SUMMARY O F PROCUREMENT PLAN Project Preparation Advancement (PPA) Project information: Harmonizing and Improving Statistics in West Africa Project -P169265 Project Implementation agency: Liberia Institute of Statistics and Geo- Information Services (LISGIS) Date of the Procurement Plan: February 3, 2020 Period covered by this Procurement Plan: 3rd February to 31st July 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 1, 2016), revised in November 2017, and August 2018 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement and Concessions Act, 2010 of the Republic of Liberia, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable for those contracts identified in the Procurement Plan tables; Works: Not Applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not Applicable. Other Relevant Procurement Information: - (a). Prior Procurement Arrangements: The Procurement Arrangements as indicated in the below table and within the thresholds indicated in the below tables will be used. The thresholds for the Bank’s prior review requirements are also provided in the table below: Table: Thresholds*, Procurement Arrangements, and Prior Review (The table below depicts the Thresholds and Procurement Methods to be used under the Regional Project for Statistics Thresholds*, Procurement Methods, and Prior Review Contract (C) Value Expenditure Procurement Contracts Subject to No Threshold* [eq. Category Method Prior Review /[eq. US$] USD] All contracts at or above USD Open Competition 5,000,000 are subject to International Market 1 Works C ≥ 5,000,000 Approach and Direct international advertising and the use of the Bank’s SPDs (or other Contracting documents agreed with the Contract (C) Value Expenditure Procurement Contracts Subject to No Threshold* [eq. Category Method Prior Review /[eq. US$] USD] Bank). Open Competition National Market 200,000 < C < 5,000,000 None Approach C ≤ 200,000 RfQ None All contracts at or above USD Open Competition 500,000 are subject to International Market international advertising and the C ≥ 500,000 Approach and Direct use of the Bank’s SPDs (or other Goods, IT and Contracting documents agreed with the 2 non-consulting Bank). services Open Competition 100,000 < C < 500,000 National Market None Approach C ≤ 100,000 RfQ None All contracts at or above USD 100,000 are subject to for international advertising and the C < 100,000 Consulting Services use of the Bank’s SPDs (or other National documents agreed with the shortlist for Bank). 3 selection of All contracts at or above USD consultant firms for 200,000 are subject to Engineering and international advertising and the C ≤ 200,000 Construction use of the Bank’s SPDs (or other Supervision documents agreed with the Bank). Selection of All values ≥ 100,000 4 Individual All Approaches consultants Training, This line activity is not subject to Workshops, Based on approved Procurement Review However, 5 Study Tours All Values Annual Work Plan & each of the activities will be Budgets (AWPB) by TTL cleared with the TTL prior to its implementation. (Special procurement arrangements like direct contracting, use of SOEs, UN Agencies, third party monitors, local NGOs, Force Account, servants needs, results based arrangements. It is not expected that there will be need for prequalification in the procurement arrangements under this Regional Project *These thresholds are for the purposes of the initial procurement plan for the PPA and for first 18 months. The thresholds will be revised periodically based on re- assessment of risks. All contracts not subject to prior review will be post-reviewed. Prequalification. Not expected for the packages of works/goods packages in the procurement plan. Proposed Procedures for CDD Components: Not Applicable Reference to (if any) Project Operational/Procurement Manual: The LISGIS Project Management Team will prepare Procurement manuals. The Procurement Plan will also form part of the Project Implementation Manual. Any Other Special Procurement Arrangements: None Procurement Packages/PLAN with Procurement Arrangements and Time Schedule: as per the Table below: b) PROCUREMENT PLAN Works There are no works under the Project Preparation Advance Goods and Non-Consulting Services 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procurement Prequ Nation Revie Expecte Expecte Comment No. (Description) Cost Method alifica al w d bid d s US$ tion Prefer by opening Contrac (yes/n ence Bank date t o) (yes/n (Prior Signatu o) / Post) re Date 1 Procurement of 4 12,100 laptops, 3 No. all- in-1 printers, Limited, RFQ No No Post 28 Feb 4 Mar office desks, a 20 20 projector, metal filing cabinet, and stationery and supplies for project management Consultancy Services 1 2 3 4 5 6 7 8 9 Ref. Description of Estimate Selection Review Expecte Expected Expected Comments No. Assignment d Method/ by Bank d date Contract Completi Cost in Arrangem (Prior / of Signatur on US$ ent Post) proposal e Date submissi Date on 1. Recruitment of a Consultant to draft and validate 10,000 INDV Post 16 Mar 10 Apr 23 Apr ToR to be curricula of the 20 20 20 submitted to IDA Statistics degree & for Review and No CEST Program at Objection. the UL 2. Recruitment of a ToR, performance Financial evaluation, draft Management contract and Officer for Project DS Prior 10 Feb 21 Feb 31 Aug minutes of Management 20 20 20 contract negotiation to be submitted to IDA for Review and No 15,600 Objection. 3. ToR, performance evaluation, draft Recruitment of a contract and Procurement DS Prior 10 Feb 21 Feb 31 Aug minutes of Specialist for 20 20 20 contract Project 18,000 negotiation to be Management submitted to IDA for Review and No Objection. Training and Workshop (Training & Workshop activities are subject to TTL clearance). Estimat Estimated Expected Ref. Training, workshop and ed Cost Duration Training/workshop No. study tours in (Days) Date (US$) Conduct of validation 54,000 workshop and TOT for the GP Feb. 20 to March 1. on the design of 13 2020 questionnaires and enumeration training manual Workshop for cartographic 150,000 Feb. 24 to March 2. field staff training 16 2020 Workshop for enumeration 113,900 3. mapping training April 15, 2020 Study Tours to regional 32,000 countries for first-hand experience on regional March to April 4. harmonization of data 2020 collection, management and communication Workshops on current 50,000 administrative data across 5. April to July 2020 MACs and LISGIS regional offices Workshop to strengthen and 35,000 6. develop institutional capacity April to July 2020 of NSO Workshops for steering 40,000 7. committee on Administrative April to July 2020 Data Workshop for Project 10,000 Steering/Technical 8. Committees for annual work February 2020 plan preparation, review and validation GENERAL NOTES 1. Training and capacity building: Training workshops (including training material and support), conference attendance and study tours, will be carried out based on approved annual training and allied activities plan by the TTL. The beneficiaries, after the training, will be requested to submit a brief report indicating what skills have been acquired and how these skills will contribute to enhance their performance and contribute to the attainment of the Project’s development objective. 