PROCUREMENT PLAN - Textual Part Project information: Sint Maarten Emergency Recovery Project (P167339) Project Implementation Agency: NRPB Date of the Procurement Plan: April 29, 2021 Period covered by this Procurement Plan: From April 2021 to March 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: Shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the National Procurement Legislation such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The Bank’s Anti- Corruption Guidelines and Sanctions Framework shall be incorporated into the national bidding documents by adding a page entitled “Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework”. 2. Contracts with an appropriate allocation of responsibilities, risks, and liabilities between the Borrower and the contractors/suppliers/consultants. 3. Rights for the Bank to review procurement documentation and activities. In accordance with the Procurement Regulations, each bidding document and contract shall include provisions stating the Bank's policy to sanction firms or individuals, found to have engaged in fraud and/or corruption as defined in the Procurement Regulations. In accordance with the Procurement Regulations, each bidding document and contract financed out of the proceeds of the Financing Agreement shall provide that bidders, suppliers, contractors and their subcontractors, agents, personnel, consultants, service providers, or suppliers shall permit the Bank to inspect all accounts, records and other documents relating to the bid submission and performance of the contract and to have said accounts and records audited by auditors appointed by the Bank. Acts intended to materially impede the exercise of the Bank's inspection and audit rights provided for in the Procurement Regulations constitute an obstructive practice as defined in the Regulations. 4. No bids shall be rejected solely because they fall below or exceed the estimated cost. All bids (including in the case when less than two bids are received) shall not be rejected, the procurement process shall not be cancelled, and new bids shall not be solicited without the Bank's prior written concurrence. The Bidding Documents template to be used under “national open competitive procurement arrangements” are subject to prior written concurrence by the Bank. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable. Procurement of Second-hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: not applicable Works: not applicable. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. Procurement in Situations of Urgent Need of Assistance or Capacity Constraints. PROCUREMENT PLAN Goods Notification Activity Draft Signed Review Procurement Evaluation of Intention Reference No. / In-Process Component Contract Contract Type Category Options of Award Description: Planned Planned Planned Restoring a community SX-NRPB- learning and 205571-GO-DIR / No cultural Post Goods Direct 2021/01/30 2021/02/13 2021/03/06 ICT Equipment environment, Project Management Consulting Services Draft Signed Negotiated Activity Contract Market Contract Reference No. In-Process Component Review Type Category Approach / Description: Planned Planned SX-NRPB- Restoring a 205590-CS- community CDS / ESS8 Consultant No learning and Post Direct 2021/03/26 2021/04/30 Cultural Services cultural Heritage environment Consultants SX-NRPB- 205594-CS- Rebuilding safe Consultant CDS / School No Prior Direct 2021/04/10 2021/05/15 schools Services and Library designs Individual Consultants Terms of Expression Signed Activity Reference of Interest Contract Reference In- Review Market Component Category No. / Process Type Approach Description: Planned Planned Planned SX-NRPB- 205589-CS- INDV / Consultant No Project Management Post Open 2021/03/04 2021/03/25 2021/06/24 MECYS Services Project Manager SX-NRPB- 205575-CS- Restoring a community INDV / learning and cultural Consultant Technical No Post Open 2021/01/04 2021/01/25 2021/04/26 environment,Project Services Assistant Management Project Engineer SX-NRPB- Restoring a community 205576-CS- learning and cultural Consultant INDV / No Post Open 2021/02/04 2021/02/25 2021/05/27 environment,Project Services Safeguards Management Specialist SX-NRPB- 205592-CS- Restoring a community INDV / Needs Consultant No learning and cultural Post Open 2021/02/04 2021/02/25 2021/05/27 Assessment Services environment for Inclusive Education SX-NRPB- 205415-CS- INDV / FRLP: Local Consultant to Restoring a community work on learning and cultural strategy and Consultant No environment,Strengthening Post Open 2021/01/04 2021/01/18 2021/04/19 Framework Services the Ministry’s Management for SXM Information System Cultural Heritage and other Learning Services SX-NRPB- 205561-CS- Consultant INDV / No Project Management Post Open 2021/01/04 2021/01/25 2021/04/26 Services Procurement Specialist SX-NRPB- 205593-CS- Strengthening the INDV / Consultant No Ministry’s Management Post Open 2021/03/01 2021/03/22 2021/06/21 Development Services Information System MIS framework PROCUREMENT St Maarten : Sint Maarten Emergency Recovery Project I PLAN General Information Country: St Maarten Bank’s Approval Date of the Original Procurement Plan: 2018-09-05 2022-02-16 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167339 GPN Date: Project Name: Sint Maarten Emergency Recovery Project I Loan / Credit No: TF / A8079 National Recovery Program Bureau Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SX-NRPB-156576-CW-RFB / Housing Repair and Public Single Stage - One 2020-12- Public Building Repairs: TF / A8079 Buildings Repair and Prior Request for Bids Open - International 5,000,000.00 0.00 Canceled 2020-03-02 2020-03-07 2020-04-18 2020-05-18 2020-06-22 Envelope 19 Education Facilities Reconstruction Housing Repair and Public SX-NRPB-165115-CW-RFB / Single Stage - One 2,418,911.5 2021-01- TF / A8079 Buildings Repair and Post Request for Bids Limited 1,000,000.00 Signed 2020-03-25 2020-05-14 2020-03-30 2020-04-16 2020-05-11 2020-05-07 2020-06-10 2020-06-01 2020-07-15 2020-07-06 Rehabilitation of Shelters Envelope 4 11 Reconstruction Housing Repair and Public SX-NRPB-181992-CW-RFB / Single Stage - One 1,946,600.0 2021-05- TF / A8079 Buildings Repair and Prior Request for Bids Limited 1,500,000.00 Signed 2020-07-14 2020-08-10 2020-07-19 2020-11-03 2020-08-30 2020-09-11 2020-09-29 2020-11-12 2020-11-03 2021-01-18 Priority School Repairs Envelope 0 02 Reconstruction SX-NRPB-183349-CW-RFQ / Housing Repair and Public Request for Single Stage - One 2021-03- SMHDF roof repairs, for TF / A8079 Buildings Repair and Post Limited 236,367.00 236,367.00 Signed 2020-07-13 2020-07-07 2020-09-07 2020-07-07 Quotations Envelope 06 retroactive finance Reconstruction SX-NRPB-202289-CW-RFB / Housing Repair and Public Single Stage - One 7,151,533.0 2021-08- Batch 2: Schools and F&A TF / A8079 Buildings Repair and Post Request for Bids Open - International 4,750,000.00 Signed 2020-11-09 2021-04-27 2020-11-14 2021-05-10 2020-12-26 2021-07-06 2021-01-25 2021-10-01 2021-03-01 2021-12-16 Envelope 0 28 Building Repairs Reconstruction Housing Repair and Public SX-NRPB-202300-CW-RFB / Single Stage - One 5,471,564.0 2021-09- TF / A8079 Buildings Repair and Post Request for Bids Open - International 6,500,000.00 Signed 2020-11-16 2021-04-01 2020-11-21 2021-04-08 2021-01-02 2021-05-24 2021-02-01 2021-09-17 2021-03-08 2021-12-16 SMHDF Repairs Phase 2 Envelope 0 04 Reconstruction Housing Repair and Public SX-NRPB-202314-CW-RFB / Single Stage - One 2021-10- TF / A8079 Buildings Repair and Post Request for Bids Open - International 5,000,000.00 0.00 Canceled 2021-01-11 2021-08-31 2021-01-16 2021-08-31 2021-02-27 2021-11-09 2021-03-29 2022-01-14 2021-05-03 Batch 3: School Repairs Envelope 30 Reconstruction Emergency measures for the SX-NRPB-202332-CW-RFB / recovery of disaster first Single Stage - One 3,779,342.0 2021-12- TF / A8079 Post Request for Bids Open - International 5,000,000.00 Signed 2021-03-01 2021-08-23 2021-03-06 2021-08-23 2021-04-17 2021-10-05 2021-05-17 2021-11-05 2021-06-21 2022-01-06 GEBE Trenching Batch 1 responders and preparedness Envelope 0 18 facilities SX-NRPB-208747-CW-DIR / Housing Repair and Public 2021-07- Minor Repair Works to Homes: TF / A8079 Buildings Repair and Post Direct Selection Direct 27,772.18 28,065.55 Completed 2020-12-09 2020-12-01 2020-12-14 2020-12-01 2021-01-18 2021-01-06 17 Aluminum System Reconstruction Request for Bids - Housing Repair and Public Pending SX-NRPB-202315-CW-RFB / Single Stage - One Small Works SPD 2022-12- TF / A8079 Buildings Repair and Post Request for Bids Open - International 4,500,000.00 0.00 Implementat 2022-03-01 2022-03-06 2022-04-17 2022-05-17 2022-06-21 Expansion of the EOC Building Envelope (1 envelope 18 Reconstruction ion process) National SX-NRPB-275606-CW-RFB / Housing Repair and Public Procurement Pending Single Stage - One 2023-02- Single Family Home Repairs TF / A8079 Buildings Repair and Post Request for Bids Open - National Document - 1 3,000,000.00 0.00 Implementat 2022-05-01 2022-05-06 2022-06-17 2022-07-17 2022-08-21 Envelope 17 PHASE 3 Reconstruction Envelope process ion (Non Bank-SPD) Emergency measures for the Request for Bids - Pending SX-NRPB-202333-CW-RFB / recovery of disaster first Single Stage - One Small Works SPD 2022-12- TF / A8079 Post Request for Bids Open - International 5,000,000.00 0.00 Implementat 2022-03-01 2022-03-06 2022-04-17 2022-05-17 2022-06-21 GEBE Trenching Batch 2 responders and preparedness Envelope (1 envelope 18 ion facilities process) National SX-NRPB-278379-CW-RFB / Housing Repair and Public Procurement Pending Procurement of Repair and Single Stage - One 2022-12- TF / A8079 Buildings Repair and Post Request for Bids Open - International Document - 1 5,000,000.00 0.00 Implementat 2022-02-14 2022-02-19 2022-04-02 2022-05-02 2022-06-06 Rehabilitation Works for 13 Envelope 03 Reconstruction Envelope process ion SXM schools - relaunch (Non Bank-SPD) SX-NRPB-278660-CW-DIR / Housing Repair and Public Request for Pending 2022-09- MAC High I.T Classroom TF / A8079 Buildings Repair and Post Direct Selection Direct Quotations (Non 4,000.00 0.00 Implementat 2022-02-15 2022-02-20 2022-03-27 23 Relocation Reconstruction Bank-SPD) ion GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Emergency measures for the SX-NRPB-136740-GO-DIR / recovery of disaster first TF / A8079 Prior Direct Selection Direct 2,250,000.00 1,938,933.00 Signed 2019-10-01 2020-06-04 2019-10-01 2020-06-18 2019-11-05 2020-02-26 2020-05-03 Fire Trucks responders and preparedness facilities Emergency measures for the SX-NRPB-143339-GO-DIR / recovery of disaster first TF / A8079 Prior Direct Selection Direct 15,000.00 15,120.00 Signed 2019-10-29 2020-05-27 2019-11-03 2020-06-15 2019-12-08 2020-01-08 2020-06-05 Safety Shoes Fire Department responders and preparedness facilities Emergency measures for the SX-NRPB-157539-GO-DIR / recovery of disaster first TF / A8079 Post Direct Selection Direct 20,000.00 17,690.00 Signed 2020-02-09 2020-02-04 2020-02-14 2020-03-19 2020-03-20 2020-03-27 2020-09-16 Diesel Water Pumps responders and preparedness facilities Emergency measures for the SX-NRPB-160723-GO-DIR / recovery of disaster first TF / A8079 Post Direct Selection Direct 60,000.00 52,355.72 Signed 2020-02-20 2019-12-11 2020-02-25 2020-03-10 2020-03-31 2020-04-14 2020-09-27 Ambulance: Spare Parts responders and preparedness facilities Emergency measures for the SX-NRPB-160730-GO-DIR / recovery of disaster first FD&AD: Additional Radios and TF / A8079 Post Direct Selection Direct 100,000.00 61,381.67 Signed 2020-02-20 2018-06-07 2020-02-25 2020-03-23 2020-03-31 2020-03-23 2020-09-27 responders and preparedness Accessories facilities Page 1 Emergency measures for the SX-NRPB-165436-GO-DIR / recovery of disaster first TF / A8079 Prior Direct Selection Direct 1,500,000.00 0.00 Canceled 2020-03-19 2020-06-04 2020-03-24 2020-06-18 2020-04-28 2020-10-25 Type II Ambulances responders and preparedness facilities Emergency measures for the SX-NRPB-167830-GO-DIR / recovery of disaster first TF / A8079 Post Direct Selection Direct 100,000.00 100,213.14 Signed 2020-04-06 2020-03-05 2020-04-06 2020-04-06 2020-05-11 2020-04-21 2020-11-07 ProPac Isolation Capsules responders and preparedness facilities Emergency measures for the AN-NRPB-76471-GO-RFB / recovery of disaster first Single Stage - One TF / A8079 Prior Request for Bids Open - International 2,385,000.00 1,645,775.00 Signed 2020-05-18 2020-06-18 2020-05-23 2020-09-14 2020-07-04 2020-09-23 2020-08-03 2020-12-10 2020-09-07 2021-02-11 2021-03-06 General Vehicles responders and preparedness Envelope facilities Emergency measures for the Under SX-NRPB-160728-GO-DIR / recovery of disaster first TF / A8079 Post Direct Selection Direct 100,000.00 0.00 Implementati 2020-02-20 2021-05-10 2020-02-25 2021-02-05 2020-03-31 2020-09-27 FD: Spare Parts responders and preparedness on facilities Emergency measures for the SX-NRPB-160720-GO-DIR / recovery of disaster first TF / A8079 Prior Direct Selection Direct 170,000.00 0.00 Canceled 2020-02-20 2020-02-25 2020-03-31 2020-09-27 Submersible Water Pumps responders and preparedness facilities Emergency measures for the SX-NRPB-185662-GO-RFQ / recovery of disaster first Request for Single Stage - One TF / A8079 Post Open - International 320,000.00 0.00 Canceled 2020-08-12 2020-10-07 2021-04-05 Crane Trucks (2) responders and preparedness Quotations Envelope facilities Emergency measures for the Under SX-NRPB-202313-GO-RFQ / recovery of disaster first Request for Single Stage - One TF / A8079 Post Open - International 630,000.00 0.00 Implementati 2020-11-20 2021-03-04 2021-01-15 2021-07-14 Command Vehicles responders and preparedness Quotations Envelope on facilities Emergency measures for the SX-NRPB-213914-GO-DIR / recovery of disaster first Sint Maarten Fire Service TF / A8079 Post Direct Selection Direct 15,400.00 21,052.00 Signed 2021-01-15 2021-03-11 2021-01-20 2021-02-05 2021-02-24 2021-04-16 2021-08-23 responders and preparedness Repair Parts 2 : Waziri Export facilities SX-NRPB-213915-GO-DIR / Emergency measures for the Sint Maarten Fire Service recovery of disaster first TF / A8079 Post Direct Selection Direct 8,800.00 6,603.47 Signed 2021-01-15 2021-03-11 2021-01-20 2021-02-05 2021-02-24 2021-05-06 2021-08-23 Repair Parts 3: Saint-Martin responders and preparedness Cars facilities Emergency measures for the Under SX-NRPB-216605-GO-RFQ / recovery of disaster first Request for Single Stage - One TF / A8079 Post Open - International 90,000.00 0.00 Implementati 2021-02-03 2021-06-28 2021-03-31 2021-09-27 Thirty Seater Bus (1) responders and preparedness Quotations Envelope on facilities SX-NRPB-218343-GO-DIR / Emergency measures for the Sint Maarten Fire Service recovery of disaster first TF / A8079 Post Direct Selection Direct 27,500.00 28,132.52 Signed 2021-02-09 2021-03-11 2021-02-14 2021-02-08 2021-03-21 2021-04-13 2021-09-17 Repair Parts Package 4: responders and preparedness Motorworld facilities SX-NRPB-218364-GO-DIR / Emergency measures for the Sint Maarten Fire Service recovery of disaster first TF / A8079 Post Direct Selection Direct 3,000.00 2,181.54 Signed 2021-02-09 2021-03-11 2021-02-14 2021-02-08 2021-03-21 2021-04-15 2021-09-17 Repair Parts package 5: Napa responders and preparedness Auto Parts SXM facilities Emergency measures for the SX-NRPB-220199-GO-DIR / recovery of disaster first Type II Ambulances: Wheeled TF / A8079 Prior Direct Selection Direct 1,500,000.00 1,146,956.00 Signed 2021-02-18 2021-02-18 2021-02-23 2021-02-18 2021-03-30 2021-02-25 2021-09-26 responders and preparedness Coach/ REV Group facilities Emergency measures for the SX-NRPB-216373-GO-RFQ / recovery of disaster first Request for Single Stage - One TF / A8079 Post Open - International 215,000.00 0.00 Canceled 2021-02-02 2021-04-12 2021-03-30 2021-09-26 Support Vehicles - Vans responders and