Procurement Plan Project: Sustainable Agricultural Intensification & Food Security Project (SAIP): P 164520. Project Implementation agency: SPIU-RAB Date of General Procurement Notice : {TBD } Date of the Procurement Plan: TBA Period covered by this Procurement Plan: From ___to ___ (For the first 18 months). Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP, constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. All Consultancy Services shall be procured following Procurement Regulations and Bank’s SPDs. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Law of Rwanda, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works): Applicable Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not Applicable. Other Relevant Procurement Information: (a). Prior Procurement Arrangements: The Procurement Arrangements as indicated in the below table and within the thresholds indicated in the below tables will be used. The thresholds for the Bank’s prior review requirements are also provided in the table below: (The table below depicts the Thresholds and Procurement Methods to be used under the Sustainable Agricultural Intensification & Food Security Project (SAIP)): Thresholds*, Procurement Methods, and Prior Review Goods, Works, and Non-Consulting Services Method of Procurement Thresholds for Method (US$ equivalent) Open International (Goods) Equal to or more than 4 million Open National ( Goods) < $4 million and > $ 25,000 RFQ (Goods) Less than $ 25,000 Open International (Works) Equal to or more than 15 million Open National (Works) - Less than 15 million RFQ (works) Less than $ 25,000 Open International (Non- Equal to or More than 4 million consulting Services) Open National (Non-consulting Less than 4 million Services) Direct Contracting All contracts less than $ 100,000 Framework Agreements All procurement that meet the requirements as per Para 6.57 to 6.59 of Procurement Regulations., and with prior agreement in PP with the Bank. Method of Procurement Thresholds for Method (US$ equivalent) First FA and All other FAs above USD 4 million are subject to prior review by Bank It is not expected that there will need for prequalification in the procurement arrangements under Sustainable Agricultural Intensification & Food Security Project (SAIP). Selection of Consultants Selection methods of procurement of Consultants' Services (Firms): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Quality and Cost Based As per requirements of para 7.3 of the Selection (QCBS) Regulations Quality Based Selection (QBS) As per requirements of para 7.8 to 7.10 of the Regulations Selection based on a Fixed As per requirements of para 7.4 and 7.5 of Budget (FBS) the Regulations Selection Based on Least Cost As per requirements of para 7.6 and 7.7 of Basis (LCS) the Regulations Selection based on As per requirements of para 7.11 and 7.12 Consultant’s Qualification of the Regulations (CQ) Direct Must meet the requirements of Para 7.13 to 7.15 of the Regulations, and with prior agreement in PP with the Bank. The short list may consist of all National consultants in case the estimated cost is less than USD 300,000 per contract. Procurement methods for Selection of Individual Consultants (IC): The Approved Selection Methods as reflected in the Section VII of the procurement regulations. Method of Procurement Thresholds for Methods Open Competitive Selection As per requirements of para 7.36 and 7.37 of the Regulations Limited Competitive As per requirements of para 7.38 of the Selection Regulations Direct Must meet the requirements of Para 7.39 of the Regulations, and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Regulations Prior Review Thresholds: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection (Project Procurement Risk Rating is “Moderate”): (a) Goods: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 4 million; (b) Works: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 15 million; (c) Consulting Services: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 2 million; and The prior review thresholds will be reviewed during the implementation of the project and modified based on the risk assessment. 1. For contracts subject to prior review, the Borrower shall seek the Bank’s no objection before agreeing to: a. an extension of the stipulated time for execution of a contract that has an impact on the planned completion of the project; b. any material modification of the scope of the Works, Goods, Non-consulting services or Consulting Services, or other significant changes to the terms and conditions of the contract; c. any variation order or contract amendment (except in cases of extreme urgency), including due to extension of time, that singly or combined with all previous variation orders or amendments, increases the original contract amount by more than 15% (fifteen percent); or d. the proposed termination of the contract. The Borrower / IA shall provide a copy of all amendments to the contract to the Bank for its records. 2. Prequalification: Not Applicable Domestic Preference: the provision of domestic preference shall be applied in the evaluation of bids in accordance with Annex VI of the Regulations. 3. Reference to Standard Procurement Documents Bank’s Standard RFB Works & Goods and RFP Consulting Services dated January 2017 will be used as a base and incorporating suitable modifications and the same would be agreed with the Bank subject to international competition. Reference to (if any) Project Operational/Procurement Manual: Yes Any Other Special Procurement Arrangements: N/A Procurement Packages/Plan with Procurement Arrangements and Time Schedule: as per the Table below: Table 4.2: Procurement Packages with Methods and Time Schedule Revie Expecte Expecte w by d Procure d Bank Bid/Pro Cost ment/ Contrac Ref Contract (Prior posal Estimat Selectio t No Description /Post Submiss e (US$) n Complet ) ion Method ion Deadlin Date e I WORKS Construction of 5 drying Decemb Novemb 1.1 200,000 NCB Post shelters/Ground (FY er 2019 er 2020 2019-2020) Construction of 2 March Decemb 1.2 storage (FY 2019- 300,000 NCB Post 2019 er 2019 2020) Construction of 5 March Decemb 1.3 storage (FY 2020- 750,000 NCB Post 2020 er 2021 2021) Construction of 2 collection/market NCB January Novemb 1.4 centres 120,000 Post 2019 er 2019 (horticulture) (FY 2019-2020) Construction of 4 collection/market NCB January Novemb 1.5 centres 240,000 Post 2020 er 2021 (horticulture) (FY 2020-2021) Rehabilitation of existing of post NCB January Novemb 1.6 300,000 Post harvest 2019 er 2020 infrastructures Rehabilitation of existing of post NCB January Novemb 1.7 380,000 Post harvest 2020 er 2021 infrastructures Rehabilitation and January April 1.7 330,000 Post improvements to NCB 2019 2020 Revie Expecte Expecte w by d Procure d Bank Bid/Pro Cost ment/ Contrac Ref Contract (Prior posal Estimat Selectio t No Description /Post Submiss e (US$) n Complet ) ion Method ion Deadlin Date e existing irrigation schemes Expansion of NCB April June 1.8 existing irrigation 820,000 Post 2019 2020 schemes Construction of medium-scale 2,400,00 NCB April October 1.9 Post irrigation scheme 0 2019 2020 development 5,840,0 S/Total 1 00 II GOODS Fittings and tools for maintenance of January 2.1 85,000 NCB Post July 2019 existing irrigation 2019 schemes Supply of irrigation equipment for February Novembe 2.2 operation of 304,000 NCB Post 2019 r 2016 existing irrigation schemes Small-scale 1,462,50 January 2.3 irrigation NCB Post July 2019 0 2019 equipment supply Purchase of post harvest equipment May Decembe 2.4 220,500 NCB Post for SAIP Project (FY 2019 r 2019 2019-2020) Provision of relevant technology October April 2.5 120,000 NCB Post and equipment for 2018 2019 agro-processing Ago-processing October April 2.6 22,500 NCB Post facilities 2018 2019 O&M of existing and June May 2.7 new postharvest 400,000 NCB Post 2019 2020 facilities Revie Expecte Expecte w by d Procure d Bank Bid/Pro Cost ment/ Contrac Ref Contract (Prior posal Estimat Selectio t No Description /Post Submiss e (US$) n Complet ) ion Method ion Deadlin Date e Purchase of IT October February 2.8 Equipment and 33,000 NCB Post 2018 2019 spare parts Maintenance of IT October February 2.9 5,000 NCB Post Equipment 2018 2019 Web and mail Single October February 2.10 2,000 Post hosting Source 2018 2019 Office supplies & October Novembe 2.11 25,000 NCB Post Stationery. 