PROCUREMENT PLAN (Mandatory Requirements) Emergency Multi-Sector Rohingya Crisis Response Project (EMRCRP) Project Implementation Agencies: Ministry of Disaster Management and Relief (MoDMR) Department of Public Health Engineering (DPHE) Local Government Engineering Department (LGED) Period covered by this Procurement Plan: Entire Project Period Preamble In accordance with paragraph 5.9 of the World Bank Procurement Regulations for IPF Borrowers, July 2016 revised November 2017 (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to record all procurement actions for the Project, including preparing, updating and clearing its Procurement Plan, and seeking and receiving the Bank’s review and No-objection to procurement actions as required. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents (SPDs) shall be used for goods, works and non- consulting services where international competition is required and for all consulting services, including their respective forms of contract. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Act 2006 and the Public Procurement Rules 2008, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) Lottery in award of contracts shall not be allowed; 2) Bidders’ qualification[s]/experience requirement[s] shall be mandatory; 3) Bids shall not be rejected based on percentage above or below the estimated cost; 4) Model Bidding Documents agreed with the Bank shall be used for all national open competitive procurement; 5) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations; 6) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 7) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts When the Borrower uses other national procurement arrangements (other than national open competitive procurement), such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), such arrangements shall be consistent with the above requirements. As per paragraph 5.4 of the Procurement Regulations, the “Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework” as attached to this document shall form part of the Model Bidding Documents. Leased Assets: Not Applicable. Procurement of Second Hand Goods: Not Applicable. Domestic preference: as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works) as follows: Goods: Applicable; Works: Not applicable. Hands-on Expanded Implementation Support (HEIS): Not Applicable. Bank’s Procurement Prior Review Thresholds: contracts at or above the thresholds set out in table 1 below are subject to the Bank’s procurement prior review. Table 1: Procurement Prior Review Thresholds (US$ millions) Type of High risk Substantial Moderate Low risk procurement risk risk Works (including 5 10 15 20 turnkey, supply & installation of plant and equipment, and PPP) Goods, information 1.5 2 4 6 technology and non-consulting services Consulting 0.5 1 2 4 services: firms Consulting 0.2 0.3 0.4 0.5 services: Individual Notes: 1. These thresholds apply to all procurement activities regardless of their procurement/selection methods. There is no automatic requirement to undertake prior review for direct selection for value less than these thresholds. Consultant services covers a range of services that are of an advisory or professional nature. 2. In addition to the provisions of Table 1 above, and irrespective of the contract value, the following procurement activities are subject to the Bank’s procurement prior review: (a) procurement processes involving contract negotiations, as described in Section VI, paragraphs 6.34-36, of the Procurement Regulations; (b) competitive dialogue; (c) sustainable procurement; (d) selection of probity assurance providers, as described in Section III, paragraph 3.3 of the Procurement Regulations; and (e) best and final offer. 3. The determination of whether a contract meets the procurement prior review threshold is based on the estimated value of the contract or the package -when the selection document contains more than one lot/slice- , including all taxes and duties payable under the contract. Bid/ Proposal Evaluation Committee: formation and alteration of the bid/proposal evaluation committee shall be subject to Bank’s no objection. Fraud and Corruption (F&C) Checklist: Fraud and Corruption (F&C) checklist, as developed and provided by the Bank, shall be properly filled in during the evaluation and be attached with the evaluation report in case of contracts following national competitive procurement and request for quotations. Attachment 1 Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: PROCUREMENT Bangladesh : Emergency Multi-Sector Rohingya Crisis Response Project PLAN General Information Country: Bangladesh 2019-02-17 Bank’s Approval Date of the Original Procurement Plan: 2024-01-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167762 GPN Date: Project Name: Emergency Multi-Sector Rohingya Crisis Response Project Loan / Credit No: / , IDA / D4190, IDA / D5900 Local Government Engineering Department Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component 1: Strengthening EMCRP/W3 / Relief Administr Delivery of Basic Services, R ation and Distribution Center Single Stage - One E 2021-04-1 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 240,000.00 228,105.67 Signed 2019-07-01 2020-03-01 2019-07-06 2019-07-21 2020-03-25 2019-08-30 2020-04-21 2019-10-11 2020-05-31 in Ukhya Upazial of Cox's Baz nvelope 3 gency Response, and Gende ar District. r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W7 / Construction of Delivery of Basic Services, R Single Stage - One E 2020-11-0 Field Office (EE Cox's Bazar) IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 180,000.00 155,966.98 Signed 2019-07-25 2019-10-16 2019-07-30 2019-08-14 2019-11-12 2019-09-23 2019-11-24 2019-11-04 2019-12-14 nvelope 3 extension with renovation gency Response, and Gende r-Based Viol ence Prevention EMCRP/W10 / Construction o Component 1: Strengthening f 12 nos. new School cum Dis Delivery of Basic Services, R Single Stage - One E 2021-09-1 aster shelter buildings in Ukh IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 6,020,000.00 347,830.11 Signed 2019-06-01 2019-10-01 2019-06-06 2019-06-21 2019-10-31 2019-07-31 2019-07-30 2019-09-11 2019-09-18 nvelope 0 ya Upazial of Cox's Bazar Dis gency Response, and Gende trict. r-Based Viol ence Prevention EMCRP/W13 / Improvement Component 1: Strengthening of 8 Access Road to different Delivery of Basic Services, R Single Stage - One E 2,088,894.6 2021-05-1 camps of forcibly displaced IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,180,000.00 Signed 2019-08-01 2019-11-03 2019-08-06 2019-08-21 2019-12-04 2019-09-30 2019-12-24 2019-11-11 2020-02-02 nvelope 1 4 Myanmar nationals under Co gency Response, and Gende x's Bazar District: r-Based Viol ence Prevention EMCRP/W14 / Improvement Component 1: Strengthening of 7 Access Road to different Delivery of Basic Services, R Single Stage - One E 1,752,754.7 2021-05-2 camps of forcibly displaced IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,160,000.00 Signed 2019-08-10 2019-10-27 2019-08-15 2019-08-30 2019-11-27 2019-10-09 2019-12-04 2019-11-20 2020-01-26 nvelope 7 3 Myanmar nationals under Co gency Response, and Gende x's Bazar District: r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W15 / Construction o Delivery of Basic Services, R Single Stage - One E 2,205,379.1 2022-07-1 f 4 RCC roads under Cox's Ba IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 3,270,000.00 Signed 2020-09-20 2020-10-16 2020-09-24 2020-10-29 2020-11-23 2020-11-25 2021-02-01 2021-01-06 2021-03-25 nvelope 2 0 zar District: gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W16 / Construction o Delivery of Basic Services, R Single Stage - One E 1,433,552.2 2022-07-1 f 4 RCC roads under Cox's Ba IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,860,000.00 Signed 2020-09-20 2020-10-16 2020-09-25 2020-10-30 2020-11-23 2020-11-26 2021-02-01 2021-01-07 2021-03-25 nvelope 0 1 zar District: gency Response, and Gende r-Based Viol ence Prevention EMCRP/W19 / Improvemento Component 1: Strengthening f 10 roads roads and constru Delivery of Basic Services, R Single Stage - One E 2022-07-1 ction of culverts with side dra IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 3,220,000.00 191,767.13 Signed 2020-09-10 2020-07-23 2020-09-14 2020-10-15 2020-08-26 2020-11-29 2020-09-06 2021-01-10 2020-11-21 nvelope 4 ins under Cox's Bazar Distri gency Response, and Gende ct: r-Based Viol ence Prevention EMCRP/W21 / Improvement Component 1: Strengthening of 17 roads roads and constr Delivery of Basic Services, R Single Stage - One E 3,263,471.5 2022-12-2 uction of culverts with side dr IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 3,190,000.00 Signed 2021-02-25 