18-MONTH PROCUREMENT PLAN Project information: Nigeria Rural Access And Agricultural Marketing Project (RAAMP) - P163353 Project Implementation Agencies: Federal Ministry of Agriculture and Rural Development and State Project Implementation Units (SPIUs) Date of the Procurement Plan: September 18, 2019 Period covered by this Procurement Plan: February 2019 to July 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Nigeria Public Procurement Act 2007, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [15% is applicable for those contracts identified in the Procurement Plan tables]; Works: [ 7.5% is applicable for those contracts identified in the Procurement Plan tables] I. Threshold for Prior Review – Goods, Works, Non-Consulting Services and Consulting Services Prior-review Thresholds Thresholds for Procurement Methods High Substanti Moderate Low Risk Goods, IT & Non-Consulting Shortlist of National Procurement Type Risk al Risk Risk Works ($'000) ($'000) ($'000) ($'000) Services Consultants Request Request Engineering Open for for Open Open Open Consultin & Quotatio Quotatio 10,0 15,0 20,0 Internatio National internatio National g Constructio Works n or n or 5,000 00 00 00 nal or ICB or NCB National nal or ICB or NCB National Services n ($'000) ($'000) ($'000) ($'000) ($'000) Supervision Shopping Shopping ($'000) ($'000) ($'000) Goods, IT & Non- 2,0 4,0 6,0 Consulting Services 1,500 00 00 00 ≧ < ≦ ≧ < ≦ < ≦ Consultants 1,0 2,0 4,0 20,0 20,0 5,0 5,0 1 3 5 200 (Firms) 500 00 00 00 00 00 00 00 00 00 00 Post Review: All contracts not subject to prior review shall be subject to post review. Summary of the procurement packages for Goods, Works and Non-Consulting Services (Planned for the first 18 months after project effectiveness): Selecti Market on Evaluation Approa Review Metho Options Expected ch Prequal- Domestic Expected by Estimat d (Most date of Sr. Contract (Open- ification Preferenc date of Bank ed Cost (RFP, Advantageou bid/ No Description Nation (Yes/ e Contract (Prior/ (US$) RFB, s Bid, BAFO, proposal al/ No) (Yes/No) Signature Post) RFQ, Rated Criteria opening Limited DS etc.) etc.) etc.) Procurement of Air Conditioners 2 Limited Lowest March. 1 Post 24,600 RFQ No No Feb. 2020 Horse power Evaluated Cost 2020 (Split Unit) (Goods) Procurement of Steel File cabinets, Lowest March. 2 Spiral Binding Post 12,600 Limited RFQ Evaluated Cost No No Feb. 2020 2020 Machines and Consumables (Goods) Procurement of External hard disk + software packages Lowest March. 3 (licensed MS Post 12,300 Limited RFQ Evaluated Cost No No 2020 April. 2020 Office, Autocads, Antivirus, Converter etc) (Goods) Procurement of Laptops and Lowest March. 4 Post 100,000 Limited RFQ No No May. 2020 Tablets Evaluated Cost 2020 (Goods) Procurement Lowest March. 5 Post 22,400 Limited RFQ No No April. 2020 of Evaluated Cost 2020 Photocopying Machines (Goods) Medium Sized Lowest March. 6 Refrigerators Post 10,800 Limited RFQ Evaluated Cost No No 2020 April. 2020 (Goods) Procurement of Safety Equipment (Boots, Lowest 7 Post 39,000 Limited RFQ No No June. 2020 July, 2020 Helmets, Evaluated Cost Reflective Jackets etc.) (Goods) Construction Measuring Manual Wheel Lowest August. 