2018 r 2019 Acquisition of insurance services Septemb October 2.12 1,000 RFQ Post for project assets er 2018 2019 and engraving Septemb October 2.13 Engraving service 1,250 Shopping Post er 2018 2019 Novembe April 2.14 Staff refreshment NCB Post 18,000 r 2018 2019 Purchase Fuel for Vehicles, Septemb Novembe 2.15 NCB Post Motorcycles and 25,000 er 2018 r 2019 Generators Purchase lubricants for Vehicles, Novembe April 2.16 NCB Post Motorcycles and 5,000 r 2018 2019 Generators Tyres for Vehicles Decembe May 2.17 NCB Post and Motorcycles 15,000 r 2018 2019 Maintenance of October January 2.18 vehicles and 10,000 NCB Post 2018 2020 motorcycles Acquisition of insurance for April May 2.19 15,000 RFQ Post Vehicles and 2019 2020 Motorcycles Hiring a car at SPIU Septemb Decembe 2.20 31,000 NCB Post head Office er 2018 r 2019 Revie Expecte Expecte w by d Procure d Bank Bid/Pro Cost ment/ Contrac Ref Contract (Prior posal Estimat Selectio t No Description /Post Submiss e (US$) n Complet ) ion Method ion Deadlin Date e Cleaning & Security Septemb Decembe 2.21 7,962 NCB Post services er 2018 r 2019 Maintenance and reparation services of vehicles and Decembe May 2.21 10,000 NCB Post motorcycles r 2018 2020 (framework contract) Procurement of sports services for October January 2.22 LWH staff 10,000 NCB Post 2018 2020 (framework contract) Purchase of training Decembe May 2.23 50,000 NCB Post facilities r 2018 2019 Provision of printing Septemb Decembe 2.24 services for SAIP 150,000 NCB Post er 2018 r 2019 Project Accounting and Single Novembe Decembe 2.25 Management 4,000 Post Source r 2018 r 2019 software Hiring hotel services for conferences, trainings and October January 2.26 200,000 NCB Post workshops at head 2018 2020 office and in sites (fr2amework contract). 3,232,7 S/Total 2 12 III Selection of Consultants Description of Estimat Selectio Revie Expecte Expecte Assignment ed n w by d Ref d Cost Method the Contrac No Proposa USD Worl t l Complet Revie Expecte Expecte w by d Procure d Bank Bid/Pro Cost ment/ Contrac Ref Contract (Prior posal Estimat Selectio t No Description /Post Submiss e (US$) n Complet ) ion Method ion Deadlin Date e d Submiss ion Bank ion Date Hiring consultant Novembe 3.1 firm for conducting 50,000 QCBS Post July 2019 r 2018 baseline studies Hiring individual consultant for Technical Assistance to Septemb April 3.2 18,000 INDIV Post support PFIs to er 2018 2020 uptake agricultural financial products developed Hiring individual consultant for Technical Assistance to February 3.3 12,000 INDIV Post July 2020 support PFIs to 2018 uptake agricultural insurance by cooperatives Supervision for construction of 5 October Decemb 3.4 drying 20,000 QCBS Post 2019 er 2020 shelters/Ground (FY 2019-2020) Supervision construction of 2 collection/market Novembe January 3.5 12,000 QCBS Post centres r 2019 2020 (horticulture) (FY 2019-2020) Supervision of construction of 2 January January 3.6 30,000 QCBS Post storage (FY 2019- 2019 2020 2020) Supervision of January January 3.7 75,000 QCBS Post construction of 2 2020 2021 Revie Expecte Expecte w by d Procure d Bank Bid/Pro Cost ment/ Contrac Ref Contract (Prior posal Estimat Selectio t No Description /Post Submiss e (US$) n Complet ) ion Method ion Deadlin Date e storage (FY 2020- 2021) Supervision of rehabilitation and October April 3.8 improvements to 33,000 QCBS Post 2018 2020 existing irrigation schemes Supervision of expansion of January June 3.9 82,000 QCBS Post existing irrigation 2019 2020 schemes Supervision of medium-scale January October 3.10 240,000 QCBS Post irrigation scheme 2019 2020 development S/Total 3 572,000 Grand Total (Sub-total 9,644,7 1+2+3) 12 Note.QCBS: Quality and Cost Based Selection CQS: Selection Based on Consultants Qualification; QBS: Quality based Selection, LCS: Least Cost selection and INDIV: Individual Consultant *Exchange rate used is 850 Frw per 1USD PROCUREMENT Rwanda : Sustainable Agricultural Intensification and Food Security Project PLAN General Information Country: Rwanda 2019-03-06 Bank’s Approval Date of the Original Procurement Plan: 2024-02-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164520 GPN Date: 2019-01-29 Project Name: Sustainable Agricultural Intensification and Food Security Project Loan / Credit No: TF / A8221, TF / B6154 Rwanda Agriculture and Animal Resources Development Board Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned RW-RAB-97830-CW-RFB / Off Component 4: Project Manag Single Stage - One E 2019-11-0 TF / A8221 Post Request for Bids Open - National 40,000.00 0.00 Canceled 2019-05-13 2019-05-18 2019-06-17 2019-07-08 2019-08-06 ice Rehabilitation and mainte ement and Technical Assista nvelope 4 nance nce RW-RAB-124752-CW-RFB / c Component 3: Market Linkag Single Stage - One E 2020-05-2 onstruction works of drying s TF / A8221 es and Value Addition Invest Post Request for Bids Open - National 149,424.00 128,217.30 Completed 2019-08-28 2019-11-01 2019-09-02 2019-10-02 2019-12-10 2019-10-23 2020-01-10 2019-11-27 2020-03-09 nvelope 5 helters ment Support RW-RAB-124756-CW-RFB / o Component 4: Project Manag Single Stage - One E 2020-04-2 TF / A8221 Post Request for Bids Open - National 32,967.00 5,037.53 Signed 2019-08-30 2021-09-20 2019-09-04 2019-10-04 2021-11-01 2019-10-25 2021-11-19 2019-11-29 2022-02-27 ffice rehabilitation and maint ement and Technical Assista nvelope 7 enance nce RW-RAB-124761-CW-RFB / o Component 3: Market Linkag Single Stage - One E 2021-01-0 peration and maintenance of TF / A8221 es and Value Addition Invest Post Request for Bids Open - National 336,264.00 69,874.40 Completed 2019-10-10 2020-02-28 2019-10-15 2019-11-14 2020-05-04 2019-12-05 2020-05-13 2020-01-09 2020-07-09 nvelope 8 existing and new post harves ment Support t facilities RW-RAB-187529-CW-RFB / C Component 2: Irrigation and Single Stage - One E 2021-05-1 onstruction works of water p TF / A8221 Post Request for Bids Open - National 37,473.00 23,223.07 Completed 2020-09-22 2020-12-02 2020-10-02 2020-11-01 2021-01-08 2020-11-22 2021-02-17 2020-12-14 2021-05-12 water use efficiency nvelope 4 oint borehole at SAIP Site RW-RAB-187563-CW-RFB / C Component 3: Market Linkag Single Stage - One E 2021-11-2 onstruction works of post har TF / A8221 es and Value Addition Invest Post Request for Bids Open - National 133,833.00 0.00 Canceled 2020-10-09 2020-10-16 2020-11-15 2020-12-06 2021-05-28 nvelope 4 vest facilities ment Support RW-RAB-249078-CW-RFB / C Request for Bids - Component 3: Market Linkag onstruction works for post ha Single Stage - One E Small Works SPD 2022-08-2 TF / A8221 es and Value Addition Invest Post Request for Bids Open - National 555,072.00 793,768.13 Signed 2021-11-07 2021-11-15 2021-11-12 2021-12-12 2021-12-16 2022-01-02 2022-01-06 2022-01-30 2022-03-06 rvest facilities, selling points nvelope (1 envelope proce 8 ment Support and construction of hygiene ss) and sanitation facilities Request for Bids - RW-RAB-249366-CW-RFB / R Component 2: Irrigation and Single Stage - One E Works (without pr 2022-12-2 ehabilitation works for irrigati TF / A8221 Post Request for Bids Open - National 350,000.00 19,748.22 Signed 2021-09-27 2021-09-17 2021-10-02 2021-11-01 2021-10-18 2021-12-01 2021-10-29 2021-12-29 2022-02-09 water use efficiency nvelope equalification) SP 9 on infrastructures for SAIP irri D gation schemes Request for Bids - RW-RAB-271418-CW-RFB / I Component 2: Irrigation and Single Stage - One E Small Works SPD Under Imple 2022-12-1 mproved of irrigation water a TF / B6154 Post Request for Bids Open - National 495,125.00 0.00 2022-01-23 2022-04-04 2022-01-28 2022-04-25 2022-02-27 2022-07-18 2022-03-20 2022-08-08 2022-04-17 water use efficiency nvelope (1 envelope proce mentation 4 ccessibility in Cyarubare end ss) command area Request for Bids - RW-RAB-302580-CW-RFB / c Component 2: Irrigation and Single Stage - One E Small Works SPD Under Imple 2023-04-2 TF / B6154 Post Request for Bids Open - National 33,000.00 0.00 2022-09-13 2023-04-20 2022-09-18 2023-05-02 2022-10-18 2022-11-08 2022-11-30 onstruction of water points water use efficiency nvelope (1 envelope proce mentation 9 ss) Request for Bids - RW-RAB-345614-CW-RFB / O Component 4: Project Manag Single Stage - One E Small Works SPD Under Imple 2024-09-0 TF / A8221 Post Request for Bids Open - National 63,000.00 0.00 2023-06-18 2023-06-30 2023-06-23 2023-07-17 2023-07-23 2023-07-31 2023-08-13 2023-08-30 2023-09-10 ffice rehabilitation and maint ement and Technical Assista nvelope (1 envelope proce mentation 9 enance nce ss) Request for Bids - RW-RAB-377306-CW-RFB / P Component 3: Market Linkag Single Stage - One E Small Works SPD Pending Imp 2024-07-2 ost harvest facilities rehabilit TF / A8221 es and Value Addition Invest Post Request for Bids Open - National 261,000.00 0.00 2023-10-10 2023-10-15 2023-11-26 2023-12-26 2024-01-30 nvelope (1 envelope proce lementation 8 ation ment Support ss) Request for Bids - RW-RAB-302458-CW-RFB / R Component 3: Market Linkag Single Stage - One E Small Works SPD 2023-10-1 ehabilitation of the post harv TF / B6154 es and Value Addition Invest Post Request for Bids Open - National 115,646.00 0.00 Canceled 2022-08-14 2022-08-19 2022-09-18 2022-10-09 2022-10-17 nvelope (1 envelope proce 7 est facilities ment Support ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-RAB-97482-GO-RFB / Off Component 4: Project Manag Single Stage - One E TF / A8221 Post Request for Bids Open - National 16,000.00 9,594.97 Completed 2019-03-04 2019-05-20 2019-03-09 2019-04-08 2019-06-24 2019-04-29 2019-07-16 2019-05-28 2019-08-18 2019-07-27 2019-09-15 ice supplies & Stationery for ement and Technical Assista nvelope SAIP Project nce RW-RAB-97773-GO-RFB / Sta Component 4: Project Manag Single Stage - One E TF / A8221 Post Request for Bids Open - National 8,000.00 7,037.95 Completed 2019-03-20 2019-05-30 2019-03-25 2019-04-24 2019-07-02 2019-05-15 2019-07-12 2019-06-13 2019-08-31 2020-06-12 2020-03-02 ff refreshment ement and Technical Assista nvelope nce RW-RAB-97776-GO-RFQ / Pu Component 4: Project Manag Request for Quota Single Stage - One E TF / A8221 Post Limited 2,000.00 0.00 Canceled 2019-05-01 2019-06-13 2019-07-13 rchase lubricants for Motorcy ement and Technical Assista tions nvelope cles nce RW-RAB-97778-GO-RFB / Tyr Component 4: Project Manag Single Stage - One E TF / A8221 Post Request for Bids Open - National 8,000.00 5,020.53 Completed 2019-03-06 2019-06-07 2019-03-11 2019-04-10 2019-07-10 2019-05-01 2019-07-24 2019-05-30 2019-09-18 2019-07-29 2019-09-30 es for Vehicles and Motorcycl ement and Technical Assista nvelope es nce Component 1: Institutional S RW-RAB-97790-GO-RFB / Pur trengthening, Agriculture Pr Single Stage - One E chase inputs, signs and labou TF / A8221 Post Request for Bids Open - National 34,000.00 15,982.34 Completed 2019-03-18 2019-05-30 2019-03-23 2019-04-22 2019-07-02 2019-05-13 2019-09-05 2019-06-11 2019-10-06 2019-12-08 2019-10-29 oductivity Enhancement and nvelope r for FFS/demos plots Nutrition Improvement RW-RAB-97803-GO-RFQ / Pr Component 4: Project Manag Request for Quota Single Stage - One E ovision of facilities for Nation TF / A8221 ement and Technical Assista Post Limited 1,100.00 854.39 Completed 2019-05-31 2019-06-10 2019-07-05 2019-07-08 2019-08-04 2019-07-08 tions nvelope al Agriculture show nce RW-RAB-97807-GO-RFQ / Pu Component 4: Project Manag Request for Quota Single Stage - One E TF / A8221 Post Limited 1,400.00 1,242.79 Completed 2019-03-16 2019-06-03 2019-04-28 2019-08-07 2019-06-27 2019-08-07 rchase of TV screen and Proj ement and Technical Assista tions nvelope ector nce Component 1: Institutional S RW-RAB-97811-GO-RFQ / Su trengthening, Agriculture Pr Request for Quota Single Stage - One E pply of water cans and nails f TF / A8221 Post Limited 1,200.00 894.04 Completed 2019-03-16 2019-06-12 2019-04-28 2019-07-24 2019-05-28 2019-07-30 oductivity Enhancement and tions nvelope or nurseries Nutrition Improvement Component 1: Institutional S RW-RAB-97828-GO-RFB / Su trengthening, Agriculture Pr Single Stage - One E pply of plastic tubing for nurs TF / A8221 Post Request for Bids Open - National 92,240.00 73,864.58 Completed 2019-03-12 2019-05-15 2019-03-17 2019-04-16 2019-06-20 2019-05-07 2019-07-03 2019-06-05 2019-07-31 2019-08-04 2019-11-19 oductivity Enhancement and nvelope eries Nutrition Improvement Page 1 RW-RAB-103016-GO-RFB / S Component 4: Project Manag Single Stage - One E upply of fuel for vehicles, mo TF / A8221 ement and Technical Assista Post Request for Bids Open - National 67,500.00 21,877.40 Completed 2019-03-11 2018-10-31 2019-03-16 2019-04-15 2018-12-31 2019-05-06 2018-12-11 2019-06-10 2019-01-30 2020-06-09 2020-03-21 nvelope torcycles and generator nce RW-RAB-103022-GO-RFQ / H iring hotel services for provisi Component 3: Market Linkag Request for Quota Single Stage - One E on of meeting facilities for Co TF / A8221 es and Value Addition Invest Post Limited 2,000.00 0.00 Canceled 2019-04-08 2019-05-04 2019-06-03 tions nvelope operatives with potential loca ment Support l buyers for Irish potatoes Est ablishment of platform RW-RAB-103024-GO-RFQ / H iring hotel services for provisi Component 1: Institutional S on of meeting facilities for Co trengthening, Agriculture Pr Request for Quota Single Stage - One E operatives with potential Vali TF / A8221 Post Limited 2,000.00 0.00 Canceled 2019-03-19 2019-04-18 2019-05-18 oductivity Enhancement and tions nvelope dation workshop of the SWO Nutrition Improvement T Analysis report and develo pment of a plan for the way f orward RW-RAB-103025-GO-RFQ / H Component 4: Project Manag Request for Quota Single Stage - One E iring hotel services for Launc TF / A8221 ement and Technical Assista Post Limited 2,000.00 0.00 Canceled 2019-03-09 2019-04-07 2019-05-07 tions nvelope hing SAIP Project nce Component 1: Institutional S RW-RAB-103029-GO-RFQ / S trengthening, Agriculture Pr Request for Quota Single Stage - One E upply of Pesticides for nurser TF / A8221 Post Limited 1,400.00 0.00 Canceled 2019-03-24 2019-04-26 2019-05-26 oductivity Enhancement and tions nvelope ies Nutrition Improvement Component 1: Institutional S RW-RAB-103031-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E upply of shanding net for nur TF / A8221 Post Request for Bids Open - National 18,000.00 11,902.80 Completed 2019-03-11 2019-05-15 2019-03-16 2019-04-15 2019-06-20 2019-05-06 2019-07-03 2019-06-10 2019-08-08 2019-09-08 2019-12-11 oductivity Enhancement and nvelope series Nutrition Improvement Component 1: Institutional S RW-RAB-124449-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E upply of Lime for Muyanza an TF / A8221 Post Request for Bids Open - National 8,654.00 7,256.43 Completed 2019-07-24 2019-07-19 2019-07-29 2019-08-28 2019-08-20 2019-09-18 2019-11-06 2019-10-16 2019-12-06 2019-11-15 2020-03-17 oductivity Enhancement and nvelope d Nyabihu sites Nutrition Improvement Component 1: Institutional S RW-RAB-124462-GO-RFB / s trengthening, Agriculture Pr Single Stage - One E upply of compost for Muyanz TF / A8221 Post Request for Bids Open - National 15,385.00 14,577.84 Completed 2019-07-24 2019-07-19 2019-07-29 2019-08-28 2019-08-20 2019-09-18 2019-10-16 2019-10-23 2019-11-20 2019-11-22 2019-12-29 oductivity Enhancement and nvelope a season A Nutrition Improvement Component 1: Institutional S RW-RAB-124467-GO-RFB / s trengthening, Agriculture Pr Single Stage - One E upply of compost for nyabihu TF / A8221 Post Request for Bids Open - National 19,231.00 22,509.90 Completed 2019-07-24 2019-07-19 2019-07-29 2019-08-28 2019-08-20 2019-09-18 2019-10-16 2019-10-23 2019-11-20 2019-11-22 2020-01-19 oductivity Enhancement and nvelope site season A Nutrition Improvement Component 1: Institutional S RW-RAB-124478-GO-RFB / s trengthening, Agriculture Pr Single Stage - One E upply of compost for karongi TF / A8221 Post Request for Bids Open - National 11,538.00 10,933.38 Completed 2019-07-24 2019-07-19 2019-07-29 2019-08-28 2019-08-20 2019-09-18 2019-10-16 2019-10-23 2019-11-20 2019-11-22 2020-01-30 oductivity Enhancement and nvelope season A Nutrition Improvement Component 1: Institutional S RW-RAB-124486-GO-RFB / s trengthening, Agriculture Pr Single Stage - One E upply of compost for Nyanza TF / A8221 Post Request for Bids Open - National 9,616.00 9,111.15 Completed 2019-07-24 2019-07-19 2019-07-29 2019-08-28 2019-08-20 2019-09-18 2019-10-16 2019-10-23 2019-11-05 2019-11-22 2019-11-22 oductivity Enhancement and nvelope site season A Nutrition Improvement Component 1: Institutional S RW-RAB-124490-GO-RFB / s trengthening, Agriculture Pr Single Stage - One E upply of compost for Rwama TF / A8221 Post Request for Bids Open - National 30,220.00 30,013.20 Completed 2019-07-24 2019-07-19 2019-07-29 2019-08-28 2019-08-20 2019-09-18 2019-10-16 2019-10-23 2019-11-07 2019-11-22 2020-04-09 oductivity Enhancement and nvelope gana sites Nutrition Improvement Component 1: Institutional S RW-RAB-124493-GO-RFB / s trengthening, Agriculture Pr Single Stage - One E upply of lime for Rwamagana TF / A8221 Post Request for Bids Open - National 11,538.00 9,880.53 Completed 2019-07-24 2019-07-19 2019-07-29 2019-08-28 2019-08-20 2019-09-18 2019-11-06 2019-10-23 2019-12-04 2019-11-22 2020-04-02 oductivity Enhancement and nvelope and Kayonza sites season A Nutrition Improvement Component 1: Institutional S RW-RAB-124604-GO-RFB / s trengthening, Agriculture Pr Single Stage - One E upply of lime for Nyanza and TF / A8221 Post Request for Bids Open - National 5,289.00 5,279.25 Completed 2019-07-25 2019-07-19 2019-07-30 2019-08-29 2019-08-20 2019-08-31 2019-11-06 2019-10-05 2019-12-04 2019-10-08 2020-02-21 oductivity Enhancement and nvelope Karongi site season A Nutrition Improvement Component 1: Institutional S RW-RAB-124611-GO-RFB / s trengthening, Agriculture Pr Single Stage - One E upply of lime compost for Ka TF / A8221 Post Request for Bids Open - National 19,231.00 29,852.42 Completed 2019-07-25 2019-07-19 2019-07-30 2019-08-29 2019-08-20 2019-09-19 2019-10-16 2019-10-24 2019-11-05 2019-11-23 2020-03-05 oductivity Enhancement and nvelope yonza site Nutrition Improvement RW-RAB-124613-GO-RFB / s Component 2: Irrigation and Single Stage - One E upply and installation of sign TF / A8221 Post Request