PROCUREMENT PLAN (Textual Part) Project information: Republic of Niger, Niger integrated water security platform project – P174414 Project Implementation agency: PPA Coordination Unit of PISEN Date of the Procurement Plan: December 12, 2020 Period covered by this Procurement Plan: December 12, 2020 to December 31, 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market as set out in Act No. 2011-37 of October 28, 2011 covering general principles, control and regulation of public procurement and public service delegations in Niger and Decree No. 2016-641/PRN/PM of 21/December 2016 on the Code of Public Procurement and Public Service Delegations, the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Code of Public Procurement and Public Service Delegations, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. a. the tender/proposal file obliges the Bidder/Proposaler submitting a Offer/Proposal to file a signed approval, which will be attached to any potential contract, to confirm that it applies and complies with the Bank's Anti-Corruption Guidelines, including without limitation, the Bank's right to sanction and the Bank's rights for inspection and audit; b. Contracting documents include provisions, agreed with the Bank, to adequately mitigate environmental, social risks and impacts (including sexual exploitation and abuse and gender-based violence), hygiene and safety ("ESHS"); c. the Bank's rights to review the file and procurement activities; d. the existence of an effective complaints’ mechanism; And e. the management and archiving of files related to the Contracting Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable PROCUREMENT Niger : Niger Integrated Water Security Platform Project (Niger-IWSP Project) PLAN General Information Country: Niger 2020-12-20 Bank’s Approval Date of the Original Procurement Plan: 2024-02-09 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174414 GPN Date: Project Name: Niger Integrated Water Security Platform Project (Niger-IWSP Project) Loan / Credit No: IDA / 69900, / , IDA / V3590, IDA / 69910, IDA / D9080 Integrated Water Security Platform Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NE-IWSP-PPA IU-315254-CW- Demande d'offres RFB / Travaux de fourniture e Component 2: Expansion of I Open - Internationa Single Stage - One E - DTPM Travaux - 11,454,545.0 En cours d'e 2023-07-2 t pose des conduites de distri IDA / 69910 A priori Appel d'offres 0.00 2022-10-10 2023-01-17 2022-10-15 2023-01-19 2022-11-26 2023-03-28 2022-12-26 2023-05-18 2023-01-30 ntegrated Water Services l nvelope Droit civil français 0 xécution 9 bution de la rive droite dans l (français) e cadre du projet de la 3ième Usine à Niamey NE-IWSP-PPA IU-315255-CW- Demande d'offres RFB / Travaux de fourniture e Component 2: Expansion of I Open - Internationa Single Stage - One E - DTPM Travaux - 43,540,000.0 En cours d'e 2023-07-2 t pose des conduites de distri IDA / 69910 A priori Appel d'offres 0.00 2022-10-10 2023-01-17 2022-10-15 2023-01-19 2022-11-26 2023-03-30 2022-12-26 2023-06-10 2023-01-30 ntegrated Water Services l nvelope Droit civil français 0 xécution 9 bution de la rive gauche dan (français) s le cadre du projet de la 3iè me Usine de Niamey Demande de cota NE-PISEN-346562-GO-RFQ / Component 3: Project Manag Single Stage - One E tions (DTPM ne pr En attente d 2023-12-1 Fourniture et installation de IDA / D9080 A posteriori Demande de prix Open - National 21,429.00 0.00 2023-04-20 2023-06-15 ement and Capacity Building nvelope ovenant pas de la 'exécution 2 hangars pour le parking de l' Banque) UGP GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PISEN-2021-001 / Acquisition de matériel informatique, bur eautique pour le comité de p Component 1: Integrated Inv Single Stage - One E En cours d'ex réparation (7 Ordinateurs por IDA / 69900 A posteriori Demande de prix Limited 19,046.00 0.00 2021-02-26 2021-06-21 2021-04-23 2021-10-20 estments for Water Security nvelope écution tables+ accessoires, 1 stabili sateur de tension + accessoi res, 10 disques durs externes de 2 To ) PISEN-2021-002 / Achat de 2 véhicules 4X4 avec tous les d Component 1: Integrated Inv Single Stage - One E ocuments administratifs pour IDA / 69900 A posteriori Demande de prix Limited 145,455.00 133,280.67 Signé 2021-02-06 2021-06-14 2021-04-03 2021-09-09 2021-09-30 2021-11-23 estments for Water Security nvelope la liaison de l'équipe de prép aration et les missions de ter rain PISEN-2021-003 / Acquisition Component 1: Integrated Inv Single Stage - One E En attente d' de mobiliers de bureau pour l IDA / 69900 A posteriori Demande de prix Limited 27,000.00 0.00 2021-02-08 2021-04-05 2021-10-02 estments for Water Security nvelope exécution e comité de préparation PISEN-2021-004 / Acquisition d’un logiciel de Gestion Finan Component 1: Integrated Inv Passation de marc En cours d'ex IDA / V3590 A posteriori Direct 55,000.00 0.00 2021-01-05 2021-03-23 2021-01-10 2021-07-20 2021-02-14 2021-08-13 cière et Comptable, y compri estments for Water Security hé de gré à gré écution s le paramétrage NE-IWSP-PPA IU-315261-GO- RFB / Acquisition de matériel Component 3: Project Manag Single Stage - One E En cours d'ex IDA / 69900 A posteriori Appel d'offres Open - National 301,455.00 0.00 2022-10-24 2023-06-07 2022-10-29 2022-12-10 2023-01-09 2023-02-13 2023-08-12 s informatiques pour le perso ement and Capacity Building nvelope écution nnel niveau régional et centr al du PISEN NE-IWSP-PPA IU-315256-GO- RFB / Acquisition de 15 véhic