PROCUREMENT PLAN (Textual Part) Project information: Democratic Republic Democratic of Congo – Multisectoral Child Nutrition and Health Project - P168756 Project Implementation agency: UGP PDSS Date of the Procurement Plan: April 2019 Period covered by this Procurement Plan: April 2019 – October 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 and revised November 2017) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Borrower’s Public Procurement Law No 10/010 of April 27, 2010 (PPL) and the Manual of Procedures of the PPL as per Borrower’s Decree No 10/22 of June 2, 2010, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (a) Standard Bidding Documents: All standard bidding documents to be used for the Project under NCB shall be found acceptable to the World Bank before their use during the implementation of Project; (b) Eligibility: Eligibility of bidders and acceptability of their goods and services shall not be based on their nationality and/or their origin; and association with a national firm shall not be a condition for participation in a bidding process. Therefore, except for the ineligibility situations referred to in paragraphs 1.10(a) (i) and 1.10(a) (ii) of the Procurement Guidelines, the eligibility of bidders must be based solely on their qualification, experience and capacity to carry out the contract related to the specific bidding process; (c) Advertising and Bid Preparation Time: Bidding opportunities shall be advertised at least in a national newspaper of wide circulation and on the website of the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) and bidders should be given at least 30 days from the date of invitation to bid or the date of availability of the bidding documents, whichever is later; (d) Criteria for Qualification of Bidders: Qualification criteria shall only concern the bidder’s capability and resources to perform the contract taking into account objective and measurable factors. Such criteria for qualification of bidders shall be clearly specified in the bidding documents; (e) Bid Evaluation and Contract Award: A contract shall be awarded to the substantially responsive and lowest evaluated bidder provided that such bidder meets the qualification criteria specified in the bidding documents. No scoring system shall be allowed for the evaluation of bids, and no “blanket” limitation to the number of lots which can be awarded to a bidder shall apply. The criteria for bid evaluation and the contract award conditions shall be clearly specified in the bidding documents; (f) Preferences: No preference shall be given to domestic/regional bidders; to domestically/regionally manufactured goods; and to bidders forming a joint venture with a national firm or proposing national sub-contractors or carrying out economic activities in the territory of the Recipient; (g) Publication of Contract Award: Information on all contract awards shall be published in at least a national newspaper of wide circulation or in the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) web-site; (h) Fraud and Corruption: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy to sanction firms or individuals found to have engaged in fraud and corruption as set forth in the Procurement Guidelines; (i) Inspection and Audit Rights: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy with respect to inspection and audit of accounts, records and other documents relating to the bid submission and contract performance; (j) Requirement for administrative documents and/or tax clearance certificate: The bidding documents shall not require foreign bidders to produce any administrative or tax related certificates prior to confirmation of awarding a contract; and (k) Modifications of a Signed Contract: Any change in the contract amount which, singly or combined with all previous changes, increases the original contract amount by fifteen (15) percent or more must be done through an amendment to the signed contract instead of signing a new contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Congo, Democratic Republic of : DRC Multisectoral Nutrition and Health Project PLAN General Information Country: Congo, Democratic Republic of 2019-05-03 Bank’s Approval Date of the Original Procurement Plan: 2024-02-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P168756 GPN Date: 2019-09-27 Project Name: DRC Multisectoral Nutrition and Health Project Loan / Credit No: IDA / 64410, / , IDA / D4790, IDA / V2420, IDA / V1400 RDC-MINISTERE DE LA SANTE PUBLIQUE Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ZR-DRC-MSP-104597-CW-RF Convergence Demonstration Single Stage - One E 2020-05-1 Q / Construction et ou réhabil / A posteriori Demande de prix Limited 280,000.00 0.00 Annulé 2019-09-21 2019-11-16 Project nvelope 4 itation des sanitaires ZR-DRC-MSP-105617-CW-RF Q / Construction et réhabilita Capacity Strengthening and Single Stage - One E 2020-03-1 / A posteriori Demande de prix Limited 280,000.00 0.00 Annulé 2019-07-20 2019-09-14 tion de structures sanitaires Project Management nvelope 2 dans les provinces d'interven tion ZR-DRC-MSP-196590-CW-RF Single Stage - One E En attente d 2021-10-0 B / Travaux de réhabilitation IDA / 64410 CERC A posteriori Appel d'offres Open - National 700,000.00 0.00 2020-12-21 2020-12-26 2021-02-06 2021-03-08 2021-04-12 nvelope 'exécution 9 et d'extension du bâtiment d u PRONANUT ZR-DRC-MSP-185062-CW-RF B / Extension/réhabilitation d es locaux PDSS pour acquérir Single Stage - One E 2021-11-0 IDA / 64410 CERC A posteriori Appel d'offres Open - National 550,000.00 0.00 Annulé 2021-01-15 2021-01-20 2021-03-03 2021-04-02 2021-05-07 l'équipe PMNS et Réhabilitati nvelope 3 on des locaux et du laboratoi re d'analyse du PRONANUT ZR-DRC-MSP-220154-CW-RF B / Travaux de construction d Single Stage - One E En attente d 2022-01-0 IDA / 64410 CERC A posteriori Appel d'offres Open - National 900,000.00 0.00 2021-03-17 2021-03-22 2021-05-03 2021-06-02 2021-07-07 es bâtiments devant abriter l nvelope 'exécution 3 es bureaux du PDSS ZR-DRC-MSP-282061-CW-RF Demande d'offres B / Travaux de Réhabilitation Capacity Strengthening and Single Stage - One E - DTPM Travaux - En attente d 2023-05-1 IDA / 64410 A posteriori Appel d'offres Open - National 700,000.00 0.00 2022-07-29 2022-08-03 2022-09-14 2022-10-14 2022-11-18 du bâtiment devant abriter le Project Management nvelope Droit civil français 'exécution 7 s bureaux du PRONANUT (Ext (français) ension) ZR-DRC-MSP-105624-CW-RF Q / Réhabilitation et rafraichi Capacity Strengthening and Single Stage - One E 2020-01-0 / A posteriori Demande de prix Limited 150,000.00 0.00 Annulé 2019-05-11 2019-07-06 ssement des locaux du PDSS Project Management nvelope 2 pour abriter le personnel du PMNS GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-DRC-MSP-105627-GO-RF Capacity Strengthening and Single Stage - One E Q / Acquisition de cinq (5) vé / A posteriori Demande de prix Limited 250,000.00 225,244.45 Signé 2019-05-18 2020-02-13 2019-07-13 2020-05-09 2020-01-09 Project Management nvelope hicules 4x4 pour la coordinati on du projet ZR-DRC-MSP-114486-GO-RF Q / Contractualisation avec le Convergence Demonstration Single Stage - One E / A priori Demande de prix Open - National 20,000,000.00 0.00 Annulé 2019-09-21 2019-11-16 2020-05-14 s agences spécialisées dans l Project nvelope e transfert monétaire des all ocations familiales ZR-DRC-MSP-212918-GO-RF Q / Acquisition du matériel in formatique, audiovisuel et d Capacity Strengthening and Single Stage - One E En attente d' IDA / 64410 A posteriori Demande de prix Limited 420,000.00 0.00 2021-03-21 2021-05-16 2021-11-12 e connexion internet pour ap Project Management nvelope exécution puyer Minagri/Minpeche , PN SR, EPSP, MINAS & PRONANU T ZR-DRC-MSP-212919-GO-RF Q / Acquisition de tablettes e Capacity Strengthening and Single Stage - One E En attente d' IDA / 64410 A posteriori Demande de prix Limited 70,000.00 0.00 2021-03-22 2021-05-17 2021-11-13 t chargeurs solaires pour les Project Management nvelope exécution vérificateurs du FBP ZR-DRC-MSP-105647-GO-RF Q / Acquisition des matériels Capacity Strengthening and Single Stage - One E En attente d' IDA / 64410 A posteriori Demande de prix Limited 200,000.00 0.00 2019-05-27 2019-07-22 2020-01-18 de connexion internet en fav Project Management nvelope exécution eur du Projet (V-SAT et conne xes) ZR-DRC-MSP-185114-GO-RF Capacity Strengthening and Single Stage - One E Q / Acquisition des équipeme IDA / 64410 A posteriori Demande de prix Limited 100,000.00 0.00 Annulé 2020-08-08 2020-10-03 2021-04-01 Project Management nvelope nts essentiels pour le PRONA NUT ZR-DRC-MSP-224670-GO-RF Convergence Demonstration Single Stage - One E Q / Acquisition des mobiliers IDA / 64410 A posteriori Demande de prix Limited 15,000.00 4,175.00 Signé 2021-03-22 2021-03-18 2021-05-17 2021-04-03 2021-11-13 Project nvelope de bureau pour le compte du PMNS ZR-DRC-MSP-282048-GO-DI Improving the Delivery of Co R / Acquisition et distribution mmunity Interventions and Passation de marc En attente d' des produits nutritionnels et l IDA / 64410 A priori Direct 12,998,321.15 0.00 2022-03-18 2022-03-23 2022-04-27 2022-10-24 Social and Behavioral Chang hé de gré à gré exécution e renforcement des capacité e s de gestion de stock (UNICE F) ZR-DRC-MSP-282018-GO-RF Improving the Delivery of Co Q / Reproduction et vulgarisa mmunity Interventions and Single Stage - One E En attente d' IDA / 64410 A posteriori Demande de prix Limited 50,000.00 0.00 2022-05-05 2022-06-30 2022-12-27 tion du Plan National Stratégi Social and Behavioral Chang nvelope exécution que Multisectoriel de Nutritio e n 2022-2026 ZR-DRC-MSP-282035-GO-RF B / Acquisition et dotation de s motos DT aux DPS (12), IP Improving Service Supply an Single Stage - One E S (8), BCZS ( 80) (Kasaï, Kasa IDA / 64410 A posteriori Appel d'offres Open - National 670,000.00 660,981.00 Signé 2022-05-25 2022-05-04 2022-05-30 2022-05-05 2022-07-11 2022-06-06 2022-08-10 2022-06-13 2022-09-14 2022-09-06 2023-03-13 d Strategic Purchasing nvelope ï Central, Kwilu et Sud-KIVU) ainsi qu'aux services techniq ues provinciaux du secteur a gricoles (dans 9 territoires) Page 1 ZR-DRC-MSP-282032-GO-RF B / Acquisition des Médicame Improving Service Supply an Open - Internationa Single Stage - One E nts Essentiels Génériques (M IDA / 64410 A priori Appel d'offres 2,340,000.00 0.00 Annulé 2022-03-31 2022-04-05 2022-05-17 2022-06-16 2022-07-21 2023-01-17 d Strategic Purchasing l nvelope EG) des dotations initiales au x CS et HGR (Kasaï, Kasaï Ce ntral, Kwilu et Sud-Kivu) ZR-DRC-MSP-282039-GO-RF B / Acquisition et dotation de Improving Service Supply an Open - Internationa Single Stage - One E s CS et HGR en petits Matérie IDA / 64410 A priori Appel d'offres 19,190,781.00 0.00 Signé 2022-03-30 2022-05-03 2022-04-04 2022-06-29 2022-05-16 2022-07-15 2022-06-15 2023-04-27 2022-07-20 2023-07-26 2023-01-16 d Strategic Purchasing l nvelope ls des soins ( DPS Kasaï, Kasa ï Central, Kwilu et Sud-Kivu) ZR-DRC-MSP-282027-GO-RF B / Acquisition et dotation de Improving Service Supply an Single Stage - One E En cours d'ex IDA / 64410 A posteriori Appel d'offres Open - National 400,000.00 0.00 2022-05-20 2022-06-03 2022-05-25 2022-06-06 2022-07-06 2022-07-04 2022-08-05 2022-09-09 2023-03-08 8 véhicules 4x4 aux DPS Ka d Strategic Purchasing nvelope écution saï, Kasaï central, Kwilu et Su d-Kivu ZR-DRC-MSP-282034-GO-RF Convergence Demonstration Single Stage - One E En attente d' IDA / 64410 A posteriori Appel d'offres Open - National 100,575.00 0.00 2022-05-20 2022-05-25 2022-07-06 2022-08-05 2022-09-09 2023-03-08 B / Acquisition et distribution Project nvelope exécution des FAF ZR-DRC-MSP-282037-GO-RF B / Acquisition et dotation de s