PROCUREMENT PLAN (Textual Part) Project information: Greater Accra Resilient Integrated Development (GARID) Project- [P-164330] Project Implementation agency: Ministry of Works and Housing Date of the Procurement Plan: March 28, 2018 Period covered by this Procurement Plan: January to December, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [Ghana Public Procurement Act 663, amended with Act 914 ], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. a. Open advertising of the procurement opportunity at the national level; b. The procurement is open to eligible firms from any country; c. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. Contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. Publication of contract award information; f. Rights for the Bank to review procurement documentation and activities; g. An effective complaints mechanism; and h. Maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. N/A Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables N/A Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables]; Works: is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. . PROCUREMENT Ghana : Greater Accra Resilient and Integrated Development Project PLAN General Information Country: Ghana 2018-04-10 Bank’s Approval Date of the Original Procurement Plan: 2024-01-11 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164330 GPN Date: Project Name: Greater Accra Resilient and Integrated Development Project Loan / Credit No: IDA / V1450, IDA / 64100 Ministry of Works and Housing Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GH-MWH-96706-CW-RFQ / R Component 4: Project Mana Request for Quota Single Stage - One E 2019-06-0 IDA / V1450 Post Open - National 30,545.92 0.00 Canceled 2019-02-10 2019-04-07 ehabilitation of Project Office gement tions nvelope 6 (PCU) GH-MWH-96639-CW-RFB / C Component 1: Climate Resil onstruction of Detention Pon Open - Internationa Single Stage - Two E 22,860,000.0 2023-04-2 IDA / V1450 ient Drainage and Flood Miti Prior Request for Bids 0.00 Canceled 2020-11-25 2020-11-30 2021-01-11 2021-03-26 2021-04-30 ds, Sand Traps, and Urgent R l nvelope 0 0 gation Measures epairs Networks in Odaw Dra inage Basin. GH-MWH-145711-CW-RFQ / Component 4: Project Mana Request for Quota Single Stage - One E 2020-07-2 IDA / V1450 Post Limited 14,700.00 16,749.88 Completed 2019-12-05 2019-11-27 2020-01-30 2020-02-09 Paving of PCU car park gement tions nvelope 8 GH-MWH-145710-CW-RFQ / I Component 4: Project Mana Request for Quota Single Stage - One E 2020-11-2 nstallation and Networking of IDA / V1450 Post Limited 21,000.00 0.00 Canceled 2020-04-04 2020-05-30 gement tions nvelope 6 PCU Offices GH-MWH-96698-CW-RFB / Dr Component 1: Climate Resil Request for Propo Open - Internationa 25,000,000.0 2025-05-2 edging of Odaw River Main C IDA / V1450 ient Drainage and Flood Miti Prior Multi Stage 0.00 Canceled 2020-08-31 2020-11-16 2020-11-16 2020-09-05 2021-01-25 2021-05-09 2021-06-13 sals l 0 3 hannel and Selected Tributari gation Measures es and Clearing GH-MWH-96703-CW-RFB / R Component 1: Climate Resil Single Stage - One E 2022-12-1 econstruction of three(3) Brid IDA / V1450 ient Drainage and Flood Miti Prior Request for Bids Open - National 7,800,000.00 0.00 Canceled 2020-12-28 2021-01-02 2021-02-13 2021-03-15 2021-04-19 nvelope 0 ges, Demolishing of two(2) F gation Measures oot Bridges GH-MWH-103675-CW-RFP / Component 1: Climate Resil Request for Quota Single Stage - One E 2019-05-2 Rehabilitation of Project Offic IDA / V1450 ient Drainage and Flood Miti Post Limited 80,000.00 0.00 Canceled 2019-03-30 2019-04-26 tions nvelope 6 e (PCU). gation Measures GH-MWH-96642-CW-RFB / C Component 1: Climate Resil onstruction of Detention pon Single Stage - One E 2022-10-2 IDA / V1450 ient Drainage and Flood Miti Prior Request for Bids Open - National 7,600,000.00 0.00 Canceled 2021-01-27 2021-02-01 2021-03-03 2021-04-02 2021-05-07 ds at Atomic East (Off-line) a nvelope 9 gation Measures nd Atomic West (in-line) GH-MWH-181877-CW-RFQ / Component 4: Project Mana Request for Quota Single Stage - One E 2021-01-1 Extension works to PCU Offic IDA / 64100 Post Limited 180,000.00 170,136.03 Completed 2020-08-22 2020-08-21 2020-10-17 2020-12-10 gement tions nvelope 5 es at PWD Head Office GH-MWH-207506-CW-RFP / Component 1: Climate Resil Request for Propo Open - Internationa Single Stage - Two E 27,000,000.0 14,245,722. 2025-07-0 Dredging of Odaw River Main IDA / 64100 ient Drainage and Flood Miti Prior Signed 2020-12-22 2021-03-09 2021-03-09 2021-09-08 2021-03-09 2021-11-23 2020-12-27 2021-04-08 2021-05-18 2022-01-14 2021-09-04 2022-09-17 sals l nvelope 0 80 5 Channel and Selected Tributa gation Measures ries and Clearing GH-MWH-219654-CW-RFB / Request for Bids - Component 1: Climate Resil Procurement of a contractor f Single Stage - One E Works (without pr 2022-07-1 IDA / 64100 ient Drainage and Flood Miti Post Request for Bids Open - National 300,000.00 0.00 Canceled 2021-09-30 2021-10-05 2021-11-16 2021-12-16 2022-01-20 or the improvement of Acces nvelope equalification) SP 9 gation Measures s to the Final Disposal site at D Amuman GH-MWH-171491-CW-RFB / Request for Bids - Component 1: Climate Resil Procurement of a contractor t Single Stage - One E Works (without pr 2022-05-2 IDA / 64100 ient Drainage and Flood Miti Post Request for Bids Open - National 2,160,000.00 0.00 Canceled 2021-09-30 2021-10-05 2021-10-26 2021-11-09 2021-11-30 o evacuate dredged material nvelope equalification) SP 9 gation Measures s from Site B to Anyaa Site D GH-MWH-240300-CW-RFQ / Component 1: Climate Resil Request for Quota Request for Quota Single Stage - One E 2021-11-1 Protection Measures for GAE IDA / 64100 ient Drainage and Flood Miti Post Limited tions (Non Bank-S 198,000.00 99,923.56 Signed 2021-08-25 2021-09-01 2021-10-18 2021-11-17 tions nvelope 7 C Lands for the detention po gation Measures PD) nds GH-MWH-219664-CW-RFB / Request for Bids - Component 1: Climate Resil Construction of Offline and In Single Stage - One E Small Works SPD 2024-02-1 IDA / 64100 ient Drainage and Flood Miti Prior Request for Bids Open - National 7,600,000.00 0.00 Canceled 2022-04-14 2022-04-19 2022-05-31 2022-06-30 2022-08-04 -line Detention Ponds at Ato nvelope (1 envelope proce 5 gation Measures mic East and Atomic West. ss) GH-MWH-286156-CW-DIR / R Request for Quota elocation of water supply pip Component 1: Climate Resil tions - Small Work 2022-12-0 elines and valves in propose IDA / 64100 ient Drainage and Flood Miti Post Direct Selection Direct - National s (Emergency) SP 611,900.00 0.00 Signed 2022-09-30 2022-09-28 2022-10-05 2022-09-29 2022-11-09 2022-12-01 9 d drainage crossing on the A gation Measures D -Non Competiti yikai Street at Kaneshie. ve Request for Bids - GH-MWH-219669-CW-RFB / Component 1: Climate Resil Single Stage - One E Works (without pr 12,409,515.0 2023-08-1 Drainage Improvement Work IDA / 64100 ient Drainage and Flood Miti Prior Request for Bids Open - National 0.00 Signed 2022-10-14 2022-11-04 2022-10-19 2022-11-14 2022-11-30 2022-12-20 2022-12-30 2023-04-03 2023-02-03 2023-07-15 nvelope equalification) SP 0 2 s to Odaw Channel at Achimo gation Measures D ta GH-MWH-317015-CW-DIR / R elocation of cables and ancill Component 1: Climate Resil Request for Quota 2022-12-0 ary facilities of Telecommuni IDA / 64100 ient Drainage and Flood Miti Post Direct Selection Direct - National tions (Non Bank-S 118,100.00 0.00 Signed 2022-09-26 2022-09-28 2022-10-01 2022-10-06 2022-11-05 2022-12-01 5 cation Agencies in proposed gation Measures PD) drainage crossing on the Ayi kai Street at Kaneshie Request for Bids - GH-MWH-286147-CW-RFB / I Component 1: Climate Resil Open - Internationa Single Stage - One E Works (without pr 17,008,315.0 2023-03-1 mprovement Works at Nima IDA / 64100 ient Drainage and Flood Miti Prior Request for Bids 0.00 Signed 2022-05-25 2023-01-27 2022-05-30 2023-02-14 