2. Operational Costs: These are expenditures incurred by the Recipient to finance: (i) communication technology (including, without limitation, internet and telephone; (ii) per diem and travel expenses of the operational staff performing their responsibilities under the Project; (iii) fuel and vehicle maintenance; (iv) maintenance of equipment; (v) photocopies and publications; (viii) bank commissions; and (ix) utilities and office supplies as defined in the FA. Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Western and Central Africa : Harmonizing and Improving Statistics in West Africa PLAN General Information Country: Western and Central Africa 2020-11-27 Bank’s Approval Date of the Original Procurement Plan: 2022-06-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169265 GPN Date: 2021-05-19 Project Name: Harmonizing and Improving Statistics in West Africa Loan / Credit No: IDA / 65730, IDA / 65770, IDA / 65740, IDA / 65760 Institut National de la Statistique et de la Démographie Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-INSD-177135-GO-RFB / A Regional component: Harmo cquisition du matériel inform nization, Data Collection, Qu Open - Internationa Single Stage - One E atique au profit des structure IDA / 65730 ality Improvement, Dissemin A posteriori Appel d'offres 1,450,000.00 0.00 Annulé 2021-03-01 2021-03-06 2021-04-20 2021-05-20 2021-06-24 2021-09-22 l nvelope s de MEO du Projet et pour l ation and Use of Core Social a mise en œuvre des enquêt and Economic Statistics es. Regional component: Harmo BF-INSD-215375-GO-RFB / fo nization, Data Collection, Qu urniture de matériels IEC pou Single Stage - One E En attente d' IDA / 65730 ality Improvement, Dissemin A posteriori Appel d'offres Open - National 146,000.00 0.00 2021-04-26 2021-05-01 2021-05-31 2021-06-15 2021-07-20 2021-10-18 r les enquêtes emploi , ména nvelope exécution ation and Use of Core Social ges et pour le MAAH and Economic Statistics Regional component: Harmo BF-INSD-175419-GO-RFQ / A nization, Data Collection, Qu Single Stage - One E cquisition de Mobiliers de bur IDA / 65730 ality Improvement, Dissemin A posteriori Demande de prix Limited 15,000.00 26,504.55 Achevé 2020-06-20 2021-10-06 2020-08-04 2021-11-09 2020-09-03 2021-12-31 nvelope eaux pour l'UGP ation and Use of Core Social and Economic Statistics Regional component: Harmo BF-INSD-175415-GO-RFQ / fo nization, Data Collection, Qu Single Stage - One E En attente d' urnitures de matériels de bur IDA / 65730 ality Improvement, Dissemin A posteriori Demande de prix Limited 15,000.00 0.00 2021-05-08 2021-06-13 2021-07-13 nvelope exécution eau pour l'UGP ation and Use of Core Social and Economic Statistics BF-INSD-175423-GO-RFQ / F Project Management and Mo Single Stage - One E ourniture matériels informati IDA / 65730 A posteriori Demande de prix Limited 25,000.00 21,688.49 Achevé 2020-06-27 2021-10-22 2020-08-02 2021-12-02 2020-08-23 2022-03-01 nitoring and Evaluation nvelope ques pour l'UGP BF-INSD-175426-GO-RFQ / A cquisition de fournitures de b Project Management and Mo Single Stage - One E IDA / 65730 A posteriori Demande de prix Limited 14,000.00 12,667.21 Achevé 2020-06-27 2021-09-30 2020-07-22 2021-11-17 2020-08-12 2021-12-21 ureau , consommables infor nitoring and Evaluation nvelope matiques et produits d'entre tien pour l'UGP BF-INSD-175443-GO-RFQ / A Project Management and Mo Single Stage - One E chat de logiciel de gestion co IDA / 65730 A posteriori Demande de prix Limited 25,000.00 26,132.24 Achevé 2021-05-22 2021-06-15 2021-06-29 2021-08-10 2021-07-29 2021-10-18 nitoring and Evaluation nvelope mptable et financière du proj et BF-INSD-175446-GO-RFQ / A Project Management and Mo Single Stage - One E cquisition de logiciel de suivi IDA / 65730 A posteriori Demande de prix Limited 25,000.00 26,509.54 Signé 2021-05-22 2022-04-11 2021-06-28 2022-06-07 2021-07-28 nitoring and Evaluation nvelope évaluation pour l'UGP Regional component: Harmo BF-INSD-176141-GO-RFQ / F nization, Data Collection, Qu ourniture de vaccin et de boit Single Stage - One E En attente d' IDA / 65730 ality Improvement, Dissemin A posteriori Demande de prix Limited 13,445.00 0.00 2021-04-05 2021-05-10 2021-06-09 e à pharmacie dans le cadre nvelope exécution ation and Use of Core Social des enquêtes ménages and Economic Statistics BF-INSD-176330-GO-RFQ / a Project Management and Mo Single Stage - One E cquisition de matériel de prot IDA / 65770 A posteriori Demande de prix Limited 15,265.00 0.00 Annulé 2021-01-30 2021-03-20 2021-04-10 nitoring and Evaluation nvelope ection pour l'enquête emploi et rebasage BF-INSD-176333-GO-RFQ / F Project Management and Mo Single Stage - One E ournitures d'imperméables, t IDA / 65770 A posteriori Demande de prix Limited 4,200.00 0.00 Annulé 2021-04-04 2021-05-12 2021-06-02 nitoring and Evaluation nvelope orches pour l'enquête ménag es BF-INSD-176335-GO-RFQ / F Project Management and Mo Single Stage - One E ournitures de matériels de co IDA / 65730 A posteriori Demande de prix Limited 12,899.00 0.00 Annulé 2020-08-30 2020-10-25 2020-12-24 nitoring and Evaluation nvelope llectes -balances, pesons, etc BF-INSD-215385-GO-RFQ / M Regional component: Harmo atériel de protection (imper nization, Data Collection, Qu Single Stage - One E méables, bottes, torches, la IDA / 65730 ality Improvement, Dissemin A posteriori Demande de prix Open - National 32,400.00 14,777.01 Achevé 2021-04-24 2021-06-19 2022-01-20 2021-08-03 2022-02-25 nvelope mpes) pour les enquêtes Em ation and Use of Core Social ploi, , Rebasage, ménage et - and Economic Statistics IHPC 12 Regional component: Harmo BF-INSD-177179-GO-RFQ / A nization, Data Collection, Qu chat de enquêteurs et sac po Single Stage - One E En attente d' IDA / 65730 ality Improvement, Dissemin A posteriori Demande de prix Limited 37,508.00 0.00 2021-04-04 2021-05-30 2021-06-29 ur tablette dans le cadre des nvelope exécution ation and Use of Core Social enquêtes. and Economic Statistics Regional