FEDERAL REPUBLIC OF NIGERIA Nigeria Erosion and Watershed Management Project (NEWMAP) PROCUREMENT PLAN I. GENERAL 1. Project information: Country: Nigeria Borrower: Federal Government of Nigeria Project Name: Nigeria Erosion and Watershed Management Project-(NEWMAP) Loan / Credit No.: PIA: National NEWMAP Coordinating Unit. 2. Bank’s approval Date of the procurement Plan: March, 2012 3. Date of General Procurement Notice: 4. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold (US$ equivalent) 1. ICB and LIB (Goods and services > 750,000.00 ALL other than consultancy services) 2. NCB 50,000.00 ≤ NONE 750,000.00 3. ICB (Works) > 5,000,000.00 ALL 4. NCB (Works) 200,000 ≤ NONE 5,000,000.00 5 Shopping-Goods < 50,000.00 NONE 6 Shopping-Works < 100,000.00 NONE 7 Training, Workshops, Study All Values Based on Tours Annual Work Plans & Budgets 2. Prequalification. Bidders for major works shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Shall apply 4. Reference to (if any) Project Operational/Procurement Manual: shall apply 5. Any Other Special Procurement Arrangements: Not Applicable 6. Procurement Packages with Methods and Time Schedule Procurement of Goods : 1 2 3 4 5 6 7 8 9 R Contract Estima Procur Prequalific Domesti Review Expecte Comment ef. (Description) ted ement ation c by Bank d s N Cost Method (yes/no) Preferen (Prior / Post) Bid- o. US$’0 ce Opening 00 (yes/no) Date 1 Computer Systems, Office, software and Accessories Computers and 684 NCB NO NO POST June 7, Procure Accessories, (see 2012 ment by remark each of software Colum) the 7 packages, Photo- SPMU & copiers, UPS, FPMU is Printers and estimate Scanners, Fax d at ( Machines, USD Laptops, 85.5) Stationeries, Consumables, LAN, Telephony,Lasers Software Licenses and Application,. 2 Office Furniture’s and Equipment Computer 680 NCB NO NO PRIOR June 7, Procure workstations and (see 2012 ment by remark each of Office Furniture Colum) the 7 Water Dispenser, SPMU & Refrigerators, FPMU is estimate Airconditioners, d at ( Tables, Chairs, etc USD 85) 3 Operational Vehicles 4-WD Vehicles (32 1440 NCB NO NO PRIOR June 7, Procure units) (see 2012 ment by remark each of Colum) the 7 SPMU & FPMU is estimate d at (180USD 4 Generator 40KVA Sound-Proof 240 NS NO NO PRIOR June 7, Procure Electricity (see 2012 ment by Generating Set- remark each of Purchase and Colum) the 7 Installation (8 SPMU & units) FPMU is estimate d at (30 USD 5 Training Communication, Presentation, Media Equipment and materials, etc Multimedia 364 NS NO NO PRIOR June 7, Procure Projectors, (see 2012 ment by remark each of Flip Chart Colum) the 7 Stands, Boards, SPMU & GSM FPMU is TV/Video/Radio/R estimate ecorders and d at Digital Cameras, (45.5 Internet Facilities, USD GPS, Raincoats and Enumerators bags, Program information kit, Program posters Community oriented Implementation manual 6 Field Equipment Purchase of 2,400 NCB NO NO PRIOR June 7, Procure Weather (see 2012 ment by Monitoring remark each of Stations, GPSs, Colum) the 7 Laser Measures, SPMU & Measuring Wheels, FPMU is 1-2km Range estimate Radios and other d at (300 survey equipment USD and tools to gauge and trace watershed, terrestrial carbon and water flow 7 Geographic Information System Purchase of GIS 3520 NCB NO NO PRIOR June 7, Procure data/Satellite (see 2012 ment by Imagery,, remark each of Overhead Colum) the 7 photography, etc SPMU & FPMU is estimate d at (440 USD Sub Total 9,328. 00 Procurement of Civil Works 1 2 3 4 5 6 7 8 9 Ref Contract Estimat Procur Prequalific Domesti Review Expecte Comment . (Description) ed ement ation c by Bank d s No. Cost Metho (yes/no) Preferen (Prior / Post) Bid- US$’00 d ce Opening 0 (yes/no) Date 1 Civil works, and 252,000. ICB NO YES PRIOR October Procure maintenance of 00 12, ment by flood and gully 2012 ICB for erosion sites all 7 SPMU 2 Office 240,000 NS NO NO PRIOR July, accommodation 2012 for 7 SPMU & FPCU SUB TOTAL 252,240 .00 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1 Consultant Services-QCBS- All Values ALL International 2 Consultant Services-QCBS- > 200,000.00 ALL National 3 Consultant Services-CQS < 200,000.00 NONE 4 Consultant Services-lC > 50,000.00 ALL 5 Consultant Services-lC < 50,000.00 ToR only but ALL 6 Consultant Services- Single All Values ALL Source Selection Note: All ToRs to be prior review QCBS = Quality and Cost Based Selection SSS = Single Source Selection CQ = Consultant Qualification LCS = Least Cost Selection IC = Individual Consultant 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $200,000.00 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: NA 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 7 Ref Description of Estimat Selecti Review Expected Comment . Assignment ed on by Bank Proposal s No. Metho (Prior / s Cost. d Post) Submissi US$’0 on 00 Date 1 Consultancy for the 3,395.24 QCBS Prior On-going Consultancy detailed Engineering (see for Priority designs and data remark sites by each collation for 35 sites Colum of the 7 SPMU (see each State Proc. Plan). 2 Consultancy for the 6,824.47 QCBS Prior September Consultancy supervision of Civil (see 2012 for Priority Works for 35sites remark sites by each Colum of the 7 SPMU (see each State Proc. Plan). 3 Consultancy for the RAP 875.00 IC Prior On-going Consultancy study for 35 sites (see for Priority remark sites by each Colum of the 7 SPMU is estimated at (25 USD. 4 Consultancy for the ESIA 875.00 IC Prior On-going Consultancy study for 35 sites (see for Priority remark sites by each Colum of the 7 SPMU is estimated at (25 USD. 5 Consultancy for the 875.00 IC Prior On-going Consultancy Socio-Economic study 35 (see for Priority sites remark sites by each Colum of the 7 SPMU is estimated at 25 USD per site 6 Consultancy for GIS data 875.00 IC Prior On-going Consultancy collection and Mapping (see for Priority for 35 sites remark sites by each Colum of the 7 SPMU is estimated at 75 USD per site 7 Consultancy for the 3500.00 QCBS Prior August, Consultancy detailed Engineering (see 2012 for 5 designs and data remark additional collation for additional Colum sites by each 35sites of the 7 SPMU is estimated at 100 USD per site 8 Consultancy for the 2625.00 QCBS Prior June, 2013 Consultancy detailed ESIA, RAP and (see for 5 Socio Economic Studies remark additional for additional 35 sites Colum sites by each of the 7 SPMU is estimated at 75 USD per site 9 Environmental 800 QCBS 9 engineering and design