for Bids Open - National 14,181.00 14,725.26 Completed 2019-08-14 2019-09-25 2019-08-19 2019-09-18 2019-10-25 2019-10-09 2019-11-07 2019-10-31 2020-01-04 2019-12-30 2020-03-16 water use efficiency nvelope posts for access roads and re servoirs Component 1: Institutional S RW-RAB-124621-GO-RFB / a trengthening, Agriculture Pr Single Stage - One E TF / A8221 Post Request for Bids Open - National 153,130.00 11,487.54 Completed 2019-07-25 2020-02-12 2019-07-30 2019-08-29 2020-03-13 2019-09-19 2020-04-01 2019-10-24 2020-06-11 2020-10-23 2021-07-02 cquisition of vegetable seeds oductivity Enhancement and nvelope Nutrition Improvement RW-RAB-124629-GO-RFB / p Component 4: Project Manag Single Stage - One E urchase of fuel for vehicles, TF / A8221 ement and Technical Assista Post Request for Bids Open - National 32,967.00 32,406.30 Completed 2019-07-25 2019-07-17 2019-07-30 2019-08-29 2019-08-19 2019-09-28 2019-08-20 2019-11-02 2019-09-29 2020-11-01 2020-07-03 nvelope motorcycles and generators nce Component 1: Institutional S RW-RAB-124632-GO-RFB / p trengthening, Agriculture Pr Single Stage - One E urchase of chicken breed and TF / A8221 Post Request for Bids Open - National 32,836.00 12,606.48 Completed 2019-07-29 2019-11-14 2019-08-03 2019-09-02 2019-11-28 2019-09-23 2019-12-13 2019-10-28 2020-02-29 2020-01-26 2020-06-25 oductivity Enhancement and nvelope feeding packages Nutrition Improvement RW-RAB-124634-GO-RFB / p Component 4: Project Manag Single Stage - One E TF / A8221 Post Request for Bids Open - National 164,835.00 153,260.00 Completed 2019-08-21 2019-11-06 2019-08-28 2019-09-27 2019-12-30 2019-10-18 2020-01-16 2019-11-22 2020-03-18 2020-01-21 2020-07-02 urchase of four (4) vehicles ement and Technical Assista nvelope nce RW-RAB-124648-GO-RFB / s Component 2: Irrigation and Single Stage - One E upply, installation and maint TF / A8221 Post Request for Bids Open - National 164,835.00 46,208.29 Signed 2019-08-20 2020-01-24 2019-08-25 2019-08-28 2020-02-28 2019-08-30 2020-03-06 2019-10-04 2020-07-07 2020-10-03 water use efficiency nvelope enance/repairs of irrigation in frastructures RW-RAB-124653-GO-RFB / s Component 1: Institutional S upply and installation of gree trengthening, Agriculture Pr Single Stage - One E TF / A8221 Post Request for Bids Open - National 32,967.00 42,908.30 Completed 2019-07-25 2019-08-09 2019-07-30 2019-08-29 2019-09-09 2019-09-19 2019-09-27 2019-10-18 2019-11-15 2019-12-17 2019-12-31 n house in Nyanza, Muyanza oductivity Enhancement and nvelope and Rwamagana Nutrition Improvement Component 1: Institutional S RW-RAB-124658-GO-RFB / s trengthening, Agriculture Pr Single Stage - One E upply and installation of gree TF / A8221 Post Request for Bids Open - National 65,934.00 42,881.33 Completed 2019-09-10 2019-10-16 2019-09-15 2019-10-15 2019-11-15 2019-11-14 2019-11-18 2019-12-19 2019-12-29 2020-02-17 2020-03-21 oductivity Enhancement and nvelope n house Nutrition Improvement Page 2 RW-RAB-124674-GO-RFB / s upply and installation of smal Component 2: Irrigation and Single Stage - One E TF / A8221 Post Request for Bids Open - National 782,417.00 11,292,836.81 Signed 2019-08-16 2020-01-06 2019-08-30 2019-09-29 2020-02-06 2019-10-20 2020-02-27 2019-11-24 2020-09-11 2020-11-23 l scale irrigation technology ( water use efficiency nvelope SSIT) implementation Component 1: Institutional S RW-RAB-124677-GO-RFB / p trengthening, Agriculture Pr Single Stage - One E TF / A8221 Post Request for Bids Open - National 15,825.00 0.00 Canceled 2019-09-12 2019-12-11 2019-09-17 2019-10-17 2019-11-07 2019-12-12 2020-02-10 urchase of spryer pumps oductivity Enhancement and nvelope Nutrition Improvement Component 1: Institutional S RW-RAB-124680-GO-RFB / s trengthening, Agriculture Pr Single Stage - One E upply of lime for Muyanza an TF / A8221 Post Request for Bids Open - National 10,577.00 5,107.81 Completed 2019-09-18 2019-10-16 2019-09-23 2019-09-26 2019-11-18 2019-10-26 2019-12-05 2019-11-30 2020-03-10 2019-12-30 2020-04-29 oductivity Enhancement and nvelope d Nyabihu sites season B Nutrition Improvement Component 1: Institutional S RW-RAB-124682-GO-RFB / s trengthening, Agriculture Pr Single Stage - One E upply of compost for Nyabihu TF / A8221 Post Request for Bids Open - National 19,231.00 10,929.49 Completed 2019-09-18 2019-10-18 2019-09-23 2019-10-23 2019-11-18 2019-11-13 2019-12-06 2019-12-18 2020-03-11 2020-01-17 2020-04-29 oductivity Enhancement and nvelope site Nutrition Improvement Component 1: Institutional S RW-RAB-124686-GO-RFB / s trengthening, Agriculture Pr Single Stage - One E upply of compost for Karongi TF / A8221 Post Request for Bids Open - National 17,692.00 18,622.27 Completed 2019-09-18 2019-10-18 2019-09-23 2019-10-23 2019-11-18 2019-11-13 2019-12-06 2019-12-18 2020-03-04 2020-01-17 2020-04-15 oductivity Enhancement and nvelope site Nutrition Improvement Component 1: Institutional S RW-RAB-124688-GO-RFB / s trengthening, Agriculture Pr Single Stage - One E upply of compost for Kayonz TF / A8221 Post Request for Bids Open - National 19,231.00 16,193.28 Completed 2019-09-18 2019-10-18 2019-09-23 2019-10-23 2019-11-18 2019-11-13 2019-12-06 2019-12-18 2020-03-23 2020-01-17 2020-04-13 oductivity Enhancement and nvelope a site Nutrition Improvement Component 1: Institutional S RW-RAB-124693-GO-RFB / s trengthening, Agriculture Pr Single Stage - One E upply of compost for Rwama TF / A8221 Post Request for Bids Open - National 26,923.00 20,241.60 Completed 2019-09-18 2019-10-18 2019-09-23 2019-10-23 2019-11-18 2019-11-13 2019-12-06 2019-12-18 2020-03-21 2020-01-17 2020-05-06 oductivity Enhancement and nvelope gana site Nutrition Improvement Component 1: Institutional S RW-RAB-124695-GO-RFB / s trengthening, Agriculture Pr Single Stage - One E upply of lime for Rwamagana TF / A8221 Post Request for Bids Open - National 7,693.00 6,006.07 Completed 2019-09-18 2019-10-18 2019-09-23 2019-10-23 2019-11-18 2019-11-13 2019-12-06 2019-12-18 2020-03-06 2020-01-17 2020-05-03 oductivity Enhancement and nvelope and kayonza sites season B Nutrition Improvement Component 1: Institutional S RW-RAB-124698-GO-RFB / s trengthening, Agriculture Pr Single Stage - One E upply of lime for Nyanza and TF / A8221 Post Request for Bids Open - National 6,346.00 10,218.46 Completed 2019-09-18 2019-10-16 2019-09-23 2019-10-23 2019-11-18 2019-11-13 2019-12-06 2019-12-18 2020-03-10 2020-01-17 2020-05-09 oductivity Enhancement and nvelope Korongi sites season B Nutrition Improvement Component 1: Institutional S RW-RAB-124700-GO-RFB / s trengthening, Agriculture Pr Single Stage - One E upply of compost for Nyanza TF / A8221 Post Request for Bids Open - National 15,654.00 46,045.55 Completed 2019-09-18 2019-10-18 2019-09-23 2019-10-23 2019-11-18 2019-11-13 2019-12-06 2019-12-18 2020-03-25 2020-01-17 2020-05-03 oductivity Enhancement and nvelope site Nutrition Improvement Component 1: Institutional S RW-RAB-124702-GO-RFB / s trengthening, Agriculture Pr Single Stage - One E upply of compost for Muyanz TF / A8221 Post Request for Bids Open - National 26,923.00 20,239.80 Completed 2019-09-18 2019-10-18 2019-09-23 2019-10-23 2019-11-18 2019-11-25 2019-12-06 2019-12-24 2020-03-27 2020-01-23 2020-05-05 oductivity Enhancement and nvelope a site Nutrition Improvement RW-RAB-124706-GO-RFB / of Component 4: Project Manag Single Stage - One E TF / A8221 Post Request for Bids Open - National 43,936.00 24,137.56 Completed 2019-09-25 2019-12-11 2019-09-30 2019-10-30 2020-01-13 2019-11-20 2020-01-20 2019-12-25 2020-03-10 2020-12-24 2020-07-07 fice supplies and stationery ement and Technical Assista nvelope nce Component 1: Institutional S RW-RAB-124713-GO-RFB / p trengthening, Agriculture Pr Single Stage - One E TF / A8221 Post Request for Bids Open - National 69,934.00 0.00 Canceled 2019-10-02 2019-12-03 2019-10-07 2019-11-06 2019-11-27 2020-01-01 2020-03-01 urchase of small tractors oductivity Enhancement and nvelope Nutrition Improvement RW-RAB-124720-GO-RFB / s Component 3: Market Linkag Single Stage - One E upply of post harvest equipm TF / A8221 es and Value Addition Invest Post Request for Bids Open - National 242,803.00 15,113.87 Signed 2019-10-03 2020-04-17 2019-10-08 2019-11-07 2020-05-18 2019-11-28 2020-06-05 2020-01-02 2020-09-20 2020-06-30 nvelope ent ment Support Component 1: Institutional S RW-RAB-187357-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E upply of compost for SAIP Ka TF / A8221 Post Request for Bids Open - National 42,827.00 34,555.00 Completed 2020-08-17 2020-07-23 2020-08-18 2020-09-17 2020-08-24 2020-10-08 2020-10-23 2020-10-30 2020-11-30 2021-07-30 2021-09-27 oductivity Enhancement and nvelope yonza site Nutrition Improvement Component 1: Institutional S RW-RAB-187371-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E upply of lime for Gatsibo SAI TF / A8221 Post Request for Bids Open - National 5,353.00 10,077.97 Signed 