Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan February 7, 2014. Revision of the Procurement Plan, February 8, 2017 2. Date of General Procurement Notice: Updated April 20, 2017 3. Period covered by this procurement plan: The procurement period of project covered from year June 2017 to December 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 5 million All 2. NCB (Goods) Above US$ 4 million All 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 15 million All 5. ICB and LIB (Non-Consultant Above US$ 5 million All Services) 6. NCB (Non-Consultant Services) Above US$ 4 million All 2. Prequalification. Not applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan IBRD 8353-BR was approved on January 8, 2014 and revised on December 23, 2015 by the Government of the State of Espirito Santo. Any Other Special Procurement Arrangements: Retroactive Financing - an aggregate amount not to exceed $20,000,000 equivalent may be made for payments made prior to this date but on or after October 1, 2013, for Eligible Expenditures. June 5, 2017 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness Estimate Goods and Works d Review Cost by Bank Comments US$ (Prior / Description of Assignment million Post) SEAMA-1F2 / Aquisição de Equipamentos para o Sistema de Informações Ambiental 4.9 Prior CESAN-2B5 / Works at Vila Velha and Single Cariacica 164 Prior Stage III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 2 million All 2. Single Source (Firms) Above US$ 2 million All 3. Individual Above US$ 0.4 million All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $1.5 million equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule Estimate Consultant Services d Review Cost by Bank Comments US$ (Prior / Description of Assignment million Post) June 5, 2017 SEAMA-1F1 / Study and Projects for the development of the Environmental 2.34 Prior Management System. QCBS CESAN-2B1 / Supervision of works and execution of socio-environmental of the 2.8 Prior sewage systems in nine municipalities of the QCBS - countryside of the State of Espirito Santo Initiated CESAN-4A1 / Management of the RMGV Works QCBS - 18 Prior Supervision Program Initiated ARSP-4B1 / Revision and Tariff Restructuring of the Sanitation Services and Regulatory 1.8 Prior Accounting QCBS June 5, 2017 PROCUREMENT Brazil : BR Espirito Santo Integrated Sustainable Water Management Project PLAN General Information Country: Brazil Bank’s Approval Date of the Original Procurement Plan: 2017-02-08 2021-12-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P130682 GPN Date: 2017-04-20 Project Name: BR Espirito Santo Integrated Sustainable Water Management Project Loan / Credit No: IBRD / 83530 E Executing Agency(ies): xecutive Secretariat of the State of Espirito Santo WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Efficient Water Supply CESAN-2B6 / Contratacao Solicitação de Single Stage - One 2018-06- IBRD / 83530 Services and Increased Prévia Open - International 0.00 Cancelado 2017-08-30 2017-09-04 2017-10-16 2017-11-15 2017-12-20 Obras de Cariacica Ofertas Envelope 18 Access to Sanitation CESAN-2B3 / Execucao de obras e servicos de Implantacao, Reabilitacao e Efficient Water Supply Ampliacao de Sistemas de Solicitação de Single Stage - One 7,040,416.2 2018-02- IBRD / 83530 Services and Increased Posterior Open - National Assinado 2017-04-28 2017-09-11 2017-05-03 2017-06-14 2017-07-14 2017-08-18 2017-12-18 Esgotamento Sanitario de Ofertas Envelope 8 14 Access to Sanitation Conceicao do Castelo, Divino de Sao Lourenco e Marechal Floriano CESAN-2B4 / Execucao de obras e servicos de Implantacao, Reabilitacao e Efficient Water Supply Solicitação de Single Stage - One 8,117,229.6 2018-03- Ampliacao de Sistemas de IBRD / 83530 Services and Increased Posterior Open - National Rescindido 2017-06-10 2017-06-15 2017-07-27 2018-04-05 2017-08-26 2017-09-30 2018-04-19 Ofertas Envelope 5 29 Esgotamento Sanitario de Access to Sanitation Santa Leopoldina e Santa Maria de Jetiba CESAN-3B2 / Construcao de Watershed Management and Solicitação de Single Stage - One 2019-01- equipamentos sociais a IBRD / 83530 Posterior Open - National 0.00 Cancelado 2018-03-15 2018-03-20 2018-05-01 2018-05-31 2018-07-05 Restoration of Forest Cover Ofertas Envelope 01 margem do Mangarai CESAN-3B6 / Adequacao e recuperacao de Estradas Watershed Management and Solicitação de Single Stage - One 2018-01- IBRD / 83530 Posterior Open - National 0.00 Cancelado 2017-03-15 2017-03-20 2017-05-01 2017-05-31 2017-07-05 vicinais de terra, com Restoration of Forest Cover Ofertas Envelope 01 confeccao de caixas secas CESAN-2B5 / Contratacao Efficient Water Supply Solicitação de Single Stage - One 2018-03- Obras de Vila Velha e IBRD / 83530 Services and Increased Prévia Open - International 0.00 Cancelado 2017-05-30 2017-06-04 2017-07-16 2017-08-15 2017-09-19 Ofertas Envelope 18 Cariacica Access to Sanitation Efficient Water Supply CESAN-2B7 / DBO de Vila Solicitação de Single Stage - One 2024-06- IBRD / 83530 Services and Increased Prévia Open - International 0.00 Cancelado 2017-12-18 2017-11-18 2018-04-05 2018-04-05 2018-02-07 2017-12-18 2018-05-20 2018-06-04 2018-07-09 Velha. Propostas Envelope 07 Access to Sanitation Efficient Water Supply CESAN-2B8 / Contratacao de Solicitação de Single Stage - One 2021-04- IBRD / 83530 Services and Increased Prévia Open - International 0.00 Cancelado 2018-01-15 2018-01-20 2018-03-03 2018-04-02 2018-05-07 Obras Cariacica Ofertas Envelope 21 Access to Sanitation CESAN-2B10 / Contratação das Obras de ampliação do Efficient Water Supply sistema de coleta de esgoto Solicitação de Single Stage - One 47,000,682. 2018-11- IBRD / 83530 Services and Increased Prévia Open - International Assinado 2018-02-05 2018-05-25 2018-02-10 2018-06-27 2018-03-24 2018-09-24 2018-04-23 2018-11-20 2018-05-28 2019-03-01 da ETE Bandeirantes para Ofertas Envelope 26 24 Access to Sanitation Bairros Cariacica e Viana, em dois Lotes. Efficient Water Supply CESAN 2 B5 / DBO de Vila Solicitação de 2020-06- IBRD / 83530 Services and Increased Prévia Open - International Multi Stage 0.00 Cancelado 2018-04-26 2018-04-26 2018-05-30 2018-04-26 2018-08-08 2018-11-20 2018-12-25 Velha Propostas 17 Access to Sanitation Efficient Water Supply CESAN-2 B5 / DBO de Vila Solicitação de 78,084,201. 2020-06- IBRD / 83530 Services and Increased Prévia Open - International Multi Stage Em Análise 2017-11-17 2018-08-06 2018-04-23 2020-10-27 2018-05-23 2020-10-28 2017-12-18 2018-08-06 2018-08-08 2019-05-23 2018-11-20 2021-04-26 2018-12-25 2021-03-09 Velha. Propostas 30 17 Access to Sanitation INCAPER 3B5-4 / Construção de Obras de Adequação e Watershed Management and Solicitação de Single Stage - One 6,042,932.6 2019-07- Recuperação de Estradas IBRD / 83530 Posterior Open - National Assinado 2018-10-10 2020-03-30 2018-10-15 2020-05-04 2018-11-26 2020-06-01 2018-12-26 2020-08-25 2019-01-30 2020-12-28 Restoration of Forest Cover Ofertas Envelope 8 29 Vicinais e Construção de Caixas Secas DEFESA CIVIL-1H7 / Construção do Centro Integrated Water Solicitação de Single Stage - One 2019-05- Estadual de Gerenciamento de IBRD / 83530 Management and Disaster Prévia Open - National 0.00 Cancelado 2018-07-13 2018-07-18 2018-08-29 2018-09-28 2018-11-02 Ofertas Envelope 01 Risco e Desastre do Espírito Risk Management Santo. SEAMA 1H7 / Construção do Integrated Water Centro Estadual de Solicitação de Single Stage - One 13,637,375. 