epreneurship opportunities Post Limited 50,000.00 0.00 2023-04-10 2023-03-24 2023-04-15 2023-05-06 2023-06-10 2023-12-07 ant Selection ation business et préparation du f for youth and women orum sur l’investissement ZR-UCP-PADMPME-352342- CS-INDV / Consultant en cha Component 1: Support entr rge des des reformes juridiq Individual Consult Under Implement IDA / 62870 epreneurship opportunities Post Limited 50,000.00 0.00 2023-04-10 2023-03-27 2023-04-15 2023-05-06 2023-06-10 2023-12-07 ues, règlementaires et instit ant Selection ation for youth and women utionnelles pour débloquer l' investissement dans le secte ur Agroalimentaire ZR-UCP-PADMPME-352301- CS-CDS / Contractualisation par Entente Directe avec Mr Charles MUSHIZI pour l'ident Component 1: Support entr Under Implement ification et l'élaboration des IDA / 62870 epreneurship opportunities Post Direct Selection Direct - National 20,000.00 0.00 2023-04-10 2023-04-14 2023-04-20 2023-04-14 2023-06-24 2023-12-21 ation mesures d'application des or for youth and women donnance-lois du 8 septemb re 2022, relatives à la prom otion de l'Entrepreneuriat et des Startups ainsi que l'arti sanat ZR-UCP-PADMPME-229694- CS-CDS / Contractualisation avec Mr Prosper KALOMBWE Component 1: Support entr MWENELUPANGO Claudine N IDA / 62870 epreneurship opportunities Post Direct Selection Direct 2,700.00 0.00 Canceled 2021-05-14 2021-07-08 2021-05-24 2021-07-28 2022-01-24 SHOKANO BALEZI comme fo for youth and women rmateur dans le cadre de la formation à l’initiative perso nnelle à Goma ZR-UCP-PADMPME-356589- CS-CDS / Contractualisation Component 3: Capacity buil Direct - Internation Pending Impleme avec le cabinet MOIHE Audit IDA / 62870 ding and Project Manageme Post Direct Selection 15,000.00 0.00 2023-04-30 2023-05-10 2023-07-14 2024-01-10 al ntation et Conseil pour l'audit exter nt ne financier et comptable de clôture du projet PADMPME ZR-UCP-PADMPME-360345- CS-INDV / Recrutement d'un consultant individuel pour él Component 2. SME Develop Individual Consult Under Implement IDA / 62870 Post Limited 15,000.00 0.00 2023-05-14 2023-05-11 2023-05-19 2023-06-09 2023-07-14 2024-01-10 aborer le PGES pour la const ment ant Selection ation ruction d’un hangar pour le centre des PME de Virunga à Goma ZR-UCP-PADMPME-360359- CS-INDV / Recrutement d'un Component 2. SME Develop Individual Consult Under Implement consultant individuel pour él IDA / 62870 Post Limited 15,000.00 0.00 2023-05-14 2023-05-11 2023-05-19 2023-06-09 2023-07-14 2024-01-10 ment ant Selection ation aborer un PGES pour la cons truction d’un Hangar pour I nginious CITY de Kinshasa ZR-UCP-PADMPME-365604- Component 3: Capacity buil CS-INDV / Recrutement d'un Individual Consult IDA / 62870 ding and Project Manageme Post Limited 6,000.00 0.00 Under Review 2023-07-10 2023-06-28 2023-07-15 2023-08-05 2023-09-09 2024-03-07 assistant administratif et fin ant Selection nt ancier pour la ville de Goma ZR-UCP-PADMPME-365609- CS-INDV / Recrutement d'un consultant pour élaborer de Component 1: Support entr s propositions de loi sur les Individual Consult IDA / 62870 epreneurship opportunities Post Limited 50,000.00 0.00 Under Review 2023-07-03 2023-06-28 2023-07-08 2023-07-29 2023-09-02 2024-02-29 mesures complémentaires n ant Selection for youth and women ationales au droit OHADA et l’actualisation de l'ouvrage s ur l'harmonisation du droit c ongolais avec les actes unifo rmes. Page 14 PROCUREMENT PLAN (Mandatory Requirements) Project information: Country: Bangladesh Project Name: Health and Gender Support Project for Cox’s Bazar District (HGSP) P-number: P171648 Project Implementation agency: Ministry of Health and Family Welfare (MoHFW) Period covered by this Procurement Plan: Entire Project Period Preamble In accordance with paragraph 5.9 of the World Bank Procurement Regulations for IPF Borrowers, July 2016, revised November 2017 and August 2018 (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to record all procurement actions for the Project, including preparing, updating and clearing its Procurement Plan, and seeking and receiving the Bank’s review and No-objection to procurement actions as required. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents (SPDs) shall be used for goods, works and non- consulting services where international competition is required and for all consulting services, including their respective forms of contract. National Procurement Arrangements: In accordance with paragraph 5.3 of the World Bank Procurement Regulations, when approaching the national market, as agreed in the Procurement Plan, the country’s own procurement procedures may be used. These procurement procedures shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti- Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Act 2006 and the Public Procurement Rules 2008, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: i. Lottery in award of contracts shall not be allowed; ii. Bidders’ qualification[s]/experience requirement[s] shall be mandatory; iii. Bids shall not be rejected based on percentage above or below the estimated cost; iv. Model Bidding Documents agreed with the Bank shall be used for all national open competitive procurement; v. The eligibility of bidders shall be as defined under Section III of the World Bank Procurement Regulations for IPF Borrowers: accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. vi. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. vii. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. As per paragraph 5.4 of the Procurement Regulations, the “Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework” as attached to this document shall form part of the Model Bidding Documents. Leased Assets: Not Applicable. Procurement of Second Hand Goods: Not Applicable. Domestic preference: as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works) as follows: Goods: Applicable; Works: Not applicable. Hands-on Expanded Implementation Support (HEIS): Not Applicable. Bank’s Procurement Prior Review Thresholds: contracts at or above the thresholds set out in table 1 below are subject to the Bank’s procurement prior review. Table 1: Procurement Prior Review Thresholds (US$ millions) Type of High risk Substantial Moderate Low risk procurement risk risk Works (including 5 10 15 20 turnkey, supply & installation of plant and equipment, and PPP) Goods, information 1.5 2 4 6 technology and non-consulting services Consulting 0.5 1 2 4 services: firms Consulting 0.2 0.3 0.4 0.5 services: Individual Notes: 1. These thresholds apply to all procurement activities regardless of their procurement/selection methods. There is no automatic requirement to undertake prior review for direct selection for value less than these thresholds. Consultant services covers a range of services that are of an advisory or professional nature. 2. In addition to the provisions of Table 1 above, and irrespective of the contract value, the following procurement activities are subject to the Bank’s procurement prior review: (a) procurement processes involving contract negotiations, as described in Section VI, paragraphs 6.34-36, of the Procurement Regulations; (b) competitive dialogue; (c) sustainable procurement; (d) selection of probity assurance providers, as described in Section III, paragraph 3.3 of the Procurement Regulations; and (e) best and final offer. 3. The determination of whether a contract meets the procurement prior review threshold is based on the estimated value of the contract or the package -when the selection document contains more than one lot/slice- , including all taxes and duties payable under the contract. Fraud and Corruption (F&C) Checklist: Fraud and Corruption (F&C) checklist, as developed and provided by the Bank, shall be properly filled in during the evaluation and be attached with the evaluation report in case of contracts following national competitive procurement and request for quotations. Attachment 1 Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: PROCUREMENT Bangladesh : Health and Gender Support Project for Cox’s Bazar district PLAN General Information Country: Bangladesh 2020-12-23 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171648 GPN Date: Project Name: Health and Gender Support Project for Cox’s Bazar district Loan / Credit No: IDA / D5920 Ministry of Health and Family Welfare Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned HGSP/P4 / Supporting HNP a Component 2: Strengthening nd GBV Service Delivery at t government system's capaci UN Agencies (Dire 31,000,000.0 31,000,000. 2023-06-3 IDA / D5920 Prior Direct Signed 2021-01-14 2021-01-18 2021-01-17 2021-01-19 2021-01-25 2021-02-08 he Community and District le ty to deliver enhanced servi ct) 0 00 0 vel in Cox’s Bazar District ces in CXB BD-MOHFW-352679-CW-RFB Component 2: Strengthening Request for Bids - / Construction / Re-constructi government system's capaci Single Stage - One E Works (without pr Pending Imp 2024-01-3 IDA / D5920 Post Request for Bids Open - National 2,700,000.00 0.00 2023-04-13 2023-04-18 2023-05-30 2023-06-29 2023-08-03 on works at Various Upazila ty to deliver enhanced servi nvelope equalification) SP lementation 0 Health Complex in Cox'sBaza ces in CXB D r District GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HGSP/P6 / Procurement of fir Component 3: Stewardship, IDA / D5920 Post Direct Selection Direct 828,402.37 0.00 Canceled 2021-09-21 2021-11-23 2021-10-01 2021-12-15 2021-12-30 st line TB drugs Management and Coordinati on HGSP/P5 / Procurement of m Component 3: Stewardship, IDA / D5920 Prior Direct Selection Direct 2,366,863.90 0.00 Canceled 2021-09-21 2021-10-01 2021-12-15 2021-12-30 edicine Management and Coordinati on HGSP/P-6 / Procurement of T Component 3: Stewardship, IDA / D5920 Prior Direct Selection Direct 1,241,000.00 1,279,007.40 Signed 2022-03-02 2022-03-25 2022-03-09 2022-05-26 2022-04-05 2022-06-09 2022-04-20 B drugs Management and Coordinati on HGSP/P-5 / Procurement of E Component 3: Stewardship, IDA / D5920 Prior Direct Selection Direct 3,600,000.00 0.00 Canceled 2022-05-23 2022-05-30 2022-07-04 2022-12-31 ssential drugs from EDCL Management and Coordinati on BD-MOHFW-348933-GO-DIR Component 2: Strengthening Under Revie / Procurement of Essential M IDA / D5920 government system's capaci Prior Direct Selection Direct - National 4,807,000.00 0.00 2023-03-30 2023-04-04 2023-05-09 2023-11-05 w edicines from EDCL ty to deliver enhanced servi ces in CXB HGSP/GD3 / Procurement of Component 2: Strengthening Open - Internationa Single Stage - One E Pending Impl Essential Medicines (Non ED IDA / D5920 government system's capaci Prior Request for Bids 2,800,000.00 0.00 2023-03-22 2023-03-27 2023-05-08 2023-06-07 2023-07-12 2024-01-08 l nvelope ementation CL) ty to deliver enhanced servi ces in CXB BD-MOHFW-365115-GO-DIR Component 2: Strengthening Direct - Internation Under Imple / Procurement of TB drugs, M IDA / D5920 government system's capaci Prior Direct Selection 3,001,801.85 0.00 2023-06-07 2023-06-09 2023-06-12 2023-06-12 2023-08-01 2024-01-28 al mentation SR and Lab equipment ty to deliver enhanced servi ces in CXB BD-MOHFW-362386-GO-DIR Component 2: Strengthening Under Imple / Essential Medicine from ED IDA / D5920 government system's capaci Prior Direct Selection Direct - National 1,678,106.52 0.00 2023-05-25 2023-06-09 2023-05-30 2023-07-19 2024-01-15 mentation CL by DPM ty to deliver enhanced servi ces in CXB NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthening HGSP/P1 / BV and SRHR Inte integrated HNP & GBV respo UN Agencies (Dire grated Services in Cox’s Baz IDA / D5920 Prior Direct 38,800,000.00 38,800,000.00 Signed 2020-12-24 2020-12-24 2020-12-28 2020-12-28 2021-01-15 2021-01-19 2023-06-30 nse services in all tiers of he ct) ar District alth care and in the DRP ca mps Component 1: Strengthening HGSP/P2 / MNCH and Nutriti integrated HNP & GBV respo UN Agencies (Dire on Service Delivery at Cox’s IDA / D5920 Prior Direct 31,000,000.00 31,000,000.00 Signed 2020-12-24 2021-01-19 2020-12-29 2021-01-20 2021-01-15 2021-02-08 2023-06-30 nse services in all tiers of he ct) Bazar District alth care and in the DRP ca mps HGSP/P3 / Technical Assistan Component 2: Strengthening UN Agencies (Dire ce support for HNP and GBV IDA / D5920 government system's capaci Prior Direct 18,700,000.00 18,700,000.00 Signed 2020-12-24 2020-12-24 2021-01-05 2020-12-28 2021-01-15 2021-01-23 2023-06-30 ct) service delivery in Cox’s Baz ty to deliver enhanced servi ar district ces in CXB CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 Third Village Investment Project (P146970) PROCUREMENT Kyrgyz Republic : Third Village Investment Project PLAN General Information Country: Kyrgyz Republic 2019-12-17 Bank’s Approval Date of the Original Procurement Plan: Revised Plan Date(s): (comma delineated, leave blank2023-05-24 if none) Project ID: P146970 GPN Date: 2022-11-22 Project Name: Third Village Investment Project Loan / Credit No: IDA / D0410, IDA / 56010, IDA / 67820, IDA / D7270 Community Development and Investment Agency Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process S Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Comple Description Component Review Type Method Amount (U ount (US$ and Recommendatio Signed Contract o. h cess (Y/N) isk ocument Type tatus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes tion S$) ) n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IDA-VIP3-HO-CW-NCB-20-1 / Construction of an additiona Single Stage - One 2021-01-1 l building for "Zhetigen" Kin IDA / D0410 Village Investments Post Request for Bids Open - National 152,173.91 132,012.63 Signed 2020-03-25 2020-04-17 2020-03-30 2020-05-11 2020-05-11 2020-06-10 2020-06-11 2020-07-15 2020-07-01 Envelope 1 dergarten in Beryu-Bash vill age, Ak-Suu region, Issyk-Ku l oblast IDA-VIP3-HO-CW-NCB-20-2 / Construction of a kindergart Single Stage - One 2021-01-1 IDA / D0410 Village Investments Post Request for Bids Open - National 143,500.00 468,937.48 Signed 2020-03-25 2020-04-17 2020-03-30 2020-05-11 2020-05-11 2020-06-10 2020-06-11 2020-07-15 2020-07-30 en for 100 places Ak-Sai vill Envelope 1 age, Ton region, Issyk-Kul o blast IDA-VIP3-HO-CW-NCB-20-3 / Construction of a kindergart Single Stage - One 2020-12-0 IDA / D0410 Village Investments Post Request for Bids Open - National 254,130.43 222,477.40 Signed 2020-02-21 2020-03-06 2020-02-26 2020-03-06 2020-04-08 2020-05-06 2020-05-08 2020-07-15 2020-06-12 2020-08-12 en for 50 places Zherge-Tal Envelope 9 village, Ak-Tala region, Nary n oblast IDA-VIP3-HO-CW-SH-20-3 / Construction of FAP in Kyzyl- Request for Quot Single Stage - One 2020-10-1 IDA / D0410 Village Investments Post Limited 28,418.48 31,135.12 Signed 2020-02-26 2020-02-21 2020-04-22 2020-03-17 Zhyldyz village, Zhumgal re ations Envelope 9 gion, Naryn oblast IDA-VIP3-HO-CW-NCB-20-4 / Construction of a kindergart Single Stage - One 2020-12-1 IDA / D0410 Village Investments Post Request for Bids Open - National 182,608.70 217,340.32 Signed 2020-02-24 2020-03-06 2020-02-29 2020-03-06 2020-04-11 2020-05-06 2020-05-11 2020-06-09 2020-06-15 2020-08-14 en for 50 places Zher-Kechk Envelope 2 yu village, Naryn region, Nar yn oblast IDA-VIP3-HO-CW-SH-20-6 / Construction of FAP in Tamc Request for Quot Single Stage - One 2020-11-2 IDA / D0410 Village Investments Post Limited 30,434.78 38,072.83 Signed 2020-03-30 2020-05-07 2020-05-25 2020-07-21 hy-Bulak village, Kara-Buura ations Envelope 1 region, Talas oblast IDA-VIP3-HO-CW-NCB-20-5 / Construction of a kindergart Single Stage - One 2020-12-1 IDA / D0410 Village Investments Post Request for Bids Open - National 258,695.65 205,590.46 Signed 2020-02-24 2020-03-06 2020-02-29 2020-03-06 2020-04-11 2020-08-05 2020-05-11 2020-08-13 2020-06-15 2020-08-21 en Ken-Aral village, Bakai-At Envelope 2 a region, Talas oblast IDA-VIP3-HO-CW-NCB-20-6 / Construction of a kindergart Single Stage - One 2020-12-1 IDA / D0410 Village Investments Post Request for Bids Open - National 227,991.99 226,285.69 Signed 2020-02-24 2020-03-06 2020-02-29 2020-03-06 2020-04-11 2020-05-06 2020-05-11 2020-06-09 2020-06-15 2020-07-21 en A.Ogonbaev village, Tala Envelope 2 s region, Talas oblast IDA-VIP3-HO-CW-NCB-20-7 / The device of a sewer collec Single Stage - One 2021-02-2 tor and connection to a city IDA / D0410 Village Investments Post Request for Bids Open - National 259,730.35 204,040.06 Signed 2020-05-04 2020-08-21 2020-05-09 2020-06-20 2020-09-11 2020-07-20 2020-09-23 2020-08-24 2020-10-16 Envelope 0 network in Nijnealarcha villa ge, Alamudun region, Chui o blast IDA-VIP3-HO-CW-SH-20-7 / Request for Quot Single Stage - One 2020-11-2 Asphalting of the road in Da IDA / D0410 Village Investments Post Limited 91,304.35 0.00 Canceled 2020-03-30 2020-05-25 ations Envelope 1 yyrbek village, Issyk-Ata reg ion, Chui oblast IDA-VIP3-HO-CW-SH-20-5 / Request for Quot Single Stage - One 2020-11-2 Construction of Library in Ot IDA / D0410 Village Investments Post Limited 45,652.17 0.00 Canceled 2020-03-30 2020-05-25 ations Envelope 1 tuk village, Naryn region, Na ryn oblast IDA-VIP3-HO-CW-SH-20-4 / Request for Quot Single Stage - One 2020-11-2 Construction of FAP in Chon- IDA / D0410 Village Investments Post Limited 39,565.00 0.00 Canceled 2020-03-30 2020-05-25 ations Envelope 1 Tash village, Tyup region, Is syk-Kul oblast IDA-VIP3-HO-CW-NCB-20-8 / Single Stage - One 2020-08-1 Construction of FAP in Chon- IDA / 56010 Village Investments Post Request for Bids Open - National 76,475.00 79,907.89 Signed 2020-04-24 2020-05-13 2020-04-29 2020-05-12 2020-06-10 2020-06-03 2020-07-10 2020-06-24 2020-07-31 2020-08-04 Envelope 5 Tash village, Tyup region, Is syk-Kul oblast IDA-VIP3-HO-CW-NCB-20-9 / Single Stage - One 2021-02-1 Construction of Library in Ot IDA / 56010 Village Investments Post Request for Bids Open - National 68,750.00 76,089.19 Signed 2020-04-27 2020-05-13 2020-05-02 2020-05-13 2020-06-13 2020-06-03 2020-07-13 2020-06-24 2020-08-17 2020-08-15 Envelope 3 tuk village, Naryn region, Na ryn oblast IDA-VIP3-HO-CW-SH-20-1 / Overhaul of school them. My Request for Quot Single Stage - One 2020-08-3 IDA / 56010 Village Investments Post Open - National 35,431.00 29,222.97 Completed 2020-02-17 2020-04-02 2020-03-26 rzakmatova in Kozhomkul vil ations Envelope 0 lage, Zhaiyl region, Chui obl ast IDA-VIP3-HO-CW-SH-20-2 / Request for Quot Single Stage - One 2020-09-1 Overhaul of kindergarten in IDA / 56010 Village Investments Post Open - National 65,625.00 45,323.76 Completed 2020-02-17 2020-04-13 2020-03-28 ations Envelope 0 Kaldyk village, Zhaiyl region , Chui oblast IDA-VIP3-HO-CW-NCB-20-10 Single Stage - One 2021-04-1 / Construction of GSV in Ak- IDA / D0410 Village Investments Post Request for Bids Open - National 102,958.00 91,295.42 Signed 2020-08-26 2020-09-04 2020-08-28 2020-09-18 2020-09-25 2020-10-18 2020-10-15 2020-11-15 2020-10-27 Envelope 4 Dobo village Bakai-Ata Ragi on, Talas Oblast IDA-VIP3-HO-CW-NCB-20-11 / Construction of kindergarte Single Stage - One 2021-10-0 IDA / 56010 Village Investments Post Request for Bids Open - National 519,484.00 401,429.27 Signed 2020-11-15 2020-12-02 2020-11-20 2020-12-02 2020-12-11 2020-12-23 2021-01-07 2021-01-26 2021-02-07 2021-02-26 n for 100 places in the Taldy Envelope 5 -Suu village, Tup Ragion, Iss yk-Kul oblast IDA-VIP3-HO-CW-NCB-20-12 / Construction of kindergarte Single Stage - One 2021-09-2 IDA / 56010 Village Investments Post Request for Bids Open - National 225,269.99 216,423.55 Signed 2020-12-09 2020-12-16 2020-12-10 2020-12-16 2020-12-31 2021-01-06 2021-01-30 2021-02-01 2021-02-28 2021-02-23 n for 50 places in the Dobol Envelope 6 u village, Naryn Ragion, Nar yn oblast IDA-VIP3-HO-CW-NCB-20-13 / Construction of kindergarte Single Stage - One 2021-08-3 IDA / 56010 Village Investments Post Request for Bids Open - National 225,707.41 215,418.47 Signed 2020-12-09 2020-12-16 2020-12-10 2020-12-16 2020-12-31 2021-01-06 2021-01-30 2021-02-05 2021-02-02 2021-02-20 n for 50 places in the Maym Envelope 1 ak village, Kara-Bura Ragion , Talas oblas IDA-VIP3-HO-CW-NCB-20-14 Single Stage - One 2021-08-1 / Repair of school in the villa IDA / 56010 Village Investments Post Request for Bids Open - National 194,077.52 198,757.36 Signed 2020-12-16 2020-12-25 2020-12-18 2020-12-28 2021-01-08 2021-01-15 2021-02-07 2021-02-03 2021-03-14 2021-02-18 Envelope 1 ge Stavropolovka, Zhayil ray on, Chui oblast IDA-VIP3-HO-CW-NCB-20-15 / Repair of the drinking wate Single Stage - One 2021-09-2 IDA / 56010 Village Investments Post Request for Bids Open - National 67,751.00 62,516.80 Signed 2021-02-10 2021-02-12 2021-02-11 2021-02-11 2021-03-04 2021-03-05 2021-04-03 2021-04-02 2021-04-29 2021-04-27 r supply system in the villag Envelope 6 e. Kadyraly, Ak-Tala rayon, Naryn oblast Page 1 IDA-VIP3-HO-CW-NCB-20-16 / Installation of lighting on th Single Stage - One 2021-11-0 e streets in the villages Zher IDA / 56010 Village Investments Post Request for Bids Open - National 42,730.00 48,268.97 Completed 2021-03-19 2021-03-19 2021-03-19 2021-04-09 2021-05-09 2021-05-09 2021-05-06 2021-06-09 2021-05-22 Envelope 6 -Kazar, Nizhniy-Nooruz, Druz hba Villages, Issyk-Ata Raion , Chuy Oblast IDA-VIP3-HO-CW-NCB-20-17 / Major Repair drinking wate Single Stage - One 2021-11-2 IDA / 56010 Village Investments Post Request for Bids Open - National 417,114.69 356,317.58 Completed 2021-04-09 2021-04-09 2021-04-09 2021-04-09 2021-04-30 2021-04-30 2021-05-30 2021-05-25 2021-06-28 2021-06-22 r system in the village Jyrgal Envelope 5 an Ak-Suu raijon Issyk-Kul o blast IDA-VIP3-HO-CW-NCB-20-18 / Major repair of kindergarte Single Stage - One 2021-11-2 IDA / 56010 Village Investments Post Request for Bids Open - National 294,029.83 0.00 Canceled 2021-04-02 2021-04-09 2021-04-02 2021-04-09 2021-04-23 2021-05-04 2021-05-23 2021-05-24 2021-06-23 n "ALENKA" in the village Pr Envelope 0 edtechenka Moscow rajion C hui oblast IDA-VIP3-HO-CW-NCB-20-19 / Construction of FAPs`in the Single Stage - One 2021-12-0 village Min-Bulak Bakai-Ata r IDA / 56010 Village Investments Post Request for Bids Open - National 134,529.40 89,501.47 Signed 2021-04-15 2021-04-23 2021-04-15 2021-04-23 2021-05-06 2021-05-14 2021-06-05 2021-06-23 2021-07-06 2021-08-25 Envelope 3 aijion Talas oblast and in the village Min-Bulak Typ rajion I ssyk-Kul oblast IDA-VIP3-HO-CW-NCB-20-20 Request for Bids / Construction of FAPs`in the Single Stage - One - Small Works SP 2021-12-1 village Ak-Bulun Tup raijion I IDA / 56010 Village Investments Post Request for Bids Open - National 106,382.00 92,992.83 Signed 2021-04-30 2021-05-21 2021-04-30 2021-05-21 2021-06-11 2021-06-20 2021-07-16 2021-07-21 2021-07-19 Envelope D (1 envelope pr 8 ssyk-Kul oblast and in the vil ocess) lage Kaiyndy-Bulak Ak-Talaa rajion Naryn oblast IDA-VIP3-HO-CW-NCB-20-18 Request for Bids /RT / Major repair of kinderg Single Stage - One - Small Works SP 2022-02-1 IDA / 56010 Village Investments Post Request for Bids Open - National 294,029.93 310,497.68 Signed 2021-05-27 2021-05-28 2021-06-01 2021-06-22 2021-06-22 2021-07-22 2021-07-21 2021-08-18 2021-08-26 arten "ALENKA" in the villag Envelope D (1 envelope pr 4 e Predtechenka Moscow raji ocess) on Chui oblast IDA-VIP3-HO-CW-NCB-20-21 / Construction of FAPs`in the Request for Bids village Jar-Bashy Internation Single Stage - One - Small Works SP 2022-03-0 IDA / 56010 Village Investments Post Request for Bids Open - National 114,282.76 53,199.76 Signed 2021-07-16 2021-07-16 2021-07-16 2021-08-06 2021-08-06 2021-09-05 2021-08-12 2021-10-06 2021-09-10 al AA Isyk-Ata district Chui Envelope D (1 envelope pr 5 oblast and in the village Bes ocess) h-Koruk Aleksandrovski AA Moscow district Chui oblast National Procure IDA-VIP3-HO-CW-NCB-20-22 ment Document - / Overhaul of the FAP buildin Single Stage - One 2022-05-2 IDA / 56010 Village Investments Post Request for Bids Open - National 1 Envelope proce 55,895.17 57,767.93 Signed 2021-09-07 2021-09-10 2021-09-07 2021-09-28 2021-10-01 2021-11-27 2021-10-20 2021-12-28 2021-11-17 g in the village Ozgorush Oz Envelope 7 ss (Non Bank-SP gorush AO Bakai-Ata rayon D) of Talas oblast IDA-VIP3-HO-CW-NCB-20-23 National Procure / Overhaul of the FAP buildin ment Document - g and improvement of the s Single Stage - One 2022-05-2 IDA / 56010 Village Investments Post Request for Bids Open - National 1 Envelope proce 51,029.51 0.00 Canceled 2021-09-07 2021-09-10 2021-09-07 2021-09-28 2021-11-27 2021-12-28 anitary and hygienic conditi Envelope 7 ss (Non Bank-SP ons of the kindergarten in th D) e village. Konorchok of Kono rchok AO Ak-Tala rayon Nar yn oblast National Procure IDA-VIP3-HO-CW-NCB-20-24 ment Document - / Renovation of high school Single Stage - One 2022-05-3 IDA / 56010 Village Investments Post Request for Bids Open - National 1 Envelope proce 56,713.16 56,418.69 Signed 2021-09-08 2021-09-10 2021-09-10 2021-10-01 2021-10-01 2021-11-30 2021-10-19 2021-12-31 2021-11-17 sanitary facilities. in with. Ky Envelope 0 ss (Non Bank-SP z-Molo Moscow rayon Chui o D) blast IDA-VIP3-HO-CW-SH-20-25 / Installation of sanitary facilit Request for Quot Request for Quot Single Stage - One 2022-04-2 ies in schools of villages Ken IDA / D0410 Village Investments Post Open - National ations (Non Bank 48,625.00 0.00 Canceled 2021-10-08 2021-11-28 ations Envelope 7 -Suu, Sary-Tologoi, San-Tash -SPD) of the San-Tash AA Tup distr ict Issyk-Kul oblast IDA-VIP3-HO-CW-NCB-20-23 National Procure /RT / Installation of sanitary ment Document - Single Stage - One 2022-05-0 facilities in schools of village IDA / D0410 Village Investments Post Request for Bids Open - National 1 Envelope proce 51,029.51 0.00 Canceled 2021-10-11 2021-10-11 2021-11-01 2021-11-29 2021-12-05 Envelope 4 s Ken-Suu, Sary-Tologoi, San ss (Non Bank-SP -Tash of the San-Tash AA Tu D) p district Issyk-Kul oblast IDA-VIP3-HO-CW-SH-20-25/ Request for Quot RT2 / Installation of sanitary Request for Quot Single Stage - One ations - Small Wo 2022-05-1 facilities in schools of village IDA / 56010 Village Investments Post Open - National 48,625.00 38,108.87 Completed 2021-11-15 2021-12-20 2021-12-16 ations Envelope rks (Emergency) 9 s Ken-Suu, Sary-Tologoi, San SPD -Competitive -Tash of the San-Tash AA Tu p district Issyk-Kul oblast IDA-VIP3-HO-CW-NCB-20-23 /RT2 / Overhaul of the FAP b Request for Bids uilding and improvement of Single Stage - One - Small Works SP 2022-06-1 the sanitary and hygienic co IDA / 56010 Village Investments Post Request for Bids Open - National 51,029.51 60,733.39 Signed 2021-11-19 2021-11-19 2021-11-19 2021-12-10 2021-11-19 2021-12-24 2022-01-11 2022-01-16 2022-01-29 Envelope D (1 envelope pr 5 nditions of the kindergarten ocess) in the village. Konorchok of Konorchok AO Ak-Tala rayon Naryn oblast ARIS-IDA-AF-VIP-3-CW-23-1 / Improving sanitary and hyg Request for Quot Pending Im ienic conditions and replacin Request for Quot Single Stage - One 2023-12-3 IDA / 56010 Village Investments Post Open - National ations (Non Bank 58,550.00 0.00 plementatio 2023-05-30 2023-07-04 g electrical wires and repair ations Envelope 1 -SPD) n s at the "Teremok" preschoo l educational establishment i n the village of Prigorodnoye ARIS-IDA-AF-VIP-3-CW-23-2 Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 / Replacing the roof of the s IDA / 67820 Village Investments Post Open - National ations (Non Bank 33,700.