Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: 2015 2. Date of General Procurement Notice: July, 10, 2015 3. Period covered by this procurement plan: The Project Period II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) Above US$ 1,500,000 All 3. ICB (Works) Above US$ 5 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 1,500,000 All [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guideline 4. Any Other Special Procurement Arrangements: Given the prevailing impact of the ISIS conflict on Iraq, and need to address the urgent and developing requirements, procurement is being processed under paragraph 20 of OP 11.00 “Procurement under Situations of Urgent Need of Assistance or Capacity Constraints”, where “Simplified Procurement Procedures” may apply in accordance with paragraph 12 of the Bank OP 10.00 for investment project financing33. Procurement activities of this Project will include goods, works and both non-consultancy and consultant services under different Components. As they are identified, the activities will be packaged and finalized. 4. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) July 9, 2010 Refer to the Procurement Plan III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) Above US$ 500,000 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Given the prevailing impact of the ISIS conflict on Iraq, and need to address the urgent and developing requirements, procurement is being processed under paragraph 20 of OP 11.00 “Procurement under Situations of Urgent Need of Assistance or Capacity Constraints”, where “Simplified Procurement Procedures” may apply in accordance with paragraph 12 of the Bank OP 10.00 for investment project financing33. Procurement activities of this Project will include goods, works and both non-consultancy and consultant services under different Components. As they are identified, the activities will be packaged and finalized. 4. Consultancy Assignments with Selection Methods and Time Schedule Refer to the Procurement Plan July 9, 2010 PROCUREMENT Iraq : Emergency Operation for Development PLAN General Information Country: Iraq 2018-11-27 Bank’s Approval Date of the Original Procurement Plan: 2024-02-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P155732 GPN Date: Project Name: Emergency Operation for Development Loan / Credit No: IBRD / 87930, IBRD / 85200 Ministry of Water Resources Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned EODP-AF-MOWR/W01 / Emer Emergency Repair of Water 2019-11-0 gency repair of Falluja Barrag IBRD / 87930 Control, Infrastructure and Ir Post Direct Selection Direct 1,100,000.00 0.00 Canceled 2018-11-12 2018-11-17 2019-01-06 2 e in AL-Anbar governorate rigation Schemes EODP-AF-MOWR/W02 / Repai Emergency Repair of Water Single Stage - One E 2020-01-2 r of Abugrape irrigation sche IBRD / 87930 Control, Infrastructure and Ir Post Request for Bids Open - National 3,000,000.00 0.00 Canceled 2018-11-19 2018-12-03 2018-12-24 2019-01-21 2019-02-25 nvelope 1 me rigation Schemes EODP-AF-MOWR/W03 / Repai Emergency Repair of Water Single Stage - One E 2019-12-2 r of Dejla irrigation scheme i IBRD / 87930 Control, Infrastructure and Ir Post Request for Bids Open - National 1,100,000.00 0.00 Canceled 2018-11-19 2018-12-03 2018-12-24 2019-01-21 2019-02-25 nvelope 2 n Salah AL-Din governorate rigation Schemes EODP-AF-MOWR/W04 / Repai Emergency Repair of Water Single Stage - One E 2019-12-2 r of Rasasi irrigation scheme IBRD / 87930 Control, Infrastructure and Ir Post Request for Bids Open - National 1,500,000.00 0.00 Canceled 2018-11-26 