The World Bank Implementation Status & Results Report Uttar Pradesh Core Road Network Development Project (P147864) Uttar Pradesh Core Road Network Development Project (P147864) SOUTH ASIA | India | Transport Global Practice | IBRD/IDA | Investment Project Financing | FY 2019 | Seq No: 11 | ARCHIVED on 06-Feb-2024 | ISR59831 | Implementing Agencies: REPUBLIC OF INDIA, Transport Department, UP Police Traffic Directorate, UP-PWD Key Dates Key Project Dates Bank Approval Date: 29-Mar-2019 Effectiveness Date: 07-Jan-2020 Planned Mid Term Review Date: 17-Oct-2022 Actual Mid-Term Review Date: 17-Oct-2022 Original Closing Date: 30-Jun-2025 Revised Closing Date: 30-Jun-2025 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective is to build capacity for results-focused road safety management in Uttar Pradesh and to improve traffic flows and safety for all road users on selected corridors of the state core road network Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Network Improvement:(Cost $476.00 M) Institutional Strengthening of PWD:(Cost $3.00 M) Road Safety:(Cost $90.00 M) Contingent Emergency Response Component Front end fees:(Cost $1.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Unsatisfactory Unsatisfactory Overall Implementation Progress (IP) Unsatisfactory Unsatisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions Network Improvement: Construction of the PWD’s Phase I roads (totaling about 257 kms) has been satisfactorily completed and the maintenance period has started. The procurement of Phase II roads totaling 229 km is delayed with three out of five packages awaiting government approval. Institutional Strengthening of PWD: PWD has established a web-based Project Management Information System (PMIS) which is operational and being used for regular monitoring of civil works contracts. Consultancy support for upgradation and operationalizing the RAMS system (Shristi) is underway. On quality management the state research unit is carrying out the quality checks and assessments for all ongoing contracts. Gender action plan has been formulated and the recommendations to be implemented by the PWD and Transport Department. Training of PWD staff is being carried out regularly on matters relating to design, construction, material testing, O&M, contracting modalities, project management, etc. 2/6/2024 Page 1 of 7 The World Bank Implementation Status & Results Report Uttar Pradesh Core Road Network Development Project (P147864) Road Safety: The Road Safety Project Management Consultants for the Transport Department is onboard and operational. There is no progress on the project’s Road Safety activities under the Traffic Directorate as formal direction from the state on the process and protocols for establishing UP Highway Police (UPHP) is pending. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Substantial Substantial Substantial Macroeconomic Moderate Moderate Moderate Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Substantial Moderate Moderate Institutional Capacity for Implementation and Substantial High High Sustainability Fiduciary Substantial Substantial Substantial Environment and Social Substantial Substantial Substantial Stakeholders Substantial Substantial Substantial Other High High High Overall Substantial Substantial Substantial Results PDO Indicators by Objectives / Outcomes Improved capacity for results-focused road safety management in Uttar Pradesh IN01398871 ►UP Highway Police in place doing general deterrence-based enforcement on pilot corridors (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 06-Nov-2018 07-Dec-2022 30-Jan-2024 30-Jun-2023 State has given agreement in principle, but implementation has not started. Comments: IN01398873 ►Crash data from UPCDAS is publicly available and used for analysis and planning interventions (Yes/No, Custom) 2/6/2024 Page 2 of 7 The World Bank Implementation Status & Results Report Uttar Pradesh Core Road Network Development Project (P147864) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes Date 06-Nov-2018 07-Dec-2022 30-Jan-2024 30-Jun-2025 IRAD system developed for crash data collection but not yet used for analysis and planning Comments: Improve travel time and safety of all road users on selected corridors IN01398804 ►Reduction of average travel time for cars on civil works corridors (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target SH42 Hamirpur -Rath - SH42 Hamirpur -Rath - SH42 Hamirpur -Rath - SH42 Hamirpur-Rath - 133 68.5 68.5 59 SH42 Garautha Chirgaon SH42 Garautha Chirgaon SH42 Garautha SH42 Garautha- Value - 68 - 48.78 Chirgaon - 48.78 Chirgaon - 39 SH51-116 SH51-72.7 SH51-72.7 SH51-66 SH93 - 94 SH93 - 53.94 SH93 - 53.94 SH93-47 Date 13-Nov-2018 07-Dec-2022 30-Jan-2024 30-Jun-2025 Average Car travel time, minutes per km. Given the negative impact of speed on road crash outcomes, recommended that these targets be reviewed, and reframe the indicator as ‘Average travel time for cars Comments: on civil works corridors’. IN01398805 ►Improved Road Users Perception (RUSS) Index on civil works corridors (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target An average of above An average of above 95 95 percent response percent response recorded as survey to be done in recorded as Satisfactory Satisfactory per report Value TBD 2019 per draft report