component: Harmo BF-INSD-177186-GO-RFB / A nization, Data Collection, Qu Single Stage - One E En attente d' chat de sac enquêteurs dans IDA / 65730 ality Improvement, Dissemin A posteriori Appel d'offres Open - National 177,311.00 0.00 2021-04-21 2021-04-26 2021-07-18 2021-08-17 2021-09-21 2021-11-20 nvelope exécution le cadre de la cartographie ation and Use of Core Social and Economic Statistics BF-INSD-216310-GO-RFB / M Country-Specific Component Single Stage - One E atériel informatique au profit IDA / 65730 : Improving and modernizing A posteriori Appel d'offres Open - National 355,000.00 0.00 Annulé 2021-05-10 2021-05-15 2021-06-14 2021-06-29 2021-08-03 2021-12-01 nvelope de l’INSD physical and statistical infra structure BF-INSD-216315-GO-RFB / F Country-Specific Component ourniture, installation et mise : Improving and modernizing Single Stage - One E En attente d' IDA / 65730 A posteriori Appel d'offres Open - National 245,000.00 0.00 2021-06-01 2021-06-06 2021-07-06 2021-07-21 2021-08-25 2021-12-23 en service des équipements physical and statistical infra nvelope exécution d’interconnexion de l’INSD a structure vec les quatre DR Page 1 BF-INSD-216330-GO-RFQ / E Country-Specific Component quiper l’INSD de kit de vidéo : Improving and modernizing Single Stage - One E En attente d' IDA / 65730 A posteriori Demande de prix Limited 27,500.00 0.00 2021-06-07 2021-08-02 2021-09-16 surveillance pour renforcer la physical and statistical infra nvelope exécution sécurité des locaux structure BF-INSD-219691-GO-UN / Fo Regional component: Harmo urniture de matériels roulant nization, Data Collection, Qu Passation de marc pour l’UGP (3 véhicules et u IDA / 65730 ality Improvement, Dissemin A posteriori hés auprès des ag Direct 1,917,000.00 1,228,143.37 Achevé 2021-03-01 2021-02-25 2021-03-06 2021-07-26 2021-04-10 2021-07-27 2021-08-08 2021-08-12 ne motos) et aux structures ation and Use of Core Social ences de l'ONU de mise en œuvre. and Economic Statistics Regional component: Harmo BF-INSD-219693-GO-RFQ / F nization, Data Collection, Qu Single Stage - One E En attente d' ournitures et consommables IDA / 65730 ality Improvement, Dissemin A posteriori Demande de prix Limited 140,000.00 0.00 2021-04-04 2021-05-30 2022-05-25 nvelope exécution informatiques ation and Use of Core Social and Economic Statistics BF-INSD-238952-GO-DIR / Sé Regional component: Harmo lection d'un concessionnaire nization, Data Collection, Qu de location de véhicules sous Single Stage - One E IDA / 65730 ality Improvement, Dissemin A posteriori Demande de prix Limited 447,272.00 405,046.38 Achevé 2021-06-24 2021-06-24 2021-07-25 2021-08-30 2021-11-25 2021-12-08 forme d'accord cadre pour la nvelope ation and Use of Core Social réalisation de la 5ème enquê and Economic Statistics te démographique et de sant é du Burkina Faso (EDS/BF-5) BF-INSD-254077-NC-RFQ / A Country-Specific Component Single Stage - One E cquisition d'un logiciel pour l IDA / 65730 : Improving and modernizing A posteriori Demande de prix Limited 7,272.00 6,453.75 Achevé 2021-10-06 2022-01-28 2021-11-04 2022-03-11 2021-11-19 2022-04-27 nvelope a gestion des dossiers de l'E physical and statistical infra DSBF-V structure Regional component: Harmo BF-INSD-267618-GO-RFQ / A nization, Data Collection, Qu Single Stage - One E cquisition d'equipements aca IDA / 65730 ality Improvement, Dissemin A posteriori Demande de prix Limited 18,181.00 16,023.87 Achevé 2021-12-19 2022-01-26 2022-01-04 2022-03-10 2022-01-09 2022-04-11 nvelope démiques pour l'ISSP ation and Use of Core Social and Economic Statistics BF-INSD-281151-GO-RFQ / A Regional component: Harmo cquisition d'équipements (m nization, Data Collection, Qu Single Stage - One E atériels informatiques et mat IDA / 65730 ality Improvement, Dissemin A posteriori Demande de prix Limited 90,909.00 74,030.65 Signé 2022-03-15 2022-04-11 2022-04-11 2022-05-24 2022-05-11 nvelope ériels de bureau) au profit du ation and Use of Core Social PHASAO et pour le compte d and Economic Statistics e l'ISSP BF-INSD-283145-GO-RFQ / A cquisition de matériels et fou Project Management and Mo Single Stage - One E En attente d' IDA / 65730 A posteriori Demande de prix Limited 52,313.00 0.00 2022-04-25 2022-06-20 2022-07-11 rnitures diverses au profit de nitoring and Evaluation nvelope exécution s structures de mise en œuvr e du PHASAO Regional component: Harmo BF-INSD-283163-GO-RFQ / a nization, Data Collection, Qu Single Stage - One E En attente d' cquisition d'équipement de p IDA / 65730 ality Improvement, Dissemin A posteriori Demande de prix Limited 6,355.00 0.00 2022-04-10 2022-06-05 2022-06-26 nvelope exécution rotection contre la COVID-19 ation and Use of Core Social and Economic Statistics Regional component: Harmo BF-INSD-283169-GO-RFQ / A nization, Data Collection, Qu cquisition de consommables i Single Stage - One E En attente d' IDA / 65730 ality Improvement, Dissemin A posteriori Demande de prix Limited 10,409.00 0.00 2022-04-04 2022-05-30 2022-06-13 nformatiques (DD, DSCVM et nvelope exécution ation and Use of Core Social MENAPLN) and Economic Statistics BF-INSD-283187-GO-RFQ / a Country-Specific Component Single Stage - One E En attente d' cquisition de matériels de bu IDA / 65730 : Improving and modernizing A posteriori Demande de prix Limited 7,045.00 0.00 2022-03-30 2022-05-25 2022-07-09 nvelope exécution reau au profit des DR-INSD physical and statistical infra structure BF-INSD-283201-GO-RFQ / a Country-Specific Component Single Stage - One E En attente d' cquisition de mobiliers de bur IDA / 65730 : Improving and modernizing A posteriori Demande de prix Limited 13,600.00 0.00 2022-03-30 2022-05-25 2022-07-09 nvelope exécution eau au profits des DR-INSD physical and statistical infra structure Regional component: Harmo BF-INSD-283207-GO-RFQ / a nization, Data Collection, Qu cquisition de produit pharma Single Stage - One E En attente d' IDA / 65730 ality Improvement, Dissemin A posteriori Demande de prix Limited 10,909.00 0.00 2022-04-25 2022-06-20 2022-07-20 ceutiques au profit de la DSC nvelope exécution ation and Use of Core Social VM and Economic Statistics BF-INSD-283228-GO-DIR / Ac Country-Specific Component Passation de marc En attente d' quisition de CERTIFICAT SSL IDA / 65730 : Improving and modernizing A posteriori Direct 1,964.00 0.00 2022-04-05 2022-04-10 2022-05-01 2022-06-15 hé de gré à gré exécution de type EV physical and statistical infra structure BF-INSD-283237-GO-RFQ / a Country-Specific Component cquisition de licences Kasper : Improving and modernizing Single Stage - One E En attente d' IDA / 65730 A posteriori Demande