2021-03-18 2021-03-01 2021-04-05 2021-05-03 2021-05-15 2021-05-30 2021-06-26 2021-07-31 nvelope 4 8 ains under Cox's Bazar Distr gency Response, and Gende ict: r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W6 / Rehabiliation of Delivery of Basic Services, R blocked hilly chorra with exc Single Stage - One E 2021-09-2 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 60,000.00 0.00 Canceled 2021-03-30 2021-04-03 2021-04-24 2021-05-19 2021-06-30 avation of canalin Ukhya Upa nvelope 8 gency Response, and Gende zial of Cox's Bazar District. r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W8 / Construction of Delivery of Basic Services, R 6 RCC Girder bridges at differ Single Stage - One E 1,409,281.9 2023-01-1 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,780,000.00 Signed 2020-09-20 2020-10-19 2020-09-24 2020-10-29 2020-11-23 2020-12-04 2021-02-01 2021-01-15 2021-03-23 ent roads under Cox's Distric nvelope 6 5 gency Response, and Gende t. r-Based Viol ence Prevention EMCRP/W20 / Improvement Component 1: Strengthening of 11 roads roads and constr Delivery of Basic Services, R Single Stage - One E 3,308,124.3 2022-08-1 uction of culverts with side dr IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 3,400,000.00 Signed 2020-10-20 2021-01-28 2020-10-24 2020-11-28 2021-03-02 2020-12-30 2021-03-16 2021-02-10 2021-04-25 nvelope 9 4 ains under Cox's Bazar Distr gency Response, and Gende ict: r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W24 / Improvement Delivery of Basic Services, R Single Stage - One E 2,207,925.9 2023-01-2 of 7 roads under Cox's Bazar IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 3,350,000.00 Signed 2021-03-25 2021-03-18 2021-03-29 2021-05-03 2021-05-03 2021-06-12 2021-06-05 2021-07-24 2021-07-31 nvelope 6 5 District: gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W22 / Improvement Delivery of Basic Services, R 15 Roads with culverts and si Single Stage - One E 2,796,624.6 2023-02-2 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,770,000.00 Signed 2021-04-20 2021-03-18 2021-04-24 2021-05-29 2021-05-03 2021-07-08 2021-06-05 2021-08-19 2021-07-31 de drain under Cox's Bazar D nvelope 3 0 gency Response, and Gende istrict r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W9 / Construction of Delivery of Basic Services, R 4 RCC Girder bridges at differ Single Stage - One E 1,278,919.1 2023-01-1 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,410,000.00 Signed 2020-09-20 2020-10-19 2020-09-24 2020-10-30 2020-11-23 2020-12-04 2021-02-01 2021-01-15 2021-03-23 ent roads under Cox's Distric nvelope 6 5 gency Response, and Gende t. r-Based Viol ence Prevention EMCRP/W11 / Construction o Component 1: Strengthening f 11 nos. new School cum Dis Delivery of Basic Services, R Single Stage - One E 4,988,485.3 2022-11-2 aster shelter buildings in Uk IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 5,520,000.00 Signed 2020-07-24 2020-07-21 2020-07-28 2020-09-02 2020-09-22 2020-10-12 2020-10-08 2020-11-23 2020-12-28 nvelope 3 3 hya (9 nos.) and Teknaf (2no gency Response, and Gende s) Upazial of Cox's Bazar Dist r-Based Viol ence Prevention rict. Page 1 Component 1: Strengthening EMCRP/W23 / Improvement Delivery of Basic Services, R 18 Roads with culverts and si Single Stage - One E 4,510,585.3 2023-02-2 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 3,190,000.00 Signed 2021-04-20 2020-10-16 2021-04-24 2021-05-29 2020-11-23 2021-07-08 2021-03-04 2021-08-19 2021-05-11 de drain under Cox's Bazar D nvelope 5 0 gency Response, and Gende istrict r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W25 / Strengthening Delivery of Basic Services, R Single Stage - One E 1,774,351.5 2023-03-2 and widening of 10 roads un IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,020,000.00 Signed 2021-05-26 2021-01-28 2021-05-30 2021-07-04 2021-03-02 2021-08-13 2021-03-16 2021-09-24 2021-04-27 nvelope 0 8 der Cox's Bazar Districts gency Response, and Gende r-Based Viol ence Prevention EMCRP/W18 / Improvement Component 1: Strengthening of 8 roads roads and constru Delivery of Basic Services, R Single Stage - One E 2,055,922.9 2022-08-1 ction of culverts with side dra IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 3,230,000.00 Signed 2020-10-20 2020-10-16 2020-10-24 2020-11-29 2020-11-23 2020-12-30 2021-02-01 2021-02-10 2021-03-23 nvelope 3 4 ins under Cox's Bazar Distri gency Response, and Gende ct: r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W1 / Improvement fo Delivery of Basic Services, R Single Stage - One E 2021-12-3 6 nos. Hat Bazar under Cox's IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 360,000.00 732,124.33 Signed 2021-03-10 2021-12-23 2021-03-14 2021-04-13 2022-01-31 2021-05-23 2022-03-03 2021-07-04 2022-05-10 nvelope 1 Bazar Districts: gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/W17 / Improvement Delivery of Basic Services, R of 8 roads and construction Single Stage - One E 2,236,005.8 2022-08-1 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,890,000.00 Signed 2020-10-20 2020-10-16 2020-10-24 2020-11-29 2020-11-23 2020-12-30 2021-02-01 2021-02-10 2021-03-23 of culverts with side drains u nvelope 1 4 gency Response, and Gende nder Cox's Bazar District: r-Based Viol ence Prevention Component 1: Strengthening National Procure EMCRP/W26 / Improvement Delivery of Basic Services, R ment Document - Single Stage - One E 1,981,314.3 2023-04-1 of 09 nos Roads under Cox's IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,514,400.00 Signed 2021-08-11 2021-03-18 2021-08-14 2021-09-04 2021-05-03 2021-09-11 2021-06-05 2021-10-16 2021-08-02 nvelope 7 4 Bazar District gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W18 / Strengtheni Delivery of Basic Services, R ment Document - ng and widening of Gorakgha Single Stage - One E 4,926,653.7 2023-07-0 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 5,617,300.00 Signed 2021-10-05 2021-10-11 2021-10-11 2021-11-08 2021-11-10 2021-11-29 2021-12-26 2022-01-10 2022-02-15 ta - Shaplapur Janata Bazar R nvelope 9 9 gency Response, and Gende ss (Non Bank-SPD oad r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W8 / Building Con Delivery of Basic Services, R ment Document - struction for Fire Service Civil Single Stage - One E 2023-05-2 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 3,000,000.00 0.00 Signed 2022-02-28 2022-06-16 2022-03-05 2022-04-02 2022-07-20 2022-04-23 2022-08-08 2022-05-28 2022-09-06 Defense (FSCD) at Cox's Baz nvelope 8 gency Response, and Gende ss (Non Bank-SPD ar r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W15 / Improveme Delivery of Basic Services, R ment Document - nt of road by RCC pavement Single Stage - One E 2023-09-0 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 629,328.00 665,315.72 Signed 2021-12-23 2021-12-27 2021-12-28 2022-01-25 2022-01-31 2022-02-08 2022-03-03 2022-03-15 2022-04-30 in Mirakata from Ch. 00-200 nvelope 6 gency Response, and Gende ss (Non Bank-SPD 0m in Kutubdia r-Based Viol ence Prevention ) Component 1: Strengthening EMCRP/W4 / Construction of Delivery of Basic Services, R Multipurpose Community and Single Stage - One E 2022-09-2 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 3,434,667.00 0.00 Canceled 2020-11-20 2021-06-27 2020-11-25 2020-12-30 2021-07-27 2021-02-06 2021-03-20 Service Center in Ukhya Upa nvelope 1 gency Response, and Gende zial of Cox's Bazar District. r-Based Viol ence Prevention EMCRP/W4-A / Construction Component 1: Strengthening National Procure of 12 nos Multipurpose Com Delivery of Basic Services, R ment Document - Single Stage - One E 2,935,355.9 2023-01-3 munity and Service Center in IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 3,091,262.00 Signed 2021-12-05 2021-12-23 2021-12-10 2022-01-07 2022-01-31 2022-01-21 2022-03-03 2022-01-30 2022-04-23 nvelope 0 0 Ukhya Upazila in Cox's Bazar gency Response, and Gende ss (Non Bank-SPD district r-Based Viol ence Prevention ) EMCRP/W4. / Construction of Component 1: Strengthening National Procure 10 nos Multipurpose Commu Delivery of Basic Services, R ment Document - Single Stage - One E 2,773,534.0 2023-02-2 nity and Service Center in U IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,773,067.00 Signed 2021-12-05 2021-12-23 2021-12-10 2022-01-07 2022-01-31 2022-01-21 2022-03-03 2022-02-25 2022-05-02 nvelope 7 5 khya Upazila in Cox's Bazar gency Response, and Gende ss (Non Bank-SPD District r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W11 / Constructio Delivery of Basic Services, R ment Document - Single Stage - One E 8,158,856.2 2023-10-0 n of 14 nos. new School cum IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 9,690,000.00 Signed 2022-01-16 2022-01-17 2022-01-21 