2019-09- IBRD / 83530 Management and Disaster Prévia Open - National Assinado 2018-10-24 2018-11-14 2018-11-23 2019-03-18 2019-01-04 2019-04-30 2019-02-03 2019-07-31 2019-03-10 2019-10-02 Gerenciamento de Risco e Ofertas Envelope 92 06 Risk Management Desastre do Espírito Santo CESAN 2B9 / Execucao de obras e servicos de Implantacao, Reabilitacao e Ampliacao de Sistemas de Efficient Water Supply Solicitação de Single Stage - One 2019-09- Esgotamento Sanitario de IBRD / 83530 Services and Increased Prévia Open - National 0.00 Cancelado 2018-11-09 2018-11-13 2018-12-04 2019-01-18 2019-02-17 2019-03-24 Ofertas Envelope 20 Domingos Martins , Distrito Access to Sanitation de Pedra Menina e Afonso Cláudio (Lote 1) e Castelo (Lote 2) SEAMA-3B6 / Adequacao e recuperacao de Estradas Watershed Management and Solicitação de Single Stage - One 2018-05- IBRD / 83530 Posterior Open - National 0.00 Cancelado 2017-07-31 2017-08-05 2017-09-16 2017-10-16 2017-11-20 vicinais de terra, com Restoration of Forest Cover Ofertas Envelope 19 confeccao de caixas secas SEAMA-3B2 / Construcao de Watershed Management and Solicitação de Single Stage - One 2019-01- equipamentos sociais a IBRD / 83530 Posterior Open - National 0.00 Cancelado 2018-03-15 2018-03-20 2018-05-01 2018-05-31 2018-07-05 Restoration of Forest Cover Ofertas Envelope 01 margem do Mangarai Page 1 CESAN-2B2 / Implantacao, Reabilitacao e Ampliacao de Efficient Water Supply Em fase de Solicitação de Single Stage - One 2019-02- Sistemas de Esgotamento IBRD / 83530 Services and Increased Prévia Open - National 0.00 Implementaç 2016-07-16 2016-07-21 2016-08-06 2016-08-21 2016-08-31 Ofertas Envelope 17 Sanitario de Dores do Rio Access to Sanitation ão Preto, Ibatiba, Irupi e Iuna CESAN 2B11 / Implantação, Reabilitação e Ampliação de Sistemas de Esgotamento Sanitário na Região do Efficient Water Supply Solicitação de Single Stage - One 2022-08- Caparaó – Município de IBRD / 83530 Services and Increased Posterior Open - National 0.00 Cancelado 2020-12-11 2020-12-22 2020-12-17 2020-12-23 2021-01-16 2021-01-25 2021-02-05 2021-03-02 Ofertas Envelope 24 Ibatiba (Lote 1), Iúna (Lote 2), Access to Sanitation Irupi (Lote 3), Dores do Rio Preto e Distrito de Pedra Menina (Lote 4) CESAN 2B12 / Implantação, Reabilitação e Ampliação de Efficient Water Supply Sistemas de Esgotamento Solicitação de Single Stage - One 2023-01- IBRD / 83530 Services and Increased Posterior Open - National 0.00 Cancelado 2020-12-18 2020-12-23 2021-01-07 2021-02-06 2021-02-26 2021-03-23 Sanitário de Domingos Ofertas Envelope 12 Access to Sanitation Martins (Lote 1) e Castelo (Lote 2). CESAN 2B13 / Implantação, Reabilitação e Ampliação de Efficient Water Supply Solicitação de Single Stage - One 2022-11- Sistemas de Esgotamento IBRD / 83530 Services and Increased Posterior Open - National 0.00 Cancelado 2021-01-08 2021-01-24 2021-02-23 2021-03-15 2021-04-09 Ofertas Envelope 30 Sanitário de Afonso Cláudio Access to Sanitation (Lote 1) e Apiacá (Lote 2) CESAN 2B14 / Implantação, Reabilitação e Ampliação de Efficient Water Supply Solicitação de Single Stage - One 11,051,203. 2023-02- Sistemas de Esgotamento IBRD / 83530 Services and Increased Posterior Open - National Assinado 2021-03-17 2021-03-31 2021-04-06 2021-05-05 2021-05-06 2021-05-04 2021-05-26 2021-06-10 2021-06-20 2021-07-27 Ofertas Envelope 15 10 Sanitário do Município de Access to Sanitation Castelo. CESAN 2B15 / Implantação, Reabilitação e Ampliação de Sistemas de Esgotamento Sanitário de Domingos Efficient Water Supply Solicitação de Single Stage - One 14,734,785. 2023-02- Martins e Afonso Cláudio IBRD / 83530 Services and Increased Posterior Open - National Assinado 2021-03-17 2021-05-26 2021-04-06 2021-05-31 2021-05-06 2021-06-28 2021-05-26 2021-08-17 2021-06-20 2021-10-13 Ofertas Envelope 90 10 (Lote 1), Ibatiba, Iúna e Irupi Access to Sanitation (Lote 2) e Dores do Rio Preto , Distrito de Pedra Menina e Apiacá (Lote 3). National CESAN 2B16 / Implantação, Procurement Reabilitação e Ampliação de Efficient Water Supply Em fase de Solicitação de Single Stage - One Document - 1 2023-02- Sistemas de Esgotamento IBRD / 83530 Services and Increased Posterior Open - National 0.00 Implementaç 2021-09-24 2021-10-08 2021-09-29 2021-11-10 2021-11-12 2021-12-10 2021-12-01 2022-02-08 Ofertas Envelope Envelope 03 Sanitário de Santa Leopoldina Access to Sanitation ão process (Non e Santa Maria de Jetibá. Bank-SPD) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CESAN-2A3 / Aquisicao de Motores Eletricos de Alta Efficient Water Supply Solicitação de Single Stage - One Eficiencia para substituicao de IBRD / 83530 Services and Increased Posterior Open - National 0.00 Cancelado 2018-04-20 2018-04-25 2018-06-06 2018-07-06 2018-08-10 2019-02-06 Ofertas Envelope equipamentos diversos na Access to Sanitation CESAN (Item 8 Efic Energetica) CESAN-2A6 / Aquisicao de Motores Eletricos de Alta Efficient Water Supply Eficiencia para substituicao de IBRD / 83530 Services and Increased Posterior Leilões eletrônicos Open 590,279.03 Assinado 2017-11-28 2017-12-17 2018-05-29 2018-01-21 2018-09-24 2018-07-20 equipamentos diversos na Access to Sanitation CESAN (Item 8 Efic Energética) DEFESA CIVIL-1H32 / Integrated Water Solicitação de Single Stage - One Aquisicao de equipamentos IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2017-04-10 2017-09-04 2017-04-15 2017-05-27 2017-06-26 2017-07-31 2018-01-27 Ofertas Envelope de comunicacao e outros Risk Management SEAMA-1F2 / Aquisicao de Integrated Water Solicitação de Single Stage - One Hardware para o Sistema de IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2017-05-15 2017-05-20 2017-07-01 2017-07-31 2017-09-04 2018-03-03 Ofertas Envelope Informacoes Ambiental Risk Management SEAMA-1F8 / Aquisicao de Integrated Water Hardware para o Sistema de IBRD / 83530 Management and Disaster Posterior Leilões eletrônicos Open 2,632,149.13 Assinado 2017-11-28 2017-12-17 2019-10-14 2018-01-21 2019-10-14 2018-07-20 Informacoes Ambiental Risk Management DEFESA CIVIL-1H5 / Integrated Water Solicitação de Single Stage - One Aquisicao de estacoes moveis IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2017-05-20 2017-09-04 2017-05-25 2017-07-06 2017-08-05 2017-09-09 2018-03-08 Ofertas Envelope de tratamento de agua Risk Management SEAMA-1C1 / Aquisicao de Integrated Water sondas multiparametricas IBRD / 83530 Management and Disaster Posterior Leilões eletrônicos Open 76,328.36 Assinado 2018-06-04 2018-06-23 2018-12-03 2018-07-28 2018-12-03 2019-01-24 portateis. Risk Management CESAN 2A2 / Serviços de Modernização Efficient Water Supply (Retrofit/Revamp) de Bombas IBRD / 83530 Services and Increased Prévia Aquisição Direta Direct 3,063,298.76 Assinado 2018-07-19 2018-11-08 2018-08-15 2018-11-14 2018-09-11 2019-03-27 2020-10-09 Verticais de Grande Porte do Access to Sanitation Sistema de Produção e Água da RMGV CESAN-2A2 / Reforma ou substituicao das bombas de grande porte da CESAN, com Efficient Water Supply Solicitação de Single Stage - One intuito de recuperacao do IBRD / 83530 Services and Increased Posterior Open - National 0.00 Cancelado 2018-03-20 2018-03-25 2018-05-06 2018-06-05 2018-07-10 2019-01-06 Ofertas Envelope