mobiliers des bureaux dans Convergence Demonstration Single Stage - One E En cours d'ex IDA / 64410 A posteriori Appel d'offres Open - National 100,000.00 0.00 2022-03-30 2022-09-13 2022-04-04 2022-09-14 2022-05-16 2022-06-15 2022-07-20 2023-01-16 le cadre de l'Appui institution Project nvelope écution nel aux services du secteur a gricoles (SNV, SENASEM, DEP ) Agriculture et Pêche Elevag e ZR-DRC-MSP-282053-GO-RF B / Acquisition et dotation de s matériels informatique et a udiovisuels aux structures pa Capacity Strengthening and Single Stage - One E IDA / 64410 A posteriori Appel d'offres Open - National 137,760.00 0.00 Signé 2022-06-20 2022-09-13 2022-06-25 2022-10-11 2022-08-06 2022-10-18 2022-09-05 2022-11-25 2022-10-10 2023-03-02 2023-04-08 rties prenantes du niveau nat Project Management nvelope ional (PNSR, PRONANUT, PNS A, EPST, MINAS) ainsi qu'aux Coordinations provinciales (P NSR, PRONANUT, PNSA) ZR-DRC-MSP-282062-GO-RF Q / Acquisition de quatre (4) Capacity Strengthening and Single Stage - One E En cours d'ex IDA / 64410 A posteriori Demande de prix Limited 200,000.00 0.00 2022-03-20 2022-06-09 2022-05-15 2022-11-11 véhicules 4X4 pour les 4 bur Project Management nvelope écution eaux provinciaux du PMNS ZR-DRC-MSP-282069-GO-RF Capacity Strengthening and Single Stage - One E Q / Conception et Production IDA / 64410 A posteriori Demande de prix Limited 115,000.00 0.00 Signé 2022-05-05 2022-07-06 2022-06-30 2023-03-28 2022-12-27 Project Management nvelope des supports de communicati on du projet ZR-DRC-MSP-282070-GO-RF Capacity Strengthening and Single Stage - One E En attente d' Q / Acquisition des équipeme IDA / 64410 A posteriori Demande de prix Limited 35,000.00 0.00 2022-05-02 2022-06-27 2022-12-24 Project Management nvelope exécution nts de communication pour l e Projet ZR-DRC-MSP-282024-GO-RF Improving the Delivery of Co Q / Reproduction des outils d mmunity Interventions and Single Stage - One E En cours d'ex IDA / 64410 A posteriori Demande de prix Limited 450,000.00 0.00 2022-12-10 2023-03-01 2023-02-04 2023-08-03 e collecte des données pour Social and Behavioral Chang nvelope écution 1.026 FOSA dans les 4 provin e ces ZR-DRC-MSP-272829-GO-RF B / Acquisition et distribution du petit matériel médical pou Improving Service Supply an Open - Internationa Single Stage - One E r une dotation initiale aux For IDA / 64410 A priori Appel d'offres 13,100,000.00 0.00 Annulé 2022-04-20 2022-04-25 2022-06-06 2022-07-06 2022-08-10 2023-02-06 d Strategic Purchasing l nvelope mations Sanitaires (FoSa) ap puyées par le PMNS dans les provinces de Kasai, Kasai Ce ntral, Kwilu et Sud Kivu (en 4 lots) ZR-DRC-MSP-282060-GO-RF B / Acquisition des équipeme Capacity Strengthening and Single Stage - One E nts (mobilier et matériels info IDA / 64410 A posteriori Appel d'offres Open - National 100,000.00 0.00 Annulé 2022-03-31 2022-04-05 2022-05-17 2022-06-16 2022-07-21 2023-01-17 Project Management nvelope rmatiques) pour les 4 bureau x provinciaux ( kasai,Kasai-c entral,Kwilu et Sud Kivu) ZR-DRC-MSP-105628-GO-RF Capacity Strengthening and Single Stage - One E Q / Acquisition en deux lots d / A posteriori Appel d'offres Open - National 750,000.00 0.00 Annulé 2019-07-15 2019-07-20 2019-08-31 2019-09-30 2019-11-04 2020-05-02 Project Management nvelope es mobiliers et équipements i nformatiques ZR-DRC-MSP-282019-GO-RF Improving the Delivery of Co Q / Acquisition et dotation de mmunity Interventions and Single Stage - One E IDA / 64410 A posteriori Demande de prix Limited 40,000.00 0.00 Annulé 2022-03-30 2022-05-25 2022-11-21 s motos DT 125 aux Coordina Social and Behavioral Chang nvelope tions PRONANUT (2 motos pa e r coordination) ZR-DRC-MSP-282052-GO-RF Q / Acquisition et dotation de Improving Service Supply an Single Stage - One E IDA / 64410 A posteriori Demande de prix Limited 75,000.00 0.00 Annulé 2022-04-05 2022-05-31 2022-11-27 s motos DT 125 aux Coordina d Strategic Purchasing nvelope tions PNSR et PNSA ZR-DRC-MSP-282038-GO-RF Q / Acquisition des équipeme nts informatiques pour les S Convergence Demonstration Single Stage - One E ervices techniques au nivea IDA / 64410 A posteriori Demande de prix Limited 50,370.00 0.00 Annulé 2022-04-04 2022-05-30 2022-11-26 Project nvelope u provincial des IPAPEL et IT ATEL de l'Agriculture et Pêch e (24 PC, 6 LCD, 24 Modems , 3 Scaners, 3 imprimantes et c) ZR-DRC-MSP-282044-GO-RF Q / Acquisition et dotation de s équipements et mobiliers d Convergence Demonstration Single Stage - One E IDA / 64410 A posteriori Demande de prix Limited 99,000.00 0.00 Annulé 2022-04-02 2022-05-28 2022-11-24 es bureaux dans le cadre de l Project nvelope 'Appui institutionnel aux serv ices provinciaux du secteur a gricoles (AGRI & P-E) ZR-DRC-MSP-212915-GO-RF Q / Acquisition de matériels e Capacity Strengthening and Single Stage - One E IDA / 64410 A posteriori Demande de prix Limited 100,000.00 0.00 Annulé 2021-03-28 2021-05-23 2021-11-19 t équipements informatiques Project Management nvelope pour les bureaux ZR-DRC-MSP-357677-GO-RF B / Acquisition des matériels i nformatiques et mobiliers de Convergence Demonstration Single Stage - One E En attente d' IDA / 64410 A posteriori Appel d'offres Open - National 300,000.00 0.00 2023-05-31 2023-06-05 2023-07-17 2023-08-16 2023-09-20 2024-03-18 bureau (en 2 lots) en faveur Project nvelope exécution des directions (DEP-MINAS, P NSR, PNSA, PRONANUT, Educ ation) impliquées dans le Proj et ZR-DRC-MSP-363658-GO-RF Capacity Strengthening and Single Stage - One E En attente d' Q / Reproduction des outils d IDA / 64410 A posteriori Demande de prix Limited 190,000.00 0.00 2023-07-05 2023-08-30 2024-02-26 Project Management nvelope exécution e communication du Projet Page 2 ZR-DRC-MSP-282030-GO-RF Q / Acquisition et dotation de Improving Service Supply an Single Stage - One E IDA / 64410 A posteriori Demande de prix Limited 110,000.00 0.00 Annulé 2022-05-30 2022-07-25 2023-01-21 s PC aux DPS (12), IPS(8 ) et d Strategic Purchasing nvelope BCZS ( 80) (Kasaï, Kasaï Cent ral, Kwilu et Sud-Kivu) ZR-DRC-MSP-363659-GO-RF Capacity Strengthening and Single Stage - One E En attente d' Q / Location des Panneaux G IDA / 64410 A posteriori Demande de prix Limited 45,000.00 0.00 2023-09-05 2023-10-31 2024-04-28 Project Management nvelope exécution éants de visibilité dans les ax es stratégiques ZR-DRC-MSP-357545-GO-RF B / Acquisition des véhicules Improving the Delivery of Co 4X4 en faveur de l'UG-PDSS, mmunity Interventions and Single Stage - One E En attente d' IDA / 64410 A posteriori Appel d'offres Open - National 585,000.00 0.00 2023-08-31 2023-09-05 2023-10-17 2023-11-16 2023-12-21 2024-06-18 du PRONANUT et des Coordin Social and Behavioral Chang nvelope exécution ations provinciales du PRONA e NUT, PNSR et PNSA dans le c adre du PMNS ZR-DRC-MSP-395677-GO-RF Convergence Demonstration Single Stage - One E En cours d'ex Q / Acquisition des mobiliers IDA / 64410 A posteriori Demande de prix Open - National 200,000.00 0.00 2023-12-10 2024-02-04 2024-08-02 Project nvelope écution de bureau en faveur du PRO NANUT ZR-DRC-MSP-400493-GO-DI R / Contractualisation avec P Improving the Delivery of Co HATKIN pour Appui en médic mmunity Interventions and Passation de marc aments , dispositifs et équipe IDA / 64410 A posteriori Direct - National 325,000.00 0.00 Signé 2024-01-20 2024-01-11 2024-01-25 2024-01-18 2024-02-29 2024-08-27 Social and Behavioral Chang hé de gré à gré ments médicaux en faveur d e es sinistrés des pluies diluvie nnes dans la ville de Kanang a dans la province du Kasaï C entral NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-DRC-MSP-268434-NC-DIR / Assistance technique dans l Convergence Demonstration Passation de marc a fourniture de kits agricoles IDA / 64410 A priori Direct 13,000,000.00 12,111,858.00 Signé 2021-12-28 2022-01-07 2022-01-02 2022-01-17 2022-02-06 2022-02-12 2022-08-05 Project hé de gré à gré et de petites exploitations, E ntente directe avec FAO ZR-DRC-MSP-288158-NC-DIR / Contractualisation avec le U NFPA chargé de la mise en œ uvre des activités de prévent Improving Service Supply an Passation de marc ion et réponse aux Violences IDA / 64410 A priori Direct 20,000,000.00 20,000,000.00 Signé 2022-04-21 2022-04-18 2022-04-26 2022-05-10 2022-05-31 2022-06-27 2022-11-27 d Strategic Purchasing hé de gré à gré Basées sur le Genre (VBG), y compris l’exploitation et les a bus sexuels (EAS) et le harcè lement sexuel (HS), dans le c adre du PMNS ZR-DRC-MSP-282064-NC-DIR / Contractualisation avec PA M pour l’amélioration de la s écurité alimentaire des popul Passation de marc IDA / 64410 CERC A priori Direct 10,416,000.00 14,364,977.00 Signé 2022-04-20 2022-05-23 2022-04-25 2022-05-31 2022-05-30 2022-06-30 2022-11-26 ations vulnérables à travers hé de gré à gré une réponse intégrée en filet s sociaux (transferts monétai res) dans 5 zones de santé a u Kasaï et au Kasaï Central ZR-DRC-MSP-282067-NC-DIR / Contractualisation avec UNI CEF pour l’amélioration de la sécurité alimentaire des pop Passation de marc IDA / 64410 CERC A priori Direct 11,104,000.00 11,103,989.00 Signé 2022-07-30 2022-05-23 2022-08-04 2022-05-31 2022-09-08 2022-06-20 2023-03-07 ulations vulnérables à traver hé de gré à gré s des interventions nutritionn elles et en eau, hygiène et as sainissement (EHA) dans 5 z ones de santé au Kasaï et au Kasaï Central ZR-DRC-MSP-282063-NC-DIR / Contractualisation avec FAO pour l’amélioration de la séc urité alimentaire des populati Passation de marc IDA / 64410 CERC A priori Direct 10,200,000.00 10,200,000.00 Signé 2022-07-20 2022-05-16 2022-07-25 2022-06-06 2022-08-29 2022-06-26 2023-02-25 ons vulnérables au travers u hé de gré à gré ne agriculture sensible à la n utrition dans 5 zones de sant és dans les provinces du Kas aï et Kasaï-Central ZR-DRC-MSP-293975-NC-DIR / Contractualisation avec le F AO pour l’amélioration de la sécurité alimentaire des pop Passation de marc IDA / 64410 CERC A priori Direct 6,000,000.00 0.00 Annulé 2022-07-25 2022-10-27 2022-07-30 2022-09-03 2023-03-02 ulations vulnérables au trave hé de gré à gré rs une agriculture sensible à l a nutrition dans 2 zones de s anté dans la province du Kas aï Oriental ZR-DRC-MSP-293979-NC-DIR / Contractualisation avec le P AM pour l’amélioration de la sécurité alimentaire des pop Passation de marc IDA / 64410 CERC A priori Direct 3,135,023.00 0.00 Annulé 2022-07-27 2022-10-27 2022-08-01 2022-09-05 2023-03-04 ulations vulnérables à traver hé de gré à gré s une réponse intégrée en fil ets sociaux (transfert monéta ire inditionnel) dans 2 zones de santé dans la province du Kasaï Oriental ZR-DRC-MSP-293973-NC-DIR / Contractualisation avec UNI CEF pour l’amélioration de la sécurité alimentaire des pop Passation de marc ulations vulnérables à traver IDA / 64410 CERC A priori Direct 5,200,000.00 0.00 Annulé 2022-07-20 2022-10-28 2022-07-25 2022-08-29 2023-02-25 hé de gré à gré s des interventions nutritionn elles et en eau, hygiène et as sainissement (EHA) dans 2 z ones de santé dans la provin ce du Kasaï Oriental ZR-DRC-MSP-319185-CS-CD Improving the Delivery of Co S / Contractualisation avec U mmunity Interventions and Passation de marc Direct - Internation IDA / 64410 A priori 5,000,000.00 0.00 Signé 2023-01-20 2023-01-30 2023-01-25 2023-02-03 2023-03-01 2023-04-19 2023-08-28 NICEF pour réaliser l'enquête Social and Behavioral Chang hé de gré à gré al démographique et de santé ( e EDS-RDC III 2022) ZR-DRC-MSP-357552-NC-DIR / Contractualisation avec FAO pour la production et distribu Convergence Demonstration Passation de marc Direct - Internation tion des semences et culture IDA / 64410 A priori 9,000,000.00 0.00 Signé 2023-06-30 2023-09-20 2023-07-05 2023-10-10 2023-08-09 2024-02-05 Project hé de gré à gré al s bio certifiées dans le cadre