2018-12-10 2018-12-31 2019-01-28 2019-03-04 nvelope 9 in Salah AL-Din governorate rigation Schemes EODP-AF-MOWR/W05 / Repai Emergency Repair of Water Single Stage - One E 2020-01-0 r of Alam irrigation scheme in IBRD / 87930 Control, Infrastructure and Ir Post Request for Bids Open - National 1,100,000.00 0.00 Canceled 2018-12-03 2020-05-31 2018-12-17 2019-01-07 2019-02-04 2019-03-11 nvelope 5 Salah AL-Din governorate rigation Schemes EODP-AF-MOWR/W06 / Repai Emergency Repair of Water Single Stage - One E 2020-01-1 r of Boujail irrigation scheme IBRD / 87930 Control, Infrastructure and Ir Post Request for Bids Open - National 1,400,000.00 0.00 Canceled 2018-12-10 2018-12-24 2019-01-14 2019-02-11 2019-03-18 nvelope 2 in Salah AL-Din governorate rigation Schemes EODP-AF-MOWR/W07 / Repai Emergency Repair of Water Single Stage - One E 2020-01-1 r of Dhuluia irrigation schem IBRD / 87930 Control, Infrastructure and Ir Post Request for Bids Open - National 1,300,000.00 0.00 Canceled 2018-12-17 2018-12-31 2019-01-21 2019-02-18 2019-03-25 nvelope 9 e in Salah AL-Din governorat rigation Schemes e EODP-MOWR/W03 / Repair o Emergency Repair of Water Single Stage - One E 2021-01-2 f Dejla irrigation scheme in S IBRD / 85200 Control, Infrastructure and Ir Post Request for Bids Open - National 1,100,000.00 0.00 Canceled 2019-12-22 2020-06-14 2020-01-05 2020-06-16 2020-01-26 2020-07-06 2020-02-23 2020-10-25 2020-03-29 nvelope 3 alah AL-Din governorate rigation Schemes EODP-MOWR/W05 / Repair o Emergency Repair of Water Single Stage - One E 2021-01-3 f Alam irrigation scheme in S IBRD / 85200 Control, Infrastructure and Ir Post Request for Bids Open - National 1,100,000.00 0.00 Canceled 2019-12-29 2020-05-31 2020-01-12 2020-02-02 2020-07-20 2020-03-01 2020-10-25 2020-04-05 nvelope 0 alah AL-Din governorate rigation Schemes EODP-MOWR/W04 / Repair o Emergency Repair of Water Single Stage - One E 1,165,901.0 2021-01-2 f Rasasi irrigation scheme in IBRD / 85200 Control, Infrastructure and Ir Post Request for Bids Open - National 1,500,000.00 Signed 2019-12-22 2020-05-11 2020-01-05 2020-01-26 2020-07-13 2020-02-23 2020-10-04 2020-03-29 2021-01-12 nvelope 0 3 Salah AL-Din governorate rigation Schemes EODP-MOWR/W06 / Repair o Emergency Repair of Water Single Stage - One E 1,011,811.2 2021-03-0 f Boujail irrigation scheme in IBRD / 85200 Control, Infrastructure and Ir Post Request for Bids Open - National 1,400,000.00 Signed 2020-01-05 2020-05-31 2020-01-19 2020-02-09 2020-08-10 2020-03-08 2020-10-06 2020-04-12 2020-12-03 nvelope 0 8 Salah AL-Din governorate rigation Schemes EODP-MOWR/W07 / Repair o Emergency Repair of Water Single Stage - One E 1,059,214.0 2021-02-2 f Dhuluia irrigation scheme in IBRD / 85200 Control, Infrastructure and Ir Post Request for Bids Open - National 1,300,000.00 Signed 2020-01-12 2020-05-31 2020-01-26 2020-02-16 2020-08-17 2020-03-22 2020-09-30 2020-04-26 2020-11-19 nvelope 0 0 Salah AL-Din governorate rigation Schemes EODP-MOWR/W08 / Reconstr Emergency Repair of Water Single Stage - One E 2021-02-2 uction of Anbar operation dir IBRD / 85200 Control, Infrastructure and Ir Post Request for Bids Open - National 1,200,000.00 953,840.00 Signed 2019-12-08 2020-05-11 2019-12-22 2020-06-17 2020-01-19 2020-07-08 2020-02-23 2020-09-27 2020-03-29 2020-12-01 nvelope 2 ectorate office in Al-Anbar Go rigation Schemes vernorate EODP-MOWR/W01 / Emerge Emergency Repair of Water 1,077,257.0 2020-11-2 ncy repair of Falluja Barrage i IBRD / 85200 Control, Infrastructure and Ir Post Direct Selection Direct 1,100,000.00 Signed 2019-12-08 2020-02-09 