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 chool in Ozernoye village -SPD) n ARIS-IDA-AF-VIP-3-CW-23-3 Request for Quot Pending Im / Rehabilitation of indoor san Request for Quot Single Stage - One 2023-12-3 IDA / 67820 Village Investments Post Open - National ations (Non Bank 25,000.00 0.00 plementatio 2023-05-30 2023-07-04 itary facilities in the seconda ations Envelope 1 -SPD) n ry school in the village of Sa ry-Bulak ARIS-IDA-AF-VIP-3-CW-23-4 Request for Quot Pending Im / Replacing the interior and Request for Quot Single Stage - One 2023-12-3 IDA / 67820 Village Investments Post Open - National ations (Non Bank 25,000.00 0.00 plementatio 2023-05-30 2023-07-04 exterior doors of the second ations Envelope 1 -SPD) n ary school in the village of A k-Tyuz ARIS-IDA-AF-VIP-3-CW-23-5 / Installation of an indoor sa Request for Quot Pending Im nitary facilities in the second Request for Quot Single Stage - One 2023-12-3 IDA / 67820 Village Investments Post Open - National ations (Non Bank 33,000.00 0.00 plementatio 2023-05-30 2023-07-04 ary village of Ilyich village a ations Envelope 1 -SPD) n nd repair of indoor facilities i n the secondary school of So vetskoye village ARIS-IDA-AF-VIP-3-CW-23-6 Request for Quot Pending Im / Rehabilitation of indoor san Request for Quot Single Stage - One 2023-12-3 IDA / 67820 Village Investments Post Open - National ations (Non Bank 33,000.00 0.00 plementatio 2023-05-30 2023-07-04 itary facilities in the seconda ations Envelope 1 -SPD) n ry school of Kichi-Kemin villa ge ARIS-IDA-AF-VIP-3-CW-23-7 Request for Quot Pending Im / Repair of the sewage syste Request for Quot Single Stage - One 2023-12-3 IDA / 67820 Village Investments Post Open - National ations (Non Bank 25,000.00 0.00 plementatio 2023-05-30 2023-07-04 m of the "Kutu-Yan" kinderg ations Envelope 1 -SPD) n arten in Tolok village ARIS-IDA-AF-VIP-3-CW-23-8 Request for Quot Pending Im / Rehabilitation of the water Request for Quot Single Stage - One 2023-12-3 IDA / 67820 Village Investments Post Open - National ations (Non Bank 25,000.00 0.00 plementatio 2023-05-30 2023-07-04 supply system of a secondar ations Envelope 1 -SPD) n y school in the village of Tse linnyi Page 2 ARIS-IDA-AF-VIP-3-CW-23-9 Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 / Replacing the roof of the s IDA / 67820 Village Investments Post Open - National ations (Non Bank 33,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 econdary school building in -SPD) n Spartak Village ARIS-IDA-AF-VIP-3-CW-23-1 0 / Repairing the sewage sys Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 tem of the canteen and repa IDA / 67820 Village Investments Post Open - National ations (Non Bank 41,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 iring the indoor sanitary facil -SPD) n ities of the secondary school of Erkin-Sai village ARIS-IDA-AF-VIP-3-CW-23-1 Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 1 / Replacing the roof of the IDA / 67820 Village Investments Post Open - National ations (Non Bank 33,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 secondary school in Kamysh -SPD) n anovka village ARIS-IDA-AF-VIP-3-CW-23-1 2 / Repair of ventilation syst National Procure em and sanitary facilities an ment Document - Pending Im d replacement of windows a Single Stage - One 2024-02-2 IDA / 67820 Village Investments Post Request for Bids Open - National 1 Envelope proce 115,294.00 0.00 plementatio 2023-05-25 2023-05-30 2023-07-11 2023-08-10 2023-08-24 nd doors of the secondary s Envelope 0 ss (Non Bank-SP n chool named after Ch.Aitma D) tov and secondary school # 1. Installation of an outdoor toilet at the secondary scho ol #2 ARIS-IDA-AF-VIP-3-CW-23-1 3 / Repair of sanitary facilitie Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 s, electrical wiring, plumbing IDA / 67820 Village Investments Post Open - National ations (Non Bank 54,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 and sewage systems in the -SPD) n kindergarten in Krasnaya Re chka village ARIS-IDA-AF-VIP-3-CW-23-1 4 / Improving the energy effi Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 ciency (insulation of exterior IDA / 67820 Village Investments Post Open - National ations (Non Bank 65,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 walls and roofing) of Balasta -SPD) n n Kindergarten in Boz-Uchuk village ARIS-IDA-AF-VIP-3-CW-23-1 5 / Improving sanitary and h Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 ygienic conditions (installing IDA / 67820 Village Investments Post Open - National ations (Non Bank 13,640.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 hand-washing sinks) in the s -SPD) n chool named after Asanaliev in Otuz-Uul village ARIS-IDA-AF-VIP-3-CW-23-1 6 / Improving the energy effi Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 ciency (insulation of exterior IDA / 67820 Village Investments Post Open - National ations (Non Bank 37,580.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 walls and roofing) of the "Alt -SPD) n yn Beshik" kindergarten in O ktyabr Village ARIS-IDA-AF-VIP-3-CW-23-1 7 / Improvement of energy e Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 fficiency (installation of wind IDA / 67820 Village Investments Post Open - National ations (Non Bank 60,580.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 ows) at the school named af -SPD) n ter Mamakeev in the village of Teplokluchenka ARIS-IDA-AF-VIP-3-CW-23-1 8 / Improving energy efficie ncy (installation of windows) Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 and sanitary and hygienic co IDA / 67820 Village Investments Post Open - National ations (Non Bank 54,300.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 nditions (installation of hand -SPD) n -washing sinks) in school na med after Kirov in the villag e of Teplocluchenka ARIS-IDA-AF-VIP-3-CW-23-1 9 / Improvement of energy e Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 fficiency (insulation of exteri IDA / 67820 Village Investments Post Open - National ations (Non Bank 85,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 or walls) of the school name -SPD) n d after D. Imanov in Zheti-O guz village ARIS-IDA-AF-VIP-3-CW-23-2 0 / Improvement of sanitary Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 and hygienic conditions (rep IDA / 67820 Village Investments Post Open - National ations (Non Bank 54,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 air of sanitary facilities) in sc -SPD) n hools in Toru-Aygyr village a nd Sary-Kamysh village ARIS-IDA-AF-VIP-3-CW-23-2 Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 1 / Repair of sanitary facilitie IDA / 67820 Village Investments Post Open - National ations (Non Bank 64,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 s at Ch.Asekov Secondary S -SPD) n chool ARIS-IDA-AF-VIP-3-CW-23-2 Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 2 / Renovation of the FAP in IDA / 67820 Village Investments Post Open - National ations (Non Bank 33,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 the village of Epkin -SPD) n ARIS-IDA-AF-VIP-3-CW-23-2 Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 3 / Construction of a Family IDA / 67820 Village Investments Post Open - National ations (Non Bank 75,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 Practice Center (GFD) in Zha -SPD) n ny-Aryk village ARIS-IDA-AF-VIP-3-CW-23-2 Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 4 / Repair of FAP with the pu IDA / 67820 Village Investments Post Open - National ations (Non Bank 65,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 rchase of equipment in Kara -SPD) n -Suu village Request for Quot ARIS-IDA-AF-VIP-3-CW-23-2 Request for Quot Single Stage - One Pending Im 2023-12-3 IDA / 67820 Village Investments Post Open - National ations (Non Bank 70,450.00 0.00 2023-05-30 2023-07-04 5 / Construction of a FAP in ations Envelope plementatio 1 -SPD) Tendik village n Request for Quot ARIS-IDA-AF-VIP-3-CW-23-2 Request for Quot Single Stage - One Pending Im 2024-01-2 IDA / 67820 Village Investments Post Open - National ations (Non Bank 26,350.00 0.00 2023-05-30 2023-07-25 6 / Insulation of the school ( ations Envelope plementatio 1 -SPD) sports hall) n ARIS-IDA-AF-VIP-3-CW-23-2 Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 7 / Insulation of the school i IDA / 67820 Village Investments Post Open - National ations (Non Bank 95,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 n Oro-Bashy village -SPD) n ARIS-IDA-AF-VIP-3-CW-23-2 8 / Improving energy efficie Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 ncy and sanitary conditions IDA / 67820 Village Investments Post Open - National ations (Non Bank 25,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 (replacing windows and door -SPD) n s in the kindergarten and re pairing sanitary facilities) ARIS-IDA-AF-VIP-3-CW-23-2 9 / Improvement of sanitary Request for Quot Pending Im Request for Quot Single Stage - One 2024-01-2 and hygienic conditions (Inst IDA / 67820 Village Investments Post Open - National ations (Non Bank 54,000.00 0.00 plementatio 2023-05-30 2023-07-25 ations Envelope 1 allation of sanitary facilities i -SPD) n n the secondary school nam ed after Zh. Mambetov) ARIS-IDA-AF-VIP-3-CW-23-3 0 / Improvement of sanitary Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 condition, replacement of th IDA / 67820 Village Investments Post Open - National ations (Non Bank 54,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 e roof in the secondary scho -SPD) n ol named after U. Akynbeko v ARIS-IDA-AF-VIP-3-CW-23-3 Request for Quot Pending Im 1 / Replacing the heating sy Request for Quot Single Stage - One 2023-12-3 IDA / 67820 Village Investments Post Open - National ations (Non Bank 54,000.00 0.00 plementatio 2023-05-30 2023-07-04 stem, flooring the secondary ations Envelope 1 -SPD) n school named after Toichub ek uulu Zhanadil ARIS-IDA-AF-VIP-3-CW-23-3 Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 2 / Construction of a FAP in t IDA / 67820 Village Investments Post Open - National ations (Non Bank 41,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 he village of Kamash -SPD) n Page 3 ARIS-IDA-AF-VIP-3-CW-23-3 Request for Quot Pending Im 3 / Replacement of roof, win Request for Quot Single Stage - One 2023-12-3 IDA / 67820 Village Investments Post Open - National ations (Non Bank 54,000.00 0.00 plementatio 2023-05-30 2023-07-04 dows and exterior doors of t ations Envelope 1 -SPD) n he secondary school named after T.Aitmanbetov ARIS-IDA-AF-VIP-3-CW-23-3 4 / Replacement of roof, ove Request for Quot Pending Im Request for Quot Single Stage - One 2023-12-3 rhaul of sanitary units and s IDA / 67820 Village Investments Post Open - National ations (Non Bank 41,000.00 0.00 plementatio 2023-05-30 2023-07-04 ations Envelope 1 ewage system of the kinder -SPD) n garten named after B.Sagyn dykov ARIS-IDA-AF-VIP-3-CW-23-3 5 / Overhaul of sanitary facil Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 ities in the secondary school IDA / 67820 Village Investments Post Open - National ations (Non Bank 49,500.00 0.00 plementatio 2023-06-10 2023-08-05 ations Envelope 1 of the village of Kara-Bulak, -SPD) n Kara-Bulak AA, Kemin distric t, Chui region ARIS-IDA-AF-VIP-3-CW-23-3 6 / Improving the sanitary a nd hygienic condition of the Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 school canteen of the Tabal IDA / 67820 Village Investments Post Open - National ations (Non Bank 53,200.00 0.00 plementatio 2023-06-10 2023-08-05 ations Envelope 1 dinovskaya secondary schoo -SPD) n l in the village of Kara-Jygac h, Kara-Jygach AA, Alamudu n district, Chui region ARIS-IDA-AF-VIP-3-CW-23-3 7 / Replacement of electric h Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 eaters in Baitik uulu, Kanaev IDA / 67820 Village Investments Post Open - National ations (Non Bank 33,750.00 0.00 plementatio 2023-06-10 2023-08-05 ations Envelope 1 secondary school in the villa -SPD) n ge of Oktyabrsky AA, Alamu dun district, Chui region ARIS-IDA-AF-VIP-3-CW-23-3 Request for Quot Pending Im 8 / Construction of a FAP in t Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 76,200.00 0.00 plementatio 2023-06-12 2023-08-07 he village of Zelenoye, Zhan ations Envelope 3 -SPD) n y-Zhersky AA, Sokuluk distri ct, Chui region ARIS-IDA-AF-VIP-3-CW-23-3 Request for Quot Pending Im 9 / Construction of a FAP in t Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 34,100.00 0.00 plementatio 2023-06-12 2023-08-07 he village of Saz, Sazski AA, ations Envelope 3 -SPD) n Sokuluk district, Chui region ARIS-IDA-AF-VIP-3-CW-23-4 Request for Quot Pending Im 0 / Construction of a FAP in t Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 30,000.00 0.00 plementatio 2023-06-12 2023-08-07 he village of Saz, Sazski AA, ations Envelope 3 -SPD) n Sokuluk district, Chui region ARIS-IDA-AF-VIP-3-CW-23-4 1 / Improving energy efficie Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 ncy (insulation of external w IDA / 67820 Village Investments Post Open - National ations (Non Bank 38,850.00 0.00 plementatio 2023-06-12 2023-08-07 ations Envelope 3 alls) of the school of Yu. Tu -SPD) n manov, Ak-Bulun AA, Ak-Suu district, Issyk-Kul region ARIS-IDA-AF-VIP-3-CW-23-4 2 / Redevelopment of the pr Request for Quot Pending Im emises of the social instituti Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 40,500.00 0.00 plementatio 2023-06-12 2023-08-07 on "Nauka" for a dental offic ations Envelope 3 -SPD) n e with the purchase of equip ment from AA Orgochor Jeti- Oguz district of Issyk-Kul reg ion ARIS-IDA-AF-VIP-3-CW-23-4 3 / Improvement of the sanit ary and hygienic condition (r Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 epair of bathrooms) in the s IDA / 67820 Village Investments Post Open - National ations (Non Bank 49,100.00 0.00 plementatio 2023-06-12 2023-08-07 ations Envelope 3 chool named after K. Orozov -SPD) n in the village of Korumdu, K um-Bel AA, Issyk-Kul district, Issyk-Kul region ARIS-IDA-AF-VIP-3-CW-23-4 4 / Improving energy efficie Request for Quot Pending Im ncy (insulation of external w Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 45,900.00 0.00 plementatio 2023-06-12 2023-08-07 alls) of a school in the villag ations Envelope 3 -SPD) n e of Chon-Oruktu, Orukta AA , Issyk-Kul district, Issyk-Kul region ARIS-IDA-AF-VIP-3-CW-23-4 5 / Improving sanitary and h Request for Quot Pending Im ygienic conditions (renovati Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 20,650.00 0.00 plementatio 2023-06-12 2023-08-07 on of sanitary facilities) in O ations Envelope 3 -SPD) n rto-Oruktu school, Orukta A A, Issyk-Kul district, Issyk-Ku l region ARIS-IDA-AF-VIP-3-CW-23-4 6 / Improving energy efficie ncy (insulation of external w Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 alls and roofs) of the school IDA / 67820 Village Investments Post Open - National ations (Non Bank 22,800.00 0.00 plementatio 2023-06-12 2023-08-07 ations Envelope 3 cafeteria in the school of E. -SPD) n Kerimkaziev in the village of Temir, Temirovsky AA, Issyk -Kul district, Issyk-Kul region ARIS-IDA-AF-VIP-3-CW-23-4 7 / Improvement of energy e Request for Quot Pending Im fficiency (installation of wind Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 52,200.00 0.00 plementatio 2023-06-12 2023-08-07 ows) at the K. Kudaiberdiev ations Envelope 3 -SPD) n school in Kashat village, Te mirovsky AA, Issyk-Kul distri ct, Issyk-Kul region ARIS-IDA-AF-VIP-3-CW-23-4 8 / Improving energy efficie Request for Quot Pending Im ncy (insulation of external w Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 37,400.00 0.00 plementatio 2023-06-12 2023-08-07 alls and roofs) of a building i ations Envelope 3 -SPD) n n the village. Ak-Bulak Ak-B ulak AA Tyup district Issyk-K ul region ARIS-IDA-AF-VIP-3-CW-23-4 9 / Improvement of sanitary Request for Quot Pending Im facilities in the secondary sc Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 36,400.00 0.00 plementatio 2023-06-12 2023-08-07 hool. A. Koichumanova of Ak ations Envelope 3 -SPD) n -Moyun village, Ak-Moyun A A, At-Bashyn district, Naryn region ARIS-IDA-AF-VIP-3-CW-23-5 Request for Bids Pending Im 0 / Repair of a kindergarten i Single Stage - One - Small Works SP 2024-01-3 IDA / D7270 Village Investments Post Request for Bids Open - National 144,870.00 0.00 plementatio 2023-06-07 2023-06-08 2023-06-29 2023-07-29 2023-08-04 n the village of Chaek, Chae Envelope D (1 envelope pr 1 n k AA, Jumgal district, Naryn r ocess) egion ARIS-IDA-AF-VIP-3-CW-23-5 1 / Replacement of the heati Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 ng system and the roof of th IDA / 67820 Village Investments Post Open - National ations (Non Bank 32,650.00 0.00 plementatio 2023-06-12 2023-08-07 ations Envelope 3 e school of Son-Kul AA, Koch -SPD) n kor district, Naryn region ARIS-IDA-AF-VIP-3-CW-23-5 Request for Quot Pending Im 2 / Replacement of windows Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 31,500.00 0.00 plementatio 2023-06-12 2023-08-07 in the school of the village o ations Envelope 3 -SPD) n f Cholpon, Cholpon AA, Koch kor district, Naryn region Page 4 ARIS-IDA-AF-VIP-3-CW-23-5 3 / Repair of the heating sys Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 tem of the 2nd building of th IDA / 67820 Village Investments Post Open - National ations (Non Bank 26,200.00 0.00 plementatio 2023-06-12 2023-08-07 ations Envelope 3 e school in the village of Epk -SPD) n in, Cholpon AA, Kochkor dist rict, Naryn region ARIS-IDA-AF-VIP-3-CW-23-5 4 / Replacing windows and i Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 nstalling a bathroom in a se IDA / 67820 Village Investments Post Open - National ations (Non Bank 52,300.00 0.00 plementatio 2023-06-12 2023-08-07 ations Envelope 3 condary school with. March -SPD) n 8, Ak-Kuduk AA, Naryn distri ct, Naryn region ARIS-IDA-AF-VIP-3-CW-23-5 Request for Quot Pending Im 5 / Construction of a FAP in t Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 66,400.00 0.00 plementatio 2023-06-12 2023-08-07 he village of Echki-Bashi, On ations Envelope 3 -SPD) n -Archinskiy AA, Naryn distric t, Naryn region ARIS-IDA-AF-VIP-3-CW-23-5 6 / Repair of the kindergarte Request for Quot Pending Im n Chon-Alysh (replacement Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 91,500.00 0.00 plementatio 2023-06-12 2023-08-07 of internal lighting, replace ations Envelope 3 -SPD) n ment of floors, interior decor ation of classrooms) of Baka i-Ata AA, Bakai-Ata district, Talas region ARIS-IDA-AF-VIP-3-CW-23-5 7 / Repair of the building of t Request for Quot Pending Im he secondary school named Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 53,400.00 0.00 plementatio 2023-06-12 2023-08-07 after D. Duishebaev for prim ations Envelope 3 -SPD) n ary classes of Boo-Terek AA, Bakai-Ata district, Talas regi on ARIS-IDA-AF-VIP-3-CW-23-5 8 / Construction of an exten Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 sion to the kindergarten "Ar IDA / 67820 Village Investments Post Open - National ations (Non Bank 56,800.00 0.00 plementatio 2023-06-12 2023-08-07 ations Envelope 3 cha-Beshik" in the village of -SPD) n Archagul, Shekersky AA, Kar a-Buura district, Talas regio n ARIS-IDA-AF-VIP-3-CW-23-5 9 / Replacement of windows, Request for Quot Pending Im installation of internal lightin Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 41,500.00 0.00 plementatio 2023-06-12 2023-08-07 g and repair of the heating s ations Envelope 3 -SPD) n ystem in the kindergarten N ariste AA Kyrgyzstan, Manas district, Talas region ARIS-IDA-AF-VIP-3-CW-23-6 Request for Quot Pending Im 0 / Repair of the FAP in the v Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 15,100.00 0.00 plementatio 2023-06-12 2023-08-07 illage of Zhyyde, Uch-Korgo ations Envelope 3 -SPD) n n AA, Manas district, Talas r egion ARIS-IDA-AF-VIP-3-CW-23-6 1 / Construction of a buildin Request for Quot Pending Im Request for Quot Single Stage - One 2024-01-3 g for a FDC (Family Doctors IDA / 67820 Village Investments Post Open - National ations (Non Bank 67,000.00 0.00 plementatio 2023-07-01 2023-08-03 ations Envelope 0 Center) in the Kaynazarova -SPD) n village, Kainazarov AA, Socu luc district, Chui oblast ARIS-IDA-AF-VIP-3-CW-23-6 2 / Renovation of indoor sani Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 tary facilities of secondary s IDA / 67820 Village Investments Post Open - National ations (Non Bank 37,000.00 0.00 plementatio 2023-07-05 2023-08-07 ations Envelope 3 chool in Internatsionalnoye -SPD) n village, Internatsionalny AA, Issyk-Ata district, Chui oblas t ARIS-IDA-AF-VIP-3-CW-23-6 Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-2 3 / Construction of FAP in th IDA / 67820 Village Investments Post Open - National ations (Non Bank 65,000.00 0.00 plementatio 2023-07-05 2023-08-26 ations Envelope 2 e Telman village Issyk-Ata di -SPD) n strict Chui oblast ARIS-IDA-AF-VIP-3-CW-23-6 Request for Quot Pending Im 4 / Construction of FAP in th Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 64,700.00 0.00 