de la mise en œuvre des acti vités de GAFSP dans les zone s d'interventions Page 3 ZR-DRC-MSP-378556-NC-RF B / Production des Spots, cap Capacity Strengthening and Single Stage - One E En attente d' IDA / 64410 A posteriori Appel d'offres Open - National 368,000.00 0.00 2023-09-30 2023-10-05 2023-11-16 2023-12-16 2024-01-20 2024-07-18 sules, diffusion et activités d Project Management nvelope exécution e visibilité du Programme ZR-DRC-MSP-325968-NC-RF Q / Entreposage des petits m Improving the Delivery of Co atériels des soins et des outil mmunity Interventions and Single Stage - One E s de collecte des données da IDA / 64410 A posteriori Appel d'offres Open - National 800,000.00 0.00 Annulé 2023-06-30 2023-07-05 2023-08-16 2023-09-15 2023-10-20 2024-04-17 Social and Behavioral Chang nvelope ns les quatre (4) provinces c e oncernées par le PMNS (Kasa ï, Kasaï Central, Kwilu et Sud- Kivu) ZR-DRC-MSP-400297-NC-RF Improving the Delivery of Co Q / Distribution des petits ma mmunity Interventions and Single Stage - One E En attente d' tériels des soins aux niveaux IDA / 64410 A posteriori Demande de prix Limited 350,000.00 0.00 2024-03-05 2024-04-30 2024-10-27 Social and Behavioral Chang nvelope exécution des Formations Sanitaires da e ns la province du Kasaï ZR-DRC-MSP-400298-NC-RF Improving the Delivery of Co Q / Distribution des petits ma mmunity Interventions and Single Stage - One E En attente d' tériels des soins aux niveaux IDA / 64410 A posteriori Demande de prix Limited 350,000.00 0.00 2024-03-05 2024-04-30 2024-10-27 Social and Behavioral Chang nvelope exécution des Formations Sanitaires da e ns la province du Kasaï Centr al ZR-DRC-MSP-400299-NC-RF Improving the Delivery of Co Q / Distribution des petits ma mmunity Interventions and Single Stage - One E En attente d' tériels des soins aux niveaux IDA / 64410 A posteriori Demande de prix Limited 350,000.00 0.00 2024-03-05 2024-04-30 2024-10-27 Social and Behavioral Chang nvelope exécution des Formations Sanitaires da e ns la province du Kwilu ZR-DRC-MSP-400300-NC-RF Improving the Delivery of Co Q / Distribution des petits ma mmunity Interventions and Single Stage - One E En attente d' tériels des soins aux niveaux IDA / 64410 A posteriori Demande de prix Limited 350,000.00 0.00 2024-03-05 2024-04-30 2024-10-27 Social and Behavioral Chang nvelope exécution des Formations Sanitaires da e ns la province du Sud-Kivu ZR-DRC-MSP-325973-NC-RF Q / Distribution des petits ma tériels des soins et des outils Improving the Delivery of Co de collecte des données aux mmunity Interventions and Single Stage - One E IDA / 64410 A posteriori Appel d'offres Open - National 1,400,000.00 0.00 Annulé 2023-08-31 2023-09-05 2023-10-17 2023-11-16 2023-12-21 2024-06-18 niveaux des Formations Sanit Social and Behavioral Chang nvelope aires dans les quatre (4) prov e inces concernées par le PMN S (Kasaï, Kasaï Central, Kwilu et Sud-Kivu) ZR-DRC-MSP-400294-NC-RF Improving the Delivery of Co Q / Entreposage des Petits m mmunity Interventions and Single Stage - One E En attente d' IDA / 64410 A posteriori Demande de prix Limited 130,000.00 0.00 2024-01-23 2024-03-19 2024-09-15 atériels des soins dans la pro Social and Behavioral Chang nvelope exécution vince du Kasaï Central e ZR-DRC-MSP-400293-NC-RF Improving the Delivery of Co Single Stage - One E En attente d' Q / Entreposage des petits m IDA / 64410 mmunity Interventions and A posteriori Demande de prix Limited 130,000.00 0.00 2024-01-23 2024-03-19 2024-09-15 nvelope exécution atériels des soins dans la pro Social and Behavioral Chang vince Kasaï e ZR-DRC-MSP-400295-NC-RF Improving the Delivery of Co Single Stage - One E En attente d' Q / Entreposage des Petits m IDA / 64410 mmunity Interventions and A posteriori Demande de prix Limited 130,000.00 0.00 2024-01-23 2024-03-19 2024-09-15 nvelope exécution atériels des soins dans la pro Social and Behavioral Chang vince du Kwilu e ZR-DRC-MSP-400296-NC-RF Improving the Delivery of Co Q / Entreposage des Petits m mmunity Interventions and Single Stage - One E En attente d' IDA / 64410 A posteriori Demande de prix Limited 130,000.00 0.00 2024-01-23 2024-03-19 2024-09-15 atériels des soins dans la pro Social and Behavioral Chang nvelope exécution vince du Sud-Kivu e CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-DRC-MSP-104572-CS-CQ S / Recrutement d'une firme Sélection fondée s Convergence Demonstration En attente d'exéc pour le ciblage des ménages / A posteriori ur les qualification Open - National 350,000.00 0.00 2019-09-09 2019-09-30 2019-11-13 2019-12-13 2020-01-17 2020-07-15 Project ution vulnérables bénéficiaires des s des consultants allocations financières ZR-DRC-MSP-104542-CS-QC BS / Recrutement d'ONG Cad Capacity Strengthening and Sélection fondée s Open - Internationa res Internationales pour la mi IDA / D4790 A priori 150,000,000.00 0.00 Annulé 2019-07-08 2019-07-29 2019-09-11 2019-10-09 2019-11-08 2019-12-08 2020-01-12 2021-01-11 Project Management ur la qualité l se en œuvre de l'approche N utrition à Assise Communaut aire ZR-DRC-MSP-197623-CS-QC BS / Recrutement d’une ONG chargée de la mise en œuvre des activités de prévention e Sélection fondée s Capacity Strengthening and t réponse aux Violences Basé IDA / D4790 A posteriori ur la qualité et le Open - National 200,000.00 0.00 Annulé 2021-01-22 2020-10-01 2021-02-12 2021-03-28 2021-04-25 2021-05-25 2021-06-29 2021-08-03 2022-08-03 Project Management es sur le Genre (VBG), y com coût pris l’exploitation et les abus sexuels (EAS) et le harcèlem ent sexuel (HS), dans le cadr e du PMNS ZR-DRC-MSP-185113-CS-CQ Sélection fondée s S / Recrutement d'une firme IDA / 64410 CERC A posteriori ur les qualification Open - National 45,000.00 0.00 Annulé 2020-10-02 2020-10-23 2020-12-06 2021-01-05 2021-02-09 2021-08-08 pour le renforcement des cap s des consultants acités de PRONANUT ZR-DRC-MSP-212852-CS-QC Sélection fondée s BS / Recrutement des ONG p IDA / 64410 CERC A priori ur la qualité et le Open - National 150,000,000.00 0.00 Annulé 2021-02-17 2021-03-10 2021-04-23 2021-05-21 2021-06-20 2021-07-25 2021-08-29 2022-08-29 our la mise en œuvre de l’ap coût proche Nutrition à Assise Co mmunautaire ZR-DRC-MSP-209258-CS-CQ S / Recrutement et financem Sélection fondée s ent des ONG pour la mise en IDA / 64410 CERC A posteriori ur les qualification Open - National 50,000.00 0.00 Annulé 2020-12-23 2021-01-13 2021-02-26 2021-03-28 2021-05-02 2021-10-29 œuvre de l'approche nutritio s des consultants n à assise communautaire(N AC) ZR-DRC-MSP-185059-CS-QC Sélection fondée s Capacity Strengthening and BS / Recrutement d'un cabin IDA / 64410 A posteriori ur la qualité et le Open - National 60,000.00 0.00 Annulé 2020-10-26 2020-11-16 2020-12-30 2021-01-27 2021-02-26 2021-04-02 2021-05-07 2022-05-07 Project Management et pour l'audit externe du pro coût jet PMNS Page 4 ZR-DRC-MSP-204745-CS-QC BS / Recrutement d'une ONG chargée de la mise en œuvr e des activités de prévention Sélection fondée s Capacity Strengthening and et réponse aux Violences Bas IDA / D4790 A priori ur la qualité et le Open - National 4,000,000.00 0.00 Annulé 2020-12-21 2021-01-11 2021-02-24 2021-03-24 2021-04-23 2021-05-28 2021-07-02 2022-07-02 Project Management ées sur le Genre (VBG), y co coût mpris l'exploitation et les ab us sexuels (EAS) et le harcèle ment sexuel (HS), dans le ca dre de la mise en œuvre ZR-DRC-MSP-196582-CS-CQ S / Recrutement d'un consult Sélection fondée s ant chargé des études, contr Capacity Strengthening and IDA / 64410 A posteriori ur les qualification Open - National 100,000.00 0.00 Annulé 2020-10-12 2020-10-01 2020-11-02 2020-12-16 2021-01-15 2021-02-19 2021-08-18 ôles et surveillances des trav Project Management s des consultants aux de réhabilitation et exte nsion du bâtiment du PRONA NUT ZR-DRC-MSP-212823-CS-CQ Sélection fondée s S / Contractualisation avec u IDA / 64410 CERC A posteriori ur les qualification Open - National 45,000.00 0.00 Annulé 2021-04-06 2021-04-27 2021-06-10 2021-07-10 2021-08-14 2022-02-10 ne firme pour le renforcemen s des consultants t des capacités du PRONANU T ZR-DRC-MSP-212830-CS-CQ S / Recrutement des Consult Sélection fondée s En attente d'exéc ants pour l'évaluation des be IDA / 64410 CERC A posteriori ur les qualification Open - National 350,000.00 0.00 2021-04-15 2021-05-06 2021-06-19 2021-07-19 2021-08-23 2022-02-19 ution soins d'investissement des F s des consultants OSA dans les 4 provinces cibl ées ZR-DRC-MSP-235317-CS-QC BS / Contractualisation avec l Sélection fondée s Capacity Strengthening and es ONG (Acteurs non Etatiqu IDA / D4790 A priori ur la qualité et le Open - National 13,000,000.00 11,969,674.90 Signé 2021-05-31 2021-05-27 2021-06-21 2021-05-28 2021-08-04 2021-08-16 2021-09-01 2021-10-08 2021-10-01 2022-01-10 2021-11-05 2022-05-04 2021-12-10 2022-05-09 2022-12-10 Project Management es) pour appuyer la planificat coût ion familiale dans la province du Kasaï ZR-DRC-MSP-235318-CS-QC BS / Contractualisation avec l Sélection fondée s Capacity Strengthening and es ONG (Acteurs non Etatiqu IDA / D4790 A priori ur la qualité et le Open - National 13,000,000.00 11,247,745.61 Signé 2021-06-15 2021-05-27 2021-07-06 2021-05-28 2021-08-19 2021-08-11 2021-09-16 2021-10-08 2021-10-16 2022-02-02 2021-11-20 2022-06-08 2021-12-25 2022-06-14 2022-12-25 Project Management es) pour appuyer la planificat coût ion familiale dans la province du Kasaï Central ZR-DRC-MSP-235319-CS-QC BS / Contractualisation avec l Sélection fondée s Capacity Strengthening and En cours d'exécut es ONG (Acteurs non Etatiqu IDA / D4790 A priori ur la qualité et le Open - National 13,000,000.00 0.00 2021-06-15 2021-05-27 2021-07-06 2021-05-28 2021-08-19 2021-08-11 2021-09-16 2021-10-19 2021-10-16 2022-02-16 2021-11-20 2022-11-17 2021-12-25 2022-12-25 Project Management ion es) pour appuyer la planificat coût ion familiale dans la province du Sud-Kivu ZR-DRC-MSP-235320-CS-QC BS / Contractualisation avec l Sélection fondée s Capacity Strengthening and es ONG (Acteurs non Etatiqu IDA / D4790 A priori ur la qualité et le Open - National 13,000,000.00 11,791,594.00 Signé 2021-06-15 2021-05-27 2021-07-06 2021-05-28 2021-08-19 2021-09-06 2021-09-16 2021-10-22 2021-10-16 2022-02-18 2021-11-20 2022-05-05 2021-12-25 2022-05-10 2022-12-25 Project Management es) pour appuyer la planificat coût ion familiale dans la province du Kwilu ZR-DRC-MSP-235326-CS-QC Sélection fondée s BS / Recrutement d'un consul Capacity Strengthening and En cours d'exécut IDA / 64410 A priori ur la qualité et le Open - National 2,000,000.00 0.00 2021-06-23 2021-11-17 2021-07-14 2022-01-10 2021-08-27 2022-08-02 2021-09-24 2022-09-16 2021-10-24 2022-11-04 2021-11-28 2023-06-02 2022-01-02 2023-01-02 tant firme pour le diagnostic Project Management ion coût organisationnel du PRONANU T ZR-DRC-MSP-235329-CS-QC BS / Recrutement d’une ONG Sélection fondée s En cours d'exécut chargée de la mise en œuvre IDA / 64410 CERC A priori ur la qualité et le Open - National 37,500,000.00 0.00 2021-06-24 2021-06-08 2021-07-15 2021-07-22 2021-08-28 2022-02-11 2021-09-25 2022-04-20 2021-10-25 2022-07-13 2021-11-29 2023-06-07 2022-01-03 2023-01-03 ion de l'approche Nutrition à Assi coût se Communautaire dans la pr ovince du Kasaï ZR-DRC-MSP-235330-CS-QC BS / Recrutement d’une ONG Sélection fondée s chargée de la mise en œuvre En cours d'exécut IDA / 64410 CERC A priori ur la qualité et le Open - National 37,500,000.00 0.00 2021-06-24 2021-06-08 2021-07-15 2021-07-23 2021-08-28 2022-03-15 2021-09-25 2022-04-29 2021-10-25 2022-07-13 2021-11-29 2023-06-07 2022-01-03 2023-01-03 de l'approche Nutrition à Assi ion coût se Communautaire dans la pr ovince du Kasaï Central ZR-DRC-MSP-235333-CS-QC BS / Recrutement d’une ONG Sélection fondée s chargée de la