PROCUREMENT PLAN (Textual Part) Project information: Angola, Electricity Sector Improvement Project (P166805) Project Implementation agency: Ministry of Energy and Water - GEPE Date of the Procurement Plan: 24 July 2019 Period covered by this Procurement Plan: July 2019 to 30 June 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used, once and if approved by the World Bank. When the Borrower uses its own national open competitive procurement arrangements as set forth in Law No. 9/16 dated 16 June (Lei dos Contratos Públicos), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and additional conditions acceptable to and agreed with the World Bank. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables. PROCUREMENT Angola : Angola - Electricity Sector Improvement and Access Project PLAN General Information Country: Angola 2019-07-25 Bank’s Approval Date of the Original Procurement Plan: 2024-02-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166805 GPN Date: 2021-06-22 Project Name: Angola - Electricity Sector Improvement and Access Project Loan / Credit No: IBRD / P4990, IBRD / 92040 Ministry of Energy and Water - GEPE Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned AO-MINEA - GEPE-210427-C Electricity service improvem Open - Internationa Single Stage - One E 33,250,000.0 Pending Imp 2024-01-3 W-RFB / Rehabilitation and u IBRD / P4990 Prior Request for Bids 0.00 2022-04-03 2022-04-08 2022-05-20 2022-07-04 2022-08-08 ent l nvelope 0 lementation 0 pgrade of Quileva and Cuito substations AO-MINEA - GEPE-210432-C W-RFB / Construction of Nati onal Control Centre (primary and backup), Market Operato Electricity service improvem Open - Internationa Single Stage - One E 40,500,000.0 Pending Imp 2024-08-1 IBRD / P4990 Prior Request for Bids 0.00 2022-04-08 2022-04-13 2022-05-25 2022-07-09 2022-08-13 r and supporting offices, inst ent l nvelope 0 lementation 2 allation of SCADA System an d upgrade of local substation automation systems and sup ply and installation of meters at border points AO-MINEA - GEPE-210439-C W-RFB / Construction of Prim ary and Backup Datacentres Electricity service improvem Open - Internationa Single Stage - One E Pending Imp 2024-08-2 IBRD / P4990 Post Request for Bids 2,750,000.00 0.00 2022-04-17 2022-04-22 2022-06-03 2022-07-18 2022-08-22 (Disaster Recovery Backup D ent l nvelope lementation 1 ata Centre and upgrade of ex isting Data Centre infrastruct ure and Systems) AO-MINEA - GEPE-210434-C Electricity service improvem Open - Internationa Single Stage - One E 24,700,000.0 Pending Imp 2024-10-0 W-RFB / Expansion and upgra IBRD / P4990 Prior Request for Bids 0.00 2022-06-01 2022-06-06 2022-07-18 2022-09-01 2022-10-06 ent l nvelope 0 lementation 5 de of the telecommunication network AO-MINEA - GEPE-396624-C W-RFB / EPC for Civil works - Electricity access expansion Request for Bids - Rehabilitation and expansion Open - Internationa Single Stage - Two E 235,710,000. Under Imple 2027-01-0 IBRD / 92040 and improvement of revenu Prior Request for Bids Works SPD (after 0.00 2024-02-05 2024-05-09 2024-05-24 2024-02-09 2024-08-02 2024-10-17 2024-11-07 of Distribution Networks - Pa l nvelope 00 mentation 6 e collection prequalification) ckages A (Luanda-Benguela), B (Luanda-Huambo) and C (L uanda-Lubango) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AO-MINEA - GEPE-210044-G Electricity access expansion O-RFB / Supply and Installati Open - Internationa Single Stage - One E Under Imple IBRD / P4990 and improvement of revenu Prior Request for Bids 7,000,000.00 0.00 2021-09-20 2022-09-19 2021-10-05 2022-11-03 2021-11-24 2023-04-20 2021-12-24 2023-10-25 2022-01-28 2023-04-28 on of meters and meter contr l nvelope mentation e collection ol center for the RRP (Reven ue Protection Program) AO-MINEA - GEPE-210374-G Improvement of PRODEL’s c O-RFB / Supply and installati apacity and strengthening s Open - Internationa Single Stage - One E Pending Impl IBRD / P4990 Post Request for Bids 2,000,000.00 0.00 2022-06-23 2022-06-28 2022-08-09 2022-09-08 2022-10-13 2023-04-11 on of dam safety monitoring ustainable management of g l nvelope ementation equipment, software and trai eneration plants ning AO-MINEA - GEPE-210380-G Improvement of PRODEL’s c O-RFB / Supply and installati apacity and strengthening s Open - Internationa Single Stage - One E Pending Impl IBRD / P4990 Post Request for Bids 1,000,000.00 0.00 2022-06-30 2022-07-05 2022-08-16 2022-09-15 2022-10-20 2023-04-18 on of hydro-meteorological m ustainable management of g l nvelope ementation onitoring equipment and trai eneration plants ning Improvement of PRODEL’s c AO-MINEA - GEPE-210382-G apacity and strengthening s Open - Internationa Single Stage - One E Pending Impl O-RFB / Supply of special tool IBRD / P4990 Post Request for Bids 500,000.00 0.00 2022-06-15 2022-06-20 2022-08-01 2022-08-31 2022-10-05 2023-04-03 ustainable management of g l nvelope ementation s for maintenance (O&M) eneration plants AO-MINEA - GEPE-210385-G Improvement of PRODEL’s c O-RFB / Supply and installati apacity and strengthening s Open - Internationa Single Stage - One E Pending Impl IBRD / P4990 Post Request for Bids 1,000,000.00 0.00 2022-06-13 2022-06-18 2022-07-30 2022-08-29 2022-10-03 2023-04-01 on of equipment to upgrade t ustainable management of g l nvelope ementation raining facilities in Lauca eneration plants AO-MINEA - GEPE-210440-G O-RFB / Supply and training o f Engineering and project ma Electricity service improvem Open - Internationa Single Stage - One E nagement software, software IBRD / P4990 Post Request for Bids 1,250,000.00 0.00 Canceled 2021-06-01 2023-05-21 2021-06-06 2023-05-26 2021-07-18 2023-07-06 2021-09-01 2023-10-10 2021-10-06 2022-07-03 ent l nvelope for power system planning, s oftware for operational studi es, software for managing an d controlling hydrothermal g eneration AO-MINEA - GEPE-210377-G Improvement of PRODEL’s c O-RFB / Supply and installati apacity and strengthening s Open - Internationa Single Stage - One E Pending Impl on of generation monitoring IBRD / P4990 Prior Request for Bids 7,000,000.00 0.00 2021-06-15 2021-06-20 2021-08-01 2021-08-31 2021-10-05 2022-04-03 ustainable management of g l nvelope ementation centre and data platform (da eneration plants ta centre and equipment) AO-MINEA - GEPE-210441-G O-RFB / Supply and installati Electricity service improvem Open - Internationa Single Stage - One E Pending Impl IBRD / P4990 Post Request for Bids 2,000,000.00 0.00 2021-09-01 2021-09-06 2021-10-18 2021-12-02 2022-01-06 2023-04-01 on of Primary and Backup Da ent l nvelope ementation tacentres software AO-MINEA - GEPE-210443-G O-RFB / Upgrade of the actua Electricity service improvem Open - Internationa Single Stage - One E Pending Impl IBRD / P4990 Post Request for Bids 1,490,000.00 0.00 2021-09-06 2021-09-11 2021-10-23 2021-12-07 2022-01-11 2023-04-06 l Management Support Syste ent l nvelope ementation ms to RNT-EP's Business Proc esses and training AO-MINEA - GEPE-210386-G Improvement of PRODEL’s c O-RFB / Supply of O&M softw apacity and strengthening s Open - Internationa Single Stage - One E Pending Impl IBRD / P4990 Post Request for Bids 1,500,000.00 0.00 2022-06-06 2022-06-11 2022-07-23 2022-08-22 2022-09-26 2023-03-25 are for Lauca and Luachimo ustainable management of g l nvelope ementation dams eneration plants Page 1 AO-MINEA - GEPE-210442-G O-RFB / Upgrade, Licensing a Electricity service improvem Open - Internationa Single Stage - One E Pending Impl IBRD / P4990 Post Request for Bids 2,710,000.00 0.00 2021-09-08 2021-09-13 2021-10-25 2021-12-09 2022-01-13 2023-04-08 nd Support of the Informatio ent l nvelope ementation n and communication techno logy Systems AO-MINEA - GEPE-210444-G Electricity service improvem Open - Internationa Single Stage - One E O-RFB / Maintenance Manage IBRD / P4990 Post Request for Bids 250,000.00 0.00 Canceled 2021-06-02 2023-05-21 2021-06-07 2023-05-26 2021-07-19 2023-07-06 2021-09-02 2023-09-29 2021-10-07 2022-07-04 ent l nvelope ment Tool (Portal RNT + Shar epoint AO-MINEA - GEPE-210373-G Improvement of PRODEL’s c O-RFB / Purchase of hardwar apacity and strengthening s Open - Internationa Single Stage - One E Pending Impl e computers, customization, IBRD / P4990 Prior Request for Bids 5,000,000.00 0.00 2022-06-23 2022-06-28 2022-08-09 2022-09-08 2022-10-13 2023-04-11 ustainable management of g l nvelope ementation software licensing and trainin eneration plants g for the upgrade of the ERP MINIMAL AO-MINEA - GEPE-297767-G Project management suppor Request for Quota Single Stage - One E Under Imple O-RFQ / Supply of Informatio IBRD / 92040 Post Limited 70,000.00 0.00 2022-07-22 2023-02-08 2022-09-16 2023-03-15 t tions nvelope mentation n Technology Equipment AO-MINEA - GEPE-297763-G Project management suppor Request for Quota Single Stage - One E Pending Impl O-RFQ / Purchase of three 4x IBRD / 92040 Post Limited 225,000.00 0.00 2022-08-06 2022-10-01 2023-01-29 t tions nvelope ementation 4 all-terrain vehicle AO-MINEA - GEPE-297771-C Project management suppor Request for Quota Single Stage - One E Pending Impl S-QCBS / Supply, installation IBRD / 92040 Post Limited 75,000.00 0.00 2022-09-10 2022-11-05 2023-05-04 t tions nvelope ementation of computerized accounting s oftware AO-MINEA - GEPE-368703-G O-DIR / Procurement of IT Eq Project management suppor Under Imple uipment and Supply for the i IBRD / 92040 Post Direct Selection Direct - National 15,000.00 0.00 2023-07-10 2023-07-11 2023-07-15 2023-07-14 2023-08-09 2024-08-08 t mentation nstallation of a Server at Proj ect Coordinating Unit Office t o support the ESIAP Project NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AO-MINEA - GEPE-297776-N C-RFB / Supply and installatio Electricity service improvem Open - Internationa Single Stage - One E Under Imple IBRD / 92040 Prior Request for Bids 2,116,300.00 0.00 2022-07-27 2023-05-24 2022-08-01 2023-05-30 2022-09-12 2022-10-12 2022-11-16 2023-05-15 n of a Geospatial Network Inf ent l nvelope mentation ormation System CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AO-MINEA - GEPE-210094-C S-QCBS / Consulting firm (Ow ner's Engineer) to support PR Improvement of PRODEL’s c ODEL in preparation of techni apacity and strengthening s Quality And Cost- Open - Internationa Under Implement cal specifications, bidding do IBRD / P4990 Prior 4,000,000.00 0.00 2022-01-09 2022-08-18 2022-02-08 2022-08-29 2022-04-14 2023-10-31 2022-05-14 2022-06-28 2022-08-17 2022-09-21 2023-09-21 ustainable management of g Based Selection l ation cuments, bid evaluation repo eneration plants rts and supervision of imple mentation of generation mo nitoring centre, dam safety e quipment and O&M software AO-MINEA - GEPE-210364-C S-QCBS / Consulting firm to p Improvement of PRODEL’s c rovide PRODEL with corporat apacity and strengthening s Quality And Cost- Under Implement IBRD / P4990 Post 2,000,000.00 0.00 2021-09-10 2022-08-19 2021-10-10 2022-08-29 2021-12-14 2023-09-14 2022-01-13 2022-02-27 2022-04-18 2022-05-23 2022-11-19 e advisory services and supe ustainable management of g Based Selection ation rvision of implementation of eneration plants ERP (Upgrade of MINIMAL) in stallation AO-MINEA - GEPE-210372-C Improvement of PRODEL’s c S-QCBS / Corporate and tech apacity and strengthening s Quality And Cost- Open - Internationa Pending Impleme IBRD / P4990 Post 2,000,000.00 0.00 2021-09-15 2021-10-15 2021-12-29 2022-01-28 2022-03-14 2022-05-03 2022-06-07 2023-06-07 nical training (HR, Finance, P ustainable management of g Based Selection l ntation rocurement, etc) eneration plants AO-MINEA - GEPE-210406-C S-QCBS / Owner's Engineer fi rm to design, prepare biddin g