8 Post 6,500 Limited RFQ No No July 2020 (Surveyor’s Evaluated Cost 2020 Wheel) (Goods) Roads Maintenance Equipment for Community based road maintenance (30 Nos tipping tricycles and other Open- 1,235,0 Lowest 9 equipment Post Nationa RFB No No Sept. 2020 Dec. 2020 00 Evaluated Cost such roads l signs and; cutlasses, wheelbarrows, hand rammer, digger, helmet, watering cans, reflective jacket, long shovel, nose cover, boots etc) (Goods) Procurement of Office Equipment, Printers, Open- Digital Lowest August. 10 Post 420,000 Nationa RFB No No June. 2020 Cameras & Evaluated Cost 2020 l Sundry Communicatio n devices (Goods) Purchase of Open- Project 2,940,0 Lowest March. 11 Prior Nationa RFB No No May. 2020 Vehicles 00 Evaluated Cost 2020 l (Goods) Server, Network System and other Open- Lowest equipment & Post 150,000 Nationa RFB Evaluated Cost No No Feb. 2020 May. 2020 accessories for l NiRTIMS and CosMos (Goods) Design and Construction of 200km of Rural Roads Open- 134,000 Rated Criteria (13 Prior Interna RFP No No Jun. 2020 Dec. 2020 ,000.00 and Cost Contracts of tional US$10.3 Million each) (Works) Construction/E stablishment Open – of Agro- 2,000,0 Lowest March. Post Nationa RFB No No July. 2021 Logistics 00 Evaluated Cost 2021 l centers/hubs at strategic locations (Multiple contracts) (Works) Construction /Rehabilitation of 10 Nos. Rural Bridges Open- 8,000,0 Lowest March. & Large Post Nationa RFB No No July. 2022 00 Evaluated Cost 2021 culverts (US$ l 0.6 M each Package) (Works) Local Community Group (LCG) and micro- enterprises maintenance Open- 14,000, Lowest of pilot roads Post Nationa RFB No No April. 2020 June.2020 000 Evaluated Cost (Multiple l Contracts in 13 States - US$ 0.002/year) (Works) II. Summary of the procurement packages for Consulting Services -Planned for the first 18 months after project effectiveness): Selection Market Method Review Approach Expected Expected Estimate (QCBS, Shortlisti Sr. by Bank (Open - date of bid/ date of Contract Description d Cost FBS, ng No (Prior/ International proposal Contract (US$) LCBS, (Yes/ No) Post) / National/ opening Signature QBS, CQS, etc.) DS etc.) Offshore & Onshore training and Workshops for Open- March. 1 the 13 states (Multiple Post 5,200,000 CQS No May. 2020 National 2020 contracts not to exceed US$ 0.1 M) (Consultancy) Consultancy Services for Detailed assessment, preliminary engineering design, ESIA, Procurement Support for Rural roads and Bridges; Road and 25,390,00 Open- 2 Bridge Supervision Prior QCBS Yes June. 2020 Nov. 2020 0 International Consultancy; Assessment of project security risk and mitigation (Multiple contracts spread in different locations) (Consultancy) Consultancy Services for design, procurement and supervision for Agro- Open- 3 logistics centers (Multiple Post 6,500,000 QCBS Yes Sep. 2020 Dec. 2020 International contracts spread in different locations) (Consultancy) Consultancy Services for the establishment of state Open- March. August. 4 road fund, and Post 5,665,000 QCBS Yes National 2020 2020 establishment of state rural access roads administration (Multiple contracts at 13 states) (Consultancy) Consultancy services on the development and operationalization of the Nigeria Rural Transport Infrastructure Management System (NiRTIMS) for sustainable road asset; Planning and Open- 5 Post 5,860,000 QCBS Yes Feb. 2020 July. 2020 implementation of the National routine maintenance system, spot improvement, periodic maintenance for rural roads. (Multiple contracts at 13 states) (Consultancy) Technical assistance consultancy services for the provision of technical advice (TA) to enhance the performance of agro- logistics centers (to ensure effective utilization of the facilities at the agro- Open- National March. 