2019-12-22 2020-02-09 2020-02-02 2020-05-12 0 8 n AL-Anbar governorate rigation Schemes EODP-AF-MOWR/W10 / Reha Emergency Repair of Water Single Stage - One E 2021-05-1 b of Anna water resource offi IBRD / 87930 Control, Infrastructure and Ir Post Request for Bids Open - National 200,000.00 0.00 Canceled 2020-06-23 2020-06-14 2020-06-28 2020-07-19 2020-07-27 2020-08-16 2020-09-20 nvelope 8 ce in Al-Anbar governorate rigation Schemes EODP-MOWR/W9 / Reconstru Emergency Repair of Water Single Stage - One E 2021-04-2 ction of Saqlawia water resou IBRD / 85200 Control, Infrastructure and Ir Post Request for Bids Open - National 350,000.00 213,416.98 Signed 2020-06-23 2020-05-31 2020-06-24 2020-06-26 2020-07-15 2020-07-24 2020-09-30 2020-08-28 2020-11-20 nvelope 5 rces office in AL-Anbar gover rigation Schemes norate EODP-MOWR/W10 / Reconstr Emergency Repair of Water Single Stage - One E 2021-05-0 uction of Anna Water Resour IBRD / 85200 Control, Infrastructure and Ir Post Request for Bids Open - National 200,000.00 140,620.75 Signed 2020-06-08 2020-06-14 2020-06-13 2020-07-04 2020-07-27 2020-08-01 2020-09-24 2020-09-05 2020-11-11 nvelope 3 ces Building in Al-Anbar Gove rigation Schemes rnorate EODP-AF-MOWR/W11 / Const Emergency Repair of Water Single Stage - One E 3,173,899.5 2022-07-0 ruction of the first pumping s IBRD / 87930 Control, Infrastructure and Ir Post Request for Bids Open - National 4,500,000.00 Signed 2021-01-04 2021-01-05 2021-01-11 2021-02-01 2021-02-09 2021-03-08 2021-04-11 2021-04-12 2021-07-11 nvelope 0 6 tation in Ramadi Irrigation Pr rigation Schemes oject EODP-AF-MOWR/W12 / Const Emergency Repair of Water Single Stage - One E 2,978,724.0 2022-07-1 ruction of the second pumpin IBRD / 87930 Control, Infrastructure and Ir Post Request for Bids Open - National 3,400,000.00 Signed 2021-01-11 2021-01-05 2021-01-18 2021-02-08 2021-02-23 2021-03-15 2021-04-20 2021-04-19 2021-07-11 nvelope 0 3 g station in Ramadi Irrigation rigation Schemes Project EODP-AF-MOWR/W15 / Reha Emergency Repair of Water bilitation of Diyala Weir and Single Stage - One E 2021-10-3 IBRD / 87930 Control, Infrastructure and Ir Post Request for Bids Open - National 1,400,000.00 0.00 Canceled 2021-01-25 2021-02-01 2021-02-22 2021-03-29 2021-05-03 Common Head Regulator Bra nvelope 0 rigation Schemes nch in Diyala Governorate Request for Bids - EODP-MOWR/W03/R / Repair Emergency Repair of Water Single Stage - One E Small Works SPD 2022-04-1 of Dejla irrigation scheme in IBRD / 85200 Control, Infrastructure and Ir Post Request for Bids Open - National 800,000.00 764,119.20 Signed 2021-07-12 2021-07-04 2021-07-19 2021-08-09 2021-08-16 2021-09-13 2021-09-19 2021-10-18 2021-11-08 nvelope (1 envelope proce 6 Salah AL-Din governorate rigation Schemes ss) Request for Bids - EODP-MOWR/W05/R / Repair Emergency Repair of Water Single Stage - One E Small Works SPD 2022-04-2 of Alam irrigation scheme in IBRD / 85200 Control, Infrastructure and Ir Post Request for Bids Open - National 800,000.00 847,015.00 Signed 2021-07-19 2021-07-04 2021-07-26 2021-08-16 2021-08-22 2021-09-20 2021-09-13 2021-10-25 2021-11-08 nvelope (1 envelope proce 3 Salah AL-Din governorate rigation Schemes ss) Page 1 Request for Bids - EODP-MOWR/W13 / Completi Emergency Repair of Water Single Stage - One E Small Works SPD 1,243,870.5 2022-05-0 on of the fifth and sixth parts IBRD / 85200 Control, Infrastructure and Ir Post Request for Bids Open - National 1,350,000.00 Signed 2021-08-02 2021-06-28 2021-08-09 2021-08-30 2021-09-19 2021-10-04 2021-11-01 2021-11-08 2021-12-24 nvelope (1 envelope