consultancy, 10 Procurement consultancy 800 QCBS 10 June 1012 for support of FPMU and SPMUs 11 M&E consultancy 400 QCBS 11 12 Consultancy for the 800.00 QCBS 12 Sept., 2012 Consultancy support of SPMUs and (see by each of FPMU remark the 7 SPMU Colum & FPMU is estimated at (100 USD 13 Consultancy for Legal 800.00 IC 13 Sept., 2012 Consultancy Services (see by each of remark the 7 SPMU Colum & FPMU is estimated at (100 USD 14 Consultancy for 3500.00 14 Sept., 2012 Consultancy valuation and (see by each of resettlement remark the 7 SPMU, implementation Colum to cover all sites is estimated at (500 USD per SPMU 15 Consultancy for Training 1600.00 QCBS Prior August, Consultancy and Capacity Building (see 2012 by each of remark the 7 SPMU Colum & FPMU is estimated at (200 USD 16 Consultancy-External 400.00 QCBS Prior March, Consultancy Auditor (see 2013 by FPMU to remark cover each Colum SPMU 17 Consultancy on 800.00 IC Prior Sept., 2012 Consultancy Community consultation, (see by each of Public Education and remark the 7 SPMU Erosion Management Colum & FPMU is and awareness estimated at Techniques, (100 USD Sub Total 27,744. 71 IV. Implementing Agency Capacity Building Activities with Time Schedule 1. In this section the agreed Capacity Building Activities are listed with time schedule below; No. Expected outcome / Estimated Estimate Start Date Com Activity Description Cost US$ d m ‘000 Duration e n t s A. TRAINING 1 3. Nos. Training courses August Capacity for PMU staff; Project 2012 Building Coordinator, activities for Procurement Specialist, each of the 7 SPMU & FPMU and financial mgt, M&E, is estimated at Environmental (90 USD specialists, Communication, 720.00(see Livelihood, Engineering remark 2WKS, specialists Colum each 2 August Capacity 2012 Building activities for Training of project each of the 7 finance staff(FMS, APA, 160.00(see SPMU & FPMU FO, IA) on flexible remark is estimated at accounting software Colum 1wk (20 USD B. WORKSHOP 3 Septembe Capacity r 2012 Building activities for each of the 7 240.00(see SPMU & FPMU Capacity Building for remark is estimated at key stakeholders Colum 3 days (30 USD 4 Septembe Capacity r, 2012 Building activities for each of the 7 160(see SPMU & FPMU remark is estimated at ICT Training Colum 1 wk (20 USD 5 Various Capacity Building activities for each of the 7 Professional 120.00(see SPMU & FPMU Seminars/Workshops/ remark is estimated at subscriptions Colum Various (15 USD 6 Septembe Capacity r 2012 Building 2 Days Sensitization/ activities for Workshop for State and each of the 7 Local Govt. Officials on 200.00(see SPMU & FPMU erosion and watershed remark is estimated at management Colum 2 days (25 USD 7 October Capacity 2012 Building 3 Day workshop for Line activities for Ministries and MDAs on each of the 7 addressing and 240.00(see SPMU & FPMU prevention of Land remark is estimated at Degradation Colum 3- days (30 USD 8 3 Day workshop for local October Capacity 2012 Building Govt. Focal Persons and activities for Community Erosion each of the 7 watch Dogs on 240.00(see SPMU & FPMU prevention of erosion remark is estimated at and land degradation Colum 3-days (30 USD 9 2013 Capacity Building activities for each of the 7 Capacity Building on use 200.00(see SPMU & FPMU of Metrological and GPS remark is estimated at Equipment Colum 5-days (25 USD C. STUDY/TOURS 10 240.00(see Various October Capacity remark times 2012 Building Colum activities for Baseline survey/ each of the 7 Community needs SPMU & FPMU assessment and is estimated at capacity building (30 USD 11 240.00(see Various August, Capacity remark times 2012 Building Colum activities for each of the 7 Sensitization/ SPMU & FPMU Awareness creation of is estimated at NEWMAP in the 18 LGA (30 USD 12 160.00(see WB and Capacity remark FAO to Building Colum determin activities for Participation in each of the 7 watershed studies e SPMU & FPMU organized by the world is estimated at bank and FAO (20 USD 13 240.00(see Various December Capacity remark , 2012 Building Colum activities for each of the 7 SPMU & FPMU Launching of ESIA and is estimated at RAP for priority sites (30 USD 14 160.00(see Various Oct., Capacity remark 2012 Building Colum activities for each of the 7 SPMU & FPMU is estimated at livelihood studies (20 USD 15 160.00(see Various World Capacity remark Bank Building Colum determine activities for Participation in each of the 7 Biodiversity/forest d SPMU & FPMU carbon study organized is estimated at by the World Bank (20 USD 16 120.00(see 4-days July 2012 Capacity remark each Building Colum activities for each of the 7 Recognizance survey of SPMU & FPMU Project sites (Erosion is estimated at and Watershed) (15 USD 17 2480.00(se 4-wks February., Capacity e remark 2013 Building International Training Colum activities for and study tours each of the 7 SPMU & FPMU is estimated at (310 USD 18 Various World Capacity Bank Building determine activities for Attendance of World each of the 7 Bank Organized d 800.00(see SPMU & FPMU training, meetings, remark is estimated at seminar and workshops Colum (100 USD Sub Total 6,880.00 PROCUREMENT Nigeria : Nigeria Erosion and Watershed Management Project PLAN General Information Country: Nigeria Bank’s Approval Date of the Original Procurement Plan: 2017-07-14 2022-02-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P124905 GPN Date: Project Name: Nigeria Erosion and Watershed Management Project Loan / Credit No: IDA / 51050, IDA / 62770 NEWMAP - Federal Projects Management Unit Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-NEWMAP-FPMU-78533- Component 2: Erosion and CW-RFB / Rehabilitation and Watershed Management Single Stage - One 2019-12- development of underground IDA / 51050 Post Request for Bids Open - National 450,000.00 54,209.06 Completed 2019-03-12 2019-04-22 2019-03-17 2019-04-28 2019-05-20 2019-05-28 2019-05-20 2019-07-02 2019-07-24 Institutions and Information Envelope 29 water monitoring systems Services (including instrumentation) NG-NEWMAP-FPMU-102206- Component 4: Project Request for Single Stage - One 2019-11- CW-RFQ / Renovation of New IDA / 51050 Post Limited 100,000.00 80,589.08 Signed 2019-04-02 2019-04-05 2019-05-28 2019-04-24 Management Quotations Envelope 24 and Old Offices NG-NEWMAP-FPMU-115677- Pending CW-RFB / Rehabilitation and Component 4: Project Single Stage - One 2020-05- IDA / 51050 Post Request for Bids Open - National 3,000,000.00 0.00 