rendimento eletrico dos Access to Sanitation equipamentos (Item 6 Efic Energetica) AGERH-1C2 / Aquisicao de 03 medidores de vazao para conduto forcado, 01 medidor Integrated Water de vazao para pequenas Solicitação de Single Stage - One IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2017-05-22 2017-05-27 2017-07-08 2017-08-07 2017-09-11 2018-03-10 profundidades, 01 medidor de Ofertas Envelope Risk Management vazao para medias e grandes profundidades e 04 sondas multiparametros Page 2 DEFESA CIVIL-1H31 / Aquisicao de mobiliario para Integrated Water Solicitação de Single Stage - One Coordenadorias Regionais e IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2017-07-20 2017-09-14 2018-03-13 Cotações Envelope Municipais de Protecao e Risk Management Defesa Civil DEFESA CIVIL-1H321 / Integrated Water Aquisicao de veiculos para IBRD / 83530 Management and Disaster Posterior Leilões eletrônicos Open 0.00 Cancelado 2017-11-20 2017-12-09 2018-01-13 2018-07-12 combate a incendio florestal e Risk Management outros DEFESA CIVIL-1H322 / Integrated Water Aquisicao de empilhadeira e IBRD / 83530 Management and Disaster Posterior Leilões eletrônicos Open 0.00 Cancelado 2017-11-23 2017-12-18 2018-01-22 2018-07-21 mini escavadeira Risk Management DEFESA CIVIL-1H323 / Integrated Water Aquisicao de equipamentos IBRD / 83530 Management and Disaster Posterior Leilões eletrônicos Open 0.00 Cancelado 2017-12-15 2018-01-03 2018-02-07 2018-08-06 para salvamento em Risk Management enchentes e outros DEFESA CIVIL-1H6 / Integrated Water Aquisicao de estacoes moveis IBRD / 83530 Management and Disaster Posterior Leilões eletrônicos Open 0.00 Cancelado 2017-12-05 2017-12-24 2018-01-28 2018-07-27 de tratamento de agua Risk Management SEAMA-1F7 / Aquisicao de Integrated Water Solicitação de Single Stage - One Fibra Ótica para o Sistema de IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2017-07-04 2017-07-09 2017-08-20 2017-09-19 2017-10-24 2018-04-22 Ofertas Envelope Informacoes Ambiental Risk Management CESAN 2A10 / Fornecimento, configuração e implantação Efficient Water Supply de sistema móvel de dados e Solicitação de Single Stage - One IBRD / 83530 Services and Increased Posterior Open - National 1,072,373.62 Assinado 2018-11-09 2018-11-07 2018-12-04 2019-03-26 2019-01-15 2019-04-23 2019-02-14 2019-06-11 2019-03-21 2019-09-04 2019-09-17 planejamento de recursos na Ofertas Envelope Access to Sanitation manutenção eletromecânica da CESAN. CESAN 1A1 / Monitoramento Efficient Water Supply Solicitação de Single Stage - One e Gestão de Índices Elétricos IBRD / 83530 Services and Increased Posterior Open - National 672,022.57 Assinado 2018-11-20 2018-11-07 2018-12-15 2019-03-26 2019-01-26 2019-05-08 2019-02-25 2019-07-09 2019-04-01 2019-09-02 2019-09-28 Ofertas Envelope (MGI). Access to Sanitation SEAMA 1H31 / Aquisição de mobiliário para Integrated Water Solicitação de Single Stage - One Coordenadorias Regionais e IBRD / 83530 Management and Disaster Posterior Open - National 22,490.27 Assinado 2018-10-28 2018-06-26 2018-11-12 2018-12-24 2018-07-12 2019-01-23 2018-09-17 2019-02-27 2018-11-29 2019-08-26 Ofertas Envelope Municipais de Proteção e Risk Management Defesa Civil SEAMA 1H321 / Aquisicao de Integrated Water Solicitação de Single Stage - One veiculos para combate a IBRD / 83530 Management and Disaster Posterior Open - National 283,525.19 Assinado 2018-12-15 2018-12-04 2018-12-30 2019-02-10 2018-12-19 2019-03-12 2019-05-21 2019-04-16 2019-06-11 2019-10-13 Ofertas Envelope incendio florestal e outros Risk Management SEAMA 1H322 / Aquisicao de Integrated Water Solicitação de Single Stage - One empilhadeira e mini IBRD / 83530 Management and Disaster Posterior Open - National 7,307.58 Assinado 2018-10-28 2018-12-04 2018-11-12 2018-12-24 2018-12-19 2019-01-23 2019-03-19 2019-02-27 2019-07-03 2019-08-26 Ofertas Envelope escavadeira Risk Management SEAMA 1H323 / Aquisicao de Integrated Water equipamentos para Solicitação de Single Stage - One IBRD / 83530 Management and Disaster Posterior Open - National 1,145,212.43 Assinado 2018-10-28 2020-03-17 2018-11-12 2018-12-24 2020-04-02 2019-01-23 2020-09-24 2019-02-27 2020-10-14 2019-08-26 salvamento em enchentes e Ofertas Envelope Risk Management outros SEAMA 1H324 / Aquisição de Veículo do Tipo Plataforma Integrated Water Solicitação de Single Stage - One para transporte de máquinas, IBRD / 83530 Management and Disaster Posterior Open - National 68,239.13 Assinado 2018-12-21 2020-08-13 2019-01-15 2020-08-04 2019-02-26 2020-08-28 2019-03-28 2020-10-30 2019-05-02 2020-10-30 2019-10-29 Ofertas Envelope equipamentos e autossocorro Risk Management de viaturas SEAMA-1F6 / Aquisicao de Integrated Water Solicitação de Single Stage - One Software para o Sistema de IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2017-07-09 2017-09-03 2018-03-02 Cotações Envelope Informacoes Ambiental Risk Management SEAMA 1H10 / Estações Meteorológicas - Aquisição de 32 plataformas de coleta de Integrated Water Solicitação de Single Stage - One dados para complementar a IBRD / 83530 Management and Disaster Posterior Open - National 505,292.60 Assinado 2019-03-29 2020-02-17 2019-05-18 2019-06-17 2020-03-04 2019-07-17 2020-07-14 2019-08-21 2020-07-24 2019-11-19 Ofertas Envelope rede de monitoramento Risk Management meteorológica do Espirito Santo CESAN 2A11 / Modernização Efficient Water Supply e Ampliação da Telemetria, Solicitação de Single Stage - One IBRD / 83530 Services and Increased Posterior Open - National 0.00 Cancelado 2019-04-01 2019-04-16 2019-05-28 2019-06-27 2019-08-01 2020-07-26 Telecomando e Centro de Ofertas Envelope Access to Sanitation Controle Operacional. SEAMA 1H6 / Aquisição de Integrated Water Solicitação de Single Stage - One estações móveis de IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2018-10-28 2018-11-17 2018-12-29 2019-01-28 2019-03-04 2019-08-31 Ofertas Envelope tratamento de água Risk Management CESAN 4C7 / Aquisição de Project Management, Solicitação de Single Stage - One computadores para a gestão IBRD / 83530 Supervision and Institutional Posterior Open - National 19,253.66 Assinado 2019-09-10 2019-10-25 2020-08-27 2019-11-24 Cotações Envelope do Projeto Strengthening SEAMA 1F7 / Implantação de infraestrutura de cabeamento óptico e telefônico, bem como Integrated Water de implantação, com IBRD / 83530 Management and Disaster Posterior Leilões eletrônicos Open 0.00 Cancelado 2018-10-30 2018-11-24 2018-12-13 2019-01-17 2019-07-16 fornecimento de Risk Management equipamentos e acessórios de rede Wireless SEAMA 1H326 / Aquisição de Integrated Water Em fase de 03 (três) caminhões tração 4 x Solicitação de Single Stage - One IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Implementaçã 2020-02-04 2020-07-27 2020-02-14 2020-08-04 2020-03-15 2020-03-30 2020-04-29 2020-10-26 4 para gestão de riscos e Ofertas Envelope Risk Management o desastre. SEAMA 1H327 / Aquisição de Integrated Water Solicitação de Single Stage - One mini escavadeira para gestão IBRD / 83530 Management and Disaster Posterior Open - National 46,778.42 Assinado 2020-02-04 2020-08-14 2020-02-14 2020-08-04 2020-03-15 2020-09-02 2020-03-30 2020-11-09 2020-04-29 2020-11-09 2020-10-26 Ofertas Envelope de riscos e desastre. Risk Management Page 3 SEAMA-1H325 / Aquisição de veículos Auto Bomba Tanque