PROCUREMENT PLAN (Textual Part) Project information: Country: Bolivia. Project name: INNOVATION FOR RESILIENT FOOD SYSTEMS (ALIANZAS RURALES – PAR III) PROJECT P-number: P175672 Project Implementation agency: EMPODERAR Date of the Procurement Plan: November 21, 2022 Period covered by this Procurement Plan: 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: Not Applicable Leased Not Applicable. Procurement of Second Hand Goods Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable Works: Not Applicable PROCUREMENT Bolivia : Innovation for Resilient Food Systems (Alianzas Rurales - PAR III) Project PLAN General Information Country: Bolivia 2022-11-21 Bank’s Approval Date of the Original Procurement Plan: Revised Plan Date(s): (comma delineated, leave blank2024-02-09 if none) Project ID: P175672 GPN Date: Project Name: Innovation for Resilient Food Systems (Alianzas Rurales - PAR III) Project Loan / Credit No: IBRD / 94370 EMPODERAR Program Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process S Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Comple Description Component Review Type Method Amount (U ount (US$ and Recommendatio Signed Contract o. h cess (Y/N) isk ocument Type tatus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes tion S$) ) n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BO-EMPODERAR-351827-G Solicitud de ofert Open - Internation Single Stage - One O-RFQ / COMPRA DE 29 VEH IBRD / 94370 3. Project Management Posterior 1,185,161.00 0.00 En ejecución 2023-03-24 2023-06-09 2023-03-29 2023-07-07 2023-05-18 2023-06-17 2023-07-22 2023-10-08 as al Envelope ICULOS CAMIONETAS DOBR E CABINA 4x4 BO-EMPODERAR-352389-G Solicitud de cotiz Single Stage - One O-RFQ / COMPRA DE TONER IBRD / 94370 3. Project Management Posterior Open - National 28,871.00 0.00 Finalizado 2023-03-29 2023-05-24 2023-05-02 2023-08-30 aciones Envelope PARA IMPRESORAS Y FOTOC OPIAS DEL PAR III BO-EMPODERAR-352390-G Solicitud de cotiz Single Stage - One O-RFQ / COMPRA DE MATERI IBRD / 94370 3. Project Management Posterior Open - National 14,296.00 0.00 Finalizado 2023-03-29 2023-05-24 2023-05-02 2023-08-30 2023-05-05 aciones Envelope AL DE ESCRITORIO PARA OFI CINAS DEL PAR III BO-EMPODERAR-354355-G Solicitud de cotiz Single Stage - One O-RFQ / COMPRA DE LLANTA IBRD / 94370 3. Project Management Posterior Open - National 21,430.00 0.00 Finalizado 2023-04-05 2023-05-31 2023-05-02 2023-07-31 aciones Envelope S PARA VEHICULOS DEL EMP ODERAR PAR BO-EMPODERAR-360045-G Solicitud de ofert Single Stage - One Ejecución pe O-RFB / ADQUISICION DE EQ IBRD / 94370 3. Project Management Posterior Open - National 223,055.00 0.00 2023-05-03 2023-05-08 2023-06-19 2023-07-19 2023-08-23 2023-11-30 as Envelope ndiente UIPOS DE COMPUTACION Y T ABLETS - PAR III BO-EMPODERAR-360047-G Solicitud de ofert Single Stage - One Ejecución pe O-RFB / ADQUISICION DE IM IBRD / 94370 3. Project Management Posterior Open - National 139,263.00 0.00 2023-05-03 2023-05-08 2023-06-19 2023-07-19 2023-08-23 2023-11-30 as Envelope ndiente PRESORAS, PROYECTORES Y ESCANER - PAR III BO-EMPODERAR-360049-G O-RFQ / COMPRA DE EQUIPO DE SONIDO MOVIL (PARLAN Solicitud de cotiz Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 24,200.00 0.00 Finalizado 2023-05-08 2023-07-03 2023-09-30 TE) Y MICROFONOS PARA DI aciones Envelope FUSION DE LOS COMPONEN TES DEL PAR III, EN FERIAS, TALLERES Y OTROS. BO-EMPODERAR-360050-G Solicitud de cotiz Single Stage - One O-RFQ / COMPRA DE HERRA IBRD / 94370 3. Project Management Posterior Open - National 6,597.00 0.00 Finalizado 2023-05-08 2023-07-03 2023-05-31 2023-07-31 aciones Envelope MIENTAS MENORES - PAR III BO-EMPODERAR-361175-G O-RFB / ADQUISICION DE EQ Solicitud de ofert Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 56,692.00 0.00 Finalizado 2023-05-10 2023-06-23 2023-05-15 2023-06-26 2023-07-24 2023-07-26 2023-07-26 2023-08-30 2023-10-31 UIPO DE FILMACION Y FOTO as Envelope GRAFIA PARA EL PAR III BO-EMPODERAR-363746-G O-RFQ / COMPRA DE PAPEL Solicitud de cotiz Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 7,690.00 0.00 Finalizado 2023-05-30 2023-07-25 2023-06-19 2023-09-30 2023-06-23 PARA LA OFICINA NACIONAL aciones Envelope Y DEPARTAMENTALES - PAR III BO-EMPODERAR-363747-G O-RFQ / COMPRA DE CHAMA Solicitud de cotiz Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 13,047.00 0.00 Finalizado 2023-05-30 2023-07-25 2023-12-13 2023-09-30 RRAS (PRENDAS DE VESTIR) aciones Envelope INSTITUCIONALES PARA EL P AR III BO-EMPODERAR-363750-G O-RFB / ADQUISICION DE FO TOCOPIADORAS PAR ALA UN Solicitud de ofert Single Stage - One Ejecución pe IBRD / 94370 3. Project Management Posterior Open - National 112,513.00 0.00 2023-05-25 2023-05-30 2023-07-11 2023-08-10 2023-09-14 2023-12-22 IDAD DE COORDINACION NA as Envelope ndiente CIONAL Y UNIDADES OPERA TIVAS DEPARTAMENTALES - PAR III BO-EMPODERAR-363744-G O-RFQ / COMPRA DE MATERI Solicitud de cotiz Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 21,074.00 0.00 Finalizado 2023-05-30 2023-07-25 2023-06-28 2023-09-30 2023-06-29 AL DE ESCRITORIO PARA LA aciones Envelope OFICINA NACIONAL Y DEPAR TAMENTALES - PAR III BO-EMPODERAR-363743-G O-RFQ / COMPRA DE TONER Solicitud de cotiz Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 33,325.00 0.00 Finalizado 2023-05-30 2023-07-25 2023-06-29 2023-10-31 2023-06-29 PARA LA OFICINA NACIONAL aciones Envelope Y DEPARTAMENTALES DEL P AR III BO-EMPODERAR-363749-G Solicitud de cotiz Single Stage - One Ejecución pe O-RFQ / COMPRA DE LLANTA IBRD / 94370 3. Project Management Posterior Open - National 21,429.00 0.00 2023-05-30 2023-07-25 2023-09-30 aciones Envelope ndiente S PARA VEHICULOS CAMION ETAS DEL PAR III BO-EMPODERAR-371927-G Solicitud de cotiz Single Stage - One O-RFQ / COMPRA DE MOCHI IBRD / 94370 3. Project Management Posterior Open - National 12,317.00 0.00 Finalizado 2023-07-18 2023-09-12 2023-11-07 2023-11-18 2023-11-21 aciones Envelope LAS DE VIAJE PARA LAPTOP BO-EMPODERAR-377851-G O-RFQ / Software LICENCIAS Solicitud de cotiz Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 8,530.00 0.00 Finalizado 2023-08-23 2023-10-18 2024-04-15 MICROSOFT OFFICE 365 par aciones Envelope a los equipos de computació n del PAR III BO-EMPODERAR-377857-G O-RFQ / ADQUISICION DE CE Solicitud de cotiz Single Stage - One NTRALES TELEFONICAS, TEL IBRD / 94370 3. Project Management Posterior Open - National 42,274.00 0.00 Finalizado 2023-08-23 2023-10-18 2024-04-15 aciones Envelope EFONOS IP, EQUIPAMIENTO NETWORKING PARA EL PAR I II BO-EMPODERAR-377833-G O-RFQ / COMPRA DE TONER Solicitud de cotiz Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 28,716.00 0.00 Finalizado 2023-08-23 2023-10-18 2023-10-12 2023-10-31 PARA IMPRESORAS Y FOTOC aciones Envelope OPIADORAS DEL PAR III BO-EMPODERAR-377858-G O-RFQ / ADQUISICION DE SE Solicitud de ofert Single Stage - One Ejecución pe RVIDORES DE DATOS Y APLI IBRD / 94370 3. Project Management Posterior Open - National 67,055.00 0.00 2023-08-23 2023-08-28 2023-10-09 2023-11-08 2023-12-13 2024-06-10 as Envelope ndiente CACIONES, Y PROTECCION E LECTRICA DE EQUIPOS ELEC TRONICOS PAR III Page 1 BO-EMPODERAR-380590-G O-RFQ / COMPRA DE AIRE A Solicitud de cotiz Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 4,235.00 0.00 Finalizado 2023-09-10 2023-11-05 2023-09-27 2023-11-30 2023-10-16 CONDICIONADO PARA LA UO aciones Envelope D SANTA CRUZ - PAR III BO-EMPODERAR-380591-G Solicitud de cotiz Single Stage - One O-RFQ / ADQUISICION DE 40 IBRD / 94370 3. Project Management Posterior Open - National 3,090.00 0.00 Finalizado 2023-09-10 2023-11-05 2023-09-27 2023-12-30 2023-09-29 aciones Envelope SILLAS PARA LA UOD SANTA CRUZ - PAR III BO-EMPODERAR-380592-G O-RFQ / ADQUISICION DE 12 Solicitud de cotiz Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 997.00 0.00 Finalizado 2023-09-10 2023-11-05 2023-09-27 2023-12-30 2023-09-29 MESAS PLEGABLES PARA LA aciones Envelope UOD SANTA CRUZ - PAR III BO-EMPODERAR-380593-G Solicitud de cotiz Single Stage - One O-RFQ / ADQUISICION DE 12 IBRD / 94370 3. Project Management Posterior Open - National 2,045.00 0.00 Finalizado 2023-09-10 2023-11-05 2023-09-21 2023-12-29 2023-09-25 aciones Envelope CARPAS PARA LA OFICINA N ACIONAL - PAR III BO-EMPODERAR-385259-G O-RFQ / COMPRA DE 5 SILLA Solicitud de cotiz Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 692.00 0.00 Finalizado 2023-10-08 2023-12-03 2024-01-27 S SEMIEJECUTIVAS PARA LA aciones Envelope UFICINA UOR RIBERALTA - P AR III BO-EMPODERAR-385263-G O-RFQ / MOBILIARIO PARA L Solicitud de cotiz Single Stage - One A UOR RIBERALTA (ESCRITO IBRD / 94370 3. Project Management Posterior Open - National 2,872.00 0.00 Finalizado 2023-10-08 2023-12-03 2023-11-01 2024-01-27 2023-12-11 aciones Envelope RIO EJECUTIVO, ESTANTES D E MADERA Y MESA DE REUN IONES) - PAR III BO-EMPODERAR-386908-G O-RFQ / COMPRA DE TONER Solicitud de cotiz Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 28,426.00 0.00 Finalizado 2023-10-16 2023-12-11 2023-11-08 2023-12-24 2023-11-10 A PARA LAS NUEVAS IMPRES aciones Envelope ORAS Y FOTOCOPIADORAS DEL PAR III BO-EMPODERAR-386909-G Solicitud de cotiz Single Stage - One O-RFQ / LLANTAS PARA CAM IBRD / 94370 3. Project Management Posterior Open - National 25,714.00 0.00 Finalizado 2023-10-16 2023-12-11 2023-10-25 2024-02-16 aciones Envelope IONETAS 4X4 FRONTIER DEL PAR III BO-EMPODERAR-388719-G O-RFQ / COMPRA DE MATERI Solicitud de cotiz Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 23,688.00 0.00 Finalizado 2023-10-25 2023-12-20 2023-11-16 2024-03-27 2023-11-21 AL DE ESCRITORIO PARA LA aciones Envelope S OFICINAS DEPARTAMENTA LES Y NACIONAL DEL PAR III BO-EMPODERAR-388721-G O-RFQ / COMPRA DE MOBILI Solicitud de cotiz Single Stage - One ARIO (ESTANTE DE MADERA IBRD / 94370 3. Project Management Posterior Open - National 2,040.00 0.00 Finalizado 2023-10-25 2023-12-20 2024-02-13 aciones Envelope Y ESCRITORIO DE MADERA) PARA LA UOD PANDO - PAR I II BO-EMPODERAR-388724-G Solicitud de cotiz Single Stage - One O-RFQ / COMPRA DE SILLAS IBRD / 94370 3. Project Management Posterior Open - National 753.00 0.00 Finalizado 2023-10-25 2023-12-20 2024-02-13 aciones Envelope