2022-02-18 2022-02-24 2022-03-11 2022-03-13 2022-04-15 2022-05-21 nvelope 0 7 Disaster Shelter Buildings gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) EMCRP/AF/W11-A / Construct Component 1: Strengthening National Procure ion of New 03 nos School cu Delivery of Basic Services, R ment Document - Single Stage - One E 1,962,622.7 2023-10-0 m Disaster Shelter Buildings IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,280,000.00 Signed 2022-01-16 2022-02-01 2022-01-21 2022-02-18 2022-03-07 2022-03-11 2022-03-29 2022-04-15 2022-05-15 nvelope 0 7 and associated 1.90 Km conn gency Response, and Gende ss (Non Bank-SPD ecting roads r-Based Viol ence Prevention ) EMCRP/W2 / Construction of Component 1: Strengthening National Procure warehouse for firefighting eq Delivery of Basic Services, R ment Document - Single Stage - One E 1,021,518.0 2024-01-0 uipment and Satellite fire sta IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 1,089,150.00 Signed 2022-03-30 2022-03-29 2022-04-04 2022-05-02 2022-05-10 2022-05-23 2022-05-24 2022-07-04 2022-07-02 nvelope 9 5 tions in Ukhya Upazial of Cox gency Response, and Gende ss (Non Bank-SPD 's Bazar District. r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W4 / Improvemen Delivery of Basic Services, R ment Document - t of Gorokghata Jetty in Mohe Single Stage - One E 2024-05-2 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 4,358,068.00 0.00 Canceled 2022-08-16 2022-08-25 2022-08-21 2022-09-18 2022-09-27 2022-10-16 2022-11-27 skhali and Darbarghat Jetty i nvelope 5 gency Response, and Gende ss (Non Bank-SPD n Kutubdia r-Based Viol ence Prevention ) Component 1: Strengthening National Procure Delivery of Basic Services, R ment Document - EMCRP/AF/W5 / Improvemen Single Stage - One E Pending Imp 2024-03-2 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 117,785.00 0.00 2022-12-15 2022-12-20 2023-01-10 2023-02-07 2023-03-21 t of two Jettis at Teknaf nvelope lementation 0 gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) EMCRP/W5 / Construction of Component 1: Strengthening National Procure internal road, footpath, drain Delivery of Basic Services, R ment Document - Single Stage - One E Pending Imp 2023-08-2 age and side slope protection IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,150,000.00 0.00 2022-12-01 2022-12-06 2022-12-27 2023-01-17 2023-02-28 nvelope lementation 7 in Ukhya Upazial of Cox's Baz gency Response, and Gende ss (Non Bank-SPD ar District. r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W7 / Improvemen Delivery of Basic Services, R ment Document - Single Stage - One E 2023-12-0 t of Existing Fire Service Offic IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 913,910.00 0.00 Signed 2022-09-15 2023-07-30 2022-09-20 2022-10-18 2023-08-29 2022-11-01 2023-09-10 2022-12-06 nvelope 6 e at Ukhiya and Teknaf gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) Page 2 Component 1: Strengthening National Procure EMCRP/AF/W9 / LGED Buildin Delivery of Basic Services, R ment Document - Single Stage - One E 2023-11-0 g Improvement at Cox's Baza IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 150,766.00 0.00 Signed 2022-08-25 2023-07-30 2022-08-30 2022-09-13 2023-08-29 2022-09-27 2023-09-13 2022-11-01 nvelope 1 r gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W10 / Training Fa Delivery of Basic Services, R ment Document - Single Stage - One E 2023-11-2 cility Construction for LGED a IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 1,896,350.00 0.00 Signed 2022-08-25 2022-11-14 2022-08-30 2022-09-27 2022-12-21 2022-10-18 2023-01-26 2022-11-22 2023-03-07 nvelope 2 t Cox's Bazar gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W14 / "Constructi Delivery of Basic Services, R ment Document - on of 7 RCC roads under Cox' Single Stage - One E Under Imple 2024-06-2 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 1,695,276.00 0.00 2022-10-13 2023-08-10 2022-10-18 2022-11-15 2023-09-11 2022-11-29 2023-09-21 2023-01-03 s Bazar District including culv nvelope mentation 6 gency Response, and Gende ss (Non Bank-SPD ert and drain r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W16 / Improveme Delivery of Basic Services, R ment Document - Single Stage - One E 2024-06-1 nt of 4 roads roads under Co IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,127,962.00 0.00 Signed 2022-10-01 2023-03-09 2022-10-06 2022-11-03 2023-04-12 2022-11-17 2023-04-12 2022-12-22 2023-06-23 nvelope 4 x's Bazar District gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W17 / Improveme Delivery of Basic Services, R ment Document - Single Stage - One E 2024-04-2 nt of 5 roads roads under Co IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 1,118,103.00 0.00 Signed 2022-08-16 2022-08-10 2022-08-21 2022-09-18 2022-09-15 2022-10-02 2022-10-13 2022-11-06 2022-12-19 nvelope 9 x's Bazar District gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W2 / Improvemen Delivery of Basic Services, R ment Document - t of Baro Junchari Rubber Da Single Stage - One E 2024-01-2 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 242,420.00 0.00 Signed 2022-11-06 2023-02-09 2022-11-11 2022-12-02 2023-03-06 2022-12-23 2023-03-13 2023-01-27 2023-05-16 m in Ramu under Additional f nvelope 7 gency Response, and Gende ss (Non Bank-SPD inancing for EMCRP r-Based Viol ence Prevention ) EMCRP/AF/.W4 / Improveme Component 1: Strengthening National Procure nt of Gorokghata Jetty in Moh Delivery of Basic Services, R ment Document - Single Stage - One E 2024-06-2 eskhali Upazila & Darbarhat J IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 4,358,068.00 0.00 Signed 2022-12-15 2023-02-07 2022-12-20 2023-01-10 2023-03-01 2023-02-07 2023-04-13 2023-02-23 2023-07-11 nvelope 2 etty in Kutubdia upazila in C gency Response, and Gende ss (Non Bank-SPD ox’s Bazar District r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/W10-A / Construction Delivery of Basic Services, R ment Document - of 03 nos new School cum Di Single Stage - One E 2024-06-0 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 1,766,780.00 0.00 Signed 2023-03-05 2023-06-11 2023-03-10 2023-04-07 2023-07-10 2023-05-05 2023-07-31 2023-06-09 2023-09-06 sater Shelter Building in Cox' nvelope 8 gency Response, and Gende ss (Non Bank-SPD s Bazar District r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/W11-A / Construction Delivery of Basic Services, R ment Document - of 04 nos New School cum Di Single Stage - One E 2024-06-0 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,355,700.00 0.00 Signed 2023-03-05 2023-06-11 2023-03-10 2023-04-07 2023-07-10 2023-05-05 2023-07-30 2023-06-09 2023-09-06 saster Shelter Building in Cox nvelope 8 gency Response, and Gende ss (Non Bank-SPD 's Bazar District. r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W1 / Improvemen Delivery of Basic Services, R ment Document - t of Joarianala Sonachari Rub Single Stage - One E Under Imple 2024-03-0 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 191,500.00 0.00 2022-12-01 2023-07-30 2022-12-06 2022-12-27 2023-01-24 2023-03-07 ber Dam at Ramu in Cox'sBa nvelope mentation 6 gency Response, and Gende ss (Non Bank-SPD zar District r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/W3 / Improvemen Delivery of Basic Services, R ment Document - t of Monirjheel Sonachari Rub Single Stage - One E Pending Imp 2024-03-0 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 53,500.00 0.00 2022-12-01 2022-12-06 2022-12-27 2023-01-24 2023-03-07 ber Dam at Ramu in Cox's B nvelope lementation 6 gency Response, and Gende ss (Non Bank-SPD azar district. r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/W12 / Improvement Delivery of Basic Services, R ment Document - of 8 nos roads (11.30km) in Single Stage - One E Pending Imp 2024-12-3 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,283,606.39 0.00 2023-12-10 2023-12-15 2024-01-15 2024-01-31 2024-03-13 Tefnaf Upazilla under Cox's B nvelope lementation 0 gency Response, and Gende ss (Non Bank-SPD azar District. r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/W12A / Improvement Delivery of Basic Services, R ment Document - of 4 nos (8.085 km) roads in Single Stage - One E Under Imple 2024-12-3 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,602,540.52 0.00 2023-12-10 2023-10-09 2023-12-15 2024-01-15 2023-11-08 2024-01-30 2023-11-22 2024-03-05 Ukhiya Upazilla under Cox's nvelope mentation 0 gency Response, and Gende ss (Non Bank-SPD Bazar District r-Based Viol ence Prevention ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthening EMCRP/G-04 / Procurement Delivery of Basic Services, R Single Stage - One E of 10000 + 1000 Liter water / esilient Infrastructure, Emer Post Request for Bids Open - National 2,408,000.00 0.00 Canceled 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-07-02 2019-04-21 2019-05-26 2019-09-23 nvelope tender for FSCD gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-05 / Procurement Delivery of Basic Services, R Single Stage - One E of Fire and Rescue Vehicle IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,744,000.00 2,654,506.42 Completed 2019-02-20 2019-05-28 2019-02-25 2019-03-12 2019-07-02 2019-04-21 2019-08-20 2019-05-26 2019-10-17 2019-09-23 2019-10-17 nvelope (medium) for FSCD gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-06 / Procurement Delivery of Basic Services, R of Towing Vehicle ( Pick up ty Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,974,000.00 3,014,898.23 Signed 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-07-02 2019-04-21 2019-07-09 2019-05-26 2019-10-19 2019-09-23 2019-10-19 pe with CAF and Water ) for F nvelope gency Response, and Gende SCD r-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-07 / Procurement Delivery of Basic Services, R Single Stage - One E of Fire Fighting portable pum IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 397,000.00 372,622.94 Completed 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-06-25 2019-04-21 2019-07-30 2019-05-26 2019-09-19 2019-09-23 2020-07-02 nvelope p ( Small) for FSCD gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-10 / Procurement Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 361,000.00 349,065.04 Completed 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-07-02 2019-04-21 2019-07-30 2019-05-26 2019-09-19 2019-09-23 2019-09-19 of Ambulance for FSCD nvelope gency Response, and Gende r-Based Viol ence Prevention Page 3 Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-11 / Procurement Single Stage - One E / esilient Infrastructure, Emer Post Request for Bids Open - National 1,499,000.00 0.00 Canceled 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-07-02 2019-04-21 2019-05-26 2019-09-23 of Rescue Boat for FSCD nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-12 / Procurement Delivery of Basic Services, R Single Stage - One E of Fire Fighting Turn Table fo IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,746,000.00 0.00 Canceled 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-07-02 2019-04-21 2019-05-26 2019-09-23 nvelope r FSCD gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-08 / Procurement Delivery of Basic Services, R Single Stage - One E of Fire Service Command Ve IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 255,000.00 189,293.33 Completed 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-06-25 2019-04-21 2019-08-30 2019-05-26 2019-09-19 2019-09-23 2019-09-19 nvelope hicle for FSCD gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-01 / Procurement Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 81,000.00 0.00 Canceled 2019-07-01 2019-07-06 2019-07-21 2019-08-30 2019-10-11 2020-02-08 of Motorcycles nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-02 / Procurement Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,075,000.00 70,758.90 Completed 2019-07-10 2019-04-30 2019-07-15 2019-05-29 2019-07-30 2019-05-30 2019-09-08 2019-07-30 2019-10-20 2019-08-30 2020-04-17 2021-04-05 of Solar Street Light nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-03 / Supply and in Delivery of Basic Services, R stallation of Early Steamer E Single Stage - One E / esilient Infrastructure, Emer Post Request for Bids Open - National 2,239,000.00 0.00 Canceled 2019-07-13 2019-07-18 2019-08-02 2019-09-11 2019-10-23 2020-04-20 mission Lightening Protection nvelope gency Response, and Gende System r-Based Viol ence Prevention EMCRP/G-03A / Supply and i Component 1: Strengthening nstallation of 90 nos. Early St Delivery of Basic Services, R Single Stage - One E eamer Emission Lightening P IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 537,314.00 411,717.06 Completed 2019-04-25 2019-04-30 2019-04-30 2019-05-29 2019-05-24 2019-05-30 2019-06-23 2019-07-11 2019-08-04 2019-08-02 2020-08-03 2020-12-01 nvelope rotection System in Rohingya gency Response, and Gende Camps r-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-12A / Procurement Delivery of Basic Services, R Single Stage - One E of 1 no. Fire Fighting Turn Ta IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,746,000.00 1,638,365.11 Signed 2019-07-30 2019-10-28 2019-08-04 2019-08-24 2019-11-20 2019-10-03 2019-12-26 2019-11-07 2020-02-09 2020-05-05 nvelope ble for FSCD gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-04A / Procurement Delivery of Basic Services, R Single Stage - One E of 5 nos. 10000 +1000 Liter IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,408,000.00 2,350,486.60 Completed 2019-07-30 2019-07-27 2019-08-04 2019-08-24 2019-08-20 2019-10-03 2019-10-07 2019-11-07 2019-11-13 2020-05-05 2019-11-13 nvelope Water Tender gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-11A / Procurement Delivery of Basic Services, R Single Stage - One E of 6 nos. Rescue Boat for FSC IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,499,000.00 0.00 Canceled 2019-07-30 2019-09-03 2019-08-04 2019-08-24 2019-11-26 2019-10-03 2019-11-07 2020-05-05 nvelope D gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-1 / Procurement of IDA / D4190 esilient Infrastructure, Emer Post Direct Selection Direct 68,823.00 68,688.89 Completed 2020-06-07 2018-12-11 2020-06-12 2020-01-13 2020-07-19 2020-07-02 2020-10-17 2020-07-02 34 Motorcycle under EMCRP gency Response, and Gende r-Based Viol ence Prevention EMCRP/COVID19/G-22 / Proc Component 1: Strengthening urement of soap, hand saniti Delivery of Basic Services, R zer and disinfectant spray for IDA / D4190 esilient Infrastructure, Emer Post Direct Selection Direct 5,978.00 4,660.05 Completed 2020-05-27 2020-05-19 2020-05-30 2020-05-31 2020-07-04 2020-06-13 2020-07-19 2020-09-12 prevention of COVID-19 infec gency Response, and Gende tions in cyclone shelters in C r-Based Viol ence Prevention ox's Bazar District. Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-16 / Procurement Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 60,000.00 0.00 Canceled 2020-11-30 2020-12-04 2020-12-24 2021-01-14 2021-02-25 2021-04-26 of Stationery nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-11B / Procurement Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,499,000.00 0.00 Canceled 2020-10-15 2020-10-08 2020-10-18 2020-11-22 2021-01-04 2021-01-09 2021-02-20 2021-08-19 of 6 rescue boats for FSCD nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-09 / Procurement Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 255,000.00 0.00 Canceled 2020-08-15 2020-08-27 2020-08-20 2020-09-24 2020-09-21 2020-11-03 2020-10-05 2020-12-15 2021-06-28 of Command Vehicle nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-09_ / Procurement Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 255,000.00 187,462.92 Signed 2020-10-30 2020-10-21 2020-11-04 2020-11-22 2020-11-05 2020-12-07 2020-12-30 2021-01-11 2021-01-19 2021-07-10 of two command vehicles nvelope gency Response, and Gende r-Based Viol ence Prevention EMCRP/G-03B / Supply and I Component 1: Strengthening nstallation of 268 nos Early S Delivery of Basic Services, R Single Stage - One E teamer Emission Lightening IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,764,240.00 0.00 Canceled 2021-09-14 2021-12-16 2021-09-19 2021-10-17 2022-01-25 2021-11-07 2021-12-12 2022-12-12 nvelope Protection System in differen gency Response, and Gende t Rohingya camps r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/G-17 / Supply & In Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,766,485.00 0.00 Canceled 2021-12-12 2021-12-12 2021-12-16 2022-01-13 2022-01-25 2022-02-03 2022-03-10 2022-07-08 stallation of Solar Light nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-18 / Supply and Delivery of Basic Services, R Single Stage - One E Installation of Solar PV Nano IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,750,000.00 0.00 Canceled 2021-12-14 2022-01-18 2021-12-19 2022-01-16 2022-03-10 2022-02-06 2022-03-13 2022-12-08 nvelope Grid gency Response, and Gende r-Based Viol ence Prevention Page 4 Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/G-07 / Supply of S Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 66,928.00 0.00 Canceled 2022-01-24 2022-01-26 2022-02-09 2022-02-23 2022-03-30 2022-07-28 preader nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/G-08 / Supply of R Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 35,877.00 0.00 Canceled 2022-01-24 2022-01-26 2022-02-09 2022-02-23 2022-03-30 2022-07-28 am Jack nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-13 / Procurement