PROCUREMENT PLAN Project information: NIGERIA AGILE PROJECT P 170664 Project Implementation agency: FEDERAL MINISTRY OF EDUCATION Date of the Procurement Plan: 2021-10-25 Period covered by this Procurement Plan: 2021-2023] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Bureau of Public Procurement Act (PPA 2007), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations.. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods, Services and Works Goods: is not applicable. Works: is not applicable. Other Relevant Procurement Information. Procedures for CDD components: PROCUREMENT Nigeria : Adolescent Girls Initiative for Learning and Empowerment PLAN General Information Country: Nigeria 2021-12-07 Bank’s Approval Date of the Original Procurement Plan: 2024-01-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P170664 GPN Date: Project Name: Adolescent Girls Initiative for Learning and Empowerment Loan / Credit No: IDA / 67380, IDA / 74060 AGILE NPCU Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-NPCU-265698-GO-RFQ / Project management and sy Request for Quota Single Stage - One E Procurement and Installation IDA / 67380 Post Limited 50,000.00 39,766.57 Signed 2022-01-10 2022-01-31 2022-03-07 2022-03-07 2022-09-03 stem strengthening tions nvelope of 100kva generator NG-NPCU-267540-GO-RFQ / Project management and sy Request for Quota Single Stage - One E Purchase of 10 Nos. Laptops IDA / 67380 Post Limited 18,935.00 17,303.20 Signed 2022-04-30 2022-04-25 2022-06-25 2022-05-20 2022-12-22 stem strengthening tions nvelope and 6 desktops for NPCU Tea m NG-NPCU-267548-GO-RFQ / Project management and sy Request for Quota Single Stage - One E Supply and Installation of Vid IDA / 67380 Post Limited 45,000.00 45,285.38 Signed 2022-05-21 2022-05-16 2022-07-16 2022-05-30 2023-01-12 stem strengthening tions nvelope eo Conference Equipment for NPCU office NG-NPCU-267553-GO-RFQ / Project management and sy Request for Quota Single Stage - One E IDA / 67380 Post Limited 67,686.00 0.00 Canceled 2022-04-23 2022-01-31 2022-06-18 2022-12-15 Purchase of 1 No. utility vehi stem strengthening tions nvelope cle 4×4 NG-NPCU-267555-GO-RFQ / Office Furnishing inclusive of Project management and sy Request for Quota Single Stage - One E IDA / 67380 Post Limited 50,000.00 51,691.96 Signed 2022-04-12 2022-04-13 2022-06-07 2022-04-29 2022-12-04 Conference tables, office cha stem strengthening tions nvelope irs, settees, visitors chair. NG-NPCU-291803-GO-RFQ / Project management and sy Request for Quota Single Stage - One E Procurement of Office Equip IDA / 67380 Post Limited 30,000.00 30,361.46 Signed 2022-05-10 2022-05-06 2022-07-05 2022-05-24 2022-08-05 stem strengthening tions nvelope ment and Stationary and oth er consumables. NG-NPCU-297442-GO-RFQ / Procurement of Saloon Car fo Project management and sy Request for Quota Single Stage - One E IDA / 67380 Post Limited 100,000.00 98,086.47 Signed 2022-06-06 2022-06-01 2022-08-01 2022-08-14 2023-01-28 r NPCU Office including the In stem strengthening tions nvelope surance premium NG-NPCU-377827-GO-RFQ / Project management and sy Request for Quota Single Stage - One E Pending Impl IDA / 67380 Post Limited 15,000.00 0.00 2023-08-23 2023-10-18 2024-04-15 Procurement of Laptops stem strengthening tions nvelope ementation NG-NPCU-377828-GO-RFQ / Project management and sy Request for Quota Single Stage - One E Pending Impl IDA / 67380 Post Limited 20,000.00 0.00 2023-08-23 2023-10-18 2024-04-15 Printing of Souvenirs for the stem strengthening tions nvelope ementation Project NG-NPCU-394946-GO-RFQ / Project management and sy Request for Quota Single Stage - One E Pending Impl Purchase of Office equipment IDA / 67380 Post Limited 15,000.00 0.00 2023-11-29 2024-01-24 2024-07-22 stem strengthening tions nvelope ementation and stationaries NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-NPCU-291754-NC-RFQ / Project management