Procurement 1. Procurement for the project will be carried out in accordance with the World Bank’s “Guidelines: Procurement of Goods, Works, and Non-Consulting Services under IBRD Loans and IDA Credits & Grants” dated January 2011 (revised July 2014); and “Guidelines: Selection and Employment of Consultants under IBRD Loans and IDA Credits & Grants by World Bank Borrowers” dated January 2011 (revised 2014); and the provisions stipulated in the Loan Agreement and the POM and GOM. The World Bank Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by IBRD Loans and IDA Credit and Grants dated October 15, 2006 and revised on January 2011, would also apply. Procurement arrangements and capacity assessment 2. Considering the complexity of the project and the weak procurement and management capacity at the MoESTD, the risk rating is assessed as “high.” The procurement method and prior review thresholds applicable to the project will be based on the ECA Regional Maximum Procurement Thresholds, effective January 2, 2014 (revised February 10, 2015). Table 1. Procurement Thresholds PROCUREMENT METHOD THRESHOLDS PRIOR REVIEW THRESHOLDS ICB: =/>EUR 900,000 (Goods); =/>EUR All 4.5M (Works) NCB: EUR 265,000 =/> EUR 450,000 CQS: EUR 2,000 accordance with paras. 3.8-3.11 of the Consultant Guidelines Direct Contracting – none, in accordance =/>EUR45,000 with paras. 3.7 & 3.8 of the Procurement Guidelines 3. All TORs are subject to prior review irrespective of prior/post review status. 4. A detailed Project Operational Manual (POM) and Grants Operational Manual (GOM) is being prepared. The manuals will include procurement and selection methods to be used in the project along with their step–by-step explanation as well as the standard and sample documents to be used for each method, and service standards, responsibilities and accountability of PMU and CFU staff and management for carrying out the activities. 5. Risk Mitigation: The following measures were agreed to mitigate the risks and maintain the implementing team’s capacity. Table 2. Procurement Mitigation Actions Risk Mitigation Delay in project implementation due to • Retroacting financing of key challenges in setting up the CFU and consultant positions in the CFU and PMU and in selecting qualified PMU so that selection can be consultants. launched before or immediately after negotiations. These key consultants will complete/revise the procurement plan and prepare the draft bidding documents and TORs for the initial packages. Limited procurement capacity of the CFU • All TORs for consulting services are and lack of knowledge of Bank’s subject to the Bank’s prior review. procurement and consultant guidelines • The selection process for the 3 CFU may delay selection/bidding process and positions are subject to the Bank’s contract management prior review. • Training will be provided to the procurement specialist especially in regard to the use of System Tracking of Exchanges in Procurement (STEP). • Additional procurement and FM training will be provided to the staff. • Post review of contracts. • CFU staff, especially the procurement expert, will attend procurement training organized by the Bank. • CFU will be provided with full set of the relevant, most recent Bank procurement documents, including but not limited to standard and sample bidding documents, proposal formats, evaluation report documents, etc. Risk Mitigation Unsatisfactory quality of technical • All TORs are subject to the Bank’s designs/ToRs may lead to delays in prior review. contract implementation and to contract • Bank team will provide MoESTD amendments with sample TORs as needed. • Preparation of draft technical specifications/terms of reference before project effectiveness, at least for the contracts for which the selection process is to take place in the first 12 months of the project implementation; • Technical assistance of Bank technical experts in the review of the TOR/TS and designs. The public officials/technical staff who • POM and GOM will detail service will be involved in project procurement standards, responsibilities and through tender committees may not be accountability of CFU staff, PMU familiar with the applicable procurement staff, and technical staff procedures, slowing down the management for carrying out the procurement process activities. • The order for appointment of evaluation committees will specify the timeframe by which the evaluation committee should complete evaluation and recommendation of award. Insufficient technical capacity within • A coordinator for each component MoESTD to coordinate and supervise will be financed under the project. activities may cause contract • Adequate consulting services and supervision delays related to technical assistance, training, implementation and poor quality of knowledge exchange will be goods, works and services. financed by the project to supplement the existing capacity. • Bank staff will provide intensive and close supervision. Procurement Plan 6. The Borrower, at appraisal, prepared a draft procurement plan for the first 18 months of project implementation (see Table 4), which provides the relevant activities to be procured and forms the basis for procurement methods. It does not yet include the Bank’s review requirements and thresholds as these will be determined based on the costs. The procurement plan will be further reviewed and agreed between the Borrower and the Bank during negotiations. The Procurement Plan will then be updated on a regular basis as needed, in agreement with the Bank, to reflect the actual project implementation needs. Table 4. Procurement Plan Reference Description of Activity No. Com ponent 1 - Ex panding the s uply of pres chool s ervices(approx im ately $34M) 1a Renovation, Repurposing and Expansion of Buildings for Preschools 1b Technical docum entation for m odel kindergardens in formfactors 4 to 10 groups 