de prix Limited 15,614.00 0.00 2022-04-16 2022-05-15 2022-05-18 sky Endpoint Security et Kas physical and statistical infra nvelope exécution persky Security for internet G structure ateway Regional component: Harmo BF-INSD-284201-GO-RFQ / A nization, Data Collection, Qu cquisition des matériels d'arc Single Stage - One E En attente d' IDA / 65730 ality Improvement, Dissemin A posteriori Demande de prix Limited 27,727.00 0.00 2022-05-10 2022-06-09 2022-07-24 hivage des questionnaires de nvelope exécution ation and Use of Core Social s recensements de 2006 and Economic Statistics BF-INSD-284209-GO-RFQ / A Regional component: Harmo cquisition de matériels d'arch nization, Data Collection, Qu Single Stage - One E En attente d' ivage numérique des actes a IDA / 65730 ality Improvement, Dissemin A posteriori Demande de prix Limited 43,636.00 0.00 2022-05-10 2022-06-02 2022-07-17 nvelope exécution dministratifs et autres docum ation and Use of Core Social ents administratifs and Economic Statistics Regional component: Harmo BF-INSD-284217-GO-RFQ / a nization, Data Collection, Qu Single Stage - One E En attente d' cquisition de fournitures pour IDA / 65730 ality Improvement, Dissemin A posteriori Demande de prix Limited 45,454.00 0.00 2022-04-09 2022-05-13 2022-06-12 nvelope exécution l'école ation and Use of Core Social and Economic Statistics BF-INSD-284265-GO-RFQ / A Project Management and Mo Single Stage - One E En attente d' IDA / 65730 A posteriori Demande de prix Limited 90,909.00 0.00 2022-04-20 2022-05-21 2022-07-20 cquisition de 25 motos pour l nitoring and Evaluation nvelope exécution 'UGP BF-INSD-284276-GO-RFQ / A cquisition de matériel d'acco Project Management and Mo Single Stage - One E En attente d' mmodation (frigos, bottes, i IDA / 65730 A posteriori Demande de prix Limited 18,818.00 0.00 2022-04-25 2022-05-26 2022-06-25 nitoring and Evaluation nvelope exécution mperméables, chaussures de sécurité, gourdes etc.) BF-INSD-284288-GO-RFQ / C onfection de gadgets (tee-shi Project Management and Mo Single Stage - One E En attente d' IDA / 65730 A posteriori Demande de prix Limited 27,272.00 0.00 2022-04-20 2022-05-28 2022-07-12 rts, casquettes, calendrier...) nitoring and Evaluation nvelope exécution pour la visibilité du Projet Page 2 BF-INSD-216319-GO-RFB / M Country-Specific Component ettre en place un centre d’ap : Improving and modernizing Single Stage - One E En attente d' IDA / 65730 A posteriori Appel d'offres Open - National 272,727.00 0.00 2021-06-08 2021-06-13 2021-07-13 2021-07-28 2021-09-01 2021-11-30 pel pour la réalisation des en physical and statistical infra nvelope exécution quêtes par téléphone structure BF-INSD-216313-GO-RFB / A Country-Specific Component Open - Internationa Single Stage - One E cquisition de logiciel pour l'IN IDA / 65730 : Improving and modernizing A posteriori Appel d'offres 602,000.00 0.00 Annulé 2021-05-17 2021-05-22 2021-07-06 2021-07-21 2021-08-25 2021-10-24 l nvelope SD physical and statistical infra structure BF-INSD-177146-GO-RFB / A Project Management and Mo Open - Internationa Single Stage - One E cquisition de divers équipem IDA / 65730 A posteriori Appel d'offres 193,277.00 0.00 Annulé 2021-05-17 2021-05-22 2021-07-06 2021-08-05 2021-09-09 2021-11-08 nitoring and Evaluation l nvelope ents d'imprimerie pour l'INSD Regional component: Harmo nization, Data Collection, Qu BF-INSD-177130-GO-RFB / A Single Stage - One E En attente d' IDA / 65730 ality Improvement, Dissemin A posteriori Appel d'offres Open - National 353,200.00 0.00 2020-06-30 2020-07-05 2020-08-04 2020-08-19 2020-09-16 2020-11-15 chat de kits solaires nvelope exécution ation and Use of Core Social and Economic Statistics Regional component: Harmo BF-INSD-229234-GO-UN / Ac nization, Data Collection, Qu quisition du matériel informa Passation de marc En attente d' IDA / 65730 ality Improvement, Dissemin A priori Direct 4,545,454.00 0.00 2021-06-01 2021-06-06 2021-07-11 2021-11-08 tique au profit pour la mise e hé de gré à gré exécution ation and Use of Core Social n œuvre du projet and Economic Statistics BF-INSD-295495-GO-RFB / A Country-Specific Component cquisition de matériels péri-i : Improving and modernizing Single Stage - One E En attente d' IDA / 65730 A posteriori Appel d'offres Open - National 663,636.00 0.00 2022-06-20 2022-06-25 2022-07-25 2022-08-01 2022-08-25 2022-10-24 nformatiques au profit des st physical and statistical infra nvelope exécution ructures de mise en œuvre d structure u PHASAO NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Regional component: Harmo BF-INSD-175402-NC-RFQ / L nization, Data Collection, Qu Single Stage - One E En attente d' ocation de bureau pour l'unit IDA / 65730 ality Improvement, Dissemin A posteriori Demande de prix Limited 30,000.00 0.00 2021-03-06 2021-04-20 2022-04-20 nvelope exécution é de gestion du projet. ation and Use of Core Social and Economic Statistics BF-INSD-177147-NC-DIR / Li Project Management and Mo Passation de marc En attente d' aison internet entre le siège IDA / 65730 A posteriori Direct 244,900.00 0.00 2021-04-01 2021-04-06 2021-05-11 2022-05-06 nitoring and Evaluation hé de gré à gré exécution de l'INSD et ses directions ré gionales Regional component: Harmo BF-INSD-215338-NC-RFQ / C nization, Data Collection, Qu ontrat d'assurances travail p Single Stage - One E En attente d' IDA / 65730 ality Improvement, Dissemin A posteriori Demande de prix Limited 75,500.00 0.00 2021-02-13 2021-04-10 2022-04-05 our les-enquêtes emploi, IHP nvelope exécution ation and Use of Core Social C et ménage and Economic Statistics BF-INSD-175435-NC-RFQ / S Project Management and Mo Single Stage - One E En attente d' ociété de gardiennage pour l IDA / 65730 A posteriori Demande de prix Limited 10,000.00 0.00 2021-04-25 2021-05-27 2023-05-27 nitoring and Evaluation nvelope exécution a sécurité des bureaux de l'U GP BF-INSD-175440-NC-RFQ / S Project Management and Mo Single Stage - One E En attente d' ociété d'entretien et de netto IDA / 65730 A posteriori Demande de prix Limited 14,000.00 0.00 2020-06-27 2020-08-03 2022-08-03 nitoring and Evaluation nvelope exécution yage des bureaux de l'UGP BF-INSD-177154-NC-RFQ / R Project Management and Mo Single Stage - One E eproduction de rapports pour IDA / 65770 A posteriori Demande de prix Limited 25,210.00 0.00 Annulé 2020-12-20 2021-02-14 2021-03-16 nitoring and Evaluation nvelope l’enquête emploi BF-INSD-177175-NC-RFQ / re Project Management and Mo Single Stage - One E IDA / 65770 A posteriori Demande de prix Limited 1,008.00 0.00 Annulé 2020-07-20 2020-09-01 2020-09-16 prographies pour ICC nitoring and