PROCUREMENT PLAN (Textual Part) Project information: Nepal Urban Governance and Infrastructure Project (P 163418) Project Implementation agency: Department of Urban Development and Building Construction (DUDBC) Date of the Procurement Plan: 30 June 2020 Period covered by this Procurement Plan: August 2020 – February 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used, with applicable caveats as follows. National Procurement Procedures: These procedures are applicable for the procurement of goods, works and non-consulting services only. In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market, as agreed in the Procurement Plan tables in STEP, the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Nepal’s Public Procurement Act, 2007, as amended by Amendment 2073 (2016) – (1st Amendment) and the Public Procurement Regulation, 2007, as amended by 10th Amendment ((27 Apr 2020)), such arrangements shall be subject to paragraph 5.4 of the Bank’s Procurement Regulations and the following conditions: 1) Model bidding documents, including contract conditions agreed with the Bank (as amended from time to time), shall be used. Bidding documents shall be made available, by mail or in person, or through e-GP portal to all who are willing to pay the required fee. 2) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations; 3) The request for bids / request for proposals document shall require that Bidders / Proposers submitting Bids / Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Qualification criteria (in case pre-qualifications were not carried out) shall be stated in the bidding documents for all contracts, irrespective of the value, and if a registration process is required, a foreign firm declared as the lowest evaluated bidder shall be given a reasonable opportunity to register, without let or hindrance. 5) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts. 6) Performance security should be an amount of five (5) to ten (10) percent of the contract price and shall not be increased merely based on comparison of the bid price of awarded bidders with the pre-bid cost estimate. 7) If a contract is terminated because of fundamental breach of contract by the contractor, the amount to be recovered from the contractor representing the employer’s additional costs for completing the contract shall be provisioned as agreed with the Bank in model bidding documents. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable. Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables PROCUREMENT Nepal : Nepal Urban Governance and Infrastructure Project PLAN General Information Country: Nepal 2020-06-30 Bank’s Approval Date of the Original Procurement Plan: 2024-02-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163418 GPN Date: Project Name: Nepal Urban Governance and Infrastructure Project Loan / Credit No: IDA / V0710, IDA / 67780 Department of Urban Development and Building Construction Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NP-DUDBC-167805-CW-RFB Urban Development Grants ( Open - Internationa Single Stage - Two E 5,922,625.4 2023-09-0 / Upgradation of Talchowk - B IDA / 67780 UDG) for strategic municipal Prior Request for Bids Signed 2021-04-07 2021-05-01 2021-04-17 2021-07-09 2021-06-01 2021-08-02 2021-07-30 2022-04-26 2021-09-03 2022-07-24 l nvelope 0 3 egnas Road, Pokhara infrastructure and service de livery Request for B NP-DUDBC-167839-CW-RFB Urban Development Grants ( ids - Works ( Open - Internationa Single Stage - Two E 2024-04-1 / Upgradation of Mangalapur IDA / 67780 UDG) for strategic municipal Prior Request for Bids without preq 0.00 Canceled 2021-10-30 2021-11-13 2021-12-28 2022-03-08 2022-04-19 l nvelope 8 - Kanchhibazar Road, Tilotta infrastructure and service de ualification) ma livery SPD Request for B NP-DUDBC-167836-CW-RFB Urban Development Grants ( ids - Works ( Open - Internationa Single Stage - Two E 2024-04-1 / Upgradation of Buttabari - P IDA / 67780 UDG) for strategic municipal Prior Request for Bids without preq 0.00 Canceled 2021-10-30 2021-11-13 2021-12-28 2022-03-08 2022-04-19 l nvelope 8 yakurel Chowk Road, Birtamo infrastructure and service de ualification) d livery SPD Request for B NP-DUDBC-167837-CW-RFB Urban Development Grants ( ids - Works ( Open - Internationa Single Stage - Two E 2024-04-1 / Upgradation of Madandangi IDA / 67780 UDG) for strategic municipal Prior Request for Bids without preq 0.00 Canceled 2021-10-30 2021-11-13 2021-12-28 