Implementat 2019-07-15 2019-07-20 2019-08-31 2019-09-30 2019-11-04 Renovation of EIA Building Management Envelope 02 ion FMEVN NG-NEWMAP-FPMU-154708- CW-RFQ / Procurement and Component 3: Climate Request for Single Stage - One 2020-03- Installation of solar-powered IDA / 51050 Post Limited 180,000.00 156,548.92 Completed 2020-01-29 2020-03-27 2020-02-24 2020-04-20 Change Response Quotations Envelope 30 borehole and installation of drip irrigation system NG-NEWMAP-FPMU-154901- CW-RFQ / Procurement of Bamboo Charcoal making machines(including Housing Component 3: Climate Request for Single Stage - One 2020-03- IDA / 51050 Post Limited 180,000.00 141,023.56 Signed 2020-01-27 2020-03-27 2020-02-25 2020-04-20 and Installation) &Provision of Change Response Quotations Envelope 25 solar-powered borehole in an identified community in Abia State. NG-NEWMAP-FPMU-154971- CW-RFQ / Procurement of solar meat driers and Component 3: Climate Request for Single Stage - One 2020-03- IDA / 51050 Post Limited 180,000.00 156,426.60 Completed 2020-02-05 2020-03-27 2020-02-24 2020-04-20 construction of fuel-efficient Change Response Quotations Envelope 30 kilns with Motorised Borehole and overhead tank. NG-NEWMAP-FPMU-154644- CW-RFQ / Provision & Installation of a solarized Component 3: Climate Request for Single Stage - One 2020-06- cassava-processing machines IDA / 51050 Post Limited 120,000.00 117,330.01 Signed 2020-03-31 2020-03-27 2020-05-12 2020-04-20 Change Response Quotations Envelope 09 with Housing for smallholder farmers in identified community in Kogi State NG-NEWMAP-FPMU-154642- CW-RFQ / Procurement and Installation of 3X10kw Solar Component 3: Climate Single Stage - One 2020-06- IDA / 51050 Post Request for Bids Open - National 300,000.00 210,735.37 Signed 2020-03-31 2020-04-29 2020-04-07 2020-04-21 2020-05-15 2020-05-05 2020-06-18 2020-05-19 2020-07-20 off-grid stand-alone system Change Response Envelope 19 for the identified Community in kogi State NG-NEWMAP-FPMU-165878- CW-RFB / Establishment of 8Nos additional underground Component 2: Erosion and Water Monitoring Wells across Watershed Management Single Stage - One 2020-12- IDA / 51050 Post Request for Bids Open - National 300,000.00 41,269.63 Signed 2020-08-12 2020-11-20 2020-08-19 2020-09-02 2020-12-09 2020-09-16 2020-12-09 2020-09-30 2021-04-08 5 Hydrological Areas and Institutions and Information Envelope 30 application soft wares for Services underground water resources monitoring and development NG-NEWMAP-FPMU-154974- CW-RFQ / Building of demonstration fish iNo. farm Component 3: Climate Single Stage - One 2020-07- IDA / 51050 Post Request for Bids Open - National 240,000.00 188,799.42 Signed 2020-04-10 2020-04-29 2020-04-17 2020-05-04 2020-05-15 2020-05-18 2020-06-18 2020-06-01 2020-07-20 and Procurement and Change Response Envelope 14 installation of Solar fish driers with borehole in Sokoto State NG-NEWMAP-FPMU-154649- CW-RFQ / Procurement and Installation of 2x10kw Solar Component 3: Climate Single Stage - One 2020-06- IDA / 51050 Post Request for Bids Open - National 200,000.00 158,343.25 Completed 2020-04-06 2020-04-29 2020-04-13 2020-04-27 2020-05-15 2020-05-11 2020-06-18 2020-05-25 2020-07-20 power with infrastructure for Change Response Envelope 25 identified Primary Health Care Centre in Nasarawa State NG-NEWMAP-FPMU-154818- CW-RFQ / Construction of solar-powered Borehole and Component 3: Climate Single Stage - One 2020-08- IDA / 51050 Post Request for Bids Open - National 240,000.00 205,114.25 Signed 2020-04-12 2020-04-29 2020-04-19 2020-05-04 2020-05-15 2020-05-18 2020-06-18 2020-06-01 2020-07-20 overhead tank, irrigation Change Response Envelope 03 equipment & Installation of Green House in Plateau State NG-NEWMAP-FPMU-264265- Request for Bids - CW-RFB / Office Space Pending Component 4: Project Single Stage - One Works (without 2022-04- Renovation/ Rehabilitation IDA / 51050 Post Request for Bids Limited 500,000.00 0.00 Implementat 2021-12-01 2021-12-06 2022-01-17 2022-02-01 2022-02-15 Management Envelope prequalification) 16 UNILAG & Installation of Solar ion SPD Power GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 NG-NEWMAP-FPMU-19584- GO-RFQ / Production of IEC Materials & Newsletters on Component 4: Project Request for Single Stage - One IDA / 51050 Post Open - National 96,000.00 72,839.57 Completed 2017-07-30 2017-09-24 2019-04-10 2018-03-23 2019-05-02 Activities of NEWMAP (for Management Quotations Envelope Awareness Raising and Advocacy purposes) NG-NEWMAP-FPMU-19572- Component 2: Erosion and GO-RFB / Procurement of Watershed Management Single Stage - One statistical and analytical IDA / 51050 Post Request for Bids Open - National 250,000.00 167,072.74 Completed 2017-08-07 2019-04-22 2017-08-12 2017-09-23 2019-05-13 2017-10-23 2019-05-15 2017-11-27 2019-07-09 2018-05-26 2019-09-20 Institutions and Information Envelope software tools and equipment Services for DPRS of the FMEnv Component 2: Erosion and NG-NEWMAP-FPMU-19537- Watershed Management Single Stage - One GO-RFB / Upscaling of IDA / 51050 Post Request for Bids Open - National 138,000.00 0.00 Canceled 2017-07-24 2017-07-29 2017-09-09 2017-10-09 2017-11-13 2018-05-12 Institutions and Information Envelope National EA Portal Services NG-NEWMAP-FPMU-19516- GO-RFB / Operationalisation Component 3: Climate Single Stage - One of National Climate Change IDA / 51050 Post Request for Bids Open - National 175,000.00 0.00 Canceled 2017-08-16 2017-08-21 2017-10-02 2017-11-01 2017-12-06 2018-06-04 Change Response Envelope GHG Data Management System- NG-NEWMAP-FPMU-19527- Pending Component 4: Project Request for Single Stage - One GO-RFQ / Procurement of ICT IDA / 51050 Post Open - National 40,000.00 0.00 Implementati 2017-07-22 2017-09-16 2018-03-15 Management Quotations Envelope equipment for GEF desk office on NG-NEWMAP-FPMU-83102- GO-RFQ / Stationaries, File Component 3: Climate Request for Single Stage - One Jackets, Folders & Branded IDA / 51050 Post Limited 5,000.00 3,963.41 Signed 2019-01-28 2020-01-13 2019-03-25 2020-02-06 2019-09-21 Change Response Quotations Envelope Notepads,Green Bond Secretariat. NG-NEWMAP-FPMU-83087- GO-RFQ / Support to Steering Component 4: Project Request for Single Stage - One IDA / 51050 Post Limited 486,000.00 372,926.16 Completed 2019-02-15 2018-10-10 2019-04-12 2019-08-15 2019-10-09 2019-08-21 committee (FMenv), Management Quotations Envelope Procurement of 2No. SUVs