The World Bank                                                                                        Implementation Status & Results Report
           Somali Electricity Sector Recovery Project (P173088)



Somali Electricity Sector Recovery Project (P173088)


 AFRICA EAST | Somalia | Energy & Extractives Global Practice |
 IBRD/IDA | Investment Project Financing | FY 2022 | Seq No: 1 | ARCHIVED on 07-Mar-2022 | ISR50405 |


 Implementing Agencies: Ministry of Energy and Minerals, Somaliland, Federal Ministry of Energy and Water Resources (MoEWR), Federal Republic
 of Somalia, Ministry of Finance, Somaliland, Ministry of Finance, Federal Republic of Somalia



 Key Dates


  Key Project Dates

   Bank Approval Date: 08-Dec-2021                                                Effectiveness Date: --
   Planned Mid Term Review Date: 01-Aug-2024                                      Actual Mid-Term Review Date:
   Original Closing Date: 31-Dec-2026                                             Revised Closing Date: 31-Dec-2026
 pdoTable

 Project Development Objectives

  Project Development Objective (from Project Appraisal Document)
  The Project Development Objective is to increase access to lower cost and cleaner electricity supply in project areas and to reestablish the
  electricity supply industry.

  Has the Project Development Objective been changed since Board Approval of the Project Objective?
  No


 Components Table

 Name
 Component 1 –Subtransmission and distribution network reconstruction, reinforcement and operations
 efficiency in the major load centers of Mogadishu and Hargeisa:(Cost $75.00 M)
 Component 2 –Hybridization and battery storage systems for minigrids:(Cost $20.00 M)
 Component 3 – Stand-alone solar off-grid access to public institutions (health and education):(Cost $40.00
 M)
 Component 4 -Institutional development and capacity building:(Cost $15.00 M)

 Overall Ratings

 Name                                                                        Previous Rating                            Current Rating

 Progress towards achievement of PDO                                         --                                         Satisfactory
 Overall Implementation Progress (IP)                                        --                                         Satisfactory
 Overall Risk Rating                                                         --                                         Substantial


 Implementation Status and Key Decisions

  The project was approved by World Bank Board on December 8, 2021; and the Grant Agreement between the World Bank and Federal
  Government of Somalia (FGS) was signed on December 17, 2021. The project is on track to achieving effectiveness.




3/7/2022                                                                                                                        Page 1 of 9
            The World Bank                                                                                          Implementation Status & Results Report
            Somali Electricity Sector Recovery Project (P173088)




  Risks


 Systematic Operations Risk-rating Tool


  Risk Category                                                Rating at Approval                Previous Rating                Current Rating

  Political and Governance                                     High                             --                             High
  Macroeconomic                                                Substantial                      --                             Substantial
  Sector Strategies and Policies                               Moderate                         --                             Moderate
  Technical Design of Project or Program                       Moderate                         --                             Moderate
  Institutional Capacity for Implementation and
                                                               Substantial                      --                             Substantial
  Sustainability
  Fiduciary                                                    Substantial                      --                             Substantial
  Environment and Social                                       High                             --                             High
  Stakeholders                                                 Moderate                         --                             Moderate
  Other                                                        High                             --                             High
  Overall                                                      Substantial                      --                             Substantial



  Results


 PDO Indicators by Objectives / Outcomes



   Increase access to lower cost and cleaner electricity, re-establish the electricity supply industry

    IN01108850
    ►Increase in electricity supply (Megawatt hour(MWh), Custom)

                                        Baseline                     Actual (Previous)                Actual (Current)          End Target

    Value                               0.00                         --                               0.00                      237,000.00

    Date                                31-Jul-2021                  --                               23-Feb-2022              31-Jul-2027

                                        The indicator will track the additional electricity supply provided as a result a) technical loss reduction and
   Comments:
                                        synchronization under component 1; b) off-grid solar generation from component 3
    IN01108901
    ►Generation capacity of energy constructed or rehabilitated (Megawatt, Corporate)

                                        Baseline                     Actual (Previous)                Actual (Current)          End Target

    Value                               0.00                         --                               0.00                      23.00

    Date                                30-Jul-2021                  --                               23-Feb-2022              30-Jun-2026

     IN01108902
     Renewable energy generation capacity (other than hydropower) constructed under the project (Megawatt, Corporate Breakdown)


3/7/2022                                                                                                                           Page 2 of 9
           The World Bank                                                                                       Implementation Status & Results Report
           Somali Electricity Sector Recovery Project (P173088)