e Salvamento (ABTS) para Integrated Water Solicitação de Single Stage - One fortalecer a capacidade de IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2019-04-02 2019-05-17 2019-06-16 2019-07-01 2019-08-05 2020-02-01 Ofertas Envelope resposta a desastre do Corpo Risk Management de Bombeiros Militar do Espírito Santo. SEAMA 1H325 / Aquisição de veículos Auto Bomba Tanque Integrated Water e Salvamento (ABTS) para Solicitação de Single Stage - One IBRD / 83530 Management and Disaster Prévia Open - International 6,405,910.93 Assinado 2020-03-03 2020-05-18 2020-03-18 2020-10-28 2020-05-02 2020-11-06 2020-06-01 2021-01-29 2020-07-06 2021-06-29 2021-01-02 fortalecer a capacidade de Ofertas Envelope Risk Management resposta a desastre do Corpo de Bombeiros Militar do ES. Efficient Water Supply CESAN 4C19 / Aquisição de Solicitação de Single Stage - One Implementaçã IBRD / 83530 Services and Increased Posterior Open - National 0.00 2021-06-12 2021-08-07 2021-09-21 equipamentos de informática Cotações Envelope o Pendente Access to Sanitation SEAMA 3A8 / Aquisição de equipamentos de informática Watershed Management and Solicitação de Single Stage - One Implementaçã IBRD / 83530 Posterior Open - National 0.00 2021-06-30 2021-08-25 2021-10-24 para apoio ao Núcleo Gestor Restoration of Forest Cover Cotações Envelope o Pendente do Programa Reflorestar SEAMA 1H19 / Aquisição de 25 (vinte e cinco) Integrated Water pluviômetros automáticos Solicitação de Single Stage - One Implementaçã IBRD / 83530 Management and Disaster Posterior Open - National 0.00 2021-07-22 2021-08-06 2021-09-17 2021-10-17 2021-11-21 2022-05-20 para a Rede Estadual de Ofertas Envelope o Pendente Risk Management Monitoramento Hidrometereologico SEAMA 1H17 / Aquisição de retroescavadeiras compactas Integrated Water Solicitação de Single Stage - One Implementaçã para apoio logístico ao IBRD / 83530 Management and Disaster Posterior Open - National 0.00 2021-07-22 2021-08-06 2021-09-17 2021-10-17 2021-11-21 2022-02-19 Ofertas Envelope o Pendente Sistema Estadual de Proteção Risk Management e Defesa Civil SEAMA 3A9 / Aquisição de Watershed Management and Solicitação de Single Stage - One Implementaçã veículos para apoio logístico IBRD / 83530 Posterior Open - National 0.00 2021-07-05 2021-07-20 2021-08-31 2021-09-30 2021-11-04 2022-02-02 Restoration of Forest Cover Ofertas Envelope o Pendente ao Programa Reflorestar SEAMA 1H16 / Aquisição de Integrated Water caminhões baús para apoio Solicitação de Single Stage - One Implementaçã IBRD / 83530 Management and Disaster Posterior Open - National 0.00 2021-08-09 2021-08-24 2021-10-05 2021-11-04 2021-12-09 2022-06-07 logístico ao Sistema Estadual Ofertas Envelope o Pendente Risk Management de Proteção e Defesa Civil SEAMA 1H20 / Aquisição de contêineres e caixas de Integrated Water Solicitação de Single Stage - One Implementaçã proteção para armazenagem IBRD / 83530 Management and Disaster Posterior Open - National 0.00 2021-07-12 2021-07-27 2021-09-07 2021-10-07 2021-11-11 2022-08-08 Ofertas Envelope o Pendente de equipamentos de Risk Management salvamento SEAMA 3A12 / Aquisição de equipamentos de informática para suporte ao Watershed Management and Solicitação de Single Stage - One Implementaçã IBRD / 83530 Posterior Open - National 0.00 2021-11-27 2022-04-03 2022-05-03 desenvolvimento das Restoration of Forest Cover Cotações Envelope o Pendente atividades previstas no âmbito do Programa Reflorestar. SEAMA 1H21 / Aquisição de viaturas para atividades operacionais em desastres, Integrated Water contemplando 01 Viatura para Solicitação de Single Stage - One Implementaçã IBRD / 83530 Management and Disaster Prévia Open - International 0.00 2021-11-30 2021-12-20 2022-01-31 2022-03-02 2022-04-26 2023-01-21 busca e resgate em estruturas Ofertas Envelope o Pendente Risk Management colapsadas e 03 Viaturas de implemento aéreo com escada acoplada SEAMA 1H18 / Aquisição de viaturas para atividades operacionais em desastres, Integrated Water sendo: Lote 01 - 01 Viatura Solicitação de Single Stage - One IBRD / 83530 Management and Disaster Prévia Open - National 0.00 Cancelado 2021-07-27 2021-08-11 2021-09-22 2021-10-22 2021-11-26 2022-08-23 para busca e resgate em Ofertas Envelope Risk Management estruturas colapsadas e Lote 2 - 03 Viaturas de implemento aéreo com escada acoplada SEAMA-3A10 / Aquisição de veículos aéreos não tripulados (VANT/RPA) para suporte as Watershed Management and Solicitação de Single Stage - One Implementaçã IBRD / 83530 Posterior Open - National 0.00 2021-12-18 2022-02-11 2022-03-13 atividades de fiscalização e Restoration of Forest Cover Cotações Envelope o Pendente auditoria de campo do Programa Reflorestar NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SEAMA-1D2 / Servicos de Integrated Water levantamento de batimetria e Solicitação de Single Stage - One IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-04-23 medicao de ondas e correntes Ofertas Envelope Risk Management da Costa do Espirito Santo CESAN-3B1 / Elaboracao e Implementacao do Plano de Watershed Management and Solicitação de Single Stage - One IBRD / 83530 Posterior Open - National 0.00 Cancelado 2017-05-15 2017-05-20 2017-07-01 2017-07-31 2017-09-04 2018-03-03 Comunicacao Social do Restoration of Forest Cover Ofertas Envelope Mangarai Project Management, CESAN-4C5 / Auditoria Solicitação de Single Stage - One IBRD / 83530 Supervision and Institutional Posterior Open - National 20,993.69 Assinado 2017-11-20 2018-01-15 2018-05-22 2020-12-30 Externa do Projeto Cotações Envelope Strengthening CESAN-4C2 / Contratacao de Project Management, Solicitação de Single Stage - One modernizacao do Sistema IBRD / 83530 Supervision and Institutional Posterior Open - National 0.00 Cancelado 2017-02-10 2017-02-15 2017-03-29 2017-04-28 2017-06-02 2017-11-29 Ofertas Envelope SAFFI Strengthening CESAN-4C6 / Contratacao de Project Management, modernizacao do Sistema IBRD / 83530 Supervision and Institutional Posterior Leilões eletrônicos Open 455,837.41 Assinado 2017-12-10 2017-12-29 2018-02-02 2018-06-04 2020-01-23 SAFFI Strengthening Page 4 SEAMA-3B7 / Assistencia Watershed Management and Solicitação de Single Stage - One Tecnica Rural - ATER IBRD / 83530 Posterior Open - International 0.00 Cancelado 2017-10-10 2017-10-15 2017-11-26 2017-12-26 2018-01-30 2018-07-29 Restoration of Forest Cover Ofertas Envelope Mangarai. DEFESA CIVIL-1H21 / Integrated Water Solicitação de Single Stage - One Aquisicao de passagens IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2018-08-20 2018-10-15 2019-04-13 Cotações Envelope aereas Risk Management Integrated Water DEFESA CIVIL-1H22 / IBRD / 83530 Management and Disaster Posterior Aquisição Direta Direct 0.00 Cancelado 2018-08-06 2018-08-11 2018-09-15 2019-03-14 Inscricoes Risk Management SEAMA-3B10 / Servicos de Monitoramento Ambiental em Bacias de Controle e Watershed Management and Contribuicao de Sedimentos IBRD / 83530 Posterior Leilões eletrônicos Open 0.00 Cancelado 2018-06-15 2018-06-20 2018-07-09 2018-08-13 2019-02-09 Restoration of Forest Cover por Estradas Vicinais nao Pavimentadas na Bacia do Rio Mangarai. INCAPER-3B5-1 / Monitoramento Ambiental da Bacia do Mangaraí e em Bacias Watershed Management and Solicitação de Single Stage - One IBRD / 83530 Posterior Open - National 0.00 Cancelado 