documents to contract the Electricity service improvem Quality And Cost- Open - Internationa Under Implement EPC and supervise the Constr IBRD / P4990 Post 2,250,000.00 0.00 2021-05-24 2022-08-22 2021-06-23 2022-08-29 2021-08-27 2021-09-26 2021-11-10 2021-12-30 2022-02-03 2024-05-03 ent Based Selection l ation uction of the National Control Centre (main and backup), M arket Operator and supportin g offices, installation of SCAD A System and Upgrade of loc al sub AO-MINEA - GEPE-210416-C S-QCBS / Consultant firm pre pare the RNT's IT Strategic pl an and support the client dur Electricity service improvem Quality And Cost- Open - Internationa Pending Impleme IBRD / P4990 Post 450,000.00 0.00 2021-06-01 2021-07-01 2021-09-04 2021-10-04 2021-11-18 2022-01-22 2022-02-26 2023-08-20 ing the upgrade and customi ent Based Selection l ntation zation of the Modules of the " MINIMAL" ERP and installatio n of Primary and Backup Dat acentres software AO-MINEA - GEPE-210422-C S-QCBS / Consulting firm to c Electricity service improvem Quality And Cost- Open - Internationa Under Implement arry out feasibility study for t IBRD / P4990 Post 3,500,000.00 0.00 2021-06-10 2021-08-10 2021-07-10 2021-10-24 2021-09-13 2023-06-16 2021-10-13 2023-08-03 2021-11-27 2022-01-07 2022-02-11 2023-08-05 ent Based Selection l ation he expansion of the Network (Eastern connection to North ern) AO-MINEA - GEPE-210424-C S-QCBS / Consulting firm to c Electricity service improvem Quality And Cost- Open - Internationa Under Implement IBRD / P4990 Post 1,500,000.00 0.00 2021-06-10 2022-08-31 2021-07-10 2022-11-03 2021-09-13 2021-10-13 2021-11-27 2022-01-31 2022-03-07 2023-08-29 arry out feasibility studies for ent Based Selection l ation the expansion of the Cabinda Network AO-MINEA - GEPE-210420-C S-QCBS / Consulting firm to p Electricity service improvem Quality And Cost- Open - Internationa Under Implement IBRD / P4990 Post 1,500,000.00 0.00 2021-06-08 2022-04-12 2021-07-08 2022-08-15 2021-09-11 2021-10-11 2021-11-25 2022-01-29 2022-03-05 2023-08-27 repare and implement the ca ent Based Selection l ation pacity building plan for RNT s taff Page 2 AO-MINEA - GEPE-210411-C S-QCBS / Owner's Engineer fi rm to design, prepare biddin Electricity service improvem Quality And Cost- Open - Internationa Pending Impleme IBRD / P4990 Post 1,300,000.00 0.00 2021-06-27 2021-07-27 2021-09-30 2021-10-30 2021-12-14 2022-02-17 2022-03-24 2024-06-21 g documents to contract the ent Based Selection l ntation EPC and supervise Expansion and upgrade of the telecom munication network AO-MINEA - GEPE-210063-C S-QCBS / Owner's Engineer f Electricity access expansion or revision of preliminary des Quality And Cost- Open - Internationa Under Implement IBRD / P4990 and improvement of revenu Prior 2,430,000.00 0.00 2021-04-15 2021-05-15 2021-07-19 2021-08-18 2021-10-02 2021-11-21 2021-12-26 2024-03-25 ign and supervision of works Based Selection l ation e collection for distribution networks reh abilitation and expansion - Pa ckage B AO-MINEA - GEPE-210079-C S-QCBS / Owner's Engineer f Electricity access expansion or revision of preliminary des Quality And Cost- Open - Internationa Under Implement IBRD / P4990 and improvement of revenu Prior 2,430,000.00 0.00 2021-04-15 2021-05-15 2021-07-19 2021-08-18 2021-10-02 2021-11-21 2021-12-26 2024-03-25 ign and supervision of works Based Selection l ation e collection for distribution networks reh abilitation and expansion - Pa ckage C AO-MINEA - GEPE-210060-C S-QCBS / Owner's Engineer f Electricity access expansion or revision of preliminary des Quality And Cost- Open - Internationa Under Implement IBRD / P4990 and improvement of revenu Prior 2,430,000.00 0.00 2021-04-15 2021-05-15 2021-07-19 2021-08-18 2021-10-02 2021-11-21 2021-12-26 2024-03-25 ign and supervision of works Based Selection l ation e collection for distribution networks reh abilitation and