EJECUTIVAS PARA LA UOD P ANDO - PAR III BO-EMPODERAR-388725-G O-RFQ / COMPRA DE AIRES Solicitud de cotiz Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 2,642.00 0.00 Finalizado 2023-10-25 2023-12-20 2024-02-13 ACONDICIONADOS, RUOTER aciones Envelope Y ECRAM PARA LA UOD PAN DO - PAR III BO-EMPODERAR-392009-G Solicitud de cotiz Single Stage - One O-RFQ / COMPRA DE SILLAS IBRD / 94370 3. Project Management Posterior Open - National 2,186.00 0.00 Finalizado 2023-11-12 2024-01-07 2023-11-20 2024-03-02 2023-11-28 aciones Envelope DE ESPERA PARA LA OFICIN A NACIONAL - PAR III BO-EMPODERAR-392010-G O-RFQ / COMPRA DE MOBILI Solicitud de cotiz Single Stage - One Ejecución pe IBRD / 94370 3. Project Management Posterior Open - National 2,930.00 0.00 2023-11-12 2024-01-07 2024-03-02 ARIO PARA LA UOD TARIJA ( aciones Envelope ndiente ESCRITORIO EJECUTIVO, EST ANTES) - PAR III BO-EMPODERAR-392468-G O-RFQ / COMPRA DE MOBILI Solicitud de cotiz Single Stage - One Ejecución pe IBRD / 94370 3. Project Management Posterior Open - National 2,544.00 0.00 2023-11-14 2024-01-09 2024-03-04 ARIO (ESTANTES Y MUEBLE aciones Envelope ndiente AUXILIAR) PARA LA UOD CO CHABAMBA - PAR III BO-EMPODERAR-394125-G O-RFQ / COMPRA DE ECRAM Solicitud de cotiz Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 164.00 0.00 Finalizado 2023-11-25 2024-01-20 2023-12-04 2024-03-15 2023-12-12 PARA PRESENTACIONES Y R aciones Envelope EUNIONES DE LA UOD TARIJ A - PAR III BO-EMPODERAR-394127-G Solicitud de cotiz Single Stage - One O-RFQ / COMPRA DE SILLAS IBRD / 94370 3. Project Management Posterior Open - National 2,165.00 0.00 Finalizado 2023-11-25 2024-01-20 2023-12-01 2024-03-15 2023-12-12 aciones Envelope PARA REUNIONES PARA LA UOD TARIJA - PAR III BO-EMPODERAR-394128-G Solicitud de cotiz Single Stage - One O-RFQ / COMPRA DE SILLOS IBRD / 94370 3. Project Management Posterior Open - National 1,670.00 0.00 Finalizado 2023-11-25 2024-01-20 2023-12-01 2024-03-15 2023-12-12 aciones Envelope EJECUTIVOS PARA LA UOD T ARIJA - PAR III BO-EMPODERAR-394129-G O-RFQ / COMPRA DE 10 MES Solicitud de cotiz Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 880.00 0.00 Finalizado 2023-11-25 2024-01-20 2024-03-15 AS PLEGABLES PARA REUNI aciones Envelope ONES DE LA UOD TARIJA - P AR III BO-EMPODERAR-394131-G O-RFQ / COMPRA DE 10 MES Solicitud de cotiz Single Stage - One Ejecución pe IBRD / 94370 3. Project Management Posterior Open - National 835.00 0.00 2023-11-25 2024-01-20 2024-03-15 AS PLEGABLES PARA REUNI aciones Envelope ndiente ONES DE LA UOD COCHABA MBA - PAR III BO-EMPODERAR-394132-G O-RFQ / COMPRA DE TONER Solicitud de cotiz Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 32,070.00 0.00 Finalizado 2023-11-25 2024-01-20 2023-12-01 2024-02-02 2023-12-05 PARA IMPRESORAS Y FOTOC aciones Envelope OPIADORAS DEL PAR III BO-EMPODERAR-394144-G O-RFQ / COMPRA DE 25 SILL Solicitud de cotiz Single Stage - One Ejecución pe IBRD / 94370 3. Project Management Posterior Open - National 1,804.00 0.00 2023-11-25 2024-01-20 2024-03-15 AS PARA REUNIONES DE LA aciones Envelope ndiente UOD COCHABAMBA - PAR III BO-EMPODERAR-394149-G O-RFQ / ADQUISICION DE 24 Solicitud de cotiz Single Stage - One Ejecución pe IBRD / 94370 3. Project Management Posterior Open - National 48,980.00 0.00 2023-11-25 2024-01-20 2024-07-18 EQUIPOS DE COMPUTACION aciones Envelope ndiente (LAPTOP) PARA EL PAR III BO-EMPODERAR-396400-G O-RFQ / COMPRA DE SILLON Solicitud de cotiz Single Stage - One ES EJECUTIVOS Y SEMIEJECU IBRD / 94370 3. Project Management Posterior Open - National 4,112.00 0.00 Finalizado 2023-12-09 2024-02-03 2024-03-29 aciones Envelope TIVOS PARA EL PERSONAL D E LA UOD SANTA CRUZ - PA R III BO-EMPODERAR-396405-G O-RFQ / COMPRA AIRES ACO Solicitud de cotiz Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 3,041.00 0.00 Finalizado 2023-12-09 2024-02-03 2024-02-28 NDICIONADOS PARA LA UOD aciones Envelope SANTA CRUZ - PAR III BO-EMPODERAR-396407-G O-RFQ / COMPRA DE MOBILI Solicitud de cotiz Single Stage - One Ejecución pe IBRD / 94370 3. Project Management Posterior Open - National 6,179.00 0.00 2023-12-09 2024-02-03 2024-03-29 ARIO (ESCRITORIOS, ESTAN aciones Envelope ndiente TES Y ARCHIVEROS) PARA L A UOD SANTA CRUZ- PAR III Page 2 BO-EMPODERAR-396409-G O-RFQ / COMPRA DE AIRES Solicitud de cotiz Single Stage - One Ejecución pe IBRD / 94370 3. Project Management Posterior Open - National 1,915.00 0.00 2023-12-09 2024-02-03 2024-02-28 ACONDICIONADOS PARA LA aciones Envelope ndiente UOR RIBERALTA - PAR III BO-EMPODERAR-396412-G Solicitud de cotiz Single Stage - One O-RFQ / COMPRA SE SILLON IBRD / 94370 3. Project Management Posterior Open - National 1,312.00 0.00 Finalizado 2023-12-09 2024-02-03 2024-03-29 aciones Envelope ES SEMI EJECUTIVOS PARA L A UOD BENI - PAR III BO-EMPODERAR-396414-G Solicitud de cotiz Single Stage - One O-RFQ / COMPRA DE ECRAM IBRD / 94370 3. Project Management Posterior Open - National 166.00 0.00 Finalizado 2023-12-09 2024-02-03 2024-03-29 aciones Envelope PARA LA UOD BENI - PAR III BO-EMPODERAR-396415-G Solicitud de cotiz Single Stage - One O-RFQ / COMPRA DE MATERI IBRD / 94370 3. Project Management Posterior Open - National 22,827.00 0.00 Finalizado 2023-12-09 2024-02-03 2024-05-11 aciones Envelope AL DE ESCRITORIO Y TONER PARA EL PAR III BO-EMPODERAR-401690-G Solicitud de cotiz Single Stage - One Ejecución pe O-RFQ / COMPRA DE TONER IBRD / 94370 3. Project Management Posterior Open - National 21,866.00 0.00 2024-01-13 2024-03-09 2024-03-22 aciones Envelope ndiente A PARA IMPRESORAS Y FOT OCOPIADORAS BO-EMPODERAR-401692-G Solicitud de cotiz Single Stage - One Ejecución pe O-RFQ / COMPRA DE MATERI IBRD / 94370 3. Project Management Posterior Open - National 14,577.00 0.00 2024-01-13 2024-03-09 2024-05-15 aciones Envelope ndiente AL DE ESCRITORIO PARA EL PAR III BO-EMPODERAR-403599-G O-RFQ / COMPRA DE LICENCI Solicitud de cotiz Single Stage - One Ejecución pe IBRD / 94370 3. Project Management Posterior Open - National 24,952.00 0.00 2024-01-22 2024-03-18 2024-09-14 AS OFFICE 365 ESTANDAR P aciones Envelope ndiente ARA EQUIPOS DE COMPUTA CION - PAR III BO-EMPODERAR-406714-G O-RFQ / COMPRA DE DOS AI Solicitud de cotiz Single Stage - One Ejecución pe IBRD / 94370 3. Project Management Posterior Open - National 1,137.00 0.00 2024-02-05 2024-04-01 2024-05-26 RES ACONDICIONADOS PAR aciones Envelope ndiente A LA UOR RURRENABAQUE - PAR III BO-EMPODERAR-406717-G Solicitud de cotiz Single Stage - One Ejecución pe O-RFQ / COMPRA DE LLANTA IBRD / 94370 3. Project Management Posterior Open - National 29,154.00 0.00 2024-02-05 2024-04-01 2024-06-01 aciones Envelope ndiente S PARA VEHICULOS DEL EMP ODERAR PAR III BO-EMPODERAR-406804-G O-RFQ / COMPRA DE MOBILI Solicitud de cotiz Single Stage - One Ejecución pe IBRD / 94370 3. Project Management Posterior Open - National 2,580.00 0.00 2024-02-05 2024-04-01 2024-05-26 ARIO (SILLONES SEMIEJECUT aciones Envelope ndiente IVOS Y ESCRITORIOS) PARA LA UOR CAMARGO - PAR III BO-EMPODERAR-406808-G O-RFQ / COMPRA DE MESA P Solicitud de cotiz Single Stage - One Ejecución pe IBRD / 94370 3. Project Management Posterior Open - National 969.00 0.00 2024-02-05 2024-04-01 2024-05-26 LEGABLE Y SILLAS DE PLAST aciones Envelope ndiente ICO PARA LA UOD PANDO - P AR III NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BO-EMPODERAR-351830-N C-RFQ / SERVICIO DE LIMPIE Solicitud de cotiz Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 10,760.00 0.00 Firmado 2023-03-27 2023-05-22 2023-04-03 2023-12-31 ZA DE OFICINAS DE LA UNID aciones Envelope AD DE COORDINACION NACI ONAL BO-EMPODERAR-351831-N C-RFQ / SERVICIO DE AGENC Solicitud de cotiz Single Stage - One IA DE VIAJES PARA PASAJES IBRD / 94370 3. Project Management Posterior Open - National 17,492.00 0.00 Firmado 2023-03-27 2023-05-22 2023-04-03 2023-12-31 aciones Envelope AEREOS NACIONALES E INTE RNACIONALES DEL PERSON AL DEL PAR III BO-EMPODERAR-359799-N C-RFQ / IMPRESION DE CART ILLAS DE DIFUSION DE REQ 1. Capacity Building and Ins Solicitud de cotiz Single Stage - One IBRD / 94370 Posterior Open - National 50,000.00 0.00 Finalizado 2023-05-07 2023-07-02 2023-06-13 2023-08-31 2023-07-24 UISITOS Y BENEFICIOS DEL P titutional Strengthening aciones Envelope AR III, CUATRIPTICOS DE IN FORMACION DEL COMPONE NTE 2 (Y SUB COMPONENTE S) BO-EMPODERAR-363936-N C-RFQ / FABRICACION DE GL Solicitud de cotiz Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 49,562.00 0.00 Finalizado 2023-05-31 2023-07-26 2023-06-20 2023-08-31 2023-07-19 OBOS INFLABLES Y CARPA D aciones Envelope E LONA (PARA EVENTOS DE DIFUSION DEL PAR III) BO-EMPODERAR-363938-N C-RFQ / IMPRESION DE MATE Solicitud de cotiz Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 46,584.00 0.00 Finalizado 2023-05-31 2023-07-26 2023-06-19 2023-08-31 2023-07-19 RIAL DE DIFUSION BANNERS aciones Envelope Y ROLLER PARA EL PAR III BO-EMPODERAR-365736-N C-RFQ / FABRICACION DE LE Solicitud de cotiz Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 41,095.00 0.00 Finalizado 2023-06-11 2023-08-06 2023-06-22 2023-09-11 2023-07-28 TREROS DE DIFUSION DE RE aciones Envelope SULTADOS DEL PAR II BO-EMPODERAR-367211-N C-RFQ / IMPRESION DE GUIA S PARA ELABORACION DE PL Solicitud de cotiz Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 48,854.00 0.00 Finalizado 2023-06-19 2023-08-14 2023-07-04 2023-08-31 2023-08-21 ANES DE ALIANZA, PPC, PRO aciones Envelope YECTOS DE INFRAESTRUCTU RA PRODUCTIVA Y GUIA DEL MEGAS - PAR III BO-EMPODERAR-369484-N C-RFQ / IMPRESION DE MATE RIAL RECREATIVO AFICHES Solicitud de cotiz Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 48,251.00 0.00 Finalizado 2023-07-02 2023-08-27 2023-08-09 2023-10-02 2023-08-31 CALENDARIO, AGENDAS, CA aciones Envelope LENDARIO DE ESCRITORIO ( 2023-2024) Y CUADERNOS DE CAMPO DEL PAR III BO-EMPODERAR-375095-N C-RFQ / SERVICIO DE COLOC Solicitud de cotiz Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 17,318.00 0.00 Finalizado 2023-08-05 2023-09-30 2021-08-30 2023-11-05 ADO DE LETREROS DEL PRO aciones Envelope YECTO DE ALIANZAS RURAL ES (PAR II) BO-EMPODERAR-377869-N C-RFQ / IMPRESION DE DOC Solicitud de ofert Single Stage - One UMENTOS