2022-03-08 2022-04-19 l nvelope 8 - Tarabari Dipu Road, Damak infrastructure and service de ualification) livery SPD Request for B NP-DUDBC-167838-CW-RFB Urban Development Grants ( ids - Works ( Open - Internationa Single Stage - Two E 2024-04-1 / Upgradation of Krishna Cho IDA / 67780 UDG) for strategic municipal Prior Request for Bids without preq 0.00 Canceled 2021-10-30 2021-11-13 2021-12-28 2022-03-08 2022-04-19 l nvelope 8 wk - Community Forest Road, infrastructure and service de ualification) Urlabari livery SPD Request for B NP-DUDBC-273140-CW-RFB Urban Development Grants ( ids - Works ( Open - Internationa Single Stage - One E 3,650,875.8 2024-05-2 / Upgradation of Mangalapur IDA / 67780 UDG) for strategic municipal Prior Request for Bids without preq Signed 2022-01-20 2022-01-31 2022-01-25 2022-02-03 2022-03-11 2022-04-04 2022-04-25 2022-09-13 2022-05-30 2022-07-22 l nvelope 7 9 - Kanchhibazar Road, Tilotta infrastructure and service de ualification) ma livery SPD Request for B NP-DUDBC-273141-CW-RFB Urban Development Grants ( ids - Works ( Open - Internationa Single Stage - One E 2024-06-2 / Upgradation of Buttabari - P IDA / 67780 UDG) for strategic municipal Prior Request for Bids without preq 0.00 Signed 2022-02-11 2022-06-30 2022-02-16 2022-07-15 2022-04-02 2022-08-29 2022-05-17 2022-11-07 2022-06-21 2023-03-23 l nvelope 0 yakurel Chowk Road, Birtamo infrastructure and service de ualification) d livery SPD Request for B NP-DUDBC-273142-CW-RFB Urban Development Grants ( ids - Works ( Open - Internationa Single Stage - One E 2024-06-2 / Upgradation of Madandangi IDA / 67780 UDG) for strategic municipal Prior Request for Bids without preq 0.00 Signed 2022-02-18 2022-06-30 2022-02-23 2022-09-28 2022-04-09 2022-11-18 2022-05-24 2023-02-19 2022-06-28 2023-06-04 l nvelope 7 - Tarabari Dipu Road, Damak infrastructure and service de ualification) livery SPD Request for B NP-DUDBC-273143-CW-RFB Urban Development Grants ( ids - Works ( Open - Internationa Single Stage - One E 2024-06-1 / Upgradation of Krishna Cho IDA / 67780 UDG) for strategic municipal Prior Request for Bids without preq 0.00 Signed 2022-02-04 2022-06-30 2022-02-09 2022-07-15 2022-03-26 2022-08-29 2022-05-10 2023-01-11 2022-06-14 2023-05-19 l nvelope 3 wk - Community Forest Road, infrastructure and service de ualification) Urlabari livery SPD Request for B NP-DUDBC-370501-CW-RFB Urban Development Grants ( ids - Works ( Open - Internationa Single Stage - One E 2025-06-2 / Upgradation of Pokharapali- IDA / 67780 UDG) for strategic municipal Prior Request for Bids without preq 0.00 Signed 2023-07-09 2023-07-12 2023-07-16 2023-07-12 2023-08-30 2023-08-29 2023-09-24 2023-09-13 2023-10-29 2023-10-04 l nvelope 0 Panditpur Road, Ramgram infrastructure and service de ualification) livery SPD NP-DUDBC-395275-CW-RFB Urban Development Grants ( Other (with fi Single Stage - One E Under Imple 2024-09-0 / Upgradation of Bebra to Ka IDA / 67780 UDG) for strategic municipal Post Request for Bids Open - National eld for expla 0.00 2023-11-28 2023-12-08 2023-12-03 2024-01-02 2024-02-01 2024-03-07 nvelope mentation 3 nchibazar Section, Tilottama infrastructure and service de nation) livery NP-DUDBC-395280-CW-RFB / UPGRADATION OF DOBILLA – BAGMARA – TIKLANG – BAD Request for B Urban Development Grants ( ARKOT - LAMGADHI- ids - Works ( UDG) for strategic municipal Open - Internationa Single Stage - Two E Under Imple 2025-07-1 CHAPLANG – UPALLO PUDITA IDA / 67780 Prior Request for Bids without preq 0.00 2023-11-28 2023-12-24 2023-11-29 2023-12-25 2024-01-10 2024-03-21 infrastructure and service de l nvelope mentation 4 R – TALLO PUDITAR – JHIGAT ualification) livery E (JANAJAGRITI MA VI) SPD TAGAREGAUDA ROAD, Pokha ra NP-DUDBC-395571-CW-RFB Request for B / Upgradation of Jutbikash Ch Urban Development Grants ( ids - Works ( owk (Mahendra Highway)- Ta UDG) for strategic municipal Open - Internationa Single Stage - Two E Under Imple 2025-07-2 IDA / 67780 Prior Request for Bids without preq 0.00 2023-11-29 2023-12-21 2023-12-04 2023-12-21 2024-01-15 2024-02-08 2024-04-03 ltaliya Road and Bargachhi C infrastructure and service de l nvelope mentation 7 ualification) howk (Koshi Highway)-Mahen livery SPD dra School- Taltalatiya Road, Itahari NP-DUDBC-396306-CW-RFB Urban Development Grants ( Other (with fi / UPGRADATION OF SISUWA- UDG) for strategic municipal Single Stage - Two E Under Imple 2025-06-2 IDA / 67780 Post Request for Bids Open - National eld for expla 