6 logistics centers); Post 4,975,000 QCBS Yes July. 2020 provision of TA and 2020 implements to farm level post-harvest agro-logistics activities and enhance the engagement of women and unemployed youth. (Multiple contracts at 13 states) (Consultancy) Consultancy services support for coordination of Open- 7 Post 2,442,000 CQS No Feb. 2020 April. 2020 project implementation at National Federal and State Levels (Multiple contracts at 13 states) (Consultancy) Consultancy services on Impact Evaluation, Baseline Data Collection, Comprehensive Technical Audit, Consultancy support for the development and Open- March. 8 operationalization of the Post 5,325,000 QCBS Yes July.2020 National 2020 smartphone-based construction site monitoring system (CoSMoS) (Multiple contracts at 13 states) (Consultancy) Consultancy support for the development and monitoring of Grievance Redress Mechanism and Gender-Based Violence; Development of road safety manual and training Open- 9 Post 1,843,000 CQS No April.2020 June. 2020 at the state level; National establishment/strengtheni ng the state traffic management agencies; road safety audit. (Multiple contracts at 13 states) (Consultancy) Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a 1Guidelineson Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Nigeria : Nigeria Rural Access and Agricultural Marketing Project PLAN General Information Country: Nigeria 2021-04-23 Bank’s Approval Date of the Original Procurement Plan: 2024-02-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163353 GPN Date: Project Name: Nigeria Rural Access and Agricultural Marketing Project Loan / Credit No: IDA / 65190 Oyo RAAMP Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - NG-OYO RAAMP-230798-CW- Component B. Asset Manage Single Stage - One E Small Works SPD Pending Imp 2026-02-0 RFB / Backlog Maintenance/ IDA / 65190 ment, Agro-logistics Perform Post Request for Bids Open - National 9,500,000.00 0.00 2024-04-30 2024-05-05 2024-06-16 2024-07-16 2024-08-13 nvelope (1 envelope proce lementation 4 Rehabilitation of about 70km ance Enhancement and Sect ss) Rural Roads or Reform Request for Bids - NG-OYO RAAMP-280597-CW- Component A. Improvement Single Stage - One E Small Works SPD Pending Imp 2026-02-1 RFB / Construction of Rural R IDA / 65190 of Rural Access and Trading Post Request for Bids Open - National 6,640,650.00 0.00 2024-04-30 2024-05-05 2024-06-16 2024-07-16 2024-08-20 nvelope (1 envelope proce lementation 1 oads Upgrading of about 31. Infrastructure ss) 2km in Oyo State NG-OYO RAAMP-230817-CW- Request for Bids - Component A. Improvement RFB / construction of about 3 Single Stage - One E Small Works SPD Pending Imp 2026-03-1 IDA / 65190 of Rural Access and Trading Post Request for Bids Open - National 1,500,000.00 0.00 2024-05-31 2024-06-05 2024-07-17 2024-08-16 2024-09-20 0metres rural cross drainage nvelope (1 envelope proce lementation 4 Infrastructure structure (Culvert/Bridges) in ss) Oyo State NG-OYO RAAMP-280610-CW- Request for Bids - Component A. Improvement RFB / Physical improvement Single Stage - One E Small Works SPD Pending Imp 2026-01-1 IDA / 65190 of Rural Access and Trading Post Request for Bids Open - National 4,800,000.00 0.00 2024-03-31 2024-04-05 2024-05-17 2024-06-16 2024-07-21 of about 3 