Component 3: Project Manag Passation de marc Direct - Internation En cours d'ex IDA / 69900 A posteriori 1,150,000.00 0.00 2022-12-05 2023-02-16 2022-12-10 2023-02-06 2023-01-14 2023-07-13 ules et 76 motos pour les ant ement and Capacity Building hé de gré à gré al écution ennes et le niveau central du PISEN NE-IWSP-PPA IU-325821-GO- RFQ / Acquisition de mobilier Component 3: Project Manag Single Stage - One E En attente d' IDA / D9080 A posteriori Demande de prix Limited 100,000.00 0.00 2022-11-28 2023-01-23 2023-07-22 de bureau pour le niveau nati ement and Capacity Building nvelope exécution onal et régional du PISEN NE-PISEN-344892-GO-RFB / Component 1: Integrated Inv Single Stage - One E En attente d' Acquisition d'équipement po IDA / D9080 A posteriori Appel d'offres Open - National 272,727.00 0.00 2023-03-30 2023-04-04 2023-05-16 2023-06-15 2023-07-20 2024-01-16 estments for Water Security nvelope exécution ur les laboratoires existants NE-PISEN-346514-GO-RFQ / Component 3: Project Manag Single Stage - One E En attente d' Fourniture et installation d'éq IDA / D9080 A posteriori Demande de prix Limited 54,545.00 0.00 2023-03-20 2023-05-15 2023-11-11 ement and Capacity Building nvelope exécution uipement de visioconférence à l'UGP PISEN NE-PISEN-346559-GO-RFQ / Component 3: Project Manag Single Stage - One E En attente d' acquisition de consommables IDA / D9080 A posteriori Demande de prix Open - National 26,188.00 0.00 2023-06-05 2023-07-31 2024-01-27 ement and Capacity Building nvelope exécution informatiques pour l'UGP NE-PISEN-346039-GO-RFP / Component 3: Project Manag Single Stage - One E En attente d' Acquisition d'équipements au IDA / D9080 A posteriori Demande de prix Limited 63,636.00 0.00 2023-05-06 2023-07-01 2023-12-28 ement and Capacity Building nvelope exécution diovisuels pour la Cellule Co mmunication NE-PISEN-365825-GO-RFB / Acquisition de huit (8) group Component 3: Project Manag Single Stage - One E En attente d' IDA / 69900 A posteriori Appel d'offres Open - National 200,000.00 0.00 2023-07-03 2023-07-08 2023-08-19 2023-09-18 2023-10-23 2024-04-20 es électrogènes (1 de 100kw ement and Capacity Building nvelope exécution a pour l'UGP et 7 de 50kwa p our les UCR) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PISEN-346051-NC-RFQ / Component 3: Project Manag Single Stage - One E En attente d' IDA / D9080 A posteriori Demande de prix Limited 29,090.00 0.00 2023-04-04 2023-05-30 2023-11-26 Création d'un site Web pour l ement and Capacity Building nvelope exécution e projet Page 1 NE-PISEN-346545-NC-RFB / Recrutement d'un prestataire Component 3: Project Manag Single Stage - One E En attente d' IDA / D9080 A posteriori Appel d'offres Open - National 297,818.00 0.00 2023-04-10 2023-04-15 2023-05-27 2023-06-26 2023-07-31 2024-01-27 de gardiennage et d'entretie ement and Capacity Building nvelope exécution n des locaux de bureaux de l' UGP et des UCR NE-PISEN-346566-NC-RFQ / Recrutement d'un prestataire Component 3: Project Manag Single Stage - One E En attente d' IDA / D9080 A posteriori Demande de prix Limited 25,000.00 0.00 2023-04-15 2023-06-10 2023-12-07 pour le câblage du réseau inf ement and Capacity Building nvelope exécution ormatique de l'UGP CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PISEN-2021-010 / Etude sur l e développement local et l'en Sélection fondée s Component 1: Integrated Inv gagement citoyen du projet IDA / 69900 A posteriori ur les qualification Open - National 91,000.00 84,544.73 Signé 2021-02-15 2021-01-27 2021-03-08 2021-02-05 2021-04-21 2021-05-17 2021-05-21 2021-05-19 2021-06-25 2021-06-14 2021-12-22 estments for Water Security de la plateforme intégrée de s des consultants la sécurité de l'eau au Niger ( PISEN). PISEN-2021-011 / Etude sur l e genre et l’impact du chang Sélection fondée s ement climatique sur les fem Component 1: Integrated Inv En cours d'exécut IDA / 69900 A posteriori ur les qualification Open - National 90,000.00 0.00 2021-02-10 2021-01-27 2021-03-03 2021-02-05 2021-04-16 2021-05-16 2021-06-20 2021-12-17 mes et les mécanismes d’ad estments for Water Security ion s des consultants aptation du projet plateforme intégrée de sécurité de l’eau au Niger (PISEN) PISEN-2021-018 / Consultant Sélection fondée s En cours d'exécut pour l'élaboration du manuel / A posteriori ur les qualification Open - National 8,182.00 0.00 2021-01-14 2021-04-22 2021-02-04 2021-03-20 2021-04-19 2021-05-24 2021-11-20 ion de procédures et d'opération s des consultants PISEN-2021-005 / Etudes de faisabilité des activités et d’o Sélection fondée s pérationnalisation de la Gesti Component 1: Integrated Inv Open - Internationa En cours d'exécut IDA / V3590 A priori ur la qualité et le 500,000.00 0.00 2021-01-11 2020-12-24 2021-01-15 2021-01-12 2021-02-28 2021-09-06 2021-03-28 2021-10-20 2021-04-27 2022-04-16 2021-06-01 2022-12-12 2021-07-06 2022-07-06 on Intégrée des Ressources e estments for Water Security l ion coût n Eau (GIRE) dans la zone de s sept (7) sous bassins couve rts par le PISEN PISEN-2021-006 / Etudes d’A PS – APD et DAO et contrôle et surveillance des travaux d’ Sélection fondée s Component 1: Integrated Inv Open - Internationa En cours d'exécut Hydraulique Rurale, d’Assaini IDA / V3590 A priori ur la qualité et le 550,000.00 0.00 2021-02-07 2020-12-24 2021-02-12 2021-01-12 2021-03-28 2021-12-17 2021-04-25 2022-03-08 2021-05-25 2023-09-25 2021-06-29 2023-10-25 2021-08-03 2022-08-03 estments for Water Security l ion ssement dans les zones Oues coût t et