                                     Baseline                      Actual (Previous)             Actual (Current)             End Target

     Value                           0.00                         --                             0.00                         23.00

     Date                            30-Jul-2021                  --                             23-Feb-2022                 30-Jun-2026

    IN01108903
    ►Annual GHG avoided (Metric ton, Custom)

                                       Baseline                        Actual (Previous)           Actual (Current)           End Target

    Value                              0.00                         --                            0.00                        604,000.00

    Date                               31-Jul-2021                  --                            23-Feb-2022                 30-Jun-2026

                                       The indicator will track the reduction in GHG emissions resulting from improved efficiency of ESPs
   Comments:
                                       operations and establishment of renewable generation replacing diesel based one.
    IN01108904
    ►Decrease in tariffs under the project (Percentage, Custom)

                                       Baseline                        Actual (Previous)           Actual (Current)           End Target

    Value                              0.00                         --                            0.00                        30.00

    Date                               01-Jul-2021                  --                            23-Feb-2022                 30-Jun-2026

                                       The indicator will track the decrease in the participating ESPs tariffs due to project intervention under
   Comments:
                                       Component 2.
    IN01108905
    ►Establishment of the Electricity Supply Industry institutions with clear roles and responsibilities (Yes/No, Custom)

                                       Baseline                        Actual (Previous)           Actual (Current)           End Target

    Value                              No                           --                            No                          Yes

    Date                               30-Jul-2021                  --                            23-Feb-2022                 30-Jun-2026
                                       The indicator will track the reestablishment of the sector institutions with clear mandates. Key milestones
                                       will include (a) Adaption of a new ESI Institutional Organization structure; (ii) Establishment of the
   Comments:
                                       Somaliland Energy Regulatory Commission and the FGS National Electricity Authority; (iii) Enactment of
                                       FGS Electricity Law/Act, and (iv) Licenses issued for generation, transmission and distribution operations.


 Intermediate Results Indicators by Components



   Subtransmission, distribution network reconstruction, reinforcement in Mogadishu, Hargeisa

    IN01108909
    ►Distribution lines constructed or rehabilitated (Kilometers, Custom)

                                       Baseline                        Actual (Previous)           Actual (Current)           End Target

    Value                              0.00                         --                            0.00                        331.00

    Date                               30-Jul-2021                  --                            23-Feb-2022                 30-Jun-2026

   Comments:                           The indicator will track progress in the length of distribution network rehabilitation and extension.


3/7/2022                                                                                                                         Page 3 of 9
           The World Bank                                                                                       Implementation Status & Results Report
           Somali Electricity Sector Recovery Project (P173088)



    IN01108912
    ►Sub-transmission lines constructed under the project (Kilometers, Custom)

                                       Baseline                     Actual (Previous)             Actual (Current)           End Target

    Value                              0.00                         --                            0.00                       52.00

    Date                               30-Jul-2021                  --                            23-Feb-2022                30-Jun-2026

   Comments:                           The indicator will track progress in the establishment of the sub-transmission network in the country.

    IN01108917
    ►Generators synchronized (Megawatt, Custom)

                                       Baseline                     Actual (Previous)             Actual (Current)           End Target

    Value                              0.00                         --                            0.00                       48.00

    Date                               30-Jul-2021                  --                            23-Feb-2022                30-Jun-2026

                                       The indicator will track the progress in the synchronization of existing generators improving their efficiency
   Comments:
                                       in utilization of available installed capacity.
    IN01108920
    ►Technical loss reduction (Percentage, Custom)

                                       Baseline                     Actual (Previous)             Actual (Current)           End Target

    Value                              40.00                        --                            0.00                       32.00

    Date                               30-Jul-2021                  --                            23-Feb-2022                30-Jun-2026

                                       This indicator will track the reduction in technical losses for ESPs in the program areas resulting from
   Comments:
                                       distribution network interconnection and rehabilitation.
    IN01108922
    ►Number of people benefitting from improved electricity service delivery under component 1 (Number, Custom)

                                       Baseline                     Actual (Previous)             Actual (Current)           End Target

    Value                              0.00                         --                            0.00                       3,150,000.00

    Date                               30-Jul-2021                  --                            23-Feb-2022                30-Jun-2026

   Comments:                           This indicator will track the number of people benefitting from improved electricity service delivery



   Hybridization and Battery Storage Systems for Minigrids

    IN01108906
    ►Generation capacity of energy constructed or rehabilitated (Megawatt, Corporate)

