Ibarra Transport Infrastructure Improvement Project (P147280) Procurement Plan Country: Ecuador Region: LATIN AMERICA AND CARIBBEAN Approval Date: 16-Jun-2016 General Procurement Notice published on: 31-Ene-2017 July 9, 2010 PROCUREMENT Ecuador : EC Ibarra Transport Infrastructure Improvement Project PLAN General Information Country: Ecuador 2017-04-19 Bank’s Approval Date of the Original Procurement Plan: 2024-02-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P147280 GPN Date: Project Name: EC Ibarra Transport Infrastructure Improvement Project Loan / Credit No: IBRD / 85790 Municipality of Ibarra Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GADI-UGP-YAH-003 / Constru Component 2: Improve publi Solicitud de oferta Single Stage - One E 2,847,429.6 2018-03-0 2018-05 cción de la infraestructura de IBRD / 85790 Posterior Open - National Finalizado 2017-04-23 2017-04-04 2017-06-04 2017-07-05 2017-07-05 2017-07-15 2017-07-31 2017-08-06 2017-08-21 c and tourist spaces s nvelope 1 4 -11 portiva y recreativa Yahuarco cha. GADI-UGP-AVN-001 / Constr ucción Anillo Vial tramo Nort Component 1: Improve mobi Solicitud de oferta Open - Internationa Single Stage - One E 19,673,216. 2019-02-1 IBRD / 85790 Previa Firmado 2017-09-26 2017-10-01 2017-09-27 2017-10-01 2017-11-11 2017-11-20 2017-11-19 2018-02-05 2017-12-24 2018-02-25 e, vía de cuatro carriles asfal lity in the city s l nvelope 12 7 tada parterre central. GADI-UGP-AVS-002 / Constru Component 1: Improve mobi Solicitud de oferta Open - Internationa Single Stage - One E 2020-03-0 IBRD / 85790 Previa 0.00 Cancelado 2018-06-04 2018-06-10 2018-07-25 2018-08-09 2018-09-13 cción Anillo Vial tramo Sur lity in the city s l nvelope 6 EC-GAD-I-2021-OBR-LPI-01 / Construcción de conexión Ani llo Vial tramo Norte - Laguna Component 1: Improve mobi Pedido de propues Open - Internationa Single Stage - One E Ejecución p 2022-06-2 IBRD / 85790 Previa 0.00 2020-12-28 2021-01-25 2021-03-26 2021-04-15 2021-05-05 Yahuarcocha y Obras comple lity in the city tas l nvelope endiente 9 mentarias de Mejoramiento d e la Infraestructura de Trans porte GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GADI-UGP-EQ-018 / Equipam Component 4: Project Manag Solicitud de cotiza Single Stage - One E IBRD / 85790 Posterior Open - National 21,264.54 Finalizado 2017-04-30 2017-06-26 2017-06-28 2017-07-06 2017-08-30 iento (informatico) ement ciones nvelope GADI-UGP-EQ-017 / Equipam Component 4: Project Manag Solicitud de cotiza Single Stage - One E IBRD / 85790 Posterior Open - National 12,261.76 Finalizado 2017-05-05 2017-06-09 2017-07-08 2017-07-09 2017-09-14 iento (mobiliario) ement ciones nvelope GADI-UGP-ECOM-018 / ADQU Component 4: Project Manag Solicitud de cotiza Single Stage - One E ISICIÓN DE EQUIPOS DE COM IBRD / 85790 Posterior Open - National 14,992.32 Finalizado 2018-11-06 2018-12-15 2018-12-10 2019-01-14 2019-01-15 ement ciones nvelope UNICACIÓN EC-GAD-I-2020-BN-CP-02 / A dquisición de suministros de Component 4: Project Manag Solicitud de cotiza Single Stage - One E IBRD / 85790 Posterior Open - National 1,250.61 Finalizado 2020-04-27 2020-05-29 2020-10-05 2020-06-08 2020-10-13 oficina para la Unidad de Ges ement ciones nvelope tión del Proyecto EC-GAD-I-2020-BN-CP-03 / A Component 4: Project Manag Solicitud de cotiza Single Stage - One E Ejecución pe dquisición de un Vehículo par IBRD / 85790 Posterior Open - National 0.00 2020-04-27 2020-05-29 2020-06-08 ement ciones nvelope ndiente a la Unidad de Gestión del Pr oyecto EC-GAD-I-2020-BN-CP-04 / A dquisición de Implementos d Component 4: Project Manag Solicitud de cotiza Single Stage - One E Ejecución pe IBRD / 85790 Posterior Open - National 0.00 2020-05-11 2020-06-15 2020-06-25 e Seguridad Industrial y Bios ement ciones nvelope ndiente eguridad para la Unidad de G estión del Proyecto EC-GAD-I-2020-BN-CP-01 / A dquisición de Bienes Informá Component 4: Project Manag Solicitud de cotiza Single Stage - One E ticos y Suministros de Equipo IBRD / 85790 Posterior Open - National 0.00 Cancelado 2020-04-27 2020-05-29 2020-06-08 ement ciones nvelope s de Oficina para la Unidad d e Gestión del Proyecto EC-GAD-IBARRA-275670-GO- DIR / Adquisición de Bienes I Component 4: Project Manag Adquisición direct Ejecución pe nformáticos y Suministros de IBRD / 85790 Posterior Direct 0.00 2022-01-31 2022-02-07 2022-02-14 2022-02-24 ement a ndiente Equipos de Oficina para la Un idad de Gestión del Proyecto MITCI EC-GAD-IBARRA-2024-01-UG P / Adquisición de suministro Component 4: Project Manag Solicitud de cotiza Single Stage - One E Ejecución pe IBRD / 85790 Posterior Open - National 0.00 2024-01-13 2024-03-02 2024-04-01 s de oficina para la Unidad d ement ciones nvelope ndiente e Gestión del Proyecto. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EC-GAD-IBARRA-16145-NC-D Component 4: Project Manag Adquisición direct IBRD / 85790 Posterior Direct 10,752.13 Finalizado 2017-05-24 2017-01-25 2017-05-25 2017-02-15 2017-05-28 2017-03-08 2018-05-23 2018-03-07 IR / ASISTENTE ADMINISTRAT ement a IVO EC-GAD-IBARRA-52692-NC-D Component 4: Project Manag Adquisición direct IR / CONTRATACIÓN DE ASIS IBRD / 85790 Posterior Direct 10,764.23 Finalizado 2018-03-07 2018-03-27 2018-04-01 2018-05-01 2018-04-12 2021-04-15 2019-03-12 ement a TENTE ADMINISTRATIVA. EC-GAD-I-2020-SNC-CP-01 / Servicio de mantenimiento d Component 4: Project Manag Solicitud de cotiza Single Stage - One E Ejecución pe IBRD / 85790 Posterior Open - National 0.00 2020-06-01 2020-07-16 2021-06-30 e los equipos informáticos de ement ciones nvelope ndiente la oficina de la Unidad de Ge stión del Proyecto EC-GAD-I-2020-SNC-CP-02 / Adquisición de un Seguro par Component 4: Project Manag Solicitud de cotiza Single Stage - One E Ejecución pe IBRD / 85790 Posterior Open - National 0.00 2020-05-11 2020-06-30 2021-06-30 a el Vehículo de la Unidad de ement ciones nvelope ndiente Gestión del Proyecto Page 1 EC-GAD-I-2020-SNC-CP-03 / Servicio de agencia de public Component 4: Project Manag Solicitud de cotiza Single Stage - One E IBRD / 85790 Posterior Open - National 14,213.92 Firmado 2020-05-11 2020-06-30 2020-10-12 2021-06-30 idad para beneficio de los act ement ciones nvelope ores interesados del Proyecto EC-GAD-I-2020-SNC-CP-04 / Servicio de mantenimiento d Component 4: Project Manag Solicitud de cotiza Single Stage - One E Ejecución pe IBRD / 85790 Posterior Open - National 0.00 2020-05-11 2020-06-30 2021-06-30 el vehículo de la Unidad de G ement ciones nvelope ndiente estión del Proyecto EC-GAD-I-2020-SNC-CP-05 / Component 4: Project Manag Solicitud de cotiza Single Stage - One E Servicio de internet para la o IBRD / 85790 Posterior Open - National 0.00 Cancelado 2020-04-20 2020-06-01 2021-06-30 ement ciones nvelope ficina de la Unidad de Gestió n del Proyecto EC-GAD-I-2021-SNC-CD-01 / Contratación de asistente ad Component 4: Project Manag Adquisición direct IBRD / 85790 Posterior Direct 4,016.11 Firmado 2020-11-02 2020-12-09 2020-11-17 2020-12-10 2021-01-01 2021-01-18 2021-06-30 ministrativa de la Unidad de ement a Gestión del Proyecto EC-GAD-I-2019-SNC-CD-01 / Contratación de asistente ad Component 4: Project Manag Adquisición direct IBRD / 85790 Posterior Direct 10,035.32 Finalizado 2020-04-06 2019-01-16 2020-04-07 2019-02-04 2020-04-23 2019-03-06 2020-04-24 2020-01-05 ministrativa de la Unidad de ement a Gestión del Proyecto 2019 EC-GAD-I-2020-SNC-CD-01 / Contratación de asistente ad Component 4: Project Manag Adquisición direct IBRD / 85790 Posterior Direct 10,035.30 Firmado 2020-04-06 2019-12-13 2020-04-07 2019-12-16 2020-04-10 2020-01-06 2020-12-31 ministrativa de la Unidad de ement a Gestión del Proyecto MITCI EC-GAD-I-2020-SNC-CD-02 / Contratación de asistente ad Component 4: Project Manag Solicitud de cotiza Single Stage - One E ministrativa de la Unidad de IBRD / 85790 Posterior Open - National 3,278.16 Finalizado 2020-07-21 2020-08-01 2020-10-07 2020-12-31 2021-01-17 ement ciones nvelope Gestión del Proyecto MITCI a gosto-diciembre 2020 EC-GAD-I-2020-SNC-CP-06 / Servicio de organización, digi Component 4: Project Manag Solicitud de cotiza Single Stage - One E IBRD / 85790 Posterior Open - National 0.00 Cancelado 2020-05-11 2020-06-30 2021-06-30 talización e inventario de los ement ciones nvelope procesos contractuales del Pr oyecto MITCI CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EC-GAD-IBARRA-9863-CS-QC BS / SERVICIO DE CONSULTO Component 2: Improve publi Selección basada RIA PARA LA FISCALIZACION IBRD / 85790 Posterior Open - National 189,097.98 Firmado 2017-03-10 2017-04-14 2017-03-15 2017-04-29 2017-06-04 2017-05-29 2017-05-29 2017-06-03 2017-06-05 2017-06-12 2017-06-20 2017-07-02 2017-08-21 2018-03-29 c and tourist spaces en calidad y costo DEL LAS AREAS RECREATIVA S Y TURISTICAS YAHUARCOC HA. GADI-UGP-AVN-004 / Fiscaliz Component 1: Improve mobi Selección basada Open - Internationa ación de la construcción del IBRD / 85790 Previa 2,613,680.20 Firmado 2017-01-29 2017-09-12 2017-05-24 2017-09-14 2017-06-13 2017-09-18 2017-07-13 2017-10-27 2017-07-18 2017-12-04 2017-07-26 2018-01-15 2017-08-07 2018-01-30 2018-11-30 lity in the city en calidad y costo l anillo vial tramo Norte GADI-UGP-CONS-007 / Cons Component 3: Technical Assi Selección basada Open - Internationa IBRD / 85790 Previa 0.00 Cancelado 2017-10-21 2017-10-31 2017-12-10 2017-12-20 2017-12-30 2018-01-19 2018-02-08 2018-05-09 ultoria Mantenimiento de la r stance en calidad y costo l ed vial GADI-UGP-CONS-008 / Cons Component 3: Technical Assi Selección basada Open - Internationa ultoría del Plan de Transporte IBRD / 85790 Previa 0.00 Cancelado 2017-10-21 2017-10-31 2017-11-25 2017-12-05 2017-12-12 2018-01-01 2018-01-21 2018-07-20 stance en calidad y costo l no motorizado y seguridad vi al GADI-UGP-CONS-010 / Contr Component 4: Project Manag Selección basada IBRD / 85790 Posterior Open - National 13,435.00 Finalizado 2017-08-18 2017-10-16 2017-09-01 2017-10-25 2017-09-21 2017-11-19 2017-10-23 2017-12-19 2017-10-30 2018-01-08 2017-11-11 2018-01-29 2017-12-01 2018-02-24 2018-04-27 2019-01-15 atación auditoría financiera ement en calidad y costo GADI-UGP-CONS-020-2018 / Component 4: Project Manag Selección basada AUDITORIA A LOS ESTADOS F IBRD / 85790 Posterior Open - National 18,500.00 Finalizado 2018-10-10 2018-10-17 2018-10-24 2018-11-13 2018-12-15 2018-11-21 2018-12-22 2018-12-12 2019-01-03 2018-12-18 2019-01-23 2019-02-27 