plementatio 2023-07-05 2023-08-07 e Jany-Turmush village Iskri ations Envelope 3 -SPD) n nski AA Chui district Chui obl ast ARIS-IDA-AF-VIP-3-CW-23-6 Request for Quot Pending Im 5 / Renovation of a kinderga Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 34,000.00 0.00 plementatio 2023-07-05 2023-08-07 rten in the Kirov village of K ations Envelope 3 -SPD) n urpuldek AA Panfilocski distr ict Chui oblast ARIS-IDA-AF-VIP-3-CW-23-6 6 / Installation of sanitary fa Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 cilities of the secondary sch IDA / 67820 Village Investments Post Open - National ations (Non Bank 25,300.00 0.00 plementatio 2023-07-05 2023-08-07 ations Envelope 3 ool in the Kyzyl-Oy village S -SPD) n uusamyr AA, Zhaiyl district Chui oblast ARIS-IDA-AF-VIP-3-CW-23-6 7 / Repair of sanitary units o Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 f a secondary school in the IDA / 67820 Village Investments Post Open - National ations (Non Bank 6,800.00 0.00 plementatio 2023-07-05 2023-08-07 ations Envelope 3 Madaniyat village Onbir-Zhyl -SPD) n ga AA, Chui district Chyi obl ast ARIS-IDA-AF-VIP-3-CW-23-6 8 / Establishing a medical ro Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 om for medical staff at the s IDA / 67820 Village Investments Post Open - National ations (Non Bank 3,500.00 0.00 plementatio 2023-07-05 2023-08-07 ations Envelope 3 econdary school in the Kayir -SPD) n ma village, Chui district Chui oblast ARIS-IDA-AF-VIP-3-CW-23-6 Request for Quot Pending Im 9 / Repair of FAP in the Vino Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 33,000.00 0.00 plementatio 2023-07-05 2023-08-07 gradnoye village of Saylyk A ations Envelope 3 -SPD) n A Chui district Chui oblast ARIS-IDA-AF-VIP-3-CW-23-7 Request for Quot Pending Im 0 / Repair of sanitary units o Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 5,000.00 0.00 plementatio 2023-07-05 2023-08-07 f kindergarten in the Saylyk ations Envelope 3 -SPD) n village of Saylyk AA Chui dis trict Chui oblast ARIS-IDA-AF-VIP-3-CW-23-7 Request for Quot Pending Im 1 / Heating system of FAP in Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 6,800.00 0.00 plementatio 2023-07-05 2023-08-07 the Saylyk village of Saylyk ations Envelope 3 -SPD) n AA Chui district Chui oblast ARIS-IDA-AF-VIP-3-CW-23-7 Request for Quot Pending Im 2 / Construction of a FAP in I Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 35,000.00 0.00 plementatio 2023-07-05 2023-08-07 chke Zhergez village of Boz ations Envelope 3 -SPD) n unchuk AA, Ak-suu district, I ssyk-kul oblast ARIS-IDA-AF-VIP-3-CW-23-7 3 / Installation of a septic ta nk in the kindergarten and r Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 ehabilitation of the school w IDA / 67820 Village Investments Post Open - National ations (Non Bank 20,300.00 0.00 plementatio 2023-07-05 2023-08-07 ations Envelope 3 ater supply system in the Zh -SPD) n arkynbaevo village of Abdyr ahman AA, Issyk-Kul district Issyk-kul oblast Page 5 ARIS-IDA-AF-VIP-3-CW-23-7 4 / Improving sanitary and h ygiene conditions (partial re Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 placement of sanitary equip IDA / 67820 Village Investments Post Open - National ations (Non Bank 17,700.00 0.00 plementatio 2023-07-05 2023-08-07 ations Envelope 3 ment in the sanitary units a -SPD) n nd kitchen) of the kindergart en in the Ton village of Ton AA, Ton district, Issyk-kul ob last ARIS-IDA-AF-VIP-3-CW-23-7 Request for Quot Pending Im 5 / Warming the school in th Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 38,000.00 0.00 plementatio 2023-07-05 2023-08-07 e Shor-Bulak village, Ulakol ations Envelope 3 -SPD) n AA, Ton district, Issyk-kul ob last ARIS-IDA-AF-VIP-3-CW-23-7 6 / Improvement of energy e Request for Quot Pending Im fficiency (installation of exte Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 12,000.00 0.00 plementatio 2023-07-05 2023-08-11 rior doors and a vestibule) o ations Envelope 7 -SPD) n f the school in the Tuura-Su u-2 village, Ton district, Issy k-kul oblast ARIS-IDA-AF-VIP-3-CW-23-7 7 / Improving energy efficie Request for Quot Pending Im ncy (installation of electrical Request for Quot Single Stage - One 2024-02-2 IDA / 67820 Village Investments Post Open - National ations (Non Bank 32,300.00 0.00 plementatio 2023-07-05 2023-08-26 convectors) in the school in ations Envelope 2 -SPD) n the Ak-Olon village of Kok- Moinok AA, Ton district, Issy k-kul oblast ARIS-IDA-AF-VIP-3-CW-23-7 Request for Quot Pending Im 8 / Construction of FAP in th Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 54,000.00 0.00 plementatio 2023-07-05 2023-08-07 e Santash 3 ferma village of ations Envelope 3 -SPD) n San-Tash AA, Tyup district, I ssyk-kul oblast ARIS-IDA-AF-VIP-3-CW-23-7 Request for Quot Pending Im 9 / Renovation of FAP in the Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 20,000.00 0.00 plementatio 2023-07-05 2023-08-07 Ara-Kol village of Cholpon A ations Envelope 3 -SPD) n A, Kochkor district, Naryn ob last ARIS-IDA-AF-VIP-3-CW-23-8 Request for Quot Pending Im 0 / Construction of a FAP in t Request for Quot Single Stage - One 2024-02-2 IDA / 67820 Village Investments Post Open - National ations (Non Bank 73,000.00 0.00 plementatio 2023-07-05 2023-08-26 he Kyzyl-Charba village of A ations Envelope 2 -SPD) n k-Dobo AA, Bakai-Ata distric t, Talas oblast ARIS-IDA-AF-VIP-3-CW-23-8 1 / Installation of ventilation Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 system in theM.Chaldanbae IDA / 67820 Village Investments Post Open - National ations (Non Bank 20,300.00 0.00 plementatio 2023-07-05 2023-08-07 ations Envelope 3 v secondary school, Bakayir -SPD) n AA, Kara-Buura district, Tala s oblast ARIS-IDA-AF-VIP-3-CW-23-8 Request for Quot Pending Im 2 / Construction of a FAP in t Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 34,700.00 0.00 plementatio 2023-07-05 2023-08-07 he Sogot village, Pokrovka A ations Envelope 3 -SPD) n A, Manas district, Talas obla st ARIS-IDA-AF-VIP-3-CW-23-8 3 / Redesigning the school b Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 uilding for a kindergarten for IDA / 67820 Village Investments Post Open - National ations (Non Bank 53,400.00 0.00 plementatio 2023-07-05 2023-08-07 ations Envelope 3 50 children in the Aral villag -SPD) n e of Aral AA, Talas district,T alas oblast ARIS-IDA-AF-VIP-3-CW-23-8 Request for Quot Pending Im 4 / Construction of a FAP in t Request for Quot Single Stage - One 2024-02-0 IDA / 67820 Village Investments Post Open - National ations (Non Bank 52,000.00 0.00 plementatio 2023-07-05 2023-08-07 he Ak-Zhar village of Talas d ations Envelope 3 -SPD) n istrict, Talas oblast ARIS-IDA-AF-VIP-3-CW-23-8 5 / Construction of an additi Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 onal building for FAP in the IDA / 67820 Village Investments Post Open - National ations (Non Bank 47,200.00 0.00 plementatio 2023-07-05 2023-08-07 ations Envelope 3 Kara-Suu village of Kara-Suu -SPD) n AA, Talas district, Talas obla st ARIS-IDA-AF-VIP-3-CW-23-8 6 / Construction of an additi Request for Quot Pending Im Request for Quot Single Stage - One 2024-02-0 onal building for 25 children IDA / 67820 Village Investments Post Open - National ations (Non Bank 53,400.00 0.00 plementatio 2023-07-05 2023-08-07 ations Envelope 3 for the kindergarten named -SPD) n after A. Eshalieva of Omurali ev AA, Talas district, Talas o blast IDA-VIP3-HO-CW-16-05 / Co Capacity Building of Local S nstruction of a kindergarten Single Stage - One IDA / 56010 elf-Governments and Comm Prior Request for Bids Open - National 0.00 347,529.04 Signed 2016-10-03 2016-09-30 2016-10-19 2016-10-20 for 100 places in Tosor v., T Envelope unities amga AO, Jeti-Oguz Raion, Is syk-Kul Region GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-VIP3-HO-GOODS-SH-20- Request for Quot Single Stage - One 3 / personal protective equip IDA / D0410 Village Investments Post Limited 99,800.00 88,621.41 Signed 2020-04-24 2020-05-06 2020-05-08 2020-05-19 2020-05-29 2020-05-21 ations Envelope ment for work in the centers of COVID-19 IDA-VIP3-HO-EQ-NCB-20-7 / Purchase of special equipme Single Stage - One IDA / 56010 Village Investments Post Request for Bids Open - National 91,304.00 117,736.29 Signed 2020-11-05 2020-11-06 2020-11-05 2020-11-06 2020-11-26 2020-11-27 2020-12-17 2020-12-09 2021-01-17 2020-12-29 2021-05-17 nt for the removal of SHW T Envelope uz AA, Chui oblast IDA-VIP3-HO-EQ-NCB-20-8 / Purchase of special equipme Single Stage - One IDA / 56010 Village Investments Post Request for Bids Open - National 87,296.00 72,307.85 Signed 2020-11-05 2020-11-06 2020-11-05 2020-11-06 2020-11-26 2020-11-27 2020-12-17 2020-12-10 2021-01-17 2020-12-29 2021-05-17 nt for loading and transporti Envelope ng goods Nurjanov AA, Talas oblast IDA-VIP3-HO-EQ-NCB-20-9 / Purchase of electrical equip Single Stage - One IDA / 56010 Village Investments Post Request for Bids Open - National 68,500.00 0.00 Canceled 2020-11-04 2020-11-27 2020-11-04 2020-11-25 2020-12-18 2020-12-16 2020-12-29 2021-01-16 2021-03-17 ment for the reconstruction Envelope of VL-6-0,4 kV Kabak AA, Na ryn oblast IDA-VIP3-HO-EQ-NCB-20-9/ RT1 / Purchase of electrical Single Stage - One IDA / 56010 Village Investments Post Request for Bids Open - National 68,500.00 0.00 Canceled 2021-01-18 2021-01-20 2021-02-10 2021-03-12 2021-04-14 2021-06-13 equipment for the reconstru Envelope ction of VL-6-0,4 kV Kabak A A, Naryn oblast IDA-VIP3-GOODS-SH-22-1 / Request for Quot Single Stage - One Purhase of Firnitures for sch IDA / 56010 Village Investments Post Open - National 80,000.00 78,720.96 Signed 2022-03-03 2022-04-03 2022-04-21 2022-06-02 ations Envelope ool and kindergartens of 12 AA IDA-VIP3-GOODS-SH-22-2 / Request for Quot Single Stage - One Purhase of Office equipment IDA / 56010 Village Investments Post Open - National 80,500.00 88,409.65 Signed 2022-02-26 2022-03-29 2022-04-20 2022-05-28 ations Envelope for school and kindergartens of 12 AA IDA-VIP3-GOODS-SH-22-3 / Request for Quot Single Stage - One Purhase of kitchen equipme IDA / 56010 Village Investments Post Open - National 46,000.00 31,930.69 Signed 2022-02-26 2022-03-29 2022-04-20 2022-05-28 ations Envelope nt for school and kindergart ens of 12 AA Page 6 IDA-VIP3-EQ-NCB-20-9/RT2 / Purchase of electrical equi Single Stage - One IDA / 56010 Village Investments Post Request for Bids Open - National 68,500.00 84,582.00 Signed 2022-03-10 2022-02-12 2022-03-10 2022-03-31 2022-03-15 2022-04-14 2022-03-17 2022-05-13 2022-05-01 2022-06-12 pment for the reconstruction Envelope of VL-6-0,4 kV Kabak AA, Na ryn oblast IDA-VIP3-HO-GOODS-SH-22- 2 / Purchase of office equip ments and furnitures for the Request for Quot Single Stage - One IDA / 56010 Project Management Post Open - National 63,000.00 115,952.24 Signed 2022-02-18 2022-03-25 2022-04-20 2022-05-24 Project Team in the central ations Envelope office also for the Regional o ffice team and for CTSOs of all oblasts. IDA-AFVIP3-HO-GOODS-SH- Capacity Building of Local S 23-1 / Purchase of services o Request for Quot Single Stage - One IDA / 56010 elf-Governments and Comm Post Open - National 21,000.00 0.00 Canceled 2023-01-23 2023-03-12 2023-05-11 f internet provider for install ations Envelope unities ation of wi-fi hotspots for VIP -3 AF target areas IDA-AFVIP3-HO-GOODS-DS- Capacity Building of Local S 23-2 / Purchase of services o Pending Impl IDA / 56010 elf-Governments and Comm Post Direct Selection Direct - National 21,000.00 0.00 2023-03-06 2023-03-09 2023-03-15 2023-05-14 f internet provider for install ementation unities ation of wi-fi hotspots for VIP -3 AF target areas ARIS-IDA-AF-VIP-3-GOODS-2 Request for Quot Single Stage - One Pending Impl 3-1 / Purchase of special ma IDA / 67820 Village Investments Post Open - National 41,000.00 0.00 2023-05-30 2023-07-04 2023-12-31 ations Envelope ementation chinery (waste collection tru ck) ARIS-IDA-AF-VIP-3-GOODS-2 3-2 / Purchase of equipment Request for Quot Single Stage - One Pending Impl IDA / 67820 Village Investments Post Open - National 33,000.00 0.00 2023-05-30 2023-07-25 2024-01-21 and furniture for the FAP in ations Envelope ementation Kazhy-Saz and Ton villages ARIS-IDA-AF-VIP-3-GOODS-2 3-3 / Purchase of equipment Request for Quot Single Stage - One Pending Impl IDA / 67820 Village Investments Post Open - National 33,000.00 0.00 2023-05-30 2023-07-04 2023-12-31 for the kitchen of Nur Zheles ations Envelope ementation i kindergarten Kuugandy a/a Talas district ARIS-IDA-AF-VIP-3-GOODS-2 3-4 / Purchase of equipment Request for Quot Single Stage - One Pending Impl IDA / 67820 Village Investments Post Open - National 4,900.00 0.00 2023-07-05 2023-08-26 2024-02-22 and furniture for the FAP in t ations Envelope ementation he Telek AA of Moscovski dis trict Chui oblast ARIS-IDA-AF-VIP-3-GOODS-2 3-5 / Purchase of equipment Request for Quot Single Stage - One Pending Impl and furniture for the FAP in t IDA / 67820 Village Investments Post Open - National 10,000.00 0.00 2023-07-05 2023-08-07 2024-02-03 ations Envelope ementation he Kara-Shaar and Ottuk vill ages of Ton AA, Ton district, Issyk-Kul oblast ARIS-IDA-AF-VIP-3-GOODS-2 3-6 / Purchase of special eq uipment for FDC (Family Do Request for Quot Single Stage - One Pending Impl IDA / 67820 Village Investments Post Open - National 22,700.00 0.00 2023-07-05 2023-08-07 2024-02-03 ctors Center) (dental office) ations Envelope ementation in the Kara-Talaa village, Ul akol AA, Ton district, Issyk-k ul oblast ARIS-IDA-AF-VIP-3-GOODS-2 3-7 / Purchase of equipment Request for Quot Single Stage - One Pending Impl and furniture for the FAP in t IDA / 67820 Village Investments Post Open - National 8,300.00 0.00 2023-07-05 2023-08-07 2024-02-03 ations Envelope ementation he Kok-Moinok-1 village of K ok-Moinok AA, Ton district, I ssyk-kul oblast NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Techni Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) t (US$) Notice equest for Proposals as Issued Proposals / Minutes cal Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-VIP3-S-CQ-20-4 / Devel opment of detailed design e stimates for the installation Consultant Qualifi IDA / D0410 Village Investments Post Open - National 15,000.00 31,208.89 Signed 2020-07-13 2020-07-14 2020-08-03 2020-09-07 2020-10-13 2020-09-14 2020-12-07 2020-09-28 2020-12-11 2020-12-27 of lighting on the streets of cation Selection Zher-Kazar, Nizhniy-Nooruz, Druzhba Villages, Issyk-Ata Raion, Chuy Oblast IDA-VIP3-S-CQ-20-5 / develo pment of detailed design est imates for the capital repair Consultant Qualifi of the drinking water sup-ply IDA / D0410 Village Investments Post Open - National 30,000.00 12,277.54 Signed 2020-07-13 2020-08-13 2020-08-03 2020-09-07 2020-09-11 2020-09-14 2020-10-28 2020-09-28 2020-10-29 2020-12-27 cation Selection system in Zhyrgalan Village, Ak-Suy Raion, Issyk-Kul Obla st and in Kadyraly Village, A k-Talaa Raion, Naryn Oblast IDA-VIP3-S-CQ-20-6 / develo pment of detailed design est imates for the capital repair Consultant Qualifi IDA / D0410 Village Investments Post Open - National 15,000.00 12,026.61 Signed 2020-07-13 2020-08-17 2020-08-03 2020-09-07 2020-10-15 2020-09-14 2020-11-16 2020-09-28 2020-12-08 2020-12-27 of the building of the Alen-k cation Selection a kindergarten in the village of Predtechenka, Moskovski y Raion, Chuy Oblast IDA-VIP3-V-CQ-2020-16 / Pr Capacity Building of Local S Consultant Qualifi IDA / D0410 Post Open - National 2,000.00 3,713.63 Signed 2020-08-18 2020-10-26 2020-09-08 2020-10-13 2020-10-23 2020-10-18 2020-11-17 2020-10-28 2020-12-08 2021-01-26 eparing Audio and Video Les elf-Governments and Comm cation Selection sons unities IDA-VIP-S-CQ-20-7 / develop ment of detailed design esti mates for the construction o Consultant Qualifi IDA / D0410 Village Investments Post Open - National 15,000.00 0.00 Canceled 2020-07-24 2020-08-07 2020-09-13 2020-09-16 2020-09-18 2020-12-17 f the building for the GFD (G cation Selection roup of Family Doctors) in A k-Dobo Village, Bakai-Ata Ra ion, Talas Oblast IDA-VIP3-V-CQ-2021-1 / Info Capacity Building of Local S Consultant Qualifi IDA / D0410 Post Open - National 6,000.00 13,895.36 Signed 2021-03-29 2021-04-30 2021-04-19 2021-05-17 2021-06-21 2021-05-20 2021-08-11 2021-05-26 2021-09-08 2021-08-24 rmation Compaign elf-Governments and Comm cation Selection unities IDA-VIP3-CQ-2021-2 / AF VI Capacity Building of Local S Consultant Qualifi P-3 Baseline survey and VIP IDA / D0410 elf-Governments and Comm Post Open - National 60,000.00 69,949.01 Signed 2021-05-28 2021-05-31 2021-06-11 2021-07-14 2021-07-09 2021-07-19 2021-10-14 2021-07-25 2021-12-14 2021-11-22 cation Selection -3 Impact Assessment unities ARIS-AUDIT-LCS-2021-1 / A Least Cost Selecti Open - Internation Under Implement IDA / 56010 Project Management Post 42,589.00 0.00 2021-08-10 2021-08-16 2021-08-24 2021-09-24 2021-09-21 2021-10-12 2021-10-19 2021-11-05 2021-11-26 2023-12-31 udit on al ation IDA-VIP3-CQ-2021-3 / Cond Capacity Building of Local S ucting Market and Value Ch Consultant Qualifi IDA / 56010 elf-Governments and Comm Post Open - National 60,000.00 76,672.08 Signed 2021-10-04 2021-10-05 2021-10-18 2021-11-17 2022-05-10 2021-11-22 2022-05-10 2021-12-02 2022-05-21 2022-04-01 ain Analysis research in the cation Selection unities target areas of the Project IDA-VIP-AF-CQS-2021-3 / De Capacity Building of Local S Consultant Qualifi velopment of training modul IDA / D0410 elf-Governments and Comm Post Open - National 70,000.00 0.00 Signed 2022-05-26 2022-06-14 2022-06-09 2022-06-22 2022-07-07 2022-10-12 2022-07-14 2022-11-15 2022-07-20 2022-10-18 cation Selection es and conducting training o unities f traineers Page 7 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Draft Negotiated Con Description Component Review Type Method Process Status Terms of Reference d/Selected Consultan Signed Contract Contract Completion o. h unt (US$) t (US$) tract t Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-VIP3-T-IC-2020-1 / Tech nical Supervision Engineer ( Individual Consult TSE) for subproject ‘Constru IDA / D0410 Village Investments Post Open 5,600.00 2,888.23 Signed 2020-02-26 2020-02-24 2020-04-15 2020-05-29 2020-05-06 2020-05-29 2020-06-10 2020-06-12 2020-12-07 ant Selection ction of FAP in Kyzyl-Zhyldyz village, Zhumgal region, Nar yn oblast’ IDA-VIP3-T-IC-2020-2 / Tech nical Supervision Engineer ( Individual Consult TSE) for subproject ‘Overha IDA / D0410 Village Investments Post Open 5,600.00 0.00 Canceled 2020-02-21 2020-02-18 2020-04-10 2020-05-01 2020-06-05 2020-12-02 ant Selection ul of school them. Myrzakma tova in Kozhomkul village, Z haiyl region, Chui oblast’ IDA-VIP3-T-IC-2020-3 / Tech nical Supervision Engineer ( Individual Consult TSE) for subproject ‘Overha IDA / D0410 Village Investments Post Open 5,600.00 2,888.31 Signed 2020-02-21 2020-02-18 2020-04-10 2020-05-22 2020-05-01 2020-06-04 2020-06-05 2020-06-06 2020-12-02 ant Selection ul of kindergarten in Kaldyk village, Zhaiyl region, Chui o blast’ IDA-VIP3-T-IC-2020-4 / Tech nical Supervision Engineer ( Individual Consult TSE) for subproject “Constru IDA / D0410 Village Investments Post Open 5,600.00 2,954.24 Signed 2020-03-18 2020-03-16 2020-05-06 2020-08-03 2020-05-27 2020-08-03 2020-07-01 2020-08-06 2020-12-28 ant Selection ction of a kindergarten Ken- Aral village, Bakai-Ata regio n, Talas oblast” IDA-VIP3-T-IC-2020-5 / Tech nical Supervision Engineer ( Individual Consult TSE) for subproject “Constru IDA / D0410 Village Investments Post Open 5,600.00 3,211.66 Signed 2020-03-18 2020-03-16 2020-05-06 2020-08-03 2020-05-27 2020-08-04 2020-07-01 2020-08-06 2020-12-28 ant Selection ction of a kindergarten A.Og onbaev village, Talas region, Talas oblast” IDA-VIP3-T-IC-2020-6 / Tech nical Supervision Engineer ( Individual Consult TSE) for subproject “Constru IDA / D0410 Village Investments Post Open 5,600.00 4,002.26 Signed 2020-03-18 2020-03-16 2020-05-06 2020-08-03 2020-05-27 2020-08-04 2020-07-01 2020-08-06 2020-12-28 ant Selection ction of a kindergarten for 5 0 places Zherge-Tal village, Ak-Tala region, Naryn oblast ” IDA-VIP3-T-IC-2020-7 / Tech nical Supervision Engineer ( Individual Consult TSE) for subproject “Constru IDA / D0410 Village Investments Post Open 5,600.00 4,126.04 Signed 2020-03-18 2020-03-16 2020-05-06 2020-08-03 2020-05-27 2020-08-04 2020-07-01 2020-08-06 2020-12-28 ant Selection ction of a kindergarten for 5 0 places Zher-Kechkyu villag e, Naryn region, Naryn oblas t” IDA-VIP3-T-IC-2020-8 / Tech nical Supervision Engineer ( Individual Consult TSE) for subproject “Constru IDA / D0410 Village Investments Post Open 7,100.00 4,628.29 Signed 2020-05-19 2020-05-18 2020-07-07 2020-08-03 2020-07-28 2020-08-04 2020-09-01 2020-08-06 2021-02-28 ant Selection ction of a kindergarten for 1 00 places Ak-Sai village, Ton region, Issyk-Kul oblast” IDA-VIP3-T-IC-2020-9 / Tech nical Supervision Engineer ( TSE) for subproject “Constru Individual Consult IDA / D0410 Village Investments Post Open 7,100.00 5,133.08 Signed 2020-05-19 2020-05-18 2020-07-07 2020-08-03 2020-07-28 2020-08-04 2020-09-01 2020-08-06 2021-02-28 ction of an additional buildin ant Selection g for "Zhetigen" Kindergarte n in Beryu-Bash village, Ak-S uu region, Issyk-Kul oblast” IDA-VIP3-T-IC-2020-10 / Tec hnical Supervision Engineer Individual Consult (TSE) for subproject “Constr IDA / D0410 Village Investments Post Open 5,600.00 3,201.81 Completed 2020-05-19 2020-05-18 2020-07-07 2020-08-03 2020-07-28 2020-08-04 2020-09-01 2020-08-09 2021-02-28 2021-01-11 ant Selection uction of FAP in Tamchy-Bul ak village, Kara-Buura regio n, Talas oblast” IDA-VIP3-T-IC-2020-11 / Tec hnical Supervision Engineer Individual Consult (TSE) for subproject “Constr IDA / D0410 Village Investments Post Open 5,600.00 3,460.08 Completed 2020-05-20 2020-05-18 2020-07-08 2020-08-03 2020-07-29 2020-08-04 2020-09-02 2020-08-06 2021-03-01 2021-01-01 ant Selection uction of FAP in Chon-Tash v illage, Tyup region, Issyk-Kul oblast” IDA-VIP3-T-IC-2020-12 / Tec hnical Supervision Engineer Individual Consult (TSE) for subproject “Constr IDA / D0410 Village Investments Post Open 5,600.00 4,126.04 Signed 2020-05-20 2020-05-18 2020-07-08 2020-08-03 2020-07-29 2020-08-04 2020-09-02 2020-08-06 2021-03-01 ant Selection uction of Library in Ottuk vill age, Naryn region, Naryn ob last” IDA-VIP3-T-IC-2020-13 / Tec hnical Supervision Engineer (TSE) for subproject “The de Individual Consult IDA / D0410 Village Investments Post Open 5,600.00 2,617.09 Signed 2020-06-16 2020-05-20 2020-08-04 2020-10-19 2020-08-25 2020-10-19 2020-09-29 2020-10-21 2021-03-28 vice of a sewer collector and ant Selection connection to a city network in Nijnealarcha village, Alam udun region, Chui oblast” VIP-S-CQ-20-2 / The geo-ref erencing to the area design documents (DDE), calculatio n of the estimated cost of w IDA / D0410 Village Investments Post Direct Selection Direct 5,000.00 0.00 Canceled 2020-05-22 2020-08-13 2020-05-29 2020-06-03 2020-08-02 orks and materials, and con ducting supervision of the fa cility of Construction of a ki ndergarten for 50 children in the village of Maimak, Kara- Buura Raion IDA-VIP3-IC-20-13 / Develop ment Cost Estimate for the Individual Consult IDA / D0410 Village Investments Post Open 2,000.00 869.57 Signed 2020-07-13 2020-08-18 2020-08-17 2020-10-14 2020-08-20 2020-10-14 2020-08-26 2020-10-21 2020-11-24 Capital Repair of the buildin ant Selection g of School Stravopolovka of Jaiyl Ragion, Chui Region IDA-VIP-S-DC-20-3 / The ge o-referencing to the area of deteiled design documents ( DDE), calculation of the esti IDA / D0410 Village Investments Post Direct Selection Direct 13,500.00 12,195.12 Completed 2020-07-20 2020-07-23 2020-07-27 2020-08-03 2020-08-01 2020-08-16 2020-09-30 2020-10-31 mated cost of works and ma terials, and conducting supe rvision of the facility of Con struction of a kindergarten f or 100 children in the village of Taldy-Suu,IK IDA-VIP-S-DC-20-8 / author' s supervision Construction o f an additional building for " IDA / D0410 Village Investments Post Direct Selection Direct 2,000.00 1,460.18 Signed 2020-07-24 2020-08-13 2020-08-03 2020-08-19 2020-08-07 2020-08-27 2021-03-05 Zhetigen" Kindergarten