and sy Request for Quota Single Stage - One E Purchase and installation of IDA / 67380 Post Limited 10,000.00 0.00 Canceled 2022-06-20 2022-08-15 2023-02-11 stem strengthening tions nvelope Accounting Software CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-NPCU-288969-CS-CQS / Design, hosting and mainten Project management and sy Consultant Qualifi Under Implement IDA / 67380 Post Limited 45,000.00 0.00 2022-06-06 2022-06-21 2022-06-20 2022-07-20 2022-08-24 2023-02-20 ance of Project Website and t stem strengthening cation Selection ation raining of 2 officers NG-NPCU-267573-CS-CQS / Project management and sy Consultant Qualifi IDA / 67380 Post Open - National 32,751.00 0.00 Canceled 2022-06-20 2022-06-28 2022-07-11 2022-08-24 2022-09-23 2022-10-28 2023-04-26 Hiring of Media Consultant stem strengthening cation Selection NG-NPCU-267577-CS-CQS / Development of Monitoring g Project management and sy Consultant Qualifi uidelines (standard operating IDA / 67380 Post Limited 150,000.00 142,895.52 Signed 2022-08-01 2022-06-28 2022-08-15 2022-07-14 2022-09-14 2022-07-27 2022-10-19 2022-08-05 2023-04-17 stem strengthening cation Selection procedures) for implementati on of the project M&E both in Federal and state level. NG-NPCU-291791-CS-CQS / Project management and sy Consultant Qualifi Pending Impleme Engagement of Consultant fo IDA / 67380 Post Limited 120,000.00 0.00 2022-05-15 2022-05-29 2022-06-28 2022-08-02 2023-01-29 stem strengthening cation Selection ntation r GBV for NPCU and SPIUs NG-NPCU-291794-CS-CQS / Engagement of Consultant o Project management and sy Consultant Qualifi IDA / 67380 Post Limited 100,000.00 0.00 Canceled 2022-05-10 2022-05-24 2022-06-23 2022-07-28 2022-10-26 n Environmental and Social s stem strengthening cation Selection afeguard in the implementin g states. NG-NPCU-291783-CS-CQS / Project management and sy Consultant Qualifi Engagement of Technical Ass IDA / 67380 Post Limited 120,000.00 148,064.98 Signed 2022-04-22 2022-03-28 2022-05-06 2022-04-18 2022-06-05 2022-05-03 2022-07-10 2022-05-20 2022-10-09 stem strengthening cation Selection istance for M&E Page 1 NG-NPCU-291760-CS-CQS / Project management and sy Consultant Qualifi Research Mapping for 3 new IDA / 67380 Post Limited 70,000.00 0.00 Canceled 2022-04-22 2022-05-06 2022-06-05 2022-07-10 2023-01-06 stem strengthening cation Selection states for inclusion into AGIL E NG-NPCU-288990-CS-CQS / Project management and sy Consultant Qualifi Engagement of firm for third IDA / 67380 Post Limited 450,000.00 0.00 Canceled 2022-04-25 2022-05-09 2022-06-08 2022-07-13 2023-01-09 stem strengthening cation Selection Party monitoring NG-NPCU-304635-CS-CQS / ENGAGEMENT OF A SOCIAL T ECHNICAL ASSISTANT FOR T Project management and sy Consultant Qualifi HE ADOLESCENT GIRLS INITI IDA / 67380 Post Limited 120,000.00 0.00 Canceled 2022-07-18 2022-07-25 2022-07-25 2022-08-01 2022-08-15 2023-08-10 stem strengthening cation Selection ATIVE FOR LEARNING AND E MPOWERMENT (AGILE) PROJE CT NATIONAL PROJECT COOR DITING UNIT (NPCU) NG-NPCU-304638-CS-CQS / ENGAGEMENT OF AN ENVIRO NMENTAL SAFEGUARDS TEC HNICAL ASSISTANT (TA) FOR Project management and sy Consultant Qualifi IDA / 67380 Post Limited 120,000.00 0.00 Canceled 2022-07-18 2022-07-25 2022-07-25 2022-08-01 2022-08-15 2023-08-10 ADOLESCENT GIRLS INITIATIV stem strengthening cation Selection E FOR LEARNING AND EMPO WERMENT (AGILE) PROJECT NATIONAL PROJECT COORDIN ATING UNIT (NPCU) NG-NPCU-305916-CS-CQS / Engagement of a Technical A ssistant for Project System St Project management and sy Consultant Qualifi rengthening at the National P IDA / 67380 Post Limited 50,000.00 0.00 Canceled 2022-07-31 2022-08-05 2022-08-14 2022-08-15 2022-09-01 2023-02-28 stem strengthening cation Selection roject Coordinating Office Un der Adolescent Girls Initiative for Learning & Empowerment Project NG-NPCU-308280-CS-CQS / Engagement of consultant to Fostering