2019-06-19 2019-05-26 ement en calidad y costo INANCIEROS DEL PROYECTO MITCI - 2018 EC-GAD-IBARRA-101163-CS- QCBS / CONSULTORÍA PARA L Component 2: Improve publi Selección basada IBRD / 85790 Posterior Open - National 0.00 Cancelado 2019-02-19 2019-02-20 2019-02-24 2019-03-20 2019-04-26 2019-05-10 2019-05-31 2019-07-31 2019-11-29 A OPTIMIZACIÓN Y AJUSTES A c and tourist spaces en calidad y costo L TRAZADO ANILLO VIAL TRA MO SUR EC-GAD-I-2021-CS-SBCC-01 / Auditoría Externa a los Estad os Financieros del Proyecto, f Component 4: Project Manag Selección basada inanciado con Recursos Prov IBRD / 85790 Posterior Open - National 0.00 Cancelado 2021-02-01 2021-02-15 2021-03-08 2021-04-05 2021-04-19 2021-05-08 2021-05-31 2021-08-29 ement en calidad y costo enientes del Contrato de Prés tamo IBRD-8579-EC y Fondos Propios Municipales, para el Ejercicio Fiscal 2021 EC-GAD-I-2021-CS-SBCC-03 / Component 4: Project Manag Selección basada Ejecución pendien Consultoría de evaluación y d IBRD / 85790 Posterior Open - National 0.00 2021-02-01 2021-02-15 2021-03-08 2021-04-05 2021-04-19 2021-05-08 2021-05-31 2021-08-29 ement en calidad y costo te e impacto final del Proyecto GADI-UGP-AVS-005 / Fiscaliz Component 1: Improve mobi Selección basada Open - Internationa ación de la construcción del IBRD / 85790 Previa 0.00 Cancelado 2017-10-01 2017-10-11 2017-11-20 2017-11-30 2017-12-15 2017-12-30 2019-03-05 2019-04-04 lity in the city en calidad y costo l anillo vial tramo Sur GADI-UGP-CONS-009 / Cons ultoria Estudio de Integración Component 3: Technical Assi Selección basada Open - Internationa IBRD / 85790 Previa 0.00 Cancelado 2017-10-21 2017-10-31 2017-11-20 2017-11-30 2017-12-10 2017-12-30 2018-01-14 2018-07-13 , planificación Urbana densifi stance en calidad y costo l cación y movilidad. GADI-UGP-CONS-002-2019 / Auditoría Externa a los Estad os Financieros del Proyecto, f Component 4: Project Manag Selección basada inanciado con Recursos Prov IBRD / 85790 Posterior Open - National 21,262.08 Firmado 2020-05-06 2019-11-01 2020-05-07 2020-05-09 2019-11-20 2020-05-10 2020-01-16 2020-05-11 2020-02-03 2020-05-13 2020-02-03 2020-05-15 2020-05-24 2020-06-15 ement en calidad y costo enientes del Contrato de Prés tamo IBRD-8579-EC y Fondos Propios Municipales, para el Ejercicio Fiscal 2019 EC-GAD-I-2021-CS-SBCC-02 / Consultoría de Supervisión y Fiscalización de la Construcci Component 1: Improve mobi Selección basada Open - Internationa Ejecución pendien ón de la conexión Anillo Vial t IBRD / 85790 Previa 0.00 2020-12-28 2021-01-12 2021-02-09 2021-03-11 2021-03-25 2021-04-12 2021-05-05 2022-07-29 lity in the city en calidad y costo l te ramo Norte - Laguna Yahuarc ocha y Obras complementari as de Mejoramiento de la Infr aestructura de Transporte Page 2 EC-GAD-I-2020-CS-SBCC-04 / Estudio de Reestructuración Component 3: Technical Assi Selección basada Open - Internationa IBRD / 85790 Posterior 0.00 Firmado 2020-05-04 2021-12-09 2020-05-18 2021-12-20 2020-06-01 2022-06-30 2020-06-29 2022-10-17 2020-07-13 2023-02-14 2020-07-30 2023-04-14 2020-08-24 2023-04-21 2021-08-24 del Transporte Público y su P stance en calidad y costo l rotocolo de Seguridad de la C iudad de Ibarra EC-GAD-I-2020-CS-SBCC-01 / Consultoría evaluación de alt ernativas para conexión vial entre Anillo Norte y acceso a Component 1: Improve mobi Selección basada Open - Internationa Yahuarcocha, Optimización d IBRD / 85790 Previa 2,003,901.01 Firmado 2020-03-13 2020-06-04 2020-05-18 2020-06-17 2020-06-08 2020-10-15 2020-07-08 2020-11-26 2020-07-17 2021-08-31 2020-07-30 2021-09-14 2020-08-09 2021-11-16 2021-02-15 lity in the city en calidad y costo l el trazado Anillo Sur y estudi os definitivos de ingeniería, s ocial y ambiental para altern ativa seleccionada y trazado definitivo Anillo Sur EC-GAD-I-2020-CS-SBCC-03 / Estudio del centro histórico y su patrimonio cultural ademá Component 3: Technical Assi Selección basada Open - Internationa s de planes parciales urbanís IBRD / 85790 Posterior 0.00 Cancelado 2020-05-04 2021-07-14 2020-05-18 2020-06-01 2020-06-29 2020-07-13 2020-07-30 2020-08-24 2021-08-24 stance en calidad y costo l ticos de sectores específicos de la Ciudad de Ibarra para e l mejoramiento de su planific ación urbana EC-GAD-I-2020-CS-SBCC-05 / Sistema para la Gestión y Ma ntenimiento de Activos Viale Component 3: Technical Assi Selección basada s y el establecimiento de un IBRD / 85790 Posterior Open - National 0.00 Cancelado 2020-05-04 2020-05-18 2020-06-01 2020-06-29 2020-07-13 2020-07-30 2020-08-24 2021-06-20 stance en calidad y costo programa para la formación de microempresas de mante nimiento vial rutinario de la C iudad de Ibarra EC-GAD-I-2021-CS-SBCC-06 / Sistema para la Gestión y Ma ntenimiento de Activos Viale Component 3: Technical Assi Selección basada Open - Internationa s y el establecimiento de un IBRD / 85790 Posterior 0.00 En ejecución 2021-04-12 2021-01-29 2021-05-03 2021-06-07 2021-05-31 2021-07-15 2021-07-29 2021-08-12 2021-08-22 2022-03-20 stance en calidad y costo l programa para la formación de microempresas de mante nimiento vial rutinario de la C iudad de Ibarra EC-GAD-I-2020-CS-SBCC-02 / Auditoría Externa a los Estad os Financieros del Proyecto, f