Nord (Tillabéri, Dosso, Ta houa et Agadez) des quatre ( 4) sous bassins couvert par l e PISEN PISEN-2021-007 / Etudes d’A PS – APD et DAO et contrôle et surveillance des travaux d’ Sélection fondée s Component 1: Integrated Inv Open - Internationa En cours d'exécut Hydraulique Rurale, d’Assaini IDA / V3590 A priori ur la qualité et le 500,000.00 0.00 2021-02-07 2020-12-24 2021-02-12 2021-01-12 2021-03-28 2021-10-19 2021-04-25 2021-11-24 2021-05-25 2023-03-27 2021-06-29 2023-07-07 2021-08-03 2022-08-03 estments for Water Security l ion ssement dans les zones Cent coût re et Est (Maradi, Zinder et D iffa) des trois (3) sous bassin s couvert par le PISEN PISEN-2021-008 / Etudes de restauration des écosystème s, de mobilisation des ressou Sélection fondée s rces en eau et d’aménageme Component 1: Integrated Inv En cours d'exécut IDA / V3590 A priori ur la qualité et le 550,000.00 0.00 2021-02-02 2020-12-26 2021-02-07 2021-01-12 2021-03-23 2021-12-15 2021-04-20 2022-03-17 2021-05-20 2023-01-10 2021-06-24 2023-04-19 2021-07-29 2022-07-29 nts agricoles dans les zone O estments for Water Security ion coût uest et Nord (Tillabéri, Dosso , Tahoua et Agadez des quatr e (4) sous bassins couvert pa r le PISEN PISEN-2021-009 / Etudes de restauration des écosystème s, de mobilisation des ressou Sélection fondée s Component 1: Integrated Inv Open - Internationa En cours d'exécut rces en eau et d’aménageme IDA / V3590 A priori ur la qualité et le 500,000.00 0.00 2021-03-10 2020-12-25 2021-03-15 2021-01-07 2021-04-28 2021-12-17 2021-05-26 2022-03-22 2021-06-25 2022-09-07 2021-07-30 2023-02-21 2021-09-03 2022-09-03 estments for Water Security l ion nts agricoles dans les zones coût centre et Est (Maradi, Zinder et Diffa) des trois (3) sous ba ssins couvert par le PISEN PISEN-2021-012 / Etude sur l e contrôle de la qualité de l’e au de consommation humain Sélection fondée s e et le profil épidémiologique Open - Internationa En cours d'exécut / A posteriori ur la qualité et le 332,273.00 0.00 2021-02-15 2022-03-05 2021-02-20 2021-01-04 2021-04-05 2021-03-23 2021-05-03 2021-06-02 2021-07-07 2021-08-11 2022-08-11 des maladies à transmission l ion coût hydrique dans les Sept (7) ba ssins versants de Plate - For me Intégrée de Sécurité de l’ Eau au Niger (PISEN) PISEN-2021-020 / Cabinet po Component 1: Integrated Inv Sélection fondée s En cours d'exécut IDA / 69900 A posteriori Open - National 55,000.00 0.00 2021-11-10 2022-12-13 2021-12-01 2023-01-25 2022-01-14 2022-02-11 2022-03-13 2022-04-17 2022-05-22 2023-05-22 ur l'audit externe du PPF estments for Water Security ur la qualité et le ion coût PISEN-2021-025 / Sélection Sélection fondée s Component 1: Integrated Inv d'un cabinet chargé du recru IDA / V3590 A posteriori ur les qualification Limited 2,200.00 0.00 Annulé 2021-04-22 2021-04-22 2021-04-29 2021-05-01 2021-05-08 2021-05-18 estments for Water Security tement du RAF du PISEN s des consultants PISEN-2021-25A / Sélection d'un cabinet chargé du recru Sélection fondée s Component 1: Integrated Inv En cours d'exécut tement du RAF du PISEN, du IDA / V3590 A posteriori ur les qualification Limited 75,000.00 0.00 2021-05-18 2021-08-25 2021-05-25 2021-10-04 2021-05-27 2021-06-03 2021-07-03 estments for Water Security ion restant du personnel de l'UG s des consultants P, et celui du niveau régional PISEN-2021-018A / Recrute ment d’un cabinet charge de l’élaboration du manuel de M Sélection fondée s ise en Œuvre du Projet -MOP- Component 1: Integrated Inv En cours d'exécut IDA / V3590 A posteriori ur les qualification Limited 55,000.00 0.00 2021-08-27 2021-09-10 2021-09-10 2021-10-20 2021-09-20 2021-12-03 2021-10-02 2021-11-16 (I) volume sur les procédures estments for Water Security ion s des consultants administratives et fiduciaires, (II) volume sur les procédure s de suivi-évaluation et (III) v olume sur les procédures d'e xécution PISEN-2021-028 / Sélection Sélection fondée s Component 1: Integrated Inv Open - Internationa En cours d'exécut d'un cabinet, chargé de l'assi IDA / V3590 A priori ur la qualité et le 1,018,000.00 0.00 2021-10-19 2021-12-20 2021-11-09 2022-01-06 2021-12-23 2022-09-20 2022-01-20 2022-11-01 2022-02-19 2023-03-12 2022-03-26 2023-10-25 2022-04-30 2023-04-30 estments for Water Security l ion stance en passation des mar coût chés NE-IWSP-PPA IU-298251-CS- QCBS / Sélection d'un cabine Sélection fondée s Component 1: Integrated Inv Open - Internationa En cours d'exécut t pour le Service de Maitrise IDA / V3590 A priori ur la qualité et le 2,200,000.00 0.00 2022-06-20 2022-07-07 2022-07-11 2022-08-24 2022-09-21 2022-10-21 2022-11-25 2022-12-30 2023-12-30 estments for Water Security l ion d’œuvre pour le suivi et le co coût ntrôle des travaux des lots 2. 