PROCUREMENT PLAN (Textual Part) Project information: Democratic Republic Democratic of Congo – Forest and Savanna Restoration Investment Program (P178642) Project Implementation agency: Forest Investment Program Coordination Unit (FIP-CU) Date of the Procurement Plan: June 8, 2023 Period covered by this Procurement Plan: 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Borrower’s Public Procurement Law No 10/010 of April 27, 2010 (PPL) and the Manual of Procedures of the PPL as per Borrower’s Decree No 10/22 of June 2, 2010, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (a) Standard Bidding Documents: All standard bidding documents to be used for the Project under NCB shall be found acceptable to the World Bank before their use during the implementation of Project; (b) Eligibility: Eligibility of bidders and acceptability of their goods and services shall not be based on their nationality and/or their origin; and association with a national firm shall not be a condition for participation in a bidding process. Therefore, except for the ineligibility situations referred to in paragraphs 3.23.10(a) (i) and 3.23(a) (ii) of the Procurement Guidelines, the eligibility of bidders must be based solely on their qualification, experience and capacity to carry out the contract related to the specific bidding process; (c) Advertising and Bid Preparation Time: Bidding opportunities shall be advertised at least in a national newspaper of wide circulation and on the website of the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) and bidders should be given at least 30 days from the date of invitation to bid or the date of availability of the bidding documents, whichever is later; (d) Criteria for Qualification of Bidders: Qualification criteria shall only concern the bidder’s capability and resources to perform the contract taking into account objective and measurable factors. Such criteria for qualification of bidders shall be clearly specified in the bidding documents; (e) Bid Evaluation and Contract Award: A contract shall be awarded to the substantially responsive and lowest evaluated bidder provided that such bidder meets the qualification criteria specified in the bidding documents. No scoring system shall be allowed for the evaluation of bids, and no “blanket” limitation to the number of lots which can be awarded to a bidder shall apply. The criteria for bid evaluation and the contract award conditions shall be clearly specified in the bidding documents; (f) Preferences: No preference shall be given to domestic/regional bidders; to domestically/regionally manufactured goods; and to bidders forming a joint venture with a national firm or proposing national sub- contractors or carrying out economic activities in the territory of the Recipient; (g) Publication of Contract Award: Information on all contract awards shall be published in at least a national newspaper of wide circulation or in the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) web-site; (h) Fraud and Corruption: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy to sanction firms or individuals found to have engaged in fraud and corruption as set forth in the Procurement Regulations ; (i) Inspection and Audit Rights: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy with respect to inspection and audit of accounts, records and other documents relating to the bid submission and contract performance; (j) Requirement for administrative documents and/or tax clearance certificate: The bidding documents shall not require foreign bidders to produce any administrative or tax related certificates prior to confirmation of awarding a contract; and (k) Modifications of a Signed Contract: Any change in the contract amount which, singly or combined with all previous changes, increases the original contract amount by fifteen (15) percent or more must be done through an amendment to the signed contract instead of signing a new contract.. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable for those contracts identified in the Procurement Plan tables] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc (Not Applicable). PROCUREMENT Congo, Democratic Republic of : Forest and Savanna Restoration Investment Program PLAN General Information Country: Congo, Democratic Republic of 2023-06-09 Bank’s Approval Date of the Original Procurement Plan: 2024-01-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178642 GPN Date: Project Name: Forest and Savanna Restoration Investment Program Loan / Credit No: IDA / V4550, IDA / 73340 DRC FIP Improved Foreted Landscape Management Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-PIF-360167-GO-RFB / Acq 2. Development of Agrofores uisition des matériels inform try and Forest Value Chains f Single Stage - One E En attente d' atiques, GPS, drones mappin IDA / V4550 or Sustainable Landscape M A posteriori Appel d'offres Open - National 850,000.00 0.00 2023-07-26 2023-07-31 2023-09-11 2023-10-11 2023-11-15 2024-05-13 nvelope exécution g et autres équipements de r anagement and Improved Li eprographie pour les ALE. velihoods 2. Development of Agrofores ZR-PIF-360172-GO-RFB / Acq try and Forest Value Chains f Open - Internationa Single Stage - One E En attente d' uisition de 36 tracteurs équip IDA / V4550 A priori Appel d'offres 10,200,000.00 0.00 2023-08-14 2023-08-19 2023-09-30 2023-10-30 2023-12-04 2024-06-01 or Sustainable Landscape M l nvelope exécution és pour les ALEs anagement and Improved Li velihoods ZR-PIF-360173-GO-DIR / Acq 2. Development of Agrofores uisition des sachets biodégra try and Forest Value Chains f Passation de marc En cours d'ex dable de pépinières (en fave IDA / V4550 or Sustainable Landscape M A posteriori Direct - National 900,000.00 0.00 2023-06-22 2023-08-15 2023-06-27 2023-08-01 2024-01-28 hé de gré à gré écution ur des ALEs du projet dans le anagement and Improved Li cadre des activités d'agrofor velihoods esterie) 2. Development of Agrofores ZR-PIF-360175-GO-RFQ / Ac try and Forest Value Chains f Single Stage - One E En attente d' quisition de 216 motos pour l IDA / V4550 A posteriori Demande de prix Limited 972,000.00 0.00 2023-08-21 2023-10-16 2024-04-13 or Sustainable Landscape M nvelope exécution es ALE anagement and Improved Li velihoods 2. Development of Agrofores ZR-PIF-360178-GO-RFB / Acq try and Forest Value Chains f Single Stage - One E En attente d' uisition de 72 Tricycles avec IDA / V4550 A posteriori Appel d'offres Open - National 360,000.00 0.00 2023-09-13 2023-09-18 2023-10-30 2023-11-29 2024-01-03 2024-07-01 or Sustainable Landscape M nvelope exécution accessoires pour les ALE anagement and Improved Li velihoods ZR-PIF-360181-GO-RFB / Acq 2. Development of Agrofores uisition des outils aratoires p try and Forest Value Chains f Open - Internationa Single Stage - One E En attente d' our la mise en place des pépi IDA / V4550 or Sustainable Landscape M A posteriori Appel d'offres 1,800,000.00 0.00 2023-09-26 2023-10-01 2023-11-12 2023-12-12 2024-01-16 2024-07-14 l nvelope exécution nières (en faveur des ALEs anagement and Improved Li du projet dans le cadre des a velihoods ctivités d'agroforesterie) ZR-PIF-357838-GO-RFQ / Ac 5. Project