Component 4: Project Manag Selección basada inanciado con Recursos Prov IBRD / 85790 Posterior Open - National 0.00 Cancelado 2020-10-05 2020-10-19 2020-11-09 2020-12-07 2020-12-21 2021-01-04 2021-02-01 2021-05-02 ement en calidad y costo enientes del Contrato de Prés tamo IBRD-8579-EC y Fondos Propios Municipales, para el Ejercicio Fiscal 2020 EC-GAD-I-2021-CS-SBCC-04 / Estudio de planificación urba na, gestión patrimonial y turí stica destinado a promover e Component 3: Technical Assi Selección basada Open - Internationa IBRD / 85790 Posterior 0.00 En ejecución 2021-07-23 2021-10-27 2021-08-23 2021-11-29 2021-09-20 2021-11-04 2021-11-25 2021-12-16 2021-12-27 2022-06-25 l desarrollo urbano integral d stance en calidad y costo l el área de influencia de la ob ra del tramo norte del Anillo Vial de la ciudad de Ibarra y su centro histórico EC-GAD-I-2023-CS-SBCC-08 / Auditoría a los Estados Finan cieros del proyecto, financiad Component 3: Technical Assi Selección basada os con recursos provenientes IBRD / 85790 Posterior Open - National 0.00 En ejecución 2023-08-07 2023-09-08 2023-08-28 2023-09-15 2023-09-18 2023-10-10 2023-10-02 2023-11-15 2023-10-23 2023-11-21 2023-11-20 2023-11-30 2023-12-11 2024-12-10 stance en calidad y costo del contrato de préstamo BIR F-8579-EC y fondos propios municipales, para el ejercicio Fiscal 2023 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EC-GAD-IBARRA-14798-CS-C DS / CONSULTORIA PARA LA COORDINACION DE LA UNIDA Component 4: Project Manag Selección directa IBRD / 85790 Posterior Direct 49,733.53 Finalizado 2017-05-24 2016-12-30 2017-05-26 2017-01-25 2017-05-29 2017-02-19 2018-05-24 2018-02-18 D DE GESTION DEL PROYECT ement de consultores O DE MEJORAMIENTO DE INF RAESTRUCTURA DE TRANSP ORTE DE LA CIUDAD DE IBAR RA. GADI-UGP-CONS-012 / Cons Component 4: Project Manag IBRD / 85790 Posterior Individual Open 38,778.85 Finalizado 2017-01-02 2017-01-02 2017-01-22 2017-02-02 2017-01-27 2017-02-06 2017-02-21 2018-02-01 2018-02-07 ultor Asesor Financiero ement GADI-UGP-CONS-013 / Cons Component 4: Project Manag IBRD / 85790 Posterior Individual Open 29,084.14 Firmado 2017-02-02 2017-01-02 2017-03-14 2017-02-20 2017-03-24 2017-03-15 2017-04-06 2017-04-11 2018-04-01 2017-04-11 ultor Asesor Ambiental ement GADI-UGP-CONS-014 / Cons Component 4: Project Manag IBRD / 85790 Posterior Individual Direct 38,778.85 Finalizado 2017-01-02 2016-12-30 2017-01-18 2017-01-30 2017-01-28 2017-01-31 2018-02-02 2017-02-08 2018-02-12 2018-02-07 ultor Asesor Tecnico ement GADI-UGP-CONS-015 / Cons Component 4: Project Manag IBRD / 85790 Posterior Individual Direct 34,224.09 Finalizado 2017-02-02 2017-02-02 2017-02-22 2017-02-23 2017-02-25 2017-02-27 2017-03-04 2017-03-28 2018-02-27 2018-03-07 ultor Asesor Social ement GADI-UGP-CONS-016 / Cons Component 4: Project Manag IBRD / 85790 Posterior Individual Open 22,022.66 Finalizado 2017-03-02 2017-03-06 2017-03-24 2017-03-27 2017-03-29 2017-04-08 2017-04-12 2018-04-03 2018-04-05 ultor Monitor Social ement GADI-UGP-CONS-018 / Cons Component 4: Project Manag IBRD / 85790 Posterior Individual Open 22,022.66 Finalizado 2017-04-24 2017-05-16 2017-05-14 2017-05-29 2017-05-19 2017-05-30 2017-05-29 2017-06-28 2018-05-24 2018-05-05 ultor Asistente de Adquicisio ement nes EC-GAD-IBARRA-52407-CS-C Component 4: Project Manag Selección directa IBRD / 85790 Posterior Direct 38,790.94 Firmado 2018-03-06 2018-03-27 2018-04-05 2018-04-25 2018-04-17 2021-04-09 DS / CONSULTOR ASESOR FI ement de consultores NANCIERO EC-GAD-IBARRA-52473-CS-I Component 4: Project Manag IBRD / 85790 Posterior Individual Open 38,778.85 Finalizado 2018-03-06 2016-04-17 2018-04-15 2017-12-22 2018-04-20 2017-12-26 2018-04-30 2018-01-24 2019-04-30 2020-01-19 NDV / CONSULTOR ASESOR A ement MBIENTAL EC-GAD-IBARRA-52475-CS-C Component 4: Project Manag Selección directa IBRD / 85790 Posterior Direct 41,517.15 Firmado 2018-03-06 2018-03-26 2018-04-05 2018-04-25 2018-04-17 2021-04-09 DS / CONSULTOR ASESOR TÉ ement de consultores CNICO EC-GAD-IBARRA-52649-CS-C Component 4: Project Manag Selección directa DS / CONSULTORIA PARA LA IBRD / 85790 Posterior Direct 49,745.63 Firmado 2018-03-07 2018-03-26 2018-04-06 2018-04-26 2018-04-17 2021-04-10 ement de consultores COORDINACIÓN DE LA UGP- MITCI EC-GAD-IBARRA-52984-CS-I Component 4: Project Manag NDV / CONSULTOR ESPECIALI IBRD / 85790 Posterior Individual Open 43,445.87 Finalizado 2018-03-08 2018-04-10 2018-05-22 2018-05-07 2018-06-06 2018-05-10 2018-07-01 2018-05-28 2021-06-15 2019-05-14 ement STA EN INFRAESTRUCTURA. Page 3 EC-GAD-IBARRA-54515-CS-I Component 4: Project Manag IBRD / 85790 Posterior Individual Open 26,764.14 Firmado 2018-03-19 2018-04-09 2018-05-23 2018-05-07 2018-06-06 2018-05-10 2018-07-01 2018-05-20 2021-06-15 NDV / CONSULTOR COMUNIC ement ACIONAL EC-GAD-IBARRA-54567-CS-I Component 4: Project Manag Selección directa NDV / CONSULTOR ESPECIALI IBRD / 85790 Posterior Direct 39,471.32 Firmado 2018-03-19 2018-03-27 2018-04-14 2018-05-01 2018-04-17 2021-04-15 ement de consultores STA SOCIAL EC-GAD-IBARRA-63785-CS-C DS / Renovación de servicios Component 4: Project Manag Selección directa de consultoría para Especiali IBRD / 85790 Posterior Direct 24,678.93 