0.00 2023-12-11 2023-12-28 2023-12-16 2024-01-15 2024-02-28 2024-03-30 SISHAGHAT (SISUWA - KHUD infrastructure and service de nvelope mentation 3 nation) HI KHOLA SECTION) ROAD livery NP-DUDBC-396312-CW-RFB Urban Development Grants ( Other (with fi / Upgrading of Pragatinagar- UDG) for strategic municipal Single Stage - Two E Under Imple 2025-06-2 IDA / 67780 Post Request for Bids Open - National eld for expla 0.00 2023-12-12 2023-12-28 2023-12-17 2024-01-16 2024-02-29 2024-03-31 Bahakot-Namche-Kalku Road infrastructure and service de nvelope mentation 4 nation) , Putalibazar Municipality livery NP-DUDBC-396319-CW-RFB Urban Development Grants ( Other (with fi / Improvement of Dulegaund UDG) for strategic municipal Single Stage - Two E Under Imple 2025-06-2 IDA / 67780 Post Request for Bids Open - National eld for expla 0.00 2023-12-13 2024-01-01 2023-12-18 2024-01-17 2024-03-01 2024-04-01 a – Lamagaun Road (Dulegau infrastructure and service de nvelope mentation 5 nation) nda – Lila Chowk Section) livery NP-DUDBC-396323-CW-RFB Urban Development Grants ( Other (with fi / UPGRADATION OF HILE (SH UDG) for strategic municipal Single Stage - Two E Under Imple 2025-06-2 IDA / 67780 Post Request for Bids Open - National eld for expla 0.00 2023-12-14 2024-01-14 2023-12-19 2024-01-18 2024-03-02 2024-04-02 ADESHWOR TEMPLE)-BHIRGA infrastructure and service de nvelope mentation 6 nation) UN-MADHUGANGA ROAD livery Request for B NP-DUDBC-400279-CW-RFB Urban Development Grants ( ids - Works ( / upgradation of Gaighat Tow UDG) for strategic municipal Open - Internationa Single Stage - Two E 2025-07-0 IDA / 67780 Prior Request for Bids without preq 0.00 Canceled 2024-01-05 2024-01-10 2024-02-24 2024-04-23 2024-05-28 n Planning Area Road Section infrastructure and service de l nvelope 2 ualification) plus other roads livery SPD NP-DUDBC-400270-CW-RFB Urban Development Grants ( Other (with fi / Up gradation of Sahid Marg UDG) for strategic municipal Single Stage - One E Under Imple 2025-06-2 IDA / 67780 Post Request for Bids Open - National eld for expla 0.00 2024-01-04 2024-01-07 2024-01-09 2024-02-08 2024-02-23 2024-03-29 a (Dhulabari to Thaple Biran infrastructure and service de nvelope mentation 2 nation) Chowk)- Mechinagar livery Page 1 NP-DUDBC-400272-CW-RFB Urban Development Grants ( Other (with fi / Up gradation of Suryodaya UDG) for strategic municipal Single Stage - One E Under Imple 2025-06-2 IDA / 67780 Post Request for Bids Open - National eld for expla 0.00 2024-01-04 2024-01-07 2024-01-09 2024-02-08 2024-02-23 2024-03-29 Marga (Kakarbhitta to Bhand infrastructure and service de nvelope mentation 2 nation) angi Road)- Mechinagar livery NP-DUDBC-400273-CW-RFB Urban Development Grants ( / Parasar Marga (Buldikhola-B Other (with fi UDG) for strategic municipal Single Stage - One E Under Imple 2025-06-2 eltari-Farakchaur-Adheribhya IDA / 67780 Post Request for Bids Open - National eld for expla 0.00 2024-01-05 2024-01-11 2024-01-10 2024-02-09 2024-02-24 2024-03-30 infrastructure and service de nvelope mentation 3 njang-Pokharelfat-Kumalgau nation) livery n-Samata School Kalesti Roa d)- Byas NP-DUDBC-400274-CW-RFB Urban Development Grants ( Other (with fi Single Stage - One E Pending Imp 2025-06-2 / Dumre Khola-Tallo Gufa Cha IDA / 67780 UDG) for strategic municipal Post Request for Bids Open - National eld for expla 0.00 2024-01-10 2024-01-15 2024-02-14 2024-02-29 2024-04-04 nvelope lementation 8 ur Road- Tansen infrastructure and service de nation) livery NP-DUDBC-400275-CW-RFB / Upgradation of Gothgaun C Urban Development Grants ( Other (with fi hiuramil Purwanchal Biswabi UDG) for strategic municipal Single Stage - One E Under Imple 2025-06-2 IDA / 67780 Post Request for Bids Open - National eld for expla 0.00 2024-01-04 2024-01-07 2024-01-09 2024-02-08 2024-02-23 2024-03-29 dhya Gothgaun Sadak (5.147 infrastructure and service de nvelope mentation 2 nation) Km) and Maheshwor Subba livery Marg Sadak (5.075 Km)- Sun derharaicha NP-DUDBC-400277-CW-RFB / Upgradation of : Mulpani Sc Urban Development Grants ( Other (with fi hool Hararchaur Kalimati Tita UDG) for strategic municipal Single Stage - One E Under Imple 2025-06-2 IDA / 67780 Post Request for Bids Open - National eld for expla 0.00 2024-01-05 2024-01-11 2024-01-10 2024-02-09 2024-02-24 2024-03-30 ura 8+560, Majhibasti Nirahe infrastructure and service de nvelope mentation 3 nation) ghat Road (1+620), : Odarch livery aur Dhodeni Phosre (2+140)- Baglung