Implementation an Single Stage - One E En cours d'ex quisition des matériels roulan IDA / V4550 A posteriori Appel d'offres Open - National 770,000.00 0.00 2023-07-17 2023-07-05 2023-07-22 2023-07-07 2023-09-02 2023-08-17 2023-10-02 2023-11-06 2024-05-04 d Monitoring and Evaluation nvelope écution t pour l'UC-PIF ZR-PIF-336496-GO-RFQ / Ac quisition des matériels infor 5. Project Implementation an Single Stage - One E IDA / V4550 A posteriori Demande de prix Limited 75,000.00 0.00 Achevé 2023-07-02 2023-06-29 2023-08-11 2023-08-09 2023-11-09 2023-08-12 matique et de reprographie p d Monitoring and Evaluation nvelope our les antenne et la coordin ation de l'UC-PIF 2. Development of Agrofores ZR-PIF-402623-GO-RFB / Acq try and Forest Value Chains f Single Stage - Two E En attente d' uisition de 216 motos pour le IDA / 73340 A posteriori Appel d'offres Open - National 972,000.00 0.00 2024-01-29 2024-02-03 2024-03-16 2024-04-23 2024-05-28 2024-11-24 or Sustainable Landscape M nvelope exécution s ALE anagement and Improved Li velihoods NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-PIF-336133-CS-CQS / Rec rutement d'un cabinet en ch Sélection fondée s 5. Project Implementation an En attente d'exéc arge des Études de référence IDA / V4550 A posteriori ur les qualification Open - National 600,000.00 0.00 2023-04-26 2023-05-05 2023-06-16 2023-06-29 2023-07-27 2023-10-25 d Monitoring and Evaluation ution sur la situation socioéconomi s des consultants que des ménages de la zone du Projet ZR-PIF-357847-CS-QCBS / Ét udes prospectives sur la plan 1. Improved Land use Planni Sélection fondée s ification du développement s ng and Governance for Natu Open - Internationa En attente d'exéc IDA / V4550 A posteriori ur la qualité et le 300,000.00 0.00 2023-05-22 2023-06-12 2023-07-26 2023-08-23 2023-09-22 2023-10-27 2023-12-01 2024-02-29 patial dans les secteurs écon ral Resource Management in l ution coût omiques clés en tenant comp Selected Project Areas te de la résilience climatique à long terme. ZR-PIF-357859-CS-QCBS / Mi ssion d’un Consultant en cha 1. Improved Land use Planni rge de l’élaboration des Plan Sélection fondée s ng and Governance for Natu Open - Internationa En cours d'exécut s provinciaux d’aménagemen IDA / V4550 A posteriori ur la qualité et le 1,000,000.00 0.00 2023-05-25 2023-07-07 2023-06-15 2023-07-29 2023-08-26 2023-09-25 2023-10-30 2023-12-04 2026-12-03 ral Resource Management in l ion t du territoire (PPAT) « provin coût Selected Project Areas ces et territoires » dans les p rovinces concernées par le PI FORES Page 1 ZR-PIF-357874-CS-QCBS / Mi 1. Improved Land use Planni ssion d'n Consultant pour acc Sélection fondée s ng and Governance for Natu Open - Internationa En attente d'exéc ompagner la CONAREF afin d IDA / V4550 A posteriori ur la qualité et le 700,000.00 0.00 2023-05-19 2023-06-09 2023-07-23 2023-08-20 2023-09-19 2023-10-24 2023-11-28 2026-11-27 ral Resource Management in l ution e tester la mise en place d'un coût Selected Project Areas registre des terres rurales ZR-PIF-357877-CS-QCBS / Ét udes sur le genre et les autre 1. Improved Land use Planni Sélection fondée s s groupes vulnérables pour i ng and Governance for Natu IDA / V4550 A posteriori ur la qualité et le Open - National 100,000.00 0.00 Annulé 2023-05-23 2023-06-13 2023-07-27 2023-08-24 2023-09-23 2023-10-28 2023-12-02 2024-12-01 dentifier les priorités respecti ral Resource Management in coût ves à prendre en compte dan Selected Project Areas s le processus d'aménageme nt du territoire ZR-PIF-357882-CS-QCBS / Re crutement d’un assistant tec 1. Improved Land use Planni