Firmado 2018-05-22 2018-05-22 2018-06-01 2018-06-21 2018-05-06 2021-06-05 ement de consultores sta de Adquisiciones que pre stara sus servicios en la UGP EC-GAD-IBARRA-63792-CS-C Component 4: Project Manag Selección directa DS / Renovación de servicios IBRD / 85790 Posterior Direct 28,285.08 Firmado 2018-05-22 2018-05-22 2018-06-11 2018-07-01 2018-04-06 2021-06-15 ement de consultores de consultoría para Monitor S ocial EC-GAD-IBARRA-82571-CS-I NDV / CONSULTORÍA PARA P Component 4: Project Manag IBRD / 85790 Posterior Individual Open 10,000.00 Firmado 2018-10-31 2018-10-02 2018-12-19 2019-01-09 2019-01-23 2019-02-13 2019-02-20 2019-05-13 REPARACIÓN DE TDR DE ASI ement STENCIA TÉCNICA. EC-GAD-I-2020-CS-INDV-CD- 01 / Contratación de un cons Component 4: Project Manag IBRD / 85790 Posterior Individual Direct 55,714.92 Finalizado 2020-04-06 2019-12-12 2020-04-08 2019-12-16 2020-04-09 2019-12-23 2020-04-11 2020-01-06 2020-12-31 2021-01-05 ultor individual para la Coordi ement nación de la Unidad de Gesti ón del Proyecto MITCI EC-GAD-I-2020-CS-INDV-CD- 02 / Contratación de un cons Component 4: Project Manag ultor individual como Especia IBRD / 85790 Posterior Individual Direct 43,432.32 Finalizado 2020-04-06 2019-12-12 2020-04-08 2019-12-16 2020-04-09 2019-12-23 2020-04-11 2020-01-06 2020-12-31 2021-01-05 ement lista Ambiental de la Unidad de Gestión del Proyecto MITC I EC-GAD-I-2020-CS-INDV-CD- 03 / Contratación de un cons Component 4: Project Manag ultor individual como Oficial IBRD / 85790 Posterior Individual Direct 43,445.88 Finalizado 2020-04-06 2019-12-12 2020-04-08 2019-12-16 2020-04-09 2019-12-23 2020-04-11 2020-01-06 2020-12-31 2021-01-05 ement Financiero de la Unidad de G estión del Proyecto MITCI EC-GAD-I-2020-CS-INDV-CD- 04 / Contratación de un cons Component 4: Project Manag ultor individual como Especia IBRD / 85790 Posterior Individual Direct 43,571.16 Finalizado 2020-04-06 2019-12-12 2020-04-08 2019-12-16 2020-04-09 2019-12-23 2020-04-11 2020-01-06 2020-12-31 2021-01-05 ement lista Social de la Unidad de G estión del Proyecto MITCI EC-GAD-I-2020-CS-INDV-CD- 05 / Contratación de un cons Component 4: Project Manag ultor individual como Asesor IBRD / 85790 Posterior Individual Direct 3,874.93 Finalizado 2020-04-06 2019-12-12 2020-04-08 2019-12-16 2020-04-09 2019-12-23 2020-04-11 2020-01-06 2020-12-31 2021-01-05 ement Técnico de la Unidad de Gest ión del Proyecto MITCI EC-GAD-I-2020-CS-INDV-CD- 06 / Contratación de un cons Component 4: Project Manag ultor individual como Comuni IBRD / 85790 Posterior Individual Direct 26,764.20 Finalizado 2020-04-06 2019-12-12 2020-04-08 2019-12-16 2020-04-09 2019-12-23 2020-04-11 2020-01-06 2020-12-31 2021-01-05 ement cador Social de la Unidad de Gestión del Proyecto MITCI EC-GAD-I-2020-CS-INDV-CD- 07 / Contratación de un cons Component 4: Project Manag IBRD / 85790 Posterior Individual Direct 31,679.28 Finalizado 2020-04-06 2019-12-12 2020-04-08 2019-12-16 2020-04-09 2019-12-23 2020-04-11 2020-01-06 2020-12-31 2021-01-05 ultor individual como Monitor ement Social de la Unidad de Gestió n del Proyecto MITCI EC-GAD-I-2020-CS-INDV-3CV -01 / Contratación de un cons Component 4: Project Manag ultor individual como Especia IBRD / 85790 Posterior Individual Open 36,960.00 Finalizado 2020-04-06 2019-09-25 2020-04-09 2019-12-11 2020-04-10 2020-01-30 2020-04-12 2020-02-06 2020-12-31 2021-01-05 ement lista en Adquisiciones de la U nidad de Gestión del Proyect o MITCI EC-GAD-I-2020-CS-INDV-3CV -02 / Contratación de un cons Component 4: Project Manag ultor individual como Especia IBRD / 85790 Posterior Individual Open 25,343.43 Firmado 2020-03-16 2020-05-04 2020-04-20 2020-05-25 2020-04-24 2020-05-29 2020-05-01 2021-01-06 2021-01-30 ement lista en Planificación de la Un idad de Gestión del Proyecto MITCI EC-GAD-I-2021-CS-INDV-CD- 01 / Contratación de un cons Component 4: Project Manag IBRD / 85790 Posterior Individual Direct 55,714.98 Firmado 2020-11-02 2020-12-09 2020-11-17 2020-12-30 2020-11-27 2020-12-31 2021-01-01 2021-01-18 2021-06-30 ultor individual para la Coordi ement nación de la Unidad de Gesti ón del Proyecto MITCI EC-GAD-I-2021-CS-INDV-CD- 02 / Contratación de un cons Component 4: Project Manag ultor individual como Especia IBRD / 85790 Posterior Individual Direct 43,432.30 Firmado 2020-11-02 2020-12-09 2020-11-17 2020-12-30 2020-11-27 2020-12-31 2021-01-01 2021-01-18 2021-06-30 ement lista Ambiental de la Unidad de Gestión del Proyecto MITC I EC-GAD-I-2021-CS-INDV-CD- 03 / Contratación de un cons Component 4: Project Manag ultor individual como Oficial IBRD / 85790 Posterior Individual Direct 43,445.88 Firmado 2020-11-02 2020-12-09 2020-11-17 2020-12-30 2020-11-27 2020-12-31 2021-01-01 2021-01-18 2021-06-30 ement Financiero de la Unidad de G estión del Proyecto MITCI EC-GAD-I-2021-CS-INDV-CD- 04 / Contratación de un cons Component 4: Project Manag ultor individual como Especia IBRD / 85790 Posterior Individual Direct 43,571.14 Firmado 2020-11-02 2020-12-09 2020-11-17 2020-12-30 2020-11-27 2020-12-31 2021-01-01 2021-01-18 2021-06-30 ement lista Social de la Unidad de G estión del Proyecto MITCI EC-GAD-I-2021-CS-INDV-CD- 05 / Contratación de un cons Component 4: Project Manag