NP-DUDBC-401454-CW-RFB Urban Development Grants ( Other (with fi Single Stage - One E Under Imple 2025-06-3 / Package 1: Different interco IDA / 67780 UDG) for strategic municipal Post Request for Bids Open - National eld for expla 0.00 2024-01-12 2024-01-17 2024-01-17 2024-02-16 2024-03-02 2024-04-06 nvelope mentation 0 nnected road within Triyuga infrastructure and service de nation) Municipality livery NP-DUDBC-401455-CW-RFB Urban Development Grants ( / Package 2: Sagarmatha Agr Other (with fi UDG) for strategic municipal Single Stage - One E Under Imple 2025-06-3 iculture bazar west to south IDA / 67780 Post Request for Bids Open - National eld for expla 0.00 2024-01-12 2024-01-17 2024-01-17 2024-02-16 2024-03-02 2024-04-06 infrastructure and service de nvelope mentation 0 Madan Bhandari Hall to Janpr nation) livery emi tole Bisanpur ward 12 Ro ad- Triyuga NP-DUDBC-403911-CW-RFB / IMPROVEMENT OF DUMARE Urban Development Grants ( Other (with fi KHOLA – SUNDADA – TELGAH UDG) for strategic municipal Single Stage - Two E Pending Imp 2025-06-2 IDA / 67780 Post Request for Bids Open - National eld for expla 0.00 2024-01-22 2024-01-24 2024-02-23 2024-03-24 2024-04-28 A – GUFA CHAUR – GAUN DA infrastructure and service de nvelope lementation 7 nation) DA – SALLAGHARI – HULUNG livery DI ROAD, TANSEN PALPA NP-DUDBC-410658-CW-RFB Urban Development Grants ( Other (with fi Single Stage - Two E Pending Imp 2025-07-0 / Upgradation of Different Int IDA / 67780 UDG) for strategic municipal Post Request for Bids Open - National eld for expla 0.00 2024-02-23 2024-02-26 2024-03-27 2024-04-26 2024-05-31 nvelope lementation 1 er-connected Roads within R infrastructure and service de nation) ajbiraj Municipality livery GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NP-DUDBC-255719-GO-RFB / Institutional strengthening o Single Stage - One E Under Imple IT Equipment for Participatin IDA / 67780 f the participating municipali Post Request for Bids Open - National 0.00 2021-10-06 2021-10-11 2021-11-22 2021-12-22 2022-01-26 2022-03-27 nvelope mentation g Municipalities ties NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NP-DUDBC-255678-NC-RFB / Institutional strengthening o Single Stage - One E Under Imple Training on Revised Nepal Na IDA / 67780 f the participating municipali Post Request for Bids Open - National 0.00 2022-01-20 2022-01-20 2022-01-25 2022-02-24 2022-03-26 2022-04-30 2022-07-14 nvelope mentation tional Building Code and othe ties r Byelaws NP-DUDBC-408401-NC-RFB / Institutional strengthening o Training to the participating Single Stage - One E Under Imple IDA / 67780 f the participating municipali Post Request for Bids Open - National 0.00 2024-02-12 2024-02-13 2024-02-17 2024-03-18 2024-03-21 2024-04-11 2024-05-26 municipalities regarding Nep nvelope mentation ties al National Building Code CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NP-DUDBC-167759-CS-QCBS Institutional strengthening o Quality And Cost- / Urban Development Suppor IDA / V0710 f the participating municipali Prior Open - National 0.00 Canceled 2020-08-12 2020-08-23 2020-10-02 2020-11-01 2020-11-18 2020-12-16 2021-01-13 2026-01-12 Based Selection t Team (UDST) for Eastern Cl ties uster NP-DUDBC-167798-CS-QCBS Institutional strengthening o Quality And Cost- / Urban Development Suppor IDA / V0710 f the participating municipali Prior Open - National 0.00 Canceled 2020-08-12 2020-08-23 2020-10-02 2020-11-01 2020-11-18 2020-12-16 2021-01-13 2026-01-12 Based Selection t Team (UDST) for Western Cl ties uster NP-DUDBC-189374-CS-QCBS Institutional strengthening o Quality And Cost- Open - Internationa / Urban Development Suppor IDA / 67780 f the participating municipali Prior 0.00 Canceled 2021-04-07 2021-08-29 2021-04-21 2021-12-16 2021-06-05 2022-04-13 2021-07-20 2022-06-13 2021-08-19 2022-09-02 2021-09-23 2021-10-28 2025-07-15 Based Selection l t Team (UDST) ties NP-DUDBC-167715-CS-QCBS Project management and co Quality And Cost- Open - Internationa / Project Management Suppo IDA / 67780 Prior 3,132,868.67 Signed 2021-02-21 2021-02-14 2021-03-07 2021-04-05 2021-04-21 2021-10-06 2021-06-05 2022-01-24 2021-07-05 2022-06-03 2021-08-09 2022-08-26 2021-09-13 2022-10-04 2025-07-15 ordination Based Selection l rt Team (PMST) NP-DUDBC-215991-CS-QCBS Urban Development Grants ( Quality And Cost- Open - Internationa Under Implement / Design and Supervision Con IDA / 67780 UDG) for strategic municipal Prior 0.00 2021-04-15 2021-05-01 