2020-10-01 2020-12-07 2020-10-04 2020-11-03 2021-01-12 2020-11-24 2021-03-29 2020-12-15 2021-04-27 2021-10-15 oductivity Enhancement and nvelope P site Nutrition Improvement Component 1: Institutional S RW-RAB-187379-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E upply of compost for Muyanz TF / A8221 Post Request for Bids Open - National 102,784.00 96,996.48 Signed 2020-08-17 2020-07-23 2020-08-18 2020-09-17 2020-08-24 2020-10-08 2020-10-23 2020-10-30 2020-11-30 2021-08-30 oductivity Enhancement and nvelope a SAIP site Nutrition Improvement Component 1: Institutional S RW-RAB-187382-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E upply of compost for Nyanza TF / A8221 Post Request for Bids Open - National 77,088.00 69,109.99 Completed 2020-08-17 2020-07-23 2020-08-18 2020-09-17 2020-08-24 2020-10-08 2020-10-23 2020-10-30 2020-11-30 2021-08-30 2021-09-27 oductivity Enhancement and nvelope SAIP site Nutrition Improvement Component 1: Institutional S RW-RAB-187385-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E upply of compost for Karongi TF / A8221 Post Request for Bids Open - National 42,827.00 38,808.26 Completed 2020-08-17 2020-07-23 2020-08-18 2020-09-17 2020-08-24 2020-10-08 2020-10-23 2020-10-30 2020-11-30 2021-08-30 2021-09-27 oductivity Enhancement and nvelope SAIP site Nutrition Improvement Component 1: Institutional S RW-RAB-187389-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E upply of compost for Rwama TF / A8221 Post Request for Bids Open - National 42,827.00 40,415.20 Signed 2020-08-17 2020-07-23 2020-08-18 2020-09-17 2020-08-24 2020-10-08 2020-10-23 2020-10-30 2020-11-30 2021-08-30 oductivity Enhancement and nvelope gana SAIP site Nutrition Improvement Component 1: Institutional S RW-RAB-187390-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E upply of compost for Nyabihu TF / A8221 Post Request for Bids Open - National 42,827.00 23,238.74 Completed 2020-08-17 2020-07-23 2020-08-18 2020-09-17 2020-08-24 2020-10-08 2020-10-23 2020-10-30 2020-11-30 2021-08-30 2021-09-27 oductivity Enhancement and nvelope SAIP site Nutrition Improvement Component 1: Institutional S RW-RAB-187394-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E upply of compost for Gatsibo TF / A8221 Post Request for Bids Open - National 21,413.00 10,103.80 Completed 2020-08-17 2020-07-23 2020-08-18 2020-09-17 2020-08-24 2020-10-08 2020-10-23 2020-10-30 2020-11-30 2021-08-30 2021-09-27 oductivity Enhancement and nvelope SAIP site Nutrition Improvement Component 1: Institutional S RW-RAB-187425-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E upply of plastic tubing for nur TF / A8221 Post Request for Bids Open - National 53,230.00 5.93 Signed 2020-08-17 2020-07-13 2020-08-18 2020-09-17 2020-08-13 2020-10-08 2020-08-28 2020-10-30 2020-10-05 2021-10-30 oductivity Enhancement and nvelope series Nutrition Improvement Page 3 Component 1: Institutional S RW-RAB-187431-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E upply of lime for Kayonza SAI TF / A8221 Post Request for Bids Open - National 10,707.00 10,000.07 Signed 2020-10-01 2020-08-21 2020-10-04 2020-11-03 2021-01-12 2020-11-24 2021-03-29 2020-12-15 2021-04-17 2021-10-15 oductivity Enhancement and nvelope P site Nutrition Improvement Component 1: Institutional S RW-RAB-187434-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E TF / A8221 Post Request for Bids Open - National 27,837.00 10,000.08 Signed 2020-10-01 2020-12-07 2020-10-04 2020-11-03 2021-01-12 2020-11-24 2021-03-29 2020-12-15 2021-04-27 2021-10-15 upply of lime for Nyanza site oductivity Enhancement and nvelope Nutrition Improvement Component 1: Institutional S RW-RAB-187437-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E upply of lime for Rwamagana TF / A8221 Post Request for Bids Open - National 16,060.00 0.07 Signed 2020-10-01 2020-12-07 2020-10-04 2020-11-03 2021-01-12 2020-11-24 2021-03-29 2020-12-15 2021-04-27 2021-10-15 oductivity Enhancement and nvelope SAIP site Nutrition Improvement Component 1: Institutional S RW-RAB-187438-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E upply of lime for Nyabihu SAI TF / A8221 Post Request for Bids Open - National 10,707.00 10,000.07 Signed 2020-10-01 2020-12-07 2020-10-04 2020-11-03 2021-01-12 2020-11-24 2021-01-12 2020-12-15 2021-04-27 2021-10-15 oductivity Enhancement and nvelope P site Nutrition Improvement Component 1: Institutional S RW-RAB-187442-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E upply of lime for Muyanza SA TF / A8221 Post Request for Bids Open - National 27,837.00 87.96 Signed 2020-10-01 2020-12-07 2020-10-04 2020-11-03 2021-01-12 2020-11-24 2021-03-29 2020-12-15 2021-04-27 2021-10-15 oductivity Enhancement and nvelope IP site Nutrition Improvement Component 1: Institutional S RW-RAB-187445-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E upply of lime for Karongi SAI TF / A8221 Post Request for Bids Open - National 16,060.00 10,000.08 Signed 2020-10-01 2020-12-07 2020-10-04 2020-11-03 2021-01-12 2020-11-24 2021-03-29 2020-12-15 2021-04-25 2021-10-15 oductivity Enhancement and nvelope P site Nutrition Improvement RW-RAB-187448-GO-RFB / A Component 1: Institutional S cquisition of chicken, feeding trengthening, Agriculture Pr Single Stage - One E TF / A8221 Post Request for Bids Open - National 165,953.00 40,145.69 Signed 2020-09-02 2020-11-16 2020-09-06 2020-10-06 2020-12-17 2020-10-27 2021-01-05 2020-11-18 2021-03-06 2021-11-18 packages, disease control pa oductivity Enhancement and nvelope ckages and installation of chi Nutrition Improvement cken hatched houses RW-RAB-187450-GO-RFB / A Component 4: Project Manag Single Stage - One E TF / A8221 Post Request for Bids Open - National 32,120.00 1,039.81 Signed 2020-09-10 2020-12-02 2020-09-17 2020-10-29 2021-01-06 2020-11-28 2021-01-25 2021-01-02 2021-03-30 2021-07-01 cquisition of office supply & s ement and Technical Assista nvelope tationery nce RW-RAB-187452-GO-RFB / P Component 3: Market Linkag Single Stage - One E urchase of equipment for pos TF / A8221 es and Value Addition Invest Post Request for Bids Open - National 78,051.00 0.00 Canceled 2020-08-27 2021-02-16 2020-09-01 2020-10-01 2021-01-18 2020-10-22 2020-11-13 2021-11-13 nvelope t harvest handling and agro- ment Support processing RW-RAB-187457-GO-RFB / s Component 1: Institutional S upply and installation of gree trengthening, Agriculture Pr Single Stage - One E TF / A8221 Post Request for Bids Open - National 154,176.00 0.00 Canceled 2020-09-10 2020-09-18 2020-10-18 2020-11-08 2020-11-30 2021-11-30 n houses and shade nets for oductivity Enhancement and nvelope different sites of SAIP sites Nutrition Improvement RW-RAB-187522-GO-RFB / In Component 2: Irrigation and Single Stage - One E stallation of signposts on acc TF / A8221 Post Request for Bids Open - National 6,167.00 0.00 Canceled 2020-09-10 2021-02-02 2020-09-13 2020-10-13 2020-11-03 2020-11-25 2021-01-24 water use efficiency nvelope ess roads and around reserv oir and SSIT SITES RW-RAB-187531-GO-RFB / A Component 1: Institutional S cquisition of nursery establis trengthening, Agriculture Pr Single Stage - One E TF / A8221 Post Request for Bids Open - National 82,473.00 370.48 Signed 2020-09-28 2020-11-16 2020-10-07 2020-11-06 2020-12-18 2020-11-27 2021-01-05 2020-12-20 2021-03-08 2021-12-20 hment, farm management m oductivity Enhancement and nvelope aterials/equipment and safet Nutrition Improvement y hygienic kits Component 1: Institutional S RW-RAB-187617-GO-RFB / P trengthening, Agriculture Pr Single Stage - One E urchase of IT equipment and TF / A8221 Post Request for Bids Open - National 57,816.00 43,254.95 Signed 2020-10-08 2020-12-07 2020-10-15 2020-11-15 2021-01-18 2020-12-06 2021-02-16 2021-01-03 2021-07-14 2022-01-03 oductivity Enhancement and nvelope spare parts Nutrition Improvement Component 1: Institutional S RW-RAB-249030-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E upply and installation of shad TF / A8221 Post Request for Bids Open - National 36,500.00 5,307.67 Signed 2021-08-25 2021-09-03 2021-08-30 2021-09-29 2021-10-06 2021-10-29 2021-10-11 2021-11-26 2021-12-10 2022-11-25 oductivity Enhancement and nvelope net Nutrition Improvement RW-RAB-249044-GO-RFB / of Component 4: Project Manag Single Stage - One E TF / A8221 Post Request for Bids Open - National 40,000.00 1,830.92 Signed 2021-10-10 2021-12-02 2021-10-15 2021-12-06 2021-11-14 2022-05-09 2021-12-05 2022-05-24 2022-01-03 2022-07-05 2023-01-03 fice stationery and supplies ement and Technical Assista nvelope nce Component 1: Institutional S RW-RAB-248087-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E upply of tubings for tree prod TF / A8221 Post Request for Bids Open - National 75,000.00 30.06 Signed 2021-10-04 2021-09-03 2021-10-08 2021-11-07 2021-10-06 2021-11-28 2021-10-15 2021-12-19 2021-11-16 2022-12-19 oductivity Enhancement and nvelope