preparedness Quotations Envelope facilities SX-NRPB-221791-GO-DIR / Emergency measures for the Pending Computer Tablets and recovery of disaster first TF / A8079 Post Direct Selection Direct 3,000.00 0.00 Implementati 2021-02-27 2021-03-04 2021-04-08 2021-10-05 Protective Cases: Keijzer responders and preparedness on Computer Systems NV facilities Emergency measures for the SX-NRPB-239642-GO-RFQ / recovery of disaster first Request for Single Stage - One TF / A8079 Post Limited 215,000.00 124,500.00 Signed 2021-06-22 2021-06-21 2021-08-17 2021-09-16 2022-02-13 Vans II responders and preparedness Quotations Envelope facilities Emergency measures for the Under SX-NRPB-241317-GO-RFQ / recovery of disaster first Request for Single Stage - One TF / A8079 Post Open - International 486,500.00 0.00 Implementati 2021-07-02 2021-07-21 2021-08-27 2022-02-23 Command Vehicles II (7) responders and preparedness Quotations Envelope on facilities Emergency measures for the Under SX-NRPB-241320-GO-RFQ / recovery of disaster first Request for Single Stage - One TF / A8079 Post Open - International 142,500.00 0.00 Implementati 2021-07-02 2021-07-15 2021-08-27 2022-02-23 Command Pick-up Trucks (3) responders and preparedness Quotations Envelope on facilities Emergency measures for the Pending SX-NRPB-202345-GO-RFQ / recovery of disaster first Request for Single Stage - One TF / A8079 Post Open - National 35,000.00 0.00 Implementati 2020-12-06 2021-01-31 2021-07-30 MDS Goods responders and preparedness Quotations Envelope on facilities Emergency measures for the SX-NRPB-202327-GO-RFQ / Pending recovery of disaster first Request for Single Stage - One MDS Automatic Weather TF / A8079 Post Open - International 350,000.00 0.00 Implementati 2022-06-06 2022-08-01 2023-01-28 responders and preparedness Quotations Envelope Stations and Tidal Gauges on facilities Emergency measures for the Under SX-NRPB-275366-GO-DIR / recovery of disaster first TF / A8079 Post Direct Selection Direct 100,000.00 0.00 Implementati 2022-02-01 2022-01-26 2022-02-06 2022-03-13 2022-09-09 Fire Suits - Viking responders and preparedness on facilities NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Page 2 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SX-NRPB-160721-NC-DIR / Housing Repair and Public Emergency Mold Assessment TF / A8079 Buildings Repair and Post Direct Selection Direct 150,000.00 8,082.00 Signed 2020-02-20 2020-02-21 2020-02-25 2020-02-17 2020-03-31 2020-02-21 2020-09-27 and Remediation Action Plan Reconstruction SX-NRPB-232003-NC-DIR / Housing Repair and Public Under Retroactive Lease Agreement: TF / A8079 Buildings Repair and Post Direct Selection Direct 4,200.00 0.00 Implementati 2021-04-30 2021-04-09 2021-05-05 2021-04-09 2021-06-09 2021-12-06 Simpson Bay Community Reconstruction on Center SX-NRPB-278661-NC-RFQ / Housing Repair and Public Pending Request for Single Stage - One Dumpster Rental for 16 TF / A8079 Buildings Repair and Post Limited 6,000.00 0.00 Implementati 2022-02-20 2022-04-17 2022-10-14 Quotations Envelope Schools Reconstruction on SX-NRPB-278700-NC-RFQ / Housing Repair and Public Pending Request for Single Stage - One Moving Company for 16 TF / A8079 Buildings Repair and Post Limited 100,000.00 0.00 Implementati 2022-02-20 2022-04-17 2022-10-14 Quotations Envelope Schools Reconstruction on SX-NRPB-278672-NC-DIR / Housing Repair and Public Pending Security Company Services for TF / A8079 Buildings Repair and Post Direct Selection Direct 30,000.00 0.00 Implementati 2022-02-15 2022-02-20 2022-03-27 2022-09-23 MPC School Reconstruction on SX-NRPB-278674-NC-RFQ / Housing Repair and Public Pending Request for Single Stage - One Storage Space/ Container TF / A8079 Buildings Repair and Post Limited 130,000.00 0.00 Implementati 2022-02-20 2022-04-17 2022-10-14 Quotations Envelope Rental for 16 Schools Reconstruction on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SX-NRPB-132867-CS-LCS / Institutional Support for Least Cost TF / A8079 Prior Open - National 150,000.00 0.00 Canceled 2019-09-05 2019-09-26 2019-11-09 2019-12-07 2020-01-06 2020-02-10 2020-03-16 2020-09-12 Audit Services NRPB Reconstruction Selection Institutional Support for Least Cost ERP_C_015 / Audit services TF / A8079 Post Open - National 150,000.00 421,998.00 Signed 2019-09-05 2019-02-13 2019-09-26 2019-09-18 2019-11-09 2019-04-25 2019-12-07 2019-07-11 2020-01-06 2019-07-11 2020-02-10 2019-07-11 2020-03-16 2019-09-25 2020-09-12 Reconstruction Selection SX-NRPB-160722-CS-LCS / Housing Repair and Public Least Cost Works Verification Audit TF / A8079 Buildings Repair and Post Open - National 25,000.00 59,696.00 Signed 2019-11-06 2020-01-30 2019-11-27 2020-01-10 2020-01-30 2020-02-07 2020-03-25 2020-03-08 2020-03-25 2020-04-12 2020-03-25 2020-05-17 2020-04-23 2020-11-13 Selection SMHDF Reconstruction AN-IRC-NRPB-88561-CS- Housing Repair and Public Consultant CQS / SMHDF Technical TF / A8079 Buildings Repair and Post Qualification Open - National 250,000.00 207,300.00 Signed 2020-10-15 2019-01-03 2020-11-05 2020-11-17 2020-12-19 2019-01-24 2021-01-18 2019-09-27 2021-02-22 2019-09-27 2021-08-21 Assessment and Design for Reconstruction Selection Phase 2 AN-IRC-NRPB-109549-CS- Housing Repair and Public Quality And Cost- QCBS / Technical Assessment TF / A8079 Buildings Repair and