in B eryu-Bash village, Ak-Suu re gion, Issyk-Kul oblast IDA-VIP-S-DC-20-9 / Author' s supervision of Constructio IDA / D0410 Village Investments Post Direct Selection Direct 2,000.00 730.09 Signed 2020-07-24 2020-08-13 2020-08-03 2020-08-19 2020-08-06 2020-08-27 2021-01-03 n of FAP in Tamchy-Bulak vil lage, Kara-Buura region, Tal as oblast IDA-VIP-S-DC-20-10 / Author 's supervision of constructio IDA / D0410 Village Investments Post Direct Selection Direct 2,000.00 878.40 Signed 2020-07-24 2020-08-13 2020-08-03 2020-08-19 2020-08-06 2020-08-27 2021-01-03 n of a kindergarten A.Ogonb aev village, Talas region, Tal as oblast Page 8 IDA-VIP-S-DC-20-11 / Author 's supervision of constructio IDA / D0410 Village Investments Post Direct Selection Direct 2,000.00 1,169.07 Signed 2020-07-24 2020-08-13 2020-08-03 2020-08-19 2020-08-06 2020-08-27 2021-01-03 n of a kindergarten Ken-Aral village, Bakai-Ata region, Tal as oblast IDA-VIP-S-DC-20-12 / Author 's supervision of сonstructio IDA / D0410 Village Investments Post Direct Selection Direct 2,000.00 1,226.87 Signed 2020-07-24 2020-08-13 2020-07-30 2020-08-19 2020-08-07 2020-08-27 2021-01-04 n of a kindergarten Zher-Kec hkyu village, Naryn region, Naryn oblast IDA-VIP-S-DC-20-13 / Author 's supervision of Constructio IDA / D0410 Village Investments Post Direct Selection Direct 2,000.00 1,746.01 Signed 2020-07-24 2020-08-13 2020-07-30 2020-08-19 2020-08-07 2020-08-27 2021-01-04 n of a kindergarten Zherge- Tal village, Ak-Tala region, N aryn oblast IDA-VIP-S-DC-20-14 / Author 's supervision of Constructio IDA / D0410 Village Investments Post Direct Selection Direct 1,322.00 1,155.89 Signed 2020-07-24 2020-08-13 2020-07-30 2020-08-19 2020-08-07 2020-08-28 2021-03-05 n of a kindergarten Ak-Sai vi llage, Ton region, Issyk-Kul o blast IDA-VIP-S-DC-20-15 / Author 's supervision of Constructio IDA / D0410 Village Investments Post Direct Selection Direct 2,000.00 1,469.34 Signed 2020-07-24 2020-08-13 2020-07-30 2020-08-19 2020-08-07 2020-08-28 2021-01-04 n of FAP in Chon-Tash villag e, Tyup region, Issyk-Kul obl ast IDA-VIP-S-DC-20-16 / Author 's supervision of Constructio IDA / D0410 Village Investments Post Direct Selection Direct 2,000.00 1,130.53 Signed 2020-07-24 2020-08-13 2020-07-30 2020-08-19 2020-08-07 2020-08-28 2021-01-04 n of Library in Ottuk village, Naryn region, Naryn oblast IDA-VIP-S-DC-20-1 / The ge o-referencing to the area of deteiled design documents ( DDE), calculation of the esti IDA / D0410 Village Investments Post Direct Selection Direct 5,500.00 4,728.87 Completed 2020-08-03 2020-08-13 2020-08-09 2020-08-24 2020-08-12 2020-08-27 2020-11-10 2020-11-27 mated cost of works and ma terials, and conducting supe rvision of the facility of Cons truction of a kindergarten fo r 50 children in the village of Dobolu, Naryn Raio IDA-VIP-S-DC-20-2 / The ge o-referencing to the area de sign documents (DDE), calc ulation of the estimated cost IDA / D0410 Village Investments Post Direct Selection Direct 5,500.00 4,728.87 Completed 2020-08-17 2020-08-24 2020-08-27 2020-08-24 2020-09-05 2020-08-27 2020-12-04 2020-11-27 of works and materials, and conducting supervision of th e facility of Construction of a kindergarten for 50 children in the village of Maimak, Kar a-Buura Raion IDA-VIP3-T-IC-2020-14 / Tec hnical supervision consultan Capacity Building of Local S t for sub projects of the cons Individual Consult IDA / D0410 elf-Governments and Comm Post Open 6,000.00 2,744.40 Signed 2020-10-21 2020-10-22 2020-11-12 2020-11-20 2020-11-13 2020-12-07 2020-11-17 2021-01-05 2021-07-15 truction of building for a gro ant Selection unities up of family doctors (FGP) in the village Ak-Dobo Talas ob last(3 cycle) IDA-VIP-S-DC-20-17 / Author 's supervision of the constru ction drainage collector and IDA / D0410 Village Investments Post Direct Selection Direct 2,500.00 2,563.50 Signed 2020-10-25 2020-11-13 2020-10-27 2020-10-26 2020-10-30 2021-01-07 2021-03-29 conection Bishkek City net i n the Chui oblast, Alamudun rajion, Nijnee Ala-Archa IDA-VIP-S-DC-20-18 / The g eo-referencing to the area o f deteiled design documents (DDE), calculation of the esti IDA / D0410 Village Investments Post Direct Selection Direct 18,115.00 14,246.62 Signed 2020-11-04 2020-11-04 2020-11-09 2020-11-05 2020-11-13 2020-12-10 2021-02-26 mated cost of works and ma terials, and conducting supe rvision of the facility of Cons truction of feldsher-obstetric station (FAP) in the villages. IDA-VIP3-T-IC-2020-15 / Tec hnical supervision consultan Individual Consult t for sub projects of the cons IDA / D0410 Village Investments Post Open 5,294.00 0.00 Canceled 2020-11-19 2020-11-20 2020-12-19 2020-12-22 2020-12-27 2021-09-23 ant Selection truction of Kindergarten for 100 places in the village Tal du-Suu Issyk-Kul (3 cycle) IDA-VIP3-T-IC-2020-16 / Tec hnical supervision consultan t for sub project of the сonst Individual Consult IDA / D0410 Village Investments Post Open 5,294.00 4,265.14 Signed 2020-12-16 2021-02-04 2021-01-14 2021-02-25 2021-01-15 2021-02-26 2021-01-21 2021-03-02 2021-10-18 ruction of kindergarten for 5 ant Selection 0 places in the Dobolu villag e, Naryn Ragion, Naryn obla st (3 cycle) IDA-VIP3-T-IC-2020-17 / Tec hnical supervision consultan t for sub project of the const Individual Consult IDA / D0410 Village Investments Post Open 5,294.00 0.00 Canceled 2020-12-16 2021-02-04 2021-01-01 2021-01-02 2021-01-21 2021-10-18 ruction of kindergarten for 5 ant Selection 0 places in the Maymak villa ge, Kara-Bura Ragion, Talas oblas (3 cycle) IDA-VIP3-IC-2020-18 / Selec tion of a consultant for the d evelopment of design estim Individual Consult ates for: IDA / D0410 Village Investments Post Open 1,647.00 0.00 Canceled 2020-12-16 2020-12-14 2021-01-14 2021-01-15 2021-01-21 2021-02-20 ant Selection "Repair of FAP, purchase of i nventory and equipment" in the village. Zhar-Bashy, Inte rnational AO, Issyk-Ata rayo n, Chui oblast " IDA-VIP3-T-IC-2020-18 / Tec hnical supervision consultan Individual Consult t for sub project of the Repai IDA / D0410 Village Investments Post Open 2,994.00 3,271.67 Signed 2021-01-06 2021-01-24 2021-02-08 2021-03-15 2021-02-08 2021-03-15 2021-02-13 2021-03-24 2021-09-11 ant Selection ring of school in the village Stavropolovka, Zhayil rayon, Chui oblast (3 cycle) IDA-VIP3-IC-2020-17 / Infras Capacity Building of Local S Individual Consult IDA / D0410 Post Open 5,835.00 0.00 Canceled 2020-11-19 2020-11-25 2020-12-20 2020-12-23 2020-12-25 2021-08-22 tructure Engineer elf-Governments and Comm ant Selection unities IDA-VIP3-T-IC-2021-1 / Tech nical supervision consultant Individual Consult for sub project of the Repairi IDA / D0410 Village Investments Post Open 2,948.00 3,361.79 Signed 2021-03-02 2021-03-04 2021-03-31 2021-05-13 2021-04-01 2021-05-13 2021-04-03 2021-05-15 2021-09-30 ant Selection ng water sistem in the Kadyr aly village Ak-Tala raijion Na ryn oblast IDA-VIP-S-DC-21-1 / Author' s supervision of the construc tion kindergarten for 50 plac IDA / D0410 Village Investments Post Direct Selection Direct 2,500.00 1,031.56 Signed 2021-03-03 2021-03-03 2021-03-18 2021-03-17 2021-03-21 2021-03-18 2021-10-17 es in the Maymak village Ka ra-Bura Rajion Talas oblast IDA-VIP-S-DC-21-2 / Author' s supervision of the construc IDA / D0410 Village Investments Post Direct Selection Direct 2,500.00 990.29 Signed 2021-03-03 2021-03-10 2021-03-18 2021-03-09 2021-03-21 2021-03-18 2021-10-17 tion kindergarten for 50 plac es in the Dobolu village Nar yn Rajion Naryn oblast IDA-VIP-S-DC-21-3 / Author' s supervision of the construc tion kindergarten for 100 pla IDA / D0410 Village Investments Post Direct Selection Direct 2,500.00 1,325.99 Signed 2021-03-03 2021-03-05 2021-03-18 2021-03-12 2021-03-21 2021-03-16 2021-10-17 ces in the Taldy-Suu village Tup Rajion Issyk-Kul oblast Page 9 IDA-VIP-S-DC-21-4 / Author' s supervision of Capital Rep IDA / D0410 Village Investments Post Direct Selection Direct 2,500.00 0.00 Canceled 2021-03-12 2021-03-18 2021-03-17 2021-03-20 2021-08-17 air Water System in the villa ge Kadyraly Naryn oblast (3 Cicle) IDA-VIP3-IC-2021-1 / Buisin Capacity Building of Local S Individual Consult IDA / D0410 Post Open 3,300.00 0.00 Canceled 2021-03-12 2021-04-12 2021-04-15 2021-04-24 2021-08-22 ess Planning Trainer elf-Governments and Comm ant Selection unities IDA-VIP3-IC-TR-2021-2 / Bus Capacity Building of Local S Individual Consult iness Planning and Financial IDA / D0410 elf-Governments and Comm Post Open 700.00 1,178.75 Signed 2021-03-29 2021-04-02 2021-04-29 2021-06-21 2021-04-30 2021-08-02 2021-05-02 2021-08-14 2021-08-30 ant Selection Literacy Trainer in the Naryn unities oblast IDA-VIP3-IC-TR-2021-3 / Bus Capacity Building of Local S Individual Consult iness Planning and Financial IDA / D0410 elf-Governments and Comm Post Open 700.00 1,178.75 Signed 2021-03-29 2021-04-02 2021-04-27 2021-06-21 2021-04-28 2021-06-21 2021-04-30 2021-08-14 2021-08-28 ant Selection Literacy Trainer in the Talas unities oblast IDA-VIP3-IC-TR-2021-4 / Bus Capacity Building of Local S Individual Consult iness Planning and Financial IDA / D0410 elf-Governments and Comm Post Open 700.00 1,178.75 Signed 2021-03-29 2021-04-02 2021-04-27 2021-06-21 2021-04-28 2021-08-02 2021-04-30 2021-08-14 2021-08-28 ant Selection Literacy Trainer in the Issyk- unities Kul oblast IDA-VIP3-IC-TR-2021-5 / Bus Capacity Building of Local S Individual Consult iness Planning and Financial IDA / D0410 elf-Governments and Comm Post Open 700.00 1,178.75 Signed 2021-03-29 2021-04-02 2021-04-27 2021-06-21 2021-04-28 2021-08-02 2021-04-30 2021-08-14 2021-08-28 ant Selection Literacy Trainer in the Chui unities oblst (1) IDA-VIP3-IC-TR-2021-6 / Bus Capacity Building of Local S Individual Consult iness Planning and Financial IDA / D0410 elf-Governments and Comm Post Open 700.00 1,178.75 Signed 2021-03-29 2021-04-02 2021-04-27 2021-06-21 2021-04-28 2021-08-02 2021-04-30 2021-08-14 2021-08-28 ant Selection Literacy Trainer in the Chui unities oblst (2) IDA-VIP3-IC-2021-2 / Senior Capacity Building of Local S Individual Consult Economist (Local Markets an IDA / D0410 elf-Governments and Comm Post Open 4,400.00 8,414.76 Signed 2021-03-31 2021-03-30 2021-04-30 2021-04-28 2021-05-02 2021-04-30 2021-05-07 2021-05-02 2021-11-03 ant Selection d Buisiness Expert) unities IDA-VIP3-IC-2021-3 / Consul Capacity Building of Local S tant for the development of IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 4,000.00 5,212.56 Signed 2021-03-31 2021-04-15 2021-04-03 2021-04-16 2021-04-12 2021-04-20 2021-07-11 Project Operational Manual f unities or VIP-3 AF IDA-VIP3-IC-SSS-TR-2021-7 Capacity Building of Local S / Trainer for basic trainings IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-24 2021-04-30 2021-05-25 2021-07-29 of Operational Manual of Pr unities oject in the Naryn oblast (1) IDA-VIP3-IC-SSS-TR-2021-8 Capacity Building of Local S / Trainer for basic trainings IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-08-23 2021-04-30 2021-05-25 2021-07-29 of Operational Manual of Pr unities oject in the Chui oblast (1) IDA-VIP3-IC-SSS-TR-2021-9 Capacity Building of Local S / Trainer for basic trainings IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-23 2021-04-30 2021-05-25 2021-07-29 of Operational Manual of Pr unities oject in the Chui oblast (2) IDA-VIP3-IC-SSS-TR-2021-1 Capacity Building of Local S 0 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.31 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Chui oblast (3) IDA-VIP3-IC-SSS-TR-2021-1 Capacity Building of Local S 1 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.31 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Issyk-Kul oblast (1) IDA-VIP3-IC-SSS-TR-2021-1 Capacity Building of Local S 2 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.31 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Naryn oblast (2) IDA-VIP3-IC-SSS-TR-2021-1 Capacity Building of Local S 3 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.31 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Chui oblast (4) IDA-VIP3-IC-SSS-TR-2021-1 Capacity Building of Local S 4 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Issyk-Kul oblast (2) IDA-VIP3-IC-SSS-TR-2021-1 Capacity Building of Local S 5 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 722.33 Signed 2021-04-19 2021-04-29 2021-04-24 2021-06-08 2021-04-30 2021-07-20 2021-07-29 s of Operational Manual of P unities roject in the Chui oblast (5) IDA-VIP3-IC-SSS-TR-2021-1 Capacity Building of Local S 7 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-29 2021-05-25 2021-07-28 s of Operational Manual of P unities roject in the Chui oblast (7) IDA-VIP3-IC-SSS-TR-2021-1 Capacity Building of Local S 8 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Chui oblast (8) IDA-VIP3-IC-SSS-TR-2021-1 Capacity Building of Local S 9 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Talas oblast (1) IDA-VIP3-IC-SSS-TR-2021-2 Capacity Building of Local S 0 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-05-19 2021-05-25 2021-08-17 s of Operational Manual of P unities roject in the Chui oblast (9) IDA-VIP3-IC-SSS-TR-2021-2 Capacity Building of Local S 1 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-20 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Chui oblast (10) IDA-VIP3-IC-SSS-TR-2021-2 Capacity Building of Local S 2 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.38 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Issyk-Kul oblast (3) IDA-VIP3-IC-SSS-TR-2021-2 Capacity Building of Local S 3 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.38 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Talas oblast (2) IDA-VIP3-IC-SSS-TR-2021-2 Capacity Building of Local S 4 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.38 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Naryn oblast (3) Page 10 IDA-VIP3-IC-SSS-TR-2021-2 Capacity Building of Local S 5 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.38 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Chui oblast (11) IDA-VIP3-IC-SSS-TR-2021-2 Capacity Building of Local S 6 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.38 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Issyk-Kul oblast (4) IDA-VIP3-IC-SSS-TR-2021-2 Capacity Building of Local S 7 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.38 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Naryn oblast (4) IDA-VIP3-IC-SSS-TR-2021-2 Capacity Building of Local S 8 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,591.47 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Naryn oblast (4) IDA-VIP3-IC-SSS-TR-2021-2 Capacity Building of Local S 9 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Talas oblast (3) IDA-VIP3-IC-SSS-TR-2021-3 Capacity Building of Local S 0 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Naryn oblast (5) IDA-VIP3-IC-SSS-TR-2021-3 Capacity Building of Local S 1 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Chui oblast (13) IDA-VIP3-IC-SSS-TR-2021-3 Capacity Building of Local S 2 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Chui oblast (14) IDA-VIP3-IC-SSS-TR-2021-3 Capacity Building of Local S 3 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Talas oblast (4) IDA-VIP3-IC-SSS-TR-2021-3 Capacity Building of Local S 4 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,768.30 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Issyk-Kul oblast (6) IDA-VIP3-IC-SSS-TR-2021-3 Capacity Building of Local S 5 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,591.47 Signed 2021-04-19 2021-04-29 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Chui oblast (14) IDA-VIP3-IC-SSS-TR-2021-3 Capacity Building of Local S 6 / Trainer for basic training IDA / D0410 elf-Governments and Comm Post Direct Selection Direct 1,588.00 1,945.13 Signed 2021-04-19 2021-04-30 2021-04-24 2021-05-10 2021-04-30 2021-05-25 2021-07-29 s of Operational Manual of P unities roject in the Chui oblast (15) IDA-VIP3-T-IC-2021-2 / Tech nical supervision consultant Individual Consult for sub project of the Major r IDA / D0410 Village Investments Post Open 3,800.00 3,932.67 Signed 2021-05-03 2021-05-06 2021-06-03 2021-09-02 2021-06-06 2021-09-02 2021-06-10 2021-10-02 2022-01-06 ant Selection epair kindergarten Alenka in the Predtechenka village Ch ui oblast (3 cycle) IDA-VIP3-T-IC-2021-3 / Tech nical supervision consultant Individual Consult for sub project of the Repairi IDA / D0410 Village Investments Post Open 4,800.00 0.00 Canceled 2021-05-03 2021-06-07 2021-06-08 2021-06-10 2022-03-07 ant Selection ng water sistem in the Jyrgal an village Tup raijion Issyk-K ul oblast (3 cycle) IDA-VIP3-T-IC-2021-4 / Tech nical supervision consultant Individual Consult for sub project of the сonstr IDA / D0410 Village Investments Post Open 3,200.00 0.00 Canceled 2021-05-04 2021-06-04 2021-06-07 2021-06-09 2021-12-06 ant Selection uction of FAP`in the village Min-Bulak Bakai-Ata raijion T alas oblast (3 cycle) IDA-VIP3-T-IC-2021-5 / Tech nical supervision consultant Individual Consult for sub project of the сonstr IDA / D0410 Village Investments Post Open 3,200.00 0.00 Canceled 2021-05-03 2021-06-05 2021-06-06 2021-06-08 2021-12-05 ant Selection uction of FAP`in the village Min-Bulak Typ rajion Issyk-K ul oblast (3 cycle) IDA-VIP3-T-IC-2021-6 / Tech nical supervision consultant for sub project Installation of Individual Consult IDA / 56010 Village Investments Post Open 2,948.00 1.00 Signed 2021-05-17 2021-05-05 2021-06-17 2021-06-30 2021-06-20 2021-06-30 2021-06-24 2021-07-02 2021-12-21 lighting on the streets in vill ant Selection ages Zher-Kazar, Nizhniy-No oruz, Druzhba Villages, Issyk -Ata Raion, Chuy Oblast IDA-VIP3-T-IC-2021-7 / Tech nical supervision consultant Individual Consult for sub project of the Constr IDA / 56010 Village Investments Post Open 2,948.00 2,368.93 Signed 2021-05-17 2021-05-06 2021-06-17 2021-07-23 2021-06-20 2021-07-23 2021-06-24 2021-07-27 2021-12-21 ant Selection uction of FAP in the village Min-Bulak Bakai-Ata raijion T alas oblast IDA-VIP3-IC-2020-19 / Nary Capacity Building of Local S n Regional Specialist for Soc Individual Consult IDA / D0410 elf-Governments and Comm Post Open 6,000.00 4,291.43 Signed 2021-06-01 2021-05-25 2021-06-30 2021-07-26 2021-07-01 2021-07-27 2021-07-03 2021-08-03 2021-12-31 ial Mobilization, Capacity Bui ant Selection unities lding and Gender Developm ent IDA-VIP-S-DC-21-5 / Author' s supervision of the Installati on of lighting on the streets IDA / D0410 Village Investments Post Direct Selection Direct 2,500.00 722.33 Signed 2021-06-01 2021-06-08 2021-06-16 2021-06-08 2021-06-19 2021-07-20 2021-12-16 in villages Zher-Kazar, Nizhn iy-Nooruz, Druzhba Villages, Issyk-Ata Raion, Chuy Oblast (3 Cicle) IDA-VIP-S-DC-21-6 / Author' s supervision of the Major R epair drinking water system IDA / D0410 Village Investments Post Direct Selection Direct 10,700.00 2,058.40 Signed 2021-06-03 2021-06-08 2021-06-18 2021-06-09 2021-06-21 2021-07-16 2022-03-18 in the village Jyrgalan Ak-Su u raijon Issyk-Kul oblast (3 Cicle) IDA-VIP3-IC-2021-4 / Сonsul tant for the development of detailed design estimates fo r installation of sanitary facil Individual Consult IDA / D0410 Village Investments Post Open 1,176.00 1,315.56 Signed 2021-06-15 2021-06-15 2021-07-13 2021-07-12 2021-07-13 2021-07-19 2021-07-18 2021-07-23 2021-08-17 ities in a secondary school i ant Selection n the villages of Santash 3-f erma, Sary-Tologoi, Ken-Suu , Baizak, Santash AO, Tyup r ayon, Issyk-Kul oblast Page 11 IDA-VIP3-IC-2021-6 / Сonsul tant for the development of detailed design estimates fo Individual Consult IDA / D0410 Village Investments Post Open 1,176.00 1.14 Signed 2021-06-16 2021-06-15 2021-07-14 2021-07-13 2021-07-14 2021-07-12 2021-07-19 2021-07-23 2021-08-18 r the renovation of a FAP an ant Selection d purchase of inventory in t he village of Ozgorush, Ozgu rush AO, Bakai-Ata rayon, T alas oblast IDA-VIP3-IC-2021-7 / Сonsul tant for the development of detailed design estimates fo Individual Consult r the repair of sanitary facilit IDA / D0410 Village Investments Post Open 1,176.00 825.21 Signed 2021-06-16 2021-06-15 2021-07-14 2021-07-12 2021-07-14 2021-07-22 2021-07-19 2021-07-24 2021-08-18 ant Selection ies in the secondary school i n the village of Kyz-Molo, Ts elinniy AO, Moskovskiy rayo n, Chuy oblast IDA-VIP3-IC-2021-5 / Consul tant for the development of DED for the renovation of a FAP, the purchase of furnitur Individual Consult IDA / D0410 Village Investments Post Open 1,176.00 750.97 Signed 2021-06-16 2021-06-14 2021-07-14 2021-07-12 2021-07-14 2021-07-20 2021-07-19 2021-07-23 2021-08-18 e, office equipment, and the ant Selection installation of a water suppl y system with sanitary facilit ies in a kindergarten in the v illage of Konorchok, Ak-Taal a rayon, Naryn obl IDA-VIP3-IC-2021-8 / Techni cal supervision consultant fo Individual Consult r sub project of the Construc IDA / D0410 Village Investments Post Open 2,948.00 4,543.90 Signed 2021-07-22 2021-08-05 2021-08-22 2021-09-06 2021-08-25 2021-09-07 2021-08-29 2021-09-09 2022-02-25 ant Selection tion of FAP in the village Ak- Bulun Tup Ragion Issyk-Kul oblast IDA-VIP3-IC-2021-9 / Techni cal supervision consultant fo Individual Consult r sub project of the Construc IDA / D0410 Village Investments Post Open 2,948.00 0.00 Canceled 2021-07-22 2021-08-22 2021-08-25 2021-08-29 2022-02-25 ant Selection tion of FAP in the village Min -Bulak Bakai-Ata raijion Tala s oblast IDA-VIP3-T-IC-2021-10 / Tec hnical supervision consultan Individual Consult t for sub project of the Const IDA / D0410 Village Investments Post Open 2,948.00 4,131.14 Signed 2021-08-09 2021-08-05 2021-09-08 2021-09-03 2021-09-11 2021-09-06 2021-09-16 2021-09-09 2022-03-15 ant Selection ruction of FAP in the village Kaiyndy Bulak Ak-Tala raijio n Naryn oblast IDA-VIP3-T-IC-2021-11 / Tec hnical supervision consultan Individual Consult t for sub project of the Const IDA / D0410 Village Investments Post Open 2,948.00 3,361.55 Signed 2021-08-09 2021-08-05 2021-09-08 2021-09-14 2021-09-11 2021-09-16 2021-09-16 2021-09-21 2022-03-15 ant Selection ruction of FAP in the village J ar-Bashy Issyk-Ata district C hui oblast IDA-VIP-S-DC-21-7 / Author Supervision of Construction of feldsher-obstetric station IDA / D0410 Village Investments Post Direct Selection Direct 5,325.00 2,416.83 Signed 2021-08-12 2021-09-24 2021-08-18 2021-09-27 2021-08-29 2021-12-02 2022-02-25 (FAP) in the villages Ak-Bulu n, Min-Bulak, Kaindy-Bulak, Min-Bulak, Besh-kooruk, Jar- Bashy IDA-VIP3-IC-2021-10 / Monit IDA / 56010 Project Management Post Direct Selection Direct 2,625.00 2,589.59 Signed 2021-09-22 2021-10-01 2021-09-28 2021-10-04 2021-10-01 2021-10-05 2021-12-31 oring and MIS specialist IDA-VIP3-T-IC-2020-5/RT1 / I Individual Consult IDA / D0410 Village Investments Post Open 5,835.00 6,429.17 Signed 2021-01-28 2021-02-01 2021-03-18 2021-03-17 2021-04-08 2021-04-13 2021-05-13 2021-04-14 2021-11-09 nfrastructure Engineer ant Selection IDA-VIP3-T-IC-2021-12 / Tec hnical supervision consultan Individual Consult t for sub project of the Major IDA / 56010 Village Investments Post Open 2,948.00 4,670.57 Signed 2021-11-16 2021-11-19 2021-12-13 2021-12-13 2021-12-17 2021-12-13 2021-12-24 2021-12-14 2022-06-22 ant Selection Repair of Building FAP in the Ozgorysh village Bakai-Ata d istrict Talas oblast IDA-VIP-S-DC-21-8 / Author Supervision of Construction of Major repair of kindergart IDA / 56010 Village Investments Post Direct Selection Direct 5,325.00 1,007.37 Signed 2021-12-07 2021-12-08 2021-12-21 2021-12-06 2021-12-26 2021-11-06 2022-06-24 en "ALENKA" in the village P redtechenka Moscow rajion Chui oblast IDA-VIP3-AF-IC-2022-1 / CD Capacity Building of Local S Individual Consult Under Implement SO for the Alamudun rayon IDA / D0410 elf-Governments and Comm Post Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 ant Selection ation of the Chui oblast unities IDA-VIP3-AF-IC-2022-2 / CD Capacity Building of Local S Individual Consult IDA / D0410 Post Open 8,325.00 5,288.46 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-02 2022-02-11 2022-02-02 2022-02-13 2022-02-04 2022-12-31 SO for the Zhayil rayon of th elf-Governments