proce 5 7 / Phase V/ Ramadi Irrigation rigation Schemes ss) Scheme Request for Bids - EODP-AF-MOWR/W14/R / Re Emergency Repair of Water Single Stage - One E Small Works SPD 1,498,713.0 2022-06-0 pair of Salamiya irrigation sc IBRD / 87930 Control, Infrastructure and Ir Post Request for Bids Open - National 1,850,000.00 Signed 2021-08-29 2021-08-18 2021-09-05 2021-09-26 2021-10-05 2021-10-31 2021-11-14 2021-12-05 2022-01-10 nvelope (1 envelope proce 0 3 heme in Naynawa Governora rigation Schemes ss) te EODP-AF-MOWR/W14 / Repai Emergency Repair of Water Single Stage - One E 2021-10-2 r of Salamiya irrigation sche IBRD / 87930 Control, Infrastructure and Ir Post Request for Bids Open - National 1,750,000.00 0.00 Canceled 2021-01-18 2021-01-05 2021-01-25 2021-02-15 2021-03-16 2021-03-22 2021-04-26 nvelope 3 me in Naynawa Governorate rigation Schemes National Procure EODP-AF-MOWR/W15/R / Re Emergency Repair of Water ment Document - habilitation of Diyala Weir an 2022-07-0 IBRD / 87930 Control, Infrastructure and Ir Post Direct Selection Direct 1 Envelope proce 800,000.00 775,228.00 Signed 2021-09-12 2021-09-06 2021-09-26 2021-06-15 2021-11-07 2021-12-25 d Common Head Regulator B 5 rigation Schemes ss (Non Bank-SPD ranch in Diyala Governorate ) National Procure EODP-MOWR/W16 / Reconstr Emergency Repair of Water ment Document - Pending Imp 2024-12-1 uction of Administrative Build IBRD / 85200 Control, Infrastructure and Ir Post Direct Selection Direct - National 1 Envelope proce 1,000,000.00 0.00 2024-02-11 2024-02-18 2024-04-14 lementation 0 ing for Diyala Weir rigation Schemes ss (Non Bank-SPD ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EODP-AF-MOWR/G01 / Suppl Emergency Repair of Water Open - Internationa Single Stage - One E y of excavators, loaders and IBRD / 87930 Control, Infrastructure and Ir Prior Request for Bids 6,500,000.00 6,067,480.00 Signed 2018-11-21 2019-03-17 2018-12-05 2019-04-15 2019-01-19 2019-05-14 2019-03-05 2019-11-12 2019-04-09 2020-01-14 2019-12-05 l nvelope bulldozers ( 3 Lots) rigation Schemes EODP-AF-MOWR/G02 / Suppl Emergency Repair of Water ying Submersible pumps for Open - Internationa Single Stage - One E IBRD / 87930 Control, Infrastructure and Ir Prior Request for Bids 3,000,000.00 2,534,740.00 Signed 2018-12-05 2019-03-17 2018-12-19 2019-06-10 2019-02-02 2019-07-10 2019-03-19 2020-01-07 2019-04-23 2020-05-28 2019-10-20 wells , generators , Casing pi l nvelope rigation Schemes pes for wells & drilling access ories for wells.(4 Lots) EODP-AF-MOWR/G05 / Suppl Emergency Repair of Water Open - Internationa Single Stage - One E ying Truck cranes and Trailer IBRD / 87930 Control, Infrastructure and Ir Prior Request for Bids 1,500,000.00 0.00 Signed 2021-06-16 2021-11-22 2021-06-23 2021-11-25 2021-08-11 2022-01-10 2021-09-22 2022-07-22 2021-10-27 2022-09-08 2022-05-25 l nvelope s (two lots) rigation Schemes EODP-AF-MOWR/G03 / Suppl Emergency Repair of Water Open - Internationa Single Stage - One E y of twelve amphibious exca IBRD / 87930 Control, Infrastructure and Ir Prior Request for Bids 4,800,000.00 0.00 Canceled 2021-06-02 2021-10-11 2021-06-09 2021-10-19 2021-07-28 2021-12-01 2021-09-08 2022-06-15 2021-10-13 2022-05-11 l nvelope vators rigation Schemes EODP-AF-MOWR/SH01 / Sup Emergency Repair of Water Request for Quota Single Stage - One E ply of Copiers, laptops, and a IBRD / 87930 Control, Infrastructure and Ir Post Open - National 55,000.00 51,875.00 Signed 2021-10-11 2021-11-29 2021-12-19 2021-12-29 tions nvelope ccessories rigation Schemes Emergency Repair of Water EODP-AF-MOWR/SH02 / Sup