uction in nurseries Nutrition Improvement Component 1: Institutional S RW-RAB-248977-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E TF / A8221 Post Request for Bids Open - National 21,000.00 178.63 Signed 2021-09-27 2021-11-19 2021-10-02 2021-11-29 2021-11-02 2021-12-24 2021-12-02 2022-01-27 2021-12-30 2022-02-28 2022-12-29 upply of mushroom spawns oductivity Enhancement and nvelope Nutrition Improvement Component 1: Institutional S RW-RAB-248162-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E TF / A8221 Post Request for Bids Open - National 21,000.00 14,464.51 Completed 2021-09-28 2021-08-20 2021-10-02 2021-11-01 2021-09-24 2021-11-21 2021-10-11 2021-12-12 2021-11-16 2022-01-11 2022-02-05 upply of pineapple suckers oductivity Enhancement and nvelope Nutrition Improvement RW-RAB-249037-GO-RFB / p Component 3: Market Linkag Single Stage - One E urchase of equipment for pos TF / A8221 es and Value Addition Invest Post Request for Bids Open - National 45,000.00 582.11 Signed 2021-09-27 2021-08-20 2021-10-02 2021-11-01 2021-09-20 2021-11-22 2021-10-05 2021-12-20 2021-11-16 2022-12-14 nvelope tharvest handling ment Support RW-RAB-249043-GO-RFB / P Component 2: Irrigation and Single Stage - One E Under Imple urchase of protection materi TF / A8221 Post Request for Bids Open - National 57,000.00 0.00 2021-10-04 2021-10-08 2021-10-09 2021-11-08 2021-12-08 2022-01-05 2023-01-05 water use efficiency nvelope mentation als for dams, night storages and rivers RW-RAB-248100-GO-RFB / s Component 2: Irrigation and Single Stage - One E upply, installation and maint TF / A8221 Post Request for Bids Open - National 150,000.00 71,861.28 Signed 2021-09-27 2021-07-26 2021-10-02 2021-11-01 2021-08-27 2021-11-22 2021-09-09 2021-12-14 2021-10-25 2022-12-13 water use efficiency nvelope enance/repair of irrigation inf rastructure RW-RAB-248960-GO-RFB / s Component 4: Project Manag Single Stage - One E TF / A8221 Post Request for Bids Open - National 30,000.00 8,471.53 Signed 2021-09-27 2021-08-26 2021-10-02 2021-11-01 2021-09-27 2021-11-22 2021-10-08 2021-12-20 2021-11-16 2022-03-21 upply of office furniture ement and Technical Assista nvelope nce Component 1: Institutional S RW-RAB-248952-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E upply of fortified beans seeds TF / A8221 Post Request for Bids Open - National 79,250.00 547.03 Signed 2021-08-27 2021-08-20 2021-08-31 2021-09-30 2021-10-30 2021-10-30 2021-10-08 2021-11-29 2021-11-28 2022-11-28 oductivity Enhancement and nvelope and Irish potatoes seeds Nutrition Improvement Component 1: Institutional S RW-RAB-254192-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E upply of compost for Nyanza TF / A8221 Post Request for Bids Open - National 78,750.00 0.03 Signed 2021-09-27 2021-05-13 2021-10-02 2021-11-01 2021-06-22 2021-11-22 2021-07-09 2021-12-20 2021-09-21 2022-12-20 oductivity Enhancement and nvelope site Season A,B and C 2022 Nutrition Improvement Component 1: Institutional S RW-RAB-254200-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E upply of compost for Gatsibo TF / A8221 Post Request for Bids Open - National 31,500.00 0.03 Signed 2021-10-03 2021-05-13 2021-10-08 2021-11-07 2021-06-22 2021-11-28 2021-09-19 2021-12-26 2021-09-21 2022-12-26 oductivity Enhancement and nvelope site Season A,B and C 2022 Nutrition Improvement Page 4 Component 1: Institutional S RW-RAB-254206-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E upply of compost for Kayonz TF / A8221 Post Request for Bids Open - National 45,000.00 0.03 Signed 2021-10-03 2021-05-13 2021-10-08 2021-11-07 2021-06-22 2021-11-28 2021-07-09 2021-12-26 2021-09-21 2022-12-26 oductivity Enhancement and nvelope a site Season A,B and C 2022 Nutrition Improvement Component 1: Institutional S RW-RAB-254214-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E upply of compost for Muyanz TF / A8221 Post Request for Bids Open - National 121,500.00 0.04 Signed 2021-10-03 2021-05-13 2021-10-08 2021-11-07 2021-06-22 2021-11-28 2021-07-09 2021-12-26 2021-09-28 2022-12-26 oductivity Enhancement and nvelope a site Season A,B and C 2022 Nutrition Improvement RW-RAB-254211-GO-RFB / S Component 1: Institutional S upply of compost for Rwama trengthening, Agriculture Pr Single Stage - One E TF / A8221 Post Request for Bids Open - National 85,500.00 0.03 Signed 2021-10-03 2021-05-13 2021-10-08 2021-11-07 2021-06-22 2021-11-28 2021-07-09 2021-12-26 2021-09-28 2022-12-26 gana sites Season A,B and C oductivity Enhancement and nvelope 2022 Nutrition Improvement Component 1: Institutional S RW-RAB-254224-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E upply of compost for Nyabihu TF / A8221 Post Request for Bids Open - National 56,250.00 0.04 Signed 2021-10-03 2021-05-13 2021-10-08 2021-11-07 2021-06-22 2021-11-28 2021-07-09 2021-12-26 2021-09-28 2022-12-26 oductivity Enhancement and nvelope site Season A,B and C 2022 Nutrition Improvement Component 1: Institutional S RW-RAB-254226-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E upply of compost for Karongi TF / A8221 Post Request for Bids Open - National 58,500.00 0.03 Signed 2021-10-03 2021-05-19 2021-10-08 2021-11-07 2021-06-22 2021-11-28 2021-07-19 2021-12-19 2021-09-28 2022-12-19 oductivity Enhancement and nvelope site Season A,B and C 2022 Nutrition Improvement Component 1: Institutional S RW-RAB-254230-GO-RFB / Fr trengthening, Agriculture Pr Single Stage - One E amework contract for supply TF / A8221 Post Request for Bids Open - National 362,956.00 334,394.68 Signed 2021-10-03 2021-06-24 2021-10-08 2021-11-07 2021-08-04 2021-11-28 2021-08-18 2021-12-26 2021-09-25 2022-12-26 oductivity Enhancement and nvelope of agricultural inputs Nutrition Improvement Component 1: Institutional S RW-RAB-271369-GO-RFB / c trengthening, Agriculture Pr Single Stage - One E ontract for supply of compost TF / B6154 Post Request for Bids Open - National 124,800.00 0.06 Signed 2022-01-17 2022-02-24 2022-01-22 2022-03-01 2022-02-01 2022-03-28 2022-03-03 2022-06-23 2022-03-31 2022-08-12 2023-03-31 oductivity Enhancement and nvelope in Ngoma and Nyabirasi sites Nutrition Improvement RW-RAB-271420-GO-RFB / T Component 1: Institutional S ender for supply of lime in N trengthening, Agriculture Pr Single Stage - One E TF / B6154 Post Request for Bids Open - National 27,200.00 0.15 Signed 2022-01-16 2022-02-25 2022-01-21 2022-03-01 2022-02-21 2022-03-28 2022-03-14 2022-06-23 2022-04-11 2022-08-15 2023-04-11 goma and Nyabirasi project s oductivity Enhancement and nvelope ites Nutrition Improvement Component 1: Institutional S RW-RAB-271422-GO-RFB / A trengthening, Agriculture Pr Single Stage - One E Under Imple cquisition of smallstock dom TF / B6154 Post Request for Bids Open - National 468,000.00 0.00 2022-04-13 2022-06-22 2022-04-18 2022-06-29 2022-05-18 2022-06-08 2022-07-06 2023-07-06 oductivity Enhancement and nvelope mentation estic animals Nutrition Improvement RW-RAB-271423-GO-RFB / A Component 1: Institutional S cquisition of chicken breeds, trengthening, Agriculture Pr Single Stage - One E feeding packages, disease co TF / B6154 Post Request for Bids Open - National 29,000.00 116.26 Signed 2022-02-23 2022-03-08 2022-02-28 2022-03-18 2022-03-30 2022-04-13 2022-04-29 2022-04-22 2022-06-03 2022-06-05 2023-06-03 oductivity Enhancement and nvelope ntrol packages and installatio Nutrition Improvement n of chicken cages in Ngoma District Component 1: Institutional S RW-RAB-302323-GO-RFB / P trengthening, Agriculture Pr Single Stage - One E Under Imple urchase of IT equipment and TF / A8221 Post Request for Bids Open - National 69,000.00 0.00 2022-08-21 2023-04-20 2022-08-26 2023-05-02 2022-09-25 2022-10-16 2022-11-07 2023-11-07 oductivity Enhancement and nvelope mentation spare parts Nutrition Improvement RW-RAB-302471-GO-RFB / P Component 4: Project Manag Single Stage - One E TF / B6154 Post Request for Bids Open - National 55,000.00 0.00 Canceled 2022-10-03 2022-10-08 2022-11-07 2022-11-28 2022-12-20 2023-03-20 urchase of project vehicle ement and Technical Assista nvelope nce Component 1: Institutional S RW-RAB-302488-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E Under Imple upply of tubings for tree prod TF / A8221 Post Request for Bids Open - National 65,000.00 0.00 2023-02-02 2023-01-10 2023-02-07 2023-03-09 2023-01-31 2023-03-30 2023-02-08 2023-04-21 2024-04-20 oductivity Enhancement and nvelope mentation uction in nurseries Nutrition Improvement Component 1: Institutional S RW-RAB-302511-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E upply and installation of shad TF / A8221 Post Request for Bids Open - National 20,000.00 0.00 Canceled 2023-02-20 2023-02-25 2023-03-29 2023-04-28 2023-05-20 2024-05-19 oductivity Enhancement and nvelope e nets Nutrition Improvement Component 1: Institutional S RW-RAB-302527-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E Under Imple