DEL PAR III - MEG IBRD / 94370 3. Project Management Posterior Open - National 62,827.00 0.00 En ejecución 2023-08-23 2023-10-01 2023-08-28 2023-10-09 2023-11-08 2023-12-13 2024-06-10 as Envelope AS, GUIA DE ELABORACION PECAS, GUIA 3 Y FOLDER IN STITUCIONAL BO-EMPODERAR-396642-N C-RFQ / COMPRA DE GLOBO Solicitud de cotiz Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 23,411.00 0.00 En ejecución 2023-12-10 2024-02-04 2024-03-11 S DE INFLABLES Y ROLLER P aciones Envelope UBLICITARIO PARA DIFUSIO N DEL PROYECTO PAR III BO-EMPODERAR-401637-N Solicitud de cotiz Single Stage - One Ejecución pe C-RFQ / SEGURO AUTOMOT IBRD / 94370 3. Project Management Posterior Open - National 39,780.00 0.00 2024-01-13 2024-03-09 2024-09-05 aciones Envelope ndiente OR PARA VEHICULOS DEL E MPODERAR PAR III Page 3 BO-EMPODERAR-401666-N Adquisición direct Ejecución pe C-DIR / POLIZA DE SEGURO IBRD / 94370 3. Project Management Posterior Direct - National 80,640.00 0.00 2024-01-08 2024-01-13 2024-02-17 2024-08-15 a ndiente DE SALUDO PARA EL PERSO NAL DEL PAR III CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Techni Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) t (US$) Notice equest for Proposals as Issued Proposals / Minutes cal Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BO-EMPODERAR-351840-CS -CQS / SERVICIOS DE CONSU Selección basada LTORÍA PARA EL DESARROLL IBRD / 94370 3. Project Management Posterior en calificaciones Open - National 45,000.00 0.00 En ejecución 2023-03-22 2023-03-24 2023-04-12 2023-05-26 2023-06-25 2023-07-30 2023-11-30 O DEL MÓDULO DE SUBPRO de consultores YECTOS DE INFRAESTRUCTU RA PRODUCTIVA COMPLEME NTARIA- PAR III BO-EMPODERAR-351849-CS -CQS / SELECCION DE PERS Selección basada ONAL TECNICO DE LA UNIDA IBRD / 94370 3. Project Management Posterior en calificaciones Open - National 42,274.00 0.00 Cancelado 2023-03-22 2023-03-24 2023-04-12 2023-05-26 2023-06-25 2023-07-30 2024-12-31 D DE COORDINACION NACIO de consultores NAL, UNIDADES OPERATIVA S DEPARTAMENTALES Y REG IONALES DEL PAR III BO-EMPODERAR-368809-CS -QCBS / CONSULTORIA PARA Selección basada LA EJECUCIÓN DEL PROCES IBRD / 94370 3. Project Management Posterior en calidad y cost Open - National 227,405.00 0.00 En ejecución 2023-06-22 2023-06-30 2023-07-13 2023-08-26 2023-09-23 2023-10-23 2023-11-27 2024-01-01 2024-12-31 O DE PLANIFICACION PARTIC o IPATIVA COMUNITARIA (PPC) PAQUETE 1 LA PAZ (ALTIPL ANO YUNGAS) BO-EMPODERAR-369487-CS -QCBS / CONSULTORIA PARA Selección basada LA EJECUCIÓN DEL PROCES IBRD / 94370 3. Project Management Posterior en calidad y cost Open - National 233,090.00 0.00 En ejecución 2023-06-27 2023-06-30 2023-07-18 2023-08-31 2023-09-28 2023-10-28 2023-12-02 2024-01-06 2025-01-05 O DE PLANIFICACION PARTIC o IPATIVA COMUNITARIA (PPC) Paquete 8 LA PAZ (LAGO SU R) BO-EMPODERAR-368805-CS -QCBS / CONSULTORIA PARA Selección basada LA EJECUCIÓN DEL PROCES IBRD / 94370 3. Project Management Posterior en calidad y cost Open - National 299,417.00 0.00 En ejecución 2023-06-22 2023-06-30 2023-07-13 2023-08-26 2023-09-23 2023-10-23 2023-11-27 2024-01-01 2024-12-31 O DE PLANIFICACION PARTIC o IPATIVA COMUNITARIA (PPC) Paquete 5 CHUQUISACA BO-EMPODERAR-368804-CS -QCBS / CONSULTORIA PARA Selección basada LA EJECUCIÓN DEL PROCES IBRD / 94370 3. Project Management Posterior en calidad y cost Open - National 280,466.00 0.00 En ejecución 2023-06-22 2023-06-30 2023-07-13 2023-08-26 2023-09-23 2023-10-23 2023-11-27 2024-01-01 2024-12-31 O DE PLANIFICACION PARTIC o IPATIVA COMUNITARIA (PPC) PAQUETE 6 LA PAZ (LAGO N ORTE) BO-EMPODERAR-368806-CS -QCBS / CONSULTORIA PARA Selección basada LA EJECUCIÓN DEL PROCES IBRD / 94370 3. Project Management Posterior en calidad y cost Open - National 255,831.00 0.00 En ejecución 2023-06-22 2023-06-30 2023-07-13 2023-08-26 2023-09-23 2023-10-23 2023-11-27 2024-01-01 2024-12-31 O DE PLANIFICACION PARTIC o IPATIVA COMUNITARIA (PPC) PAQUETE 4 POTOSI - ESTE BO-EMPODERAR-369485-CS -QCBS / CONSULTORIA PARA Selección basada LA EJECUCIÓN DEL PROCES IBRD / 94370 3. Project Management Posterior en calidad y cost Open - National 244,461.00 0.00 En ejecución 2023-06-22 2023-06-30 2023-07-13 2023-08-26 2023-09-23 2023-10-23 2023-11-27 2024-01-01 2024-12-31 O DE PLANIFICACION PARTIC o IPATIVA COMUNITARIA (PPC) PAQUETE 3 COCHABAMBA BO-EMPODERAR-368808-CS -QCBS / CONSULTORIA PARA Selección basada LA EJECUCIÓN DEL PROCES IBRD / 94370 3. Project Management Posterior en calidad y cost Open - National 329,738.00 0.00 En ejecución 2023-06-22 2023-06-30 2023-07-13 2023-08-26 2023-09-23 2023-10-23 2023-11-27 2024-01-01 2024-12-31 O DE PLANIFICACION PARTIC o IPATIVA COMUNITARIA (PPC) PAQUETE 2 ORURO BO-EMPODERAR-369486-CS -QCBS / CONSULTORIA PARA Selección basada LA EJECUCIÓN DEL PROCES IBRD / 94370 3. Project Management Posterior en calidad y cost Open - National 261,516.00 0.00 En ejecución 2023-06-27 2023-06-30 2023-07-18 2023-08-31 2023-09-28 2023-10-28 2023-12-02 2024-01-06 2025-01-05 O DE PLANIFICACION PARTIC o IPATIVA COMUNITARIA (PPC) Paquete 7 POTOSI - OESTE BO-EMPODERAR-377856-CS -CQS / CONSULTORIA PARA DIAGNOSTICO, COMPLEMEN Selección basada TACION Y AJUSTE DE EDTP(E IBRD / 94370 3. Project Management Posterior en calificaciones Open - National 25,449.00 0.00 En ejecución 2023-08-18 2023-08-23 2023-09-08 2023-10-22 2023-11-21 2023-12-26 2024-04-27 STUDIO DE DISEÑO TECNIC de consultores O DE PREINVERSION) DE SU B PROYECTOS DE INFRAEST RUCTURA COMPLEMENTARI A DEL PAR III BO-EMPODERAR-393031-CS -CQS / EVALUACIÓN DE DES EMPEÑO DEL PERSONAL TÉC Selección basada NICO DEL PROYECTO DE INN IBRD / 94370 3. Project Management Posterior en calificaciones Open - National 29,621.00 0.00 Cancelado 2023-11-13 2023-11-20 2023-12-04 2024-01-17 2024-02-16 2024-03-22 2024-07-23 OVACIÓN PARA SISTEMAS A de consultores LIMENTARIOS RESILIENTES ( ALIANZAS RURALES – PAR III ) Y ESTUDIO DE SATISFACCI ÓN DE BENEFICIARIOS INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Draft Negotiated Con Description Component Review Type Method Process Status Terms of Reference d/Selected Consultan Signed Contract Contract Completion o. h unt (US$) t (US$) tract t Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BO-EMPODERAR-327304-CS -INDV / COORDINADOR GEN IBRD / 94370 3. Project Management Posterior Individual Direct - National 102,516.00 0.00 En ejecución 2022-11-18 2022-11-21 2022-11-28 2022-12-19 2023-01-23 2025-11-30 ERAL DEL EMPODERAR PAR A EL PAR III BO-EMPODERAR-349701-CS -INDV / JEFE DE PLANIFICACI IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,530.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 ÓN Y MONITOREO BO-EMPODERAR-349709-CS -INDV / ESPECIALISTA EN ASI IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 STENCIA TÉCNICA, DESARR OLLO ORGANIZACIONAL Y P PPI BO-EMPODERAR-349711-CS -INDV / ESPECIALISTA EN AD IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 QUISICIONES BO-EMPODERAR-349715-CS -INDV / ESPECIALISTA AMBIE IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 NTAL, SEGURIDAD Y SALUD BO-EMPODERAR-349716-CS -INDV / JEFE ADMINISTRATIV IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,530.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 O FINANCIERO Page 4 BO-EMPODERAR-349718-CS -INDV / ESPECIALISTA EN NE IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 GOCIOS RURALES BO-EMPODERAR-349726-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 -INDV / ANALISTA COMUNIC ACIÓN BO-EMPODERAR-349729-CS -INDV / ANALISTA DE ADQUI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-12-31 SICIONES PARA ALIANZAS BO-EMPODERAR-349730-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-12-31 -INDV / ANALISTA DESEMBO LSOS BO-EMPODERAR-349731-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 -INDV / ANALISTA FINANCIER O BO-EMPODERAR-349732-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 14,907.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 -INDV / ANALISTA PROGRAM ADOR BO-EMPODERAR-349733-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 -INDV / RECEPCIONISTA UCN BO-EMPODERAR-349758-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 9,061.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-12-31 -INDV / CHOFER UCN BO-EMPODERAR-349759-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 9,061.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 -INDV / SECRETARIA EJECUTI VA UCN BO-EMPODERAR-349760-CS -INDV / ASISTENTE DE ADQU IBRD / 94370 3. Project Management Posterior Individual Direct - National 11,400.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 ISICIONES PARA ALIANZAS BO-EMPODERAR-349761-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 12,178.00 0.00 Firmado 2023-03-14 2023-03-23 2023-03-24 2023-03-31 2023-03-27 2023-04-20 2023-04-03 2023-04-24 2023-12-31 -INDV / ANALISTA DE TRANS PARENCIA BO-EMPODERAR-349762-CS -INDV / ESPECIALISTA EN INF IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 RAESTRUCTURA BO-EMPODERAR-349763-CS -INDV / ESPECIALISTA ADMIN IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 ISTRATIVO FINANCIERO BO-EMPODERAR-349764-CS -INDV / OPERADOR DEPART IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 AMENTAL UOD LA PAZ BO-EMPODERAR-349765-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-12-31 O UOD LA PAZ BO-EMPODERAR-349766-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 -INDV / CHOFER UOD LA PAZ BO-EMPODERAR-349767-CS -INDV / OPERADOR DEPART IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 AMENTAL UOD BENI BO-EMPODERAR-349768-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 S PRODUCTIVAS UOD BENI BO-EMPODERAR-349769-CS -INDV / OPERADOR REGIONA IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 L UOR CHACO (CAMIRI) BO-EMPODERAR-349770-CS -INDV / SECRETARIA UOR CH IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 ACO (CAMIRI) BO-EMPODERAR-349771-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 -INDV / CHOFER UOR CHACO (CAMIRI) BO-EMPODERAR-349772-CS -INDV / OPERADOR DEPART IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 AMENTAL UOD PANDO BO-EMPODERAR-349773-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 S PRODUCTIVAS UOD PAND O BO-EMPODERAR-349774-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 -INDV / SECRETARIA UOD PA NDO BO-EMPODERAR-349775-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 O UOR RIBERALTA BO-EMPODERAR-349776-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 -INDV / SECRETARIA UOR RI BERALTA BO-EMPODERAR-349777-CS -INDV / OPERADOR DEPART IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 AMENTAL UOD POTOSI BO-EMPODERAR-349778-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 -INDV / CHOFER UOD POTOS I BO-EMPODERAR-349779-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 O UOD POTOSI BO-EMPODERAR-349780-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 S PRODUCTIVAS UOD POTO SI BO-EMPODERAR-349781-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 S PRODUCTIVAS UOR CAMA RGO BO-EMPODERAR-349782-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,028.