Procurement Plan Jamaica Disaster Vulnerability Reduction Project (P146965) I. General 1. Bank’s approval Date of the procurement Plan: Revision 1 of Updated Procurement Plan, December 2017 2. Date of General Procurement Notice: N/A 3. Period covered by this procurement plan: July 2016 – December 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 1 million All 2. NCB (Goods) Above US$ 0.1 n/a million 3. ICB (Works) Above US$ 7.5 All million 4. NCB (Works) Above US$ 0.2 n/a million 5. (Non-Consultant Services) Above US$ 1 million All III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 2 million 2. Single Source (Firms) Above US$ 1 million 3. Individual Above US$ 0.4 million 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. PROCUREMENT Jamaica : Jamaica Disaster Vulnerability Reduction Project PLAN General Information Country: Jamaica 2017-12-18 Bank’s Approval Date of the Original Procurement Plan: 2024-01-16 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P146965 GPN Date: Project Name: Jamaica Disaster Vulnerability Reduction Project Loan / Credit No: IBRD / 85810 Jamaica Social Investment Fund Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned RISK REDUCTION - 13 / Drain Single Stage - One E 2018-12-0 IBRD / 85810 Risk Reduction Post Request for Bids Open - National 750,000.00 602,130.62 Completed 2017-12-01 2018-01-15 2017-12-06 2018-01-17 2018-02-13 2018-05-01 2018-05-30 2018-06-05 2018-08-02 age Works - Church Pen nvelope 2 UNDERSTANDING RISK - 12 / Technical Assistance for Imp Construction and Upgrading Request for Quota Single Stage - One E 2017-10-1 IBRD / 85810 roved Disaster and Climate Post Limited 33,127.00 30,130.35 Completed 2017-02-18 2017-02-17 2017-04-15 2017-04-03 of Towers (Font Hill, Yallahs, tions nvelope 2 Resilience UWI, Stoney Hill + minor wor ks at stations) RISK REDUCTION - 3 / Constr Single Stage - One E 2019-08-0 IBRD / 85810 Risk Reduction Post Request for Bids Open - National 1,300,000.00 818,126.34 Completed 2018-09-01 2019-02-14 2018-09-06 2018-11-15 2019-03-19 2018-12-31 2019-04-01 2019-02-04 2019-12-22 uction of Yallahs Fire Station nvelope 3 RISK REDUCTION - 1 / Constr Single Stage - One E 4,078,202.1 2019-09-0 IBRD / 85810 Risk Reduction Post Request for Bids Open - National 2,500,000.00 Completed 2018-10-01 2018-09-20 2018-10-06 2018-12-15 2018-11-06 2019-01-30 2019-01-08 2019-03-06 2019-11-24 uction of Montego Bay Fire St nvelope 7 2 ation RISK REDUCTION - 2 / Constr Single Stage - One E 1,605,219.4 2019-07-0 IBRD / 85810 Risk Reduction Post Request for Bids Open - National 1,500,000.00 Completed 2018-08-01 2018-10-25 2018-08-06 2018-10-15 2019-01-31 2018-11-30 2019-12-04 2019-01-04 2019-11-07 uction of Port Maria Fire Stati nvelope 7 3 on RR - 17 - 1 / Port Royal Coast Single Stage - One E 6,801,990.5 2021-04-0 IBRD / 85810 Risk Reduction Post Request for Bids Open - National 4,730,000.00 Completed 2019-03-18 2019-04-16 2019-03-23 2019-06-01 2019-06-18 2019-08-20 2019-07-22 2019-10-07 2020-03-17 al Revetment Works nvelope 0 7 RISK REDUCTION - 17 / Port Single Stage - One E 2019-05-0 IBRD / 85810 Risk Reduction Post Request for Bids Open - National 4,730,000.00 0.00 Canceled 2018-06-01 2018-08-20 2018-06-06 2018-08-15 2018-10-23 2018-09-30 2018-11-04 Royal Coastal Revetment Wo nvelope 3 rks UR - 10 - 1 / Supply & Install Technical Assistance for Imp Single Stage - One E 2020-10-3 IBRD / 85810 Post Request for Bids Open - National 33,000.00 23,339.03 Completed 2020-01-13 2017-11-20 2020-01-18 2020-02-29 2017-12-01 2020-03-30 2017-12-11 2020-05-04 2017-12-27 ation of Pole Mount roved Disaster and Climate nvelope 1 Resilience RR - 9 / St. Benedicts Primar Single Stage - One E 2021-07-2 IBRD / 85810 Risk Reduction Post Request for Bids Open - National 450,000.00 0.00 Canceled 2020-10-04 2020-10-09 2020-11-20 2020-12-20 2021-01-24 y Construction Works nvelope 3 Request for Bids - RISK REDUCTION - 15 - 1 / M Single Stage - One E Works (without pr 2023-04-0 IBRD / 85810 Risk Reduction Post Request for Bids Open - National 2,000,000.00 0.00 Signed 2021-10-25 2021-10-29 2021-10-30 2021-10-29 2021-12-14 2021-12-15 2022-05-13 2022-04-05 2022-07-08 2022-11-16 yton Gully Drainage Phase 1 nvelope equalification) SP 4 D UR - 29 / Procurement