expansion - Pa ckage A AO-MINEA - GEPE-286055-C Project management suppor Least Cost Selecti Open - Internationa Under Implement IBRD / 92040 Post 140,000.00 0.00 2022-03-31 2022-03-23 2022-04-21 2022-07-11 2022-06-04 2023-03-13 2022-07-02 2023-04-17 2022-08-01 2023-05-31 2022-09-05 2023-06-14 2022-10-10 2024-12-31 S-LCS / External Auditor of th t on l ation e Project AO-MINEA - GEPE-297806-C Project management suppor Quality And Cost- Open - Internationa Under Implement S-QCBS / Master Plan for the IBRD / 92040 Prior 1,050,000.00 0.00 2022-09-05 2022-08-22 2022-09-26 2022-08-29 2022-11-09 2023-10-31 2022-12-07 2023-01-06 2023-02-10 2023-03-17 2024-03-16 t Based Selection l ation Angolan Electrical System AO-MINEA - GEPE-297814-C S-QBS / Consulting firm to pr epare the preliminary design Electricity service improvem Quality Based Sel Open - Internationa Under Implement IBRD / 92040 Prior 1,330,000.00 0.00 2022-09-15 2022-08-22 2022-10-06 2022-08-29 2022-11-19 2023-11-30 2022-12-17 2023-01-16 2023-02-15 2023-03-22 2024-03-21 and Bidding Documents for r ent ection l ation ehabilitation and upgrade of Cuito and Quileva substation s. AO-MINEA - GEPE-210392-C S-QCBS / Owner's Engineer fi Electricity service improvem Quality And Cost- Open - Internationa Under Implement rm to supervise the works for IBRD / 92040 Prior 1,750,000.00 0.00 2023-01-09 2022-08-15 2023-02-08 2022-08-29 2023-04-14 2023-11-21 2023-05-14 2023-06-28 2023-08-17 2023-09-21 2024-07-17 ent Based Selection l ation rehabilitation and upgrade of Cuito and Quileva substation s AO-MINEA - GEPE-309125-C S-QCBS / Management and s upervision Consultant firm - Electricity service improvem Quality And Cost- Open - Internationa Under Implement Construction of the National IBRD / 92040 Prior 1,956,000.00 0.00 2022-10-03 2023-06-19 2022-10-24 2022-12-07 2023-01-04 2023-02-03 2023-03-10 2023-04-14 2024-08-06 ent Based Selection l ation Control Centre, upgrade of th e telecommunication networ k and implementation of adv anced metering infrastructur e AO-MINEA - GEPE-366311-C S-QCBS / Development and I mplementation of a "Sensitiz Project management suppor Quality And Cost- Open - Internationa Pending Impleme IBRD / P4990 Post 400,000.00 0.00 2023-06-16 2023-07-07 2023-08-20 2023-09-17 2023-10-08 2023-10-20 2023-11-17 2025-05-20 ation and Education Strategy t Based Selection l ntation and Energy literacy targeting women and vulnerable group s". AO-MINEA - GEPE-396609-C S-CQS / Consulting Firm to pr epare the Simplified Environ mental and Social Study aimi Project management suppor Consultant Qualifi Under Implement IBRD / 92040 Post Limited 286,000.00 0.00 2023-12-11 2023-12-07 2024-01-25 2024-02-01 2024-02-22 2024-05-22 ng at the rehabilitation and e t cation Selection ation xpansion of energy distributi on networks in 4 provincial c apitals (Luanda, Benguela, H uambo and Lubango). AO-MINEA - GEPE-396618-C S-QCBS / Owner's Engineer f or review and approval of EP Electricity access expansion C's design and supervision of Quality And Cost- Open - Internationa IBRD / 92040 and improvement of revenu Prior 7,290,000.00 0.00 Under Review 2023-12-13 2023-12-20 2024-01-03 2024-02-21 2024-04-22 2024-05-22 2024-07-05 2024-07-26 2026-09-24 works for distribution networ Based Selection l e collection ks rehabilitation and expansi on - Packages A (Luanda-Ben guela), B (Luanda-Huambo) a nd C (Luanda-Lubango) AO-MINEA - GEPE-403827-C Electricity service improvem Quality And Cost- Open - Internationa Under Implement S-QCBS / Feasibility Study of IBRD / 92040 Prior 1,500,000.00 0.00 2024-02-02 2024-01-19 2024-03-04 2024-02-03 2024-04-17 2024-06-04 2024-07-05 2024-08-04 2024-08-26 2025-10-20 ent Based Selection l ation Cunene Transmission System Project (CTS) AO-MINEA - GEPE-407776-C S-LCS / Consulting Firm to pr Project management suppor Least Cost Selecti Pending Impleme ovide Translation and Interpr