2018-11-12 2018-12-07 2019-01-18 2019-02-17 2019-03-24 2019-09-20 de Controle e Contribuição de Restoration of Forest Cover Ofertas Envelope Sedimentos por Estradas Vicinais SEAMA 1H12 / Serviços especializados para Integrated Water Solicitação de Single Stage - One Implantação e customização IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2018-12-21 2019-01-15 2019-02-26 2019-03-28 2019-05-02 2019-10-29 Ofertas Envelope do sistema Terra MA2 - Alerta Risk Management - ES. SEAMA 3A4 / Capacitação e Treinamento em Ações de Gestão de Mananciais e Watershed Management and Restauração Florestal - IBRD / 83530 Posterior Aquisição Direta Direct 3,940.08 Assinado 2018-10-29 2018-10-30 2018-11-13 2018-11-01 2018-12-18 2018-11-06 2019-06-16 Restoration of Forest Cover Aquisição de Inscrições para o 5ª Congresso Brasileiro de Reflorestamento SEAMA-1D3 / Servicos de Integrated Water levantamento de batimetria e IBRD / 83530 Management and Disaster Posterior Leilões eletrônicos Open 0.00 Cancelado 2018-02-08 2018-03-25 2018-04-29 2018-10-26 medicao de ondas e correntes Risk Management da costa do Espirito Santo SEAMA 1H11 / Instalação das Integrated Water Solicitação de Single Stage - One Implementaçã Estações Meteorológicas - IBRD / 83530 Management and Disaster Posterior Open - National 0.00 2019-07-25 2019-09-13 2019-10-13 2019-11-02 2019-11-30 2020-02-28 Ofertas Envelope o Pendente Alerta - ES. Risk Management SEAMA 1H13 / Inscrição no curso "Structural Collapse Specialist - Instructor Led Training", a ser realizado na Integrated Water Em fase de Texas A&M Enginnering IBRD / 83530 Management and Disaster Posterior Aquisição Direta Direct 0.00 Implementaçã 2019-03-20 2019-06-13 2019-05-04 2019-06-18 2019-07-23 Extension Service (TEEX) - Risk Management o USA, para 02 (dois) oficiais bombeiros militares. Realização em Set/2019. SEAMA 1H14 / Inscrição no curso "EOC Operations and Planning for All Harzards", Integrated Water Em fase de Escola Maryland Fire and IBRD / 83530 Management and Disaster Posterior Aquisição Direta Direct 0.00 Implementaçã 2019-03-20 2019-06-13 2019-05-04 2019-06-18 2019-07-23 Rescue Institute (MFRI) - USA Risk Management o - para 08 (oito) oficiais bombeiros militares. Realização em Out/2019. SEAMA-1C4 / Aquisição e Integrated Water Solicitação de Single Stage - One Implementaçã instalação de estações IBRD / 83530 Management and Disaster Posterior Open - National 0.00 2019-07-25 2019-09-13 2019-11-02 2019-12-02 2020-01-06 2020-12-01 Ofertas Envelope o Pendente hidrológicas automáticas. Risk Management SEAMA-3A3 / Assistencia Watershed Management and Solicitação de Single Stage - One IBRD / 83530 Posterior Open - International 0.00 Cancelado 2017-09-20 2017-09-25 2017-11-06 2017-12-06 2018-01-10 2018-07-09 Tecnica Rural - ATER Restoration of Forest Cover Ofertas Envelope SEAMA 1H1 / Desenvolvimento do Sistema Integrado de Proteção e Integrated Water Defesa Civil (Lote 1) e Solicitação de Single Stage - One IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2018-11-30 2018-12-25 2019-02-05 2019-03-07 2019-04-11 2019-10-08 Desenvolvimento do sistema Ofertas Envelope Risk Management de Integração de Dados Didometereológicos do ES (Lote 2) SEAMA-1F3 / Capacitacao em Integrated Water Solicitação de Single Stage - One Gestao Ambiental e de IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2018-08-17 2018-08-22 2018-10-03 2018-11-02 2018-12-07 2019-06-05 Ofertas Envelope Recursos Hidricos Risk Management SEAMA-3A2 / Elaboracao e Implementacao do Plano de Watershed Management and Solicitação de Single Stage - One IBRD / 83530 Posterior Open - National 0.00 Cancelado 2017-07-17 2017-07-22 2017-09-02 2017-10-02 2017-11-06 2018-05-05 Comunicacao Social do Restoration of Forest Cover Ofertas Envelope Reflorestar SEAMA 1H15 / Aquisição de passagens aéreas, incluindo reserva, emissão e marcação de bilhetes em vôos nacionais Integrated Water Em fase de e internacionais para USA - Solicitação de Single Stage - One IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Implementaçã 2019-05-25 2019-07-20 2019-08-19 Treinamento e visita técnica Cotações Envelope Risk Management o na Texas Enginnering Extension Service e no Maryland Fire and Recue Institute. SEAMA 3A1 / Contratação de serviços de aperfeiçoamento Watershed Management and Solicitação de Single Stage - One do Sistema de Gestão Técnica IBRD / 83530 Posterior Open - National 108,787.02 Assinado 2020-04-30 2020-08-11 2020-05-05 2020-06-16 2020-09-01 2020-07-16 2020-09-23 2020-08-20 2020-11-12 2021-02-16 Restoration of Forest Cover Ofertas Envelope e Financeira do Programa Reflorestar - Portal Reflorestar Page 5 5C16 - AUDITORIA 2021- 2022-2023 / Contratação de Serviços de Auditoria Independente do Contrato de Empréstimo Nº 8353-BR, Project Management, Em fase de Solicitação de Single Stage - One firmado entre o Governo do IBRD / 83530 Supervision and Institutional Posterior Open - National 0.00 Implementaçã 2021-04-20 2021-07-19 2023-09-30 Cotações Envelope Estado do Espírito Santo e o Strengthening o Banco Mundial - BIRD, para os exercícios de 2021, 2022 e 2023 (01/01/2023 a 31/07/2023). SEAMA 3A2 / Serviços para Suporte e Adequação da Watershed Management and Solicitação de Single Stage - One Implementaçã IBRD / 83530 Posterior Open - National 0.00 2021-09-30 2021-10-15 2021-11-26 2021-12-03 2021-12-23 2023-03-18 Estratégia de Comunicação do Restoration of Forest Cover Ofertas Envelope o Pendente Programa Reflorestar. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ARSP-4B1 / Revisao e Project Management, Seleção Baseada Reestruturacao Tarifaria dos IBRD / 83530 Supervision and Institutional Prévia na Qualidade e Open - International 1,495,227.64 Assinado 2017-04-10 2017-05-01 2017-06-16 2017-06-14 2017-11-05 2017-07-12 2018-03-08 2017-08-11 2018-05-18 2017-09-15 2018-10-30 2017-10-20 2019-03-27 2018-10-20 Servicos de Saneamento e Strengthening Custo Contabilidade Regulatoria SEDURB-1G1 / Elaboracao de Integrated Water Seleção Baseada Estudos e Desenvolvimento IBRD / 83530 Management and Disaster Posterior na Qualidade e Open - International 0.00 Cancelado 2017-09-20 2017-10-11 2017-11-24 2017-12-22 2018-01-21 2018-02-25 2018-04-01 2019-04-01 Plano Diretor de Aguas Risk Management Custo Urbanas da RMGV - Fase 1 CESAN-4A1 / Gerenciamento Project Management, Seleção Baseada Em fase de do Programa e Supervisao de IBRD / 83530 Supervision and Institutional Prévia na Qualidade e Open - International 0.00 2017-04-15 2017-06-23 2017-05-06 2017-06-19 2017-10-16 2017-07-17 2018-02-20 2017-08-16 2018-04-18 2017-09-20 2017-10-25 2018-10-25 Implementação Obras RMGV Strengthening Custo SEAMA-3A1 / Contratacao de Servicos de Aperfeicoamento Seleção Baseada do Sistema de Gestao Tecnica Watershed Management and IBRD / 83530 Posterior na Qualidade e Open - National 0.00 Cancelado 2017-06-15 2017-07-06 2017-08-19 2017-09-16 2017-10-16 2017-11-20 2017-12-25 2018-12-25 e Financeira do Programa Restoration of Forest Cover Custo Reflorestar - PORTAL REFLORESTAR AGERH-1C1 / Projeto executivo de microlocalizacao (Identificacao dos pontos e Integrated Water Seleção Baseada referenciais de niveis), Teste IBRD / 83530 Management and Disaster Posterior nas Qualificações Open - National 0.00 Cancelado 2017-06-05 2017-08-26 2017-10-09 2017-11-08 2017-12-13 2018-06-11 