3A ;2.4A ;3A et 4A Page 2 NE-IWSP-PPA IU-298255-CS- QCBS / Sélection d'un cabine Sélection fondée s t pour le Service de Maitrise Component 1: Integrated Inv Open - Internationa En cours d'exécut IDA / V3590 A priori ur la qualité et le 1,800,000.00 0.00 2022-06-20 2022-06-29 2022-07-11 2022-11-23 2022-08-24 2023-05-24 2022-09-21 2023-07-18 2022-10-21 2024-01-31 2022-11-25 2022-12-30 2023-12-30 d’œuvre pour le suivi et le co estments for Water Security l ion coût ntrôle des travaux des lots 6 et 7 (voir les détails des trav aux en annexe) NE-IWSP-PPA IU-312999-CS- QCBS / SELECTION D'UN CAB INET POUR L'ELABORATION D ’UNE EIES ET D’UN PLAN D’A Sélection fondée s Component 1: Integrated Inv Open - Internationa En cours d'exécut CTION DE REINSTALLATION ( IDA / V3590 A posteriori ur la qualité et le 215,000.00 0.00 2022-09-05 2022-11-15 2022-09-09 2023-02-06 2022-10-23 2022-11-20 2022-12-20 2023-01-24 2023-02-28 2024-02-28 estments for Water Security l ion PAR) DU PROJET POUR L’AL coût IMENTATION EN EAU POTABL E DE LA VILLE DE TERA A PA RTIR DU FLEUVE NIGER A GO THEYE ET VILLAGES ASSOCIE S NE-IWSP-PPA IU-325717-CS- QCBS / Recrutement d'un ca binet chargé de la réalisation Sélection fondée s de l'étude sur le contrôle de l Component 1: Integrated Inv Open - Internationa En cours d'exécut IDA / D9080 A posteriori ur la qualité et le 332,000.00 0.00 2022-11-23 2022-12-01 2022-12-14 2023-02-06 2023-01-27 2023-02-24 2023-03-26 2023-04-30 2023-06-04 2024-06-03 a qualité de l'eau de consom estments for Water Security l ion coût mation humaine et le profil é pidémiologique des maladies à transmission hydrique dans les 7 bassins versants du PIS EN NE-PISEN-344862-CS-CQS / Recrutement d'un cabinet po Sélection fondée s ur la réalisation des études E Component 1: Integrated Inv En attente d'exéc IDA / D9080 A posteriori ur les qualification Open - National 27,273.00 0.00 2023-04-15 2023-05-06 2023-06-19 2023-07-19 2023-08-23 2024-02-19 IES/PAR dans le cadre des tra estments for Water Security ution s des consultants vaux du laboratoire central moderne de recherche sur la qualité de l'eau NE-PISEN-346063-CS-INDV / recrutement d'un consultant Sélection fondée s pour les enquêtes et revue d Component 1: Integrated Inv En attente d'exéc IDA / D9080 A posteriori ur les qualification Open - National 18,182.00 0.00 2023-03-30 2023-04-20 2023-06-03 2023-07-03 2023-08-07 2024-02-03 ocumentaire pour définir le n estments for Water Security ution s des consultants iveau de connaissances, attit udes et pratiques des popula tions des sous bassins NE-PISEN-346037-CS-QCBS / Recrutement d'ONG en charg Sélection fondée s e de la mise en œuvre et du Component 1: Integrated Inv Open - Internationa En cours d'exécut IDA / D9080 A posteriori ur la qualité et le 849,057.00 0.00 2023-04-17 2023-05-02 2023-05-08 2023-06-09 2023-06-21 2023-07-19 2023-08-18 2023-09-22 2023-10-27 2024-10-26 suivi des activités d'Engage estments for Water Security l ion coût ment Citoyen et de la mise e n place des organes GIRE po ur la région d'Agadez NE-PISEN-344905-CS-CQS / Recrutement d'un cabinet po ur l'élaboration des avant-pr Sélection fondée s Component 1: Integrated Inv Open - Internationa En attente d'exéc ojets détaillés et DAO et le su IDA / D9080 A posteriori ur les qualification 136,364.00 0.00 2023-04-30 2023-05-21 2023-07-04 2023-08-03 2023-09-07 2024-03-05 estments for Water Security l ution ivi et contrôle des travaux de s des consultants construction des sièges des a gences de l'eau de dix sous b assins NE-PISEN-354196-CS-QCBS / Recrutement d’ONG en charg Sélection fondée s e de la mise en œuvre et du Component 1: Integrated Inv Open - Internationa En cours d'exécut IDA / 69910 A priori ur la qualité et le 1,415,094.00 0.00 2023-05-01 2023-05-05 2023-05-22 2023-06-09 2023-07-05 2023-08-02 2023-09-01 2023-10-06 2023-11-10 2024-11-09 suivi des activités d’Engage estments for Water Security l ion coût ment Citoyen et de la mise e n place des organes GIRE po ur la région de Dosso NE-PISEN-354193-CS-QCBS / Recrutement d’ONG en charg Sélection fondée s e de la mise en œuvre et du Component 1: Integrated Inv Open - Internationa En cours d'exécut IDA / 69910 A posteriori ur la qualité et le 566,038.00 0.00 2023-05-01 2023-05-02 2023-05-22 2023-06-09 2023-07-05 2023-08-02 2023-09-01 2023-10-06 2023-11-10 2024-11-09 suivi des activités d’Engage estments for Water Security l ion coût ment Citoyen et de la mise e n place des organes GIRE po ur la région de Diffa NE-PISEN-354204-CS-QCBS / Recrutement d’ONG en charg Sélection fondée s e de la mise en œuvre et du Component 1: Integrated Inv Open - Internationa En cours d'exécut IDA / 69910 A posteriori ur la qualité et le 660,377.00 0.00 2023-05-01 2023-05-02 2023-05-22 2023-06-09 2023-07-05 2023-08-02 2023-09-01 2023-10-06 2023-11-10 2024-11-09 suivi des activités d’Engage estments for Water Security l ion coût ment Citoyen et de la mise e n place des organes GIRE po ur la région e Tillabéri NE-PISEN-354202-CS-QCBS / Recrutement d’ONG en charg Sélection fondée s e de la mise en œuvre et du Component 1: Integrated Inv Open - Internationa En cours d'exécut IDA / 69910 A priori ur la qualité et le 1,698,113.00 0.00 2023-05-01 2023-05-05 2023-05-22 2023-06-27 2023-07-05 2023-12-06 2023-08-02 2023-09-01 2023-10-06 2023-11-10 2024-11-09 suivi des activités d’Engage estments for Water Security l ion coût ment Citoyen et de la mise e n place des organes GIRE po ur la région de Tahoua NE-PISEN-354207-CS-QCBS / Recrutement d’ONG en charg Sélection fondée s e de la mise en œuvre et du Component 1: Integrated Inv Open - Internationa En cours d'exécut IDA / 69910 A priori ur la qualité et le 2,641,509.00 0.00 2023-05-01 2023-05-02 2023-05-22 2023-06-09 2023-07-05 2023-08-02 2023-09-01 2023-10-06 2023-11-10 2024-11-09 suivi des activités d’Engage estments for Water Security l ion coût ment Citoyen et de la mise e n place des organes GIRE po ur la région de Zinder NE-PISEN-344365-CS-CQS / Recrutement d'un consultant pour la réalisation des étude Sélection fondée s Component 1: Integrated Inv Open - Internationa En attente d'exéc s (APS, APD, DAO) et le contr IDA / D9080 A posteriori ur les qualification 54,545.00 0.00 2023-04-30 2023-05-21 2023-07-04 2023-08-03 2023-09-07 2024-03-05 estments for Water