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 -INDV / SECRETARIA UOR CA MARGO BO-EMPODERAR-349783-CS -INDV / OPERADOR DEPART IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 AMENTAL UOD COCHABAMB A Page 5 BO-EMPODERAR-349784-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 O UOD COCHABAMBA BO-EMPODERAR-349785-CS -INDV / SECRETARIA UOD C IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 OCHABAMBA BO-EMPODERAR-349786-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 O UOD CHUQUISACA BO-EMPODERAR-349787-CS -INDV / ANALISTA AMBIENTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 L UOD CHUQUISACA BO-EMPODERAR-349788-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 -INDV / CHOFER UOD CHUQ UISACA BO-EMPODERAR-349789-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 -INDV / CHOFER UOD TARIJA BO-EMPODERAR-349790-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 O UOD TARIJA BO-EMPODERAR-349791-CS -INDV / OPERADOR DEPART IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 AMENTAL UOD ORURO BO-EMPODERAR-349792-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 -INDV / SECRETARIA UOD O RURO BO-EMPODERAR-349793-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 O UOD ORURO BO-EMPODERAR-349794-CS -INDV / OPERADOR DEPART IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 AMENTAL UOD SANTA CRUZ BO-EMPODERAR-349796-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 O UOD SANTA CRUZ BO-EMPODERAR-349797-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 S PRODUCTIVAS UOD SANTA CRUZ BO-EMPODERAR-349799-CS -INDV / SECRETARIA UOD SA IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 NTA CRUZ BO-EMPODERAR-349801-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 -INDV / CHOFER UOD SANTA CRUZ BO-EMPODERAR-349803-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 -INDV / CHOFER UOD SANTA CRUZ BO-EMPODERAR-349804-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 S PRODUCTIVAS UOR CHIQU ITANIA BO-EMPODERAR-349805-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-12-31 S PRODUCTIVAS UOD LA PA Z BO-EMPODERAR-350019-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Cancelado 2023-03-15 2023-03-25 2023-03-28 2023-04-03 2023-12-31 S PRODUCTIVAS UOR RURRE NABAQUE BO-EMPODERAR-350025-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-15 2023-03-24 2023-03-25 2023-03-31 2023-03-28 2023-04-03 2023-04-03 2023-04-05 2023-12-31 O UOD PANDO BO-EMPODERAR-350029-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-15 2023-03-24 2023-03-25 2023-03-31 2023-03-28 2023-04-03 2023-04-03 2023-12-31 S COMUNITARIAS UOR CHIQ UITANIA BO-EMPODERAR-350037-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Cancelado 2023-03-15 2023-03-25 2023-03-28 2023-04-03 2023-12-31 S COMUNITARIAS UOD SANT A CRUZ BO-EMPODERAR-350145-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-15 2023-03-24 2023-03-25 2023-03-31 2023-03-28 2023-04-03 2023-04-03 2023-04-05 2023-12-31 O UOR CHACO (CAMIRI) BO-EMPODERAR-350155-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-15 2023-03-24 2023-03-25 2023-03-31 2023-03-28 2023-04-03 2023-04-03 2023-04-05 2023-12-31 S PRODUCTIVAS UOD CHUQ UISACA BO-EMPODERAR-350156-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-15 2023-03-24 2023-03-25 2023-03-31 2023-03-28 2023-04-03 2023-04-03 2023-04-05 2023-12-31 S PRODUCTIVAS UOD COCH ABAMBA BO-EMPODERAR-350157-CS -INDV / OFICIAL DE INFRAES IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-15 2023-03-24 2023-03-25 2023-03-31 2023-03-28 2023-04-03 2023-04-03 2023-04-05 2023-12-31 TRUCTURA UOD COCHABAM BA BO-EMPODERAR-354356-CS -INDV / ANALISTA SOCIAL Y IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,050.00 0.00 Firmado 2023-03-31 2023-05-04 2023-04-10 2023-03-31 2023-04-13 2023-04-03 2023-04-19 2023-04-05 2023-12-31 GENERO UOD SANTA CRUZ - PAR III BO-EMPODERAR-354357-CS -INDV / ANALISTA SOCIAL Y IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,050.00 0.00 Firmado 2023-03-31 2023-05-04 2023-04-10 2023-03-31 2023-04-13 2023-04-03 2023-04-19 2023-12-31 GENERO UOD LA PAZ - PAR I II BO-EMPODERAR-356762-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-03 2023-04-24 2023-03-31 2023-04-27 2023-05-12 2023-05-04 2023-05-15 2023-12-31 O UOD LA PAZ BO-EMPODERAR-356764-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-03 2023-04-24 2023-03-31 2023-04-27 2023-05-10 2023-05-04 2023-05-10 2023-12-31 S PRODUCTIVAS UOD LA PA Z BO-EMPODERAR-356765-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-03 2023-04-24 2023-03-31 2023-04-27 2023-05-10 2023-05-04 2023-05-10 2023-12-31 S PRODUCTIVAS UOR CHAC O (CAMIRI) Page 6 BO-EMPODERAR-356766-CS -INDV / ANALISTA AMBIENTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-04 2023-04-24 2023-03-31 2023-04-27 2023-05-10 2023-05-04 2023-06-12 2023-12-31 L UOR CHACO (CAMIRI) BO-EMPODERAR-356767-CS -INDV / ANALISTA SOCIAL Y IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-04 2023-04-24 2023-03-31 2023-04-27 2023-07-21 2023-05-04 2023-12-31 GENERO UOR CHACO (CAMI RI) BO-EMPODERAR-356768-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-03 2023-04-24 2023-03-31 2023-04-27 2023-05-12 2023-05-04 2023-05-15 2023-12-31 O UOR CHACO (CAMIRI) BO-EMPODERAR-356769-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-04-14 2023-05-02 2023-04-24 2023-03-31 2023-04-27 2023-05-10 2023-05-04 2023-05-10 2023-12-31 -INDV / CHOFER UOD PAND O BO-EMPODERAR-356770-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-04-14 2023-05-02 2023-04-24 2023-03-31 2023-04-27 2023-05-10 2023-05-04 2023-05-10 2023-12-31 -INDV / CHOFER UOR RIBER ALTA BO-EMPODERAR-356771-CS -INDV / OFICIAL DE SUB PRO IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-04 2023-04-24 2023-03-31 2023-04-27 2023-05-11 2023-05-04 2023-05-15 2023-12-31 YECTOS DE INFRAESTRUCTU RA UOD POTOSI BO-EMPODERAR-356773-CS -INDV / ANALISTA AMBIENTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-04 2023-04-24 2023-03-31 2023-04-27 2023-06-07 2023-05-04 2023-06-12 2023-12-31 L UOD POTOSI BO-EMPODERAR-356785-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-04-14 2023-05-02 2023-04-24 2023-03-31 2023-04-27 2023-05-10 2023-05-04 2023-05-10 2023-12-31 -INDV / CHOFER UOD COCH ABAMBA BO-EMPODERAR-356787-CS -INDV / ANALISTA AMBIENTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-04 2023-04-24 2023-03-31 2023-04-27 2023-06-07 2023-05-04 2023-06-12 2023-12-31 L UOD COCHABAMBA BO-EMPODERAR-356788-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-03 2023-04-24 2023-03-31 2023-04-27 2023-05-10 2023-05-04 2023-05-10 2023-12-31 S PRODUCTIVAS UOD CHUQ UISACA BO-EMPODERAR-356789-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-04 2023-04-24 2023-03-31 2023-04-27 2023-05-15 2023-05-04 2023-05-15 2023-12-31 S COMUNITARIAS UOD TARIJ A BO-EMPODERAR-356790-CS -INDV / ANALISTA AMBIENTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-04 2023-04-24 2023-03-31 2023-04-27 2023-06-08 2023-05-04 2023-06-12 2023-12-31 L UOD TARIJA BO-EMPODERAR-356792-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Rescindido 2023-04-14 2023-05-03 2023-04-24 2023-03-31 2023-04-27 2023-05-12 2023-05-04 2023-12-31 A UOD ORURO BO-EMPODERAR-356793-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Rescindido 2023-04-14 2023-05-03 2023-04-24 2023-03-31 2023-04-27 2023-06-22 2023-05-04 2023-06-27 2023-12-31 S PRODUCTIVAS UOD ORUR O BO-EMPODERAR-356794-CS -INDV / OFICIAL DE SUB PRO IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-04 2023-04-24 2023-03-31 2023-04-27 2023-05-12 2023-05-04 2023-05-15 2023-12-31 YECTOS DE INFRAESTRUCTU RA UOD ORURO BO-EMPODERAR-356795-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-04 2023-04-24 2023-03-31 2023-04-27 2023-06-26 2023-05-04 2023-06-29 2023-12-31 S COMUNITARIAS UOD ORU RO BO-EMPODERAR-356797-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-04-14 2023-05-02 2023-04-24 2023-03-31 2023-04-27 2023-05-10 2023-05-04 2023-05-10 2023-12-31 -INDV / CHOFER UOD ORUR O BO-EMPODERAR-356798-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 En ejecución 2023-04-14 2023-05-03 2023-04-24 2023-03-31 2023-04-27 2023-05-04 2023-12-31 O UOD SANTA CRUZ BO-EMPODERAR-356802-CS -INDV / OFICIAL DE SUB PRO IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-04 2023-04-24 2023-03-31 2023-04-27 2023-05-11 2023-05-04 2023-05-15 2023-12-31 YECTOS DE INFRAESTRUCTU RA UOD SANTA CRUZ BO-EMPODERAR-356806-CS -INDV / ANALISTA AMBIENTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-04 2023-04-24 2023-03-31 2023-04-27 2023-06-07 2023-05-04 2023-06-12 2023-12-31 L UOD SANTA CRUZ BO-EMPODERAR-356808-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-04-14 2023-05-02 2023-04-24 2023-03-31 2023-04-27 2023-05-10 2023-05-04 2023-05-10 2023-12-31 -INDV / CHOFER UOR CHIQUI TANIA BO-EMPODERAR-360043-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 15,155.00 0.00 Firmado 2023-05-03 2023-05-04 2023-05-13 2023-03-31 2023-05-16 2023-05-10 2023-05-23 2023-05-10 2023-12-31 S PRODUCTIVAS UOD TARIJA BO-EMPODERAR-360838-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,834.00 0.00 Firmado 2023-05-09 2023-05-12 2023-05-19 2023-03-31 2023-05-22 2023-05-16 2023-05-29 2023-05-17 2023-12-31 -INDV / CHOFER UOD LA PAZ BO-EMPODERAR-360840-CS -INDV / ANALISTA SOCIAL Y IBRD / 94370 3. Project Management Posterior