Evaluation nvelope BF-INSD-216326-NC-DIR / Ex Country-Specific Component Passation de marc En attente d' ternalisation de la sauvegard IDA / 65730 : Improving and modernizing A posteriori Direct 100,000.00 0.00 2021-06-21 2021-06-26 2021-07-31 2023-07-21 hé de gré à gré exécution e des données de l’INSD (loc physical and statistical infra ation de serveur) structure Regional component: Harmo BF-INSD-219697-NC-RFQ / R nization, Data Collection, Qu eproduction des documents Single Stage - One E En attente d' IDA / 65730 ality Improvement, Dissemin A posteriori Demande de prix Limited 167,000.00 0.00 2021-04-17 2021-06-12 2022-06-07 des enquêtes financés par le nvelope exécution ation and Use of Core Social projet and Economic Statistics BF-INSD-234163-NC-DIR / An Regional component: Harmo alyse des prélèvements de s nization, Data Collection, Qu Passation de marc En attente d' ang de l'enquête démographi IDA / 65730 ality Improvement, Dissemin A posteriori Direct 118,200.00 0.00 2021-06-07 2021-06-12 2021-07-17 2021-09-15 hé de gré à gré exécution que de santé au Burkina Fas ation and Use of Core Social o EDSBF-2021 and Economic Statistics Regional component: Harmo BF-INSD-215392-NC-RFB / Lo nization, Data Collection, Qu cation de véhicules - Enquête Open - Internationa Single Stage - One E IDA / 65730 ality Improvement, Dissemin A posteriori Appel d'offres 1,038,000.00 0.00 Annulé 2021-04-23 2021-04-28 2021-06-12 2021-06-27 2021-08-01 2022-07-27 Emploi,( DGESS MENAPLN et l nvelope ation and Use of Core Social Carto) et Enquête ménage and Economic Statistics Regional component: Harmo BF-INSD-267619-NC-RFQ / R nization, Data Collection, Qu Single Stage - One E En cours d'ex eproduction des publications IDA / 65730 ality Improvement, Dissemin A posteriori Demande de prix Limited 45,455.00 40,109.46 2021-12-19 2022-01-27 2022-01-06 2022-01-11 nvelope écution de l'INSD ation and Use of Core Social and Economic Statistics BF-INSD-281153-NC-RFQ / C Regional component: Harmo onfection de gadgets pour la nization, Data Collection, Qu Single Stage - One E En attente d' visibilité de l’INSD dans le ca IDA / 65730 ality Improvement, Dissemin A posteriori Demande de prix Limited 60,000.00 0.00 2022-03-15 2022-04-11 2022-05-02 nvelope exécution dre de la mise en œuvre du P ation and Use of Core Social HASAO and Economic Statistics Regional component: Harmo BF-INSD-283204-NC-RFQ / L nization, Data Collection, Qu Single Stage - One E En attente d' ocation de véhicules au profit IDA / 65730 ality Improvement, Dissemin A posteriori Demande de prix Limited 10,909.00 0.00 2022-04-20 2022-06-15 2023-06-10 nvelope exécution du MENAPLN ation and Use of Core Social and Economic Statistics Regional component: Harmo BF-INSD-283209-NC-RFQ / E nization, Data Collection, Qu Single Stage - One E En attente d' ntretien de véhicules au profi IDA / 65730 ality Improvement, Dissemin A posteriori Demande de prix Limited 7,273.00 0.00 2022-04-04 2022-05-30 2022-11-26 nvelope exécution t du MENAPLN ation and Use of Core Social and Economic Statistics Page 3 BF-INSD-283238-NC-RFQ / C Country-Specific Component Single Stage - One E En attente d' onnexion internet haut débit IDA / 65730 : Improving and modernizing A posteriori Demande de prix Limited 32,400.00 0.00 2022-04-25 2022-05-29 2022-07-13 nvelope exécution de l'INSD physical and statistical infra structure BF-INSD-284285-NC-RFQ / M Project Management and Mo Single Stage - One E En attente d' aintenance de matériels infor IDA / 65730 A posteriori Demande de prix Limited 10,909.00 0.00 2022-05-15 2022-06-15 2022-12-12 nitoring and Evaluation nvelope exécution matiques et péri-informatiqu es Regional component: Harmo BF-INSD-284291-NC-RFQ / I nization, Data Collection, Qu Single Stage - One E En attente d' mpression des documents du IDA / 65730 ality Improvement, Dissemin A posteriori Demande de prix Limited 24,818.00 0.00 2022-07-20 2022-08-07 2022-09-06 nvelope exécution MSL et du RGA2 ation and Use of Core Social and Economic Statistics Regional component: Harmo BF-INSD-176125-NC-RFQ / a nization, Data Collection, Qu gence de communication mé Single Stage - One E En attente d' IDA / 65730 ality Improvement, Dissemin A posteriori Demande de prix Limited 286,134.00 0.00 2020-07-20 2020-09-01 2020-10-01 diatique (RGE, DSCVM-emplo nvelope exécution ation and Use of Core Social i, MENAPLN et RGA2) and Economic Statistics BF-INSD-216323-NC-DIR / Co Country-Specific Component Passation de marc En attente d' nnexion haut débit du siège IDA / 65730 : Improving and modernizing A posteriori Direct 54,545.00 0.00 2021-05-26 2021-05-31 2021-07-05 2023-06-25 hé de gré à gré exécution de l’INSD physical and statistical infra structure CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Country-Specific Component BF-INSD-177236-CS-LCS / Au Sélection au moin En attente d'exéc IDA / 65730 : Improving and modernizing A posteriori Open - National 50,000.00 0.00 2021-03-26 2021-04-16 2021-05-08 2021-05-23 2021-06-07 2021-06-29 2021-07-21 2021-09-19 dit de l'enquête ménage dre coût ution physical and statistical infra structure BF-INSD-177237-CS-LCS / Au Regional component: Harmo dit comptable, financier et de nization, Data Collection, Qu Sélection au moin passation de marchés du proj IDA / 65730 ality Improvement, Dissemin A posteriori Open - National 50,000.00 16,895.68 Signé 2020-07-15 2021-05-11 2020-08-05 2021-11-11 2020-08-27 2022-03-03 2020-09-11 2022-04-14 2020-09-26 2022-04-25 2020-10-18 2022-05-27 2020-11-09 2022-05-31 2020-12-24 dre coût et- exercie 2020, 2021 et 20 ation and Use of Core Social 22 and Economic Statistics BF-INSD-240242-CS-CQS / C Country-Specific Component onception de spots publicitair Sélection fondée s : Improving and modernizing En attente d'exéc es pour les enquêtes ménage IDA / 65760 A posteriori ur les qualification Limited 15,000.00 0.00 2021-08-14 2021-09-13 physical and statistical infra ution s, enquête emploi et enquête s des consultants structure démographique et de santé ( EDS) BF-INSD-247466-CS-CQS / S Regional component: Harmo élection d'un consultant pour nization, Data Collection, Qu Sélection fondée s En cours d'exécut l'élaboration du statut et de l IDA / 65730 ality Improvement, Dissemin A posteriori ur les qualification Open - National 36,400.00 0.00 2021-08-23 2021-10-07 2021-09-13 2021-10-07 2021-11-06 2021-12-11 2022-01-25 ion a stratégie d'abondement du ation and Use of Core Social s des consultants fond de développement de la and Economic Statistics statistique (FDS) BF-INSD-240246-CS-CQS / Él Country-Specific Component Sélection fondée s En cours d'exécut aboration