an enabling enviro Consultant Qualifi Under Implement implement National Commun IDA / 67380 Post Limited 400,000.00 0.00 2022-08-08 2022-07-31 2022-08-15 2022-08-29 2022-09-12 2022-11-11 nment for girls cation Selection ation ication campaign in National Project Coordinating office of AGILE Project NG-NPCU-308284-CS-CQS / ENGAGEMENT OF A COMMUN ICATION FIRM/CONSULTANT Fostering an enabling enviro Consultant Qualifi Under Implement FOR THE PRODUCTION OF A IDA / 67380 Post Limited 230,000.00 0.00 2022-08-08 2022-07-31 2022-08-15 2022-08-10 2022-08-29 2022-08-23 2022-09-12 2023-03-11 nment for girls cation Selection ation WEEKLY AGILE PROJECT TELE VISION PROGRAMME SERIES AND A QUARTERLY MAGAZIN E SERIES NG-NPCU-312039-CS-CQS / Engagement of Consultant fo Fostering an enabling enviro Consultant Qualifi Under Implement r Remote Learning Platform f IDA / 67380 Post Limited 490,000.00 0.00 2022-08-31 2022-09-08 2022-09-14 2022-09-28 2022-10-12 2023-02-09 nment for girls cation Selection ation or Adolescent Girls’ Initiative for Learning and Empowerme nt Project (AGILE) NG-NPCU-323573-CS-INDV / Consultancy Services for Bas Project management and sy Consultant Qualifi Under Implement IDA / 67380 Post Limited 350,000.00 0.00 2022-10-26 2022-10-26 2022-11-09 2022-12-09 2023-01-13 2023-07-12 eline Data Collection for Imp stem strengthening cation Selection ation act Evaluation on AGILE Proje ct NG-NPCU-339295-CS-CQS / Engagement of a data Scienc e Survey firm to Validate All Targeted and Enrolled AGILE Fostering an enabling enviro Consultant Qualifi Under Implement IDA / 67380 Post Limited 230,000.00 0.00 2023-02-06 2023-02-15 2023-02-20 2023-03-22 2023-04-26 2023-10-23 Cohorts into a National AGILE nment for girls cation Selection ation Beneficiary Register (ABR) an d Issuance of Unique (ABR) Id entification Quick Response ( QR) Codes and ID Cards. NG-NPCU-346085-CS-CQS / Engagement of External Audi Project management and sy Consultant Qualifi Under Implement tor for the 2022 Financial yea IDA / 67380 Post Limited 30,000.00 0.00 2023-02-27 2023-03-08 2023-03-13 2023-04-12 2023-05-17 2023-06-07 stem strengthening cation Selection ation r of National Project Coordina ting Unit (NPCU) of AGILE Pro ject NG-NPCU-377775-CS-CQS / Project management and sy Consultant Qualifi Under Implement Preparation of ESMP for 112 IDA / 67380 Post Limited 130,000.00 0.00 2023-08-18 2023-10-13 2023-09-01 2023-10-01 2023-11-05 2024-05-03 stem strengthening cation Selection ation unity schools across the coun try NG-NPCU-385295-CS-QCBS / Engagement of Consulting Fir Fostering an enabling enviro Quality And Cost- Pending Impleme m for the Production of AGILE IDA / 67380 Post Open - National 600,000.00 0.00 2023-10-13 2023-11-03 2023-12-17 2024-01-14 2024-02-13 2024-03-19 2024-04-23 2025-04-23 nment for girls Based Selection ntation Weekly TV Series, Quarterly Magazine Production and Dis semination of TV Series. NG-NPCU-385296-CS-QCBS / Engagement of Consulting Fir Fostering an enabling enviro Quality And Cost- Pending Impleme IDA / 67380 Post Open - National 750,000.00 0.00 2024-04-02 2024-04-23 2024-06-06 2024-07-04 2024-08-03 2024-09-07 2024-10-12 2025-10-12 m for AGILE National Commu nment for girls Based Selection ntation nication Campaign Phase II. NG-NPCU-390968-CS-CQS / Consultancy Services for the Fostering an enabling enviro Consultant Qualifi Pending Impleme Engagement of a Firm to con IDA / 67380 Post Limited 82,500.00 0.00 2023-11-02 2023-11-16 2023-12-16 2024-01-20 2024-07-18 nment for girls cation Selection ntation duct a Digital Skills Gap Asse ssment for AGILE Project. NG-NPCU-395354-CS-CQS / Project management and sy Consultant Qualifi Pending Impleme Engagement of Data Science IDA / 67380 Post Limited 37,500.00 0.00 2023-11-28 2023-12-12 2024-01-11 2024-02-15 2024-08-13 stem strengthening cation Selection ntation Consultant Management Firm NG-NPCU-383986-CS-CQS / Engagement