Individual Direct - National 15,155.00 0.00 Firmado 2023-05-09 2023-05-12 2023-05-19 2023-03-31 2023-05-22 2023-07-26 2023-05-29 2023-07-26 2023-12-31 GENERO UOD TARIJA BO-EMPODERAR-360845-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 6,963.00 0.00 Firmado 2023-05-09 2023-05-12 2023-05-19 2023-03-31 2023-05-22 2023-05-16 2023-05-29 2023-05-17 2023-12-31 -INDV / SECRETARIA UOR CH IQUITANIA BO-EMPODERAR-367088-CS -INDV / SECRETARIA PARA L IBRD / 94370 3. Project Management Posterior Individual Open - National 5,223.00 0.00 Firmado 2023-06-13 2023-06-15 2023-08-01 2023-06-30 2023-08-22 2023-06-30 2023-09-26 2023-07-06 2023-12-31 A UOD LA PAZ - PAR III BO-EMPODERAR-367089-CS -INDV / SECRETARIA PARA L IBRD / 94370 3. Project Management Posterior Individual Open - National 5,223.00 0.00 Firmado 2023-06-13 2023-06-15 2023-08-01 2023-10-11 2023-08-22 2023-10-25 2023-09-26 2023-10-30 2023-12-31 A UOD POTOSI - PAR III BO-EMPODERAR-367091-CS -INDV / SECRETARIA PARA U IBRD / 94370 3. Project Management Posterior Individual Open - National 5,223.00 0.00 Firmado 2023-06-13 2023-06-15 2023-08-01 2023-07-10 2023-08-22 2023-08-02 2023-09-26 2023-08-10 2023-12-31 OD CHUQUISACA - PAR III BO-EMPODERAR-367092-CS -INDV / SECRETARIA PARA L IBRD / 94370 3. Project Management Posterior Individual Open - National 5,223.00 0.00 Firmado 2023-06-13 2023-06-15 2023-08-01 2023-09-11 2023-08-22 2023-09-19 2023-09-26 2023-12-31 A UOD TARIJA - PAR III BO-EMPODERAR-367213-CS -CDS / SELECCION DE PERS ONAL TECNICO DE LA UNIDA Selección directa IBRD / 94370 3. Project Management Posterior Direct - National 42,274.00 0.00 En ejecución 2023-06-14 2023-06-15 2023-06-24 2023-08-28 2023-12-31 D DE COORDINACION NACIO de consultores NAL, UNIDADES OPERATIVA S DEPARTAMENTALES Y REG IONALES DEL PAR III BO-EMPODERAR-368606-CS -INDV / ESPECIALISTA EN PP IBRD / 94370 3. Project Management Posterior Individual Open - National 12,470.00 0.00 Firmado 2023-06-22 2023-06-29 2023-08-10 2023-07-30 2023-08-31 2023-09-28 2023-10-05 2024-12-31 C Y PROYECTOS CONSULTO R INDIVIDUAL DE LINEA - PA R III Page 7 BO-EMPODERAR-368729-CS -INDV / ESPECIALISTA EN RIE IBRD / 94370 3. Project Management Posterior Individual Open - National 12,471.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 GO CONSULTOR INDIVIDUAL DE LINEA - PAR III BO-EMPODERAR-368731-CS -INDV / ANALISTA EN PLANIF IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 ICACION Y PROYECTOS CON SULTOR INDIVIDUAL DE LINE A - PAR III BO-EMPODERAR-368732-CS -INDV / PROFESIONAL EN CU IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-30 2023-08-31 2023-09-28 2023-10-05 2023-10-23 2024-12-31 ESTION DE GENERO CONSU LTOR INDIVIDUAL DE LINEA - PAR III BO-EMPODERAR-368733-CS -INDV / OFICIAL DE SUBPRO YECTOS DE INFRAESTRUCTU IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 RA PARA LA UOD LA PAZ C ONSULTOR INDIVIDUAL DE L INEA - PAR II BO-EMPODERAR-368734-CS -INDV / OFICIAL DE SUBPRO YECTOS DE RIEGO PARA LA IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 UOD LA PAZ CONSULTOR IN DIVIDUAL DE LINEA PAR III BO-EMPODERAR-368735-CS -INDV / ANALISTA AMBIENTA IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 En ejecución 2023-06-22 2023-06-23 2023-08-10 2023-08-31 2023-10-05 2024-12-31 L PARA LA UOD LA PAZ, CON SULTOR INDIVIDUAL DE LINE A PAR III BO-EMPODERAR-368737-CS -INDV / ASISTENTE DE SUBP ROYECTOS COMUNITARIOS IBRD / 94370 3. Project Management Posterior Individual Open - National 7,560.00 0.00 Firmado 2023-06-22 2023-06-29 2023-08-10 2023-09-11 2023-08-31 2023-09-20 2023-10-05 2024-12-31 PARA LA UOD LA PAZ, CONS ULTOR INDIVIDUAL DE LINE A PAR III BO-EMPODERAR-368739-CS -INDV / ASISTENTE DE SUBP ROYECTOS PRODUCTIVOS P IBRD / 94370 3. Project Management Posterior Individual Open - National 7,560.00 0.00 Firmado 2023-06-22 2023-06-29 2023-08-10 2023-08-04 2023-08-31 2023-08-22 2023-10-05 2023-08-28 2024-12-31 ARA UOD LA PAZ, CONSULT OR INDIVIDUAL DE LINEA PA R III BO-EMPODERAR-368740-CS -INDV / OFICIAL DE ALIANZA S PRODUCTIVAS PARA LA U IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-19 2024-12-31 OR RURRENABAQUE, CONSU LTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-368743-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 O PARA LA UOR RURRENABA QUE, CONSULTOR INDIVIDU L DE LINEA PAR III BO-EMPODERAR-368744-CS -INDV / SECRETARIA PARA L IBRD / 94370 3. Project Management Posterior Individual Open - National 5,222.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-27 2023-08-31 2023-08-21 2023-10-05 2023-08-23 2024-12-31 A UOR RURRENABAQUE, CO NSULTOR INDIVIDUAL DE LI NEA PAR III BO-EMPODERAR-368745-CS -INDV / CHOFER PARA LA UO IBRD / 94370 3. Project Management Posterior Individual Open - National 5,222.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-27 2023-08-31 2023-08-16 2023-10-05 2023-08-21 2024-12-31 R RURRENABAQUE, CONSUL TOR INDIVIDUAL DE LINEA P AR III BO-EMPODERAR-368747-CS -INDV / OFICIAL DE SUBPRO IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2024-12-31 YECTOS DE INFRAESTRUCTU RA PARA LA UOD BENI, CON SULTOR DE LINEA PAR III BO-EMPODERAR-368749-CS -INDV / ANALISTA AMBIENTA IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-19 2023-08-31 2023-09-20 2023-10-05 2024-12-31 L PARA LA UOD BENI, CONS ULTOR DE LINEA PAR III BO-EMPODERAR-368750-CS -INDV / ANALISTA SOCIAL Y IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-30 2023-08-31 2023-09-28 2023-10-05 2023-10-23 2024-12-31 GENERO PARA LA UOD BENI, CONSULTOR DE LINEA PAR II I BO-EMPODERAR-368751-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 O PARA LA UOD BENI, CONS ULTOR DE LINEA PAR III BO-EMPODERAR-368752-CS -INDV / SECRETARIA PARA L IBRD / 94370 3. Project Management Posterior Individual Open - National 5,222.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-04 2023-08-31 2023-07-24 2023-10-05 2023-08-01 2024-12-31 A UOD BENI, CONSULTOR D E LINEA PAR III BO-EMPODERAR-368754-CS -INDV / CHOFER PARA LA UO IBRD / 94370 3. Project Management Posterior Individual Open - National 5,222.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-04 2023-08-31 2023-07-25 2023-10-05 2023-08-01 2024-12-31 D BENI, CONSULTOR DE LIN EA PAR III BO-EMPODERAR-368756-CS -INDV / ANALISTA SOCIAL Y IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-30 2023-08-31 2023-09-28 2023-10-05 2023-10-23 2024-12-31 GENERO PARA LA UOD CHA CO (CAMIRI), CONSULTOR D E LINEA PAR III BO-EMPODERAR-368758-CS -INDV / OFICIAL DE SUBPRO YECTOS DE INFRAESTRUCTU IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2024-12-31 RA PARA LA UOD CHACO (C AMIRI), CONSULTOR DE LINE A PAR III BO-EMPODERAR-368760-CS -INDV / OFICIAL DE SUBPRO IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-26 2024-12-31 YECTOS DE RIEGO UOD CHA CO (CAMIRI), CONSULTOR D E LINEA PAR III BO-EMPODERAR-368766-CS -INDV / OFICIAL DE SUBPRO YECTOS DE INFRAESTRUCTU IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-10-30 2023-10-05 2024-12-31 RA PARA LA UOD PANDO, C ONSULTOR DE LINEA PAR III BO-EMPODERAR-368767-CS -INDV / OFICIAL DE SUBPRO IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-20 2024-12-31 YECTOS DE RIEGO PARA LA UOD PANDO, CONSULTOR D E LINEA PAR III BO-EMPODERAR-368768-CS -INDV / ANALISTA AMBIENTA IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-19 2023-08-31 2023-09-20 2023-10-05 2024-12-31 L PARA LA UOD PANDO, CO NSULTOR DE LINEA PAR III Page 8 BO-EMPODERAR-368769-CS -INDV / ANALISTA SOCIAL Y IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-30 2023-08-31 2023-09-28 2023-10-05 2023-11-01 2024-12-31 GENERO PARA LA UOD PAN DO, CONSULTOR DE LINEA P AR III BO-EMPODERAR-368770-CS -INDV / ASISTENTE DE SUB P IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 2023-06-29 2023-08-10 2023-08-04 2023-08-31 2023-08-21 2023-10-05 2024-12-31 ROYECTOS PRODUCTIVOS P ARA LA UOD PANDO, CONSU LTOR DE LINEA PAR III BO-EMPODERAR-368771-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 PRODUCTIVAS PARA LA UOD RIBERALTA, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368772-CS -INDV / ANALISTA SOCIAL EN IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-30 2023-08-31 2023-09-28 2023-10-05 2024-12-31 GENERO PARA LA UOD POT OSI, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368773-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-19 2024-12-31 S COMUNITARIAS PARA LA U OD POTOSI, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368774-CS -INDV / OFICIAL DE SUBPRO IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 YECTOS DE REIGO PARA LA UOD POTOSI, CONSULTOR D E LINEA PAR III BO-EMPODERAR-368775-CS -INDV / ASISTENTE DE SUB P ROYECTOS COMUNITARIOS IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 2023-06-29 2023-08-10 2023-10-11 2023-08-31 2023-10-26 2023-10-05 2023-11-01 2024-12-31 PARA LA UOD POTOSI, CONS ULTOR DE LINEA PAR III BO-EMPODERAR-368776-CS -INDV / ASISTENTE DE SUB P IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 2023-06-29 2023-08-10 2023-07-20 2023-08-31 2023-08-15 2023-10-05 2023-08-23 2024-12-31 ROYECTOS PRODUCTIVOS P ARA LA UOD POTOSI, CONS ULTOR DE LINA PAR III BO-EMPODERAR-368778-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-19 2024-12-31 S PRODUCTIVAS PARA LA U OR CAMARGO, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368779-CS -INDV / CHOFER PARA LA UO IBRD / 94370 3. Project Management Posterior Individual Open - National 5,222.