and Comm ant Selection e Chui oblast unities IDA-VIP3-AF-IC-2022-3 / CD Capacity Building of Local S Individual Consult IDA / D0410 Post Open 8,325.00 5,236.74 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-02 2022-02-11 2022-02-02 2022-02-13 2022-02-04 2022-12-31 SO for the Kemin rayon of th elf-Governments and Comm ant Selection e Chui oblast unities IDA-VIP3-AF-IC-2022-4 / CD Capacity Building of Local S Individual Consult SO for the Moskova rayon of IDA / D0410 elf-Governments and Comm Post Open 8,325.00 5,236.74 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-02 2022-02-11 2022-02-02 2022-02-13 2022-02-04 2022-12-31 ant Selection the Chui oblast unities IDA-VIP3-AF-IC-2022-5 / CD Capacity Building of Local S Individual Consult SO for the Panfilov rayon of IDA / D0410 elf-Governments and Comm Post Open 8,325.00 5,344.13 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-02 2022-02-11 2022-02-02 2022-02-13 2022-02-04 2022-12-31 ant Selection the Chui oblast unities IDA-VIP3-AF-IC-2022-6 / CD Capacity Building of Local S Individual Consult SO for the Sokuluk rayon of IDA / D0410 elf-Governments and Comm Post Open 8,325.00 5,344.13 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-02 2022-02-11 2022-02-02 2022-02-13 2022-02-15 2022-12-31 ant Selection the Chui oblast unities IDA-VIP3-AF-IC-2022-7 / CD Capacity Building of Local S Individual Consult IDA / D0410 Post Open 8,325.00 5,344.13 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-02 2022-02-11 2022-02-02 2022-02-13 2022-02-04 2022-12-31 SO for the Chui rayon of the elf-Governments and Comm ant Selection Chui oblast unities IDA-VIP3-AF-IC-2022-8 / CD Capacity Building of Local S Individual Consult SO for the Ysyk-Ata rayon of IDA / D0410 elf-Governments and Comm Post Open 8,325.00 5,344.13 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-02 2022-02-11 2022-02-02 2022-02-13 2022-02-04 2022-12-31 ant Selection the Chui oblast unities IDA-VIP3-AF-IC-2022-9 / CD Capacity Building of Local S Individual Consult Under Implement SO for the Ak-Tala rayon of t IDA / 56010 elf-Governments and Comm Post Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 ant Selection ation he Naryn oblast unities IDA-VIP3-AF-IC-2022-10 / C Capacity Building of Local S Individual Consult DSO for the At-Bashy rayon IDA / D0410 elf-Governments and Comm Post Open 8,325.00 6,470.59 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-01 2022-02-11 2022-02-01 2022-02-13 2022-02-04 2022-12-31 ant Selection of the Naryn oblast unities IDA-VIP3-AF-IC-2022-11 / C Capacity Building of Local S Individual Consult DSO for the Zhumgal rayon IDA / D0410 elf-Governments and Comm Post Open 8,325.00 6,470.59 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-01 2022-02-11 2022-02-03 2022-02-13 2022-02-04 2022-12-31 ant Selection of the Naryn oblast unities IDA-VIP3-AF-IC-2022-12 / C Capacity Building of Local S Individual Consult DSO for the Kochkor rayon o IDA / D0410 elf-Governments and Comm Post Open 8,325.00 6,470.59 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-01 2022-02-11 2022-02-01 2022-02-13 2022-02-04 2022-12-31 ant Selection f the Naryn oblast unities IDA-VIP3-AF-IC-2022-13 / C Capacity Building of Local S Individual Consult DSO for the Naryn rayon of t IDA / D0410 elf-Governments and Comm Post Open 8,325.00 5,628.23 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-01 2022-02-11 2022-02-01 2022-02-13 2022-02-04 2022-12-31 ant Selection he Naryn oblast unities IDA-VIP3-AF-IC-2022-14 / C Capacity Building of Local S Individual Consult Under Implement DSO for the Ak-Suu rayon of IDA / D0410 elf-Governments and Comm Post Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 ant Selection ation the Issyk-Kul oblast unities Page 12 IDA-VIP3-AF-IC-2022-15 / C Capacity Building of Local S Individual Consult Under Implement DSO for the Jeti-Oguz rayon IDA / D0410 elf-Governments and Comm Post Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 ant Selection ation of the Issyk-Kul oblast unities IDA-VIP3-AF-IC-2022-16 / C Capacity Building of Local S Individual Consult DSO for the Ton rayon of the IDA / D0410 elf-Governments and Comm Post Open 8,325.00 5,628.23 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-01 2022-02-11 2022-02-01 2022-02-13 2022-02-04 2022-12-31 ant Selection Issyk-Kul oblast unities IDA-VIP3-AF-IC-2022-17 / C Capacity Building of Local S Individual Consult Under Implement DSO for the Tup rayon of the IDA / D0410 elf-Governments and Comm Post Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 ant Selection ation Issyk-Kul oblast unities IDA-VIP3-AF-IC-2022-18 / C Capacity Building of Local S Individual Consult DSO for the Issyk-Kul rayon IDA / D0410 elf-Governments and Comm Post Open 8,325.00 5,628.23 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-01 2022-02-11 2022-02-01 2022-02-13 2022-02-04 2022-12-31 ant Selection of the Issyk-Kul oblast unities IDA-VIP3-AF-IC-2022-19 / C Capacity Building of Local S Individual Consult DSO for the Talas rayon of t IDA / D0410 elf-Governments and Comm Post Open 8,325.00 6,470.59 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-01 2022-02-11 2022-02-01 2022-02-13 2022-02-04 2022-12-31 ant Selection he Talas oblast unities IDA-VIP3-AF-IC-2022-20 / C Capacity Building of Local S Individual Consult Under Implement DSO for the Bakai-Ata rayon IDA / D0410 elf-Governments and Comm Post Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 ant Selection ation of the Talas oblast unities IDA-VIP3-AF-IC-2022-21 / C Capacity Building of Local S Individual Consult DSO for the Manas rayon of IDA / D0410 elf-Governments and Comm Post Open 8,325.00 5,628.23 Signed 2022-01-12 2022-01-13 2022-02-10 2022-02-01 2022-02-11 2022-02-01 2022-02-13 2022-02-04 2022-12-31 ant Selection the Talas oblast unities IDA-VIP3-AF-IC-2022-22 / C Capacity Building of Local S Individual Consult Under Implement DSO for the Kara-Buura rayo IDA / D0410 elf-Governments and Comm Post Open 8,325.00 0.00 2022-01-12 2022-01-13 2022-02-10 2022-02-11 2022-02-13 2022-12-31 ant Selection ation n of the Talas oblast unities IDA-VIP3-IC-2022-22 / Talas Capacity Building of Local S Regional Specialist for Social Individual Consult IDA / D0410 elf-Governments and Comm Post Open 4,376.00 4,000.00 Signed 2022-01-19 2022-01-14 2022-02-19 2022-02-02 2022-02-22 2022-02-02 2022-02-28 2022-02-04 2022-06-30 Mobilization, Capacity Buildi ant Selection unities ng and Gender Developmen t IDA-VIP3-AF-IC-2022-57 / Cli Capacity Building of Local S Individual Consult IDA / 56010 Post Open 2,950.00 0.00 Canceled 2022-02-18 2022-02-18 2022-03-04 2022-03-07 2022-03-13 2022-06-30 mate Change Specialist elf-Governments and Comm ant Selection unities IDA-VIP3-AF-IC-2022-57/RT / Capacity Building of Local S Individual Consult IDA / D0410 Post Open 2,950.00 0.00 Signed 2022-06-12 2022-06-10 2022-07-20 2022-08-04 2022-07-22 2022-09-01 2022-07-26 2022-12-31 Climate Change Specialist elf-Governments and Comm ant Selection unities IDA-VIP3-AF-IC-2022-58 / Ec Capacity Building of Local S Individual Consult IDA / D0410 Post Open 2,950.00 0.00 Signed 2022-06-12 2022-06-10 2022-07-20 2022-08-04 2022-07-22 2022-09-05 2022-07-26 2022-12-31 onomist (Expert of buisiness elf-Governments and Comm ant Selection skills) unities IDA-AFVIP3-CDSE-IC-2022-2 Capacity Building of Local S Individual Consult 3 / CDSO of the Ak-Suu distri IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-01 2022-11-24 2022-10-12 2022-12-31 ant Selection ct of the Issyk-Kul oblast unities IDA-AFVIP3-CDSE-IC-2022-2 Capacity Building of Local S Individual Consult 4 / CDSO of the Zheti-Oguz IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-01 2022-11-24 2022-10-12 2022-12-14 ant Selection district of the Issyk-Kul oblas unities t IDA-AFVIP3-CDSE-IC-2022-2 Capacity Building of Local S Individual Consult 5 / CDSO of the Issyk-Kul dis IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2023-01-24 2022-10-01 2023-01-24 2022-10-12 2022-12-27 ant Selection trict of the Issyk-kul oblast unities IDA-AFVIP3-CDSE-IC-2022-2 Capacity Building of Local S Individual Consult 6 / CDSO of the Ton district IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-19 2022-09-30 2022-11-11 2022-10-01 2022-11-24 2022-10-12 2022-12-31 ant Selection of the Issyk-Kul oblast unities IDA-AFVIP3-CDSE-IC-2022-2 Capacity Building of Local S Individual Consult 7 / CDSO of the Tup district IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-01 2022-11-24 2022-10-12 2022-12-31 ant Selection of the Issyk-kul oblast unities IDA-AFVIP3-CDSE-IC-2022-2 Capacity Building of Local S Individual Consult 8 / CDSO of the Ak-Tala distr IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-19 2022-09-30 2022-12-23 2022-10-01 2023-01-11 2022-11-01 2023-01-20 ant Selection ict of the Naryn oblast unities IDA-AFVIP3-CDSE-IC-2022-2 Capacity Building of Local S Individual Consult 9 / CDSO of the At-Bashy dis IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-12-23 2022-10-05 2023-01-11 2022-11-01 2023-01-20 ant Selection trict of the Naryn oblast unities IDA-AFVIP3-CDSE-IC-2022-3 Capacity Building of Local S Individual Consult 0 / CDSO of the Jumgal distri IDA / 56010 elf-Governments and Comm Post Open - National 100.00 0.00 Completed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-01 2022-11-24 2022-10-12 2022-12-31 2023-03-11 ant Selection ct of the Naryn oblast unities IDA-AFVIP3-CDSE-IC-2022-3 Capacity Building of Local S Individual Consult 1 / CDSO of the Kochkor dist IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-01 2022-11-24 2022-10-12 2022-12-31 ant Selection rict of the Naryn oblast unities IDA-AFVIP3-CDSE-IC-2022-3 Capacity Building of Local S Individual Consult 2 / CDSO of the Naryn distric IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-12-23 2022-10-01 2023-01-11 2022-10-12 2022-12-31 ant Selection t of the Naryn oblast unities IDA-AFVIP3-CDSE-IC-2022-3 Capacity Building of Local S Individual Consult 3 / CDSO of the Bakai-Ata di IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-05 2022-11-24 2022-11-01 2023-01-20 ant Selection strict of the Talas oblast unities IDA-AFVIP3-CDSE-IC-2022-3 Capacity Building of Local S Individual Consult 4 / CDSO of the Kara-Bura di IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-01 2022-11-28 2022-10-12 2022-12-31 ant Selection strict of the Talas oblast unities IDA-AFVIP3-CDSE-IC-2022-3 Capacity Building of Local S Individual Consult 5 / CDSO of the Manas distri IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-05 2022-11-24 2022-11-01 2023-01-20 ant Selection ct of the Talas oblast unities IDA-AFVIP3-CDSE-IC-2022-3 Capacity Building of Local S Individual Consult 6 / CDSO of the Talas district IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-01 2022-11-28 2022-11-01 2023-01-20 ant Selection of the Talas oblast unities IDA-AFVIP3-CDSE-IC-2022-3 Capacity Building of Local S Individual Consult 7 / CDSO of the Alamudun di IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-05 2022-11-24 2022-11-01 2023-01-20 ant Selection strict of the Chui oblast unities IDA-AFVIP3-CDSE-IC-2022-3 Capacity Building of Local S Individual Consult 8 / CDSO of the Jaiyl district IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-01 2022-11-24 2022-11-01 2023-01-20 ant Selection of the Chui oblast unities IDA-AFVIP3-CDSE-IC-2022-3 Capacity Building of Local S Individual Consult 9 / CDSO of the Kemin distri IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-05 2022-11-24 2022-11-01 2023-01-20 ant Selection ct of the Chui oblast unities IDA-AFVIP3-CDSE-IC-2022-4 Capacity Building of Local S Individual Consult 0 / CDSO of the Moscow dist IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-05 2022-11-24 2022-10-16 2023-01-04 ant Selection rict of the Chui oblast unities IDA-AFVIP3-CDSE-IC-2022-4 Capacity Building of Local S Individual Consult 1 / CDSO of the Panfilov dist IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-05 2022-11-24 2022-11-01 2023-01-20 ant Selection rict of the Chui oblast unities Page 13 IDA-AFVIP3-CDSE-IC-2022-4 Capacity Building of Local S Individual Consult 2 / CDSO of the Sokuluk dist IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-11 2022-10-05 2022-11-24 2022-10-27 2023-01-15 ant Selection rict of the Chui oblast unities IDA-AFVIP3-CDSE-IC-2022-4 Capacity Building of Local S Individual Consult 3 / CDSO of the Chui district IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2023-01-18 2022-10-05 2023-02-01 2022-11-01 2023-01-20 ant Selection of the Chui oblast unities IDA-AFVIP3-CDSE-IC-2022-4 Capacity Building of Local S Individual Consult 4 / CDSO of the Yssyk-Ata di IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2023-01-18 2022-10-05 2023-02-01 2022-11-01 2023-01-20 ant Selection strict of the Chui oblast unities IDA-AFVIP3-CHV-IC-2022-45 Capacity Building of Local S Individual Consult / Issyk-Kul regional chain val IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-10-03 2022-10-05 2022-10-19 2022-11-01 2023-01-20 ant Selection ue Specialist unities IDA-AFVIP3-CHV-IC-2022-46 Capacity Building of Local S Individual Consult IDA / 56010 Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-10-03 2022-10-05 2022-10-03 2022-11-01 2023-01-20 / Naryn regional chain value elf-Governments and Comm ant Selection Specialist unities IDA-AFVIP3-CHV-IC-2022-47 Capacity Building of Local S Individual Consult IDA / 56010 Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-10-03 2022-10-05 2022-10-19 2022-11-01 2023-01-20 / Talas regional chain value elf-Governments and Comm ant Selection Specialist unities IDA-AFVIP3-CHV-IC-2022-48 Capacity Building of Local S Individual Consult IDA / 56010 Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-10-03 2022-10-21 2022-10-19 2022-11-05 2023-01-24 / Chui regional chain value S elf-Governments and Comm ant Selection pecialist unities IDA-AFVIP3-TR-IC-2022-48 / Capacity Building of Local S Individual Consult IDA / 56010 Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-10-03 2022-10-01 2022-10-19 2022-10-12 2022-12-31 Chain Value Coach for the C elf-Governments and Comm ant Selection hui oblast (1) unities IDA-AFVIP3-TR-IC-2022-49 / Capacity Building of Local S Individual Consult IDA / 56010 Post Open - National 10,000.00 0.00 Completed 2022-09-01 2022-09-05 2022-09-30 2022-10-03 2022-10-01 2022-10-19 2022-10-12 2022-12-31 2023-03-10 Chain Value Coach for the C elf-Governments and Comm ant Selection hui oblast (2) unities IDA-AFVIP3-TR-IC-2022-50 / Capacity Building of Local S Individual Consult IDA / 56010 Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-10-16 2022-10-03 2022-10-17 2022-10-19 2022-10-28 2023-01-16 Chain Value Coach for the C elf-Governments and Comm ant Selection hui oblast (3) unities IDA-AFVIP3-TR-IC-2022-51 / Capacity Building of Local S Individual Consult IDA / 56010 Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-10-03 2022-10-05 2022-11-01 2022-10-29 2023-01-17 Chain Value Coach for the C elf-Governments and Comm ant Selection hui oblast (4) unities IDA-AFVIP3-TR-IC-2022-52 / Capacity Building of Local S Individual Consult Chain Value Coach for the T IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-10-03 2022-10-05 2022-10-19 2022-11-05 2023-01-24 ant Selection alas oblast (1) unities IDA-AFVIP3-TR-IC-2022-53 / Capacity Building of Local S Individual Consult Chain Value Coach for the T IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-11-18 2022-10-01 2022-12-01 2022-10-12 2022-12-31 ant Selection alas oblast (2) unities IDA-AFVIP3-TR-IC-2022-54 / Capacity Building of Local S Individual Consult Chain Value Coach for the Is IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-10-03 2022-10-05 2022-10-19 2022-10-29 2023-01-17 ant Selection syk-Kul oblast (1) unities IDA-AFVIP3-TR-IC-2022-55 / Capacity Building of Local S Individual Consult Chain Value Coach for the Is IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-10-03 2022-10-01 2022-10-19 2022-11-01 2023-01-20 ant Selection syk-Kul oblast (2) unities IDA-AFVIP3-TR-IC-2022-56 / Capacity Building of Local S Individual Consult Chain Value Coach for the Is IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-10-03 2022-10-01 2022-10-03 2022-10-12 2022-12-31 ant Selection syk-Kul oblast (3) unities IDA-AFVIP3-TR-IC-2022-57 / Capacity Building of Local S Individual Consult Chain Value Coach for the N IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-10-20 2022-10-05 2022-11-01 2022-10-16 2023-01-04 ant Selection aryn oblast (1) unities IDA-AFVIP3-TR-IC-2022-58 / Capacity Building of Local S Individual Consult Chain Value Coach for the N IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-10-20 2022-10-01 2022-11-01 2022-11-01 2023-01-20 ant Selection aryn oblast (2) unities IDA-AFVIP3-TR-IC-2022-59 / Capacity Building of Local S Individual Consult Chain Value Coach for the N IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 Signed 2022-09-01 2022-09-05 2022-09-30 2022-10-20 2022-10-05 2022-11-01 2022-11-01 2023-01-20 ant Selection aryn oblast (3) unities IDA-AFVIP3-CHV-IC-2022-49 Capacity Building of Local S Individual Consult IDA / 56010 Post Open - National 10,000.00 0.00 Signed 2023-01-19 2023-01-23 2023-02-02 2023-02-14 2023-02-07 2023-03-01 2023-02-09 2023-12-31 / Chui regional chain value S elf-Governments and Comm ant Selection pecialist unities IDA-AFVIP3-CDSE-IC-2022-4 Capacity Building of Local S Individual Consult Under Implement 5 / CDSO of the Alamudun di IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 2023-02-10 2023-02-13 2023-03-20 2023-03-20 2023-03-25 2023-12-31 ant Selection ation strict of the Chui oblast unities IDA-AFVIP3-CDSE-IC-2022-4 Capacity Building of Local S Individual Consult Under Implement 6 / CDSO for the Ak-Tala ray IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 2023-02-10 2023-03-20 2023-03-20 2023-03-25 2023-12-31 ant Selection ation on of the Naryn oblast unities IDA-AFVIP3-CDSE-IC-2022-4 Capacity Building of Local S Individual Consult Pending Impleme 7 / CDSO for the Jugal distric IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 2023-03-01 2023-04-08 2023-04-09 2023-04-30 2023-12-31 ant Selection ntation t rayon of the Naryn oblast unities IDA-AFVIP3-TR-IC-2022-60 / Capacity Building of Local S Individual Consult Pending Impleme Chain Value Coach for the P IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 2023-03-01 2023-04-08 2023-04-09 2023-04-11 2023-12-31 ant Selection ntation anfilov and Jaiyl districtsChui unities oblast IDA-AFVIP3-TR-IC-2022-61 / Capacity Building of Local S Individual Consult Under Implement Chain Value Coach for the Y IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 2023-03-13 2023-03-13 2023-04-20 2023-04-21 2023-05-06 2023-12-31 ant Selection ation ssyk-Ata and Alamedein dist unities ricts Chui oblast IDA-AFVIP3-TR-IC-2022-62 / Capacity Building of Local S Individual Consult Under Implement Chain Value Coach for the Ju IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 2023-03-13 2023-03-13 2023-04-11 2023-04-12 2023-04-14 2023-12-27 ant Selection ation mgal districts Naryn oblast unities IDA-AFVIP3-CDSE-IC-2022-4 Capacity Building of Local S Individual Consult Pending Impleme 8 / CDSO for the Kochkor dis IDA / 56010 elf-Governments and Comm Post Open - National 10,000.00 0.00 2023-05-04 2023-06-11 2023-06-12 2023-06-14 2023-12-31 ant Selection ntation trict rayon of the Naryn obla unities st IDA-VIP3-AF-IC-2023-2 / Issy Individual Consult Under Implement IDA / 67820 Project Management Post Open - National 10,000.00 0.00 2023-06-20 2023-06-22 2023-08-08 2023-08-29 2023-10-03 2024-03-31 k-Kul regional engineer ant Selection ation IDA-VIP3-AF-IC-2023-1 / Chu Individual Consult Under Implement IDA / 67820 Project Management Post Open - National 10,000.00 0.00 2023-06-20 2023-06-22 2023-08-08 2023-08-29 2023-10-03 2024-03-31 i Regional Social Mobilizatio ant Selection ation n Specialist Page 14 18-MONTH PROCUREMENT PLAN Project information: Phase I of Improved Child Survival Program for Human Capital MPA- P167156-- Immunization Plus and Malaria Progress by Accelerating Coverage and Transforming Services (IMPACT) Project Project Implementation Agencies: Federal Ministry of Health (NMEP and NPHCDA) Date of the Procurement Plan: January 1, 2020 Period covered by this Procurement Plan: January 2020 to June 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016), revised on November 1, 2017 and on August 1, 2018 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Nigeria Public Procurement Act 2007, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [15% is applicable for those contracts identified in the Procurement Plan tables]; Works: [ 7.5% is applicable for those contracts identified in the Procurement Plan tables] I. Threshold for Prior Review – Goods, Works, Non-Consulting Services and Consulting Services Prior-review Thresholds Thresholds for Procurement Methods High Substanti Moderate Low Risk Goods, IT & Non-Consulting Shortlist of National Procurement Type Risk al Risk Risk Works ($'000) ($'000) ($'000) ($'000) Services Consultants Request Request Engineering Open for for Open Open Open Consultin & Quotatio Quotatio 10,0 15,0 20,0 Internatio National internatio National g Constructio Works n or n or 5,000 00 00 00 nal or ICB or NCB National nal or ICB or NCB National Services n ($'000) ($'000) ($'000) ($'000) ($'000) Supervision Shopping Shopping ($'000) ($'000) ($'000) Goods, IT & Non- 2,0 4,0 6,0 Consulting Services 1,500 00 00 00 ≧ < ≦ ≧ < ≦ < ≦ Consultants 1,0 2,0 4,0 20,0 20,0 5,0 5,0 1 3 5 200 (Firms) 500 00 00 00 00 00 00 00 00 00 00 Post Review: All contracts not subject to prior review shall be subject to post review. Summary of the procurement packages for Goods, Works and Non-Consulting Services (Planned for the first 18 months after project effectiveness): Selec Evaluation Market tion Options Approa Review Meth (Most Expected ch Prequal- Domestic Expected by od Advantageo date of Sr. Contract Estimated (Open- ification Preferenc date of Bank (RFP, us Bid, bid/ No Description Cost (US$) Nation (Yes/ e Contract (Prior/ RFB, BAFO, proposal al/ No) (Yes/No) Signature Post) RFQ, Rated opening Limited DS Criteria etc.) etc.) etc.) Nigeria Malaria Elimination Programme (NMEP) GOODS Procurement of Long Lasting Open- Insecticide Internati Most Treated Nets 45,852,523 3rd Feb 13th July 1 Prior onal RFB Advantageou No Yes (Mass .29 2020 2020 s Bid Campaign & Routine Distribution) Procurement of Artemisinin based Open - Most National 3rd Feb 13th July 2 Combination Post 2,381,472 RFB Advantageou No No 2020 2020 Therapy (ACT)- s Bid (Public and Private) Procurement of Open- Most Rapid National 3rd Feb 13th July 3 Post 1,960,202 RFB Advantageou No No Diagnostics 2020 2020 s Bid Tests (RDTs) Most Artesunate Open- 3rd Feb 13th July 4 Post 420,881.89 RFB Advantageou No No Injection National 2020 2020 s Bid Sulphodoxine/P Most Open - 3rd Feb 13th July 5 yrimethamine_I Post 612,322 RFB Advantageou No No National 2020 2020 PTp s Bid Amodiaquine/Su Most lphodoxine/Pyri 2,990,781. Open - 3rd Feb 13th July 6 Post RFB Advantageou No No methamine 47 National 2020 2020 s Bid (SPAQ) Most Open - 3rd Feb 13th July 7 Sharp Boxes Post 152,122,43 RFB Advantageou No No National 2020 2020 s Bid Most Microscope Open - 3rd Feb 13th July 8 Post 491,031 RFB Advantageou No No commodities National 2020 2020 s Bid NON-CONSULTING SERVICES - NMEP State Malaria Elimination MOU/P Programme erform 10th 2,250,000. 9th July 1 (SMEP) Prior Limited ance Rated Criteria No NA February 00 2020 Performance Contra 2020 Contract and ct Operations National Malaria Elimination MOU/P Programme erform 10th 1,500,000. 9th July 2 (NMEP) Prior Limited ance Rated Criteria No NA February 00 2020 Performance Contra 2020 Contract and ct Operations National Primary Health Care Development Agency (NPHCDA) GOODS Procurement of Most vaccines and 61,380,767 5th Feb 13th July 1 Prior UN RFB Advantageou No No devices for .00 2020 2020 s Bid immunization Procurement and maintenance of Most UN 5th Feb 13th July 2 Generators and Post 900,000.00 RFB Advantageou No No System 2020 2020 Cold Chain s Bid Equipment (CCEs) Procurement and installation of Cold Chain Most 4,500,000. 