                                       Baseline                     Actual (Previous)             Actual (Current)           End Target

    Value                              0.00                         --                            0.00                       18.00

    Date                               30-Jul-2021                  --                            23-Feb-2022                30-Jun-2026

     IN01108910


3/7/2022                                                                                                                         Page 4 of 9
           The World Bank                                                                                        Implementation Status & Results Report
           Somali Electricity Sector Recovery Project (P173088)




     Renewable energy generation capacity (other than hydropower) constructed under the project (Megawatt, Corporate Breakdown)

                                     Baseline                     Actual (Previous)             Actual (Current)             End Target

     Value                           0.00                         --                            0.00                         18.00

     Date                            30-Jul-2021                  --                            23-Feb-2022                 30-Jun-2026

    IN01108914
    ►Capacity of solar PV installed (Megawatt, Custom)

                                       Baseline                        Actual (Previous)          Actual (Current)           End Target

    Value                              0.00                         --                            0.00                       14.00

    Date                               30-Jul-2021                  --                            23-Feb-2022                30-Jun-2026

   Comments:                           The indicator will track the installed PV capacity in the program areas

    IN01108918
    ►Capacity of BESS installed (Megawatt, Custom)

                                       Baseline                        Actual (Previous)          Actual (Current)           End Target

    Value                              0.00                         --                            0.00                       4.00

    Date                               30-Jul-2021                  --                            23-Feb-2022                30-Jun-2026

   Comments:                           The indicator will track the installed BESS capacity in the program areas

    IN01108924
    ►Number of people to benefit from improved electricity service delivery under component 2 (Number, Custom)

                                       Baseline                        Actual (Previous)          Actual (Current)           End Target

    Value                              0.00                         --                            0.00                       2,564,000.00

    Date                               30-Jul-2021                  --                            23-Feb-2022                30-Jun-2026

   Comments:                           This indicator will track the number of people benefitting from improved electricity service delivery



   Stand-alone solar off-grid access to public institutions (Health and Education)

    IN01108907
    ►Health facilities connected under the project (Number, Custom)

                                       Baseline                        Actual (Previous)          Actual (Current)           End Target

    Value                              0.00                         --                            0.00                       205.00

    Date                               30-Jul-2021                  --                            23-Feb-2022                30-Jun-2026

   Comments:                           The indicator will track the number of health facilities provided with SHS connectivity under the project

    IN01108911
    ►Education facilities connected under the project (Number, Custom)


3/7/2022                                                                                                                         Page 5 of 9
           The World Bank                                                                                       Implementation Status & Results Report
           Somali Electricity Sector Recovery Project (P173088)




                                       Baseline                        Actual (Previous)          Actual (Current)           End Target

    Value                              0.00                         --                            0.00                       380.00

    Date                               30-Jul-2021                  --                            23-Feb-2022                30-Jun-2026

   Comments:                           the indicator will track the number of health facilities provided with SHS connectivity under the project

    IN01108915
    ►Number of people benefitting from improved electricity service delivery through health and educational facilities (Number, Custom)

                                       Baseline                        Actual (Previous)          Actual (Current)           End Target

    Value                              0.00                         --                            0.00                       2,565,000.00

    Date                               30-Jul-2021                  --                            23-Feb-2022                30-Jun-2026

                                       This indicator will track the number of people benefitting from improved electricity service delivery through
   Comments:
                                       health and educational facilities
    IN01108919
    ►Generation capacity of energy constructed or rehabilitated (Megawatt, Corporate)

                                       Baseline                        Actual (Previous)          Actual (Current)           End Target

    Value                              0.00                         --                            0.00                       5.00

    Date                               30-Jul-2021                  --                            23-Feb-2022                30-Jun-2026

     IN01108927
     Renewable energy generation capacity (other than hydropower) constructed under the project (Megawatt, Corporate Breakdown)

                                     Baseline                     Actual (Previous)              Actual (Current)            End Target

     Value                           0.00                         --                            0.00                         5.00

     Date                            30-Jul-2021                  --                            23-Feb-2022                  30-Jun-2026


   Institutional Development and Capacity Building

    IN01108908
    ►Establishment of the Somaliland Energy Regulatory Commission and the FGS National Electricity Authority (Yes/No, Custom)

                                       Baseline                        Actual (Previous)          Actual (Current)           End Target

    Value                              No                           --                            No                         Yes

    Date                               01-Jul-2021                  --                            23-Feb-2022                30-Jun-2026