received received from from borrower borrower for Phase 1 roads Date 20-Mar-2019 07-Dec-2022 30-Jan-2024 30-Jun-2025 Comments: Road User Perception measured through primary survey in terms of an Index on civil works corridors IN01398872 ►Reduced number of fatalities on Highway Police pilot corridors (NH25 and NH2) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20.00 Date 13-Nov-2018 07-Dec-2022 30-Jan-2024 30-Jun-2023 Decision on this indicator would depend on reaching agreement on establishment of UPHP and Comments: strengthening road safety enforcement under the project. Intermediate Results Indicators by Components 2/6/2024 Page 3 of 7 The World Bank Implementation Status & Results Report Uttar Pradesh Core Road Network Development Project (P147864) Network Improvement IN01398874 ►Roads rehabilitated, Non-rural (Kilometers, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 258.00 258.00 500.00 Date 13-Nov-2018 07-Dec-2022 30-Jan-2024 30-Jun-2025 Kilometers of all non-rural roads reopened to motorized traffic, rehabilitated, or upgraded under the project. Non-rural roads are roads functionally classified in various countries as Trunk or Primary, Comments: Secondary or Link roads, or sometimes Tertiary roads. Typically, non-rural roads connect urban centers/towns/settlements of more than 5,000 inhabitants to each other or to higher classes of road, market towns and urban centers. Urban roads are included in non-rural roads. IN01398877 ►Satisfactory post-construction road safety audit (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes Date 13-Nov-2018 07-Dec-2022 30-Jan-2024 30-Jun-2025 A road safety audit after construction is completed and before opening it for traffic Comments: IN01398879 ►Women employed for routine maintenance under EPC contracts (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 13.00 13.00 30.00 Date 13-Nov-2018 07-Dec-2022 07-Dec-2022 30-Jun-2025 UPG-01:SH42 - 20 UPG-02: SH42 - 30 Comments: UPG-03: SH93- 0 UPG-04:SH51 - 0: Values at October 31, 2022 IN01398881 ►Assessment of gender actions conducted (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 13-Nov-2018 07-Dec-2022 30-Jan-2024 30-Jun-2022 Assessment of gender actions to be carried out for all the three agencies as part of RAP and GAP Comments: implementation evaluation. PWD is yet to hire the agency Institutional Strengthening 2/6/2024 Page 4 of 7 The World Bank Implementation Status & Results Report Uttar Pradesh Core Road Network Development Project (P147864) IN01398875 ►RAMS operationalized and used for annual maintenance planning (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target At least 50 percent of RAMS is not used for annual budget Value RAMS in use. RAMS in use. annual planning allocated based on RAMS Date 13-Nov-2018 07-Dec-2022 30-Jan-2024 31-Dec-2023 RAMS consultancy underway, Task 1 satisfactorily completed and other tasks on course Comments: Road Safety IN01398876 ►UP Highway Police established, equipped and trained (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Mobile, skilled and UP Highway Police does UP Highway Police UP Highway Police does well-equipped force in Value not exist. does not exist. not exist place operating 24 hours a day Date 13-Nov-2018 31-Dec-2021 30-Jan-2024 30-Jun-2023 IN01398878 ►Improved Driving Behaviors (Use of helmets and seatbelts ) on Highway Police Pilot Corridors (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value To be collected in 2019 To be collected To be collected TBD in YR1 Date 13-Nov-2018 31-Dec-2021 30-Jan-2024 30-Jun-2023 Improved driving behaviors on UPHP corridors (use of seatbelts and correctly worn, safety standard Comments: approved helmets) IN01398880 ►RS Cell at Transport Department staffed and supporting implementation of the state RS policy (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Fully functional RS RS Cell established but RS Cell established and RS Cell established Value Cell at the Transport not staffed partially staffed and partially staffed department Date 13-Nov-2018 31-Dec-2021 30-Jan-2024 30-Jun-2025 Comments: RS Cell staffed with technical expertise, resourced and supporting implementation of the state RS policy IN01398882 ►Road safety engineering improvement program implemented on CRN (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target targeted programs Program not yet Value Program not yet started Program not yet started. completed started. satisfactorily 2/6/2024 Page 5 of 7 The World Bank Implementation Status & Results Report Uttar Pradesh Core Road Network Development Project (P147864) Date 13-Nov-2018 31-Dec-2021 30-Jan-2024 30-Jun-2025 Comments: Targeted programs with cost-effecting engineering measures for road safety improvements, Performance-Based Conditions Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P147864 IBRD-89400 Effective USD 400.00 330.00 70.00 126.50 203.50 38% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P147864 IBRD-89400 Effective 29-Mar-2019 11-Oct-2019 07-Jan-2020 30-Jun-2025 30-Jun-2025 Cumulative Disbursements 2/6/2024 Page 6 of 7 The World Bank Implementation Status & Results Report Uttar Pradesh Core Road Network Development Project (P147864) Restructuring History Level 2 Approved on 10-Oct-2019 ,Level 2 Approved on 04-Nov-2020 Related Project(s) There are no related projects. 2/6/2024 Page 7 of 7