IBRD / 92040 Post Open - National 655,700.00 0.00 2024-02-08 2024-02-26 2024-03-20 2024-04-30 2024-05-21 2024-06-25 2024-07-16 2026-07-06 t on ntation etation services (Portuguese/ English/Portuguese to the ESI AP Project Coordination Unit INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AO-MINEA - GEPE-123486-C S-INDV / Short-term Environ Project management suppor Individual Consult mental Consultant (for prepa IBRD / P4990 Post Limited 70,000.00 110,837.99 Signed 2019-07-28 2019-07-25 2019-08-02 2019-08-01 2019-08-22 2019-08-25 2019-08-30 2019-11-15 2019-10-29 t ant Selection ration of Environmental and Social Management Framewo rk - ESMF) AO-MINEA - GEPE-144993-C Improvement of PRODEL’s c S-INDV / Project Coordinator ( apacity and strengthening s Individual Consult IBRD / P4990 Prior Open 240,000.00 535,646.42 Signed 2019-11-18 2019-11-14 2020-01-18 2020-02-21 2020-02-08 2020-07-21 2020-03-14 2020-08-14 2021-06-07 Lead Staff, Project Coordinati ustainable management of g ant Selection on Unit - PCU) eneration plants Improvement of PRODEL’s c AO-MINEA - GEPE-145487-C apacity and strengthening s Individual Consult S-INDV / Procurement Special IBRD / P4990 Prior Open 230,000.00 298,636.90 Signed 2019-11-18 2019-11-14 2020-01-18 2020-02-21 2020-02-08 2020-07-07 2020-03-14 2020-08-09 2021-06-07 ustainable management of g ant Selection ist eneration plants Page 3 Improvement of PRODEL’s c AO-MINEA - GEPE-145488-C apacity and strengthening s Individual Consult S-INDV / Financial Manageme IBRD / P4990 Prior Open 155,000.00 281,500.00 Signed 2019-11-18 2019-11-13 2020-01-18 2020-02-21 2020-02-08 2020-07-21 2020-03-14 2020-08-20 2021-06-07 ustainable management of g ant Selection nt Specialist eneration plants Improvement of PRODEL’s c AO-MINEA - GEPE-191630-C apacity and strengthening s Individual Consult S-INDV / Social Safeguard Sp IBRD / P4990 Post Open 175,000.00 0.00 Canceled 2020-09-21 2020-09-24 2020-12-05 2020-12-26 2021-01-29 2022-01-29 ustainable management of g ant Selection ecialist eneration plants Improvement of PRODEL’s c AO-MINEA - GEPE-191639-C apacity and strengthening s Individual Consult S-INDV / Environmental Speci IBRD / P4990 Post Open 175,000.00 0.00 Canceled 2020-09-21 2020-09-16 2020-12-05 2020-12-26 2021-01-30 2022-04-25 ustainable management of g ant Selection alist eneration plants Improvement of PRODEL’s c AO-MINEA - GEPE-191619-C apacity and strengthening s Individual Consult S-INDV / Junior Procurement IBRD / P4990 Prior Limited 120,000.00 0.00 Canceled 2020-09-10 2020-11-03 2020-11-17 2021-01-07 2022-01-07 ustainable management of g ant Selection Specialist eneration plants AO-MINEA - GEPE-210042-C S-INDV / Individual consultan Project management suppor Individual Consult Pending Impleme t to assist in preparation of bi IBRD / P4990 Post Open 50,000.00 0.00 2021-02-08 2021-04-24 2021-05-15 2021-06-19 2021-09-17 t ant Selection ntation dding documents and bid ev aluation reports for the RPP ( Revenue Protection Program) AO-MINEA - GEPE-210045-C S-INDV / Individual consultan t to assist in preparation of bi Project management suppor Individual Consult Pending Impleme IBRD / P4990 Post Open 50,000.00 0.00 2021-01-11 2021-03-27 2021-04-17 2021-05-22 2021-11-18 dding documents and bid ev t ant Selection ntation aluation reports for the distri bution networks rehabilitatio n and expansion projects AO-MINEA - GEPE-210361-C S-INDV / Individual consultan Project management suppor Individual Consult Pending Impleme IBRD / P4990 Post Open 50,000.00 0.00 2021-01-25 2021-04-10 2021-05-01 2021-06-05 2021-09-03 t to prepare terms of referen t ant Selection ntation ce for the corporate advisory services AO-MINEA - GEPE-216418-C Project management suppor Individual Consult IBRD / P4990 Post 120,000.00 0.00 Canceled 2021-01-29 2021-03-31 2021-03-24 2021-04-14 2021-05-19 2022-05-19 S-INDV / Project Accountant t ant Selection