ultor individual como Asesor IBRD / 85790 Posterior Individual Direct 46,499.04 Firmado 2020-11-02 2020-12-09 2020-11-17 2020-12-30 2020-11-27 2020-12-31 2021-01-01 2021-01-18 2021-06-30 ement Técnico de la Unidad de Gest ión del Proyecto MITCI EC-GAD-I-2021-CS-INDV-CD- 06 / Contratación de un cons Component 4: Project Manag ultor individual como Comuni IBRD / 85790 Posterior Individual Direct 26,764.15 Firmado 2020-11-02 2020-12-09 2020-11-17 2020-12-30 2020-11-27 2020-12-31 2021-01-01 2021-01-18 2021-06-30 ement cador Social de la Unidad de Gestión del Proyecto MITCI EC-GAD-I-2021-CS-INDV-CD- 08 / Contratación de un cons Component 4: Project Manag ultor individual como Especia IBRD / 85790 Posterior Individual Direct 40,320.00 Firmado 2020-11-02 2020-12-09 2020-11-17 2020-12-30 2020-11-27 2020-12-31 2021-01-01 2021-01-18 2021-06-30 ement lista en Adquisiciones de la U nidad de Gestión del Proyect o MITCI Page 4 EC-GAD-I-2021-CS-INDV-CD- 09 / Contratación de un cons Component 4: Project Manag IBRD / 85790 Posterior Individual Direct 31,679.29 Firmado 2020-11-02 2020-12-09 2020-11-17 2020-12-30 2020-11-27 2020-12-31 2021-01-01 2021-01-18 2021-06-30 ultor individual como Monitor ement Social de la Unidad de Gestió n del Proyecto MITCI EC-GAD-I-2019-CS-INDV-CD- 01 / Contratación de un cons Component 4: Project Manag IBRD / 85790 Posterior Individual Direct 20,428.84 Finalizado 2020-04-06 2019-08-06 2020-04-08 2019-08-14 2020-04-09 2019-08-19 2020-04-11 2019-08-23 2020-04-12 2020-01-05 ultor individual para la Coordi ement nación de la Unidad de Gesti ón del Proyecto MITCI EC-GAD-I-2019-CS-INDV-CD- 02 / Contratación de un cons Component 4: Project Manag ultor individual como Especia IBRD / 85790 Posterior Individual Direct 43,432.30 Finalizado 2020-04-06 2018-12-21 2020-04-08 2019-01-02 2020-04-09 2019-01-02 2020-04-11 2019-01-07 2020-04-12 2020-01-05 ement lista Ambiental de la Unidad de Gestión del Proyecto MITC I EC-GAD-I-2019-CS-INDV-3CV -01 / Contratación de un cons Component 4: Project Manag ultor individual como Oficial IBRD / 85790 Posterior Individual Open 10,861.47 Finalizado 2020-04-06 2019-09-16 2020-04-09 2019-09-26 2020-04-10 2019-09-27 2020-04-12 2019-10-05 2020-04-13 2020-01-05 ement Financiero de la Unidad de G estión del Proyecto MITCI EC-GAD-I-2019-CS-INDV-CD- 03 / Contratación de un cons Component 4: Project Manag ultor individual como Especia IBRD / 85790 Posterior Individual Direct 15,976.13 Finalizado 2020-04-06 2019-08-12 2020-04-08 2019-08-14 2020-04-09 2019-08-19 2020-04-11 2019-08-23 2020-04-12 2020-01-05 ement lista Social de la Unidad de G estión del Proyecto MITCI EC-GAD-I-2019-CS-INDV-3CV -02 / Contratación de un cons Component 4: Project Manag ultor individual como Asesor IBRD / 85790 Posterior Individual Open 7,749.86 Finalizado 2020-04-06 2019-09-26 2020-04-09 2019-10-18 2020-04-10 2019-10-28 2020-04-12 2019-11-05 2020-04-13 2020-01-05 ement Técnico de la Unidad de Gest ión del Proyecto MITCI EC-GAD-I-2019-CS-INDV-3CV -03 / Contratación de un cons Component 4: Project Manag ultor individual como Comuni IBRD / 85790 Posterior Individual Open 4,460.70 Finalizado 2020-04-06 2019-09-26 2020-04-09 2019-10-21 2020-04-10 2019-10-30 2020-04-12 2019-11-05 2020-04-13 2020-01-05 ement cador Social de la Unidad de Gestión del Proyecto MITCI EC-GAD-I-2019-CS-INDV-3CV -04 / Contratación de un cons Component 4: Project Manag ultor individual como Monitor IBRD / 85790 Posterior Individual Open 11,615.74 Finalizado 2020-04-06 2019-07-30 2020-04-09 2019-08-14 2020-04-10 2019-08-16 2020-04-12 2019-08-23 2020-04-13 2020-01-05 ement Social de la Unidad de Gestió n del Proyecto MITCI EC-GAD-I-2021-CS-SBCC-07 / Auditoría Externa a los Estad os Financieros del Proyecto, f Component 4: Project Manag Selección directa inanciado con Recursos Prov IBRD / 85790 Posterior Direct 21,262.08 Firmado 2021-03-31 2021-04-22 2021-04-12 2021-05-10 2021-04-30 2021-06-04 2021-06-30 ement de consultores enientes del Contrato de Prés tamo BIRF 8579-EC y Fondos Propios Municipales, para el Ejercicio Fiscal 2020 EC-GAD-I-2021-CS-SD-01 / A uditoría Externa a los Estado s Financieros del Proyecto, fi Component 4: Project Manag Selección directa nanciado con Recursos Prove IBRD / 85790 Posterior Direct 0.00 En ejecución 2021-11-15 2021-12-07 2021-11-25 2021-12-27 2022-03-27 ement de consultores nientes del Contrato de Prést amo IBRD-8579-EC y Fondos Propios Municipales, para el Ejercicio Fiscal 2021 EC-GAD-I-2021-CS-INDV-CD- 07 / Contratación de un cons Component 4: Project Manag ultor individual como Especia IBRD / 85790 Posterior Individual Direct 0.00 Cancelado 2020-11-02 2020-11-17 2020-11-27 2021-01-01 2021-06-30 ement lista en Planificación de la Un idad de Gestión del Proyecto MITCI EC-GAD-IBARRA-275668-CS-I NDV / Contratación de un co nsultor individual como asist Component 4: Project Manag Ejecución pendien IBRD / 85790 Posterior Individual Open 0.00 2022-01-31 2022-02-20 2022-02-21 2022-03-01 2024-12-31 ente administrativo de la Uni ement te dad de Gestión del Proyecto MITCI para el período 2022-2 024 EC-GAD-IBARRA-275651-CS- CDS / Contratación de un con Component 4: Project Manag sultor individual como Asesor IBRD / 85790 