Security l ution ôle des travaux de constructi s des consultants on du laboratoire central mo derne de recherche sur la qu alité de l'eau NE-PISEN-354201-CS-QCBS / Recrutement d’ONG en charg Sélection fondée s e de la mise en œuvre et du Component 1: Integrated Inv Open - Internationa En cours d'exécut IDA / 69910 A priori ur la qualité et le 2,169,811.00 0.00 2023-05-01 2023-05-05 2023-05-22 2023-06-09 2023-07-05 2023-08-02 2023-09-01 2023-10-06 2023-11-10 2024-11-09 suivi des activités d’Engage estments for Water Security l ion coût ment Citoyen et de la mise e n place des organes GIRE po ur la région de Maradi NE-PISEN-355321-CS-CQS / Sélection d’un consultant cha Sélection fondée s rgé de l’élaboration du manu Component 1: Integrated Inv En attente d'exéc IDA / 69900 A posteriori ur les qualification Open - National 50,000.00 0.00 2023-05-01 2023-05-22 2023-07-05 2023-08-04 2023-09-08 2024-03-06 el des conditions basées sur l estments for Water Security ution s des consultants a performance (CBP) pour la mise en place de l’agence dé diée à l’hydraulique rurale NE-PISEN-365822-CS-QCBS / Sélection fondée s Recrutement d'un cabinet po Component 3: Project Manag Open - Internationa En cours d'exécut IDA / 69900 A priori ur la qualité et le 1,374,545.00 0.00 2023-07-03 2023-07-24 2023-09-06 2023-10-04 2023-11-03 2023-12-08 2024-01-12 2025-01-11 ur la mise en œuvre de l'eng ement and Capacity Building l ion coût ament citoyen et technologie disruptives Page 3 NE-PISEN-365824-CS-QCBS / Sélection fondée s Recrutement d'un cabinet po Component 3: Project Manag Open - Internationa En cours d'exécut IDA / 69900 A priori ur la qualité et le 1,909,091.00 0.00 2023-07-03 2023-07-24 2023-09-06 2023-10-04 2023-11-03 2023-12-08 2024-01-12 2025-01-11 ur la réalisation des campagn ement and Capacity Building l ion coût es de communication NE-PISEN-384970-CS-QCBS / Etude sur le contrôle de la qu alité de l’eau de consommati Sélection fondée s on humaine et le profil épidé Component 1: Integrated Inv Open - Internationa En cours d'exécut IDA / D9080 A posteriori ur la qualité et le 332,000.00 0.00 2023-10-16 2023-10-02 2023-11-06 2023-11-07 2023-12-20 2024-01-17 2024-02-16 2024-03-22 2024-04-26 2025-04-26 miologique des maladies à tr estments for Water Security l ion coût ansmission hydrique dans les Sept (7) bassins versants de Plate - Forme Intégrée de Sé curité de l’Eau au Niger (PISE N) NE-PISEN-384993-CS-CQS / Sélection fondée s Sélection d’un vérificateur po Component 1: Integrated Inv En cours d'exame IDA / D9080 A posteriori ur les qualification Open - National 254,545.00 0.00 2023-10-20 2024-02-06 2023-11-10 2023-12-24 2024-01-23 2024-02-27 2024-08-25 ur la gestion des fonds CBP ( estments for Water Security n s des consultants agence de l’hydraulique rural e) PISEN-2021-031 / Sélection Sélection fondée s d'un vérificateur pour la gesti Component 1: Integrated Inv IDA / V3590 A posteriori ur les qualification Open - National 254,545.00 0.00 Annulé 2021-10-29 2023-07-24 2021-11-19 2023-02-06 2022-01-02 2022-02-01 2022-03-08 2022-09-04 on des fonds CBP (agence de estments for Water Security s des consultants l'hydraulique rurale) NE-PISEN-393928-CS-QCBS / Recrutement d'un Consortiu Sélection fondée s m de bureau d'études chargé Component 1: Integrated Inv Open - Internationa En cours d'exécut IDA / D9080 A priori ur la qualité et le 1,261,818.00 0.00 2023-11-30 2023-12-08 2023-12-21 2024-01-31 2024-02-03 2024-03-02 2024-04-01 2024-05-06 2024-06-10 2025-06-10 de conduire l'étude et d'acco estments for Water Security l ion coût mpagner le processus de mis e en œuvre de la reforme de l'hydraulique rurale au Niger NE-PISEN-393929-CS-CQS / Recrutement d’un cabinet po ur la réalisation des études E Sélection fondée s Component 1: Integrated Inv En cours d'exécut IES/PAR des travaux d’hydra IDA / D9080 A posteriori ur les qualification Limited 100,000.00 0.00 2023-11-30 2023-11-23 2023-12-14 2024-01-13 2024-02-17 2024-08-15 estments for Water Security ion ulique rurale et d’assainisse s des consultants ment dans les zones de Mara di, Zinder et Diffa des trois (3 ) sous bassins couverts par le PISEN NE-PISEN-408969-CS-CQS / Sélection fondée s Recrutement d'un consultant Component 1: Integrated Inv En attente d'exéc IDA / 69910 A posteriori ur les qualification Open - National 91,000.00 0.00 2024-02-23 2024-03-15 2024-04-28 2024-05-28 2024-07-02 2025-08-26 pour la mise à niveau du syst estments for Water Security ution s des consultants ème d'information sur les ter res restaurées INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PISEN-2021-013 / Consultant Individuel en qualité de gesti En cours d'exécut / A posteriori Individuel Open 16,364.00 0.00 2021-01-04 2021-06-07 2021-02-22 2021-03-15 2021-04-19 2021-10-16 onnaire financier et comptabl ion e pour la préparation du PISE N PISEN-2021-014 / Consultant individuel pour l'élaboration / A posteriori Individuel Limited 50,000.00 0.00 Annulé 2021-01-05 2021-01-12 2021-01-10 2021-01-31 2021-03-07 2021-09-03 des instruments de sauvegar des (CGES, CPRP) PISEN-2021-015 / Consultant individuel pour l'élaboration Component 1: Integrated Inv IDA / V3590 A posteriori Individuel Limited 10,000.00 25,001.54 Signé 2021-01-13 2021-01-27 2021-01-18 2021-01-28 2021-02-08 2021-02-19 2021-03-15 2021-03-06 2021-09-11 de Plan de gestion intégrée d estments for Water Security es pestes et pesticides (PGIP P) PISEN-2021-016 / Consultant Component 1: Integrated Inv individuel pour l'élaboration IDA / V3590 A posteriori Individuel Limited 10,000.00 40,079.46 Achevé 2021-01-13 2021-01-27 2021-01-18 2021-02-08 2021-02-08 2021-02-19 2021-03-15 2021-03-08 2021-09-11 2021-04-11 estments for Water Security du plan de gestion de la biodi versité PISEN-2021-017 / Consultant individuel pour l'élaboration Component 1: Integrated Inv En cours d'exécut IDA / V3590 A posteriori Individuel Limited 10,000.00 0.00 2021-01-13 2021-01-12 2021-01-18 2021-02-15 2021-02-08 2021-02-19 2021-03-15 2021-09-11 d’une procédure de Gestion estments for Water Security ion de la Main d’œuvre (PGMO) PISEN-2021-019 / Consultant Component 1: Integrated Inv en charge de l’élaboration du IDA / V3590 A posteriori Individuel Limited 55,000.00 21,167.97 Achevé 2021-01-02 2021-01-27 2021-01-07 2021-05-10 2021-01-28 2021-05-24 2021-03-04 2021-07-02 2021-08-31 2021-08-01 estments for Water Security PPSD du PISEN PISEN-2021-14 A / Consultan Component 1: Integrated Inv En cours d'exécut t individuel pour l'élaboration IDA / V3590 A posteriori Individuel Limited 25,000.00 0.00 2021-02-04 2021-01-14 2021-02-09 2021-01-29 2021-02-19 2021-02-26 2021-02-23 2021-03-25 estments for Water Security ion du CPRP du PISEN PISEN-2021-021 / Consultant Component 1: Integrated Inv En cours d'exame individuel pour l'élaboration IDA / V3590 A posteriori Individuel Limited 25,000.00 0.00 2021-02-08 2021-04-29 2021-02-11 2021-02-12 2021-02-28 2021-03-30 estments for Water Security n du CGES du PISEN PISEN-2021-026 / Évaluation préliminaire des risques de s Component 1: Integrated Inv En cours d'exécut IDA / V3590 A posteriori Individuel Direct 4,500.00 0.00 2021-08-04 2021-08-01 2021-08-07 2021-08-09 2021-08-11 2021-08-18 écurité estments for Water Security ion Programme Intégrée pour la Sécurité de l'Eau au Niger (PI SEN) PISEN-2021-027 / ELABORAT ION DE LA STRATEGIE DE LA Component 1: Integrated Inv PASSATION DES MARCHES P IDA / V3590 A posteriori Individuel Direct 19,000.00 28,892.19 Signé 2021-08-13 2021-08-16 2021-08-16 2021-08-14 2021-08-19 2021-08-16 2021-08-22 2021-08-31 2021-09-06 estments for Water Security OUR PROMOUVOIR LE DEVEL OPPEMENT (PPSD) DU PISEN PISEN-2021-029 / Plan de ge Component 1: Integrated Inv En cours d'exame IDA / V3590 A posteriori Individuel Limited 32,000.00 0.00 2021-09-10 2021-10-05 2021-09-15 2021-09-29 2021-10-04 2021-10-09 stion des risques sécuritaires estments for Water Security n (PGS) PISEN-2021-030 / Sélection Component 1: Integrated Inv En cours d'exécut IDA / V3590 A posteriori Individuel Limited 60,000.00 0.00 2021-09-13 2021-10-05 2021-09-18 2021-11-23 2021-09-28 2021-10-06 2021-10-11 d'un consultant pour l'évalua estments for Water Security ion tion sociale PISEN-2021-033 / Sélection d'un consultant chargé de l'él aboration du manuel des con Component 1: Integrated Inv En cours d'exécut IDA / V3590 A posteriori Individuel Open 50,000.00 0.00 2021-10-29 2022-12-20 2021-12-17 2022-01-07 2022-02-11 2022-08-10 ditions basées sur la perform estments for Water Security ion ance (CBP) pour la mise en pl ace de l'agence dédiée à l'hy draulique rurale Page 4 PISEN-2021-034 / Sélection d'un consultant chargé de l'él Component 1: Integrated Inv En attente d'exéc aboration du manuel d'opéra IDA / V3590 A posteriori Individuel Open 40,000.00 0.00 2021-10-19 2021-12-07 2021-12-28 2022-02-01 2022-07-31 estments for Water Security ution tions et plan d'action de la co mposante 4 d'intervention d' urgence PISEN-2021-035 / Consultant Component 1: Integrated Inv En cours d'exécut Individuel en qualité de coor IDA / V3590 A posteriori Individuel Open 369,600.00 0.00 2021-10-15 2021-09-29 2021-12-03 2021-12-24 2022-01-28 2022-07-27 estments for Water Security ion donnateur du PISEN pour la durée du projet PISEN-2021-036 / Consultant Component 1: Integrated Inv En cours d'exécut individuel en qualité de Resp IDA / V3590 A posteriori Individuel Open 302,400.00 0.00 2021-10-15 2021-09-29 2021-12-03 2021-12-24 2022-01-28 2022-07-27 estments for Water Security ion onsable Administratif et Fina ncier (RAF) PISEN-2021-039 / Consultant Component 1: Integrated Inv En cours d'exame individuel en qualité d’Exper IDA / V3590 A posteriori Individuel Open 302,400.00 0.00 2021-10-15 2021-09-30 2021-12-03 2021-12-24 2022-01-28 2022-07-27 estments for Water Security n t en genre et inclusion social e du PISEN PISEN-2022-001 / recruteme Component 1: Integrated Inv En cours d'exame IDA / V3590 A posteriori Individuel Open 18,000.00 0.00 2022-02-18 2022-02-08 2022-04-08 2022-04-29 2022-06-03 2022-11-30 nt d’un Assistant au Compta estments for Water Security n ble Principal PISEN-2022-002 / recruteme Component 1: Integrated Inv En cours d'exame IDA / V3590 A posteriori Individuel Open 33,000.00 0.00 2022-02-18 2022-03-16 2022-04-08 2022-04-29 2022-06-03 2022-11-30 nt d’un Auditeur Interne Princ estments for Water Security n ipal PISEN-2022-004 / recruteme Component 1: Integrated Inv En cours d'exame IDA / V3590 A posteriori Individuel Open 33,000.00 0.00 2022-02-18 2022-03-23 2022-04-08 2022-04-29 2022-06-03 2022-11-30 nt d’un Expert Eau estments for Water Security n PISEN-2022-006 / recruteme Component 1: Integrated Inv En cours d'exame IDA / V3590 A posteriori Individuel Open 33,000.00 0.00 2022-02-19 2022-02-08 2022-04-09 2022-04-30 2022-06-04 2022-12-01 nt d’un Expert en Environne estments for Water Security n ment PISEN-2022-008 / recruteme Component 1: Integrated Inv nt d’un Spécialiste en Hygièn IDA / V3590 A posteriori Individuel Open 33,000.00 0.00 Annulé 2022-02-18 