PROCUREMENT PLAN (Textual Part) Project information: Khyber Pakhtunkhwa Rural Accessibility Project (KP- RAP) Project Implementation agency(ies): Communications & Works Department KP Date of the Procurement Plan: July 15, 2022 Period covered by this Procurement Plan: July 2022 – December 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used, subject to Bank’s prior concurrence When the Borrower uses its own national open competitive procurement arrangements as set forth in Public Procurement Rules, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 2) For national open competitive procurement, only the model procurement documents acceptable to the World Bank, shall be used. 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 5) Access to procurement opportunities shall not be restricted to firms that have pre-registered and/or paid a registration fee. 6) No preference of any kind shall be given to national bidders in the bidding process. 7) Procurement methods that use two-envelope process and rated criteria shall be subject to Bank’s prior concurrence When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact- finding activities undertaken by the Bank or persons appointed by the Bank to address specific the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Pakistan : Khyber Pakhtunkhwa Rural Accessibility Project (KPRAP) PLAN General Information Country: Pakistan 2022-07-15 Bank’s Approval Date of the Original Procurement Plan: 2024-01-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P177069 GPN Date: Project Name: Khyber Pakhtunkhwa Rural Accessibility Project (KPRAP) Loan / Credit No: IDA / 71430 KPK Communications and Works Department Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - PK-KP C&W-366498-CW-RFB Works (without pr / Package-1: Improvement & Component 1. Safe and clim Open - Internationa Single Stage - One E equalification) SP 15,237,890.0 Under Imple 2024-04-1 Upgradation of Rural Access IDA / 71430 Prior Request for Bids 0.00 2023-07-02 2023-07-14 2023-07-07 2023-09-04 2023-08-18 2023-10-25 2023-09-17 2023-11-17 2023-10-22 ate resilient access l nvelope D - Applying contr 0 mentation 9 and Flood Affected Roads in actor disqualificia District Shangla [Lot-1 and L tion ot-2] PK-KP C&W-375116-CW-RFB / Package-2: Rehabilitation a nd Improvement of Rural Acc ess Roads in District Shangla Request for Bids - [Lot-1 & Lot-2] Works (without pr Lot-1: Component 1. Safe and clim Open - Internationa Single Stage - One E equalification) SP 21,205,000.0 Under Imple 2024-05-2 IDA / 71430 Prior Request for Bids 0.00 2023-08-04 2023-08-21 2023-08-09 2023-09-04 2023-09-20 2023-10-25 2023-10-20 2024-01-30 2023-11-24 Karora to Ajmir Road, Shangl ate resilient access l nvelope D - Applying contr 0 mentation 2 a (28.274 Km) actor disqualificia Lot-2: tion Chakaiser to Dandai Road, S hangla (26.30 Km) Chakaisar to Karora Road, Sh angla (28.30 Km) Request for Bids - PK-KP C&W-375117-CW-RFB Works (without pr / Package-3: Rehabilitation a Component 1. Safe and clim Single Stage - One E equalification) SP 19,500,000.0 Under Imple 2024-05-2 nd Improvement of Flood Aff IDA / 71430 Prior Request for Bids Open - National 0.00 2023-08-04 2023-08-21 2023-08-09 2023-09-04 2023-09-20 2023-10-25 2023-10-20 2023-12-19 2023-11-24 ate resilient access nvelope D - Applying contr 0 mentation 2 ected and Rural Access Road actor disqualificia s in District Swat [Lot-1 and L tion ot-2] PK-KP C&W-375120-CW-RFB Request for Bids - / Package-4: Rehabilitation a Works (without pr nd Improvement of Flood Aff Component 1. Safe and clim Single Stage - One E equalification) SP 18,400,000.0 Under Imple 2024-05-2 IDA / 71430 Prior Request for Bids Open - National 0.00 2023-08-04 2023-08-21 2023-08-09 2023-09-04 2023-09-20 2023-10-25 2023-10-20 2024-01-30 2023-11-24 ected and Rural Access Road ate resilient access nvelope D - Applying contr 0 mentation 2 s & Bridges in Dir Upper, Dir actor disqualificia Lower & Bajaur [Lot-1 and Lo tion t-2] PK-KP C&W-392525-CW-RFB National Procure / Package-6: Rehabilitation a ment Document - Component 1. Safe and clim Single Stage - One E 17,000,000.0 Under Revie 2025-09-0 nd Improvement of Flood Aff IDA / 71430 Prior Request for Bids Open - National 1 Envelope proce 0.00 2023-11-20 2023-11-25 2024-01-06 2024-02-05 2024-03-11 ate resilient access nvelope 0 w 2 ected and Rural Access Road ss (Non Bank-SPD s & Bridges in Dera Ismail Kh ) an [Lot-1 and Lot-2] PK-KP C&W-390539-CW-RFB National Procure / Package-5: Rehabilitation a ment Document - Component 1. Safe and clim Single Stage - One E 16,171,200.0 Under Revie 2026-02-2 nd Improvement of Flood Aff IDA / 71430 Prior Request for Bids Open - National 1 Envelope proce 0.00 2023-11-05 2023-11-10 2023-12-22 2024-01-21 2024-02-25 ate resilient access nvelope 0 w 4 ected and Rural Access Road ss (Non Bank-SPD s & Bridges in Dera Ismail Kh ) an [Lot-1 and Lot-2] PK-KP C&W-400550-CW-RFB Request for Bids - / Package-7: Rehabilitation a Works (without pr nd Improvement of Flood Aff Component 1. Safe and clim Single Stage - One E equalification) SP 16,000,000.0 Under Revie 2026-04-2 IDA / 71430 Prior Request for Bids Open - National 0.00 2024-01-08 2024-01-13 2024-02-24 2024-03-25 2024-04-29 ected and Rural Access Road ate resilient access nvelope D - Applying contr 0 w 9 s and Bridges in District Char actor disqualificia sadda, Khyber Agency, and tion Mohmand Agency PK-KP C&W-400551-CW-RFB Request for Bids - / Package-8: Rehabilitation a Works (without pr nd Improvement of Flood Aff Component 1. Safe and clim Single Stage - One E equalification) SP 16,200,000.0 Under Revie 2025-10-2 IDA / 71430 Prior Request for Bids Open - National 0.00 2024-01-08 2024-01-13 2024-02-24 2024-03-25 2024-04-29 ected and Rural Access Road ate resilient access nvelope D - Applying contr 0 w 1 s and Bridges in District Kara actor disqualificia k, Kohat, Kurram, and Orakza tion i GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-KP C&W-395097-GO-RFQ Component 3. Project mana Request for Quota Single Stage - One E Under Imple IDA / 71430 Post Limited 12,300.00 0.00 2023-12-05 2024-01-04 2024-01-30 2024-07-28 / Procurement of IT Equipme gement and institutional str tions nvelope mentation nt engthening PK-KP C&W-395098-GO-RFQ Component 3. Project mana Request for Quota Single Stage - One E Pending Impl / Procurement of Office Furni IDA / 71430 gement and institutional str Post Limited 35,000.00 0.00 2023-12-05 2024-01-30 2024-07-28 tions nvelope ementation ture and Fixture engthening PK-KP C&W-395099-GO-RFQ Component 3. Project mana Request for Quota Single Stage - One E Pending Impl IDA / 71430 Post Limited 1,500.00 0.00 2023-12-05 2024-01-30 2024-07-28 / Procurement of Office Equip gement and institutional str tions nvelope ementation ment engthening PK-KP C&W-395096-GO-RFQ Component 3. Project mana Request for Quota Single Stage - One E Pending Impl / Procurement and Supply of IDA / 71430 gement and institutional str Post