of Consultant to Fostering an enabling enviro Consultant Qualifi IDA / 67380 Post Limited 55,000.00 0.00 Canceled 2023-09-25 2023-10-13 2023-10-09 2023-11-08 2023-12-13 2024-06-10 implement Second Chance O nment for girls cation Selection pportunities for Out-of-School Girls INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-NPCU-277825-CS-INDV / Project management and sy Individual Consult Engagement of Procurement IDA / 67380 Post Limited 69,869.00 80,283.63 Signed 2022-04-26 2022-04-13 2022-05-01 2022-04-14 2022-05-22 2022-05-05 2022-06-26 2022-06-05 2022-12-23 stem strengthening ant Selection Consultant Page 2 NG-NPCU-292953-CS-CDS / Project management and sy Research Mapping for Three ( IDA / 67380 Post Direct Selection Direct 70,000.00 69,054.72 Signed 2022-04-28 2022-04-25 2022-05-08 2022-04-27 2022-07-12 2022-06-03 2022-08-11 stem strengthening 3) New States inclusion into AGILE Project NG-NPCU-292955-CS-CDS / Project management and sy Engagement of Firm for Third IDA / 67380 Post Direct Selection Direct 450,000.00 439,695.36 Signed 2022-04-28 2022-04-20 2022-05-08 2022-04-22 2022-07-12 2022-05-09 2023-01-08 stem strengthening Party Monitoring NG-NPCU-301843-CS-CDS / Research Mapping for Nasara Project management and sy IDA / 67380 Post Direct Selection Direct 70,000.00 69,014.15 Signed 2022-06-28 2022-07-07 2022-07-08 2022-08-08 2022-08-03 2022-07-21 2022-09-02 wa, Zamfara and Bauchi Stat stem strengthening es inclusion into AGILE Projec t NG-NPCU-301845-CS-CDS / Research Mapping for Inclusi Project management and sy IDA / 67380 Post Direct Selection Direct 90,000.00 87,793.51 Signed 2022-06-30 2022-07-07 2022-07-10 2022-08-08 2022-08-07 2022-07-21 2023-02-03 on of Sokoto, Kwara, Jigawa a stem strengthening nd Niger States into AGILE Pr oject NG-NPCU-307909-CS-INDV / Engagement of a Technical A Project management and sy Individual Consult IDA / 67380 Post Limited 50,000.00 52,439.02 Signed 2022-08-05 2022-08-09 2022-08-10 2022-08-09 2022-08-17 2022-08-15 2022-08-29 2022-08-31 2023-08-24 ssistant to the National Proje stem strengthening ant Selection ct Coordinator of AGILE Proje ct NG-NPCU-315014-CS-INDV / Engagement of a Technical A ssistant for Project System St Project management and sy Individual Consult Under Implement rengthening at the National P IDA / 67380 Post Limited 60,000.00 0.00 2022-09-08 2022-08-28 2022-09-13 2022-09-20 2022-09-28 2023-09-23 stem strengthening ant Selection ation roject Coordinating Office Un der Adolescent Girls Initiative for Learning & Empowerment Project NG-NPCU-315028-CS-INDV / Engagement of Technical Ass Fostering an enabling enviro Individual Consult Under Implement IDA / 67380 Post Limited 120,000.00 0.00 2022-09-08 2022-08-28 2022-09-13 2022-08-29 2022-09-20 2022-09-16 2022-10-02 2023-09-27 istant on Social Safeguard at nment for girls ant Selection ation the National Office of the AGI LE Project NG-NPCU-315032-CS-INDV / Engagement of Technical Ass Fostering an enabling enviro Individual Consult Under Implement IDA / 67380 Post Limited 120,000.00 0.00 2022-09-08 2022-08-28 2022-09-13 2022-09-19 2022-09-20 2022-09-16 2022-10-02 2023-09-27 istant on Environmental Safe nment for girls ant Selection ation guards at the National Office of AGILE Project NG-NPCU-316554-CS-INDV / Engagement of Consultant to Fostering an enabling enviro Individual Consult Under Implement conduct research on the incl IDA / 67380 Post Limited 150,000.00 0.00 2022-09-18 2022-09-16 2022-09-23 2022-09-19 2022-10-14 2022-09-28 2022-11-18 2022-12-09 nment for girls ant Selection ation usion of livelihood skills of yo ung girls (married/ unmarried ) into the AGILE Project NG-NPCU-318798-CS-INDV / Engagement of Consultant fo r the Preparation of a Resettl Project management and sy Individual Consult Under Implement IDA / 67380 Post Limited 50,000.00 0.00 2022-09-29 2022-10-04 2022-10-04 2022-10-25 2022-11-29 2022-12-27 ement Policy