5th Feb 13th July 3 Hubs (3 Prior UN RFB Advantageou No No 00 2020 2020 walking-in cold s Bid rooms) in Lagos Procurement of Emergency Transport 5th Feb 13th July 4 Service (ETS) Post 45,101.72 Limited RFQ Rated Criteria No No 2020 2020 vouchers, handbooks, and logbooks Procurement of Most Open- 5th Feb 13th July 5 equipment for Post 281,969.00 RFB Advantageou No No National 2020 2020 call centre s Bid Most Procurement of Open- 5th Feb 13th July 6 Post 969,529.00 RFB Advantageou No No 14 vehicles National 2020 2020 s Bid Procurement of 5th Feb 13th July 7 14 computer Post 14,000 Limited RFQ Rated Criteria No No 2020 2020 sets II. Summary of the procurement packages for Consulting Services -Planned for the first 18 months after project effectiveness): Selection Market Method Review Approach Expected Expected Estimate (QCBS, Shortlisti Sr. by Bank (Open - date of bid/ date of Contract Description d Cost FBS, ng No (Prior/ International proposal Contract (US$) LCBS, (Yes/ No) Post) / National/ opening Signature QBS, CQS, etc.) DS etc.) Nigeria Malaria Elimination Programme (NMEP) NGOs Service Contract (for 5 11,525,51 Open 10th Feb 31st Aug 1 Prior QCBS Yes states) 1.00 International 2020 2020 Technical Assistance to SMEP in 5 participating states, 630,000.0 10th Feb 31st July 2 Prior Limited INDV No multiple contracts by 0 2020 2020 different consultants Technical Assistance to NMEP (including procurement 150,000.0 10th Feb 31st July 3 Post Limited INDV No consultant), multiple 0 2020 2020 contracts. Independent Verification 300,000.0 Open- 10th Feb 31st July 4 Post CQS No Agents (IVA) for NGOs 0 National 2020 2020 Social and Behavioral Change 3,000,000. Open 10th Feb 31st Aug 5 Prior QCBS Yes Communication (SBCC) 00 International 2020 2020 Operations research on 2,131,148. Open 10th Feb 31st Aug 6 Prior QCBS Yes disease vector mapping 00 International 2020 2020 Operations research on entomological surveillance by 655,738.0 10th Feb 31st July 7 Prior Direct DS No Nigeria Institute of 0 2020 2020 Medical Research (NIMR) Operations research on therapeutic efficacy by 655,738.0 10th Feb 31st July 8 Prior Direct CDS No Nigeria Institute of 0 2020 2020 Medical Research (NIMR) Consultancy on warehouse 10th Feb 31st July 9 Post 32,131.00 Limited INDV No assessment 2020 2020 Programme Management Training (case management, 2,000,000. 10th Feb 31st July 10 Prior Limited INDV No M&E, IVM etc.) Multiple 00 2020 2020 Contracts National Primary Health Care Development Agency (NPHCDA) Technical assistance support 9,869,000. 10th Feb 31st July 1 to government for polio Prior UN CDS No 00 2020 2020 surveillance Technical assistance support to government for polio 15,301,00 10th Feb 31st July 2 Supplemental Immunization Prior UN CDS No 0.00 2020 2020 Activities (SIAs) surveillance through WHO Technical assistance support to government for polio 4,830,000. 10th Feb 31st July 3 logistics and social Prior UN CDS No 00 2020 2020 mobilization for polio through UNICEF Procurement of consultant for 10th Feb 31st July 4 Post 20,000.00 Limited INDV No landscape survey (SQUATS) 2020 2020 Technical assistance support 837,673.1 10th Feb 31st July 5 Prior Open-National INDV No to 12 SPHCDA PIU 3 2020 2020 Technical assistance support 10th Feb 31st July 6 Post 89,750.63 Limited INDV No to NPHCDA PIU 2020 2020 Procurement of Emergency Transport Services (ETS), MOU with National Union of 530,794.3 10th Feb 31st July 7 Prior Direct CDS No Road Transport Workers 9 2020 2020 (NURTW) and NACTOROMAS Training of ETS service providers, MOU with Federal 207,672.0 10th Feb 31st July 8 Post Direct CDS No Road Safety Commission 0 2020 2020 (FRSC) Conduct PAPA – Lot Quality Assurance Sampling, MOU 2,213,850. 10th Feb 31st July 9 Prior Limited CDS No with National Bureau of 00 2020 2020 Statistics (NBS) Consultancy for RCT research 1,902,356. 10th Feb 31st Aug 10 services with Nigerian Prior Open-National QCBS Yes 00 2020 2020 Universities Procurement of operations 1,689,751. Open- 10th Feb 31st Aug 11 Prior QCBS Yes research services 00 International 2020 2020 Support to Cold Chain Equipment (CCE) 23,000,00 10th Feb 31st July 12 Prior UN CDS No optimization platform 0.00 2020 2020 through UNICEF Technical assistance to 1,553,185. 10th Feb 31st July 13 LGHAs (89 total), multiple Post Open-National INDV No 50 2020 2020 contracts Technical assistance 310,076.0 10th Feb 31st July 14 Post Open-National QCBS Yes management firm 0 2020 2020 10th Feb 31st July 15 IVA for performance contract Post 300,000 Open-National CQS No 2020 2020 Procurement of services 3,203,345 Open- 10th Feb 31st Aug 16 for GIS imagery and Prior QCBS Yes .45 International 2020 2020 microplanning Procurement of Social Behaviour Change Open- 10th Feb 31st Aug 17 Prior 5,000,000 QCBS Yes Communication (SBCC) International 2020 2020 services Contracting of direct 2,000,000. Open- 10th Feb 31st Aug 18 Prior QCBS Yes facility financing firms 00 International 2020 2020 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a 1Guidelineson Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Nigeria : Nigeria Improved Child Survival Program for Human Capital MPA PLAN General Information Country: Nigeria 2022-02-22 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167156 GPN Date: Project Name: Nigeria Improved Child Survival Program for Human Capital MPA Loan / Credit No: IDA / 65390 Ekiti MPA Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-EKITI MPA-294418-CW-R Request for Quota FQ / minor Partitioning of PIU Component 1:Malaria Contro Request for Quota Single Stage - One E Under Imple 2022-06-1 IDA / 65390 Post Limited tions (Non Bank-S 5,139.00 0.00 2022-05-13 2022-05-13 2022-05-31 office with HDF plywood , Re l tions nvelope mentation 4 PD) novation , changing of 3 door s and painting GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-EKITI MPA-279594-GO-R FQ / the office furniture are n Component 1:Malaria Contro Request for Quota Single Stage - One E eeded for the setting up of th IDA / 65390 Post Limited 5,213.00 0.00 Signed 2022-02-25 2022-03-30 2022-03-23 2022-03-30 l tions nvelope e office to allow the PIU have a conducive working place NG-EKITI MPA-279618-GO-R Component 1:Malaria Contro Request for Quota Single Stage - One E FQ / Procurement of office eq IDA / 65390 Post Limited 9,193.96 0.00 Signed 2022-02-27 2022-04-01 2022-03-15 2022-03-22 l tions nvelope uipment for the commencem ent of the project NG-EKITI MPA-279626-GO-R Component 1:Malaria Contro Request for Quota Single Stage - One E Under Imple FQ / procurement of electrica IDA / 65390 Post Limited 2,886.68 0.00 2022-03-11 2022-09-01 2022-03-28 2022-04-04 l tions nvelope mentation l and electronic appliances fo r the office. NG-EKITI MPA-278920-GO-R FQ / the procurement of the one Project Pick-up van is to f Component 1:Malaria Contro Request for Quota Single Stage - One E Under Imple IDA / 65390 Post Limited 88,131.00 0.00 2022-03-10 2022-04-01 2022-03-27 2022-04-03 acilitate the effective covera l tions nvelope mentation ge of the project and enhanc e mobility to necessary place s for the Project NG-EKITI MPA-322643-GO-R FQ / HP Laptop, intel core i5, Component 1:Malaria Contro Request for Quota Single Stage - One E Pending Impl IDA / 65390 Post Open - National 9,530.00 0.00 2022-11-08 2022-11-17 2022-11-18 1TB HDD, 8.0GB RAM, wirele l tions nvelope ementation ss and blue tooth, windows 1 0 OS version NG-EKITI MPA-329886-GO-DI R / Supply and installation of the appropriate Accounting S oftware package to automate Component 1:Malaria Contro Under Imple IDA / 65390 Post Direct Selection Direct - National 11,800.00 0.00 2022-12-02 2023-01-04 2022-12-07 2022-12-20 2022-12-18 2022-12-24 the financial l mentation management system, autom ated backup system and recovery for the PIU of I MPACT Project Ekiti State NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-EKITI MPA-296175-CS-Q Component 1:Malaria Contro Quality And Cost- Under Implement CBS / ENGAGEMENT OF NON IDA / 65390 Post Open - National 938,140.00 0.00 2022-05-26 2022-07-26 2022-05-26 2022-07-29 2022-07-09 2022-08-16 2022-08-06 2022-09-05 2022-10-10 2022-11-14 2023-11-14 l Based Selection ation GOVERNMENT ORGANIZATIO N (NGO) NG-EKITI MPA-313447-CS-Q CBS / Engagement of NGO/N Component 1:Malaria Contro Quality And Cost- Under Implement on State Actor to carry out fu IDA / 65390 Prior Open - National 938,140.00 0.00 2022-09-05 2022-09-01 2022-09-26 2022-09-01 2022-11-09 2022-09-05 2022-12-07 2022-10-04 2023-01-06 2022-11-02 2023-02-10 2023-01-17 2023-03-17 2024-03-16 l Based Selection ation ll scale implementation of m alaria intervention in Ekiti Sta te INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-EKITI MPA-362488-CS-CD Component 1:Malaria Contro Under Implement S / ENGAGEMENT OF EXTERN IDA / 65390 Post Direct Selection Direct - National 3,333.33 0.00 2023-05-18 2023-05-18 2023-05-21 2023-05-22 2023-06-02 2023-06-09 l ation AL AUDITOR Page 1 PROCUREMENT PLAN (Textual Part) Project information: Country: Federal Democratic Republic of Ethiopia De-Risking, Inclusion and Value Enhancement of Pastoral Economies (DRIVE) in the Horn of Africa Project, Project ID No. P176517 Project Implementation agency: Ministry of Agriculture and Ministry of trade and Regional Integration Date of the Procurement Plan: July 14, 2022 Period covered by this Procurement Plan: July 2022 to Dec 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (Fourth Edition, November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Public Procurement and Property Administration Proclamation No. 649/2009, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works is not applicable for those contracts identified in the Procurement Plan tables] Other Relevant Procurement Information. Not Applicable PROCUREMENT Eastern and Southern Africa : De-risking, inclusion and value enhancement of pastoral economies in the Horn of Africa PLAN General Information Country: Eastern and Southern Africa 2023-05-31 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P176517 GPN Date: 2022-08-24 Project Name: De-risking, inclusion and value enhancement of pastoral economies in the Horn of Africa Loan / Credit No: IDA / E0380 Ministry of Trade and Regional Integration - Ethiopia Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOTRI-ETH-358156-GO-R Livestock Value Chains and Request for Quota Single Stage - One E Pending Impl FQ / Laptop, printer and phot IDA / E0380 Post Limited 85,000.00 0.00 2023-05-31 2023-07-26 2023-09-09 Trade Facilitation tions nvelope ementation ocopier and related IT equip ment NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOTRI-ETH-357812-CS-IN Livestock Value Chains and Individual Consult Pending Impleme IDA / E0380 Post Open - National 24,000.00 0.00 2023-05-26 2023-07-14 2023-08-04 2023-09-08 2024-09-02 DV / Recruitment of project C Trade Facilitation ant Selection ntation oordinator ET-MOTRI-ETH-357815-CS-IN Livestock Value Chains and Individual Consult Pending Impleme DV / Recruitment of Procure IDA / E0380 Prior Open - National 18,000.00 0.00 2023-05-26 2023-07-14 2023-08-04 2023-09-08 2024-09-02 Trade Facilitation ant Selection ntation ment Specialist ET-MOTRI-ETH-357816-CS-IN Livestock Value Chains and Individual Consult Pending Impleme IDA / E0380 Post Open - National 18,000.00 0.00 2023-05-26 2023-07-14 2023-08-04 2023-09-08 2024-09-02 DV / Recruitment of Financial Trade Facilitation ant Selection ntation specialist Page 1 PROCUREMENT PLAN (Textural Part) Project information Country: Federal Democratic Republic of Ethiopia Project Name: Development Response to Displacement Impacts Project in the Horn of Africa Phase II (DRDIP II) Project ID: P178047 Project Implementation Agency: Ministry of Agriculture (MoA) Date of the Procurement Plan: September 2022 Period covered by this Procurement Plan: September 2022 to December 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” dated November 2020 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Directives of the Federal and Regional Governments of Ethiopia such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations. Goods: Applicable Works: Applicable Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Not Applicable. Proposed Procedures for CDD Components: Applicable Other Relevant Procurement Information: The procurement procedures for Situations in Urgent Need of Assistance or Capacity Constraints described under paragraph 12 of Section III of the World Bank Policy on IPF, which will be applicable to fast track emergency procurements shall not apply. PROCUREMENT Eastern and Southern Africa : Development Response to Displacement Impacts Project in the Horn of Africa Phase II PLAN General Information Country: Eastern and Southern Africa 2023-05-24 Bank’s Approval Date of the Original Procurement Plan: 2023-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178047 GPN Date: 2022-10-05 Project Name: Development Response to Displacement Impacts Project in the Horn of Africa Phase II Loan / Credit No: IDA / E0590 Gambella Region Bureau of Agriculture and Natural Resources Development Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ET-GR-BOA&NRD-359315-C W-RFB / Expansion of Nyikwo Request for Quota Kebele High School (2 Blocks, Social and Economic Service Request for Quota Single Stage - One E Pending Imp 2024-02-0 IDA / E0590 Post Limited tions (Non Bank-S 199,930.00 0.00 2023-06-18 2023-07-14 SIF Sub-project, Sub-Compon s and Infrastructure tions nvelope lementation 9 PD) ent 1.1) in Gambella Zuria W oreda procured by Gambella Zureau Woreda Finance Offic e ET-GR-BOA&NRD-359322-C W-RFB / Expansion of Otiel K Request for Quota ebele Human Health Center ( Social and Economic Service Request for Quota Single Stage - One E Pending Imp 2024-03-1 IDA / E0590 Post Limited tions (Non Bank-S 199,950.00 0.00 2023-06-18 2023-07-14 2 Blocks, SIF Sub-project, Su s and Infrastructure tions nvelope lementation 0 PD) b-component 1.1) in Gog Wor eda procure by Gog woreda f inance office ET-GR-BOA&NRD-359319-C W-RFB / Expansion of Elieya Request for Quota Social and Economic Service Request for Quota Single Stage - One E Pending Imp 2024-02-0 Kebele HHC (2 Blocks, SIF Su IDA / E0590 Post Limited tions (Non Bank-S 199,980.00 0.00 2023-06-17 2023-07-13 s and Infrastructure tions nvelope lementation 8 b-project, Sub-Component 1. PD) 1) in Itang Woreda procure b y Itang woreda finance office ET-GR-BOA&NRD-359323-C W-RFB / Construction of Koy- Request for Quota Tunsi Kebele 5km Feeder Ro Social and Economic Service Request for Quota Single Stage - One E Pending Imp 2024-03-0 IDA / E0590 Post Limited tions (Non Bank-S 199,990.00 0.00 2023-06-17 2023-07-13 ad (SIF Sub-project, Sub-Com s and Infrastructure tions nvelope lementation 9 PD) ponent 1.1) in Dimma Wored a procure by Dimma woreda finance office GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-GR-BOA&NRD-359368-G O-RFQ / Procurement of Cook ing Stoves(165 in Qty) for D emonstration for Dimma, Go Sustainable Environmental Request for Quota Single Stage - One E Pending Impl IDA / E0590 Post Open - National 26,179.25 0.00 2023-05-30 2023-06-24 2023-08-08 g, Gambella Zuria, Itang (ne Management tions nvelope ementation w Kebeles), Lare Woreda an d Gambella Town(new Wored as) by Bureau of Agriculture and natural resources ET-GR-BOA&NRD-359372-G O-RFQ / Procurement of Solar Light (79 in Qty) for Demonst ration for Dimma, Gog, Itang, Sustainable Environmental Request for Quota Single Stage - One E Pending Impl IDA / E0590 Post Open - National 60,644.00 0.00 2023-05-31 2023-06-25 2023-08-09 Gambella Zuria (new Kebeles Management tions nvelope ementation ), Lare Woreda and Gambella Town(new Woredas) by Regi onal Bureau of Agriculture an d Natural Resources ET-GR-BOA&NRD-359887-G O-RFQ / Demonstration of im proved agricultural livestock technologies on FTC/PTC (Far Request for Quota Single Stage - One E Pending Impl m toools-402 in Qty) for Gog, IDA / E0590 Livelihoods Program Post Open - National 16,982.00 0.00 2023-06-03 2023-06-25 2023-08-09 tions nvelope ementation Dimma, Itang, Gambella Zuri a (new Kebeles), Lare Wored a and Gambella Town(new W oredas) by Bureau of Agricult ure and Natural Resources ET-GR-BOA&NRD-359883-G O-RFQ / Procurement of farm tools/equipment (2400 in Qty Sustainable Environmental Request for Quota Single Stage - One E Pending Impl ) for Gog, Dimma, Itang, Gam IDA / E0590 Post Open - National 26,042.00 0.00 2023-05-31 2023-07-07 2023-08-21 Management tions nvelope ementation bella Zuria(new Kebeles), Lar e Woreda and Gambella Tow n (new Woredas) by Bureau of Agriculture and Natural Re sources ET-GR-BOA&NRD-365114-G O-RFQ / Procurement of IT eq uipment (desktop, laptop, pri nter, photocopy and LCD ) fo Social and Economic Service Request for Quota Single Stage - One E Pending Impl IDA / E0590 Post Limited 89,000.00 0.00 2023-06-08 2023-06-21 2023-07-06 r Woredas (Gog, Dimma, Ga s and Infrastructure tions nvelope ementation mbella Zuria, Itang, Lare), Ga mbella city administration an d DRDIP-II Regional Office pr ocured by Regional BoANR ET-GR-BOA&NRD-364956-G O-RFQ / Procurement of offic e furniture (shelf, file cabinet Social and Economic Service Request for Quota Single Stage - One E Pending Impl , table, chair, bench, and cas IDA / E0590 Post Limited 11,075.00 0.00 2023-06-08 2023-06-21 2023-07-05 s and Infrastructure tions nvelope ementation h box machine) for Itang Spe cial woreda and new kebeles procured by Itang Special Wo reda Finance Office ET-GR-BOA&NRD-365106-G O-RFQ / Procurement of offic e furniture (shelf, file cabinet Social and Economic Service Request for Quota Single Stage - One E Pending Impl , table, chair, bench, and cas IDA / E0590 Post Limited 8,704.00 0.00 2023-06-08 2023-06-20 2023-07-04 s and Infrastructure tions nvelope ementation h box machine) for Gambella woreda and new kebeles pro cured by Gambella Woreda Fi nance Office Page 1 ET-GR-BOA&NRD-365108-G O-RFQ / Procurement of offic e furniture (shelf, file cabinet Social and Economic Service Request for Quota Single Stage - One E Pending Impl , table, chair, bench, and cas IDA / E0590 Post Limited 7,519.00 0.00 2023-06-08 2023-06-19 2023-07-05 s and Infrastructure tions nvelope ementation h box machine) for Dimma w oreda and new kebeles procu red by Dimma Woreda Finan ce Office ET-GR-BOA&NRD-365109-G O-RFQ / Procurement of offic e furniture (shelf, file cabinet Social and Economic Service Request for Quota Single Stage - One E Pending Impl IDA / E0590 Post Limited 8,704.00 0.00 2023-06-08 2023-06-18 2023-07-04 , table, chair, bench, and cas s and Infrastructure tions nvelope ementation h box machine) for Gog wore da and new kebeles procured by Gog Woreda Finance Offic e ET-GR-BOA&NRD-365110-G O-RFQ / Procurement of offic Social and Economic Service Request for Quota Single Stage - One E Pending Impl e furniture (shelf, table, chair IDA / E0590 Post Limited 5,204.00 0.00 2023-06-08 2023-06-21 2023-07-06 s and Infrastructure tions nvelope ementation , and cash box machine) for Lare woreda procured by Lar e Woreda Finance Office ET-GR-BOA&NRD-365111-G O-RFQ / Procurement of offic e furniture (shelf, table, chair Social and Economic Service Request for Quota Single Stage - One E Pending Impl IDA / E0590 Post Limited 5,204.00 0.00 2023-06-08 2023-06-21 2023-07-06 , and cash box machine) for s and Infrastructure tions nvelope ementation Gambella City Administration procured by Gambella City A dministration Finance Office ET-GR-BOA&NRD-365112-G O-RFQ / Procurement of offic e furniture (shelf, and chairs) Social and Economic Service Request for Quota Single Stage - One E Pending Impl IDA / E0590 Post Limited 1,593.00 0.00 2023-06-08 2023-06-21 2023-07-05 for regional DRDIP II Office to s and Infrastructure tions nvelope ementation be procured by Regional Bur eau of Agriculture and Natur al Resources Development NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 ANDHRA PRADESH INTEGRATED IRRIGATION AND AGRICULTURE TRANSFORMATION PROJECT Procurement Methods Procurement Approaches and Thresholds (US$ Equivalent) Methods Open international (goods, IT, and non- >3 million consulting services) Open national (goods, IT, and non- >100,000 and up to 3 million consulting services) National request for quotation Up to 100,000 (goods/works) Open international (works) >40 million Open national (works) >100,000 and up to 40 million Direct selection No threshold; For goods/works/non-consulting services: According to paragraphs 6.8–6.10 of the Regulations; For consultants: According to paragraphs 7.13–7.15 of the Regulations Framework Agreements For goods, works, and non-consulting services: According to paragraphs 6.57–6.59 of the Regulations Shortlist of national consultants Up to 800,000 1. Procurement prior-review thresholds based on the Moderate rating. The World Bank requires its prior review of the following types of contract: (a) Works: All contracts more than US$15 million equivalent (b) Goods and IT: All contracts more than US$4 million equivalent (c) Non-consulting services: All contracts more than US$4 million equivalent (d) Consultants: All contracts more than US$2 million equivalent for firms and US$400,000 equivalent for individuals (e) Direct selection: Justification of DS for all contracts more than US$100,000 equivalent 2. National procurement procedure conditions. National competition for the procurement of goods, works, and non-consulting services will be within the thresholds and will comply with the Procurement Provisions of paragraphs 5.3–5.6 of Section V of the Regulations and the following additional provisions: (a) Only the model bidding documents agreed with the World Bank (as amended from time to time) will be used for bidding. (b) At least 30 days before the deadline for submission of bids, invitations to bid will be advertised in at least one widely circulated national daily newspaper, or on a widely-used website or electronic portal with free national and international access inan abridged version of the advertisement published in a widely circulated national daily, giving details of the electronic portal where the full invitation to bid can be downloaded. (c) No preference will be accorded to any bidder for price or for other terms when competing with foreign bidders, state-owned enterprises, small- scale enterprises, or enterprises from a given state. (d) Extension of bid validity will not be allowed for contracts subject to World Bank prior review without prior World Bank concurrence (i) for the first request for an extension longer than four weeks and (ii) for all subsequent requests for extension whatever the length; concurrence will be considered only in cases of force majeure and other circumstances beyond the control of the purchaser employer. (e) There will be no re-bidding of contracts subject to World Bank prior review without prior World Bank concurrence. In this project, bids will not be rejected for being outside a predetermined range of prices. (f) To improve the efficiency and transparency of small-value purchases in WB-financed projects, the Bank has agreed to allow the following uses of Government e-Marketplace (GeM): (i) in lieu of shopping, up to US$30,000 in catalog mode; (ii) in lieu of shopping, up to US$100,000 if there are at least three suppliers for the item on GeM and the purchaser uses the GeM Request for Quotation feature (mini-competition) to discover the final price; (iii) in both cases, borrowers will record their assessment that the price is reasonable, and (iv) GeM is not to be used in lieu of National Competitive Bidding. (g) No negotiations are to be conducted even with the lowest evaluated responsive bidders. Domestic preference. Domestic preference will be applied in evaluating bids in accordance with Annex VI of the Regulations. PROCUREMENT India : AP Integrated Irrigation & Agriculture Transformation Project PLAN General Information Country: India 2019-01-09 Bank’s Approval Date of the Original Procurement Plan: 2023-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160463 GPN Date: Project Name: AP Integrated Irrigation & Agriculture Transformation Project Loan / Credit No: IBRD / 89100 Andhra Pradesh Ground Water and Water Audit Department Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-APGWWAD-93500-CW-DI R / Procurement of Drilling of Component A: Improving Irri 2019-03-2 Piezometers in Kurnool Distri IBRD / 89100 Post Direct Selection Direct 12,857.14 0.00 Canceled 2019-01-02 2019-01-07 2019-02-04 gated Agriculture Efficiency 2 ct. This procurement is to be carried out on District collect ors Rate contract for drilling. IN-APGWWAD-93503-CW-DI R / Procurement of Drilling of Piezometers in Vizayanagara Component A: Improving Irri 2019-03-2 IBRD / 89100 Post Direct Selection Direct 42,900.