Single Stage - One E Under Imple IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 6,000.00 0.00 2022-03-30 2022-06-08 2022-04-04 2022-04-19 2022-05-03 2022-06-14 2022-08-13 of Computer and accessories nvelope mentation gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-14 / Printers and P Single Stage - One E Under Imple IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 18,000.00 0.00 2022-03-30 2022-06-08 2022-04-04 2022-04-19 2022-05-03 2022-06-14 2022-08-13 hotocopy Machines nvelope mentation gency Response, and Gende r-Based Viol ence Prevention EMCRP/AF/G-03 / Supply of Component 1: Strengthening 08 nos Smoke Ejector, 08 no Delivery of Basic Services, R Single Stage - One E s Power chain saw, 04 nos P IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 167,255.00 0.00 Canceled 2022-01-24 2022-03-29 2022-01-26 2022-02-09 2022-04-21 2022-02-23 2022-03-30 2022-07-28 nvelope ower cutter, 08 nos Spreader gency Response, and Gende and 04 nos Ram Jack r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-01 / Supply of Delivery of Basic Services, R Single Stage - One E Water Vehicle, Toying Vehicl IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,521,320.00 1,226,172.26 Signed 2022-04-03 2022-03-27 2022-04-03 2022-05-01 2022-04-28 2022-05-15 2022-07-17 2022-06-19 2022-09-22 2022-10-17 nvelope e and Portable Pump gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-02 / Supply of Delivery of Basic Services, R Delivery hose, Hand control Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 59,835.00 0.00 Canceled 2022-04-03 2022-03-29 2022-04-05 2022-04-19 2022-04-21 2022-05-03 2022-06-07 2022-10-05 branch pipe and Foam makin nvelope gency Response, and Gende g branch pipe r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-04 / Supply of B Delivery of Basic Services, R reathing apparatus, Diving a Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 270,906.00 0.00 Canceled 2022-04-03 2022-03-28 2022-04-05 2022-04-19 2022-04-24 2022-05-03 2022-06-07 2022-10-05 pparatus, Heat protective sui nvelope gency Response, and Gende t and Fireman suit r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-05 / Supply of Delivery of Basic Services, R Single Stage - One E Gas detector, Stretcher and IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 86,925.00 0.00 Canceled 2022-04-03 2022-03-28 2022-04-05 2022-04-19 2022-04-21 2022-05-03 2022-05-31 2022-09-28 nvelope Extension ladder gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/G-06 / Supply of T Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 65,960.00 0.00 Canceled 2022-04-03 2022-03-28 2022-04-05 2022-04-26 2022-04-21 2022-05-10 2022-06-14 2022-10-12 hermal Imaging Camera nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/G-09 / Supply of L Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 200,000.00 0.00 Canceled 2022-04-03 2022-03-28 2022-04-05 2022-04-19 2022-04-21 2022-05-03 2022-06-06 2022-10-04 ife detecting device nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/G-10 / Supply of Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 23,887.00 0.00 Canceled 2022-04-03 2022-03-28 2022-04-05 2022-04-19 2022-04-21 2022-05-03 2022-06-07 2022-10-05 Helmet nvelope gency Response, and Gende r-Based Viol ence Prevention EMCRP/G-03B. / Supply and I Component 1: Strengthening nstallation of 268 Nos. Early Delivery of Basic Services, R Streamer Emission Lightning Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Prior Request for Bids Open - National 1,764,240.00 0.00 Canceled 2022-04-05 2022-05-24 2022-04-08 2022-06-05 2022-04-29 2022-07-19 2022-05-20 2022-10-18 2022-06-24 2023-03-21 Protection System at differen nvelope gency Response, and Gende t Rohingya camps under Ukhi r-Based Viol ence Prevention ya & Teknaf Upazila in Cox's Bazar district under EMCRP EMCRP/AF/G-17. / Supply an Component 1: Strengthening d Installation of 2500 sets Sol Delivery of Basic Services, R Single Stage - One E ar Street Light at different Ro IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,766,485.00 0.00 Canceled 2022-04-05 2022-04-18 2022-04-08 2022-04-29 2022-05-11 2022-05-20 2022-06-24 2022-10-22 nvelope hingya camps under Ukhiya gency Response, and Gende & Teknaf Upazila in Cox’s Ba r-Based Viol ence Prevention zar District Component 1: Strengthening EMCRP/AF/G-18. / Supply an Delivery of Basic Services, R Single Stage - One E d installation of Solar PV Nan IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,750,000.00 0.00 Signed 2022-06-19 2022-06-07 2022-06-24 2022-07-21 2022-06-30 2022-08-11 2022-08-21 2022-09-22 2022-11-03 2023-06-19 nvelope o Grid gency Response, and Gende r-Based Viol ence Prevention EMCRP/AF/.G-17 / Supply an Component 1: Strengthening d Installation of 2500 set Sol Delivery of Basic Services, R Single Stage - One E ar Street Light at different Ro IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,766,485.00 0.00 Signed 2022-08-07 2022-08-22 2022-08-12 2022-09-02 2022-09-15 2022-09-30 2023-01-01 2022-11-11 2023-02-08 2023-08-08 nvelope hingya camps under Ukhia & gency Response, and Gende Teknaf Upazila in Coxs Bazar r-Based Viol ence Prevention District . Component 1: Strengthening EMCRP/AF/.G-02 / Supply of Delivery of Basic Services, R Delivery Hose, Hand Control Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 59,835.00 0.00 Signed 2022-08-07 2022-08-22 2022-08-12 2022-09-02 2022-09-12 2022-09-23 2023-01-03 2022-11-04 2023-02-07 2023-03-04 Branch Pipe and Foam Makin nvelope gency Response, and Gende g Branch Pipe r-Based Viol ence Prevention EMCRP/AF/.G-03 / Supply of Component 1: Strengthening 8 Nos Ejector, 8 Nos Power C Delivery of Basic Services, R Single Stage - One E hain Saw, 4 Nos Hydraulic Po IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 167,255.00 0.00 Signed 2022-08-07 2022-08-22 2022-08-12 2022-09-02 2022-09-12 2022-09-23 2023-01-05 2022-11-04 2023-02-08 2023-03-04 nvelope wer Cutter, 8 Nos Hydraulic S gency Response, and Gende preader and 4 Nos Ram Jack r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/.G-04 / Supply of Delivery of Basic Services, R Breathing Apparatus, Diving Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 270,906.00 0.00 Signed 2022-08-07 2022-08-22 2022-08-12 2022-09-02 2022-09-12 2022-09-04 2023-01-03 2022-10-16 2023-02-06 2023-02-13 Apparatus, Heat Protective s nvelope gency Response, and Gende uit and Fireman suit r-Based Viol ence Prevention Page 5 Component 1: Strengthening EMCRP/AF/.G-05 / Supply of Delivery of Basic Services, R Single Stage - One E Gas Detector, Stretcher and IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 86,925.00 0.00 Signed 2022-08-07 2022-08-22 2022-08-12 2022-09-02 2022-09-12 2022-09-23 2023-01-05 2022-11-04 2023-02-24 2023-03-04 nvelope Extension Ladder, gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/.G-06 / Supply of Delivery of Basic Services, R Single Stage - One E Thermal Imaging Camera (TI IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 65,960.00 0.00 Canceled 2022-08-07 2022-08-22 2022-08-12 2022-09-02 2022-09-12 2022-09-23 2022-11-04 2023-03-04 nvelope C) gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/.G-09 / Supply of Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 200,000.00 0.00 Signed 2022-08-07 2022-08-22 2022-08-12 2022-09-02 2022-09-12 2022-09-23 2023-01-01 2022-11-04 2023-02-06 2023-03-04 Life Detecting Device nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/.G-10 / Supply of Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 23,687.00 0.00 Signed 2022-08-07 2022-08-22 2022-08-12 2022-09-02 2022-09-12 2022-09-23 2023-01-03 2022-11-04 2023-02-03 2023-03-04 Helmet nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-11 / Supply and Delivery of Basic Services, R Installation of Emergency Op Open - Internationa Single Stage - One E Pending Impl IDA / D5900 esilient Infrastructure, Emer Prior Request for Bids 4,000,000.00 0.00 2022-12-01 2022-12-11 2023-01-22 2023-02-21 2023-04-04 2023-10-01 eration System for Fire Servi l nvelope ementation gency Response, and Gende ce Civil Defense r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/G-12 / ICT Equipm Single Stage - One E Pending Impl IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 353,357.00 0.00 2023-01-01 2023-01-06 2023-01-27 2023-02-10 2023-03-17 2023-07-15 ent for LGED Training Facility nvelope ementation gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-15 / Supply & In Delivery of Basic Services, R stallation of 300 nos of Early Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,413,427.00 0.00 Signed 2022-09-15 2023-01-15 2022-09-20 2022-10-18 2023-02-23 2022-11-08 2023-04-18 2022-12-13 2023-08-31 2023-08-10 Steamer Emission Lightening nvelope gency Response, and