mise en œuvre IDA / 64410 CERC A priori ur la qualité et le Open - National 37,500,000.00 0.00 Signé 2021-06-24 2021-06-08 2021-07-15 2021-07-22 2021-08-28 2022-03-15 2021-09-25 2022-04-29 2021-10-25 2022-07-13 2021-11-29 2023-10-25 2022-01-03 2023-12-12 2023-01-03 de l'approche Nutrition à Assi coût se Communautaire dans la pr ovince du Sud-Kivu ZR-DRC-MSP-235334-CS-QC BS / Recrutement d’une ONG Sélection fondée s chargée de la mise en œuvre IDA / 64410 CERC A priori ur la qualité et le Open - National 37,500,000.00 0.00 Signé 2021-06-24 2021-06-08 2021-07-15 2021-07-22 2021-08-28 2022-03-15 2021-09-25 2022-04-29 2021-10-25 2022-07-13 2021-11-29 2023-10-25 2022-01-03 2023-11-28 2023-01-03 de l'approche Nutrition à Assi coût se Communautaire dans la pr ovince du Kwilu ZR-DRC-MSP-261471-CS-CQ S / Recrutement d’ONG/cons ortium d’ONG chargées de la mise en œuvre des activités Sélection fondée s de prévention et réponse aux IDA / 64410 CERC A posteriori ur les qualification Open - National 250,000.00 0.00 Annulé 2021-11-30 2021-11-11 2021-12-21 2022-02-03 2022-03-05 2022-04-09 2022-10-06 Violences Basées sur le Genr s des consultants e (VBG), y compris l’exploitat ion et les abus sexuels (EAS) et le harcèlement sexuel (HS ) dans la Province du Kasaï ZR-DRC-MSP-261472-CS-CQ S / Recrutement d’ONG/cons ortium d’ONG chargées de la mise en œuvre des activités Sélection fondée s de prévention et réponse aux IDA / 64410 CERC A posteriori ur les qualification Open - National 250,000.00 0.00 Annulé 2021-11-30 2021-11-11 2021-12-21 2022-02-03 2022-03-05 2022-04-09 2022-10-06 Violences Basées sur le Genr s des consultants e (VBG), y compris l’exploitat ion et les abus sexuels (EAS) et le harcèlement sexuel (HS ) dans la Province du Kwilu ZR-DRC-MSP-261473-CS-CQ S / Recrutement d’ONG/cons ortium d’ONG chargées de la mise en œuvre des activités Sélection fondée s de prévention et réponse aux IDA / 64410 CERC A posteriori ur les qualification Open - National 250,000.00 0.00 Annulé 2021-11-30 2021-12-21 2022-02-03 2022-03-05 2022-04-09 2022-10-06 Violences Basées sur le Genr s des consultants e (VBG), y compris l’exploitat ion et les abus sexuels (EAS) et le harcèlement sexuel (HS ) dans la Province du Sud Kiv u Page 5 ZR-DRC-MSP-261475-CS-CQ S / Recrutement d’ONG/cons ortium d’ONG chargées de la mise en œuvre des activités Sélection fondée s de prévention et réponse aux IDA / 64410 CERC A posteriori ur les qualification Open - National 250,000.00 0.00 Annulé 2021-11-30 2021-11-11 2021-12-21 2022-02-03 2022-03-05 2022-04-09 2022-10-06 Violences Basées sur le Genr s des consultants e (VBG), y compris l’exploitat ion et les abus sexuels (EAS) et le harcèlement sexuel (HS ) dans la Province du Kasaï c ent ZR-DRC-MSP-272824-CS-QC BS / Recrutement d’une age nce/ firme de vérification ext Sélection fondée s Improving Service Supply an Open - Internationa En cours d'exécut erne chargée de la vérificatio IDA / 64410 A priori ur la qualité et le 2,300,000.00 0.00 2022-04-22 2022-11-21 2022-05-13 2023-10-16 2022-06-26 2024-02-06 2022-07-24 2022-08-23 2022-09-27 2022-11-01 2023-11-01 d Strategic Purchasing l ion n des services des ONG NAC coût et ONG PF et la contre vérific ation des prestations de l'ach at stratégique ZR-DRC-MSP-282059-CS-QC BS / Sélection d'un Consultan Sélection fondée s Capacity Strengthening and En attente d'exéc t firme pour la Réalisation de IDA / 64410 A posteriori ur la qualité et le Open - National 425,000.00 0.00 2022-03-15 2022-04-05 2022-05-19 2022-06-16 2022-07-16 2022-08-20 2022-09-24 2023-09-24 Project Management ution s études environnementales coût et sociales (EIES, PPA, PGES, etc,) ZR-DRC-MSP-325931-CS-CQ Improving the Delivery of Co Sélection fondée s S / Recrutement d’un Consult mmunity Interventions and Open - Internationa En cours d'exécut IDA / 64410 A posteriori ur la qualité et le 500,000.00 0.00 2022-12-30 2023-02-02 2023-01-20 2023-02-15 2023-03-05 2023-04-02 2023-05-02 2023-06-06 2023-07-11 2024-07-10 ant Cabinet pour réaliser les Social and Behavioral Chang l ion coût enquêtes SMART dans le cad e re du PMNS ZR-DRC-MSP-212871-CS-CQ S / Recrutement d'une ONG c hargée de la mise en ŒUVR Sélection fondée s E des activités de preventio Capacity Strengthening and IDA / D4790 A posteriori ur les qualification Open - National 536,000.00 0.00 Annulé 2021-03-25 2021-03-15 2021-04-15 2021-04-30 2021-05-29 2021-06-28 2021-08-02 2022-01-29 n et reponse aux violences b Project Management s des consultants asées sur le genre(VBG), y co mpris l'exploitation et les ab us sexuels (EAS) et le harcele ment sexuel dans le cadre du PMNS ZR-DRC-MSP-282047-CS-CQ S / Recrutement d'un consult Sélection fondée s Capacity Strengthening and ant Cabinet (Bureau d'études IDA / 64410 A posteriori ur les qualification Open - National 100,000.00 0.00 Annulé 2022-04-30 2022-05-21 2022-07-04 2022-08-03 2022-09-07 2023-03-06 Project Management ) chargé de la surveillance de s des consultants s travaux du PRONANUT ZR-DRC-MSP-212875-CS-QB S / Recrutement d’agences s Sélection fondée s IDA / 64410 CERC A priori Open - National 20,000,000.00 0.00 Annulé 2021-03-29 2021-04-19 2021-06-02 2021-06-30 2021-07-30 2021-08-29 2021-10-03 2022-10-03 pécialisées dans les transfert ur la qualité s de monétaires (Cash Transf ert) ZR-DRC-MSP-212860-CS-QC Sélection fondée s BS / Contractualisation avec l Capacity Strengthening and IDA / D4790 A priori ur la qualité et le Open - National 52,000,000.00 0.00 Annulé 2021-02-17 2021-02-24 2021-03-10 2021-02-25 2021-04-23 2021-05-21 2021-06-20 2021-07-25 2021-08-29 2022-08-29 es ONG (Acteurs non Etatiqu Project Management coût es) pour appuyer la planificat ion familiale ZR-DRC-MSP-104546-CS-QC BS / Contractualisation avec l Capacity Strengthening and Sélection fondée s Open - Internationa IDA / D4790 A priori 52,000,000.00 0.00 Annulé 2019-07-08 2019-07-29 2019-09-11 2019-10-09 2019-11-08 2019-12-08 2020-01-12 2021-01-11 es ONG pour appuyer la plani Project Management ur la qualité l fication familiale ZR-DRC-MSP-104595-CS-CQ S / Contractualisation avec o Sélection fondée s pérateur de téléphonie mobil Convergence Demonstration / A posteriori ur les qualification Limited 50,000.00 0.00 Annulé 2019-08-05 2019-08-19 2019-09-18 2019-10-23 2020-04-20 e chargé de la vulgarisation Project s des consultants des messages d'alerte en lan gues nationales au profit des ménages ciblés ZR-DRC-MSP-104562-CS-QC BS / Contractualisation avec Sélection fondée s une firme pour développer et Capacity Strengthening and Open - Internationa / A priori ur la qualité et le 7,000,000.00 0.00 Annulé 2019-08-12 2020-05-14 2019-09-02 2019-10-16 2019-11-13 2019-12-13 2020-01-17 2020-02-21 2021-02-20 mettre en œuvre la stratégie Project Management l coût de changement des comport ements et le changement so cial ZR-DRC-MSP-185072-CS-CQ Sélection fondée s S / Recrutement d'un consult Capacity Strengthening and IDA / 64410 A posteriori ur les qualification Open - National 200,000.00 0.00 Annulé 2021-05-12 2021-06-02 2021-07-16 2021-08-15 2021-09-19 2022-03-18 ant firme pour le diagnostic o Project Management s des consultants rganisationnel du PRONANUT ZR-DRC-MSP-185059-CS-QC BS-2 / Services de consultant (Cabinet) chargé de l’audit e xterne financier, comptable e Sélection fondée s Capacity Strengthening and En attente d'exéc t de Passation des Marchés d IDA / 64410 A posteriori ur la qualité et le Open - National 200,000.00 0.00 2023-08-31 2023-09-21 2023-11-04 2023-12-02 2024-01-01 2024-02-05 2024-03-11 2025-03-11 Project Management ution es projets P147555- PDSS, P1 coût 68756 – PMNS, P167817- RE DISSE IV composante RDC et P173825 – COVID 19 (EXERCI CES 2021 et 2022) ZR-DRC-MSP-405217-CS-QC BS / Recrutement d'un Consu ltant (Cabinet) Chargé de l'A Sélection fondée s udit Externe Financier et Co Capacity Strengthening and En cours d'exécut IDA / 64410 A posteriori ur la qualité et le Open - National 200,000.00 0.00 2024-02-15 2024-02-07 2024-03-07 2024-02-14 2024-04-20 2024-05-18 2024-06-17 2024-07-22 2024-08-26 2025-08-26 mptable des Projets P147555 Project Management ion coût - PDSS, P168756 – PMNS, P16 7817- REDISSE IV composant e RDC et P173825 – COVID 1 9, EXERCICES 2024, 2025 et 2026. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-DRC-MSP-104560-CS-CD Sélection de cons S / Contractualisation avec H Convergence Demonstration IDA / 64410 A priori ultants par entent Direct 12,000,000.00 11,010,837.00 Signé 2019-07-15 2020-05-05 2019-07-25 2021-05-14 2019-09-28 2021-06-18 2020-03-26 arvest Plus pour la productio Project e directe n de semences bio fortifiées ZR-DRC-MSP-104569-CS-CD Sélection de cons Capacity Strengthening and En cours d'exécut S / Contractualisation avec l' / A priori ultants par entent Direct 4,000,000.00 0.00 2019-08-28 2020-11-24 2019-09-07 2019-11-11 2020-05-09 Project Management ion UNICEF pour l'appui techniqu e directe e et logistique Page 6 ZR-DRC-MSP-104592-CS-CD Sélection de cons S / Contractualisation avec S Convergence Demonstration / A posteriori ultants par entent Direct 100,000.00 0.00 Annulé 2019-08-20 2019-08-30 2019-11-03 2020-05-01 ENASEM pour la production d Project e directe e semences bio fortifiées ZR-DRC-MSP-105637-CS-IND Capacity Strengthening and V / Recrutement d'un Spécial IDA / 64410 A priori Individuel Open 216,000.00 168,400.00 Signé 2019-05-13 2019-05-14 2019-07-01 2019-05-22 2019-07-22 2019-08-16 2019-08-26 2019-09-29 2020-02-22 Project Management iste en Passation des Marché s ZR-DRC-MSP-105641-CS-IND Capacity Strengthening and En cours d'exécut V / Responsable d'un respons / A priori Individuel Open 216,000.00 0.00 2019-05-13 2019-05-14 2019-07-01 2019-07-22 2019-08-26 2020-02-22 Project Management ion able suivi et évaluation ZR-DRC-MSP-105643-CS-IND Capacity Strengthening and IDA / 64410 A priori Individuel Open 288,000.00 156,000.00 Signé 2019-05-13 2019-09-16 2019-07-01 2020-04-16 2019-07-22 2020-10-27 2019-08-26 2020-08-31 2020-02-22 V / Recrutement d'un Chef de Project Management Projet ZR-DRC-MSP-105646-CS-IND Capacity Strengthening and En cours d'exécut / A priori Individuel Open 240,000.00 0.00 2019-05-13 2019-05-14 2019-07-01 2019-05-21 2019-07-22 2019-12-03 2019-08-26 2020-02-22 V / Recrutement de deux co Project Management ion mptables ZR-DRC-MSP-104548-CS-CD Sélection de cons S / Contractualisation avec la Convergence Demonstration / A priori ultants par entent Direct 14,000,000.00 0.00 Annulé 2019-07-22 2020-04-30 2019-08-01 2020-08-04 2019-10-05 2020-04-02 FAO pour la mise à dispositi Project e directe on de kits agricoles et petits élevages ZR-DRC-MSP-159573-CS-IND V / Recrutement d'un Spécial iste en Santé Publique, charg Capacity Strengthening and IDA / 64410 A priori Individuel Open 240,000.00 57,600.00 Signé 2020-02-17 2020-03-06 2020-04-06 2020-08-04 2020-04-27 2020-09-16 2020-06-01 2020-10-12 2020-11-28 é du Suivi et Evaluation, pour Project Management le compte du Programme Mul tisectoriel de Nutrition et de Santé ZR-DRC-MSP-159577-CS-IND V / Recrutement d'un Spécial Capacity Strengthening and iste en Sauvegarde Sociale, p IDA / 64410 A priori Individuel Open 250,000.00 57,600.00 Signé 2020-02-17 2020-03-06 2020-04-06 2020-08-05 2020-04-27 2020-09-16 2020-06-01 2020-10-13 2020-11-28 Project Management our le compte du Projet Multi sectoriel de Nutrition et de S anté ZR-DRC-MSP-159578-CS-IND V / Recrutement d'un Spécial Capacity Strengthening and iste en Sauvegarde Environn IDA / 64410 A priori Individuel Open 250,000.00 45,000.00 Signé 2020-02-17 2020-03-16 2020-04-06 2020-08-05 2020-04-27 2020-09-16 2020-06-01 2020-10-12 2020-11-28 Project Management ementale, pour le compte du Programme Multisectoriel de Nutrition et de Santé ZR-DRC-MSP-179043-CS-IND V / RECRUTEMENT D´UN SPE Capacity Strengthening