for th Technical Assistance for Imp Single Stage - One E 2022-01-0 IBRD / 85810 Post Request for Bids Limited 35,000.00 0.00 Canceled 2021-04-05 2021-04-19 2021-05-17 2021-06-14 2021-07-12 e execution of small works pr roved Disaster and Climate nvelope 8 oject Resilience RR - 22 / Connection of elect Request for Quota 2022-08-1 ricity, water and sewerage su IBRD / 85810 Risk Reduction Post Direct Selection Direct tions (Non Bank-S 100,000.00 104,257.47 Signed 2022-03-08 2022-03-04 2022-03-16 2022-04-06 2022-05-19 2022-05-03 7 pplies for Montego Bay Fire S PD) tation RR - 25 / Contract for the co Request for Quota nstruction of a soak away pit, 2022-08-2 IBRD / 85810 Risk Reduction Post Direct Selection Direct tions (Non Bank-S 90,000.00 0.00 Canceled 2022-06-15 2022-06-22 2022-07-13 supply and installation of fire 4 PD) pump and railings to fire pole . National Procure RR - 29 / Contractor to under ment Document - take coastal protection works Under Imple 2024-05-3 IBRD / 85810 Risk Reduction Post Direct Selection Direct - National 1 Envelope proce 1,150,000.00 0.00 2023-11-27 2023-11-20 2023-12-04 2023-12-08 2024-03-04 including beach nourishment mentation 1 ss (Non Bank-SPD and revetment in Annotto Ba ) y GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UNDERSTANDING RISK - 4 / Technical Assistance for Imp Request for Quota Single Stage - One E Supply of Computer Server ( IBRD / 85810 roved Disaster and Climate Post Limited 16,726.00 17,989.29 Completed 2017-02-01 2017-01-27 2017-03-29 2017-03-20 2017-09-25 2020-03-12 tions nvelope 1) & Monitors (8) Resilience UNDERSTANDING RISK - 5 / Technical Assistance for Imp Request for Quota Single Stage - One E Supply of Oscilloscope (1) an IBRD / 85810 roved Disaster and Climate Post Limited 8,986.00 18,900.35 Completed 2017-03-01 2017-03-16 2017-04-26 2017-04-08 2017-10-23 2017-09-22 tions nvelope d Spectrum Analyzer (1) Resilience UNDERSTANDING RISK - 9 / Technical Assistance for Imp Supply & Installation (24 Sola Request for Quota Single Stage - One E IBRD / 85810 roved Disaster and Climate Post Limited 54,655.00 45,723.51 Completed 2017-04-15 2017-04-11 2017-06-10 2017-08-23 2017-12-07 2018-04-12 r Systems for the remote stat tions nvelope Resilience ions + 1 for UWI CRS) UNDERSTANDING RISK - 11 / Technical Assistance for Imp Supply & Installation (8 Grou Request for Quota Single Stage - One E IBRD / 85810 roved Disaster and Climate Post Limited 50,156.00 39,618.66 Completed 2017-04-30 2017-04-10 2017-06-25 2017-07-01 2017-12-22 2018-04-28 nding & Lightening Protectio tions nvelope Resilience n + 3 Communication tower + 1 repair) RISK REDUCTION - 19 / Proc Single Stage - One E urement of *2 Water Tanker IBRD / 85810 Risk Reduction Post Request for Bids Open - National 400,000.00 457,810.48 Completed 2017-12-11 2018-02-13 2017-12-16 2018-01-27 2018-04-11 2018-04-13 2018-04-11 2018-05-18 2018-11-17 2018-11-14 2018-11-17 nvelope Trucks (incl. spare parts & m aintenance) RISK REDUCTION - 20 / Proc Single Stage - One E urement of *4 Pumper Trucks IBRD / 85810 Risk Reduction Post Request for Bids Open - National 2,000,000.00 2,214,364.70 Completed 2017-12-11 2018-02-12 2017-12-16 2018-01-27 2018-04-11 2018-04-13 2018-04-30 2018-05-18 2018-12-25 2018-11-14 2018-12-25 nvelope (incl. spare parts & maintena nce) PROJECT MANAGEMENT - 4 / Request for Quota Single Stage - One E IBRD / 85810 Project Administration Post Limited 50,000.00 61,118.33 Completed 2017-11-29 2019-04-10 2018-01-24 2018-06-02 2018-07-23 2018-06-03 Motor Vehicle tions nvelope UNDERSTANDING RISK - 3 / Technical Assistance for Imp Request for Quota Single Stage - One E Supply of Equipment (Ethern IBRD / 85810 roved Disaster and Climate Post Limited 36,615.00 27,728.10 Completed 2017-02-28 2017-02-24 2017-04-25 2017-04-16 2017-10-22 2017-08-04 tions nvelope et Radios + Antenna - Type A Resilience & Type B) Page 1 UNDERSTANDING RISK - 7 / Technical Assistance for Imp Request for Quota Single Stage - One E IBRD / 85810 Post Limited 28,292.00 26,744.01 Completed 2017-11-20 2017-11-21 2018-01-15 2017-12-28 2018-07-14 2019-02-15 Supply and install communic roved Disaster and Climate tions nvelope ation link Resilience UNDERSTANDING RISK 6B / IBRD / 85810 Risk Reduction Post Direct