Gende Protection System r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-19 / Supply and Delivery of Basic Services, R Single Stage - One E Installation of Solar PV Nano IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,750,000.00 0.00 Signed 2022-09-15 2022-11-16 2022-09-20 2022-10-18 2022-12-21 2022-11-08 2023-01-18 2022-12-13 2023-03-08 2023-09-09 nvelope Grid gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/G-20 / Supply and Delivery of Basic Services, R Single Stage - One E Installation of Solar PV Nano IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,500,000.00 0.00 Signed 2022-11-15 2023-09-21 2022-11-20 2022-12-18 2023-10-23 2023-01-08 2023-12-11 2023-02-12 2023-11-09 nvelope Grid gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/G-15 / Office Furnitur Single Stage - One E Pending Impl IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 12,000.00 0.00 2023-03-01 2023-03-06 2023-03-21 2023-04-04 2023-05-16 2023-07-15 e nvelope ementation gency Response, and Gende r-Based Viol ence Prevention EMCRP/ G-03B / Supply and I Component 1: Strengthening nstallation of 268 nos Early S Delivery of Basic Services, R teamer Emission Lightning Pr Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,764,240.00 0.00 Signed 2022-11-10 2022-11-13 2022-11-15 2022-12-13 2022-12-07 2023-01-10 2023-01-10 2023-02-14 2023-03-01 2023-11-11 otection System at different nvelope gency Response, and Gende Rohingya Camps under Ukhiy r-Based Viol ence Prevention a & Teknaf Upazila in Cox's B azar under EMCRP Component 1: Strengthening EMCRP/AF/ G-06 / Supply of Delivery of Basic Services, R Single Stage - One E Thermal Imaging Camera (TI IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 65,960.00 0.00 Canceled 2023-02-22 2023-03-01 2023-02-25 2023-03-11 2023-03-20 2023-03-25 2023-06-20 2023-04-29 2023-08-27 nvelope C) gency Response, and Gende r-Based Viol ence Prevention EMCRP./G-11A / Supply of Fir Component 1: Strengthening e Rescue Command Tender ( Delivery of Basic Services, R Single Stage - One E Heavy), Fire Rescue Comman IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,611,940.00 0.00 Signed 2023-04-30 2023-06-22 2023-05-05 2023-06-02 2023-07-20 2023-06-23 2023-09-05 2023-07-28 2023-09-06 2023-11-25 nvelope d Tender (medium), Fire Res gency Response, and Gende cue Command Tender (light), r-Based Viol ence Prevention Portable Fire Pump Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/G-13 / Supplying Single Stage - One E Pending Impl IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 11,778.56 0.00 2023-10-30 2023-11-04 2023-11-19 2023-12-03 2024-01-14 2024-03-14 of Computer and accessories nvelope ementation gency Response, and Gende r-Based Viol ence Prevention EMCRP/AF/G-16 / Supply and Component 1: Strengthening installation of 150 (One hund Delivery of Basic Services, R Single Stage - One E Under Imple red Fifty) Nos. Early Streame IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 763,655.02 0.00 2023-11-30 2023-11-15 2023-12-05 2024-01-02 2024-01-23 2024-02-27 2024-10-24 nvelope mentation r Emission Lightning Protecti gency Response, and Gende on System under Cox's Bazar r-Based Viol ence Prevention District. EMCRP/AF/G-16A / Supply an Component 1: Strengthening d installation of 150 (One hu Delivery of Basic Services, R Single Stage - One E Under Imple ndred Fifty) Nos. Early Strea IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 763,655.02 0.00 2023-11-30 2023-11-15 2023-12-05 2024-01-02 2024-01-23 2024-02-27 2024-10-24 nvelope mentation mer Emission Lightning Prote gency Response, and Gende ction System under Cox's Ba r-Based Viol ence Prevention zar District. EMCRP/AF/G-22 / Supply of F SCD Firefighting Equipment a Component 1: Strengthening nd Rescue Vehicles 1) Water Delivery of Basic Services, R Tender (1800 Litre)-03 Nos 2 Single Stage - One E Pending Impl IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,850,000.00 0.00 2024-01-15 2024-01-20 2024-02-19 2024-03-11 2024-04-22 2024-11-15 ) Portable Fire Pump (Small)- nvelope ementation gency Response, and Gende 25 Nos 3) Portable Fire Pump r-Based Viol ence Prevention (Small Heavy Duty)-5 Nos & 4) Tailor Based Generator wit h Telescope light must 4 Nos under EMCRP. EMCRP/AF/G-23 / Supply of F SCD Firefighting Equipment a Component 1: Strengthening nd Rescue Vehicles 1) Fire an Delivery of Basic Services, R Single Stage - One E Pending Impl d Rescue Command Vehicle- IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,846,344.00 0.00 2024-03-14 2024-03-14 2024-04-11 2024-04-25 2024-05-30 2024-12-20 nvelope ementation 2 nos 2) Fire Rescue Comma gency Response, and Gende nd Vehicle-1no 3) Water Ten r-Based Viol ence Prevention der (4300 Litre)-4 nos under EMCRP (additional financing) Page 6 EMCRP/AF/G-24 / Supply of F Component 1: Strengthening SCD Firefighting Equipment Delivery of Basic Services, R Single Stage - One E Pending Impl Water Browser (5000 litre)-1 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,801,839.00 0.00 2024-05-01 2024-05-01 2024-05-29 2024-06-12 2024-07-17 2024-12-28 nvelope ementation 0 nos under EMCRP (addition gency Response, and Gende al financing) r-Based Viol ence Prevention NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthening EMCRP/GBV/S2 / Gender Bas Delivery of Basic Services, R UN Agencies (Dire ed Violance Management Fir IDA / D4190 esilient Infrastructure, Emer Prior Direct 8,480,000.00 7,999,951.00 Signed 2019-08-01 2019-07-11 2019-08-06 2019-10-16 2019-10-07 2019-11-27 2021-11-30 ct) m gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/NS-01 / Transport re Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 180,000.00 159,525.23 Signed 2019-06-01 2019-11-28 2019-06-06 2019-07-06 2020-01-02 2019-08-05 2020-01-15 2019-09-16 2020-02-16 2022-02-01 ntal expenses nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/NS-01 / Transport Delivery of Basic Services, R Single Stage - One E Rental Services ( Hiring of ve IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 294,460.00 0.00 Canceled 2021-12-05 2021-12-10 2021-12-24 2022-01-03 2022-01-31 2024-01-31 nvelope hicles ) gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/NS-01. / Transpor Delivery of Basic Services, R t Rental Services (Hiring of V IDA / D5900 esilient Infrastructure, Emer Post Direct Selection Direct 294,460.00 287,585.97 Signed 2022-01-05 2022-01-09 2022-01-10 2022-01-12 2022-01-30 2022-02-01 2024-06-30 ehicles) gency Response, and Gende r-Based Viol ence Prevention CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthening EMCRP/ME/S2 / Monitoring a Delivery of Basic Services, R Consultant Qualifi nd Evaluation Consultancy S IDA / D4190 esilient Infrastructure, Emer Post Open - National 480,000.00 621,765.16 Signed 2019-02-13 2019-05-23 2019-03-06 2019-05-22 2019-04-19 2019-08-19 2019-05-19 2019-12-10 2019-06-30 2019-12-21 2021-12-16 cation Selection ervices gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/CIA/S3 / Cumulative I Delivery of Basic Services, R Consultant Qualifi mpact Assessment Consultan IDA / D4190 esilient Infrastructure, Emer Post Open - National 490,000.00 483,492.42 Signed 2019-02-13 2019-06-15 2019-03-06 2019-07-17 2019-04-19 2019-12-31 2019-05-19 2020-01-29 2019-06-30 2020-03-09 2020-03-26 cation Selection cy Services gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/CA/S5 / Communicati Delivery of Basic Services, R Consultant Qualifi on and Awareness Consultan IDA / D4190 esilient Infrastructure, Emer Post Open - National 360,000.00 353,785.40 Signed 2019-02-13 2019-06-15 2019-03-06 2019-07-17 2019-04-19 2019-10-28 2019-05-19 2020-01-29 2019-06-30 2020-03-10 2021-12-16 cation Selection cy Services gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/FS/S7 / Consultan Delivery of Basic Services, R cy Services for Feasibility Stu Quality And Cost- Open - Internationa IDA / D4190 esilient Infrastructure, Emer Prior 3,396,000.00 2,429,875.88 Signed 2020-09-15 2020-09-15 2020-10-15 2020-09-17 2020-12-28 2021-04-27 2021-01-27 2021-03-02 2021-03-28 2021-05-10 2021-05-11 2021-07-27 2021-06-22 2021-09-21 2022-02-17 dy of Resilient Infrastructure Based Selection l gency Response, and Gende Development Project (RIDP) r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/IA/S4 / Appointment Consultant Qualifi IDA / D4190 esilient Infrastructure, Emer Post Open - National 20,000.00 0.00 Canceled 2022-11-01 2022-08-25 2022-11-22 2023-01-01 2023-01-31 2023-03-14 2023-06-12 of Internal Audit Firm cation Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/IA/.S4 / Selection of I Consultant Qualifi IDA / D4190 esilient Infrastructure, Emer Post Limited 20,000.00 0.00 Signed 2022-11-10 2022-11-02 2022-11-17 2023-01-18 2022-12-08 2023-06-25 