Request for Quota Single Stage - One E IBRD / 87930 Control, Infrastructure and Ir Post Open - National 5,000.00 0.00 Signed 2021-10-18 2021-12-06 2022-08-09 2022-01-05 ply of Office Furniture tions nvelope rigation Schemes EODP-AF-MOWR/G03/R / Sup Emergency Repair of Water Open - Internationa Single Stage - One E ply of twelve amphibious exc IBRD / 87930 Control, Infrastructure and Ir Prior Request for Bids 4,800,000.00 0.00 Signed 2022-10-05 2022-10-24 2022-10-19 2022-11-02 2022-11-30 2022-12-21 2023-01-18 2023-05-12 2023-03-01 2023-07-17 2023-10-27 l nvelope avators rigation Schemes EODP-AF-MOWR/G04 / Suppl Emergency Repair of Water Open - Internationa Single Stage - One E ying pontoons for Hitachi am IBRD / 87930 Control, Infrastructure and Ir Prior Request for Bids 4,100,000.00 0.00 Signed 2022-10-19 2022-11-14 2022-11-02 2022-11-22 2022-12-14 2023-01-11 2023-02-01 2023-05-10 2023-03-15 2023-07-16 2023-11-10 l nvelope phibious excavators rigation Schemes EODP-AF-MOWR/G05/LOT 1/ Emergency Repair of Water Open - Internationa Single Stage - One E R / Supplying two truck crane IBRD / 87930 Control, Infrastructure and Ir Post Request for Bids 960,000.00 0.00 Signed 2022-11-16 2023-01-21 2022-11-30 2023-01-22 2023-01-11 2023-03-08 2023-03-01 2023-05-15 2023-04-12 2023-07-15 2024-02-06 l nvelope s with spare parts rigation Schemes EODP-AF-MOWR/G06 / Suppl Emergency Repair of Water Open - Internationa Single Stage - One E Under Imple ying Solar submersible pump IBRD / 87930 Control, Infrastructure and Ir Post Request for Bids 900,000.00 0.00 2023-07-19 2023-07-12 2023-08-02 2023-07-17 2023-09-13 2023-08-30 2023-11-01 2023-12-27 2023-12-20 2024-06-17 l nvelope mentation s for wells rigation Schemes Emergency Repair of Water EODP-AF-MOWR/G07 / Suppl Open - Internationa Single Stage - One E Under Imple IBRD / 87930 Control, Infrastructure and Ir Post Request for Bids 1,100,000.00 0.00 2023-07-26 2023-07-18 2023-08-09 2023-07-27 2023-09-20 2023-09-28 2023-11-08 2024-01-07 2023-12-27 2024-06-24 ying drilling tools for well l nvelope mentation rigation Schemes NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EODP-AF-MOWR/C02A / Cons Emergency Repair of Water Consultant Qualifi truction supervision/quality c IBRD / 87930 Control, Infrastructure and Ir Post Open - National 300,000.00 0.00 Canceled 2018-11-23 2019-08-01 2018-12-14 2019-01-27 2019-02-26 2019-04-02 2020-03-27 cation Selection ontrol for Anbar contracts rigation Schemes EODP-AF-MOWR/C02B / Cons Emergency Repair of Water Consultant Qualifi truction supervision/quality c IBRD / 87930 Control, Infrastructure and Ir Post Open - National 350,000.00 0.00 Canceled 2018-11-23 2018-12-14 2019-01-27 2019-02-26 2019-04-02 2020-03-27 cation Selection ontrol for Salahaldeen contra rigation Schemes cts EODP-AF-MOWR/C02C / Cons Emergency Repair of Water Consultant Qualifi truction supervision/quality c IBRD / 87930 Control, Infrastructure and Ir Post Open - National 400,000.00 0.00 Canceled 2018-11-30 2018-12-21 2019-02-03 2019-03-05 2019-04-09 2020-04-03 cation Selection ontrol for Kirkuk and Naynaw rigation Schemes a contracts EODP-MOWR/C02A / Constru Emergency Repair of Water Consultant Qualifi ction supervision for Anbar c IBRD / 85200 Control, Infrastructure and Ir Post Open - National 300,000.00 0.00 Canceled 2019-11-26 2019-12-03 2019-12-17 2019-12-04 2020-02-04 2020-02-25 2020-03-10 2020-04-14 2021-07-08 cation Selection ontracts rigation Schemes EODP-MOWR/C02B / Constru Emergency Repair of Water Consultant Qualifi ction supervision for Salahald IBRD / 85200 Control, Infrastructure