   Comments:                           The indicator will track the establishment and operationalization of sector regulatory authorities

    IN01108913
    ►Adoption of secondary legislation stemming from the Electricity Act (Yes/No, Custom)

                                       Baseline                        Actual (Previous)          Actual (Current)           End Target

    Value                              No                           --                            No                         Yes



3/7/2022                                                                                                                         Page 6 of 9
           The World Bank                                                                                       Implementation Status & Results Report
           Somali Electricity Sector Recovery Project (P173088)




    Date                               01-Jul-2021                  --                            23-Feb-2022                 30-Jun-2026

   Comments:                           The indicator will track the adoption of the secondary legislation for sector operations

    IN01108916
    ►Adoption of sector integrated Least-Cost Plan (Yes/No, Custom)

                                       Baseline                     Actual (Previous)              Actual (Current)           End Target

    Value                              No                           --                            No                          Yes

    Date                               01-Jul-2021                  --                            23-Feb-2022                 30-Jun-2026

                                       The indicator will track the adoption of the fundamental sector planning instruments for sector recovery
   Comments:
                                       and development
    IN01108921
    ►Completion of the detailed Diagnostic Gender Assessment (Yes/No, Custom)

                                       Baseline                     Actual (Previous)              Actual (Current)           End Target

    Value                              No                           --                            No                          Yes

    Date                               01-Jul-2021                  --                            23-Feb-2022                 30-Jun-2026

   Comments:                           The indicator will track the completion of the Gender Diagnostic assessment

    IN01108923
    ►Increase in women's employment in the energy sector (Percentage, Custom)

                                       Baseline                     Actual (Previous)              Actual (Current)           End Target

    Value                              0.00                         --                            0.00                        20.00

    Date                               30-Jun-2021                  --                            23-Feb-2022                 29-May-2026

                                       The indicator will track progress in the female workforce participation in energy sector institutions in the
   Comments:
                                       country as supported by project activities.
    IN01108925
    ►Beneficiaries that feel project investments reflected their needs (%) (Percentage, Custom)

                                       Baseline                     Actual (Previous)              Actual (Current)           End Target

    Value                              0.00                         --                            0.00                        50.00

    Date                               01-Jul-2021                  --                            23-Feb-2022                 30-Jun-2026
                                       This is a Citizen Engagement indicator which will measure the satisfaction of project beneficiaries (ESPs
   Comments:                           customers under Component 1 and 2, beneficiaries of improved services of health and education facilities)
                                       with project activities.
    IN01108926
    ►Satisfaction of enterprises in beneficiaries survey (Percentage, Custom)

                                       Baseline                     Actual (Previous)              Actual (Current)           End Target

    Value                              0.00                         --                            0.00                        50.00




3/7/2022                                                                                                                          Page 7 of 9
           The World Bank                                                                                          Implementation Status & Results Report
           Somali Electricity Sector Recovery Project (P173088)




    Date                               30-Jul-2021                  --                               23-Feb-2022              30-Jun-2026

                                       This is a Citizen Engagement indicator which will measure the satisfaction of enterprises beneficiaries of
   Comments:
                                       project activities under Component 1 and 2.


 Performance-Based Conditions



 Data on Financial Performance


 Disbursements (by loan)

 Project       Loan/Credit/TF     Status       Currency        Original   Revised        Cancelled      Disbursed       Undisbursed              % Disbursed

                                  Not
 P173088       IDA-D9310                       USD             150.00      150.00             0.00           0.00            149.20                       0%
                                  Effective


 Key Dates (by loan)

 Project        Loan/Credit/TF     Status      Approval Date       Signing Date     Effectiveness Date        Orig. Closing Date      Rev. Closing Date

                                   Not
 P173088        IDA-D9310                      08-Dec-2021         17-Dec-2021      --                        31-Dec-2026             31-Dec-2026
                                   Effective


Cumulative Disbursements




3/7/2022                                                                                                                           Page 8 of 9
           The World Bank                                                                         Implementation Status & Results Report
           Somali Electricity Sector Recovery Project (P173088)



 PBC Disbursement

                                                                                 Achievement   Disbursed amount in     Disbursement %
 PBC ID                    PBC Type     Description           Coc   PBC Amount
                                                                                 Status        Coc                     for PBC




  Restructuring History


  There has been no restructuring to date.


  Related Project(s)


  There are no related projects.




3/7/2022                                                                                                         Page 9 of 9