1c Construction or renovation of Innovative ECEC Centers 1d Design Services and Author Supervision 1e Construction Supervision Services 1f Furniture and Equipm ent for Preschools (including toys and playgrounds) 1g Training for local architects and engineers Com ponent 2 - Ens uring the quality of pres chool S ervices(approx imately $5M) Sub-com bonent 2.1: Supporting the im plem entation of the preschool curriculum 2.1a TA to Evaluate & reform/harmonize the systemand curriculumframework for initial educaion of ECEC teachers 2.1b Teacher training Sub-com bonent 2.2: Im proving pre- and in-service teacher training 2.2.a TA to im prove the content & form s of teacher professional developm ent 2.2.b Harm onization of current legislation on preschool education Sub-com bonent 2.3: Im proving the m onitoring and evaluation of preschools to im prove decision-m aking 2.3.a EMIS +Module for MoLEVSA MIS for Subsidies TA Developm ent of in-service training programfor im plem entation of the new curriculumand the developm ent 2.3.b of teaching-learning m aterials (e.g. guidelines, m anuals, etc.) based on the new curriculum 2.3.c TA assessm ent of the existing quality evaluation instrum ents and m ethodology and their im provem ent 2.3.d TA to develop strategies to expand and regulate the provision of ECEC Com ponent 3 - S upporting young children and fam ilies(approxim ately $9M) Sub-com bonent 3.1: Com m unication cam paign 3.1a Preparation of com mucation strategy 3.1b TV Broadcast over licensed TV stations 3.1c Radio Broadcast over licensed radio stations Sub-com ponent 3.2: Outreach to vulnerable fam ilies 3.2a Grants to at least 30 m unicipalities Sub-com ponent 3.3: Subsidies to ensure free preschool participation am ong the m ost vulnerable children 3.3a Annual reim bursem ent of up to $1M Com ponent 4: Project m anag em ent, technical as sistance, and m onitoring and evaluation (approx im ately $2M) Sub-com ponent 4.1: Project m anagem ent and technical assistance 4.1a Project Director 4.1b Coordinator of Com ponent 1 4.1c Coordinator of Com ponent 2 4.1d Coordinator of Com ponent 3 4.1e Grant Coordinator 4.1f Safeguard Specialist 4.1g CFU Director 4.1h CFU Procurem ent Specialist 4.1i CFU Financial Managem ent Specialist 4.1j Audit Services 4.1k PMU Office Equipm ent and Furniture 4.1l Operating Expenses Sub-com ponent 4.2: Monitoring and evaluation 4.2a Monitoring & Evaluation Specialist 4.2b Baseline Survey 4.2.c Technical audit of various activities under the project 4.2d Technical evaluation of the first phase of the grant program 4.2e Staff Training Procurement of Goods, Works and Non-Consulting Services 7. The following methods may be used for procurement of goods, works and non-consulting services as agreed in the procurement plan: International Competitive Bidding (ICB), National Competitive Bidding (NCB), Shopping (S), and Direct Contracting (DC). 8. Procurement of Works. Civil works include new construction and rehabilitation of pre-schools. Procurement will be conducted for the most part at the municipal level using NCB as defined in the applicable Guidelines. There is no prequalification anticipated under the project. Works may be packaged into lots depending on the availability of designs, location of schools, and procurement capacity of municipalities involved. In such a case, procurement will be conducted by the CFU. At a minimum, the CFU procurement specialist will be a member of the Evaluation Committee (EC) who will ensure that bid evaluation procedures are observed and bid evaluation report prepared and signed by the EC members. 9. Procurement of Goods. Goods to be procured include furniture, equipment and toys for the schools, among others. Selection of Consultants 10. The following methods may be used for the selection of consultants: Quality and Cost-Based Selection (QCBS), Quality-Based Selection (QBS), Least-Cost Selection (LCS), Fixed Budget Selection (FBS), Selection based on Consultants Qualifications (CQS), Individual Consultant Selection (IC), and Single Source Selection (SSS). The World Bank's Standard Request for Proposals will be used. All Terms of Reference, irrespective of prior/post review status, are subject to Bank’s review and no objection. 11. A variety of consulting services are required (e.g. communication campaign, which is anticipated to be launched under QCBS). Other technical assistance activities required are: analysis of and regulatory changes to encourage expansion of preschool services including reforms, analysis and adjustment of Serbia’s ECEC system to improve its economic and organizational efficiency, improve the content and forms of teacher professional development, and harmonization of the current legislation that regulates preschool education Post-review Percentages and Frequency 12. Contracts not subject to Bank’s prior review would be subject to post review by the Bank’s procurement specialist. Post review of contracts will be carried out once per year. At a minimum, one out of five contracts will be randomly selected for post review. General Procurement Notice 13. The General Procurement Notice (GPN) for the Project will be published in the UN Development Business after loan negotiations. PROCUREMENT Serbia : Inclusive Early Childhood Education and Care PLAN General Information Country: Serbia 2018-09-27 Bank’s Approval Date of the Original Procurement Plan: 2024-02-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P157117 GPN Date: Project Name: Inclusive Early Childhood Education and Care Loan / Credit No: IBRD / 86930 Central Fiduciary Unit Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SER-ECEC-8693YF-NCB-W-19 -40 / Reconstruction, Extensi Expanding the supply of pre Single Stage - One E 1,749,819.5 2020-08-1 on Works and Construction W IBRD / 86930 Post Request for Bids Open - National Signed 2019-04-12 2019-05-24 2019-04-17 2019-05-28 2019-05-27 