and IDA / 64410 A priori Individuel Open 228,000.00 57,000.00 Signé 2020-06-15 2020-07-17 2020-08-03 2020-12-23 2020-08-24 2021-01-19 2020-09-28 2021-02-09 2021-03-27 CIALISTE VIOLENCE BASE SU Project Management R LE GENRE AU SEIN DE DU PROJET PMNS ZR-DRC-MSP-182812-CS-CD S / Contractualisation en ent Sélection de cons ente directe avec YOUSSOUF Capacity Strengthening and IDA / V2420 A posteriori ultants par entent Direct 6,000.00 5,860.00 Signé 2020-07-08 2020-07-13 2020-07-18 2020-08-06 2020-09-21 2020-08-21 2021-03-20 CISSE, consultant chargé de l Project Management e directe 'élaboration du manuel de mi se en oeuvre opérationnel de s activités du PMNS ZR-DRC-MSP-104563-CS-CD Improving the Delivery of Co S / Contractualisation avec B Sélection de cons mmunity Interventions and LUESQUARE pour développer / A priori ultants par entent Direct 900,000.00 0.00 Annulé 2019-08-22 2019-09-01 2019-11-05 2020-05-03 Social and Behavioral Chang et tester un système de la vé e directe e rification base sur les risques ZR-DRC-MSP-185078-CS-IND V / Recrutement d'un audite Capacity Strengthening and En attente d'exéc ur interne pour le respect de IDA / 64410 A posteriori Individuel Open 240,000.00 0.00 2020-08-27 2020-10-15 2020-11-05 2020-12-10 2021-06-08 Project Management ution s procédures des gestions ad ministratives et financières d u PMNS ZR-DRC-MSP-196577-CS-IND V / Recrutement d'un assista Capacity Strengthening and IDA / V1400 A priori Individuel Open 216,000.00 57,000.00 Signé 2020-09-30 2020-11-16 2020-11-18 2021-06-22 2020-12-09 2021-07-12 2021-01-13 2021-07-13 2021-07-12 nt technique volet agricole e Project Management n appui au PMNS ZR-DRC-MSP-185076-CS-IND En cours d'exécut V / Recrutement des trois (3) IDA / 64410 CERC A posteriori Individuel Open 151,200.00 0.00 2020-12-14 2020-12-01 2021-02-01 2021-02-22 2021-03-29 2021-09-25 ion chauffeurs pour le compte du PMNS ZR-DRC-MSP-197616-CS-IND V / Recrutement d'un Consult Capacity Strengthening and ant Individuel chargé de la C IDA / V2420 A posteriori Individuel Open 80,000.00 0.00 Annulé 2021-01-20 2020-10-02 2021-03-10 2021-03-31 2021-05-05 2021-11-01 Project Management artographie Générique Violen ce Basée sur le Genre pour P MNS ZR-DRC-MSP-105638-CS-IND Capacity Strengthening and V / Recrutement d'un Respon / A priori Individuel Open 216,000.00 0.00 Annulé 2019-05-13 2019-05-14 2019-07-01 2019-07-22 2019-08-26 2020-02-22 Project Management sable Administratif et Financi er ZR-DRC-MSP-105631-CS-IND Capacity Strengthening and V / Recrutement d'un Assista / A priori Individuel Open 216,000.00 0.00 Annulé 2019-06-17 2019-12-19 2019-08-05 2019-08-26 2019-09-30 2020-03-28 Project Management nt Technique en appui au Vol et agriculture ZR-DRC-MSP-212818-CS-IND Capacity Strengthening and V / Recrutement d' un Assista IDA / 64410 A posteriori Individuel Open 54,000.00 0.00 Annulé 2021-02-15 2021-04-05 2021-04-26 2021-05-31 2021-11-27 Project Management nt Technique en appui au vol et Education ZR-DRC-MSP-105635-CS-IND Capacity Strengthening and V / Recrutement d'un Assista / A priori Individuel Open 216,000.00 0.00 Annulé 2019-05-13 2019-07-01 2019-07-22 2019-08-26 2020-02-22 Project Management nt Technique en appui au Vol et Education ZR-DRC-MSP-212819-CS-IND V / Recrutement d' un Assista Capacity Strengthening and En attente d'exéc IDA / 64410 A posteriori Individuel Open 54,000.00 0.00 2021-02-23 2021-04-13 2021-05-04 2021-06-08 2021-12-05 nt Technique en appui au vol Project Management ution et Protection Sociale ZR-DRC-MSP-105634-CS-IND V / Recrutement d'un Assista Capacity Strengthening and / A priori Individuel Open 216,000.00 0.00 Annulé 2019-06-17 2019-08-05 2019-08-26 2019-09-30 2020-03-28 nt Technique en appui au Vol Project Management et protection sociale ZR-DRC-MSP-212824-CS-IND V / Recrutement d'un Consult Capacity Strengthening and En attente d'exéc ant pour l’identification et l'e IDA / 64410 A posteriori Individuel 15,000.00 0.00 2021-03-24 2021-03-29 2021-04-19 2021-05-24 2021-11-20 Project Management ution stimation des besoins d’amél ioration du laboratoire d'anal yse du Pronanut Page 7 ZR-DRC-MSP-212829-CS-IND V / Recrutement d’un Consult ant (ou groupe de consultant s) pour la détermination d’un Capacity Strengthening and En attente d'exéc IDA / 64410 A posteriori Individuel Open 50,000.00 0.00 2021-02-25 2021-04-15 2021-05-06 2021-06-10 2021-12-07 taux de paiement conforme Project Management ution à la situation socio-économiq ue dans les zones ciblées po ur les participants aux activit és de « cash Transfer » ZR-DRC-MSP-212839-CS-IND Capacity Strengthening and V / Recrutement d’un contrôl IDA / 64410 A posteriori Individuel Open 160,000.00 0.00 Annulé 2021-03-17 2021-05-05 2021-05-26 2021-06-30 2021-12-27 Project Management eur de gestion ZR-DRC-MSP-212845-CS-CD Sélection de cons Convergence Demonstration S / Contractualisation avec le IDA / 64410 A priori ultants par entent Direct 24,000,000.00 0.00 Annulé 2021-03-24 2021-04-03 2021-06-07 2021-12-04 Project s EUPs pour l’achat stratégiq e directe ue ZR-DRC-MSP-182814-CS-CD S / Contractualisation en ent Sélection de cons Capacity Strengthening and ente directe avec l'agence de IDA / D4790 A priori ultants par entent Direct 2,000,000.00 0.00 Annulé 2020-07-13 2020-08-25 2020-07-23 2020-09-26 2021-03-25 Project Management contre vérification externe (C e directe REDES) pour l'achat stratégiq ue ZR-DRC-MSP-212849-CS-CD S / Contractualisation avec C Sélection de cons CP/JHU pour développer et m IDA / 64410 CERC A priori ultants par entent Direct 10,000,000.00 0.00 Annulé 2021-02-24 2021-02-23 2021-03-06 2021-05-10 2021-11-06 ettre en œuvre la stratégie d e directe e changement de comporte ment et de changement soci al ZR-DRC-MSP-212883-CS-IND V / Recrutement d' un Consul tant individuel pour évaluer l es besoins en appui et propo Capacity Strengthening and ser un plan de renforcement IDA / 64410 A posteriori Individuel Open 50,000.00 0.00 Annulé 2021-03-30 2021-05-18 2021-06-08 2021-07-13 2022-01-09 Project Management des capacités des Directions et Services techniques des M inistères de l’Agriculture et d e Pêche et Elevage qui interv iennent dans la mise en œuv ZR-DRC-MSP-212887-CS-IND Improving the Delivery of Co V / Recrutement d'un AT en a IDA / 64410 mmunity Interventions and A posteriori Individuel Open 54,000.00 0.00 Annulé 2021-03-30 2021-05-18 2021-06-08 2021-07-13 2022-01-09 ppui au PRONANUT Social and Behavioral Chang e ZR-DRC-MSP-185071-CS-IND Improving the Delivery of Co V / Recrutement d'un assista IDA / 64410 mmunity Interventions and A priori Individuel Open 216,000.00 0.00 Annulé 2021-01-05 2020-11-12 2021-02-23 2021-03-16 2021-04-20 2021-10-17 nt technique en appui au PR Social and Behavioral Chang ONANUT e ZR-DRC-MSP-212894-CS-IND V / Recrutement d'un AT char En cours d'exécut IDA / 64410 CERC A posteriori Individuel Open 54,000.00 0.00 2021-03-23 2021-02-27 2021-05-11 2021-06-01 2021-07-06 2022-01-02 gé du suivi des activités du P ion MNS dans le Sud Kivu ZR-DRC-MSP-185103-CS-IND Improving the Delivery of Co V / Recrutement d'un assista mmunity Interventions and IDA / 64410 A priori Individuel Open 216,000.00 0.00 Annulé 2020-11-16 2021-01-04 2021-01-25 2021-03-01 2021-08-28 nt technique en appui au PM Social and Behavioral Chang NS dans le KASAI e ZR-DRC-MSP-185099-CS-IND Improving the Delivery of Co V / Recrutement d'un assista mmunity Interventions and IDA / 64410 A priori Individuel Open 216,000.00 0.00 Annulé 2020-11-16 2021-01-04 2021-01-25 2021-03-01 2021-08-28 nt technique en appui au PM Social and Behavioral Chang NS dans le Kasai-Central e ZR-DRC-MSP-185101-CS-IND Improving the Delivery of Co V / Recrutement d'un assista mmunity Interventions and IDA / 64410 A priori Individuel Open 216,000.00 0.00 Annulé 2020-11-16 2021-01-04 2021-01-25 2021-03-01 2021-08-28 nt technique en appui au PM Social and Behavioral Chang NS dans le KWILU e ZR-DRC-MSP-209302-CS-CD S / Contractualisation par ent ente directe avec Médecin d' Sélection de cons Afrique (MEDA), pour l' Etude En cours d'exécut IDA / 64410 CERC A posteriori ultants par entent Direct 210,000.00 0.00 2021-02-17 2021-03-03 2021-02-27 2021-05-03 2021-10-30 de base sur les indicateurs n ion e directe utritionnels dans les provinc es d'intervention du PMNS da ns le cadre de l'étude d'impa ct du PDSS ZR-DRC-MSP-185096-CS-IND Improving the Delivery of Co V / Recrutement d'un assista mmunity Interventions and IDA / 64410 A priori Individuel Open 216,000.00 0.00 Annulé 2020-11-16 2021-01-04 2021-01-25 2021-03-01 2021-08-28 nt technique en appui au PM Social and Behavioral Chang NS dans le Sud-Kivu e ZR-DRC-MSP-197611-CS-IND Improving the Delivery of Co V / Recrutement d'un Spécial IDA / 64410 mmunity Interventions and A priori Individuel Open 240,000.00 0.00 Annulé 2020-11-18 2021-01-06 2021-01-27 2021-03-03 2021-08-30 iste en Nutrition pour le PMN Social and Behavioral Chang S e ZR-DRC-MSP-185075-CS-IND V / Recrutement d'une assist IDA / 64410 CERC A posteriori Individuel Open 128,000.00 0.00 Annulé 2020-12-23 2021-02-10 2021-03-03 2021-04-07 2021-10-04 ante de programme ZR-DRC-MSP-204735-CS-CD S / Contractualisation par ent ente directe avec Center for Communication Programms ( Sélection de cons CCP)/ John HOPKINS Universit IDA / 64410 CERC A priori ultants par entent Direct 2,500,000.00 0.00 Annulé 2020-11-16 2020-11-26 2021-01-30 2021-07-29 y pour une Recherche Forma e directe tive et le développement de l a stratégie de communicatio n pour le changement social et comportements ZR-DRC-MSP-217495-CS-IND V / Recrutement d'un Consult ant Individuel chargé de la R éalisation des Etudes Techni Capacity Strengthening and IDA / 64410 A posteriori Individuel Open 100,000.00 0.00 Annulé 2021-03-25 2021-02-26 2021-05-13 2021-06-03 2021-07-08 2022-01-04 ques et surveillance des trav Project Management aux de Réhabilitation, extens ion des Bureaux et Laboratoi res du PRONANUT à Kinshasa /Gombe ZR-DRC-MSP-212834-CS-IND V / Recrutement d’un Assista Capacity Strengthening and En attente d'exéc IDA / 64410 A priori Individuel Open 360,000.00 0.00 2021-03-30 2021-05-18 2021-06-08 2021-07-13 2022-01-09 nt Technique en gestion fina Project Management ution ncière et comptable Page 8 ZR-DRC-MSP-212898-CS-IND Improving the Delivery of Co V / Recrutement d'un AT char mmunity Interventions and IDA / 64410 A posteriori Individuel Open 162,000.00 56,400.00 Signé 2021-03-30 2021-02-27 2021-05-18 2021-07-07 2021-06-08 2021-08-18 2021-07-13 2021-09-24 2022-01-09 gé du suivi des activités du Social and Behavioral Chang PMNS dans le Kwilu e ZR-DRC-MSP-212910-CS-IND Improving the Delivery of Co V / Recrutement d'un Consult mmunity Interventions and En attente d'exéc IDA / 64410 A posteriori Individuel Open 54,000.00 0.00 2021-03-25 2021-05-13 2021-06-03 2021-07-08 2022-01-04 ant spécialiste en Nutrition p Social and Behavioral Chang ution our le PRONANUT e ZR-DRC-MSP-212882-CS-IND V / Recrutement d'un Consult Capacity Strengthening and IDA / 64410 A posteriori Individuel Open 20,000.00 0.00 Annulé 2021-03-25 2021-05-13 2021-06-03 2021-07-08 2022-01-04 ant national pour l'élaboratio Project Management n du plan strategique du PNS R ZR-DRC-MSP-212914-CS-IND Capacity Strengthening and V / Recrutement d'un Consult IDA / V1400 A posteriori Individuel Open 272,000.00 0.00 Annulé 2021-03-31 2021-05-19 2021-06-09 2021-07-14 2022-01-10 Project Management ant spécialiste en Nutrition p our le PMNS ZR-DRC-MSP-185053-CS-IND V / Recrutement d'un consult Capacity Strengthening and En attente d'exéc IDA / V2420 A posteriori Individuel Open 20,000.00 0.00 2021-04-15 2021-06-03 2021-06-24 2021-07-29 2022-01-25 ant national pour l'élaboratio Project Management ution n d'un plan stratégique du P NSA ZR-DRC-MSP-212896-CS-IND