de la politique de s IDA / 65730 : Improving and modernizing A posteriori ur les qualification Limited 25,000.00 0.00 2021-07-14 2021-10-07 2021-07-19 2021-08-02 2021-08-30 2021-10-29 ion écurité du système d’informa physical and statistical infra s des consultants tion structure BF-INSD-240235-CS-CQS / R Country-Specific Component Sélection fondée s ecrutement d’un cabinet pou : Improving and modernizing En cours d'exécut IDA / 65730 A posteriori ur les qualification Limited 30,000.00 26,255.19 2021-08-23 2022-04-11 2021-09-06 2022-04-11 2021-09-16 2022-05-31 2021-09-30 2022-01-28 r l’élaboration du Schéma dir physical and statistical infra ion s des consultants ecteur de l’informatique (SDI structure -2021-2025) BF-INSD-284664-CS-CQS / R Regional component: Harmo ecrutement d'un consultant p nization, Data Collection, Qu Sélection fondée s En attente d'exéc our la réalisation d'une étude IDA / 65730 ality Improvement, Dissemin A posteriori ur les qualification Open - National 36,363.00 0.00 2022-06-30 2022-07-14 2022-07-26 2022-08-05 2022-08-20 2022-10-04 ution sur la déconcentration de l'IN ation and Use of Core Social s des consultants SD and Economic Statistics BF-INSD-284945-CS-CQS / re crutement d'un consultant en Sélection fondée s Project Management and Mo vue de l'élaboration de la car IDA / 65730 A posteriori ur les qualification Open - National 57,272.00 0.00 Annulé 2022-08-10 2022-08-24 2022-09-08 2022-09-15 2022-10-04 2022-11-18 nitoring and Evaluation tographie des risques et le pl s des consultants an de mitigation du PHASAO BF-INSD-284969-CS-CQS / R Regional component: Harmo ecrutement d'un consultant p nization, Data Collection, Qu Sélection fondée s En attente d'exéc our l'élaboration d'un cadre d IDA / 65730 ality Improvement, Dissemin A posteriori ur les qualification Limited 36,363.00 0.00 2022-06-15 2022-06-29 2022-07-04 2022-07-16 2022-07-22 ution 'assurance qualité et d'un ma ation and Use of Core Social s des consultants nuel de procédures techniqu and Economic Statistics e du SSN BF-INSD-216673-CS-CQS / S Regional component: Harmo élection du consultant pour l' nization, Data Collection, Qu Sélection fondée s élaboration du statut et relec IDA / 65730 ality Improvement, Dissemin A posteriori ur les qualification Open - National 27,300.00 0.00 Annulé 2021-06-01 2021-08-10 2021-06-22 2021-11-11 2021-08-05 2021-09-04 2021-10-09 2021-12-08 ture de l'organigramme de l'I ation and Use of Core Social s des consultants NSD and Economic Statistics BF-INSD-284980-CS-CQS / re Regional component: Harmo crutement d'un consultant po nization, Data Collection, Qu Sélection fondée s En cours d'exécut ur la réalisation de la rétrosp IDA / 65730 ality Improvement, Dissemin A posteriori ur les qualification Open - National 49,818.00 0.00 2022-07-25 2022-06-22 2022-08-08 2022-08-23 2022-09-02 2022-09-17 2022-11-16 ion ective macro-économique du ation and Use of Core Social s des consultants Burkina Faso and Economic Statistics INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-INSD-177190-CS-INDV / r Country-Specific Component ecrutement d'un chef de proj IDA / 65730 : Improving and modernizing A posteriori Individuel Open 36,000.00 0.00 Annulé 2020-06-30 2020-07-26 2020-08-16 2020-09-10 2020-10-10 et physical and statistical infra structure Regional component: Harmo BF-INSD-177193-CS-INDV / R nization, Data Collection, Qu ecrutement d'un spécialiste e IDA / 65730 ality Improvement, Dissemin A posteriori Individuel Open 21,000.00 0.00 Annulé 2020-06-30 2020-07-26 2020-08-09 2020-08-31 2020-09-30 n passation de marchés ation and Use of Core Social and Economic Statistics Regional component: Harmo BF-INSD-177197-CS-INDV / R nization, Data Collection, Qu ecrutement d'un spécialiste e IDA / 65730 ality Improvement, Dissemin A posteriori Individuel Open 21,000.00 0.00 Annulé 2020-06-30 2020-08-03 2020-08-18 2020-09-04 2020-10-04 n gestion financière ation and Use of Core Social and Economic Statistics Page 4 Regional component: Harmo BF-INSD-177199-CS-INDV / R nization, Data Collection, Qu ecrutement d'un spécialiste e IDA / 65730 ality Improvement, Dissemin A posteriori Individuel Open 21,000.00 0.00 Annulé 2020-06-30 2020-07-29 2020-08-13 2020-09-04 2020-10-04 n suivi-évaluation ation and Use of Core Social and Economic Statistics Regional component: Harmo BF-INSD-177203-CS-INDV / r nization, Data Collection, Qu ecrutement d'un Auditeur Int IDA / 65730 ality Improvement, Dissemin A posteriori Individuel Open 21,000.00 0.00 Annulé 2020-06-30 2020-08-03 2020-08-18 2020-09-09 2020-10-09 erne ation and Use of Core Social and Economic Statistics BF-INSD-177204-CS-INDV / R Country-Specific Component ecrutement d'un comptable IDA / 65730 : Improving and modernizing A posteriori Individuel Open 14,000.00 0.00 Annulé 2020-06-30 2020-08-03 2020-08-17 2020-09-08 2020-10-08 pour l'UGP physical and statistical infra structure BF-INSD-177206-CS-INDV / R Country-Specific Component ecrutement d'un Assistant Ad IDA / 65730 : Improving and modernizing A posteriori Individuel Open 9,500.00 0.00 Annulé 2020-06-30 2020-08-03 2020-08-18 2020-09-09 2020-10-09 ministratif physical and statistical infra structure BF-INSD-177207-CS-INDV / R Country-Specific Component ecrutement du personnel d'a IDA / 65730 : Improving and modernizing A posteriori Individuel Limited 21,000.00 0.00 Annulé 2020-06-30 2020-07-05 2020-07-26 2020-08-30 2020-09-29 ppui pour l'UGP physical and statistical infra structure BF-INSD-177220-CS-INDV / C Country-Specific Component onsultant pour l'évaluation fi : Improving and modernizing IDA / 65770 A posteriori Individuel Limited 45,500.00 0.00 Annulé 2020-06-30 2020-07-05 2020-07-20 2020-08-11 2020-09-10 nal du SDS 2016-2020 et éla physical and statistical infra boration du SDS 2021-2025 structure Regional component: Harmo BF-INSD-177230-CS-INDV / E nization, Data Collection, Qu laboration du manuel opérati IDA / 65740 ality Improvement, Dissemin A posteriori Individuel Open 13,000.00 0.00 Annulé 2020-06-30 2020-08-03 2020-08-18 2020-09-09 2020-10-09 onnel du projet ation and Use of Core Social and Economic Statistics BF-INSD-216344-CS-INDV / C onsultant pour la formation e Regional component: Harmo n passation de marchés suiv nization, Data Collection, Qu En attente d'exéc ant le nouveau règlement de IDA / 65730 ality Improvement, Dissemin A posteriori Individuel Limited 50,000.00 0.00 2021-04-01 2021-04-06 2021-04-27 2021-06-01 2021-06-16 ution passation de marchés de la B ation and Use of Core Social anque Mondiale au profit des and Economic Statistics acteurs de la chaine de pass ation du projet BF-INSD-216671-CS-INDV / C Regional component: Harmo onsultants pour l'élaboration nization, Data Collection, Qu En attente d'exéc des cahiers de charge de la p IDA / 65730 ality Improvement, Dissemin A posteriori Individuel Open 54,500.00 0.00 2021-06-16 2021-08-04 2021-08-25 2021-09-29 2021-10-05 ution lateforme de collecte des DS ation and Use of Core Social F and Economic Statistics BF-INSD-177212-CS-INDV / S Regional component: Harmo élection de consultants indivi nization, Data Collection, Qu En attente d'exéc duels pour la formation conti IDA / 65730 ality Improvement, Dissemin A posteriori Individuel Open 28,570.00 0.00 2021-06-30 2021-08-03 2021-08-18 2021-09-09 2021-10-09 ution nue sur les nouvelles techniq ation and Use of Core Social ues de production et d'analys and Economic Statistics e des données BF-INSD-216664-CS-INDV / R Regional component: Harmo ecrutement d'un consultant p nization, Data Collection, Qu our l’élaboration d'un manuel IDA / 65730 ality Improvement, Dissemin A posteriori Individuel Open 30,250.00 15,765.46 Signé 2021-06-30 2021-06-30 2021-08-18 2022-04-27 2021-09-08 2022-05-10 2021-09-30 2022-05-24 2021-10-30 de suivi évaluation du Projet ation and Use of Core Social et la mise en place d'un disp and Economic Statistics ositif de suivi-évaluation. BF-INSD-219711-CS-INDV / C onsultant individuel pour une Project Management and Mo IDA / 65730 A posteriori Individuel Direct 22,500.00 19,689.83 Achevé 2021-02-25 2021-03-22 2021-03-07 2021-04-20 2021-03-28 2021-05-05 2021-05-02 2021-07-26 2021-08-30 2021-11-04 assistance technique en pass nitoring and Evaluation ation de marchés Regional component: Harmo BF-INSD-177233-CS-INDV / A nization, Data Collection, Qu En attente d'exéc ctualisation du schéma direct IDA / 65730 ality Improvement, Dissemin A posteriori Individuel Open 15,000.00 0.00 2020-06-30 2020-08-03 2020-08-18 2020-09-09 2020-11-08 ution eur informatique de l'INSD ation and Use of Core Social and Economic Statistics BF-INSD-216338-CS-INDV / C Country-Specific Component onsultant pour la conception : Improving and modernizing de spot publicitaire pour les IDA / 65730 A posteriori Individuel Limited 15,000.00 0.00 Annulé 2021-04-30 2021-05-05 2021-05-26 2021-06-30 2021-08-14 physical and statistical infra enquêtes ménages, enquête structure emploi et enquête démograp hique et de santé (EDS) Regional component: Harmo BF-INSD-177235-CS-INDV / A nization, Data Collection, Qu ctualisation de la politique de IDA / 65730 ality Improvement, Dissemin A posteriori Individuel Open 10,000.00 0.00 Annulé 2021-03-29 2021-05-02 2021-05-17 2021-06-08 2021-08-07 sécurité du système d'inform ation and Use of Core Social ation de l'INSD and Economic Statistics BF-INSD-216674-CS-INDV / S Regional component: Harmo élection d'un consultant pour nization, Data Collection, Qu l'élaboration du statut et de l IDA / 65730 ality Improvement, Dissemin A posteriori Individuel Open 36,400.00 0.00 Annulé 2021-06-01 2021-07-20 2021-08-10 2021-09-14 2021-11-13 a stratégie d'abondement du ation and Use of Core Social fond de développement de la and Economic Statistics statistique (FDS) BF-INSD-177214-CS-INDV / C onsultants pour réalisation d' Country-Specific Component analyses thématiques approf : Improving and modernizing IDA / 65730 A posteriori Individuel Open 25,210.00 0.00 Annulé 2021-06-08 2021-07-12 2021-07-27 2021-08-18 2021-09-17 ondies de données secondair physical and statistical infra es pour soutenir la mise en structure œuvre des politiques publiqu es BF-INSD-240207-CS-INDV / R Project Management and Mo En attente d'exéc ecrutement d’un spécialiste IDA / 65760 A posteriori Individuel Open 21,000.00 0.00 2021-06-30 2021-08-02 2021-08-09 2021-08-23 2022-08-23 nitoring and Evaluation ution en passation des marchés BF-INSD-240209-CS-INDV / R Project Management and Mo En attente d'exéc ecrutement d’un spécialiste IDA / 65760 A posteriori Individuel Open 21,000.00 0.00 2021-08-24 2021-09-26 2021-10-03 2021-10-17 2022-10-17 nitoring and Evaluation ution en gestion financière BF-INSD-240216-CS-INDV / R Project Management and Mo En attente d'exéc IDA / 65760 A posteriori Individuel Open 14,000.00 0.00 2021-08-24 2021-09-19 2021-09-26 2021-10-10 2022-10-10 ecrutement d’un comptable nitoring and Evaluation ution BF-INSD-284501-CS-CQS / R Regional component: Harmo ecrutement de consultant ind nization, Data Collection, Qu En attente d'exéc ividuel pour l'élaboration des IDA / 65730 ality Improvement, Dissemin A posteriori Individuel Open 36,363.00 0.00 2022-04-20 2022-05-23 2022-06-02 2022-06-23 2022-08-22 ution textes d'application de la nou ation and Use of Core Social velle loi statistique and Economic Statistics Page 5 BF-INSD-284544-CS-INDV / r Regional component: Harmo ecrutement d'un consultant i nization, Data Collection, Qu En attente d'exéc ndividuel pour la conception IDA / 65730 ality Improvement, Dissemin A posteriori Individuel Limited 54,545.00 0.00 2022-07-15 2022-07-20 2022-08-03 2022-08-22 2022-10-21 ution et la mise en place d'un web ation and Use of Core Social gis and Economic Statistics Regional component: Harmo BF-INSD-284547-CS-INDV / R nization, Data Collection, Qu ecrutement d'un consultant i En attente d'exéc IDA / 65730 ality Improvement, Dissemin A posteriori Individuel Limited 27,273.00 0.00 2022-07-15 2022-07-20 2022-08-03 2022-08-22 2022-10-21 ndividuel pour la mise en pla ution ation and Use of Core Social ce d'une infrastructure SIG and Economic Statistics Regional component: Harmo BF-INSD-284560-CS-INDV / R nization, Data Collection, Qu ecrutement d'un consultant i En attente d'exéc IDA / 65730 ality Improvement, Dissemin A posteriori Individuel Limited 11,454.00 0.00 2022-07-15 2022-07-20 2022-07-30 2022-08-18 2022-10-17 ndividuel pour la relecture de ution ation and Use of Core Social la charte graphique de l'INSD and Economic Statistics BF-INSD-284566-CS-INDV / r Regional component: Harmo ecrutement d'un consultant i nization, Data Collection, Qu En attente d'exéc ndividuel pour la formation d IDA / 65730 ality Improvement, Dissemin A posteriori Individuel Limited 3,818.00 0.00 2022-06-01 2022-06-06 2022-06-20 2022-07-09 2022-07-30 ution u personnel du service charg ation and Use of Core Social é de la diffusion en communi and Economic Statistics cation digitale BF-INSD-284573-CS-INDV / R ecrutement d'un consultant i Regional component: Harmo ndividuel pour former le pers nization, Data Collection, Qu En attente d'exéc onnel de l'INSD à l'édition de IDA / 65730 ality Improvement, Dissemin A posteriori Individuel Limited 8,727.00 0.00 2022-07-20 2022-07-25 2022-08-01 2022-08-20 2022-09-10 ution