2022-07-11 2023-04-17 2022-08-10 2023-07-13 2022-09-14 2023-09-16 l nvelope equalification) SP 0 8 Drain gation Measures D GH-MWH-240302-CW-RFQ / I Component 1: Climate Resil Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-10-2 mprovement of access to fin IDA / 64100 ient Drainage and Flood Miti Post Open - National tions (Non Bank-S 198,000.00 0.00 2023-05-30 2023-07-25 tions nvelope lementation 3 al disposal site at Anyaa and gation Measures PD) Pokuase Request for Bids - GH-MWH-286153-CW-RFB / I Component 1: Climate Resil Open - Internationa Single Stage - One E Works (without pr 25,764,840.0 Under Imple 2025-04-2 mprovement Works at Kanes IDA / 64100 ient Drainage and Flood Miti Prior Request for Bids 0.00 2023-06-30 2023-08-15 2023-07-05 2023-08-18 2023-08-16 2023-10-03 2023-09-15 2023-10-20 l nvelope equalification) SP 0 mentation 2 hie Drain and Channel gation Measures D GH-MWH-341758-CW-RFQ / Renovation of 4 Regional Offi Component 1: Climate Resil Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-11-2 ces of Ghana Hydrological Au IDA / 64100 ient Drainage and Flood Miti Post Open - National tions (Non Bank-S 70,000.00 0.00 2023-07-03 2023-08-28 tions nvelope lementation 6 thority in Ashanti Region, Nor gation Measures PD) thern Region, Upper East Reg ion and Volta Region. Page 1 Request for Bids - GH-MWH-362732-CW-RFB / Component 1: Climate Resil Single Stage - One E Small Works SPD Pending Imp 2024-02-1 Construction of Accra FEWS IDA / 64100 ient Drainage and Flood Miti Post Request for Bids Open - National 300,000.00 0.00 2023-06-23 2023-06-28 2023-08-09 2023-09-08 2023-10-13 nvelope (1 envelope proce lementation 0 Center at Ghana Hydrological gation Measures ss) Authority. GH-MWH-369762-CW-RFQ / Thrust Boring for Relocation Component 1: Climate Resil Request for Quota Request for Quota Single Stage - One E 2023-10-0 of Water Supply Pipelines an IDA / 64100 ient Drainage and Flood Miti Post Limited tions (Non Bank-S 35,000.00 0.00 Signed 2023-07-17 2023-09-04 2023-09-11 2023-10-23 tions nvelope 2 d Valves in Proposed Drainag gation Measures PD) e Crossing on the Ayikai Stre et at Kaneshie GH-MWH-392244-CW-RFQ / Component 1: Climate Resil Request for Quota Request for Quota Single Stage - One E Pending Imp 2024-03-2 Construction of Chain Link Fe IDA / 64100 ient Drainage and Flood Miti Post Limited tions (Non Bank-S 19,000.00 0.00 2023-11-27 2024-01-29 tions nvelope lementation 9 ncing for Hydromet Equipme gation Measures PD) nt. GH-MWH-341763-CW-RFQ / Renovation and refurbish of Component 1: Climate Resil Request for Quota Ghana Hydrological Authority Request for Quota Single Stage - One E Pending Imp 2024-04-2 IDA / 64100 ient Drainage and Flood Miti Post Open - National tions (Non Bank-S 75,000.00 0.00 2023-12-02 2024-01-27 Head Office, comprising rewi tions nvelope lementation 6 gation Measures PD) ring, changing defective door s, airconditioning and paintin g. GH-MWH-395964-CW-RFQ / Component 1: Climate Resil Request for Quota Aerial Relocation of Optic Fib Request for Quota Single Stage - One E Pending Imp 2024-08-0 IDA / 64100 ient Drainage and Flood Miti Post Limited tions (Non Bank-S 51,000.00 0.00 2023-12-16 2024-02-10 re Infrastructure for AT, CSqu tions nvelope lementation 8 gation Measures PD) ared and Vodafone at Ayikai Street. Request for Bids - GH-MWH-286154-CW-RFB / Component 1: Climate Resil Open - Internationa Single Stage - One E Works (without pr 16,000,000.0 Pending Imp 2025-04-0 Reconstruction of Bridge at D IDA / 64100 ient Drainage and Flood Miti Prior Request for Bids 0.00 2024-03-20 2024-03-25 2024-05-06 2024-06-05 2024-07-10 l nvelope equalification) SP 0 lementation 6 ome Road gation Measures D Request for Bids - GH-MWH-286146-CW-RFB / Component 1: Climate Resil Open - Internationa Single Stage - One E Works (without pr 20,335,548.0 Pending Imp 2026-01-2 Construction of Atomic West IDA / 64100 ient Drainage and Flood Miti Prior Request for Bids 0.00 2024-03-29 2024-04-03 2024-05-15 2024-06-14 2024-07-19 l nvelope equalification) SP 0 lementation 0 Detention Pond gation Measures D Request for Bids - GH-MWH-286144-CW-RFB / Component 1: Climate Resil Open - Internationa Single Stage - One E Works (without pr 22,117,448.0 Pending Imp 2026-01-2 Construction of Atomic East IDA / 64100 ient Drainage and Flood Miti Prior Request for Bids 0.00 2024-04-01 2024-04-06 2024-05-18 2024-06-17 2024-07-22 l nvelope equalification) SP 0 lementation 3 Detention Pond gation Measures D Request for Bids - GH-MWH-219660-CW-RFB / I Component 1: Climate Resil Single Stage - One E Works (without pr 10,911,558.0 Pending Imp 2025-07-1 mprovement Works at Alajo IDA / 64100 ient Drainage and Flood Miti Prior Request for Bids Open - National 0.00 2024-03-25 2024-03-30 2024-05-11 2024-06-10 2024-07-15 nvelope equalification) SP 0 lementation 5 Drain gation Measures D Request for Bids - GH-MWH-219663-CW-RFB / Component 1: Climate Resil Single Stage - One E Small Works SPD Pending Imp 2025-07-0 Reconstruction of Abbosey O IDA / 64100 ient Drainage and Flood Miti Prior Request for Bids Open - National 8,411,170.00 0.00 2024-03-15 2024-03-20 2024-05-01 2024-05-31 2024-07-05 nvelope (1 envelope proce lementation 5 kai Bridge gation Measures ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MWH-56616-GO-RFQ / Pr Component 1: Climate Resil ocurement of 3No Executive Request for Quota Single Stage - One E IDA / V1450 ient Drainage and Flood Miti Prior Limited 10,000.00 0.00 Canceled 2018-04-12 2018-06-07 2018-12-04 L' shape Tables, 3No Office tions nvelope gation Measures Desk, 5No Executive Chairs. GH-MWH-56618-GO-RFB / Pr Component 1: Climate Resil Single Stage - One E ocurement of 5No, Saloon V IDA / V1450 ient Drainage and Flood Miti Prior Request for Bids Open - National 200,000.00 0.00 Canceled 2018-04-10 2018-04-15 2018-05-27 2018-06-26 2018-07-31 2019-01-27 nvelope ehicles gation Measures GH-MWH-56619-GO-RFQ / Pr ocurement of 3No Desktop C Component 1: Climate Resil omputers and Accessories, 2 Request for Quota Single Stage - One E IDA / V1450 ient Drainage and Flood Miti Prior Limited 20,000.00 0.00 Canceled 2018-04-14 2018-06-09 2018-12-06 0No Laptop Computers, 5No tions nvelope gation Measures Printers, 5No Scanners, 1No Photocopiers, 5No Digital Ca meras, 2No Projectors. GH-MWH-56620-GO-RFQ / Pr Component 1: Climate Resil Request for Quota Single Stage - One E ocurement Of Equipment For IDA / V1450 ient Drainage and Flood Miti Prior Limited 70,000.00 0.00 Canceled 2018-04-18 2018-06-13 2018-12-10 tions nvelope Improving Monitoring gation Measures GH-MWH-96537-GO-RFB / Pr Component 1: Climate Resil ocurement of Vehicles (6 No, Single Stage - One E IDA / V1450 ient Drainage and Flood Miti Post Request for Bids Open - National 319,215.00 0.00 Canceled 2019-03-04 2019-04-08 2019-03-09 2019-04-20 2019-05-20 2019-06-24 2019-12-21 s Double Cabin Pick- up , 1 N nvelope gation Measures o. Salon Car and 1 No. Motor Bike) GH-MWH-103671-GO-RFB / P Component 1: Climate Resil rocurement of Vehicles (6 No Request for Quota Single Stage - One E IDA / V1450 ient Drainage and Flood Miti Post Limited 320,000.00 0.00 Canceled 2019-03-30 2019-04-26 2019-05-26 s Double Cabin Pick-Up, 1No. tions nvelope gation Measures Saloon and 1No. Motto Bike. GH-MWH-96524-GO-RFB / Pr Component 1: Climate Resil Single Stage - One E ocurement of light imaging, IDA / V1450 ient Drainage and Flood Miti Post Request for Bids Open - National 800,000.00 0.00 Canceled 2019-09-02 2019-09-07 2019-10-19 2019-11-18 2019-12-23 2020-01-22 nvelope Detection and Ranging ( LIDA gation Measures R/DEM) GH-MWH-137038-GO-RFQ / Procurement of 1 No Double Component 4: Project Mana Request for Quota Single Stage - One E IDA / V1450 Post Limited 290,000.00 272,709.36 Completed 2019-11-29 2019-11-27 2020-01-24 2020-04-03 2020-02-28 2020-05-11 Cabin Pick- up and 4 No Medi gement tions nvelope um Cross country vehicles fo r PCU