Nos. Agro-Logistic nvelope (1 envelope proce lementation 2 Infrastructure s Centre (ALC) in Oyo State ss) Request for Bids - NG-OYO RAAMP-230782-CW- Component B. Asset Manage Single Stage - One E Small Works SPD Pending Imp 2026-01-1 RFB / Spot Improvement of a IDA / 65190 ment, Agro-logistics Perform Post Request for Bids Open - National 3,750,000.00 0.00 2024-03-31 2024-04-07 2024-05-19 2024-06-18 2024-07-23 nvelope (1 envelope proce lementation 4 bout 126.3 km Rural Roads i ance Enhancement and Sect ss) n Oyo State or Reform GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-OYO RAAMP-230403-GO- Component C. Institutional D Request for Quota Single Stage - One E RFQ / Purchase of 50 KVA Ge IDA / 65190 evelopment, Project Manage Post Limited 33,000.00 0.00 Signed 2022-06-06 2022-10-24 2022-07-18 2022-12-19 2022-10-16 tions nvelope nerators ment and Risk Mitigation NG-OYO RAAMP-230384-GO- RFQ / Purchase of laptops, D Component C. Institutional D esktops, Printers/Fax, Heavy Request for Quota Single Stage - One E IDA / 65190 evelopment, Project Manage Post Limited 80,000.00 0.00 Signed 2021-05-24 2022-07-25 2021-07-05 2022-09-17 2021-11-02 Duty Photocopiers Scanners, tions nvelope ment and Risk Mitigation Projectors, Internet Installatio n, Air Conditioners and Cons umables NG-OYO RAAMP-230320-GO- Component C. Institutional D Request for Quota Single Stage - One E RFQ / Purchase of office furni IDA / 65190 evelopment, Project Manage Post Limited 50,000.00 0.00 Canceled 2021-05-10 2021-06-21 2021-09-19 tions nvelope ture and equipment ment and Risk Mitigation NG-OYO RAAMP-230279-GO- Component C. Institutional D Request for Quota Single Stage - One E RFQ / Purchase of 2 Nos. of o IDA / 65190 evelopment, Project Manage Post Limited 150,000.00 0.00 Signed 2021-05-10 2022-10-24 2021-06-21 2022-12-09 2021-10-19 tions nvelope perating project vehicles ment and Risk Mitigation NG-OYO RAAMP-230593-GO- RFQ / Purchase of Safeguard equipment (PPEs, first aid kit Component C. Institutional D s, environmental monitoring Request for Quota Single Stage - One E Pending Impl IDA / 65190 evelopment, Project Manage Post Limited 100,000.00 0.00 2022-04-01 2022-05-13 2022-08-11 and tracking equipment inclu tions nvelope ementation ment and Risk Mitigation ding in-situ air quality kits, n oise meter, PH meter, cautio n tapes, measuring tapes, ca mera, GPS etc.) NG-OYO RAAMP-230588-GO- Component C. Institutional D Request for Quota Single Stage - One E Pending Impl RFQ / Purchase of promotion IDA / 65190 evelopment, Project Manage Post Limited 25,000.00 0.00 2021-05-29 2021-07-10 2021-10-08 tions nvelope ementation al materials (Flip Chart, Mem ment and Risk Mitigation o etc.) NG-OYO RAAMP-230564-GO- Component C. Institutional D Request for Quota Single Stage - One E Pending Impl RFQ / Purchase of Data Colle IDA / 65190 evelopment, Project Manage Post Limited 10,000.00 0.00 2022-12-24 2023-02-04 2023-05-05 tions nvelope ementation ction Gadget (6Nos.) ment and Risk Mitigation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-OYO RAAMP-280643-CS- QCBS / Consultancy Services Component A. Improvement Quality And Cost- Open - Internationa for Design and Supervision of IDA / 65190 of Rural Access and Trading Post 430,000.00 0.00 Signed 2022-03-08 2022-03-08 2022-03-29 2022-08-11 2022-05-12 2022-11-10 2022-06-09 2022-12-23 2022-07-09 2023-01-30 2022-08-13 2023-02-16 2022-09-17 