2021-04-29 2021-05-05 2021-06-12 2021-12-09 2021-07-10 2022-03-29 2021-08-09 2022-06-17 2021-09-13 2023-03-29 2021-10-18 2025-07-15 Based Selection l ation sultant (DSC), Pokhara infrastructure and service de livery NP-DUDBC-216356-CS-QCBS Urban Development Grants ( Quality And Cost- / Design and Supervision Con IDA / 67780 UDG) for strategic municipal Post Open - National 0.00 Signed 2021-05-02 2021-06-12 2021-05-16 2021-06-27 2021-06-29 2022-01-26 2021-07-27 2022-03-10 2021-08-26 2022-05-02 2021-09-30 2022-05-30 2021-11-04 2022-06-22 2025-07-15 Based Selection sultant (DSC), Ramgram infrastructure and service de livery NP-DUDBC-216325-CS-QCBS Urban Development Grants ( Quality And Cost- Under Implement / Design and Supervision Con IDA / 67780 UDG) for strategic municipal Post Open - National 0.00 2021-05-02 2021-06-12 2021-05-16 2021-06-27 2021-06-29 2021-07-27 2021-08-26 2021-09-30 2021-11-04 2025-07-15 Based Selection ation sultant (DSC), Sundarharaich infrastructure and service de a livery Page 2 NP-DUDBC-216332-CS-QCBS Urban Development Grants ( Quality And Cost- Open - Internationa Under Implement / Design and Supervision Con IDA / 67780 UDG) for strategic municipal Post 0.00 2021-05-02 2021-06-12 2021-05-16 2021-06-27 2021-06-29 2022-02-14 2021-07-27 2022-03-25 2021-08-26 2022-07-18 2021-09-30 2021-11-04 2025-07-15 Based Selection l ation sultant (DSC), Byas infrastructure and service de livery NP-DUDBC-216341-CS-QCBS Urban Development Grants ( Quality And Cost- Open - Internationa Under Implement / Design and Supervision Con IDA / 67780 UDG) for strategic municipal Post 0.00 2021-05-02 2021-05-17 2021-05-16 2021-05-26 2021-06-29 2021-07-27 2021-08-26 2021-09-30 2021-11-04 2025-07-15 Based Selection l ation sultant (DSC), Mechinagar infrastructure and service de livery NP-DUDBC-216346-CS-QCBS Urban Development Grants ( Quality And Cost- Open - Internationa / Design and Supervision Con IDA / 67780 UDG) for strategic municipal Post 0.00 Signed 2021-05-02 2021-05-17 2021-05-16 2021-06-02 2021-06-29 2022-01-27 2021-07-27 2022-03-10 2021-08-26 2022-06-28 2021-09-30 2022-06-27 2021-11-04 2022-11-28 2025-07-15 Based Selection l sultant (DSC), Itahari infrastructure and service de livery NP-DUDBC-216353-CS-QCBS Urban Development Grants ( Quality And Cost- Under Implement / Design and Supervision Con IDA / 67780 UDG) for strategic municipal Post Open - National 0.00 2021-05-02 2021-05-18 2021-05-16 2021-06-02 2021-06-29 2022-02-21 2021-07-27 2022-02-16 2021-08-26 2022-04-19 2021-09-30 2022-06-15 2021-11-04 2025-07-15 Based Selection ation sultant (DSC), Tansen infrastructure and service de livery NP-DUDBC-215996-CS-QCBS Urban Development Grants ( Quality And Cost- / Design and Supervision Con IDA / 67780 UDG) for strategic municipal Post Open - National 0.00 Signed 2021-04-15 2021-06-08 2021-04-29 2021-06-27 2021-06-12 2021-12-27 2021-07-10 2022-02-10 2021-08-09 2022-03-22 2021-09-13 2022-07-01 2021-10-18 2022-09-08 2025-07-15 Based Selection sultant (DSC), Birtamod infrastructure and service de livery NP-DUDBC-216001-CS-QCBS Urban Development Grants ( Quality And Cost- Open - Internationa / Design and Supervision Con IDA / 67780 UDG) for strategic municipal Post 0.00 Signed 2021-04-15 2021-06-12 2021-04-29 2021-06-27 2021-06-12 2022-01-31 2021-07-10 2022-05-01 2021-08-09 2022-05-05 2021-09-13 2022-06-10 2021-10-18 2022-09-09 2025-07-15 Based Selection l sultant (DSC), Tilottama infrastructure and service de livery NP-DUDBC-216002-CS-QCBS Urban Development Grants ( Quality And Cost- Under Implement / Design and Supervision Con IDA / 67780 UDG) for strategic municipal Post Open - National 0.00 2021-04-15 2021-06-12 2021-04-29 2021-06-27 2021-06-12 2021-07-10 2021-08-09 2021-09-13 2021-10-18 2025-07-15 Based Selection ation sultant (DSC), Urlabari infrastructure and service de livery NP-DUDBC-216352-CS-QCBS Urban Development Grants ( Quality And Cost- Under Implement / Design and Supervision Con IDA / 67780 UDG) for strategic municipal Post Open - National 0.00 2021-05-02 2021-05-17 2021-05-16 2021-06-02 2021-06-29 2022-05-28 2021-07-27 2021-08-26 2021-09-30 2021-11-04 2025-07-15 Based Selection ation sultant (DSC), Baglung infrastructure and service de livery NP-DUDBC-216339-CS-QCBS Urban Development Grants ( Quality And Cost- Under Implement / Design and Supervision Con IDA / 67780 UDG) for strategic municipal Post Open - National 0.00 2021-05-02 2021-05-18 2021-05-16 2021-06-02 2021-06-29 2021-07-27 2021-08-26 