Post Open - National 500,000.00 426,523.00 Signed 2020-11-03 2019-07-10 2020-11-24 2021-08-04 2021-01-07 2019-04-22 2021-02-04 2019-04-22 2021-03-06 2019-04-22 2021-04-10 2019-07-11 2021-05-15 2019-07-12 2022-05-15 Based Selection Single family Home Repairs 2 Reconstruction AN-NRPB-76431-CS-CQS / Supervision Shelter Repairs Consultant Institutional Support for Main and Recovery Housing TF / A8079 Post Qualification Open - National 100,000.00 0.00 Under Review 2021-05-19 2021-06-09 2021-07-23 2021-08-22 2021-09-26 2022-03-25 Reconstruction Repair and Public Buildings Selection Repair and Reconstruction Emergency measures for the SX-NRPB-202330-CS-CQS / recovery of disaster first Quality And Cost- Pending Emergency Cell Broadcast TF / A8079 Post Open - International 350,000.00 0.00 2022-06-01 2022-06-22 2022-08-05 2022-09-02 2022-10-02 2022-11-06 2022-12-11 2023-12-11 responders and preparedness Based Selection Implementation System facilities INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SX-NRPB-124802-CS-INDV / Individual PROJECT COORDINATOR– Sint Institutional Support for TF / A8079 Post Consultant Open 180,000.00 267,983.36 Signed 2019-07-25 2019-07-25 2019-09-12 2019-10-18 2019-10-03 2019-11-25 2019-11-07 2020-05-29 2020-05-05 Maarten Digital Government Reconstruction Selection Project SX-NRPB-126135-CS-INDV / Individual Institutional Support for Procurement Assistant TF / A8079 Prior Consultant Open 60,000.00 59,241.98 Signed 2019-08-03 2019-08-07 2019-09-21 2019-11-21 2019-10-12 2020-07-07 2019-11-16 2020-01-16 2020-05-14 Reconstruction Consultant Selection SX-NRPB-126138-CS-INDV / Individual Institutional Support for Procurement Specialist TF / A8079 Prior Consultant Open 90,000.00 0.00 Canceled 2019-08-03 2019-08-07 2019-09-21 2019-10-12 2019-11-16 2020-05-14 Reconstruction Consultant Selection SX-NRPB-126137-CS-INDV / Individual Portfolio and Accounting Institutional Support for TF / A8079 Post Consultant Open 180,000.00 0.00 Canceled 2019-08-03 2019-08-07 2019-09-21 2019-10-12 2019-11-16 2020-05-14 Officer for Small Enterprise Reconstruction Selection Recovery Project SX-NRPB-126665-CS-CDS / Institutional Support for Interim Financial Management TF / A8079 Post Direct Selection Direct 14,000.00 12,150.00 Signed 2019-08-12 2019-09-01 2019-08-22 2019-08-08 2019-10-26 2019-09-01 2020-04-23 Reconstruction Officer SX-NRPB-127209-CS-CDS / Institutional Support for Stakeholder Engagement TF / A8079 Post Direct Selection Direct 45,000.00 44,000.00 Signed 2019-08-14 2019-08-09 2019-08-24 2019-08-08 2019-10-28 2019-08-15 2020-04-25 Reconstruction Home Repairs SX-NRPB-128034-CS-INDV / Individual Institutional Support for Junior Communications TF / A8079 Post Consultant Open 80,000.00 43,436.52 Terminated 2019-08-20 2019-08-23 2019-10-08 2019-10-18 2019-10-29 2019-11-12 2019-12-03 2019-11-15 2020-05-31 Reconstruction Consultant Selection SX-NRPB-128036-CS-INDV / Individual Institutional Support for Financial Management TF / A8079 Post Consultant Open 40,000.00 27,000.00 Signed 2019-08-19 2019-08-22 2019-10-07 2019-11-19 2019-10-28 2019-11-26 2019-12-02 2019-11-26 2020-05-30 Reconstruction Assistant Selection Individual SX-NRPB-129158-CS-INDV / Institutional Support for TF / A8079 Post Consultant Open 80,000.00 61,699.24 Signed 2019-08-26 2019-08-30 2019-10-14 2019-11-13 2019-11-04 2019-11-18 2019-12-09 2019-11-19 2020-06-06 Executive Assistant Reconstruction Selection Page 3 SX-NRPB-129299-CS-INDV / Individual Institutional Support for Jr Environmental Safeguards TF / A8079 Post Consultant Open 80,000.00 106,076.17 Signed 2019-08-30 2019-08-30 2019-10-18 2019-11-18 2019-11-08 2020-03-30 2019-12-13 2020-05-29 2020-06-10 Reconstruction Specialist Selection Individual SX-NRPB-134548-CS-INDV / Institutional Support for TF / A8079 Post Consultant Open 25,000.00 0.00 Canceled 2019-09-16 2018-12-10 2019-11-04 2019-11-25 2019-12-30 2020-06-27 Communications Specialist Reconstruction Selection Emergency measures for the SX-NRPB-144180-CS-CDS / recovery of disaster first Design Fire Department TF / A8079 Post Direct Selection Direct 100,000.00 0.00 Canceled 2019-11-04 2021-05-03 2019-11-04 2020-01-08 2020-07-06 responders and preparedness Renovation and Expansion facilities Individual SX-NRPB-146192-CS-INDV / Institutional Support for TF / A8079 Post Consultant Open 150,000.00 0.00 Canceled 2019-12-12 2019-12-12 2020-02-14 2020-03-06 2020-04-10 2020-10-07 Contract Manager Reconstruction Selection SX-NRPB-153308-CS-INDV / Individual Institutional Support for Project Manager Education TF / A8079 Post Consultant Open 150,000.00 108,000.00 Signed 2020-01-31 2020-01-24 2020-03-20 2020-06-11 2020-04-10 2020-06-24 2020-05-15 2020-06-24 2020-11-11 Reconstruction Project Selection SX-NRPB-154610-CS-CDS / Institutional Support for Mission Project Manager TF / A8079 Post Direct Selection Direct 8,000.00 7,250.00 Signed 2020-01-20 2020-01-21 2020-01-20 2019-10-18 2020-01-27 2020-01-23 2020-02-17 Reconstruction Digital Government SX-NRPB-155761-CS-INDV / Individual Institutional Support for Project Manager Enterprise TF / A8079 Post Consultant Open 150,000.00 0.00 Canceled 2020-01-24 2020-03-13 2020-04-03 2020-05-08 2020-11-04 Reconstruction Recovery Project Selection SX-NRPB-156570-CS-CDS / Institutional Support for Procurement Consultant TF / A8079 