GH-MWH-137042-GO-RFQ / Procurement of Office Furnitu re for PCU comprising 9 No. Component 4: Project Mana Request for Quota Single Stage - One E Desks, 4 No. Steel wide cabin IDA / V1450 Post Limited 36,000.00 16,924.54 Completed 2019-11-29 2019-11-27 2020-01-24 2020-02-07 2020-02-28 2020-02-19 gement tions nvelope ets for Arch Files, 8 No. Medi um Steel cabinets with drawe rs, 1 No. workstation, woode n bookshelves, 18No. Visitors chairs GH-MWH-137050-GO-RFQ / Procurement of Computers a nd Accessories comprising 6 Component 4: Project Mana Request for Quota Single Stage - One E No. Laptop Computers and a IDA / V1450 Post Limited 43,000.00 57,098.75 Completed 2019-11-25 2019-11-27 2020-01-20 2020-04-03 2020-02-28 2020-06-12 gement tions nvelope ccessories, 2No. Desktop co mputers, 2 No. Photocopiers, 3 No. Scanners, 3 No printers , 1No. Project with screen Page 2 GH-MWH-137043-GO-RFQ / Procurement of Office equip ment comprising 9 sets of St Component 4: Project Mana Request for Quota Single Stage - One E aple machines, Perforator, Fil IDA / V1450 Post Limited 7,800.00 3,018.34 Completed 2019-11-29 2019-11-27 2020-01-24 2020-02-07 2020-02-28 2020-02-19 gement tions nvelope ing trays, Filing trays, waste bins, 3No paper shredders, 1 No. Comb binding machine, 1 No cash safe, 3No. Small size fridges. GH-MWH-161187-GO-RFQ / Procurement of Survey Equip Component 1: Climate Resil Request for Quota Single Stage - One E ment for the Supervision of d IDA / 64100 ient Drainage and Flood Miti Post Open - National 135,000.00 0.00 Canceled 2020-07-20 2020-09-14 2020-12-13 tions nvelope redging Works by Hydrologic gation Measures al Services Department (HSD ) GH-MWH-161017-GO-RFQ / Component 1: Climate Resil Request for Quota Single Stage - One E Procurement of Office Furnitu IDA / 64100 ient Drainage and Flood Miti Post Limited 8,000.00 0.00 Canceled 2020-06-30 2020-08-25 2020-09-24 tions nvelope re for 5 contract staff Recruit gation Measures ed for GARID PIUs GH-MWH-178464-GO-RFQ / Procurement of 4Nos. Double Component 1: Climate Resil Request for Quota Single Stage - One E Cabin Pick Ups for the Project IDA / 64100 ient Drainage and Flood Miti Post Limited 180,000.00 178,996.99 Completed 2020-08-01 2020-07-07 2020-09-19 2020-10-21 2020-12-18 2020-12-25 tions nvelope Implementation Units for the gation Measures four Ministries-MWH,MSWR,M LGRD,MIZD) GH-MWH-161013-GO-RFQ / Procurement of Office Equip Component 1: Climate Resil ment (2 No. Laptop, 1 No. He Request for Quota Single Stage - One E IDA / 64100 ient Drainage and Flood Miti Post Limited 4,500.00 7,439.18 Completed 2020-08-01 2020-11-06 2020-09-12 2020-09-21 2020-11-11 2020-09-29 avy Duty Photocopier Machin tions nvelope gation Measures es, 1 No. Heavy Duty Colour Printer and Accessories, 2 No s Cabinet,) GH-MWH-161016-GO-RFQ / Procurement of Stationery a nd Consumables (100 boxes Component 1: Climate Resil A4 Papers, 10No. Staplers, 2 Request for Quota Single Stage - One E IDA / 64100 ient Drainage and Flood Miti Post Limited 10,000.00 8,946.22 Completed 2020-08-14 2020-11-17 2020-10-09 2020-09-07 2020-11-08 2020-09-09 0 Pkt Paper Clips, 3No. Calcul tions nvelope gation Measures ators, 1No. Electronic Binding Machine, 10 Cabinets, 1No. E lectronic Perforator, 1No. Ma nual Perforator), 5 No, File tr ays etc GH-MWH-204957-GO-RFB / P rocurement of Survey Equip Component 1: Climate Resil Single Stage - One E ment and Drone for Supervisi IDA / 64100 ient Drainage and Flood Miti Post Request for Bids Open - National 158,000.00 169,087.38 Completed 2020-11-30 2020-12-21 2020-12-05 2020-12-21 2021-01-16 2021-01-29 2021-02-15 2021-02-04 2021-03-22 2021-07-19 2021-09-18 2021-10-11 nvelope on of Dredging Works by Hyd gation Measures rological Services Departmen t (HSD) GH-MWH-187078-GO-RFQ / Component 1: Climate Resil Procurement of Automatic W Request for Quota Single Stage - One E IDA / 64100 ient Drainage and Flood Miti Post Limited 100,000.00 83,790.94 Terminated 2020-12-05 2020-11-23 2021-01-30 2021-03-17 2021-07-29 eather Stations and Meteorol tions nvelope gation Measures ogical Equipment for GMet GH-MWH-204958-GO-RFQ / Component 1: Climate Resil Procurement of Information, Request for Quota Single Stage - One E IDA / 64100 ient Drainage and Flood Miti Post Limited 15,000.00 3,400.73 Completed 2020-12-05 2020-12-24 2021-01-30 2021-03-15 2021-07-29 2021-05-30 Education and Communicatio tions nvelope gation Measures n Materials in 2 Lots GH-MWH-204962-GO-RFQ / Component 1: Climate Resil Procurement and Installation Request for Quota Single Stage - One E IDA / 64100 ient Drainage and Flood Miti Post Limited 100,000.00 92,968.82 Terminated 2020-12-05 2020-11-23 2021-01-30 2021-03-16 2021-07-29 of Hydromet Equipment for H tions nvelope gation Measures ydrological Services Departm ent GH-MWH-187061-GO-RFQ / Procurement of Computers, p Component 4: Project Mana Request for Quota Single Stage - One E IDA / 64100 Post Limited 35,000.00 37,274.90 Completed 2020-12-05 2020-11-23 2021-01-30 2021-01-10 2021-04-30 2021-02-04 rinters and accessories for ad gement tions nvelope ditional project Specialists for PIUs. GH-MWH-219686-GO-RFQ / Component 1: Climate Resil Request for Quota Single Stage - One E Procurement of 2Nos. double IDA / 64100 ient Drainage and Flood Miti Post Limited 100,000.00 100,275.86 Completed 2021-05-14 2021-03-30 2021-06-25 2021-07-09 2021-08-24 2021-09-10 tions nvelope Cabin Pick ups for Monitoring gation Measures of Fews Network GH-MWH-219700-GO-RFQ / Procurement of 11 No. Lapto p Computers (3 No.-HSD,1N o.-WRC, 4No.-MWH and 3No.- Component 1: Climate Resil Request for Quota Single Stage - One E PCU), 3No. Desktop Compute IDA / 64100 ient Drainage and Flood Miti Post Limited 69,000.00 50,748.26 Completed 2021-09-08 2021-08-20 2021-10-18 2021-11-25 2021-11-17 2021-12-05 tions nvelope rs and Accessories, 5No. Prin gation Measures ters (All-in 1), 2No. Heavy Du ty Photocopier Machine, 4No. Heavy duty Shredder, 2No Di gital Cameras for MWH- PIU GH-MWH-247696-GO-RFQ / Component 4: Project Mana Request for Quota Single Stage - One E Procurement of office curtain IDA / 64100 Post Limited 5,000.00 3,254.61 Completed 2021-09-01 2021-09-09 2021-10-27 2021-10-15 2021-11-26 2021-11-09 gement tions nvelope s and furnishing for PCU Offic e Extension GH-MWH-264352-GO-RFB / P rocurement and Installation o f Hydromet Equipment for Hy Component 1: Climate Resil Single Stage - One E drological Services Departme IDA / 64100 ient Drainage and Flood Miti Post Request for Bids Open - National 230,000.00 0.00 Signed 2022-01-14 2022-02-01 2022-01-19 2022-02-15 2022-03-02 2022-03-03 2022-04-01 2022-07-18 2022-05-06 2022-10-21 2022-07-05 nvelope nt gation Measures and Automatic Weather Stati ons and Meteorological Equip ment for GMet GH-MWH-283492-GO-RFQ / Component 1: Climate Resil Request for Quota Single Stage - One E Procurement of a video Conf IDA / 64100 ient Drainage and Flood Miti Post Limited 4,200.00 4,076.38 Completed 2022-04-09 2022-05-12 2022-06-04 2022-06-17 2022-07-19 2022-06-26 tions nvelope erencing facility for MWH Co gation Measures nference room GH-MWH-283493-GO-RFQ / Procurement of 3 No. vehicle Component 1: Climate Resil s for Project Implementation Request for Quota Single Stage - One E IDA / 64100 ient Drainage and Flood Miti Post Limited 200,000.00 188,115.17 Signed 2022-04-09 2022-05-09 2022-06-04 2022-09-02 2022-09-02 Monitoring (1No. Cross Count tions nvelope gation Measures ry for PIU-Lead MWH, 1No. Pi ckup vehicle for MWH PIU an d 1No. Pickup vehicle for HS D) GH-MWH-283496-GO-RFB / P Component 1: Climate Resil Single Stage - One E rocurement of 1 No. X-Band IDA / 64100 ient Drainage and Flood Miti Post Request for Bids Open - National 1,250,000.00 0.00 Signed 2022-04-05 2022-09-08 2022-04-10 2022-09-13 2022-05-22 2022-10-11 2022-06-21 2022-10-25 2022-07-26 2022-12-24 2022-10-24 nvelope Radar and hydromet equipm gation Measures ent GH-MWH-283498-GO-RFB / P Component 1: Climate Resil rocurement of 4No. compute Single Stage - One E Under Imple IDA / 64100 ient Drainage and Flood Miti Post Request for Bids Open - National 211,780.00 0.00 2022-10-20 2022-10-05 2022-10-25 2022-10-06 2022-12-06 2022-10-31 2023-01-05 2023-03-24 2023-02-09 2023-04-10 rs and 4No. Servers and a da nvelope mentation gation Measures ta storage for implementatio n of FEWS Page 3 GH-MWH-317011-GO-RFQ / Procurement of 1No. Steel ca Component 4: Project Mana Request for Quota Single Stage - One E IDA / 64100 Post Limited 6,000.00 0.00 Signed 2022-10-15 2022-10-11 2022-12-10 2022-10-31 2023-01-09 binet, 1No. paper Shredder a gement tions nvelope nd 1No. Stainless hot water d ispenser GH-MWH-341511-GO-RFQ / Component 1: Climate Resil Request for Quota Single Stage - One E Procurement of 1No. Motorbi IDA / 64100 ient Drainage and Flood Miti Post Limited 5,000.00 0.00 Completed 2023-03-15 2023-03-08 2023-05-10 2023-04-14 2023-07-09 2023-04-07 tions nvelope ke for MWH. gation Measures GH-MWH-341752-GO-RFQ / Component 1: Climate Resil Request for Quota Single Stage - One E Procurement of 1 Unit Doubl IDA / 64100 ient Drainage and Flood Miti Post Limited 54,000.00 0.00 Completed 2023-03-20 2023-03-08 2023-05-15 2023-05-30 2023-08-13 2023-06-06 tions nvelope e Cabin Pickup for FEWS Mon gation Measures itoring GH-MWH-341520-GO-RFQ / Component 1: Climate Resil Procurement of Conference R Request for Quota Single Stage - One E IDA / 64100 ient Drainage and Flood Miti Post Open - National 90,000.00 0.00 Signed 2023-07-01 2023-07-07 2023-08-26 2023-10-18 2023-11-24 oom Tables and Chairs for M tions nvelope gation Measures WH and Ghana Hydrological Authority Head Office. GH-MWH-317008-GO-RFQ / Procurement of 6 laptops, all- Component 4: Project Mana Request for Quota Single Stage - One E IDA / 64100 Post Limited 51,000.00 0.00 Signed 2023-06-07 2022-12-12 2023-08-02 2023-03-15 2023-09-16 in-one desktop, workstation a gement tions nvelope nd high-computer set-up ser ver and accessories GH-MWH-336740-GO-RFB / P rocurement and Installation o Component 1: Climate Resil Single Stage - One E Under Imple f X-Band Radar and Automati IDA / 64100 ient Drainage and Flood Miti Prior Request for Bids Open - National 2,200,000.00 0.00 2023-06-07 2023-07-09 2023-06-12 2023-07-10 2023-07-24 2023-08-14 2023-08-23 2023-09-27 2024-03-05 nvelope mentation c Weather Stations for Ghana gation Measures Meteorological Agency. GH-MWH-341737-GO-RFQ / Procurement of Office Equip ment comprising 5No. All-in- One Printers, 5No. Shredders Component 1: Climate Resil Request for Quota Single Stage - One E , 5No. Cabinets, 40 No. All-In- IDA / 64100 ient Drainage and Flood Miti Post Open - National 80,000.00 0.00 Completed 2023-05-15 2023-07-07 2023-07-10 2023-09-04 2023-09-08 2023-11-14 tions nvelope One Desktop Computers, 30 gation Measures No, UPS, 13No. Laptops, 1No. Heavy Duty photocopier, 1No .Scanner and 3No. Coloured Printers for HSD.. GH-MWH-341749-GO-RFQ / Procurement and Installation Component 1: Climate Resil Request for Quota Single Stage - One E of CCTV Camera, Access Con IDA / 64100 ient Drainage and Flood Miti Post Open - National 15,000.00 0.00 Completed 2023-07-04 2023-07-07 2023-08-29 2023-09-18 2023-10-28 tions nvelope trol System at Head Office of gation Measures Ghana Hydrological Authority GH-MWH-341519-GO-RFQ / Component 1: Climate Resil Procurement and Installation Request for Quota Single Stage - One E IDA / 64100 ient Drainage and Flood Miti Post Open - National 40,000.00 0.00 Completed 2023-07-05 2023-07-07 2023-08-30 2023-09-04 2023-11-28 of Power Generator Set for G tions nvelope gation Measures hana Hydrological Authority Head of Office, Accra. GH-MWH-341518-GO-RFQ / Component 1: Climate Resil Request for Quota Single Stage - One E Procurement and Installation IDA / 64100 ient Drainage and Flood Miti Post Limited 10,000.00 0.00 Completed 2023-05-30 2023-06-16 2023-07-25 2023-08-15 2023-09-23 2023-08-19 tions nvelope of Video Conferencing Faciliti gation Measures es and Screen. GH-MWH-341513-GO-RFQ / Component 1: Climate Resil Printing of the Ghana Hydrol Request for Quota Single Stage - One E Pending Impl IDA / 64100 ient Drainage and Flood Miti Post Limited 18,000.00 0.00 2023-07-15 2023-09-09 2023-11-08 ogical Authority Brouchures, tions nvelope ementation gation Measures flyers, Memos, Letter Heads, SBCC Materials. GH-MWH-363367-GO-RFQ / Procurement of Branded Shir Component 4: Project Mana Request for Quota Single Stage - One E Under Imple IDA / 64100 Post Open - National 95,000.00 0.00 2023-06-25 2023-08-20 2023-10-04 ts, Baseball Caps and Reflecti gement tions nvelope mentation ve Vests for SBCC activities GH-MWH-363373-GO-RFQ / Procurement of various Offic Component 4: Project Mana Request for Quota Single Stage - One E Under Imple IDA / 64100 Post Open - National 40,000.00 0.00 2023-06-25 2023-08-20 2023-09-19 e Equipment, Kitchenette Ap gement tions nvelope mentation pliances and 5No. Swivel Cha irs in 4 lots GH-MWH-363397-GO-RFQ / Component 4: Project Mana Request for Quota Single Stage - One E Under Imple IDA / 64100 Post Limited 6,000.00 0.00 2023-06-25 2023-08-11 2023-08-20 2023-10-04 Procurement of 1No. 125cc M gement tions nvelope mentation otorcycle GH-MWH-363499-GO-RFQ / Component 4: Project Mana Request for Quota Single Stage - One E Procurement of Conference S IDA / 64100 Post Limited 7,000.00 0.00 Completed 2023-06-25 2023-07-10 2023-08-20 2023-08-03 2023-09-19 gement tions nvelope mart Tv Screen for PCU Conf erence Room GH-MWH-392217-GO-RFQ / Procurement and installation Component 4: Project Mana Request for Quota Single Stage - One E Under Imple of Cabinet Rack, Port Switche IDA / 64100 Post Limited 6,000.00 0.00 2023-11-29 2023-12-06 2024-01-31 2024-02-21 gement tions nvelope mentation s and SSD Drives for Network Data Storage for PCU. GH-MWH-341507-GO-RFQ / Component 1: Climate Resil Request for Quota Single Stage - One E Pending Impl Procurement and Installation IDA / 64100 ient Drainage and Flood Miti Post Open - National 50,000.00 0.00 2023-12-02 2024-01-27 2024-04-26 tions nvelope ementation of Server for Ghana Hydrolog gation Measures ical Authority. GH-MWH-341515-GO-RFQ / Component 1: Climate Resil Request for Quota Single Stage - One E Pending Impl Procurement and Installation IDA / 64100 ient Drainage and Flood Miti Post Limited 15,000.00 0.00 2023-11-29 2024-01-31 2024-05-30 tions nvelope ementation of 3No. Automatic Flow Monit gation Measures oring Stations. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MWH-122693-NC-RFB / Mapping of the Odaw Draina Component 1: Climate Resil ge Basin using Light Imaging Single Stage - One E IDA / V1450 ient Drainage and Flood Miti Post Request for Bids Open - National 800,000.00 1,591,627.00 Signed 2019-07-30 2019-08-20 2019-08-04 2019-11-27 2019-09-15 2020-01-06 2019-10-15 2020-05-06 2019-11-19 2020-09-06 2020-07-16 Detection and Ranging (LiDA nvelope gation Measures R/DEM) technology and prod uction of digital colour orthop hoto maps GH-MWH-124174-NC-RFP / D evelopment, Implementation, operation and Hand-over of F Component 1: Climate Resil Request for Propo Open - Internationa Single Stage - Two E lood Early Warning Response IDA / V1450 ient Drainage and Flood Miti Prior 6,000,000.00 0.00 Canceled 2021-01-20 2021-01-25 2021-03-08 2021-05-21 2021-06-25 2023-12-12 sals l nvelope System (FEWS) Accra, includi gation Measures ng procurement and installati on of equipment and training . Page 4 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MWH-56565-CS-CQS / Co Component 1: Climate Resil nsultancy services for the stu Consultant Qualifi IDA / V1450 ient Drainage and Flood Miti Prior Limited 100,000.00 0.00 Canceled 2018-04-20 2018-08-30 2018-05-04 2018-06-03 2018-07-08 2019-01-04 dy to identify sustainable opt cation Selection gation Measures ion for disposing dredged ma terials GH-MWH-56568-CS-CQS / Co