Limited 42,000.00 0.00 2023-12-26 2024-01-16 2024-01-26 tions nvelope ementation 02 Number 1500 cc Sedan C engthening ars PK-KP C&W-395095-GO-RFQ Component 3. Project mana Request for Quota Single Stage - One E Under Imple / Procurement and Supply of IDA / 71430 gement and institutional str Post Limited 210,000.00 0.00 2023-12-26 2024-01-14 2024-01-24 tions nvelope mentation 06 Number 2000 cc SUV Vehi engthening cles PK-KP C&W-403485-GO-RFQ Component 3. Project mana Request for Quota Single Stage - One E Pending Impl / Procurement and Supply of IDA / 71430 gement and institutional str Post Limited 77,000.00 0.00 2024-02-03 2024-03-30 2024-09-26 tions nvelope ementation 03 Number 1800 cc Sedan C engthening ars NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-KP C&W-302792-CS-QCB S / CONSULTANCY SERVICES Phase-1: Preparation of Feasi Component 3. Project mana bility and Detailed Engineerin Quality And Cost- Open - Internationa Under Implement IDA / 71430 gement and institutional str Prior 14,117,586.00 0.00 2022-07-08 2022-07-29 2022-08-08 2022-08-03 2022-09-21 2023-03-30 2022-10-19 2023-05-19 2022-11-18 2023-09-27 2022-12-24 2023-12-22 2023-01-28 2027-01-27 g Design including Procurem Based Selection l ation engthening ent Assistance; and Phase-2: Construction Supervision & C ontract Administration of Wor ks under KP-RAP PK-KP C&W-331514-CS-CQS / Consulting Services Detaile d Study on Identifying Benefi Component 2. Safe and affor Consultant Qualifi Under Implement ciaries and Transport Service IDA / 71430 dable school journeys for girl Post Open - National 300,000.00 0.00 2022-12-19 2022-12-18 2023-01-09 2022-12-27 2023-02-22 2023-04-11 2023-03-24 2023-04-28 2023-08-26 cation Selection ation Providers for Subsidized Tran s sport Provision in Selected Di stricts of Khyber Pakhtunkhw a, Pakistan PK-KP C&W-367035-CS-CQS / Consulting Services for Revi Component 3. Project mana Consultant Qualifi Under Implement ew of Detailed Engineering D IDA / 71430 gement and institutional str Post Open - National 157,900.00 0.00 2023-06-18 2023-06-26 2023-07-09 2023-08-22 2023-08-11 2023-09-21 2023-10-26 2024-04-23 cation Selection ation esigns of Khyber Pakhtunkhw engthening a Rural Accessibility Project INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-KP C&W-333769-CS-INDV Component 1. Safe and clim Individual Consult / Hiring of Gender Specialist ( IDA / 71430 Post Open - National 80,000.00 0.00 Signed 2022-12-29 2022-12-27 2023-02-14 2023-04-30 2023-03-07 2023-05-11 2023-04-11 2024-08-23 ate resilient access ant Selection Individual Consultant) PK-KP C&W-333770-CS-INDV / Hiring of Individual Consulta Component 1. Safe and clim Individual Consult IDA / 71430 Post Open - National 266,000.00 0.00 Canceled 2022-12-29 2022-12-27 2023-02-14 2023-05-09 2023-03-07 2023-04-11 2026-01-04 nt (Procurement Specialist) o ate resilient access ant Selection n Intermittent Basis PK-KP C&W-379479-CS-INDV Component 2. Safe and affor Individual Consult / Selection of Senior Educatio IDA / 71430 dable school journeys for girl Post Open - National 48,000.00 0.00 Canceled 2023-09-08 2023-10-27 2023-11-17 2023-12-22 2026-12-21 ant Selection n Specialist s PK-KP C&W-382533-CS-INDV Component 1. Safe and clim Individual Consult IDA / 71430 Prior Open - National 200,000.00 0.00 Signed 2023-09-20 2023-09-19 2023-11-08 2023-11-15 2023-11-29 2023-11-30 2024-01-03 2023-12-01 2027-01-02 / Hiring of Procurement Speci ate resilient access ant Selection alist Page 2