AO-MINEA - GEPE-198004-C S-CDS / Technical training to IRSEA by MRC Consultants so Improvement of PRODEL’s c that it will be able to fulfil its apacity and strengthening s IBRD / P4990 Prior Direct Selection Direct 60,000.00 0.00 Canceled 2020-10-09 2020-10-19 2020-12-23 2021-06-21 enhanced role in the implem ustainable management of g entation of the Presidential D eneration plants ecree No 178/20 of 25 June 2 020, for establishing, and per iodically adjusting, revenue r equirements. Improvement of PRODEL’s c AO-MINEA - GEPE-204622-C apacity and strengthening s Individual Consult S-INDV / Procurement Special IBRD / P4990 Prior Limited 120,000.00 0.00 Canceled 2020-11-12 2021-01-21 2021-01-05 2021-01-19 2021-02-07 2021-08-06 ustainable management of g ant Selection ist eneration plants AO-MINEA - GEPE-226466-C Project management suppor Individual Consult S-INDV / Technical Specialist/ IBRD / P4990 Post Open 200,000.00 0.00 Canceled 2021-03-31 2021-06-23 2021-07-07 2021-07-28 2021-09-01 2022-09-01 t ant Selection Transmission Engineer (PCU Staff) AO-MINEA - GEPE-224718-C Project management suppor Individual Consult IBRD / P4990 Prior Open 120,000.00 0.00 Canceled 2021-05-17 2021-08-21 2021-09-11 2021-10-16 2022-10-16 S-INDV / Procurement Special t ant Selection ist AO-MINEA - GEPE-226474-C S-CDS / Technical Training to Project management suppor IBRD / P4990 Post Direct Selection Direct 60,000.00 0.00 Signed 2021-06-20 2021-06-24 2021-07-11 2022-06-21 2021-09-14 2023-02-23 2022-01-12 IRSEA for the implementation t of the Presidential Decree No . 178/20. AO-MINEA - GEPE-241638-C S-INDV / Selection of the Seni Project management suppor Individual Consult IBRD / P4990 Post Open 155,000.00 163,035.76 Signed 2021-07-12 2021-06-30 2021-09-18 2022-01-06 2021-10-09 2022-02-07 2021-11-13 2022-03-19 2022-11-13 or Management Financial Sp t ant Selection ecialist for the PCU. AO-MINEA - GEPE-191630-C Project management suppor Individual Consult S-INDV-2 / Senior Social and IBRD / 92040 Post Open 175,000.00 162,210.76 Signed 2021-10-15 2021-10-06 2021-12-29 2022-02-17 2022-01-19 2022-02-17 2022-02-22 2022-03-12 2023-02-22 t ant Selection Gender Risk Management Sp ecialist AO-MINEA - GEPE-257489-C Project management suppor Individual Consult S-INDV / Senior Environment IBRD / P4990 Post Open 175,000.00 134,842.28 Signed 2021-10-15 2021-10-20 2021-12-29 2022-02-14 2022-01-19 2022-02-16 2022-02-23 2022-03-25 2023-05-19 t ant Selection al Specialist AO-MINEA - GEPE-287279-C Project management suppor Individual Consult IBRD / 92040 Prior Open 230,000.00 0.00 Canceled 2022-06-15 2022-06-17 2022-09-19 2022-09-27 2022-10-10 2022-11-14 2023-11-14 S-INDV / Senior Procurement t ant Selection Specialist AO-MINEA - GEPE-224718-C Project management suppor Individual Consult S-INDV-2 / SENIOR PROCURE IBRD / P4990 Post Open 230,000.00 0.00 Canceled 2021-06-13 2021-06-10 2021-09-17 2021-10-08 2021-11-12 2022-11-12 t ant Selection MENT SPECIALIST AO-MINEA - GEPE-297766-C Project management suppor Individual Consult S-INDV / Administrative Assis IBRD / 92040 Post Limited 30,000.00 0.00 Signed 2022-06-30 2022-06-22 2022-07-05 2022-10-19 2022-07-26 2022-10-20 2022-08-30 2023-02-23 2023-02-26 t ant Selection tant for the PCU AO-MINEA - GEPE-297768-C Project management suppor Individual Consult Pending Impleme S-INDV / Information Technol IBRD / 92040 Post Open 45,000.00 0.00 2022-07-31 2022-09-18 2022-10-09 2022-11-13 2023-05-12 t ant Selection ntation ogy Specialist AO-MINEA - GEPE-226461-C Project management suppor Individual Consult S-INDV / Technical Specialist/ IBRD / P4990 Post Open 200,000.00 0.00 Canceled 2021-03-30 2021-11-22 2021-06-30 2021-07-21 2021-08-25 2022-08-25 t ant Selection Distribution Engineer (PCU st aff) AO-MINEA - GEPE-210085-C Improvement of PRODEL’s c S-INDV / Individual consultan apacity and strengthening s Individual Consult IBRD / P4990 