Post Direct Selection Direct 320,000.00 0.00 Canceled 2020-01-29 2020-01-29 2020-05-03 2020-10-30 Reconstruction Services SX-NRPB-146438-CS-INDV / Individual Institutional Support for Procurement Specialist TF / A8079 Prior Consultant Open 150,000.00 0.00 Canceled 2019-11-20 2020-01-08 2020-01-29 2020-03-04 2020-08-31 Reconstruction Consultant 2 Selection SX-NRPB-156572-CS-CDS / Project Manager ERP-1 This is a continuation of the Institutional Support for TF / A8079 Post Direct Selection Direct 185,000.00 184,500.00 Signed 2020-01-29 2020-03-10 2020-02-08 2020-03-10 2020-04-13 2020-03-25 2020-10-10 current contract. This contract Reconstruction will go into effect on April 1 - March 31 2021. SX-NRPB-146440-CS-INDV / Individual Institutional Support for Activity Manager School TF / A8079 Post Consultant Limited 50,000.00 57,975.00 Signed 2019-11-22 2019-11-27 2019-11-27 2020-01-20 2020-02-07 2020-03-09 2020-03-13 2020-03-09 2020-09-09 Reconstruction Repairs Selection SX-NRPB-159532-CS-CDS / Institutional Support for TF / A8079 Prior Direct Selection Direct 200,000.00 49,262.46 Signed 2020-02-13 2021-02-02 2020-02-13 2020-02-13 2020-04-17 2020-02-12 2020-10-14 NRPB Legal Services Reconstruction SX-NRPB-161524-CS-CDS / Institutional Support for Pending TF / A8079 Post Direct Selection Direct 8,000.00 0.00 2020-02-26 2020-03-07 2020-05-11 2020-11-07 Airport Benchmark Study Reconstruction Implementation SX-NRPB-165435-CS-CDS / Institutional Support for TF / A8079 Post Direct Selection Direct 225,000.00 220,500.00 Signed 2020-03-19 2019-07-09 2020-03-29 2020-03-20 2020-06-02 2020-03-20 2020-11-29 Engineer Reconstruction SX-NRPB-166957-CS-CDS / Institutional Support for Project Coordinator Digital TF / A8079 Post Direct Selection Direct 16,000.00 0.00 Under Review 2020-03-30 2019-12-01 2020-04-09 2020-06-13 2020-12-10 Reconstruction Government INTERIM SX-NRPB-168099-CS-CDS / Institutional Support for TF / A8079 Post Direct Selection Direct 150,000.00 45,000.00 Signed 2020-04-08 2020-07-31 2020-04-18 2020-04-07 2020-06-22 2020-08-13 2020-12-19 Social Safeguards Specialist Reconstruction SX-NRPB-168800-CS-CDS / Institutional Support for Design Rehabilitation of TF / A8079 Post Direct Selection Direct 120,000.00 177,000.00 Signed 2020-04-15 2020-04-14 2020-04-25 2020-05-04 2020-06-29 2020-05-04 2020-12-26 Reconstruction Shelters Individual SX-NRPB-173096-CS-INDV / Institutional Support for TF / A8079 Post Consultant Open 60,000.00 7,824.54 Signed 2020-05-11 2019-10-01 2020-06-29 2020-05-15 2020-07-20 2020-06-19 2020-08-24 2020-06-19 2021-02-20 Jr Communication Officer 2 Reconstruction Selection SX-NRPB-167363-CS-CDS / Institutional Support for TF / A8079 Prior Direct Selection Direct 30,000.00 63,000.00 Signed 2020-04-02 2021-01-12 2020-04-12 2020-05-08 2020-06-16 2020-05-07 2020-12-13 MP: Procurement Consultant Reconstruction SX-NRPB-167376-CS-CDS / Institutional Support for TF / A8079 Prior Direct Selection Direct 30,000.00 223,500.00 Signed 2020-04-02 2020-07-22 2020-04-12 2020-04-02 2020-06-16 2020-04-23 2020-12-13 SI: Procurement Consultant Reconstruction SX-NRPB-186632-CS-CDS / Housing Repair and Public Twenty Schools and F&A TF / A8079 Buildings Repair and Prior Direct Selection Direct 820,600.00 790,190.00 Under Review 2020-07-30 2020-08-19 2020-08-09 2020-05-19 2020-10-13 2020-08-31 2021-04-11 building Design Consulting Reconstruction SX-NRPB-186392-CS-CDS / Housing Repair and Public Asbestos Assessment TF / A8079 Buildings Repair and Post Direct Selection Direct 25,000.00 33,950.00 Signed 2020-07-29 2020-07-29 2020-08-08 2020-08-23 2020-10-12 2020-09-15 2021-04-10 Consulting Services ROBERTO Reconstruction DAVIDOVICH Individual SX-NRPB-189349-CS-INDV / Institutional Support for TF / A8079 Post Consultant Open 85,000.00 0.00 Canceled 2020-08-18 2019-11-14 2020-10-06 2020-10-27 2020-12-01 2021-05-30 HR Consultant Reconstruction Selection SX-NRPB-189691-CS-CDS / Emergency measures for the Land Negotiation for Link 6 recovery of disaster first TF / A8079 Prior Direct Selection Direct 50,000.00 0.00 Canceled 2020-08-20 2020-08-28 2020-08-30 2020-09-23 2020-11-03 2021-05-02 Road-Hubert Lopez HISMAR responders and preparedness NV facilities SX-NRPB-191068-CS-CDS / Institutional Support for TF / A8079 Prior Direct Selection Direct 125,000.00 284,060.00 Signed 2020-08-28 2021-04-01 2020-09-07 2020-10-20 2020-11-11 2020-10-22 2021-05-10 SGS Procurement Service Reconstruction SX-NRPB-196201-CS-CDS / Institutional Support for TF / A8079 Post Direct Selection Direct 30,000.00 0.00 Under Review 2020-09-25 2020-10-05 2020-12-09 2021-06-07 FMO Consultant Home Based Reconstruction Individual SX-NRPB-197284-CS-INDV / Institutional Support for TF / A8079 Post Consultant Open 180,000.00 181,250.00 Signed 2020-10-01 2020-12-12 2020-11-19 2020-05-18 2020-12-10 2020-06-01 2021-01-14 2021-01-11 2021-07-13 DL - Contract Manager Reconstruction Selection Page 4 Individual SX-NRPB-198813-CS-INDV / Institutional Support for TF / A8079 Post Consultant Open 150,000.00 0.00 Canceled 2020-10-15 2020-11-19 2020-12-03 2020-12-24 2021-01-28 2021-07-27 AR - Contract Manager Reconstruction Selection SX-NRPB-126986-CS-CDS / Institutional Support for Pending Corporate Governance Lawyer TF / A8079 Post Direct Selection Direct 85,690.00 0.00 2019-08-16 2019-08-26 