Component 2: Solid Waste nsultancy Service for Feasibil Consultant Qualifi IDA / V1450 Management Capacity Impro Prior Open - National 300,000.00 0.00 Canceled 2018-04-17 2018-05-08 2018-06-21 2018-07-21 2018-08-25 2019-02-21 ity and Design Studies for De cation Selection vements signing Integrated Solid Wast e Management GH-MWH-56573-CS-CQS / Co Component 2: Solid Waste Consultant Qualifi nsultancy Service for detaile IDA / V1450 Management Capacity Impro Prior Open - National 200,000.00 0.00 Canceled 2018-04-12 2018-08-23 2018-05-03 2018-06-16 2018-07-16 2018-08-20 2019-02-16 cation Selection d Engineering Design of Tran vements sfer Stations. GH-MWH-66198-CS-CQS / Co Component 2: Solid Waste nsultancy Services for Enviro Consultant Qualifi IDA / V1450 Management Capacity Impro Prior Limited 60,000.00 0.00 Canceled 2018-06-11 2018-06-19 2018-06-21 2018-06-23 2018-07-15 2018-08-03 2018-11-01 nmental and Social Impact A cation Selection vements ssessment(ESIA) for Capping GH-MWH-56589-CS-CQS / Co Component 3: Participatory nsultancy Services For Procu Upgrading of Targeted Flood Consultant Qualifi IDA / V1450 Prior Limited 100,000.00 0.00 Canceled 2018-04-16 2018-04-30 2018-05-30 2018-07-04 2018-12-31 rement on Community Liaiso Prone Low-income Communi cation Selection ns ties and Local Government S upport GH-MWH-80965-CS-CQS / Co Component 2: Solid Waste nsultancy Services to Improvi Consultant Qualifi IDA / V1450 Management Capacity Impro Post Open - National 150,000.00 149,272.04 Signed 2018-10-08 2019-07-25 2018-10-29 2019-08-30 2018-12-12 2019-10-29 2018-12-19 2020-02-10 2019-01-02 2021-09-30 2019-07-01 ng Waste Management in Lo cation Selection vements w Income Communities. GH-MWH-56593-CS-CQS / Co nsultancy Service for Prepara Component 4: Project Mana Consultant Qualifi IDA / V1450 Prior Open - National 500,000.00 0.00 Canceled 2018-04-13 2018-05-31 2018-05-04 2018-06-17 2018-07-17 2018-08-21 2019-02-17 tion of ESIA, RAP, ESMF and gement cation Selection RPF and Socioeconomic Asse ssment and Survey GH-MWH-56611-CS-CQS / Co Component 4: Project Mana Consultant Qualifi nsultancy Service for Project IDA / V1450 Post Limited 30,000.00 33,000.00 Signed 2018-04-23 2018-05-07 2019-05-22 2018-06-06 2019-07-05 2018-07-11 2019-08-03 2019-01-07 gement cation Selection Implementation Manual. GH-MWH-56561-CS-CQS / Co nsultancy Service for prepara tory studies for improving flo Component 1: Climate Resil Consultant Qualifi od, drain, wetland and retent IDA / V1450 ient Drainage and Flood Miti Post Limited 100,000.00 0.00 Canceled 2018-04-12 2018-04-26 2018-05-26 2018-06-30 2018-12-27 cation Selection ion basins management, incl gation Measures uding land ownership, enforc ement, operation and mantia nance GH-MWH-56601-CS-CQS / Co Component 4: Project Mana Consultant Qualifi nsultant Service to Publish, P IDA / V1450 Post Limited 30,000.00 0.00 Canceled 2018-04-10 2018-04-24 2018-05-24 2018-06-28 2018-12-25 gement cation Selection rint and Disseminate the rep ort. GH-MWH-56622-CS-CQS / Co nsultancy Service to Conduct Component 4: Project Mana Consultant Qualifi IDA / V1450 Post Limited 10,000.00 0.00 Canceled 2018-04-17 2018-05-01 2018-05-31 2018-07-05 2019-01-01 a Sensitization and Readines gement cation Selection s Assessment Study within th e Project Area GH-MWH-56595-CS-CQS / Co Component 4: Project Mana Consultant Qualifi nsultancy Service for finalizat IDA / V1450 Post Limited 10,000.00 0.00 Canceled 2018-04-25 2018-05-09 2018-06-08 2018-07-13 2019-01-09 gement cation Selection ion of the Metropolitan Study Report GH-MWH-96509-CS-INDV / C onsultancy Services for Envir Component 1: Climate Resil Consultant Qualifi onmental, Social Impact Asse IDA / V1450 ient Drainage and Flood Miti Post Open - National 220,000.00 250,000.00 Signed 2019-09-02 2019-08-20 2019-09-23 2019-10-25 2019-11-06 2019-11-27 2019-12-06 2020-12-22 2020-01-10 2020-08-06 2020-07-08 cation Selection ssment(ESIA) for Detention P gation Measures onds, Urgent Repairs and Bri dges GH-MWH-103660-CS-CQS / C Component 1: Climate Resil Consultant Qualifi onsultancy Services - Supervi IDA / V1450 ient Drainage and Flood Miti Post Open - National 300,000.00 0.00 Canceled 2019-05-08 2019-05-29 2019-07-12 2019-08-11 2019-09-15 2019-10-15 cation Selection sion of FEWS- Accra. gation Measures GH-MWH-56592-CS-CQS / Co Component 3: Participatory nsultancy Services For Rapid Upgrading of Targeted Flood Consultant Qualifi IDA / V1450 Post Open - National 100,000.00 0.00 Canceled 2018-04-19 2018-05-10 2018-06-23 2018-07-23 2018-08-27 2019-02-23 Assessment on Housing and Prone Low-income Communi cation Selection Resettlement Options ties and Local Government S upport GH-MWH-56579-CS-CQS / Co Component 3: Participatory nsultancy Service for Land O Upgrading of Targeted Flood Consultant Qualifi IDA / V1450 Post Open - National 100,000.00 0.00 Canceled 2018-10-26 2018-10-26 2018-10-26 2018-10-26 2018-10-26 2018-10-26 wnership Mapping and Acces Prone Low-income Communi cation Selection s to Land Study ties and Local Government S upport GH-MWH-56581-CS-CQS / Co Component 3: Participatory nsultancy Service for Commu Upgrading of Targeted Flood Consultant Qualifi IDA / V1450 Prior Open - National 200,000.00 0.00 Canceled 2018-04-26 2018-10-01 2018-05-17 2018-06-30 2018-07-21 2018-08-18 2019-02-14 nity Profiling and Enumeratio Prone Low-income Communi cation Selection n ties and Local Government S upport GH-MWH-123092-CS-QCBS / Consulting Services for Prepa Component 3: Participatory ration of Community Facilitat Upgrading of Targeted Flood Quality And Cost- Open - Internationa ion, Planning, Preliminary an IDA / V1450 Prone Low-income Communi Prior 1,400,000.00 1,147,718.75 Signed 2019-10-15 2020-01-29 2019-11-05 2020-02-04 2019-12-19 2020-12-19 2020-01-16 2021-02-12 2020-02-15 2021-03-09 2020-03-21 2021-05-08 2020-04-25 2021-06-10 2021-03-06 Based Selection l d Detailed Engineering Desig ties and Local Government S n and Construction Supervisi upport on and Contract Managemen t for 3 Communities GH-MWH-145641-CS-QCBS / Consultancy Service for Detai Component 1: Climate Resil Quality And Cost- Open - Internationa led Engineering Design for D IDA / V1450 ient Drainage and Flood Miti Prior 2,600,000.00 1,875,104.19 Signed 2019-11-20 2019-12-18 2019-12-11 2019-12-20 2020-01-24 2020-03-19 2020-02-21 2020-06-03 2020-03-22 2021-02-12 2020-04-26 2021-02-22 2020-05-31 2021-04-14 2022-05-31 Based Selection l etention Ponds, Bridge Recon gation Measures struction and Urgent Repairs. GH-MWH-145730-CS-LCS / C onsulting Services for the pre Component 4: Project Mana Least Cost Selecti IDA / V1450 Post Open - National 35,000.00 29,800.00 Completed 2019-12-05 2020-03-25 2019-12-26 2020-02-08 2020-06-04 2020-03-07 2020-07-20 2020-04-06 2020-09-02 2020-05-11 2020-10-27 2020-06-15 2021-01-13 2020-12-12 2022-03-23 paration of Online Grievance gement on s Redress Mechanism GH-MWH-145703-CS-CQS / Component 4: Project Mana Consultant Qualifi Development of Website and IDA / V1450 Post Open - National 15,000.00 18,020.87 Completed 2019-11-25 2019-12-16 2019-12-16 2020-01-29 2020-03-24 2020-02-28 2020-06-10 2020-04-03 2020-07-13 2020-09-30 2021-03-04 gement cation Selection hosting for GARID Project Page 5 GH-MWH-56465-CS-QCBS / Consultancy Service for Detai Component 1: Climate Resil Quality And Cost- Open - Internationa led Engineering Design for D IDA / V1450 ient Drainage and Flood Miti Prior 2,600,000.00 0.00 Canceled 2019-09-02 2019-05-15 2019-09-23 2019-11-06 2019-12-04 2020-01-03 2020-02-07 2020-03-13 2021-03-13 Based Selection l etention Ponds, Bridge Recon gation Measures struction and Urgent Repairs . GH-MWH-56586-CS-CQS / Co Component 3: Participatory nsultancy Service for Strateg Upgrading of Targeted Flood Consultant Qualifi IDA / V1450 Post Open - National 100,000.00 0.00 Canceled 2020-04-15 2020-05-06 2020-06-19 2020-07-19 2020-08-23 2021-02-19 y on Livelihoods