Post Open 50,000.00 0.00 Canceled 2021-04-05 2021-11-22 2021-06-19 2021-07-10 2021-08-14 2021-11-12 t to prepare terms of referen ustainable management of g ant Selection ce for the Owner's Engineer eneration plants AO-MINEA - GEPE-298252-C Project management suppor Individual Consult Under Implement S-INDV / Technical Specialist/ IBRD / 92040 Post Open 200,000.00 0.00 2022-07-30 2022-06-08 2022-09-17 2022-10-08 2022-11-12 2023-11-12 t ant Selection ation Distribution Engineer (PCU st aff) AO-MINEA - GEPE-298244-C Improvement of PRODEL’s c S-INDV / Individual Consultan apacity and strengthening s Individual Consult Pending Impleme IBRD / 92040 Post Open 50,000.00 0.00 2022-08-08 2022-09-26 2022-10-17 2022-11-21 2023-07-19 t to prepare the Terms of Ref ustainable management of g ant Selection ntation erence for the selection of th eneration plants e Owner's Engineer. Page 4 AO-MINEA - GEPE-300359-C Project management suppor Individual Consult IBRD / 92040 Prior Open 120,000.00 0.00 Signed 2022-07-17 2022-06-24 2022-09-04 2023-03-20 2022-09-25 2023-05-02 2022-10-30 2023-05-23 2023-10-30 S-INDV / Procurement Officer t ant Selection Improvement of PRODEL’s c AO-MINEA - GEPE-303244-C apacity and strengthening s Individual Consult S-INDV / Coordinator for the IBRD / P4990 Post Open 200,000.00 0.00 Signed 2022-08-31 2022-07-08 2022-10-31 2023-02-10 2022-11-21 2023-02-22 2022-12-26 2023-03-11 2023-12-21 ustainable management of g ant Selection Project Coordination Unit eneration plants AO-MINEA - GEPE-321848-C Project management suppor Individual Consult Direct - Internation IBRD / 92040 Prior 200,000.00 0.00 Signed 2022-11-01 2022-10-20 2022-11-11 2022-11-25 2022-12-02 2023-01-13 2023-01-06 2023-02-17 2024-01-01 S-INDV / Senior Procurement t ant Selection al Specialist AO-MINEA - GEPE-321854-C Project management suppor Individual Consult Direct - Internation IBRD / 92040 Post 100,000.00 0.00 Canceled 2022-11-10 2022-10-20 2022-11-20 2022-11-04 2022-12-11 2023-01-15 2023-07-14 S-INDV / Procurement Consul t ant Selection al tant Expert AO-MINEA - GEPE-368689-C Project management suppor Individual Consult Under Implement S-INDV / Employment of a Pr IBRD / 92040 Prior Open - National 100,000.00 0.00 2023-07-17 2023-08-23 2023-08-27 2023-09-17 2023-10-11 2024-10-10 t ant Selection ation ocurement Officer AO-MINEA - GEPE-368698-C S-INDV / Employment of Seni Project management suppor Individual Consult Open - Internationa Under Implement IBRD / 92040 Post 175,000.00 0.00 2023-07-14 2023-07-20 2023-09-01 2023-09-15 2023-10-06 2024-10-12 or Social and Gender Risk Ma t ant Selection l ation nagement Specialist AO-MINEA - GEPE-369774-C S-INDV / Selection of Technic al Specialist - Distribution En Project management suppor Individual Consult Open - Internationa Under Implement gineer to support the Project IBRD / 92040 Post 200,000.00 0.00 2023-06-30 2023-08-07 2023-08-18 2023-09-08 2023-10-13 2024-04-10 t ant Selection l ation Coordinating Unit and three Utilities in implementing the Electricity Sector Improveme nt Access Project AO-MINEA - GEPE-368694-C Project management suppor Individual Consult Open - Internationa S-INDV / Employment of a Pr IBRD / 92040 Post 180,000.00 0.00 Canceled 2023-07-12 2023-08-22 2023-09-01 2023-09-23 2024-03-21 t ant Selection l ocurement Consultant to ESI AP Project AO-MINEA - GEPE-378740-C Project management suppor Individual Consult Direct - Internation Under Implement S-INDV / Procurement Expert IBRD / 92040 Prior 180,000.00 0.00 2023-09-21 2023-10-02 2023-10-03 2023-10-12 2023-10-10 2023-10-25 2023-11-10 2024-05-08 t ant Selection al ation for PCU (Short Term) AO-MINEA - GEPE-396632-C Project management suppor Individual Consult Under Implement IBRD / 92040 Post Limited 50,000.00 0.00 2023-12-15 2023-12-07 2024-01-12 2024-01-19 2024-02-09 2025-02-08 S-INDV / Assistant Accountan t ant Selection ation t for PCU Page 5