and Ir Post Open - National 275,000.00 0.00 Canceled 2019-12-03 2019-12-08 2019-12-24 2019-12-22 2020-02-11 2020-06-30 2020-03-17 2020-04-21 2021-07-15 cation Selection een contracts rigation Schemes Page 2 EODP-MOWR/C02A/R / Const Emergency Repair of Water Consultant Qualifi ruction supervision for Anbar IBRD / 85200 Control, Infrastructure and Ir Post Open - National 300,000.00 244,133.00 Signed 2020-09-07 2020-10-06 2020-09-28 2020-10-20 2020-11-16 2020-12-06 2020-12-21 2021-01-31 2021-01-25 2021-03-09 2022-01-20 cation Selection contracts rigation Schemes EODP-MOWR/C02B/R / Const Emergency Repair of Water Consultant Qualifi ruction supervision for Salah IBRD / 85200 Control, Infrastructure and Ir Post Open - National 275,000.00 351,601.00 Signed 2020-09-14 2020-09-13 2020-10-05 2020-10-26 2020-11-23 2020-11-30 2020-12-28 2020-12-29 2021-02-01 2021-03-09 2022-01-27 cation Selection aldeen contracts rigation Schemes EODP-AF-MOWR/C11 / Const Emergency Repair of Water Consultant Qualifi ruction supervision for Rama IBRD / 87930 Control, Infrastructure and Ir Post Open - National 300,000.00 292,883.00 Signed 2021-01-19 2021-01-23 2021-02-09 2021-03-02 2021-03-30 2021-04-27 2021-05-04 2021-06-01 2021-06-08 2021-07-08 2022-09-01 cation Selection di pump stations rigation Schemes EODP-AF-MOWR/C12 / Const Emergency Repair of Water Consultant Qualifi ruction supervision for Diyala IBRD / 87930 Control, Infrastructure and Ir Post Open - National 200,000.00 185,464.00 Signed 2021-01-26 2021-01-23 2021-02-16 2021-03-04 2021-04-06 2021-04-29 2021-05-11 2021-06-08 2021-06-15 2021-09-20 2022-09-08 cation Selection and Naynawa Contracts rigation Schemes INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EODP-AF-MOWR/C06 / Prepa Emergency Repair of Water ration of Environmental and IBRD / 87930 Control, Infrastructure and Ir Post Direct Selection Direct 90,000.00 0.00 Canceled 2019-05-29 2019-05-30 2019-06-08 2019-08-12 2020-02-08 Social instruments rigation Schemes Emergency Repair of Water EODP-AF-MOWR/C14 / Procu Individual Consult IBRD / 87930 Control, Infrastructure and Ir Post Open 40,000.00 0.00 Canceled 2020-01-19 2020-01-16 2020-03-08 2020-03-29 2020-05-03 2021-05-03 rement Specialist ant Selection rigation Schemes Emergency Repair of Water EODP-AF-MOWR/C16 / Procu Individual Consult IBRD / 87930 Control, Infrastructure and Ir Post Open 150,000.00 0.00 Canceled 2020-03-15 2020-03-15 2020-05-03 2020-05-24 2020-06-28 2021-06-27 rement Specialist ant Selection rigation Schemes Emergency Repair of Water EODP-AF-MOWR/C15 / Local IBRD / 87930 Control, Infrastructure and Ir Post Direct Selection Direct 15,000.00 30,000.00 Signed 2020-03-01 2020-03-02 2020-03-08 2020-03-05 2020-03-29 2020-04-13 2021-03-29 Procurement Specialist rigation Schemes Emergency Repair of Water EODP-AF-MOWR/C17 / Procu IBRD / 87930 Control, Infrastructure and Ir Post Direct Selection Direct 15,000.00 15,000.00 Completed 2020-07-29 2020-08-09 2020-08-05 2020-07-29 2020-08-26 2020-08-24 2021-02-22 2021-01-17 rement Advisor rigation Schemes Emergency Repair of Water EODP-AF-MOWR/C19 / Procu IBRD / 87930 Control, Infrastructure and Ir Post Direct Selection Direct 40,000.00 0.00 Canceled 2021-02-10 2021-02-17 2021-03-10 2022-03-05 rement Advisor rigation Schemes Emergency Repair of Water EODP-AF-MOWR/C20 / Local Individual Consult IBRD / 87930 Control, Infrastructure and Ir Post Limited 15,000.00 17,000.00 Signed 2022-03-15 2022-03-16 2022-03-20 2022-04-21 2022-03-27 2022-05-08 2022-04-10 2022-06-11 2023-04-10 procurement Specialist ant Selection rigation Schemes Page 3