2023-01-05 2023-08-01 2023-03-06 nternal Audit firm cation Selection gency Response, and Gende r-Based Viol ence Prevention INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthening EMCRP/DS/S1 / Design and S Delivery of Basic Services, R upervision Consultancy Servi IDA / D4190 esilient Infrastructure, Emer Prior Direct Selection Direct 1,650,000.00 1,616,870.20 Signed 2019-02-13 2019-05-23 2019-02-23 2019-05-05 2019-04-19 2019-10-30 2022-01-31 ce for EMCRP gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/SPS/S2 / Senior Proc Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Limited 240,000.00 205,711.06 Signed 2019-03-25 2019-05-01 2019-04-04 2019-05-01 2019-04-25 2019-06-16 2019-06-06 2019-07-12 2022-02-15 urement Specialist ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/SDS/S4 / Social Deve Individual Consult / esilient Infrastructure, Emer Post Limited 70,000.00 59,102.76 Signed 2019-04-10 2019-05-01 2019-04-20 2019-05-03 2019-05-11 2019-05-26 2019-06-22 2019-07-15 2021-11-30 lopment Specialist ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/FSDS/S5 / Field Level Delivery of Basic Services, R Individual Consult Social Development Speciali IDA / D4190 esilient Infrastructure, Emer Post Limited 50,000.00 41,100.11 Signed 2019-07-30 2020-01-23 2019-08-09 2020-02-04 2019-08-30 2019-06-10 2019-10-11 2020-04-07 2021-11-30 ant Selection st gency Response, and Gende r-Based Viol ence Prevention Page 7 Component 1: Strengthening Delivery of Basic Services, R EMCRP/FENS/S7 / Field Level Individual Consult / esilient Infrastructure, Emer Post Limited 50,000.00 39,629.07 Signed 2019-08-01 2019-05-01 2019-08-11 2019-05-03 2019-09-01 2019-05-26 2019-10-13 2019-07-15 2021-11-30 Environment Specialist ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/GS/S8 / Gender Speci Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Limited 60,000.00 70,941.25 Signed 2019-08-25 2019-08-01 2019-09-04 2019-09-05 2019-09-25 2019-10-20 2019-11-06 2019-11-02 2021-11-30 alist ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/CS/S10 / Communica Individual Consult / esilient Infrastructure, Emer Post Limited 60,000.00 30,034.25 Signed 2019-06-01 2019-05-01 2019-06-11 2019-05-03 2019-07-02 2019-05-26 2019-08-13 2019-07-15 2021-11-30 tion Specialist ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/DCCS/S11 / Disaster Individual Consult / esilient Infrastructure, Emer Post Limited 40,000.00 34,796.15 Signed 2019-05-01 2019-05-01 2019-05-11 2019-05-03 2019-06-01 2019-05-26 2019-07-13 2019-07-15 2021-11-30 & Climate Change Specialis ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/IPP/INT-1/S12 / Procu Delivery of Basic Services, R Individual Consult rement Panel International M IDA / D4190 esilient Infrastructure, Emer Post Direct 80,000.00 80,190.00 Completed 2019-04-01 2019-05-01 2019-04-11 2019-05-03 2019-05-02 2019-05-18 2019-06-06 2019-05-15 2019-12-03 2021-02-08 ant Selection ember-1 gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/IPP/NAT-1/S14 / Proc Delivery of Basic Services, R Individual Consult urement Panel National Mem IDA / D4190 esilient Infrastructure, Emer Post Direct 20,000.00 18,246.05 Completed 2019-04-01 2019-05-01 2019-04-11 2019-05-03 2019-05-02 2019-05-20 2019-06-06 2019-05-15 2019-12-03 2021-02-08 ant Selection ber-3 gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/GISE/S15 / GIS Exper Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Limited 40,000.00 58,380.21 Signed 2019-08-30 2019-05-30 2019-09-09 2019-06-11 2019-09-30 2019-08-20 2019-11-11 2019-11-02 2021-10-31 t ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/MIS/S5A / Individual Delivery of Basic Services, R Consultancy Services of a MI Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Direct 1,176.00 12,657.94 Signed 2020-02-16 2020-01-15 2020-02-26 2020-02-04 2020-03-02 2020-03-15 2020-04-06 2020-04-10 2020-10-03 S Specialist for RAP Preparati ant Selection gency Response, and Gende on r-Based Viol ence Prevention Component 1: Strengthening EMCRP/IPP/NAT-1/S14A / Me Delivery of Basic Services, R mber, National of 2-member I Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Direct 28,236.00 25,014.58 Completed 2020-03-01 2020-01-20 2020-03-09 2020-02-02 2020-03-14 2020-03-01 2020-03-24 2020-03-16 2020-05-28 2021-02-24 ndependent Procurement Pa ant Selection gency Response, and Gende nel r-Based Viol ence Prevention Component 1: Strengthening EMCRP/IPP/INT-1/12A / Chair Delivery of Basic Services, R man, 2-member Procurement Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Direct 120,565.00 120,565.00 Completed 2020-03-01 2020-01-20 2020-03-09 2020-02-02 2020-03-14 2020-03-01 2020-03-24 2020-03-16 2020-05-28 2021-02-24 Panel Expert, International E ant Selection gency Response, and Gende xpert r-Based Viol ence Prevention Component 1: Strengthening EMCRP/STS/S1 / Senior Proje Delivery of Basic Services, R Individual Consult ct Management Specialist/Se IDA / D4190 esilient Infrastructure, Emer Post Limited 240,000.00 0.00 Canceled 2020-11-07 2020-11-12 2020-11-26 2021-01-07 2023-02-25 ant Selection nior Technical Specialist gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/FGS/S9 / Field Level Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Limited 50,000.00 0.00 Canceled 2020-08-10 2020-08-12 2020-08-26 2020-10-07 2022-10-27 Gender Specialist ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/SENS/S6 / Senior Env Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Limited 70,000.00 0.00 Canceled 2020-08-25 2020-08-31 2020-09-21 2020-11-02 2023-01-27 ironment Specialist ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/SFMS/S3 / Senior Fin Delivery of Basic Services, R Individual Consult ancial Management Specialis IDA / D4190 esilient Infrastructure, Emer Post Limited 170,000.00 0.00 Canceled 2020-07-30 2021-01-19 2020-08-02 2020-08-16 2020-09-20 2023-03-10 ant Selection t gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/ICT/INT/S17 / Indi Delivery of Basic Services, R Individual Consult vidual Consultancy Services f IDA / D4190 esilient Infrastructure, Emer Post Limited 200,720.00 0.00 Canceled 2020-09-25 2020-09-28 2020-10-19 2020-11-16 2022-11-06 ant Selection or ICT Specialist International gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/ICT/S18 / Individu Delivery of Basic Services, R Individual Consult al Consultancy Services for I IDA / D4190 esilient Infrastructure, Emer Post Limited 72,000.00 0.00 Canceled 2020-09-25 2020-09-28 2020-10-19 2020-11-16 2022-11-06 ant Selection CT Specialist-Local gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/ES/S16 / Consulta Delivery of Basic Services, R Individual Consult ncy Services for Energy Speci IDA / D4190 esilient Infrastructure, Emer Post Limited 65,000.00 0.00 Canceled 2021-03-15 2021-02-10 2021-03-20 2021-04-04 2021-04-26 2023-10-13 ant Selection alist (Individual Consultant) gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/D&S/S1 / Design Delivery of Basic Services, R and Supervision Consulting S IDA / D4190 esilient Infrastructure, Emer Prior Direct Selection Direct 2,356,000.00 0.00 Canceled 2021-02-15 2021-02-25 2021-05-01 2024-01-16 ervices of EMCRP under addit gency Response, and Gende ional financing. r-Based Viol ence Prevention Component 1: Strengthening EMCRP/SPS/S2A / Individual Delivery of Basic Services, R Individual Consult Consultancy Services for Seni IDA / D4190 esilient Infrastructure, Emer Post Limited 76,900.00 95,579.82 Signed 2021-02-28 2021-02-22 2021-03-03 2021-03-15 2021-03-18 2021-03-22 2021-04-22 2021-05-07 2023-04-22 ant Selection or Procurement Specialist gency Response, and Gende r-Based Viol ence Prevention Page 8 Component 1: Strengthening EMCRP/AF/ES/S16. / Consult Delivery of Basic Services, R ancy Services for Energy Spe Individual Consult IDA / D5900 esilient Infrastructure, Emer Post Limited 65,000.00 64,294.41 Signed 2021-09-01 2021-09-01 2021-09-06 2021-09-06 2021-09-20 2021-09-22 2021-10-18 2021-09-30 2024-04-15 cialist (Individual Consultant) ant Selection gency Response, and Gende . r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/ICT/INT./S17 / Con Delivery of Basic Services, R sultancy Services for Internat Individual Consult Under Implement IDA / D5900 esilient Infrastructure, Emer Post Limited 198,000.00 0.00 2021-10-05 2021-10-18 2021-10-13 2021-11-18 2021-12-31 2024-01-01 ional ICT Specialist (Individua ant Selection ation gency Response, and Gende l Consultant). r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/ICT/S18. / Consult Delivery of Basic Services, R Individual Consult ancy Services for ICT Speciali IDA / D5900 esilient Infrastructure, Emer Post Limited 70,700.00 0.00 Signed 2021-10-05 2021-10-03 2021-10-10 2023-10-05 