Selection Direct 9,150.00 9,150.00 Completed 2018-03-12 2018-03-16 2018-03-17 2018-03-16 2018-04-21 2018-06-12 2018-10-18 2018-06-12 Supply of Multiplex Board UNDERSTANDING RISK - 1 / Technical Assistance for Imp Supply of Equipment (10 sies Single Stage - One E IBRD / 85810 roved Disaster and Climate Post Request for Bids Open - National 409,459.00 322,847.00 Completed 2018-03-26 2017-02-17 2018-03-31 2018-05-12 2017-03-16 2018-06-11 2017-07-18 2018-07-16 2017-10-02 2019-01-12 2018-03-13 mometers + 25 Accelerograp nvelope Resilience hs + Microzonation software) UNDERSTANDING RISK - 8 / Technical Assistance for Imp IBRD / 85810 Post Direct Selection Direct 12,764.00 18,925.98 Completed 2017-11-30 2017-03-08 2017-12-05 2017-03-31 2018-01-09 2017-05-08 2018-07-08 2017-07-24 Supply and install fibreglass roved Disaster and Climate housing Resilience UNDERSTANDING RISK - 6 / Technical Assistance for Imp Request for Quota Single Stage - One E IBRD / 85810 Post Limited 10,000.00 10,956.35 Completed 2017-03-01 2017-02-24 2017-04-26 2017-04-17 2017-10-23 2020-01-04 Supply of Computer Digitizer roved Disaster and Climate tions nvelope Resilience UNDERSTANDING RISK - 10 / Technical Assistance for Imp Request for Quota Single Stage - One E IBRD / 85810 Post Limited 7,179.00 0.00 Canceled 2017-11-25 2018-01-20 2018-07-19 Supply & Installation of Pole roved Disaster and Climate tions nvelope Mounts Resilience RR - 11 / Equipping St. Bene Request for Quota Single Stage - One E dicts Primary - School furnitu IBRD / 85810 Risk Reduction Post Limited 10,000.00 0.00 Canceled 2020-10-10 2020-12-05 2021-06-03 tions nvelope re and administrative items UR - 25 / Training and Aware Technical Assistance for Imp ness - Rental and application IBRD / 85810 roved Disaster and Climate Post Direct Selection Direct 6,772.00 7,007.77 Completed 2020-12-14 2020-10-12 2020-12-28 2020-11-11 2021-02-08 2021-01-21 2021-04-09 2021-11-28 of 3 panel wraps of artworks Resilience unto a bus. UR - 27 / Procurement of go ods for Communications Cam Technical Assistance for Imp paign - one (1) Digital Billboa IBRD / 85810 roved Disaster and Climate Post Direct Selection Direct 16,400.00 27,085.85 Signed 2021-03-30 2021-03-18 2021-04-06 2021-03-31 2021-06-01 2021-05-31 2021-11-28 rd in Portmore, St. Catherine Resilience and one (1) Static Billboard i n Yallahs, St. Thomas RR - 8M - 2 / Procurement of Request for Quota Single Stage - One E IBRD / 85810 Risk Reduction Post Limited 34,200.00 23,497.85 Completed 2021-04-12 2021-05-25 2021-06-15 2021-11-19 2021-09-13 2022-01-27 Domestic Appliances tions nvelope UR - 26 / Procurement of go ods for Communications Cam paign - Static Super Billboard Technical Assistance for Imp including print production, fa IBRD / 85810 roved Disaster and Climate Post Direct Selection Direct 14,700.00 27,085.85 Completed 2021-03-29 2021-03-18 2021-04-12 2021-03-31 2021-05-31 2021-05-31 2021-07-30 2021-12-09 brication and installation of 3 Resilience 2'x10' board and one (1) yea r rental and The Fabrication and Installation of 2 billboard signs Islandwide UR - 28 / Procurement of go ods for Communications Cam Technical Assistance for Imp paign - Three (3) Digital Billb IBRD / 85810 roved Disaster and Climate Post Direct Selection Direct 26,000.00 27,085.85 Completed 2021-03-29 2021-03-18 2021-04-05 2021-03-31 2021-05-31 2021-05-29 2021-11-27 2022-02-22 oards signs Islandwide (Mand Resilience eville Square, Manchester ; M ontego Bay, St. James; Cross Roads, Kingston) RISK REDUCTION - 8 / Equip Single Stage - One E ping for Fire Stations (Furnitu IBRD / 85810 Risk Reduction Post Request for Bids Open - National 200,000.00 0.00 Canceled 2020-12-14 2020-12-19 2021-01-30 2021-03-01 2021-04-05 2021-10-02 nvelope re, Adminstrative items) UR - 35 & RR - 8M - 5 / Procu Technical Assistance for Imp Request for Quota Single Stage - One E rement of Software & License IBRD / 85810 roved Disaster and Climate Post Limited 82,800.00 11,075.19 Completed 2021-04-26 2021-05-25 2021-07-26 2021-12-22 2021-10-24 2022-04-03 tions nvelope s (incl. for Risk Atlas) for NRI Resilience P and JFB RR - 8M - 3, RR - 8M - 4 & UR Technical Assistance for Imp Single Stage - One E IBRD / 85810 Post Request for Bids Open - National 299,400.00 