NG-NEWMAP-FPMU-83059- Component 3: Climate Request for Single Stage - One GO-RFQ / Nigeria's Green IDA / 62770 Post Limited 98,360.00 70,647.89 Completed 2019-02-17 2019-05-07 2019-04-14 2019-05-30 2019-10-11 2019-08-08 Change Response Quotations Envelope Bond Story NG-NEWMAP-FPMU-83090- Component 3: Climate Request for Single Stage - One GO-RFQ / Prospectus Green IDA / 51050 Post Limited 8,196.00 6,496.82 Signed 2019-01-26 2020-01-17 2019-03-23 2020-01-30 2019-09-19 Change Response Quotations Envelope Bond Second Issuance. NG-NEWMAP-FPMU-83085- GO-RFQ / Procurement of 1 Pending Component 3: Climate Request for Single Stage - One No. 16 Seater Bus for Green IDA / 51050 Post Limited 91,803.00 0.00 Implementati 2019-02-02 2019-03-30 2019-09-26 Change Response Quotations Envelope Bond Monitoring & verification on of Projects. NG-NEWMAP-FPMU-83091- Pending Component 3: Climate Request for Single Stage - One GO-RFQ / Green Bond Manual IDA / 51050 Post Limited 3,279.00 0.00 Implementati 2019-02-23 2019-04-20 2019-10-17 Change Response Quotations Envelope Green Bond Second Issuance. on NG-NEWMAP-FPMU-83060- GO-RFQ / Procurement of Component 4: Project Request for Single Stage - One IDA / 51050 Post Limited 166,000.00 137,646.00 Completed 2019-02-02 2019-01-31 2019-03-30 2019-02-28 2019-09-26 2019-03-15 2No. 4x4wd Pick Up Van for Management Quotations Envelope FPMU NG-NEWMAP-FPMU-83113- GO-RFQ / Facts behind the Component 3: Climate Request for Single Stage - One IDA / 51050 Post Limited 3,279.00 2,580.33 Signed 2019-04-24 2020-01-06 2019-06-19 2020-01-30 2019-12-16 figures Green Bond Second Change Response Quotations Envelope Issuance. NG-NEWMAP-FPMU-83066- GO-RFQ / Procurement of 3 Component 3: Climate Request for Single Stage - One No. professional Still cameras IDA / 51050 Post Limited 3,442.00 2,599.23 Signed 2019-03-04 2020-01-16 2019-04-29 2020-02-06 2019-10-26 Change Response Quotations Envelope with high resolution for Green Bond Secretariat. NG-NEWMAP-FPMU-102202- GO-RFQ / Production of Component 3: Climate Request for Single Stage - One IDA / 51050 Post Limited 50,000.00 46,875.08 Signed 2019-04-14 2021-12-03 2019-06-09 2021-12-14 2019-12-06 guidance manual  for Climate Change Response Quotations Envelope Change response  Agenda NG-NEWMAP-FPMU-102207- Pending Component 4: Project Request for Single Stage - One GO-RFQ / Office Equipment IDA / 51050 Post Limited 350,000.00 0.00 Implementati 2019-03-05 2019-04-30 2019-10-27 Management Quotations Envelope and Furniture on NG-NEWMAP-FPMU-103297- Component 4: Project Request for Single Stage - One GO-RFQ / Office IDA / 51050 Post Limited 30,000.00 26,851.27 Signed 2019-06-05 2021-05-25 2019-07-31 2021-06-18 2019-10-22 Management Quotations Envelope Consumables. NG-NEWMAP-FPMU-127610- Pending GO-RFQ / Procurement 2No. Component 4: Project Request for Single Stage - One IDA / 51050 Post Limited 166,000.00 0.00 Implementati 2019-10-21 2019-11-20 2019-12-04 4x4wd Pick Up Vans for EA Management Quotations Envelope on Department, FMENV NG-NEWMAP-FPMU-165802- Component 3: Climate Request for Single Stage - One GO-RFQ / Production of Bio IDA / 51050 Post Limited 30,000.00 26,943.22 Completed 2020-07-07 2021-09-10 2020-08-04 2021-09-30 2020-09-04 2021-11-12 Change Response Quotations Envelope Engineering Manual NG-NEWMAP-FPMU-165861- Component 2: Erosion and GO-RFQ / Procurement of Set- Watershed Management Request for Single Stage - One up -3 High Configuration IDA / 51050 Post Limited 86,000.00 79,012.36 Signed 2020-04-13 2021-04-27 2020-05-19 2021-05-27 2020-06-02 Institutions and Information Quotations Envelope Server and Installation of Services Network Devices NG-NEWMAP-FPMU-165876- GO-RFQ / Procurement, Pending installation of furniture’s and Component 4: Project Request for Single Stage - One IDA / 51050 Post Limited 78,000.00 0.00 Implementati 2020-04-13 2020-05-19 2020-06-02 office equipment’s at the new Management Quotations Envelope on office Administration block and laboratory (UNILAG) Page 2 NG-NEWMAP-FPMU-165854- GO-RFB / Procurement and Component 4: Project Single Stage - One Installation of Computer & IDA / 51050 Post Request for Bids Open - National 390,000.00 299,452.51 Signed 2020-04-22 2020-11-23 2020-04-29 2020-05-13 2020-12-09 2020-05-27 2020-12-09 2020-06-10 2021-02-24 2020-07-24 Management Envelope ICT Equipments (for FPMU & UNILAG) NG-NEWMAP-FPMU-165855- GO-RFB / Procurement and Installation of GIS Equipment Component 4: Project Single Stage - One IDA / 51050 Post Request for Bids Open - National 325,000.00 159,948.10 Signed 2020-05-10 2021-01-15 2020-05-17 2020-05-31 2021-02-08 2020-06-22 2021-02-08 2020-07-06 2021-05-24 2020-09-07 & Software for FPMU, DFECZM Management Envelope & UNILAG, including Tilia Licences for UNILAG NG-NEWMAP-FPMU-165862- GO-RFB / Procurement and Component 2: Erosion and Installation of Geochemical , Pending Watershed Management Single Stage - One Hydrological ,Chemical Lab, IDA / 51050 Post Request for Bids Open - National 420,884.75 0.00 Implementati 2020-05-14 2020-05-21 2020-06-11 2020-06-25 2020-07-09 2020-10-02 Institutions and Information Envelope Air Pollution , and Heavy Metal on Services Equipment for Unilag Centre of Excellence. NG-NEWMAP-FPMU-165852- GO-RFQ / Procurement and Component 4: Project Request for Single Stage - One IDA / 51050 Post Limited 30,000.00 0.00 Canceled 2020-04-13 2020-05-19 2020-06-02 installation of 1 No. 100KVA Management Quotations Envelope Generator (UNILAG) . NG-NEWMAP-FPMU-262352- Pending Component 4: Project Single Stage - One GO-RFB / Acquisition of E- IDA / 51050 Post Request for Bids Limited 500,000.00 0.00 Implementati 2021-11-29 2021-12-06 2022-01-06 2022-01-25 2022-01-30 2022-04-30 Management Envelope Procurement System on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-NEWMAP-FPMU-19582- Component 2: Erosion and NC-RFB / Consultancy Watershed Management Single Stage - One IDA / 51050 Post Request for Bids Open - National 250,000.00 304,222.46 Signed 2017-07-03 2016-09-14 2017-07-08 2017-08-19 2016-12-09 2017-09-18 2017-08-22 2017-10-23 2018-01-17 2018-04-21 Services for EA Archiival Institutions and Information Envelope Digital cataloguing Services NG-NEWMAP-FPMU-19575- Component 2: Erosion and NC-RFB / Bathymetry & Watershed Management Single Stage - One Geomorphological Study of IDA / 51050 Post Request for Bids Open - International 1,400,000.00 811,120.04 Completed 2017-07-03 2015-05-08 