2019-06-26 2019-06-19 2019-10-04 2019-07-24 2019-10-30 school spaces nvelope 5 7 orks for Preschool Facilities i n Doljevac, Žitorađa and Sre mska Mitrovica SER-ECEC-8693YF-NCB-W-20 -58 / Reconstruction and exte nsion of the existing facilities Golub Mira and Labud, Kruse Expanding the supply of pre Single Stage - One E 2,616,432.9 2022-03-2 IBRD / 86930 Post Request for Bids Open - National Signed 2020-11-30 2021-01-12 2020-12-07 2021-01-18 2021-02-10 2021-02-19 2021-06-17 2021-03-19 2021-07-18 vac (lot1); Construction of th school spaces nvelope 3 1 e preschool facility kindergar ten in Loznicko Polje, Loznica (lot2); Construction of the ne w facility as part of Poletarac , Merosina (lot3) SER-ECEC-8693YF-NCB-W-21 Request for B -63 / Construction works of Pr ids - Small W Expanding the supply of pre Single Stage - One E 1,120,418.5 2022-11-0 eschool Facility in Prokuplje - IBRD / 86930 Post Request for Bids Open - National orks SPD (1 e Signed 2021-07-12 2021-07-27 2021-07-17 2021-08-28 2021-08-26 2021-09-27 2021-11-01 2021-11-01 2021-12-13 school spaces nvelope 6 1 Lot 1 and Extension works of nvelope proc Preschool Facility in Vladičin ess) Han- Lot 2 Request for B SER-ECEC-8693YF-NCB-W-21 ids - Small W -65 / Construction of Prescho Expanding the supply of pre Single Stage - One E 2,719,988.7 2022-12-1 IBRD / 86930 Post Request for Bids Open - National orks SPD (1 e Signed 2021-08-27 2021-11-08 2021-09-03 2021-10-15 2021-12-06 2021-11-14 2022-04-05 2021-12-12 2022-06-09 ol Facilities in Smederevo an school spaces nvelope 7 2 nvelope proc d Sid (Lot 1 and Lot 2) ess) Request for B SER-ECEC-8693YF-NCB-W-21 ids - Small W Expanding the supply of pre Single Stage - One E 2023-01-0 -77 / Construction of Prescho IBRD / 86930 Post Request for Bids Open - National orks SPD (1 e 846,148.69 Signed 2021-11-22 2021-12-15 2021-11-27 2022-01-08 2022-02-07 2022-02-07 2022-04-12 2022-03-14 2022-05-16 school spaces nvelope 8 ol facility-Kindergarten in Tut nvelope proc in ess) Request for B SER-ECEC-8693YF-NCB-W-22 ids - Small W Expanding the supply of pre Single Stage - One E 2024-02-1 -78 / Construction of combine IBRD / 86930 Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-11-10 2022-12-23 2022-11-15 2022-12-27 2022-12-15 2023-02-07 2023-01-14 2023-03-27 2023-02-18 2023-04-12 school spaces nvelope 8 d Preschool facility "Naše det nvelope proc e" in Novi Pazar ess) Request for B SER-8693YF-NCB-W-22-83 / ids - Small W Expanding the supply of pre Single Stage - One E 2024-03-0 Construction of Preschool fac IBRD / 86930 Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-12-02 2022-12-28 2022-12-07 2023-01-24 2023-01-18 2023-02-28 2023-02-17 2023-06-02 2023-03-10 2023-07-20 school spaces nvelope 9 ility in Petrovac na Mlavi nvelope proc ess) Request for B SER-8693YF-NCB-W-22-84 / ids - Small W Expanding the supply of pre Single Stage - One E 2024-03-2 Construction of Preschool Fac IBRD / 86930 Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-12-07 2023-04-27 2022-12-12 2023-01-23 2023-06-02 2023-02-22 2023-08-14 2023-03-22 2023-10-01 school spaces nvelope 1 ility in Ćićevac nvelope proc ess) Request for B SER-8693YF-NCB-W-22-85 / ids - Small W Expanding the supply of pre Single Stage - One E 2024-03-2 Construction of Preschool Fac IBRD / 86930 Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2022-12-15 2023-06-07 2022-12-20 2023-01-31 2023-07-14 2023-03-02 2023-08-30 2023-03-30 2023-10-05 school spaces nvelope 9 ility in Leskovac nvelope proc ess) Request for B SER-8693YF-NCB-W-23-89 / ids - Small W Expanding the supply of pre Single Stage - One E 2024-03-3 Construction of a children's i IBRD / 86930 Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2023-06-30 2023-07-07 2023-07-10 2023-08-10 2023-08-03 2023-08-28 2023-11-30 2023-09-22 school spaces nvelope 1 nstitution - kindergarten in Kr nvelope proc agujevac ess) Request for B SER-8693YF-NCB-W-23-90 / ids - Small W Expanding the supply of pre Single Stage - One E 2024-03-3 Construction of a children's i IBRD / 86930 Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2023-06-30 2023-07-07 2023-07-10 2023-08-10 2023-08-04 2023-08-28 2023-09-20 2023-09-22 school spaces nvelope 1 nstitution - kindergarten in Al nvelope proc eksandrovac ess) Request for B SER-8693YF-NCB-W-23-91 / ids - Small W Expanding the supply of pre Single Stage - One E 2024-03-3 Construction of a children's i IBRD / 86930 Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2023-07-10 2023-07-07 2023-07-20 2023-08-21 2023-08-07 2023-09-11 2023-10-27 2023-10-06 2023-11-22 school spaces nvelope 1 nstitution in Prijepolje nvelope proc ess) Request for B SER-8693YF-NCB-W-23-92 / ids - Small W Expanding the supply of pre Single Stage - One E 2024-03-3 Construction of a kindergarte IBRD / 86930 Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2023-07-10 2023-07-07 2023-07-20 2023-08-21 2023-08-08 2023-09-11 2023-11-16 2023-10-13 school spaces nvelope 1 n building in Čačak nvelope proc ess) Request for B SER-8693YF-NCB-W-23-94 / ids - Small W Expanding the supply of pre Single Stage - One E Under Imple 2024-03-3 Construction of a building for IBRD / 86930 Post Request for Bids Open - National orks SPD (1 e 0.00 2023-07-10 2023-08-04 2023-07-13 2023-08-10 2023-09-11 2023-08-20 2023-09-12 school spaces nvelope mentation 1 preschool education in Alibun nvelope proc ar ess) Request for B SER-8693YF-NCB-W-23-96 / ids - Small W Expanding the supply of pre Single Stage - One E 2024-03-3 Extension of the kindergarte IBRD / 86930 Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2023-07-10 2023-08-04 2023-07-13 2023-08-10 2023-09-13 2023-08-21 2023-12-19 2023-09-14 school spaces nvelope 1 n building in Pećinci nvelope proc ess) Request for B SER-8693YF-NCB-W-23-95 / ids - Small W Expanding the supply of pre Single Stage - One E 2024-03-3 Construction of the kindergar IBRD / 86930 Post Request