2022-02-08 2022-04-08 2022-04-29 2022-06-03 2022-11-30 estments for Water Security e et Assainissement (SHA) PISEN-2022-003 / recruteme Component 1: Integrated Inv IDA / V3590 A posteriori Individuel Open 33,000.00 0.00 Annulé 2022-02-18 2022-02-08 2022-04-08 2022-04-29 2022-06-03 2022-11-30 nt d’un Expert en Agriculture estments for Water Security PISEN-2022-009 / recruteme Component 1: Integrated Inv nt d’un Assistant en Passatio IDA / V3590 A posteriori Individuel Open 18,000.00 0.00 Annulé 2022-02-18 2022-04-08 2022-04-29 2022-06-03 2022-11-30 estments for Water Security n des Marchés au niveau de l’UGP PISEN-2022-007 / recruteme nt d’un Spécialiste en Comm Component 1: Integrated Inv IDA / V3590 A posteriori Individuel Open 33,000.00 0.00 Annulé 2022-02-17 2022-02-08 2022-04-07 2022-04-28 2022-06-02 2022-11-29 unication et Gestion des Con estments for Water Security naissances (SCGC) PISEN-2022-005 / recruteme Component 1: Integrated Inv IDA / V3590 A posteriori Individuel Open 33,000.00 0.00 Annulé 2022-02-18 2022-02-08 2022-04-08 2022-04-29 2022-06-03 2022-11-30 nt d’un Expert Génie Rural (E estments for Water Security GR) PISEN-2022-014 / recruteme Component 1: Integrated Inv nt d’un Assistant en Passatio IDA / V3590 A posteriori Individuel Open 18,000.00 0.00 Annulé 2022-02-19 2022-04-09 2022-04-30 2022-06-04 2022-12-01 estments for Water Security n des Marchés, pour la régio n de Maradi PISEN-2022-015 / recruteme Component 1: Integrated Inv nt d’un Assistant en Passatio IDA / V3590 A posteriori Individuel Open 18,000.00 0.00 Annulé 2022-02-18 2022-04-08 2022-04-29 2022-06-03 2022-11-30 estments for Water Security n des Marchés, pour la régio n de Zinder PISEN-2022-016 / recruteme Component 1: Integrated Inv nt d’un Assistant en Passatio IDA / V3590 A posteriori Individuel Open 18,000.00 0.00 Annulé 2022-02-19 2022-04-09 2022-04-30 2022-06-04 2022-12-01 estments for Water Security n des Marchés, pour la régio n de Diffa PISEN-2022-012 / recruteme Component 1: Integrated Inv nt d’un Assistant en Passatio IDA / V3590 A posteriori Individuel Open 18,000.00 0.00 Annulé 2022-02-18 2022-04-08 2022-04-29 2022-06-03 2022-11-30 estments for Water Security n des Marchés, pour la régio n de Tahoua PISEN-2022-011 / recruteme Component 1: Integrated Inv nt d’un Assistant en Passatio IDA / V3590 A posteriori Individuel Open 18,000.00 0.00 Annulé 2022-02-19 2022-04-09 2022-04-30 2022-06-04 2022-12-01 estments for Water Security n des Marchés, pour la régio n de Dosso PISEN-2022-017 / recruteme Component 1: Integrated Inv nt d’un Comptable pour la ré IDA / V3590 A posteriori Individuel Open 18,000.00 0.00 Annulé 2022-02-19 2022-04-09 2022-04-30 2022-06-04 2022-12-01 estments for Water Security gion de Diffa PISEN-2022-018 / recruteme Component 1: Integrated Inv nt d’un Comptable pour la ré IDA / V3590 A posteriori Individuel Open 18,000.00 0.00 Annulé 2022-02-18 2022-04-08 2022-04-29 2022-06-03 2022-11-30 estments for Water Security gion de Zinder PISEN-2022-021 / recruteme Component 1: Integrated Inv nt d’un Comptable pour la ré IDA / V3590 A posteriori Individuel Open 18,000.00 0.00 Annulé 2022-02-18 2022-04-08 2022-04-29 2022-06-03 2022-11-30 estments for Water Security gion de Maradi PISEN-2022-020 / recruteme Component 1: Integrated Inv nt d’un Comptable pour la ré IDA / V3590 A posteriori Individuel Open 18,000.00 0.00 Annulé 2022-02-18 2022-04-08 2022-04-29 2022-06-03 2022-11-30 estments for Water Security gion de Tahoua PISEN-2022-019 / recruteme Component 1: Integrated Inv nt d’un Comptable pour la ré IDA / V3590 A posteriori Individuel Open 18,000.00 0.00 Annulé 2022-02-19 2022-04-09 2022-04-30 2022-06-04 2022-12-01 estments for Water Security gion d'Agadez PISEN-2022-023 / recruteme Component 1: Integrated Inv nt d’un Comptable pour la ré IDA / V3590 A posteriori Individuel Open 18,000.00 0.00 Annulé 2022-02-19 2022-04-09 2022-04-30 2022-06-04 2022-12-01 estments for Water Security gion de Tillabery PISEN-2022-013 / recruteme Component 1: Integrated Inv nt d’un Assistant en Passatio IDA / V3590 A posteriori Individuel Open 18,000.00 0.00 Annulé 2022-02-19 2022-04-09 2022-04-30 2022-06-04 2022-12-01 estments for Water Security n des Marchés, pour la régio n d’Agadez PISEN-2022-010 / recruteme Component 1: Integrated Inv nt d’un Assistant en Passatio IDA / V3590 A posteriori Individuel Open 18,000.00 0.00 Annulé 2022-02-18 2022-04-08 2022-04-29 2022-06-03 2022-11-30 estments for Water Security n des Marchés, pour la régio n de Tillabéry PISEN-2022-022 / recruteme Component 1: Integrated Inv nt d’un Comptable pour la ré IDA / V3590 A posteriori Individuel Open 18,000.00 0.00 Annulé 2022-02-19 2022-04-09 2022-04-30 2022-06-04 2022-12-01 estments for Water Security gion de Dosso Page 5 PISEN-2021-024 / Consultant Individuel en qualité de spéci aliste en passation des marc IDA / V3590 A posteriori Individuel Direct 32,727.00 0.00 Annulé 2021-02-15 2021-02-15 2021-02-21 2021-02-23 2021-02-26 2021-02-26 hés pour la préparation du PI SEN (pour la période allant d u 01 janvier au 31 décembre 2021) PISEN-2021-023 / Consultant Individuel en qualité de spéci aliste environnement et socia IDA / V3590 A posteriori Individuel Direct 32,727.00 0.00 Annulé 2021-02-15 2021-02-15 2021-02-21 2021-02-23 2021-02-26 2021-02-26 l pour la préparation du PISE N (pour la période allant du 0 1 janvier au 31 décembre 20 21) PISEN-2021-037 / consultant individuel en qualité d’Exper Component 1: Integrated Inv IDA / V3590 A priori Individuel