124,962.79 Completed 2021-04-12 2021-10-01 2021-04-26 2021-10-01 2021-05-24 2021-06-25 2021-07-05 2021-10-08 2021-08-02 2021-12-22 2021-10-31 2022-06-03 - 30 / Procurement of Furnitu roved Disaster and Climate nvelope re Resilience UR - 34, UR - 31 & RR - 8M - Technical Assistance for Imp 1 / Procurement of IT Equipm Single Stage - One E IBRD / 85810 roved Disaster and Climate Post Request for Bids Open - National 333,991.00 30,565.20 Completed 2021-04-26 2021-08-10 2021-05-10 2021-11-17 2021-06-07 2021-06-25 2021-07-26 2021-06-29 2021-08-30 2022-01-03 2021-12-28 2022-04-14 ent (incl. for Risk Atlas) for N nvelope Resilience RIP, Fire Stations and EarthQ uake Unit UR - 24 / Procurement of go ods for Communications cam Technical Assistance for Imp Request for Quota Single Stage - One E paign, social awareness, envi IBRD / 85810 roved Disaster and Climate Post Limited 88,000.00 0.00 Canceled 2021-04-10 2021-06-05 2021-12-02 tions nvelope ronmental development, DRR Resilience awareness and education pro gramme UR - 17 / Procurement of IT Technical Assistance for Imp Single Stage - One E IBRD / 85810 Post Request for Bids Open - National 255,000.00 0.00 Canceled 2021-04-05 2021-04-10 2021-05-22 2021-06-21 2021-07-26 2022-01-22 Equipment (incl. for Risk Atla roved Disaster and Climate nvelope s) Resilience UR – 35 - R1 / Procurement o Technical Assistance for Imp Single Stage - One E f Software & Licenses (incl. fo IBRD / 85810 roved Disaster and Climate Post Request for Bids Open - National 247,240.00 0.00 Canceled 2022-04-20 2022-05-10 2022-05-02 2022-06-13 2022-06-14 2022-08-01 2022-06-14 2022-09-05 2023-03-04 nvelope r Risk Atlas) for NRIP Resilience RR - 8M - 6 / Procurement of Request for Quota Single Stage - One E IBRD / 85810 Risk Reduction Post Open - National 90,000.00 0.00 Canceled 2022-06-13 2022-08-19 2022-11-30 Furniture tions nvelope RISK REDUCTION - 7 / Equip ping for Fire Brigade (Fire Fig IBRD / 85810 Risk Reduction Post Request for Bids 200,000.00 0.00 Canceled 2022-04-04 2022-04-09 2022-05-21 2022-06-20 2022-07-25 2023-01-21 hting & Rescue Equipment) UR - 32 / Procurement of Sur Technical Assistance for Imp vey equipment for Microzona IBRD / 85810 roved Disaster and Climate Post Request for Bids 269,105.00 0.00 Canceled 2022-07-18 2022-08-01 2022-09-05 2022-10-24 2022-11-28 2023-03-28 tion Studies Resilience UR - 37 / Power tools and ac Technical Assistance for Imp cessories for the EQU to facili Request for Quota Single Stage - One E IBRD / 85810 roved Disaster and Climate Post Open - National 5,000.00 0.00 Canceled 2022-09-26 2023-01-02 2023-07-01 tate microzonation training a tions nvelope Resilience nd execution of microzonatio n studies UR - 38 / Survey equipment f Technical Assistance for Imp or the EQU to facilitate micro Request for Quota Single Stage - One E IBRD / 85810 roved Disaster and Climate Post Open - National 60,000.00 0.00 Canceled 2022-09-26 2023-01-02 2023-07-01 zonation training and executi tions nvelope Resilience on of microzonation studies UR - 33 / Computer/IT equip Technical Assistance for Imp ment for the EQU to facilitate Request for Quota Single Stage - One E IBRD / 85810 roved Disaster and Climate Post Open - National 25,000.00 0.00 Signed 2022-09-26 2023-01-02 2023-04-06 2023-07-01 microzonation training and e tions nvelope Resilience xecution of microzonation st udies Page 2 UR - 34 - R1 / Procurement o Technical Assistance for Imp Single Stage - One E f IT Equipment (incl. for Risk IBRD / 85810 roved Disaster and Climate Post Request for Bids Open - National 88,897.00 0.00 Canceled 2022-04-13 2022-05-10 2022-04-27 2022-05-27 2022-06-08 2022-06-14 2022-07-27 2022-08-31 2022-12-29 nvelope Atlas) for NRIP Resilience UR - 39 / Seismic equipment (Servo Accelerometer Networ k Sensor AND Portable Ambie Technical Assistance for Imp Direct - Internation nt Vibration Monitoring Syste IBRD / 85810 roved Disaster and Climate Post Direct Selection 51,000.00 0.00 Signed 2022-10-31 2022-11-02 2022-11-28 2022-11-04 2023-03-10 2023-08-22 2023-09-06 al m) for the EQU to facilitate m Resilience icrozonation training and exe cution of microzonation studi es UR - 40 / Seismic equipment (Exploration Seismograph) fo Technical Assistance for Imp Direct - Internation