for Bids Open - National orks SPD (1 e 0.00 Signed 2023-07-21 2023-08-04 2023-07-28 2023-08-27 2023-09-12 2023-09-10 2023-11-14 2023-10-01 school spaces nvelope 1 ten "Sunce 2" in Aranđelova nvelope proc c ess) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SER-ECEC-8693YF-RFQ-G-21 -71 / Procurement of wooden furniture and other equipme Expanding the supply of pre Request for Quota Single Stage - One E nt for furnishing children's ro IBRD / 86930 Post Limited 78,772.45 Signed 2021-09-03 2021-09-10 2021-10-29 2021-11-20 2022-01-27 school spaces tions nvelope oms and other spaces in new ly built facilities of preschool institutions in Doljevac (Puko vac) and Žitorađa Page 1 SER-ECEC-8693YF-RFQ-G-21 -70 / Supply and delivery of t oys, didactic material, sports Expanding the supply of pre Request for Quota Single Stage - One E equipment and props for equ IBRD / 86930 Post Limited 0.00 Canceled 2021-09-03 2021-09-08 2021-10-15 2021-11-09 school spaces tions nvelope ipping children's rooms in ne wly built preschool facilities i n Doljevac (Pukovac) and Žit orađa SER-ECEC-8693YF-DC-G-21- 70-2 / Supply and delivery of toys, didactic material, sport Expanding the supply of pre s equipment and props for eq IBRD / 86930 Post Direct Selection Direct 0.00 Canceled 2021-10-07 2021-09-30 2021-10-08 2021-10-11 2021-10-27 2021-11-21 school spaces uipping children's rooms in n ewly built preschool facilities in Doljevac (Pukovac) and Žit orađa SER-ECEC-8693YF-SH-G-21- 73 / Shopping of Furniture for Children's Rooms in Preschoo Expanding the supply of pre Request for Quota Single Stage - One E IBRD / 86930 Post Limited 83,300.96 Signed 2021-11-05 2021-11-10 2021-12-24 2022-02-04 2022-05-31 l Institutions Novi Sad (Kalim school spaces tions nvelope ero), Loznica (Bambi), Zemu n (Zemunski Biser), Cacak (L ane), and Pirot (Lane) SER-ECEC-8693YF-SH-G-21- 74 / Shopping of IT equipmen t for children's rooms in pre-s Expanding the supply of pre Request for Quota Single Stage - One E IBRD / 86930 Post Limited 84,935.68 Signed 2021-11-05 2021-11-02 2021-12-24 2022-01-27 2022-05-31 chool institutions Novi Sad (K school spaces tions nvelope alimero), Loznica (Bambi), Ze mun (Zemunski biser), Cacak (Lane), and Pirot (Lane) SER-ECEC-8693YF-SH-G-21- 72 / Shopping of Printing and distributing handbooks, guid Strengthening the quality of Request for Quota Single Stage - One E ebooks and the related mate IBRD / 86930 Post Limited 118,455.36 Signed 2021-11-26 2021-11-01 2022-01-21 2021-12-11 2023-01-27 preschool services tions nvelope rial to support the preschool curriculum framework imple mentation and preschool ins titutions self-evaluation SER-ECEC-8693YF-NCB-G-21 Expanding the supply of pre Single Stage - One E -62 / Procurement of Furnitur IBRD / 86930 Post Request for Bids Open - National 448,095.03 Signed 2021-12-06 2022-02-09 2021-12-17 2022-02-11 2022-03-23 2022-03-13 2022-04-20 2022-04-04 2022-05-22 2022-12-30 school spaces nvelope e for 106 Preschool Institutio ns SER-ECEC-8693YF-NCB-G-21 Expanding the supply of pre Single Stage - One E -75 / Procurement of ICT Equi IBRD / 86930 Post Request for Bids Open - National 534,364.56 Signed 2021-12-06 2022-01-18 2021-12-17 2022-02-11 2022-03-03 2022-03-13 2022-04-08 2022-04-04 2022-05-17 2022-12-30 school spaces nvelope pment for 106 Preschool Insti tutions SER-ECEC-8693YF-DC-G-21- 70-2-2 / Supply and delivery of toys, didactic material, spo Expanding the supply of pre rts equipment and props for IBRD / 86930 Post Direct Selection Direct 5,609.32 Signed 2021-12-03 2021-11-23 2021-12-10 2021-11-24 2022-01-12 2022-01-25 2022-02-11 school spaces equipping children's rooms in newly built preschool facilitie s in Doljevac (Pukovac) and Z itoradja SER-ECEC-8693YF-SH-G-22- 86 / Shopping of furniture for Expanding the supply of pre Request for Quota Single Stage - One E IBRD / 86930 Post Limited 0.00 Signed 2022-12-23 2022-12-13 2023-02-01 2023-01-23 2023-05-02 classrooms in pre-school facil school spaces tions nvelope ity “Bambi”, Loznica SER-ECEC-8693YF-DC-G-23- Expanding the supply of pre 87 / Procurement of didactics IBRD / 86930 Post Direct Selection Direct - National 0.00 Signed 2023-01-13 2023-01-11 2023-01-23 2023-01-11 2023-02-06 2023-02-02 2023-04-07 school spaces for pre-school institution "Ba mbi", Loznica SER-ECEC-8693YF-SH-G-23- 98 / Procurement of didactic equipment for children's roo Expanding the supply of pre Request for Quota Single Stage - One E ms in pre-school institutions IBRD / 86930 Post Limited 0.00 Signed 2023-07-24 2023-07-04 2023-08-15 2023-08-24 2023-12-13 school spaces tions nvelope Novi Sad (“Kalimero”), Loznic a (“Bambi”), Zemun (“Zemu nski biser”), Čačak (“Mladost ”), Pirot (“Lane”) SER-ECEC-8693YF-SH-G-23- 99 / PROCUREMENT OF IT EQ Expanding the supply of pre Request for Quota Single Stage - One E UIPMENT FOR 16 PRESCHOO IBRD / 86930 Post Limited 0.00 Signed 2023-08-08 2023-07-20 2023-09-11 2023-10-17 2024-01-09 school spaces tions nvelope L TEACHER TRAINING HIGHE R EDUCATION INSTITUTIONS SER-ECEC-8693YF-DC-G-23- 100 / Procurement of didactic Expanding the supply of pre IBRD / 86930 Post Direct Selection Direct - National 0.00 Signed 2023-08-24 2023-08-24 2023-08-28 2023-08-28 2023-09-18 2023-09-19 2023-10-18 equipment for seven new cla school spaces ssrooms in the newly built ki ndergarten in Sid SER-ECEC-8693YF-DC-G-23- 101 / Procurement of furnitur Expanding the supply of pre IBRD / 86930 Post Direct Selection Direct - National 0.00 Signed 2023-08-24 2023-08-24 2023-08-28 2023-08-28 2023-09-18 2023-09-20 2023-10-18 e for seven new classrooms i school spaces n the newly built kindergarte n in Sid SER-ECEC-8693YF-SH-G-23- 105 / Procurement of didactic Expanding the supply of pre Request for Quota Single Stage - One E IBRD / 86930 Post Limited 0.00 Signed 2023-11-13 2023-11-06 2023-11-29 2023-11-17 2023-12-29 equipment for the newly-buil school spaces tions nvelope