2021-09-30 2021-11-04 2025-07-15 Based Selection ation sultant (DSC), Dhankuta infrastructure and service de livery NP-DUDBC-216334-CS-QCBS Urban Development Grants ( Quality And Cost- Under Implement / Design and Supervision Con IDA / 67780 UDG) for strategic municipal Post Open - National 0.00 2021-05-02 2021-06-12 2021-05-16 2021-06-27 2021-06-29 2021-07-27 2021-08-26 2021-09-30 2021-11-04 2025-07-15 Based Selection ation sultant (DSC), Putalibazar infrastructure and service de livery NP-DUDBC-215999-CS-QCBS Urban Development Grants ( Quality And Cost- Under Implement / Design and Supervision Con IDA / 67780 UDG) for strategic municipal Post Open - National 0.00 2021-04-15 2021-06-08 2021-04-29 2021-06-27 2021-06-12 2022-01-17 2021-07-10 2022-02-21 2021-08-09 2022-05-23 2021-09-13 2023-06-27 2021-10-18 2025-07-15 Based Selection ation sultant (DSC), Damak infrastructure and service de livery NP-DUDBC-216333-CS-QCBS Urban Development Grants ( Quality And Cost- Under Implement / Design and Supervision Con IDA / 67780 UDG) for strategic municipal Post Open - National 0.00 2021-05-02 2021-06-12 2021-05-16 2021-06-27 2021-06-29 2021-07-27 2021-08-26 2021-09-30 2021-11-04 2025-07-15 Based Selection ation sultant (DSC), Shuklagandaki infrastructure and service de livery NP-DUDBC-216329-CS-QCBS Urban Development Grants ( Quality And Cost- Open - Internationa Under Implement / Design and Supervision Con IDA / 67780 UDG) for strategic municipal Post 0.00 2021-05-02 2021-06-12 2021-05-16 2021-06-27 2021-06-29 2021-12-26 2021-07-27 2022-02-10 2021-08-26 2022-04-22 2021-09-30 2022-05-18 2021-11-04 2025-07-15 Based Selection l ation sultant (DSC), Triyuga infrastructure and service de livery NP-DUDBC-216350-CS-QCBS Urban Development Grants ( Quality And Cost- / Design and Supervision Con IDA / 67780 UDG) for strategic municipal Post Open - National 0.00 Signed 2021-05-02 2021-06-12 2021-05-16 2021-06-27 2021-06-29 2022-01-21 2021-07-27 2022-02-17 2021-08-26 2022-06-04 2021-09-30 2023-02-14 2021-11-04 2023-05-05 2025-07-15 Based Selection sultant (DSC), Rajbiraj infrastructure and service de livery NP-DUDBC-216393-CS-QCBS Institutional strengthening o / Integrated Revenue and Ac Quality And Cost- IDA / 67780 f the participating municipali Post Open - National 0.00 Canceled 2022-03-16 2022-03-30 2022-05-13 2022-06-10 2022-07-10 2022-08-14 2022-09-18 2022-11-17 counting System Customizati Based Selection ties on and Implementation NP-DUDBC-359397-CS-QCBS Institutional strengthening o / Preparation of Institutional Quality And Cost- Under Implement IDA / 67780 f the participating municipali Post Open - National 0.00 2023-05-30 2023-07-28 2023-06-20 2023-08-03 2023-08-31 2023-09-30 2023-11-04 2023-12-09 2024-06-06 Strengthening Plan (ISP) of 2 Based Selection ation ties 1 participating municipalities NP-DUDBC-359395-CS-QCBS Institutional strengthening o Quality And Cost- Open - Internationa Under Implement / Urban Development Suppor IDA / 67780 f the participating municipali Prior 0.00 2023-05-15 2023-08-18 2023-06-05 2023-07-19 2023-08-30 2023-09-29 2023-11-03 2023-12-08 2025-06-10 Based Selection l ation t Team (UDST) ties NP-DUDBC-359834-CS-QCBS Project management and co Quality And Cost- Under Implement / Hiring third party monitorin IDA / 67780 Post Open - National 0.00 2023-07-15 2023-09-01 2023-08-20 2023-09-18 2023-10-16 2023-10-31 2023-12-05 2024-01-09 2024-04-08 ordination Based Selection ation g service for midterm review of the project INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NP-DUDBC-167843-CS-INDV Project management and co Individual Consult IDA / V0710 Post Direct 7,509.14 Completed 2020-06-29 2020-06-22 2020-06-29 2020-07-01 2020-07-01 2020-07-02 2020-07-04 2020-07-08 2020-12-31 2021-01-05 / Financial Management Spec ordination ant Selection ialist NP-DUDBC-167845-CS-INDV Project management and co Individual Consult IDA / V0710 Post Direct 10,449.86 Completed 2020-06-29 2020-07-01 2020-06-29 2020-07-07 2020-07-01 2020-07-08 2020-07-04 2020-07-14 2020-12-31 2021-01-05 / Senior Urban Planner ordination ant Selection NP-DUDBC-167842-CS-INDV Project management and co Individual Consult IDA / V0710 Post Direct 6,116.21 Completed 2020-06-29 2020-06-02 2020-06-29 2020-06-11 2020-07-01 2020-06-12 2020-07-04 2020-06-18 2020-12-31 2021-01-05 / Procurement Specialist ordination ant Selection NP-DUDBC-216004-CS-INDV Project management and co Individual Consult IDA / 67780 Prior Open 36,642.41 Signed 