Posterior Individual Direct 0.00 Bajo Revision 2022-02-16 2021-12-27 2022-02-18 2022-02-19 2022-02-21 2024-12-31 ement Técnico de la Unidad de Gest ión del Proyecto MITCI para e l período 2022-2024 EC-GAD-IBARRA-275660-CS- CDS / Contratación de un con Component 4: Project Manag sultor individual como Oficial IBRD / 85790 Posterior Individual Direct 0.00 Bajo Revision 2022-02-16 2021-12-27 2022-02-18 2022-02-19 2022-02-21 2024-12-31 ement Financiero de la Unidad de G estión del Proyecto MITCI par a el período 2022-2024 EC-GAD-IBARRA-275662-CS- CDS / Contratación de un con sultor individual como Especi Component 4: Project Manag IBRD / 85790 Posterior Individual Direct 0.00 Bajo Revision 2022-02-16 2021-12-27 2022-02-18 2022-02-19 2022-02-21 2024-12-31 alista Ambiental de la Unidad ement de Gestión del Proyecto MITC I para el período 2022-2024 EC-GAD-IBARRA-275663-CS- CDS / Contratación de un con sultor individual como Especi Component 4: Project Manag IBRD / 85790 Posterior Individual Direct 0.00 Bajo Revision 2022-02-16 2021-12-27 2022-02-18 2022-02-19 2022-02-21 2024-12-31 alista en Planificación de la U ement nidad de Gestión del Proyect o MITCI para el período 2022- 2024 EC-GAD-IBARRA-275664-CS- CDS / Contratación de un con sultor individual como Especi Component 4: Project Manag IBRD / 85790 Previa Individual Direct 0.00 Bajo Revision 2022-02-16 2022-02-18 2022-02-19 2022-02-21 2024-12-31 alista en Adquisiciones de la ement Unidad de Gestión del Proyec to MITCI para el período 2022 -2024 EC-GAD-IBARRA-275661-CS- CDS / Contratación de un con Component 4: Project Manag sultor individual como Especi IBRD / 85790 Posterior Individual Direct 0.00 Bajo Revision 2022-02-16 2021-12-27 2022-02-18 2022-02-19 2022-02-21 2024-12-31 ement alista Social de la Unidad de Gestión del Proyecto MITCI p ara el período 2022-2024 Page 5 EC-GAD-IBARRA-275650-CS- CDS / Contratación de un con Component 4: Project Manag sultor individual para la Coor IBRD / 85790 Posterior Individual Direct 0.00 En ejecución 2022-02-16 2021-12-27 2022-02-18 2022-02-19 2022-02-21 2024-12-31 ement dinación de la Unidad de Ges tión del Proyecto MITCI para el período 2022-2024 EC-GAD-IBARRA-275665-CS- CDS / Contratación de un con Component 4: Project Manag sultor individual como Monito IBRD / 85790 Posterior Individual Direct 0.00 Bajo Revision 2022-02-16 2021-12-27 2022-02-18 2022-02-19 2022-02-21 2024-12-31 ement r Social de la Unidad de Gesti ón del Proyecto MITCI para el período 2022-2024 EC-GAD-IBARRA-275667-CS- CDS / Contratación de un con sultor individual como Comu Component 4: Project Manag IBRD / 85790 Posterior Individual Direct 23,896.56 Firmado 2022-02-16 2021-12-27 2022-02-18 2021-12-21 2022-02-19 2021-12-30 2022-02-21 2022-01-06 2024-12-31 nicador Social de la Unidad d ement e Gestión del Proyecto MITCI para el período 2022-2024 EC-GAD-IBARRA-303776-CS-I NDV / Contratación ingeniero civil con especialización en e structuras y experiencia en p Component 1: Improve mobi uentes para la revisión del di IBRD / 85790 Posterior Individual Limited 0.00 En ejecución 2022-08-01 2022-08-22 2022-08-05 2022-08-19 2022-09-01 2022-11-30 lity in the city seño y proceso constructivo del puente que se incluye en la alternativa seleccionada p ara la conexión vial entre el Anillo Vial y Yahuarcocha EC-GAD-IBARRA-303806-CS-I NDV / Contratación de un co Component 4: Project Manag nsultor individual como Anali IBRD / 85790 Posterior Individual Open - National 0.00 En ejecución 2022-08-01 2022-08-31 2022-08-19 2022-08-26 2022-09-01 2023-05-31 ement sta en Infraestructura Vial de la Unidad de Gestión del Proy ecto MITCI EC-GAD-IBARRA-316150-CS-I NDV / Contratación de un co nsultor individual como Com Component 4: Project Manag IBRD / 85790 Posterior Individual Limited 0.00 En ejecución 2022-09-14 2022-09-15 2022-09-19 2022-10-10 2022-11-14 2023-05-31 unicador Social de la Unidad ement de Gestión del Proyecto MITC I para el período 2022-2023 EC-GAD-IBARRA-325653-CS- CDS / Auditoría Externa a los Estados Financieros del Proy Component 4: Project Manag Selección directa ecto, financiado con Recurso IBRD / 85790 Posterior Direct - National 0.00 En ejecución 2022-11-11 2022-12-20 2022-11-21 2022-12-23 2023-03-23 ement de consultores s Provenientes del Contrato d e Préstamo IBRD-8579-EC y F ondos Propios Municipales, p ara el Ejercicio Fiscal 2022 EC-GAD-IBARRA-361526-CS-I NDV / Contratación de un co nsultor individual como Espe Component 4: Project Manag IBRD / 85790 Posterior Individual Limited 0.00 En ejecución 2023-05-15 2023-09-11 2023-05-19 2023-05-29 2023-06-01 2027-12-31 cialista Social de la Unidad d ement e Gestión del Proyecto MITCI para el período 2023-2027 EC-GAD-IBARRA-361530-CS-I NDV / Contratación de un co nsultor individual como Espe Component 4: Project Manag IBRD / 85790 Posterior Individual Limited 0.00 En ejecución 2023-05-15 2023-05-29 2023-05-19 2023-06-01 2023-05-29 2023-06-01 2027-12-31 cialista Ambiental de la Unid ement ad de Gestión del Proyecto M ITCI para el período 2023-20 27 EC-GAD-IBARRA-361533-CS-I NDV / Contratación de un co Component 4: Project Manag nsultor individual como Ofici IBRD / 85790 Posterior Individual Limited 0.00 Firmado 