Sélection fondée s hnique en appui au renforce ng and Governance for Natu Open - Internationa En attente d'exéc IDA / V4550 A posteriori ur la qualité et le 500,000.00 0.00 2023-06-13 2023-07-04 2023-08-17 2023-09-14 2023-10-14 2023-11-18 2023-12-23 2026-12-22 ment des capacités du secte ral Resource Management in l ution coût ur public sur les politiques na Selected Project Areas tionales sur l'environnement ZR-PIF-357891-CS-QCBS / Re 2. Development of Agrofores Sélection fondée s crutement d'un consultant en try and Forest Value Chains f En attente d'exéc IDA / V4550 A posteriori ur la qualité et le Open - National 250.00 0.00 2023-05-26 2023-06-16 2023-07-30 2023-08-27 2023-09-26 2023-10-31 2023-12-05 2025-12-04 charge de renforcer les ALE e or Sustainable Landscape M ution coût n technique GALS anagement and Improved Li velihoods ZR-PIF-357892-CS-QCBS / Mi ssion d'un assistant techniqu 3. Development of Sustainab Sélection fondée s Open - Internationa En attente d'exéc e en charge du développeme IDA / V4550 le Value Chain for Energy an A posteriori ur la qualité et le 700,000.00 0.00 2023-06-22 2023-07-13 2023-08-26 2023-09-23 2023-10-23 2023-11-27 2024-01-01 2026-12-31 l ution nt et de suivi d'une chaine de d Efficient Cooking coût valeur du bois Energie propre ZR-PIF-357896-CS-QCBS / Mi ssion d'un Assistant Techniqu 2. Development of Agrofores e en charge de l'Appui à la M try and Forest Value Chains f Sélection fondée s aitrise d'Ouvrage (AMO) de la Open - Internationa En attente d'exéc IDA / V4550 or Sustainable Landscape M A posteriori ur la qualité et le 700,000.00 0.00 2023-05-15 2023-06-05 2023-07-19 2023-08-16 2023-09-15 2023-10-20 2023-11-24 2027-11-23 composante 2.1.b du projet s l ution anagement and Improved Li coût ur les subvention du secteur velihoods privé pour la zone centre du Projet (KASAI-CENTRAL, KASA I ORIENTAL et LOMAMI) ZR-PIF-360154-CS-QCBS / Mi ssion d'un Assistant Techniqu 2. Development of Agrofores e en charge de l'Appui à la M try and Forest Value Chains f Sélection fondée s aitrise d'Ouvrage (AMO) de la Open - Internationa En attente d'exéc IDA / V4550 or Sustainable Landscape M A posteriori ur la qualité et le 700,000.00 0.00 2023-07-18 2023-08-02 2023-09-15 2023-10-13 2023-11-03 2023-12-01 2023-12-16 2023-12-30 composante 2.1.b du projet s l ution anagement and Improved Li coût ur les subvention du secteur velihoods privé pour la zone ouest du P rojet (Kwilu, Kassai, Kongo ce ntral et Kinshasa) ZR-PIF-336275-CS-LCS / Ser vices d'un consultant pour l'A Sélection fondée s udit financier et comptable d 5. Project Implementation an IDA / V4550 A posteriori ur la qualité et le Open - National 50,000.00 0.00 Annulé 2023-09-18 2023-10-09 2023-11-22 2023-12-20 2024-01-19 2024-02-23 2024-03-29 2025-03-29 e deux premières années du d Monitoring and Evaluation coût Projet (y inclus le fonds de pr éparation au premier exercic e). ZR-PIF-379332-CS-QCBS / Se rvice d'un Consultant pour l'é Sélection fondée s 5. Project Implementation an En cours d'exame tude sur l'estimation de beso IDA / 73340 A posteriori ur la qualité et le Open - National 50,000.00 0.00 2023-09-08 2024-01-12 2023-09-29 2023-10-21 2023-11-18 2023-12-03 2024-01-01 2024-02-05 2024-04-05 d Monitoring and Evaluation n in en combustibles ligneux d coût es principales villes des provi nces du PIFORES ZR-PIF-379355-CS-QCBS / Mi 2. Development of Agrofores ssion d'un MOD en charge d' try and Forest Value Chains f Sélection fondée s appuyer le développement d Open - Internationa En attente d'exéc IDA / 73340 or Sustainable Landscape M A priori ur la qualité et le 