r the EQU to facilitate microz IBRD / 85810 roved Disaster and Climate Post Direct Selection 55,000.00 0.00 Signed 2022-10-31 2022-11-02 2022-11-28 2022-11-04 2023-03-10 2023-08-21 2023-09-06 al onation training and executio Resilience n of microzonation studies UR - 34 / Seismic equipment (Geophysics resistivity meter Technical Assistance for Imp Direct - Internation ) for the EQU to facilitate mic IBRD / 85810 roved Disaster and Climate Post Direct Selection 54,000.00 0.00 Signed 2022-10-31 2022-11-02 2022-11-28 2022-11-04 2023-03-10 2023-11-02 2023-09-06 al rozonation training and exec Resilience ution of microzonation studie s UR - 43 / Procurement of Dro Technical Assistance for Imp Request for Quota Single Stage - One E IBRD / 85810 Post Limited 55,000.00 0.00 Canceled 2022-11-19 2023-01-28 2023-07-27 nes roved Disaster and Climate tions nvelope Resilience UR - 34 & 35 - R2 / Procurem Technical Assistance for Imp Request for Quota Single Stage - One E IBRD / 85810 Post Open - National 99,000.00 0.00 Signed 2022-12-19 2023-03-27 2023-06-06 2023-09-23 ent of IT Equipment and soft roved Disaster and Climate tions nvelope ware Resilience UR - 42 / Procurement of UP Technical Assistance for Imp Single Stage - One E IBRD / 85810 Post Request for Bids Open - National 140,000.00 0.00 Canceled 2022-12-14 2022-12-19 2023-01-18 2023-02-17 2023-03-24 2023-09-20 S roved Disaster and Climate nvelope Resilience UR - 41 / Procurement of Ent Technical Assistance for Imp Single Stage - One E IBRD / 85810 Post Request for Bids Open - National 128,000.00 0.00 Signed 2022-12-30 2023-01-17 2023-01-13 2023-02-12 2023-02-17 2023-04-02 2023-02-23 2023-05-07 2023-06-01 2023-09-04 erprise server system roved Disaster and Climate nvelope Resilience RR-8M-6-R1 / Procurement o Request for Quota Single Stage - One E f domestic furniture to be us IBRD / 85810 Risk Reduction Post Limited 68,000.00 0.00 Canceled 2023-01-09 2023-01-30 2023-03-06 2024-03-05 tions nvelope ed in the newly constructed f ire stations UR - 45 / Electrical and Gene Technical Assistance for Imp ral supplies for the EQU to fa Request for Quota Single Stage - One E IBRD / 85810 roved Disaster and Climate Post Open - National 5,000.00 0.00 Signed 2023-01-21 2023-04-29 2023-10-06 2023-10-26 cilitate microzonation trainin tions nvelope Resilience g and execution of microzon ation studies UR - 42 - M1 / Procurement o Technical Assistance for Imp Request for Quota Single Stage - One E IBRD / 85810 Post Limited 12,000.00 0.00 Signed 2023-01-17 2023-01-19 2023-03-21 2023-05-18 2023-09-17 f UPS roved Disaster and Climate tions nvelope Resilience UR - 38 - R1 / Procurement o Technical Assistance for Imp Request for Quota Single Stage - One E IBRD / 85810 Post Open - National 60,000.00 0.00 Signed 2023-01-21 2023-05-13 2023-10-06 2023-11-09 f Surveying Equipment. roved Disaster and Climate tions nvelope Resilience DVRP11/05/2023 / Procurem Technical Assistance for Imp ent of goods for Billboard sig IBRD / 85810 roved Disaster and Climate Post Direct Selection Direct - National 20,000.00 0.00 Signed 2023-05-28 2023-05-01 2023-06-02 2023-06-07 2023-07-07 2023-07-26 2024-01-03 n within the vicinity of the My Resilience ton Gully Drainage Improvem ent works JD003 / Procurement of IT Eq Technical Assistance for Imp Request for Quota Single Stage - One E Pending Impl uipment and software for net IBRD / 85810 roved Disaster and Climate Post Open - National 8,000.00 0.00 2023-07-14 2023-09-08 2024-03-06 tions nvelope ementation work access switches Resilience JD004 / Enterprise Firewall s Technical Assistance for Imp Request for Quota Single Stage - One E IBRD / 85810 Post Open - National 19,000.00 0.00 Canceled 2023-07-14 2023-09-08 2024-03-06 ystem for use and functionin roved Disaster and Climate tions nvelope g of NRIP. Resilience JD002 / Procurement of IT Eq Technical Assistance for Imp Under Imple IBRD / 85810 Post Direct Selection Direct - National 170,000.00 0.00 2023-07-09 2023-09-28 2023-07-14 2023-09-28 2023-08-18 2024-02-14 uipment and software roved Disaster and Climate mentation Resilience NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UNDERSTANDING RISK - 25 / Technical Assistance for Imp Training & Awareness (Works Single Stage - One E