V / Recrutement d'un AT char IDA / 64410 CERC A posteriori Individuel Open 162,000.00 56,400.00 Signé 2021-03-23 2021-03-11 2021-05-11 2021-07-07 2021-06-01 2021-08-18 2021-07-06 2021-09-24 2022-01-02 gé du suivi des activités du PMNS dans le Kasai ZR-DRC-MSP-212895-CS-IND V / Recrutement d'un AT char IDA / 64410 CERC A posteriori Individuel Open 162,000.00 56,400.00 Signé 2021-03-25 2021-03-11 2021-05-13 2021-08-17 2021-06-03 2021-08-18 2021-07-08 2021-09-24 2022-01-04 gé du suivi des activités du P MNS dans le Kasai Central ZR-DRC-MSP-220149-CS-CD Sélection de cons S / Contractualisation avec l' Capacity Strengthening and IDA / 64410 A priori ultants par entent Direct 25,000,000.00 24,941,597.69 Signé 2021-03-17 2021-05-28 2021-03-27 2021-06-14 2021-05-31 2022-03-07 2021-11-27 UNICEF pour l'acquisition des Project Management e directe intrants nutritionnels pour le compte du PMNS ZR-DRC-MSP-222858-CS-IND V / Recrutement d'un AT char En attente d'exéc IDA / 64410 CERC A posteriori Individuel Open 162,000.00 0.00 2021-03-30 2021-05-18 2021-06-08 2021-07-13 2022-01-09 gé du suivi des activités du P ution MNS dans le Sud Kivu ZR-DRC-MSP-225929-CS-IND V / Recrutement d'un Consult ant Individuel chargé de la R éalisation des Etudes Techni Capacity Strengthening and IDA / 64410 A posteriori Individuel Limited 100,000.00 30,000.00 Signé 2021-03-31 2021-03-31 2021-04-05 2021-04-14 2021-04-26 2021-06-24 2021-05-31 2021-07-15 2021-11-27 ques (actualisation) et survei Project Management llance des travaux de Réhabil itation, extension des Bureau x et Laboratoires du PRONAN UT à Kinshasa / Gombe ZR-DRC-MSP-228773-CS-CD S / Contractualisation par ent ente directe avec CCP/JHU po ur la recherche formative po Sélection de cons ur la mise en œuvre de la str IDA / 64410 CERC A priori ultants par entent Direct 500,000.00 518,461.94 Signé 2021-04-29 2021-04-27 2021-05-09 2021-06-25 2021-07-13 2021-10-14 2022-01-09 atégie de communication po e directe ur le changement social et d e comportement en faveur d’ une nutrition adéquate et de la promotion de la planificati on ZR-DRC-MSP-228776-CS-CD S / Contractualisation par ent ente direct avec CCP/JHU pou Sélection de cons r l'élaboration de la stratégie IDA / 64410 CERC A priori ultants par entent Direct 9,000,000.00 0.00 Annulé 2021-04-30 2021-05-10 2021-07-14 2022-01-10 de communication pour le ch e directe angement social et de compo rtement en faveur d’une nutr ition adéquate et de la prom otion de la planification famili ale ZR-DRC-MSP-234322-CS-IND Improving the Delivery of Co En cours d'exécut V / Recrutement d'un assista IDA / 64410 mmunity Interventions and A priori Individuel Open 270,000.00 0.00 2021-05-31 2021-06-15 2021-07-19 2022-01-28 2021-08-09 2021-09-13 2022-03-12 ion nt technique en appui au PR Social and Behavioral Chang ONANUT e ZR-DRC-MSP-234328-CS-IND V / Contractualisation par ent ente directe avec Monsieur E IDA / 64410 CERC A priori Individuel Direct 228,000.00 0.00 Annulé 2021-06-23 2021-07-26 2021-07-03 2021-07-24 2021-08-28 2022-02-24 variste KAYEMBE consultant spécialiste en violence basée sur le Genre en appui au PM NS ZR-DRC-MSP-234340-CS-IND V / Recrutement d'un consult ant senior chargé de l'évalua IDA / 64410 CERC A posteriori Individuel Open 7,000.00 0.00 Annulé 2021-06-23 2021-08-11 2021-09-01 2021-10-06 2022-04-04 tion des demandes des propo sitions techniques et financiè res des ONG NAC dans le cad re du PMNS ZR-DRC-MSP-234345-CS-IND V / Contractualisation par ent En cours d'exécut ente directe avec Monsieur A IDA / 64410 CERC A priori Individuel Direct 318,000.00 0.00 2021-06-29 2021-11-16 2021-07-09 2021-07-30 2021-09-03 2022-03-02 ion braham MAFUMO TOBOLOLO , spécialiste en gestion finan cière en appui au PMNS ZR-DRC-MSP-235335-CS-IND Improving the Delivery of Co V / Sélection et Recrutement mmunity Interventions and En cours d'exécut IDA / 64410 A priori Individuel Open 216,000.00 0.00 2021-07-15 2021-09-02 2021-09-23 2021-10-28 2022-04-26 d'un assistant technique nutr Social and Behavioral Chang ion ition pour le PMNS e ZR-DRC-MSP-255693-CS-CD S / Contractualisation par ent Sélection de cons ente directe avec l'AAP/EUP S Convergence Demonstration IDA / 64410 A priori ultants par entent Direct 2,285,465.00 1,919,947.00 Signé 2021-10-12 2021-11-10 2021-10-22 2021-12-09 2021-12-26 2022-02-09 2022-06-24 UD-KIVU pour la mise en œu Project e directe vre de l'achat stratégique d ans la province du Sud-Kivu ZR-DRC-MSP-255696-CS-CD S / Contractualisation en ent Sélection de cons Convergence Demonstration ente directe avec AAP/EUP-B IDA / 64410 A priori ultants par entent Direct 2,500,000.00 2,549,470.69 Signé 2021-10-13 2022-02-23 2021-10-23 2022-03-03 2021-12-27 2022-03-06 2022-06-25 Project andundu pour la mise en œu e directe vre de l'achat stratégique da ns la province du Bandundu Page 9 ZR-DRC-MSP-255699-CS-CD S / Contractualisation en ent Sélection de cons ente directe avec AAP/EUP-K Convergence Demonstration IDA / 64410 A priori ultants par entent Direct 1,383,296.00 3,549,513.93 Signé 2021-10-13 2021-11-29 2021-10-23 2022-01-28 2021-12-27 2022-04-06 2022-06-25 asai-Central pour la mise en Project e directe œuvre de l'achat stratégique dans la province du Kasai-Ce ntral ZR-DRC-MSP-255701-CS-CD S / Contractualisation en ent Sélection de cons Convergence Demonstration ente directe avec AAP/EUP-K IDA / 64410 A priori ultants par entent Direct 1,120,608.00 2,966,302.58 Signé 2021-10-13 2021-11-29 2021-10-23 2022-01-28 2021-12-27 2022-04-06 2022-06-25 Project asai pour la mise en œuvre d e directe e l'achat stratégique dans la province du Kasai. ZR-DRC-MSP-261476-CS-IND V / Recrutement d'un consult Capacity Strengthening and ant Chargé de l'élaboration d IDA / 64410 A posteriori Individuel Open 70,000.00 0.00 Annulé 2021-11-30 2022-03-23 2022-01-18 2022-02-08 2022-03-15 2022-09-11 Project Management u plan stratégique national m ultisectoriel de nutrition 2022 -2026 ZR-DRC-MSP-266790-CS-IND En attente d'exéc V / Recrutement d’une Assist IDA / 64410 CERC A posteriori Individuel Limited 30,000.00 0.00 2022-01-26 2022-01-31 2022-02-21 2022-03-28 2022-09-24 ution ante au Programme en appui à l’UG-PDSS ZR-DRC-MSP-266793-CS-IND V / Recrutement en urgence d’Un Expert National Junior e En cours d'exécut IDA / 64410 CERC A posteriori Individuel Limited 54,000.00 0.00 2022-01-28 2022-02-15 2022-02-02 2022-02-23 2022-03-30 2022-09-26 n Passation des marchés cha ion rgés d’appuyer le service de Passation des marchés de l’U nité de Gestion du PDSS ZR-DRC-MSP-212846-CS-CD Sélection de cons S / Contractualisation avec u Capacity Strengthening and IDA / D4790 A priori ultants par entent Direct 2,000,000.00 0.00 Annulé 2021-04-05 2021-09-13 2021-04-15 2021-06-19 2021-12-16 ne agence de contre-vérificat Project Management e directe ion (GINGER CREDES) de l’ac hat stratégique ZR-DRC-MSP-272846-CS-CD S / Contractualisation avec l e UNFPA chargé de la mise e n œuvre des activités de pré Sélection de cons Improving Service Supply an En cours d'exécut vention et réponse aux Viole IDA / 64410 A priori ultants par entent Direct 6,500,000.00 0.00 2022-03-24 2022-02-08 2022-04-03 2022-06-07 2022-12-04 d Strategic Purchasing ion nces Basées sur le Genre (VB e directe G), y compris l’exploitation et les abus sexuels (EAS) et le harcèlement sexuel (HS), da ns le cadre de PMNS ZR-DRC-MSP-272805-CS-CD S / Contractualisation par ent Sélection de cons ente directe avec CREDES GI Improving Service Supply an IDA / 64410 A priori ultants par entent Direct 2,000,000.00 0.00 Signé 2022-03-24 2022-02-27 2022-04-03 2022-03-17 2022-06-07 2022-12-08 2022-12-04 NGER en vue de la contre vé d Strategic Purchasing e directe rification des prestations de l' achat stratégique et des serv ices des ONG NAC et ONG PF . ZR-DRC-MSP-282022-CS-IND Improving the Delivery of Co V / Recrutement d'un consult mmunity Interventions and En attente d'exéc ant international en appui a IDA / 64410 A posteriori Individuel Open 70,000.00 0.00 2022-03-31 2022-05-19 2022-06-09 2022-07-14 2023-01-10 Social and Behavioral Chang ution u processus de l'élaboration e du PNSMN 2022 2026 ZR-DRC-MSP-282020-CS-IND Improving the Delivery of Co V / Recruter un consultant na mmunity Interventions and IDA / 64410 A posteriori Individuel Limited 20,000.00 0.00 Signé 2022-03-31 2022-10-19 2022-04-05 2023-01-11 2022-04-26 2022-12-21 2022-05-31 2023-03-22 2022-11-27 tional en appui au processu Social and Behavioral Chang s de l'élaboration du PNSMN e 2022 2026 ZR-DRC-MSP-282051-CS-IND V / Recrutement de 4 Consult ants individuels pour les étud Improving Service Supply an En attente d'exéc IDA / 64410 A priori Individuel Open 350,000.00 0.00 2022-04-30 2022-06-18 2022-07-09 2022-08-13 2023-02-09 es préalables en vue des réh d Strategic Purchasing ution abilitations et constructions des FOSA de démonstration dans les 4 provinces ciblées ZR-DRC-MSP-286042-CS-IND V / Recrutement de 6 Experts Capacity Strengthening and En cours d'exécut spécialisés dans différents do IDA / 64410 A posteriori Individuel Limited 90,000.00 0.00 2022-03-31 2022-03-22 2022-04-05 2022-04-26 2022-05-31 2022-11-27 Project Management ion maines techniques en rappor t avec les activités mises en œuvre par le PMNS ZR-DRC-MSP-286670-CS-CD S / Contractualisation avec l' Ecole de santé Publique de l' Improving the Delivery of Co UNIKIN pour appuyer le PRO Sélection de cons mmunity Interventions and NANUT dans l'organisation d IDA / 64410 A posteriori ultants par entent Direct 400,000.00 0.00 Annulé 2022-04-29 2022-05-09 2022-07-13 2023-01-09 Social and Behavioral Chang e qualité des formations de r e directe e enforcement des capacités d es acteurs Provinciaux dans les DPS Sud Kivu, Kwilu, Kasa ï et Kasaï Central ZR-DRC-MSP-301732-CS-IND V / Recrutement d'un Consult ant Individuel chargé d'élabo Convergence Demonstration En cours d'exécut IDA / 64410 A posteriori Individuel Open 100,000.00 0.00 2022-07-20 2022-08-15 2022-09-07 2022-09-28 2022-11-02 2023-05-01 rer le Cadre de Protection de Project ion s peuples autochtones (CPPA ) dans les provinces concern ées par le PMNS ZR-DRC-MSP-309950-CS-IND V / Recrutement d'un Spécial Convergence Demonstration En cours d'exécut iste provincial en sauvegarde IDA / 64410 A posteriori Individuel Open - National 56,400.00 0.00 2022-09-15 2022-08-16 2022-11-03 2022-11-24 2022-12-29 2023-06-27 Project ion environnementale et sociale pour la province du Sud-Kivu ZR-DRC-MSP-309955-CS-IND V / Recrutement d'un Spécial Convergence Demonstration En cours d'exécut iste provincial en sauvegarde IDA / 64410 A posteriori Individuel Open - National 56,400.00 0.00 2022-09-15 2022-08-16 2022-11-03 2022-11-24 2022-12-29 2023-06-27 Project ion environnementale et sociale pour la province du Kwilu ZR-DRC-MSP-309958-CS-IND V / Recrutement d'un Spécial Convergence Demonstration En cours d'exécut iste provincial en sauvegarde IDA / 64410 A posteriori Individuel Open - National 56,400.00 0.00 2022-09-15 2022-08-16 2022-11-03 2022-11-24 2022-12-29 2023-06-27 Project ion environnemental et social po ur la province du Kasaï Centr al ZR-DRC-MSP-309957-CS-IND V / Recrutement d'un Spécial Convergence Demonstration En cours d'exécut iste provincial en sauvegarde IDA / 64410 A posteriori Individuel Open - National 56,400.00 0.00 2022-09-15 2022-08-16 2022-11-03 2022-11-24 2022-12-29 2023-06-27 Project ion environnemental et social po ur la province du Kasaï Page 10 ZR-DRC-MSP-309959-CS-IND V / Recrutement d'un Consult Convergence Demonstration En cours d'exécut IDA / 64410 A posteriori Individuel Open - National 70,000.00 0.00 2022-09-30 2022-08-16 2022-11-18 2022-12-09 2023-01-13 2023-07-12 ant Individuel chargé de l'éla Project ion boration d'un Plan de santé e t bien être animal ZR-DRC-MSP-311245-CS-IND