2023-05-15 2023-05-29 2023-05-19 2023-06-01 2023-05-29 2023-06-13 2023-06-01 2023-06-14 2027-12-31 ement al Financiero de la Unidad de Gestión del Proyecto MITCI p ara el período 2023-2027 EC-GAD-IBARRA-361534-CS-I NDV / Contratación de un co Component 4: Project Manag nsultor individual como Ases IBRD / 85790 Posterior Individual Limited 0.00 Firmado 2023-05-15 2023-06-28 2023-05-19 2023-06-29 2023-05-29 2023-07-14 2023-06-01 2023-07-14 2027-12-31 ement or Técnico de la Unidad de G estión del Proyecto MITCI par a el período 2023-2027 EC-GAD-IBARRA-361535-CS-I NDV / Contratación de un co nsultor individual como Anali Component 4: Project Manag IBRD / 85790 Posterior Individual Limited 0.00 Firmado 2023-05-15 2023-06-16 2023-05-19 2023-06-28 2023-05-29 2023-07-12 2023-06-01 2023-07-14 2027-12-31 sta de Infraestructura Vial de ement la Unidad de Gestión del Proy ecto MITCI para el período 20 23-2027 EC-GAD-IBARRA-361536-CS-I NDV / Contratación de un co nsultor individual como Com Component 4: Project Manag IBRD / 85790 Posterior Individual Limited 0.00 En ejecución 2023-05-15 2023-05-29 2023-05-19 2023-06-01 2023-05-29 2023-06-12 2023-06-01 2027-12-31 unicador Social de la Unidad ement de Gestión del Proyecto MITC I para el período 2023-2027 EC-GAD-IBARRA-361868-CS-I NDV / Contratación de un co nsultor individual como Anali Component 4: Project Manag Ejecución pendien IBRD / 85790 Previa Individual Limited 0.00 2023-05-15 2023-05-19 2023-05-29 2023-06-01 2027-12-31 sta en Adquisiciones de la Un ement te idad de Gestión del Proyecto MITCI para el período 2023-2 027 EC-GAD-IBARRA-364748-CS-I NDV / Contratación de un co nsultor individual como Espe Component 4: Project Manag IBRD / 85790 Previa Individual Limited 0.00 En ejecución 2023-05-31 2023-06-29 2023-06-14 2023-06-29 2023-06-21 2023-07-01 2027-12-31 cialista en Adquisiciones de l ement a Unidad de Gestión del Proy ecto MITCI para el período 20 23-2027 EC-GAD-IBARRA-364749-CS-I NDV / Contratación de un co Component 4: Project Manag nsultor individual como Coor IBRD / 85790 Posterior Individual Limited 0.00 Firmado 2023-05-31 2023-05-29 2023-06-14 2023-06-01 2023-06-21 2023-07-13 2023-07-01 2023-07-14 2027-12-31 ement dinador de la Unidad de Gest ión del Proyecto MITCI para e l período 2023-2027 EC-GAD-IBARRA-364752-CS-I NDV / Contratación de un co Component 4: Project Manag nsultor individual como Monit IBRD / 85790 Posterior Individual Limited 0.00 En ejecución 2023-05-31 2023-05-29 2023-06-14 2023-06-01 2023-06-21 2023-07-01 2027-12-31 ement or Social de la Unidad de Ges tión del Proyecto MITCI para el período 2023-2027 Page 6 EC-GAD-IBARRA-364753-CS-I NDV / Contratación de un co nsultor individual como Asist Component 4: Project Manag IBRD / 85790 Posterior Individual Limited 0.00 Rescindido 2023-05-31 2023-05-29 2023-06-14 2023-06-01 2023-06-21 2023-06-14 2023-07-01 2023-06-14 2023-12-28 ente Administrativa de la Uni ement dad de Gestión del Proyecto MITCI para el período 2023-2 027 EC-GAD-IBARRA-390774-CS-I NDV / Contratación de un co nsultor individual como asist Component 4: Project Manag IBRD / 85790 Posterior Individual Open - National 0.00 En ejecución 2023-11-24 2023-11-29 2023-12-18 2023-12-25 2023-12-31 2024-12-31 ente administrativa de la Uni ement dad de Gestión del Proyecto MITCI para el periodo 2024 - 2027. EC-GAD-IBARRA-390786-CS-I NDV / Contratación de un co nsultor individual como Espe Component 4: Project Manag IBRD / 85790 Previa Individual Open - National 0.00 Bajo Revision 2023-11-24 2023-12-04 2023-12-16 2023-12-23 2023-12-31 2024-12-31 cialista de Adquisiciones en l ement a Unidad de Gestión del Proy ecto MITCI para el periodo 20 24 - 2027. EC-GAD-IBARRA-390789-CS-I NDV / Contratación de un co nsultor individual como Espe Component 4: Project Manag IBRD / 85790 Posterior Individual Open - National 0.00 En ejecución 2023-11-22 2023-11-29 2023-12-18 2023-12-25 2024-01-02 2024-06-30 cialista en Infraestructura y T ement ransporte en la Unidad de Ge stión del Proyecto MITCI para el periodo 2024 - 2027. EC-GAD-IBARRA-404111-202 4-CS-INDV / Contratación dire Component 4: Project Manag Ejecución pendien IBRD / 85790 Posterior Individual Direct - National 0.00 2024-01-21 2024-01-27 2024-02-01 2024-02-09 2024-06-22 cta del Especialista Ambienta ement te l para la Unidad de Gestión d el Proyecto. EC-GAD-IBARRA-404118-202 4-CS-INDV / Contratación dire Component 4: Project Manag Ejecución pendien cta del Asesor Técnico como IBRD / 85790 Posterior Individual Direct - National 0.00 2024-01-21 2024-01-27 2024-01-30 2024-02-05 2024-06-30 ement te Especialista para la Unidad d e Gestión del Proyecto, EC-GAD-IBARRA-404129-202 4-CS-INDV / Contratación dire Component 4: Project Manag Ejecución pendien IBRD / 85790 Posterior Individual Direct - National 0.00 2024-01-21 2024-01-25 2024-01-28 2024-02-03 2024-06-24 cta de Monitora Social para l ement te a Unidad de Gestión del Proy ecto EC-GAD-IBARRA-404130-202 4-CS-INDV / Contratación dire Component 4: Project Manag Ejecución pendien IBRD / 85790 Posterior Individual Direct - National 0.00 2024-01-21 2024-01-25 2024-01-28 2024-02-03 2024-06-30 cta del Coordinador de la Uni ement te dad de Gestión del Proyecto Page 7