t preschool facility in Smeder evo SER-ECEC-8693YF-SH-G-23- 106 / Procurement of furnitur Expanding the supply of pre Request for Quota Single Stage - One E IBRD / 86930 Post Limited 0.00 Signed 2023-11-13 2023-11-06 2023-11-29 2023-11-21 2023-12-29 e for the newly-built prescho school spaces tions nvelope ol facility in Smederevo SER-ECEC-8693YF-RFQ-G-23 -107 / Procurement of didacti Expanding the supply of pre Request for Quota Single Stage - One E IBRD / 86930 Post Limited 0.00 Signed 2024-01-03 2023-12-22 2024-01-31 2024-03-01 c equipment for 9 new presc school spaces tions nvelope hool classrooms in Merosina and Tutin SER-ECEC-8693YF-RFQ-G-23 -108 / Procurement of Furnitu Expanding the supply of pre Request for Quota Single Stage - One E IBRD / 86930 Post Limited 0.00 Signed 2024-01-03 2023-12-22 2024-01-31 2024-03-01 re for 9 new preschool classr school spaces tions nvelope ooms in Merosina and Tutin NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SER-ECEC-8693-YF-SSS-CS-1 8-28 / DEVELOPMENT AND IM PLEMENTATION OF THE CAPA Strengthening the quality of UN Agencies (Dire IBRD / 86930 Prior Direct 3,865,726.44 Signed 2019-02-06 2019-06-09 2022-12-30 CITY BUILDING PROGRAMME preschool services ct) FOR PRE-SCHOOL EDUCATIO N CURRICULUM IMPLEMENTA TION IN SERBIA SER-ECEC-8693YF-QCBS-CS- Supporting young children a Quality And Cost- Open - Internationa IBRD / 86930 Prior 2,659,440.82 Signed 2019-02-01 2019-02-07 2019-03-01 2019-04-01 2019-04-26 2019-04-22 2019-05-31 2019-05-24 2019-07-12 2019-06-06 2019-08-30 2019-07-09 2019-10-18 2019-07-28 2022-09-02 19-36 / Public Awareness Ca nd families Based Selection l mpaign SER-ECEC-8693YF-LCS-CS-1 9-38 / AUDIT OF THE ECEC P ROJECT FOR THE YEARS 2018 Project management, techni - FIRST PERIOD, 2019-SECON Least Cost Selecti IBRD / 86930 cal assistance, and monitori Post Open - National 65,247.07 Signed 2019-02-19 2019-02-13 2019-02-26 2019-04-11 2019-02-19 2019-05-09 2019-03-19 2019-06-08 2019-03-28 2019-07-13 2019-04-16 2019-08-17 2019-04-28 2022-12-16 D PERIOD, 2020-THIRD PERIO on ng and evaluation D, 2021-FORTH PERIOD AND 2022-FIFTH PERIOD ENDED O N THE LAST DAY OF THE YEA R FOR THE SAID PERIOD SER-ECEC-8693YF-CQ-CS-19 -39 / IMPROVING THE EVALU ATION SYSTEM OF PRESCHO Strengthening the quality of Consultant Qualifi OL EDUCATION IN SERBIA AN IBRD / 86930 Post Open - National 101,919.79 Signed 2019-03-13 2019-03-18 2019-04-03 2019-05-17 2019-04-22 2019-06-16 2019-05-28 2019-07-21 2019-06-04 2020-01-17 preschool services cation Selection D MONITORING THE PROJECT DEVELOPMENT OBJECTIVE IN THE AREA OF PRESCHOOL ED UCATION QUALITY SER-ECEC-8693YF-CQ-CS-19 Project management, techni Consultant Qualifi -46 / ENVIRONMENTAL CONS IBRD / 86930 cal assistance, and monitori Post Open - National 203,930.14 Signed 2019-11-08 2019-11-04 2019-11-22 2019-12-06 2019-12-05 2019-12-13 2020-02-27 2019-12-19 2020-03-14 2022-12-30 cation Selection ULTING FIRM ng and evaluation SER-ECEC-8693YF-CQ-CS-19 -52 / PERFORMANCE AND OP Project management, techni Consultant Qualifi ERATIONAL AUDIT FOR THE IBRD / 86930 cal assistance, and monitori Post Open - National 59,040.00 Signed 2019-12-27 2020-01-23 2020-01-24 2020-02-23 2020-06-01 2020-03-24 2020-10-07 2020-04-28 2020-10-11 2022-10-31 cation Selection GRANT PROGRAM ng and evaluation FOR IMPROVING THE PROVISI ON OF QUALITY ECEC SERVIC ES SER-ECEC-8693YF-CQ-CS-20 -54 / IMPROVING PROFESSIO Strengthening the quality of Consultant Qualifi IBRD / 86930 Post Open - National 42,349.48 Signed 2020-08-07 2020-07-28 2020-09-04 2020-10-16 2020-09-18 2020-10-23 2021-02-18 2020-11-13 2021-03-08 2021-06-30 NAL DEVELOPMENT OF PRES preschool services cation Selection CHOOL EDUCATION SYSTEM PRACTITIONERS SER-ECEC-8693YF-CQ-CS-20 -57 / Supporting the Develop Strengthening the quality of Consultant Qualifi IBRD / 86930 Post Open - National 73,769.97 Signed 2020-09-30 2020-09-21 2020-10-28 2020-12-09 2021-03-23 2020-12-16 2021-06-10 2020-12-28 2021-06-19 2022-06-30 ment of Digital Competencie preschool services cation Selection s of Preschool Education Syst em Practitioners SER-ECEC-8693YF-CQ-CS-21 Strengthening the quality of Consultant Qualifi -60 / Improving Preschool Ins IBRD / 86930 Post Open - National 188,471.31 Signed 2021-01-25 2021-01-13 2021-02-22 2021-04-16 2021-04-05 2021-04-23 2021-05-20 2021-05-05 2021-05-27 2022-12-30 preschool services cation Selection titutions Self-Evaluation Proc ess SER-ECEC-8693YF-CQ-CS-24 Strengthening the quality of Consultant Qualifi Pending Impleme -112 / RECRUITMENT SERVIC IBRD / 86930 Post Open - National 0.00 2024-02-23 2024-03-15 2024-04-12 2024-05-12 2024-06-04 2024-10-12 preschool services cation Selection ntation ES FOR EMIS DATA ENTRY OF FICERS INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SER-ECEC-8693YF-IC-CS-17- Expanding the supply of pre Individual Consult 03 / Central Fiduciary Unit (C IBRD / 86930 Prior Open 182,834.47 Signed 2017-10-06 2017-10-30 school spaces ant Selection FU) Procurement Specialist SER-ECEC-8693YF-IC-CS-17- Expanding the supply of pre Individual Consult 02 / Central Fiduciary Unit (C IBRD / 86930 Prior Open 182,834.47 Signed 2017-10-06 2017-10-30 school spaces ant Selection FU) Financial Management S pecialist SER-ECEC-8693YF-IC-CS-17- Expanding the supply of pre Individual Consult IBRD / 86930 Prior Open 241,178.95 Signed 2017-10-06 2017-10-30 01 / CFU Director school spaces ant Selection SER-ECEC-8693YF-IC-CS-17- Expanding the supply of pre Individual Consult IBRD / 86930 Prior Open 273,887.91 Signed 2017-10-17 2017-11-07 04 / PMU Director school spaces ant Selection SER-ECEC-8693YF-IC-CS-18- Project management, techni Individual Consult 14 / CENTRAL FIDUCIARY UNI IBRD / 86930 cal assistance, and monitori Prior Open 239,330.32 Signed 2018-10-03 2018-10-04 2018-11-21 2018-10-08 2018-12-12 2018-10-08 2019-01-16 2018-10-24 2019-07-15 ant Selection T (CFU) DIRECTOR ng and evaluation