2019-10-30 2020-04-27 Reconstruction Implementation 1 SX-NRPB-126988-CS-CDS / Institutional Support for Pending Corporate Governance Legal TF / A8079 Post Direct Selection Direct 61,250.00 0.00 2019-08-16 2019-08-26 2019-10-30 2020-04-27 Reconstruction Implementation Support 1 SX-NRPB-126989-CS-CDS / Institutional Support for Pending Corporate Governance Legal TF / A8079 Post Direct Selection Direct 28,500.00 0.00 2019-08-16 2019-08-26 2019-10-30 2020-04-27 Reconstruction Implementation Support 2 SX-NRPB-126987-CS-CDS / Institutional Support for Pending Corporate Governance Lawyer TF / A8079 Post Direct Selection Direct 79,000.00 0.00 2019-08-16 2019-08-26 2019-10-30 2020-04-27 Reconstruction Implementation 2 SX-NRPB-199448-CS-CDS / Institutional Support for Contract Manager (DL) Home TF / A8079 Post Direct Selection Direct 23,750.00 23,684.00 Signed 2020-10-13 2020-11-19 2020-10-23 2020-02-06 2020-12-27 2020-10-28 2021-06-25 Reconstruction Based SX-NRPB-170435-CS-CDS / Institutional Support for Interim Environmental TF / A8079 Post Direct Selection Direct 20,000.00 10,000.00 Signed 2020-04-24 2019-09-02 2020-05-04 2019-11-18 2020-07-08 2020-05-06 2021-01-04 Reconstruction Safeguards Specialist SX-NRPB-201640-CS-CDS / Institutional Support for TF / A8079 Prior Direct Selection Direct 95,000.00 189,000.00 Signed 2020-10-26 2020-10-29 2020-11-05 2020-10-29 2021-01-09 2020-12-31 2021-07-08 JB: Procurement Coordinator Reconstruction Individual SX-NRPB-201789-CS-INDV / Institutional Support for Under TF / A8079 Post Consultant Limited 25,000.00 0.00 2020-10-27 2020-10-27 2020-11-01 2020-11-22 2020-12-27 2021-06-25 Insurance Consultant Reconstruction Implementation Selection SX-NRPB-201788-CS-CDS / Institutional Support for UB: Activity Manager Home TF / A8079 Post Direct Selection Direct 155,000.00 154,660.50 Signed 2020-10-27 2020-10-21 2020-11-06 2020-09-16 2021-01-10 2020-11-02 2021-07-09 Reconstruction Repairs SX-NRPB-201795-CS-CDS / Institutional Support for TF / A8079 Post Direct Selection Direct 200,000.00 125,000.00 Signed 2020-10-27 2020-11-24 2020-11-06 2019-11-01 2021-01-10 2020-12-16 2021-07-09 BB: ICT Helpdesk Reconstruction Individual SX-NRPB-205755-CS-INDV / Institutional Support for TF / A8079 Post Consultant Open 50,000.00 60,000.00 Signed 2020-11-24 2020-11-20 2021-01-12 2021-03-04 2021-02-02 2021-03-04 2021-03-09 2021-05-19 2021-09-05 Copywriter Reconstruction Selection SX-NRPB-208921-CS-CDS / Mold Assessment Institutional Support for TF / A8079 Post Direct Selection Direct 50,000.00 141,910.00 Signed 2020-12-09 2020-12-07 2020-12-19 2020-12-03 2021-02-22 2021-01-14 2021-08-21 Consultancy: Farmer Reconstruction Environmental Group SX-NRPB-214549-CS-CDS / Institutional Support for TF / A8079 Prior Direct Selection Direct 50,000.00 48,000.00 Signed 2021-01-18 2021-01-28 2021-01-28 2021-01-07 2021-04-03 2021-02-05 2021-09-30 JA: Procurement Consultant Reconstruction SX-NRPB-215465-CS-CDS / Housing Repair and Public AC: Project Manager TF / A8079 Buildings Repair and Post Direct Selection Direct 200,000.00 198,000.00 Signed 2021-01-21 2021-01-20 2021-01-31 2021-01-21 2021-04-06 2021-02-11 2021-10-03 Infrastructure Reconstruction SX-NRPB-211337-CS-CDS / Institutional Support for TF / A8079 Post Direct Selection Direct 350,000.00 0.00 Canceled 2020-12-23 2021-01-02 2021-03-08 2021-09-04 Engineer Reconstruction Emergency measures for the SX-NRPB-231555-CS-INDV / Individual recovery of disaster first Junior Environmental TF / A8079 Post Consultant Open 60,000.00 70,200.00 Signed 2021-04-29 2021-05-18 2021-06-17 2021-09-06 2021-07-08 2021-09-30 2021-08-12 2021-09-30 2022-02-08 responders and preparedness Specialist Selection facilities Individual SX-NRPB-232896-CS-INDV / Institutional Support for TF / A8079 Post Consultant Open 15,000.00 33,800.00 Signed 2021-05-03 2021-05-06 2021-06-21 2021-08-13 2021-07-12 2021-08-19 2021-08-16 2021-08-27 2022-02-12 HRM Consultant Reconstruction Selection Individual SX-NRPB-236664-CS-INDV / Institutional Support for TF / A8079 Post Consultant Open 30,000.00 20,000.00 Signed 2021-05-28 2021-06-08 2021-07-16 2021-08-05 2021-08-06 2021-09-21 2021-09-10 2021-10-29 2022-03-09 Graphic Design Services Reconstruction Selection Individual SX-NRPB-236668-CS-INDV / Institutional Support for TF / A8079 Post Consultant Open 30,000.00 35,000.00 Signed 2021-05-28 2021-06-08 2021-07-16 2021-08-05 2021-08-06 2021-09-21 2021-09-10 2021-11-03 2022-03-09 Video Production Services Reconstruction Selection Individual SX-NRPB-236671-CS-INDV / Institutional Support for TF / A8079 Post Consultant Open 30,000.00 30,000.00 Signed 2021-05-28 2021-06-08 2021-07-16 2021-08-05 2021-08-06 2021-09-21 2021-09-10 2021-10-29 2022-03-09 Animation Services Reconstruction Selection SX-NRPB-239247-CS-CDS / Institutional Support for Social Safeguards Consultant: TF / A8079 Post Direct Selection Direct 200,000.00 200,000.00 Signed 2021-06-14 2021-06-16 2021-06-24 2021-05-04 2021-08-28 2020-07-06 2022-02-24 Reconstruction Jo-Ann George SX-NRPB-240330-CS-CDS / Institutional Support for TF / A8079 Post Direct Selection Direct 280,000.00 251,210.00 Signed 2021-06-18 2021-06-28 2021-06-20 2021-06-21 2021-06-23 2021-07-06 2023-05-31 MH: Project Manager EDMP Reconstruction Emergency measures for the SX-NRPB-241445-CS-CDS / recovery of disaster