de Intensidade de sinais GSM, Risk Management dos Consultores anuencia de instalacao e croqui de estrutura de fixacao (50 ptos) CESAN-3B4 / Avaliacao Seleção Baseada Socioambiental da Bacia e Watershed Management and IBRD / 83530 Posterior na Qualidade e Open - National 0.00 Cancelado 2017-05-15 2017-06-05 2017-07-19 2017-08-16 2017-09-15 2017-10-20 2017-11-24 2018-11-24 Monitoramento de Impacto de Restoration of Forest Cover Custo Resultados INCAPER-3B5 / Elaboracao de Seleção Baseada Watershed Management and Diagnostico Socioeconomico IBRD / 83530 Posterior na Qualidade e Open - National 0.00 Cancelado 2017-06-15 2017-07-06 2017-08-19 2017-09-16 2017-10-16 2017-11-20 2017-12-25 2018-12-25 Restoration of Forest Cover de 800 propriedades rurais Custo Project Management, CESAN-4C1 / Auditoria Seleção Baseada IBRD / 83530 Supervision and Institutional Posterior Open - National 0.00 Cancelado 2017-05-22 2017-06-12 2017-07-26 2017-08-23 2017-09-22 2017-10-27 2017-12-01 2018-05-30 Externa do Projeto no Menor Custo Strengthening SEDURB-1G2 / Elaboracao do Integrated Water Seleção Baseada Em fase de Plano Diretor de Aguas IBRD / 83530 Management and Disaster Posterior na Qualidade e Open - National 907,489.02 2018-02-08 2018-05-17 2018-03-08 2018-07-31 2018-05-21 2019-06-25 2018-06-18 2019-08-15 2018-07-18 2019-08-14 2018-08-22 2020-01-15 2018-09-26 2020-01-22 2019-09-26 Implementação Urbanas da RMGV Risk Management Custo CESAN-2B1 / Supervisao de obras e execucao de Servicos Efficient Water Supply Seleção Baseada Socioambientais dos Sistemas IBRD / 83530 Services and Increased Prévia na Qualidade e Open - International 0.00 Cancelado 2017-05-22 2017-09-13 2017-06-12 2017-07-26 2018-03-08 2017-08-23 2017-09-22 2017-10-27 2017-12-01 2018-12-01 de Esgotamento Sanitario em Access to Sanitation Custo 09 (nove) municipios do interior do Espirito Santo CESAN-2A1 / 1a. Etapa do Plano Diretor de Conservacao de Energia Eletrica para Efficient Water Supply Seleção Baseada Sistemas de Coleta e IBRD / 83530 Services and Increased Posterior na Qualidade e Open - National 0.00 Cancelado 2018-05-21 2018-06-11 2018-07-25 2018-08-22 2018-09-21 2018-10-26 2018-11-30 2019-11-30 Tratamento de Esgoto da Access to Sanitation Custo CESAN no Espirito Santo (Item 10 Efic Energetica) INCAPER-3B5-3 / Supervisão de Obras de Adequação e Watershed Management and Seleção Baseada Recuperação de Estradas IBRD / 83530 Posterior Open - National 0.00 Cancelado 2018-11-30 2018-12-21 2019-02-09 2019-03-09 2019-04-08 2019-05-13 2019-06-17 2019-12-14 Restoration of Forest Cover no Menor Custo Vicinais e Construção de Caixas Secas SEAMA 1H8 / Serviços de Supervisão dos Projetos e Integrated Water Obras de Implantação do Seleção Baseada IBRD / 83530 Management and Disaster Posterior Open - National 643,788.07 Assinado 2018-12-20 2019-05-07 2019-01-10 2019-09-20 2019-02-23 2020-01-14 2019-03-23 2020-02-11 2019-04-22 2020-04-17 2019-05-27 2020-05-14 2019-07-01 2020-10-29 2019-12-28 Centro Estadual de no Menor Custo Risk Management Gerenciamento de Riscos e Desastres (CEGRD). SEAMA-1F9 / Serviços de consultoria especializada para realização de levantamentos Integrated Water Seleção Baseada de requisitos e as respectivas IBRD / 83530 Management and Disaster Posterior na Qualidade e Open - National 0.00 Cancelado 2019-03-11 2019-03-22 2019-04-08 2019-03-25 2019-06-07 2019-07-05 2019-08-04 2019-09-08 2019-10-13 2020-01-11 contagens estimadas em Risk Management Custo pontos de função de sistemas de informação da SEMA/IEMA/AGERH SEAMA-1D1 / Determinacao Integrated Water Seleção Baseada da variacao temporal da linha IBRD / 83530 Management and Disaster Posterior na Qualidade e Open - National 0.00 Cancelado 2017-06-16 2017-07-07 2017-08-20 2017-09-17 2017-10-17 2017-11-21 2017-12-26 2018-12-26 de costa do Espirito Santo Risk Management Custo Page 6 SEAMA-3B4 / Avaliacao Seleção Baseada Socioambiental da Bacia e Watershed Management and IBRD / 83530 Posterior na Qualidade e Open - National 0.00 Cancelado 2018-03-15 2018-04-05 2018-05-19 2018-06-16 2018-07-16 2018-08-20 2018-09-24 2019-09-24 Monitoramento de Impacto de Restoration of Forest Cover Custo Resultados INCAPER-3B1 / Consultoria técnica especializada em Educação Ambiental e Seleção Baseada Watershed Management and Mobilização Social com IBRD / 83530 Posterior na Qualidade e Open - National 690,198.37 Assinado 2019-03-11 2019-03-12 2019-04-01 2019-03-25 2019-05-31 2019-10-25 2019-06-28 2020-01-20 2019-07-28 2020-02-14 2019-09-01 2020-06-18 2019-10-06 2020-12-09 2020-12-29 Restoration of Forest Cover enfoque no empoderamento Custo feminino, no âmbito do Projeto Piloto do Rio Mangaraí. INCAPER-3B5-2 / Gestão da Terra, Educação Ambiental e Seleção Baseada Watershed Management and Mobilização Social com IBRD / 83530 Prévia na Qualidade e Open - International 0.00 Cancelado 2018-10-30 2019-01-23 2018-11-20 2019-01-14 2019-02-11 2019-03-13 2019-04-17 2019-05-22 2020-05-21 Restoration of Forest Cover enfoque no empoderamento Custo feminino SEAMA-3B9 / Contratação de consultoria técnica Seleção Baseada especializada em Mobilização Watershed Management and IBRD / 83530 Posterior na Qualidade e Open - National 0.00 Cancelado 2018-01-30 2018-02-20 2018-04-05 2018-05-03 2018-06-02 2018-07-07 2018-08-11 2019-08-11 Social e Educação Ambiental Restoration of Forest Cover Custo no âmbito do Projeto Piloto Mangaraí SEAMA-1C3 / Microlocalização em campo para instalação de estações hidrológicas automáticas com Integrated Water Seleção Baseada seus respectivos lances de IBRD / 83530 Management and Disaster Posterior na Qualidade e Open - National 203,106.78 Assinado 2019-03-11 2019-03-22 2019-04-01 2019-03-25 2019-06-05 2020-01-23 2019-07-03 2020-03-02 2019-08-02 2020-06-01 2019-09-06 2020-08-27 2019-10-11 2020-11-16 2020-06-07 réguas linimétricas e Risk Management Custo referenciais de nível, incluindo levantamento topo- batimétrico e elaboração de projetos construtivos. SEAMA-1C1-2 / Consultoria Integrated Water Seleção Baseada para Microlocalização de IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2018-10-28 2018-11-18 2019-01-01 2019-01-29 2019-02-28 2019-04-04 2019-05-09 2019-11-05 no Menor Custo Estações Hidrológicas Risk Management SEAMA-1C2 / Projeto executivo de microlocalizacao (Identificacao dos pontos e Integrated Water Seleção Baseada referenciais de niveis), Teste IBRD / 83530 Management and Disaster Posterior na Qualidade e Open - National 0.00 Cancelado 2018-07-25 2018-08-15 2018-09-28 2018-10-26 2018-11-25 2018-12-30 2019-02-03 2020-02-03 de Intensidade de sinais GSM, Risk Management Custo anuencia de instalacao e croqui de estrutura de fixacao (50 ptos). SEAMA-1F10 / Desenvolver sistema de informações integrado ao Geobases - Serviços técnicos de Integrated Water Seleção Baseada parametrização, construção IBRD / 83530 Management and Disaster Posterior na Qualidade e Open - National 195,731.59 Assinado 2019-03-11 2019-03-22 2019-04-01 2019-03-25 2019-06-15 2020-03-19 2019-07-13 2020-06-17 2019-08-12 2020-07-08 2019-09-16 2020-07-31 2019-10-21 2020-10-19 2020-10-20 de navegadores geográficos, Risk Management Custo documentação e transferência de conhecimento para o Geobases SEAMA 1H4 / Integrated Water Seleção Baseada Desenvolvimento do Geobases IBRD / 83530 Management and Disaster Posterior na Qualidade e Open - National 0.00 Cancelado 2018-10-01 2018-10-22 2018-12-05 2019-01-02 2019-02-01 2019-03-08 2019-04-12 2020-04-11 2.0. Risk Management Custo SEAMA-1F5 / Modelagem Integrated Water Seleção Baseada Institucional da Agencia IBRD / 83530 Management and Disaster Posterior na Qualidade e Open - National 0.00 Cancelado 2017-09-20 2017-10-11 2017-11-24 2017-12-22 2018-01-21 2018-02-25 2018-04-01 2019-04-01 Ambiental Risk Management Custo SEAMA-3B11 / Elaboracao de estudos de aplicacao das Seleção Baseada Watershed Management and metodologias e ferramentas IBRD / 83530 Posterior na Qualidade e Open - National 0.00 Cancelado 2018-07-10 2018-07-31 2018-09-13 2018-10-11 2018-11-10 2018-12-15 2019-01-19 2020-01-19 Restoration of Forest Cover do Sistema de Modelagem Custo Costeira - SMC Brasil. SEAMA-3B5 / Elaboracao de Seleção Baseada Watershed Management and Diagnostico Socioeconomico IBRD / 83530 Posterior na Qualidade e Open - National 0.00 Cancelado 2017-09-15 2017-10-06 2017-11-19 2017-12-17 2018-01-16 2018-02-20 2018-03-27 2019-03-27 Restoration of Forest Cover de 800 propriedades rurais Custo SEAMA-3B8 / Assistencia Watershed Management and Seleção Baseada IBRD / 83530 Posterior Open - National 0.00 Cancelado 2017-11-14 2017-12-05 2018-01-18 2018-02-15 2018-03-17 2018-04-21 2018-05-26 2019-05-26 Tecnica Rural - ATER Restoration of Forest Cover na Qualidade e MangaraI Custo SEAMA 1H5 / Integrated Water Seleção Baseada Desenvolvimento do sistema IBRD / 83530 Management and Disaster Posterior na Qualidade e Open - National 140,424.84 Assinado 2019-04-15 2019-05-07 2019-05-06 2019-06-19 2020-01-23 2019-07-17 2020-03-04 2019-08-16 2020-05-05 2019-09-20 2020-07-09 2019-10-25 2020-10-19 2020-06-21 de Integração de Dados Risk Management Custo Hidrometereológicos do ES CESAN-2B12 / Supervisão de Obras e Execução de Serviços Efficient Water Supply Socioambientais de Sistemas Seleção Baseada IBRD / 83530 Services and Increased Prévia Open - International 0.00 Cancelado 2018-09-17 2018-10-08 2018-11-21 2018-12-19 2019-01-18 2019-02-22 2019-03-29 2019-09-25 de Esgotamento Sanitário em no Menor Custo Access to Sanitation Municípios do Interior do Estado. SEAMA-1H3 / Integrated Water Seleção Baseada Desenvolvimento do Sistema IBRD / 83530 Management and Disaster Posterior na Qualidade e Open - National 126,374.31 Assinado 2019-04-15 2019-05-07 2019-05-06 2019-06-19 2019-12-06 2019-07-17 2020-02-20 2019-08-16 2020-05-05 2019-09-20 2020-05-18 2019-10-25 2020-10-19 2020-06-21 Integrado de Proteção e Risk Management Custo Defesa Civil. SEAMA 1H3 / Integrated Water Desenvolvimento do Sistema Seleção Baseada IBRD / 83530 Management and Disaster Posterior Open - National 0.00 Cancelado 2019-05-10 2019-05-31 2019-08-04 2019-09-01 2019-10-01 2019-10-31 2019-12-05 2020-05-03 Integrado de Proteção e na Qualidade Risk Management Defesa Civil SEAMA-1F1 / Integrated Water Seleção Baseada Desenvolvimento de Sistemas IBRD / 83530 Management and Disaster Prévia na Qualidade e Open - International 0.00 Cancelado 2019-12-02 2019-12-23 2020-02-01 2020-02-29 2020-03-30 2020-05-04 2020-06-08 2021-04-04 Finalísticos de Gestão Risk Management Custo Ambiental. CESAN 2A7 / Plano Diretor Efficient Water Supply Seleção Baseada de Conservação de Energia - IBRD / 83530 Services and Increased Posterior na Qualidade e Open - National 0.00 Cancelado 2018-09-17 2018-10-08 2018-11-21 2018-12-19 2019-01-18 2019-02-22 2019-03-29 2020-03-28 PDCE - 2º Etapa. Access to Sanitation Custo Page 7 CESAN 4A3 / Servicos de Supervisao de Obras de Project Management, Seleção Baseada Esgotamento Sanitario da IBRD / 83530 Supervision and Institutional Prévia Open - International 0.00 Cancelado 2018-07-30 2018-09-18 2018-08-20 2019-03-19 2018-10-03 2018-10-31 2018-11-30 2019-01-04 2019-02-08 2019-08-07 no Menor Custo RMGV, no Município de Vila Strengthening Velha. CESAN 4A2 / Servicos de Supervisao de Obras de Project Management, Seleção Baseada Esgotamento Sanitario de IBRD / 83530 Supervision and Institutional Prévia Open - International 0.00 Cancelado 2018-07-25 2018-09-03 2018-08-15 2019-02-28 2018-09-28 2018-10-26 2018-11-25 2018-12-30 2019-02-03 2019-08-02 no Menor Custo Cariacica - ETE Bandeirantes Strengthening (Bairros Cariacica e Viana) CESAN 4A4 / Serviços de Project Management, Supervisão de Obras de Seleção Baseada IBRD / 83530 Supervision and Institutional Prévia Open - International 3,048,098.63 Assinado 2019-10-02 2019-11-11 2019-10-02 2019-10-31 2020-06-15 2019-12-15 2020-08-10 2020-01-14 2020-10-05 2020-02-09 2021-01-20 2020-03-02 2021-06-03 2023-06-15 Esgotamento Sanitário da no Menor Custo Strengthening RMGV, Município de Vila Velha CESAN 4A5 / Supervisão de Project Management, Obras de Esgotamento Seleção Baseada IBRD / 83530 Supervision and Institutional Prévia Open - International 2,345,760.06 Assinado 2019-10-01 2019-11-11 2019-10-22 2019-12-05 2020-06-16 2020-01-02 2020-08-10 2020-02-01 2020-09-29 2020-03-07 2020-11-06 2020-04-11 2021-02-02 2023-07-25 Sanitário de Cariacica e no Menor Custo Strengthening Bairros Viana na RMGV CESAN 4C17 / Contratação de consultoria especializada de pessoa jurídica para elaboração da Avaliação Project Management, Seleção Baseada Ambiental e Social do Implementação IBRD / 83530 Supervision and Institutional Posterior na Qualidade e Open - National 0.00 2021-07-30 2021-08-20 2021-09-19 2021-10-17 2021-11-06 2021-11-30 2021-12-15 2023-03-10 Programa de Gestão Integrada Pendente Strengthening Custo dos Recursos Hídricos e Revitalização de Bacias Hidrográficas do Espírito Santo - Águas e Paisagem II SEAMA 1F11 / Consultoria especializada para elaboração de estudos de definição de Integrated Water Seleção Baseada Em fase de estrutura para o IBRD / 83530 Management and Disaster Posterior na Qualidade e Open - National 0.00 2021-10-19 2021-12-21 2021-11-18 2022-01-01 2022-01-29 2022-02-28 2022-04-04 2022-05-09 2023-01-04 Implementação fortalecimento da Agerh como Risk Management Custo órgão gestor de recursos hídricos do Espírito Santo. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CESAN-4C4 / Contratacao de Project Management, Implementação profissional para servicos de IBRD / 83530 Supervision and Institutional Posterior Individual Open 0.00 2017-03-15 2017-05-03 2017-05-24 2017-06-28 2017-12-25 Pendente traducao para apoio ao Strengthening Projeto AGERH-1E1 / Contratacao de Hidrogeologo para elaboracao Integrated Water de TDR e acompanhamento IBRD / 83530 Management and Disaster Posterior Individual Open 0.00 Cancelado 2017-05-22 2017-07-10 2017-07-31 2017-09-04 2018-03-03 dos trabalhos do Risk Management Levantamento. CESAN-4C3 / Contratacao de Project Management, um especialista em licitacoes IBRD / 83530 Supervision and Institutional Posterior Individual Open 6,242.28 Assinado 2017-12-08 2017-12-13 2018-01-03 2018-01-08 2018-01-08 2018-01-08 2018-04-08 para apoio ao Projeto Strengthening SEAMA-1E1 / Contratação de Hidrogeólogo para elaboração Integrated Water de Termo de Referência para a IBRD / 83530 Management and Disaster Posterior Individual Open 0.00 Cancelado 2018-01-30 2019-03-25 2018-03-20 2018-04-10 2018-05-15 2018-11-11 Execução do Levantamento e Risk Management Sistematização de dados e de estudos Hidrogeológico do ES SEAMA-1F4 / Elaboracao de Termo de Referencia para o Integrated Water desenho da Modelagem