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-04 m. This procurement is to be gated Agriculture Efficiency 2 carried out on District collect ors Rate contract for drilling. IN-APGWWAD-93505-CW-DI R / Procurement of Drilling of Component A: Improving Irri 2019-03-2 Piezometers in Kadapa Distri IBRD / 89100 Post Direct Selection Direct 9,286.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-04 gated Agriculture Efficiency 2 ct. This procurement is to be carried out on District collect ors Rate contract for drilling. IN-APGWWAD-93551-CW-DI R / Procurement of drilling of piezometers in West Godavar Component A: Improving Irri Pending Imp 2019-03-2 IBRD / 89100 Post Direct Selection Direct 57,807.00 0.00 2019-01-03 2019-01-08 2019-02-05 i District. This procurement is gated Agriculture Efficiency lementation 2 to be carried out on District c ollectors Rate contract for dri lling. IN-APGWWAD-126602-CW-DI R / Procurement of drilling of Component A: Improving Irri Pending Imp 2020-03-2 piezometers in srikakulam di IBRD / 89100 Post Direct Selection Direct 11,538.20 0.00 2019-08-19 2019-08-24 2019-09-28 gated Agriculture Efficiency lementation 6 strict.This procurement is to be carried out District Collect or rate contract for drilling. IN-APGWWAD-126608-CW-DI R / Procurement of drilling of piezometers in Visakhapatna Component A: Improving Irri Pending Imp 2020-03-2 IBRD / 89100 Post Direct Selection Direct 5,165.80 0.00 2019-08-20 2019-08-25 2019-09-29 m district. This procurement i gated Agriculture Efficiency lementation 7 s to be carried out on District Collector rate contract for dr illing IN-APGWWAD-126610-CW-DI R / Procurement of drilling of piezometers in East Godavari Component A: Improving Irri Pending Imp 2020-03-2 IBRD / 89100 Post Direct Selection Direct 15,093.50 0.00 2019-08-19 2019-08-24 2019-09-28 district. This procurement is t gated Agriculture Efficiency lementation 6 o be carried out on District C ollector rate contract for drilli ng IN-APGWWAD-126611-CW-DI R / Procurement of drilling of Component A: Improving Irri Pending Imp 2020-03-2 piezometers in Prakasam dist IBRD / 89100 Post Direct Selection Direct 28,461.00 0.00 2019-08-19 2019-08-24 2019-09-28 gated Agriculture Efficiency lementation 6 rict. This procurement is to b e carried out on District Colle ctor rate contract for drilling IN-APGWWAD-126612-CW-DI R / Procurement of drilling of Component A: Improving Irri Pending Imp 2020-03-2 piezometers in Nellore distric IBRD / 89100 Post Direct Selection Direct 9,009.74 0.00 2019-08-19 2019-08-24 2019-09-28 gated Agriculture Efficiency lementation 6 t. This procurement is to be c arried out on District Collecto r rate contract for drilling IN-APGWWAD-126613-CW-DI R / Procurement of drilling of Component A: Improving Irri Pending Imp 2021-03-1 5 nos piezometers in Chittoo IBRD / 89100 Post Direct Selection Direct 9,248.00 0.00 2021-01-18 2021-01-25 2021-03-01 gated Agriculture Efficiency lementation 5 r district. This procurement is to be carried out on District C ollector rate contract. IN-APGWWAD-240950-CW-DI R / Drilling of 08 piezometers Request for Quota in Visakhapatnam district thr tions - Small Work Component A: Improving Irri Pending Imp 2021-09-2 ough the direct selection pro IBRD / 89100 Post Direct Selection Direct s (Emergency) SP 7,402.40 0.00 2021-06-23 2021-06-28 2021-07-26 gated Agriculture Efficiency lementation 4 curement methode by adopti D -Non Competiti ng district collector approval ve rates. (District Collector Rate Contract) IN-APGWWAD-240955-CW-DI R / Procurement of 04 piezo Request for Quota meter in East Godavari Distri tions - Small Work Component A: Improving Irri Pending Imp 2021-09-2 ct through the direct selectio IBRD / 89100 Post Direct Selection Direct s (Emergency) SP 2,534.82 0.00 2021-06-23 2021-06-28 2021-07-26 gated Agriculture Efficiency lementation 4 n procurement methode by a D -Non Competiti dopting District Collector Rat ve e contract (District Collector Approved Rates) IN-APGWWAD-241705-CW-R FQ / Procurement of Drilling of 20 piezometers through R FQ under national shopping p Request for Quota Component A: Improving Irri Request for Quota Single Stage - One E Pending Imp 2022-03-0 rocedures from registered Ri IBRD / 89100 Post Limited tions (Non Bank-S 16,614.74 0.00 2021-07-13 2021-09-07 gated Agriculture Efficiency tions nvelope lementation 6 gs under APWALTA by adopti PD) ng Common Schedule Rates ( SoR) which was approved by Govt of AP in srikakulam distr ict are submitting for approv al. Page 1 IN-APGWWAD-241883-CW-R FQ / Procurement of Drilling of 22 piezometers through R FQ under national shopping p Request for Quota Component A: Improving Irri Request for Quota Single Stage - One E Pending Imp 2022-03-0 rocedures from the registere IBRD / 89100 Post Limited tions (Non Bank-S 22,600.66 0.00 2021-07-13 2021-09-07 gated Agriculture Efficiency tions nvelope lementation 6 d Rigs under APWALTA by ad PD) opting Common Schedule Ra tes (SoR) which was approve d by Govt of AP in Vizainagar am district are submitting for approval. IN-APGWWAD-241893-CW-R FQ / Procurement of Drilling of 05 piezometers through R FQ under national shopping p Request for Quota Component A: Improving Irri Request for Quota Single Stage - One E 2022-03-0 rocedures from the registere IBRD / 89100 Post Limited tions (Non Bank-S 7,621.03 0.00 Canceled 2021-07-13 2021-09-07 gated Agriculture Efficiency tions nvelope 6 d Rigs under APWALTA by ad PD) opting Common Schedule Ra tes (SoR) which was approve d by Govt of AP in Prakasam district are submitting for ap proval. IN-APGWWAD-241897-CW-R FQ / Procurement of Drilling of 29 piezometers through R FQ under national shopping p Request for Quota Component A: Improving Irri Request for Quota Single Stage - One E Pending Imp 2022-03-0 rocedures from the registere IBRD / 89100 Post Limited tions (Non Bank-S 35,176.03 0.00 2021-07-13 2021-09-07 gated Agriculture Efficiency tions nvelope lementation 6 d Rigs under APWALTA by ad PD) opting Common Schedule Ra tes (SoR) which was approve d by Govt of AP in Nellore dis trict are submitting for appro val. IN-APGWWAD-241905-CW-R FQ / Procurement of Drilling of 05 piezometers through R FQ under national shopping p Request for Quota Component A: Improving Irri Request for Quota Single Stage - One E 2022-03-0 rocedures from the registere IBRD / 89100 Post Limited tions (Non Bank-S 7,532.55 0.00 Canceled 2021-07-13 2021-09-07 gated Agriculture Efficiency tions nvelope 6 d Rigs under APWALTA by ad PD) opting Common Schedule Ra tes (SoR) which was approve d by Govt of AP in Chittoor di strict are submitting for appr oval. IN-APGWWAD-241908-CW-R FQ / Procurement of Drilling of 05 piezometers through R FQ under national shopping p Request for Quota Component A: Improving Irri Request for Quota Single Stage - One E 2022-03-0 rocedures from the registere IBRD / 89100 Post Limited tions (Non Bank-S 7,286.76 0.00 Canceled 2021-07-13 2021-09-07 gated Agriculture Efficiency tions nvelope 6 d Rigs under APWALTA by ad PD) opting Common Schedule Ra tes (SoR) which was approve d by Govt of AP in Anantapur amu district are submitting f or approval. IN-APGWWAD-241909-CW-R FQ / Procurement of Drilling of 17 piezometers through R FQ under national shopping p Request for Quota Component A: Improving Irri Request for Quota Single Stage - One E Pending Imp 2022-03-0 rocedures from the registere IBRD / 89100 Post Limited tions (Non Bank-S 26,039.85 0.00 2021-07-13 2021-09-07 gated Agriculture Efficiency tions nvelope lementation 6 d Rigs under APWALTA by ad PD) opting Common Schedule Ra tes (SoR) which was approve d by Govt of AP in Kurnool di strict are submitting for appr oval. IN-APGWWAD-244607-CW-R FQ / Procurement of Drilling of 25 piezometers through R equest for Quotation under s Request for Quota Component A: Improving Irri Request for Quota Single Stage - One E Pending Imp 2022-03-1 hopping procedures (RFQ) by IBRD / 89100 Post Limited tions (Non Bank-S 38,068.79 0.00 2021-08-07 2021-09-18 gated Agriculture Efficiency tions nvelope lementation 7 adopting Common Schedule PD) Rates (SoR) which was appro ved by Government of Andhr a Pradesh in Visakhapatnam district are submitting for ap proval. IN-APGWWAD-272300-CW-R FQ / Procurement of drilling o f 6 piezometers in Visakhapa tnam district through RFQ fro Component A: Improving Irri Request for Quota Single Stage - One E Other (with field f Pending Imp 2022-02-2 IBRD / 89100 Post Limited 5,566.49 0.00 2022-01-18 2022-02-11 m registered Rigs under APW gated Agriculture Efficiency tions nvelope or explanation) lementation 8 ALTA by adopting Common S chedule of Rates (SoR) which is approved by Govt. of AP an d submitting for approval. IN-APGWWAD-272323-CW-R FQ / Procurement of drilling o f 29 piezometers in Prakasha m district through Request F Component A: Improving Irri Request for Quota Single Stage - One E Other (with field f Pending Imp 2022-03-0 IBRD / 89100 Post Limited 43,512.74 0.00 2022-01-18 2022-02-11 or Quotation from registered gated Agriculture Efficiency tions nvelope or explanation) lementation 4 Rigs under APWALTA by adop ting common Schedule of Rat es (SoR) which is approved b y Govt.of AP are submitting f or approval . IN-APGWWAD-272328-CW-R FQ / Procurement of drilling o f 13 piezometers in Chittoor district through Request For Component A: Improving Irri Request for Quota Single Stage - One E Other (with field f 2022-02-2 IBRD / 89100 Post Limited 19,884.40 0.00 Canceled 2022-01-18 2022-02-11 Quotation from registered rig gated Agriculture Efficiency tions nvelope or explanation) 8 s under APWALTA by adoptin g common Schedule of Rates (SoR) which is approved by G ovt. of AP are submitting for approval. IN-APGWWAD-272338-CW-R FQ / procurement of drilling o f 16 piezometers in Kadapa d istrict through RFQ from regi Component A: Improving Irri Request for Quota Single Stage - One E Other (with field f 2022-02-2 IBRD / 89100 Post Limited 21,753.40 0.00 Canceled 2022-01-18 2022-02-11 stered rigs under APWALTA b gated Agriculture Efficiency tions nvelope or explanation) 8 y adopting common schedule of rates (SoR) which is appro ved by govt. of AP are submit ting for approval. IN-APGWWAD-293028-CW-R FQ / Procurement of Drilling of 04 piezometers in Ananta puram district through RFQ Request for Quota Component A: Improving Irri Request for Quota Single Stage - One E 2022-05-2 under shopping procedures fr IBRD / 89100 Post Limited tions (Non Bank-S 6,041.82 0.00 Canceled 2022-05-04 2022-05-12 gated Agriculture Efficiency tions nvelope 7 om the registered Rigs under PD) APWALTA by adopting Comm on Schedule of Rates (SoR) w hich was approved by Govt o f AP is submitting for approval. Page 2 IN-APGWWAD-347127-CW-R FQ / In the newly formed Ana ntapur District 09 Locations a Request for Quota re selected for drilling of Piez Component A: Improving Irri Request for Quota Single Stage - One E Pending Imp 2023-05-2 IBRD / 89100 Post Limited tions (Non Bank-S 11,706.05 0.00 2023-04-06 2023-04-25 ometers to install Digital wat gated Agriculture Efficiency tions nvelope lementation 5 PD) er level Recorders in piezom eters to conduct monitoring of Depth to Groundwater lev els to arrive at water product ivity & efficiency. IN-APGWWAD-347227-CW-R FQ / Procurement of Drilling of 06 piezometers( Fresh site s) in the NTR district through Request for Quota Component A: Improving Irri Request for Quota Single Stage - One E Pending Imp 2023-05-2 RFQ in shopping procedures f IBRD / 89100 Post Limited tions (Non Bank-S 7,042.83 0.00 2023-04-03 2023-04-25 gated Agriculture Efficiency tions nvelope lementation 5 rom the registered Rigs unde PD) r APWALTA by adopting Com mon Schedule of Rates (SoR) which was approved by Govt of AP is submitted for approv al. IN-APGWWAD-93501-CW-DI R / Procurement of Drilling of Component A: Improving Irri Other (with field f Pending Imp 2019-03-2 Piezometers in Krishna Distri IBRD / 89100 Post Direct Selection Direct - National 23,186.00 0.00 2019-01-02 2019-01-07 2019-02-04 gated Agriculture Efficiency or explanation) lementation 2 ct. This procurement is to be carried out on District collect ors Rate contract for drilling. IN-APGWWAD-241891-CW-R FQ / Procurement of Drilling of 22 piezometers through R FQ under national shopping p Request for Quota Component A: Improving Irri Request for Quota Single Stage - One E Pending Imp 2022-03-0 rocedures from the registere IBRD / 89100 Post Limited tions (Non Bank-S 28,215.18 0.00 2021-07-13 2021-09-07 gated Agriculture Efficiency tions nvelope lementation 6 d Rigs under APWALTA by ad PD) opting Common Schedule Ra tes (SoR) which was approve d by Govt of AP in Krishna dis trict are submitting for appro val. IN-APGWWAD-93499-CW-DI R / procurement of Drilling of Piezometers in Anantapur dis Component A: Improving Irri Other (with field f Pending Imp 2019-03-2 IBRD / 89100 Post Direct Selection Direct - National 15,729.00 0.00 2019-01-02 2019-01-07 2019-02-04 trict. This procurement is to gated Agriculture Efficiency or explanation) lementation 2 be carried out on District coll ectors Rate contract for drilli ng. IN-APGWWAD-353482-CW-R FQ / Procurement of Drilling of 10 piezometers through R FQ under national shopping p Request for Quota Component A: Improving Irri Request for Quota Single Stage - One E Pending Imp 2023-06-0 rocedures from the registere IBRD / 89100 Post Limited tions (Non Bank-S 16,661.54 0.00 2023-04-17 2023-05-10 gated Agriculture Efficiency tions nvelope lementation 9 d Rigs under APWALTA by ad PD) opting Common Schedule of Rates (SoR) which has appro ved by Govt of AP in Annama iah District is submitting for a pproval. IN-APGWWAD-353667-CW-R FQ / Procurement of Drilling of Eight piezometers through RFQ under national shopping Request for Quota Component A: Improving Irri Request for Quota Single Stage - One E Pending Imp 2023-05-2 procedures from the register IBRD / 89100 Post Limited tions (Non Bank-S 12,635.41 0.00 2023-04-10 2023-04-28 gated Agriculture Efficiency tions nvelope lementation 9 ed Rigs under APWALTA by a PD) dopting Common Schedule of Rates(SoR) which has approv ed by AP Govt in Chithoor Di strict is submitting for approv al. IN-APGWWAD-354729-CW-R FQ / Procurement of Drilling of 03 piezometers through R FQ under national shopping p Request for Quota Component A: Improving Irri Request for Quota Single Stage - One E Pending Imp 2023-06-0 rocedures from the registere IBRD / 89100 Post Limited tions (Non Bank-S 4,073.03 0.00 2023-04-17 2023-05-09 gated Agriculture Efficiency tions nvelope lementation 8 d Rigs under APWALTA by ad PD) opting Common Schedule of Rates(SoR)which has approv ed by Govt of AP in Visakhap atnam District is submitted f or approval. IN-APGWWAD-354747-CW-R FQ / Procurement of Drilling of 01 piezometer through RF Q under national shopping pr Request for Quota Component A: Improving Irri Request for Quota Single Stage - One E Pending Imp 2023-06-1 ocedures from the registered IBRD / 89100 Post Limited tions (Non Bank-S 723.54 0.00 2023-04-18 2023-05-09 gated Agriculture Efficiency tions nvelope lementation 2 Rigs under APWALTA by adop PD) ting Common Schedule of Ra tes(SoR)which has been appr oved by Govt of AP in Bapatl a District is submitted for ap proval. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-APGWWAD-87896-GO-RF Q / Procurement of groundwa ter modelling software like G Component A: Improving Irri Request for Quota Single Stage - One E IBRD / 89100 Post Open - National 71,429.00 0.00 Canceled 2019-01-07 2019-03-04 2019-03-29 W Flow modelling software Vi gated Agriculture Efficiency tions nvelope stas6, Rockworks 17, Aquifer test pro 2015.1, Visual Modfl ow flex-2015.2, Aquachem 2 015.1. IN-APGWWAD-93496-GO-RF Q / Procurement of PHM Equi pment i.e. Measuring Tapes Component A: Improving Irri Request for Quota Single Stage - One E 30m- 1285 Numbers , 50m-4 IBRD / 89100 Post Open - National 44,364.92 0.00 Canceled 2019-01-07 2019-02-25 2019-03-22 gated Agriculture Efficiency tions nvelope 75 Numbers, 100m-27 Numb ers, Stop watches-810 and 1 00ltr Plastic Drums for water yield measurements -810 for 405 tanks. IN-APGWWAD-204049-GO-R FQ / Procurement of Chemica l Consumables and Glasswar e for 5 Chemical labs of Grou Component A: Improving Irri Request for Quota Single Stage - One E Pending Impl nd Water and Water Audit De IBRD / 89100 Post Open - National 11,502.52 0.00 2021-01-18 2021-02-19 2021-03-13 gated Agriculture Efficiency tions nvelope ementation partment of Andhra Pradesh . They are 1.Vijayawada, 2. Vi sakhapatnam, 3. dowaleswaram of East Go davari, 4.Kurnool, 5.Kadapa . Page 3 IN-APGWWAD-204056-GO-R FQ / Procurement of chemica l equipment for strengthenin g of 05 labs of Groundwater Component A: Improving Irri Request for Quota Single Stage - One E IBRD / 89100 Post Open - National 56,104.30 0.00 Canceled 2021-01-18 2021-02-19 2021-03-12 and water audit department gated Agriculture Efficiency tions nvelope of Andhra pradesh. thees lab s are located at Visakhapatn am, Dawaleswaram of East G odavari, Kadapa, Kurnool and Vijayawada. IN-APGWWAD-211814-GO-R FQ / Procurement of Ultrasoni c Flow Meter(Portable Hand h Component A: Improving Irri Request for Quota Single Stage - One E eld Clamp On) for measurem IBRD / 89100 Post Open - National 56,194.79 0.00 Canceled 2021-01-18 2021-02-22 2021-03-15 gated Agriculture Efficiency tions nvelope ent of yields of bore wells in the tanks ayacut as part of PHM equipment for 12 distri cts and head office of Andhra Pradesh. IN-APGWWAD-245125-GO-R FQ / Procurement of Ultrasoni c Flow Meter (Portable and H Component A: Improving Irri Request for Quota Single Stage - One E Pending Impl IBRD / 89100 Post Limited 56,194.79 0.00 2021-08-03 2021-09-07 2022-03-06 and held ) through RFQ unde gated Agriculture Efficiency tions nvelope ementation r shopping procedures by m anual tendering are submitte d for approval. IN-APGWWAD-245128-GO-R FQ / Procurement of PHM Equ ipment i.e.Freemens Measuri ng tapes 30m, 50m and 100 Component A: Improving Irri Request for Quota Single Stage - One E m length with 10 cm GI Hollo IBRD / 89100 Post Limited 34,582.87 0.00 Canceled 2021-08-09 2021-09-13 2022-03-12 gated Agriculture Efficiency tions nvelope w pipe attached at the end, P lastic drum 100 Lts. and Stop Watch through RFQ under s hopping procedures by man ual tendering are submitting for approval IN-APGWWAD-250470-GO-R FQ / Procurement for supply of Split Beam / Reference Be am UV-Visible Spectrophoto Component A: Improving Irri Request for Quota Single Stage - One E Pending Impl IBRD / 89100 Post Open - National 81,441.72 0.00 2021-12-28 2022-01-28 2022-02-12 meter through Request For Q gated Agriculture Efficiency tions nvelope ementation uotation (RFQ) (Manual Procu rement Tendering Process) fo r strengthening of 05 Chemi cal Labs is submitted for app roval. IN-APGWWAD-276791-GO-R FQ / Procurement of PHM Equ ipment i.e Freemans Measuri ng Tapes 30m, 50M length wi Component A: Improving Irri Request for Quota Single Stage - One E Pending Impl IBRD / 89100 Post Limited 29,539.88 0.00 2022-02-15 2022-02-27 2022-03-09 th 10cm GI hallow pipe attac gated Agriculture Efficiency tions nvelope ementation hed at the end ,open top plas tic drums and Stopwatches u nder Shopping Procedure is s ubmitting for approval. IN-APGWWAD-282173-GO-R FQ / Procurement of chemica ls under chemical consumabl es is proposed for 05 water q Component A: Improving Irri Request for Quota Single Stage - One E Pending Impl uality labs located at Vishaka IBRD / 89100 Post Limited 6,058.28 0.00 2022-03-14 2022-03-24 2022-03-29 gated Agriculture Efficiency tions nvelope ementation patnam,Dowleswaram,Kadap a,Kurnool and Vijayawada for water samples analysis unde r shopping procedure and su bmitting for approval IN-APGWWAD-283086-GO-R FQ / Procurement of PVC pipe s for water sharing under sho pping procedure at Krishna di Component A: Improving Irri Request for Quota Single Stage - One E Pending Impl IBRD / 89100 Post Limited 9,471.81 0.00 2022-03-14 2022-03-24 2022-03-29 strict level is proposed to pro gated Agriculture Efficiency tions nvelope ementation vide PVC pipes for water shar ing for 05 tanks to irrigate an additional area of 33.4 acres in ayacut and submitted for a pproval IN-APGWWAD-244604-GO-R FQ / Procurement of Work sta tions, Desktop computers, All in One Printer- Xerox - Scann Component A: Improving Irri Request for Quota Single Stage - One E IBRD / 89100 Post Limited 38,343.56 0.00 Canceled 2021-08-02 2021-09-03 2021-11-02 er, Printer - Color Inkjet, Hard gated Agriculture Efficiency tions nvelope disks and Laptops through RF Q under shopping procedure s by manual tendering are su bmitted for approval. IN-APGWWAD-326747-GO-R FQ / IN-APGWWAD-326747-G O-RFQ / Procurement of Desk top computers, All in One Pri Component A: Improving Irri Request for Quota Single Stage - One E Pending Impl IBRD / 89100 Post Limited 59,509.20 0.00 2022-12-19 2023-01-17 2023-02-16 nter- Copier - Scanner, Printe gated Agriculture Efficiency tions nvelope ementation r -Inktank, Hard disks and La ptops through RFQ under sho pping procedures by manual tendering are submitted for a pproval. IN-APGWWAD-335559-GO-R FB / Procurement of Hundred Digital Water Level Recorder s for installation in Piezomet Component A: Improving Irri Single Stage - Two E Pending Impl IBRD / 89100 Post Request for Bids Open - National 184,049.07 0.00 2023-01-25 2023-01-30 2023-03-13 2023-05-26 2023-06-30 2023-09-28 ers to measure depth to grou gated Agriculture Efficiency nvelope ementation nd water levels, with Telemet ry system including Required Accessories for data transmis sion through RTDA System IN-APGWWAD-335685-GO-R FB / Procurement of hundred number of smart ultra sonic F low meters (Fixed type) with Component A: Improving Irri Single Stage - Two E Pending Impl Telemetry and required Acce IBRD / 89100 Post Request for Bids Open - National 230,061.34 0.00 2023-01-30 2023-02-04 2023-03-18 2023-05-31 2023-07-05 2023-11-02 gated Agriculture Efficiency nvelope ementation ssories. these flow meters m ay have to be installed in the bore wells to find out water y ields of the Bore wells from g round water regime. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Page 4 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 5 The United Republic of Tanzania Procurement Plan for Project Preparation Advance Activities General 1. Project Information Country: The United Republic of Tanzania Project Name: Land Tenure Improvement Project (LTIP) Project ID: P164906 2. Project Implementation Agency: Ministry of Lands, Housing and Human Settlements Development 3. Date of the Procurement Plan: 11/10/2018 4. Period Covered by this procurement plan: 06 months I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. III. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in The Public Procurement Act, 2011, The Public Procurement (Amendment) Act, 2016 and the Regulations, 2016, such arrangements shall be subject to paragraph 5.3 and 5.4 of the Procurement Regulations and the following conditions: o There should be no mandatory requirements for inclusion of local experts and firms for the consulting assignments; 1 o There should be no exclusive preference based on threshold prescribed in PPA and its Regulations; o Negotiations with the lowest evaluated bidder to reduce price in the case of goods, works and non-consulting services where competitive methods have been used shall not be allowed; o The fixed budget method shall not be used for goods, works and non- consulting services; o Established and approved procurement standards by the government may be used, provided that they are not restrictive When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.53 of the Procurement Regulations. In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. IV. Prequalification: Not Applicable V. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable VI. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable VII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Domestic preference is not applicable for National Open Competitive Procurement VIII. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Not Applicable IX. Other Relevant Procurement Information Not Applicable 2 3 X. Threshold for Prior Review, Procurement Approaches and Methods – Good, Works and Non- Consulting Services Procurement Approaches and Methods (US$ millions) Prior Review Category Open Open Request for (US$ millions) International National Quotation (RfQ) Works ≥5 ≥ 15 <15 ≤ 0.2 Goods, IT, and non-consulting ≥ 1.5 ≥5 <5 ≤ 0.1 services Post Review: All contracts not subject to prior review shall be subject to post review. Summary of the procurement packages for Good, Works and Non-Consulting Services Sr. Contract Estim Revie Market Selection Evaluati Procurem Prequ Domes Expect Expect No Description ated w by Approac Method on ent alifica tic ed ed date Cost Bank h (Open- (RFP, Options Process tion Prefer date of (US$) (Prio National/ RFB, (Most (Single (Yes/ ence of bid/ Contra r/ Limited RFQ, DS Advanta stage- No) (Yes/N propo ct Post) etc.) etc.) geous single o) sal Signat Bid, envelope openin ure BAFO, etc.) g Rated Criteria etc.) GOODS Total Goods WORKS Total works NON-CONSULTING SERVICES 4 Total Non- Consulting Services XI. Thresholds for Prior Review, Selection Approaches and Methods – Consulting Services Category Prior Review Short List of National Consultants (US$ millions) Consulting Engineering and Construction Supervision Services Consultants (Firms) ≥ 0.5 ≤ 0.3 ≤ 0.3 Individual Consultants ≥ 0.2 n.a. n.a. Note: Consultancy services estimated to cost equivalent to US $ 300,000 and above per contract shall be advertised in the United Nations Development Business (UNDB) online in addition to advertising in national newspaper(s) of wide circulation and/or regional newspaper. XII. Summary of the procurement packages for Consulting Services Sr. No Contract Description Estimat Review Market Selection Shortlisti Expected Expected ed Cost by Approach Method ng date of bid/ date of (US$) Bank (Open - (QCBS, (Yes/ No) proposal Contract (Prior/ International FBBS, LCBS, opening Signature Post) / National/ QBS, CQS, etc.) DS etc.) 1 Consultancy Services for YesNo preparation of an Environmental 53,097 Post DSNational QBSIC and Social Management Framework 2 Consultancy Services for IC YesNo preparation of Social Assessment 22,555 Post DS for Land Tenure Improvement Project 3 Preparation of theA Resettlement IC YesYes Policy Framework (Rpf) for The 6,336 Post DS Land Tenure Improvement Project 4 Provision of Consultancy IC No 83,935 Post Open-National Services for Technical Adviser 5 for Preparations of Land Tenure Improvement Project 5 Consultancy Services for IC Commented [RJM1]: Going by the scope, the Preparation of Terms of estimated amount is on the higher side. References and RFP for selecting Post Open-National YesNo Consultant for design, and 80,000 Supervision of construction of ILMIS compliant Zonal, Municipal and District Office Buildings 6 Consultancy Services for Post Open- IC YesNo preparation of Terms of National References and RFP for selecting a consultant for design, Implementationse. of Upgrading 58,500 and Enhancement and Assessment of ICT infrastructure and Data Conversion Requirement 7 Consultancy Services for Post Open - IC YesNo Preparation of Terms of National References and Bid documents 48,100 for procurement of ortho photo and Base Maps 8 Consultancy Services for review Post Open- IC YesNo of specifications and assist in National tender process and preparation of Bid documents for the detailed 48,100 design and establishment of Continuously Operating Reference Station (CORS) 9 Consultancy Services for Post Open - CQS No preparation of detailed work National arrangement for mass registration in urban areas 54,600 including preparation of implementation guidelines, terms of reference and Bid documents 10 Consultancy Services for Review Post Open - CQS No of specification and statement of National requirements for Valuation 61,750 Functions and preparation of terms of reference and Bid 6 documents for developing ILMIS compliant Land Value Maps 11 Consultancy Services for Review Post Open - IC YesNo. and preparation of Terms of National References and RFP to procure 32,500 Consultancy Services to review prepare or update and harmonize land-related policies and laws. 12 Consultancy Services for Post Open - 195,000 QCBSCQS NoNo conducting baseline survey. National Total Consulting Services 774,473 7 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti- Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non- responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 8 contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub- agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. 2For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 9 Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 10 PROCUREMENT Tanzania : Land Tenure Improvement Project PLAN General Information Country: Tanzania 2019-05-10 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164906 GPN Date: 2022-03-31 Project Name: Land Tenure Improvement Project Loan / Credit No: / , IDA / 70220 Ministry of Lands, Housing and Human Settlements Development Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MLHHSD-288016-GO-RFQ Component 4: Project mana Single Stage - One E Under Imple / Supply of office furniture for IDA / 70220 Post Request for Bids Limited 0.00 2022-04-20 2022-05-25 2022-04-25 2022-05-25 2022-06-06 2022-06-13 2022-07-06 2022-06-17 2022-08-10 2023-02-06 gement nvelope mentation Project Implementation Team (PIT) TZ-MLHHSD-288019-GO-RFQ / Procurement of computers, Component 4: Project mana Request for Quota Single Stage - One E IDA / 70220 Post Limited 0.00 Signed 2022-04-25 2022-08-12 2022-06-20 2022-12-17 scanners, printers and photo gement tions nvelope copiers for Project Implement ation Team (PIT) TZ-MLHHSD-300017-GO-RFB / Procurement of ICT Equipm ent for Upscaling ILMIS phase II (Server, Storage, San Switc Component 2: Land Informa Single Stage - One E Under Imple h, Core Switch, IP PBX, Lapto IDA / 70220 Post Request for Bids Open - National 0.00 2022-06-26 2022-12-22 2022-07-01 2022-12-22 2022-08-12 2022-09-11 2022-10-02 2022-12-04 tion Management nvelope mentation ps, Security Software Packag es, Security Information and Event Management, Databas e Activity Monitor and Encryp tion PGP Desktop) TZ-MLHHSD-319426-GO-RFQ Component 3: Physical Deve Request for Quota Single Stage - One E / Supply of electronic equipm IDA / 70220 lopment of Land Administrat Post Limited 0.00 Signed 2022-10-17 2022-11-16 2022-11-28 2023-02-17 tions nvelope ent for communication and p ion System ublication TZ-MLHHSD-322879-GO-RFB / Procurement of ICT and offi Component 1: Increased Te Single Stage - One E Under Imple ce equipment for Direct Oper IDA / 70220 Post Request for Bids Open - National 0.00 2022-11-28 2023-03-28 2022-12-03 2023-03-29 2023-01-14 2023-02-13 2023-03-20 2023-05-04 nure Security nvelope mentation ation teams, LUFP, DLHT and ICT development team. TZ-MLHHSD-325949-GO-DIR Component 1: Increased Te Direct - Internation IDA / 70220 Post Direct Selection 0.00 Signed 2022-11-28 2023-03-06 2022-12-03 2023-03-08 2023-01-07 2023-07-06 / Procurement of FWD Motor nure Security al Vehicle TZ-MLHHSD-325955-GO-RFB / Procurement of 15 units of Component 1: Increased Te Single Stage - One E Under Imple IDA / 70220 Post Request for Bids Open - National 0.00 2022-11-28 2022-12-22 2022-12-03 2022-12-22 2023-01-14 2023-02-13 2023-03-20 2023-09-16 GNSS GPS Receiver and 50 u nure Security nvelope mentation nits of GNSS Tablets TZ-MLHHSD-322867-GO-RFQ / Supply of technical office su Component 1: Increased Te Request for Quota Single Stage - One E Pending Impl pplies for planning and surve IDA / 70220 Post Limited 0.00 2022-12-23 2023-02-17 2023-08-16 nure Security tions nvelope ementation ys - drafting film, drawing pe ns, tracing papers, Manila pa pers TZ-MLHHSD-325975-GO-RFQ / Supply of Office Stationery and Consumables for the Pre Component 1: Increased Te Request for Quota Single Stage - One E Pending Impl IDA / 70220 Post Limited 0.00 2022-12-24 2023-02-18 2023-08-17 paration of the District Land nure Security tions nvelope ementation Use Framework Plan, CCRO T raining manuals, and Support to DLHT offices. TZ-MLHHSD-322880-GO-RFB Component 3: Physical Deve Single Stage - One E Pending Impl / Supply of Office furniture fo IDA / 70220 lopment of Land Administrat Post Request for Bids Open - National 0.00 2023-02-21 2023-02-26 2023-03-19 2023-04-18 2023-05-23 2023-11-19 nvelope ementation r District Land and Housing T ion System ribunals offices TZ-MLHHSD-300019-GO-RFQ Component 2: Land Informa Request for Quota Single Stage - One E / Procurement of ICT Equipm IDA / 70220 Post Limited 0.00 Canceled 2022-07-01 2023-03-08 2022-08-12 2022-09-30 tion Management tions nvelope ent for Upscaling ILMIS phase II ( Laptops) TZ-MLHHSD-358311-GO-RFQ Component 2: Land Informa Request for Quota Single Stage - One E Pending Impl / Procurement of ICT Equipm IDA / 70220 Post Open - National 0.00 2023-05-07 2023-07-02 2023-12-29 tion Management tions nvelope ementation ent for Upscaling ILMIS phase II ( Laptops) TZ-MLHHSD-364776-GO-RFB Component 1: Increased Te Single Stage - One E Pending Impl / Procurement of 100 units of IDA / 70220 Post Request for Bids Open - National 0.00 2023-07-03 2023-07-08 2023-08-19 2023-09-18 2023-10-23 2024-04-20 nure Security nvelope ementation GNSS Tablets NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MLHHSD-358294-NC-RFB / Establishment of Continuou Component 2: Land Informa Open - Internationa Single Stage - One E Under Imple sly Operating Reference Stati IDA / 70220 Prior Request for Bids 0.00 2023-05-02 2023-06-28 2023-05-07 2023-06-18 2023-07-18 2023-08-22 2026-08-06 tion Management l nvelope mentation ons Network (CORS) for Land Administration Sector of Tanz ania TZ-MLHHSD-358306-NC-DIR / Procurement of Internet Ser Component 4: Project mana Pending Impl IDA / 70220 Post Direct Selection Direct - National 0.00 2023-05-09 2023-05-14 2023-06-18 2024-06-17 vice Provider for Land Tenure gement ementation Improvement Project (LTIP) o ffice CONSULTING FIRMS Page 1 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MLHHSD-309789-CS-CQS Component 3: Physical Deve / Provision of Consultancy ser Consultant Qualifi Under Implement IDA / 70220 lopment of Land Administrat Post Open - National 0.00 2022-10-12 2022-10-18 2022-10-26 2022-10-24 2022-11-16 2022-11-30 2022-12-28 2023-05-02 vices for development of Co cation Selection ation ion System mmunication strategy TZ-MLHHSD-322849-CS-CQS Component 1: Increased Te Consultant Qualifi Under Implement / Provision of consultancy ser IDA / 70220 Post Open - National 0.00 2022-11-27 2022-12-01 2022-12-18 2023-01-19 2023-01-31 2023-03-02 2023-04-06 2023-08-04 nure Security cation Selection ation vices for preparation of SEA f or six districts TZ-MLHHSD-319374-CS-QCB S / Provision of Consultancy S ervices to undertake Environ Component 4: Project mana Quality And Cost- Open - Internationa mental and Social Impact Ass IDA / 70220 Post 0.00 Canceled 2022-10-25 2022-10-20 2022-11-15 2022-11-01 2022-12-29 2023-01-28 2023-02-11 2023-03-11 2023-04-08 2023-08-11 gement Based Selection l essment (ESIA) for the Constr uction of Regional Land Offic es and National Archive Build ing TZ-MLHHSD-326013-CS-CQS Component 3: Physical Deve / Provision of consultancy ser Consultant Qualifi Under Implement IDA / 70220 lopment of Land Administrat Post Open - National 0.00 2022-11-28 2023-01-19 2022-12-19 2023-04-14 2023-02-01 2023-03-03 2023-04-07 2023-10-04 vices to conduct Training Ne cation Selection ation ion System eds Assessment (TNA). TZ-MLHHSD-322885-CS-QCB S / Consultancy services for Component 3: Physical Deve Design and Supervision of I Quality And Cost- Under Implement IDA / 70220 lopment of Land Administrat Post Open - National 0.00 2022-12-18 2023-01-03 2023-01-08 2023-01-19 2023-02-21 2023-03-21 2023-04-20 2023-05-25 2023-06-29 2025-07-31 LMIS office buildings in Five Based Selection ation ion System (5) Regional offices in Dodom a, Manyara, Arusha, Kilimanj aro,and Tanga Regions TZ-MLHHSD-331235-CS-CQS / Package 4: Consulting Servi ces to undertake Environmen Component 4: Project mana Consultant Qualifi Under Implement tal and Social Impact Assess IDA / 70220 Post Open - National 0.00 2022-12-20 2022-12-29 2023-01-10 2023-01-15 2023-02-23 2023-03-25 2023-04-29 2023-10-26 gement cation Selection ation ment (ESIA) for the Construct ion of Regional Land Offices i n Singida, Tabora, Shinyanga , Katavi and Kigoma. TZ-MLHHSD-331229-CS-CQS / Package 5: Consulting Servi ces to undertake Environmen Component 4: Project mana Consultant Qualifi Under Implement tal and Social Impact Assess IDA / 70220 Post Open - National 0.00 2022-12-20 2022-12-29 2023-01-10 2023-01-15 2023-02-23 2023-03-25 2023-04-29 2023-10-26 gement cation Selection ation ment (ESIA) for the Construct ion of Regional Land Offices i n Simiyu, Mara, Mwanza, Kag era and Geita. TZ-MLHHSD-322887-CS-QCB S / Consultancy services for Component 3: Physical Deve Design and Supervision of I Quality And Cost- Under Implement IDA / 70220 lopment of Land Administrat Post Open - National 0.00 2022-12-18 2023-01-03 2023-01-08 2023-01-19 2023-02-21 2023-03-21 2023-04-20 2023-05-25 2023-06-29 2025-07-31 LMIS office buildings in Five Based Selection ation ion System (5) Regional offices in Iringa, Njombe, Mbeya, Songwe and Rukwa regions. TZ-MLHHSD-322891-CS-QCB S / Consultancy services for Component 3: Physical Deve Design and Supervision of I Quality And Cost- Under Implement IDA / 70220 lopment of Land Administrat Post Open - National 0.00 2022-12-18 2023-01-03 2023-01-08 2023-01-19 2023-02-21 2023-03-21 2023-04-20 2023-05-25 2023-06-29 2025-07-31 LMIS office buildings in Five Based Selection ation ion System (5) Regional offices in Simiyu , Mara, Mwanza, Kagera and Geita regions. TZ-MLHHSD-322890-CS-QCB S / Consultancy services for Component 3: Physical Deve Design and Supervision of I Quality And Cost- Under Implement IDA / 70220 lopment of Land Administrat Post Open - National 0.00 2022-12-18 2023-01-03 2023-01-08 2023-01-19 2023-02-21 2023-03-21 2023-04-20 2023-05-25 2023-06-29 2025-07-31 LMIS office buildings in Five Based Selection ation ion System (5) Regional offices in Singid a, Tabora, Shinyanga, Katavi and Kigoma regions. TZ-MLHHSD-322888-CS-QCB S / Consultancy services for Component 3: Physical Deve Design and Supervision of I Quality And Cost- Under Implement IDA / 70220 lopment of Land Administrat Post Open - National 0.00 2022-12-18 2023-01-03 2023-01-08 2023-01-19 2023-02-21 2023-03-21 2023-04-20 2023-05-25 2023-06-29 2025-07-31 LMIS office buildings in Five Based Selection ation ion System (5) Regional offices in Morog oro, Pwani, Lindi, Mtwara and Ruvuma regions. TZ-MLHHSD-331236-CS-CQS / Package 3: Consulting Servi ces to undertake Environmen Component 4: Project mana Consultant Qualifi Under Implement tal and Social Impact Assess IDA / 70220 Post Open - National 0.00 2022-12-20 2022-12-29 2023-01-10 2023-01-15 2023-02-23 2023-03-25 2023-04-29 2023-10-26 gement cation Selection ation ment (ESIA) for the Construct ion of Regional Land Offices i n Morogoro, Coast, Lindi, Mt wara and Ruvuma. TZ-MLHHSD-331238-CS-CQS / Package 1: Consulting Servi ces to undertake Environmen tal and Social Impact Assess Component 4: Project mana Consultant Qualifi Under Implement IDA / 70220 Post Open - National 0.00 2022-12-20 2022-12-29 2023-01-10 2023-01-15 2023-02-23 2023-03-25 2023-04-29 2023-10-26 ment (ESIA) for the Construct gement cation Selection ation ion of Regional Land Offices i n Dodoma, Manyara, Arusha, Kilimanjaro, Tanga and Archi ve Building in Dodoma. TZ-MLHHSD-331237-CS-CQS / Package 2: Consulting Servi ces to undertake Environmen Component 4: Project mana Consultant Qualifi Under Implement tal and Social Impact Assess IDA / 70220 Post Open - National 0.00 2022-12-20 2022-12-29 2023-01-10 2023-01-15 2023-02-23 2023-03-25 2023-04-29 2023-10-26 gement cation Selection ation ment (ESIA) for the Construct ion of Regional Land Offices i n Iringa, Njombe, Mbeya, Ruk wa and Songwe. TZ-MLHHSD-325976-CS-CQS / Consultancy services for Pre Component 4: Project mana Consultant Qualifi paration of Guidance note o IDA / 70220 Post Open - National 0.00 Canceled 2022-11-28 2022-12-01 2022-12-19 2023-02-01 2023-03-03 2023-04-07 2023-10-04 gement cation Selection n women’s land rights in poly gamous households TZ-MLHHSD-325965-CS-CQS / Consultancy services for Pre paration of Guidance note on Component 4: Project mana Consultant Qualifi IDA / 70220 Post Open - National 0.00 Canceled 2022-11-28 2022-12-01 2022-12-19 2023-02-01 2023-03-03 2023-04-07 2023-10-04 Pastoralist Community / Hunt gement cation Selection er Gatherer participation in V LUP and systematic mass reg istration. Page 2 TZ-MLHHSD-331239-CS-CQS Component 3: Physical Deve Consultant Qualifi Under Implement / Consultancy Service for Dev IDA / 70220 lopment of Land Administrat Post Open - National 0.00 2023-01-22 2023-02-01 2023-02-12 2023-03-20 2023-03-28 2023-04-27 2023-06-01 2023-11-28 cation Selection ation eloping archive strategy ion System TZ-MLHHSD-331226-CS-CQS / Consultancy services for pr Component 4: Project mana Consultant Qualifi IDA / 70220 Post Open - National 0.00 Canceled 2022-12-18 2023-01-08 2023-02-21 2023-03-23 2023-04-27 2023-10-24 eparation of Grievance Redre gement cation Selection ss Mechanism (GRM) TZ-MLHHSD-331224-CS-CQS / Consultancy services for de Component 4: Project mana Consultant Qualifi veloping measures for addre IDA / 70220 Post Open - National 0.00 Canceled 2022-12-18 2023-01-08 2023-02-21 2023-03-23 2023-04-27 2023-10-24 gement cation Selection ssing gender discrimination a nd Gender Based Violence (G BV) TZ-MLHHSD-326007-CS-CQS Component 3: Physical Deve Consultant Qualifi Under Implement / Consultancy Services for De IDA / 70220 lopment of Land Administrat Post Open - National 0.00 2023-02-17 2023-05-09 2023-03-10 2023-04-30 2023-05-30 2023-07-04 2023-07-28 cation Selection ation sign & Supervision of 4 lectur ion System e theatres TZ-MLHHSD-341516-CS-CQS / Consultancy Service for Pro Component 2: Land Informa Consultant Qualifi Under Implement IDA / 70220 Post Open - National 0.00 2023-02-17 2023-03-24 2023-03-10 2023-04-12 2023-04-21 2023-05-21 2023-06-25 2023-12-22 vision of Technical Assistanc tion Management cation Selection ation e To Develop a System for La nd Values Mapping. TZ-MLHHSD-355087-CS-CQS / Consultancy Services for Su pervision of Continuously Op Component 2: Land Informa Consultant Qualifi IDA / 70220 Post Open - National 0.00 Canceled 2023-05-03 2023-05-11 2023-05-24 2023-07-07 2023-08-06 2023-09-10 2024-03-08 erating Reference Stations (C tion Management cation Selection ORS) Network for Land Admi nistration Sector of Tanzania INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MLHHSD-113852-CS-IND V / Consultancy Services for Component 1: Increased Te Individual Consult / Post Limited 0.00 Canceled 2019-05-09 2019-05-14 2019-06-04 2019-07-09 2020-01-05 preparation of an Environme nure Security ant Selection ntal and Social Management Framework TZ-MLHHSD-288011-CS-IND V / Procurement of Individual Component 4: Project mana Individual Consult IDA / 70220 Prior Limited 0.00 Signed 2022-04-20 2022-04-27 2022-04-25 2022-06-09 2022-05-16 2023-01-20 2022-06-20 2023-07-05 Consultant for Provision of M gement ant Selection onitoring and Evaluation Man agement TZ-MLHHSD-287705-CS-IND V / Procurement of Individual Component 4: Project mana Individual Consult IDA / 70220 Prior Limited 0.00 Signed 2022-04-20 2022-04-27 2022-04-25 2022-05-12 2022-05-16 2022-08-29 2022-06-20 2023-07-12 Consultant for Provision of Pr gement ant Selection ocurement Capacity Strength ening Services TZ-MLHHSD-288002-CS-IND V / Procurement of Individual Component 4: Project mana Individual Consult Consultant for Provision of Fi IDA / 70220 Prior Limited 0.00 Signed 2022-04-20 2022-05-09 2022-04-25 2022-05-12 2022-05-16 2022-08-30 2022-06-20 2023-07-12 gement ant Selection nancial Management Capacit y Strengthening Services TZ-MLHHSD-307744-CS-IND V / PROCUREMENT OF INDIVI Component 4: Project mana Individual Consult Under Implement DUAL CONSULTANT FOR PRO IDA / 70220 Prior Open - National 0.00 2022-08-05 2022-09-07 2022-09-04 2023-03-08 2022-09-15 2023-06-13 2022-10-20 2023-04-18 gement ant Selection ation VISION OF SOCIAL AND SAFE GUARD MANAGEMENT SERVI CES TZ-MLHHSD-288008-CS-IND V / Procurement of Individual Component 4: Project mana Individual Consult IDA / 70220 Post Limited 0.00 Canceled 2022-04-20 2022-06-03 2022-04-25 2022-06-09 2022-05-16 2022-06-20 2023-07-05 Consultant for Provision of So gement ant Selection cial and Safeguard Managem ent TZ-MLHHSD-288006-CS-IND Component 4: Project mana Individual Consult V / Procurement of Environm IDA / 70220 Post Limited 0.00 Canceled 2022-04-20 2022-06-03 2022-04-25 2022-06-09 2022-05-16 2022-06-20 2023-07-12 gement ant Selection ental Specialist TZ-MLHHSD-322837-CS-IND Component 4: Project mana Individual Consult Under Implement V / Procurement of Environm IDA / 70220 Prior Open - National 0.00 2022-11-25 2022-12-20 2023-01-22 2023-02-12 2023-03-19 2025-03-19 gement ant Selection ation ental Specialist TZ-MLHHSD-331249-CS-IND V / Consultancy services for P Component 1: Increased Te Individual Consult Under Implement reparation of Guidance Note IDA / 70220 Post Open - National 0.00 2022-12-19 2022-12-29 2023-02-06 2023-02-27 2023-04-03 2023-09-30 nure Security ant Selection ation on Women’s Land Rights in P olygamous Households. TZ-MLHHSD-331252-CS-IND V / Consultancy services for P reparation of Guidance note Component 1: Increased Te Individual Consult Under Implement IDA / 70220 Post Open - National 0.00 2022-12-19 2022-12-29 2023-02-06 2023-02-27 2023-04-03 2023-09-30 on Pastoralist Community / H nure Security ant Selection ation unter Gatherer participation i n VLUP and systematic mass registration. TZ-MLHHSD-336296-CS-IND V / Consultancy services for Component 4: Project mana Individual Consult Under Implement IDA / 70220 Post Open - National 0.00 2023-01-24 2023-02-01 2023-03-14 2023-04-04 2023-05-09 2023-11-05 preparation of Grievance Red gement ant Selection ation ress Mechanism (GRM) TZ-MLHHSD-336298-CS-IND V / Consultancy services for Component 4: Project mana Individual Consult Under Implement developing measures for add IDA / 70220 Post Open - National 0.00 2023-01-24 2023-02-01 2023-03-14 2023-04-04 2023-05-09 2023-11-05 gement ant Selection ation ressing gender discriminatio n and Gender Based Violence (GBV) Page 3 MINISTRY OF HEALTH Transforming Health Systems for Universal Care Project Project Procurement Plan Financial Year 2016/2017 IDA CREDIT No. 5836-KE GFF Grant Agreement TF0A2561 PHRD Grant Agreement TF0A2792 General 1. Project information: The Government of Kenya has applied for a Credit from the International Development Association supporting the Transforming Health Systems or Universal Care Project 2. Bank’s approval Date of the procurement Plan [Original::] 3. Date of General Procurement Notice: 4. Period covered by this procurement plan: 1st June, 2016 to 31st December, 2017 II. Goods and Works and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Method Threshold Prior Review Threshold 1 ICB – Works ≥US$15 million ≥US$10 million 2 NCB- Works = US$ Open International All contracts over US$ 1,000,000 1,500,000 < US$ Open National 1,000,000 <= US$ 50,000 Quotation — Direct Selection Goods and ≥US$100,000 Open International All contracts over Non- US$750,000 Consulting