upply of compost for Rwama TF / B6154 Post Request for Bids Open - National 61,600.00 0.00 2022-07-10 2022-08-09 2022-07-15 2022-08-10 2022-08-14 2022-09-04 2022-09-26 2023-09-26 oductivity Enhancement and nvelope mentation gana site Nutrition Improvement Component 1: Institutional S RW-RAB-302529-GO-RFB / s trengthening, Agriculture Pr Single Stage - One E Under Imple upply of lime for cyngo-base TF / B6154 Post Request for Bids Open - National 10,000.00 0.00 2022-07-10 2022-08-04 2022-07-15 2022-08-10 2022-08-14 2022-09-04 2022-09-26 2023-09-26 oductivity Enhancement and nvelope mentation and Rwangingo sites Nutrition Improvement Component 1: Institutional S RW-RAB-302536-GO-RFB / s trengthening, Agriculture Pr Single Stage - One E Under Imple upply of compost for cyungo- TF / B6154 Post Request for Bids Open - National 48,000.00 0.00 2022-07-10 2022-08-04 2022-07-15 2022-08-10 2022-08-14 2022-09-04 2022-09-26 2023-09-26 oductivity Enhancement and nvelope mentation base and Rwangingo sites Nutrition Improvement Component 1: Institutional S RW-RAB-302538-GO-RFB / s trengthening, Agriculture Pr Single Stage - One E Under Imple TF / B6154 Post Request for Bids Open - National 22,000.00 0.00 2022-07-24 2022-09-02 2022-07-29 2022-09-08 2022-08-28 2022-10-12 2022-09-27 2023-01-10 2022-10-17 2023-10-17 upply of fortified beans seeds oductivity Enhancement and nvelope mentation Nutrition Improvement Component 1: Institutional S RW-RAB-302570-GO-RFB / A trengthening, Agriculture Pr Single Stage - One E Under Imple cquisition of materials for far TF / A8221 Post Request for Bids Open - National 85,750.00 0.00 2022-10-19 2022-11-16 2022-10-24 2022-11-23 2022-12-14 2023-01-05 2024-01-05 oductivity Enhancement and nvelope mentation mer organizations Nutrition Improvement RW-RAB-302600-GO-RFB / S upply and installation for sm Component 2: Irrigation and Single Stage - One E Under Imple TF / A8221 Post Request for Bids Open - National 750,000.00 0.00 2023-01-08 2023-04-20 2023-01-13 2023-05-02 2023-02-12 2023-03-14 2023-04-11 2024-04-10 all scale irrigation technology water use efficiency nvelope mentation (SSIT) implementation Component 3: Market Linkag RW-RAB-345559-GO-RFB / A Single Stage - One E Under Imple TF / A8221 es and Value Addition Invest Post Request for Bids Open - National 16,200.00 0.00 2023-03-15 2023-03-10 2023-03-20 2023-03-10 2023-04-21 2023-05-12 2023-06-09 2023-08-08 cquisition of smart phones nvelope mentation ment Support Component 1: Institutional S RW-RAB-345568-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E Under Imple upply of lime for Rwamagana TF / A8221 Post Request for Bids Open - National 10,206.00 0.00 2023-03-26 2023-03-29 2023-03-31 2023-03-30 2023-04-30 2023-05-21 2023-06-18 2024-06-17 oductivity Enhancement and nvelope mentation site Nutrition Improvement Component 1: Institutional S RW-RAB-345596-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E Under Imple upply of lime for Rulindo, Ny TF / A8221 Post Request for Bids Open - National 15,997.50 0.00 2023-04-02 2023-03-29 2023-04-07 2023-03-30 2023-05-07 2023-05-28 2023-06-25 2024-06-25 oductivity Enhancement and nvelope mentation abihu and Karongi sites Nutrition Improvement Page 5 RW-RAB-345644-GO-RFB / of Component 4: Project Manag Single Stage - One E Under Imple TF / A8221 Post Request for Bids Open - National 40,000.00 0.00 2023-05-30 2023-06-30 2023-06-04 2023-07-17 2023-07-16 2023-08-15 2023-09-19 2024-09-18 fice supplies and consumable ement and Technical Assista nvelope mentation s nce Component 1: Institutional S RW-RAB-376968-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E Under Imple TF / A8221 Post Request for Bids Open - National 95,000.00 0.00 2023-10-04 2024-02-02 2023-10-09 2023-11-20 2023-12-20 2024-01-24 2024-07-22 upply of Irish potato seeds oductivity Enhancement and nvelope mentation Nutrition Improvement RW-RAB-377312-GO-RFB / Pr Component 3: Market Linkag Single Stage - One E ovision of Post-Harvest Equip TF / A8221 es and Value Addition Invest Post Request for Bids Open - National 45,000.00 0.00 Canceled 2023-11-09 2023-11-14 2023-12-26 2024-01-25 2024-02-29 2024-08-27 nvelope ment ment Support Component 1: Institutional S RW-RAB-376951-GO-RFB / S trengthening, Agriculture Pr Single Stage - One E Pending Impl TF / A8221 Post Request for Bids Open - National 15,000.00 0.00 2023-09-21 2023-09-26 2023-11-07 2023-12-07 2024-01-11 2025-01-10 upply of Soya bean seeds oductivity Enhancement and nvelope ementation Nutrition Improvement RW-RAB-376976-GO-RFB / P Component 4: Project Manag Single Stage - One E Under Imple TF / A8221 Post Request for Bids Open - National 12,000.00 0.00 2023-11-06 2024-02-06 2023-11-11 2024-02-08 2023-12-23 2024-01-22 2024-02-26 2025-02-25 urchase of vehicle tyres ement and Technical Assista nvelope mentation nce Component 1: Institutional S RW-RAB-376964-GO-RFB / In trengthening, Agriculture Pr Single Stage - One E Under Imple stallation of chicken hatched TF / A8221 Post Request for Bids Open - National 16,000.00 0.00 2023-09-20 2023-09-08 2023-09-25 2023-09-11 2023-11-06 2023-10-09 2023-12-06 2023-10-26 2024-01-10 2024-06-28 oductivity Enhancement and nvelope mentation houses Nutrition Improvement RW-RAB-409449-GO-RFB / S Component 1: Institutional S upply and provision of Perso trengthening, Agriculture Pr Single Stage - One E Pending Impl TF / A8221 Post Request for Bids Open - National 6,000.00 0.00 2024-03-01 2024-03-01 2024-03-22 2024-04-21 2024-05-26 2024-06-25 nal Protective Equiments (PP oductivity Enhancement and nvelope ementation Es) for Grievance Redressal C Nutrition Improvement ommittees. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-RAB-97485-NC-RFQ / Ac Component 4: Project Manag Request for Quota Single Stage - One E quisition of insurance service TF / A8221 ement and Technical Assista Post Limited 1,000.00 0.00 Canceled 2019-05-11 2019-06-15 2020-06-14 tions nvelope s for project assets nce RW-RAB-97781-NC-RFQ / Ac Component 4: Project Manag Request for Quota Single Stage - One E quisition of insurance for Veh TF / A8221 ement and Technical Assista Post Limited 8,000.00 18,333.25 Completed 2019-03-11 2019-04-26 2019-04-23 2019-07-12 2020-04-22 2020-07-12 tions nvelope icles and Motorcycles nce RW-RAB-97784-NC-RFB / Mai Component 4: Project Manag ntenance and reparation serv Single Stage - One E TF / A8221 ement and Technical Assista Post Request for Bids Open - National 15,000.00 34,850.83 Completed 2019-03-04 2018-12-10 2019-03-09 2019-04-08 2019-01-10 2019-04-22 2019-01-27 2019-05-20 2019-09-11 2020-05-19 2020-09-10 ices of vehicles and motorcy nvelope nce cles (framework contract) RW-RAB-97788-NC-RFB / Pro Component 4: Project Manag Single Stage - One E curement of sports services f TF / A8221 ement and Technical Assista Post Request for Bids Open - National 5,000.00 0.00 Canceled 2019-03-19 2019-03-24 2019-04-23 2019-05-14 2019-06-12 2020-06-11 nvelope or SPIU staff (framework cont nce ract) RW-RAB-97794-NC-RFB / Pro Component 4: Project Manag Single Stage - One E TF / A8221 Post Request for Bids Open - National 25,000.00 3,790.32 Completed 2019-03-11 2019-05-23 2019-03-16 2019-04-15 2019-06-26 2019-05-06 2019-07-25 2019-06-04 2019-08-20 2020-06-03 2020-08-20 vision of printing services ement and Technical Assista nvelope nce RW-RAB-97800-NC-RFB / Hiri Component 1: Institutional S ng hotel services for confere trengthening, Agriculture Pr Single Stage - One E nces, trainings and workshop TF / A8221 Post Request for Bids Open - National 135,000.00 11,074.54 Completed 2019-03-07 2019-05-15 2019-03-12 2019-04-11 2019-06-17 2019-05-02 2019-07-24 2019-05-31 2019-08-27 2020-05-30 2020-08-26 oductivity Enhancement and nvelope s at head office and in differe Nutrition Improvement nt Districts (framework contr act). RW-RAB-97804-NC-RFB / Hiri Component 4: Project Manag Single Stage - One E ng a film for production of inf TF / A8221 ement and Technical Assista Post Request for Bids Open - National 23,000.00 31,452.80 Signed 2019-03-19 2019-07-09 2019-03-24 2019-04-23 2019-08-08 2019-05-14 2019-09-02 2019-06-12 2019-10-19 2020-06-11 nvelope ormation dissemination mate nce rials RW-RAB-102955-NC-RFQ / v Component 4: Project Manag Request for Quota Single Stage - One E TF / A8221 Post Limited 1,685.00 634.84 Completed 2019-03-25 2019-06-27 2019-04-25 2019-07-29 2019-05-10 2019-08-11 aluation of old motorcycles ement and Technical Assista tions nvelope nce RW-RAB-124724-NC-RFB / pr Component 1: Institutional S ovision of hotel services for c trengthening, Agriculture Pr Single Stage - One E onferences, training and wor TF / A8221 Post Request for Bids Open - National 173,089.00 24,910.59 Signed 2020-04-08 2020-06-17 2020-04-13 2020-05-13 2020-07-17 2020-05-15 2020-08-14 2020-06-19 2020-11-26 2021-06-19 oductivity Enhancement and nvelope kshops at head office and sit Nutrition Improvement