2021-10-31 2023-11-01 2021-12-02 2023-11-20 2023-12-01 ant Selection st (Individual Consultant). gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/D&S./S1 / Design Delivery of Basic Services, R & Supervision Consulting Ser IDA / D4190 esilient Infrastructure, Emer Prior Direct Selection Direct 2,356,000.00 2,206,757.23 Signed 2021-11-02 2021-12-09 2021-11-10 2021-12-12 2021-12-23 2022-04-03 2024-06-30 vices of EMCRP under additio gency Response, and Gende nal financing r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/FS/S19 / Consulta Delivery of Basic Services, R Individual Consult ncy services for Forestry Spe IDA / D5900 esilient Infrastructure, Emer Post Limited 55,000.00 53,231.55 Signed 2021-11-14 2021-12-26 2021-11-19 2021-12-27 2021-12-03 2022-01-26 2021-12-31 2022-02-04 2023-12-31 ant Selection cialist (Individual Consultant) gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/M&E./S2 / Monitor Delivery of Basic Services, R ing and Evaluation Consultan IDA / D5900 esilient Infrastructure, Emer Post Direct Selection Direct 824,450.00 803,590.77 Signed 2021-12-08 2021-12-13 2021-12-18 2021-12-22 2022-01-30 2022-01-24 2024-05-29 t gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/SDS/S4 / Individu Delivery of Basic Services, R al Consultancy services for S Individual Consult IDA / D5900 esilient Infrastructure, Emer Post Direct 57,300.00 56,805.01 Signed 2021-12-05 2021-12-09 2021-12-13 2021-12-27 2021-12-18 2021-12-28 2021-12-30 2022-01-03 2023-12-30 enior Social Development Sp ant Selection gency Response, and Gende ecialist r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/FENS/S7 / Individ Delivery of Basic Services, R Individual Consult ual Consultancy services for IDA / D5900 esilient Infrastructure, Emer Post Direct 38,700.00 38,208.68 Signed 2021-12-05 2021-12-09 2021-12-13 2022-01-02 2021-12-18 2022-01-03 2021-12-30 2022-01-08 2023-12-30 ant Selection Environment Specialist gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/GS/S8 / Individual Delivery of Basic Services, R Individual Consult Consultancy services for Gen IDA / D5900 esilient Infrastructure, Emer Post Direct 77,550.00 70,056.04 Signed 2021-12-05 2021-12-09 2021-12-13 2021-12-27 2021-12-18 2021-12-28 2021-12-30 2022-01-03 2023-12-30 ant Selection der Specialist gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/GIS/S15 / Individu Delivery of Basic Services, R Individual Consult al Consultancy services for GI IDA / D5900 esilient Infrastructure, Emer Post Direct 63,825.00 58,059.06 Signed 2021-12-05 2021-12-09 2021-12-13 2021-12-23 2021-12-18 2021-12-28 2021-12-30 2022-01-03 2023-12-30 ant Selection S Expert gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/IPP/INT-1/S12 / Co Delivery of Basic Services, R nsultancy Services of Procure Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Direct 86,000.00 0.00 Canceled 2021-02-28 2021-03-06 2021-03-13 2021-03-27 2021-05-26 ment Panel Member (Internat ant Selection gency Response, and Gende ional) r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/IPP/NAT-1/S14 / C Delivery of Basic Services, R onsultancy Services of Procur Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Direct 25,000.00 0.00 Canceled 2021-02-28 2021-03-06 2021-03-13 2021-03-27 2021-05-26 ement Panel Member (Nation ant Selection gency Response, and Gende al) r-Based Viol ence Prevention EMCRP/AF/M&E/S2 / Consulti Component 1: Strengthening ng Services for Monitoring a Delivery of Basic Services, R nd Evaluation under EMCRP- IDA / D4190 esilient Infrastructure, Emer Post Direct Selection Direct 857,500.00 0.00 Canceled 2021-02-15 2021-02-25 2021-05-01 2024-01-16 AF under additional Financin gency Response, and Gende g. r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/CS/S10.A / Individ Delivery of Basic Services, R Individual Consult ual Consultancy services for IDA / D5900 esilient Infrastructure, Emer Post Direct 28,430.00 28,069.68 Signed 2021-12-05 2021-12-09 2021-12-13 2021-12-23 2021-12-18 2021-12-28 2021-12-30 2022-01-03 2023-12-30 ant Selection Communication Specialist gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/SFMS/S3 / Individ Delivery of Basic Services, R ual Consultancy services for Individual Consult IDA / D5900 esilient Infrastructure, Emer Post Limited 109,620.00 0.00 Signed 2022-05-10 2022-08-25 2022-05-20 2022-08-11 2022-06-10 2022-09-11 2022-07-01 2022-10-09 2024-06-30 Senior Financial Management ant Selection gency Response, and Gende Specialist r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/CA./S5 / Communi Delivery of Basic Services, R cation and Awareness Consul IDA / D5900 esilient Infrastructure, Emer Post Direct Selection Direct - National 505,300.00 0.00 Signed 2022-09-15 2022-10-23 2022-09-25 2022-12-27 2022-11-29 2023-04-04 2024-06-17 tant gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/IPP./NAT-1/S14 / C Delivery of Basic Services, R onsultancy services for Procu Pending Impleme IDA / D5900 esilient Infrastructure, Emer Post Direct Selection Direct - National 17,000.00 0.00 2022-10-01 2022-10-11 2022-11-25 2023-11-25 rement Panel Member (Natio ntation gency Response, and Gende nal) r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/IPP./INT-1./S12 / C Delivery of Basic Services, R onsultancy services for Procu Direct - Internation Pending Impleme IDA / D5900 esilient Infrastructure, Emer Post Direct Selection 57,500.00 0.00 2022-10-01 2022-10-11 2022-11-19 2023-11-19 rement Panel Member (Intern al ntation gency Response, and Gende ational) r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/SRRD/S10 / Senio Individual Consult Pending Impleme IDA / D5900 esilient Infrastructure, Emer Post Limited 34,500.00 0.00 2022-10-20 2022-10-25 2022-11-15 2022-12-20 2023-08-17 r Engineer (Rubber Dam) ant Selection ntation gency Response, and Gende r-Based Viol ence Prevention Page 9 Component 1: Strengthening EMCRP/STS./S1 / Senior Proj Delivery of Basic Services, R Individual Consult ect Management/Senior Tech IDA / D4190 esilient Infrastructure, Emer Post Limited 71,650.00 0.00 Signed 2022-10-20 2022-11-02 2022-10-25 2022-11-17 2022-11-15 2022-11-27 2022-12-27 2022-12-10 2023-12-27 ant Selection nical Specialist gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/SPS/S2 / Selection IDA / D5900 esilient Infrastructure, Emer Prior Direct Selection Direct - National 28,000.00 0.00 Canceled 2023-02-19 2023-03-08 2023-02-25 2023-04-02 2023-04-16 2023-10-13 of Sr. Procurement Specialist gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/CA/S5 / Communi Delivery of Basic Services, R cation and Awareness consul IDA / D5900 esilient Infrastructure, Emer Post Direct Selection Direct 505,300.00 0.00 Canceled 2022-06-01 2022-06-11 2022-07-18 2024-07-17 tant gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/IPP/INT-1./S12 / C Delivery of Basic Services, R onsultancy services for Procu Individual Consult IDA / D5900 esilient Infrastructure, Emer Post Direct 57,500.00 0.00 Canceled 2022-01-09 2022-01-19 2022-02-09 2022-03-09 2023-03-09 rement Panel Member (Intern ant Selection gency Response, and Gende ational) r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/IPP/NAT-1./S14 / C Delivery of Basic Services, R onsultancy services for Procu Individual Consult IDA / D5900 esilient Infrastructure, Emer Post Direct 17,000.00 0.00 Canceled 2022-01-09 2022-01-19 2022-02-09 2022-03-09 2023-03-09 rement Panel Member (Natio ant Selection gency Response, and Gende nal) r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF./SPS/S2 / Individu Delivery of Basic Services, R Individual Consult al Consulting Services as a 'S IDA / D5900 esilient Infrastructure, Emer Prior Limited 57,500.00 0.00 Signed 2023-05-18 2023-05-31 2023-05-21 2023-06-07 2023-06-04 2023-06-22 2023-06-30 2023-06-26 2024-06-30 ant Selection enior Procurement Specialist' gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/SERC/S20 / Indivi Delivery of Basic Services, R dual Consulting Services as a Individual Consult Under Implement IDA / D5900 esilient Infrastructure, Emer Post Limited 35,300.00 0.00 2023-05-15 2023-08-27 2023-05-20 2023-10-08 2023-06-03 2023-06-18 2025-07-18 'Senior Emergency Response ant Selection ation gency Response, and Gende Specialist' r-Based Viol ence Prevention EMCRP/AF/SGS/S8 / Consulti Component 1: Strengthening ng Services for Safeguards St Delivery of Basic Services, R udy for future project (Consul IDA / D4190 esilient Infrastructure, Emer Post Direct Selection Direct - National 812,721.00 0.00 Signed 2023-10-31 2023-11-14 2023-11-10 2023-11-23 2024-01-14 2024-07-12 ting Services for Environmen gency Response, and Gende tal and Social Framework Co r-Based Viol ence Prevention mpliance Study for future Pro ject) Page 10