2017-07-08 2017-08-19 2019-06-11 2017-09-18 2019-06-11 2017-10-23 2016-01-13 2018-04-21 2017-08-17 Institutions and Information Envelope the River Benue System & Services Kiridam NG-NEWMAP-FPMU-102204- NC-RFQ / Engagement of a Pending Component 4: Project Request for Single Stage - One service provider for the IDA / 51050 Post Limited 20,000.00 0.00 Implementati 2019-04-03 2019-05-29 2019-11-25 Management Quotations Envelope maintenance of Project on Vehicles CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-NEWMAP-FPMU-19512- Component 4: Project Quality And Cost- Pending CS-QCBS / Extension of IDA / 51050 Post Open - International 1,500,000.00 0.00 2017-09-29 2017-10-20 2017-12-03 2017-12-31 2018-01-30 2018-03-06 2018-04-10 2019-04-10 Management Based Selection Implementation Procurement Consultancy Firm NG-NEWMAP-FPMU-19567- CS-QCBS / Consulting services for the development of framework for the adoption Component 3: Climate Quality And Cost- IDA / 51050 Prior Open - International 3,500,000.00 3,011,027.28 Signed 2017-02-06 2017-02-27 2017-04-12 2017-05-10 2017-06-09 2017-07-14 2018-01-09 2017-08-18 2018-01-29 2018-08-18 of LPG as Low Carbon Change Response Based Selection Alternative to Firewood and Kerosene and Supervision of the Implementation. NG-NEWMAP-FPMU-19578- CS-QCBS / Federal quality Component 1: Erosion and Quality And Cost- Under control and engineering IDA / 51050 Watershed Management Prior Open - International 3,000,000.00 0.00 2017-07-17 2019-01-22 2017-08-07 2019-02-05 2017-09-20 2019-04-10 2017-10-18 2019-07-16 2017-11-17 2019-10-18 2017-12-22 2020-08-24 2018-01-26 2019-01-26 Based Selection Implementation design firm of erosion control Infrastructure Investments sites Old and New States. NG-NEWMAP-FPMU-19589- CS-QCBS / Procurement of Component 4: Project Quality And Cost- IDA / 51050 Prior Open - International 2,000,000.00 1,305,683.21 Signed 2017-09-29 2018-08-12 2017-10-20 2019-02-05 2017-12-03 2019-04-10 2017-12-31 2019-07-18 2018-01-30 2019-10-01 2018-03-06 2020-01-16 2018-04-10 2020-01-27 2019-04-10 Procurement firm in Old and Management Based Selection New States. NG-NEWMAP-FPMU-19580- CS-QCBS / Spatial Baseline Modelling of Electricity Infrastructure for Remote and Component 3: Climate Quality And Cost- IDA / 51050 Prior Open - International 3,000,000.00 0.00 Canceled 2017-07-26 2017-08-16 2017-09-29 2017-10-27 2017-11-26 2017-12-31 2018-02-04 2019-02-04 Off-Grid Power Supply and Change Response Based Selection Demonstration Projects on Low Carbon Off-Grid/mini- grid options NG-NEWMAP-FPMU-19586- CS-CQS / Technology Needs Consultant Component 3: Climate Assessment for Climate IDA / 51050 Post Qualification Open - National 100,000.00 0.00 Canceled 2017-07-22 2017-08-12 2017-09-25 2017-10-25 2017-11-29 2018-05-28 Change Response Change in Nigeria Towards Selection low Carbon Development NG-NEWMAP-FPMU-19533- Consultant Component 3: Climate CS-CQS / Development of IDA / 51050 Post Qualification Open - National 100,000.00 0.00 Canceled 2017-07-22 2017-08-12 2017-09-25 2017-10-25 2017-11-29 2018-05-28 Change Response Climate Smart Agriculture. Selection NG-NEWMAP-FPMU-19585- CS-CQS / Procurement of Component 2: Erosion and Consultant Consultant for the Spatial Watershed Management IDA / 51050 Post Qualification Open - National 290,000.00 0.00 Canceled 2017-08-21 2017-09-11 2017-10-25 2017-11-24 2017-12-29 2018-06-27 Knowledge Information Institutions and Information Selection System on Erosion and Services Watershed Page 3 Component 2: Erosion and NG-NEWMAP-FPMU-19561- Watershed Management Quality And Cost- CS-QCBS / Engagement of IDA / 51050 Prior Open - International 500,000.00 0.00 Canceled 2017-03-20 2017-04-10 2017-05-24 2017-06-21 2017-07-21 2017-08-25 2017-09-29 2018-09-29 Institutions and Information Based Selection IUCN Services NG-NEWMAP-FPMU-19530- CS-QCBS / Vulnerability Component 3: Climate Quality And Cost- IDA / 51050 Prior Open - International 500,000.00 0.00 Canceled 2017-09-04 2017-09-25 2017-11-08 2017-12-06 2018-01-05 2018-02-09 2018-03-16 2019-03-16 Mapping and Action Plan for Change Response Based Selection Nigeria. NG-NEWMAP-FPMU-83088- CS-QCBS / Strategy Development for the Component 3: Climate Quality And Cost- Pending Commercialization of 50 Nos. IDA / 51050 Prior Open - International 3,901,095.00 0.00 2019-03-20 2019-04-10 2019-05-24 2019-06-21 2019-07-21 2019-08-25 2019-09-29 2020-09-28 Change Response Based Selection Implementation Flared Associated Gas Sites in Crude Oil Exploration in Nigeria NG-NEWMAP-FPMU-100131- Component 2: Erosion and CS-QCBS / Procurement of an Watershed Management Quality And Cost- Under IDA / 51050 Prior Open - International 900,000.00 0.00 2019-02-14 2019-03-19 2019-03-07 2019-05-18 2019-04-20 2019-12-31 2019-05-18 2020-06-06 2019-06-17 2020-08-14 2019-07-22 2020-08-27 2019-08-26 2020-08-25 Umbrella NGO for the Old and Institutions and Information Based Selection Implementation New States of NEWMAP Services NG-NEWMAP-FPMU-98274- Consultant Component 3: Climate Pending CS-CDS / Legal Adviser Green IDA / 51050 Post Qualification Open - National 82,000.00 0.00 2019-02-15 2019-03-08 2019-04-21 2019-05-21 2019-06-25 2019-12-22 Change Response Implementation Bond Second Issuance. Selection NG-NEWMAP-FPMU-102209- CS-QCBS / Consultancy services for the Study of the Component 3: Climate Quality And Cost- adoption of gas based (CNG IDA / 51050 Prior Open - International 3,300,000.00 2,764,249.57 Signed 2019-05-29 2019-07-30 2019-06-19 2019-10-21 2019-08-02 2020-08-13 2019-08-30 2020-10-07 2019-09-29 2021-06-09 2019-11-03 2021-11-05 2019-12-08 2021-11-26 2020-12-07 Change Response Based Selection and LPG) fuels in road transportation and carbon capture sequenstration. NG-NEWMAP-FPMU-19531- Component 2: Erosion and CS-QCBS / Engagement of an Watershed Management Quality And Cost- IDA / 51050 Prior Open - International 600,000.00 0.00 Canceled 2017-09-29 2018-01-15 2017-10-20 2017-12-03 2017-12-31 2018-01-30 2018-03-06 2018-04-10 2019-04-10 Umbrella NGO in Old and New Institutions and Information Based Selection States. Services NG-NEWMAP-FPMU-95582- Consultant CS-CDS / Engagement of Component 3: Climate Pending IDA / 51050 Post Qualification Open - National 196,722.00 0.00 2019-02-15 2019-03-08 2019-04-21 2019-05-21 2019-06-25 2019-12-22 Financial Adviser Green Bond Change Response Implementation Selection Second Issuance. NG-NEWMAP-FPMU-115686- CS-QCBS / Inventorisation of Component 3: Climate Quality And Cost- IDA / 51050 Prior Open - International 1,000,000.00 1,285,043.48 Signed 2019-06-17 2019-09-11 2019-07-08 2019-12-17 2019-08-21 2020-12-12 2019-09-18 2021-01-18 2019-10-18 2021-04-30 2019-11-22 2021-06-03 2019-12-27 2021-08-10 2020-12-26 GHG emissions of NEWMAP Change Response Based Selection intervention sites. NG-NEWMAP-FPMU-102198- CS-QCBS / Consultancy Component 4: Project Quality And Cost- Under services to carry out the re- IDA / 51050 Post Open - National 400,000.00 0.00 2019-05-07 2020-03-17 2019-05-28 2019-07-11 2019-08-08 2019-09-07 2019-10-12 2019-11-16 2020-11-15 Management Based Selection Implementation evaluation of the capacity of the FPMU and States NG-NEWMAP-FPMU-115678- Component 3: Climate Quality And Cost- Under CS-QCBS / Climate Smart IDA / 51050 Prior Open - International 900,000.00 0.00 2019-09-04 2020-02-10 2019-09-25 2019-11-08 2019-12-06 2020-01-05 2020-02-09 2020-03-15 2021-03-15 Change Response Based Selection Implementation Agriculture Atlas NG-NEWMAP-FPMU-165797- Consultant Component 4: Project CS-CQS / Engagement of an IDA / 51050 Post Qualification Limited 295,000.00 207,373.72 Signed 2020-03-31 2020-04-24 2020-04-07 2020-04-27 2020-04-21 2020-05-01 2020-05-05 2020-05-04 2020-06-30 Management External Audit Firm for FPMU Selection NG-NEWMAP-FPMU-165836- CS-CQS / Consultancy services for the review of existing road designs Component 1: Erosion and Consultant Under standards and construction IDA / 51050 Watershed Management Post Qualification Limited 295,000.00 0.00 2020-04-14 2020-04-14 2020-04-28 2020-05-12 2020-06-02 2020-09-02 Implementation and maintenance practices in Infrastructure Investments Selection order to identify causes of soil erosion linked to road in the Federal Republic of Nigeria NG-NEWMAP-FPMU-165882- CS-CQS / 2 No. thematic Component 2: Erosion and Consultant Guidelines for Strengthening Watershed Management Under IDA / 51050 Post Qualification Limited 138,000.00 0.00 2020-05-25 2020-04-10 2020-06-08 2020-09-02 2020-06-22 2020-09-15 2020-07-06 2020-08-17 Technical effectiveness of Institutions and Information Implementation Selection environmental and Social Services safeguards NG-NEWMAP-FPMU-165896- Component 2: Erosion and CS-CQS / Consultancy Consultant Watershed Management Services to carry out RAP IDA / 51050 Post Qualification Limited 298,000.00 239,209.85 Signed 2020-06-29 2020-09-08 2020-07-20 2020-11-25 2020-08-10 2020-12-18 2020-08-24 2020-12-21 2020-11-24 Institutions and Information Audit for the Implemented Selection Services RAP sites in NEWMAP states NG-NEWMAP-FPMU-165898- Consultant Component 4: Project CS-CQS / NEWMAP Project IDA / 51050 Post Qualification Limited 115,000.00 114,046.49 Signed 2020-11-05 2020-08-21 2020-11-26 2020-11-23 2020-12-17 2020-12-18 2021-01-07 2020-12-22 2021-04-07 Management Compendium Selection NG-NEWMAP-FPMU-165866- Component 2: Erosion and Consultant CS-CQS / Module Watershed Management Under IDA / 51050 Post Qualification Limited 295,000.00 0.00 2020-04-22 2020-11-30 2020-05-06 2020-05-13 2020-05-27 2020-08-25 Development for the Centre of Institutions and Information Implementation Selection Excellence, UNILAG Services NG-NEWMAP-FPMU-165893- CS-QCBS / Consultancy services for the Supervision of the Implementation of the Component 3: Climate Quality And Cost- Under IDA / 51050 Prior Open - International 1,600,000.00 0.00 2020-05-19 2020-06-02 2020-07-07 2020-08-04 2020-08-18 2020-09-29 2020-10-27 2021-04-30 Developed Framework for the Change Response Based Selection Implementation adoption of LPG as Low Carbon Alternative to Firewood and Kerosene NG-NEWMAP-FPMU-165895- Component 4: Project Quality And Cost- Under CS-QCBS / NEWMAP Impact IDA / 51050 Prior Open - International 800,000.00 0.00 2020-06-08 2020-06-29 2020-08-03 2020-08-24 2020-09-14 2020-10-19 2020-11-16 2021-05-24 Management Based Selection Implementation Assessment NG-NEWMAP-FPMU-102200- Consultant CS-CQS / Inventorisation of Component 3: Climate IDA / 51050 Post Qualification Open - National 250,000.00 0.00 Canceled 2019-03-21 2019-04-11 2019-05-25 2019-06-24 2019-07-29 2020-01-25 GHG emissions of NEWMAP Change Response Selection intervention sites . Page 4 NG-NEWMAP-FPMU-165887- Consultant CS-CQS / Engagement of Component 3: Climate IDA / 51050 Post Qualification Limited 215,000.00 0.00 Canceled 2020-04-24 2020-05-01 2020-05-15 2020-05-29 2020-12-15 Financial Adviser for the Third Change Response Selection Issuance of Green Bond. NG-NEWMAP-FPMU-102203- CS-QCBS / Engagement of Component 3: Climate Quality And Cost- IDA / 51050 Post Open - National 782,000.00 0.00 Canceled 2019-04-15 2019-05-06 2019-06-19 2019-07-17 2019-08-16 2019-09-20 2019-10-25 2020-10-24 Firm for Green Bond Third Change Response Based Selection Issuance NG-NEWMAP-FPMU-165892- Consultant CS-CQS / Engagement of Component 3: Climate IDA / 51050 Post Qualification Limited 115,000.00 0.00 Canceled 2020-04-16 2020-04-30 2020-05-14 2020-05-28 2020-11-24 Legal Adviser for the Third Change Response Selection Issuance of Green Bond. NG-NEWMAP-FPMU-83063- CS-QCBS / Project Management Consultancy provide technical and administrative support to the Component 4: Project Quality And Cost- FPMU NEWMAP in the areas of IDA / 51050 Prior Open - International 3,000,000.00 0.00 Canceled 2019-02-27 2019-07-28 2019-03-20 2019-10-07 2019-05-03 2019-05-31 2019-06-30 2019-08-04 2019-09-08 2020-09-07 Management Based Selection Erosion and Watershed Management Investments, Erosion and Watershed Management Institution and Information Services, NG-NEWMAP-FPMU-19539- CS-QCBS / Federal Quality Control and Engineering Design Firm (FQCEDF)- Component 1: Erosion and EXTENSION- for additional Quality And Cost- IDA / 51050 Watershed Management Post Open - International 1,100,000.00 0.00 Canceled 2017-07-03 2017-07-24 2017-09-06 2017-10-04 2017-11-03 2017-12-08 2018-01-12 2019-01-12 area for the aerial Based Selection Infrastructure Investments photography/survey of erosion sites Including capacity building and GIS software, archiving system. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Erosion and NG-NEWMAP-FPMU-19571- Watershed Management Pending CS-CDS / Engagement of an IDA / 51050 Post Direct Selection Direct 85,000.00 0.00 2017-07-10 2017-07-20 2017-09-23 2018-03-22 Institutions and Information Implementation Umbrella NGO -EXTENSION Services NG-NEWMAP-FPMU-19587- Component 1: Erosion and Individual Under CS-INDV / Engagement of a IDA / 51050 Watershed Management Post Consultant Open 50,000.00 0.00 2017-07-29 2018-10-23 2017-09-16 2017-10-07 2017-11-11 2018-05-10 Implementation Senior Engineering Advisor Infrastructure Investments Selection NG-NEWMAP-FPMU-19662- Individual Component 4: Project CS-INDV / Engagement of IDA / 51050 Post Consultant Open 40,000.00 24,608.07 Completed 2017-08-15 2017-10-09 2017-10-03 2017-10-24 2017-10-24 2017-10-25 2017-11-28 2017-10-26 2018-05-27 2018-02-20 Management Expert for Mid-Term Review Selection NG-NEWMAP-FPMU-19560- Individual Component 4: Project Under CS-INDV / Engagement of IDA / 51050 Post Consultant Open 45,000.00 0.00 2017-08-08 2018-03-27 2017-09-26 2017-10-17 2017-11-21 2018-05-20 Management Implementation Ombudsman Selection NG-NEWMAP-FPMU-19583- Individual Component 4: Project Under CS-INDV / Re-imaging of IDA / 51050 Post Consultant Open 50,000.00 0.00 2017-08-17 2019-04-01 2017-10-05 2017-10-26 2017-11-30 2018-05-29 Management Implementation NEWMAP interactive Website Selection NG-NEWMAP-FPMU-19565- CS-INDV / Consultancy Individual Component 3: Climate Services for the preparation of IDA / 51050 Post Consultant Open 100,000.00 0.00 Canceled 2017-01-30 2017-03-20 2017-04-10 2017-05-15 2017-11-11 Change Response Restructuring paper for Selection NEWMAP. NG-NEWMAP-FPMU-19525- Individual CS-INDV / Engagement of HR Component 4: Project IDA / 51050 Post Consultant Open 90,000.00 0.00 Canceled 2017-08-31 2017-10-19 2017-11-09 2017-12-14 2018-06-12 Firm International and Management Selection National. NG-NEWMAP-FPMU-19522- Component 4: Project CS-CDS / Update of IDA / 51050 Post Direct Selection Direct 30,000.00 0.00 Canceled 2017-10-24 2017-11-03 2018-01-07 2018-07-06 Management accounting system NG-NEWMAP-FPMU-83089- Individual CS-INDV / Water Specialist,for Component 3: Climate Pending IDA / 51050 Post Consultant Limited 16,983.00 0.00 2019-01-22 2019-01-27 2019-02-17 2019-03-24 2019-09-20 the Green Bond Second Change Response Implementation Selection Issuance. NG-NEWMAP-FPMU-83078- Individual CS-INDV / Oil Spills Clean-Up Component 3: Climate Pending IDA / 51050 Post Consultant Limited 26,406.00 0.00 2019-01-22 2019-01-27 2019-02-17 2019-03-24 2019-09-20 Mgt Specialist,Green Bond Change Response Implementation Selection Second Issuance. NG-NEWMAP-FPMU-83096- CS-INDV / Recruitment of Individual Component 3: Climate Pending Economics and Financial IDA / 51050 Post Consultant Limited 46,300.00 0.00 2019-01-21 2019-01-26 2019-02-16 2019-03-23 2019-09-19 Change Response Implementation Analyst,Green Bond Second Selection Issuance. NG-NEWMAP-FPMU-83076- CS-INDV / Recruitment of Individual Component 3: Climate Pending Solar Power and OfF-Grid IDA / 51050 Post Consultant Limited 36,460.00 0.00 2019-01-23 2019-01-28 2019-02-18 2019-03-25 2019-09-21 Change Response Implementation Specialist for Green Bond Selection Second Issuance. NG-NEWMAP-FPMU-83064- CS-INDV / Communications Individual Component 3: Climate Pending and Knowledge Mgt. IDA / 51050 Post Consultant Limited 28,890.00 0.00 2019-01-24 2019-01-29 2019-02-19 2019-03-26 2019-09-22 Change Response Implementation Specialist,Green Bond Second Selection Issuance. Page 5 NG-NEWMAP-FPMU-83067- Individual CS-INDV / Recruitment of Component 3: Climate Pending IDA / 51050 Post Consultant Limited 16,980.00 0.00 2019-01-24 2019-01-29 2019-02-19 2019-03-26 2019-09-22 Transport Specialist for Green Change Response Implementation Selection Bond Second Issuance. NG-NEWMAP-FPMU-83062- CS-INDV / Recruitment of Individual Component 3: Climate Pending Forest and Carbon Emission IDA / 51050 Post Consultant Limited 38,950.00 0.00 2019-01-22 2019-01-27 2019-02-17 2019-03-24 2019-09-20 Change Response Implementation Expert for Green Bond Second Selection Issuance. NG-NEWMAP-FPMU-83017- Individual Component 4: Project Pending CS-INDV / Monitoring and IDA / 51050 Post Consultant Limited 2,600.00 0.00 2019-04-02 2019-04-07 2019-04-28 2019-06-02 2019-11-29 Management Implementation Evaluation Clinic Facilitator Selection NG-NEWMAP-FPMU-78677- Component 2: Erosion and Individual CS-INDV / Engagement of a Watershed Management Under IDA / 51050 Post Consultant Limited 95,000.00 0.00 2019-03-25 2019-02-26 2019-03-30 2019-04-25 2019-04-20 2019-11-22 2019-05-25 2019-11-21 Watershed/Catchment Institutions and Information Implementation Selection Planning Expert Advisor Services Component 2: Erosion and NG-NEWMAP-FPMU-78684- Individual Watershed Management Under CS-INDV / Engagement of a IDA / 51050 Post Consultant Limited 95,000.00 0.00 2019-03-25 2018-11-21 2019-03-30 2019-04-20 2019-05-25 2019-11-21 Institutions and Information Implementation Geotechnical Expert Advisor Selection Services NG-NEWMAP-FPMU-78685- Individual CS-INDV / Engagement of a Component 3: Climate IDA / 51050 Post Consultant Limited 95,000.00 70,000.00 Signed 2019-03-25 2019-03-08 2019-03-30 2019-04-30 2019-04-20 2019-09-27 2019-05-25 2019-11-04 2019-11-21 Natural Resources Expert Change Response Selection Advisor NG-NEWMAP-FPMU-78532- Individual CS-INDV / Engagement of a Component 3: Climate IDA / 51050 Post Consultant Limited 95,000.00 68,554.58 Completed 2019-03-25 2019-02-26 2019-03-30 2019-11-13 2019-04-20 2019-11-22 2019-05-25 2019-11-25 2019-11-21 2020-12-31 Climate Change Expert Change Response Selection Advisor NG-NEWMAP-FPMU-95584- Component 2: Erosion and Individual CS-INDV / Engagement of a Watershed Management Under IDA / 51050 Post Consultant Limited 95,000.00 0.00 2019-03-25 2019-02-26 2019-03-30 2019-04-20 2019-05-25 2019-11-21 Social Livelihood Expert Institutions and Information Implementation Selection Advisor Services NG-NEWMAP-FPMU-78686- Individual Component 4: Project CS-INDV / Engagement of IDA / 51050 Post Consultant Limited 95,000.00 67,319.45 Signed 2019-03-25 2019-02-26 2019-03-30 2019-04-25 2019-04-20 2020-08-24 2019-05-25 2020-10-26 2019-11-21 Management M&E Expert Advisor Selection NG-NEWMAP-FPMU-83095- Individual Component 4: Project Under CS-INDV / NEWMAP IDA / 51050 Post Consultant Limited 45,000.00 0.00 2019-02-22 2019-03-08 2019-02-27 2019-03-20 2019-04-24 2019-10-21 Management Implementation Documentary Selection NG-NEWMAP-FPMU-98234- CS-INDV / Engagement of a Individual Component 4: Project Pending Monitoring and Evaluation IDA / 51050 Post Consultant Limited 40,000.00 0.00 2019-02-01 2019-02-06 2019-02-27 2019-04-03 