es in different districts (fram ework contract) Component 1: Institutional S RW-RAB-124778-NC-RFB / pr trengthening, Agriculture Pr Single Stage - One E ovision of printing services fo TF / A8221 Post Request for Bids Open - National 43,956.00 3,519.27 Signed 2020-03-11 2019-05-23 2020-03-16 2020-04-15 2019-06-26 2020-05-15 2019-07-25 2020-06-19 2020-08-23 2021-06-19 oductivity Enhancement and nvelope r SAIP Project Nutrition Improvement RW-RAB-187611-NC-RFB / M Component 4: Project Manag Single Stage - One E aintenance service of vehicle TF / A8221 ement and Technical Assista Post Request for Bids Open - National 42,827.00 26,150.66 Signed 2020-08-23 2021-01-27 2020-08-30 2020-09-29 2021-03-01 2020-10-20 2021-03-11 2020-11-11 2022-04-22 2021-11-11 nvelope s and motorcycles nce Component 1: Institutional S RW-RAB-249370-NC-RFB / Pr trengthening, Agriculture Pr Single Stage - One E TF / A8221 Post Request for Bids Open - National 50,000.00 2,426.71 Signed 2021-09-27 2021-08-14 2021-10-02 2021-11-01 2021-09-14 2021-11-22 2021-10-29 2021-12-20 2022-01-26 2022-12-20 ovision of printing services oductivity Enhancement and nvelope Nutrition Improvement RW-RAB-271447-NC-RFB / m Component 3: Market Linkag Single Stage - One E aintenance of post harvest fa TF / A8221 es and Value Addition Invest Post Request for Bids Open - National 65,000.00 0.00 Canceled 2022-02-09 2022-02-14 2022-03-16 2022-04-06 2022-05-04 2023-05-04 nvelope cilities ment Support RW-RAB-271424-NC-DIR / on Component 3: Market Linkag -grid power line supply and c TF / B6154 es and Value Addition Invest Post Direct Selection Direct 733,980.00 714,543.88 Signed 2022-02-13 2022-02-15 2022-02-18 2022-02-15 2022-04-09 2022-05-13 2022-10-06 onnection to post-harvest fac ment Support ilities RW-RAB-271432-NC-DIR / w Component 3: Market Linkag ater supply and connection t TF / B6154 es and Value Addition Invest Post Direct Selection Direct 135,000.00 44,313.82 Signed 2022-02-13 2022-02-15 2022-02-18 2022-03-04 2022-04-09 2022-03-25 2022-10-06 o post-harvest facilities ment Support RW-RAB-302468-NC-RFB / P Component 4: Project Manag Single Stage - One E Under Imple urchase of fuel for project ve TF / A8221 ement and Technical Assista Post Request for Bids Open - National 50,000.00 0.00 2022-07-24 2022-07-25 2022-07-29 2022-08-03 2022-08-28 2022-09-18 2022-10-10 2023-10-10 nvelope mentation hicles, motorcycles and gene nce rators RW-RAB-302476-NC-RFB / in Component 4: Project Manag Single Stage - One E Under Imple TF / A8221 Post Request for Bids Open - National 40,000.00 0.00 2023-04-02 2023-06-12 2023-04-07 2023-07-17 2023-05-07 2023-07-17 2023-05-28 2023-07-19 2023-06-19 2024-06-18 surance for vehicles and mot ement and Technical Assista nvelope mentation orcycles nce Page 6 RW-RAB-302478-NC-RFB / Hi Component 4: Project Manag Single Stage - One E Under Imple ring a firm for production of i TF / A8221 ement and Technical Assista Post Request for Bids Open - National 40,000.00 0.00 2022-08-15 2022-08-22 2022-08-20 2022-08-24 2022-09-19 2022-09-21 2022-10-10 2022-10-28 2022-11-01 2023-11-01 nvelope mentation nformation dissemination ma nce terials RW-RAB-302482-NC-RFB / M Component 4: Project Manag Single Stage - One E Under Imple aintenance of IT equipment a TF / A8221 ement and Technical Assista Post Request for Bids Open - National 30,000.00 0.00 2022-08-08 2022-07-27 2022-08-13 2022-08-03 2022-09-12 2022-10-03 2022-10-25 2023-10-25 nvelope mentation nd repair of office equipment nce RW-RAB-345649-NC-RFB / M Component 4: Project Manag Single Stage - One E Under Imple TF / A8221 Post Request for Bids Open - National 80,000.00 0.00 2023-03-15 2023-06-02 2023-03-20 2023-05-01 2023-07-05 2023-05-31 2023-08-28 2023-07-05 2024-07-04 aintenance of project vehicle ement and Technical Assista nvelope mentation s nce CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-RAB-97832-CS-QCBS / Hi Component 1: Institutional S ring a firm that will conduct a trengthening, Agriculture Pr Quality And Cost- TF / A8221 Post Open - National 50,000.00 0.00 Canceled 2019-02-19 2019-04-17 2019-03-05 2019-04-09 2019-05-09 2019-05-30 2019-07-04 2019-08-03 2019-12-01 Value chain analysis (includin oductivity Enhancement and Based Selection g market analysis) Nutrition Improvement RW-RAB-103036-CS-QCBS / Component 4: Project Manag Hiring a firm that will conduc Quality And Cost- TF / A8221 ement and Technical Assista Post Open - National 35,000.00 81,272.48 Signed 2019-03-11 2019-04-08 2019-03-26 2019-04-16 2019-06-20 2019-05-16 2019-07-22 2019-05-30 2019-08-15 2019-06-27 2019-09-19 2019-07-25 2019-11-19 2019-09-23 2020-05-16 t base line survey data collec Based Selection nce tion for selected sites RW-RAB-111212-CS-UN / Te Component 4: Project Manag chnical Assistance to the Sus UN Agencies (Dire TF / A8221 ement and Technical Assista Post Direct 1,500,000.00 1,600,000.00 Signed 2019-06-29 2019-06-29 2022-06-28 tainable Agricultural Intensifi ct) nce cation and Food Security Proj ect (TA-SAIP). RW-RAB-124770-CS-QCBS / Component 3: Market Linkag Quality And Cost- supervision of construction w TF / A8221 es and Value Addition Invest Post Open - National 16,484.00 7,477.60 Completed 2019-08-07 2019-09-02 2019-08-21 2019-09-06 2019-10-31 2019-10-06 2019-12-09 2019-10-27 2019-12-27 2019-12-01 2020-02-06 2020-01-05 2020-03-18 2020-06-03 2020-08-22 Based Selection orks of drying shelters ment Support RW-RAB-187569-CS-QCBS / Environmental & Social Impa Component 2: Irrigation and Quality And Cost- ct Assessment (ESIA) & Envir TF / A8221 Post Open - National 32,120.00 29,167.43 Signed 2020-08-17 2020-09-02 2020-09-01 2020-10-07 2020-11-01 2020-11-06 2020-12-03 2020-11-27 2020-12-23 2020-12-28 2021-01-26 2021-01-21 2021-04-01 2021-03-22 water use efficiency Based Selection onmental & Social Managem ent Plan (ESMP).(In PRO) RW-RAB-187574-CS-QCBS / Component 3: Market Linkag Hiring services provider in ca Quality And Cost- TF / A8221 es and Value Addition Invest Post Open - National 157,388.00 980.30 Signed 2020-09-15 2020-12-02 2020-09-30 2020-11-05 2021-03-26 2020-12-06 2021-04-26 2020-12-27 2021-06-25 2021-01-24 2021-05-18 2021-02-28 2021-08-05 2022-02-28 pacity building development Based Selection ment Support and implementation of busin ess plan RW-RAB-187583-CS-QCBS / Component 3: Market Linkag Quality And Cost- Supervision of construction w TF / A8221 es and Value Addition Invest Post Open - National 10,707.00 0.00 Canceled 2020-08-24 2020-09-07 2020-10-08 2020-11-07 2020-11-28 2020-12-18 2021-01-09 2021-06-28 Based Selection orks for post harvest facilities ment Support RW-RAB-249081-CS-QCBS / supervision of construction w Component 3: Market Linkag Quality And Cost- orks for post harvest facilities TF / A8221 es and Value Addition Invest Post Open - National 60,500.00 27,377.08 Signed 2021-08-26 2021-11-19 2021-09-16 2021-11-29 2021-10-14 2022-01-08 2021-11-13 2022-02-11 2021-12-04 2022-02-15 2022-01-01 2022-03-01 2022-01-30 2022-04-06 2022-06-23 Based Selection and selling points and constr ment Support uction of hygiene and sanitat ion facilities. RW-RAB-249368-CS-QCBS / Component 4: Project Manag Quality And Cost- Consultancy services for Mid TF / A8221 ement and Technical Assista Post Open - National 10,000.00 0.00 Canceled 2021-10-01 2021-10-22 2021-11-26 2021-12-26 2022-01-16 2022-02-20 2022-03-20 2022-06-20 Based Selection term review nce RW-RAB-249350-CS-QCBS / Component 2: Irrigation and Quality And Cost- Consultancy service of ESIA o TF / A8221 Post Open - National 30,000.00 0.00 Canceled 2021-08-31 2021-11-19 2021-09-21 2021-12-23 2021-10-26 2021-11-25 2021-12-16 2022-01-20 2022-02-24 2023-02-24 water use efficiency Based Selection r ESMPs for potential sites wi th SSIT RW-RAB-302593-CS-QCBS / Consultancy service of enviro nmental social impact assess Component 2: Irrigation and Quality And Cost- Under Implement TF / A8221 Post Open - National 75,000.00 0.00 2022-07-17 2022-08-29 2022-07-31 2022-10-05 2022-09-04 2022-10-04 2022-10-25 2022-11-22 2022-12-14 2023-12-14 ment (ESIA) or environment water use efficiency Based Selection ation al social (ESIA) management plans for potential sites with SSIT RW-RAB-377300-CS-QCBS / Component 4: Project Manag Quality And Cost- Under Implement TF / A8221 Post Open - National 75,000.00 0.00 2023-10-18 2023-11-22 2023-11-08 2023-12-29 2023-12-22 2024-01-19 2024-02-18 2024-03-24 2024-04-28 2024-07-27 Endline survey for SAIP Proje ement and Technical Assista Based Selection ation ct nce INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-RAB-260415-CS-INDV / Component 4: Project Manag Hiring individual consultants Individual Consult Under Implement TF / A8221 ement and Technical Assista Post Open 10,000.00 0.00 2021-11-15 2021-11-15 2021-12-27 2022-01-17 2022-02-14 2022-03-31 for preparing the mid-term re ant Selection ation nce view report for SAIP Project Page 7