IBRD / 85810 roved Disaster and Climate Post Request for Bids Open - National 300,000.00 0.00 Canceled 2021-04-05 2021-04-10 2021-05-22 2021-06-21 2021-07-26 2022-01-22 hops, Promotional Materials, nvelope Resilience Displays, Communication too ls, Videos, etc JM-JSIF-46993-NC-RFQ / Soft Technical Assistance for Imp ware Training and materials f Request for Quota Single Stage - One E IBRD / 85810 roved Disaster and Climate Post Limited 25,000.00 0.00 Canceled 2021-04-10 2021-06-05 2021-12-02 or application to or use with tions nvelope Resilience seismic equipment. UNDERSTANDING RISK – 25- Technical Assistance for Imp 1 / The Fabrication and Instal Request for Quota Single Stage - One E IBRD / 85810 roved Disaster and Climate Post Limited 23,000.00 0.00 Canceled 2021-04-05 2021-06-14 2021-09-12 lation of 3 billboard signs Isla tions nvelope Resilience ndwide (St. Thomas, Kingsto n and St. Mary) RR - 23 / Provision of Water IBRD / 85810 Risk Reduction Post Direct Selection Direct 1,000.00 0.00 Canceled 2022-04-12 2022-04-26 2022-04-17 2022-04-28 2022-05-15 2022-06-14 and sewerage connections/S ervices RR - 24 / Provision of Electric IBRD / 85810 Risk Reduction Post Direct Selection Direct 16,000.00 0.00 Canceled 2022-04-12 2022-05-05 2022-04-17 2022-05-09 2022-05-15 2022-06-14 al connection UNDERSTANDING RISK -27 / Social Awareness and Enviro Technical Assistance for Imp Request for Quota Single Stage - One E nmental Development (social IBRD / 85810 roved Disaster and Climate Post Open - National 40,348.00 0.00 Canceled 2022-04-23 2022-06-18 2022-12-15 tions nvelope media boosting, social media Resilience management, tv/radio produ ction) PROJECT MANAGEMENT - 3 / Study Tours, Training, Meetin Request for Quota Single Stage - One E IBRD / 85810 Project Administration Post Limited 100,000.00 0.00 Canceled 2022-04-09 2022-06-04 2022-12-01 gs, Events - Venues, Travel, tions nvelope Accommodations, Training M aterials UNDERSTANDING RISK - 30 / Technical Assistance for Imp Training & Awareness – Place IBRD / 85810 roved Disaster and Climate Post Direct Selection Direct 2,000.00 0.00 Canceled 2022-07-04 2022-09-05 2022-11-07 2023-05-06 ment of On-Air (radio) Hurric Resilience ane Tips Page 3 UNDERSTANDING RISK - 22 / Training & Awareness (Works Technical Assistance for Imp Single Stage - One E hops, Promotional Materials, IBRD / 85810 roved Disaster and Climate Post Request for Bids Open - National 200,000.00 0.00 Canceled 2022-08-15 2022-08-20 2022-10-01 2022-10-31 2022-12-05 2023-06-03 nvelope Displays, Communication too Resilience ls, Videos, etc) Multiple contr acts RR - 27 / JPS to relocate conc rete light pole located in Bar IBRD / 85810 Risk Reduction Post Direct Selection Direct - National 10,000.00 0.00 Signed 2022-09-12 2022-08-29 2022-09-17 2022-09-08 2022-11-05 2022-11-01 2023-01-04 nett Street driveway of newly constructed Montego Bay fire station JD001 / Procurement of brok Technical Assistance for Imp Under Imple erage, transportation and log IBRD / 85810 roved Disaster and Climate Post Direct Selection Direct - National 8,500.00 0.00 2023-07-09 2023-08-22 2023-07-14 2023-08-22 2023-08-18 2024-02-14 mentation istics services Resilience CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RISK REDUCTION - 5 / Consul Least Cost Selecti tancy for Design & Supervisio IBRD / 85810 Risk Reduction Post Open - National 147,500.00 144,248.42 Completed 2017-03-16 2017-03-18 2017-04-06 2017-05-20 2017-05-10 2017-06-17 2017-06-02 2017-07-17 2017-06-19 2017-08-21 2017-06-26 2017-09-25 2017-08-12 2018-03-24 2017-08-12 on n Services for Yallahs Fire St ation RISK REDUCTION - 6 / Consul Least Cost Selecti tancy for Design & Supervisio IBRD / 85810 Risk Reduction Post Open - National 147,500.00 144,636.97 Completed 2017-03-16 2017-03-18 2017-04-06 2017-05-20 2017-05-10 2017-06-17 2017-06-02 2017-07-17 2017-06-13 2017-08-21 2017-06-26 2017-09-25 2017-08-15 2018-03-24 2017-08-15 on n Services for Port Maria Fire Station RISK REDUCTION - 4 / Consul Consultant Qualifi tancy for Design & Supervisio IBRD / 85810 Risk Reduction Post Open - National 165,000.00 181,733.33 Completed 2017-01-10 2016-11-20 2017-01-31 2017-03-16 2017-01-12 2017-04-15 2019-12-11 2017-05-20 2017-06-09 2017-11-16 2017-06-09 cation