2021-02-01 2021-02-14 2021-02-28 2021-03-25 2021-03-03 2021-03-29 2021-03-11 2021-04-22 2025-07-15 / Procurement Specialist ordination ant Selection NP-DUDBC-216005-CS-INDV Project management and co Individual Consult IDA / 67780 Post Open 41,412.12 Signed 2021-02-01 2021-02-10 2021-02-28 2021-03-22 2021-03-03 2021-03-30 2021-03-11 2021-04-22 2025-07-15 / Financial Management Spec ordination ant Selection ialist NP-DUDBC-216006-CS-INDV Project management and co Individual Consult IDA / 67780 Post Open 41,988.29 Signed 2021-02-01 2021-02-10 2021-02-28 2021-03-22 2021-03-03 2021-03-25 2021-03-11 2021-04-22 2025-07-15 / Project Advisor (Senior Urba ordination ant Selection n Planner) NP-DUDBC-216401-CS-INDV Project management and co Individual Consult IDA / 67780 Post Direct 9,016.87 Completed 2021-02-05 2021-02-21 2021-02-15 2021-02-26 2021-02-20 2021-02-28 2021-03-02 2021-03-17 2021-07-15 2021-07-29 / Monitoring and Evaluation E ordination ant Selection ngineer NP-DUDBC-216403-CS-INDV Project management and co Individual Consult IDA / 67780 Post Direct 9,016.87 Completed 2021-02-05 2021-02-21 2021-02-15 2021-02-26 2021-02-20 2021-02-28 2021-03-02 2021-03-17 2021-07-15 2021-07-29 / Monitoring and Evaluation E ordination ant Selection ngineer NP-DUDBC-216404-CS-INDV Project management and co Individual Consult IDA / 67780 Post Direct 9,016.87 Completed 2021-02-05 2021-02-21 2021-02-15 2021-03-02 2021-02-20 2021-03-03 2021-03-02 2021-03-19 2021-07-15 2021-07-29 / Monitoring and Evaluation E ordination ant Selection ngineer Page 3 NP-DUDBC-216405-CS-INDV Project management and co Individual Consult IDA / 67780 Post Direct 9,016.87 Completed 2021-02-05 2021-02-21 2021-02-15 2021-02-26 2021-02-20 2021-02-28 2021-03-02 2021-03-17 2021-07-15 2021-07-29 / Monitoring and Evaluation E ordination ant Selection ngineer NP-DUDBC-216410-CS-INDV Project management and co Individual Consult IDA / 67780 Post Direct 0.00 Canceled 2021-02-05 2021-02-15 2021-02-20 2021-03-02 2021-07-15 / Social Safeguard Specialist ordination ant Selection NP-DUDBC-216411-CS-INDV Project management and co Individual Consult IDA / 67780 Post Direct 0.00 Canceled 2021-02-05 2021-02-15 2021-02-20 2021-03-02 2021-07-15 / Environmental Safeguard S ordination ant Selection pecialist NP-DUDBC-216412-CS-INDV Project management and co Individual Consult Under Implement IDA / 67780 Post Direct 0.00 2021-02-05 2021-08-26 2021-02-15 2021-02-20 2021-03-02 2021-07-15 / Road Safety Specialist ordination ant Selection ation NP-DUDBC-225894-CS-INDV Project management and co Individual Consult IDA / 67780 Post Direct 2,634.68 Completed 2021-03-25 2021-03-25 2021-03-29 2021-03-31 2021-03-31 2021-04-04 2021-04-05 2021-04-18 2021-07-15 2021-07-29 / Assistant Financial Officer ordination ant Selection NP-DUDBC-241984-CS-INDV Project management and co Individual Consult IDA / 67780 Post Limited 23,202.39 Signed 2021-07-05 2021-07-12 2021-07-10 2021-07-29 2021-07-15 2021-07-30 2021-08-01 2021-08-15 2022-07-15 / Monitoring and Evaluation E ordination ant Selection ngineer NP-DUDBC-241995-CS-INDV Project management and co Individual Consult IDA / 67780 Post Limited 23,202.39 Signed 2021-07-05 2021-07-12 2021-07-10 2021-07-29 2021-07-15 2021-07-30 2021-08-01 2021-08-18 2022-07-15 2022-08-05 / Monitoring and Evaluation E ordination ant Selection ngineer NP-DUDBC-242001-CS-INDV Project management and co Individual Consult Under Implement IDA / 67780 Post Limited 0.00 2021-07-05 2021-07-12 2021-07-10 2021-07-15 2021-08-01 2022-07-15 / Monitoring and Evaluation E ordination ant Selection ation ngineer NP-DUDBC-242008-CS-INDV Project management and co Individual Consult IDA / 67780 Post Limited 23,202.39 Signed 2021-07-05 2021-07-12 2021-07-10 2021-07-29 2021-07-15 2021-07-30 2021-08-01 2021-08-15 2022-07-15 / Monitoring and Evaluation E ordination ant Selection ngineer NP-DUDBC-242016-CS-INDV Project management and co Individual Consult IDA / 67780 Post Limited 6,857.92 Signed 2021-07-05 2021-07-22 2021-07-10 2021-07-27 2021-07-15 2021-07-28 2021-08-01 2021-08-12 2022-04-16 / Assistant Financial Officer ordination ant Selection NP-DUDBC-242025-CS-INDV Project management and co Individual Consult Under Implement IDA / 67780 Post Limited 0.00 2021-09-15 2021-09-26 2021-09-20 2021-09-25 2021-10-12 2022-06-11 / Environmental Safeguard S ordination ant Selection ation pecialist NP-DUDBC-242026-CS-INDV Project management and co Individual Consult Under Implement IDA / 67780 