2023-05-11 2024-12-02 Based Selection l 160km Rural Road Upgrading Infrastructure (Design & Build; Non-Design & Build Contracts) NG-OYO RAAMP-280650-CS- QCBS / Consultancy Service f Component A. Improvement Quality And Cost- Open - Internationa or Design and Supervision of IDA / 65190 of Rural Access and Trading Post 395,000.00 0.00 Signed 2022-03-06 2022-06-22 2022-03-27 2022-12-22 2022-05-10 2023-05-08 2022-06-07 2023-06-23 2022-07-07 2023-07-17 2022-08-11 2023-08-07 2022-09-15 2024-11-29 Based Selection l Physical Improvement of 5 to Infrastructure 6 Nos. Agro Logistics Centers (ALCs) Page 1 NG-OYO RAAMP-230446-CS- CQS / Consultancy services f or Design and Supervision of Component B. Asset Manage Backlog Maintenance/Rehabil ment, Agro-logistics Perform Consultant Qualifi IDA / 65190 Post Open - National 212,000.00 0.00 Canceled 2022-03-22 2022-03-29 2022-05-05 2022-05-19 2022-06-16 2024-11-02 itation (125km) Spot Improve ance Enhancement and Sect cation Selection ment (300km), and Construct or Reform ion of 50 linear meter cross d rainage structures (bridges/c ulverts) in Oyo State NG-OYO RAAMP-230423-CS- CQS / Consultancy Services f Component A. Improvement or Design and Supervision of Consultant Qualifi IDA / 65190 of Rural Access and Trading Post Open - National 350,000.00 0.00 Canceled 2021-09-06 2021-09-13 2021-10-20 2021-11-03 2021-12-01 2024-06-18 Rural Road Upgrading (Desig cation Selection Infrastructure n & Build) and Improvement of Agro-Logistics Hubs (ALHs) in Oyo State NG-OYO RAAMP-282646-CS- Component B. Asset Manage CQS / Consultancy Service fo ment, Agro-logistics Perform Consultant Qualifi IDA / 65190 Post Open - National 180,000.00 0.00 Signed 2022-03-22 2022-03-08 2022-03-29 2022-06-15 2022-05-05 2022-10-12 2022-05-19 2022-12-12 2022-06-16 2023-01-22 2024-11-02 r Design & Supervision of Ba ance Enhancement and Sect cation Selection cklog Maintenance/Rehabilita or Reform tion of Roads NG-OYO RAAMP-282647-CS- Component B. Asset Manage CQS / Consultancy Service fo ment, Agro-logistics Perform Consultant Qualifi r Design & Supervision of Sp IDA / 65190 Post Open - National 200,000.00 0.00 Signed 2022-03-22 2022-06-24 2022-03-29 2022-06-01 2022-05-05 2022-09-01 2022-05-19 2022-11-17 2022-06-16 2022-12-01 2024-11-02 ance Enhancement and Sect cation Selection ot Improvement and Constru or Reform ction of Cross Drainage Struc tures (Bridges and Culverts) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-OYO RAAMP-230510-CS-I Component C. Institutional D Individual Consult NDV / Engagement of Techni IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2022-03-07 2022-03-12 2022-04-02 2022-04-18 2023-04-13 ant Selection cal Assistance (TA) on Social ment and Risk Mitigation Safeguards. NG-OYO RAAMP-230530-CS-I Component C. Institutional D NDV / Engagement of Techni Individual Consult IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2022-04-04 2022-04-09 2022-04-30 2022-05-16 2023-05-11 cal Assistance (TA) on Enviro ant Selection ment and Risk Mitigation nmental Safeguards. NG-OYO RAAMP-230475-CS-I Component C. Institutional D Individual Consult NDV / Engagement of Techni IDA / 65190 evelopment, Project Manage Post Limited 40,000.00 0.00 Canceled 2022-03-07 2022-03-12 2022-04-02 2022-04-18 2023-04-13 ant Selection cal Assistance (TA) on GBV . ment and Risk Mitigation NG-OYO RAAMP-230548-CS-I Component C. Institutional D Individual Consult