first Design Fire Dept. Renovation TF / A8079 Post Direct Selection Direct 160,000.00 159,900.00 Signed 2021-06-28 2021-05-21 2021-07-08 2021-05-03 2021-09-11 2021-06-30 2022-03-10 responders and preparedness and Expansion: ICE facilities SX-NRPB-242711-CS-CDS / Institutional Support for Procurement Coordinator: TF / A8079 Post Direct Selection Direct 267,000.00 266,640.00 Signed 2021-07-11 2021-07-15 2021-07-21 2021-06-08 2021-09-24 2021-07-30 2022-03-23 Reconstruction Santiago Ibarguen Individual SX-NRPB-246966-CS-INDV / Institutional Support for Under TF / A8079 Prior Consultant Open 80,000.00 0.00 2021-09-17 2021-09-21 2021-11-05 2021-11-26 2021-12-31 2022-06-29 NRPB Procurement Assistant Reconstruction Implementation Selection SX-NRPB-252781-CS-CDS / Institutional Support for Project Funding Coordinator – TF / A8079 Post Direct Selection Direct 20,000.00 0.00 Canceled 2021-09-12 2021-09-08 2021-09-22 2021-11-26 2022-05-25 Reconstruction Housing Project Page 5 Individual SX-NRPB-253548-CS-INDV / Institutional Support for TF / A8079 Post Consultant Open 180,000.00 102,600.00 Signed 2021-09-17 2021-09-30 2021-11-05 2021-11-15 2021-11-26 2022-01-12 2021-12-31 2022-01-12 2022-06-29 DGTP Project Manager for DLT Reconstruction Selection SX-NRPB-254305-CS-INDV / Individual Institutional Support for Under Program Management TF / A8079 Post Consultant Open 90,000.00 0.00 2021-09-24 2021-09-15 2021-11-12 2021-12-03 2022-01-07 2022-07-06 Reconstruction Implementation Assistant Selection SX-NRPB-256482-CS-INDV / Individual Institutional Support for Under Project Manager - Mental TF / A8079 Post Consultant Open 90,000.00 0.00 2021-10-07 2021-10-05 2021-11-25 2021-12-16 2022-01-20 2022-07-19 Reconstruction Implementation Health Project Selection Individual SX-NRPB-257387-CS-INDV / Institutional Support for Under TF / A8079 Post Consultant Open 60,000.00 0.00 2021-10-12 2021-10-08 2021-11-30 2021-12-21 2022-01-25 2022-07-24 Executive Assistant II Reconstruction Implementation Selection Individual SX-NRPB-257388-CS-INDV / Institutional Support for TF / A8079 Post Consultant Open 180,000.00 163,500.00 Signed 2021-10-12 2021-10-07 2021-11-30 2021-09-20 2021-12-21 2021-10-19 2022-01-25 2021-10-21 2022-07-24 Engineer II Reconstruction Selection Individual SX-NRPB-257389-CS-INDV / Institutional Support for TF / A8079 Post Consultant Open 245,000.00 244,000.00 Signed 2021-10-12 2021-10-07 2021-11-30 2021-09-22 2021-12-21 2021-10-12 2022-01-25 2021-11-01 2022-07-24 Contract Manager II Reconstruction Selection SX-NRPB-257455-CS-CDS / Institutional Support for TF / A8079 Post Direct Selection Direct 20,000.00 31,972.50 Signed 2021-10-12 2021-10-07 2021-10-22 2021-09-20 2021-12-26 2021-10-21 2022-06-24 Engineer II Reconstruction SX-NRPB-258195-CS-CDS / Institutional Support for Procurement Consultant: TF / A8079 Prior Direct Selection Direct 40,000.00 82,400.00 Signed 2021-10-15 2021-10-19 2021-10-25 2021-10-20 2021-12-29 2021-11-01 2022-06-27 Reconstruction Paolo Maculotti SX-NRPB-258246-CS-CDS / Institutional Support for Project Finance Specialist- TF / A8079 Post Direct Selection Direct 20,000.00 23,240.00 Signed 2021-10-14 2021-10-13 2021-10-24 2021-10-14 2021-12-28 2021-10-14 2022-06-26 Reconstruction Housing Project SX-NRPB-258918-CS-CDS / Institutional Support for Project Officer - Mental Health TF / A8079 Post Direct Selection Direct 15,000.00 12,750.00 Signed 2021-10-22 2021-10-27 2021-11-01 2021-10-27 2022-01-05 2021-10-29 2022-07-04 Reconstruction Project Individual SX-NRPB-260433-CS-INDV / Institutional Support for Pending TF / A8079 Post Consultant Open 25,000.00 0.00 2021-10-29 2021-12-17 2022-01-07 2022-02-11 2022-08-10 Sector Expert - Housing Reconstruction Implementation Selection SX-NRPB-262565-CS-INDV / Individual Institutional Support for Procurement Consultant: Ms. TF / A8079 Post Consultant Direct 130,000.00 140,000.00 Signed 2021-11-12 2021-11-08 2021-11-22 2021-10-20 2021-12-13 2021-12-04 2022-01-17 2021-12-04 2022-07-16 Reconstruction Jackson Selection SX-NRPB-270528-CS-CDS / Housing Repair and Public Under School Gyms Technical TF / A8079 Buildings Repair and Post Direct Selection Direct 350,000.00 0.00 2021-12-24 2022-01-17 2022-01-03 2021-12-21 2022-03-09 2022-09-05 Implementation Assessment Reconstruction SX-NRPB-272351-CS-CDS / Institutional Support for Procurement Consultant - TF / A8079 Post Direct Selection Direct 72,090.00 72,090.00 Signed 2022-01-10 2022-01-14 2022-01-20 2022-01-18 2022-03-26 2022-01-21 2022-09-22 Reconstruction Home Based : Paolo Maculotti SX-NRPB-272355-CS-CDS / Institutional Support for Under Project Manager EDMP: East TF / A8079 Post Direct Selection Direct 165,000.00 0.00 2022-01-10 2022-01-07 2022-01-20 2022-03-26 2022-09-22 Reconstruction Implementation West Consultancy BV Individual SX-NRPB-278264-CS-INDV / Institutional Support for Pending TF / A8079 Post Consultant Open 250,000.00 0.00 2022-02-14 2022-04-04 2022-04-25 2022-05-30 2022-11-26 Senior Project Manager ERP1 Reconstruction Implementation Selection SX-NRPB-278699-CS-CDS / Housing Repair and Public Design of Fire Dept. Pending TF / A8079 Buildings Repair and Post Direct Selection Direct 171,124.00 0.00 2022-02-15 2022-02-25 2022-05-01 2022-10-28 Renovation and Expansion Implementation Reconstruction completion of deliverables Page 6