22,000,000.00 0.00 2023-09-07 2023-09-28 2023-10-20 2023-11-17 2023-12-02 2023-12-31 2024-01-29 2028-01-28 e la foresterie communautair l ution anagement and Improved Li coût e à travers les CFCL et la mis velihoods e en place des chaines de val eur durable INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-PIF-335968-CS-INDV / Ét ude et diagnostic sur les filièr es porteuses des cultures agr 5. Project Implementation an En attente d'exéc icoles (y compris les cultures IDA / V4550 A posteriori Individuel Limited 30,000.00 0.00 2023-07-07 2023-08-06 2023-08-20 2023-09-09 2023-10-09 d Monitoring and Evaluation ution pérennes et les produits fore stiers non ligneux) existantes dans les différentes zones d u Projet ZR-PIF-335986-CS-INDV / Mi ssion d'un consultant en char ge de la Géolocalisation des zones cibles du programme ( En cours d'exame IDA / V4550 A posteriori Individuel Limited 70,000.00 0.00 2023-02-20 2023-09-13 2023-04-06 2023-04-20 2023-05-10 2023-11-06 Bassins de production, voies n de communication, infrastruc ture socio-économique de ba se) pour orienter les mécanis mes d’incitation (PSE) ZR-PIF-336181-CS-INDV / Mi ssion d'un Consultant en cha 5. Project Implementation an En attente d'exéc IDA / V4550 A posteriori Individuel Limited 30,000.00 0.00 2023-07-14 2023-07-24 2023-08-07 2023-08-27 2023-11-25 rge de l'Etude sur la foresteri d Monitoring and Evaluation ution e communautaire dans les zo nes du projet. ZR-PIF-336268-CS-INDV / Mi ssion d'un Consultant en cha rge de l'identification des pot 5. Project Implementation an En cours d'exécut IDA / V4550 A posteriori Individuel Limited 50,000.00 0.00 2023-05-23 2023-07-04 2023-06-02 2023-06-16 2023-07-06 2023-10-04 entialités en matière d'inter d Monitoring and Evaluation ion médiation financière (banque s, microfinance, mobile mone y) ZR-PIF-336457-CS-INDV / Se rvices d'un Consultant pour l' 5. Project Implementation an En attente d'exéc élaboration des EIES des tra IDA / V4550 A posteriori Individuel Limited 75,000.00 0.00 2023-07-11 2023-07-21 2023-08-11 2023-08-31 2024-02-27 d Monitoring and Evaluation ution vaux de réhabilitation du bati ment devant abriter les bure aux du Projet ZR-PIF-357386-CS-INDV / Mi ssion d'un Spécialiste en Pas 5. Project Implementation an En cours d'exécut IDA / V4550 A priori Individuel Limited 300,000.00 0.00 2023-04-28 2023-06-16 2023-05-03 2023-06-29 2023-05-17 2023-08-25 2023-06-21 2023-12-28 sation des Marchés supplém d Monitoring and Evaluation ion entaire pour le PIFORES Page 2 ZR-PIF-357392-CS-INDV / Re 5. Project Implementation an En cours d'exécut crutement d'un forestier spé IDA / V4550 A priori Individuel Limited 300,000.00 0.00 2023-05-05 2023-06-16 2023-05-10 2023-08-10 2023-05-31 2023-07-05 2023-12-31 d Monitoring and Evaluation ion cialiste en biodiversité ZR-PIF-357824-CS-INDV / Re 5. Project Implementation an En cours d'exame crutement d'un Expert Agroé IDA / V4550 A priori Individuel Limited 300,000.00 0.00 2023-05-04 2023-06-16 2023-05-09 2023-08-10 2023-05-30 2023-06-27 2023-12-29 d Monitoring and Evaluation n conomiste pour l'UC-PIF ZR-PIF-357827-CS-INDV / Re 5. Project Implementation an En cours d'exame crutement d'un Expert en ch IDA / V4550 A priori Individuel Limited 300,000.00 0.00 2023-05-09 2023-07-17 2023-05-14 2023-08-29 2023-06-04 2023-07-09 2024-01-05 d Monitoring and Evaluation n arge du MRV ZR-PIF-357833-CS-INDV / Re crutement d'un chargé de Pr 5. Project Implementation an En cours d'exécut IDA / V4550 A priori Individuel Limited 300,000.00 0.00 2023-05-30 2023-08-15 2023-06-04 2023-08-23 2023-06-25 2023-10-17 2023-07-30 