Pending Impleme NDV / Engagement of Techni IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 2022-03-14 2022-03-19 2022-04-09 2022-04-25 2023-04-20 ant Selection ntation cal Assistance (TA) on Procur ment and Risk Mitigation ement. NG-OYO RAAMP-280565-CS-I Component C. Institutional D Individual Consult NDV / Engagement of Techni IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Signed 2022-03-21 2022-11-21 2022-03-26 2022-09-12 2022-04-16 2023-03-28 2022-05-21 2023-05-16 ant Selection cal Assistant on Security Spe ment and Risk Mitigation cialist NG-OYO RAAMP-280578-CS-I Component C. Institutional D NDV / Engagement of Techni Individual Consult IDA / 65190 evelopment, Project Manage Post Limited 25,000.00 0.00 Canceled 2022-03-21 2022-03-26 2022-04-16 2022-05-06 2023-05-01 cal Assistance on Geographic ant Selection ment and Risk Mitigation Information System (GIS) Spe cialist NG-OYO RAAMP-280580-CS-I Component C. Institutional D Individual Consult NDV / Engagement of Techni IDA / 65190 evelopment, Project Manage Post Limited 25,000.00 0.00 Canceled 2022-03-21 2022-03-26 2022-04-16 2022-05-06 2023-05-01 ant Selection cal Assistance for Data Entry ment and Risk Mitigation Specialist (DES) NG-OYO RAAMP-230553-CS-I Component C. Institutional D Individual Consult Under Implement NDV / Engagement of Techni IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 2023-01-23 2023-03-15 2023-01-28 2023-01-23 2023-02-18 2023-03-25 2023-09-21 ant Selection ation cal Assistance (TA) on Civil E ment and Risk Mitigation ngineering NG-OYO RAAMP-354047-CS-I Component C. Institutional D Individual Consult Under Implement NDV / Engagement of Techni IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 2023-03-30 2023-05-15 2023-04-04 2023-04-25 2023-05-11 2024-05-05 ant Selection ation cal assistance on Environme ment and Risk Mitigation ntal safeguard NG-OYO RAAMP-380546-CS-I NDV / CONSULTANCY SERVIC ES FOR THE ENGAGEMENT O F AN INDIVIDUAL CONSULTA Component C. Institutional D NT FOR THE PREPARATION O Individual Consult Under Implement IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 2023-09-11 2023-09-19 2023-09-16 2023-10-07 2023-11-11 2024-11-05 F ENVIRONMENTAL AND SOCI ant Selection ation ment and Risk Mitigation AL MANAGEMENT PLAN (ESM P) FOR 9Nos – 112.6Km ROA D INTERVENTIONS (4Nos - 60 .3Km SPOT IMPROVEMENT, 3 Nos-30.1Km BACKLOG MAINT ENANCE, 2Nos-22.2Km NG-OYO RAAMP-392738-CS-I NDV / CONSULTANCY SERVIC ES FOR THE ENGAGEMENT O F AN INDIVIDUAL CONSULTA Component C. Institutional D NT FOR THE PREPARATION O Individual Consult Pending Impleme IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 2023-11-15 2023-11-20 2023-12-11 2024-01-15 2025-01-09 F RESETTLEMENT ACTION PL ant Selection ntation ment and Risk Mitigation AN (RAP) FOR 9 NOS (112.6K M) ROAD REHABILITATION A ND 4NOS – 30M CROSS DRAI NAGES INTERVENTIONS IN O YO STATE UNDER PHASE 1 IN TERVENTION NG-OYO RAAMP-395984-CS-I NDV / ENGAGEMENT OF AN I NDIVIDUAL CONSULTANT FO R THE PREPARATION OF ENVI Component C. Institutional D Individual Consult Pending Impleme RONMENTAL AND SOCIAL MA IDA / 65190 evelopment, Project Manage Post Limited 15,000.00 0.00 2024-02-15 2024-02-20 2024-03-12 2024-04-16 2024-08-14 ant Selection ntation NAGEMENT PLAN (ESMP) FOR ment and Risk Mitigation OJA-AGBE MARKET @ ISEYIN L.G; AGBEJODA MARKET @ O NA-ARA L.G; AND OJA-OBA M ARKET @ IBARAPA L.G. AREA S OF OYO STATE. Page 2