Selection n Services for Montego Bay F ire Station RISK REDUCTION - 16 / Cons Consultant Qualifi ultancy for Supervision Servi IBRD / 85810 Risk Reduction Post Open - National 100,000.00 0.00 Canceled 2018-03-05 2018-03-26 2018-05-09 2018-06-08 2018-07-13 2019-01-09 cation Selection ces (Big Pond/Myton Works) UNDERSTANDING RISK - 24 / Consulting Firm for Coastal A Technical Assistance for Imp ssessments & Preliminary De Quality And Cost- IBRD / 85810 roved Disaster and Climate Post Open - National 1,400,000.00 0.00 Canceled 2017-12-04 2017-12-25 2018-02-07 2018-03-07 2018-04-06 2018-08-05 2018-09-09 2019-09-09 signs - Phase I (Micro-zonatio Based Selection Resilience n & EBA for 6 Locations) & Ph ase II (Multi-hazard, Micro-zo nation & EBA for 2 Locations) RISK REDUCTION - 14 / Cons Consultant Qualifi ultancy for Supervision Servi IBRD / 85810 Risk Reduction Post Open - National 50,000.00 0.00 Canceled 2018-01-22 2018-02-12 2018-03-28 2018-04-27 2018-06-01 2018-11-28 cation Selection ces (Church Pen Works) UR - 21 / Procurement of Co nsulting Firm for Coastal Ass essments & Preliminary Desi Technical Assistance for Imp Quality And Cost- gns - EBA for Portland Cotta IBRD / 85810 roved Disaster and Climate Post Open - National 1,200,000.00 992,672.37 Completed 2018-10-01 2018-10-11 2018-10-22 2018-12-05 2018-10-06 2019-01-02 2018-11-22 2019-02-01 2018-12-13 2019-03-08 2019-01-30 2019-04-12 2019-10-15 2020-04-11 2019-10-15 Based Selection ge, Manchioneal, Ocho Rios, Resilience Morant Bay, Savanah-La-Mar & Black River and Multi-hazar d & EBA for Port Maria & Allig ator Pond UR - 23 / Procurement of Co nsulting Firm to develop and Technical Assistance for Imp Consultant Qualifi roll out communications cam IBRD / 85810 roved Disaster and Climate Post Open - National 112,000.00 92,502.49 Completed 2018-10-01 2018-09-27 2018-10-22 2018-12-05 2018-11-26 2019-01-04 2019-02-28 2019-02-08 2019-03-24 2019-08-07 2019-03-24 cation Selection paign and DRR awareness an Resilience d education programme UR - 16 / Procurement of Co Technical Assistance for Imp nsulting Firm for NRIP Devel Quality And Cost- Open - Internationa IBRD / 85810 roved Disaster and Climate Post 631,400.00 221,481.05 Completed 2019-11-18 2019-05-03 2019-12-09 2020-01-22 2019-05-09 2020-02-19 2019-06-19 2020-03-20 2019-07-12 2020-04-24 2019-09-30 2020-05-29 2019-12-18 2021-05-29 2019-12-18 opment (including RA), and T Based Selection l Resilience raining (NRIP & RA Usage, Co ordination) UR - 20 - 1 / Procurement of Consulting Firm to conduct M icro-zonation studies in 8 loc Technical Assistance for Imp Quality And Cost- Open - Internationa ations (i.e. Port Maria, Manch IBRD / 85810 roved Disaster and Climate Post 631,400.00 544,581.85 Terminated 2020-01-13 2020-01-02 2020-02-03 2020-01-02 2020-03-18 2020-03-18 2020-04-15 2020-04-23 2020-05-15 2020-02-08 2020-06-19 2020-04-23 2020-07-24 2020-12-26 2021-07-24 Based Selection l ioneal, Ocho Rios, Morant Ba Resilience y, Savanah-La-Mar , Black Ri ver, Alligator Pond & Portland Cottage) UR - 20 / Procurement of Co nsulting Firm to conduct Micr Technical Assistance for Imp o-zonation studies in 8 locati Consultant Qualifi IBRD / 85810 roved Disaster and Climate Post Open - National 200,000.00 0.00 Canceled 2018-10-01 2018-10-22 2018-12-05 2019-01-04 2019-02-08 2019-08-07 ons (i.e. Port Maria, Manchio cation Selection Resilience neal, Ocho Rios, Morant Bay, Savanah-La-Mar , Black River , Alligator Pond & Portland Co ttage) RR -16-1 / Design Review - B Consultant Qualifi IBRD / 85810 Risk Reduction Post Open - National 100,000.00 0.00 Canceled 2018-10-29 2018-11-19 2019-01-02 2019-02-01 2019-03-08 2019-09-04 ig Pond/Myton Gully & Myton cation Selection Bridge RR - 16 - 3 / Consultancy Ser Consultant Qualifi vices to Social Assessment re IBRD / 85810 Risk Reduction Post Open - National 65,000.00 94,573.36 Signed 2020-08-24 2020-09-14 2020-09-07 2020-09-28 2020-11-18 2020-10-05 2021-06-22 2020-10-19 2021-05-10 2021-04-17 2022-08-26 cation Selection Myton Gully Drainage Infrastr ucture project UR - 33 / Procurement for C Technical Assistance for Imp Quality And Cost- Open - Internationa Under Implement IBRD / 85810 Post 565,690.00 0.00 2021-04-12 2021-06-03 2021-05-03 2021-10-11 2021-06-14 