SER-ECEC-8693YF-IC-CS-18- Project management, techni Individual Consult 16 / Project Coordinator for C IBRD / 86930 cal assistance, and monitori Post Open 186,764.41 Signed 2018-11-30 2019-01-18 2018-09-27 2019-02-08 2018-11-05 2019-03-15 2018-11-13 2019-09-11 ant Selection omponent 1 ng and evaluation SER-ECEC-8693-YF-SSS-CS-1 Project management, techni Individual Consult 8-17 / Junior Engineer for Co IBRD / 86930 cal assistance, and monitori Post Direct 78,678.00 Signed 2018-11-30 2018-11-05 2018-12-10 2018-12-31 2018-11-05 2019-02-04 2018-11-18 2019-08-03 ant Selection mponent 1 ng and evaluation Project management, techni SER-ECEC-8693-YF-IC-CS-18- Individual Consult IBRD / 86930 cal assistance, and monitori Post Open 112,712.08 Signed 2018-11-30 2019-01-18 2018-09-27 2019-02-08 2018-11-05 2019-03-15 2018-11-18 2019-09-11 18 / Project Architect ant Selection ng and evaluation SER-ECEC-8693-YF-IC-CS-18- Project management, techni 19 / Engineer responsible for Individual Consult IBRD / 86930 cal assistance, and monitori Post Open 68,697.19 Completed 2018-11-30 2019-01-18 2019-02-08 2018-11-02 2019-03-15 2018-11-16 2019-09-11 2023-01-19 Bidding Procedures, Monitori ant Selection ng and evaluation ng Contracts and Constructio n Works SER-ECEC-8693-YF-IC-CS-18- Project management, techni Individual Consult 20 / Structural Engineer part IBRD / 86930 cal assistance, and monitori Post Open 27,297.60 Completed 2018-11-30 2019-01-18 2019-02-08 2018-11-02 2019-03-15 2018-11-15 2019-09-11 2019-11-12 ant Selection time ng and evaluation SER-ECEC-8693-YF-IC-CS-18- Project management, techni Individual Consult 21 / Mechanical Engineer par IBRD / 86930 cal assistance, and monitori Post Open 27,297.60 Signed 2018-11-30 2019-01-18 2018-11-02 2019-02-08 2018-11-02 2019-03-15 2018-11-15 2019-09-11 ant Selection t time ng and evaluation Page 3 SER-ECEC-8693-YF-IC-CS-18- Project management, techni Individual Consult 23 / Urban Planning Engineer IBRD / 86930 cal assistance, and monitori Post Open 27,280.00 Completed 2018-11-30 2019-01-18 2019-02-08 2018-11-02 2019-03-15 2018-11-15 2019-09-11 2019-11-12 ant Selection part time ng and evaluation SER-ECEC-8693-YF-IC-CS-18- Project management, techni Individual Consult 24 / Legal Expert for Compon IBRD / 86930 cal assistance, and monitori Post Open 69,664.98 Signed 2018-11-30 2019-01-18 2019-02-08 2018-11-02 2019-03-15 2018-11-16 2019-09-11 ant Selection ent 1 part time ng and evaluation SER-ECEC-8693-YF-IC-CS-18- Project management, techni Individual Consult 25 / Component 1 Economist IBRD / 86930 cal assistance, and monitori Post Open 70,411.14 Signed 2018-11-30 2019-01-18 2019-02-08 2018-11-23 2019-03-15 2018-12-06 2019-09-11 ant Selection part-time ng and evaluation SER-ECEC-8693-YF-IC-CS-18- Project management, techni Individual Consult 27 / Project Coordinator for C IBRD / 86930 cal assistance, and monitori Post Open 146,381.38 Signed 2018-12-10 2018-12-07 2019-02-13 2019-01-18 2019-03-08 2019-01-18 2019-04-16 2019-01-25 2022-12-30 ant Selection omponent Three ng and evaluation Project management, techni SER-ECEC-8693-YF-IC-CS-17- Individual Consult IBRD / 86930 cal assistance, and monitori Post Open 122,405.18 Signed 2018-12-07 2017-12-08 2019-02-10 2018-02-28 2019-03-05 2018-02-28 2019-04-13 2018-03-07 2022-12-27 07 / Project Assistant ant Selection ng and evaluation Project management, techni SER-ECEC-8693-YF-IC-CS-18- Individual Consult IBRD / 86930 cal assistance, and monitori Post Open 179,606.03 Signed 2018-12-07 2019-02-10 2018-07-09 2019-03-05 2018-07-09 2019-04-13 2018-07-17 2022-12-27 10 / Grant Coordinator ant Selection ng and evaluation SER-ECEC-8693-YF-IC-CS-18- Project management, techni Individual Consult 12 / Project Coordinator for C IBRD / 86930 cal assistance, and monitori Post Open 159,429.39 Signed 2018-12-07 2019-02-10 2018-07-09 2019-03-05 2018-07-09 2019-04-13 2018-07-15 2022-12-27 ant Selection omponent Two ng and evaluation Project management, techni SER-ECEC-8693-YF-IC-CS-18- Individual Consult IBRD / 86930 cal assistance, and monitori Post Open 55,602.45 Signed 2018-12-11 2018-12-13 2019-02-22 2019-01-22 2019-03-22 2019-02-08 2019-05-10 2019-02-15 2019-11-06 29 / LEGAL SPECIALIST ant Selection ng and evaluation SER-ECECI-8693YF-IC-CS-19- 30 / Development and Maint Strengthening the quality of Individual Consult enance of the Preschool Educ IBRD / 86930 Post Open 79,091.51 Signed 2019-01-28 2019-01-22 2019-04-08 2019-04-05 2019-05-06 2019-04-16 2019-06-17 2019-04-22 2022-12-30 preschool services ant Selection ation and Monitoring Informa tion System Consultant SER-ECEC-8693YF-IC-CS-19- 32 / Component Two Consult Strengthening the quality of Individual Consult ant for Devising Research Me IBRD / 86930 Post Open 2,126.50 Signed 2019-01-28 2019-01-22 2019-04-29 2019-04-19 2019-06-03 2019-05-07 2019-07-22 2019-05-13 2019-12-23 preschool services ant Selection thodology of Preschool Instit utions Self-Evaluation Practic es SER-ECEC-8693YF-IC-CS-19- 33 / Component Two Consult Strengthening the quality of Individual Consult IBRD / 86930 Post Open 1,603.48 Signed 2019-01-28 2019-01-22 2019-04-10 2019-04-05 2019-05-08 2019-04-16 2019-06-12 2019-04-22 2019-11-12 ant for Conducting Research preschool services ant Selection of Preschool Institutions Self- Evaluation Practices SER-ECEC-8693YF-IC-CS-19- Strengthening the quality of Individual Consult 35 / Preschool Education Ass IBRD / 86930 Post Open 90,722.75 Signed 2019-01-28 2019-01-22 2019-05-01 2019-04-05 2019-05-29 2019-04-25 2019-07-12 2019-04-30 2022-12-30 preschool services ant Selection ociate for Component Two SER-ECEC-8693YF-SSS-CS-1 9-31 / Education Specialist fo Strengthening the quality of IBRD / 86930 Post Direct Selection Direct 4,517.68 Signed 2019-01-28 2019-01-23 2019-02-13 2019-01-30 2019-05-10 2019-02-27 2020-05-10 r Designing and Implementin preschool services g Specific Training Program f or