2024-01-26 ojet cuisson propre PIFORES d Monitoring and Evaluation ion au niveau de l'ANSER ZR-PIF-336272-CS-INDV / Se rvice d'un Consultant pour l'é 5. Project Implementation an tude sur l'estimation de beso IDA / V4550 A posteriori Individuel Open - National 30,000.00 0.00 Annulé 2023-07-25 2023-09-12 2023-10-03 2023-11-07 2024-02-05 d Monitoring and Evaluation ins en combustibles ligneux des principales villes de provi nces ZR-PIF-336274-CS-INDV / Se rvices d'un Consultant pour l' 5. Project Implementation an élaboration du manuel des pr IDA / V4550 A posteriori Individuel Limited 20,000.00 0.00 Annulé 2023-07-28 2023-08-10 2023-08-24 2023-09-13 2023-12-12 d Monitoring and Evaluation océdures du Projet (y compri s le manuel d'appel à projets ). ZR-PIF-369523-CS-INDV / Re 5. Project Implementation an En cours d'exame crutement d'un Expert en dé IDA / 73340 A priori Individuel Open - National 300,000.00 0.00 2023-07-05 2023-07-10 2023-08-03 2023-08-13 2023-09-06 2023-12-30 d Monitoring and Evaluation n veloppement social pour l'UC -PIF ZR-PIF-369526-CS-INDV / Re 5. Project Implementation an En cours d'exécut crutement d'un Expert nation IDA / 73340 A priori Individuel Open - National 300,000.00 0.00 2023-07-06 2023-07-10 2023-08-04 2023-08-14 2023-08-29 2024-08-28 d Monitoring and Evaluation ion al Genre et VBG pour l'UC-PIF ZR-PIF-385206-CS-INDV / Re 5. Project Implementation an En cours d'exécut crutement d'un Chef Compta IDA / 73340 A posteriori Individuel Open - National 42,000.00 0.00 2023-10-09 2023-10-10 2023-11-27 2023-12-18 2024-01-22 2025-01-21 d Monitoring and Evaluation ion ble pour l'UC-PIF ZR-PIF-385208-CS-INDV / Se 5. Project Implementation an En cours d'exécut rvice d'un Comptable pour l' IDA / 73340 A posteriori Individuel Open - National 40,000.00 0.00 2023-10-06 2023-10-10 2023-11-24 2023-12-15 2024-01-19 2025-01-18 d Monitoring and Evaluation ion UC-PIF dans le cadre du PIFO RES ZR-PIF-385525-CS-INDV / Mi ssion d'un Consultant en app ui à l’évaluation des services 5. Project Implementation an En cours d'exécut techniques centraux et déco IDA / 73340 A posteriori Individuel Limited 40,000.00 0.00 2023-10-11 2023-10-11 2023-10-16 2023-11-06 2023-12-11 2024-06-08 d Monitoring and Evaluation ion ncentrés (niveau provincial e t territorial) pour l’implication et l’accompagnement dans l a mise en œuvre du PIFORES ; ZR-PIF-394851-CS-INDV / Mi ssion d’un Consultant pour l’ évaluation des capacités org 5. Project Implementation an En attente d'exéc anisationnelles et fonctionnel IDA / 73340 A posteriori Individuel Limited 20,000.00 0.00 2023-12-04 2023-12-09 2023-12-30 2024-02-03 2024-02-23 d Monitoring and Evaluation ution les du Centre d’Etudes et des Recherches sur les Energies Renouvelables Kitsisa Khond e (CERERK) ZR-PIF-402017-CS-INDV / Mi ssion de 3 consultants en cha rge des études architecturale s relatives à la réhabilitation des bâtiments devant abriter 5. Project Implementation an En attente d'exéc IDA / 73340 A posteriori Individuel Limited 75,000.00 0.00 2024-01-19 2024-01-24 2024-02-14 2024-03-07 2024-05-06 les bureaux du Projets en pro d Monitoring and Evaluation ution vinces Lot 1: Kongo Central - Kwilu Lot 2: Kasai Central - Kasai O riental Lot 3: Lomami-Kasai ZR-PIF-402608-CS-INDV / MI SSION D'UN CONSULTANT EX PERT NATIONAL JURISTE POU 5. Project Implementation an En attente d'exéc IDA / 73340 A posteriori Individuel Limited 20,000.00 0.00 2024-01-22 2024-01-26 2024-02-16 2024-03-22 2024-07-19 R APPUYER L'ELABORATION d Monitoring and Evaluation ution DES TEXTES JURIDIQUES SUR LE SECTEUR DE LA CUISSON PROPRE Page 3