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-18 2023-08-31 2023-09-29 2023-10-05 2024-12-31 R CAMARGO, CONSULTOR D E LINEA PAR III BO-EMPODERAR-368780-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-20 2023-10-05 2024-12-31 O PARA LA UOR CAMARGO, CONSULTOR DE LINEA PAR II I BO-EMPODERAR-368781-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 S COMUNITARIAS PARA LA U OD COCHABAMBA, CONSUL TOR DE LINEA PAR III BO-EMPODERAR-368783-CS -INDV / ANALISTA SOCIAL Y IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-30 2023-08-31 2023-09-28 2023-10-05 2024-12-31 GENERO PARA LA UOD COC HABAMBA, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368784-CS -INDV / ASISTENTE DE SUBP ROYECTOS COMUNITARIOS IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 2023-06-29 2023-08-10 2023-09-11 2023-08-31 2023-09-21 2023-10-05 2024-12-31 PARA LA UOD COCHABAMBA , CONSULTOR DE LINEA PAR III BO-EMPODERAR-368785-CS -INDV / ASISTENTE DE SUB P ROYECTOS PRODUCTIVOS P IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 2023-06-29 2023-08-10 2023-09-11 2023-08-31 2023-09-21 2023-10-05 2024-12-31 ARA LA UOD COCHABAMBA, CONSULTOR DE LINEA PAR II I BO-EMPODERAR-368786-CS -INDV / OFICIAL DE SUBPRO YECTOS DE INFRAESTRUCTU IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-19 2024-12-31 RA PARA LA UOD CHUQUISA CA, CONSULTOR DE LINEA P AR III BO-EMPODERAR-368787-CS -INDV / OFICIAL DE SUB PRO IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2024-12-31 YECTOS DE RIEGO PARA LA UOD CHUQUISCA, CONSULT OR DE LINEA PAR III BO-EMPODERAR-368788-CS -INDV / OPERADOR DEPART IBRD / 94370 3. Project Management Posterior Individual Open - National 15,375.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-20 2023-10-05 2024-12-31 AMENTAL UOD CHUQUISCA, CONSULTOR DE LINEA PAR II I BO-EMPODERAR-368789-CS -INDV / ASISTENTE DE SUB P ROYECTOS COMUNITARIOS IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 2023-06-29 2023-08-10 2023-07-20 2023-08-31 2023-08-22 2023-10-05 2023-08-28 2024-12-31 PARA LA UOD CHUQUISCA, CONSULTOR DE LINEA PAR II I BO-EMPODERAR-368790-CS -INDV / ASISTENTE DE SUB P ROYECTOS PRODUCTIVOS P IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 2023-06-29 2023-08-10 2023-07-20 2023-08-31 2023-08-22 2023-10-05 2023-08-28 2024-12-31 ARA LA UOD CHUQUISACA, CONSULTOR DE LINEA PAR II I BO-EMPODERAR-368791-CS -INDV / OFICIAL DE SUBPRO YECTOS DE INFRAESTRUCTU IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-19 2024-12-31 RA PARA LA UOD TARIJA, CO NSULTOR DE LINEA PAR III BO-EMPODERAR-368792-CS -INDV / OFICIAL DE SUBPRO IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-19 2024-12-31 YECTOS DE RIEGO PARA LA UOD TARIJA, CONSULTOR D E LINEA PAR III BO-EMPODERAR-368794-CS -INDV / OFICIAL DE SUBPRO IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 YECTOS DE RIEGO PARA LA UOD ORURO, CONSULTOR D E LINEA PAR III BO-EMPODERAR-368795-CS -INDV / ANALISTA AMBIENTA IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 L PARA LA UOD ORURO, CO NSULTOR DE LINEA PAR III Page 9 BO-EMPODERAR-368796-CS -INDV / ANALISTA SOCIAL Y IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-30 2023-08-31 2023-09-28 2023-10-05 2024-12-31 GENERO PARA LA UOD ORU RO, CONSULTOR DE LINEA P AR III BO-EMPODERAR-368797-CS -INDV / ASISTENTE DE SUBP IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 2023-06-29 2023-08-10 2023-07-20 2023-08-31 2023-08-21 2023-10-05 2023-08-22 2024-12-31 ROYECTOS COMUNITARIOS PARA LA UOD ORURO, CONS ULTOR DE LINEA PAR III BO-EMPODERAR-368798-CS -INDV / ASISTENTE DE SUBP IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 2023-06-29 2023-08-10 2023-07-20 2023-08-31 2023-08-08 2023-10-05 2023-08-14 2024-12-31 ROYECTOS PRODUCTIVOS P ARA LA UOD ORURO, CONS ULTOR DE LINEA PAR III BO-EMPODERAR-368799-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2024-12-31 S COMUNITARIAS PARA LA U OD SANTA CRUZ, CONSULT OR DE LINEA PAR III BO-EMPODERAR-368800-CS -INDV / OFICIAL DE SUBPRO IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-10-06 2023-10-05 2023-11-01 2024-12-31 YECTOS DE RIEGO PARA LA UOD SANTA CRUZ, CONSUL TOR DE LINEA PAR III BO-EMPODERAR-368801-CS -INDV / ASISTENTE DE SUB P ROYECTOS PRODUCTIVOS P IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 2023-06-29 2023-08-10 2023-07-20 2023-08-31 2023-08-22 2023-10-05 2023-08-28 2024-12-31 ARA LA UOD SANTA CRUZ, C ONSULTOR DE LINEA PAR III BO-EMPODERAR-368802-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 O PARA LA UOR CHIQUITANI A, CONSULTOR DE LINEA PA R III BO-EMPODERAR-368803-CS -INDV / CONSULTOR INDIVID Selección directa UAL POR PRODUCTO PARA A IBRD / 94370 3. Project Management Posterior Direct - National 2,611.00 0.00 Firmado 2023-06-22 2023-06-26 2023-07-02 2023-07-18 2023-09-05 2024-03-03 de consultores CTUALIZAR EL REGISTRO DE ACTIVIDADES APROBADAS E N EL STEP BO-EMPODERAR-357205-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Cancelado 2023-04-17 2023-05-03 2023-04-27 2023-04-30 2023-05-07 2023-12-31 O UOD BENI BO-EMPODERAR-356753-CS -INDV / RESPONSABLE EN PP IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Cancelado 2023-04-14 2023-04-24 2023-04-27 2023-05-04 2023-12-31 C Y PROYECTOS BO-EMPODERAR-369772-CS -INDV / OPERADOR REGIONA IBRD / 94370 3. Project Management Posterior Individual Open - National 12,471.00 0.00 Firmado 2023-06-30 2023-07-12 2023-08-18 2023-07-19 2023-09-08 2023-09-20 2023-10-13 2023-10-03 2024-04-10 L UOR CAMARGO BO-EMPODERAR-356786-CS -INDV / OFICIAL DE SUB PRO IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Cancelado 2023-04-14 2023-05-04 2023-04-24 2023-04-27 2023-05-04 2023-12-31 YECTOS DE RIEGO UOD COC HABAMBA BO-EMPODERAR-374370-CS -INDV / ANALISTA DE ADQUI IBRD / 94370 3. Project Management Posterior Individual Open - National 9,472.00 0.00 Firmado 2023-07-26 2023-08-09 2023-09-13 2023-08-30 2023-10-04 2023-10-18 2023-11-08 2023-11-06 2023-12-31 SICIONES PARA INFRAESTRU CTURA - CONSULTOR DE LIN EA PAR III BO-EMPODERAR-374371-CS -INDV / ASISTENTE FINANCIE IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-26 2023-10-04 2023-09-13 2023-11-03 2023-10-04 2023-11-13 2023-11-08 2023-12-31 RO PARA LA UCN - CONSULT OR DE LINEA PAR III BO-EMPODERAR-374372-CS -INDV / ASISTENTE DE SUBP ROYECTOS DE INFRAESTRU IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-26 2023-08-17 2023-09-13 2023-11-10 2023-10-04 2023-11-23 2023-11-08 2023-11-27 2023-12-31 CTURA PARA LA UOD LA PAZ - CONSULTOR DE LINEA PAR III BO-EMPODERAR-374381-CS -INDV / ASISTENTE DE SUBP IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 En ejecución 2023-07-26 2023-08-17 2023-09-13 2023-10-04 2023-11-08 2023-12-31 ROYECTOS DE RIEGO PARA LA UOD LA PAZ - CONSULTO R DE LINEA PAR III BO-EMPODERAR-374563-CS -INDV / OFICIAL DE SUBPRO IBRD / 94370 3. Project Management Posterior Individual Open - National 9,472.00 0.00 En ejecución 2023-07-27 2023-08-09 2023-09-14 2023-10-05 2023-11-09 2023-12-31 YECTOS DE RIEGO UOD BEN I - CONSULTOR DE LINEA PA R III BO-EMPODERAR-374566-CS -INDV / ASISTENTE DE SUBP ROYECTOS DE INFRAESTRU IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-27 2023-08-17 2023-09-14 2023-09-15 2023-10-05 2023-10-04 2023-11-09 2023-12-31 CTURA PARA LA UOD COCH ABAMBA - CONSULTOR DE LI NEA PAR III BO-EMPODERAR-374567-CS -INDV / ASISTENTE DE SUBP ROYECTOS DE INFRAESTRU IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-27 2023-08-17 2023-09-14 2023-11-15 2023-10-05 2023-11-23 2023-11-09 2023-11-29 2023-12-31 CTURA PARA LA UOD CHUQ UISACA - CONSULTOR DE LI NEA PAR III BO-EMPODERAR-374569-CS -INDV / ASISTENTE DE SUBP ROYECTOS DE INFRAESTRU IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-27 2023-08-17 2023-09-14 2023-09-14 2023-10-05 2023-09-28 2023-11-09 2023-12-31 CTURA PARA LA UOD TARIJA - CONSULTOR DE LINEA PAR III BO-EMPODERAR-374570-CS -INDV / ASISTENTE DE SUBP ROYECTOS DE INFRAESTRU IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-27 2023-08-17 2023-09-14 2023-09-14 2023-10-05 2023-09-20 2023-11-09 2023-12-31 CTURA PARA LA UOD ORUR O - CONSULTOR DE LINEA P AR III BO-EMPODERAR-374572-CS -INDV / ASISTENTE DE SUBP ROYECTOS DE INFRAESTRU IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-27 2023-08-17 2023-09-14 2023-08-31 2023-10-05 2023-09-19 2023-11-09 2023-09-21 2023-12-31 CTURA PARA LA UOD SANTA CRUZ - CONSULTOR DE LINE A PAR III BO-EMPODERAR-356761-CS IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Cancelado 2023-04-14 2023-06-14 2023-04-24 2023-04-27 2023-05-04 2023-12-31 -INDV / RESPONSABLE EN SI STEMAS BO-EMPODERAR-356799-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Cancelado 2023-04-14 2023-05-03 2023-04-24 2023-04-27 2023-05-04 2023-12-31 S PRODUCTIVAS UOD SANTA CRUZ BO-EMPODERAR-374632-CS -INDV / OFICIAL DE SUBPRO IBRD / 94370 3. Project Management Posterior Individual Direct - National 9,471.00 0.00 Firmado 2023-07-27 2023-08-09 2023-08-06 2023-03-31 2023-08-09 2023-08-28 2023-08-16 2023-09-04 2023-12-31 YECTOS DE RIEGO PARA LA UOD COCHABAMBA -PAR III Page 10 BO-EMPODERAR-375094-CS -INDV / ANALISTA EN FORTA LECIMIENTO ORGANIZACION IBRD / 94370 3. Project Management Posterior Individual Open - National 7,577.00 0.00 Firmado 2023-07-31 2023-08-23 2023-09-18 2023-08-30 2023-10-09 2023-10-18 2023-11-13 2024-01-05 AL PARA LA UCN CONSULT OR INDIVIDUAL DE LINEA PA RA EL PAR II BO-EMPODERAR-374600-CS -CDS / Consultor Individual p or producto para ajuste de h IBRD / 94370 3. Project Management Posterior Individual Direct - National 24,942.00 0.00 Firmado 2023-08-18 2023-08-23 2023-08-28 2023-09-06 2023-09-18 2023-09-06 2023-10-23 2024-04-20 erramientas y apoyo al inici o en el sistema de informaci ón gerencial georreferencia do del PAR III BO-EMPODERAR-377834-CS -INDV / LEGAL JURIDICO CO IBRD / 94370 3. Project Management Posterior Individual Direct - National 6,333.00 0.00 Firmado 2023-08-18 2023-08-23 2023-08-28 2023-03-31 2023-08-31 2023-08-31 2023-09-07 2023-09-04 2023-12-31 NSULTOR INDIVIDUAL DE LI NEA PARA LA UNIDAD DE CO ORDINACION NACIONAL BO-EMPODERAR-378752-CS -INDV / CHOFER PARA LA UO IBRD / 94370 3. Project Management Posterior Individual Open - National 3,481.00 0.00 Firmado 2023-08-24 2023-09-04 2023-10-12 2023-10-11 2023-11-02 2023-10-23 2023-12-07 2025-03-04 D COCHABAMBA CONSULTO R INDIVIDUAL DE LINEA - PA R III BO-EMPODERAR-379304-CS -INDV / OPERADOR DEPART IBRD / 94370 3. Project Management Posterior Individual Direct - National 10,250.00 0.00 En ejecución 2023-08-28 2023-09-04 2023-09-07 2023-09-10 2023-09-17 2024-06-15 AMENTAL DE TARIJA CONSU LTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-379305-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,577.00 0.00 Firmado 2023-08-28 2023-09-04 2023-09-07 2023-03-31 2023-09-10 2023-09-11 2023-09-17 2023-09-13 2024-06-15 O PARA LA UOR RIBERALTA CONSULTOR DE LINEA PARA EL PAR III BO-EMPODERAR-379535-CS -INDV / 50 Facilitadores (apr oximadamente) UOD La Paz: Facilitador de la Unidad Ope 1. Capacity Building and Ins IBRD / 94370 Posterior Individual Open - National 174,950.00 0.00 En ejecución 2023-08-29 2023-09-04 2023-10-17 2023-11-07 2023-12-12 2024-06-09 rativa Departamental La Paz titutional Strengthening , Consultor por producto, En cargado de la elaborar plane s de alianza (planes de nego cio) para su financiamiento BO-EMPODERAR-379536-CS -INDV / 20 Facilitadores (apr oximadamente) UOR Rurren abaque: Facilitador de la Uni 1. Capacity Building and Ins IBRD / 94370 Posterior Individual Open - National 69,980.00 0.00 En ejecución 2023-08-29 2023-09-04 2023-10-17 2023-11-07 2023-12-12 2024-06-09 dad Operativa Regional Rurr titutional Strengthening enabaque, Consultor por pro ducto, Encargado de la elab orar planes de alianza (plan es de negocio) para su finan ciamiento BO-EMPODERAR-379537-CS -INDV / 30 Facilitadores (apr oximadamente) UOD Oruro: Facilitador de la Unidad Ope 1. Capacity Building and Ins IBRD / 94370 Posterior Individual Open - National 104,970.00 0.00 En ejecución 2023-08-29 2023-09-04 2023-10-17 2023-11-07 2023-12-12 2024-06-09 rativa Departamental Oruro, titutional Strengthening Consultor por producto, Enc argado de la elaborar planes de alianza (planes de negoci o) para su financiamiento BO-EMPODERAR-379538-CS -INDV / 30 Facilitadores UOD Potosi (aproximadamente): Facilitador de la Unidad Ope 1. Capacity Building and Ins IBRD / 94370 Posterior Individual Open - National 104,970.00 0.00 En ejecución 2023-08-29 2023-09-04 2023-10-17 2023-11-07 2023-12-12 2024-06-09 rativa Departamental Potosi, titutional Strengthening Consultor por producto, Enc argado de la elaborar planes de alianza (planes de negoci o) para su financiamiento BO-EMPODERAR-379539-CS -INDV / 45 Facilitadores UOD Cochabamba (aproximadam ente): Facilitador de la Unid 1. Capacity Building and Ins IBRD / 94370 Posterior Individual Open - National 174,950.00 0.00 En ejecución 2023-08-29 2023-09-04 2023-10-17 2023-11-07 2023-12-12 2024-06-09 ad Operativa Departamental titutional Strengthening Cochabamba, Consultor por producto, Encargado de la el aborar planes de alianza (pl anes de negocio) para su fin anciamiento BO-EMPODERAR-379540-CS -INDV / 15 Facilitadores UOR CAMARGO (aproximadamen te): Facilitador de la Unidad 1. Capacity Building and Ins IBRD / 94370 Posterior Individual Open - National 52,485.00 0.00 En ejecución 2023-08-29 2023-09-04 2023-10-17 2023-11-07 2023-12-12 2024-06-09 Operativa Regional Camarg titutional Strengthening o, Consultor por producto, E ncargado de la elaborar plan es de alianza (planes de neg ocio) para su financiamiento BO-EMPODERAR-379541-CS -INDV / 40 Facilitadores UOD Tarija (aproximadamente): F acilitador de la Unidad Oper 1. Capacity Building and Ins IBRD / 94370 Posterior Individual Open - National 139,960.00 0.00 En ejecución 2023-08-29 2023-09-04 2023-10-17 2023-11-07 2023-12-12 2024-06-09 ativa Departamental Tarija, titutional Strengthening Consultor por producto, Enc argado de la elaborar planes de alianza (planes de negoci o) para su financiamiento BO-EMPODERAR-379542-CS -INDV / 15 Facilitadores UOR Chiquitania (aproximadame nte): Facilitador de la Unida 1. Capacity Building and Ins IBRD / 94370 Posterior Individual Open - National 52,485.00 0.00 En ejecución 2023-08-29 2023-09-04 2023-10-17 2023-11-07 2023-12-12 2024-06-09 d Operativa Regional Chiquit titutional Strengthening ania, Consultor por producto , Encargado de la elaborar p lanes de alianza (planes de negocio) para su financiami ento BO-EMPODERAR-379543-CS -INDV / 50 Facilitadores UOD Santa Cruz (aproximadamen te): Facilitador de la Unidad 1. Capacity Building and Ins IBRD / 94370 Posterior Individual Open - National 174,950.00 0.00 En ejecución 2023-08-29 2023-09-04 2023-10-17 2023-11-07 2023-12-12 2024-06-09 Operativa Departamental Sa titutional Strengthening nta Cruz, Consultor por prod ucto, Encargado de la elabor ar planes de alianza (planes de negocio) para su financia miento BO-EMPODERAR-379654-CS -INDV / 10 Facilitadores UOD BENI (aproximadamente): F acilitador de la Unidad Oper 1. Capacity Building and Ins IBRD / 94370 Posterior Individual Open - National 34,990.00 0.00 En ejecución 2023-08-30 2023-09-04 2023-10-18 2023-11-08 2023-12-13 2024-06-10 ativa Departamental Beni, C titutional Strengthening onsultor por producto, Encar gado de la elaborar planes d e alianza (planes de negocio ) para su financiamiento BO-EMPODERAR-379660-CS -INDV / 20 Facilitadores UOD PANDO (aproximadamente) : Facilitador de la Unidad Op 1. Capacity Building and Ins IBRD / 94370 Posterior Individual Open - National 69,980.00 0.00 En ejecución 2023-08-30 2023-09-04 2023-10-18 2023-11-08 2023-12-13 2024-06-10 erativa Departamental de P titutional Strengthening ando Consultor por producto , Encargado de la elaborar p lanes de alianza (planes de negocio) para su financiami ento Page 11 BO-EMPODERAR-379662-CS -INDV / 10 Facilitadores UOR Riberalta (aproximadamente ): Facilitador de la Unidad O 1. Capacity Building and Ins IBRD / 94370 Posterior Individual Open - National 34,990.00 0.00 En ejecución 2023-08-30 2023-09-04 2023-10-18 2023-11-08 2023-12-13 2024-06-10 perativa Regional Riberalta, titutional Strengthening Consultor por producto, Enc argado de la elaborar planes de alianza (planes de negoci o) para su financiamiento BO-EMPODERAR-381938-CS -INDV / 40 Facilitadores UOD Chuquisaca (aproximadame nte): Facilitador de la Unida 1. Capacity Building and Ins IBRD / 94370 Posterior Individual Open - National 139,960.00 0.00 En ejecución 2023-09-13 2023-10-02 2023-11-01 2023-11-22 2023-12-27 2024-06-24 d Operativa Departamental titutional Strengthening Chuquisaca, Consultor por p roducto, Encargado de la ela borar planes de alianza (pla nes de negocio) para su fina nciamiento BO-EMPODERAR-381939-CS -INDV / 30 Facilitadores UOR CHACO -CAMIRI (aproximad amente): Facilitador de la U 1. Capacity Building and Ins IBRD / 94370 Posterior Individual Open - National 104,970.00 0.00 En ejecución 2023-09-13 2023-10-02 2023-11-01 2023-11-22 2023-12-27 2024-06-24 nidad Operativa Regional Ch titutional Strengthening aco, Consultor por producto, Encargado de la elaborar pla nes de alianza (planes de ne gocio) para su financiamient o BO-EMPODERAR-385098-CS -INDV / CHOFER II PARA LA IBRD / 94370 3. Project Management Posterior Individual Open - National 2,611.00 0.00 Firmado 2023-10-02 2023-10-04 2023-11-20 2023-11-03 2023-12-11 2023-11-08 2024-01-15 2023-11-09 2025-01-31 UOD ORURO - PAR III BO-EMPODERAR-385099-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Open - National 5,683.00 0.00 Firmado 2023-10-02 2023-10-04 2023-11-20 2023-10-22 2023-12-11 2023-11-24 2024-01-15 2025-01-31 O II PARA LA UOD COCHABA MBA - PAR III CONSULTOR IN DIVIDUAL DE LINEA BO-EMPODERAR-385101-CS -INDV / ANALISTA FINANCIER IBRD / 94370 3. Project Management Posterior Individual Open - National 5,683.00 0.00 Firmado 2023-10-02 2023-10-04 2023-11-20 2023-10-22 2023-12-11 2023-11-24 2024-01-15 2025-01-31 O (SISIN) PARA LA UNIDAD D E CORDINACION NACIONAL - PAR III BO-EMPODERAR-385102-CS -INDV / ASISTENTE DE SUB P IBRD / 94370 3. Project Management Posterior Individual Open - National 3,780.00 0.00 Firmado 2023-10-02 2023-10-05 2023-11-20 2023-11-07 2023-12-11 2023-11-10 2024-01-15 2025-01-31 ROYECTOS DE INFRAESTRU CTURA PARA LA UOD POTOS I - PAR III BO-EMPODERAR-385111-CS -CDS / 8 PROFESIONALES DE APOYO PARA DISTINTAS ARE IBRD / 94370 3. Project Management Posterior Individual Direct - National 24,075.00 0.00 Firmado 2023-10-06 2023-10-16 2023-10-16 2023-10-25 2023-11-06 2023-12-14 2023-12-11 2024-06-08 AS DEL PAR III - PRACTICAS PROFESIONALES (CONSULT ORES POR PRODUCTO) BO-EMPODERAR-385109-CS -CDS / CONSULTORIA POR P RODUCTO: PROFESIONAL DE IBRD / 94370 3. Project Management Posterior Individual Direct - National 4,582.00 0.00 Firmado 2023-10-04 2023-10-13 2023-10-14 2023-11-14 2023-11-04 2023-11-15 2023-12-09 2024-06-06 APOYO A EVALUACION DE S UBPROYECTOS DE INFRAEST RUCTURA UNIDAD DE COOR DINACION NACIONAL BO-EMPODERAR-388726-CS -INDV / OFICIAL DE SUB PRO IBRD / 94370 3. Project Management Posterior Individual Direct - National 3,789.00 0.00 Firmado 2023-10-20 2023-10-23 2023-10-30 2023-11-23 2023-11-02 2023-11-30 2023-11-09 2024-03-25 YECTOS COMUNITARIOS PAR A LA UOD CHUQUISACA - PA R III BO-EMPODERAR-390112-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Open - National 23,413.00 0.00 En ejecución 2023-10-27 2023-11-07 2023-12-15 2024-01-05 2024-02-09 2024-12-31 PARA LA UOD ORURO - CON SULTOR INDIVIDUAL DE LINE A PAR III BO-EMPODERAR-391003-CS -CDS / SERVICIO DE CONSUL TORIA DE DESARROLLO DE SISTEMA PARA LA ADMINIST Selección directa IBRD / 94370 3. Project Management Posterior Direct - National 50,522.00 0.00 En ejecución 2023-11-01 2023-11-07 2023-11-11 2024-01-15 2024-07-13 RACION DE LA LICITACION, E de consultores JECUCION Y CIERRE DE SUB PROYECTOS DE INFRAESTRU CTURA PRODUCTIVA COMPL EMENTARIA - PAR III (ETAPA II) BO-EMPODERAR-396645-CS -CDS / EVALUACIÓN DE DES EMPEÑO DEL PERSONAL TÉC NICO DEL PROYECTO DE INN Selección directa IBRD / 94370 3. Project Management Posterior Direct - National 29,620.00 0.00 En ejecución 2023-12-05 2024-01-03 2023-12-15 2024-02-18 2024-06-22 OVACIÓN PARA SISTEMAS A de consultores LIMENTARIOS RESILIENTES ( ALIANZAS RURALES – PAR III ) Y ESTUDIO DE SATISFACCI ÓN DE BENEFICIARIOS BO-EMPODERAR-397982-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 En ejecución 2023-12-12 2024-01-02 2024-01-30 2024-02-20 2024-03-26 2025-04-12 O II PARA LA UOD ORURO - P AR III BO-EMPODERAR-397985-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 En ejecución 2023-12-12 2024-01-02 2024-01-30 2024-02-20 2024-03-26 2025-04-12 O II PARA LA UOD POTOSI - PAR III BO-EMPODERAR-397991-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 En ejecución 2023-12-12 2024-01-02 2024-01-30 2024-02-20 2024-03-26 2025-04-12 O II PARA LA UOD CHUQUIS ACA - PAR III BO-EMPODERAR-397993-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 En ejecución 2023-12-12 2024-01-02 2024-01-30 2024-02-20 2024-03-26 2025-04-12 O II PARA LA UOD TARIJA - P AR III BO-EMPODERAR-397995-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 En ejecución 2023-12-12 2024-01-02 2024-01-30 2024-02-20 2024-03-26 2025-04-12 