External Evaluators SER-ECEC-8693YF-SSS-CS-1 9-34 / Component Two Educa Strengthening the quality of tion Specialist for Preparing a IBRD / 86930 Post Direct Selection Direct 6,023.57 Signed 2019-01-28 2019-01-23 2019-02-27 2019-01-31 2019-06-07 2019-02-27 2019-11-01 preschool services Draft Rule Book on Keeping R ecords of Educational Activiti es Project management, techni SER-ECEC-8693-YF-IC-CS-19- Individual Consult IBRD / 86930 cal assistance, and monitori Post Open 0.00 Canceled 2019-02-01 2019-06-17 2019-04-12 2019-05-10 2019-06-28 2022-12-30 37 / Electrical Engineer ant Selection ng and evaluation SER-ECEC-8693YF-IC-CS-19- Project management, techni Individual Consult 41 / Environmental Specialist IBRD / 86930 cal assistance, and monitori Post Open 0.00 Canceled 2019-04-18 2019-04-15 2019-05-28 2019-06-03 2019-06-09 2022-12-25 ant Selection (part -time) ng and evaluation Project management, techni SER-ECEC-8693YF-IC-CS-19- Individual Consult IBRD / 86930 cal assistance, and monitori Post Open 52,519.46 Signed 2019-05-17 2019-05-17 2019-07-15 2019-07-29 2019-08-01 2019-08-01 2019-08-21 2019-08-13 2022-12-30 43 / Grant Assistant ant Selection ng and evaluation SER-ECEC-8693YF-SSS-CS-1 Project management, techni 9-42 / Consultant for the pre Individual Consult IBRD / 86930 cal assistance, and monitori Post Direct 3,417.45 Signed 2019-05-15 2019-05-20 2019-05-20 2019-05-20 2019-05-23 2019-05-21 2019-06-07 2019-05-27 2019-09-05 paration of the furniture proc ant Selection ng and evaluation urement specification SER-ECEC-8693YF-IC-CS-19- Project management, techni Individual Consult 44 / Environmental Specialist IBRD / 86930 cal assistance, and monitori Post Open 0.00 Canceled 2019-09-12 2019-09-12 2019-10-13 2019-10-15 2019-10-20 2022-12-30 ant Selection (part-time) ng and evaluation Project management, techni SER-ECEC-8693YF-IC-CS-19- Individual Consult IBRD / 86930 cal assistance, and monitori Post Open 78,015.90 Terminated 2019-09-23 2019-09-16 2019-10-18 2019-09-27 2019-10-25 2019-10-11 2019-11-04 2019-10-16 2022-12-30 45 / Grant Assistent ant Selection ng and evaluation Project management, techni SER-ECEC-8693YF-IC-CS-19- Individual Consult IBRD / 86930 cal assistance, and monitori Post Open 82,160.54 Signed 2019-11-15 2019-11-27 2019-12-27 2020-01-29 2020-01-03 2020-01-31 2020-01-13 2020-02-16 2022-12-30 47 / Financial Associate ant Selection ng and evaluation SER-ECEC-8693-YF-IC-CS-19- Project management, techni Individual Consult 48 / Structural Engineer part IBRD / 86930 cal assistance, and monitori Post Open 50,372.08 Signed 2019-12-02 2019-12-04 2020-01-20 2021-08-10 2020-02-10 2021-08-20 2020-03-16 2021-08-25 2020-09-12 ant Selection time ng and evaluation SER-ECEC-8693-YF-IC-CS-19- Project management, techni Individual Consult 49 / Urban Planning Engineer IBRD / 86930 cal assistance, and monitori Post Open 0.00 Canceled 2019-12-02 2021-08-08 2020-01-20 2020-02-10 2020-03-16 2020-09-12 ant Selection part time ng and evaluation Project management, techni SER-ECEC-8693-YF-IC-CS-19- Individual Consult IBRD / 86930 cal assistance, and monitori Post Open 0.00 Canceled 2019-12-02 2019-12-04 2020-02-10 2020-03-09 2020-04-27 2023-10-30 50 / Electrical Engineer ant Selection ng and evaluation SER-ECEC-8693YF-IC-CS-19- Strengthening the quality of Individual Consult 51 / Associate for Inclusive Pr IBRD / 86930 Post Open 36,413.91 Signed 2019-12-08 2019-12-13 2020-03-10 2020-01-27 2020-04-07 2020-01-28 2020-05-21 2020-02-14 2023-11-09 preschool services ant Selection eschool Education- full time SER-ECEC-8693YF-IC-CS-20- Expanding the supply of pre Individual Consult IBRD / 86930 Post Open 52,032.26 Signed 2020-06-19 2020-06-12 2020-07-24 2020-12-11 2020-07-31 2020-12-21 2020-08-14 2020-12-26 2022-10-31 53 / Junior Architect school spaces ant Selection Page 4 SER-ECEC-8693YF-SSS-CS-2 0-56 / Converting the Presch Strengthening the quality of IBRD / 86930 Post Direct Selection Direct 3,607.89 Signed 2020-09-18 2020-09-17 2020-09-28 2020-09-21 2020-10-27 2020-10-17 2020-12-31 ool Institutions principles trai preschool services ning from in vivo into distanc e-learning format SER-ECEC-8693YF-SSS-CS-2 0-59 / Coordination of Activiti Expanding the supply of pre IBRD / 86930 Prior Direct Selection Direct 2,470,118.62 Signed 2021-01-08 2021-01-13 2021-01-18 2021-01-20 2021-03-01 2021-05-21 2022-12-30 es on Renovating/Repurposin school spaces g and Equipping New Presch ool Classrooms SER-ECEC-8693YF-SSS-CS-2 1-61 / CONSULTANT FOR PRE Project management, techni PARING SPECIFICATION FOR Individual Consult IBRD / 86930 cal assistance, and monitori Post Direct 21,620.70 Signed 2021-04-12 2021-04-07 2021-04-22 2021-04-15 2021-04-26 2021-04-23 2021-05-04 2021-04-30 2021-10-31 PROCURING FURNITURE AND ant Selection ng and evaluation DIDACTIC EQUIPMENT FOR N EWLY BUILT PRESCHOOL FAC ILITIES (PART-TIME CONSULT ANT) SER-ECEC-8693YF-SSS-CS-2 Project management, techni Individual Consult 1-64 / Advisor on Parenting a IBRD / 86930 cal assistance, and monitori Post Direct 60,534.09 Terminated 2021-08-12 2021-08-09 2021-08-22 2021-08-10 2021-08-27 2021-08-16 2021-08-31 2021-08-30 2022-12-30 ant Selection nd Inclusion ng and evaluation SERC-ECEC-8693-YF-IC-CS-2 1-66 / ASSOCIATE FOR SUPP ORTING REFLECTIVE PRACTIC E DEVELOPMENT IN KINDERG Strengthening the quality of Individual Consult IBRD / 86930 Post Open 10,654.06 Signed 2021-08-25 2021-08-25 2021-10-13 2021-10-25 2021-11-03 2021-10-26 2021-12-08 2021-11-12 2022-12-30 ARTENS AS PART OF THE PR preschool services ant Selection OFESSIONAL LEARNING COM MUNITY MODEL – CONSULTA NT FOR KINDERGARTENS IN GROUP ONE (IC) (PART-TIME CONSULTANT) SER-ECEC-8693-YF-IC-CS-21- 67 / ASSOCIATE FOR SUPPOR TING REFLECTIVE PRACTICE DEVELOPMENT IN KINDERGA Strengthening the quality of Individual Consult IBRD / 86930 Post Open 10,654.06 Signed 2021-08-25 2021-08-25 2021-10-13 2021-10-25 2021-11-03 2021-10-26 