The World Bank Implementation Status & Results Report Jharkhand Power System Improvement Project (P162086) Jharkhand Power System Improvement Project (P162086) SOUTH ASIA | India | Energy & Extractives Global Practice | IBRD/IDA | Investment Project Financing | FY 2019 | Seq No: 11 | ARCHIVED on 02-Feb-2024 | ISR59714 | Implementing Agencies: Government of India, Jharkhand Bijli Vitran Nigam Ltd., Jharkhand Urja Sancharan Nigam Ltd. Key Dates Key Project Dates Bank Approval Date: 01-Oct-2018 Effectiveness Date: 22-Apr-2019 Planned Mid Term Review Date: 15-Mar-2022 Actual Mid-Term Review Date: 31-Jul-2022 Original Closing Date: 31-May-2024 Revised Closing Date: 31-May-2024 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The project development objectives (PDO) are to increase the transmission capacity of electricity network in the state of Jharkhand and strengthen the institutional capacity of state-owned power transmission and distribution utilities. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Component 1: Intra-state transmission system strengthening:(Cost $336.20 M) Component 2: Technical assistance for institutional development and capacity building of JUSNL:(Cost $13.80 M) Component 3: Improving operational efficiency and developing institutional capacity of JBVNL:(Cost $99.20 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions The project has added an additional capacity of 200 MVA at 132kV, till December 31, 2023, and the same is in commercial use. Another 600 MVA of additional capacity and augmentation of 6 existing sub-stations, is ready for commissioning subject to completion of associated transmission lines. JUSNL is making regular compensation payment for temporary displacement to project affected persons (PAPs) in transmission lines. The distribution company, JBVNL, has implemented a new digital application for Revenue Management System. Around 900,000 consumers (25% of total) are being billed through this system. The contract for 3,50,000 smart meters in Ranchi is under progress and 170,000 smart meters were installed till December 31, 2023. Implementation of automated network metering, power procurement optimization and customer care centre is also in progress. An IT Project Management Office (staffed by a consulting Firm) is supporting JBVNL in implementation of these packages. 2/2/2024 Page 1 of 6 The World Bank Implementation Status & Results Report Jharkhand Power System Improvement Project (P162086) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Moderate Moderate Moderate Macroeconomic Low Low Low Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Moderate Moderate Moderate Institutional Capacity for Implementation and High High High Sustainability Fiduciary Substantial Substantial Substantial Environment and Social Substantial Substantial Substantial Stakeholders Substantial Substantial Substantial Other -- -- -- Overall Substantial Substantial Substantial Results PDO Indicators by Objectives / Outcomes Increase the transmission capacity of electricity network in the state of Jharkhand IN01394749 ►Amount of electricity wheeled through JUSNL network for supply to consumers in the State (Gigawatt-hour (GWh), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 8,592.30 10,660.00 8,266.00 15,000.00 Date 30-Mar-2018 31-Mar-2023 30-Nov-2023 31-Mar-2024 The target value of the indicator is for 12 months. The indicated value in this ISR is for 8 months. Ona pro- rata basis, the likely value is 12,400 (~44 percent increase over the baseline), but the actual figure will Comments: depend on consumer demand. IN01394997 ►Increase in transformation capacity of the power transmission network in the state under the project (Kilovolt-Amphere(KVA), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 200,000.00 200,000.00 2,400,000.00 2/2/2024 Page 2 of 6 The World Bank Implementation Status & Results Report Jharkhand Power System Improvement Project (P162086) Date 30-Mar-2018 31-Mar-2023 31-Dec-2023 31-May-2024 Strengthen the institutional capacity of state-owned power distribution utility IN01394996 ►Percentage of consumers serviced through upgraded commercial system (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 1.00 25.00 90.00 Date 01-Mar-2018 30-Apr-2023 31-Dec-2023 31-May-2024 The migration of consumers to upgraded commercial system has started and the system is in testing Comments: phase. Strengthen the institutional capacity of state-owned power transmission utility IN01394750 ►Financial, Procurement and Contract management framework strengthened in JUSNL (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target AFS manually prepared Draft WPPP document and limited Draft WPPP document FM, Procurement and has been prepared. standardization in has been prepared. Tally Contract management Value Tally ERP has been procurement and ERP has been partially framework implemented in JUSNL contract management implemented. strengthened HQ office practices Date 31-Mar-2018 31-Mar-2023 31-Dec-2023 31-May-2024 Intermediate Results Indicators by Components Component 1: Intra-state transmission system strengthening IN01394998 ►Transmission lines constructed under the project (circuit km) (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 342.68 436.72 2,000.00 Date 31-Mar-2018 31-Mar-2023 31-Dec-2023 31-May-2024 IN01395001 ►Number of transmission substations constructed under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 8.00 8.00 25.00 Date 31-Mar-2018 31-Mar-2023 31-Dec-2023 31-May-2024 2/2/2024 Page 3 of 6 The World Bank Implementation Status & Results Report Jharkhand Power System Improvement Project (P162086) IN01395004 ►Women employed as a percentage of total persons employed in construction activities; (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 5.00 Date 01-Jun-2018 31-Mar-2023 31-Dec-2023 31-May-2024 IN01395006 ►Grievances received that are addressed within two months of receipt (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 60.00 72.00 90.00 Date 01-Jun-2018 31-Mar-2023 31-Dec-2023 31-May-2024 IN01395007 ►Number of persons consulted during project implementation (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 2,300.00 3,468.00 500.00 Date 31-Mar-2018 31-Mar-2023 31-Dec-2023 31-May-2024 Component 2: Technical assistance for institutional development and capacity building of JUSNL IN01394999 ►Person-days of JUSNL and JBVNL staff participating in trainings (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 394.00 600.00 500.00 Date 01-Jun-2018 30-Apr-2023 31-Dec-2023 31-May-2024 IN01395002 ►Person-days of trainings provided to women employees of JUSNL and JBVNL (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 46.00 139.00 30.00 Date 01-Jun-2018 30-Apr-2023 31-Dec-2023 31-May-2024 Component 3: Improving operational efficiency and developing institutional capacity of JBVNL IN01395000 ►Number of smart meters installed (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 2/2/2024 Page 4 of 6 The World Bank Implementation Status & Results Report Jharkhand Power System Improvement Project (P162086) Value 0.00 75,000.00 170,000.00 300,000.00 Date 01-Jun-2018 31-Mar-2023 31-Dec-2023 31-May-2024 IN01395003 ►Commercial Systems (Billing, Collection and Customer Resource Management) of JBVNL upgraded (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Existing commercial system has been improved to include HT The new Commercial Upgraded commercial Existing system has billing [supported by IT IT system has been Value system has been limited capacity PMC financed under deployed and is in deployed Bank loan]. Testing of commercial use new Commercial IT system is in progress. Date 01-Jun-2018 31-Mar-2023 31-Dec-2023 31-May-2024 IN01395005 ►Establishment of sexual harassment prevention cell in JBVNL (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes Date 01-Jun-2018 30-Jun-2022 30-Jun-2022 31-May-2024 Performance-Based Conditions Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P162086 IBRD-89080 Effective USD 310.00 280.00 30.00 133.95 146.05 48% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P162086 IBRD-89080 Effective 01-Oct-2018 20-Nov-2018 22-Apr-2019 31-May-2024 31-May-2024 Cumulative Disbursements 2/2/2024 Page 5 of 6 The World Bank Implementation Status & Results Report Jharkhand Power System Improvement Project (P162086) Restructuring History Level 2 Approved on 09-Apr-2021 Related Project(s) There are no related projects. 2/2/2024 Page 6 of 6