O II PARA LA UOD PANDO - P AR III BO-EMPODERAR-398015-CS -INDV / 20 CONSULTORES P 1. Capacity Building and Ins OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 titutional Strengthening LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOR CHACO (CAMIRI) BO-EMPODERAR-398005-CS -INDV / 20 CONSULTORES P 1. Capacity Building and Ins OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 45,772.59 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 titutional Strengthening LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOD ORURO BO-EMPODERAR-398008-CS -INDV / 10 CONSULTORES P 1. Capacity Building and Ins OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 titutional Strengthening LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOR CAMARGO Page 12 BO-EMPODERAR-398011-CS -INDV / 20 CONSULTORES P 1. Capacity Building and Ins OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 titutional Strengthening LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOD COCHABAMBA BO-EMPODERAR-398012-CS -INDV / 20 CONSULTORES P 1. Capacity Building and Ins OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 titutional Strengthening LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOD SANTA CRUZ BO-EMPODERAR-398007-CS -INDV / 20 CONSULTORES P 1. Capacity Building and Ins OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 titutional Strengthening LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOD CHUQUISACA BO-EMPODERAR-398006-CS -INDV / 20 CONSULTORES P 1. Capacity Building and Ins OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 titutional Strengthening LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOD POTOSI BO-EMPODERAR-398001-CS -INDV / 10 CONSULTORES P 1. Capacity Building and Ins OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 titutional Strengthening LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOD PANDO BO-EMPODERAR-398002-CS -INDV / 20 CONSULTORES P 1. Capacity Building and Ins OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 titutional Strengthening LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOD LA PAZ BO-EMPODERAR-398013-CS -INDV / 10 CONSULTORES P 1. Capacity Building and Ins OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 titutional Strengthening LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOR CHIQUITANIA BO-EMPODERAR-398004-CS -INDV / 10 CONSULTORES P 1. Capacity Building and Ins OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 titutional Strengthening LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOR RIBERALTA BO-EMPODERAR-398003-CS -INDV / 10 CONSULTORES P 1. Capacity Building and Ins OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 titutional Strengthening LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOR RURRENABAQUE BO-EMPODERAR-398014-CS -INDV / 10 CONSULTORES P 1. Capacity Building and Ins OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 titutional Strengthening LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOD BENI BO-EMPODERAR-398010-CS -INDV / 20 CONSULTORES P 1. Capacity Building and Ins OR PRODUCTO PARA LA EVA IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 titutional Strengthening LUACIÓN FINANCIERA DE ALI ANZAS PRODUCTIVAS - UOD TARIJA BO-EMPODERAR-399455-CS Ejecución pendie -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 2023-12-19 2024-02-06 2024-02-27 2024-04-02 2025-04-19 nte O II PARA LA UOD CAMIRI (C HACO) - PAR III BO-EMPODERAR-401624-CS -INDV / SECRETARIA PARA L IBRD / 94370 3. Project Management Posterior Individual Direct - National 10,309.00 0.00 En ejecución 2024-01-08 2024-01-08 2024-01-18 2024-01-21 2024-01-28 2024-06-13 A UNIDAD DE COORDINACIO N NACIONAL - PAR III BO-EMPODERAR-368793-CS -INDV / OPERADOR DEPART IBRD / 94370 3. Project Management Posterior Individual Open - National 15,375.00 0.00 Cancelado 2023-06-22 2023-06-23 2023-08-10 2023-08-31 2023-10-05 2024-12-31 AMENTAL PARA LA UOD TAR IJA, CONSULTOR DE LINEA P AR III BO-EMPODERAR-403600-CS -CDS / CONSULTOR INDIVID Selección directa UAL POR PRODUCTO PARA R IBRD / 94370 3. Project Management Posterior Direct - National 2,690.00 0.00 En ejecución 2024-01-17 2024-01-23 2024-01-27 2024-04-01 2024-09-28 de consultores EGISTRO DE INFORMACION EN EL SISTEMA STEP DEL P AR III BO-EMPODERAR-403941-CS -INDV / ASISTENTE DE SUB P IBRD / 94370 3. Project Management Posterior Individual Open - National 15,656.00 0.00 En ejecución 2024-01-19 2024-01-24 2024-03-08 2024-03-29 2024-05-03 2024-12-31 ROYECTOS DE RIEGO - UOD LA PAZ, CONSULTOR INDIVI DUAL DE LINEA PAR III BO-EMPODERAR-403942-CS -INDV / SECRETARIA - UOD L IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 En ejecución 2024-01-19 2024-01-24 2024-03-08 2024-03-29 2024-05-03 2024-12-31 A PAZ, CONSULTOR INDIVID UAL DE LINEA PAR III BO-EMPODERAR-403947-CS -INDV / ANALISTA FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 En ejecución 2024-01-19 2024-01-24 2024-03-08 2024-03-29 2024-05-03 2024-12-31 O - UOR CHACO (CAMIRI), C ONSULTOR INDIVIDUAL DE L INEA PAR III BO-EMPODERAR-403952-CS -INDV / ASISTENTE DE SUBP IBRD / 94370 3. Project Management Posterior Individual Open - National 15,656.00 0.00 En ejecución 2024-01-19 2024-01-24 2024-03-08 2024-03-29 2024-05-03 2024-12-31 ROYECTOS DE RIEGO - UOD PANDO, CONSULTOR INDIVI DUAL DE LINEA PAR III BO-EMPODERAR-403954-CS -INDV / OFICIAL DE SUB PRO IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 En ejecución 2024-01-19 2024-01-24 2024-03-08 2024-03-29 2024-05-03 2024-12-31 YECTOS DE RIEGO - UOD PA NDO, CONSULTOR INDIVIDU AL DE LINEA PAR III BO-EMPODERAR-403955-CS -INDV / ANALISTA AMBIENTA IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 En ejecución 2024-01-19 2024-01-24 2024-03-08 2024-03-29 2024-05-03 2024-12-31 L Y SEGURIDAD SOCIAL - UO D PANDO, CONSULTOR INDI VIDUAL DE LINEA PAR III BO-EMPODERAR-403957-CS -INDV / ANALISTA SOCIAL Y IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 En ejecución 2024-01-19 2024-01-24 2024-03-08 2024-03-29 2024-05-03 2024-12-31 DE GENERO - UOD PANDO, CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-403958-CS -INDV / SECRETARIA - UOR R IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 En ejecución 2024-01-19 2024-01-24 2024-03-08 2024-03-29 2024-05-03 2024-12-31 IBERALTA, CONSULTOR INDI VIDUAL DE LINEA PAR III Page 13 BO-EMPODERAR-403959-CS -INDV / ASISTENTE DE SUB P IBRD / 94370 3. Project Management Posterior Individual Open - National 15,656.00 0.00 En ejecución 2024-01-19 2024-01-24 2024-03-08 2024-03-29 2024-05-03 2024-12-31 ROYECTOS DE RIEGO - UOD POTOSI, CONSULTOR INDIVI DUAL DE LINEA PAR III BO-EMPODERAR-403965-CS -INDV / OFICIAL DE SUBPRO YECTOS DE INFRAESTRUCTU IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 En ejecución 2024-01-19 2024-01-24 2024-03-08 2024-03-29 2024-05-03 2024-12-31 RA - UOD COCHABAMBA, CO NSULTOR INDIVIDUAL DE LI NEA PAR III BO-EMPODERAR-403966-CS -INDV / ASISTENTE DE SUB P ROYECTOS DE RIEGO - UOD IBRD / 94370 3. Project Management Posterior Individual Open - National 15,656.00 0.00 En ejecución 2024-01-19 2024-01-24 2024-03-08 2024-03-29 2024-05-03 2024-12-31 CHUQUISACA, CONSULTOR I NDIVIDUAL DE LINEA PAR III BO-EMPODERAR-403967-CS -INDV / SECRETARIA - UOD C IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 En ejecución 2024-01-19 2024-01-24 2024-03-08 2024-03-29 2024-05-03 2024-12-31 HUQUISACA, CONSULTOR IN DIVIDUAL DE LINEA PAR III BO-EMPODERAR-403969-CS -INDV / SECRETARIA - UOD T IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 En ejecución 2024-01-19 2024-01-24 2024-03-08 2024-03-29 2024-05-03 2024-12-31 ARIJA, CONSULTOR INDIVIDU AL DE LINEA PAR III BO-EMPODERAR-403970-CS -INDV / CHOFER - UOD TARIJ IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 En ejecución 2024-01-19 2024-01-24 2024-03-08 2024-03-29 2024-05-03 2024-12-31 A, CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-403971-CS -INDV / OFICIAL DE ALIANZA IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Cancelado 2024-01-19 2024-03-08 2024-03-29 2024-05-03 2024-12-31 S PRODUCTIVAS - UOD ORU RO, CONSULTOR INDIVIDUA L DE LINEA PAR III BO-EMPODERAR-403972-CS -INDV / ASISTENTE DE SUB P IBRD / 94370 3. Project Management Posterior Individual Open - National 15,656.00 0.00 En ejecución 2024-01-19 2024-01-24 2024-03-08 2024-03-29 2024-05-03 2024-12-31 ROYECTOS DE RIEGO - UOD ORURO, CONSULTOR INDIVI DUAL DE LINEA PAR III BO-EMPODERAR-403973-CS -INDV / SECRETARIA - UOD IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 En ejecución 2024-01-19 2024-01-24 2024-03-08 2024-03-29 2024-05-03 2024-12-31 ORURO, CONSULTOR INDIVI DUAL DE LINEA PAR III BO-EMPODERAR-403977-CS -INDV / ANALISTA AMBIENTA L Y SEGURIDAD SOCIAL - UO IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 En ejecución 2024-01-19 2024-01-24 2024-03-08 2024-03-29 2024-05-03 2024-12-31 R CAMARGO, CONSULTOR IN DIVIDUAL DE LINEA PAR III BO-EMPODERAR-403978-CS -INDV / OFICIAL DE SUB PRO IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 En ejecución 2024-01-19 2024-01-24 2024-03-08 2024-03-29 2024-05-03 2024-12-31 YECTOS DE RIEGO - UOR CA MARGO, CONSULTOR INDIVI DUAL DE LINEA PAR III BO-EMPODERAR-403979-CS -INDV / ANALISTA SOCIAL Y IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 En ejecución 2024-01-19 2024-01-24 2024-03-08 2024-03-29 2024-05-03 2024-12-31 DE GENERO - UOR CAMARG O, CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-405255-CS -INDV / ESPECIALISTA EN RIE IBRD / 94370 3. Project Management Posterior Individual Open - National 23,549.00 0.00 En ejecución 2024-01-25 2024-01-25 2024-03-14 2024-04-04 2024-05-09 2025-01-06 GO PARA LA UCN - PAR III BO-EMPODERAR-405256-CS -INDV / ESPECIALISTA EN NE IBRD / 94370 3. Project Management Posterior Individual Open - National 23,549.00 0.00 En ejecución 2024-01-25 2024-01-25 2024-03-14 2024-04-04 2024-05-09 2025-01-06 GOCIOS PARA LA UCN - PAR III BO-EMPODERAR-406713-CS -INDV / CONSULTOR INDIVID Ejecución pendie UAL POR PRODUCTO PARA IBRD / 94370 3. Project Management Posterior Individual Open - National 5,220.00 0.00 2024-02-09 2024-03-29 2024-04-19 2024-05-24 2024-11-20 nte SEGUIMIENTO A OBSERVACI ONES AL CONTROL INTERNO DEL PROYECTO PAR III Page 14