Open 302,400.00 0.00 Annulé 2021-09-14 2021-11-26 2021-11-02 2021-11-23 2021-12-28 2022-06-26 t en sauvegarde environnem estments for Water Security entale du PISEN PISEN-2021-047 / Consultant Component 1: Integrated Inv individuel en qualité de coor IDA / V3590 A posteriori Individuel Open 33,000.00 0.00 Annulé 2021-12-23 2021-12-21 2022-02-10 2022-03-03 2022-04-07 2022-10-04 estments for Water Security donnateur pour la région de Diffa PISEN-2021-048 / Consultant Component 1: Integrated Inv individuel en qualité de coor IDA / V3590 A posteriori Individuel Open 33,000.00 0.00 Annulé 2021-12-23 2021-12-21 2022-02-10 2022-03-03 2022-04-07 2022-10-04 estments for Water Security donnateur pour la région de Zinder PISEN-2021-046 / Consultant Component 1: Integrated Inv individuel en qualité de coor IDA / V3590 A posteriori Individuel Open 33,000.00 0.00 Annulé 2021-12-27 2021-12-21 2022-02-14 2022-03-07 2022-04-11 2022-10-08 estments for Water Security donnateur pour la région de Maradi PISEN-2021-045 / Consultant Component 1: Integrated Inv individuel en qualité de coor IDA / V3590 A posteriori Individuel Open 33,000.00 0.00 Annulé 2021-12-23 2021-12-21 2022-02-10 2022-03-03 2022-04-07 2022-10-04 estments for Water Security donnateur pour la région d'A gadez PISEN-2021-044 / Consultant Component 1: Integrated Inv individuel en qualité de coor IDA / V3590 A posteriori Individuel Open 33,000.00 0.00 Annulé 2021-12-23 2021-12-21 2022-02-10 2022-03-03 2022-04-07 2022-10-04 estments for Water Security donnateur pour la région de Tahoua PISEN-2021-043 / Consultant Component 1: Integrated Inv individuel en qualité de coor IDA / V3590 A posteriori Individuel Open 33,000.00 0.00 Annulé 2021-12-23 2021-12-21 2022-02-10 2022-03-03 2022-04-07 2022-10-04 estments for Water Security donnateur pour la région de Dosso PISEN-2021-042 / Consultant Component 1: Integrated Inv individuel en qualité de coor IDA / V3590 A posteriori Individuel Open 33,000.00 0.00 Annulé 2021-12-23 2021-12-21 2022-02-10 2022-03-03 2022-04-07 2022-10-04 estments for Water Security donnateur pour la région de Tillabery PISEN-2021-041 / Consultant Component 1: Integrated Inv individuel en qualité de comp IDA / V3590 A posteriori Individuel Open 302,400.00 0.00 Annulé 2021-10-14 2021-09-29 2021-12-02 2021-12-23 2022-01-27 2022-07-26 estments for Water Security table principal PISEN-2021-040 / Consultant Component 1: Integrated Inv individuel en qualité d’expert IDA / V3590 A posteriori Individuel Open 302,400.00 0.00 Annulé 2021-10-15 2021-09-29 2021-12-03 2021-12-24 2022-01-28 2022-07-27 estments for Water Security en suivi et évaluation du PISE N PISEN-2021-038 / Consultant Component 1: Integrated Inv individuel en qualité de Spéci IDA / V3590 A posteriori Individuel Open 302,400.00 0.00 Annulé 2021-10-15 2021-09-29 2021-12-03 2021-12-24 2022-01-28 2022-07-27 estments for Water Security aliste en Passation des March és du PISEN NE-IWSP-PPA IU-315262-CS-I NDV / Sélection d'un consulta Component 3: Project Manag Open - Internationa En cours d'exécut nt pour une formation group IDA / D9080 A posteriori Individuel 18,000.00 0.00 2022-11-24 2022-12-20 2023-01-12 2023-02-02 2023-03-09 2023-09-05 ement and Capacity Building l ion ée en passation de marchés au personnel de l'UCP PISEN NE-IWSP-PPA IU-315263-CS-I NDV / Formation groupée sur Component 3: Project Manag En attente d'exéc IDA / D9080 A posteriori Individuel Limited 5,000.00 0.00 2022-10-10 2022-10-15 2022-11-05 2022-12-10 2023-06-08 le manuel de procédures (MO ement and Capacity Building ution P) à l'endroit du Personnel de l'UCP PISEN NE-PISEN-344907-CS-INDV / Recrutement d'un consultant Component 1: Integrated Inv En attente d'exéc individuel pour la réalisation IDA / D9080 A posteriori Individuel Open - National 45,455.00 0.00 2023-03-15 2023-05-03 2023-05-24 2023-06-28 2023-12-25 estments for Water Security ution des études EIES/PAR pour la construction des sièges des a gences des sous bassins NE-PISEN-346550-CS-INDV / Recrutement d'un consultant Component 3: Project Manag En attente d'exéc IDA / D9080 A posteriori Individuel Open - National 27,273.00 0.00 2023-04-10 2023-05-29 2023-06-19 2023-07-24 2024-01-20 pour la formation sur le logici ement and Capacity Building ution el de suivi évaluation (format ion GEMS) NE-PISEN-346061-CS-INDV / Recrutement d'un consultant Component 1: Integrated Inv En attente d'exéc individuel pour la formation 5 IDA / D9080 A posteriori Individuel Limited 9,091.00 0.00 2023-04-10 2023-04-15 2023-05-06 2023-06-10 2023-12-07 estments for Water Security ution S KAIZEN appliquée à la GIRE et à la gestion des écosystè mes NE-PISEN-346538-CS-INDV / Recrutement d'un consultant pour les études EIES/PAR des Component 1: Integrated Inv Open - Internationa En attente d'exéc travaux d'hydraulique rurale IDA / D9080 A posteriori Individuel 109,094.00 0.00 2023-03-29 2023-05-17 2023-06-07 2023-07-12 2024-01-08 estments for Water Security l ution et d'assainissement dans les zones de Tillabéry, Dosso, Ta houa et Agadez des quatre ( 4) sous bassins couverts par le PISEN NE-PISEN-346540-CS-INDV / Recrutement d'un consultant pour les études EIES/PAR des Component 1: Integrated Inv travaux d'hydraulique rurale IDA / D9080 A posteriori Individuel Open - National 72,727.00 0.00 Annulé 2023-04-10 2023-10-05 2023-05-29 2023-06-19 2023-07-24 2024-01-20 estments for Water Security et d'assainissement dans les zones de Maradi, Zinder et Di ffa des trois (3) sous bassins couverts par le PISEN Page 6