IBRD / 83530 Management and Disaster Posterior Individual Open 0.00 Cancelado 2017-06-20 2017-08-08 2017-08-29 2017-10-03 2018-04-01 Institucional da Agencia Risk Management Ambiental SEAMA 1H9 / Profissional para apoiar a Defesa Civil no gerenciamento, análise de Integrated Water projeto e supervisão das IBRD / 83530 Management and Disaster Posterior Individual Open 0.00 Cancelado 2018-10-29 2018-12-17 2019-01-07 2019-02-11 2019-08-10 obras do Centro de Risk Management Gerenciamento de Risco e outras atividades do Programa de execução do Órgão. SEAMA-3A5 / Compilação de dados sobre sistemas de abastecimento e de Watershed Management and reservação de água IBRD / 83530 Posterior Individual Open 20,038.18 Assinado 2019-03-13 2019-03-28 2019-05-01 2019-10-09 2019-05-22 2019-12-18 2019-06-26 2019-12-18 2019-10-13 Restoration of Forest Cover localizados nas bacias do Doce, São Mateus e Itaúnas (Regiao Norte) - Programa Reflorestar SEAMA-3A6 / Compilação de dados sobre sistemas de abastecimento e de reservação de água Watershed Management and localizados nas bacias do IBRD / 83530 Posterior Individual Open 23,451.22 Assinado 2019-03-13 2019-03-28 2019-05-01 2019-10-14 2019-05-22 2019-12-18 2019-06-26 2019-12-18 2019-10-18 Restoration of Forest Cover Riacho, Reis Magos, Santa Maria da Vitória, Jucu, Guarapari, Benevente, Rio Novo, Itabapoana, Itapemirim (Região Sul) - Reflorestar SEAMA 3A7 / Dimensionamento das áreas de intervenção e dos efeitos da mudança do uso da terra Watershed Management and sobre a qualidade da água em IBRD / 83530 Posterior Individual Open 25,710.10 Assinado 2019-03-28 2019-03-28 2019-05-16 2019-10-14 2019-06-06 2019-12-18 2019-07-11 2019-12-18 2020-02-21 Restoration of Forest Cover microbacias que fornecem água para ETA's e em 51 microbacias que captam água que abastece reservatório. Page 8 SEDURB-1G3 / Contratação de especialista em aquisições Project Management, nas diretrizes de agencias IBRD / 83530 Supervision and Institutional Posterior Individual Direct 0.00 Cancelado 2018-10-02 2018-10-12 2018-11-02 2018-12-07 2019-06-05 multilaterais com domínio no Strengthening idioma Ingles. CESAN 4C9 / Profissional Project Management, para apoio técnico IBRD / 83530 Supervision and Institutional Posterior Individual Open 45,266.46 Assinado 2019-08-30 2019-09-04 2019-09-07 2019-10-23 2019-09-10 2019-11-01 2019-09-25 2019-11-01 2021-04-30 administrativo à Gestão do Strengthening Projeto CESAN 4C10 / Profissional Project Management, para apoio de engenharia a IBRD / 83530 Supervision and Institutional Posterior Individual Open 65,444.11 Assinado 2019-08-30 2019-09-04 2019-09-09 2019-10-23 2019-09-12 2019-11-01 2019-09-27 2019-11-01 2021-04-30 Unidade de Gestão do Projeto Strengthening CESAN 4C11 / Profissional Project Management, para apoio a gestao financeira IBRD / 83530 Supervision and Institutional Posterior Individual Open 65,189.48 Assinado 2019-08-30 2019-09-04 2019-09-07 2019-10-23 2019-09-10 2019-11-18 2019-09-25 2019-11-18 2021-04-30 do Projeto (Controller). Strengthening CESAN 4C12 / Profissional Project Management, Implementação para apoio a gestão contábil IBRD / 83530 Supervision and Institutional Posterior Individual Open 0.00 2019-09-06 2019-09-14 2019-09-17 2019-10-02 2021-04-30 Pendente do Projeto Strengthening CESAN 4C13 / Profissional para apoio a Unidade de Project Management, Gerenciamento do Projeto nos IBRD / 83530 Supervision and Institutional Posterior Individual Open 40,315.80 Assinado 2019-09-20 2020-03-02 2019-09-28 2020-05-14 2019-10-01 2020-05-15 2019-10-16 2020-06-09 2021-04-30 serviços de supervisão Strengthening ambiental CESAN 4C14 / Profissional Project Management, para apoio a Unidade de Implementação IBRD / 83530 Supervision and Institutional Posterior Individual Open 0.00 2019-09-20 2019-09-28 2019-10-01 2019-10-16 2021-04-30 Gerenciamento do Projeto nos Pendente Strengthening serviços de supervisão social CESAN 4C8 / Especialista em Project Management, aquisições para apoio ao IBRD / 83530 Supervision and Institutional Prévia Individual Open 0.00 Cancelado 2019-09-10 2019-09-18 2019-09-21 2019-10-06 2021-04-30 Projeto Strengthening CESAN 4D1 / Treinamento e transferência de Project Management, Seleção Direta de conhecimentos técnicos sobre IBRD / 83530 Supervision and Institutional Posterior Direct 35,634.38 Assinado 2019-10-01 2019-11-05 2019-10-06 2019-11-26 2019-11-05 2020-01-06 2020-04-03 Consultores Concessões e Parcerias Strengthening Público-Privadas CESAN-4C8 / Especialista em Project Management, Seleção Direta de Em fase de aquisição para apoio à gestão IBRD / 83530 Supervision and Institutional Posterior Direct 0.00 2019-10-01 2019-10-15 2019-10-11 2019-11-05 2021-04-30 Consultores Implementação do Projeto Strengthening CESAN 4C15 / Profissional para apoio à gestão do Project Management, Projeto no desenvolvimento IBRD / 83530 Supervision and Institutional Posterior Individual Open 42,781.60 Assinado 2020-07-11 2019-12-17 2020-07-16 2020-05-14 2020-07-18 2020-05-14 2020-07-30 2020-07-08 2021-04-30 dos trabalhos do Núcleo Strengthening Reflorestar. CESAN 4C18 / Apoio técnico à SEAMA nos procedimentos Project Management, Implementação de aquisição e gestão de IBRD / 83530 Supervision and Institutional Posterior Individual Open 0.00 2021-07-15 2021-07-30 2021-08-20 2021-09-24 2023-03-18 Pendente contratos de atividades dos Strengthening componentes 1 e 3a. CESAN 4C16 / Apoio técnico especializado na preparação do Programa de Gestão Project Management, Integrada dos Recursos IBRD / 83530 Supervision and Institutional Posterior Individual Open 51,250.51 Assinado 2021-06-04 2021-06-23 2021-06-15 2021-08-09 2021-06-20 2021-08-10 2021-07-02 2021-09-20 2023-02-22 Hídricos e Revitalização de Strengthening Bacias Hidrográficas do Espírito Santo - Águas e Paisagem 2. CESAN 4C20 / Consultor individual para preparação da Project Management, Avaliação Socioambiental e Em fase de IBRD / 83530 Supervision and Institutional Posterior Individual Open 0.00 2021-10-11 2021-10-15 2021-11-15 2021-11-20 2021-12-07 2022-03-07 Marco de Gestão Implementação Strengthening Socioambiental do Programa Águas e Paisagem II CESAN 4C21 / Consultor individual para preparação do Marco de Reassentamento e Project Management, Em fase de Plano de Envolvimento das IBRD / 83530 Supervision and Institutional Posterior Individual Open 0.00 2021-10-11 2021-10-15 2021-11-15 2021-11-20 2021-12-07 2022-02-05 Implementação Partes Interessadas e Strengthening Divulgação de Informação do Programa Águas e Paisagem II CESAN 4C22 / Apoio técnico na preparação do novo projeto relacionado ao Project Management, Implementação Subcomponente 2.1 - IBRD / 83530 Supervision and Institutional Posterior Individual Open 0.00 2022-01-05 2022-02-09 2022-02-14 2022-03-03 2023-03-28 Pendente Programa Reflorestar, para Strengthening melhoria da cobertura florestal e do uso do solo CESAN 4C23 / Preparação e evolução do Sistema de Gestão Técnica, Administrativa e Financeira do Programa Reflorestar-Portal Project Management, Implementação Reflorestar, para IBRD / 83530 Supervision and Institutional Posterior Individual Open 0.00 2022-01-05 2022-02-09 2022-02-14 2022-03-03 2023-03-28 Pendente gerenciamento do Programa Strengthening Águas e da Paisagem II, no âmbito da nova operação de financiamento com o Banco Mundial Page 9