Restoration Prone Low-income Communi cation Selection and Enhancement ties and Local Government S upport GH-MWH-145638-CS-QCBS / Design and Supervision of Fl Component 1: Climate Resil ood Early Warning Response Quality And Cost- Open - Internationa IDA / V1450 ient Drainage and Flood Miti Prior 800,000.00 254,212.88 Signed 2019-11-29 2019-12-04 2019-12-20 2019-12-10 2020-02-02 2021-01-28 2020-03-01 2021-01-03 2020-03-31 2021-01-28 2020-05-05 2021-01-29 2020-06-09 2021-02-15 2023-01-30 System (FEWS) Accra, includi Based Selection l gation Measures ng the development of CONO PS for HSD, GMet and NADM O GH-MWH-123083-CS-QCBS / Design and Supervision of Fl Component 1: Climate Resil ood Early Warning Response Quality And Cost- Open - Internationa IDA / V1450 ient Drainage and Flood Miti Prior 800,000.00 0.00 Canceled 2019-07-30 2019-09-06 2019-08-20 2019-10-03 2019-10-31 2019-11-30 2020-01-04 2020-02-08 2022-09-30 System (FEWS) Accra, includi Based Selection l gation Measures ng the development of CONO PS for HSD, GMet and NADM O GH-MWH-148850-CS-LCS / P Component 2: Solid Waste Quality And Cost- Open - Internationa rocurement of a Transaction IDA / V1450 Management Capacity Impro Post 370,000.00 0.00 Canceled 2020-01-30 2020-02-20 2020-04-04 2020-05-02 2020-06-01 2020-07-06 2020-08-10 2021-08-10 Based Selection l Advisor for PPP for Landfill Sit vements e GH-MWH-145704-CS-QCBS / Component 2: Solid Waste Consultancy Service for Studi Quality And Cost- IDA / V1450 Management Capacity Impro Post Open - National 200,000.00 0.00 Canceled 2019-12-10 2019-12-31 2020-02-13 2020-03-12 2020-04-11 2020-05-16 2020-06-20 2021-06-20 es and PreliminaryDesign for Based Selection vements Solid Waste Management to wards PPP GH-MWH-145732-CS-LCS / C Component 3: Participatory onsulting Services for the De Upgrading of Targeted Flood Least Cost Selecti IDA / V1450 Post Open - National 110,000.00 0.00 Canceled 2019-11-30 2019-12-21 2020-02-03 2020-03-02 2020-04-01 2020-05-06 2020-06-10 2021-01-06 velopment of a Geospatial As Prone Low-income Communi on set Management System for ties and Local Government S the MMDAs. upport GH-MWH-160874-CS-LCS / P reparation of Gender-Based Component 1: Climate Resil Quality And Cost- Violence Services Mapping a IDA / 64100 ient Drainage and Flood Miti Post Open - National 200,000.00 107,059.90 Completed 2020-04-10 2020-04-25 2020-05-01 2020-06-22 2020-06-14 2020-08-10 2020-07-04 2020-09-10 2020-07-25 2020-09-29 2020-08-22 2021-01-10 2020-09-12 2021-04-01 2021-01-10 2021-10-24 Based Selection nd Gender-Based Violence Tr gation Measures aining of Project Stakeholder s GH-MWH-160863-CS-LCS / C onsulting Service for the Prep Component 1: Climate Resil Least Cost Selecti aration of Resettlement Actio IDA / 64100 ient Drainage and Flood Miti Post Open - National 150,000.00 168,927.30 Signed 2020-05-05 2020-09-10 2020-05-26 2020-11-05 2020-07-09 2021-01-05 2020-07-30 2021-06-02 2020-08-19 2021-02-11 2020-09-16 2021-04-28 2020-10-21 2021-09-28 2021-02-18 on n Plan for Deferred and Routi gation Measures ne Maintenance Dredging Od aw Drainage Basin GH-MWH-160872-CS-LCS / C onsulting Service for the Eng agement of a Non-Governme ntal Organisation for Stakeho Component 1: Climate Resil Least Cost Selecti lder and Community Engage IDA / 64100 ient Drainage and Flood Miti Post Open - National 150,000.00 0.00 Canceled 2020-05-05 2020-05-22 2020-05-26 2020-07-09 2020-07-23 2020-08-06 2020-09-10 2020-10-01 2021-03-30 on ment for the Deferred and Ro gation Measures utine Maintenance Dredging Odaw Drainage Basin, Constr uction of Detention Ponds, Sa nd Traps, Reconstruction of b ridges GH-MWH-177995-CS-LCS / C onsultancy Services for Prep Component 1: Climate Resil aration of Environmental, So Least Cost Selecti IDA / 64100 ient Drainage and Flood Miti Post Open - National 100,000.00 0.00 Canceled 2020-08-25 2020-09-14 2020-09-15 2020-10-29 2020-11-12 2020-11-26 2020-12-31 2021-01-28 2021-07-27 cial Impact Assessment (ESIA on gation Measures )/ Resettlement Action Plan f or final disposal of dredge m aterial- Amuman GH-MWH-160860-CS-LCS / C onsulting Service for the Prep aration of Resettlement Actio Component 1: Climate Resil Least Cost Selecti n Plan for the construction of IDA / 64100 ient Drainage and Flood Miti Post Open - National 150,000.00 77,462.69 Signed 2020-08-20 2020-08-11 2020-09-10 2020-11-05 2020-10-24 2021-01-05 2020-11-14 2021-06-02 2020-12-04 2021-02-11 2021-01-01 2021-04-28 2021-01-25 2021-09-28 2021-05-25 on Sand Traps, Detention Ponds, gation Measures Reconstruction of 3 bridges and Repairs of the Odaw Drai nage Channel GH-MWH-145708-CS-QCBS / Component 2: Solid Waste Consultancy Service for Desi Quality And Cost- IDA / V1450 Management Capacity Impro Post Open - National 150,000.00 0.00 Canceled 2019-11-20 2020-01-06 2019-12-11 2020-01-24 2020-02-21 2020-03-22 2020-04-26 2020-05-31 2021-05-31 gn and construction supervisi Based Selection vements on for Capping of Dumpsites. GH-MWH-204954-CS-CQS / Component 1: Climate Resil Consultant Qualifi Monthly Topographic and Bat IDA / 64100 ient Drainage and Flood Miti Post Open - National 168,000.00 178,399.83 Signed 2020-11-30 2020-12-08 2020-12-21 2020-12-28 2021-02-03 2021-04-30 2021-03-05 2021-06-10 2021-04-09 2021-08-27 2022-01-13 cation Selection hymetric Survey of the Odaw gation Measures River GH-MWH-96501-CS-QCBS / Consultancy Services for Sup Component 1: Climate Resil Quality And Cost- Open - Internationa ervision of Works for Detenti IDA / V1450 ient Drainage and Flood Miti Prior 4,000,000.00 0.00 Canceled 2020-12-15 2021-01-05 2021-02-18 2021-03-18 2021-04-17 2021-05-22 2021-06-26 2022-06-26 Based Selection l on Ponds, Dredging and urg gation Measures ent repairs of drainage netwo rk and bridges. GH-MWH-171486-CS-QCBS / Consultancy Services for Pre paration of Environmental, S Component 1: Climate Resil Quality And Cost- ocial Impact Assessment (ESI IDA / 64100 ient Drainage and Flood Miti Post Open - National 140,000.00 0.00 Canceled 2020-06-05 2020-09-14 2020-06-26 2020-07-30 2020-08-27 2020-09-17 2020-10-15 2020-11-05 2021-03-05 Based Selection A) for Proposed Handling Site gation Measures and disposal of dredge mater ial- Agbobgloshie and Anyaa) GH-MWH-211351-CS-CQS / C onsultancy Services for Prep Component 1: Climate Resil Consultant Qualifi aration of Environmental, So IDA / 64100 ient Drainage and Flood Miti Post Open - National 70,000.00 0.00 Canceled 2021-01-20 2021-01-19 2021-02-10 2021-03-11 2021-03-18 2021-04-08 2021-10-05 cation Selection cial Impact Assessment (ESIA gation Measures ) for Proposed disposal of dre dge material at Anyaa GH-MWH-229995-CS-CQS / C onsulting Services for the Pre Component 4: Project Mana Consultant Qualifi paration and Implementation IDA / 64100 Post Open - National 300,000.00 367,160.11 Signed 2021-04-30 2021-04-27 2021-05-21 2021-05-06 2021-07-04 2021-07-29 2021-08-03 2022-01-13 2021-09-07 2022-01-25 2023-03-19 gement cation Selection of Behaviour Change Commu nication Strategy for GARID P roject Page 6 GH-MWH-240096-CS-CQS / C onsulting Services for Enviro nmental and Social Manage Component 1: Climate Resil ment Plan (ESMP) of Propose Consultant Qualifi IDA / 64100 ient Drainage and Flood Miti Post Open - National 100,000.00 87,147.85 Signed 2021-07-23 2021-09-29 2021-08-13 2021-10-07 2021-09-26 2021-11-17 2021-10-26 2022-03-25 2021-11-30 2022-04-19 2022-03-10 d Handling and Transportatio cation Selection gation Measures n of Dredged Material from L avender Hill, Odawna, Korlen a and Pasico Sites to Final Di sposal Sites in the Greater Ac cra Region GH-MWH-207514-CS-CQS / C onsultancy Services for Prep aration of Environmental, So Component 1: Climate Resil cial Impact Assessment (ESIA Consultant Qualifi IDA / 64100 ient Drainage and Flood Miti Post Open - National 140,000.00 0.00 Canceled 2021-08-20 2021-09-19 2021-10-13 2021-10-23 2021-11-13 2022-05-22 ) for removal, transportation