V / Recrutement d’un consult Improving the Delivery of Co ant international en appui au mmunity Interventions and IDA / 64410 A posteriori Individuel Limited 70,000.00 0.00 Signé 2022-09-15 2022-10-06 2022-09-20 2022-10-14 2022-10-11 2023-02-09 2022-11-15 2023-03-15 2023-05-14 processus de l’élaboration du Social and Behavioral Chang Plan Stratégique National Mu e ltisectoriel de Nutrition 2022 – 2026 ZR-DRC-MSP-325942-CS-IND V / Recrutement d’un Assista Capacity Strengthening and En cours d'exécut IDA / 64410 A posteriori Individuel Open - National 57,000.00 0.00 2022-12-20 2022-11-28 2023-02-07 2023-02-28 2023-04-04 2023-10-01 nt technique en Santé publiq Project Management ion ue pour la province du Kasaï ZR-DRC-MSP-325956-CS-IND V / Recrutement d’un Assista Capacity Strengthening and En cours d'exécut IDA / 64410 A posteriori Individuel Open - National 57,000.00 0.00 2022-12-20 2022-11-28 2023-02-07 2023-02-28 2023-04-04 2023-10-01 nt technique en Santé publiq Project Management ion ue pour la province du Kasaï- Central ZR-DRC-MSP-325958-CS-IND V / Recrutement d’un Assista Capacity Strengthening and En cours d'exécut IDA / 64410 A posteriori Individuel Open - National 57,000.00 0.00 2022-12-20 2022-11-28 2023-02-07 2023-02-28 2023-04-04 2023-10-01 nt technique en Santé publiq Project Management ion ue pour la province du Kwilu ZR-DRC-MSP-325959-CS-IND V / Recrutement d’un Assista Capacity Strengthening and En cours d'exécut IDA / 64410 A posteriori Individuel Open - National 57,000.00 0.00 2022-12-20 2022-11-28 2023-02-07 2023-02-28 2023-04-04 2023-10-01 nt technique en Santé publiq Project Management ion ue pour la province du Sud-Ki vu ZR-DRC-MSP-282026-CS-CD Improving the Delivery of Co Sélection de cons S / Contrat avec CCP/JHU pou mmunity Interventions and IDA / 64410 A posteriori ultants par entent Direct 466,615.75 0.00 Annulé 2022-04-26 2022-05-06 2022-07-10 2023-01-06 r la recherche formative sur Social and Behavioral Chang e directe la nutrition et la planification e ZR-DRC-MSP-282023-CS-CD Improving the Delivery of Co S / Contrat avec CCP/JHU pou Sélection de cons mmunity Interventions and r le développement de la str IDA / 64410 A priori ultants par entent Direct 948,153.81 0.00 Annulé 2022-10-25 2022-11-04 2023-01-08 2023-07-07 Social and Behavioral Chang atégie de communication po e directe e ur le changement social et d e comportement ZR-DRC-MSP-319202-CS-CD S / Recrutement de Monsieur Willy N'SHOLE en qualité de Sélection de cons Capacity Strengthening and Consultant individuel chargé IDA / 64410 A posteriori ultants par entent Direct - National 45,000.00 0.00 Signé 2022-11-25 2022-12-02 2022-12-05 2022-12-14 2023-02-08 2023-03-15 2023-08-07 Project Management de contrôle et surveillance d e directe es travaux de réhabilitation d es locaux devant abriter les bureaux du PRONANUT ZR-DRC-MSP-212889-CS-IND V / Recrutement d'une assist IDA / 64410 CERC A posteriori Individuel Open 30,000.00 0.00 Annulé 2021-03-23 2021-12-03 2021-05-11 2021-06-01 2021-07-06 2022-01-02 ante de programme ZR-DRC-MSP-104593-CS-IND V / Recrutement d'un consult ant individuel pour les étude Capacity Strengthening and / A posteriori Individuel Limited 50,000.00 0.00 Annulé 2019-07-31 2019-08-05 2019-08-26 2019-09-30 2020-03-28 s de faisabilité et de concepti Project Management on des infrastructures d'eau hygiène et assainissement ZR-DRC-MSP-105650-CS-IND Improving the Delivery of Co V / Recrutement d'un consult mmunity Interventions and / A posteriori Individuel Limited 350,000.00 0.00 Annulé 2019-05-23 2019-05-28 2019-06-18 2019-07-23 2020-01-19 ant pour faire l'état des lieux Social and Behavioral Chang des FOSA dans les cinq provi e nces ciblées ZR-DRC-MSP-212885-CS-IND V / Recrutement d' un Consul tant individuel pour évaluer l es besoins en appui en terme Capacity Strengthening and s de renforcement des capaci IDA / 64410 A posteriori Individuel Open 15,000.00 0.00 Annulé 2021-03-26 2021-05-14 2021-06-04 2021-07-09 2022-01-05 Project Management tés techniques, opérationnell es et managériales au CAPSA Benalongo pour contribuer e fficacement dans la producti on et la diffusion des semenc es ZR-DRC-MSP-334421-CS-IND Improving the Delivery of Co V / Recrutement de Monsieur mmunity Interventions and BANYWESIZE CHIGANGU Cla IDA / 64410 A posteriori Individuel Direct - National 56,400.00 0.00 Signé 2023-01-20 2023-01-18 2023-01-30 2023-01-24 2023-02-20 2023-02-02 2023-03-27 2023-02-13 2023-09-23 Social and Behavioral Chang ude en qualité d'Assistant Te e chnique en Nutrition pour le PMNS ZR-DRC-MSP-334424-CS-IND V / Recrutement de Monsieur Capacity Strengthening and Yancy KABONGO en qualité d IDA / 64410 A posteriori Individuel Direct - National 36,000.00 0.00 Signé 2023-01-20 2023-01-15 2023-01-30 2023-01-26 2023-02-20 2023-01-31 2023-03-27 2023-02-10 2023-09-23 Project Management e Consultant Individuel Comp table pour le PMNS ZR-DRC-MSP-334426-CS-IND V / Recrutement de Monsieur Capacity Strengthening and MUNGU Philémon en qualité IDA / 64410 A posteriori Individuel Direct - National 36,000.00 0.00 Annulé 2023-01-20 2023-01-15 2023-01-30 2023-01-26 2023-02-20 2023-03-27 2023-09-23 Project Management de Consultant Individuel Com ptable pour le PMNS ZR-DRC-MSP-343081-CS-IND V / Recrutement de Madame Capacity Strengthening and IDA / 64410 A posteriori Individuel Direct - National 36,000.00 0.00 Signé 2023-02-20 2023-02-27 2023-03-02 2023-03-01 2023-03-23 2023-03-02 2023-04-27 2023-03-12 2023-10-24 Sylvie NGEVESISE en qualité Project Management de Consultant Comptable po ur le PMNS ZR-DRC-MSP-343083-CS-IND V / Renouvellement du contr Capacity Strengthening and En attente d'exéc at de Monsieur Olivier MBO IL IDA / 64410 A posteriori Individuel Direct - National 67,200.00 0.00 2023-02-20 2023-03-02 2023-03-23 2023-04-27 2023-10-24 Project Management ution ENGA en qualité de Spécialist e en Passation des Marchés p our le PMNS ZR-DRC-MSP-344301-CS-IND V / Recrutement d'un deuxiè Capacity Strengthening and En cours d'exécut IDA / 64410 A posteriori Individuel Limited 67,200.00 0.00 2023-03-15 2023-02-27 2023-03-20 2023-04-10 2023-05-15 2023-11-11 me Spécialiste en Passation Project Management ion des Marchés pour le PMNS Page 11 ZR-DRC-MSP-246445-CS-CD S / Contractualisation par ent ente directe (ED) avec INACO , Institut National des Archive Sélection de cons Capacity Strengthening and s du Congo, pour l’archivage IDA / 64410 A posteriori ultants par entent Direct 200,000.00 0.00 Annulé 2021-08-26 2021-08-20 2021-09-05 2021-11-09 2022-05-08 Project Management électronique et physique des e directe données et documents de l’U nité de Gestion du Programm e de Développement du Syst ème de Santé, « UG – PDSS ZR-DRC-MSP-325928-CS-CD S / Contractualisation avec JH U pour l’élaboration de la str Improving the Delivery of Co atégie de communication po Sélection de cons mmunity Interventions and Direct - Internation En cours d'exécut ur le changement social et d IDA / 64410 A priori ultants par entent 9,000,000.00 0.00 2023-03-31 2023-04-13 2023-04-10 2023-05-19 2023-06-14 2023-12-11 Social and Behavioral Chang al ion e comportement (CCSC) en f e directe e aveur d’une nutrition adéqua te et de la promotion de la pl anification familiale chez les adolescentes et les femmes ZR-DRC-MSP-375730-CS-IND V / Recrutement de Monsieur Capacity Strengthening and Direct - Internation En cours d'exécut Christian SIMBANANIYE en qu IDA / 64410 A posteriori Individuel 158,400.00 0.00 2023-08-15 2023-06-27 2023-08-25 2023-09-15 2023-10-20 2024-04-17 Project Management al ion alité de Spécialiste en Gestio n Financière pour le PMNS ZR-DRC-MSP-375734-CS-IND V / Contractualisation avec M Capacity Strengthening and En cours d'exécut onsieur Claude NTABUYANT IDA / 64410 A posteriori Individuel Direct - National 76,599.60 0.00 2023-08-15 2023-06-27 2023-08-25 2023-09-15 2023-10-20 2024-04-17 Project Management ion WA en qualité d'Assistant Te chnique aux acteurs provinci aux ZR-DRC-MSP-375736-CS-IND V / Contractualisation avec M Capacity Strengthening and En cours d'exécut onsieur Pacifique MUSHAGAL IDA / 64410 A posteriori Individuel Direct - National 73,500.00 0.00 2023-08-15 2023-06-27 2023-08-25 2023-09-15 2023-10-20 2024-04-17 Project Management ion USHA en qualité de Gestionn aire du programme achat str atégique ZR-DRC-MSP-375740-CS-IND V / Contractualisation avec M Capacity Strengthening and En cours d'exécut onsieur Antoine BILONGI en q IDA / 64410 A posteriori Individuel Direct - National 65,919.84 0.00 2023-08-15 2023-06-27 2023-08-25 2023-09-15 2023-10-20 2024-04-17 Project Management ion ualité d'Assistant Technique Gestion et Suivi des contrats ZR-DRC-MSP-375745-CS-IND V / Contractualisation avec M Capacity Strengthening and En cours d'exécut adame Jeanine SELEMANI en IDA / 64410 A posteriori Individuel Direct - National 61,800.00 0.00 2023-08-15 2023-06-27 2023-08-25 2023-09-15 2023-10-20 2024-04-17 Project Management ion qualité de Responsable Admi nistratif et Ressources Humai nes ZR-DRC-MSP-375748-CS-IND V / Contractualisation avec M Capacity Strengthening and En cours d'exécut IDA / 64410 A posteriori Individuel Direct - National 64,119.84 0.00 2023-08-15 2023-06-27 2023-08-25 2023-09-15 2023-10-20 2024-04-17 onsieur Jules MBANGU en qu Project Management ion alité d'Auditeur Interne ZR-DRC-MSP-375756-CS-IND V / Contractualisation avec M Capacity Strengthening and En cours d'exécut adame Gisèle MPOYI en quali IDA / 64410 A posteriori Individuel Direct - National 60,360.00 0.00 2023-08-15 2023-06-27 2023-08-25 2023-09-15 2023-10-20 2024-04-17 Project Management ion té de Spécialiste 2 en Passati on des marchés pour le PMN S ZR-DRC-MSP-375770-CS-IND V / Contractualisation avec M onsieur Célestin KALEKA ILU Capacity Strengthening and En attente d'exéc IDA / 64410 A posteriori Individuel Direct - National 60,360.00 0.00 2023-08-15 2023-08-25 2023-09-15 2023-10-20 2024-04-17 NGA en qualité d'Assistant Fi Project Management ution nancier chargé de suivi des c ompte de tiers et appui à la Comptabilité ZR-DRC-MSP-376006-CS-IND V / Contractualisation avec M Capacity Strengthening and En cours d'exécut adame Julie MUSEME en quali IDA / 64410 A posteriori Individuel Direct - National 36,000.00 0.00 2023-08-15 2023-06-27 2023-08-25 2023-09-15 2023-10-20 2024-04-17 Project Management ion té d'Assistante Administrativ e et Gestionnaire Site ZR-DRC-MSP-376008-CS-IND V / Contractualisation avec M Capacity Strengthening and En cours d'exécut IDA / 64410 A posteriori Individuel Direct - National 15,034.32 0.00 2023-08-15 2023-06-27 2023-08-25 2023-09-15 2023-10-20 2024-04-17 onsieur Guylain MAFUTA en q Project Management ion ualité d'Assistant en Informat ique ZR-DRC-MSP-376009-CS-IND V / Contractualisation avec M Capacity Strengthening and En cours d'exécut IDA / 64410 A posteriori Individuel Direct - National 28,733.76 0.00 2023-08-15 2023-06-27 2023-08-25 2023-09-15 2023-10-20 2024-04-17 adame Ghislaine FUMU en qu Project Management ion alité d'Assistante Trésorière ZR-DRC-MSP-376012-CS-IND V / Contractualisation avec M Capacity Strengthening and En cours d'exécut adame Sophie MADUNA en q IDA / 64410 A posteriori Individuel Direct - National 23,475.29 0.00 2023-08-15 2023-06-27 2023-08-25 2023-09-15 2023-10-20 2024-04-17 Project Management ion ualité d'Archiviste et Assistan te en Passation des Marchés ZR-DRC-MSP-376013-CS-IND Capacity Strengthening and En cours d'exécut V / Recrutement d'un (e) Assi IDA / 64410 A posteriori Individuel Limited 24,000.00 0.00 2023-08-15 2023-07-20 2023-08-20 2023-09-10 2023-10-15 2024-04-12 Project Management ion stant (e) en passation des Ma rchés ZR-DRC-MSP-357548-CS-IND V / Recrutement d'un Consult Improving the Delivery of Co ant Individuel International p mmunity