2021-12-08 2021-11-12 2022-12-30 RTENS AS PART OF THE PROF preschool services ant Selection ESSIONAL LEARNING COMMU NITY MODEL – CONSULTANT FOR KINDERGARTENS IN GR OUP TWO (IC) (PART-TIME CO NSULTANT) SER-ECEC-8693-YF-IC-CS-21- 68 / ASSOCIATE FOR SUPPOR TING REFLECTIVE PRACTICE DEVELOPMENT IN KINDERGA Strengthening the quality of Individual Consult IBRD / 86930 Post Open 10,654.06 Signed 2021-08-25 2021-08-25 2021-10-13 2021-10-25 2021-11-03 2021-10-26 2021-12-08 2021-11-12 2022-12-30 RTENS AS PART OF THE PROF preschool services ant Selection ESSIONAL LEARNING COMMU NITY MODEL – CONSULTANT FOR KINDERGARTENS IN GR OUP THREE (IC) (PART-TIME CONSULTANT) SER-ECEC-8693-YF-IC-CS-21- 69 / ASSOCIATE FOR HORIZO Strengthening the quality of Individual Consult NTAL EXCHANGE BETWEEN P IBRD / 86930 Post Open 5,830.00 Signed 2021-08-25 2021-08-25 2021-10-13 2021-10-13 2021-11-03 2021-10-18 2021-12-08 2021-11-01 2022-12-30 preschool services ant Selection RESCHOOL PRACTITIONERS ( PART-TIME POSITION) (IC) SER-ECEC-8693YF-IC-CS-21- Project management, techni Individual Consult 76 / Monitoring and Evaluatio IBRD / 86930 cal assistance, and monitori Post Open 38,119.52 Signed 2021-11-19 2021-11-04 2022-01-03 2021-12-03 2022-01-17 2021-12-10 2022-01-31 2021-12-15 2022-12-30 ant Selection n Specialist ng and evaluation SER-ECEC-8693YF-SSS-CS-2 2-79 / EXPERT ANALYSIS OF T HE ADEQUACY OF COSTS AND DETERMINATION OF TH Expanding the supply of pre E MARKET VALUE OF PRESCH IBRD / 86930 Post Direct Selection Direct 24,362.40 Signed 2022-07-07 2022-07-07 2022-07-12 2022-07-08 2022-07-15 2022-07-29 2022-12-31 school spaces OOL FACILITIES CONSTRUCTI ON WORKS UNDER THE INCL USIVE CHILDHOOD EDUCATI ON AND CARE (ECEC) PROJEC T SER-ECEC-8693YF-SSS-CS-2 2-80 / PILOTING DRAFT RECO MMENDATIONS FOR THE HAR Strengthening the quality of IBRD / 86930 Post Direct Selection Direct - National 10,263.50 Signed 2022-07-28 2022-07-15 2022-08-05 2022-07-15 2022-08-31 2022-07-24 2023-12-30 MONISATION OF STUDY PRO preschool services GRAMMES/COURSES AND PR OFESSIONAL TRAINING IN TR AINING ROOMS SER-ECEC-8693YF-SSS-CS-2 2-81 / OVERVIEW AND THE A NALYSIS OF HARMONISATION OF STUDY PROGRAMMES OFF Strengthening the quality of IBRD / 86930 Post Direct Selection Direct - National 10,263.50 Signed 2022-07-26 2022-07-15 2022-08-03 2022-07-15 2022-08-31 2022-07-26 2023-12-28 ERED BY PUBLIC PRESCHOOL preschool services TEACHER TRAINING FACULTI ES AND ACADEMIES WITH PR ESCHOOL TEACHER COMPET ENCE STANDARDS SER-ECEC-8693YF-SSS-CS-2 0-82 / PRODUCING RECOMME NDATIONS FOR THE HARMON Strengthening the quality of ISATION OF INNITIAL PRESCH IBRD / 86930 Post Direct Selection Direct - National 10,263.50 Signed 2022-07-26 2022-07-15 2022-08-03 2022-07-15 2022-08-31 2022-07-26 2023-12-28 preschool services OOL TEACHER TRAINING STU DY PROGRAMMES WITH PRES CHOOL TEACHER PROFESSIO NAL COMPETENCE STANDAR DS Project management, techni SER-ECEC-8693YF-IC-CS-23- Individual Consult IBRD / 86930 cal assistance, and monitori Post Limited 0.00 Signed 2023-03-17 2023-03-15 2023-03-31 2023-03-20 2023-04-07 2023-04-25 2023-04-21 2023-05-03 2024-03-31 88 / Liason Officer ant Selection ng and evaluation SER-ECEC-8693YF-SSS-CS-2 3-93 / Analysis of the effects of half-day/flexible preschool Project management, techni programs within Grant Progr IBRD / 86930 cal assistance, and monitori Post Direct Selection Direct - National 0.00 Signed 2023-05-22 2023-05-10 2023-05-29 2023-05-12 2023-06-30 2023-08-02 2023-12-29 am under the ECEC Project, b ng and evaluation y collecting feedback from pa rents/caregivers whose childr en participated in such progr ams SER-ECEC-8693YF-SSS-CS-2 3-97 / Coordination of activiti Expanding the supply of pre IBRD / 86930 Post Direct Selection Direct - National 0.00 Signed 2023-06-09 2023-06-20 2023-06-19 2023-07-07 2023-07-31 2023-08-31 2024-03-01 es on renovating/repurposing school spaces and equipping new preschool classrooms SER-ECEC8693YF-IC-CS-23-1 Expanding the supply of pre Individual Consult 02 / Administrative Assistant IBRD / 86930 Post Limited 0.00 Signed 2023-10-18 2023-10-17 2023-10-20 2023-10-24 2023-11-10 2023-11-03 2023-11-17 2023-11-03 2024-03-31 school spaces ant Selection for Component 1 SER-ECEC-8693YF-IC-CS-23- 104 / Consultant Responsible Expanding the supply of pre Individual Consult IBRD / 86930 Post Limited 0.00 Signed 2023-11-10 2023-11-13 2023-11-17 2023-11-15 2023-12-08 2023-11-21 2023-12-29 2023-11-21 2024-03-31 for Monitoring Contracts and school spaces ant Selection Construction Works Page 5 SER-ECEC-8693YF-IC-CS-23- 109 / Consultant for preparin Strengthening the quality of Individual Consult g methodology for the desk a IBRD / 86930 Post Open - National 0.00 Signed 2023-12-15 2023-12-21 2024-01-29 2024-02-09 2024-01-30 2024-02-14 2024-01-31 2024-05-31 preschool services ant Selection nalysis of the Report on Self- evaluation of PIs in 2021/22 SER-ECEC-8693YF-IC-CS-23- 110 / Consultant for the desk Strengthening the quality of Individual Consult IBRD / 86930 Post Open - National 0.00 Signed 2023-12-15 2023-12-21 2024-01-29 2024-02-09 2024-01-30 2024-02-14 2024-01-31 2024-05-31 analysis of the Report on Self preschool services ant Selection -evaluation of PIs in 2021/22 (first group of PIs) SER-ECEC-8693YF-IC-CS-23- 111 / Consultant for the desk Strengthening the quality of Individual Consult IBRD / 86930 Post Open - National 0.00 Signed 2023-12-15 2023-12-21 2024-01-29 2024-02-09 2024-01-30 2024-02-14 2024-01-31 2024-05-31 analysis of the Report on Self preschool services ant Selection -evaluation of PIs in 2021/22 (Second group of PIs) SER-ECEC-8693YF-SSS-CS-2 Project management, techni Individual Consult Pending Impleme 3-103 / ASSOCIATE FOR COM IBRD / 86930 cal assistance, and monitori Post Direct - National 0.00 2024-02-21 2024-02-22 2024-02-23 2024-02-26 2024-11-29 ant Selection ntation MUNICATION ON SENSITIVE T ng and evaluation OPICS Page 6