cation Selection gation Measures and disposal of legacy dredg ed materials at Korle Bu and Lavenda Hill to Final Disposal sites at Anyaa and Pokuase. GH-MWH-283495-CS-QCBS / Selection of a Service Provid Component 1: Climate Resil er to Develop, Implementatio Quality And Cost- Open - Internationa Under Implement IDA / 64100 ient Drainage and Flood Miti Prior 1,500,000.00 0.00 2022-05-18 2022-06-27 2022-06-08 2022-08-02 2022-07-22 2023-04-05 2022-08-19 2023-02-06 2022-09-18 2023-04-16 2022-10-23 2022-11-27 2024-11-16 n, operation and Hand-over o Based Selection l ation gation Measures f Flood Early Warning Respon se System (FEWS) Accra, incl uding training GH-MWH-334367-CS-LCS / S Component 4: Project Mana Least Cost Selecti Under Implement election of External Auditors IDA / 64100 Post Open - National 60,000.00 0.00 2023-01-10 2023-01-06 2023-01-31 2023-03-16 2023-04-03 2023-04-13 2023-05-03 2023-05-13 2023-07-12 2023-06-17 2023-09-12 2023-07-22 2026-07-21 gement on ation for the GARID Project GH-MWH-351443-CS-CQS / Component 1: Climate Resil Organise National Flood Foru Consultant Qualifi IDA / 64100 ient Drainage and Flood Miti Post Open - National 30,000.00 0.00 Under Review 2023-07-03 2024-01-03 2023-07-24 2023-09-06 2023-10-06 2023-11-10 2024-02-08 m and Launch Social & Beha cation Selection gation Measures vioral Change Campaign. GH-MWH-369761-CS-QCBS / Construction Supervision and Component 1: Climate Resil Quality And Cost- Open - Internationa Under Implement Contract Management for De IDA / 64100 ient Drainage and Flood Miti Post 980,000.00 0.00 2023-07-10 2023-08-08 2023-07-31 2023-08-10 2023-09-13 2023-12-27 2023-10-11 2023-11-10 2023-12-15 2024-01-19 2026-04-18 Based Selection l ation tention Ponds, Bridge Recons gation Measures truction and Drainage Works. GH-MWH-341471-CS-CQS / C onsulting Services for Strateg Component 1: Climate Resil Consultant Qualifi ic Partner for Support in fundi IDA / 64100 ient Drainage and Flood Miti Post Open - National 40,000.00 0.00 Canceled 2023-06-26 2023-11-03 2023-07-17 2023-08-30 2023-09-29 2023-11-03 2024-02-01 cation Selection ng applications including trai gation Measures ning Staff in funding applicati ons. GH-MWH-341475-CS-CQS / C Component 1: Climate Resil apacity Building for Hydro St Consultant Qualifi IDA / 64100 ient Drainage and Flood Miti Post Open - National 40,000.00 0.00 Canceled 2023-06-29 2023-11-03 2023-07-20 2023-09-02 2023-10-02 2023-11-06 2024-02-04 aff including Development of cation Selection gation Measures Scheme of Service. GH-MWH-401067-CS-QCBS / Component 1: Climate Resil Capacity Building for Hydro S Quality And Cost- Pending Impleme IDA / 64100 ient Drainage and Flood Miti Post Open - National 40,000.00 0.00 2024-01-24 2024-02-14 2024-03-29 2024-04-26 2024-05-26 2024-06-30 2024-08-04 2025-01-31 taff including Development o Based Selection ntation gation Measures f Scheme of Service. GH-MWH-401070-CS-QCBS / Consulting Services for cond ucting financial and operatio Component 1: Climate Resil Quality And Cost- nal gap analysis, design of fi IDA / 64100 ient Drainage and Flood Miti Post Open - National 40,000.00 0.00 Under Review 2024-01-24 2024-01-05 2024-02-14 2024-03-29 2024-04-26 2024-05-26 2024-06-30 2024-08-04 2025-08-04 Based Selection nancial strategy and piloting gation Measures including identification of pot ential funding partners, prep aration of proposal and staff training. GH-MWH-401274-CS-CQS / C onsultancy services for comp Component 1: Climate Resil Consultant Qualifi Pending Impleme rehensive gap analyses and s IDA / 64100 ient Drainage and Flood Miti Post Open - National 30,000.00 0.00 2024-01-25 2024-02-15 2024-03-30 2024-04-29 2024-06-03 2024-11-30 cation Selection ntation coping of existing legal fram gation Measures ework in relation to flood risk management. GH-MWH-401278-CS-CQS / C Component 1: Climate Resil onsultancy Services for Revie Consultant Qualifi Pending Impleme IDA / 64100 ient Drainage and Flood Miti Post Open - National 40,000.00 0.00 2024-01-29 2024-02-19 2024-04-03 2024-05-03 2024-06-07 2024-10-05 w and Updating of Drainage cation Selection ntation gation Measures Standards including Nature B ased Solutions. GH-MWH-341472-CS-CQS / C Component 1: Climate Resil onsulting Services for develo Consultant Qualifi IDA / 64100 ient Drainage and Flood Miti Post Open - National 30,000.00 0.00 Canceled 2023-06-29 2023-11-03 2023-07-20 2023-09-02 2023-10-02 2023-11-06 2024-01-15 ping Regulations including St cation Selection gation Measures orm Water Regulations. GH-MWH-341468-CS-CQS / C Component 1: Climate Resil onsultancy Services for Revie Consultant Qualifi IDA / 64100 ient Drainage and Flood Miti Post Open - National 40,000.00 0.00 Canceled 2023-06-27 2023-10-27 2023-07-18 2023-08-31 2023-09-30 2023-11-04 2024-02-02 w and Updating of Drainage cation Selection gation Measures Standards including Nature B ased Solutions. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MWH-56604-CS-INDV / P Component 1: Climate Resil Individual Consult rocurement of Project Coordi IDA / V1450 ient Drainage and Flood Miti Prior Limited 76,000.00 2,783.28 Signed 2018-04-11 2018-04-13 2018-04-16 2018-04-11 2018-05-07 2018-05-08 2018-06-11 2018-05-24 2018-12-08 ant Selection nator. gation Measures GH-MWH-59168-CS-INDV / C Component 2: Solid Waste onsultancy Service for enviro Individual Consult IDA / V1450 Management Capacity Impro Prior Limited 45,000.00 0.00 Canceled 2018-04-16 2018-04-21 2018-04-27 2018-05-12 2018-11-08 nmental and social impact as ant Selection vements sessment (ESIA) for waste tra nsfer station GH-MWH-60059-CS-CQS / Pr Component 1: Climate Resil Individual Consult ocurement of an Environmen IDA / V1450 ient Drainage and Flood Miti Prior Open 84,000.00 1,671.64 Signed 2018-05-21 2018-08-30 2018-07-09 2018-10-16 2018-07-30 2019-04-25 2018-08-27 2019-03-04 2018-11-05 ant Selection tald Safeguard specialist gation Measures GH-MWH-60064-CS-CQS / Pr Component 1: Climate Resil Individual Consult ocurement of Financial Mana IDA / V1450 ient Drainage and Flood Miti Prior Open 96,000.00 2,173.13 Signed 2018-05-21 2018-10-16 2018-07-09 2019-05-10 2018-07-30 2019-07-15 2018-08-27 2019-08-13 2018-11-05 ant Selection gement Specialist gation Measures GH-MWH-63174-CS-INDV / P Component 1: Climate Resil Individual Consult rocurement of a Social Safeg IDA / V1450 ient Drainage and Flood Miti Prior Open 84,000.00 2,079.60 Signed 2018-05-21 2018-08-30 2018-07-09 2018-09-18 2018-07-30 2019-05-29 2018-08-27 2019-06-18 2018-11-05 ant Selection uard Specialist gation Measures Page 7 GH-MWH-65243-CS-INDV / C Component 2: Solid Waste onsultancy Services for the E Individual Consult IDA / V1450 Management Capacity Impro Prior Limited 35,000.00 0.00 Canceled 2018-06-08 2018-06-11 2018-06-13 2018-06-18 2018-06-19 2018-06-23 2018-06-28 2018-09-06 nvironmental and Social Imp ant Selection vements act Assessment(ESIA) for Wa ste Transfer Stations GH-MWH-60063-CS-CQS / Pr Component 1: Climate Resil Individual Consult ocurement of a Procurement IDA / V1450 ient Drainage and Flood Miti Prior Open 84,000.00 2,302.58 Signed 2018-05-21 2018-07-09 2018-07-30 2019-06-10 2018-08-27 2019-06-26 2018-11-05 ant Selection Specialist gation Measures Component 3: Participatory GH-MWH-67597-CS-CQS / Co Upgrading of Targeted Flood Individual Consult nsultancy Service for Commu IDA / V1450 Post Open 25,000.00 5,346.53 Signed 2018-07-09 2018-10-16 2018-08-27 2019-06-27 2018-09-03 2019-07-03 2018-10-08 2019-08-11 2019-04-06 Prone Low-income Communi ant Selection nity Laison in Nima ties and Local Government S upport Component 3: Participatory GH-MWH-67593-CS-CQS / Co Upgrading of Targeted Flood Individual Consult nsultancy Services for Comm IDA / V1450 Post Open 25,000.00 5,346.53 Signed 2018-07-09 2018-10-16 2018-08-27 2019-06-27 2018-09-03 2019-07-03 2018-10-08 2019-08-11 2019-04-06 Prone Low-income Communi ant Selection unity