Post Limited 0.00 2021-09-15 2021-09-26 2021-09-20 2021-09-25 2021-10-12 2022-06-11 / Social Safeguard Specialist ordination ant Selection ation NP-DUDBC-306440-CS-INDV Project management and co Individual Consult Under Implement IDA / 67780 Post Limited 0.00 2022-08-05 2022-08-16 2022-08-10 2022-08-17 2022-08-29 2023-07-16 / Monitoring and Evaluation E ordination ant Selection ation ngineer NP-DUDBC-306447-CS-INDV Project management and co Individual Consult Under Implement IDA / 67780 Post Limited 0.00 2022-08-05 2022-08-16 2022-08-10 2022-08-17 2022-08-29 2023-07-16 / Monitoring and Evaluation E ordination ant Selection ation ngineer NP-DUDBC-306449-CS-INDV Project management and co Individual Consult Under Implement IDA / 67780 Post Limited 0.00 2022-08-05 2022-08-16 2022-08-10 2022-08-17 2022-08-29 2023-07-16 / Monitoring and Evaluation E ordination ant Selection ation ngineer NP-DUDBC-306454-CS-INDV Project management and co Individual Consult Under Implement IDA / 67780 Post Limited 0.00 2022-08-05 2022-08-16 2022-08-10 2022-08-17 2022-08-29 2023-07-16 / Monitoring and Evaluation E ordination ant Selection ation ngineer NP-DUDBC-306456-CS-INDV Project management and co Individual Consult Under Implement IDA / 67780 Post Limited 0.00 2022-08-05 2022-07-31 2022-08-10 2022-08-17 2022-08-29 2023-07-16 / Assistant Financial Officer ordination ant Selection ation NP-DUDBC-306458-CS-INDV Project management and co Individual Consult Under Implement IDA / 67780 Post Limited 0.00 2022-08-05 2022-09-11 2022-08-10 2022-08-17 2022-08-29 2023-07-16 / Environmental Safeguard S ordination ant Selection ation pecialist NP-DUDBC-306469-CS-INDV Project management and co Individual Consult Under Implement IDA / 67780 Post Limited 0.00 2022-08-05 2022-09-11 2022-08-10 2022-09-15 2022-08-17 2022-10-12 2022-08-29 2023-07-16 / Social Safeguard Specialist ordination ant Selection ation NP-DUDBC-395283-CS-INDV Project management and co Individual Consult Under Implement IDA / 67780 Post Limited 0.00 2023-11-30 2023-12-02 2023-12-05 2023-12-26 2024-01-30 2025-06-13 / Hiring of Project Manageme ordination ant Selection ation nt Expert NP-DUDBC-400625-CS-INDV Institutional strengthening o Individual Consult Under Implement / Hiring of Team Leader for c IDA / 67780 f the participating municipali Post Open - National 0.00 2024-01-08 2024-01-21 2024-02-11 2024-03-03 2024-04-07 2025-04-02 ant Selection ation omponent 2 ties NP-DUDBC-400628-CS-INDV Institutional strengthening o Individual Consult Under Implement / Hiring of Institutional and G IDA / 67780 f the participating municipali Post Open - National 0.00 2024-01-08 2024-01-21 2024-02-11 2024-03-03 2024-04-07 2025-04-02 ant Selection ation overnance Expert ties NP-DUDBC-400629-CS-INDV Institutional strengthening o Individual Consult Under Implement IDA / 67780 Post Open - National 0.00 2024-01-08 2024-01-21 2024-02-11 2024-03-03 2024-04-07 2025-04-02 / Hiring of Urban Planning Ex f the participating municipali ant Selection ation pert ties NP-DUDBC-400631-CS-INDV Institutional strengthening o Individual Consult Under Implement IDA / 67780 Post Open - National 0.00 2024-01-08 2024-01-21 2024-02-11 2024-03-03 2024-04-07 2025-04-02 / Hiring of Social Developmen f the participating municipali ant Selection ation t Expert ties NP-DUDBC-400632-CS-INDV Institutional strengthening o Individual Consult Under Implement IDA / 67780 Post Open - National 0.00 2024-01-08 2024-01-21 2024-02-11 2024-03-03 2024-04-07 2025-04-02 / Hiring of Gesi Expert f the participating municipali ant Selection ation ties NP-DUDBC-400633-CS-INDV Institutional strengthening o Individual Consult Under Implement / Hiring of Municipal Finance IDA / 67780 f the participating municipali Post Open - National 0.00 2024-01-08 2024-01-21 2024-02-11 2024-03-03 2024-04-07 2025-04-02 ant Selection ation and Revenue Expert ties NP-DUDBC-400635-CS-INDV Institutional strengthening o Individual Consult Under Implement / Hiring of Municipal Infrastru IDA / 67780 f the participating municipali Post Open - National 0.00 2024-01-08 2024-01-21 2024-02-11 2024-03-03 2024-04-07 2025-04-02 ant Selection ation cture and Asset Management ties Expert NP-DUDBC-400636-CS-INDV Institutional strengthening o Individual Consult Under Implement IDA / 67780 Post Open - National 0.00 2024-01-08 2024-01-21 2024-02-11 2024-03-03 2024-04-07 2025-04-02 / Hiring of Environment Exper f the participating municipali ant Selection ation t ties Page 4