Framework for stem strengthening ant Selection ation Additional Financing under A dolescent Girls Initiative and Empowerment Project NG-NPCU-318799-CS-INDV / Engagement of Consultant fo r the Preparation of the Stak Project management and sy Individual Consult Under Implement IDA / 67380 Post Limited 50,000.00 0.00 2022-09-29 2022-10-04 2022-10-04 2022-10-25 2022-11-29 2022-12-27 eholders Engagement Plan fo stem strengthening ant Selection ation r Additional Financing under Adolescent Girls Initiative an d Empowerment Project NG-NPCU-318801-CS-INDV / Engagement of Consultant fo r the Preparation of an Enviro Project management and sy Individual Consult Under Implement nmental and Social Manage IDA / 67380 Post Limited 50,000.00 0.00 2022-09-29 2022-10-04 2022-10-04 2022-10-25 2022-11-29 2022-12-27 stem strengthening ant Selection ation ment Framework (ESMF) for Additional Financing under A dolescent Girls Initiative and Empowerment Project NG-NPCU-322547-CS-CDS / Engagement of Construction Consultant to monitor Civil W Project management and sy Individual Consult Under Implement IDA / 67380 Post Limited 70,000.00 0.00 2022-10-26 2022-10-26 2022-10-31 2022-11-21 2022-12-26 2023-12-21 orks under Component 1 un stem strengthening ant Selection ation der the Adolescent Girls' Initi ative for Learning and Empo werment Project NG-NPCU-323565-CS-INDV / ENGAGEMENT OF CONSULTA Project management and sy Individual Consult Under Implement NT FOR THE EFFECTIVE TRAC IDA / 67380 Post Limited 60,000.00 0.00 2022-10-26 2022-10-27 2022-10-31 2022-11-21 2022-12-26 2023-01-22 stem strengthening ant Selection ation KING OF CONDITIONAL CASH TRANSFER (CCT) FOR THE AG ILE PROJECT NG-NPCU-327661-CS-INDV / Engagement of Consultant fo Project management and sy Individual Consult Under Implement r the Development of Payme IDA / 67380 Post Limited 60,000.00 0.00 2022-11-22 2022-11-29 2022-11-27 2022-12-18 2023-01-22 2023-08-17 stem strengthening ant Selection ation nt and Technology Systems a nd MIS to enable AGILE CCT Project NG-NPCU-373450-CS-INDV / Project management and sy Individual Consult Under Implement To provide support to NPCU/S IDA / 67380 Post Limited 70,000.00 0.00 2023-07-21 2023-10-13 2023-07-26 2023-08-16 2023-09-20 2024-03-18 stem strengthening ant Selection ation PIUs during project implemen tation NG-NPCU-373453-CS-CDS / Project management and sy Under Implement To support the NPCU in cond IDA / 67380 Post Direct Selection Direct - National 10,000.00 0.00 2023-07-21 2023-10-13 2023-07-31 2023-10-04 2024-04-01 stem strengthening ation ucting market survey/analysi s NG-NPCU-373460-CS-INDV / Project management and sy Individual Consult Under Implement To review and update/finalize IDA / 67380 Post Limited 10,000.00 0.00 2023-07-21 2023-10-13 2023-07-26 2023-08-16 2023-09-20 2024-03-18 stem strengthening ant Selection ation the project implementation manual. NG-NPCU-377824-CS-INDV / Engagement of Strategy and Technical Advisor to the NPC U to assist the project in eng Project management and sy Individual Consult Under Implement IDA / 67380 Post Limited 60,000.00 0.00 2023-08-18 2023-10-13 2023-08-23 2023-09-13 2023-10-18 2024-04-15 aging with the Legislators, Ex stem strengthening ant Selection ation ecutive, Judiciary, Traditional and Religious Leaders includi ng organizing of the Annual Conferences. NG-NPCU-387358-CS-CDS / Project management and sy Pending Impleme Engagement of Consultant fo IDA / 74060 Post Direct Selection Direct - National 180,000.00 0.00 2023-10-13 2023-10-23 2023-12-27 2024-06-24 stem strengthening ntation r the National Communicatio n Campaign. Page 3 NG-NPCU-394881-CS-INDV / Project management and sy Individual Consult Pending Impleme Engagement of Technical Ass IDA / 67380 Post Limited 75,000.00 0.00 2024-01-18 2024-01-23 2024-02-13 2024-03-19 2024-09-15 stem strengthening ant Selection ntation istance for Second Chance E ducation Page 4