Laison Alogboshie ties and Local Government S upport Component 3: Participatory GH-MWH-67599-CS-CQS / Co Upgrading of Targeted Flood Individual Consult nsultancy Services for Comm IDA / V1450 Post Open 25,000.00 5,346.53 Signed 2018-07-09 2018-10-16 2018-08-27 2019-06-27 2018-09-03 2019-07-03 2018-10-08 2019-08-11 2019-04-06 Prone Low-income Communi ant Selection unity Laison for Akweteman ties and Local Government S upport GH-MWH-72548-CS-INDV / C Component 2: Solid Waste Individual Consult onsultancy Service for Desig IDA / V1450 Management Capacity Impro Post Open 150,000.00 0.00 Canceled 2018-08-02 2018-09-20 2018-10-11 2018-11-15 2019-05-14 ant Selection n and construction supervisio vements n for Capping GH-MWH-81175-CS-INDV / C Component 1: Climate Resil onsultancy service for the pr Individual Consult IDA / V1450 ient Drainage and Flood Miti Post Limited 50,000.00 0.00 Canceled 2018-10-10 2018-10-16 2018-10-15 2018-10-29 2018-11-05 2018-12-10 2019-06-08 eparation of an Environment ant Selection gation Measures al and Social Impact Assessm ent on Dredging. Component 3: Participatory GH-MWH-67598-CS-CQS / Co Upgrading of Targeted Flood Individual Consult nsultancy Services for Comm IDA / V1450 Post Open 25,000.00 0.00 Canceled 2018-07-09 2018-10-16 2018-08-27 2018-09-03 2018-10-08 2019-04-06 Prone Low-income Communi ant Selection unity Laison for Alajo ties and Local Government S upport GH-MWH-96520-CS-INDV / C onsultancy services for prepa Component 1: Climate Resil Individual Consult ration of concept of operatio IDA / V1450 ient Drainage and Flood Miti Post Open 30,000.00 0.00 Canceled 2019-03-20 2019-05-08 2019-05-29 2019-07-03 2019-12-30 ant Selection ns (CONOPS) to support Hydr gation Measures ological services department (HSD) GH-MWH-103657-CS-INDV / Component 1: Climate Resil Consultancy Services for pre Individual Consult IDA / V1450 ient Drainage and Flood Miti Post Open 30,000.00 0.00 Canceled 2019-03-29 2019-05-17 2019-06-07 2019-07-12 2019-08-11 paration of Operation (CONO ant Selection gation Measures PS) to support NADMO. GH-MWH-96514-CS-INDV / C onsultancy service for prepar Component 1: Climate Resil Individual Consult ation of concept of operation IDA / V1450 ient Drainage and Flood Miti Post Open 30,000.00 0.00 Canceled 2019-03-20 2019-05-08 2019-05-29 2019-07-03 2019-12-30 ant Selection s (CONOPS) to support Ghan gation Measures a Meteorological Agency(G-M et) GH-MWH-145632-CS-INDV / Component 4: Project Mana Individual Consult Procurement of a Communic IDA / V1450 Post Open 92,000.00 84,000.00 Signed 2019-11-24 2019-12-16 2020-01-12 2020-04-23 2020-02-02 2020-05-06 2020-03-08 2020-06-30 2022-02-28 gement ant Selection ation Specialist GH-MWH-56614-CS-INDV / P Component 4: Project Mana Individual Consult rocurement of a Monitoring a IDA / V1450 Post Open 92,000.00 84,000.00 Signed 2019-11-24 2020-01-06 2020-01-12 2020-04-23 2020-02-02 2020-06-10 2020-03-08 2020-06-30 2022-02-28 gement ant Selection nd Evaluation Specialist GH-MWH-147718-CS-INDV / Component 3: Participatory Procurement of a Slum Upgra Upgrading of Targeted Flood Individual Consult IDA / V1450 Prior Open 120,000.00 115,200.00 Signed 2019-12-13 2020-03-08 2020-01-31 2020-09-11 2020-02-21 2020-10-12 2020-03-27 2020-11-05 2022-03-17 ding and Community Develo Prone Low-income Communi ant Selection pment Specialist ties and Local Government S upport GH-MWH-147973-CS-INDV / Component 3: Participatory Consulting Services to condu Upgrading of Targeted Flood ct Feasibility Studies of the Jo Individual Consult IDA / V1450 Prone Low-income Communi Post Open 120,000.00 0.00 Canceled 2019-12-30 2020-02-17 2020-03-09 2020-04-13 2022-04-03 int Development Planning Ar ant Selection ties and Local Government S ea and Operationalisation of upport the Inter-Jurisdictional Coordi nation Management Framew ork. GH-MWH-171381-CS-CDS / Component 1: Climate Resil Monthly Topographic and Bat IDA / 64100 ient Drainage and Flood Miti Prior Direct Selection Direct 168,000.00 0.00 Canceled 2020-05-11 2020-07-13 2020-05-21 2020-07-25 2021-04-21 hymetric Survey of the Odaw gation Measures River GH-MWH-147708-CS-INDV / Component 1: Climate Resil Individual Consult Procurement of a Drainage S IDA / V1450 ient Drainage and Flood Miti Prior Open 120,000.00 0.00 Canceled 2019-12-12 2019-12-18 2020-01-30 2020-02-20 2020-03-26 2022-03-16 ant Selection pecialist gation Measures GH-MWH-181685-CS-INDV / Component 4: Project Mana Individual Consult IDA / 64100 Prior Open 120,000.00 91,200.00 Signed 2020-07-06 2020-06-30 2020-08-24 2020-09-11 2020-09-14 2020-10-12 2020-10-19 2020-11-16 2022-10-19 Procurement of a Drainage S gement ant Selection pecialist GH-MWH-147713-CS-INDV / Component 2: Solid Waste Individual Consult Procurement of a Solid Waste IDA / V1450 Management Capacity Impro Prior Open 120,000.00 0.00 Canceled 2019-12-13 2019-12-18 2020-01-31 2020-02-21 2020-03-27 2022-03-17 ant Selection Management Specialist vements GH-MWH-181875-CS-INDV / Component 4: Project Mana Individual Consult Procurement of a Solid Waste IDA / 64100 Prior Open 120,000.00 102,634.68 Signed 2020-07-07 2020-06-30 2020-08-25 2020-12-18 2020-09-15 2021-01-18 2020-10-20 2021-03-04 2022-10-20 gement ant Selection Management Specialist GH-MWH-148849-CS-CDS / C onsulting Services for the Pre Component 2: Solid Waste paration of Environmental, S IDA / V1450 Management Capacity Impro Prior Direct Selection Direct 51,000.00 0.00 Canceled 2020-08-28 2020-09-07 2020-11-11 2021-01-10 ocial Impact Assessment (ESI vements A) for a Landfill site at Ayidan GH-MWH-223741-CS-INDV / Component 4: Project Mana Individual Consult Selection of a Procurement O IDA / 64100 Post Open 72,000.00 60,000.00 Signed 2021-04-30 2021-04-27 2021-06-18 2021-08-05 2021-07-09 2021-09-13 2021-08-13 2021-10-05 2023-08-03 gement ant Selection fficer for GARID Project GH-MWH-224551-CS-INDV / Component 1: Climate Resil Selection of a Probity Assura Individual Consult IDA / 64100 ient Drainage and Flood Miti Prior Open 24,000.00 15,500.00 Signed 2021-05-05 2021-06-30 2021-06-23 2021-10-22 2021-07-14 2022-01-04 2021-08-18 2022-01-24 2021-11-16 nce Provider for Performance ant Selection gation Measures Based Contract for Odaw Dre dging Works Page 8 GH-MWH-240095-CS-CDS / C onsulting Services for the pre Component 1: Climate Resil paration of Environmental an IDA / 64100 ient Drainage and Flood Miti Post Direct Selection Direct 95,000.00 72,932.56 Signed 2021-07-27 2021-09-22 2021-08-06 2021-10-25 2021-10-10 2022-02-20 2022-02-02 d Social Impact Assessment gation Measures of Anyaa and Pokuase Dispos al Sites GH-MWH-240299-CS-INDV / Recruitment of Technical Adv Component 4: Project Mana Individual Consult IDA / 64100 Post Open 108,000.00 132,000.00 Signed 2021-07-26 2021-07-22 2021-09-13 2021-09-23 2021-10-04 2021-09-23 2021-11-08 2021-10-15 2023-11-08 isor to assist MWH in the imp gement ant Selection lementation of Component 1 GH-MWH-82203-CS-INDV / C Component 2: Solid Waste onsultancy Service for the pr Individual Consult IDA / V1450 Management Capacity Impro Post Open 49,000.00 0.00 Canceled 2018-10-22 2018-04-10 2018-12-10 2018-12-31 2019-02-04 2019-08-03 eparation of a Resettlement ant Selection vements Action Plan for proposed Cap ping of Dumpsite. GH-MWH-80964-CS-INDV / C Component 2: Solid Waste Individual Consult onsultancy Services for Envir IDA / V1450 Management Capacity Impro Post Limited 24,000.00 0.00 Canceled 2018-10-04 2018-10-09 2018-10-29 2018-10-16 2018-10-30 2019-04-28 ant Selection onmental Audit of Kpone Lan vements dfill Site GH-MWH-364037-CS-CDS / Morphological Studies, Engin Component 1: Climate Resil Direct - Internation eering Design of Coastal Prot IDA / 64100 ient Drainage and Flood Miti Post Direct Selection 271,400.00 0.00 Under Review 2023-06-12 2023-11-22 2023-06-22 2023-08-26 2024-02-10 al ection Structures at the Oda gation Measures w River Outlet for WACA Proj ect Page 9