2021-11-29 2021-07-12 2022-01-04 2021-08-11 2022-02-28 2021-11-23 2022-11-24 2022-01-18 2023-01-18 onsultancy services for Micro roved Disaster and Climate Based Selection l ation zonation Resilience UR - 36 / Procurement for a consultancy firm for the exec Technical Assistance for Imp Quality And Cost- ution of a 'Train the trainer' p IBRD / 85810 roved Disaster and Climate Post Open - National 230,000.00 0.00 Signed 2021-04-12 2021-06-01 2021-05-03 2021-11-24 2021-05-31 2021-09-01 2021-06-28 2021-09-01 2021-07-28 2021-09-21 2021-09-01 2022-08-17 2021-10-13 2022-12-28 2022-10-13 Based Selection rogramme on the customized Resilience 2018 edition of the Jamaica B uilding Code RR - 10 / Design & Supervisi Consultant Qualifi IBRD / 85810 Risk Reduction Post Open - National 50,000.00 0.00 Canceled 2021-04-04 2021-04-25 2021-06-08 2021-07-08 2021-08-12 2022-02-08 on of Works for St. Benedicts cation Selection Primary RR - 21 / Environmental Mon itoring (Testing - Water, Air, Least Cost Selecti IBRD / 85810 Risk Reduction Post Open - National 180,000.00 0.00 Canceled 2022-04-04 2022-04-25 2022-06-08 2022-07-06 2022-08-05 2022-09-09 2022-10-14 2023-04-12 Turbidity, Noise, ete) - Coast on al Works, Urban Drainage et al PROJECT MANAGEMENT - 5 / Consultant Qualifi Pending Impleme IBRD / 85810 Project Administration Post Open - National 271,046.00 0.00 2023-06-01 2023-06-22 2023-08-05 2023-10-05 2023-11-09 2024-05-07 Consultancy Firm for Impact cation Selection ntation Evaluation Page 4 RR - 28 / Consultant firm to provide supervision of works Consultant Qualifi IBRD / 85810 Risk Reduction Post Open - National 162,000.00 0.00 Canceled 2023-01-03 2023-01-15 2023-01-24 2023-03-16 2023-02-13 2023-04-20 2023-03-20 2023-05-25 2024-05-24 for the Big Pond/Myton Gully cation Selection Drainage Improvement Proje ct - Phase 1 JM-JSIF-402711-CS-CQS / Pro curement of consultancy ser Consultant Qualifi Pending Impleme IBRD / 85810 Project Administration Post Open - National 30,000.00 0.00 2024-01-19 2024-01-22 2024-02-09 2024-03-01 2024-04-01 2024-05-30 vices to evaluate the Disaste cation Selection ntation r Vulnerability Reduction Proj ect. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RISK REDUCTION - 18 / Cons ultancy for Coastal Design & IBRD / 85810 Risk Reduction Post Direct Selection Direct 150,000.00 166,130.65 Completed 2017-12-04 2017-10-13 2017-12-14 2018-01-11 2018-02-17 2018-03-28 2018-08-16 2022-04-28 Supervision Services (Design ). Supervision (optional - NW A) UNDERSTANDING RISK - 15 / Technical Assistance for Imp Project Coordination (for Nati Individual Consult IBRD / 85810 roved Disaster and Climate Post Open 100,000.00 28,844.12 Completed 2017-09-05 2017-09-05 2017-10-24 2017-11-09 2017-11-14 2017-11-29 2017-12-19 2017-12-15 2018-06-17 2018-06-11 onal Risk Information Platfor ant Selection Resilience m (NRIP), Risk Atlas (RA), Stu dies) (DRR Specialist) UNDERSTANDING RISK -28 / Technical Assistance for Imp IBRD / 85810 Post Direct Selection Direct 120,000.00 120,000.00 Signed 2019-11-01 2019-01-15 2019-11-11 2019-10-28 2020-01-15 2020-03-18 2020-07-13 Building Code Editing roved Disaster and Climate Resilience RR - 16 - 2 / Design Review - Individual Consult IBRD / 85810 Risk Reduction Post Limited 100,000.00 214,227.08 Completed 2020-01-13 2018-11-08 2020-01-18 2018-12-03 2020-02-08 2019-05-24 2020-03-14 2019-06-04 2020-09-10 2020-03-30 Big Pond/Myton Gully & Myto ant Selection n Bridge RR - 16 - 4 / Consultancy for Engineering Services (Big Po IBRD / 85810 Risk Reduction Post Direct Selection Direct 75,000.00 84,036.84 Signed 2021-03-29 2021-03-29 2021-04-17 2021-06-15 2021-06-07 2021-07-06 2021-12-04 nd/Myton Works) UNDERSTANDING RISK - 13 / Technical Assistance for Imp Researcher in Seismology - S Individual Consult IBRD / 85810 roved Disaster and Climate Post Open 35,907.00 0.00 Canceled 2021-04-05 2021-05-24 2021-06-14 2021-07-19 2022-01-15 tipend, Per diem, Accommod ant Selection Resilience ations, Travel & Research Co sts RR - 26 / Annotto Bay Coast al Protection - Consultant to IBRD / 85810 Risk Reduction Post Direct Selection Direct - National 64,516.00 0.00 Signed 2022-09-28 2022-11-03 2022-10-24 2022-11-03 2023-01-20 2023-03-24 2023-07-19 do design review and update Page 5