2019-09-30 Management Implementation Specialist for Green Bond Selection Second Issuance. NG-NEWMAP-FPMU-102194- CS-INDV / Engagement of a Individual National Consultant to Component 4: Project Pending IDA / 51050 Post Consultant Limited 90,000.00 0.00 2019-04-08 2019-04-13 2019-05-04 2019-06-08 2019-12-05 prepare a harmonized Policy Management Implementation Selection for Erosion Control and Watershed Management NG-NEWMAP-FPMU-32655- CS-INDV / ENGAGEMENT OF Individual CONSULTANT FOR THE Component 4: Project IDA / 51050 Post Consultant Limited 30,000.00 0.00 Canceled 2017-10-31 2017-11-08 2017-11-05 2017-11-26 2017-12-31 2018-06-29 REVIEW OF THE PROJECT Management Selection IMPLEMENTATION MANUAL FOR NEWMAP NG-NEWMAP-FPMU-19524- Individual CS-INDV / Activities towards Component 3: Climate IDA / 51050 Post Consultant Open 500,000.00 0.00 Canceled 2017-01-30 2017-03-20 2017-04-10 2017-05-15 2017-11-11 establishing and issuance of Change Response Selection Nigeria Green Bond. NG-NEWMAP-FPMU-115682- CS-INDV / Consultancy Individual Component 3: Climate Under Services for the Production of IDA / 51050 Post Consultant Limited 60,000.00 0.00 2019-06-26 2019-09-07 2019-07-01 2019-07-22 2019-08-26 2019-11-12 Change Response Implementation Guidance Manual for Climate Selection Response. NG-NEWMAP-FPMU-127255- CS-INDV / Consultancy Individual Component 4: Project Pending services for the valuation of IDA / 51050 Post Consultant Limited 20,000.00 0.00 2019-09-02 2019-09-06 2019-09-13 2019-09-17 2019-09-30 Management Implementation proposed NEWMAP House to Selection be procured NG-NEWMAP-FPMU-129812- CS-INDV / Documentary on Component 2: Erosion and Individual NEWMAP Institutional Support Watershed Management Under IDA / 51050 Post Consultant Limited 45,000.00 0.00 2019-09-08 2020-12-22 2019-09-13 2019-10-04 2019-10-10 2019-11-10 to Data Collection and Institutions and Information Implementation Selection Decision Making (AFEWs & Services Hyromet Equipment) NG-NEWMAP-FPMU-154960- CS-INDV / Consultancy Individual Component 3: Climate services for the review of Pre IDA / 51050 Post Consultant Limited 90,000.00 87,804.72 Signed 2020-01-30 2020-05-10 2020-02-04 2020-07-17 2020-02-11 2020-08-28 2020-02-17 2020-08-31 2020-03-30 Change Response and Post Issuance of Green Selection Bonds. NG-NEWMAP-FPMU-165247- CS-CDS / Upgrade and Component 4: Project IDA / 51050 Prior Direct Selection Direct 500,000.00 441,065.85 Signed 2020-03-30 2020-07-09 2020-04-09 2020-12-01 2020-04-30 2021-05-17 2021-06-30 Hosting of M&E-MIS Web- Management Portal NG-NEWMAP-FPMU-165798- Individual Component 3: Climate Under CS-INDV / Review and update IDA / 51050 Post Consultant Limited 70,000.00 0.00 2020-04-03 2020-04-16 2020-04-08 2020-04-22 2020-05-06 2020-06-30 Change Response Implementation of Bio-Engineering Manual Selection Page 6 NG-NEWMAP-FPMU-165804- CS-INDV / Engagement of a Component 1: Erosion and Individual Consultant to prepare a Under IDA / 51050 Watershed Management Post Consultant Limited 100,000.00 0.00 2020-04-16 2020-11-04 2020-04-21 2020-05-05 2020-05-26 2020-07-07 harmonized Policy for Erosion Implementation Infrastructure Investments Selection Control and Watershed Management NG-NEWMAP-FPMU-165844- Component 1: Erosion and Individual CS-INDV / Consultancy for IDA / 51050 Watershed Management Post Consultant Limited 100,000.00 97,744.74 Signed 2020-05-11 2020-09-15 2020-05-18 2020-10-30 2020-06-08 2020-11-20 2020-06-22 2020-11-25 2020-08-23 ESMP Audit Infrastructure Investments Selection NG-NEWMAP-FPMU-165864- Component 2: Erosion and CS-INDV / Center Website Individual Watershed Management Development and IDA / 51050 Post Consultant Limited 15,000.00 14,098.37 Signed 2020-05-19 2020-11-30 2020-05-26 2021-05-13 2020-06-09 2021-06-07 2020-06-23 2021-06-08 2020-09-23 Institutions and Information Management for UNILAG Selection Services Centre of Excellence NG-NEWMAP-FPMU-165884- Component 2: Erosion and CS-CDS / Consultancy Service Watershed Management Under IDA / 51050 Post Direct Selection Direct 250,000.00 0.00 2020-05-27 2020-04-17 2020-06-17 2020-07-22 2020-09-02 for EAD Archiving Digital Institutions and Information Implementation Cataloguing Services NG-NEWMAP-FPMU-202983- Component 2: Erosion and Individual CS-INDV / Environmental and Watershed Management Under IDA / 51050 Post Consultant Limited 100,000.00 0.00 2020-11-18 2020-11-17 2020-11-25 2020-12-02 2020-12-16 2021-02-16 Social Management Institutions and Information Implementation Selection Framework Services Component 2: Erosion and NG-NEWMAP-FPMU-202989- Individual Watershed Management Under CS-INDV / Resettlement Policy IDA / 51050 Post Consultant Limited 100,000.00 0.00 2020-11-18 2020-11-18 2020-11-25 2020-12-02 2020-12-16 2021-02-02 Institutions and Information Implementation Framework Selection Services Component 2: Erosion and NG-NEWMAP-FPMU-202990- Individual Watershed Management CS-INDV / Stakeholders IDA / 51050 Post Consultant Limited 100,000.00 88,321.17 Signed 2020-11-18 2020-11-18 2020-11-25 2020-12-04 2020-12-02 2020-12-28 2020-12-16 2020-12-30 2021-02-02 Institutions and Information Engagement Plan Selection Services Component 2: Erosion and NG-NEWMAP-FPMU-202993- Individual Watershed Management CS-INDV / Integrated Pest IDA / 51050 Post Consultant Limited 100,000.00 87,120.16 Signed 2020-11-18 2020-11-17 2020-11-25 2020-12-14 2020-12-02 2020-01-10 2020-12-16 2021-01-13 2021-02-02 Institutions and Information Management Plan Selection Services Component 2: Erosion and NG-NEWMAP-FPMU-202995- Individual Watershed Management Under CS-INDV / Security IDA / 51050 Post Consultant Limited 100,000.00 0.00 2020-11-18 2021-02-17 2020-11-25 2020-12-02 2020-12-16 2021-02-02 Institutions and Information Implementation Assessment Selection Services Component 2: Erosion and NG-NEWMAP-FPMU-202997- Individual Watershed Management CS-INDV / Labor Management IDA / 51050 Post Consultant Limited 100,000.00 196,335.20 Signed 2020-11-18 2020-11-18 2020-11-25 2020-12-02 2020-12-02 2020-12-14 2020-12-16 2020-12-30 2021-02-02 Institutions and Information Procedure Selection Services Component 2: Erosion and NG-NEWMAP-FPMU-19563- Individual Watershed Management CS-INDV / Engagement of EA IDA / 51050 Post Consultant Open 75,000.00 0.00 Canceled 2017-01-09 2018-10-23 2017-02-27 2017-03-20 2017-04-24 2017-10-21 Institutions and Information Expert Advisor (International) Selection Services Page 7