Interventions and En cours d'exécut IDA / 64410 A posteriori Individuel Limited 70,000.00 0.00 2023-08-31 2023-08-29 2023-09-05 2023-09-26 2023-10-31 2024-04-28 our l'élaboration du module d Social and Behavioral Chang ion e formation des approches m e ultisectorielles en matière de nutrition ZR-DRC-MSP-357549-CS-IND V / Recrutement d'un Consult Improving the Delivery of Co ant Individuel National pour l' mmunity Interventions and En cours d'exécut IDA / 64410 A posteriori Individuel Limited 25,000.00 0.00 2023-08-31 2023-08-28 2023-09-05 2023-09-26 2023-10-31 2024-04-28 élaboration du module de for Social and Behavioral Chang ion mation des approches multis e ectorielles en matière de nut rition ZR-DRC-MSP-357555-CS-CD S / Contractualisation avec la firme BLUESQUARE pour dév elopper et tester un système Sélection de cons Capacity Strengthening and de la vérification basé sur les IDA / 64410 A posteriori ultants par entent Direct - National 350,000.00 0.00 Annulé 2023-08-31 2023-08-25 2023-09-10 2023-09-13 2023-11-14 2024-05-12 Project Management risques, le suivi numérique d e directe es activités communautaires des Recos,la géocartographie des activités de l'Achat strat égique et AT aux SG et ONG Page 12 ZR-DRC-MSP-378670-CS-IND V / Recrutement de quatre (4 Capacity Strengthening and En cours d'exécut IDA / 64410 A posteriori Individuel Limited 144,000.00 0.00 2023-09-20 2023-10-31 2023-09-25 2023-10-16 2023-11-20 2024-05-18 ) Comptables pour les quatre Project Management ion (4) provinces concernées par le PMNS ZR-DRC-MSP-282042-CS-IND Capacity Strengthening and V / Recrutement d'un assista IDA / 64410 A posteriori Individuel Open 54,000.00 0.00 Annulé 2022-03-25 2022-05-13 2022-06-03 2022-07-08 2023-01-04 Project Management nt technique Nutrition ZR-DRC-MSP-376014-CS-IND Capacity Strengthening and V / Recrutement d'un (e) Assi IDA / 64410 A posteriori Individuel Limited 24,000.00 0.00 Annulé 2023-08-15 2023-08-20 2023-09-10 2023-10-15 2024-04-12 Project Management stant Administratif et appui a ux finances ZR-DRC-MSP-381426-CS-IND V / Recrutement d'un Consult Capacity Strengthening and En cours d'exécut ant Gestionnaire de base des IDA / 64410 A posteriori Individuel Limited 56,000.00 0.00 2023-10-15 2023-11-23 2023-10-20 2023-11-10 2023-12-15 2024-06-12 Project Management ion données en appui au Spéciali ste en Suivi Evaluation ZR-DRC-MSP-381438-CS-IND V / Recrutement d'un Consult ant Individuel International e Capacity Strengthening and En attente d'exéc IDA / 64410 A posteriori Individuel Limited 72,000.00 0.00 2023-09-30 2023-10-05 2023-10-26 2023-11-30 2024-05-28 n charge de l'évaluation des i Project Management ution nterventions des ONG de la p lanification familiale avant l'e xtension des contrats ZR-DRC-MSP-382638-CS-IND V / Contractualisation avec M onsieur Charles MBUYI WA M POYI en qualité de Consultan Capacity Strengthening and En cours d'exécut IDA / 64410 A posteriori Individuel Direct - National 40,000.00 0.00 2023-10-10 2023-10-05 2023-10-20 2023-11-10 2023-12-15 2024-06-12 t Spécialiste Senior en Passat Project Management ion ion des Marchés pour évaluer les dossiers de Passation des Marchés des 4 provinces d'in tervention du PMNS ZR-DRC-MSP-382640-CS-IND V / Recrutement d'un Consult Capacity Strengthening and En cours d'exécut IDA / 64410 A posteriori Individuel Limited 70,000.00 0.00 2023-10-15 2023-10-05 2023-10-20 2023-11-10 2023-12-15 2024-06-12 ant Senior pour les activités Project Management ion agricoles lors des crises alim entaires ZR-DRC-MSP-382642-CS-IND V / Recrutement d'un Consult ant Individuel en charge de l' actualisation du manuel des Capacity Strengthening and En cours d'exécut IDA / V2420 A posteriori Individuel Limited 20,000.00 0.00 2023-09-30 2023-09-25 2023-10-05 2023-10-26 2023-11-30 2024-05-28 procédures administratives, f Project Management ion inancières et comptables de l 'UG-PDSS ainsi que l'élaborat ion du manuel de gestion des bureaux provinciaux ZR-DRC-MSP-382644-CS-IND V / Contractualisation avec M Capacity Strengthening and En cours d'exécut aître NKUNDA MUSUMBU Barl IDA / V2420 A posteriori Individuel Direct - National 37,500.00 0.00 2023-09-30 2023-09-29 2023-10-10 2023-10-31 2023-12-05 2024-06-02 Project Management ion y en qualité d'Avocat Conseil en appui à l'UG-PDSS ZR-DRC-MSP-357697-CS-IND V / Recrutement d’un Consult ant Individuel Ingénieur char Capacity Strengthening and IDA / 64410 A posteriori Individuel Open - National 45,000.00 0.00 Annulé 2023-05-31 2023-07-19 2023-08-09 2023-09-13 2024-03-11 gé de suivi des activités de r Project Management éhabilitation des structures s anitaires dans la province du Kwilu ZR-DRC-MSP-357684-CS-IND V / Recrutement d'un Consult ant Individuel Ingénieur char Capacity Strengthening and IDA / 64410 A posteriori Individuel Open - National 45,000.00 0.00 Annulé 2023-06-30 2023-08-18 2023-09-08 2023-10-13 2024-04-10 gé de suivi des activités de r Project Management éhabilitation des structures s anitaires dans la province du Kasaï ZR-DRC-MSP-357692-CS-IND V / Recrutement d’un Consult ant Individuel Ingénieur char Capacity Strengthening and IDA / 64410 A posteriori Individuel Open - National 45,000.00 0.00 Annulé 2023-05-31 2023-07-19 2023-08-09 2023-09-13 2024-03-11 gé de suivi des activités de r Project Management éhabilitation des structures s anitaires dans la province du Kasaï Central ZR-DRC-MSP-357700-CS-IND V / Recrutement d’un Consult ant Individuel Ingénieur char Capacity Strengthening and IDA / 64410 A posteriori Individuel Open - National 45,000.00 0.00 Annulé 2023-05-31 2023-07-19 2023-08-09 2023-09-13 2024-03-11 gé de suivi des activités de r Project Management éhabilitation des structures s anitaires dans la province du Sud-Kivu ZR-DRC-MSP-329777-CS-IND V / Recrutement d'un Consult ant Individuel Expert Pharma Capacity Strengthening and cien en charge de suivi des a IDA / 64410 A posteriori Individuel Open - National 56,000.00 0.00 Annulé 2022-12-31 2023-02-18 2023-03-11 2023-04-15 2023-10-12 Project Management cquisitions en médicaments et autres intrants effectués p ar l'UG-PDSS aux niveaux de s provinces ZR-DRC-MSP-197607-CS-IND V / Consultant International c Capacity Strengthening and IDA / V2420 A posteriori Individuel Open 50,000.00 0.00 Annulé 2021-02-02 2021-03-23 2021-04-13 2021-05-18 2021-11-14 hargé de l'élaboration du pla Project Management n stratégique du PNSA ZR-DRC-MSP-212880-CS-IND V / Recrutement d'un Consult Capacity Strengthening and IDA / 64410 A posteriori Individuel Open 50,000.00 0.00 Annulé 2021-03-16 2021-05-04 2021-05-25 2021-06-29 2021-12-26 ant international pour l'élabo Project Management ration du plan stratégique d u PNSR ZR-DRC-MSP-378675-CS-IND V / Recrutement d'un Consult ant Architecte en appui à l’U G-PDSS pour la validation de Capacity Strengthening and En attente d'exéc IDA / 64410 A posteriori Individuel Limited 50,000.00 0.00 2023-11-20 2023-11-25 2023-12-16 2024-01-20 2024-07-18 s dossiers techniques de réh Project Management ution abilitation profonde des Form ations Sanitaires (FOSA) et le suivi des travaux dans les Pr ovinces d’intervention du PM NS. ZR-DRC-MSP-381428-CS-IND V / Recrutement de quatre (4 ) Ingénieurs – Points focaux q Improving Service Supply an ui seront chargés du Suivi et IDA / 64410 A posteriori Individuel Open - National 200,000.00 0.00 Annulé 2023-11-20 2024-01-08 2024-01-29 2024-03-04 2024-08-31 d Strategic Purchasing Evaluation des travaux de ré habilitation des formations sanitaires dans les différente s provinces appuyées par le PMNS Page 13 ZR-DRC-MSP-392165-CS-CD S / Contractualisation avec B LUESQUARE pour le Dévelop pement d’un système de Sui Sélection de cons Capacity Strengthening and vi numérique des activités co IDA / 64410 A posteriori ultants par entent Direct - National 468,728.00 0.00 Signé 2023-11-20 2023-11-10 2023-11-30 2023-09-13 2024-02-03 2023-11-28 2024-08-01 Project Management mmunautaires de Nutrition e e directe t l’Appui technique au Secrét ariat Général de la Santé dan s le cadre de l’exécution du P roject PMNS ZR-DRC-MSP-395484-CS-IND V / Recrutement d'un Ingénie ur en infrastructure – Point fo Capacity Strengthening and En attente d'exéc cal qui sera chargé du Suivi e IDA / 64410 A posteriori Individuel Limited 54,000.00 0.00 2023-12-15 2023-12-20 2024-01-10 2024-02-14 2024-08-12 Project Management ution t Evaluation des travaux de r éhabilitation des formations sanitaires dans les différente s provinces appuyées par le PMNS ZR-DRC-MSP-395568-CS-CD S / Contractualisation avec l' Sélection de cons Convergence Demonstration En attente d'exéc EUP Nord Kivu pour la Provin IDA / 64410 A posteriori ultants par entent Direct - National 296,860.00 0.00 2024-01-20 2024-01-30 2024-04-04 2024-10-01 Project ution ce de NORD KIVU dans le cad e directe re de la mise en œuvre du P MNS ZR-DRC-MSP-395572-CS-CD S / Contractualisation avec l' Sélection de cons Convergence Demonstration En attente d'exéc EUP Sud Ubangi pour la provi IDA / 64410 A posteriori ultants par entent Direct - National 296,860.00 0.00 2024-01-20 2024-01-30 2024-04-04 2024-10-01 Project ution nce de SUD UBANGI dans le c e directe adre de la mise en œuvre du PMNS ZR-DRC-MSP-395574-CS-CD S / Contractualisation avec l' Sélection de cons Convergence Demonstration En attente d'exéc EUP Tshuapa pour la provinc IDA / 64410 A posteriori ultants par entent Direct - National 296,860.00 0.00 2024-01-20 2024-01-30 2024-04-04 2024-10-01 Project ution e de TSHUAPA dans le cadre e directe de la mise en œuvre du PMN S ZR-DRC-MSP-395576-CS-CD S / Contractualisation avec l' Sélection de cons Convergence Demonstration En attente d'exéc EUP Mongala pour la provinc IDA / 64410 A posteriori ultants par entent Direct - National 296,860.00 0.00 2024-01-20 2024-01-30 2024-04-04 2024-10-01 Project ution e de MONGALA dans le cadre e directe de la mise en œuvre du PMN S ZR-DRC-MSP-395579-CS-CD S / Contractualisation avec l' Sélection de cons Convergence Demonstration En attente d'exéc EUP Katanga pour la provinc IDA / 64410 A posteriori ultants par entent Direct - National 296,860.00 0.00 2024-01-20 2024-01-30 2024-04-04 2024-10-01 Project ution e de HAUT LOMAMI dans le c e directe adre de la mise en œuvre du PMNS ZR-DRC-MSP-395591-CS-CD S / Contractualisation avec l' Sélection de cons Convergence Demonstration En attente d'exéc EUP Bandundu pour les provi IDA / 64410 A posteriori ultants par entent Direct - National 430,520.00 0.00 2024-01-20 2024-01-30 2024-04-04 2024-10-01 Project ution nces de KWANGO et MAINDO e directe MBE dans le cadre de la mise en œuvre du PMNS ZR-DRC-MSP-395679-CS-IND V / Recrutement d'un Assista nt technique en charge du su Capacity Strengthening and En attente d'exéc IDA / 64410 A posteriori Individuel Limited 54,000.00 0.00 2023-12-20 2023-12-25 2024-01-15 2024-02-19 2024-08-17 ivi de la mise en œuvre du pr Project Management ution ogramme d'accouchement gr atuit et les ONG de la planific ation familiale ZR-DRC-MSP-403728-CS-CD S / Contractualisation avec le Sélection de cons Groupement FIDEXCA s.a.r.l- Capacity Strengthening and Direct - Internation En cours d'exécut IDA / 64410 A posteriori ultants par entent 78,000.00 0.00 2024-01-31 2024-01-25 2024-02-10 2024-02-02 2024-04-15 2024-10-12 FAUCON pour réaliser l'Audit Project Management al ion e directe financier et comptables des P rojets de l’UG-PDSS, exercice 2023 ZR-DRC-MSP-412104-CS-IND Improving the Delivery of Co V / Recrutement de Monsieur mmunity Interventions and En attente d'exéc KALALA MBUYAMBA Danny e IDA / 64410 A posteriori Individuel Direct - National 60,000.00 0.00 2024-02-28 2024-03-09 2024-03-30 2024-05-04 2024-10-31 Social and Behavioral Chang ution n qualité d'Assistant Techniq e ue en Nutrition en appui à l'U G-PDSS Page 14