s documents professionnel a ation and Use of Core Social vec l'application InDesign et and Economic Statistics en infographie avec Adobe P hotoshop et Illustrator public ation BF-INSD-284581-CS-INDV / r Regional component: Harmo ecrutement d'un consultant p nization, Data Collection, Qu our faire la refonte de la plat En attente d'exéc IDA / 65730 ality Improvement, Dissemin A posteriori Individuel Limited 4,909.00 0.00 2022-08-10 2022-08-15 2022-08-29 2022-09-17 2022-11-01 eforme de diffusion des micr ution ation and Use of Core Social o-données avec l'outil NADA and Economic Statistics et former le personnel de l'IN SD aux techniques d'archiva ge BF-INSD-284675-CS-INDV / R ecrutement d'un consultant i Regional component: Harmo ndividuel pour la formation d nization, Data Collection, Qu En attente d'exéc es chauffeur de l'INSD en con IDA / 65730 ality Improvement, Dissemin A posteriori Individuel Limited 18,181.00 0.00 2022-09-15 2022-09-20 2022-09-30 2022-10-15 2022-11-05 ution duite opérationnelle de perso ation and Use of Core Social nnalité, gestion du risque séc and Economic Statistics uritaire et bonne tenue du vé hicule BF-INSD-284680-CS-INDV / R ecrutement d'un consultant p our la réalisation d'une étude Regional component: Harmo d'évaluation des performanc nization, Data Collection, Qu En attente d'exéc es de prévision des sources d IDA / 65730 ality Improvement, Dissemin A posteriori Individuel Limited 34,909.00 0.00 2022-07-15 2022-07-20 2022-07-30 2022-08-14 2022-09-28 ution e données du modèle IAP, dé ation and Use of Core Social velopper un module TCEI de l and Economic Statistics 'IAP et modéliser et construir e un module TOFE consolidé avec l’intégration des sous BF-INSD-284942-CS-INDV / R Regional component: Harmo ecrutement d'un consultant p nization, Data Collection, Qu our la réalisation d'une étude En attente d'exéc IDA / 65730 ality Improvement, Dissemin A posteriori Individuel Limited 11,454.00 0.00 2022-08-25 2022-08-30 2022-09-09 2022-09-24 2022-11-23 de faisabilité et de mise en ution ation and Use of Core Social œuvre de l'interconnexion du and Economic Statistics siège de l'INSD avec les DR-I NSD Regional component: Harmo BF-INSD-284959-CS-INDV / R nization, Data Collection, Qu ecrutement d'un consultant p En attente d'exéc IDA / 65730 ality Improvement, Dissemin A posteriori Individuel Limited 18,181.00 0.00 2022-07-01 2022-07-06 2022-07-16 2022-07-31 2022-09-14 our l'élaboration du cahier de ution ation and Use of Core Social charge de l'interfaçage and Economic Statistics Regional component: Harmo BF-INSD-284962-CS-INDV / R nization, Data Collection, Qu ecrutement d'un consultant i En attente d'exéc IDA / 65730 ality Improvement, Dissemin A posteriori Individuel Limited 36,363.00 0.00 2022-07-01 2022-07-06 2022-07-16 2022-07-31 2022-09-14 ndividuel pour la réalisation ution ation and Use of Core Social de l'interfaçage and Economic Statistics BF-INSD-284965-CS-INDV / R Regional component: Harmo ecrutement d'un consultant i nization, Data Collection, Qu En attente d'exéc ndividuel pour la formation d IDA / 65730 ality Improvement, Dissemin A posteriori Individuel Limited 7,772.00 0.00 2022-07-15 2022-07-20 2022-07-30 2022-08-14 2022-09-04 ution u personnel du service charg ation and Use of Core Social é de la diffusion en webmast and Economic Statistics er BF-INSD-284977-CS-INDV / R ecrutement d'un consultant i Project Management and Mo En attente d'exéc IDA / 65730 A posteriori Individuel Limited 9,090.00 0.00 2022-07-25 2022-07-30 2022-08-09 2022-08-24 2022-10-08 ndividuel pour l'élaboration d nitoring and Evaluation ution e la stratégie de communicat ion du projet BF-INSD-177217-CS-INDV / E Country-Specific Component valuation du plan de formatio : Improving and modernizing n 2015-2020 du personnel du IDA / 65730 A posteriori Individuel Open 31,933.00 0.00 Annulé 2021-04-28 2021-08-10 2021-06-01 2021-06-16 2021-07-03 2021-08-02 physical and statistical infra système statistique national structure et élaboration du plan de for mation 2021-2025 BF-INSD-177219-CS-INDV / E Country-Specific Component laboration et adoption du sta IDA / 65730 : Improving and modernizing A posteriori Individuel Open 25,210.00 0.00 Annulé 2021-07-12 2021-08-15 2021-08-30 2021-09-21 2021-10-21 tut particulier du statisticien physical and statistical infra structure BF-INSD-182528-CS-INDV / R Project Management and Mo IDA / 65730 A posteriori Individuel Open 9,076.00 0.00 Annulé 2021-05-28 2021-07-01 2021-07-16 2021-08-07 2021-09-06 ecrutement aide comptable. nitoring and Evaluation BF-INSD-216670-CS-INDV / R ecrutement d'un consultant i Project Management and Mo nternational pour l'appui à la IDA / 65730 A posteriori Individuel Open 27,300.00 0.00 Annulé 2021-06-22 2021-06-16 2021-08-10 2021-11-11 2021-08-31 2021-10-05 2022-02-02 nitoring and Evaluation mise en œuvre d'un système permanent d'enquêtes sur l'e mploi BF-INSD-295493-CS-CDS / R ecrutement d'experts interna Country-Specific Component tionaux en vue d’appuyer l’IN Sélection de cons : Improving and modernizing En attente d'exéc SD dans la réalisation du RG IDA / 65730 A posteriori ultants par entent Direct 115,729.00 0.00 2022-06-01 2022-06-11 2022-08-15 2023-02-11 physical and statistical infra ution E, de ENESI, de l’ICC ? dans l e directe structure a nomenclature de travail de la nouvelle base et du rebas age des comptes nationaux Page 6 BF-INSD-295497-CS-INDV / R Regional component: Harmo ecrutement d'un consultant i nization, Data Collection, Qu ndividuel pour la formation d En attente d'exéc IDA / 65730 ality Improvement, Dissemin A posteriori Individuel Limited 9,694.00 0.00 2022-07-25 2022-07-30 2022-08-09 2022-08-26 2022-09-25 es cadres de l'INSD sur les ap ution ation and Use of Core Social proches sécurisées de collect and Economic Statistics e de données et de supervisi on en milieu d'insécurité BF-INSD-216672-CS-INDV / S Regional component: Harmo election d'un consultant pour nization, Data Collection, Qu En attente d'exéc l'élaboration des projets de t IDA / 65730 ality Improvement, Dissemin A posteriori Individuel Direct 36,363.00 0.00 2021-06-01 2021-06-11 2021-07-02 2021-08-06 2021-10-05 ution extes d'application de la nou ation and Use of Core Social velle loi statistique and Economic Statistics BF-INSD-298771-CS-INDV / R ecrutement d'un consultant i Project Management and Mo En attente d'exéc ndividuel pour l'élaboration d IDA / 65730 A posteriori Individuel Limited 20,909.00 0.00 2022-06-27 2022-07-02 2022-07-16 2022-07-28 2022-09-11 nitoring and Evaluation ution e la cartographie et du plan de mitigation des risques du PHASAO Page 7